National Library of Energy BETA

Sample records for operators manhattan project

  1. The Manhattan Project -- Its Story

    Office of Scientific and Technical Information (OSTI)

    The Manhattan Project -- Its Story Establishment * Operations * Immediate Influences * Long-term Influences * Other Info More About the Manhattan Project atom image Courtesy Argonne National Laboratory The Manhattan Project -- Its Background This year is the 70th anniversary of the establishment of the Manhattan Project, a predecessor of the U.S. Department of Energy. To honor its impacts on science and history, various aspects of its background, establishment, operations, and immediate and

  2. Gosling, The Manhattan Project: Making the Atomic Bomb | Department...

    Energy Savers [EERE]

    Operational Management History Historical Resources History Publications Gosling, The Manhattan Project: Making the Atomic Bomb Gosling, The Manhattan Project: Making...

  3. Manhattan Project: Operation Crossroads, Bikini Atoll, July 1946

    Office of Scientific and Technical Information (OSTI)

    Crossroads Baker, Bikini Atoll, July 25, 1946 OPERATION CROSSROADS (Bikini Atoll, July 1946) Events > Postscript -- The Nuclear Age, 1945-present Informing the Public, August 1945 The Manhattan Engineer District, 1945-1946 First Steps toward International Control, 1944-1945 Search for a Policy on International Control, 1945 Negotiating International Control, 1945-1946 Civilian Control of Atomic Energy, 1945-1946 Operation Crossroads, July 1946 The VENONA Intercepts, 1946-1980 The Cold War,

  4. The Manhattan Project

    Office of Scientific and Technical Information (OSTI)

    The Manhattan Project Sites and Their Contributions * Key Events * Scientists * Its Story * Additional Information * Related Information President Roosevelt Establishes the Manhattan Project President Roosevelt instructs the Army to take responsibility for construction of atomic weapons complex. The Army delegates the task to the Corps of Engineers, which establishes the Manhattan Engineer District. Courtesy of National Nuclear Security Administration August 13, 2012 was the 70th anniversary of

  5. Manhattan Project | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Project Manhattan Project Manhattan Project New! Manhattan Project National Historical Park New! K-25 Virtual Museum The Department of Energy traces its origins to World War II and the Manhattan Project effort to build the first atomic bomb. As the direct descendent of the Manhattan Engineer District, the organization set up by the Army Corps of Engineers to develop and build the bomb, the Department continues to own and manage the Federal properties at most of the major Manhattan Project sites,

  6. Manhattan Project: People

    Office of Scientific and Technical Information (OSTI)

    groups of people contributing to the success of the Manhattan Project can be obtained by reading the summary pages for each of the categories, located in the left navigation bar. ...

  7. Manhattan Project: Places

    Office of Scientific and Technical Information (OSTI)

    Places "Met Lab" (Metallurgical Laboratory) Oak Ridge: Clinton Engineer Works Hanford Engineer Works Los Alamos Other Places Places of the Manhattan Project Places PLEASE NOTE: The Places pages are not yet available. Links to the pages listed below and to the left will be activated as content is developed. Select topics relating to the places where the Manhattan Project occurred have been grouped into the categories listed to the left. A quick overview of places involved in the

  8. Manhattan Project: Science

    Office of Scientific and Technical Information (OSTI)

    Science In the Laboratory Particle Accelerators and Other Technologies The Atom and Atomic Structure Nuclear Physics Bomb Design and Components Radioactivity Science and technology of the Manhattan Project Science PLEASE NOTE: The Science pages are not yet available. Links to the pages listed below and to the left will be activated as content is developed. Select topics relating to the science and technology of the Manhattan Project have been grouped into the categories listed to the left. A

  9. Manhattan Project: Events

    Office of Scientific and Technical Information (OSTI)

    Albert Einstein and Leo Szilard Events The events of the Manhattan Project have been grouped under the time periods listed to the left. A quick overview of the Manhattan Project can be obtained by reading the summaries on each of the eight "Time Periods" pages, located in the left navigation bar. Each summary page also has a listing of the events pages for that particular time period. For a complete menu of all events pages, see the comprehensive list of events below. Comprehensive

  10. Manhattan Project: Y-12 Operation, 1943-1944

    Office of Scientific and Technical Information (OSTI)

    Alpha Racetrack, Y-12 Electromagnetic Plant, Oak Ridge Y-12: OPERATION (Oak Ridge: Clinton, 1943-1944) Events > The Uranium Path to the Bomb, 1942-1944 Y-12: Design, 1942-1943 Y-12: Construction, 1943 Y-12: Operation, 1943-1944 Working K-25 into the Mix, 1943-1944 The Navy and Thermal Diffusion, 1944 During the summer and fall of 1943, the Y-12 Electromagnetic Plant at Oak Ridge began to take shape. The huge buildings to house the operating equipment were readied as manufacturers began

  11. Manhattan Project: Hanford Becomes Operational, 1943-1944

    Office of Scientific and Technical Information (OSTI)

    F Reactor Plutonium Production Complex at Hanford, 1945 HANFORD BECOMES OPERATIONAL (Hanford Engineer Works, 1943-1944) Events > The Plutonium Path to the Bomb, 1942-1944 Production Reactor (Pile) Design, 1942 DuPont and Hanford, 1942 CP-1 Goes Critical, December 2, 1942 Seaborg and Plutonium Chemistry, 1942-1944 Final Reactor Design and X-10, 1942-1943 Hanford Becomes Operational, 1943-1944 The plutonium production facilities at the Hanford Engineer Works took shape with the same wartime

  12. Manhattan Project National Historical Park

    Broader source: Energy.gov [DOE]

    The Department, as the direct descendent of the Manhattan Engineer District, owns and manages the Federal properties at most of the major Manhattan Project sites, including Oak Ridge, Tennessee;...

  13. Manhattan Project: Processes

    Office of Scientific and Technical Information (OSTI)

    Processes Uranium Mining, Milling, and Refining Uranium Isotope Separation Plutonium Production Bomb Design, Development, and Production Bomb Testing and Weapon Effects Processes PLEASE NOTE: The Processes pages are not yet available. Links to the pages listed below and to the left will be activated as content is developed. Select topics relating to the industrial processes of the Manhattan Project have been grouped into the categories listed to the left. A quick overview of processes involved

  14. Manhattan Project: Resources

    Office of Scientific and Technical Information (OSTI)

    RESOURCES RELATING TO THE MANHATTAN PROJECT In addition to the events, people, places, processes, and science pages that comprise the bulk of this web site, a number of additional resources are also provided: Reference Materials Maps Photo Gallery To Learn More Library Suggested Readings Background on this Site About this Site How to Navigate this Site Site Map Sources Note on Sources, A Nuclear Energy and the Public's Right to Know Sources and Notes (for each page) Sources and notes for this

  15. Manhattan Project: Site Map

    Office of Scientific and Technical Information (OSTI)

    SITE MAP Resources > Site Map THE MANHATTAN PROJECT Events 1890s-1939: Atomic Discoveries A Miniature Solar System, 1890s-1919 Exploring the Atom, 1919-1932 Atomic Bombardment, 1932-1938 The Discovery of Fission, 1938-1939 Fission Comes to America, 1939 1939-1942: Early Government Support Einstein's Letter, 1939 Early Uranium Research, 1939-1941 Piles and Plutonium, 1939-1941 Reorganization and Acceleration, 1940-1941 The MAUD Report, 1941 A Tentative Decision to Build the Bomb, 1941-1942

  16. The Manhattan Project | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    The Manhattan Project The Manhattan Project A brief History of the Manhattan Project: Terrence R. Fehner and F.G. Gosling, The Manhattan Project, 2012, 10 p. PDF icon The Manhattan Project.pdf More Documents & Publications Fehner and Gosling, Origins of the Nevada Test Site Fehner and Gosling, Atmospheric Nuclear Weapons Testing, 1951-1963. Battlefield of the Cold War: The Nevada Test Site, Volume I Gosling, The Manhattan Project: Making the Atomic Bomb

  17. Manhattan Project Signature Facilities | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... at three sites: Oak Ridge, Tennessee; Hanford, Washington; and Los Alamos, New Mexico. ... Manhattan Project Learn about the history of the Manhattan Project on this interactive ...

  18. Authorizing Legislation: HR 3979, SEC. 3039 Manhattan Project National

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Historical Park | Department of Energy Operational Management » History » Manhattan Project National Historical Park » Authorizing Legislation: HR 3979, SEC. 3039 Manhattan Project National Historical Park Authorizing Legislation: HR 3979, SEC. 3039 Manhattan Project National Historical Park Section 3039 from the 2015 National Defense Authorization Act, authorizing the Manhattan Project National Historical Park. File HR 3979 Park Bill.docx PDF icon mapr_540-108834-C_Sept 2012.pdf More

  19. Manhattan Project Historical Resources | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Project » Manhattan Project Historical Resources Manhattan Project Historical Resources New! Manhattan Project National Historical Park New! K-25 Virtual Museum The Department of Energy has developed and made available to the public--in print, online, and on display--a variety of Manhattan Project historical resources. These include histories, websites, reports and document collections, and exhibits and tours. Histories produced by the Department include The Manhattan Project, which provides a

  20. The Manhattan Project National Security History Series

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    The Manhattan Project National Security History Series 5 Visit our Manhattan Project web site: http://www.cfo.doe.gov/me70/manhattan/index.htm 5 DOE/MA-0002 Revised F. G. Gosling Offce of History and Heritage Resources Executive Secretariat Offce of Management Department of Energy January 2010 The Manhattan Project National Security History Series 5 National Security History Series Volume I: The Manhattan Project: Making the Atomic Bomb Volume II: Building the Nuclear Arsenal: Cold War Nuclear

  1. The_Manhattan_Project_2010.pdf | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    TheManhattanProject2010.pdf TheManhattanProject2010.pdf PDF icon TheManhattanProject2010.pdf More Documents & Publications Gosling, The Manhattan Project: Making the...

  2. Manhattan Project National Historical Park

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Manhattan Project National Historical Park U.S. Interior Secretary Ken Salazar recommended on July 13, 2011 that Congress establish a Manhattan Project National Historical Park. He is quoted as saying, "The secret development of the atomic bomb in multiple locations across the United States is an important story and one of the most transformative events in our nation"s history." The park is intended to be located in Hanford, Washington; Los Alamos, New Mexico; and Oak Ridge,

  3. Manhattan Project Sites at Los Alamos

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Gallery » Historic Manhattan Project Sites at Los Alamos National Lab The Manhattan Project National Historical Park The Manhattan Project National Historical Park includes 17 sites at Los Alamos National Laboratory and 13 sites in downtown Los Alamos. These remaining sites represent the world-changing history of the Manhattan Project at Los Alamos. Their preservation and interpretation will bring to life the scientific, social, political, and cultural stories of the men & women who ushered

  4. Manhattan Project Signature Facilities | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Manhattan Project » Manhattan Project Signature Facilities Manhattan Project Signature Facilities The "Gadget" device fully assembled atop the 100-foot firing tower, shortly before the Trinity test. July 15, 1945. The "Gadget" device fully assembled atop the 100-foot firing tower, shortly before the Trinity test. July 15, 1945. New! Manhattan Project National Historical Park New! K-25 Virtual Museum The Department of Energy, in the mid-1990s, developed a list of eight

  5. Manhattan Project truck unearthed at landfill cleanup site

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Manhattan project truck Manhattan Project truck unearthed at landfill cleanup site A LANL excavation crew working on a Recovery Act cleanup project has uncovered the remnants of a 1940s military truck buried in a Manhattan Project-era landfill. April 8, 2011 image description Excavator operator Kevin Miller looks at the remnants of a 1940s military truck buried in a Manhattan Project-era landfill. Contact Fred deSousa Communications Office (505) 665-3430 Email Remnants of a 1940s military truck

  6. President Roosevelt Establishes Manhattan Project | National Nuclear

    National Nuclear Security Administration (NNSA)

    Security Administration Establishes Manhattan Project | National Nuclear Security Administration Facebook Twitter Youtube Flickr RSS People Mission Managing the Stockpile Preventing Proliferation Powering the Nuclear Navy Emergency Response Recapitalizing Our Infrastructure Countering Nuclear Terrorism About Our Programs Our History Who We Are Our Leadership Our Locations Budget Our Operations Library Bios Congressional Testimony Fact Sheets Newsletters Press Releases Photo Gallery Jobs

  7. Manhattan Project: The Manhattan Engineer District, 1945-1946

    Office of Scientific and Technical Information (OSTI)

    (Unofficial) MED emblem, 1946 THE MANHATTAN ENGINEER DISTRICT (1945-1946) Events > Postscript -- The Nuclear Age, 1945-Present Informing the Public, August 1945 The Manhattan Engineer District, 1945-1946 First Steps toward International Control, 1944-1945 Search for a Policy on International Control, 1945 Negotiating International Control, 1945-1946 Civilian Control of Atomic Energy, 1945-1946 Operation Crossroads, July 1946 The VENONA Intercepts, 1946-1980 The Cold War, 1945-1990 Nuclear

  8. Manhattan Project: The Venona Intercepts

    Office of Scientific and Technical Information (OSTI)

    Venona intercept regarding Theodore Hall THE VENONA INTERCEPTS (Washington, D.C., 1946-1980) Events > Postscript -- The Nuclear Age, 1945-Present Informing the Public, August 1945 The Manhattan Engineer District, 1945-1946 First Steps toward International Control, 1944-1945 Search for a Policy on International Control, 1945 Negotiating International Control, 1945-1946 Civilian Control of Atomic Energy, 1945-1946 Operation Crossroads, July 1946 The VENONA Intercepts, 1946-1980 The Cold War,

  9. Manhattan Project: The Manhattan Project and the Second World War,

    Office of Scientific and Technical Information (OSTI)

    1939-1945 Oak Ridgers celebrate V-J Day THE MANHATTAN PROJECT AND THE SECOND WORLD WAR (1939-1945) Events > Dawn of the Atomic Era, 1945 The War Enters Its Final Phase, 1945 Debate Over How to Use the Bomb, Late Spring 1945 The Trinity Test, July 16, 1945 Safety and the Trinity Test, July 1945 Evaluations of Trinity, July 1945 Potsdam and the Final Decision to Bomb, July 1945 The Atomic Bombing of Hiroshima, August 6, 1945 The Atomic Bombing of Nagasaki, August 9, 1945 Japan Surrenders,

  10. Manhattan Project: Sources and Notes

    Office of Scientific and Technical Information (OSTI)

    SOURCES AND NOTES Resources > Sources Below are the collected specific notes for the text and images used on the pages of this web site. For a discussion of the most important works on the Manhattan Project, see the "Suggested Readings." For a general discussion of the use of sources in this web site, see "A Note on Sources." To scan the sources and notes for various categories, choose from the list below. To view the sources and notes for a specific web page, see the

  11. The Manhattan Project: Making the Atomic Bomb | Department of...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    The Manhattan Project: Making the Atomic Bomb The Manhattan Project: Making the Atomic Bomb This report is an account of work on the atomic bomb. PDF icon The Manhattan Project:...

  12. MANHATTAN PROJECT NATIONAL HISTORICAL PARK | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    at three sites: Oak Ridge, Tennessee; Hanford, Washington; and Los Alamos, New Mexico. ... Manhattan Project Learn about the history of the Manhattan Project on this interactive ...

  13. Manhattan Project: Nuclear Proliferation, 1949-Present

    Office of Scientific and Technical Information (OSTI)

    -- The Nuclear Age, 1945-Present Informing the Public, August 1945 The Manhattan ... been informed of the bomb project and had no knowledge of the Hyde Park aide-mmoire. ...

  14. The Manhattan Project: An Interactive History

    Office of Scientific and Technical Information (OSTI)

    The advent of nuclear weapons, made possible by the Manhattan Project, not only helped bring an end to the Second World War-it ushered in the atomic age and determined how the next ...

  15. The Manhattan Project: Making of the Atomic Bomb | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    The Manhattan Project: Making of the Atomic Bomb The Manhattan Project: Making of the Atomic Bomb history of the manhattan project PDF icon The Manhattan Project: Making of the Atomic Bomb More Documents & Publications Gosling, The Manhattan Project: Making the Atomic Bomb The_Manhattan_Project_2010.pdf The Manhattan Project: Making the Atomic Bomb

  16. Events leading to the Manhattan Project

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    leading to the Manhattan Project This is the third in a series of articles on the unique history of Y-12. A series of significant events across the world were precursors to the Manhattan Project and Y-12. The basic building blocks and mechanisms of atomic energy were discovered over the first 40 years of the twentieth century. The basic knowledge of physics was greatly expanded around the turn of the century when scientists began to understand the nature of atoms. French physicist Pierre Curie

  17. DOE Under Secretary Recognizes Residents who Helped Plan Manhattan Project

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Park | Department of Energy Under Secretary Recognizes Residents who Helped Plan Manhattan Project Park DOE Under Secretary Recognizes Residents who Helped Plan Manhattan Project Park October 5, 2015 - 12:05pm Addthis DOE Deputy Under Secretary for Management and Performance David Klaus discussed the Manhattan Project National Historical Park during the National Cleanup Workshop. DOE Deputy Under Secretary for Management and Performance David Klaus discussed the Manhattan Project National

  18. Manhattan Project Resources | Y-12 National Security Complex

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Manhattan Project Resources Manhattan Project Resources Building 9731 was the first building completed at Y-12 and was the "Pilot Plant" for the Calutron electromagnetic separation of uranium. The Manhattan Project web pages are designed to disseminate information and documentation on the Manhattan Project to a broad audience including scholars, students, and the general public. These web pages are a joint collaboration between DOE's Office of Classification and Office of History and

  19. Manhattan Project National Historical Park Open House Event

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Manhattan Project National Historical Park Open House Event Manhattan Project National Historical Park Open House Event WHEN: Jun 02, 2015 5:00 PM - 7:00 PM WHERE: Fuller Lodge 2132 Central Avenue, Los Alamos, New Mexico, 87544 USA CONTACT: Linda Deck 505 665-3906 CATEGORY: Bradbury INTERNAL: Calendar Login Los Alamos Manhattan Project Era Main Gate Entrance Event Description Public Open House with the US Dept. of Energy and National Park Service planning team for the Manhattan Project National

  20. Manhattan Project: Nuclear Proliferation, 1949-Present

    Office of Scientific and Technical Information (OSTI)

    Joe 1, the first Soviet atomic test, August 29, 1949. NUCLEAR PROLIFERATION (1949-Present) Events > Postscript -- The Nuclear Age, 1945-Present Informing the Public, August 1945 The Manhattan Engineer District, 1945-1946 First Steps toward International Control, 1944-1945 Search for a Policy on International Control, 1945 Negotiating International Control, 1945-1946 Civilian Control of Atomic Energy, 1945-1946 Operation Crossroads, July 1946 The VENONA Intercepts, 1946-1980 The Cold War,

  1. Manhattan Project Truck Unearthed in Recovery Act Cleanup | Department of

    Office of Environmental Management (EM)

    Energy Manhattan Project Truck Unearthed in Recovery Act Cleanup Manhattan Project Truck Unearthed in Recovery Act Cleanup A Los Alamos National Laboratory (LANL) excavation crew working on an American Recovery and Reinvestment Act cleanup project has uncovered the remnants of a 1940s military truck buried in a Manhattan Project landfill. The truck was unearthed inside a sealed building where digging is taking place at Material Disposal Area B (MDA-B), the Lab's first hazardous and

  2. It's official: the Manhattan Project National Historical Park | Y-12

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    National Security Complex About / History / It's official: the ... It's official: the Manhattan Project National Historical Park Posted: December 17, 2015 - 5:05pm Y-12 Historian Ray Smith, wearing a bow tie in memory of Oak Ridge famed historian Bill Wilcox, shares his view of attending the Manhattan Project National Historic Park signing. Y-12 Historian Ray Smith was a part of history when he attended the signing of the Manhattan Project National Historical Park. He shares his memories

  3. Manhattan Project: About the Site

    Office of Scientific and Technical Information (OSTI)

    ABOUT THIS SITE Resources Project Directors: Terrence R. Fehner, Chief Historian F. G. Gosling, former Chief Historian (retired) Assisted By: David Rezelman, Glenn T. Seaborg Fellow in Nuclear History Stephanie Young, Edward Teller Fellow in Science and National Security Studies Andrew Mamo, Edward Teller Fellow in Science and National Security Studies Emily Hamilton, Edward Teller Fellow in Science and National Security Studies Douglas O’Reagan, Edward Teller Fellow in Science and National

  4. Authorizing Legislation: HR 3979, SEC. 3039 Manhattan Project...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    DOEEA-1868 (September 2010) Before the House Subcommittee on National Parks, Forests ... SEC. 3039 Manhattan Project National Historical Park Park Implementation Sustainability

  5. Agencies Move Closer to Creating Manhattan Project National Park |

    Energy Savers [EERE]

    Department of Energy Agencies Move Closer to Creating Manhattan Project National Park Agencies Move Closer to Creating Manhattan Project National Park August 31, 2015 - 12:40pm Addthis Shown here are the remains of Hanford High School, built in 1916 in the town of Hanford. It will be one of many pieces of the Manhattan Project National Historical Park. Shown here are the remains of Hanford High School, built in 1916 in the town of Hanford. It will be one of many pieces of the Manhattan

  6. Manhattan Project: How to Navigate this Site

    Office of Scientific and Technical Information (OSTI)

    HOW TO NAVIGATE THIS SITE Resources > Navigation There are five main topical areas on this web site: Events, People, Places, Processes, and Science. These are further divided into sub-sections, each with its own introduction. The main topical areas can be accessed by clicking on a button on the horizontal bar above. Sub-sections can be accessed by clicking on a topic in the vertical column to your left. If you would like to begin with a quick survey of the Manhattan Project, try reading, in

  7. Manufacturing Fuel Cell Manhattan Project | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Presented at the NREL Hydrogen and Fuel Cell Manufacturing R&D Workshop in Washington, DC, August 11-12, 2011. PDF icon Manufacturing Fuel Cell Manhattan Project More Documents & Publications Manufacturing Fuel Cell Manhattan Project 2011 NREL/DOE Hydrogen and Fuel Cell Manufacturing R&D Workshop Report Low Temperature PEM Fuel Cell Manufacturing Needs

  8. Manhattan Project: Groves and the MED, 1942

    Office of Scientific and Technical Information (OSTI)

    In addition, Groves moved the Manhattan Engineer District headquarters from New York to Washington. He quickly recognized the talents of Marshall's deputy, Colonel Kenneth D. ...

  9. Luis Alvarez and the Manhattan Project | Department of Energy

    Energy Savers [EERE]

    Luis Alvarez and the Manhattan Project Luis Alvarez and the Manhattan Project January 14, 2016 - 4:02pm Addthis What does this project do? Goal 6. Engage the Public, Governments, and Interested Parties 1Luis Alvarez_DOE Flickr Cropped 2 HD.4G.049.jpg Luis W. Avarez (c. 1940s). The Nobel Laureate made significant contributions to the Manhattan Project. National Hispanic Heritage Month (September 15 to October 15, 2015) provided an opportunity to remember Luis W. Alvarez's involvement in the

  10. Ohio and the Manhattan Project | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Ohio and the Manhattan Project Ohio and the Manhattan Project October 13, 2015 - 2:44pm Addthis What does this project do? Goal 5. Sustain management excellence. (top) B&T Metals, in Columbus; and (bottom) the Fernald Feed Materials Production Center, near Cincinnati. After a briefing regarding the Manhattan Project, Nobel Laureate Niels Bohr said to physicist Edward Teller, "I told you it couldn't be done without turning the whole country into a factory." Of course, the state

  11. Gosling, The Manhattan Project: Making the Atomic Bomb | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy Gosling, The Manhattan Project: Making the Atomic Bomb Gosling, The Manhattan Project: Making the Atomic Bomb F.G. Gosling. The Manhattan Project: Making the Atomic Bomb. DOE/MA-0002 Revised. Washington, D.C.: Department of Energy, 2010. 115 pp., with 38 pp. photo gallery). From the Forward to the 2010 Edition: "In a national survey at the turn of the millennium, journalists and historians ranked the dropping of the atomic bomb and the surrender of Japan to end the Second World

  12. Special Resource Study/Environmental Assessment for Manhattan Project

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Sites, DOE/EA-1868 (September 2010) | Department of Energy Special Resource Study/Environmental Assessment for Manhattan Project Sites, DOE/EA-1868 (September 2010) Special Resource Study/Environmental Assessment for Manhattan Project Sites, DOE/EA-1868 (September 2010) The purpose of this study is to comply with the Manhattan Project National Historical Park Study Act (Public Law 108-340), passed in 2004, which directed the Secretary of the Interior to "conduct a study on the

  13. Manhattan Project: The Navy and Thermal Diffusion, 1944

    Office of Scientific and Technical Information (OSTI)

    Diffusion columns, S-50 Thermal Diffusion Plant, Oak Ridge, 1945. THE NAVY AND THERMAL DIFFUSION (Oak Ridge: Clinton, 1944) Events > The Uranium Path to the Bomb, 1942-1944 Y-12: Design, 1942-1943 Y-12: Construction, 1943 Y-12: Operation, 1943-1944 Working K-25 into the Mix, 1943-1944 The Navy and Thermal Diffusion, 1944 As problems with both Y-12 and K-25 reached crisis proportions in spring and summer 1944, the Manhattan Project received help from an unexpected source: the United States

  14. Recovery Act milestone: Excavation begins at Manhattan Project...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    a series of trenches used from 1944 to 1948 to dispose of hazardous and non-hazardous trash from Manhattan Project labs and buildings. July 1, 2010 Los Alamos National Laboratory...

  15. New Manhattan Project Resource Page Launched | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Manhattan Project Resource Page Launched New Manhattan Project Resource Page Launched July 16, 2013 - 5:48pm Addthis General Leslie Groves and J. Robert Oppenheimer are pictured here at the Trinity Test site in New Mexico, 1945. General Leslie Groves and J. Robert Oppenheimer are pictured here at the Trinity Test site in New Mexico, 1945. Terry Fehner Terry Fehner Historian, Federal Preservation Officer Andrew Weston-Dawkes Andrew Weston-Dawkes Director, Office of Classification What are the key

  16. Workers Make History by Demolishing Manhattan Project Facilities |

    Energy Savers [EERE]

    Department of Energy Workers Make History by Demolishing Manhattan Project Facilities Workers Make History by Demolishing Manhattan Project Facilities February 16, 2016 - 1:45pm Addthis Once K-27 is demolished, it will mark the first-ever cleanup of an entire gaseous diffusion complex anywhere. | Office of Environmental Management video David Sheeley David Sheeley Editor/Writer For the first time in history, workers will complete the demolition and cleanup of an entire gaseous diffusion

  17. Interior and Energy Departments Formally Establish the Manhattan Project

    Office of Environmental Management (EM)

    National Historical Park | Department of Energy Interior and Energy Departments Formally Establish the Manhattan Project National Historical Park Interior and Energy Departments Formally Establish the Manhattan Project National Historical Park November 10, 2015 - 12:55pm Addthis NEWS MEDIA CONTACT (202) 586-4940 DOENews@hq.doe.gov WASHINGTON - U.S. Secretary of the Interior Sally Jewell and U.S. Secretary of Energy Ernest Moniz signed a memorandum of agreement today establishing the

  18. MANHATTAN PROJECT NATIONAL HISTORICAL PARK | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    MANHATTAN PROJECT NATIONAL HISTORICAL PARK MANHATTAN PROJECT NATIONAL HISTORICAL PARK What's New July 28, 2015: Draft Memorandum of Agreement between DOE and NPS posted July 28, 2015: Draft Memorandum of Agreement between DOE and NPS posted The NPS posts for comment the draft Memorandum of Agreement between DOE and NPS on its Planning, Environment and Public Comment (PEPC) site. The Park Service also provides a list of Frequently Asked Questions and maps with the initial properties to be

  19. Historic Manhattan Project Sites at Los Alamos

    ScienceCinema (OSTI)

    McGehee, Ellen

    2014-05-22

    The Manhattan Project laboratory constructed at Los Alamos, New Mexico, beginning in 1943, was intended from the start to be temporary and to go up with amazing speed. Because most of those WWII-era facilities were built with minimal materials and so quickly, much of the original infrastructure was torn down in the late '40s and early '50s and replaced by more permanent facilities. However, a few key facilities remained, and are being preserved and maintained for historic significance. Four such sites are visited briefly in this video, taking viewers to V-Site, the buildings where the first nuclear explosive device was pre-assembled in preparation for the Trinity Test in Southern New Mexico. Included is another WWII area, Gun Site. So named because it was the area where scientists and engineers tested the so-called "gun method" of assembling nuclear materials -- the fundamental design of the Little Boy weapon that was eventually dropped on Hiroshima. The video also goes to Pajarito Site, home of the "Slotin Building" and "Pond Cabin." The Slotin Building is the place where scientist Louis Slotin conducted a criticality experiment that went awry in early 1946, leading to his unfortunate death, and the Pond Cabin served the team of eminent scientist Emilio Segre who did early chemistry work on plutonium that ultimately led to the Fat Man weapon.

  20. Manhattan Project: Nuclear Proliferation, 1949-Present

    Office of Scientific and Technical Information (OSTI)

    Bernard Baruch presents the United States plan for international control of atomic energy to the United Nations, June 14, 1946. NEGOTIATING INTERNATIONAL CONTROL (December 1945-1946) Events > Postscript -- The Nuclear Age, 1945-Present Informing the Public, August 1945 The Manhattan Engineer District, 1945-1946 First Steps toward International Control, 1944-1945 Search for a Policy on International Control, 1945 Negotiating International Control, 1945-1946 Civilian Control of Atomic Energy,

  1. Manhattan Project: A Note on Sources

    Office of Scientific and Technical Information (OSTI)

    A NOTE ON SOURCES Resources > Note on Sources The text for this web site is a combination of original material and adaptations from previous publications of the Department of Energy (including contractors), its predecessor agencies (primarily the Atomic Energy Commission and the Manhattan Engineer District), and other government agencies. Adaptations run the gamut from summaries to close paraphrases to text being taken directly. This material was gathered and adapted for use by the DOE's

  2. Turning the Manhattan Project into a National Park | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    the Manhattan Project into a National Park Turning the Manhattan Project into a National Park February 23, 2015 - 3:43pm Addthis This photo shows the B Reactor -- the world’s first large-scale plutonium production reactor -- in Hanford, Washington, part of the Manhattan Project National Park. | Photo courtesy of the Energy Department. This photo shows the B Reactor -- the world's first large-scale plutonium production reactor -- in Hanford, Washington, part of the Manhattan Project National

  3. Manhattan Project: Postscript--The Nuclear Age, 1945-Present

    Office of Scientific and Technical Information (OSTI)

    Government-suggested fallout shelter design, 1950s POSTSCRIPT--THE NUCLEAR AGE (1945-Present) Events Informing the Public, August 1945 The Manhattan Engineer District, 1945-1946 First Steps toward International Control, 1944-1945 Search for a Policy on International Control, 1945 Negotiating International Control, 1945-1946 Civilian Control of Atomic Energy, 1945-1946 Operation Crossroads, July 1946 The VENONA Intercepts, 1946-1980 The Cold War, 1945-1990 Nuclear Proliferation, 1949-present Joe

  4. Manhattan Project: The Cold War, 1945-1990

    Office of Scientific and Technical Information (OSTI)

    West Berliner talks to the East, Berlin Wall, November 1962 THE COLD WAR (1945-1990) Events > Postscript -- The Nuclear Age, 1945-Present Informing the Public, August 1945 The Manhattan Engineer District, 1945-1946 First Steps toward International Control, 1944-1945 Search for a Policy on International Control, 1945 Negotiating International Control, 1945-1946 Civilian Control of Atomic Energy, 1945-1946 Operation Crossroads, July 1946 The VENONA Intercepts, 1946-1980 The Cold War, 1945-1990

  5. Recovery Act Helps Y-12 Exceed Cleanup Goal at Manhattan Project...

    National Nuclear Security Administration (NNSA)

    Helps Y-12 Exceed Cleanup Goal at Manhattan Project-Era Building | National Nuclear Security Administration Facebook Twitter Youtube Flickr RSS People Mission Managing the...

  6. Recovery Act Helps Y-12 Exceed Cleanup Goal at Manhattan Project-Era

    National Nuclear Security Administration (NNSA)

    Building | National Nuclear Security Administration Helps Y-12 Exceed Cleanup Goal at Manhattan Project-Era Building | National Nuclear Security Administration Facebook Twitter Youtube Flickr RSS People Mission Managing the Stockpile Preventing Proliferation Powering the Nuclear Navy Emergency Response Recapitalizing Our Infrastructure Countering Nuclear Terrorism About Our Programs Our History Who We Are Our Leadership Our Locations Budget Our Operations Library Bios Congressional Testimony

  7. Manhattan Project: Y-12 Construction, 1943

    Office of Scientific and Technical Information (OSTI)

    Groundbreaking for Y-12, Oak Ridge Y-12: CONSTRUCTION (Oak Ridge: Clinton, 1943) Events > The Uranium Path to the Bomb, 1942-1944 Y-12: Design, 1942-1943 Y-12: Construction, 1943 Y-12: Operation, 1943-1944 Working K-25 into the Mix, 1943-1944 The Navy and Thermal Diffusion, 1944 Groundbreaking for the Alpha plant of the Y-12 Electromagnetic Plant took place at Oak Ridge on February 18, 1943 (right). Soon blueprints could not be produced fast enough to keep up with construction as Stone &

  8. The Manhattan Project: Making the Atomic Bomb. 1999 edition.

    SciTech Connect (OSTI)

    Gosling, F.G.

    1999-01-01

    ``The Manhattan Project: Making the Atomic Bomb`` is a short history of the origins and development of the American atomic bomb program during World War II. Beginning with the scientific developments of the pre-war years, the monograph details the role of the United States government in conducting a secret, nationwide enterprise that took science from the laboratory and into combat with an entirely new type of weapon. The monograph concludes with a discussion of the immediate postwar period, the debate over the Atomic Energy Act of 1946, and the founding of the Atomic Energy Commission.

  9. Manhattan Project: Bringing it All Together, 1942-1945

    Office of Scientific and Technical Information (OSTI)

    Eric Jette, Charles Critchfield, and J. Robert Oppenheimer, Los Alamos BRINGING IT ALL TOGETHER (1942-1945) Events > Bringing It All Together, 1942-1945 Establishing Los Alamos, 1942-1943 Early Bomb Design, 1943-1944 Basic Research at Los Alamos, 1943-1944 Implosion Becomes a Necessity, 1944 Oak Ridge and Hanford Come Through, 1944-1945 Final Bomb Design, 1944-1945 Atomic Rivals and the ALSOS Mission, 1938-1945 Espionage and the Manhattan Project, 1940-1945 No matter how much enriched uranium

  10. Manhattan Project: Dawn of the Atomic Era, 1945

    Office of Scientific and Technical Information (OSTI)

    Trinity, July 16, 1945 DAWN OF THE ATOMIC ERA (1945) Events The War Enters Its Final Phase, 1945 Debate Over How to Use the Bomb, Late Spring 1945 The Trinity Test, July 16, 1945 Safety and the Trinity Test, July 1945 Evaluations of Trinity, July 1945 Potsdam and the Final Decision to Bomb, July 1945 The Atomic Bombing of Hiroshima, August 6, 1945 The Atomic Bombing of Nagasaki, August 9, 1945 Japan Surrenders, August 10-15, 1945 The Manhattan Project and the Second World War, 1939-1945 As the

  11. The Manhattan Project: Making the Atomic Bomb. 1999 edition.

    DOE R&D Accomplishments [OSTI]

    Gosling, F. G.

    1999-01-01

    "The Manhattan Project: Making the Atomic Bomb" is a short history of the origins and development of the American atomic bomb program during World War II. Beginning with the scientific developments of the pre-war years, the monograph details the role of the United States government in conducting a secret, nationwide enterprise that took science from the laboratory and into combat with an entirely new type of weapon. The monograph concludes with a discussion of the immediate postwar period, the debate over the Atomic Energy Act of 1946, and the founding of the Atomic Energy Commission.

  12. Manhattan Project: Basic Research at Los Alamos, 1943-1944

    Office of Scientific and Technical Information (OSTI)

    Norris Bradbury, Robert Oppenheimer, Richard Feynman, Enrico Fermi, and others, Los Alamos, 1946 BASIC RESEARCH AT LOS ALAMOS (Los Alamos: Laboratory, 1943-1944) Events > Bringing It All Together, 1942-1945 Establishing Los Alamos, 1942-1943 Early Bomb Design, 1943-1944 Basic Research at Los Alamos, 1943-1944 Implosion Becomes a Necessity, 1944 Oak Ridge and Hanford Come Through, 1944-1945 Final Bomb Design, 1944-1945 Atomic Rivals and the ALSOS Mission, 1938-1945 Espionage and the Manhattan

  13. Manhattan Project buildings and facilities at the Hanford Site: A construction history

    SciTech Connect (OSTI)

    Gerber, M.S.

    1993-09-01

    This document thoroughly examines the role that the Hanford Engineer Works played in the Manhattan project. The historical aspects of the buildings and facilities are characterized. An in depth look at the facilities, including their functions, methods of fabrication and appearance is given for the 100 AREAS, 200 AREAS, 300 AREAS, 500, 800 and 900 AREAS, 600 AREA, 700 AREA, 1100 AREA and temporary construction structures.

  14. Workers Safely Tear Down Towers at Manhattan Project Site

    Broader source: Energy.gov [DOE]

    LOS ALAMOS, N.M. – After decades dominating the Los Alamos National Laboratory skyline, two water towers were safely demolished by workers in a matter of hours recently, bringing EM’s Environmental Projects Office at Los Alamos a step closer to transferring the land for future commercial or industrial use.

