National Library of Energy BETA

Sample records for mill tailings grand

  1. EIS-0355: Remediation of the Moab Uranium Mill Tailings, Grand and San Juan Counties, Utah

    Broader source: Energy.gov [DOE]

    The Remediation of the Moab Uranium Mill Tailings, Grand and San Juan Counties, Utah, Environmental Impact Statement and associated supplements and amendments provides information on the environmental impacts of the U.S. Department of Energy’s (DOE’s) proposal to (1) remediate approximately 11.9 million tons of contaminated materials located on the Moab site and approximately 39,700 tons located on nearby vicinity properties and (2) develop and implement a ground water compliance strategy for the Moab site using the framework of the Programmatic Environmental Impact Statement for the Uranium Mill Tailings Remedial Action Ground Water Project (DOE/EIS-0198, October 1996). The surface remediation alternatives analyzed in the EIS include on-site disposal of the contaminated materials and off-site disposal at one of three alternative locations in Utah using one or more transportation options: truck, rail, or slurry pipeline.

  2. Baseline risk assessment of ground water contamination at the Uranium Mill Tailings Site near Grand Junction, Colorado

    SciTech Connect (OSTI)

    Not Available

    1994-06-01

    This Baseline Risk Assessment of Ground Water Contamination at the Uranium Mill Tailings Site Near Grand Junction, Colorado evaluates potential impacts to public health or the environment resulting from ground water contamination at the former uranium mill processing site. The tailings and other contaminated material at this site were placed in an off-site disposal cell by the US Department of Energy`s (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project. The remedial activities at the site were conducted from 1989 to 1993. Currently, the UMTRA Project is evaluating ground water contamination. This risk assessment is the first document specific to this site for the Ground Water Project. This risk assessment evaluates the most contaminated ground water that flows beneath the processing site toward the Colorado River. The monitor wells that have consistently shown the highest concentrations of most contaminants are used to assess risk. This risk assessment will be used in conjunction with additional activities and documents to determine what remedial action may be needed for contaminated ground water at the site. This risk assessment follows an approach outlined by the EPA. the first step is to evaluate ground water data collected from monitor wells at the site. Evaluation of these data showed that the contaminants of potential concern in the ground water are arsenic, cadmium, cobalt, fluoride, iron, manganese, molybdenum, nickel, sulfate, uranium, vanadium, zinc, and radium-226. The next step in the risk assessment is to estimate how much of these contaminants people would be exposed to if they drank from a well installed in the contaminated ground water at the former processing site.

  3. Engineering assessment of inactive uranium mill tailings

    SciTech Connect (OSTI)

    Not Available

    1981-07-01

    The Grand Junction site has been reevaluated in order to revise the October 1977 engineering assessment of the problems resulting from the existence of radioactive uranium mill tailings at Grand Junction, Colorado. This engineering assessment has included the preparation of topographic maps, the performance of core drillings and radiometric measurements sufficient to determine areas and volumes of tailings and radiation exposures of individuals and nearby populations, the investigations of site hydrology and meteorology, and the evaluation and costing of alternative corrective actions. Radon gas released from the 1.9 million tons of tailings at the Grand Junction site constitutes the most significant environmental impact, although windblown tailings and external gamma radiation are also factors. The eight alternative actions presented herein range from millsite and off-site decontamination with the addition of 3 m of stabilization cover material (Option I), to removal of the tailings to remote disposal sites and decontamination of the tailings site (Options II through VIII). Cost estimates for the eight options range from about $10,200,000 for stabilization in-place to about $39,500,000 for disposal in the DeBeque area, at a distance of about 35 mi, using transportation by rail. If transportation to DeBeque were by truck, the cost estimated to be about $41,900,000. Three principal alternatives for the reprocessing of the Grand Junction tailings were examined: (a) heap leaching; (b) treatment at an existing mill; and (c) reprocessing at a new conventional mill constructed for tailings reprocessing. The cost of the uranium recovered would be about $200/lb by heap leach and $150/lb by conventional plant processes. The spot market price for uranium was $25/lb early in 1981. Therefore, reprocessing the tailings for uranium recovery appears not to be economically attractive.

  4. DOE/EIS-0355 Remediation of the Moab Uranium Mill Tailings, Grand and San Juan Counties, Utah, Final Environmental Impact Statement (July 2005)

    SciTech Connect (OSTI)

    N /A

    2005-08-05

    The U.S. Department of Energy (DOE or the Department) is proposing to clean up surface contamination and implement a ground water compliance strategy to address contamination that resulted from historical uranium-ore processing at the Moab Uranium Mill Tailings Site (Moab site), Grand County, Utah. Pursuant to the National Environmental Policy Act (NEPA), 42 United States Code (U.S.C.) {section} 4321 et seq., DOE prepared this environmental impact statement (EIS) to assess the potential environmental impacts of remediating the Moab site and vicinity properties (properties where uranium mill tailings were used as construction or fill material before the potential hazards associated with the tailings were known). DOE analyzed the potential environmental impacts of both on-site and off-site remediation and disposal alternatives involving both surface and ground water contamination. DOE also analyzed the No Action alternative as required by NEPA implementing regulations promulgated by the Council on Environmental Quality. DOE has determined that its preferred alternatives are the off-site disposal of the Moab uranium mill tailings pile, combined with active ground water remediation at the Moab site. The preferred off-site disposal location is the Crescent Junction site, and the preferred method of transportation is rail. The basis for this determination is discussed later in this Summary. DOE has entered into agreements with 12 federal, tribal, state, and local agencies to be cooperating agencies in the development and preparation of this EIS. Several of the cooperating agencies have jurisdiction by law and intend to use the EIS to support their own decisionmaking. The others have expertise relevant to potential environmental, social, or economic impacts within their geographic regions. During the preparation of the EIS, DOE met with the cooperating agencies, provided them with opportunities to review preliminary versions of the document, and addressed their comments and concerns to the fullest extent possible. DOE received over 1,600 comments on the draft EIS from the public, federal, state and local agencies, tribes, governors, and members of Congress. DOE has considered these comments in finalizing the EIS and has provided responses to all comments in the EIS.

  5. Monticello Mill Tailings Site Operable Unit III Ecological Risk

    Office of Legacy Management (LM)

    Monticello Mill Tailings Site Operable Unit III Ecological Risk Assessment September 1998 Prepared by U.S. Department of Energy Grand JunctionOffice Grand Junction, Colorado Project Number MSG-035-0004-00-000 Document Number Q0002l 00 Work Performed Under DOE Contract Number DE-AC13-96GJ87335 Task Order Number MAC98-03 This page intentionally blank , ** 1 ( ( Document Number Q00021 00 Contents Contents Page Acronyms . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

  6. Moab Mill Tailings Removal Project Plans to Resume Train Shipments...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Tons of Mill Tailings Removed From DOE Moab Project Site Laborers place a disposable liner in a tailings container. Moab Project Continues Progress on Tailings Removal with...

  7. Moab Mill Tailings Removal Project Celebrates 5 Years of Success |

    Office of Environmental Management (EM)

    Department of Energy Removal Project Celebrates 5 Years of Success Moab Mill Tailings Removal Project Celebrates 5 Years of Success October 3, 2012 - 12:00pm Addthis Pictured here is the Moab uranium mill tailings pile. Tailings excavation and conditioning activities are seen in the foreground. The water spray is used to eliminate extracted contaminated groundwater. Pictured here is the Moab uranium mill tailings pile. Tailings excavation and conditioning activities are seen in the

  8. DOE Moab Project Reaches Halfway Mark in Mill Tailings Removal 2.5 Million

    Office of Environmental Management (EM)

    Hours Safely Worked | Department of Energy Moab Project Reaches Halfway Mark in Mill Tailings Removal 2.5 Million Hours Safely Worked DOE Moab Project Reaches Halfway Mark in Mill Tailings Removal 2.5 Million Hours Safely Worked January 20, 2016 - 12:00pm Addthis DOE Moab Project Reaches Halfway Mark in Mill Tailings Removal 2.5 Million Hours Safely Worked Media Contact Wendee Ryan, S&K Aerospace Public Affairs Manager, (970) 257-2145 (Grand Junction, CO) - The U.S. Department of Energy

  9. 6 Million Tons of Mill Tailings Removed From DOE Moab Project Site |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy 6 Million Tons of Mill Tailings Removed From DOE Moab Project Site 6 Million Tons of Mill Tailings Removed From DOE Moab Project Site June 18, 2013 - 12:00pm Addthis Media Contacts Donald Metzler, Moab Federal Project Director (970) 257-2115 Wendee Ryan, S&K Aerospace Public Affairs Manager (970) 257-2145 (Grand Junction, CO) - Today, the Department of Energy (DOE) announced that 6 million tons of uranium mill tailings have been shipped from Moab, Utah, under the

  10. Moab Mill Tailings Pile 25 Percent Disposed: DOE Moab Project Reaches

    Office of Environmental Management (EM)

    Significant Milestone | Department of Energy Pile 25 Percent Disposed: DOE Moab Project Reaches Significant Milestone Moab Mill Tailings Pile 25 Percent Disposed: DOE Moab Project Reaches Significant Milestone June 3, 2011 - 12:00pm Addthis Media Contacts Donald Metzler Moab Federal Project Director (970) 257-2115 Wendee Ryan S&K Aerospace Public Affairs Manager (970) 257-2145 Grand Junction, CO - One quarter of the uranium mill tailings pile located in Moab, Utah, has been relocated to

  11. Monticello Mill Tailings Site Operable Unit Ill Interim Remedial Action

    Office of Legacy Management (LM)

    Site Operable Unit Ill Interim Remedial Action Mark Perfxmed Under DOE Contrici No. DE-AC13-96CJ873.35 for th3 U.S. De[:ar!menf of Energy app~oveJioi'ptiL#ic re1ease;dCinWlionis Unlimilra' This page intentionally left blank Monticello Mill Tailings Site Operable Unit I11 Interim Remedial Action Annual Status Report August 1999 Prepared for U.S. Department of Energy Albuquerque Operations Office Grand Junction Office Project Number MSG-035-0011-00-000 Document Number Q0017700 Work Performed Under

  12. Uranium Mill Tailings Radiation Control Act Sites Fact Sheet

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    This fact sheet provides information about the Uranium Mill Tailings Radiation Control Act Title I and II disposal and processing sites. The sites are managed by the U.S. Department of Energy Office of Legacy Management. Introduction The Uranium Mill Tailings Radiation Control Act (UMTRCA) of 1978 (Public Law 95-604) is a federal law that provides for the safe and environmentally sound disposal, long-term stabilization, and control of uranium mill tailings in a manner that minimizes or

  13. Monticello Mill Tailings Site Operable Unit I11 Remedial Investigation Addendum1

    Office of Legacy Management (LM)

    Monticello Mill Tailings Site Operable Unit I11 Remedial Investigation Addendum1 Focused Feasibility Study January 2004 Prepared by U.S. Department of Energy Grand Junction, Colorado Work performed under DOE Contract No. DE-AC1342GJ79491 DOE Task Order No. ST03-205 Document N u m b e r Q0029500 S i g t ~ a t u r e Page Signature Page Monticello Mill Tailings Site Operable Unit I11 Remedial Investigation Addendud Focused Feasibility Study January 2004 Submitted By: Arthur W. Kleinrath, Project

  14. Accelerated aging tests of liners for uranium mill tailings disposal

    SciTech Connect (OSTI)

    Barnes, S.M.; Buelt, J.L.; Hale, V.Q.

    1981-11-01

    This document describes the results of accelerated aging tests to determine the long-term effectiveness of selected impoundment liner materials in a uranium mill tailings environment. The study was sponsored by the US Department of Energy under the Uranium Mill Tailings Remedial Action Project. The study was designed to evaluate the need for, and the performance of, several candidate liners for isolating mill tailings leachate in conformance with proposed Environmental Protection Agency and Nuclear Regulatory Commission requirements. The liners were subjected to conditions known to accelerate the degradation mechanisms of the various liners. Also, a test environment was maintained that modeled the expected conditions at a mill tailings impoundment, including ground subsidence and the weight loading of tailings on the liners. A comparison of installation costs was also performed for the candidate liners. The laboratory testing and cost information prompted the selection of a catalytic airblown asphalt membrane and a sodium bentonite-amended soil for fiscal year 1981 field testing.

  15. DOE Announces Preferred Alternatives For Moab, Utah, Uranium Mill Tailings

    Broader source: Energy.gov [DOE]

    WASHINGTON, DC – The U.S. Department of Energy today announced the department’s preferred alternatives for remediation of the Moab, Utah, Uranium Mill Tailings Remedial Action Project Site:  active...

  16. Uranium Mill Tailings Remedial Action Project 1994 environmental report

    SciTech Connect (OSTI)

    1995-08-01

    This annual report documents the Uranium Mill Tailings Remedial Action (UMTRA) Project environmental monitoring and protection program. The UMTRA Project routinely monitors radiation, radioactive residual materials, and hazardous constituents at associated former uranium tailings processing sites and disposal sites. At the end of 1994, surface remedial action was complete at 14 of the 24 designated UMTRA Project processing sites: Canonsburg, Pennsylvania; Durango, Colorado; Grand Junction, Colorado; Green River Utah, Lakeview, Oregon; Lowman, Idaho; Mexican Hat, Utah; Riverton, Wyoming; Salt Lake City, Utah; Falls City, Texas; Shiprock, New Mexico; Spook, Wyoming, Tuba City, Arizona; and Monument Valley, Arizona. Surface remedial action was ongoing at 5 sites: Ambrosia Lake, New Mexico; Naturita, Colorado; Gunnison, Colorado; and Rifle, Colorado (2 sites). Remedial action has not begun at the 5 remaining UMTRA Project sites that are in the planning stage. Belfield and Bowman, North Dakota; Maybell, Colorado; and Slick Rock, Colorado (2 sites). The ground water compliance phase of the UMTRA Project started in 1991. Because the UMTRA Project sites are.` different stages of remedial action, the breadth of the UMTRA environmental protection program differs from site to site. In general, sites actively undergoing surface remedial action have the most comprehensive environmental programs for sampling media. At sites where surface remedial action is complete and at sites where remedial action has not yet begun, the environmental program consists primarily of surface water and ground water monitoring to support site characterization, baseline risk assessments, or disposal site performance assessments.

  17. Monticello Mill Tailings Site Operable Unit III Annual Groundwater Report

    Office of Legacy Management (LM)

    3 Through April 2014 October 2014 LMS/MNT/S11802 This page intentionally left blank LMS/MNT/S11802 Monticello Mill Tailings Site Operable Unit III Annual Groundwater Report May 2013 through April 2014 October 2014 This page intentionally left blank U.S. Department of Energy Monticello Mill Tailings Site OU III Annual Groundwater Report May 2013-April 2014 October 2014 Doc. No. S11802 Page i Contents Abbreviations

  18. Cost of radon-barrier systems for uranium mill tailings

    SciTech Connect (OSTI)

    Baker, E.G.; Hartley, J.N.

    1982-08-01

    This report deals specifically with the cost of three types of radon barrier systems, earthen covers, asphalt emulsion covers, and multilayer covers, which could meet standards proposed by the Environmental Protection Agency to stabilize uranium mill tailings located primarily in the western US. In addition, the report includes a sensitivity analysis of various factors which significantly effect the overall cost of the three systems. These analyses were based on a generic disposal site. Four different 3m thick earthen covers were tested and cost an average of $27/m/sup 2/. The least expensive earthen cover cost was about $21/m/sup 2/. The asphalt cover system (6 to 7 cm of asphalt topped with 0.6m of overburden) cost about $28/m/sup 2/. The four multilayer covers averaged $57/m/sup 2/, but materials handling problems encountered during the test inflated this cost above what was anticipated and significant cost reductions should be possible. The least expensive multilayer cover cost $43/m/sup 2/. Based on the results of the Grand Junction field test we estimated the cost of covering the tailings from three high priority sites, Durango, Shiprock, and Salt Lake City (Vitro). The cost of a 3m earthen cover ranged from $18 to 33/m/sup 2/ for the seven disposal sites (two or three at each location) studied. The cost of asphalt cover systems were $23 to 28/m/sup 2/ and the multilayer cover costs were between $31 to 36/m/sup 2/. The earthen cover costs are less than the Grand Junction field test cost primarily because cover material is available at or near most of the disposal sites selected. Earthen material was imported from 6 to 10 miles for the field test. Assuming more efficienct utilization of materials significantly reduced the cost of the multilayer covers.

  19. Asphalt emulsion sealing of uranium mill tailings. 1979 annual report

    SciTech Connect (OSTI)

    Hartley, J.N.; Koehmstedt, P.L.; Esterl, D.J.; Freeman, H.D.

    1980-06-01

    Uranium mill tailings are a source of low-level radiation and radioactive materials that may be released into the environment. Stabilization or disposal of these tailings in a safe and environmentally sound way is necessary to minimize radon exhalation and other radioactive releases. One of the most promising concepts for stabilizing uranium tailings is being investigated at the Pacific Northwest Laboratory: the use of asphalt emulsion to contain radon and other potentially hazardous materials in uranium tailings. Results of these studies indicate that radon flux from uranium tailings can be reduced by greater than 99% by covering the tailings with an asphalt emulsion that is poured on or sprayed on (3.0 to 7.0 mm thick), or mixed with some of the tailings and compacted to form an admixture seal (2.5 to 15.2 cm) containing 18 wt % residual asphalt.

  20. DOE Awards Technical Assistance Contract for Moab Mill Tailings Cleanup |

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Department of Energy Technical Assistance Contract for Moab Mill Tailings Cleanup DOE Awards Technical Assistance Contract for Moab Mill Tailings Cleanup May 31, 2012 - 12:00pm Addthis Media Contact Bill Taylor bill.taylor@srs.gov 803-952-8564 Cincinnati-The U.S. Department of Energy (DOE) today announced the award of an $18 million small disadvantaged business contract with S&K Aerospace, LLC, of St. Ignatius, Montana to continue to provide technical assistance services for the Moab

  1. Asphalt emulsion radon barrier systems for uranium mill tailings: an overview of the technology

    SciTech Connect (OSTI)

    Baker, E.G.; Hartley, J.N.; Freeman, H.D.; Gates, T.E.; Nelson, D.A.; Dunning, R.L.

    1984-03-01

    Pacific Northwest Laboratory (PNL), under contract to the US Department of Energy (DOE) Uranium Mill Tailings Remedial Action Project (UMTRAP) office, has developed an asphalt emulsion cover system to reduce the release of radon from uranium mill tailings. The system has been field tested at Grand Junction, Colorado. Results from laboratory and field tests indicate that this system is effective in reducing radon release to near-background levels (<2.5 pCi m/sup -2/s/sup -1/) and has the properties required for long-term effectiveness and stability. Engineering specifications have been developed, and analysis indicates that asphalt emulsion covers are cost-competitive with other cover systems. This report summarizes the technology for asphalt emulsion radon barrier systems. 59 references, 45 figures, 36 tables.

  2. Liner evaluation for uranium mill tailings. Final report

    SciTech Connect (OSTI)

    Buelt, J.L. (comp.)

    1983-09-01

    The Liner Evaluation for Uranium Mill Tailings Program was conducted to evaluate the need for and performance of prospective lining materials for the long-term management of inactive uranium mill tailings piles. On the basis of program results, two materials have been identified: natural foundation soil amended with 10% sodium bentonite; catalytic airblown asphalt membrane. The study showed that, for most situations, calcareous soils typical of Western US sites adequately buffer tailings leachates and prevent groundwater contamination without additional liner materials or amendments. Although mathematical modeling of disposal sites is recommended on a site-specific basis, there appears to be no reason to expect significant infiltration through the cover for most Western sites. The major water source through the tailings would be groundwater movement at sites with shallow groundwater tables. Even so column leaching studies showed that contaminant source terms were reduced to near maximum contaminant levels (MCL's) for drinking water within one or two pore volumes; thus, a limited source term for groundwater contamination exists. At sites where significant groundwater movement or infiltration is expected and the tailings leachates are alkaline, however, the sodium bentonite or asphalt membrane may be necessary.

  3. Uranium Mill Tailings Remedial Action Program. Annual status report

    SciTech Connect (OSTI)

    Not Available

    1983-12-01

    The FY 1983 project accomplishments are: completed the Remedial Action Plan and Phase I engineering design for the Canonsburg processing site; completed remedial action on an additional 52 vicinity properties and the inclusion of an additional 303 properties in the Uranium Mill Tailings Remedial Action Project; executed cooperative agreements with four states and the Navajo Nation; published the draft environmental impact statement for Salt Lake City site; and issued the approved Project Plan.

  4. Revegetation/rock cover for stabilization of inactive uranium mill tailings disposal sites

    SciTech Connect (OSTI)

    Beedlow, P.A.; McShane, M.C.; Cadwell, L.L.

    1982-07-01

    Pacific Northwest Laboratory is developing design and performance guidelines for surface stabilization of inactive uranium mill tailings. In this work, vegetation and rock covers are being evaluated for maintaining long-term integrity of impoundment systems. Methods are being developed to estimate erosion rates associated with rock and/or vegetation covers, and to determine the effects of surface treatments on soil moisture. Interactions between surface treatments and barriers (radon and biological) are being studied as well. The product will be a set of guidelines to aid in designing surface covers. This report presents the status of this program and a discussion of considerations pertinent to the application of surface covers to tailings. Test plots located in Grand Junction, Colorado and Waterflow, New Mexico are being used to study: (1) the interactions between vegetation and radon and biological barriers, (2) the effects of surface covers on soil moisture, and (3) the effects of rock covers on vegetation.

  5. DOE - Office of Legacy Management -- Climax Uranium Co Grand Junction Mill

    Office of Legacy Management (LM)

    - CO 0-03 Climax Uranium Co Grand Junction Mill - CO 0-03 FUSRAP Considered Sites Site: Climax Uranium Co. (Grand Junction Mill) (CO.0-03) Designated Name: Alternate Name: Location: Evaluation Year: Site Operations: Site Disposition: Radioactive Materials Handled: Primary Radioactive Materials Handled: Radiological Survey(s): Site Status: Also see Grand Junction, Colorado, Processing Site Documents Related to Climax Uranium Co. (Grand Junction Mill) Data Validation Package for the August

  6. DOE to Transport Moab Mill Tailings by Rail | Department of Energy

    Energy Savers [EERE]

    to Transport Moab Mill Tailings by Rail DOE to Transport Moab Mill Tailings by Rail August 5, 2008 - 2:40pm Addthis Department Approves Project Baseline and Obtains Nuclear Regulatory Commission Nod WASHINGTON, DC - The U.S. Department of Energy (DOE) today reaffirmed its prior decision to relocate mill tailings predominantly by rail from the former uranium-ore processing site near Moab, Utah, 30 miles north to Crescent Junction, Utah. As determined previously, oversized material that is not

  7. Uranium Mill Tailings Remedial Action Project 1993 Environmental Report

    SciTech Connect (OSTI)

    Not Available

    1994-10-01

    This annual report documents the Uranium Mill Tailing Remedial Action (UMTRA) Project environmental monitoring and protection program. The UMTRA Project routinely monitors radiation, radioactive residual materials, and hazardous constituents at associated former uranium tailings processing sites and disposal sites. At the end of 1993, surface remedial action was complete at 10 of the 24 designated UMTRA Project processing sites. In 1993 the UMTRA Project office revised the UMTRA Project Environmental Protection Implementation Plan, as required by the US DOE. Because the UMTRA Project sites are in different stages of remedial action, the breadth of the UMTRA environmental protection program differs from site to site. In general, sites actively undergoing surface remedial action have the most comprehensive environmental programs for sampling media. At sites where surface remedial action is complete and at sites where remedial action has not yet begun, the environmental program consists primarily of surface water and ground water monitoring to support site characterization, baseline risk assessments, or disposal site performance assessments.

  8. Uranium Mill Tailings Remedial Action Project. 1995 Environmental Report

    SciTech Connect (OSTI)

    1996-06-01

    In accordance with U.S. Department of Energy (DOE) Order 23 1. 1, Environment, Safety and Health Reporting, the DOE prepares an annual report to document the activities of the Uranium Mill Tailings Remedial Action (UMTRA) Project environmental monitoring program. This monitoring must comply with appropriate laws, regulations, and standards, and it must identify apparent and meaningful trends in monitoring results. The results of all monitoring activities must be communicated to the public. The UMTRA Project has prepared annual environmental reports to the public since 1989.

  9. Moab Mill Tailings Removal Project Plans to Resume Train Shipments in March; All of the Laid Off Workers Will Return

    Broader source: Energy.gov [DOE]

    Grand Junction, CO ― All 27 employees of the Remedial Action Contractor (RAC) to the U.S. Department of Energy will return to work on the Uranium Mill Tailings Remedial Action Project on March 4, following a 3-month planned furlough. Project shipping and disposal operations have been shut down, as planned, since late November 2012, but are scheduled to resume March 7, after the contractor ensures employees have received refresher training, reviewed procedures, and measures are in place for a safe startup.

  10. Economic impact study of the Uranium Mill Tailings Remedial Action project in Colorado: Colorado state fiscal year 1995

    SciTech Connect (OSTI)

    1995-12-01

    This Colorado economic impact study summarizes employment and economic benefits to the state from activities associated with the Uranium Mill Tailings Remedial Action (UMTRA) Project during Colorado state fiscal year (FY) 1995 (1 July 1994 through 30 June 1995). To capture employment information, a questionnaire was distributed to subcontractor employees at the active UMTRA Project sites of Grand Junction, Gunnison, Maybell, Naturita, Rifle, and Slick Rock, Colorado. Economic data were requested from the Remedial Action Contractor (RAC), the Technical Assistance Contractor (TAC) and the US Department of Energy (DOE). The most significant benefits associated with the UMTRA Project in Colorado are summarized.

  11. Moab Uranium Mill Tailings Cleanup Project Steps into Spotlight at International Meeting in Vienna

    Broader source: Energy.gov [DOE]

    VIENNA – The Moab Uranium Mill Tailings Remedial Action (UMTRA) Project has kept the United States at the forefront of characterization, remediation, and end-state reuse of uranium millsites around the world.

  12. Moab Project Disposes 2 Million Tons of Uranium Mill Tailings with Recovery Act Funds

    Broader source: Energy.gov [DOE]

    The Moab Uranium Mill Tailings Remedial Action Project reached its primary American Recovery and Reinvestment Act milestone ahead of schedule on Wednesday with the disposal of 2 million tons of...

  13. DOE Amends Decision for the Remediation of the Moab Uranium Mill Tailings in Moab, Utah

    Broader source: Energy.gov [DOE]

    WASHINGTON, DC - The U.S. Department of Energy (DOE) today announced an amendment to its 2005 Record of Decision (ROD) for the Moab Uranium Mill Tailings Remedial Action (UMTRA) Project to allow...

  14. 2013 Annual Site Inspection and Monitoring Report for Uranium Mill Tailings

    Office of Scientific and Technical Information (OSTI)

    Radiation Control Act Title I Disposal Sites (Technical Report) | SciTech Connect Technical Report: 2013 Annual Site Inspection and Monitoring Report for Uranium Mill Tailings Radiation Control Act Title I Disposal Sites Citation Details In-Document Search Title: 2013 Annual Site Inspection and Monitoring Report for Uranium Mill Tailings Radiation Control Act Title I Disposal Sites This report, in fulfillment of a license requirement, presents the results of long-term surveillance and

  15. 2013 Annual Site Inspection and Monitoring Report for Uranium Mill Tailings

    Office of Scientific and Technical Information (OSTI)

    Radiation Control Act Title I Disposal Sites (Technical Report) | SciTech Connect Technical Report: 2013 Annual Site Inspection and Monitoring Report for Uranium Mill Tailings Radiation Control Act Title I Disposal Sites Citation Details In-Document Search Title: 2013 Annual Site Inspection and Monitoring Report for Uranium Mill Tailings Radiation Control Act Title I Disposal Sites × You are accessing a document from the Department of Energy's (DOE) SciTech Connect. This site is a product

  16. 2013 Annual Site Inspection and Monitoring Report for Uranium Mill Tailings

    Office of Scientific and Technical Information (OSTI)

    Radiation Control Act Title II Disposal Sites (Technical Report) | SciTech Connect 2013 Annual Site Inspection and Monitoring Report for Uranium Mill Tailings Radiation Control Act Title II Disposal Sites Citation Details In-Document Search Title: 2013 Annual Site Inspection and Monitoring Report for Uranium Mill Tailings Radiation Control Act Title II Disposal Sites This report, in fulfillment of a license requirement, presents the results of long-term surveillance and maintenance

  17. Moab Mill Tailings Removal Project Reaches 5 Million Tons Disposed: Project

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Accomplishes Milestone While Doing it Safely | Department of Energy Moab Mill Tailings Removal Project Reaches 5 Million Tons Disposed: Project Accomplishes Milestone While Doing it Safely Moab Mill Tailings Removal Project Reaches 5 Million Tons Disposed: Project Accomplishes Milestone While Doing it Safely February 27, 2012 - 12:00pm Addthis Media Contacts Donald Metzler, Moab Federal Project Director, (970) 257-2115 Wendee Ryan, S&K Aerospace Public Affairs Manager, (970) 257-2145

  18. DOE Awards Contract for Moab Mill Tailings Cleanup | Department of Energy

    Office of Environmental Management (EM)

    Moab Mill Tailings Cleanup DOE Awards Contract for Moab Mill Tailings Cleanup November 4, 2011 - 12:00pm Addthis Media Contact Bill Taylor bill.taylor@srs.gov 803-952-8564 Cincinnati- The Department of Energy (DOE) announced today that it has awarded a competitive small business contract worth $121.2 million over the next five years as part of the Department's continued efforts to protect the Colorado River and downstream water users by removing uranium tailings at the former Atlas uranium-ore

  19. DOE Moab Project Safely Removes 7 Million Tons of Mill Tailings |

    Office of Environmental Management (EM)

    Department of Energy Moab Project Safely Removes 7 Million Tons of Mill Tailings DOE Moab Project Safely Removes 7 Million Tons of Mill Tailings July 30, 2014 - 12:00pm Addthis View of the Crescent Junction disposal cell, looking northwest. From center left to right, the photo shows final cover, interim cover, tailings, and excavated cell ready to be filled. View of the Crescent Junction disposal cell, looking northwest. From center left to right, the photo shows final cover, interim cover,

  20. Scientific basis for risk assessment and management of uranium mill tailings

    SciTech Connect (OSTI)

    Not Available

    1986-01-01

    A National Research Council study panel, convened by the Board on Radioactive Waste Management, has examined the scientific basis for risk assessment and management of uranium mill tailings and issued this final report containing a number of recommendations. Chapter 1 provides a brief introduction to the problem. Chapter 2 examines the processes of uranium extraction and the mechanisms by which radionuclides and toxic chemicals contained in the ore can enter the environment. Chapter 3 is devoted to a review of the evidence on health risks associated with radon and its decay products. Chapter 4 provides a consideration of conventional and possible new technical alternatives for tailings management. Chapter 5 explores a number of issues of comparative risk, provides a brief history of uranium mill tailings regulation, and concludes with a discussion of choices that must be made in mill tailing risk management. 211 refs., 30 figs., 27 tabs.

