National Library of Energy BETA

Sample records for mitigation action implementation

  1. Mitigation Action Implementation Network (MAIN) | Open Energy...

    Open Energy Info (EERE)

    of Nationally Appropriate Mitigation Actions (NAMAs) and Low-Carbon Development (LCD) strategies in developing countries through regionally based dialogues, web-based...

  2. Implementing mitigative actions on the Superconducting Super Collider project

    SciTech Connect (OSTI)

    Sands, T.L. )

    1993-01-01

    The Super Collider is the first project for which a Mitigation Action Plan (MAP) was prepared under a DOE Order that became effective in 1990. The policy requires a MAP for any project where environmental findings were predicated on taking mitigative actions. The MAP must be approved prior to the start of preliminary design and thus cannot be site or facility-specific because the requisite level of detail would not be available. This gap is filled by a series of environmental compliance plans (ECP) that are prepared by the architect-engineer/constructions manager under the direction of the DOE Management and Operations Contractor for the Super Collider. A given ECP identifies the environmental protection measures applicable to the respective contract package. The designated design team uses the ECP as one of its requirements documents and the environmental staff uses it during design reviews to verify compliance with the MAP. Site audits and monitoring data are used to document compliance and verify the effectiveness of mitigative actions, or identify required corrective actions. The applicability of this process to other projects falling within the scope of the National Environmental Policy Act is discussed.

  3. WREP Mitigation Action Plan

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Electrical Interconnection of the Whistling Ridge Energy Project 1 Mitigation Action Plan June 2015 Mitigation Action Plan for the Whistling Ridge Energy Project Measure Implementation Timeline Implementation Responsibility Earth (geology, soils, topography, and geologic hazards) Prior to Project construction, confirm subsurface soil and rock types and strength properties through a detailed geotechnical investigation of the specific locations of all wind Project elements, including wind

  4. Mitigation Action Plan

    SciTech Connect (OSTI)

    Not Available

    1994-02-01

    This Mitigation Action Plan (MAP) focuses on mitigation commitments stated in the Supplemental Environmental Impact Statement (SEIS) and the Record of Decision (ROD) for the Naval Petroleum Reserve No. 1 (NPR-1). Specific commitments and mitigation implementation actions are listed in Appendix A-Mitigation Actions, and form the central focus of this MAP. They will be updated as needed to allow for organizational, regulatory, or policy changes. It is the intent of DOE to comply with all applicable federal, state, and local environmental, safety, and health laws and regulations. Eighty-six specific commitments were identified in the SEIS and associated ROD which pertain to continued operation of NPR-1 with petroleum production at the Maximum Efficient Rate (MER). The mitigation measures proposed are expected to reduce impacts as much as feasible, however, as experience is gained in actual implementation of these measures, some changes may be warranted.

  5. Mitigation Action Plan

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Mitigation Action Plan FutureGen 2.0 Project DOE/EIS-0460 U.S. Department of Energy National Energy Technology Laboratory March 2014 DOE/EIS-0460 FUTUREGEN 2.0 PROJECT MITIGATION ACTION PLAN INTENTIONALLY LEFT BLANK DOE/EIS-0460 FUTUREGEN 2.0 PROJECT MITIGATION ACTION PLAN TABLE OF CONTENTS Introduction ................................................................................................................................................... 1 Purpose

  6. Mitigation Action Plan

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Mitigation Action Plan FutureGen 2.0 Project DOE/EIS-0460 U.S. Department of Energy National Energy Technology Laboratory March 2014 DOE/EIS-0460 FUTUREGEN 2.0 PROJECT MITIGATION ACTION PLAN INTENTIONALLY LEFT BLANK DOE/EIS-0460 FUTUREGEN 2.0 PROJECT MITIGATION ACTION PLAN TABLE OF CONTENTS Introduction ................................................................................................................................................... 1 Purpose

  7. EA-1628: Mitigation Action Plan | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    Lignocellulosic Biorefinery, Emmetsburg, Iowa This Mitigation Action Plan specifieis the methods for implementing mitigation measures that address the potential environmental...

  8. EA-1508: Mitigation Action Plan | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    and dewatering, landscape engineering, borrow pits and recommended procedures for Raptors and powerline construction. Mitigation Action Plan to Implement Mitigation...

  9. EIS-0422: Mitigation Action Plan | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    Mitigation measures and estimated time of implementation within the Mitigation Action Plan for the Central Ferry-Lower Monumental 500-kilovolt Transmission Line Project. Mitigation...

  10. EIS-0218: Mitigation Action Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Mitigation Action Plan EIS-0218: Mitigation Action Plan Implementation of a Nuclear Weapons Nonproliferation Policy Concerning Foreign Research Reactor Spent Nuclear Fuel The ...

  11. EIS-0486: Mitigation Action Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Mitigation Action Plan EIS-0486: Mitigation Action Plan Plains & Eastern Clean Line Transmission Project DOE issued a Mitigation Action Plan that explains how mitigation measures, which have been designed to mitigate adverse environmental impacts associated with the course of action directed by the Record of Decision, will be planned and implemented. For more information visit the project page: http://energy.gov/node/583039. Download Document EIS-0486: Mitigation Action Plan (12.85 MB) More

  12. EIS-0464: Mitigation Action Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Mitigation Action Plan EIS-0464: Mitigation Action Plan Lake Charles Carbon Capture and Sequestration Project, Lake Charles, Louisiana and Brazoria County, Texas This Mitigation Action Plan (MAP) briefly describes the mitigation actions and monitoring and reporting requirements the recipient must implement during the design, construction, and demonstration of the Lake Charles Carbon Capture and Sequestration Project. DOE prepared this MAP in accordance with 10 CFR 1021.331. EIS-0464-MAP-2014.pdf

  13. EIS-0323: Mitigation Action Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    approval is implemented. PDF icon Mitigation Action Plan for the Sacramento Area Voltage Support Project Prepared to Accompany The Sacramento Area Voltage Support Project...

  14. Mitigation Action Plans (MAP) and Related Documents | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    EIS-0218: Mitigation Action Plan Implementation of a Nuclear Weapons Nonproliferation Policy Concerning Foreign Research Reactor Spent Nuclear Fuel May 1, 1994 EIS-0186:...

  15. EA-1704: Mitigation Action Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    4: Mitigation Action Plan EA-1704: Mitigation Action Plan Construction and Operation of a Proposed Cellulosic Biorefinery, BlueFire Fulton Renewable Energy, LLC, Fulton, Mississippi This Mitigation Action Plan specifies the methods for implementing mitigation measures that address the potential environmental impacts associated with the construction and operation of a lignocellulosic ethanol refinery, BlueFire Fulton Renewable Energy, LLC in Fulton, Mississippi. EA-1704-MAP-2010.pdf (2.11 MB)

  16. EIS-0380: Mitigation Action Plan Annual Report

    Broader source: Energy.gov [DOE]

    Los Alamos National Laboratory Site-Wide Environmental Impact Statement Fiscal Year 2012 Mitigation Action Plan Annual Report

  17. EIS-0397: Mitigation Action Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Mitigation Action Plan EIS-0397: Mitigation Action Plan Lyle Falls Fish Passage Project This Mitigation Action Plan identifies measures that are intended to avoid, reduce, or...

  18. EA-1934: 2014 Annual Report for Mitigation Action Plan | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Hanford Site, Richland, Washington This annual report provides a summary of DOEEA-1934 Mitigation Action Plan implementation in calendar year 2014. PDF icon EA-1934-FEA-MAP-2014...

  19. EA-1923: Mitigation Action Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Mitigation Action Plan EA-1923: Mitigation Action Plan Green Energy School Wind Turbine Project on Saipan, Commonwealth of the Northern Mariana Islands This Mitgation Action Plan ...

  20. Mitigation Action Plans and Scenarios (MAPS) | Open Energy Information

    Open Energy Info (EERE)

    Mitigation Action Plans and Scenarios (MAPS) (Redirected from CIFF-Chile-Mitigation Action Plans and Scenarios (MAPS)) Jump to: navigation, search Retrieved from "http:...

  1. EA-1595: Mitigation Action Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Mitigation Action Plan EA-1595: Mitigation Action Plan Davis-Mead 230-kV Transmission Line Reconductor Project Western Area Power Administration proposes to reconductor ...

  2. Mitigation Action Plans (MAP) and Related Documents | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    November 25, 2014 EIS-0472: Mitigation Action Plan Uranium Leasing Program Mitigation Action Plan for the Final Uranium Leasing Program Programmatic Environmental Impact Statement ...

  3. EA-1706: Mitigation Action Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Mitigation Action Plan EA-1706: Mitigation Action Plan West Tennessee Solar Farm Project Haywood County, Tennessee Based on the analyses in the Environmental Assessment, DOE...

  4. EIS-0380: Mitigation Action Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    : Mitigation Action Plan EIS-0380: Mitigation Action Plan Continued Operation of Los Alamos National Laboratory, Los Alamos, New Mexico PDF icon Site-Wide Environmental Impact ...

  5. EIS-0380: Fiscal Year 2011 Mitigation Action Plan Annual Report...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Fiscal Year 2011 Mitigation Action Plan Annual Report for the 2008 Los Alamos Site-Wide Environmental Impact Statement EIS-0380: Fiscal Year 2011 Mitigation Action Plan Annual ...

  6. Angola-Nationally Appropriate Mitigation Actions (NAMAs) in the...

    Open Energy Info (EERE)

    Angola-Nationally Appropriate Mitigation Actions (NAMAs) in the Congo Basin Jump to: navigation, search Name Angola-Nationally Appropriate Mitigation Actions (NAMAs) in the Congo...

  7. DOE Uranium Leasing Program 2015 Mitigation Action Plan Activity...

    Energy Savers [EERE]

    DOE Uranium Leasing Program 2015 Mitigation Action Plan Activity Summary Report DOE Uranium Leasing Program 2015 Mitigation Action Plan Activity Summary Report DOE Uranium Leasing ...

  8. EA-1917: Mitigation Action Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    7: Mitigation Action Plan EA-1917: Mitigation Action Plan Wave Energy Test Facility Project, Newport, OR Through the environmental review process, DOE determined, via consultations ...

  9. EIS-0419: Mitigation Action Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Mitigation Action Plan EIS-0419: Mitigation Action Plan Whistling Ridge Energy Project; Skamania County, Washington Bonneville Power Administration (BPA) adopted all the mitigation measures described in the Whistling Ridge Energy Project EIS and prepared a mitigation action plan. The applicant will be responsible for executing the mitigation measures for the wind project, and BPA will be responsible for executing the mitigation measures for the BPA interconnection facilities. For more

  10. EIS-0350-S1: Mitigation Action Plan | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    Los Alamos, NM This Mitigation Action Plan (MAP) describes mitigation and monitoring commitments for constructing and operating the Modified CMRR-NF. The commitments made in this ...

  11. EIS-0472: Mitigation Action Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Mitigation Action Plan EIS-0472: Mitigation Action Plan Uranium Leasing Program Mitigation Action Plan for the Final Uranium Leasing Program Programmatic Environmental Impact Statement DOE LM issued the Final Uranium Leasing Program Programmatic Environmental Impact Statement (DOE/EIS-0472) in March 2014 and issued the associated Record of Decision (ROD) on May 6, 2014; the ROD was published in the Federal Register on May 12, 2014. This Mitigation Action Plan addresses the mitigation commitments

  12. EA-1440-S1: Mitigation Action Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Mitigation Action Plan EA-1440-S1: Mitigation Action Plan National Renewable Energy ... Biorefinery Pilot Plant (TBPP). EA-1440-S1-MAP-2008.pdf (3.04 MB) More Documents & ...

  13. EIS-0425: Record of Decision and Mitigation Action Plan

    Broader source: Energy.gov [DOE]

    Bonneville Power Administration Record of Decision and Mitigation Action Plan for the Mid-Columbia Restoration Project

  14. Peru-GEF Nationally Appropriate Mitigation Actions in the Energy...

    Open Energy Info (EERE)

    (Redirected from UNDP-Peru GEF Nationally Appropriate Mitigation Actions in the Energy Generation and End-Use Sectors)...

  15. DOE Uranium Leasing Program 2015 Mitigation Action Plan Activity Summary

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Report | Department of Energy Uranium Leasing Program 2015 Mitigation Action Plan Activity Summary Report DOE Uranium Leasing Program 2015 Mitigation Action Plan Activity Summary Report DOE Uranium Leasing Program 2015 Mitigation Action Plan Activity Summary Report (447.33 KB) More Documents & Publications LM Annual NEPA Planning Summary 2014 EA-1535: Final Programmatic Environmental Assessment EA-1934: 2015 Annual Report for Mitigation Action

  16. EIS-0380: Annual Mitigation Action Plan Annual Report

    Office of Energy Efficiency and Renewable Energy (EERE)

    Los Alamos National Laboratory Site-Wide Environmental Impact Statement Fiscal Year 2013 Mitigation Action Plan Annual Report

  17. EIS-0389: Mitigation Action Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Action Plan EIS-0389: Mitigation Action Plan Trinity Public Utilities District Direct Interconnection Project Western Area Power Administration (Western) proposes to...

  18. EA-1934: 2015 Annual Report for Mitigation Action Plan | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy 2015 Annual Report for Mitigation Action Plan EA-1934: 2015 Annual Report for Mitigation Action Plan Expansion of Active Borrow Areas, Hanford Site, Richland, Washington This annual report provides a summary of DOE/EA-1934 Mitigation Action Plan implementation in calendar year 2015. For more information, see http://energy.gov/node/381343. EA-1934_FEA_MAP_2015 (1.33 MB) More Documents & Publications EA-1934: 2014 Annual Report for Mitigation Action Plan EA-1934: Final Environmental

  19. EA-1440-S-I: Mitigation Action Plan Completion Report

    Broader source: Energy.gov [DOE]

    This report presents the U.S. Department of Energy’s completion of the May 2008 Mitigation Action Plan (MAP) for the Supplement to the Final Site-Wide Environmental Assessment of the National Renewable Energy Laboratory’s South Table Mountain Complex (DOE/EA-1440-S-I) . Since May 2008, DOE and the National Renewable Energy Laboratory (NREL) have implemented various traffic mitigation measures and routinely monitored traffic at the NREL South Table Mountain (STM) campus in Golden, Colorado in accordance with the MAP. With the completion and occupancy of the new Research Support Facility (RSF) and Energy Systems Integration Facility (ESIF) and with offsite traffic impacts maintained below threshold levels, implementation of the MAP is hereby complete. NREL and DOE will continue to implement current traffic control measures and conduct informal traffic monitoring as part of standard operations and sustainability initiatives.

  20. Dual Axis Radiographic Hydrodynamic Test Facility mitigation action plan. Annual report for 1998

    SciTech Connect (OSTI)

    Haagenstad, T.

    1999-01-15

    This Mitigation Action Plan Annual Report (MAPAR) has been prepared as part of implementing the Dual Axis Radiographic Hydrodynamic Test Facility (DARHT) Mitigation Action Plan (MAP) to protect workers, soils, water, and biotic and cultural resources in and around the facility.

  1. EA-1934: Mitigation Action Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Mitigation Action Plan EA-1934: Mitigation Action Plan Expansion of Active Borrow Areas, Hanford Site, Richland, Washington This Mitigation Action Plan is an integral part of the Finding of No Significant Impact for the proposed action within the Expansion of Active Borrow Areas, Hanford Site. The proposed action would expand 11active borrow pits on the Hanford Site that were included in the previous Environmental Assessments (DOE/EA-1403, DOE/EA-1454), and establish 1 new borrow source. This

  2. MITIGATION ACTION PLAN FOR THE PLAINS & EASTERN CLEAN LINE TRANSMISSION PROJECT

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    MITIGATION ACTION PLAN FOR THE PLAINS & EASTERN CLEAN LINE TRANSMISSION PROJECT DOE/EIS-0486 MARCH 2016 3 1 INTRODUCTION The U.S. Department of Energy (DOE) National Environmental Policy Act (NEPA) Implementing Procedures (Title 10 Code of Federal Regulations [CFR] 1021.331) require completion of a mitigation action plan (MAP) following each Environmental Impact Statement (EIS) and its associated Record of Decision (ROD) to address mitigation commitments expressed in the ROD. The DOE Notice

  3. UNEP-Ethiopia-Facilitating Implementation and Readiness for Mitigation...

    Open Energy Info (EERE)

    UNEP-Ethiopia-Facilitating Implementation and Readiness for Mitigation (FIRM) Redirect page Jump to: navigation, search REDIRECT Facilitating Implementation and Readiness for...

  4. EA-1915: Mitigation Action Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Mitigation Action Plan EA-1915: Mitigation Action Plan Proposed Conveyance of Land at the Hanford Site, Richland, Washington DOE prepared a Mitigation Action Plan (MAP) as an integral part of the Finding of No Significant Impact for DOE's EA. For more information on this project, see the project webpage: http://energy.gov/nepa/ea-1915-proposed-conveyance-land-hanford-site-ric... EA-1915-MAP-2015.pdf (86.09 KB) More Documents & Publications EA-1915: Final Environmental Assessment EA-1915:

  5. EA-1855: Mitigation Action Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Lincoln and Spokane Counties, Washington (aka DOEEA-4406) This Mitigation Action Plan (MAP) is part of the Finding of No Significant Impact for the Creston-Bell...

  6. EA-1591: Mitigation Action Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Plan Palisades-Goshen Transmission Line Reconstruction Project This Mitigation Action Plan (MAP) is part of the Finding of No Significant Impact (FONSI) for the...

  7. Mitigation Action Plans (MAP) and Related Documents | Department...

    Broader source: Energy.gov (indexed) [DOE]

    EA-1704: Mitigation Action Plan Construction and Operation of a Proposed Cellulosic Biorefinery, BlueFire Fulton Renewable Energy, LLC, Fulton, Mississippi March 10, 2010...

  8. EA-1858: Mitigation Action Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    boiler and a 20-megawatt steam turbine at its existing paper mill in Port Angeles, Washington. PDF icon Mitigation Action Plan for the Environmental Assessment for the...

  9. EIS-0323: Mitigation Action Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Mitigation Action Plan for the Sacramento Area Voltage Support Project which is prepared to accompany the Sacramento Area Voltage Support Project Supplement Environmental Impact...

  10. Mitigation Action Plans (MAP) and Related Documents | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Project, Grant and Okanogon Counties, Washington November 1, 2011 EIS-0350-S1: Mitigation Action Plan Nuclear Facility Portion of the Chemistry and Metallurgy Research Building...

  11. EA-1901: Mitigation Action Plan | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    White Sturgeon and Burbot Hatcheries Project, Bonners Ferry, Boundary County, Idaho This Mitigation Action Plan (MAP) is referenced in the Finding of No Significant Impact for the...

  12. Central African Republic-Nationally Appropriate Mitigation Actions...

    Open Energy Info (EERE)

    Appropriate Mitigation Actions (NAMAs) in the Congo Basin AgencyCompany Organization Environment Canada, International Institute for Sustainable Development (IISD) Sector...

  13. Burundi-Nationally Appropriate Mitigation Actions (NAMAs) in...

    Open Energy Info (EERE)

    Appropriate Mitigation Actions (NAMAs) in the Congo Basin AgencyCompany Organization Environment Canada, International Institute for Sustainable Development (IISD) Sector...

  14. Rwanda-Nationally Appropriate Mitigation Actions (NAMAs) in the...

    Open Energy Info (EERE)

    Appropriate Mitigation Actions (NAMAs) in the Congo Basin AgencyCompany Organization Environment Canada, International Institute for Sustainable Development (IISD) Sector...

  15. Cameroon-Nationally Appropriate Mitigation Actions (NAMAs) in...

    Open Energy Info (EERE)

    Appropriate Mitigation Actions (NAMAs) in the Congo Basin AgencyCompany Organization Environment Canada, International Institute for Sustainable Development (IISD) Sector...

  16. EIS-0332: Mitigation Action Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    transmission line between Bonneville Power Administration's existing McNary and John Day substations. PDF icon Mitigation Action Plan for the McNary-John Day Transmission...

  17. EA-1739: Mitigation Action Plan | Department of Energy

    Energy Savers [EERE]

    More Documents & Publications EA-1951: Finding of No Significant Impact and Mitigation Action Plan EA-1739: Finding of No Significant Impact EIS-0285-SA-117: Supplement Analysis

  18. Fiscal Year 2013 Trails Management Program Mitigation Action Plan Annual Report, October 2013

    SciTech Connect (OSTI)

    Pava, Daniel S.

    2015-03-25

    This Trails Management Program Mitigation Action Plan Annual Report (Trails MAPAR) has been prepared for the Department of Energy (DOE)/National Nuclear Security Administration (NNSA) as part of implementing the 2003 Final Environmental Assessment for the Proposed Los Alamos National Laboratory Trails Management Program (DOE 2003). The Trails Mitigation Action Plan (MAP) is now a part of the Site-Wide Environmental Impact Statement for the Continued Operation of Los Alamos National Laboratory (DOE/EIS 0380) Mitigation Action Plan (2008 SWEIS MAP) (DOE 2008). The MAP provides guidance for the continued implementation of the Trails Management Program at Los Alamos National Laboratory (LANL) and integration of future mitigation actions into the 2008 SWEIS MAP to decrease impacts associated with recreational trails use at LANL. This eighth MAPAR includes a summary of Trails Management Program activities and actions during Fiscal Year (FY) 2013, from October 2012 through September 2013.

  19. EIS-0026: Mitigation Action Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    EIS-0026: Mitigation Action Plan Waste Isolation Pilot Plant This MAP focuses on ... Action Plan, is the central focus of this MAP and will be updated as needed to allow for ...

  20. Southern Idaho Wildlife Mitigation Implementation 2000 Annual Report.

    SciTech Connect (OSTI)

    Bottum, Edward; Mikkelsen, Anders

    2001-03-01

    This report covers calendar year 2000 activities for the Southern Idaho Wildlife Mitigation Implementation project. This project, implemented by Idaho Department of Fish and Game and Shoshone Bannock Tribes wildlife mitigation staff, is designed to protect, enhance and maintain wildlife habitats to mitigate construction losses for Palisades, Anderson Ranch, Black Canyon and Minidoka hydroelectric projects. Additional project information is available in the quarterly reports.

  1. Southern idaho Wildlife Mitigation Implementation 1999 Annual Report.

    SciTech Connect (OSTI)

    Bottum, Edward; Mikkelsen, Anders

    2000-04-01

    This report is for the Southern Idaho Wildlife Mitigation Implementation project. This project, implemented by IDFG and SBT wildlife mitigation staff, is designed to protect, enhance and maintain wildlife habitats to mitigate construction losses for Palisades, Anderson Ranch, Black Canyon and Minidoka hydroelectric projects. Additional project information is available in the quarterly reports.

  2. Hungry Horse Dam Fisheries Mitigation Implementation Plan, 1990-2003 Progress (Annual) Report.

    SciTech Connect (OSTI)

    Montana Department of Fish, Wildlife and Parks; Confederated Salish and Kootenai Tribes

    1993-03-10

    In this document the authors present mitigation implementation activities to protect and enhance resident fish and aquatic habitat affected by the construction and operation of Hungry Horse Dam. This plan only addresses non-operational actions (mitigation measures that do not affect dam operation) described in the 'Fisheries Mitigation Plan for Losses Attributable to the Construction and Operation of Hungry Horse Dam' (Mitigation Plan) submitted to the Northwest Power Planning Council (Council) in March 1991 and in accordance with subsequent Council action on that Mitigation Plan. Operational mitigation was deferred for consideration under the Columbia Basin System Operation Review (SOR) process. This document represents an implementation plan considered and conditionally approved by the Council in March of 1993.

  3. EA-1636: Mitigation Action Plan | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    Burnt Woods and Santiam-Toledo Pole Replacement Project This Mitigation Action Plan (MAP) is part of the Finding of No Significant Impact (FONSI) for the Albany-Burnt Woods and...

  4. EIS-0473: Mitigation Action Plan | Department of Energy

    Office of Environmental Management (EM)

    EIS-0473: Mitigation Action Plan W.A. Parish Post-Combustion CO2 Capture and Sequestration ... demonstration of the W.A. Parish Post-Combustion CO2 Capture and Sequestration Project. ...

  5. EIS-0460: Mitigation Action Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    FutureGen 2.0 Project, Morgan County, Illinois This Mitigation Action Plan (MAP) briefly ... DOE prepared this MAP in accordance with 10 Code of Federal Regulations (CFR) 1021.331. ...

  6. EIS-0332: Mitigation Action Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    kV transmission line between Bonneville Power Administration's existing McNary and John Day substations. PDF icon DOEEIS-0332: Mitigation Action Plan for the McNary-John Day...

  7. Dual Axis Radiographic Hydrodynamic Test Facility mitigation action plan. Annual report for 1997

    SciTech Connect (OSTI)

    Haagenstad, H.T.

    1998-01-15

    This Mitigation Action Plan Annual Report (MAPAR) has been prepared by the US Department of Energy (DOE) as part of implementing the Dual Axis Radiographic Hydrodynamic Test Facility (DARHT) Mitigation Action Plan (MAP). This MAPAR provides a status on specific DARHT facility design- and construction-related mitigation actions that have been initiated in order to fulfill DOE`s commitments under the DARHT MAP. The functions of the DARHT MAP are to (1) document potentially adverse environmental impacts of the Phased Containment Option delineated in the Final EIS, (2) identify commitments made in the Final EIS and ROD to mitigate those potential impacts, and (3) establish Action Plans to carry out each commitment (DOE 1996). The DARHT MAP is divided into eight sections. Sections 1--5 provide background information regarding the NEPA review of the DARHT project and an introduction to the associated MAP. Section 6 references the Mitigation Action Summary Table which summaries the potential impacts and mitigation measures; indicates whether the mitigation is design-, construction-, or operational-related; the organization responsible for the mitigation measure; and the projected or actual completion data for each mitigation measure. Sections 7 and 8 discuss the Mitigation Action Plan Annual Report and Tracking System commitment and the Potential Impacts, Commitments, and Action Plans respectively. Under Section 8, potential impacts are categorized into five areas of concern: General Environment, including impacts to air and water; Soils, especially impacts affecting soil loss and contamination; Biotic Resources, especially impacts affecting threatened and endangered species; Cultural/Paleontological Resources, especially impacts affecting the archeological site known as Nake`muu; and Human Health and Safety, especially impacts pertaining to noise and radiation. Each potential impact includes a brief statement of the nature of the impact and its cause(s). The commitment

  8. EIS-0425: Mitigation Action Plan | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    Project BPA decided to implement the Proposed Action of the Mid-Columbia Coho Restoration Program as described in the Mid-Columbia Coho Restoration Program Final Environmental...

  9. EA-2006: Finding of No Significant Impact and Mitigation Action Plan |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy Finding of No Significant Impact and Mitigation Action Plan EA-2006: Finding of No Significant Impact and Mitigation Action Plan Columbia Estuary Ecosystem Restoration Program Bonneville Power Administration issued a FONSI and a floodplain and wetland statement of findings for a proposed program of actions to help restore ecological structure, function, and biodiversity within the Columbia River estuary. The mitigation measures listed in the Mitigation Action Plan and

  10. EA-1950: Finding of No Significant Impact and Mitigation Action Plan |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy 0: Finding of No Significant Impact and Mitigation Action Plan EA-1950: Finding of No Significant Impact and Mitigation Action Plan Grand Coulee-Creston Transmission Line Rebuild; Grant and Lincoln Counties, Washington Bonneville Power Administration issued a finding of no significant impact and a mitigation action plan for rebuilding approximately 28 miles of the Grand Coulee-Creston No. 1 115-kilovolt (kV) transmission line between Coulee Dam in Grant County and

  11. Addendum to 2010 NREL Environmental Performance Report … Traffic Mitigation Action Plan Update

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Addendum to the National Renewable Energy Laboratory Environmental Performance Report for 2010 (Annual Site Environmental Report per the U.S. Department of Energy Order 231.1-1A Chg 2) Traffic Mitigation Action Plan Update November 2011 Page 1 of 4 Traffic Mitigation Action Plan 2010 Update Traffic Management A Mitigation Action Plan (MAP), finalized in May 2008, was developed to address potential environmental impacts from changes in traffic at NREL and to support a Finding of No Significant

  12. EIS-0380: Fiscal Year 2011 Mitigation Action Plan Annual Report for the

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    2008 Los Alamos Site-Wide Environmental Impact Statement | Department of Energy Fiscal Year 2011 Mitigation Action Plan Annual Report for the 2008 Los Alamos Site-Wide Environmental Impact Statement EIS-0380: Fiscal Year 2011 Mitigation Action Plan Annual Report for the 2008 Los Alamos Site-Wide Environmental Impact Statement Fiscal Year 2011 Mitigation Action Plan Annual Report for the 2008 Los Alamos Site-Wide Environmental Impact Statement This Annual Report summarizes the activities that

  13. Implementation Proposal for the National Action Plan on Demand...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Implementation Proposal for the National Action Plan on DemandResponse - July 2011 Implementation Proposal for the National Action Plan on Demand Response - July 2011 Report to ...

  14. Mitigation Action Plan: Lease of Parcel ED-1 of the Oak Ridge Reservation by the East Tennessee Economic Council

    SciTech Connect (OSTI)

    1996-04-01

    In April 1996, the U.S. Department of Energy (DOE) completed an environmental assessment (EA) (DOE/EA-1113) for the proposed lease of 957-16 acres (Parcel ED-1) of the Oak Ridge (Tennessee) Reservation (ORR) by the East Tennessee Economic Council (ETEC) for industrial development. DOE plans to issue a Finding of No Significant Impact (FONSI) for the proposed action, conditional upon the implementation of mitigation and monitoring to protect environmental resources. According to DOE`s National Environmental Policy Act (NEPA) regulations (10 CFR 1021.322), a FONSI shall include {open_quotes}any commitments to mitigations that are essential to render the impacts of the proposed action not significant, beyond those mitigations that are integral elements of the proposed action, and a reference to the Mitigation Action Plan prepared under 10 CTR 1021.331{close_quotes}. Terms of the lease offer DOE the option of terminating the lease with ETEC should the lessee and/or sublessees fail to implement the mitigation defined in the FONSI.

  15. Institutional Change Process Step 4: Implement an Action Plan | Department

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    of Energy 4: Implement an Action Plan Institutional Change Process Step 4: Implement an Action Plan Graphic showing 5 gears. They progress from Determine Goal to Identify Context-Rules, Roles and Tools to Develop Action Plan to Implement Plan to Measure and Evaluate. Process for Continuous Change Writing a good action plan is one thing; implementing it is another. Institutional change principles and methods can be incorporated into action plans (program design), but on-the-ground

  16. EAC Recommendations for DOE Action Regarding Implementing Effective...

    Broader source: Energy.gov (indexed) [DOE]

    Implementing Effective Enterprise Security Governance, approved at the March 12-13, 2014 meeting. EAC Recommendations for DOE Action Regarding Implementing Effective...

  17. EA-1945: Finding of No Significant Impact and Mitigation Action Plan |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy Finding of No Significant Impact and Mitigation Action Plan EA-1945: Finding of No Significant Impact and Mitigation Action Plan Northern Mid-Columbia Joint Project; Grant, Douglas, and Chelan Counties, Washington Bonneville Power Administration (BPA) issued a finding of no significant impact, which includes a floodplain statement of findings, for the proposed Northern Mid-Columbia Joint Project, a 230-kilvolt transmission line proposed by BPA and the Public Utility

  18. EIS-0384: Mitigation Action Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    project designers and reviewers minimized short-term and long-term environmental and social impacts of the Proposed Action through project design, consultation with regulatory...

  19. Evaluating the implementation of environmental review mitigation in local planning and development processes

    SciTech Connect (OSTI)

    Slotterback, Carissa Schively

    2008-11-15

    The implementation of mitigation strategies and outcomes of environmental review remains a challenge for planners and regulators. While the process and content of environmental review is clearly defined, there is often little attention to what happens after the review is completed. This paper presents the results of an evaluation of the implementation of the outcomes of environmental review, specifically mitigation measures designed to respond to environmental impacts identified in the environmental impact analysis. Drawing on previous evaluations of environmental review outcomes and plan implementation, the research provides a methodology for evaluating the implementation of mitigation efforts, points to the challenges associated with implementing the mitigation outcomes of local environmental review in planning and development processes, and identifies opportunities to integrate planning and environmental review processes.

  20. EIS-0506: Record of Decision and Mitigation Action Plan | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    BPA decided to provide funding for implementing the project to improve tributary fish ... debris for bank structure and instream fish habitat, constructing side channels and ...

  1. Environmental Assessment and Finding of No Significant Impact: Implementation of the Wetland Mitigation Bank Program at the Savannah River Site

    SciTech Connect (OSTI)

    N /A

    1999-04-28

    The Department of Energy (DOE) has prepared an environmental assessment (EA) (DOE/EA-1205) for the proposed implementation of a wetland mitigation bank program at the Savannah River Site (SRS), located near Aiken, South Carolina. Based on the analyses in the EA, DOE has determined that the proposed action is not a major Federal action significantly affecting the quality of the human environment within the meaning of the National Environmental Policy Act of 1969 (NEPA). Therefore, the preparation of an environmental impact statement (EIS) is not required, and DOE is issuing this Finding of No Significant Impact (FONSI) and Floodplain Statement of Findings.

  2. Argentina-The Mitigation Action Implementation Network (MAIN...

    Open Energy Info (EERE)

    Ministry of Energy Argentina Sector Climate, Energy, Land Focus Area Renewable Energy, Non-renewable Energy, Agriculture, Biomass, - Waste to Energy, Economic Development,...

  3. Colombia-The Mitigation Action Implementation Network (MAIN)...

    Open Energy Info (EERE)

    of Energy Thailand, Ministry of Industry Thailand, Ministry of Natural Resources and Environment Thailand, Pollution Control Department, Ministry of Natural Resources and...

  4. Thailand-The Mitigation Action Implementation Network (MAIN)...

    Open Energy Info (EERE)

    of Energy Thailand, Ministry of Industry Thailand, Ministry of Natural Resources and Environment Thailand, Pollution Control Department, Ministry of Natural Resources and...

  5. India-The Mitigation Action Implementation Network (MAIN) | Open...

    Open Energy Info (EERE)

    of Energy Thailand, Ministry of Industry Thailand, Ministry of Natural Resources and Environment Thailand, Pollution Control Department, Ministry of Natural Resources and...

  6. Mexico-The Mitigation Action Implementation Network (MAIN) |...

    Open Energy Info (EERE)

    of Energy Thailand, Ministry of Industry Thailand, Ministry of Natural Resources and Environment Thailand, Pollution Control Department, Ministry of Natural Resources and...

  7. Panama-The Mitigation Action Implementation Network (MAIN) |...

    Open Energy Info (EERE)

    of Energy Thailand, Ministry of Industry Thailand, Ministry of Natural Resources and Environment Thailand, Pollution Control Department, Ministry of Natural Resources and...

  8. Costa Rica-The Mitigation Action Implementation Network (MAIN...

    Open Energy Info (EERE)

    of Energy Thailand, Ministry of Industry Thailand, Ministry of Natural Resources and Environment Thailand, Pollution Control Department, Ministry of Natural Resources and...

  9. Dominican Republic-The Mitigation Action Implementation Network...

    Open Energy Info (EERE)

    Republic, National Energy Commission Dominican Republic, Ministry of Environment and Natural Resources Dominican Republic, Ministry of Economy, Planning and Development Dominican...

  10. Indonesia-The Mitigation Action Implementation Network (MAIN...

    Open Energy Info (EERE)

    of Energy Thailand, Ministry of Industry Thailand, Ministry of Natural Resources and Environment Thailand, Pollution Control Department, Ministry of Natural Resources and...

  11. Brazil-The Mitigation Action Implementation Network (MAIN) |...

    Open Energy Info (EERE)

    of Energy Thailand, Ministry of Industry Thailand, Ministry of Natural Resources and Environment Thailand, Pollution Control Department, Ministry of Natural Resources and...

  12. Philippines-The Mitigation Action Implementation Network (MAIN...

    Open Energy Info (EERE)

    of Energy Thailand, Ministry of Industry Thailand, Ministry of Natural Resources and Environment Thailand, Pollution Control Department, Ministry of Natural Resources and...

  13. China-The Mitigation Action Implementation Network (MAIN) | Open...

    Open Energy Info (EERE)

    of Energy Thailand, Ministry of Industry Thailand, Ministry of Natural Resources and Environment Thailand, Pollution Control Department, Ministry of Natural Resources and...

  14. Vietnam-The Mitigation Action Implementation Network (MAIN) ...

    Open Energy Info (EERE)

    of Energy Thailand, Ministry of Industry Thailand, Ministry of Natural Resources and Environment Thailand, Pollution Control Department, Ministry of Natural Resources and...

  15. Malaysia-The Mitigation Action Implementation Network (MAIN)...

    Open Energy Info (EERE)

    of Energy Thailand, Ministry of Industry Thailand, Ministry of Natural Resources and Environment Thailand, Pollution Control Department, Ministry of Natural Resources and...

  16. Chile-The Mitigation Action Implementation Network (MAIN) | Open...

    Open Energy Info (EERE)

    of Energy Thailand, Ministry of Industry Thailand, Ministry of Natural Resources and Environment Thailand, Pollution Control Department, Ministry of Natural Resources and...

  17. Pakistan-The Mitigation Action Implementation Network (MAIN)...

    Open Energy Info (EERE)

    of Energy Thailand, Ministry of Industry Thailand, Ministry of Natural Resources and Environment Thailand, Pollution Control Department, Ministry of Natural Resources and...