  15. Manhattan Project: Y-12: Design, 1942-1943

    Office of Scientific and Technical Information (OSTI)

    Ernest Lawrence slumps in his chair from fatigue in front of a cyclotron control panel while conducting calutron-related experiments, Berkeley, 1943. Y-12: DESIGN (Oak Ridge: Clinton, 1942-1943) Events > The Uranium Path to the Bomb, 1942-1944 Y-12: Design, 1942-1943 Y-12: Construction, 1943 Y-12: Operation, 1943-1944 Working K-25 into the Mix, 1943-1944 The Navy and Thermal Diffusion, 1944 Although the Lewis Report had placed gaseous diffusion ahead of the electromagnetic approach, many were

  16. Manhattan Project: Atomic Rivals and the ALSOS Mission, 1938-1945

    Office of Scientific and Technical Information (OSTI)

    Werner Heisenberg, the leader of the German atomic weapons program. ATOMIC RIVALS AND THE ALSOS MISSION (Germany and Japan, 1938-1945) Events > Bringing It All Together, 1942-1945 Establishing Los Alamos, 1942-1943 Early Bomb Design, 1943-1944 Basic Research at Los Alamos, 1943-1944 Implosion Becomes a Necessity, 1944 Oak Ridge and Hanford Come Through, 1944-1945 Final Bomb Design, 1944-1945 Atomic Rivals and the ALSOS Mission, 1938-1945 Espionage and the Manhattan Project, 1940-1945 For most

  17. Manhattan Project: Early Bomb Design, Los Alamos: Laboratory, 1943-1944

    Office of Scientific and Technical Information (OSTI)

    Little Boy at Tinian Island, August 1945 EARLY BOMB DESIGN (Los Alamos: Laboratory, 1943-1944) Events > Bringing it All Together, 1942-1945 Establishing Los Alamos, 1942-1943 Early Bomb Design, 1943-1944 Basic Research at Los Alamos, 1943-1944 Implosion Becomes a Necessity, 1944 Oak Ridge and Hanford Come Through, 1944-1945 Final Bomb Design, 1944-1945 Atomic Rivals and the ALSOS Mission, 1938-1945 Espionage and the Manhattan Project, 1940-1945 Early work on the design of the atomic bomb

  18. Manhattan Project: Final Bomb Design, Los Alamos: Laboratory, 1944-1945

    Office of Scientific and Technical Information (OSTI)

    The first 0.11 seconds of the nuclear age, Trinity, July 16, 1945. FINAL BOMB DESIGN (Los Alamos: Laboratory, 1944-1945) Events > Bringing It All Together, 1942-1945 Establishing Los Alamos, 1942-1943 Early Bomb Design, 1943-1944 Basic Research at Los Alamos, 1943-1944 Implosion Becomes a Necessity, 1944 Oak Ridge and Hanford Come Through, 1944-1945 Final Bomb Design, 1944-1945 Atomic Rivals and the ALSOS Mission, 1938-1945 Espionage and the Manhattan Project, 1940-1945 American troops

  19. Manhattan Project: Oak Ridge and Hanford Come Through, 1944-1945

    Office of Scientific and Technical Information (OSTI)

    Y-12 Plant, Oak Ridge, 1944 OAK RIDGE AND HANFORD COME THROUGH (Oak Ridge [Clinton] and Hanford, 1944-1945) Events > Bringing It All Together, 1942-1945 Establishing Los Alamos, 1942-1943 Early Bomb Design, 1943-1944 Basic Research at Los Alamos, 1943-1944 Implosion Becomes a Necessity, 1944 Oak Ridge and Hanford Come Through, 1944-1945 Final Bomb Design, 1944-1945 Atomic Rivals and the ALSOS Mission, 1938-1945 Espionage and the Manhattan Project, 1940-1945 None of Los Alamos's bomb design

  20. The Manhattan Project By Terrence R. Fehner and F.G. Gosling

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    At its peak, the project employed 130,000 workers and, by ... to President Roosevelt, informing him that recent research ... bombs, let alone the knowledge of the physics behind ...

  1. Atomic Bombs, Winning the War and Women in Pants: Voices of the Manhattan

    Energy Savers [EERE]

    Project Speak of the Nation's History | Department of Energy Atomic Bombs, Winning the War and Women in Pants: Voices of the Manhattan Project Speak of the Nation's History Atomic Bombs, Winning the War and Women in Pants: Voices of the Manhattan Project Speak of the Nation's History November 28, 2012 - 12:00pm Addthis Manhattan Project veteran Ralph Gates (far right) celebrates Christmas in 1945. Gates contributed to the Voices of the Manhattan Project, a storytelling project launched by

  2. Recovery Act Helps Y-12 Exceed Cleanup Goal at Manhattan Project-Era Building

    Broader source: Energy.gov [DOE]

    Beta 4, one of the oldest and largest buildings at the Y-12 National Security Complex, recently reached a significant cleanup milestone. The second floor of the building, more than 82,000 square feet, has been cleared of large equipment and waste from Cold War operations.

  3. Special Resource Study/Environmental Assessment for Manhattan...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Secretary of the Interior to "conduct a study on the preservation and interpretation of historic sites of the Manhattan Project for potential inclusion in the National Park System. ...

  4. Manhattan Project: CP-1 Goes Critical, Met Lab, December 2, 1942

    Office of Scientific and Technical Information (OSTI)

    CP-1 GOES CRITICAL (Met Lab, December 2, 1942) Events > The Plutonium Path to the Bomb, 1942-1944 Production Reactor (Pile) Design, 1942 DuPont and Hanford, 1942 CP-1 Goes Critical, December 2, 1942 Seaborg and Plutonium Chemistry, 1942-1944 Final Reactor Design and X-10, 1942-1943 Hanford Becomes Operational, 1943-1944 While arrangements were proceeding for the construction of full-size plutonium production reactors, critical questions remained about their basic design. The Italian physicist

  5. Manhattan Project: DuPont and Hanford, Hanford Engineer Works, 1942

    Office of Scientific and Technical Information (OSTI)

    The president of DuPont, Walter Carpenter, with Generals Levin H. Campbell, Everett Hughes, and Charles T. Harris. DUPONT AND HANFORD (Hanford Engineer Works, 1942) Events > The Plutonium Path to the Bomb, 1942-1944 Production Reactor (Pile) Design, 1942 DuPont and Hanford, 1942 CP-1 Goes Critical, December 2, 1942 Seaborg and Plutonium Chemistry, 1942-1944 Final Reactor Design and X-10, 1942-1943 Hanford Becomes Operational, 1943-1944 The scientists of the Met Lab had the technical expertise

  6. Manhattan Project: Final Reactor Design and X-10, 1942-1943

    Office of Scientific and Technical Information (OSTI)

    Schematic of the X-10 Graphite Reactor, Oak Ridge FINAL REACTOR DESIGN AND X-10 (Met Lab and Oak Ridge [Clinton], 1942-1943) Events > The Plutonium Path to the Bomb, 1942-1944 Production Reactor (Pile) Design, 1942 DuPont and Hanford, 1942 CP-1 Goes Critical, December 2, 1942 Seaborg and Plutonium Chemistry, 1942-1944 Final Reactor Design and X-10, 1942-1943 Hanford Becomes Operational, 1943-1944 Before any plutonium could be chemically separated from uranium for a bomb, however, that uranium

  7. Manhattan Project: Seaborg and Plutonium Chemistry, Met Lab, 1942-1944

    Office of Scientific and Technical Information (OSTI)

    Glenn T. Seaborg looks through a microscope at the world's first sample of pure plutonium, Met Lab, August 20, 1942. SEABORG AND PLUTONIUM CHEMISTRY (Met Lab, 1942-1944) Events > The Plutonium Path to the Bomb, 1942-1944 Production Reactor (Pile) Design, 1942 DuPont and Hanford, 1942 CP-1 Goes Critical, December 2, 1942 Seaborg and Plutonium Chemistry, 1942-1944 Final Reactor Design and X-10, 1942-1943 Hanford Becomes Operational, 1943-1944 While the Met Lab labored to make headway on pile

  8. Manhattan Project: The Plutonium Path to the Bomb, 1942-1944

    Office of Scientific and Technical Information (OSTI)

    THE PLUTONIUM PATH TO THE BOMB (1942-1944) Events > The Plutonium Path to the Bomb, 1942-1944 Production Reactor (Pile) Design, 1942 DuPont and Hanford, 1942 CP-1 Goes Critical, December 2, 1942 Seaborg and Plutonium Chemistry, 1942-1944 Final Reactor Design and X-10, 1942-1943 Hanford Becomes Operational, 1943-1944 Plutonium, produced in a uranium-fueled reactor (pile), was the second path taken toward achieving an atomic bomb. Design work on a full-scale plutonium production reactor began

  9. Manhattan Project: The Uranium Path to the Bomb, 1942-1944

    Office of Scientific and Technical Information (OSTI)

    Alpha Racetrack, Y-12 Electromagnetic Plant, Oak Ridge THE URANIUM PATH TO THE BOMB (1942-1944) Events > The Uranium Path to the Bomb, 1942-1944 Y-12: Design, 1942-1943 Y-12: Construction, 1943 Y-12: Operation, 1943-1944 Working K-25 into the Mix, 1943-1944 The Navy and Thermal Diffusion, 1944 The uranium path to the atomic bomb ran through Oak Ridge, Tennessee. Only if the new plants built at Oak Ridge produced enough enriched uranium-235 would a uranium bomb be possible. General Groves

  10. Manhattan Project: Working K-25 into the Mix, 1943-1944

    Office of Scientific and Technical Information (OSTI)

    K-25 Gaseous Diffusion Plant, Oak Ridge WORKING K-25 INTO THE MIX (Oak Ridge: Clinton, 1943-1944) Events > The Uranium Path to the Bomb, 1942-1944 Y-12: Design, 1942-1943 Y-12: Construction, 1943 Y-12: Operation, 1943-1944 Working K-25 into the Mix, 1943-1944 The Navy and Thermal Diffusion, 1944 In 1941 and 1942, gaseous diffusion had been considered by many as the most promising method of enriching uranium. The British in the influential 1941 MAUD Report had advocated the use of gaseous

  11. Y-12 and the National Park Service study, part 2 -- Or: Manhattan Project: No substitute for the real thing (title as it appeared in The Oak Ridger)

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    2 Or: Manhattan Project: No substitute for the real thing (title as it appeared in The Oak Ridger) Let's continue with the details of the National Park Service's and the Atomic Heritage Foundation's visit to Y-12 during the last week of January, 2010. The group visited Building 9204-3, Beta 3 Calutrons, as well as Building 9731, the pilot facility and the first building completed on the site. They indicated that they found both facilities fascinating. In addition to visiting the Beta 3 calutron

  12. Manhattan Project: Events Images

    Office of Scientific and Technical Information (OSTI)

    Resources About this Site How to Navigate this Site Library Maps Note on Sources Nuclear Energy and the Public's Right to Know Photo Gallery Site Map Sources and Notes Suggested Readings EVENTS IMAGES Resources > Photo Gallery Page Content Here Scroll down to see each of these images individually. The images are: 1. Albert Einstein and Leo Szilard (courtesy the Federation of American Scientists); 2. Painting of CP-1 going critical (courtesy the National Archives); 3. An Alpha Racetrack inside

  13. Manhattan Project: Photo Gallery

    Office of Scientific and Technical Information (OSTI)

    Pueblo Party Science Images Solvay Physics Conference Tech Area Gallery (Large) Tech Area Gallery (Small) Trinity Images Trinity (Color Photograph) Ed Westcott Previous Next...

  14. Project Analysis Standard Operating Procedure

    Energy Savers [EERE]

    and Project Analysis Standard Operating Procedure (EPASOP) Issued by Office of Acquisition and Project Management MA-63 March 12, 2014 DEPARTMENT OF ENERGY Office of Acquisition and Project Management (OAPM) EVMS & PROJECT ANALYSIS SOP MARCH 2014 ii Earned Value Management System (EVMS) and Project Analysis Standard Operating Procedure (EPASOP) OPR: MA-63 March 2014 1. PURPOSE. This EVMS and Project Analysis Standard Operating Procedure (EPASOP) will serve as a primary reference for MA-631

  15. Project Analysis Standard Operating Procedure

    Office of Environmental Management (EM)

    Standard Operating Procedure (EPASOP) Issued by Office of Acquisition and Project Management MA-63 March 12, 2014 DEPARTMENT OF ENERGY Office of Acquisition and Project...

  16. Pulling History from the Waste Stream: Identification and Collection of Manhattan Project and Cold War Era Artifacts on the Hanford Site

    SciTech Connect (OSTI)

    Marceau, Thomas E.; Watson, Thomas L.

    2013-11-13

    One man's trash is another man's treasure. Not everything called "waste" is meant for the refuse pile. The mission of the Curation Program is at direct odds with the remediation objectives of the Hanford Site. While others are busily tearing down and burying the Site's physical structures and their associated contents, the Curation Program seeks to preserve the tangible elements of the Site's history from these structures for future generations before they flow into the waste stream. Under the provisions of a Programmatic Agreement, Cultural Resources staff initiated a project to identify and collect artifacts and archives that have historic or interpretive value in documenting the role of the Hanford Site throughout the Manhattan Project and Cold War Era. The genesis of Hanford's modern day Curation Program, its evolution over nearly two decades, issues encountered, and lessons learned along the way -- particularly the importance of upper management advocacy, when and how identification efforts should be accomplished, the challenges of working within a radiological setting, and the importance of first hand information -- are presented.

  17. DOE Under Secretary Recognizes Residents who Helped Plan Manhattan...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    well. "The park is an opportunity to recognize what came before the start of the Manhattan Project era and also to show how it still affects these communities today," Klaus said. ...

  18. A Platinum Anniversary for U.S. Atomic Heritage - EM's Historic Manhattan

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Project Sites Gain International Media Attention | Department of Energy A Platinum Anniversary for U.S. Atomic Heritage - EM's Historic Manhattan Project Sites Gain International Media Attention A Platinum Anniversary for U.S. Atomic Heritage - EM's Historic Manhattan Project Sites Gain International Media Attention September 1, 2012 - 12:00pm Addthis WASHINGTON, D.C. - Traditionally, a platinum anniversary marks 70-years. The Manhattan roject legacy reached that special milestone this

  19. Manhattan Project: Espionage and the Manhattan Project, 1940...

    Office of Scientific and Technical Information (OSTI)

    ... In 1950, the confession of Klaus Fuchs led the FBI to his handler, Harry Gold, who in turn led the FBI to David Greenglass. When confronted, Greenglass confessed, implicating his ...

  20. Manhattan Project: Difficult Choices, 1942

    Office of Scientific and Technical Information (OSTI)

    "Met Lab" alumni at the University of Chicago -- Fermi is on the far left of the front row; Zinn is on Fermi's left; Anderson is on the far right of the front row; and Szilard is over Anderson's right shoulder. DIFFICULT CHOICES (1942) Events More Uranium Research, 1942 More Piles and Plutonium, 1942 Enter the Army, 1942 Groves and the MED, 1942 Picking Horses, November 1942 Final Approval to Build the Bomb, December 1942 By early 1942, as the United States suffered a series of

  1. Manhattan Project: Einstein's Letter, 1939

    Office of Scientific and Technical Information (OSTI)

    Einstein's letter to Roosevelt, August 2, 1939 EINSTEIN'S LETTER (1939) Events > Early Government Support, 1939-1942 Einstein's Letter, 1939 Early Uranium Research, 1939-1941 Piles and Plutonium, 1939-1941 Reorganization and Acceleration, 1940-1941 The MAUD Report, 1941 A Tentative Decision to Build the Bomb, 1941-1942 On October 11, 1939, Alexander Sachs, Wall Street economist and longtime friend and unofficial advisor to President Franklin Delano Roosevelt, met with the President to discuss

  2. Project Execution and Operational Readiness Reviews

    Broader source: Energy.gov [DOE]

    PMCDP is offering its annual delivery of the 3-day course, Project Execution and Operational Readiness Reviews, December 15-17, in Washington, D.C.

  3. Manhattan Team | Y-12 National Security Complex

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Team Section Chief Global Security Analysis & Training 865.574.0877 (office) Casey Cole Program Manager III Manhattan Team Deputy Global Security Analysis & Training...

  4. Richland Operations Office Cleanup Strategy, Scope

    Energy Savers [EERE]

    Richland Operations Office Cleanup Strategy, Scope Matt McCormick Manager Richland Operations Office May 1, 2014 John Ciucci Chief Operating Officer CH2M HILL Plateau Remediation Company Scott Sax President and Project Manager Washington Closure Hanford Frank Armijo President and General Manager Mission Support Alliance www.energy.gov/EM 2 Richland Operations Office Hanford Site History Hanford * Hanford began in 1943 as part of the Manhattan Project * Production of plutonium increased during

  5. Manhattan Project Historical Resources | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... exhibits also are on display at the Department's American Museum of Science and Energy and Y-12 History Center in Oak Ridge and Bradbury Science Museum in Los Alamos, New Mexico. ...

  6. Manhattan Project Sites at Los Alamos

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    about the role Los Alamos played during the Cold War. Los Alamos Historical Society Arts and Crafts Building 4. ARTS & CRAFTS BUILDING Originally classrooms for the Ranch...

  7. Manhattan Project: Atomic Bombardment, 1932-1938

    Office of Scientific and Technical Information (OSTI)

    Solvay Physics Conference, Brussels, October 1933 ATOMIC BOMBARDMENT (1932-1938) Events > Atomic Discoveries, 1890s-1939 A Miniature Solar System, 1890s-1919 Exploring the Atom, 1919-1932 Atomic Bombardment, 1932-1938 The Discovery of Fission, 1938-1939 Fission Comes to America, 1939 M. Stanley Livingston and Ernest O. Lawrence in front of a 27-inch cyclotron, Rad Lab, University of California, Berkeley, 1934. In the 1930s, scientists learned a tremendous amount about the structure of the

  8. Manhattan Project: Enter the Army, 1942

    Office of Scientific and Technical Information (OSTI)

    Army parade, Los Alamos ENTER THE ARMY (1942) Events > Difficult Choices, 1942 More Uranium Research, 1942 More Piles and Plutonium, 1942 Enter the Army, 1942 Groves and the MED, 1942 Picking Horses, November 1942 Final Approval to Build the Bomb, December 1942 The decision to proceed with planning for the production of enriched uranium and of plutonium led directly to the involvement of the Army, specifically the Corps of Engineers. President Roosevelt had approved Army involvement on

  9. Manhattan Project: Evaluations of Trinity, July 1945

    Office of Scientific and Technical Information (OSTI)

    Leslie Groves and J. Robert Oppenheimer EVALUATIONS OF TRINITY (July 1945) Events > Dawn of the Atomic Era, 1945 The War Enters Its Final Phase, 1945 Debate Over How to Use the Bomb, Late Spring 1945 The Trinity Test, July 16, 1945 Safety and the Trinity Test, July 1945 Evaluations of Trinity, July 1945 Potsdam and the Final Decision to Bomb, July 1945 The Atomic Bombing of Hiroshima, August 6, 1945 The Atomic Bombing of Nagasaki, August 9, 1945 Japan Surrenders, August 10-15, 1945 The

  10. Manhattan Project: Fission Comes to America, 1939

    Office of Scientific and Technical Information (OSTI)

    Excerpt from the comic book "Adventures Inside the Atom." Click on this image or visit the "Library" to view the whole comic book. FISSION COMES TO AMERICA (1939) Events > Atomic Discoveries, 1890s-1939 A Miniature Solar System, 1890s-1919 Exploring the Atom, 1919-1932 Atomic Bombardment, 1932-1938 The Discovery of Fission, 1938-1939 Fission Comes to America, 1939 News of the fission experiments of Otto Hahn and Fritz Strassmann, and of the Meitner-Frisch calculations that

  11. Manhattan Project: More Piles and Plutonium, 1942

    Office of Scientific and Technical Information (OSTI)

    "Met Lab" alumni at the University of Chicago -- Fermi is on the far left of the front row; Zinn is on Fermi's left; Anderson is on the far right of the front row; and Szilard is over Anderson's right shoulder. MORE PILES AND PLUTONIUM (1942) Events > Difficult Choices, 1942 More Uranium Research, 1942 More Piles and Plutonium, 1942 Enter the Army, 1942 Groves and the MED, 1942 Picking Horses, November 1942 Final Approval to Build the Bomb, December 1942 At the University of

  12. Manhattan Project: Picking Horses, November 1942

    Office of Scientific and Technical Information (OSTI)

    General Leslie Groves PICKING HORSES (November 1942) Events > Difficult Choices, 1942 More Uranium Research, 1942 More Piles and Plutonium, 1942 Enter the Army, 1942 Groves and the MED, 1942 Picking Horses, November 1942 Final Approval to Build the Bomb, December 1942 Leslie Groves (right) moved swiftly to make good on his new timetable by scheduling a decisive meeting of the Military Policy Committee for November 12, 1942, and of the S-1 Executive Committee for November 14. The scientists at

  13. Manhattan Project: More Uranium Research, 1942

    Office of Scientific and Technical Information (OSTI)

    ... The production of adequate centrifuges was proving to be a very difficult task, and it ... Both separation methods demanded the design and construction of new technologies and ...

  14. Manhattan Project: Informing the Public, August 1945

    Office of Scientific and Technical Information (OSTI)

    The Smyth Report, August 1945. INFORMING THE PUBLIC (August 1945) Events > Postscript -- ... to withhold from the world scientific knowledge. . . . but under present circumstances ...

  15. Manhattan Project: Atomic Discoveries, 1890s-1939

    Office of Scientific and Technical Information (OSTI)

    The exact nature of these atoms remained elusive, however, despite centuries of attempts by alchemists to create a "philosopher's stone" that could transmute atoms of lead to gold, ...

  16. Manhattan Project | National Nuclear Security Administration

    National Nuclear Security Administration (NNSA)

    celebration of Y-12's 70th anniversary, a short film capturing highlights of the site's history now is available for viewing on the Y-12 public Web site at http:www.y12.doe.gov

  17. Manhattan Project: Nuclear Proliferation, 1949-Present

    Office of Scientific and Technical Information (OSTI)

    1945) Events > Postscript -- The Nuclear Age, 1945-Present Informing the Public, ... The United States, Stimson noted in explaining his plan, might propose to stop all weapons ...

  18. Manhattan Project: The Maud Report, 1941

    Office of Scientific and Technical Information (OSTI)

    ... version, which is at http:www.nuclearfiles.orgmenukey-issuesnuclear-weaponshistorypre-cold-warmanhattan-projectmaud-report.htm, the MAUD Report is available on the ...

  19. EVMS and Project Analysis Standard Operating Procedure (EPASOP) |

    Energy Savers [EERE]

    Department of Energy and Project Analysis Standard Operating Procedure (EPASOP) EVMS and Project Analysis Standard Operating Procedure (EPASOP) PURPOSE This EVMS and Project Analysis Standard Operating Procedure (EPASOP) will serve as a primary reference for PM-20 when conducting project-level data analysis to support Monthly Project Assessments and other assessment needs. This SOP refers to several Project Assessment and Reporting System (PARS IIe) reports and provides instruction on

  20. Project Profile: High Operating Temperature Liquid Metal Heat...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    High Operating Temperature Liquid Metal Heat Transfer Fluids Project Profile: High Operating Temperature Liquid Metal Heat Transfer Fluids Logos for The University of California, ...

  1. Sunrayce 97 Continues Day 5 - Lee's Summit to Manhattan

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    5 - Lee's Summit to Manhattan For more information contact: Patrick Booher, Sunrayce Program Manager (202) 586-0713 Manhattan, Kan. -- Crowds filled the streets around the Capitol Building in downtown Topeka today, as 36 solar powered vehicles passed through on their way to Manhattan, Kansas. Local favorite Kansas State University finished 22nd for the day. "This warm welcome by the city of Topeka certainly made both the teams and staff feel great," said Tom Sheffler, Sunrayce 97

  2. EA-2008: Colorado River Storage Project Programmatic Operations and

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Maintenance Project; Coconino, Maricopa, Navajo, and Yavapai Counties (Arizona) and San Juan County (Utah) | Department of Energy 08: Colorado River Storage Project Programmatic Operations and Maintenance Project; Coconino, Maricopa, Navajo, and Yavapai Counties (Arizona) and San Juan County (Utah) EA-2008: Colorado River Storage Project Programmatic Operations and Maintenance Project; Coconino, Maricopa, Navajo, and Yavapai Counties (Arizona) and San Juan County (Utah) Summary Western Area

  3. Sunrayce 97 Continues Day 6 - Manhattan to Smith Center

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    6 - Manhattan to Smith Center For more information contact: Patrick Booher, Sunrayce Program Manager (202) 586-0713 Smith Center, Kan.- --Racing across the heartland of Kansas at ...

  4. Step 4: Project Implementation Introduction to Step 5: Project Operations & Maintenance

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    5: Project Operations & Maintenance Project Development Process 2 1 Potential 3 Refinement 2 Options 4 Implementation 5 Operations & Maintenance 3 Step 5: Operations & Maintenance (O&M) Photo from Florida Solar Energy Center, NREL 14728 1 Potential 3 Refinement 5 Operations & Maintenance 2 Options 4 Implementation Purpose: To ensure ongoing, effective project operation, i.e., energy production Operational Costs: * Equipment maintenance and replacement * Monitoring * Insurance

  5. 20 MW Maibarara Geothermal Power Project Starts Commercial Operations...

    Open Energy Info (EERE)

    02092014 DOI Not Provided Check for DOI availability: http:crossref.org Online Internet link for 20 MW Maibarara Geothermal Power Project Starts Commercial Operations...

  6. AWEA Wind Project Operations and Maintenance and Safety Seminar

    Broader source: Energy.gov [DOE]

    The AWEA Wind Project O&M and Safety Seminar is designed for owners, operators, turbine manufactures, material suppliers, wind technicians, managers, supervisors, engineers, and occupational...

  7. Midwest Independent Transmission System Operator Smart Grid Project...

    Open Energy Info (EERE)

    to optimize the dispatch and operation of power plants while improving the reliability of the bulk transmission system. This project deploys phasor measurement units...

  8. AVTA Federal Fleet PEV Readiness Data Logging and Characterization Study for Department of Veterans Affairs – VA Manhattan Campus

    SciTech Connect (OSTI)

    Stephen Schey; Jim Francfort

    2014-10-01

    This report focuses on the Department of Veterans Affairs, VA Manhattan Campus (VA- Manhattan) fleet to identify the daily operational characteristics of select vehicles and report findings on vehicle and mission characterizations to support successful introduction of plug-in electric vehicles (PEVs) into the agency’s fleet. Individual observations of these selected vehicles provide the basis for recommendations related to electric vehicle adoption and whether a battery electric vehicle or plug-in hybrid electric vehicle (collectively called PEVs) can fulfill the mission requirements.

  9. Operational Environmental Monitoring Program Quality Assurance Project Plan

    SciTech Connect (OSTI)

    Perkins, C.J.

    1994-08-01

    This Quality Assurance Project Plan addresses the quality assurance requirements for the activities associated with the preoperational and operational environmental monitoring performed by Westinghouse Hanford Company as it implements the Operational Environmental Monitoring program. This plan applies to all sampling and monitoring activities performed by Westinghouse Hanford Company in implementing the Operational Environmental Monitoring program at the Hanford Site.

  10. A Nuclear Family: The Manhattan District | Y-12 National Security...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    The ... A Nuclear Family: The Manhattan District The mp4 video format is not supported by this browser. Download video Captions: On Time: 26:40 min. Episode 2 tells our World War...

  11. Project Profile: High Operating Temperature Liquid Metal Heat Transfer

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Fluids | Department of Energy High Operating Temperature Liquid Metal Heat Transfer Fluids Project Profile: High Operating Temperature Liquid Metal Heat Transfer Fluids Logos for The University of California, Los Angeles, the University of California, Berkeley, and Yale University, and Four graphics in a grid that represent the sputtering technique being used in this project. The University of California, Los Angeles (UCLA), along with partners at the University of California, Berkeley, and

  12. PROJECT PROFILE: Regional Test Center Operations | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    PROJECT PROFILE: Regional Test Center Operations PROJECT PROFILE: Regional Test Center Operations Funding Opportunity: SuNLaMP SunShot Subprogram: Photovoltaics Location: Sandia National Laboratories, Albuquerque, NM SunShot Award Amount: $6,999,432 Location: National Renewable Energy Laboratory, Golden, CO SunShot Award Amount: $1,250,000 The Regional Test Center (RTC) program aims to support technical innovation in the U.S. solar sector by validating the performance of new PV products in

  13. IDAHO OPERATIONS OFFICE NAMES NEW IDAHO CLEANUP PROJECT MANAGER

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    doe logo Media Contact: Brad Bugger (208) 526-0833 For Immediate Release: Wednesday, June 29, 2011 IDAHO OPERATIONS OFFICE NAMES NEW IDAHO CLEANUP PROJECT MANAGER Idaho Falls, ID � The Department of Energy Idaho Operations Office today announced that James Cooper has been named deputy manager of its highly-successful Idaho Cleanup Project, which oversees the environmental cleanup and waste management mission at DOE's Idaho site. Cooper has more than 30 years of experience in commercial and

  14. The Ames Project (1942-1946)

    ScienceCinema (OSTI)

    None

    2013-06-05

    The Ames Laboratory was officially founded on May 17, 1947, following development of a process to purify uranium metal for the historic Manhattan Project. From 1942 to 1946, Ames Lab scientists produced over two-million pounds of uranium metal. A U.S. Department of Energy national research laboratory, the Ames Laboratory creates materials and energy solutions. Iowa State University operates Ames Laboratory under contract with the DOE.

  15. CRAD, Conduct of Operations- Idaho Accelerated Retrieval Project Phase II

    Broader source: Energy.gov [DOE]

    A section of Appendix C to DOE G 226.1-2 "Federal Line Management Oversight of Department of Energy Nuclear Facilities." Consists of Criteria Review and Approach Documents (CRADs) used for a February, 2006 Commencement of Operations assessment of the Conduct of Operations program at the Idaho Accelerated Retrieval Project Phase II.

  16. IDAHO OPERATIONS OFFICE NAMES NEW IDAHO CLEANUP PROJECT MANAGER

    Broader source: Energy.gov [DOE]

    Idaho Falls, ID The Department of Energy Idaho Operations Office today announced that James Cooper has been named deputy manager of its highly-successful Idaho Cleanup Project, which oversees the environmental cleanup and waste management mission at DOEs Idaho site.

  17. Work of Manhattan Project-era photographer Ed Westcott lives...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    soldier. The stage is set for the four-episode chronological description of a sense of family and deep pride felt by those who were and are connected to the work of Y-12....

  18. Manufacturing Fuel Cell Manhattan Project | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Utilizing experts from industry, government, and academia, the Navy Manufacturing Technology Program's Benchmarking Best Practices Center of Excellence, in conjunction with Montana ...

  19. Manhattan Project: A Miniature Solar System, 1890s-1919

    Office of Scientific and Technical Information (OSTI)

    John Joseph Thomson A MINIATURE SOLAR SYSTEM (1890s-1919) Events > Atomic Discoveries, 1890s-1939 A Miniature Solar System, 1890s-1919 Exploring the Atom, 1919-1932 Atomic Bombardment, 1932-1938 The Discovery of Fission, 1938-1939 Fission Comes to America, 1939 The modern effort to uncover the inner structure of the atom began with the discovery of the electron by the English physicist J. J. Thomson (above) in 1897. Thomson proved that cathode rays were not some sort of undefined process

  20. Manhattan Project: Debate Over How to Use the Bomb, 1945

    Office of Scientific and Technical Information (OSTI)

    Ernest Lawrence, Arthur Compton, Vannevar Bush, James Conant, Karl Compton, and Alfred Loomis, Berkeley, 1940 DEBATE OVER HOW TO USE THE BOMB (Washington, D.C., Late Spring 1945) Events > Dawn of the Atomic Era, 1945 The War Enters Its Final Phase, 1945 Debate Over How to Use the Bomb, Late Spring 1945 The Trinity Test, July 16, 1945 Safety and the Trinity Test, July 1945 Evaluations of Trinity, July 1945 Potsdam and the Final Decision to Bomb, July 1945 The Atomic Bombing of Hiroshima,

  1. Manhattan Project: Early Government Support, 1939-1942

    Office of Scientific and Technical Information (OSTI)

    Albert Einstein and Leo Szilard EARLY GOVERNMENT SUPPORT (1939-1942) Events Einstein's Letter, 1939 Early Uranium Research, 1939-1941 Piles and Plutonium, 1939-1941 Reorganization and Acceleration, 1940-1941 The MAUD Report, 1941 A Tentative Decision to Build the Bomb, 1941-1942 As the news of the fission breakthrough spread from Berlin in early 1939, many physicists within the United States (and elsewhere) immediately realized the potential danger posed by atomic energy. Especially concerned

  2. Manhattan Project: Early Uranium Research, 1939-1941

    Office of Scientific and Technical Information (OSTI)

    Ernest Lawrence, Arthur Compton, Vannevar Bush, and James Conant discuss uranium research, Berkeley, March 29, 1940. EARLY URANIUM RESEARCH (1939-1941) Events > Early Government Support, 1939-1942 Einstein's Letter, 1939 Early Uranium Research, 1939-1941 Piles and Plutonium, 1939-1941 Reorganization and Acceleration, 1940-1941 The MAUD Report, 1941 A Tentative Decision to Build the Bomb, 1941-1942 President Franklin D. Roosevelt responded to the call for government support of uranium research

  3. Manhattan Project: Exploring the Atom, 1919-1932

    Office of Scientific and Technical Information (OSTI)

    Ernest Rutherford (and James Chadwick, on the far right) EXPLORING THE ATOM (1919-1932) Events > Atomic Discoveries, 1890s-1939 A Miniature Solar System, 1890s-1919 Exploring the Atom, 1919-1932 Atomic Bombardment, 1932-1938 The Discovery of Fission, 1938-1939 Fission Comes to America, 1939 The road to the atomic bomb began in earnest in 1919 with the first artificial transmutation of an element. The New Zealander Ernest Rutherford, working in the Cavendish Laboratory at Cambridge University

  4. Manhattan Project: Japan Surrenders, August 10-15, 1945

    Office of Scientific and Technical Information (OSTI)

    Japanese envoys arrive on board the U.S.S. Missouri for the surrender ceremony, Tokyo Bay, September 2, 1945. JAPAN SURRENDERS (August 10-15, 1945) Events > Dawn of the Atomic Era, 1945 The War Enters Its Final Phase, 1945 Debate Over How to Use the Bomb, Late Spring 1945 The Trinity Test, July 16, 1945 Safety and the Trinity Test, July 1945 Evaluations of Trinity, July 1945 Potsdam and the Final Decision to Bomb, July 1945 The Atomic Bombing of Hiroshima, August 6, 1945 The Atomic Bombing of

  5. Manhattan Project: Piles and Plutonium, 1939-1942

    Office of Scientific and Technical Information (OSTI)

    Enrico Fermi PILES AND PLUTONIUM (1939-1942) Events > Early Government Support, 1939-1942 Einstein's Letter, 1939 Early Uranium Research, 1939-1941 Piles and Plutonium, 1939-1941 Reorganization and Acceleration, 1940-1941 The MAUD Report, 1941 A Tentative Decision to Build the Bomb, 1941-1942 The Uranium Committee's first report, issued on November 1, 1939, recommended that, despite the uncertainty of success, the government should immediately obtain four tons of graphite and fifty tons of

  6. Manhattan Project: Safety and the Trinity Test, July 1945

    Office of Scientific and Technical Information (OSTI)

    Trinity test radiation safety team SAFETY AND THE TRINITY TEST (Trinity Test Site, July 1945) Events > Dawn of the Atomic Era, 1945 The War Enters Its Final Phase, 1945 Debate Over How to Use the Bomb, Late Spring 1945 The Trinity Test, July 16, 1945 Safety and the Trinity Test, July 1945 Evaluations of Trinity, July 1945 Potsdam and the Final Decision to Bomb, July 1945 The Atomic Bombing of Hiroshima, August 6, 1945 The Atomic Bombing of Nagasaki, August 9, 1945 Japan Surrenders, August

  7. Manhattan Project: The Atomic Bombing of Nagasaki, August 9, 1945

    Office of Scientific and Technical Information (OSTI)

    Nagasaki, August 9, 1945 THE ATOMIC BOMBING OF NAGASAKI (Nagasaki, Japan, August 9, 1945) Events > Dawn of the Atomic Era, 1945 The War Enters Its Final Phase, 1945 Debate Over How to Use the Bomb, Late Spring 1945 The Trinity Test, July 16, 1945 Safety and the Trinity Test, July 1945 Evaluations of Trinity, July 1945 Potsdam and the Final Decision to Bomb, July 1945 The Atomic Bombing of Hiroshima, August 6, 1945 The Atomic Bombing of Nagasaki, August 9, 1945 Japan Surrenders, August 10-15,

  8. Manhattan Project: The Discovery of Fission, 1938-1939

    Office of Scientific and Technical Information (OSTI)

    Lise Meitner and Otto Hahn, Kaiser-Wilhelm Institute, Berlin THE DISCOVERY OF FISSION Berlin, Germany (1938-1939) Events > Atomic Discoveries, 1890s-1939 A Miniature Solar System, 1890s-1919 Exploring the Atom, 1919-1932 Atomic Bombardment, 1932-1938 The Discovery of Fission, 1938-1939 Fission Comes to America, 1939 The English word "atom" derives from the Greek word "atomon" ("ατομον"), which means "that which cannot be divided." In 1938, the

  9. Manhattan Project: The Trinity Test, July 16, 1945

    Office of Scientific and Technical Information (OSTI)

    Trinity test, July 16, 1945 THE TRINITY TEST (Trinity Test Site, July 16, 1945) Events > Dawn of the Atomic Era, 1945 The War Enters Its Final Phase, 1945 Debate Over How to Use the Bomb, Late Spring 1945 The Trinity Test, July 16, 1945 Safety and the Trinity Test, July 1945 Evaluations of Trinity, July 1945 Potsdam and the Final Decision to Bomb, July 1945 The Atomic Bombing of Hiroshima, August 6, 1945 The Atomic Bombing of Nagasaki, August 9, 1945 Japan Surrenders, August 10-15, 1945 The

  10. Manhattan Project: The War Enters Its Final Phase, 1945

    Office of Scientific and Technical Information (OSTI)

    American troops approaching the beach, D-Day, June 6, 1944. THE WAR ENTERS ITS FINAL PHASE (1945) Events > Dawn of the Atomic Era, 1945 The War Enters Its Final Phase, 1945 Debate Over How to Use the Bomb, Late Spring 1945 The Trinity Test, July 16, 1945 Safety and the Trinity Test, July 1945 Evaluations of Trinity, July 1945 Potsdam and the Final Decision to Bomb, July 1945 The Atomic Bombing of Hiroshima, August 6, 1945 The Atomic Bombing of Nagasaki, August 9, 1945 Japan Surrenders, August

  11. Manhattan Project: Reorganization and Acceleration, 1940-1941

    Office of Scientific and Technical Information (OSTI)

    Lawrence took his case to Karl T. Compton and Alfred L. Loomis at Harvard University, both ... headed by James B. Conant, president of Harvard University, became an advisory body ...

