1

Final Report Navajo Transmission Project (NTP)  

SciTech Connect (OSTI)

The Diné Power Authority is developing the Navajo Transmission Project (NTP) to relieve the constraints on the transmission of electricity west of the Four Corners area and to improve the operation flexibility and reliability of the extra-high-voltage transmission system in the region. The NTP creates the wholesale transmission capacity for more economical power transfers, sales, and purchases in the region. It will facilitate the development of Navajo energy resources, improve economic conditions on the Navajo Nation as well as allow DPA to participate in the western electrical utility industry.

Bennie Hoisington; Steven Begay

2006-09-14T23:59:59.000Z

2

EIS-0231: Navajo Transmission Project | Department of Energy  

Broader source: Energy.gov (indexed) [DOE]

31: Navajo Transmission Project 31: Navajo Transmission Project EIS-0231: Navajo Transmission Project SUMMARY This EIS evaluates the environmental impacts of a proposal to by Dine Power Authority, a Navajo Nation enterprise, to construct, operate, and maintain a 500 kilovolt (kV) transmission line planned to deliver electric power from the Four Comers area in northwestern New Mexico across northern Arizona to a terminus in southeastern Nevada. The proposed project, the Navajo Transmission Project, is currentiy planned to be in service in the year 2001 and operate for about 50 years. PUBLIC COMMENT OPPORTUNITIES None available at this time. DOCUMENTS AVAILABLE FOR DOWNLOAD September 1, 1996 EIS-0231: Draft Environmental Impact Statement Draft Environmental Impact Statement Navajo Transmission Project

3

Navajo Transmission Project Draft Environmental Impact Statement (DEIS)  

Broader source: Energy.gov (indexed) [DOE]

. . SUMRY INTRODUCTION Din6 Power Authority @PA), a Navajo Nation enterprise, proposes to construct, operate, and maintain a 500 kilovolt (kV) transmission line planned to deliver electric power from the Four Comers area in northwestern New Mexico across northern Arizona to a terminus in southeastern Nevada. The proposed project, the Navajo Transmission Project ~), is currentiy planned to be in service in the year 2001 and operate for about 50 years. The preparation of an environment impact statement @IS) is required because of Federal government involvement, which includes (1) granting rights-of-way across Federrd and tribal lands and (2) certain participation by Western Area Power Administration ~estem), and agency of the U.S. Department of Energy (DOE). In accordance the National Environmental Policy Act of 1969 ~PA), Council on Environmental Quality (CEQ) regulations

4

Navajo Electrification Demonstraiton Project  

SciTech Connect (OSTI)

This is a final technical report required by DOE for the Navajo Electrification Demonstration Program, This report covers the electric line extension project for Navajo families that currently without electric power.

Larry Ahasteen, Project Manager

2006-07-17T23:59:59.000Z

5

Final Report - Navajo Electrification Demonstration Project - FY2004  

SciTech Connect (OSTI)

The Navajo Electrification Demonstration Project (NEDP) is a multi-year projects which addresses the needs of unserved Navajo Nation residents without basic electricity services. The Navajo Nation is the United States' largest tribe, in terms of population and land. An estimated 18,000 Navajo Nation homes do not have basic grid-tied electricity--and this third year of funding, known as NEDP-3, provided 351 power line extensions to Navajo families.

Kenneth L. Craig, Interim General Manager

2007-03-31T23:59:59.000Z

6

Navajo Tribal Utility Association Smart Grid Project | Open Energy  

Open Energy Info (EERE)

Navajo Tribal Utility Association Smart Grid Project Navajo Tribal Utility Association Smart Grid Project Jump to: navigation, search Project Lead Navajo Tribal Utility Association Country United States Headquarters Location Ft. Defiance, Arizona Additional Benefit Places New Mexico, Utah Recovery Act Funding $4991750 Total Project Value $10611849 Coverage Area Coverage Map: Navajo Tribal Utility Association Smart Grid Project Coordinates 35.7444602°, -109.0764828° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[]}

7

Navajo Marketing Plan Process  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Navajo Surplus Marketing Reference Material Amended Navajo Marketing Plan AZ Water Settlements Act Colorado River Basin Project Act General Power Contract Provisions (GCPC) - 09...

8

Navajo Tribal Utility Authority | Open Energy Information  

Open Energy Info (EERE)

Utility Authority Utility Authority (Redirected from Navajo Tribal Utility Association) Jump to: navigation, search Name Navajo Tribal Utility Authority Place Arizona Utility Id 13314 Utility Location Yes Ownership S NERC Location WECC NERC WECC Yes Activity Transmission Yes Activity Buying Transmission Yes Activity Distribution Yes Activity Buying Distribution Yes Activity Bundled Services Yes Alt Fuel Vehicle Yes Alt Fuel Vehicle2 Yes References EIA Form EIA-861 Final Data File for 2010 - File1_a[1] Energy Information Administration Form 826[2] SGIC[3] LinkedIn Connections CrunchBase Profile No CrunchBase profile. Create one now! This article is a stub. You can help OpenEI by expanding it. Navajo Tribal Utility Association Smart Grid Project was awarded $4,991,750 Recovery Act Funding with a total project value of $10,611,849.

9

Navajo Tribal Utility Authority | Open Energy Information  

Open Energy Info (EERE)

Navajo Tribal Utility Authority Navajo Tribal Utility Authority Place Arizona Utility Id 13314 Utility Location Yes Ownership S NERC Location WECC NERC WECC Yes Activity Transmission Yes Activity Buying Transmission Yes Activity Distribution Yes Activity Buying Distribution Yes Activity Bundled Services Yes Alt Fuel Vehicle Yes Alt Fuel Vehicle2 Yes References EIA Form EIA-861 Final Data File for 2010 - File1_a[1] Energy Information Administration Form 826[2] SGIC[3] LinkedIn Connections CrunchBase Profile No CrunchBase profile. Create one now! This article is a stub. You can help OpenEI by expanding it. Navajo Tribal Utility Association Smart Grid Project was awarded $4,991,750 Recovery Act Funding with a total project value of $10,611,849. Utility Rate Schedules Grid-background.png

10

San Luis Transmission Project  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Luis Transmission Project EIS/EIR Luis Transmission Project EIS/EIR San Luis Transmission Project EIS/EIR Western proposes to construct, own, operate, and maintain a new 230-kilovolt transmission line about 62 miles in length between Western's Tracy Substation and Western's San Luis Substation and a new 70-kV transmission line about 5 miles in length between the San Luis and O'Neill Substations. Western also will consider other transmission construction options including: A new 500-kV transmission line about 62 miles in length operated at 230-kV between Western's Tracy and San Luis Substations; A new 500-kV transmission line operated at 500-kV about 62 miles in length between the Tracy Substation and Pacific Gas and Electric's Los Banos Substation; and A new 230-kV transmission line about 18 miles in length between San Luis Substation and Dos Amigos Substation.

11

NREL: Transmission Grid Integration - Projects  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Projects NREL's transmission integration projects provide data and models that help utilities and policymakers make informed decisions about the integration of variable generation,...

12

Transmission Commercial Project Integration  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Improvement (CBPI) Customer Forum Energy Imbalance Market Generator Interconnection Reform Implementation Network Integration Transmission Service (NT Service) Network Open...

13

EIS-0411: Transmission Agency of Northern California Transmission Project  

Broader source: Energy.gov [DOE]

This EIS is for the Western Area Power Administration construction, operation, and maintenance of the proposed transmission agency of Northern California Transmission Project, California.

14

Regional Transmission Projects: Finding Solutions  

SciTech Connect (OSTI)

The Keystone Center convened and facilitated a year-long Dialogue on "Regional Transmission Projects: Finding Solutions" to develop recommendations that will help address the difficult and contentious issues related to expansions of regional electric transmission systems that are needed for reliable and economic transmission of power within and across regions. This effort brought together a cross-section of affected stakeholders and thought leaders to address the problem with the collective wisdom of their experience and interests. Transmission owners sat at the table with consumer advocates and environmental organizations. Representatives from regional transmission organizations exchanged ideas with state and federal regulators. Generation developers explored common interests with public power suppliers. Together, the Dialogue participants developed consensus solutions about how to begin unraveling some of the more intractable issues surrounding identification of need, allocation of costs, and reaching consensus on siting issues that can frustrate the development of regional transmission infrastructure. The recommendations fall into three broad categories: 1. Recommendations on appropriate institutional arrangements and processes for achieving regional consensus on the need for new or expanded transmission infrastructure 2. Recommendations on the process for siting of transmission lines 3. Recommendations on the tools needed to support regional planning, cost allocation, and siting efforts. List of Dialogue participants: List of Dialogue Participants: American Electric Power American Transmission Company American Wind Energy Association California ISO Calpine Corporation Cinergy Edison Electric Institute Environmental Defense Federal Energy Regulatory Commission Great River Energy International Transmission Company ISO-New England Iowa Public Utility Board Kanner & Associates Midwest ISO National Association of Regulatory Utility Commissioners National Association of State Utility Consumer Advocates National Grid Northeast Utilities PA Office of Consumer Advocates Pacific Gas & Electric Corporation Pennsylvania Public Utility Commission PJM Interconnection The Electricity Consumers Resource Council U.S. Department of Energy US Department of the Interior Van Ness Feldman Western Interstate Energy Board Wind on the Wires Wisconsin Public Service Commission Xcel Energy

The Keystone Center

2005-06-15T23:59:59.000Z

15

SunZia Southwest Transmission Project Comments  

Broader source: Energy.gov (indexed) [DOE]

SunZia Southwest Transmission Project SunZia Southwest Transmission Project Comments Provided to the US Department of Energy Office of Electricity Delivery and Energy Reliability Request for Information Relating to the Permitting of Transmission Lines Submitted as of March 28, 2012 2 1.0 Background. SunZia Southwest Transmission Project (SunZia or the Project) is a joint development effort currently underway in Arizona and New Mexico. The Project definition includes licensing, permitting, financing, constructing and operating up to two 500 kilovolt alternating current (AC) transmission lines and up to five interconnecting substations.

16

Big Bend-Witten Transmission Line Project  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Big Bend-Witten Transmission Line Project The Western Area Power Administration (Western), an agency of the Department of Energy (DOE), has prepared a draft environmental...

17

SunZia Southwest Transmission Project Comments  

Energy Savers [EERE]

Transmission Project Comments Provided to the US Department of Energy Office of Electricity Delivery and Energy Reliability Request for Information Relating to the Permitting...

18

Williston to Stateline Transmission Line Project  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Williston to Stateline Transmission Line Project, ND The Western Area Power Administration (Western), an agency of the Department of Energy (DOE), has prepared an environmental...

19

Grand Coulee Transmission Line Replacement Project  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Grand-Coulee-Transmission-Line-Replacement-Project Sign In About | Careers | Contact | Investors | bpa.gov Search Doing Business Expand Doing Business Customer Involvement Expand...

20

Boardman to Hemingway Transmission Project  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Improvement (CBPI) Customer Forum Energy Imbalance Market Generator Interconnection Reform Implementation Network Integration Transmission Service (NT Service) Network Open...

Note: This page contains sample records for the topic "navajo transmission project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


21

LM Continues to Work with the Navajo Nation | Department of Energy  

Broader source: Energy.gov (indexed) [DOE]

Continues to Work with the Navajo Nation Continues to Work with the Navajo Nation LM Continues to Work with the Navajo Nation January 9, 2013 - 4:00pm Addthis What does this project do? Goal 1. Protect human health and the environment LM continues to work with the Navajo Nation to perform long-term surveillance and maintenance (LTS&M) at four Uranium Mill Tailings Radiation Control Act (UMTRCA) Title I sites located on the Navajo Nation. Compliance activities include monitoring and maintaining engineered disposal cells, as well as remediating groundwater. The Navajo Nation encompasses more than 27,000 square miles in the southwestern United States. Uranium exploration, mining, and milling occurred in the Four Corners area; nearly 4 million tons of uranium ore were extracted from Navajo lands.

22

TransWest Express Transmission Project  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

operate, maintain and decommission the TransWest Express 600-kV Direct Current Transmission Project. TransWest Express, LLC is a whollyowned subsidiary of the Anschutz...

23

"1. Palo Verde","Nuclear","Arizona Public Service Co",3937 "2. Navajo","Coal","Salt River Project",2250  

U.S. Energy Information Administration (EIA) Indexed Site

Arizona" Arizona" "1. Palo Verde","Nuclear","Arizona Public Service Co",3937 "2. Navajo","Coal","Salt River Project",2250 "3. Gila River Power Station","Gas","Gila River Power Station LP",2060 "4. Springerville","Coal","Tucson Electric Power Co",1618 "5. Glen Canyon Dam","Hydroelectric","U S Bureau of Reclamation",1312 "6. Santan","Gas","Salt River Project",1227 "7. Mesquite Generating Station","Gas","Mesquite Power LLC",1073 "8. Harquahala Generating Project","Gas","New Harquahala Generating Co, LLC",1054 "9. Hoover Dam","Hydroelectric","U S Bureau of Reclamation",1040

24

EIS-0502: Hot Springs to Anaconda Transmission Line Rebuild Project...  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

Hot Springs to Anaconda Transmission Line Rebuild Project, Montana EIS-0502: Hot Springs to Anaconda Transmission Line Rebuild Project, Montana SUMMARY DOE's Bonneville Power...

25

EA-1961: Kalispell-Kerr Transmission Line Rebuild Project, Kalispell...  

Energy Savers [EERE]

1: Kalispell-Kerr Transmission Line Rebuild Project, Kalispell and Polson, Montana EA-1961: Kalispell-Kerr Transmission Line Rebuild Project, Kalispell and Polson, Montana SUMMARY...

26

EIS-0499: Great Northern Transmission Line Project, Minnesota...  

Energy Savers [EERE]

EIS-0499: Great Northern Transmission Line Project, Minnesota EIS-0499: Great Northern Transmission Line Project, Minnesota SUMMARY This EIS will evaluate the potential...

27

EA-1891: Alvey-Fairview Transmission Line Rebuild Project, Oregon...  

Broader source: Energy.gov (indexed) [DOE]

1: Alvey-Fairview Transmission Line Rebuild Project, Oregon EA-1891: Alvey-Fairview Transmission Line Rebuild Project, Oregon Summary Bonneville Power Administration prepared an EA...

28

US Recovery Act Smart Grid Projects - Electric Transmission Systems | Open  

Open Energy Info (EERE)

American_Transmission_Company_LLC_II_Smart_Grid_Project\" American_Transmission_Company_LLC_II_Smart_Grid_Project\" title=\"American Transmission Company LLC II Smart Grid Project\">American Transmission Company LLC II Smart Grid Project","title":"American Transmission Company LLC II Smart Grid Project","link":null,"lat":43.0116784,"lon":-88.2314813,"alt":0,"address":"","icon":"","group":"","inlineLabel":"","visitedicon":""},{"text":"Transmission_Company_LLC_Smart_Grid_Project\" title=\"American Transmission Company LLC Smart Grid Project\">American

29

EIS-0325: Schultz-Hanford Area Transmission Line Project, WA  

Broader source: Energy.gov [DOE]

BPA proposes to construct a new 500-kilovolt (kV) transmission line in central Washington. This project would increase transmission system capacity north of Hanford.

30

BPA, Transmission, I-5 Corridor Project, data by segments and...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

alternatives for new transmission system facilities, including the new transmission line and substations proposed for the I-5 Corridor Reinforcement Project. Foremost is...

31

Category:Smart Grid Projects - Electric Transmission Systems | Open Energy  

Open Energy Info (EERE)

Transmission Systems category. Transmission Systems category. Pages in category "Smart Grid Projects - Electric Transmission Systems" The following 10 pages are in this category, out of 10 total. A American Transmission Company LLC II Smart Grid Project American Transmission Company LLC Smart Grid Project D Duke Energy Carolinas, LLC Smart Grid Project E Entergy Services, Inc. Smart Grid Project I ISO New England, Incorporated Smart Grid Project M Midwest Energy Inc. Smart Grid Project Midwest Independent Transmission System Operator Smart Grid Project N New York Independent System Operator, Inc. Smart Grid Project P PJM Interconnection, LLC Smart Grid Project W Western Electricity Coordinating Council Smart Grid Project Retrieved from "http://en.openei.org/w/index.php?title=Category:Smart_Grid_Projects_-_Electric_Transmission_Systems&oldid=214227

32

EIS-0465: Mid-Atlantic Power Pathway Transmission Line Project...  

Broader source: Energy.gov (indexed) [DOE]

5: Mid-Atlantic Power Pathway Transmission Line Project in Maryland and Delaware EIS-0465: Mid-Atlantic Power Pathway Transmission Line Project in Maryland and Delaware March 4,...

33

EA-1896: Williston to Stateline Transmission Line Project, Mountrail  

Broader source: Energy.gov (indexed) [DOE]

96: Williston to Stateline Transmission Line Project, 96: Williston to Stateline Transmission Line Project, Mountrail Williams Electric Cooperative, Williston, North Dakota EA-1896: Williston to Stateline Transmission Line Project, Mountrail Williams Electric Cooperative, Williston, North Dakota Summary DOE's Western Area Power Administration is preparing this EA to evaluate the environmental impacts of interconnecting the proposed Stateline I transmission line, in Williston, North Dakota, to Western's transmission system. Public Comment Opportunities No public comment opportunities available at this time. Documents Available for Download May 4, 2012 EA-1896: Finding of No Significant Impact Williston to Stateline Transmission Line Project, Mountrail Williams Electric Cooperative, Williams County, North Dakota

34

Transmission Bottleneck Project Report. March 19, 2003 | Department of  

Broader source: Energy.gov (indexed) [DOE]

Transmission Bottleneck Project Report. March 19, 2003 Transmission Bottleneck Project Report. March 19, 2003 Transmission Bottleneck Project Report. March 19, 2003 The U.S. Department of Energy (DOE) National Transmission Grid Study (DOE 2002) determined that congestion in the U.S. electricity transmission system places daily constraints on electricity trade, increasing both electricity costs to consumers and impacts reliable operations. In an effort to support DOE's investigation of transmission bottlenecks, the Consortium for Electric Reliability Technology Solutions (CERTS) surveyed the current state of transmission congestion around the nation. Transmission Bottleneck Project Report. March 19, 2003 More Documents & Publications Electricity Transmission Congestion Costs: A Review of Recent Reports 2012 National Electric Transmission Congestion Study: Preliminary Findings

35

EIS-0390: Eastern Plains Transmission Project, Colorado and Kansas.  

Broader source: Energy.gov [DOE]

This EIS is for Western Area Power Administration's proposal to participate with Tri-State Generation and Transmission Association, Inc. (Tri-State), to construct the proposed Eastern Plains Transmission Project (Project). Western’s participation with Tri-State would be in exchange for capacity rights on the transmission lines.

36

Protection of Navajo Sacred Objects  

E-Print Network [OSTI]

. In an article written in the Gallup Independent on Thursday November 15, 2007, state representative Tom Udall stated that there was no cancer on 22 the Navajo reservation before uranium mining. Now there are reports of lung cancer. There is a lot... of information that is not known by the Navajos, such as how many are living near abandoned uranium mines. There are 1,300 abandoned uranium mines across the reservation and more and more people are getting sick without realizing it. 11 Water is sacred...

Yazzie, Elerina

2008-07-31T23:59:59.000Z

37

EIS-0474: Southline Transmission Project, Arizona and New Mexico |  

Broader source: Energy.gov (indexed) [DOE]

4: Southline Transmission Project, Arizona and New Mexico 4: Southline Transmission Project, Arizona and New Mexico EIS-0474: Southline Transmission Project, Arizona and New Mexico Summary The Department of the Interior's Bureau of Land Management (BLM) and Department of Energy's Western Area Power Administration (Western) are preparing this EIS as joint lead agencies to evaluate the environmental impacts of the proposed Southline Transmission Project and address associated potential land use plan amendments. The project would consist of a new 225-mile transmission line between existing substations at Afton, New Mexico, and Apache, Arizona, and improvements to approximately 130 miles of existing transmission lines between the Apache and Saguaro, Arizona substations. Project website: http://www.blm.gov/nm/southline.

38

Wind Integration, Transmission, and Resource Assessment and Characterization Projects  

Broader source: Energy.gov [DOE]

This report covers the Wind and Water Power Program’s Wind Integration, Transmission, and Resource Assessment and Characterization Projects from FY 2006 to FY 2014.

39

BPA, Transmission, I-5 Corridor Reinforcement Project, August...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Power Administration has refined the potential transmission line route segments and substation sites for the proposed I-5 Corridor Reinforcement Project. The refinements are...

40

BPA, Transmission, I-5 Corridor Reinforcement Project Update...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

environmental impact statement (EIS) for our proposed I-5 Corridor Reinforcement Project. BPA is proposing to build a 500-kilovolt transmission line to reinforce the high-voltage...

Note: This page contains sample records for the topic "navajo transmission project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


41

BPA, Transmission, I-5 Corridor Reinforcement Project, presentation...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

About the Project 500-kilovolt transmission New substations at - Castle Rock, Wash. - Troutdale, Ore. 70 miles apart Many route segments 17 Factors we consider Electrical needs for...

42

Wind Integration, Transmission, and Resource Assessment and Characterization Projects  

Broader source: Energy.gov [DOE]

This report covers the Wind and Water Power Technologies Office’s Wind integration, transmission, and resource assessment and characterization projects from fiscal years 2006 to 2014.

43

EA-1960: Townsite Solar Project Transmission Line, Clark County, Nevada |  

Broader source: Energy.gov (indexed) [DOE]

60: Townsite Solar Project Transmission Line, Clark County, 60: Townsite Solar Project Transmission Line, Clark County, Nevada EA-1960: Townsite Solar Project Transmission Line, Clark County, Nevada SUMMARY The Bureau of Land Management, with Western Area Power Administration as a cooperating agency, prepared an EA to evaluate potential impacts of a proposal to build and operate a 180-MW photovoltaic facility; a 220, 230, or 500 kV transmission line; and associated facilities in Clark County, Nevada. PUBLIC COMMENT OPPORTUNITIES None available at this time. DOCUMENTS AVAILABLE FOR DOWNLOAD October 28, 2013 EA-1960: Finding of No Significant Impact Townsite Solar Project Transmission Line, Clark County, Nevada June 28, 2013 EA-1960: Final Environmental Assessment Townsite Solar Project Transmission Line, Clark County, Nevada

44

Mountain States Transmission Intertie (MSTI) Project  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Improvement (CBPI) Customer Forum Energy Imbalance Market Generator Interconnection Reform Implementation Network Integration Transmission Service (NT Service) Network Open...

45

Department of Energy Finalizes Loan Guarantee for New Transmission Project  

Broader source: Energy.gov (indexed) [DOE]

for New Transmission for New Transmission Project to Deliver Renewable Energy to Southwest Department of Energy Finalizes Loan Guarantee for New Transmission Project to Deliver Renewable Energy to Southwest February 15, 2011 - 12:00am Addthis Washington, D.C. -- Energy Secretary Steven Chu today announced that the U.S. Department of Energy has finalized a $343 million loan guarantee, supported by the Recovery Act, to develop the One Nevada Transmission Line, known as the ON Line project. The ON Line project, which is jointly owned by Great Basin Transmission South, LLC and NV Energy, consists of a new 500 kilovolt (kV) AC transmission line that will carry approximately 600 megawatts of electricity, including from renewable energy resources, in northern Nevada. This is the Department's first loan guarantee for a

46

Lovell-Yellowtail transmission line rebuild project, Western Area Power  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Lovell-Yellowtail Transmission Line Rebuild Project Lovell-Yellowtail Transmission Line Rebuild Project Project overview LVYT-1_158_092512 A contractor crew worked out of the bucket truck, Sept. 25, 2012, to perform dead-ending operations as part of phase 1 of the Lovell-to-Yellowtail transmission line rebuild. (Photo by Bob Kemp) See more photos of phase 1 and 2 constuction on Flickr. Western is rebuilding the Lovell-to-Yellowtail No. 1 and No. 2 115-kV transmission lines. The 94-circuit-miles of lines are located between Lovell, Wyo., and Yellowtail Dam, Mont. The rebuilt transmission lines are needed because the original lines were built by the Bureau of Reclamation in 1956 and 1966. The project will: Ensure reliability and safety of the transmission lines Improve capability to transmit full output from Yellowtail

47

Department of Energy Finalizes Loan Guarantee for New Transmission Project  

Broader source: Energy.gov (indexed) [DOE]

Loan Guarantee for New Transmission Loan Guarantee for New Transmission Project to Deliver Renewable Energy to Southwest Department of Energy Finalizes Loan Guarantee for New Transmission Project to Deliver Renewable Energy to Southwest February 15, 2011 - 12:00am Addthis Washington, D.C. -- Energy Secretary Steven Chu today announced that the U.S. Department of Energy has finalized a $343 million loan guarantee, supported by the Recovery Act, to develop the One Nevada Transmission Line, known as the ON Line project. The ON Line project, which is jointly owned by Great Basin Transmission South, LLC and NV Energy, consists of a new 500 kilovolt (kV) AC transmission line that will carry approximately 600 megawatts of electricity, including from renewable energy resources, in northern Nevada. This is the Department's first loan guarantee for a

48

EIS-0447: Champlain Hudson Power Express Transmission Line Project, New  

Broader source: Energy.gov (indexed) [DOE]

7: Champlain Hudson Power Express Transmission Line Project, 7: Champlain Hudson Power Express Transmission Line Project, New York EIS-0447: Champlain Hudson Power Express Transmission Line Project, New York Summary This EIS evaluates the potential environmental impacts of a DOE proposal to grant a Presidential permit to Champlain Hudson Power Express, Inc., to construct, operate, maintain, and connect a new 1000-megawatt (MW) electric transmission system across the U.S.-Canada border in northeastern New York State. The proposed transmission line would run from the Canadian Province of Quebec to New York City. Public Comment Opportunities None available at this time. Documents Available for Download December 6, 2013 EIS-0447: DOE Notice of Availability of Draft Environmental Impact Statement Champlain Hudson Power Express Transmission Line Project, New York

49

Northern Pass Transmission Line Project Environmental Impact Statement:  

Broader source: Energy.gov (indexed) [DOE]

Northern Pass Transmission Line Project Environmental Impact Northern Pass Transmission Line Project Environmental Impact Statement: Announcement of Change in Public Meeting Location: Federal Register Notice Volume 78, No. 181 - September 18, 2013 Northern Pass Transmission Line Project Environmental Impact Statement: Announcement of Change in Public Meeting Location: Federal Register Notice Volume 78, No. 181 - September 18, 2013 DOE has changed the location of the September 26 public scoping meeting for the Northern Pass Transmission Line Project to Colebrook Elementary School, 27 Dumont Street, Colebrook, NH. On September 6, 2013, the U.S. Department of Energy (DOE) published in the Federal Register an amended Notice of Intent (NOI) to modify the scope of the Northern Pass Transmission Line Project Environmental Impact Statement

50

EIS-0478: Antelope Valley Station to Neset Transmission Project, Mercer,  

Broader source: Energy.gov (indexed) [DOE]

8: Antelope Valley Station to Neset Transmission Project, 8: Antelope Valley Station to Neset Transmission Project, Mercer, Dunn, Billngs, Williams, McKenzie, and Mountrail Counties, ND EIS-0478: Antelope Valley Station to Neset Transmission Project, Mercer, Dunn, Billngs, Williams, McKenzie, and Mountrail Counties, ND SUMMARY USDA Rural Utilities Service is preparing this EIS to evaluate the environmental impacts of constructing, operating, and maintaining a proposed transmission line and associated facilities in western North Dakota. DOE's Western Area Power Administration (WAPA), a cooperating agency, would modify its existing Williston Substation to allow a connection of the proposed new transmission line to Western's transmission system. PUBLIC COMMENT OPPORTUNITIES No Public Comment Opportunities at this time

51

Oahu Wind Integration and Transmission Study (OWITS): Hawaiian Islands Transmission Interconnection Project  

Broader source: Energy.gov (indexed) [DOE]

Oahu Wind Integration and Oahu Wind Integration and Transmission Study (OWITS) Hawaiian Islands Transmission Interconnection Project Dennis Woodford Electranix Corporation Winnipeg, Manitoba Canada Subcontract Report NREL/SR-5500-50411 February 2011 NREL is a national laboratory of the U.S. Department of Energy, Office of Energy Efficiency & Renewable Energy, operated by the Alliance for Sustainable Energy, LLC. National Renewable Energy Laboratory 1617 Cole Boulevard Golden, Colorado 80401 303-275-3000 * www.nrel.gov Contract No. DE-AC36-08GO28308 Oahu Wind Integration and Transmission Study (OWITS) Hawaiian Islands Transmission Interconnection Project Dennis Woodford Electranix Corporation Winnipeg, Manitoba Canada NREL Technical Monitor: David Corbus

52

EIS-0447: Champlain Hudson Power Express Transmission Line Project, New  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

447: Champlain Hudson Power Express Transmission Line Project, 447: Champlain Hudson Power Express Transmission Line Project, New York EIS-0447: Champlain Hudson Power Express Transmission Line Project, New York Summary This EIS evaluates the environmental impacts of a DOE proposal to grant a Presidential permit to Champlain Hudson Power Express, Inc., to construct, operate, maintain, and connect a new 1000-megawatt (MW) electric transmission system across the U.S.-Canada border in northeastern New York State. The proposed transmission line will run from the Canadian Province of Quebec to New York City. DOE also published a notice correcting the location of the public hearing that was held on November 19, 2013. Public Comment Opportunities As of December 6, 2013 - Comment Period Extended through 1/15/14 Written comments must be received by January 15, 2014. Comments submitted

53

Subject: SPPR Proposed ED5 to Palo Verde Transmission Project  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Date: 832010 4:02 PM Subject: SPPR Proposed ED5 to Palo Verde Transmission Project VIA ELECTRONIC MAIL TO: DSWFPP@wapa.gov August 3, 2010 Mr. Darrick...

54

Subject: SPPR Proposed ED5 to Palo Verde Transmission Project  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Date: 832010 4:04 PM Subject: SPPR Proposed ED5 to Palo Verde Transmission Project VIA ELECTRONIC MAIL TO: DSWFPP@wapa.gov August 3, 2010 Mr. Darrick...

55

BPA, Transmission, I-5 Corridor Reinforcement Project, abbreviated...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

About the Project 500-kilovolt transmission New substations at - Castle Rock, Wash. - Troutdale, Ore. 70 miles apart Many route segments 9 Benefits of a new line Keeps the lights...

56

EA-1946: Salem-Albany Transmission Line Rebuild Project; Polk...  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

rebuild of the 24-mile Salem-Albany No. 1 and 28-mile Salem-Albany No. 2 transmission lines between Salem and Albany, Oregon. Additional information is available at the project...

57

Energy Department, Arizona Utilities Announce Transmission Infrastructure Project Energization  

Broader source: Energy.gov [DOE]

Today, the Department of Energy’s Western Area Power Administration (Western) and a group of Arizona utilities celebrated the energizing of a new transmission infrastructure project that will serve the state’s growing electrical energy needs, attract renewable energy development to the area, and strengthen the transmission system in the Southwestern United States.

58

Eldorado Ivanpah Transmission Project | Open Energy Information  

Open Energy Info (EERE)

of all necessary local, state, and federal approvals, authorizations and permits. Data Completion Notes BLM Project website: http:www.blm.govcastenfoneedles...

59

EIS-0483: Estes to Flatiron Substation Transmission Lines Rebuild Project,  

Broader source: Energy.gov (indexed) [DOE]

3: Estes to Flatiron Substation Transmission Lines Rebuild 3: Estes to Flatiron Substation Transmission Lines Rebuild Project, Larimer County, CO EIS-0483: Estes to Flatiron Substation Transmission Lines Rebuild Project, Larimer County, CO SUMMARY DOE's Western Area Power Administration (Western) owns and operates two 16-mile, 115-kilovolt transmission lines on separate rights-of-way between Flatiron Reservoir (near Loveland, Colorado) and the town of Estes Park, Colorado. Western is preparing this EIS to evaluate the environmental impacts of a proposal to upgrade and co-locate these transmission lines, by removing one and abandoning its right-of-way, and rebuilding the other along the existing right-of-way as a double-circuit line (i.e., six conductors per pole). The USDA Forest Service, Arapaho and Roosevelt National Forest, is a cooperating agency in preparing the EIS to support

60

Southwest Transmission Cooperative, Inc. Smart Grid Project | Open Energy  

Open Energy Info (EERE)

Inc. Smart Grid Project Inc. Smart Grid Project Jump to: navigation, search Project Lead Southwest Transmission Cooperative, Inc. Country United States Headquarters Location Benson, Arizona Recovery Act Funding $32,244,485.00 Total Project Value $64,488,970.00 Coverage Area Coverage Map: Southwest Transmission Cooperative, Inc. Smart Grid Project Coordinates 31.9678611°, -110.2945174° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[]}

Note: This page contains sample records for the topic "navajo transmission project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


61

Midwest Independent Transmission System Operator Smart Grid Project | Open  

Open Energy Info (EERE)

Operator Smart Grid Project Operator Smart Grid Project Jump to: navigation, search Project Lead Midwest Independent Transmission System Operator Country United States Headquarters Location Carmel, Indiana Additional Benefit Places Iowa, Illinois, Michigan, Minnesota, Missouri, Montana, North Dakota, Ohio, Pennsylvania, South Dakota, Wisconsin Recovery Act Funding $17,271,738.00 Total Project Value $34,543,476.00 Coverage Area Coverage Map: Midwest Independent Transmission System Operator Smart Grid Project Coordinates 39.978371°, -86.1180435° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[]}

62

American Transmission Company LLC II Smart Grid Project | Open Energy  

Open Energy Info (EERE)

Smart Grid Project Smart Grid Project Jump to: navigation, search Project Lead American Transmission Company LLC Country United States Headquarters Location Waukesha, Wisconsin Recovery Act Funding $11,444,180 Total Project Value $22,888,360 Coverage Area Coverage Map: American Transmission Company LLC II Smart Grid Project Coordinates 43.0116784°, -88.2314813° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[]}

63

Kangley - Echo Lake Transmission Line Project, Final Environmental Impact Statement  

Broader source: Energy.gov (indexed) [DOE]

STATEMENT STATEMENT Kangley-Echo Lake Transmission Line Project Final Environmental Impact Statement Responsible Agency: U.S. Department of Energy, Bonneville Power Administration (BPA) Cooperating Agency: U.S. Department of Agriculture, Forest Service (USFS) Title of Proposed Project: Kangley-Echo Lake Transmission Line Project State Involved: Washington Abstract: BPA is proposing to build a new transmission line to accommodate increasing demand for electricity and ensure reliability in the Puget Sound area. The Proposed Action would construct a new line that would connect to an existing transmis- sion line near the community of Kangley, and then connect with BPA's existing Echo Lake Substation. The major purpose of this proposal is to improve system reliability in the King County area. An outage on an existing line during times of heavy use, such as

64

Phase 2 Report: Oahu Wind Integration and Transmission Study (OWITS); Hawaiian Islands Transmission Interconnection Project  

Broader source: Energy.gov (indexed) [DOE]

Phase 2 Report: Oahu Wind Phase 2 Report: Oahu Wind Integration and Transmission Study (OWITS) Hawaiian Islands Transmission Interconnection Project Dennis Woodford Electranix Corporation Winnipeg, Manitoba Canada Subcontract Report NREL/SR-5500-50414 February 2011 NREL is a national laboratory of the U.S. Department of Energy, Office of Energy Efficiency & Renewable Energy, operated by the Alliance for Sustainable Energy, LLC. National Renewable Energy Laboratory 1617 Cole Boulevard Golden, Colorado 80401 303-275-3000 * www.nrel.gov Contract No. DE-AC36-08GO28308 Phase 2 Report: Oahu Wind Integration and Transmission Study (OWITS) Hawaiian Islands Transmission Interconnection Project Dennis Woodford Electranix Corporation Winnipeg, Manitoba Canada

65

Navajo Generating Station and Air Visibility Regulations: Alternatives and Impacts (Revised), Energy Analysis, NREL (National Renewable Energy Laboratory)  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Navajo Generating Station Navajo Generating Station Navajo Generating Station and Air Visibility Regulations: Alternatives and Impacts David J. Hurlbut, Scott Haase, Gregory Brinkman, Kip Funk, Rachel Gelman, Eric Lantz, Christina Larney, David Peterson, Christopher Worley National Renewable Energy Laboratory Ed Liebsch HDR Engineering, Inc. Prepared under Task No. WFJ5.1000 Technical Report NREL/TP-6A20-53024 * Revised March 2012 Contract No. DE-AC36-08G028308 Produced under direction of the U.S. Department of the Interior by the National Renewable Energy Laboratory (NREL) under Interagency Agreement R11PG30024 and Task No. WFJ5.1000. ERRATA SHEET NREL REPORT/PROJECT NUMBER: NREL/TP-6A20-53024 DOE NUMBER: N/A TITLE: Navajo Generating Station and Air Visibility Regulations: Alternatives and

66

BPA, Transmission, I-5 Corridor Reinforcement Project, Project...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

for this project, we have defined four route alternatives by combining route segments and substation sites. We are sharing this information with you now, because we expect to refer...

67

American Transmission Company LLC Smart Grid Project | Open Energy  

Open Energy Info (EERE)

American Transmission Company LLC American Transmission Company LLC Country United States Headquarters Location Waukesha, Wisconsin Recovery Act Funding $1,330,825.00 Total Project Value $2,661,650.00 Coverage Area Coverage Map: American Transmission Company LLC Smart Grid Project Coordinates 43.0116784°, -88.2314813° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[]}

68

McMinnville Area Support Transmission Project : Environmental Assessment.  

SciTech Connect (OSTI)

This document discusses a project to provide continuing reliable electrical service to the McMinnville, Oregon, area. BPA proposes to participate with the City of McMinnville Water and Light Department in constructing a new 230-kilovolt transmission line and substation. BPA has prepared an environmental assessment evaluating the proposed project. Reasons that constructing the line and substation would not cause significant environmental impact include: consistency with local land use plans, consistency of appearance with existing transmission and manufacturing facilities in the area, only slight effect on farmland, and avoidance of wetlands and other environmentally sensitive areas. A finding is included that there is no practicable alternative to locating the project within a 100-year floodplain. 1 fig.

United States. Bonneville Power Administration.