  18. Uruguay-The Mitigation Action Implementation Network (MAIN) ...

    Open Energy Info (EERE)

    of Energy Thailand, Ministry of Industry Thailand, Ministry of Natural Resources and Environment Thailand, Pollution Control Department, Ministry of Natural Resources and...

  19. Peru-The Mitigation Action Implementation Network (MAIN) | Open...

    Open Energy Info (EERE)

    of Energy Thailand, Ministry of Industry Thailand, Ministry of Natural Resources and Environment Thailand, Pollution Control Department, Ministry of Natural Resources and...

  20. Mitigation Action Implementation Network (MAIN) Feed | Open Energy...

    Open Energy Info (EERE)

    US Savannah River National Laboratory (SRNL) UNEP-Risoe Centre on Energy, Climate and Sustainable Development United Nations Environment Programme (UNEP) United Nations...

  1. Step 4: Implement an Action Plan for Institutional Change

    Broader source: Energy.gov [DOE]

    Writing a good action plan is one thing; implementing it is another. Institutional change principles and methods can be incorporated into action plans (program design), but on-the-ground implementation activities must also be conducted in a manner that is suitable to the organizational context and the people in the roles being targeted.

  2. Institutional Change Process Step 4: Implement an Action Plan

    Office of Energy Efficiency and Renewable Energy (EERE)

    Writing a good action plan is one thing; implementing it is another. Institutional change principles and methods can be incorporated into action plans (program design), but on-the-ground implementation activities must also be conducted in a manner that is suitable to the organizational context and the people in the roles being targeted.

  3. Implement an Institutional Change Action Plan for Sustainability

    Broader source: Energy.gov [DOE]

    Writing a good action plan is one thing; implementing it is another. Institutional change principles and methods can be incorporated into action plans (program design), but on-the-ground implementation activities must also be conducted in a manner that is suitable to the organizational context and the people in the roles being targeted.

  4. Mitigation Measures for Distributed PV Interconnection

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Mitigation Action Plans (MAP) and Related Documents Mitigation Action Plans (MAP) and Related Documents Mitigation Action Plans are documents DOE prepares in accordance with DOE NEPA regulations (10 CFR 1021.331) that describes the plan for implementing commitments made in a DOE environmental impact statement and its associated record of decision, or, when appropriate, an EA or FONSI, to mitigate adverse environmental impacts associated with an action. If you have any trouble finding a specific

  5. Implementation of the Formerly Utilized Sites Remedial Action Program:

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Coordination Between the U.S. Department of Energy and the U.S. Army Corps of Engineers | Department of Energy Implementation of the Formerly Utilized Sites Remedial Action Program: Coordination Between the U.S. Department of Energy and the U.S. Army Corps of Engineers Implementation of the Formerly Utilized Sites Remedial Action Program: Coordination Between the U.S. Department of Energy and the U.S. Army Corps of Engineers Implementation of the Formerly Utilized Sites Remedial Action

  6. Final environmental impact statement for the Nevada Test Site and off-site locations in the state of Nevada: Mitigation action plan

    SciTech Connect (OSTI)

    1997-02-01

    The DOE Notice of Availability for this environmental impact statement was published in the Federal Register on Friday, October 18, 1996 (61 FR 54437). The final environmental impact statement identifies potential adverse effects resulting from the four use alternatives evaluated and discusses measures that DOE considered for the mitigation of these potential adverse effects. The Secretary of Energy signed the Record of Decision on the management and operation of the Nevada Test Site and other DOE sites in the state of Nevada on December 9, 1996. These decisions will result in the continuation of the multipurpose, multi-program use of the Nevada Test Site, under which DOE will pursue a further diversification of interagency, private industry, and public-education uses while meeting its Defense Program, Waste Management, and Environmental Restoration mission requirements at the Nevada Test Site and other Nevada sites, including the Tonopah Test Range, the Project Shoal Site, the Central Nevada Test Area, and on the Nellis Air Force Range Complex. The Record of Decision also identifies specific mitigation actions beyond the routine day-to-day physical and administrative controls needed for implementation of the decisions. These specific mitigation actions are focused on the transportation of waste and on groundwater availability. This Mitigation Action Plan elaborates on these mitigation commitments.

  7. Making the Most of Mitigation

    Broader source: Energy.gov [DOE]

    The Los Alamos Field Office uses a comprehensive Mitigation Action Plan to monitor and manage commitments to mitigate adverse environmental impacts associated with the 2008 Los Alamos National Laboratory Site-Wide Environmental Impact Statement (EIS) and multiple project-specific EISs and environmental assessments (EAs). The DOE NEPA Order requires a publicly available annual report on progress made in implementing mitigation commitments and the effectiveness of the mitigation.

  8. Final Report. SFAA No. DEFC02-98CH10961. Technical assistance for joint implementation and other supporting mechanisms and measures for greenhouse gas emissions mitigation

    SciTech Connect (OSTI)

    Knight, Denise

    2001-10-15

    IIEC, a division of CERF, has developed an extensive base of experience implementing activities that support climate action by developing USIJI projects in transitional countries within Asia, Latin America, Central and Eastern Europe, and southern Africa. IIEC has been able to provide a range of technical and policy assistance to governments and industry in support of sustainable energy use. IIEC continues to work in key countries with local partners to develop and implement energy efficiency policies and standards, develop site-specific projects, and assist governing bodies to establish national priorities and evaluation criteria for approving GHG-mitigation projects. As part of this project, IIEC focused on promoting a series of activities in Thailand and South Africa in order to identify GHG mitigation projects and work within the national approval process of those countries. The sections of this report outline the activities conducted in each country in order to achieve that goal.

  9. EAC Recommendations for DOE Action Regarding Implementing Effective Enterprise Security Governance- March 2014

    Broader source: Energy.gov [DOE]

    EAC Recommendations for DOE Action Regarding Implementing Effective Enterprise Security Governance, approved at the March 12-13, 2014 meeting.

  10. EIS-0026: Annual Mitigation Report | Department of Energy

    Office of Environmental Management (EM)

    2010 Annual Mitigation Report EIS-0026: 2010 Annual Mitigation Report Waste Isolation Pilot Plant Guidance for the development of a Mitigation Action Plan (MAP) is contained in Department of Energy (DOE) Order 451.1B, National Environmental Policy Act Compliance Program, and 10 CFR 1021, National Environmental Policy Act Implementing Procedures. These documents specify that a MAP be prepared to mitigate environmental impacts resulting from the implementation of commitments made in the Record of

  11. Implementation of a Noise Mitigation Strategy for a High-Pressure Xenon Detector

    SciTech Connect (OSTI)

    Seifert, Allen; Milbrath, Brian D.; Pitts, W. K.; Smith, Leon E.

    2005-10-23

    High-pressure xenon (HPXe) detectors have historically been unable to achieve or even approach the theoretically predicted energy resolution, a phenomenon usually attributed to problems with microphonic, vibrational, or acoustic noise. All these noises are expected to have characteristic frequency signatures. We have determined the effects of external acoustic noise signals on the resolution of HPXe spectrometers and implemented a technique to reduce or eliminate the resolution loss caused by external acoustic noise in real time. Using a precision waveform generator as the driver on a 400-watt speaker, we determined the response of a commercial HPXe detector to a variety of constant frequency acoustic noise signals by performing a fast Fourier transform on a buffered detector output signal and noting distortions to the spectral response of the frequency domain. A data acquisition package was developed using the frequency response information to perform real time digital signal noise filtering on each gamma-ray pulse. With external acoustic noise, the measured resolution of HPXe gamma-ray energy spectra was degraded by a factor of 2 to 3. With the noise mitigating data acquisition package the spectroscopic resolution was restored to values comparable to the resolution measured under ideal (non-noisy) conditions.

  12. Implementation of Executive Order 12114 Environmental Effects Abroad of Major Federal Actions: Final Guideline (DOE, 1981)

    Office of Energy Efficiency and Renewable Energy (EERE)

    The Department of Energy hereby adopts final Departmental guidelines implementing Executive Order 12114-Environmental Effecrs Abroad of Major Federal Actions, whic was issued on January 4, 1979.

  13. Institutional Change Process Step 4: Implement an Action Plan...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Graphic showing 5 gears. They progress from Determine Goal ... into action plans (program design), but on-the-ground ... even if they are not top management.) If there is a ...

  14. Mitigation action plan sale of Naval Petroleum Reserve No. 1 (Elk Hills) Kern County, California

    SciTech Connect (OSTI)

    1998-01-01

    Naval Petroleum Reserve No. 1 (NPR-1, also called {open_quotes}Elk Hills{close_quotes}), a Federally-owned oil and gas production field in Kern County, California, was created by an Executive Order issued by President Taft on September 2, 1912. He signed another Executive Order on December 13, 1912, to establish Naval Petroleum Reserve No. 2 (NPR-2), located immediately south of NPR-1 and containing portions of the town of Taft, California. NPR-1 was not developed until the 1973-74 oil embargo demonstrated the nation`s vulnerability to oil supply interruptions. Following the embargo, Congress passed the Naval Petroleum Reserves Production Act of 1976 which directed that the reserve be explored and developed to its fall economic potential at the {open_quotes}maximum efficient rate{close_quotes} (MER) of production. Since Elk Hills began full production in 1976, it has functioned as a commercial operation, with total revenues to the Federal government through FY 1996 of $16.4 billion, compared to total exploration, development and production costs of $3.1 billion. In February 1996, Title 34 of the National Defense Authorization Act for Fiscal Year 1996 (P.L. 104-106), referred to as the Elk Hills Sales Statute, directed the Secretary of Energy to sell NPR-1 by February 10, 1998.The Secretary was also directed to study options for enhancing the value of the other Naval Petroleum and Oil Shale Reserve properties such as NPR-2, located adjacent to NPR-1 in Kern County- Naval Petroleum Reserve No. 3 (NPR-3) located in Natrona County, Wyoming; Naval Oil Shale Reserves No. 1 and No. 3 (NOSR-1 and NOSR-3) located in Garfield County, Colorado; and Naval Oil Shale Reserve No. 2 (NOSR-2) located in Uintah and Carbon Counties, Utah. The purpose of these actions was to remove the Federal government from the inherently non-Federal function of operating commercial oil fields while making sure that the public would obtain the maximum value from the reserves.

  15. Experimental Investigation of the Root Cause Mechanism and Effectiveness of Mitigating Actions for Axial Offset Anomaly in Pressurized Water Reactors

    SciTech Connect (OSTI)

    Said Abdel-Khalik

    2005-07-02

    Axial offset anomaly (AOA) in pressurized water reactors refers to the presence of a significantly larger measured negative axial offset deviation than predicted by core design calculations. The neutron flux depression in the upper half of high-power rods experiencing significant subcooled boiling is believed to be caused by the concentration of boron species within the crud layer formed on the cladding surface. Recent investigations of the root-cause mechanism for AOA [1,2] suggest that boron build-up on the fuel is caused by precipitation of lithium metaborate (LiBO2) within the crud in regions of subcooled boiling. Indirect evidence in support of this hypothesis was inferred from operating experience at Callaway, where lithium return and hide-out were, respectively, observed following power reductions and power increases when AOA was present. However, direct evidence of lithium metaborate precipitation within the crud has, heretofore, not been shown because of its retrograde solubility. To this end, this investigation has been undertaken in order to directly verify or refute the proposed root-cause mechanism of AOA, and examine the effectiveness of possible mitigating actions to limit its impact in high power PWR cores.

  16. MITIGATION ACTION PLAN

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Georgia MITEC Small Business Boot Camp In Georgia October 4, 2016 9:00AM to 3:00PM EDT Atlanta, GA DOE's Clean Energy Manufacturing Initiative (CEMI) is hosting a MITEC Boot Camp in Atlanta, Georgia coordinated through the Manufacturing Impacts Through Energy and Commerce (MITEC) program. This boot camp is designed to help small- to medium-sized enterprises (SMEs) in advanced energy sectors access DOE national lab capabilities and assets; learn about DOE programs targeting SMEs including the

  17. Mitigation Action Plan

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    ... A11 Revegetate disturbed areas as soon as practicable after disturbance. On agricultural ... Contain and dispose of spill cleanup wastes and contaminated soils in accordance with ...

  18. NEPA mitigation and monitoring activities on Army installations

    SciTech Connect (OSTI)

    Reinke, D.C.; Robitaille, P.

    1995-12-01

    The Army National Environmental Policy Act (NEPA) implementation regulation AR 200-2 (Army Regulation) requires only mitigation measures that can reasonably be accompanied as part of a proposed alternative be identified in the NEPA document. Failure of the identified mitigation actions to be executed or to perform as expected leads to a required reevaluation of the project and the significance of its impacts. The USAEC has undertaken a study of mitigation and monitoring actions listed in Army NEPA documents. As part of the USAEC NEPA program the study has outlined three major tasks (1) collection of a significant sample of Army NEPA documents, (2) review environmental documentation management and retention, and (3) review in detail a subsample of documents and follow-up with site visits. Some 242 Army NEPA documents, Environmental Assessments (EA) and Environmental Impact Statements (EIS) were collected and evaluated for mitigation requirements. Ninety seven of the 242 NEPA documents committed to one or more mitigation actions. While a wide array of mitigating activities have been identified in these documents, the four most common are (1) management plans and practices, (2) training actions, (3) revegetation actions, and (4) construction practices. Site visits to selected Army installations showed that mitigation practices were for the most part being done, but were poorly documented. No installation visited had a mitigation monitoring plan in place as required by AR 200-2.

  19. FY 95 engineering work plan for the design reconstitution implementation action plan

    SciTech Connect (OSTI)

    Bigbee, J.D.

    1994-11-09

    Design reconstitution work is to be performed as part of an overall effort to upgrade Configuration Management (CM) at TWRS. WHC policy is to implement a program that is compliant with DOE-STD-1073-93, Guide for Operational Configuration Management Program. DOE-STD-1073 requires an adjunct program for reconstituting design information. WHC-SD-WM-CM-009, Design Reconstitution Program Plan for Waste Tank Farms and 242-A Evaporator of Tank Waste Remediation System, is the TWRS plan for meeting DOE-STD-1073 design reconstitution requirements. The design reconstitution plan is complex requiring significant time and effort for implementation. In order to control costs, and integrate the work into other TWRS activities, a Design Reconstitution Implementation Action Plan (DR IAP) will be developed, and approved by those organizations having ownership or functional interest in this activity.

  20. EIS-0026: Annual Mitigation Report | Department of Energy

    Energy Savers [EERE]

    Annual Mitigation Report EIS-0026: Annual Mitigation Report The Waste Isolation Pilot Plant (WIPP) Mitigation Action Plan was prepared to address commitments made in the RODs for...

  1. DOE and FERC Jointly Submit Implementation Proposal for The National Action Plan on Demand Response to Congress

    Office of Energy Efficiency and Renewable Energy (EERE)

    The U.S. Department of Energy and the Federal Energy Regulatory Commission (FERC) jointly submitted to Congress a required “Implementation Proposal for The National Action Plan on Demand Response.”

  2. National technology needs assessment for the preparation and implementation of climate change action plans

    SciTech Connect (OSTI)

    Berkel, C.W.M. van; Blonk, T.J.; Westra, C.A.

    1996-12-31

    In the United National Framework Convention on Climate Change (FCCC) it is recognised that developed countries have a responsibility in assisting developing countries and countries in economic transition in building a national capacity for the development, acquisition and transfer of Climate-related Technologies (CTs). Such assistance is most likely to be successful once it is tailored to the results of a sound assessment of the country`s development needs and once the results of this assessment have been endorsed by the most important stakeholders in the country. Recent insight in the opportunities and constraints for National (technology) Needs Assessments (NNAs) as planning tool for both capacity building and technology transfer regarding Environmentally Sound Technologies (ESTs) is applied here to propose a participatory Climate Change Action Planning (CCAP) process. This participatory planning process is thought to serve the dual objective of defining a national Climate Change Action Plan (CCAP) while at the same time contributing to the creation of a broad supportive basis for its acceptance and implementation among stakeholders in the developing country.

  3. Mitigation Monitoring and Reporting Program for continued operation of Lawrence Livermore National Laboratory

    SciTech Connect (OSTI)

    Not Available

    1992-08-01

    A Mitigation Monitoring and Reporting Program, required by the California Environmental Quality Act, was developed by UC as part of the Final EIS/EIR process. This document describing the program is a companion to the Final Environmental Impact Statement/Environmental Impact Report (EIS/EIR) for the Continued Operation of Lawrence Livermore National Laboratory (LLNL) and Sandia National Laboratories, Livermore (SNL, Livermore). The Final EIS/EIR analyzes the potential environmental impacts of the proposed action, which for the purposes of NEPA is: continued operation, including near-term (within 5 to 1 0 years) proposed projects, of LLNL and SNL, Livermore. The proposed action for the EIR is the renewal of the contract between DOE and UC for UC`s continued operation and management of LLNL. The Mitigation Monitoring and Reporting Program is for implementing and monitoring progress of measures taken to mitigate the significant impacts of the proposed action. A complete description of the impacts and proposed mitigations is in Section 5 of Volume I of the Final EIS/EIR. This report summarizes the mitigation measures, identifies the responsible party at the Laboratory for implementing the mitigation measure, states when monitoring will be implemented, when the mitigation measure will be in place and monitoring completed, and who will verify that the mitigation measure was implemented.

  4. Model-Predictive Cascade Mitigation in Electric Power Systems With Storage and Renewables-Part I: Theory and Implementation

    SciTech Connect (OSTI)

    Almassalkhi, MR; Hiskens, IA

    2015-01-01

    A novel model predictive control (MPC) scheme is developed for mitigating the effects of severe line-overload disturbances in electrical power systems. A piece-wise linear convex approximation of line losses is employed to model the effect of transmission line power flow on conductor temperatures. Control is achieved through a receding-horizon model predictive control (MPC) strategy which alleviates line temperature overloads and thereby prevents the propagation of outages. The MPC strategy adjusts line flows by rescheduling generation, energy storage and controllable load, while taking into account ramp-rate limits and network limitations. In Part II of this paper, the MPC strategy is illustrated through simulation of the IEEE RTS-96 network, augmented to incorporate energy storage and renewable generation.

  5. EIS-0246: Wildlife Mitigation Program, Idaho, Montana, Nevada, Washington, Oregon

    Broader source: Energy.gov [DOE]

    BPA has decided to adopt the set of prescriptions (goals, strategies, and procedural requirements) identified in the final EIS as “Alternative 6, Balanced Action (BPA’s Preferred Alternative).” This decision will standardize the planning and implementation process, while achieving balance among all decision factors: (1) meeting the biological objectives of wildlife mitigation projects, (2) achievement of cost and administrative efficiency, (3) compliance with all applicable laws and regulations, and (4) protection and improvement of other environmental resources when such actions would support wildlife mitigation.

  6. Bonneville Power Administration Wildlife Mitigation Program : Draft Environmental Impact Statement.

    SciTech Connect (OSTI)

    United States. Bonneville Power Administration.

    1996-08-01

    Bonneville Power Administration (BPA) is responsible for mitigating the loss of wildlife habitat caused by the development of the Federal Columbia River Power System. BPA accomplishes this mitigation by funding projects consistent with those recommended by the Northwest Power Planning Council (Council). The projects are submitted to the Council from Indian Tribes, state agencies, property owners, private conservation groups, and other Federal agencies. Future wildlife mitigation actions with potential environmental impacts are expected to include land acquisition and management, water rights acquisition and management, habitat restoration and enhancement, installation of watering devices, riparian fencing, and similar wildlife conservation actions. BPA needs to ensure that individual wildlife mitigation projects are planned and managed with appropriate consistency across projects, jurisdictions, and ecosystems, as well as across time. BPA proposes to standardize the planning and implementation of individual wildlife mitigation projects funded by BPA. Alternative 1 is the No Action alternative. Five standardizing alternatives are identified to represent the range of possible strategies, goals, and procedural requirements reasonably applicable to BPA-funded projects under a standardized approach to project planning and implementation. All action alternatives are based on a single project planning process designed to resolve site-specific issues in an ecosystem context and to adapt to changing conditions and information.

  7. EIS-0026: Annual Mitigation Report | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    4 Annual Mitigation Report addresses those WIPP Project-related mitigation activities undertaken from the time of submittal of the 1994 Annual Mitigation Report in July 1994 through June 2014. EIS-0026-MAP-2014.pdf (1.05 MB) More Documents & Publications EIS-0026: Annual Mitigation Report EIS-0026: Annual Mitigation Report EIS-0026: Mitigation Action Plan

  8. EA-1679: Mitigation Action Plan

    Office of Energy Efficiency and Renewable Energy (EERE)

    Grand Coulee's Third Powerplant 500-kV Transmission Line Replacement Project, Grant and Okanogon Counties, Washington

  9. EA-1456: Mitigation Action Plan

    Broader source: Energy.gov [DOE]

    Cheyenne-Miracle Mile and Ault-Cheyenne Transmission Line Rebuild Project Carbon, Albany and Laramie Counties, Wyoming and Weld County, Colorado

  10. EA-1736: Mitigation Action Plan

    Broader source: Energy.gov [DOE]

    Expansion of the Sanitary Effluent Reclamation Facility and Environmental Restoration of Reach S-2 of Sandia Canyon at Los Alamos National Laboratory, Los Alamos, Los Alamos, New Mexico

  11. EA-1755: Mitigation Action Plan

    Broader source: Energy.gov [DOE]

    Reconstruction of the South Access Road (CR 802) in Support of the Department of Energy, Waste Isolation Pilot Plant (WIPP) in Eddy County, New Mexico

  12. EA-1617: Mitigation Action Plan

    Office of Energy Efficiency and Renewable Energy (EERE)

    Lovell-Yellowtail and Basin-Lovell Transmission Line Rebuild Project, Big Horn County, Wyoming, Big Horn and Carbon Counties, Montana

  13. EA-1212: Mitigation Action Plan

    Broader source: Energy.gov [DOE]

    Lease of Land for the Development of a Research Park at Los Alamos National Laboratory, Los Alamos, NM

  14. EIS-0380: Mitigation Action Plan

    Office of Energy Efficiency and Renewable Energy (EERE)

    2008 Site-Wide Environmental Impact Statement for the Continued Operation of Los Alamos National Laboratory

  15. Status Update on Action 2a: Implementation Handbook for Activity-level Work Planning and Control

    Broader source: Energy.gov [DOE]

    Slide Presentation by James Winter, NA-00-10. DOE Handbook: Implementing Activity-Level Work Planning & Control at Nuclear Facilities. Project Justification Statement submitted 1-29-13, with focus upon improved implementation of WP&C and activity-level work. Provides the background, project plan, and key elements of a new DOE handbook on implementing activity-level work planning and control at DOE nuclear facilities.

  16. Recommendation 195: Mitigation of Contamination in Bear Creek Burial Grounds

    Broader source: Energy.gov [DOE]

    The ORSSAB requests DOE provide possible remedial actions to mitigate releases of contamination from Bear Creek Burial Grounds.

  17. Technical Assistance to Kansas City Plant: Mitigation of Polychlorinated Biphenyl Discharges

    SciTech Connect (OSTI)

    Looney, B.B.

    2003-04-21

    Soil and storm water discharges from the Department of Energy Kansas City Plant (KCP) contain polychlorinated biphenyls (PCBs) resulting from past spills and discharges. KCP has implemented a range of actions to mitigate the soil contamination and to reduce the measured PCB releases.

  18. Wildlife Protection, Mitigation, and Enhancement Planning Phase II, Dworshak Reservoir, Final Report.

    SciTech Connect (OSTI)

    Hansen, H. Jerome; Martin, Robert C.

    1989-11-01

    The Pacific Northwest Electric Power Planning and Conservation Act of 1980 directed that measures be implemented to protect, mitigate, and enhance fish and wildlife to the extent affected by development and operation of hydropower projects on the Columbia River System. This Act created the Northwest Power Planning Council, which in turn developed the Columbia River Basin Fish and Wildlife Program. This program established a four-part process: wildlife mitigation status reports; wildlife impact assessments; wildlife protection, mitigation, and enhancement plans; and implementation of protection, mitigation, and enhancement projects. This mitigation plan for the Dworshak Reservoir Hydroelectric Facility was developed to fulfill requirements of Sections 1003(b)(2) and (3) of the Columbia River Basin Fish and Wildlife Program. Specific objectives of wildlife protection, mitigation, and enhancement planning for Dworshak Reservoir included: quantify net impacts to target wildlife species affected by hydroelectric development and operation of Dworshak Dam and Reservoir; develop protection, mitigation, and enhancement goals and objectives for the target wildlife species; recommend protection, mitigation, and enhancement actions for the target wildlife species; and coordination of project activities. 46 refs., 4 figs., 31 tabs.

  19. Priority mitigation measures in non-energy sector in Kazakstan

    SciTech Connect (OSTI)

    Mizina, S.V.; Pilifosova, O.V.; Gossen, E.F.

    1996-12-31

    Fulfilling the Commitments on UN FCCC through the U.S. Country Studies Program, Kazakstan has developed the national GHG Inventory, vulnerability and adaptation assessment and estimated the possibility of mitigation measures in certain sectors. Next step is developing National Climate Change Action Plan. That process includes such major steps as setting priorities in mitigation measures and technologies, their comprehensive evaluation, preparation implementation strategies, developing the procedure of incorporation of the National Action Plan into other development plans and programs. This paper presents programs and measures that can reduce GHG emissions in non-energy sector. Measures in land-use change and forestry, agriculture and coal mining are considered. Current situation in non-energy sector of Kazakstan is discussed. The amount of GHG emissions reduction and cost analysis presented in this paper was developed with the use of IPCC recommendations.

  20. The role of the U.S. Clean Coal Technology Program in implementing the objectives of the joint Canada-U.S. acid rain mitigation initiative

    SciTech Connect (OSTI)

    Baldwin, A.L.; Smith, D.N.; Mann, A.W.; McIlvried, H.G.; Russell, D.L. Sr.

    1997-12-31

    The Clean Coal Technology (CCT) Program was initiated by the US Department of Energy (DOE) in part as a response to the 1986 Joint Report of the US and Canadian Special Envoys on Acid Rain, with a particular focus on coal-burning electric power plants. The fist three solicitations of the CCT Program were aimed primarily at mitigating the potential impacts of acid rain. Subsequently, the Clean Air Act Amendments of 1990 established emission reduction targets for SO{sub 2} and No{sub x}, which influenced the goals of the last two CCT Program. This paper provides an overview of the CCT Program and reports the significant results, with emphasis on emissions reduction as well as their impact on ozone formation.

  1. Climate Action Plan | OpenEI Community

    Open Energy Info (EERE)

    actions that the administration believes will mitigate the environmental and economic costs of climate change. Obama's six Climate Action Initiatives: 1. Phasing out Fossil Fuels...

  2. EA-1731: Mitigation Acton Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Plan Walla Walla-Tucannon River Transmission Line Rebuild Project This Mitigation Action Plan (MAP) is part of the Finding of No Significant Impact (FONSI) for the Walla...

  3. Democratic Republic of Congo-Nationally Appropriate Mitigation...

    Open Energy Info (EERE)

    Appropriate Mitigation Actions (NAMAs) in the Congo Basin AgencyCompany Organization Environment Canada, International Institute for Sustainable Development (IISD) Sector...

  4. Mitigation of Vehicle Fast Charge Grid Impacts with Renewables and Energy

    Broader source: Energy.gov (indexed) [DOE]

    Mitigation Action Plan FutureGen 2.0 Project DOE/EIS-0460 U.S. Department of Energy National Energy Technology Laboratory March 2014 DOE/EIS-0460 FUTUREGEN 2.0 PROJECT MITIGATION ACTION PLAN INTENTIONALLY LEFT BLANK DOE/EIS-0460 FUTUREGEN 2.0 PROJECT MITIGATION ACTION PLAN TABLE OF CONTENTS Introduction ................................................................................................................................................... 1 Purpose

  5. Implementation document for northwest boundary system, long-term improvements, interim response action. Volume 1. General. Final report

    SciTech Connect (OSTI)

    1992-01-01

    This IRA is being conducted as part of the IRA process for the RMA. The Long-Term Improvements IRA consist of completion of the short-term improvements IRA and implementation of monitoring program for the entire Northwest Boundary System, with no modification to the existing treatment plant. The implementation of the NWB system long-term improvements IRA is intended to provide monitoring data, construction of additional monitoring wells (including revegetation of areas disturbed during construction), monitoring both treatment plant and aquifer water quality, water-table monitoring, and preparation of a report containing an evaluation of system performance based on quarterly monitoring L-R one year.

  6. Nationally Appropriate Mitigation Actions | Open Energy Information

    Open Energy Info (EERE)

    Topics: GHG inventory, Low emission development planning Resource Type: Publications, Lessons learnedbest practices, Case studiesexamples Website: unfccc.inthomeitems...

  7. Mitigation for the Construction and Operation of Libby Dam, 2004-2005 Annual Report.

    SciTech Connect (OSTI)

    Dunnigan, James; DeShazer, Jay; Garrow, Larry (Montana Department of Fish, Wildlife and Parks, Libby, MT)

    2005-06-01

    ''Mitigation for the Construction and Operation of Libby Dam'' is part of the Northwest Power and Conservation Council's (NPCC) resident fish and wildlife program. The program was mandated by the Northwest Planning Act of 1980, and is responsible for mitigating damages to fish and wildlife caused by hydroelectric development in the Columbia River Basin. The objective of Phase I of the project (1983 through 1987) was to maintain or enhance the Libby Reservoir fishery by quantifying seasonal water levels and developing ecologically sound operational guidelines. The objective of Phase II of the project (1988 through 1996) was to determine the biological effects of reservoir operations combined with biotic changes associated with an aging reservoir. The objectives of Phase III of the project (1996 through present) are to implement habitat enhancement measures to mitigate for dam effects, to provide data for implementation of operational strategies that benefit resident fish, monitor reservoir and river conditions, and monitor mitigation projects for effectiveness. This project completes urgent and high priority mitigation actions as directed by the Kootenai Subbasin Plan. Montana Fish, Wildlife & Parks (MFWP) uses a combination of techniques to collect physical and biological data within the Kootenai River Basin. These data serve several purposes including: the development and refinement of models used in management of water resources and operation of Libby Dam; investigations into the limiting factors of native fish populations, gathering basic life history information, tracking trends in endangered and threatened species, and the assessment of restoration or management activities designed to restore native fishes and their habitats.

  8. Libby Mitigation Program, 2007 Annual Progress Report: Mitigation for the Construction and Operation of Libby Dam.

    SciTech Connect (OSTI)

    Dunnigan, James; DeShazer, J.; Garrow, L.

    2009-05-26

    basin streams and lakes. 'Mitigation for the Construction and Operation of Libby Dam' is part of the Northwest Power and Conservation Council's (NPCC) resident fish and wildlife program. The program was mandated by the Northwest Planning Act of 1980, and is responsible for mitigating damages to fish and wildlife caused by hydroelectric development in the Columbia River Basin. The objective of Phase I of the project (1983 through 1987) was to maintain or enhance the Libby Reservoir fishery by quantifying seasonal water levels and developing ecologically sound operational guidelines. The objective of Phase II of the project (1988 through 1996) was to determine the biological effects of reservoir operations combined with biotic changes associated with an aging reservoir. The objectives of Phase III of the project (1996 through present) are to implement habitat enhancement measures to mitigate for dam effects, to provide data for implementation of operational strategies that benefit resident fish, monitor reservoir and river conditions, and monitor mitigation projects for effectiveness. This project completes urgent and high priority mitigation actions as directed by the Kootenai Subbasin Plan.

  9. A demonstration of the applicability of implementing the enhanced Remedial Action Priority System (RAPS) for environmental releases

    SciTech Connect (OSTI)

    Whelan, G.; Droppo, J.G. Jr.; Strenge, D.L.; Walter, M.B.; Buck, J.W.

    1989-12-01

    The Remedial Action Priority System (RAPS) and the Multimedia Environmental Pollutant Assessment System (MEPAS) were developed to prioritize problems associated with potential releases of hazardous chemical and radioactive materials in a scientific and objective manner based on limited site information. This report documents the model testing efforts of the RAPS/MEPAS methodology for the atmospheric, surface water, groundwater, and exposure components. Comparisons are given of model outputs with measured data at three sites: the US Department of Energy's Mound facility in Ohio and Hanford facility in Washington, and a chromium-cadmium plating site in New York. The results show that the simulated magnitudes, spacial and temporal trends, and distributions of contaminants corresponded well with the measured data. 25 refs., 86 figs., 26 tabs.

  10. Neutralize & Mitigate

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Capabilities » Neutralize & Mitigate Neutralize & Mitigate Scientists are developing technologies designed to mitigate the effects of IEDs, protecting personnel and equipment from the detonation effects of these and other types of explosives. v Protecting personnel and equipment from the detonation effects At Los Alamos, scientists are developing technologies designed to mitigate the effects of IEDs, protecting personnel and equipment from the detonation effects of these and other types

  11. Mitigating Wildland Fires

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Mitigating Wildland Fires Mitigating Wildland Fires Our interactive wildland fire map displays the locations of wildland fire mitigation activities. Contact Environmental Communication & Public Involvement P.O. Box 1663 MS M996 Los Alamos, NM 87545 (505) 667-0216 Email View in Google Maps What we are doing to mitigate wildland fires Recent large wildfires in the area, including the La Mesa Fire (1977), the Dome Fire (1996), the Oso Fire (1998), the Cerro Grande Fire (2000), and the Las

  12. Conclusions drawn from actions implemented within the first stage of the Cracow program of energy conservation and clean fossil fuels

    SciTech Connect (OSTI)

    Bieda, J.; Bardel, J.; Pierce, B.

    1995-12-31

    Since 1992 Brookhaven National Laboratory (BNL) and Pacific Northwest Laboratory (PNL), acting on behalf of the U.S. Department of Energy, executed the first stage of the Cracow Program of Energy Conservation and Clean Fossil Fuels, called also American-Polish Program of Actions for Elimination of Low Emission Sources in Cracow. The main contractor for BNL and PNL was the Cracow Development Office (BRK). The interest in improving the condition of Cracow air results from the fact that the standard for permissible air pollution was exceeded several times in Cracow and especially within the central part of the town. Therefore, air pollution appeared one of the most important problems that faced the municipal authorities. It followed from monitoring investigations that the high level of air pollutant concentration is caused by in-home coal-fired tile stoves operated in winter seasons and by coal- and coke-fired boiler houses simulated mainly in the central part of the town. The results obtained in first stage are presented. This paper is an attempt to formulate conclusions drawn from these works and recommendations with regard to the future policy of the town authorities; selected results are presented to clarify or illustrate the conclusions.

  13. Blue Creek Winter Range : Wildlife Mitigation Project : Final Environmental Assessment.

    SciTech Connect (OSTI)

    United States. Bonneville Power Administration; United States. Bureau of Indian Affairs; Spokane Tribe of the Spokane Reservation, Washington

    1994-11-01

    Bonneville Power Administration (BPA) proposes to fund that portion of the Washington Wildlife Agreement pertaining to the Blue Creek Winter Range Wildlife Mitigation Project (Project) in a cooperative effort with the Spokane Tribe, Upper Columbia United Tribes, and the Bureau of Indian Affairs (BIA). If fully implemented, the proposed action would allow the sponsors to protect and enhance 2,631 habitat units of big game winter range and riparian shrub habitat on 2,185 hectares (5,400 acres) of Spokane Tribal trust lands, and to conduct long term wildlife management activities within the Spokane Indian Reservation project area. This Final Environmental Assessment (EA) examines the potential environmental effects of securing land and conducting wildlife habitat enhancement and long term management activities within the boundaries of the Spokane Indian Reservation. Four proposed activities (habitat protection, habitat enhancement, operation and maintenance, and monitoring and evaluation) are analyzed. The proposed action is intended to meet the need for mitigation of wildlife and wildlife habitat adversely affected by the construction of Grand Coulee Dam and its reservoir.

  14. Wildlife Protection, Mitigation and Enhancement Planning for Grand Coulee Dam, Final Report.

    SciTech Connect (OSTI)

    Creveling, Jennifer

    1986-08-01

    The development and operation of Grand Coulee Dam inundated approximately 70,000 acres of wildlife habitat under the jurisdictions of the Colville Confederated Tribes, the Spokane Tribe, and the State of Washington. Under the provisions of the Pacific Northwest Electric Power Planning and Conservation Act of 1980, this study reviews losses to wildlife and habitat, and proposes mitigation for those losses. Wildlife loss estimates were developed from information available in the literature. Habitat losses and potential habitat gains through mitigation were estimated by a modified Habitat Evaluation Procedure. The mitigation plan proposes (1) acquisition of sufficient land or management rights to land to protect Habitat Units equivalent to those lost (approximately 73,000 acres of land would be required), (2) improvement and management of those lands to obtain and perpetuate target Habitat Units, and (3) protection and enhancement of suitable habitat for bald eagles. Mitigation is presented as four actions to be implemented over a 10-year period. A monitoring program is proposed to monitor mitigation success in terms of Habitat Units and wildlife population trends.

  15. Mitigating Greenhouse Gas Emissions: Voluntary Reporting 1996

    Reports and Publications (EIA)

    1997-01-01

    Presents information on voluntary actions to reduce greenhouse gases or remove such gases from the atmosphere in 1995. It provides an overview of participation in the Voluntary Reporting Program, a perspective on the composition of activities reported, and a review of some key issues in interpreting and evaluating achievements associated with reported emissions mitigation initiatives.

