Powered by Deep Web Technologies
Note: This page contains sample records for the topic "operation 1943-1944 working" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


1

Manhattan Project: Y-12 Operation, 1943-1944  

Office of Scientific and Technical Information (OSTI)

Alpha Racetrack, Y-12 Electromagnetic Plant, Oak Ridge Y-12: OPERATION Alpha Racetrack, Y-12 Electromagnetic Plant, Oak Ridge Y-12: OPERATION (Oak Ridge: Clinton, 1943-1944) Events > The Uranium Path to the Bomb, 1942-1944 Y-12: Design, 1942-1943 Y-12: Construction, 1943 Y-12: Operation, 1943-1944 Working K-25 into the Mix, 1943-1944 The Navy and Thermal Diffusion, 1944 During the summer and fall of 1943, the Y-12 Electromagnetic Plant at Oak Ridge began to take shape. The huge buildings to house the operating equipment were readied as manufacturers began delivering everything from electrical switches to motors, valves, and tanks. While construction and outfitting proceeded, almost 5,000 operating and maintenance personnel were hired and trained. Then, between October and mid-December, Y-12 paid the price for being a new technology that had not been put through its paces in a pilot plant. Vacuum tanks in the first Alpha racetrack leaked and shimmied out of line due to magnetic pressure, welds failed, electrical circuits malfunctioned, and operators made frequent mistakes. Most seriously, the magnet coils shorted out because of rust and sediment in the cooling oil.

2

Manhattan Project: Working K-25 into the Mix, 1943-1944  

Office of Scientific and Technical Information (OSTI)

K-25 Gaseous Diffusion Plant, Oak Ridge WORKING K-25 INTO THE MIX K-25 Gaseous Diffusion Plant, Oak Ridge WORKING K-25 INTO THE MIX (Oak Ridge: Clinton, 1943-1944) Events > The Uranium Path to the Bomb, 1942-1944 Y-12: Design, 1942-1943 Y-12: Construction, 1943 Y-12: Operation, 1943-1944 Working K-25 into the Mix, 1943-1944 The Navy and Thermal Diffusion, 1944 In 1941 and 1942, gaseous diffusion had been considered by many as the most promising method of enriching uranium. The British in the influential 1941 MAUD Report had advocated the use of gaseous diffusion alone, and the 1942 Lewis committee placed it first among isotope separation methods. Despite the soundness of the theory, the process had yet to produce any samples of enriched uranium when the K-25 Gaseous Diffusion Plant was authorized in late 1942.

3

Manhattan Project: Hanford Becomes Operational, 1943-1944  

Office of Scientific and Technical Information (OSTI)

F Reactor Plutonium Production Complex at Hanford, 1945 HANFORD BECOMES OPERATIONAL F Reactor Plutonium Production Complex at Hanford, 1945 HANFORD BECOMES OPERATIONAL (Hanford Engineer Works, 1943-1944) Events > The Plutonium Path to the Bomb, 1942-1944 Production Reactor (Pile) Design, 1942 DuPont and Hanford, 1942 CP-1 Goes Critical, December 2, 1942 Seaborg and Plutonium Chemistry, 1942-1944 Final Reactor Design and X-10, 1942-1943 Hanford Becomes Operational, 1943-1944 The plutonium production facilities at the Hanford Engineer Works took shape with the same wartime urgency as did the uranium facilities at Oak Ridge. In February 1943, Colonel Matthias returned to the location he had helped select the previous December and set up a temporary headquarters. In late March, Matthias received his assignment. The three water-cooled production reactor (piles), designated by the letters B, D, and F, would be built about six miles apart on the south bank of the Columbia River. The four chemical separation plants would be built in pairs at two sites nearly ten miles south of the piles. A facility to produce slugs and perform tests would be approximately twenty miles southeast of the separation plants near Richland. Temporary quarters for construction workers would be put up at the Hanford town site, while permanent facilities for other personnel would be located down the road in Richland, safely removed from the production and separation plants. Life at Hanford would soon come to resemble that of the other "atomic boomtowns" of the Manhattan Project, Los Alamos and Oak Ridge.

4

Manhattan Project: Basic Research at Los Alamos, 1943-1944  

Office of Scientific and Technical Information (OSTI)

Norris Bradbury, Robert Oppenheimer, Richard Feynman, Enrico Fermi, and others, Los Alamos, 1946 BASIC RESEARCH AT LOS ALAMOS Norris Bradbury, Robert Oppenheimer, Richard Feynman, Enrico Fermi, and others, Los Alamos, 1946 BASIC RESEARCH AT LOS ALAMOS (Los Alamos: Laboratory, 1943-1944) Events > Bringing It All Together, 1942-1945 Establishing Los Alamos, 1942-1943 Early Bomb Design, 1943-1944 Basic Research at Los Alamos, 1943-1944 Implosion Becomes a Necessity, 1944 Oak Ridge and Hanford Come Through, 1944-1945 Final Bomb Design, 1944-1945 Atomic Rivals and the ALSOS Mission, 1938-1945 Espionage and the Manhattan Project, 1940-1945 Enrico Fermi The first few months at Los Alamos were occupied with briefings on nuclear physics for the technical staff and with planning research priorities and organizing the laboratory. Leslie Groves called once again on Warren Lewis to head a committee, this time to evaluate the Los Alamos program. The committee's recommendations resulted in the coordinated effort envisioned by those who advocated a unified laboratory for bomb research. Enrico Fermi (left) took control of critical mass experiments and standardization of measurement Hans Bethe techniques. Plutonium purification work, begun at the Met Lab, became high priority at Los Alamos, and increased attention was paid to metallurgy. The committee also recommended that an engineering division be organized to collaborate with physicists on bomb design and fabrication. The laboratory was thus organized into four divisions: theoretical (Hans A. Bethe, right); experimental physics (Robert F. Bacher); chemistry and metallurgy (Joseph W. Kennedy); and ordnance (Navy Captain William S. "Deke" Parsons). Like other Manhattan Project installations, Los Alamos soon began to expand beyond initial expectations.

5

Manhattan Project: Early Bomb Design, Los Alamos: Laboratory, 1943-1944  

Office of Scientific and Technical Information (OSTI)

Little Boy at Tinian Island, August 1945 EARLY BOMB DESIGN Little Boy at Tinian Island, August 1945 EARLY BOMB DESIGN (Los Alamos: Laboratory, 1943-1944) Events > Bringing it All Together, 1942-1945 Establishing Los Alamos, 1942-1943 Early Bomb Design, 1943-1944 Basic Research at Los Alamos, 1943-1944 Implosion Becomes a Necessity, 1944 Oak Ridge and Hanford Come Through, 1944-1945 Final Bomb Design, 1944-1945 Atomic Rivals and the ALSOS Mission, 1938-1945 Espionage and the Manhattan Project, 1940-1945 Early work on the design of the atomic bomb began even as scientists continued to arrive at Los Alamos throughout 1943. The properties of uranium were reasonably well understood, those of plutonium less so, and knowledge of fission explosions entirely theoretical. That 2.2 secondary neutrons were produced when uranium-235 fissioned was accepted, but while Glenn Seaborg's team had proven in March 1941 that plutonium underwent neutron-induced fission, it was not known yet if plutonium released secondary neutrons during bombardment. Further, the exact sizes of the "cross sections" of various fissionable substances had yet to be determined in experiments using the various particle accelerators then being shipped to Los Alamos. The theoretical consensus was that fission Fission chain reaction chain reactions (left) did take place with sufficient speed to produce powerful releases of energy (and not simply result in the explosion of the critical mass itself), but only experiments could test this theory. The optimum size of the critical mass remained to be established, as did the optimum shape. When enough data were gathered to establish optimum critical mass, optimum effective mass still had to be determined. That is, it was not enough simply to start a chain reaction in a critical mass; it was necessary to start one in a mass that would release the greatest possible amount of energy before it was destroyed in the explosion.

6

NUCLEAR POWER AND RESEARCH REACTORS 1939 1942 1943 1944  

E-Print Network (OSTI)

trash bags) of having been at the HFIR facility, which is surrounded by woods. Bears had also been by TWRA officials near ORNL's HFIR and moved to a wildlife management area in Scott County. (Photo: Jason

7

Manhattan Project: DuPont and Hanford, Hanford Engineer Works, 1942  

Office of Scientific and Technical Information (OSTI)

The president of DuPont, Walter Carpenter, with Generals Levin H. Campbell, Everett Hughes, and Charles T. Harris. DUPONT AND HANFORD The president of DuPont, Walter Carpenter, with Generals Levin H. Campbell, Everett Hughes, and Charles T. Harris. DUPONT AND HANFORD (Hanford Engineer Works, 1942) Events > The Plutonium Path to the Bomb, 1942-1944 Production Reactor (Pile) Design, 1942 DuPont and Hanford, 1942 CP-1 Goes Critical, December 2, 1942 Seaborg and Plutonium Chemistry, 1942-1944 Final Reactor Design and X-10, 1942-1943 Hanford Becomes Operational, 1943-1944 The scientists of the Met Lab had the technical expertise to design a production pile, but construction and management on an industrial scale required an outside contractor. The DuPont Corporation was an ideal candidate, but the giant chemical firm was hesitant to join the project due to concern over accusations that it had profiteered during World War I. On October 3, 1942, DuPont agreed to design and build the chemical separation plant for the production pile facility then planned for Oak Ridge. Leslie Groves tried to entice further DuPont participation by having the firm prepare an appraisal of the pile (reactor) project and by placing three DuPont staff members on the Lewis Committee. DuPont ultimately agreed to become the primary contractor for plutonium-related work, but because of continuing sensitivity about its public image its contract called for a total payment of only dollar over actual costs. In addition, DuPont vowed to stay out of the bomb business after the war and offered all patents to the United States government.

8

Standards Working Groups - Safety and Operating ...  

Science Conference Proceedings (OSTI)

*. Bookmark and Share. Safety and Operating Environment Working Group. Scope: These two areas have been combined ...

2010-12-27T23:59:59.000Z

9

Audit of Work Force Restructuring at the Oak Ridge Operations...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Other Agencies You are here Home Audit of Work Force Restructuring at the Oak Ridge Operations Office, ER-B-95-06 Audit of Work Force Restructuring at the Oak Ridge...

10

Modeling and Simulation for Mission Operations Work System Design  

Science Conference Proceedings (OSTI)

Work system analysis and design is complex and nondeterministic. In this paper we describe Brahms, a multiagent modeling and simulation environment for designing complex interactions in human-machine systems. Brahms was originally conceived as a business ... Keywords: Agent Languages, Business Process Modeling, Mission Operations Design, Multiagent Simulation, Work Practices

Maarten Sierhuis; William J. Clancey; Chin Seah; Jay P. Trimble; Michael H. Sims

2003-04-01T23:59:59.000Z

11

Time on the Mountain: The Office of Strategic Services in Axis-Occupied Greece, 1943-1944.  

E-Print Network (OSTI)

??Using the wartime reports produced by various field agents of the Office of Strategic Services (OSS), this dissertation attempts to rebut the currently hegemonic notion (more)

Nalmpantis, Kyriakos

2010-01-01T23:59:59.000Z

12

Manhattan Project: The Navy and Thermal Diffusion, 1944  

Office of Scientific and Technical Information (OSTI)

Diffusion columns, S-50 Thermal Diffusion Plant, Oak Ridge, 1945. THE NAVY AND THERMAL DIFFUSION Diffusion columns, S-50 Thermal Diffusion Plant, Oak Ridge, 1945. THE NAVY AND THERMAL DIFFUSION (Oak Ridge: Clinton, 1944) Events > The Uranium Path to the Bomb, 1942-1944 Y-12: Design, 1942-1943 Y-12: Construction, 1943 Y-12: Operation, 1943-1944 Working K-25 into the Mix, 1943-1944 The Navy and Thermal Diffusion, 1944 As problems with both Y-12 and K-25 reached crisis proportions in spring and summer 1944, the Manhattan Project received help from an unexpected source: the United States Navy. President Roosevelt had instructed that the atomic bomb effort be an Army program and that the Navy be excluded from deliberations. Navy research on atomic power, conducted primarily for submarines, received no direct aid from Leslie Groves, who, in fact, was not up-to-date on the state of Navy efforts when he received a letter on the subject from Robert Oppenheimer late in April 1944.

13

Manhattan Project: The Uranium Path to the Bomb, 1942-1944  

Office of Scientific and Technical Information (OSTI)

Alpha Racetrack, Y-12 Electromagnetic Plant, Oak Ridge THE URANIUM PATH TO THE BOMB Alpha Racetrack, Y-12 Electromagnetic Plant, Oak Ridge THE URANIUM PATH TO THE BOMB (1942-1944) Events > The Uranium Path to the Bomb, 1942-1944 Y-12: Design, 1942-1943 Y-12: Construction, 1943 Y-12: Operation, 1943-1944 Working K-25 into the Mix, 1943-1944 The Navy and Thermal Diffusion, 1944 The uranium path to the atomic bomb ran through Oak Ridge, Tennessee. Only if the new plants built at Oak Ridge produced enough enriched uranium-235 would a uranium bomb be possible. General Groves placed two methods into production: 1) electromagnetic, based on the principle that charged particles of the lighter isotope would be deflected more when passing through a magnetic field; and 2) gaseous diffusion, based on the principle that molecules of the lighter isotope, uranium-235, would pass more readily through a porous barrier. Full-scale electromagnetic and gaseous diffusion production plants were built at Oak Ridge at sites designated as "Y-12" and "K-25", respectively.

14

Manhattan Project: Y-12 Construction, 1943  

Office of Scientific and Technical Information (OSTI)

Groundbreaking for Y-12, Oak Ridge Y-12: CONSTRUCTION Groundbreaking for Y-12, Oak Ridge Y-12: CONSTRUCTION (Oak Ridge: Clinton, 1943) Events > The Uranium Path to the Bomb, 1942-1944 Y-12: Design, 1942-1943 Y-12: Construction, 1943 Y-12: Operation, 1943-1944 Working K-25 into the Mix, 1943-1944 The Navy and Thermal Diffusion, 1944 Groundbreaking for the Alpha plant of the Y-12 Electromagnetic Plant took place at Oak Ridge on February 18, 1943 (right). Soon blueprints could not be produced fast enough to keep up with construction as Stone & Webster labored to meet Leslie Groves's deadline. The Beta facility was actually begun before formal authorization. While laborers were aggressively recruited, there was always a shortage of workers skilled Y-12 construction, Oak Ridge enough to perform jobs according to the rigid specifications. (A further complication was that some tasks could be performed only by workers with security clearances.) Huge amounts of material had to be obtained (38 million board feet of lumber, for instance), and the magnets needed so much copper for windings that the Army had to borrow almost 15,000 tons of silver bullion from the United States Treasury to fabricate into strips and wind on to coils as a substitute for copper. Treasury silver was also used to manufacture the busbars that ran around the top of the racetracks.

15

Operational efficiency through resource planning optimization and work process improvement  

E-Print Network (OSTI)

This thesis covers work done at National Grid to improve resource planning and the execution of pipeline construction and maintenance work carried out at the yards. Resource Planning, the art of picking the right jobs for ...

Balwani, Siddharth (Siddharth Vashdev)

2012-01-01T23:59:59.000Z

16

When Laboratory Work and Operating Plant Don't Agree ...  

Science Conference Proceedings (OSTI)

... carbonate leach process was used to produce nickel from Mayari ores at the Nicaro plant in Oriente Province, Cuba. While operation was generally successful

17

Solution of basic operational problems of water-development works at the Votkinsk hydroproject  

Science Conference Proceedings (OSTI)

Basic operational problems of water-development works at the Votkinsk HPP are examined. Measures for restoration of normal safety conditions for the water-development works at the HPP, which had been taken during service, are presented.

Deev, A. P.; Borisevich, L. A.; Fisenko, V. F. [Votkinsk Branch of the JSC 'RusGidro,' Chaikovskii (Russian Federation)

2012-11-15T23:59:59.000Z

18

U.S. CMS - U.S. CMS @ Work - Detector Commissioning and Operations  

NLE Websites -- All DOE Office Websites (Extended Search)

USCMS Detector Ops USCMS Detector Ops Detector Commissioning and Operations In This Section: LHC@ FNAL Remote Operations Center Remote Operations Center at Fermilab Global Run Contact The US CMS Operations Group works very closely with the main CMS commissioning and operations team to develop and maintain the many online detector monitoring tools that make remote operations possible for hundreds of collaborators. One of the group's major roles focuses on coordinating the operation of the Remote Operations Center (ROC) at Fermilab with CMS operations at CERN. The main CMS control room resides at Point 5. Because this is a half-hour drive from the main laboratory campus in Meyrin, the experiment built the CMS Centre, a remote operations center on CERN's main site. The US CMS group therefore makes sure that operations remain seamless between the ROC

19

Description of work for 100-DR-2 Operable Unit Vadose Drilling/test pits  

SciTech Connect

This report describes the scope of work for the boreholes/test pits of the 100-DR-2 Operable Unit. Sampling and field activities include: Soil screening; geologic sampling; soil sampling (physical property); analytical sampling and depths; and geophysical logging.

Naiknimbalkar, N.

1993-08-01T23:59:59.000Z

20

work  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

THE THE U.S. DEPARTMENT OF ENERGY'S WORKING CAPITAL FUND U.S. DEPARTMENT OF ENERGY OFFICE OF INSPECTOR GENERAL OFFICE OF AUDIT SERVICES OCTOBER 1998 AUDIT REPORT CR-B-99-01 MEMORANDUM FOR THE DIRECTOR, BUSINESS MANAGEMENT STAFF FROM: William S. Maharay Acting Manager, Capital Regional Audit Office, Office of Inspector General SUBJECT: INFORMATION : Audit Report on the Department's Working Capital Fund BACKGROUND The Department established the Working Capital Fund (Fund) in January 1996 as a financial management tool for charging the costs of common services provided at Headquarters to Departmental program offices. The objectives in establishing the Fund were to increase efficiency of the Department's operations, improve management of administrative services

Note: This page contains sample records for the topic "operation 1943-1944 working" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


21

Manhattan Project: Production Reactor (Pile) Design, Met Lab, 1942  

Office of Scientific and Technical Information (OSTI)

Schematic of the X-10 Graphite Reactor, Oak Ridge PRODUCTION REACTOR (PILE) DESIGN Schematic of the X-10 Graphite Reactor, Oak Ridge PRODUCTION REACTOR (PILE) DESIGN (Met Lab, 1942) Events > The Plutonium Path to the Bomb, 1942-1944 Production Reactor (Pile) Design, 1942 DuPont and Hanford, 1942 CP-1 Goes Critical, December 2, 1942 Seaborg and Plutonium Chemistry, 1942-1944 Final Reactor Design and X-10, 1942-1943 Hanford Becomes Operational, 1943-1944 By 1942, scientists had established that some of the uranium exposed to radioactivity in a reactor (pile) would eventually decay into plutonium, which could then be separated by chemical means from the uranium. Important theoretical research on this was ongoing, but the work was scattered at various universities from coast to coast. In early 1942, Arthur Compton arranged for all pile research to be moved to the Met Lab at the University of Chicago.

22

RCRA and operational monitoring 1994 fiscal year work plan, WBS 1.5.3  

SciTech Connect

RCRA & Operational Monitoring (ROM) Program Office manages the direct funded Resource Conservation Recovery Act (RCRA) and Operational Monitoring under Work Breakdown Structure (WBS) 1.5.3. The ROM Program Office is a Branch of liquid Waste Disposal, a part of Restoration and Remediation of Westinghouse Hanford Company (WHC). The Fiscal Year Work Plan (FYWP) takes it direction from the Multi-Year Program Plan (MYPP). The FYWP provides the near term, enhanced details for the Program Office to use as baseline Cost, Scope and Schedule. Changs Control administered during the fiscal year is against the baseline provided by the FYWP.

Not Available

1993-12-01T23:59:59.000Z

23

Proposal for the Award of a Contract for Maintenance, Operation and Minor Installation Work for CERN Cooling and HVAC Systems  

E-Print Network (OSTI)

Proposal for the Award of a Contract for Maintenance, Operation and Minor Installation Work for CERN Cooling and HVAC Systems

1996-01-01T23:59:59.000Z

24

,"U.S. Working Storage Capacity at Operable Refineries"  

U.S. Energy Information Administration (EIA) Indexed Site

Storage Capacity at Operable Refineries" Storage Capacity at Operable Refineries" ,"Click worksheet name or tab at bottom for data" ,"Worksheet Name","Description","# Of Series","Frequency","Latest Data for" ,"Data 1","U.S. Working Storage Capacity at Operable Refineries",28,"Annual",2013,"6/30/1982" ,"Release Date:","6/21/2013" ,"Next Release Date:","6/20/2014" ,"Excel File Name:","pet_pnp_capwork_dcu_nus_a.xls" ,"Available from Web Page:","http://www.eia.gov/dnav/pet/pet_pnp_capwork_dcu_nus_a.htm" ,"Source:","Energy Information Administration" ,"For Help, Contact:","infoctr@eia.gov"

25

Manhattan Project: Y-12: Design, 1942-1943  

Office of Scientific and Technical Information (OSTI)

Ernest Lawrence slumps in his chair from fatigue in front of a cyclotron control panel while conducting calutron-related experiments, Berkeley, 1943. Y-12: DESIGN Ernest Lawrence slumps in his chair from fatigue in front of a cyclotron control panel while conducting calutron-related experiments, Berkeley, 1943. Y-12: DESIGN (Oak Ridge: Clinton, 1942-1943) Events > The Uranium Path to the Bomb, 1942-1944 Y-12: Design, 1942-1943 Y-12: Construction, 1943 Y-12: Operation, 1943-1944 Working K-25 into the Mix, 1943-1944 The Navy and Thermal Diffusion, 1944 Although the Lewis Report had placed gaseous diffusion ahead of the electromagnetic approach, many were still betting in early 1943 that Ernest Lawrence (right) and his "calutron" would eventually predominate. Lawrence and his laboratory of mechanics at the University of California, Berkeley, continued to experiment with the giant 184-inch cyclotron magnet, trying to reach a consensus on which shims, sources, and Electromagnetic method for the enrichment of uranium collectors to incorporate into the Y-12 Electromagnetic Plant that was to be built at Oak Ridge. Research on magnet size and placement and beam resolution led Lawrence and his group in fall 1942 to propose an arrangement of huge electromagnetic coils connected by a bus bar in an oval racetrack configuration, as seen from above. Forty-eight gaps in the racetrack between the coils would each contain two vacuum tanks. With two racetracks per building, ten buildings would be necessary to provide the estimated 2,000 sources and collectors needed to separate 100 grams of uranium-235 daily. The Berkeley researchers hoped that improvements in calutron design, or placing multiple sources and collectors in each tank, might increase efficiency and reduce the number of tanks and buildings required, but experimental results were inconclusive even as Stone & Webster of Boston, the Y-12 contractor at Oak Ridge, prepared to break ground.

26

Manhattan Project: Oak Ridge and Hanford Come Through, 1944-1945  

Office of Scientific and Technical Information (OSTI)

Y-12 Plant, Oak Ridge, 1944 OAK RIDGE AND HANFORD COME THROUGH Y-12 Plant, Oak Ridge, 1944 OAK RIDGE AND HANFORD COME THROUGH (Oak Ridge [Clinton] and Hanford, 1944-1945) Events > Bringing It All Together, 1942-1945 Establishing Los Alamos, 1942-1943 Early Bomb Design, 1943-1944 Basic Research at Los Alamos, 1943-1944 Implosion Becomes a Necessity, 1944 Oak Ridge and Hanford Come Through, 1944-1945 Final Bomb Design, 1944-1945 Atomic Rivals and the ALSOS Mission, 1938-1945 Espionage and the Manhattan Project, 1940-1945 None of Los Alamos's bomb design work would be of any use if Oak Ridge or Hanford did not come through with enough uranium-235 or plutonium for at least one bomb. Spending on the Manhattan Project reached $100 million per month by mid-1944, yet it was still far from clear that enough of either fissionable substance could be produced before war's end. In the summer of 1944, Oak Ridge's Y-12 Electromagnetic Plant (above) was plagued by operational problems, and the ongoing barrier crisis at the K-25 Gaseous Diffusion Plant threatened to render it useless. At Hanford, the first production reactor had not yet been completed. In addition, officials feared that not enough of the uranium-containing slugs to feed the pile would be available. Even assuming that enough uranium or plutonium could be delivered by Oak Ridge or Hanford, there was no guarantee that the Los Alamos laboratory would be able to design and fabricate weapons in time. Only the most optimistic in the Manhattan Project would have predicted, as Groves did when he met with Marshall in August of 1944, that a bomb or bombs powerful enough to make a difference in the current war would be ready by August 1, 1945.

27

RCRA facility investigation/corrective measures study work plan for the 200-UP-2 Operable Unit, Hanford Site, Richland, Washington  

Science Conference Proceedings (OSTI)

The 200-UP-2 Operable Unit is one of two source operable units at the U Plant Aggregate Area at the Hanford Site. Source operable units include waste management units and unplanned release sites that are potential sources of radioactive and/or hazardous substance contamination. This work plan, while maintaining the title RFI/CMS, presents the background and direction for conducting a limited field investigation in the 200-UP-2 Operable Unit, which is the first part of the process leading to final remedy selection. This report discusses the background, prior recommendations, goals, organization, and quality assurance for the 200-UP-2 Operable Unit Work Plan. The discussion begins with a summary of the regulatory framework and the role of the work plan. The specific recommendations leading into the work plan are then addressed. Next, the goals and organization of the report are discussed. Finally, the quality assurance and supporting documentation are presented.

Not Available

1993-06-01T23:59:59.000Z

28

U.S. CMS - U.S. CMS @ Work - Data and Computing - Facility Operations...  

NLE Websites -- All DOE Office Websites (Extended Search)

File Transfer Batch Systems CRAB Quota and Usage Statistics CERN Bluearc Quota and Stats System Status U.S. CMS Grid Facility Operations: Batch System Batch Systems: The batch...

29

Operated by Los Alamos National Security, LLC for the U.S. Department of Energy's NNSA CAS Working Conference  

E-Print Network (OSTI)

Blake Research Library Director Los Alamos National Laboratory #12;Operated by Los Alamos National Conference Library and Information Services November 2011 Slide 1 Research Libraries: Now and Forward Miriam Services LANL Research Library Leader in the DOE Complex & federal agencies · Work with DOE National

30

A Framework for Assessing Operational MaddenJulian Oscillation Forecasts: A CLIVAR MJO Working Group Project  

Science Conference Proceedings (OSTI)

The U.S. Climate Variability and Predictability (CLIVAR) MJO Working Group (MJOWG) has taken steps to promote the adoption of a uniform diagnostic and set of skill metrics for analyzing and assessing dynamical forecasts of the MJO. Here we ...

J. Gottschalck; M. Wheeler; K. Weickmann; F. Vitart; N. Savage; H. Lin; H. Hendon; D. Waliser; K. Sperber; M. Nakagawa; C. Prestrelo; M. Flatau; W. Higgins

2010-09-01T23:59:59.000Z

31

Original Articles: Universal wind turbine working in grid-connected and island operating modes  

Science Conference Proceedings (OSTI)

In the future power system based on active distribution grid, allowing some portion to be disconnected, the concept of universal wind turbine systems may arise. This concept covers both grid-connected and island operations. This may happen if the voltage ... Keywords: Distributed generation, Droop control, Resynchronization, Wind power

Mario Rizo, Marco Liserre, Emilio Bueno, Francisco J. RodrGuez, Francisco Huerta

2013-05-01T23:59:59.000Z

32

U.S. CMS - U.S. CMS @ Work - Data and Computing - Facility Operations -  

NLE Websites -- All DOE Office Websites (Extended Search)

Data and Computing Facility Operations Data and Computing Facility Operations In This Section: Getting Started Computing Environment Resources Setup Software Tutorials, Documentation, How Tos Mass Storage File Transfer Batch Systems CRAB Quota and Usage Statistics CERN Bluearc Quota and Stats System Status U.S. CMS Grid Data Transfer to and from UAF At Fermilab, access to User Analysis Farm (UAF) goes through cmsuaf.fnal.gov. This can be accessed using Secure Copy (scp) or sftp. The following storage areas on NFS are available for users: /uscms/home/username /uscms_data/d1/username To transfer a file to UAF: Usage: scp file_name username@cmsuaf.fnal.gov:/uscms/home/username e.g. $ scp zprime705.jdf wenzel@cmsuaf.fnal.gov:/uscms/home/wenzel zprime705.jdf 100% |*****************************| 286 00:00

33

U.S. CMS - U.S. CMS @ Work - Data and Computing - Facility Operations - How  

NLE Websites -- All DOE Office Websites (Extended Search)

Data and Computing Facility Operations Data and Computing Facility Operations In This Section: Getting Started Computing Environment Resources Setup Software Tutorials, Documentation, How Tos Mass Storage File Transfer Batch Systems CRAB Quota and Usage Statistics CERN Bluearc Quota and Stats System Status U.S. CMS Grid How to use SRM on the UAF Introduction Prerequisites Prepare your UAF account to use srmcp Transfering a file Monitoring SRM Gettin Help Introduction SRM (Storage Resource Management) is a grid-service available on the UAF. The srmcp command allows for file transfers between sites and mass storage systems. Here we will show examples to transfer files from CASTOR at CERN to Fermilab. Since it is a grid service there are two prerequisites: Prerequisites The whole procedure will probaly take a few days but you might want to

34

Remedial investigation work plan for the Groundwater Operable Unit at Oak Ridge National Laboratory, Oak Ridge, Tennessee  

Science Conference Proceedings (OSTI)

This Remedial Investigation (RI) Work Plan has been developed as part of the US Department of Energy`s (DOE`s) investigation of the Groundwater Operable Unit (GWOU) at Oak Ridge National Laboratory (ORNL) located near Oak Ridge, Tennessee. The first iteration of the GWOU RI Work Plan is intended to serve as a strategy document to guide the ORNL GWOU RI. The Work Plan provides a rationale and organization for groundwater data acquisition, monitoring, and remedial actions to be performed during implementation of environmental restoration activities associated with the ORNL GWOU. It Is important to note that the RI Work Plan for the ORNL GWOU is not a prototypical work plan. The RI will be conducted using annual work plans to manage the work activities, and task reports will be used to document the results of the investigations. Sampling and analysis results will be compiled and reported annually with a review of data relative to risk (screening level risk assessment review) for groundwater. This Work Plan outlines the overall strategy for the RI and defines tasks which are to be conducted during the initial phase of investigation. This plan is presented with the understanding that more specific addenda to the plan will follow.

Not Available

1994-03-01T23:59:59.000Z

35

Work Control Center Operating Procedure page 1 D-NSTX-OP-AD-129 Rev.OO  

E-Print Network (OSTI)

(ESH-016) Lift Procedure (ENG-021) ES&H Review (NEPA, IH, etc.) Independent Review Pre-Job Brief D-SITE SPECIFIC: D-Site Work Permit (OP-AD-09) Door Permit (OP-G-93) USQD (OP-AD-63) Pre-Job Brief (OP-AD-79) T of the Day Meetings 12 7.2 Weekly Progress Meetings 12 7.3 Pre-job Briefings

Princeton Plasma Physics Laboratory

36

Remedial investigation/feasibility study work plan for the 100-BC-2 operable unit, Hanford Site, Richland, Washington  

SciTech Connect

This work plan and attached supporting project plans establish the operable unit setting and the objectives, procedures, tasks, and schedule for conducting the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA) remedial investigation/feasibility study (RI/FS) for the 100-BC-2 operable unit in the 100 Area of the Hanford Site. The 100 Area is one of four areas at the Hanford Site that are on the US Environmental Protection Agency`s (EPA) National Priorities List under CERCLA. The 100-BC-2 operable unit is one of two source operable units in the 100-B/C Area (Figure ES-1). Source operable units are those that contain facilities and unplanned release sites that are potential sources of hazardous substance contamination. The 100-BC-2 source operable unit contains waste sites that were formerly in the 100-BC-2, 100-BC-3, and 100-BC-4 operable units. Because of their size and geographic location, the waste sites from these two operable units were added to 100-BC-2. This allows for a more efficient and effective investigation of the remaining 100-B/C Reactor area waste sites. The investigative approach to waste sites associated with the 100-BC-2 operable unit are listed in Table ES-1. The waste sites fall into three general categories: high priority liquid waste disposal sites, low priority liquid waste disposal sites, and solid waste burial grounds. Several sites have been identified as candidates for conducting an IRM. Two sites have been identified as warranting additional limited field sampling. The two sites are the 116-C-2A pluto crib, and the 116-C-2C sand filter.

Not Available

1993-05-01T23:59:59.000Z

37

Operable Unit 7-13/14 in situ thermal desorption treatability study work plan  

SciTech Connect

This Work Plan provides technical details for conducting a treatability study that will evaluate the application of in situ thermal desorption (ISTD) to landfill waste at the Subsurface Disposal Area (SDA) at the Idaho National Engineering and Environmental Laboratory (INEEL). ISTD is a form of thermally enhanced vapor vacuum extraction that heats contaminated soil and waste underground to raise its temperature and thereby vaporize and destroy most organics. An aboveground vapor vacuum collection and treatment system then destroys or absorbs the remaining organics and vents carbon dioxide and water to the atmosphere. The technology is a byproduct of an advanced oil-well thermal extraction program. The purpose of the ISTD treatability study is to fill performance-based data gaps relative to off-gas system performance, administrative feasibility, effects of the treatment on radioactive contaminants, worker safety during mobilization and demobilization, and effects of landfill type waste on the process (time to remediate, subsidence potential, underground fires, etc.). By performing this treatability study, uncertainties associated with ISTD as a selected remedy will be reduced, providing a better foundation of remedial recommendations and ultimate selection of remedial actions for the SDA.

Shaw, P.; Nickelson, D.; Hyde, R.

1999-05-01T23:59:59.000Z

38

Old hydrofracture facility tanks contents removal action operations plan at the Oak Ridge National Laboratory, Oak Ridge, Tennessee. Volume 2: Checklists and work instructions  

SciTech Connect

This is volume two of the ORNL old hydrofracture facility tanks contents removal action operations plan. This volume contains checklists and work instructions.

1998-05-01T23:59:59.000Z

39

Remedial Design/Remedial Action Work Plan for Operable Units 6-05 and 10-04, Phase III  

SciTech Connect

The remedial design/remedial action for Operable Unit 6-05 (Waste Area Group 6) and Operable Unit 10-04 (Waste Area Group 10) - collectively called Operable Unit 10-04 has been divided into four phases. Phase I consists of developing and implementing institutional controls at Operable Unit 10-04 sites and developing and implementing Idaho National Laboratory-wide plans for both institutional controls and ecological monitoring. Phase II will remediate sites contaminated with trinitrotoluene and Royal Demolition Explosive. Phase III will remediate lead contamination at a gun range, and Phase IV will remediate hazards from unexploded ordnance. This Phase III remedial Design/Remedial Action Work Plan addresses the remediation of lead-contaminated soils found at the Security Training Facility (STF)-02 Gun Range located at the Idaho National Laboratory. Remediation of the STF-02 Gun Range will include excavating contaminated soils; physically separating copper and lead for recycling; returning separated soils below the remediation goal to the site; stabilizing contaminated soils, as required, and disposing of the separated soils that exceed the remediation goal; encapsulating and disposing of creosote-contaminated railroad ties and power poles; removing and disposing of the wooden building and asphalt pads found at the STF-02 Gun Range; sampling and analyzing soil to determine the excavation requirements; and when the remediation goals have been met, backfilling and contouring excavated areas and revegetating the affected area.

R. P. Wells

2006-09-19T23:59:59.000Z

40

Audit of Work Force Restructuring at the Oak Ridge Operations Office, ER-B-95-06  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

OFFICE OF INSPECTOR GENERAL AUDIT OF WORK FORCE RESTRUCTURING AT THE OAK RIDGE OPERATIONS OFFICE The Office of Inspector General wants to make the distribution of its reports as customer friendly and cost effective as possible. Therefore, this report will be available electronically through the Internet five to seven days after publication at the following alternative addresses: Department of Energy Headquarters Gopher gopher.hr.doe.gov Department of Energy Headquarters Anonymous FTP vm1.hqadmin.doe.gov U.S. Department of Energy Human Resources and Administration Home Page

Note: This page contains sample records for the topic "operation 1943-1944 working" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


41

Report on Inspection of an Intelligence Work-For-Others Project at the Idaho Operations Office, IG-0367  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

REPORT ON INSPECTION OF AN INTELLIGENCE WORK-FOR-OTHERS PROJECT AT THE IDAHO OPERATIONS OFFICE The Office of Inspections wants to make the distribution of its inspection reports as customer friendly and cost effective as possible. Therefore, we are making this report available electronically through the Internet at the following alternative addresses: Department of Energy Headquarters Gopher gopher.hr.doe.gov Department of Energy Headquarters Anonymous FTP vml.hqadmin.doe.gov We are experimenting with various options to facilitate audit report distribution. Your comments would be appreciated and can be provided on the Customer Comment Form attached to the

42

Manhattan Project: Establishing Los Alamos, 1942-1943  

Office of Scientific and Technical Information (OSTI)

Entrance to the Los Alamos "Tech Area" ESTABLISHING LOS ALAMOS Entrance to the Los Alamos "Tech Area" ESTABLISHING LOS ALAMOS (Los Alamos: Laboratory, 1942-1943) Events > Bringing it All Together, 1942-1945 Establishing Los Alamos, 1942-1943 Early Bomb Design, 1943-1944 Basic Research at Los Alamos, 1943-1944 Implosion Becomes a Necessity, 1944 Oak Ridge and Hanford Come Through, 1944-1945 Final Bomb Design, 1944-1945 Atomic Rivals and the ALSOS Mission, 1938-1945 Espionage and the Manhattan Project, 1940-1945 Map of Los Alamos, New Mexico. The final link in the Manhattan Project's far-flung network was the bomb research and development laboratory at Los Alamos, located in the mountains of northern New Mexico. Codenamed "Project Y," the laboratory that designed and fabricated the first atomic bombs began to take shape in spring 1942 when James Conant suggested to Vannevar Bush that the Office of Scientific and Research Development and the Army form a committee to study bomb development. Bush agreed and forwarded the recommendation to Vice President Henry Wallace, Secretary of War Henry Stimson, and General George Marshall (the Top Policy Group). By the time of his appointment in late September, Leslie Groves had orders to set up a committee to study military applications of the bomb. Meanwhile, sentiment was growing among the Manhattan Project scientists that research on the bomb project needed to be better coordinated. Robert Oppenheimer, among others, advocated a central facility where theoretical and experimental work could be conducted according to standard scientific protocols. This would insure accuracy and speed progress. Oppenheimer suggested that the bomb design laboratory operate secretly in an isolated area but allow free exchange of ideas among the scientists on the staff. Groves accepted Oppenheimer's suggestion and began seeking an appropriate location. By the end of the year, they had settled on an unlikely site for the laboratory: an isolated boys' school on a mesa high in the Jemez Mountains (map at left).

43

Remedial Investigation/Feasibility Study Work Plan for the 200-UP-1 Groundwater Operable Unit, Hanford Site, Richland, Washington. Revision  

Science Conference Proceedings (OSTI)

This work plan identifies the objectives, tasks, and schedule for conducting a Remedial Investigation/Feasibility Study for the 200-UP-1 Groundwater Operable Unit in the southern portion of the 200 West Groundwater Aggregate Area of the Hanford Site. The 200-UP-1 Groundwater Operable Unit addresses contamination identified in the aquifer soils and groundwater within its boundary, as determined in the 200 West Groundwater Aggregate Area Management Study Report (AAMSR) (DOE/RL 1992b). The objectives of this work plan are to develop a program to investigate groundwater contaminants in the southern portion of the 200 West Groundwater Aggregate Area that were designated for Limited Field Investigations (LFIs) and to implement Interim Remedial Measures (IRMs) recommended in the 200 West Groundwater AAMSR. The purpose of an LFI is to evaluate high priority groundwater contaminants where existing data are insufficient to determine whether an IRM is warranted and collect sufficient data to justify and implement an IRM, if needed. A Qualitative Risk Assessment (QRA) will be performed as part of the LFI. The purpose of an IRM is to develop and implement activities, such as contaminant source removal and groundwater treatment, that will ameliorate some of the more severe potential risks of groundwater contaminants prior to the RI and baseline Risk Assessment (RA) to be conducted under the Final Remedy Selection (FRS) at a later date. This work plan addresses needs of a Treatability Study to support the design and implementation of an interim remedial action for the Uranium-{sup 99}{Tc}-Nitrate multi-contaminant IRM plume identified beneath U Plant.

Not Available

1994-01-01T23:59:59.000Z

44

New Pump and Treat Facility Remedial Action Work Plan for Test Area North (TAN) Final Groundwater Remediation, Operable Unit 1-07B  

SciTech Connect

This operations and maintenance plan supports the New Pump and Treat Facility (NPTF) remedial action work plan and identifies the approach and requirements for the operations and maintenance activities specific to the final medical zone treatment remedy. The NPTF provides the treatment system necessary to remediate the medical zone portion of the OU 1-07B contaminated groundwater plume. Design and construction of the New Pump and Treat Facility is addressed in the NPTF remedial action work plan. The scope of this operation and maintenance plan includes facility operations and maintenance, remedy five-year reviews, and the final operations and maintenance report for the NPTF.

L. O. Nelson

2003-09-01T23:59:59.000Z

45

Baseline risk assessment for groundwater operable units at the Chemical Plant Area and the Ordnance Works Area, Weldon Spring, Missouri  

Science Conference Proceedings (OSTI)

The U.S. Department of Energy (DOE) and the U.S. Department of the Army (DA) are evaluating conditions in groundwater and springs at the DOE chemical plant area and the DA ordnance works area near Weldon Spring, Missouri. The two areas are located in St. Charles County, about 48 km (30 mi) west of St. Louis. The 88-ha (217-acre) chemical plant area is chemically and radioactively contaminated as a result of uranium-processing activities conducted by the U.S. Atomic Energy Commission in the 1950s and 1960s and explosives-production activities conducted by the U.S. Army (Army) in the 1940s. The 6,974-ha (17,232-acre) ordnance works area is primarily chemically contaminated as a result of trinitrotoluene (TNT) and dinitrotoluene (DNT) manufacturing activities during World War II. This baseline risk assessment (BRA) is being conducted as part of the remedial investigation/feasibility study (RUFS) required under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) of 1980, as amended. The purpose of the BRA is to evaluate potential human health and ecological impacts from contamination associated with the groundwater operable units (GWOUs) of the chemical plant area and ordnance works area. An RI/FS work plan issued jointly in 1995 by the DOE and DA (DOE 1995) analyzed existing conditions at the GWOUs. The work plan included a conceptual hydrogeological model based on data available when the report was prepared; this model indicated that the aquifer of concern is common to both areas. Hence, to optimize further data collection and interpretation efforts, the DOE and DA have decided to conduct a joint RI/BRA. Characterization data obtained from the chemical plant area wells indicate that uranium is present at levels slightly higher than background, with a few concentrations exceeding the proposed U.S. Environmental Protection Agency (EPA) maximum contaminant level (MCL) of 20 {micro}g/L (EPA 1996c). Concentrations of other radionuclides (e.g., radium and thorium) were measured at back-ground levels and were eliminated from further consideration. Chemical contaminants identified in wells at the chemical plant area and ordnance works area include nitroaromatic compounds, metals, and inorganic anions. Trichloroethylene (TCE) and 1,2-dichloroethylene (1,2 -DCE) have been detected recently in a few wells near the raffinate pits at the chemical plant.

