National Library of Energy BETA

Sample records for remedial project managers

  1. EIS-0195: Remedial Actions at Operable Unit 4, Fernald Environmental Management Project, Fernald, Ohio

    Broader source: Energy.gov [DOE]

    This EIS evaluates the potential environmental impacts of a proposal to conduct remedial action at Operable Unit 4 at the Fernald Environmental Management Project.

  2. Uranium Mill Tailings Remedial Action Project, Surface Project Management Plan. Revision 1

    SciTech Connect (OSTI)

    Not Available

    1994-12-01

    Title I of the Uranium Mill Tailings Radiation Control Act (UMTRCA) authorizes the US Department of Energy (DOE) to undertake remedial action at 24 designated inactive uranium processing sites and associated vicinity properties (VP) containing uranium mill tailings and related residual radioactive materials. The purpose of the Uranium Mill Tailings Remedial Action (UMTRA) Surface Project is to minimize or eliminate radiation health hazards to the public and the environment at the 24 sites and related VPs. This document describes the management organization, system, and methods used to manage the design, construction, and other activities required to clean up the designated sites and associated VPs, in accordance with the UMTRCA.

  3. Tank Waste Remediation System Characterization Project Programmatic Risk Management Plan

    SciTech Connect (OSTI)

    Baide, D.G.; Webster, T.L.

    1995-12-01

    The TWRS Characterization Project has developed a process and plan in order to identify, manage and control the risks associated with tank waste characterization activities. The result of implementing this process is a defined list of programmatic risks (i.e. a risk management list) that are used by the Project as management tool. This concept of risk management process is a commonly used systems engineering approach which is being applied to all TWRS program and project elements. The Characterization Project risk management plan and list are subset of the overall TWRS risk management plan and list.

  4. Documenting cost and performance for environmental remediation projects: Department of Energy Office of Environmental Management

    SciTech Connect (OSTI)

    1996-08-08

    The purpose of this DOE guide is to facilitate the use of consistent procedures to document cost and performance information for projects involving the remediation of media contaminated with hazardous and radioactive wastes. It provides remedial action project managers with a standardized set of data to document completed remediation projects. Standardized reporting of data will broaden the utility of the information, increase confidence in the effectiveness of future remedial technologies, and enhance the organization, storage and retrieval of relevant information for future cleanup projects. The foundation for this guide was laid down by the Federal Remediation Technologies Roundtable (FRTR) in their publication, Guide to Documenting Cost and Performance for Remediation Projects, EPA-542-B- 95-002. Member agencies of the FRTR include the US EPA, the US DOD, the US DOE, and the US DOI. All the member agencies are involved in site remediation projects and anticipate following the guidance provided in the above reference. Therefore, there is much to be gained for DOE to be consistent with the other member agencies as it will be easier to compare projects across different agencies and also to learn from the experiences of a wider spectrum of prior completed projects.

  5. Management and overview Quality Assurance Program Plan. [Uranium Mill Tailings Remedial Action (UMTRA) Project

    SciTech Connect (OSTI)

    Not Available

    1986-08-01

    The Uranium Mill Tailings Remedial Action (UMTRA) Project Office (DOE/ UMTRA-PO) is the US Department of Energy (DOE) Albuquerque Operations Office (AL) organization charged with the responsibility of managing and coordinating the activities of the various participating organizations and support contractors working on the UMTRA Project. This Quality Assurance Program Plan (QAPP) describes how the DOE/UMTRA-PO, as assisted by the Technical Assistance Contractor (TAC), performs the quality assurance (QA) aspects of managing and coordinating UMTRA Project activities. This QAPP was developed to comply with DOE Order 5700.6A, August, 1981, and AL Order 5700.6B, April, 1984, which contain the criteria applicable to Project QA activities.

  6. Tank waste remediation system immobilized high-level waste storage project configuration management implementation plan

    SciTech Connect (OSTI)

    Burgard, K.G.

    1998-09-24

    This Configuration Management Implementation Plan was developed to assist in the management of systems, structures, and components, to facilitate the effective control and statusing of changes to systems, structures, and components; and to ensure technical consistency between design, performance, and operational requirements. Its purpose is to describe the approach Project W-464 will take in implementing a configuration management control, to determine the rigor of control, and to identify the mechanisms for imposing that control.This Configuration Management Implementation Plan was developed to assist in the management of systems, structures, and components, to facilitate the effective control and statusing of changes to systems, structures, and components; and to ensure technical consistency between design, performance, and operational requirements. Its purpose is to describe the approach Project W-464 will take in implementing a configuration management control, to determine the rigor of control, and to identify the mechanisms for imposing that control.

  7. Tank waste remediation system configuration management plan

    SciTech Connect (OSTI)

    Vann, J.M.

    1998-01-08

    The configuration management program for the Tank Waste Remediation System (TWRS) Project Mission supports management of the project baseline by providing the mechanisms to identify, document, and control the functional and physical characteristics of the products. This document is one of the tools used to develop and control the mission and work. It is an integrated approach for control of technical, cost, schedule, and administrative information necessary to manage the configurations for the TWRS Project Mission. Configuration management focuses on five principal activities: configuration management system management, configuration identification, configuration status accounting, change control, and configuration management assessments. TWRS Project personnel must execute work in a controlled fashion. Work must be performed by verbatim use of authorized and released technical information and documentation. Application of configuration management will be consistently applied across all TWRS Project activities and assessed accordingly. The Project Hanford Management Contract (PHMC) configuration management requirements are prescribed in HNF-MP-013, Configuration Management Plan (FDH 1997a). This TWRS Configuration Management Plan (CMP) implements those requirements and supersedes the Tank Waste Remediation System Configuration Management Program Plan described in Vann, 1996. HNF-SD-WM-CM-014, Tank Waste Remediation System Configuration Management Implementation Plan (Vann, 1997) will be revised to implement the requirements of this plan. This plan provides the responsibilities, actions and tools necessary to implement the requirements as defined in the above referenced documents.

  8. Tank waste remediation system characterization project quality policies. Revision 1

    SciTech Connect (OSTI)

    Trimble, D.J.

    1995-10-02

    These Quality Policies (QPs) describe the Quality Management System of the Tank Waste Characterization Project (hereafter referred to as the Characterization Project), Tank Waste Remediation System (TWRS), Westinghouse Hanford Company (WHC). The Quality Policies and quality requirements described herein are binding on all Characterization Project organizations. To achieve quality, the Characterization Project management team shall implement this Characterization Project Quality Management System.

  9. Environmental Management and Remediation Committee Roster | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Management and Remediation Committee Roster Environmental Management and Remediation Committee Roster List of NNMCAB members that participate on the Environmental Monitoring and ...

  10. Contract/Project Management

    Office of Environmental Management (EM)

    2 nd Quarter Overall Contract and Project Management Performance Metrics and Targets Contract/Project Management Performance Metrics FY 2009 Target FY 2009 Actual Comment 1. Capital Asset Line Item Projects: 90% of projects completed within 110% of CD-2 TPC by FY11. 80% - Two projects completed in the 2 nd Qtr FY09. This is a 3-year rolling average (FY07 to FY09). 2. EM Cleanup (Soil and Groundwater Remediation, D&D, and Waste Treatment and Disposal) Projects: 90% of EM cleanup projects

  11. Contract/Project Management

    Office of Environmental Management (EM)

    8 4 th Quarter Metrics Final Overall Contract and Project Management Performance Metrics and Targets Contract/Project Management Performance Metrics FY 2008 Target FY 2008 Actual Comment 1. Capital Asset Line Item Projects: 90% of projects completed within 110% of CD-2 TPC by FY11. 75% 76% This is a 3-year rolling average Data includes FY06 to FY08. (37/48) 2. EM Cleanup (Soil and Groundwater Remediation, D&D, and Waste Treatment and Disposal) Projects: 90% of EM cleanup projects complete

  12. Contract/Project Management

    Office of Environmental Management (EM)

    1 st Quarter Overall Contract and Project Management Performance Metrics and Targets Contract/Project Management Performance Metrics FY 2009 Target FY 2009 Actual Comment 1. Capital Asset Line Item Projects: 90% of projects completed within 110% of CD-2 TPC by FY11. 80% - No 1 st Qtr FY09 completions. This is a 3-year rolling average (FY07 to FY09). 2. EM Cleanup (Soil and Groundwater Remediation, D&D, and Waste Treatment and Disposal) Projects: 90% of EM cleanup projects complete 80% of

  13. Contract/Project Management

    Office of Environmental Management (EM)

    3 rd Quarter Overall Contract and Project Management Performance Metrics and Targets Contract/Project Management Performance Metrics FY 2009 Target FY 2009 Actual Comment 1. Capital Asset Line Item Projects: 90% of projects completed within 110% of CD-2 TPC by FY11. 80% 72% This is a 3-year rolling average (FY07 to FY09). No 3 rd qtr FY09 completions. 2. EM Cleanup (Soil and Groundwater Remediation, D&D, and Waste Treatment and Disposal) Projects: 90% of EM cleanup projects complete 80% of

  14. Contract/Project Management

    Office of Environmental Management (EM)

    4 th Quarter Metrics Final Overall Contract and Project Management Performance Metrics and Targets Contract/Project Management Performance Metrics FY 2009 Target FY 2009 Actual Comment 1. Capital Asset Line Item Projects: 90% of projects completed within 110% of CD-2 TPC by FY11. 80% 73% This is a 3-year rolling average (FY07 to FY09). 2. EM Cleanup (Soil and Groundwater Remediation, D&D, and Waste Treatment and Disposal) Projects: 90% of EM cleanup projects complete 80% of scope within 125%

  15. project management

    National Nuclear Security Administration (NNSA)

    3%2A en Project Management and Systems Support http:www.nnsa.energy.govaboutusouroperationsapmprojectmanagementandsystemssupport

  16. project management

    National Nuclear Security Administration (NNSA)

    %2A en Project Management and Systems Support http:nnsa.energy.govaboutusouroperationsapmprojectmanagementandsystemssupport

  17. PROJECT MANAGEMENT PLANS Project Management Plans

    Office of Environmental Management (EM)

    MANAGEMENT PLANS Project Management Plans Overview Project Management Plan Suggested Outline Subjects Crosswalk between the Suggested PMP Outline Subjects and a Listing ...

  18. Project Management Plan

    SciTech Connect (OSTI)

    Not Available

    1988-01-01

    The mission of the Uranium Mill Tailings Remedial Action (UMTRA) Project is explicitly stated and directed in the Uranium Mill Tailings Radiation Control Act of 1978, Public Law 95-604, 42 USC 7901 (hereinafter referred to as the Act''). Title I of the Act authorizes the Department of Energy (DOE) to undertake remedial actions at 24 designated inactive uranium processing sites and associated vicinity properties containing uranium mill tailings and other residual radioactive materials derived from the processing sites. The Act, amended in January 1983, by Public Law 97-415, also authorizes DOE to perform remedial actions at vicinity properties in Edgemont, South Dakota. Cleanup of the Edgemont processing site is the responsibility of the Tennessee Valley Authority. This document describes the plan, organization, system, and methodologies used to manage the design, construction, and other activities required to clean up the designated sites and associated vicinity properties in accordance with the Act. The plan describes the objectives of the UMTRA Project, defines participants' roles and responsibilities, outlines the technical approach for accomplishing the objectives, and describes the planning and managerial controls to be used in integrating and performing the Project mission. 21 figs., 21 tabs.

  19. THE POSITIVE IMPACTS OF AMERICAN REINVESTMENT AND RECOVERY ACT (ARRA) FUNDING TO THE WASTE MANAGEMENT PROGRAM ON HANFORD'S PLATEAU REMEDIATION PROJECT

    SciTech Connect (OSTI)

    BLACKFORD LT

    2010-01-19

    In April 2009, the Department of Energy (DOE) Richland Operations Office (RL) was allocated $1.6 billion (B) in ARRA funding to be applied to cleanup projects at the Hanford Site. DOE-RL selected projects to receive ARRA funding based on 3-criteria: creating/saving jobs, reducing the footprint of the Hanford Site, and reducing life-cycle costs for cleanup. They further selected projects that were currently covered under regulatory documents and existing prime contracts, which allowed work to proceed quickly. CH2M HILL Plateau Remediation Company (CHPRC) is a prime contractor to the DOE focused on the environmental cleanup of the DOE Hanford Site Central Plateau. CHPRC was slated to receive $1.36B in ARRA funding. As of January, 2010, CHPRC has awarded over $200 million (M) in subcontracts (64% to small businesses), created more that 1,100 jobs, and touched more than 2,300 lives - all in support of long-term objectives for remediation of the Central Plateau, on or ahead of schedule. ARRA funding is being used to accelerate and augment cleanup activities already underway under the baseline Plateau Remediation Contract (PRC). This paper details challenges and accomplishments using ARRA funding to meet DOE-RL objectives of creating/saving jobs, expediting cleanup, and reducing lifecycle costs for cleanup during the first months of implementation.

  20. Uranium Mill Tailings Remedial Action Project 1993 Environmental Report

    SciTech Connect (OSTI)

    Not Available

    1994-10-01

    This annual report documents the Uranium Mill Tailing Remedial Action (UMTRA) Project environmental monitoring and protection program. The UMTRA Project routinely monitors radiation, radioactive residual materials, and hazardous constituents at associated former uranium tailings processing sites and disposal sites. At the end of 1993, surface remedial action was complete at 10 of the 24 designated UMTRA Project processing sites. In 1993 the UMTRA Project office revised the UMTRA Project Environmental Protection Implementation Plan, as required by the US DOE. Because the UMTRA Project sites are in different stages of remedial action, the breadth of the UMTRA environmental protection program differs from site to site. In general, sites actively undergoing surface remedial action have the most comprehensive environmental programs for sampling media. At sites where surface remedial action is complete and at sites where remedial action has not yet begun, the environmental program consists primarily of surface water and ground water monitoring to support site characterization, baseline risk assessments, or disposal site performance assessments.

  1. Tank waste remediation system configuration management implementation plan

    SciTech Connect (OSTI)

    Vann, J.M.

    1998-03-31

    The Tank Waste Remediation System (TWRS) Configuration Management Implementation Plan describes the actions that will be taken by Project Hanford Management Contract Team to implement the TWRS Configuration Management program defined in HNF 1900, TWRS Configuration Management Plan. Over the next 25 years, the TWRS Project will transition from a safe storage mission to an aggressive retrieval, storage, and disposal mission in which substantial Engineering, Construction, and Operations activities must be performed. This mission, as defined, will require a consolidated configuration management approach to engineering, design, construction, as-building, and operating in accordance with the technical baselines that emerge from the life cycles. This Configuration Management Implementation Plan addresses the actions that will be taken to strengthen the TWRS Configuration Management program.

  2. Unique environmental remediation project on steep canyon successfully

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    completed Environmental remediation project on canyon completed Unique environmental remediation project on steep canyon successfully completed A team recently completed a remediation project that involved removing contaminated rock and soil from the parking lot of a busy shopping center. July 29, 2015 A telescoping crane hoists a spider excavator over Los Alamos Canyon before placing it on the canyon slope to excavate historically contaminated soil. A telescoping crane hoists a spider

  3. Tank Waste Remediation System Projects Document Control Plan

    SciTech Connect (OSTI)

    Slater, G.D.; Halverson, T.G.

    1994-09-30

    The purpose of this Tank Waste Remediation System Projects Document Control Plan is to provide requirements and responsibilities for document control for the Hanford Waste Vitrification Plant (HWVP) Project and the Initial Pretreatment Module (IPM) Project.

  4. Uranium Mill Tailings Remedial Action (UMTRA) Project. [UMTRA project

    SciTech Connect (OSTI)

    Not Available

    1989-09-01

    The mission of the Uranium Mill Tailings Remedial Action (UMTRA) Project is explicitly stated and directed in the Uranium Mill Tailings Radiation Control Act of 1978, hereinafter referred to as the Act.'' Title I of the Act authorizes the Department of Energy (DOE) to undertake remedial action at designated inactive uranium processing sites (Attachment 1 and 2) and associated vicinity properties containing uranium mill tailings and other residual radioactive materials derived from the processing site. The purpose of the remedial actions is to stabilize and control such uranium mill tailings and other residual radioactive materials in a safe and environmentally sound manner to minimize radiation health hazards to the public. The principal health hazards and environmental concerns are: the inhalation of air particulates contaminated as a result of the emanation of radon from the tailings piles and the subsequent decay of radon daughters; and the contamination of surface and groundwaters with radionuclides or other chemically toxic materials. This UMTRA Project Plan identifies the mission and objectives of the project, outlines the technical and managerial approach for achieving them, and summarizes the performance, cost, and schedule baselines which have been established to guide operational activity. Estimated cost increases by 15 percent, or if the schedule slips by six months. 4 refs.

  5. 2016 DOE Project Management Workshop - "Enhancing Project Management...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    6 DOE Project Management Workshop - "Enhancing Project Management" 2016 DOE Project Management Workshop - "Enhancing Project Management" 20160407-doe-project-management-workshop-AD...

  6. In Situ Thermal NAPL Remediation at the Northeast Site Pinellas Environmental Restoration Project

    SciTech Connect (OSTI)

    Juhlin, R.; Butherus, M.