  12. Manhattan Project: Establishing Los Alamos, 1942-1943

    Office of Scientific and Technical Information (OSTI)

    ... Neither thought a military environment was conducive to scientific research. At ... Oppenheimer would supervise all scientific work, and the military would maintain the post ...

  13. Manhattan Project National Historical Park Open House Event

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    National Historical Park Open House Event WHEN: Jun 02, 2015 5:00 PM - 7:00 PM WHERE: Fuller Lodge 2132 Central Avenue, Los Alamos, New Mexico, 87544 USA CONTACT: Linda Deck 505...

  14. Manhattan Project NHP Photo Gallery | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    Skip to main content Menu Energy.gov Office of Management Search Search form Search Office of Management Office of Management Services Services Home Employee Services Employee...

  15. Manhattan Project: Leslie Groves and J. Robert Oppenheimer

    Office of Scientific and Technical Information (OSTI)

    Leslie Groves and J. Robert Oppenheimer Home Events > Difficult Choices, 1942 > Groves and the MED, 1942 Events > Bringing it All Together, 1942-1945 Events > Bringing it All Together, 1942-1945 > Implosion Becomes A Necessity, Los Alamos: Laboratory, 1944 Events > Dawn of the Atomic Era, 1945 > Evaluations of Trinity, July 1945 Science > In the Laboratory > Los Alamos Organization and Management, Los Alamos, New Mexico, 1942-1946 Resources > Photo Gallery Leslie

  16. Integrated Manhattan Project for Excellence in Radiochemistry (IMPER)

    SciTech Connect (OSTI)

    Lewis, Jason

    2014-03-27

    Accomplishments are reported in these areas: single step radiolabeling of peptides with fluorine-18; photoreduction of 99Tc pertechnetate by nanometer-sized metal oxides for environmental remediation; synthesis and characterization of multi-modal CNT imaging constructs.

  17. Manhattan Project: Implosion Becomes a Necessity, Los Alamos...

    Office of Scientific and Technical Information (OSTI)

    Implosion IMPLOSION BECOMES A NECESSITY (Los Alamos: Laboratory, 1944) Events > Bringing ... Consequently, Seth H. Neddermeyer performed his early implosion tests in relative ...

  18. Ohio and the Manhattan Project | Department of Energy

    Office of Environmental Management (EM)

    Industries, Inc., switched from making toys cars to making ammunition for anti-tank guns. In Dayton, National Cash Register started making magazines for anti-aircraft guns. In...

  19. Manhattan Project: The Atomic Bombing of Hiroshima, August 6...

    Office of Scientific and Technical Information (OSTI)

    ... exposure, such as an increased danger of cancer, would linger for the rest of the ... have reached or even exceeded 200,000, as cancer and other long-term effects took hold. ...

  20. Manhattan Project: Production Reactor (Pile) Design, Met Lab...

    Office of Scientific and Technical Information (OSTI)

    ... In June 1942, a group headed by Arthur Compton's chief engineer, Thomas V. Moore, began ... During the summer, Moore and his group began planning a helium-cooled pilot pile to be ...

  1. EM Capital and Major Operating Project Standard Review Plan Edition Two |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy EM Capital and Major Operating Project Standard Review Plan Edition Two EM Capital and Major Operating Project Standard Review Plan Edition Two This memorandum introduces the Second Edition of the Capital and Major Operations Projects Standard Review Plan (SRP). PDF icon Memo Issuance of EM Capital and Major Operating Project Standard Review Plan Edition Two More Documents & Publications Standard Review Plan - Overview EM Quality Assurance Assessment Schedule FY 2010

  2. New York Independent System Operator, Inc. Smart Grid Project...

    Open Energy Info (EERE)

    capacitors across the New York transmission system. The project aims to improve the reliability of the transmission grid and prevent the spread of local outages to neighboring...

  3. EVMS and Project Analysis Standard Operating Procedure (EPASOP...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Enhancing Earned Value (EV) Analysis Using Project Assessment & Reporting System (PARS II) - Road Show Presentation Earned Value Management System Gold Card Integrated Program ...

  4. INDEPENDENT VERIFICATION SURVEY REPORT FOR THE OPERABLE UNIT-1 LANDFILL TRENCHES, MIAMISBURG CLOSURE PROJECT

    SciTech Connect (OSTI)

    W.C. Adams

    2010-05-24

    INDEPENDENT VERIFICATION SURVEY REPORT FOR THE OPERABLE UNIT-1 LANDFILL TRENCHES, MIAMISBURG CLOSURE PROJECT, MIAMISBURG, OHIO DCN: 0468-SR-02-0

  5. EIS-0195: Remedial Actions at Operable Unit 4, Fernald Environmental Management Project, Fernald, Ohio

    Broader source: Energy.gov [DOE]

    This EIS evaluates the potential environmental impacts of a proposal to conduct remedial action at Operable Unit 4 at the Fernald Environmental Management Project.

  6. INDEPENDENT VERIFICATION SURVEY REPORT OPERABLE UNIT-1 LANDFILL TRENCHES, MIAMISBURG CLOSURE PROJECT

    SciTech Connect (OSTI)

    W.C. Adams

    2010-07-21

    INDEPENDENT VERIFICATION SURVEY REPORT FOR THE OPERABLE UNIT-1 LANDFILL TRENCHES, MIAMISBURG CLOSURE PROJECT, MIAMISBURG, OHIO DCN: 0468-SR-03-0

  7. Georgia System Operations Corporation Inc. Smart Grid Project...

    Open Energy Info (EERE)

    Power Quality Optimized Generator Operation Reduced Ancillary Service Cost Reduced Electricity Costs for Customers Reduced Greenhouse Gas and Criteria Pollutant Emissions Reduced...

  8. Reduce Operating Costs with an EnergySmart School Project

    Broader source: Energy.gov [DOE]

    EnergySmart Schools fact sheet on how school operations and maintenance (O&M) personnel can play a greater role in managing ever-increasing energy costs.

  9. Walla Walla River Fish Passage Operations Project : Annual Progress Report October 2007 - September 2008.

    SciTech Connect (OSTI)

    Bronson, James P.; Duke, Bill; Loffink, Ken

    2008-12-30

    In the late 1990s, the Confederated Tribes of the Umatilla Indian Reservation, Oregon Department of Fish and Wildlife, and Washington Department of Fish and Wildlife, along with many other agencies, began implementing fisheries restoration activities in the Walla Walla Basin. An integral part of these efforts is to alleviate the inadequate fish migration conditions in the basin. Migration concerns are being addressed by removing diversion structures, constructing fish passage facilities, implementing minimum instream flow requirements, and providing trap and haul efforts when needed. The objective of the Walla Walla River Fish Passage Operations Project is to increase the survival of migrating adult and juvenile salmonids in the Walla Walla River basin. The project is responsible for coordinating operation and maintenance of ladders, screen sites, bypasses, trap facilities, and transportation equipment. In addition, the project provides technical input on passage and trapping facility design, operation, and criteria. Operation of the various passage facilities and passage criteria guidelines are outlined in an annual operations plan that the project develops. Beginning in March of 2007, two work elements from the Walla Walla Fish Passage Operations Project were transferred to other projects. The work element Enumeration of Adult Migration at Nursery Bridge Dam is now conducted under the Walla Walla Basin Natural Production Monitoring and Evaluation Project and the work element Provide Transportation Assistance is conducted under the Umatilla Satellite Facilities Operation and Maintenance Project. Details of these activities can be found in those project's respective annual reports.

  10. Toledo Bend Project Joint Oper | Open Energy Information

    Open Energy Info (EERE)

    SERC NERC SERC Yes Operates Generating Plant Yes Activity Generation Yes Activity Wholesale Marketing Yes This article is a stub. You can help OpenEI by expanding it. Utility...

  11. Tribal Renewable Energy Webinar on Project Implementation and Operations & Maintenance on Aug. 8

    Broader source: Energy.gov [DOE]

    The Energy Department's Office of Indian Energy, Tribal Energy Program, and Western Area Power Administration will present the next Tribal Renewable Energy Series webinar, Project Implementation and Operations & Maintenance, on Friday, Aug. 8, 2014, from 11:00 a.m. to 12:30 p.m. Mountain time. The webinar will focus on the last two steps of a five-step tribal energy project development framework: Project Implementation and Operations and Maintenance (O&M).

  12. Memo Issuance of EM Capital and Major Operating Project Standard Review Plan Edition Two

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    MAR 2 4 201011 MEMORANDUM FOR DISTRIBUTION FROM: DR. STEVEN L. KRAHN DEPUTY ASSISTANT SAFETY AND SECU EIVVIROIVMENTAL MANAGEMENT SUBJECT: Issuance of Environmental Management Capital and Major Operating Project Standard Review Plan Edition Two The Office of Environmental Management (EM) is responsible for managing the design, construction, operation, and eventual disposition of mission critical projects/facilities. Effective management of these projects requires multiple disciplines to be

  13. Framework for Adaptable Operating and Runtime Systems: Final Project Report

    SciTech Connect (OSTI)

    Patrick G. Bridges

    2012-02-01

    In this grant, we examined a wide range of techniques for constructing high-performance con#12;gurable system software for HPC systems and its application to DOE-relevant problems. Overall, research and development on this project focused in three specifc areas: (1) software frameworks for constructing and deploying con#12;gurable system software, (2) applcation of these frameworks to HPC-oriented adaptable networking software, (3) performance analysis of HPC system software to understand opportunities for performance optimization.

  14. PROJECT MANGEMENT PLAN EXAMPLES Policy & Operational Decisions, Assumptions

    Office of Environmental Management (EM)

    Policy & Operational Decisions, Assumptions and Strategies Examples 1 & 2 Example 1 1.0 Summary The 322-M Metallurgical Laboratory is currently categorized as a Radiological Facility. It is inactive with no future DOE mission. In May of 1998 it was ranked Number 45 in the Inactive Facilities Risk Ranking database which the Facilities Decommissioning Division maintains. A short-term surveillance and maintenance program is in-place while the facility awaits final deactivation. Completion

  15. Preparation plan, preliminary safety documentation, tank farm restoration and safe operations, Project W-314

    SciTech Connect (OSTI)

    Kidder, R.J.

    1994-10-20

    This preparation plan is developed to establish planning for the preliminary safety documentation for Project W-314, {open_quotes}Tank Farm Restoration and Safe Operations.{close_quotes}

  16. Operational and Environmental Monitoring Within a Three-Mile Radius of Project Rulison

    Office of Legacy Management (LM)

    FIRST QUARTER 20 08 REPORT Operational and Environmental Monitoring Within a Three-Mile Radius of Project Rulison Prepared by: A U G U S T 2 0 0 8 FIRST QUARTER 2008 REPORT OPERATIONAL AND ENVIRONMENTAL MONITORING WITHIN A THREE-MILE RADIUS OF PROJECT RULISON Prepared for: Noble Energy Production, Inc. Prepared by: URS Corporation 8181 East Tufts Avenue Denver, CO 80237 August 12, 2008 First Quarter 2008 Report August 2008 i TABLE OF CONTENTS Page 1 Introduction

  17. Database Aids Building Owners and Operators in Energy-Efficiency Project

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Decision Making | Department of Energy Database Aids Building Owners and Operators in Energy-Efficiency Project Decision Making Database Aids Building Owners and Operators in Energy-Efficiency Project Decision Making September 23, 2013 - 12:00am Addthis In June 2013, the Building Technologies Office launched the Buildings Performance Database (BPD). Currently, residential and commercial buildings account for approximately 70% of electricity consumption in the United States. One of the

  18. EA-2014: Emergency Operations Center Project; Oak Ridge, TN | Department of

    Office of Environmental Management (EM)

    Energy 4: Emergency Operations Center Project; Oak Ridge, TN EA-2014: Emergency Operations Center Project; Oak Ridge, TN Summary In this Environmental Assessment (EA), the National Nuclear Security Administration (NNSA) proposes to design and build a new emergency response facility to support the Y-12 National Security Complex (Y-12) missions. The proposed action would consolidate the Plant Shift Superintendent's (PSS) Office, the Emergency Command Center (ECC), the Technical Support Center

  19. EEG operational radiation surveillance of the WIPP Project during 2001

    SciTech Connect (OSTI)

    Gray, Donald H.; Ballard, Sally C.; Channell, James K.

    2002-12-31

    The Environmental Evaluation Group (EEG) has measured the levels of 241Am, 238Pu, 239/240Pu, 137Cs, and 90Sr in samples of air and water collected at and in the vicinity of the U. S. Department of Energys (DOE) Waste Isolation Pilot Plant (WIPP) during 2001. The WIPP received the first shipment of waste in March 1999 and became operational at that time. The EEG has compared these levels to those measured in the preoperational phase, prior to receipt of waste, as well as to the results of other monitoring organizations and to the U. S. Environmental Protection Agency (EPA) dose standards established for the WIPP at 40 CFR 191, Subpart A, and, by an agreement between the DOE and the EPA, at 40 CFR 61, Subpart H. Based on these analyses and applying a t test for significant differences for normally-distributed data (Taylor 1987), or analysis of variance (ANOVA) for non-normal data, the EEG concludes that: 1. Three measurements of radionuclides in the environment around WIPP during 2001 were different from the preoperational baseline levels. Only two of these 241Am in both the Loving and WIPP3 low volume air sampler (LVAS) samples, first quarter and second quarter, respectively exceeded the minimum detectable activity (MDA). These measurements were carefully investigated, but no clearly assignable cause was discovered. No measurements of 241Am in effluent air from the WIPP underground exceeded the action level, and converting the highest LVAS measured concentration to radiation dose yielded a committed dose of much less than 1% of the limit allowable under the EPA standard. 2. Comparison of the EEGs 2001 results with those of other monitoring organizations revealed two sets of measurements which did not agree. One set 241Am in surface water was found to be in agreement with the corresponding EEG baseline. The other 90Sr in groundwater was probably a result of 226

  20. Philadelphia gas works medium-Btu coal gasification project: capital and operating cost estimate, financial/legal analysis, project implementation

    SciTech Connect (OSTI)

    Not Available

    1981-12-01

    This volume of the final report is a compilation of the estimated capital and operating costs for the project. Using the definitive design as a basis, capital and operating costs were developed by obtaining quotations for equipment delivered to the site. Tables 1.1 and 1.2 provide a summary of the capital and operating costs estimated for the PGW Coal Gasification Project. In the course of its Phase I Feasibility Study of a medium-Btu coal-gas facility, Philadelphia Gas Works (PGW) identified the financing mechanism as having great impact on gas cost. Consequently, PGW formed a Financial/Legal Task Force composed of legal, financial, and project analysis specialists to study various ownership/management options. In seeking an acceptable ownership, management, and financing arrangement, certain ownership forms were initially identified and classified. Several public ownership, private ownership, and third party ownership options for the coal-gas plant are presented. The ownership and financing forms classified as base alternatives involved tax-exempt and taxable financing arrangements and are discussed in Section 3. Project implementation would be initiated by effectively planning the methodology by which commercial operation will be realized. Areas covered in this report are sale of gas to customers, arrangements for feedstock supply and by-product disposal, a schedule of major events leading to commercialization, and a plan for managing the implementation.

  1. CRAD, Conduct of Operations- Oak Ridge National Laboratory TRU ALPHA LLWT Project

    Broader source: Energy.gov [DOE]

    A section of Appendix C to DOE G 226.1-2 "Federal Line Management Oversight of Department of Energy Nuclear Facilities." Consists of Criteria Review and Approach Documents (CRADs) used for a November, 2003 assessment of the Conduct of Operations Program portion of an Operational Readiness Review of the Oak Ridge National Laboratory, TRU ALPHA LLWT Project.

  2. BP Exploration`s Pompano subsea development: Operational strategy for a subsea project

    SciTech Connect (OSTI)

    Clarke, D.G.; Cordner, J.P.

    1996-12-31

    On a platform, facility modifications to cope with unexpected operating conditions or unanticipated problems may be made relatively easily at moderate cost. In contrast, subsea systems are placed on the seabed often beyond diver depth and are difficult if not impossible to retrieve or modify. Consequently the design must be optimized up front and have sufficient inherent flexibility to cope with the unexpected. It is therefore critical to develop an operational strategy in conjunction with suppliers, designers and operational staff, concurrently with the design. Input from Operations personnel is necessary from project conception throughout detailed design, fabrication, system integrating testing, installation and commissioning. This paper discusses BP Exploration`s work on the Pompano subsea project in the Gulf of Mexico and addresses many of the practical aspects in which Operations staff need to become involved with throughout a subsea project to ensure a problem free start-up and operation. It will provide a useful guide for Operations groups involved in the planning and operation of a subsea development

  3. Optimizing hourly hydro operations at the Salt Lake City Area Integrated Projects

    SciTech Connect (OSTI)

    Veselka, T.D.; Hamilton, S.; McCoy, J.

    1995-10-01

    The Salt Lake City Area (SLCA) office of the Western Area Power Administration (Western) is responsible for marketing the capacity and energy generated by the Colorado River Storage, Collbran, and Rio Grande hydropower projects. These federal resources are collectively called the Salt Lake City Area Integrated Projects (SLCA/IP). In recent years, stringent operational limitations have been placed on several of these hydropower plants including the Glen Canyon Dam, which accounts for approximately 80% of the SLCA/IP resources. Operational limitations on SLCA/IP hydropower plants continue to evolve as a result of decisions currently being made in the Glen Canyon Dam Environmental Impact Statement (EIS) and the Power Marketing EIS. The Hydro LP (Linear Program) model, which was developed by Argonne National Laboratory (ANL), was used to analyze a broad range of issues associated with many possible future operational restrictions at SLCA/IP power plants. With technical assistance from Western, the Hydro LP model was configured to simulate hourly power plant operations for weekly periods with the objective of maximizing Western`s net revenues. The model considers hydropower operations for the purpose of serving SLCA firm loads, loads for special projects, Inland Power Pool (IPP) operating reserve requirements, and Western`s purchasing programs. The model estimates hourly SLCA/IP generation and spot market activities. For this paper, hourly SLCA/IP hydropower plant generation was simulated under three operational scenarios and three hydropower conditions. For each scenario an estimate of Western`s net revenue was computed.

  4. Conceptual design report for tank farm restoration and safe operations, project W-314

    SciTech Connect (OSTI)

    Briggs, S.R., Westinghouse Hanford

    1996-05-02

    This Conceptual Design Report (CDR) presents the conceptual level design approach that satisfies the established technical requirements for Project W-314, `Tank Farm Restoration and Safe Operations.` The CDR also addresses the initial cost and schedule baselines for performing the proposed Tank Farm infrastructure upgrades. The scope of this project includes capital improvements to Hanford`s existing tank farm facilities(primarily focused on Double- Shell Tank Farms) in the areas of instrumentation/control, tank ventilation, waste transfer, and electrical systems.

  5. Operational and Environmental Monitoring Within a Three-Mile Radius of Project Rulison

    Office of Legacy Management (LM)

    THIRD QUARTER 20 08 REPORT Operational and Environmental Monitoring Within a Three-Mile Radius of Project Rulison Prepared by: M A R C H 2 0 0 9 THIRD QUARTER 2008 REPORT OPERATIONAL AND ENVIRONMENTAL MONITORING WITHIN A THREE-MILE RADIUS OF PROJECT RULISON Prepared for: Noble Energy Inc. EnCana Oil & Gas (USA) Inc. Williams Production RMT Inc. Prepared by: URS Corporation 8181 East Tufts Avenue Denver, CO 80237 March 16, 2009 Rulison Third Quarter 2008 Report March 2009 i TABLE OF CONTENTS

  6. Operational and Environmental Monitoring Within a Three-Mile Radius of Project Rulison

    Office of Legacy Management (LM)

    FOURTH QUARTER 20 08 REPORT Operational and Environmental Monitoring Within a Three-Mile Radius of Project Rulison F F Prepared by: M A R C H 2 0 0 9 FOURTH QUARTER 2008 REPORT OPERATIONAL AND ENVIRONMENTAL MONITORING WITHIN A THREE-MILE RADIUS OF PROJECT RULISON Prepared for: Noble Energy Inc. EnCana Oil & Gas (USA) Inc. Williams Production RMT Inc. Prepared by: URS Corporation 8181 East Tufts Avenue Denver, CO 80237 March 26, 2009 Rulison Fourth Quarter 2008 Report March 2009 i TABLE OF

  7. Optimizing hourly hydro operations at the Salt Lake City Area integrated projects

    SciTech Connect (OSTI)

    Veselka, T.D.; Hamilton, S.; McCoy, J.

    1995-06-01

    The Salt Lake City Area (SLCA) office of the Western Area Power Administration (Western) is responsible for marketing the capacity and energy generated by the Colorado Storage, Collbran, and Rio Grande hydropower projects. These federal resources are collectively called the Salt Lake City Area Integrated Projects (SLCA/IP). In recent years, stringent operational limitations have been placed on several of these hydropower plants including the Glen Canyon Dam, which accounts for approximately 80% of the SLCA/IP resources. Operational limitations on SLCA/IP hydropower plants continue to evolve as a result of decisions currently being made in the Glen Canyon Dam Environmental Impact Statement (EIS) and the Power Marketing EIS. To analyze a broad range of issues associated with many possible future operational restrictions, Argonne National Laboratory (ANL), with technical assistance from Western has developed the Hydro LP (Linear Program) Model. This model simulates hourly operations at SLCA/IP hydropower plants for weekly periods with the objective of maximizing Western`s net revenues. The model considers hydropower operations for the purpose of serving SLCA firm loads, loads for special projects, Inland Power Pool (IPP) spinning reserve requirements, and Western`s purchasing programs. The model estimates hourly SLCA/IP generation and spot market activities. For this paper, hourly SLCA/IP hydropower plant generation is simulated under three operational scenarios and three hydropower conditions. For each scenario an estimate of Western`s net revenue is computed.

  8. Expansion of Michigan EOR Operations Using Advanced Amine Technology at a 600 MW Project Wolverine Carbon Capture and Storage Project

    SciTech Connect (OSTI)

    H Hoffman; Y kishinevsky; S. Wu; R. Pardini; E. Tripp; D. Barnes

    2010-06-16

    Wolverine Power Supply Cooperative Inc, a member owned cooperative utility based in Cadillac Michigan, proposes to demonstrate the capture, beneficial utilization and storage of CO{sub 2} in the expansion of existing Enhanced Oil Recovery operations. This project is being proposed in response to the US Department of Energy Solicitation DE-FOA-0000015 Section III D, 'Large Scale Industrial CCS projects from Industrial Sources' Technology Area 1. The project will remove 1,000 metric tons per day of CO{sub 2} from the Wolverine Clean Energy Venture 600 MW CFB power plant owned and operated by WPC. CO{sub 2} from the flue gas will be captured using Hitachi's CO{sub 2} capture system and advanced amine technology. The capture system with the advanced amine-based solvent supplied by Hitachi is expected to significantly reduce the cost and energy requirements of CO{sub 2} capture compared to current technologies. The captured CO{sub 2} will be compressed and transported for Enhanced Oil Recovery and CO{sub 2} storage purposes. Enhanced Oil Recovery is a proven concept, widely used to recover otherwise inaccessible petroleum reserves. While post-combustion CO{sub 2} capture technologies have been tested at the pilot scale on coal power plant flue gas, they have not yet been demonstrated at a commercial scale and integrated with EOR and storage operations. Amine-based CO{sub 2} capture is the leading technology expected to be available commercially within this decade to enable CCS for utility and industrial facilities firing coal and waste fuels such as petroleum coke. However, traditional CO{sub 2} capture process utilizing commercial amine solvents is very energy intensive for regeneration and is also susceptible to solvent degradation by oxygen as well as SOx and NO{sub 2} in the flue gas, resulting in large operating costs. The large volume of combustion flue gas with its low CO{sub 2} concentration requires large equipment sizes, which together with the highly corrosive nature of the typical amine-based separation process leads to high plant capital investment. According to recent DOE-NETL studies, MEA-based CCS will increase the cost of electricity of a new pulverized coal plant by 80-85% and reduce the net plant efficiency by about 30%. Non-power industrial facilities will incur similar production output and efficiency penalties when implementing conventional carbon capture systems. The proposed large scale demonstration project combining advanced amine CO{sub 2} capture integrated with commercial EOR operations significantly advances post-combustion technology development toward the DOE objectives of reducing the cost of energy production and improving the efficiency of CO{sub 2} Capture technologies. WPC has assembled a strong multidisciplinary team to meet the objectives of this project. WPC will provide the host site and Hitachi will provide the carbon capture technology and advanced solvent. Burns and Roe bring expertise in overall engineering integration and plant design to the team. Core Energy, an active EOR producer/operator in the State of Michigan, is committed to support the detailed design, construction and operation of the CO{sub 2} pipeline and storage component of the project. This team has developed a Front End Engineering Design and Cost Estimate as part of Phase 1 of DOE Award DE-FE0002477.

  9. Phase 5 storage (Project W-112) Central Waste Complex operational readiness review, final report

    SciTech Connect (OSTI)

    Wight, R.H.

    1997-05-30

    This document is the final report for the RFSH conducted, Contractor Operational Readiness Review (ORR) for the Central Waste Complex (CWC) Project W-112 and Interim Safety Basis implementation. As appendices, all findings, observations, lines of inquiry and the implementation plan are included.

  10. Test and evaluation plan for Project W-314 tank farm restoration and safe operations

    SciTech Connect (OSTI)

    Hays, W.H.

    1998-06-25

    The ``Tank Farm Restoration and Safe Operations`` (TFRSO), Project W-314 will restore and/or upgrade existing Hanford Tank Farm facilities and systems to ensure that the Tank Farm infrastructure will be able to support near term TWRS Privatization`s waste feed delivery and disposal system and continue safe management of tank waste. The capital improvements provided by this project will increase the margin of safety for Tank Farms operations, and will aid in aligning affected Tank Farm systems with compliance requirements from applicable state, Federal, and local regulations. Secondary benefits will be realized subsequent to project completion in the form of reduced equipment down-time, reduced health and safety risks to workers, reduced operating and maintenance costs, and minimization of radioactive and/or hazardous material releases to the environment. The original regulatory (e.g., Executive Orders, WACS, CFRS, permit requirements, required engineering standards, etc.) and institutional (e.g., DOE Orders, Hanford procedures, etc.) requirements for Project W-314 were extracted from the TWRS S/RIDs during the development of the Functions and Requirements (F and Rs). The entire family of requirements were then validated for TWRS and Project W-314. This information was contained in the RDD-100 database and used to establish the original CDR. The Project Hanford Management Contract (PHMC) team recognizes that safety, quality, and cost effectiveness in the Test and Evaluation (T and E) program is achieved through a planned systematic approach to T and E activities. It is to this end that the Test and Evaluation Plan (TEP) is created. The TEP for the TFRSO Project, was developed based on the guidance in HNF-IP-0842, and the Good Practice Guide GPG-FM-005, ``Test and Evaluation,`` which is derived from DOE Order 430.1, ``Life Cycle Asset Management.`` It describes the Test and Evaluation program for the TFRSO project starting with the definitive design phase and ending with operational testing and turn-over of the upgraded systems to Tank Farm Operations. The TEP will be updated as required to reflect the appropriate test acceptance and startup requirements to support design, construction, turnover and initial operations.

  11. Nez Perce Tribal Hatchery Project; Operations and Maintenance and Planning and Design, 2002 Annual Report.

    SciTech Connect (OSTI)

    Larson, Roy Edward; Walker, Grant W.; Penney, Aaron K.

    2005-12-01

    This report fulfills the contract obligations based on the Statement of Work (SOW) for the project as contracted with Bonneville Power Administration (BPA). Nez Perce Tribal Hatchery (NPTH) Year-2002 annual report combines information from two contracts with a combined value of $3,036,014. Bonneville Power Administration identifies them as follows; (1) Part I--Operations and Maintenance--Project No. 1983-350-00, Contract No. 4504, and $2,682,635 which includes--Equipment costs of $1,807,105. (2) Part II--Planning and Design--Project No. 1983-35-04, Contract No. 4035, $352,379 for Clearwater Coho Restoration Master Plan development Based on NPPC authorization for construction and operation of NPTH, the annual contracts were negotiated for the amounts shown above under (1) and (2). Construction contracts were handled by BPA until all facilities are completed and accepted.

  12. Solid Waste Operations Complex W-113, Detail Design Report (Title II). Volume 4: Project cost estimate

    SciTech Connect (OSTI)

    1995-09-01

    The Solid Waste Retrieval Facility--Phase 1 (Project W113) will provide the infrastructure and the facility required to retrieve from Trench 04, Burial ground 4C, contact handled (CH) drums and boxes at a rate that supports all retrieved TRU waste batching, treatment, storage, and disposal plans. This includes (1) operations related equipment and facilities, viz., a weather enclosure for the trench, retrieval equipment, weighing, venting, obtaining gas samples, overpacking, NDE, NDA, shipment of waste and (2) operations support related facilities, viz., a general office building, a retrieval staff change facility, and infrastructure upgrades such as supply and routing of water, sewer, electrical power, fire protection, roads, and telecommunication. Title I design for the operations related equipment and facilities was performed by Raytheon/BNFL, and that for the operations support related facilities including infrastructure upgrade was performed by KEH. These two scopes were combined into an integrated W113 Title II scope that was performed by Raytheon/BNFL. This volume represents the total estimated costs for the W113 facility. Operating Contractor Management costs have been incorporated as received from WHC. The W113 Facility TEC is $19.7 million. This includes an overall project contingency of 14.4% and escalation of 17.4%. A January 2001 construction contract procurement start date is assumed.

  13. 90 MW build/own/operate gas turbine combined cycle cogeneration project with sludge drying plant

    SciTech Connect (OSTI)

    Schroppe, J.T.

    1986-04-01

    This paper will discuss some of the unique aspects of a build/own/operate cogeneration project for an oil refinery in which Foster Wheeler is involved. The organization is constructing a 90 MW plant that will supply 55 MW and 160,000 lb/hr of 600 psi, 700F steam to the Tosco Corporation's 130,000 bd Avon Oil Refinery in Martinez, California. (The refinery is located about 45 miles northeast of San Francisco.) Surplus power production will be sold to the local utility, Pacific Gas and Electric Co. (PG and E). Many of the aspects of this project took on a different perspective, since the contractor would build, own and operate the plant.

  14. EMAB Briefing on Capital Assets Projects and Operations Activities Presentation by Mark Gilbertson

    Office of Environmental Management (EM)

    Capital Asset Projects and Operations Activities www.em.doe.gov 1 Presented to Environmental Management Advisory Boards Mark Gilbertson Deputy Assistant Secretary for Site Restoration Office of Environmental Management May 31, 2012 We reduce risks and protect our workers, our communities and the environment through cleanup Our work is urgent and essential to the health and economic vitality of our communities and the nation and positions our Sites for future missions and use Our mission is not

  15. Operational Awareness Review of the Hanford Sludge Treatment Project, April 2011

    Office of Environmental Management (EM)

    HSS Independent Activity Report - Rev. 0 Report Number: HIAR-RL-2011-04-07 Site: DOE-Richland Operations Office Subject: Office of Enforcement and Oversight's Office of Safety and Emergency Management Evaluations Activity Report for the Sludge Treatment Project Dates of Activity : 11/17/2010 - 04/07/2011 Report Preparer: Jake Wechselberger Activity Description/Purpose: The U.S. Department of Energy's Office of Enforcement and Oversight, within the Office of Health, Safety and Security (HSS),

  16. Operating experience during high-level waste vitrification at the West Valley Demonstration Project

    SciTech Connect (OSTI)

    Valenti, P.J.; Elliott, D.I.

    1999-01-01

    This report provides a summary of operational experiences, component and system performance, and lessons learned associated with the operation of the Vitrification Facility (VF) at the West Valley Demonstration Project (WVDP). The VF was designed to convert stored high-level radioactive waste (HLW) into a stable waste form (borosilicate glass) suitable for disposal in a federal repository. Following successful completion on nonradioactive test, HLW processing began in July 1995. Completion of Phase 1 of HLW processing was reached on 10 June 1998 and represented the processing of 9.32 million curies of cesium-137 (Cs-137) and strontium-90 (Sr-90) to fill 211 canisters with over 436,000 kilograms of glass. With approximately 85% of the total estimated curie content removed from underground waste storage tanks during Phase 1, subsequent operations will focus on removal of tank heel wastes.

  17. DOE - Office of Legacy Management -- TA-1 Manhattan Laboratory...

    Office of Legacy Management (LM)

    Technical Area LASL LANL NM.11-1 NM.11-2 NM.11-3 Location: Los Alamos , New Mexico NM.11-3 Evaluation Year: 1985 NM.11-1 Site Operations: Nuclear weapons research and development. ...

  18. Operations start and shipments begin

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Operations start and shipments begin Y-12's formal operational start date of record is January 27, 1944. George Robinson, in The Oak Ridge Story, tells us that on that date, "a select group of Manhattan [Engineer] District personnel and officials of Stone and Webster and the Tennessee Eastman Corporation...witnessed the epochal first 'run' of uranium 235 on a mass basis by the electromagnetic method." Even this first successful production run had its share of frustrating problems.

  19. Summary of operations and performance of the Murdock site restoration project in 2008.

    SciTech Connect (OSTI)

    LaFreniere, L. M.; Environmental Science Division

    2009-06-04

    This document summarizes the performance of the groundwater and surface water restoration systems installed by the Commodity Credit Corporation of the U.S. Department of Agriculture (CCC/USDA) at the former CCC/USDA grain storage facility in Murdock, Nebraska, during the third full year of system operation, from January 1 through December 31, 2008. Performance in June 2005 through December 2007 was reported previously (Argonne 2007, 2008). In the Murdock project, several innovative technologies are being used to remove carbon tetrachloride contamination from a shallow aquifer underlying the town, as well as from water naturally discharged to the surface at the headwaters of a small creek (a tributary to Pawnee Creek) north of the town (Figure 1.1). The restoration activities at Murdock are being conducted by the CCC/USDA as a non-time-critical removal action under the regulatory authority and supervision of the U.S. Environmental Protection Agency (EPA), Region VII. Argonne National Laboratory assisted the CCC/USDA by providing technical oversight for the restoration effort and facilities during this review period. Included in this report are the results of all sampling and monitoring activities performed in accord with the EPA-approved Monitoring Plan for this site (Argonne 2006), as well as additional investigative activities conducted during the review period. The annual performance reports for the Murdock project assemble information that will become part of the five-year review and evaluation of the remediation effort. This review will occur in 2010. This document presents overviews of the treatment facilities (Section 2) and site operations and activities (Section 3), then describes the groundwater, surface water, vegetation, and atmospheric monitoring results (Section 4) and modifications and costs during the review period (Section 5). Section 6 summarizes the current period of operation. A gallery of photographs of the Murdock project is in Appendix A.

  20. Optimizing Installation, Operation, and Maintenance at Offshore Wind Projects in the United States

    Broader source: Energy.gov [DOE]

    For the United States to ensure that the substantial rollout of offshore wind energy projects envisioned by the DOE is carried out in an efficient and cost-effective manner, it is important to observe the current and emerging practices in the international offshore wind energy industry. In this manner, the United States can draw from the experience already gained around the world, combined with experience from the sizeable U.S. land-based wind industry, to develop a strong offshore wind sector. The work detailed in this report will support that learning curve by enabling optimization of the cost-effectiveness of installation, operation, and maintenance activities for offshore wind farms.

  1. EA-0930: Facility Operations at the U.S. DOE Grand Junction Projects Office, Grand Junction, Colorado

    Broader source: Energy.gov [DOE]

    This EA evaluates the environmental impacts of the proposal to expand and upgrade the U.S. Department of Energy's Grand Junction Projects Office facilities and operations in Grand Junction, Colorado.