  1. Engineering assessment of inactive uranium mill tailings: Monument Valley Site, Monument Valley, Arizona

    SciTech Connect (OSTI)

    Not Available

    1981-10-01

    Ford, Bacon and Davis Utah Inc. has reevalated the Monument Valley site in order to revise the March 1977 engineering assessment of the problems resulting from the existence of radioactive uranium mill tailings at Monument Valley, Arizona. This engineering assessment has included the preparation of topographic maps, the performance of core drillings and radiometric measurements sufficient to determine areas and volumes of tailings and radiation exposure of individuals and nearby populations, the investigations of site hydrology and meteorology, and the evaluation and costing of alternative corrective actions. Radon gas released from the 1.1 million tons of tailings at the Monument Valley site constitutes the most significant environmental impact, although windblown tailings and external gamma radiation also are factors. The four alternative actions presented in this engineering assessment range from millsite decontamination with the addition of 3 m of stabilization cover material (Option I), to removal of the tailings to remote disposal sites and decontamination of the tailings site (Options II through IV). Cost estimates for the four options range from about $6,600,000 for stabilization in-place, to about $15,900,000 for disposal at a distance of about 15 mi. Three principal alternatives for reprocessing the Monument Valley tailings were examined: heap leaching; Treatment at an existing mill; and reprocessing at a new conventional mill constructed for tailings reprocessing. The cost of the uranium recovery is economically unattractive.

  2. Assessment of the radiological impact of the inactive uranium-mill tailings at Mexican Hat, Utah

    SciTech Connect (OSTI)

    Haywood, F.F.; Goldsmith, W.A.; Ellis, B.S.; Hubbard, H.M. Jr.; Fox, W.F.; Shinpaugh, W.H.

    1980-03-01

    High surface soil concentrations of /sup 226/Ra and high above-ground measurements of gamma-ray intensity in the vicinity of the inactive uranium-mill tailings at Mexican Hat show both wind and water erosion of the tailings. The former mill area, occupied by a trade school at the time of this survey, shows a comparatively high level of contamination, probably from unprocessed ore on the surface of the ore storage area near the location of the former mill buildings. However, the estimated health effect of exposure to gamma rays during a 2000-hr work year in the area represents an increase of 0.1% in the risk of death from cancer. Exposure of less than 600 persons within 1.6 km of the tailings to radon daughters results in an estimated 0.2%/year increase in risk of lung cancer.

  3. Process for Transition of Uranium Mill Tailings Radiation Control Act Title

    Energy Savers [EERE]

    II Disposal Sites to the U.S. Department of Energy Office of Legacy Management for Long-Term Surveillance and Maintenance | Department of Energy Uranium Mill Tailings Radiation Control Act Title II Disposal Sites to the U.S. Department of Energy Office of Legacy Management for Long-Term Surveillance and Maintenance Process for Transition of Uranium Mill Tailings Radiation Control Act Title II Disposal Sites to the U.S. Department of Energy Office of Legacy Management for Long-Term

  4. Environmental assessment of remedial action at the Slick Rock uranium mill tailings sites, Slick Rock, Colorado

    SciTech Connect (OSTI)

    1995-01-01

    The Uranium Mill Tailings Radiation Control Act of 1978, hereafter referred to as the UMTRCA, authorized the US Department of Energy (DOE) to clean up two uranium mill tailings processing sites near Slick Rock, Colorado, in San Miguel County. The purpose of the cleanup is to reduce the potential health effects associated with the radioactive materials remaining on the processing sites and on vicinity properties (VPs) associated with the sites. The US Environmental Protection Agency (EPA) promulgated standards for the UMTRCA that contained measures to control the contaminated materials and to protect the ground water from further degradation. The sites contain concrete foundations of mill buildings, tailings piles, and areas contaminated by windblown and waterborne radioactive tailings materials. The proposed action is to remediate the UC and NC sites by removing all contaminated materials within the designated site boundaries or otherwise associated with the sites, and relocating them to, and stabilizing them at, a location approximately 5 road mi (8 km) northeast of the processing sites on land administered by the US Bureau of Land Management (BLM). Remediation would be performed by the DOE`s Uranium Mill Tailings Remedial Action (UMTRA) Project.

  5. Engineering assessment of inactive uranium mill tailings: Maybell Site, Maybell, Colorado

    SciTech Connect (OSTI)

    1981-09-01

    Ford, Bacon and Davis Utah Inc. has reevaluated the Maybell site in order to revise the October 1977 engineering assessment of the problems resulting from the existence of radioactive uranium mill tailings at Maybell, Colorado. This engineering assessment has included the preparation of topographic maps, the performance of core drillings and radiometric measurements sufficient to determine areas and volumes of tailings and radiation exposures of individuals and nearby populations, the investigations of site hydrology and meteorology, and the evaluation and costing of alternative corrective actions. Radon gas released from the 2.6 million dry tons of tailings at the Maybell site constitutes the most significant environmental impact, although windblown tailings and external gamma radiation also are factors. The two alternative actions presented in this engineering assessment range from millsite decontamination with the addition of 3 m of stabilization cover material (Option I), to disposal of the tailings in a nearby open pit mine and decontamination of the tailings site (Option II). Cost estimates for the two options are about $11,700,000 for stabilization in-place and about $22,700,000 for disposal within a distance of 2 mi. Three principal alternatives for the reprocessing of the Maybell tailings were examined: (a) heap leaching; (b) treatment at an existing mill; and (c) reprocessing at a new conventional mill constructed for tailings reprocessing. The cost of the uranium recovered would be about $125 and $165/lb of U/sub 3/O/sub 8/ by heap leach and conventional plant processes, respectively. The spot market price for uranium was $25/lb early in 1981. Therefore, reprocessing the tailings for uranium recovery is not economically attractive at present.

  6. Engineering assessment of inactive uranium mill tailings: Maybell Site, Maybell, Colorado. Summary

    SciTech Connect (OSTI)

    1981-09-01

    Ford, Bacon and Davis Utah Inc. has reevaluated the Maybell site in order to revise the October 1977 engineering assessment of the problems resulting from the existence of radioactive uranium mill tailings at Maybell, Colorado. This engineering assessment has included the preparation of topographic maps, the performance of core drillings and radiometric measurements sufficient to determine areas and volumes of tailings and radiation exposures of individuals and nearby populations, the investigations of site hydrology and meteorology, and the evaluation and costing of alternative corrective actions. Radon gas released from the 2.6 million dry tons of tailings at the Maybell site constitutes the most significant environmental impact, although windblown tailings and external gamma radiation also are factors. The two alternative actions presented in this engineering assessment range from millsite decontamination with the addition of 3 m of stabilization cover material (Option I), to disposal of the tailings in a nearby open pit mine and decontamination of the tailings site (Option II). Cost estimates for the two options are about $11,700,000 for stabilization in-place and about $22,700,000 for disposal within a distance of 2 mi. Three principal alternatives for the reprocessing of the Maybell tailings were examined: (a) heap leaching; (b) treatment at an existing mill; and (c) reprocessing at a new conventional mill constructed for tailings reprocessing. The cost of the uranium recovered would be about $125 and $165/lb of U/sub 3/O/sub 8/ by heap leach and conventional plant processes, respectively. The spot market price for uranium was $25/lb early in 1981. Therefore, reprocessing the tailings for uranium recovery is not economically attractive at present.

  7. Engineering assessment of inactive uranium mill tailings: Mexican Hat Site, Mexican Hat, Utah

    SciTech Connect (OSTI)

    1981-09-01

    Ford, Bacon and Davis Utah Inc. has reevaluated the Mexican Hat site in order to revise the March 1977 engineering assessment of the problems resulting from the existence of radioactive uranium mill tailings at Mexican Hat, Utah. This engineering assessment has included the preparation of topographic maps, the performance of core drillings and radiometric measurements sufficient to determine areas and volumes of tailings and radiation exposures of individuals and nearby populations, the investigations of site hydrology and meteorology, and the evaluation and costing of alternative corrective actions. Radon gas released from the 2.2 million tons of tailings at the Mexican Hat site constitutes the most significant environmental impact, although windblown tailings and external gamma radiation also are factors. The four alternative actions presented in this engineering assessment range from millsite decontamination with the addition of 3 m of stabilization cover material to removal of the tailings to remote disposal sites and decontamination of the tailings site. Cost estimates for the four options range from about $15,200,000 for stabilization in place, to about $45,500,000 for disposal at a distance of about 16 mi. Three principal alternatives for the reprocessing of the Mexican Hat tailings were examined: heap leaching; treatment at an existing mill; and reprocessing at a new conventional mill constructed for tailings reprocessing. The cost of the uranium recovered would be about $115/lb of U/sub 3/O/sub 8/ whether by heap leach or conventional plant processes. The spot market price for uranium was $25/lb early in 1981. Reprocessing the Mexican Hat tailings for uranium recovery is not economically attractive under present conditions.

  8. Summary of the engineering assessment of inactive uranium mill tailings, Shiprock Site, Shiprock, New Mexico

    SciTech Connect (OSTI)

    1981-07-01

    Ford, Bacon and Davis Utah Inc. has reevaluated the Shiprock site in order to revise the March 1977 engineering assessment of the problems resulting from the existence of radioactive uranium mill tailings at Shiprock, New Mexico. This engineering assessment has included the preparation of topographic maps, the performance of core drillings and radiometric measurements sufficient to determine areas and volumes of tailings and radiation exposures of individuals and nearby populations, the investigations of site hydrology and meteorology, and the evaluation and costing of alternative corrective actions. Radon gas released from the 1.5 million dry tons of tailings at the Shiprock site constitutes the most significant environmental impact, although windblown tailings and external gamma radiation also are factors. The eight alternative actions presented in this engineering assessment range from millsite decontamination with the addition of 3 m of the stabilization cover material (Option I), to removal of the tailings to remote disposal sites and decontamination of the tailings site (Options II through VIII). Cost estimates for the eight options range from about $13,400,000 for stabilization in place to about $37,900,000 for disposal at a distance of about 16 miles. Three principal alternatives for the reprocessing of the Shiprock tailings were examined: (a) heap leaching; (b) treatment at an existing mill; and(c) reprocessing at a new conventional mill constructed for tailings reprocessing. The cost of the uranium recovered would be about $230/lb by heap leach and $250/lb by conventional plant processes. The spot market price for uranium was $25/lb early in 1981. Therefore, reprocessing the tailings for uranium recovery is not economically attractive.

  9. CLEANING UP MILL TAILINGS AND GROUND WATER AT THE MOAB UMTRA PROJECT SITE

    Broader source: Energy.gov [DOE]

    Moab, UT - Sixteen million tons of uranium mill tailings 80 feet high stood on the banks of the Colorado River near Moab in southeast Utah, as a legacy to the former ore-processing site that operated for nearly three decades beginning in the mid-1950s.

  10. Monticello Mill Tailings, Operable Unit III Surface and Ground Water Remedial Investigation Addendum/Focused Feasibility Study

    Office of Legacy Management (LM)

    S H E E T November 2003 Figure 1. Monticello Millsite Location Background The Monticello Mill Tailings Site is a former ore-buying station and vanadium and uranium mill that operated from about 1942 through 1959 (see Figure 1). The former millsite and nearby properties are being cleaned up as required by the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA). The Monticello Mill Tailings Site was placed on the U.S. Environmental Protection Agency National Priorities

  11. Engineering assessment of inactive uranium mill tailings, Gunnison Site, Gunnison, Colorado: summary

    SciTech Connect (OSTI)

    none,

    1981-09-01

    Ford, Bacon and Davis Utah Inc. has reevaluated the Gunnison site in order to revise the November 1977 engineering assessment of the problems resulting from the existence of radioactive uranium mill tailings at Gunnison, Colorado. This evaluation has included the preparation of topographic maps, the performance of core drillings and radiometric measurements sufficient to determine areas and volumes of tailings and radiation exposures of individuals and nearby populations, the ivnvestigations of site hydrology and meteorology, and the evaluation and costing of alternative remedial actions. Radon gas released from the combined 540,000 dry tons of tailings and the 435,400 tons of contaminated waste at the Gunnison site constitutes the most significant environmental impact, although windblown tailings and external gamma radiation also are factors. The 10 alternative actions presented in this engineering assessment range from stabilization of the site in its present location with the addition of 3 m of stabilization cover material (Option I), to removal of the tailings to disposal sites along with decontamination of the Gunnison site (Options II through X). Cost estimates for the 10 options range from about $8,900,000 for stabilization in-place, to about $14,000,000 for disposal in the North Alkali Creek area at a distance of about 18 mi. Truck haulage would be used to transport the tailings and contaminated materials from the Gunnison site to the selected disposal site. Three principal alternatives for the reprocessing of the Gunnison tailings were examined: heap leaching; treatment at an existing mill; and reprocessing at a new conventional mill constructed for tailings reprocesssing. The cost of the uranium recovered would be about $250 and $230/lb of U/sub 3/O/sub 8/ by heap leach and conventional plant processes, respectively. The spot market price for uranium was $25/lb early in 1981.

  12. Cleanup of inactive Uranium Mill Tailings Sites in the Navajo Nation

    SciTech Connect (OSTI)

    Martin, B.

    1994-12-31

    The U.S. Congress passed the Uranium Mill Tailings Radiation Control Act (UMTRCA) in 1978 to address potential and significant radiation health hazards to the public from active and inactive mill operations. Title I to the UMTRCA identified sites to be designated for remedial action. These include four uranium mill tailings remedial action (UMTRA) sites in the Navajo Nation. These sites are located in Shiprock, New Mexico; Tuba City, Arizona; Cane Valley, Arizona; and Halchita, Utah. The U.S. Department of Energy (DOE) was directed to select and execute a plan of remedial action that provides long-term stabilization and control of radioactive materials and satisfies the U.S. Environmental Protection Agency standards and other applicable laws and regulations.

  13. Economic impact study of the Uranium Mill Tailings Remedial Action Project in Colorado: Colorado State fiscal year 1994. Revision 1

    SciTech Connect (OSTI)

    Not Available

    1994-12-01

    The Colorado economic impact study summarizes employment and economic benefits to the state from activities associated with the Uranium Mill Tailings Remedial Action (UMTRA) Project during Colorado state fiscal year 1994 (1 July 1993 through 30 June 1994). To capture employment information, a questionnaire was distributed to subcontractor employees at the active UMTRA Project sites of Grand Junction, Naturita, Gunnison, and Rifle, Colorado. Economic data were requested from each site prime subcontractor, as well as from the Remedial Action Contractor. Information on wages, taxes, and subcontract expenditures in combination with estimates and economic multipliers is used to estimate the dollar economic benefits to Colorado during the state fiscal year. Finally, the fiscal year 1994 estimates are compared to fiscal year 1993 employment and economic information.

  14. Long-term protection of uranium mill tailings

    SciTech Connect (OSTI)

    Beedlow, P.A.; Hartley, J.N.

    1984-04-01

    US Environmental Protection Agency standards for the cleanup and disposal of inactive tailings sites require that control measures for disposal of tailings be designed to be effective for up to 1000 years if reasonably achievable, and, in any case, for 200 years at least. To control the escape of contaminants over such long periods, containment systems must be capable of adjusting to changing environmental conditions. Elements of a containment system include surface covers, biotic barriers, radon barriers, and, in some cases, liners. Each element of the system affects the others, and the whole system responds to the surrounding environment. Interaction is facilitated primarily by soil moisture. Consequently, the control of soil moisture is critical to the effectiveness of containment systems. Protective covers are necessary to prevent disruption of the containment system by physical or biological factors, to provide for the effective functioning of the radon barrier, and to prevent infiltration of excess water that could cause leaching. In order to design protective covers, a working knowledge of the factors and processes impacting tailings piles is required. This report characterizes the major factors and processes, and presents generic solutions based on current research. 65 references, 9 figures, 6 tables.

  15. The U.S. regulatory framework for long-term management of uranium mill tailings

    SciTech Connect (OSTI)

    Smythe, C.; Bierley, D.; Bradshaw, M.

    1995-03-01

    The US established the regulatory structure for the management, disposal, and long-term care of uranium mill tailings in 1978 with the passage of the Uranium Mill Tailings Radiation Control Act (UMTRCA) (Pub. L. 95-604). This legislation has governed the cleanup and disposal of uranium tailings at both inactive and active sites. The passage of the UMTRCA established a federal regulatory program for the cleanup and disposal of uranium mill tailings in the US. This program involves the DOE, the NRC, the EPA, various states and tribal governments, private licensees, and the general public. The DOE has completed surface remediation at 14 sites, with the remaining sites either under construction or in planning. The DOE`s UMTRA Project has been very successful in dealing with public and agency demands, particularly regarding disposal site selection and transportation issues. The active sites are also being cleaned up, but at a slower pace than the inactive sites, with the first site tentatively scheduled for completion in 1996.

  16. Summary of the engineering assessment of inactive uranium mill tailings, Tuba City site, Tuba City, Arizona

    SciTech Connect (OSTI)

    1981-09-01

    Ford, Bacon and Davis Utah Inc. has reevaluated the Tuba City site in order to revise the March 1977 engineering assessment of the problems resulting from the existence of radioactive uranium mill tailings at Tuba City, Arizona. This engineering assessment has included the preparation of topographic maps, the performance of core drillings and radiometric measurements sufficient to determine areas and volumes of tailings and radiation exposures of individuals and nearby populations, the investigations of site hydrology and meteorology, and the evaluation and costing of alternative corrective actions. Radon gas released from the 0.8 million tons of tailings at the Tuba City site constitutes the most significant environmental impact, although windblown tailings and external gamma radiation also are factors.

  17. Engineering assessment of inactive uranium mill tailings, Tuba City site, Tuba City, Arizona

    SciTech Connect (OSTI)

    Not Available

    1981-09-01

    Ford, Bacon and Davis Utah Inc. has reevaluated the Tuba City site in order to revise the March 1977 engineering assessment of the problems resulting from the existence of radioactive uranium mill tailings at Tuba City, Arizona. This engineering assessment has included the preparation of topographic maps, the performance of core drillings and radiometric measurements sufficient to determine areas and volumes of tailings and radiation exposures of individuals and nearby populations, the investigations of site hydrology and meteorology, and the evaluation and costing of alternative corrective actions. Radon gas released from the 0.8 million tons of tailings at the Tuba City site constitutes the most significant environmental impact, although windblown tailings and external gamma radiation also are factors.

  18. BASELINE RISK ASSESSMENT OF GROUND WATER CONTAMINATION AT THE URAN~UM MILL TAILINGS

    Office of Legacy Management (LM)

    I~:-:ii*.i: i,<;.;.-;_r- --:-:ir-- - . . - -. . - . . - , -, . , , , - - - - . BASELINE RISK ASSESSMENT OF GROUND WATER CONTAMINATION AT THE URAN~UM MILL TAILINGS SITE NEAR RIVERTON, WYOMING I i I I I Prepared by the U.S. Department of Energy Albuquerque, New Mexico September 1995 INTENDED FOR PUBLIC RELEASE This report has been reproduced from the best available copy. Avai and microfiche Number of pages in this report: 166 DOE and DOE contractors can obtain copies of this report from: Office

  19. Environmental factors affecting long-term stabilization of radon suppression covers for uranium mill tailings

    SciTech Connect (OSTI)

    Young, J.K.; Long, L.W.; Reis, J.W.

    1982-04-01

    Pacific Northwest Laboratory is investigating the use of a rock armoring blanket (riprap) to mitigate wind and water erosion of an earthen radon suppression cover applied to uranium mill tailings. To help determine design stresses for the tailings piles, environmental parameters are characterized for the five active uranium-producing regions on a site-specific basis. Only conventional uranium mills that are currently operating or that are scheduled to open in the mid 1980s are considered. Available data indicate that flooding has the most potential for disrupting a tailings pile. The arid regions of the Wyoming Basins and the Colorado Plateau are subject to brief storms of high intensity. The Texas Gulf Coast has the highest potential for extreme precipitation from hurricane-related storms. Wind data indicate average wind speeds from 3 to 6 m/sec for the sites, but extremes of 40 m/sec can be expected. Tornado risks range from low to moderate. The Colorado Plateau has the highest seismic potential, with maximum acceleration caused by earthquakes ranging from 0.2 to 0.4 g. Any direct effect from volcanic eruption is negligible, as all mills are located 90 km or more from an igneous or hydrothermal system.

  20. Radiological survey of the inactive uranium-mill tailings at Rifle, Colorado

    SciTech Connect (OSTI)

    Haywood, F.F.; Jacobs, D.J.; Ellis, B.S.; Hubbard, H.M. Jr.; Shinpaugh, W.H.

    1980-06-01

    Results of radiological surveys of two inactive uranium-mill sites near Rifle, Colorado, in May 1976 are presented. These sites are referred to as Old Rifle and New Rifle. The calculated /sup 226/Ra inventory of the latter site is much higher than at the older mill location. Data on above-ground measurements of gamma exposure rates, surface and near-surface concentration of /sup 226/Ra in soil and sediment samples, concentration of /sup 226/Ra in water, calculated subsurface distribution of /sup 226/Ra, and particulate radionuclide concentrations in air samples are given. The data serve to define the extent of contamination in the vicinity of the mill sites and their immediate surrounding areas with tailings particles. Results of these measurements were utilized as technical input for an engineering assessment of these two sites.

  1. Remedial action plan and site design for stabilization of the inactive uranium mill tailings sites at Rifle, Colorado

    SciTech Connect (OSTI)

    Not Available

    1992-02-01

    This appendix assesses the present conditions and data gathered about the two inactive uranium mill tailings sites near Rifle, Colorado, and the designated disposal site six miles north of Rifle in the area of Estes Gulch. It consolidates available engineering, radiological, geotechnical, hydrological, meteorological, and other information pertinent to the design of the Remedial Action Plan (RAP). The data characterize conditions at the mill, tailings, and disposal site so that the Remedial Action Contractor (RAC) may complete final designs for the remedial actions.

  2. Economic impact study of the Uranium Mill Tailings Remedial Action Project in Colorado: Colorado state fiscal year 1994

    SciTech Connect (OSTI)

    Not Available

    1994-11-01

    The Colorado economic impact study summarizes employment and economic benefits to the state from activities associated with the Uranium Mill Tailings Remedial Action (UMTRA) Project during Colorado state fiscal year 1994. To capture employment information, a questionnaire was distributed to subcontractor employees at the active UMTRA Project sites of Grand Junction, Naturita, Gunnison, and Rifle, Colorado. Economic data were requested from each site prime subcontractor, as well as from the Remedial Action Contractor. The most significant benefits associated with the UMTRA Project in Colorado are summarized. This study assesses benefits associated with the Grand Junction, Gunnison, Naturita, and Rifle UMTRA Projects sites for the 1-year period under study. Work at the Naturita site was initiated in April 1994 and involved demolition of buildings at the processing site. Actual start-up of remediation of Naturita is planned to begin in the spring of 1995. Work at the Slick Rock and Maybell sites is expected to begin in 1995. The only current economic benefits associated with these sites are related to UMTRA Project support work.

  3. Radiological survey of the inactive uranium-mill tailings at Maybell, Colorado

    SciTech Connect (OSTI)

    Haywood, F.F.; Perdue, P.T.; Ellis, B.S.

    1980-03-01

    Results of a radiological survey of the inactive uranium-mill tailings near Maybell, Colorado are presented. Measurements of external gamma exposure rate at 1 m above the tailings ranged 16 to 340 ..mu..R/hr with an average value of 65 ..mu..R/hr. Radionuclide analysis of offsite soil and sediment samples, as well as above-ground gamma exposure rate measurements defined the spread of contamination around the tailings pile. This spread is greatest toward the east, in the direction of surface water runoff. Calculated concentrations of /sup 226/Ra in all of the holes drilled in the tailngs, based on gamma monitoring data, showed maximum concentrations in the range 100 to 800 pCi/g.

  4. Radiological survey of the inactive uranium-mill tailings at Durango, Colorado

    SciTech Connect (OSTI)

    Haywood, F.F.; Perdue, P.T.; Shinpaugh, W.H.; Ellis, B.S.; Chou, K.D.

    1980-03-01

    Results of a radiological survey of the inactive uranium-mill site at Durango, Colorado, conducted in April 1976, in cooperation with a team from Ford, Bacon and Davis Utah Inc., are presented together with descriptions of the instruments and techniques used to obtain the data. Direct above-ground gamma measurements and analysis of surface soil and sediment samples indicate movement of tailings from the piles toward Lightner Creek on the north and the Animas River on the east side of the piles. The concentration of /sup 226/Ra in the former raffinate pond area is only slightly above the background level. Two structures in Durango were found to contain high concentrations of airborne radon daughters, where tailings are known to have been utilized in construction. Near-background concentrations of radon daughters were found in a well-ventilated building close to the tailings.

  5. Environmental assessment of remedial action at the slick rock Uranium Mill Tailings sites Slick Rock, Colorado

    SciTech Connect (OSTI)

    Not Available

    1994-09-01

    The Uranium Mill Tailings Radiation Control Act of 1978 (42 USC {section} 7901 et seq.), hereafter referred to as the UMTRCA, authorized the U.S. Department of Energy (DOE) to clean up two uranium mill tailings processing sites near Slick Rock, Colorado, in San Miguel County. The purpose of the cleanup is to reduce the potential health effects associated with the radioactive materials remaining on the sites and on vicinity properties (VPs) associated with the sites. Contaminated materials cover an estimated 55 acres of the Union Carbide (UC) processing site and 12 ac of the North Continent (NC) processing site. The total estimated volume of contaminated materials is approximately 61 8,300 cubic yards. In addition to the contamination in the two processing site areas, four VPs were found to contain contamination. As a result of the tailings being exposed to the environment, contamination associated with the UC and NC sites has leached into shallow ground water. Surface water has not been affected. The closest residence is approximately 0.3 air mi from either site. The proposed action is to remediate the UC and NC sites by removing all contaminated materials within the designated site boundaries or otherwise associated with the sites, and relocating them to, and stabilizing them at, a location approximately 5 road mi (8 km) northeast of the sites on land administered by the Bureau of Land Management (BLM). Remediation would be performed by the DOE`s Uranium Mill Tailings Remedial Action (UMTRA) Project. All solid contaminated materials would be buried under 5 feet (ft) of rock and soil materials. The proposed disposal site area is currently used by ranchers for cattle grazing over a 7-month period. The closest residence to the proposed disposal site is 2 air mi. An estimated 44 ac of land would be permanently transferred from the BLM to the DOE and restricted from future use.

  6. Laboratory measurements of contaminant attenuation of uranium mill tailings leachates by sediments and clay liners

    SciTech Connect (OSTI)

    Serne, R.J.; Peterson, S.R.; Gee, G.W.

    1983-04-01

    We discuss FY82 progress on the development of laboratory tools to aid in the prediction of migration potential of contaminants present in acidic uranium mill tailings leachate. Further, empirical data on trace metal and radionuclide migration through a clay liner are presented. Acidic uranium mill tailings solution from a Wyoming mill was percolated through a composite sediment called Morton Ranch Clay liner. These laboratory columns and subsequent sediment extraction data show: (1) As, Cr, Pb, Ag, Th and V migrate very slowly; (2) U, Cd, Ni, Zn, Fe, Mn and similar transition metals are initially immobilized during acid neutralization but later are remobilized as the tailings solution exhausts the clay liner's acid buffering capacity. Such metals remain immobilized as long as the effluent pH remains above a pH value of 4 to 4.5, but they become mobile once the effluent pH drops below this range; and (3) fractions of the Se and Mo present in the influent tailings solution are very mobile. Possible controlling mechanisms for the pH-dependent immobilization-mobilization of the trace metals are discussed. More study is required to understand the controlling mechanisms for Se and Mo and Ra for which data were not successfully collected. Using several column lengths (from 4.5 to 65 cm) and pore volume residence times (from 0.8 to 40 days) we found no significant differences in contaminant migration rates or types and extent of controlling processes. Thus, we conclude that the laboratory results may be capable of extrapolation to actual disposal site conditions.

  7. Laboratory evaluation of limestone and lime neutralization of acidic uranium mill tailings solution. Progress report

    SciTech Connect (OSTI)

    Opitz, B.E.; Dodson, M.E.; Serne, R.J.

    1984-02-01

    Experiments were conducted to evaluate a two-step neutralization scheme for treatment of acidic uranium mill tailings solutions. Tailings solutions from the Lucky Mc Mill and Exxon Highland Mill, both in Wyoming, were neutralized with limestone, CaCO/sub 3/, to an intermediate pH of 4.0 or 5.0, followed by lime, Ca(OH)/sub 2/, neutralization to pH 7.3. The combination limestone/lime treatment methods, CaCO/sub 3/ neutralization to pH 4 followed by neutralization with Ca(OH)/sub 2/ to pH 7.3 resulted in the highest quality effluent solution with respect to EPA's water quality guidelines. The combination method is the most cost-effective treatment procedure tested in our studies. Neutralization experiments to evaluate the optimum solution pH for contaminant removal were performed on the same two tailings solutions using only lime Ca(OH)/sub 2/ as the neutralizing agent. The data indicate solution neutralization above pH 7.3 does not significantly increase removal of pH dependent contaminants from solution. Column leaching experiments were performed on the neutralized sludge material (the precipitated solid material which forms as the acidic tailings solutions are neutralized to pH 4 or above). The sludges were contacted with laboratory prepared synthetic ground water until several effluent pore volumes were collected. Effluent solutions were analyzed for macro ions, trace metals and radionuclides in an effort to evaluate the long term effectiveness of attenuating contaminants in sludges formed during solution neutralization. Neutralized sludge leaching experiments indicate that Ca, Na, Mg, Se, Cl, and SO/sub 4/ are the only constituents which show solution concentrations significantly higher than the synthetic ground water in the early pore volumes of long-term leaching studies.

  8. Summary report on reprocessing evaluation of selected inactive uranium mill tailings sites

    SciTech Connect (OSTI)

    Not Available

    1983-09-01

    Sandia National Laboratories has been assisting the Department of Energy in the Uranium Mill Tailings Remedial Actions Program (UMTRAP) the purpose of which is to implement the provisions of Title I of Public Law 95-604, Uranium Mill Tailings Radiation Control Act of 1978.'' As part of this program, there was a need to evaluate the mineral concentration of the residual radioactive materials at some of the designated processing sites to determine whether mineral recovery would be practicable. Accordingly, Sandia contracted Mountain States Research and Development (MSRD), a division of Mountain States Mineral Enterprises, to drill, sample, and test tailings at 12 sites to evaluate the cost of and the revenue that could be derived from mineral recovery. UMTRAP related environmental and engineering sampling and support activities were performed in conjunction with the MSRD operations. This summary report presents a brief description of the various activities in the program and of the data and information obtained and summarizes the results. 8 refs., 9 tabs.