    2006-07-01

    The U.S. Department of Energy (DOE) is conducting thermal remediation to remove non-aqueous phase liquids (NAPLs) from the subsurface at the Northeast Site that is part of the Pinellas Environmental Restoration Project. The Northeast Site is located on the Young - Rainey Science, Technology, and Research (STAR) Center in Largo, Florida. The STAR Center was formerly a DOE facility. The NAPL remediation was performed at Area A and is currently being performed at Area B at the Northeast Site. The remediation at Area A was completed in 2003 and covered an area of 900 m{sup 2} (10,000 ft{sup 2}) and a depth of remediation that extended to 10.7 m (35 ft) below ground surface. Cleanup levels achieved were at or below maximum contaminant levels in almost all locations. The remediation project at Area B is ongoing and covers an area of 3,240 m{sup 2} (36,000 ft{sup 2}), a volume of 41,300 m (54,000 yd 3), and a depth of remediation to 12 m (40 ft) below ground surface. In addition, a portion of the subsurface under an occupied building in Area B is included in the remediation. The cleanup levels achieved from this remediation will be available in the Area B Final Report that will be posted on the DOE Office of Legacy Management web site (www.lm.doe.gov/land/sites/fl/ pinellas/pinellas.htm) in January 2007. Electrical resistive heating and steam were the chosen remediation methods at both areas. Lessons learned from the Area A remediation were incorporated into the Area B remediation and could benefit managers of similar remediation projects. (authors)

  7. Uranium Mill Tailings Remedial Action Project 1994 environmental report

    SciTech Connect (OSTI)

    1995-08-01

    This annual report documents the Uranium Mill Tailings Remedial Action (UMTRA) Project environmental monitoring and protection program. The UMTRA Project routinely monitors radiation, radioactive residual materials, and hazardous constituents at associated former uranium tailings processing sites and disposal sites. At the end of 1994, surface remedial action was complete at 14 of the 24 designated UMTRA Project processing sites: Canonsburg, Pennsylvania; Durango, Colorado; Grand Junction, Colorado; Green River Utah, Lakeview, Oregon; Lowman, Idaho; Mexican Hat, Utah; Riverton, Wyoming; Salt Lake City, Utah; Falls City, Texas; Shiprock, New Mexico; Spook, Wyoming, Tuba City, Arizona; and Monument Valley, Arizona. Surface remedial action was ongoing at 5 sites: Ambrosia Lake, New Mexico; Naturita, Colorado; Gunnison, Colorado; and Rifle, Colorado (2 sites). Remedial action has not begun at the 5 remaining UMTRA Project sites that are in the planning stage. Belfield and Bowman, North Dakota; Maybell, Colorado; and Slick Rock, Colorado (2 sites). The ground water compliance phase of the UMTRA Project started in 1991. Because the UMTRA Project sites are.` different stages of remedial action, the breadth of the UMTRA environmental protection program differs from site to site. In general, sites actively undergoing surface remedial action have the most comprehensive environmental programs for sampling media. At sites where surface remedial action is complete and at sites where remedial action has not yet begun, the environmental program consists primarily of surface water and ground water monitoring to support site characterization, baseline risk assessments, or disposal site performance assessments.

  8. The Management of the Plateau Remediation Contract, OAS-L-13-03

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    The Management of the Plateau Remediation Contract OAS-L-13-03 December 2012 Department of Energy Washington, DC 20585 December 21, 2012 MEMORANDUM FOR THE DEPUTY ASSISTANT SECRETARY FOR ACQUISITION AND PROJECT MANAGEMENT FROM: George W. Collard Assistant Inspector General for Audits Office of Inspector General SUBJECT: INFORMATION: Audit Report on "The Management of the Plateau Remediation Contract" BACKGROUND The Department of Energy's Richland Operations Office (Richland) awarded a

  9. MANAGEMENT ALERT Remediation of Selected Transuranic Waste Drums...

    Office of Environmental Management (EM)

    MANAGEMENT ALERT Remediation of Selected Transuranic Waste Drums at Los Alamos National Laboratory - Potential Impact on the Shutdown of the Department's Waste Isolation Plant DOE...

  10. Tank waste remediation system privatization phase 1 infrastructure project, systems engineering implementation plan

    SciTech Connect (OSTI)

    Schaus, P.S.

    1998-08-19

    This Systems Engineering Implementation Plan (SEIP) describes the processes, products, and organizational responsibilities implemented by Project W-519 to further define how the project`s mission, defined initially by the Tank Waste Remediation System Phase 1 Privatization Infrastructure Project W-503 Mission Analysis Report (Hoertkorn 1997), will be accomplished using guidance provided by the Tank Waste Remediation System Systems Engineering Management Plan (SEMP) (Peck 1998). This document describes the implementation plans for moving from a stated mission to an executable cost, schedule, and technical baseline and to help ensure its successful completion of those baselines.

  11. Final 2014 Remedial Action Report Project Chariot, Cape Thompson, Alaska

    SciTech Connect (OSTI)

    None, None

    2015-03-01

    This report was prepared to document remedial action (RA) work performed at the former Project Chariot site located near Cape Thompson, Alaska during 2014. The work was managed by the U.S. Army Corps of Engineers (USACE) Alaska District for the U.S. Department of Energy (DOE) Office of Legacy Management (LM). Due to the short field season and the tight barge schedule, all field work was conducted at the site July 6 through September 12, 2014. Excavation activities occurred between July 16 and August 26, 2014. A temporary field camp was constructed at the site prior to excavation activities to accommodate the workers at the remote, uninhabited location. A total of 785.6 tons of petroleum, oil, and lubricants (POL)-contaminated soil was excavated from four former drill sites associated with test holes installed circa 1960. Diesel was used in the drilling process during test hole installations and resulted in impacts to surface and subsurface soils at four of the five sites (no contamination was identified at Test Hole Able). Historic information is not definitive as to the usage for Test Hole X-1; it may have actually been a dump site and not a drill site. In addition to the contaminated soil, the steel test hole casings were decommissioned and associated debris was removed as part of the remedial effort.

  12. Tank waste remediation system privatization infrastructure program requirements and document management process guide

    SciTech Connect (OSTI)

    ROOT, R.W.

    1999-05-18

    This guide provides the Tank Waste Remediation System Privatization Infrastructure Program management with processes and requirements to appropriately control information and documents in accordance with the Tank Waste Remediation System Configuration Management Plan (Vann 1998b). This includes documents and information created by the program, as well as non-program generated materials submitted to the project. It provides appropriate approval/control, distribution and filing systems.

  13. Managing Legacy Records for Formerly Utilized Sites Remedial Action Program Sites

    Broader source: Energy.gov [DOE]

    Managing Legacy Records for Formerly Utilized Sites Remedial Action Program Sites (Waste Management Conference 2008)

  14. Contract/Project Management

    Broader source: Energy.gov (indexed) [DOE]

    Second Quarter Overall Contract and Project Management Improvement Performance Metrics and Targets 1 ContractProject Management Performance Metric FY 2012 Target FY 2012 Forecast ...

  15. Contract/Project Management

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Fourth Quarter Overall Contract and Project Management Improvement Performance Metrics and Targets 1 ContractProject Management Primary Performance Metrics FY 2011 Target FY 2011 ...

  16. Contract/Project Management

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    2 nd Quarter Overall Contract and Project Management Performance Metrics and Targets ContractProject Management Performance Metrics FY 2009 Target FY 2009 Actual Comment 1. ...

  17. Contract/Project Management

    Broader source: Energy.gov (indexed) [DOE]

    3 rd Quarter Overall Contract and Project Management Performance Metrics and Targets ContractProject Management Performance Metrics FY 2009 Target FY 2009 Actual Comment 1. ...

  18. Contract/Project Management

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Fourth Quarter Overall Contract and Project Management Performance Metrics and Targets 1 ContractProject Management Primary Performance Metrics FY 2010 Target FY 2010 Actual FY ...

  19. Contract/Project Management

    Broader source: Energy.gov (indexed) [DOE]

    Third Quarter Overall Contract and Project Management Improvement Performance Metrics and Targets 1 ContractProject Management Performance Metric FY 2012 Target FY 2012 Forecast ...

  20. Contract/Project Management

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Fourth Quarter Overall Contract and Project Management Improvement Performance Metrics and Targets 1 ContractProject Management Performance Metric FY 2012 Target FY 2012 Final FY ...

  1. Contract/Project Management

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Third Quarter Overall Contract and Project Management Improvement Performance Metrics and Targets 1 ContractProject Management Primary Performance Metrics FY 2011 Target FY 2011 ...

  2. Contract/Project Management

    Broader source: Energy.gov (indexed) [DOE]

    Second Quarter Overall Contract and Project Management Performance Metrics and Targets 1 ContractProject Management Primary Performance Metrics FY 2010 Target FY 2010 Actual FY ...

  3. Contract/Project Management

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    1 st Quarter Overall Contract and Project Management Performance Metrics and Targets ContractProject Management Performance Metrics FY 2009 Target FY 2009 Actual Comment 1. ...

  4. Contract/Project Management

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    8 4 th Quarter Metrics Final Overall Contract and Project Management Performance Metrics and Targets ContractProject Management Performance Metrics FY 2008 Target FY 2008 Actual ...

  5. Contract/Project Management

    Broader source: Energy.gov (indexed) [DOE]

    Third Quarter Overall Contract and Project Management Performance Metrics and Targets 1 ContractProject Management Primary Performance Metrics FY 2010 Target FY 2010 Forecast FY ...

  6. Contract/Project Management

    Broader source: Energy.gov (indexed) [DOE]

    Contract and Project Management Performance Metrics and Targets 1 ContractProject Management Primary Performance Metrics FY 2011 Target FY 2011 Actual & Forecast FY 2011 Pre- & ...

  7. Contract/Project Management

    Broader source: Energy.gov (indexed) [DOE]

    and Project Management Improvement Performance Metrics and Targets 1 ContractProject Management Primary Performance Metrics FY 2011 Target FY 2011 Forecast FY 2011 Pre- & ...

  8. Adaptive management: a paradigm for remediation of public facilities

    SciTech Connect (OSTI)

    Janecky, David R; Whicker, Jeffrey J; Doerr, Ted B

    2009-01-01

    Public facility restoration planning traditionally focused on response to natural disasters and hazardous materials accidental releases. These plans now need to integrate response to terrorist actions. Therefore, plans must address a wide range of potential vulnerabilities. Similar types of broad remediation planning are needed for restoration of waste and hazardous material handling areas and facilities. There are strong similarities in damage results and remediation activities between unintentional and terrorist actions; however, the uncertainties associated with terrorist actions result in a re-evaluation of approaches to planning. Restoration of public facilities following a release of a hazardous material is inherently far more complex than in confined industrial settings and has many unique technical, economic, social, and political challenges. Therefore, they arguably involve a superset of drivers, concerns and public agencies compared to other restoration efforts. This superset of conditions increases complexity of interactions, reduces our knowledge of the initial conditions, and even condenses the timeline for restoration response. Therefore, evaluations of alternative restoration management approaches developed for responding to terrorist actions provide useful knowledge for large, complex waste management projects. Whereas present planning documents have substantial linearity in their organization, the 'adaptive management' paradigm provides a constructive parallel operations paradigm for restoration of facilities that anticipates and plans for uncertainty, multiple/simUltaneous public agency actions, and stakeholder participation. Adaptive management grew out of the need to manage and restore natural resources in highly complex and changing environments with limited knowledge about causal relationships and responses to restoration actions. Similarities between natural resource management and restoration of a facility and surrounding area(s) after a

  9. Environmental remediation and waste management information systems

    SciTech Connect (OSTI)

    Harrington, M.W.; Harlan, C.P.

    1993-12-31

    The purpose of this paper is to document a few of the many environmental information systems that currently exist worldwide. The paper is not meant to be a comprehensive list; merely a discussion of a few of the more technical environmental database systems that are available. Regulatory databases such as US Environmental Protection Agency`s (EPA`s) RODS (Records of Decision System) database [EPA, 1993] and cost databases such as EPA`s CORA (Cost of Remedial Action) database [EPA, 1993] are not included in this paper. Section 2 describes several US Department of Energy (DOE) Environmental Restoration and Waste Management (EM) information systems and databases. Section 3 discusses several US EPA information systems on waste sites and technologies. Section 4 summarizes a few of the European Community environmental information systems, networks, and clearinghouses. And finally, Section 5 provides a brief overview of Geographical Information Systems. Section 6 contains the references, and the Appendices contain supporting information.

  10. River Protection Project (RPP) Project Management Plan

    SciTech Connect (OSTI)

    SEEMAN, S.E.

    2000-04-01

    The U.S. Department of Energy (DOE), in accordance with the Strom Thurmond National Defense Authorization Act for Fiscal Year 1999, established the Office of River Protection (ORP) to successfully execute and manage the River Protection Project (RPP), formerly known as the Tank Waste Remediation System (TWRS). The mission of the RPP is to store, retrieve, treat, and dispose of the highly radioactive Hanford tank waste in an environmentally sound, safe, and cost-effective manner. The team shown in Figure 1-1 is accomplishing the project. The ORP is providing the management and integration of the project; the Tank Farm Contractor (TFC) is responsible for providing tank waste storage, retrieval, and disposal; and the Privatization Contractor (PC) is responsible for providing tank waste treatment.

  11. MANAGING ENGINEERING ACTIVITIES FOR THE PLATEAU REMEDIATION CONTRACT - HANFORD

    SciTech Connect (OSTI)

    KRONVALL CM

    2011-01-14

    In 2008, the primary Hanford clean-up contract transitioned to the CH2MHill Plateau Remediation Company (CHPRC). Prior to transition, Engineering resources assigned to remediation/Decontamination and Decommissioning (D&D) activities were a part of a centralized engineering organization and matrixed to the performing projects. Following transition, these resources were reassigned directly to the performing project, with a loose matrix through a smaller Central Engineering (CE) organization. The smaller (10 FTE) central organization has retained responsibility for the overall technical quality of engineering for the CHPRC, but no longer performs staffing and personnel functions. As the organization has matured, there are lessons learned that can be shared with other organizations going through or contemplating performing a similar change. Benefits that have been seen from the CHPRC CE organization structure include the following: (1) Staff are closely aligned with the 'Project/facility' that they are assigned to support; (2) Engineering priorities are managed to be consistent with the 'Project/facility' priorities; (3) Individual Engineering managers are accountable for identifying staffing needs and the filling of staffing positions; (4) Budget priorities are managed within the local organization structure; (5) Rather than being considered a 'functional' organization, engineering is considered a part of a line, direct funded organization; (6) The central engineering organization is able to provide 'overview' activities and maintain independence from the engineering organizations in the field; and (7) The central engineering organization is able to maintain a stable of specialized experts that are able to provide independent reviews of field projects and day-to-day activities.

  12. Tank waste remediation system systems engineering management plan

    SciTech Connect (OSTI)

    Peck, L.G.

    1998-01-08

    This Systems Engineering Management Plan (SEMP) describes the Tank Waste Remediation System (TWRS) implementation of the US Department of Energy (DOE) systems engineering policy provided in 97-IMSD-193. The SEMP defines the products, process, organization, and procedures used by the TWRS Project to implement the policy. The SEMP will be used as the basis for tailoring the systems engineering applications to the development of the physical systems and processes necessary to achieve the desired end states of the program. It is a living document that will be revised as necessary to reflect changes in systems engineering guidance as the program evolves. The US Department of Energy-Headquarters has issued program management guidance, DOE Order 430. 1, Life Cycle Asset Management, and associated Good Practice Guides that include substantial systems engineering guidance.

  13. Scheduling the Remediation of Port Hope: Logistical and Regulatory Challenges of a Multiple Site Urban Remediation Project - 13119

    SciTech Connect (OSTI)

    Ferguson Jones, Andrea; Lee, Angela; Palmeter, Tim

    2013-07-01

    The Port Hope Project is part of the larger CAN$1.28 billion Port Hope Area Initiative (PHAI), a community-based program for the development and implementation of a safe, local, long-term management solution for historic Low-Level Radioactive Waste (LLRW) in the Municipalities of Port Hope and Clarington, Ontario, Canada. Atomic Energy of Canada (AECL) is the Project Proponent, Public Works and Government Services (PWGSC) is managing the procurement of services and the MMM Group Limited - Conestoga Rovers and Associates Joint Venture (MMM-CRA Joint Venture) is providing detailed design and construction oversight and administration services for the Project. The Port Hope Project includes the construction of a long-term waste management facility (LTWMF) in the Municipality of Port Hope and the remediation of 18 (eighteen) large-scale LLRW, numerous small-scale sites still being identified and industrial sites within the Municipality. The total volume to be remediated is over one million cubic metres and will come from sites that include temporary storage sites, ravines, beaches, parks, private commercial and residential properties and vacant industrial sites all within the urban area of Port Hope. Challenges that will need to be overcome during this 10 year project include: - Requirements stipulated by the Environmental Assessment (EA) that affect Project logistics and schedule. - Coordination of site remediation with the construction schedule at the LTWMF. - Physical constraints on transport routes and at sites affecting production rates. - Despite being an urban undertaking, seasonal constrains for birds and fish (i.e., nesting and spawning seasons). - Municipal considerations. - Site-specific constraints. - Site interdependencies exist requiring consideration in the schedule. Several sites require the use of an adjacent site for staging. (authors)

  14. 2014 DOE Project Management Workshop

    Broader source: Energy.gov [DOE]

    What:  2014 DOE Project Management Workshop (Meeting the Challenge—Integrated Acquisition & Project Management)

  15. Project Management Lessons Learned

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2008-08-05

    The guide supports DOE O 413.3A, Program and Project Management for the Acquisition of Capital Assets, and aids the federal project directors and integrated project teams in the execution of projects.

  16. Savannah River Remediation (SRR) Expanded Staff Meeting

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Savannah River Remediation Delivering the Mission Dave Olson President and Project Manager ... Liquid Waste Operations contractor Savannah River Remediation LLC * Began work in ...

  17. Information Technology Project Management

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2012-12-03

    The Order provides program and project management direction for the acquisition and management of IT projects, investments, and initiatives. Cancels DOE G 200.1-1. Admin Chg 1 approved 1-16-2013.

  18. Information Technology Project Management

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2012-12-03

    The Order provides program and project management direction for the acquisition and management of IT projects, investments, and initiatives. Admin Chg 1, dated 1-16-2013, supersedes DOE O 415.1.

  19. Interstate Technology & Regulatory Council (ITRC) Remediation Management of Complex Sites: Case Studies and Guidance

    Broader source: Energy.gov [DOE]

    Interstate Technology & Regulatory Council (ITRC) Remediation Management of Complex Sites: Case Studies and Guidance

  20. Consolidated Online Data Management Strategy in Support of Environmental Remediation Activities at the Dupont Chambers Works Formerly Utilized Sites Remedial Action Program (Fusrap) Site

    SciTech Connect (OSTI)

    Nelson, K.A.; Desai, N.B.; Samus, J.E.; Bock, G.O.