  2. Summary of operations and performance of the Murdock site restoration project in 2007.

    SciTech Connect (OSTI)

    LaFreniere, L. M.; Environmental Science Division

    2008-06-03

    This document summarizes the performance of the groundwater and surface water restoration systems installed by the Commodity Credit Corporation of the U.S. Department of Agriculture (CCC/USDA) at the former CCC/USDA grain storage facility in Murdock, Nebraska, during the second full year of system operation, from January 1 through December 31, 2007. Performance in June 2005 through December 2006 was reported previously (Argonne 2007). In the Murdock project, several innovative technologies are being used to remove carbon tetrachloride contamination from a shallow aquifer underlying the town, as well as from water naturally discharged to the surface at the headwaters of a small creek (a tributary to Pawnee Creek) north of the town (Figure 1.1). The restoration activities at Murdock are being conducted by the CCC/USDA as a non-time-critical removal action under the regulatory authority and supervision of the U.S. Environmental Protection Agency (EPA), Region VII. Argonne National Laboratory assisted the CCC/USDA by providing technical oversight for the restoration effort and facilities during this review period. Included in this report are the results of all sampling and monitoring activities performed in accord with the EPA-approved Monitoring Plan for this site (Argonne 2006), as well as additional investigative activities conducted during the review period. The annual performance reports for the Murdock project assemble information that will become part of the five-year review and evaluation of the remediation effort. This review will occur in 2010. This document presents overviews of the treatment facilities (Section 2) and site operations and activities (Section 3), then describes the groundwater, surface water, vegetation, and atmospheric monitoring results (Section 4) and modifications and costs during the review period (Section 5). Section 6 summarizes the current period of operation. A gallery of photographs of the Murdock project is in Appendix A. A brief videorecording of the trees in high-wind conditions is on the compact disc (CD) inside the back cover of this document.

  3. Project Management Plan/Progress Report UT/GTKS Training Program Development for Commercial Building Operators

    SciTech Connect (OSTI)

    None, None

    2013-03-31

    Universidad del Turabo (UT), in a collaborative effort with Global Turn Key Services, Inc. (GTKS), proposed to develop a training program and a commercialization plan for the development of Commercial Building Operators (CBOs). The CBOs will operate energy efficient buildings to help maintain existing buildings up to their optimal energy performance level, and ensure that net-zero-energy buildings continuously operate at design specifications, thus helping achieve progress towards meeting BTP Strategic Goals of creating technologies and design approaches that enable net-zero-energy buildings at low incremental costs by 2025. The proposed objectives were then: (1) Develop a Commercial Building Operator (CBO) training program and accreditation that will in turn provide a certification to participants recognized by Accreditation Boards such as the North American Board of Certified Energy Practitioners (NABCEP) and Leadership in Energy & Environmental Designs (LEED). (2) Develop and implement a commercialization and sustainability plan that details marketing, deployment, financial characterization, job placement, and other goals required for long-term sustainability of the project after the funding period. (3) After program development and deployment, provide potential candidates with the knowledge and skill sets to obtain employment in the commercial building green energy (net-zero-energy building) job market. The developed CBO training program will focus on providing skills for participants, such as displaced and unemployed workers, to enter the commercial building green energy (net-zeroenergy building) job market. This course was designed to allow a participant with minimal to no experience in commercial building green technology to obtain the required skill sets to enter the job market in as little as 12 weeks of intensive multi-faceted learning. After completion of the course, the CBO staff concluded the participant will meet minimum established accreditation standards established by UT and will complete the contact hours required of training to apply to the Certification on Energy Management (CEM) offered by the Association of Energy Engineers (AEE). The CBO training program consists of a combination of theory (classroom), online & computer simulation, laboratory & hands on (onsite) training lessons. The training is addressed four basic learning elements: (1) Learn the Technology; (2) Practice Skills with hands-on the Energy Simulation Builder program; (3) Final Project and Presentation; and, (4) Accreditation and Certifications.

  4. EA-1903: Kansas State University Zond Wind Energy Project, Manhattan, Kansas

    Broader source: Energy.gov [DOE]

    This EA evaluates the potential environmental impacts of a proposal to use Congressional Directed funds to develop the Great Plains Wind Energy Consortium aimed at increasing the penetration of wind energy via distributed wind power generation throughout the region.

  5. Manhattan Project: A Tentative Decision to Build the Bomb<!--Include title

    Office of Scientific and Technical Information (OSTI)

    of the page here--> President Franklin Roosevelt's note to Vannevar Bush giving Bush the tentative go-ahead to build the atomic bomb. A TENTATIVE DECISION TO BUILD THE BOMB Washington, D.C.(1941-1942) Events > Early Government Support, 1939-1942 Einstein's Letter, 1939 Early Uranium Research, 1939-1941 Piles and Plutonium, 1939-1941 Reorganization and Acceleration, 1940-1941 The MAUD Report, 1941 A Tentative Decision to Build the Bomb, 1941-1942 Vannevar Bush moved swiftly to take

  6. Manhattan Project: Final Approval to Build the Bomb, Washington, D.C.,

    Office of Scientific and Technical Information (OSTI)

    December 1942 President Roosevelt signs declaration of war with Japan, December 8, 1941. FINAL APPROVAL TO BUILD THE BOMB (Washington, D.C., December 1942) Events > Difficult Choices, 1942 More Uranium Research, 1942 More Piles and Plutonium, 1942 Enter the Army, 1942 Groves and the MED, 1942 Picking Horses, November 1942 Final Approval to Build the Bomb, December 1942 Anxious as he was to get moving, Leslie Groves decided to make one final quality control check. On November 18, 1942,

  7. Manhattan Project: Potsdam and the Final Decision to Use the Bomb, July

    Office of Scientific and Technical Information (OSTI)

    1945 Joseph Stalin, Harry Truman, and Winston Churchill at the Potsdam Conference, July 1945 POTSDAM AND THE FINAL DECISION TO USE THE BOMB (Potsdam, Germany, July 1945) Events > Dawn of the Atomic Era, 1945 The War Enters Its Final Phase, 1945 Debate Over How to Use the Bomb, Late Spring 1945 The Trinity Test, July 16, 1945 Safety and the Trinity Test, July 1945 Evaluations of Trinity, July 1945 Potsdam and the Final Decision to Bomb, July 1945 The Atomic Bombing of Hiroshima, August 6,

  8. Maintenance and operations contractor plan for transition to the project Hanford management contract (PHMC)

    SciTech Connect (OSTI)

    Waite, J.L.

    1996-04-12

    This plan has been developed by Westinghouse Hanford Company (WHC), and its subcontractors ICF Kaiser Hanford (ICF KH) and BCS Richland, Inc. (BCSR), at the direction of the US Department of Energy (DOE), Richland Operations Office (RL). WHC and its subcontractors are hereafter referred to as the Maintenance and Operations (M and O) Contractor. The plan identifies actions involving the M and O Contractor that are critical to (1) prepare for a smooth transition to the Project Hanford Management Contractor (PHMC), and (2) support and assist the PHMC and RL in achieving transition as planned, with no or minimal impact to ongoing baseline activities. The plan is structured around two primary phases. The first is the pre-award phase, which started in mid-February 1996 and is currently scheduled to be completed on June 1, 1996, at which time the contract is currently planned to be awarded. The second is the follow-on four-month post-award phase from June 1, 1996, until October 1, 1996. Considering the magnitude and complexity of the scope of work being transitioned, completion in four months will require significant effort by all parties. To better ensure success, the M and O Contractor has developed a pre-award phase that is intended to maximize readiness for transition. Priority is given to preparation for facility assessments and processing of personnel, as these areas are determined to be on the critical path for transition. In addition, the M and O Contractor will put emphasis during the pre-award phase to close out open items prior to contract award, to include grievances, employee concerns, audit findings, compliance issues, etc.

  9. After More Than 20 Years Operating, Hanford’s Soil Vapor Extraction Project Nears Completion

    Broader source: Energy.gov [DOE]

    RICHLAND, Wash. – Hanford workers are fast approaching the successful completion of a long-term cleanup project.

  10. Management and operating contractor plan for transition to the project Hanford Management Contractor

    SciTech Connect (OSTI)

    Waite, J.L., Westinghouse Hanford

    1996-06-27

    This is Revision 1 to the M{ampersand}O Contractor Plan for Transition to the Project Hanford Management Contractor.

  11. Spent Nuclear Fuel (SNF) Project Cold Vacuum Drying (CVD) Facility Operations Manual

    SciTech Connect (OSTI)

    IRWIN, J.J.

    2000-11-18

    The mission of the Spent Nuclear Fuel (SNF) Project Cold Vacuum Drying Facility (CVDF) is to achieve the earliest possible removal of free water from Multi-Canister Overpacks (MCOs). The MCOs contain metallic uranium SNF that have been removed from the 100K Area fuel storage water basins (i.e., the K East and K West Basins) at the US. Department of Energy Hanford Site in Southeastern Washington state. Removal of free water is necessary to halt water-induced corrosion of exposed uranium surfaces and to allow the MCOs and their SNF payloads to be safely transported to the Hanford Site 200 East Area and stored within the SNF Project Canister Storage Building (CSB). The CVDF is located within a few hundred yards of the basins, southwest of the 165KW Power Control Building and the 105KW Reactor Building. The site area required for the facility and vehicle circulation is approximately 2 acres. Access and egress is provided by the main entrance to the 100K inner area using existing roadways. The CVDF will remove free. water from the MCOs to reduce the potential for continued fuel-water corrosion reactions. The cold vacuum drying process involves the draining of bulk water from the MCO and subsequent vacuum drying. The MCO will be evacuated to a pressure of 8 torr or less and backfilled with an inert gas (helium). The MCO will be sealed, leak tested, and then transported to the CSB within a sealed shipping cask. (The MCO remains within the same shipping Cask from the time it enters the basin to receive its SNF payload until it is removed from the Cask by the CSB MCO handling machine.) The CVDF subproject acquired the required process systems, supporting equipment, and facilities. The cold vacuum drying operations result in an MCO containing dried fuel that is prepared for shipment to the CSB by the Cask transportation system. The CVDF subproject also provides equipment to dispose of solid wastes generated by the cold vacuum drying process and transfer process water removed from the MCO back to the K Basins.

  12. SLUDGE TREATMENT PROJECT ENGINEERED CONTAINER RETRIEVAL AND TRANSFER SYSTEM PRELMINARY DESIGN HAZARD AND OPERABILITY STUDY

    SciTech Connect (OSTI)

    CARRO CA

    2011-07-15

    This Hazard and Operability (HAZOP) study addresses the Sludge Treatment Project (STP) Engineered Container Retrieval and Transfer System (ECRTS) preliminary design for retrieving sludge from underwater engineered containers located in the 105-K West (KW) Basin, transferring the sludge as a sludge-water slurry (hereafter referred to as 'slurry') to a Sludge Transport and Storage Container (STSC) located in a Modified KW Basin Annex, and preparing the STSC for transport to T Plant using the Sludge Transport System (STS). There are six, underwater engineered containers located in the KW Basin that, at the time of sludge retrieval, will contain an estimated volume of 5.2 m{sup 3} of KW Basin floor and pit sludge, 18.4 m{sup 3} of 105-K East (KE) Basin floor, pit, and canister sludge, and 3.5 m{sup 3} of settler tank sludge. The KE and KW Basin sludge consists of fuel corrosion products (including metallic uranium, and fission and activation products), small fuel fragments, iron and aluminum oxide, sand, dirt, operational debris, and biological debris. The settler tank sludge consists of sludge generated by the washing of KE and KW Basin fuel in the Primary Clean Machine. A detailed description of the origin of sludge and its chemical and physical characteristics can be found in HNF-41051, Preliminary STP Container and Settler Sludge Process System Description and Material Balance. In summary, the ECRTS retrieves sludge from the engineered containers and hydraulically transfers it as a slurry into an STSC positioned within a trailer-mounted STS cask located in a Modified KW Basin Annex. The slurry is allowed to settle within the STSC to concentrate the solids and clarify the supernate. After a prescribed settling period the supernate is decanted. The decanted supernate is filtered through a sand filter and returned to the basin. Subsequent batches of slurry are added to the STSC, settled, and excess supernate removed until the prescribed quantity of sludge is collected. The sand filter is then backwashed into the STSC. The STSC and STS cask are then inerted and transported to T Plant.

  13. Hydrothermal Testing of K Basin Sludge and N Reactor Fuel at Sludge Treatment Project Operating Conditions

    SciTech Connect (OSTI)

    Delegard, Calvin H.; Schmidt, Andrew J.; Thornton, Brenda M.

    2007-03-30

    The Sludge Treatment Project (STP), managed for the U. S. DOE by Fluor Hanford (FH), was created to design and operate a process to eliminate uranium metal from K Basin sludge prior to packaging for Waste Isolation Pilot Plant (WIPP). The STP process uses high temperature liquid water to accelerate the reaction, produce uranium dioxide from the uranium metal, and safely discharge the hydrogen. Under nominal process conditions, the sludge will be heated in pressurized water at 185°C for as long as 72 hours to assure the complete reaction (corrosion) of up to 0.25-inch diameter uranium metal pieces. Under contract to FH, the Pacific Northwest National Laboratory (PNNL) conducted bench-scale testing of the STP hydrothermal process in November and December 2006. Five tests (~50 ml each) were conducted in sealed, un-agitated reaction vessels under the hydrothermal conditions (e.g., 7 to 72 h at 185°C) of the STP corrosion process using radioactive sludge samples collected from the K East Basin and particles/coupons of N Reactor fuel also taken from the K Basins. The tests were designed to evaluate and understand the chemical changes that may be occurring and the effects that any changes would have on sludge rheological properties. The tests were not designed to evaluate engineering aspects of the process. The hydrothermal treatment affected the chemical and physical properties of the sludge. In each test, significant uranium compound phase changes were identified, resulting from dehydration and chemical reduction reactions. Physical properties of the sludge were significantly altered from their initial, as-settled sludge values, including, shear strength, settled density, weight percent water, and gas retention.

  14. UNITED STATE% ENGINEER OFFICE I" RaCLI MANHATTAN D' ISTRICT

    Office of Legacy Management (LM)

    =A-; _.__ - ._-.. w-1 -~ ,.. P..*e ,e.arzUE.m ~-~JuTm-&a- . . .~ _ UNITED STATE% ENGINEER OFFICE I" RaCLI MANHATTAN D' ISTRICT RLFSR TO ; I=. 0. eox a ,. STATJON J= N E W YORK, N. Y. ~~~tr.~et h % -j&2 Smg-J E" I, du da r"r~~~~e 4% bP&wQ I tlnatodt 3tut8a ~o~tra~t~~ Q.tYiQlaT,* Erar%by r&08, acthg tdwo*. ttra tm!wi~Qmd in tholr dartost ptmx&b~as t&q, #' pm OLIN tit-h you that yell shtikn, the l_aboq at&M.&~, tada, aatbioerg, ae+nt, JkdUtiar,

  15. Data Collection for Current U.S. Wind Energy Projects: Component Costs, Financing, Operations, and Maintenance; January 2011 - September 2011

    SciTech Connect (OSTI)

    Martin-Tretton, M.; Reha, M.; Drunsic, M.; Keim, M.

    2012-01-01

    DNV Renewables (USA) Inc. (DNV) used an Operations and Maintenance (O&M) Cost Model to evaluate ten distinct cost scenarios encountered under variations in wind turbine component failure rates. The analysis considers: (1) a Reference Scenario using the default part failure rates within the O&M Cost Model, (2) High Failure Rate Scenarios that increase the failure rates of three major components (blades, gearboxes, and generators) individually, (3) 100% Replacement Scenarios that model full replacement of these components over a 20 year operating life, and (4) Serial Failure Scenarios that model full replacement of blades, gearboxes, and generators in years 4 to 6 of the wind project. DNV selected these scenarios to represent a broad range of possible operational experiences. Also in this report, DNV summarizes the predominant financing arrangements used to develop wind energy projects over the past several years and provides summary data on various financial metrics describing those arrangements.

  16. Project Execution Plan, Waste Management Division, Nevada Operations Office, U.S. Department of Energy, April 2000

    SciTech Connect (OSTI)

    DOE /NV

    2000-04-01

    This plan addresses project activities encompassed by the U.S. Department of Energy/Nevada Operations Office Waste Management Division and conforms to the requirements contained in the ''Life Cycle Asset Management,'' U.S. Department of Energy Order O430.1A; the Joint Program Office Policy on Project Management in Support of DOE Order O430.1, and the Project Execution and Engineering Management Planning Guide. The plan also reflects the milestone philosophies of the Federal Facility Agreement and Consent Order, as agreed to by the state of Nevada; and traditional project management philosophies such as the development of life cycle costs, schedules, and work scope; identification of roles and responsibilities; and baseline management and controls.

  17. Functions and requirements for tank farm restoration and safe operations, Project W-314. Revision 3

    SciTech Connect (OSTI)

    Garrison, R.C.

    1995-02-01

    This Functions and Requirements document (FRD) establishes the basic performance criteria for Project W-314, in accordance with the guidance outlined in the letter from R.W. Brown, RL, to President, WHC, ``Tank Waste Remediation System (TWRS) Project Documentation Methodology,`` 94-PRJ-018, dated 3/18/94. The FRD replaces the Functional Design Criteria (FDC) as the project technical baseline documentation. Project W-314 will improve the reliability of safety related systems, minimize onsite health and safety hazards, and support waste retrieval and disposal activities by restoring and/or upgrading existing Tank Farm facilities and systems. The scope of Project W-314 encompasses the necessary restoration upgrades of the Tank Farms` instrumentation, ventilation, electrical distribution, and waste transfer systems.

  18. Wind-To-Hydrogen Project: Operational Experience, Performance Testing, and Systems Integration

    SciTech Connect (OSTI)

    Harrison, K. W.; Martin, G. D.; Ramsden, T. G.; Kramer, W. E.; Novachek, F. J.

    2009-03-01

    The Wind2H2 system is fully functional and continues to gather performance data. In this report, specifications of the Wind2H2 equipment (electrolyzers, compressor, hydrogen storage tanks, and the hydrogen fueled generator) are summarized. System operational experience and lessons learned are discussed. Valuable operational experience is shared through running, testing, daily operations, and troubleshooting the Wind2H2 system and equipment errors are being logged to help evaluate the reliability of the system.

  19. Project Profile: A Novel Storage Method for CSP Plants Allowing Operation at High Temperature

    Broader source: Energy.gov [DOE]

    City College of New York (CCNY), under the Thermal Storage FOA, is developing and testing a novel thermal storage method that allows operation at very high temperatures.

  20. Moab Project Exceeds 5 Years of Operations Without Lost-Time...

    Broader source: Energy.gov (indexed) [DOE]

    workers on the Moab Uranium Mill Tailings Remedial Action Project in Utah had a lost-time injury or illness. This represents roughly 2.2 million hours of safe work. Although the...

  1. FY 2014 Projects for Improving the Design, Construction, and Operation of Fossil Energy Systems

    Broader source: Energy.gov [DOE]

    In FY 2014, the U.S. Department of Energy selected 38 new projects from across the nation under the Crosscutting Research Program that target innovative concepts and technologies to improve...

  2. Programmatic agreement among the USDOE/RL Operations Office, the Advisory Council on Historic Preservation, and the WA State Historic Preservation Office for the maintenance, deactivation, alteration and demolition of the built environment on the Hanford Site, Washington

    SciTech Connect (OSTI)

    Lloyd, D.W.

    1997-08-01

    This Programmatic Agreement (PA) addresses the built environment (i.e., buildings and structures) constructed during the Manhattan Project and Cold War Era periods of Hanford`s operational history. As such it encompasses the years 1943 through 1990. The identification, evaluation, and treatment of buildings and historic archeological remains on the Hanford Site predating 1943 will be accomplished through Sections 800.4 through 800.6 of the Council`s regulations. This PA will be in effect from the date of signature until September 30, 2000. Completion of the Sitewide Treatment Plan established under this PA satisfies all Section 106 requirements for identification, evaluation, and treatment necessary for all undertakings, up to and including demolition which may affect Manhattan Project and Cold War Era properties. This PA may be extended if the Sitewide Treatment Plan has not been completed by the end of FY 2000. Identification, evaluation, and treatment of properties constructed on the Hanford Site after 1990 will be handled pursuant to the regulations in effect at the time such properties are eligible for review.

  3. Audit of Electrical System Construction Projects at the Nevada Operations Office, WR-B-97-01

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ELECTRICAL SYSTEM CONSTRUCTION PROJECTS AT THE NEVADA OPERATIONS OFFICE The Office of Inspector General wants to make the distribution of its reports as customer friendly and cost-effective as possible. Therefore, this report will be available electronically through the Internet five to seven days after publication at the following alternative addresses: Department of Energy Headquarters Gopher gopher.hr.doe.gov Department of Energy Headquarters Anonymous FTP vm1.hqadmin.doe.gov Department of

  4. DOE/EA-2008: Colorado River Storage Project Programmatic Operations and Maintenance Project; Coconino, Maricopa, Navajo, and Yavapai Counties (Arizona) and San Juan County (Utah)

    Broader source: Energy.gov [DOE]

    Western Area Power Administration is preparing an EA that assesses the potential environmental impacts of Westerns programmatic operations and management (O&M) process and an integrated vegetation management (IVM) program on the Colorado River Storage Project System. O&M activities would consist of aerial and ground patrols, regular and preventive maintenance, inspections and repairs, and road repair. The IVM program would remove vegetation to protect facilities from fire, control the spread of noxious weeds to protect environmental quality, establish and maintain stable, low-growing plant communities in the ROW, and activities for public and worker safety around transmission lines and other facilities.

  5. EA-2008: Colorado River Storage Project Programmatic Operations and Maintenance Project; Coconino, Maricopa, Navajo, and Yavapai Counties (Arizona) and San Juan County (Utah)

    Broader source: Energy.gov [DOE]

    Western Area Power Administration is preparing an EA that assesses the potential environmental impacts of Western’s programmatic operations and management (O&M) process and an integrated vegetation management (IVM) program on the Colorado River Storage Project System. O&M activities would consist of aerial and ground patrols, regular and preventive maintenance, inspections and repairs, and road repair. The IVM program would remove vegetation to protect facilities from fire, control the spread of noxious weeds to protect environmental quality, establish and maintain stable, low-growing plant communities in the ROW, and activities for public and worker safety around transmission lines and other facilities.

  6. Kalispel Resident Fish Project- Kalispel Tribal Hatchery Operations and Maintenance, 1997 Annual Report.

    SciTech Connect (OSTI)

    Kalispel Tribe, Department of Natural Resources

    1998-01-01

    In 1996, construction activities commenced on a largemouth bass hatchery located on the Kalispel Indian Reservation. The major construction activities were complete as of October 1997. Of the six objectives identified in the 1997 Annual Operating Plan two objectives were fully achieved: the assembly of the life support system, and the preparation of the hatchery Operations and Maintenance Manual. The remaining four objectives were not fully achieved due to the hatchery not being completed before the spawning season (spring).

  7. Moab Project Exceeds 5 Years of Operations Without Lost-Time Injury, Illness

    Broader source: Energy.gov [DOE]

    GRAND JUNCTION, Colo. – It has been more than five years since workers on the Moab Uranium Mill Tailings Remedial Action Project in Utah had a lost-time injury or illness. This represents roughly 2.2 million hours of safe work.

  8. Review of the Sodium Bearing Waste Treatment Project - Integrated Waste Treatment Unit Federal Operational Readiness Review

    Office of Environmental Management (EM)

    Federal Operational Readiness Review June 2012 Office of Safety and Emergency Management Evaluations Office of Enforcement and Oversight Office of Health, Safety and Security U.S. Department of Energy i Table of Contents 1.0 Purpose ................................................................................................................................................... 1 2.0 Background

  9. HANFORD DOUBLE SHELL TANK (DST) THERMAL & SEISMIC PROJECT SUMMARY OF COMBINED THERMAL & OPERATING LOADS

    SciTech Connect (OSTI)

    MACKEY, T.C.

    2006-03-17

    This report summarizes the results of the Double-Shell Tank Thermal and Operating Loads Analysis (TOLA) combined with the Seismic Analysis. This combined analysis provides a thorough, defensible, and documented analysis that will become a part of the overall analysis of record for the Hanford double-shell tanks (DSTs).

  10. Kalispel Resident Fish Project: Kalispel Tribal Hatchery Operations and Maintenance, 2000 Annual Report.

    SciTech Connect (OSTI)

    Bluff, Stanley

    2000-12-01

    No Annual Production Goals were achieved for the year. The Kalispel Hatchery experienced two episodes of brood fish mortality. The first due to a standpipe malfunction and the second attributed to gas bubble disease caused by elevated Total Dissolved Gases (TDG's) in the reservoir. To date, the hatchery has 29 brood fish in the raceway and ready to spawn. If all things go well this spring, hatchery operations should be well underway next year.

  11. EIS-0351: Operation of Flaming Gorge Dam, Colorado River Storage Project, Colorado River, UT

    Office of Energy Efficiency and Renewable Energy (EERE)

    The Secretary of the United States Department of the Interior (Secretary), acting through the Bureau of Reclamation (Reclamation), is considering whether to implement a proposed action under which Flaming Gorge Dam would be operated to achieve the flow and temperature regimes recommended in the September 2000 report Flow and Temperature Recommendations for Endangered Fishes in the Green River Downstream of Flaming Gorge Dam (2000 Flow and Temperature Recommendations), published by the Upper Colorado River Endangered Fish Recovery Program (Recovery Program).

  12. Selected Hanford reactor and separations operating data for 1960--1964. Hanford Environmental Dose Reconstruction Project

    SciTech Connect (OSTI)

    Gydesen, S.P.

    1992-09-01

    The purpose of this letter report is to reconstruct from available information that data which can be used to develop daily reactor operating history for 1960--1964. The information needed for source team calculations (as determined by the Source Terms Task Leader) were extracted and included in this report. The data on the amount of uranium dissolved by the separations plants (expressed both as tons and as MW) is also included in this compilation.

  13. Nuclear Power 2010 Program: Combined Construction and Operating License & Design Certification Demonstration Projects Lessons Learned Report

    Broader source: Energy.gov [DOE]

    The Nuclear Power 2010 (NP 2010) Construction and Operating License/Design Certification (COL/DC) Demonstration program together with the financial incentives provided by the Energy Policy Act of 2005 are the two primary reasons why a number of license applications for new nuclear construction are before the NRC today, and why the first new nuclear plants in over 30 years are under construction in the United States.

  14. Renewable Resource Integration Project - Scoping Study of Strategic Transmission, Operations, and Reliability Issues

    SciTech Connect (OSTI)

    Eto, Joseph; Budhraja, Vikram; Ballance, John; Dyer, Jim; Mobasheri, Fred; Eto, Joseph

    2008-07-01

    California is on a path to increase utilization of renewable resources. California will need to integrate approximately 30,000 megawatts (MW) of new renewable generation in the next 20 years. Renewable resources are typically located in remote locations, not near the load centers. Nearly two/thirds or 20,000 MW of new renewable resources needed are likely to be delivered to Los Angeles Basin transmission gateways. Integration of renewable resources requires interconnection to the power grid, expansion of the transmission system capability between the backbone power grid and transmission gateways, and increase in delivery capacity from transmission gateways to the local load centers. To scope the transmission, operations, and reliability issues for renewables integration, this research focused on the Los Angeles Basin Area transmission gateways where most of new renewables are likely. Necessary actions for successful renewables integration include: (1) Expand Los Angeles Basin Area transmission gateway and nomogram limits by 10,000 to 20,000 MW; (2) Upgrade local transmission network for deliverability to load centers; (3) Secure additional storage, demand management, automatic load control, dynamic pricing, and other resources that meet regulation and ramping needed in real time operations; (4) Enhance local voltage support; and (5) Expand deliverability from Los Angeles to San Diego and Northern California.

  15. Background report for the formerly utilized Manhattan Engineer District/Atomic Energy Commission sites program

    SciTech Connect (OSTI)

    1980-09-01

    The Department of Energy is conducting a program to determine radiological conditions at sites formerly used by the Army Corps of Engineers' Manhattan Engineer District and the Atomic Energy Commission in the early years of nuclear energy development. Also included in the program are sites used in the Los Alamos plutonium development program and the Trinity atomic bomb test site. Materials, equipment, buildings, and land became contaminated, primarily with naturally occurring radioactive nuclides. They were later decontaminated in accordance with the standards and survey methods in use at that time. Since then, however, radiological criteria, and proposed guidelines for release of such sites for unrestricted use have become more stringent as research on the effects of low-level radiation has progressed. In addition, records documenting some of these decontamination efforts cannot be found, and the final radiological conditions of the sites could not be adequately determined from the records. As a result, the Formerly Utilized Sites Program was initiated in 1974 to identify these formerly used sites and to reevaluate their radiological status. This report covers efforts through June 1980 to determine the radiological status of sites for which the existing conditions could not be clearly defined. Principal contractor facilities and associated properties have already been identified and activities are continuing to identify additional sites. Any new sites located will probably be subcontractor facilities and areas used for disposal of contractor waste or equipment; however, only limited information regarding this equipment and material has been collected to date. As additional information becomes available, supplemental reports will be published.

  16. DOE/EA-1628: Environmental Assessment for Construction and Operation of a Proposed Lignocellulosic Biorefinery, POET Project LIBERTY, LLC. (September 2008)

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Assessment and Notice of Wetlands Involvement Construction and Operation of a Proposed Lignocellulosic Biorefinery, POET Project LIBERTY, LLC. Emmetsburg, Iowa Prepared for U.S. Department of Energy by September 2008 September 2008 i POET Project LIBERTY - Final EA 9-26-08.doc Contents Executive Summary ............................................................................................................................................i Acronyms, Abbreviations, and

  17. Projecting

    U.S. Energy Information Administration (EIA) Indexed Site

    Projecting the scale of the pipeline network for CO2-EOR and its implications for CCS ... for CO 2 -EOR and CO 2 transportation for CCS assuming a carbon price are discussed. ...

  18. Environmental assessment of facility operations at the U.S. Department of Energy Grand Junction Projects Office, Grand Junction, Colorado

    SciTech Connect (OSTI)

    1996-06-01

    The US Department of Energy (DOE) has prepared a sitewide environmental assessment (EA) of the proposed action to continue and expand present-day activities on the DOE Grand Junction Projects Office (GJPO) facility in Grand Junction, Colorado. Because DOE-GJPO regularly proposes and conducts many different on-site activities, DOE decided to evaluate these activities in one sitewide EA rather than in multiple, activity-specific documents. On the basis of the information and analyses presented in the EA, DOE has determined that the proposed action does not constitute a major Federal action significantly affecting the quality of the human environment, as defined by the National Environmental Policy Act (NEPA) of 1969. Therefore, preparation of an environmental impact statement is not required for facility operations, and DOE is issuing this Finding of No Significant Impact (FONSI).

  19. SWEIS Yearbook-2012 Comparison of 2012 Data to Projections of the 2008 Site-Wide Environmental Impact Statement for Continued Operation of Los Alamos National Laboratory

    SciTech Connect (OSTI)

    Mahowald, Hallie B.; Wright, Marjorie Alys

    2014-01-16

    Los Alamos National Laboratory (LANL or the Laboratory) operations data for Calendar Year (CY) 2012 mostly fell within the 2008 Site-Wide Environmental Impact Statement (SWEIS) projections. Operation levels for one LANL facility exceeded the 2008 SWEIS capability projections—Radiochemistry Facility; however, none of the capability increases caused exceedances in radioactive air emissions, waste generation, or National Pollutant Discharge Elimination System (NPDES) discharge. Several facilities exceeded the2008 SWEIS levels for waste generation quantities; however, all were one-time, non-routine events that do not reflect the day-to-day operations of the Laboratory. In addition, total site-wide waste generation quantities were below SWEIS projections for all waste types, reflecting the overall levels of operations at both the Key and Non-Key Facilities. Although gas and electricity consumption have remained within the 2008 SWEIS limits for utilities, water consumption exceeded the 2008 SWEIS projections by 27 million gallons in CY 2012.

  20. OSTI, US Dept of Energy, Office of Scientific and Technical Information |

    Office of Scientific and Technical Information (OSTI)

    Speeding access to science information from DOE and Beyond Calutron (Y-12) Operators Topic OpenNet spotlights The Manhattan Project by Rita Hohenbrink 30 Jul, 2013 in Products and Content Calutron (Y-12) Operators Manhattan Project Sixty-eight years ago, an atomic bomb was detonated on an isolated corner of southern New Mexico in a weapon test named Trinity. Related Topics: atomic bomb, Calutron (Y-12) Operators, Leslie Groves, Manhattan Project, OpenNet, OpenNet

  1. Recovery Efficiency Test Project: Phase 1, Activity report. Volume 1: Site selection, drill plan preparation, drilling, logging, and coring operations

    SciTech Connect (OSTI)

    Overbey, W.K. Jr.; Carden, R.S.; Kirr, J.N.

    1987-04-01

    The recovery Efficiency Test well project addressed a number of technical issues. The primary objective was to determine the increased efficiency gas recovery of a long horizontal wellbore over that of a vertical wellbore and, more specifically, what improvements can be expected from inducing multiple hydraulic fractures from such a wellbore. BDM corporation located, planned, and drilled a long radius turn horizontal well in the Devonian shale Lower Huron section in Wayne County, West Virginia, demonstrating that state-of-the-art technology is capable of drilling such wells. BDM successfully tested drilling, coring, and logging in a horizontal well using air as the circulating medium; conducted reservoir modeling studies to protect flow rates and reserves in advance of drilling operations; observed two phase flow conditions in the wellbore not observed previously; cored a fracture zone which produced gas; observed that fractures in the core and the wellbore were not systematically spaced (varied from 5 to 68 feet in different parts of the wellbore); observed that highest gas show rates reported by the mud logger corresponded to zone with lowest fracture spacing (five feet) or high fracture frequency. Four and one-half inch casting was successfully installed in the borehole and was equipped to isolate the horizontal section into eight (8) zones for future testing and stimulation operations. 6 refs., 48 figs., 10 tabs.

  2. MULTIPLE LETTERS Mr. James Speir, Vice President Phosphate Operations

    Office of Legacy Management (LM)

    52. APR 9 1986 MULTIPLE LETTERS Mr. James Speir, Vice President Phosphate Operations International Minerals and Chemical Corporation P.O. Box 7047 Lakeland, Florida 33807 Dear Mr. Speir: The Department of Energy is evaluating the radiological condition of sites that were utilized by the Manhattan Engineer District and the Atomic Energy Commission (AEC) during the early years of nuclear energy development to determine whether they need remedial action and whether the Department has authority to

  3. Operating Costs

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    This chapter is focused on capital costs for conventional construction and environmental restoration and waste management projects and examines operating cost estimates to verify that all elements of the project have been considered and properly estimated.

  4. Integration of health physics, safety and operational processes for management and disposition of recycled uranium wastes at the Fernald Environmental Management Project (FEMP)

    SciTech Connect (OSTI)

    Barber, James; Buckley, James

    2003-02-23

    Fluor Fernald, Inc. (Fluor Fernald), the contractor for the U. S. Department of Energy (DOE) Fernald Environmental Management Project (FEMP), recently submitted a new baseline plan for achieving site closure by the end of calendar year 2006. This plan was submitted at DOE's request, as the FEMP was selected as one of the sites for their accelerated closure initiative. In accordance with the accelerated baseline, the FEMP Waste Management Project (WMP) is actively evaluating innovative processes for the management and disposition of low-level uranium, fissile material, and thorium, all of which have been classified as waste. These activities are being conducted by the Low Level Waste (LLW) and Uranium Waste Disposition (UWD) projects. Alternatives associated with operational processing of individual waste streams, each of which poses potentially unique health physics, industrial hygiene and industrial hazards, are being evaluated for determination of the most cost effective and safe met hod for handling and disposition. Low-level Mixed Waste (LLMW) projects are not addressed in this paper. This paper summarizes historical uranium recycling programs and resultant trace quantity contamination of uranium waste streams with radionuclides, other than uranium. The presentation then describes how waste characterization data is reviewed for radiological and/or chemical hazards and exposure mitigation techniques, in conjunction with proposed operations for handling and disposition. The final part of the presentation consists of an overview of recent operations within LLW and UWD project dispositions, which have been safely completed, and a description of several current operations.

  5. Understanding Building Infrastructure and Building Operation through DOE Asset Score Model: Lessons Learned from a Pilot Project

    SciTech Connect (OSTI)

    Wang, Na; Goel, Supriya; Gorrissen, Willy J.; Makhmalbaf, Atefe

    2013-06-24

    The U.S. Department of Energy (DOE) is developing a national voluntary energy asset score system to help building owners to evaluate the as-built physical characteristics (including building envelope, the mechanical and electrical systems) and overall building energy efficiency, independent of occupancy and operational choices. The energy asset score breaks down building energy use information by simulating building performance under typical operating and occupancy conditions for a given use type. A web-based modeling tool, the energy asset score tool facilitates the implementation of the asset score system. The tool consists of a simplified user interface built on a centralized simulation engine (EnergyPlus). It is intended to reduce both the implementation cost for the users and increase modeling standardization compared with an approach that requires users to build their own energy models. A pilot project with forty-two buildings (consisting mostly offices and schools) was conducted in 2012. This paper reports the findings. Participants were asked to collect a minimum set of building data and enter it into the asset score tool. Participants also provided their utility bills, existing ENERGY STAR scores, and previous energy audit/modeling results if available. The results from the asset score tool were compared with the building energy use data provided by the pilot participants. Three comparisons were performed. First, the actual building energy use, either from the utility bills or via ENERGY STAR Portfolio Manager, was compared with the modeled energy use. It was intended to examine how well the energy asset score represents a buildings system efficiencies, and how well it is correlated to a buildings actual energy consumption. Second, calibrated building energy models (where they exist) were used to examine any discrepancies between the asset score model and the pilot participant buildings [known] energy use pattern. This comparison examined the end use breakdowns and more detailed time series data. Third, ASHRAE 90.1 prototype buildings were also used as an industry standard modeling approach to test the accuracy level of the asset score tool. Our analysis showed that the asset score tool, which uses simplified building simulation, could provide results comparable to a more detailed energy model. The buildings as-built efficiency can be reflected in the energy asset score. An analysis between the modeled energy use through the asset score tool and the actual energy use from the utility bills can further inform building owners about the effectiveness of their buildings operation and maintenance.