  9. Environmental assessment of remedial action at the Mexican Hat uranium mill tailings site, Mexican Hat, Utah. [Contains glossary

    SciTech Connect (OSTI)

    Not Available

    1987-10-01

    This document assesses the environmental impacts of the proposed remedial action at the Mexican Hat uranium mill tailings site located on the Navajo Reservation in southern Utah. The site covers 235 acres and contains 69 acres of tailings and several of the original mill structures. Remedial action must be performed in accordance with standards and with the concurrence of the US Nuclear Regulatory Commission and the Navajo Nation. The proposed action is to stabilize the tailings within the present tailings site by consolidating the tailings and associated contaminated soils into a recontoured pile. A radon barrier of compacted earth would be constructed over the pile, and various erosion control measures would be taken to assure the long-term stability of the pile. The no action alternative is also assessed in this document. 240 refs., 12 figs., 20 tabs.

  10. Environmental assessment of remedial action at the Maybell uranium mill tailings site near Maybell, Colorado

    SciTech Connect (OSTI)

    Not Available

    1993-09-01

    The purpose of this environmental assessment (EA) is to evaluate the environmental impacts resulting from remedial action at the Maybell uranium mill tailings site near Maybell, Colorado. A biological assessment (Attachment 1) and a floodplain/wetlands assessment (Assessment 2) are included as part of this EA. The following sections and attachments describe the proposed action, affected environment, and environmental impacts associated with the proposed remedial action, including impacts to threatened and endangered species listed or proposed for listing by the US Fish and Wildlife Service.

  11. Uranium Mill Tailings Remedial Action Project Safety Advancement Field Effort (SAFE) Program

    SciTech Connect (OSTI)

    Not Available

    1994-02-01

    In 1992, the Uranium Mill Tailings Remedial Action (UMTRA) Project experienced several health and safety related incidents at active remediation project sites. As a result, the U.S. Department of Energy (DOE) directed the Technical Assistance Contractor (TAC) to establish a program increasing the DOE`s overall presence at operational remediation sites to identify and minimize risks in operations to the fullest extent possible (Attachments A and B). In response, the TAC, in cooperation with the DOE and the Remedial Action Contractor (RAC), developed the Safety Advancement Field Effort (SAFE) Program.

  12. Environmental Assessment of remedial action at the Ambrosia Lake uranium mill tailings site, Ambrosia Lake, New Mexico

    SciTech Connect (OSTI)

    Not Available

    1987-06-01

    This document assesses and compares the environmental impacts of various alternatives for remedial action at the Ambrosia Lake uranium mill tailings site located near Ambrosia Lake, New Mexico. The designated site covers 196 acres and contains 111 acres of tailings and some of the original mill structures. The Uranium Mill Tailings Radiation Control Act (UMTRCA), Public Law 95-604, authorizes the US Department of Energy to clean up the site to reduce the potential health impacts associated with the residual radioactive materials remaining at the site and at associated properties off the site. The US Environmental Protection Agency promulgated standards for th remedial action (40 CFR Part 192). Remedial action must be performed in accordance with these standards and with the concurrence of the Nuclear Regulatory Commission. The proposed action is to stabilize the tailings at their present location by consolidating the tailings and associated contaminated materials into a recontoured pile. A radon barrier would be constructed over the pile and various erosion protection measures would be taken to assure the long-term stability of the pile. Another alternative which would involve moving the tailings to a new location is also assessed in this document. This alternative would generally involve greater short-term impacts and costs but would result in stabilization of the tailings at an undeveloped location. The no action alternative is also assessed in this document.

  13. Grand Junction, Colorado, Processing Site and Disposal Sites Fact Sheet

    Office of Legacy Management (LM)

    Grand Junction, Colorado, Disposal and Processing Sites This fact sheet provides information about the Uranium Mill Tailings Radiation Control Act of 1978 Title I disposal and processing sites at Grand Junction, Colorado. These sites are managed by the U.S. Department of Energy Office of Legacy Management. Locations of the Grand Junction, Colorado, Sites Site Description and History The former Grand Junction processing site, historically known as the Climax uranium mill, sits at an elevation of

  14. Baseline risk assessment of ground water contamination at the Uranium Mill Tailings Site near Naturita, Colorado

    SciTech Connect (OSTI)

    1995-08-01

    The Uranium Mill Tailings Remedial Action (UMTRA) Project consists of the Surface Project (phase I), and the Ground Water Project (phase II). For the UMTRA Project site located near Naturita, Colorado (the Naturita site), phase I involves the removal of radioactively contaminated soils and materials and their transportation to a disposal site at Union Carbide Corporation`s Upper Burbank Repository at Uravan, Colorado, about 13 road miles (mi) (21 kilometers [km]) to the northwest. No uranium mill tailings are involved because the tailings were removed from the Naturita site and placed at Coke Oven, Colorado, during 1977 to 1979. Phase II of the project will evaluate the nature and extent of ground water contamination resulting from uranium processing and its effect on human health or the environment; and will determine site-specific ground water compliance strategies in accordance with the US Environmental Protection Agency (EPA) ground water standards established for the UMTRA Project. Human health risks could occur from drinking water pumped from a hypothetical well drilled in the contaminated ground water area. Environmental risks may result if plants or animals are exposed to contaminated ground water, or surface water that has received contaminated ground water. Therefore, a risk assessment is conducted for the Naturita site. This risk assessment report is the first site-specific document prepared for the Ground Water Project at the Naturita site. What follows is an evaluation of current and possible future impacts to the public and the environment from exposure to contaminated ground water. The results of this evaluation and further site characterization will be used to determine whether any action is needed to protect human health or the environment.

  15. Baseline risk assessment for groundwater contamination at the uranium mill tailings site near Monument Valley, Arizona. Draft

    SciTech Connect (OSTI)

    Not Available

    1993-09-01

    This baseline risk assessment evaluates potential impact to public health or the environment resulting from groundwater contamination at the former uranium mill processing site near Monument Valley, Arizona. The tailings and other contaminated material at this site are being relocated and stabilized in a disposal cell at Mexican Hat, Utah, through the US Department of Energy (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project. The tailings removal is planned for completion by spring 1994. After the tailings are removed, groundwater contamination at the site will continue to be evaluated. This risk assessment is the first document specific to this site for the Groundwater Project. It will be used to assist in determining what remedial action is needed for contaminated groundwater at the site.

  16. Baseline risk assessment of ground water contamination at the Uranium Mill Tailings Site near Maybell, Colorado

    SciTech Connect (OSTI)

    1996-03-01

    The U.S. Department of Energy (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project consists of the Surface Project (Phase I) and the Ground Water Project (Phase II). Under the UMTRA Surface Project, tailings, contaminated soil, building foundations, and materials associated with the former processing of uranium ore at UMTRA Project sites are placed into disposal cells. The cells are designed to reduce radon and other radiation emissions and to prevent further contamination of ground water. One UMTRA Project site is near Maybell, Colorado. Surface cleanup at this site began in 1995 and is scheduled for completion in 1996. The tailings are being stabilized in place at this site. The disposal area has been withdrawn from public use by the DOE and is referred to as the permanent withdrawal area. The Ground Water Project evaluates the nature and extent of ground water contamination resulting from past uranium ore processing activities. The Ground Water Project at this site is in its beginning stages. This report is a site-specific document that will be used to evaluate current and future potential impacts to the public and the environment from exposure to contaminated ground water. The results presented in this document and other evaluations will determine whether any action is needed to protect human health or the environment.

  17. Survivability of ancient man-made earthen mounds: implications for uranium mill tailings impoundments

    SciTech Connect (OSTI)

    Lindsey, C.G.; Mishima, J.; King, S.E.; Walters, W.H.

    1983-06-01

    As part of a study for the Nuclear Regulatory Commission (NRC), the Pacific Northwest Laboratory (PNL) is investigating long-term stabilization techniques for uranium mill impoundments. Part of this investigation involves the design of a rock armoring blanket (riprap) to mitigate wind and water erosion of the underlying soil cover, which in turn prevents exposure of the tailings to the environment. However, the need for the armoring blanket, as well as the blanket's effectiveness, depends on the stability of the underlying soil cap (radon suppression cover) and on the tailings themselves. Compelling evidence in archaeological records suggests that large man-made earthen structures can remain sound and intact for time periods comparable to those required for the stabilization of the tailings piles if properly constructed. We present archaeological evidence on the existence and survivability of man-made earthen and rock structures through specific examples of such structures from around the world. We also review factors contributing to their survival or destruction and address the influence of climate, building materials, and construction techniques on survivability.

  18. Economic evaluation of inactive uranium mill tailings, Gunnison Site, Gunnison, Colorado

    SciTech Connect (OSTI)

    Teel, J H

    1982-12-01

    Mountain States Research and Development was contracted on March 1, 1981 to make an economic evaluation study at each of 12 abandoned uranium mill tailings sites in the western states. The objective of this work was to obtain the data necessary at each site to determine the possible revenue that could be derived from reprocessing the tailings. To accomplish this objective a drilling and sampling program was established for each site to determine the total amount of tailings and subbase material available for treatment and the amount of recoverable uranium, vanadium and molybdenum. These three metals were selected due to their common occurrence in uranium ores and common extractability in the leaching process. Laboratory leaching was then conducted on the samples obtained to determine the extractability of each of these metals and the optimum plant process to be applied. As the metal contents were generally low and represented mineral that had not been leached during previous processing, the economic evaluation is limited to consideration of the direct capital and operating costs required in connection with processing of each respective site material. Excavating, transportation and disposal of the material from each site in an environmentally acceptable location and manner was not within the scope of this project. It will be necessary to complete a separate study of these areas in order to determine the total costs involved. This report contains the results of the investigations of the Old Rifle Site.

  19. Environmental assessment of remedial action at the Slick Rock uranium mill tailings sites, Slick Rock, Colorado. Revision 1

    SciTech Connect (OSTI)

    Not Available

    1994-09-01

    The Uranium Mill Tailings Radiation Control Act of 1978 (42 USC {section}7901 et seq.), hereafter referred to as the UMTRCA, authorized the US Department of Energy (DOE) to clean up two uranium mill tailings processing sites near Slick Rock, Colorado, in San Miquel County. Contaminated materials cover an estimated 63 acres of the Union Carbide (UC) processing site and 15 ac of the North Continent (NC) processing site. The sites are within 1 mile of each other and are adjacent to the Dolores River. The sites contain concrete foundations of mill buildings, tailings piles, and areas contaminated by windblown and waterborne radioactive tailings materials. The total estimated volume of contaminated materials is approximately 621,300 cubic yards (yd{sup 3}). In addition to the contamination in the two processing site areas, four VPs were found to contain contamination. As a result of the tailings being exposed to the environment, contamination associated with the UC and NC sites has leached into shallow ground water. Surface water has not been affected. The closest residence is approximately 0.3 air mi from either site. The proposed action is to remediate the UC and NC sites by removing all contaminated materials within the designing site boundaries or otherwise associated with the sites, and relocating them to, and stabilizing them at, a location approximately 5 road mi northeast of the sites on land administered by the Bureau of Land Management (BLM).

  20. Contents of environmental assessments prepared for the Uranium Mill Tailings Remedial Action Project

    SciTech Connect (OSTI)

    Not Available

    1986-01-01

    This document presents two versions of the outline for the environmental assessments (EAS) to be prepared for the Uranium Mill Tailings Remedial Action (UMTRA) Project. The first displays the basic structure of the assessments; it lists only the titles of sections. The second is a guide to the contents of the assessments which provides, under each title, a brief summary of contents. The outline is intended to comply with the planning requirements (40 CFR Part 1501) and the definitions of terms (40-' CFR Part 1508) established by the Council on Environmental Quality as well as DOE order 5440.lB (Implementation of the National Environmental Policy Act), and compliance with Floodplain/Wetlands Environmental Review Requirements (10 CFR Part 1022). These requirements and definitions are implicitly part of the outline. The outline presented in this document will guide the preparation of EAs. The UMTRA Project EAs will be used in determining whether the DOE should prepare an environmental impact statement or a finding of no significant impact for the actions at each of the sites. If no impact statement is necessary, the environmental assessment for that site will aid the DOE in complying with the National Environmental Policy Act before beginning remedial actions. If an impact statement is needed, the assessment will aid its preparation. These purposes, established by the Council on Environmental Quality in 40 CFR Part 1508.9(a), have guided the construction of the outline presented in this document. Remedial actions at each site will include the cleanup of properties in the vicinity of the tailings sites that have been contaminated by the tailings.

  1. Contents of environmental assessments prepared for the Uranium Mill Tailings Remedial Action Project

    SciTech Connect (OSTI)

    Not Available

    1986-01-01

    This document presents two versions of the outline for the environmental assessments (EAS) to be prepared for the Uranium Mill Tailings Remedial Action (UMTRA) Project. The first displays the basic structure of the assessments; it lists only the titles of sections. The second is a guide to the contents of the assessments which provides, under each title, a brief summary of contents. The outline is intended to comply with the planning requirements (40 CFR Part 1501) and the definitions of terms (40-` CFR Part 1508) established by the Council on Environmental Quality as well as DOE order 5440.lB (Implementation of the National Environmental Policy Act), and compliance with Floodplain/Wetlands Environmental Review Requirements (10 CFR Part 1022). These requirements and definitions are implicitly part of the outline. The outline presented in this document will guide the preparation of EAs. The UMTRA Project EAs will be used in determining whether the DOE should prepare an environmental impact statement or a finding of no significant impact for the actions at each of the sites. If no impact statement is necessary, the environmental assessment for that site will aid the DOE in complying with the National Environmental Policy Act before beginning remedial actions. If an impact statement is needed, the assessment will aid its preparation. These purposes, established by the Council on Environmental Quality in 40 CFR Part 1508.9(a), have guided the construction of the outline presented in this document. Remedial actions at each site will include the cleanup of properties in the vicinity of the tailings sites that have been contaminated by the tailings.

  2. Baseline risk assessment of ground water contamination at the Uranium Mill Tailings Site near Maybell, Colorado

    SciTech Connect (OSTI)

    1995-09-01

    The US Department of Energy (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project consists of the Surface Project (Phase I) and the Ground Water Project (Phase II). Under the UMTRA Surface Project, tailings, radioactive contaminated soil, building foundations, and materials associated with the former processing of uranium ore at UMTRA sites are placed into disposal cells. The cells are designed to reduce radon and other radiation emissions and to prevent further contamination of ground water. One UMTRA Project site is near Maybell, Colorado. Surface cleanup at this site is under way and is scheduled for completion in 1996. The tailings are being stabilized in-place at this site. The disposal area has been withdrawn from public use by the DOE and is referred to as the permanent withdrawal area. The Ground Water Project evaluates the nature and extent of ground water contamination resulting from past uranium ore processing activities. The Ground Water Project at this site is in its beginning stages. This report is a site-specific document that will be used to evaluate current and future potential impacts to the public and the environment from exposure to contaminated ground water. The results of this evaluation and further site characterization will determine whether any action is needed to protect human health or the environment. Currently, no points of exposure (e.g. a drinking water well); and no receptors of contaminated ground water have been identified at the Maybell site. Therefore, there are no current human health and ecological risks associated with exposure to contaminated ground water. Furthermore, if current site conditions and land- and water-use patterns do not change, it is unlikely that contaminated ground water would reach people or the ecological communities in the future.

  3. Grand Junction, Colorado, Disposal Site Long-Term Surveillance and Maintenance Program Fact Sheet, July 2001

    Office of Legacy Management (LM)

    Grand Junction Disposal Site Uranium ore was processed at the Climax millsite at Grand Junction, Colorado, between 1951 and 1970. The milling operations created process-related waste and tailings, a sandlike material containing radioactive materials and other contaminants. The tailings were an ideal and inexpensive construction material suitable for concrete, mortar, and fill. Accordingly, the tailings were widely used in the Grand Junction area for these purposes. The U.S. Department of Energy

  4. Baseline risk assessment of ground water contamination at the Monument Valley Uranium Mill Tailings Site, Cane Valley, Arizona. Revision 1

    SciTech Connect (OSTI)

    Not Available

    1994-08-01

    This baseline risk assessment evaluates potential impact to public health or the environment from ground water contamination at the former uranium mill processing site in Cane Valley near Monument Valley, Arizona. The US Department of Energy (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project has relocated and stabilized this site`s tailings and other contaminated material in a disposal cell at Mexican Hat, Utah. The second phase of the UMTRA Project is to evaluate ground water contamination. This risk assessment is the first document specific to this site for the Ground Water Project that evaluates potential health and environmental risks. It will help determine the approach required to address contaminated ground water at the site.

  5. Environmental assessment of remedial action at the Maybell uranium mill tailings site near Maybell, Colorado: Revision 2

    SciTech Connect (OSTI)

    Not Available

    1994-11-01

    The purpose of this environmental assessment (EA) is to evaluate the environmental impacts resulting from remedial action at the Maybell uranium mill tailings site near Maybell, Colorado. A biological assessment and a floodplain/wetlands assessment are included as part of this EA. This report and attachments describe the proposed action, affected environment, and environmental impacts associated with the proposed remedial action, including impacts to threatened and endangered species listed or proposed for listing by the US Fish and Wildlife Service (FWS).

  6. Environmental assessment of remedial action at the Maybell Uranium Mill Tailings Site near Maybell, Colorado. Revision 1

    SciTech Connect (OSTI)

    Not Available

    1994-04-01

    The purpose of this environmental assessment (EA) is to evaluate the environmental impacts resulting from remedial action at the Maybell uranium mill tailings site near Maybell, Colorado. A biological assessment (Attachment 1) and a floodplain/wetlands attachments describe the proposed action, affected environment, and environmental impacts associated with the proposed remedial action, including impacts to threatened and endangered species listed or proposed for listing by the US Fish and Wildlife Service (FWS).

  7. Remedial action and site design for stabilization of the inactive uranium mill tailings sites at Slick Rock, Colorado. Attachment 2, Geology report

    SciTech Connect (OSTI)

    Not Available

    1993-07-01

    This report presents geologic considerations that are pertinent to the Remedial Action Plan for Slick Rock mill tailings. Topics covered include regional geology, site geology, geologic stability, and geologic suitability.

  8. Remedial action plan and site design for stabilization of the inactive uranium mill tailings sites at Rifle, Colorado. Volume 2, Appendices D and E: Final report

    SciTech Connect (OSTI)

    Not Available

    1992-02-01

    This appendix assesses the present conditions and data gathered about the two inactive uranium mill tailings sites near Rifle, Colorado, and the designated disposal site six miles north of Rifle in the area of Estes Gulch. It consolidates available engineering, radiological, geotechnical, hydrological, meteorological, and other information pertinent to the design of the Remedial Action Plan (RAP). The data characterize conditions at the mill, tailings, and disposal site so that the Remedial Action Contractor (RAC) may complete final designs for the remedial actions.

  9. DESIGN, PERFORMANCE, AND SUSTAINABILITY OF ENGINEERED COVERS FOR URANIUM MILL TAILINGS

    SciTech Connect (OSTI)

    Waugh, W. Jody

    2004-04-21

    Final remedies at most uranium mill tailings sites include engineered covers designed to contain metals and radionuclides in the subsurface for hundreds of years. Early cover designs rely on compacted soil layers to limit water infiltration and release of radon, but some of these covers inadvertently created habitats for deep-rooted plants. Root intrusion and soil development increased the saturated hydraulic conductivity several orders of magnitude above design targets. These covers may require high levels of maintenance to sustain long-term performance. Relatively low precipitation, high potential evapotranspiration, and thick unsaturated soils favor long-term hydrologic isolation of buried waste at arid and semiarid sites. Later covers were designed to mimic this natural soil-water balance with the goal of sustaining performance with little or no maintenance. For example, the cover for the Monticello, Utah, Superfund site relies on a thick soil-sponge layer overlying a sand-and-gravel capillary barrier to store precipitation while plants are dormant and on native vegetation to dry the soil sponge during the growing season. Measurements of both off-site caisson lysimeters and a large 3-ha lysimeter built into the final cover show that drainage has been well below a U.S. Environmental Protection Agency target of less than 3.0 mm/yr. Our stewardship strategy combines monitoring precursors to failure, probabilistic riskbased modeling, and characterization of natural analogs to project performance of covers for a range of possible future environmental scenarios. Natural analogs are needed to understand how ecological processes will influence cover performance, processes that cannot be predicted with short-term monitoring and existing numerical models.

  10. Biological assessment of remedial action at the abandoned uranium mill tailings site near Naturita, Colorado

    SciTech Connect (OSTI)

    1996-03-01

    Pursuant to the Uranium Mill Tailings Radiation Control Act (UMTRCA) of 1978, the U.S. Department of Energy (DOE) is proposing to conduct remedial action to clean up the residual radioactive materials (RRM) at the Naturita uranium processing site in Colorado. The Naturita site is in Montrose County, Colorado, and is approximately 2 miles (mi) (3 kilometer [km]) from the unincorporated town of Naturita. The proposed remedial action is to remove the RRM from the Naturita site to the Upper Burbank Quarry at the Uravan disposal site. To address the potential impacts of the remedial action on threatened and endangered species, the DOE prepared this biological assessment. Informal consultations with the U.S. Department of the Interior, Fish and Wildlife Service (FWS) were initiated in 1986, and the FWS provided a list of the threatened and endangered species that may occur in the Naturita study area. This list was updated by two FWS letters in 1988 and by verbal communication in 1990. A biological assessment was included in the environmental assessment (EA) of the proposed remedial action that was prepared in 1990. This EA addressed the impacts of moving the Naturita RRM to the Dry Flats disposal site. In 1993, the design for the Dry Flats disposal alternative was changed. The FWS was again consulted in 1993 and provided a new list of threatened and endangered species that may occur in the Naturita study area. The Naturita EA and the biological assessment were revised in response to these changes. In 1994, remedial action was delayed because an alternate disposal site was being considered. The DOE decided to move the FIRM at the Naturita site to the Upper Burbank Quarry at the Uravan site. Due to this delay, the FWS was consulted in 1995 and a list of threatened and endangered species was provided. This biological assessment is a revision of the assessment attached to the Naturita EA and addresses moving the Naturita RRM to the Upper Burbank Quarry disposal site.

  11. Environmental assessment of remedial action at the Gunnison Uranium Mill Tailings Site near Gunnison, Colorado. Final

    SciTech Connect (OSTI)

    Not Available

    1992-02-01

    The presence of contaminated uranium mill tailings adjacent to the city of Gunnison has been a local concern for many years. The following issues were identified during public meetings that were held by the DOE prior to distribution of an earlier version of this EA. Many of these issues will require mitigation. Groundwater contamination; in December 1989, a herd of 105 antelope were introduced in an area that includes the Landfill disposal site. There is concern that remedial action-related traffic in the area would result in antelope mortality. The proposed Tenderfoot Mountain haul road may restrict antelope access to their water supply; a second wildlife issue concerns the potential reduction in sage grouse use of breeding grounds (leks) and nesting habitat; the proposed Tenderfoot Mountain haul road would cross areas designated as wetlands by US Army Corps of Engineers (COE); the proposed disposal site is currently used for grazing by cattle six weeks a year in the spring. Additional concerns were stated in comments on a previous version of this EA. The proposed action is to consolidate and remove all contaminated materials associated with the Gunnison processing site to the Landfill disposal site six air miles east of Gunnison. All structures on the site (e.g., water tower, office buildings) were demolished in 1991. The debris is being stored on the site until it can be incorporated into the disposal cell at the disposal site. All contaminated materials would be trucked to the Landfill disposal site on a to-be-constructed haul road that crosses BLM-administered land.

  12. Grande

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    breaks ground on key sediment control project November 5, 2009 Structures will limit flow of sediments toward Rio Grande Los Alamos, New Mexico, November 5, 2009- Crews broke...

  13. Review and analysis of proposed EPA groundwater standards for the UMTRA Project. [Uranium Mill Tailings Remedial Action (UMTRA) Project

    SciTech Connect (OSTI)

    Not Available

    1987-10-01

    The Title I groundwater standards for inactive uranium mill tailings sites, which were promulgated on January 5, 1983, by the US Environmental Protection Agency (EPA) for the Uranium Mill Tailings Remedial Action (UMTRA) Project, were remanded to the EPA on September 3, 1985, by the US Tenth Circuit Court of Appeals. The Court instructed the EPA to compile general groundwater standards for all sites. On September 24, 1987, the EPA published proposed standards in response to the remand. This Summary Report includes an evaluation of the potential effects of the proposed EPA groundwater standards on the UMTRA Project as well as a discussion of the DOE's position on the proposed standards. This report is accompanied by a detailed Technical Report and Appendices which provide supporting information and analyses. This Summary Report results from a study undertaken to: determine the impact of the proposed standards on the UMTRA Project; and recommend provisions for the implementation of the final standards that will minimize adverse impact to the conduct of the UMTRA Project while ensuring protection of human health and the environment. Specifically, the following were considered: the flexibility of the proposed standards; interpretations of the proposed standards; the extent of aquifer restoration that may be required to implement the proposed standards at each site; the costs of aquifer restoration; and design changes necessary to meet the standards.

  14. EA-1155: Ground-water Compliance Activities at the Uranium Mill Tailings Site, Spook, Wyoming

    Broader source: Energy.gov [DOE]

    This EA evaluates the environmental impacts for the proposal to comply with the Environmental Protection Agency's ground-water standards set forth in 40 CFR 192 at the Spook, Wyoming Uranium Mill...

  15. Remedial Action Plan and site design for stabilization of the inactive uranium mill tailings site at Mexican Hat, Utah: Appendix D. Final report

    SciTech Connect (OSTI)

    1988-07-01

    This appendix is an assessment of the present conditions of the inactive uranium mill site near Mexican Hat, Utah. It consolidates available engineering, radiological, geotechnical, hydrological, meteorological, and other information pertinent to the design of the Remedial Action Plan. Plan is to characterize the conditions at the mill and tailings site so that the Remedial Action Contractor may complete final designs of the remedial action.

  16. Remedial action plan and site conceptual design for stabilization of the inactive uranium mill tailings sites at Rifle, Colorado. Appendix D, Final report

    SciTech Connect (OSTI)

    1992-02-01

    This appendix assesses the present conditions and data gathered about the two designated inactive uranium mill tailings sites near Rifle, Colorado, and the proposed disposal site six miles north of Rifle in the area of Estes Gulch. It consolidates available engineering, radiological, geotechnical, hydrological, meteorological, and other information pertinent to the design of the Remedial Action Plan (RAP). The data characterize conditions at the mill, tailings, and disposal site so that the Remedial Action Contractor (RAC) may complete final designs for the remedial actions.

  17. Grande

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    breaks ground on key sediment control project November 5, 2009 Structures will limit flow of sediments toward Rio Grande Los Alamos, New Mexico, November 5, 2009- Crews broke ground this week on one of two engineered structures in a Los Alamos National Laboratory environmental project to reduce the flow of sediments down two canyons toward the Rio Grande. Called "grade-control" structures, the approximately $2 million features are up to eight feet high and made of rocks packed tightly

  18. 2013 Annual Site Inspection and Monitoring Report for Uranium Mill Tailings Radiation Control Act Title II Disposal Sites

    SciTech Connect (OSTI)

    2013-11-01

    This report, in fulfillment of a license requirement, presents the results of long-term surveillance and maintenance activities conducted by the U.S. Department of Energy (DOE) Office of Legacy Management in 2013 at six uranium mill tailings disposal sites reclaimed under Title II of the Uranium Mill Tailings Radiation Control Act (UMTRCA) of 1978. These activities verified that the UMTRCA Title II disposal sites remain in compliance with license requirements. DOE manages six UMTRCA Title II disposal sites under a general license granted by the U.S. Nuclear Regulatory Commission (NRC) established at Title 10 Code of Federal Regulations Part 40.28. Reclamation and site transition activities continue at other sites, and DOE ultimately expects to manage approximately 27 Title II disposal sites. Long-term surveillance and maintenance activities and services for these disposal sites include inspecting and maintaining the sites; monitoring environmental media and institutional controls; conducting any necessary corrective action; and performing administrative, records, stakeholder services, and other regulatory functions. Annual site inspections and monitoring are conducted in accordance with site-specific long-term surveillance plans (LTSPs) and procedures established by DOE to comply with license requirements. Each site inspection is performed to verify the integrity of visible features at the site; to identify changes or new conditions that may affect the long-term performance of the site; and to determine the need, if any, for maintenance, follow-up inspections, or corrective action. LTSPs and site compliance reports are available online at http://www.lm.doe.gov

  19. Baseline risk assessment of ground water contamination at the uranium mill tailings sites near Rifle, Colorado. Revision 1

    SciTech Connect (OSTI)

    1995-08-01

    The US Department of Energy (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project consists of the Surface Project (Phase 1) and the Ground Water Project (Phase 2). Under the UMTRA Surface Project, tailings, radioactive contaminated soil, equipment, and materials associated with the former uranium ore processing sites are placed into disposal cells. The cells are designed to reduce radon and other radiation emissions and to prevent further ground water contamination. The Ground Water Project evaluates the nature and extent of ground water contamination resulting from the uranium ore processing activities. Two UMTRA Project sites are near Rifle, Colorado: the Old Rifle site and the New Rifle site. Surface cleanup at the two sites is under way and is scheduled for completion in 1996. The Ground Water Project is in its beginning stages. A risk assessment identifies a source of contamination, how that contamination reaches people and the environment, the amount of contamination to which people or the environment may be exposed, and the health or environmental effects that could result from that exposure. This report is a site-specific document that will be used to evaluate current and future impacts to the public and the environment from exposure to contaminated ground water. This evaluation and further site characterization will be used to determine if action is needed to protect human health or the environment.

  20. Remedial Action Plan and Site Design for Stabilization of the Inactive Uranium Mill Tailings Site, Maybell, Colorado. Remedial action selection report: Attachment 2, Geology report, Final

    SciTech Connect (OSTI)

    Not Available

    1994-06-01

    The Maybell uranium mill tailings site is 25 miles (mi) (40 kilometers [km]) west of the town of Craig, Colorado, in Moffat County, in the northwestern part of the state. The unincorporated town of Maybell is 5 road mi (8 km) southwest of the site. The designated site covers approximately 110 acres (ac) (45 hectares [ha]) and consists of a concave-shaped tailings pile and rubble from the demolition of the mill buildings buried in the former mill area. Contaminated materials at the Maybell processing site include the tailings pile, which has an average depth of 20 feet (ft) (6 meters [m]) and contains 2.8 million cubic yards (yd{sup 3}) (2.1 million cubic meters [m{sup 3}]) of tailings. The former mill processing area is on the north side of the site and contains 20,000 yd{sup 3} (15,000 m{sup 3}) of contaminated demolition debris. Off-pile contamination is present and includes areas adjacent to the tailings pile, as well as contamination dispersed by wind and surface water flow. The volume of off-pile contamination to be placed in the disposal cell is 550,000 yd{sup 3} (420,000 m{sup 3}). The total volume of contaminated materials to be disposed of as part of the remedial action is estimated to be 3.37 million yd{sup 3} (2.58 million m{sup 3}). Information presented in this Final Remedial Action Plan (RAP) and referenced in supporting documents represents the current disposal cell design features and ground water compliance strategy proposed by the US Department of Energy (DOE) for the Maybell, Colorado, tailings site. Both the disposal cell design and the ground water compliance strategy have changed from those proposed prior to the preliminary final RAP document as a result of prudent site-specific technical evaluations.