NONE

1999-07-14T23:59:59.000Z

46

New Pump and Treat Facility Remedial Action Work Plan For Test Area North Final Groundwater Remediation, Operable Unit 1-07B  

Science Conference Proceedings (OSTI)

This remedial action work plan identifies the approach and requirements for implementing the medial zone remedial action for Test Area North, Operable Unit 1-07B, at the Idaho National Laboratory. This plan details the management approach for the construction and operation of the New Pump and Treat Facility (NPTF). As identified in the remediatial design/remedial action scope of work, a separate remedial design/remedial action work plan will be prepared for each remedial component of the Operable Unit 1-07B remedial action.

Nelson, L. O.

2007-06-12T23:59:59.000Z

47

Work plan for the remedial investigation/feasibility study for the groundwater operable units at the Chemical Plant Area and the Ordnance Works Area, Weldon Spring, Missouri  

Science Conference Proceedings (OSTI)

US Department of Energy (DOE) and the US Army Corps of Engineers (CE) are conducting cleanup activities at two properties, the chemical plant area and the ordnance works area, located adjacent to one another in St. Charles County, Missouri. In accordance with the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), as amended, DOE and CE are evaluating conditions and potential responses at the chemical plant area and at the ordnance works area, respectively, to address groundwater and surface water contamination. This work plan provides a comprehensive evaluation of areas that are relevant to the (GWOUs) of both the chemical plant and the ordnance works area. Following areas or media are addressed in this work plan: groundwater beneath the chemical plant area (including designated vicinity properties described in Section 5 of the RI for the chemical plant area [DOE 1992d]) and beneath the ordnance works area; surface water and sediment at selected springs, including Burgermeister Spring. The organization of this work plan is as follows: Chapter 1 discusses the objectives for conducting the evaluation, including a summary of relevant site information and overall environmental compliance activities to be undertaken; Chapter 2 presents a history and a description of the site and areas addressed within the GWOUs, along with currently available data; Chapter 3 presents a preliminary evaluation of areas included in the GWOUs, which is based on information given in Section 2, and discusses data requirements; Chapter 4 presents rationale for data collection or characterization activities to be carried out in the remedial investigation (RI) phase, along with brief summaries of supporting documents ancillary to this work plan; Chapter 5 discusses the activities planned for GWOUs under each of the 14 tasks for an remedial (RI/FS); Chapter 6 presents proposed schedules for RI/FS for the GWOUS; and Chapter 7 explains the project management structure.

NONE

1995-08-01T23:59:59.000Z

48

Remedial Design/Remedial Action Work Plan for Operable Units 6-05 and 10-04, Phase IV  

Science Conference Proceedings (OSTI)

This Phase IV Remedial Design/Remedial Action Work Plan addresses the remediation of areas with the potential for UXO at the Idaho National Laboratory. These areas include portions of the Naval Proving Ground, the Arco High-Altitude Bombing Range, and the Twin Buttes Bombing Range. Five areas within the Naval Proving Ground that are known to contain UXO include the Naval Ordnance Disposal Area, the Mass Detonation Area, the Experimental Field Station, The Rail Car Explosion Area, and the Land Mine Fuze Burn Area. The Phase IV remedial action will be concentrated in these five areas. For other areas, such as the Arco High-Altitude Bombing Range and the Twin Buttes Bombing Range, ordnance has largely consisted of sand-filled practice bombs that do not pose an explosion risk. Ordnance encountered in these areas will be addressed under the Phase I Operations and Maintenance Plan that allows for the recovery and disposal of ordnance that poses an imminent risk to human health or the environment.

R. P. Wells

2006-11-14T23:59:59.000Z

49

Manhattan Project: The Plutonium Path to the Bomb, 1942-1944  

Office of Scientific and Technical Information (OSTI)

Painting of CP-1 going critical THE PLUTONIUM PATH TO THE BOMB Painting of CP-1 going critical THE PLUTONIUM PATH TO THE BOMB (1942-1944) Events > The Plutonium Path to the Bomb, 1942-1944 Production Reactor (Pile) Design, 1942 DuPont and Hanford, 1942 CP-1 Goes Critical, December 2, 1942 Seaborg and Plutonium Chemistry, 1942-1944 Final Reactor Design and X-10, 1942-1943 Hanford Becomes Operational, 1943-1944 Plutonium, produced in a uranium-fueled reactor (pile), was the second path taken toward achieving an atomic bomb. Design work on a full-scale plutonium production reactor began at the Met Lab in June 1942. Scientists at the Met Lab had the technical expertise to design a production pile, but construction and management on an industrial scale required an outside contractor. General Groves convinced the DuPont Corporation to become the primary contractor for plutonium production. With input from the Met Lab and DuPont, Groves selected a site at Hanford, Washington, on the Columbia River, to build the full-scale production reactors.

50

Manhattan Project: Seaborg and Plutonium Chemistry, Met Lab, 1942-1944  

Office of Scientific and Technical Information (OSTI)

Glenn T. Seaborg looks through a microscope at the world's first sample of pure plutonium, Met Lab, August 20, 1942. SEABORG AND PLUTONIUM CHEMISTRY Glenn T. Seaborg looks through a microscope at the world's first sample of pure plutonium, Met Lab, August 20, 1942. SEABORG AND PLUTONIUM CHEMISTRY (Met Lab, 1942-1944) Events > The Plutonium Path to the Bomb, 1942-1944 Production Reactor (Pile) Design, 1942 DuPont and Hanford, 1942 CP-1 Goes Critical, December 2, 1942 Seaborg and Plutonium Chemistry, 1942-1944 Final Reactor Design and X-10, 1942-1943 Hanford Becomes Operational, 1943-1944 While the Met Lab labored to make headway on pile (reactor) design, Glenn T. Seaborg (right) and his coworkers were trying to learn enough about transuranium chemistry to ensure that plutonium could be chemically separated from the uranium that would be irradiated in a production pile. Using lanthanum fluoride as a carrier, Seaborg isolated a weighable sample of plutonium in August 1942. At the same time, Isadore Perlman and William J. Knox explored the peroxide method of separation; John E. Willard studied various materials to determine which best adsorbed (gathered on its surface) plutonium; Theodore T. Magel and Daniel K. Koshland, Jr., researched solvent-extraction processes; and Harrison S. Brown and Orville F. Hill performed experiments into volatility reactions. Basic research on plutonium's chemistry continued as did work on radiation and fission products.

51

Wind Power Impacts on Electric Power System Operating Costs: Summary and Perspective on Work to Date; Preprint  

DOE Green Energy (OSTI)

Electric utility system planners and operators are concerned that variations in wind plant output may increase the operating costs of the system. This concern arises because the system must maintain an instantaneous balance between the aggregate demand for electric power and the total power generated by all power plants feeding the system. This is a highly sophisticated task that utility operators and automatic controls perform routinely, based on well-known operating characteristics for conventional power plants and a great deal of experience accumulated over many years. System operators are concerned that variations in wind plant output will force the conventional power plants to provide compensating variations to maintain system balance, thus causing the conventional power plants to deviate from operating points chosen to minimize the total cost of operating the system. The operators' concerns are compounded by the fact that conventional power plants are generally under their control and thus are dispatchable, whereas wind plants are controlled instead by nature. Although these are valid concerns, the key issue is not whether a system with a significant amount of wind capacity can be operated reliably, but rather to what extent the system operating costs are increased by the variability of the wind.

Smith, J. C.; DeMeo, E. A.; Parsons, B.; Milligan, M.

2004-03-01T23:59:59.000Z

52

Operable Unit 3-14, Tank Farm Soil and INTEC Groundwater Remedial Design/Remedial Action Scope of Work  

SciTech Connect

This Remedial Design/Remedial Action (RD/RA) Scope of Work pertains to OU 3-14 Idaho Nuclear Technology and Engineering Center and the Idaho National Laboratory and identifies the remediation strategy, project scope, schedule, and budget that implement the tank farm soil and groundwater remediation, in accordance with the May 2007 Record of Decision. Specifically, this RD/RA Scope of Work identifies and defines the remedial action approach and the plan for preparing the remedial design documents.

D. E. Shanklin

2007-07-25T23:59:59.000Z

53

Working Copy  

NLE Websites -- All DOE Office Websites (Extended Search)

NWP subcontractor personnel work at a number of DOE generator sites where NWP has no direct contractual authority for overall site operations. NWP has therefore negotiated...

54

Operation and control of space-based solar energy power plants with CCGT using helium as a working medium  

Science Conference Proceedings (OSTI)

The features of a Space-based Solar Energy Power Plant for electric power generation with a closed cycle gas turbine running on Helium are discussed. The system is intended for generating both electricity and process heat for industrial manufacturing processes in a large space station. A system overview for operation and control of such a plant is presented.

Sutsch, A.

1986-01-01T23:59:59.000Z

55

Operable Unit 3-13, Group 3, Other Surface Soils Remediation Sets 4-6 (Phase II) Remedial Design/Remedial Action Work Plan  

SciTech Connect

This Remedial Design/Remedial Action Work Plan provides the framework for defining the remedial design requirements, preparing the design documentation, and defining the remedial actions for Waste Area Group 3, Operable Unit 3-13, Group 3, Other Surface Soils, Remediation Sets 4-6 (Phase II) located at the Idaho Nuclear Technology and Engineering Center at the Idaho National Laboratory. This plan details the design developed to support the remediation and disposal activities selected in the Final Operable Unit 3-13, Record of Decision.

D. E. Shanklin

2006-06-01T23:59:59.000Z

56

Work with Apple's Rhapsody Operating System which Allows Simultaneous UNIX Program Development, UNIX Program Execution, and PC Application Execution  

E-Print Network (OSTI)

Over the past decade, UNIX workstations have provided a very powerful program development environment. However, workstations are more expensive than PCs and Macintoshes and require a system manager for day-to-day tasks such as disk backup, adding users, and setting up print queues. Native commercial software for system maintenance and "PC applications" has been lacking under UNIX. Apple's new Rhapsody operating system puts the current MacOS on a NeXT UNIX foundation and adds an enhanced NeXTSTEP object oriented development environment called Yellow Box. Rhapsody simultaneously runs UNIX and commercial Macintosh applications such as word processing or spreadsheets. Thus a UNIX detector Monte Carlo can run for days in the background at the same time as a commercial word processing program. And commercial programs such as Dantz Retrospect are being made available to make disk backup easy under Rhapsody. Apple has announced that in 1999 they intend to be running Rhapsody, or MacOS X as it will be called in the commercial release, on all their newer computers. MacOS X may be of interest to those who have trouble hiring expert UNIX system managers; and to those who would prefer to have a single computer and operating system on their desktop that serves both the needs of UNIX program development and running commercial applications, simultaneously. We present our experiences running UNIX programs and Macintosh applications under the Rhapsody DR2 Developer Release.

Don Summers; Chris Riley; Lucien Cremaldi; David Sanders

2001-05-27T23:59:59.000Z

57

FY 1991 environmental research programs for the Nevada Operations Office: Work plan and quarterly reports, first and second quarter reports  

SciTech Connect

The work carried out on behalf of the DOE by the Desert Research Institute (DRI) includes a wide range of research and support activities associated with the Weapons Testing Program conducted at the Nevada Test Site (NTS). Ongoing and new environmental research programs to be conducted by DRI over the period of this contract include archaeological studies, site mitigation plans, compliance activities, and historical research; offsite community radiation monitoring support; environmental compliance activities related to stat and federal regulations; hydrologic assessment of containment of underground nuclear detonations; hydrology/radionuclide investigations designed to better understand and predict the possible subsurface movement of radionuclides at the NTS; and support of various statistical and data management and design, laboratory, field, and administrative activities. In addition to these, archaeological site characterization, flood hazards for rail transportation, and paleofaunal investigations will be carried out in support of the Yucca Mountain Project. Other areas of the overall program which require DRI support are classified security activities, radiation safety and training, quality assurance and control, computer protection and historical data management, review and classification of DRI documents, and preparation of any special reports, e.g., quarterly reports, not included in the requirements of the individual projects. A new set of programs funded by the Office of Technology Development will be in place by the third quarter of FY 1991. These projects will address environmental restoration and waste management concerns, among other related topics. This document contains the Work Plan, including project descriptions, tasks, deliverables and quarterly progress reports on each project for FY 1991.

NONE

1991-05-01T23:59:59.000Z

58

FY 1990 environmental research programs for the Nevada Operations Office. Work plan and quarterly reports, first through fourth quarter reports  

Science Conference Proceedings (OSTI)

This work includes a wide range of research and support activities associated with the Weapons Testing Program conducted at the Nevada Test Site (NTS). Ongoing and new environmental research programs to be conducted by DRI over the period of this contract include archaeological studies and site mitigation plans; offsite community radiation monitoring support; environmental compliance activities related to state and federal regulations; hydrologic assessment of containment of underground nuclear detonations; hydrology/radionuclide investigations designed to better understand and predict the possible subsurface movement of radionuclides at the NTS; and support of various statistical and data management and design activities. In addition to these, archaeological and other activities will be carried out in support of the Yucca Mountain Project. Other areas of the overall program which require DRI support are classified security activities, radiation safety and training, quality assurance and control, computer protection and historical data management, derivative classification of DRI documents, and preparation of any special reports not included in the requirements of the individual projects.

NONE

1990-11-01T23:59:59.000Z

59

Manhattan Project: Emilio Segr, 1954  

Office of Scientific and Technical Information (OSTI)

Emilio Segr, 1954 Events > Bringing It All Together, 1942-1945 > Basic Research at Los Alamos, Los Alamos: Laboratory, 1943-1944 Emilio Segr, 1954...

60

Manhattan Project: Enrico Fermi  

Office of Scientific and Technical Information (OSTI)

Enrico Fermi Events > Bringing it All Together, 1942-1945 > Basic Research at Los Alamos, Los Alamos: Laboratory, 1943-1944 Enrico Fermi...

Note: This page contains sample records for the topic "operation 1943-1944 working" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


61

Manhattan Project: Hans Bethe  

Office of Scientific and Technical Information (OSTI)

Hans Bethe Events > Bringing It All Together, 1942-1945 > Basic Research at Los Alamos, Los Alamos: Laboratory, 1943-1944 People > Scientists > Hans Bethe Hans Bethe...

62

Remedial Investigation Work Plan for Upper East Fork Poplar Creek Operable Unit 3 at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee. Environmental Restoration Program  

Science Conference Proceedings (OSTI)

Upper East Fork Popular Creek Operable Unit 3 (UEFPC OU 3) is a source term OU composed of seven sites, and is located in the western portion of the Y-12 Plant. For the most part, the UEFPC OU 3 sites served unrelated purposes and are geographically removed from one another. The seven sites include the following: Building 81-10, the S-2 Site, Salvage Yard oil storage tanks, the Salvage Yard oil/solvent drum storage area, Tank Site 2063-U, the Salvage Yard drum deheader, and the Salvage Yard scrap metal storage area. All of these sites are contaminated with at least one or more hazardous and/or radioactive chemicals. All sites have had some previous investigation under the Y-12 Plant RCRA Program. The work plan contains summaries of geographical, historical, operational, geological, and hydrological information specific to each OU 3 site. The potential for release of contaminants to receptors through various media is addressed, and a sampling and analysis plan is presented to obtain objectives for the remedial investigation. Proposed sampling activities are contingent upon the screening level risk assessment, which includes shallow soil sampling, soil borings, monitoring well installation, groundwater sampling, and surface water sampling. Data from the site characterization activities will be used to meet the above objectives. A Field Sampling Investigation Plan, Health and Safety Plan, and Waste Management Plan are also included in this work plan.

Not Available

1993-08-01T23:59:59.000Z

63

Feasibility study for remedial action for the groundwater operable units at the chemical plant area and the ordnance works area, Weldon Spring, Missouri  

SciTech Connect

The U.S. Department of Energy (DOE) and the U.S. Department of Army (DA) are conducting an evaluation to identify the appropriate response action to address groundwater contamination at the Weldon Spring Chemical Plant (WSCP) and the Weldon Spring Ordnance Works (WSOW), respectively. The two areas are located in St. Charles County, about 48 km (30 rni) west of St. Louis. The groundwater operable unit (GWOU) at the WSCP is one of four operable units being evaluated by DOE as part of the Weldon Spring Site Remedial Action Project (WSSRAP). The groundwater operable unit at the WSOW is being evaluated by the DA as Operable Unit 2 (OU2); soil and pipeline contamination are being managed under Operable Unit 1 (OU1). Remedial activities at the WSCP and the WSOW are being conducted in accordance with the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA). Consistent with DOE policy, National Environmental Policy Act (NEPA) values have been incorporated into the CERCLA process. A remedial investigation/feasibility study (RI/FS) work plan summarizing initial site conditions and providing site hydrogeological and exposure models was published in August of 1995 (DOE 1995). The remedial investigation (RI) and baseline risk assessment (BRA) have also recently been completed. The RI (DOE and DA 1998b) discusses in detail the nature, extent, fate, and transport of groundwater and spring water contamination. The BRA (DOE and DA 1998a) is a combined baseline assessment of potential human health and ecological impacts and provides the estimated potential health risks and ecological impacts associated with groundwater and springwater contamination if no remedial action were taken. This feasibility study (FS) has been prepared to evaluate potential options for addressing groundwater contamination at the WSCP and the WSOW. A brief description of the history and environmental setting of the sites is presented in Section 1.1, key information relative to the nature and extent of contamination is presented in Section 1.2, and the results of the BRA are summarized in Section 1.3. The objective of this FS is discussed in Section 1.4, and preliminary remediation goals are identified in Section 1.5. The organization of the remaining chapters of this FS is outlined in Section 1.6.

NONE

1999-07-15T23:59:59.000Z

64

Remedial investigation/feasibility study Work Plan and addenda for Operable Unit 4-12: Central Facilities Area Landfills II and III at the Idaho National Engineering Laboratory  

SciTech Connect

This document is divided into two main sections -- the Work Plan and the addenda. The Work Plan describes the regulatory history and physical setting of Operable Unit 4-12, previous sampling activities, and data. It also identifies a preliminary conceptual model, preliminary remedial action alternatives, and preliminary applicable or relevant and appropriate requirements. In addition, the Work Plan discusses data gaps and data quality objectives for proposed remedial investigation activities. Also included are tasks identified for the remedial investigation/feasibility study (RI/FS) and a schedule of RI/FS activities. The addenda include details of the proposed field activities (Field Sampling Plan), anticipated quality assurance activities (Quality Assurance Project Plan), policies and procedures to protect RI/FS workers and the environment during field investigations (Health and Safety Plan), and policies, procedures, and activities that the Department of Energy will use to involve the public in the decision-making process concerning CFA Landfills II and III RI/FS activities (Community Relations Plan).

Keck, K.N.; Stormberg, G.J.; Porro, I.; Sondrup, A.J.; McCormick, S.H.

1993-07-01T23:59:59.000Z

65

Remedial investigation work plan for Chestnut Ridge Operable Unit 4 (Rogers Quarry/Lower McCoy Branch) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee  

SciTech Connect

The Oak Ridge Y-12 Plant includes - 800 acres near the northeast comer of the reservation and adjacent to the city of Oak Ridge (Fig. 1-1). The plant is a manufacturing and developmental engineering facility that produced components for various nuclear weapons systems and provides engineering support to other Energy Systems facilities. More than 200 contaminated sites have been identified at the Y-12 Plant that resulted from past waste management practices. Many of the sites have operable units (OUs) based on priority and on investigative and remediation requirements. This Remedial Investigation RI work plan specifically addresses Chestnut Ridge OU 4. Chestnut Ridge OU 4 consists of Rogers Quarry and Lower McCoy Branch (MCB). Rogers Quarry, which is also known as Old Rogers Quarry or Bethel Valley Quarry was used for quarrying from the late 1940s or early 1950s until about 1960. Since that time, the quarry has been used for disposal of coal ash and materials from Y-12 production operations, including classified materials. Disposal of coal ash ended in July 1993. An RI is being conducted at this site in response to CERCLA regulations. The overall objectives of the RI are to collect data necessary to evaluate the nature and extent of contaminants of concern, support an Ecological Risk Assessment and a Human Health Risk Assessment, support the evaluation of remedial alternatives, and ultimately develop a Record of Decision for the site. The purpose of this work plan is to outline RI activities necessary to define the nature and extent of suspected contaminants at Chestnut Ridge OU 4. Potential migration pathways also will be investigated. Data collected during the RI will be used to evaluate the risk posed to human health and the environment by OU 4.

Not Available

1993-09-01T23:59:59.000Z

66

Remedial investigation work plan for Bear Creek Valley Operable Unit 4 (shallow groundwater in Bear Creek Valley) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee  

Science Conference Proceedings (OSTI)

To effectively evaluate the cumulative impact of releases from multiple sources of contamination, a structured approach has been adopted for Oak Ridge Reservation (ORR) based on studies of the groundwater and surface water separate from studies of the sources. Based on the realization of the complexity of the hydrogeologic regime of the ORR, together with the fact that there are numerous sources contributing to groundwater contamination within a geographical area, it was agreed that more timely investigations, at perhaps less cost, could be achieved by separating the sources of contamination from the groundwater and surface water for investigation and remediation. The result will be more immediate attention [Records of Decision (RODs) for interim measures or removal actions] for the source Operable Units (OUs) while longer-term remediation investigations continue for the hydrogeologic regimes, which are labeled as integrator OUs. This remedial investigation work plan contains summaries of geographical, historical, operational, geological, and hydrological information specific to the unit. Taking advantage of the historical data base and ongoing monitoring activities and applying the observational approach to focus data gathering activities will allow the feasibility study to evaluate all probable or likely alternatives.

Not Available

1993-07-01T23:59:59.000Z

67

Remedial Investigation work plan for Bear Creek Valley Operable Unit 4 (shallow groundwater in Bear Creek Valley) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee  

Science Conference Proceedings (OSTI)

To effectively evaluate the cumulative impact of releases from multiple sources of contamination, a structured approach has been adopted for Oak Ridge Reservation (ORR) based on studies of the groundwater and surface water separate from studies of the sources. Based on the realization of the complexity of the hydrogeologic regime of the ORR, together with the fact that there are numerous sources contributing to groundwater contamination within a geographical area, it was agreed that more timely investigations, at perhaps less cost, could be achieved by separating the sources of contamination from the groundwater and surface water for investigation and remediation. The result will be more immediate attention [Records of Decision (RODS) for interim measures or removal actions] for the source Operable Units (OUs) while longer-term remediation investigations continue for the hydrogeologic regime`s, which are labeled as integrator OUs. This Remedial Investigation work plan contains summaries of geographical, historical, operational, geological, and hydrological information specific to the unit. Taking advantage of the historical data base and ongoing monitoring activities and applying the observational approach to focus data gathering activities will allow the Feasibility Study to evaluate all probable or likely alternatives.

Not Available

1993-09-01T23:59:59.000Z

68

7/26/2011 University of Texas at Austin Information Technology Services ITS Security Operations A. Security Consultant Scope of Work  

E-Print Network (OSTI)

7/26/2011 University of Texas at Austin ­ Information Technology Services ITS Security;7/26/2011 University of Texas at Austin ­ Information Technology Services ITS Security Operations 2 ii. Document of Texas at Austin ­ Information Technology Services ITS Security Operations 3 iii. Attend

Texas at Austin, University of

69

NREL is a national laboratory of the U.S. Department of Energy, Office of Energy Efficiency and Renewable Energy, operated by the Alliance for Sustainable Energy, LLC. Working with NREL -Commercialization  

E-Print Network (OSTI)

NREL is a national laboratory of the U.S. Department of Energy, Office of Energy Efficiency need and the capabilities available at NREL. #12;NREL is a national laboratory of the U.S. Department and Renewable Energy, operated by the Alliance for Sustainable Energy, LLC. Working with NREL

70

OPERATIONS (OPS)  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

OPS) OPS) OBJECTIVE OPS.1 The formality and discipline of operations is adequate to conduct work safely and programs are in place to maintain this formality and discipline. (CR 13) Scope: The Conduct of Operations Program was evaluated during the recent KE Basin FTS ORR and was found to be adequately implemented. Based on this result and the subsequent program enhancements, the scope of the review is to be limited to the SWS operating and maintenance evolutions. Criteria * Programmatic elements of conduct of operations are in place for SWS operations. (DOE Order 5480.19) * The SWS operations personnel adequately demonstrate the principles of conduct of operations requirements during the shift performance period. (DOE Order 5480.19)

71

Working/Functional Fluids  

Science Conference Proceedings (OSTI)

... power cycle except that it uses an organic working fluid instead of water to allow operation at lower temperatures, including geothermal or solar ...

2012-10-05T23:59:59.000Z

72

Work Address:  

NLE Websites -- All DOE Office Websites (Extended Search)

BO SAULSBURY BO SAULSBURY Work Address: Home Address: Oak Ridge National Laboratory 12952 Buckley Road National Transportation Research Center Knoxville, TN 37934 Building NTRC-2, Room 118 (865) 288-0750 Oak Ridge, TN 37831-6479 (865) 574-4694 saulsburyjw@ornl.gov Technical Specialties: Land use planning Environmental and socioeconomic impact assessment National Environmental Policy Act (NEPA) project management Vehicle fuel economy Education: 1986 B. A., History (minors in English and Business), The University of Tennessee 1989 M. S., Planning, The University of Tennessee (Thesis title: Land Use Compatibility Planning for Airfield Environs: Intergovernmental Cooperation to Protect Land Users From the Effects of Aircraft Operations)

73

Materials Reliability Program: Characterizations of Type 316 Cold-Worked Stainless Steel Highly Irradiated Under PWR Operating Condi tions (MRP-73)  

Science Conference Proceedings (OSTI)

Irradiation-induced material degradations such as irradiation-assisted stress corrosion cracking (IASCC), irradiation-induced void swelling, and irradiation-caused embrittlement have been observed in core internals components in pressurized water reactors (PWRs). This report describes hot cell testing and characterization of a bottom-mounted instrument tube (flux thimble) that was exposed in an operating PWR for about 23 years, providing valuable data for assessing radiation effects in PWRs.

2002-08-26T23:59:59.000Z

74

Materials Reliability Program: Characterization of Type 316 Cold Worked Stainless Steel Highly Irradiated Under PWR Operating Conditions (International IASCC Advisory Committee Phase 3 Program Final Report) (MRP-214)  

Science Conference Proceedings (OSTI)

Various types of irradiation-induced material degradation such as irradiation-assisted stress corrosion cracking (IASCC), irradiation-induced void swelling, and irradiation-caused embrittlement have been observed in core internals components in pressurized water reactors (PWR). This report describes hot cell testing and characterization of bottom-mounted instrument tubes (flux thimble) that were exposed in operating PWRs for about 10 to 20 effective full power years (EFPY), providing valuable data for as...

2007-09-06T23:59:59.000Z

75

TANK OPERATIONS CONTRACT CONSTRUCTION MANAGEMENT METHODOLOGY UTILIZING THE AGENCY METHOD OF CONSTRUCTION MANAGEMENT TO SAFELY AND EFFECTIVELY COMPLETE NUCLEAR CONSTRUCTION WORK  

SciTech Connect

Washington River Protection Solutions, LLC (WRPS) has faced significant project management challenges in managing Davis-Bacon construction work that meets contractually required small business goals. The unique challenge is to provide contracting opportunities to multiple small business construction subcontractors while performing high hazard work in a safe and productive manner. Previous to the Washington River Protection Solutions, LLC contract, Construction work at the Hanford Tank Farms was contracted to large companies, while current Department of Energy (DOE) Contracts typically emphasize small business awards. As an integral part of Nuclear Project Management at Hanford Tank Farms, construction involves removal of old equipment and structures and installation of new infrastructure to support waste retrieval and waste feed delivery to the Waste Treatment Plant. Utilizing the optimum construction approach ensures that the contractors responsible for this work are successful in meeting safety, quality, cost and schedule objectives while working in a very hazardous environment. This paper describes the successful transition from a traditional project delivery method that utilized a large business general contractor and subcontractors to a new project construction management model that is more oriented to small businesses. Construction has selected the Agency Construction Management Method. This method was implemented in the first quarter of Fiscal Year (FY) 2009, where Construction Management is performed by substantially home office resources from the URS Northwest Office in Richland, Washington. The Agency Method has allowed WRPS to provide proven Construction Managers and Field Leads to mentor and direct small business contractors, thus providing expertise and assurance of a successful project. Construction execution contracts are subcontracted directly by WRPS to small or disadvantaged contractors that are mentored and supported by DRS personnel. Each small contractor is mentored and supported utilizing the principles of the Construction Industry Institute (CII) Partnering process. Some of the key mentoring and partnering areas that are explored in this paper are, internal and external safety professional support, subcontractor safety teams and the interface with project and site safety teams, quality assurance program support to facilitate compliance with NQA-1, construction, team roles and responsibilities, work definition for successful fixed price contracts, scheduling and interface with project schedules and cost projection/accruals. The practical application of the CII Partnering principles, with the Construction Management expertise of URS, has led to a highly successful construction model that also meets small business contracting goals.

LESO KF; HAMILTON HM; FARNER M; HEATH T

2010-01-14T23:59:59.000Z

76

NSLS Operations & Engineering  

NLE Websites -- All DOE Office Websites (Extended Search)

Operations & Engineering Electrical Equipment Controls & Diagnostics Computer Systems Power Systems Mechanical Design Mechanical Tech Utilities Vacuum Work Planning & Controls...

77

Remedial Investigation Work Plan for Chestnut Ridge Operable Unit 1 (Chestnut Ridge Security Pits) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee  

Science Conference Proceedings (OSTI)

This document outlines the activities necessary to conduct a Remedial Investigation (RI) of the Chestnut Ridge Security Pits (CRSP) at the Oak Ridge Y-12 Plant. The CRSP, also designated Chestnut Ridge Operable Unit (OU) 1, is one of four OUs along Chestnut Ridge on the Oak Ridge Reservation (ORR). The purpose of the RI is to collect data to (1) evaluate the nature and extent of known and suspected contaminants, (2) support an Ecological Risk Assessment (ERA) and a Human Health Risk Assessment (HHRA), (3) support the feasibility study in the development and analysis of remedial alternatives, and (4) ultimately, develop a Record of Decision (ROD) for the site. This chapter summarizes the regulatory background of environmental investigation on the ORR and the approach currently being followed and provides an overview of the RI to be conducted at the CRSP. Subsequent chapters provide details on site history, sampling activities, procedures and methods, quality assurance (QA), health and safety, and waste management related to the RI.

Not Available

1994-03-01T23:59:59.000Z

78

Manhattan Project: Bringing it All Together, 1942-1945  

Office of Scientific and Technical Information (OSTI)

Eric Jette, Charles Critchfield, and J. Robert Oppenheimer, Los Alamos BRINGING IT ALL TOGETHER Eric Jette, Charles Critchfield, and J. Robert Oppenheimer, Los Alamos BRINGING IT ALL TOGETHER (1942-1945) Events > Bringing It All Together, 1942-1945 Establishing Los Alamos, 1942-1943 Early Bomb Design, 1943-1944 Basic Research at Los Alamos, 1943-1944 Implosion Becomes a Necessity, 1944 Oak Ridge and Hanford Come Through, 1944-1945 Final Bomb Design, 1944-1945 Atomic Rivals and the ALSOS Mission, 1938-1945 Espionage and the Manhattan Project, 1940-1945 No matter how much enriched uranium and plutonium might be produced at Oak Ridge and Hanford, it would all come to nothing if workable weapon designs could not be developed in time. To this end, in late 1942 Leslie Groves established a bomb research and development laboratory at Los Alamos in the remote mountains of northern New Mexico. The early work at Los Alamos concentrated primarily on defining the problems that needed to be solved. Basic research on a variety of theoretical issues continued throughout 1943. By 1944, it had become clear that, while a simple and reliable "gun-type" design could be used for a uranium bomb, the considerably more complicated implosion method would be required to produce a plutonium weapon. With the successful Leslie Groves and J. Robert Oppenheimer Allied landings in France on "D-Day," June 6, 1944, the war in Europe appeared to be entering its final phase. Germany ceased to be the primary intended target. General Groves and his advisers turned their sights on Japan, and the rush was on to complete the atomic bomb in time to end the war in the Pacific.

79

Manhattan Project: Implosion Becomes a Necessity, Los Alamos, 1944  

Office of Scientific and Technical Information (OSTI)

Implosion IMPLOSION BECOMES A NECESSITY Implosion IMPLOSION BECOMES A NECESSITY (Los Alamos: Laboratory, 1944) Events > Bringing It All Together, 1942-1945 Establishing Los Alamos, 1942-1943 Early Bomb Design, 1943-1944 Basic Research at Los Alamos, 1943-1944 Implosion Becomes a Necessity, 1944 Oak Ridge and Hanford Come Through, 1944-1945 Final Bomb Design, 1944-1945 Atomic Rivals and the ALSOS Mission, 1938-1945 Espionage and the Manhattan Project, 1940-1945 An early implosion experiment, Los Alamos, 1944 Because the gun-type bomb design seemed so simple and practical, Deke Parsons had assigned implosion studies a low priority and placed the emphasis on the more familiar artillery method. Consequently, Seth H. Neddermeyer performed his early implosion tests in relative obscurity. Neddermeyer found it difficult to achieve symmetrical implosions at the low velocities he had achieved. When the Princeton mathematician John von Neumann, a Hungarian refugee, visited Los Alamos late in 1943, he suggested that high-speed assembly and high velocities would prevent predetonation and achieve more symmetrical explosions. A relatively small, subcritical mass could be placed under so much pressure by a symmetrical implosion that an efficient detonation would occur. Less fissionable material would be required, bombs could be ready earlier, and extreme purification of plutonium would be unnecessary. Von Neumann's theories excited Robert Oppenheimer, who assigned Parsons's deputy, George B. Kistiakowsky, the task of perfecting implosion techniques. (Kistiakowsky would later become President Dwight D. Eisenhower's science adviser.) Because Parsons and Neddermeyer did not get along, it was Kistiakowsky who worked with the scientists on the implosion project.

80

Manhattan Project: William S. "Deke" Parsons  

Office of Scientific and Technical Information (OSTI)

Alamos, Los Alamos: Laboratory, 1943-1944 Places > Other Places > Bomb Casing and Drop Test Sites Places > Los Alamos: The Laboratory > S-Site Implosion Facility William S. "Deke"...

Note: This page contains sample records for the topic "operation 1943-1944 working" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


81

BOREAS Operations  

NLE Websites -- All DOE Office Websites (Extended Search)

Study Area Operations/Thompson Airport (NSA-Ops) Study Area Operations/Thompson Airport (NSA-Ops) NSA Operations (NSA-Ops) The Keewatin Air Hanger: site of BOREAS Ops 1994 Dr. Piers Sellers working in Ops, 1994 BOREAS "Air Force" The NASA C-130 The University of Wyoming King Air The NASA Helicopter The NRC Twin Otter The NCAR Electra The Ontario Chieftain Back to the BOREAS Photo Page Index Other Sites: NSA Photos ||NSA-BP Photos | NSA-Fen Photos | NSA-OA Photos | NSA-OBS Photos | NSA-OJP Photos | NSA-UBS Photos | NSA-YJP Photos | NSA-Ops Photos SSA Photos || SSA-Airport Photos | SSA-Fen Photos | SSA-Mix Photos | SSA-OA Photos | SSA-OBS Photos | SSA-OJP Photos | SSA-YA Photos | SSA-YJP Photos | SSA-Ops Photos | ORNL DAAC Home || ORNL Home || NASA || Privacy, Security, Notices || Data Citation || Rate Us || Help |

82

Chemistry Department Operations  

NLE Websites -- All DOE Office Websites (Extended Search)

Procedures (c). Laser Safety Information: (d). Chemistry Department Laser Safety Guidelines Operational Work Planning (a). Training waiver (b). Staff Shop Posting Local...

83

Remedial investigation work plan for Bear Creek Valley Operable Unit 2 (Rust Spoil Area, SY-200 Yard, Spoil Area 1) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee. Environmental Restoration Program  

Science Conference Proceedings (OSTI)

The enactment of the Resource Conservation and Recovery Act (RCRA) in 1976 and the Hazardous and Solid Waste Amendments (HSWA) to RCRA in 1984 created management requirements for hazardous waste facilities. The facilities within the Oak Ridge Reservation (ORR) were in the process of meeting the RCRA requirements when ORR was placed on the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) National Priorities List (NPL) on November 21, 1989. Under RCRA, the actions typically follow the RCRA Facility Assessment (RFA)/RCRA Facility Investigation (RFI)/Corrective Measures Study (CMS)/Corrective Measures implementation process. Under CERCLA the actions follow the PA/SI/Remedial Investigation (RI)/Feasibility Study (FS)/Remedial Design/Remedial Action process. The development of this document will incorporate requirements under both RCRA and CERCLA into an RI work plan for the characterization of Bear Creek Valley (BCV) Operable Unit (OU) 2.

Not Available

1993-05-01T23:59:59.000Z

84

Work Manager  

Science Conference Proceedings (OSTI)

A real-time control system has been developed and deployed nationally to support BTs work management programme. This paper traces the history, system architecture, development, deployment and service aspects of this very large programme. Many ...

G. J. Garwood

1997-01-01T23:59:59.000Z

85

JGI - Operations  

NLE Websites -- All DOE Office Websites (Extended Search)

Operations The Operations Department sees to it that JGI has the best possible facilities and support, ensuring that its operations are conducted in accordance with the...

86

Power Operations  

NLE Websites -- All DOE Office Websites (Extended Search)

Power Operations Outage Coordination Standards of Conduct Transmission Planning You are here: SN Home page > Power Operations Power Operations Western's Sierra Nevada Region...

87

Alaska Natural Gas in Underground Storage (Working Gas) (Million...  

U.S. Energy Information Administration (EIA) Indexed Site

9302013 Next Release Date: 10312013 Referring Pages: Underground Working Natural Gas in Storage - All Operators Alaska Underground Natural Gas Storage - All Operators Working...

88

Ropes for Live Working  

Science Conference Proceedings (OSTI)

Fiber ropes represent an essential tool in many applications associated with the electric power industry. Ropes used in proximity to or in contact with high-voltage power lines require demanding dielectric properties as well as strength and durability. A comprehensive understanding of live working (LW) rope construction, performance, and use is necessary for safe and efficient operations wherever such ropes are used.

2008-11-18T23:59:59.000Z

89

Working Copy  

NLE Websites -- All DOE Office Websites (Extended Search)

DOE/WIPP-99-2286 Waste Isolation Pilot Plant Environmental Notification or Reporting Implementation Plan Revision 7 U.S. Department of Energy December 2013 This document supersedes DOE/WIPP-99-2286, Rev. 6. Working Copy Waste Isolation Pilot Plant Environmental Notification or Reporting Implementation Plan DOE/WIPP-99-2286, Rev. 7 2 TABLE OF CONTENTSCHANGE HISTORY SUMMARY .............................................. 3 ACRONYMS AND ABBREVIATIONS ............................................................................ 4 1.0 INTRODUCTION .................................................................................................. 6 2.0 NOTIFICATION OR REPORTING REQUIREMENTS AND COMMITMENTS ..... 7

90

Working Copy  

NLE Websites -- All DOE Office Websites (Extended Search)

1 Effective Date: 11/05/13 WP 12-IS.01-6 Revision 10 Industrial Safety Program - Visitor, Vendor, User, Tenant, and Subcontractor Safety Controls Cognizant Section: Industrial Safety/Industrial Hygiene Approved By: Tom Ferguson Working Copy Industrial Safety Program - Visitor, Vendor, User, Tenant, and Subcontractor Safety Controls WP 12-IS.01-6, Rev. 10 2 TABLE OF CONTENTS CHANGE HISTORY SUMMARY ..................................................................................... 7 ACRONYMS AND ABBREVIATIONS ............................................................................. 8 1.0 INTRODUCTION 1 ............................................................................................... 10 2.0 VISITORS ........................................................................................................... 11

91

New Switching Operator Training  

Science Conference Proceedings (OSTI)

This Technical Update report summarizes work done on a new project, launched in 2006, that is focused on the development of training materials for apprentice and new operators. The project is part of EPRI's Switching Safety and Reliability research.

2006-12-11T23:59:59.000Z

92

CONDUCT OF OPERATIONS (CO)  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

CONDUCT OF OPERATIONS (CO) CONDUCT OF OPERATIONS (CO) OBJECTIVE TA-55 SST Facility NNSA ORR Implementation Plan 1 1 CO.1 The formality and discipline of operations is adequate to conduct work safely and programs are inplace to maintain this formality and discipline. (Core Requirement 13) Criteria 1. Programmatic elements of conduct of operations are in place for TA-55 SST operations. 2. The TA-55 SST operations personnel adequately demonstrate the principles of conduct ofoperations requirements during the shift performance period. Approach Record Reviews: Review procedures and other facility documents to verify compliance with conduct of operations principles. Interviews: Interview a sampling of the TA-55 SST associated personnel to validate their understanding of the conduct of operations principles (e.g., procedure usage,

93

Live Work Guide for Substations  

Science Conference Proceedings (OSTI)

Live work (work on energized circuits) is the preferred method of maintenance where system integrity, system reliability, and operating revenues are at a premium and removal of a circuit or a substation from service is not acceptable. Live work (LW) may also be beneficial in construction and storm damage repair. Furthermore, live work may be unavoidable in the case of substations that serve essential facilities such as hospitals, law enforcement, fire departments, and intrusion alarms if standby local ge...

2004-10-28T23:59:59.000Z

94

Operations & Maintenance  

NLE Websites -- All DOE Office Websites (Extended Search)

Rates Operations & Maintenance Operations OASIS: WACM (Note: this site is not hosted by Western and requires a digital certificate and login for full access.) wesTTrans Common...

95

CFN Ops Plan | Work Planning  

NLE Websites -- All DOE Office Websites (Extended Search)

Operations Plan Operations Plan Work Planning & Control for Experiments and Operations All experimental work will be conducted in accordance with Work Planning and Control for Experiments and Operations, which ensures proper design and operation of all experiments prior to their commencement. CFN will use the SBMS provided standard form for the formal documentation. The Lead Experimenter/Responsible person will notify the Experimental Safety Review Committee of any new experiments or modifications to existing experiments. CFN will appoint an Experimental Safety Review Committee. This committee will consist of the Experiment Review Coordinator, CFN personnel, Facility Support Representative (FSR), Environmental Compliance Representative (ECR). Additional subject matter experts may be appointed on an ad-hoc

96

Statement of Work  

NLE Websites -- All DOE Office Websites (Extended Search)

DE-SOL-0003174 1 FOR OFFICIAL USE ONLY - SOURCE SELECTION SENSITIVE, SEE FAR 3.104-3 PERFORMANCE WORK STATEMENT (PWS) Emergency Operations Training Academy (EOTA) Support Services May 27, 2011 Draft 1.0 Introduction The U.S. Department of Energy (DOE), National Nuclear Security Administration (NNSA), Office of Emergency Operations (NA-40) requires support services in the development and delivery of training, exercises, and other related technical and administrative support services at the Emergency Operations Training Academy (EOTA) in Albuquerque, New Mexico. 2.0 Background NA-40's mission is to ensure that capabilities are in place to respond to any NNSA and DOE facility emergency. NA-40 is the nation's premier responder to any nuclear or radiological

97

ARM - Engineering Work Request & Engineering Work Order Guidelines  

NLE Websites -- All DOE Office Websites (Extended Search)

Work Request & Engineering Work Request & Engineering Work Order Guidelines Page Contents: Introduction Discussion of the ARM Climate Research Facility Engineering Process: The Engineering Change Request (ECR) and the Engineering Change Order (ECO) Operations and Engineering Task Consulting: The Engineering Work Request (EWR) and the Engineering Work Order (EWO) Relationship of the ECR/ECO and EWR/EWO to the Engineering Task Tracking Tool Relationship of the ECR/ECO and EWR/EWO to the Existing Configuration Control Process in the ARM Climate Research Facility(PIF/CAR, PRR, ORR, and BCR) Glossary Frequently Asked Questions (PDF, 173K) Engineering Work Request & Engineering Work Order Guidelines Process Guidelines for the Engineering Change Request/Engineering Change Order and Engineering Work Request/Engineering Work Order

98

Mon Valley work plan  

Office of Legacy Management (LM)

GWSHP 1.8 GWSHP 1.8 U.S. Department of Energy UMTRA Ground Water Project Work Plan for Characterization Activities at the Shiprock UMTRA Project Site June 1998 Prepared by U.S. Department of Energy Albuquerque Operations Office Grand Junction Office Project Number UGW-511-0020-01-000 Document Number U0013400 Work Performed under DOE Contract No. DE-AC13-96GJ87335 Note: Some of the section page numbers in the Table of Contents may not correspond to the page on which the section appears when viewing them in Adobe Acrobat. Document Number U0013400 Contents DOE/Grand Junction Office Work Plan for Characterization Activities at Shiprock Project Site June 1998 Draft Final Page v Contents Acronyms . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . xi 1.0 Introduction .