  16. Assessing and Implementing Long-Term Surveillance and Maintenance Requirements for Remediated Sites Under the Formerly Utilized Sites Remedial Action Program

    SciTech Connect (OSTI)

    Clayton, C.; Widdop, M.

    2007-07-01

    The U.S. Department of Energy (DOE) initiated the Formerly Utilized Sites Remedial Action Program (FUSRAP) in 1974 to address concerns about radiological conditions at locations where work was performed for the Manhattan Engineer District and the U.S. Atomic Energy Commission. The DOE Office of Legacy Management (LM) is responsible for 27 FUSRAP sites and will ultimately assume responsibility for more than 50 FUSRAP sites. DOE-LM assumed responsibility for 25 FUSRAP sites in 2004 and began an assessment of site conditions to ensure that complete site knowledge was preserved in DOE records and that the sites are and will remain protective of human health and the environment. For the assessment, site conditions were assumed to be dynamic. Therefore, the most restrictive site exposure scenarios were considered, as well as the implications for disturbing materials to which supplemental limits were applied. If conditions under these possible future scenarios were found to be protective, no use restrictions were needed. However, if future use or exposure scenarios could result in potential unacceptable risk, restrictions on site use were indicated. The assessment relied on access to documentation of site activities, characteristics, remedial action activities, remediated conditions, and land-use restrictions. In addition, an ongoing program of site visits commenced in 2005. DOE-LM assessed the level of knowledge and sought to identify and preserve site information for use by future custodians. DOE-LM has applied lessons learned in site management since 1989, when a formal DOE program was established to implement long-term surveillance and maintenance (LTS and M) activities. Former FUSRAP staff members with the DOE Office of Environmental Management also conveyed lessons learned. We present the assessment process that was used, the application of results, and a framework for evaluating LTS and M requirements for FUSRAP sites. (authors)

  17. Buildings Greenhouse Gas Mitigation Estimator Worksheet | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy Buildings Greenhouse Gas Mitigation Estimator Worksheet Buildings Greenhouse Gas Mitigation Estimator Worksheet Excel tool helps agencies estimate the greenhouse gas (GHG) mitigation reduction from implementing energy efficiency measures across a portfolio of buildings. It is designed to be applied to groups of office buildings. For example, at a program level (regional or site) that can be summarized at the agency level. While the default savings and cost estimates apply to office

  18. Mitigation for the Construction and Operation of Libby Dam, 2003-2004 Annual Report.

    SciTech Connect (OSTI)

    Dunnigan, James; DeShazer, Jay; Garrow, Larry

    2004-06-01

    ''Mitigation for the Construction and Operation of Libby Dam'' is part of the Northwest Power and Conservation Council's (NPCC) resident fish and wildlife program. The program was mandated by the Northwest Planning Act of 1980, and is responsible for mitigating for damages to fish and wildlife caused by hydroelectric development in the Columbia River Basin. The objective of Phase I of the project (1983 through 1987) was to maintain or enhance the Libby Reservoir fishery by quantifying seasonal water levels and developing ecologically sound operational guidelines. The objective of Phase II of the project (1988 through 1996) was to determine the biological effects of reservoir operations combined with biotic changes associated with an aging reservoir. The objectives of Phase III of the project (1996 through present) are to implement habitat enhancement measures to mitigate for dam effects, to provide data for implementation of operational strategies that benefit resident fish, monitor reservoir and river conditions, and monitor mitigation projects for effectiveness. This project completes urgent and high priority mitigation actions as directed by the Kootenai Subbasin Plan. Montana FWP uses a combination of diverse techniques to collect a variety of physical and biological data within the Kootenai River Basin. These data serve several purposes including: the development and refinement of models used in management of water resources and operation of Libby Dam; investigations into the limiting factors of native fish populations, gathering basic life history information, tracking trends in endangered, threatened species, and the assessment of restoration or management activities intended to restore native fishes and their habitats.

  19. NREL: Technology Deployment - Strategy and Implementation Group...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Domestic and international greenhouse gas mitigation and climate change resiliency strategy analysis, decision support, and implementation. Analysis and integration of water and ...

  20. Appropriate Use of Mitigation and Monitoring and Clarifying the Appropriate Use of Mitigated Findings of No Significant Impact (CEQ, 2011)

    Broader source: Energy.gov [DOE]

    The Council on Environmental Quality is issuing this guidance for Federal departments and agencies on establishing, implementing, and monitoring mitigation commitments identified and analyzed in Environmental Assessments, Environmental Impact Statements, and adopted in the final decision documents. This guidance also clarifies the appropriate use of mitigated "Findings of No Significant Impact" under the National Environmental Policy Act (NEPA). The guidance explains the requirements of NEPA and the CEQ Regulations, describes CEQ policies, and recommends procedures for agencies to use to help them comply with the requirements of NEPA and the CEQ Regulations when they establish mitigation planning and implementation procedures

  1. Center for Clean Air Policy (CCAP) | Open Energy Information

    Open Energy Info (EERE)

    in the Cement Sector Mexico-The Mitigation Action Implementation Network (MAIN) Pakistan-The Mitigation Action Implementation Network (MAIN) Panama-The Mitigation Action...

  2. Independent Oversight Activity Report for Review of Corrective Actions for Findings from the Independent Oversight Review of Los Alamos National Laboratory Radiological Controls Activity-Level Implementation - February 12, 2014

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    HSS Independent Activity Report - Rev. 0 Report Number: HIAR LANL-2014-02-12 Site: Los Alamos National Laboratory (LANL) Subject: Office of Enforcement and Oversight's Office of Safety and Emergency Management Evaluations Activity Report for Review of Corrective Actions for Findings from the Independent Oversight Review of LANL Radiological Controls Activity-Level Implementation (Published November 2013) Dates of Activity : 02/12/2014 Report Preparer: Robert Freeman, Nuclear Engineer Activity

  3. Hellsgate Winter Range : Wildlife Mitigation Project. Preliminary Environmental Assessment.

    SciTech Connect (OSTI)

    United States. Bonneville Power Administration.

    1995-01-01

    The Bonneville Power Administration proposes funding the Hellsgate Winter Range Wildlife Mitigation Project in cooperation with the Colville Convederated Tribes and Bureau of Indian Affairs. This Preliminary Environmental Assessment examines the potential environmental effects of acquiring and managing property for wildlife and wildlife habitat within a large project area. The Propose action is intended to meet the need for mitigation of wildlife and wild life habitat that was adversely affected by the construction of Grand Coulee and Chief Joseph Dams and their reservoirs.

  4. Siting and Barrier Mitigation

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Siting and Barrier Mitigation - Sandia Energy Energy Search Icon Sandia Home Locations Contact Us Employee Locator Energy & Climate Secure & Sustainable Energy Future Stationary Power Energy Conversion Efficiency Solar Energy Wind Energy Water Power Supercritical CO2 Geothermal Natural Gas Safety, Security & Resilience of the Energy Infrastructure Energy Storage Nuclear Power & Engineering Grid Modernization Battery Testing Nuclear Energy Defense Waste Management Programs

  5. Energy Agency Coordinators for Energy Action Month

    Broader source: Energy.gov [DOE]

    Agency coordinators serve as primary Federal agency points of contact for Energy Action Month. Contact them if you have questions about implementing an Energy Action Month campaign.

  6. The Climate Change Action Plan: Technical supplement

    SciTech Connect (OSTI)

    Not Available

    1994-03-01

    This Technical Annex documents the assumptions and parameters used in developing the supporting analysis for the Climate Change Action Plan (the Plan) issued by President Clinton on October 19, 1993. The Annex is intended to meet the needs of independent energy and environmental analysts who wish to better understand the Plan, its analytical underpinnings, and the events that need to transpire for the emissions reductions called for in the Plan to be realized. The Plan documented in this Annex reflects the outcome of a wide-ranging effort by Government agencies and interested members of the public to develop and implement actions that can reduce net greenhouse gas emissions in the year 2000 to their aggregate 1990 level. Based on agency and public input, the Climate Change Mitigation Group, chaired by the White House Office on Environmental Policy, developed the Plan`s content. Many of the actions called for in the Plan are now underway, while others are in advanced planning pending congressional action on the fiscal year 1995 budget. The analysis supporting the Plan represents the results of an interagency effort. The US Department of Energy (DOE) was responsible for the integrated analysis of energy-related options, based on the analysis of individual energy-related options by DOE, the US Environmental Protection Agency (EPA), and the US Department of Transportation (DOT). EPA led in providing analysis for actions related to methane, hydrofluorocarbons, and perfluorocarbons. The US Department of Agriculture (USDA) led the analysis of carbon sequestration actions and cooperated with EPA in the analysis of actions to reduce nitrous oxide emissions.

  7. Hungry Horse Dam Fisheries Mitigation, 1992-1993 Progress Report.

    SciTech Connect (OSTI)

    DosSantos, Joe; Vashro, Jim; Lockard, Larry

    1994-06-01

    In February of 1900, over forty agency representatives and interested citizens began development of the 1991 Mitigation Plan. This effort culminated in the 1993 Implementation Plan for mitigation of fish losses attributable to the construction and operation of Hungry Horse Dam. The primary purpose of this biennial report is to inform the public of the status of ongoing mitigation activities resulting from those planning efforts. A habitat improvement project is underway to benefit bull trout in Big Creek in the North Fork drainage of the Flathead River and work is planned in Hay Creek, another North Fork tributary. Bull trout redd counts have been expanded and experimental programs involving genetic evaluation, outmigrant monitoring, and hatchery studies have been initiated, Cutthroat mitigation efforts have focused on habitat improvements in Elliott Creek and Taylor`s Outflow and improvements have been followed by imprint plants of hatchery fish and/or eyed eggs in those streams. Rogers Lake west of Kalispell and Lion Lake, near Hungry Horse, were chemically rehabilitated. Cool and warm water fish habitat has been improved in Halfmoon Lake and Echo Lake. Public education and public interest is important to the future success of mitigation activities. As part of the mitigation team`s public awareness responsibility we have worked with numerous volunteer groups, public agencies, and private landowners to stimulate interest and awareness of mitigation activities and the aquatic ecosystem. The purpose of this biennial report is to foster public awareness of, and support for, mitigation activities as we move forward in implementing the Hungry Horse Dam Fisheries Mitigation Implementation Plan.

  8. Mitigation measures and programs in Hungary

    SciTech Connect (OSTI)

    Molnar, S.

    1996-12-31

    In Hungary there are four main governmental programs, which may result in a decrease of emissions of anthropogenic greenhouse gases (GHGs): (1) National program of energy efficiency improvement and energy conservation, (2) Afforestation program, (3) Volatile organic compounds (VOC) emission reduction program, and (4) Program to reduce the use of ozone depleting substances. These ambitious programs were launched in the beginning of the 90`s, but they have been slowed down because of budgetary problems. The comprehensive action plan for mitigation of GHG emissions should be based on these ongoing programs. These programs should be expanded by further measures and programs in order to fulfill the requirements of the FCCC. In the next sections the results and prospects of the above mentioned programs will be summarized. Also the results of the mitigation study supported by the U.S. Country Studies Program are included.

  9. Plans for Implementing the Columbia River Basin Fish and Wildlife Program in Fiscal Year 1986.

    SciTech Connect (OSTI)

    United States. Bonneville Power Administration

    1985-10-01

    The Fish and Wildlife Program is an effort to enhance, protect, and mitigate losses of those fish and wildlife which have been affected by the development, operation, and management of hydroelectric facilities in the Columbia River Basin. The implementation plan is organized to address the action items assigned to BPA in Section 1500 of the Council's Fish and Wildlife Program (1984). These action items generally relate to one or more specific measures in the Program. The following information is listed for each project: budget summary, projects, obligation plan, and work plan and milestones.

  10. NREL: Climate Neutral Research Campuses - Implementing the Climate...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Implementing the Climate Action Plan When implementing climate action plans on research campuses, two important and related questions must be answered. How do we pay for climate ...

  11. Corrective Action Program Guide

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2006-03-02

    This Guide was developed to assist the Department of Energy (DOE) organizations and contractors in the development, implementation, and followup of corrective action programs utilizing the feedback and improvement core safety function within DOE's Integrated Safety Management System. This Guide outlines some of the basic principles, concepts, and lessons learned that DOE managers and contractors might consider when implementing corrective action programs based on their specific needs. Canceled by DOE G 414.1-2B. Does not cancel other directives.

  12. Buildings GHG Mitigation Estimator Worksheet, Version 1

    Broader source: Energy.gov [DOE]

    Xcel document describes Version 1 of the the Buildings GHG Mitigation Estimator tool. This tool assists federal agencies in estimating the greenhouse gas mitigation reduction from implementing energy efficiency measures across a portfolio of buildings. It is designed to be applied to groups of office buildings, for example, at a program level (regional or site) that can be summarized at the agency level. While the default savings and cost estimates apply to office buildings, users can define their own efficiency measures, costs, and savings estimates for inclusion in the portfolio assessment. More information on user-defined measures can be found in Step 2 of the buildings emission reduction guidance. The output of this tool is a prioritized set of activities that can help the agency to achieve its greenhouse gas reduction targets most cost-effectively.

  13. BIAS MITIGATION | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Diversity and Inclusion » BIAS MITIGATION BIAS MITIGATION BIAS MITIGATION The DOE has focused its efforts on eliminating implicit bias at the individual and institutional levels. At the individual level, the DOE's efforts to eliminate implicit bias include: conflict prevention and resolution; Ombudsman - which promotes the early identification and resolution of issues in order to promote morale and productivity through an informal process; workplace improvement forums; and an anti-harassment

  14. GHG emission mitigation measures and technologies in the Czech Republic

    SciTech Connect (OSTI)

    Tichy, M.

    1996-12-31

    The paper presents a short overview of main results in two fields: projection of GHG emission from energy sector in the Czech Republic and assessment of technologies and options for GHG mitigation. The last part presents an overview of measures that were prepared for potential inclusion to the Czech Climate Change Action Plan.

  15. Implementation of Executive Order 12114 Environmental Effects...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Implementation of Executive Order 12114 Environmental Effects Abroad of Major Federal Actions: Final Guideline (DOE, 1981) Implementation of Executive Order 12114 Environmental ...

  16. Bear Creek Valley Floodplain Hot Spot Removal Action Project Plan, Oak Ridge Y-12 Plant, Oak Ridge, Tennessee

    SciTech Connect (OSTI)

    NONE

    1998-01-01

    The Bear Creek Valley Floodplain Hot Spot Removal Action Project Plan, Oak Ridge Y-12 Plant, Oak Ridge, Tennessee (Y/ER-301) was prepared (1) to safely, cost-effectively, and efficiently evaluate the environmental impact of solid material in the two debris areas in the context of industrial land uses (as defined in the Bear Creek Valley Feasibility Study) to support the Engineering Evaluation/Cost Assessment and (2) to evaluate, define, and implement the actions to mitigate these impacts. This work was performed under Work Breakdown Structure 1.x.01.20.01.08.

  17. Albeni Falls Wildlife Mitigation Project, 2008 Annual Report.

    SciTech Connect (OSTI)

    Soults, Scott

    2009-08-05

    The Albeni Falls Interagency Work Group (AFIWG) was actively involved in implementing wildlife mitigation activities in late 2007, but due to internal conflicts, the AFIWG members has fractionated into a smaller group. Implementation of the monitoring and evaluation program continued across protected lands. As of 2008, The Albeni Falls Interagency Work Group (Work Group) is a coalition comprised of wildlife managers from three tribal entities (Kalispel Tribe, Kootenai Tribe, Coeur d Alene Tribe) and the US Army Corps of Engineers. The Work Group directs where wildlife mitigation implementation occurs in the Kootenai, Pend Oreille and Coeur d Alene subbasins. The Work Group is unique in the Columbia Basin. The Columbia Basin Fish and Wildlife Authority (CBFWA) wildlife managers in 1995, approved what was one of the first two project proposals to implement mitigation on a programmatic basis. The maintenance of this kind of approach through time has allowed the Work Group to implement an effective and responsive habitat protection program by reducing administrative costs associated with site-specific project proposals. The core mitigation entities maintain approximately 9,335 acres of wetland/riparian habitats in 2008.

  18. Preparing for Project Implementation during an Energy Assessment

    Broader source: Energy.gov [DOE]

    This presentation discusses actions to take during the energy assessment to encourage project implementation.

  19. Peaking of world oil production: Impacts, mitigation, & risk management

    SciTech Connect (OSTI)

    Hirsch, R.L.; Bezdek, Roger; Wendling, Robert

    2005-02-01

    The peaking of world oil production presents the U.S. and the world with an unprecedented risk management problem. As peaking is approached, liquid fuel prices and price volatility will increase dramatically, and, without timely mitigation, the economic, social, and political costs will be unprecedented. Viable mitigation options exist on both the supply and demand sides, but to have substantial impact, they must be initiated more than a decade in advance of peaking.... The purpose of this analysis was to identify the critical issues surrounding the occurrence and mitigation of world oil production peaking. We simplified many of the complexities in an effort to provide a transparent analysis. Nevertheless, our study is neither simple nor brief. We recognize that when oil prices escalate dramatically, there will be demand and economic impacts that will alter our simplified assumptions. Consideration of those feedbacks will be a daunting task but one that should be undertaken. Our aim in this study is to-- • Summarize the difficulties of oil production forecasting; • Identify the fundamentals that show why world oil production peaking is such a unique challenge; • Show why mitigation will take a decade or more of intense effort; • Examine the potential economic effects of oil peaking; • Describe what might be accomplished under three example mitigation scenarios. • Stimulate serious discussion of the problem, suggest more definitive studies, and engender interest in timely action to mitigate its impacts.

  20. CORRECTIVE ACTION PLAN FOR CORRECTIVE ACTION UNIT 543: LIQUID DISPOSAL UNITS, NEVADA TEST SITE, NEVADA

    SciTech Connect (OSTI)

    2006-09-01

    The purpose of this Corrective Action Plan is to provide the detailed scope of work required to implement the recommended corrective actions as specified in the approved Corrective Action Decision Document.

  1. Mitigation Monitoring Program at Lawrence Livermore National Laboratory FY00 Annual Report

    SciTech Connect (OSTI)

    Mcguff, R R

    2003-12-01

    Lawrence Livermore National Laboratory (LLNL) has completed eight years of implementing the mitigation measures from the Final Environmental Impact Statement/Environmental Impact Report (EIS/EIR) for the Continued Operation of LLNL and Sandia National Laboratories (SNL), Livermore. This eighth annual report documents LLNL's implementation of the mitigation measures during the fiscal year ending September 30, 2000 (FY00). It provides background information on the mitigation measures, describes activities undertaken during FY00, and documents changes in the monitoring program. Table 1 on page 12, provides a numerical listing of each mitigation measure, the department responsible for implementing it, and the location within this report where the status is discussed. The discussion of the mitigation measures is organized by the University of California (UC)'s three categories of approaches to implementation: project-specific, service-level and administrative. Table 2 on page 19, Table 6 on page 55, and Table 7 on page 63 provide a detailed discussion of each mitigation measure, including LLNL's implementation strategy and the status as of the end of the fiscal year. Table 3 on page 37, Table 4 on page 46, and Table 5 on page 47 list each construction project undertaken in FY00 and the mitigation measures implemented.

  2. Microsoft Word - Final Mitigated Action Plan - CNMI.docx

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... In addition, an initial report will be submitted six months after turbine operations begins. 6 | P a g e Dead Marian swiftlets found under a wind turbine will be collected by ...

  3. EA-1891: Mitigation Action Plan | Department of Energy

    Office of Environmental Management (EM)

    The project would rebuild the aging 97.5-mile-long 230- kilovolt (kV) Alvey-Fairview transmission line in Lane, Douglas, and Coos counties, Oregon. This MAP is for the Proposed ...

  4. EA-1440: Mitigation Action Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Impact for the National Renewable Energy Laboratory's South Table Mountain Complex, DOEEA-1440-S-1 (May 2008) More Documents & Publications EA-1440-S2: Final ...

  5. EIS-0186: Mitigation Action Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Healy Clean Coal Project In response to a Program Opportunity Notice issued in May 1989 by the Department of Energy (DOE) for the third solicitation of the Clean Coal...

  6. EA-1611: Mitigation Action Plan | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    LLC applied to Western Area Power Administration to interconnect a 90-megawatt wind power facility with Western's existing Sterling-Frenchman Creek 115-kV transmission line....

  7. EA-1562-SA-1: Mitigation Action Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    subsequent loss of mature shrub-steppe habitat associated with Phase II build out ... loss of the areal extent of the priority habitat by replacement of the lost habitat value, ...

  8. EA-1870: Mitigation Action Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    could be suitable for production of clean fuels such as substitute natural gas, sulfur-free Fischer-Tropsch diesel, jet fuel, dimethyl ether, and methane. This MAP identifies...

  9. Viresco-Mitigation-Action-Plan12-20-11.pdf

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

  10. EIS-0421: Record of Decision and Mitigation Action Plan | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    FEIS for this project, the Bonneville Power Administration has decided to construct the Big Eddy-Knight Transmission Project in Wasco County, Oregon and Klickitat County,...

  11. EA-1782: Mitigation Action Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    to aid its decision whether to provide funding for the University of Delaware's construction and operation of a 2-megawatt wind turbine adjacent to the University's...

  12. EA-1912: Mitigation Action Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Midway-Benton No. 1 transmission line and approximately 11 miles of the 115-kV Benton-Othello No. 1 transmission line between the existing Midway and Benton Substations, located...

  13. EIS-0409: Mitigation Action Plan | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    Draft Environmental Impact Statement EIS-0409: Final Environmental Impact Statement Successful Field-Scale In Situ Thermal NAPL Remediation at the Young - Rainey STAR Center...

  14. EA-1974: Finding of No Significant Impact and Mitigation Action...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Bonneville Power Administration issued a finding of no significant impact (FONSI) for the proposed restoration of a tidal marsh in the Columbia River Estuary, near Astoria in ...

  15. MITIGATION ACTION PLAN FOR THE PLAINS & EASTERN CLEAN LINE TRANSMISSIO...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... or updated as required, issued by the U.S. Fish and Wildlife Service pursuant to Section 7 ... Recreation; Special Status Wildlife, Fish, Aquatic Invertebrate, and Amphibian ...

  16. Ecofys-Nationally Appropriate Mitigation Actions: Insights from...

    Open Energy Info (EERE)

    Topics: Low emission development planning, Policiesdeployment programs Resource Type: Lessons learnedbest practices Website: www.ecofys.comcompublications...

  17. EA-1592: Mitigation Action Plan | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    NNSA's Kansas City Plant Based on the analysis in the Environmental Assessment prepared for the proposal by the GSA and NNSA, neither the construction nor operation of the selected...

  18. EA-1973: Finding of No Significant Impact and Mitigation Action...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    the project webpage. PDF icon EA-1973-FONSI-MAP-2015 More Documents & Publications EA-1973: Draft Environmental Assessment EA-1901: Finding of No Significant Impact EA-1518: Final

  19. EA-1941: Mitigation Action Plan (MAP) | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    1 Transmission Line. PDF icon EA-1941-MAP-2014.pdf More Documents & Publications EA-1941: Finding of No Significant Impact (FONSI) EA-1941: Final Environmental Assessment EA-1941

  20. EA-1931: Finding of No Significant Impact and Mitigation Action...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Bonneville Power Administration issued a finding of no significant impact and a ... More Documents & Publications EA-1931: Draft Environmental Assessment EA-1931: Final ...

  1. EA-1946: Finding of No Significant Impact and Mitigation Action...

    Broader source: Energy.gov (indexed) [DOE]

    PDF icon EA-1946-FONSI-MAP-2014.pdf More Documents & Publications EA-1946: Draft Environmental Assessment EA-1946: Final Environmental Assessment EIS-0285-SA-140: Supplement ...

  2. Peru-Mitigation Action Plans and Scenarios (MAPS) | Open Energy...

    Open Energy Info (EERE)

    in an effort to build best practice, share tools and research and to create a growing body of knowledge, from a developing country perspective, that is accessible to the...

  3. Argentina-Mitigation Action Plans and Scenarios (MAPS) | Open...

    Open Energy Info (EERE)

    in an effort to build best practice, share tools and research and to create a growing body of knowledge, from a developing country perspective, that is accessible to the...

  4. South Africa-Mitigation Action Plans and Scenarios (MAPS) | Open...

    Open Energy Info (EERE)

    in an effort to build best practice, share tools and research and to create a growing body of knowledge, from a developing country perspective, that is accessible to the...

  5. Brazil-Mitigation Action Plans and Scenarios (MAPS) | Open Energy...

    Open Energy Info (EERE)

    in an effort to build best practice, share tools and research and to create a growing body of knowledge, from a developing country perspective, that is accessible to the...

  6. Chile-Mitigation Action Plans and Scenarios (MAPS) | Open Energy...

    Open Energy Info (EERE)

    in an effort to build best practice, share tools and research and to create a growing body of knowledge, from a developing country perspective, that is accessible to the...

  7. Colombia-Mitigation Action Plans and Scenarios (MAPS) | Open...

    Open Energy Info (EERE)

    in an effort to build best practice, share tools and research and to create a growing body of knowledge, from a developing country perspective, that is accessible to the...

  8. Federal Interagency Wind Turbine Radar Interference Mitigation...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Federal Interagency Wind Turbine Radar Interference Mitigation Strategy Federal Interagency Wind Turbine Radar Interference Mitigation Strategy Cover of the Federal Interagency ...

  9. Technologies for Climate Change Mitigation: Transport Sector...

    Open Energy Info (EERE)

    Technologies for Climate Change Mitigation: Transport Sector Jump to: navigation, search Tool Summary LAUNCH TOOL Name: Technologies for Climate Change Mitigation: Transport Sector...

  10. Unveiling the Implementation Guide

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Oak Ridge National Laboratory www.ornl.gov Unveiling the Implementation Guide October 11, 2011 Michaela Martin Program Manager Residential, Commercial, and Industrial Energy Efficiency Oak Ridge National Laboratory 2 | Oak Ridge National Laboratory www.ornl.gov Guiding Principles for Successfully Implementing Industrial Energy Assessment Recommendations * New resource for industry * Identifies key principles and actions that lead to successful implementation of energy assessment recommendations

  11. UNEP-Facilitating Implementation and Readiness for Mitigation...

    Open Energy Info (EERE)

    focus will be on reducing emissions of greenhouse gases in ways that also contribute to national development goals, such as creating jobs, enhancing energy security, and reducing...

  12. Costa Rica-Facilitating Implementation and Readiness for Mitigation...

    Open Energy Info (EERE)

    six to eight developing countries to strengthen their national low carbon development strategies and get a "quick start" on NAMAs. The focus will be on reducing emissions of...

  13. Morocco-Facilitating Implementation and Readiness for Mitigation...

    Open Energy Info (EERE)

    six to eight developing countries to strengthen their national low carbon development strategies and get a "quick start" on NAMAs. The focus will be on reducing emissions of...

  14. Ghana-Facilitating Implementation and Readiness for Mitigation...

    Open Energy Info (EERE)

    six to eight developing countries to strengthen their national low carbon development strategies and get a "quick start" on NAMAs. The focus will be on reducing emissions of...

  15. Vietnam-Facilitating Implementation and Readiness for Mitigation...

    Open Energy Info (EERE)

    six to eight developing countries to strengthen their national low carbon development strategies and get a "quick start" on NAMAs. The focus will be on reducing emissions of...

  16. South Africa-Facilitating Implementation and Readiness for Mitigation...

    Open Energy Info (EERE)

    six to eight developing countries to strengthen their national low carbon development strategies and get a "quick start" on NAMAs. The focus will be on reducing emissions of...

  17. Indonesia-Facilitating Implementation and Readiness for Mitigation...

    Open Energy Info (EERE)

    six to eight developing countries to strengthen their national low carbon development strategies and get a "quick start" on NAMAs. The focus will be on reducing emissions of...

  18. Mexico-Facilitating Implementation and Readiness for Mitigation...

    Open Energy Info (EERE)

    six to eight developing countries to strengthen their national low carbon development strategies and get a "quick start" on NAMAs. The focus will be on reducing emissions of...

  19. Senegal-Facilitating Implementation and Readiness for Mitigation...

    Open Energy Info (EERE)

    six to eight developing countries to strengthen their national low carbon development strategies and get a "quick start" on NAMAs. The focus will be on reducing emissions of...

  20. Ethiopia-Facilitating Implementation and Readiness for Mitigation...

    Open Energy Info (EERE)

    six to eight developing countries to strengthen their national low carbon development strategies and get a "quick start" on NAMAs. The focus will be on reducing emissions of...

  1. Wildlife mitigation and monitoring report Gunnison, Colorado, site

    SciTech Connect (OSTI)

    1997-04-01

    The Uranium Mill Tailings Remedial Action (UMTRA) Project is administered by the U.S. Department of Energy (DOE); its purpose is to cleanup uranium mill tailings and other contaminated material at 24 UMTRA Project sites in 10 states. This report summarizes the wildlife mitigation and monitoring program under way at the Gunnison UMTRA Project, Gunnison, Colorado. Remedial action at the Gunnison site was completed in December 1995 and is described in detail in the Gunnison completion report. The impacts of this activity were analyzed in the Gunnison environmental assessment (EA). These impacts included two important game species: the pronghorn antelope (Antilocapra americans) and sage grouse (Wentrocerus urophasianus). Haul truck traffic was predicted to limit antelope access to water sources north of the Tenderfoot Mountain haul road and that truck traffic along this and other haul roads could result in antelope road kills. Clearing land at the disposal cell, haul road and borrow site activities, and the associated human activities also were predicted to negatively impact (directly and indirectly) sage grouse breeding, nesting, loafing, and wintering habitat. As a result, an extensive mitigation and monitoring plan began in 1992. Most of the monitoring studies are complete and the results of these studies, written by different authors, appear in numerous reports. This report will: (1) Analyze existing impacts and compare them to predicted impacts. (2) Summarize mitigation measures. (3) Summarize all existing monitoring data in one report. (4) Analyze the effectiveness of the mitigation measures.

  2. Enhanced Separation and Mitigated Plasticization in Membranes...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Enhanced Separation and Mitigated Plasticization in Membranes using Metal-Organic Framework Nanoparticles

  3. U.S. Mayor's Climate Protection Agreement: Climate Action Handbook...

    Open Energy Info (EERE)

    Action Handbook offers examples of actions that local governments can take to reduce global warming emissions and implement the commitments for climate protection called out...

  4. Mitigation Options in Forestry, Land-Use, Change and Biomass Burning in Africa

    SciTech Connect (OSTI)

    Makundi, Willy R.

    1998-06-01

    Mitigation options to reduce greenhouse gas emissions and sequester carbon in land use sectors are describe in some detail. The paper highlights those options in the forestry sector, which are more relevant to different parts of Africa. It briefly outlines a bottom-up methodological framework for comprehensively assessing mitigation options in land use sectors. This method emphasizes the application of end-use demand projections to construct a baseline and mitigation scenarios and explicitly addresses the carbon storage potential on land and in wood products, as well as use of wood to substitute for fossil fuels. Cost-effectiveness indicators for ranking mitigation options are proposed, including those, which account for non-carbon monetary benefits such as those derived from forest products, as well as opportunity cost of pursuing specific mitigation option. The paper finally surveys the likely policies, barriers and incentives to implement such mitigation options in African countries .

  5. Action Items

    Office of Environmental Management (EM)

    ACTION ITEMS Presentation to the DOE High Level Waste Corporate Board July 29, 2009 Kurt Gerdes Office of Waste Processing DOE-EM Office of Engineering & Technology 2 ACTION ITEMS...

  6. ACTION PLAN

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    -1 ACTION PLAN 1.0 INTRODUCTION 1.1 PURPOSE The purpose of this action plan is to establish the overall plan for hazardous waste permitting, meeting closure and postclosure requirements, and remedial action under the Federal Resource Conservation and Recovery Act (RCRA) and Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), and the Washington State Hazardous Waste Management Act. All actions required to be taken pursuant to this Agreement shall be taken in accordance

  7. Blue Creek Winter Range : Wildlife Mitigation Project : Preliminary Environmental Assessment.

    SciTech Connect (OSTI)

    United States. Bonneville Power Administration; United States. Bureau of Indian Affairs; Spokane Tribe of the Spokane Reservation, Washington

    1994-11-01

    This preliminary Environmental Assessment examines the potential environmental effects of securing land and conducting wildlife habitat enhancement and long term management activities within the boundaries of the Spokane Indian Reservation. Four proposed activities are analyzed: Habitat protection; Habitat enhancement; Operation and maintenance; and Monitoring and evaluation. The proposed action is intended to meet the need for mitigation of wildlife and wildlife habitat adversely affected by the construction of Grand Coulee Dam and its reservoir.

  8. Estimating the potential of greenhouse gas mitigation in Kazakhstan

    SciTech Connect (OSTI)

    Monacrovich, E.; Pilifosova, O.; Danchuck, D.

    1996-09-01

    As part of the studies related to the obligations of the UN Framework Convention on Climate Change, the Republic of Kazakhstan started activities to inventory greenhouse gas (GHG) emissions and assess of GHG mitigation options, The objective of this paper is to present an estimate of the possibility of mitigating GHG emissions and determine the mitigation priorities. It presents a compilation of the possible options and their assessment in terms of major criteria and implementation feasibility. Taking into account the structure of GHG emissions in Kazakhstan in 1990, preliminary estimates of the potential for mitigation are presented for eight options for the energy sector and agriculture and forestry sector. The reference scenario prepared by expert assessments assumes a reduction of CO{sub 2} emissions in 1996-1998 by about 26% from the 1990 level due to general economic decline, but then emissions increase. It is estimated that the total potential for the mitigation of CO{sub 2} emissions for the year 2000 is 3% of the CO{sub 2} emissions in the reference scenario. The annual reduction in methane emissions due to the estimated options can amount to 5%-6% of the 1990 level. 10 refs., 1 fig., 4 tabs.

  9. Hungry Horse Mitigation; Flathead Lake, 2003-2004 Annual Report.

    SciTech Connect (OSTI)

    Hansen, Barry; Evarts, Les

    2005-06-01

    The Confederated Salish and Kootenai Tribes (CSKT) and Montana Fish Wildlife and Parks (MFWP) wrote the ''Fisheries Mitigation Plan for Losses Attributable to the Construction and Operation of Hungry Horse Dam'' in March 1991 to define the fisheries losses, mitigation alternatives and recommendations to protect, mitigate and enhance resident fish and aquatic habitat affected by Hungry Horse Dam. On November 12, 1991, the Northwest Power Planning Council (NPPC) approved the mitigation plan with minor modifications, called for a detailed implementation plan, and amended measures 903(h)(1) through (7). A long-term mitigation plan was submitted in August 1992, was approved by the Council in 1993, and the first contract for this project was signed on November 11, 1993. The problem this project addresses is the loss of habitat, both in quality and quantity, in the Flathead Lake and River basin resulting from the construction and operation of Hungry Horse Dam. The purpose of the project is to both implement mitigation measures and monitor the biological responses to those measures including those implemented by Project Numbers 9101903 and 9101904. Goals and objectives of the 1994 Fish and Wildlife Program (Section 10.1) addressed by this project are the rebuilding to sustainable levels weak, but recoverable, native populations injured by the hydropower system. The project mitigates the blockage of spawning runs by Hungry Horse Dam by restoring and even creating spawning habitats within direct drainages to Flathead Lake. The project also addresses the altered habitat within Flathead Lake resulting from species shifts and consequent dominance of new species that restricts the potential success of mitigation measures. Specific goals of this project are to create and restore habitat and quantitatively monitor changes in fish populations to verify the efficacy of our mitigation measures. The project consists of three components: monitoring, restoration and research. Monitoring

  10. Generalized Comprehensive Mitigation Assessment Process (GCOMAP...

    Open Energy Info (EERE)

    Generalized Comprehensive Mitigation Assessment Process (GCOMAP) (Redirected from GCOMAP) Jump to: navigation, search Tool Summary LAUNCH TOOL Name: Generalized Comprehensive...

  11. Generalized Comprehensive Mitigation Assessment Process (GCOMAP...

    Open Energy Info (EERE)

    search Tool Summary LAUNCH TOOL Name: Generalized Comprehensive Mitigation Assessment Process (GCOMAP) AgencyCompany Organization: Lawrence Berkeley National Laboratory...

  12. American Samoa Energy Action Plan

    SciTech Connect (OSTI)

    Haase, Scott; Esterly, Sean; Herdrich, David; Bodell, Tim; Visser, Charles

    2013-08-01

    Describes the five near-term strategies selected by the American Samoa Renewable Energy Committee (ASREC) during action planning workshops conducted in May 2013, and outlines the actions being taken to implement those strategies. Each option is tied to a priority identified in the earlier draft American Samoa Strategic Energy Plan as being an essential component of reducing American Samoa'spetroleum energy consumption. The actions described for each strategy provide a roadmap to facilitate the implementation of each strategy. This document is intended to evolve along with the advancement of the projects, and will be updated to reflect progress.