  1. Environmental Assessment of Remedial Action at the Riverton Uranium Mill Tailings Site, Riverton, Wyoming

    SciTech Connect (OSTI)

    1987-06-01

    The US Department of Energy (DOE) has prepared an environmental assessment (DOE/EA-0254) on the proposed remedial action at the inactive uranium milling site near Riverton, Wyoming. Based on the analyses in the EA, the DOE has determined that the proposed action does not constitute a major Federal action significantly affecting the quality of the human environment within the meaning of the National Environmental Policy Act (NEPA) of 1969 (42 U.S.C. 4321, et seq.). Therefore, the preparation of an environmental impact statement (EIS) is not required.

  2. U.S. Department of Energy at Grand Junction 2003 Annual Inspection⎯Monticello, Utah

    Office of Legacy Management (LM)

    at Grand Junction 2003 Annual Inspection⎯Monticello, Utah November 2003 Page 1 2003 Annual Inspection of the Monticello Mill Tailings (USDOE) and Monticello Radioactively Contaminated Properties Sites Summary The Monticello site, which includes the U.S. Department of Energy (DOE) Monticello Mill Tailings Site (MMTS) and the Monticello Radioactively Contaminated Properties site, was inspected September 23-25, 2003. A follow-up inspection of the Soil and Sediment properties was conducted on

  3. Baseline risk assessment of ground water contamination at the Monument Valley uranium mill tailings site Cane Valley, Arizona

    SciTech Connect (OSTI)

    1996-03-01

    The U.S. Department of Energy (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project consists of the Surface Project (Phase I) and the Ground Water Project (Phase II). Under the UMTRA Surface Project, tailings, radioactive contaminated soil, equipment, and materials associated with the former uranium ore processing at UMTRA Project sites are placed into disposal cells. The cells are designed to reduce radon and other radiation emissions and to minimize further contamination of ground water. Surface cleanup at the Monument Valley UMTRA Project site near Cane Valley, Arizona, was completed in 1994. The Ground Water Project evaluates the nature and extent of ground water contamination that resulted from the uranium ore processing activities. The Ground Water Project is in its beginning stages. Human health may be at risk from exposure to ground water contaminated by uranium ore processing. Exposure could occur by drinking water pumped out of a hypothetical well drilled in the contaminated areas. Adverse ecological and agricultural effects may also result from exposure to contaminated ground water. For example, livestock should not be watered with contaminated ground water. A risk assessment describes a source of contamination, how that contamination reaches people and the environment, the amount of contamination to which people or the ecological environment may be exposed, and the health or ecological effects that could result from that exposure. This risk assessment is a site-specific document that will be used to evaluate current and potential future impacts to the public and the environment from exposure to contaminated ground water. The results of this evaluation and further site investigations will be used to determine a compliance strategy to comply with the UMTRA ground water standards.

  4. Baseline risk assessment of ground water contamination at the Uranium Mill Tailings Sites near Rifle, Colorado. Revision 2

    SciTech Connect (OSTI)

    1996-02-01

    The U.S. Department of Energy (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project consists of the Surface Project (Phase I) and the Ground Water Project (Phase II). Under the UMTRA Surface Project, tailings, radioactive contaminated soil, equipment, and materials associated with the former uranium ore processing sites are placed into disposal cells. The cells are designed to reduce radon and other radiation emissions and to prevent further ground water contamination. The Ground Water Project evaluates the nature and extent of ground water contamination resulting from the uranium ore processing activities. Two UMTRA Project sites are near Rifle, Colorado: the Old Rifle site and the New Rifle site. Surface cleanup at the two sites is under way and is scheduled for completion in 1996. The Ground Water Project is in its beginning stages. A risk assessment identifies a source of contamination, how that contamination reaches people and the environment, the amount of contamination to which people or the environment may be exposed, and the health or environmental effects that could result from that exposure. This report is a site-specific document that will be used to evaluate current and future impacts to the public and the environment from exposure to contaminated ground water. This evaluation and further site characterization will be used to determine if action is needed to protect human health or the environment. Human health risk may result from exposure to ground water contaminated from uranium ore processing. Exposure could occur from drinking water obtained from a well placed in the areas of contamination. Furthermore, environmental risk may result from plant or animal exposure to surface water and sediment that have received contaminated ground water.

  5. Economic impact study of the Uranium Mill Tailings Remedial Action project in Colorado: Colorado state fiscal year 1995. Revision 1

    SciTech Connect (OSTI)

    1995-12-01

    As required by the Romer-Twining Agreement of 1990, the US Department of Energy (DOE) has prepared this annual economic impact study for the state of Colorado. This report assesses the economic impacts related to the DOE Uranium Mill Tailings Remedial Action (UMTRA) Project in Colorado during the state fiscal year (FY) between 1 July 1994 and 30 June 1995. To estimate net economic benefit, employment, salaries and wages, and other related economic benefits are discussed, quantified, and then compared to the state`s 10 percent share of the remedial action costs. Actual data obtained from sites currently undergoing remedial action were used as the basis for analyses. If data were not available, estimates were used to derive economic indicators. This study describes the types of employment associated with the UMTRA Project and estimates of the numbers of people employed by UMTRA Project subcontractors in Colorado during state FY 1995. Employment totals are reported in estimated average annual jobs; however, the actual number of workers at the site fluctuates depending on weather and on the status of remedial action activities. In addition, the actual number of people employed on the Project during the year may be higher than the average annual employment reported due to the temporary nature of some of the jobs.

  6. Process for Transition of Uranium Mill Tailings Radiation Control Act Title II Disposal Sites to the U.S. Department of Energy Office of Legacy Management for Long-Term Surveillance and Maintenance

    SciTech Connect (OSTI)

    2012-03-01

    This document presents guidance for implementing the process that the U.S. Department of Energy (DOE) Office of Legacy Management (LM) will use for assuming perpetual responsibility for a closed uranium mill tailings site. The transition process specifically addresses sites regulated under Title II of the Uranium Mill Tailings Radiation Control Act (UMTRCA) but is applicable in principle to the transition of sites under other regulatory structures, such as the Formerly Utilized Sites Remedial Action Program.

  7. Baseline risk assessment of ground water contamination at the Uranium Mill Tailings Site near Naturita, Colorado. Revision 1

    SciTech Connect (OSTI)

    1995-11-01

    The Uranium Mill Tailings Remedial Action (UMTRA) Project consists of the Surface Project, and the Ground Water Project. For the UMTRA Project site located near Naturita, Colorado, phase I involves the removal of radioactively contaminated soils and materials and their transportation to a disposal site at Union Carbide Corporation`s Upper Burbank Repository at Uravan, Colorado. The surface cleanup will reduce radon and other radiation emissions from the former uranium processing site and prevent further site-related contamination of ground water. Phase II of the project will evaluate the nature and extent of ground water contamination resulting from uranium processing and its effect on human health and the environment, and will determine site-specific ground water compliance strategies in accordance with the US Environmental Protection Agency (EPA) ground water standards established for the UMTRA Project. Human health risks could occur from drinking water pumped from a hypothetical well drilled in the contaminated ground water area. Environmental risks may result if plants or animals are exposed to contaminated ground water or surface water that has mixed with contaminated ground water. Therefore, a risk assessment was conducted for the Naturita site. This risk assessment report is the first site-specific document prepared for the Ground Water Project at the Naturita site. What follows is an evaluation of current and possible future impacts to the public and the environment from exposure to contaminated ground water. The results of this evaluation and further site characterization will be used to determine whether any action is needed to protect human health or the environment.

  8. Status of activities on the inactive uranium mill tailings sites remedial action program. Office of the Assistant Secretary for Environment

    SciTech Connect (OSTI)

    Not Available

    1981-04-01

    This report on the status of the Office of Environment's program for inactive uranium mill tailings sites is an analysis of the current status and a forecast of future activities of the Office of Environment. The termination date for receipt of information was September 30, 1980. Aerial radiological surveys and detailed ground radiological assessments of properties within the communities in the vicinity of the designated processing sites in Canonsburg, Pennsylvania, Salt Lake City, Utah, and Boise, Idaho led to the designation of an initial group of vicinity properties for remedial action. The potential health effects of the residual radioactive materials on or near these properties were estimated, and the Assistant Secretary for Environment recommended priorities for performing remedial action to the Department's Assistant Secretary for Nuclear Energy. In designating these properties and establishing recommended priorities for performing remedial action, the Office of Environment consulted with the Environmental Protection Agency, the Nuclear Regulatory Commission, representatives from the affected State and local governments, and individual property owners. After notifying the Governors of each of the affected States and the Navajo Nation of the Secretary of Energy's designation of processing sites within their areas of jurisdiction and establishment of remedial action priorities, a Sample Cooperative Agreement was developed by the Department in consultation with the Nuclear Regulatory Commission and provided to the affected States and the Navajo Nation for comments. During September 1980, a Cooperative Agreement with the Commonwealth of Pennsylvania for the designated Canonsburg processing site was executed by the Department. It is anticipated that a Cooperative Agreement between the State of Utah and the Department to perform remedial actions at the designated Salt Lake City site will be executed in the near future.

  9. Remedial actions at the former Climax Uranium Company, Uranium Mill site, Grand Junction, Mesa County, Colorado. Volume 1, Text: Final environmental impact statement

    SciTech Connect (OSTI)

    1986-12-01

    This statement evaluates and compares the environmental impacts associated with the remedial actions of the residual radioactive materials remaining at the inactive uranium processing site and associated vicinity properties at Grand Junction, Mesa County, Colorado. This statement is also intended to aid the BLM in amending their management framework plans and final resource management plan, as well as assisting in compliance with the withdrawal application as appropriate. The site is a 114-acre tract of private and state owned land which contains approximately 3.1 million cubic yards of tailings and associated contaminated soils. The vicinity properties are homes, businesses, public buildings, and vacant lots which may have been contaminated during construction by the use of tailings as building material. An estimated 3465 vicinity properties would be cleaned up during remedial action of the tailings pile. The tailings were produced by the former Climax Uranium Company which processed uranium ore, which it sold to the US Atomic Energy Commission from 1951 to 1966 and to private sources from 1966 to 1970. This statement evaluates six alternatives for stabilization and disposal of the tailings and other contaminated materials: (1) No action. (2) Stabilization at the Grand Junction site. (3) Disposal at the Cheney Reservoir site with truck transport. (4) Disposal at the Cheney Reservoir site with train and truck transport. (5) Disposal at the Two Road site with truck transport. (6) Disposal at the Two Road site with train and truck transport. All of the alternatives except no action include remedial action at an estimated 3465 vicinity properties. Alternative 3 is DOE`s preferred alternative.

  10. EIS-0126: Remedial Actions at the Former Climax Uranium Company Uranium Mill Site, Grand Junction, Mesa County, Colorado

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy developed this EIS to assess the environmental impacts of remediating the residual radioactive materials left from the inactive uranium processing site and associated properties located in Grand Junction, Colorado.

  11. Remedial Action Plan and site design for stabilization of the inactive uranium mill tailings site at Mexican Hat, Utah: Appendix E. Final report

    SciTech Connect (OSTI)

    1988-07-01

    This document provides Appendix E of the Remedial Action Plan (RAP) presented in 1988 for the stabilization of the inactive uranium mill tailings at the Mexican Hat, Utah site. The RAP was developed to serve a two- fold purpose. It presents the activities proposed by the Department of Energy (DOE) to accomplish long-term stabilization and control of the residual radioactive materials (RRM) from Monument Valley, Arizona, and Mexican Hat, Utah, at the Mexican Hat disposal site. It also serves to document the concurrence of both the Navajo Nation and the Nuclear Regulatory Commission (NRC) in the remedial action. This agreement, upon execution by the DOE and the Navajo Nation and concurrence by the NRC, becomes Appendix B of the Cooperative Agreement. The RAP has been structured to provide a comprehensive understanding of the remedial action proposed for the Monument Valley and Mexican Hat sites. It includes specific design and construction requirements for the remedial action.

  12. Environmental Audit of the Grand Junction Projects Office

    SciTech Connect (OSTI)

    Not Available

    1991-08-01

    The Grand Junction Projects Office (GJPO) is located in Mesa County, Colorado, immediately south and west of the Grand Junction city limits. The US Atomic Energy Commission (AEC) established the Colorado Raw Materials Office at the present-day Grand Junction Projects Office in 1947, to aid in the development of a viable domestic uranium industry. Activities at the site included sampling uranium concentrate; pilot-plant milling research, including testing and processing of uranium ores; and operation of a uranium mill pilot plant from 1954 to 1958. The last shipment of uranium concentrate was sent from GJPO in January, 1975. Since that time the site has been utilized to support various DOE programs, such as the former National Uranium Resource Evaluation (NURE) Program, the Uranium Mill Tailings Remedial Action Project (UMTRAP), the Surplus Facilities Management Program (SFMP), and the Technical Measurements Center (TMC). All known contamination at GJPO is believed to be the result of the past uranium milling, analyses, and storage activities. Hazards associated with the wastes impounded at GJPO include surface and ground-water contamination and potential radon and gamma-radiation exposure. This report documents the results of the Baseline Environmental Audit conducted at Grand Junction Projects Office (GJPO) located in Grand Junction, Colorado. The Grand Junction Baseline Environmental Audit was conducted from May 28 to June 12, 1991, by the Office of Environmental Audit (EH-24). This Audit evaluated environmental programs and activities at GJPO, as well as GJPO activities at the State-Owned Temporary Repository. 4 figs., 12 tabs.

  13. Moab Project Continues Progress on Tailings Removal with Contract

    Energy Savers [EERE]

    Transition | Department of Energy Progress on Tailings Removal with Contract Transition Moab Project Continues Progress on Tailings Removal with Contract Transition December 27, 2012 - 12:00pm Addthis Laborers place a disposable liner in a tailings container. Laborers place a disposable liner in a tailings container. MOAB, Utah - The Moab mill tailings removal project in Utah ended the year having shipped more than 35 percent of the total 16 million tons of uranium mill tailings off-site.

  14. Remedial Action Plan and Site design for stabilization of the inactive Uranium Mill Tailings sites at Slick Rock, Colorado: Revision 1. Remedial action selection report, Attachment 2, geology report, Attachment 3, ground water hydrology report, Attachment 4, water resources protection strategy. Final

    SciTech Connect (OSTI)

    1995-09-01

    The Slick Rock uranium mill tailings sites are located near the small community of Slick Rock, in San Miguel County, Colorado. There are two designated Uranium Mill Tailings Remedial Action (UMTRA) Project sites at Slick Rock: the Union Carbide site and the North Continent site. Both sites are adjacent to the Dolores River. The sites contain former mill building concrete foundations, tailings piles, demolition debris, and areas contaminated by windblown and waterborne radioactive materials. The total estimated volume of contaminated materials is approximately 621,000 cubic yards (475,000 cubic meters). In addition to the contamination at the two processing site areas, 13 vicinity properties were contaminated. Contamination associated with the UC and NC sites has leached into ground water. Pursuant to the requirements of the Uranium Mill Tailings Radiation Control Act (UMTRCA) (42 USC {section}7901 et seq.), the proposed remedial action plan (RAP) will satisfy the final US Environmental Protection Agency (EPA) standards in 40 CFR Part 192 (60 FR 2854) for cleanup, stabilization, and control of the residual radioactive material (RRM) (tailings and other contaminated materials) at the disposal site at Burro Canyon. The requirements for control of the RRM (Subpart A) will be satisfied by the construction of an engineered disposal cell. The proposed remedial action will consist of relocating the uranium mill tailings, contaminated vicinity property materials, demolition debris, and windblown/weaterborne materials to a permanent repository at the Burro Canyon disposal site. The site is approximately 5 road mi (8 km) northeast of the mill sites on land recently transferred to the DOE by the Bureau of Land Management.

  15. Remedial action and site design for stabilization of the inactive uranium mill tailings sites at Slick Rock, Colorado. Attachment 2, Geology report: Appendix B, Preliminary final

    SciTech Connect (OSTI)

    Not Available

    1994-03-01

    Detailed investigations of geologic, geomorphic, and seismic conditions at the Burro Canyon site were conducted by the US Department of Energy (DOE) as a disposal site for the tailings at two processing sites near the Slick Rock, Colorado, post office. The purposes of these studies are basic site characterization and identification of potential geologic hazards that could affect long-term site stability. Subsequent engineering studies (e.g., analyses of hydrologic and liquefaction hazards) used the data developed in these studies. The geomorphic analysis was employed in the design of effective erosion protection. Studies of the regional and local seismotectonic setting, which included a detailed search for possible capable faults within a 65-km radius of the site, provided the basis for seismic design parameters.

  16. Rio Grande

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Rio Grande Rio Grande In New Mexico, the Rio Grande flows from one sediment-filled basin to another, cutting canyons between the basins and supporting a fragile ecosystem on its...

  17. Remedial action plan and site design for stabilization of the inactive Uranium Mill Tailing site Maybell, Colorado. Attachment 3, ground water hydrology report, Attachment 4, water resources protection strategy. Final report

    SciTech Connect (OSTI)

    Not Available

    1994-06-01

    The U.S. Environmental Protection Agency (EPA) has established health and environmental regulations to correct and prevent ground water contamination resulting from former uranium processing activities at inactive uranium processing sites (40 CFR Part 192 (1993)) (52 FR 36000 (1978)). According to the Uranium Mill Tailings Radiation Control Act (UMTRCA) of 1978 (42 USC {section} 7901 et seq.), the U.S. Department of Energy (DOE) is responsible for assessing the inactive uranium processing sites. The DOE has decided that each assessment will include information on hydrogeologic site characterization. The water resources protection strategy that describes the proposed action compliance with the EPA ground water protection standards is presented in Attachment 4, Water Resources Protection Strategy. Site characterization activities discussed in this section include the following: (1) Definition of the hydrogeologic characteristics of the environment, including hydrostratigraphy, aquifer parameters, areas of aquifer recharge and discharge, potentiometric surfaces, and ground water velocities. (2) Definition of background ground water quality and comparison with proposed EPA ground water protection standards. (3) Evaluation of the physical and chemical characteristics of the contaminant source and/or residual radioactive materials. (4) Definition of existing ground water contamination by comparison with the EPA ground water protection standards. (5) Description of the geochemical processes that affect the migration of the source contaminants at the processing site. (6) Description of water resource use, including availability, current and future use and value, and alternate water supplies.

  18. Grand Challenges

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Grand Challenges Grand Challenges Our goals to live a sustainable future LANL stakeholders TA-21 cleanup activities water on LANL land Collaborate with our stakeholders and tribal...

  19. Supplemental Modeling and Analysis Report, Atlas Corporation Moab Mill, Moab, Utah

    SciTech Connect (OSTI)

    Easterly, CE

    2001-11-05

    The purpose of this report is to provide additional numerical modeling and data evaluation for the Atlas tailings pile near Moab, Utah. A previous report (Tailings Pile Seepage Model: The Atlas Corporation Moab Mill, Moab, Utah, January 9, 1998) prepared for the Nuclear Regulatory Commission (NRC) by Oak Ridge National Laboratory/Grand Junction (ORNL/GJ) presented the results of steady-state modeling of water flow and subsequent discharge to the underlying groundwater system. At the request of the Fish and Wildlife Service (FWS), this model was expanded to evaluate the impact of drainage from the tailings pile in addition to recharge from precipitation in a transient mode simulation. In addition, the FWS requested transient simulations of contaminant transport in the alluvial aquifer. Subsequently, NRC requested an evaluation of additional hydrologic issues related to the results presented in the Tailings Pile Seepage Model (ORNL/GJ 1998a) and the Limited Groundwater Investigation (ORNL/GJ 1998b). Funding for the report was provided by the U.S. Department of Energy. The following section lists the individual tasks with subsequent sections providing the results. A map for the Atlas Moab Mill site is presented in Fig. 1.1.

  20. DOE Signs Decision to Move Moab Tailings | Department of Energy

    Energy Savers [EERE]

    Decision to Move Moab Tailings DOE Signs Decision to Move Moab Tailings September 14, 2005 - 10:23am Addthis WASHINGTON, DC - U.S. Secretary of Energy Samuel W. Bodman today announced that a Record of Decision (ROD) clearing the way for the removal of 11.9 million tons of radioactive Uranium Mill Tailings from the banks the Colorado River in Utah has been signed. Under the Moab Uranium Mill Tailings Remedial Action Project Site Record of Decision, the tailings will be moved, predominately by

  1. Rio Grande

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Rio Grande Rio Grande In New Mexico, the Rio Grande flows from one sediment-filled basin to another, cutting canyons between the basins and supporting a fragile ecosystem on its flood plain. August 1, 2013 river bank Banks of the Rio Grande Groundwater at LANL discharges to springs along the Rio Grande. Stream flow resulting from heavy storms and snowmelt also has the potential to reach the Rio Grande. RELATED IMAGES http://farm3.staticflickr.com/2818/9628464665_3a972e1387_t.jpg Enlarge

  2. DOE - Office of Legacy Management -- Monticello Mill Site - UT 03

    Office of Legacy Management (LM)

    Mill Site - UT 03 FUSRAP Considered Sites Site: Monticello Mill Site (UT.03) Designated Name: Alternate Name: Location: Evaluation Year: Site Operations: Site Disposition: Radioactive Materials Handled: Primary Radioactive Materials Handled: Radiological Survey(s): Site Status: Also see Monticello, Utah, Disposal and Processing Sites Documents Related to Monticello Mill Site Monticello Mill Tailings Site Operable Unit III Interim Remedial Action Progress Report July 1999-July 2000.

  3. DOE - Office of Legacy Management -- Edgemont Mill Site - SD 01

    Office of Legacy Management (LM)

    Edgemont Mill Site - SD 01 FUSRAP Considered Sites Site: Edgemont Mill Site (SD.01) Designated Name: Alternate Name: Location: Evaluation Year: Site Operations: Site Disposition: Radioactive Materials Handled: Primary Radioactive Materials Handled: Radiological Survey(s): Site Status: Also see Edgemont, South Dakota, Disposal Site Documents Related to Edgemont Mill Site 2014 Annual Site Inspection and Monitoring Report for Uranium Mill Tailings Radiation Control Act Title II Disposal

  4. Moab Reaches 40-Percent Mark in Tailings Removal

    Broader source: Energy.gov [DOE]

    MOAB, Utah – The Moab Uranium Mill Tailings Remedial Action Project had a productive year, despite continued budget constraints and a first-ever, three-month curtailment of shipping operations last winter.

  5. Grand Challenges

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Grand Challenges Grand Challenges Our goals to live a sustainable future LANL stakeholders TA-21 cleanup activities water on LANL land Collaborate with our stakeholders and tribal governments to ensure that LANL's impact on the environment is as low as reasonably achievable Remove or stabilize pollutants from the Manhattan Project and Cold War eras Protect water resource quality and reduce water use Stormwater drainage at LANL LANL land waste workers at LANL Eliminate industrial emissions,

  6. DOE - Office of Legacy Management -- Ambrosia Lake Mill Site - NM 0-01

    Office of Legacy Management (LM)

    Ambrosia Lake Mill Site - NM 0-01 FUSRAP Considered Sites Site: Ambrosia Lake Mill Site (NM.0-01) Designated Name: Alternate Name: Location: Evaluation Year: Site Operations: Site Disposition: Radioactive Materials Handled: Primary Radioactive Materials Handled: Radiological Survey(s): Site Status: Also see Ambrosia Lake Mill Site Documents Related to Ambrosia Lake Mill Site 2014 Annual Site Inspection and Monitoring Report for Uranium Mill Tailings Radiation Control Act Title I Disposal

  7. Remedial action plan and site design for stabilization of the inactive uranium mill tailings site at Falls City, Texas. Remedial action selection report, attachment 2, geology report; attachment 3, groundwater hydrology report; and attachment 4, water resources protection strategy. Final report

    SciTech Connect (OSTI)

    1992-09-01

    The uranium processing site near Falls City, Texas, was one of 24 inactive uranium mill sites designated to be remediated by the U.S. Department of Energy (DOE) under Title I of the Uranium Mill Tailings Radiation Control Act of 1978 (UMTRCA). The UMTRCA requires that the U.S. Nuclear Regulatory Commission (NRC) concur with the DOE`s remedial action plan (RAP) and certify that the remedial action conducted at the site complies with the standards promulgated by the U.S. Environmental Protection Agency (EPA). The RAP, which includes this summary remedial action selection report (RAS), serves a two-fold purpose. First, it describes the activities proposed by the DOE to accomplish long-term stabilization and control of the residual radioactive materials at the inactive uranium processing site near Falls City, Texas. Second, this document and the remainder of the RAP, upon concurrence and execution by the DOE, the State of Texas, and the NRC, becomes Appendix B of the Cooperative Agreement between the DOE and the State of Texas.

  8. EA-1406-FEA-2003.pdf

    Office of Environmental Management (EM)

    Mill Tailings Remedial Action (Project) UMTRCA Uranium Mill Tailings Radiation Control Act EA of Ground Water Compliance at the New Rifle Site DOE Grand Junction Office Page viii...

  9. DOE - Office of Legacy Management -- Gunnison Mill Site - CO 0-06

    Office of Legacy Management (LM)

    Gunnison Mill Site - CO 0-06 FUSRAP Considered Sites Site: Gunnison Mill Site (CO.0-06 ) Designated Name: Alternate Name: Location: Evaluation Year: Site Operations: Site Disposition: Radioactive Materials Handled: Primary Radioactive Materials Handled: Radiological Survey(s): Site Status: Also see Gunnison, Colorado, Processing Site Documents Related to Gunnison Mill Site Baseline Risk Assessment of Groundwater Contamination at the Uranium Mill Tailings Site Near Gunnison, Colorado.

  10. DOE - Office of Legacy Management -- Maybell Mill Site - CO 0-07

    Office of Legacy Management (LM)

    Maybell Mill Site - CO 0-07 FUSRAP Considered Sites Site: Maybell Mill Site (CO.0-07) Designated Name: Alternate Name: Location: Evaluation Year: Site Operations: Site Disposition: Radioactive Materials Handled: Primary Radioactive Materials Handled: Radiological Survey(s): Site Status: Also see Maybell, Colorado, Disposal Site Documents Related to Maybell Mill Site 2014 Annual Site Inspection and Monitoring Report for Uranium Mill Tailings Radiation Control Act Title I Disposal Sites-Maybell,

  11. DOE - Office of Legacy Management -- Mexican Hat Mill Site - UT 0-02A

    Office of Legacy Management (LM)

    Mill Site - UT 0-02A FUSRAP Considered Sites Site: Mexican Hat Mill Site (UT.0-02A) Designated Name: Alternate Name: Location: Evaluation Year: Site Operations: Site Disposition: Radioactive Materials Handled: Primary Radioactive Materials Handled: Radiological Survey(s): Site Status: Also see Mexican Hat, Utah, Disposal Site Documents Related to Mexican Hat Mill Site 2014 Annual Site Inspection and Monitoring Report for Uranium Mill Tailings Radiation Control Act Title I Disposal Sites-Mexican

  12. DOE - Office of Legacy Management -- Slick Rock Mill Site - CO 08

    Office of Legacy Management (LM)

    Slick Rock Mill Site - CO 08 FUSRAP Considered Sites Site: Slick Rock Mill Site (CO.08) Designated Name: Alternate Name: Location: Evaluation Year: Site Operations: Site Disposition: Radioactive Materials Handled: Primary Radioactive Materials Handled: Radiological Survey(s): Site Status: Also see Slick Rock, Colorado, Processing Site Documents Related to Slick Rock Mill Site 2014 Annual Site Inspection and Monitoring Report for Uranium Mill Tailings Radiation Control Act Title I Disposal

  13. DOE - Office of Legacy Management -- Tuba City Mill Site - AZ 0-02

    Office of Legacy Management (LM)

    Mill Site - AZ 0-02 FUSRAP Considered Sites Site: Tuba City Mill Site (AZ.0-02 ) Designated Name: Alternate Name: Location: Evaluation Year: Site Operations: Site Disposition: Radioactive Materials Handled: Primary Radioactive Materials Handled: Radiological Survey(s): Site Status: Also see Tuba City, Arizona, Disposal Site Documents Related to Tuba City Mill Site 2014 Navajo Nation Five-Year Plan 2014 Annual Site Inspection and Monitoring Report for Uranium Mill Tailings Radiation Control Act

  14. DOE - Office of Legacy Management -- Durango Mill Site - CO 0-05

    Office of Legacy Management (LM)

    Durango Mill Site - CO 0-05 FUSRAP Considered Sites Site: Durango Mill Site (CO.0-05 ) Designated Name: Alternate Name: Location: Evaluation Year: Site Operations: Site Disposition: Radioactive Materials Handled: Primary Radioactive Materials Handled: Radiological Survey(s): Site Status: Also see Durango, Colorado, Processing Site Documents Related to Durango Mill Site 2005 Annual Site Inspection and Monitoring Report for Uranium Mill Tailings Radiation Control Act Title I Disposal

  15. Ionfab Mill

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Oxford Ionfab System 300+ Ion Mill For questions concerning this machines capabilities, please contact Varshni Singh, at 578-0248. ionfab.jpg (60579 bytes) Removal of metallic patterns from a surface can be performed evenly with this inert gas ion beam system, which uses a projected Ar ion beam to sputter etch the surface of a six inch wafer at the users choice of angle and rotation speed. The Ionfab 300+ can allow researchers to investigate thin film structures with vertical or angled side

  16. White Tail | Open Energy Information

    Open Energy Info (EERE)

    Tail Jump to: navigation, search Name White Tail Facility White Tail Sector Wind energy Facility Type Commercial Scale Wind Facility Status In Service Owner Exelon Wind Developer...

  17. EIS-0198: Uranium Mill Tailings Remedial Action Groundwater Project

    Broader source: Energy.gov [DOE]

    This EIS assesses the potential programmatic impacts of conducting the Ground Water Project, provides a method for determining the site-specific ground water compliance strategies, and provides...