  6. Nuclear Power 2010 Program Dominion Virginia Power Cooperative Project U.S. Department of Energy Cooperative Agreement DE-FC07-05ID14635 Construction and Operating License Demonstration Project Final Report

    SciTech Connect (OSTI)

    Eugene S. Grecheck David P. Batalo

    2010-11-30

    This report serves to summarize the major activities completed as part of Virginia Electric and Power Company's North Anna construction and operating license demonstration project with DOE. Project successes, lessons learned, and suggestions for improvement are discussed. Objectives of the North Anna COL project included preparation and submittal of a COLA to the USNRC incorporating ESBWR technology for a third unit a the North Anna Power Station site, support for the NRC review process and mandatory hearing, obtaining NRC approval of the COLA and issuance of a COL, and development of a business case necessary to support a decision on building a new nuclear power plant at the North Anna site.

  7. Assessment of the Portsmouth/Paducah Project Office Conduct of Operations Oversight of the Depleted Uranium Hexafluoride Conversion Plants, May 2012

    Office of Environmental Management (EM)

    Assessment of the Portsmouth/Paducah Project Office Conduct of Operations Oversight of the Depleted Uranium Hexafluoride Conversion Plants May 2012 Office of Safety and Emergency Management Evaluations Office of Enforcement and Oversight Office of Health, Safety and Security U.S. Department of Energy i Table of Contents 1.0 Purpose ................................................................................................................................................... 1 2.0 Background

  8. Wind Energy Management System EMS Integration Project: Incorporating Wind Generation and Load Forecast Uncertainties into Power Grid Operations

    SciTech Connect (OSTI)

    Makarov, Yuri V.; Huang, Zhenyu; Etingov, Pavel V.; Ma, Jian; Guttromson, Ross T.; Subbarao, Krishnappa; Chakrabarti, Bhujanga B.

    2010-01-01

    The power system balancing process, which includes the scheduling, real time dispatch (load following) and regulation processes, is traditionally based on deterministic models. Since the conventional generation needs time to be committed and dispatched to a desired megawatt level, the scheduling and load following processes use load and wind and solar power production forecasts to achieve future balance between the conventional generation and energy storage on the one side, and system load, intermittent resources (such as wind and solar generation), and scheduled interchange on the other side. Although in real life the forecasting procedures imply some uncertainty around the load and wind/solar forecasts (caused by forecast errors), only their mean values are actually used in the generation dispatch and commitment procedures. Since the actual load and intermittent generation can deviate from their forecasts, it becomes increasingly unclear (especially, with the increasing penetration of renewable resources) whether the system would be actually able to meet the conventional generation requirements within the look-ahead horizon, what the additional balancing efforts would be needed as we get closer to the real time, and what additional costs would be incurred by those needs. To improve the system control performance characteristics, maintain system reliability, and minimize expenses related to the system balancing functions, it becomes necessary to incorporate the predicted uncertainty ranges into the scheduling, load following, and, in some extent, into the regulation processes. It is also important to address the uncertainty problem comprehensively by including all sources of uncertainty (load, intermittent generation, generators forced outages, etc.) into consideration. All aspects of uncertainty such as the imbalance size (which is the same as capacity needed to mitigate the imbalance) and generation ramping requirement must be taken into account. The latter unique features make this work a significant step forward toward the objective of incorporating of wind, solar, load, and other uncertainties into power system operations. Currently, uncertainties associated with wind and load forecasts, as well as uncertainties associated with random generator outages and unexpected disconnection of supply lines, are not taken into account in power grid operation. Thus, operators have little means to weigh the likelihood and magnitude of upcoming events of power imbalance. In this project, funded by the U.S. Department of Energy (DOE), a framework has been developed for incorporating uncertainties associated with wind and load forecast errors, unpredicted ramps, and forced generation disconnections into the energy management system (EMS) as well as generation dispatch and commitment applications. A new approach to evaluate the uncertainty ranges for the required generation performance envelope including balancing capacity, ramping capability, and ramp duration has been proposed. The approach includes three stages: forecast and actual data acquisition, statistical analysis of retrospective information, and prediction of future grid balancing requirements for specified time horizons and confidence levels. Assessment of the capacity and ramping requirements is performed using a specially developed probabilistic algorithm based on a histogram analysis, incorporating all sources of uncertainties of both continuous (wind and load forecast errors) and discrete (forced generator outages and start-up failures) nature. A new method called the flying brick technique has been developed to evaluate the look-ahead required generation performance envelope for the worst case scenario within a user-specified confidence level. A self-validation algorithm has been developed to validate the accuracy of the confidence intervals.

  9. Relationships between Western Area Power Administration`s power marketing program and hydropower operations at Salt Lake City area integrated projects

    SciTech Connect (OSTI)

    Veselka, T.D.; Folga, S.; Poch, L.A.

    1995-03-01

    This technical memorandum provides background information on the Western Area Power Administration (Western) and the physical characteristics of the Salt Lake City Area Integrated Projects (SLCA/IP) hydropower plants, which include the Colorado River Storage Project, the Rio Grande Project, and the Collbran Project. In addition, the history, electrical capacity, storage capacity, and flow restrictions at each dam are presented. An overview of Western`s current programs and services, including a review of statutory authorities, agency discretion, and obligations, is also provided. The variability of SLCA/IP hourly generation under various alternative marketing strategies and purchasing programs is discussed. The effects of Western`s services, such as area load control, outage assistance, and transmission, on SLCA/IP power plant operations are analyzed.

  10. SINGLE-SHELL TANK INTEGRITY PROJECT ANALYSIS OF RECORD-PRELIMINARY MODELING PLAN FOR THERMAL AND OPERATING LOADS

    SciTech Connect (OSTI)

    RAST RS; RINKER MW; BAPANAALLI SK; DEIBLER JE; GUZMAN-LEONG CE; JOHNSON KI; KARRI NK; PILLI SP; SANBORN SE

    2010-10-22

    This document is a Phase I deliverable for the Single-Shell Tank Analysis of Record effort. This document is not the Analysis of Record. The intent of this document is to guide the Phase II detailed modeling effort. Preliminary finite element models for each of the tank types were developed and different case studies were performed on one or more of these tank types. Case studies evaluated include thermal loading, waste level variation, the sensitivity of boundary effects (soil radial extent), excavation slope or run to rise ratio, soil stratigraphic (property and layer thickness) variation at different farm locations, and concrete material property variation and their degradation under thermal loads. The preliminary analysis document reviews and preliminary modeling analysis results are reported herein. In addition, this report provides recommendations for the next phase of the SST AOR project, SST detailed modeling. Efforts and results discussed in this report do not include seismic modeling as seismic modeling is covered by a separate report. The combined results of both static and seismic models are required to complete this effort. The SST AOR project supports the US Department of Energy's (DOE) Office of River Protection (ORP) mission for obtaining a better understanding of the structural integrity of Hanford's SSTs. The 149 SSTs, with six different geometries, have experienced a range of operating histories which would require a large number of unique analyses to fully characterize their individual structural integrity. Preliminary modeling evaluations were conducted to determine the number of analyses required for adequate bounding of each of the SST tank types in the Detailed Modeling Phase of the SST AOR Project. The preliminary modeling was conducted in conjunction with the Evaluation Criteria report, Johnson et al. (2010). Reviews of existing documents were conducted at the initial stage of preliminary modeling. These reviews guided the topics that were explored in the SST preliminary modeling. The reviews determined the level of detail necessary to perform the analyses of the SSTs. To guide the Phase II detailed modeling effort, preliminary finite element models for each of the tank types were developed and different case studies were performed on one or more of these tank types. Case studies evaluated include thermal loading, waste level variation, the sensitivity of boundary effects (soil radial extent), excavation slope or run to rise ratio, soil stratigraphic (property and layer thickness) variation at different farm locations, and concrete material property variation and their degradation under thermal loads. Conclusions were derived from case studies on one of the tank types when no additional runs of similar cases on other types of tanks were found necessary to derive those conclusions. The document reviews provided relatively complete temperature histories for Type IV tanks. The temperature history data for Type I, II, and III tanks was almost nonexistent for years prior to 1975. Document reviews indicate that there might be additional useful data in the US Department of Energy, Richland Operations Office (DOE-RL) records in Seattle, WA, and these records need to be reviewed to extract data that might have been disregarded during previous reviews. Thermal stress analyses were conducted using different temperature distribution scenarios on Type IV tanks. Such studies could not be carried out for other tank types due to lack of temperature history data. The results from Type IV tank analyses indicate that factors such as temperature distribution in the tank waste and rate of rise in waste temperature have a significant impact on the thermal stresses in the tank structures. Overall, the conclusion that can drawn from the thermal stress analyses is that these studies should be carried out for all tank types during the detailed analysis phase with temperature values that are reasonably close to the typical temperature histories of the respective tank types. If and/or when additional waste temperature data is acquired for tank Type I, II, and III tanks, additional cases need to be considered as tank structural integrity is sensitive to thermal loads. A few case studies were also performed using Type IV-b models to comprehend the effects of excavation boundaries, change in soil stratigraphy (layer thickness and properties), and radial extent of soil in the finite element models. The result from the case studies indicates that the slight variation in soil stratigraphy has little effects on the tank sections force and moment demands under mechanical loads. The case study for excavation slope or backfill transition boundary indicated that inclusion of such boundary yields conservative demands in the wall region while demands at other locations remain unaffected. Hence this excavation slope will be modeled in the detailed analysis of SSTs.

  11. OSTI, US Dept of Energy, Office of Scientific and Technical Information |

    Office of Scientific and Technical Information (OSTI)

    Speeding access to science information from DOE and Beyond 70th Anniversary Topic The Manhattan Project -- Its Operations by Mary Schorn 29 Nov, 2012 in Science Communications Major operations for the Manhattan Engineer District (Manhattan Project) took place in remote site locations in the states of Tennessee, New Mexico, and Washington, with additional research being conducted in university laboratories at Chicago and Berkeley. At the Metallurgical Laboratory in Chicago, Enrico Fermi's

  12. OSTI, US Dept of Energy, Office of Scientific and Technical Information |

    Office of Scientific and Technical Information (OSTI)

    Speeding access to science information from DOE and Beyond electromagnetic Topic The Manhattan Project -- Its Operations by Mary Schorn 29 Nov, 2012 in Science Communications Major operations for the Manhattan Engineer District (Manhattan Project) took place in remote site locations in the states of Tennessee, New Mexico, and Washington, with additional research being conducted in university laboratories at Chicago and Berkeley. At the Metallurgical Laboratory in Chicago, Enrico Fermi's

  13. OSTI, US Dept of Energy, Office of Scientific and Technical Information |

    Office of Scientific and Technical Information (OSTI)

    Speeding access to science information from DOE and Beyond gaseous diffusion Topic The Manhattan Project -- Its Operations by Mary Schorn 29 Nov, 2012 in Science Communications Major operations for the Manhattan Engineer District (Manhattan Project) took place in remote site locations in the states of Tennessee, New Mexico, and Washington, with additional research being conducted in university laboratories at Chicago and Berkeley. At the Metallurgical Laboratory in Chicago, Enrico Fermi's

  14. OSTI, US Dept of Energy, Office of Scientific and Technical Information |

    Office of Scientific and Technical Information (OSTI)

    Speeding access to science information from DOE and Beyond uranium Topic The Manhattan Project -- Its Operations by Mary Schorn 29 Nov, 2012 in Science Communications Major operations for the Manhattan Engineer District (Manhattan Project) took place in remote site locations in the states of Tennessee, New Mexico, and Washington, with additional research being conducted in university laboratories at Chicago and Berkeley. At the Metallurgical Laboratory in Chicago, Enrico Fermi's experiments

  15. OSTI, US Dept of Energy, Office of Scientific and Technical Information |

    Office of Scientific and Technical Information (OSTI)

    Speeding access to science information from DOE and Beyond spotlights The Manhattan Project by Rita Hohenbrink on Tue, Jul 30, 2013 Calutron (Y-12) Operators Manhattan Project Sixty-eight years ago, an atomic bomb was detonated on an isolated corner of southern New Mexico in a weapon test named Trinity. This month, The Manhattan Project: Resources, a web-based, joint collaboration between the Department's Office of Classification and Office of History and Heritage Resources has been

  16. Exposure Based Health Issues Project Report: Phase I of High Level Tank Operations, Retrieval, Pretreatment, and Vitrification Exposure Based Health Issues Analysis

    SciTech Connect (OSTI)

    Stenner, Robert D.; Bowers, Harold N.; Kenoyer, Judson L.; Strenge, Dennis L.; Brady, William H.; Ladue, Buffi; Samuels, Joseph K.

    2001-11-30

    The Department of Energy (DOE) has the responsibility to understand the ''big picture'' of worker health and safety which includes fully recognizing the vulnerabilities and associated programs necessary to protect workers at the various DOE sites across the complex. Exposure analysis and medical surveillance are key aspects for understanding this big picture, as is understanding current health and safety practices and how they may need to change to relate to future health and safety management needs. The exposure-based health issues project was initiated to assemble the components necessary to understand potential exposure situations and their medical surveillance and clinical aspects. Phase I focused only on current Hanford tank farm operations and serves as a starting point for the overall project. It is also anticipated that once the pilot is fully developed for Hanford HLW (i.e., current operations, retrieval, pretreatment, vitrification, and disposal), the process and analysis methods developed will be available and applicable for other DOE operations and sites. The purpose of this Phase I project report is to present the health impact information collected regarding ongoing tank waste maintenance operations, show the various aspects of health and safety involved in protecting workers, introduce the reader to the kinds of information that will need to be analyzed in order to effectively manage worker safety.

  17. HANFORD DOUBLE SHELL TANK THERMAL AND SEISMIC PROJECT SUMMARY OF COMBINED THERMAL AND OPERATING LOADS WITH SEISMIC ANALYSIS

    SciTech Connect (OSTI)

    MACKEY TC; DEIBLER JE; RINKER MW; JOHNSON KI; ABATT FG; KARRI NK; PILLI SP; STOOPS KL

    2009-01-15

    This report summarizes the results of the Double-Shell Tank Thermal and Operating Loads Analysis (TaLA) combined with the Seismic Analysis. This combined analysis provides a thorough, defensible, and documented analysis that will become a part of the overall analysis of record for the Hanford double-shell tanks (DSTs). The bases of the analytical work presented herein are two ANSYS{reg_sign} finite element models that were developed to represent a bounding-case tank. The TaLA model includes the effects of temperature on material properties, creep, concrete cracking, and various waste and annulus pressure-loading conditions. The seismic model considers the interaction of the tanks with the surrounding soil including a range of soil properties, and the effects of the waste contents during a seismic event. The structural evaluations completed with the representative tank models do not reveal any structural deficiencies with the integrity of the DSTs. The analyses represent 60 years of use, which extends well beyond the current date. In addition, the temperature loads imposed on the model are significantly more severe than any service to date or proposed for the future. Bounding material properties were also selected to provide the most severe combinations. While the focus of the analyses was a bounding-case tank, it was necessary during various evaluations to conduct tank-specific analyses. The primary tank buckling evaluation was carried out on a tank-specific basis because of the sensitivity to waste height, specific gravity, tank wall thickness, and primary tank vapor space vacuum limit. For this analysis, the occurrence of maximum tank vacuum was classified as a service level C, emergency load condition. The only area of potential concern in the analysis was with the buckling evaluation of the AP tank, which showed the current limit on demand of l2-inch water gauge vacuum to exceed the allowable of 10.4 inches. This determination was based on analysis at the design waste temperature of 350 F and the full 60-year corrosion allowance on the tank wall of 0.060 inch. However, analysis at a more realistic temperature of 250 F or corrosion allowance of 0.025 inch results in an acceptable demand/capacity ratio according to the ASME code criteria. Thus, buckling of the primary tank is judged to be unlikely for the current lack of corrosion in the tanks, and the expectation that the maximum waste temperature will not exceed 210 F. The reinforced concrete structure was evaluated as specified by the American Concrete Institute (ACI) code requirements for nuclear safety-related structures (ACI-349). The demand was demonstrated to be lower than the capacity at all locations. Revision 1 is being issued to document changes to the anchor bolt evaluation. RPP-RPT-32237 Rev. 1, Hanford Double-Shell Tank Thermal and Seismic Project-Increased Liquid Level Analysis for 241AP Tank Farms, described changes to the anchor bolt modeling and evaluation which were implemented in response to the independent reviewer's comments. Similar changes have been made in the bounding tank analysis and are documented in RPP-RPT-28968 Rev. 1. The conclusions of the previous releases of this report remain unchanged.

  18. Operation Castle. Project 7. 1. Electromagnetic radiation calibration, Pacific )roving ground. Report for March-May 1954

    SciTech Connect (OSTI)

    Olseon, M.H.

    1984-08-31

    A total of 17 stations, one close-in (320 km from Bikini and 23 km from Eniwetok) and the balance at distances, were operated for the electromagnetic experimental effort. Seventy-four sets of data were obtained from a possible total of 102. Of the remaining 28 sets, no data were obtained because equipment was not in operation, records were not readable, the alert notifications were not received, signals were not discernible, or equipment malfunctioned.

  19. Review of the Sodium Bearing Waste Treatment Project - Integrated Waste Treatment Uinit Contractor Operational Readiness Review, June 2012

    Office of Environmental Management (EM)

    Contractor Operational Readiness Review June 2012 Office of Safety and Emergency Management Evaluations Office of Enforcement and Oversight Office of Health, Safety and Security U.S. Department of Energy i Table of Contents 1.0 Purpose ................................................................................................................................................... 1 2.0 Background

  20. Lessons from Iowa : development of a 270 megawatt compressed air energy storage project in midwest Independent System Operator : a study for the DOE Energy Storage Systems Program.

    SciTech Connect (OSTI)

    Holst, Kent; Huff, Georgianne; Schulte, Robert H.; Critelli, Nicholas

    2012-01-01

    The Iowa Stored Energy Park was an innovative, 270 Megawatt, $400 million compressed air energy storage (CAES) project proposed for in-service near Des Moines, Iowa, in 2015. After eight years in development the project was terminated because of site geological limitations. However, much was learned in the development process regarding what it takes to do a utility-scale, bulk energy storage facility and coordinate it with regional renewable wind energy resources in an Independent System Operator (ISO) marketplace. Lessons include the costs and long-term economics of a CAES facility compared to conventional natural gas-fired generation alternatives; market, legislative, and contract issues related to enabling energy storage in an ISO market; the importance of due diligence in project management; and community relations and marketing for siting of large energy projects. Although many of the lessons relate to CAES applications in particular, most of the lessons learned are independent of site location or geology, or even the particular energy storage technology involved.

  1. A Complexity Science-Based Framework for Global Joint Operations Analysis to Support Force Projection: LDRD Final Report.

    SciTech Connect (OSTI)

    Lawton, Craig R.

    2015-01-01

    The military is undergoing a significant transformation as it modernizes for the information age and adapts to address an emerging asymmetric threat beyond traditional cold war era adversaries. Techniques such as traditional large-scale, joint services war gaming analysis are no longer adequate to support program evaluation activities and mission planning analysis at the enterprise level because the operating environment is evolving too quickly. New analytical capabilities are necessary to address modernization of the Department of Defense (DoD) enterprise. This presents significant opportunity to Sandia in supporting the nation at this transformational enterprise scale. Although Sandia has significant experience with engineering system of systems (SoS) and Complex Adaptive System of Systems (CASoS), significant fundamental research is required to develop modeling, simulation and analysis capabilities at the enterprise scale. This report documents an enterprise modeling framework which will enable senior level decision makers to better understand their enterprise and required future investments.

  2. Operation Hardtack. Project 3. 2. Response of earth-confined flexible-arch structures in high-overpressure regions

    SciTech Connect (OSTI)

    LeDoux, J.C.; Rush, P.J.

    1985-09-01

    The purpose of this project was to determine structural responses and failure criteria of earth-confined corrugated-steel flexible arches subjected to high overpressure blast loading from nuclear detonations. A flexible arch is considered as an arch structure whose ultimate supporting capacity is dependent upon confinement within a surrounding earth configuration. A collateral objective was to determine the radiation-shielding effectiveness of such structures with a minimum cover of five feet of coral sand. Because the soil and ground-water conditions at Eniwetok did not permit the placing of the steel arches below natural-grade level, the structures were confined within massive non-drag sensitive earthwork configurations of coral sand. Empirical determinations were made of the responses of (1) three earth-confined prefabricated corrugated-steel flexible arches when subjected to relatively long-duration blast loadings from a megaton range detonation; and (2) one similar earth-confined flexible-arch when subjected to relatively short-duration blast loadings from a kiloton-range detonation.

  3. Policy Flash 2013-40 Acquisition Guide Chapter 43.3 Maintaining Alignment of Project Management with Contract Management of Non-Management and Operating (M&O) Cost Reimburstment Contracts

    Broader source: Energy.gov [DOE]

    Attached is Policy Flash 2013-40 Acquisition Guide Chapter 43.3 Maintaining Alignment of Project Management with Contract Management of Non-Management and Operating (M&O) Cost Reimbursement...

  4. DOE - Office of Legacy Management -- NewYork_FUSRAP

    Office of Legacy Management (LM)

    New York, New York, Site FUSRAP Site New York Map Background-The New York, New York, Site, in Manhattan, was remediated under the Formerly Utilized Sites Remedial Action Program (FUSRAP). FUSRAP was established in 1974 to remediate sites where radioactive contamination remained from Manhattan Project and early U.S. Atomic Energy Commission operations. History-The New York Site was used by the Manhattan Engineer District in the early 1940s for the short-term storage of uranium concentrates that

  5. Projects | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Projects Projects

  6. Operation Redwing. Project 3. 1. Effect of length of positive phase of blast on drag-type and semidrag-time industrial buildings

    SciTech Connect (OSTI)

    Sinnamon, G.K.; Haltiwanger, J.D.; Newmark, N.M.

    1985-09-01

    The primary objective of the project was to obtain information regarding the effect of the length of the positive phase of blast on the response of drag and semidrag structures. A total of six steel-frame buildings were tested during this operation. The structure of each type nearest ground zero was located such that if the yield of the weapon was near the lower limit of its predicted range, it would probably undergo considerable inelastic deformation. Conversely, those structures farthest from ground zero were located such that if the yield of the nuclear device was near the upper limit of its predicted range, they would be substantially deformed, but would not collapse. The third building of each type was located at an intermediate point between these two extremes. Instrumentation was provided to obtain records of the transient structural deflections, strains, and accelerations, as well as of overpressure and dynamic pressure versus time at the sites of the various test structures.

  7. Step 4: Project Implementation

    Energy Savers [EERE]

    Process Step 4: Project Implementation Presentation Agenda * Step 4: Project Implementation - Pre-construction - Contract execution - Interconnection - Project construction - Commissioning * Project Example 2 1/28/2016 2 1 Potential 3 Refinement 5 Operations & Maintenance 2 Options 4 Implementation 4 Implementation 3 Potential Options Refinement Implementation Operations & Maintenance Step 4: Implementation 4 Purpose: Contract and begin physical construction of project Tasks: * Finalize

  8. Radioactive air emissions notice of construction for installation and operation of a waste retrieval system and tanks 241-AP-102 and 241-AP-104 project

    SciTech Connect (OSTI)

    DEXTER, M.L.

    1999-11-15

    This document serves as a notice of construction (NOC) pursuant to the requirements of Washington Administrative Code (WAC) 246 247-060, and as a request for approval to modify pursuant to 40 Code of Federal Regulations (CFR) 61 07 for the installation and operation of one waste retrieval system in the 24 1 AP-102 Tank and one waste retrieval system in the 241 AP 104 Tank Pursuant to 40 CFR 61 09 (a)( 1) this application is also intended to provide anticipated initial start up notification Its is requested that EPA approval of this application will also constitute EPA acceptance of the initial start up notification Project W 211 Initial Tank Retrieval Systems (ITRS) is scoped to install a waste retrieval system in the following double-shell tanks 241-AP 102-AP 104 AN 102, AN 103, AN-104, AN 105, AY 102 AZ 102 and SY-102 between now and the year 2011. Because of the extended installation schedules and unknowns about specific activities/designs at each tank, it was decided to submit NOCs as that information became available This NOC covers the installation and operation of a waste retrieval system in tanks 241 AP-102 and 241 AP 104 Generally this includes removal of existing equipment installation of new equipment and construction of new ancillary equipment and buildings Tanks 241 AP 102 and 241 AP 104 will provide waste feed for immobilization into a low activity waste (LAW) product (i.e. glass logs) The total effective dose equivalent (TEDE) to the offsite maximally exposed individual (MEI) from the construction activities is 0 045 millirem per year The unabated TEDE to the offsite ME1 from operation of the mixer pumps is 0 042 millirem per year.

  9. Operation Schedule

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Operation Schedule Daily Hours of Operation

  10. Mechanical Design Engineering, MDE, Accelerator Operations and...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AOT-MDE's primary responsibilities include supporting accelerator operations, maintenance, and performance improvement projects; developing leadership roles in projects...

  11. Optimizing Installation, Operation, and Maintenance at Offshore...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Optimizing Installation, Operation, and Maintenance at Offshore Wind Projects in the United States Optimizing Installation, Operation, and Maintenance at Offshore Wind Projects in...

  12. Optimizing Installation, Operation, and Maintenance at Offshore...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Optimizing Installation, Operation, and Maintenance at Offshore Wind Projects in the United States Optimizing Installation, Operation, and Maintenance at Offshore Wind Projects in ...

  13. Johnson Creek Artificial Propagation and Enhancement Project Operations and Maintenance Program; Brood Year 1998: Johnson Creek Chinook Salmon Supplementation, Biennial Report 1998-2000.

    SciTech Connect (OSTI)

    Daniel, Mitch; Gebhards, John

    2003-05-01

    The Nez Perce Tribe, through funding provided by the Bonneville Power Administration, has implemented a small scale chinook salmon supplementation program on Johnson Creek, a tributary in the South Fork of the Salmon River, Idaho. The Johnson Creek Artificial Propagation Enhancement project was established to enhance the number of threatened Snake River summer chinook salmon (Oncorhynchus tshawytscha) returning to Johnson Creek through artificial propagation. Adult chinook salmon collection and spawning began in 1998. A total of 114 fish were collected from Johnson Creek and 54 fish (20 males and 34 females) were retained for Broodstock. All broodstock were transported to Lower Snake River Compensation Plan's South Fork Salmon River adult holding and spawning facility, operated by the Idaho Department of Fish and Game. The remaining 60 fish were released to spawn naturally. An estimated 155,870 eggs from Johnson Creek chinook spawned at the South Fork Salmon River facility were transported to the McCall Fish Hatchery for rearing. Average fecundity for Johnson Creek females was 4,871. Approximately 20,500 eggs from females with high levels of Bacterial Kidney Disease were culled. This, combined with green-egg to eyed-egg survival of 62%, resulted in about 84,000 eyed eggs produced in 1998. Resulting juveniles were reared indoors at the McCall Fish Hatchery in 1999. All of these fish were marked with Coded Wire Tags and Visual Implant Elastomer tags and 8,043 were also PIT tagged. A total of 78,950 smolts were transported from the McCall Fish Hatchery and released directly into Johnson Creek on March 27, 28, 29, and 30, 2000.

  14. Step 5: Operations and Maintenance

    Energy Savers [EERE]

    Process Step 5: Project Operations and Maintenance Project Development Process 1 Potential 5 Operations & Maintenance 3 Refinement 2 Options 4 Implementation 2 1/28/2016 2 Presentation Agenda * Step 5: Project Operations and Maintenance (O&M) * Post-procurement activities * Drivers * Technology examples * Activity 3 Potential Options Refinement Implementation Operations & Maintenance Step 5: Operations & Maintenance 4 Photo by Warren Getz, NREL 00180 Purpose: Conduct or ensure

  15. Step 3: Project Refinement

    Energy Savers [EERE]

    3: Project Refinement 2 1 Potential 3 Refinement 4 Implementation 5 Operations & Maintenance 2 Options 3 Refinement 1/28/2016 2 3 FUNDING AND FINANCING OPTIONS Project Ownership Financing structure is highly dependent on size of the project and the capital available for a given project: * Tribe owns the project (cash purchase or debt) * Tribe hosts the project and buys the electricity (power purchase agreement) * Tribe partners with private sector and co-owns the project (uncertainties about

  16. HGP-A Wellhead Generator, Proof-Of-Feasibility Project 3 MW Wellhead Generator, Start-Up Training and Operating Manual

    SciTech Connect (OSTI)

    1981-01-01

    The start-up manual is an information aid to initially familiarize plant operators with the plant operation and later be used as a reference manual while operating the plant. This start-up manual is supplemented by the Plant Data Manual which contains a detailed description of the philosophy of operation and equipment characteristics. The sequencing herein presents the necessary operating procedures which must be followed in order that a smooth start-up is obtained. The sequence includes, first conditioning the well and stabilizing the steam/water separations, and then bringing the operating machinery on line. The Piping and Instrumentation Diagrams and Electrical Drawings are included under Section 12.0 and are frequently referred to in the text. Information for ''trouble-shooting'' is provided in the maintenance and operations manuals on all the equipment.

  17. Hewlett and Duncan - Atomic Shield | Department of Energy

    Energy Savers [EERE]

    & Public Tours History Publications Labs and Field Site Histories Researching DOE Records DOE History Timeline Manhattan Project Manhattan Project National Historical Park...

  18. Welcome to College Programs at Y-12 | Y-12 National Security Complex

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Did You Know? Oak Ridge was established in the 1940s to house the Manhattan Project. Learn more about the Manhattan Project and the history of Oak Ridge

  19. Project Management Career Development Program | Department of...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    are here Home Operational Management Certifications and Professional Development Project Management Career Development Program Project Management Career Development...

  20. MHK Projects/Oyster 800 Project | Open Energy Information

    Open Energy Info (EERE)

    4 Project Details Operational testing of Oyster 800 commenced in June 2012 when the machine produced first electrical power to the grid. Project Installed Capacity (MW) 1...

  1. Independent Activity Report, Hanford Sludge Treatment Project...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Sludge Treatment Project - February 2012 Independent Activity Report, Hanford Sludge Treatment Project - February 2012 February 2012 Hanford Sludge Treatment Project Operational...

  2. Hydaburg Cooperative Association: Haida Corporation- 1995 Project

    Broader source: Energy.gov [DOE]

    This project analyzes the benefits of the proposed project and the effects of project construction and operation on the natural resources of the Reynolds Creek Basin.

  3. North American LNG Project Sourcebook

    SciTech Connect (OSTI)

    2007-06-15

    The report provides a status of the development of LNG Import Terminal projects in North America, and includes 1-2 page profiles of 63 LNG projects in North America which are either in operation, under construction, or under development. For each project, the sourcebook provides information on the following elements: project description, project ownership, project status, projected operation date, storage capacity, sendout capacity, and pipeline interconnection.

  4. Environmental Restoration Program project management plan for the DOE Oak Ridge Field Office Major System Acquisition OR-1. Revision 1, Environmental Restoration Program

    SciTech Connect (OSTI)

    Not Available

    1992-12-01

    In the early 1940s, the Manhattan Project was conducted in a regulatory and operational environment less sophisticated than today. Less was known of the measures needed to protect human health and safety and the environment from the dangers posed by radioactive and hazardous wastes, and experience in dealing with these hazardous materials has grown slowly. Certain hazards were recognized and dealt with from the beginning. However, the techniques used, though standard practices at the time, are now known to have been inadequate. Consequently, the DOE has committed to an aggressive program for cleaning up the environment and has initiated an Environmental Restoration Program involving all its field offices. The objective of this program is to ensure that inactive and surplus DOE facilities and sites meet current standards to protect human health and the environment. The objective of these activities is to ensure that risks posed to human health and safety and the environment by inactive sites and surplus facilities contaminated with radioactive, hazardous, and/or mixed wastes are either eliminated or reduced to prescribed safe levels. This Project Management Plan for Major System Acquisition OR-1 Project documents, communicates, and contributes to the evolution of, the management organizations, systems, and tools necessary to carry out effectively the long-range complex cleanup of the DOE sites on the Oak Ridge Reservation, and at the Paducah, Kentucky, and Piketon, Ohio, uranium enrichment plants managed by the Department of Energy Oak Ridge Field Office; the cleanup of off-site contamination resulting from past releases; and the Decontamination and Decommissioning of surplus DOE facilities at these installations.

  5. Glen Ganyon Dam, Colorado River Storage Project, Arizona. The short-run economic cost of environmental constraints on hydropower operations. Final report

    SciTech Connect (OSTI)

    Harpman, D.A.

    1997-06-01

    In October of 1995, the Secretary of the Interior announced that Glen Canyon Dam would be operated under the Modified Low Fluctuating Flow (MLFF) criteria to protect downstream archeological, cultural, aquatic and riparian resources. Although the annual and monthly amounts of water released downstream remain the same, MLFF imposes a unique and complex set of constraints on hourly and daily hydropower operations. These constraints include restrictions on ramp rates (hourly rate of change in release), minimum flows, maximum flows, and the daily change in flow. In addition, a key component of MLFF operations is adaptive management which establishes a framework of research and monitoring on which future changes in operation will be based. Consequently, MLFF operations are not static and variants of these hourly constraints may be contemplated in the future. This paper summarizes the environmental concerns which led to MLFF, reviews some pertinent electric power concepts, and describes current institutional and market conditions. A generalized method for simulating and valuing hourly hydroelectric generation under various operational constraints is then introduced.

  6. DOE Chooses Idaho Treatment Group, LLC to Disposition Waste at the Advanced Mixed Waste Treatment Project: Contract will continue cleanup and waste operations at the Idaho Site

    Broader source: Energy.gov [DOE]

    Idaho Falls – In order to further meet the U.S. Department of Energy’s commitments to the citizens of the state of Idaho, the DOE today announced that it has selected Idaho Treatment Group, LLC (ITG) to perform waste processing at the Advanced Mixed Waste Treatment Project (AMWTP) at DOE’s Idaho Site near Idaho Falls.

  7. RECONSTRUCTION OF DOSE TO THE RESIDENTS OF OZERSK FROM THE OPERATION OF THE MAYAK PRODUCTION ASSOCIATION: 1948-2002: Progress Report on Project 1.4

    SciTech Connect (OSTI)

    Mokrov, Y.; Rovny, Sergey I.; Anspaugh, L. R.; Napier, Bruce A.

    2009-10-23

    This Progress Report for Project 1.4 of the U.S.Russia Joint Coordinating Committee on Radiation Effects Research continues in the abbreviated format of providing details only on the work accomplished during this six-month reporting period.

  8. Step 2: Project Options

    Energy Savers [EERE]

    2: Project Options 2 2 Design 1 Potential 3 Refinement 4 Implementation 2 Options 5 Operations & Maintenance 1/28/2016 2 Presentation Agenda * Step 2: Project Options * Project members and roles * Activity * Project ownership options - Interconnection, net metering, permitting, and considerations * Tools * Case in Point 3 Potential Options Refinement Implementation Operations & Maintenance 4 Step 2: Roles, Business Structures, & Regulatory Considerations Purpose: Determine ownership

  9. Step 4: Project Implementation

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    4: Project Implementation Project Implementation 2 1 Potential 3 Refinement 5 Operations & Maintenance 2 Options 4 Implementation Step 4: Implementation 3 1 Potential 3 Refinement 5 Operations & Maintenance 2 Options 4 Implementation Step 4: Implementation 1. Pre-construction - Project kickoff - Design and construction documents, plans/schedules, submittals 2. Construction of project - Contract oversight/quality control - Change control 3. Commissioning - Testing and verification -

  10. Mascoma: Frontier Biorefinery Project

    Broader source: Energy.gov [DOE]

    This project involves the construction and operation of a biorefinery that produces ethanol and other co-products from cellulosic materials through advanced consolidated bioprocessing.

  11. Conduct of Operations

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2010-06-29

    This Order defines the requirements for establishing and implementing Conduct of Operations Programs at Department of Energy (DOE), including National Nuclear Security Administration (NNSA), facilities and projects. Cancels DOE O 5480.19. Admin Chg 1, 6-25-13

  12. Conduct of Operations

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2010-06-29

    This Order defines the requirements for establishing and implementing Conduct of Operations Programs at Department of Energy (DOE), including National Nuclear Security Administration (NNSA), facilities and projects. Admin Chg 2, dated 12-3-14, supersedes Admin Chg 1.

  13. Simulating operations at Glen Canyon Dam, Colorado River Storage Project, Arizona gcflow version 1.4 (for microcomputers). Model-Simulation

    SciTech Connect (OSTI)

    1996-06-01

    This product is a modeling tool for examining the amount and pattern of daily water releases from Glen Canyon Dam under various operational constraints. This program is an extension of the geometric model used by Western Area Power Administration and is primarily an educational tool. It is designed to help the user understand hydropower operations at Glen Canyon Dam and to illustrate how the alternatives examined in the Glen Canyon Dam Environmental Impact Statement affect power production. This program demonstrates, in a simplified way, the relationship between monthly release volume, flow constraints, lake elevation, and power production.

  14. Distributed Generation Operational Reliability and Availability...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    generation (DG)combined heat and power (CHP) project operators, owners, and developers, ... Specifically, the project team analyzed event histories for 121 DGCHP units over a ...

  15. Next Generation Nuclear Plant Project Evaluation of Siting a HTGR Co-generation Plant on an Operating Commercial Nuclear Power Plant Site

    SciTech Connect (OSTI)

    L.E. Demick

    2011-10-01

    This paper summarizes an evaluation by the Idaho National Laboratory (INL) Next Generation Nuclear Plant (NGNP) Project of siting a High Temperature Gas-cooled Reactor (HTGR) plant on an existing nuclear plant site that is located in an area of significant industrial activity. This is a co-generation application in which the HTGR Plant will be supplying steam and electricity to one or more of the nearby industrial plants.

  16. EA-1982: Parker-Davis Transmission System Routine Operation and...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Operation and Maintenance Project and Proposed Integrated Vegetation Management Program EA-1982: Parker-Davis Transmission System Routine Operation and Maintenance Project and ...