99

Robotic Technologies for Live Working  

Science Conference Proceedings (OSTI)

The objective of this report is to review selected available robotic technologies and evaluate their possible applicability to live working. The selection criteria for robotic technologies included suitability for operation in a high-voltage environment; mechanical load capacity; and extent of reach, size, and weight compatible with live work applications. The report provides a brief history of robotics in live work dating back to late 1970s and the development of the EPRI TOMCAT (Teleoperator for Operat...

2010-12-23T23:59:59.000Z

100

the decision of the ReliabilityFirst Corporation (RFC) to include Holland Board of Public Works (Holland) on the NERC Compliance Registry as a Transmission Owner (TO) and Transmission Operator (TOP). Statement of Appeal  

E-Print Network (OSTI)

NERC Compliance Registry within the RFC Region for the functions of TO and TOP. Holland appeals its registration as a TO and TOP arguing that: (a) its facilities are operated as radial facilities and, therefore, fall under the exclusion of RFCs definition of bulk electric system (BES) facilities; 1 (b) its facilities are not material to the BES; (c) registration of its facilities will not improve BES reliability; (d) excluding its facilities from the registry will not result in a gap in BES reliability; and (e) compliance with TO and TOP standards presents a disproportionate and undue hardship on Holland. 2 Holland serves approximately 27,000 retail and commercial customers in Holland, Michigan, as well as portions of Holland, Park, Laketown, and Fillmore townships. 3 Holland owns and operates 24 miles of 138 kV transmission lines, seven generating units (ranging from 11.5 to 83 MW) and eight high voltage substations. 4 Holland has a total of 226 MW of internal generation. 5 Holland also owns shares in the J.H. Campbell Complex and the Belle River Plant which are operated by Consumers Energy and Detroit Edison, respectively. 6

unknown authors

2010-01-01T23:59:59.000Z

Note: This page contains sample records for the topic "operation 1943-1944 working" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


101

Modeling of Copper Converter Foamover and Operational ...  

Science Conference Proceedings (OSTI)

ESP Dust Recovery Process Test Works, Plant Trial, Commissioning, Operations and Metallurgical Performance Expansion and Collapse of Liquid Aluminum...

102

Advance In system Materials Processing Operations  

Science Conference Proceedings (OSTI)

ESP Dust Recovery Process Test Works, Plant Trial, Commissioning, Operations and Metallurgical Performance Expansion and Collapse of Liquid Aluminum...

103

TRU TeamWorks  

NLE Websites -- All DOE Office Websites (Extended Search)

8, 2012 8, 2012 WIPP Quick Facts (As of 9-26-12) 10,849 Shipments received since opening (10,252 CH and 597 RH) 83,693 Cubic meters of waste disposed (82,394 CH and 299 RH) 162,472 Containers disposed in the underground (161,882 CH and 590 RH) Photo above right: CBFO Deputy Manager Ed Ziemianski presents a WIPP team with the Green Zia Program Silver Level Award from the New Mexico Environment Department on Aug. 15, 2012 in recognition of environmental initiatives. Shown right of Ziemianski is Farok Sharif, WTS President and General Manager. New WIPP Management and Operating Contractor to start October 1 Nuclear Waste Partnership LLC (NWP) will start work as the WIPP Management and Operating Contractor on Monday, October 1. WIPP receives Green Zia Award The Waste Isolation Pilot Plant (WIPP), the U.S. Department of Energy (DOE)

104

TRUTeamWorks 06-24-04  

NLE Websites -- All DOE Office Websites (Extended Search)

nuclear waste repository program to assist with these challenges is also in the works." "WIPP is, of course, the only operational geological repository in the world,"...

105

Argonne TDC: Work for Others Program - ANL  

Identify In-house Project Support: 3 : Draft Statement of Work (SOW) with milestones. 4: Submit WFO information to DOE Operations Office Send Draft WFO Agreement to ...

106

Operating strategy generators for nuclear reactors  

Science Conference Proceedings (OSTI)

Operating strategy generators, i.e., the software intended for increasing the efficiency of work of nuclear power plant operators, are discussed. The possibilities provided by the domestic and foreign operating-strategy generators are analyzed.

Solovyev, D. A., E-mail: and@est.mephi.ru; Semenov, A. A.; Shchukin, N. V. [National Research Nuclear University MEPhI (Russian Federation)

2011-12-15T23:59:59.000Z

107

MPI Collective Operations over IP Multicast  

Science Conference Proceedings (OSTI)

Many common implementations of Message Passing Interface (MPI) implement collective operations over point-to-point operations. This work examines IP multicast as a framework for collective operations. IP multicast is not reliable. If a receiver is not ...

Hsiang Ann Chen; Yvette O. Carrasco; Amy W. Apon

2000-05-01T23:59:59.000Z

108

HANFORD ENGINEER WORKS  

Office of Legacy Management (LM)

HANFORD ENGINEER WORKS HANFORD ENGINEER WORKS IJd *P-t - - ~~~ssiticatiC+n cwcetted rat G.E. NUCLEONICS PROJECT xi I ~@L.%&~--G-ENERAI,@ ELECTRIC z ,m ._.__.-. _ I--..-. By Authority of. COMPANY ._ Atmic Energy Commission Office of Hanford Dire&xl Operations Riohland, Washington Attention; Mr. Carleton Shugg, Manager ./ ALPKA-ROLLED EL'GIL%I jw -879 ' . *_ a. f' Richland, Washington February 6, 1948 , Thla Dclc.Jv-

109

Government Operation  

Science Conference Proceedings (OSTI)

Use Cases from NBD(NIST Big Data) Requirements WG V1.0. http://bigdatawg. nist.gov/home.php. Contents. Blank Template. Government Operation ...

2013-09-07T23:59:59.000Z

110

Operations Research  

E-Print Network (OSTI)

Mar 1, 2005 ... Operations Research. Report 2005-01. On a closedness theorem. Mikls Ujvri. Marc 2005. Etvs Lornd University of Sciences. Department...

111

Operating Instructions  

Science Conference Proceedings (OSTI)

... The system operation is center around 3 areas of the equipment 1) Deposition chamber 2) Vaporizer 3) Chiller/cold finger ...

2013-01-18T23:59:59.000Z

112

Operations research  

Science Conference Proceedings (OSTI)

In Evita, Andrew Lloyd Webber and Tim Rice wrote: Politics, the Art of the Possible. To those of us in the operations research community, we postulate: Operations Research, the Science of Better - (i.e. better processes, better systems and better decisions). ...

William P. Pierskalla

2009-01-01T23:59:59.000Z

113

Operation crosscheck  

SciTech Connect

This report consists of three sections covering the three major areas of Lawrence Livermore Laboratory`s participation in Operation Crosscheck. These areas are: Diagnostic Aircraft; Radiochemical Sampling; and Device Assembly and Handling, Barbers Point. The information contained in these sections has been extracted from Crosscheck post-operation reports.

Gilbert, F. C.

1964-11-06T23:59:59.000Z

114

February 28, 2006, Department letter reporting completion of NNSA portion of Commitment 23 in the 2004-1 implementation plan, Oversight of Complex, High-Hazard Nuclear Operations, which requires the development of site office action plans to improve the consistency and reliability of work planning and work control at the activity level, including the incorporation of Integrated Safety Management core functions  

NLE Websites -- All DOE Office Websites (Extended Search)

Washington, DC 20585 Washington, DC 20585 February 28, 2006 OFFICE O F THE ADMINISTRATOR The Honorable A. J. Eggenberger Ch a i rm an Defensc Nuclear Facilities Safety Board 625 Indiana Avenue, NW., Suite 700 Washington, D.C. 20004-2901 Dear Mr. Chairman: On Julie 10, 2005, Secretary Bodnian submitted the Department's Iiizplenzentution Plun to Itizpt-ove Oversight qf'Nucleur Operutions in response to Defense Nuclear Facilities Safety Board (DNFSB) Recommendation 2004- I , Oversight qf Complex, High-Hrrzurd Nucleur Openrtiotzs. Section 5.3 of the Implementation Plan (IP) addresses Revitalizing Integruted SU/i-'ty Munagernent Implementution, and Subsection 5.3.2 addresses Work Plunning mil Work Control ut the Activity Level. Commitment 23 of the 1P requires development of site office action plans to improve the consistency and reliability of work

115

TRU TeamWorks  

NLE Websites -- All DOE Office Websites (Extended Search)

, 2004 , 2004 By the Numbers WIPP marks five-year anniversary Shipments scheduled to arrive at WIPP for the week of 4/4/04 - 4/10/04: 18 Total shipments received at WIPP: 2,456 Total volume disposed at WIPP: 19,042 m 3 FY04 Performance Metrics D E P A R T M E N T O F E N E R G Y U N I T E D S T A T ES O F A M E R I C A TeamWorks TeamWorks TRU A weekly e-newsletter for the Waste Isolation Pilot Plant team For those who endured the early morning cold of March 26, 1999, to witness WIPP's first shipment, it may seem like yesterday. Yet Friday marked five years of WIPP operations. Relative newcomer to WIPP - but not to the waste management industry - CBFO Deputy Manager Lloyd Piper observed, "The transformation from a facility in "standby" mode to operational mode has been nothing short of amazing."

116

NSLS Work Planning & Controls  

NLE Websites -- All DOE Office Websites (Extended Search)

Work Planning & Controls NSLS Work Planning and Control Procedure Lead Working Guidelines Information on Working in Areas Subject to Radiation from VUV Injection Procedure for...

117

REACTOR OPERATIONS AND CONTROL  

E-Print Network (OSTI)

of Neural Networks to the Operations of Nuclear Power Plants," Nucl. Safety, 32, 68 ~1991!. 3. I. PÁZSIT detectors.1 According to the technical specifications of the Ring- hals power plant, in which this work and the "distorted" axial flux shape, and from the latter, *Current address: The Swedish Nuclear Power Inspectorate

Pázsit, Imre

118

Quantum Operations and Measurement  

E-Print Network (OSTI)

Quantum Operations and Measurement M.P Seevinck E-mail: M.P.Seevinck@phys.uu.nl Utrecht field in quantum physics ­ or perhaps better, a new way of doing quantum physics ­ . . . Surprisingly of these developments to the conceptual problems of quantum mechanics. In our view, the new work on quantum information

Seevinck, Michiel

119

Quantum Operations and Measurement  

E-Print Network (OSTI)

Quantum Operations and Measurement # M.P Seevinck # E­mail: M.P.Seevinck@phys.uu.nl Utrecht in quantum physics -- or perhaps better, a new way of doing quantum physics -- . . . Surprisingly, with few to the conceptual problems of quantum mechanics. In our view, the new work on quantum information changes

Seevinck, Michiel

120

Submitted Work & Work in Preparation - CECM  

E-Print Network (OSTI)

May 23, 2001 ... Submitted Work & Work in Preparation. I. G. Lisle and G. J. Reid, Symmetry Classification Using Invariant Moving Frames, to be submitted.

Note: This page contains sample records for the topic "operation 1943-1944 working" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


121

Operation Terminology  

NLE Websites -- All DOE Office Websites (Extended Search)

Energy Conservation Magnets require a large amount of power to control a particle beam. In order to conserve energy and money when a beam line is down, Operations will install a...

122

NSLS Committees | Work Planning/Permit Review Committee  

NLE Websites -- All DOE Office Websites (Extended Search)

require enhanced work planning. Committees review and approve submitted work permits. NSLS reports to Operations Section Head, Emil Zitvogel. NSLS-II reports to ESH Manager,...

123

DOE - Office of Legacy Management -- Hanford Engineer Works ...  

NLE Websites -- All DOE Office Websites (Extended Search)

Hanford Engineer Works - WA 01 FUSRAP Considered Sites Site: Hanford Engineer Works (WA.01 ) Designated Name: Alternate Name: Location: Evaluation Year: Site Operations: Site...

124

Operations Research Analysts  

U.S. Energy Information Administration (EIA) Indexed Site

Operations Research Analysts Operations Research Analysts The U.S. Energy Information Administration (EIA) within the Department of Energy has forged a world-class information program that stresses quality, teamwork, and employee growth. In support of our program, we offer a variety of profes- sional positions, including the Operations Research Analyst, whose work is associated with the development and main- tenance of energy modeling systems. Responsibilities: Operations Research Analysts perform or participate in one or more of the following important functions: * Develop, design, perform, and document a broad range of analyses and studies involving current and projected energy pricing, production, supply, and distribution, and consumption * Using computer programming skills and knowledge of energy industries and markets, designs and develops math-

125

SSA Operations  

NLE Websites -- All DOE Office Websites (Extended Search)

Area Operations (SSA-Ops) Area Operations (SSA-Ops) "BOREAS Ops" was located at the Snodrifters Lodge, in Candle Lake, Saskatchewan. Radiosonde balloon launch at Ops The NASA Helicopter lands at Ops A meeting at the Snodrifter's Lodge Release of a radiosonde at the SSA operations center in Candle Lake. Back to the BOREAS Photo Page Index Other Sites: NSA Photos ||NSA-BP Photos | NSA-Fen Photos | NSA-OA Photos | NSA-OBS Photos | NSA-OJP Photos | NSA-UBS Photos | NSA-YJP Photos | NSA-Ops Photos SSA Photos || SSA-Airport Photos | SSA-Fen Photos | SSA-Mix Photos | SSA-OA Photos | SSA-OBS Photos | SSA-OJP Photos | SSA-YA Photos | SSA-YJP Photos | SSA-Ops Photos | ORNL DAAC Home || ORNL Home || NASA || Privacy, Security, Notices || Data Citation || Rate Us || Help | User Services - Tel: +1 (865) 241-3952 or E-mail: uso@daac.ornl.gov

126

Field Guide: Live Working Rope  

Science Conference Proceedings (OSTI)

Ropes are an essential tool in many applications associated with the electric power industry. Ropes used in proximity to or in contact with high-voltage power lines require demanding dielectric properties as well as strength and durability. A comprehensive understanding of live working rope use is necessary for safe and efficient operations wherever such ropes are used.

2009-03-31T23:59:59.000Z

127

Work Force Restructuring Activities  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Force Restructuring Activities Force Restructuring Activities December 10, 2008 Note: Current updates are in bold # Planned Site/Contractor HQ Approved Separations Status General * LM has finalized the compilation of contractor management team separation data for the end of FY07 actuals and end of FY08 and FY09 projections. LM has submitted to Congress the FY 2007 Annual Report on contractor work force restructuring activities. The report has been posted to the LM website. *LM conducted a DOE complex-wide data call to the Field and Operations offices for DOE Contractor Management teams to provide, by program, actual contractor separation data for the end of FY 2008 and projections for the end of FY 2009 and FY 2010. The data will be used to keep senior management informed of upcoming large WFR actions.

128

Integrated formal operations plan  

SciTech Connect

The concept of formal operations (that is, a collection of business practices to assure effective, accountable operations) has vexed the Laboratory for many years. To date most attempts at developing such programs have been based upon rigid, compliance-based interpretations of a veritable mountain of Department of Energy (DOE) orders, directives, notices, and standards. These DOE dictates seldom take the broad view but focus on highly specialized programs isolated from the overall context of formal operations. The result is a confusing array of specific, and often contradictory, requirements that produce a patchwork of overlapping niche programs. This unnecessary duplication wastes precious resources, dramatically increases the complexity of our work processes, and communicates a sense of confusion to our customers and regulators. Coupled with the artificial divisions that have historically existed among the Laboratory`s formal operations organizations (quality assurance, configuration management, records management, training, etc.), this approach has produced layers of increasingly vague and complex formal operations plans, each of which interprets its parent and adds additional requirements of its own. Organizational gridlock ensues whenever an activity attempts to implement these bureaucratic monstrosities. The integrated formal operations plan presented is to establish a set of requirements that must be met by an integrated formal operations program, assign responsibilities for implementation and operation of the program, and specify criteria against which the performance of the program will be measured. The accountable line manager specifies the items, processes, and information (the controlled elements) to which the formal operations program specified applies. The formal operations program is implemented using a graded approach based on the level of importance of the various controlled elements and the scope of the activities in which they are involved.

Cort, G.; Dearholt, W.; Donahue, S.; Frank, J.; Perkins, B.; Tyler, R.; Wrye, J.

1994-01-05T23:59:59.000Z

129

Surveillance Guides - Work Control Process  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Work Control Process Work Control Process 1.0 Objective The objective of this surveillance guide is to provide lines of inquiry for evaluating the effectiveness of the contractor's work control process. Users should be cognizant that the lines of inquiry need to be further tailored to fit specific facilities or activities in accordance with contractual mechanisms such as Maintenance Implementation Plans, Conduct of Operations Implementation Plans, and the Integrated Safety Management System Description. 2.0 References 2.1 DOE 4330.4B Maintenance Management Program 2.2 48 CFR 1970.5204-2 Department of Energy Acquisition Regulations 2.3 DOE O 5480.19, Conduct of Operations 2.4 10 CFR 830.120, Quality Assurance 3.0 Requirements Implemented This surveillance is conducted to verify implementation of Core

130

Operations | National Nuclear Security Administration  

National Nuclear Security Administration (NNSA)

| National Nuclear Security Administration | National Nuclear Security Administration Our Mission Managing the Stockpile Preventing Proliferation Powering the Nuclear Navy Emergency Response Recapitalizing Our Infrastructure Continuing Management Reform Countering Nuclear Terrorism About Us Our Programs Our History Who We Are Our Leadership Our Locations Budget Our Operations Media Room Congressional Testimony Fact Sheets Newsletters Press Releases Speeches Events Social Media Video Gallery Photo Gallery NNSA Archive Federal Employment Apply for Our Jobs Our Jobs Working at NNSA Blog Operations Home > About Us > Our Programs > Emergency Response > Responding to Emergencies > Operations Operations NNSA's Emergency Response Operations program acts as the headquarters command and control, functioning as the coordinating focal point for all

131

Operations | National Nuclear Security Administration  

NLE Websites -- All DOE Office Websites (Extended Search)

| National Nuclear Security Administration | National Nuclear Security Administration Our Mission Managing the Stockpile Preventing Proliferation Powering the Nuclear Navy Emergency Response Recapitalizing Our Infrastructure Continuing Management Reform Countering Nuclear Terrorism About Us Our Programs Our History Who We Are Our Leadership Our Locations Budget Our Operations Media Room Congressional Testimony Fact Sheets Newsletters Press Releases Speeches Events Social Media Video Gallery Photo Gallery NNSA Archive Federal Employment Apply for Our Jobs Our Jobs Working at NNSA Blog Operations Home > About Us > Our Programs > Emergency Response > Responding to Emergencies > Operations Operations NNSA's Emergency Response Operations program acts as the headquarters command and control, functioning as the coordinating focal point for all

132

Work Force Retention Work Group Charter  

Energy.gov (U.S. Department of Energy (DOE))

The Work force Retention Work Group is established to support the Departments critical focus on maintaining a high-performing work force at a time when a significant number of the workers needed to support DOEs national security mission are reaching retirement age.

133

Live Working Resource Center  

Science Conference Proceedings (OSTI)

This report is a summary of work performed in 2008 on the EPRI Live Working Resource Center (LWRC) web site.

2008-12-16T23:59:59.000Z

134

War Gaming Peace Operations  

Science Conference Proceedings (OSTI)

Today's military personnel fight against and work with a diverse variety of nonstate actors, from al-Qaeda terrorists to major nongovernmental organizations who provide vital humanitarian assistance. Furthermore, the nontraditional battle spaces where ... Keywords: Afghanistan, NGOs, active learning, board game, course of action, culture, curriculum, facilitator, faith-based, humanitarian, humanitarian assistance, indeterminacy, index, intelligence, kinetic, military, negotiations, operations, post-conflict, provincial reconstruction, random events, relationships, religion, religious, stability, terrorists, war game for peace

Roger Mason, Eric Patterson

2013-02-01T23:59:59.000Z

135

ORNL radioactive waste operations  

SciTech Connect

Since its beginning in 1943, ORNL has generated large amounts of solid, liquid, and gaseous radioactive waste material as a by-product of the basic research and development work carried out at the laboratory. The waste system at ORNL has been continually modified and updated to keep pace with the changing release requirements for radioactive wastes. Major upgrading projects are currently in progress. The operating record of ORNL waste operation has been excellent over many years. Recent surveillance of radioactivity in the Oak Ridge environs indicates that atmospheric concentrations of radioactivity were not significantly different from other areas in East Tennesseee. Concentrations of radioactivity in the Clinch River and in fish collected from the river were less than 4% of the permissible concentration and intake guides for individuals in the offsite environment. While some radioactivity was released to the environment from plant operations, the concentrations in all of the media sampled were well below established standards.

Sease, J.D.; King, E.M.; Coobs, J.H.; Row, T.H.

1982-01-01T23:59:59.000Z

136

Underground Working Natural Gas in Storage - All Operators  

U.S. Energy Information Administration (EIA) Indexed Site

Monthly Download Series History Download Series History Definitions, Sources & Notes Definitions, Sources & Notes Show Data By: Data Series Area Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 View History U.S. 1,857,570 2,270,934 2,642,060 2,936,813 3,210,598 3,564,920 1973-2013 Alaska 14,007 15,277 16,187 17,087 18,569 20,455 2013-2013 Lower 48 States 1,843,563 2,255,657 2,625,874 2,919,726 3,192,029 3,544,465 2011-2013 Alabama 20,405 20,908 20,110 20,532 19,968 21,262 1995-2013 Arkansas 1,486 1,928 2,330 2,735 3,168 3,372 1990-2013 California 255,453 287,757 309,448 326,906 329,024 338,271 1990-2013 Colorado 15,625 19,489 25,833 32,642 40,240 46,136 1990-2013 Illinois 50,160 75,951 110,815 142,938 177,700 218,245 1990-2013

137

Underground Working Natural Gas in Storage - All Operators  

Gasoline and Diesel Fuel Update (EIA)

Monthly Download Series History Download Series History Definitions, Sources & Notes Definitions, Sources & Notes Show Data By: Data Series Area Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 View History U.S. 1,857,570 2,270,934 2,642,060 2,936,813 3,210,598 3,564,920 1973-2013 Alaska 14,007 15,277 16,187 17,087 18,569 20,455 2013-2013 Lower 48 States 1,843,563 2,255,657 2,625,874 2,919,726 3,192,029 3,544,465 2011-2013 Alabama 20,405 20,908 20,110 20,532 19,968 21,262 1995-2013 Arkansas 1,486 1,928 2,330 2,735 3,168 3,372 1990-2013 California 255,453 287,757 309,448 326,906 329,024 338,271 1990-2013 Colorado 15,625 19,489 25,833 32,642 40,240 46,136 1990-2013 Illinois 50,160 75,951 110,815 142,938 177,700 218,245 1990-2013

138

U.S. Working Storage Capacity at Operable Refineries  

Annual Energy Outlook 2012 (EIA)

Area: U.S. East Coast (PADD 1) Midwest (PADD 2) Gulf Coast (PADD 3) Rocky Mountain (PADD 4) West Coast (PADD 5) Period: Annual (as of January 1) Download Series History Download...

139

FY 1994 Annual Work Plan  

SciTech Connect

In accordance with the Inspector General`s Strategic Planning Policy directive, the Office of Inspector General (OIG) annually updates its Strategic Plan with budgetary and program guidance for the next fiscal year. The program guidance identifies and establishes priorities for OIG coverage of important DOE issues and operations, provides the basis for assigning OIG resources, and is the source for issues covered in Assistant Inspectors General annual work plans. The Office of the Assistant Inspector General for Audits (AIGA) publishes an Annual Work Plan in September of each year. The plan includes the OIG program guidance and shows the commitment of resources necessary to accomplish the assigned work and meet our goals. The program guidance provides the framework within which the AIGA work will be planned and accomplished. Audits included in this plan are designed to help insure that the requirements of our stakeholders have been considered and blended into a well balanced audit program.

1993-09-30T23:59:59.000Z

140

Training Work Group Charter | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Charter Charter Training Work Group Charter The Training Work Group fosters improvements in the quality, efficacy, and delivery of DOE safety training, and realizes significant efficiencies by minimizing redundancies across the DOE Complex. The Work Group provides a collaborative opportunity for DOE to gain insights from operating contractors, the contractor work force and their representatives, and to combine the best wisdom to assure that the most efficient and effective worker health and safety program expectations, approaches and processes are in place and are well communicated. Training Work Group Charter More Documents & Publications HSS Briefing to the Defense Nuclear Facilities Safety Board (DNFSB) on Union Activities 10 CFR 851 Implementation Work Group Charter

Note: This page contains sample records for the topic "operation 1943-1944 working" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


141

Manhattan Project: CP-1 Goes Critical, Met Lab, December 2, 1942  

Office of Scientific and Technical Information (OSTI)

Painting of CP-1 going critical CP-1 GOES CRITICAL Painting of CP-1 going critical CP-1 GOES CRITICAL (Met Lab, December 2, 1942) Events > The Plutonium Path to the Bomb, 1942-1944 Production Reactor (Pile) Design, 1942 DuPont and Hanford, 1942 CP-1 Goes Critical, December 2, 1942 Seaborg and Plutonium Chemistry, 1942-1944 Final Reactor Design and X-10, 1942-1943 Hanford Becomes Operational, 1943-1944 While arrangements were proceeding for the construction of full-size plutonium production reactors, critical questions remained about their basic design. The Italian physicist Enrico Fermi hoped to answer some of these questions with CP-1, his experimental "Chicago Pile #1" at the University of Chicago. On December 2, 1942, after a series of frustrating delays, CP-1 first achieved a self-sustaining fission chain reaction. After the end of the war, Leslie Groves, commander of the Manhattan Project, described the first time CP-1 went critical as the single most important scientific event in the development of atomic power.

142

ORISE: Work for Others  

NLE Websites -- All DOE Office Websites (Extended Search)

Institute for Science Education Work for Others The U.S. Department of Energy's (DOE) Work for Others (WFO) program allows the performance of work for non-DOE entities when the...

143

IBRD Operational Decision Framework  

SciTech Connect

The IBRD Operational Decision Framework in this document is an expansion of an emerging general risk management framework under development by an interagency working group. It provides the level of detail necessary to develop a general Consequence Management Guidance Document for biological contamination remediation and restoration. It is the intent of this document to support both wide area and individual site remediation and restoration activities. This product was initiated as a portion of the IBRD Task 1 Systems Analysis to aid in identification of wide area remediation and restoration shortcomings and gaps. The draft interagency general risk management framework was used as the basis for the analysis. The initial Task 1 analysis document expanded the draft interagency framework to a higher level of resolution, building on both the logic structure and the accompanying text explanations. It was then employed in a qualitative manner to identify responsible agencies, data requirements, tool requirements, and current capabilities for each decision and task. This resulted in identifying shortcomings and gaps needing resolution. Several meetings of a joint LLNL/SNL working group reviewed and approved the initial content of this analysis. At the conclusion of Task 1, work continued on the expanded framework to generate this Operational Decision Framework which is consistent with the existing interagency general risk management framework. A large LLNL task group met repeatedly over a three-month period to develop the expanded framework, coordinate the framework with the biological remediation checklist, and synchronize the logic with the Consequence Management Plan table of contents. The expanded framework was briefed at a large table top exercise reviewing the interagency risk management framework. This exercise had representation from major US metropolitan areas as well as national agencies. This product received positive comments from the participants. Upon completion of the Operational Decision Framework, another joint LLNL/SNL working group conducted a day-long review. Identified modifications were made to the document, resulting in the included product.

Greenwalt, R; Hibbard, W; Raber, E; Carlsen, T; Folks, K; MacQueen, D; Mancieri, S; Bunt, T; Richards, J; Hirabayashi-Dethier, J

2010-11-12T23:59:59.000Z

144

Live Working Resource Center  

Science Conference Proceedings (OSTI)

EPRI created the Live Working Resource Center web site to provide utilities the critical information they need to conduct live work safely and efficiently. This report is a summary of work performed in 2007 on the web site. See EPRI's Live Working Resource Center.

2007-11-30T23:59:59.000Z

145

Scientific Working Groups  

Science Conference Proceedings (OSTI)

... TWGDAM 1988). SWGDOG, Scientific Working Group on Dogs and Orthogonal Detection Guidelines, 2004. SWGTOX, Scientific ...

2013-07-10T23:59:59.000Z

146

Accelerator Operators and Software Development  

SciTech Connect

At Thomas Jefferson National Accelerator Facility, accelerator operators perform tasks in their areas of specialization in addition to their machine operations duties. One crucial area in which operators contribute is software development. Operators with programming skills are uniquely qualified to develop certain controls applications because of their expertise in the day-to-day operation of the accelerator. Jefferson Lab is one of the few laboratories that utilizes the skills and knowledge of operators to create software that enhances machine operations. Through the programs written; by operators, Jefferson Lab has improved machine efficiency and beam availability. Because many of these applications involve automation of procedures and need graphical user interfaces, the scripting language Tcl and the Tk toolkit have been adopted. In addition to automation, some operator-developed applications are used for information distribution. For this purpose, several standard web development tools such as perl, VBScript, and ASP are used. Examples of applications written by operators include injector steering, spin angle changes, system status reports, magnet cycling routines, and quantum efficiency measurements. This paper summarizes how the unique knowledge of accelerator operators has contributed to the success of the Jefferson Lab control system. *This work was supported by the U.S. DOE contract No. DE-AC05-84-ER40150.

April Miller; Michele Joyce

2001-11-01T23:59:59.000Z

147

Remedial investigation work plan for Bear Creek Valley Operable Unit 1 (S-3 Ponds, Boneyard/Burnyard, Oil Landfarm, Sanitary Landfill 1, and the Burial Grounds, including Oil Retention Ponds 1 and 2) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee. Volume 1, Main text  

Science Conference Proceedings (OSTI)

The intent and scope of the work plan are to assemble all data necessary to facilitate selection of remediation alternatives for the sites in Bear Creek Valley Operable Unit 1 (BCV OU 1) such that the risk to human health and the environment is reduced to acceptable levels based on agreements with regulators. The ultimate goal is to develop a final Record Of Decision (ROD) for all of the OUs in BCV, including the integrator OU. However, the initial aim of the source OUs is to develop a ROD for interim measures. For source OUs such as BCV OU 1, data acquisition will not be carried out in a single event, but will be carried out in three stages that accommodate the schedule for developing a ROD for interim measures and the final site-wide ROD. The three stages are as follows: Stage 1, Assemble sufficient data to support decisions such as the need for removal actions, whether to continue with the remedial investigation (RI) process, or whether no further action is required. If the decision is made to continue the RI/FS process, then: Stage 2, Assemble sufficient data to allow for a ROD for interim measures that reduce risks to the human health and the environment. Stage 3, Provide input from the source OU that allows a final ROD to be issued for all OUs in the BCV hydrologic regime. One goal of the RI work plan will be to ensure that sampling operations required for the initial stage are not repeated at later stages. The overall goals of this RI are to define the nature and extent of contamination so that the impact of leachate, surface water runoff, and sediment from the OU I sites on the integrator OU can be evaluated, the risk to human health and the environment can be defined, and the general physical characteristics of the subsurface can be determined such that remedial alternatives can be screened.

Not Available

1993-09-01T23:59:59.000Z

148

Live Work with High Temperature Conductors  

Science Conference Proceedings (OSTI)

This report examines issues that may arise when live work is undertaken on conductors that operate at high temperatures (HT conductors) and provides the results from selected tests on the temperature levels reached by tools in contact with hot conductors. It also discusses possible concerns that may arise during de-energized work on lines that use HT conductors.

2009-12-15T23:59:59.000Z

149

FUPWG Purpose, Policies, and Operations  

NLE Websites -- All DOE Office Websites (Extended Search)

FEDERAL UTILITY PARTNERSHIP WORKING GROUP FEDERAL UTILITY PARTNERSHIP WORKING GROUP Purpose, Policies and Operations Draft - For Review and Comment Only Table of Contents: I. Introduction II. Membership III. Steering Committee Membership and Responsibilities IV. Meetings V. Meeting Content VI. Future Direction Appendices: 1) Vision Statement 2) Edison Electric Institute (EEI) Commitment Statement 3) FUPWG Members 4) List of Steering Committee Members 5) List of Previous and planned Future Meetings 6) List of Topics Addressed By FUPWG 7) Speaker Guidelines 8) Host Responsibilities 1 Last Updated 7/22/2010 I. Introduction The Federal Utility Partnership Working Group (FUPWG or Working Group) was initiated by

150

FUPWG Purpose, Policies, and Operations  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

FEDERAL UTILITY PARTNERSHIP WORKING GROUP FEDERAL UTILITY PARTNERSHIP WORKING GROUP Purpose, Policies and Operations Draft - For Review and Comment Only Table of Contents: I. Introduction II. Membership III. Steering Committee Membership and Responsibilities IV. Meetings V. Meeting Content VI. Future Direction Appendices: 1) Vision Statement 2) Edison Electric Institute (EEI) Commitment Statement 3) FUPWG Members 4) List of Steering Committee Members 5) List of Previous and planned Future Meetings 6) List of Topics Addressed By FUPWG 7) Speaker Guidelines 8) Host Responsibilities 1 Last Updated 7/22/2010 I. Introduction The Federal Utility Partnership Working Group (FUPWG or Working Group) was initiated by

151

Improve your operations training  

Science Conference Proceedings (OSTI)

Operators need problem-solving expertise that allows them to successfully restore the system online. But they should also understand how what they did worked, and why. The method for this is process logic (PL). PL is a common-sense, efficient method of problem solving using an if-them deductive-reasoning approach to discover root cause of system upsets. PL procedures in troubleshooting call for the operator to: examine all effects; separate logical (expected) changes from unexpected; identify and tag unique set(s) of thumbprints; determine source of thumbprints (i.e. originating component); locate original change in said component; verify root cause change; devise appropriate corrective action plan; and implement corrective action. Several examples illustrate this method for troubleshooting.

Swain, J.H.; Maddux, M. (K and S Associates, Texas City, TX (United States))

1994-12-01T23:59:59.000Z

152

CRAD, Work Controls Assessment Plan | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Work Controls Assessment Plan Work Controls Assessment Plan CRAD, Work Controls Assessment Plan Performance Objective: Management should have an established work control process in place with authorized, controlled and documented methods that provide an accurate status of the work to be performed. Criteria: Work planning addresses applicable laws, codes and regulations. Work planning includes operational configuration constraints; material, tool, and manpower requirements; inter-organizational coordination; operational history; special training; safety considerations; hazards protection requirements; post-maintenance testing; quality control requirements; and other considerations as necessary. The work to be accomplished is defined by identifying the existing deficiency and condition; prescribing appropriate approvals; and including

153

Mechanical Operations and Maintenance  

NLE Websites -- All DOE Office Websites (Extended Search)

Holiday Work Status Holiday Work Status Mechanical Operations & Maintenance Group APS Storage Ring Magnets The Advanced Photon Source (APS) at the Argonne National Laboratory is a national synchrotron-radiation research facility funded by the U.S. Department of Energy. Using high-brilliance x-ray beams from the APS, an international community of scientists conducts forefront basic and applied research in the fields of material science, biological science, physics, chemistry, environmental, geophysical and planetary science. The 1.1-km circumference APS facility consists of several major subsystems including magnets, vacuum chambers, radio-frequency cavities, diagnostics instrumentation, x-ray absorbers and apertures, and cooling water subsystems. Each of these subsystems contains hundreds of mechanical

154

Infrastructure and Operations | National Nuclear Security Administration  

National Nuclear Security Administration (NNSA)

Operations | National Nuclear Security Administration Operations | National Nuclear Security Administration Our Mission Managing the Stockpile Preventing Proliferation Powering the Nuclear Navy Emergency Response Recapitalizing Our Infrastructure Continuing Management Reform Countering Nuclear Terrorism About Us Our Programs Our History Who We Are Our Leadership Our Locations Budget Our Operations Media Room Congressional Testimony Fact Sheets Newsletters Press Releases Speeches Events Social Media Video Gallery Photo Gallery NNSA Archive Federal Employment Apply for Our Jobs Our Jobs Working at NNSA Blog Infrastructure and Operations Home > About Us > Our Operations > Infrastructure and Operations Infrastructure and Operations NNSA's missions require a secure production and laboratory infrastructure meeting immediate and long term needs. The Associate Administrator for

155

Operations Authorization Assessment Plan | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Operations Authorization Assessment Plan Operations Authorization Assessment Plan Operations Authorization Assessment Plan Performance Objective: The objective of this assessment is to verify there is documentation in place which accurately describes the safety envelope for a facility, program or project. Criteria: Conditions and requirements should be established to ensure programs addressing all applicable functional areas are adequately implemented to support safe performance of the work. The extent of documentation and level of authority for agreement shall be tailored to the complexity and hazards associated with the work. Personnel shall be responsible and accountable for performance of work in accordance with the controls established. Operations-Authorization.doc More Documents & Publications

156

Extracting work from quantum systems  

E-Print Network (OSTI)

We consider the task of extracting work from quantum systems in the resource theory perspective of thermodynamics, where free states are arbitrary thermal states, and allowed operations are energy conserving unitary transformations. Taking as our work storage system a 'weight' we prove the second law and then present simple protocols which extract average work equal to the free energy change of the system - the same amount as in classical thermodynamics. Crucially, for systems in 'classical' states (mixtures of energy eigenstates) our protocol works on a single copy of the system. This is in sharp contrast to previous results, which showed that in case of almost-deterministic work extraction, collective actions on multiple copies are necessary to extract the free energy. This establishes the fact that free energy is a meaningful notion even for individual systems in classical states. However, for non-classical states, where coherences between energy levels exist, we prove that collective actions are necessary, so long as no external sources of coherence are used.

Paul Skrzypczyk; Anthony J. Short; Sandu Popescu

2013-02-12T23:59:59.000Z

157

http://bellview/TeamWorks/TRUTeamWorks.htm  

NLE Websites -- All DOE Office Websites (Extended Search)

9/04 9/04 Shipments expected this week: NTS (2), RFETS (13), SRS (6) January 29, 2004 The Big Story WTS restructures workforce Topics Characterization News Transportation News Disposal News Safety News Working Smart Announcements Our Team Tools Acronym List Archives Back to Main Page WIPP Home Page Links Feedback Contact us with feedback or submit your e-mail address for updates. Click here to e-mail. WIPP Shipments (as of 1/29/04 at 7:14 a.m.) Shipments scheduled to arrive at WIPP this week 21 Total shipments received at WIPP 2,309 Earlier this week WTS, the management and operating contractor at WIPP, announced a workforce restructuring plan to meet the current and future operational needs of the WIPP facility. It is anticipated

158

Electrical Safe Work Practices  

NLE Websites -- All DOE Office Websites (Extended Search)

Electrical Safe Work Practices Electrical Safe Work Practices July 15, 2005 NOTE: Working hot is a last alternative All activities on or near electrically energized systems having live parts shall be conducted in accordance with the limitations and procedures specified in the latest version of NFPA 70E and with the safe work practices and conditions that follow. Only qualified personnel {as defined in NFPA 70E Article 110.6(D)} as authorized by supervisor can perform such work. Safe Work Practices: Know the equipment and potential hazards - Define the scope of work. Submit the scope of work to your supervisor for approval. Analyze the hazards use engineered methods to mitigate hazards. Establish procedures as necessary. Use barricades or other means to prevent unqualified persons crossing approach boundaries.

159

Working Group 7 Summary  

SciTech Connect

The primary subject of working group 7 at the 2012 Advanced Accelerator Concepts Workshop was muon accelerators for a muon collider or neutrino factory. Additionally, this working group included topics that did not fit well into other working groups. Two subjects were discussed by more than one speaker: lattices to create a perfectly integrable nonlinear lattice, and a Penning trap to create antihydrogen.

Nagaitsev S.; Berg J.

2012-06-10T23:59:59.000Z

160

Live Working Resource Forum  

Science Conference Proceedings (OSTI)

This project involves development of a Live Working Resource Forum for documenting common and unique live work practices. It also serves as a repository of lessons learned derived from analysis of live work incidents. This Technical Update report is the design document of the Forum.

2006-12-14T23:59:59.000Z

Note: This page contains sample records for the topic "operation 1943-1944 working" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


161

http://bellview/TeamWorks/TRUTeamWorks.htm  

NLE Websites -- All DOE Office Websites (Extended Search)

A weekly e-newsletter for the Waste Isolation Pilot Plant team September 18, 2003 The Big Story Characterization Operations completed at ANL-E Topics Characterization News Transportation News Disposal News Safety News Working Smart Announcements Our Team Tools Acronym List Archives Back to Main Page WIPP Home Page Links Feedback Contact us with feedback or submit your e-mail address for updates. Click here to e-mail. WIPP Shipments (as of 9-18-03 at 7:17 a.m.) 21 Shipments scheduled to arrive at WIPP this week 2,020 Total shipments received at WIPP Months of dedication and teamwork have paid off for WIPP Central Characterization Project (CCP) employees working at Argonne National Laboratory - East (ANL-E). Characterization activities at the site have

162

TWRS Systems Engineering Working Plan  

SciTech Connect

The purpose of this Systems Engineering (SE) Working Plan (SEWP) is to describe how the Westinghouse Hanford Company (WHC) Tank Waste Remediation System (TWRS) will implement the SE polity and guidance provided in the Tank Waste Remediation System (TWRS) Systems Engineering Management Plan (SEMP). Sections 2.0 through 4.0 cover how the SE process and management will be performed to develop a technical baseline within TWRS. Section 5.0 covers the plans and schedules to implement the SE process and management within TWRS. Detailed information contained in the TWRS Program SEMP is not repeated in this document. This SEWP and the SE discipline defined within apply to the TWRS Program and new and ongoing TWRS projects or activities, including new facilities and safety. The SE process will be applied to the existing Tank Farm operations where the Richland TWRS Program Office management determines the process appropriate and where value will be added to existing Tank Farm system and operations.

Eiholzer, C.R.

1994-09-16T23:59:59.000Z

163

ORISE: Operations Support and Planning  

NLE Websites -- All DOE Office Websites (Extended Search)

Securing the Golden State Amber Waves 2012 Bureau of Reclamation Emergency Management Issues Special Interest Group Golden Guardian Joint Information Center Preventing Nuclear Smuggling Program Training and Technology Support Resources How to Work With Us Contact Us Oak Ridge Institute for Science Education Operations Support and Planning Operations Support and Planning The Oak Ridge Institute for Science and Education (ORISE) provides operations and planning support to the U.S. Department of Energy (DOE), Federal Emergency Management Agency and other government agencies for their counterterrorism and emergency response readiness programs. ORISE's planning, logistical and administrative support areas are focused on enhancing the radiological preparedness and response coordination

164

Fermilab | Office of Partnerships and Technology Transfer | Work ...  