  18. Uranium Mill Tailings Remedial Action Program. Annual status report

    SciTech Connect (OSTI)

    Not Available

    1980-12-01

    The purpose, scope, history, requirements, and management organization of the UMTRA Program are summarized in the Introduction. The remainder of the report describes progress made during the past year (F 1980) and discusses future plants and activities. Early emphasis has been on the four highest-priority sites because of their proximity to population centers. These sites are: (1) Canonsburg, Pennsylvania; (2) Salt Lake City, Utah; (3) Durango, Colorado; and (4) Shiprock, New Mexico (Navajo Reservation). To date, twenty-five vicinity properties near the Canonsburg site and two such properties near the Salt Lake City site have been designated for remedial action. A research effort was undertaken at a major vicinity property, the Mountain States Supply Company in Salt Lake City, to study the effects of heating-and-ventilating-system modification on indoor radon-daughter concentrations. A cooperative agreement was executed between DOE and the Commonwealth of Pennsylvania. A similar agreement with the State of Utah is expected to be executed in early FY 1981. Further, it is expected that additional cooperative agreements will be negotiated during FY 1981 with the States of Colorado and Wyoming and the Navajo Nation. It is expected that the processing site at Canonsburg, PA (the Canonsburg Industrial Park) will be acquired during FY 1981. Draft Environmental Impact Statements for the four highest-priority sites will be completed during FY 1981.

  19. SOFT COST GRAND CHALLENGE

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    energycenter.org California Center for Sustainable Energy Soft Cost Grand Challenge May 22, 2014 Accelerating the transition to a sustainable world powered by clean energy 2...

  20. GRAND CHALLENGE PROBLEMS

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    GRAND CHALLENGE PROBLEMS Time is the biggest issue. Materials typically become critical in a matter of months, but solutions take years or decades to develop and implement. Our first two grand challenges address this discrepancy. Anticipating Which Materials May Go Critical In an ideal world, users of materials would anticipate supply-chain disruptions before they occur. They would undertake activities to manage the risks of disruption, including R&D to diversify and increase supplies or to

  1. Raptor Use of the Rio Grande Gorge

    SciTech Connect (OSTI)

    Ponton, David A.

    2015-03-20

    The Rio Grande Gorge is a 115 km long river canyon located in Southern Colorado (15 km) and Northern New Mexico (100 km). The majority of the canyon is under the administration of the Bureau of Land Management {BLM), and 77 km of the canyon south of the Colorado/New Mexico border are designated Wild River under the National Wild and Scenic Rivers Act of 1968. Visits I have made to the Rio Grande Gorge over the past 15 .years disclosed some raptor utilization. As the Snake River Birds of Prey Natural Area gained publicity, its similarity to the Rio Grande Gorge became obvious, and I was intrigued by the possibility of a high raptor nesting density in the Gorge. A survey in 1979 of 20 km of the northern end of the canyon revealed a moderately high density of red-tailed hawks and prairie falcons. With the encouragement of that partial survey, and a need to assess the impact of river-running on nesting birds of prey, I made a more comprehensive survey in 1980. The results of my surveys, along with those of a 1978 helicopter survey by the BLM, are presented in this report, as well as general characterization of the area, winter use by raptors, and an assessment of factors influencing the raptor population.

  2. Mountain View Grand | Open Energy Information

    Open Energy Info (EERE)

    Mountain View Grand Jump to: navigation, search Name Mountain View Grand Facility Mountain View Grand Sector Wind energy Facility Type Small Scale Wind Facility Status In Service...

  3. Cassie Mills | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Cassie Mills About Us Cassie Mills - Communications Associate in the Advanced Manufacturing Office Cassie Mills is a communications associate in the Advanced Manufacturing Office in the Office of Energy Efficiency and Renewable Energy. Most Recent Industrial Assessment Centers Train Future Energy-Savvy Engineers April 12

  4. DOE - Office of Legacy Management -- Grand Junction Sites

    Office of Legacy Management (LM)

    Grand Junction Sites Grand Junction Sites gj_map Grand Junction Disposal Site Grand Junction Processing Site Grand Junction Site Contact Us

  5. Evaluation of End Mill Coatings

    SciTech Connect (OSTI)

    L. J. Lazarus; R. L. Hester,

    2005-08-01

    Milling tests were run on families of High Speed Steel (HSS) end mills to determine their lives while machining 304 Stainless Steel. The end mills tested were made from M7, M42 and T15-CPM High Speed Steels. The end mills were also evaluated with no coatings as well as with Titanium Nitride (TiN) and Titanium Carbo-Nitride (TiCN) coatings to determine which combination of HSS and coating provided the highest increase in end mill life while increasing the cost of the tool the least. We found end mill made from M42 gave us the largest increase in tool life with the least increase in cost. The results of this study will be used by Cutting Tool Engineering in determining which end mill descriptions will be dropped from our tool catalog.

  6. 2015 Race to Zero Competition Grand Winner and Grand Winner Finalist Team

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Submissions | Department of Energy Grand Winner and Grand Winner Finalist Team Submissions 2015 Race to Zero Competition Grand Winner and Grand Winner Finalist Team Submissions Read the team submissions for the Grand Winner and Grand Winner Finalist teams from the 2015 Race to Zero Student Design Competition below. Learn more about the results of the 2015 competition. PDF icon Grand Winner: Opti-MN, University of Minnesota PDF icon Grand Winner Finalist: Team App, Appalachian State

  7. Environmental Impact Statements (EIS) | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Impact Statement Remediation of the Moab Uranium Mill Tailings, Grand and San Juan Counties, Utah September 3, 2004 EIS-0346: Draft Environmental Impact Statement Salmon...

  8. Grand Challenge Portfolio: Driving Innovations in Industrial...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Grand Challenge Portfolio: Driving Innovations in Industrial Energy Efficiency, January 2011 Grand Challenge Portfolio: Driving Innovations in Industrial Energy Efficiency, January ...

  9. Rio Grande North | Open Energy Information

    Open Energy Info (EERE)

    search Name Rio Grande North Facility Rio Grande North Sector Wind energy Facility Type Offshore Wind Facility Status Proposed Owner Baryonyx Corporation Developer Baryonyx...

  10. Nuclear Proliferation and Grand Challenges

    ScienceCinema (OSTI)

    McCarthy, Kathy

    2013-05-28

    Nuclear engineer Dr. Kathy McCarthy leads systems analysis. She talks about proliferation and the grand challenges of nuclear R&D. For more information about INL energy research, visit http://www.facebook.com/idahonationallaboratory.

  11. Estimated dose to man from uranium milling via the terrestrial food-chain pathway

    SciTech Connect (OSTI)

    Rayno, D.R.

    1982-01-01

    One of the major pathways of radiological exposure to man from uranium milling operations is through the terrestrial food chain. Studies by various investigators have shown the extent of uptake and distribution of U-238, U-234, Th-230, Ra-226, Pb-210, and Po-210 in plants and animals. These long-lived natural radioisotopes, all nuclides of the uranium decay series, are found in concentrated amounts in uranium mill tailings. Data from these investigations are used to estimate the dose to man from consumption of beef and milk contaminated by the tailings. This dose estimate from this technologically enhanced source is compared with that from average normal dietary intake of these radionuclides from natural sources.

  12. Langdon II - Otter Tail Wind Farm | Open Energy Information

    Open Energy Info (EERE)

    Otter Tail Wind Farm Jump to: navigation, search Name Langdon II - Otter Tail Wind Farm Facility Langdon II - Otter Tail Sector Wind energy Facility Type Commercial Scale Wind...

  13. U0004500.DOC

    Office of Legacy Management (LM)

    155 Environmental Assessment of Ground-Water Compliance Activities at the Uranium Mill Tailings Site, Spook, Wyoming February 1997 DOE/EA-1155 Uranium Mill Tailing Remedial Action Project Environmental Assessment of Ground-Water Compliance Activities At the Uranium Mill Tailings Site Spook, Wyoming February 1997 Prepared by U.S. Department of Energy Albuquerque Operations Office Grand Junction Office Environmental Assessment of Ground-Water Compliance Activities at the Uranium Mill Tailings Site

  14. SU(6) grand unified model

    SciTech Connect (OSTI)

    Dong, J.X.

    1986-03-14

    A model of grand unified theory based on SU(6) gauge group is proposed. It can accommodate two generations of ordinary fermions with V-A weak coupling and two generations of weird fermions with V+A weak coupling. In this model, a new discrete symmetry is introduced that insures existence of fermions with lower masses when SU(6) gauge symmetry is spontaneously broken. Simple Higgs fields with appropriate vacuum expectation values are chosen, so that the masses of weird fermions are heavier than those of ordinary fermions. This model also gives the same value of Weinberg angle, sin sq of Theta/sub w/ = 3/8, as in the usual SU(5) grand unified model at the grand unified scale.

  15. Gas fluidized-bed stirred media mill

    DOE Patents [OSTI]

    Sadler, III, Leon Y. (Tuscaloosa, AL)

    1997-01-01

    A gas fluidized-bed stirred media mill is provided for comminuting solid ticles. The mill includes a housing enclosing a porous fluidizing gas diffuser plate, a baffled rotor and stator, a hollow drive shaft with lateral vents, and baffled gas exhaust exit ports. In operation, fluidizing gas is forced through the mill, fluidizing the raw material and milling media. The rotating rotor, stator and milling media comminute the raw material to be ground. Small entrained particles may be carried from the mill by the gas through the exit ports when the particles reach a very fine size.

  16. Gary Mills | Savannah River Ecology Laboratory

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Mills Curriculum Vitae Faculty & Scientists SREL Home Gary Mills Savannah River Ecology Laboratory P O Drawer E, Aiken, SC 29802 (803) 725-5368 office (803) 725-3309 fax...

  17. EA-33 Rio Grande Electric | Department of Energy

    Energy Savers [EERE]

    Rio Grande Electric EA-33 Rio Grande Electric Order authorizing Rio Grande Electric to export electric energy to Mexico PDF icon EA-33 Rio Grande Electric More Documents & Publications EA-33-A and PP-33-1 Rio Grande Electric Cooperative, Inc. PP-33-1 and EA-33-A Rio Grande Electric Cooperative Inc PP-53 Rio Grande

  18. Race to Zero 2015 Grand Winner Finalists | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Grand Winner Finalists Race to Zero 2015 Grand Winner Finalists View the presentations for the 2015 Race to Zero Student Design Competition Grand Winner Finalists below. Mountain...

  19. EV Everywhere Grand Challenge Blueprint

    Office of Environmental Management (EM)

    A Message from the Assistant Secretary Every challenge presents an even greater opportunity, and the EV Everywhere Grand Challenge is no exception. The need for clean energy solutions drives the most important economic development race of the 21st century, providing opportunity for America to invent, manufacture, and export clean energy technologies. Recognizing that vehicle electrification is an essential part of our country's "all-of-the above" energy strategy, President Obama issued

  20. Grand Junction, Colorado, Site Fact Sheet

    Office of Legacy Management (LM)

    D D&D Page 1 of 3 Fact Sheet Grand Junction, Colorado, Site This fact sheet provides information about the Grand Junction, Colorado, Site. This site is managed by the U.S. Department of Energy Office of Legacy Management under the Defense Decontamination and Decommissioning (D&D) Program. Location of the Grand Junction, Colorado, Site Site Description and History The Grand Junction site is located in the city of Grand Junction, in west-central Colorado about 26 miles from the Utah

  1. Progress Toward Remediation of Uranium Tailings in Mailuu-Suu, Kyrgyzstan

    SciTech Connect (OSTI)

    Buckley, P B; Ranville, J; Honeyman, B D; Smith, D K; Rosenberg, N; Knapp, R B

    2003-07-09

    The town of Mailuu-Suu in Kyrgyzstan inherited 23 distinct tailings deposits from Soviet-Era uranium mining operations. Mailuu-Suu is located in the narrow landslide-prone valley of the Mailuu-Suu River about 25 km from the Uzbekistan border. Large-scale release of the radioactive tailings, as a result of landslides, could lead to irreversible contamination of the river and downstream areas. The Mailuu-Suu River is a tributary to the Syr-Darya River, the Fergana valley's main source of irrigation water. The Fergana Valley is a key agricultural region and major population center that spans Kyrgyzstan, Tajikistan, and Uzbekistan. The trans-boundary nature of the Mailuu-Suu tailings issue presents an opportunity for collaboration among these Central Asian states. A cooperative approach to addressing environmental issues such as Mailuu-Suu may contribute to the region's stability by facilitating peaceful associations. Experience from remediation of sites in the US under the Uranium Mill Tailings Remediation Action Project (UMTRA) will be useful in progressing toward remediation at Mailuu-Suu.

  2. Comet tail formation: Giotto observations

    SciTech Connect (OSTI)

    Wilken, B.; Jockers, K.; Johnstone, A.; Coates, A.; Heath, J.; Formisano, V.; Amata, E.; Winningham, J.D.; Thomsen, M.; Bryant, D.A.

    1986-01-01

    The process of mass loading of the solar wind by cometary ions, which forms comet tails, has been observed throughout the coma of comet Halley. Three distinct regimes were found where the nature of the energy and momentum coupling between solar wind and cometary ions is different. Outside the bow shock, where there is little angular scattering of the freshly ionized particles, the coupling is described by the simple pickup trajectory and the energy is controlled by the angle between the flow and the magnetic field. Just inside the bow shock, there is considerable scattering accompanied by another acceleration process which raises some particle energies well above the straightforward pickup value. Finally, closer to the nucleus, the amount of scattering decreases and the coupling is once more controlled by the magnetic field direction. 4 refs., 3 figs.

  3. Uranium Mill Tailings Remedial Action Project Annual Environmental Monitoring Report calendar year 1992: Volume 2

    SciTech Connect (OSTI)

    1993-12-31

    This report contains environmental monitoring information for the following UMTRA sites for the 1992 Calendar Year: Lakeview, OR; Lowman, ID; Mexican Hat, UT; Monument Valley, AZ; Rifle, CO; Riverton, WY; Shiprock, NM; Spook, WY; Tuba City, AZ. Each site report contains a site description, compliance summary, environmental program information, environmental radiological and non-radiological program information, water resources protection, and quality assurance information.

  4. Baseline risk assessment of ground water contamination at the Uranium Mill Tailings Sites near Rifle, Colorado

    SciTech Connect (OSTI)

    1995-05-01

    The ground water project evaluates the nature and extent of ground water contamination resulting from the uranium ore processing activities. This report is a site specific document that will be used to evaluate current and future impacts to the public and the environment from exposure to contaminated ground water. Currently, no one is using the ground water and therefore, no one is at risk. However, the land will probably be developed in the future and so the possibility of people using the ground water does exist. This report examines the future possibility of health hazards resulting from the ingestion of contaminated drinking water, skin contact, fish ingestion, or contact with surface waters and sediments.

  5. Annual status report on the Uranium Mill Tailings Remedial Action Program

    SciTech Connect (OSTI)

    Not Available

    1985-12-01

    FY 1985 project accomplishments include: completed 90% of the processing site remedial actions at Canonsburg, Pennsylvania, and initiated remedial actions at Salt Lake City, Utah, and Shiprock, New Mexico; awarded remedial action contracts on 329 vicinity properties at seven designated locations and completed survey and inclusion activities on a total of 1620 vicinity properties; published the Environmental Assessment (EA) for Lakeview, Oregon, issued the draft and prepared the final Environmental Impact Statement (EIS) for Durango, Colorado; completed the Remedial Action Plan (RAP) for Lakeview, Oregon, and prepared the draft RAP for Durango, Colorado; executed cooperative agreements with Idaho, New Mexico, and the Navajo Nation/Hopi Tribe; executed a Memorandum of Understanding with the Nuclear Regulatory Commission; and developed proposed UMTRA Project design review criteria between DOE and the NRC.

  6. Remedial action plan for stabilization of the inactive uranium mill tailings site at Monument Valley, Arizona

    SciTech Connect (OSTI)

    1986-02-01

    This Remedial Action Plan (RAP) has been developed to serve a two-fold purpose. It presents the series of activities which are proposed by the U.S. Department of Energy (DOE) to accomplish long-term stabilization and control of radioactive materials at the inactive uranium processing site located near Monument Valley, Arizona It also serves to document the concurrence of both the Navajo Nation and the U.S. Nuclear Regulatory Commission (NRC) in the remedial action. This agreement, upon execution by DOE and the Navajo Nation and concurrence by NRC, becomes Appendix B of the Cooperative Agreement.

  7. Design, Performance, and Sustainability of Engineered Covers for Uranium Mill Tailings

    Broader source: Energy.gov [DOE]

    Proceedings of the Workshop on Long-Term Performance Monitoring of Metals and Radionuclides in the Subsurface: Strategies, Tools, and Case Studies. U.S. Geological Survey.April 21 and 22, 2004,...

  8. Mississippi Nuclear Profile - Grand Gulf

    U.S. Energy Information Administration (EIA) Indexed Site

    Grand Gulf" "Unit","Summer capacity (mw)","Net generation (thousand mwh)","Summer capacity factor (percent)","Type","Commercial operation date","License expiration date" 1,"1,251","9,643",88.0,"BWR","application/vnd.ms-excel","application/vnd.ms-excel" ,"1,251","9,643",88.0 "Data for 2010" "BWR = Boiling Water Reactor."

  9. Online SAG Mill Pluse Measurement and Optimization

    SciTech Connect (OSTI)

    Raj Rajamani; Jose Delgadillo; Vishal Duriseti

    2007-06-30

    The grinding efficiency of semi autogenous milling or ball milling depends on the tumbling motion of the total charge within the mill. Utilization of this tumbling motion for efficient breakage of particles depends on the conditions inside the mill. However, any kind of monitoring device to measure the conditions inside the mill shell during operation is virtually impossible due to the severe environment presented by the tumbling charge. An instrumented grinding ball, which is capable of surviving a few hours and transmitting the impacts it experiences, is proposed here. The spectrum of impacts collected over 100 revolutions of the mills presents the signature of the grinding environment inside mill. This signature could be effectively used to optimize the milling performance by investigating this signature's relation to mill product size, mill throughput, make-up ball size, mill speed, liner profile and ball addition rates. At the same time, it can also be used to design balls and liner systems that can survive longer in the mill. The technological advances made in electronics and communication makes this leap in instrumentation certainly viable. Hence, the instrumented grinding ball offers the ability to qualitatively observe and optimize the milling environment. An instrumented load cell package that can measure the force of impacts inside the grinding chamber of a mill is developed here. The signal from the instrumented load cell package is interpreted in terms of a histogram termed as an impact spectrum which is a plot of the number of impacts at a specific energy level against the energy. It reflects on the average force regime of the mill. The instrumented load cell package was calibrated against the ultra fast load cell which has been unanimously accepted as a standard to measure single breakage events. The load cell package was successfully used to produce impact spectra in an 8.5 inch lab scale mill. The mill speed and the ball size were varied to study their effect on the impact spectra. A good correlation was found between the process variables and the impact spectra. The load cell package was then used in a 16 inch pilot scale mill. The mill speed, ball size, and mill filling were varied here and a consistent trend between these variables and impact spectra was observed. With a better understanding developed from the initial tests, the design of the load cell package was significantly changed to eliminate noise. With the new design, the impact spectra were re-determined in the 16 inch pilot mill varying the process variables - ball size, mill speed, and mill filling. Finally, it is successfully shown that a change in the operating variables of a mill can be seen in the impact spectra and that this concept can be successfully developed to monitor the grinding operation of industrial mills. To adapt it to industrial level it is mandatory to make the load cell package wireless. A design of a wireless circuit that is capable of transferring data at the required speed of 1000 kbps was also developed and tested at Cortez Gold Mines (CGM), Nevada.

  10. An Analytical Approach for Tail-Pipe Emissions Estimation with...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    An Analytical Approach for Tail-Pipe Emissions Estimation with Coupled Engine and Aftertreatment System An Analytical Approach for Tail-Pipe Emissions Estimation with Coupled Engine ...

  11. Finding of No Significant Impact, proposed remediation of the Maybell Uranium Mill Processing Site, Maybell, Colorado

    SciTech Connect (OSTI)

    Not Available

    1995-12-31

    The U.S. Department of Energy (DOE) has prepared an environmental assessment (EA) (DOE/EA-0347) on the proposed surface remediation of the Maybell uranium mill processing site in Moffat County, Colorado. The mill site contains radioactively contaminated materials from processing uranium ore that would be stabilized in place at the existing tailings pile location. Based on the analysis in the EA, DOE has determined that the proposed action does not constitute a major federal action significantly affecting the quality of the human environment within the meaning of the National Environmental Policy Act (NEPA) of 1969, Public Law 91-190 (42 U.S.C. {section}4321 et seq.), as amended. Therefore, preparation of an environmental impact statement is not required and DOE is issuing this Finding of No Significant Impact (FONSI).

  12. The Bowersock Mills and Power Company 1874

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Incremental Hydroelectric Energy The Bowersock Mills and Power Co., Lawrence, KS Hydroelectric Energy Potential for U.S. BMPC Plant At Forefront of Development Curve "In our ...

  13. Kumar, Jitendra; Hoffman, Forrest; Hargrove, William; Mills,...

    Office of Scientific and Technical Information (OSTI)

    based Sampling Network Design for the State of Alaska Kumar, Jitendra; Hoffman, Forrest; Hargrove, William; Mills, Richard 54 Environmental Sciences Ecoregions; Representativeness;...

  14. Colony Mills Limited | Open Energy Information

    Open Energy Info (EERE)

    Place: Lahore, Pakistan Sector: Solar Product: Yarn manufacturer, plans to set up solar thermal plant. References: Colony Mills Limited1 This article is a stub. You can help...

  15. Mille Lacs Energy Cooperative | Open Energy Information

    Open Energy Info (EERE)

    Cooperative Place: Minnesota Phone Number: 1-800-450-2191 Website: www.mlecmn.net Facebook: https:www.facebook.compagesMille-Lacs-Energy-Cooperative299198793447582 Outage...

  16. Destilaria Rio Grande | Open Energy Information

    Open Energy Info (EERE)

    to: navigation, search Name: Destilaria Rio Grande Place: Fronteira, Minas Gerais, Brazil Zip: 38230-000 Product: Brazil based ethanol producer. References: Destilaria Rio...

  17. Usina Serra Grande | Open Energy Information

    Open Energy Info (EERE)

    navigation, search Name: Usina Serra Grande Place: Maceio, Alagoas, Brazil Product: Ethanol producer Coordinates: -9.666479, -35.734954 Show Map Loading map......

  18. EV Everywhere Grand Challenge - Charging Infrastructure Enabling...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Presentation given at the EV Everywhere Grand Challenge: Consumer Acceptance and Charging Infrastructure Workshop on July 30, 2012 held at the LAX Marriott, Los Angeles, CA PDF ...

  19. EV Everywhere Grand Challenge - Battery Workshop Agenda

    Broader source: Energy.gov (indexed) [DOE]

    7252012 EV Everywhere Grand Challenge -- Battery Workshop Thursday, July 26, 2012 - Doubletree O'Hare, Chicago, IL Event Objective: DOE aims to obtain stakeholder input on the...

  20. Grand Challenge Portfolio: Driving Innovations in Industrial...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    8 Grand Challenge Portfolio: Driving Innovations in Industrial Energy Efficiency, January 2011 - pg 8 PDF icon grandchallengesportfoliopg8.pdf More Documents & Publications ...

  1. Grand Challenge Portfolio: Driving Innovations in Industrial...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    6 Grand Challenge Portfolio: Driving Innovations in Industrial Energy Efficiency, January 2011 - pg 6 PDF icon grandchallengesportfoliopg6.pdf More Documents & Publications ...

  2. Grand Challenge Portfolio: Driving Innovations in Industrial...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    9 Grand Challenge Portfolio: Driving Innovations in Industrial Energy Efficiency, January 2011 - pg 9 PDF icon grandchallengesportfoliopg9.pdf More Documents & Publications ...

  3. Grand River Dam Authority | Open Energy Information

    Open Energy Info (EERE)

    River Dam Authority Place: Oklahoma Phone Number: 918-256-5545 Website: www.grda.com Twitter: @okgrda Facebook: https:www.facebook.compagesGrand-River-Dam-Authority...

  4. Hydrogen Storage Grand Challenge Individual Projects

    Broader source: Energy.gov [DOE]

    Hydrogen Storage Grand Challenge individual projects funded for three Centers of Excellence, led by the National Renewable Energy Laboratory, Sandia National Laboratories, and Los Alamos National Laboratory

  5. Grand Junction Office Founder Honored at the

    Office of Environmental Management (EM)

    4 Grand Junction Office Founder Honored at the Philip C. Leahy Memorial Park Dedication and Open House The U.S. Department of Energy (DOE) Offce of Legacy Management (LM) held an open house and park dedication at the Grand Junction, Colorado, Offce to commemorate its place in the Manhattan Project and Cold War histories. The park, located in the middle of the Grand Junction Offce campus, was dedicated to Army Major (retired) Philip C. Leahy. Leahy came to Grand Junction in 1943 under secret

  6. Final technical evaluation report for the proposed revised reclamation plan for the Atlas Corporation Moab Mill

    SciTech Connect (OSTI)

    1997-03-01

    This final Technical Evaluation Report (TER) summarizes the US Nuclear Regulatory Commission staff`s review of Atlas Corporation`s proposed reclamation plan for its uranium mill tailings pile near Moab, Utah. The proposed reclamation would allow Atlas to (1) reclaim the tailings pile for permanent disposal and long-term custodial care by a government agency in its current location on the Moab site, (2) prepare the site for closure, and (3) relinquish responsibility of the site after having its NRC license terminated. The NRC staff concludes that, subject to license conditions identified in the TER, the proposed reclamation plan meets the requirements identified in NRC regulations, which appear primarily in 10 CFR Part 40. 112 refs., 6 figs., 16 tabs.

  7. Hanford Site Black-tailed Jackrabbit

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    0 Hanford Site Black-tailed Jackrabbit Monitoring Report for Fiscal Year 2013 C. Lindsey, J. Nugent, J. Wilde, and S. Johnson Mission Support Alliance Date Published February 2014...

  8. Uranium mill ore dust characterization

    SciTech Connect (OSTI)

    Knuth, R.H.; George, A.C.

    1980-11-01

    Cascade impactor and general air ore dust measurements were taken in a uranium processing mill in order to characterize the airborne activity, the degree of equilibrium, the particle size distribution and the respirable fraction for the /sup 238/U chain nuclides. The sampling locations were selected to limit the possibility of cross contamination by airborne dusts originating in different process areas of the mill. The reliability of the modified impactor and measurement techniques was ascertained by duplicate sampling. The results reveal no significant deviation from secular equilibrium in both airborne and bulk ore samples for the /sup 234/U and /sup 230/Th nuclides. In total airborne dust measurements, the /sup 226/Ra and /sup 210/Pb nuclides were found to be depleted by 20 and 25%, respectively. Bulk ore samples showed depletions of 10% for the /sup 226/Ra and /sup 210/Pb nuclides. Impactor samples show disequilibrium of /sup 226/Ra as high as +-50% for different size fractions. In these samples the /sup 226/Ra ratio was generally found to increase as particle size decreased. Activity median aerodynamic diameters of the airborne dusts ranged from 5 to 30 ..mu..m with a median diameter of 11 ..mu..m. The maximum respirable fraction for the ore dusts, based on the proposed International Commission on Radiological Protection's (ICRP) definition of pulmonary deposition, was < 15% of the total airborne concentration. Ore dust parameters calculated for impactor duplicate samples were found to be in excellent agreement.

  9. Tamil Nadu Spinning Mills Association TASMA | Open Energy Information

    Open Energy Info (EERE)

    Tamil Nadu, India Zip: 624003 Sector: Wind energy Product: Association of spinning mill owners; promoting wind power projects. References: Tamil Nadu Spinning Mills...

  10. Mill Run Wind Power Project | Open Energy Information

    Open Energy Info (EERE)

    Run Wind Power Project Jump to: navigation, search Name Mill Run Wind Power Project Facility Mill Run Wind Power Project Sector Wind energy Facility Type Commercial Scale Wind...

  11. Beijing Jingye Bearing Manufacture for Rolling Mills Co Ltd ...

    Open Energy Info (EERE)

    Beijing Jingye Bearing Manufacture for Rolling Mills Co Ltd Jump to: navigation, search Name: Beijing Jingye Bearing Manufacture for Rolling Mills Co Ltd Place: Beijing...

  12. West Coast Paper Mills Ltd WCPML | Open Energy Information

    Open Energy Info (EERE)

    Paper Mills Ltd WCPML Jump to: navigation, search Name: West Coast Paper Mills Ltd. (WCPML) Place: Dandeli, Karnataka, India Zip: 581 325 Sector: Biomass Product: Dandeli based...

  13. EV Everywhere Grand Challenge Overview Presentation | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Overview Presentation EV Everywhere Grand Challenge Overview Presentation Presentation at the EV Everywhere Grand Challenge Kick-Off meeting held on June 21, 2012 at the Hyatt Regency, Dearborn, MI. PDF icon 2-danielson.pdf More Documents & Publications EV Everywhere Grand Challenge Introduction for Electric Drive Workshop EV Everywhere Grand Challenge Overview EV Everywhere Grand Challenge Overview

  14. City of Grand Marais, Minnesota (Utility Company) | Open Energy...

    Open Energy Info (EERE)

    Grand Marais Place: Minnesota Phone Number: (218) 387-3030 or (218)387-1848 Website: www.ci.grand-marais.mn.usinde Facebook: https:www.facebook.comGrandMaraisMN Outage Hotline:...

  15. 2014 Race to Zero Student Design Competition: Grand Winner Teams...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Grand Winner Teams 2014 Race to Zero Student Design Competition: Grand Winner Teams 2014 Race to Zero Student Design Competition: Grand Winner Teams, from the U.S. Department of...

  16. EV Everywhere Grand Challenge Overview | Department of Energy

    Office of Environmental Management (EM)

    2_danielson_caci.pdf More Documents & Publications EV Everywhere Grand Challenge Introduction for Electric Drive Workshop EV Everywhere Grand Challenge Overview EV Everywhere Battery Workshop: Setting the Stage for the EV Everywhere Grand Challenge

  17. Defining the Mechanisms of Friction: A Grand Challenge in Interfacial...

    Office of Scientific and Technical Information (OSTI)

    Defining the Mechanisms of Friction: A Grand Challenge in Interfacial Mechanics. Citation Details In-Document Search Title: Defining the Mechanisms of Friction: A Grand Challenge...

  18. Agropecuaria e Industrial Serra Grande | Open Energy Information

    Open Energy Info (EERE)

    e Industrial Serra Grande Jump to: navigation, search Name: Agropecuaria e Industrial Serra Grande Place: So Raimundo das Mangabeiras, Maranhao, Brazil Product: Privately owned...

  19. Rio Grande Rift Geothermal Region | Open Energy Information

    Open Energy Info (EERE)

    Region Data Acquisition-Manipulation At Rio Grande Rift Region (Morgan, Et Al., 2010) Ground Gravity Survey At Rio Grande Rift Region (Aiken & Ander, 1981) Magnetotellurics At...