  17. Database Aids Building Owners and Operators in Energy-Efficiency...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Database Aids Building Owners and Operators in Energy-Efficiency Project Decision Making Database Aids Building Owners and Operators in Energy-Efficiency Project Decision Making ...

  18. Transforming the Commercial Building Operations - 2014 BTO Peer...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    - 2014 BTO Peer Review Transforming the Commercial Building Operations - 2014 BTO Peer Review Project Objective The overall goal of this project is to train building operations...

  19. Five-year summary and evaluation of operations and performance of the Utica aquifer and North Lake Basin Wetlands restoration project in 2004-2009.

    SciTech Connect (OSTI)

    LaFreniere, L. M.

    2011-09-13

    This document reviews the performance of the groundwater (and wetlands) restoration program implemented by the Commodity Credit Corporation of the U.S. Department of Agriculture (CCC/USDA) at the former CCC/USDA grain storage facility in Utica, Nebraska, during the first five years (2004-2009) of this initiative. The report summarizes treatment system operational data and regulatory compliance monitoring results for the site during this period, together with the results of the targeted groundwater sampling and analysis for volatile organic compounds (VOCs) conducted in early 2010 (following completion of the fifth year of systems operation), to assess the initial five years of progress of the Utica remediation effort. On the basis of the 2003 groundwater sampling results, a remedial system employing 4 extraction wells (GWEX1-GWEX4), with groundwater treatment by spray irrigation and conventional air stripping, was implemented with the concurrence of the CCC/USDA and the agencies (Table 1.1). The principal components of the system are shown in Figure 1.3 and are briefly described in Section 1.2. Operation of well GWEX4 and the associated air stripper began on October 29, 2004, and routine operation of wells GWEX1-GWEX3 and the spray irrigation treatment units began on November 22, 2004.

  20. CO-operation development project for new treatment of steam generator's - impact on final disposal volumes and recycling in Northern Europe

    SciTech Connect (OSTI)

    Wirendal, B.O.; Lindstrom, A.; Lindberg, M.; Hansson, T.

    2007-07-01

    This paper describes a real case of cost effective volume reduction of a retired, full size SG removed from the Ringhals Nuclear Power Plant, Sweden. The project is described from the first step of fulfilling the demands from the authorities before treatment to the results of the treatment. The evaluations of the method is also included and compared to the other possibilities and the driving forces that work in favour of our method. The waste owners' strategy is also described in this paper. Finally is the method of treatment described as a principle as well as the results. Technical details as well as detailed results are given in Paper 7131 [ref 1]. (authors)

  1. Hanford Blog Archive - Hanford Site

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    November 2015 November 19, 2015 Department of Energy completes chromium cleanup along Columbia River More than two million tons of chromium-contaminated soil have been moved away from several areas near the Columbia River at the Hanford Site. November 12, 2015 Agencies welcome Manhattan Project National Historical Park Following the Nov. 10 establishment of the Manhattan Project National Historical Park, the Department of Energy's (DOE) Richland Operations Office has eliminated the age

  2. For Immediate Release:

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    2, 2015 Media Contacts: Mark Heeter, DOE, (509) 373-1970, mark.heeter@rl.doe.gov Chip Jenkins, NPS, (360) 770-8882. Agencies welcome Manhattan Project National Historical Park DOE Eliminates Age Requirement for B Reactor National Historic Landmark RICHLAND, Wash. - Following the Nov. 10 establishment of the Manhattan Project National Historical Park, the Department of Energy's (DOE) Richland Operations Office has eliminated the age requirement for entrance to the B Reactor National Historic

  3. Cloudnet Project

    DOE Data Explorer [Office of Scientific and Technical Information (OSTI)]

    Hogan, Robin

    2008-01-15

    Cloudnet is a research project supported by the European Commission. This project aims to use data obtained quasi-continuously for the development and implementation of cloud remote sensing synergy algorithms. The use of active instruments (lidar and radar) results in detailed vertical profiles of important cloud parameters which cannot be derived from current satellite sensing techniques. A network of three already existing cloud remote sensing stations (CRS-stations) will be operated for a two year period, activities will be co-ordinated, data formats harmonised and analysis of the data performed to evaluate the representation of clouds in four major european weather forecast models.

  4. Cloudnet Project

    DOE Data Explorer [Office of Scientific and Technical Information (OSTI)]

    Hogan, Robin

    Cloudnet is a research project supported by the European Commission. This project aims to use data obtained quasi-continuously for the development and implementation of cloud remote sensing synergy algorithms. The use of active instruments (lidar and radar) results in detailed vertical profiles of important cloud parameters which cannot be derived from current satellite sensing techniques. A network of three already existing cloud remote sensing stations (CRS-stations) will be operated for a two year period, activities will be co-ordinated, data formats harmonised and analysis of the data performed to evaluate the representation of clouds in four major european weather forecast models.

  5. Operation Hardtack. Project 1. 9. Loading on buried simulated structures in high-overpressure regions. Report for April-October 1958

    SciTech Connect (OSTI)

    Bultmann, E.H.; McDonough, G.F.; Sinnamon, G.K.

    1984-10-31

    The objective of this project was to study some of the factors affecting the transmission of air-blast-induced pressure through soil and the loading produced on buried structures by such pressures in the high-pressure region (approximately 250 psi). Factors studied were: (1) the attenuation of pressure in a sand deposit when the water table is a few feet below the ground surface; (2) the effect of duration of positive phase of blast on the pressure transmitted through such a soil; (3) the effect of structure flexibility on the pressure acting on structures buried in such a soil; and (4) the relationship between horizontal and vertical pressures in such a soil. The project employed 43 devices, each a rigid cylinder having one rigid end and one deformable-diaphragm end. The devices were buried at depths ranging from 0 to 20 feet at each of two locations at the Eniwetok Proving Ground. The locations were chosen to give a predicted ground surface overpressure of about 250 psi from each of two shots, Cactus and Koa.

  6. Independent Activity Report, Richland Operations Office - April...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    1 Independent Activity Report, Richland Operations Office - April 2011 April 2011 Operational Awareness Review of the Hanford Sludge Treatment Project HIAR-RL-2011-04-07 This...

  7. Business Operations Organization Chart

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Office of Business Operations Organization Chart Office of Business Operations Michael Budney, Director Project Management Coordination Office Scott Hine, Director Information and Technology Services Office Steve VonVital, Director (Acting) Workforce Management Office Jennifer Blankenheim, Director Golden Field Office Timothy Meeks, Director

  8. OSTI, US Dept of Energy, Office of Scientific and Technical Information |

    Office of Scientific and Technical Information (OSTI)

    Speeding access to science information from DOE and Beyond Operations by Mary Schorn on Thu, Nov 29, 2012 Major operations for the Manhattan Engineer District (Manhattan Project) took place in remote site locations in the states of Tennessee, New Mexico, and Washington, with additional research being conducted in university laboratories at Chicago and Berkeley. At the Metallurgical Laboratory in Chicago, Enrico Fermi's experiments at the CP-1 pile took place to determine the exact amount of

  9. DOE - Office of Legacy Management -- Brunswick2_FUSRAP

    Office of Legacy Management (LM)

    Jersey New Brunswick, New Jersey, Site FUSRAP Site New Brunswick Map Background-The New Brunswick, New Jersey, Site was remediated under the Formerly Utilized Sites Remedial Action Program (FUSRAP). FUSRAP was established in 1974 to remediate sites where radioactive contamination remained from Manhattan Project and early U.S. Atomic Energy Commission (AEC) operations. History-From 1948 to 1977, the Manhattan Engineer District and AEC operated the New Brunswick Site as a general nuclear chemistry

  10. 100-OL-1 Operable Unit Pilot Study: XRF Evaluation of Select Pre-Hanford Orchards

    SciTech Connect (OSTI)

    Bunn, Amoret L.; Fritz, Brad G.; Pulsipher, Brent A.; Gorton, Alicia M.; Bisping, Lynn E.; Brandenberger, Jill M.; Pino, Christian; Martinez, Dominique M.; Rana, Komal; Wellman, Dawn M.

    2014-11-20

    Prior to the acquisition of land by the U.S. Department of War in February 1943 and the creation of the Hanford Site, the land along the Columbia River was home to over 1000 people. Farming and orchard operations by both homesteaders and commercial organizations were prevalent. Orchard activities and the associated application of lead arsenate pesticide ceased in 1943, when residents were moved from the Hanford Site at the beginning of the Manhattan Project. Today, the residues from historical application of lead arsenate pesticide persist in some locations on the Hanford Site. In 2012, the U.S. Department of Energy, U.S. Environmental Protection Agency, and Washington State Department of Ecology established the 100-OL-1 Operable Unit (OU) through the Hanford Federal Facility Agreement and Consent Order, known as the Tri-Party Agreement. The pre-Hanford orchard lands identified as the 100-OL-1 OU are located south of the Columbia River and east of the present-day Vernita Bridge, and extend southeast to the former Hanford townsite. The discontinuous orchard lands within 100-OL-1 OU are approximately 20 km2 (5000 ac). A pilot study was conducted to support the approval of the remedial investigation/feasibility study work plan to evaluate the 100-OL-1 OU. This pilot study evaluated the use of a field portable X-ray fluorescence (XRF) analyzer for evaluating lead and arsenic concentrations on the soil surface as an indicator of lead arsenate pesticide residues in the OU. The objectives of the pilot study included evaluating a field portable XRF analyzer as the analytical method for decision making, estimating the nature and extent of lead and arsenic in surface soils in four decision units, evaluating the results for the purpose of optimizing the sampling approach implemented in the remedial investigation, and collecting information to improve the cost estimate and planning the cultural resources review for sampling activities in the remedial investigation. Based on the results of the pilot study, the recommendations for the revision of the work plan are as follows: characterize the surface soil using field portable XRF measurements with confirmatory inductively coupled plasma mass spectroscopy sampling for the remedial investigation establish decision units of similar defined areas establish a process for field investigation of soil concentrations exceeding the screening criteria at the border of the 100-OL-1 OU define data quality objectives for the work plan using the results of the pilot study and refining the sampling approach for the remedial investigation.

  11. Hallmark Project

    Office of Environmental Management (EM)

    Project Commercialization of the Secure SCADA Communications Protocol, a cryptographic security solution for device-to-device communication Increased connectivity and automation in the control systems that manage the nation's energy infrastructure have improved system functionality, but left systems more vulnerable to cyber attack. Intruders could severely disrupt control system operation by sending fabricated information or commands to control system devices. To ensure message integrity,

  12. Early Oak Ridge Home | Y-12 National Security Complex

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Home Early Oak Ridge Home A typical dwelling predating the Manhattan Project homes

  13. Evaluation Project 4492

    National Nuclear Security Administration (NNSA)

    12-2010 NNSA-B-10-0412 Sandia National Laboratories/New Mexico (SNL/NM) proposes to support the Bio-Response Operational Testing and Evaluation (BOTE) project. The BOTE project would involve multiple releases of a biological simulant, characterization sampling, decontamination, and clearance sampling, at the Idaho National Laboratory (INL) Test Site. Sandia Site Office Bio-Response Operational Testing and Evaluation (BOTE) Project (TA-I, TA-III, & Offsite at INL) INL LACY,SUSAN DOYLENE

  14. Final environmental assessment for the U.S. Department of Energy, Oak Ridge Operations receipt and storage of uranium materials from the Fernald Environmental Management Project site

    SciTech Connect (OSTI)

    1999-06-01

    Through a series of material transfers and sales agreements over the past 6 to 8 years, the Fernald Environmental Management Project (FEMP) has reduced its nuclear material inventory from 14,500 to approximately 6,800 metric tons of uranium (MTU). This effort is part of the US Department of energy`s (DOE`s) decision to change the mission of the FEMP site; it is currently shut down and the site is being remediated. This EA focuses on the receipt and storage of uranium materials at various DOE-ORO sites. The packaging and transportation of FEMP uranium material has been evaluated in previous NEPA and other environmental evaluations. A summary of these evaluation efforts is included as Appendix A. The material would be packaged in US Department of Transportation-approved shipping containers and removed from the FEMP site and transported to another site for storage. The Ohio Field Office will assume responsibility for environmental analyses and documentation for packaging and transport of the material as part of the remediation of the site, and ORO is preparing this EA for receipt and storage at one or more sites.

  15. IMPACTS OF INTERACTING ELEVATED ATMOSPHERIC CO2 AND O3 ON THE STRUCTURE AND FUNCTIONING OF A NORTHERN FOREST ECOSYSTEM: OPERATING AND DECOMMISSIONING THE ASPEN FACE PROJECT

    SciTech Connect (OSTI)

    Burton, Andrew J.; Zak, Donald R.; Kubiske, Mark E.; Pregitzer, Kurt S.

    2014-06-30

    Two of the most important and pervasive greenhouse gases driving global change and impacting forests in the U.S. and around the world are atmospheric CO2 and tropospheric O3. As the only free air, large-scale manipulative experiment studying the interaction of elevated CO2 and O3 on forests, the Aspen FACE experiment was uniquely designed to address the long-term ecosystem level impacts of these two greenhouse gases on aspen-birch-maple forests, which dominate the richly forested Lake States region. The project was established in 1997 to address the overarching scientific question: “What are the effects of elevated [CO2] and [O3], alone and in combination, on the structure and functioning of northern hardwood forest ecosystems?” From 1998 through the middle of the 2009 growing season, we examined the interacting effects of elevated CO2 and O3 on ecosystem processes in an aggrading northern forest ecosystem to compare the responses of early-successional, rapid-growing shade intolerant trembling aspen and paper birch to those of a late successional, slower growing shade tolerant sugar maple. Fumigations with elevated CO2 (560 ppm during daylight hours) and O3 (approximately 1.5 x ambient) were conducted during the growing season from 1998 to 2008, and in 2009 through harvest date. Response variables quantified during the experiment included growth, competitive interactions and stand dynamics, physiological processes, plant nutrient status and uptake, tissue biochemistry, litter quality and decomposition rates, hydrology, soil respiration, microbial community composition and respiration, VOC production, treatment-pest interactions, and treatment-phenology interactions. In 2009, we conducted a detailed harvest of the site. The harvest included detailed sampling of a subset of trees by component (leaves and buds, fine branches, coarse branches and stem, coarse roots, fine roots) and excavation of soil to a depth of 1 m. Throughout the experiment, aspen and birch photosynthesis increased with elevated CO2 and tended to decrease with elevated O3, compared to the control. In contrast to aspen and birch, maple photosynthesis was not enhanced by elevated CO2. Elevated O3 did not cause significant reductions in maximum photosynthesis in birch or maple. In addition, photosynthesis in ozone sensitive clones was affected to a much greater degree than that in ozone tolerant aspen clones. Treatment effects on photosynthesis contributed to CO2 stimulation of aboveground and belowground growth that was species and genotype dependent, with birch and aspen being most responsive and maple being least responsive. The positive effects of elevated CO2 on net primary productivity NPP were sustained through the end of the experiment, but negative effects of elevated O3 on NPP had dissipated during the final three years of treatments. The declining response to O3 over time resulted from the compensatory growth of O3-tolerant genotypes and species as the growth of O3-sensitive individuals declined over time. Cumulative NPP over the entire experiment was 39% greater under elevated CO2 and 10% lower under elevated O3. Enhanced NPP under elevated CO2 was sustained by greater root exploration of soil for growth-limiting N, as well as more rapid rates of litter decomposition and microbial N release during decay. Results from Aspen FACE clearly indicate that plants growing under elevated carbon dioxide, regardless of community type or ozone level, obtained significantly greater amounts of soil N. These results indicate that greater plant growth under elevated carbon dioxide has not led to “progressive N limitation”. If similar forests growing throughout northeastern North America respond in the same manner, then enhanced forest NPP under elevated CO2 may be sustained for a longer duration than previously thought, and the negative effect of elevated O3 may be diminished by compensatory growth of O3-tolerant plants as they begin to dominate forest communities. By the end of the experiment, elevated CO2 increased ecosystem C content by 11%, whereas elevated O3 decreased ecosystem C content by 9%. Total ecosystem C content in the interaction treatment (elevated CO2 and O3) did not significantly differ from that of the control. Total ecosystem C content responded similarly to the treatments across the three forest communities. The treatment effects on ecosystem C content resulted from differences in tree biomass, particularly woody tissues (branches, stem, and coarse roots), and lower C content in the near-surface mineral soil. During its duration, the Aspen FACE project involved collaboration between scientists from 9 countries, and over the course of the experiment there were over 120 Aspen FACE scientific users. These scientists helped produce 75 publications during the most recent funding period (2008-2014) and 207 peer-reviewed publications (169 in refereed journals) since the beginning of the project.

  16. Business Operations | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Operations Business Operations The Office of Business Operations is the central organization for all Office of Energy Efficiency and Renewable Energy (EERE) organizational products and services, processes, and systems. The four main offices and managers of Business Operations - the Project Management Coordination Office, the Information Technology and Services Office, Workforce Management Office and the Golden Field Office - are outlined in the Business Operations organization chart. Offices

  17. Independent Activity Report, West Valley Demonstration Project...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    West Valley Demonstration Project - July 2012 Independent Activity Report, West Valley Demonstration Project - July 2012 July 2012 Operational Awareness Oversight of the West...

  18. DOE - Office of Legacy Management -- Oakridge_FUSRAP

    Office of Legacy Management (LM)

    Tennessee Oak Ridge, Tennessee, Warehouses Site FUSRAP Site Oak Ridge Warehouses Map Background-The Oak Ridge Warehouses Site, located in Oak Ridge, Tennessee, was remediated under the Formerly Utilized Sites Remedial Action Program (FUSRAP). FUSRAP was established in 1974 to remediate sites where radioactive contamination remained from Manhattan Project and early U.S. Atomic Energy Commission operations. History-The Oak Ridge Warehouses Site was used in the early 1940s by the Manhattan Engineer

  19. DOE - Office of Legacy Management -- ChicNorth_FUSRAP

    Office of Legacy Management (LM)

    North, Illinois, Site FUSRAP Site Chicago North Map Background-The Chicago North, Illinois, Site was remediated under the Formerly Utilized Sites Remedial Action Program (FUSRAP). FUSRAP was established in 1974 to remediate sites where radioactive contamination remained from Manhattan Project and early U.S. Atomic Energy Commission operations. History-The Chicago North Site is owned by the State of Illinois and used as a National Guard Armory. Between 1942 and 1951, the Manhattan Engineer

  20. DOE - Office of Legacy Management -- ColumbusEast_FUSRAP

    Office of Legacy Management (LM)

    Columbus East, Ohio, Site FUSRAP Site Columbus East Map Background-The Columbus East Site in Columbus, Ohio, was remediated under the Formerly Utilized Sites Remedial Action Program (FUSRAP). FUSRAP was established in 1974 to remediate sites where radioactive contamination remained from Manhattan Project and early U.S. Atomic Energy Commission operations. History-At the Columbus East Site uranium metal was heated and extruded into rods for the Manhattan Engineer District, contaminating building

  1. DOE - Office of Legacy Management -- Hamilton_FUSRAP

    Office of Legacy Management (LM)

    Ohio Hamilton, Ohio, Site FUSRAP Site Hamilton Map Background-The Hamilton, Ohio, Site was remediated under the Formerly Utilized Sites Remedial Action Program (FUSRAP). FUSRAP was established in 1974 to remediate sites where radioactive contamination remained from Manhattan Project and early U.S. Atomic Energy Commission operations. History-Intermittently from 1943 to 1951, the Herring-Hall-Marvin Safe Company fabricated slugs from rolled natural uranium metal stock for use by the Manhattan

  2. DOE - Office of Legacy Management -- Toledo_FUSRAP

    Office of Legacy Management (LM)

    Ohio Toledo, Ohio, Site FUSRAP Site Toledo Map Background-The Toledo, Ohio, Site was remediated under the Formerly Utilized Sites Remedial Action Program (FUSRAP). FUSRAP was established in 1974 to remediate sites where radioactive contamination remained from Manhattan Project and early U.S. Atomic Energy Commission operations. History-During the early and mid-1940s, Baker Brothers, Inc., fabricated slugs from natural uranium metal for the Manhattan Engineer District. In 1992, DOE designated the

  3. EA-1903-NoticeofScoping-2012.pdf

    Office of Environmental Management (EM)

    SCOPING The U.S. Department of Energy (DOE) is requesting public input on the scope of environmental issues and alternatives to be addressed in the: Environmental Assessment Kansas State Univ. Zond Wind Energy Project Manhattan, Kansas The U.S. Department of Energy (DOE) is proposing to authorize the expenditure of federal funding to Kansas State University (KSU) to refurbish, install, operate, and maintain a 750- kilowatt Zond wind turbine on KSU property north of Manhattan, Kansas. An

  4. About Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    DOE Projects MicroBooNE Project Web Pages The Project Pages hold information and links for the collaboration and its Project Managers, and also hold links to project Director's and...

  5. Tribal Renewable Energy Webinar: Project Development for Long Term Tribal Energy

    Broader source: Energy.gov [DOE]

    The webinar will cover how to determine project savings and production potential estimates, define project options, refine the project, implement the project, and plan for operations and maintenance.

  6. Operational results of National Solar Demonstration Projects

    SciTech Connect (OSTI)

    Waite, E.V.

    1981-01-01

    Included in the National Solar Demonstration Program are examples of earth-sheltered, passive solar designs. The data obtained from these sites presents an interesting look at what is both technically and economically feasible. Data from four demonstration sites that are members of the National Solar Data Network are utilized to present an economic and technical analyses of a group of four sites. Three of these sites are earth sheltered residential structures, the fourth is a commercial passive structure. This sample of four demonstration sites is not intended to provide a statistical representation of passive earth sheltered structures, but rather, an example of the type of information available through the National Solar Data Program and how this information may be utilized.

  7. NREL: Transmission Grid Integration - Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Projects NREL's transmission integration projects provide data and models that help utilities and policymakers make informed decisions about the integration of variable generation, such as solar and wind energy, into the electric power system. Researchers are exploring the potential impacts of higher penetrations of solar and wind power on system operations. Our projects provide insights that enable improved and economical operation practices. Some projects also analyze bulk power market

  8. Concept of Operations: Essence

    SciTech Connect (OSTI)

    Hutton, William J.

    2014-04-01

    This concept of operations is designed to give the reader a brief overview of the National Rural Electric Cooperative Association’s Essence project and a description of the Essence device design. The data collected by the device, how the data are used, and how the data are protected are also discussed in this document.

  9. Conduct of Operations

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2010-06-29

    This Order defines the requirements for establishing and implementing Conduct of Operations Programs at Department of Energy (DOE), including National Nuclear Security Administration (NNSA), facilities and projects. Cancels DOE O 5480.19. Admin Chg 1, dated 6-25-13, cancels DOE O 422.1. Certified 12-3-14.

  10. SPEAR Operations

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Operations SPEAR Status SPEAR Status SPEAR Status Web Message Management (authorized access only) ED's stuff Run statistic (preliminary and unofficial) Training Sessions 10/20/03 rev-3 The schedule of talks listed below have a machine operations focus and are intended for operators, physicists and support personnel who will participate in SPEAR3 commissioning and operation. The talks are video taped and stored in the control room along with any pertinent hardcopies for future reference. Date

  11. Gasification Systems Project Information

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Project Information Gasifier Optimization Archived Projects Agreement Number Project Title Performer Name Technology Area FE0023497 Alstom's Limestone Chemical Looping Gasification Process for High Hydrogen Syngas Generation Alstom Power, Inc Gasification Systems FE0023577 Advanced Gasifier and Water Gas Shift Technologies for Low Cost Coal Conversion to High Hydrogen Syngas Gas Technology Institute Coal & Coal-Biomass to Liquids, Gasification Systems FE0023915 Pilot Scale Operation and

  12. Operational Excellence

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Operational Excellence /about/_assets/images/icon-70th.jpg Operational Excellence The Lab's mission is to develop and apply science and technology to ensure the safety, security, and reliability of the U.S. nuclear deterrent; reduce global threats; and solve other emerging national security and energy challenges. aeiral shot of los alamos, new mexico What Los Alamos gets done as a premier national security science laboratory depends on how we do it The Laboratory's operations and business

  13. Project Reports for Hualapai Tribe- 2005 Project

    Broader source: Energy.gov [DOE]

    The Hualapai Tribe is located on the end of their existing utility grid which has subjected them to high costs and poor reliability of electric service. The first phase of the project will establish a tribally operated utility to provide service to tribal customers at Grand Canyon West, which has been operating without grid power for the past seven years. The second phase of the project will examine the feasibility and strategy for establishing a tribal utility to serve the remainder of the Hualapai Reservation.

  14. operations center

    National Nuclear Security Administration (NNSA)

    servers and other critical Operations Center equipment

  15. Independent air supply system filtered to protect against biological and radiological agents (99.7%).
  16. <...

  17. Emery Station Operations Center

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Emery Station Operations Center

  18. High Operating Temperature Liquid Metal Heat Transfer Fluids...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    High Operating Temperature Liquid Metal Heat Transfer Fluids High Operating Temperature Liquid Metal Heat Transfer Fluids This fact sheet describes a UCLA-led solar project to ...

  19. Research Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    LaboratoryNational Security Education Center Menu NSEC Educational Programs Los Alamos Dynamics Summer School Science of Signatures Advanced Studies Institute Judicial Science School SHM Data Sets and Software Research Projects Current Projects Past Projects Publications NSEC » Engineering Institute » Research Projects » Joint Los Alamos National Laboratory/UCSD research projects Past Research Projects Previous collaborations between Los Alamos National Laboratory and the University of

  20. 2013 Annual Planning Summary for the Idaho Operations Office

    Broader source: Energy.gov [DOE]

    The ongoing and projected Environmental Assessments and Environmental Impact Statements for 2013 and 2014 within the Idaho Operations Office.

  21. 2012 Annual Planning Summary for Savannah River Operations Office

    Office of Energy Efficiency and Renewable Energy (EERE)

    The ongoing and projected Environmental Assessments and Environmental Impact Statements for 2012 and 2013 within Savannah River Operations Office.

  22. Research Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Current Research Projects Joint Los Alamos National LaboratoryUCSD Research Projects Collaborations between Los Alamos National Laboratory and the University of California at San...

  1. Project Management

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Project Management Project Management MaRIE is the experimental facility needed to control the time-dependent properties of materials for national security science missions. It...

  2. Project Accounts

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Project Accounts Project Accounts A redirector page has been set up without anywhere to redirect to. Last edited: 2016-02-01 08:06:53

  3. DIGESTER GAS - FUEL CELL - PROJECT

    SciTech Connect (OSTI)

    Dr.-Eng. Dirk Adolph; Dipl.-Eng. Thomas Saure

    2002-03-01

    GEW has been operating the first fuel cell in Europe producing heat and electricity from digester gas in an environmentally friendly way. The first 9,000 hours in operation were successfully concluded in August 2001. The fuel cell powered by digester gas was one of the 25 registered ''Worldwide projects'' which NRW presented at the EXPO 2000. In addition to this, it is a key project of the NRW State Initiative on Future Energies. All of the activities planned for the first year of operation were successfully completed: installing and putting the plant into operation, the transition to permanent operation as well as extended monitoring till May 2001.

  4. Project Controls

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    Project controls are systems used to plan, schedule, budget, and measure the performance of a project/program. The cost estimation package is one of the documents that is used to establish the baseline for project controls. This chapter gives a brief description of project controls and the role the cost estimation package plays.

  5. Project Information

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Project Information Slider award map The REE Program funds projects focused on developing economically feasible and environmentally benign technologies for recovering REEs from coal and/or coal by-products. Project Information The listed projects represent the current REE program portfolio. Agreement Number Project Title Performer Name FWP-ORD REE FY2016-2020 Rare Earth Elements (REE) from Coal and Coal By-Products National Energy Technology Laboratory

  6. Hualapai Tribe- 2005 Project

    Broader source: Energy.gov [DOE]

    The Hualapai Tribe is located on the end of their existing utility grid which has subjected them to high costs and poor reliability of electric service. The first phase of the project will establish a tribally operated utility to provide service to tribal customers at Grand Canyon West, which has been operating without grid power for the past seven years. The second phase of the project will examine the feasibility and strategy for establishing a tribal utility to serve the remainder of the Hualapai Reservation.

  7. Lake Charles CCS Project

    SciTech Connect (OSTI)

    Leib, Thomas; Cole, Dan

    2015-06-30

    In late September 2014 development of the Lake Charles Clean Energy (LCCE) Plant was abandoned resulting in termination of Lake Charles Carbon Capture and Sequestration (CCS) Project which was a subset the LCCE Plant. As a result, the project was only funded through Phase 2A (Design) and did not enter Phase 2B (Construction) or Phase 2C (Operations). This report was prepared relying on information prepared and provided by engineering companies which were engaged by Leucadia Energy, LLC to prepare or review Front End Engineering and Design (FEED) for the Lake Charles Clean Energy Project, which includes the Carbon Capture and Sequestration (CCS) Project in Lake Charles, Louisiana. The Lake Charles Carbon Capture and Sequestration (CCS) Project was to be a large-scale industrial CCS project intended to demonstrate advanced technologies that capture and sequester carbon dioxide (CO2) emissions from industrial sources into underground formations. The Scope of work was divided into two discrete sections; 1) Capture and Compression prepared by the Recipient Leucadia Energy, LLC, and 2) Transport and Sequestration prepared by sub-Recipient Denbury Onshore, LLC. Capture and Compression-The Lake Charles CCS Project Final Technical Report describes the systems and equipment that would be necessary to capture CO2 generated in a large industrial gasification process and sequester the CO2 into underground formations. The purpose of each system is defined along with a description of its equipment and operation. Criteria for selection of major equipment are provided and ancillary utilities necessary for safe and reliable operation in compliance with environmental regulations are described. Construction considerations are described including a general arrangement of the CCS process units within the overall gasification project. A cost estimate is provided, delineated by system area with cost breakdown showing equipment, piping and materials, construction labor, engineering, and other costs. The CCS Project Final Technical Report is based on a Front End Engineering and Design (FEED) study prepared by SK E&C, completed in [June] 2014. Subsequently, Fluor Enterprises completed a FEED validation study in mid-September 2014. The design analyses indicated that the FEED package was sufficient and as expected. However, Fluor considered the construction risk based on a stick-build approach to be unacceptable, but construction risk would be substantially mitigated through utilization of modular construction where site labor and schedule uncertainty is minimized. Fluor’s estimate of the overall EPC project cost utilizing the revised construction plan was comparable to SKE&C’s value after reflecting Fluor’s assessment of project scope and risk characteristic. Development was halted upon conclusion of Phase 2A FEED and the project was not constructed.Transport and Sequestration – The overall objective of the pipeline project was to construct a pipeline to transport captured CO2 from the Lake Charles Clean Energy project to the existing Denbury Green Line and then to the Hastings Field in Southeast Texas to demonstrate effective geologic sequestration of captured CO2 through commercial EOR operations. The overall objective of the MVA portion of the project was to demonstrate effective geologic sequestration of captured CO2 through commercial Enhanced Oil Recovery (EOR) operations in order to evaluate costs, operational processes and technical performance. The DOE target for the project was to capture and implement a research MVA program to demonstrate the sequestration through EOR of approximately one million tons of CO2 per year as an integral component of commercial operations.

  8. Tulalip Tribe - Biogas Project

    Energy Savers [EERE]

    Bio-Gas Project Daryl Williams November 18, 2008 Introduction Background Description of Project Partnership Feasibility Study/Business Plan Creation of Quil Ceda Power Funding Creation of Qualco Energy Closing Background Land-Use Changes from Agriculture to Other Types of Development Skykomish River WQ Problems Bacteria Nutrient Loading Relationship Between Tribes and Dairies Poor Economy for Dairy Operations Project Description Sewage Treatment for

  9. Operating Strategies

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Operating Strategies and Design Recommendations for Mitigating Local Damage Effects in Offshore Turbine Blades Phillip W. Richards phillip@gatech.edu Graduate Research Assistant Daniel Guggenheim School of Aerospace Engineering Atlanta, Georgia, USA D. Todd Griffith dgriffi@sandia.gov Principal Member of the Technical Staff Sandia National Laboratories Albuquerque, New Mexico, USA Dewey H. Hodges dhodges@gatech.edu Professor Daniel Guggenheim School of Aerospace Engineering Atlanta, Georgia, USA

  10. Renewable Energy Project Development and Finance: Advanced Development...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... Most costly for Tribedeveloper to acquire long-term ownership of project (large cash infusion year 10) * Tribedeveloper operates the project * Requires largest equity ...

  11. MHK Projects/Seaflow Tidal Energy System | Open Energy Information

    Open Energy Info (EERE)

    been operating the Seaflow Tidal Energy System project since May 2003. This was an experimental test rig - the successor, SeaGen is intended for commercial applications Project...

  12. Independent Activity Report, Portsmouth/Paducah Project Office...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    PortsmouthPaducah Project Office - April 2013 Independent Activity Report, PortsmouthPaducah Project Office - April 2013 April 2003 Operational Awareness Oversight of the...

  13. San Diego Gas and Electric Company Smart Grid Project | Open...

    Open Energy Info (EERE)

    system covering up to 90% of the utility's customers. The project aims to enhance reliability and reduce outage durations and operations and maintenance costs. The project...

  14. Operational Management | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Management Operational Management The Office of Management supports many leadership responsibilities for the Department of Energy (DOE), providing support for project and contract management and other administrative functions. For example, the office oversees more than $22 billion in annual contract obligations and $2 billion in financial assistance obligations. It supports the management of the Department's multi-billion dollar project portfolio, and provides the Secretary of Energy and senior

  15. Operations Office

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    (~ii~,Richland Operations Office ~Z4TESO~Richland, Washington 99352 SEP 2 2009 CERTIFIED MAIL Ms. Sarah Washburn Heart of America Northwest 1314 N.E. 5 6 th Street Suite 100 Seattle, Washington 98105 Dear Ms. Washburn: FREEDOM OF INFORMATION ACT REQUEST (FOI 2009-0067) You requested, pursuant to the Freedom of Information Act (FOJA), the following documents relating to: 1 . "The authorization, decision to use, and actual use of any and all pesticides and herbicides anywhere within the

  16. Line Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Grand Coulee Transmission Line Replacement Project Hooper Springs McNary-John Day Montana-to-Washington Transmission System Upgrade Project - M2W Olympia-Grand Coulee No. 1...

  17. Project Gnome

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Project Gnome Double Beta Decay Dark Matter Biology Repository Science Renewable Energy The first underground physics experiment near Carlsbad was Project Gnome, December 10, 1961 Totally unrelated (and many years prior) to WIPP, the Project Gnome detonation was the first U.S. underground nuclear test with the objective of using nuclear explosives for peaceful applications. Project Gnome was intended to provide a detailed understanding of the underground environment created when a nuclear

  18. PROJECT PROFILE: Brayton Energy

    Broader source: Energy.gov [DOE]

    The Brayton Energy project will integrate a solar power plant’s absorber, energy storage system, and power block into one system. By combining these elements, Brayton Energy hopes to develop a synergistic system that is less expensive to assemble, easier to permit and install, and easier to operate and maintain, resulting in low-cost electricity.

  19. Instream Flow Project

    Broader source: Energy.gov [DOE]

    As a part of the Department of Energy’s Water Power Program, the Instream Flow Project was carried out by Oak Ridge National Laboratory, Pacific Northwest National Laboratory, and Argonne National Laboratory to develop tools aimed at defining environmental flow needs for hydropower operations.

  20. Evaluation Project 4492

    National Nuclear Security Administration (NNSA)

    6 Sandia National Laboratories/New Mexico (SNL/NM), proposes to perform research, development, and testing for the Low-Earth Orbit Nanosatellite Integrated Defense Autonomous System (LEONIDAS) project, to be managed through the U.S. Air Force (USAF) Operationally Responsive Space (ORS) Office. ✖ Sandia Site Office Missile System LEONIDAS Component Development Sandia National Laboratories - New Mexico

  1. Enterprise Assessments Operational Awareness Record for the Follow-Up Review of the Idaho Site Fire Protection Program as Implemented for the Irradiated Materials Characterization Laboratory and the Advanced Mixed Waste Treatment Project, OAR # EA-ID-2015-10-22

    Office of Environmental Management (EM)

    EA Operational Awareness Record Report Number: EA-ID-2015-10-22 Site: Idaho Site Subject: Follow-Up Review of the Idaho Site Fire Protection Program as Implemented for the Irradiated Materials Characterization Laboratory and the Advanced Mixed Waste Treatment Project Dates of Activity: 10/19/2015 - 10/22/2015 Report Preparer: Aleem E. Boatright Activity Description / Purpose: The Office of Environment, Safety and Health Assessments, within the Office of Enterprise Assessments (EA), performed a

  2. DOE-ID Operations Summary

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    November 1, 2014 - November 30, 2014 EDITOR'S NOTE: The following is a summary of contractor operations at the Idaho National Laboratory Site, managed by the DOE- Idaho Operations Office. It has been compiled in response to a request from stakeholders for more information on health, safety and environmental incidents at DOE facilities in Idaho. It also includes a brief summary of accomplishments at the Site. POC: Danielle Miller, (208) 526-5709. Advanced Mixed Waste Treatment Project (AMWTP)

  3. DOE-ID Operations Summary

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    December 1, 2014 - December 31, 2014 EDITOR'S NOTE: The following is a summary of contractor operations at the Idaho National Laboratory Site, managed by the DOE- Idaho Operations Office. It has been compiled in response to a request from stakeholders for more information on health, safety and environmental incidents at DOE facilities in Idaho. It also includes a brief summary of accomplishments at the Site. POC: Danielle Miller, (208) 526-5709. Advanced Mixed Waste Treatment Project (AMWTP)

  4. Municipal Electric Authority of Georgia Smart Grid Project |...

    Open Energy Info (EERE)

    This project aims to reduce operating and maintenance costs, while improving the reliability of the transmission and distribution assets owned and operated by MEAG. The...