Identify In-house Project Support 3 : Draft Statement of Work (SOW) with milestones : 4: Submit WFO information to DOE Operations Office;

165

Transportation External Coordination Working Group:  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Study of Study of DOE FY03 SNF Shipments Judith Holm National Transportation Program Albuquerque, New Mexico April 21, 2004 Background Benchmarking * The goal of benchmarking is to identify, understand, and adapt outstanding practices from organizations anywhere in the world to help your organization improve its performance * Benchmarking looks outward to find best practice and high performance and then measures actual business operations against those goals Background Best Practices * Best practices are proven solutions that represent superior performance when adapted and implemented in one's own organization. This includes processes and procedures that others are using to transport radioactive materials Background Lessons Learned * Lessons learned are "good work practices" or

166

Climate Data Operators (CDO)  

NLE Websites -- All DOE Office Websites (Extended Search)

Climate Climate Data Operators (CDO) Climate Data Operators (CDO) Description and Overview CDO is a large tool set for working on climate data. NetCDF 3/4, GRIB including SZIP compression, EXTRA, SERVICE and IEG are supported as IO-formats. Apart from that cdo can be used to analyse any kind gridded data not related to climate science. CDO has very small memory requirements and can process files larger than the physical memory. How to Use CDO module load cdo cdo [Options] Operators ... Further Information CDO Online Documentation Availability Package Platform Category Version Module Install Date Date Made Default cdo carver libraries/ I/O 1.4.1 cdo/1.4.1 2012-01-13 2012-01-13 cdo carver libraries/ I/O 1.4.6 cdo/1.4.6 2012-05-24 2012-05-25 cdo carver libraries/ I/O 1.6.1 cdo/1.6.1 2013-07-02

167

Office of Business Operations  

NLE Websites -- All DOE Office Websites (Extended Search)

Operations HSS Logo Office of Business Operations Reports to the Office of Resource Management Director's Message Welcome to the Office of Business Operations Richard D....

168

Operations Strategic Plan  

NLE Websites -- All DOE Office Websites (Extended Search)

Operations Strategic Plan Updated July 2009 Operations Organization Chief Operating Officer (COO) Deputy COO Environment, Health & Safety EH&S Facilities FAC Project Management...

169

Available work in geothermal energy  

DOE Green Energy (OSTI)

The most important thermodynamic considerations needed for a clear understanding of the operation of geothermal installations used for the production of electricity are presented. A brief description is given of the nature of a geothermal reservoir and the characteristics of the most practical systems for the conversion of geothermal energy into work are described. The appropriate specialized forms of the First and Second Laws of Thermodynamics are derived and the related concepts of optimum available work, available work, entropy production, dissipated energy, and utilization factor are introduced. The shortcomings of the method of cycle analysis are discussed when applied to geothermal plants. Special attention is devoted to a detailed discussion of the most important general indicators that follow for the designer from a thermodynamic analysis. Various methods of graphically interpreting the concept of available work are described in detail and the importance of easily accessible, reliable formulations of the thermophysical properties of the pure substances, solutions, and mixtures that the designer needs for success are discussed. (MHR)

Kestin, J.

1978-07-01T23:59:59.000Z

170

Nuclear Maintenance Applications Center: Maintenance Work Package Planning Guidance  

Science Conference Proceedings (OSTI)

The work management process is one of the core business processes outlined within the Nuclear Energy Institute (NEI) Standard Nuclear Performance Model for operation and maintenance of nuclear power plants. The preparation of work packages is a key element of this overall process. The purpose of this report is to provide guidance to power plant personnel regarding work package quality as a supplement to Institute of Nuclear Power Operations (INPO) AP-928, Work Management Process Description. The ...

2013-09-10T23:59:59.000Z

171

Work/Life Balance  

NLE Websites -- All DOE Office Websites (Extended Search)

Work/Life Balance Work/Life Balance /careers/_assets/images/careers-icon.jpg Work/Life Balance Explore the multiple dimensions of a career at LANL: work with the best minds on the planet in an inclusive environment that is rich in intellectual vitality and opportunities for growth. What our employees say: Health & Wellness "The Lab pays 80 percent of my family's medical premiums with Blue Cross Blue Shield of New Mexico." Retirement & Savings "With the Lab matching my 401K contributions of six percent, I'm making good progress in saving for my retirement." Time Off "Like many of my colleagues here, I work nine hours on most work days so that I can take every other Friday off." Tax Savings "My flexible spending accounts allow me to set aside pre-tax dollars for

172

Working with Interpreters | National Nuclear Security Administration  

National Nuclear Security Administration (NNSA)

Working with Interpreters | National Nuclear Security Administration Working with Interpreters | National Nuclear Security Administration Our Mission Managing the Stockpile Preventing Proliferation Powering the Nuclear Navy Emergency Response Recapitalizing Our Infrastructure Continuing Management Reform Countering Nuclear Terrorism About Us Our Programs Our History Who We Are Our Leadership Our Locations Budget Our Operations Media Room Congressional Testimony Fact Sheets Newsletters Press Releases Speeches Events Social Media Video Gallery Photo Gallery NNSA Archive Federal Employment Apply for Our Jobs Our Jobs Working at NNSA Blog The National Nuclear Security Administration Working with Interpreters Home > About Us > Our Programs > Defense Programs > Future Science & Technology Programs > Office of Advanced Simulation and Computing and

173

EPRI Live Working Project  

Science Conference Proceedings (OSTI)

The Electric Power Research Institute (EPRI) has been conducting research in the area of live working for several decades. This research has resulted in a large number of reports and other products. To help users locate the results of EPRIs research in live working, an annual update is prepared containing brief descriptions of the products.BackgroundLive workthe performance of maintenance, construction, or testing on equipment and circuits that ...

2012-09-06T23:59:59.000Z

174

Hot Working I - TMS  

Science Conference Proceedings (OSTI)

The conversion of ingot structure to fine equiaxed wrought structure will be ... Special methods to breakdown the difficult-to-work titanium aluminide alloys will ...

175

tchr_work_template  

NLE Websites -- All DOE Office Websites (Extended Search)

are identified and prepared in advance. f. teachers receive advance communication about program logistics. 4. The Teacher's Work Experience a. relates to the scientific and...

176

Aggregation operators for fuzzy ontologies  

Science Conference Proceedings (OSTI)

Fuzzy ontologies extend classical ontologies to allow the representation of imprecise and vague knowledge. Although a relatively important amount of work has been carried out in the field during the last years and they have been successfully used in ... Keywords: Aggregation operators, Fuzzy Description Logics, Fuzzy integrals, Fuzzy ontologies, Logic for the Semantic Web

Fernando Bobillo, Umberto Straccia

2013-09-01T23:59:59.000Z

177

Emergency Operations Training Academy | National Nuclear Security  

National Nuclear Security Administration (NNSA)

Operations Training Academy | National Nuclear Security Operations Training Academy | National Nuclear Security Administration Our Mission Managing the Stockpile Preventing Proliferation Powering the Nuclear Navy Emergency Response Recapitalizing Our Infrastructure Continuing Management Reform Countering Nuclear Terrorism About Us Our Programs Our History Who We Are Our Leadership Our Locations Budget Our Operations Media Room Congressional Testimony Fact Sheets Newsletters Press Releases Speeches Events Social Media Video Gallery Photo Gallery NNSA Archive Federal Employment Apply for Our Jobs Our Jobs Working at NNSA Blog Emergency Operations Training Academy Home > About Us > Our Programs > Emergency Response > Training > Emergency Operations Training Academy Emergency Operations Training Academy Rotating image showing pictures of Classroom, Online and Hands on trainings

178

Operations Directorate (OPS Directorate)  

NLE Websites -- All DOE Office Websites (Extended Search)

Operations Directorate (OPS Directorate) Operations Directorate (OPS Directorate) Purpose A group chartered by the Associate Laboratory Director for the Advanced Photon Source that includes the responsible Division Directors and other appropriate APS operations personnel. The Operations Directorate collectively coordinates operating decisions that affect the facility as a whole and establishes both long- and short-term schedules, including scheduled maintenance and facility improvement periods. The Operations Directorate is the APS forum in which decisions regarding operations are discussed: These include, but are not limited to: Safety issues related to operations Operational Schedule Global operating parameters within the defined and approved operational and safety envelopes, such as energy, maximum circulating beam

179

WIPP AT WORK | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

AT WORK AT WORK WIPP AT WORK February 1, 2010 - 12:00pm Addthis Carlsbad, NM - Transuranic (TRU) waste cleanup efforts are underway across the DOE complex, as the Waste Isolation Pilot Plant (WIPP) wraps up its 11th year of disposal operations. The Carlsbad Field Office (CBFO) manages the DOE's National TRU Program (NTP) Office and WIPP facility operations. TRU waste temporarily stored at DOE generator sites around the country is shipped to WIPP and disposed in rooms mined out of an ancient salt formation 2,150 feet below the surface. WIPP, which began waste disposal operations in 1999, is located 26 miles outside of Carlsbad, New Mexico. Over the last year, CBFO has successfully completed two major remote-handled (RH) TRU waste shipping campaigns and continues efforts to

180

WIPP AT WORK | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

WIPP AT WORK WIPP AT WORK WIPP AT WORK February 1, 2010 - 12:00pm Addthis Carlsbad, NM - Transuranic (TRU) waste cleanup efforts are underway across the DOE complex, as the Waste Isolation Pilot Plant (WIPP) wraps up its 11th year of disposal operations. The Carlsbad Field Office (CBFO) manages the DOE's National TRU Program (NTP) Office and WIPP facility operations. TRU waste temporarily stored at DOE generator sites around the country is shipped to WIPP and disposed in rooms mined out of an ancient salt formation 2,150 feet below the surface. WIPP, which began waste disposal operations in 1999, is located 26 miles outside of Carlsbad, New Mexico. Over the last year, CBFO has successfully completed two major remote-handled (RH) TRU waste shipping campaigns and continues efforts to

Note: This page contains sample records for the topic "operation 1943-1944 working" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


181

STATEMENT OF WORK  

National Nuclear Security Administration (NNSA)

PART III - SECTION J APPENDIX B STATEMENT OF WORK Table of Contents 1.0 General.................................................................................................................... 273 2.0 Laboratory Mission and Scope of Work. ................................................................ 274 3.0 Science & Technology. ........................................................................................... 275 3.1 Defense Programs. .................................................................................................. 276 3.1.1 Stewardship of United States Nuclear Weapons. ................................................ 276 3.1.1.1 Stockpile Certification. .......................................................................................

182

Making Microgrids Work  

Science Conference Proceedings (OSTI)

Distributed energy resources including distributed generation and distributed storage are sources of energy located near local loads and can provide a variety of benefits including improved reliability if they are properly operated in the electrical distribution system. Microgrids are systems that have at least one distributed energy resource and associated loads and can form intentional islands in the electrical distribution systems. This paper gives an overview of the microgrid operation. Microgrid testing experiences from different counties was also provided.

Kroposki, B.; Lasseter, R.; Ise, T.; Morozumi, S.; Papathanassiou, S.; Hatziargyriou, N.

2008-05-01T23:59:59.000Z

183

Trails Working Group  

NLE Websites -- All DOE Office Websites (Extended Search)

Trails Working Group Trails Working Group Trails Working Group Our mission is to inventory, map, and prepare historical reports on the many trails used at LANL. Contact Environmental Communication & Public Involvement P.O. Box 1663 MS M996 Los Alamos, NM 87545 (505) 667-0216 Email The LANL Trails Working Group inventories, maps, and prepares historical reports on the many trails used at LANL. Some of these trails are ancient pueblo footpaths that continue to be used for recreational hiking today. Some serve as quiet and non-motorized alternatives between the Townsite and LANL or between technical areas. The Trails Working Group, established in December 2003, includes representatives from local citizen hiking groups, Los Alamos County, Forest Service, Park Service, Los Alamos National Laboratory and the NNSA Los

184

Interagency Working Groups (IWGs)  

NLE Websites -- All DOE Office Websites (Extended Search)

Interagency Working Groups (IWGs) Print E-mail Interagency Working Groups (IWGs) Print E-mail Interagency Working Groups (IWGs) are the primary USGCRP vehicles for implementing and coordinating research activities within and across agencies. These groups are critical to Program integration and in assessing the Program's progress. The working groups span a wide range of interconnected issues of climate and global change, and address major components of the Earth's environmental and human systems, as well as cross-disciplinary approaches for addressing these issues. IWGs correspond to program functions and are designed to bring agencies together to plan and develop coordinated activities, implement joint activities, and identify and fill gaps in the Program's plans. They allow public officials to communicate with each other on emerging directions within their agencies, on their stakeholder needs, and on best practices learned from agency activities. Together, these functions allow the agencies to work in a more coordinated and effective manner.

185

ORISE: Working with ORISE  

NLE Websites -- All DOE Office Websites (Extended Search)

Oak Ridge Institute for Science Education Oak Ridge Institute for Science Education Working with ORISE If you are interested in learning about how your agency can utilize the capabilities of the Oak Ridge Institute for Science and Education (ORISE) through a Work for Others agreement or a procurement contract, or if you are looking for career opportunities, the following information provides an explanation of how to work with ORISE. If you do not see an option that applies to your needs, please contact ORISE General Information. Work for Others For organizations and agencies that are not affiliated with U.S. Department of Energy (DOE), such groups still have the opportunity to partner with the Oak Ridge Institute for Science and Education (ORISE) through the DOE Work For Others (WFO) program. DOE's WFO program allows ORISE to support

186

Live Work on High Temperature Conductors  

Science Conference Proceedings (OSTI)

Feedback from field personnel working with high-temperature conductors indicates that when a dead-end compression yoke assembly (DCYA) is installed on the conductor according to normal utility procedures, the soft aluminum strands are deformed and "birdcage." This is of course a concern to the field crews and the utility operating the line. This report presents results of research and tests performed on selected conductors operating at high temperature (approximately 250-260C) with selected live wor...

2011-12-13T23:59:59.000Z

187

ICDF Complex Remedial Action Work Plan  

SciTech Connect

This Remedial Action Work Plan provides the framework for operation of the Idaho Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) Disposal Facility Complex (ICDF). This facility includes (a) an engineered landfill that meets the substantial requirements of DOE Order 435.1, Resource Conservation and Recovery Act Subtitle C, Idaho Hazardous Waste Management Act, and Toxic Substances Control Act polychlorinated biphenyl landfill requirements; (b) centralized receiving, inspections, administration, storage/staging, and treatment facilities necessary for CERCLA investigation-derived, remedial, and removal waste at the Idaho National Laboratory (INL) prior to final disposition in the disposal facility or shipment off-Site; and (c) an evaporation pond that has been designated as a corrective action management unit. The ICDF Complex, including a buffer zone, will cover approximately 40 acres, with a landfill disposal capacity of approximately 510,000 yd3. The ICDF Complex is designed and authorized to accept INL CERCLA-generated wastes, and includes the necessary subsystems and support facilities to provide a complete waste management system. This Remedial Action Work Plan presents the operational approach and requirements for the various components that are part of the ICDF Complex. Summaries of the remedial action work elements are presented herein, with supporting information and documents provided as appendixes to this work plan that contain specific detail about the operation of the ICDF Complex. This document presents the planned operational process based upon an evaluation of the remedial action requirements set forth in the Operable Unit 3-13 Final Record of Decision.

W. M. Heileson

2006-12-01T23:59:59.000Z

188

Peak Underground Working Natural Gas Storage Capacity  

Gasoline and Diesel Fuel Update (EIA)

Definitions Definitions Definitions Since 2006, EIA has reported two measures of aggregate capacity, one based on demonstrated peak working gas storage, the other on working gas design capacity. Demonstrated Peak Working Gas Capacity: This measure sums the highest storage inventory level of working gas observed in each facility over the 5-year range from May 2005 to April 2010, as reported by the operator on the Form EIA-191M, "Monthly Underground Gas Storage Report." This data-driven estimate reflects actual operator experience. However, the timing for peaks for different fields need not coincide. Also, actual available maximum capacity for any storage facility may exceed its reported maximum storage level over the last 5 years, and is virtually certain to do so in the case of newly commissioned or expanded facilities. Therefore, this measure provides a conservative indicator of capacity that may understate the amount that can actually be stored.

189

HQ Work Control Permit | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

HQ Work Control Permit HQ Work Control Permit HQ Work Control Permit To ensure safe operations when undertaking work at DOE Headquarters, the Office of Headquarters Health and Safety has developed a Work Permit document (doc) to help ensure the safety of all workers and headquarters employees. The form should be completed and brought to the Office of Headquarters Safety, Health and Security office at GE-112 at the Forrestal facility, or the Germantown Building Manager's office at E-076 for review and sign off. Any questions can be directed to the HQ Health and Safety office on (202) 586-1005. HQ_Work_Control_Permit.docx More Documents & Publications Preliminary Notice of Violation, Petsco and Son, Inc - EA-96-06 OSS 19.10 Barriers and Postings 5/26/95 OSS 19.3 Confined Space Entry 5/23/95

190

HQ Work Control Permit | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

HQ Work Control Permit HQ Work Control Permit HQ Work Control Permit To ensure safe operations when undertaking work at DOE Headquarters, the Office of Headquarters Health and Safety has developed a Work Permit document (doc) to help ensure the safety of all workers and headquarters employees. The form should be completed and brought to the Office of Headquarters Safety, Health and Security office at GE-112 at the Forrestal facility, or the Germantown Building Manager's office at E-076 for review and sign off. Any questions can be directed to the HQ Health and Safety office on (202) 586-1005. HQ_Work_Control_Permit.docx More Documents & Publications Preliminary Notice of Violation, Petsco and Son, Inc - EA-96-06 OSS 19.3 Confined Space Entry 5/23/95 WA_02_026_UNITED_TECHNOLOGIES_Waiver_of_Domestic_and_Foreign

191

Work Authorization System  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Washington, D.C. DOE O 412.1A Approved: 4-21-05 This directive was reviewed and certified as current and necessary by Susan J. Grant, Director, Office of Management, Budget and Evaluation/Chief Financial Officer, 4-21-05. SUBJECT: WORK AUTHORIZATION SYSTEM 1. OBJECTIVES. To establish a work authorization and control process for work performed by designated site and facility management contractors, and other contractors as determined by the procurement executive, consistent with the budget execution and program evaluation requirements of the Department of Energy's (DOE's) Planning, Programming, Budgeting, and Evaluation process. 2. CANCELLATIONS. DOE O 412.1 Work Authorization System, dated 4-20-99. Cancellation of a directive does not, by itself, modify or otherwise affect any contractual

192

How Hybrids Work  

NLE Websites -- All DOE Office Websites (Extended Search)

How Hybrids Work How Hybrids Work Diagram of full hybrid vehicle components, including (1) an internal combustion engine, (2) an electric motor, (3) a generator, (4) a power split device, and (5) a high-capacity battery. Flash Animation: How Hybrids Work (Requires Flash 6.0 or higher) HTML Version: How Hybrids Work Hybrid-electric vehicles (HEVs) combine the benefits of gasoline engines and electric motors and can be configured to obtain different objectives, such as improved fuel economy, increased power, or additional auxiliary power for electronic devices and power tools. Some of the advanced technologies typically used by hybrids include Regenerative Braking. The electric motor applies resistance to the drivetrain causing the wheels to slow down. In return, the energy from the

193

Working, Living, and Belonging  

E-Print Network (OSTI)

and Belonging June 28, 2013 Noah D. Zatz, UCLA, and EileenUniversity Press, 1998). Noah D. Zatz, "Working at theUniversity Press, 2012); Noah D. Zatz, "The Impossibility of

Zatz, Noah; Boris, Eileen

2013-01-01T23:59:59.000Z

194

NREL: Working for NREL  

NLE Websites -- All DOE Office Websites (Extended Search)

Working for NREL Working for NREL We're always on the lookout for talented people who believe in our mission and support our values. NREL's inclusive work environment benefits from diversity throughout the organization, values individual differences, and encourages employees to develop and contribute to their full potential. Working for NREL is a challenging and exciting experience for nearly 2,300 staff members of all backgrounds. We offer competitive salaries and excellent benefits. NREL Mission While our cultures and creeds, and lifestyles and languages may differ, we share a common desire to carry out our mission- To develop renewable energy and energy efficiency technologies and practices, To advance related science and engineering, and To transfer knowledge and innovations to address the nation's energy

195

Use of organic working fluids in Rankine engines  

DOE Green Energy (OSTI)

A compilation is presented of state-of-the-art data on the use of organic working fluids in operational Rankine cycle engines. Particular attention is given to the determination of the maximum temperatures used for various working fluids in operational Rankine cycle engines and identification of thermal instability and chemical reaction problems related to these temperatures. Information is included on the characteristics and selection of working fluids; the behavior of lubricating oils in contact with working fluids; operational experience; and recommended organic fluids R and D. (LCL)

Curran, H M

1979-09-01T23:59:59.000Z

196

Uncertain generalized aggregation operators  

Science Conference Proceedings (OSTI)

The aim of this paper is to extend the generalized ordered weighted averaging operator and provide a new class of operators called the uncertain generalized ordered weighted averaging (UGOWA) operator. It provides a very general formulation that includes ... Keywords: Aggregation, Decision making, Generalized mean, OWA operator, Operator weights

Li-Gang Zhou; Hua-You Chen; Jos M. Merig; Anna M. Gil-Lafuente

2012-01-01T23:59:59.000Z

197

Hydrate Control for Gas Storage Operations  

Science Conference Proceedings (OSTI)

The overall objective of this project was to identify low cost hydrate control options to help mitigate and solve hydrate problems that occur in moderate and high pressure natural gas storage field operations. The study includes data on a number of flow configurations, fluids and control options that are common in natural gas storage field flow lines. The final phase of this work brings together data and experience from the hydrate flow test facility and multiple field and operator sources. It includes a compilation of basic information on operating conditions as well as candidate field separation options. Lastly the work is integrated with the work with the initial work to provide a comprehensive view of gas storage field hydrate control for field operations and storage field personnel.

Jeffrey Savidge

2008-10-31T23:59:59.000Z

198

Interview: LaborWorks@NeighborWorks Provides Vermont Contractors...  

NLE Websites -- All DOE Office Websites (Extended Search)

Focus Series LaborWorks@NeighborWorks Provides Vermont Contractors With Help When They Need It NeighborWorks of Western Vermont (NWWVT), a nonprofit home ownership organization...

199

Heat Transfer Operators Associated with Quantum Operations  

E-Print Network (OSTI)

Any quantum operation applied on a physical system is performed as a unitary transformation on a larger extended system. If the extension used is a heat bath in thermal equilibrium, the concomitant change in the state of the bath necessarily implies a heat exchange with it. The dependence of the average heat transferred to the bath on the initial state of the system can then be found from the expectation value of a hermitian operator, which is named as the heat transfer operator (HTO). The purpose of this article is the investigation of the relation between the HTOs and the associated quantum operations. Since, any given quantum operation on a system can be realized by different baths and unitaries, many different HTOs are possible for each quantum operation. On the other hand, there are also strong restrictions on the HTOs which arise from the unitarity of the transformations. The most important of these is the Landauer erasure principle. This article is concerned with the question of finding a complete set of restrictions on the HTOs that are associated with a given quantum operation. An answer to this question has been found only for a subset of quantum operations. For erasure operations, these characterizations are equivalent to the generalized Landauer erasure principle. For the case of generic quantum operations however, it appears that the HTOs obey further restrictions which cannot be obtained from the entropic restrictions of the generalized Landauer erasure principle.

. Aksak; S. Turgut

2010-02-03T23:59:59.000Z

200

Air Carrier Flight Operations  

E-Print Network (OSTI)

Most air carriers operate under a system of prioritized goals including safety, customer service (on-time departures and arrivals) and operating economics. The flight operations department is responsible for the safe and ...

Midkif, Alan H.

Note: This page contains sample records for the topic "operation 1943-1944 working" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


201

How Fuel Cells Work  

NLE Websites -- All DOE Office Websites (Extended Search)

How Fuel Cells Work How Fuel Cells Work Diagram: How a PEM fuel cell works. 1. Hydrogen fuel is channeled through field flow plates to the anode on one side of the fuel cell, while oxygen from the air is channeled to the cathode on the other side of the cell. 2. At the anode, a platinum catalyst causes the hydrogen to split into positive hydrogen ions (protons) and negatively charged electrons. 3. The Polymer Electrolyte Membrane (PEM) allows only the positively charged ions to pass through it to the cathode. The negatively charged electrons must travel along an external circuit to the cathode, creating an electrical current. 4. At the cathode, the electrons and positively charged hydrogen ions combine with oxygen to form water, which flows out of the cell.

202

ORISE: Work Smart Standards  

NLE Websites -- All DOE Office Websites (Extended Search)

Work Smart Standards Work Smart Standards ORISE Work Smart Standards Set for Environment, Safety, and Health Revision #1, March 21, 2000 Revision #2, Sept. 29, 2000 Revision #3, June 28, 2001 Revision #4, Nov. 9, 2001 Revision #5, Nov. 30, 2001 Revision #6, Jan. 31, 2002 Revision #7, June 28, 2002 Revision #8, Oct. 17, 2002 Revision #9, Nov. 21, 2002 Revision #10, Feb. 28, 2003 Revision #11, May 23, 2003 Revision #12, May 30, 2003 Revision #13, Oct. 30, 2003 Revision #14, Jan. 21, 2004 Revision #15, May 24, 2004 Revision #16, Aug. 17, 2004 Revision #17, Aug. 27, 2004 Revision #18, Oct. 14, 2004 Revision #19, March 28, 2005 Revision #20, May 31, 2005 Revision #21, Aug. 24, 2005 Revision #22, Feb. 17, 2006 Revision #23, March 22, 2006 Revision #24, May 19, 2006 Revision #25, July 26, 2006 Revision #26, Nov. 28, 2006

203

A conserved Parity Operator  

E-Print Network (OSTI)

The symmetry of Nature under a Space Inversion is described by a Parity operator. Contrary to popular belief, the Parity operator is not unique. The choice of the Parity operator requires several arbitrary decisions to be made. It is shown that alternative, equally plausible, choices leads to the definition of a Parity operator that is conserved by the Weak Interactions. The operator commonly known as CP is a more appropriate choice for a Parity operator.

Mark J Hadley

2004-06-24T23:59:59.000Z

204

Working with NIST  

NLE Websites -- All DOE Office Websites (Extended Search)

NIST NIST Terry Lynch Office of Technology Partnerships How to Work with NIST How to Work with NIST „ „ Standards Standards „ „ Collaborative Research & Technology Devolvement Collaborative Research & Technology Devolvement Programs Programs „ „ Invention Licensing Invention Licensing Collaborative Research & Technology Collaborative Research & Technology Development Programs Development Programs „ „ Informal collaboration involving intramural research programs Informal collaboration involving intramural research programs „ „ Guest Research Agreements Guest Research Agreements „ „ Facility Use Agreements Facility Use Agreements „ „ Material Transfer Agreements Material Transfer Agreements „ „ Cooperative Research and Development Agreements (CRADA

205

FY 1996 annual work plan  

SciTech Connect

In April 1994, the Department of Energy (DOE) Strategic Plan was issued. This Plan presents the Department`s strategic outlook in response to a changing world. It discusses the Department`s unique capabilities; its mission, vision, and core values; and key customer and stakeholder considerations. The DOE Strategic Plan lists business strategies and critical success factors which are intended to aid the Department in accomplishing its mission and reaching its vision of itself in the future. The Office of Inspector General (OIG) has an important role in carrying out the goals and objectives of the Secretary`s Strategic Plan. The ultimate goal of the OIG is to facilitate positive change by assisting its customers, responsible Government officials, in taking actions to improve programs and operations. The Inspector General annually issues his own Strategic Plan that contains program guidance for the next fiscal year. As part of its responsibility in carrying out the OIG mission, the Office of the Deputy Inspector General for Audit Services (Office of Audit Services) publishes an Annual Work Plan that sets forth audits that are planned for the next fiscal year. Selection of these audits is based on the overall budget of the Department, analyses of trends in Departmental operations, guidance contained in the agency`s strategic plans, statutory requirements, and the expressed needs and audit suggestions of Departmental program managers and OIG managers and staff. This work plan includes audits that are carried over from FY 1995 and audits scheduled to start during FY 1996. Audits included in the plan will be performed by OIG staff.

1995-09-30T23:59:59.000Z

206

Operating Experience Summaries  

NLE Websites -- All DOE Office Websites (Extended Search)

Operating Experience Summaries The Office of Health, Safety and Security (HSS) Office of Analysis publishes the Operating Experience Summary to exchange lessons-learned information...

207

ARM - NSA Operations  

NLE Websites -- All DOE Office Websites (Extended Search)

Images Information for Guest Scientists Contacts NSA Operations Barrow Facility Instrumentation at the Barrow facility operates 7 days a week, 24 hours a day, year around. The...

208

Provincial Operating Standards (Ontario) | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Provincial Operating Standards (Ontario) Provincial Operating Standards (Ontario) Provincial Operating Standards (Ontario) < Back Eligibility Construction Developer Fuel Distributor Industrial Installer/Contractor Investor-Owned Utility Municipal/Public Utility Utility Program Info Start Date 1/24/2002 State Ontario Program Type Environmental Regulations Fees Safety and Operational Guidelines Siting and Permitting Provider Ontario Ministry of Natural Resources The Provincial Operating Standards set the technical minimum requirements for cover wells and works regulated under the Oil, Gas and Salt Resources Act. These standards are the minimum requirements for the design, installation, operation, abandonment and safety of wells and works, but are not intended for use as a design handbook. In addition, the Standards outline the permitting process for injection

209

Working at NNSA | National Nuclear Security Administration  

National Nuclear Security Administration (NNSA)

at NNSA | National Nuclear Security Administration at NNSA | National Nuclear Security Administration Our Mission Managing the Stockpile Preventing Proliferation Powering the Nuclear Navy Emergency Response Recapitalizing Our Infrastructure Continuing Management Reform Countering Nuclear Terrorism About Us Our Programs Our History Who We Are Our Leadership Our Locations Budget Our Operations Media Room Congressional Testimony Fact Sheets Newsletters Press Releases Speeches Events Social Media Video Gallery Photo Gallery NNSA Archive Federal Employment Apply for Our Jobs Our Jobs Working at NNSA Blog The National Nuclear Security Administration Working at NNSA Home > Federal Employment > Working at NNSA Working at NNSA The work at NNSA will challenge you. You may take on significant responsibility quickly, and you will always be engaged in some of the most

210

Working at NNSA | National Nuclear Security Administration  

NLE Websites -- All DOE Office Websites (Extended Search)

at NNSA | National Nuclear Security Administration at NNSA | National Nuclear Security Administration Our Mission Managing the Stockpile Preventing Proliferation Powering the Nuclear Navy Emergency Response Recapitalizing Our Infrastructure Continuing Management Reform Countering Nuclear Terrorism About Us Our Programs Our History Who We Are Our Leadership Our Locations Budget Our Operations Media Room Congressional Testimony Fact Sheets Newsletters Press Releases Speeches Events Social Media Video Gallery Photo Gallery NNSA Archive Federal Employment Apply for Our Jobs Our Jobs Working at NNSA Blog The National Nuclear Security Administration Working at NNSA Home > Federal Employment > Working at NNSA Working at NNSA The work at NNSA will challenge you. You may take on significant responsibility quickly, and you will always be engaged in some of the most

211

Accumulated waste characterization work plan  

Science Conference Proceedings (OSTI)

The Portsmouth Gaseous Diffusion Plant (PORTS) as part of the uranium enrichment complex produces enriched uranium for power generation and defense purposes. Since the beginning of diffusion plant operations in 1953, a variety of waste materials and excess equipment has been generated through both normal operations and as part of major system upgrade programs. However, as a result of the closure of former onsite radioactive management facilities and limited onsite and offsite disposal facilities for mixed (hazardous and radioactive) wastes, PORTS has accumulated large quantities of waste awaiting final disposition. These accumulated wastes were estimated in the Accumulated Waste Plan (AWP) to consist of some 21,700 containers of the radioactive, RCRA hazardous, PCB, mixed and asbestos wastes in various storage areas and process buildings with PORTS. In order to proper manage these wastes onsite and prepare for them for ultimate treatment or disposal, a detailed understanding of the waste contents and characteristics must be developed. The strategy for managing and disposing of these wastes was outlined in the AWP. The purpose of this Accumulated Waste Characterization Work Plan (AWCWP) is to provide a detailed plan for characterizing waste containers from the existing PORTS inventory. The AWCWP documents the process and analytical information currently available and describes statistically-based sampling and analyses required to support proper regulatory classification.

Not Available

1992-01-01T23:59:59.000Z

212

METHOD OF WORKING BERYLLIUM  

DOE Patents (OSTI)

>A process is presented for fabricating beryllium metal. The billet cf beryllium metal is sheathed with a jacket of either copper or stainless steel. It may then be worked by drawing or the like at a tcmperature of 300 to 400 C.

Macherey, R.E.

1959-02-01T23:59:59.000Z

213

Work Package Templates  

Science Conference Proceedings (OSTI)

Work Package Templates provides fossil plant maintenance personnel with assorted inspection, minor repair or overhaul templates for various pieces of plant equipment. This guide will assist plant maintenance personnel in improving the efficiency, reliability and reducing the maintenance costs for associated with maintenance on selected pieces of equipment.

2007-02-15T23:59:59.000Z

214

Interagency Sustainability Working Group | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Program Areas » Sustainable Buildings & Campuses » Interagency Program Areas » Sustainable Buildings & Campuses » Interagency Sustainability Working Group Interagency Sustainability Working Group October 4, 2013 - 5:00pm Addthis The Interagency Sustainability Working Group (ISWG) is the coordinating body for sustainable buildings in the Federal Government. The ISWG: Serves as a forum for information exchange and promotes agency implementation of goals for high-performance and sustainable buildings Develops policy and reporting guidance that fosters the widespread adoption of sustainable design and operations in the Federal sector Develops technical guidance and tools to support implementation of agency sustainability policies for Federally owned, operated, and leased buildings. The ISWG is also charged with providing assistance for implementing the

215

D and D Operational Experience  

SciTech Connect

This paper describes the operational experience gained from more than 25 million man-hours of Decontamination and Decommissioning (D and D) work on both Department of Energy sites and commercial nuclear facilities in the United States. Nuclear D and D activities encompass some of the most hazardous activities imaginable - protecting workers from a huge range and endless combinations of industrial safety, radiological, nuclear safety, and industrial hygiene issues which challenges managers and safety professionals. Performing D and D activities safely is essential to project success. Managers must ensure that work is properly planned and executed, that hazards are identified and mitigated, and that operational experience is captured and utilized on future projects. Many of the lessons learned directly relate to the principles of behavioral-based safety. Our experience indicates that improved safety performance leads to improved productivity. (authors)

Meyer, K.A.; Smith, C.B. [BNG America, 9781 S. Meridian Blvd., Suite 100, Englewood, CO 80112 (United States)

2006-07-01T23:59:59.000Z

216

Operator pencil passing through a given operator  

E-Print Network (OSTI)

Let $\\Delta$ be a linear differential operator acting on the space of densities of a given weight $\\lo$ on a manifold $M$. One can consider a pencil of operators $\\hPi(\\Delta)=\\{\\Delta_\\l\\}$ passing through the operator $\\Delta$ such that any $\\Delta_\\l$ is a linear differential operator acting on densities of weight $\\l$. This pencil can be identified with a linear differential operator $\\hD$ acting on the algebra of densities of all weights. The existence of an invariant scalar product in the algebra of densities implies a natural decomposition of operators, i.e. pencils of self-adjoint and anti-self-adjoint operators. We study lifting maps that are on one hand equivariant with respect to divergenceless vector fields, and, on the other hand, with values in self-adjoint or anti-self-adjoint operators. In particular we analyze the relation between these two concepts, and apply it to the study of $\\diff(M)$-equivariant liftings. Finally we briefly consider the case of liftings equivariant with respect to the algebra of projective transformations and describe all regular self-adjoint and anti-self-adjoint liftings.

A. Biggs; H. M. Khudaverdian

2013-01-28T23:59:59.000Z

217

Public Works Transportation Infrastructure Study  

E-Print Network (OSTI)

Public Works Transportation Infrastructure Study Minneapolis City of Lakes Minneapolis Public Works Transportation Infrastructure Study #12;Public Works Transportation Infrastructure Study Minneapolis City Works Transportation Infrastructure Study Minneapolis City of Lakes Background: · Currently, funding

Minnesota, University of

218

NIST: Methane Symmetry Operations  

Science Conference Proceedings (OSTI)

*. Bookmark and Share. Version History Methane Symmetry Operations. JT Hougen Optical Technology Division Gloria Wiersma ...

2010-10-05T23:59:59.000Z

219

Working With Berkeley Lab  

NLE Websites -- All DOE Office Websites (Extended Search)

Working with the Lab Working with the Lab A-Z Index Search Phone Book Comments Ernest Orlando Lawrence Berkeley National Laboratory Technology Transfer Patent Department Sponsored Projects Office Procurement: Doing Business with the Lab Visitor Information Scientififc Divisions and National User Facilities UC Campus-Labs Collaboration Programs Berkeley Lab stresses collaboration in everything we do. The Laboratory is involved in many research partnerships with private industry. Our mission also includes the transfer of Laboratory inventions to the private sector for rapid commercialization. The role of the Technology Transfer Office is to make technology and expertise developed here available to industry. Contact the Technology Transfer Office to pinpoint research areas of common interest, negotiate rights to Laboratory intellectual property, and to discuss current patent and copyright licensing opportunities.

220

Working Group Reports  

NLE Websites -- All DOE Office Websites (Extended Search)

5 5 Working Group Reports Special Working Session on the Role of Buoy Observations in the Tropical Western Pacific Measurement Scheme J. Downing Marine Sciences Laboratory Sequim, Washington R. M. Reynolds Brookhaven National Laboratory Upton, New York Attending W. Clements (TWPPO) F. Barnes (TWPPO) T. Ackerman (TWP Site Scientist) M. Ivey (ARCS Manager) H. Church J. Curry J. del Corral B. DeRoos S. Kinne J. Mather J. Michalsky M. Miller P. Minnett B. Porch J. Sheaffer P. Webster M. Wesely K. Zorika G. Zhang Focus of Discussion The session convened on March 2, with brief introductions by Bill Clements. The purpose of the session was to discuss the scientific merits of retrofitting TOGA/TAO buoys with shortwave radiometers. Three questions were posed at the outset of the session to focus the discussion.

Note: This page contains sample records for the topic "operation 1943-1944 working" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


221

ARM - SGP Operations  

NLE Websites -- All DOE Office Websites (Extended Search)

Operations Operations SGP Related Links Facilities and Instruments Central Facility Boundary Facility Extended Facility Intermediate Facility Radiometric Calibration Facility Geographic Information ES&H Guidance Statement Operations Science Field Campaigns Visiting the Site Fact Sheet Images Information for Guest Scientists Contacts SGP Operations Routine Operations SGP central facility offices. SGP central facility offices. The overwhelming majority of the measurements with the highest priority, on which the existing experimental designs are based, are regular routine observations, as specified in the ARM Program Plan, 1990 (U.S. Department of Energy 1990). Scientifically and logistically, routine operations also serve as the basis and background for all nonroutine operations, including

222

CHA Guidelines Working Group  

E-Print Network (OSTI)

The Community Health Assessment Guidelines have been updated from the original document published in 1997. The revisions reflect various published sources, as well as accumulated experience with community health assessment within the province of Manitoba. Special thanks to the members of the CHA Guidelines Working Group, composed of representatives of regional health authorities from across the province and Manitoba Health and Healthy Living staff. These guidelines are made

Jody Allan; Sonia Busca Owczar; Ingrid Botting; Maggie Campbell; Bunmi Fatoye; Bill Funk; Tannis Erickson; Sue Lockhart; Ales Morga; Deborah Malazdrewicz; Leonie Stranc

2009-01-01T23:59:59.000Z

223

BOGlanl.working.indd  

NLE Websites -- All DOE Office Websites (Extended Search)

Delivering Excellence in Delivering Excellence in National Security Science 2010 Board of Governors Annual Report Los Alamos National Security, LLC Los Alamos National Laboratory is operated by Los Alamos National Security, LLC for DOE's National Nuclear Security Administration LANS BOARD OF GOVERNORS ANNUAL REPORT FY10 Significant Accomplishments ----------- 4 Targeted Investing for the Future ------------ 5 Creating Our Future ----------------- 6 Enabling Our Mission ----------------12 Outreach and Community Commitment ---------13 2010 LANS Board of Governors ------------14 Contents Front cover In FY10, the Laboratory's Dual Axis Radiographic Hydrodynamic Test (DARHT) facility completed four successful two axis, multi-frame hydrodynamic tests. Here, Terry Priestley inspects components on

224

BNL | Center for Functional Nanomaterials Hours of Operation  

NLE Websites -- All DOE Office Websites (Extended Search)

CFN Hours of Operation CFN Hours of Operation Normal working hours at the CFN are 8 a.m. to 6 p.m. Working Outside of Normal Hours CFN scientific and technical personnel, as well as external users, may need to work outside of normal operating hours, during which time support is limited and many colleagues may not be around. Therefore, working outside the 8 a.m. to 6 p.m. envelope on weekdays, or anytime on weekends and holidays, requires special precautions, especially if working in a laboratory. CFN users are expected to work at the CFN during normal working hours. Users with extensive experience working at the CFN may be granted permission by the appropriate facility leader and ES&H Coordinator to work after hours. Users first must complete the Request to Work After-Hours at

225

Operations | Argonne National Laboratory  

NLE Websites -- All DOE Office Websites (Extended Search)

Quality of Work Life brochure Read more about Quality of Work Life brochure CELS Diversity & Inclusion Action Plan Computing, Environment & Life Sciences Diversity & Inclusion...

226

Operating Efficiency Comes From Teamwork  

E-Print Network (OSTI)

A group of operating and planning personnel formed the INter Plant Utilities Team [INPUT] to improve energy efficiency and reliability for Exxon's Baytown, Texas, refinery and chemical plants complex. The Team coordinates the day-to-day operations of the Site's utilities generation and distribution systems, which cross the operating boundaries of all three of the plants in the complex, and supports both capital improvements and long-term energy optimization projects for those systems. INPUTs origins go back to the early 1980's, when a utility coordination team was organized to manage the interplay of the Site's several high-level steam systems, and to reduce the impact of occasional steam shortages on the operations of both Refinery and Chemical Plant. Three years ago the current team was formed to find ways to make the systems more efficient and reliable, and to pave the way for the Site's cogeneration expansion. INPUT provides a regular forum for surfacing and resolving issues that affect the economics and reliability of the Site's utility systems, and is a commitment on the part of the three Plants at the Site to work together for the overall benefit of the Site --a commitment worth over $5,000,000 annually in operating cost savings.

Relyea, D. L.; Stone, A.

1997-04-01T23:59:59.000Z

227

Putting Science to Work  

NLE Websites -- All DOE Office Websites (Extended Search)

(continued on page 4) (continued on page 4) ORNL Technology Transfer & Economic Development (TTED) seeks to foster economic development and the growth of business & industry by making available the most innovative equipment, the latest technology, and the expertise of ORNL researchers to technology-based companies throughout the nation. Building Synergy in a 'Deep Green' Community(tm) O ak Ridge National Laboratory researchers have been clamoring for years to prove and demon- strate the benefits of employing energy efficiency in residential buildings. Such high-performing, energy-efficient buildings tend to be more durable, comfortable, and desirable, and they use less energy and cost less to operate. They can help the environment and our nation, improving our energy security as well as the everyday lives of Americans.