1990-01-01T23:59:59.000Z

69

Renewable Resource Integration Project - Scoping Study of Strategic Transmission, Operations, and Reliability Issues  

E-Print Network [OSTI]

kV line is upgraded.   The Tehachapi Renewable Transmission Transmission Project and the Palo Verde/Harquahala?Devers No.  2  500 kV line 

Budhraja, Vikram

2008-01-01T23:59:59.000Z

70

Wallula-McNary Transmission Line Project and Wallula Power Project EIS (DOE/EIS-0030)  

Broader source: Energy.gov (indexed) [DOE]

RECORD OF DECISION for the Wallula-McNary Transmission Line Project and Wallula Power Project THE DECISION The Bonneville Power Administration (BPA) has decided to implement its portion of the proposed action identified in the Wallula Power Project and Wallula-McNary Transmission Line Project Final Environmental Impact Statement (DOE/EIS-0330, August 2002). The proposed action includes construction of the Wallula Power Project (Wallula Project) that has been proposed by Wallula Generation, LLC (Wallula LLC). The proposed Wallula Project is a 1,300- megawatt (MW) natural-gas-fired, combined-cycle turbine power plant that Wallula LLC is planning to construct on a site near the Columbia River in Walla Walla County, Washington, approximately eight miles south of the City of Pasco. BPA's portion of the proposed action

71

BPA/Lower Valley Transmission Project Final Environmental Impact Statement  

Broader source: Energy.gov (indexed) [DOE]

1 1 Summary Summary * The Purpose and Need for Action * Alternatives * Affected Environment * Impacts This summary gives the major points of the Final Environmental Impact Statement (EIS) prepared for the BPA/Lower Valley Transmission Project by Bonneville Power Administration (BPA). BPA is the lead federal agency on this project and supervises the preparation of the EIS. The U.S. Forest Service is a cooperating agency and assists BPA in EIS preparation. The Targhee and Bridger-Teton National Forests are crossed by BPA's existing transmission line and some of the alternatives. S.1 Purpose and Need For Action S.1.1 BPA Lower Valley Power and Light, Inc. (LVPL) buys electricity from BPA and then supplies it to the residences, farms and businesses of the Jackson and Afton, Wyoming areas. Since the late 1980s,

72

EIS-0486: Plains & Eastern Clean Line Transmission Project  

Broader source: Energy.gov [DOE]

This EIS will evaluate the potential environmental impacts of participating with Clean Line Energy Partners LLC (Clean Line) in the proposed Plains & Eastern Project. The proposed project would include an overhead ± 600 kilovolt (kV) high voltage direct current (HVDC) electric transmission system and associated facilities with the capacity to deliver approximately 3,500 megawatts (MW) primarily from renewable energy generation facilities in the Oklahoma Panhandle region to load-serving entities in the Mid-South and Southeast via an interconnection with the Tennessee Valley Authority (TVA).

73

EA-1952: Lane-Wendson No. 1 Transmission Line Rebuild Project...  

Energy Savers [EERE]

52: Lane-Wendson No. 1 Transmission Line Rebuild Project; Lane County, Oregon EA-1952: Lane-Wendson No. 1 Transmission Line Rebuild Project; Lane County, Oregon SUMMARY Bonneville...

74

Transmission  

Broader source: Energy.gov (indexed) [DOE]

Transmission Transmission ,... ,...vc- "' ""'\ S I r;. Dr. Jerry Pell, CCM Principal NEP A Document Manager Permitting, Siting, and Analysis (OE-20) Office of Electricity Delivery and Energy Reliability U.S. Department of Energy 1 000 Independence A venue SW Washington, D.C. 20585-0001 Subject: Champlain Hudson Power Express Project Submittal of Amendment Application Dear Dr. Pell: February 28, 2012 On January 25, 2010, Transmission Developers, Inc. ("TDI") submitted on behalf of Champlain Hudson Power Express, Inc. ("CHPEI") an application to the U.S. Department of Energy ("DOE") for a Presidential Permit ("Application) in connection with the Champlain Hudson Power Express project ("Project"). The Application proposed to connect clean sources

75

Wallula Power Project and Wallula - McNary Transmission Line Project Final Environmental Impact Statement  

SciTech Connect (OSTI)

Wallula Generation, LLC proposes to construct a 1,300-megawatt (MW) natural gas-fired combined-cycle combustion gas turbine facility (the Wallula Power Project). The project would be located in the northwestern portion of Walla Walla County, Washington, approximately 8 miles south of the City of Pasco, 2 miles north of the unincorporated community of Wallula, and 7 miles southeast of the unincorporated community of Burbank. The purpose of the proposed power project is to provide energy to meet the needs of the Northwest and other interconnected electric transmission areas where electrical energy is needed. Firm transmission of the power generated by the Wallula Power Project would require construction of a new 500-kilovolt (kV) transmission line and construction of a new switchyard near Smiths Harbor. Approximately 5.1 miles of new transmission line from the proposed generation plant to the new switchyard would be completed. An additional 28 miles of new transmission line from the Smiths Harbor Switchyard to the McNary Substation would be constructed adjacent to the existing Lower Monumental-McNary transmission line and upgrades completed to the existing McNary Substation if loads are exceeded on the existing line. Wallula Generation, LLC, would construct and operate the generation plant and associated facilities, including the makeup water supply line. Bonneville would design, construct, and operate the two 500 kV transmission line segments and switchyard. To supply natural gas to the plant site, a 5.9-mile pipeline interconnection would be engineered, constructed, owned, and operated by PG&E Gas Transmission-Northwest (GTN). This EIS evaluates the environmental impacts of the proposed action, which includes the proposed power plant and 33-mile transmission line. It also evaluates an alternative using taller towers and longer spans between towers along part of the transmission line, and the use of an alternative approach for the transmission line where it would enter the McNary Substation. The No Action Alternative is also addressed.

N /A

2002-08-16T23:59:59.000Z

76

Collaboration and Communication: DOE and Navajo Nation Tour Uranium...  

Broader source: Energy.gov (indexed) [DOE]

site managers, along with Navajo Nation technical staff, visited five reclaimed uranium-mine sites on tribal lands to share expertise in the use of technical approaches...

77

Wallula Power Project and Wallula - McNary Transmission Line Project, Final Environmental Impact Statement  

Broader source: Energy.gov (indexed) [DOE]

and and Wallula - McNary Transmission Line Project Final Environmental Impact Statement DOE/EIS-0330 Lead Agencies Bonneville Power Administration Washington State Energy Facility Site Evaluation Council Cooperating Agencies Bureau of Land Management U.S. Fish and Wildlife Service August 2002 EFSEC Washington State Energy Facility Site Evaluation Council August 2002 Dear Reader: Enclosed for your reference is the abbreviated form Final Environmental Impact Statement (FEIS) for the proposed Wallula Power Project and Wallula-McNary Transmission Line Project. This document is designed to supplement or correct information provided in the Draft Environmental Impact Statement (DEIS). The proponent, Wallula Generation, LLC, has requested to build a 1,300-megawatt, gas-fired

78

BPA/Lower Valley Transmission Project Final Environmental Impact Statement  

Broader source: Energy.gov (indexed) [DOE]

1 9 9 7 1 9 9 7 B PA / L O W E R VA L L E Y T R A N S M I S S I O N P R O J E C T Final Environmental Impact Statement DOE/EIS-0267 J U N E 1 9 9 8 Bonneville Power Administration PO Box 3621 Portland, Oregon 97208-3621 DOE/BP-3067 JUNE 1998 450 Final Environmental Impact Statement BPA/Lower Valley Transmission Project Bonneville Power Administration U.S. Department of Energy and Forest Service U.S. Department of Agriculture June 1998 Table of Contents - i Table of Contents Summary ............................................................................................................................ S-1 S.1 Purpose and Need For Action ................................................................................................ S-1 S.1.1 BPA ...............................................................................................................................................

79

DSW Power Projects  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Power Projects Contact DSW Customers Customer Meetings Environmental Review-NEPA Operations & Maintenance Planning & Projects Power Marketing Power Projects Contact DSW Customers Customer Meetings Environmental Review-NEPA Operations & Maintenance Planning & Projects Power Marketing Rates DSW Power Projects Boulder Canyon: Straddling the Colorado River near the Arizona-Nevada border, Hoover Dam in Boulder Canyon creates Lake Mead. River waters turning turbines at Hoover Powerplant produce about 2,074 MW--enough electricity for nearly 8 million people. Western markets this power to public utilities in Arizona, California and Nevada over 53.30 circuit-miles of transmission line. Central Arizona: Authorized in 1968, the Central Arizona Project in Arizona and western New Mexico was built to improve water resources in the Colorado River Basin. Segments of the authorization allowed for Federal participation in the Navajo Generating Station. The Federal share of the powerplant's combined capacity is 547 MW.

80

DOE/EA-1366; Environmental Assessment Santiam-Bethel Transmission Line Project (09/2001)  

Broader source: Energy.gov (indexed) [DOE]

Preliminary Environmental Assessment Preliminary Environmental Assessment Santiam-Bethel Transmission Line Project Bonneville Power Administration September 2001 Santiam-Bethel Transmission Line Project Responsible Agency: U.S. Department of Energy, Bonneville Power Administration (BPA) Name of Proposed Project: Santiam-Bethel Transmission Line Project Abstract: Bonneville Power Administration proposes to rebuild the first 17 miles of the Santiam-Chemawa transmission line from Santiam Substation to the line's connection to Portland General Electric's Bethel Substation. BPA would replace the existing single-circuit 230-kilovolt (kV) line with towers that could support two circuits. The existing line supplies both Bethel Substation and BPA's Chemawa Substation. The new lines would eliminate

Note: This page contains sample records for the topic "navajo transmission project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


81

EIS-0377: Big Stone II Power Plant and Transmission Project | Department of  

Broader source: Energy.gov (indexed) [DOE]

7: Big Stone II Power Plant and Transmission Project 7: Big Stone II Power Plant and Transmission Project EIS-0377: Big Stone II Power Plant and Transmission Project SUMMARY A systems study was carried out to identify the most appropriate locations to interconnect the proposed Big Stone II power plant to the regional utility grid. The study also identified transmission line and substation upgrades and modifications that would be required to support the addition of 600 MW of capacity within the system. PUBLIC COMMENT OPPORTUNITIES None available at this time. DOCUMENTS AVAILABLE FOR DOWNLOAD August 24, 2009 EIS-0377: Record of Decision Big Stone II Power Plant and Transmission Project June 1, 2009 EIS-0377: Final Environmental Impact Statement Big Stone II Power Plant and Transmission Project October 26, 2007 EIS-0377: Supplemental Draft Environmental Impact Statement

82

Schultz-Hanford Area Transmission Line Project (DOE-eis-0325)  

Broader source: Energy.gov (indexed) [DOE]

Schultz-Hanford Area Transmission Line Project Schultz-Hanford Area Transmission Line Project Record of Decision March 2003 Bonneville Power Administration Schultz-Hanford Area Transmission Line Project Record of Decision Decision The Bonneville Power Administration (BPA) has decided to construct the proposed Schultz-Hanford Area Transmission Line Project in Benton, Douglas, Grant, Kittitas, and Yakima Counties, Washington. BPA has decided to implement the Agency Preferred Alternative identified in the Schultz-Hanford Area Transmission Line Project Final Environmental Impact Statement (DOE/EIS-0325, January 2003), with the exception of Option 1 of the Sickler-Schultz Reroute. Due to landowner concerns, BPA will now implement Option 2 of the Sickler-Schultz Reroute. The Agency Preferred Alternative consists of constructing a new 500-kilovolt (kV) transmission

83

EIS-0256: Sierra Pacific Power Company Alturas Transmission Line Project (adopted from BLM)  

Broader source: Energy.gov [DOE]

This EIS evaluates the environmental setting and consequences of the construction and operation of the proposal Alturas Transmission Line Project. Sierra Pacific Power Company (SPPCO) has proposed this electric power transmission line to improve the existing operational capacity and reliability of its power transmission system and provide for anticipated growth in demand for electric power.

84

EIS-0484: Montana-to-Washington Transmission System Upgrade Project in  

Broader source: Energy.gov (indexed) [DOE]

4: Montana-to-Washington Transmission System Upgrade Project 4: Montana-to-Washington Transmission System Upgrade Project in Washington, Idaho, and Montana EIS-0484: Montana-to-Washington Transmission System Upgrade Project in Washington, Idaho, and Montana SUMMARY This EIS will evaluate the environmental impacts of a proposal to replace roughly 12 miles of transmission line on the Taft-Dworshak 500-kV transmission line, install new series capacitors on the Garrison-Taft 500-kV transmission line, and perform various upgrades to Bell, Hatwai, Dworshak, Garrison, and Hot Springs substations. The project website is http://efw.bpa.gov/environmental_services/Document_Library/M2W/. PUBLIC COMMENT OPPORTUNITIES None available at this time. DOCUMENTS AVALABLE FOR DOWNLOAD May 3, 2012 EIS-0484: Notice of Intent to Prepare an Environmental Impact Statement

85

EIS-0325: Schultz-Hanford Area Transmission Line Project Final Environmental Impact Statement, EIS-0325 (January 2003)  

Broader source: Energy.gov [DOE]

BPA proposes to construct a new 500-kilovolt (kV) transmission line in central Washington. This project would increase transmission system capacity north of Hanford.

86

EIS-0450: TransWest Express 600 kV Direct Current Transmission Project in  

Broader source: Energy.gov (indexed) [DOE]

0: TransWest Express 600 kV Direct Current Transmission 0: TransWest Express 600 kV Direct Current Transmission Project in Wyoming, Colorado, Utah, and Nevada EIS-0450: TransWest Express 600 kV Direct Current Transmission Project in Wyoming, Colorado, Utah, and Nevada Summary This EIS, being prepared jointly by DOE's Western Area Power Administration and the Department of the Interior's Bureau of Land Management (Wyoming State Office), evaluates the environmental impacts of granting a right-of-way for the TransWest Express 600-kilovolt Direct Current Transmission Project and amending a land use plan. The project consists of an overhead transmission line that would extend approximately 725 miles from south-central Wyoming, through Colorado and Utah. Western proposes to be a joint owner of the project. Public Comment Opportunities

87

DOE/EA-1485: Environmental Assessment for the Nisqually Transmission Line Relocation Project (January 2005)  

Broader source: Energy.gov (indexed) [DOE]

Nisqually Transmission Line Relocation Project Nisqually Transmission Line Relocation Project Revision Sheet for the Environmental Assessment Finding of No Significant Impact Mitigation Action Plan DOE/EA-1485 Bonneville Power Administration January 2005 Nisqually Transmission Line Relocation Project Revision Sheet for Final Environmental Assessment 1 Revision Sheet for the Nisqually Transmission Line Relocation Project Final Environmental Assessment DOE/EA -1485 Summary This revision sheet documents the changes to be incorporated into the Nisqually Transmission Line Project Preliminary Environmental Assessment (EA). With the addition of these changes, the Preliminary EA will not be reprinted and will serve as the Final EA. On October 18, 2004, the Preliminary EA was sent to agencies and interested parties. Notification

88

EIS-0317: Kangley-Echo Lake Transmission Line Project  

Broader source: Energy.gov [DOE]

This EIS analyzes BPA's proposal to build a new transmission line to accommodate increasing demand for electricity and ensure reliability in the Puget Sound area.

89

BPA, transmission, I-5 Corridor Reinforcement Project, new Permission...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

also identify protective measures that BPA would take during the construction process if BPA decides to build a transmission line or substation. An archeologist or historian may...

90

BPA transmission, I-5 corridor reinforcement project, updated...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Facilities Proposed New Substation sde.SDE.BPAPlannedTlines sde.SDE.BPAPlannedTlines BPA Substation Non-BPA Substation BPA Transmission Lines Cities and Towns Urban Areas...

91

BPA Transmission, I-5 Corridor Reinforcement Project, Scoping...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

the transmission lines and consider energy efficiency strategies. Commenters also asked BPA to consider whether a new substation will be needed half-way between Troutdale and...

92

BPA, Transmission, I-5 Corridor Reinforcement Project Map, August...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

lettered route segments added for consideration Segments no longer being considered 5 K BPA Substation Non-BPA Substation BPA Transmission Lines Cities and Towns Urban Areas...

93

BPA, proposed I-5 Corridor Reinforcement transmission project...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Regional GIS Database, 2009. Facilities Proposed New Substation Proposed Route Segments BPA Substation Non-BPA Substation BPA Transmission Lines Cities and Towns Urban Areas...

94

EIS-0124: Conrad-Shelby Transmission Line Project, Montana  

Broader source: Energy.gov [DOE]

The U.S. Department of Energy's Western Area Power Administration developed this statement to assess the environmental impact of adding a 230 kV transmission line between Conrad and Shelby, Montana and a new substation near Shelby to update the stressed electrical transmission system.

95

EIS-0101: Thermopolis, Alcova, Casper Transmission Line Project  

Broader source: Energy.gov [DOE]

The Western Area Power Administration developed this statement to evaluate the environmental impacts of constructing, operating and maintaining a 230-kilovolt transmission line between Thermopolis, Wyoming, and Alcova, Wyoming, and a 230/345-kilovolt transmission line between Alcova, Wyoming, and Casper, Wyoming.

96

EIS-0499: Great Northern Transmission Line Project, Minnesota  

Broader source: Energy.gov [DOE]

This EIS will evaluate the potential environmental impacts of a DOE proposal to grant a Presidential permit to Minnesota Power to construct, operate, maintain, and connect a new 750-megawatt electric transmission system across the U.S.-Canada border. The proposed 220 mile transmission line would cross the border near Roseau, Minnesota, and continue to Grand Rapids, Minnesota.

97

DOE/EA-1644: Kildeer to Mountain Transmission Project Pre-Decisional Environmental Assessment (May 2009)  

Broader source: Energy.gov (indexed) [DOE]

KILLDEER TO MOUNTAIN KILLDEER TO MOUNTAIN TRANSMISSION PROJECT PRE-DECISIONAL ENVIRONMENTAL ASSESSMENT MAY 5, 2009 DOE/EA-1644 PRE-DECISIONAL ENVIRONMENTAL ASSESSMENT KILLDEER TO MOUNTAIN PAGE i MAY 2009 TRANSMISSION PROJECT DOE/EA -1644 TABLE OF CONTENTS 1.0 INTRODUCTION .............................................................................................. 1-1 1.1 Purpose of and Need for Action ........................................................................................... 1-1 1.1.1 Project Purpose ............................................................................................................ 1-1 1.1.2 Western's Purpose and Need ..................................................................................... 1-1

98

EIS-0496: San Luis Transmission Project, Alameda, Merced, San Joaquin and  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

96: San Luis Transmission Project, Alameda, Merced, San 96: San Luis Transmission Project, Alameda, Merced, San Joaquin and Stanislaus Counties, California EIS-0496: San Luis Transmission Project, Alameda, Merced, San Joaquin and Stanislaus Counties, California Summary DOE's Western Area Power Administration, with the Bureau of Reclamation as a cooperating agency, is preparing a joint EIS and environmental impact report (under the California Environmental Quality Act) to evaluate the potential environmental impacts of the proposed interconnection of certain San Luis Unit facilities to Western's Central Valley Project Transmission System. Western proposes at a minimum to construct, own, operate, and maintain a new 230-kilovolt (kV) transmission line about 62 miles in length between Western's Tracy Substation and Western's San Luis Substation and a

99

EA-1880: Big Bend to Witten Transmission Line Project, South Dakota |  

Broader source: Energy.gov (indexed) [DOE]

80: Big Bend to Witten Transmission Line Project, South Dakota 80: Big Bend to Witten Transmission Line Project, South Dakota EA-1880: Big Bend to Witten Transmission Line Project, South Dakota Summary The USDA Rural Utilities Service, with DOE's Western Area Power Administration as a cooperating agency, is preparing this EA to evaluate the environmental impacts of a proposal to construct a 70-mile long 230-kV single-circuit transmission line, a new Western Area Power Administration substation, an addition to the existing substation, and approximately 2 miles of 230-kV double-circuit transmission line, all in South Dakota. Proposed action is related to the Keystone XL project (see DOE/EIS-0433-S1). Public Comment Opportunities No public comment opportunities available at this time. Documents Available for Download April 12, 2011

100

EA-1665: Davis-Kingman 69-kV Transmission Line Rebuild Project, Arizona |  

Broader source: Energy.gov (indexed) [DOE]

65: Davis-Kingman 69-kV Transmission Line Rebuild Project, 65: Davis-Kingman 69-kV Transmission Line Rebuild Project, Arizona EA-1665: Davis-Kingman 69-kV Transmission Line Rebuild Project, Arizona Overview Western plans to rebuild a 26.6-mile-long portion of the existing 27.3-mile-long Davis-Kingman Tap 69-kV Transmission Line within the existing ROW in order to improve the reliability of the transmission service. The line has been in service well beyond its projected service life, customer load on the line has increased considerably over the years, and reliability has decreased due to natural aging, extreme weather exposure, vandalism, and lightning strikes. The western-most 0.7 mile of the existing line was rebuilt as part of the Davis Dam Switchyard in 2010. Public Comment Opportunities No public comment opportunities available at this time.

Note: This page contains sample records for the topic "navajo transmission project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


101

EIS-0451: Hooper Springs Transmission Project, Caribou County, Idaho  

Broader source: Energy.gov [DOE]

Bonneville Power Administration (BPA) is preparing an EIS to assess the potential environmental impacts of a proposed new 115-kilovolt (kV) transmission line that would extend from BPA's proposed Hooper Springs Substation near Soda Springs, Idaho, to either an existing Lower Valley Energy (LVE) substation or a proposed BPA connection facility that would connect with LVE's existing transmission system in northeastern Caribou County. The proposed new transmission line would be about 22 to 33 miles depending on the route alternative or option.

102

Port Angeles-Juan de Fuca Transmission Project Final Environmental Impact Statement  

Broader source: Energy.gov (indexed) [DOE]

Port Angeles-Juan de Fuca Port Angeles-Juan de Fuca Transmission Project Final Environmental Impact Statement DOE/EIS-0378 October 2007 Port Angeles-Juan de Fuca Transmission Project Final Environmental Impact Statement DOE/EIS - 0378 D e p a r t m e n t o f E n e r g y Office of Electricity Delivery and Energy Reliability and Bonneville Power Administration October 2007 Port Angeles-Juan de Fuca Transmission Project DOE/EIS-0378 Responsible Agency: U.S. Department of Energy (DOE): Office of Electricity Delivery and Energy Reliability (OE) and Bonneville Power Administration (BPA) Title of Proposed Project: Port Angeles-Juan de Fuca Transmission Project State Affected: Washington (WA) Abstract: Sea Breeze Olympic Converter LP (Sea Breeze) has applied to DOE for authorizations and approvals

103

EIS-0486: Plains & Eastern Clean Line Transmission Project | Department of  

Broader source: Energy.gov (indexed) [DOE]

86: Plains & Eastern Clean Line Transmission Project 86: Plains & Eastern Clean Line Transmission Project EIS-0486: Plains & Eastern Clean Line Transmission Project SUMMARY This EIS will evaluate the potential environmental impacts of participating with Clean Line Energy Partners LLC (Clean Line) in the proposed Plains & Eastern Project. The proposed project would include an overhead ± 600 kilovolt (kV) high voltage direct current (HVDC) electric transmission system and associated facilities with the capacity to deliver approximately 3,500 megawatts (MW) primarily from renewable energy generation facilities in the Oklahoma Panhandle region to load-serving entities in the Mid-South and Southeast via an interconnection with the Tennessee Valley Authority (TVA). PUBLIC COMMENT OPPORTUNITIES None available at this time.

104

BPA, transmission, I-5 Corridor Reinforcement Project, letter...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

made to the PEP form and how they affect any rights you may or have granted. Background - BPA is proposing to build a 500-kilovolt transmission line and associated substations. The...

105

EA-1891: Alvey-Fairview Transmission Line Rebuild Project, Oregon  

Broader source: Energy.gov [DOE]

This EA evaluates the environmental impacts of a proposal to rebuild DOE’s Bonneville Power Administration’s Alvey-Fairview No. 1 230-kV transmission line located between Eugene, Oregon, and Coquille, Oregon.

106

EIS-0106: Great Falls-Conrad Transmission Line Project, Montana  

Broader source: Energy.gov [DOE]

The Western Area Power Administration prepared this EIS to evaluate the environmental impacts of the construction and operation of a 230-kilovolt transmission line from Great Falls, Montana, to Conrad, Montana.

107

EIS-0496: San Luis Transmission Project, Alameda, Merced, San...  

Energy Savers [EERE]

proposes at a minimum to construct, own, operate, and maintain a new 230-kilovolt (kV) transmission line about 62 miles in length between Western's Tracy Substation and...

108

BPA, Transmission, I-5 Corridor Reinforcement Project, meeting...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

BPA I-5 Corridor Reinforcement Project - AugustSeptember 2010 Open Houses Page 1 of 4 Meeting Summary and Survey Results BPA I-5 Corridor Reinforcement Project - AugustSeptember...

109

Phase 2 Report: Oahu Wind Integration and Transmission Study (OWITS); Hawaiian Islands Transmission Interconnection Project  

SciTech Connect (OSTI)

This report provides an independent review including an initial evaluation of the technical configuration and capital costs of establishing an undersea cable system and examining impacts to the existing electric transmission systems as a result of interconnecting the islands

Woodford, D.

2011-02-01T23:59:59.000Z

110

EIS-0317-S1: Kangley-Echo Lake Transmission Line Project Final Environmental Impact Statement  

Broader source: Energy.gov [DOE]

Bonneville Power Administration (BPA) has completed a supplemental draft Environmental Impact Statement (SDEIS) for the proposed Kangley-Echo Lake Transmission Line Project. The proposed line in central King County, Washington is needed to accommodate electrical growth and reliability concerns in the Puget Sound area. The SDEIS analyzes four additional transmission alternatives not analyzed in detail in the draft Environmental Impact Statement (DEIS) issued in June 2001, and a number of non-transmission alternatives.

111

File:08-CA-d - CPCN for Transmission Projects (2).pdf | Open...  

Open Energy Info (EERE)

(2).pdf Jump to: navigation, search File File history File usage Metadata File:08-CA-d - CPCN for Transmission Projects (2).pdf Size of this preview: 463 599 pixels....

112

Keeler-to-Tillamook Transmission Line Rebuild Project Draft Environmental Assessment  

Broader source: Energy.gov (indexed) [DOE]

Keeler-to-Tillamook Transmission Line Keeler-to-Tillamook Transmission Line Rebuild Project Draft Environmental Assessment October 2013 This page deliberately left blank. Bonneville Power Administration i Contents Chapter 1 Purpose and Need for Action ............................................................................................ 1-1 1.1 Introduction ................................................................................................................................. 1-1 1.2 Need for Action ............................................................................................................................ 1-1 1.3 Purposes of Action ....................................................................................................................... 1-2

113

EIS-0378: Port Angeles-Juan de Fuca Transmission Project, WA  

Broader source: Energy.gov [DOE]

This EIS assesses DOE decision to approve the Sea Breeze Transmission project for a Presidential permit for through DOE's Office of Electricity Delivery and Energy Reliability and for approval for interconnection into the federal transmission system through the Bonneville Power Administration (BPA).

114

Kangley - Echo Lake Transmission Line Project, Supplemental Draft Environmental Impact Statement  

Broader source: Energy.gov (indexed) [DOE]

Bonneville Power Administration Bonneville Power Administration P.O. Box 491 Vancouver, Washington 98666-0491 TRANSMISSION BUSINESS LINE January 14, 2003 In reply refer to: T-DITT-2 To: People Interested in the Kangley-Echo Lake Transmission Line Project Bonneville Power Administration (BPA) has completed a supplemental draft Environmental Impact Statement (SDEIS) for the proposed Kangley-Echo Lake Transmission Line Project. The proposed line in central King County, Washington is needed to accommodate electrical growth and reliability concerns in the Puget Sound area. The SDEIS analyzes four additional transmission alternatives not analyzed in detail in the draft Environmental Impact Statement (DEIS) issued in June 2001, and a number of non-transmission alternatives. This letter provides

115

BPA, Transmission, I-5 Corridor Reinforcement Project, January...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

soon as possible. The decision document is available on the I-5 Project website at www.bpa.govgoi5. Non-wire measures won't delay route analysis As plans take shape to address...

116

UPDATE TO PLAINS & EASTERN CLEAN LINE PROPOSAL FOR NEW OR UPGRADED TRANSMISSION LINE PROJECTS  

Broader source: Energy.gov (indexed) [DOE]

UPDATE TO PLAINS & EASTERN CLEAN LINE PROPOSAL UPDATE TO PLAINS & EASTERN CLEAN LINE PROPOSAL FOR NEW OR UPGRADED TRANSMISSION LINE PROJECTS UNDER SECTION 1222 OF THE ENERGY POLICY ACT OF 2005 AUGUST 2011 Table of Contents 1. Executive Summary .......................................................................................................... 1 2. Project Update .................................................................................................................. 2 a. Jobs and Economic Development ........................................................................................................... 5 b. Interconnection Studies ............................................................................................................................. 6 c. Routing and Public Outreach ................................................................................................................... 7

117

Buffalo Flat Service 115-KV Transmission Project : Environmental Assessment.  

SciTech Connect (OSTI)

BPA, in conjunction with Midstate Electric Cooperative (Midstate), proposed to construct two sections of a new 115-kV transmission line in central Oregon: one section from BPA's LaPine Substation to Midstate's Fort Rock Substation (BPA), and the other from Fort Rock Substation to the proposed US Air Force radar transmitter site at Buffalo Flat (Midstate). The proposed line would be a total of about 74 miles long, and of either wood or steel single-pole construction; it would parallel existing corridors and/or roads for much of the distance. 23 refs., 6 figs., 5 tabs.

United States. Bonneville Power Administration.

1987-07-01T23:59:59.000Z

118

Microsoft Word - Grand Coulee Transmission Line Replacement Project Prelim EA.doc  

Broader source: Energy.gov (indexed) [DOE]

Grand Coulee's Third Powerplant 500-kilovolt Transmission Line Replacement Project Preliminary Environmental Assessment May 2011 DOE/EA-1679 Agency Proposing Action. U.S. Bureau of Reclamation is the lead NEPA agency. The Bonneville Power Administration is assisting Reclamation through project design, environmental review and construction, if the Proposed Action is taken. Action. Reclamation is proposing to replace the six, 500- kV transmission lines of the Third Powerplant (TPP) at Grand Coulee Dam. The transmission lines are presently installed within the dam and a two-chambered tunnel that leads to a Spreader Yard about a mile away. Purpose and Need. The TPP's six generators and transmission lines are critical to the regional power supply.

119

DOE/EA-1602: Alternative Intake Project Transmission Line and Interconnection Final Environmental Assessment (November 2008)  

Broader source: Energy.gov (indexed) [DOE]

Alternative Intake Project Alternative Intake Project Transmission Line and Interconnection Final Environmental Assessment November 2008 DOE/EA-1602 DOE/EA-1602 Final Environmental Assessment for the Western Area Power Administration Alternative Intake Project Transmission Line and Interconnection As part of its comprehensive water quality strategy to protect and improve water quality for its customers, the Contra Costa Water District (CCWD) is implementing the Alternative Intake Project (AIP). The AIP will enable CCWD to relocate some of its existing diversions to Victoria Canal, a Delta location with higher-quality source water than is currently available at its Old River and Rock Slough intakes. The AIP project purpose is to protect and improve the quality of water delivered to CCWD's untreated-

120

Silver Creek-Morton Transmission Project: Environmental assessment  

SciTech Connect (OSTI)

Bonneville Power Administration (BPA) will in 1989, replace the Silver Creek-Morton 69-kV transmission line with a line of 115-kV construction and, in the late 1990's, add capacitors at Morton Substation. Portions of the new line would be constructed on new right-of-way adjacent to the old 69-kV line and portions would be constructed on the same right-of-way. Construction on adjacent right-of-way would require new right-of-way up to 50 feet wide on one side of the present right-of-way. BPA would then release to private ownership right-of-way up to 50 feet wide on the opposite side, after the old line has been removed. Parts of the new line would be constructed on H-frame wood-pole sructures and parts on single wood-pole structures, depending on land use constraints. 16 refs., 3 figs., 3 tabs.

Not Available

1986-06-01T23:59:59.000Z

Note: This page contains sample records for the topic "navajo transmission project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


121

Supplemental Draft Environmental Impact StatementS Big Stone II Power Plant and Transmission Project  

Broader source: Energy.gov (indexed) [DOE]

ES-1 ES-1 ES.0 Summary In May 2006, Western Area Power Administration (Western), Rural Utilities Service (RUS), and U.S. Army Corps of Engineers (USACE) issued the Big Stone II Power Plant and Transmission Project Draft Environmental Impact Statement (Draft EIS, DOE/EIS-0377). The Draft EIS described the details of constructing and operating a nominal 600-megawatt (MW), coal-fired, baseload electric generating facility and associated transmission line and substation upgrades, known as the Big Stone II Project (proposed Project). The proposed Project would be constructed by Otter Tail Corporation (dba Otter Tail Power Company (OTP)), Central Minnesota Municipal Power Agency, Great River Energy, Heartland Consumers Power District, Montana-Dakota Utilities Co., Southern Minnesota Municipal Power Agency, and

122

ORIGINAL ARTICLE Navajo SandstonebrineCO2 interaction: implications  

E-Print Network [OSTI]

in the western US (Loope and Rowe 2003), and is thus potentially sig- nificant with respect to carbonORIGINAL ARTICLE Navajo Sandstone­brine­CO2 interaction: implications for geological carbon a source of carbon for the precipitation of carbonate minerals. Mineral trapping through the precipitation

Zhu, Chen

123

The Nature of Optional Sibilant Harmony in Navajo  

E-Print Network [OSTI]

The Nature of Optional Sibilant Harmony in Navajo By Copyright 2010 Kelly Harper Berkson Submitted to the graduate degree program in... Linguistics and the Graduate Faculty of the University of Kansas in partial fulfillment of the requirements for the degree of Master of Arts...

Berkson, Kelly Harper

2010-12-03T23:59:59.000Z

124

EA-1961: Kalispell-Kerr Transmission Line Rebuild Project, Kalispell and Polson, Montana  

Broader source: Energy.gov [DOE]

Bonneville Power Administration is preparing an EA to evaluate potential environmental impacts of rebuilding its 41-mile long 115 kilovolt (kV) wood-pole Kalispell-Kerr transmission line between Kalispell and Polson, Montana. Additional information is available on the project website, http://efw.bpa.gov/environmental_services/Document_Library/KALISPELL_KERR/.

125

Amended Notice of Intent for the Northern Pass Transmission Line Project Published in the Federal Register  

Broader source: Energy.gov [DOE]

The Department of Energy announces its intent to modify the scope of the Northern Pass Transmission Line Project Environmental Impact Statement and to conduct additional public scoping meetings. The Federal Register Notice, which is now available for downloading, includes information on how to submit comments and participate in the additional public scoping meetings.

126

Mitigation Action Plan Phase I Lovell Yellowtail and Basin-Lovell Transmission Line Rebuild Project  

Broader source: Energy.gov (indexed) [DOE]

Mitigation Action Plan Phase I Lovell Yellowtail and Basin-Lovell Transmission Line Rebuild Project Big Horn and Carbon Counties, Montana and Big Horn County, Wyoming MITIGATION ACTION IDENTIFIER RESPONSIBLE PARTY FOR IMPLEMENTING MITIGATION ACTION LOCATION IF AVAILABLE/ STRUCTURE NUMBERS PARTY RESPONSIBLE FOR MONITORING AND ENSURING COMPLIANCE 1 Construction Contractor Western Maintenance Standard Construction Project Practices will be implemented through Phases I of Project construction and operation (Table 2.1-3 in the Final EA.) Western Construction (during Construction Phase) Western Maintenance (During maintenance of facility) NPS - WESTERN INTERAGENCY AGREEMENT FOR BIGHORN CANYON NRA 2 NPS, Western The Interagency Agreement between United

127

Schultz-Hanford Area Transmission Line Project, Final Environmental Impact Statement  

Broader source: Energy.gov (indexed) [DOE]

Final Environmental Impact Statement Final Environmental Impact Statement Bonneville Power Administration U.S. Department of Energy Bureau of Land Management Bureau of Reclamation Fish and Wildlife Service U.S. Department of Interior Department of Army U.S. Department of Defense January 2003 Final Environmental Impact Statement Responsible Agencies: U.S. Department of Energy, Bonneville Power Administration (BPA), Richland Operations Office (RL); U.S. Department of Defense, Department of Army (USDOA); U.S. Department of Interior, Bureau of Land Management (BLM), Bureau of Reclamation (BOR), Fish and Wildlife Service (USFWS). Title of Proposed Project: Schultz-Hanford Area Transmission Line Project - DOE/EIS-0325 State Involved: Washington Abstract: BPA proposes to construct a new 500-kilovolt (kV) transmission line in central Washington. This project

128

Schultz-Hanford Area Transmission Line Project Draft Environmental Impact Statement  

SciTech Connect (OSTI)

This summary covers the major points of the Draft Environmental Impact Statement (EIS) prepared for the BPA Schultz-Hanford Transmission Project proposed by the Bonneville Power Administration (BPA). The project involves constructing a new 500-kilovolt (kV) line in central Washington, north of Hanford. The new line would connect to an existing line at the Schultz Substation near Ellensburg and to a new or existing substation in the Hanford area (see Map 2 in EIS). The project may also involve constructing a new substation to accommodate the new transmission line. As a federal agency, BPA is required by the National Environmental Policy Act (NEPA) to take into account potential environmental consequences of its proposal and take action to protect, restore, and enhance the environment during and after construction. Preparation of this EIS assists in meeting those requirements.

N /A

2002-02-08T23:59:59.000Z

129

Bonneville Power Administration Grand Coulee-Bell 500-kV Transmission Line Project Record of Decision  

Broader source: Energy.gov (indexed) [DOE]

Grand Coulee-Bell 500-kV Transmission Line Project Grand Coulee-Bell 500-kV Transmission Line Project Record of Decision Decision The Bonneville Power Administration (BPA) has decided to construct the proposed Grand Coulee-Bell 500-kV Transmission Line Project in Douglas, Grant, Lincoln, and Spokane Counties, Washington. BPA has decided to implement the proposed action identified in the Grand Coulee-Bell 500-kV Transmission Line Project Final Environmental Impact Statement (DOE/EIS-0344, December 2002). The proposed action consists of constructing a new 500- kilovolt (kV) transmission line between the Bureau of Reclamation's (BOR) Grand Coulee 500- kV Switchyard near Grand Coulee, Washington, and BPA's Bell Substation near Spokane, a distance of 84 miles. The proposed action involves removing an existing 115-kV transmission

130

Plains & Eastern Clean Line Project Proposal for New or Upgraded Transmission Line Projects Under Section 1222 of the Energy Policy Act of 2005 (July 2010)  

Broader source: Energy.gov (indexed) [DOE]

PROJECT PROPOSAL PROJECT PROPOSAL FOR NEW OR UPGRADED TRANSMISSION LINE PROJECTS UNDER SECTION 1222 OF THE ENERGY POLICY ACT OF 2005 JULY 2010 TABLE OF CONTENTS INTRODUCTION 1. The Challenge ....................................................................................................................................... 1 2. The Solution .......................................................................................................................................... 1 SECTION I: STATUTORY CRITERIA 1. General Description of the Entity ................................................................................................... 4 2. Project Description ............................................................................................................................. 5

131

EA-1880: Big Bend to Witten Transmission Line Project, South Dakota  

Broader source: Energy.gov [DOE]

The USDA Rural Utilities Service, with DOE’s Western Area Power Administration as a cooperating agency, is preparing this EA to evaluate the environmental impacts of a proposal to construct a 70-mile long 230-kV single-circuit transmission line, a new Western Area Power Administration substation, an addition to the existing substation, and approximately 2 miles of 230-kV double-circuit transmission line, all in South Dakota. Proposed action is related to the Keystone XL project (see DOE/EIS-0433-S1).)