  13. A greenhouse-gas information system monitoring and validating emissions reporting and mitigation

    SciTech Connect (OSTI)

    Jonietz, Karl K; Dimotakis, Paul E; Walker, Bruce C

    2011-09-26

    Current GHG-mitigating regimes, whether internationally agreed or self-imposed, rely on the aggregation of self-reported data, with limited checks for consistency and accuracy, for monitoring. As nations commit to more stringent GHG emissions-mitigation actions and as economic rewards or penalties are attached to emission levels, self-reported data will require independent confirmation that they are accurate and reliable, if they are to provide the basis for critical choices and actions that may be required. Supporting emissions-mitigation efforts and agreements, as well as monitoring energy- and fossil-fuel intensive national and global activities would be best achieved by a process of: (1) monitoring of emissions and emission-mitigation actions, based, in part, on, (2) (self-) reporting of pertinent bottom-up inventory data, (3) verification that reported data derive from and are consistent with agreed-upon processes and procedures, and (4) validation that reported emissions and emissions-mitigation action data are correct, based on independent measurements (top-down) derived from a suite of sensors in space, air, land, and, possibly, sea, used to deduce and attribute anthropogenic emissions. These data would be assessed and used to deduce and attribute measured GHG concentrations to anthropogenic emissions, attributed geographically and, to the extent possible, by economic sector. The validation element is needed to provide independent assurance that emissions are in accord with reported values, and should be considered as an important addition to the accepted MRV process, leading to a MRV&V process. This study and report focus on attributes of a greenhouse-gas information system (GHGIS) needed to support MRV&V needs. These needs set the function of such a system apart from scientific/research monitoring of GHGs and carbon-cycle systems, and include (not exclusively): the need for a GHGIS that is operational, as required for decision-support; the need for a

  14. EIS-0026: 2009 Annual Mitigation Report | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    Annual Mitigation Report (AMR) addresses those WIPP-related mitigation activities undertaken from the time of submittal of the 1994 Annual Mitigation Report in July 1994 through...

  15. EIS-0026: Annual Mitigation Report | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    Annual Mitigation Report addresses those WIPP Project-related mitigation activities undertaken from the time of submittal of the 1994 Annual Mitigation Report in July 1994 through...

  16. EIS-0026: Annual Mitigation Report | Department of Energy

    Office of Environmental Management (EM)

    7 Annual Mitigation Report (2007 AMR) addresses those WIPP- related mitigation activities undertaken from the time of submittal of the 1994 Annual Mitigation Report in July 1994...

  17. EIS-0026: Annual Mitigation Report | Department of Energy

    Office of Environmental Management (EM)

    8 Annual Mitigation Report (AMR) addresses those WIPP-related mitigation activities undertaken from the time of submittal of the 1994 Annual Mitigation Report in July 1994 through...

  18. Appropriate Use of Mitigation and Monitoring and Clarifying the...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Appropriate Use of Mitigation and Monitoring and Clarifying the Appropriate Use of Mitigated Findings of No Significant Impact Appropriate Use of Mitigation and Monitoring and ...

  19. Greenhouse gas mitigation options for Washington State

    SciTech Connect (OSTI)

    Garcia, N.

    1996-04-01

    President Clinton, in 1993, established a goal for the United States to return emissions of greenhouse gases to 1990 levels by the year 2000. One effort established to help meet this goal was a three part Environmental Protection Agency state grant program. Washington State completed part one of this program with the release of the 1990 greenhouse gas emissions inventory and 2010 projected inventory. This document completes part two by detailing alternative greenhouse gas mitigation options. In part three of the program EPA, working in partnership with the States, may help fund innovative greenhouse gas reduction strategies. The greenhouse gas control options analyzed in this report have a wide range of greenhouse gas reductions, costs, and implementation requirements. In order to select and implement a prudent mix of control strategies, policy makers need to have some notion of the potential change in climate, the consequences of that change and the uncertainties contained therein. By understanding the risks of climate change, policy makers can better balance the use of scarce public resources for concerns that are immediate and present against those that affect future generations. Therefore, prior to analyzing alternative greenhouse gas control measures, this report briefly describes the phenomenon and uncertainties of global climate change, and then projects the likely consequences for Washington state.

  20. Mitigation of Syngas Cooler Plugging and Fouling

    SciTech Connect (OSTI)

    Bockelie, Michael J.

    2015-06-29

    This Final Report summarizes research performed to develop a technology to mitigate the plugging and fouling that occurs in the syngas cooler used in many Integrated Gasification Combined Cycle (IGCC) plants. The syngas cooler is a firetube heat exchanger located downstream of the gasifier. It offers high thermal efficiency, but its’ reliability has generally been lower than other process equipment in the gasification island. The buildup of ash deposits that form on the fireside surfaces in the syngas cooler (i.e., fouling) lead to reduced equipment life and increased maintenance costs. Our approach to address this problem is that fouling of the syngas cooler cannot be eliminated, but it can be better managed. The research program was funded by DOE using two budget periods: Budget Period 1 (BP1) and Budget Period 2 (BP2). The project used a combination of laboratory scale experiments, analysis of syngas cooler deposits, modeling and guidance from industry to develop a better understanding of fouling mechanisms and to develop and evaluate strategies to mitigate syngas cooler fouling and thereby improve syngas cooler performance. The work effort in BP 1 and BP 2 focused on developing a better understanding of the mechanisms that lead to syngas cooler plugging and fouling and investigating promising concepts to mitigate syngas cooler plugging and fouling. The work effort focused on the following: • analysis of syngas cooler deposits and fuels provided by an IGCC plant collaborating with this project; • performing Jet cleaning tests in the University of Utah Laminar Entrained Flow Reactor to determine the bond strength between an ash deposit to a metal plate, as well as implementing planned equipment modifications to the University of Utah Laminar Entrained Flow Reactor and the one ton per day, pressurized Pilot Scale Gasifier; • performing Computational Fluid Dynamic modeling of industrially relevant syngas cooler configurations to develop a better

  1. Guide for the Mitigation of Natural Phenomena Hazards for DOE Nuclear Facilities and NonNuclear Facilities

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2000-03-28

    This document provides guidance in implementing the Natural Phenomena Hazard (NPH) mitigation requirements of DOE O 420.1, Facility Safety, Section 4.4, "Natural Phenomena Hazards Mitigation." This Guide does not establish or invoke any new requirements. Any apparent conflicts arising from the NPH guidance would defer to the requirements in DOE O 420.1. No cancellation.

  2. White House Highlights Climate Action Champions' Achievements

    Broader source: Energy.gov [DOE]

    After a competitive application process, the Department of Energy designated 16 communities as Climate Action Champions, including two tribes: the Sault Ste. Marie Tribe of Chippewa Indians (Michigan) and the Blue Lake Rancheria Tribe (California). These tribes were selected for their local leadership in climate mitigation and adaptation.

  3. Mitigation for the Construction and Operation of Libby Dam, 2000 Annual Report.

    SciTech Connect (OSTI)

    Hoffman, Greg; Marotz, Brian L.; Dunnigan, James

    2002-09-01

    ''Mitigation for the Construction and Operation of Libby Dam'' is part of the Northwest Power Planning Council's resident fish and wildlife program. The program was mandated by the Northwest Planning Act of 1980, and is responsible for mitigating for damages to fish and wildlife caused by hydroelectric development in the Columbia River Basin. The objective of Phase I of the project (1983 through 1987) was to maintain or enhance the Libby Reservoir fishery by quantifying seasonal water levels and developing ecologically sound operational guidelines. The objective of Phase II of the project (1988 through 1996) was to determine the biological effects of reservoir operations combined with biotic changes associated with an aging reservoir. The objectives of Phase III of the project (1996 through present) are to implement habitat enhancement measures to mitigate for dam effects, to provide data for implementation of operational strategies that benefit resident fish, monitor reservoir and river conditions, and monitor mitigation projects for effectiveness.

  4. Fiscal Year 2015 Annual Environmental Justice Implementation...

    Energy Savers [EERE]

    Fiscal Year 2015 Annual Environmental Justice Implementation Progress Report Fiscal Year 2015 Annual Environmental ... More Documents & Publications Draft FY 2016-2018 Action Agenda ...

  5. Corrective Action

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    of Corrective Action Complete is demonstrated by one of the following: Eliminate Exposure (11 SMAs, 16 Sites) SMA SITE Submittal Date Document 2M-SMA-2.2 03-003(k) September...

  6. Unconventional Nuclear Warfare Defense (UNWD) containment and mitigation subtask.

    SciTech Connect (OSTI)

    Wente, William Baker

    2005-06-01

    The objective of this subtask of the Unconventional Nuclear Warfare Design project was to demonstrate mitigation technologies for radiological material dispersal and to assist planners with incorporation of the technologies into a concept of operations. The High Consequence Assessment and Technology department at Sandia National Laboratories (SNL) has studied aqueous foam's ability to mitigate the effects of an explosively disseminated radiological dispersal device (RDD). These benefits include particle capture of respirable radiological particles, attenuation of blast overpressure, and reduction of plume buoyancy. To better convey the aqueous foam attributes, SNL conducted a study using the Explosive Release Atmospheric Dispersion model, comparing the effects of a mitigated and unmitigated explosive RDD release. Results from this study compared health effects and land contamination between the two scenarios in terms of distances of effect, population exposure, and remediation costs. Incorporating aqueous foam technology, SNL created a conceptual design for a stationary containment area to be located at a facility entrance with equipment that could minimize the effects from the detonation of a vehicle transported RDD. The containment design was evaluated against several criteria, including mitigation ability (both respirable and large fragment particle capture as well as blast overpressure suppression), speed of implementation, cost, simplicity, and required space. A mock-up of the conceptual idea was constructed at SNL's 9920 explosive test site to demonstrate the containment design.

  7. Albeni Falls Wildlife Mitigation Project; Idaho Department of Fish and Game 2007 Final Annual Report.

    SciTech Connect (OSTI)

    Cousins, Katherine

    2009-04-03

    The Idaho Department of Fish and Game maintained a total of about 2,743 acres of wildlife mitigation habitat in 2007, and protected another 921 acres. The total wildlife habitat mitigation debt has been reduced by approximately two percent (598.22 HU) through the Department's mitigation activities in 2007. Implementation of the vegetative monitoring and evaluation program continued across protected lands. For the next funding cycle, the IDFG is considering a package of restoration projects and habitat improvements, conservation easements, and land acquisitions in the project area.

  8. Hungry Horse Mitigation Plan; Fisheries Mitigation Plan for Losses Attributable to the Construction and Operation of Hungry Horse Dam, 1990-2003 Technical Report.

    SciTech Connect (OSTI)

    Fraley, John J.; Marotz, Brian L.; DosSantos, Joseph M.

    2003-04-01

    In this document we present fisheries losses, mitigation alternatives, and recommendations to protect, mitigate, and enhance resident fish and aquatic habitat affected by the construction and operation of Hungry Horse Dam. This plan addresses six separate program measures in the 1987 Columbia Basin Fish and Wildlife Program. We designed the plan to be closely coordinated in terms of dam operations, funding, and activities with the Kerr Mitigation Plan presently before the Federal Energy Regulatory Commission. This document represents a mitigation plan for consideration by the Northwest Power Planning Council process; it is not an implementation plan. Flathead Lake is one of the cleanest lakes of its size in the world. The exceptional water quality and unique native fisheries make the Flathead Lake/River system extremely valuable to the economy and quality of life in the basin. The recreational fishery in Flathead Lake has an estimated value of nearly eight million dollars annually. This mitigation process represents our best opportunity to reduce the impacts of hydropower in this valuable aquatic system and increase angling opportunity. We based loss estimates and mitigation alternatives on an extensive data base, agency reports, nationally and internationally peer-reviewed scientific articles, and an innovative biological model for Hungry Horse Reservoir and the Flathead River. We conducted an extensive, 14-month scoping and consultation process with agency representatives, representatives of citizen groups, and the general public. This consultation process helped identify issues, areas of agreement, areas of conflict, and advantages and disadvantages of mitigation alternatives. The results of the scoping and consultation process helped shape our mitigation plan. Our recommended plan is based firmly on principles of adaptive management and recognition of biological uncertainty. After we receive direction from the NPPC, we will add more detailed hypotheses and

  9. EIS-0026: Annual Mitigation Report | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    6 Annual Mitigation Report addresses those WIPP Project-related mitigation activities undertaken since time of submittal of the 1994 Annual Mitigation Report in July 1994 through June 2016. Download Document EIS-0026: Annual Mitigation Report - 2016 (139.49 KB) More Documents & Publications EIS-0026: Annual Mitigation Report EIS-0026: Annual Mitigation Report EIS-0026: 2010

  10. EIS-0026: Annual Mitigation Report | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    5 Annual Mitigation Report addresses those WIPP Project-related mitigation activities undertaken since time of submittal of the 1994 Annual Mitigation Report in July 1994 through June 2015. EIS-0026: Annual Mitigation Report - 2015 (133.54 KB) More Documents & Publications EIS-0026: Annual Mitigation Report EIS-0026: Annual Mitigation Report EIS-0026:

  11. National climate change action plans: Interim report for developing and transition countries

    SciTech Connect (OSTI)

    Benioff, R.; Ness, E.; Hirst, J.

    1997-10-01

    Under its Support for National Action Plans (SNAP) initiative, the U.S. Country Studies Program is providing financial and technical assistance to 18 countries for the development of climate change action plans. Although most of the countries have not yet completed their plans, the important lessons learned thus far are valuable and should be shared with other countries and international institutions that have an interest in the process of action plan development. This interim report describes the experience of 11 countries that are the furthest along in their planning activity and who have offered to share their results to date with the larger community of interested nations. These action plans delineate specific mitigation and adaptation measures that the countries will implement and integrate into their ongoing development programs. This report focuses on the measures the countries have selected and the methods they used to prepare their action plans. This executive summary presents key lessons and common themes using a structure similar to that used in the individual country chapters.

  12. L-325 Sagebrush Habitat Mitigation Project: Final Compensation Area Monitoring Report

    SciTech Connect (OSTI)

    Durham, Robin E.; Becker, James M.

    2013-09-26

    This document provides a review and status of activities conducted in support of the Fluor Daniel Hanford Company (Fluor), now Mission Support Alliance (MSA), Mitigation Action Plan (MAP) for Project L-325, Electrical Utility Upgrades (2007). Three plantings have been installed on a 4.5-hectare mitigation area to date. This review provides a description and chronology of events, monitoring results, and mitigative actions through fiscal year (FY) 2012. Also provided is a review of the monitoring methods, transect layout, and FY 2012 monitoring activities and results for all planting years. Planting densities and performance criteria stipulated in the MAP were aimed at a desired future condition (DFC) of 10 percent mature sagebrush (Artemisia tridentata ssp wyomingensis) cover. Current recommendations for yielding this DFC are based upon a conceptual model planting of 1000 plants/ha (400/ac) exhibiting a 60-percent survival rate after 5 monitoring years (DOE 2003). Accordingly, a DFC after 5 monitoring years would not be less than 600 plants/ha (240/ac). To date, about 8700 sagebrush plants have been grown and transplanted onto the mitigation site. Harsh site conditions and low seedling survival have resulted in an estimated 489 transplants/ha on the mitigation site, which is 111 plants/ha short of the target DFC. Despite this apparent shortcoming, 71, 91, and 24 percent of the surviving seedlings planted in FY 2007 and FY 2008 and FY 2010, respectively, showed signs of blooming in FY 2012. Blooming status may be a positive indication of future sagebrush recruitment, and is therefore a potential source for reaching the target DFC of 600 plants/ha on this mitigation site over time. Because of the difficulty establishing small transplants on this site, we propose that no additional plantings be considered for this mitigation area and to rely upon the potential recruitment by established seedlings to achieve the mitigation commitment set forth in the MAP of 600 plants/ha.

  13. Environmental Mitigation Technology (Innovative System Testing...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Fish-Friendly Turbine Environmental Mitigation Technology (Innovative System Testing)-Deployment and Testing of the Alden Hydropower Fish-Friendly Turbine Environmental ...

  14. Federal Interagency Wind Turbine Radar Interference Mitigation...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Interagency Wind Turbine Radar Interference Mitigation Strategy January 2016 This report ... First, the authors would like to thank the entire Wind Turbine Radar Interference Working ...

  15. Implantation, Activation, Characterization and Prevention/Mitigation...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    of Internal Short Circuits in Lithium-Ion Cells Implantation, Activation, Characterization and PreventionMitigation of Internal Short Circuits in Lithium-Ion Cells 2012 ...

  16. Federal Interagency Wind Turbine Radar Interference Mitigation...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Interagency Wind Turbine Radar Interference Mitigation Strategy January 2016 This report ... from the advice and comments of two wind industry and trade association ...

  17. Advanced Technology Development and Mitigation | National Nuclear...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    The Advanced Technology Development and Mitigation (ATDM) subprogram includes laboratory code and computer engineering and science projects that pursue long-term simulation and ...

  18. Level maintenance for Tank 101-SY mitigation-by-mixing test

    SciTech Connect (OSTI)

    Sobocinski, R.G.

    1994-11-16

    This document provides the procedure to be followed to implement the requirements of the Mixer Pump Long-Term Operations Plan for Tank 241-SY-101 Mitigation, WHC-SD-WM-PLN-081. The test is divided into 2 distinct sequences, named Single Position Pump Run and Tank Sweep. Instructions for all sequences are defined within the procedure. All safety requirements as defined in LA-UR-92-3196, A Safety Assessment for Proposed Mixing Operations to Mitigate Episodic Gas Releases in Tank 241-101-SY have been implemented into this procedure.

  19. Defining the no action alternative for NEPA document of continuing actions

    SciTech Connect (OSTI)

    McCold, L.N.; Saulsbury, J.W.

    1995-12-01

    Environmental professionals today must address many issues that might not have been foreseen by developers of the National Environmental Policy Act of 1969 (NEPA) or the President`s Council on Environmental Quality (CEQ) regulations for implementing NEPA. One issue is the definition of the no action alternative for NEPA documentation of continuing actions. The CEQ regulations do not define the no action alternative, but merely state that NEPA analyses shall {open_quotes}include the alternative of no action{close_quotes}. For NEPA analyses of newly proposed actions, the practical definition of the no action alternative is clear (i.e., the agency will not implement the proposed action or alternative actions). However, the practical definition for NEPA analyses of continuing actions is not so clear. To clarify the definition of the no action alternative for continuing actions, particularly those that involve agency decisions about relicensing existing projects or continuing to operate existing programs or facilities. In trying to clarify the definition of the no action alternative for continuing actions, this paper examines the function of the no action alternative for NEPA analyses in general. Pertinent issues include how the definition of the no action alternative affects the selection of the baseline for environmental analysis and whether inclusion of the no action alternative really forces agencies to consider no action as a realistic alternative. To address these issues, this paper begins with a discussion of relevant legal decisions involving the no action alternative in NEPA analyses. The paper then examines some agency NEPA regulations and recent NEPA documents to provide examples of how some agencies address the no action alternative for continuing actions. Finally, the paper suggests definitions of the no action alternative for continuing actions and methods for addressing no action as a realistic alternative.

  20. Hellsgate Winter Range : Wildlife Mitigation Project. Final Environmental Assessment.

    SciTech Connect (OSTI)

    United States. Bonneville Power Administration.

    1995-03-01

    Bonneville Power Administration (BPA) proposes to fund the Hellsgate Winter Range Wildlife Mitigation Project (Project) in a cooperative effort with the Colville Confederated Tribes and the Bureau of Indian Affairs (BIA). The proposed action would allow the sponsors to secure property and conduct wildlife management activities within the boundaries of the Colville Indian Reservation. This Final Environmental Assessment (EA) examines the potential environmental effects of acquiring and managing property for wildlife and wildlife habitat within a large project area. This area consists of several separated land parcels, of which 2,000 hectares (4,943 acres) have been purchased by BPA and an additional 4,640 hectares (11,466 acres) have been identified by the Colville Confederated Tribes for inclusion in the Project. Four proposed activities (habitat protection, habitat enhancement, operation and maintenance, and monitoring and evaluation) are analyzed. The proposed action is intended to meet the need for mitigation of wildlife and wildlife habitat that was adversely affected by the construction of Grand Coulee and Chief Joseph Dams and their reservoirs.

  1. Mitigation Measures for Distributed PV Interconnection

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Mitigation Measures for Distributed Interconnection" Michael Coddington with National Renewable Energy Laboratory and Robert Broderick with Sandia National Laboratories July 9, 2014 2 Speakers Michael Coddington Principal Investigator Distributed Grid Integration NREL Robert Broderick Technical Lead Distributed Grid Integration Programs Sandia National Laboratories Kristen Ardani Solar Analyst, (today's moderator) NREL 3 INTERCONNECTION, SCREENING & MITIGATION PRACTICES OF 21 UTILITIES

  2. Mitigation assessment results and priorities in China

    SciTech Connect (OSTI)

    Wu Zongxin; Wei Zhihong

    1996-12-31

    In this paper energy related CO2 emission projections of China by 2030 are given. CO2 mitigation potential and technology options in main fields of energy conservation and energy substitution are analyzed. CO2 reduction costs of main mitigation technologies are estimated and the AHP approach is used for helping assessment of priority technologies.

  3. Business Case for Energy Efficiency in Support of Climate Change Mitigation, Economic and Societal Benefits in the United States

    SciTech Connect (OSTI)

    Bojda, Nicholas; Ke, Jing; de la Rue du Can, Stephane; E. Letschert, Virginie; E. McMahon, James; McNeil, Michael A.

    2011-06-01

    This study seeks to provide policymakers and other stakeholders with actionable information towards a road map for reducing energy consumption in the most cost-effective way. A major difference between the current study and some others is that we focus on individual equipment types that might be the subject of policies - such as labels, energy performance standards, and incentives - to affect market transformation in the short term, and on high-efficiency technology options that are available today. The approach of the study is to assess the impact of short-term actions on long-term impacts. “Short term” market transformation is assumed to occur by 2015, while “long-term” energy demand reduction impacts are assessed in 2030. In the intervening years, most but not all of the equipment studied will turn over completely. The 15-year time frame is significant for many products however, indicating that delay of implementation postpones impacts such as net economic savings and mitigation of emissions of carbon dioxide. Such delays would result in putting in place energy-wasting technologies, postponing improvement until the end of their service life, or potentially resulting in expensive investment either in additional energy supplies or in early replacement to achieve future energy or emissions reduction targets.

  4. Corrective Action Plan for Corrective Action Unit 424: Area 3 Landfill Complex, Tonopah Test Range, Nevada

    SciTech Connect (OSTI)

    Bechtel Nevada

    1998-08-31

    This corrective action plan provides the closure implementation methods for the Area 3 Landfill Complex, Corrective Action Unit (CAU) 424, located at the Tonopah Test Range. The Area 3 Landfill Complex consists of 8 landfill sites, each designated as a separate corrective action site.

  5. Comprehensive mitigation assessment process (COMAP) - Description and instruction manual

    SciTech Connect (OSTI)

    Makundi, Willy; Sathaye, Jayant

    2001-11-09

    In order to prepare policies and plans to reduce GHG emissions, national policy-makers need information on the costs and benefits of different mitigation options in addition to their carbon implications. Policy-makers must weigh the costs, benefits, and impacts of climate change mitigation and adaptation options, in the face of competition for limited resources. The policy goal for mitigation options in the land use sector is to identify which mix of options is likely to best achieve the desired forestry service and production objectives at the least cost, while attempting to maximize economic and social benefits, and minimize negative environmental and social impacts. Improved national-level cost estimates of response options in the land use sector can be generated by estimating the costs and benefits of different forest management practices appropriate for specific country conditions which can be undertaken within the constraint of land availability and its opportunity cost. These co st and land use estimates can be combined to develop cost curves, which would assist policy-makers in constructing policies and programs to implement forest responses.

  6. Implementation Manual

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Skip navigation links BPA Energy Efficiency Plan BPA Post-2011 EE Role Implementation Manual Archives IM Document Library Interim Solution 2.0 Files Low Income Efficiency...

  7. U.S. Postal Service radon assessment and mitigation program. Progress report, September 1993--November 1994

    SciTech Connect (OSTI)

    Velazquez, L.E.; Petty, J.L. Jr.

    1994-12-31

    In 1992, the US Postal Service (USPS) entered into an Interagency Agreement with the Department of Energy (DOE) whereby DOE would provide technical assistance in support of the USPS Radon Assessment and Mitigation Program. To aid in this effort, DOE tasked the Hazardous Waste Remedial Actions Program (HAZWRAP), which is managed by Martin Marietta Energy Systems, Inc., for DOE under contract AC05-84OR21400. Since that time, HAZWRAP has developed and finalized the sampling protocol, mitigation diagnostic protocol, and the quality assurance and quality control procedures. These procedures were validated during the Protocol Validation (1992-1993) and Pilot Study (1993-1994) phases of the program. To date, HAZWRAP has performed approximately 16,000 radon measurements in 250 USPS buildings. Mitigation diagnostics have been performed in 27 buildings. Thus far, 13% of the measurements have been above the Environmental Protection Agency action level of 4 pCi/L. This report summarizes the pilot program radon testing data and mitigation diagnostic data for 22 sites and contains recommendations for mitigation diagnostics.

  8. A wedge-based approach to estimating health co-benefits of climate change mitigation activities in the United States

    SciTech Connect (OSTI)

    Balbus, John M.; Greenblatt, Jeffery B.; Chari, Ramya; Millstein, Dev; Ebi, Kristie L.

    2015-02-01

    While it has been recognized that actions reducing greenhouse gas (GHG) emissions can have significant positive and negative impacts on human health through reductions in ambient fine particulate matter (PM2.5) concentrations, these impacts are rarely taken into account when analyzing specific policies. This study presents a new framework for estimating the change in health outcomes resulting from implementation of specific carbon dioxide (CO2) reduction activities, allowing comparison of different sectors and options for climate mitigation activities. Our estimates suggest that in the year 2020, the reductions in adverse health outcomes from lessened exposure to PM2.5 would yield economic benefits in the range of $6 to $14 billion (in 2008 USD), depending on the specific activity. This equates to between $40 and $93 per metric ton of CO2 in health benefits. Specific climate interventions will vary in the health co-benefits they provide as well as in potential harms that may result from their implementation. Rigorous assessment of these health impacts is essential for guiding policy decisions as efforts to reduce GHG emissions increase in scope and intensity.

  9. Corrective Action Decision Document/Corrective Action Plan for Corrective Action Unit 447: Project Shoal Area, Subsurface, Nevada, Rev. No.: 3 with Errata Sheet

    SciTech Connect (OSTI)

    Tim Echelard

    2006-03-01

    of Energy (DOE) determined that the degree of uncertainty in transport predictions for PSA remained unacceptably large. As a result, a second CAIP was developed by DOE and approved by the Nevada Division of Environmental Protection (NDEP) in December 1998 (DOE/NV, 1998a). This plan prescribed a rigorous analysis of uncertainty in the Shoal model and quantification of methods of reducing uncertainty through data collection. This analysis is termed a Data Decision Analysis (Pohll et al., 1999a) and formed the basis for a second major characterization effort at PSA (Pohll et al., 1999b). The details for this second field effort are presented in an Addendum to the CAIP, which was approved by NDEP in April 1999 (DOE/NV, 1999a). Four additional characterization wells were drilled at PSA during summer and fall of 1999; details of the drilling and well installation are in IT Corporation (2000), with testing reported in Mihevc et al. (2000). A key component of the second field program was a tracer test between two of the new wells (Carroll et al., 2000; Reimus et al., 2003). Based on the potential exposure pathways, two corrective action objectives were identified for CAU 447: Prevent or mitigate exposure to groundwater contaminants of concern at concentrations exceeding regulatory maximum contaminant levels or risk-based levels; and Reduce the risk to human health and the environment to the extent practicable. Based on the review of existing data, the results of the modeling, future use, and current operations at PSA, the following alternatives have been developed for consideration at CAU 447: Alternative 1--No Further Action; Alternative 2--Proof-of-Concept and Monitoring with Institutional Controls; and Alternative 3--Contaminant Control. The corrective action alternatives were evaluated based on the approach outlined in the ''Focused Evaluation of Selected Remedial Alternatives for the Underground Test Area'' (DOE/NV, 1998b). Each alternative was assessed against nine

  10. 2009 River Corridor Closure Contractor Revegetation and Mitigation Monitoring Report

    SciTech Connect (OSTI)

    C. T. Lindsey; K. A. Gano; R. D. Teel

    2009-09-30

    This document details the results of revegetation and mitigation monitoring conducted in 2009, including 25 revegetation/restoration projects, one revegetation/mitigation project, and three bat mitigation projects.

  11. Corrective Action Tracking System (CATS) | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    The CATS web-based database is used to enter, track, and report the status of corrective actions developed and implemented in the DOE Corrective Action Management Program (CAMP) to...

  12. A comparison of the RCRA Corrective Action and CERCLA Remedial Action Processes

    SciTech Connect (OSTI)

    Traceski, Thomas T.

    1994-02-01

    This document provides a comprehensive side-by-side comparison of the RCRA corrective action and the CERCLA remedial action processes. On the even-numbered pages a discussion of the RCRA corrective action process is presented and on the odd-numbered pages a comparative discussion of the CERCLA remedial action process can be found. Because the two programs have a difference structure, there is not always a direct correlation between the two throughout the document. This document serves as an informative reference for Departmental and contractor personnel responsible for oversight or implementation of RCRA corrective action and CERCLA remedial action activities at DOE environmental restoration sites.

  13. CORRECTIVE ACTION PLAN FOR CORRECTIVE ACTION UNIT 224: DECON PAD AND SEPTIC SYSTEMS NEVADA TEST SITE, NEVADA

    SciTech Connect (OSTI)

    2006-07-01

    The purpose of this Corrective Action Plan is to provide the detailed scope of work required to implement the recommended corrective actions as specified in the approved CAU 224 CADD.

  14. Improving Department of Energy Capabilities for Mitigating Beyond...

    Energy Savers [EERE]

    Improving Department of Energy Capabilities for Mitigating Beyond Design Basis Events Improving Department of Energy Capabilities for Mitigating Beyond Design Basis Events April ...

  15. Oregon Fish and Wildlife Mitigation Policy | Open Energy Information

    Open Energy Info (EERE)

    Fish and Wildlife Mitigation Policy Jump to: navigation, search OpenEI Reference LibraryAdd to library Reference: Oregon Fish and Wildlife Mitigation Policy Published Publisher Not...

  16. Recent Diesel Engine Emission Mitigation Activities of the Maritime...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Diesel Engine Emission Mitigation Activities of the Maritime Administration Energy Technologies Program Recent Diesel Engine Emission Mitigation Activities of the Maritime ...

  17. Mitigating Breakdown in High Energy Density Perovskite Polymer...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Mitigating Breakdown in High Energy Density Perovskite Polymer Nanocomposite Capacitors Mitigating Breakdown in High Energy Density Perovskite Polymer Nanocomposite Capacitors 2012 ...

  18. National and Sectoral GHG Mitigation Potential: A Comparison...

    Open Energy Info (EERE)

    and Sectoral GHG Mitigation Potential: A Comparison Across Models Jump to: navigation, search Tool Summary LAUNCH TOOL Name: National and Sectoral GHG Mitigation Potential: A...

  19. EA-1923: Mitigated Finding of No Significant Impact | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Mitigated Finding of No Significant Impact EA-1923: Mitigated Finding of No Significant Impact Green Energy School Wind Turbine Project on Saipan, Commonwealth of the Northern ...

  20. Nanoparticles to Mitigate Biofilm Growth. (Conference) | SciTech...

    Office of Scientific and Technical Information (OSTI)

    Nanoparticles to Mitigate Biofilm Growth. Citation Details In-Document Search Title: Nanoparticles to Mitigate Biofilm Growth. Abstract not provided. Authors: Altman, Susan Jeanne ...

  1. National integrated mitigation planning in agriculture: A review...

    Open Energy Info (EERE)

    National integrated mitigation planning in agriculture: A review paper This review of national greenhouse gas (GHG) mitigation planning in the agriculture sector has two...

  2. Property:Environmental Monitoring and Mitigation Efforts | Open...

    Open Energy Info (EERE)

    Environmental Monitoring and Mitigation Efforts Jump to: navigation, search Property Name Environmental Monitoring and Mitigation Efforts Property Type String Retrieved from...

  3. Exploring changes in solar model physics to mitigate the solar...

    Office of Scientific and Technical Information (OSTI)

    Exploring changes in solar model physics to mitigate the solar abundance problem Citation Details In-Document Search Title: Exploring changes in solar model physics to mitigate the ...

  4. Procedures for Interagency Consultation to Avoid or Mitigate...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    or Mitigate Adverse Effects on Rivers in the Nationwide Inventory (CEQ, 1980) Procedures for Interagency Consultation to Avoid or Mitigate Adverse Effects on Rivers in the ...

  5. Korea's Green Growth Strategy: Mitigating Climate Change and...

    Open Energy Info (EERE)

    Korea's Green Growth Strategy: Mitigating Climate Change and Developing New Growth Engines Jump to: navigation, search Name Korea's Green Growth Strategy: Mitigating Climate Change...

  6. Financing Global Climate Change Mitigation | Open Energy Information

    Open Energy Info (EERE)

    Global Climate Change Mitigation Jump to: navigation, search Tool Summary LAUNCH TOOL Name: Financing Global Climate Change Mitigation AgencyCompany Organization: United Nations...

  7. Information Needs for Energy Mitigation and Siting

    Broader source: Energy.gov (indexed) [DOE]

    esources University o f W yoming QUADRENNIAL ENERGY REVIEW - Aug. 21,2014 1. A shared language 2. Solid baseline data to guide planning and siting 3. Mitigation best practices -...

  8. Mitigating the Impacts of Glint and Glare

    SciTech Connect (OSTI)

    Hillesheim, Michael; Kandt, Alicen; Phillips, Steven

    2015-09-01

    The National Renewable Energy Laboratory, supporting the Department of the Navy Renewable Energy Program Office, has developed an innovative glint/glare analysis and visualization methodology to understand and mitigate the possible impacts of light reflecting off solar photovoltaic arrays.

  9. After Action Report: Specific Manufacturing Capability 2014 Evaluated Drill October 29, 2014

    SciTech Connect (OSTI)

    V. Scott Barnes

    2014-12-01

    On October 29, 2014, the Specific Manufacturing Capability (SMC) facility located at the Idaho National Laboratory (INL) conducted its annual evaluated emergency drill. As a result, this after action report is required by DOE O 151.1C, “Comprehensive Emergency Management System.” The SMC facility, in coordination with other onsite organizations, and the Department of Energy Idaho Operations Office (DOE ID) conducted an annual facility emergency drill to demonstrate the ability to implement the requirements of DOE O 151.1C, “Comprehensive Emergency Management System.” The INL contractor, Battelle Energy Alliance, LLC (BEA) in coordination with other onsite organizations, conducted operations and demonstrated proper response measures to mitigate an event and protect the health and safety of onsite personnel, the environment, and property. Report data was collected from multiple sources, including documentation generated during drill response, critiques conducted immediately after terminating the drill, and evaluation critiques.

  10. Willow Creek Wildlife Mitigation Project. Final Environmental Assessment.

    SciTech Connect (OSTI)

    1995-04-01

    Today`s notice announces BPA`s proposal to fund land acquisition or acquisition of a conservation easement and a wildlife management plan to protect and enhance wildlife habitat at the Willow Creek Natural Area in Eugene, Oregon. This action would provide partial mitigation for wildlife and wildlife habitat lost by the development of Federal hydroelectric projects in the Willamette River Basin. The project is consistent with BPA`s obligations under provisions of the Pacific Northwest Electric Power Planning and Conservation Act of 1980 as outlined by the Northwest Power Planning Council`s 1994 Columbia River Basin Fish and Wildlife Program. BPA has prepared an environmental assessment (DOE/EA-1023) evaluating the proposed project. Based on the analysis in the EA, BPA has determined that the proposed action is not a major Federal action significantly affecting the quality of the human environment, within the meaning of the National Environmental Policy Act (NEPA) of 1969. Therefore, the preparation of an environmental impact statement (EIS) is not required and BPA is issuing this FONSI.

  11. Assessment of GHG mitigation technology measures in Ukraine

    SciTech Connect (OSTI)

    Raptsoun, N.; Parasiouk, N.

    1996-12-31

    In June 1992 the representatives of 176 countries including Ukraine met in Rio de Janeiro at the UN Conference to coordinate its efforts in protecting and guarding the environment. Signature of the UN Framework Convention on Climate Change by around 150 countries indicates that climate change is potentially a major threat to the world`s environment and economic development. The project {open_quotes}Country Study on Climate Change in Ukraine{close_quotes} coordinated by the Agency for Rational Energy Use and Ecology (ARENIA-ECO) and supported by the US Country Studies Program Support for Climate Change Studies. The aim of the project is to make the information related to climate change in Ukraine available for the world community by using the potential of Ukrainian research institutes for further concerted actions to solve the problem of climate change on the global scale. The project consists of four elements: (1) the development of the GHG Inventory in Ukraine; (2) assessments of ecosystems-vulnerability to climate change and adaptation options; and (3) mitigation options analysis; (4) public education and outreach activities. This paper contains the main results of the third element for the energy and non-energy sectors. Main tasks of the third element were: (1) to select, test and describe or develop the methodology for mitigation options assessment; (2) to analyze the main sources of GHG emissions in Ukraine; (3) to give the macro economic analysis of Ukrainian development and the development of main economical sectors industry, energy, transport, residential, forestry and agriculture; (4) to forecast GHG emissions for different scenarios of the economic development; and (5) to analyze the main measures to mitigate climate change.

  12. Advanced Mitigating Measures for the Cell Internal Short Risk (Presentation)

    SciTech Connect (OSTI)

    Darcy, E.; Smith, K.

    2010-04-01

    This presentation describes mitigation measures for internal short circuits in lithium-ion battery cells.

  13. Defining the no-action alternative for National Environmental Policy Act analyses of continuing actions

    SciTech Connect (OSTI)

    McCold, L.N.; Saulsbury, J.W.