  5. Duke Energy Carolinas, LLC Smart Grid Project | Open Energy Informatio...

    Open Energy Info (EERE)

    grid operators' ability to visualize and manage the transmission system, improving reliability and grid operations. Information Page Equipment Synchrophasor...

  6. AWEA Wind Project Siting Seminar

    Broader source: Energy.gov [DOE]

    The AWEA Wind Project Siting Seminar takes an in-depth look at the latest siting challenges and identify opportunities to reduce risks associated with the siting and operation of wind farms to...

  7. NNSA project receives DOE Secretary's Award for Project Management

    National Nuclear Security Administration (NNSA)

    Improvement | National Nuclear Security Administration project receives DOE Secretary's Award for Project Management Improvement | National Nuclear Security Administration Facebook Twitter Youtube Flickr RSS People Mission Managing the Stockpile Preventing Proliferation Powering the Nuclear Navy Emergency Response Recapitalizing Our Infrastructure Countering Nuclear Terrorism About Our Programs Our History Who We Are Our Leadership Our Locations Budget Our Operations Library Bios

  8. Y-12 Steam Plant Project Received National Recognition for Project

    National Nuclear Security Administration (NNSA)

    Management Excellence | National Nuclear Security Administration Steam Plant Project Received National Recognition for Project Management Excellence | National Nuclear Security Administration Facebook Twitter Youtube Flickr RSS People Mission Managing the Stockpile Preventing Proliferation Powering the Nuclear Navy Emergency Response Recapitalizing Our Infrastructure Countering Nuclear Terrorism About Our Programs Our History Who We Are Our Leadership Our Locations Budget Our Operations

  9. PROJECT MANGEMENT PLAN EXAMPLES Project Management Plan Examples

    Office of Environmental Management (EM)

    Management Plan Examples The following material has been extracted from several project management plans. The order in which it is presented is arbitrary. The elements table below should be used to navigate to the subject of interest. Elements of Deactivation Project Planning Deactivation Project Key Planning Elements Reference DOE O 430.1A Reference DOE G 430.1-3 DOE G 430.1- 3 Fig. 1 Link to Examples Policy & Operational Decisions, Assumptions and Strategies Includes organizational

  10. Step 1: Identify Project Potential

    Energy Savers [EERE]

    1: Identify Project Potential Presentation Agenda * Brief Review of Day 1 * Step 1: Identifying Project Potential - Community Market Potential - Resource Potential - Initial Site Considerations * Tools and Resources * Small Group Exercise/Discussion 2 1/28/2016 2 1 Potential 5 Operations & Maintenance 4 Implementation 3 Refinement 2 Options 1 Potential 3 Potential Options Refinement Implementation Operations and Maintenance Step 1: Site, Scale, Resource, and Community Market Potential

  11. MHK Projects/Wavegen | Open Energy Information

    Open Energy Info (EERE)

    since 2000 with 30,000 hours of grid connected operating experience and high reliability. Project Installed Capacity (MW) 1 Number of Devices Deployed 1 Main Overseeing...

  12. Project Completion/Closeout Guide

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2011-10-26

    This Guide is developed to provide processes and information for project Closeout. It is based on the principles and requirements taken from DOE O 413.3B. This Guide addresses project transition to operations, lessons learned, physical closeout, and financial closeout. Admin Chg 1 dated 10-22-2015.

  13. The Mississippi CCS Project

    SciTech Connect (OSTI)

    Doug Cathro

    2010-09-30

    The Mississippi CCS Project is a proposed large-scale industrial carbon capture and sequestration (CCS) project which would have demonstrated advanced technologies to capture and sequester carbon dioxide (CO{sub 2}) emissions from industrial sources into underground formations. Specifically, the Mississippi CCS Project was to accelerate commercialization of large-scale CO{sub 2} storage from industrial sources by leveraging synergy between a proposed petcoke to Substitute Natural Gas (SNG) plant that is selected for a Federal Loan Guarantee and would be the largest integrated anthropogenic CO{sub 2} capture, transport, and monitored sequestration program in the U.S. Gulf Coast Region. The Mississippi CCS Project was to promote the expansion of enhanced oil recovery (EOR) in the Mississippi, Alabama and Louisiana region which would supply greater energy security through increased domestic energy production. The capture, compression, pipeline, injection, and monitoring infrastructure would have continued to sequester CO{sub 2} for many years after the completion of the term of the DOE agreement. The objectives of this project were expected to be fulfilled through two distinct phases. The overall objective of Phase 1 was to develop a fully definitive project basis for a competitive Renewal Application process to proceed into Phase 2 - Design, Construction and Operations. Phase 1 included the studies that establish the engineering design basis for the capture, compression and transportation of CO{sub 2} from the MG SNG Project, and the criteria and specifications for a monitoring, verification and accounting (MVA) plan at the Soso oil field in Mississippi. The overall objective of Phase 2, was to execute design, construction and operations of three capital projects: the CO{sub 2} capture and compression equipment, the Mississippi CO{sub 2} Pipeline to Denbury's Free State Pipeline, and an MVA system at the Soso oil field.

  14. Calutron Operations | Y-12 National Security Complex

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Operations Calutron Operations

  15. Project Management Career Development Program | Department of Energy

    Energy Savers [EERE]

    Operational Management » Certifications and Professional Development » Project Management Career Development Program Project Management Career Development Program All PMCDP-related information has been moved to Powerpedia - Project Management Career Development Program.

  16. Project Management Career Development Program | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    You are here Home » Operational Management » Certifications and Professional Development » Project Management Career Development Program Project Management Career Development Program All PMCDP-related information has been moved to Powerpedia - Project Management Career Development Program.

  17. OSTI, US Dept of Energy, Office of Scientific and Technical Information |

    Office of Scientific and Technical Information (OSTI)

    Speeding access to science information from DOE and Beyond Background by Mary Schorn on Thu, Jul 12, 2012 This year is the 70th anniversary of the establishment of the Manhattan Project, a predecessor of the U.S. Department of Energy. In honor of its impacts on science and history, a 'Manhattan Project' series on this blog will revisit various aspects of its background, establishment, operations, and immediate and long-term influences. The first of the series is about the background of the

  18. Research Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    structure whose behavior is fundamentally nonlinear. Thus, the students assigned to this project will develop control techniques that will allow an electrodynamic shake table to...

  19. Project Construction

    Office of Energy Efficiency and Renewable Energy (EERE)

    Integrating renewable energy into Federal new construction or major renovations requires effective structuring of the construction team and project schedule. This overview discusses key construction team considerations for renewable energy as well as timing and expectations for the construction phase. The project construction phase begins after a project is completely designed and the construction documents (100%) have been issued. Construction team skills and experience with renewable energy technologies are crucial during construction, as is how the integration of renewable energy affects the project construction schedule.

  20. project management

    National Nuclear Security Administration (NNSA)

    3%2A en Project Management and Systems Support http:www.nnsa.energy.govaboutusouroperationsapmprojectmanagementandsystemssupport

  1. Custom Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Energy Management Small Industrial Lighting Compressed Air ESUE Motors Federal Agriculture Custom Projects No two industrial customers are alike; each has its own unique...

  2. project management

    National Nuclear Security Administration (NNSA)

    %2A en Project Management and Systems Support http:nnsa.energy.govaboutusouroperationsapmprojectmanagementandsystemssupport

  3. Project Tour

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Project Tour Transportation Transportation to the tour will be provided from Hilton Santa Fe Buffalo Thunder to Los Alamos National Laboratory, Technical Area 55. After the...

  4. Project Complete

    Broader source: Energy.gov [DOE]

    DOE has published its Record of Decision announcing and explaining DOEs chosen project alternative and describing any commitments for mitigating potential environmental impacts. The NEPA process...

  5. Independent Oversight Review, Sodium Bearing Waste Treatment Project- Federal- June 2012

    Broader source: Energy.gov [DOE]

    Review of the Sodium Bearing Waste Treatment Project - Integrated Waste Treatment Unit Federal Operational Readiness Review

  6. Independent Oversight Review, Sodium Bearing Waste Treatment Project- Contractor- June 2012

    Broader source: Energy.gov [DOE]

    Review of the Sodium Bearing Waste Treatment Project - Integrated Waste Treatment Unit Contractor Operational Readiness Review

  7. Categorical Exclusion Determinations: Idaho Operations Office | Department

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    of Energy Idaho Operations Office Categorical Exclusion Determinations: Idaho Operations Office Categorical Exclusion Determinations issued by Idaho Operations Office. DOCUMENTS AVAILABLE FOR DOWNLOAD March 24, 2014 CX-012097: Categorical Exclusion Determination Microgrid Demonstration Project CX(s) Applied: B5.15 Date: 03/24/2014 Location(s): Idaho Offices(s): Idaho Operations Office January 22, 2014 CX-011843: Categorical Exclusion Determination Enhanced Shielding Performance of High Level

  8. Project Cost Profile Spreadsheet | Department of Energy

    Energy Savers [EERE]

    Project Cost Profile Spreadsheet Project Cost Profile Spreadsheet Under DOE O 413.3B, Program and Project Management for the Acquisition of Capital Assets, the Office of Acquisition and Project Management (OAPM) must perform a Performance Baseline External Independent Review (EIR) prior to Critical Decision (CD) 2, and a Construction/Execution Readiness EIR for all Major System projects prior to CD-3. The EIR Standard Operating Procedures (SOP) discuss all elements of EIRs including review

  9. Project Portfolio Oversight | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Business Operations » Project Management Coordination Office » Project Portfolio Oversight Project Portfolio Oversight PMCO provides oversight and risk management of the EERE project portfolio, including base-funded, Recovery Act and Congressionally Directed Projects. Goals and Priorities Complete the orderly closeout and de-obligation of EERE's Recovery Act portfolio. Regularly work with the EERE Legislative Affairs and DOE Congressional and Intergovernmental Affairs to bring an orderly close

  10. Microsoft PowerPoint - Arkansa River System Operation.ppt

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Serving The Army and the Nation Tulsa District Tulsa District Tulsa District Arkansas River System Arkansas River System Operation Operation One Corps Serving The Army and the Nation Tulsa District Overview Overview * * Tulsa District Tulsa District * * Authorized Purposes Authorized Purposes * * Types of projects and storage zones Types of projects and storage zones * * Flood damage risk reduction operation. Flood damage risk reduction operation. * * Arkansas River System Operation Arkansas

  11. Preparation for Facility Operations RM | Department of Energy

    Energy Savers [EERE]

    Preparation for Facility Operations RM Preparation for Facility Operations RM The objective of this Standard Review Plan (SRP) on Preparation for Facility Operations is to provide consistency guidance to evaluate the effectiveness of the final project closure of major construction projects for transition from Critical Decision-4 (CD-4) to facility operations. PDF icon Preparation for Facility Operations RM More Documents & Publications Code of Record Standard Review Plan (SRP) Standard

  12. 2012 Annual Planning Summary for Idaho Operations Office | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy Idaho Operations Office 2012 Annual Planning Summary for Idaho Operations Office The ongoing and projected Environmental Assessments and Environmental Impact Statements for 2012 and 2013 within Idaho Operations Office. PDF icon APS-2012-ID.pdf More Documents & Publications 2011 Annual Planning Summary for Idaho Operations Office (ID) 2010 Annual Planning Summary for Idaho Operations Office (ID

  13. Project Reports for White Mountain Apache Tribe- 2002 Project

    Office of Energy Efficiency and Renewable Energy (EERE)

    The project will involve an examination of the feasibility of a cogeneration facility at the Fort Apache Timber Company (FATCO), an enterprise of the White Mountain Apache Tribe. FATCO includes a sawmill and a remanufacturing operation that process timber harvested on the tribe's reservation. The operation's main facility is located in the reservation's largest town, Whiteriver. In addition, the tribe operates an ancillary facility in the town of Cibeque on the reservation's west side.

  14. CONNECTICUT BIOFUELS TECHNOLOGY PROJECT

    SciTech Connect (OSTI)

    BARTONE, ERIK

    2010-09-28

    DBS Energy Inc. (DBS) intends on using the Connecticut Biofuels Technology Project for the purpose of developing a small-scale electric generating systems that are located on a distributed basis and utilize biodiesel as its principle fuel source. This project will include research and analysis on the quality and applied use of biodiesel for use in electricity production, 2) develop dispatch center for testing and analysis of the reliability of dispatching remote generators operating on a blend of biodiesel and traditional fossil fuels, and 3) analysis and engineering research on fuel storage options for biodiesel of fuels for electric generation.

  15. DOE-Idaho Operations Office | Department of Energy

    Office of Environmental Management (EM)

    DOE-Idaho Operations Office DOE-Idaho Operations Office Offices in Idaho PDF icon DOE-Idaho Operations Office More Documents & Publications Idaho Cleanup Project CH2M-WG Idaho, LLC Bechtel BWXT Idaho, LLCAdvanced Mixed Waste Treatment Project Enforcement Letter, Bechtel BWXT Idaho, LLC - March 17, 2008

  16. Awarded projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    projects Awarded projects 2016 Allocation Awards This page lists the allocation awards for NERSC for the 2016 allocation year (Jan 12, 2016 through Jan 09, 2017). Read More » Previous Year Awards Last edited: 2016-02-01 08:07:34

  17. River Protection Project (RPP) Project Management Plan

    SciTech Connect (OSTI)

    NAVARRO, J.E.

    2001-03-07

    The Office of River Protection (ORP) Project Management Plan (PMP) for the River Protection Project (RPP) describes the process for developing and operating a Waste Treatment Complex (WTC) to clean up Hanford Site tank waste. The Plan describes the scope of the project, the institutional setting within which the project must be completed, and the management processes and structure planned for implementation. The Plan is written from the perspective of the ORP as the taxpayers' representative. The Hanford Site, in southeastern Washington State, has one of the largest concentrations of radioactive waste in the world, as a result of producing plutonium for national defense for more than 40 years. Approximately 53 million gallons of waste stored in 177 aging underground tanks represent major environmental, social, and political challenges for the U.S. Department of Energy (DOE). These challenges require numerous interfaces with state and federal environmental officials, Tribal Nations, stakeholders, Congress, and the US Department of Energy-Headquarters (DOE-HQ). The cleanup of the Site's tank waste is a national issue with the potential for environmental and economic impacts to the region and the nation.

  18. DOE-Idaho Operations Summary For Dec. 9 to Dec. 21, 2009

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Mexico for disposal. Idaho Cleanup Project No items to report. Operational Summary Buried Waste Excavation Activities: Construction of the Advanced Retrieval Project-IV, which will...

  19. PROJECT PROFILE: Purdue University

    Broader source: Energy.gov [DOE]

    This project will create millichanneled heat exchangers made up of mechanically-, thermally-, and chemically-robust, high-temperature composite materials. It will demonstrate the capability of such heat exchangers for operation in high-temperature heat transfer fluids and supercritical carbon dioxide (sCO2) at a temperatures of up to 800°C. The proposed composites have demonstrated to be highly-resistant to thermal shock and are able to operate in a sCO2 environment at 800°C.

  20. The Wind Forecast Improvement Project (WFIP). A Public/Private Partnership for Improving Short Term Wind Energy Forecasts and Quantifying the Benefits of Utility Operations -- the Northern Study Area

    SciTech Connect (OSTI)

    Finley, Cathy

    2014-04-30

    This report contains the results from research aimed at improving short-range (0-6 hour) hub-height wind forecasts in the NOAA weather forecast models through additional data assimilation and model physics improvements for use in wind energy forecasting. Additional meteorological observing platforms including wind profilers, sodars, and surface stations were deployed for this study by NOAA and DOE, and additional meteorological data at or near wind turbine hub height were provided by South Dakota State University and WindLogics/NextEra Energy Resources over a large geographical area in the U.S. Northern Plains for assimilation into NOAA research weather forecast models. The resulting improvements in wind energy forecasts based on the research weather forecast models (with the additional data assimilation and model physics improvements) were examined in many different ways and compared with wind energy forecasts based on the current operational weather forecast models to quantify the forecast improvements important to power grid system operators and wind plant owners/operators participating in energy markets. Two operational weather forecast models (OP_RUC, OP_RAP) and two research weather forecast models (ESRL_RAP, HRRR) were used as the base wind forecasts for generating several different wind power forecasts for the NextEra Energy wind plants in the study area. Power forecasts were generated from the wind forecasts in a variety of ways, from very simple to quite sophisticated, as they might be used by a wide range of both general users and commercial wind energy forecast vendors. The error characteristics of each of these types of forecasts were examined and quantified using bulk error statistics for both the local wind plant and the system aggregate forecasts. The wind power forecast accuracy was also evaluated separately for high-impact wind energy ramp events. The overall bulk error statistics calculated over the first six hours of the forecasts at both the individual wind plant and at the system-wide aggregate level over the one year study period showed that the research weather model-based power forecasts (all types) had lower overall error rates than the current operational weather model-based power forecasts, both at the individual wind plant level and at the system aggregate level. The bulk error statistics of the various model-based power forecasts were also calculated by season and model runtime/forecast hour as power system operations are more sensitive to wind energy forecast errors during certain times of year and certain times of day. The results showed that there were significant differences in seasonal forecast errors between the various model-based power forecasts. The results from the analysis of the various wind power forecast errors by model runtime and forecast hour showed that the forecast errors were largest during the times of day that have increased significance to power system operators (the overnight hours and the morning/evening boundary layer transition periods), but the research weather model-based power forecasts showed improvement over the operational weather model-based power forecasts at these times.

  1. The Nautilus project

    SciTech Connect (OSTI)

    Salis, J. de

    1996-02-01

    The objective of the Nautilus project is to design, build, and evaluate a subsea multiphase electrical booster system to demonstrate its operability and reliability. The subsea station will reflect the integration of existing, tested, and recently developed equipment. The integration of various technologies, control, and maintenance in a subsea environment represents the challenging aspect of the project. Boosted by a helicoaxial pump, the produced multiphase effluent receives enough energy to reach either a host platform or the shore where the classical separation and treatment operations are performed. For deep offshore developments, the concept should induce a lower investment than alternative solutions. The concept should also give access to marginal fields, currently undeveloped for economical reasons, with the benefit of maximizing existing infrastructure. Furthermore, where sea traffic or environment concerns may limit offshore surface developments, Nautilus should demonstrate itself as an economical alternative.

  2. Project Reports for Oneida Tribe of Indians of Wisconsin- 2011 Project

    Broader source: Energy.gov [DOE]

    This project will fund energy audits of approximately 44 tribally owned buildings operated by the Oneida Tribe, which total 1,031,905 square feet.

  3. POET Project Liberty, LLC

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    POET Project LIBERTY, LLC (formerly Broin Companies) Corporate HQ: Sioux Falls, South Dakota Facility Location: Emmetsburg, Palo Alto County, Iowa Description: This 21-year old Midwest-based company is the nation's largest ethanol producer, which currently operates 26 production facilities in the United States. The company produces and markets more than 1.5 billion gallons of ethanol annually. Their proposal will demonstrate the benefits of integrating an innovative lignocellulose-to- ethanol

  4. Project Evaluation Models

    Energy Savers [EERE]

    Project Evaluation Models Ian Baring-Gould Alaska Native Village Energy Development Workshop April 30, 2014 2 Why do we need options analysis? 3 There are many different energy resources Which ones are available in Alaska? 4 photovoltaics fuel cells wind turbines batteries diesels microturbines small hydro small modular biomass grid connection ...and many energy conversion technologies 5 ...which have different operating requirements, advantages, disadvantages, costs, etc. Diesel generators Wind

  5. Data Report Project Shoal Area Churchill County, Nevada

    Office of Legacy Management (LM)

    505 UCC-700 DATA REPORT PROJECT SHOAL AREA CHURCHILL COUNTY, NEVADA DOE Nevada Operations Office Las Vegas, Nevada July 1998 DATA REPORT PROJECT SHOAL AREA CHURCHILL COUNTY, NEVADA Approved by: Date: Monica Sanchez, Project Manager Off-Sites Subproject Approved by: Date: Runore C. Wycoff, Project Manager Nevada Environmental Restoration Project i Table of Contents List of Figures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

  6. Manhattan, Montana: Energy Resources | Open Energy Information

    Open Energy Info (EERE)

    Montana: Energy Resources Jump to: navigation, search Equivalent URI DBpedia Coordinates 45.8563173, -111.3307931 Show Map Loading map... "minzoom":false,"mappingservice":"goo...

  7. Manhattan, Kansas: Energy Resources | Open Energy Information

    Open Energy Info (EERE)

    Kansas: Energy Resources Jump to: navigation, search Equivalent URI DBpedia Coordinates 39.1836082, -96.5716694 Show Map Loading map... "minzoom":false,"mappingservice":"googl...

  8. 50th Anniv Manhattan.pdf

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

  9. RENOTER Project

    Broader source: Energy.gov [DOE]

    Overview of French project on thermoelectric waste heat recovery for cars and trucks with focus on cheap, available, efficient, and sustainable TE materials, as well as efficient material integration and production process.

  10. Research Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Research Projects Joint Los Alamos National Laboratory/UCSD Research Projects Collaborations between Los Alamos National Laboratory and the University of California at San Diego (UCSD) Jacobs School of Engineering Contact Institute Director Charles Farrar (505) 663-5330 Email UCSD EI Director Michael Todd (858) 534-5951 Professional Staff Assistant Jutta Kayser (505) 663-5649 Email Administrative Assistant Stacy Baker (505) 663-5233 Email "Since 2003, LANL has funded numerous collaborative

  11. STANDARD OPERATING PROTOCOLS FOR DECOMMISSIONING

    SciTech Connect (OSTI)

    Foss, D. L.; Stevens, J. L.; Gerdeman, F. W.

    2002-02-25

    Decommissioning projects at Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) sites are conducted under project-specific decision documents, which involve extensive preparation time, public comment periods, and regulatory approvals. Often, the decision documents must be initiated at least one year before commencing the decommissioning project, and they are expensive and time consuming to prepare. The Rocky Flats Environmental Technology Site (RFETS) is a former nuclear weapons production plant at which hazardous substances and wastes were released or disposed during operations. As a result of the releases, RFETS was placed on the National Priorities List in 1989, and is conducting cleanup activities under a federal facilities compliance agreement. Working closely with interested stakeholders and state and federal regulatory agencies, RFETS has developed and implemented an improved process for obtaining the approvals. The key to streamlining the approval process has been the development of sitewide decision documents called Rocky Flats Cleanup Agreement Standard Operating Protocols or ''RSOPs.'' RSOPs have broad applicability, and could be used instead of project-specific documents. Although no two decommissioning projects are exactly the same and they may vary widely in contamination and other hazards, the basic steps taken for cleanup are usually similar. Because of this, using RSOPs is more efficient than preparing a separate project-specific decision documents for each cleanup action. Over the Rocky Flats cleanup life cycle, using RSOPs has the potential to: (1) Save over 5 million dollars and 6 months on the site closure schedule; (2) Eliminate preparing one hundred and twenty project-specific decision documents; and (3) Eliminate writing seventy-five closure description documents for hazardous waste unit closure and corrective actions.

  12. UNITED STATES ATOMIC ENERGY COMMISSION CHICAGO OPERATIONS OFFICE

    Office of Legacy Management (LM)

    ," . i ' > ;.:a c. JAN 17 1975 Martin B. Biles, Director Division of Operational Safety, HQ DISPOSAL OF SCRAP COPPER, CYCLOTRON DISMANTLING PROJECT, NUCLEAR RESEARCH...

  13. 2011 Annual Planning Summary for Chicago Operations Office (CH)

    Broader source: Energy.gov [DOE]

    The ongoing and projected Environmental Assessments and Environmental Impact Statements for 2011 and 2012 within the Chicago Operations Office (CH) (See Science APS).

  14. MEMORANDUM FORMA TTHEW S. MCCORMICK MANAGER RICHLAND OPERATIONS...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    , SUBJECT: ENVIRONMENTAL MANAGEMENT Delegation of Acquisition Executive AuthorJty for Capital Asset Projects at. Richland Operations Office In accordance with the guidelines of...

  15. 2011 Annual Planning Summary for Savannah River Operations Office (SRS)

    Broader source: Energy.gov [DOE]

    The ongoing and projected Environmental Assessments and Environmental Impact Statements for 2011 and 2012 within the Savannah River Operations Office (SRS) (See also Environmental Management).

  16. Project Management Information Systems (PMIS) | Department of Energy

    Energy Savers [EERE]

    Project Management Information Systems (PMIS) Project Management Information Systems (PMIS) Project Management Information Systems (PMIS) Project Assessment & Reporting System (PARS IIe) Office of Project Management Oversight & Assessments (PM) manages and operates Project Assessment and Reporting System (PARS IIe) - the Department's official "System of Record" for project information, documentation, and performance data of all non-IT Capital Asset Acquisitions. It is used by

  17. Design and Operation of A Setup with A Camera and Adjustable Mirror to Inspect the Sense-Wire Planes of the Time Projection Chamber Inside the MicroBooNE Cryostat

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Carls, Benjamin; Horton-Smith, Glenn; James, Catherine C.; Kubinski, Robert M.; Pordes, Stephen; Schukraft, Anne; Strauss, Thomas

    2015-08-26

    Detectors in particle physics, particularly when including cryogenic components, are often enclosed in vessels that do not provide any physical or visual access to the detectors themselves after installation. However, it can be desirable for experiments to visually investigate the inside of the vessel. The MicroBooNE cryostat hosts a TPC with sense-wire planes, which had to be inspected for damage such as breakage or sagging. This inspection was performed after the transportation of the vessel with the enclosed detector to its final location, but before filling with liquid argon. Our paper describes an approach to view the inside of themore » MicroBooNE cryostat with a setup of a camera and a mirror through one of its cryogenic service nozzles. The paper also describes the camera and mirror chosen for the operation, the illumination, and the mechanical structure of the setup. It explains how the system was operated and demonstrates its performance.« less

  18. Transforming the Commercial Building Operations- 2014 BTO Peer Review

    Broader source: Energy.gov [DOE]

    The overall goal of this project is to train building operations staff and service providers in a systematic process for identifying and correcting no-cost building operational problems that lead to energy waste.

  19. ARM - AMF2 Operations

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    and Contacts Management and Operations Operations Overview ARM Links BCR | ECR ECO, EWO Extraview PIF, CAR, DQR & DQPR Operations Status System i.arm.gov AMF2 Deployment...

  20. Radiation Embrittlement Archive Project

    SciTech Connect (OSTI)

    Klasky, Hilda B; Bass, Bennett Richard; Williams, Paul T; Phillips, Rick; Erickson, Marjorie A; Kirk, Mark T; Stevens, Gary L

    2013-01-01

    The Radiation Embrittlement Archive Project (REAP), which is being conducted by the Probabilistic Integrity Safety Assessment (PISA) Program at Oak Ridge National Laboratory under funding from the U.S. Nuclear Regulatory Commission s (NRC) Office of Nuclear Regulatory Research, aims to provide an archival source of information about the effect of neutron radiation on the properties of reactor pressure vessel (RPV) steels. Specifically, this project is an effort to create an Internet-accessible RPV steel embrittlement database. The project s website, https://reap.ornl.gov, provides information in two forms: (1) a document archive with surveillance capsule(s) reports and related technical reports, in PDF format, for the 104 commercial nuclear power plants (NPPs) in the United States, with similar reports from other countries; and (2) a relational database archive with detailed information extracted from the reports. The REAP project focuses on data collected from surveillance capsule programs for light-water moderated, nuclear power reactor vessels operated in the United States, including data on Charpy V-notch energy testing results, tensile properties, composition, exposure temperatures, neutron flux (rate of irradiation damage), and fluence, (Fast Neutron Fluence a cumulative measure of irradiation for E>1 MeV). Additionally, REAP contains data from surveillance programs conducted in other countries. REAP is presently being extended to focus on embrittlement data analysis, as well. This paper summarizes the current status of the REAP database and highlights opportunities to access the data and to participate in the project.

  1. DOE Project Scorecards

    Broader source: Energy.gov [DOE]

    DOE Project Scorecards DOEproject scorecards summarize capital asset project performance compared to the current approved baseline.

  2. The PROJECT

    Office of Scientific and Technical Information (OSTI)

    PROJECT Copies of this publication are available while supply lasts from the Office of Scientific and Technical Information P.O. Box 62 Oak Ridge, TN 37831 Attention: Information Services Telephone: (423) 576-8401 Also Available: The United States Department of Energy: A Summary History, 1977-1994 @ Printed with soy ink on recycled paper The PROJECT U N I T E D S T A T E S D E P A R T M E N T O F E N E R G Y F.G. Gosling History Division Executive Secretariat Management and Administration

  3. SunZia Southwest Transmission Project Comments

    Broader source: Energy.gov (indexed) [DOE]

    SunZia Southwest Transmission Project Comments Provided to the US Department of Energy Office of Electricity Delivery and Energy Reliability Request for Information Relating to the Permitting of Transmission Lines Submitted as of March 28, 2012 2 1.0 Background. SunZia Southwest Transmission Project (SunZia or the Project) is a joint development effort currently underway in Arizona and New Mexico. The Project definition includes licensing, permitting, financing, constructing and operating up to

  4. Savannah River Site Waste Disposition Project

    Office of Environmental Management (EM)

    Terrel J. Spears Assistant Manager Waste Disposition Project DOE Savannah River Operations Office Savannah River Site Savannah River Site Waste Disposition Project Waste Disposition Project 2 Waste Disposition Project - Mission Radioactive Liquid Waste - Tank Waste Stabilization and Disposition - Disposition 36 million gallons of radioactive liquid waste - Close 49 underground storage tanks in which the waste now resides 3 36.7 Million 33.7 Mgal (92%) 3.0 Mgal (8%) Saltcake Sludge Salt Supernate

  5. Project Management Coordination Office | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Project Management Coordination Office Project Management Coordination Office The Project Management Coordination Office (PMCO) provides guidance, leadership, training, and tools in program and project management.to Office of Energy Efficiency and Renewable Energy (EERE) Headquarters and field employees. PMCO is an internal business operations office with a mission to provide EERE executive managers, line managers, and staff offices the unified corporate tools, products, and services that enable

  6. Project Title

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Unruh (INL) 03:30 Embedded Instrumentation and Controls for Extreme Environments Roger Kisner (ORNL) NE I&C Review Webinar Agenda September 17, 2014 PM 04:00 Operator Support ...

  7. Environmental Assessment Lakeview Geothermal Project

    SciTech Connect (OSTI)

    Treis, Tania

    2012-04-30

    The Town of Lakeview is proposing to construct and operate a geothermal direct use district heating system in Lakeview, Oregon. The proposed project would be in Lake County, Oregon, within the Lakeview Known Geothermal Resources Area (KGRA). The proposed project includes the following elements: Drilling, testing, and completion of a new production well and geothermal water injection well; construction and operation of a geothermal production fluid pipeline from the well pad to various Town buildings (i.e., local schools, hospital, and Lake County Industrial Park) and back to a geothermal water injection well. This EA describes the proposed project, the alternatives considered, and presents the environmental analysis pursuant to the National Environmental Policy Act. The project would not result in adverse effects to the environment with the implementation of environmental protection measures.

  8. The Wind Forecast Improvement Project (WFIP): A Public/Private Partnership for Improving Short Term Wind Energy Forecasts and Quantifying the Benefits of Utility Operations. The Southern Study Area, Final Report

    SciTech Connect (OSTI)

    Freedman, Jeffrey M.; Manobianco, John; Schroeder, John; Ancell, Brian; Brewster, Keith; Basu, Sukanta; Banunarayanan, Venkat; Hodge, Bri-Mathias; Flores, Isabel

    2014-04-30

    This Final Report presents a comprehensive description, findings, and conclusions for the Wind Forecast Improvement Project (WFIP) -- Southern Study Area (SSA) work led by AWS Truepower (AWST). This multi-year effort, sponsored by the Department of Energy (DOE) and National Oceanographic and Atmospheric Administration (NOAA), focused on improving short-term (15-minute - 6 hour) wind power production forecasts through the deployment of an enhanced observation network of surface and remote sensing instrumentation and the use of a state-of-the-art forecast modeling system. Key findings from the SSA modeling and forecast effort include: 1. The AWST WFIP modeling system produced an overall 10 - 20% improvement in wind power production forecasts over the existing Baseline system, especially during the first three forecast hours; 2. Improvements in ramp forecast skill, particularly for larger up and down ramps; 3. The AWST WFIP data denial experiments showed mixed results in the forecasts incorporating the experimental network instrumentation; however, ramp forecasts showed significant benefit from the additional observations, indicating that the enhanced observations were key to the model systems’ ability to capture phenomena responsible for producing large short-term excursions in power production; 4. The OU CAPS ARPS simulations showed that the additional WFIP instrument data had a small impact on their 3-km forecasts that lasted for the first 5-6 hours, and increasing the vertical model resolution in the boundary layer had a greater impact, also in the first 5 hours; and 5. The TTU simulations were inconclusive as to which assimilation scheme (3DVAR versus EnKF) provided better forecasts, and the additional observations resulted in some improvement to the forecasts in the first 1 - 3 hours.

  9. Hanford Environmental Dose Reconstruction Project

    SciTech Connect (OSTI)

    Cannon, S.D.; Finch, S.M.

    1992-10-01

    The objective of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The independent Technical Steering Panel (TSP) provides technical direction. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed from release to impact on humans (dose estimates):Source Terms, Environmental Transport, Environmental Monitoring Data, Demography, Food Consumption, and Agriculture, and Environmental Pathways and Dose Estimates.

  10. PROJECT MANAGEMENT PLANS Project Management Plans

    Office of Environmental Management (EM)

    MANAGEMENT PLANS Project Management Plans  Overview  Project Management Plan Suggested Outline Subjects  Crosswalk between the Suggested PMP Outline Subjects and a Listing of Project Planning Elements  Elements of Deactivation Project Planning  Examples From Project Management Plans Overview The purpose here is to assist project managers and project planners in creating a project plan by providing examples and pointing to information that have been successfully used by others in

  11. California Hydrogen Infrastructure Project

    SciTech Connect (OSTI)

    Edward C. Heydorn

    2013-03-12

    Air Products and Chemicals, Inc. has completed a comprehensive, multiyear project to demonstrate a hydrogen infrastructure in California. The specific primary objective of the project was to demonstrate a model of a “real-world” retail hydrogen infrastructure and acquire sufficient data within the project to assess the feasibility of achieving the nation’s hydrogen infrastructure goals. The project helped to advance hydrogen station technology, including the vehicle-to-station fueling interface, through consumer experiences and feedback. By encompassing a variety of fuel cell vehicles, customer profiles and fueling experiences, this project was able to obtain a complete portrait of real market needs. The project also opened its stations to other qualified vehicle providers at the appropriate time to promote widespread use and gain even broader public understanding of a hydrogen infrastructure. The project engaged major energy companies to provide a fueling experience similar to traditional gasoline station sites to foster public acceptance of hydrogen. Work over the course of the project was focused in multiple areas. With respect to the equipment needed, technical design specifications (including both safety and operational considerations) were written, reviewed, and finalized. After finalizing individual equipment designs, complete station designs were started including process flow diagrams and systems safety reviews. Material quotes were obtained, and in some cases, depending on the project status and the lead time, equipment was placed on order and fabrication began. Consideration was given for expected vehicle usage and station capacity, standard features needed, and the ability to upgrade the station at a later date. In parallel with work on the equipment, discussions were started with various vehicle manufacturers to identify vehicle demand (short- and long-term needs). Discussions included identifying potential areas most suited for hydrogen fueling stations with a focus on safe, convenient, fast-fills. These potential areas were then compared to and overlaid with suitable sites from various energy companies and other potential station operators. Work continues to match vehicle needs with suitable fueling station locations. Once a specific site was identified, the necessary agreements could be completed with the station operator and expected station users. Detailed work could then begin on the site drawings, permits, safety procedures and training needs. Permanent stations were successfully installed in Irvine (delivered liquid hydrogen), Torrance (delivered pipeline hydrogen) and Fountain Valley (renewable hydrogen from anaerobic digester gas). Mobile fueling stations were also deployed to meet short-term fueling needs in Long Beach and Placerville. Once these stations were brought online, infrastructure data was collected and reported to DOE using Air Products’ Enterprise Remote Access Monitoring system. Feedback from station operators was incorporated to improve the station user’s fueling experience.

  12. NREL Smart Grid Projects

    SciTech Connect (OSTI)

    Hambrick, J.

    2012-01-01

    Although implementing Smart Grid projects at the distribution level provides many advantages and opportunities for advanced operation and control, a number of significant challenges must be overcome to maintain the high level of safety and reliability that the modern grid must provide. For example, while distributed generation (DG) promises to provide opportunities to increase reliability and efficiency and may provide grid support services such as volt/var control, the presence of DG can impact distribution operation and protection schemes. Additionally, the intermittent nature of many DG energy sources such as photovoltaics (PV) can present a number of challenges to voltage regulation, etc. This presentation provides an overview a number of Smart Grid projects being performed by the National Renewable Energy Laboratory (NREL) along with utility, industry, and academic partners. These projects include modeling and analysis of high penetration PV scenarios (with and without energy storage), development and testing of interconnection and microgrid equipment, as well as the development and implementation of advanced instrumentation and data acquisition used to analyze the impacts of intermittent renewable resources. Additionally, standards development associated with DG interconnection and analysis as well as Smart Grid interoperability will be discussed.