  20. EV Everywhere Grand Challenge - Battery Workshop attendees list...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    attendees list EV Everywhere Grand Challenge - Battery Workshop attendees list Attendance list for the EV Everywhere Grand Challenge: Battery Workshop on July 26, 2012 held at the...

  1. East Grand St Bridge Snowmelt Low Temperature Geothermal Facility...

    Open Energy Info (EERE)

    East Grand St Bridge Snowmelt Low Temperature Geothermal Facility Jump to: navigation, search Name East Grand St Bridge Snowmelt Low Temperature Geothermal Facility Facility East...

  2. Grand Challenges | U.S. DOE Office of Science (SC)

    Office of Science (SC) Website

    Grand Challenges Energy Frontier Research Centers (EFRCs) EFRCs Home Centers Research ... Print Text Size: A A A FeedbackShare Page Grand Challenge Report The Basic Energy Sciences ...

  3. Grand Coulee & Hungry Horse SCADA Replacement

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Gates Replacement This project is part of the Third Powerplant overhaul at Grand Coulee Dam. The full overhaul effort involves a mechanical overhaul of units G19 - G24. The...

  4. Wintertime meteorology of the Grand Canyon region

    SciTech Connect (OSTI)

    Whiteman, C.D.

    1992-09-01

    The Grand Canyon region of the American Southwest is an interesting region meteorologically, but because of its isolated location, the lack of major population centers in the region, and the high cost of meteorological field experiments, it has historically received little observational attention. In recent years, however, attention has been directed to episodes of visibility degradation in many of the US National parks, and two recent field studies focused on this visibility problem have greatly increased the meteorological data available for the Grand Canyon region. The most recent and comprehensive of these studies is the Navajo Generating Station Winter Visibility Study of 1989--90. This study investigated the sources of visibility degradation in Grand Canyon National Park and the meteorological mechanisms leading to low visibility episodes. In this paper we present analyses of this rich data set to gain a better understanding of the key wintertime meteorological features of the Grand Canyon region.

  5. DOE Grand Junction Projects Office Edgemont LTSP

    Office of Legacy Management (LM)

    DOE Grand Junction Projects Office Edgemont LTSP June 1996 Page ii Contents Page 1.0 Introduction ....................................................................................................................................... 1 1.1 Purpose ..................................................................................................................................... 1 1.2 Legal and Regulatory Requirements

  6. CMI Grand Challenge Problems | Critical Materials Institute

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    CMI Grand Challenge Problems Time is the biggest issue. Materials typically become critical in a matter of months, but solutions take years or decades to develop and implement. Our first two grand challenges address this discrepancy. Anticipating Which Materials May Go Critical In an ideal world, users of materials would anticipate supply-chain disruptions before they occur. They would undertake activities to manage the risks of disruption, including R&D to diversify and increase supplies or

  7. Lake Mills Light & Water | Open Energy Information

    Open Energy Info (EERE)

    Light & Water Jump to: navigation, search Name: Lake Mills Light & Water Place: Wisconsin Phone Number: (920) 648-4026 Website: www.lakemillslw.com Outage Hotline: (920) 648-4026...

  8. 2015 Race to Zero Competition Grand Winner and Grand Winner Finalist...

    Office of Environmental Management (EM)

    Williamsport Grand Winner Finalist: Team Illinois, University of Illinois at Urbana-Champaign More Documents & Publications Opti-MN Impact House Presentation 2015 Race to...

  9. O:\GRAPHICS\Factsheets\NEW\mont

    Office of Legacy Management (LM)

    9 United States Department of Energy Grand Junction Office Background The original Monticello mill was built in 1942 to provide an additional supply of vanadium during World War II. The mill was modified in the early 1950s to process uranium ore. Milling continued intermittently until the early 1960s, when the mill was dismantled. Tailings are the sandlike material that remains after processing of ore. Uranium tailings contain naturally occurring materials that radioactively decay to radium and

  10. This fact sheet describes the environmental cleanup activities the U.S. Departme

    Office of Legacy Management (LM)

    environmental cleanup activities the U.S. Department of Energy Grand Junction Projects Office is conducting at the Monticello Mill Tailings Site in Monticello, Utah. These activities are being performed in accordance with Federal and State environmental laws. Background The original Monticello mill was built in 1942 to provide an additional supply of vanadium during World War II. Vanadium, an element used to strengthen steel, and uranium were milled intermittently until 1960. Mill tailings are

  11. Background

    Office of Legacy Management (LM)

    explains the potential health hazards associated with air quality related to the removal and storage of mill tailings and other contaminated materials. Background From 1942 to 1960, uranium ore was processed at the Monticello mill in southeast Utah. When the mill was closed, approximately 2.3 million cubic yards of low-level radioactive mill tailings, contaminated soil, and other miscellaneous debris remained on the site. The U.S. Department of Energy (DOE) Grand Junction Projects Office, in

  12. F A C T S H E E T

    Office of Legacy Management (LM)

    June 2000 United States Department of Energy Grand Junction Office Background The original mill at Monticello, Utah, was built in 1942 to provide an additional supply of vanadium during World War II. The mill was modified in the early 1950s to process uranium ore. Milling continued intermittently until the early 1960s, when the mill was dismantled. Tailings are the sandlike material that remains after processing of ore. Uranium tailings contain naturally occurring materials that radioactively

  13. Hydrogen Storage Grand Challenge Centers of Excellence | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy Centers of Excellence Hydrogen Storage Grand Challenge Centers of Excellence DOE's Hydrogen Storage Grand Challenge Centers of Excellence and partners, led by NREL, SNL, and LANL PDF icon grand_challenge_centers.pdf More Documents & Publications Hydrogen Storage Grand Challenge Individual Projects Final Solar and Wind H2 Report EPAct 812.doc Microsoft Word - H2 National Release 2.doc

  14. Grand Challenge Portfolio: Driving Innovations in Industrial Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Efficiency, January 2011 - pg 6 | Department of Energy 6 Grand Challenge Portfolio: Driving Innovations in Industrial Energy Efficiency, January 2011 - pg 6 PDF icon grand_challenges_portfolio_pg6.pdf More Documents & Publications Grand Challenge Portfolio: Driving Innovations in Industrial Energy Efficiency, January 2011 - pg 8 Grand Challenge Portfolio: Driving Innovations in Industrial Energy Efficiency, January 2011 - pg 9

  15. EV Everywhere Grand Challenge - Battery Workshop Agenda | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy Agenda EV Everywhere Grand Challenge - Battery Workshop Agenda Agenda for the EV Everywhere Grand Challenge: Battery Workshop on July 26, 2012 held at the Doubletree O'Hare, Chicago, IL. PDF icon agenda_b.pdf More Documents & Publications EV Everywhere Grand Challenge - Charge to the Breakout Groups EV Everywhere Grand Challenge Introduction for Electric Drive Workshop EV Everywhere Grand Challenge Overview Presentation

  16. EV Everywhere Grand Challenge - Battery Workshop attendees list |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy attendees list EV Everywhere Grand Challenge - Battery Workshop attendees list Attendance list for the EV Everywhere Grand Challenge: Battery Workshop on July 26, 2012 held at the Doubletree OHare, Chicago, IL. PDF icon companies_in_attendance_b.pdf More Documents & Publications EV Everywhere Grand Challenge - Electric Drive (Power Electronics and Electric Machines) Workshop EV Everywhere Grand Challenge Overview EV Everywhere Grand Challenge Introduction for

  17. EV Everywhere Grand Challenge Road to Success

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    24 A M E S S A G E F R O M T H E a s s i s t a n t s e c r e t a r y Through the EV Everywhere Grand Challenge, U.S. researchers, employers, and PEV owners are all contributing to the growth of the clean energy economy. One year ago, we shared with you the EV Everywhere Grand Challenge Blueprint, providing a strategy to enable the U.S. to become the first nation in the world to produce plug-in vehicles (PEVs) that are as affordable and convenient as today's gasoline powered vehicles by 2022. The

  18. Validation of the Hot Strip Mill Model

    SciTech Connect (OSTI)

    Richard Shulkosky; David Rosberg; Jerrud Chapman

    2005-03-30

    The Hot Strip Mill Model (HSMM) is an off-line, PC based software originally developed by the University of British Columbia (UBC) and the National Institute of Standards and Technology (NIST) under the AISI/DOE Advanced Process Control Program. The HSMM was developed to predict the temperatures, deformations, microstructure evolution and mechanical properties of steel strip or plate rolled in a hot mill. INTEG process group inc. undertook the current task of enhancing and validating the technology. With the support of 5 North American steel producers, INTEG process group tested and validated the model using actual operating data from the steel plants and enhanced the model to improve prediction results.

  19. Owings Mills, Maryland: Energy Resources | Open Energy Information

    Open Energy Info (EERE)

    You can help OpenEI by expanding it. Owings Mills is a census-designated place in Baltimore County, Maryland.1 Registered Energy Companies in Owings Mills, Maryland...

  20. Middle Rio Grande Cooperative Water Model

    Energy Science and Technology Software Center (OSTI)

    2005-11-01

    This is computer simulation model built in a commercial modeling product Called Studio Expert, developed by Powersim, Inc. The simulation model is built in a system dynamics environment, allowing the simulation of the interaction among multiple systems that are all changing over time. The model focuses on hydrology, ecology, demography, and economy of the Middle Rio Grande, with Water as the unifying feature.

  1. Mill Designed Bio bleaching Technologies

    SciTech Connect (OSTI)

    Institute of Paper Science Technology

    2004-01-30

    A key finding of this research program was that Laccase Mediator Systems (LMS) treatments on high-kappa kraft could be successfully accomplished providing substantial delignification (i.e., > 50%) without detrimental impact on viscosity and significantly improved yield properties. The efficiency of the LMS was evident since most of the lignin from the pulp was removed in less than one hour at 45 degrees C. Of the mediators investigated, violuric acid was the most effective vis-a-vis delignification. A comparative study between oxygen delignification and violuric acid revealed that under relatively mild conditions, a single or a double LMS{sub VA} treatment is comparable to a single or a double O stage. Of great notability was the retention of end viscosity of LMS{sub VA} treated pulps with respect to the end viscosity of oxygen treated pulps. These pulps could then be bleached to full brightness values employing conventional ECF bleaching technologies and the final pulp physical properties were equal and/or better than those bleached in a conventional ECF manner employing an aggressively O or OO stage initially. Spectral analyses of residual lignins isolated after LMS treated high-kappa kraft pulps revealed that similar to HBT, VA and NHA preferentially attack phenolic lignin moieties. In addition, a substantial decrease in aliphatic hydroxyl groups was also noted, suggesting side chain oxidation. In all cases, an increase in carboxylic acid was observed. Of notable importance was the different selectivity of NHA, VA and HBT towards lignin functional groups, despite the common N-OH moiety. C-5 condensed phenolic lignin groups were overall resistant to an LMS{sub NHA, HBT} treatments but to a lesser extent to an LMS{sub VA}. The inactiveness of these condensed lignin moieties was not observed when low-kappa kraft pulps were biobleached, suggesting that the LMS chemistry is influenced by the extent of delignification. We have also demonstrated that the current generation of laccase has a broad spectrum of operating parameters. Nonetheless, the development of future genetically engineered laccases with enhanced temperature, pH and redox potentials will dramatically improve the overall process. A second challenge for LMS bleaching technologies is the need to develop effective, catalytic mediators. From the literature we already know this is feasible since ABTS and some inorganic mediators are catalytic. Unfortunately, the mediators that exhibit catalytic properties do not exhibit significant delignification properties and this is a challenge for future research studies. Potential short-term mill application of laccase has been recently reported by Felby132 and Chandra133 as they have demonstrated that the physical properties of linerboard can be improved when exposed to laccase without a chemical mediator. In addition, xxx has shown that the addition of laccase to the whitewater of the paper machine has several benefits for the removal of colloidal materials. Finally, this research program has presented important features on the delignification chemistry of LMS{sub NHA} and LMS{sub VA} that, in the opinion of the author, are momentous contributions to the overall LMS chemistry/biochemistry knowledge base which will continue to have future benefits.

  2. Microstructure Engineering for Hot Strip Mills | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Microstructure Engineering for Hot Strip Mills Microstructure Engineering for Hot Strip Mills Innovative Model Provides a More Detailed Insight into Mill Operations to Reduce Costs and Improve Quality Many hot rolled products must achieve strict strength and toughness requirements, making control of the microstructure critical. This causes these products to be difficult to make and requires many costly full production trials before the range of both chemical composition and hot strip mill

  3. Bay Mills Indian Community Energy Reduction Feasibility Study

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Tribal Council of Michigan, Inc. Environmental Services Division Chris Kushman Bay Mills Indian Community Energy Reduction Feasibility Study *DOE Tribal Energy Program *Tribal Energy Program Review presenters *Bay Mills Indian Community Thank You * Great relationship between ITCMI and Bay Mills * Proactive in exploring renewable energy alternatives - Bay Mills Community College Alternative Energy Curriculum - Biofuels and the crops to support biofuels - Wind resource data collection * Upper

  4. Comments of Mille Lacs Energy Cooperative | Department of Energy

    Office of Environmental Management (EM)

    Mille Lacs Energy Cooperative Comments of Mille Lacs Energy Cooperative Comments of Mille Lacs Energy Cooperative on Implementing the National Broadband Plan by Studying the Communications Requirements of Electric Utilities to Inform Federal Smart Grid Policy PDF icon Comments of Mille Lacs Energy Cooperative More Documents & Publications Comments of Utilities Telecom Council Communications Requirements of Smart Grid Technologies NBP RFI: Communications Requirements - Reply Comments of

  5. DOE - Office of Legacy Management -- Lowman Mill Site - ID 01

    Office of Legacy Management (LM)

    Lowman Mill Site - ID 01 FUSRAP Considered Sites Site: Lowman Mill Site (ID.01) Designated Name: Alternate Name: Location: Evaluation Year: Site Operations: Site Disposition: Radioactive Materials Handled: Primary Radioactive Materials Handled: Radiological Survey(s): Site Status: Also see Lowman, Idaho, Disposal Site Documents Related to Lowman Mill Site

  6. DOE Moab Site Cost-Effectively Eliminates 200 Million Gallons of Contaminated Ground Water

    Broader source: Energy.gov [DOE]

    Grand Junction, CO ― The Department of Energy (DOE) announced today that it has extracted 200 million gallons of contaminated ground water from the Moab site in Utah as part of the Moab Uranium Mill Tailings Remedial Action Project.

  7. EIS-0355: Record of Decision | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Record of Decision Remediation of the Moab Uranium Mill Tailings, Grand and San Juan Counties, UT The U.S. Department of Energy (DOE) announces its decision to implement...

  8. EIS-0355: Amended Record of Decision | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Amended Record of Decision Remediation of the Moab Uranium Mill Tailings, Grand and San Juan Counties, UT The U.S. Department of Energy (DOE) is amending its decision regarding the...

  9. Rio Grande LNG LLC- Dkt. No. 15-190-LNG

    Broader source: Energy.gov [DOE]

    The Office of Fossil Energy gives notice of receipt of an Application filed December 23, 2015, by Rio Grande LNG, LLC (Rio Grande), seeking a long-term multi-contract authorization to export...

  10. SunShot Grand Challenge Summit Breakout Sessions Announced

    Broader source: Energy.gov [DOE]

    The 2014 SunShot Grand Challenge Summit is only six weeks away! SunShot is excited to announce our thought-provoking lineup of Grand Challenge Breakout Sessions.

  11. City of Grand Haven, Michigan (Utility Company) | Open Energy...

    Open Energy Info (EERE)

    Grand Haven Place: Michigan Phone Number: (616) 846-6250 Website: www.ghblp.org Twitter: @ghblp Facebook: https:www.facebook.comGrandHavenBLP Outage Hotline: (616) 842-2241...

  12. Sandia Energy - Upper Rio Grande Simulation Model (URGSiM)

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Upper Rio Grande Simulation Model (URGSiM) Home Climate & Earth Systems WaterEnergy Nexus Decision Models for Integrating EnergyWater Systems Modeling Upper Rio Grande Simulation...

  13. SunShot Grand Challenge: Summit and Technology Forum

    Broader source: Energy.gov [DOE]

    The SunShot Grand Challenge: Summit and Technology Forum was the first event in a series of Department of Energy Grand Challenges. This event focused on SunShot Initiative goals of achieving grid...

  14. Sharp-tailed Grouse and Pygmy Rabbit Wildlife Mitigation Project. Final Environmental Assessment

    SciTech Connect (OSTI)

    Not Available

    1992-10-01

    The Proposed Action is needed to protect and enhance shrub-steppe and riparian habitat for sharp-tailed grouse (Tympanuchus phasianellus columbianus), Pygmy rabbits (Brachylagus idahoensis), and other indigenous wildlife species. The purpose of the Proposed Action is to compensate, in part, for wildlife habitat lost from the construction of Grand Coulee Dam and the inundation of Lake Roosevelt. Bonneville Power Administration proposes to fund management agreements, conservation easements, acquisition of fee title, or a combination of these on as many as 29,000 acres in Lincoln and Douglas Counties to improve shrub-steppe and riparian habitat for sharp-tailed grouse and pygmy rabbits. The BPA also proposes to fund habitat improvements (enhancements) on project lands including existing public lands. Proposed habitat treatments would include control of grazing; planting of native trees, shrubs, forbs and grasses; protection of wetlands and streambanks; herbicide use; fire prescriptions; and wildfire suppression. Proposed management activities may include predator control, population introductions, and control of crop depredation.

  15. Sharp-Tailed Grouse and Pygmy Rabbit Wildlife Mitigation Project : Final Environmental Assessment.

    SciTech Connect (OSTI)

    Untied States. Bonneville Power Adminsitration.

    1992-10-01

    The Proposed Action is needed to protect and enhance shrub-steppe and riparian habitat for sharp-tailed grouse (Tympanuchus phasianellus columbianus), Pygmy rabbits (Brachylagus idahoensis), and other indigenous wildlife species. The purpose of the Proposed Action is to compensate, in part, for wildlife habitat lost from the construction of Grand Coulee Dam and the inundation of Lake Roosevelt. Bonneville Power Administration proposes to fund management agreements, conservation easements, acquisition of fee title, or a combination of these on as many as 29,000 acres in Lincoln and Douglas Counties to improve shrub-steppe and riparian habitat for sharp-tailed grouse and pygmy rabbits. The BPA also proposes to fund habitat improvements (enhancements) on project lands including existing public lands. Proposed habitat treatments would include control of grazing; planting of native trees, shrubs, forbs and grasses; protection of wetlands and streambanks; herbicide use; fire prescriptions; and wildfire suppression. Proposed management activities may include predator control, population introductions, and control of crop depredation.

  16. 2014 Race to Zero Student Design Competition: Grand Winner Teams |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy Grand Winner Teams 2014 Race to Zero Student Design Competition: Grand Winner Teams 2014 Race to Zero Student Design Competition: Grand Winner Teams, from the U.S. Department of Energy. PDF icon rtz_grand_winner_team_rosters.pdf More Documents & Publications 2014 Race to Zero Student Design Competition: Montage Builders Team Submission 2014 Race to Zero Student Design Competition: Montage Builders Profile 2014 Race to Zero Student Design Competition: Auburn

  17. PP-33 Rio Grande Electric Cooperative Inc | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Rio Grande Electric Cooperative Inc PP-33 Rio Grande Electric Cooperative Inc Presidential permit authorizing Grande Electric Cooperative Inc to construct, operate, and maintain electric transmission facilities at the U.S-Mexico border. PDF icon PP-33 Rio Grande Electric Cooperative Inc More Documents & Publications PP-35 Trico Electric Cooperative Inc PP-285 Sharyland Utilities LP PP-107-1 Arizona Public Service Company

  18. PP-53 Rio Grande Electric Cooperative, Inc. | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    3 Rio Grande Electric Cooperative, Inc. PP-53 Rio Grande Electric Cooperative, Inc. Presidential Permit authorizing Rio Grande Electric Cooperative, Inc.to construct, operate, and maintain electric transmission facilities at the U.S. - Mexico Border. PDF icon PP-53 Rio Grande Electric Cooperative, Inc. More Documents & Publications PP-55 Roseau Electric Cooperative, Inc. PP-42 Roseau Electric Cooperative, Inc. PP-67 North Central Electric Cooperative, Inc.

  19. Grand Challenges | U.S. DOE Office of Science (SC)

    Office of Science (SC) Website

    Grand Challenges Energy Frontier Research Centers (EFRCs) EFRCs Home Centers Research Science Highlights News & Events Publications History Grand Challenges BES Reports Document Archives Contests Contact BES Home History Grand Challenges Print Text Size: A A A FeedbackShare Page Grand Challenge Report The Basic Energy Sciences Advisory Committee (BESAC) report, Directing Matter and Energy: Five Challenges for Science and the Imagination was the culmination of a series of BES-sponsored

  20. Grand Coulee-Creston_FONSI_and_MAP_27May2014

    Office of Environmental Management (EM)

    Grand Coulee-Creston Transmission Line Rebuild Project 1 Finding of No Significant Impact Grand Coulee-Creston Transmission Line Rebuild Project Finding of No Significant Impact (FONSI) Bonneville Power Administration DOE/EA-1950 May 2014 SUMMARY Bonneville Power Administration (BPA) announces its environmental findings on the Grand Coulee-Creston Transmission Line Rebuild Project. The project would rebuild nearly 28 miles of the Grand Coulee-Creston No. 1 115-kilovolt (kV) transmission line

  1. EV Everywhere Grand Challenge Introduction for Electric Drive Workshop |

    Office of Environmental Management (EM)

    Department of Energy Introduction for Electric Drive Workshop EV Everywhere Grand Challenge Introduction for Electric Drive Workshop Presentation given by EERE Assistant Secretary David Danielson at the EV Everywhere Grand Challenge - Electric Drive (Power Electronics and Electric Machines) Workshop on July 24, 2012 held at the Doubletree O'Hare, Chicago, IL. PDF icon 1_danielson_ed.pdf More Documents & Publications EV Everywhere Grand Challenge Overview EV Everywhere Grand Challenge

  2. Grand Challenge Portfolio: Driving Innovations in Industrial Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Efficiency, January 2011 - pg 8 | Department of Energy 8 Grand Challenge Portfolio: Driving Innovations in Industrial Energy Efficiency, January 2011 - pg 8 PDF icon grand_challenges_portfolio_pg8.pdf More Documents & Publications Grand Challenge Portfolio: Driving Innovations in Industrial Energy Efficiency, January 2011 - pg 9

  3. Grand Challenge Portfolio: Driving Innovations in Industrial Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Efficiency, January 2011 - pg 9 | Department of Energy 9 Grand Challenge Portfolio: Driving Innovations in Industrial Energy Efficiency, January 2011 - pg 9 PDF icon grand_challenges_portfolio_pg9.pdf More Documents & Publications Grand Challenge Portfolio: Driving Innovations in Industrial Energy Efficiency, January 2011 - pg 8

  4. EA-0930: Facility Operations at the U.S. DOE Grand Junction Projects Office, Grand Junction, Colorado

    Broader source: Energy.gov [DOE]

    This EA evaluates the environmental impacts of the proposal to expand and upgrade the U.S. Department of Energy's Grand Junction Projects Office facilities and operations in Grand Junction, Colorado.

  5. Upper Rio Grande Simulation Model (URGSIM)

    Energy Science and Technology Software Center (OSTI)

    2010-08-05

    URGSIM estimates the location of surface water and groundwater resources in the upper Rio Grande Basin between the Colorado-New Mexico state line, and Caballo Reservoir from 1975 - 2045. It is a mass balance hydrology model of the Upper Rio Grande surface water, groundwater, and water demand systems which runs at a monthly timestep from 1975-1999 in calibration mode, 2000 – 2004 in validation mode, and 2005 – 2045 in scenario analysis mode.

  6. F:\SHARE\SE\Web_Origs\Wrk_Jan\mvsowp\MONPIP.PDF

    Office of Legacy Management (LM)

    7.1 UMTRA Ground Water Project Public Involvement Plan for the Environmental Assessment of Ground Water Compliance at the Monument Valley, Arizona, Uranium Mill Tailings Site July 1999 Prepared by U.S. Department of Energy Grand Junction Office Grand Junction, Colorado Work performed under DOE Contract No. DE-AC13-96GJ87335 Public Involvement Plan for the Monument Valley UMTRA Site Page 2 Introduction This Public Involvement Plan is tiered to the Uranium Mill Tailings Remedial Action (UMTRA)

  7. Rio Grande pipeline introduces LPG to Mexico

    SciTech Connect (OSTI)

    1997-06-01

    Rio Grande Pipeline, a joint venture between Mid-America Pipeline Co., Amoco Pipeline Co. and Navajo Pipeline Co., has broken new ground in the energy industry as the first LPG pipeline to cross the US-Mexico border. Plans for the project were announced in November 1995 and first deliveries started three months ago on March 21, 1997. The 8-inch, 265-mile pipeline originates near Odessa, TX, where it receives an 85-15 propane-butane mix via a connection to Mid-America Pipeline. From Odessa, product moves west through the Texas desert and crosses the Rio Grande River about 15 miles south of El Paso near Clint, TX and extends 20 miles into Mexico. Capacity of the line is 24,000 bpd and it has been averaging about 22,000 bpd since line-fill. All in all, it sounded like a reasonably feasible, routine project. But perceptions can be deceiving, or at least misleading. In other words, the project can be summarized as follows: one river, two cultures and a world of difference. The official border crossing for pipeline construction took place on Dec. 2, 1996, with a directional drill under the Rio Grande River, but in actuality, the joint venture partners were continually bridging differences in language, laws, customs and norms with Pemex and contracted workers from Mexico.

  8. SunShot Grand Challenge | Department of Energy

    Energy Savers [EERE]

    SunShot Grand Challenge SunShot Grand Challenge Addthis SunShot Grand Challenge 1 of 28 SunShot Grand Challenge Participants gather for the plenary session at the SunShot Grand Challenge Summit and Technology Forum in Denver, Colorado. (Photo by DENNIS SCHROEDER / NREL) Date taken: 2012-06-13 07:10 Arun Majumdar, Founding Director, ARPA-E 2 of 28 Arun Majumdar, Founding Director, ARPA-E Arun Majumdar, Founding Director, ARPA-E gives the welcoming remarks. (Photo by DENNIS SCHROEDER / NREL) Date

  9. Beneficial uses of paper mill residuals for New York State`s recycled-paper mills. Final report

    SciTech Connect (OSTI)

    1995-09-01

    This report evaluates the New York paper mill industry in terms of the productive management and treatment of solid wastes. It identifies current efforts by recycling mills to beneficially use paper mill residuals (often called sludge) and suggests additional options that should be considered by the industry in general and individual mills in particular. It also examines the regulations and economics affecting the mills and suggests actions that could improve the industry`s ability to convert wastes to value-added products. The report recommends that the mills should continue measures to reduce fiber and filler clay losses, promote the transfer of usable fiber and clay to mills able to use them, upgrade sludge dewatering capabilities, and take a more regional approach to solid waste disposal problems. State agencies are urged to support these efforts, encourage the development and commercialization of new beneficial use technologies, and reduce regulatory barriers whenever possible.

  10. Remedial action plan and site design for stabilization of the inactive Uranium Mill Tailings Site at Lowman, Idaho

    SciTech Connect (OSTI)

    Not Available

    1991-09-01

    The DOE proposes to achieve compliance with the proposed EPA groundwater protection standards (Subparts A and B of 40 CFR 192) by meeting the EPA maximum concentration limits (MCLs) or background concentrations for designated hazardous constituents in groundwater in the uppermost aquifer (alluvium/weathered granodiorite) at the point of compliance (POC) at the Lowman disposal site near Lowman, Idaho. The proposed remedial action in conjunction with existing hydrogeological conditions at the Lowman site will ensure sufficient protection of human health and the environment. The DOE has concluded that the EPA groundwater protection standards will be met at the POC because, with the exception of antimony, none of the hazardous constituents that exceed laboratory method detection limits within the radioactive sand pore fluids were above the proposed concentration limits. The DOE has demonstrated that antimony will meet the proposed concentration limits at the POC through attenuation in subsoils beneath the disposal cell and by dilution in groundwater underflow. The Lowman processing site is in compliance with Subpart B of 40 CFR 192 because statistical analyses of groundwater samples indicate no groundwater contamination.

  11. Remedial action plan and site design for stabilization of the inactive uranium mill tailings sites at Rifle, Colorado: Final report

    SciTech Connect (OSTI)

    Not Available

    1992-02-01

    This volume contains Appendix F, bid schedule and specifications for remedial action on three sites: Old Rifle processing site; New Rifle processing site and Estes Gulch disposal site.

  12. Remedial Action Plan and site conceptual design for stabilization of the inactive uranium mill tailings site at Shiprock, New Mexico

    SciTech Connect (OSTI)

    Hill, T.V.; Morley, J.A. . Uranium Mill Tailings Remedial Action Project Office); Began, E.T. )

    1985-06-01

    This Remedial Action Plan (RAP) has been developed to serve a twofold purpose. It presents the series of activities which are proposed by the Department of Energy (DOE) to effect long-term control of radioactive materials at the inactive uranium processing site located on the Navajo Reservation at Shiprock, New Mexico. It also serves to document the concurrence of both the Navajo Nation and the Nuclear Regulatory Commission (NRC) in the remedial action. This document has been structured to provide a comprehensive understanding of the remedial action proposed for the Shiprock site. Detailed supporting information can be found in appendices and referenced documents. Section 2.0 presents the EPA standards, including a discussion of their objectives. Section 3.0 traces the history of operations at the Shiprock site with a description of the present site characteristics. Section 4.0 provides a definition of site-specific problems, a listing of remedial action alternatives which have been considered, and the action which is being proposed. Section 5.0 presents a summary of the conceptual design for the proposed action which includes objectives, design features, schedule, cost, and implementation methods. Section 6.0 summarizes the plan for ensuring health and safety protection for the surrounding community and the onsite workers. Section 7.0 presents a detailed listing of the responsibilities of the project participants. Section 8.0 describes the quality assurance process that will be used by the RAC during construction. Section 9.0 describes the features of the long-term maintenance and surveillance plan. Section 10.0 documents the on-going activities to keep the public informed and participating in the project. Attached as part of the RAP are five appendices which describe in more detail various aspects of the remedial action.

  13. Final programmatic environmental impact statement for the uranium mill tailings remedial action ground water project. Volume II

    SciTech Connect (OSTI)

    1996-10-01

    Volume II of the programmatic environmental impact statement (PElS) is a comment and response document; it is the collection of the comments received on the draft PElS. The U.S. Department of Energy's (DOE) response to each comment is provided after each comment. If the comment resulted in a change to the PElS, the affected section number of the PElS is provided in the response. Comments 1 through 259 were received at public hearings. The name of the hearing at which the comment was received is listed after each comment. Comments were recorded on flip charts and by notetakers. DOE representatives were present to hear the comments and respond to them. The DOE's written response is provided after each comment. Comments 260 through 576 were received in writing at the hearings, and from various federal, tribal, and state agencies and from individuals during the public comment period. Copies of the written comments follow the comments and responses.