    1998-01-01

    The Council on Environmental Quality (CEQ) regulations for implementing the National Environmental Policy Act of 1969 (NEPA) do not define the no-action alternative, stating only that EPA analyses shall include the alternative of no action. The definition of the no-action alternative for newly proposed actions seems clear. However, for continuing actions, the meaning of the no-action alternative is ambiguous. This article examines the overall function of the no-action alternative for NEPA analyses of continuing actions. It begins with a discussion of the conflicting definitions of the no-action alternative for continuing activities, including CEQ regulations and guidelines related to the no-action alternative and legal decisions that have helped establish precedence for defining no action. A review of NEPA regulations and guidelines of 10 federal agencies shows how different agencies define no-action for continuing actions. Review of six recent NEPA documents on continuing actions reveals how their definition of the no-action alternative promote or impede informed decision-making.

  14. On the road to HF mitigation

    SciTech Connect (OSTI)

    VanZele, R.L.; Diener, R. )

    1990-06-01

    The hazards of hydrogen fluoride (HF) have long been recognized and industry performance reflects sound operating practices. However, full-scale industry-sponsored HF release test conducted at the U.S. Department of Energy (DOE) test site in 1986 caused concern in view of HF's toxicity. Ambient impacts were greater than anticipated. And diking, a primary mitigation technique, proved ineffective for releases of pressurized superheated HF. In partial response to these new technical data, an ad-hoc three-component Industry Cooperative Hydrogen Fluoride Mitigation Assessment Program (ICHMAP) was begun in late 1987 to study and test techniques for mitigating accidental releases of HF and alkylation unit acid (AUA) and to enhance capabilities to estimate ambient impacts from such releases. AUA is a mixture of HF and hydrocarbons. The program's mitigation components have recently been completed while work on the impact assessment component is nearing completion. This article describes the program and summarizes the objective, scope of work, structure, and conclusions from the program's two mitigation components. In addition, the objectives and scope of work of the impact assessment components are described.

  15. Disruption mitigation using high pressure gas jets

    SciTech Connect (OSTI)

    Dennis G. Whyte

    2007-10-11

    The goal of this research is to establish credible disruption mitigation scenarios based on the technique of massive gas injection. Disruption mitigation seeks to minimize or eliminate damage to internal components that can occur due to the rapid dissipation of thermal and magnetic energy during a tokamak disruption. In particular, the focus of present research is extrapolating mitigation techniques to burning plasma experiments such as ITER, where disruption-caused damage poses a serious threat to the lifetime of internal vessel components. A majority of effort has focused on national and international collaborative research with large tokamaks: DIII-D, Alcator C-Mod, JET, and ASDEX Upgrade. The research was oriented towards empirical trials of gas-jet mitigation on several tokamaks, with the goal of developing and applying cohesive models to the data across devices. Disruption mitigation using gas jet injection has proven to be a viable candidate for avoiding or minimizing damage to internal components in burning plasma experiments like ITER. The physics understanding is progress towards a technological design for the required gas injection system in ITER.

  16. Platelet composite coatings for tin whisker mitigation

    SciTech Connect (OSTI)

    Rohwer, Lauren E. S.; Martin, James E.

    2015-09-14

    In this study, reliable methods for tin whisker mitigation are needed for applications that utilize tin-plated commercial components. Tin can grow whiskers that can lead to electrical shorting, possibly causing critical systems to fail catastrophically. The mechanisms of tin whisker growth are unclear and this makes prediction of the lifetimes of critical components uncertain. The development of robust methods for tin whisker mitigation is currently the best approach to eliminating the risk of shorting. Current mitigation methods are based on unfilled polymer coatings that are not impenetrable to tin whiskers. In this paper we report tin whisker mitigation results for several filled polymer coatings. The whisker-penetration resistance of the coatings was evaluated at elevated temperature and high humidity and under temperature cycling conditions. The composite coatings comprised Ni and MgF2-coated Al/Ni/Al platelets in epoxy resin or silicone rubber. In addition to improved whisker mitigation, these platelet composites have enhanced thermal conductivity and dielectric constant compared with unfilled polymers.

  17. Platelet composite coatings for tin whisker mitigation

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Rohwer, Lauren E. S.; Martin, James E.

    2015-09-14

    In this study, reliable methods for tin whisker mitigation are needed for applications that utilize tin-plated commercial components. Tin can grow whiskers that can lead to electrical shorting, possibly causing critical systems to fail catastrophically. The mechanisms of tin whisker growth are unclear and this makes prediction of the lifetimes of critical components uncertain. The development of robust methods for tin whisker mitigation is currently the best approach to eliminating the risk of shorting. Current mitigation methods are based on unfilled polymer coatings that are not impenetrable to tin whiskers. In this paper we report tin whisker mitigation results formore » several filled polymer coatings. The whisker-penetration resistance of the coatings was evaluated at elevated temperature and high humidity and under temperature cycling conditions. The composite coatings comprised Ni and MgF2-coated Al/Ni/Al platelets in epoxy resin or silicone rubber. In addition to improved whisker mitigation, these platelet composites have enhanced thermal conductivity and dielectric constant compared with unfilled polymers.« less

  18. CERCLA interim action at the Par Pond unit: A case study

    SciTech Connect (OSTI)

    Hickey, H.M.; Matthews, S.S.; Neal, L.W.; Weiss, W.R.

    1993-11-01

    The Par Pond unit designated under CERCLA consists of sediments within a Savannah River Site (SRS) cooling water reservoir. The sediments are contaminated with radionuclides and nonradioactive constituents from nuclear production reactor operations. The mercury in Par Pond is believed to have originated from the Savannah River. Because of Par Pond Dam safety Issues, the water level of the reservoir was drawn down, exposing more than 1300 acres of contaminated sediments and triggering the need for CERCLA interim remedial action. This paper presents the interim action approach taken with Par Pond as a case study. The approach considered the complexity of the Par Pond ecosystem, the large size of Par Pond, the volume of contaminated sediments, and the institutional controls existing at SRS. The Environmental Protection Agency (EPA) considers units with large volumes of low-concentration wastes, as is the case with Par Pond, to be {open_quotes}special sites.{close_quotes} Accordingly, EPA guidance establishes that the range of alternatives developed focus primarily on containment options and other remedial approaches that mitigate potential risks associated with the {open_quotes}special site.{close_quotes} The remedial alternatives, according to EPA, are not to be prohibitively expensive or difficult to implement. This case study also is representative of the types of issues that will need to be addressed within the Department of Energy (DOE) complex as nuclear facilities are transitioned to inactive status and corrective/remedial actions are warranted.

  19. Compensatory mitigation and screening rules in environmental impact assessment

    SciTech Connect (OSTI)

    Macintosh, Andrew Waugh, Lauren

    2014-11-15

    . For urban development actions, the ratio between lawful and unlawful particular manner decisions was worse than 1:1. • The extent of non-compliance is explained on the basis of convenience. Budget and interest group pressures resulted in the development of an informal custom whereby the formal compensatory mitigation restrictions were ignored. • The results highlight the relative significance of formal and informal institutions in EIA. Formal EIA rules typically provide a mere outline of the process. The informal institutions adopted by administrators often have a greater influence on how the process operates and what it achieves.

  20. Oregon Trust Agreement Planning Project : Potential Mitigations to the Impacts on Oregon Wildlife Resources Associated with Relevant Mainstem Columbia River and Willamette River Hydroelectric Projects.

    SciTech Connect (OSTI)

    United States. Bonneville Power Administration.

    1993-10-01

    A coalition of the Oregon wildlife agencies and tribes (the Oregon Wildlife Mitigation Coalition) have forged a cooperative effort to promote wildlife mitigation from losses to Oregon wildlife resources associated with the four mainstream Columbia River and the eight Willamette River Basin hydroelectric projects. This coalition formed a Joint Advisory Committee, made up of technical representatives from all of the tribes and agencies, to develop this report. The goal was to create a list of potential mitigation opportunities by priority, and to attempt to determine the costs of mitigating the wildlife losses. The information and analysis was completed for all projects in Oregon, but was gathered separately for the Lower Columbia and Willamette Basin projects. The coalition developed a procedure to gather information on potential mitigation projects and opportunities. All tribes, agencies and interested parties were contacted in an attempt to evaluate all proposed or potential mitigation. A database was developed and minimum criteria were established for opportunities to be considered. These criteria included the location of the mitigation site within a defined area, as well as other criteria established by the Northwest Power Planning Council. Costs were established for general habitats within the mitigation area, based on estimates from certified appraisers. An analysis of the cost effectiveness of various types of mitigation projects was completed. Estimates of operation and maintenance costs were also developed. The report outlines strategies for gathering mitigation potentials, evaluating them, determining their costs, and attempting to move towards their implementation.

  1. Guam Energy Action Plan

    SciTech Connect (OSTI)

    Conrad, M. D.; Ness, J. E.

    2013-07-01

    Describes the four near-term strategies selected by the Guam Energy Task Force during action planning workshops conducted in March 2013, and outlines the steps being taken to implement those strategies. Each strategy addresses one of the energy sectors identified in the earlier Guam strategic energy plan as being an essential component of diversifying Guam's fuel sources and reducing fossil energy consumption 20% by 2020. The four energy strategies selected are: (1) expanding public outreach on energy efficiency and conservation, (2) establishing a demand-side management revolving loan program, (3) exploring waste-to-energy options, and (4) influencing the transportation sector via anti-idling legislation, vehicle registration fees, and electric vehicles.

  2. ENHANCED PRACTICAL PHOTOSYNTHETIC CO2 MITIGATION

    SciTech Connect (OSTI)

    Dr. Gregory Kremer; Dr. David J. Bayless; Dr. Morgan Vis; Dr. Michael Prudich; Dr. Keith Cooksey; Dr. Jeff Muhs

    2002-01-15

    This quarterly report documents significant achievements in the Enhanced Practical Photosynthetic CO{sub 2} Mitigation project during the period from 10/3/2001 through 1/02/2002. Most of the achievements are milestones in our efforts to complete the tasks and subtasks that constitute the project objectives. Our research team has made significant progress towards completion of our Phase I objectives, and our current efforts remain focused on fulfilling these research objectives in accordance with the project timeline. Overall, we believe that we are on schedule to complete Phase I activities by 10/2002, which is the milestone date from the original project timeline. Specific results and accomplishments for the fourth quarter of 2001 include: (1) New procedures and protocols have been developed to increase the chances of successful implementation in the bioreactor of organisms that perform well in the lab. The new procedures include pre-screening of organisms for adhesion characteristics and a focus on identifying the organisms with maximum growth rate potential. (2) Preliminary results show an increase in adhesion to glass and a decrease in overall growth rates when using growth media prepared with tap water rather than distilled water. (3) Several of the organisms collected from Yellowstone National Park using the new procedures are currently being cultured in preparation for bioreactor tests. (4) One important result from a test of growth surface temperature distribution as a function of gas stream and drip-fluid temperatures showed a high dependence of membrane temperature on fluid temperature, with gas stream temperature having minimal effect. This result indicates that bioreactor growth surface temperatures can be controlled using fluid delivery temperature. The possible implications for implementation of the bioreactor concept are encouraging, since it may be possible to use the bioreactor with very high gas stream temperatures by controlling the temperature

  3. Guide to the Successful Implementation of State Combined Heat and Power Policies

    SciTech Connect (OSTI)

    Industrial Energy Efficiency and Combined Heat and Power Working Group

    2013-03-11

    Provides utility regulators and other policymakers with actionable information based on effective state strategies for implementing CHP policies

  4. Ray Effect Mitigation Through Reference Frame Rotation

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Tencer, John

    2016-06-14

    The discrete ordinates method is a popular and versatile technique for solving the radiative transport equation, a major drawback of which is the presence of ray effects. Mitigation of ray effects can yield significantly more accurate results and enhanced numerical stability for combined mode codes. Moreover, when ray effects are present, the solution is seen to be highly dependent upon the relative orientation of the geometry and the global reference frame. It is an undesirable property. A novel ray effect mitigation technique of averaging the computed solution for various reference frame orientations is proposed.

  5. Mitigating PQ Problems in Legacy Data Centers

    SciTech Connect (OSTI)

    Ilinets, Boris; /SLAC

    2011-06-01

    The conclusions of this presentation are: (1) Problems with PQ in legacy data centers still exist and need to be mitigated; (2) Harmonics generated by non-linear IT load can be lowered by passive, active and hybrid cancellation methods; (3) Harmonic study is necessary to find the best way to treat PQ problems; (4) AHF's and harmonic cancellation transformers proved to be very efficient in mitigating PQ problems; and (5) It is important that IT leaders partner with electrical engineering to appropriate ROI statements, justifying many of these expenditures.

  6. Gas powered fluid gun with recoil mitigation

    DOE Patents [OSTI]

    Grubelich, Mark C; Yonas, Gerold

    2013-11-12

    A gas powered fluid gun for propelling a stream or slug of a fluid at high velocity toward a target. Recoil mitigation is provided that reduces or eliminates the associated recoil forces, with minimal or no backwash. By launching a quantity of water in the opposite direction, net momentum forces are reduced or eliminated. Examples of recoil mitigation devices include a cone for making a conical fluid sheet, a device forming multiple impinging streams of fluid, a cavitating venturi, one or more spinning vanes, or an annular tangential entry/exit.

  7. Gas powered fluid gun with recoil mitigation

    DOE Patents [OSTI]

    Grubelich, Mark C.; Yonas, Gerold

    2016-03-01

    A gas powered fluid gun for propelling a stream or slug of a fluid at high velocity toward a target. Recoil mitigation is provided that reduces or eliminates the associated recoil forces, with minimal or no backwash. By launching a quantity of water in the opposite direction, net momentum forces are reduced or eliminated. Examples of recoil mitigation devices include a cone for making a conical fluid sheet, a device forming multiple impinging streams of fluid, a cavitating venturi, one or more spinning vanes, or an annular tangential entry/exit.

  8. CORRECTIVE ACTION DECISION DOCUMENT FOR THE AREA 3 LANDFILL COMPLEX, TONOPAH TEST RANGE, CAU 424, REVISION 0, MARCH 1998

    SciTech Connect (OSTI)

    DOE /NV

    1998-03-03

    This Corrective Action Decision Document (CADD) has been prepared for the Area 3 Landfill Complex (Corrective Action Unit [CAU] 424) in accordance with the Federal Facility Agreement and Consent Order (FFACO) of 1996. Corrective Action Unit 424 is located at the Tonopah Test Range (TTR) and is comprised of the following Corrective Action Sites (CASs), each an individual landfill located around and within the perimeter of the Area 3 Compound (DOE/NV, 1996a): (1) Landfill A3-1 is CAS No. 03-08-001-A301. (2) Landfill A3-2 is CAS No. 03-08-002-A302. (3) Landfill A3-3 is CAS No. 03-08-002-A303. (4) Landfill A3-4 is CAS No. 03-08-002-A304. (5) Landfill A3-5 is CAS No. 03-08-002-A305. (6) Landfill A3-6 is CAS No. 03-08-002-A306. (7) Landfill A3-7 is CAS No. 03-08-002-A307. (8) Landfill A3-8 is CAS No. 03-08-002-A308. The purpose of this CADD is to identify and provide a rationale for the selection of a recommended corrective action alternative for each CAS. The scope of this CADD consists of the following: (1) Develop corrective action objectives. (2) Identify corrective action alternative screening criteria. (3) Develop corrective action alternatives. (4) Perform detailed and comparative evaluations of the corrective action alternatives in relation to the corrective action objectives and screening criteria. (6) Recommend and justify a preferred corrective action alternative for each CAS. In June and July 1997, a corrective action investigation was performed as set forth in the Corrective Action Investigation Plan (CAIP) for CAU No. 424: Area 3 Landfill Complex, Tonopah Test Range, Nevada (DOE/NV, 1997). Details can be found in Appendix A of this document. The results indicated four groupings of site characteristics as shown in Table ES-1. Based on the potential exposure pathways, the following corrective action objectives have been identified for CAU No. 424: (1) Prevent or mitigate human exposure to subsurface soils containing waste. (2) Remediate the site per

  9. Discovery in Action - Pacific Northwest National Laboratory

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Discovery in Action Discovery in Action

  10. US country studies program: Results from mitigation studies

    SciTech Connect (OSTI)

    1996-12-31

    This paper describes the U.S. Country Studies Program which was implemented to support the principles and objectives of the Framework Convention on Climate Change (FCCC). There were three principle objectives in this program: to enhance capabilities to conduct climate change assessments, prepare action plans, and implement technology projects; to help establish a process for developing and implementing national policies and measures; to support principles and objective of the FCCC. As a result, 55 countries are completing studies, more than 2000 analysts engaged in the studies have been trained, and there is a much broader understanding and support for climate change concerns. The article describes experiences of some countries, and general observations and conclusions which are broadly seperated into developed countries and those with economies in transition.

  11. Highly concentrated foam formulation for blast mitigation

    DOE Patents [OSTI]

    Tucker, Mark D.; Gao, Huizhen

    2010-12-14

    A highly concentrated foam formulation for blast suppression and dispersion mitigation for use in responding to a terrorism incident involving a radiological dispersion device. The foam formulation is more concentrated and more stable than the current blast suppression foam (AFC-380), which reduces the logistics burden on the user.

  12. RCRA corrective action determination of no further action

    SciTech Connect (OSTI)

    1996-06-01

    On July 27, 1990, the U.S. Environmental Protection Agency (EPA) proposed a regulatory framework (55 FR 30798) for responding to releases of hazardous waste and hazardous constituents from solid waste management units (SWMUs) at facilities seeking permits or permitted under the Resource Conservation and Recovery Act (RCRA). The proposed rule, `Corrective Action for Solid Waste Management Units at Hazardous Waste Facilities`, would create a new Subpart S under the 40 CFR 264 regulations, and outlines requirements for conducting RCRA Facility Investigations, evaluating potential remedies, and selecting and implementing remedies (i.e., corrective measures) at RCRA facilities. EPA anticipates instances where releases or suspected releases of hazardous wastes or constituents from SWMUs identified in a RCRA Facility Assessment, and subsequently addressed as part of required RCRA Facility Investigations, will be found to be non-existent or non-threatening to human health or the environment. Such releases may require no further action. For such situations, EPA proposed a mechanism for making a determination that no further corrective action is needed. This mechanism is known as a Determination of No Further Action (DNFA) (55 FR 30875). This information Brief describes what a DNFA is and discusses the mechanism for making a DNFA. This is one of a series of Information Briefs on RCRA corrective action.

  13. Role of Biochar in Mitigation of Climate Change

    SciTech Connect (OSTI)

    Lehmann, Johannes C.; Amonette, James E.; Roberts, Kelli G.

    2010-09-30

    stability is achieved by the conversion of fresh organic materials, which mineralize comparatively quickly, into biochar, which mineralizes much more slowly. The difference between the mineralization of uncharred and charred material results in a greater amount of carbon storage in soils and a lower amount of carbon dioxide, the major greenhouse gas, in the atmosphere. The principle of creating and managing biochar systems may address multiple environmental constraints. Biochar may help not only in mitigating climate change, but also fulfill a role in management of agricultural and forestry wastes, enhancement of soil sustainability, and generation of energy. Pyrolysis is a comparatively low-technology intervention. Deployment on a global scale, however, must be done carefully if the full mitigation potential is to be reached. Critical aspects of a successful implementation are that: 1) the biochar is sufficiently stable to reduce greenhouse gases in the atmosphere for an appropriate length of time. 2) the storage of carbon as biochar in soil is not offset by greenhouse gas emissions along the value chain of the system, such as mineralization of soil carbon or emissions of other greenhouse gases (e.g., methane and nitrous oxide). 3) net emission reductions are achieved for the entire life cycle of the system including indirect land use. 4) the biochar product does not cause unwanted side effects in soil. 5) the handling and production of biochar are in compliance with health and safety standards and do not pose hurdles to implementation. and 6) the biochar system is financially viable. This chapter discusses these issues in separate sections, identifies knowledge gaps, and proposes a road map to fully evaluate an environmentally and socially safe exploration of the biochar potential to mitigate climate change if adopted widely around the world.

  14. Status of Corrective Actions

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    WIPP AIB Report Status of Corrective Actions Status of Corrective Actions at LANL Department of Energy Issues Accident Investigation Board (AIB) Report on February 14 Incident ...

  15. Step 4: Project Implementation

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... expected * Technology O&M Assumed low, mitigable or allocatable Sources: Adapted from Holland & Hart, RE Project Development & Finance & Infocast, Advanced RE Project Finance & ...

  16. Safety equipment list for the 241-SY-101 RAPID mitigation project

    SciTech Connect (OSTI)

    MORRIS, K.L.

    1999-06-29

    This document provides the safety classification for the safety (safety class and safety RAPID Mitigation Project. This document is being issued as the project SEL until the supporting authorization basis documentation, this document will be superseded by the TWRS SEL (LMHC 1999), documentation istlralized. Upon implementation of the authorization basis significant) structures, systems, and components (SSCS) associated with the 241-SY-1O1 which will be updated to include the information contained herein.

  17. Mitigation and Remediation of Mercury Contamination at the Y...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Mitigation and Remediation of Mercury Contamination at the Y-12 Plant Oak Ridge Mitigation and Remediation of Mercury Contamination at the Y-12 Plant Oak Ridge Full Document and ...

  18. Market-Based Wildlife Mitigation in Wyoming | Open Energy Information

    Open Energy Info (EERE)

    in Wyoming Jump to: navigation, search OpenEI Reference LibraryAdd to library Report: Market-Based Wildlife Mitigation in Wyoming Abstract Covers the basics of mitigation...

  19. Siting: Wind Turbine/Radar Interference Mitigation (TSPEAR &...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    ... Wind TurbineRadar Interference Mitigation (TSPEAR & IFT&E) HomeStationary PowerEnergy Conversion EfficiencyWind EnergySiting and Barrier MitigationSiting: Wind TurbineRadar ...

  20. Wildfire Mitigation at Los Alamos National Laboratory | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy Wildfire Mitigation at Los Alamos National Laboratory Wildfire Mitigation at Los Alamos National Laboratory The Laboratory's Fire Mitigation program is closely integrated with Los Alamos County, the U.S. Forest Service and the National Park Service to fight any wildfire in the region. The Laboratory's Fire Management posts daily Fire Danger Ratings on their website. Wildfire-Mitigation-at-Los-Alamos-National-Laboratory.pdf (2.69 MB) More Documents & Publications Remediated Nitrate

  1. 2008 River Corridor Closure Contractor Revegetation and Mitigation Monitoring Report

    SciTech Connect (OSTI)

    C. T. Lindsey; K. A. Gano

    2008-09-30

    The purpose of this report is to document the status of revegetation projects and natural resources mitigation efforts that have been conducted for remediated waste sites and other activities associated with the Comprehensive Environmental Response, Compensation, and Liability Act cleanup of National Priorities List waste sites at Hanford. This report documents the results of revegetation and mitigation monitoring conducted in 2008 and includes 22 revegetation/restoration projects, one revegetation/mitigation project, and two bat habitat mitigation projects.

  2. 2007 River Corridor Closure Contractor Revegetation and Mitigation Monitoring Report

    SciTech Connect (OSTI)

    K. A. Gano; C. T. Lindsey

    2007-09-27

    The purpose of this report is to document the status of revegetation projects and natural resources mitigation efforts that have been conducted for remediated waste sites and other activities associated with the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) cleanup of National Priorities List waste sites at Hanford. This report documents the results of revegetation and mitigation monitoring conducted in 2007 and includes 11 revegetation/restoration projects, one revegetation/mitigation project, and 3 bat habitat mitigation projects.

  3. 300 Area Building Retention Evaluation Mitigation Plan

    SciTech Connect (OSTI)

    D. J. McBride

    2007-07-03

    Evaluate the long-term retention of several facilities associated with the PNNL Capability Replacement Laboratory and other Hanfor mission needs. WCH prepared a mitigation plan for three scenarios with different release dates for specific buildings. The evaluations present a proposed plan for providing utility services to retained facilities in support of a long-term (+20 year) lifespan in addition to temporary services to buildings with specified delayed release dates.

  4. Explosive parcel containment and blast mitigation container

    DOE Patents [OSTI]

    Sparks, Michael H.

    2001-06-12

    The present invention relates to a containment structure for containing and mitigating explosions. The containment structure is installed in the wall of the building and has interior and exterior doors for placing suspicious packages into the containment structure and retrieving them from the exterior of the building. The containment structure has a blast deflection chute and a blowout panel to direct over pressure from explosions away from the building, surrounding structures and people.

  5. Corrective Actions Process

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Community, Environment » Environmental Stewardship » Environmental Cleanup » Corrective Actions Corrective Actions Process The general process for evaluating and remediating potential release sites is called the corrective action process. Contact Environmental Communication & Public Involvement P.O. Box 1663 MS M996 Los Alamos, NM 87545 (505) 667-0216 Email Corrective actions The Laboratory's corrective actions process refers to the way in which the Laboratory investigates, stabilizes,

  6. Field Guide for Testing Existing Photovoltaic Systems for Ground Faults and Installing Equipment to Mitigate Fire Hazards

    SciTech Connect (OSTI)

    Brooks, William; Basso, Thomas; Coddington, Michael

    2015-10-01

    Ground faults and arc faults are the two most common reasons for fires in photovoltaic (PV) arrays and methods exist that can mitigate the hazards. This report provides field procedures for testing PV arrays for ground faults, and for implementing high resolution ground fault and arc fault detectors in existing and new PV system designs.

  7. Potential GHG mitigation options for agriculture in China

    SciTech Connect (OSTI)

    Erda, Lin; Yue, Li; Hongmin, Dong

    1996-12-31

    Agriculture contributes more or less to anthropogenic emissions of carbon dioxide (CO{sub 2}), methane (CH{sub 4}), and nitrous oxide (N{sub 2}O). China`s agriculture accounts for about 5-15% of total emissions for these gases. Land-use changes related to agriculture are not major contributors in China. Mitigation options are available that could result in significant decrease in CH{sub 4} and N{sub 2}O emissions from agricultural systems. If implemented, they are likely to increase crop and animal productivity. Implementation has the potential to decrease CH{sub 4} emissions from rice, ruminants, and animal waste by 4-40%. The key to decreasing N{sub 2}O emissions is improving the efficiency of plant utilization of fertilizer N. This could decrease N{sub 2}O emissions from agriculture by almost 20%. Using animal waste to produce CH{sub 4} for energy and digested manure for fertilizer may at some time be cost effective. Economic analyses of options proposed should show positive economic as well as environmental benefits.

  8. Update on Common-Cause Failure Experience and Mitigation Practices

    SciTech Connect (OSTI)

    Wood, Richard Thomas; Muhlheim, Michael David; Pullum, Laura L; Smith, Cyrus M; Holcomb, David Eugene; Korsah, Kofi

    2014-04-01

    Experience in other industries has shown that digital technology can provide substantial benefits in terms of performance and reliability. However, the U.S. nuclear power industry has been slow to adopt the technology extensively in its instrumentation and control (I&C) applications because of inhibiting factors such as regulatory uncertainty, insufficient technological experience base, implementation complexity, limited availability of nuclear-qualified products and vendors, and inadequate definition of modernization cost recapture. Although there have been examples of digital technology usage in the nuclear power industry, challenges to the qualification of digital technology for high-integrity nuclear power plant (NPP) applications have severely constrained more widespread progress in achieving the benefits that are possible through the transition to digital. The U.S. Department of Energy (DOE) Office of Nuclear Energy (NE) established the Advanced Sensors and Instrumentation (ASI) technology area under the Nuclear Energy Enabling Technologies (NEET) Program to coordinate the instrumentation and controls (I&C) research across DOE NE and to identify and lead efforts to address common needs. As part of the NEET ASI research program, the Digital Technology Qualification project was established. Under this project, the Oak Ridge National Laboratory (ORNL) is leading the investigation into mitigation of digital common-cause failure (CCF) vulnerabilities for nuclear-qualified applications. This technical report documents updated and expanded findings from research activities by ORNL. Specifically, the report describes CCF experience in the nuclear and nonnuclear industries, identifies the state of the practice for CCF mitigation through key examples, and presents conclusions from the determination of knowledge gaps.

  9. Preparing for Project Implementation Financing Project Implementation

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Financing Project Implementation Save Energy Now LEADER Web Conference Project Implementation Seminar Series Save Energy Now LEADER Web Conference Agenda Seminar Series ...

  10. System design description for SY-101 hydrogen mitigation test project data acquisition and control system (DACS-1)

    SciTech Connect (OSTI)

    Truitt, R.W.; Pounds, T.S.; Smith, S.O.

    1994-08-24

    This document describes the hardware subsystems of the data acquisition and control system (DACS) used in mitigation tests conducted on waste tank SY-101 at the Hanford Nuclear Reservation. The system was designed and implemented by Los Alamos National Laboratory (LANL) and supplied to Westinghouse Hanford Company (WHC). The mitigation testing uses a pump immersed in the waste tank, directed at certain angles and operated at different speeds and time durations. The SY-101 tank has experienced recurrent periodic gas releases of hydrogen, nitrous oxide, ammonia, and (recently discovered) methane. The hydrogen gas represents a danger, as some of the releases are in amounts above the lower flammability limit (LFL). These large gas releases must be mitigated. Several instruments have been added to the tank to monitor the gas compositions, the tank level, the tank temperature, and other parameters. A mixer pump has been developed to stir the tank waste to cause the gases to be released at a slow rate. It is the function of the DACS to monitor those instruments and to control the mixer pump in a safe manner. During FY93 and FY94 the mixer pump was installed with associated testing operations support equipment and a mitigation test project plan was implemented. These activities successfully demonstrated the mixer pump`s ability to mitigate the SY-101 tank hydrogen gas hazard.

  11. UNDERSTANDING METHANE EMISSIONS SOURCES AND VIABLE MITIGATION MEASURES IN THE NATURAL GAS TRANSMISSION SYSTEMS: RUSSIAN AND U.S. EXPERIENCE

    SciTech Connect (OSTI)

    Ishkov, A.; Akopova, Gretta; Evans, Meredydd; Yulkin, Grigory; Roshchanka, Volha; Waltzer, Suzie; Romanov, K.; Picard, David; Stepanenko, O.; Neretin, D.

    2011-10-01

    This article will compare the natural gas transmission systems in the U.S. and Russia and review experience with methane mitigation technologies in the two countries. Russia and the United States (U.S.) are the world's largest consumers and producers of natural gas, and consequently, have some of the largest natural gas infrastructure. This paper compares the natural gas transmission systems in Russia and the U.S., their methane emissions and experiences in implementing methane mitigation technologies. Given the scale of the two systems, many international oil and natural gas companies have expressed interest in better understanding the methane emission volumes and trends as well as the methane mitigation options. This paper compares the two transmission systems and documents experiences in Russia and the U.S. in implementing technologies and programs for methane mitigation. The systems are inherently different. For instance, while the U.S. natural gas transmission system is represented by many companies, which operate pipelines with various characteristics, in Russia predominately one company, Gazprom, operates the gas transmission system. However, companies in both countries found that reducing methane emissions can be feasible and profitable. Examples of technologies in use include replacing wet seals with dry seals, implementing Directed Inspection and Maintenance (DI&M) programs, performing pipeline pump-down, applying composite wrap for non-leaking pipeline defects and installing low-bleed pneumatics. The research methodology for this paper involved a review of information on methane emissions trends and mitigation measures, analytical and statistical data collection; accumulation and analysis of operational data on compressor seals and other emission sources; and analysis of technologies used in both countries to mitigate methane emissions in the transmission sector. Operators of natural gas transmission systems have many options to reduce natural gas losses

  12. 2014 Joint Action Workshop

    Broader source: Energy.gov [DOE]

    The Joint Action Workshop is an annual event for joint action agencies and their members to meet informally and discuss emerging policy, regulatory, and power supply issues, and other topics...

  13. Action Recommendation for Cyber Resilience

    SciTech Connect (OSTI)

    Choudhury, Sutanay; Rodriguez, Luke R.; Curtis, Darren S.; Oler, Kiri J.; Nordquist, Peter L.; Chen, Pin-Yu; Ray, Indrajit

    2015-09-01

    This paper presents an unifying graph-based model for representing the infrastructure, behavior and missions of an enterprise. We describe how the model can be used to achieve resiliency against a wide class of failures and attacks. We introduce an algorithm for recommending resilience establishing actions based on dynamic updates to the models. Without loss of generality, we show the effectiveness of the algorithm for preserving latency based quality of service (QoS). Our models and the recommendation algorithms are implemented in a software framework that we seek to release as an open source framework for simulating resilient cyber systems.

  14. HANFORD TANK FARM RESOURCE CONVERVATION & RECOVERY ACT (RCRA) CORRECTIVE ACTION PROGRAM

    SciTech Connect (OSTI)

    KRISTOFZSKI, J.G.

    2007-01-15

    As a consequence of producing special nuclear material for the nation's defense, large amounts of extremely hazardous radioactive waste was created at the US Department of Energy's (DOE) Hanford Site in south central Washington State. A little over 50 million gallons of this waste is now stored in 177 large, underground tanks on Hanford's Central Plateau in tank farms regulated under the Atomic Energy Act and the Resource, Conservation, and Recovery Act (RCRA). Over 60 tanks and associated infrastructure have released or are presumed to have released waste in the vadose zone. In 1998, DOE's Office of River Protection established the Hanford Tank Farm RCRA Corrective Action Program (RCAP) to: (1) characterize the distribution and extent of the existing vadose zone contamination; (2) determine how the contamination will move in the future; (3) estimate the impacts of this contamination on groundwater and other media; (4) develop and implement mitigative measures; and (5) develop corrective measures to be implemented as part of the final closure of the tank farm facilities. Since its creation, RCAP has made major advances in each of these areas, which will be discussed in this paper.

  15. EAC Recommendations for DOE Action Regarding Implementing Effective...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    DOE Responses to EAC Work Products - June 2014 Electricity Advisory Committee Meeting Presentations June 2013 - Wednesday, June 5, 2013 Electricity Subsector Cybersecurity ...

  16. Wildfre Mitigation at Los Alamos National Laboratory

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Wildfre Mitigation at Los Alamos National Laboratory Background Established in 1943, Los Alamos National Laboratory consists of 1,280 buildings in 47 technical areas spread out over 37 square miles. The complex includes 11 nuclear facilities and more than 10,000 workers. In the past, large wildfres in the area, including the La Mesa Fire (1977), the Dome Fire (1996), the Oso Fire (1998), the Cerro Grande Fire (2000), and the Las Conchas Fire (2011) demonstrate that forests on and surrounding the

  17. Industrial Energy Efficiency and Climate Change Mitigation

    SciTech Connect (OSTI)

    Worrell, Ernst; Bernstein, Lenny; Roy, Joyashree; Price, Lynn; de la Rue du Can, Stephane; Harnisch, Jochen

    2009-02-02

    Industry contributes directly and indirectly (through consumed electricity) about 37% of the global greenhouse gas emissions, of which over 80% is from energy use. Total energy-related emissions, which were 9.9 GtCO2 in 2004, have grown by 65% since 1971. Even so, industry has almost continuously improved its energy efficiency over the past decades. In the near future, energy efficiency is potentially the most important and cost-effective means for mitigating greenhouse gas emissions from industry. This paper discusses the potential contribution of industrial energy efficiency technologies and policies to reduce energy use and greenhouse gas emissions to 2030.

  18. Security Informatics Research Challenges for Mitigating Cyber Friendly Fire

    SciTech Connect (OSTI)

    Carroll, Thomas E.; Greitzer, Frank L.; Roberts, Adam D.

    2014-09-30

    This paper addresses cognitive implications and research needs surrounding the problem of cyber friendly re (FF). We dene cyber FF as intentional o*ensive or defensive cyber/electronic actions intended to protect cyber systems against enemy forces or to attack enemy cyber systems, which unintentionally harms the mission e*ectiveness of friendly or neutral forces. We describe examples of cyber FF and discuss how it ts within a general conceptual framework for cyber security failures. Because it involves human failure, cyber FF may be considered to belong to a sub-class of cyber security failures characterized as unintentional insider threats. Cyber FF is closely related to combat friendly re in that maintaining situation awareness (SA) is paramount to avoiding unintended consequences. Cyber SA concerns knowledge of a system's topology (connectedness and relationships of the nodes in a system), and critical knowledge elements such as the characteristics and vulnerabilities of the components that comprise the system and its nodes, the nature of the activities or work performed, and the available defensive and o*ensive countermeasures that may be applied to thwart network attacks. We describe a test bed designed to support empirical research on factors a*ecting cyber FF. Finally, we discuss mitigation strategies to combat cyber FF, including both training concepts and suggestions for decision aids and visualization approaches.