    2007-07-01

    The U.S. Army Corps of Engineers (USACE) has developed and implemented an innovative online data management application in support of site characterization and remediation activities at the DuPont Chambers Works Formerly Utilized Sites Remedial Action Program (FUSRAP) Site. The password-protected, web-based application was implemented to centralize project data, facilitate project communications, and provide a large and diverse group of project team members with access to the data and analytical tools they need to efficiently and effectively manage the ongoing characterization and remediation efforts. Centralizing resources using the online application and web-based strategy streamlines data access and communications, allowing the team to effectively keep the project on track while reducing the costs associated with data requests, data duplication, document review and retrieval, software requirements, and lapses in communication or data transfer. (authors)

  1. Project Management Resources | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Project Management Resources Project Management Resources Performance & Project Completion Environmental Management Completed Projects 2005-Present EM Current Project Performance ...

  2. Waste Management Plan for the Oak Ridge National Remedial Investigation/Feasibility Study

    SciTech Connect (OSTI)

    Not Available

    1988-04-01

    In accordance with the requirements of the Remedial Investigation/Feasibility Study (RI/FS) Project Quality Assurance Plan, this Waste Management Plan establishes clear lines of responsibility and authority, documentation requirements, and operational guidance for the collection, identification, segregation, classification, packaging, certification, and storage/disposal of wastes. These subjects are discussed in the subsequent sections of this document.

  3. Voluntary Protection Program Onsite Review, Soil and Groundwater Remediation Project- March 2007

    Broader source: Energy.gov [DOE]

    Evaluation to determine whether Soil and Groundwater Remediation Project is performing at a level deserving DOE-VPP recognition.

  4. Gas cylinder disposal pit remediation waste minimization and management

    SciTech Connect (OSTI)

    Alas, C.A.; Solow, A.; Criswell, C.W.; Spengler, D.; Brannon, R.; Schwender, J.M.; Eckman, C.K.; Rusthoven, T.

    1995-02-01

    A remediation of a gas cylinder disposal pit at Sandia National Laboratories, New Mexico has recently been completed. The cleanup prevented possible spontaneous releases of hazardous gases from corroded cylinders that may have affected nearby active test areas at Sandia`s Technical Area III. Special waste management, safety, and quality plans were developed and strictly implemented for this project. The project was conceived from a waste management perspective, and waste minimization and management were built into the planning and implementation phases. The site layout was planned to accommodate light and heavy equipment, storage of large quantities of suspect soil, and special areas to stage and treat gases and reactive chemicals removed from the pit, as well as radiation protection areas. Excavation was a tightly controlled activity using experienced gas cylinder and reactive chemical specialists. Hazardous operations were conducted at night under lights, to allow nearby daytime operations to function unhindered. The quality assurance plan provided specific control of, and documentation for, critical decisions, as well as the record of daily operations. Both hand and heavy equipment excavation techniques were utilized. Hand excavation techniques were utilized. Hand excavation techniques allows sealed glass containers to be exhumed unharmed. In the end, several dozen thermal batteries; 5 pounds (2.3 kg) of lithium metal; 6.6 pounds (3.0 kg) of rubidium metal; several kilograms of unknown chemicals; 140 cubic yards (107 cubic meters) of thorium-contaminated soil; 270 cubic yards (205 cubic meters) of chromium-contaminated soil; and 450 gas cylinders, including 97 intact cylinders containing inert, flammable, toxic, corrosive, or oxidizing gases were removed and effectively managed to minimize waste.

  5. Acquisition and Project Management

    National Nuclear Security Administration (NNSA)

    4%2A en Acquisition and Project Management Office volunteers get up-close look at Office of Secure Transportation exercise http:nnsa.energy.govblogacquisition-and-project-mana...

  6. Spent Nuclear Fuel project, project management plan

    SciTech Connect (OSTI)

    Fuquay, B.J.

    1995-10-25

    The Hanford Spent Nuclear Fuel Project has been established to safely store spent nuclear fuel at the Hanford Site. This Project Management Plan sets forth the management basis for the Spent Nuclear Fuel Project. The plan applies to all fabrication and construction projects, operation of the Spent Nuclear Fuel Project facilities, and necessary engineering and management functions within the scope of the project

  7. Tank waste remediation system systems engineering management plan

    SciTech Connect (OSTI)

    Peck, L.G.

    1996-02-06

    This Systems Engineering Management Plan (SEMP) describes the Tank Waste Remediation Systems (TWRS) implementation of U.S. Department of Energy (DOE) Systems Engineering (SE) policy provided in Tank Waste Remediation System Systems Engineering Management Policy, DOE/RL letter, 95-RTI-107, Oct. 31, 1995. This SEMP defines the products, process, organization, and procedures used by the TWRS Program to accomplish SE objectives. This TWRS SEMP is applicable to all aspects of the TWRS Program and will be used as the basis for tailoring SE to apply necessary concepts and principles to develop and mature the processes and physical systems necessary to achieve the desired end states of the program.

  8. Contract/Project Management

    Office of Environmental Management (EM)

    1 st Quarter Overall Contract and Project Management Performance Metrics and Targets 1 Contract/Project Management Primary Performance Metrics FY 2010 Target 1st Qtr FY 2010 Actual FY 2010 Pre- & Post-CAP Comment 1a. Capital Asset Line Item Projects: (Pre-RCA/CAP) 90% of projects completed within 110% of CD-2 TPC by FY11. 1b. Capital Asset Line Item Projects: (Post-RCA/CAP) 85% Line Item 73% Line Item 70% Pre-CAP 100% Post-CAP This is a projection based on a 3-year rolling average (FY08 to

  9. Contract/Project Management

    Office of Environmental Management (EM)

    Second Quarter Overall Contract and Project Management Performance Metrics and Targets 1 Contract/Project Management Primary Performance Metrics FY 2010 Target FY 2010 Actual FY 2010 Pre- & Post-CAP Comment 1a. Capital Asset Line Item Projects: (Pre-RCA/CAP) 90% of projects completed within 110% of CD-2 TPC by FY11. 1b. Capital Asset Line Item Projects: (Post-RCA/CAP) 85% Line Item 73% Line Item 70% Pre-CAP 100% Post-CAP This is a projection based on a 3-year rolling average (FY08 to FY10).

  10. Contract/Project Management

    Office of Environmental Management (EM)

    Third Quarter Overall Contract and Project Management Performance Metrics and Targets 1 Contract/Project Management Primary Performance Metrics FY 2010 Target FY 2010 Forecast FY 2010 Pre- & Post-CAP Comment 1a. Capital Asset Line Item Projects: (Pre-RCA/CAP) 90% of projects completed within 110% of CD-2 TPC by FY11. 1b. Capital Asset Line Item Projects: (Post-RCA/CAP) 85% Line Item 71% Line Item 70% Pre-CAP 100% Post-CAP This is a projection based on a 3-year rolling average (FY08 to FY10).

  11. Uranium Mill Tailings Remedial Action Project. 1995 Environmental Report

    SciTech Connect (OSTI)

    1996-06-01

    In accordance with U.S. Department of Energy (DOE) Order 23 1. 1, Environment, Safety and Health Reporting, the DOE prepares an annual report to document the activities of the Uranium Mill Tailings Remedial Action (UMTRA) Project environmental monitoring program. This monitoring must comply with appropriate laws, regulations, and standards, and it must identify apparent and meaningful trends in monitoring results. The results of all monitoring activities must be communicated to the public. The UMTRA Project has prepared annual environmental reports to the public since 1989.

  12. Contract/Project Management

    Office of Environmental Management (EM)

    Fourth Quarter Overall Contract and Project Management Performance Metrics and Targets 1 Contract/Project Management Primary Performance Metrics FY 2010 Target FY 2010 Actual FY 2010 Pre- & Post-CAP Comment 1a. Capital Asset Line Item Projects: (Pre-RCA/CAP) 90% of projects completed within 110% of CD-2 TPC by FY11. 1b. Capital Asset Line Item Projects: (Post-RCA/CAP) 85% Line Item 69% Line Item 67% Pre-CAP 100% Post-CAP This is based on a 3-year rolling average (FY08 to FY10). TPC is Total

  13. Contract/Project Management

    Office of Environmental Management (EM)

    First Quarter Overall Contract and Project Management Performance Metrics and Targets 1 Contract/Project Management Primary Performance Metrics FY 2011 Target FY 2011 Actual & Forecast FY 2011 Pre- & Post-CAP Comment 1a. Capital Asset Line Item Projects: (Pre-RCA/CAP) Projects completed within 110% of CD-2 TPC. 1b. Capital Asset Line Item Projects: (Post-RCA/CAP) 90% Line Item 79% Line Item 71% Pre-CAP 100% Post-CAP This is based on a 3-year rolling average (FY09 to FY11). TPC is Total

  14. Contract/Project Management

    Office of Environmental Management (EM)

    Second Quarter Overall Contract and Project Management Improvement Performance Metrics and Targets 1 Contract/Project Management Primary Performance Metrics FY 2011 Target FY 2011 Forecast FY 2011 Pre- & Post-CAP Forecast Comment 1a. Capital Asset Line Item Projects: (Pre-RCA/CAP) Projects completed within 110% of CD-2 TPC. 1b. Capital Asset Line Item Projects: (Post-RCA/CAP) 90% Line Item 84% Line Item 78% Pre-CAP 100% Post-CAP This is based on a 3-year rolling average (FY09 to FY11). TPC

  15. Contract/Project Management

    Office of Environmental Management (EM)

    Third Quarter Overall Contract and Project Management Improvement Performance Metrics and Targets 1 Contract/Project Management Primary Performance Metrics FY 2011 Target FY 2011 Forecast FY 2011 Pre- & Post-CAP Forecast Comment 1a. Capital Asset Line Item Projects: (Pre-RCA/CAP) Projects completed within 110% of CD-2 TPC. 1b. Capital Asset Line Item Projects: (Post-RCA/CAP) 90% Line Item 84% Line Item 78% Pre-CAP 100% Post-CAP This is based on a 3-year rolling average (FY09 to FY11). TPC is

  16. Contract/Project Management

    Office of Environmental Management (EM)

    Fourth Quarter Overall Contract and Project Management Improvement Performance Metrics and Targets 1 Contract/Project Management Primary Performance Metrics FY 2011 Target FY 2011 Actual FY 2011 Pre- & Post-CAP Actual Comment 1a. Capital Asset Line Item Projects: (Pre-RCA/CAP) Projects completed within 110% of CD-2 TPC. 1b. Capital Asset Line Item Projects: (Post-RCA/CAP) 90% Line Item 84% Line Item 77% Pre-CAP 100% Post-CAP This is based on a 3-year rolling average (FY09 to FY11). TPC is

  17. Contract/Project Management

    Office of Environmental Management (EM)

    First Quarter Overall Contract and Project Management Improvement Performance Metrics and Targets 1 Contract/Project Management Performance Metric FY 2012 Target FY 2012 Forecast FY 2012 Pre- & Post-CAP Forecast Comment Capital Asset Project Success: Complete 90% of capital asset projects at original scope and within 110% of CD-2 TPC. 90%* 84% Construction 83% Cleanup 85% 77% Pre-CAP 86% Post- CAP This is based on a 3- year rolling average (FY10 to FY12). TPC is Total Project Cost.

  18. Contract/Project Management

    Office of Environmental Management (EM)

    Second Quarter Overall Contract and Project Management Improvement Performance Metrics and Targets 1 Contract/Project Management Performance Metric FY 2012 Target FY 2012 Forecast FY 2012 Pre- & Post-CAP Forecast Comment Capital Asset Project Success: Complete 90% of capital asset projects at original scope and within 110% of CD-2 TPC. 90%* 88% Construction 87% Cleanup 89% 77% Pre-CAP 92% Post- CAP This is based on a 3- year rolling average (FY10 to FY12). TPC is Total Project Cost.

  19. Contract/Project Management

    Office of Environmental Management (EM)

    Third Quarter Overall Contract and Project Management Improvement Performance Metrics and Targets 1 Contract/Project Management Performance Metric FY 2012 Target FY 2012 Forecast FY 2012 Pre- & Post-CAP Forecast Comment Capital Asset Project Success: Complete 90% of capital asset projects at original scope and within 110% of CD-2 TPC. 90%* 87% Construction 87% Cleanup 87% 77% Pre-CAP 90% Post- CAP This is based on a 3- year rolling average (FY10 to FY12). TPC is Total Project Cost.

  20. Contract/Project Management

    Office of Environmental Management (EM)

    Fourth Quarter Overall Contract and Project Management Improvement Performance Metrics and Targets 1 Contract/Project Management Performance Metric FY 2012 Target FY 2012 Final FY 2012 Pre- & Post-CAP Final Comment Capital Asset Project Success: Complete 90% of capital asset projects at original scope and within 110% of CD-2 TPC. 90%* 86% Construction 87% Cleanup 84% 77% Pre-CAP 89% Post-CAP This is based on a 3- year rolling average (FY10 to FY12). TPC is Total Project Cost.

  1. Tank waste remediation system risk management list

    SciTech Connect (OSTI)

    Collard, L.B.

    1995-10-31

    The Tank Waste Remedation System (TWRS) Risk Management List and it`s subset of critical risks, the Critical Risk Management List, provide a tool to senior RL and WHC management (Level-1 and -2) to manage programmatic risks that may significantly impact the TWRS program. The programmatic risks include cost, schedule, and performance risks. Performance risk includes technical risk, supportability risk (such as maintainability and availability), and external risk (i.e., beyond program control, for example, changes in regulations). The risk information includes a description, its impacts, as evaluation of the likelihood, consequences and risk value, possible mitigating actions, and responsible RL and WHC managers. The issues that typically form the basis for the risks are presented in a separate table and the affected functions are provided on the management lists.

  2. Enterprise Assessments Targeted Review of Work Planning and Control at the Hanford Central Plateau Environmental Remediation Projects- June 2015

    Broader source: Energy.gov [DOE]

    Targeted Review of Work Planning and Control at the Hanford Central Plateau Environmental Remediation Projects

  3. Remediation

    SciTech Connect (OSTI)

    Oostrom, Mart; Falta, Ron W.; Mayer, Alex S.; Javandel, I.; Hassanizadeh, S. M.

    2005-12-06

    The three most frequently used remediation technologies are discussed: (1) NAPL removal, (2) Pump-and-Treat, (3) Soil Vapor Extraction.

  4. Tank waste remediation system characterization project quality policies

    SciTech Connect (OSTI)

    Trible, T.C., Westinghouse Hanford

    1996-07-31

    This quality plan describes the system used by Characterization Project management to achieve quality. This plan is comprised on eleven quality policies which, when taken together, form a management system deployed to achieve quality. This quality management system is based on the customer`s quality requirements known as the `RULE`, 10 CFR 830.120, Quality Assurance.

  5. Contract/Project Management

    Office of Environmental Management (EM)

    Fourth Quarter Overall Root Cause Analysis (RCA)/Corrective Action Plan (CAP) Performance Metrics 1 Contract/Project Management Performance Metric FY 2013 Target FY 2013 Actual FY 2013 Pre- & Post-CAP* Actual Comment Capital Asset Project Success: Complete 90% of capital asset projects at original scope and within 110% of CD-2 TPC. 90% 83% Construction 84% Cleanup 82% 70% Pre-CAP 84% Post-CAP Based on 3-year rolling period (FY11 to FY13) of 93 projects. TPC is Total Project Cost.

  6. The Gunite and Associated Tanks Remediation Project Tank Waste Retrieval Performance and Lessons Learned, vol. 1 [of 2

    SciTech Connect (OSTI)

    Lewis, BE

    2003-10-07

    The Gunite and Associated Tanks (GAAT) Remediation Project was the first of its kind performed in the United States. Robotics and remotely operated equipment were used to successfully transfer almost 94,000 gal of remote-handled transuranic sludge containing over 81,000 Ci of radioactive contamination from nine large underground storage tanks at the Oak Ridge National Laboratory (ORNL). The sludge was transferred with over 439,000 gal of radioactive waste supernatant and {approx}420,500 gal of fresh water that was used in sluicing operations. The GAATs are located in a high-traffic area of ORNL near a main thoroughfare. A phased and integrated approach to waste retrieval operations was used for the GAAT Remediation Project. The project promoted safety by obtaining experience from low-risk operations in the North Tank Farm before moving to higher-risk operations in the South Tank Farm. This approach allowed project personnel to become familiar with the tanks and waste, as well as the equipment, processes, procedures, and operations required to perform successful waste retrieval. By using an integrated approach to tank waste retrieval and tank waste management, the project was completed years ahead of the original baseline schedule, which resulted in avoiding millions of dollars in associated costs. This report is organized in two volumes. Volume 1 provides information on the various phases of the GAAT Remediation Project. It also describes the different types of equipment and how they were used. The emphasis of Volume 1 is on the description of the tank waste retrieval performance and the lessons learned during the GAAT Remediation Project. Volume 2 provides the appendixes for the report, which include the following information: (A) Background Information for the Gunite and Associated Tanks Operable Unit; (B) Annotated Bibliography; (C) Comprehensive Listing of the Sample Analysis Data from the GAAT Remediation Project; (D) GAAT Equipment Matrix; and (E) Vendor List

  7. Project Management Policies & Principles Memo

    Broader source: Energy.gov [DOE]

    Memo enhances and clarifies departmental policy related to project management as a result of the Improving Project Management Study and subsequent Secretarial Memo dated December 2014.

  8. Project Overview: Successful Field-Scale In Situ Thermal NAPL Remediation |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy Project Overview: Successful Field-Scale In Situ Thermal NAPL Remediation Project Overview: Successful Field-Scale In Situ Thermal NAPL Remediation Paper presented at the Third International Conference on Oxidation and Reduction Technologies for Soil and Groundwater. October 2004, San Diego, California. Michael Butherus, David S. Ingle, Randall Juhlin, Joseph Daniel Project Overview: Successful Field-Scale In Situ Thermal NAPL Remediation (305.82 KB) More Documents &

  9. Acquisition and Project Management Continuous Improvement Presentation...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    and Project Management Continuous Improvement Presentation Acquisition and Project Management Continuous Improvement Presentation Presentation on Acquisition and Project Management ...