132

BPA/Puget Power Northwest Washington Transmission Project : Summary of the Supplemental Draft Environmental Statement.  

SciTech Connect (OSTI)

BPA and Puget Sound Power and Light (Puget Power) are proposing to upgrade the existing electric transmission power system in the Whatcom and Skagit County area of northwest Washington to increase the capacity of the US-Canada Intertie transmission system. The project would satisfy the need to provide more ability to store and return energy with Canada, would provide additional capacity on the Intertie for anticipated increases in power transactions, and would increase flexibility in operation of the US and Canadian hydroelectric system. It would protect Puget Power`s local system against thermal overloads, and improve local reliability. In November 1993, Bonneville Power Administration (BPA), and Whatcom County (Washington) published a draft environmental impact statement (DEIS) for the proposed Northwest Washington Transmission Project. In order to present some shifts in need for the project and to permit additional review, BPA and Whatcom County have elected to issue a Supplemental Draft EIS. This Summary presents background material, explains project needs and purposes, and then focuses on alternatives and the possible effects.

United States. Bonneville Power Administration.

1995-04-01T23:59:59.000Z

133

Navajo Tribal Utility Authority (Utah) | Open Energy Information  

Open Energy Info (EERE)

Authority (Utah) Authority (Utah) Jump to: navigation, search Name Navajo Tribal Utility Authority Place Utah Utility Id 13314 References Energy Information Administration.[1] LinkedIn Connections CrunchBase Profile No CrunchBase profile. Create one now! This article is a stub. You can help OpenEI by expanding it. Utility Rate Schedules Grid-background.png No rate schedules available. Average Rates Residential: $0.0967/kWh Commercial: $0.1150/kWh The following table contains monthly sales and revenue data for Navajo Tribal Utility Authority (Utah). Month RES REV (THOUSAND $) RES SALES (MWH) RES CONS COM REV (THOUSAND $) COM SALES (MWH) COM CONS IND_REV (THOUSAND $) IND SALES (MWH) IND CONS OTH REV (THOUSAND $) OTH SALES (MWH) OTH CONS TOT REV (THOUSAND $) TOT SALES (MWH) TOT CONS

134

Navajo Tribal Utility Authority (New Mexico) | Open Energy Information  

Open Energy Info (EERE)

Mexico) Mexico) Jump to: navigation, search Name Navajo Tribal Utility Authority Place New Mexico Utility Id 13314 References Energy Information Administration.[1] LinkedIn Connections CrunchBase Profile No CrunchBase profile. Create one now! This article is a stub. You can help OpenEI by expanding it. Utility Rate Schedules Grid-background.png No rate schedules available. Average Rates Residential: $0.1000/kWh Commercial: $0.1170/kWh Industrial: $0.0605/kWh The following table contains monthly sales and revenue data for Navajo Tribal Utility Authority (New Mexico). Month RES REV (THOUSAND $) RES SALES (MWH) RES CONS COM REV (THOUSAND $) COM SALES (MWH) COM CONS IND_REV (THOUSAND $) IND SALES (MWH) IND CONS OTH REV (THOUSAND $) OTH SALES (MWH) OTH CONS TOT REV (THOUSAND $) TOT SALES (MWH) TOT CONS

135

McNary-John Day Transmission Line Project, Final Environmental Impact Statement  

Broader source: Energy.gov (indexed) [DOE]

ENVIRONMENT, FISH AND WILDLIFE August 30, 2002 In reply refer to: T To: People Interested in the McNary-John Day Transmission Line Project Bonneville Power Administration (Bonneville) has finalized the enclosed Environmental Impact Statement (EIS) for the McNary-John Day Transmission Line Project. In March, we sent you the draft EIS, asked for your comments and had three public meetings. The response was great; we received about 350 comments on the draft document. Thank you for taking the time to read the document and tell us your ideas. This letter briefly describes the final EIS, outlines our next steps and tells where to call if you have questions. The final EIS is abbreviated, consisting of an introduction to the document, changes to the draft

136

Port Angeles-Juan de Fuca Transmission Project Draft Environmental Impact Statement  

Broader source: Energy.gov (indexed) [DOE]

This summary includes information regarding the following elements of the draft environmental impact statement (EIS) prepared for the Port Angeles-Juan de Fuca Transmission Project: * purpose and need for action; * Proposed Action and No Action Alternative; and * affected environment, environmental impacts, and mitigation measures. S.1 Purpose and Need for Action Sea Breeze Olympic Converter LP (Sea Breeze) has applied to the United States Department of Energy (DOE) for authorizations and approvals necessary to construct the U.S. portion of a proposed international electric power transmission cable. Specifically, Sea Breeze has applied to the Office of Electricity Delivery and Energy Reliability (DOE/OE), an organizational unit within DOE, for a Presidential permit for its project. Sea Breeze has also submitted a request to

137

EIS-0483: Estes to Flatiron Substation Transmission Lines Rebuild Project, Larimer County, Colorado  

Broader source: Energy.gov [DOE]

Western Area Power Administration (Western) – with USDA Forest Service, Arapaho and Roosevelt National Forest, as a cooperating agency – is preparing an EIS that analyzes the potential environmental impacts of a proposal to rebuild and upgrade two 115-kilovolt single-circuit transmission lines between the Flatiron Substation and the intersection of Mall Road and U.S. Highway 36 in Estes Park, Larimer County, Colorado. Additional information is available on Western’s project website.

138

McNary-John Day Transmission Line Project Record of Decision (DOE/EIs-0332), (11/08/02)  

Broader source: Energy.gov (indexed) [DOE]

McNary-John Day Transmission Line Project McNary-John Day Transmission Line Project Record of Decision Decision The Bonneville Power Administration (Bonneville) has decided to construct the proposed McNary-John Day Transmission Line Project in Benton and Klickitat Counties, Washington, and Sherman and Umatilla Counties, Oregon. Bonneville has decided to implement the proposed action identified in the McNary-John Day Transmission Line Project Final Environmental Impact Statement (DOE/EIS-0332, August 2002). The proposed action consists of building 79 miles of 500-kilovolt (kV) transmission line between Bonneville's McNary Substation and John Day Substation. As part of the proposed action, Bonneville has also decided to construct certain short-line routing alternatives identified in the Final EIS. These alternatives are the

139

EIS-0164: Pacific Gas Transmission/Pacific Gas and Electric and Altamont Natural Gas Pipeline Project  

Broader source: Energy.gov [DOE]

The Federal Energy Regulatory Commission (FERC) has prepared the PGT/PG&E and Altamont Natural Gas Pipeline Projects Environmental Impact Statement to satisfy the requirements of the National Environmental Policy Act. This project addresses the need to expand the capacity of the pipeline transmission system to better transfer Canadian natural gas to Southern California and the Pacific Northwest. The U.S. Department of Energy cooperated in the preparation of this statement because Section 19(c) of the Natural Gas Act applies to the Department’s action of authorizing import/export of natural gas, and adopted this statement by the spring of 1992. "

140

Canby Area Service Project : Substation and Associated Transmission Line : Environmental Assessment.  

SciTech Connect (OSTI)

Bonneville Power Administration (BPA) provides power to Surprise Valley Electrification Corporation (SVEC) in Modoc County, California. BPA uses PacificCorp's substation and transmission facilities between Alturas and Canby, California to transfer power to SVEC's Canby Substation. In the next year, SVEC expects increased industrial, agricultural, and residential electric loads on their 69-kV transmission system south of Canby. SVEC's substation can accommodate only about 10 percent of the expected additional electric load. BPA's proposed action is intended to meet SVEC's increasing electric load. BPA proposes to meet SVEC's increasing energy load by tapping into BPA's existing BPA Malin-Warner 230-kV transmission line, and building an 7.9-mile transmission line to a new BPA substation. BPA proposes to build the new substation next to the west side of SVEC's Canby Substation (Figure 1). This new substation will allow SVEC to move the additional power over their existing transmission or distribution lines. This report is the environmental assessment of the potential impact of the proposed project. The assessment determined that no environmental impact statement'' is not required.

United States. Bonneville Power Administration.

1992-02-01T23:59:59.000Z

Note: This page contains sample records for the topic "navajo transmission project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


141

Canby Area Service Project substation and associated transmission line. Environmental Assessment  

SciTech Connect (OSTI)

Bonneville Power Administration (BPA) provides power to Surprise Valley Electrification Corporation (SVEC) in Modoc County, California. BPA uses PacificCorp`s substation and transmission facilities between Alturas and Canby, California to transfer power to SVEC`s Canby Substation. In the next year, SVEC expects increased industrial, agricultural, and residential electric loads on their 69-kV transmission system south of Canby. SVEC`s substation can accommodate only about 10 percent of the expected additional electric load. BPA`s proposed action is intended to meet SVEC`s increasing electric load. BPA proposes to meet SVEC`s increasing energy load by tapping into BPA`s existing BPA Malin-Warner 230-kV transmission line, and building an 7.9-mile transmission line to a new BPA substation. BPA proposes to build the new substation next to the west side of SVEC`s Canby Substation (Figure 1). This new substation will allow SVEC to move the additional power over their existing transmission or distribution lines. This report is the environmental assessment of the potential impact of the proposed project. The assessment determined that no ``environmental impact statement`` is not required.

Not Available

1992-02-01T23:59:59.000Z

142

Survey of Transmission Cost Allocation Methodologies for Regional Transmission Organizations  

SciTech Connect (OSTI)

The report presents transmission cost allocation methodologies for reliability transmission projects, generation interconnection, and economic transmission projects for all Regional Transmission Organizations.

Fink, S.; Porter, K.; Mudd, C.; Rogers, J.

2011-02-01T23:59:59.000Z

143

Kangley - Echo Lake Transmission Line Project Supplemental Draft Environmental Impact Statement  

SciTech Connect (OSTI)

Bonneville Power Administration (BPA) is proposing to build a new transmission line to accommodate increasing demand for electricity and address reliability concerns in the Puget Sound area. The Proposed Action would construct a new line that would connect to an existing transmission line near the community of Kangley, and then connect with BPA's existing Echo Lake Substation. The major purpose of this proposal is to improve system reliability in the King County area. An outage on an existing line during times of heavy use, such as during a winter cold snap, could cause voltage instability and a loss of power in the King County area. System planners have projected total system load using normal growth in demand and determined that system instability could develop as early as the winter of 2002-03. Besides meeting this need for system reliability, this project would enhance the United States' delivery of power to Canada as required under the Columbia River Treaty of 1961. BPA described and analyzed transmission route alternatives in a draft environmental impact statement (DEIS) released in June 2001. The DEIS identified a preferred alternative that would parallel an existing BPA transmission line through the Cedar River Municipal Watershed. BPA received over 700 comments from landowners, agencies, tribes and special interest groups on the DEIS. Many of the comments suggested BPA re-evaluate the range of alternatives considered and prepare a supplemental draft environmental impact statement (SDEIS). After reviewing the comments and refining the cost estimates associated with BPA's preferred alternative, BPA decided to prepare this SDEIS to re-evaluate alternatives not analyzed in detail in the DEIS. The added transmission alternatives, all located outside of the Cedar River Watershed, were initially considered but dropped from detailed analysis. They are identified as Alternatives A, B, C, and D. Alternatives A and C are located to the west of the Cedar River Watershed boundary. Alternatives B and D cross the Mt. Baker-Snoqualmie and Okanogan-Wenatchee National Forests. Under all transmission alternatives, Echo Lake Substation would be expanded about three acres to the east and new equipment to accommodate the new line would be installed. BPA is also considering a Non-Transmission Alternative and the No Action Alternative.

N /A

2003-01-10T23:59:59.000Z

144

Supplemental Draft Environmental Impact StatementS Big Stone II Power Plant and Transmission Project  

Broader source: Energy.gov (indexed) [DOE]

Lead Agency: U.S. Department of Energy, Western Area Power Administration Lead Agency: U.S. Department of Energy, Western Area Power Administration Cooperating Agencies: U.S. Department of Agriculture, Rural Utilities Service U.S. Department of Defense, Army Corps of Engineers Title: Big Stone II Power Plant and Transmission Project Supplemental Draft Environmental Impact Statement Location: Proposed Big Stone II Plant: Big Stone City, South Dakota Proposed Transmission Facilities: Northeastern South Dakota and Southwestern Minnesota Contacts: For additional information on this Supplemental Draft Environmental Impact Statement, or to receive a copy, contact: For general information on the DOE National Environmental Policy Act process, write or call: Ms. Nancy Werdel Western Area Power Administration

145

Marys Lake 69/115-kV transmission line upgrade and substation expansion projects  

SciTech Connect (OSTI)

Western Area Power Administration (Western) and the Platte River Power Authority (Platte River) propose to upgrade portions of the existing electric transmission and substation system that serves the Town of Estes Park, Colorado. The existing transmission lines between the Estes Power Plant Switchyard and the Marys Lake Substation include a 115,000 volt (115-kV) line and 69,000 volt (69-kV) line. Approximately one mile is a double-circuit 115/69-kV line on steel lattice structures, and approximately two miles consists of separate single-circuit 115-kV and a 69-kV lines, constructed on wood H-Frame structures. Both lines were constructed in 1951 by the US Bureau of Reclamation. The existing transmission lines are on rights-of-way (ROW) that vary from 75 feet to 120 feet and are owned by Western. There are 48 landowners adjacent to the existing ROW. All of the houses were built adjacent to the existing ROW after the transmission lines were constructed. Upgrading the existing 69-kV transmission line between the Marys Lake Substation and the Estes Power Plant Switchyard to 115-kV and expanding the Marys Lake Substation was identified as the most effective way in which to improve electric service to Estes Park. The primary purpose and need of the proposed project is to improve the reliability of electric service to the Town of Estes Park. Lack of reliability has been a historical concern, and reliability will always be less than desired until physical improvements are made to the electrical facilities serving Estes Park.

NONE

1996-05-01T23:59:59.000Z

146

Wallula Power Project and Wallula - McNary Transmission Line Project, Final Environmental Impact Statement  

Broader source: Energy.gov (indexed) [DOE]

Final EIS Appendix A: Revised Mitigation Measures Final EIS Appendix A: Revised Mitigation Measures August 2002 Page A-1 Appendix A Revised Mitigation Measures The proposed project includes measures that would limit construction and operation impacts to elements of the natural and human environment. These measures are presented for each element of the environment identified as a potential concern by Bonneville and EFSEC based on preliminary environmental review and public and regulatory agency input. Updates to the mitigation table below are in response to comments on the Draft EIS or to incorporate new information included in the Settlement Agreements. Mitigation Measure Power Plant Pipelines Bonneville T-Line EARTH Seismicity Facilities would be designed to meet regional seismic design criteria as presented in the Uniform Building Code (UBC). X X

147

Moving Beyond Paralysis: How States and Regions Are Creating Innovative Transmission Projects; May 2009 - May 2010  

SciTech Connect (OSTI)

This report profiles certain state and regional transmission policy initiatives aimed at promoting transmission development, mainly to access renewable resources.

Schumacher, A.; Fink, S.; Porter, K.

2009-10-01T23:59:59.000Z

148

Final Environmental Assessment for the Cheyenne-Miracle Mile and Ault-Cheyenne Transmission Line Rebuild Project  

Broader source: Energy.gov (indexed) [DOE]

Assessment Assessment Cheyenne-Miracle Mile and Ault-Cheyenne Transmission Line Rebuild Project DOE/EA -1456 U.S. Department of Energy Western Area Power Administration Rocky Mountain Region Loveland, Colorado October 2006 Final Environmental Assessment Cheyenne-Miracle Mile and Ault-Cheyenne Transmission Line Rebuild Project DOE/EA-1456 U.S. Department of Energy Western Area Power Administration Rocky Mountain Region Loveland, Colorado October 2006 Table of Contents CH-MM & AU-CH Transmission Line Rebuild Table of Contents i Table of Contents Summary ......................................................................................................................................... 1 1.0 Introduction ..................................................................................................................

149

Final environmental impact statement, Washington Water Power/B.C. Hydro Transmission Interconnection Project  

SciTech Connect (OSTI)

Washington Water Power (WWP) proposes to construct and operate an electric transmission line that would connect with the electrical system of the British Columbia Hydro and Power Authority (B.C. Hydro). The project would be composed of a double-circuit, 230-kilovolt (kV) transmission line from WWP`s existing Beacon Substation located northeast of Spokane, Washington to the international border located northwest of Metaline Falls, Washington. The original Presidential permit application and associated proposed route presented in the draft environmental impact statement (DEIS) have been modified to terminate at the Beacon Substation, instead of WWP`s initially proposed termination point at the planned Marshall Substation located southwest of Spokane. A supplemental draft EIS was prepared and submitted for review to not only examine the new proposed 5.6 miles of route, but to also compare the new Proposed Route to the other alternatives previously analyzed in the DEIS. This final EIS (FEIS) assesses the environmental effects of the proposed transmission line through construction, operation, maintenance, and abandonment activities and addresses the impacts associated with the Proposed Action, Eastern Alternative, Western Alternative, Northern Crossover Alternative, Southern Crossover Alternative, and No Action Alternative. The FEIS also contains the comments received and the responses to these comments submitted on the DEIS and Supplemental DEIS.

Not Available

1992-10-01T23:59:59.000Z

150

McNary-John Day Transmission Line Project Draft Environmental Impact Statement  

SciTech Connect (OSTI)

Bonneville is proposing to construct, operate, and maintain a 79-mile-long 500-kilovolt-transmission line in Benton and Klickitat Counties, Washington, and Umatilla and Sherman counties, Oregon. The new line would start at Bonneville's McNary Substation in Oregon and would cross the Columbia River just north of the substation into Washington. The line would then proceed west for about 70 miles along the Columbia River. At the John Day Dam, the line would again cross the Columbia River into Oregon and terminate at Bonneville's John Day Substation. The new line would parallel existing transmission lines for the entire length; mostly within existing available right-of-way. Presently, the existing transmission lines in the area are operating at capacity. These lines help move power from the east side of the Cascades to the west side, where there is a high need for electricity (cities along the I-5 corridor). Because the Northwest has only recently recovered from a shortfall in electric energy supply and a volatile wholesale power market in which prices reached record highs, there are many new proposals for facilities to generate new power. Some of these facilities are in the vicinity of the McNary-John Day project; the proposed line would help insure that existing and newly generated power could move through the system. Bonneville is also considering the No Action Alternative and several short-line routing alternatives. The short routing alternatives include three half-mile-long routes for getting from the McNary Substation to the Columbia River crossing; three two-mile-long routes where the Hanford-John Day transmission line joins the existing corridor; two 1,000-foot-long routes at corridor mile 32; and two 500-foot-long routes at corridor mile 35.

N /A

2002-03-08T23:59:59.000Z

151

EIS-0450: TransWest Express 600 kV Direct Current Transmission Project in Wyoming, Colorado, Utah, and Nevada  

Broader source: Energy.gov [DOE]

This EIS, being prepared jointly by DOE’s Western Area Power Administration and the Department of the Interior’s Bureau of Land Management (Wyoming State Office), evaluates the environmental impacts of granting a right-of-way for the TransWest Express 600-kilovolt Direct Current Transmission Project and amending a land use plan. The project consists of an overhead transmission line that would extend approximately 725 miles from south-central Wyoming, through Colorado and Utah. Western proposes to be a joint owner of the project.

152

Navajo Wind Energy | Open Energy Information  

Open Energy Info (EERE)

Wind Energy Wind Energy Place Atlanta, Georgia Zip 30318 Sector Wind energy Product Atalanta-based but China-focused wind project developer. Coordinates 33.748315°, -84.391109° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[{"text":"","title":"","link":null,"lat":33.748315,"lon":-84.391109,"alt":0,"address":"","icon":"","group":"","inlineLabel":"","visitedicon":""}]}

153

Montana-to-Washington Transmission System Upgrade Project - M2W  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

an existing BPA transmission line, and the proposed addition of a new series compensation substation along other existing BPA transmission lines. To understand the potential...

154

BPA/Puget Power Northwest Washington Transmission Project Final Environmental Impact Statement.  

SciTech Connect (OSTI)

Bonneville Power Administration (BPA) and Puget Sound Power & Light Company (Puget Power) propose to upgrade the existing high-voltage transmission system in the Whatcom and Skagit counties area between the towns of Custer and Sedro Woolley, including some areas within the City of Bellingham, starting in 1995. A Draft Environmental Impact Statement (DEIS) for the project was issued in November 1993, followed by a 45-day public comment period. Public response to the DEIS included the identification of several new transmission route alternatives in the Lake Whatcom area. BPA issued a Supplemental DEIS in April 1995 to provide a second public review-and-comment period. Rebuilding an existing 230-kV line to a double-circuit 230-kV transmission line was identified in the Supplemental DEIS as the Proposed Action. The Supplemental DEIS also examined in detail a North Shore Road alternative which was proposed by some members of the public. Public comments on the EIS were listed and responded to in the Supplemental DEIS. In May 1995, a second set of open houses and public meetings was held to review the Supplemental DEIS. Electromagnetic field (EMF) effects raised as an issue in the DEIS continued to be an issue of public concern in the meetings. The EIS has identified impacts that would generally be classified as low to moderate and localized. Effects on soils and water resources in sensitive areas (e.g., near Lake Whatcom) would be low to moderate; there would be little change in magnetic fields; noise levels would remain at existing levels; and land use and property value impacts would be minimal. Threatened and endangered species would not be adversely affected, and all proposed actions in wetlands would be covered by a Corps of Engineers Nationwide Permit. Visual and socioeconomic would be low to moderate. There would be no effect on cultural resources.

United States. Bonneville Power Administration.

1995-08-01T23:59:59.000Z

155

DOE/EA-1470: Environmental Assessment Harry Allen-Mead 500 kV Transmission Line Project Environmental Assessment  

Broader source: Energy.gov (indexed) [DOE]

the the Interior Bureau of Land Management Las Vegas Field Office Las Vegas, Nevada March 2004 Interstate Intertie Centennial Plan Environmental Assessment Harry Allen - Mead 500kV Transmission Line DOE/EA-1470 Harry Allen-Mead 500kV Transmission Line Project Harry Allen-Mead 500kV Transmission Line Environmental Assessment 1 Chapter 1 Purpose and Need 1.1 Introduction The construction of new transmission and distribution facilities is required throughout the western United States to meet the increasing demand for power as more people move to many of the fastest growing communities. According to Executive Order 13212 dated May 18, 2001, "The increased production and transmission of energy in a safe and environmentally sound manner is essential to the well-being of the American people...agencies shall take appropriate actions, to the extent

156

Data Collection for the Bonneville Power Administration Project on Wind Loading of Transmission Conductors  

Science Journals Connector (OSTI)

ABSTRACT The Bonneville Power Administration (BPA) project, “Wind Effects on Conductors for Span Factors” was established to determine the relationship between actual and theoretical wind loads on overhead transmission conductors. This study aims to improve BPA transmission line design methods and criteria as they relate to wind conditions in the Pacific Northwest. For the past seven years, BPA has collected data from seven sites in the Pacific Northwest. Measurements of wind speeds and directions, ambient temperatures and barometric pressures, and conductor swing angles enable engineers to compare measured wind loads on conductors to theoretical values. Impact of such variables as height of conductor, span lengths and conductor diameter are also investigated. Three sites were instrumented with vertically arranged anemometers to measure wind speed as a function of height above ground. This paper covers site determination, instrumentation, data collection, and some site maintenance and operation challenges. The maintenance and manipulation of the very large data base that has been collected is discussed. As data analysis is not yet finished, final results are not included.

H.W. VOLPE

1987-01-01T23:59:59.000Z

157

Mitigation Action Plan for Los Banos - Gates (Path 15) Transmission Project (DOE/EIS-0128) (12/3/03)  

Broader source: Energy.gov (indexed) [DOE]

2 Date: December 3, 2003 1 2 Date: December 3, 2003 1 Western Area Power Administration Mitigation Action Plan for the Los Banos - Gates (Path 15) Transmission Project 1.0 INTRODUCTION 1.1 HISTORY AND BACKGROUND In May 2001, Secretary of Energy Spencer Abraham directed the Western Area Power Administration (Western) to take the first steps, including the preparation of environmental studies, toward developing the Los Banos - Gates Transmission Project, also known as the Path 15 Project. This directive was issued to carry out a recommendation in the May 2001 National Energy Policy. Western is a power marketing administration within the Department of Energy (DOE) whose role is to market and transmit electricity from multi-use water projects in the western United States, including California. The Path 15 Project, located in California's western

158

Liberty-Parker No. 2 230-kV transmission line project, La Paz and Maricopa Counties, Arizona: Environmental assessment  

SciTech Connect (OSTI)

The proposed project was not found to have the potential for significant impact on the human environment. The proposed project is essentially a rebuild of an existing transmission line on an existing right-of-way (ROW) through mostly unpopulated open desert. Analysis of the proposed action and its potential effects on various environmental components showed that the project would not significantly affect climate, air quality, noise levels, topography, geology, or soils. No significant impact would occur to vegetation or wildlife as a result of the project. Visual resources will not be significantly affected, as both the existing Liberty-Parker No. 2 Transmission Line and its parallel sister No. 1 line are already present. Land ownership, land use, and socioeconomics will not be significantly affected. No significant cultural resources will be affected by the proposed project. The lines will be constructed on areas previously surveyed for cultural resources and the site density of this region is known to be very low.

Not Available

1986-09-01T23:59:59.000Z

159

Environmental Assessment of the Gering-Stegall 115-kV Transmission Line Consolidation Project, Scotts Bluff County, Nebraska  

SciTech Connect (OSTI)

The Department of Energy (DOE), Western Area Power Administration (Western) proposes to consolidate segments of two transmission lines near the Gering Substation in Gering, Nebraska. The transmission lines are both located in Scotts Bluff County, Nebraska. The transmission lines are both located in Scotts Bluff County, Nebraska, within the city of Gering. Presently, there are three parallel 115-kilovolt (kV) transmission lines on separate rights-of-way (ROW) that terminate at the Gering Substation. The project would include dismantling the Archer-Gering wood-pole transmission line and rebuilding the remaining two lines on single-pole steel double circuit structures. The project would consolidate the Gering-Stegall North and Gering-Stegall South 115-kV transmission lines on to one ROW for a 1.33-mile segment between the Gering Substation and a point west of the Gering Landfill. All existing wood-pole H-frame structures would be removed, and the Gering-Stegall North and South ROWs abandoned. Western is responsible for the design, construction, operation, and maintenance of the line. Western prepared an environmental assessment (EA) that analyzed the potential environmental impacts of the proposed construction, operation, and maintenance of the 115-kV transmission line consolidation. Based on the analyses in the EA, the DOE finds that the proposed action is not a major Federal action significantly affecting the quality of the human environment, within the meaning of the National Environmental Policy Act of 1969 (NEPA).

NONE

1995-05-01T23:59:59.000Z

160

HQ State HQ City Name of Primary Selectee Project Type Project Title and Brief Project Description  

Broader source: Energy.gov (indexed) [DOE]

Total Project Value Total Project Value Including Cost Share AZ Fort Defiance Navajo Tribal Utility Authority Company Smart Grid Workforce Training (Topic B) Navajo Tribal Utility Authority Smart Grid Workforce Training Program - Develop a workforce that is well-trained and committed to the mission of modernizing NTUA's distribution services, including an expeditious and well- built smart grid system. The training program is designed to maximize employment opportunities for citizens of the Navajo Nation located on the reservation. Arizona New Mexico $704,486 $1,408,971 $704,486 $1,408,971 Glendale Glendale Community College Developing and Enhancing Workforce Training Programs (Topic A) Southern California Utility Initiative - Expand training curricula and programs in the Southern California region. The project will raise awareness and

Note: This page contains sample records for the topic "navajo transmission project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


161

McNary-John Day Transmission Line Project, Final Environmental Impact Statement  

SciTech Connect (OSTI)

Bonneville is proposing to construct, operate, and maintain a 79-mile-long 500-kilovolt-transmission line in Benton and Klickitat Counties, Washington, and Umatilla and Sherman Counties, Oregon. The new line would start at Bonneville's McNary Substation in Oregon and would cross the Columbia River just north of the substation into Washington. The line would then proceed west for about 70 miles along the Columbia River. At the John Day Dam, the line would again cross the Columbia River into Oregon and terminate at Bonneville's John Day Substation. The new line would parallel existing transmission lines for the entire length; mostly within existing available right-of-way. Presently, the existing transmission lines in the area are operating at capacity. These lines help move power from the east side of the Cascades to the west side, where there is a high need for electricity (cities along the I-5 corridor). Because the Northwest has only recently recovered from a shortfall in electric energy supply and a volatile wholesale power market in which prices reached record highs, there are many new proposals for facilities to generate new power. Some of these facilities are in the vicinity of the McNary-John Day project; the proposed line would help insure that existing and newly generated power could move through the system. Bonneville is also considering the No Action Alternative and several short-line routing alternatives. The short routing alternatives include three half-mile-long routes for getting from the McNary Substation to the Columbia River crossing; three two-mile-long routes where the Hanford-John Day transmission line joins the existing corridor; two 1,000-foot-long routes at corridor mile 32; and two 500-foot-long routes at corridor mile 35. This abbreviated final EIS consists of an introduction to the document, changes to the draft EIS, copies of all the comments received on the draft EIS, and Bonneville's written responses to the comments. The final EIS should be used as a companion document to the draft EIS (dated February 2002), which contains the full text of the affected environment, environmental analysis, and appendices.

N /A

2002-08-30T23:59:59.000Z

162

(DOE/EIS-0128): Mitigation Action Plan for the Los Banos-Gates Transmission project 1/28/03  

Broader source: Energy.gov (indexed) [DOE]

Date: ____________________________ 1 Date: ____________________________ 1 Western Area Power Administration Mitigation Action Plan for the Los Banos - Gates (Path 15) Transmission Project 1.0 INTRODUCTION 1.1 HISTORY AND BACKGROUND In May 2001, Secretary of Energy Spencer Abraham directed the Western Area Power Administration (Western) to take the first steps, including the preparation of environmental studies, toward developing the Los Banos - Gates Transmission Project, also known as the Path 15 Project. This directive was issued to carry out a recommendation in the May 2001 National Energy Policy. Western is a Power Marketing Administration within the Department of Energy (DOE) whose role is to market and transmit electricity from multi- use water projects in the western United States, including California. The

163

DOE/EIS-0332; McNary-John Day Transmission Line Project Draft Envrionmental Impact Statement(02/2002)  

Broader source: Energy.gov (indexed) [DOE]

McNary-John Day Transmission Line Project McNary-John Day Transmission Line Project Draft Environmental Impact Statement (DOE/EIS -0332) Responsible Agency: Bonneville Power Administration (Bonneville), U.S. Department of Energy (DOE) Cooperating Agencies: U.S. Department of Interior: U.S. Fish and Wildlife Service, Bureau of Land Management, and Bureau of Indian Affairs. Department of Army: Corps of Engineers. States Involved: Oregon and Washington Abstract: Bonneville is proposing to construct, operate, and maintain a 79-mile-long 500-kilovolt- transmission line in Benton and Klickitat Counties, Washington, and Umatilla and Sherman counties, Oregon. The new line would start at Bonneville's McNary Substation in Oregon and would cross the Columbia River just north of the substation into Washington. The line would then proceed west for about

164

OE Issues Notice of Intent to Prepare an Environmental Impact Statement for the Plains & Eastern Clean Line Transmission Project  

Broader source: Energy.gov [DOE]

On December 21, 2012, DOE’s Office of Electricity Delivery and Energy Reliability (OE) issued a Notice of Intent (NOI) to Prepare an Environmental Impact Statement (EIS) for the Plains & Eastern Clean Line Transmission Project on behalf of the Department and Southwestern Power Administration

165

EIS-0484: Montana-to-Washington Transmission System Upgrade Project in Washington, Idaho, and Montana  

Broader source: Energy.gov [DOE]

This EIS will evaluate the environmental impacts of a proposal to replace roughly 12 miles of transmission line on the Taft-Dworshak 500-kV transmission line, install new series capacitors on the Garrison-Taft 500-kV transmission line, and perform various upgrades to Bell, Hatwai, Dworshak, Garrison, and Hot Springs substations.

166

EA-1982: Parker-Davis Transmission System Programmatic Operations and Maintenance Project; Arizona, California, and Nevada  

Broader source: Energy.gov [DOE]

Western Area Power Administration (Western) is preparing an EA to assess potential environmental impacts of the proposed continuation of operations and maintenance activities and implementation of a vegetation management program on Western’s Parker-Davis Transmission System. These actions would occur on existing transmission line and access road rights-of-way, and at substations and maintenance facilities associated with the transmission system.

167

Analysis of dc harmonics using the three-pulse model for the intermountain power project HVDC transmission  

SciTech Connect (OSTI)

The harmonic analysis of the dc-side of an HVDC line transmission requires realistic models of the converters, the dc line, and other relevant equipment. These models must include all important paths for harmonic current, and appropriate sources of harmonic voltage generation. The classical converter modeling technique has been demonstrated to be insufficient in field measurements and analysis of the harmonic spectra found on recent HVDC line transmission. For this reason, a new model of the converter bridge which takes into account the major stray capacitances in the converter (the three-pulse model) has been developed, and is described in detail elsewhere. This paper presents comparisons between the classical and three-pulse calculations for the Intermountain Power Project (IPP) HVDC transmission. The calculation results from the three-pulse model agree favorably with the harmonics found in field measurements.

Dickmander, D.L.; Peterson, K.J.

1989-04-01T23:59:59.000Z

168

Wholesale Power and Transmission Rate Projections 1993--2014 and Historical Wholesale Power Rates 1939--1992.  

SciTech Connect (OSTI)

This document provides a range of high, medium, and low case long-term projections of Bonneville Power Administration`s (BPA) wholesale power rates and a medium case long-term projection of BPA`s wheeling rates. These projections are produced annually by BPA. BPA uses these projections in long-term marketing, resource, transmission, and financial planning assessments. BPA`s projections also are used by public utility commissions, utilities, and others for a variety of planning purposes. The analysis used for these rate projections assumes that current rate making methodologies continue into the future and are further based on certain assumptions about regional loads, extra-regional markets, the costs of resources, BPA`s financial requirements, and the capability of the region`s power plants. While these projections are intended to address the overall uncertainty in rate levels, BPA realizes that the future will not reflect any specific set of assumptions. The rate projections in this document have been prepared prior to the Draft 1993 BPA Marketing Plan, the implementation of which is almost certain to push BPA away from any set of assumptions in this document. Therefore, this document can be thought of as representing the ``old`` BPA with its products and policies. It can be viewed as a starting point or reference point to measure the impact of the ``new`` BPA with its Marketing Plan, and the broader undertaking referred to as the Competitiveness Project.

US Bonneville Power Administration

1993-11-01T23:59:59.000Z

169

EIS-0134: Charlie Creek-Belfield Transmission Line Project, North Dakota  

Broader source: Energy.gov [DOE]

The Western Area Power Administration developed this EIS to assess the environmental impact of constructing a high voltage transmission line between Charlie Creek and Belfield, North Dakota, and a new substation near Belfield to as a means of adding transmission capacity to the area.

170

Renewable Resource Integration Project - Scoping Study of Strategic Transmission, Operations, and Reliability Issues  

SciTech Connect (OSTI)

California is on a path to increase utilization of renewable resources. California will need to integrate approximately 30,000 megawatts (MW) of new renewable generation in the next 20 years. Renewable resources are typically located in remote locations, not near the load centers. Nearly two/thirds or 20,000 MW of new renewable resources needed are likely to be delivered to Los Angeles Basin transmission gateways. Integration of renewable resources requires interconnection to the power grid, expansion of the transmission system capability between the backbone power grid and transmission gateways, and increase in delivery capacity from transmission gateways to the local load centers. To scope the transmission, operations, and reliability issues for renewables integration, this research focused on the Los Angeles Basin Area transmission gateways where most of new renewables are likely. Necessary actions for successful renewables integration include: (1) Expand Los Angeles Basin Area transmission gateway and nomogram limits by 10,000 to 20,000 MW; (2) Upgrade local transmission network for deliverability to load centers; (3) Secure additional storage, demand management, automatic load control, dynamic pricing, and other resources that meet regulation and ramping needed in real time operations; (4) Enhance local voltage support; and (5) Expand deliverability from Los Angeles to San Diego and Northern California.