  19. Mitigation of Severe Accident Consequences Using Inherent Safety Principles

    SciTech Connect (OSTI)

    R. A. Wigeland; J. E. Cahalan

    2009-12-01

    Sodium-cooled fast reactors are designed to have a high level of safety. Events of high probability of occurrence are typically handled without consequence through reliable engineering systems and good design practices. For accidents of lower probability, the initiating events are characterized by larger and more numerous challenges to the reactor system, such as failure of one or more major engineered systems and can also include a failure to scram the reactor in response. As the initiating conditions become more severe, they have the potential for creating serious consequences of potential safety significance, including fuel melting, fuel pin disruption and recriticality. If the progression of such accidents is not mitigated by design features of the reactor, energetic events and dispersal of radioactive materials may result. For severe accidents, there are several approaches that can be used to mitigate the consequences of such severe accident initiators, which typically include fuel pin failures and core disruption. One approach is to increase the reliability of the reactor protection system so that the probability of an ATWS event is reduced to less than 1 x 10-6 per reactor year, where larger accident consequences are allowed, meeting the U.S. NRC goal of relegating such accident consequences as core disruption to these extremely low probabilities. The main difficulty with this approach is to convincingly test and guarantee such increased reliability. Another approach is to increase the redundancy of the reactor scram system, which can also reduce the probability of an ATWS event to a frequency of less than 1 x 10-6 per reactor year or lower. The issues with this approach are more related to reactor core design, with the need for a greater number of control rod positions in the reactor core and the associated increase in complexity of the reactor protection system. A third approach is to use the inherent reactivity feedback that occurs in a fast reactor to

  20. FTCP Corrective Action Plan- Revision 2

    Broader source: Energy.gov [DOE]

    March 2009 FTCP Corrective Action Plan, Revision 2, which is Deliverable B for Commitment 13 in the Department of Energy (DOE) Implementation Plan to Improve Oversight of Nuclear Operations, issued in response to Defense Nuclear Facilities Safety Board Recommendation 2004-1, Oversight of Complex, High-Hazard Nuclear Operations

  1. FTCP Corrective Action Plan- Revision 1

    Broader source: Energy.gov [DOE]

    January 2007 FTCP Corrective Action Plan, Revision 1, which is Deliverable B for Commitment 13 in the Department of Energy (DOE) Implementation Plan to Improve Oversight of Nuclear Operations, issued in response to Defense Nuclear Facilities Safety Board Recommendation 2004- 1, Oversight of Complex, High-Hazard Nuclear Operations

  2. Step 4: Project Implementation

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Process Step 4: Project Implementation Presentation Agenda * Step 4: Project Implementation - Pre-construction - Contract execution - Interconnection - Project construction - Commissioning * Project Example 2 1/28/2016 2 1 Potential 3 Refinement 5 Operations & Maintenance 2 Options 4 Implementation 4 Implementation 3 Potential Options Refinement Implementation Operations & Maintenance Step 4: Implementation 4 Purpose: Contract and begin physical construction of project Tasks: * Finalize

  3. Global climate change and the mitigation challenge

    SciTech Connect (OSTI)

    Frank Princiotta

    2009-10-15

    Anthropogenic emissions of greenhouse gases, especially carbon dioxide (CO{sub 2}), have led to increasing atmospheric concentrations, very likely the primary cause of the 0.8{sup o}C warming the Earth has experienced since the Industrial Revolution. With industrial activity and population expected to increase for the rest of the century, large increases in greenhouse gas emissions are projected, with substantial global additional warming predicted. This paper examines forces driving CO{sub 2} emissions, a concise sector-by-sector summary of mitigation options, and research and development (R&D) priorities. To constrain warming to below approximately 2.5{sup o}C in 2100, the recent annual 3% CO{sub 2} emission growth rate needs to transform rapidly to an annual decrease rate of from 1 to 3% for decades. Furthermore, the current generation of energy generation and end-use technologies are capable of achieving less than half of the emission reduction needed for such a major mitigation program. New technologies will have to be developed and deployed at a rapid rate, especially for the key power generation and transportation sectors. Current energy technology research, development, demonstration, and deployment (RDD&D) programs fall far short of what is required. 20 refs., 18 figs., 4 tabs.

  4. DOE/EA-1915 MITIGATION ACTION PLAN PROPOSED CONVEYANCE OF LAND...

    Energy Savers [EERE]

    ... including extraction or production of any coal, oil, gas, geothermal steam, associated ... to protect property (e.g., wildlands, buildings, and equipment) by minimizing fire risk. ...

  5. EA-1951: Finding of No Significant Impact and Mitigation Action Plan

    Office of Energy Efficiency and Renewable Energy (EERE)

    Midway-Moxee Rebuild and Midway-Grandview Upgrade Transmission Line Project; Benton and Yakima Counties, Washington

  6. DOE/EA-1915 MITIGATION ACTION PLAN PROPOSED CONVEYANCE OF LAND...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    ... Indian Policy and Order 144.1, Department of Energy Grantor requires Grantee's acoustic and noise signature on the premises will not exceed current Washington State standards and ...

  7. Corrective Action Decision Document/Closure Report for Corrective Action Unit 567: Miscellaneous Soil Sites - Nevada National Security Site, Nevada

    SciTech Connect (OSTI)

    Matthews, Patrick

    2014-12-01

    This Corrective Action Decision Document/Closure Report presents information supporting the closure of Corrective Action Unit (CAU) 567: Miscellaneous Soil Sites, Nevada National Security Site, Nevada. The purpose of this Corrective Action Decision Document/Closure Report is to provide justification and documentation supporting the recommendation that no further corrective action is needed for CAU 567 based on the implementation of the corrective actions. The corrective actions implemented at CAU 567 were developed based on an evaluation of analytical data from the CAI, the assumed presence of COCs at specific locations, and the detailed and comparative analysis of the CAAs. The CAAs were selected on technical merit focusing on performance, reliability, feasibility, safety, and cost. The implemented corrective actions meet all requirements for the technical components evaluated. The CAAs meet all applicable federal and state regulations for closure of the site. Based on the implementation of these corrective actions, the DOE, National Nuclear Security Administration Nevada Field Office provides the following recommendations: • No further corrective actions are necessary for CAU 567. • The Nevada Division of Environmental Protection issue a Notice of Completion to the DOE, National Nuclear Security Administration Nevada Field Office for closure of CAU 567. • CAU 567 be moved from Appendix III to Appendix IV of the FFACO.

  8. Climate Action Champions: Southeast Florida Regional Climate Change

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Compact, FL | Department of Energy Southeast Florida Regional Climate Change Compact, FL Climate Action Champions: Southeast Florida Regional Climate Change Compact, FL The Southeast Florida Regional Climate Change Compact was executed by Broward, Miami-Dade, Monroe, and Palm Beach Counties in January 2010 to coordinate mitigation and adaptation efforts across county lines. The Compact represents a new form of regional climate governance designed to allow local governments to set the agenda

  9. Transformational Energy Action Management (TEAM) Wireless Energy Efficiency Keys Initiative

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    by Transformational Energy Action Management (TEAM) Wireless Energy Efficiency Keys Initiative *Ways of Using Wireless Technology to Help You Reduce Energy Usage at your Facility Together with our industry partners, we strive to: * Accelerate adoption of the many energy-efficient technologies and practices available today * Conduct vigorous technology innovation to radically improve future energy diversity, resource efficiency, and carbon mitigation * Promote a corporate culture of energy

  10. A safety assessment for proposed pump mixing operations to mitigate episodic gas releases in tank 241-SY-101: Hanford Site,Richland, Washington

    SciTech Connect (OSTI)

    Lentsch, J.W.

    1996-07-01

    This safety assessment addresses each of the elements required for the proposed action to remove a slurry distributor and to install, operate, and remove a mixing pump in Tank 241-SY-101,which is located within the Hanford Site, Richland, Washington.The proposed action is required as part of an ongoing evaluation of various mitigation concepts developed to eliminate episodic gas releases that result in hydrogen concentrations in the tank dome space that exceed the lower flammability limit.

  11. Safety assessment for proposed pump mixing operations to mitigate episodic gas releases in tank 241-101-SY: Hanford Site, Richland, Washington

    SciTech Connect (OSTI)

    Lentsch, J.W., Westinghouse Hanford

    1996-05-16

    This safety assessment addresses each of the elements required for the proposed action to remove a slurry distributor and to install, operate, and remove a mixing pump in Tank 241-SY-101, which is located within the Hanford Site, Richland, Washington. The proposed action is required as part of an ongoing evaluation of various mitigation concepts developed to eliminate episodic gas releases that result in hydrogen concentrations in the tank dome space that exceed the lower flammability limit.

  12. Develop an Institutional Change Action Plan for Sustainability

    Broader source: Energy.gov [DOE]

    After establishing a goal and assessing the rules, roles, and tools, federal agencies can develop an action plan (select the strategies that will be implemented over time to achieve and maintain energy and sustainability goals).

  13. Institutional Change Process Step 3: Develop an Action Plan

    Office of Energy Efficiency and Renewable Energy (EERE)

    After establishing a goal and assessing the rules, roles, and tools, federal agencies can develop an action plan (select the strategies that will be implemented over time to achieve and maintain energy and sustainability goals).

  14. National Action Plan Vision for 2025: A Framework for Change

    SciTech Connect (OSTI)

    National Action Plan for Energy Efficiency

    2008-11-01

    Establishes a goal of achieving all cost-effective energy efficiency by 2025 and presents 10 implementation goals as a framework for advancing the National Action Plans key policy recommendations.

  15. Action Item Review and Status

    Office of Environmental Management (EM)

    Board Action Items Action Item Resolution Action Item Strategic Planning Initiative Optimization Study Resolution Presentation by S. Schneider (HLW System Integrated Project...

  16. Institutional Change Process Step 3: Develop an Action Plan | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy 3: Develop an Action Plan Institutional Change Process Step 3: Develop an Action Plan Graphic showing 5 gears. They progress from Determine Goal to Identify Context-Rules, Roles and Tools to Develop Action Plan to Implement Plan to Measure and Evaluate. Process for Continuous Change After establishing goals and assessing the rules, roles, and tools, you can develop an action plan (select the strategies that will be implemented over time to achieve and maintain energy and

  17. TOP 10 VULNERABILITIES OF CONTROL SYSTEMS AND THEIR ASSOCIATED MITIGATIONS

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    | Department of Energy TOP 10 VULNERABILITIES OF CONTROL SYSTEMS AND THEIR ASSOCIATED MITIGATIONS TOP 10 VULNERABILITIES OF CONTROL SYSTEMS AND THEIR ASSOCIATED MITIGATIONS This document provides practices that can help mitigate the potential risks that can occur to some electricity sector organizations. Each organization decides for itself the risks it can accept and the practices it deems appropriate to manage those risks. TOP 10 VULNERABILITIES OF CONTROL SYSTEMS AND THEIR ASSOCIATED

  18. Improving Department of Energy Capabilities for Mitigating Beyond Design

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Basis Events | Department of Energy Improving Department of Energy Capabilities for Mitigating Beyond Design Basis Events Improving Department of Energy Capabilities for Mitigating Beyond Design Basis Events April 2013 OE-1: 2013-01 Improving Department of Energy Capabilities for Mitigating Beyond Design Basis Events The purpose of this Operating Experience (OE) document is to: provide results from U.S. Department of Energy (DOE), including the National Nuclear Security Administration,

  19. Burlington Bottoms Wildlife Mitigation Project. Final Environmental Assessment/Management Plan and Finding of No Significant Impact.

    SciTech Connect (OSTI)

    Not Available

    1994-12-01

    Bonneville Power Administration (BPA) proposes to fund wildlife management and enhancement activities for the Burlington bottoms wetlands mitigation site. Acquired by BPA in 1991, wildlife habitat at Burlington bottoms would contribute toward the goal of mitigation for wildlife losses and inundation of wildlife habitat due to the construction of Federal dams in the lower Columbia and Willamette River Basins. Target wildlife species identified for mitigation purposes are yellow warbler, great blue heron, black-capped chickadee, red-tailed hawk, valley quail, spotted sandpiper, wood duck, and beaver. The Draft Management Plan/Environmental Assessment (EA) describes alternatives for managing the Burlington Bottoms area, and evaluates the potential environmental impacts of the alternatives. Included in the Draft Management Plan/EA is an implementation schedule, and a monitoring and evaluation program, both of which are subject to further review pending determination of final ownership of the Burlington Bottoms property.

  20. International perspectives on mitigating laboratory biorisks.

    SciTech Connect (OSTI)

    Pinard, William J.; Salazar, Carlos A.

    2010-11-01

    The International Perspectives on Mitigating Laboratory Biorisks workshop, held at the Renaissance Polat Istanbul Hotel in Istanbul, Republic of Turkey, from October 25 to 27, 2010, sought to promote discussion between experts and stakeholders from around the world on issues related to the management of biological risk in laboratories. The event was organized by Sandia National Laboratories International Biological Threat Reduction program, on behalf of the US Department of State Biosecurity Engagement Program and the US Department of Defense Cooperative Biological Engagement Program. The workshop came about as a response to US Under Secretary of State Ellen O. Tauscher's statements in Geneva on December 9, 2009, during the Annual Meeting of the States Parties to the Biological Weapons Convention (BWC). Pursuant to those remarks, the workshop was intended to provide a forum for interested countries to share information on biorisk management training, standards, and needs. Over the course of the meeting's three days, participants discussed diverse topics such as the role of risk assessment in laboratory biorisk management, strategies for mitigating risk, measurement of performance and upkeep, international standards, training and building workforce competence, and the important role of government and regulation. The meeting concluded with affirmations of the utility of international cooperation in this sphere and recognition of positive prospects for the future. The workshop was organized as a series of short presentations by international experts on the field of biorisk management, followed by breakout sessions in which participants were divided into four groups and urged to discuss a particular topic with the aid of a facilitator and a set of guiding questions. Rapporteurs were present during the plenary session as well as breakout sessions and in particular were tasked with taking notes during discussions and reporting back to the assembled participants a brief

  1. Urban Surfaces and Heat Island Mitigation Potentials (Journal...

    Office of Scientific and Technical Information (OSTI)

    Journal Article: Urban Surfaces and Heat Island Mitigation Potentials Citation Details ... and urban vegetation (trees, grass, shrubs) on the meteorology and air quality of a city. ...

  2. MCA 22-3-430 - Montana Antiquities Avoidance and Mitigation ...

    Open Energy Info (EERE)

    MCA 22-3-430 - Montana Antiquities Avoidance and MitigationLegal Abstract Sets forth a principle of preferred avoidance of heritage properties or paleontological remains,...

  3. RAPID/Best Practices/Landscape-Scale Mitigation | Open Energy...

    Open Energy Info (EERE)

    features that minimize impacts (for example, the best types of materials and structure types for visual mitigation or avian-safe structure design) would have been identified...

  4. Mitigations for Security Vulnerabilities Found in Control System...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Mitigations for Security Vulnerabilities Found in Control System Networks (425.98 KB) More Documents & Publications Cyber Assessment Methods for SCADA Security Introduction SCADA ...

  5. Oregon Willamette River Basin Mitigation Agreement | Open Energy...

    Open Energy Info (EERE)

    River Basin Mitigation Agreement Author State of Oregon Recipient Bonneville Power Administration Published Publisher Not Provided, 10222010 DOI Not Provided Check for DOI...

  6. Monitoring and Assessment of Greenhouse Gas Emissions and Mitigation...

    Open Energy Info (EERE)

    Monitoring and Assessment of Greenhouse Gas Emissions and Mitigation Potential in Agriculture) Jump to: navigation, search Logo: Monitoring and Assessment of Greenhouse Gas...

  7. Exploring changes in solar model physics to mitigate the solar...

    Office of Scientific and Technical Information (OSTI)

    Exploring changes in solar model physics to mitigate the solar abundance problem Citation ... Visit OSTI to utilize additional information resources in energy science and technology. A ...

  8. Property:NEPA Resource Imposed Mitigation | Open Energy Information

    Open Energy Info (EERE)

    Protection) for applicable mitigation measures. Antelope Valley NesetNEPAImpactwithAirQuality + See http:ww2.wapa.govsiteswesternbusinesssellingDocuments...

  9. Wind Turbine Radar Interference Mitigation Working Group Releases...

    Broader source: Energy.gov (indexed) [DOE]

    Wind Turbine Radar Interference Mitigation Working Group to address these challenges. This new report lays out the plan for how the working group will address wind turbine radar ...

  10. Game-Changing Process Mitigates CO2 Emissions Using Renewable...

    Broader source: Energy.gov (indexed) [DOE]

    Game-Changing Process Mitigates CO2 Emissions Using Renewable Energy Gold nanoparticles ... Researchers developed a special form of gold nanoparticle that contains exactly 25 gold ...

  11. Mitigation of Vehicle Fast Charge Grid Impacts with Renewables...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Vehicle Fast Charge Grid Impacts with Renewables and Energy Storage Mitigation of Vehicle Fast ... AVTA: 2010 Honda Civic HEV with Experimental Ultra Lead Acid Battery Testing Results

  12. Climate Change Adaptation and Mitigation in the Tourism Sector...

    Open Energy Info (EERE)

    their decision making processes and operations. It presents an overview of the current science and policy of climate change, followed by self-guidance material on mitigation and...

  13. Characterizing Uncertainty for Regional Climate Change Mitigation and Adaptation Decisions

    SciTech Connect (OSTI)

    Unwin, Stephen D.; Moss, Richard H.; Rice, Jennie S.; Scott, Michael J.

    2011-09-30

    This white paper describes the results of new research to develop an uncertainty characterization process to help address the challenges of regional climate change mitigation and adaptation decisions.

  14. Micro-Structural Mitigation Strategies for PEM Fuel Cells

    Broader source: Energy.gov [DOE]

    Download presentation slides from the DOE Fuel Cell Technologies Office webinar Micro-Structural Mitigation Strategies for PEM Fuel Cells held on November 19, 2013.

  15. International Partnership on Mitigation and MRV | Open Energy...

    Open Energy Info (EERE)

    climate experts from a variety of countries, the Partnership seeks to: foster mutual learning between peers identify best practices establish a shared mitigation-related knowledge...

  16. Webinar: Micro-Structural Mitigation Strategies for PEM Fuel Cells

    Broader source: Energy.gov [DOE]

    Video recording of the Fuel Cell Technologies Office webinar, Micro-Structural Mitigation Strategies for PEM Fuel Cells, originally presented on November 19, 2013.

  17. Microsoft PowerPoint - Financial Plan Risk Mitigation Master...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    within acceptable bounds BPA Financial Plan Workshop 5 Financial Plan Risk Metrics Agenda Origin of the Risk Metrics Issue History of risk mitigation measures and origin of...

  18. Monitoring and Assessment of Greenhouse Gas Emissions and Mitigation...

    Open Energy Info (EERE)

    the MAGHG project is to support developing countries assess and report their greenhouse gas (GHG) emissions from agriculture, including assessment of mitigation options for...

  19. Greenhouse Gas Training Program for Inventory and Mitigation...

    Open Energy Info (EERE)

    divisionsfuture-perfect Country: South Korea Eastern Asia Language: English References: Greenhouse Gas Training Program for Inventory and Mitigation Modeling1...

  20. Mitigation of Vehicle Fast Charge Grid Impacts with Renewables...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Charge Grid Impacts with Renewables and Energy Storage Mike Simpson National Renewable Energy ... Grid Impact Mitigation * Identify system benefits - Add efficient, electric ...

  1. Chile-Climate Change Mitigation and Agriculture in Latin America...

    Open Energy Info (EERE)

    Agriculture in Latin America and the Caribbean Jump to: navigation, search Logo: Chile-Climate Change Mitigation and Agriculture in Latin America and the Caribbean Name...

  2. Climate Change Mitigation in the Energy and Forestry Sectors...

    Open Energy Info (EERE)

    of Developing Countries Jump to: navigation, search Tool Summary LAUNCH TOOL Name: Climate Change Mitigation in the Energy and Forestry Sectors of Developing Countries...

  3. Development based climate change adaptation and mitigation-conceptual...

    Open Energy Info (EERE)

    based climate change adaptation and mitigation-conceptual issues and lessons learned in studies in developing countries Jump to: navigation, search Tool Summary LAUNCH TOOL Name:...

  4. Agricultural Technologies for Climate Change Mitigation and Adaptation...

    Open Energy Info (EERE)

    Technologies for Climate Change Mitigation and Adaptation in Developing Countries: Policy Options for Innovations and Technology Diffusion Jump to: navigation, search Tool Summary...

  5. Congressional Notification of Pending Award of a Contract Action

    Broader source: Energy.gov [DOE]

    AL 2012-07/FAL 2012-01 (AL/FAL) implements statutory Congressional notification of pending award of a contract action, announcement of selected applications for negotiation of financial assistance awards, or to award a financial assistance action in excess of $1 million. The total value of the award includes options, budget periods and cost share. The AL/FAL implements Division B, Consolidated Appropriations Act, Fiscal Year 2012, Pub. L. No. 112-74, Title III – General Provisions, section 311.

  6. Statement from Secretary Moniz on Implementation Day for the Joint

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Comprehensive Plan of Action | Department of Energy Statement from Secretary Moniz on Implementation Day for the Joint Comprehensive Plan of Action Statement from Secretary Moniz on Implementation Day for the Joint Comprehensive Plan of Action January 16, 2016 - 5:07pm Addthis News Media Contact (202) 586-4940 DOENews@hq.doe.gov Implementation Day is a milestone in the effort to ensure that Iran's nuclear program is exclusively peaceful in nature by blocking potential pathways to a bomb. As

  7. Site mitigation issues along the Alameda Corridor

    SciTech Connect (OSTI)

    Ripaldi, C.P.

    1996-12-31

    The Alameda Corridor is a consolidated railroad link between the Ports of Los Angeles and Long Beach and the regional and national rail systems linking the nation. A joint Environmental Impacts Report/Environmental Impact Statement (EIR/EIS) was prepared for the project. The Final EIS was issued in February 1996, and a record of decision was issued in May, 1996. Various Phase 1 and Phase 2 Environmental Site Assessments have provided extensive historical documentation of environmental contamination in the vicinity of the Alameda Corridor Transportation Project. A Site Mitigation Master Plan provides guidance and direction for the clean-up activities. Samples will be analyzed for metals, PCB`s TRPH, BTEX, and VOCs.

  8. Mitigation of radiation induced surface contamination

    DOE Patents [OSTI]

    Klebanoff, Leonard E.; Stulen, Richard H.

    2003-01-01

    A process for mitigating or eliminating contamination and/or degradation of surfaces having common, adventitious atmospheric contaminants adsorbed thereon and exposed to radiation. A gas or a mixture of gases is introduced into the environment of a surface(s) to be protected. The choice of the gaseous species to be introduced (typically a hydrocarbon gas, water vapor, or oxygen or mixtures thereof) is dependent upon the contaminant as well as the ability of the gaseous species to bind to the surface to be protected. When the surface and associated bound species are exposed to radiation reactive species are formed that react with surface contaminants such as carbon or oxide films to form volatile products (e.g., CO, CO.sub.2) which desorb from the surface.

  9. Action Plan - Hanford Site

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Agreement Action Plan Tri-Party Agreement The Agreement Action Plan Announcements List of Approved Changes TPA Project Manager's Lists Modifications for Public Comment Data Management MP-14 WIDS Information Hanford Site Waste Management Units Report Hanford Public Involvement Plan Administrative Record (AR) Related Links Action Plan Email Email Page | Print Print Page | Text Increase Font Size Decrease Font Size Executive Summary 1.0 Introduction 1.1 Purpose 1.2 Regulatory Authorities 1.3

  10. US initiative on joint implementation: An overview

    SciTech Connect (OSTI)

    Dixon, R.K.

    1996-12-31

    More than 150 countries are now Party to United Nations Framework Convention on Climate Change, which seeks as its ultimate objective, to stabilize atmospheric concentrations of greenhouse gases at a level that would prevent dangerous human interference with the global climate system. As a step towards that goal, all Parties are to take measures to mitigate greenhouse gas emissions and to promote cooperation in the development and diffusion of technologies and practices that control or reduce emissions and enhance sinks of greenhouse gases. In the U.S. view, efforts between countries or entities within them to reduce net greenhouse gas emissions undertaken cooperatively, termed joint implementation (JI), holds significant potential both for reducing the threat of global climate change and for promoting sustainable development. To develop and operationalize the JI concept, the U.S. launched its Initiative on Joint Implementation (IJI) in October, 1993, and designed a program to attract private sector resources and to encourage the diffusion of innovative technologies to mitigate greenhouse gas emissions. The goals of U.S. IJI complement the principles of Decision 5, First Conference of the FCCC Parties, establishing an Activities Implemented Jointly pilot phase.

  11. Protective Actions and Reentry

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-08-21

    This volume defines appropriate protective actions and reentry of a site following an emergency. Canceled by DOE G 151.1-4.

  12. Mitigation for one & all: An integrated framework for mitigation of development impacts on biodiversity and ecosystem services

    SciTech Connect (OSTI)

    Tallis, Heather; Kennedy, Christina M.; Ruckelshaus, Mary; Goldstein, Joshua; Kiesecker, Joseph M.

    2015-11-15

    Emerging development policies and lending standards call for consideration of ecosystem services when mitigating impacts from development, yet little guidance exists to inform this process. Here we propose a comprehensive framework for advancing both biodiversity and ecosystem service mitigation. We have clarified a means for choosing representative ecosystem service targets alongside biodiversity targets, identified servicesheds as a useful spatial unit for assessing ecosystem service avoidance, impact, and offset options, and discuss methods for consistent calculation of biodiversity and ecosystem service mitigation ratios. We emphasize the need to move away from area- and habitat-based assessment methods for both biodiversity and ecosystem services towards functional assessments at landscape or seascape scales. Such comprehensive assessments more accurately reflect cumulative impacts and variation in environmental quality, social needs and value preferences. The integrated framework builds on the experience of biodiversity mitigation while addressing the unique opportunities and challenges presented by ecosystem service mitigation. These advances contribute to growing potential for economic development planning and execution that will minimize impacts on nature and maximize human wellbeing. - Highlights: • This is the first framework for biodiversity and ecosystem service mitigation. • Functional, landscape scale assessments are ideal for avoidance and offsets. • Servicesheds define the appropriate spatial extent for ecosystem service mitigation. • Mitigation ratios should be calculated consistently and based on standard factors. • Our framework meets the needs of integrated mitigation assessment requirements.

  13. Distributed generation implementation guidelines

    SciTech Connect (OSTI)

    Guzy, L.; O`Sullivan, J.B.; Jacobs, K.; Major, W.

    1999-11-01

    The overall economics of a distributed generation project is based on cost elements which include: Equipment and financing, fuel, displaced electricity cost, operation and maintenance. Of critical importance is how the facility is managed, including adequate provision for a comprehensive operator training program. Proper equipment maintenance and fuel procurement policy will also lead to greater system availability and optimal system economics. Various utility tariffs are available which may be economically attractive, with an added benefit to the utility of providing a peak shaving resource during peak periods. Changing modes of operation of the distributed generation system may affect staff readiness, require retraining and could affect maintenance costs. The degree of control and oversight that is provided during a project`s implementation and construction phases will impact subsequent maintenance and operating costs. The long term effect of siting impacts, such as building facades that restrict turbine inlet airflow will affect subsequent operations and require supplemental maintenance action. It is possible to site a variety of distributed generation technologies in settings which vary from urban to remote unattended locations with successful results from both an economic and operational perspective.

  14. Stream Classification Tool User Manual: For Use in Applications in Hydropower-Related Evironmental Mitigation

    SciTech Connect (OSTI)

    McManamay, Ryan A.; Troia, Matthew J.; DeRolph, Christopher R.; Samu, Nicole M.

    2016-01-01

    Stream classifications are an inventory of different types of streams. Classifications help us explore similarities and differences among different types of streams, make inferences regarding stream ecosystem behavior, and communicate the complexities of ecosystems. We developed a nested, layered, and spatially contiguous stream classification to characterize the biophysical settings of stream reaches within the Eastern United States (~ 900,000 reaches). The classification is composed of five natural characteristics (hydrology, temperature, size, confinement, and substrate) along with several disturbance regime layers, and each was selected because of their relevance to hydropower mitigation. We developed the classification at the stream reach level using the National Hydrography Dataset Plus Version 1 (1:100k scale). The stream classification is useful to environmental mitigation for hydropower dams in multiple ways. First, it creates efficiency in the regulatory process by creating an objective and data-rich means to address meaningful mitigation actions. Secondly, the SCT addresses data gaps as it quickly provides an inventory of hydrology, temperature, morphology, and ecological communities for the immediate project area, but also surrounding streams. This includes identifying potential reference streams as those that are proximate to the hydropower facility and fall within the same class. These streams can potentially be used to identify ideal environmental conditions or identify desired ecological communities. In doing so, the stream provides some context for how streams may function, respond to dam regulation, and an overview of specific mitigation needs. Herein, we describe the methodology in developing each stream classification layer and provide a tutorial to guide applications of the classification (and associated data) in regulatory settings, such as hydropower (re)licensing.

  15. Hellsgate Winter Range Mitigation Project; Long-term Management Plan, Project Report 1993, Final Draft.

    SciTech Connect (OSTI)

    Berger, Matthew T.

    1994-01-01

    A study was conducted on the Hellsgate Winter Range Mitigation Project area, a 4,943 acre ranch purchased for mitigating some habitat losses associated with the original construction of Grand Coulee Dam and innundation of habitat by Lake Roosevelt. A Habitat Evaluation Procedure (HEP) study was used to determine habitat quality and quantity baseline data and future projections. Target species used in the study were sharp-tailed grouse (Tympanuchus phasianellus), mule deer (Odocoileus hemoinus), mink (Mustela vison), spotted sandpiper (Actiius colchicus), bobcat (Felis reufs), blue grouse (Dendragapus obscurus), and mourning dove (Zenaida macroura). From field data collected, limiting life values or HSI's (Habitat Suitability Index's) for each indicator species was determined for existing habitats on project lands. From this data a long term management plan was developed. This report is designed to provide guidance for the management of project lands in relation to the habitat cover types discussed and the indicator species used to evaluate these cover types. In addition, the plan discusses management actions, habitat enhancements, and tools that will be used to enhance, protect and restore habitats to desired conditions. Through planned management actions biodiversity and vegetative structure can be optimized over time to reduce or eliminate, limiting HSI values for selected wildlife on project lands.

  16. Mitigation technologies and measures in energy sector of Kazakstan

    SciTech Connect (OSTI)

    Pilifosova, O.; Danchuk, D.; Temertekov, T.

    1996-12-31

    An important commitment in the UN Framework Convention on Climate Change is to conduct mitigation analysis and to communicate climate change measures and policies. In major part reducing CO{sub 2} as well as the other greenhouse gas emissions in Kazakstan, can be a side-product of measures addressed to increasing energy efficiency. Since such measures are very important for the national economy, mitigation strategies in the energy sector of Kazakstan are directly connected with the general national strategy of the energy sector development. This paper outlines the main measures and technologies in energy sector of Kazakstan which can lead to GHG emissions reduction and presents the results of current mitigation assessment. The mitigation analysis is addressed to energy production sector. A baseline and six mitigation scenarios were developed to evaluate the most attractive mitigation options, focusing on specific technologies which have been already included in sustainable energy programs. According to the baseline projection, Kazakstan`s CO{sub 2} emissions will not exceed their 1990 level until 2005. The potential for CO{sub 2} emission reduction is estimated to be about 11 % of the base line emission level by the end of considered period (in 2020). The main mitigation options in the energy production sector in terms of mitigation potential and technical and economical feasibility include rehabilitation of thermal power plants aimed to increasing efficiency, use of nuclear energy and further expansion in the use of hydro energy based on small hydroelectric power plants.

  17. Proactive DSA application and implementation

    SciTech Connect (OSTI)

    Draelos, T.; Hamilton, V.; Istrail, G.

    1998-05-03

    Data authentication as provided by digital signatures is a well known technique for verifying data sent via untrusted network links. Recent work has extended digital signatures to allow jointly generated signatures using threshold techniques. In addition, new proactive mechanisms have been developed to protect the joint private key over long periods of time and to allow each of the parties involved to verify the actions of the other parties. In this paper, the authors describe an application in which proactive digital signature techniques are a particularly valuable tool. They describe the proactive DSA protocol and discuss the underlying software tools that they found valuable in developing an implementation. Finally, the authors briefly describe the protocol and note difficulties they experienced and continue to experience in implementing this complex cryptographic protocol.

  18. Energy Efficiency Financing Program Implementation Primer

    Broader source: Energy.gov [DOE]

    This primer provides an overview of key considerations for state and local policymakers, utility energy efficiency program administrators, and program partners such as financial institutions and contractors in designing and implementing successful energy efficiency financing programs for existing buildings in the residential and commercial sectors. Author: State and Local Energy Efficiency Action Network

  19. Earned Value Management System (EVMS) Corrective Action Standard Operating Procedure

    Broader source: Energy.gov [DOE]

    This EVMS Corrective Action Standard Operating Procedure (ECASOP) serves as PM's primary reference for development of Corrective Action Requests (CARs) and Continuous Improvement Opportunities (CIOs), as well as the assessment of contractors procedures and implementation associated with Variance Analysis Reports (VARs) and Corrective Action Plans (CAPs) in accordance with the EIA-748 (current version) EVMS standard. The SOP is based on regulatory guidance and standardized processes based upon a common understanding of EVMS Industry and Government best practices for use by the Department of Energy (DOE). All information contained herein provides detailed processes to implement the requirements in DOE O 413.3 Current Version.

  20. A hot-cracking mitigation technique for welding high-strength aluminum alloy

    SciTech Connect (OSTI)

    Yang, Y.P.; Dong, P.; Zhang, J.; Tian, X.

    2000-01-01

    A hot-cracking mitigation technique for gas tungsten arc welding (GTAW) of high-strength aluminum alloy 2024 is presented. The proposed welding technique incorporates a trailing heat sink (an intense cooling source) with respect to the welding torch. The development of the mitigation technique was based on both detailed welding process simulation using advanced finite element techniques and systematic laboratory experiments. The finite element methods were used to investigate the detailed thermomechanical behavior of the weld metal that undergoes the brittle temperature range (BTR) during welding. As expected, a tensile deformation zone within the material BTR region was identified behind the weld pool under conventional GTA welding process conventional GTA welding process conditions for the aluminum alloy studied. To mitigate hot cracking, the tensile zone behind the weld pool must be eliminated or reduce to a satisfactory level if the weld metal hot ductility cannot be further improved. With detailed computational modeling, it was found that by the introduction of a trailing heat sink at some distance behind the welding arc, the tensile strain rate with respect to temperature in the zone encompassing the BTR region can be significantly reduced. A series of parametric studies were also conducted to derive optimal process parameters for the trailing heat sink. The experimental results confirmed the effectiveness of the trailing heat sink technique. With a proper implementation of the trailing heat sink method, hot cracking can be completely eliminated in welding aluminum alloy 2024 (AA 2024).

  1. Implementing Executive Order 13423

    Broader source: Energy.gov [DOE]

    Guide describes the instructions on the requirements and how fleets should implement the Executive Order 13423.

  2. GHG Mitigation potential and cost in tropical forestry - Relative role for agroforestry

    SciTech Connect (OSTI)

    Makundi, Willy R.; Sathaye, Jayant A.

    2004-01-01

    This paper summarizes studies of carbon mitigation potential (MP) and costs of forestry options in seven developing countries with a focus on the role of agroforestry. A common methodological approach known as comprehensive mitigation assessment process (COMAP) was used in each study to estimate the potential and costs between 2000 and 2030. The approach requires the projection of baseline and mitigation land-use scenarios derived from the demand for forest products and forestland for other uses such as agriculture and pasture. By using data on estimated carbon sequestration, emission avoidance, costs and benefits, the model enables one to estimate cost effectiveness indicators based on monetary benefit per t C, as well as estimates of total mitigation costs and potential when the activities are implemented at equilibrium level. The results show that about half the MP of 6.9 Gt C (an average of 223 Mt C per year) between 2000 and 2030 in the seven countries could be achieved at a negative cost, and the other half at costs not exceeding $100 per t C. Negative cost indicates that non-carbon revenue is sufficient to offset direct costs of about half of the options. The agroforestry options analyzed bear a significant proportion of the potential at medium to low cost per t C when compared to other options. The role of agroforestry in these countries varied between 6% and 21% of the MP, though the options are much more cost effective than most due to the low wage or opportunity cost of rural labor. Agroforestry options are attractive due to the large number of people and potential area currently engaged in agriculture, but they pose unique challenges for carbon and cost accounting due to the dispersed nature of agricultural activities in the tropics, as well as specific difficulties arising from requirements for monitoring, verification, leakage assessment and the establishment of credible baselines.

  3. Mitigation potential and cost in tropical forestry - relative role for agroforestry

    SciTech Connect (OSTI)

    Makundi, Willy R.; Sathaye, Jayant A.

    2004-01-01

    This paper summarizes studies of carbon mitigation potential (MP) and costs of forestry options in seven developing countries with a focus on the role of agroforestry. A common methodological approach known as comprehensive mitigation assessment process (COMAP) was used in each study to estimate the potential and costs between 2000 and 2030. The approach requires the projection of baseline and mitigation land-use scenarios derived from the demand for forest products and forestland for other uses such as agriculture and pasture. By using data on estimated carbon sequestration, emission avoidance, costs and benefits, the model enables one to estimate cost effectiveness indicators based on monetary benefit per t C, as well as estimates of total mitigation costs and potential when the activities are implemented at equilibrium level. The results show that about half the MP of 6.9 Gt C (an average of 223 Mt C per year) between 2000 and 2030 in the seven countries could be achieved at a negative cost, and the other half at costs not exceeding $100 per t C. Negative cost indicates that non-carbon revenue is sufficient to offset direct costs of about half of the options. The agroforestry options analyzed bear a significant proportion of the potential at medium to low cost per t C when compared to other options. The role of agroforestry in these countries varied between 6% and 21% of the MP, though the options are much more cost effective than most due to the low wage or opportunity cost of rural labor. Agroforestry options are attractive due to the large number of people and potential area currently engaged in agriculture, but they pose unique challenges for carbon and cost accounting due to the dispersed nature of agricultural activities in the tropics, as well as specific difficulties arising from requirements for monitoring, verification, leakage assessment and the establishment of credible baselines.