  10. Project Management Coordination Office | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Project Management Coordination Office Project Management Coordination Office The Project Management Coordination Office (PMCO) provides guidance, leadership, training, and tools ...

  11. Contract/Project Management

    Office of Environmental Management (EM)

    3 Third Quarter Overall Root Cause Analysis (RCA)/Corrective Action Plan (CAP) Performance Metrics 1 Contract/Project Management Performance Metric FY 2013 Target FY 2013 Forecast FY 2013 Pre- & Post-CAP* Forecast Comment Capital Asset Project Success: Complete 90% of capital asset projects at original scope and within 110% of CD-2 TPC. 90%* 83% Construction 85% Cleanup 80% 70% Pre-CAP 84% Post-CAP This is based on a 3- year rolling average (FY11 to FY13). TPC is Total Project Cost.

  12. Tank waste remediation system nuclear criticality safety program management review

    SciTech Connect (OSTI)

    BRADY RAAP, M.C.

    1999-06-24

    This document provides the results of an internal management review of the Tank Waste Remediation System (TWRS) criticality safety program, performed in advance of the DOE/RL assessment for closure of the TWRS Nuclear Criticality Safety Issue, March 1994. Resolution of the safety issue was identified as Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) Milestone M-40-12, due September 1999.

  13. The Gunite and Associated Tanks Remediation Project Tank Waste Retrieval Performance and Lessons Learned, vol. 2 [of 2

    SciTech Connect (OSTI)

    Lewis, BE

    2003-10-07

    The Gunite and Associated Tanks (GAAT) Remediation Project was the first of its kind performed in the United States. Robotics and remotely operated equipment were used to successfully transfer almost 94,000 gal of remote-handled transuranic sludge containing over 81,000 Ci of radioactive contamination from nine large underground storage tanks at the Oak Ridge National Laboratory (ORNL). The sludge was transferred with over 439,000 gal of radioactive waste supernatant and {approx}420,500 gal of fresh water that was used in sluicing operations. The GAATs are located in a high-traffic area of ORNL near a main thoroughfare. Volume 1 provides information on the various phases of the project and describes the types of equipment used. Volume 1 also discusses the tank waste retrieval performance and the lessons learned during the remediation effort. Volume 2 consists of the following appendixes, which are referenced in Vol. 1: A--Background Information for the Gunite and Associated Tanks Operable Unit; B--Annotated Bibliography; C--GAAT Equipment Matrix; D--Comprehensive Listing of the Sample Analysis Data from the GAAT Remediation Project; and E--Vendor List for the GAAT Remediation Project. The remediation of the GAATs was completed {approx}5.5 years ahead of schedule and {approx}$120,435K below the cost estimated in the Remedial Investigation/Feasibility Study for the project. These schedule and cost savings were a direct result of the selection and use of state-of-the-art technologies and the dedication and drive of the engineers, technicians, managers, craft workers, and support personnel that made up the GAAT Remediation Project Team.

  14. DOE Project Management Update (Metrics)

    Broader source: Energy.gov [DOE]

    Michael Peek, Deputy Director, Office of Project Management Oversight and Assessments March 22, 2016

  15. 2014 DEPARTMENT OF ENERGY PROJECT MANAGEMENT WORKSHOP

    Broader source: Energy.gov [DOE]

    What:  2014 DOE Project Management Workshop (Meeting the Challenge—Integrated Acquisition & Project Management)

  16. Project Management Information Systems (PMIS) | Department of...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Project Management Information Systems (PMIS) Project Management Information Systems (PMIS) Project Assessment & Reporting System (PARS IIe) Office of Project Management Oversight...

  17. Uranium Mill Tailings Remedial Action Project Safety Advancement Field Effort (SAFE) Program

    SciTech Connect (OSTI)

    Not Available

    1994-02-01

    In 1992, the Uranium Mill Tailings Remedial Action (UMTRA) Project experienced several health and safety related incidents at active remediation project sites. As a result, the U.S. Department of Energy (DOE) directed the Technical Assistance Contractor (TAC) to establish a program increasing the DOE`s overall presence at operational remediation sites to identify and minimize risks in operations to the fullest extent possible (Attachments A and B). In response, the TAC, in cooperation with the DOE and the Remedial Action Contractor (RAC), developed the Safety Advancement Field Effort (SAFE) Program.

  18. Project Management Lessons Learned (PMLL) Repository | Department...

    Energy Savers [EERE]

    Information Systems Project Management Lessons Learned (PMLL) Repository Project Management Lessons Learned (PMLL) Repository The Department of Energy utilizes Project ...

  19. LTS Project Management - Hanford Site

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Project Management About Us Hanford Cultural Resources LTS Home Page LTS Project Management LTS Transition and Timeline LTS Execution LTS Background LTS Information Management LTS Fact Sheets / Briefings LTS In The News LTS Related Links LTS Contact Us LTS Project Management Email Email Page | Print Print Page | Text Increase Font Size Decrease Font Size DOE-RL Office of Assistant Manager for Mission Support (AMMS) is responsible for LTS Program Management. The Site Stewardship Division is

  20. Project Management | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Employees in our Project Management Division address projects' planning and execution, as specified in DOE Order ... the critical decision process, reporting, and career ...

  1. Project Management Career Development Program | Department of...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    are here Home Operational Management Certifications and Professional Development Project Management Career Development Program Project Management Career Development...

  2. Unique Regulatory Approach for Licensing the Port Hope Remediation Project in Canada - 13315

    SciTech Connect (OSTI)

    Kostova, M.; Howard, D.; Elder, P.

    2013-07-01

    The Port Hope remediation project is a part of a larger initiative of the Canadian Federal Government the Port Hope Area Initiative (PHAI) which is based upon a community proposal. The Government of Canada, through Natural Resources Canada (NRCan) is investing $1.28 billion over 10 years to clean up historic low-level radioactive waste in the Port Hope Area and to provide long-term safe management of the low-level radioactive wastes in the Port Hope Area. These wastes arose from the activities of a former Federal Crown Corporation (Eldorado Nuclear) and its private sector predecessors. In Canada, historic waste are defined as low-level radioactive waste that was managed in a manner no longer considered acceptable, but for which the original producer cannot reasonably be held responsible or no longer exists and for which the Federal Government has accepted responsibility. In Canada, under the current regulatory framework, the environmental remediation is not considered as a distinct phase of the nuclear cycle. The regulatory approach for dealing with existing sites contaminated with radioactive residues is defined on the basis of risk and application of existing regulations. A unique regulatory approach was taken by the Canadian Nuclear Safety Commission (CNSC) to address the various licensing issues and to set out the requirements for licensing of the Port Hope Project within the current regulatory framework. (authors)

  3. Environmental Management (EM) Cleanup Projects

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2008-09-24

    The guide supports DOE O 413.3A, Program and Project Management for the Acquisition of Capital Assets, and provides guidance on environmental management cleanup projects. Canceled by DOE N 251.105.

  4. Project Management Career Development Program

    Office of Energy Efficiency and Renewable Energy (EERE)

    The Project Management Career Development Program (PMCDP) in Office of Project Management Oversight and Assessments was established in 2001 by a Congressional mandate to ensure the Department of...

  5. Process safety management and interim or remedial action plans

    SciTech Connect (OSTI)

    Boss, M.J.; Henney, D.A.; Heitzman, V.K. [HWS Consulting Group, Inc., Omaha, NE (United States); Day, D.W. [Army Corps of Engineers, Omaha, NE (United States)

    1996-12-31

    Remedial Actions, including Interim Remedial Activities, often require the use of treatment facilities or stabilization techniques using on-site chemical processes. As such, the 29 CFR 1910.119 Process Safety Management (PSM) of Highly Hazardous Chemicals (PSM Standard) and the USEPA regulations for Risk Management Planning require that these chemicals and their attendant potential hazards be identified. A Hazard and Operation (HAZOP) study, Failure Mode and Effect Analysis (FMEA), Fault Tree Analysis, or equivalent graphic presentation of processes must be completed. These studies form a segment of the Process Hazard Analysis (PHA). HAZOP addresses each system and each element of a system that could deviate from normal operations and thus cause a hazard. A full assessment of each process is produced by looking at the hazards, consequences, causes and personnel protection needed. Many variables must be considered when choosing the appropriate PHA technique including the size of the plant, the number of processes, the types of processes, and the types of chemicals used. A mixture of these techniques may be required to adequately transmit information about the process being evaluated.

  6. Project Management Improvements Drive Progress

    Broader source: Energy.gov [DOE]

    WASHINGTON, D.C. – Improving project management has been a top priority of EM’s senior leadership.

  7. Vicinity Property Assessments at Formerly Utilized Sites Remedial Action Program Project Sites in the New York District - 13420

    SciTech Connect (OSTI)

    Ewy, Ann; Hays, David

    2013-07-01

    The Formerly Utilized Sites Remedial Action Program (FUSRAP) has addressed sites across the nation for almost 4 decades. Multiple stake holder pressures, multiple regulations, and process changes occur over such long time periods. These result in many challenges to the FUSRAP project teams. Initial FUSRAP work was not performed under Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) Records of Decision (ROD). The ROD identifies the remedy decision and ultimately the criteria to be used to release a site. Early FUSRAP projects used DOE Orders or the Uranium Mill Tailings Radiation Control Act (UMTRCA) standards. Under current RODs, regulations may differ, resulting in different cleanup criteria than that used in prior Vicinity Property (VP) remediation. The USACE, in preparation for closeout of Sites, conducts reviews to evaluate whether prior actions were sufficient to meet the cleanup criteria specified in the current ROD. On the basis of these reviews, USACE has conducted additional sampling, determined that prior actions were sufficient, or conducted additional remediation consistent with the selected remedy in the ROD. As the public pressures, regulations, and processes that the FUSRAP encounters continue to change, the program itself continues to evolve. Assessment of VPs at FUSRAP sites is a necessary step in the life cycle of our site management. (authors)

  8. Project Management Plans | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Management Plans Project Management Plans The purpose here is to assist project managers and project planners in creating a project plan by providing examples and pointing to information that have been successfully used by others in the past. Project Management Plans (353.99 KB) More Documents & Publications Project Management Plan Examples Project Management Plan Examples 1 - 80 Deactivation Management

  9. Protecting Lake Ontario - Treating Wastewater from the Remediated Low-Level Radioactive Waste Management Facility - 13227

    SciTech Connect (OSTI)

    Freihammer, Till; Chaput, Barb; Vandergaast, Gary; Arey, Jimi

    2013-07-01

    The Port Granby Project is part of the larger Port Hope Area Initiative, a community-based program for the development and implementation of a safe, local, long-term management solution for historic low level radioactive waste (LLRW) and marginally contaminated soils (MCS). The Port Granby Project involves the relocation and remediation of up to 0.45 million cubic metres of such waste from the current Port Granby Waste Management Facility located in the Municipality of Clarington, Ontario, adjacent to the shoreline of Lake Ontario. The waste material will be transferred to a new suitably engineered Long-Term Waste Management Facility (LTWMF) to be located inland approximately 700 m from the existing site. The development of the LTWMF will include construction and commissioning of a new Wastewater Treatment Plant (WWTP) designed to treat wastewater consisting of contaminated surface run off and leachate generated during the site remediation process at the Port Granby Waste Management Facility as well as long-term leachate generated at the new LTWMF. Numerous factors will influence the variable wastewater flow rates and influent loads to the new WWTP during remediation. The treatment processes will be comprised of equalization to minimize impacts from hydraulic peaks, fine screening, membrane bioreactor technology, and reverse osmosis. The residuals treatment will comprise of lime precipitation, thickening, dewatering, evaporation and drying. The distribution of the concentration of uranium and radium - 226 over the various process streams in the WWTP was estimated. This information was used to assess potential worker exposure to radioactivity in the various process areas. A mass balance approach was used to assess the distribution of uranium and radium - 226, by applying individual contaminant removal rates for each process element of the WTP, based on pilot scale results and experience-based assumptions. The mass balance calculations were repeated for various flow

  10. Fermilab | Directorate | Office of Project Management Oversight...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Office of Project Management Oversight Fermilab ManagementNon-Scientific Projects Current Management Projects IARC OTE Building Liquid Argon Test Building (LArTB) TeV ...

  11. IT Project Management Profile | Department of Energy

    Energy Savers [EERE]

    Project Management Profile IT Project Management Profile This form lists positionsexperience and training relating to project management; include other positionsexperience or ...

  12. IT Project Management Profile | Department of Energy

    Energy Savers [EERE]

    Project Management Profile IT Project Management Profile This is a form that must be completed to initiate the assessment of a Project Manager to determine the level of ...

  13. Project Management Plan Examples | Department of Energy

    Office of Environmental Management (EM)

    Examples Project Management Plan Examples Examples From Project Management Plans The following material has been extracted from several project management plans. The order in which ...

  14. Project Management Perspective - Paul Bosco, Director, Office...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Project Management Perspective - Paul Bosco, Director, Office of Acquisition and Project Management Project Management Perspective - Paul Bosco, Director, Office of Acquisition and ...

  15. Evaluation of surface water treatment and discharge options for the Weldon Spring Site Remedial Action Project

    SciTech Connect (OSTI)

    Goyette, M.L.; MacDonell, M.M.

    1992-09-01

    The US Department of Energy (DOE), under its Environmental Restoration and Waste Management Program, is responsible for conducting response actions at the Weldon Spring site in St. Charles County, Missouri. The site consists of two noncontiguous areas: (1) the chemical plant area, which includes four raffinate pits and two small ponds, and (2) a 3.6-ha (9-acre) quarry located about 6.4 km (4 mi) southwest of the chemical plant area. Both of these areas became chemically and radioactively contaminated as a result of processing and disposal activities that took place from the 1940s through 1960s. The Weldon Spring site, located about 48 km (30 mi) west of St. Louis, is listed on the National Priorities List of the US Environmental Protection Agency. Nitroaromatic explosives were processed by the Army at the chemical plant area during the 1940s, and radioactive materials were processed by DOE`s predecessor agency (the Atomic Energy Commission) during the 1950s and 1960s. Overall remediation of the Weldon Spring site is being addressed through the Weldon Spring Site Remedial Action Project, and it consists of several components. One component is the management of radioactively and chemically contaminated surface water impoundments at the chemical plant area -- i.e., the four raffinate pits, Frog Pond, and Ash Pond which was addressed under a separate action and documented in an engineering evaluation/cost analysis report. This report discusses the evaluation of surface water treatment at the Weldon Spring site.

  16. Quality assurance plan for the molten salt reactor experiment Remediation Project at Oak Ridge National Laboratory, Oak Ridge, Tennessee

    SciTech Connect (OSTI)

    1998-02-01

    This Quality Assurance Plan (QAP) identifies and describes the systems utilized by Molten Salt Reactor Experiment (MSRE) Remediation Project personnel to implement the requirements and associated applicable guidance contained in the Quality Program Description, Y/QD-15 Rev. 2 (Martin Marietta Energy Systems, Inc., 1995) and Environmental Management and Enrichment Facilities Work Smart Standards. This QAP defines the quality assurance (QA) requirements applicable to all activities and operations in and directly pertinent to the MSRE Remediation Project. This QAP will be periodically reviewed, revised, and approved as necessary. This QAP identifies and describes the QA activities and procedures implemented by the various Oak Ridge National Laboratory support organizations and personnel to provide confidence that these activities meet the requirements of this project. Specific support organization (Division) quality requirements, including the degree of implementation of each, are contained in the appendixes of this plan.

  17. Fernald Environmental Management Project Archived Soil & Groundwater...

    Office of Environmental Management (EM)

    Fernald Environmental Management Project Archived Soil & Groundwater Master Reports Fernald Environmental Management Project Archived Soil & Groundwater Master Reports Fernald ...

  18. Miamisburg Environmental Management Project Archived Soil & Groundwate...

    Office of Environmental Management (EM)

    Miamisburg Environmental Management Project Archived Soil & Groundwater Master Reports Miamisburg Environmental Management Project Archived Soil & Groundwater Master Reports ...

  19. Safety Improves Dramatically In Fluor Hanford Soil and Groundwater Remediation Project

    SciTech Connect (OSTI)

    Foster, A.L.; Gerber, M.S.; VonBargen, B.H.

    2008-07-01

    This paper describes dramatic improvements in the safety record of the Soil and Groundwater Remediation Project (SGRP) at the Hanford Site in southeast Washington state over the past four years. During a period of enormous growth in project work and scope, contractor Fluor Hanford reduced injuries, accidents, and other safety-related incidents and enhanced a safety culture that earned the SGRP Star Status in the Department of Energy's (DOE's) Voluntary Protection Program (VPP) in 2007. This paper outlines the complex and multi-faceted work of Fluor Hanford's SGRP and details the steps taken by the project's Field Operations and Safety organizations to improve safety. Holding field safety meetings and walk-downs, broadening safety inspections, organizing employee safety councils, intensively flowing down safety requirements to subcontractors, and adopting other methods to achieve remarkable improvement in safety are discussed. The roles of management, labor and subcontractors are detailed. Finally, SGRP's safety improvements are discussed within the context of overall safety enhancements made by Fluor Hanford in the company's 11 years of managing nuclear waste cleanup at the Hanford Site. (authors)

  20. Radiological Survey Results for Areas A1 North, A5A, A6, and B2 at the Molycorp Washington Remediation Project, Washington, Pennsylvania

    SciTech Connect (OSTI)

    W.C. Adams

    2007-03-13

    Perform radiological surveys of the Molycorp Washington Remediation Project (MWRP) facility in Washington, Pennsylvania

  1. Project Management | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    EM CAPITAL PORTFOLIO EM is tasked with solving the large scale, technically challenging ... to more effectively manage the cost and schedule performance of capital asset projects. ...

  2. Tank waste remediation system privatization phase 1 infrastructure project W-519, project execution plan

    SciTech Connect (OSTI)

    Parazin, R.J.