228

Maintenance Work Package Planning Guidance for Fossil Power Plant Personnel  

Science Conference Proceedings (OSTI)

The work management process is one of the core business processes for operation and maintenance of fossil power plants. The preparation of work packages is a key element of this overall process. The purpose of this report is to provide guidance to power plant personnel regarding work package quality, by providing a consistent approach for administrative control, achieving an appropriate level-of-detail, ensuring an acceptable level-of-use, work package format, and application.

2005-12-21T23:59:59.000Z

229

RHIC Polarized proton operation  

DOE Green Energy (OSTI)

The Relativistic Heavy Ion Collider (RHIC) operation as the polarized proton collider presents unique challenges since both luminosity(L) and spin polarization(P) are important. With longitudinally polarized beams at the experiments, the figure of merit is LP{sup 4}. A lot of upgrades and modifications have been made since last polarized proton operation. A 9 MHz rf system is installed to improve longitudinal match at injection and to increase luminosity. The beam dump was upgraded to increase bunch intensity. A vertical survey of RHIC was performed before the run to get better magnet alignment. The orbit control is also improved this year. Additional efforts are put in to improve source polarization and AGS polarization transfer efficiency. To preserve polarization on the ramp, a new working point is chosen such that the vertical tune is near a third order resonance. The overview of the changes and the operation results are presented in this paper. Siberian snakes are essential tools to preserve polarization when accelerating polarized beams to higher energy. At the same time, the higher order resonances still can cause polarization loss. As seen in RHIC, the betatron tune has to be carefully set and maintained on the ramp and during the store to avoid polarization loss. In addition, the orbit control is also critical to preserve polarization. The higher polarization during this run comes from several improvements over last run. First we have a much better orbit on the ramp. The orbit feedback brings down the vertical rms orbit error to 0.1mm, much better than the 0.5mm last run. With correct BPM offset and vertical realignment, this rms orbit error is indeed small. Second, the jump quads in the AGS improved input polarization for RHIC. Third, the vertical tune was pushed further away from 7/10 snake resonance. The tune feedback maintained the tune at the desired value through the ramp. To calibrate the analyzing power of RHIC polarimeters at any energy above injection, the polarized hydrogen jet target runs for every fill with both beams. Based on the known analyzing power, there is very little polarization loss between injection and 100 GeV. An alternative way is to measure the asymmetry at 100 GeV followed by ramping up to 250 GeV and back down to 100 GeV and then to measure the asymmetry again at 100 GeV. If the asymmetry after the down ramp is similar to the measurement before the up ramp, polarization was also preserved during the ramp to 250 GeV. The analyzing power at storage energy can then be extracted from the asymmetries measured at 100 GeV and 250 GeV. The tune and orbit feedbacks are essential for the down ramp to be possible. The polarized proton operation is still going on. We will push bunch intensity higher until reaching the beam-beam limit. The even higher intensity will have to wait for the electron lenses to compensate the beam-beam effect. To understand the details of spin dynamics in RHIC with two snakes, spin simulation with the real magnet fields have been developed recently. The study will provide guidance for possible polarization loss schemes. Further polarization gain will requires a polarized source upgrade; more careful setup jump quads in the AGS to get full benefit; and control emittance in the whole accelerator chain.

Huang, H.; Ahrens, L.; Alekseev, I.G.; Aschenauer, E.; Atoian, G.; Bai, M.; Bazilevsky, A.; Blaskiewicz, M.; Brennan, J.M.; Brown, K.A.; Bruno, D.; Connolly, R.; Dion, A.; D'Ottavio, T.; Drees, K.A.; Fischer, W.; Gardner, C.; Glenn, J.W.; Gu, X.; Harvey, M.; Hayes, T.; Hoff, L.; Hulsart, R.L.; Laster, J.; Liu, C.; Luo, Y.; MacKay, W.W.; Makdisi, Y.; Marr, G.J.; Marusic, A.; Meot, F.; Mernick, K.; Michnoff, R,; Minty, M.; Montag, C.; Morris, J.; Nemesure, S.; Poblaguev, A.; Ptitsyn, V.; Ranjibar, V.; Robert-Demolaize, G.; Roser, T.; J.; Severino, F.; Schmidke, B.; Schoefer, V.; Severino, F.; Smirnov, D.; Smith, K.; Steski, D.; Svirida, D.; Tepikian, S.; Trbojevic, D.; Tsoupas, N.; Tuozzolo, J. Wang, G.; Wilinski, M.; Yip, K.; Zaltsman, A.; Zelenski, A.; Zeno, K.; Zhang, S.Y.

2011-03-28T23:59:59.000Z

230

LANL continuity of operations plan  

SciTech Connect

The Los Alamos National Laboratory (LANL) is a premier national security research institution, delivering scientific and engineering solutions for the nation's most crucial and complex problems. Our primary responsibility is to ensure the safety, security, and reliability of the nation's nuclear stockpile. LANL emphasizes worker safety, effective operational safeguards and security, and environmental stewardship, outstanding science remains the foundation of work at the Laboratory. In addition to supporting the Laboratory's core national security mission, our work advances bioscience, chemistry, computer science, earth and environmental sciences, materials science, and physics disciplines. To accomplish LANL's mission, we must ensure that the Laboratory EFs continue to be performed during a continuity event, including localized acts of nature, accidents, technological or attack-related emergencies, and pandemic or epidemic events. The LANL Continuity of Operations (COOP) Plan documents the overall LANL COOP Program and provides the operational framework to implement continuity policies, requirements, and responsibilities at LANL, as required by DOE 0 150.1, Continuity Programs, May 2008. LANL must maintain its ability to perform the nation's PMEFs, which are: (1) maintain the safety and security of nuclear materials in the DOE Complex at fixed sites and in transit; (2) respond to a nuclear incident, both domestically and internationally, caused by terrorist activity, natural disaster, or accident, including mobilizing the resources to support these efforts; and (3) support the nation's energy infrastructure. This plan supports Continuity of Operations for Los Alamos National Laboratory (LANL). This plan issues LANL policy as directed by the DOE 0 150.1, Continuity Programs, and provides direction for the orderly continuation of LANL EFs for 30 days of closure or 60 days for a pandemic/epidemic event. Initiation of COOP operations may be required to support an allhazards event, including a national security emergency, major fire, catastrophic natural disaster, man-made disaster, terrorism event, or technological disaster by rendering LANL buildings, infrastructure, or Technical Areas unsafe, temporarily unusable, or inaccessible.

Senutovitch, Diane M [Los Alamos National Laboratory

2010-12-22T23:59:59.000Z

231

Live Working Tools for High Temperature Conductors  

Science Conference Proceedings (OSTI)

In long-duration (several days) tests, strain link sticks used for live work were removed from service and exposed to conductors operating at high temperature of about 250-260C. Only strain link sticks were tested to date. Results obtained do not indicate damage or deterioration of the tested sticks. The research is a joint effort between project 35.010 Live Working Research for Overhead Transmission Equipment, Techniques, Procedures and Protective Grounding and project 35.015 Advanced Conductors to inve...

2010-12-17T23:59:59.000Z

232

FUNDAMENTALS IN THE OPERATION OF NUCLEAR TEST REACTORS. VOLUME 2. MATERIALS TESTING REACTOR DESIGN AND OPERATION  

SciTech Connect

The reactor components, building, control system and circuitry, and experimental and handling facilities are described and discussed, together with operation, shutdown, tank work and supplemental facilities. Training questions and answers are included. (D.C.W.)

1963-10-01T23:59:59.000Z

233

End of Month Working  

Gasoline and Diesel Fuel Update (EIA)

The level of gas in storage at the end of the last heating season (March The level of gas in storage at the end of the last heating season (March 31, 2000) was 1,150 billion cubic feet (Bcf), just above the 1995-1999 average of 1,139 Bcf. Underground working gas storage levels are currently about 8-9 percent below year-ago levels. In large part, this is because injection rates since April 1 have been below average. Storage injections picked up recently due to warm weather in the last half of October. The month of November is generally the last month available in the year for injections into storage. A cold November would curtail net injections into storage. If net injections continue at average levels this winter, we project that storage levels will be low all winter, reaching a level of 818 Bcf at the end of March, the lowest level since 1996

234

COMMENTARY Making sustainability work  

E-Print Network (OSTI)

Todays economic theory usually neglects the role of nature and environment. To make sustainability work it is, however, essential to (re-)integrate nature into the standard concepts of economics, especially by incorporating natural factors into the production function. It must be acknowledged that economic growth is not (only) the result of technical change but is mainly caused by rising energy-inputs into the economy, and that this is necessarily followed by resource exhaustion and pollution. Therefore, nature must not only be taken into account as a central factor of production but also in the form of environmental quality which is the basis for human quality of life. A numeric example shows that a small, but steady decrease of yearly resource consumption is already apt to redirect the economy on a path of sustainable development. 1998 Elsevier Science B.V. All rights reserved. Keywords: Sustainable development; Economic theory of production; Economic growth; Technical change; Non-renewable resources

Hans Christoph Binswanger

1996-01-01T23:59:59.000Z

235

Working With FEERC  

NLE Websites -- All DOE Office Websites (Extended Search)

Mechanisms For Partnering Mechanisms For Partnering with the Fuels, Engines, and Emissions Research Center at the Oak Ridge National Laboratory Oak Ridge National Laboratory (ORNL) has a program designed to provide technology-based solutions to organizations ranging from startups to Fortune 100 companies to academic institutions. Underlying this philosophy is our belief that strong partnerships with U.S. industry are the best way to share technological know-how with the private sector. Regardless of the activity-entering into a Cooperative Research and Development Agreement (CRADA) or Work for Others (WFO) agreement, or interacting with an industry or university through other means-we are committed to outcomes that create beneficial opportunities for the external organization as well as

236

Transforming Commercial Building Operations  

NLE Websites -- All DOE Office Websites (Extended Search)

Transforming Commercial Building Operations Transforming Commercial Building Operations Transforming Commercial Building Operations Ron Underhill Pacific Northwest National Laboratory ronald.underhill@pnnl.gov (509)375-9765 April 4, 2013 2 | Building Technologies Office eere.energy.gov * Most buildings are not commissioned (Cx) before occupancy, including HVAC and lighting systems * Buildings often are poorly operated and maintained leading to significant energy waste of 5 to 20%, even when they have building automation systems (BASs)

237

Transforming Commercial Building Operations  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Transforming Commercial Building Operations Transforming Commercial Building Operations Transforming Commercial Building Operations Ron Underhill Pacific Northwest National Laboratory ronald.underhill@pnnl.gov (509)375-9765 April 4, 2013 2 | Building Technologies Office eere.energy.gov * Most buildings are not commissioned (Cx) before occupancy, including HVAC and lighting systems * Buildings often are poorly operated and maintained leading to significant energy waste of 5 to 20%, even when they have building automation systems (BASs)

238

Operating Procedures and Control  

Science Conference Proceedings (OSTI)

...The principal operating variables are: Distance from inner cone of oxy-fuel gas flames or from air-fuel

239

Furnace Design and Operation  

Science Conference Proceedings (OSTI)

...S. Lampman, Energy-Efficient Heat-Treating Furnace Design and Operation, Heat Treating, Vol 4, ASM Handbook, ASM International,

240

Operational Readiness Team: OPERATIONAL READINESS REVIEW PLAN FOR THE  

NLE Websites -- All DOE Office Websites (Extended Search)

oak ridge oak ridge 12 ...... Prepared by the Operational Readiness Team: OPERATIONAL READINESS REVIEW PLAN FOR THE RAD1 0 1 SOT0 PE THERMOELECTRIC GENERATOR MATERIALS PRODUCTION TASKS R. H. Cooper M. M. Martin C. R. Riggs R. L. Beatty E. K. Ohriner R. N. Escher OISTRIBUTIQM OF THIS DOCUMENT IS UNLIMITED DISCLAIMER This report was prepared as an account of work sponsored by an agency of the United States Government. Neither the United States Government nor any agency Thereof, nor any of their employees, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately

Note: This page contains sample records for the topic "operation 1943-1944 working" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


241

Work Management Improvement at Burlington Generating Station  

Science Conference Proceedings (OSTI)

The Work Coordination Process (WCP), developed in an EPRI tailored collaboration effort to upgrade the maintenance program at Burlington Generating Station, is an organized methodology to prepare for and perform preventative and corrective maintenance during both outages and running periods. The coordinating process supports both the need of operational personnel for maximum equipment availability and the need of maintenance personnel for access to plant equipment to ensure maximum reliability.

2001-11-19T23:59:59.000Z

242

BNL | ATF Operations Weekly Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

Operations Weekly Summary Operations Weekly Summary Week Starts E-beam Status CO2 Status 2013/12/30 Up time: 0 days Down time: 5 days Activity: Maintenance & holiday week Up time: 0 days Down time: 5 days (setup) Activity: OPA work & holiday week 2013/12/23 Up time: 1 days Down time: 4 days (holiday week) Exp: Beam Studies Group: ATF Energy: 57.6 MeV Charge: 500 pC Up time: 0 days Down time: 5 days Activity: OPA work & holiday week 2013/12/16 Up time: Down time: Exp: AE-58, ERL BPM testing + beam studies Group: AE58, BNL (C-AD) / ATF Energy: 57.6 MeV Charge: 500 pC Up time: 0 days Down time: 5 days (setup) Activity: OPA work, EUVL test setup (AE59) and maintenance 2013/12/09 Up time: Down time: Exp: AE-52, Beam Manipulation by self wakefield Group: AE52, Euclid techlabs Energy: 57.6 MeV

243

NSLS Committees | Interlock Working Group  

NLE Websites -- All DOE Office Websites (Extended Search)

Interlock Working Group Charge The NSLS Interlock Working Group shall review all new construction and modification of NSLS and SDL personnel protection interlock systems. It is the...

244

May 21, 2012, Office of Health, Safety and Security (HSS) Focus Group Work Force Retention Work Group Charter  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Work Force Retention Work Group Charter Work Force Retention Work Group Charter In an ongoing effort to further the improvement of health, safety, environmental, and security performance within the Department, DOE is engaged in the establishment of work groups to pursue health and safety improvements across the DOE Complex. These efforts support DOE's responsibility as owner/manager to protect its greatest asset: the worker. The work groups support DOE's integrated safety management system and further DOE's best interests by fostering worker involvement and partnerships to maximize continuity of operations and the success of the Department's national security mission.

245

Fuel Cell Technologies Office: Durability Working Group  

NLE Websites -- All DOE Office Websites (Extended Search)

Durability Working Group Durability Working Group The Durability Working Group meets twice per year to exchange information, create synergies, and collaboratively develop both an understanding of and tools for studying degradation mechanisms of polymer electrolyte fuel cell stacks. Its members include principle investigators and supporting personnel from U.S. Department of Energy (DOE)-funded durability projects. More information on DOE durability activities can be found in the Multi-Year Research, Development, and Demonstration Plan. Description Technical Targets Meetings Contacts Description DOE durability targets for stationary and transportation fuel cells are 40,000 hours and 5,000 hours, respectively, under realistic operating conditions. In the most demanding applications, realistic operating conditions include impurities in the fuel and air, starting and stopping, freezing and thawing, and humidity and load cycles that result in stresses on the chemical and mechanical stability of the fuel cell materials, components, and interfaces. Degradation-exacerbating conditions resulting from cyclic operation include hydrogen starvation, differential pressure imbalance, oxidation-reduction cycling, and oxygen ingress to the anode, resulting in high cathode potentials. Significant progress has been made in determining the degradation mechanisms of fuel cell components and developing improved materials. However, as stated in the 2008 DOE Fuel Cell Solicitation, there is a need for further research and development in the following areas:

246

Peak Underground Working Natural Gas Storage Capacity  

Gasoline and Diesel Fuel Update (EIA)

Methodology Methodology Methodology Demonstrated Peak Working Gas Capacity Estimates: Estimates are based on aggregation of the noncoincident peak levels of working gas inventories at individual storage fields as reported monthly over a 60-month period ending in April 2010 on Form EIA-191M, "Monthly Natural Gas Underground Storage Report." The months of measurement for the peak storage volumes by facilities may differ; i.e., the months do not necessarily coincide. As such, the noncoincident peak for any region is at least as big as any monthly volume in the historical record. Data from Form EIA-191M, "Monthly Natural Gas Underground Storage Report," are collected from storage operators on a field-level basis. Operators can report field-level data either on a per reservoir basis or on an aggregated reservoir basis. It is possible that if all operators reported on a per reservoir basis that the demonstrated peak working gas capacity would be larger. Additionally, these data reflect inventory levels as of the last day of the report month, and a facility may have reached a higher inventory on a different day of the report month, which would not be recorded on Form EIA-191M.

247

Spent Fuel Working Group Report. Volume 1  

SciTech Connect

The Department of Energy is storing large amounts of spent nuclear fuel and other reactor irradiated nuclear materials (herein referred to as RINM). In the past, the Department reprocessed RINM to recover plutonium, tritium, and other isotopes. However, the Department has ceased or is phasing out reprocessing operations. As a consequence, Department facilities designed, constructed, and operated to store RINM for relatively short periods of time now store RINM, pending decisions on the disposition of these materials. The extended use of the facilities, combined with their known degradation and that of their stored materials, has led to uncertainties about safety. To ensure that extended storage is safe (i.e., that protection exists for workers, the public, and the environment), the conditions of these storage facilities had to be assessed. The compelling need for such an assessment led to the Secretary`s initiative on spent fuel, which is the subject of this report. This report comprises three volumes: Volume I; Summary Results of the Spent Fuel Working Group Evaluation; Volume II, Working Group Assessment Team Reports and Protocol; Volume III; Operating Contractor Site Team Reports. This volume presents the overall results of the Working Group`s Evaluation. The group assessed 66 facilities spread across 11 sites. It identified: (1) facilities that should be considered for priority attention. (2) programmatic issues to be considered in decision making about interim storage plans and (3) specific vulnerabilities for some of these facilities.

O`Toole, T.

1993-11-01T23:59:59.000Z

248

Will NIF Work  

E-Print Network (OSTI)

It is vital that new clean and abundant sources of energy be developed for the sustainability of modern society. Nuclear fusion of the hydrogen isotopes deuterium and tritium, if successful, might make a major contribution toward satisfying this need. The U.S. has an important effort aimed at achieving practical inertial confinement fusion, ICF, which has been under development for decades at the Lawrence Livermore National Laboratory. The National Ignition Facility (NIF) is a giant laser to multiply-shock and thus quasi-isentropically compress a capsule of deuterium-tritium (DT) to high density and temperature, where the fusion rate is proportional to density squared times temperature to the fourth power. The principal problem that must be solved for NIF to work successfully is elimination of the Rayleigh-Tailor (R-T) instability that originates from the interface between the solid shell and the DT fuel within it. The R-T instability poisons the fusion reaction by reducing the temperature of the DT achieved ...

Nellis, W J

2009-01-01T23:59:59.000Z

249

Relaxation labeling using modular operators  

SciTech Connect

Probabilistic relaxation labeling has been shown to be useful in image processing, pattern recognition, and artificial intelligence. The approaches taken to date have been encumbered with computationally extensive summations which generally prevent real-time operation and/or easy hardware implementation. The authors present a new and unique approach to the relaxation labeling problem using modular, VLSI-oriented hierarchical complex operators. One of the fundamental concepts of this work is the representation of the probability distribution of the possible labels for a given object (pixel) as an ellipse, which may be summed with neighboring object's distribution ellipses, resulting in a new, relaxed label space. The mathematical development of the elliptical approach will be presented and compared to more classical approaches, and a hardware block diagram that shows the implementation of the relaxation scheme using vlsi chips will be presented. Finally, results will be shown which illustrate applications of the modular scheme, iteratively, to both edges and lines. 13 references.

Duncan, J.S.; Frei, W.

1983-01-01T23:59:59.000Z

250

Why.Spring. working.indd  

NLE Websites -- All DOE Office Websites (Extended Search)

nuclear inspectors nuclear inspectors train by playing video games | pg. 10 April 2011 In this Issue Plans to reduce LANL's environmental impact | pg. 16 LANL is operated by Los Alamos National Security, LLC for the U.S. Department of Energy's National Nuclear Security Administration About this issue Why would a graphic artist choose to work at Los Alamos National Laboratory over DreamWorks or Pixar? Why would a team of scientists and engineers play games to make the world a safer place? We'll introduce you to an unlikely team working (and playing) together to blend the real world with the virtual one. Step into the best of both on page 10. In your own corner of the world, you may notice fewer copies of Why magazine in your workplace-starting with this issue, you will only be mailed a printed paper copy if you

251

Working and Net Available Shell Storage Capacity  

U.S. Energy Information Administration (EIA) Indexed Site

Working and Net Available Shell Storage Capacity Working and Net Available Shell Storage Capacity With Data for September 2013 | Release Date: November 27, 2013 | Next Release Date: May 29, 2013 Previous Issues Year: September 2013 March 2013 September 2012 March 2012 September 2011 March 2011 September 2010 Go Containing storage capacity data for crude oil, petroleum products, and selected biofuels. The report includes tables detailing working and net available shell storage capacity by type of facility, product, and Petroleum Administration for Defense District (PAD District). Net available shell storage capacity is broken down further to show the percent for exclusive use by facility operators and the percent leased to others. Crude oil storage capacity data are also provided for Cushing, Oklahoma, an

252

Dieting: Does It Really Work?  

E-Print Network (OSTI)

this to the world of medical research, which operates onwhy a large body of medical research exists that puts people

Tomiyama, A. Janet

2007-01-01T23:59:59.000Z

253

A sequence transformation algorithm for supporting cooperative work on mobile devices  

Science Conference Proceedings (OSTI)

Operational transformation (OT) is a promising technique for supporting collaboration using mobile devices because it allows users to work on local data replicas even in a disconnected mode. However, as work goes mobile, a large number of operations ... Keywords: collaborative applications, data consistency, group editing, mobile computing, operational transformation

Bin Shao; Du Li; Ning Gu

2010-02-01T23:59:59.000Z

254

Manhattan Project: Final Bomb Design, Los Alamos: Laboratory, 1944-1945  

Office of Scientific and Technical Information (OSTI)

The first 0.11 seconds of the nuclear age, Trinity, July 16, 1945. FINAL BOMB DESIGN The first 0.11 seconds of the nuclear age, Trinity, July 16, 1945. FINAL BOMB DESIGN (Los Alamos: Laboratory, 1944-1945) Events > Bringing It All Together, 1942-1945 Establishing Los Alamos, 1942-1943 Early Bomb Design, 1943-1944 Basic Research at Los Alamos, 1943-1944 Implosion Becomes a Necessity, 1944 Oak Ridge and Hanford Come Through, 1944-1945 Final Bomb Design, 1944-1945 Atomic Rivals and the ALSOS Mission, 1938-1945 Espionage and the Manhattan Project, 1940-1945 American troops approaching the beach, D-Day, June 6, 1944. Late in 1944, Los Alamos began to shift from research to development and bomb production. Increased production at Oak Ridge and Hanford seemed to promise that enough plutonium and enriched uranium would be available for at least one bomb using each. Germany no longer was the intended primary target. The war in Europe (left) appeared to be entering its final phase, and evidence uncovered by the ALSOS mission in November 1944 indicated that the German atomic program had not gone beyond the research phase. Already by summer 1944, Groves and his advisers had turned their sights toward Japan. The atomic bomb would justify the years of effort, including both the vast expenditures and the judgment of everyone responsible, by bringing the war in the Pacific to a fiery end. J. Robert Oppenheimer Ongoing problems continued to complicate the efforts of Robert Oppenheimer (right) to finalize bomb design. Foremost among these were continuing personnel shortages, particularly of physicists, and supply difficulties. The procurement system, designed to protect the secrecy of the Los Alamos project, led to frustrating delays and, when Herb Lehr, SED, holding the Gadget's core, July 1945. combined with persistent late war shortages, proved a constant headache. The lack of contact between the remote laboratory and its supply sources exacerbated the problem, as did the relative lack of experience the academic scientists had with logistical matters. Leslie Groves and James Conant were determined not to let mundane problems compromise the bomb effort, and in fall 1944 they made several changes to prevent this possibility. Conant shipped as many scientists as could be spared from the Met Lab and Oak Ridge to Los Alamos, hired every civilian machinist he could lay his hands on, and arranged for Army enlisted men to supplement the work force (these GIs were known as SEDS ("Special Engineering Detachment"). Hartley Rowe, an experienced industrial engineer, provided help in easing the transition from research to production. Los Alamos also arranged for a rocket research team at the California Institute of Technology to aid in procurement, test fuses, and contribute to component development. These changes kept Los Alamos on track as design work reached its final stages.

255

Site Operator Program  

DOE Green Energy (OSTI)

Collectively, the organizations participating in the Site Operator Program have over forty years of EV experience and have operated electric vehicles (EVs) for over 600,000 miles, providing the most extensive EV operating and knowledge base in the country. The Site Operator Program is intended to provide financial and technical support and organizational resources to organizations active in the advancement of electric vehicles. Support is provided for the demonstration of vehicles and the test and evaluation of vehicles, components, and batteries. Support is also provided for the management and support of the program for the participating organizations. The Program provides a forum for participants to exchange information among the group, as well as with vehicle and equipment manufacturers and suppliers, and the public. A central data base at the Idaho National Engineering Laboratory provides a repository for-data on the vehicles being operated by the Program participants. Data collection emphasis is in the areas of operations, maintenance, and life cycle costs.

Warren, J.F.

1991-01-01T23:59:59.000Z

256

Site Operator Program  

DOE Green Energy (OSTI)

Collectively, the organizations participating in the Site Operator Program have over forty years of EV experience and have operated electric vehicles (EVs) for over 600,000 miles, providing the most extensive EV operating and knowledge base in the country. The Site Operator Program is intended to provide financial and technical support and organizational resources to organizations active in the advancement of electric vehicles. Support is provided for the demonstration of vehicles and the test and evaluation of vehicles, components, and batteries. Support is also provided for the management and support of the program for the participating organizations. The Program provides a forum for participants to exchange information among the group, as well as with vehicle and equipment manufacturers and suppliers, and the public. A central data base at the Idaho National Engineering Laboratory provides a repository for-data on the vehicles being operated by the Program participants. Data collection emphasis is in the areas of operations, maintenance, and life cycle costs.

Warren, J.F.

1991-12-31T23:59:59.000Z

257

Operating Procedures Guideline  

Science Conference Proceedings (OSTI)

The intention of this report is to provide guidance for generating stations management and personnel striving for successful methods of developing effective operating procedures. Standard operating procedure management is used in most businesses and industries to assist in the safe and efficient operation of those companies. Effectively managing the program is essential in order to comply with mandatory regulations, maintain the highest possible level of plant integrity, minimize human ...

2012-12-12T23:59:59.000Z

258

Updated Operations Assessment Guideline  

Science Conference Proceedings (OSTI)

The Operations Assessment Guideline (OAG) can be used to assess the organization and processes of operations departments. An internal utility team or third party can use this report to guide a team composed of industry experts and members of the assessed utility. This report is an update to EPRI report 1008520, Operations Assessment Guideline, published in March 2005. This improved version includes insights gained after three years of experience with the original report.

2008-03-25T23:59:59.000Z

259

Operations Cost Allocation Project  

NLE Websites -- All DOE Office Websites (Extended Search)

Operations Consolidation Project Operations Consolidation Project Operations Consolidation Project (OCP) Cost Allocation Presentation - September 20, 2011 OCP Cost Allocation Customer Presentation List of Acronyms OCP Cost Allocation Spreadsheets OCP Cost Allocation Customer Presentation - Questions and Answers - September 19 - 20, 2011 Additional Questions and Answers Customer Comments/Questions and Answers: Arizona Municipal Power Users Association Arizona Power Authority Central Arizona Project Colorado River Commission Colorado River Energy Distributors Association City of Gilbert, AZ Irrigation and Electrical Districts Association of Arizona Town of Marana, AZ City of Mesa, AZ Town of Wickenburg, AZ Western's Final Decision Regarding the Long-Term Cost Allocation Methodology for Operations Staff Costs

260

Pipeline Operations Program (Louisiana)  

Energy.gov (U.S. Department of Energy (DOE))

The Pipeline Operations Program regulates the construction, acquisition, abandonment and interconnection of natural gas pipelines, as well as, the transportation and use of natural gas supplies.

Note: This page contains sample records for the topic "operation 1943-1944 working" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


261

Bevalac Operations, 1989  

Science Conference Proceedings (OSTI)

This report discusses the following topics in relation to the Bevalac accelerator: accelerator technology operations summary; nuclear science; biomedical research; and publications and presentations.

Not Available

1990-06-01T23:59:59.000Z

262

SERIES B: Operations Research  

E-Print Network (OSTI)

Tokyo Institute of Technology. SERIES B: Operations ... Department of Computer Science, The University of Electro-Communications,. Chofugaoka, Chofu-Shi...

263

HQ - Human Resources Operations  

Energy.gov (U.S. Department of Energy (DOE))

HQs Human Recources Operations delivers services, including position management, recruitment, staffing and classification, and reduction in force at Headquarters. Click the "Contacts" Link to find...

264

Operating Conditions Opportunity  

NLE Websites -- All DOE Office Websites (Extended Search)

Components in Aggressive Operating Conditions Opportunity Research is active on the patent-pending technology, titled "3-Dimensional Functionally Gradient Coatings for...

265

The Emergency Response Operations  

Science Conference Proceedings (OSTI)

... ICS Incident Command System ... Trade Center Disaster: The Con Ed Substation in World ... operations, FDNY, NYPD, and fire ground positioning of ...

266

PLATO administers operator training  

SciTech Connect

Baltimore Gas and Electric Co. is committed to an in-depth training program for substation operators. For the past two years, one important part of the training program has been a computer-based educational system with a CRT touch-response graphic display that is interactive with the trainee. This system, known as PLATO, reproduces a training situation so realistic that the operator becomes completely involved with the lesson. When used for pretraining prior to substation operating experience, it provides a hands-on insight into operating practices without jeopardizing personnel or equipment, or degrading customer service.

Buehner, R.E.

1979-02-15T23:59:59.000Z

267

Operating Oak Ridge's "Calutrons"  

NLE Websites -- All DOE Office Websites (Extended Search)

Operating Oak Ridge's "Calutrons" The following Oral History is taken from The Manhattan Project - The Birth of the Atomic Bomb in the Words of Its Creators, Eyewitnesses, and...

268

Working Copy Effective Date 10/08/08  

E-Print Network (OSTI)

Drawing · DOE/WIPP 90-45, Remote-Handled Transuranic Content Codes (RH- TRUCON) · Contact-HandledWorking Copy Effective Date 10/08/08 WP 08-PT.16 Revision 0 Shielded Container Assembly Handling #12;Working Copy Shielded Container Assembly Handling and Operation Manual WP 08-PT.16, Rev. 0 TABLE

269

Manhattan Project: Final Reactor Design and X-10, 1942-1943  

Office of Scientific and Technical Information (OSTI)

Schematic of the X-10 Graphite Reactor, Oak Ridge FINAL REACTOR DESIGN AND X-10 Schematic of the X-10 Graphite Reactor, Oak Ridge FINAL REACTOR DESIGN AND X-10 (Met Lab and Oak Ridge [Clinton], 1942-1943) Events > The Plutonium Path to the Bomb, 1942-1944 Production Reactor (Pile) Design, 1942 DuPont and Hanford, 1942 CP-1 Goes Critical, December 2, 1942 Seaborg and Plutonium Chemistry, 1942-1944 Final Reactor Design and X-10, 1942-1943 Hanford Becomes Operational, 1943-1944 Before any plutonium could be chemically separated from uranium for a bomb, however, that uranium would first have to be irradiated in a production pile. CP-1 had been a success as a scientific experiment, but the pile was built on such a small scale that recovering any significant amounts of plutonium from it was impractical. In the fall of 1942, scientists of the Met Lab had decided to build a second Fermi pile at Argonne as soon as his experiments on the first were completed and to proceed with the "Mae West" design for a helium-cooled production pile as well. When DuPont engineers assessed the Met Lab's plans in the late fall, they agreed that helium should be given first priority. They placed heavy water second and urged an all-out effort to produce more of this highly effective moderator. Bismuth and water were ranked third and fourth in DuPont's analysis. Priorities began to change when Enrico Fermi's CP-1 calculations demonstrated a higher value for the neutron reproduction factor k (for a theoretical reactor of infinite size) than anyone had anticipated. Met Lab scientists concluded that a water-cooled pile was now feasible. Crawford Greenewalt, head of the DuPont effort, continued, however, to support helium cooling.

270

Name Title Work Phone Work E-Mail  

NLE Websites -- All DOE Office Websites (Extended Search)

12012 EOTA - STAFF Name Title Work Phone Work E-Mail Melissa Otero Program Manager 505-842-7112 motero@eota.energy.gov Janet Lee Online Learning Support Specialist 505-842-7110...

271

Work-Life Programs and Services  

Science Conference Proceedings (OSTI)

... NIST? Work Life Programs; Work Schedules. *. Bookmark and Share. Work-Life Programs and Services. Alternative ...

2011-09-22T23:59:59.000Z

272

CRAD, Conduct of Operations - Y-12 Enriched Uranium Operations...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Y-12 Enriched Uranium Operations Oxide Conversion Facility CRAD, Conduct of Operations - Y-12 Enriched Uranium Operations Oxide Conversion Facility January 2005 A section of...

273

Top 100 Operators: Proved Reserves and Production, Operated vs ...  

U.S. Energy Information Administration (EIA)

Top 100 Operators: Proved Reserves and Production, Operated vs Owned, 2008 . The operator of an oil or gas field is the company responsible for the fields ...

274

Maintenance Work Management Improvement: Improving Culture and Work Process  

Science Conference Proceedings (OSTI)

EPRI's Plant Maintenance Optimization (PMO) mission is to develop and demonstrate products and services for improved use of power plant maintenance resources and increased profitability. Based on a series of work management improvement projects, EPRI plans to develop a best practices guideline. As part of this effort, this document details how to improve fossil power plant work culture and work processes.

1998-06-16T23:59:59.000Z

275

Operating Practices Guidebook (OPG)  

Science Conference Proceedings (OSTI)

This guidebook is a summary of current practices concerning operation, maintenance, siting, and staffing of combustion turbine, combined cycle, and cogeneration equipment. Information obtained from both utility and independent generators addresses the important issues faced by operators, project planners, and business managers.

1995-05-12T23:59:59.000Z

276

Cloud Computing Operations Research  

Science Conference Proceedings (OSTI)

This paper argues that the cloud computing industry faces many decision problems where operations research OR could add tremendous value. To this end, we provide an OR perspective on cloud computing in three ways. First, we compare the cloud computing ... Keywords: cloud IT, cloud computing, green IT, operations research, supply chain

Ilyas Iyoob, Emrah Zarifoglu, A. B. Dieker

2013-06-01T23:59:59.000Z

277

http://bellview/TeamWorks/TRUTeamWorks.PDF  

NLE Websites -- All DOE Office Websites (Extended Search)

two cranes in operation. " But the preparations don't stop there. The Maintenance, Engineering and Waste Handling groups have collectively assessed the availability of spare...

278

Radiation Safety Work Control Form  

NLE Websites -- All DOE Office Websites (Extended Search)

Radiation Safety Work Control Form Radiation Safety Work Control Form (see instructions on pg-2) Rev July-2012 Area: Form #: Date: Preliminary Applicability Screen: (a) Will closing the beam line injection stoppers mitigate the radiological hazards introduced by the proposed work? Yes No (b) Can the closed state of the beam line injection stoppers be assured during the proposed work (ie., work does NOT involve injection stoppers or associated HPS)? Yes No If the answers to both questions are yes, the work can be performed safely under an SSRL RSWCF. If the answer to either question is no, then the work must be performed under a SPEAR3 RSWCF. Section 1: Description of work to be done, including date and time. (Person Responsible completes section)

279

The Work for Others Agreement  

NLE Websites -- All DOE Office Websites (Extended Search)

were granted the authority to perform work for others by the Atomic Energy Act of 1954 Public Law 83-703; 42 USC 2053. Work For Others programs at the DOE national...

280

How does the brain work?  

NLE Websites -- All DOE Office Websites (Extended Search)

Conceptually though it's a widget to get folks from where they live to where they work, and it works by figuring out the paths they take, assigning trains to those routes,...

Note: This page contains sample records for the topic "operation 1943-1944 working" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


281

LANL continuity of operations plan  

SciTech Connect

The Los Alamos National Laboratory (LANL) is a premier national security research institution, delivering scientific and engineering solutions for the nation's most crucial and complex problems. Our primary responsibility is to ensure the safety, security, and reliability of the nation's nuclear stockpile. LANL emphasizes worker safety, effective operational safeguards and security, and environmental stewardship, outstanding science remains the foundation of work at the Laboratory. In addition to supporting the Laboratory's core national security mission, our work advances bioscience, chemistry, computer science, earth and environmental sciences, materials science, and physics disciplines. To accomplish LANL's mission, we must ensure that the Laboratory EFs continue to be performed during a continuity event, including localized acts of nature, accidents, technological or attack-related emergencies, and pandemic or epidemic events. The LANL Continuity of Operations (COOP) Plan documents the overall LANL COOP Program and provides the operational framework to implement continuity policies, requirements, and responsibilities at LANL, as required by DOE 0 150.1, Continuity Programs, May 2008. LANL must maintain its ability to perform the nation's PMEFs, which are: (1) maintain the safety and security of nuclear materials in the DOE Complex at fixed sites and in transit; (2) respond to a nuclear incident, both domestically and internationally, caused by terrorist activity, natural disaster, or accident, including mobilizing the resources to support these efforts; and (3) support the nation's energy infrastructure. This plan supports Continuity of Operations for Los Alamos National Laboratory (LANL). This plan issues LANL policy as directed by the DOE 0 150.1, Continuity Programs, and provides direction for the orderly continuation of LANL EFs for 30 days of closure or 60 days for a pandemic/epidemic event. Initiation of COOP operations may be required to support an allhazards event, including a national security emergency, major fire, catastrophic natural disaster, man-made disaster, terrorism event, or technological disaster by rendering LANL buildings, infrastructure, or Technical Areas unsafe, temporarily unusable, or inaccessible.

Senutovitch, Diane M [Los Alamos National Laboratory

2010-12-22T23:59:59.000Z

282

Plant Operational Status - Pantex Plant  

NLE Websites -- All DOE Office Websites (Extended Search)

Status Plant Operational Status Page Content Operational Status Shift 1 - Day The Pantex Plant is open for normal operations. All personnel are to report for duty according to...

283

Stirling machine operating experience  

Science Conference Proceedings (OSTI)

Numerous Stirling machines have been built and operated, but the operating experience of these machines is not well known. It is important to examine this operating experience in detail, because it largely substantiates the claim that stirling machines are capable of reliable and lengthy operating lives. The amount of data that exists is impressive, considering that many of the machines that have been built are developmental machines intended to show proof of concept, and are not expected to operate for lengthy periods of time. Some Stirling machines (typically free-piston machines) achieve long life through non-contact bearings, while other Stirling machines (typically kinematic) have achieved long operating lives through regular seal and bearing replacements. In addition to engine and system testing, life testing of critical components is also considered. The record in this paper is not complete, due to the reluctance of some organizations to release operational data and because several organizations were not contacted. The authors intend to repeat this assessment in three years, hoping for even greater participation.

Ross, B. [Stirling Technology Co., Richland, WA (United States); Dudenhoefer, J.E. [Lewis Research Center, Cleveland, OH (United States)

1994-09-01T23:59:59.000Z

284

Installation, Operation & Maintenance Instructions  

Science Conference Proceedings (OSTI)

... Connection by line plug: the plug should be within reach of the ... 1-phase L Brown To live to either power conductor ... Wash work clothing separately. ...

2013-11-29T23:59:59.000Z

285

HOT WORK PERMIT STANDARD OPERATING PROCEDURES Hot Work Permit Page 1 of 3 Adopted 11/22/2004  

E-Print Network (OSTI)

and Human Services Office of Inspector General, (HHS-OIG) Atlanta Region. "From Medicare fraud to theft of Investigation; the Department of Health and Human Services-Office of Inspector General; the U.S. Air Force of the Inspector General; the Department of Veterans Affairs-Office of Inspector General; the NASA Office

Papautsky, Ian

286

Quantum Operation Time Reversal  

E-Print Network (OSTI)

The dynamics of an open quantum system can be described by a quantum operation, a linear, complete positive map of operators. Here, I exhibit a compact expression for the time reversal of a quantum operation, which is closely analogous to the time reversal of a classical Markov transition matrix. Since open quantum dynamics are stochastic, and not, in general, deterministic, the time reversal is not, in general, an inversion of the dynamics. Rather, the system relaxes towards equilibrium in both the forward and reverse time directions. The probability of a quantum trajectory and the conjugate, time reversed trajectory are related by the heat exchanged with the environment.

Crooks, Gavin E

2007-01-01T23:59:59.000Z

287

Quantum Operation Time Reversal  

E-Print Network (OSTI)

The dynamics of an open quantum system can be described by a quantum operation, a linear, complete positive map of operators. Here, I exhibit a compact expression for the time reversal of a quantum operation, which is closely analogous to the time reversal of a classical Markov transition matrix. Since open quantum dynamics are stochastic, and not, in general, deterministic, the time reversal is not, in general, an inversion of the dynamics. Rather, the system relaxes towards equilibrium in both the forward and reverse time directions. The probability of a quantum trajectory and the conjugate, time reversed trajectory are related by the heat exchanged with the environment.

Gavin E. Crooks

2007-06-26T23:59:59.000Z

288

Reliability mathematics analysis on traction substation operation  

Science Conference Proceedings (OSTI)

In electrified railway traction power supply systems, the operational qualities and reliabilities of the main traction transformer loop is higher, but ones of bus output units is comparatively low. The traction transformer loop still works when output ... Keywords: Erlang distribution, Markov theory, life, reliability, traction substation, transformer

Hongsheng Su

2008-11-01T23:59:59.000Z

289

Dual Arm Work Module Development and Appplications  

SciTech Connect

The dual arm work module (DAWM) was developed at Oak Ridge National Laboratory (ORNL) by the Robotics Technology Development Program (RTDP) as a development test bed to study issues related to dual arm manipulation, including platform cotilguration, controls, automation, operations, and tooling. The original platform was based on two Schilling Titan II manipulators mounted to a 5-degree-of- freedom (DOF) base fabricated by RedZone Robotics, Inc. The 5-DOF articulation provided a center torso rotation, linear actuation to change the separation between the arms, and arm base rotation joints to provide "elbows up," elbows down," or "elbows out" orientation. A series of tests were conducted on operations, tooling, and task space scene analysis (TSSA)-driven robotics for overhead transporter- mounted and crane hook-deployed scenarios. A concept was developed for DAWM deployment from a large remote work vehicle, but the project was redirected to support dismantlement of the Chicago Pile #5 (CP-5) reactor at Argonne National Laboratory in fiscal year (FY) 1997. Support of CP-5 required a change in focus of the dual arm technology from that of a development test bed to a system focussed for a specific end user. ORNL teamed with the Idaho National Environmental ,Engineering Laboratory, Sandia National Laboratory, and the Savannah River Technology Center to deliver a crane-deployed derivative of the DAWM, designated the dual arm work platform (DAWP). RTDP staff supported DAWP at CP-5 for one FY; Argonne staff continued operation through to dismantlement of the reactor internals. Lessons learned from this interaction were extensive. Beginning in FY 1999, dual arm development activities are again being pursued in the context of those lessons learned. This paper describes the progression of philosophy of the DAWM from initial test bed to lessons learned through interaction at CP-5 and to the present investigation of telerobotic assist of teleoperation and TSSA- driven robotics.