  13. The IPHI Project

    SciTech Connect (OSTI)

    Ferdinand, Robin; Beauvais, Pierre-Yves

    2005-06-08

    High Power Proton Accelerators (HPPAs) are studied for several projects based on high-flux neutron sources driven by proton or deuteron beams. Since the front end is considered as the most critical part of such accelerators, the two French national research agencies CEA and CNRS decided to collaborate in 1997 to study and build a High-Intensity Proton Injector (IPHI). The main objective of this project is to master the complex technologies used and the concepts of manufacturing and controlling the HPPAs. Recently, a collaboration agreement was signed with CERN and led to some evolutions in the design and in the schedule. The IPHI design current was maintained at 100 mA in Continuous Wave mode. This choice should allow to produce a high reliability beam at reduced intensity (typically 30 mA) tending to fulfill the Accelerator Driven System requirements. The output energy of the Radio Frequency Quadrupole (RFQ), was reduced from 5 to 3 MeV, allowing then the adjunction and the test, in pulsed operation of a chopper line developed by CERN for the Superconducting Proton Linac (SPL). In a final step, the IPHI RFQ and the chopper line should become parts of the SPL injector. In this paper, the IPHI project and the recent evolutions are reported together with the construction and operation schedule.

  14. Protocol_for_Environmental_Management_Cleanup_Projects_(clean).pdf |

    Energy Savers [EERE]

    Department of Energy Protocol_for_Environmental_Management_Cleanup_Projects_(clean).pdf Protocol_for_Environmental_Management_Cleanup_Projects_(clean).pdf PDF icon Protocol_for_Environmental_Management_Cleanup_Projects_(clean).pdf More Documents & Publications External Independent Review (EIR) Standard Operating Procedure (SOP) October 2008 DOE EIR FM.doc External Independent Review (EIR) Standard Operating Procedure (SOP) September 2010

  15. Hydropower Projects

    SciTech Connect (OSTI)

    2015-04-02

    The Water Power Program helps industry harness this renewable, emissions-free resource to generate environmentally sustainable and cost-effective electricity. Through support for public, private, and nonprofit efforts, the Water Power Program promotes the development, demonstration, and deployment of advanced hydropower devices and pumped storage hydropower applications. These technologies help capture energy stored by diversionary structures, increase the efficiency of hydroelectric generation, and use excess grid energy to replenish storage reserves for use during periods of peak electricity demand. In addition, the Water Power Program works to assess the potential extractable energy from domestic water resources to assist industry and government in planning for our nation’s energy future. From FY 2008 to FY 2014, DOE’s Water Power Program announced awards totaling approximately $62.5 million to 33 projects focused on hydropower. Table 1 provides a brief description of these projects.

  16. Research Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Past Research Projects Composite-to-Steel Joint Integrity Monitoring and Assessment Collaboration between Los Alamos National Laboratory and the University of California at San Diego (UCSD) Jacobs School of Engineering Contact Institute Director Charles Farrar (505) 663-5330 Email UCSD EI Director Michael Todd (858) 534-5951 Professional Staff Assistant Ellie Vigil (505) 667-2818 Email Administrative Assistant Rebecca Duran (505) 665-8899 Email UCSD Faculty and Graduate Students Professor

  17. MONTICELLO PROJECTS

    Office of Legacy Management (LM)

    09 January 2010 Doc. No. S06172 Page 1 1.3 Peripheral Properties (Private and City-Owned) * No land use or supplemental standards compliance issues were observed or reported by LTSM on-site staff. Monticello National Priorities List Sites Federal Facilities Agreement (FFA) Quarterly Report: October 1-December 31, 2009 This report summarizes project status and activities implemented October through December 2009, and provides a schedule of near-term activities for the Monticello Mill Tailings

  18. MONTICELLO PROJECTS

    Office of Legacy Management (LM)

    1 July 2011 Doc. No. S07978 Page 1 Monticello, Utah, National Priorities List Sites Federal Facility Agreement (FFA) Quarterly Report: April 1-June 30, 2011 This report summarizes project status and activities implemented April through June 2011 and provides a schedule for near-term activities at the Monticello Vicinity Properties (MVP) site and the Monticello Mill Tailings Site (MMTS) located in and near Monticello, Utah. The MMTS and MVP were placed on the U.S. Environmental Protection Agency

  19. MONTICELLO PROJECTS

    Office of Legacy Management (LM)

    31, 2011 April 2011 Doc. No. S07666 Page 1 Monticello, Utah, National Priorities List Sites Federal Facility Agreement (FFA) Quarterly Report: January 1-March 31, 2011 This report summarizes project status and activities implemented January through March 2011 and provides a schedule for near-term activities at the Monticello Vicinity Properties (MVP) site and the Monticello Mill Tailings Site (MMTS) located in and near Monticello, Utah. The MMTS and MVP were placed on the U.S. Environmental

  20. The Lake Charles CCS Project

    SciTech Connect (OSTI)

    Doug Cathro

    2010-06-30

    The Lake Charles CCS Project is a large-scale industrial carbon capture and sequestration (CCS) project which will demonstrate advanced technologies that capture and sequester carbon dioxide (CO{sub 2}) emissions from industrial sources into underground formations. Specifically the Lake Charles CCS Project will accelerate commercialization of large-scale CO{sub 2} storage from industrial sources by leveraging synergy between a proposed petroleum coke to chemicals plant (the LCC Gasification Project) and the largest integrated anthropogenic CO{sub 2} capture, transport, and monitored sequestration program in the U.S. Gulf Coast Region. The Lake Charles CCS Project will promote the expansion of EOR in Texas and Louisiana and supply greater energy security by expanding domestic energy supplies. The capture, compression, pipeline, injection, and monitoring infrastructure will continue to sequester CO{sub 2} for many years after the completion of the term of the DOE agreement. The objectives of this project are expected to be fulfilled by working through two distinct phases. The overall objective of Phase 1 was to develop a fully definitive project basis for a competitive Renewal Application process to proceed into Phase 2 - Design, Construction and Operations. Phase 1 includes the studies attached hereto that will establish: the engineering design basis for the capture, compression and transportation of CO{sub 2} from the LCC Gasification Project, and the criteria and specifications for a monitoring, verification and accounting (MVA) plan at the Hastings oil field in Texas. The overall objective of Phase 2, provided a successful competitive down-selection, is to execute design, construction and operations of three capital projects: (1) the CO{sub 2} capture and compression equipment, (2) a Connector Pipeline from the LLC Gasification Project to the Green Pipeline owned by Denbury and an affiliate of Denbury, and (3) a comprehensive MVA system at the Hastings oil field.

  1. Healy Clean Coal Project

    SciTech Connect (OSTI)

    1997-12-31

    The Healy Clean Coal Project, selected by the U.S. Department of Energy under Round 111 of the Clean Coal Technology Program, has been constructed and is currently in the Phase 111 Demonstration Testing. The project is owned and financed by the Alaska Industrial Development and Export Authority (AIDEA), and is cofunded by the U.S. Department of Energy. Construction was 100% completed in mid-November of 1997, with coal firing trials starting in early 1998. Demonstration testing and reporting of the results will take place in 1998, followed by commercial operation of the facility. The emission levels of nitrogen oxides (NOx), sulfur dioxide (S02), and particulate from this 50-megawatt plant are expected to be significantly lower than current standards.

  2. Project Management Information Systems (PMIS) | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Project Management Information Systems (PMIS) Project Management Information Systems (PMIS) Project Assessment & Reporting System (PARS IIe) Office of Project Management Oversight & Assessments (PM) manages and operates Project Assessment and Reporting System (PARS IIe) - the Department's official "System of Record" for project information, documentation, and performance data of all non-IT Capital Asset Acquisitions. It is used by Federal and contractor personnel across the

  3. Audit Report: DOE/IG-0854 | Department of Energy

    Energy Savers [EERE]

    4 Audit Report: DOE/IG-0854 July 13, 2011 The Department of Energy's K-25 Building Decontamination and Decommissioning Project The East Tennessee Technology Park (ETTP), formerly the Oak Ridge Gaseous Diffusion Plant, began operation during World War II as part of the Manhattan Project. As the Department of Energy's missions changed, operations at the Plant ceased and the Department began a massive environmental remediation effort with completion anticipated in 2016. In 2001, the Department

  4. PROJECT MANGEMENT PLAN EXAMPLES Project Organization Examples

    Office of Environmental Management (EM)

    Organization Examples Example 8 4.0 PROJECT ORGANIZATION Chapter 4.0 describes the principle project organizations, including their responsibilities and relationships. Other organizations, that have an interest in the project, also are described. 4.1 Principal Project Organizations and Responsibilities The management organization for the 324/327 Buildings Stabilization/Deactivation Project represents a partnership between four principal project organizations responsible for the project. The four

  5. Project Reports for Upper Skagit Indian Tribe- 2010 Project

    Broader source: Energy.gov [DOE]

    Under this project, the tribe will explore the feasibility of wind development in an effort to achieve energy self-sufficiency by reducing the tribe's long-term operational costs and providing reasonable capital cost rate of returns and to reduce the tribe's carbon footprint and impact on climate change.

  6. MHK Projects/Manchac Point Project | Open Energy Information

    Open Energy Info (EERE)

    el":"","visitedicon":"" Project Profile Project Start Date 112008 Project City St Gabriel, LA Project StateProvince Louisiana Project Country United States Project Resource...

  7. MHK Projects/Claiborne Island Project | Open Energy Information

    Open Energy Info (EERE)

    el":"","visitedicon":"" Project Profile Project Start Date 112008 Project City St Gabriel, LA Project StateProvince Louisiana Project Country United States Project Resource...

  8. MHK Projects/Point Pleasant Project | Open Energy Information

    Open Energy Info (EERE)

    el":"","visitedicon":"" Project Profile Project Start Date 112008 Project City St Gabriel, LA Project StateProvince Louisiana Project Country United States Project Resource...

  9. MHK Projects/College Point Project | Open Energy Information

    Open Energy Info (EERE)

    bel":"","visitedicon":"" Project Profile Project Start Date 112008 Project City St James, LA Project StateProvince Louisiana Project Country United States Project Resource...

  10. Independent Activity Report, Richland Operations Office - June 2011 |

    Office of Environmental Management (EM)

    Department of Energy June 2011 Independent Activity Report, Richland Operations Office - June 2011 June 2011 Hanford Sludge Treatment Project Review [HIAR-RL-2011-06-17] This Independent Activity Report documents an operational awareness activity conducted by Office of Health, Safety and Security's Office of Safety and Emergency Management Evaluations June 13-17, 2011, at the Sludge Treatment Project at the Department of Energy's (DOE) Hanford Site. The activity consisted of touring project

  11. HIGS Flux Performance Projection

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    HIGS flux performance table for high-flux, quasi-CW operation, DFELL/TUNL, Nov. 9, 2010 (Version 2.3). HIGS Flux Performance Projection (2010 - 2011) Total Flux [g/s] CW Operation Two-Bunch (*) Collimated Flux (∆E γ /E γ = 5% FWHM) (#), (@) FEL λ [nm] Comment No-loss Mode : < 20 MeV Linear Pol. with OK-4 Circular Pol with OK-5 E γ = 1 - 2 MeV (E e = 237 - 336 MeV) 1 x 10 8 - 4 x 10 8 6 x 10 6 - 2.4 x 10 7 1064 Linear and Circular (a), (b) E γ = 2 - 2.9 MeV (E e = 336 - 405 MeV) 4 x 10

  12. Popeye Project: ROV interfaces

    SciTech Connect (OSTI)

    Scates, C.R.; Hickok, D.D.; Hernandez, D.A.

    1997-04-01

    The Popeye Project in the Gulf of Mexico helped advance the technology and standardization of ROV interfaces for deepwater subsea production systems. Some of the many successful ROV operations during installation and completion were {open_quotes}first-of-it`s-kind{close_quotes} activities-enabled by many technical advances. The use and reliance upon ROV systems for support of deepwater drilling and installation operations significantly increased in the past 10 years. Shell Offshore Inc.`s (SOI) confidence in this increased capability was an important factor in many of the design decisions which characterized the innovative system. Technology advancements, which depended on effective ROV intervention, were implemented with no significant difficulties. These advancements, in particular the flying leads and seabed position methods, are available to the industry for other deepwater subsea systems. In addition, several Popeye ROV interfaces have helped advance the subsea standardization initiative; e.g., hot stabs, torque-tool end effectors, and paint color.

  13. FUSRAP Project

    Office of Legacy Management (LM)

    Project 23b 14501 FUSRAP TECHNICAL BULLETIN N O . - R 3 v . L DATE: 1.2 9-99 SUBJECT : Pr.pec.d BY T r m L u d Approval Summary of the results for the Springdale characterization activities performed per WI-94-015, Rev. 0. TUO separate radiological characterization surveys and a limited cherical characterization survey were performed on the Springdale Site in Octcjer and December, 1993. The design of the radiological surveys were to supplement and define existing ORNL surveys. The limited

  14. PROJECT RULISON

    Office of Legacy Management (LM)

    17 RADIOLOGICAL OPERATIONS I I ' iL ROLLUP PLAN INTRODUCT ION se of t h i s rollup i s t o remove f r & the Rulison s i r e which have radioactive contamination in excess of c l e a n u F ~ r i t e r i a provided by AEC Headquarters and are.not . needed fon future operations a t the s i t e . i I TABLE O F CONTENTS S e c t i o n . T i t l e . R a d i a t i o n Monitoring P l a n A. P e r s o n n e l Monitoring B. M a t e r i a l and Hardware 11. Decontamination and D i s p o s a l ir- A. D i

  15. MHK Projects/Lunar Energy St David s Peninsula Pembrokeshire...

    Open Energy Info (EERE)

    Reform (BERR), which has contributed 2.5 million of the 10 million in development costs; and the project should be operational by 2010. Project Installed Capacity (MW) 8...

  16. Ceramic Technology Project

    SciTech Connect (OSTI)

    Not Available

    1992-03-01

    The Ceramic Technology Project was developed by the USDOE Office of Transportation Systems (OTS) in Conservation and Renewable Energy. This project, part of the OTS's Materials Development Program, was developed to meet the ceramic technology requirements of the OTS's automotive technology programs. Significant accomplishments in fabricating ceramic components for the USDOE and NASA advanced heat engine programs have provided evidence that the operation of ceramic parts in high-temperature engine environments is feasible. These programs have also demonstrated that additional research is needed in materials and processing development, design methodology, and data base and life prediction before industry will have a sufficient technology base from which to produce reliable cost-effective ceramic engine components commercially. A five-year project plan was developed with extensive input from private industry. In July 1990 the original plan was updated through the estimated completion of development in 1993. The objective is to develop the industrial technology base required for reliable ceramics for application in advanced automotive heat engines. The project approach includes determining the mechanisms controlling reliability, improving processes for fabricating existing ceramics, developing new materials with increased reliability, and testing these materials in simulated engine environments to confirm reliability. Although this is a generic materials project, the focus is on the structural ceramics for advanced gas turbine and diesel engines, ceramic bearings and attachments, and ceramic coatings for thermal barrier and wear applications in these engines. To facilitate the rapid transfer of this technology to US industry, the major portion of the work is being done in the ceramic industry, with technological support from government laboratories, other industrial laboratories, and universities.

  17. 2011 Annual Planning Summary for Idaho Operations Office (ID) | Department

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    of Energy Idaho Operations Office (ID) 2011 Annual Planning Summary for Idaho Operations Office (ID) The ongoing and projected Environmental Assessments and Environmental Impact Statements for 2011 and 2012 within the Idaho Operations Office (ID) (See Environmental Management). PDF icon 2011 Annual Planning Summary for Idaho Operations Office (ID) More Documents & Publications 2010 Annual Planning Summary for Idaho Operations Office (ID) 2012 Annual Planning Summary for SLAC Site Office

  18. 2013 Annual Planning Summary for the Savannah River Operations Office |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy Savannah River Operations Office 2013 Annual Planning Summary for the Savannah River Operations Office The ongoing and projected Environmental Assessments and Environmental Impact Statements for 2013 and 2014 within the Savannah River Operations Office. PDF icon NNSA_SROO_NEPA-APS-2013.pdf More Documents & Publications 2012 Annual Planning Summary for Savannah River Operations Office 2010 Annual Planning Summary for Savannah River Operations Office (SRS) 2012 Annual

  19. High Operating Temperature Liquid Metal Heat Transfer Fluids | Department

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    of Energy High Operating Temperature Liquid Metal Heat Transfer Fluids High Operating Temperature Liquid Metal Heat Transfer Fluids This fact sheet describes a UCLA-led solar project to investigate high operating temperature liquid metal heat transfer fluids, funded by the SunShot initiative. The project team is using a combination of modeling along with a variety of property measurement and validation studies to demonstrate that the metal alloys identified can meet all the needs of a

  20. Earned Value Management System (EVMS) Surveillance Standard Operating Procedure

    Office of Environmental Management (EM)

    Surveillance Standard Operating Procedure (ESSOP) Issued by Office of Acquisition and Project Management MA-63 September 30, 2013 V2 DEPARTMENT OF ENERGY Office of Acquisition and Project Management (OAPM) EVMS SURVEILLANCE SOP (ESSOP) SEPTEMBER 30, 2013 ii Earned Value Management System (EVMS) Surveillance Standard Operating Procedure (ESSOP) OPR: MA-63 Update V2: September 30, 2013 1. PURPOSE. This EVMS Surveillance Standard Operating Procedure (ESSOP) serves as a primary reference for OAPM

  1. What is the status of the Project

    Broader source: Energy.gov (indexed) [DOE]

    status of the Project? The frst phase of the project was energized on July 20, 2006. It operated fawlessly as an integral part of National Grid's 35-kilovolt network in Albany, serving the equivalent of 25,000 homes. It was taken offine after nine months to begin phase II of the project: replacing a 30-meter section with 2G cable, which will be the world's frst use of 2G in any utility device. Phase II of the project was energized on January 8, 2008. Project Fact Sheet Albany HTS Power Cable

  2. Director, Salt Waste Processing Facility Project Office

    Broader source: Energy.gov [DOE]

    This position is located within The Department of Energy (DOE) Savannah River (SR) Operations Office, Salt Waste Processing Facility Project Office (SWPFPO). SR is located in Aiken, South Carolina....

  3. Western Baldwin County, AL Grid Interconnection Project

    SciTech Connect (OSTI)

    Thomas DeBell

    2011-09-30

    The Objective of this Project was to provide an additional supply of electricity to the affected portions of Baldwin County, AL through the purchase, installation, and operation of certain substation equipment.

  4. Independent Oversight Assessment, Portsmouth/Paducah Project Office - May

    Energy Savers [EERE]

    2012 | Department of Energy Portsmouth/Paducah Project Office - May 2012 Independent Oversight Assessment, Portsmouth/Paducah Project Office - May 2012 May 2012 Assessment of the Portsmouth/Paducah Project Office Conduct of Operations Oversight of the Depleted Uranium Hexafluoride Conversion Plants This report provides the results of an independent assessment of the Department of Energy's (DOE) Portsmouth/Paducah Project Office oversight of conduct of operations at DOE's depleted uranium

  5. Independent Activity Report, Hanford Sludge Treatment Project - February

    Office of Environmental Management (EM)

    2012 | Department of Energy Hanford Sludge Treatment Project - February 2012 Independent Activity Report, Hanford Sludge Treatment Project - February 2012 February 2012 Hanford Sludge Treatment Project Operational Awareness Review [HIAR-RL-2012-02-27] The U.S. Department of Energy's (DOE) Office of Enforcement and Oversight, within the Office of Health, Safety and Security (HSS), performed operational awareness reviews of the Sludge Treatment Project (STP), Engineered Container Retrieval and

  6. Preliminary Project Execution Plan for the Remote-Handled Low-Level Waste Disposal Project

    SciTech Connect (OSTI)

    David Duncan

    2011-05-01

    This preliminary project execution plan (PEP) defines U.S. Department of Energy (DOE) project objectives, roles and responsibilities of project participants, project organization, and controls to effectively manage acquisition of capital funds for construction of a proposed remote-handled low-level waste (LLW) disposal facility at the Idaho National Laboratory (INL). The plan addresses the policies, requirements, and critical decision (CD) responsibilities identified in DOE Order 413.3B, 'Program and Project Management for the Acquisition of Capital Assets.' This plan is intended to be a 'living document' that will be periodically updated as the project progresses through the CD process to construction and turnover for operation.

  7. REP&V TO ATTNJF: NE-23 SUWECC Commercial Facilities Used by National Lead Company of Ohio in Support

    Office of Legacy Management (LM)

    REP&V TO ATTNJF: NE-23 SUWECC Commercial Facilities Used by National Lead Company of Ohio in Support 'of FMPC Operations TO: Robert E. Lynch Procuresnent and CorXracts Division, AD-42 Oak Ridge Operations Office The Division of Facility and Site Decormnissioning Projects (DFSP) is responsible for managing the Department's Formerly Utilized Sites Remedial Action Program (FUSRAP). The purposes of FUSRAP are (1) to identify facilities formerly operated for or by the Manhattan Engineer District

  8. Interstate Electrification Improvement Project

    SciTech Connect (OSTI)

    Puckette, Margaret; Kim, Jeff

    2015-07-01

    The Interstate Electrification Improvement Project, publicly known as the Shorepower Truck Electrification Project (STEP), started in May 2011 and ended in March 2015. The project grant was awarded by the Department of Energy’s Vehicles Technology Office in the amount of $22.2 million. It had three overarching missions: 1. Reduce the idling of Class 8 tractors when parked at truck stops, to reduce diesel fuel consumption and thus U.S. dependence on foreign petroleum; 2. Stimulate job creation and economic activity as part of the American Reinvestment and Recovery Act of 2009; 3. Reduce greenhouse gas emissions (GHG) from diesel combustion and the carbon footprint of the truck transportation industry. The project design was straightforward. First, build fifty Truck Stop Electrification (TSE) facilities in truck stop parking lots across the country so trucks could plug-in to 110V, 220V, or 480VAC, and shut down the engine instead of idling. These facilities were strategically located at fifty truck stops along major U.S. Interstates with heavy truck traffic. Approximately 1,350 connection points were installed, including 150 high-voltage electric standby Transport Refrigeration Unit (eTRU) plugs--eTRUs are capable of plugging in to shore power1 to cool the refrigerated trailer for loads such as produce, meats and ice cream. Second, the project provided financial incentives on idle reduction equipment to 5,000 trucks in the form of rebates, to install equipment compatible with shore power. This equipment enables drivers to shut down the main engine when parked, to heat or cool their cab, charge batteries, or use other household appliances without idling—a common practice that uses approximately 1 gallon of diesel per hour. The rebate recipients were intended to be the first fleets to plug into Shorepower to save diesel fuel and ensure there is significant population of shore power capable trucks. This two part project was designed to complement each other by providing: 1) the infrastructure to plug into and 2) the on-board equipment capable of plugging into the infrastructure. This project generated the largest dataset to date on shore power TSE utilization and use patterns, providing: insight into driver behavior and acceptance; evidence of cost savings; experience with system operations and management; and data for guiding future development of shore power, whether as a private enterprise or a publicly-subsidized service for meeting air quality goals.

  9. Operation Warfighter Internship Fair

    Broader source: Energy.gov [DOE]

    Attendees: Participants of Operation Warfighter Program Cost: Free Supports: Veteran and Disability Employment Programs

  10. ARM - SGP Operations

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Operations SGP Related Links Virtual Tour Facilities and Instruments Central Facility Boundary Facility Extended Facility Intermediate Facility Radiometric Calibration Facility Geographic Information ES&H Guidance Statement Operations Science Field Campaigns Visiting the Site SGP Fact Sheet Images Information for Guest Scientists Contacts SGP Operations Routine Operations SGP central facility offices. SGP central facility offices. The overwhelming majority of the measurements with the

  11. Capital Project Prioritization

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Capital-Project-Prioritization Sign In About | Careers | Contact | Investors | bpa.gov Search News & Us Expand News & Us Projects & Initiatives Expand Projects &...

  12. EIS-0411: Transmission Agency of Northern California Transmission Project

    Broader source: Energy.gov [DOE]

    This EIS is for the Western Area Power Administration construction, operation, and maintenance of the proposed transmission agency of Northern California Transmission Project, California.

  13. The Boeing Company Smart Grid Demonstration Project | Open Energy...

    Open Energy Info (EERE)

    Overview Demonstrate an advanced Smart Grid software technology with military-grade cybersecurity for improving regional transmission system planning and operation. The project...

  14. Chile-World Bank Climate Projects | Open Energy Information

    Open Energy Info (EERE)

    The design and operation of this project, in conjunction with the avoidance of methane emissions and production of compost as a soil amendment (and a source of revenues),...

  15. CenterPoint Energy Smart Grid Project | Open Energy Information

    Open Energy Info (EERE)

    distribution automation equipment. The project aims to reduce peak loads, overall electricity use, and operations and maintenance costs while increasing distribution system...

  16. Two Savannah River Site Projects Gain National Recognition |...

    Broader source: Energy.gov (indexed) [DOE]

    environmental stewardship. They are awarded for projects and programs that reduce environmental impacts, enhance site operations, and reduce costs. One award, for Renewable...

  17. Ensuring Project Success - The Fundamental Art of Managing the...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Ensuring Project Success - The Fundamental Art of Managing the Interfaces August 2009 Presenter: Jeff Smith, Deputy for Operations, Oak Ridge National Laboratory Track 8-3 Topics ...

  18. AWEA Wind Project O&M and Safety Seminar

    Broader source: Energy.gov [DOE]

    The AWEA Wind Project O&M and Safety Seminar is where leading owners, operators, turbine manufacturers, material suppliers, wind technicians, managers, supervisors, engineers, and occupational...

  19. EIS-0489: Jordan Cove Liquefaction Project (Coos County, OR)...

    Energy Savers [EERE]

    to construct and operate the Jordan Cove Liquefaction and Pacific Connector Pipeline Projects, respectively a proposed new liquefied natural gas (LNG) export terminal and ...

  20. Oneida Tribe of Indians of Wisconsin- 2011 Energy Efficiency Project

    Broader source: Energy.gov [DOE]

    This project will fund energy audits of approximately 44 tribally owned buildings operated by the Oneida Tribe, which total 1,031,905 square feet.

  1. NSTAR Electric & Gas Corporation Smart Grid Demonstration Project...

    Open Energy Info (EERE)

    on low voltage (secondary) networks in downtown Boston to improve grid reliability and safety. The project will provide additional visibility for operators, which...

  2. Wisconsin Power and Light Company Smart Grid Project | Open Energy...

    Open Energy Info (EERE)

    automation project is designed to improve distribution system efficiency and reliability while lowering operations and maintenance costs. WPL is deploying a new centralized...

  3. EIS-0401: NextGen Project, South Dakota

    Broader source: Energy.gov [DOE]

    This EIS analyzes WAPA's proposed action for the construction and operation of the proposed NextGen Energy Facility (Project) in South Dakota.

  4. Project Grandmaster

    Energy Science and Technology Software Center (OSTI)

    2013-09-16

    The purpose of the Project Grandmaster Application is to allow individuals to opt-in and give the application access to data sources about their activities on social media sites. The application will cross-reference these data sources to build up a picture of each individual activities they discuss, either at present or in the past, and place this picture in reference to groups of all participants. The goal is to allow an individual to place themselves inmore » the collective and to understand how their behavior patterns fit with the group and potentially find changes to make, such as activities they weren’t already aware of or different groups of interest they might want to follow.« less

  5. Project Grandmaster

    SciTech Connect (OSTI)

    2013-09-16

    The purpose of the Project Grandmaster Application is to allow individuals to opt-in and give the application access to data sources about their activities on social media sites. The application will cross-reference these data sources to build up a picture of each individual activities they discuss, either at present or in the past, and place this picture in reference to groups of all participants. The goal is to allow an individual to place themselves in the collective and to understand how their behavior patterns fit with the group and potentially find changes to make, such as activities they weren?t already aware of or different groups of interest they might want to follow.

  6. Project Hanford management contract quality improvement project management plan

    SciTech Connect (OSTI)

    ADAMS, D.E.

    1999-03-25

    On July 13, 1998, the U.S. Department of Energy, Richland Operations Office (DOE-RL) Manager transmitted a letter to Fluor Daniel Hanford, Inc. (FDH) describing several DOE-RL identified failed opportunities for FDH to improve the Quality Assurance (QA) Program and its implementation. In addition, DOE-RL identified specific Quality Program performance deficiencies. FDH was requested to establish a periodic reporting mechanism for the corrective action program. In a July 17, 1998 response to DOE-RL, FDH agreed with the DOE concerns and committed to perform a comprehensive review of the Project Hanford Management Contract (PHMC) QA Program during July and August, 1998. As a result, the Project Hanford Management Contract Quality Improvement Plan (QIP) (FDH-3508) was issued on October 21, 1998. The plan identified corrective actions based upon the results of an in-depth Quality Program Assessment. Immediately following the scheduled October 22, 1998, DOE Office of Enforcement and Investigation (EH-10) Enforcement Conference, FDH initiated efforts to effectively implement the QIP corrective actions. A Quality Improvement Project (QI Project) leadership team was assembled to prepare a Project Management Plan for this project. The management plan was specifically designed to engage a core team and the support of representatives from FDH and the major subcontractors (MSCs) to implement the QIP initiatives; identify, correct, and provide feedback as to the root cause for deficiency; and close out the corrective actions. The QI Project will manage and communicate progress of the process.

  7. OCGen Module Mooring Project

    SciTech Connect (OSTI)

    McEntee, Jarlath

    2015-02-06

    Ocean Renewable Power Company's OCGen Module Mooring Project provided an extensive research, design, development, testing and data collection effort and analysis conducted with respect to a positively buoyant, submerged MHK device secured to the seabed using a tensioned mooring system. Different analytic tools were evaluated for their utility in the design of submerged systems and their moorings. Deployment and testing of a prototype OCGen® system provided significant data related to mooring line loads and system attitude and station keeping. Mooring line loads were measured in situ and reported against flow speeds. The Project made a significant step in the development of designs, methodologies and practices related to floating and mooring of marine hydrokinetic (MHK) devices. Importantly for Ocean Renewable Power Company, the Project provided a sound basis for advancing a technically and commercially viable OCGen® Power System. The OCGen® Power System is unique in the MHK industry and, in itself, offers distinct advantages of MHK devices that are secured to the seabed using fixed structural frames. Foremost among these advantages are capital and operating cost reductions and increased power extraction by allowing the device to be placed at the most energetic level of the water column.

  8. ARM - Historical Operational Statistics

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Operational Statistics 2016 Quarterly Reports First Quarter (PDF) Second Quarter (PDF) Third Quarter (PDF) Fourth Quarter (PDF) Past Quarterly Reports Historical Statistics Field Campaigns Operational Visitors and Accounts Data Archive and Usage (October 1995 - Present) Historical Operational Statistics The reporting requirements for DOE national user facilities are based on time. These requirements concern the actual hours of operation (ACTUAL) and the established maximum operation or uptime

  9. Fermilab SRF cryomodule operational experience

    SciTech Connect (OSTI)

    Martinez, A.; Klebaner, A.L.; Theilacker, J.C.; DeGraff, B.D.; White, M.; Johnson, G.S.; /Fermilab

    2011-06-01

    Fermi National Accelerator Laboratory is constructing an Advanced Accelerator Research and Development facility at New Muon Lab. The cryogenic infrastructure in support of the initial phase of the facility consists of two Tevatron style standalone refrigerators, cryogenic distribution system as well as an ambient temperature pumping system to achieve 2K operations with supporting purification systems. During this phase of the project a single Type III plus 1.3 GHz cryomodule was installed, cooled and tested. Design constraints of the cryomodule required that the cryomodule individual circuits be cooled at predetermined rates. These constraints required special design solutions to achieve. This paper describes the initial cooldown and operational experience of a 1.3 GHz cryomodule using the New Muon Lab cryogenic system.

  10. Web Operational Status Boards

    Energy Science and Technology Software Center (OSTI)

    2004-04-16

    Web Operational Status Boards (WebOSB)is a web-based application designed to acquire, display, and update highly dynamic status information between multiple users and jurisdictions. WebOSB is able to disseminate real-time status information—support the timely sharing of information—with constant, dynamic updates via personal computers and the Internet between emergency operations centers (EOCs), incident command centers, and to users outside the EOC who need to know the information (hospitals, shelters, schools). The WebOSB application far exceeds outdated information-sharingmore » methods used by emergency workers: whiteboards, Word and Excel documents, or even locality-specific Web sites. WebOSB’s capabilities include the following elements: - Secure access. Multiple users can access information on WebOSB from any personal computer with Internet access and a secure ID. Privileges are use to control access and distribution of status information and to identify users who are authorized to add or edit information. - Simultaneous update. WebOSB provides options for users to add, display, and update dynamic information simultaneously at all locations involved in the emergency management effort, A single status board can be updated from multiple locations enabling shelters and hospitals to post bed availability or list decontamination capability. - On-the-fly modification. Allowing the definition of an existing status board to be modified on-the-fly can be an asset during an emergency, where information requirements can change quickly. The status board designer feature allows an administrator to quickly define, modi,, add to, and implement new status boards in minutes without needing the help of Web designers and computer programmers. - Publisher/subscriber notification. As a subscriber, each user automatically receives notification of any new information relating to specific status boards. The publisher/subscriber feature automatically notified each user of any new information relating to specific status boards. WebOSB can be installed to fit the specific needs of an emergency management community. Because it was originally developed to concurrently support multiple EOCs at the local, county, and state level, it can also support multi-user environments for other types of projects.« less

  11. Web Operational Status Boards

    SciTech Connect (OSTI)

    2004-04-16

    Web Operational Status Boards (WebOSB)is a web-based application designed to acquire, display, and update highly dynamic status information between multiple users and jurisdictions. WebOSB is able to disseminate real-time status information?support the timely sharing of information?with constant, dynamic updates via personal computers and the Internet between emergency operations centers (EOCs), incident command centers, and to users outside the EOC who need to know the information (hospitals, shelters, schools). The WebOSB application far exceeds outdated information-sharing methods used by emergency workers: whiteboards, Word and Excel documents, or even locality-specific Web sites. WebOSB?s capabilities include the following elements: - Secure access. Multiple users can access information on WebOSB from any personal computer with Internet access and a secure ID. Privileges are use to control access and distribution of status information and to identify users who are authorized to add or edit information. - Simultaneous update. WebOSB provides options for users to add, display, and update dynamic information simultaneously at all locations involved in the emergency management effort, A single status board can be updated from multiple locations enabling shelters and hospitals to post bed availability or list decontamination capability. - On-the-fly modification. Allowing the definition of an existing status board to be modified on-the-fly can be an asset during an emergency, where information requirements can change quickly. The status board designer feature allows an administrator to quickly define, modi,, add to, and implement new status boards in minutes without needing the help of Web designers and computer programmers. - Publisher/subscriber notification. As a subscriber, each user automatically receives notification of any new information relating to specific status boards. The publisher/subscriber feature automatically notified each user of any new information relating to specific status boards. WebOSB can be installed to fit the specific needs of an emergency management community. Because it was originally developed to concurrently support multiple EOCs at the local, county, and state level, it can also support multi-user environments for other types of projects.

  12. Transforming Commercial Building Operations - 2013 BTO Peer Review |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy Commercial Building Operations - 2013 BTO Peer Review Transforming Commercial Building Operations - 2013 BTO Peer Review Commercial Buildings Integration Project for the 2013 Building Technologies Office's Program Peer Review PDF icon commlbldgs13_underhill_040413.pdf More Documents & Publications Transforming the Commercial Building Operations - 2014

  13. Waste management project technical baseline description

    SciTech Connect (OSTI)

    Sederburg, J.P.

    1997-08-13

    A systems engineering approach has been taken to describe the technical baseline under which the Waste Management Project is currently operating. The document contains a mission analysis, function analysis, requirement analysis, interface definitions, alternative analysis, system definition, documentation requirements, implementation definitions, and discussion of uncertainties facing the Project.

  14. Wind Forecasting Improvement Project | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Forecasting Improvement Project Wind Forecasting Improvement Project October 3, 2011 - 12:12pm Addthis This is an excerpt from the Third Quarter 2011 edition of the Wind Program R&D Newsletter. In July, the Department of Energy launched a $6 million project with the National Oceanic and Atmospheric Administration (NOAA) and private partners to improve wind forecasting. Wind power forecasting allows system operators to anticipate the electrical output of wind plants and adjust the electrical

  15. Project LIBERTY Biorefinery Starts Cellulosic Ethanol Production |

    Energy Savers [EERE]

    Department of Energy Project LIBERTY Biorefinery Starts Cellulosic Ethanol Production Project LIBERTY Biorefinery Starts Cellulosic Ethanol Production September 3, 2014 - 12:05pm Addthis News Media Contact 202-586-4940 WASHINGTON - Project LIBERTY, the nation's first commercial-scale cellulosic ethanol plant to use corn waste as a feedstock, announced the start of production today. Once operating at full, commercial-scale, the biorefinery in Emmetsburg, Iowa will produce 25 million gallons

  16. Initiatives and Projects | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Initiatives and Projects Initiatives and Projects As part of its work to support energy efficiency and renewable energy research, the Office of Energy Efficiency and Renewable Energy has collaborated with private organizations, researchers, and other nations. Here you can read about the results of EERE's collaboration and research activities. This list includes projects completed at the office level, or by the Business Operations or Strategic Programs areas. Read about EERE's cross-cutting,

  17. Commemorating Black History: Contributions of African Americans...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Project Speak of the Nation's History General Leslie Groves and J. Robert Oppenheimer are pictured here at the Trinity Test site in New Mexico, 1945. New Manhattan Project ...

  18. EM News Flashes | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    of workers who produced plutonium for the Manhattan Project, World War II, and Cold War. September 4, 2014 EM Acquisition and Project Management Deputy Assistant Secretary...

  19. EM News Flashes | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Christmas in 1945. Gates contributed to the Voices of the Manhattan Project, a storytelling project launched by the Atomic Heritage Foundation and Los Alamos Historical...

  20. Ferry Barge | Y-12 National Security Complex

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Ferry Barge Ferry Barge Before the Manhattan Project, modern bridges were very far into the future for the Oak Ridge area. They came more quickly with the project.