    1998-08-28

    This Project Execution Plan (PEP) defines the overall strategy, objectives, and contractor management requirements for the execution phase of Project W-519 (98-D403), Privatization Phase 1 Infrastructure Support, whose mission is to effect the required Hanford site infrastructure physical changes to accommodate the Privatization Contractor facilities. This plan provides the project scope, project objectives and method of performing the work scope and achieving objectives. The plan establishes the work definitions, the cost goals, schedule constraints and roles and responsibilities for project execution. The plan also defines how the project will be controlled and documented.

  3. Fermilab | Directorate | Office of Project Management Oversight...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Office of Project Management Oversight (OPMO) OPMO Projects Organization and Human Asset Plan Last modified: 12092011

  4. Office of Project Management Oversight & Assessments | Department...

    Broader source: Energy.gov (indexed) [DOE]

    Office of Project Management Oversight & Assessments Career Development Project Management Career Development Program (DOE Only) Acquisition Career Management Program (DOE Only)...

  5. TPA Project Manager's Lists - Hanford Site

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    TPA Project Manager's Lists Tri-Party Agreement The Agreement Announcements List of Approved Changes TPA Project Manager's Lists Modifications for Public Comment Data Management...

  6. Radiation Protection Considerations at USACE Formerly Utilized Sites Remedial Action Program (FUSRAP) Projects

    SciTech Connect (OSTI)

    Brown, S.H.

    2008-07-01

    The Formerly Utilized Sites Remedial Action Program (FUSRAP) was initially authorized by Congress in 1974. FUSRAP was enacted to address residual radioactive contamination associated with numerous sites across the U.S. at which radioactive material (primarily Uranium ores and related milling products) had been processed in support of the nation's nuclear weapons program dating back to the Manhattan Project and the period immediately following World War II. In October 1997, Congress transferred the management of this program from the Department of Energy to the United States Corp of Engineers. Through this program, the Corps addresses the environmental remediation of certain sites once used by DOE's predecessor agencies, the Manhattan Engineer District and the Atomic Energy Commission. The waste at FUSRAP sites consists mainly of low levels of uranium, thorium and radium, along with some mixed wastes. Upon completion of remedial activities, these sites are transferred to DOE for long-term stewardship activities. This paper presents and contrasts the radiological conditions and recent monitoring results associated with five large ongoing FUSRAP projects including Maywood, N.J.; the Linde site near Buffalo, N.Y.; Colonie in Albany N.Y. and the St Louis, Mo. airport and downtown sites. The radiological characteristics of soil and debris at each site and respective regulatory clean up criteria is presented and contrasted. Some differences are discussed in the radiological characteristics of material at some sites that result in variations in radiation protection monitoring programs. Additionally, summary data for typical personnel radiation exposure monitoring results are presented. In summary: 1. The FUSRAP projects for which data and observations are reported in this paper are considered typical of the radiological nature of FUSRAP sites in general. 2. These sites are characterized by naturally occurring uranium and thorium series radionuclides in soil and debris, at

  7. Contract/Project Management

    Broader source: Energy.gov (indexed) [DOE]

    Metric FY 2013 Target FY 2013 Forecast FY 2013 Pre- & Post-CAP* Forecast Comment Capital Asset Project Success: Complete 90% of capital asset projects at original scope and ...

  8. Contract/Project Management

    Broader source: Energy.gov (indexed) [DOE]

    Metric FY 2012 Target FY 2012 Forecast FY 2012 Pre- & Post-CAP Forecast Comment Capital Asset Project Success: Complete 90% of capital asset projects at original scope and ...

  9. Project Manager's Guide to Managing Impact and Process Evaluation...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Project Manager's Guide to Managing Impact and Process Evaluation Studies This report provides a step-by-step approach to help managers of EERE evaluation projects create and ...

  10. Career Map: Project Manager | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Manager Career Map: Project Manager A project manager and several workers stand over a large sheet of paper. Project Manager Position Title Project Manager Alternate Title(s) n/a Education & Training Level Bachelors required, prefer graduate degree Education & Training Level Description Experience in construction management, particularly wind plant construction, is vital for project managers. Most managers have experience working on several wind plant projects before they are selected to

  11. Management assessment of tank waste remediation system contractor readiness to proceed with phase 1B privatization

    SciTech Connect (OSTI)

    Honeyman, J.O.

    1998-01-09

    This Management Assessment of Tank Waste Remediation System (TWRS) Contractor Readiness to Proceed With Phase 1B Privatization documents the processes used to determine readiness to proceed with tank waste treatment technologies from private industry, now known as TWRS privatization. An overall systems approach was applied to develop action plans to support the retrieval and disposal mission of the TWRS Project. The systems and infrastructure required to support the mission are known. Required systems are either in place or plans have been developed to ensure they exist when needed. Since October 1996 a robust system engineering approach to establishing integrated Technical Baselines, work breakdown structures, tank farms organizational structure and configurations, work scope, and costs has become part of the culture within the TWRS Project. An analysis of the programmatic, management, and technical activities necessary to declare readiness to proceed with execution of the mission demonstrates that the system, personnel, and hardware will be on-line and ready to support the private contractors. The systems approach included defining the retrieval and disposal mission requirements and evaluating the readiness of the Project Hanford Management Contract (PHMC) team to support initiation of waste processing by the private contractors in June 2002 and to receive immobilized waste shortly thereafter. The Phase 1 feed delivery requirements from the private contractor Requests for Proposal were reviewed. Transfer piping routes were mapped, existing systems were evaluated, and upgrade requirements were defined.

  12. Final audit report of remedial action construction at the UMTRA Project Mexican Hat, Utah -- Monument Valley, Arizona, sites

    SciTech Connect (OSTI)

    1995-10-01

    The final audit report for remedial action at the Mexican Hat, Utah, Monument Valley, Arizona, Uranium Mill Tailings Remedial Action (UMTRA) Project sites consists of a summary of the radiological surveillances/audits, quality assurance (QA) in-process surveillances, and QA remedial action close-out inspections performed by the US Department of Energy (DOE) and the Technical Assistance Contractor (TAC); on-site construction reviews (OSCR) performed by the US Nuclear Regulatory Commission (NRC); and a surveillance performed by the Navajo Nation. This report refers to remedial action activities performed at the Mexican Hat, Utah--Monument Valley, Arizona, Uranium Mill Tailings Remedial Action (UMTRA) Project sites.

  13. Project Hanford management contract quality improvement project management plan

    SciTech Connect (OSTI)

    ADAMS, D.E.

    1999-03-25

    On July 13, 1998, the U.S. Department of Energy, Richland Operations Office (DOE-RL) Manager transmitted a letter to Fluor Daniel Hanford, Inc. (FDH) describing several DOE-RL identified failed opportunities for FDH to improve the Quality Assurance (QA) Program and its implementation. In addition, DOE-RL identified specific Quality Program performance deficiencies. FDH was requested to establish a periodic reporting mechanism for the corrective action program. In a July 17, 1998 response to DOE-RL, FDH agreed with the DOE concerns and committed to perform a comprehensive review of the Project Hanford Management Contract (PHMC) QA Program during July and August, 1998. As a result, the Project Hanford Management Contract Quality Improvement Plan (QIP) (FDH-3508) was issued on October 21, 1998. The plan identified corrective actions based upon the results of an in-depth Quality Program Assessment. Immediately following the scheduled October 22, 1998, DOE Office of Enforcement and Investigation (EH-10) Enforcement Conference, FDH initiated efforts to effectively implement the QIP corrective actions. A Quality Improvement Project (QI Project) leadership team was assembled to prepare a Project Management Plan for this project. The management plan was specifically designed to engage a core team and the support of representatives from FDH and the major subcontractors (MSCs) to implement the QIP initiatives; identify, correct, and provide feedback as to the root cause for deficiency; and close out the corrective actions. The QI Project will manage and communicate progress of the process.

  14. Managing Large Capital Projects

    Broader source: Energy.gov [DOE]

    Presentation from the 2015 DOE National Cleanup Workshop by Ken Picha, Deputy Assistant Secretary for Tank Waste and Nuclear Material, Office of Environmental Management.

  15. Project Management Practices

    Broader source: Energy.gov (indexed) [DOE]

    Version) See Figure 3-3. 19. Administrative Controls 1. Provisions relating to organization and management, procedures, recordkeeping, assessment, and reporting necessary to...

  16. WIPP Project Records Management Handbook

    SciTech Connect (OSTI)

    Not Available

    1991-01-01

    The Waste Isolation Pilot Plant (WIPP) Records Management Handbook provides the WIPP Project Records Management personnel with a tool to use to fulfill the requirements of the WIPP Records Program and direct their actions in the important area of records management. The handbook describes the various project areas involved in records management, and how they function. The handbook provides the requirements for Record Coordinators and Master Record Center (MRC) personnel to follow in the normal course of file management, records scheduling, records turnover, records disposition, and records retrieval. More importantly, the handbook provides a single reference which encompasses the procedures set fourth in DOE Order 1324.2A, Records Disposition'' ASME NQA-1, Quality Assurance Program Requirements for Nuclear Facilities'' and DOE-AL 5700.6B, General Operations Quality Assurance.'' These documents dictate how an efficient system of records management will be achieved on the WIPP Project.

  17. 2015 Project Management Awards | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    5 Project Management Awards 2015 Project Management Awards The annual DOE Project Management Workshop provides an opportunity to recognize and reward excellence in project management across the complex. This Year, the Department recognized eight (8) individual and team successes in project management. Award presentations were made by Elizabeth Sherwood-Randall, Deputy Secretary of Energy. The annual DOE Project Management Workshop provides an opportunity to recognize and reward excellence in

  18. Jefferson Lab Project Management & Integrated Planning

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    FEL Contact Our Staff Directorate Project Control System Manual Technical Engineering Development Facility (TEDF) Utilities Infrastructure Modernization (UIM) Office of Project Management Org Chart Project Management Office Kelly K. Krug, Project Management Office Manager (757) 269-6044, krug@jlab.org Christine Fragapane, Project Management Executive Assistant (757) 269-7502, chummel@jlab.org Matrixed: Claus H. Rode, 12 GeV Upgrade Project Manager (757) 269-7511, rode@jlab.org Program

  19. UMTRA Surface Project management action process document: Final. Revision 2

    SciTech Connect (OSTI)

    1996-06-01

    Title 1 of the UMTRCA authorized the DOE to undertake remedial actions at these designed sites and associated vicinity properties (VP), which contain uranium mill tailings and other residual radioactive materials (RRM) derived from the processing sites. Title 2 of the UMTRCA addresses uranium mill sites that were licensed at the time the UMTRCA was enacted. Cleanup of these Title 2 sites is the responsibility of the licensees. The cleanup of the Title 1 sites has been split into two separate projects: the Surface Project, which deals with the mill buildings, tailings, and contaminated soils at the sites and VPs; and the Ground Water Project, which is limited to the contaminated ground water at the sites. This management action process (MAP) document discusses the Uranium Mill Tailings Remedial Action (UMTRA) Surface Project. Since its inception through March 1996, the Surface Project (hereinafter called the Project) has cleaned up 16 of the 24 designated processing sites and approximately 5,000 VPs, reducing the risk to human health and the environment posed by the uranium mill tailings. Two of the 24 sites, Belfield and Bowman, North Dakota, will not be remediated at the request of the state, reducing the total number of sites to 22. By the start of FY1998, the remaining 6 processing sites and associated VPs will be cleaned up. The remedial action activities to be funded in FY1998 by the FY1998 budget request are remediation of the remaining Grand Junction, Colorado, VPs; closure of the Cheney disposal cell in Grand Junction, Colorado; and preparation of the completion reports for 4 completed sites.

  20. Information Technology Project Management - DOE Directives, Delegation...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    5.1 Admin Chg 1, Information Technology Project Management by Denise Hill Functional areas: Administrative Change, Information Technology, Project Management, The Order provides...

  1. Secretarial Memorandum on Integrating Project Management with...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Secretarial Memorandum on Integrating Project Management with NEPA Compliance to Improve Decision Making Secretarial Memorandum on Integrating Project Management with NEPA ...

  2. Acquisition and Project Management Continuous Improvement Presentation |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy and Project Management Continuous Improvement Presentation Acquisition and Project Management Continuous Improvement Presentation Presentation on Acquisition and Project Management Continuous Improvement. Acquisition and Project Management Continuous Improvement presentation (1.43 MB) More Documents & Publications Occupational Safety Performance Voluntary Protection Program Onsite Review, Safeguards and Security - August 2012 Report on Acquisition and Project

  3. Decontamination Technologies, Task 3, Urban Remediation and Response Project

    SciTech Connect (OSTI)

    Heiser,J.; Sullivan, T.

    2009-06-30

    In the aftermath of a Radiological Dispersal Device (RDD, also known as a dirty bomb) it will be necessary to remediate the site including building exteriors and interiors, equipment, pavement, vehicles, personal items etc. Remediation will remove or reduce radioactive contamination from the area using a combination of removing and disposing of many assets (including possible demolition of buildings), decontaminating and returning to service other assets, and fixing in place or leaving in place contamination that is deemed 'acceptable'. The later will require setting acceptable dose standards, which will require negotiation with all involved parties and a balance of risk and cost to benefit. To accomplish the first two, disposal or decontamination, a combination of technologies will be deployed that can be loosely classified as: Decontamination; Equipment removal and size reduction; and Demolition. This report will deal only with the decontamination technologies that will be used to return assets to service or to reduce waste disposal. It will not discuss demolition, size reduction or removal technologies or equipment (e.g., backhoe mounted rams, rock splitter, paving breakers and chipping hammers, etc.). As defined by the DOE (1994), decontamination is removal of radiological contamination from the surfaces of facilities and equipment. Expertise in this field comes primarily from the operation and decommissioning of DOE and commercial nuclear facilities as well as a small amount of ongoing research and development closely related to RDD decontamination. Information related to decontamination of fields, buildings, and public spaces resulting from the Goiania and Chernobyl incidents were also reviewed and provide some meaningful insight into decontamination at major urban areas. In order to proceed with decontamination, the item being processed needs to have an intrinsic value that exceeds the cost of the cleaning and justifies the exposure of any workers during the

  4. River Protection Project (RPP) Project Management Plan

    SciTech Connect (OSTI)

    NAVARRO, J.E.

    2001-03-07

    The Office of River Protection (ORP) Project Management Plan (PMP) for the River Protection Project (RPP) describes the process for developing and operating a Waste Treatment Complex (WTC) to clean up Hanford Site tank waste. The Plan describes the scope of the project, the institutional setting within which the project must be completed, and the management processes and structure planned for implementation. The Plan is written from the perspective of the ORP as the taxpayers' representative. The Hanford Site, in southeastern Washington State, has one of the largest concentrations of radioactive waste in the world, as a result of producing plutonium for national defense for more than 40 years. Approximately 53 million gallons of waste stored in 177 aging underground tanks represent major environmental, social, and political challenges for the U.S. Department of Energy (DOE). These challenges require numerous interfaces with state and federal environmental officials, Tribal Nations, stakeholders, Congress, and the US Department of Energy-Headquarters (DOE-HQ). The cleanup of the Site's tank waste is a national issue with the potential for environmental and economic impacts to the region and the nation.

  5. EIS-0198: Uranium Mill Tailings Remedial Action Groundwater Project

    Broader source: Energy.gov [DOE]

    This EIS assesses the potential programmatic impacts of conducting the Ground Water Project, provides a method for determining the site-specific ground water compliance strategies, and provides...

  6. DOE Office of Environmental Management Project and Contract Management

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Improvement Timeline | Department of Energy Acquisition » DOE Office of Environmental Management Project and Contract Management Improvement Timeline DOE Office of Environmental Management Project and Contract Management Improvement Timeline Improving DOE contract and project management is a top priority of the Department's senior management and entire organization. View some highlights of EM's improvement actions here. DOE Office of Environmental Management Contract and Project Management

  7. The CHPRC Groundwater and Technical Integration Support (Master Project) Quality Assurance Management Plan

    SciTech Connect (OSTI)

    Fix, N. J.

    2009-04-03

    The scope of the CH2M Hill Plateau Remediation Company, LLC (CHPRC) Groundwater and Technical Integration Support (Master Project) is for Pacific Northwest National Laboratory staff to provide technical and integration support to CHPRC. This work includes conducting investigations at the 300-FF-5 Operable Unit and other groundwater operable units, and providing strategic integration, technical integration and assessments, remediation decision support, and science and technology. The projects under this Master Project will be defined and included within the Master Project throughout the fiscal year, and will be incorporated into the Master Project Plan. This Quality Assurance Management Plan provides the quality assurance requirements and processes that will be followed by the CHPRC Groundwater and Technical Integration Support (Master Project) and all releases associated with the CHPRC Soil and Groundwater Remediation Project. The plan is designed to be used exclusively by project staff.

  8. Fermilab | Directorate | Office of Project Management Oversight...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    We work with project teams to establish standard project management processes, tools and training designed to both maximize project success and comply with DOE and Fermilab rules ...

  9. Fermilab | Directorate | Office of Project Management Oversight...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    DOE links DOE Office of Project Assessment (SC-28) DOE Office of Project Assessment Project Management Processes and Procedures DOE Directives Home Page DOE Policies, Orders and ...

  10. 2016 DOE Project Management Workshop | Department of Energy

    Office of Environmental Management (EM)

    6 DOE Project Management Workshop 2016 DOE Project Management Workshop 2016 DOE Project Management Workshop Completed The 2016 Project Management Workshop was held on March 22-23, ...

  11. X-701B Groundwater Remedy Portsmouth Ohio

    Office of Environmental Management (EM)

    X-701B Groundwater Remediation ETR Report Date: December 2008 ETR-20 United States Department of Energy Office of Environmental Management (DOE-EM) External Technical Review of the X-701B Groundwater Remedy, Portsmouth, Ohio Why DOE-EM Did This Review The Department of Energy (DOE) Portsmouth Paducah Project Office (PPPO) has responsibility for remediation of the X-701B ground water plume with the key contaminant of trichloroethene (TCE). The remedy has been divided into four phases: Phase I-

  12. Tank Waste Remediation Systems (TWRS) Configuration Management Implementation Plan

    SciTech Connect (OSTI)

    WEIR, W.R.