Noakes, M.W.

1999-04-25T23:59:59.000Z

290

July 2012, Work Force Retention Work Group Status Overview  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Work Force Retention Work Group Status Overview Work Force Retention Work Group Status Overview Accomplishments: 1. Progress on the completion of the 10 CFR 1046 modifications to address barriers to workforce retention. Written response to public comment is being drafted by HS-51. 2. Pro-Force (PF) union representative, Randy Lawson, identified this accomplishment as the single most significant step toward PF workforce retention in over 20 years. 3. Draft re-charter of PF Career Options Committee (PFCOC) to establish a PF Working Group approved by GC-63 and GC NNSA. Near Term Goals and Activities: 1. Publish 1046 as a final rule - anticipated completion no later than September, assuming timely OMB review and approval. 2. Draft PF Working Group charter final review by senior management to be

291

Field Operations Program  

NLE Websites -- All DOE Office Websites (Extended Search)

688 688 May 1999 Field Operations Program Activities Status Report Fiscal Years 1997 through mid-1999 J. E. Francfort D. V. O'Hara L. A. Slezak DOE/ID-10688 Field Operations Program Activities Status Report Fiscal Years 1997 through mid-1999 J. E. Francfort 1 D. V. O'Hara 2 L. A. Slezak 2 Published May 1999 Idaho National Engineering and Environmental Laboratory Automotive Systems and Technology Department Lockheed Martin Idaho Technologies Company Idaho Falls, Idaho 83415 Prepared for the U.S. Department of Energy Idaho Operations Office 1 INEEL/Lockheed Martin Idaho Technologies Co. 2 U.S. Department of Energy iii EXECUTIVE SUMMARY The Field Operations Program is an electric vehicle testing and evaluation program sponsored by U.S. Department of Energy and managed by the Idaho National Engineering and Environmental

292

Operational Area Monitoring Plan  

Office of Legacy Management (LM)

' ' SECTION 11.7B Operational Area Monitoring Plan for the Long -Term H yd rol og ical M o n i to ri ng - Program Off The Nevada Test Site S . C. Black Reynolds Electrical & Engineering, Co. and W. G. Phillips, G. G. Martin, D. J. Chaloud, C. A. Fontana, and 0. G. Easterly Environmental Monitoring Systems Laboratory U. S. Environmental Protection Agency October 23, 1991 FOREWORD This is one of a series of Operational Area Monitoring Plans that comprise the overall Environmental Monitoring Plan for the DOE Field Office, Nevada (DOEINV) nuclear and non- nuclear testing activities associated with the Nevada Test Site (NTS). These Operational Area Monitoring Plans are prepared by various DOE support contractors, NTS user organizations, and federal or state agencies supporting DOE NTS operations. These plans and the parent

293

CH Packaging Operations Manual  

Science Conference Proceedings (OSTI)

This procedure provides instructions for assembling the CH Packaging Drum payload assembly, Standard Waste Box (SWB) assembly, Abnormal Operations and ICV and OCV Preshipment Leakage Rate Tests on the packaging seals, using a nondestructive Helium (He) Leak Test.

Washington TRU Solutions LLC

2005-06-13T23:59:59.000Z

294

Oak Ridge Operations.  

Office of Legacy Management (LM)

9 4s - 22 Department of Energy Oak Ridge Operations. SI9J>liB P.O. Box 2001 Oak Ridge. Tennessee 37831-8723 October 21, 1994 Mr. Charles A. Duritsa Regional Director...

295

Operating plan FY 1998  

SciTech Connect

This document is the first edition of Argonne`s new Operating Plan. The Operating Plan complements the strategic planning in the Laboratory`s Institutional Plan by focusing on activities that are being pursued in the immediate fiscal year, FY 1998. It reflects planning that has been done to date, and it will serve in the future as a resource and a benchmark for understanding the Laboratory`s performance. The heart of the Institutional Plan is the set of major research initiatives that the Laboratory is proposing to implement in future years. In contrast, this Operating Plan focuses on Argonne`s ongoing R&D programs, along with cost-saving measures and other improvements being implemented in Laboratory support operations.

1997-10-01T23:59:59.000Z

296

Paste Plant Operations  

Science Conference Proceedings (OSTI)

Mar 5, 2013 ... It now provides data extraction features that aggregate system ... DUBAL Carbon Plant management team defined and implemented a 3-year strategic ... how to best approach Paste Plant operating and maintenance activities.

297

Cogeneration Operational Issues  

E-Print Network (OSTI)

A great deal of the discussions concerning congeneration projects are focused on the "avoided cost" and other legal issues which effect these projects. These areas are extremely important and are essential to the success of the venture. Equally important, however, are the operational Issues which impact the utility and the cogenerator. This paper addresses the utility perspective in regard to possible impact of cogeneration systems on utility service to other customer, safety and substation operations. Other operational issues also include utility transmission planning, generation planning and fuel mix decisions. All of these operational problems have an impact on the ratepayer in regard to quality of electric service and future rates. Both the cogenerator and the utility have an interest in solving these problems.

Williams, M.

1985-05-01T23:59:59.000Z

298

Cell Technology and Operation  

Science Conference Proceedings (OSTI)

Mar 14, 2012 ... The potlines are operating at 353 kA with excellent performances exceeding 96.0 % current efficiency and achieving 13.0 kWh/kgAl for more...

299

Oak Ridge Operations YTO  

Office of Legacy Management (LM)

ed States Government Department of Energy Oak Ridge Operations YTO r , , EM-93:Hartman I - CATEGORICAL EXCLUSION (CX) DETERMINATION - RMOVAL ACTION AT M E SPRINGDALE r SITE I -a...

300

Idaho Operations Office  

NLE Websites -- All DOE Office Websites (Extended Search)

TFA-0404) (OM-PA-I0- 062) Dear Mr. Berman: This is a revised final response from the Idaho Operations Office (DOE-ID), regarding your July 22, 2010, Freedom ofInformation Act...

Note: This page contains sample records for the topic "operation 1943-1944 working" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


301

Idaho Operations Office  

NLE Websites -- All DOE Office Websites (Extended Search)

(ID-2010-01986-F) (OM-PA-I0-061) Dear Mr. Wetsch: This is in final response from the Idaho Operations Office (DOE-ID), regarding your June 2, 2010, Freedom of Information Act...

302

APS Operational Statistics  

NLE Websites -- All DOE Office Websites (Extended Search)

physics, geology, and environmental science. The APS was built by the U.S. Department of Energy as a national user facility. This page provides access to operational statistics...

303

Human Performance - Fossil Operations  

Science Conference Proceedings (OSTI)

All humans make errors. Industrial human errors can result in a loss of life and can significantly impact the productivity and cost effectiveness of any facility or company. Several industries in which human error has had a significant impact (for example, airline, medical, military, nuclear power, aviation, and chemical) have implemented human performance programs with excellent results. Human errors by fossil plant operators can easily challenge plant safety and production. In the fossil operations are...

2007-02-28T23:59:59.000Z

304

Operational Waste Volume Projection  

SciTech Connect

Waste receipts to the double-shell tank system are analyzed and wastes through the year 2015 are projected based on generation trends of the past 12 months. A computer simulation of site operations is performed, which results in projections of tank fill schedules, tank transfers, evaporator operations, tank retrieval, and aging waste tank usage. This projection incorporates current budget planning and the clean-up schedule of the Tri-Party Agreement. Assumptions were current as of June. 2000.

STRODE, J.N.

2000-08-28T23:59:59.000Z

305

Analysis of Unsafe Failure in Shell Type Boiler Working with Safe ...  

Science Conference Proceedings (OSTI)

The boiler was working under normal water level, it's safety valve operating normal. The design was normal and proven. All parameters were as usual and there...

306

DOE - Office of Legacy Management -- Gleason Works - NY 55  

Office of Legacy Management (LM)

Gleason Works - NY 55 Gleason Works - NY 55 FUSRAP Considered Sites Site: GLEASON WORKS (NY.55 ) Eliminated from consideration under FUSRAP Designated Name: Not Designated Alternate Name: None Location: Rochester , New York NY.55-1 Evaluation Year: 1994 NY.55-2 Site Operations: Metal fabrication operations - Rolled uranium metal. NY.55-1 Site Disposition: Eliminated - Potential for contamination considered remote NY.55-2 Radioactive Materials Handled: Yes Primary Radioactive Materials Handled: Uranium NY.55-1 Radiological Survey(s): Health and Safety Monitoring NY.55-1 NY.55-3 Site Status: Eliminated from consideration under FUSRAP Also see Documents Related to GLEASON WORKS NY.55-1 - NLO Report; Klein to Quigley; Trip Report to the Gleason Works, Rochester, New York on October 30 Thru November 10, 1961; December

307

Intermodal Subgroup Draft Work Plan2  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

1 of 2 Work Plan for the DOE TEC Rail Topic Group Intermodal Sub-Group Status: Active Chair: Melissa Bailey (CSG-NE) DOE Lead: Alex Thrower (OCRWM) Contractor Support: John Smegal (Legin) Start Date: July 17, 2007 Purpose: The purpose of the Transportation External Coordinating (TEC) Working Group's Rail Topic Group (RTG) is to provide stakeholder perspectives and feedback to the Office of National Transportation (ONT) in the Department of Energy's (DOE) Office of Civilian Radioactive Waste Management (OCRWM) and Environmental Management (EM) regarding topics of common interest concerning operating practices, logistical constraints, and other rail-related issues affecting the development and deployment of a safe, secure, and efficient system for transporting spent fuel (SNF) and high-level radioactive waste (HLW) to a

308

Working at Argonne's Center for Nanoscale Materials  

NLE Websites -- All DOE Office Websites (Extended Search)

Working at CNM Working at CNM For information on visiting Argonne National Laboratory, collaborating with us, or becoming an independent outside user of our facilities, please contact the CNM User Office. Hours of Operation The CNM, which is mandated to offer user access only 40 hours per week, provides users with routine access to facilities and instrumentation, as well as technical assistance when needed, between the hours of 7:00 a.m. and 7:00 p.m., Monday-Friday, except for Laboratory holidays and maintenance shutdowns. These hours are also in place for the availability of staff in the Theory and Modeling and X-Ray Microscopy Groups. The supercomputing facility (Carbon) and the hard X-ray nanoprobe facility at Sector 26 of the APS are available 24 hours, 7 days a week, except for maintenance shutdowns.

309

TeamWorks09-30-04  

NLE Websites -- All DOE Office Websites (Extended Search)

30, 2004 30, 2004 By the Numbers Congressional delegates tour WIPP Transportation and disposal statistics are available on pages 3 and 4. D E P A R T M E N T O F E N E R G Y U N I T E D S T A T ES O F A M E R I C A TeamWorks TeamWorks TRU A biweekly e-newsletter for the Waste Isolation Pilot Plant team roject personnel were honored to host a group of distinguished visitors on a rare weekend tour that included Chairman David Hobson of the U.S. House of Representatives Energy and Water Development Appropriations subcommittee; Ambassador Linton Brooks, Under Secretary for Nuclear Security; Congressman Steve Pearce; Ines Triay, DOE-EM Deputy Chief Operating Officer, Susan Grant, DOE Chief Financial Officer and several state and city officials. CBFO Deputy Manager Lloyd Piper said it was apparent that the

310

Annual work plan for FY 1992  

SciTech Connect

The Office of Inspector General (OIG) has an overall mission to prevent and detect fraud, waste, and mismanagement in Department of Energy (DOE) programs. As part of its responsibility in accomplishing its mission, the DOE Office of Audits publishes an Annual Work Plan'' in September of each year. The prime focus of the plan is to identify opportunities for audits to enhance the effectiveness, efficiency, and integrity of the DOE's programs and operations. Through this plan, we are able to maximize the effectiveness of our resources and to avoid duplicating audit coverage being provided by other audit groups, such as the US General Accounting Office (GAO) to US Department of Energy programs. Such planning is required by Office of Management and Budget Circular A-73 and DOE Order 2321.1A. This work plan, includes those audits that are to be carried over from Fiscal Year 1991 and those that are to be started during Fiscal year 1992.

Not Available

1991-09-30T23:59:59.000Z

311

Facility Operations Office, Brookhaven National Laboratory, BNL  

NLE Websites -- All DOE Office Websites (Extended Search)

Facility Operations Office Facility Operations Office Safely supporting the missions of the laboratory... The Facility Operations Office addresses key issues in work planning, maintenance engineering, service-delivery models, and annual facility-work plans. Facility Operations Center: The Facility Operations Center provides computer programs designed to assist in the planning, management and administrative procedures required for an effective maintenance and asset management process. As an information technology tool for managing the maintenance process, a Computerized Maintenance Management System (CMMS) is a mission-essential part of any organization, and a tool for success. Infrastructure Management: IM's goal is to ensure Brookhaven National Laboratory real property assets are planned for, managed, tracked, and upgraded as required in order to meet BNL's current and future programmatic needs. To accomplish this IM performs site and utilities master planning, manages BNL's new project request and prioritization system (3PBP), maintains utilities maps, manages BNL's space and facilities data base, and provides program management for BNL's GPP, Line Item and Operating Funded Project programs.

312

Working on the moon: The Apollo experience  

Science Conference Proceedings (OSTI)

The successful completion of any scientific or engineering project on the Moon will depend, in part, on human ability to do useful work under lunar conditions. In making informed decisions about such things as the use of humans rather than robots for specific tasks, the scheduling of valuable human time, and the design and selection of equipment and tools, good use can be made of the existing experience base. During the six completed landing missions, Apollo lunar surface crews conducted 160 astronaut-hours of extra-vehicular activities (EVAs) and also spent a similar sum of waking hours working in the cramped confines of the Lunar Module. The first three missions were primarily proof-tests of flight hardware and procedures. The ability to land equipment and consumables was very modest but, despite stay times of no more than 32 hours, the crews of Apollos 11, 12, and 14 were able to test their mobility and their capability of doing useful work outside the spacecraft. For the last three missions, thanks to LM modifications which enabled landings with significant amounts of cargo, stay times more than doubled to three days. The crews were able to use Lunar Rovers to conduct extensive local exploration and to travel up to 10 kilometers away from their immediate landing sites. During these final missions, the astronauts spent enough time doing work of sufficient complexity that their experience should be of use in the formulation early-stage lunar base operating plans. 2 refs.

Jones, E.M.

1989-01-01T23:59:59.000Z

313

FACT SHEET: BIOENERGY WORKING GROUP  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

, 2010 , 2010 1 FACT SHEET: BIOENERGY WORKING GROUP At the Clean Energy Ministerial in Washington, D.C. on July 19 th and 20 th , ministers launched a Bioenergy Working Group, which will advance the deployment of bioenergy technologies by implementing recommendations of the Technology Action Plan on Bioenergy Technologies that was released by the Major Economies Forum Global Partnership in December 2009. The Working Group will work in close cooperation with the Global Bioenergy Partnership (GBEP), which is co-chaired by Brazil and Italy. Initial key activities of the Working Group include: 1. Global Bioenergy Atlas: The Working Group will combine and build upon existing databases of sustainably-developed bioenergy potential around the globe and make it available in an open web-

314

September 2012, Work Force Retention Work Group Status Overview  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Work Force Retention Work Group Status Overview Work Force Retention Work Group Status Overview 2 Subgroups: Pro-Force and Non-Pro-Force Pro-Force Subgroup: Accomplishments: 1. Completion of 10 CFR 1046 [Protective Force Personnel Medical, Physical Readiness, Training, and Access Authorization Standards] as a final rule that includes modification efforts to address barriers to workforce retention. 2. Pro-Force (PF) union representative, Randy Lawson, identified this accomplishment as the single most significant step toward PF workforce retention in over 20 years. 3. Draft re-charter of PF Career Options Committee (PFCOC) to establish a PF Working Group approved by GC-63 and GC NNSA. Near Term Goals and Activities: 1. Publish 1046 as a final rule - publication anticipated this month.

315

Construction Work in Progress (Kansas)  

Energy.gov (U.S. Department of Energy (DOE))

This Act allows nuclear power plants to qualify for recovery of Construction Work in Progress (CWIP) and other preconstruction expenditures in rates. Previously, nuclear power plants were excluded...

316

Work Family Community, Human Resources  

NLE Websites -- All DOE Office Websites (Extended Search)

Work-Life Balance Programs Adoption Assistance Program Benefits Blood Drives Brookhaven Employee's Recreation Association (BERA) Brookhaven Retired Employee Association (BREA)...

317

Radiation Safety Work Control Form  

NLE Websites -- All DOE Office Websites (Extended Search)

Radiation Safety Work Control Form (see instructions on pg-2) Rev July-2012 Area: Form : Date: Preliminary Applicability Screen: (a) Will closing the beam line injection stoppers...

318

Evaluation of Fuel Cell Operation and Degradation  

Science Conference Proceedings (OSTI)

The concepts of area specific resistance (ASR) and degradation are developed for different fuel cell operating modes. The concepts of exergetic efficiency and entropy production were applied to ASR and degradation. It is shown that exergetic efficiency is a time-dependent function useful describing the thermal efficiency of a fuel cell and the change in thermal efficiency of a degrading fuel cell. Entropy production was evaluated for the cases of constant voltage operation and constant current operation of the fuel cell for a fuel cell undergoing ohmic degradation. It was discovered that the Gaussian hypergeometric function describes the cumulative entropy and electrical work produced by fuel cells operating at constant voltage. The Gaussian hypergeometric function is found in many applications in modern physics. This paper builds from and is an extension of several papers recently published by the authors in the Journal of The Electrochemical Society (ECS), ECS Transactions, Journal of Power Sources, and the Journal of Fuel Cell Science and Technology.

Williams, Mark; Gemmen, Randall; Richards, George

2011-06-01T23:59:59.000Z

319

Quantum Operator Design for Lattice Baryon Spectroscopy  

Science Conference Proceedings (OSTI)

A previously-proposed method of constructing spatially-extended gauge-invariant three-quark operators for use in Monte Carlo lattice QCD calculations is tested, and a methodology for using these operators to extract the energies of a large number of baryon states is developed. This work is part of a long-term project undertaken by the Lattice Hadron Physics Collaboration to carry out a first-principles calculation of the low-lying spectrum of QCD. The operators are assemblages of smeared and gauge-covariantly-displaced quark fields having a definite flavor structure. The importance of using smeared fields is dramatically demonstrated. It is found that quark field smearing greatly reduces the couplings to the unwanted high-lying short-wavelength modes, while gauge field smearing drastically reduces the statistical noise in the extended operators.

Adam Lichtl

2007-09-06T23:59:59.000Z

320

Storage Ring Operation Modes  

NLE Websites -- All DOE Office Websites (Extended Search)

Longitudinal bunch profile and Up: APS Storage Ring Parameters Longitudinal bunch profile and Up: APS Storage Ring Parameters Previous: Source Parameter Table Storage Ring Operation Modes Standard Operating Mode, top-up Fill pattern: 102 mA in 24 singlets (single bunches) with a nominal current of 4.25 mA and a spacing of 153 nanoseconds between singlets. Lattice configuration: Low emittance lattice with effective emittance of 3.1 nm-rad and coupling of 1%. Bunch length (rms): 33.5 ps. Refill schedule: Continuous top-up with single injection pulses occurring at a minimum of two minute intervals, or a multiple of two minute intervals. Special Operating Mode - 324 bunches, non top-up Fill pattern: 102 mA in 324 uniformly spaced singlets with a nominal single bunch current of 0.31 mA and a spacing of 11.37 nanoseconds between singlets.

Note: This page contains sample records for the topic "operation 1943-1944 working" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


321

Operations Information for Studies  

NLE Websites -- All DOE Office Websites (Extended Search)

Operations Information for Studies Operations Information for Studies This page contains historical information about hydropower operations. Reclamation UC Region 24-Month Studies FY2009 Load Information (pdf) SLIP total customer loads for Fiscal Year 2009 (Oct, 2008-Sept, 2009) FY2010 Load Information (pdf) SLIP total customer loads for Fiscal Year 2010 (Oct, 2009-Sept, 2010) FY2011 Load Information (pdf) SLIP total customer loads for Fiscal Year 2011 (Oct, 2010-Sept, 2011) FY2012 Load Information (pdf) SLIP total customer loads for Fiscal Year 2012 (Oct, 2011-Sept, 2012) FY2013 Load Information (pdf) SLIP total customer loads for Fiscal Year 2013 (Oct, 2012-Sept, 2013) CRSP Projected Power Releases From USBR (Excel) The most recent file of projected future power releases from CRSP Dams, median projection

322

GNF2 Operating Experience  

Science Conference Proceedings (OSTI)

GNF's latest generation fuel product, GNF2, is designed to deliver improved nuclear efficiency, higher bundle and cycle energy capability, and more operational flexibility. But along with high performance, our customers face a growing need for absolute fuel reliability. This is driven by a general sense in the industry that LWR fuel reliability has plateaued. Too many plants are operating with fuel leakers, and the impact on plant operations and operator focus is unacceptable. The industry has responded by implementing an INPO-coordinated program aimed at achieving leaker-free reliability by 2010. One focus area of the program is the relationship between fuel performance (i.e., duty) and reliability. The industry recognizes that the right balance between performance and problem-free fuel reliability is critical. In the development of GNF2, GNF understood the requirement for a balanced solution and utilized a product development and introduction strategy that specifically addressed reliability: evolutionary design features supported by an extensive experience base; thoroughly tested components; and defense-in-depth mitigation of all identified failure mechanisms. The final proof test that the balance has been achieved is the application of the design, initially through lead use assemblies (LUAs), in a variety of plants that reflect the diversity of the BWR fleet. Regular detailed surveillance of these bundles provides the verification that the proper balance between performance and reliability has been achieved. GNF currently has GNF2 lead use assemblies operating in five plants. Included are plants that have implemented extended power up-rates, plants on one and two-year operating cycles, and plants with and without NobleChem{sup TM} and zinc injection. The leading plant has undergone three pool-side inspections outages to date. This paper reviews the actions taken to insure GNF2's reliability, and the lead use assembly surveillance data accumulated to date to validate the adequacy/expected behavior of the design. (authors)

Schardt, John [GE Energy, Nuclear, 3901 Castle Hayne Road, Wilmington, NC 28402 (United States)

2007-07-01T23:59:59.000Z

323

DOE - Office of Legacy Management -- Pennsylvania Ordnance Works - PA 32  

Office of Legacy Management (LM)

Ordnance Works - PA 32 Ordnance Works - PA 32 FUSRAP Considered Sites Site: Pennsylvania Ordnance Works (PA.32 ) Designated Name: Alternate Name: Location: Evaluation Year: Site Operations: Site Disposition: Radioactive Materials Handled: Primary Radioactive Materials Handled: Radiological Survey(s): Site Status: This site is one of a group of 77 FUSRAP considered sites for which few, if any records are available in their respective site files to provide an historical account of past operations and their relationship, if any, with MED/AEC operations. Reviews of contact lists, accountable station lists, health and safety records and other documentation of the period do not provide sufficient information to warrant further search of historical records for information on these sites. These site files remain "open" to

324

Transuranic Waste Transportation Working Group Agenda | Department...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Transportation Working Group Agenda Transuranic Waste Transportation Working Group Agenda Transuranic Waste Transportation Working Group Agenda More Documents & Publications...

325

TRIGA reactor operating experience  

SciTech Connect

The Oregon State TRIGA Reactor (OSTR) has been in operation 3 years. Last August it was upgraded from 250 kW to 1000 kW. This was accomplished with little difficulty. During the 3 years of operation no major problems have been experienced. Most of the problems have been minor in nature and easily corrected. They came from lazy susan (dry bearing), Westronics Recorder (dead spots in the range), The Reg Rod Magnet Lead-in Circuit (a new type lead-in wire that does not require the lead-in cord to coil during rod withdrawal hss been delivered, much better than the original) and other small corrections.

Anderson, T.V. [Oregon State University, Corvallis, OR (United States)

1970-07-01T23:59:59.000Z

326

Appendix A - Statement of Work  

NLE Websites -- All DOE Office Websites (Extended Search)

o Cyber Security Plan ATTACHMENT 1- RFP RHB-3-23115 - 2 - o Construction Safety and Health Plan o Project Completion Criteria o Project Transition to Operations Plan o...

327

WORK PLAN FOR ENVIRONMENTAL WORK PLAN FOR ENVIRONMENTAL WORK PLAN FOR ENVIRONMENTAL  

Office of Legacy Management (LM)

WORK PLAN FOR ENVIRONMENTAL WORK PLAN FOR ENVIRONMENTAL WORK PLAN FOR ENVIRONMENTAL WORK PLAN FOR ENVIRONMENTAL WORK PLAN FOR ENVIRONMENTAL RESTORATION OF THE DOE MOUND RESTORATION OF THE DOE MOUND RESTORATION OF THE DOE MOUND RESTORATION OF THE DOE MOUND SITE, THE MOUND 2000 APPROACH SITE, THE MOUND 2000 APPROACH SITE, THE MOUND 2000 APPROACH SITE, THE MOUND 2000 APPROACH FEBRUARY 1999 Final (Revision 0) Department of Energy Babcock & Wilcox of Ohio Mr. Daniel Bird AICP, Planning Manager Miamisburg Mound Community Improvement Corporation 720 Mound Road Miamisburg, Ohio 45342-6714 Dear Mr. Bird: The Core Team, consisting of the U.S. Department of Energy Miamisburg Environmental Management Project (DOE-MEMP), U.S. Environmental Protection Agency (USEPA), and the Ohio Environmental Protection Agency (OEPA), appreciates your comments on the Work

328

The future of crowd work  

Science Conference Proceedings (OSTI)

Paid crowd work offers remarkable opportunities for improving productivity, social mobility, and the global economy by engaging a geographically distributed workforce to complete complex tasks on demand and at scale. But it is also possible that crowd ... Keywords: crowd work, crowdsourcing, organization design, research vision

Aniket Kittur; Jeffrey V. Nickerson; Michael Bernstein; Elizabeth Gerber; Aaron Shaw; John Zimmerman; Matt Lease; John Horton

2013-02-01T23:59:59.000Z

329

FY 1994 Annual Work Plan  

SciTech Connect

This is the third Office of Inspector General (OIG)Annual Work Plan. Its purpose is to summarize work completed in Fiscal Year (FY) 1993, identify ongoing projects from previous fiscal years which the OIG intends to continue into FY 1994, and announce planned projects which the OIG intends to begin in FY 19994.

Not Available

1993-10-01T23:59:59.000Z

330

Coiled tubing - Operations and services  

Science Conference Proceedings (OSTI)

Drilling with a continuous (rather than jointed) drill string is an old concept that is gaining new attention as a result of recent advances made in coiled tubing and drilling technology. The development of larger diameter, reliable, high-strength coiled tubing and smaller diameter, positive displacement motors, orienting tools, surveying systems and fixed cutting drill bits have given drilling with a continuous drill string a capability that was previously unattainable. Like its many other uses, (e.g., squeeze cementing, wellbore cleanouts, flow initiation, logging) the continuity of coiled tubing gives it several advantages over conventional drill strings. These include: drilling underbalanced safely, significantly reduced trip time, continuous circulation, smaller surface requirements. Coiled tubing drilling operations have smaller surface lease requirements than most conventional rigs due to the smaller footprint of the coiled tubing unit and associated equipment. Current coiled tubing drilling operations have the following limitations: conventional rig assistance is required for well preparation; conventional rigs must assist in running long protective and production casing strings or liners; hole sizes are smaller; working depth capabilities are shallower, coiled tubing life is less. This paper goes on to discuss the history of continuous drill strings and includes information on tubing units, circulating systems, drilling fluids, well control systems, downhole tools, orientation tools, and bottomhole assemblies. It then gives a cost comparison and an application of this type of drilling.

Gronseth, J.M. (Imperial Oil Resources Ltd., Calgary, Alberta (Canada))

1993-04-01T23:59:59.000Z

331

http://bellview/TeamWorks/TRUTeamWorks.htm  

NLE Websites -- All DOE Office Websites (Extended Search)

stemmed from a commitment made by WTS management to CBFO in May to "promote safety consciousness while we perform our work" and "improve our ability to manage people in a...

332

file://\\Bellview\TeamWorks\TRUTeamWorks.htm  

NLE Websites -- All DOE Office Websites (Extended Search)

8/03 TRU TeamWorks will resume printing on January 8, 2004 | Shipments expected this we 8/03 TRU TeamWorks will resume printing on January 8, 2004 | Shipments expected this we December 18, 2003 The Big Story: It's a wrap - 2003 Topics Characterization News Transportation News Disposal News Safety News Working Smart Announcements Our Team Tools Acronym List Archives Back to Main Page WIPP Home Page Links Feedback Contact us with feedback or submit your e-mail address for updates. Click here to e- mail. WIPP Shipments (as of 12/18/03 at 8:14 a.m.) Shipments scheduled to arrive at WIPP this week 23 Total shipments received at WIPP 2,226 In 2003, the WIPP team delivered in every mission-essential area. TRU TeamWorks wraps up the calendar year with 2003's performance highlights. Steve Warren, Washington TRU Solutions (WTS) general manager, says, "I view

333

Measurement of autonomous operation  

Science Conference Proceedings (OSTI)

While robotic systems and the field of Artificial Intelligence (AI) have been funded through the Department Of Defense (DoD) and Industry for decades, it was not until recent years that the combination of these two technologies has made truly significant ... Keywords: C4ISR, automated decision aid (ADA), autonomous control, autonomous operations, unmanned aerial system

W. Hamel

2010-09-01T23:59:59.000Z

334

NUCLEAR PLANT OPERATIONS AND  

E-Print Network (OSTI)

NUCLEAR PLANT OPERATIONS AND CONTROL KEYWORDS: neutron flux, cur- rent noise, vibration diagnostics: Swedish Nuclear Power Inspectorate SE- 10658 Stockholm, Sweden. NUCLEAR TECHNOLOGY VOL. 131 AUG. 2000 239 by the Swedish Nuclear Power Inspectorate, contract 14.5-980942-98242. REFERENCES 1. A. M. WEINBERG and H. C

Pázsit, Imre

335

Applications: Operational wind turbines  

E-Print Network (OSTI)

Capability Applications: Operational wind turbines Benefits: Optimize wind turbine performance Summary: Researchers at the Los Alamos National Laboratory (LANL) Intelligent Wind Turbine Program are developing a multi-physics modeling approach for the analysis of wind turbines in the presence of realistic

336

Operator strength reduction  

Science Conference Proceedings (OSTI)

Operator strength reduction is a technique that improves compiler-generated code by reformulating certain costly computations in terms of less expensive ones. A common case arises in array addressing expressions used in loops. The compiler can replace ... Keywords: loops, static single assignment form, strength reduction

Keith D. Cooper; L. Taylor Simpson; Christopher A. Vick

2001-09-01T23:59:59.000Z

337

Designing intelligent healthcare operations  

Science Conference Proceedings (OSTI)

Effective decision making is vital in all healthcare activities. While this decision making is typically complex and unstructured, it requires the decision maker to gather multi-spectral data and information in order to make an effective choice when ... Keywords: healthcare operations, intelligence continuum, knowledge management, multi agent systems

Nilmini Wickramasinghe; Christian Guttmann; Jonathan Schaffer

2009-12-01T23:59:59.000Z

338

Mobile workstation for decontamination and decommissioning operations  

SciTech Connect

This project is an interdisciplinary effort to develop effective mobile worksystems for decontamination and decommissioning (D&D) of facilities within the DOE Nuclear Weapons Complex. These mobile worksystems will be configured to operate within the environmental and logistical constraints of such facilities and to perform a number of work tasks. Our program is designed to produce a mobile worksystem with capabilities and features that are matched to the particular needs of D&D work by evolving the design through a series of technological developments, performance tests and evaluations. The project has three phases. In this the first phase, an existing teleoperated worksystem, the Remote Work Vehicle (developed for use in the Three Mile Island Unit 2 Reactor Building basement), was enhanced for telerobotic performance of several D&D operations. Its ability to perform these operations was then assessed through a series of tests in a mockup facility that contained generic structures and equipment similar to those that D&D work machines will encounter in DOE facilities. Building upon the knowledge gained through those tests and evaluations, a next generation mobile worksystem, the RWV II, and a more advanced controller will be designed, integrated and tested in the second phase, which is scheduled for completion in January 1995. The third phase of the project will involve testing of the RWV II in the real DOE facility.

Whittaker, W.L.; Osborn, J.F.; Thompson, B.R. [Carnegie-Mellon Univ., Pittsburgh, PA (United States). Robotics Inst.

1993-10-01T23:59:59.000Z

339

Sandia National Laboratories: Working with Sandia: Procurement: Potential  

NLE Websites -- All DOE Office Websites (Extended Search)

Small Business Small Business Opportunities Potential Suppliers Becoming a Supplier to Sandia Small Business Supplier Summit Small Business Categories Current Suppliers What Does Sandia Buy? Enterprise IT Services Working with Sandia Small Business Categories Small businesses we work with should have the following characteristics: An independently owned and operated entity. Not dominant in the field of operation in which it is bidding on government contracts. Meets criteria concerning number of employees or annual receipts established by the Small Business Administration (SBA). Concerns are "affiliates," when one controls or has the power to control another or when a third party controls or has the power to control both. North American Industry Classification System (NAICS)

340

Top 100 Operators: Proved Reserves and Production, Operated vs ...  

U.S. Energy Information Administration (EIA)

The operator of an oil or gas field is the company ... Operators in the United States are obligated to ... Reserves Production Reserves Production ...

Note: This page contains sample records for the topic "operation 1943-1944 working" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


341

Operations modeling and analysis of an underground coal mine  

Science Conference Proceedings (OSTI)

In general, it is quite difficult to describe and model operations and conveyance systems precisely in underground coal mines because of geological components, poor visibility, unreliable installed facilities, and difficult work conditions. In this study, ...

Kanna Miwa; Soemon Takakuwa

2011-12-01T23:59:59.000Z

342

Analyses of Wind Energy Impact on WFEC System Operations: Preprint  

DOE Green Energy (OSTI)

The National Renewable Energy Laboratory worked with the Western Farmers Electric Cooperative to analyze the impact of wind power from the Blue Canyon Wind Power Project on WFEC system operations.

Wan, Y.; Liao, J. R.

2006-03-01T23:59:59.000Z

343

Solar Industry At Work: Streamlining Home Solar Installation | Department  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Solar Industry At Work: Streamlining Home Solar Installation Solar Industry At Work: Streamlining Home Solar Installation Solar Industry At Work: Streamlining Home Solar Installation June 12, 2012 - 11:59am Addthis Sunrun is a home solar installation company based in San Francisco. | Photo by Francis Fine Art Photography. Sunrun is a home solar installation company based in San Francisco. | Photo by Francis Fine Art Photography. Erin R. Pierce Erin R. Pierce Digital Communications Specialist, Office of Public Affairs What are the key facts? Tillie Peterson works at Sunrun a home solar installation company based in San Francisco. As Director of Operations, Tillie works to get solar panels up and running for homeowners as simply and quickly as possible. Our Solar Industry At Work Series shares the personal success of

344

Underground Natural Gas Working Storage Capacity - Energy Information  

Gasoline and Diesel Fuel Update (EIA)

Underground Natural Gas Working Storage Capacity Underground Natural Gas Working Storage Capacity With Data for November 2012 | Release Date: July 24, 2013 | Next Release Date: Spring 2014 Previous Issues Year: 2013 2012 2011 2010 2009 2008 2007 2006 Go Overview Natural gas working storage capacity increased by about 2 percent in the Lower 48 states between November 2011 and November 2012. The U.S. Energy Information Administration (EIA) has two measures of working gas storage capacity, and both increased by similar amounts: Demonstrated maximum volume increased 1.8 percent to 4,265 billion cubic feet (Bcf) Design capacity increased 2.0 percent to 4,575 Bcf Maximum demonstrated working gas volume is an operational measure of the highest level of working gas reported at each storage facility at any time

345

Work Management Guidelines for Fossil Power Plant Personnel  

Science Conference Proceedings (OSTI)

This report provides overview guidance for implementing or improving the work management process at fossil power plants. The concepts in this report are based on best practices from many power plants at various utilities. Also, recent operations and maintenance assessments revealed that work management processes were in various stages of implementation and not at the generally accepted industry standards. Problems noted during recent assessments included lack of coordination among plant organizations, la...

2008-03-21T23:59:59.000Z

346

FY 1987 current fiscal year work plan  

SciTech Connect

This Current Year Work Plan presents a detailed description of the activities to be performed by the Joint Integration Office during FY87. It breaks down the activities into two major work areas: Program Management and Program Analysis. Program Management is performed by the JIO by providing technical planning and guidance for the development of advanced TRU waste management capabilities. This includes equipment/facility design, engineering, construction, and operations. These functions are integrated to allow transition from interim storage to final disposition. JIO tasks include program requirements identification, long-range technical planning, budget development, program planning document preparation, task guidance, task monitoring, information gathering and task reporting to DOE, interfacing with other agencies and DOE lead programs, integrating public involvement with program efforts, and preparation of program status reports for DOE. Program Analysis is performed by the JIO to support identification and assessment of alternatives, and development of long-term TRU waste program capabilities. This work plan includes: system analyses, requirements analyses, interim and procedure development, legislative and regulatory analyses, dispatch and traffic analyses, and data bases.

1986-12-01T23:59:59.000Z

347

FAQS Qualification Card - Nuclear Operations Specialist | Department of  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Nuclear Operations Specialist Nuclear Operations Specialist FAQS Qualification Card - Nuclear Operations Specialist A key element for the Department's Technical Qualification Programs is a set of common Functional Area Qualification Standards (FAQS) and associated Job Task Analyses (JTA). These standards are developed for various functional areas of responsibility in the Department, including oversight of safety management programs identified as hazard controls in Documented Safety Analyses (DSA). For each functional area, the FAQS identify the minimum technical competencies and supporting knowledge and skills for a typical qualified individual working in the area. FAQC-NuclearOperationsSpecialist.docx Description Nuclear Operations Specialist Qualification Card More Documents & Publications

348

NIF's Operations Support Building awarded LEED certification | National  

National Nuclear Security Administration (NNSA)

NIF's Operations Support Building awarded LEED certification | National NIF's Operations Support Building awarded LEED certification | National Nuclear Security Administration Our Mission Managing the Stockpile Preventing Proliferation Powering the Nuclear Navy Emergency Response Recapitalizing Our Infrastructure Continuing Management Reform Countering Nuclear Terrorism About Us Our Programs Our History Who We Are Our Leadership Our Locations Budget Our Operations Media Room Congressional Testimony Fact Sheets Newsletters Press Releases Speeches Events Social Media Video Gallery Photo Gallery NNSA Archive Federal Employment Apply for Our Jobs Our Jobs Working at NNSA Blog Home > NNSA Blog > NIF's Operations Support Building awarded LEED certification NIF's Operations Support Building awarded LEED certification Posted By Office of Public Affairs

349

07.A GENERAL 07.A.01 Proper illumination of work spaces, project sites, roadways  

E-Print Network (OSTI)

NFPA Standards. 07.A.09 If work is to be performed at night, a night operations' lighting plan shall outdoor - tunnels and general underground work areas (minimum 110 lux required at tunnel and shaft heading during drilling, mucking, and scaling) 110 50 110 10 5 10 Conveyor routes 110 10 Dam Operating Areas

US Army Corps of Engineers

350

CRAD, Conduct of Operations - Y-12 Enriched Uranium Operations Oxide  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Conduct of Operations - Y-12 Enriched Uranium Operations Conduct of Operations - Y-12 Enriched Uranium Operations Oxide Conversion Facility CRAD, Conduct of Operations - Y-12 Enriched Uranium Operations Oxide Conversion Facility January 2005 A section of Appendix C to DOE G 226.1-2 "Federal Line Management Oversight of Department of Energy Nuclear Facilities." Consists of Criteria Review and Approach Documents (CRADs) used for a January, 2005 assessment of Conduct of Operations program at the Y-12 - Enriched Uranium Operations Oxide Conversion Facility. CRADs provide a recommended approach and the types of information to gather to assess elements of a DOE contractor's programs. CRAD, Conduct of Operations - Y-12 Enriched Uranium Operations Oxide Conversion Facility More Documents & Publications CRAD, DOE Oversight - Y-12 Enriched Uranium Operations Oxide Conversion

351

RHIC II Science Working Groups  

NLE Websites -- All DOE Office Websites (Extended Search)

Workshops Workshops The series of RHIC II Science Workshops began in November 2004, at which time seven Working Groups were initiated. These groups met in workshops through 2005, with the purpose of providing an organized forum for the community to address and describe quantitatively the most important science issues for the proposed RHIC II luminosity upgrade, and corresponding detector upgrades. Each Working Group was led by three convenors representing theory and experiment, and each has produced a detailed report (except for the "New Directions" group, which provided a sounding board and input to the other groups). The Working Group reports are linked below. The summary "white paper" document, "Future Science at the Relativistic Heavy Ion Collider" (PDF), is based on these reports, and was prepared by a Writing Committee that included at least one convenor from each of the Working Groups.

352

Working with Modules within Python  

NLE Websites -- All DOE Office Websites (Extended Search)

Working with Modules within Perl and Python Working with Modules within Perl and Python Working with Modules within Perl and Python It can often be convenient to work with the modules system from within perl or python scripts. You can do this! Using Modules within Python The EnvironmentModules python package gives access to the module system from within python. The EnvironmentModules python package has a single function: module. Using this function you can provide the same arguments you would to "module" on the command line. The module() function accepts a list of arguments, like ['load','']; or ['unload','']. >>> import EnvironmentModules as EnvMod >>> EnvMod.module(['load','blast+']) It is important to understand that this is most effective for scripts

353

Clean Energy Works Oregon (Oregon)  

Energy.gov (U.S. Department of Energy (DOE))

Clean Energy Works began in 2009 as a pilot program run by the City of Portland. In 2010, the US department of Energy awarded $20 million to create a statewide nonprofit to expand the program...

354

DOE Work Breakdown Structure Handbook  

Energy.gov (U.S. Department of Energy (DOE))

This handbook provides suggested guidance and best practices on the development of product-oriented Work Breakdown Structures (WBS) that should be used by all projects within DOE to organize and...

355

First Aid at Work Introduction  

E-Print Network (OSTI)

provided. 2. People, wherever they work in our industry, can suffer injury or be taken ill. It is essential such equipment and facilities as are adequate and appropriate in the circumstances for enabling first

356

Nevada Operations Office  

Office of Legacy Management (LM)

Nevada Operations Office Nevada Operations Office t' . 0. Box 14100, Las Vegas, NV 89114-4100 Lt. Col. Kent J. Rohlof; USAF Commander 554th Civil Engineering Support Squadron (TAC) Nellis Air Force Base, NV 89191 DISPOSAL OF LIQUID RADIOACTIVE WASTE--NELLIS AIR FORCE BASE Layton O'Neill and Thomas Graham of my office recently visited two sites at Nellis AFB, Area II, identified as locations for burial of radioactive waste. The purpose of this visit was to visually inspect the physical status of the sites, one identified as the location of the subject liquid wastes. Numerous readings were made with a hand-held Ludlum Model 125 Micro-R meter, for the purpose of personnel radiation protection walking into the controlled, posted radioactive waste compounds. No readings were above background.