Eto, Joseph; Budhraja, Vikram; Ballance, John; Dyer, Jim; Mobasheri, Fred; Eto, Joseph

2008-07-01T23:59:59.000Z

171

DOE/EA-1470: Environmental Assessment Harry Allen-Mead 500 kV Transmission Line Project Environmental Assessment  

Broader source: Energy.gov (indexed) [DOE]

4 4 DOE/EA-1470 DEPARTMENT OF ENERGY Western Area Power Administration Finding of No Significant Impact and Floodplain Statement of Findings Nevada Power Company's Harry Allen-Mead 500-kV Transmission Line Project Summary - Nevada Power Company (Nevada Power) proposes to build a 48- mile, 500-kilovolt (kV) transmission line between the Harry Allen Substation, northeast of Las Vegas Nevada, and the Mead Substation, southeast of Las Vegas (Proposed Action). The project would be part of the Interstate Intertie of the Centennial Plan. Of the 48 miles, 32 miles are within lands managed by the Bureau of Land Management (BLM), 8 miles are within lands managed by the US Bureau of Reclamation (USBR), and 4 miles are within lands managed by Western Area

172

DOE/EA-1635: Environmental Assessment for Pre-approval Review Williston to Tioga Transmission Line Project (March 2010)  

Broader source: Energy.gov (indexed) [DOE]

Environmental Assessment for Pre-approval Review DOE/EA - 1635 Williston to Tioga Transmission Line Project Environmental Assessment for Pre-approval Review DOE/EA - 1635 Williston to Tioga Transmission Line Project Environmental Assessment for Pre-approval Review DOE/EA - 1635 March 2010 Acronyms and Abbreviations °C degrees Celsius AAQS Ambient Air Quality Standards AIRFA American Indian Religious Freedom Act of 1978 amsl above mean sea level APLIC Avian Power Line Interaction Committee BEPC Basin Electric Power Cooperative BFE Base Flood Elevation BGEPA Bald and Golden Eagle Protection Act BMP best management practice CFR Code of Federal Regulations CO 2 carbon dioxide Council Advisory Council on Historic Preservation CRP Conservation Reserve Program

173

HQ State HQ City Name of Primary Selectee Project Type Project Title and Brief Project Description  

Broader source: Energy.gov (indexed) [DOE]

Participant Participant Share Total Project Value Including Cost Share AZ Fort Defiance Navajo Tribal Utility Authority Company Smart Grid Workforce Training (Topic B) Navajo Tribal Utility Authority Smart Grid Workforce Training Program - Develop a workforce that is well-trained and committed to the mission of modernizing NTUA's distribution services, including an expeditious and well-built smart grid system. The training program is designed to maximize employment opportunities for citizens of the Navajo Nation located on the reservation. Arizona New Mexico $704,486 $704,486 $1,408,972 $704,486 $704,486 $1,408,972 Glendale Glendale Community College Developing and Enhancing Workforce Training Programs (Topic A) Southern California Utility Initiative - Expand training curricula and

174

DOE/EIS-0332: McNary-John Day Transmission Line Project Supplement Analysis (DOE/EIS-0332-SA-1) (02/09/09)  

Broader source: Energy.gov (indexed) [DOE]

09 09 REPLY TO ATTN OF: KEC-4 SUBJECT: McNary-John Day Transmission Line Project Supplement Analysis (DOE/EIS-0332/SA-1) Mark Korsness, Project Manager, McNary-John Day Transmission Line Project Proposed Action: McNary-John Day Transmission Line - Review for significant new circumstances or information Proposed by: Bonneville Power Administration (BPA) Location: Umatilla and Sherman Counties, Oregon; Benton and Klickitat Counties, Washington. Background: In 2002, BPA completed the McNary-John Day Transmission Line Project Final Environmental Impact Statement (EIS) (DOE/EIS-0332). The Final EIS analyzed the potential impacts of constructing, maintaining, and operating a new 79-mile, 500-kV transmission line between BPA's McNary and John Day substations. This line was proposed in early 2000 to

175

Record of Decision for the Fourmile Hill Geothermal Development Project Power Purchase and Transmission Service Agreements (DOE/EIS-0266) (11/20/00)  

Broader source: Energy.gov (indexed) [DOE]

BONNEVILLE POWER ADMINISTRATION BONNEVILLE POWER ADMINISTRATION Fourmile Hill Geothermal Development Project Power Purchase and Transmission Service Agreements Administrator's Record of Decision Summary The Bonneville Power Administration (BPA) has decided to execute Transmission Services Agreements (TSAs) and Power Purchase Agreements (PPAs) with Calpine Siskiyou Geothermal Partners, L.P. (Calpine) to acquire output from the Fourmile Hill Geothermal Development Project (Project). Initially, BPA will execute one or more PPAs in order to acquire up to the entire Project output. TSAs will be executed before the Project becomes operational. The United States Forest Service (Forest Service) and the Bureau of Land Management (BLM) were the joint lead Federal agencies in the preparation of

176

EIS-0332: McNary-John Day Transmission Line Project, OR  

Broader source: Energy.gov [DOE]

This EIS analyzes BPA's decision to construct, operate, and maintain a 79-mile-long 500-kilovolt transmission line in Benton and Klickitat Counties, Washington, and Umatilla and Sherman counties, Oregon.

177

EA-1952: Lane-Wendson No. 1 Transmission Line Rebuild Project; Lane County, Oregon  

Broader source: Energy.gov [DOE]

Bonneville Power Administration is preparing an EA to assess the potential environmental impacts of the proposed rebuild of the 41.3-mile Lane-Wendson No. 1 transmission line between Eugene and Florence, Oregon.

178

EIS-0011: New Melones 230-kV Electrical Transmission Line, Central Valley Project, California  

Broader source: Energy.gov [DOE]

The U.S. Department of Energy's Western Area Power Administration prepared this statement to evaluate the environmental impacts of proposed development of an electrical transmission system for the New Melones Power Plant.

179

Kangley-Echo Lake Transmission Line Project Final Environmental Impact Statement  

SciTech Connect (OSTI)

BPA proposes to build a single-circuit 500-kV transmission line from a tap point on an existing 500-kV line near Kangley, Washington, to its Echo Lake Substation near North Bend, Washington. The proposed route for this line, also called Alternative 1, is about nine miles long. About five miles of the proposed route would go through the Cedar River Municipal Watershed. In addition, Echo Lake Substation would be expanded about three acres to the east and new equipment would be installed there to accommodate the new line (common to all transmission alternatives). This alternative was proposed because it would be located immediately parallel to an existing BPA existing 500-kV transmission line, the Raver-Echo Lake Transmission Line. Locating a new line next to an existing one reduces right-of-way (ROW) clearing needed for the new line and reduces the need for additional access roads. Lattice steel transmission towers would support the 500-kV transmission line. These structures average 135 feet high, with the average span between towers of about 1,150 feet.

N /A

2003-06-20T23:59:59.000Z

180

Environmental Assessment for the USK Loop Line 230 kV Transmission Project.  

SciTech Connect (OSTI)

This Environmental Assessment (EA) covers the transmission/substation facilities that would be constructed or modified. It has been prepared by an interdisciplinary team, as well as through consultation on the Federal, state and local levels. It is subject to a 60-day review by the general public and other agencies and will generally coincide with the release of the final state EIS. This EA presents an expansion of those transmission-related discussions in the state EIS where BPA could undertake their construction or modifiction.

United States. Bonneville Power Administration.

1985-09-01T23:59:59.000Z

Note: This page contains sample records for the topic "navajo transmission project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


181

EA-1948: Gila-North Gila Transmission Line Rebuild and Upgrade Project, Yuma County, Arizona  

Broader source: Energy.gov [DOE]

DOE’s Western Area Power Administration (Western) prepared this EA to analyze the potential environmental impacts of a proposal to rebuild and upgrade two parallel 4.8-mile transmission lines between the Gila and North Gila Substations and take actions in support of portions of Arizona Public Service’s construction of a new, 12.8 mile 230-kV transmission line between North Gila and a proposed substation in Yuma County, Arizona. The U.S. Bureau of Reclamation and U.S. Army Corps of Engineers are cooperating agencies.

182

Eastern Wind Integration and Transmission Study: Executive Summary and Project Overview  

Broader source: Energy.gov [DOE]

This study evaluates the future operational and integration impacts of three different 20 percent wind energy penetration scenarios and one 30 percent wind penetration scenario, including a high-level analysis of transmission to deliver the wind energy to load centers, in the study year 2024.

183

EA-1946: Salem-Albany Transmission Line Rebuild Project; Polk, Benton, Marion, and Linn Counties, Oregon  

Broader source: Energy.gov [DOE]

Bonneville Power Administration is preparing an EA to assess the potential environmental impacts of the proposed rebuild of the 24-mile Salem-Albany No. 1 and 28-mile Salem-Albany No. 2 transmission lines between Salem and Albany, Oregon.

184

EIS-0141: Washington Water Power/B.C. Hydro Transmission Interconnection Project  

Broader source: Energy.gov [DOE]

The U.S. Department of Energy developed this statement to evaluate the environmental impacts of constructing and operating a double-circuit 230-kilovolt electrical transmission line that would link the electrical systems of the Washington Water Power Company and the British Columbia Hydro and Power Authority.

185

EIS-0502: Hot Springs to Anaconda Transmission Line Rebuild Project, Montana  

Broader source: Energy.gov [DOE]

DOE’s Bonneville Power Administration (BPA) is preparing an EIS that will analyze the potential environmental impacts of a proposal to rebuild approximately 120 miles of existing transmission line in Sanders, Lake, Missoula, Granite, Powell, and Deer Lodge Counties in Montana.

186

EA-1952: Lane-Wendson No. 1 Transmission Line Rebuild Project...  

Energy Savers [EERE]

line between Eugene and Florence, Oregon. Additional information is available at the project website: http:efw.bpa.govenvironmentalservicesDocumentLibraryLane-Wendson...

187

Grand Coulee - Bell 500-kV Transmission Line Project, Draft Environmental Impact Statement  

SciTech Connect (OSTI)

BPA is proposing to construct a 500-kilovolt (kV) transmission line that would extend approximately 84 miles between the Grand Coulee 500-kV Switchyard, near Grand Coulee Dam, and the Bell Substation, in Mead just north of Spokane. The new line would cross portions of Douglas, Grant, Lincoln, and Spokane counties. In addition to the transmission line, new equipment would be installed at the substations at each end of the new line and at other facilities. The proposed action would remove an existing 115-kV transmission line and replace it with the new 500-kV line on existing right-of-way for most of its length. Additional right-of-way would be needed in the first 3.5 miles out of the Grand Coulee Switchyard to connect to the existing 115-kV right-of-way. Since the mid-1990s, the transmission path west of Spokane, called the West of Hatwai transmission pathway, has grown increasingly constrained. To date, BPA has been able to manage operation of the path through available operating practices, and customer needed have been met while maintaining the reliability of the path. however, in early 2001, operations showed that the amount of electricity that needs to flow from east to west along this path creates severe transmission congestion. Under these conditions, the system is at risk of overloads and violation of industry safety and reliability standards. The problem is particularly acute in the spring and summer months because of the large amount of power generated by dams east of the path. Large amounts of water cannot be spilled during that time in order for BPA to fulfill its obligation to protect threatened and endangered fish. The amount of power that needs to move through this area during these months at times could exceed the carrying capacity of the existing transmission lines. In additional capacity is not added, BPA will run a significant risk that it will not be able to continue to meet its contractual obligations to deliver power and maintain reliability standards that minimize risks to public safety and to equipment. BPA is considering two construction alternatives, the Agency Proposed Action and the Alternative Action. The Alternative Action would include all the components of the Preferred Action except a double-circuit line would be constructed in the Spokane area between a point about 2 miles west of the Spokane River and Bell Substation, a distance of about 9 miles. BPA is also considering the No Action Alternative.

N /A

2002-08-09T23:59:59.000Z

188

California Energy Commission Public Interest Energy Research/Energy System Integration -- Transmission-Planning Research & Development Scoping Project  

E-Print Network [OSTI]

stakeholders in transmission-line route planning and sitingan “optimal” transmission line route-finding tool. This tool

Eto, Joseph H.; Lesieutre, Bernard; Widergren, Steven

2004-01-01T23:59:59.000Z

189

Weld-Windsor 115-kV Transmission Line Project, Weld County, Colorado  

SciTech Connect (OSTI)

The Western Area Power Administration is proposing to rebuild a 3.0 mile segment of the existing Flatiron-Weld 115-kV transmission line in Weld County. The line would be reconductored with new conductor on new wood pole double circuit structures. The new structures would support a double circuit transmission line configuration. The first circuit would be owned by Western and the second by Public Service Company of Colorado (PSCO). Alternatives considered included no action, constructing PSCO`s circuit on new right-of-way, and reconductoring Western`s existing line on the same structures. The proposed action was selected because it provided an opportunity to share structures with PSCO and, overall, would minimize costs and environmental impacts. The environmental assessment identifies minor effects on existing natural or human resources and minor benefits for agricultural operations.

NONE

1996-05-01T23:59:59.000Z

190

DOE/EA-1354; Environmental Assessment for the Fort Collins 115kV Transmission Line Upgrade Project (12/2001)  

Broader source: Energy.gov (indexed) [DOE]

Western Area Power Administration Western Area Power Administration Fort Collins 115-kV Transmission Line Upgrade Project, Fort Collins, Colorado. AGENCY: Western Area Power Administration, DOE ACTION: Finding of no significant impact SUMMARY: The Department of Energy (DOE), Western Area Power Administration (Western) is the lead federal agency for a proposed project to upgrade the electric transmission system in the Fort Collins, Colorado area. Platte River Power Authority (Platte River) is proposing to add additional generation at its Rawhide Power Plant, to rebuild and upgrade segments of Western's existing Flatiron-Poudre and Poudre-Richard's Lake 115-kilovolt (kV) transmission lines, and to install additional 230 kV transmission to Platte River's existing electrical system. Western prepared an environmental assessment (EA) titled "Fort Collins 115kV Transmission

191

DOE/EA-1508: Environmental Assessment for the Beaver Creek-Hoyt-Erie Transmission Line Rebuild Project  

Broader source: Energy.gov (indexed) [DOE]

BC-HT-EE Mitigation Action Plan Nov. 2005 1 BC-HT-EE Mitigation Action Plan Nov. 2005 1 Mitigation Action Plan To Implement Mitigation Requirements for Beaver Creek-Hoyt-Erie Transmission Line Upgrade Project Morgan and Weld Counties, Colorado November 2005 BC-HT-EE Mitigation Action Plan Nov. 2005 2 Action Plan for Standard Project Practices and Mitigation Mitigation Action Identifier Responsible Party for Implementing Mitigation Action Party Responsible for Monitoring and Ensuring Compliance Construction Contractor Western Maintenance The contractor shall limit the movement of crews and equipment to the ROW, including access routes. The contractor shall limit movement on the ROW to minimize damage to residential yards, grazing land, crops, orchards, and property, and shall avoid marring the lands.

192

Validation of phasor calculations in the Macrodyne PMU for California-Oregon Transmission Project tests of March 1993  

SciTech Connect (OSTI)

Faults applied during March 1993 commissioning tests for the California-Oregon Transmission Project produced 14 Hz transient oscillations that were conspicuous in BPA`s enhanced transducers at Malin, and in PG and E`s Dynamic System Monitor at Table Mountain. Prony analysis of high speed fault data provided a detailed model for the underlying network resonance signal, and a basis for validating transient performance of a Macrodyne Phasor Measurement Unit (PMU) at the test site. This instrument, which is closely associated with EPRI`s FACTS project, provides useful insight into emerging technology for high speed digital transducers. The phasor calculations are found to be of very high quality, but filtering enhancements are recommended for broadband applications.

Hauer, J.F. [Pacific Northwest Labs., Richland, WA (United States)] [Pacific Northwest Labs., Richland, WA (United States)

1996-07-01T23:59:59.000Z

193

EIS-0091: Garrison-Spokane 500-kV Transmission Project  

Broader source: Energy.gov [DOE]

The U.S. Department of Energy's Bonneville Power Administration (BPA) developed this statement to evaluate the environmental impacts of constructing between 254 and 271 miles of 500-kilovolt transmission line across western Montana and northern Idaho to the Spokane area in order to reinforce a section of the BPA electric power grid and to permit reliable integration of 1,240 megawatts of power produced by Colstrip Units 3 and 4, for use in Montana and throughout the Northwest.

194

EIS-0173: Bonneville Power Administration/Puget Power Northwest Washington Transmission Project  

Broader source: Energy.gov [DOE]

The Bonneville Power Administration (BPA) prepared this environmental impact statement to analyze the environmental impacts of an upgrade that BPA and Puget Sound Power & Light Company are considering implementing on the existing high- voltage transmission system in the Whatcom and Skagit Counties area of the State of Washington, between the towns of Custer and Sedro Woolley, including some areas within the City of Bellingham, starting in 1995.

195

Bonneville Power Administration Kangley-Echo Lake Transmission Line Project Record of Decision (DOE/EIS-0317) (7/21/03)  

Broader source: Energy.gov (indexed) [DOE]

Bonneville Power Administration Bonneville Power Administration Kangley-Echo Lake Transmission Line Project Record of Decision Decision The Bonneville Power Administration (BPA) has decided to construct the proposed Kangley-Echo Lake Transmission Line Project in King County, Washington. BPA has decided to implement the Proposed Action (Alternative 1) identified in the Kangley-Echo Lake Transmission Line Project Final Environmental Impact Statement (DOE/EIS-0317-S1, June 2003). This decision is made thirty (30) days after publication of the notice for a final EIS (June 20, 2003) in the Federal Register. The Proposed Action consists of constructing a new 500-kilovolt (kV) transmission line from a tap point on an existing 500-kV line near Kangley, Washington, to BPA's Echo Lake

196

Collaboration and Communication: DOE and Navajo Nation Tour Uranium Mine Reclamation Sites to Share Expertise and Experiences  

Broader source: Energy.gov [DOE]

In February 2014, U.S. Department of Energy (DOE) Office of Legacy Management (LM) and LM Support (LMS) contractor site managers, along with Navajo Nation technical staff, visited five reclaimed...

197

Background, status and future of the Transmission Electron Aberration-corrected Microscope project  

Science Journals Connector (OSTI)

...Microscope project Recent advances in aberration-correcting...DOEs) Office of Science to jointly design...great interest for aerospace and cryogenic applications...be possible to advance to a new level...heart of materials science. At this level...

2009-01-01T23:59:59.000Z

198

EA-1931: Keeler to Tillamook Transmission Line Rebuild Project, Washington and Tillamook Counties, Oregon  

Broader source: Energy.gov [DOE]

Bonneville Power Administration prepared this EA to assess the potential environmental impacts of the proposed rebuild of the Keeler-Forest Grove and Forest Grove-Tillamook 115-kilovolt (kV) transmission lines between the cities of Hillsboro and Tillamook, in Washington and Tillamook Counties, Oregon. The 58-mile-long rebuild would include replacement of all wood-pole structures over 10 years in age. Some existing access roads would be improved to accommodate construction equipment and some new road access would be acquired or constructed in areas where access is not available.

199

Design studies for the Mead-Phoenix 500 kV AC transmission project  

SciTech Connect (OSTI)

The Mead-Phoenix 500 kV ac line is 243 miles long and runs parallel to the existing Mead-Liberty 345 kV line. This line is planned for 70% series and 70% shunt compensation; it also incorporates the first application of a 50 kV phase shifting transformer that enables a 1,300 MW transmission capacity. This paper presents the design studies that were undertaken in arriving at the equipment ratings and insulation levels that lead to the equipment specifications. The shunt reactor switching requirements utilizing MOV across the breaker, line switching with line connected arresters and the breaker transient recovery voltage are also dealt with in the paper.

Thallam, R.S.; Lundquist, T.G.; Gerlach, D.W. [Salt River Project, Phoenix, AZ (United States)] [Salt River Project, Phoenix, AZ (United States); Atmuri, S.R. [Teshmont Consultants Inc., Winnipeg, Manitoba (Canada)] [Teshmont Consultants Inc., Winnipeg, Manitoba (Canada); Selin, D.A. [Arizona Public Service Co., Phoenix, AZ (United States)] [Arizona Public Service Co., Phoenix, AZ (United States)

1995-10-01T23:59:59.000Z

200

Summit-Watertown transmission line project, South Dakota. Final Environmental Assessment  

SciTech Connect (OSTI)

The Western Area Power Administration (Western) needs to rebuild the existing Summit-Watertown 115-kV transmission line, located in northeastern South Dakota, and western Minnesota. Nearly 60 percent of the existing facility was replaced in 1965 after severe ice-loading broke structures and wires. Because of the extensive loss of the line, surplus poles had to be used to replace the damaged H-frame structures. These were of varying sizes, causing improper structure loading. Additionally, the conductors and overhead shield wires have been spliced in numerous places. This provides additional space on these wires for icing and wind resistance, which in turn create problems for reliability. Finally, a progressive fungal condition has weakened the poles and, along with the improper loading, has created an unsafe condition for maintenance personnel and the general public.

Not Available

1993-12-01T23:59:59.000Z

Note: This page contains sample records for the topic "navajo transmission project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


201

Navajo Generating Station and Clean-Energy Alternatives: Options for Renewables  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Navajo Generating Station and Clean-Energy Alternatives: Options for Renewables D.J. Hurlbut, S. Haase, C.S. Turchi, and K. Burman National Renewable Energy Laboratory Produced under direction of the U.S. Department of the Interior by the National Renewable Energy Laboratory (NREL) under Interagency Agreement R11PG30024 and Task No WFJ5.1000. Technical Report NREL/TP-6A20-54706 June 2012 NREL is a national laboratory of the U.S. Department of Energy, Office of Energy Efficiency & Renewable Energy, operated by the Alliance for Sustainable Energy, LLC. National Renewable Energy Laboratory 15013 Denver West Parkway Golden, Colorado 80401 303-275-3000 * www.nrel.gov Contract No. DE-AC36-08GO28308 Navajo Generating Station and

202

DOE Tribal Intern Focuses on Integrating Energy Policy and Navajo Cultural Values  

Broader source: Energy.gov [DOE]

My interest in energy planning on the Navajo Nation stemmed from the desire to improve energy resource development in my own community. The legacy of environmental and health impacts from uranium and coal mining motivated me to find ways of developing energy resources in a manner more consistent with cultural values and the visions of the Navajo Nation. While I have developed many valuable technical analysis skills and tools in my Ph.D. program, most of the knowledge about Indian energy issues requires significant on-the-ground engagement with communities and their leaders. As a Tribal Energy Program intern, I have developed important connections in the area of tribal energy working with tribal leaders and my fellow interns.

203

DOE/EA-1596: Finding of No Significant Impact for Belfield to Rhame Transmission Line Project Stark, Slope, and Bowman Counties, North Dakota (02/18/09)  

Broader source: Energy.gov (indexed) [DOE]

WESTERN AREA POWER ADMINISTRATION WESTERN AREA POWER ADMINISTRATION UPPER GREAT PLAINS CUSTOMER SERVICE REGION FINDING OF NO SIGNIFICANT IMPACT Belfield to Rhame Transmission Line Project Stark, Slope, and Bowman Counties, North Dakota DOEIEA-1596 AGENCY: U.S. Department of Energy (DOE), Western Area Power Administration (Western) ACTION: Finding of No Significant Impact SUMMARY: Basin Electric Power Cooperative (Basin) has requested to interconnect their proposed new Belfield to Rhame 230-kilovolt (kV) transmission line and new Rhame Substation (Project) to the Western Area Power Administration's (Western) transmission system at Western's existing Belfield Substation. Under its Open Access Transmission Service Tariff (Tariff), Western is required to respond to Basin's interconnection requests. Western's Tariff

204

Notice of Intent to Prepare an Environmental Impact Statement for the Proposed Sutter Power Plant and Transmission Line Project, California  

Broader source: Energy.gov (indexed) [DOE]

2 2 Federal Register / Vol. 63, No. 30 / Friday, February 13, 1998 / Notices taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a motion to intervene. Copies of his filing are on file with the Commission and are available for public inspection in the Public Reference Room. David P. Boergers, Acting Secretary. [FR Doc. 98-3659 Filed 2-12-98; 8:45 am] BILLING CODE 6717-01-M DEPARTMENT OF ENERGY Western Area Power Administration Notice of Intent To Prepare an Environmental Impact Statement for the Proposed Sutter Power Plant and Transmission Line Project, California AGENCY: Western Area Power Administration, DOE. ACTION: Notice of intent to prepare an Environmental Impact Statement. SUMMARY: In accordance with Section

205

DOE/EIS-0325; Environmental Impact Statement for Schultz-Hanford Area Transmission Line Project (02/2002)  

Broader source: Energy.gov (indexed) [DOE]

Draft Environmental Impact Statement Draft Environmental Impact Statement Bonneville Power Administration U.S. Department of Energy Bureau of Land Management Bureau of Reclamation Fish and Wildlife Service U.S. Department of Interior Department of Army U.S. Department of Defense February 2002 Schultz-Hanford Area Transmission Line Project Draft Environmental Impact Statement Summary Bonneville Power Administration U.S. Department of Energy Bureau of Land Management Bureau of Reclamation Fish and Wildlife Service U.S. Department of Interior Department of Army U.S. Department of Defense February 2002 Summary S-1 Summary In this Summary: * The Purposes and Need for Action * Alternatives * Affected Environment * Impacts This summary covers the major points of the Draft Environmental

206

Mitigation Action Plan for the McNary-John Day Transmission Line Project,(DOE/EIS-0332)  

Broader source: Energy.gov (indexed) [DOE]

Measures Adopted Measures Adopted for the McNary-John Day Transmission Line Project Land Use and Recreation Locate towers and roads so as not to disrupt irrigation circles, where possible. Locate structures and roads outside of agricultural fields, orchards, and vineyards, where possible. Coordinate with landowners for farm operations, including plowing, crop dusting, and harvesting. Redesign irrigation equipment and compensate landowner for additional reasonable costs where new right-of-way needs to be acquired. Compensate farmers for crop damage and restore compacted soils. Control weeds around the base of the towers. Keep gates and fences closed and in good repair to contain livestock. Repair damages to access roads caused by or arising out of Bonneville use, leaving roads in good or better

207

Record of Decision for the Los Banos-Gates Transmission Project (DOE/EIS-0128-SA-01)  

Broader source: Energy.gov (indexed) [DOE]

99 99 Federal Register / Vol. 66, No. 245 / Thursday, December 20, 2001 / Notices A copy of any motion to intervene must also be served upon the representative of the RAWA specified in item h, above. p. Agency Comments-Federal, state, and local agencies are invited to file comments on the subject application for surrender of exemption. If an agency does not file comments within the time specified for filing comments, it will be presumed to have no comments. One copy of an agency's comments must also be sent to the Applicant's representative listed in item h, above. Linwood A. Watson, Jr., Acting Secretary. [FR Doc. 01-31311 Filed 12-19-01; 8:45 am] BILLING CODE 6717-01-P DEPARTMENT OF ENERGY Western Area Power Administration Los Banos-Gates Transmission Project AGENCY: Western Area Power

208

Flatiron-Erie 115kV transmission line project, Larimer, Weld and Boulder Counties, Colorado. Draft environmental impact statement  

SciTech Connect (OSTI)

Western Area Power Administration (Western) proposes to uprate its existing 115-kV Flatiron-Erie transmission line. The line is located in Larimer, Weld and Boulder Counties, Colorado, and passes through the City of Longmont. The line connects Flatiron Substation and several of the substations supplying Longmont. It is a single circuit 115-kV line, 31.5 miles long, and was built in 1950-51 on a 75-foot wide right-of-way (ROW) using wood H-frame structures. Western proposes to build 27 new structures along the line, to replace or modify 45 of the existing structures and to remote 11 of them. Many of these additions and changes would involve structures that are approximately 5 to 15 feet taller than the existing ones. The existing conductors and ground wires would remain in place. The purpose of these actions would be to allow the power carrying capability of the line to be increased and to replace deteriorating/structural members. Western would be the sole participant in the proposed project. This report gives an analysis of the study area environment and the development of alternative routes. An assessment is presented of the impacts of the primary alternative routes. The environmental consequences of this project are addressed.

Not Available

1993-05-01T23:59:59.000Z

209

DOE/EA-1354; Environmental Assessment for the Fort Collins 115kV Transmission Line Upgrade Project (12/2001)  

Broader source: Energy.gov (indexed) [DOE]

ENVIRONMENTAL ASSESSMENT ENVIRONMENTAL ASSESSMENT FOR THE FORT COLLINS 115kV TRANSMISSION LINE UPGRADE PROJECT Prepared for: Platte River Power Authority and U.S. Department of Energy Western Area Power Administration DOE/EA 1354 September 2001 i TABLE OF CONTENTS SUMMARY ............................................................................................................... S-1 1.0 INTRODUCTION ...............................................................................................1-1 1.1 DESCRIPTION OF PROPOSED PROJECT .................................................................. 1-1 1.3 PURPOSE OF ENVIRONMENTAL ASSESSMENT....................................................

210

Notice of Availability of Plains & Eastern Clean Line Transmission Project Draft Environmental Impact Statement and Public Hearings: Federal Register Notice, Volume 79, No. 242- Dec. 17, 2014  

Broader source: Energy.gov [DOE]

The U.S. Department of Energy (DOE) announces the availability of the Draft Environmental Impact Statement for the Plains & Eastern Clean Line Transmission Project (DOE/EIS–0486; Draft EIS) for a 90-day public comment period. DOE also announces 15 public hearings to receive comments on the Draft EIS. In addition, DOE invites comments on the National Historic Preservation Act Section 106 process and any potential adverse impacts to historic properties from the proposed Project.

211

Hawaii Geothermal Project annotated bibliography: Biological resources of the geothermal subzones, the transmission corridors and the Puna District, Island of Hawaii  

SciTech Connect (OSTI)

Task 1 of the Hawaii Geothermal Project Interagency Agreement between the Fish and Wildlife Service and the Department of Energy-Oak Ridge National Laboratory (DOE) includes an annotated bibliography of published and unpublished documents that cover biological issues related to the lowland rain forest in Puna, adjacent areas, transmission corridors, and in the proposed Hawaii Geothermal Project (HGP). The 51 documents reviewed in this report cover the main body of biological information for these projects. The full table of contents and bibliography for each document is included along with two copies (as requested in the Interagency Agreement) of the biological sections of each document. The documents are reviewed in five main categories: (1) geothermal subzones (29 documents); (2) transmission cable routes (8 documents); (3) commercial satellite launching facility (Spaceport; 1 document); (4) manganese nodule processing facility (2 documents); (5) water resource development (1 document); and (6) ecosystem stability and introduced species (11 documents).

Miller, S.E.; Burgett, J.M. [Fish and Wildlife Service, Honolulu, HI (United States). Pacific Islands Office

1993-10-01T23:59:59.000Z

212

EA-1982: Parker-Davis Transmission System Routine Operation and Maintenance Project and Proposed Integrated Vegetation Management Plan  

Broader source: Energy.gov [DOE]

Western Area Power Administration (Western) is preparing an EA to assess potential environmental impacts of the proposed continuation of operations and maintenance activities and implementation of a vegetation management program on Western’s Parker-Davis Transmission System. These actions would occur on existing transmission line and access road rights-of-way, and at substations and maintenance facilities associated with the transmission system.

213

California Energy Commission Public Interest Energy Research/Energy System Integration -- Transmission-Planning Research & Development Scoping Project  

E-Print Network [OSTI]

California Energy Commission Transmission Planning Analysis92, No. 5, Dec. CEC (California Energy Commission). 2004.of MCPs. California Energy Commission. Nov. CERTS PIER

Eto, Joseph H.; Lesieutre, Bernard; Widergren, Steven

2004-01-01T23:59:59.000Z

214

STRATEGIC TRANSMISSION INVESTMENT PLAN  

E-Print Network [OSTI]

CALIFORNIA ENERGY COMMISSION STRATEGIC TRANSMISSION INVESTMENT PLAN Prepared in Support of the 2005............................................................................................ 5 Project Investment Recommendations ............................................................... 6 Actions to Implement Investments

215

STRATEGIC TRANSMISSION INVESTMENT PLAN  

E-Print Network [OSTI]

CALIFORNIA ENERGY COMMISSION STRATEGIC TRANSMISSION INVESTMENT PLAN Prepared in Support of the 2005............................................................................................ 5 Project Investment Recommendations ............................................................... 5 Actions to Implement Investments

216

Bayesian models for elevated disease risk due to exposure to uranium mine and mill waste on the Navajo Nation  

E-Print Network [OSTI]

ForReview Only Bayesian models for elevated disease risk due to exposure to uranium mine and mill of Pharmacy, Community Environmental Health Program Keywords: abandoned uranium mines, conditionally specified to ex- posure to uranium mine and mill waste on the Navajo Nation Glenn A. Stark University of New

Huerta, Gabriel

217

EIS-0505: Vantage to Pomona Heights 230 kV Transmission Line Project, Yakima, Grant, Benton and Kittitas Counties, Washington  

Broader source: Energy.gov [DOE]

The Bureau of Land Management is preparing, with DOE’s Bonneville Power Administration (BPA) as a cooperating agency, an EIS that evaluates the potential environmental impacts of a proposal to construct a 60- to 67-mile long 230-kV transmission line. BPA’s proposed action is to interconnect the transmission line to an existing BPA substation. Additional information is available at http://www.blm.gov/or/districts/spokane/plans/vph230/.

218

Applicant Location Requested DOE Funds Project Summary Feasibility Studies  

Broader source: Energy.gov (indexed) [DOE]

Requested Requested DOE Funds Project Summary Feasibility Studies Confederated Salish and Kootenai Tribes Pablo, MT $850,000 This project will evaluate the technical and economic viability of a co-generation biomass fuel power plant. The plant would use fuels from tribal forest management activities to provide between 2.5 to 20 megawatts (MW) of electricity to heat tribal buildings or sell on the wholesale market. Standing Rock Sioux Tribe Fort Yates, ND $430,982 This project will perform a feasibility study over the course of two years on three tribal sites to support the future development of 50 to 100 MW of wind power. Navajo Hopi Land Commission (NHLCO), Navajo Nation Window Rock, AZ $347,090 This project will conduct a feasibility study to explore potential

219

Southline Transmission Line | Open Energy Information  

Open Energy Info (EERE)

Impact Statement for the Southline Transmission Line Project General NEPA Document Info Energy Sector Transmission Environmental Analysis Type EIS Applicant Southline...

220

EIS-0483: Estes to Flatiron Substation Transmission Lines Rebuild...  

Broader source: Energy.gov (indexed) [DOE]

EIS-0483: Estes to Flatiron Substation Transmission Lines Rebuild Project, Larimer County, Colorado EIS-0483: Estes to Flatiron Substation Transmission Lines Rebuild Project,...

Note: This page contains sample records for the topic "navajo transmission project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


221

Amended Notice of Intent for the Northern Pass Transmission Line...  

Broader source: Energy.gov (indexed) [DOE]

Amended Notice of Intent for the Northern Pass Transmission Line Project Published in the Federal Register Amended Notice of Intent for the Northern Pass Transmission Line Project...

222

(DOE/EIS-0128-SA-02): Supplement Analysis: Los Banos-Gates (Path 15) Transmission line project changes to alignment, access road stream crossing, and basis for Supplemental EIS Determination  

Broader source: Energy.gov (indexed) [DOE]

Los Banos-Gates (Path 15) Transmission Line Project DOE/EIS-0128-SA02 Western Area Power Administration Sierra Nevada Customer Service Region U.S. Department of Energy Changes to Alignment, Access Road Stream Crossing, and Basis for Supplemental Environmental Impact Statement Determination Background The Los Banos-Gates 500-kilovolt Transmission Line project was originally proposed as part of the California-Oregon Transmission Project in the 1980s. These two projects were the subject of a single set of documents prepared in 1986 (draft) and 1988 (final) that served as the Environmental Impact Statement (EIS) under the National Environmental Policy Act and the Environmental Impact Report (EIR) under the California Environmental Quality Act. The EIS is entitled "Final Environmental Impact

223

EIS-0116: Blue River-Gore Pass Portion of the Hayden-Blue River Transmission Line Project  

Broader source: Energy.gov [DOE]

The U.S. Department of Energy’s Western Area Power Administration (WAPA) adopted this U.S. Department of Agriculture Rural Electrification Administration so that WAPA could supplement it in support of WAPA’s National Environmental Policy Act requirements for a related project.

224

Coordination of Transmission Line Transfer Capabilities  

E-Print Network [OSTI]

Coordination of Transmission Line Transfer Capabilities Final Project Report Power Systems since 1996 PSERC #12;Power Systems Engineering Research Center Coordination of Transmission Line Summary The maximum power that can be transferred over any transmission line, called the transfer capacity

225

10-Yr. Transmission Plan  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Power Marketing Rates Power Marketing Rates 10-Yr Transmission Plan 2012 Customer Meeting Announcement Agenda 120611 CRSP South Projects CRSP South PowerPoint Presentation CRSP South 2009-2011 Capitalized Execution CRSP North Projects CRSP North PowerPoint Presentation CRSP North 2009-2011 Capitalized Execution About Power Marketing Transmission Newsroom Business Policies Products Plan contents OASIS News features Careers No FEAR act Organization chart Plan processes Functions News releases Doing business Privacy policy History General power contract provisions OATT Revisions Fact sheets Energy Services Accessibility Financial information Rates and Repayment Interconnection Publications EPTC Adobe PDF Power projects EPAMP Infrastructure projects Federal Register Notices

226

RECIPIENT:Princeton Power Systems STATE: NJ PROJECT Marine High-Voltage Power Conditioning and Transmission System with Integrated Energy Storage  

Broader source: Energy.gov (indexed) [DOE]

Princeton Power Systems Princeton Power Systems STATE: NJ PROJECT Marine High-Voltage Power Conditioning and Transmission System with Integrated Energy Storage TITLE: Funding Opportunity Announcement Number Procurement Instrument Number NEPA Control Number cm Number DE-FOA-0000293 DE-EE0003640 GFO-000364~001 GOO Based on my review of the information concerning the proposed action, as NEPA Compliance Officer (authorized under DOE Order 451.1A), I have made the foUowing determination: CX, EA, EIS APPENDIX AND NUMBER: Description: A9 Information gathering (including, but not limited to, ~terature surveys, inventories, audits), data analysis (including computer modeling), document preparation (such as conceptual design or feasibility studies, analytical energy supply

227

Notice of Intent for the Construction and Operation of the Proposed Big Stone II Power Plant and Transmission Project, South Dakota and Minnesota (5/27/05)  

Broader source: Energy.gov (indexed) [DOE]

16 16 Federal Register / Vol. 70, No. 102 / Friday, May 27, 2005 / Notices Regulatory Commission, 888 First Street, NE., Washington, DC 20426. Note that also there is an ''eSubscription'' link on the web site that enables subscribers to receive e- mail notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov, or call (866) 208-3676 (toll free). For TTY, call (202) 502-8659. Comment Date: June 9, 2005. Magalie R. Salas, Secretary. [FR Doc. E5-2702 Filed 5-26-05; 8:45 am] BILLING CODE 6717-01-P DEPARTMENT OF ENERGY Western Area Power Administration Construction and Operation of the Proposed Big Stone II Power Plant and Transmission Project, South Dakota and Minnesota

228

Wind Integration, Transmission, and Resource Assessment andCharacteri...  

Energy Savers [EERE]

& Publications Wind Integration, Transmission, and Resource Assessment and Characterization Projects Offshore Wind Projects Testing, Manufacturing, and Component Development...

229

Record of Decision for the Interconnection of the Sutter Power Project With the Western Area Power Administration's Keswick-Elverta/Olinda-Elverta 230-Kilovolt Double-Circuit Transmission Line, June 15, 1999  

Broader source: Energy.gov (indexed) [DOE]

41 41 Federal Register / Vol. 64, No. 114 / Tuesday, June 15, 1999 / Notices DEPARTMENT OF ENERGY Western Area Power Administration Record of Decision for the Interconnection of the Sutter Power Project With the Western Area Power Administration's Keswick-Elverta/ Olinda-Elverta 230-Kilovolt Double- Circuit Transmission Line AGENCY: Western Area Power Administration, DOE. ACTION: Record of decision. SUMMARY: The Western Area Power Administration (Western) prepared this Record of Decision in response to a request submitted to Western for a direct interconnection of Calpine Corporation's (Calpine) proposed Sutter Power Project (SPP) with Western's electric transmission system. In response to this request, Western completed an Interconnection Feasibility Study that determined that

230

Limited exemption to hydroelectric licensing provisions for transmission facilities associated with the El Vado Hydroelectric Project. Introduced in the Senate, One Hundred Fourth Congress, First Session, April 27, 1995  

SciTech Connect (OSTI)

The report addresses bill S. 522 which is to provide for a limited exemption to the hydroelectric licensing provisions of part I of the Federal Power Act for certain transmission facilities associated with the El Vado Hydroelectric Project in New Mexico. The bill proposes to permit a limited exemption for a 12 mile transmission line to Rio Arriba County, New Mexico. The project was licensed by the Federal Energy Regulatory Commission. The background and need for the exemption is presented. Statements of government officials are included.