    2000-12-18

    The Tank Waste Configuration Management (TWRS) Configuration Management Implementation Plan descibes the execution of the configuration management (CM) that the contractor uses to manage and integrate its programmatic and functional operations to perform work.

  13. Grand Junction Projects Office Remedial Action Project Building 2 public dose evaluation. Final report

    SciTech Connect (OSTI)

    Morris, R.

    1996-05-01

    Building 2 on the U.S. Department of Energy (DOE) Grand Junction Projects Office (GJPO) site, which is operated by Rust Geotech, is part of the GJPO Remedial Action Program. This report describes measurements and modeling efforts to evaluate the radiation dose to members of the public who might someday occupy or tear down Building 2. The assessment of future doses to those occupying or demolishing Building 2 is based on assumptions about future uses of the building, measured data when available, and predictive modeling when necessary. Future use of the building is likely to be as an office facility. The DOE sponsored program, RESRAD-BUILD, Version. 1.5 was chosen for the modeling tool. Releasing the building for unrestricted use instead of demolishing it now could save a substantial amount of money compared with the baseline cost estimate because the site telecommunications system, housed in Building 2, would not be disabled and replaced. The information developed in this analysis may be used as part of an as low as reasonably achievable (ALARA) cost/benefit determination regarding disposition of Building 2.

  14. Tools for Closure Project and Contract Management: Development of the Rocky Flats Integrated Closure Project Baseline

    SciTech Connect (OSTI)

    Gelles, C. M.; Sheppard, F. R.

    2002-02-26

    This paper details the development of the Rocky Flats Integrated Closure Project Baseline - an innovative project management effort undertaken to ensure proactive management of the Rocky Flats Closure Contract in support of the Department's goal for achieving the safe closure of the Rocky Flats Environmental Technology Site (RFETS) in December 2006. The accelerated closure of RFETS is one of the most prominent projects within the Department of Energy (DOE) Environmental Management program. As the first major former weapons plant to be remediated and closed, it is a first-of-kind effort requiring the resolution of multiple complex technical and institutional challenges. Most significantly, the closure of RFETS is dependent upon the shipment of all special nuclear material and wastes to other DOE sites. The Department is actively working to strengthen project management across programs, and there is increasing external interest in this progress. The development of the Rocky Flats Integrated Closure Project Baseline represents a groundbreaking and cooperative effort to formalize the management of such a complex project across multiple sites and organizations. It is original in both scope and process, however it provides a useful precedent for the other ongoing project management efforts within the Environmental Management program.

  15. NNSA project receives DOE Secretary's Award for Project Management...

    National Nuclear Security Administration (NNSA)

    receives DOE Secretary's Award for Project Management Improvement Monday, April 13, 2015 - 3:28pm The NNSA Nuclear Materials Safeguards and Security Upgrade Project (NMSSUP) ...

  16. PROJECT MANGEMENT PLAN EXAMPLES Project Management Plan Examples

    Office of Environmental Management (EM)

    Management Plan Examples The following material has been extracted from several project management plans. The order in which it is presented is arbitrary. The elements table below ...

  17. Concrete growth problems and remedial measures at TVA projects

    SciTech Connect (OSTI)

    Hammer, J.J.

    1984-01-01

    Most concrete structures are designed and detailed to provide for a volume decrease without excessive cracking. Occasionally, however, a concrete structure exhibits a long-term increase in volume termed concrete growth. Concrete growth may result from a variety of reactions, such as the hydration of unstable oxides included in the concrete mix, or the oxidation of minerals or from an outside attack of sulfates. The most important reaction creating concrete growth is that between minor alkali hydroxides from cement and the concrete aggregates. Two distinctly different harmful reactions have been recognized: the alkali-silicate and alkali-carbonate reactions. Concrete deteriorating from an alkali-aggregate reaction, regardless of the type, develops an obvious network of cracks called pattern or map cracking. These alkali-aggregate reactions and their accompanying concrete growth have presented numerous problems at TVA's Fontana Dam, Chickamauga Dam and lock, and Hiwassee Dam. Much has been learned about alkali-aggregate reaction since 1940. Most harmful reactions can now be prevented in proposed structures by interpreting the results of standard test methods. It is not possible, however, in existing structures to determine how far the growth phenomenon has progressed, how long the effects will have to be dealt with, or what the future effects will be. A program of close surveillance and monitoring is maintained at these projects, and problems are dealt with as they arise.

  18. [Uranium Mill Tailings Remedial Action Project Office Quality Assurance Program Plan

    SciTech Connect (OSTI)

    Not Available

    1992-06-01

    The Uranium Mill Tailings Remedial Action (UMTRA) Project was established to accomplish remedial actions at inactive uranium mill tailings sites in accordance with Public Law 95-604, the Uranium Mill Tailings Radiation Control Act of 1978 (UMTRCA). The UMTRA Project's mission is to stabilize and control the residual radioactive materials at designated sites in a safe and environmentally sound manner so as to minimize or eliminate radiation health hazards to the public. The US Department of Energy (DOE) UMTRA Project Office (UMTRA PO) directs the overall project. Since these efforts may involve possible risks to public health and safety, a quality assurance (QA) program that conforms to the applicable criteria (set forth in the reference documents) has been established to control the quality of the work. This document, the Quality Assurance Program Plan (QAPP), brings into one document the essential criteria to be applied on a selective basis, depending upon the nature of the activity being conducted, and describes how those criteria shall be applied to the UMTRA Project. The UMTRA PO shall require each Project contractor to prepare and submit for approval a more detailed QAPP that is based on the applicable criteria of this QAPP and the referenced documents. All QAPPs on the UMTRA Project shall fit within the framework of this plan.

  19. CNS Project Management | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    CNS Project Management CNS Project Management CNS Project Management The experience with major nuclear design and construction projects continues to highlight the importance of a focused, technically rigorous, and standardized approach to project reviews performed at Critical Decision (CD) approval points. This approach is fundamental to a positive safety culture and effective nuclear safety management. The CNS led the technical development of Standard Review Plans (SRPs). The SRPs are designed

  20. Tank waste remediation system tank waste retrieval risk management plan

    SciTech Connect (OSTI)

    Klimper, S.C.

    1997-11-07

    This Risk Management Plan defines the approach to be taken to manage programmatic risks in the TWRS Tank Waste Retrieval program. It provides specific instructions applicable to TWR, and is used to supplement the guidance given by the TWRS Risk Management procedure.

  1. Measuring Performance and Benchmarking Project Management

    Energy Savers [EERE]

    implemented. Monthly 4. Project management staffing Is project staffing adequate in terms of number and qualifications? Assessment scale from 1 (poor) to 5 (excellent)....

  2. Fermilab | Directorate | Office of Project Management Oversight...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Resources Project Management References Sample Documents Reference Documents Office of Energy Research - Project Performance E. Temple, Feb 1986 Geographical Information Systems ...

  3. CNS Project Management | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    CNS Project Management The experience with major nuclear design and construction projects continues to highlight the importance of a focused, technically rigorous, and standardized...

  4. Project Management Methodology | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    provides the tools and guidance necessary to ensure consistent and effective management oversight of performer performance and consolidated reporting. The project management...

  5. Report: EMAB Acquisition and Project Management Subcommittee...

    Broader source: Energy.gov (indexed) [DOE]

    and contract management. On November 2, a very comprehensive report (124 pages) outlining continuous improvement actions in acquisition and project management was approved by Dr....

  6. Project Schedules and Milestones Draft July 2014 Site Management Plan Page 1

    Office of Legacy Management (LM)

    Draft July 2014 Site Management Plan Page 1 5.0 Project Schedules and Milestones (FY 2015-FY 2017) 5.1 Establishing Project Schedules and Milestones As stated in Section 1.1.2, the Site Management Plan (SMP) establishes the overall plan for remedial actions at the Monticello Mill Tailings Site (MMTS) and milestones against which progress can be measured. The SMP also documents the overall plan for remedial actions at the Monticello Vicinity Properties site (MVP), which was deleted from the

  7. Project Schedules and Milestones Final August 2013 Site Management Plan Page 1

    Office of Legacy Management (LM)

    Final August 2013 Site Management Plan Page 1 5.0 Project Schedules and Milestones (FY 2014-FY 2016) 5.1 Establishing Project Schedules and Milestones As stated in Section 1.1.2, the Site Management Plan (SMP) establishes the overall plan for remedial actions at the Monticello Mill Tailings Site (MMTS) and milestones against which progress can be measured. The SMP also documents the overall plan for remedial actions at the Monticello Vicinity Properties site (MVP), which was deleted from the

  8. Update on Service Management project

    ScienceCinema (OSTI)

    None

    2011-04-25

    GS and IT Service Management project status meeting -------------------------------------------------------------------------- Distribution: Sigurd Lettow, Frederic Hemmer, Thomas Pettersson, David Foster, Matti Tiirakari, GS⁢ Service Providers When and where: Thursday 2nd September at 10:00-11:30 in IFiltration Plant (222-R-001) Dear All, We would like to inform you about progress made on different topics like the Service Catalogue, the new Service Management Tool and the Service Desk. We would also like to present the plan for when we hope to "go live" and what this will mean for all of you running and providing services today. We will need your active support and help in the coming months to make this happen. GS⁢ Service Management Teams Reinoud Martens, Mats Moller

  9. Project Manager's Guide to Managing Impact and Process Evaluation Studies

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    | Department of Energy Project Manager's Guide to Managing Impact and Process Evaluation Studies Project Manager's Guide to Managing Impact and Process Evaluation Studies This report provides a step-by-step approach to help managers of EERE evaluation projects create and manage objective, high quality, independent, and useful impact and process evaluations. It provides information to help with the following: Determine why, what and when to evaluate; identify the questions that need to be

  10. US Department of Energy Grand Junction Projects Office Remedial Action Project, final report of the decontamination and decommissioning of Building 36 at the Grand Junction Projects Office Facility

    SciTech Connect (OSTI)

    Widdop, M.R.

    1996-08-01

    The U.S. Department of Energy (DOE) Grand Junction Projects Office (GJPO) occupies a 61.7-acre facility along the Gunnison River near Grand Junction, Colorado. This site was contaminated with uranium ore and mill tailings during uranium refining activities of the Manhattan Engineer District and during pilot milling experiments conducted for the U.S. Atomic Energy Commission`s domestic uranium procurement program. The DOE Defense Decontamination and Decommissioning Program established the GJPO Remedial Action Project to clean up and restore the facility lands, improvements, and the underlying aquifer. The site contractor for the facility, Rust Geotech, also is the remedial action contractor. Building 36 was found to be radiologically contaminated and was demolished in 1996. The soil beneath the building was remediated in accordance with identified standards and can be released for unlimited exposure and unrestricted use. This document was prepared in response to a DOE request for an individual final report for each contaminated GJPO building.

  11. Project Management Coordination Office Organization Chart

    Broader source: Energy.gov [DOE]

    Project Management Coordination Office Organization Chart, U.S. Department of Energy's Office of Energy Efficiency and Renewable Energy.

  12. Project Management Policy & Guidance Documents | Department of...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Policy & Guidance Documents Project Management Policy & Guidance Documents << Return to Directives & Documents | Proceed to Publications & Documents >> Document Type Function

  13. Project Management Publications & Documents | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Publications & Documents Project Management Publications & Documents << Return to Directives & Documents | Proceed to Policy & Guidance >> Filter by Source Filter by Topic

  14. Project Management Expectations for Financial Assistance Activities

    Broader source: Energy.gov [DOE]

    Memo on Project Management Expectations for Financial Assistance Activities from David K. Garman, dated June 23, 2006.

  15. NIM Guide for PIs and Project Managers

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    PIs NIM Guide for PIs and Project Managers NERSC Allocations Allocations are made to project accounts called repositories (repos). Every year Principal Investigators or their designated PI Proxies apply for NERSC resources for both existing and new repositories. See the ERCAP Allocation Request Form. The PI or PI Proxy may designate Project Managers who help to administer the project. PIs, PI Proxies and Project Managers can request user additions to and deletions from their repositories using

  16. Finance and supply management project execution plan

    SciTech Connect (OSTI)

    BENNION, S.I.

    1999-02-10

    As a subproject of the HANDI 2000 project, the Finance and Supply Management system is intended to serve FDH and Project Hanford major subcontractor with financial processes including general ledger, project costing, budgeting, and accounts payable, and supply management process including purchasing, inventory and contracts management. Currently these functions are performed with numerous legacy information systems and suboptimized processes.

  17. Spent Nuclear Fuel Project Safety Management Plan

    SciTech Connect (OSTI)

    Garvin, L.J.

    1996-02-01

    The Spent Nuclear Fuel Project Safety Management Plan describes the new nuclear facility regulatory requirements basis for the Spemt Nuclear Fuel (SNF) Project and establishes the plan to achieve compliance with this basis at the new SNF Project facilities.

  18. Systems engineering management and implementation plan for Project W-465, immobilized low-activity waste plan

    SciTech Connect (OSTI)

    Latray, D.A.

    1998-05-15

    The Systems Engineering Management and Implementation Plan (SEMIP) for TWRS Project W-465 describes the project implementation of the Tank Waste Remediation System Systems Engineering Management Plan (TWRS SEMP), Rev. 1. The SEMIP outlines systems engineering (SE) products and processes to be used by the project for technical baseline development. A formal graded approach is used to determine the products necessary for requirements, design, and operational baseline completion. SE management processes are defined, and roles and responsibilities for management processes and major technical baseline elements are documented.

  19. Systems engineering management and implementation plan for Project W-464, immobilized high-level waste storage

    SciTech Connect (OSTI)

    Wecks, M.D.

    1998-04-15

    The Systems Engineering Management and Implementation Plan (SEMIP) for TWRS Project W-46 describes the project implementation of the Tank Waste Remediation System Systems Engineering Management Plan. (TWRS SEMP), Rev. 1. The SEMIP outlines systems engineering (SE) products and processes to be used by the project for technical baseline development. A formal graded approach is used to determine the products necessary for requirements, design, and operational baseline completion. SE management processes are defined, and roles and responsibilities for management processes and major technical baseline elements are documented.

  20. Hanford Site Tank Waste Remediation System. Waste management 1993 symposium papers and viewgraphs

    SciTech Connect (OSTI)

    Not Available

    1993-05-01

    The US Department of Energy`s (DOE) Hanford Site in southeastern Washington State has the most diverse and largest amount of highly radioactive waste of any site in the US. High-level radioactive waste has been stored in large underground tanks since 1944. A Tank Waste Remediation System Program has been established within the DOE to safely manage and immobilize these wastes in anticipation of permanent disposal in a geologic repository. The Hanford Site Tank Waste Remediation System Waste Management 1993 Symposium Papers and Viewgraphs covered the following topics: Hanford Site Tank Waste Remediation System Overview; Tank Waste Retrieval Issues and Options for their Resolution; Tank Waste Pretreatment - Issues, Alternatives and Strategies for Resolution; Low-Level Waste Disposal - Grout Issue and Alternative Waste Form Technology; A Strategy for Resolving High-Priority Hanford Site Radioactive Waste Storage Tank Safety Issues; Tank Waste Chemistry - A New Understanding of Waste Aging; Recent Results from Characterization of Ferrocyanide Wastes at the Hanford Site; Resolving the Safety Issue for Radioactive Waste Tanks with High Organic Content; Technology to Support Hanford Site Tank Waste Remediation System Objectives.

  1. 2012 Department of Energy Project Management Workshop | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    2 Department of Energy Project Management Workshop 2012 Department of Energy Project Management Workshop 2012 Department of Energy Project Management Workshop ***...

  2. Program & Project Management For The Acquisition Of Capital Assets...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Program & Project Management For The Acquisition Of Capital Assets Program & Project Management For The Acquisition Of Capital Assets 2014 DOE Project Management Workshop ...

  3. Best-In-Class Project Management Initiative Corporate Implementation...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Best-In-Class Project Management Initiative Corporate Implementation Plan Best-In-Class Project Management Initiative Corporate Implementation Plan To continue Project Management ...

  4. Remedial design/remedial action strategy report

    SciTech Connect (OSTI)

    Dieffenbacher, R.G.

    1994-06-30

    This draft Regulatory Compliance Strategy (RCS) report will aid the ER program in developing and implementing Remedial Design/Remedial Action (RD/RA) projects. The intent of the RCS is to provide guidance for the implementation of project management requirements and to allow the implementation of a flexible, graded approach to design requirements depending on the complexity, magnitude, schedule, risk, and cost for any project. The RCS provides a functional management-level guidance document for the identification, classification, and implementation of the managerial and regulatory aspects of an ER project. The RCS has been written from the perspective of the ER Design Manager and provides guidance for the overall management of design processes and elements. The RCS does not address the project engineering or specification level of detail. Topics such as project initiation, funding, or construction are presented only in the context in which these items are important as sources of information or necessary process elements that relate to the design project phases.

  5. Jefferson Lab Project Management & Integrated Planning

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    LERF Contact Our Staff Directorate Project Control System Manual Technical Engineering Development Facility (TEDF) Utilities Infrastructure Modernization (UIM) Office of Project Management Org Chart Project Management Office Vision: Partnering with our customers, we provide support to further the laboratory's mission to operate a world class user facility for conducting nuclear physics research. Our focus is to provide project management and integrated planning support across the Lab that is

  6. Project Management Update - Paul Bosco, Director, Office of Acquisitio...

    Office of Environmental Management (EM)

    Update - Paul Bosco, Director, Office of Acquisition & Project Mgt Project Management Update - Paul Bosco, Director, Office of Acquisition & Project Mgt 2014 DOE Project Management ...

  7. Economic impact study of the Uranium Mill Tailings Remedial Action project in Colorado: Colorado state fiscal year 1995

    SciTech Connect (OSTI)

    1995-12-01

    This Colorado economic impact study summarizes employment and economic benefits to the state from activities associated with the Uranium Mill Tailings Remedial Action (UMTRA) Project during Colorado state fiscal year (FY) 1995 (1 July 1994 through 30 June 1995). To capture employment information, a questionnaire was distributed to subcontractor employees at the active UMTRA Project sites of Grand Junction, Gunnison, Maybell, Naturita, Rifle, and Slick Rock, Colorado. Economic data were requested from the Remedial Action Contractor (RAC), the Technical Assistance Contractor (TAC) and the US Department of Energy (DOE). The most significant benefits associated with the UMTRA Project in Colorado are summarized.