  4. Notes and Action Items

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Notes and Action Items Notes and Action Items ERSUG Action Items from June 1996 meeting at Germantown, MD Get DOE staff on mailers for broadcast of ERSUG issues Responsibility: Kendall and Kitchens Review and comment on ERSUG Proposal to SAC Responsibility: All of ERSUG Comments to Rick Kendall by July 17th email: ra_kendall@pnl.gov Fax : (509) 375-6631 Review and comment on Requirements Document "Greenbook" Responsibility: All of ERSUG Comments to Rick Kendall by August 7th email:

  5. Modeling the dynamic crush of impact mitigating materials

    SciTech Connect (OSTI)

    Logan, R.W.; McMichael, L.D.

    1995-05-12

    Crushable materials are commonly utilized in the design of structural components to absorb energy and mitigate shock during the dynamic impact of a complex structure, such as an automobile chassis or drum-type shipping container. The development and application of several finite-element material models which have been developed at various times at LLNL for DYNA3D will be discussed. Between the models, they are able to account for several of the predominant mechanisms which typically influence the dynamic mechanical behavior of crushable materials. One issue we addressed was that no single existing model would account for the entire gambit of constitutive features which are important for crushable materials. Thus, we describe the implementation and use of an additional material model which attempts to provide a more comprehensive model of the mechanics of crushable material behavior. This model combines features of the pre-existing DYNA models and incorporates some new features as well in an invariant large-strain formulation. In addition to examining the behavior of a unit cell in uniaxial compression, two cases were chosen to evaluate the capabilities and accuracy of the various material models in DYNA. In the first case, a model for foam filled box beams was developed and compared to test data from a 4-point bend test. The model was subsequently used to study its effectiveness in energy absorption in an aluminum extrusion, spaceframe, vehicle chassis. The second case examined the response of the AT-400A shipping container and the performance of the overpack material during accident environments selected from 10CFR71 and IAEA regulations.

  6. Corrective Action Decision Document/Closure Report for Corrective Action Unit 370: T-4 Atmospheric Test Site, Nevada Test Site, Nevada, Revision 0

    SciTech Connect (OSTI)

    Patrick Matthews

    2009-05-01

    This Corrective Action Decision Document/Closure Report has been prepared for Corrective Action Unit (CAU) 370, T-4 Atmospheric Test Site, located in Area 4 at the Nevada Test Site, Nevada, in accordance with the Federal Facility Agreement and Consent Order (FFACO). Corrective Action Unit 370 is comprised of Corrective Action Site (CAS) 04-23-01, Atmospheric Test Site T-4. The purpose of this Corrective Action Decision Document/Closure Report is to provide justification and documentation supporting the recommendation that no further corrective action is needed for CAU 370 due to the implementation of the corrective action of closure in place with administrative controls. To achieve this, corrective action investigation (CAI) activities were performed from June 25, 2008, through April 2, 2009, as set forth in the Corrective Action Investigation Plan for Corrective Action Unit 370: T-4 Atmospheric Test Site and Record of Technical Change No. 1.

  7. Remedial Action Performed

    Office of Legacy Management (LM)

    ... I 2. IMPLEMENTATION. DOE elements shall develop plans and ... defined as unconsolidated earth material, including rubble ... per minute (dpm) means the rare of emission by ndioanive ...

  8. Criticality Safety Controls Implementation, May 31, 2013 (HSS CRAD 45-18,

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Rev. 1) | Department of Energy Criticality Safety Controls Implementation, May 31, 2013 (HSS CRAD 45-18, Rev. 1) Criticality Safety Controls Implementation, May 31, 2013 (HSS CRAD 45-18, Rev. 1) The Department of Energy (DOE) has set expectations for implementing criticality safety controls that are selected to provide preventive and/or mitigative functions for specific potential accident scenarios. There are additional expectations for criticality safety controls that are also designated as

  9. Status of Corrective Actions

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Report on February 14 Incident at the Waste Isolation Pilot Project in Carlsbad, New Mexico April 12, 2012 x x Contact Communication Office (505) 667-7000 Corrective Actions...

  10. Notices ACTION: Notice.

    Office of Environmental Management (EM)

    8867 Federal Register Vol. 80, No. 215 Friday, November 6, 2015 Notices ACTION: Notice. SUMMARY: This notice announces EPA's receipt of an application 91163-EUP-R from Texas...

  11. Notices ACTION: Notice.

    Energy Savers [EERE]

    867 Federal Register Vol. 80, No. 215 Friday, November 6, 2015 Notices ACTION: Notice. SUMMARY: This notice announces EPA's receipt of an application 91163-EUP-R from Texas...

  12. Field Guide for Testing Existing Photovoltaic Systems for Ground Faults and Installing Equipment to Mitigate Fire Hazards: November 2012 - October 2013

    SciTech Connect (OSTI)

    Brooks, William

    2015-02-01

    Ground faults and arc faults are the two most common reasons for fires in photovoltaic (PV) arrays and methods exist that can mitigate the hazards. This report provides field procedures for testing PV arrays for ground faults, and for implementing high resolution ground fault and arc fault detectors in existing and new PV system designs.

  13. Mitigating Wind-Radar Interference | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Mitigating Wind-Radar Interference Mitigating Wind-Radar Interference April 1, 2013 - 12:54pm Addthis This is an excerpt from the First Quarter 2013 edition of the Wind Program R&D Newsletter. The U.S. Department of Energy (DOE) and federal agency partners recently completed the final operational field test in a 2-year initiative to accelerate the deployment of the most promising new technologies for mitigating radar interference caused by the physical and electromagnetic effects of wind

  14. Insider Threat - Material Control and Accountability Mitigation

    SciTech Connect (OSTI)

    Powell, Danny H; Elwood Jr, Robert H; Roche, Charles T

    2011-01-01

    compensating mitigation can decrease the risk of an insider performing a malicious act without detection.

  15. Climate Action Champion: Technical

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    energy.gov/betterbuildings Climate Action Champion: Technical Assistance to the City of Seattle Planning for Seattle's new Building Energy Code Overview The City of Seattle, identified as a Climate Action Champion (CAC) by the Department of Energy (DOE), is revising its 2012 Energy Code, already one of the most progressive in the country. Seattle has made a pledge to be carbon neutral by 2050. Seattle received technical assistance from the Pacific Northwest National Laboratory in order to

  16. double-action | netl.doe.gov

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Reversible Ionic Liquids as Double-Action Solvents for Efficient CO2 Capture Project No.: DE-NT0005287 In this project, the Georgia Tech Research Corporation is using totally novel chemistryto engender the dramatic changes needed for widespread implementation of CO2 capture in a both environmentally benign and economical process. Current methods of CO2 post-combustion recovery from coal-fired power plants focus on such techniques as absorption in aqueous ethanolamine scrubbers - and this is now

  17. Mitigating greenhouse gas emissions: Voluntary reporting

    SciTech Connect (OSTI)

    1997-10-01

    The Voluntary Reporting Program, developed pursuant to Section 1605(b) of the Energy Policy Act of 1992, permits corporations, government agencies, households, and voluntary organizations to report on their emissions of greenhouse gases, and on actions taken that have reduced or avoided emissions or sequestered carbon, to the Energy Information Administration (EIA). This, the second annual report of the Voluntary Reporting Program, describes information provided by the participating organizations on their aggregate emissions and emissions reductions, as well as their emissions reduction or avoidance projects, through 1995. This information has been compiled into a database that includes reports from 142 organizations and descriptions of 967 projects that either reduced greenhouse gas emissions or sequestered carbon. Fifty-one reporters also provided estimates of emissions, and emissions reductions achieved, for their entire organizations. The projects described actions taken to reduce emissions of carbon dioxide from energy production and use; to reduce methane and nitrous oxide emissions from energy use, waste management, and agricultural processes; to reduce emissions of halocarbons, such as CFCs and their replacements; and to increase carbon sequestration.

  18. RCRA corrective action program guide (Interim)

    SciTech Connect (OSTI)

    Not Available

    1993-05-01

    The US Department of Energy (DOE) is responsible for compliance with an increasingly complex spectrum of environmental regulations. One of the most complex programs is the corrective action program proposed by the US Environmental Protection Agency (EPA) under the authority of the Resource Conservation and Recovery Act (RCRA) as amended by the Hazardous and Solid Waste Amendments (HSWA). The proposed regulations were published on July 27, 1990. The proposed Subpart S rule creates a comprehensive program for investigating and remediating releases of hazardous wastes and hazardous waste constituents from solid waste management units (SWMUs) at facilities permitted to treat, store, or dispose of hazardous wastes. This proposed rule directly impacts many DOE facilities which conduct such activities. This guidance document explains the entire RCRA Corrective Action process as outlined by the proposed Subpart S rule, and provides guidance intended to assist those persons responsible for implementing RCRA Corrective Action at DOE facilities.

  19. Testing Controls to Mitigate Fatigue Loads in the Controls Advanced Research Turbine

    SciTech Connect (OSTI)

    Wright, A. D.; Fingersh, L. J.; Stol, K. A.

    2009-01-01

    Wind turbines are complex, nonlinear, dynamic systems forced by aerodynamic, gravitational, centrifugal, and gyroscopic loads. The aerodynamics of wind turbines is nonlinear, unsteady, and complex. Turbine rotors are subjected to a complicated three-dimensional (3D) turbulent wind inflow field with imbedded coherent vortices that drive fatigue loads and reduce lifetime. Design of control algorithms for wind turbines must account for multiple control objectives. Future large multi-megawatt turbines must be designed with lighter weight structures, using active controls to mitigate fatigue loads, maximize energy capture, and add active damping to maintain stability for these dynamically active structures operating in a complex environment. Researchers at the National Renewable Energy Laboratory are designing, implementing, and testing advanced controls to maximize energy extraction and reduce structural dynamic loads. These control designs are based on a linear model of the turbine that is generated by specialized modeling software. This paper describes testing of a control algorithm to mitigate blade, tower, and drivetrain loads using advanced state-space control methods. The controller uses independent blade pitch to regulate the turbine's speed in Region 3, mitigate the effects of shear across the rotor disk, and add active damping to the tower's first fore-aft bending mode. Additionally, a separate generator torque control loop is designed to add active damping to the tower's first side-side mode and the first drivetraintorsion mode. This paper discusses preliminary implementation and field tests of this controller in the Controls Advanced Research Turbine at the National Renewable Energy Laboratory. Also included are preliminary comparisons of the performance of this controller to results from a typical baseline Proportional-Integral-Derivative controller designed with just Region 3 speed regulation as the goal.

  20. Wildlife and Wildlife Habitat Mitigation Plan for Libby Hydroelectric Project, Final Report.

    SciTech Connect (OSTI)

    Mundinger, John

    1985-01-01

    This report describes the proposed mitigation plan for wildlife losses attributable to the construction of the Libby hydroelectric project. Mitigation objectives and alternatives, the recommended mitigation projects, and the crediting system for each project are described by each target species. The report describes mitigation that has already taken place and 8 recommended mitigation projects designed to complete total wildlife mitigation. 8 refs., 2 figs., 12 tabs.

  1. Global climate change mitigation and sustainable forest management--The challenge of monitoring and verification

    SciTech Connect (OSTI)

    Makundi, Willy R.

    1997-12-31

    In this paper, sustainable forest management is discussed within the historical and theoretical framework of the sustainable development debate. The various criteria and indicators for sustainable forest management put forth by different institutions are critically explored. Specific types of climate change mitigation policies/projects in the forest sector are identified and examined in the light of the general criteria for sustainable forest management. Areas of compatibility and contradiction between the climate mitigation objectives and the minimum criteria for sustainable forest management are identified and discussed. Emphasis is put on the problems of monitoring and verifying carbon benefits associated with such projects given their impacts on pre-existing policy objectives on sustainable forest management. The implications of such policy interactions on assignment of carbon credits from forest projects under Joint Implementation/Activities Implemented Jointly initiatives are discussed. The paper concludes that a comprehensive monitoring and verification regime must include an impact assessment on the criteria covered under other agreements such as the Biodiversity and/or Desertification Conventions. The actual carbon credit assigned to a specific project should at least take into account the negative impacts on the criteria for sustainable forest management. The value of the impacts and/or the procedure to evaluate them need to be established by interested parties such as the Councils of the respective Conventions.

  2. Corrective Action Decision Document/Closure Report for Corrective Action Unit 105: Area 2 Yucca Flat Atmospheric Test Sites, Nevada National Security Site, Nevada, Revision 1

    SciTech Connect (OSTI)

    Matthews, Patrick

    2014-01-01

    The purpose of this Corrective Action Decision Document/Closure Report is to provide justification and documentation supporting the recommendation that no further corrective action is needed for CAU 105 based on the implementation of the corrective actions. Corrective action investigation (CAI) activities were performed from October 22, 2012, through May 23, 2013, as set forth in the Corrective Action Investigation Plan for Corrective Action Unit 105: Area 2 Yucca Flat Atmospheric Test Sites; and in accordance with the Soils Activity Quality Assurance Plan, which establishes requirements, technical planning, and general quality practices.

  3. 324 Building fire hazards analysis implementation plan

    SciTech Connect (OSTI)

    Eggen, C.D.

    1998-09-16

    In March 1998, the 324 Building Fire Hazards Analysis (FHA) (Reference 1) was approved by the US Department of Energy, Richland Operations Office (DOE-RL) for implementation by B and W Hanford Company (BWHC). The purpose of the FHA was to identify gaps in compliance with DOE Order 5480.7A (Reference 2) and Richland Operations Office Implementation Directive (RLID) 5480.7 (Reference 3), especially in regard to loss limitation. The FHA identified compliance gaps in six areas and provided 20 recommendations to bring the 324 Building into compliance with DOE Order 5480.7A. Additionally, one observation was provided. To date, four of the recommendations and the one observation have been completed. Actions identified for seven of the recommendations are currently in progress. Exemption requests will be transmitted to DOE-RL for three of the recommendations. Six of the recommendations are related to future shut down activities of the facility and the corrective actions are not being addressed as part of this plan. The actions for recommendations associated with the safety related part of the 324 Building and operation of the cells and support areas were evaluated using the Unreviewed Safety Question (USQ) process. Major Life Safety Code concerns have been corrected. The status of the recommendations and actions was confirmed during the July 1998 Fire Protection Assessment. BVMC will use this Implementation Plan to bring the 324 Building and its operation into compliance with DOE Order 5480.7A and RLID 5480.7.

  4. 327 Building fire hazards analysis implementation plan

    SciTech Connect (OSTI)

    Eggen, C.D.

    1998-09-16

    In March 1998, the 327 Building Fire Hazards Analysis (FRA) (Reference 1) was approved by the US Department of Energy, Richland Operations Office (DOE-RL) for implementation by B and W Hanford Company (B and WHC). The purpose of the FHA was to identify gaps in compliance with DOE Order 5480.7A (Reference 2) and Richland Operations Office Implementation Directive (RLID) 5480.7 (Reference 3), especially in regard to loss limitation. The FHA identified compliance gaps in five areas and provided nine recommendations (11 items) to bring the 327 Building into compliance. To date, actions for five of the 11 items have been completed. Exemption requests will be transmitted to DOE-RL for two of the items. Corrective actions have been identified for the remaining four items. The completed actions address combustible loading requirements associated with the operation of the cells and support areas. The status of the recommendations and actions was confirmed during the July 1998 Fire Protection Assessment. B and WHC will use this Implementation Plan to bring the 327 Building and its operation into compliance with DOE Order 5480.7A and RLID 5480.7.

  5. Gearbox Typical Failure Modes, Detection, and Mitigation Methods (Presentation)

    SciTech Connect (OSTI)

    Sheng, S.

    2014-01-01

    This presentation was given at the AWEA Operations & Maintenance and Safety Seminar and focused on what the typical gearbox failure modes are, how to detect them using detection techniques, and strategies that help mitigate these failures.

  6. Market-based Wildlife Mitigation in Wyoming: A Primer | Open...

    Open Energy Info (EERE)

    A Primer Jump to: navigation, search OpenEI Reference LibraryAdd to library Report: Market-based Wildlife Mitigation in Wyoming: A Primer Abstract Covers the basics of...

  7. Introduction to Administrative Programs that Mitigate the Insider Threat

    SciTech Connect (OSTI)

    Gerke, Gretchen K.; Rogers, Erin; Landers, John; DeCastro, Kara

    2012-09-01

    This presentation begins with the reality of the insider threat, then elaborates on these tools to mitigate the insider threat: Human Reliability Program (HRP); Nuclear Security Culture (NSC) Program; Employee Assistance Program (EAP).

  8. National Mitigation Planning in Agriculture: Review and Guidelines...

    Open Energy Info (EERE)

    Simple Website: www.fao.orgdocrep017i3237ei3237e.pdf Language: English This review of national greenhouse gas (GHG) mitigation planning in the agriculture sector provides...

  9. EA-1096: Washington Wildlife Mitigation Projects (Programmatic), Washington

    Broader source: Energy.gov [DOE]

    This EA evaluates the environmental impacts of the proposal for the U.S. Department of Energy Bonneville Power Administration to fund the portion of the Washington Wildlife Mitigation Agreement...

  10. Over-Pressurized Drums: Their Causes and Mitigation

    SciTech Connect (OSTI)

    Simmons, Fred; Kuntamukkula, Murty; Quigley, David; Robertson, Janeen; Freshwater, David

    2009-07-10

    Having to contend with bulging or over-pressurized drums is, unfortunately, a common event for people storing chemicals and chemical wastes. (Figure 1) The Department of Energy alone reported over 120 incidents of bulging drums between 1992 and 1999 (1). Bulging drums can be caused by many different mechanisms, represent a number of significant hazards and can be tricky to mitigate. In this article, we will discuss reasons or mechanisms by which drums can become over-pressurized, recognition of the hazards associated with and mitigation of over-pressurized drums, and methods that can be used to prevent drum over-pressurization from ever occurring. Drum pressurization can represent a significant safety hazard. Unless recognized and properly mitigated, improperly manipulated pressurized drums can result in employee exposure, employee injury, and environmental contamination. Therefore, recognition of when a drum is pressurized and knowledge of pressurized drum mitigation techniques is essential.

  11. Mitigation of cache memory using an embedded hard-core PPC440 processor in a Virtex-5 Field Programmable Gate Array.

    SciTech Connect (OSTI)

    Learn, Mark Walter

    2010-02-01

    Sandia National Laboratories is currently developing new processing and data communication architectures for use in future satellite payloads. These architectures will leverage the flexibility and performance of state-of-the-art static-random-access-memory-based Field Programmable Gate Arrays (FPGAs). One such FPGA is the radiation-hardened version of the Virtex-5 being developed by Xilinx. However, not all features of this FPGA are being radiation-hardened by design and could still be susceptible to on-orbit upsets. One such feature is the embedded hard-core PPC440 processor. Since this processor is implemented in the FPGA as a hard-core, traditional mitigation approaches such as Triple Modular Redundancy (TMR) are not available to improve the processor's on-orbit reliability. The goal of this work is to investigate techniques that can help mitigate the embedded hard-core PPC440 processor within the Virtex-5 FPGA other than TMR. Implementing various mitigation schemes reliably within the PPC440 offers a powerful reconfigurable computing resource to these node-based processing architectures. This document summarizes the work done on the cache mitigation scheme for the embedded hard-core PPC440 processor within the Virtex-5 FPGAs, and describes in detail the design of the cache mitigation scheme and the testing conducted at the radiation effects facility on the Texas A&M campus.

  12. Recent Developments in Field Response for Mitigation of Radiological

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Incidents | Department of Energy Developments in Field Response for Mitigation of Radiological Incidents Recent Developments in Field Response for Mitigation of Radiological Incidents Carlos Corredor*, Department of Energy; Charley Yu, Argonne National Labs Abstract: Since September 11, 2001, there has been a large effort by the government to develop new methods to reduce the consequence of potential radiological incidents. This is evident in the enhancement of technologies and methods to

  13. Recent Diesel Engine Emission Mitigation Activities of the Maritime

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Administration Energy Technologies Program | Department of Energy Diesel Engine Emission Mitigation Activities of the Maritime Administration Energy Technologies Program Recent Diesel Engine Emission Mitigation Activities of the Maritime Administration Energy Technologies Program 2003 DEER Conference Presentation: Maritime Administration 2003_deer_gore.pdf (759.73 KB) More Documents & Publications The Maritime Administration's Energy and Emissions Program - Part 2 Reduction of Emissions

  14. EERE Success Story-Mitigating Potential Environmental Impacts of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Development | Department of Energy Mitigating Potential Environmental Impacts of Energy Development EERE Success Story-Mitigating Potential Environmental Impacts of Energy Development April 15, 2013 - 12:00am Addthis Partnering with EERE, Normandeau Associates of Bedford, New Hampshire, developed a tool that characterizes the risk for bird and bat species that may be susceptible to collisions with wind turbines. This tool will be used in environmental decision-making for the planning,

  15. 2011 River Corridor Closure Contractor Revegetation and Mitigation Monitoring Report

    SciTech Connect (OSTI)

    West, W. J.; Lucas, J. G.; Gano, K. A.

    2011-11-14

    This report documents the status of revegetation projects and natural resources mitigation efforts conducted for remediated waste sites and other activities associated with the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 cleanup of National Priorities List waste sites at Hanford. This report contains the vegetation monitoring data that was collected in the spring and summer of 2011 from the River Corridor Closure Contractors revegetation and mitigation areas on the Hanford Site.

  16. Advanced Technology Development and Mitigation | National Nuclear Security

    National Nuclear Security Administration (NNSA)

    Administration | (NNSA) Advanced Technology Development and Mitigation The Advanced Technology Development and Mitigation (ATDM) subprogram includes laboratory code and computer engineering and science projects that pursue long-term simulation and computing goals relevant to the broad national security missions of the NNSA. It addresses the need to adapt current integrated design codes and build new codes that are attuned to emerging computing technologies. Performing this work within the

  17. 2010 River Corridor Closure Contractor Revegetation and Mitigation Monitoring Report

    SciTech Connect (OSTI)

    C. T. Lindsey, A. L. Johnson

    2010-09-30

    This report documents eh status of revegetation projects and natural resources mitigation efforts conducted for remediated waste sites and other activities associated with CERLA cleanup of National Priorities List waste sites at Hanford. This report contains vegetation monitoring data that were collected in the spring and summer of 2010 from the River Corridor Closure Contract’s revegetation and mitigation areas on the Hanford Site.

  18. 2014 WIND POWER PROGRAM PEER REVIEW-MARKET BARRIER MITIGATION

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Market Barrier Mitigation March 6-27, 2014 Wind Energy Technologies PR-5000-62152 2 Contents Market Barrier Mitigation Siting, Environmental and Permitting- Karin Sinclair, National Renewable Energy Laboratory Developing high-resolution spatial data of migration corridors for avian species of concern in regions of high potential wind development- Todd Katzner, West Virginia University Deepwater Offshore Bat Monitoring Program-Steven K Pelletier, Stantec Consulting Services, Inc. A Synchronized

  19. Implementing HB 3672

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Ten Year Energy Action Plan Goal 1: Meet 100 percent of new electric load growth through energy efficiency and conservation Goal 2: Remove barriers to developing clean energy...

  20. Uranium Mill Tailings Remedial Action Project 1993 Environmental Report

    SciTech Connect (OSTI)

    Not Available

    1994-10-01

    This annual report documents the Uranium Mill Tailing Remedial Action (UMTRA) Project environmental monitoring and protection program. The UMTRA Project routinely monitors radiation, radioactive residual materials, and hazardous constituents at associated former uranium tailings processing sites and disposal sites. At the end of 1993, surface remedial action was complete at 10 of the 24 designated UMTRA Project processing sites. In 1993 the UMTRA Project office revised the UMTRA Project Environmental Protection Implementation Plan, as required by the US DOE. Because the UMTRA Project sites are in different stages of remedial action, the breadth of the UMTRA environmental protection program differs from site to site. In general, sites actively undergoing surface remedial action have the most comprehensive environmental programs for sampling media. At sites where surface remedial action is complete and at sites where remedial action has not yet begun, the environmental program consists primarily of surface water and ground water monitoring to support site characterization, baseline risk assessments, or disposal site performance assessments.

  1. ES H action plan

    SciTech Connect (OSTI)

    Not Available

    1991-01-01

    This document contains planned actions to correct the deficiencies identified in the Pre-Tiger Team Self-Assessment (PTTSA), January 1991, of Sandia National Laboratories (SNL -- Albuquerque, New Mexico; Tonopah, Nevada; and Kauai, Hawaii). The Self-Assessment was conducted by a Self-Assessment Working Group consisting of 19 department managers, with support from Environment, Safety, and Health (ES H) professionals, from October through December 1990. Findings from other past audits, dating back to 1985, were reviewed and compared with the PTTSA findings to determine if additional findings, key findings, or root causes were warranted. The resulting ES H Action Plan and individual planned actions were prepared by the ES H Action Plan Project Group with assistance from the Program owners/authors during February and March 1991. The plan was reviewed by SNL Management in April 1991. This document serves as a planning instrument for the Laboratories to aid in the scoping and sizing of activities related to ES H compliance for the coming five years. It will be modified as required to ensure a workload/funding balance and to address the findings resulting from the Tiger Team assessment at SNL, Albuquerque. The process of producing this document has served well to prepare SNL, Albuquerque, for the coming task of producing the required post-Tiger Team action plan document. 8 tabs.

  2. A statistical approach to designing mitigation for induced ac voltages

    SciTech Connect (OSTI)

    Dabkowski, J. [Electro Sciences, Inc., Crystal Lake, IL (United States)

    1996-08-01

    Induced voltage levels on buried pipelines collocated with overhead electric power transmission lines are usually mitigated by means of grounding the pipeline. Maximum effectiveness is obtained when grounds are placed at discrete locations along the pipeline where the peak induced voltages occur. The degree of mitigation achieved is dependent upon the local soil resistivity at these locations. On occasion it may be necessary to employ an extensive distributed grounding system, for example, a parallel buried wire connected to the pipe at periodic intervals. In this situation the a priori calculation of mitigated voltage levels is sometimes made assuming an average value for the soil resistivity. Over long distances, however, the soil resistivity generally varies as a log-normally distributed random variable. The effect of this variability upon the predicted mitigated voltage levels is examined. It is found that the predicted levels exhibit a statistical variability which precludes a precise determination of the mitigated voltage levels. Thus, post commissioning testing of the emplaced mitigation system is advisable.

  3. Carbon mitigation potential and costs of forestry options in Brazil, China, India, Indonesia, Mexico, the Philippines and Tanzania

    SciTech Connect (OSTI)

    Sathaye, J.; Makundi, W.; Andrasko, K.; Boer, R.; Ravindranath, N.; Sudha, P.; Rao, S.; Lasco, R.; Pulhin, F.; Masera, O.; Ceron, A.; Ordonez, J.; Deying, X.; Zhang, X.; Zuomin, S.

    2001-01-01

    This paper summarizes studies of carbon (C) mitigation potential and costs of about 40 forestry options in seven developing countries. Each study uses the same methodological approach - Comprehensive Mitigation Assessment Process (COMAP) - to estimate the above parameters between 2000 and 2030. The approach requires the projection of baseline and mitigation land-use scenarios. Coupled with data on a per ha basis on C sequestration or avoidance, and costs and benefits, it allows the estimation of monetary benefit per Mg C, and the total costs and carbon potential. The results show that about half (3.0 Pg C) the cumulative mitigation potential of 6.2 Petagram (Pg) C between 2000 and 2030 in the seven countries (about 200 x 106 Mg C yr-1) could be achieved at a negative cost and the remainder at costs ranging up to $100 Mg C-1. About 5 Pg C could be achieved, at a cost less than $20 per Mg C. Negative cost potential indicates that non-carbon revenue is sufficient to offset direct costs of these options. The achievable potential is likely to be smaller, however, due to market, institutional, and sociocultural barriers that can delay or prevent the implementation of the analyzed options.

  4. Corrective Action Plan for Corrective Action Unit 562: Waste Systems, Nevada National Security Site, Nevada

    SciTech Connect (OSTI)

    NSTec Environmental Restoration

    2011-04-30

    This Corrective Action Plan has been prepared for Corrective Action Unit (CAU) 562, Waste Systems, in accordance with the Federal Facility Agreement and Consent Order (1996; as amended March 2010). CAU 562 consists of 13 Corrective Action Sites (CASs) located in Areas 2, 23, and 25 of the Nevada National Security Site. Site characterization activities were performed in 2009 and 2010, and the results are presented in Appendix A of the Corrective Action Decision Document for CAU 562. The scope of work required to implement the recommended closure alternatives is summarized. (1) CAS 02-26-11, Lead Shot, will be clean closed by removing shot. (2) CAS 02-44-02, Paint Spills and French Drain, will be clean closed by removing paint and contaminated soil. As a best management practice (BMP), asbestos tile will be removed. (3) CAS 02-59-01, Septic System, will be clean closed by removing septic tank contents. As a BMP, the septic tank will be removed. (4) CAS 02-60-01, Concrete Drain, contains no contaminants of concern (COCs) above action levels. No further action is required; however, as a BMP, the concrete drain will be removed. (5) CAS 02-60-02, French Drain, was clean closed. Corrective actions were completed during corrective action investigation activities. As a BMP, the drain grates and drain pipe will be removed. (6) CAS 02-60-03, Steam Cleaning Drain, will be clean closed by removing contaminated soil. As a BMP, the steam cleaning sump grate and outfall pipe will be removed. (7) CAS 02-60-04, French Drain, was clean closed. Corrective actions were completed during corrective action investigation activities. (8) CAS 02-60-05, French Drain, will be clean closed by removing contaminated soil. (9) CAS 02-60-06, French Drain, contains no COCs above action levels. No further action is required. (10) CAS 02-60-07, French Drain, requires no further action. The french drain identified in historical documentation was not located during corrective action investigation

  5. Notes and Action Items

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Notes and Action Items Notes and Action Items Report on the NUGEX business meeting of June 6, 2000, in Oak Ridge Minute notes by Bas Braams First of all, many thanks to the organizers of the preceding NUG meeting: Roberta Boucher, David Dean, Brian Hingerty, Bill Kramer, Donald Spong and Malcolm Stocks. Likewise thanks to Brian Hingerty and Mike Minkoff for organizing the Users Helping Users events, and to Tom DeBoni, Osni Marques, Jeffrey Squyres and David Turner for the NERSC training classes.

  6. Scenarios of forestry carbon sequestration measures in the Russian Federation and priorities for action plan

    SciTech Connect (OSTI)

    Kokorin, A.O.

    1996-12-31

    Development of forestry mitigation strategy under Russian transition economy conditions has many difficulties and specific features. The most important factors are: shortage in funds; absence of well defined legislation, rules and standards; absence of adequate control systems; weak transport infrastructure and export problems. Assessment of economic possibilities, potential, short- and middle-term measures show that strategies have to be focused on improvement and promotion of current carbon sequestration activity. Five baseline forestry scenario (No. 1) and four other scenarios (No. 2 - No. 5) for 2000-2040 were developed. Each scenario covers all forested area but provides separate analysis of 30 `forestry ecoregions`. Three types of forestry management were included in scenarios: clear-cut logging and reforestation (by scenarios No. 2 and No. 3); selective logging and thinning (No. 4); measures to prevent and manage fires (No. 5). The baseline scenario results in a constant net-sink of about 150 MtC/yr. An increase in clear-cut logging on the basis of current forestry practice will cause a rapid drop of net-sink. Implementation of a modest increase in clear-cut logging with active forest fire and selective logging measures could provide with a slight increase of net-sink. Consideration of scenarios helps identify regional forestry priorities for Russian Climate Change Action Plan. The priorities by region include: European-Ural: (1) creation of economy mechanism to increase forestry effectiveness on the same cutting areas, (2) assistance to natural reforestation. Central and North-East Siberia: promotion of forest fire protection system. South Siberia and Primorie and Priamurie: limit of clear-cut logging and creation market situation for better forestry efficiency. The proposed Joint Implementation Vologda reforestation project which is being considered now by special bodies of the USA and the Russian Federation is in good agreement with these priorities.

  7. Corrective Action Plan for Corrective Action Unit 139: Waste Disposal Sites, Nevada Test Site, Nevada

    SciTech Connect (OSTI)

    NSTec Environmental Restoration

    2007-07-01

    Corrective Action Unit (CAU) 139, Waste Disposal Sites, is listed in the Federal Facility Agreement and Consent Order (FFACO) of 1996 (FFACO, 1996). CAU 139 consists of seven Corrective Action Sites (CASs) located in Areas 3, 4, 6, and 9 of the Nevada Test Site (NTS), which is located approximately 65 miles (mi) northwest of Las Vegas, Nevada (Figure 1). CAU 139 consists of the following CASs: CAS 03-35-01, Burn Pit; CAS 04-08-02, Waste Disposal Site; CAS 04-99-01, Contaminated Surface Debris; CAS 06-19-02, Waste Disposal Site/Burn Pit; CAS 06-19-03, Waste Disposal Trenches; CAS 09-23-01, Area 9 Gravel Gertie; and CAS 09-34-01, Underground Detection Station. Details of the site history and site characterization results for CAU 139 are provided in the approved Corrective Action Investigation Plan (CAIP) (U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office [NNSA/NSO], 2006) and in the approved Corrective Action Decision Document (CADD) (NNSA/NSO, 2007). The purpose of this Corrective Action Plan (CAP) is to present the detailed scope of work required to implement the recommended corrective actions as specified in Section 4.0 of the approved CADD (NNSA/NSO, 2007). The approved closure activities for CAU 139 include removal of soil and debris contaminated with plutonium (Pu)-239, excavation of geophysical anomalies, removal of surface debris, construction of an engineered soil cover, and implementation of use restrictions (URs). Table 1 presents a summary of CAS-specific closure activities and contaminants of concern (COCs). Specific details of the corrective actions to be performed at each CAS are presented in Section 2.0 of this report.

  8. Appendix VI Corrective Action Strategy

    National Nuclear Security Administration (NNSA)

    ......... 15 3.0 Underground Test Area............ 13 3-1 Underground Test Area Corrective Action ...

  9. Probability, consequences, and mitigation for lightning strikes to Hanford site high-level waste tanks

    SciTech Connect (OSTI)

    Zach, J.J.

    1996-08-01

    The purpose of this report is to summarize selected lightning issues concerning the Hanford Waste Tanks. These issues include the probability of lightning discharge striking the area immediately adjacent to a tank including a riser, the consequences of significant energy deposition from a lightning strike in a tank, and mitigating actions that have been or are being taken. The major conclusion of this report is that the probability of a lightning strike depositing sufficient energy in a tank to cause an effect on employees or the public is unlikely;but there are insufficient, quantitative data on the tanks and waste to prove that. Protection, such as grounding of risers and air terminals on existing light poles, is recommended.

  10. Probability, consequences, and mitigation for lightning strikes of Hanford high level waste tanks

    SciTech Connect (OSTI)

    Zach, J.J.

    1996-06-05

    The purpose of this report is to summarize selected lightning issues concerning the Hanford Waste Tanks. These issues include the probability of a lightning discharge striking the area immediately adjacent to a tank including a riser, the consequences of significant energy deposition from a lightning strike in a tank, and mitigating actions that have been or are being taken. The major conclusion of this report is that the probability of a lightning strike deposition sufficient energy in a tank to cause an effect on employees or the public is unlikely;but there are insufficient, quantitative data on the tanks and waste to prove that. Protection, such as grounding of risers and air terminals on existing light poles, is recommended.

  11. Hellsgate Big Game Winter Range Wildlife Mitigation Site Specific Management Plan for the Hellsgate Project.

    SciTech Connect (OSTI)

    Berger, Matthew T.; Judd, Steven L.

    1999-01-01

    This report contains a detailed site-specific management plan for the Hellsgate Winter Range Wildlife Mitigation Project. The report provides background information about the mitigation process, the review process, mitigation acquisitions, Habitat Evaluation Procedures (HEP) and mitigation crediting, current habitat conditions, desired future habitat conditions, restoration/enhancements efforts and maps.

  12. Overview of the State and Local Energy Efficiency Action Network

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    SEE Action Update for the State and Local Energy Advisory Board Johanna Zetterberg SEE Action Network Coordinator March 12, 2013 www.seeaction.energy.gov * Executive Group met Jan 30 th (Washington DC) to review Working Group plans for this year * New guidance documents were published - Energy Efficiency Program Impact Evaluation Guide - Guide for Regulators on Data Access and Privacy - Guide to the Successful Implementation of State Combined Heat and Power (CHP) Policies * New events were held

  13. Climate Action Champions: Blue Lake Rancheria Tribe, CA | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy Blue Lake Rancheria Tribe, CA Climate Action Champions: Blue Lake Rancheria Tribe, CA The Blue Lake Rancheria, California, a federally recognized Native American tribal Government and community, is located on over 100 acres of land spanning the scenic Mad River in northwestern California. In its operational strategy, the Tribe has implemented the ‘seven generations’ philosophy, where actions taken today will have a positive impact for seven generations to come. This results

  14. Implementing Bayesian Statistics

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Appliance & Equipment Standards » Implementation, Certification and Enforcement Implementation, Certification and Enforcement The U.S. Department of Energy (DOE) is authorized by the Energy Policy and Conservation Act of 1975 (as amended) to enforce compliance with the energy and water conservation standards established for certain consumer products and commercial and industrial equipment. To ensure the implementation of the current standards for covered appliances and equipment, DOE has

  15. Status of research toward the ITER disruption mitigation system

    SciTech Connect (OSTI)

    Hollmann, E. M.; Izzo, V. A.; Aleynikov, P. B.; Lehnen, M.; Snipes, J. A.; Fülöp, T.; Humphreys, D. A.; Lukash, V. E.; Papp, G.; Pautasso, G.; Saint-Laurent, F.