NONE

1995-12-31T23:59:59.000Z

231

NREL: Transmission Grid Integration - Publications  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Publications Publications Want updates about future transmission grid integration webinars and publications? Join our mailing list. NREL has an extensive collection of publications related to transmission integration research. Explore the resources below to learn more. Selected Project Publications Read selected publications related to these transmission integration projects: Western Wind and Solar Integration Study Eastern Renewable Generation Integration Study Oahu Wind Integration and Transmission Study Flexible Energy Scheduling Tool for Integration of Variable generation (FESTIV) Active power controls Forecasting Grid Simulation. NREL Publications Database NREL's publications database offers a variety of documents related to transmission integration that were written by NREL staff and

232

EIS-0478: Antelope Valley Station to Neset Transmission Project, Mercer, Dunn, Billings, Williams, McKenzie, and Mountrail Counties, North Dakota  

Broader source: Energy.gov [DOE]

USDA Rural Utilities Service prepared an EIS that evaluates the potential environmental impacts of constructing, operating, and maintaining a proposed transmission line and associated facilities in western North Dakota. DOE’s Western Area Power Administration, a cooperating agency, would modify its existing Williston Substation to allow a connection of the proposed new transmission line to Western’s transmission system.

233

EEI/DOE Transmission Capacity Report  

Broader source: Energy.gov (indexed) [DOE]

TRANSMISSION CAPACITY: TRANSMISSION CAPACITY: PRESENT STATUS AND FUTURE PROSPECTS Eric Hirst Consulting in Electric-Industry Restructuring Bellingham, Washington June 2004 Prepared for Energy Delivery Group Edison Electric Institute Washington, DC Russell Tucker, Project Manager and Office of Electric Transmission and Distribution U.S. Department of Energy Washington, DC Larry Mansueti, Project Manager ii iii CONTENTS Page SUMMARY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . v LIST OF ACRONYMS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . vii 1. INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 2. TRANSMISSION CAPACITY: DATA AND PROJECTIONS . . . . . . . . . . . . . . . . . . . 5 HISTORICAL DATA . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 CURRENT CONDITIONS . . . . . . .

234

The Cost of Transmission for Wind Energy: A Review of Transmission Planning Studies  

E-Print Network [OSTI]

NREL/CP-500-35969. Global WindPower Conference. Chicago,Transmission Projects. ” Windpower 2007 Conference. Los

Mills, Andrew D.

2009-01-01T23:59:59.000Z

235

Microsoft PowerPoint - CF-LM M2W Project Updates_final [Compatibility...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Transmission Upgrade Project (M2W Project) Project description: * Upgrade existing BPA Transmission system West of Garrison substation. Project includes upgrades at five...

236

Oahu Wind Integration and Transmission Study (OWITS): Hawaiian Islands  

Broader source: Energy.gov (indexed) [DOE]

Oahu Wind Integration and Transmission Study (OWITS): Hawaiian Oahu Wind Integration and Transmission Study (OWITS): Hawaiian Islands Transmission Interconnection Project Oahu Wind Integration and Transmission Study (OWITS): Hawaiian Islands Transmission Interconnection Project This report provides an independent review included an initial evaluation of the technical configuration and capital costs of establishing an undersea cable system and examining impacts to the existing electric transmission systems as a result of interconnecting the islands. 50411.pdf More Documents & Publications Phase 2 Report: Oahu Wind Integration and Transmission Study (OWITS); Hawaiian Islands Transmission Interconnection Project OAHU Wind Integration And Transmission Study: Summary Report, NREL (National Renewable Energy Laboratory)

237

Phase 2 Report: Oahu Wind Integration and Transmission Study (OWITS);  

Broader source: Energy.gov (indexed) [DOE]

Phase 2 Report: Oahu Wind Integration and Transmission Study Phase 2 Report: Oahu Wind Integration and Transmission Study (OWITS); Hawaiian Islands Transmission Interconnection Project Phase 2 Report: Oahu Wind Integration and Transmission Study (OWITS); Hawaiian Islands Transmission Interconnection Project This report provides an independent review included an initial evaluation of the technical configuration and capital costs of establishing an undersea cable system and examining impacts to the existing electric transmission systems as a result of interconnecting the islands. 50414.pdf More Documents & Publications Oahu Wind Integration and Transmission Study (OWITS): Hawaiian Islands Transmission Interconnection Project OAHU Wind Integration And Transmission Study: Summary Report, NREL (National Renewable Energy Laboratory)

238

Environmental Assessment and Finding of No Significant Impact: Curecanti-Lost Canyon 230-kV Transmission Line Reroute Project, Montrose County, Colorado  

SciTech Connect (OSTI)

The Department of Energy (DOE), Western Area Power Administration (Western) is proposing to reroute a section of the Curecanti-Lost Canyon 230-kilovolt (kV) transmission line, in Montrose County, Colorado. A portion of the transmission line, situated 11 miles southeast of Montrose, Colorado, crosses Waterdog Peak, an area of significant geologic surface activity, which is causing the transmission line's lattice steel towers to shift. This increases stress to structure hardware and conductors, and poses a threat to the integrity of the transmission system. Western proposes to relocate the lattice steel towers and line to a more geologically stable area. The existing section of transmission line and the proposed relocation route cross Bureau of Land Management and private land holdings.

N /A

2000-03-20T23:59:59.000Z

239

Project  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Exploring the Standard Model Exploring the Standard Model       You've heard a lot about the Standard Model and the pieces are hopefully beginning to fall into place. However, even a thorough understanding of the Standard Model is not the end of the story but the beginning. By exploring the structure and details of the Standard Model we encounter new questions. Why do the most fundamental particles have the particular masses we observe? Why aren't they all symmetric? How is the mass of a particle related to the masses of its constituents? Is there any other way of organizing the Standard Model? The activities in this project will elucidate but not answer our questions. The Standard Model tells us how particles behave but not necessarily why they do so. The conversation is only beginning. . . .

240

Transmission SEAB Presentation  

Broader source: Energy.gov (indexed) [DOE]

Overcoming Overcoming Institutional Barriers to Infrastructure Development Lauren Azar Senior Advisor to the Secretary U.S. Department of Energy January 31, 2012 Lauren"s Initiatives 1. Rapid Response Team for Transmission 2. Power Marketing Administrations 3. Project Development in the Southwest 4. Congestion Study and NIETC Designations 5. Miscellaneous  EPA Regulations  Market Power

Note: This page contains sample records for the topic "navajo transmission project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


241

ENVIRONMENTAL REVIEW FOR CATEGORICAL EXCLUSION DETERMINATION  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Kayenta-Shiprock 230-kV Transmission Line Nest Removal Project San Juan County, New Mexico and Apache and Navajo Counties, Arizona A. Brief Description of Proposal: Western Area...

242

Environmental Assessment and Finding of No Significant Impact: Western's Hoover Dam Bypass Project Phase II (Double-Circuiting a Portion of the Hoover-Mead No.5 and No.7 230-kV Transmission Lines with the Henderson-Mead No.1 230-kV Transmission Line, Clark County, Nevada)  

SciTech Connect (OSTI)

The U.S. Highway 93 (U.S. 93) Hoover Dam Bypass Project calls for the U.S. Department of Energy (DOE) Western Area Power Administration (Western) to remove its Arizona and Nevada (A&N) Switchyard. As a result of this action, Western must reconfigure its existing electrical transmission system in the Hoover Dam area. Western proposes to double-circuit a portion of the Hoover-Mead No.5 and No.7 230-kV Transmission Lines with the Henderson-Mead No.1 Transmission Line (see Figure 1-1). Double-circuiting is the placement of two separate electrical circuits, typically in the form of three separate conductors or bundles of conductors, on the same set of transmission line structures. The old Henderson-Hoover 230-kV Transmission Line would become the new Henderson-Mead No.1 and would extend approximately eight miles to connect with the Mead Substation. Western owns, operates, and maintains the Hoover-Mead No.5 and No.7, and Henderson-Hoover electrical power transmission lines. Additionally, approximately 0.25 miles of new right-of-way (ROW) would be needed for the Henderson-Mead No.1 when it transfers from double-circuiting with the Hoover-Mead No.7 to the Hoover-Mead No.5 at the Boulder City Tap. The proposed project would also involve a new transmission line ROW and structures where the Henderson-Mead No.1 will split from the Hoover-Mead No.5 and enter the northeast corner of the Mead Substation. Lastly, Western has proposed adding fiber optic overhead ground wire from the Hoover Power Plant to the Mead Substation on to the Henderson-Mead No.1, Hoover-Mead No.5 and No.7 Transmission Lines. The proposed project includes replacing existing transmission line tower structures, installing new structures, and adding new electrical conductors and fiber optic cables. As a consequence of these activities, ground disturbance may result from grading areas for structure placement, constructing new roads, improving existing roads for vehicle and equipment access, and from installing structures, conductors, and fiber optic cables. Project construction activities would be conducted within the existing 200-foot transmission line ROW and 50-foot access road ROW, although new spur access roads could occur outside of existing ROWs. As lead Federal agency for this action under National Environmental Policy Act (NEPA), Western must ensure that adverse environmental effects on Federal and non-Federal lands and resources are avoided or minimized. This Environmental Assessment (EA) is intended to be a concise public document that assesses the probable and known impacts to the environment from Western's Proposed Action and alternatives, and reaches a conclusion about the significance of the impacts. This EA was prepared in compliance with NEPA regulations published by the Council on Environmental Quality (40 CFR 1500-1508) and implementing procedures of the Department of Energy (10 CFR 1021).

N /A

2003-10-27T23:59:59.000Z

243

Estes-Flatiron Transmission Line Rebuild  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Estes-Flatiron Transmission Line Rebuild Estes-Flatiron Transmission Line Rebuild Skip Navigation Links Transmission Functions Infrastructure projects Interconnection OASIS OATT Estes-Flatiron Transmission Line Rebuild Project Western Area Power Administration proposes to rebuild approximately 32 miles of double wood-pole structure 115-kilovolt transmission line that exists between Estes Park and Flatiron Reservoir in Larimer County, Colo. The proposal would remove 16 miles of transmission line, and modernize 16 miles to steel-pole double-circuit 115-kV transmission line. The reduction and modernizing of transmission lines will occur on Federal, state and private lands. The public parcels are administered by the Arapaho and Roosevelt National Forest, which is a cooperating agency in the project.

244

DOE/EIS-0378-SA-01: Supplement Analysis for the Port Angeles-Juan de Fuca Transmission Project Final Environmental Impact Statement (DOE/EIS-0378-SA-01) (02/05/08)  

Broader source: Energy.gov (indexed) [DOE]

February 5, 2008 February 5, 2008 REPLY TO ATTN OF: KEC-4 SUBJECT: Supplement Analysis for the Port Angeles-Juan de Fuca Transmssion Project Final Environmental Impact Statement (DOE/EIS-0378/SA-01) Mark Korsness Project Manager - TEP TPP-3 Proposed Action: Relocation of the marine exit hole for the horizontal directionally drilled (HDD) hole that would be drilled under the Proposed Action. Proposed by: Sea Breeze Olympic Converter LP (Sea Breeze). Location: Port Angeles Harbor near Port Angeles, Washington. Background: As part of its proposed international transmission cable analyzed in the Port Angeles-Juan de Fuca Transmssion Project EIS, Sea Breeze has proposed the drilling of a HDD hole to transition the cable from the sea bed of the Strait of Juan de Fuca to land. The HDD hole

245

Project title:  

Broader source: Energy.gov (indexed) [DOE]

Project title: Roseville Elverta (RSC-ELV) OPGW Replacement Project Project title: Roseville Elverta (RSC-ELV) OPGW Replacement Project Requested By: David Young Mail Code : N1410 Phone: 916-353-4542 Date Submitted: 5/4/2011 Date Required: 5/7/2011 Description of the Project: Purpose and Need The Western Area Power Administration (Western), Sierra Nevada Region (SNR), is responsible for the operation and maintenance (O&M) of federally owned and operated transmission lines, Switchyards, and facilities throughout California. Western and Reclamation must comply with the National Electric Safety Code, Western States Coordinating Council (WECC), and internal directives for protecting human safety, the physical environment, and maintaining the reliable operation of the transmission system. There is an existing OPGW communications fiber on the transmission towers between Roseville and Elverta

246

Open Access Transmission Tariff  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Transmission | OATT Transmission | OATT Skip Navigation Links Transmission Functions Infrastructure projects Interconnection OASIS OATT Western Open Access Transmission Service Tariff Revision Western Area Power Administration submitted its revised Open Access Transmission Service Tariff with the Federal Energy Regulatory Commission on Sept. 30, 2009. The tariff became effective on Dec. 1, 2009, as modified by Western's March 2, 2011 compliance filing. The revised tariff was developed to comply with FERC Order No. 890 and to be consistent with Western's statutory and regulatory requirements. It addresses changes in transmission services and planning. FERC issued an order on Dec. 2, 2010, granting Western's petition for a Declaratory Order approving the tariff as an acceptable reciprocity tariff, subject to Western making a compliance filing within 30 days to address items in Attachment C, Attachment P and Attachment Q. Western made its compliance filing on March 2, 2010, addressing FERC's Dec. 2, 2010, order. FERC accepted Western's March 2, 2011 compliance filing on April 25, 2011. Western has made several ministerial filings to its OATT as part of FERC's eTariff viewer system, the last of these was approved on March 29, 2013. Further detail can be found in the links below.Current OATT

247

Energy Efficiency, Renewables, Advanced Transmission and Distribution Technologies (2008)  

Broader source: Energy.gov [DOE]

Federal Loan Guarantees For Projects That Employ Innovative Energy Efficiency, Renewable Energy, And Advanced Transmission And Distribution Technologies

248

Curecanti-Blue Mesa-Salida 115-kV transmission lines access roads rehabilitation, maintenance, and construction project. Environmental Assessment  

SciTech Connect (OSTI)

Western Area Power Administration (Western) is a power marketing agency of the US Department of Energy, with jurisdiction in 15 western states. The Salt Lake City Area (SLCA) of Western performs the agency`s mission in parts of Colorado, New Mexico, Texas, Utah, Arizona, Wyoming, and Nevada. As part of its mission, Western owns, operates, and maintains a system of transmission lines for transmitting bulk electrical energy from points of generation to and between delivery points. Part of that system in southwestern Colorado includes the Blue Mesa-Curecanti and Blue Mesa-Salida 115-kV transmission lines. Western proposes to conduct maintenance and improve its access roads for these two transmission lines. This paper discusses the impacts to the existing environment as well as the environmental consequences resulting from the maintenance and construction that is proposed.

Not Available

1993-07-01T23:59:59.000Z

249

S. 522: A Bill to provide for a limited exemption to the hydroelectric licensing provisions of part I of the Federal Power Act for certain transmission facilities associated with the El Vado Hydroelectric Project in New Mexico. Introduced in the Senate of the United States, One Hundred Fourth Congress, First session  

SciTech Connect (OSTI)

This report discusses a bill that provides for a limited exemption to part I of the Federal Power Act dealing with the hydroelectric licensing provisions for certain transmission facilities associated with the El Vado Hydroelectric project in New Mexico.

NONE

1995-12-31T23:59:59.000Z

250

Section 406 Renewable Energy and Electric Transmission Loan Guarantee Program under ARRA  

Broader source: Energy.gov [DOE]

A temporary program for rapid deployment of renewable energy and electric power transmission projects.

251

Electric Transmission Line Flashover Prediction System  

E-Print Network [OSTI]

Center since 1996 PSERC #12;Power Systems Engineering Research Center Electric Transmission LineElectric Transmission Line Flashover Prediction System Ph.D. Thesis and Final Project Report Power@asu.edu Power Systems Engineering Research Center This is a project report from the Power Systems Engineering

252

Mitigation Action Implementation Plan To Implement Mitigation Requirements for Cheyenne-Miracle Mile and Ault-Cheyenne Transmission Line Rebuild Project, Carbon, Albany and Laramie Counties, Wyoming, and Weld County, Colorado  

Broader source: Energy.gov (indexed) [DOE]

Mitigation Action Plan Mitigation Action Plan To Implement Mitigation Requirements for Cheyenne-Miracle Mile and Ault-Cheyenne Transmission Line Rebuild Project, Carbon, Albany, and Laramie Counties, Wyoming, and Weld County, Colorado September 2006 CH-MM and AU-CH Mitigation Action Plan Sept. 2006 1 Action Plan for Standard Project Practices and Mitigation Mitigation Action Identifier Resources for Which the Mitigation Will Be Implemented Responsible Party for Implementing Mitigation Action Party Responsible for Monitoring and Ensuring Compliance Land use, transportation Construction Contractor Western Maintenance The contractor will limit the movement of crews and equipment to the ROW, including access routes. The contractor will limit movement on the ROW to minimize damage to

253

Blythe-Knob\t161-kV\tTransmission\tLine  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

8 Blythe-Knob 161-kV Transmission Line Maintenance Project - Continuation Sheet Project Description (continued) The proposed project also includes vegetation management in one...

254

Transmission Investment: A Primer  

SciTech Connect (OSTI)

This primer highlights recent trends in transmission investment, summarizes the division of jurisdictional authority over transmission, and presents four alternative models for transmission ownership. (author)

McGarvey, Joe

2006-10-15T23:59:59.000Z

255

Transmission | Open Energy Information  

Open Energy Info (EERE)

Transmission Lattice.jpg High-voltage transmission lines form the backbone of electricity systems. Transmission lines are designed to carry large amounts of electricity at...

256

Transmission Developers Inc.  

Broader source: Energy.gov (indexed) [DOE]

% ~ % ~ Transmission Developers Inc. July 7, 2011 Mr. Anthony J. Como Director, Permitting and Siting Office ofElectricity Delivery and Energy Reliability (OE-20) U.S. Department of Energy 1000 Independence A venue SW, Room 8G-024 Washington, D.C. 20585 Subject: Champlain Hudson Power Express Project U.S. Department of Energy Presidential Permit Application PP-362 Dear Mr. Como: On January 25, 2010, Transmission Developers, Inc. ("TDI'' or "Applicants") submitted on behalf of Champlain Hudson Power Express, Inc. ("CHPEI") an application to the U.S. Department of Energy ("DOE") for a Presidential Permit and an amendment on August 5, 2010 (collectively, the "Application") in connection with the Champlain Hudson Power Express

257

Power Projects  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Power Projects Power Projects Contact SN Customers Environmental Review-NEPA Operations & Maintenance Planning & Projects Power Marketing Rates You are here: SN Home page > About SNR Power Projects Central Valley: In California's Central Valley, 18 dams create reservoirs that can store 13 million acre-feet of water. The project's 615 miles of canals irrigate an area 400 miles long and 45 miles wide--almost one third of California. Powerplants at the dams have an installed capacity of 2,099 megawatts and provide enough energy for 650,000 people. Transmission lines total about 865 circuit-miles. Washoe: This project in west-central Nevada and east-central California was designed to improve the regulation of runoff from the Truckee and Carson river systems and to provide supplemental irrigation water and drainage, as well as water for municipal, industrial and fishery use. The project's Stampede Powerplant has a maximum capacity of 4 MW.

258

Optoelectronics 514 Transmission Hologram Transmission Hologram  

E-Print Network [OSTI]

Optoelectronics 514 Transmission Hologram Transmission Hologram Purpose: To learn about making Procedure: 1. HeNe Laser: #12;Optoelectronics 514 Transmission Hologram Mount the laser along the long axis. Development #12;Optoelectronics 514 Transmission Hologram Put the plate in the developer emulsion side up

Collins, Gary S.

259

Notice of Intent to prepare an environmental impact statement for the Eastern Plains Transmission Project, Colorado and Kansas (DOE/EIS-0390) (08/02/06)  

Broader source: Energy.gov (indexed) [DOE]

733 Federal Register 733 Federal Register / Vol. 71, No. 148 / Wednesday, August 2, 2006 / Notices term of the proposed preliminary permit would be 36 months. The work proposed under the preliminary permit would include economic analysis, preparation of preliminary engineering plans, and a study of environmental impacts. Based on the results of these studies, the Applicant would decide whether to proceed with the preparation of a development application to construct and operate the project. r. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all

260

Transmission | Department of Energy  

Broader source: Energy.gov (indexed) [DOE]

Transmission Transmission Transmission Below are resources for Tribes on transmission. Transmission 101 Presentation from the National Council on Electricity Policy's Transmissions Technologies workshop. Includes information on transmission technology, costs, and how to plan the system. Transmission on Tribal Land Basics The Tribal Energy and Environmental Information Clearinghouse provides resources for development on tribal lands. Topics covered include transmission technology basics, potential impacts, law and regulations, and tribal incentives. Transmission Pre-Feasibility Study for Tribes Presentation on the components of a pre-feasibility study including generation location, sizing, and desirability, ability and cost to deliver, capacity versus energy, time of delivery versus peak, request for

Note: This page contains sample records for the topic "navajo transmission project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


261

Plains & Eastern Clean Line Project Proposal for New or Upgraded...  

Office of Environmental Management (EM)

Plains & Eastern Clean Line Project Proposal for New or Upgraded Transmission Line Projects Under Section 1222 of the Energy Policy Act of 2005 Plains & Eastern Clean Line Project...

262

Lone Star Transmission LLC | Open Energy Information  

Open Energy Info (EERE)

Zip: 33408 Product: Wholly owned subsidiary of FPL Energy, developing transmission lines. First project is the DFW Express high voltage DC line from West Texas to DallasFort...

263

Gila to North Gila Transmission Line Rebuild  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Gila to North Gila Transmission Line Rebuild and Upgrade Project News and updates: On March 21, 2014, Western issued a Finding of No Significant Impact for the proposed action,...

264

Final audit report of remedial action construction at the UMTRA Project Mexican Hat, Utah -- Monument Valley, Arizona, sites  

SciTech Connect (OSTI)

The final audit report for remedial action at the Mexican Hat, Utah, Monument Valley, Arizona, Uranium Mill Tailings Remedial Action (UMTRA) Project sites consists of a summary of the radiological surveillances/audits, quality assurance (QA) in-process surveillances, and QA remedial action close-out inspections performed by the US Department of Energy (DOE) and the Technical Assistance Contractor (TAC); on-site construction reviews (OSCR) performed by the US Nuclear Regulatory Commission (NRC); and a surveillance performed by the Navajo Nation. This report refers to remedial action activities performed at the Mexican Hat, Utah--Monument Valley, Arizona, Uranium Mill Tailings Remedial Action (UMTRA) Project sites.

NONE

1995-10-01T23:59:59.000Z

265

Notice of Availability of Plains & Eastern Clean Line Transmission...  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

Notice of Availability of Plains & Eastern Clean Line Transmission Project Draft Environmental Impact Statement and Public Hearings: Federal Register Notice, Volume 79, No. 242 -...

266

Construction of Central Ferry-Lower Monumental Transmission Line...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

power line capabilities include transmission, overhead and underground distribution and substation projects. BPA also will be holding two "Meet the Builder" open-houses in late...

267

High voltage overhead long transmission line design and fault analysis.  

E-Print Network [OSTI]

??The goal of this project is to design a reliable high voltage overhead long transmission line that satisfies specific design criteria including voltage regulation, efficiency,… (more)

Elzain, Mohamed Ali

2011-01-01T23:59:59.000Z

268

BPA proposes rate increase to bolster federal power and transmission...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

BPA-proposes-rate-increase-to-bolster-federal-power-and-transmission-systems Sign In About | Careers | Contact | Investors | bpa.gov Search News & Us Expand News & Us Projects...

269

Department of Energy Finalizes Loan Guarantee for New Transmission...  

Office of Environmental Management (EM)

Nevada, improving grid reliability and efficiency. "As our country increases its use of alternative energy sources, new transmissions lines like the ON Line project will play a...

270

RAPID/Geothermal/Transmission Siting & Interconnection/Hawaii...  

Open Energy Info (EERE)

Utilities Commission to interconnect a proposed renewable energy project to the existing grid. Transmission Siting Threshold: No threshold provided Public Utility Definition for...

271

NREL: Transmission Grid Integration - Research Staff  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Research Staff Research Staff NREL's transmission grid integration research staff work to incorporate renewable energy into the transmission system primarily through NREL's Power Systems Engineering Center. Photo of Barbara O'Neill Barbara O'Neill, Transmission and Grid Integration Group Manager M.S., Energy Management and Policy, University of Pennsylvania Engineering Diploma, Petroleum Economics and Management, French Institute of Petroleum B.S., Electrical Engineering, Pratt Institute Barbara has a diverse background with expertise in such fields as wind and solar project development, energy forecasting, renewable energy power purchase agreements, interconnection issues, market structures, and stakeholder engagement. Barbara currently manages the Transmission and Grid

272

RRTT - Rapid Response Team for Transmission  

Broader source: Energy.gov (indexed) [DOE]

Rapid Response Team- Rapid Response Team- Transmission Exploring the Business Link Opportunity: Transmission & Clean Energy Development in the West TRIBAL LEADER FORUM SERIES February 7, 2012 Laura Smith Morton Department of Energy Laura.morton@hq.doe.gov Nine Agency MOU * Improves uniformity, consistency, and transparency - Establishes the roles and responsibilities of the nine signatory agencies regarding electric transmission infrastructure project applicants * Provides single point of contact for coordinating all federal authorizations required to locate electric transmission facilities on federal land * Establishes DOE (under authority pursuant to section 216(h) of the FPA) as lead agency for coordinating all federal authorizations and related environmental

273

Transmission Line Security Monitor: Final Report  

SciTech Connect (OSTI)

The Electric Power Transmission Line Security Monitor System Operational Test is a project funded by the Technical Support Working Group (TSWG). TSWG operates under the Combating Terrorism Technical Support Office that functions under the Department of Defense. The Transmission Line Security Monitor System is based on technology developed by Idaho National Laboratory. The technology provides a means for real-time monitoring of physical threats and/or damage to electrical transmission line towers and conductors as well as providing operational parameters to transmission line operators to optimize transmission line operation. The end use is for monitoring long stretches of transmission lines that deliver electrical power from remote generating stations to cities and industry. These transmission lines are generally located in remote transmission line corridors where security infrastructure may not exist. Security and operational sensors in the sensor platform on the conductors take power from the transmission line and relay security and operational information to operations personnel hundreds of miles away without relying on existing infrastructure. Initiated on May 25, 2007, this project resulted in pre-production units tested in realistic operational environments during 2010. A technology licensee, Lindsey Manufacturing of Azusa California, is assisting in design, testing, and ultimately production. The platform was originally designed for a security monitoring mission, but it has been enhanced to include important operational features desired by electrical utilities.

John Svoboda

2011-04-01T23:59:59.000Z

274

Transmission Business Unit Manager  

Broader source: Energy.gov [DOE]

(See Frequently Asked Questions for more information). Where would I be working? Western Area Power Administration Rocky Mountain Region Transmission Services, (J7300) Transmission Busiess Unit 615...

275

State transmission infrastructure authorities: the story so far  

SciTech Connect (OSTI)

State transmission infrastructure authorities offer a new tool for helping to overcome such obstacles to developing transmission as high capital investment requirements, uncertain cost allocation among multiple parties, and siting and permitting challenges. Yet to be determined is whether they can help stimulate large, multi-state regional transmission projects. (author)

Porter, Kevin; Fink, Sari

2009-03-15T23:59:59.000Z

276

FINAL PROJECT REPORT LOAD MODELING TRANSMISSION RESEARCH  

E-Print Network [OSTI]

family and multi?family residential buildings, the model is wall area of a building shall be   Multi-Family Rules ofclass Building type Floor area Single-family home all Multi-

Lesieutre, Bernard

2013-01-01T23:59:59.000Z

277

FINAL PROJECT REPORT LOAD MODELING TRANSMISSION RESEARCH  

E-Print Network [OSTI]

2009.   Inverter  Test Procedures Solar Generation Impact Conditioner Testing Procedures  Appendix B: Air Conditioner air conditioner testing procedures and results from studies 

Lesieutre, Bernard

2013-01-01T23:59:59.000Z

278

FINAL PROJECT REPORT LOAD MODELING TRANSMISSION RESEARCH  

E-Print Network [OSTI]

R22 PMAXLow (PSI) Phase Refrigerant Charge (LBS) Voltage (V)LRA (AMPS) Phase Refrigerant Charge (LBS) Voltage (V) PMAXR22 PMAXLow (PSI) Phase Refrigerant Charge (LBS) Voltage (V)

Lesieutre, Bernard

2013-01-01T23:59:59.000Z

279

FINAL PROJECT REPORT LOAD MODELING TRANSMISSION RESEARCH  

E-Print Network [OSTI]

at PSE is to collect load data for validating dynamic and approach decomposes recorded load data into different load “to continuously record load data for a selected time period

Lesieutre, Bernard

2013-01-01T23:59:59.000Z

280

Big Eddy-Knight Transmission Project  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

BPA's existing Big Eddy Substation in The Dalles, Oregon, to a proposed new Knight Substation that would be connected to an existing BPA line about 4 miles northwest of...

Note: This page contains sample records for the topic "navajo transmission project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


281

FINAL PROJECT REPORT LOAD MODELING TRANSMISSION RESEARCH  

E-Print Network [OSTI]

BPA), the basic requirements for an improved load model were determined. These requirements included modeling the substation

Lesieutre, Bernard

2013-01-01T23:59:59.000Z

282

FINAL PROJECT REPORT LOAD MODELING TRANSMISSION RESEARCH  

E-Print Network [OSTI]

such as synchronous and induction generators.   Most of the as  synchronous and induction generators.   Most of the 

Lesieutre, Bernard

2013-01-01T23:59:59.000Z

283

FINAL PROJECT REPORT LOAD MODELING TRANSMISSION RESEARCH  

E-Print Network [OSTI]

Unit Evaporator Coil Size (Tons) Compressor Type Refrigerant SEER FANUnit Evaporator Coil Size (Tons) Compressor Type Refrigerant SEER FANUnit Evaporator Coil Size (Tons) Compressor Type Refrigerant SEER FAN

Lesieutre, Bernard

2013-01-01T23:59:59.000Z

284

FINAL PROJECT REPORT LOAD MODELING TRANSMISSION RESEARCH  

E-Print Network [OSTI]

to be the compact fluorescent bulbs (CFBs) that the engineerbulbs with compact fluorescent bulbs (CFBs) continues to

Lesieutre, Bernard

2013-01-01T23:59:59.000Z

285

FINAL PROJECT REPORT LOAD MODELING TRANSMISSION RESEARCH  

E-Print Network [OSTI]

pump heating fraction, EF heatpump , shall be the fraction q P p P q (P) (Q) (B) Lighting Washing Heating 0.1F heatpump0.3F heatpump Cooling Refrigeration Z q Hotwater Plugs Z p (

Lesieutre, Bernard

2013-01-01T23:59:59.000Z

286

FINAL PROJECT REPORT LOAD MODELING TRANSMISSION RESEARCH  

E-Print Network [OSTI]

commercial building energy use and cost analysis. With input of building layout, construction types, space usage,

Lesieutre, Bernard

2013-01-01T23:59:59.000Z

287

FINAL PROJECT REPORT LOAD MODELING TRANSMISSION RESEARCH  

E-Print Network [OSTI]

and Africa (PVGIS).  National Renewable Energy Laboratory has solar and Africa [14].  National Renewable Energy Laboratory (NREL) has solar 

Lesieutre, Bernard

2013-01-01T23:59:59.000Z

288

Hooper Springs Transmission Project Final Environmental Impact...  

Energy Savers [EERE]

like to ensure that our ability to utilize this location as a borrow source for growth media remains unencumbered, which may necessitate BPA re-grading or realigning the access...

289

FINAL PROJECT REPORT LOAD MODELING TRANSMISSION RESEARCH  

E-Print Network [OSTI]

Bulk System Load  Model in GE PSLF TM for Investigating the a Bulk System Load Model in GE PSLF TM for Investigating thecomposite load model in  the PSLF simulation software; the 

Lesieutre, Bernard

2013-01-01T23:59:59.000Z

290

FINAL PROJECT REPORT LOAD MODELING TRANSMISSION RESEARCH  

E-Print Network [OSTI]

like hardware (PMU), software and data communication. TheSpecifications and Technical Data PMU Model Number of NumberPMU Specifications and Technical Data ..

Lesieutre, Bernard

2013-01-01T23:59:59.000Z

291

EIS-0231: Draft Environmental Impact Statement | Department of Energy  

Broader source: Energy.gov (indexed) [DOE]

1: Draft Environmental Impact Statement 1: Draft Environmental Impact Statement EIS-0231: Draft Environmental Impact Statement Draft Environmental Impact Statement Navajo Transmission Project This EIS evaluates the environmental impacts of a proposal to by Dine Power Authority, a Navajo Nation enterprise, to construct, operate, and maintain a 500 kilovolt (kV) transmission line planned to deliver electric power from the Four Comers area in northwestern New Mexico across northern Arizona to a terminus in southeastern Nevada. The proposed project, the Navajo Transmission Project, is currentiy planned to be in service in the year 2001 and operate for about 50 years. EIS-0231-DEIS-1996.pdf More Documents & Publications EA-1470: Final Environmental Assessment EIS-0256: Final Environmental Impact Statement

292

National Transmission Grid Study  

Broader source: Energy.gov (indexed) [DOE]

Grid Study Grid Study U.S. Department of Energy The Honorable Spencer Abraham Secretary of Energy May 2002 ii National Transmission Grid Study National Transmission Grid Study i ii National Transmission Grid Study National Transmission Grid Study iii How This Study Was Conducted The National Energy Policy Plan directed the U.S. Department of Energy (DOE) to conduct a study to examine the benefits of establishing a national electricity transmission grid and to identify transmission bottlenecks and measures to address them. DOE began by conducting an independent analysis of U.S. electricity markets and identifying transmission system bottlenecks using DOE's Policy Office Electricity Modeling System (POEMS). DOE's analysis, presented in Section 2, confirms the central role of the nation's transmission

293

Transmission | Open Energy Information  

Open Energy Info (EERE)

Gateway Gateway Edit History Facebook icon Twitter icon » Transmission (Redirected from Transmission) Jump to: navigation, search Transmission header.png Transmission Dashboard Permitting Atlas Compare States Arizona California Colorado Idaho Montana Nevada New Mexico Oregon Utah Washington Wyoming Resource Library NEPA Database Transmission Lattice.jpg High-voltage transmission lines form the backbone of electricity systems. Transmission lines are designed to carry large amounts of electricity at high voltages, typically 115 to 500 kilovolts (kV), across long distances. Networks of transmission lines transfer electricity from power plants or other interconnections to substations. At substations, the high-voltage electricity is "stepped down" to a lower voltage, which can be carried

294

STRATEGIC TRANSMISSION INVESTMENT PLAN  

E-Print Network [OSTI]

CALIFORNIA ENERGY COMMISSION STRATEGIC TRANSMISSION INVESTMENT PLAN Prepared in Support of the 2007. Blevins #12; i ACKNOWLEDGEMENTS The 2007 Strategic Transmission Investment Plan was prepared Investment Plan. California Energy Commission, Engineering Office. CEC7002007018CTF. #12; ii #12; iii

295

STRATEGIC TRANSMISSION INVESTMENT PLAN  

E-Print Network [OSTI]

CALIFORNIA ENERGY COMMISSION STRATEGIC TRANSMISSION INVESTMENT PLAN Prepared in Support of the 2007 Investment Plan was prepared with contribution from the following Energy Commission staff and consultants Kondoleon, Chuck Najarian. 2007 Strategic Transmission Investment Plan. California Energy Commission

296

Transmission Utilization Group (TUG)  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Improvement (CBPI) Customer Forum Energy Imbalance Market Generator Interconnection Reform Implementation Intertie Initiatives Intertie Open Season Transmission Utilization...

297

Underground Power Transmission  

Science Journals Connector (OSTI)

...The type of transmission line for a particular...will force rt transmission lines to be ground near...history of power transmission shows that d-c...characteristics of a d-c line, it is easy to...Best data fit III II I...

P. H. Rose

1970-10-16T23:59:59.000Z

298

EC Transmission Line Risk Identification and Analysis  

SciTech Connect (OSTI)

The purpose of this document is to assist in evaluating and planning for the cost, schedule, and technical project risks associated with the delivery and operation of the EC (Electron cyclotron) transmission line system. In general, the major risks that are anticipated to be encountered during the project delivery phase associated with the implementation of the Procurement Arrangement for the EC transmission line system are associated with: (1) Undefined or changing requirements (e.g., functional or regulatory requirements) (2) Underperformance of prototype, first unit, or production components during testing (3) Unavailability of qualified vendors for critical components Technical risks associated with the design and operation of the system are also identified.

Bigelow, Tim S [ORNL

2012-04-01T23:59:59.000Z

299

Energy Transmission and Infrastructure  

SciTech Connect (OSTI)

The objective of Energy Transmission and Infrastructure Northern Ohio (OH) was to lay the conceptual and analytical foundation for an energy economy in northern Ohio that will: • improve the efficiency with which energy is used in the residential, commercial, industrial, agricultural, and transportation sectors for Oberlin, Ohio as a district-wide model for Congressional District OH-09; • identify the potential to deploy wind and solar technologies and the most effective configuration for the regional energy system (i.e., the ratio of distributed or centralized power generation); • analyze the potential within the district to utilize farm wastes to produce biofuels; • enhance long-term energy security by identifying ways to deploy local resources and building Ohio-based enterprises; • identify the policy, regulatory, and financial barriers impeding development of a new energy system; and • improve energy infrastructure within Congressional District OH-09. This objective of laying the foundation for a renewable energy system in Ohio was achieved through four primary areas of activity: 1. district-wide energy infrastructure assessments and alternative-energy transmission studies; 2. energy infrastructure improvement projects undertaken by American Municipal Power (AMP) affiliates in the northern Ohio communities of Elmore, Oak Harbor, and Wellington; 3. Oberlin, OH-area energy assessment initiatives; and 4. a district-wide conference held in September 2011 to disseminate year-one findings. The grant supported 17 research studies by leading energy, policy, and financial specialists, including studies on: current energy use in the district and the Oberlin area; regional potential for energy generation from renewable sources such as solar power, wind, and farm-waste; energy and transportation strategies for transitioning the City of Oberlin entirely to renewable resources and considering pedestrians, bicyclists, and public transportation as well as drivers in developing transportation policies; energy audits and efficiency studies for Oberlin-area businesses and Oberlin College; identification of barriers to residential energy efficiency and development of programming to remove these barriers; mapping of the solar-photovoltaic and wind-energy supply chains in northwest Ohio; and opportunities for vehicle sharing and collaboration among the ten organizations in Lorain County from the private, government, non-profit, and educational sectors. With non-grant funds, organizations have begun or completed projects that drew on the findings of the studies, including: creation of a residential energy-efficiency program for the Oberlin community; installation of energy-efficient lighting in Oberlin College facilities; and development by the City of Oberlin and Oberlin College of a 2.27 megawatt solar photovoltaic facility that is expected to produce 3,000 megawatt-hours of renewable energy annually, 12% of the College’s yearly power needs. Implementation of these and other projects is evidence of the economic feasibility and technical effectiveness of grant-supported studies, and additional projects are expected to advance to implementation in the coming years. The public has benefited through improved energydelivery systems and reduced energy use for street lighting in Elmore, Oak Harbor, and Wellington; new opportunities for assistance and incentives for residential energy efficiency in the Oberlin community; new opportunities for financial and energy savings through vehicle collaboration within Lorain County; and decreased reliance on fossil fuels and expanded production of renewable energy in the region. The dissemination conference and the summary report developed for the conference also benefited the public, but making the findings and recommendations of the regional studies broadly available to elected officials, city managers, educators, representatives of the private sector, and the general public.