  14. Remedial action plan and site design for stabilization of the inactive uranium mill tailings site at Tuba City, Arizona

    SciTech Connect (OSTI)

    Not Available

    1989-08-01

    This Remedial Action Plan (RAP) has been developed to serve a threefold purpose. It presents the series of activities which are proposed by the US Department of Energy (DOE) to accomplish long-term stabilization and control of radioactive materials at the inactive uranium processing site near Tuba City, Arizona. It provides a characterization of the present conditions of the site. It also serves to document the concurrence of the Navajo Nation, the Hopi Tribe, US Bureau of Indian Affairs (BIA), and the US Nuclear Regulatory Commission (NRC) in the remedial action. This agreement, upon execution by DOE, the Navajo Nation, and the Hopi Tribe, and concurrence by NRC, becomes Appendix B of the Cooperative Agreement. Following the introduction, contents are as follows: Section 2.0 presents the EPA standards, including a discussion of their objectives. Section 3.0 summarizes the present site characteristics and provides a definition of site-specific problems. Section 4.0 is the site design for the proposed action. Section 5.0 summarizes the plan for ensuring environmental, health, and safety protection for the surrounding community and the on-site workers. Section 6.0 presents a detailed listing of the responsibilities of the project participants. Section 7.0 describes the features of the long-term surveillance and maintenance plan. Section 8.0 presents the quality assurance aspects of the project. Section 9.0 documents the ongoing activities to keep the public informed and participating in the project.

  15. Uranium Mill Tailings Remedial Action Project (UMTRAP), Slick Rock, Colorado, Revision 1. Bid schedule, special conditions, specifications, and subcontract drawings

    SciTech Connect (OSTI)

    1995-10-01

    This volume contains: bidding requirements; terms and conditions; specifications for Division 1 -- general requirements; specifications for Division 2 -- sitework; specifications for Divisions 5 -- metals; subcontract drawings, (general, Union Carbide processing site, North Continent processing site, and Burro Canyon disposal site).

  16. Geothermal Mill Redevelopment Project in Massachusetts

    SciTech Connect (OSTI)

    Vale, A.Q.

    2009-03-17

    Anwelt Heritage Apartments, LLC redeveloped a 120-year old mill complex into a mixed-use development in a lower-income neighborhood in Fitchburg, Massachusetts. Construction included 84 residential apartments rented as affordable housing to persons aged 62 and older. The Department of Energy (DOE) award was used as an essential component of financing the project to include the design and installation of a 200 ton geothermal system for space heating and cooling.

  17. Microsoft Word - Mills CV March 2015.docx

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    CURRICULUM VITAE GARY LAWRENCE MILLS Savannah River Ecology Laboratory (SREL) University of Georgia Drawer E Aiken, SC 29802 gmills@srel.uga.edu Office: 803-725-5368 Cell: 803-270-3163 PROFESSIONAL EXPERIENCE: 2010 - Present Associate Research Scientist, SREL, University of Georgia 2005 - 2010 Program Manager, Organic Analysis and Mass Spectrometry SREL, University of Georgia 1990 - 2005 Associate Research Scientist, SREL, University of Georgia 1983 - 1990 Assistant Research Scientist, SREL,

  18. NEPA„a grand new idea

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    NEPA-a grand new idea As nuclear energy became more widely known after its initial use to end World War II, Oak Ridge was the source of expansion into unknown fields of study in hopes of capitalizing on this new source of abun- dant energy. One such example was the NEPA project. The Nuclear Energy for Propulsion of Aircraft project began in May, 1946. In February, 1947, a nuclear physics seminar with special emphasis on the application of nuclear energy to aircraft was held in Oak Ridge as part

  19. SunShot Grand Challenge Summit

    Broader source: Energy.gov [DOE]

    The SunShot Initiative at the U.S. Department of Energy (DOE) will host the second SunShot Grand Challenge Summit and Peer Review from May 19-22, 2014 at the Hilton Anaheim, California. The 2014 SunShot Summit brings together 800 esteemed members of the solar energy community including SunShot-funded project teams, industry leaders, innovative researchers and scientists, and local, state and federal government policymakers to review the progress made and discuss the challenges ahead to make solar energy more affordable and widespread across America.

  20. Pulp and Paper Mills: Profiting from Efficient Motor System Use |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy Pulp and Paper Mills: Profiting from Efficient Motor System Use Pulp and Paper Mills: Profiting from Efficient Motor System Use This 2-page fact sheet describes The Paper and Allied Products Industry spending to operate electric motor systems and opportunities to reduce these costs. PDF icon Pulp and Paper Mills: Profiting from Efficient Motor System Use (January 1999) More Documents & Publications Bandwidth Study U.S. Pulp and Paper Manufacturing United States

  1. DOE - Office of Legacy Management -- Marion Mill Site - CO 09

    Office of Legacy Management (LM)

    Mill Site - CO 09 FUSRAP Considered Sites Site: MARION MILL SITE (CO.09 ) Eliminated from further consideration under FUSRAP - deferred to the State of Colorado for appropriate action. Designated Name: Not Designated Alternate Name: None Location: Sugar Leaf Road , Boulder , Colorado CO.09-1 Evaluation Year: Circa 1983 CO.09-1 Site Operations: Milled and processed thorite and other rare earth ores in 1957 and 1958. Some of the thorium concentrate produced was shipped to Davison Chemical Company

  2. DOE - Office of Legacy Management -- Uravan Mill Site - CO 02

    Office of Legacy Management (LM)

    Uravan Mill Site - CO 02 FUSRAP Considered Sites Site: Uravan Mill Site (CO.02 ) Designated Name: Alternate Name: Location: Evaluation Year: Site Operations: Site Disposition: Radioactive Materials Handled: Primary Radioactive Materials Handled: Radiological Survey(s): Site Status: Also see Naturita, Colorado, Processing Site Documents Related to Uravan Mill Site Data Validation Package for the July and October 2008 Water Sampling at the Naturita Processing and Disposal Sites Data Validation

  3. Energy Department Recognizes General Mills for Leadership and Innovation at

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Iowa Plant | Department of Energy General Mills for Leadership and Innovation at Iowa Plant Energy Department Recognizes General Mills for Leadership and Innovation at Iowa Plant October 13, 2015 - 2:38pm Addthis As part of the Obama Administration's effort to cut climate-changing carbon emissions produced by the nation's buildings and manufacturing plants, today the U.S. Department of Energy (DOE) recognized General Mills, one of the world's leading food companies, for its leadership in

  4. East Millinocket Mill Biomass Facility | Open Energy Information

    Open Energy Info (EERE)

    Mill Sector Biomass Location Penobscot County, Maine Coordinates 45.3230777, -68.5806727 Show Map Loading map... "minzoom":false,"mappingservice":"googlemaps3","type"...

  5. Cedar Mill, Oregon: Energy Resources | Open Energy Information

    Open Energy Info (EERE)

    Mill, Oregon: Energy Resources Jump to: navigation, search Equivalent URI DBpedia Coordinates 45.5048397, -122.7984325 Show Map Loading map... "minzoom":false,"mappingservice"...

  6. Nahar Spinning Mills Ltd NSML | Open Energy Information

    Open Energy Info (EERE)

    (NSML) Place: Ludhiana, Punjab, India Zip: 141 003 Product: Ludhiana-based spinning mill with cogeneration activities. Coordinates: 30.89314, 75.86938 Show Map Loading...

  7. SubTER Grand Challenge Roundtable: Imaging Geophysical and Geochemical

    Energy Savers [EERE]

    Signals in the Subsurface | Department of Energy SubTER Grand Challenge Roundtable: Imaging Geophysical and Geochemical Signals in the Subsurface SubTER Grand Challenge Roundtable: Imaging Geophysical and Geochemical Signals in the Subsurface PDF icon Grand Challenge Workshop -Imaging Subsurface.pdf More Documents & Publications AGU SubTER Town Hall Presentation 2015 SubTER Fact Sheet SubTER Presentation at Town Hall - American Geophysical Union

  8. Saft America Advanced Batteries Plant Celebrates Grand Opening in

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Jacksonville | Department of Energy Saft America Advanced Batteries Plant Celebrates Grand Opening in Jacksonville Saft America Advanced Batteries Plant Celebrates Grand Opening in Jacksonville September 16, 2011 - 12:30pm Addthis Department of Energy Investment Helps Support Job Creation, U.S. Economic Competitiveness and Advanced Vehicle Industry WASHINGTON, D.C. - Today, Secretary Steven Chu joined with Saft America to announce the grand opening of the company's Jacksonville, Florida,

  9. Grand Opening of Abengoa's Biorefinery: Nation's Third Commercial-Scale

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Facility | Department of Energy Grand Opening of Abengoa's Biorefinery: Nation's Third Commercial-Scale Facility Grand Opening of Abengoa's Biorefinery: Nation's Third Commercial-Scale Facility October 17, 2014 - 11:42am Addthis Photo courtesy of Abengoa Photo courtesy of Abengoa The nation's third commercial-scale cellulosic ethanol biorefinery celebrates its grand opening on October 17, 2014, in Hugoton, Kansas. The Abengoa Bioenergy Biomass of Kansas (ABBK) facility is the first of its

  10. DOE Announces Awardees for the Industrial Energy Efficiency Grand Challenge

    Energy Savers [EERE]

    | Department of Energy Awardees for the Industrial Energy Efficiency Grand Challenge DOE Announces Awardees for the Industrial Energy Efficiency Grand Challenge May 5, 2010 - 12:00am Addthis WASHINGTON, DC - The U.S. Department of Energy announced today that 48 research and development projects across the country have been selected as award winners of the Industrial Energy Efficiency Grand Challenge. The grantees will receive a total of $13 million to fund the development of transformational

  11. EV Everywhere EV Everywhere Grand Challenge - Electric Drive (Power

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Electronics and Electric Machines) Workshop Agenda | Department of Energy EV Everywhere Grand Challenge - Electric Drive (Power Electronics and Electric Machines) Workshop Agenda EV Everywhere EV Everywhere Grand Challenge - Electric Drive (Power Electronics and Electric Machines) Workshop Agenda Agenda for the EV Everywhere Grand Challenge - Electric Drive Workshop on July 24, 2012 at the Doubletree O'Hare, Chicago, IL PDF icon agenda_ed.pdf More Documents & Publications EV Everywhere

  12. EV Everywhere Grand Challenge Kick-Off | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Off EV Everywhere Grand Challenge Kick-Off Agenda for the EV Everywhere Grand Challenge Kick-Off meeting held on June 21, 2012 at the Hyatt Regency, Dearborn, MI PDF icon framing_workshop_agenda_062112.pdf More Documents & Publications EV Everywhere Grand Challenge Overview Presentation EV Everywhere Framing Workshop - Report Out & Lessons Learned EV Everywhere Framing Workshop Report Out & Lessons Learned

  13. EV Everywhere Grand Challenge: Consumer Acceptance and Charging

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Infrastructure Workshop Agenda | Department of Energy Agenda EV Everywhere Grand Challenge: Consumer Acceptance and Charging Infrastructure Workshop Agenda Agenda for the EV Everywhere Grand Challenge: Consumer Acceptance and Charging Infrastructure Workshop on July 30, 2012 held at the LAX Marriott, Los Angeles, CA PDF icon agenda_caci.pdf More Documents & Publications EV Everywhere Consumer Acceptance and Charging Infrastructure Workshop - Backsplash EV Everywhere Grand Challenge:

  14. The Bowersock Mills and Power Company 1874

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Incremental Hydroelectric Energy The Bowersock Mills and Power Co., Lawrence, KS Hydroelectric Energy Potential for U.S. BMPC Plant At Forefront of Development Curve "In our estimates we have about 70 GW of additional hydro which would have minimal impact; and so where does this come from? It comes from putting in better turbines in existing dams, it comes from run-of-the-river turbines that don't create the minimal environmental impact and it comes from using water storage that was made

  15. Winning the Future: Grand Ronde Solar Projects Reduce Pollution...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    coastal range, the Confederated Tribes of the Grand Ronde Community of Oregon has a strong connection to the earth and nature and a deep commitment to environmental stewardship. ...

  16. EV Everywhere Grand Challenge- Charge to the Breakout Groups

    Broader source: Energy.gov [DOE]

    Presentation given at the EV Everywhere Grand Challenge: Battery Workshop on July 26, 2012 held at the Doubletree O'Hare, Chicago, IL.

  17. Grand Junction Office Founder Honored at the Philip C. Leahy...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Junction, Colorado, Office to commemorate its place in the Manhattan Project and Cold War histories. The park, located in the middle of the Grand Junction Office campus, was...

  18. Grand Opening of Abengoa's Biorefinery: Nation's Third Commercial...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    of Abengoa Photo courtesy of Abengoa The nation's third commercial-scale cellulosic ethanol biorefinery celebrates its grand opening on October 17, 2014, in Hugoton, Kansas. The...

  19. Alpine Extensional Detachment Tectonics In The Grande Kabylie...

    Open Energy Info (EERE)

    Extensional Detachment Tectonics In The Grande Kabylie Metamorphic Core Complex Of The Maghrebides (Northern Algeria) Jump to: navigation, search OpenEI Reference LibraryAdd to...

  20. EV Everywhere Grand Challenge: Consumer Acceptance and Charging...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Attnedance list for the EV Everywhere Grand Challenge: Consumer Acceptance and Charging Infrastructure Workshop on July 30, 2012 held at the LAX Marriott, Los Angeles, CA PDF icon ...

  1. EV Everywhere Grand Challenge: Consumer Acceptance and Charging...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Agenda for the EV Everywhere Grand Challenge: Consumer Acceptance and Charging Infrastructure Workshop on July 30, 2012 held at the LAX Marriott, Los Angeles, CA PDF icon ...

  2. Grand Rapids Public Util Comm | Open Energy Information

    Open Energy Info (EERE)

    https:www.facebook.compagesGrand-Rapids-Public-Utilities108782819203449?skwall Outage Hotline: 218-326-4806 References: EIA Form EIA-861 Final Data File for 2010 -...

  3. City of Grand Junction, Iowa (Utility Company) | Open Energy...

    Open Energy Info (EERE)

    Iowa (Utility Company) Jump to: navigation, search Name: Grand Junction Municipal Utilities Place: Iowa Phone Number: (515) 738-2285 or (515) 738-2726 Facebook: https:...

  4. Rio Grande County, Colorado: Energy Resources | Open Energy Informatio...

    Open Energy Info (EERE)

    B. Places in Rio Grande County, Colorado Center, Colorado Del Norte, Colorado Monte Vista, Colorado South Fork, Colorado Retrieved from "http:en.openei.orgw...

  5. Sierra Grande Lodge Pool & Spa Low Temperature Geothermal Facility...

    Open Energy Info (EERE)

    Spa Low Temperature Geothermal Facility Facility Sierra Grande Lodge Sector Geothermal energy Type Pool and Spa Location Truth or Consequences, New Mexico Coordinates 33.1284047,...

  6. Sandia Energy - SunShot Grand Challenge: Regional Test Centers

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Challenge: Regional Test Centers Home Videos Renewable Energy Energy Events News SunShot News & Events Photovoltaic Solar SunShot Grand Challenge: Regional Test Centers Previous...

  7. Field Studies of Geothermal Reservoirs: Rio Grande Rift, New...

    Open Energy Info (EERE)

    Abstract The Rio Grande rift provides an excellent field laboratory to study the nature of geothermal systems in an extensional environment. Much of the geologic complexity...

  8. EV Everywhere Grand Challenge - Battery Status and Cost Reduction...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Status and Cost Reduction Prospects EV Everywhere Grand Challenge - Battery Status and Cost Reduction Prospects Presentation given by technology manager David Howell at the EV...

  9. Summary of Grand Challenge Products Selected for Award Negotiations

    SciTech Connect (OSTI)

    2010-04-26

    DOE provides $13 million in funding to 48 research and development projects across the country that were selected as award winners of the Industrial Energy Efficiency Grand Challenge.

  10. EV Everywhere EV Everywhere Grand Challenge - Electric Drive...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    - Electric Drive (Power Electronics and Electric Machines) Workshop Agenda EV Everywhere EV Everywhere Grand Challenge - Electric Drive (Power Electronics and Electric Machines) ...

  11. EV Everywhere Grand Challenge - Electric Drive (Power Electronics...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    - Electric Drive (Power Electronics and Electric Machines) Workshop EV Everywhere Grand Challenge - Electric Drive (Power Electronics and Electric Machines) Workshop List of ...

  12. EV Everywhere Grand Challenge Introduction for Electric Drive...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Presentation given by EERE Assistant Secretary David Danielson at the EV Everywhere Grand Challenge - Electric Drive (Power Electronics and Electric Machines) Workshop on July 24, ...

  13. Grand Junction, Colorado: Energy Resources | Open Energy Information

    Open Energy Info (EERE)

    district.12 Registered Energy Companies in Grand Junction, Colorado Ruby Canyon Engineering Inc References US Census Bureau Incorporated place and minor civil...

  14. Grand Blanc, Michigan: Energy Resources | Open Energy Information

    Open Energy Info (EERE)

    5th congressional district.12 Registered Energy Companies in Grand Blanc, Michigan 21st century Green Solutions LLC References US Census Bureau Incorporated place and...

  15. Otter Tail Power Company- Commercial & Industrial Energy Efficiency Rebate Program

    Broader source: Energy.gov [DOE]

    Information regarding rebate program eligibility and product and equipment requirements may be found on the web site listed above. Contact Otter Tail Power Company for more information on this ...

  16. A note on trans-Planckian tail effects

    SciTech Connect (OSTI)

    Graef, L.L.; Brandenberger, R.

    2015-09-09

    We study the proposal by Mersini et al. http://dx.doi.org/10.1103/PhysRevD.64.043508 that the observed dark energy might be explained by the back-reaction of the set of tail modes in a theory with a dispersion relation in which the mode frequency decays exponentially in the trans-Planckian regime. The matter tail modes are frozen out, however they induce metric fluctuations. The energy-momentum tensor with which the tail modes effect the background geometry obtains contributions from both metric and matter fluctuations. We calculate the equation of state induced by the tail modes taking into account the gravitational contribution. We find that, in contrast to the case of frozen super-Hubble cosmological fluctuations, in this case the matter perturbations dominate, and they yield an equation of state which to leading order takes the form of a positive cosmological constant.

  17. Otter Tail Power Company- Residential Energy Efficiency Rebate Program

    Broader source: Energy.gov [DOE]

    Information regarding rebate program eligibility and product and equipment requirements may be found on the web site listed above. Contact Otter Tail Power Company for more information on this pr...

  18. Western Red-tailed Skink Distribution in Southern Nevada

    SciTech Connect (OSTI)

    Hall, D. B. and Gergor, P. D.

    2011-11-01

    This slide show reports a study to: determine Western Red-tailed Skink (WRTS) distribution on Nevada National Security Site (NNSS); identify habitat where WRTS occur; learn more about WRTS natural history; and document distribution of other species.

  19. Otter Tail Ag Enterprises LLC | Open Energy Information

    Open Energy Info (EERE)

    Enterprises LLC Jump to: navigation, search Name: Otter Tail Ag Enterprises LLC Place: Fergua Falls, Minnesota Zip: 56537-7518 Product: Developed a 55m gallon ethanol facility in...

  20. Otter Tail Power Company - Dollar Smart Financing Program | Department...

    Broader source: Energy.gov (indexed) [DOE]

    Customers who have satisfactory 12-month payment histories with Otter Tail or another utility may use the 8.5% interest rate loan to finance purchases of new electric...

  1. EA-33-A and PP-33-1 Rio Grande Electric Cooperative, Inc. | Department of

    Energy Savers [EERE]

    Energy -A and PP-33-1 Rio Grande Electric Cooperative, Inc. EA-33-A and PP-33-1 Rio Grande Electric Cooperative, Inc. Order authorizing Rio Grande Electric Cooperative, Inc to export electric energy to Mexico PDF icon EA-33-A and PP-33-1 Rio Grande Electric Cooperative, Inc. More Documents & Publications PP-33-1 and EA-33-A Rio Grande Electric Cooperative Inc PP-53 Rio Grande Electric Cooperative, Inc. EA-288 Vermont

  2. EV Everywhere Grand Challenge Blueprint | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    EV Everywhere Grand Challenge Blueprint EV Everywhere Grand Challenge Blueprint Recognizing that vehicle electrification is an essential part of our countrys "all-of-the above" energy strategy, President Obama issued the EV Everywhere Grand Challenge to the nation in March 2012 with the bold goal to be the first nation in the world to produce plug-in electric vehicles that are as affordable for the average American family as todays gasoline-powered vehicles within the next 10

  3. gjpip.PDF

    Office of Legacy Management (LM)

    GWGRJ 7.1 Public Involvement Plan for the Environmental Assessment of Ground Water Compliance at the Grand Junction Uranium Mill Tailings Remedial Action (UMTRA) Project Site (Climax Uranium Millsite) July 1999 Prepared by U.S. Department of Energy Grand Junction Office Grand Junction, Colorado Work performed under DOE Contract No. DE-AC13-96GJ8733 Public Involvement Plan July 1999 Page 1 Public Involvement Plan for the Environmental Assessment of Ground Water Compliance at the Grand Junction,

  4. Spring Mills, Pennsylvania: Energy Resources | Open Energy Information

    Open Energy Info (EERE)

    Hide Map This article is a stub. You can help OpenEI by expanding it. Spring Mills is a census-designated place in Centre County, Pennsylvania.1 References ...

  5. Mill City, Oregon: Energy Resources | Open Energy Information

    Open Energy Info (EERE)

    is a stub. You can help OpenEI by expanding it. Mill City is a city in Linn County and Marion County, Oregon. It falls under Oregon's 4th congressional district and Oregon's 5th...

  6. Kemp Mill, Maryland: Energy Resources | Open Energy Information

    Open Energy Info (EERE)

    stub. You can help OpenEI by expanding it. Kemp Mill is a census-designated place in Montgomery County, Maryland.1 References US Census Bureau 2005 Place to 2006 CBSA...

  7. Mill Valley, California: Energy Resources | Open Energy Information

    Open Energy Info (EERE)

    Hide Map This article is a stub. You can help OpenEI by expanding it. Mill Valley is a city in Marin County, California. It falls under California's 6th...

  8. Anderson Mill, Texas: Energy Resources | Open Energy Information

    Open Energy Info (EERE)

    Hide Map This article is a stub. You can help OpenEI by expanding it. Anderson Mill is a census-designated place in Travis County and Williamson County, Texas.1...

  9. EA-1037: Uranium Lease Management Program, Grand Junction, Colorado

    Broader source: Energy.gov [DOE]

    This EA evaluates the environmental impacts of the U.S. Department of Energy's Grand Junction Projects Office's proposal to maintain and preserve the nation's immediately accessible supply of...

  10. Arroyo Grande, California: Energy Resources | Open Energy Information

    Open Energy Info (EERE)

    This article is a stub. You can help OpenEI by expanding it. Arroyo Grande is a city in San Luis Obispo County, California. It falls under California's 22nd congressional...

  11. Grand Forks County, North Dakota: Energy Resources | Open Energy...

    Open Energy Info (EERE)

    Dakota. Its FIPS County Code is 035. It is classified as ASHRAE 169-2006 Climate Zone Number 7 Climate Zone Subtype A. Registered Energy Companies in Grand Forks County, North...

  12. Casa Grande, Arizona: Energy Resources | Open Energy Information

    Open Energy Info (EERE)

    Hide Map This article is a stub. You can help OpenEI by expanding it. Casa Grande is a city in Pinal County, Arizona. It falls under Arizona's 1st congressional...

  13. City of Grand Rapids- Green Power Purchasing Policy

    Broader source: Energy.gov [DOE]

    In 2005, the City of Grand Rapids established a goal of purchasing 20% of its municipal power demand from renewable energy by 2008. In November 2007, the city signed a three-year agreement with a...

  14. 2014 SunShot Grand Challenge Summit Opening Session Photos |...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Anaheim Mayor Tom Tait with SunShot Director Minh Le Credit: SunShot Initiative Date ... SunShot Grand Challenge Summit Opening Session SunShot Director Minh Le Credit: SunShot ...

  15. Evaluation of Geothermal Potential of Rio Grande Rift and Basin...

    Open Energy Info (EERE)

    to: navigation, search OpenEI Reference LibraryAdd to library Report: Evaluation of Geothermal Potential of Rio Grande Rift and Basin and Range Province, New Mexico Abstract A...

  16. EV Everywhere Grand Challenge Overview | Department of Energy

    Office of Environmental Management (EM)

    3_davis_caci.pdf More Documents & Publications EV Everywhere Framing Workshop Report Out & Lessons Learned EV Everywhere Framing Workshop - Report Out & Lessons Learned EV Everywhere Grand Challenge - Charge to the Breakout Groups

  17. Summer 2011 Intern Project- Carolyn Mills | Center for Energy Efficient

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Materials Carolyn Mills ELECTRICITY FROM HEAT: SYNTHESIS AND INVNESTIGATION OF INTERMETALLIC HETEROSTRUCTURES Carolyn Mills Chemical Engineering UC Santa Barbara Mentor: Christina Birkel Faculty Advisor: Galen Stucky Department: Chemistry and Biochemistry Thermoelectric materials have the ability to convert between thermal and electrical energies. However, to maximize ZT, the thermoelectric figure of merit, a material must have a high Seebeck coefficient and a high electrical conductivity

  18. Modelling and Development of a High Performance Milling Process with

    Office of Scientific and Technical Information (OSTI)

    Monolithic Cutting Tools (Journal Article) | SciTech Connect Modelling and Development of a High Performance Milling Process with Monolithic Cutting Tools Citation Details In-Document Search Title: Modelling and Development of a High Performance Milling Process with Monolithic Cutting Tools Critical aerospace components usually require difficult to machine workpiece materials like nickel based alloys. Moreover; there is a pressing need to maximize the productivity of machining operations.

  19. Biomass Burner Cogenerates Jobs and Electricity from Lumber Mill Waste |

    Energy Savers [EERE]

    Department of Energy Burner Cogenerates Jobs and Electricity from Lumber Mill Waste Biomass Burner Cogenerates Jobs and Electricity from Lumber Mill Waste December 6, 2011 - 3:57pm Addthis Dale and Sharon Borgford, small business owners in Stevens County, WA, break ground with Peter Goldmark, Washington State Commissioner of Public Lands. The pair brought more than 75 jobs to the area with help from DOE's State Energy Program and the U.S. Forest Service. | Photo courtesy of Washington DNR.

  20. DOE - Office of Legacy Management -- Loma Mill - CO 03

    Office of Legacy Management (LM)

    Loma Mill - CO 03 FUSRAP Considered Sites Site: Loma Mill (CO.03 ) Designated Name: Alternate Name: Location: Evaluation Year: Site Operations: Site Disposition: Radioactive Materials Handled: Primary Radioactive Materials Handled: Radiological Survey(s): Site Status: This site is one of a group of 77 FUSRAP considered sites for which few, if any records are available in their respective site files to provide an historical account of past operations and their relationship, if any, with MED/AEC

  1. DOE - Office of Legacy Management -- Cincinnati Milling and Machining Co -

    Office of Legacy Management (LM)

    OH 25 Cincinnati Milling and Machining Co - OH 25 FUSRAP Considered Sites Site: Cincinnati Milling & Machining Co. (OH.25 ) Eliminated from consideration under FUSRAP - Referred to NRC Designated Name: Not Designated Alternate Name: None Location: Cincinnati , Ohio OH.25-1 Evaluation Year: 1990 OH.25-2 OH.25-3 Site Operations: Performed research and development concerning electro-chemical machining units in the 1960s. OH.25-1 Site Disposition: Eliminated - Potential for contamination

  2. Fernald Preserve Visitors Center Grand Opening and LEED Platinum

    Energy Savers [EERE]

    Certification | Department of Energy Fernald Preserve Visitors Center Grand Opening and LEED Platinum Certification Fernald Preserve Visitors Center Grand Opening and LEED Platinum Certification October 16, 2008 - 4:14pm Addthis Remarks as Prepared for Acting Deputy Secretary Kupfer Thank you, Mike, for that introduction and to both you and Jane for hosting this event. You both have been instrumental in the dramatic transformation of this site. We made a commitment more than a decade ago to

  3. Electrolyte pore/solution partitioning by expanded grand canonical ensemble

    Office of Scientific and Technical Information (OSTI)

    Monte Carlo simulation (Journal Article) | SciTech Connect Title: Electrolyte pore/solution partitioning by expanded grand canonical ensemble Monte Carlo simulation Using a newly developed grand canonical Monte Carlo approach based on fractional exchanges of dissolved ions and water molecules, we studied equilibrium partitioning of both components between laterally extended apolar confinements and surrounding electrolyte solution. Accurate calculations of the Hamiltonian and tensorial

  4. EV Everywhere Grand Challenge - Battery Status and Cost Reduction Prospects

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    | Department of Energy Status and Cost Reduction Prospects EV Everywhere Grand Challenge - Battery Status and Cost Reduction Prospects Presentation given by technology manager David Howell at the EV Everywhere Grand Challenge: Battery Workshop on July 26, 2012 held at the Doubletree O'Hare, Chicago, IL. PDF icon 5_howell_b.pdf More Documents & Publications PHEV Battery Cost Assessment Overview of Battery R&D Activities Overview of Battery R&D Activities

  5. EV Everywhere Grand Challenge - Charging Infrastructure Enabling Flexible

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    EV Design | Department of Energy Charging Infrastructure Enabling Flexible EV Design EV Everywhere Grand Challenge - Charging Infrastructure Enabling Flexible EV Design Presentation given at the EV Everywhere Grand Challenge: Consumer Acceptance and Charging Infrastructure Workshop on July 30, 2012 held at the LAX Marriott, Los Angeles, CA PDF icon 5_slezak_caci.pdf More Documents & Publications EV Everywhere Framing Workshop - Report Out & Lessons Learned EV Everywhere Framing

  6. EV Everywhere Grand Challenge - Electric Drive (Power Electronics and

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Electric Machines) Workshop | Department of Energy - Electric Drive (Power Electronics and Electric Machines) Workshop EV Everywhere Grand Challenge - Electric Drive (Power Electronics and Electric Machines) Workshop List of companies in attendance at the Electric Drive Workshop held on July 24, 2012 at the Doubletree O'Hare, Chicago, IL PDF icon companies_in_attendance_ed.pdf More Documents & Publications EV Everywhere Grand Challenge Introduction for Electric Drive Workshop EV

  7. EV Everywhere Grand Challenge: Consumer Acceptance and Charging

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Infrastructure Workshop Attendence List | Department of Energy Attendence List EV Everywhere Grand Challenge: Consumer Acceptance and Charging Infrastructure Workshop Attendence List Attnedance list for the EV Everywhere Grand Challenge: Consumer Acceptance and Charging Infrastructure Workshop on July 30, 2012 held at the LAX Marriott, Los Angeles, CA PDF icon companies_in_attendance_caci.pdf More Documents & Publications EV Everywhere Consumer Acceptance and Charging Infrastructure

  8. SubTER Grand Challenge Roundtable: Imaging Geophysical and

    Energy Savers [EERE]

    SubTER Grand Challenge Roundtable: Imaging Geophysical and Geochemical Signals in the Subsurface The Grand Challenge SubTER Panel (Dr. Marcia McNutt, Chair) DOE Leads: Margaret Coleman, Julio Friedmann, Doug Hollett, and Harriet Kung Introduction The future of the world's energy production and deployment is closely tied to our understanding of the subsurface, as well as our capabilities in subsurface or geologic engineering. Developments over the past ten years, including the growth of natural

  9. Grand Challenge Winning Entry Proposes Efficiencies to Tank Waste Cleanup |

    Energy Savers [EERE]

    Department of Energy Grand Challenge Winning Entry Proposes Efficiencies to Tank Waste Cleanup Grand Challenge Winning Entry Proposes Efficiencies to Tank Waste Cleanup December 29, 2015 - 12:55pm Addthis From left, Elaine Diaz, Office of River Protection (ORP) acting chief engineer; John Vienna, Pacific Northwest National Laboratory scientist; Albert Kruger, ORP glass scientist; and Kevin Smith, ORP manager. From left, Elaine Diaz, Office of River Protection (ORP) acting chief engineer;

  10. Grand Challenges: Request for Information on the Subsurface | Department of

    Office of Environmental Management (EM)

    Energy Grand Challenges: Request for Information on the Subsurface Grand Challenges: Request for Information on the Subsurface May 14, 2014 - 4:10pm Addthis Subsurface reservoirs account for more than 80% of U.S. primary energy, and they offer vast potential for the storage of energy, CO2, and nuclear waste. Finding and effectively exploiting these resources while mitigating impacts of their use constitute major technical and socio-political challenges and opportunities. Next generation

  11. Montage Builders Northern Forest, Ryerson University Selected as Grand

    Office of Environmental Management (EM)

    Winners of First Student Design Competition for Zero Energy Ready Homes | Department of Energy Montage Builders Northern Forest, Ryerson University Selected as Grand Winners of First Student Design Competition for Zero Energy Ready Homes Montage Builders Northern Forest, Ryerson University Selected as Grand Winners of First Student Design Competition for Zero Energy Ready Homes April 29, 2014 - 2:15pm Addthis To help cut energy waste and improve U.S. energy productivity, the Energy

  12. Compressed Air System Optimization Saves Energy and Improves Production at a Textile Manufacturing Mill (Peerless Division, Thomastown Mills, Inc.)