    2015-02-15

    An overview of the present status of research toward the final design of the ITER disruption mitigation system (DMS) is given. The ITER DMS is based on massive injection of impurities, in order to radiate the plasma stored energy and mitigate the potentially damaging effects of disruptions. The design of this system will be extremely challenging due to many physics and engineering constraints such as limitations on port access and the amount and species of injected impurities. Additionally, many physics questions relevant to the design of the ITER disruption mitigation system remain unsolved such as the mechanisms for mixing and assimilation of injected impurities during the rapid shutdown and the mechanisms for the subsequent formation and dissipation of runaway electron current.

  16. Fuel Flexibility: Landfill Gas Contaminant Mitigation for Power Generation

    SciTech Connect (OSTI)

    Storey, John Morse; Theiss, Timothy J; Kass, Michael D; FINNEY, Charles E A; Lewis, Samuel; Kaul, Brian C; Besmann, Theodore M; Thomas, John F; Rogers, Hiram; Sepaniak, Michael

    2014-04-01

    This research project focused on the mitigation of silica damage to engine-based renewable landfill gas energy systems. Characterization of the landfill gas siloxane contamination, combined with characterization of the silica deposits in engines, led to development of two new mitigation strategies. The first involved a novel method for removing the siloxanes and other heavy contaminants from the landfill gas prior to use by the engines. The second strategy sought to interrupt the formation of hard silica deposits in the engine itself, based on inspection of failed landfill gas engine parts. In addition to mitigation, the project had a third task to develop a robust sensor for siloxanes that could be used to control existing and/or future removal processes.

  17. SAVEnergy Action Plans

    SciTech Connect (OSTI)

    Mayo, K.; Westby, R.; deMonsabert, S.; Ginsberg, M.

    1994-04-01

    The Department of Energy`s Federal Energy Management Program (FEMP) is charged with carrying out key sections of EPACT and Executive Order 12903, to make the Federal government operate more efficiently. A congressionally mandated energy and water conservation audit program is one component of this growing DOE program. This paper traces the SAVEnergy Action Plan program throughout its development from (1) identifying projects and Agency champions, (2) establishing a protocol and fitting auditors into the program, (3) developing a data base to track the audits and measure their success, and (4) evaluating the process, learning from mistakes, and charting and transferring successes. A major tenet of the SAVEnergy program is to proactively prescreen all audit activities to ensure that -- where audits are done and Action Plans completed -- projects will be done.

  18. Climate Action Champions: Metropolitan Washington Council of...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    baseline regional greenhouse gas inventory, examines potential climate change impacts, evaluates mitigation and adaptation strategies, and establishes greenhouse gas emission ...

  19. Business Case for Energy Efficiency in Support of Climate Change Mitigation, Economic and Societal Benefits in China

    SciTech Connect (OSTI)

    McNeil, Michael A.; Bojda, Nicholas; Ke, Jing; Qin, Yining; de la Rue du Can, Stephane; Fridley, David; Letschert, Virginie E.; McMahon, James E.

    2011-08-18

    continues at a rapid pace. Growth in this sector means that commercial lighting and HVAC will play an increasingly important role in energy demand in China. The outlook for efficiency improvement in China is encouraging, since the Chinese national and local governments have implemented significant policies to contain energy intensity and announced their intention to continue and accelerate these. In particular, the Chinese appliance standards program, first established in 1989, was significantly strengthened and modernized after the passage of the Energy Conservation Law of 1997. Since then, the program has expanded to encompass over 30 equipment types (including motor vehicles). The current study suggests that, in spite of these efforts, there is significant savings to be captured through wide adoption of technologies already available on the Chinese market. The approach of the study is to assess the impact of short-term actions on long-term impacts. 'Short-term' market transformation is assumed to occur by 2015, while 'long-term' energy demand reduction impacts are assessed in 2030. In the intervening years, most but not all of the equipment studied will turn over completely. Early in 2011, the Chinese government announced a plan to reduce carbon dioxide emissions intensity (per unit GDP) by 16% by 2015 as part of the 12th five year plan. These targets are consistent with longer term goals to reduce emissions intensity 40-45% relative to 2005 levels by 2020. The efforts of the 12th FYP focus on short-term gains to meet the four-year targets, and concentrate mainly in industry. Implementation of cost-effective technologies for all new equipment in the buildings sector thus is largely complementary to the 12th FYP goals, and would provide a mechanism to sustain intensity reductions in the medium and long term. The 15-year time frame is significant for many products, in the sense that delay of implementation postpones economic benefits and mitigation of emissions of carbon

  20. Columbia Basin Wildlife Mitigation Project : Rainwater Wildlife Area Final Management Plan.

    SciTech Connect (OSTI)

    Childs, Allen

    2002-03-01

    This Draft Management Plan has been developed by the Confederated Tribes of the Umatilla Indian Reservation (CTUIR) to document how the Rainwater Wildlife Area (formerly known as the Rainwater Ranch) will be managed. The plan has been developed under a standardized planning process developed by the Bonneville Power Administration (BPA) for Columbia River Basin Wildlife Mitigation Projects (See Appendix A and Guiding Policies Section below). The plan outlines the framework for managing the project area, provides an assessment of existing conditions and key resource issues, and presents an array of habitat management and enhancement strategies. The plan culminates into a 5-Year Action Plan that will focus our management actions and prioritize funding during the Fiscal 2001-2005 planning period. This plan is a product of nearly two years of field studies and research, public scoping, and coordination with the Rainwater Advisory Committee. The committee consists of representatives from tribal government, state agencies, local government, public organizations, and members of the public. The plan is organized into several sections with Chapter 1 providing introductory information such as project location, purpose and need, project goals and objectives, common elements and assumptions, coordination efforts and public scoping, and historical information about the project area. Key issues are presented in Chapter 2 and Chapter 3 discusses existing resource conditions within the wildlife area. Chapter 4 provides a detailed presentation on management activities and Chapter 5 outlines a monitoring and evaluation plan for the project that will help assess whether the project is meeting the intended purpose and need and the goals and objectives. Chapter 6 displays the action plan and provides a prioritized list of actions with associated budget for the next five year period. Successive chapters contain appendices, references, definitions, and a glossary.

  1. Remedial Action Performed

    Office of Legacy Management (LM)

    Aliquippa Forge Site in Aliquippa, Pennsylvania Department of Energy Former Sites Restoration Division Oak Ridge Operations Office November 1996 CERTIFICATION DOCKE.~ FOR THE REMEDIAL ACTION PERFORMED AT THE ALIQUIPPA FORGE SITE IN ALIQUIPPA, PENNSYLVANIA NOVEMBER 1996 Prepared for . UNITED STATES DEPARTMENT OF ENERGY Oak Ridge Operations Office Under Contract No. DE-AC05-9 1 OR2 1949 Bechtel National, Inc. Oak Ridge, Tennessee Bechtel Job No. 14501 CONTENTS Page FIGURES v . . . . . . . . . . .

  2. Remedial Action Performed

    Office of Legacy Management (LM)

    Baker and Williams Warehouses Site in New York, New York, 7997 - 7993 Department of Energy Former Sites Restoration Division Oak Ridge Operations Office November 7 995 CERTIFICATION DOCKET FOR THE REMEDIAL ACTION PERFORMED AT THE BAKER AND WILLIAMS WAREHOUSES SITE IN NEW YORK, NEW YORK, 1991-1993 NOVEMBER 1995 Prepared for United States Department of Energy Oak Ridge Operations Office Under Contract No. DE-AC05-910R21949 BY Bechtel National, Inc. Oak Ridge, Tennessee Bechtel Job No. 14501 __

  3. Remedial Action Performed

    Office of Legacy Management (LM)

    Alba Craft Laboratory and Vicinity Properties Site in Oxford, Ohio C Department of Energy Former Sites Restoration Division Oak Ridge Operations Office January 1997 $$@T Op% 3 @!B . i~d!l Ab Printed on recycled/recyclable paper. CERTIFICATION DOCKET FOR THE REMEDIAL ACTION PERFORMED AT THE FORMER ALBA CRAFT LABORATORY AND VICINITY PROPERTIES SITE IN OXFORD, OHIO JANUARY 1997 Prepared for United States Department of Energy Oak Ridge Operations Office Under Contract No. DE-AC0591 OR2 1949 Bechtel

  4. Environmental Assessment - Proposed Actions

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    availability of Waste Isolation Pilot Plant (WIPP) facilities and infrastructure to scientists who wish to conduct experiments there. DOE would allow these experiments if they can be conducted without interfering with the WIPP's primary transuranic waste disposal mission and if they reflect contemporary budget priorities. This fact sheet presents questions and answers about the proposed action and its alternative. The deep geologic repository at the WIPP could provide a favorable environment for

  5. Interim Action Determination

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Interim Action Determination Processing of Plutonium Materials from the DOE Standard 3013 Surveillance Program in H-Canyon at the Savannah River Site The Department of Energy (DOE) is preparing the Surplus Plutonium Disposition Supplemental Environmental Impact Statement (SPD SEIS, DOE/EIS-0283-S2). DOE is evaluating alternatives for disposition of non-pit plutonium that is surplus to the national security needs of the United States. Although the Deputy Secretary of Energy approved Critical

  6. EERE Announces Next Steps on President's Climate Action Plan

    Broader source: Energy.gov [DOE]

    On Friday, June 28, the U.S. Department of Energy's Office of Energy Efficiency and Renewable Energy hosted a webinar on the energy efficiency aspects of the President's Climate Action Plan. Rick Duke, Associate Director of the White House Council on Environmental Quality and the Domestic Policy Council, provided an overview of President Obama's comprehensive Climate Action Plan to cut the carbon pollution that causes climate change and threatens our health. The Department of Energy's Deputy Assistant Secretary for Energy Efficiency, Kathleen Hogan, provided a deeper dive into how EERE will implement the plan's action steps to cut energy waste in our homes, businesses, and factories. See the webinar slides.

  7. Environmental Restoration Remedial Action Quality Assurance Requirements Document

    SciTech Connect (OSTI)

    Cote, R.F.

    1991-09-01

    The Environmental Restoration Remedial Action Quality Assurance Requirements Document defines the quality assurance program requirements for the US Department of Energy-Richland Field Office Environmental Restoration Remedial Action Program at the Hanford Site. This paper describes the objectives outlined in DOE/RL 90-28. The Environmental Restoration Remedial Action Program implements significant commitments made by the US Department of Energy in the Hanford Federal Facility Agreement and Consent Order entered into with the Washington State Department of Ecology and the US Environmental Protection Agency. 18 refs.

  8. The lifetime of carbon capture and storage as a climate-change mitigation technology

    SciTech Connect (OSTI)

    Juanes, Ruben

    2013-12-30

    In carbon capture and storage (CCS), CO2 is captured at power plants and then injected underground into reservoirs like deep saline aquifers for long-term storage. While CCS may be critical for the continued use of fossil fuels in a carbon-constrained world, the deployment of CCS has been hindered by uncertainty in geologic storage capacities and sustainable injection rates, which has contributed to the absence of concerted government policy. Here, we clarify the potential of CCS to mitigate emissions in the United States by developing a storage-capacity supply curve that, unlike current large-scale capacity estimates, is derived from the fluid mechanics of CO2 injection and trapping and incorporates injection-rate constraints. We show that storage supply is a dynamic quantity that grows with the duration of CCS, and we interpret the lifetime of CCS as the time for which the storage supply curve exceeds the storage demand curve from CO2 production. We show that in the United States, if CO2 production from power generation continues to rise at recent rates, then CCS can store enough CO2 to stabilize emissions at current levels for at least 100 years. This result suggests that the large-scale implementation of CCS is a geologically viable climate-change mitigation option in the United States over the next century.

  9. Method to prevent/mitigate steam explosions in casting pits

    DOE Patents [OSTI]

    Taleyarkhan, R.P.

    1996-12-24

    Steam explosions can be prevented or mitigated during a metal casting process by the placement of a perforated flooring system in the casting pit. An upward flow of compressed gas through this perforated flooring system is introduced during the casting process to produce a buffer layer between any spilled molten metal and the cooling water in the reservoir. This buffer layer provides a hydrodynamic layer which acts to prevent or mitigate steam explosions resulting from hot, molten metal being spilled into or onto the cooling water. 3 figs.

  10. Method to prevent/mitigate steam explosions in casting pits

    DOE Patents [OSTI]

    Taleyarkhan, Rusi P.

    1996-01-01

    Steam explosions can be prevented or mitigated during a metal casting process by the placement of a perforated flooring system in the casting pit. An upward flow of compressed gas through this perforated flooring system is introduced during the casting process to produce a buffer layer between any spilled molten metal and the cooling water in the reservoir. This buffer layer provides a hydrodynamic layer which acts to prevent or mitigate steam explosions resulting from hot, molten metal being spilled into or onto the cooling water.

  11. Environmental protection Implementation Plan

    SciTech Connect (OSTI)

    R. C. Holland

    1999-12-01

    This ``Environmental Protection Implementation Plan'' is intended to ensure that the environmental program objectives of Department of Energy Order 5400.1 are achieved at SNL/California. This document states SNL/California's commitment to conduct its operations in an environmentally safe and responsible manner. The ``Environmental Protection Implementation Plan'' helps management and staff comply with applicable environmental responsibilities.

  12. Simple implementation of general dark energy models

    SciTech Connect (OSTI)

    Bloomfield, Jolyon K.; Pearson, Jonathan A. E-mail: jonathan.pearson@durham.ac.uk

    2014-03-01

    We present a formalism for the numerical implementation of general theories of dark energy, combining the computational simplicity of the equation of state for perturbations approach with the generality of the effective field theory approach. An effective fluid description is employed, based on a general action describing single-scalar field models. The formalism is developed from first principles, and constructed keeping the goal of a simple implementation into CAMB in mind. Benefits of this approach include its straightforward implementation, the generality of the underlying theory, the fact that the evolved variables are physical quantities, and that model-independent phenomenological descriptions may be straightforwardly investigated. We hope this formulation will provide a powerful tool for the comparison of theoretical models of dark energy with observational data.

  13. Independent Review of Mitigating System Performance Indicator Reporting in the EPIX Database

    SciTech Connect (OSTI)

    Wierman, Thomas Edward

    2009-05-01

    This report summarizes work done to verify the component, failure mode, and method of detection information provided in the Equipment Performance Information Exchange (EPIX) to support implementation of Mitigating Systems Performance Indices. This task is to select reports from EPIX and determine if their categorization as MSPI or non-MSPI failures is consistent with the development of unreliability baseline failure rates, and whether this significantly affects estimates of plant risk. This review is of all MSPI devices in EPIX that were reported as failures. The components include emergency generators; motor-driven, turbine-driven, and enginedriven pumps; and air and motor-operated valves. The date range for this report includes all MSPI device reported failures from 2003 to the most current EPIX data at the INL (up to the 3rd quarter 2008).

  14. A Technique for Producing Large Dual-Layer Pellets in Support of Disruption Mitigation Experiments

    SciTech Connect (OSTI)

    Combs, Stephen Kirk; Leachman, J. W.; Meitner, Steven J; Baylor, Larry R; Foust, Charles R; Commaux, Nicolas JC; Jernigan, Thomas C

    2011-01-01

    A special single-shot pellet injection system that produces and accelerates large cryogenic pellets (~16 mm diameter and composed of D2 or Ne) to relatively high speeds (>300 and 600 m/s, respectively) was previously developed at the Oak Ridge National Laboratory. Subsequently, a similar system was installed on DIII-D and used successfully in disruption mitigation experiments. To circumvent some operational issues with injecting the large Ne pellets, a technique has been developed in which a relatively thin layer (0.1 to 1.0 mm) of D2 is frozen on the inner wall of the pipe-gun barrel, followed by filling the core with solid Ne. The technique and the initial laboratory tests are described, as well as the implementation and operational issues for fusion experiments.

  15. Assessment of the mitigation options in the energy system in Bulgaria

    SciTech Connect (OSTI)

    Christov, C.; Vassilev, C.; Simenova, K.

    1996-12-31

    Bulgaria signed the Framework Convention on Climate Change at the UNCEP in Rio in June 1992. The parliament ratified the Convention in March 1995. In compliance with the commitments arising under the Convention, Bulgaria elaborates climate change polity. The underlying principles in this policy are Bulgaria to joint the international efforts towards solving climate change problems to the extent that is adequate to both the possibilities of national economy and the options to attract foreign investments. All policies and measures implemented should be as cost-effective as possible. The Bulgarian GHG emission profile reveals the energy sector as the most significant emission source and also as an area where the great potential for GHG emissions reduction exists. This potential could be achieved in many cases by relatively low cost or even no-cost options. Mitigation analysis incorporates options in energy demand and energy supply within the period 1992-2020.

  16. Acting Globally: Potential Carbon Emissions Mitigation Impacts from an International Standards and Labelling Program

    SciTech Connect (OSTI)

    McNeil, Michael A; Letschert, Virginie E.; de la Rue du Can, Stephane; Egan, Christine

    2009-05-29

    This paper presents an analysis of the potential impacts of an international initiative designed to support and promote the development and implementation of appliances standards and labelling programs throughout the world. As part of previous research efforts, LBNL developed the Bottom Up Energy Analysis System (BUENAS), an analysis framework that estimates impact potentials of energy efficiency policies on a global scale. In this paper, we apply this framework to an initiative that would result in the successful implementation of programs focused on high priority regions and product types, thus evaluating the potential impacts of such an initiative in terms of electricity savings and carbon mitigation in 2030. In order to model the likely parameters of such a program, we limit impacts to a five year period starting in 2009, but assume that the first 5 years of a program will result in implementation of 'best practice' minimum efficiency performance standards by 2014. The 'high priority' regions considered are: Brazil, China, the European Union,India, Mexico and the United States. The products considered are: refrigerators, air conditioners, lighting (both fluorescent and incandescent), standby power (for consumer electronics) and televisions in the residential sector, and air conditioning and lighting in commercial buildings. In 2020, these regions and enduses account for about 37percent of global residential electricity and 29percent of electricity in commercial buildings. We find that 850Mt of CO2 could be saved in buildings by 2030 compared to the baseline forecast.

  17. 2009 EVALUATION OF TRITIUM REMOVAL AND MITIGATION TECHNOLOGIES FOR WASTEWATER TREATMENT

    SciTech Connect (OSTI)

    LUECK KJ; GENESSE DJ; STEGEN GE

    2009-02-26

    Since 1995, a state-approved land disposal site (SALDS) has received tritium contaminated effluents from the Hanford Site Effluent Treatment Facility (ETF). Tritium in this effluent is mitigated by storage in slow moving groundwater to allow extended time for decay before the water reaches the site boundary. By this method, tritium in the SALDS is isolated from the general environment and human contact until it has decayed to acceptable levels. This report contains the 2009 update evaluation of alternative tritium mitigation techniques to control tritium in liquid effluents and groundwater at the Hanford site. A thorough literature review was completed and updated information is provided on state-of-the-art technologies for control of tritium in wastewaters. This report was prepared to satisfy the Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) Milestone M-026-07B (Ecology, EPA, and DOE 2007). Tritium separation and isolation technologies are evaluated periodically to determine their feasibility for implementation to control Hanford site liquid effluents and groundwaters to meet the Us. Code of Federal Regulations (CFR), Title 40 CFR 141.16, drinking water maximum contaminant level (MCL) for tritium of 20,000 pOll and/or DOE Order 5400.5 as low as reasonably achievable (ALARA) policy. Since the 2004 evaluation, there have been a number of developments related to tritium separation and control with potential application in mitigating tritium contaminated wastewater. These are primarily focused in the areas of: (1) tritium recycling at a commercial facility in Cardiff, UK using integrated tritium separation technologies (water distillation, palladium membrane reactor, liquid phase catalytic exchange, thermal diffusion), (2) development and demonstration of Combined Electrolysis Catalytic Exchange (CECE) using hydrogen/water exchange to separate tritium from water, (3) evaporation of tritium contaminated water for dispersion in the

  18. Group action in topos quantum physics

    SciTech Connect (OSTI)

    Flori, C.

    2013-03-15

    Topos theory has been suggested first by Isham and Butterfield, and then by Isham and Doering, as an alternative mathematical structure within which to formulate physical theories. In particular, it has been used to reformulate standard quantum mechanics in such a way that a novel type of logic is used to represent propositions. In this paper, we extend this formulation to include the notion of a group and group transformation in such a way that we overcome the problem of twisted presheaves. In order to implement this we need to change the type of topos involved, so as to render the notion of continuity of the group action meaningful.

  19. Cylinder yard inspections and corrective actions

    SciTech Connect (OSTI)

    Barlow, C.R.; Ziehlke, K.T.; Pryor, W.A.

    1990-07-31

    Inspection of valves on stored uranium hexafluoride (UF{sub 6}) cylinders was initiated at the three diffusion plant sites in Oak Ridge, Tennessee, Paducah, Kentucky, and Portsmouth, Ohio as the result of the discovery of valve defects and evidence of valve leaks at the Oak Ridge K-25 plant. The coordinated inspection culminated in the identification of additional factors related to long-term safe storage of UF{sub 6}, and plans for correction of such deficiencies are presently being developed and implemented. These corrective actions supplement existing programs aimed at assurance of safe storage as summarized in the report.

  20. Corrective Action Decision Document/Closure Report for Corrective Action Unit 571: Area 9 Yucca Flat Plutonium Dispersion Sites, Nevada National Security Site, Nevada, Revision 0

    SciTech Connect (OSTI)

    Matthews, Patrick

    2014-08-01

    The purpose of this CADD/CR is to provide documentation and justification that no further corrective action is needed for the closure of CAU 571 based on the implementation of corrective actions. This includes a description of investigation activities, an evaluation of the data, and a description of corrective actions that were performed. The CAIP provides information relating to the scope and planning of the investigation. Therefore, that information will not be repeated in this document.

  1. October is Energy Action Month

    Broader source: Energy.gov [DOE]

    President Obama declared October Energy Action Month, and we are sharing tips about how you can save energy.

  2. 3RS action plan

    SciTech Connect (OSTI)

    Not Available

    1990-01-01

    The goal of the Solid Waste Interim Steering Committee (SWISC) process is to develop a long-term waste management system for the Greater Toronto Area (GTA), to be in place by 1996, which is environmentally, socially, economically and technically sound. This background report is being released to the public and member Regional Councils to facilitate input to the SWISC planning process. The report documents current reduction, reuse and recycling initiatives in the GTA, identifies opportunities for coordination and collaboration among the GTA communities, and develops an action plan for improving the effectiveness of the reduction, reuse and recycling efforts within the GTA.

  3. VIOLENT FRAMES IN ACTION

    SciTech Connect (OSTI)

    Sanfilippo, Antonio P.; McGrath, Liam R.; Whitney, Paul D.

    2011-11-17

    We present a computational approach to radical rhetoric that leverages the co-expression of rhetoric and action features in discourse to identify violent intent. The approach combines text mining and machine learning techniques with insights from Frame Analysis and theories that explain the emergence of violence in terms of moral disengagement, the violation of sacred values and social isolation in order to build computational models that identify messages from terrorist sources and estimate their proximity to an attack. We discuss a specific application of this approach to a body of documents from and about radical and terrorist groups in the Middle East and present the results achieved.

  4. DISRUPTION MITIGATION WITH HIGH-PRESSURE NOBLE GAS INJECTION

    SciTech Connect (OSTI)

    WHYTE, DG; JERNIGAN, TC; HUMPHREYS, DA; HYATT, AW; LASNIER, CJ; PARKS, PB; EVANS, TE; TAYLOR, PL; KELLMAN, AG; GRAY, DS; HOLLMANN, EM

    2002-10-01

    OAK A271 DISRUPTION MITIGATION WITH HIGH-PRESSURE NOBLE GAS INJECTION. High-pressure gas jets of neon and argon are used to mitigate the three principal damaging effects of tokamak disruptions: thermal loading of the divertor surfaces, vessel stress from poloidal halo currents and the buildup and loss of relativistic electrons to the wall. The gas jet penetrates as a neutral species through to the central plasma at its sonic velocity. The injected gas atoms increase up to 500 times the total electron inventory in the plasma volume, resulting in a relatively benign radiative dissipation of >95% of the plasma stored energy. The rapid cooling and the slow movement of the plasma to the wall reduce poloidal halo currents during the current decay. The thermally collapsed plasma is very cold ({approx} 1-2 eV) and the impurity charge distribution can include > 50% fraction neutral species. If a sufficient quantity of gas is injected, the neutrals inhibit runaway electrons. A physical model of radiative cooling is developed and validated against DIII-D experiments. The model shows that gas jet mitigation, including runaway suppression, extrapolates favorably to burning plasmas where disruption damage will be more severe. Initial results of real-time disruption detection triggering gas jet injection for mitigation are shown.

  5. Sensitivity of climate mitigation strategies to natural disturbances

    SciTech Connect (OSTI)

    Le Page, Yannick LB; Hurtt, George; Thomson, Allison M.; Bond-Lamberty, Benjamin; Patel, Pralit L.; Wise, Marshall A.; Calvin, Katherine V.; Kyle, G. Page; Clarke, Leon E.; Edmonds, James A.; Janetos, Anthony C.

    2013-02-19

    The present and future concentration of atmospheric carbon dioxide depends on both anthropogenic and natural sources and sinks of carbon. Most proposed climate mitigation strategies rely on a progressive transition to carbon12 efficient technologies to reduce industrial emissions, substantially supported by policies to maintain or enhance the terrestrial carbon stock in forests and other ecosystems. This strategy may be challenged if terrestrial sequestration capacity is affected by future climate feedbacks, but how and to what extent is little understood. Here, we show that climate mitigation strategies are highly sensitive to future natural disturbance rates (e.g. fires, hurricanes, droughts), because of potential effect of disturbances on the terrestrial carbon balance. Generally, altered disturbance rates affect the pace of societal and technological transitions required to achieve the mitigation target, with substantial consequences on the energy sector and on the global economy. Understanding the future dynamics and consequences of natural disturbances on terrestrial carbon balance is thus essential for developing robust climate mitigation strategies and policies

  6. Planning Tools For Seismic Risk Mitigation. Rules And Applications

    SciTech Connect (OSTI)

    De Paoli, Rosa Grazia

    2008-07-08

    Recently, Italian urban planning research in the field of seismic risk mitigation are renewing. In particular, it promotes strategies that integrate urban rehabilitation and aseismic objectives, and also politicizes that are directed to revitalizes urban systems, coupling physical renewal and socio-economic development.In Italy the first law concerning planning for seismic mitigation dates back 1974, the law n. 64 'Regulation for buildings with particular rules for the seismic areas' where the rules for buildings in seismic areas concerning also the local hazard. This law, in fact, forced the municipalities to acquire, during the formation of the plans, a preventive opinion of compatibility between planning conditions and geomorphology conditions of the territory. From this date the conviction that the seismic risk must be considered inside the territorial planning especially in terms of strategies of mitigation has been strengthened.The town planners have started to take an interest in seismic risk in the [80]s when the Irpinia's earthquake took place. The researches developed after this earthquake have established that the principal cause of the collapse of buildings are due to from the wrong location of urban settlements (on slopes or crowns) After Irpinia's earthquake the first researches on seismic risk mitigation, in particular on the aspects related to the hazards and to the urban vulnerability were made.

  7. Exploring Complex Systems Aspects of Blackout Risk and Mitigation

    SciTech Connect (OSTI)

    Newman, David E; Carreras, Benjamin A; Lynch, Vickie E; Dobson, Ian

    2011-01-01

    Electric power transmission systems are a key infrastructure, and blackouts of these systems have major consequences for the economy and national security. Analyses of blackout data suggest that blackout size distributions have a power law form over much of their range. This result is an indication that blackouts behave as a complex dynamical system. We use a simulation of an upgrading power transmission system to investigate how these complex system dynamics impact the assessment and mitigation of blackout risk. The mitigation of failures in complex systems needs to be approached with care. The mitigation efforts can move the system to a new dynamic equilibrium while remaining near criticality and preserving the power law region. Thus, while the absolute frequency of blackouts of all sizes may be reduced, the underlying forces can still cause the relative frequency of large blackouts to small blackouts to remain the same. Moreover, in some cases, efforts to mitigate small blackouts can even increase the frequency of large blackouts. This result occurs because the large and small blackouts are not mutually independent, but are strongly coupled by the complex dynamics.

  8. RCRA corrective action and closure

    SciTech Connect (OSTI)

    Not Available

    1995-02-01

    This information brief explains how RCRA corrective action and closure processes affect one another. It examines the similarities and differences between corrective action and closure, regulators` interests in RCRA facilities undergoing closure, and how the need to perform corrective action affects the closure of DOE`s permitted facilities and interim status facilities.

  9. ALFAL 2010-04- Congressional Notification of Pending Contract or Financial Assistance Actions in Excess of $1 Million

    Office of Energy Efficiency and Renewable Energy (EERE)

    ALIFAL 20 10-03 implements statutory and non-statutory Congressional notification of pending award of a contract action, announcement of selected applications for negotiation of financial assistance awards, or to award a financial assistance action in excess of $1 million. The ALIFAL implements the General Provision Section 3 11 of the Energy and Water Development and Related Agencies Appropriations Act, 201 0.

  10. Corrective Action Plan for Corrective Action Unit 417: Central Nevada Test Area Surface, Nevada

    SciTech Connect (OSTI)

    K. Campbell

    2000-04-01

    This Corrective Action Plan provides methods for implementing the approved corrective action alternative as provided in the Corrective Action Decision Document for the Central Nevada Test Area (CNTA), Corrective Action Unit (CAU) 417 (DOE/NV, 1999). The CNTA is located in the Hot Creek Valley in Nye County, Nevada, approximately 137 kilometers (85 miles) northeast of Tonopah, Nevada. The CNTA consists of three separate land withdrawal areas commonly referred to as UC-1, UC-3, and UC-4, all of which are accessible to the public. CAU 417 consists of 34 Corrective Action Sites (CASs). Results of the investigation activities completed in 1998 are presented in Appendix D of the Corrective Action Decision Document (DOE/NV, 1999). According to the results, the only Constituent of Concern at the CNTA is total petroleum hydrocarbons (TPH). Of the 34 CASs, corrective action was proposed for 16 sites in 13 CASs. In fiscal year 1999, a Phase I Work Plan was prepared for the construction of a cover on the UC-4 Mud Pit C to gather information on cover constructibility and to perform site management activities. With Nevada Division of Environmental Protection concurrence, the Phase I field activities began in August 1999. A multi-layered cover using a Geosynthetic Clay Liner as an infiltration barrier was constructed over the UC-4 Mud Pit. Some TPH impacted material was relocated, concrete monuments were installed at nine sites, signs warning of site conditions were posted at seven sites, and subsidence markers were installed on the UC-4 Mud Pit C cover. Results from the field activities indicated that the UC-4 Mud Pit C cover design was constructable and could be used at the UC-1 Central Mud Pit (CMP). However, because of the size of the UC-1 CMP this design would be extremely costly. An alternative cover design, a vegetated cover, is proposed for the UC-1 CMP.

  11. Remedial design/remedial action strategy report

    SciTech Connect (OSTI)

    Dieffenbacher, R.G.

    1994-06-30

    This draft Regulatory Compliance Strategy (RCS) report will aid the ER program in developing and implementing Remedial Design/Remedial Action (RD/RA) projects. The intent of the RCS is to provide guidance for the implementation of project management requirements and to allow the implementation of a flexible, graded approach to design requirements depending on the complexity, magnitude, schedule, risk, and cost for any project. The RCS provides a functional management-level guidance document for the identification, classification, and implementation of the managerial and regulatory aspects of an ER project. The RCS has been written from the perspective of the ER Design Manager and provides guidance for the overall management of design processes and elements. The RCS does not address the project engineering or specification level of detail. Topics such as project initiation, funding, or construction are presented only in the context in which these items are important as sources of information or necessary process elements that relate to the design project phases.

  12. Vehicle Technologies Program Implementation

    SciTech Connect (OSTI)

    none,

    2009-06-19

    The Vehicle Technologies Program takes a systematic approach to Program implementation. Elements of this approach include the evaluation of new technologies, competitive selection of projects and partners, review of Program and project improvement, project tracking, and portfolio management and adjustment.

  13. Corrective Action Plan for Corrective Action Unit 563: Septic Systems, Nevada Test Site, Nevada

    SciTech Connect (OSTI)

    NSTec Environmental Restoration

    2009-03-31

    This Corrective Action Plan (CAP) has been prepared for Corrective Action Unit (CAU) 563, Septic Systems, in accordance with the Federal Facility Agreement and Consent Order. CAU 563 consists of four Corrective Action Sites (CASs) located in Areas 3 and 12 of the Nevada Test Site. CAU 563 consists of the following CASs: CAS 03-04-02, Area 3 Subdock Septic Tank CAS 03-59-05, Area 3 Subdock Cesspool CAS 12-59-01, Drilling/Welding Shop Septic Tanks CAS 12-60-01, Drilling/Welding Shop Outfalls Site characterization activities were performed in 2007, and the results are presented in Appendix A of the CAU 563 Corrective Action Decision Document. The scope of work required to implement the recommended closure alternatives is summarized below. CAS 03-04-02, Area 3 Subdock Septic Tank, contains no contaminants of concern (COCs) above action levels. No further action is required for this site; however, as a best management practice (BMP), all aboveground features (e.g., riser pipes and bumper posts) will be removed, the septic tank will be removed, and all open pipe ends will be sealed with grout. CAS 03-59-05, Area 3 Subdock Cesspool, contains no COCs above action levels. No further action is required for this site; however, as a BMP, all aboveground features (e.g., riser pipes and bumper posts) will be removed, the cesspool will be abandoned by filling it with sand or native soil, and all open pipe ends will be sealed with grout. CAS 12-59-01, Drilling/Welding Shop Septic Tanks, will be clean closed by excavating approximately 4 cubic yards (yd3) of arsenic- and chromium-impacted soil. In addition, as a BMP, the liquid in the South Tank will be removed, the North Tank will be removed or filled with grout and left in place, the South Tank will be filled with grout and left in place, all open pipe ends will be sealed with grout or similar material, approximately 10 yd3 of chlordane-impacted soil will be excavated, and debris within the CAS boundary will be removed. CAS 12

  14. ORISE: Policy Implementation

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Policy Implementation The Oak Ridge Institute for Science and Education (ORISE) assists the U.S. Department of Energy (DOE) Office of Science in the implementation of its program directed at ensuring compliance with federal and DOE regulations pertaining to the protection of human subjects participating in research. The Federal Policy for the Protection of Human Subjects was adopted by DOE on June 18, 1991, as Title 10 Code of Federal Regulations 745, Protection of Human Subjects, and expressed

  15. Blackout Final Implementation Report

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Final Report on the Implementation of the Task Force Recommendations U.S.-Canada Power System Outage Task Force Natural Resources Canada U.S. Department of Energy September 2006 Final Report on the Implementation of the Task Force Recommendations U.S.-Canada Power System Outage Task Force September 2006 Natural Resources Canada U.S. Department of Energy Acknowledgments This document was prepared by staff of Natural Resources Canada and the U.S. Department of Energy. The principal contributors

  16. U.S.-Canada Clean Energy Dialogue (CED) Action Plan II

    Broader source: Energy.gov [DOE]

    Action Plan II describes initiatives that the U.S.-Canada Clean Energy Dialogue Working Groups plan to implement under Phase II of the CED to further progress toward a low-carbon economy that...

  17. Annual Report on Wildlife Activities, September 1985-April 1986, Action Item 40.1, Columbia River Basin Fish and Wildlife Program.

    SciTech Connect (OSTI)

    United States. Bonneville Power Administration.

    1986-04-01

    This annual report addresses the status of wildlife projects Bonneville Power Administration (BPA) has implemented from September 1985 to April 1986. This report provides a brief synopsis, review, and discussion of wildlife activities BPA has undertaken. BPA's effort has gone towards implementing wildlife planning. This includes measure 1004 (b)(2), loss statements and measure 1004 (b)(3), mitigation plans. Loss statements have been completed for 14 facilities in the Basin with 4 additional ones to be completed shortly. Mitigation plans have been completed for 5 hydroelectric facilities in Montana. The Northwest Power Planning Council is presently considering two mitigation plans (Hungry Horse and Libby) for amendment into the Program. Currently, mitigation plans are being prepared for the 8 Federal hydroelectric facilities in the Willamette River Basin in Oregon, Grand Coulee Dam in the state of Washington, and Palisades Dam on the Snake River in Idaho.

  18. Emergencies and Emergency Actions | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    and Emergency Actions Emergencies and Emergency Actions Selected documents on the topic of Emergencies and Emergency Actions under NEPA. May 12, 2010 Memorandum for Heads of...

  19. Ecology Action: Small Market Advanced Retrofit Transformation...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Ecology Action: Small Market Advanced Retrofit Transformation Program (SMART) Ecology Action: Small Market Advanced Retrofit Transformation Program (SMART) Ecology Action: Small ...

  20. Climate Action Tracker | Open Energy Information

    Open Energy Info (EERE)

    References: Climate Action Tracker1 "This "Climate Action Tracker" is an independent science-based assessment, which tracks the emission commitments and actions of countries. The...