Mathison, Jane

2012-12-31T23:59:59.000Z

300

Vice President, Transmission Marketing & Sales  

Broader source: Energy.gov [DOE]

Within Transmission Services at Bonneville Power Administration (BPA), Transmission Marketing and Sales (TS) provides open access to the Federal Transmission System (FTS) consistent with...

Note: This page contains sample records for the topic "navajo transmission project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


301

Windy Gap Firming Project  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Windy Gap Firming Project Windy Gap Firming Project Skip Navigation Links Transmission Functions Infrastructure projects Interconnection OASIS OATT Windy Gap Firming Project, Final Environmental Impact Statement, DOE/EIS-0370 (cooperating agency) Western's proposed action is to relocate approximately 3.8 miles of the existing Estes to Lyons 115-kilovolt transmission line, if the Chimney Hollow Reservoir alternative is constructed. The line would be moved outside the area proposed for the reservoir, and Western would ensure the new location would allow the agency to continue to operate and maintain it. Section 2.4.1.4 of the Final Environmental Impact Statement, Volume 1 provides more information on the transmission line relocation proposal. The U.S. Department of the Interior, Bureau of Reclamation is the Lead Agency for the National Environmental Policy Act Review. Cooperating agencies are Western, the U.S. Army Corps of Engineers and Grand County, Colo.

302

Transmission | Open Energy Information  

Open Energy Info (EERE)

source source History View New Pages Recent Changes All Special Pages Semantic Search/Querying Get Involved Help Apps Datasets Community Login | Sign Up Search Gateway Edit History Facebook icon Twitter icon » Transmission Jump to: navigation, search Transmission header.png Transmission Dashboard Permitting Atlas Compare States Arizona California Colorado Idaho Montana Nevada New Mexico Oregon Utah Washington Wyoming Resource Library NEPA Database Transmission Lattice.jpg High-voltage transmission lines form the backbone of electricity systems. Transmission lines are designed to carry large amounts of electricity at high voltages, typically 115 to 500 kilovolts (kV), across long distances. Networks of transmission lines transfer electricity from power plants or other interconnections to substations. At substations, the high-voltage

303

Project Title  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Infrastructure for CCS August 20-22, 2013 2 Presentation Outline * Introduction * Organization * Benefit to Program * Project Overview * Technical Status * Accomplishments to Date * Summary * Appendix Introduction * Most storage modeling studies assume a discrete reservoir/caprock interface with simple (uniform) flow conditions. * We address the question of whether or not heterogeneities at the interface influence transmission of CO 2 into the caprock 3 4 Reservoir Caprock Reservoir Introduction The nature of reservoir/caprock interfaces 4 Organization 5 Peter Mozley (PD/PI) NMT Sedimentology James Evans (Co-PI) USU Structure Thomas Dewers (Co-I) Jason Heath (Staff) SNL Modeling Mark Person (Cooperating Scientist) NMT Modeling Stefan Raduha NMT Sedimentology

304

Market-based Investment in Electricity Transmission Networks: Controllable Flow  

E-Print Network [OSTI]

in new lines, rather than small-scale network upgrades. Whereas market-based transmission investment may mitigate the problem of under- investment, it is unlikely to suffice alone and thus regulated projects by the designated transmission system... aims at transmission of bulk power to be less than small-scale AC network deepening projects; even if these AC projetcs are small scale, they may be large compared to the size of their market. The DC-interconnector projects in the USA are typically...

Brunekreeft, Gert

2004-06-16T23:59:59.000Z

305

State Transmission Infrastructure Authorities: The Story So Far; December 2007 - December 2008  

SciTech Connect (OSTI)

This report examines the status and future direction of state transmission infrastructure authorities. It summarizes common characteristics, discusses current transmission projects, and outlines common issues the state infrastructure authorities have faced.

Porter, K.; Fink. S.

2008-05-01T23:59:59.000Z

306

BLM Approves California Geothermal Development Project | Department...  

Broader source: Energy.gov (indexed) [DOE]

16 new production and injection wells, multiple pipelines, and an electric transmission line. Ormat Nevada Inc. will develop the project on public and private land. When completed,...

307

Transmission/Nepa Database | Open Energy Information  

Open Energy Info (EERE)

Nepa Database Nepa Database < Transmission Jump to: navigation, search NepaHeader.png Transmission Dashboard Permitting Atlas Compare States Arizona California Colorado Idaho Montana Nevada New Mexico Oregon Utah Washington Wyoming Resource Library NEPA Database Document Collections (1) Have a NEPA Document Collection to add that doesn't yet exist in this collection? Make sure it doesn't already exist: Please be sure to search this page by serial number and by document number Add.png Add a new NEPA Document Collection This query has been included to allow you to use the black arrows in the table header cells to sort the table data. Document Name Serial Number Analysis Type Transmission Type Project Area Applicant Lead Agency District Office Project Phase(s) TransWest EIS 600kV Wyoming Western Power Administration BLM BLM Wyoming State Office

308

Series Transmission Line Transformer  

DOE Patents [OSTI]

A series transmission line transformer is set forth which includes two or more of impedance matched sets of at least two transmissions lines such as shielded cables, connected in parallel at one end ans series at the other in a cascading fashion. The cables are wound about a magnetic core. The series transmission line transformer (STLT) which can provide for higher impedance ratios and bandwidths, which is scalable, and which is of simpler design and construction.

Buckles, Robert A. (Livermore, CA); Booth, Rex (Livermore, CA); Yen, Boris T. (El Cerrito, CA)

2004-06-29T23:59:59.000Z

309

Transmission/Resource Library/MOU | Open Energy Information  

Open Energy Info (EERE)

source source History View New Pages Recent Changes All Special Pages Semantic Search/Querying Get Involved Help Apps Datasets Community Login | Sign Up Search Page Edit History Facebook icon Twitter icon » Transmission/Resource Library/MOU < Transmission‎ | Resource Library Jump to: navigation, search ResourceLibraryHeader.png Public Involvement Resources GIS Tools and Maps Environmental Resources and Mitigation NEPA MOUs General Transmission Documents Transmission Dashboard Permitting Atlas Compare States Arizona California Colorado Idaho Montana Nevada New Mexico Oregon Utah Washington Wyoming Resource Library NEPA Database Memorandums of Understanding (MOUs)for Interstate Transmission Projects Multi-state transmission siting and permitting projects benefit from effective collaboration between government entities, tribes, project

310

Stream Control Transmission Protocol  

Science Journals Connector (OSTI)

This document describes the Stream Control Transmission Protocol (SCTP). SCTP is designed to transport PSTN signaling messages over IP networks, but is capable of broader applications.

R. Stewart; Q. Xie; K. Morneault; C. Sharp; H. Schwarzbauer; T. Taylor; I. Rytina; M. Kalla; L. Zhang; V. Paxson

2000-10-01T23:59:59.000Z

311

Application for Presidential Permit OE Docket No. PP-362 Champlain Hudson Power Express, Inc.: Record of Decision for Issuing a Presidential Permit for the CHPE Transmission Line Project: Federal Register Notice, Volume 79, No. 190- Oct. 1, 2014  

Broader source: Energy.gov [DOE]

The Department of Energy (DOE) announces its decision to issue a Presidential permit to Champlain Hudson Power Express, Inc. (CHPEI), to construct, operate, maintain, and connect an electric transmission line across the U.S./Canada border in the northeastern New York State.

312

Project Year Project Title  

E-Print Network [OSTI]

the cost of the project to labor only. The efficacy of the examples will be assessed through their useProject Year 2012-2013 Project Title Sight-Reading at the Piano Project Team Ken Johansen, Peabody) Faculty Statement The goal of this project is to create a bank of practice exercises that student pianists

Gray, Jeffrey J.

313

Project Year Project Team  

E-Print Network [OSTI]

design goals for this project include low cost (less than $30 per paddle) and robustness. The projectProject Year 2001 Project Team Faculty: Allison Okamura, Mechanical Engineering, Whiting School Project Title Haptic Display of Dynamic Systems Audience 30 to 40 students per year, enrolled

Gray, Jeffrey J.

314

Project Year Project Team  

E-Print Network [OSTI]

-year section of the summer project will cost $1344.) This project will be measured by the CER surveys conductedProject Year 2005 Project Team Sean Greenberg, Faculty, Philosophy Department, Krieger School of Arts & Sciences; Kevin Clark, Student, Philosophy Department, Krieger School of Arts & Sciences Project

Gray, Jeffrey J.

315

Transmission Line Security Monitor  

SciTech Connect (OSTI)

The Transmission Line Security Monitor is a multi-sensor monitor that mounts directly on high-voltage transmission lines to detect, characterize and communicate terrorist activity, human tampering and threatening conditions around support towers. For more information about INL's critical infrastructure protection research, visit http://www.facebook.com/idahonationallaboratory.

None

2011-01-01T23:59:59.000Z

316

Transmission Line Security Monitor  

ScienceCinema (OSTI)

The Transmission Line Security Monitor is a multi-sensor monitor that mounts directly on high-voltage transmission lines to detect, characterize and communicate terrorist activity, human tampering and threatening conditions around support towers. For more information about INL's critical infrastructure protection research, visit http://www.facebook.com/idahonationallaboratory.

None

2013-05-28T23:59:59.000Z

317

Generation and Transmission Maximization Model | Open Energy Information  

Open Energy Info (EERE)

Generation and Transmission Maximization Model Generation and Transmission Maximization Model Jump to: navigation, search Tool Summary Name: Generation and Transmission Maximization Model Agency/Company /Organization: Argonne National Laboratory Sector: Energy Topics: Pathways analysis Resource Type: Software/modeling tools User Interface: Desktop Application Website: www.dis.anl.gov/projects/Gtmax.html Cost: Paid Generation and Transmission Maximization Model Screenshot References: Generation and Transmission Maximization Model [1] Logo: Generation and Transmission Maximization Model The GTMax model helps researchers study complex marketing and system operational issues. With the aid of this comprehensive model, utility operators and managers can maximize the value of the electric system, taking into account not only its limited energy and transmission resources,

318

GRR/Section 8 - Transmission Overview | Open Energy Information  

Open Energy Info (EERE)

GRR/Section 8 - Transmission Overview GRR/Section 8 - Transmission Overview < GRR Jump to: navigation, search GRR-logo.png GEOTHERMAL REGULATORY ROADMAP Roadmap Home Roadmap Help List of Sections Section 8 - Transmission Overview 08 - TransmissionOverview.pdf Click to View Fullscreen Contact Agencies Federal Energy Regulatory Commission Regulations & Policies FERC Order No. 2003 FERC Order No. 2006 Triggers None specified Click "Edit With Form" above to add content 08 - TransmissionOverview.pdf 08 - TransmissionOverview.pdf Error creating thumbnail: Page number not in range. Error creating thumbnail: Page number not in range. Flowchart Narrative The siting of an individual project can have a major impact on transmission and interconnection. 8.1 - Will the Power Plant Developer Negotiate an Interconnection

319

Project Year Project Team  

E-Print Network [OSTI]

Project Year 2002 Project Team Faculty: Louise Pasternack, Chemistry Department, Krieger School, Krieger School of Arts & Sciences Project Title Introductory Chemistry Lab Demonstrations Audience an interactive virtual lab manual that will facilitate understanding of the procedures and techniques required

Gray, Jeffrey J.

320

EIS-0344: Grand Coulee-Bell 500 kV Transmission Line  

Broader source: Energy.gov [DOE]

This EIS analyzes DOE's proposed action for the construction and operation of the proposed Grand Coulee-Bell 500-kV Transmission Line Project.

Note: This page contains sample records for the topic "navajo transmission project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


321

Mead-Liberty 345-kV Transmission Line Access Road Maintenance...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

2 Mead-Liberty 345-kV Transmission Line Access Road Maintenance and Localized Vegetation Management Maricopa County, Arizona Categorical Exclusion Continuation Sheet Project...

322

Project Year Project Team  

E-Print Network [OSTI]

(Karl) Zhang, Undergraduate Student, Biomedical Engineering, Whiting School of Engineering; Cheryl Kim Audio, Digital Video Project Abstract The goal of this project is to develop online modular units

Gray, Jeffrey J.

323

Transmission line environmental assessment guidance document  

SciTech Connect (OSTI)

Since 1939, U.S. utility companies have been required to obtain a Presidential Permit to construct electric transmission lines that cross a U.S. border and connect with a foreign utility. The purpose of this document is to provide Presidential Permit applicants with two types of guidance: (1) on the type of environmental and project descriptive information needed to assess the potential impacts of the proposed and alternative actions and (2) on compliance with applicable federal and state regulations. The main three chapters present information on the purpose and content of this document (Chapter 1); legislative, regulatory, and consultation requirements for transmission line interconnect projects (Chapter 2); and identification of basic transmission system design parameters and environmental data requirements for analysis of potential impacts of the proposed action (Chapter 3). Chapter 3 also includes information on possible techniques or measures to mitigate impacts. Appendix A presents an overview of NEPA requirements and DOE`s implementing procedures. Appendix B summarizes information on legislation that may be applicable to transmission line projects proposed in Presidential Permit applications.

Jackson, J.; Pentecost, E.; Muzzarelli, J.

1994-01-01T23:59:59.000Z

324

Line Projects  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

(PDCI) Upgrade Project Whistling Ridge Energy Project Line Rebuild, Relocation and Substation Projects Wind Projects Line Projects BPA identifies critical infrastructure and...

325

Application Filling Requirements for Transmission Line and Substation  

Broader source: Energy.gov (indexed) [DOE]

Application Filling Requirements for Transmission Line and Application Filling Requirements for Transmission Line and Substation Construction Projects (Wisconsin) Application Filling Requirements for Transmission Line and Substation Construction Projects (Wisconsin) < Back Eligibility Agricultural Commercial Construction Developer Fed. Government Fuel Distributor General Public/Consumer Industrial Installer/Contractor Institutional Investor-Owned Utility Local Government Low-Income Residential Multi-Family Residential Municipal/Public Utility Nonprofit Residential Retail Supplier Rural Electric Cooperative Schools State/Provincial Govt Systems Integrator Transportation Tribal Government Utility Savings Category Alternative Fuel Vehicles Hydrogen & Fuel Cells Buying & Making Electricity Water Home Weatherization Wind Solar Program Info

326

Project Year Project Title  

E-Print Network [OSTI]

that incorporate video taped procedures for student preview. Solution This project will create videos for more to study the procedure and techniques before coming to class. Our previous fellowship project addressedProject Year 2009 Project Title Enhancing Biology Laboratory Preparation through Video

Gray, Jeffrey J.

327

Project Year Project Team  

E-Print Network [OSTI]

, there is no resource available to view the procedure before class. Solution The purpose of this project is to capture available to view the procedure before class. The purpose #12;of this project is to capture variousProject Year 2007 Project Team Kristina Obom, Faculty, Advanced Academic Programs, Krieger School

Gray, Jeffrey J.

328

Project Year Project Title  

E-Print Network [OSTI]

Project Year 2013-2014 Project Title German Online Placement Exam Project Team Deborah Mifflin to increased cost. As well, it lacked listening comprehension, writing and speaking components providing support, we will use Blackboard for this project. The creation will require numerous steps

Gray, Jeffrey J.

329

Transmission Access Resources  

Broader source: Energy.gov [DOE]

Historically, the addition of new electric generation facilities has been accompanied by new transmission systems. For example, large nuclear and coal plants built in the 1960s and 1970s required...

330

Performance Incentives for Transmission  

E-Print Network [OSTI]

The Federal Energy Regulatory Commission's Standard Market Design Notice of Public Rule- making (SMD NOPRPerformance Incentives for Transmission FERC's Standard Market Design should accommodate of California at Berkeley. The research described in this article was supported by National Grid, USA

Oren, Shmuel S.

331

Designing electricity transmission auctions  

E-Print Network [OSTI]

The UK has ambitious plans for exploiting offshore wind for electricity production in order to meet its challenging target under the EU Renewable Energy Directive. This could involve investing up to 20bn in transmission assets to bring electricity...

Greve, Thomas; Pollitt, Michael G.

2012-10-26T23:59:59.000Z

332

Electric Transmission Lines (Iowa)  

Broader source: Energy.gov [DOE]

Electric transmission lines capable of operating at 69 kV or greater cannot be constructed along, across, or over any public highways or grounds outside of cities without a franchise from the...

333

Audio Transmission Systems  

Science Journals Connector (OSTI)

Audio transmission systems are the means by which audio signals are routed, processed, and assigned to the desired monitor and recording output channels. In the early days of electrical recording, rarely more ...

John Eargle

1986-01-01T23:59:59.000Z

334

Transmission Grid Integration  

Broader source: Energy.gov [DOE]

The levels of solar energy penetration envisioned by the DOE SunShot Initiative must be interconnected effectively onto the transmission grid. This interconnection requires an in-depth...

335

DOE Seeking Information on Transmission Line Permitting | Department of  

Broader source: Energy.gov (indexed) [DOE]

Seeking Information on Transmission Line Permitting Seeking Information on Transmission Line Permitting DOE Seeking Information on Transmission Line Permitting February 27, 2012 - 3:25pm Addthis The Department of Energy's Office of Electricity Delivery and Energy Reliability is seeking information on the questions related to permitting of transmission lines. Infrastructure projects - such as high voltage, long distance, electric transmission facilities - often involve multiple Federal, State, local, and Tribal authorizations and are subject to a wide array of processes and procedural requirements in order to obtain all necessary permits and other authorizations. Delays in securing required statutory reviews, permits, and consultations can threaten the completion projects of national and regional significance. This Request for

336

Coordination of Federal Transmission Permitting on Federal Lands (216(h)) |  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Coordination of Federal Transmission Permitting on Federal Lands (216(h)) Coordination of Federal Transmission Permitting on Federal Lands (216(h)) Coordination of Federal Transmission Permitting on Federal Lands (216(h)) On October 23, 2009, the Department of Energy and eight other Federal agencies entered into a Memorandum of Understanding (MOU) to improve coordination among project applicants, federal agencies, states and tribes involved in the siting and permitting process for electric transmission facilities on Federal land. The MOU will improve uniformity, consistency, and transparency by describing each entity's role and responsibilities when project applicants wish to build electric transmission facilities. Additionally, the MOU designates a "Lead Agency" serving as the single point-of-contact for coordinating all federal environmental reviews

337

Honda Transmission Technical Center  

High Performance Buildings Database

Russells Point, OH The Honda Transmission Technical Center is located on the Honda of America Manufacturing Plant facility site in Russells Point, Ohio. This facility is used for product engineering and market quality testing and analysis of automatic transmissions. The building contains a large workshop area for ten cars, a future dynamometer, two laboratories, an open office area, three conference rooms, a break room, restrooms, and related support areas.

338

Transmission Right Of Way  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

About SNR > Right Of Way About SNR > Right Of Way Right Of Way Preferred Vegetation List - Redding & Foothills (XLS - 23K) Preferred Vegetation List - Sacramento Valley (XLS - 170K) WESTERN AREA POWER ADMINISTRATION GENERAL GUIDELINES CONCERNING THE USE OF ELECTRIC TRANSMISSION LINE RIGHTS-OF-WAY Western Area Power Administration (Western) owns a right-of-way easement along the length of the transmission line (width varies by transmission line). Western's rights within the easement include the right to construct, reconstruct, operate, maintain, and patrol the transmission line. Rights usually reserved to the landowner include the right to cultivate, occupy, and use the land for any purpose that does not conflict with Western's use of its easement. To avoid potential conflicts, it is Western's policy to review all proposed uses within the transmission line easement. We consider (1) Safety of the public, (2) Safety of our Employees, (3) Restrictions covered in the easement, (4) Western's maintenance requirements, and (5) Protection of the transmission line structures and (6) Road or street crossings.

339

Colorado/Transmission/Agencies | Open Energy Information  

Open Energy Info (EERE)

Agencies < Colorado | Transmission Jump to: navigation, search Colorado Transmission Roadmap Agency Links Local Regulations State Regulations Summary General Transmission...

340

National Electric Transmission Congestion Study Webinars | Department...  

Broader source: Energy.gov (indexed) [DOE]

National Electric Transmission Congestion Study National Electric Transmission Congestion Study Webinars National Electric Transmission Congestion Study Webinars The Department...

Note: This page contains sample records for the topic "navajo transmission project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


341

Transmission Planning | Department of Energy  

Office of Environmental Management (EM)

Planning Transmission Planning Modernizing America's electricity infrastructure is one of the U.S. Department of Energy's top priorities. The National Transmission Grid Study made...

342

Electricity Transmission, A Primer | Department of Energy  

Broader source: Energy.gov (indexed) [DOE]

Transmission, A Primer Electricity Transmission, A Primer This primer on electric transmission is intended to help policymakers understand the physics of the transmission system,...

343

Project Title  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Building the Building the Infrastructure for CO 2 Storage August 21-23, 2012 2 Presentation Outline * Introduction * Organization * Benefit to Program * Project Overview * Technical Status * Accomplishments to Date * Summary * Appendix Introduction * Most storage modeling studies involve a caprock/reservoir interface, and assume a discrete contact with simple (uniform) flow conditions. * We address the question of whether or not heterogeneities at the interface influence transmission of CO 2 into the caprock 3 Introduction The nature of reservoir/caprock interfaces 4 Triassic-Jurassic Strata, San Rafael Swell, UT Organization 5 Peter Mozley (PD/PI) NMT Sedimentology James Evans (Co-PI) USU Structure Thomas Dewers (Co-I) Jason Heath (Staff) SNL Modeling Mark Person

344

Natural Gas Transmission and Distribution Module  

Gasoline and Diesel Fuel Update (EIA)

page intentionally left blank page intentionally left blank 129 U.S. Energy Information Administration | Assumptions to the Annual Energy Outlook 2011 Natural Gas Transmission and Distribution Module The NEMS Natural Gas Transmission and Distribution Module (NGTDM) derives domestic natural gas production, wellhead and border prices, end-use prices, and flows of natural gas through the regional interstate network, for both a peak (December through March) and off peak period during each projection year. These are derived by solving for the market equilibrium across the three main components of the natural gas market: the supply component, the demand component, and the transmission and distribution network that links them. Natural gas flow patterns are a function of the pattern in the previous year, coupled

345

Natural Gas Transmission and Distribution Module This  

Gasoline and Diesel Fuel Update (EIA)

This This page inTenTionally lefT blank 127 U.S. Energy Information Administration | Assumptions to the Annual Energy Outlook 2012 Natural Gas Transmission and Distribution Module The NEMS Natural Gas Transmission and Distribution Module (NGTDM) derives domestic natural gas production, wellhead and border prices, end-use prices, and flows of natural gas through a regional interstate representative pipeline network, for both a peak (December through March) and off-peak period during each projection year. These are derived by solving for the market equilibrium across the three main components of the natural gas market: the supply component, the demand component, and the transmission and distribution network that links them. Natural gas flow patterns are a function of the

346

California/Transmission/State Regulations | Open Energy Information  

Open Energy Info (EERE)

California/Transmission/State Regulations California/Transmission/State Regulations < California‎ | Transmission Jump to: navigation, search CaliforniaTransmissionHeader.png Roadmap Agency Links Local Regulations State Regulations Summary General Transmission Dashboard Permitting Atlas Compare States Arizona California Colorado Idaho Montana Nevada New Mexico Oregon Utah Washington Wyoming Resource Library NEPA Database State Siting Process Transmission lines 200 kV or greater are required to undergo a two-part state siting and permitting process with the California Public Utility Commission (CPUC). One part of the process will analyze the need for the project and consists of obtaining a Certificate of Public Convenience and Necessity (CPCN) from the California Energy Commission (CEC). The other part of the process will analyze environmental and community impacts in the

347

Integrated Transmission and Distribution Control  

SciTech Connect (OSTI)

Distributed, generation, demand response, distributed storage, smart appliances, electric vehicles and renewable energy resources are expected to play a key part in the transformation of the American power system. Control, coordination and compensation of these smart grid assets are inherently interlinked. Advanced control strategies to warrant large-scale penetration of distributed smart grid assets do not currently exist. While many of the smart grid technologies proposed involve assets being deployed at the distribution level, most of the significant benefits accrue at the transmission level. The development of advanced smart grid simulation tools, such as GridLAB-D, has led to a dramatic improvement in the models of smart grid assets available for design and evaluation of smart grid technology. However, one of the main challenges to quantifying the benefits of smart grid assets at the transmission level is the lack of tools and framework for integrating transmission and distribution technologies into a single simulation environment. Furthermore, given the size and complexity of the distribution system, it is crucial to be able to represent the behavior of distributed smart grid assets using reduced-order controllable models and to analyze their impacts on the bulk power system in terms of stability and reliability. The objectives of the project were to: • Develop a simulation environment for integrating transmission and distribution control, • Construct reduced-order controllable models for smart grid assets at the distribution level, • Design and validate closed-loop control strategies for distributed smart grid assets, and • Demonstrate impact of integrating thousands of smart grid assets under closed-loop control demand response strategies on the transmission system. More specifically, GridLAB-D, a distribution system tool, and PowerWorld, a transmission planning tool, are integrated into a single simulation environment. The integrated environment allows the load flow interactions between the bulk power system and end-use loads to be explicitly modeled. Power system interactions are modeled down to time intervals as short as 1-second. Another practical issue is that the size and complexity of typical distribution systems makes direct integration with transmission models computationally intractable. Hence, the focus of the next main task is to develop reduced-order controllable models for some of the smart grid assets. In particular, HVAC units, which are a type of Thermostatically Controlled Loads (TCLs), are considered. The reduced-order modeling approach can be extended to other smart grid assets, like water heaters, PVs and PHEVs. Closed-loop control strategies are designed for a population of HVAC units under realistic conditions. The proposed load controller is fully responsive and achieves the control objective without sacrificing the end-use performance. Finally, using the T&D simulation platform, the benefits to the bulk power system are demonstrated by controlling smart grid assets under different demand response closed-loop control strategies.

Kalsi, Karanjit; Fuller, Jason C.; Tuffner, Francis K.; Lian, Jianming; Zhang, Wei; Marinovici, Laurentiu D.; Fisher, Andrew R.; Chassin, Forrest S.; Hauer, Matthew L.

2013-01-16T23:59:59.000Z

348

Bayesian Image Reconstruction for Transmission Tomography Using Deterministic Annealing  

E-Print Network [OSTI]

and non-medical applications, however, the measured projection data are photon limited and the imaging;1 INTRODUCTION Transmission tomography is perhaps most familiar in its medical guise as CT (computed tomogra- phy procedure. Because of the relatively high dose in conventional CT, the measured projection data contain

Rangarajan, Anand

349

The aim of this project is to develop an ultrasonic device for parametric imaging of standing trees. The device is designed to perform both transmission and reflection measurements that can be therefore used for quantitative  

E-Print Network [OSTI]

The aim of this project is to develop an ultrasonic device for parametric imaging of standing trees the velocity) and the attenuation of the ultrasonic waves. Tomograms were computed by fast algebraic algorithms the acceleration on circumferen- tial points (accelerometer) with a limited number of sensors. These methods give

Boyer, Edmond

350

Hybrid Transmission Corridor study  

SciTech Connect (OSTI)

Hybrid Transmission Corridors are areas where High Voltage Alternating Current (HVAC) transmission lines and High Voltage Direct Current (HVDC) transmission lines exist in close proximity of each other. Because of the acceptance of HVDC as a means of transporting electric power over long distances and the difficulties associated with obtaining new right-of-ways, HVDC lines may have to share the same transmission corridor with HVAC lines. The interactions between conductors energized with different types of voltages causes changes in the electrical stresses applied to the conductors and insulators. As a result, corona phenomena, field effects and insulation performance can be affected. This report presents the results of an investigation of the HVAC-HVDC interaction and its effect on corona and AC and DC electric field phenomena. The method of investigation was based on calculation methods developed at the EPRI High Voltage Transmission Research Center (HVTRC) and supported by the results of full and reduced-scale line tests. Also, a survey of existing hybrid corridors is given along with the results of measurements made at one of those corridors. A number of examples in which an existing AC corridor may be transformed into a hybrid corridor are discussed. The main result of the research is an analytical/empirical model for predicting the electrical/environmental performance of hybrid corridors, a definition of ACDC interaction and a set of criteria for specifying when the interaction becomes significant, and a set of design rules.

Clairmont, B.A.; Johnson, G.B.; Zaffanella, L.E. (General Electric Co., Lenox, MA (United States))

1992-06-01T23:59:59.000Z

351

Projectivities and Projective Embeddings  

Science Journals Connector (OSTI)

In this chapter, we aim to prove some of the main achievements in the theory of generalized polygons. First, we want to show what the little projective group and the groups of projectivities of some Moufang po...

Hendrik van Maldeghem

1998-01-01T23:59:59.000Z

352

Project Overview  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Questions Keeler-Pennwalt Wood Pole Removal Line Projects Line Rebuild, Relocation and Substation Projects Spacer Damper Replacement Program Wind Projects Project Overview BPA...

353

Project Year Project Title  

E-Print Network [OSTI]

operators, matrix indexing, vector computations, loops, functions, and plotting graphs, among others basic arithmetic operators, matrix indexing, and vector computations in MATLAB. After creatingProject Year 2011-2012 Project Title Online Tutorial for MATLAB Project Team Eileen Haase, Whiting

Gray, Jeffrey J.

354

Project Year Project Team  

E-Print Network [OSTI]

Project Year 2005 Project Team Krysia Hudson, Faculty, School of Nursing, Undergraduate Instruction for Educational Resources Project Title Enhanced Web-based Learning Environments for Beginning Nursing Students (e.g., demonstrations of procedures or tasks) into the WBL systems, it will be possible to increase

Gray, Jeffrey J.

355

Project Year Project Team  

E-Print Network [OSTI]

Project Year 2002 Project Team Faculty: Michael McCloskey, Cognitive Science/Neuroscience, Krieger of Arts & Sciences Project Title Cognitive Neuropsychology Audience The initial audience to access. The current procedure calls for individual students or researchers to contact the faculty member

Gray, Jeffrey J.

356

Project Year Project Title  

E-Print Network [OSTI]

Project Year 2011-2012 Project Title Using M-Health and GIS Technology in the Field to Improve into teams and having each team use a different m-health data collection tool (e.g., cellular phones, smart health patterns. The Tech Fellow, Jacqueline Ferguson, will assist in creating an m-health project

Gray, Jeffrey J.

357

Project Year Project Team  

E-Print Network [OSTI]

Project Year 2002 Project Team Faculty: Gregory Hager, Computer Science, Whiting School of Engineering Fellow: Alan Chen, Biomedical Engineering, Whiting School of Engineering Project Title Robotics is complicated, time-consuming, and costly, making a robot for an introductory-level class is not practical

Gray, Jeffrey J.

358

Project Proposal Project Logistics  

E-Print Network [OSTI]

Project Proposal · Project Logistics: ­ 2-3 person teams ­ Significant implementation, worth 55 and anticipated cost of copying to/from host memory. IV. Intellectual Challenges - Generally, what makes this computation worthy of a project? - Point to any difficulties you anticipate at present in achieving high

Hall, Mary W.

359

Record of Decision for the Modification and Construction of Transmission Lines for the U.S. 93 Hoover Dam Bypass Project (DOE/EIS-0352) (10/1/02)  

Broader source: Energy.gov (indexed) [DOE]

9 9 Federal Register / Vol. 67, No. 190 / Tuesday, October 1, 2002 / Notices ''Procedures for Public Participation in Power and Transmission Rate Adjustment,'' has been followed in connection with the proposed rate adjustment. More specifically, opportunities for public review and comment during a 90-day period on the proposed Rayburn power rate were announced by notice published in the Federal Register, May 21, 2002, 67 FR 35805. A Public Information Forum was scheduled to be held June 6, 2002, and a Public Comment Forum was scheduled to be held July 10, 2002, both in Tulsa, Oklahoma. Both forums were canceled as no one expressed an intent to participate. Written comments were due by August 19, 2002. Southwestern provided notice of the Federal Register,

360

transmission | OpenEI  

Open Energy Info (EERE)

transmission transmission Dataset Summary Description This dataset represents a historical repository of all the numerical data from the smartgrid.gov website condensed into spreadsheets to enable analysis of the data. Below are a couple of things worth noting: Source Smartgrid.gov Date Released March 04th, 2013 (9 months ago) Date Updated March 04th, 2013 (9 months ago) Keywords AMI costs distribution smart grid transmission Data application/vnd.openxmlformats-officedocument.spreadsheetml.sheet icon SmartGrid.gov Quarterly Data Summary 4Q12 (xlsx, 112.1 KiB) application/vnd.openxmlformats-officedocument.spreadsheetml.sheet icon SmartGrid.gov Quarterly Data Summary 3Q12 (xlsx, 107.9 KiB) application/vnd.openxmlformats-officedocument.spreadsheetml.sheet icon SmartGrid.gov Quarterly Data Summary 2Q12 (xlsx, 111.9 KiB)

Note: This page contains sample records for the topic "navajo transmission project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


361

NREL: Energy Analysis: Transmission Infrastructure  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Transmission Infrastructure Transmission Infrastructure Grid expansion and planning to allow large scale deployment of renewable generation Large scale deployment of renewable electricity generation will require additional transmission to connect renewable resources, which are wide-spread across the US, but regionally-constrained, to load centers. Long-term transmission planning, based on potential future growth in electric loads and generation resource expansion options, is critical to maintaining the necessary flexibility required for a reliable and robust transmission system. NREL's analyses support transmission infrastructure planning and expansion to enable large-scale deployment of renewable energy in the future. NREL's transmission infrastructure expansion and planning analyses show

362

Printed circuit dispersive transmission line  

DOE Patents [OSTI]

A printed circuit dispersive transmission line structure is disclosed comprising an insulator, a ground plane formed on one surface of the insulator, a first transmission line formed on a second surface of the insulator, and a second transmission line also formed on the second surface of the insulator and of longer length than the first transmission line and periodically intersecting the first transmission line. In a preferred embodiment, the transmission line structure exhibits highly dispersive characteristics by designing the length of one of the transmission line between two adjacent periodic intersections to be longer than the other. 5 figures.

Ikezi, H.; Lin-Liu, Y.R.; DeGrassie, J.S.

1991-08-27T23:59:59.000Z

363

Printed circuit dispersive transmission line  

DOE Patents [OSTI]

A printed circuit dispersive transmission line structure is disclosed comprising an insulator, a ground plane formed on one surface of the insulator, a first transmission line formed on a second surface of the insulator, and a second transmission line also formed on the second surface of the insulator and of longer length than the first transmission line and periodically intersecting the first transmission line. In a preferred embodiment, the transmission line structure exhibits highly dispersive characteristics by designing the length of one of the transmission line between two adjacent periodic intersections to be longer than the other.

Ikezi, Hiroyuki (Rancho Santa Fe, CA); Lin-Liu, Yuh-Ren (San Diego, CA); DeGrassie, John S. (Encinitas, CA)

1991-01-01T23:59:59.000Z

364

Bayesian Image Reconstruction for Transmission Tomography Using Mixture Model Priors and Deterministic Annealing  

E-Print Network [OSTI]

degradations in emission computed tomography (ECT) for both PET and SPECT. To improve quantitative accuracy transmission projection data. However, the transmission projection data is itself usually very noisy due to the necessities of a short-time acquisition and limited count rate . The low-count data makes the reconstruction

365

Transmission line capital costs  

SciTech Connect (OSTI)

The displacement or deferral of conventional AC transmission line installation is a key benefit associated with several technologies being developed with the support of the U.S. Department of Energy`s Office of Energy Management (OEM). Previous benefits assessments conducted within OEM have been based on significantly different assumptions for the average cost per mile of AC transmission line. In response to this uncertainty, an investigation of transmission line capital cost data was initiated. The objective of this study was to develop a database for preparing preliminary estimates of transmission line costs. An extensive search of potential data sources identified databases maintained by the Bonneville Power Administration (BPA) and the Western Area Power Administration (WAPA) as superior sources of transmission line cost data. The BPA and WAPA data were adjusted to a common basis and combined together. The composite database covers voltage levels from 13.8 to 765 W, with cost estimates for a given voltage level varying depending on conductor size, tower material type, tower frame type, and number of circuits. Reported transmission line costs vary significantly, even for a given voltage level. This can usually be explained by variation in the design factors noted above and variation in environmental and land (right-of-way) costs, which are extremely site-specific. Cost estimates prepared from the composite database were compared to cost data collected by the Federal Energy Regulatory Commission (FERC) for investor-owned utilities from across the United States. The comparison was hampered because the only design specifications included with the FERC data were voltage level and line length. Working within this limitation, the FERC data were not found to differ significantly from the composite database. Therefore, the composite database was judged to be a reasonable proxy for estimating national average costs.

Hughes, K.R.; Brown, D.R.

1995-05-01T23:59:59.000Z

366

Electric Transmission System Workshop  

Broader source: Energy.gov (indexed) [DOE]

Lauren Azar Lauren Azar Senior Advisor to Secretary Chu November 2, 2012 Electric Transmission System Workshop We all have "visions," in one form or another: * Corporations call them strategic plans * RTOs ... transmission expansion plans or Order 1000 plans * State PUCs ... integrated resource plans * Employees ... career goals Visions for the Future Artist: Paolo Frattesi Artist: Paolo Frattesi Uncertainty = changing industry Changes in technology, threats and policies Can we make decisions in the face of change? .......How can we not? Can we agree on several key design attributes for the future grid? Taking Action in the Face of Uncertainty Step 1: Establish common ground on key design attributes GTT's Proposed Key Design Attributes:

367

The Wind Project Development Process  

Wind Powering America (EERE)

Wind Project Wind Project Development Process Developed for the National Renewable Energy Laboratory by Dale Osborn Distributed Generation Systems, Inc. September 1998 The Wind Project Development Process Site Selection Land Agreements Wind Assessment Environmental Review Economic Modeling Interconnection Studies Financing Permitting Sales Agreements Turbine Procurement Construction Contracting Operations & Maintenance Site Selection Evidence of Significant Wind Preferably Privately Owned Remote Land Proximity to Transmission Lines Reasonable Road Access Few Environmental Concerns Receptive Community Land Agreements Term: Expected Life of the Turbine Assignable Indemnification Rights Compensation: Percentage of Revenues Reclamation Provision Wind Rights, Ingress/Egress Rights, Transmission Rights

368

Category:Smart Grid Investment Grant Projects | Open Energy Information  

Open Energy Info (EERE)

Investment Grant Projects Investment Grant Projects Pages in category "Smart Grid Investment Grant Projects" The following 98 pages are in this category, out of 98 total. A ALLETE Inc., d/b/a Minnesota Power Smart Grid Project American Transmission Company LLC II Smart Grid Project American Transmission Company LLC Smart Grid Project Atlantic City Electric Company Smart Grid Project Avista Utilities Smart Grid Project B Baltimore Gas and Electric Company Smart Grid Project Black Hills Power, Inc. Smart Grid Project Black Hills/Colorado Electric Utility Co. Smart Grid Project Burbank Water and Power Smart Grid Project C CenterPoint Energy Smart Grid Project Central Lincoln People's Utility District Smart Grid Project Central Maine Power Company Smart Grid Project Cheyenne Light, Fuel and Power Company Smart Grid Project

369

Continuously variable transmission  

SciTech Connect (OSTI)

This patent describes a power transmission apparatus. It comprises: a body, a pinion gear, a cam means, first and second gear rack pairs, preventing means;l first and second rack support means, a rotor mounted for rotation about a rotor axis, the rotor having rotor engaging means for engaging the rack support means so as to transmit power therebetween.