  8. Contents of environmental assessments prepared for the Uranium Mill Tailings Remedial Action Project

    SciTech Connect (OSTI)

    Not Available

    1986-01-01

    This document presents two versions of the outline for the environmental assessments (EAS) to be prepared for the Uranium Mill Tailings Remedial Action (UMTRA) Project. The first displays the basic structure of the assessments; it lists only the titles of sections. The second is a guide to the contents of the assessments which provides, under each title, a brief summary of contents. The outline is intended to comply with the planning requirements (40 CFR Part 1501) and the definitions of terms (40-' CFR Part 1508) established by the Council on Environmental Quality as well as DOE order 5440.lB (Implementation of the National Environmental Policy Act), and compliance with Floodplain/Wetlands Environmental Review Requirements (10 CFR Part 1022). These requirements and definitions are implicitly part of the outline. The outline presented in this document will guide the preparation of EAs. The UMTRA Project EAs will be used in determining whether the DOE should prepare an environmental impact statement or a finding of no significant impact for the actions at each of the sites. If no impact statement is necessary, the environmental assessment for that site will aid the DOE in complying with the National Environmental Policy Act before beginning remedial actions. If an impact statement is needed, the assessment will aid its preparation. These purposes, established by the Council on Environmental Quality in 40 CFR Part 1508.9(a), have guided the construction of the outline presented in this document. Remedial actions at each site will include the cleanup of properties in the vicinity of the tailings sites that have been contaminated by the tailings.

  9. Contents of environmental assessments prepared for the Uranium Mill Tailings Remedial Action Project

    SciTech Connect (OSTI)

    Not Available

    1986-01-01

    This document presents two versions of the outline for the environmental assessments (EAS) to be prepared for the Uranium Mill Tailings Remedial Action (UMTRA) Project. The first displays the basic structure of the assessments; it lists only the titles of sections. The second is a guide to the contents of the assessments which provides, under each title, a brief summary of contents. The outline is intended to comply with the planning requirements (40 CFR Part 1501) and the definitions of terms (40-` CFR Part 1508) established by the Council on Environmental Quality as well as DOE order 5440.lB (Implementation of the National Environmental Policy Act), and compliance with Floodplain/Wetlands Environmental Review Requirements (10 CFR Part 1022). These requirements and definitions are implicitly part of the outline. The outline presented in this document will guide the preparation of EAs. The UMTRA Project EAs will be used in determining whether the DOE should prepare an environmental impact statement or a finding of no significant impact for the actions at each of the sites. If no impact statement is necessary, the environmental assessment for that site will aid the DOE in complying with the National Environmental Policy Act before beginning remedial actions. If an impact statement is needed, the assessment will aid its preparation. These purposes, established by the Council on Environmental Quality in 40 CFR Part 1508.9(a), have guided the construction of the outline presented in this document. Remedial actions at each site will include the cleanup of properties in the vicinity of the tailings sites that have been contaminated by the tailings.

  10. Project Management Career Development Program

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Management Career Development Program Certified Federal Project Directors * Program Secretarial Office Name Certification Level Certified FPD Since EA LOW,JAMES O Level I 10/14/2009 EE BUMBACA,PRISCILLA B Level I 01/25/2011 EE COLLETTE,GREGORY D Level II 04/28/2006 EE DINS,RANDALL S Level II 02/13/2009 EE GRAHAM,MATT E Level III 04/28/2006 EE SWEENEY,ROBIN L Level I 11/21/2008 EM ABDUL,WAHED NMN Level III 12/08/2006 EM ADAMS,KAREN M Level I 07/31/2009 EM ADAMS,VINCENT NMN Level III 12/08/2006

  11. Project management plan for Project W-320, Tank 241-C-106 sluicing. Revision 2

    SciTech Connect (OSTI)

    Phillips, D.R.

    1994-07-01

    A major mission of the US Department of Energy (DOE) is the permanent disposal of Hanford Site defense wastes by utilizing safe, environmentally acceptable, and cost-effective disposal methods that meet applicable regulations. The Tank Waste Remediation System (TWRS) Program was established at the Hanford Site to manage and control activities specific to the remediation of safety watch list tanks, including high-heat-producing tanks, and for the ultimate characterization, retrieval, pretreatment, and disposal of the low- and high-level fractions of the tank waste. Project W-320, Tank 241-C-106 Sluicing, provides the methodology, equipment, utilities, and facilities necessary for retrieving the high-heat waste from single-shell tank (SST) 24-C-106. Project W-320 is a fiscal year (FY) 1993 expense-funded major project, and has a design life of 2 years. Retrieval of the waste in tank 241-C-106 will be accomplished through mobilization of the sludge into a pumpable slurry using past-practice sluicing. The waste is then transferred directly to a double-shell tank for interim storage, subsequent pretreatment, and eventual disposal. A detailed description of the management organization and responsibilities of all participants is presented in this document.

  12. Soil Management Plan For The Potable Water System Upgrades Project

    SciTech Connect (OSTI)

    Field, S. M.

    2007-04-01

    This plan describes and applies to the handling and management of soils excavated in support of the Y-12 Potable Water Systems Upgrades (PWSU) Project. The plan is specific to the PWSU Project and is intended as a working document that provides guidance consistent with the 'Soil Management Plan for the Oak Ridge Y-12 National Security Complex' (Y/SUB/92-28B99923C-Y05) and the 'Record of Decision for Phase II Interim Remedial Actions for Contaminated Soils and Scrapyard in Upper East Fork Popular Creek, Oak Ridge, Tennessee' (DOE/OR/01-2229&D2). The purpose of this plan is to prevent and/or limit the spread of contamination when moving soil within the Y-12 complex. The major feature of the soil management plan is the decision tree. The intent of the decision tree is to provide step-by-step guidance for the handling and management of soil from excavation of soil through final disposition. The decision tree provides a framework of decisions and actions to facilitate Y-12 or subcontractor decisions on the reuse of excavated soil on site and whether excavated soil can be reused on site or managed as waste. Soil characterization results from soil sampling in support of the project are also presented.

  13. acquisition and project management | National Nuclear Security

    National Nuclear Security Administration (NNSA)

    Administration and project management Acquisition and Project Management Office volunteers get up-close look at Office of Secure Transportation exercise Contracting professionals from the NNSA Acquisition & Project Management (APM) Field Program Section (FPS) recently served as role players for Office of Secure Transportation (OST) training exercises in Arkansas and Oklahoma. OST Federal Agents transport U.S. nuclear weapons, components and... SNL Starting Points Sandia Field Office Home

  14. Improving the Department's Management of Projects | Department...

    Office of Environmental Management (EM)

    DOE is managing some of the largest, most complex, and technically challenging projects in the public or private sector. Many are one-of-a-kind projects that involve the risks and ...

  15. Fernald Environmental Management Project Director's Final Findings...

    Office of Environmental Management (EM)

    644-2329 December 27. 1994 Re: U.S. Department of Energy Fernald Environmental Management Project Attn: Jack Craig, Acting Site Manager P.O. Box 389705 Cincinnati, Ohio 45239 ...

  16. 4.1 PROJECT MANAGER ROLE

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    4-1 4.0 AGREEMENT MANAGEMENT 4.1 PROJECT MANAGER ROLE The DOE and the lead regulatory agency(ies) (see Section 5.6 for discussion of lead regulatory agency) shall each designate an ...

  17. 2016 DOE Project Management Workshop – Agenda

    Broader source: Energy.gov [DOE]

    Agenda for Day 1 (Tuesday, March 22) and Day 2 (Wednesday, March 23, 2016) of the 2016 DOE Project Management Workshop.

  18. Acquisition and Project Management Awards Presentations - Ingrid...

    Broader source: Energy.gov (indexed) [DOE]

    Secretary's Achievement Award Seismic Life-Safety, Modernization & Replacement (Seismic Ph 2)Secretary's Award for Project Management Improvement Nuclear Materials Safeguards & ...

  19. Improving Project Management | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    Secretary of Energy Ernest Moniz has made improving project management a priority at the Energy Department. In August 2013, the Secretary established a special working group that...

  20. 2016 DOE Project Management Workshop - Transportation | Department...

    Office of Environmental Management (EM)

    Transportation 2016 DOE Project Management Workshop - Transportation Complimentary guest shuttle service provided by Sheraton Pentagon City Hotel. PDF icon Shuttle service Key ...

  1. 2016 DOE Project Management Workshop - Biographies | Department...

    Office of Environmental Management (EM)

    Biographies 2016 DOE Project Management Workshop - Biographies Biographies for this year's workshop are not yet available. Please check back later. PDF icon Biographies Key ...

  2. 2016 DOE Project Management Workshop - Presentations | Department...

    Energy Savers [EERE]

    Presentations 2016 DOE Project Management Workshop - Presentations The presentations for this year's workshop are not yet available. Please check back later. PDF icon Presentations ...

  3. Fernald Environmental Management Project Director's Final Findings...

    Office of Environmental Management (EM)

    Phil Hammric U.S. Department of Energy Femald Environmental Management Project P.O. Box 389705 Cincinnati, Ohio 45239 Mr. John Bradbume Femald Environmental Restoration Corporation ...

  4. Fermilab | Directorate | Office of Project Management Oversight...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Policies and Procedures Fermi Project Management EVMS PolicyProcedures EVMS Certified System Documents OPSS Guidance Description Desktop Instructions Policy FRA Earned Value ...

  5. Designation of Environmental Management Federal Project Director...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Environmental Management Federal Project Director for Brookhaven National Laboratory by sattler DesignationofEMFedProjDir-BNL-SattlerEM.pdf -- PDF Document, 240 KB ID: NA Type:...

  6. Designation of Environmental Management Federal Project Director...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Environmental Management Federal Project Director for Separations Process Research Unit by feinberg DesignationofEMFedProjDir-SeparationsProcessResearchUnit-FeinbergEM.pdf -- PDF...

  7. 2014 DOE Project Management Workshop Presentations | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    1. PM Update - Paul Bosco, Director, Office of Acquisition & Project Management 2. Ethics - Marianne Jennings, W.P. Carey School of Business at Arizona State University 3. ...

  8. Year 2000 challenge: A project management perspective

    SciTech Connect (OSTI)

    Johnston, B.

    1997-11-01

    This report contains viewgraphs which discusses the challenge to correct software when the year 2000 occurs. Project management goals are discussed.

  9. Final audit report of remedial action construction at the UMTRA Project, Grand Junction, Colorado, processing site

    SciTech Connect (OSTI)

    1995-02-01

    This final audit report (FAR) for remedial action at the Grand Junction, Colorado, Uranium Mill Tailings Remedial Action (UMTRA) Project processing site consists of a summary of the radiological surveillances/ audits, the quality assurance (QA) in-process surveillances, and the QA final close-out inspection performed by the US Department of Energy (DOE) and Technical Assistance Contractor (TAC). The FAR also summarizes other surveillances performed by the US Nuclear Regulatory Commission (NRC). To summarize, a total of one finding and 127 observations were noted during DOE/TAC audit and surveillance activities. The NRC noted general site-related observations during the OSCRs. Follow-up to responses required from MK-Ferguson for the DOE/TAC finding and observations indicated that all issues related to the Grand Junction processing site were resolved and closed out to the DOE`s satisfaction. The NRC OSCRs resulted in no issues related to the Grand Junction processing site requiring a response from MK-Ferguson.

  10. Systems approach to project risk management

    SciTech Connect (OSTI)

    Kindinger, J. P.

    2002-01-01

    This paper describes the need for better performance in the planning and execution of projects and examines the capabilities of two different project risk analysis methods for improving project performance. A quantitative approach based on concepts and tools adopted from the disciplines of systems analysis, probabilistic risk analysis, and other fields is advocated for managing risk in large and complex research & development projects. This paper also provides an overview of how this system analysis approach for project risk management is being used at Los Alamos National Laboratory along with examples of quantitative risk analysis results and their application to improve project performance.

  11. Review and analysis of proposed EPA groundwater standards for the UMTRA Project. [Uranium Mill Tailings Remedial Action (UMTRA) Project

    SciTech Connect (OSTI)

    Not Available

    1987-10-01

    The Title I groundwater standards for inactive uranium mill tailings sites, which were promulgated on January 5, 1983, by the US Environmental Protection Agency (EPA) for the Uranium Mill Tailings Remedial Action (UMTRA) Project, were remanded to the EPA on September 3, 1985, by the US Tenth Circuit Court of Appeals. The Court instructed the EPA to compile general groundwater standards for all sites. On September 24, 1987, the EPA published proposed standards in response to the remand. This Summary Report includes an evaluation of the potential effects of the proposed EPA groundwater standards on the UMTRA Project as well as a discussion of the DOE's position on the proposed standards. This report is accompanied by a detailed Technical Report and Appendices which provide supporting information and analyses. This Summary Report results from a study undertaken to: determine the impact of the proposed standards on the UMTRA Project; and recommend provisions for the implementation of the final standards that will minimize adverse impact to the conduct of the UMTRA Project while ensuring protection of human health and the environment. Specifically, the following were considered: the flexibility of the proposed standards; interpretations of the proposed standards; the extent of aquifer restoration that may be required to implement the proposed standards at each site; the costs of aquifer restoration; and design changes necessary to meet the standards.

  12. Tank waste remediation system year 2000 dedicated file server project HNF-3418 project plan

    SciTech Connect (OSTI)

    SPENCER, S.G.

    1999-04-26

    The Server Project is to ensure that all TWRS supporting hardware (fileservers and workstations) will not cause a system failure because of the BIOS or Operating Systems cannot process Year 2000 dates.

  13. Fluor Hanford, Inc. Groundwater and Technical Integration Support (Master Project) Quality Assurance Management Plan

    SciTech Connect (OSTI)

    Fix, N. J.

    2008-02-20

    The scope of the Fluor Hanford, Inc. Groundwater and Technical Integration Support (Master Project) is to provide technical and integration support to Fluor Hanford, Inc., including operable unit investigations at 300-FF-5 and other groundwater operable units, strategic integration, technical integration and assessments, remediation decision support, and science and technology. This Quality Assurance Management Plan provides the quality assurance requirements and processes that will be followed by the Fluor Hanford, Inc. Groundwater and Technical Integration Support (Master Project).

  14. Operable Unit 3-13, Group 3, Other Surface Soils Remediation Sets 4-6 (Phase II) Waste Management Plan

    SciTech Connect (OSTI)

    G. L. Schwendiman

    2006-07-01

    This Waste Management Plan describes waste management and waste minimization activities for Group 3, Other Surface Soils Remediation Sets 4-6 (Phase II) at the Idaho Nuclear Technology and Engineering Center located within the Idaho National Laboratory. The waste management activities described in this plan support the selected response action presented in the Final Record of Decision for Idaho Nuclear Technology and Engineering Center, Operable Unit 3-13. This plan identifies the waste streams that will be generated during implementation of the remedial action and presents plans for waste minimization, waste management strategies, and waste disposition.

  15. 2015 DOE Acquisition and Project Management (APM) Workshop |...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    5 DOE Acquisition and Project Management (APM) Workshop 2015 DOE Acquisition and Project Management (APM) Workshop Workshop Details: What: 2015 DOE Acquisition and Project...

  16. 2012 Awards for Project Management | Department of Energy

    Energy Savers [EERE]

    2 Awards for Project Management 2012 Awards for Project Management Federal Project Director of the Year for 2012 Mr. Hannibal Joma The 2012 Secretary Achievement Award The Office...

  17. 2013 Awards for Project Management | Department of Energy

    Energy Savers [EERE]

    3 Awards for Project Management 2013 Awards for Project Management Federal Project Director of the Year for 2013: Everett Trollinger (National Nuclear Security Administration)...

  18. Staffing Guide for Project Management - DOE Directives, Delegations...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    19 Admin Chg 1, Staffing Guide for Project Management by Brian Kong Functional areas: Administrative Change, Program Management, Project Management This Guide provides an approach...

  19. Protocol_for_Environmental_Management_Cleanup_Projects_(clean...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ProtocolforEnvironmentalManagementCleanupProjects(clean).pdf ProtocolforEnvironmentalManagementCleanupProjects(clean).pdf PDF icon ProtocolforEnvironmentalManagement...

  20. 2016 DOE Project Management Workshop | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    to project management, the Project Management Risk Committee, congressional views, ethics, and program perspectives from Environmental Management, Science, and the National...

  1. Spent Nuclear Fuel Project Configuration Management Plan

    SciTech Connect (OSTI)

    Reilly, M.A.

    1995-06-09

    This document is a rewrite of the draft ``C`` that was agreed to ``in principle`` by SNF Project level 2 managers on EDT 609835, dated March 1995 (not released). The implementation process philosphy was changed in keeping with the ongoing reengineering of the WHC Controlled Manuals to achieve configuration management within the SNF Project.

  2. US Department of Energy Grand Junction Projects Office Remedial Action Project. Final report of the decontamination and decommissioning of Building 52 at the Grand Junction Projects Office Facility

    SciTech Connect (OSTI)

    Krabacher, J.E.

    1996-08-01

    The U.S. Department of Energy (DOE) Grand Junction Projects Office (GJPO) occupies a 61.7-acre facility along the Gunnison River near Grand Junction, Colorado. This site was contaminated with uranium ore and mill tailings during uranium refining activities of the Manhattan Engineer District and during pilot milling experiments conducted for the U.S. Atomic Energy Commission`s domestic uranium procurement program. The DOE Defense Decontamination and Decommissioning Program established the GJPO Remedial Action Project to clean up and restore the facility lands, improvements, and the underlying aquifer. The site contractor for the facility, Rust Geotech, also was the remedial action contractor. Building 52 was found to be radiologically contaminated and was demolished in 1994. The soil area within the footprint of the building has been remediated in accordance with the identified standards and the area can be released for unlimited exposure and unrestricted use. This document was prepared in response to a DOE request for an individual final report for each contaminated GJPO building.