357

Operations Improvement Surveys  

E-Print Network (OSTI)

Exxon Chemical Company developed unique site-wide energy optimization technology in the mid1970's. This technology was applied by means of site energy surveys which were carried out at every major Exxon facility throughout the world during the 1976-1981 timeframe. The first 20% of energy savings, versus the 1972 reference, had already been captured or was in progress via conventional energy conservation methods. The site energy surveys identified attractive investments to save a second 20% of energy use. In early 1982, Exxon Corp. started to apply this same technology to its major facilities to define attractive NO INVESTMENT and LOW INVESTMENT operational improvement savings which could be implemented quickly. This presentation covers Exxon's approach to site energy optimization and the Operations Improvement Survey Program. The Program has identified at many sites, an average of 5% reduction in today's energy costs at No/Low investment plus additional savings in the feedstock and energy supply areas.

Guide, J. J.; O'Brien, W. J.

1984-01-01T23:59:59.000Z

358

SURVEY OF FALLOUT OPERATIONS  

SciTech Connect

A survey was made of fall-out operations in the various countries of the world, These operations are outlined by country. The source of information has largely been the reports submitted to UNSCEAR forwarding data for their consideration. In addition, some material has been received directly in exchange for HASL Quarterlies and other publications of the Laboratory. In many cases, responsible scientists from the country concerned have reviewed the sheets and have made corrections. All of the programs that are shown have been and are subject to modification as time goes on, thus, the data indicate the status of the program as of 1961. No attempt has been made to list re search projects or special fall-out measurements and only programs of a continuing nature have been covered. (auth)

1962-07-01T23:59:59.000Z

359

San Francisco Operations Office  

Office of Legacy Management (LM)

San Francisco Operations Office San Francisco Operations Office 1333 Broadway Oakland, California 94612 Dr. Joseph 0. Ward, Chief Radiological Health Section Department of Health Services 744 P Street Sacramento, California, 95814 SUBJECT: Certification Docket of Gilman Hall Dear Dr. Ward: The Department of Energy (DOE) has completed and reviewed the remedial ac- tions of Gilman Hall located at the University of California, Berkeley, California. Based on this review, DOE certifies that the condition of Gilman Hall is radiologically acceptable for restricted use under the con- trols of the University of California's State General License 1333-62 pro- vided that the University's Office of Environmental Health and Safety con- tinues to survey Gilman Hall and monitor whenever remodeling or renovation

360

User Operation Manual  

NLE Websites -- All DOE Office Websites (Extended Search)

SNS-NSSD-TOF-TD-0002 - R00 SNS-NSSD-TOF-TD-0002 - R00 1 SEQUOIA Operations Manual for Users G.E. Granroth SEQUOIA Lead Instrument Scientist A.I. Kolesnikov SEQUOIA Instrument Scientist L.M. DeBeer-Schmitt SEQUOIA Scientific Associate T.E. Sherline Sample Environment Scientist Revised - May 13, 2013 SNS-NSSD-TOF-TD-0002 - R00 2 Abstract The SEQUOIA Operations Manual for Users presents a description of the SEQUOIA spectrometer located at beamline 17 (BL17) of the Spallation Neutron Source (SNS). It is the intent of this manual to inform the user regarding the SEQUOIA spectrometer and available sample environment, to run experiments, to access and analyze the collected data, and to provide the user with other potentially useful information. The first section serves to describe the components of which the instrument is comprised.

Note: This page contains sample records for the topic "operation 1943-1944 working" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


361

SNS Target Systems Operational  

E-Print Network (OSTI)

scheduling conflict with other remote handling work planned for the next shutdown. · The target and PBW integrated monolith and hot cell structures #12;32 Managed by UT-Battelle for the U.S. Department of Energy based on testing at Riken to 1.8 x 105 Gy · Improved neutronic performance and reduced remote handling

McDonald, Kirk

362

Experience of Hot Cell Renovation Work in CPF (Chemical Processing Facility)  

Science Conference Proceedings (OSTI)

Renovation work for operation room A of the Chemical Processing Facility (CPF) was carried out. Cell renovation work involved disassembly, removal and installation of new equipment for the CA-3 cell of operation room A and the crane renovation work involved the repair of the in-cell crane for the CA-5 cell of operation room A. There were not many examples of renovation work performed on cells under high radiation environment and alpha contamination in Japan. Lessons learnt: With respect to the cell renovation work and crane repair work, a method that gave full consideration to safety was employed and the work was performed without accidents or disaster. Moreover, through improvement of the method, reduction of radioactive exposure of the workers was achieved and a melt reduction device was designed to deal with the radioactive waste material that was generated in the renovation work to achieve significant melt reduction of waste material.

Toyonobu Nabemoto; Fujio Katahira; Tadatsugu Sakaya [IHI Corporation: Isogo-ku, Yokohama, Kanagawa pref, 235-8501 (Japan); Shinichi Aose; Takafumi Kitajima; Kouji Ogasawara; Kazunori Nomura; Shigehiko Miyachi; Yoshiaki Ichige; Tadahiro Shinozaki; Shinichi Ohuchi [Japan Atomic Energy Agency: Tokai-mura, Naka-gun, Ibaraki pref, 319-1194 (Japan)

2008-01-15T23:59:59.000Z

363

HEV Fleet Testing Operating Statistics  

NLE Websites -- All DOE Office Websites (Extended Search)

calculated for this figure using mass air flow over dynamic vehicle operation. 2006 Toyota Highlander Hybrid Final Fleet Testing Results Operating Performance Cumulative MPG 1 :...

364

HEV Fleet Testing Operating Statistics  

NLE Websites -- All DOE Office Websites (Extended Search)

calculated for this figure using mass air flow over dynamic vehicle operation. 2007 Toyota Camry Hybrid Final Fleet Testing Results Operating Performance Cumulative MPG 1 : 33.6...

365

What is an accelerator operator?  

NLE Websites -- All DOE Office Websites (Extended Search)

is an accelerator operator? First I'll explain the education one must have in order to be considered for an Accelerator Operator position. Jefferson Lab's typical Accelerator...

366

Operational health physics training  

SciTech Connect

The initial four sections treat basic information concerning atomic structure and other useful physical quantities, natural radioactivity, the properties of {alpha}, {beta}, {gamma}, x rays and neutrons, and the concepts and units of radiation dosimetry (including SI units). Section 5 deals with biological effects and the risks associated with radiation exposure. Background radiation and man-made sources are discussed next. The basic recommendations of the ICRP concerning dose limitations: justification, optimization (ALARA concepts and applications) and dose limits are covered in Section seven. Section eight is an expanded version of shielding, and the internal dosimetry discussion has been extensively revised to reflect the concepts contained in the MIRD methodology and ICRP 30. The remaining sections discuss the operational health physics approach to monitoring radiation. Individual sections include radiation detection principles, instrument operation and counting statistics, health physics instruments and personnel monitoring devices. The last five sections deal with the nature of, operation principles of, health physics aspects of, and monitoring approaches to air sampling, reactors, nuclear safety, gloveboxes and hot cells, accelerators and x ray sources. Decontamination, waste disposal and transportation of radionuclides are added topics. Several appendices containing constants, symbols, selected mathematical topics, and the Chart of the Nuclides, and an index have been included.

NONE

1992-06-01T23:59:59.000Z

367

Operated device estimation framework  

E-Print Network (OSTI)

Protective device estimation is a challenging task because there are numerous protective devices present in a typical distribution system. Among various protective devices, auto-reclosers and fuses are the main overcurrent protection on distribution systems. Operation of a protective device in response to a particular fault condition depends upon the protective devices operating behavior and coordination of various such protective devices. This thesis presents the design and implementation of a protective device estimation algorithm which helps in identifying which protective devices have operated to clear a short circuit condition. The algorithm uses manufacturers device details, power quality data measured from substation monitoring devices and power system event features estimated using existing DFA algorithms. The proposed technique can be used to evaluate coordination of these protective devices and helps in locating a fault in a distribution system feeder. This approach is independent of feeder topology and could be readily used for any distribution system. The effectiveness of this algorithm is verified by simulated and actual test data. Suggestions are included for future research and application by electric utilities.

Rengarajan, Janarthanan

2008-12-01T23:59:59.000Z

368

Method and Apparatus for Remote Delivery and Manipulation of a Miniature Tool Adjacent a Work Piece in a Restricted Space  

DOE Patents (OSTI)

An apparatus for remote delivery and manipulation of a miniature tool adjacent a work piece in a restricted space, includes a tool camer, a camage for manipulating the tool carrier relative to the work piece, a first actuator for operating the carnage, and an optional remote secondary operating actuator for operating the first actuator.

Sale, Christopher H.; Kaltenbaugh, Daniel R.

2004-08-10T23:59:59.000Z

369

Work Plan - U.S.-India Coal Working Group | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Work Plan - U.S.-India Coal Working Group Work Plan - U.S.-India Coal Working Group Work Plan - U.S.-India Coal Working Group More Documents & Publications HSS Work Group Telecom...

370

Report on the NGS3 Working Group on Safeguards by Design For Aqueous Reprocessing Plants  

SciTech Connect

The objective of the Working Group on SBD for Aqueous Reprocessing Facilities was to provide recommendations, for facility operators and designers, which would aid in the coordination and integration of nuclear material accountancy and the safeguards requirements of all concerned parties - operators, state/regional authorities, and the IAEA. The recommendations, which are to be provided to the IAEA, are intended to assist in optimizing facility design and operating parameters to ensure the safeguardability of the facility while minimizing impact on the operations. The one day Working Group session addressed a wide range of design and operating topics.

Johnson, Shirley J.; Ehinger, Michael; Schanfein, Mark

2011-02-01T23:59:59.000Z

371

Material instability hazards in mine-processing operations  

SciTech Connect

Many accidents occur in the mining industry as a result of the instability of material during handling and processing operation. Accidents due to dump point instability at stockpiles, and at spoil or waste piles, for example, occur with alarming frequency. Miners must be trained to be better aware of these hazards. Information on safe working procedures at stockpiles and surge piles is provided. Mine operators must review their training and operating procedures regularly to ensure that hazardous conditions are avoided.

Fredland, J.W.; Wu, K.K.; Kirkwood, D.W.

1993-10-01T23:59:59.000Z

372

PAPIERS DE RECHERCHE WORKING PAPERS  

E-Print Network (OSTI)

with operations in Mexico are funded from foreign investments. Additionally, the manufacturing sector is where is still a traditional/manufacturing management style, for Mexico's technology intensive firms. KEY savings by relocating their labor intensive manufacturing components to facilities in Mexico, where labor

Paris-Sud XI, Université de

373

Combined Operating License Model Program Plan  

Science Conference Proceedings (OSTI)

The Model Program Plan (MPP) provides functional guidance on how to prepare a Combined Operating License (COL) application for a new nuclear power facility when incorporating previous findings from both design certification (DC) and an early site permit (ESP) proceedings. The plan identifies the activities necessary to prepare an application and provides guidance on planning and managing a COL program, including working with DC and ESP holders and using subcontracted resources to develop necessary new in...

2003-11-17T23:59:59.000Z

374

Office of Security Operations  

NLE Websites -- All DOE Office Websites (Extended Search)

Office of Physical Protection Office of Physical Protection Bill Dwyer Director, 202-586-7887 Mission The mission of the Office of Physical Protection is to implement and oversee dedicated human resources, processes, and equipment designed to protect personnel and assets entrusted to our care at Department of Energy (DOE) Headquarters facilities. The Office is comprised of dedicated DOE Federal security professionals, Headquarters Protective Force personnel, and Alarms and Access Control Technicians. These security subject matter experts work together to ensure compliance with DOE Safeguards and Security regulations, Interagency Security Committee guidance, and federal laws. The result of this collaboration is a security program designed to ensure a safe and secure working environment for all Headquarters employees.

375

Categorical Exclusion Determinations: Savannah River Operations Office |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

January 17, 2012 January 17, 2012 CX-007642: Categorical Exclusion Determination Parking Lot Construction North of Pad 717-14F CX(s) Applied: B1.15 Date: 01/17/2012 Location(s): South Carolina Offices(s): Savannah River Operations Office January 4, 2012 CX-007646: Categorical Exclusion Determination Insulation removal work in F-Tank Farm CX(s) Applied: B1.3 Date: 01/04/2012 Location(s): South Carolina Offices(s): Savannah River Operations Office January 4, 2012 CX-007645: Categorical Exclusion Determination Nonproliferation Technology Section - Nanomaterials Research CX(s) Applied: B3.6 Date: 01/04/2012 Location(s): South Carolina Offices(s): Savannah River Operations Office December 29, 2011 CX-007650: Categorical Exclusion Determination Control Room Consolidation CX(s) Applied: B2.2

376

Division of Economics and Business Working Paper Series  

E-Print Network (OSTI)

capacity, operating costs, and downward-sloping demand curves. The results of this production year, Heterogeneity, and Cost Effectiveness Harrison Fell Joshua Linn Working Paper 2012-07 http Policies, Heterogeneity, and Cost Effectiveness Author(s): Harrison Fell Division of Economics and Business

377

Equipment Operational Requirements  

SciTech Connect

The Iraq Department of Border Enforcement is rich in personnel, but poor in equipment. An effective border control system must include detection, discrimination, decision, tracking and interdiction, capture, identification, and disposition. An equipment solution that addresses only a part of this will not succeed, likewise equipment by itself is not the answer without considering the personnel and how they would employ the equipment. The solution should take advantage of the existing in-place system and address all of the critical functions. The solutions are envisioned as being implemented in a phased manner, where Solution 1 is followed by Solution 2 and eventually by Solution 3. This allows adequate time for training and gaining operational experience for successively more complex equipment. Detailed descriptions of the components follow the solution descriptions. Solution 1 - This solution is based on changes to CONOPs, and does not have a technology component. It consists of observers at the forts and annexes, forward patrols along the swamp edge, in depth patrols approximately 10 kilometers inland from the swamp, and checkpoints on major roads. Solution 2 - This solution adds a ground sensor array to the Solution 1 system. Solution 3 - This solution is based around installing a radar/video camera system on each fort. It employs the CONOPS from Solution 1, but uses minimal ground sensors deployed only in areas with poor radar/video camera coverage (such as canals and streams shielded by vegetation), or by roads covered by radar but outside the range of the radar associated cameras. This document provides broad operational requirements for major equipment components along with sufficient operational details to allow the technical community to identify potential hardware candidates. Continuing analysis will develop quantities required and more detailed tactics, techniques, and procedures.

Greenwalt, B; Henderer, B; Hibbard, W; Mercer, M

2009-06-11T23:59:59.000Z

378

Working Remotely | Argonne National Laboratory  

NLE Websites -- All DOE Office Websites (Extended Search)

Working Remotely Working Remotely Remote Access Use VPN to access Argonne resources Wake up your computer if power management policies have been applied Connect to your work computer by using Remote Desktop Communications Log into web-based e-mail Outlook Zimbra Send instant messages with Jabber Use Argonne's voice mail and teleconferencing services Use Adobe Connect for web conferencing E-Mail Client and Mobile Device Configuration Changes for Exchange 2010 Cyber Security Secure your home computers Passwords MyPassword Change your password Choosing a good password Other Tools Upload a file for retrieval by others (login required) Argonne SharePoint Server (login required) Inside Argonne (accessible onsite or through VPN) Focal Point Management Blog (accessible onsite or through VPN)

379

Energy Work | Open Energy Information  

Open Energy Info (EERE)

Work Work Jump to: navigation, search Name Energy Work Place Kelaniya, Sri Lanka Sector Biomass, Renewable Energy, Solar Product Dealing with renewable energy applications, specifically solar and biomass power generation Coordinates 6.95°, 79.916702° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[{"text":"","title":"","link":null,"lat":6.95,"lon":79.916702,"alt":0,"address":"","icon":"","group":"","inlineLabel":"","visitedicon":""}]}

380

Perma Works | Open Energy Information  

Open Energy Info (EERE)

Perma Works Perma Works Jump to: navigation, search Name Perma Works Place Albuquerque, New Mexico Zip 87123 Sector Geothermal energy Product A company that focuses on producing enhanced geothermal systems through providing electronics and software. Coordinates 35.08418°, -106.648639° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[{"text":"","title":"","link":null,"lat":35.08418,"lon":-106.648639,"alt":0,"address":"","icon":"","group":"","inlineLabel":"","visitedicon":""}]}

Note: This page contains sample records for the topic "operation 1943-1944 working" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


381

CFCC working group meeting: Proceedings  

SciTech Connect

This report is a compilation of the vugraphs presented at this meeting. Presentations covered are: CFCC Working Group; Overview of study on applications for advanced ceramics in industries for the future; Design codes and data bases: The CFCC program and its involvement in ASTM, ISO, ASME, and military handbook 17 activities; CFCC Working Group meeting (McDermott Technology); CFCC Working Group meeting (Textron); CFCC program for DMO materials; Developments in PIP-derived CFCCs; Toughened Silcomp (SiC-Si) composites for gas turbine engine applications; CFCC program for CVI materials; Self-lubricating CFCCs for diesel engine applications; Overview of the CFCC program`s supporting technologies task; Life prediction methodologies for CFCC components; Environmental testing of CFCCs in combustion gas environments; High-temperature particle filtration ORNL/DCC CRADA; HSCT CMC combustor; and Case study -- CFCC shroud for industrial gas turbines.

NONE

1997-12-31T23:59:59.000Z

382

Work Practices for Chemical Fumehoods  

NLE Websites -- All DOE Office Websites (Extended Search)

Practices for Chemical Fumehoods Practices for Chemical Fumehoods (Reviewed May 16, 2011) Always use a chemical fumehood when working with toxic and/or volatile chemicals, not on an open bench. Chemical fumehoods are designed to provide protection for the user from chemical and radiological contaminants. However, they do not absolutely eliminate exposure, even under ideal conditions. Careless work practices can result in considerable exposure to users who may believe they are protected. To optimize the performance of the chemical hood, adhere to the following work practices: 1. Ensure that your chemical hood has a current inspection sticker (dated within the last year). The face velocity should be between 80 and 120 linear feet per minute (lfpm). 2. Verify that the chemical hood is drawing air.

383

STANDARD OPERATING PROTOCOLS FOR DECOMMISSIONING  

SciTech Connect

Decommissioning projects at Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) sites are conducted under project-specific decision documents, which involve extensive preparation time, public comment periods, and regulatory approvals. Often, the decision documents must be initiated at least one year before commencing the decommissioning project, and they are expensive and time consuming to prepare. The Rocky Flats Environmental Technology Site (RFETS) is a former nuclear weapons production plant at which hazardous substances and wastes were released or disposed during operations. As a result of the releases, RFETS was placed on the National Priorities List in 1989, and is conducting cleanup activities under a federal facilities compliance agreement. Working closely with interested stakeholders and state and federal regulatory agencies, RFETS has developed and implemented an improved process for obtaining the approvals. The key to streamlining the approval process has been the development of sitewide decision documents called Rocky Flats Cleanup Agreement Standard Operating Protocols or ''RSOPs.'' RSOPs have broad applicability, and could be used instead of project-specific documents. Although no two decommissioning projects are exactly the same and they may vary widely in contamination and other hazards, the basic steps taken for cleanup are usually similar. Because of this, using RSOPs is more efficient than preparing a separate project-specific decision documents for each cleanup action. Over the Rocky Flats cleanup life cycle, using RSOPs has the potential to: (1) Save over 5 million dollars and 6 months on the site closure schedule; (2) Eliminate preparing one hundred and twenty project-specific decision documents; and (3) Eliminate writing seventy-five closure description documents for hazardous waste unit closure and corrective actions.

Foss, D. L.; Stevens, J. L.; Gerdeman, F. W.

2002-02-25T23:59:59.000Z

384

Why.Nov.work3.indd  

NLE Websites -- All DOE Office Websites (Extended Search)

Los Alamos National Laboratory Advancing National Security Through Scientifi c Inquiry scientists poke and prod the Red Planet November 2011 In this Issue Seeking solutions to global energy problems | pg. 14 LANL is operated by Los Alamos National Security, LLC for the U.S. Department of Energy's National Nuclear Security Administration About this issue We've reached the one-year mark for Why magazine-one full trip around the Sun. This issue takes us to other parts of the solar system. Our cover story highlights the science- and collaboration-behind preparing a mobile laboratory for a Mars reconnaissance mission. Meanwhile, on another side of the Lab, Los Alamos researchers work on solutions to some of planet Earth's greatest energy concerns-applying cutting-edge

385

Entanglement quantification by local unitary operations  

SciTech Connect

Invariance under local unitary operations is a fundamental property that must be obeyed by every proper measure of quantum entanglement. However, this is not the only aspect of entanglement theory where local unitary operations play a relevant role. In the present work we show that the application of suitable local unitary operations defines a family of bipartite entanglement monotones, collectively referred to as ''mirror entanglement.'' They are constructed by first considering the (squared) Hilbert-Schmidt distance of the state from the set of states obtained by applying to it a given local unitary operator. To the action of each different local unitary operator there corresponds a different distance. We then minimize these distances over the sets of local unitary operations with different spectra, obtaining an entire family of different entanglement monotones. We show that these mirror-entanglement monotones are organized in a hierarchical structure, and we establish the conditions that need to be imposed on the spectrum of a local unitary operator for the associated mirror entanglement to be faithful, i.e., to vanish in and only in separable pure states. We analyze in detail the properties of one particularly relevant member of the family, the ''stellar mirror entanglement'' associated with the traceless local unitary operations with nondegenerate spectra and equispaced eigenvalues in the complex plane. This particular measure generalizes the original analysis of S. M. Giampaolo and F. Illuminati [Phys. Rev. A 76, 042301 (2007)], valid for qubits and qutrits. We prove that the stellar entanglement is a faithful bipartite entanglement monotone in any dimension and that it is bounded from below by a function proportional to the linear entropy and from above by the linear entropy itself, coinciding with it in two- and three-dimensional spaces.

Monras, A.; Giampaolo, S. M.; Gualdi, G.; Illuminati, F. [Dipartimento di Matematica e Informatica, Universita degli Studi di Salerno, CNISM, Unita di Salerno, and INFN, Sezione di Napoli-Gruppo Collegato di Salerno, Via Ponte don Melillo, I-84084 Fisciano (Italy); Adesso, G.; Davies, G. B. [School of Mathematical Sciences, University of Nottingham, University Park, Nottingham NG7 2RD (United Kingdom)

2011-07-15T23:59:59.000Z

386

LANL highlights explosives work | National Nuclear Security Administration  

National Nuclear Security Administration (NNSA)

explosives work | National Nuclear Security Administration explosives work | National Nuclear Security Administration Our Mission Managing the Stockpile Preventing Proliferation Powering the Nuclear Navy Emergency Response Recapitalizing Our Infrastructure Continuing Management Reform Countering Nuclear Terrorism About Us Our Programs Our History Who We Are Our Leadership Our Locations Budget Our Operations Media Room Congressional Testimony Fact Sheets Newsletters Press Releases Speeches Events Social Media Video Gallery Photo Gallery NNSA Archive Federal Employment Apply for Our Jobs Our Jobs Working at NNSA Blog Home > NNSA Blog > LANL highlights explosives work LANL highlights explosives work Posted By Office of Public Affairs For more than 70 years, Los Alamos National Laboratory has been a frontrunner in explosives research, development and applications. To

387

GTRI commended for work to secure radiological sources | National Nuclear  

National Nuclear Security Administration (NNSA)

GTRI commended for work to secure radiological sources | National Nuclear GTRI commended for work to secure radiological sources | National Nuclear Security Administration Our Mission Managing the Stockpile Preventing Proliferation Powering the Nuclear Navy Emergency Response Recapitalizing Our Infrastructure Continuing Management Reform Countering Nuclear Terrorism About Us Our Programs Our History Who We Are Our Leadership Our Locations Budget Our Operations Media Room Congressional Testimony Fact Sheets Newsletters Press Releases Speeches Events Social Media Video Gallery Photo Gallery NNSA Archive Federal Employment Apply for Our Jobs Our Jobs Working at NNSA Blog Home > NNSA Blog > GTRI commended for work to secure radiological sources GTRI commended for work to secure radiological sources Posted By Office of Public Affairs Container NNSA's Global Threat Reduction Initiative (GTRI) was recently commended

388

GTRI commended for work to secure radiological sources | National Nuclear  

NLE Websites -- All DOE Office Websites (Extended Search)

GTRI commended for work to secure radiological sources | National Nuclear GTRI commended for work to secure radiological sources | National Nuclear Security Administration Our Mission Managing the Stockpile Preventing Proliferation Powering the Nuclear Navy Emergency Response Recapitalizing Our Infrastructure Continuing Management Reform Countering Nuclear Terrorism About Us Our Programs Our History Who We Are Our Leadership Our Locations Budget Our Operations Media Room Congressional Testimony Fact Sheets Newsletters Press Releases Speeches Events Social Media Video Gallery Photo Gallery NNSA Archive Federal Employment Apply for Our Jobs Our Jobs Working at NNSA Blog Home > NNSA Blog > GTRI commended for work to secure radiological sources GTRI commended for work to secure radiological sources Posted By Office of Public Affairs Container NNSA's Global Threat Reduction Initiative (GTRI) was recently commended

389

INDEPENDENT ELECTRICITY SYSTEM OPERATOR  

E-Print Network (OSTI)

The Board of Directors of the Independent Electricity System Operator (IESO) has adopted this Charter as part of its commitment to high standards of corporate governance in pursuing the objects of the IESO set out in the Electricity Act, 1998. This Charter describes the Boards mandate, accountability and composition, and sets out a specific Code of Conduct for the Board. More detailed information about the IESOs corporate governance is set out in the Governance and Structure By?law and in corporate policies, notably the Terms of Reference for a Director. The activities of the Board and its Committees are formally recorded in minutes of meetings. MANDATE The Board shall manage and supervise the management of the IESOs business and affairs and shall provide insight, input into and oversight of the development of the IESOs strategic direction. More specifically, the Boards mandate includes: periodically reviewing with Management: the strategic environment; the emergence of new risks and opportunities and the implications of such risks and opportunities for the IESOs strategic direction; and the establishment and operation of the IESO?administered markets to promote the purposes of the Electricity Act, 1998 including, without limitation, making market rules and amendments thereto; approving strategic plans that take into account the IESOs major risks and opportunities and overseeing the management of those risks; 2 appointing, monitoring and assessing the performance of the Chief Executive

unknown authors

2009-01-01T23:59:59.000Z

390

Program Operations Plan  

SciTech Connect

The Department of Energy's Atmospheric Chemistry Program (ACP) was initiated in 1991 to coordinate DOE's university and federal-laboratory atmospheric-chemistry research, and to focus these efforts on national and international information requirements in the atmospheric-chemistry field. This Program Operations Plan describes the structure and vision of the effort designed to fulfill these needs, and is divided into two major components. The first of these is a Strategic Plan, which outlines the ACP's rationale, objectives, and vision, and describes its products that are anticipated over a future ten-year period. Although based on realistic appraisals of goals that are attainable given the financial, material, and intellectual resources of the ACP community, this Strategic Plan does not describe these resources themselves. The second component of the Program Operations Plan, the Implementation Plan, deals directly with these resource considerations. As such it focuses on practical implementation of Strategic-Plan elements at the individual research institutions, the anticipated scientific contributions of these groups, and their coordination within the ACP. In contrast to the Strategic Plan, this Implementation Plan extends only five years into the future.

1993-04-01T23:59:59.000Z

391

Operating experience at CEBAF  

Science Conference Proceedings (OSTI)

CEBAF, the Continuous Electron Beam Accelerator Facility, is a 5-pass, recirculating, superconducting rf linac designed to provide exceptional beam quality at 4 GeV up to 200 {mu}A CW. It is made up of an injector, two 400-MeV linacs, and 9 recirculation arcs having a total beamline length of more than 4.5 km. On Nov. 5, 1995, CEBAF delivered a 4 GeV, 25-{mu}A CW electron beam to the first of 3 experimental halls and the experimental physics program was started 10 days later. Accelerator availability during the first month of the experimental run exceeded 75%. Beam properties measured in the experimental hall to date are a one sigma momentum spread of 5{times}10{sup -5} and an rms emittance of 0.2 nanometer-radians, better than design specification. CW beam has been provided from all 5 passes at 800 MeV intervals. Outstanding performance of the superconducting linacs suggests a machine energy upgrade to 6 GeV in the near term with eventual machine operation at 8-10 GeV. Results from commissioning and operations experience since the last conference are presented.

Legg, R.

1996-07-01T23:59:59.000Z

392

Extending quantum operations  

SciTech Connect

For a given set of input-output pairs of quantum states or observables, we ask the question whether there exists a physically implementable transformation that maps each of the inputs to the corresponding output. The physical maps on quantum states are trace-preserving completely positive maps, but we also consider variants of these requirements. We generalize the definition of complete positivity to linear maps defined on arbitrary subspaces, then formulate this notion as a semidefinite program, and relate it by duality to approximative extensions of this map. This gives a characterization of the maps which can be approximated arbitrarily well as the restriction of a map that is completely positive on the whole algebra, also yielding the familiar extension theorems on operator spaces. For quantum channel extensions and extensions by probabilistic operations we obtain semidefinite characterizations, and we also elucidate the special case of Abelian inputs or outputs. Finally, revisiting a theorem by Alberti and Uhlmann, we provide simpler and more widely applicable conditions for certain extension problems on qubits, and by using a semidefinite programming formulation we exhibit counterexamples to seemingly reasonable but false generalizations of the Alberti-Uhlmann theorem.

Heinosaari, Teiko [Turku Centre for Quantum Physics, Department of Physics and Astronomy, University of Turku (Finland); Jivulescu, Maria A. [Department of Mathematics, University Politehnica Timisoara, 300006 Timisoara (Romania); Reeb, David; Wolf, Michael M. [Department of Mathematics, Technische Universitaet Muenchen, 85748 Garching (Germany)

2012-10-15T23:59:59.000Z

393

Mobile marine operations structure  

SciTech Connect

This patent describes the process of installing a marine operations structure in a pre-determined sea floor location. The structure has a central core and a support base having at least two differently sloped ice wall surfaces for achieving fracturing of ice features, and having at least two series of circumferentially arranged ballast tanks. It consists of positioning the structure over a selected sea floor location by the use of at least three tug boats connected to the structure by tension cables arranged radially with respect to the structure; flooding a first series of lower ballast tanks in a sequential ballasting operation; flooding a second series of ballast tanks located at a higher elevation within the structure than the first series of ballast tanks; maintaining radial forces along the tension cables during the flooding steps; and after the structure has become founded on the bottom of the sea, pumping sea waver into fluid tanks some of which are located at an elevation above the water level.

Bhalaik, A.; Braddick, P.W.; Brittin, D.S.; Johnson, G.L.

1987-09-22T23:59:59.000Z

394

Training Work Group Charter | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Training Work Group Charter Training Work Group Charter The Training Work Group fosters improvements in the quality, efficacy, and delivery of DOE safety training, and realizes...

395

NREL: Transmission Grid Integration - Working With Us  

NLE Websites -- All DOE Office Websites (Extended Search)

Working With Us NREL works with industry, government, and academia on transmission integration research. Learn how you can work with us. Develop Technology Partnerships There are a...

396

Undergraduate Program Time Limits and Work Schedules  

NLE Websites -- All DOE Office Websites (Extended Search)

Time Limits and Work Schedules Undergraduate Program Time Limits and Work Schedules Point your career towards LANL: work with the best minds on the planet in an inclusive...

397

Derivative Works | Scientific and Technical Information Program  

Office of Scientific and Technical Information (OSTI)

works are those based on one or more already existing works, This includes any work in which the editorial revisions, annotations, elaborations, or other modifications,...

398

Categorical Exclusion for Maintenance Work  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Maintenance Work Maintenance Work along the Electrical District 5 to Saguaro segment (41/4 to 58/5) of the Maricopa-Saguaro 115-kV Transmission Line, between Friendly Comers and Marana, Pinal County, Arizona RECORD OF CATEGORICAL EXCLUSION DETERMINATION A. Proposed Action: Western plans to conduct maintenance work to maintain or improve the reliability and safety of electrical transmission along 17 miles of the Test Track (formerly Maricopa)-Saguaro 115-kV Transmission Line between Electrical District 5 and Saguaro Steam Plant Substations. The work includes replacing wood poles, cross arms, and knee braces in-kind at 27 structures (41/4-8, 4214, 43/6, 4417, 45/4,46/6,47/2,49/2,49/6,50/2,50/6,50/8,51/4, 52/3, 54/3, 5517, 56/1 57/1-3, 57/8 & 58/2-3), because the wood poles failed stability tests, cross arms are beyond

399

FINAL Announcement International Brainstorming Work-  

E-Print Network (OSTI)

, though in an energy in-efficient way. Organic MSW is identified as one of the potential sources of biomass energy. Biomass is a renewable resource that has a steady and abundant supply, especially thoseFINAL Announcement 1st International Brainstorming Work- shop on Waste to Energy in India Organized

Hone, James

400

http://bellview/TeamWorks/TRUTeamWorks.htm  

NLE Websites -- All DOE Office Websites (Extended Search)

| NRC Officials Visit WIPP Tod | NRC Officials Visit WIPP Tod A weekly e-newsletter for the Waste Isolation Pilot Plant team September 25, 2003 The Big Story Recertification - a work in progress Topics Characterization News Transportation News Disposal News Safety News Working Smart Announcements Our Team Tools Acronym List Archives Back to Main Page WIPP Home Page Links Feedback Contact us with feedback or submit your e-mail address for updates. Click here to e-mail. WIPP Shipments (as of 9-25-03 at 7:16 a.m.) 21 Shipments scheduled to arrive at WIPP this week 2,044 Total shipments received at WIPP Without EPA approval, WIPP could not have received the first waste shipment in 1999. In 1998, EPA cleared the way for TRU waste disposal when it certified that the WIPP repository would safely contain

Note: This page contains sample records for the topic "operation 1943-1944 working" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


401

Live Working Rope Selection Guide  

Science Conference Proceedings (OSTI)

Fiber ropes are an essential tool in many applications associated with the electric power industry. Ropes used in proximity to or in contact with high-voltage power lines require demanding dielectric properties as well as mechanical strength and durability. A comprehensive understating of rope construction, performance, and use is necessary for safe and efficient operations with ropes wherever they are used. This report describes the various types of fiber ropes and their characteristics and provides gui...

2007-11-29T23:59:59.000Z

402

Fuel Cell Technologies Office: High Temperature Membrane Working Group  

NLE Websites -- All DOE Office Websites (Extended Search)

High Temperature Membrane Working Group High Temperature Membrane Working Group The High Temperature Membrane Working Group consists of government, industry, and university researchers interested in developing high temperature membranes for fuel cells. Description Technical Targets Meetings Contacts Description Polymer electrolyte membrane (PEM) fuel cells typically operate at temperatures no higher than 60°C-80°C due to structural limitations of the membrane. Operating PEM fuel cell stacks at higher temperatures (120°C for transportation and 150°C for stationary applications), however, would yield significant energy benefits. For example, heat rejection is easier at higher temperatures, which would allow use of smaller heat exchangers in fuel cell power systems. In addition, for reformate fuel cell systems, carbon monoxide (CO) tolerance of the stack is less problematic at higher temperatures, which would reduce the size requirements or possibly eliminate the need for some CO clean-up beds in the fuel processor.

403

Differences Between Monthly and Weekly Working Gas In Storage  

Weekly Natural Gas Storage Report (EIA)

December 19, 2013 December 19, 2013 Note: The weekly storage estimates are based on a survey sample that does not include all companies that operate underground storage facilities. The sample was selected from the list of storage operators to achieve a target standard error of the estimate of working gas in storage which was no greater than 5 percent for each region. Based on a comparison of weekly estimates and monthly data from May 2002 through September 2013, estimated total working gas stocks have exhibited an average absolute error of 16 billion cubic feet, or 0.6 percent. Background The Energy Information Administration (EIA) provides weekly estimates of working gas volumes held in underground storage facilities at the national and regional levels. These are estimated from volume data provided by a

404

Differences Between Monthly and Weekly Working Gas In Storage  

Weekly Natural Gas Storage Report (EIA)

November 7, 2013 November 7, 2013 Note: The weekly storage estimates are based on a survey sample that does not include all companies that operate underground storage facilities. The sample was selected from the list of storage operators to achieve a target standard error of the estimate of working gas in storage which was no greater than 5 percent for each region. Based on a comparison of weekly estimates and monthly data from May 2002 through August 2013, estimated total working gas stocks have exhibited an average absolute error of 16 billion cubic feet, or 0.6 percent. Background The Energy Information Administration (EIA) provides weekly estimates of working gas volumes held in underground storage facilities at the national and regional levels. These are estimated from volume data provided by a

405

Development of New Biphasic Metal Organic Working Fluids for Subcritical  

Open Energy Info (EERE)

Biphasic Metal Organic Working Fluids for Subcritical Biphasic Metal Organic Working Fluids for Subcritical Geothermal Systems Geothermal Lab Call Project Jump to: navigation, search Last modified on July 22, 2011. Project Title Development of New Biphasic Metal Organic Working Fluids for Subcritical Geothermal Systems Project Type / Topic 1 Laboratory Call for Submission of Applications for Research, Development and Analysis of Geothermal Technologies Project Type / Topic 2 Working Fluids for Binary Power Plants Project Description In binary-cycle plants the cycle efficiency improves as pumping energy is reduced and from maximizing the enthalpy gain of the working fluid for a given amount of heat extracted from the geothermal source brine. Enthalpy gain of the working fluid in the heat exchanger occurs principally from sensible heat gained while passing through the heat exchanger in the liquid state and from vaporization of the organic working fluid near the exit of the heat exchanger. Additional heat transfer is limited after the vapor phase transition due the low thermal conductivity and heat capacity of the vapor. Also, operating pressures and temperatures are constrained by the bulk phase behavior and thermodynamic properties of the working fluid (boiling point, latent heat of vaporization, density, heat capacity, etc.). The fundamental underlying goal of this project is to overcome the cycle efficiency limitations imposed by the bulk thermodynamic proper-ties of the working fluid by introducing a metal-organic heat carrier (MOHC) into the system.

406

DOE-Idaho Operations Summary For June 15 to July 5, 2010  

NLE Websites -- All DOE Office Websites (Extended Search)

3, 2010. Idaho Cleanup Project Nothing to report. Operational Summary Decontamination and Decommissioning Work: At the Idaho Nuclear Technology and Engineering Center, the last...

407

Investigation of several critical issues in screen mesh heat pipe manufacturing and operation.  

E-Print Network (OSTI)

??The PhD thesis with the title Investigation of several critical issues in screen mesh heat pipe manufacturing and operation presented hereafter describes work carried out (more)

Engelhardt, Andreas

2010-01-01T23:59:59.000Z

408

Pacific Northwest National Laboratory Operated  

Office of Legacy Management (LM)

Pacific Pacific Northwest National Laboratory Operated by Battelle for the U .S. D ep artm ent of Energy PNWD-3914 Monticello Mill Tailings Site Macroinvertebrate Sampling for 2007 A.L. Bunn R.P. Mueller J.M. Brandenberger D .M. Wellman February 2008 Prepared for the U.S. Department of Energy under Contract DE-AC13-02GJ79491 DISCLAIMER This repon was prepared as an accoun t of work sponsored by an agency of the United States Government. Neither the United States Government nor any agency thereo f, no r Battelle Memorial Institute, no r any of their employees, makes an y warranty, express or implie d, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, ap paratus, produ ct, or p roce ss di sclos ed, or represen ts that its use would not in frin ge privat ely owned rights . Reference herein to any specific comm ercial product, process,

409

TYPE OF OPERATION  

Office of Legacy Management (LM)

Owner c:ontacted Owner c:ontacted TYPE OF OPERATION ----------------_ jJ Research & Development 0 Production scale testing Cl Pilot Scale 0 Bench Scale Process i Theoretical Studies Sample & Analysis B Production 0 Disposal/Storage $r Prime 0 Subcontract& 0 Purchase Order 0 Facility Type 0 Manufacturing 0 University 0 Research Organization a Other information (i.e., cost + fixed fern, unit price,' time & mate ~r~~-r~~tf~-_~_-_~-~f-~~J~ d ial, etc)_kl/Jlfits ---- -7---- -- Contract/Purchase Order # w?@7-e?-b $ 6, i;,_~~~~~----------------- - ----- C_O!!IF!KXYE-PEELEg: -lTlL-/L?~J --------------------------- OWNERSHXP: AEWHEC AEC/HED' GOVT GB' JT SiXiRACTOR CONiRkCiGR WEE LEAs_EE a!!!%? IEEE!? --------_ ..---LEASED ._ OWNED LANDS BUILDINGS EQUIPMENT

410

GARS Operations Newsletter G  

NLE Websites -- All DOE Office Websites (Extended Search)

1 1 GARS Operations Newsletter G l o b a l a n d R e g i o n a l S o l u t i o n s D i r e c t o r a t e V OLUME 2 , ISSUE 1 Safety Solutions and Pollution Prevention Proposals Congratulations to Barbara Roland of the Nonproliferation and National Security Dept.! Barbara's Safety Solution proposal has been funded. To improve personnel safety in Building 197 during emergency situations, she suggested that pathway markers be positioned on the hallway walls to help locate the Indoor Assembly Areas and Evacuation routes. Light mo- tion detectors for "common areas" in several of our buildings was also funded. This idea sprung from a suggestion received during our Director- ate Safety Stand Down in 2009. This will improve safety and conserve energy too. Remember to send us your suggestions for next year!

411

TYPE OF OPERATION  

Office of Legacy Management (LM)

OWNEF? (S) OWNEF? (S) Current: ____ LcrcJksLG! _________ Owner contacted n yes WI-IO; if yes, date contacted-- TYPE OF OPERATION ----_-------_---- m Research & Development Cl Pilot Scale Cl Disposal/Storaqe TYPE OF CDNTRACT ---__------__--- q Prime 0 Subcnntractor Cl Purchase Order 0 Other infcrmation (i.e., cnst + fixed fee, unit price, time 84 materi+, e.tc) v-7Y07-&G-W ---------------------------- Contract/Pur&aae Order # 0 -?+7- FJc-(CL --___--------~----_______________ CONTRACTING PEXIOD: fl& ,&I;'"'-?;': (&e-?)_-- ' ------------------ OWNERSHIP: AEC/MED GEC/MED SOVT GOVT CONTRACTOR CCNTRACTOR OWNE3 LEASE3 OWNE3 LEASED OWNE3 ----- ------ ----- ------ -__------- LE.352 LANDS u u q BUILDINGS EQUIPMENT 0 FINAL PRODUCT WASTE G RESIDUE a

412

TYPE OF OPERATION  

Office of Legacy Management (LM)

3!NEEi_S1 3!NEEi_S1 past: -~~~-~~~~~-~~~---------- current: ------------_------------- Owner contacted q yes g no; if ye=, date contacted TYPE OF OPERATION --~~__--~-~~~---- 5 Research & Development 5 Facility Type 0 Production scale testing c1 Pilot Scale 0 Bench Scale Process z Theareti cal Studi es Sample Sr Analysis 0 Production D Disposal/Storage TYPE OF CONTRACT ---------------- 0 Manufacturing 0 University 0 Research Clrganization B Government Cpanaored Faci 1 i ty 0 Other ~~---~~---_--~~-----_ a Prime 13 Subcontract& D PurcSase Order 0 Other information (i.e., cost + fixed fee, unit price, time & material, +z) ----_----------------------- Cantract/Purchaae Order #-d-z=&-/) -2_7~-------------Is_------------ PERIOD: CONTRACTING I%~(?) - 1465

413

Albuquerque Operations Office  

Office of Legacy Management (LM)

%r © J~4 %r © J~4 aDepartment of Energy Albuquerque Operations Office P.O. Box 5400 Albuquerue. New Mexico 87118 JUIl 0 198 Vicinity Property No. CA-401 _ U l Address; Mayer Street Bridgeville, Pennsylvania Cyclops Corporation 650 Washington Road Pittsburgh, Pennsylvania 15228 Dear Sir: Under the Uranium Mill Tailings Radiation Control Act of 1978, Public Law 95-604, the Department of Energy (DOE) is authorized to conduct remedial action at properties contaminated with residual radioactive material from inactive uranium mill sites. Evaluation of your property identified above has revealed the presence of residual radioactive material in excess of standards established by the Environmental Protection Agency (EPA). Therefore, your property has been formally included by DOE for remedial action in the Uranium Mill Tailings

414

Operation Diagnostics: Use of Visualization Techniques and Operation  

NLE Websites -- All DOE Office Websites (Extended Search)

Operation Diagnostics: Use of Visualization Techniques and Operation Operation Diagnostics: Use of Visualization Techniques and Operation Patterns to Verify and Optimize Dynamic Building and System Operation Speaker(s): Oliver Baumann Date: December 7, 2004 - 12:00pm Location: Bldg. 90 Seminar Host/Point of Contact: Peng Xu Building automation systems (BAS) and building energy management systems (BEMS) have been used in modern edifices for the last 2 decades. These systems measure, process, and monitor a huge amount of data to operate the building and systems more or less properly. Often, the data is only used to signal failures or break-downs of systems or components. Further information of the data to analyze and diagnose the building operation is not used due to the lack of analysis methods and tools. Within the Operation Diagnostics, different visualization techniques are applied to

415

Top 100 Operators: Proved Reserves and Production, Operated vs...  