Irvin, P.J.E.

1992-07-14T23:59:59.000Z

370

Autonomous data transmission apparatus  

DOE Patents [OSTI]

A autonomous borehole data transmission apparatus for transmitting measurement data from measuring instruments at the downhole end of a drill string by generating pressure pulses utilizing a transducer longitudinally responsive to magnetic field pulses caused by electrical pulses corresponding to the measured downhole parameters.

Kotlyar, Oleg M. (4675 W. 3825 S, Salt Lake City, UT 84120)

1997-01-01T23:59:59.000Z

371

Borehole data transmission apparatus  

DOE Patents [OSTI]

A borehole data transmission apparatus is described whereby a centrifugal pump impeller(s) is used to provide a turbine stage having substantial pressure characteristics in response to changing rotational speed of a shaft for the pressure pulsing of data from the borehole through the drilling mud to the surface of the earth.

Kotlyar, O.M.

1993-03-23T23:59:59.000Z

372

Project Project HQ City HQ State ARRA Funding Total Value Additional  

Open Energy Info (EERE)

Carolinas LLC Smart Grid Project Duke Energy Carolinas Carolinas LLC Smart Grid Project Duke Energy Carolinas LLC Smart Grid Project Charlotte North Carolina Entergy Services Inc Smart Grid Project Entergy Services Inc Smart Grid Project New Orleans Louisiana ISO New England Incorporated Smart Grid Project ISO New England Incorporated Smart Grid Project Holyoke Massachusetts Connecticut Maine New Hampshire Rhode Island Vermont Midwest Energy Inc Smart Grid Project Midwest Energy Inc Smart Grid Project Hays Kansas Midwest Independent Transmission System Operator Smart Grid Project Midwest Independent Transmission System Operator Smart Grid Project Carmel Indiana Iowa Illinois Michigan Minnesota Missouri Montana North Dakota Ohio Pennsylvania South Dakota Wisconsin New York Independent System Operator Inc Smart Grid Project New York

373

Amendment of Presidential Permit (PP-68) San Diego Gas & Electric Company for Interconnection of Otay Mesa Generating Project to Miguel-Tijuana 230 kV Transmission Line San Diego, California  

Broader source: Energy.gov (indexed) [DOE]

Section Page S:\COMM\NEPA\TODO \EA1383\EATOC1 -R.DOC 4/1/02 -i- 1.0 INTRODUCTION 1-1 1.1 BACKGROUND 1-1 1.2 SCOPE OF PROJECT 1-2 1.3 PURPOSE AND NEED 1-3 1.4 AGENCY ACTIONS 1-3 1.4.1 Federal 1-3 1.4.1.1 U.S. Department of Energy 1-3 1.4.1.2 U.S. Fish and Wildlife Service 1-4 1.4.2 Other Agenc y Actions 1-4 1.4.2.1 California Energy Commission 1-4 1.4.2.2 California Department of Fish and Game 1-4 1.4.2.3 State Historic Preservation Office 1-5 1.4.2.4 San Diego County 1-5 2.0 PROPOSED ACTION AND ALTERNATIVES 2-1 2.1 NO ACTION ALTERNATIVE 2-1 2.2 PROPOSED ACTION 2-1 2.2.1 Proposed Amendment to Presidential Permit (PP-68) 2-2 2.2.2 Description of Proposed Project Components and Activities 2-3 2.2.2.1 Otay Mesa 230 kV Switchyard 2-3

374

Regulations for Electric Transmission and Fuel Gas Transmission Lines Ten  

Broader source: Energy.gov (indexed) [DOE]

Electric Transmission and Fuel Gas Transmission Electric Transmission and Fuel Gas Transmission Lines Ten or More Miles Long (New York) Regulations for Electric Transmission and Fuel Gas Transmission Lines Ten or More Miles Long (New York) < Back Eligibility Commercial Fuel Distributor Investor-Owned Utility Municipal/Public Utility Rural Electric Cooperative Tribal Government Utility Savings Category Buying & Making Electricity Water Home Weatherization Solar Wind Program Info State New York Program Type Siting and Permitting Provider New York State Public Service Commission Any person who wishes to construct an electric or gas transmission line that is more than ten miles long must file documents describing the construction plans and potential land use and environmental impacts of the proposed transmission line. The regulations describe application and review

375

South Mississippi Electric Power Association Smart Grid Project (Mississippi)  

Broader source: Energy.gov [DOE]

South Mississippi Electric Power Association’s (SMEPA) smart grid project involves the deployment of advanced metering infrastructure (AMI) and covers the Generation and Transmission (G&T)...

376

BPA and partners surmount unique obstacles on Grand Coulee project  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

credits the project's success to relying on the expert support of the team, including BPA substation engineer James Kelly, transmission designer Len Custer, tower designers...

377

EIS-0417: South Mountain Freeway Project, Arizona | Department...  

Energy Savers [EERE]

Area Power Administration, a cooperating agency, would move or reconfigure several transmission line towers. Additional information is available on the ADOT project website...

378

Request for Information on Permitting of Transmission Lines: Federal  

Broader source: Energy.gov (indexed) [DOE]

Request for Information on Permitting of Transmission Lines: Request for Information on Permitting of Transmission Lines: Federal Register Notice Volume 77, No. 38 - Feb. 27, 2012 Request for Information on Permitting of Transmission Lines: Federal Register Notice Volume 77, No. 38 - Feb. 27, 2012 The Department of Energy's Office of Electricity Delivery and Energy Reliability requested information on questions related to permitting of transmission lines. Infrastructure projects - such as high voltage, long distance, electric transmission facilities - often involve multiple Federal, State, local and Tribal authorizations and are subject to a wide array of processes and procedural requirements in order to obtain all necessary permits and other authorizations. Delays in securing required statutory reviews, permits, and consultations can threaten the completion

379

Transmission/Resource Library/Resources | Open Energy Information  

Open Energy Info (EERE)

source source History View New Pages Recent Changes All Special Pages Semantic Search/Querying Get Involved Help Apps Datasets Community Login | Sign Up Search Page Edit History Facebook icon Twitter icon » Transmission/Resource Library/Resources < Transmission‎ | Resource Library(Redirected from Transmission/Resource Library/Public Involvement) Jump to: navigation, search ResourceLibraryHeader.png Public Involvement Resources GIS Tools and Maps Environmental Resources and Mitigation NEPA MOUs General Transmission Documents Transmission Dashboard Permitting Atlas Compare States Arizona California Colorado Idaho Montana Nevada New Mexico Oregon Utah Washington Wyoming Resource Library NEPA Database Public Participation for Interstate Transmission Public participation is a requirement of any project that must comply with

380

Notice of Technical Workshop in Support of 2009 Electric Transmission  

Broader source: Energy.gov (indexed) [DOE]

Notice of Technical Workshop in Support of 2009 Electric Notice of Technical Workshop in Support of 2009 Electric Transmission Congestion Study: Federal Register Volume 74, No. 32 - Feb. 19, 2009 Notice of Technical Workshop in Support of 2009 Electric Transmission Congestion Study: Federal Register Volume 74, No. 32 - Feb. 19, 2009 The Department of Energy's (DOE) Office of Electricity Delivery and Energy Reliability (OE) conducted a Technical Workshop to receive input from subject matter experts on the historical transmission data in the Western and Eastern Interconnections and on studies of future transmission projections within the two Interconnections. Technical Workshop in Support of 2009 Electric Transmission Congestion Study - Federal Register Vol 74 No. 32 - Feb. 19, 2009.pdf More Documents & Publications

Note: This page contains sample records for the topic "navajo transmission project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


381

Notice of Technical Workshop in Support of 2009 Electric Transmission  

Broader source: Energy.gov (indexed) [DOE]

Notice of Technical Workshop in Support of 2009 Electric Notice of Technical Workshop in Support of 2009 Electric Transmission Congestion Study: Federal Register Volume 74, No. 32 - Feb. 19, 2009 Notice of Technical Workshop in Support of 2009 Electric Transmission Congestion Study: Federal Register Volume 74, No. 32 - Feb. 19, 2009 The Department of Energy's (DOE) Office of Electricity Delivery and Energy Reliability (OE) conducted a Technical Workshop to receive input from subject matter experts on the historical transmission data in the Western and Eastern Interconnections and on studies of future transmission projections within the two Interconnections. Technical Workshop in Support of 2009 Electric Transmission Congestion Study - Federal Register Vol 74 No. 32 - Feb. 19, 2009.pdf More Documents & Publications

382

Request for Information on Permitting of Transmission Lines: Federal  

Broader source: Energy.gov (indexed) [DOE]

Request for Information on Permitting of Transmission Lines: Request for Information on Permitting of Transmission Lines: Federal Register Notice Volume 77, No. 38 - Feb. 27, 2012 Request for Information on Permitting of Transmission Lines: Federal Register Notice Volume 77, No. 38 - Feb. 27, 2012 The Department of Energy's Office of Electricity Delivery and Energy Reliability requested information on questions related to permitting of transmission lines. Infrastructure projects - such as high voltage, long distance, electric transmission facilities - often involve multiple Federal, State, local and Tribal authorizations and are subject to a wide array of processes and procedural requirements in order to obtain all necessary permits and other authorizations. Delays in securing required statutory reviews, permits, and consultations can threaten the completion

383

Transmission Siting_071508.indd  

Broader source: Energy.gov (indexed) [DOE]

Coordinating Interstate Electric Coordinating Interstate Electric Transmission Siting: An Introduction to the Debate The National Council on Electricity Policy 2 DISCLAIMER: The National Council on Electricity Policy is funded by the U.S. Department of Energy and the U.S. Environmental Protection Agency. The views and opinions expressed herein are strictly those of the authors and may not necessarily agree with the positions of the National Council on Electricity Policy, its committ ee members or the organizations they represent, the National Council funders, or those who commented on the paper during its draft ing. ACKNOWLEDGMENTS Coordinating Interstate Electric Transmission Siting: An Introduction to the Debate was prepared with the fi nancial assistance of a grant from the U.S. Department of Energy (DOE) Offi ce of Electricity Delivery

384

Drill string transmission line  

DOE Patents [OSTI]

A transmission line assembly for transmitting information along a downhole tool comprising a pin end, a box end, and a central bore traveling between the pin end and the box end, is disclosed in one embodiment of the invention as including a protective conduit. A transmission line is routed through the protective conduit. The protective conduit is routed through the central bore and the ends of the protective conduit are routed through channels formed in the pin end and box end of the downhole tool. The protective conduit is elastically forced into a spiral or other non-linear path along the interior surface of the central bore by compressing the protective conduit to a length within the downhole tool shorter than the protective conduit.

Hall, David R. (Provo, UT); Hall, Jr., H. Tracy (Provo, UT); Pixton, David S. (Lehi, UT); Bradford, Kline (Orem, UT); Fox, Joe (Spanish Fork, UT)

2006-03-28T23:59:59.000Z

385

Energia Sierra Juarez U.S. Transmission Line Draft EIS  

Broader source: Energy.gov (indexed) [DOE]

Energia Sierra Juarez U.S. Transmission Line Project Energia Sierra Juarez U.S. Transmission Line Project Draft Environmental Impact Statement Summary August 2010 U.S. Department of Energy Office of Electricity Delivery and Energy Reliability Washington, DC 20585 Cooperating Agency - County of San Diego San Diego, CA DOE/EIS-0414 Department of Energy Washington, DC 20585 August 2010 Dear Sir/Madam: Enclosed for your review and comment is the Energia Sierra Juarez U.S. Transmission Line Project Draft Environmental Impact Statement (DOE/EIS-0414), prepared by the Department of Energy (DOE) pursuant to the National Environmental Policy Act of 1969 (NEPA) and its implementing regulations. The County of San Diego, California, is a cooperating agency in the preparation of this Draft EIS.

386

Patterns of Transmission Investment  

E-Print Network [OSTI]

long term performance contracts with a developer of an HVDC transmission link to expand “interconnection” capacity between TSOs with no or limited interconnections and with large sustained differences in prices. Merchant investments supported... truly separate AC networks. For example, by building HVDC inter-connectors between two separate networks, opportunities to increase trades of power from high price to low priced areas can be exploited. The HVDC link between the England and France...

Joskow, Paul

2006-03-14T23:59:59.000Z

387

Notice of Intent to Prepare an Environmental Impact Statement for the Granby Pumping Plant-Windy Gap Transmission Line Rebuild Project, Grand County, CO (DOE/EIS-0400)(08/10/07)  

Broader source: Energy.gov (indexed) [DOE]

040 Federal Register 040 Federal Register / Vol. 72, No. 154 / Friday, August 10, 2007 / Notices g. Filed Pursuant to: 18 CFR 4.200. h. Applicant Contact: David Lovely, Hydro Supervisor, Madison Paper Industries, P.O. Box 129, 3 Main Street, Madison, Maine 04950-0129, (207) 696- 1225. i. FERC Contact: Robert Bell, (202) 502-6062. j. Deadline for filing comments, motions to intervene and protest: August 20, 2007. Please include the project number (P- 2365-040) on any comments or motions filed. All documents (original and seven copies) should be filed with: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. Comments, protests, and interventions may be filed electronically via the Internet in lieu of paper, see 18 CFR

388

Project title: Cottonwood-Roseville Optical Groundwire Project  

Broader source: Energy.gov (indexed) [DOE]

Cottonwood-Roseville Optical Groundwire Project Cottonwood-Roseville Optical Groundwire Project Requested By: Joe Oloriz Mail Code: N5706 Phone: 916-353-4773 Date Submitted: 7-3-13 Date Required: 7-8-13 Description of the Project: Purpose and Need The Western Area Power Administration (Western), Sierra Nevada Region (SNR), is responsible for the operation and maintenance (O&M) of federally owned and operated transmission lines, switchyards, and facilities throughout California. Western must comply with the National Electric Safety Code, Western States Coordinating Council (WECC), and internal directives for protecting human safety, the physical environment, and maintaining the reliable operation of the transmission system. The process of marketing and delivering electric power through transmission facilities requires a great

389

Transmission Line Circuit Alexander Glasser  

E-Print Network [OSTI]

Chaos in a Transmission Line Circuit Alexander Glasser Marshal Miller With... Prof. Edward Ott Prof times become shorter, circuit connections behave more and more like transmission lines. Theoretical(t) - Transmission Line (Zo, T) #12;5 Cf/Cr 1000 Vf Capacitance Voltage Cf Cr Model for Nonlinear Capacitor

Anlage, Steven

390

NREL: Transmission Grid Integration - Transmission Planning and Analysis  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Transmission Planning and Analysis Transmission Planning and Analysis Thumbnail of map the United States that shows wind resources and transmission lines. Enlarge image This map shows the location of wind resources and transmission lines in the United States. See a larger image or state maps. NREL researchers are engaged in transmission planning and analysis to strengthen the electric power system through the integration of solar and wind power. As demand for electricity increases, electric power system operators must plan for and construct new generation and transmission lines. However, variable generation such as solar and wind power plants are often located far from the loads they serve. They depend on transmission lines to transport the electricity they produce to load centers. NREL is working with industry and utilities to address issues related to

391

Transmission/Photo Gallery | Open Energy Information  

Open Energy Info (EERE)

Colorado transmission 2.jpg Bird diverters.jpg Transmission insulators.jpg Retrieved from "http:en.openei.orgwindex.php?titleTransmissionPhotoGallery&oldid687595...

392

127 Natural Gas Transmission and Distribution Module  

E-Print Network [OSTI]

and border prices, end-use prices, and flows of natural gas through a regional interstate representative pipeline network, for both a peak (December through March) and off-peak period during each projection year. These are derived by solving for the market equilibrium across the three main components of the natural gas market: the supply component, the demand component, and the transmission and distribution network that links them. Natural gas flow patterns are a function of the pattern in the previous year, coupled with the relative prices of the supply options available to bring gas to market centers within each of the NGTDM regions (Figure 9). The major assumptions used within the NGTDM are grouped into four general categories. They relate to (1) structural components of the model, (2) capacity expansion and pricing of transmission and distribution services, (3) Arctic pipelines, and (4) imports and exports. A complete listing of NGTDM assumptions and in-depth

Key Assumptions

393

Project Year Project Team  

E-Print Network [OSTI]

; Ian Sims, Student, Electrical and Computer Engineering, Whiting School of Engineering Project Title and Jazz Theory/Keyboard I & II. Technologies Used Digital Audio, Digital Video, Graphic Design, HTML

Gray, Jeffrey J.

394

Electric Transmission Line Siting Compact  

Broader source: Energy.gov (indexed) [DOE]

Electric Transmission Line Siting Compact Electric Transmission Line Siting Compact 1 ______________________________________________________________________________ 2 ARTICLE I 3 PURPOSE 4 5 Siting electric transmission lines across state borders and federal lands is an issue for states, the 6 federal government, transmission utilities, consumers, environmentalists, and other stakeholders. 7 The current, multi-year application review process by separate and equal jurisdictions constitutes 8 a sometimes inefficient and redundant process for transmission companies and complicates the 9 efforts of state and federal policy-makers and other stakeholders to develop more robust 10 economic opportunities, increase grid reliability and security, and ensure the consumers have the 11 lowest cost electricity possible. 12

395

Transmission Workshop | Department of Energy  

Broader source: Energy.gov (indexed) [DOE]

DOE Grid Tech Team » Activities/Outreach » GTT DOE Grid Tech Team » Activities/Outreach » GTT Activities » Transmission Workshop Transmission Workshop Transmission Workshop GTT Transmission Workshop - November 1-2, 2012 On November 1-2, 2012, the GTT presented a workshop on grid integration on the transmission system at the DoubleTree Crystal City near Washington, DC. A draft of the DOE Action Plan Addressing the Electricity Transmission System was discussed during the workshop, which addressed the challenges and opportunities presented by the integration of 21st century energy technologies into the electricity transmission system. Parallel sessions addressed the challenges and opportunities of modernizing the grid and drilled down into key technology areas associated with each of these: System visibility: what advances are needed to "see" the state of

396

Terahertz Quantum-Cascade Transmission-Line Metamaterials  

E-Print Network [OSTI]

Terahertz Transmission-Line Metamaterials . . . . . . .CRLH Transmission Lines . . . . . . . . . . . . . . . .Terahertz CRLH Transmission-Line Metamaterials . . . . . . .

Tavallaee, Amir Ali

2012-01-01T23:59:59.000Z

397

EIS-0421: Big Eddy-Knight Transmission Line | Department of Energy  

Broader source: Energy.gov (indexed) [DOE]

21: Big Eddy-Knight Transmission Line 21: Big Eddy-Knight Transmission Line EIS-0421: Big Eddy-Knight Transmission Line Overview BPA is proposing to build a new 500 kilovolt (kV) transmission line in Wasco County, Oregon and Klickitat County, Washington and a new substation in Klickitat County. The new BPA transmission line would extend generally northeast from BPA's existing Big Eddy Substation in The Dalles, Oregon, to a new substation (Knight Substation) proposed to be connected to an existing BPA line about 4 miles northwest of Goldendale, Washington. The proposed Big Eddy Knight Transmission Project is needed to increase transmission capacity to respond to requests for transmission service in this area. Public Comment Opportunities No public comment opportunities available at this time.

398

Northern Wind Project Draft Environmental Assessment Roberts...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Area Power Administration (Western) Forman-Summit 115 kilovolt (kV) transmission line 7.4 miles north of the Summit Substation. The Project is a federal action under the...

399

Abstract --Under a context of transmission open access, a methodology to define a common transmission trunk system  

E-Print Network [OSTI]

Terms--Transmission systems, Transmission pricing, Cooperative games, Shapley value, Transmission open

Catholic University of Chile (Universidad Católica de Chile)

400

The Cost of Transmission for Wind Energy: A Review of Transmission Planning Studies  

E-Print Network [OSTI]

Equipment Transmission Lines 765 kV (no description) 500Montana-Alberta Tie 230 kV Transmission Line: TransmissionMontana-Alberta Tie 230 kV Transmission Line: Transmission

Mills, Andrew D.

2009-01-01T23:59:59.000Z

Note: This page contains sample records for the topic "navajo transmission project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


401

Project Fact Sheet Project Brief  

E-Print Network [OSTI]

Project Fact Sheet Project Brief: Construction Project Team: Project Facts & Figures: Budget: £1.1M Funding Source: Departmental Construction Project Programme: Start on Site: November 2010 End Date : March 2011 Occupation Date: March 2011 For further information contact Project Manager as listed above

402

Project Fact Sheet Project Update  

E-Print Network [OSTI]

Project Fact Sheet Project Update: Project Brief: The works cover the refurbishment of floors 4, 5 operating theatre. The Bionanotechnology Centre is one of the projects funded from the UK Government's £20.imperial.ac.uk/biomedeng Construction Project Team: Project Facts & Figures: Budget: £13,095,963 Funding Source: SRIF II and Capital

403

Project Fact Sheet Project Brief  

E-Print Network [OSTI]

Project Fact Sheet Project Brief: This project refurbished half of the 5th and 7th floors on the Faculty of Medicine, please visit: http://www1.imperial.ac.uk/medicine/ Construction Project Team: Project Facts & Figures: Budget: £3,500,000 Funding Source: SRIF III Construction Project Programme: Start

404

National Electric Transmission Congestion Study: Preliminary...  

Broader source: Energy.gov (indexed) [DOE]

National Electric Transmission Congestion Study: Preliminary Findings National Electric Transmission Congestion Study: Preliminary Findings The Department hosted three webinars in...

405

Hydrogen Delivery Technologies and Systems - Pipeline Transmission...  

Broader source: Energy.gov (indexed) [DOE]

Hydrogen Delivery Technologies and Systems - Pipeline Transmission of Hydrogen Hydrogen Delivery Technologies and Systems - Pipeline Transmission of Hydrogen Hydrogen Delivery...

406

Dynamic Transmission Electron Microscopy  

SciTech Connect (OSTI)

Dynamic transmission electron microscopy (DTEM) combines the benefits of high spatial resolution electron microscopy with the high temporal resolution of ultrafast lasers. The incorporation of these two components into a single instrument provides a perfect platform for in situ observations of material processes. However, previous DTEM applications have focused on observing structural changes occurring in samples exposed to high vacuum. Therefore, in order to expand the pump-probe experimental regime to more natural environmental conditions, in situ gas and liquid chambers must be coupled with Dynamic TEM. This chapter describes the current and future applications of in situ liquid DTEM to permit time-resolved atomic scale observations in an aqueous environment, Although this chapter focuses mostly on in situ liquid imaging, the same research potential exists for in situ gas experiments and the successful integration of these techniques promises new insights for understanding nanoparticle, catalyst and biological protein dynamics with unprecedented spatiotemporal resolution.

Evans, James E.; Jungjohann, K. L.; Browning, Nigel D.

2012-10-12T23:59:59.000Z

407

EA-1693: Transmission Services Facility, Clark County, Washington |  

Broader source: Energy.gov (indexed) [DOE]

3: Transmission Services Facility, Clark County, Washington 3: Transmission Services Facility, Clark County, Washington EA-1693: Transmission Services Facility, Clark County, Washington Summary DOE will prepare an EA to evaluate the potential environmental impacts from the proposed three-to-five story office building that would be constructed to meet the Leadership in Energy and Environmental Design (LEED) Gold standard in energy efficiency and sustainability, near Bonneville Power Administration's (BPA) existing Dittmer Building. BPA website: http://efw.bpa.gov/environmental_services/Document_Library/TSF_Project/ For more information, contact: Stephanie Breeden Environmental Project Manager Bonneville Power Administration - KEC-4 P.O. Box 3621 Portland, Oregon, 97208-3621 Direct telephone number 503-230-5192 Toll-free telephone number 1-800-282-3713

408

Transmission/Permitting Atlas/State Data | Open Energy Information  

Open Energy Info (EERE)

Transmission/Permitting Atlas/State Data Transmission/Permitting Atlas/State Data < Transmission‎ | Permitting Atlas Jump to: navigation, search PermittingAtlasHeader.png Roadmap Compare States General Transmission Dashboard Permitting Atlas Compare States Arizona California Colorado Idaho Montana Nevada New Mexico Oregon Utah Washington Wyoming Resource Library NEPA Database State State Siting Act State Preemptive Authority Siting/Permitting Entities Permit Processing Timeframe Arizona None If TLSC finds compliance with local land use unreasonable or unfeasible, then the TLSC may grant a certificate Arizona Corporation Commission (ACC); Transmission Line Siting Committee (TLSC) 210-240 Days California Public Utilities Code Section 1001 Local jurisdictions are preempted from regulating electric power line projects California Public Utilities Commission (CPUC) 18 months

409

Project Year Project Team  

E-Print Network [OSTI]

An Engineer's Guide to the Structures of Baltimore Audience Students from the Krieger School of Arts City, interfaced through a course website, the team will integrate descriptions of structural behavior format. Technologies Used HTML/Web Design, MySQL Project Abstract Structural analysis is typically taught

Gray, Jeffrey J.

410

Project Year Project Team  

E-Print Network [OSTI]

information systems (GIS) tools to design maps that integrate data for visualizing geographic concepts School of Engineering Project Title GIS & Introductory Geography Audience Undergraduate students on how to use the Internet for geographic research, and an interactive introduction to GIS through online

Gray, Jeffrey J.

411

Project Management Project Managment  

E-Print Network [OSTI]

­ Inspired by agile methods #12;Background · Large-scale software development & IT projects, plagued relations #12;One Agile Approach to Scheduling · The creative nature of game development resist heavy up Problems ­incompatible platforms, 3rd party etc. #12;Is Games Development Similar? · Yes & No

Stephenson, Ben

412

Tropical Environments, Human Activities, and the Transmission of Infectious Diseases  

E-Print Network [OSTI]

of water sources. The transmission of cholera, a water-borne disease, is related to sanitation practices decades as a consequence of large-scale agricultural development projects that have shifted the nature and quantity of water sources and potential mosquito breeding sites. Dracunculiasis is transmitted by a small

Gottgens, Hans

413

MHK Technologies/Wave Energy Seawater Transmission WEST | Open Energy  

Open Energy Info (EERE)

Wave Energy Seawater Transmission WEST Wave Energy Seawater Transmission WEST < MHK Technologies Jump to: navigation, search << Return to the MHK database homepage Wave Energy Seawater Transmission WEST.jpg Technology Profile Primary Organization Atmocean Inc Project(s) where this technology is utilized *MHK Projects/WEST Testing Technology Resource Click here Wave Technology Type Click here Point Absorber Technology Readiness Level Click here TRL 1-3: Discovery / Concept Definition / Early Stage Development & Design & Engineering Technology Description Atmocean WEST efficiently captures wave energy by deploying many inexpensive devices across large ocean regions. By using hydraulic transmission, WEST avoids the high cost of seafloor power lines, generating electricity onshore to achieve higher reliability at lower cost. When WEST is combined with Bright Energy Storage Technologies seafloor compressed air energy storage (CAES) system, the two enable base load renewable power (eliminating the need for backup fossil-fuel power) at a projected levelized cost of electricity (LCOE) of $.08/kWh to $.12/kWh.

414

AGENDA: PETROLEUM PRODUCT TRANSMISSION & DISTRIBUTION  

Broader source: Energy.gov [DOE]

The agenda for the Quadrennial Energy Review (QER) public stakeholder meeting in New Orleans on petroleum product transmission, distribution, and storage.

415

Transmission Reliability | Department of Energy  

Energy Savers [EERE]

design, long-term supply and transmission investment, renewable integration, demand response, and environmental impacts. Researchers use models and simulations to assess how...

416

Chapter 4 Transmission Adequacy | Department of Energy  

Broader source: Energy.gov (indexed) [DOE]

Chapter 4 Transmission Adequacy Chapter 4 Transmission Adequacy Chapter 4 Transmission Adequacy Transmission lines are the critical link between the point of electricity generation and consumers. The U.S. transmission grid infrastructure is owned and operated by approximately 3,000 distribution utilities and 500 transmission owners. This structure presents a distinct set of challenges in transmission planning, siting, cost allocation, grid operations and management, technological innovation, financing and construction. The development and deployment of a national strategy on transmission that meets the needs of all parties is extremely complex; however, a solution is desperately needed. Chapter 4 Transmission Adequacy More Documents & Publications Draft Chapter 4: Transmission Adequacy

417

Project Accounts  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

» Project Accounts » Project Accounts Project Accounts Overview Project accounts are designed to facilitate collaborative computing by allowing multiple users to use the same account. All actions performed by the project account are traceable back to the individual who used the project account to perform those actions via gsisshd accounting logs. Requesting a Project Account PI's, PI proxies and project managers are allowed to request a project account. In NIM do "Actions->Request a Project Account" and fill in the form. Select the repository that the Project Account is to use from the drop-down menu, "Sponsoring Repository". Enter the name you want for the account (8 characters maximum) and a description of what you will use the account for and then click on the "Request Project Account" button. You

418

THURSDAY: Deputy Secretary of Energy to Visit Western Area Power Administration Transmission Substation  

Broader source: Energy.gov [DOE]

Deputy Secretary of Energy Elizabeth Sherwood-Randall will visit the Western Area Power Administration for a ceremony at the Electrical District No. 5 Substation to view progress on the Electrical District 5-to-Palo Verde transmission project.

419

Project Fact Sheet Project Update  

E-Print Network [OSTI]

Project Fact Sheet Project Update: Project Brief: A state of the art facility, at Hammersmith information visit the Faculty of Medicine web pages http://www1.imperial.ac.uk/medicine/ Construction Project Team: Project Facts & Figures: Budget: £60 000 000 Funding Source: SRIF II (Imperial College), GSK, MRC

420

Project Fact Sheet Project Update  

E-Print Network [OSTI]

Project Fact Sheet Project Update: Project Brief: The refurbishment of the instrumentation equipment. This project encompasses refurbishment work on over 1,150m2 of laboratory space across four, the completed project will allow researchers to expand their work in satellite instrumentation, the fabrication

Note: This page contains sample records for the topic "navajo transmission project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


421

Project Fact Sheet Project Brief  

E-Print Network [OSTI]

Project Fact Sheet Project Brief: In the first phase of the Union Building re.union.ic.ac.uk/marketing/building Construction Project Team: Project Facts & Figures: Budget: £1,400,000 Funding Source: Capital Plan and Imperial College Union reserves Construction Project Programme: Start on Site: August 2006 End Date: March

422

Description of vibration transmission through isolators in terms of interface mobilities  

E-Print Network [OSTI]

Description of vibration transmission through isolators in terms of interface mobilities For the description of vibration transmission from a source to a receiver structure, the interface mobility method on the structural parameters. Project tasks The first task is a literature study for the description of vibration

Berlin,Technische Universität

423

Volume Project  

E-Print Network [OSTI]

Math 13900. Volume Project. For the following project, you may use any materials. This must be your own original creation. Construct a right pyramid with a base ...

rroames

2010-01-12T23:59:59.000Z

424

HVDC power transmission technology assessment  

SciTech Connect (OSTI)

The purpose of this study was to develop an assessment of the national utility system`s needs for electric transmission during the period 1995-2020 that could be met by future reduced-cost HVDC systems. The assessment was to include an economic evaluation of HVDC as a means for meeting those needs as well as a comparison with competing technologies such as ac transmission with and without Flexible AC Transmission System (FACTS) controllers. The role of force commutated dc converters was to be assumed where appropriate. The assessment begins by identifying the general needs for transmission in the U.S. in the context of a future deregulated power industry. The possible roles for direct current transmission are then postulated in terms of representative scenarios. A few of the scenarios are illustrated with the help of actual U.S. system examples. non-traditional applications as well as traditional applications such as long lines and asynchronous interconnections are discussed. The classical ``break-even distance`` concept for comparing HVDC and ac lines is used to assess the selected scenarios. The impact of reduced-cost converters is reflected in terms of the break-even distance. This report presents a comprehensive review of the functional benefits of HVDC transmission and updated cost data for both ac and dc system components. It also provides some provocative thoughts on how direct current transmission might be applied to better utilize and expand our nation`s increasingly stressed transmission assets.

Hauth, R.L.; Tatro, P.J.; Railing, B.D. [New England Power Service Co., Westborough, MA (United States); Johnson, B.K.; Stewart, J.R. [Power Technologies, Inc., Schenectady, NY (United States); Fink, J.L.

1997-04-01T23:59:59.000Z

425

Hydrogen Transmission and Distribution Workshop  

Broader source: Energy.gov [DOE]

Proceedings from the Hydrogen Transmission and Distribution Workshop held February 25-26, 2014, in Golden, Colorado. The objective was to discuss and share information on the research, development, and demonstration needs and challenges for low-cost, effective hydrogen transmission and distribution from centralized production facilities to the point of use.

426

Direct current power transmission systems  

SciTech Connect (OSTI)

This book represents text on HVDC transmission available. It deals with the various aspects of the state of the art in HVDC transmission technology. This book presents many aspects of interactions of AC/DC systems. Modeling and analysis of DC systems are also discussed in detail.

Padiyar, K.R.

1991-01-01T23:59:59.000Z

427

Transmission Reliability | Department of Energy  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Transmission Reliability Transmission Reliability Transmission Reliability Modernizing America's electricity infrastructure is one of the U.S. Department of Energy's top priorities. The DOE Strategic Plan states that today's electric grid needs to be more efficient, reliable, and secure. A modern, smarter electric grid may save consumers money, help our economy run more efficiently, allow rapid growth in renewable energy sources, and enhance energy reliability. The Department's research into a variety of tools that will improve advanced system monitoring, visualization, control, operations, and market structure will ultimately modernize the electricity transmission infrastructure to ease congestion, allow for increases in demand, and provide a greater degree of security. The Transmission Reliability Program is aligned with this strategic plan

428

ITC Transmission | Open Energy Information  

Open Energy Info (EERE)

ITC Transmission ITC Transmission Jump to: navigation, search Name ITC Transmission Place Michigan Utility Id 56068 Utility Location Yes Ownership T NERC RFC Yes ISO MISO Yes Activity Transmission Yes Alt Fuel Vehicle Yes Alt Fuel Vehicle2 Yes References EIA Form EIA-861 Final Data File for 2010 - File1_a[1] LinkedIn Connections CrunchBase Profile No CrunchBase profile. Create one now! This article is a stub. You can help OpenEI by expanding it. Utility Rate Schedules Grid-background.png No rate schedules available. Average Rates No Rates Available References ↑ "EIA Form EIA-861 Final Data File for 2010 - File1_a" Retrieved from "http://en.openei.org/w/index.php?title=ITC_Transmission&oldid=410858" Categories: EIA Utility Companies and Aliases Utility

429

Fact #850: December 8, 2014 Automatic Transmissions have closed the Fuel Economy Gap with Manual Transmissions  

Broader source: Energy.gov [DOE]

Historically, manual transmissions have delivered better fuel economy than automatic transmissions. However, improvements in the efficiency of automatic transmissions have closed that gap in recent...

430

Kangley - Echo Lake Transmission Line Project, Final Environmental Impact Statement  

Broader source: Energy.gov (indexed) [DOE]

STATEMENT - APPENDICES STATEMENT - APPENDICES Appendices Appendix A Addition to Appendix A, Final Fisheries Technical Report Appendix D Final Wetlands Technical Report Appendix F Geology, Soil, Climate, and Hydrology Technical Report Appendix U Addition to Appendix U, Letter from the National Marine Fisheries Service Appendix Y Drinking Water Regulations Appendix Z Updated EMF Information Appendix AA Letter from the U.S. Fish and Wildlife Service Table of Contents Addition to Appendix A Final Fisheries Technical Report Appendix A. Data and Comments for Streams, Map and Aerial Photo-Based Surveys Appendix A. Table A-1. Data and comments for streams, map and airphoto-based survey. Stream name Number KC Class 1 Description of RMZ Segment Potential Resident

431

Bonneville Power Administration/Lower Valley Transmission Project  

Broader source: Energy.gov (indexed) [DOE]

853 853 Federal Register / Vol. 63, No. 162 / Friday, August 21, 1998 / Notices Radiological Impacts-Total radiological releases would be significantly lower than either the U.S. Environmental Protection Agency (EPA) limit or past annual releases from LANL. The resulting maximum concentrations for radionuclides measured at the location of the MEI for the demonstration is estimated to be less than two percent of the EPA limit. Radiological impacts associated with the proposed action could increase LANL total site impacts by a small percentage (1.0 percent for the MEI, 1.3 percent for the surrounding population, and 1.3 percent for the average individual). Under the proposed action, the estimated annual average dose to pit disassembly workers would be 750 mrem. The annual dose received by the

432

Joint transmission system projects to improve system reliability  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

5 12 JOINT NEWS RELEASE Bonneville Power Administration Puget Sound Energy Seattle City Light Snohomish PUD FOR IMMEDIATE RELEASE Tuesday, January 24, 2012 CONTACT: Mike Hansen,...

433

BPA, Transmission, proposed I-5 Corridor Reinforcement Project...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

dropped from consideration no longer appear on the map (segments 27, 31, 42 and 44). Substation sites BPA is now considering three sites for a new substation near Castle Rock,...

434

BPA Transmission, I-5 Corridor Reinforcement Project, letter...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

near Castle Rock, Washington in Cowlitz County, to a new substation near BPA's Troutdale Substation, Troutdale, Oregon in Multnomah County. BPA is proposing the I-5 Corridor...

435

BPA, Transmission, I-5 Corridor Reinforcement Project, August...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

near Castle Rock, Cowlitz County, Washington, to a new substation near BPA's Troutdale Substation, Troutdale, Multnomah County, Oregon (see enclosed map). Background BPA is a...

436

BPA, Transmission, I-5 Corridor Reinforcement Project factsheet...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

near Castle Rock, Wash., and Troutdale, Ore. The new line would be about 70 miles long. BPA has identified four route alternatives. Each includes a new substation near Castle...

437

BPA, Transmission, I-5 Corridor Reinforcement Project, February...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

could help relieve congestion in the Longview area, eliminate the need for a new substation at Castle Rock, and allow BPA to move the northern terminus of the line to the...

438

BPA, Transmission, I-5 Corridor Reinforcement Project, November...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Draft tower, line locations available BPA has released its preliminary designs showing tower and right-of-way locations. Information is now available online, allowing landowners to...