  3. Managing Legacy Records for Formerly Utilized Sites. Remedial Action Program Sites

    SciTech Connect (OSTI)

    Clayton, C.; Gueretta, J.; Tack, J.; Widdop, M.

    2008-07-01

    The Manhattan Engineer District (MED) and U.S. Atomic Energy Commission (AEC) contracted for support work through private and academic parties through the early 1960's. The work often involved radioactive materials. Residual radioactive contamination was left at some of more than 600 potentially contaminated (candidate) sites, and worker health and safety concerns remain from the site operations and subsequent remediation activities. The U.S. Department of Energy (DOE) initiated a program to identify and protect records of MED/AEC activities and of remediation work conducted under the Formerly Utilized Sites Remedial Action Program (FUSRAP) to aid in resolving questions about site conditions, liability, and worker health and safety and to ensure ongoing protectiveness of human health and the environment. This paper discusses DOE activities undertaken to locate records collections, confirm retention schedules and access requirements, and document information about the collections for use by future stewards. In conclusion: DOE-LM recognizes that records and information management is a critical component of effective LTS and M. Records are needed to answer questions about site conditions and demonstrate to the public in the future that the sites are safe. DOE-LM is working to satisfy present needs and anticipate future uses for FUSRAP records, and compile a collection of site and program information from which future stewards can readily locate and retrieve needed information. (authors)

  4. Interstate Technology & Regulatory Council (ITRC) Remediation...

    Office of Environmental Management (EM)

    Interstate Technology & Regulatory Council (ITRC) Remediation Management of Complex Sites: Case Studies and Guidance Interstate Technology & Regulatory Council (ITRC) Remediation ...

  5. Project Management Career Development Program | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Operational Management » Certifications and Professional Development » Project Management Career Development Program Project Management Career Development Program All PMCDP-related information has been moved to Powerpedia - Project Management Career Development Program.

  6. project management | National Nuclear Security Administration

    National Nuclear Security Administration (NNSA)

    project management NNSA projects win Secretary's Achievement Awards for cost savings and efficiency NNSA was presented with two Department of Energy Secretary's Achievement Awards at a ceremony in Arlington, Va., on Wednesday. The awards, presented by Deputy Secretary of Energy Elizabeth Sherwood-Randall, commend NNSA on delivering the Y-12 Nuclear Facility Risk Reduction Project $5.7... NNSA's G2 Management Information System Wins Association for Enterprise Information's (AFEI) "Excellence

  7. Economic impact study of the Uranium Mill Tailings Remedial Action project in Colorado: Colorado state fiscal year 1995. Revision 1

    SciTech Connect (OSTI)

    1995-12-01

    As required by the Romer-Twining Agreement of 1990, the US Department of Energy (DOE) has prepared this annual economic impact study for the state of Colorado. This report assesses the economic impacts related to the DOE Uranium Mill Tailings Remedial Action (UMTRA) Project in Colorado during the state fiscal year (FY) between 1 July 1994 and 30 June 1995. To estimate net economic benefit, employment, salaries and wages, and other related economic benefits are discussed, quantified, and then compared to the state`s 10 percent share of the remedial action costs. Actual data obtained from sites currently undergoing remedial action were used as the basis for analyses. If data were not available, estimates were used to derive economic indicators. This study describes the types of employment associated with the UMTRA Project and estimates of the numbers of people employed by UMTRA Project subcontractors in Colorado during state FY 1995. Employment totals are reported in estimated average annual jobs; however, the actual number of workers at the site fluctuates depending on weather and on the status of remedial action activities. In addition, the actual number of people employed on the Project during the year may be higher than the average annual employment reported due to the temporary nature of some of the jobs.

  8. DOE responses to Ecology review comments for ``Sampling and analysis plans for the 100-D Ponds voluntary remediation project``

    SciTech Connect (OSTI)

    NONE

    1996-12-31

    The Sampling and Analysis Plan describes the sampling and analytical activities which will be performed to support closure of the 100-D Ponds at the Hanford Reservation. This report contains responses by the US Department of Energy to Ecology review for ``Sampling and Analysis Plan for the 100-D Ponds Voluntary Remediation Project.``

  9. Status Report for Remediation Decision Support Project, Task 1, Activity 1.B Physical and Hydraulic Properties Database and Interpretation

    SciTech Connect (OSTI)

    Rockhold, Mark L.

    2008-09-26

    The objective of Activity 1.B of the Remediation Decision Support (RDS) Project is to compile all available physical and hydraulic property data for sediments from the Hanford Site, to port these data into the Hanford Environmental Information System (HEIS), and to make the data web-accessible to anyone on the Hanford Local Area Network via the so-called Virtual Library. In past years efforts were made by RDS project staff to compile all available physical and hydraulic property data for Hanford sediments and to transfer these data into SoilVision{reg_sign}, a commercial geotechnical software package designed for storing, analyzing, and manipulating soils data. Although SoilVision{reg_sign} has proven to be useful, its access and use restrictions have been recognized as a limitation to the effective use of the physical and hydraulic property databases by the broader group of potential users involved in Hanford waste site issues. In order to make these data more widely available and useable, a decision was made to port them to HEIS and to make them web-accessible via a Virtual Library module. In FY08 the objectives of Activity 1.B of the RDS Project were to: (1) ensure traceability and defensibility of all physical and hydraulic property data currently residing in the SoilVision{reg_sign} database maintained by PNNL, (2) transfer the physical and hydraulic property data from the Microsoft Access database files used by SoilVision{reg_sign} into HEIS, which has most recently been maintained by Fluor-Hanford, Inc., (3) develop a Virtual Library module for accessing these data from HEIS, and (4) write a User's Manual for the Virtual Library module. The development of the Virtual Library module was to be performed by a third party under subcontract to Fluor. The intent of these activities is to make the available physical and hydraulic property data more readily accessible and useable by technical staff and operable unit managers involved in waste site assessments and

  10. Nuclear facility decommissioning and site remedial actions

    SciTech Connect (OSTI)

    Knox, N.P.; Webb, J.R.; Ferguson, S.D.; Goins, L.F.; Owen, P.T.

    1990-09-01

    The 394 abstracted references on environmental restoration, nuclear facility decommissioning, uranium mill tailings management, and site remedial actions constitute the eleventh in a series of reports prepared annually for the US Department of Energy's Remedial Action Programs. Citations to foreign and domestic literature of all types -- technical reports, progress reports, journal articles, symposia proceedings, theses, books, patents, legislation, and research project descriptions -- have been included. The bibliography contains scientific, technical, economic, regulatory, and legal information pertinent to the US Department of Energy's Remedial Action Programs. Major sections are (1) Surplus Facilities Management Program, (2) Nuclear Facilities Decommissioning, (3) Formerly Utilized Sites Remedial Action Programs, (4) Facilities Contaminated with Naturally Occurring Radionuclides, (5) Uranium Mill Tailings Remedial Action Program, (6) Grand Junction Remedial Action Program, (7) Uranium Mill Tailings Management, (8) Technical Measurements Center, (9) Remedial Action Program, and (10) Environmental Restoration Program. Within these categories, references are arranged alphabetically by first author. Those references having no individual author are listed by corporate affiliation or by publication title. Indexes are provided for author, corporate affiliation, title word, publication description, geographic location, subject category, and keywords. This report is a product of the Remedial Action Program Information Center (RAPIC), which selects and analyzes information on remedial actions and relevant radioactive waste management technologies.

  11. Breckinridge Project, initial effort. Report VI. Project Management Plan

    SciTech Connect (OSTI)

    1982-01-01

    Report VI presents a comprehensive plan for the management of the Breckinridge Project. For the purpose of this report, the project work is divided into five major project phases: Development, Engineering, Procurement, Construction, and Operations. The results of the Development Phase (Initial Effort) of the project are discussed in Section 1.0. This phase of the project was performed under a Cooperative Agreement with US Department of Energy and has produced 43 volumes of documentation. Fifteen volumes contain information of proprietary nature for patented processes and are therefore classified as Limited Access; however, twenty-eight volumes are not classified and are suitable for public dissemination. This Project Management Plan is a volume of the unclassified documentation. The other twenty-seven volumes contain comprehensive data on technical, financial, and environmental aspects of the project. Each of the four remaining project phases is presented starting with the extensive planning that will be performed and continuing through to the execution and completion of each phase. The major roles of the Operator, Ashland Synthetic Fuels, Inc. (ASFI), and the Managing Contractor are defined. Although a contract has not yet been executed with a Managing Contractor, the procedures, controls, organization and management philosophy of Bechtel Petroleum, Inc., are presented in this report as being representative of those used by contractors in the business of performing the engineering, procurement, and construction of projects of this size and complexity. The organizational structures of the Operator and the Managing Contractor are described, with designation of key project team personnel by job description and organization charts. Provisions for cost, schedule, and material control are described.

  12. Tucson Solar Village: Project management

    SciTech Connect (OSTI)

    Not Available

    1991-11-01

    The Tucson Solar Village is a Design/Build Project In Sustainable Community Development which responds to a broad spectrum of energy, environmental, and economic challenges. This project is designed for 820 acres of undeveloped State Trust Land within the Tucson city limits; residential population will be five to six thousand persons with internal employment provided for 1200. This is a 15 year project (for complete buildout and sales) with an estimated cost of $500 million. Details of the project are addressed with emphasis on the process and comments on its transferability.

  13. Secretary's 2014 Award for Project Management Improvement | Department of

    Office of Environmental Management (EM)

    Energy for Project Management Improvement Secretary's 2014 Award for Project Management Improvement Nuclear Materials Safeguards & Security Upgrades (NMSSUP) Project (The National Nuclear Security Administration) (855.47 KB) More Documents & Publications 2014 Awards for Project Management Secretary's 2014 Achievement Awards Acquisition and Project Management Awards Presentations - Ingrid Kolb, Director, Office of Management

  14. Staffing Guide for Project Management

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2010-06-03

    This Guide provides an approach to determining the appropriate level and type of federal personnel needed to effectively plan, direct, and oversee project execution. Admin Chg 1, dated 10-12-11, cancels DOE G 413.3-19.

  15. Economic impact study of the Uranium Mill Tailings Remedial Action Project in Colorado: Colorado state fiscal year 1994

    SciTech Connect (OSTI)

    Not Available

    1994-11-01

    The Colorado economic impact study summarizes employment and economic benefits to the state from activities associated with the Uranium Mill Tailings Remedial Action (UMTRA) Project during Colorado state fiscal year 1994. To capture employment information, a questionnaire was distributed to subcontractor employees at the active UMTRA Project sites of Grand Junction, Naturita, Gunnison, and Rifle, Colorado. Economic data were requested from each site prime subcontractor, as well as from the Remedial Action Contractor. The most significant benefits associated with the UMTRA Project in Colorado are summarized. This study assesses benefits associated with the Grand Junction, Gunnison, Naturita, and Rifle UMTRA Projects sites for the 1-year period under study. Work at the Naturita site was initiated in April 1994 and involved demolition of buildings at the processing site. Actual start-up of remediation of Naturita is planned to begin in the spring of 1995. Work at the Slick Rock and Maybell sites is expected to begin in 1995. The only current economic benefits associated with these sites are related to UMTRA Project support work.

  16. Project Management Plan Examples 1- 80

    Office of Energy Efficiency and Renewable Energy (EERE)

    The following material has been extracted from several project management plans. The order in which it is presented is arbitrary. The descriptions below should be used to navigate to the subject of...

  17. U.S. DEPARTMENT OF ENERGYCONTRACT AND PROJECT MANAGEMENT | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    U.S. DEPARTMENT OF ENERGYCONTRACT AND PROJECT MANAGEMENT U.S. DEPARTMENT OF ENERGYCONTRACT AND PROJECT MANAGEMENT U.S. DEPARTMENT OF ENERGY CONTRACT AND PROJECT MANAGEMENT PDF icon...

  18. Final Hazard Categorization for the Remediation of the 116-C-3 Chemical Waste Tanks

    SciTech Connect (OSTI)

    T. M. Blakley; W. D. Schofield

    2007-09-10

    This final hazard categorization (FHC) document examines the hazards, identifies appropriate controls to manage the hazards, and documents the commitments for the 116-C-3 Chemical Waste Tanks Remediation Project. The remediation activities analyzed in this FHC are based on recommended treatment and disposal alternatives described in the Engineering Evaluation for the Remediation to the 116-C-3 Chemical Waste Tanks (BHI 2005e).

  19. Waste management project technical baseline description

    SciTech Connect (OSTI)

    Sederburg, J.P.

    1997-08-13

    A systems engineering approach has been taken to describe the technical baseline under which the Waste Management Project is currently operating. The document contains a mission analysis, function analysis, requirement analysis, interface definitions, alternative analysis, system definition, documentation requirements, implementation definitions, and discussion of uncertainties facing the Project.

  20. Office of Project Management Oversight & Assessments | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Office of Project Management Oversight & Assessments 2015 Project Management Award Winners 2015 Project Management Award Winners The annual DOE Project Management Workshop provides an opportunity to recognize and reward excellence in project management across the complex. This Year, the Department recognized eight (8) individual and team successes in project management. Award presentations were made by Elizabeth Sherwood-Randall, Deputy Secretary of Energy. Read more FPD Resource Center FPD

  1. Spent Nuclear Fuel Project Document Management Plan

    SciTech Connect (OSTI)

    Connor, M.D.; Harizison, G.L.; Rice, W.C.

    1995-12-01

    The SNF Project Document Management Plan identifies and describes the currently available systems and processes for implementing and maintaining an effective document control and records management program. This program governs the methods by which documents are generated, released, distributed, maintained current, retired, and ultimately disposed.

  2. Staffing Guide for Project Management

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2010-06-03

    This Guide provides an approach to determining the appropriate level and type of federal personnel needed to effectively plan, direct, and oversee project execution. Admin Chg 1, dated 10-12-11, cancels DOE G 413.3-19. Admin Chg 2 dated 10-22-2015.

  3. Alternatives for management of wastes generated by the formerly utilized sites remedial action program and supplement

    SciTech Connect (OSTI)

    Gilbert, T.L.; Peterson, J.M.; Vocke, R.W.; Alexander, J.K.

    1983-03-01

    Alternatives for disposal or stabilization of the wastes generated by the US Department of Energy's Formerly Utilized Sites Remedial Action Program (FUSRAP) are identified and compared, with emphasis on the long-term aspects. These wastes consist of soil material and rubble containing trace amounts of radionuclides. A detailed pathway analysis for the dose to the maximally exposed individual is carried out using an adaptation of the natural analogue method. Comparisons of the different alternatives, based on the results of the pathway analysis and qualitative cost considerations, indicate that, if the hazard is such that the wastes must be removed and disposed of rather than stabilized in place, disposal by immediate dispersal is preferable to containment, and containment followed by slow planned dispersal is preferable to containment without dispersal. The Supplement presents refinements of work that was reported at the 1982 International Decommissioning Symposium. The new material consists of revisions of the estimates of the predicted potential dose to the maximally exposed individual and a more detailed comparative assessment of the radiological impacts of alternatives for management of wastes generated by the US Department of Energy's Formerly Utilized Sites Remedial Action Program (FUSRAP).

  4. Data base management activities for the Remedial Action Program at Oak Ridge National Laboratories (ORNL)

    SciTech Connect (OSTI)

    Hook, L.A.; Voorhees, L.D.; Gentry, M.J.; Faulkner, M.A.; Shaakir-Ali, J.A.; Newman, K.A.; McCord, R.A.; Goins, L.F.; Owen, P.T.

    1990-07-01

    The Oak Ridge National Laboratory (ORNL) Remedial Action Program (RAP) was established in 1985 in response to state and federal regulations requiring comprehensive control over facility discharges and cleanup of contaminated sites. A computerized Data and Information Management System (DIMS) was developed for RAP to (1) provide a centralized repository for data pertinent to RAP and (2) provide support for the investigations and assessments leading to the long-term remediation of contaminated facilities and sites. The current status of DIMS and its role in supporting RAP during 1989 are described. The DIMS consists of three components: (1) the Numeric Data Base, (2) the Bibliographic Data Base, and (3) the Records Control Data Base. This report addresses all three data bases, but focuses on the contents of the Numeric Data Base. Significant progress was made last year with the geographic information system (GIS) and ARC/INFO, which can be interfaced with SAS/GRAPH to provide combined mapping and statistical graphic products. Several thematic layers of GIS data for the Oak Ridge Reservation are now available. 18 refs., 8 figs., 19 tabs.

  5. FY 2016 Overall Contract and Project Management Improvement Performanc...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    6 Overall Contract and Project Management Improvement Performance Metrics and Targets FY 2016 Overall Contract and Project Management Improvement Performance Metrics and Targets ...

  6. FY 2013 Overall Contract and Project Management Improvement Performanc...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    3 Overall Contract and Project Management Improvement Performance Metrics and Targets FY 2013 Overall Contract and Project Management Improvement Performance Metrics and Targets ...

  7. FY 2010 Overall Contract and Project Management Improvement Performanc...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    0 Overall Contract and Project Management Improvement Performance Metrics and Targets FY 2010 Overall Contract and Project Management Improvement Performance Metrics and Targets ...

  8. FY 2009 Overall Contract and Project Management Improvement Performanc...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    9 Overall Contract and Project Management Improvement Performance Metrics and Targets FY 2009 Overall Contract and Project Management Improvement Performance Metrics and Targets ...

  9. Contract and Project Management Improvement (CPMI) Closure Report...

    Energy Savers [EERE]

    Contract and Project Management Improvement (CPMI) Closure Report -- April 2012 Contract and Project Management Improvement (CPMI) Closure Report -- April 2012 The Department of ...

  10. FY 2011 Overall Contract and Project Management Improvement Performanc...

    Broader source: Energy.gov (indexed) [DOE]

    More Documents & Publications FY 2013 Overall Contract and Project Management Improvement Performance Metrics and Targets FY 2014 Overall Contract and Project Management Improvement ...