Annual Energy Outlook 2012 (EIA)

Total Operators: Roughly 14,000 Natural Gas: 252 Tcf (89% of U.S. Total) Source: U.S. Energy Information Administration Top 100 Operators: Proved Reserves and Production,...

416

Work Control Center Operating Procedure page 1 D-NSTX-OP-AD-129 Rev.OO  

E-Print Network (OSTI)

drawings to be included in the EWP shall be stamped "Approved for Fabrication". (Reference: ENG-OIO. (Reference: ENG·OIO, "Control of Drawings, Software, and Finnware") 10.1.1 RevisedlVoided Drawings: 10

Princeton Plasma Physics Laboratory

417

Report on audit of work force restructuring at the Oak Ridge Operations Office  

SciTech Connect

DOE`s downsizing goals were achieved at Oak Ridge without resorting to involuntary terminations; voluntary separations and worker transfers negated the need for layoffs and associated worker assistance programs. Nevertheless, Lockheed Martin Energy Systems, Inc., established training programs and an outplacement center which was felt by IG to provide little benefit to displaced workers or the Oak Ridge region, because DOE was not adequately involved in preparing the restructuring plans and did not curtail training/outplacement funding when expected layoffs did not materialize. Thus, DOE unnecessarily spent $8.2 M in FYs 1993 and 1994. In addition, substantial lobbying activity was found under a grant to an Oak Ridge advocacy group. Management did not concur with the above findings.

1995-08-03T23:59:59.000Z

418

U.S. CMS - U.S. CMS @ Work - Data and Computing - Facility Operations...  

NLE Websites -- All DOE Office Websites (Extended Search)

) Purpose: Home areas, area small quota (2GB), backed up to tape Stats sorted by usage Stats sorted by quota limit set Stats sorted by percentage of limit used Data Areas There...

419

U.S. CMS - U.S. CMS @ Work - Data and Computing - Facility Operations...  

NLE Websites -- All DOE Office Websites (Extended Search)

File Transfer Batch Systems CRAB Quota and Usage Statistics CERN Bluearc Quota and Stats System Status U.S. CMS Grid CERN Bluearc Quota and Usage Statistics The Tier 1...

420

U.S. CMS - U.S. CMS @ Work - Data and Computing - Facility Operations...  

NLE Websites -- All DOE Office Websites (Extended Search)

tas Purpose: Dedicated space for the TAS project; not backed up Stats sorted by usage Stats sorted by quota limit set Stats sorted by percentage of limit used mit Purpose:...

Note: This page contains sample records for the topic "operation 1943-1944 working" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


421

U.S. CMS - U.S. CMS @ Work - Data and Computing - Facility Operations...  

NLE Websites -- All DOE Office Websites (Extended Search)

File Transfer Batch Systems CRAB Quota and Usage Statistics CERN Bluearc Quota and Stats System Status U.S. CMS Grid Quota Policy and Usage Statistics Tier 1 Facility provides...

422

How do operators monitor a complex, dynamic work domain? The impact of control room technology  

Science Conference Proceedings (OSTI)

Keywords: cognitive engineering, control rooms, human-machine interface, monitoring, nuclear power plants, process control, supervisory control

2001-06-01T23:59:59.000Z

423

U.S. CMS - U.S. CMS @ Work - Data and Computing - Data Operations - Data  

NLE Websites -- All DOE Office Websites (Extended Search)

User Space at US CMS Tier-2 Centers and the FNAL LPC User Space at US CMS Tier-2 Centers and the FNAL LPC Overview When running jobs on large amounts of data, many users will need to write output files of substantial size -- larger than can be accommodated by the grid output sandbox. Additionally, it can be very useful to write this output in a way that it can be read back in easily by subsequent grid jobs. CMS has a mechanism for this. Computing sites will support a /store/user area in their storage systems to host user-generated data. CRAB can be instructed to write job outputs to this area through the SRM interface. Through the magic of the grid, no matter where your job actually runs, and no matter where the output is created, the output can be automatically transferred to whatever system is hosting your own /store/user area. Then,

424

U.S. CMS - U.S. CMS @ Work - Detector Maintenance and Operations Subproject  

NLE Websites -- All DOE Office Websites (Extended Search)

HCAL Announcements, Documentation, and Resources HCAL Announcements, Documentation, and Resources Forward Pixels SiTracker ECAL HCAL Endcap Muon System TriDAS (This page last updated August 2000, although the 1997 version of the TDR was added in July 2010.) [See also HCAL web pages at Maryland and Boston.] HCAL Review Documents HCAL Project Organization Chart (13 Kb gif file) [ps: 46 Kb] HCAL Meeting Announcements, Agendas, and Minutes HCAL Technical Design Report HCAL Drawings: 3-D and perspective barrel HCAL views. HCAL Trigger: Calorimeter trigger algorithm specifications. HCAL Display Resources: transparencies, misc. figures, ... HCAL Documents: Technical Proposal, DRDC Notes, and Papers. CMS Technical Notes: HCAL, HCAL-HV. HCAL Page on CMSDOC WWW Server at CERN HCAL HF Document Server from the University of Iowa

425

Will our nuclear weapons work?  

NLE Websites -- All DOE Office Websites (Extended Search)

Will our nuclear weapons work? Will our nuclear weapons work? National Security Science magazine Latest Issue:April 2013 All Issues » submit Supercomputers are essential for assessing the health of the U.S. nuclear stockpile Supercomputers provide assurance by simulating nuclear weapons performance March 25, 2013 Graphic of a missile being tested through computer simulation Los Alamos uses supercomputers to make high-resolution 3D simulations that help to assess the health of nuclear weapons like this B-61 bomb. Contact Managing Editor Clay Dillingham Email The nuclear weapons in the U.S. stockpile were designed and built to be replaced with new designs and builds every 10 to 15 years. These weapons have lived beyond their expected lifespans. Supercomputers provide the high-resolution 3D simulations needed for

426

Substances of Abuse and Work  

NLE Websites -- All DOE Office Websites (Extended Search)

SUBSTANCES OF ABUSE SUBSTANCES OF ABUSE AND WORK Mary L. Doyle, MPH, RN, COHN-5/CM DOE Headquarters January 16, 2002 Americans 12 Years and Older Using Dru s or Alcohol in the Past Month 1915 1995 1999 Substance Abuse in Industry * Drug use - associated with higher rates of )>absenteeism )>injury l> medical care utilization )> involuntary separation l> health care costs * Alcohol use in the workplace associated with l> absenteeism l> performance on specific tasks ::... mixed data on other outcomes Americans Over 12 Years Reporting Lifetime (Ever Used) Drug Use "'.11---------11--------l * Aloobol *Airf.Udruc 50.11---------11--------l * Mari- ODd ........ 40.11---------11----&.---l * Cocaiae *llalaciaogoal * Horoia Substance Abuse and Work

427

Working at ORNL | Careers | ORNL  

NLE Websites -- All DOE Office Websites (Extended Search)

View Open Positions View Open Positions View Postdoctoral Positions Create A Profile Internal applicants please apply here View or update your current application or profile. External applicants Internal applicants Internet Explorer Browser preferred for ORNL applicants. Chrome is not currently supported. For more information about browser compatibility please refer to the FAQs. If you have difficulty using the online application system or need an accommodation to apply due to a disability, please email ORNLRecruiting@ornl.gov or phone 1-866-963-9545 Careers Home | ORNL | Careers | Working at ORNL SHARE Working at ORNL Community and Culture Here at Oak Ridge National Lab we have over 4,000 employees representing more than 80 different countries. Our employees make a difference in the

428

Visualization and Modeling Working Group  

Science Conference Proceedings (OSTI)

During the 2005 Hurricane season, many consequence predictions were available from 36 to 96 hours before landfalls, via the Department of Energys Visualization and Modeling Working Group (VMWG). Real-time data can be tapped by local officials and utilities, and can also be accessed for post-event regulatory audits. An overview of VMWGs models, results and uses will be presented.

Fernandez, S.J. (LANL); Dodrill, K.A.

2007-03-01T23:59:59.000Z

429

Robotic Technologies for Live Working  

Science Conference Proceedings (OSTI)

This project investigated the feasibility of developing a robotic device for removing and inserting the cotter key on a suspension or deadend insulator string8212the Cotter Key Remover-Installer and Camera (CKRIC). Researchers reviewed EPRI report 1019962, Robotic Technologies for Life Working (2010), and requested input and photographs of insulator strings from project funders. They then prepared animation sequences to study needed motions and degrees of freedom of the device, erected insulator strings ...

2011-12-16T23:59:59.000Z

430

Management and Operating Contractors' Subcontract Audit Coverage, IG-0885  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Management and Operating Management and Operating Contractors' Subcontract Audit Coverage DOE/IG-0885 April 2013 U.S. Department of Energy Office of Inspector General Office of Audits and Inspections Department of Energy Washington, DC 20585 April 17, 2013 MEMORANDUM FOR THE SECRETARY FROM: Gregory H. Friedman Inspector General SUBJECT: INFORMATION: Special Report on "Management and Operating Contractors' Subcontract Audit Coverage" BACKGROUND The Department of Energy (Department) employs 28 Management and Operating (M&O) contractors that perform essential mission work under cost reimbursable contracts. To achieve the Department's mission, M&O contractors often utilize the services of subcontractors, which

431

Impact of High Wind Power Penetration on Hydroelectric Unit Operations  

SciTech Connect

The Western Wind and Solar Integration Study (WWSIS) investigated the operational impacts of very high levels of variable generation penetration rates (up to 35% by energy) in the western United States. This work examines the impact of this large amount of wind penetration on hydroelectric unit operations. Changes in hydroelectric unit operating unit patterns are examined for an aggregation of all hydro generators. The cost impacts of maintaining hydro unit flexibility are assessed and compared for a number of different modes of system operation.

Hodge, B. M.; Lew, D.; Milligan, M.

2011-01-01T23:59:59.000Z

432

Office of Inspector General fiscal year 1996 annual work plan  

Science Conference Proceedings (OSTI)

This FY 1996 Office of Inspector General (OIG) Annual Work Plan is a summary and distillation of information contained in annual work plans, and includes audits and inspections that are carried over from FY 1995 as well as audits and inspections scheduled to start during FY 1996. Audits and inspections included in this consolidated OIG Annual Work Plan will be performed by OIG staff. Specialized expertise available through a Certified Public Accounting firm will be used to assist in auditing the Department`s financial statements. As part of the OIG Cooperative Audit Strategy, additional audit coverage of the Department`s programs is provided by internal auditors of the Department`s integrated contractors. Through the Cooperative Audit Strategy, the OIG ensures that the internal auditors satisfy audit standards, provides planning guidance to the internal auditors, coordinates work to avoid duplication, and tracks the work of internal auditors to ensure that needed audits are performed. Applicable portions of the four annual work plans issued for Fiscal Year 1996 by the Deputy/Assistant Inspectors General have been combined to form a major part of this overall OIG Annual Work Plan. Also included are portions of the most recent OIG Semiannual Reports to Congress to give an overview of the OIG`s mission/organization, resource status, and the environment in which the OIG currently operates. The OIG Annual Work Plan also lists ongoing and planned audits and inspections, and it presents investigative statistics which have been previously reported in the two OIG Semiannual Reports to Congress which cover Fiscal Year 1995. Furthermore, included in this work plan are descriptions of several innovations developed by the OIG to streamline its operations and to conserve as much efficiency and economy as possible in a time of resource reductions.

NONE

1995-10-01T23:59:59.000Z

433

LCLS Operating Schedule  

NLE Websites -- All DOE Office Websites (Extended Search)

LCLS Operating Schedule LCLS Operating Schedule August - December 2009 Ver: 2 10/30/09 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M 0000-0800 MD MD MD MD MD 0800-1600 ROD MD AMO ROD MD AMO 1600-2400 MD MD Commissioning MD MD Comm. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W 0000-0800 MD MD MD MD MD MD MD MD MD 0800-1600 MD ROD AMO MD ROD AMO MD ROD AMO MD ROD AMO ROD 1600-2400 MD MD Commissioning MD MD Commissioning MD MD Commissioning MD MD Commissioning MD 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S 0000-0800 MD MD MD MD MD MD MD MD MD 0800-1600 Young MD ROD DiMauro MD ROD Berrah MD ROD Coffee MD ROD Young-II 1600-2400 L018 MD MD L026 MD MD L015 MD MD L027 MD MD L017 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 Su

434

PNNL Electricity Infrastructure Operations Center | Open Energy...  

Open Energy Info (EERE)

Electricity Infrastructure Operations Center Jump to: navigation, search Logo: Electricity Infrastructure Operations Center Name Electricity Infrastructure Operations Center...

435

Hanford Identification (HID) PIA, Richland Operations Office...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Identification (HID) PIA, Richland Operations Office Hanford Identification (HID) PIA, Richland Operations Office Hanford Identification (HID) PIA, Richland Operations Office...

436

Hanford Identification (HID) PIA, Richland Operations Office...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Hanford Identification (HID) PIA, Richland Operations Office Hanford Identification (HID) PIA, Richland Operations Office Hanford Identification (HID) PIA, Richland Operations...

437

Third Northeast Regional Operational Workshop  

Science Conference Proceedings (OSTI)

The Third Northeast Regional Operational Workshop, focusing on hydrometeorology in the northeastern United States, was held 6-7 November 2001 in Albany, New York. Sessions covered cold season events, warm season events, modeling,and operational ...

Eugene P. Auciello

2002-07-01T23:59:59.000Z

438

Closure operators for order structures  

Science Conference Proceedings (OSTI)

We argue that closure operators are fundamental tools for the study of relationships between order structures and their sequence representations. We also propose and analyse a closure operator for interval order structures.

Ryszard Janicki; Dai Tri Man L; Nadezhda Zubkova

2009-09-01T23:59:59.000Z

439

DOE-ID Operations Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

September 10, 2013 DOE-ID Operations Summary For the Period August 12, 2013 through August 26, 2013 EDITOR'S NOTE: The following is a summary of contractor operations at the Idaho...

440

Operations Analysis - Advanced Photon Source  

NLE Websites -- All DOE Office Websites (Extended Search)

9700 S. Cass Avenue Argonne, IL 60439 (630) 252-1148 office (630) 252-5703 FAX gfystro@aps.anl.gov Areas of interest Operator training program development Operations Group Wiki...

Note: This page contains sample records for the topic "operation 1943-1944 working" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


441

Singular operators in multiwavelet bases  

Science Conference Proceedings (OSTI)

We review some recent results on multiwavelet methods for solving integral and partial differential equations and present an efficient representation of operators using discontinuous multiwavelet bases, including the case for singular integral operators. ...

G. Fann; G. Beylkin; R. J. Harrison; K. E. Jordan

2004-03-01T23:59:59.000Z

442

Work Controls Assessment Plan Assessment Plan Assessment plan - Developed By NNSA/Nevada Site Office Facility Representative Division  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

WORK CONTROLS WORK CONTROLS Assessment Plan Developed By NNSA/Nevada Site Office Facility Representative Division Performance Objective: Management should have an established work control process in place with authorized, controlled and documented methods that provide an accurate status of the work to be performed. Criteria: Work planning addresses applicable laws, codes and regulations. Work planning includes operational configuration constraints; material, tool, and manpower requirements; inter-organizational coordination; operational history; special training; safety considerations; hazards protection requirements; post-maintenance testing; quality control requirements; and other considerations as necessary. The work to be accomplished is defined by identifying the existing

443

GARS Operations Newsletter G  

NLE Websites -- All DOE Office Websites (Extended Search)

October, 2011 October, 2011 GARS Operations Newsletter G l o b a l a n d R e g i o n a l S o l u t i o n s D i r e c t o r a t e V OLUME 2 , ISSUE 2 October is National Fire Safety Month Did you know that Fire Prevention Week was established to commemorate the Great Chicago Fire, the tragic 1871 conflagration that killed more than 250 people, left 100,000 homeless, destroyed more than 17,400 structures and burned more than 2,000 acres. The fire began on October 8, but continued into and did most of its damage on October 9, 1871. According to popular legend, the fire broke out after a cow - belonging to Mrs. Catherine O'Leary - kicked over a lamp, setting first the barn, then the whole city on fire. While the Great Chicago Fire was the best-known blaze to start during this fiery two-day stretch,

444

INDEPENDENT ELECTRICITY SYSTEM OPERATOR  

E-Print Network (OSTI)

adopted this Charter as part of its commitment to high standards of corporate governance in pursuing the objects of the IESO set out in the Electricity Act, 1998. This Charter describes the Boards mandate, accountability and composition, and sets out a specific Code of Conduct for the Board. More detailed information about the IESOs corporate governance is set out in the Governance and Structure By-law and in corporate policies, notably the Terms Of Reference for A Director. The activities of the Board and its Committees are formally recorded in minutes of meetings. MANDATE The Board shall supervise the management of the IESOs business and affairs and shall take a leadership role in the development of the IESOs strategic direction. More specifically, the Boards mandate includes: regularly reviewing with Management: the strategic environment, the emergence of new risks and opportunities and the implications for strategic direction; and the establishment and operation of the IESO-administered markets to promote the

unknown authors

2005-01-01T23:59:59.000Z

445

Operational Management | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Management Operational Management Aviation Management Executive Secretariat Energy Reduction at HQ Facilities and Infrastructure Federal Advisory Committee Management Freedom of...

446

Cell Operations and Process Control  

Science Conference Proceedings (OSTI)

Mar 5, 2013 ... Aluminum Reduction Technology: Cell Operations and Process Control Sponsored by: TMS Light Metals Division, TMS: Aluminum Committee

447

Strategies for Sustainable Institute Operations  

Science Conference Proceedings (OSTI)

... 2 ? What we heard and read: ? NNMI RFI Responses to sustainability questions ... Blueprint for Action: Sustainable Operations Outline Page 3. ...

2013-01-23T23:59:59.000Z

448

Idle Operating Total Stream Day  

U.S. Energy Information Administration (EIA) Indexed Site

3 3 Idle Operating Total Stream Day Barrels per Idle Operating Total Calendar Day Barrels per Atmospheric Crude Oil Distillation Capacity Idle Operating Total Operable Refineries Number of State and PAD District a b b 11 10 1 1,293,200 1,265,200 28,000 1,361,700 1,329,700 32,000 ............................................................................................................................................... PAD District I 1 1 0 182,200 182,200 0 190,200 190,200 0 ................................................................................................................................................................................................................................................................................................ Delaware......................................

449

DOE, Invensys Operations Management to Develop, Deploy Operator Training  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

DOE, Invensys Operations Management to Develop, Deploy Operator DOE, Invensys Operations Management to Develop, Deploy Operator Training System for Supercritical Coal Power Plants DOE, Invensys Operations Management to Develop, Deploy Operator Training System for Supercritical Coal Power Plants December 10, 2012 - 12:00pm Addthis Washington, DC - A new U.S. Department of Energy (DOE) cooperative research and development agreement to develop, test, and deploy a dynamic simulator and operator training system (OTS) could eventually help commercialize important carbon capture technologies at the nation's power plants. The high-fidelity, real-time OTS for a generic supercritical once-through (SCOT) pulverized-coal power plant will be installed at the National Energy Technology Laboratory's (NETL's) Advanced Virtual Energy Simulation

450

Operating Guidelines Narrative.DOC  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Competitive Sourcing Program Operating Guidelines Issued under authority of: Competitive Sourcing Executive Steering Group July 1, 2004 DOE Competitive Sourcing Program OPERATING GUIDELINES (CS-OG-01) i COMPETITIVE SOURCING PROGRAM OPERATING GUIDELINES Table of Contents 1. REFERENCES ................................................................................................................................... 1 2. PURPOSE ........................................................................................................................................... 1 3. APPLICABILITY AND SCOPE ......................................................................................................

451

Operating Guidelines Narrative.DOC  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Competitive Sourcing Program Operating Guidelines Issued under authority of: Competitive Sourcing Executive Steering Group July 1, 2004 DOE Competitive Sourcing Program OPERATING GUIDELINES (CS-OG-01) i COMPETITIVE SOURCING PROGRAM OPERATING GUIDELINES Table of Contents 1. REFERENCES ................................................................................................................................... 1 2. PURPOSE ........................................................................................................................................... 1 3. APPLICABILITY AND SCOPE ......................................................................................................

452

Operating Reserves and Variable Generation  

DOE Green Energy (OSTI)

This report tries to first generalize the requirements of the power system as it relates to the needs of operating reserves. It also includes a survey of operating reserves and how they are managed internationally in system operations today and then how new studies and research are proposing they may be managed in the future with higher penetrations of variable generation.

Ela, E.; Milligan, M.; Kirby, B.

2011-08-01T23:59:59.000Z

453

An Operating Raphael A. Finkel  

E-Print Network (OSTI)

An Operating Systems Vade Mecum Raphael A. Finkel University of Wisconsin at Madison Prentice Hall'') is a laboratory manual that guides the student step by step through complex procedures. Operating systems in operating systems at the undergraduate level. The subject has so many individual parts that its

Finkel, Raphael

454

Transportation External Coordination Working Group:  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Accomplishments and Future Accomplishments and Future Transportation External Coordination Working Group Meeting Phoenix, AZ Judith A. Holm, Office of National Transportation Office of Civilian Radioactive Waste Management April 4, 2005 TEC MEMBER ORGANIZATIONS American College of Emergency Physicians (ACEP) American Nuclear Society (ANS) Association of American Railroads (AAR) Brotherhood of Locomotive Engineers and Trainmen (BLET) Commercial Vehicle Safety Alliance (CVSA) Conference of Radiation Control Program Directors, Inc. (CRCPD) Council of Energy Resource Tribes (CERT) Council of State Governments-Eastern Regional Conference (CSG-ERC) Council of State Governments-Midwestern Office (CSG-MW) Council on Radionuclides and Radiopharmaceuticals (CORAR) Dangerous Goods Advisory Council (DGAC)

455

Transportation External Coordination Working Group:  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

External Coordination External Coordination Working Group: Background and Process Judith Holm National Transportation Program Albuquerque, New Mexico April 21, 2004 TEC History * DOE's Office of Environmental Management (EM) and Office of Civilian Radioactive Waste Management (OCRWM) formed TEC in 1992 * EM & RW developed MOU and TEC charter in 1992 - Other DOE program offices joined in 1993-94 * Other agencies (DOT, FRA, NRC, EPA) have been active participants Meeting Locations 1992-present Some Founding Principles * TEC concept centered on unique stakeholder accountability principles - Participation by key responsible parties in technical/policy issue discussion and resolution results in increased confidence and more efficient business decisions * Ultimate goal: develop multi-year set of

456

QuarkNet at Work  

NLE Websites -- All DOE Office Websites (Extended Search)

QuarkNet at Work Information for Active Mentors & Teachers     QuarkNet Home - Information - Calendar - Contacts - Projects - Forms: EoI - Teachers Information Active Centers Calendar Contacts Expectations: for Teachers, for Mentors Information on Other Funding Sources Program Overview Support: for Teachers, for Centers Staff Job Description Activities Essential Practices - Teaching with Inquiry (word.doc) Classroom Activities e-Labs: CMS - Cosmic Ray Boot Camp Project Activities Databases: Data Entry (password only) 2012 Center Reporting Resources Important Findings from Previous Years Mentor Tips Associate Teacher Institute Toolkit Print Bibliography - Online Resources Imaging Detector Principles of Professionalism for Science Educators - NSTA position

457

Working group 1: Coronal streamers  

SciTech Connect

The working group on colonel streamers convened on the first day of the 2nd SOHO Workshop, which took place in Marciana Marina, Isola d`Elba, 27 September--1 October 1993. Recent progress in streamer observational techniques and theoretical modeling was reported. The contribution of streamers to the mass and energy supply for the solar wind was discussed. Moreover, the importance of thin electric current sheets for determining both the gross dynamical properties of streamers and the fine-scale filamentary structure within streamers, was strongly emphasized. Potential advances to our understanding of these areas of colonel physics that could be made by the contingent of instruments aboard SOHO were pointed out.

Kopp, R.A.

1994-04-01T23:59:59.000Z

458

http://bellview/TeamWorks/TRUTeamWorks.htm  

NLE Websites -- All DOE Office Websites (Extended Search)

16/03 16/03 | Shipments expected this week: ANL-E (2) , RFETS (11), SRS (6) | A weekly e-newsletter for the Waste Isolation Pilot Plant team October 16, 2003 The Big Story EM-6 to review WIPP baseline Topics Characterization News Transportation News Disposal News Safety News Working Smart Announcements Our Team Tools Acronym List Archives Back to Main Page WIPP Home Page Links Feedback Contact us with feedback or submit your e-mail address for updates. Click here to e-mail. WIPP Shipments (as of 10/16/03 at 7:05 a.m.) Shipments scheduled to arrive at WIPP this week 19 Total shipments received at WIPP 2,095 A team from the DOE Office of Project Management, EM-6, will be on site next week to review the WIPP baseline and the integration of that baseline with the National TRU

459

http://bellview/TeamWorks/TRUTeamWorks.htm  

NLE Websites -- All DOE Office Websites (Extended Search)

3/03 3/03 | Shipments expected this week: RFETS (11), SRS (4), Hanford (2) | A weekly e-newsletter for the Waste Isolation Pilot Plant team October 23, 2003 Sealed sources: questions and answers Topics Characterization News Transportation News Disposal News Safety News Working Smart Announcements Our Team Tools Acronym List Archives Back to Main Page WIPP Home Page Links Feedback Contact us with feedback or submit your e-mail address for updates. Click here to e-mail. WIPP Shipments (as of 10/23/03 at 7:06 a.m.) Shipments scheduled to arrive at WIPP this week 17 Total shipments received at WIPP 2,115 Sealed sources have been a topic of discussion lately. Here are answers to some of the questions raised by this topic:

460

http://bellview/TeamWorks/TRUTeamWorks.htm  

NLE Websites -- All DOE Office Websites (Extended Search)

Thursday, 9/11/03 | Total shipments received at WIPP: 2003 | Shipments expected this Thursday, 9/11/03 | Total shipments received at WIPP: 2003 | Shipments expected this A weekly e-newsletter for the Waste Isolation Pilot Plant team September 11, 2003 The Big Story 2003 in 2003 Topics Characterization News Transportation News Disposal News Safety News Working Smart Announcements Our Team Tools Acronym List Archives Back to Main Page WIPP Home Page Links Feedback Contact us with feedback or submit your e-mail address for updates. Click here to e-mail. WIPP Shipments (as of 9-11-03 at 10 a.m.) 21 Shipments scheduled to arrive at WIPP this week 2,003 Total shipments received at WIPP The 2003 rd waste shipment arrived at the WIPP site today (Thursday, September 11) from Hanford. It is highly fitting that

Note: This page contains sample records for the topic "operation 1943-1944 working" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


461

file://\\Bellview\TeamWorks\TRUTeamWorks.PDF  

NLE Websites -- All DOE Office Websites (Extended Search)

Total shipments received at WIPP as of 8-25-03: 1,956 | Shipments expected this week: Hanford Total shipments received at WIPP as of 8-25-03: 1,956 | Shipments expected this week: Hanford A weekly e-newsletter for the Waste Isolation Pilot Plant team August 25, 2003 The Big Story INEEL drum fire and Senate Bill S. 1424: questions and answers Topics Characterization News Transportation News Disposal News Safety News Working Smart Announcements Our Team Tools Acronym List Archives WIPP Home Page Links Feedback Contact us with feedback or submit your e-mail address for updates. Click here to e -mail. WIPP Shipments (as of 8-25-03) 19 Shipments scheduled to arrive at WIPP this week 1,956 Total shipments received at WIPP Some recent media coverage has created some confusion in the public about the

462

Method and apparatus for removing non-condensible gas from a working fluid in a binary power system  

DOE Patents (OSTI)

Apparatus for removing non-condensible gas from a working fluid utilized in a thermodynamic system comprises a membrane having an upstream side operatively connected to the thermodynamic system so that the upstream side of the membrane receives a portion of the working fluid. The first membrane separates the non-condensible gas from the working fluid. A pump operatively associated with the membrane causes the portion of the working fluid to contact the membrane and to be returned to the thermodynamic system.

Mohr, Charles M. (Idaho Falls, ID); Mines, Gregory L. (Idaho Falls, ID); Bloomfield, K. Kit (Idaho Falls, ID)

2002-01-01T23:59:59.000Z

463

How Power Marketing Administrations Market Power and Work with Tribes  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

How Power Marketing Administrations Market Power and Work with How Power Marketing Administrations Market Power and Work with Tribes Webinar How Power Marketing Administrations Market Power and Work with Tribes Webinar April 24, 2013 11:00AM MDT Webinar The U.S. Department of Energy (DOE) Office of Indian Energy Policy and Programs, Office of Energy Efficiency and Renewable Energy Tribal Energy Program, and Western Area Power Administration (WAPA) are pleased to continue their sponsorship of the Tribal Renewable Energy Webinar Series. The country's federal Power Marketing Administrations (PMAs) have valuable generation and transmission assets and have the potential to promote renewable energy development within their respective footprints. Get information on PMA assets and operations, examples of past cooperation with Tribes, and how to work with PMAs to promote future economic growth

464

WORKING PARK-FUEL CELL COMBINED HEAT AND POWER SYSTEM  

DOE Green Energy (OSTI)

This report covers the aims and objectives of the project which was to design, install and operate a fuel cell combined heat and power (CHP) system in Woking Park, the first fuel cell CHP system in the United Kingdom. The report also covers the benefits that were expected to accrue from the work in an understanding of the full technology procurement process (including planning, design, installation, operation and maintenance), the economic and environmental performance in comparison with both conventional UK fuel supply and conventional CHP and the commercial viability of fuel cell CHP energy supply in the new deregulated energy markets.

Allan Jones

2003-09-01T23:59:59.000Z

465

EMSL 2008 Operational Review  

SciTech Connect

The William R. Wiley Environmental Molecular Sciences Laboratory (EMSL) is a national user facility that contains state-of-the-art instrumentation and expert resources available for use by researchers from academia, industry, and the national laboratory system. The facility is supported by the U.S. Department of Energys (DOE) Biological and Environmental Research Program, but the research conducted within the facility benefits many funding agencies, including other branches of DOE, the National Institutes of Health, the National Science Foundation, and the Department of Defense. EMSL requires the continued funding and support of its stakeholders and clients to continue to grow its mission, build its reputation as a sought-after national user facility with cutting-edge capabilities, and attract high-profile users who will work to solve the most critical scientific challenges that affect DOE and the nation. In this vein, this document has been compiled to provide these stakeholders and clients with a review document that provides an abundance of information on EMSLs history, current research activities, and proposed future direction.

Campbell, Allison A.

2008-08-12T23:59:59.000Z

466

How the Artificial Retina Works  

NLE Websites -- All DOE Office Websites (Extended Search)

the Artificial Retina Works the Artificial Retina Works Artificial Retina Diagram Normal vision begins when light enters and moves through the eye to strike specialized photoreceptor (light-receiving) cells in the retina called rods and cones. These cells convert light signals to electric impulses that are sent to the optic nerve and the brain. Retinal diseases like age-related macular degeneration and retinitis pigmentosa destroy vision by annihilating these cells. With the artificial retina device, a miniature camera mounted in eyeglasses captures images and wirelessly sends the information to a microprocessor (worn on a belt) that converts the data to an electronic signal and transmits it to a receiver on the eye. The receiver sends the signals through a tiny, thin cable to the microelectrode array, stimulating it to emit pulses. The artificial retina device thus bypasses defunct photoreceptor cells and transmits electrical signals directly to the retina's remaining viable cells. The pulses travel to the optic nerve and, ultimately, to the brain, which perceives patterns of light and dark spots corresponding to the electrodes stimulated. Patients learn to interpret these visual patterns.

467

Electrochromic Glazings: How they Work  

NLE Websites -- All DOE Office Websites (Extended Search)

How they Work How they Work Electrochromic glazings have great potential to improve the energy efficiency and occupant comfort afforded by architectural windows. These smart windows can dynamically control light transmission by windows in buildings, automobiles, and aircraft. Electrochromic glazings are the most significant members of a family of chromogenic light-control technologies that includes large-area dispersed liquid crystals, dispersed particle windows, and photochromic and thermochromic materials. Electrochromic devices represent the most versatile window technology of this type, exhibiting the best combination of switching properties for chromogenic window applications. Electrochromic glazings typically have a change in visible light transmission from 10% to 70%, moderately fast switching times, and low dc power consumption. These glazings have memory, so they only need power to make a change in transmission. Electrochromic technology can be coupled with smart control systems to give constant lighting levels, blending artificial lighting with daylighting for improved building energy efficiency. Energy simulations of office buildings indicate that smart windows with lighting controls in arid climates can provide 30-40% energy savings over conventional windows. Savings are realized in cooling, lighting, and peak utility electric loads. Other benefits include smaller heating, ventilating, and air-conditioning (HVAC) systems and greater thermal and visual comfort.

468

Multimegawatt power sources for commercial space operations  

SciTech Connect

There is a great deal of interest in commercial operation in space today, but very little consideration of where the power to run such an operation is to come from. For any commercial operation in space, the power source, especially those involving kilowatts and megawatts of power, must be considered at the very onset of the venture. The Multimegawatt Space Reactor Program at the Idaho National Engineering Laboratory is working this problem in conjunction with the development of Strategic Defense Initiative needs. The same type of up-front power development program needs to be considered in all discussions associated with commercial development in space. A system developed for a commercial operation in space will most likely be a hybrid system utilizing both electrical and thermal energy. Even if the commercial process consists totally of high power thermal energy usage, there will be a certain amount of electricity required for controls, mass transport, environmental control (if manned), and communications. The optimum system will thus require a great deal of planning and coordination with the development of the commercial process. 2 refs., 4 figs.

Dearien, J.A.; Martinell, J.S.

1988-01-01T23:59:59.000Z

469

Exascale Hardware Architectures Working Group  

Science Conference Proceedings (OSTI)

The ASC Exascale Hardware Architecture working group is challenged to provide input on the following areas impacting the future use and usability of potential exascale computer systems: processor, memory, and interconnect architectures, as well as the power and resilience of these systems. Going forward, there are many challenging issues that will need to be addressed. First, power constraints in processor technologies will lead to steady increases in parallelism within a socket. Additionally, all cores may not be fully independent nor fully general purpose. Second, there is a clear trend toward less balanced machines, in terms of compute capability compared to memory and interconnect performance. In order to mitigate the memory issues, memory technologies will introduce 3D stacking, eventually moving on-socket and likely on-die, providing greatly increased bandwidth but unfortunately also likely providing smaller memory capacity per core. Off-socket memory, possibly in the form of non-volatile memory, will create a complex memory hierarchy. Third, communication energy will dominate the energy required to compute, such that interconnect power and bandwidth will have a significant impact. All of the above changes are driven by the need for greatly increased energy efficiency, as current technology will prove unsuitable for exascale, due to unsustainable power requirements of such a system. These changes will have the most significant impact on programming models and algorithms, but they will be felt across all layers of the machine. There is clear need to engage all ASC working groups in planning for how to deal with technological changes of this magnitude. The primary function of the Hardware Architecture Working Group is to facilitate codesign with hardware vendors to ensure future exascale platforms are capable of efficiently supporting the ASC applications, which in turn need to meet the mission needs of the NNSA Stockpile Stewardship Program. This issue is relatively immediate, as there is only a small window of opportunity to influence hardware design for 2018 machines. Given the short timeline a firm co-design methodology with vendors is of prime importance.

Hemmert, S; Ang, J; Chiang, P; Carnes, B; Doerfler, D; Leininger, M; Dosanjh, S; Fields, P; Koch, K; Laros, J; Noe, J; Quinn, T; Torrellas, J; Vetter, J; Wampler, C; White, A

2011-03-15T23:59:59.000Z

470

Realities of Chiller Plant Operation: Utility Impacts on Owner Operating  

NLE Websites -- All DOE Office Websites (Extended Search)

Realities of Chiller Plant Operation: Utility Impacts on Owner Operating Realities of Chiller Plant Operation: Utility Impacts on Owner Operating Costs and Societal Environmental Issues Speaker(s): Don Aumann Date: March 21, 2000 - 12:00pm Location: Bldg. 90 Seminar Host/Point of Contact: Satkartar K. Kinney Don Aumann, a Senior Consultant from BKi in Oakland, will present an overview of two projects he completed for the electric utility industry. The first, a case study evaluation of a hybrid chiller plant in Jefferson City, Missouri, demonstrates the importance of carefully evaluating the impact of utility rate structures on plant operating costs. The building owner, another engineering consultant, and the local utility representatives were confused by the rates and missed an opportunity to cut chiller-plant operating costs by about 20%, totaling $15,000 per year. In

471

Operators pocket savings with wireline completions  

SciTech Connect

This article points out that the introduction of the side pocket gas lift mandrel in 1950 allowing installation and removal of gas lift valves by wireline, was the birth of wireline operations as they are known today. Prior to the development, use of wireline was limited to setting blanking plugs, shifting sliding sleeves, cutting paraffin, and running bottomhole pressure surveys. But with introduction of the side pocket gas lift mandrel, wireline service units progressed from the ''sidewinder type unit to the modern day hydraulically operated wireline units capable of working at depths to 30,000 ft and beyond. The hydraulic wireline unit's increased power capacity provided the required line pull, line speed and brake horsepower to manipulate a wireline tool string in a fashion that allowed control of downhole production tools.

Anderson, D.

1987-05-01T23:59:59.000Z

472

Hot-Work Tool Steels  

Science Conference Proceedings (OSTI)

Table 9   Recommended heat-treating practices for hot-work tool steels...1600 ? O, A 58??59 6F6 Not rec 845 (pack) 1550 (peak) (p) (p) 196 650??705 (1200??1300) (q) 925??955 (q) 1700??1750 (q) ? O (r) (s) 6F7 845??870 (1550??1600) 670 1240 22 40 260??300 730 (1350) 915 1675 ? A 54??55 6H1 Not rec 845 1550 22 (t) 40 (t) 202??235 760??790 (1400??1450) 900??940 1650??1725 ? A 48??49 6H2...

473

file://\\Bellview\TeamWorks\TRUTeamWorks.htm  

NLE Websites -- All DOE Office Websites (Extended Search)

30/03 Shipments expected this week: RFETS (11), SRS (4), Hanford (2) 30/03 Shipments expected this week: RFETS (11), SRS (4), Hanford (2) A weekly e-newsletter for the Waste Isolation Pilot Plant team October 30, 2003 ARROW-PAK Topics Characterization News Transportation News Disposal News Safety News Working Smart Announcements Our Team Tools Acronym List Archives Back to Main Page WIPP Home Page Links Feedback Contact us with feedback or submit your e-mail address for updates. Click here to e- mail. WIPP Shipments (as of 10/30/03 at 6:59 a.m.) Shipments scheduled to arrive at WIPP this week 17 Total shipments received at WIPP 2,129 You've heard of the TRUPACT-II, the pipe overpack, the RH-72B and even the 10- 160B. But have you heard about the ARROW-PAK? ARROW-PAK is a transportation container designed to contain and transport high-wattage TRU waste.

474

http://bellview/TeamWorks/TRUTeamWorks.htm  

NLE Websites -- All DOE Office Websites (Extended Search)

9/03 | Shipments expected this week: Hanford (1), RFETS (11), SRS (6) | 9/03 | Shipments expected this week: Hanford (1), RFETS (11), SRS (6) | A weekly e-newsletter for the Waste Isolation Pilot Plant team October 9, 2003 The Big Story It's a whole new "WIPP Experience" Topics Characterization News Transportation News Safety News Working Smart Announcements Our Team Tools Acronym List Archives Back to Main Page WIPP Home Page Links Feedback Contact us with feedback or submit your e-mail address for updates. Click here to e- mail. WIPP Shipments (as of 10/9/03 at 7:24 a.m.) Shipments scheduled to arrive at WIPP this week 18 Total shipments received at WIPP 2,081 If you haven't been to the SWB lately, you are in for a big surprise. The lobby sports a new look these days, complete with banners and updated exhibits. And the new look isn't just

475

Potline Operation I: Smelter Operations - Programmaster.org  

Science Conference Proceedings (OSTI)

Mar 5, 2013 ... Low Power Operation at Aluminium Dunkerque Smelter: ... place in the substation and have limited the maximum substation capacity at 285 kA...

476

Formal Specification ofOperating System Operations Dan ...  

Science Conference Proceedings (OSTI)

... ffl The process has privilege PV MAC CL (if ... Function setSLFileEnv models the operation of a process ... To model the arguments that are passed to ...

2013-05-07T23:59:59.000Z

477

Liens for Oil and Gas Operations (Nebraska)  

Energy.gov (U.S. Department of Energy (DOE))

This section contains regulations concerning lien allowances made to operators of oil and gas operations.

478

Chemical damage due to drilling operations  

DOE Green Energy (OSTI)

The drilling of geothermal wells can result in near wellbore damage of both the injection wells and production wells if proper precautions are not taken. Very little specific information on the chemical causes for drilling damage that can directly be applied to the drilling of a geothermal well in a given situation is available in the literature. As part of the present work, the sparse literature references related to the chemical aspects of drilling damage are reviewed. The various sources of chemically induced drilling damages that are related to drilling operations are summarized. Various means of minimizing these chemical damages during and after the drilling of a geothermal well are suggested also.

Vetter, O.J.; Kandarpa, V.

1982-07-14T23:59:59.000Z

479

TeamWorks12-02-04  

NLE Websites -- All DOE Office Websites (Extended Search)

Team TRU Works Works TeamWorks Shipments Scheduled to arrive 120504 - 121104: 28 Hanford - 3 LLNL - 2 NTS - 2 RFETS - 16 SRS - 4 (subject to change) 3,167 total shipments...

480

Graduate Program Time Limits and Work Schedules  

NLE Websites -- All DOE Office Websites (Extended Search)

Time Limits and Work Schedules Graduate Program Time Limits and Work Schedules Point your career towards LANL: work with the best minds on the planet in an inclusive environment...

Note: This page contains sample records for the topic "operation 1943-1944 working" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.