439

BPA, Transmission, I-5 Corridor Reinforcement Project, list of...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

* Lewis and Clark College, Paul L. Boley Law Library * Portland State University, Branford P. Millar Library * Multnomah County Library (central) Troutdale - Troutdale Library...

440

BPA, Transmission, I-5 Corridor Reinforcement Project, Alternatives...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

s Vancouver Longview Portland Castle Rock Ostrander Minnehaha Salmon Creek Camas Troutdale Battle Ground Ridgefield Woodland Saint Helens 36 T S 46 38 45 37 47 4 B 36A 41 23 W...

Note: This page contains sample records for the topic "navajo transmission project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


441

Sierra Pacific Power Company Alturas Transmission Line Project...  

Broader source: Energy.gov (indexed) [DOE]

to mitigate significant visd impacts in Secret Valley along U.S. 395 and at the Tule Patch Spring Rest Stop. Alternative Segment ESVA: 23.0 es Proposed Segments L, N: 21.1...

442

BPA Transmission, I-5 Corridor Reinforcement Project Scoping...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

like segment 31 have existing easements and well maintained streets for access and repair. 3. You could modify segment 30 so that it is pushed Eastward by 1 mile. You would...

443

SunShot Initiative: Transmission Grid Integration  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Transmission Grid Integration to Transmission Grid Integration to someone by E-mail Share SunShot Initiative: Transmission Grid Integration on Facebook Tweet about SunShot Initiative: Transmission Grid Integration on Twitter Bookmark SunShot Initiative: Transmission Grid Integration on Google Bookmark SunShot Initiative: Transmission Grid Integration on Delicious Rank SunShot Initiative: Transmission Grid Integration on Digg Find More places to share SunShot Initiative: Transmission Grid Integration on AddThis.com... Concentrating Solar Power Photovoltaics Systems Integration Research, Development, & Demonstration Distribution Grid Integration Transmission Grid Integration Solar Resource Assessment Technology Validation Power Electronics & Balance of System Hardware Technologies Competitive Awards

444

Project Controls  

Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

Project controls are systems used to plan, schedule, budget, and measure the performance of a project/program. The cost estimation package is one of the documents that is used to establish the baseline for project controls. This chapter gives a brief description of project controls and the role the cost estimation package plays.

1997-03-28T23:59:59.000Z

445

Bibliography on transmission access issues  

SciTech Connect (OSTI)

This paper presents a bibliography on issues related to transmission access in electric power systems. There are 233 citations referenced in this bibliography. This bibliography presents a collection of selected literature on issues related to transmission access. It does not contain all of the material available on this subject or the categories contained herein. Some readers may feel that citations within this bibliography should be strictly limited to transmission system issues and not include energy pricing or reliability issues. However, it was the decision of the Subcommittee of the IEEE Task Force on Transmission Access and Nonutility Generation that selected entries relating to reliability and energy pricing, most relevant to transmission access, should be included. This decision was made because certain issues relating to reliability, transmission and energy pricing are perceived by the industry to be critical in the discussion of transmission access. The bibliography has been divided into the following sections or sub-sections: 2.0 Operational (Engineering) Issues, 3.0 Planning, 4.0 Reliability, 5.1 Economics: Costing, 5.2(a) Economics: Location-Differentiated Pricing, 5.2(b) Economics: Time-Differentiated Pricing, 5.3 Economics: Brokering, Bidding, and Auctioning, 6.0 Regulatory, and 7.0 General. Although the content of many publications spanned two or more of these sections, the desire to limit document length required that all publications be placed in the single most appropriate section. Publications are sorted according to author or publication resource.

Lankford, C.B. [Oklahoma Gas and Electric Co., Oklahoma City, OK (United States)] [Oklahoma Gas and Electric Co., Oklahoma City, OK (United States); McCalley, J.D. [Iowa State Univ., Ames, IA (United States)] [Iowa State Univ., Ames, IA (United States); Saini, N.K. [Entergy Services Corp., Metairie, LA (United States)] [Entergy Services Corp., Metairie, LA (United States)

1996-02-01T23:59:59.000Z

446

Sundance Energy Project Final Environmental Impact Statement  

SciTech Connect (OSTI)

Sundance Energy LLC (Sundance) has applied to the Western Area Power Administration (Western) to interconnect a planned generator facility to Western's transmission system in the vicinity of Coolidge, Arizona. Western's proposed action is to enter into an interconnection and construction agreement with Sundance for the requested interconnection. The proposed interconnection would integrate the power generated by the Sundance Energy Project (Project) into the regional transmission grid and would allow Sundance to supply its power to the competitive electric wholesale market. The proposed Project would be built on private lands southwest of Coolidge. The proposed Project would be a ''peaking power plant project'' which means it would provide energy when it is needed during peak demand periods in the region. The proposed Project would also be a ''merchant plant'' which means it is not owned by a utility and there is currently no long-term commitment or obligation by any utility to purchase the energy generated by the power plant. Western, as a major transmission system owner, must generally provide access to its transmission system when requested by an eligible organization per existing policies, regulations and laws. The proposed Project would consist of the construction and operation of a generating facility; construction of a 14-mile pipeline to supply natural gas to the proposed Facility; a new 230-kV bay at an existing substation; a new double-circuit 230-kV transmission line; a new single-circuit 230-kV transmission line; an upgrade of a 115-kV line to 230-kV specifications; and an upgrade of an existing substation. Three alternatives would consist of different locations of the 230-kV transmission lines and would not involve upgrading the 115-kV line or the existing substation. The environmentally preferred alternative is Alternative 3, the power line routing that is furthest west.

N /A

2001-06-29T23:59:59.000Z

447

Environmental Assessment : Happy Valley [Substation Project].  

SciTech Connect (OSTI)

The proposed Happy Valley project consists of construction of a new BPA customer service 69-kV substation south of Sequim in Clallam County, Washington. A tie line, to be constructed by the customer as part of this project, will link the new BPA facility to the existing customer's transmission system in the area. This project responds to rapid load growth in the Olympic Peninsula, and will strengthen the existing BPA system and interconnected utility systems. It will reduce transmission losses presently incurred, especially on the BPA system supplying power to the Olympic Peninsula. This report describes the potential environmental impact of the proposed actions. 2 figs., 1 tab.

United States. Bonneville Power Administration.

1982-05-01T23:59:59.000Z

448

Using a Collaborative Approach to Interconnection-Wide Transmission Analyses  

Broader source: Energy.gov (indexed) [DOE]

Interconnection-Wide Planning in Interconnection-Wide Planning in the Eastern Interconnection EIPC Update for the DOE Electricity Advisory Committee October 20, 2011 David A. Whiteley Presentation Topics * Update on process and structure * Study results so far * Value unlocked * What's next 2 Update on Process and Structure * EIPC - 26 EI Planning Authorities (Planning Coordinators) * Integrate and analyze approved regional plans * Develop interregional expansion scenarios to be studied * Develop interregional transmission expansion options * Consistent with Orders 890 and 1000 * Self-funded * Primary activity is DOE funded interconnection studies project - 2 phases 3 Who are the PAs? * Alcoa Power Generating * American Transmission Co. * Duke Energy Carolinas * Electric Energy Inc. * Entergy *

449

Electrical transmission line diametrical retainer  

DOE Patents [OSTI]

The invention is a mechanism for retaining an electrical transmission line. In one embodiment of the invention it is a system for retaining an electrical transmission line within down hole components. In accordance with one aspect of the invention, the system includes a plurality of downhole components, such as sections of pipe in a drill string. The system also includes a coaxial cable running between the first and second end of a drill pipe, the coaxial cable having a conductive tube and a conductive core within it. The invention allows the electrical transmission line to with stand the tension and compression of drill pipe during routine drilling cycles.

Hall, David R. (Provo, UT); Hall, Jr., H. Tracy (Provo, UT); Pixton, David (Lehi, UT); Dahlgren, Scott (Provo, UT); Sneddon, Cameron (Provo, UT); Briscoe, Michael (Lehi, UT); Fox, Joe (Spanish Fork, UT)

2004-12-14T23:59:59.000Z

450

The Role of Demand Resources In Regional Transmission Expansion Planning and Reliable Operations  

SciTech Connect (OSTI)

Investigating the role of demand resources in regional transmission planning has provided mixed results. On one hand there are only a few projects where demand response has been used as an explicit alternative to transmission enhancement. On the other hand there is a fair amount of demand response in the form of energy efficiency, peak reduction, emergency load shedding, and (recently) demand providing ancillary services. All of this demand response reduces the need for transmission enhancements. Demand response capability is typically (but not always) factored into transmission planning as a reduction in the load which must be served. In that sense demand response is utilized as an alternative to transmission expansion. Much more demand response is used (involuntarily) as load shedding under extreme conditions to prevent cascading blackouts. The amount of additional transmission and generation that would be required to provide the current level of reliability if load shedding were not available is difficult to imagine and would be impractical to build. In a very real sense demand response solutions are equitably treated in every region - when proposed, demand response projects are evaluated against existing reliability and economic criteria. The regional councils, RTOs, and ISOs identify needs. Others propose transmission, generation, or responsive load based solutions. Few demand response projects get included in transmission enhancement plans because few are proposed. But this is only part of the story. Several factors are responsible for the current very low use of demand response as a transmission enhancement alternative. First, while the generation, transmission, and load business sectors each deal with essentially the same amount of electric power, generation and transmission companies are explicitly in the electric power business but electricity is not the primary business focus of most loads. This changes the institutional focus of each sector. Second, market and reliability rules have, understandably, been written around the capabilities and limitations of generators, the historic reliability resources. Responsive load limitations and capabilities are often not accommodated in markets or reliability criteria. Third, because of the institutional structure, demand response alternatives are treated as temporary solutions that can delay but not replace transmission enhancement. Financing has to be based on a three to five year project life as opposed to the twenty to fifty year life of transmission facilities. More can be done to integrate demand response options into transmission expansion planning. Given the societal benefits it may be appropriate for independent transmission planning organizations to take a more proactive role in drawing demand response alternatives into the resource mix. Existing demand response programs provide a technical basis to build from. Regulatory and market obstacles will have to be overcome if demand response alternatives are to be routinely considered in transmission expansion planning.

Kirby, Brendan J [ORNL

2006-07-01T23:59:59.000Z

451

Salt River Project | Open Energy Information  

Open Energy Info (EERE)

Project Project Jump to: navigation, search Name Salt River Project Place Tempe, Arizona Utility Id 16572 Utility Location Yes Ownership P NERC Location WECC NERC WECC Yes Operates Generating Plant Yes Activity Generation Yes Activity Transmission Yes Activity Buying Transmission Yes Activity Distribution Yes Activity Wholesale Marketing Yes Activity Bundled Services Yes Alt Fuel Vehicle Yes Alt Fuel Vehicle2 Yes References EIA Form EIA-861 Final Data File for 2010 - File1_a[1] SGIC[2] Energy Information Administration Form 826[3] LinkedIn Connections CrunchBase Profile No CrunchBase profile. Create one now! This article is a stub. You can help OpenEI by expanding it. Salt River Project Smart Grid Project was awarded $56,859,359 Recovery Act Funding with a total project value of $114,003,719.

452

Transmission Planning | Department of Energy  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Planning Planning Transmission Planning Modernizing America's electricity infrastructure is one of the U.S. Department of Energy's top priorities. The National Transmission Grid Study (PDF 2.0 MB) made clear that without dramatic improvements and upgrades over the next decade our nation's transmission system will fall short of the reliability standards our economy requires, and will result in higher electricity costs to consumers. The Department's research into a variety of tools that will improve advanced system monitoring, visualization, control, operations, and market structure will ultimately modernize the electricity transmission infrastructure to ease congestion, allow for increases in demand, and provide a greater degree of security. The next generation supervisory control and data acquisition (SCADA) and

453

Video transmission over wireless networks  

E-Print Network [OSTI]

Compressed video bitstream transmissions over wireless networks are addressed in this work. We first consider error control and power allocation for transmitting wireless video over CDMA networks in conjunction with multiuser detection. We map a...

Zhao, Shengjie

2005-08-29T23:59:59.000Z

454

National Electric Transmission Congestion Studies  

Broader source: Energy.gov [DOE]

Section 216(a) of the Federal Power Act, as amended by the Energy Policy Act of 2005, directs the U.S. Department of Energy (DOE) to conduct a study every three years on electric transmission congestion and constraints within the Eastern and Western Interconnections. The American Reinvestment and Recovery Act of 2009 (Recovery Act) further directed the Secretary to include in the 2009 Congestion Study an analysis of significant potential sources of renewable energy that are constrained by lack of adequate transmission capacity. Based on this study, and comments concerning it from states and other stakeholders, the Secretary of Energy may designate any geographic area experiencing electric transmission capacity constraints or congestion as a national interest electric transmission corridor (National Corridor).

455

National Transmission Grid Study: 2002  

Broader source: Energy.gov [DOE]

National Transmission Grid Study: The National Energy Policy Plan directed the U.S. Department of Energy (DOE) to conduct a study to examine the benefits of establishing a national electricity...

456

OpenEI Community - transmission  

Open Energy Info (EERE)

black out brown out bulk power system electricity grid future grid grid history security Smart Grid transmission Smart Grid Fri, 31 Oct 2014 17:58:14 +0000 Dc 955 at...

457

EA-1617: Lovell-Yellowtail and Basin-Lovell Transmission Line Rebuild  

Broader source: Energy.gov (indexed) [DOE]

17: Lovell-Yellowtail and Basin-Lovell Transmission Line 17: Lovell-Yellowtail and Basin-Lovell Transmission Line Rebuild Project, Big Horn County, Wyoming, and Big Horn and Carbon Counties, Montana EA-1617: Lovell-Yellowtail and Basin-Lovell Transmission Line Rebuild Project, Big Horn County, Wyoming, and Big Horn and Carbon Counties, Montana Summary DOE's Western Area Power Administration prepared this EA and a finding of no significant impact for a proposal to rebuild the Lovell-Yellowtail (LV-YT) No. 1 and No. 2 115-kV transmission lines, located in Big Horn County, Wyoming, and Big Horn and Carbon Counties in Montana, and the Basin-Lovell 115-kV transmission line in Big Horn County, Wyoming. Public Comment Opportunities No public comment opportunities available at this time. Documents Available for Download

458

EA-1679: Grand Coulee's Third Powerplant 500-kV Transmission Line  

Broader source: Energy.gov (indexed) [DOE]

79: Grand Coulee's Third Powerplant 500-kV Transmission Line 79: Grand Coulee's Third Powerplant 500-kV Transmission Line Replacement Project, Grant and Okanogon Counties, Washington EA-1679: Grand Coulee's Third Powerplant 500-kV Transmission Line Replacement Project, Grant and Okanogon Counties, Washington Summary This EA evaluates potential environmental impacts from the construction and operation of six new 500-kV overhead transmission lines to replace six existing underground lines at Grand Coulee Dam. DOE's Bonneville Power Administration (BPA), a cooperating agency, was asked by the U. S. Department of the Interior's Bureau of Reclamation to design and construct the proposed new transmission lines. A Finding of No Significant Impact was issued by BPA in December 2011. BPA website: http://efw.bpa.gov/environmental_services/Document_Library/Grand_Coulee/

459

Negative differential transmission in graphene  

Science Journals Connector (OSTI)

By using the Kubo linear response theory with the Keldysh Green function approach, we investigate the mechanism leading to the negative differential transmission in a system with the equilibrium electron density much smaller than the photon-excited one. It is shown that the negative differential transmission can appear at low probe-photon energy (in the order of the scattering rate) or at high energy (much larger than the scattering rate). For the low probe-photon energy case, the negative differential transmission is found to come from the increase of the intraband conductivity due to the large variation of electron distribution after the pumping. As for the high probe-photon energy case, the negative differential transmission is shown to tend to appear with the hot-electron temperature being closer to the equilibrium one and the chemical potential higher than the equilibrium one but considerably smaller than half of the probe-photon energy. We also show that this negative differential transmission can come from both the inter- and the intraband components of the conductivity. Especially, for the interband component, its contribution to the negative differential transmission is shown to come from both the Hartree-Fock self-energy and the scattering. Furthermore, the influence of the Coulomb-hole self-energy is also addressed.

B. Y. Sun and M. W. Wu

2013-12-17T23:59:59.000Z

460

DOE Transmission Capacity Report | Department of Energy  

Broader source: Energy.gov (indexed) [DOE]

Transmission Capacity Report Transmission Capacity Report DOE Transmission Capacity Report DOE Transmission Capacity Report: Transmission lines, substations, circuit breakers, capacitors, and other equipment provide more than just a highway to deliver energy and power from generating units to distribution systems. Transmission systems both complement and substitute for generation. Transmission generally enhances reliability; lowers the cost of electricity delivered to consumers; limits the ability of generators to exercise market power; and provides flexibility to protect against uncertainties about future fuel prices, load growth, generator construction, and other factors affecting the electric system. DOE Transmission Capacity Report More Documents & Publications Report to Congress:Impacts of the Federal Energy Regulatory Commission's

Note: This page contains sample records for the topic "navajo transmission project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


461

AGENDA: PETROLEUM PRODUCT TRANSMISSION & DISTRIBUTION | Department...  

Broader source: Energy.gov (indexed) [DOE]

AGENDA: PETROLEUM PRODUCT TRANSMISSION & DISTRIBUTION AGENDA: PETROLEUM PRODUCT TRANSMISSION & DISTRIBUTION A Public Meeting on the Quadrennial Energy Review, Hosted by the United...

462

Briefing Memo: Petroleum Product Transmission & Distribution...  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

Briefing Memo: Petroleum Product Transmission & Distribution Briefing Memo: Petroleum Product Transmission & Distribution Click below to download a PDF of the briefing memo....

463

Natural Gas Transmission and Distribution Module  

Gasoline and Diesel Fuel Update (EIA)

U.S. Energy Information Administration | Assumptions to the Annual Energy Outlook 2013 Natural Gas Transmission and Distribution Module The NEMS Natural Gas Transmission and...

464

Agenda: Natural Gas: Transmission, Storage and Distribution ...  

Broader source: Energy.gov (indexed) [DOE]

Natural Gas: Transmission, Storage and Distribution Agenda: Natural Gas: Transmission, Storage and Distribution A Public Meeting on the Quadrennial Energy Review, Hosted by the...

465

2006 National Electric Transmission Congestion Study Federal...  

Broader source: Energy.gov (indexed) [DOE]

6 National Electric Transmission Congestion Study Federal Register Notice & Comments 2006 National Electric Transmission Congestion Study Federal Register Notice & Comments The...

466

National Electric Transmission Congestion Study | Department...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Study National Electric Transmission Congestion Study National Electric Transmission Congestion Study Section 1221(a) of the Energy Policy Act of 2005, codified at 16 U.S.C....

467

2009 National Electric Transmission Congestion Study | Department...  

Broader source: Energy.gov (indexed) [DOE]

9 National Electric Transmission Congestion Study 2009 National Electric Transmission Congestion Study Section 216(a) of the Federal Power Act, as amended by the Energy Policy Act...

468

Electric Transmission Siting | Open Energy Information  

Open Energy Info (EERE)

navigation, search OpenEI Reference LibraryAdd to library Legal Document- OtherOther: Electric Transmission SitingLegal Abstract Electric Transmission Siting at the California...

469

2006 National Electric Transmission Congestion Study | Department...  

Broader source: Energy.gov (indexed) [DOE]

6 National Electric Transmission Congestion Study 2006 National Electric Transmission Congestion Study Section 216(a) of the Federal Power Act, as amended by the Energy Policy Act...

470

National Electric Transmission Congestion Study Workshops | Department...  

Broader source: Energy.gov (indexed) [DOE]

National Electric Transmission Congestion Study Workshops National Electric Transmission Congestion Study Workshops DOE hosted four regional pre-study workshops to receive input...

471

WINDExchange Offshore Wind Webinar: Transmission Planning and...  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

Offshore Wind Webinar: Transmission Planning and Interconnection for Offshore Wind WINDExchange Offshore Wind Webinar: Transmission Planning and Interconnection for Offshore Wind...

472

Agenda: Electricity Transmission and Distribution - East | Department...  

Broader source: Energy.gov (indexed) [DOE]

Electricity Transmission and Distribution - East Agenda: Electricity Transmission and Distribution - East A Public Meeting on the Quadrennial Energy Review, Hosted by the United...

473

Agenda: Electricity Transmission, Storage and Distribution -...  

Broader source: Energy.gov (indexed) [DOE]

Electricity Transmission, Storage and Distribution - West Agenda: Electricity Transmission, Storage and Distribution - West A Public Meeting on the Quadrennial Energy Review,...

474

Directly correlated transmission electron microscopy and atom...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Directly correlated transmission electron microscopy and atom probe tomography of grain boundary oxidation in a Ni-Al binary Directly correlated transmission electron microscopy...

475

EIS-0400: Granby Pumping Plant Switchyard-Windy Gap Substation Transmission  

Broader source: Energy.gov (indexed) [DOE]

EIS-0400: Granby Pumping Plant Switchyard-Windy Gap Substation EIS-0400: Granby Pumping Plant Switchyard-Windy Gap Substation Transmission Line Rebuild Project, Grand County, CO EIS-0400: Granby Pumping Plant Switchyard-Windy Gap Substation Transmission Line Rebuild Project, Grand County, CO Summary Western Area Power Administration prepared an EIS, with the U.S. Forest Service, Bureau of Land Management, and Grand County (Colorado) as cooperating agencies, to evaluate the potential environmental impacts of rebuilding a 12-mile, 69-kV electric transmission line in Grand County. The proposed project would rebuild the single-circuit line as a double-circuit transmission line and add a second power transformer. Western identified potentially significant impacts while preparing an EA for this proposal (DOE/EA-1520) and prepared an EIS instead of completing

476

EIS-0400: Granby Pumping Plant Switchyard-Windy Gap Substation Transmission  

Broader source: Energy.gov (indexed) [DOE]

00: Granby Pumping Plant Switchyard-Windy Gap Substation 00: Granby Pumping Plant Switchyard-Windy Gap Substation Transmission Line Rebuild Project, Grand County, CO EIS-0400: Granby Pumping Plant Switchyard-Windy Gap Substation Transmission Line Rebuild Project, Grand County, CO Summary Western Area Power Administration prepared an EIS, with the U.S. Forest Service, Bureau of Land Management, and Grand County (Colorado) as cooperating agencies, to evaluate the potential environmental impacts of rebuilding a 12-mile, 69-kV electric transmission line in Grand County. The proposed project would rebuild the single-circuit line as a double-circuit transmission line and add a second power transformer. Western identified potentially significant impacts while preparing an EA for this proposal (DOE/EA-1520) and prepared an EIS instead of completing

477

Science Projects  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Argonne Argonne Science Project Ideas! Our Science Project section provides you with sample classroom projects and experiments, online aids for learning about science, as well as ideas for Science Fair Projects. Please select any project below to continue. Also, if you have an idea for a great project or experiment that we could share, please click our Ideas page. We would love to hear from you! Science Fair Ideas Science Fair Ideas! The best ideas for science projects are learning about and investigating something in science that interests you. NEWTON has a list of Science Fair linkd that can help you find the right topic. Toothpick Bridge Web Sites Toothpick Bridge Sites! Building a toothpick bridge is a great class project for physics and engineering students. Here are some sites that we recommend to get you started!

478

Projection Systems  

Science Journals Connector (OSTI)

As a general rule, broad-band sources which employ projection optics are the most difficult to evaluate. In addition to the problems encountered in evaluating exposed lamps, one must characterize the projected...

David Sliney; Myron Wolbarsht

1980-01-01T23:59:59.000Z

479

Circle Project  

E-Print Network [OSTI]

This project asks students to decide if a collection of points in space do or do not lie on a ... The project is accessible to linear algebra students who have studied ...

480

u.s. DEPARTl'..IENT OF ENERGY EERE PROJECT MANAGEM ENT CEN T  

Broader source: Energy.gov (indexed) [DOE]

No.1 to conduct preliminary engineering analyses in support of a project to harness hydroelectric power from the Everett, WA Reservoir 4 water transmission line. The Snohomish...

Note: This page contains sample records for the topic "navajo transmission project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


481

EA-1987: Parker-Headgate Rock and Parker-Bouse Rebuild Project...  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

the existing Parker Dam-Headgate Rock and Parker Dam-Bouse 161-kilovolt transmission lines along the Colorado River in western Arizona and eastern California. The project...

482

Title 16 U.S.C. 1278(a) Restrictions on Water Resources Projects...  

Open Energy Info (EERE)

not grant any license for construction of any dam, water conduit, reservoir, powerhouse, transmission line, or other project works under the Federal Power Act on or directly...

483

Plains & Eastern Clean Line Project Proposal for New or Upgraded  

Broader source: Energy.gov (indexed) [DOE]

Plains & Eastern Clean Line Project Proposal for New or Upgraded Plains & Eastern Clean Line Project Proposal for New or Upgraded Transmission Line Projects Under Section 1222 of the Energy Policy Act of 2005 Plains & Eastern Clean Line Project Proposal for New or Upgraded Transmission Line Projects Under Section 1222 of the Energy Policy Act of 2005 Plains & Eastern Clean Line Project Proposal for New or Upgraded Transmission Line Projects Under Section 1222 of the Energy Policy Act of 2005 (July 2010) Update to Plains & Eastern Clean Line Project Proposal for New or Upgraded Transmission Line Projects Under Section 1222 of the Energy Policy Act of 2005 (August 2011) More Documents & Publications EIS-0486: Notice of Intent and Notice of Potential Floodplain and Wetland Involvement Notice of Intent To Prepare an Environmental Impact Statement for the

484

Electric Power Transmission and Distribution (EPTD) Smart Grid Program (New  

Broader source: Energy.gov (indexed) [DOE]

Electric Power Transmission and Distribution (EPTD) Smart Grid Electric Power Transmission and Distribution (EPTD) Smart Grid Program (New York) Electric Power Transmission and Distribution (EPTD) Smart Grid Program (New York) < Back Eligibility Agricultural Commercial Construction Industrial Institutional Investor-Owned Utility Municipal/Public Utility Retail Supplier Rural Electric Cooperative Systems Integrator Utility Savings Category Alternative Fuel Vehicles Hydrogen & Fuel Cells Water Buying & Making Electricity Home Weatherization Solar Wind Program Info State New York Program Type Grant Program Provider New York State Energy Research and Development Authority Up to $10 million in funds is available from NYSERDA to support research and engineering studies, product development and demonstration projects that improve the reliability, efficiency, quality, and overall performance

485

Hydropower Projects  

Broader source: Energy.gov [DOE]

This report covers the Wind and Water Power Technologies Office's hydropower project funding from fiscal years 2008 to 2014.

486

Registration Contact List: Electricity Transmission System Workshop  

Broader source: Energy.gov (indexed) [DOE]

11/2/2012 11/2/2012 First Name Last Name Title Company Address1 Address2 City State/Province Zip Country Work Phone Sandy Aivaliotis , Valley Group, a Nexans 3A Trowbridge Drive Bethel CT 6801 United States 416-648-4382 Robert Anders Management U.S. Department of Energy / EERE Rm 6A-067 1000 Independence Ave., SW Washington DC 20585 United States 202-586-4716 Phillip Anderson g g Project Leader Idaho Power 1221 W. Idaho St. Boise ID 83702 United States 208-484-2024 Mihai Anitescu Dr. Argonne National Laboratory 9700 S Cas Avenue Argonne IL 60439 United States 16302524172 Sam Baldwin Officer USDOE/EERE 1000 Independence Ave., SW Washington DC 20585 United States 202-586-0927 Thomas Baldwin Energy Lead Idaho National Laboratory P.O. Box 1655 Idaho Falls ID 83415-3810 United States 208-526-1864 Venkat Banunarayanan g Transmission Department of Energy

487

GRR/Section 8-ID-a - State Transmission | Open Energy Information  

Open Energy Info (EERE)

8-ID-a - State Transmission 8-ID-a - State Transmission < GRR Jump to: navigation, search GRR-logo.png GEOTHERMAL REGULATORY ROADMAP Roadmap Home Roadmap Help List of Sections Section 8-ID-a - State Transmission 08IDAStateTransmission.pdf Click to View Fullscreen Contact Agencies Idaho Public Utilities Commission Regulations & Policies IC §67-6508: Local Land Use Planning Duties IC §61-526: Certificate of Public Convenience and Necessity Triggers None specified Click "Edit With Form" above to add content 08IDAStateTransmission.pdf Error creating thumbnail: Page number not in range. Error creating thumbnail: Page number not in range. Error creating thumbnail: Page number not in range. Flowchart Narrative 8-ID-a.1 - Will the Transmission Project Be Undertaken by a Public Utility?

488

Bio-based Thermochromic Intelligent Roof Coating Research Project |  

Broader source: Energy.gov (indexed) [DOE]

based Thermochromic Intelligent Roof based Thermochromic Intelligent Roof Coating Research Project Bio-based Thermochromic Intelligent Roof Coating Research Project The Department of Energy is conducting research into bio-based thermochromic intelligent roof coatings. The coatings are developed from waste cooking oil. Project Description This project seeks to develop and demonstrate a waste cooking oil-based thermochromic smart roof coating technology that will adjust light transmission in response to temperature changes. This will reduce energy demands for temperature regulation. The project will also study the effects of different oil sources on coating properties. Project Partners This project is being undertaken between the Department of Energy and United Environment & Energy. Project Goals

489

Identification and definition of unbundled electric generation and transmission services  

SciTech Connect (OSTI)

State and federal regulators, private and public utilities, large and small customers, power brokers and marketers, and others are engaged in major debates about the future structure of the electric industry. Although the outcomes are far from certain, it seems clear that customers will have much greater choices about the electric services they purchase and from whom they buy these services. This report examines the ``ancillary`` services that are today buried within the typical vertically integrated utility. These ancillary services support and make possible the provision of the basic services of generating capacity, energy supply, and power delivery. These ancillary services include: Management of generating units; reserve generating capacity to follow variations in customer loads, to provide capacity and energy when generating units or transmission lines suddenly fall, to maintain electric-system stability, and to provide local-area security; transmission-system monitoring and control; replacement of real power and energy losses; reactive-power management and voltage regulation; transmission reserves; repair and maintenance of the transmission network; metering, billing, and communications; and assurance of appropriate levels of power quality. Our focus in this report, the first output from a larger Oak Ridge National Laboratory project, is on identification and definition of these services. Later work in this project will examine more closely the costs and pricing options for each service.

Kirby, B.; Hirst, E.; Vancoevering, J.

1995-03-01T23:59:59.000Z

490

Career Map: Power Systems/Transmission Engineer  

Broader source: Energy.gov [DOE]

The Wind Program's Career Map provides job description information for Power Systems and Transmission Engineer positions.

491

Development of superconducting transmission cable. CRADA final report  

SciTech Connect (OSTI)

The purpose of this Cooperative Research and Development Agreement (CRADA) between Oak Ridge National Laboratory (ORNL) and Southwire Company is to develop the technology necessary to proceed to commercialization of high-temperature superconducting (HTS) transmission cables. Power transmission cables are a promising near-term electric utility application for high-temperature superconductivity. Present HTS wires match the needs for a three-phase transmission cable: (1) the wires must conduct high currents in self-field, (2) there are no high forces developed, and (3) the cables may operate at relatively low current density. The commercially-available HTS wires, in 100-m lengths, make construction of a full three-phase, alternating current (ac) transmission cable possible. If completed through the pre-commercialization phase, this project will result in a new capability for electric power companies. The superconducting cable will enable delivery with greater efficiency, higher power density, and lower costs than many alternatives now on the market. Job creation in the US is expected as US manufacturers supply transmission cables to the expanding markets in Asia and to the densely populated European cities where pipe-type cable is prevalent. Finally, superconducting cables may enable delivery of the new, diverse and distributed sources of electricity that will constitute the majority of new installed electrical generation in the world during the coming decades.

Hawsey, R.; Stovall, J.P. [Oak Ridge National Lab., TN (United States); Hughey, R.L.; Sinha, U.K. [Southwire Co., Carrollton, GA (United States)

1997-10-01T23:59:59.000Z

492

DOE Transmission System Integration Workshop  

Broader source: Energy.gov (indexed) [DOE]

Heyeck, AEP, Sr. Vice President, Transmission Heyeck, AEP, Sr. Vice President, Transmission and Chair, EPRI Power Delivery & Utilization Sector Council November 01-02, 2012 DoubleTree Hotel, Crystal City Washington D.C. DOE Transmission System Integration Workshop 2 © 2012 Electric Power Research Institute, Inc. All rights reserved. Near-Zero Emissions Long-Term Operations Renewable Integration Water Management Electric Vehicles Demand Response & Efficiency Renewable Energy Energy Storage Sensors & Control Cyber Security Supply = Demand The Power System Supply to Demand Requires a full portfolio of innovative technologies. Tomorrow's Power System One size does not fit all 3 © 2012 Electric Power Research Institute, Inc. All rights reserved. Grid Transformation to Ensure Reliability, Efficiency, Resiliency and Security

493

Transmission Lines Emulating Moving Media  

E-Print Network [OSTI]

In this paper, we show how the electromagnetic phenomena in moving magnetodielectric media can be emulated using artificial composite structures at rest. In particular, we introduce nonreciprocal periodically loaded transmission lines which support waves obeying the same rules as plane electromagnetic waves in moving media. Because the actual physical structure is at rest, in these transmission lines there are no fundamental limitations on the velocity values, which may take values larger than the speed of light or even complex values (considering complex amplitudes in the time-harmonic regime). An example circuit of a unit cell of a "moving" transmission line is presented and analyzed both numerically and experimentally. The special case of composite right/left handed host line is also studied numerically. Besides the fundamental interest, the study is relevant for potential applications in realizing engineered materials for various transformations of electromagnetic fields.

Vehmas, Joni; Tretyakov, Sergei

2014-01-01T23:59:59.000Z

494

California/Transmission | Open Energy Information  

Open Energy Info (EERE)

California/Transmission California/Transmission < California Jump to: navigation, search CaliforniaTransmissionHeader.png Roadmap Agency Links Local Regulations State Regulations Summary General Transmission Dashboard Permitting Atlas Compare States Arizona California Colorado Idaho Montana Nevada New Mexico Oregon Utah Washington Wyoming Resource Library NEPA Database The electrical grid in California is part of the WestConnect Transmission Planning area and the California Transmission Planning Group. The desert southwest region of California belongs to the Southwest Area Transmission power grid and the northern region of the state belongs to the Sierra Subregional Planning Group. The SWAT provides the technical forum required to complete reliability assessments, develop joint business opportunities and accomplish

495

Planning considerations for the intermountain HVDC transmission system  

SciTech Connect (OSTI)

Planning of an HVDC transmission system embedded into an existing ac network may require unique control and converter equipment capability in order to satisfy stability requirements of the network. The planning and design of the Intermountain Power Project HVDC transmission system are based on unique control performance features for power transfers during terminal ac faults, rapid power recovery following fault clearing and utilization of exceptionally high transient overload capability of 2 per unit during the post-fault period to maintain system stability. The Department, in its efforts to meet the Western Systems Coordinating Council's (WSCC) reliability criteria, developed and incorporated into its HVDC specifications very rigorous reliability and availability requirements. One objective of this project was to attain the unusually low bipolar converter system outage frequency goal of one outage in five years to achieve a bipole performance rating equivalent to two ac circuits of similar capability. The reliability goals of this project have provided one of the impetus for revisions to the WSCC Reliability Criteria for System Design. The reliability goals and other features adopted for the Intermountain HVDC transmission system are discussed in this paper and study results are included to demonstrate the effectiveness of various controls implemented as stability enhancement techniques.

Lee, R.L.; Beshir, M.J.; Gee, J.H.

1986-01-01T23:59:59.000Z

496

Wind Project Development | Open Energy Information  

Open Energy Info (EERE)

Project Development Project Development Jump to: navigation, search This page provides links to information resources regarding project development steps. Photo from Iberdrola Renewables Inc., NREL 16702 To finance and construct a wind energy project, five areas must be addressed: Detailed wind resource data for the site being developed The right to access and use the land on which the project will be constructed Permission to construct and operate the project from local permitting authorities Rights to interconnect to the transmission or distribution system and to transport (wheel) that energy to its purchaser A power purchase agreement between the project owner (seller) and the power purchaser (buyer). If any of these items are not contractually supported with the proper documentation, the project is unlikely to obtain financing.[1]

497

EIS-0266: Glass Mountain/Four Mile Hill Geothermal Project, California  

Broader source: Energy.gov [DOE]

The EIS analyzes BPA's proposed action to approve the Transmission Services Agreements (TSAs) and Power Purchase Agreements (PPAs) with Calpine Siskiyou Geothermal Partners, L.P. (Calpine) to acquire output from the Fourmile Hill Geothermal Development Project (Project).

498

Getting the Crop to Market: Siting and Permitting Transmission Lines on Buffalo Ridge, Minnesota  

Science Journals Connector (OSTI)

Publisher Summary The rapid development of wind technology in southwest Minnesota has prompted the need to improve the transmission system in this area. The Minnesota Public Utilities Commission approved four major transmission line projects in 2003 to meet this need, including an 87-mile 345 kV transmission line. Northern States Power Company, d/b/a Xcel Energy, currently is involved in the State siting process with the projects and has been gathering public and agency input. Gathering the information early in the process has proven to be invaluable in deciding route locations and permitting strategies. In addition, public reception for the projects has been primarily positive since these facilities will allow additional wind generation to be developed in the area. This chapter describes the Xcel Energy projects, public reactions to the project, and the routing and siting issues, including some unique to these projects. Xcel Energy will highlight the primary lessons learned that can be used in future projects for routing transmission lines.

Michelle F. Bissonnette; Angela G.L. Piner; Pamela J. Rasmussen

2008-01-01T23:59:59.000Z

499

Project Title  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

CCS CCS August 20-22, 2013 2 Presentation Outline * Benefits to the program * Project overall objectives * Technical status * Project summary * Conclusions and future plans 3 Benefit to the Program * Develop technologies that will support industries' ability to predict CO 2 storage capacity in geologic formations to within ±30 percent. * Develop technologies to demonstrate that 99 percent of injected CO 2 remains in the injection zones. * This research project develops a reservoir scale CO 2 plume migration model at the Sleipner project, Norway. The Sleipner project in the Norwegian North Sea is the world's first commercial scale geological carbon storage project. 4D seismic data have delineated the CO 2 plume migration history. The relatively long history and high fidelity data make

500

Reliability evaluation for large-scale bulk transmission systems: Volume 1, Comparative evaluation, method development, and recommendations: Final report  

SciTech Connect (OSTI)

This volume (1 of 2) contains a comparative evaluation of existing transmission system reliability programs (SYREL, GATOR, RECS) and relevant mathematical methods for transmission reliability analysis. Several new and enhanced methods in the areas of network analysis, contingency selection, remedial action, and reliability index calculation, developed and tested during the project, are described. Recommendations for methods to be used in a production grade transmission reliability assessment program are presented. 69 figs., 41 tabs.

Lam, B.P.; Lawrence, D.J.; Reppen, N.D.; Ringlee, R.J.

1988-01-01T23:59:59.000Z