    SciTech Connect (OSTI)

    2001-06-01

    This case study is one in a series on industrial firms who are implementing energy efficient technologies and system improvements into their manufacturing processes. This case study documents the activities, savings, and lessons learned on the textile manufacturing mill project.

  13. EA-1338: Transfer of the Department of Energy Grand Junction Office to Non-DOE Ownership, Grand Junction, Colorado

    Broader source: Energy.gov [DOE]

    This EA evaluates the environmental impacts for the proposed transfer of real and personal property at the U.S. Department of Energy's Grand Junction Office to non-DOE ownership.

  14. Head-Tail Modes for Strong Space Charge

    SciTech Connect (OSTI)

    Burov, Alexey

    2008-12-01

    Head-tail modes are described here for the space charge tune shift significantly exceeding the synchrotron tune. General equation for the modes is derived. Spatial shapes of the modes, their frequencies, and coherent growth rates are explored. The Landau damping rates are also found. Suppression of the transverse mode coupling instability by the space charge is explained.

  15. MMTSAlt

    Office of Legacy Management (LM)

    Grand Junction Office This fact sheet summarizes the Alternatives Analysis Report which identifies and evaluates cleanup alternatives for soil and sediment adjacent to Montezuma Creek, which is part of Operable Unit (OU) III of the Monticello Mill Tailings Site. The OU III soil and sediment area has been divided into three segments: Upper, Middle, and Lower Montezuma Creek. Alternatives and recommended removal actions were developed separately for each segment. Monticello Mill Tailings

  16. NatPriorLst

    Office of Legacy Management (LM)

    February 1999 United States Department of Energy Grand Junction Office The U.S. Department of Energy has prepared this Fact Sheet to explain why supplemental standards are proposed for certain properties in the Monticello Vicinity Properties (MVP) Site and Monticello Mill Tailings Site (MMTS). The supplemental standards establish cleanup standards for soil contaminated with uranium mill tailings and uranium ore based on an evaluation of risk for specific exposure scenarios. The supplemental

  17. PP-33-1 and EA-33-A Rio Grande Electric Cooperative Inc | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy -1 and EA-33-A Rio Grande Electric Cooperative Inc PP-33-1 and EA-33-A Rio Grande Electric Cooperative Inc Rescission of Presidential Permit and Electricity Export Authorization for Rio Grande Electric Cooperative to Export electricity to Mexico. PDF icon PP-33-1 and EA-33-A Rio Grande Electric Cooperative Inc More Documents & Publications EA-33-A and PP-33-1 Rio Grande Electric Cooperative, Inc. PP-53 Rio Grande Electric Cooperative, Inc. PP-33 Rio Grande Electric Cooperative Inc

  18. Analyzing the performance of diamond-coated micro end mills.

    SciTech Connect (OSTI)

    Torres, C. D.; Heaney, P. J.; Sumant, A. V.; Hamilton, M. A.; Carpick, R. W.; Pfefferkorn, F. E.; Univ. of Wisconsin at Madison; Univ. of Pennsylvania

    2009-06-01

    A method is presented to improve the tool life and cutting performance of 300 {micro}m diameter tungsten carbide (WC) micro end mills by applying thin (<300 nm) fine-grained diamond (FGD) and nanocrystalline diamond (NCD) coatings using the hot-filament chemical vapor deposition (HF-CVD) process. The performance of the diamond-coated tools has been evaluated by comparing their performance in dry slot milling of 6061-T6 aluminum against uncoated WC micro end mills. Tool wear, coating integrity, and chip morphology were characterized using SEM and white light interferometry. The initial test results show a dramatic improvement in the tool integrity (i.e., corners not breaking off), a lower wear rate, no observable adhesion of aluminum to the diamond-coated tool, and a significant reduction in the cutting forces (>50%). Reduction of the cutting forces is attributed to the low friction and adhesion of the diamond coating. However, approximately 80% of the tools coated with the larger FGD coatings failed during testing due to delamination. Additional machining benefits were attained for the NCD films, which was obtained by using a higher nucleation density seeding process for diamond growth. This process allowed for thinner, smaller grained diamond coatings to be deposited on the micro end mills, and enabled continued operation of the tool even after the integrity of the diamond coating had been compromised. As opposed to the FGD-coated end mills, only 40% of the NCD-tools experienced delamination issues.

  19. Particle size and shape distributions of hammer milled pine

    SciTech Connect (OSTI)

    Westover, Tyler Lott; Matthews, Austin Colter; Williams, Christopher Luke; Ryan, John Chadron Benjamin

    2015-04-01

    Particle size and shape distributions impact particle heating rates and diffusion of volatized gases out of particles during fast pyrolysis conversion, and consequently must be modeled accurately in order for computational pyrolysis models to produce reliable results for bulk solid materials. For this milestone, lodge pole pine chips were ground using a Thomas-Wiley #4 mill using two screen sizes in order to produce two representative materials that are suitable for fast pyrolysis. For the first material, a 6 mm screen was employed in the mill and for the second material, a 3 mm screen was employed in the mill. Both materials were subjected to RoTap sieve analysis, and the distributions of the particle sizes and shapes were determined using digital image analysis. The results of the physical analysis will be fed into computational pyrolysis simulations to create models of materials with realistic particle size and shape distributions. This milestone was met on schedule.

  20. New Claus tail-gas process proved in German operation

    SciTech Connect (OSTI)

    Kettner, R.; Liermann, N.

    1988-01-11

    A process for removing sulfur components from Claus-plant tail gases increases sulfur-recovery rates to 99.5%. It has been in use for more than 4 years. In December 1983, a tail-gas cleaning unit was started up for the sulfur-recovery plants of the Nordeutsche Erdgas Aufbereitungsgesellschaft (NEAG) natural-gas treating complex at Voigten, West Germany. NEAG, a joint venture of Exxon, Shell, and Mobil Oil, desulfurizes 7.7 million normal cu m/day (approximately 271.2 million cfd) of sour gas in three plants. Up to 1,050 tons/day of elemental sulfur are produced (Fig. 1). Mobil Oil AG developed the process which has been dubbed the Mobil direct-oxidation process (Modop).

  1. Fermentation and chemical treatment of pulp and paper mill sludge

    DOE Patents [OSTI]

    Lee, Yoon Y; Wang, Wei; Kang, Li

    2014-12-02

    A method of chemically treating partially de-ashed pulp and/or paper mill sludge to obtain products of value comprising taking a sample of primary sludge from a Kraft paper mill process, partially de-ashing the primary sludge by physical means, and further treating the primary sludge to obtain the products of value, including further treating the resulting sludge and using the resulting sludge as a substrate to produce cellulase in an efficient manner using the resulting sludge as the only carbon source and mixtures of inorganic salts as the primary nitrogen source, and including further treating the resulting sludge and using the resulting sludge to produce ethanol.

  2. Milling of Sand Blocks to Make Casting Moulds

    SciTech Connect (OSTI)

    Lopez de Lacalle, L. N.; Rodriguez, A.; Lamikiz, A.; Penafiel, F. J. [Department of Mechanical Engineering, University of the Basque Country, ETSII, c/Alameda de Urquijo s/n, 48013 Bilbao (Spain)

    2011-01-17

    In this paper a full procedure to make moulds in sand for direct casting of metallic parts is presented. The technology aims at unique pieces or art pieces, where only one prototype or components is required, but lead times are much reduced. The key of the procedure is to achieve enough tool life when milling with carbide tools, avoiding the risk of sand destruction or damage.The use of inverse techniques is a common input due to the industrial sectors where the direct milling is interesting. Two examples of moulds are presented, evaluating times and costs. A special study of tool wear is also presented.

  3. Longest-Serving Active Paper Mill in the Western United States...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    While the mill does not have a formal energy man- agement policy, energy efficiency is a strong priority. In the late 1990s the mill's steam load averaged nearly 200,000 lbshour....

  4. Grand Traverse Band of Ottawa and Chippewa Indians- 2005 Project

    Broader source: Energy.gov [DOE]

    The Grand Traverse Band of Ottawa and Chippewa Indians (GTB) will conduct a feasibility study to determine the cost effectiveness and other economic, environmental, cultural, and social benefits of maximizing the diversity of energy sources used at GTB facilities. This includes an assessment of energy conservation measures as well as renewable energy sources such as wind, solar, and biomass.

  5. Mesa Grande Band of Mission Indians- 2004 Project

    Broader source: Energy.gov [DOE]

    The Mesa Grande Band of Mission Indians, located in northern San Diego County, will conduct a study of the feasibility of reducing air pollution generated on the reservation by an over-reliance on wood-burning stoves, kerosene heaters, and gasoline generators, and to identify the types of renewable energy systems that could be used for residential structures and well-pump systems.

  6. Grand Challenges of Characterization & Modeling of Cellulose Nanomaterials

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Grand Challenges of Characterization & Modeling of Cellulose Nanomaterials Robert Moon Adjunct Assistant Professor Materials Engineering Purdue University Materials Research Engineer US Forest Service Forest Products Laboratory DOE- Sustainable Nanomaterials Workshop, 26 June, 2012 Cellulose Nanomaterials (CN) 2 * Influence: * Cellulose Source * Extraction Process * Two Particle Morphologies: * Rod: CNC, NCC, NCW, NCXLS * Fibrillar: CNF, NFC, MFC, BC, AC * Questions: * What to Characterize?

  7. 2014 SunShot Grand Challenge Summit Opening Session Photos | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy 2014 SunShot Grand Challenge Summit Opening Session Photos 2014 SunShot Grand Challenge Summit Opening Session Photos Addthis SunShot Grand Challenge Summit Opening Session 1 of 35 SunShot Grand Challenge Summit Opening Session Anaheim Mayor Tom Tait with SunShot Director Minh Le Credit: SunShot Initiative Date taken: 2014-05-19 16:01 SunShot Grand Challenge Summit Opening Session 2 of 35 SunShot Grand Challenge Summit Opening Session SunShot Director Minh Le Credit: SunShot

  8. DOE - Office of Legacy Management -- Lakeview Mill - OR 0-01

    Office of Legacy Management (LM)

    Lakeview Mill - OR 0-01 FUSRAP Considered Sites Site: Lakeview Mill (OR.0-01) Designated Name: Alternate Name: Location: Evaluation Year: Site Operations: Site Disposition: Radioactive Materials Handled: Primary Radioactive Materials Handled: Radiological Survey(s): Site Status: Also see Lakeview, Oregon, Processing Site Documents Related to Lakeview Mill

  9. DOE - Office of Legacy Management -- Belfield Mill Site - ND 0-01

    Office of Legacy Management (LM)

    Belfield Mill Site - ND 0-01 FUSRAP Considered Sites Site: Belfield Mill Site (ND.0-01 ) Designated Name: Alternate Name: Location: Evaluation Year: Site Operations: Site Disposition: Radioactive Materials Handled: Primary Radioactive Materials Handled: Radiological Survey(s): Site Status: Also see http://www.em.doe.gov/SiteInfo/BelfieldAshingFacility.aspx Documents Related to Belfield Mill Site

  10. DOE - Office of Legacy Management -- Bowman Mill Site - ND 0-02

    Office of Legacy Management (LM)

    Bowman Mill Site - ND 0-02 FUSRAP Considered Sites Site: Bowman Mill Site (ND.0-02 ) Designated Name: Alternate Name: Location: Evaluation Year: Site Operations: Site Disposition: Radioactive Materials Handled: Primary Radioactive Materials Handled: Radiological Survey(s): Site Status: Also see http://www.em.doe.gov/SiteInfo/BowmanAshingFacility.aspx Documents Related to Bowman Mill Site

  11. Woolen mill captures exhaust to cut fuel costs

    SciTech Connect (OSTI)

    Not Available

    1986-02-01

    To keep ahead of growing competition, a northeast woolen mill sought a method of reducing fuel costs while increasing production. A counterflow-design plate heat exchanger was employed to recirculate dryer exhaust. It has cut propane consumption from 4900 to 2400 gallons a week while design modifications have doubled dryer speed. The heat recovery system is described.

  12. Boise Inc. St. Helens Paper Mill Achieves Significant Fuel Savings

    Broader source: Energy.gov [DOE]

    This case study describes how the Boise Inc. paper mill in St. Helens, Oregon, achieved annual savings of approximately 154,000 MMBtu and more than $1 million. This was accomplished after receiving a DOE energy assessment and implementing recommendations to improve the efficiency of its steam system.

  13. Perturbation Theory of Massive Yang-Mills Fields

    DOE R&D Accomplishments [OSTI]

    Veltman, M.

    1968-08-01

    Perturbation theory of massive Yang-Mills fields is investigated with the help of the Bell-Treiman transformation. Diagrams containing one closed loop are shown to be convergent if there are more than four external vector boson lines. The investigation presented does not exclude the possibility that the theory is renormalizable.

  14. Remediation of former uranium mining and milling activities in Central Asia

    SciTech Connect (OSTI)

    Waggitt, Peter

    2007-07-01

    Available in abstract form only. Full text of publication follows: Several of the Central Asian countries of the former Soviet Union were involved in the uranium mining and milling industry from about 1945 for varying periods until the break up of the Soviet Union in 1991 and beyond. Some facilities are still producing in Uzbekistan and Kazakhstan. However, before the break up, many facilities had been abandoned and in only a few cases had any remediation been undertaken. Since 1991 the newly independent states of the region have been seeking assistance for the remediation of the multitude of tailings piles, waste rock stockpiles and abandoned, and often semi dismantled, production facilities that may be found throughout the region. Many of these sites are close to settlements that were established as service towns for the mines. Most towns still have populations, although the mining industry has departed. In some instances there are cases of pollution and contamination and in many locations there is a significant level of public concern. The IAEA has been undertaking a number of Technical Cooperation (TC) projects throughout the region for some time to strengthen the institutions in the relevant states and assist them to establish monitoring and surveillance programs as an integral part of the long term remediation process. The IAEA is liaising with other agencies and donors who are also working on these problems to optimise the remediation effort. The paper describes the objectives and operation of the main TC regional program, liaison efforts with other agencies, the achievements so far and the long term issues for remediation of these legacies of the 'cold war' era. (authors)

  15. Radio-Ecological Conditions of Groundwater in the Area of Uranium Mining and Milling Facility - 13525

    SciTech Connect (OSTI)

    Titov, A.V.; Semenova, M.P.; Seregin, V.A.; Isaev, D.V.; Metlyaev, E.G. [FSBU SRC A.I.Burnasyan Federal Medical Biophysical Center of FMBA of Russia, Zhivopisnaya Street, 46, Moscow (Russian Federation)] [FSBU SRC A.I.Burnasyan Federal Medical Biophysical Center of FMBA of Russia, Zhivopisnaya Street, 46, Moscow (Russian Federation); Glagolev, A.V.; Klimova, T.I.; Sevtinova, E.B. [FSESP 'Hydrospecgeologiya' (Russian Federation)] [FSESP 'Hydrospecgeologiya' (Russian Federation); Zolotukhina, S.B.; Zhuravleva, L.A. [FSHE 'Centre of Hygiene and Epidemiology no. 107' under FMBA of Russia (Russian Federation)] [FSHE 'Centre of Hygiene and Epidemiology no. 107' under FMBA of Russia (Russian Federation)

    2013-07-01

    Manmade chemical and radioactive contamination of groundwater is one of damaging effects of the uranium mining and milling facilities. Groundwater contamination is of special importance for the area of Priargun Production Mining and Chemical Association, JSC 'PPMCA', because groundwater is the only source of drinking water. The paper describes natural conditions of the site, provides information on changes of near-surface area since the beginning of the company, illustrates the main trends of contaminators migration and assesses manmade impact on the quality and mode of near-surface and ground waters. The paper also provides the results of chemical and radioactive measurements in groundwater at various distances from the sources of manmade contamination to the drinking water supply areas. We show that development of deposits, mine water discharge, leakages from tailing dams and cinder storage facility changed general hydro-chemical balance of the area, contributed to new (overlaid) aureoles and flows of scattering paragenetic uranium elements, which are much smaller in comparison with natural ones. However, increasing flow of groundwater stream at the mouth of Sukhoi Urulyungui due to technological water infiltration, mixing of natural water with filtration streams from industrial reservoirs and sites, containing elevated (relative to natural background) levels of sulfate-, hydro-carbonate and carbonate- ions, led to the development and moving of the uranium contamination aureole from the undeveloped field 'Polevoye' to the water inlet area. The aureole front crossed the southern border of water inlet of drinking purpose. The qualitative composition of groundwater, especially in the southern part of water inlet, steadily changes for the worse. The current Russian intervention levels of gross alpha activity and of some natural radionuclides including {sup 222}Rn are in excess in drinking water; regulations for fluorine and manganese concentrations are also in excess. Possible ways to improve the situation are considered. (authors)

  16. shprkEA.doc

    Office of Legacy Management (LM)

    EA-1388 Environmental Assessment of Ground Water Compliance at the Shiprock Uranium Mill Tailings Site Final September 2001 Prepared by U.S. Department of Energy Grand Junction Office Grand Junction, Colorado Work Performed Under DOE Contract No. DE-AC13-96GJ87335 This Page Intentionally Blank DOE Grand Junction Office EA of Ground Water Compliance at the Shiprock Site September 2001 Final Page iii Contents Page Acronyms and Abbreviations

  17. U.S. Department of Energy 2014 UMTRCA Title I Annual Report

    Office of Legacy Management (LM)

    Grand Junction, Colorado Page 6-1 6.0 Grand Junction, Colorado, Disposal Site 6.1 Compliance Summary The Grand Junction, Colorado, Uranium Mill Tailings Radiation Control Act (UMTRCA) Title I Disposal Site was inspected on December 9, 2014. A portion of the disposal cell remains open to receive low-level radioactive materials from various sources, and the open cell and its supporting structures and facilities are not included in the annual inspection. Ongoing cell cover study areas, which

  18. DOE/EA-1261 Rev.

    Office of Legacy Management (LM)

    1 Rev. 0 Environmental Assessment of Ground Water Compliance at the Riverton, Wyoming, Uranium Mill Tailings Site Final September 1998 Prepared by U.S. Department of Energy Grand Junction Office Grand Junction, Colorado Work Performed Under DOE Contract No. DE-AC13 -96GJ87335 for the U.S. Department of Energy This page intentionally left blank DOE Grand Junction Office Page iii EA of Ground Water Compliance at Riverton Final September 1998 Contents Page Acronyms and Abbreviations . . . . . . . .

  19. F:\SHARE\SE\Web_Origs\Wrk_Jan\00-075\U0027603.WP6

    Office of Legacy Management (LM)

    8 Rev. 0 Environmental Assessment of Ground Water Compliance at the Tuba City Uranium Mill Tailings Site December 1998 Prepared by U.S. Department of Energy Grand Junction Office Grand Junction, Colorado Work Performed Under DOE Contract No. DE-AC13-96GJ87335 for the U.S. Department of Energy Document Number U0027603 DOE Grand Junction Office Page iii EA of Ground Water Compliance at Tuba City December 1998 Contents Page Acronyms and Abbreviations . . . . . . . . . . . . . . . . . . . . . . . .

  20. Reclamation of acidic copper mine tailings using municipal biosolids

    SciTech Connect (OSTI)

    Rogers, M.T.; Thompson, T.L.; Bengson, S.A.

    1998-12-31

    Reclamation of copper mine tailings in a cost effective, successful, and sustainable manner is an ongoing area of evaluation in the arid southwest. A study was initiated in September, 1996 near Hayden, Arizona to evaluate the use of municipal biosolids for reclaiming acidic copper mine tailings (pH of 2.5 to 4.0). The main objectives of the study were to (1) define an appropriate level of biosolids application for optimum plant growth, and (2) evaluate the effects of green waste and lime amendments. The experiment was a randomized complete block design with four biosolid rates of 20, 70, 100 and 135 dry tons/acre, three amendment treatments (none, green waste, and green waste plus lime); with three replications. Non-replicated controls (no treatment, green waste only and lime only) were included for comparison. Shortly after biosolids incorporation to a depth of 10--12 inches, composite soil samples (0--12 inches) of each plot were taken. Biosolids incorporation increased the pH of the tailings (>5.75) and additional increases in pH were noted with lime application. In January 1997, the plots were seeded and sprinkler irrigation was commenced. A total of 4.47 inches of rainfall and 3.8 inches of irrigation were applied until harvest in May 1997. Data from the first growing season indicates optimum growth (>66 lbs/acre) at biosolids rates of 70--100 dry tons/acre. There was a significant positive effect on growth of green waste and lime amendments. Surface NO{sub 3}-N concentrations in biosolids amended plots were greatly reduced (from 23 to 6 mg/kg) by addition of green waste. There was no evidence for NO{sub 3}N leaching below 12 inches.

  1. Winning the Future: Grand Ronde Solar Projects Reduce Pollution, Cut Costs

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    | Department of Energy Grand Ronde Solar Projects Reduce Pollution, Cut Costs Winning the Future: Grand Ronde Solar Projects Reduce Pollution, Cut Costs October 20, 2014 - 5:00pm Addthis PV panels installed on Grand Ronde Tribal Housing Authority carport. Photo from GRTHA, NREL 31797 PV panels installed on Grand Ronde Tribal Housing Authority carport. Photo from GRTHA, NREL 31797 Challenge: Situated on nearly 12,000 acres in the heart of Western Oregon's scenic coastal range, the

  2. 2011 Annual Planning Summary for Office of Legacy Management (LM), Grand

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Junction (See LM APS) | Department of Energy Legacy Management (LM), Grand Junction (See LM APS) 2011 Annual Planning Summary for Office of Legacy Management (LM), Grand Junction (See LM APS) The ongoing and projected Environmental Assessments and Environmental Impact Statements for 2011 and 2012 within the Office of Legacy Management (LM), Grand Junction (See LM APS). PDF icon 2011 Annual Planning Summary for Office of Legacy Management (LM), Grand Junction (See LM APS) More Documents &

  3. Grand Traverse Band Renewable Energy Feasibility Study in Wind, Biomass and Solar

    SciTech Connect (OSTI)

    Suzanne McSawby, Project Director Steve Smiley, Principle Investigator Grand Traverse Resort, Cost Sharing Partner

    2008-12-31

    Renewable Energy Feasibility Study for wind, biomass, solar on the Grand Traverse Band tribal lands from 2005 - 2008

  4. Winning the Future: Grand Ronde Solar Projects Reduce Pollution, Cut Costs

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    | Department of Energy Winning the Future: Grand Ronde Solar Projects Reduce Pollution, Cut Costs Winning the Future: Grand Ronde Solar Projects Reduce Pollution, Cut Costs October 20, 2014 - 5:00pm Addthis PV panels installed on Grand Ronde Tribal Housing Authority carport. Photo from GRTHA, NREL 31797 PV panels installed on Grand Ronde Tribal Housing Authority carport. Photo from GRTHA, NREL 31797 Challenge: Situated on nearly 12,000 acres in the heart of Western Oregon's scenic coastal

  5. Data Compendium for the Logging Test Pits at the ERDA Grand Junction

    Office of Environmental Management (EM)

    Compound (December 1975) | Department of Energy Data Compendium for the Logging Test Pits at the ERDA Grand Junction Compound (December 1975) Data Compendium for the Logging Test Pits at the ERDA Grand Junction Compound (December 1975) Data Compendium for the Logging Test Pits at the ERDA Grand Junction Compound (December 1975) PDF icon Data Compendium for the Logging Test Pits at the ERDA Grand Junction Compound (December 1975) More Documents & Publications Field Calibration Facilities

  6. August 2015 Groundwater Sampling at the Grand Junction, Colorado, Disposal Site

    Office of Legacy Management (LM)

    Sampling at the Grand Junction, Colorado, Disposal Site October 2015 LMS/GRJ/S00815 This page intentionally left blank U.S. Department of Energy DVP-August 2015, Grand Junction, Colorado October 2015 RIN 15077245 Page i Contents Sampling Event Summary ...............................................................................................................1 Grand Junction, Colorado, Disposal Site, Sample Location Map ...................................................3 Data Assessment

  7. City of Grand Rapids Building Solar Roof Demonstration

    SciTech Connect (OSTI)

    DeClercq, Mark; Martinez, Imelda

    2012-08-31

    Grand Rapids, Michigan is striving to reduce it environmental footprint. The municipal government organization has established environmental sustainability policies with the goal of securing 100% of its energy from renewable sources by 2020. This report describes the process by which the City of Grand Rapids evaluated, selected and installed solar panels on the Water/Environmental Services Building. The solar panels are the first to be placed on a municipal building. Its new power monitoring system provides output data to assess energy efficiency and utilization. It is expected to generate enough clean solar energy to power 25 percent of the building. The benefit to the public includes the economic savings from reduced operational costs for the building; an improved environmentally sustainable area in which to live and work; and increased knowledge about the use of solar energy. It will serve as a model for future energy saving applications.

  8. Grande Ronde Basin Supplementation Program; Lostine River, 2000 Annual Report.

    SciTech Connect (OSTI)

    Onjukka, Sam T.; Harbeck, Jim

    2003-03-01

    The Northwest Power Planning Council (NPPC) identified supplementation as a high priority to achieve its goal of increasing runs of anadromous fish in the Columbia Basin. Supplementation activities in the Lostine River and associated monitoring and evaluation conducted by the Nez Perce Tribe relate directly to the needs addressed in the Columbia River Basin Fish and Wildlife Program (NPPC 1994). Measure 7.4L.1 of the Program mandates that appropriate research accompany any proposed supplementation. In addition, measure 7.3B.2 of the Program stresses the need for evaluating supplementation projects to assess their ability to increase production. Finally, Section 7.4D.3 encourages the study of hatchery rearing and release strategies to improve survival and adaptation of cultured fish. In 1997, Oregon Department of Fisheries and Wildlife (ODFW) requested a modification of Permit 1011 to allow the take of adult spring chinook salmon. In 1998, the Nez Perce Tribe also requested a permit specific to activities on Lostine River. The permit was issued in 2000. A special condition in the permits required the development of a long term management plan for the spring chinook salmon of the Grande Ronde Basin. The Nez Perce Tribe, ODFW, and the Confederated Tribes of the Umatilla Indian Reservation (CTUIR) completed a formal long range plan entitled ''Grande Ronde Basin Endemic Spring Chinook Salmon Supplementation Program''. The program proposes to increase the survival of spring chinook salmon in the Grand Ronde Basin through hatchery intervention. Adult salmon from the Lostine River, Catherine Creek, and the Upper Grande Ronde River are used for a conventional supplementation program in the basin. The Nez Perce program currently operates under the ESA Section 10 Permit 1149.

  9. Grande Ronde Basin Supplementation Program; Lostine River, 2001 Annual Report.

    SciTech Connect (OSTI)

    Onjukka, Sam T.; Harbeck, Jim

    2003-03-01

    The Northwest Power Planning Council (NPPC) identified supplementation as a high priority to achieve its goal of increasing runs of anadromous fish in the Columbia Basin. Supplementation activities in the Lostine River and associated monitoring and evaluation conducted by the Nez Perce Tribe relate directly to the needs addressed in the Columbia River Basin Fish and Wildlife Program (NPPC 1994). Measure 7.4L.1 of the Program mandates that appropriate research accompany any proposed supplementation. In addition, measure 7.3B.2 of the Program stresses the need for evaluating supplementation projects to assess their ability to increase production. Finally, Section 7.4D.3 encourages the study of hatchery rearing and release strategies to improve survival and adaptation of cultured fish. In 1997, Oregon Department of Fisheries and Wildlife (ODFW) requested a modification of Permit 1011 to allow the take of adult spring chinook salmon. In 1998, the Nez Perce Tribe also requested a permit specific to activities on Lostine River. The permit was issued in 2000. A special condition in the permits required the development of a long term management plan for the spring chinook salmon of the Grande Ronde Basin. The Nez Perce Tribe, ODFW, and the Confederated Tribes of the Umatilla Indian Reservation (CTUIR) completed a formal long range plan entitled ''Grande Ronde Basin Endemic Spring Chinook Salmon Supplementation Program''. The program proposes to increase the survival of spring chinook salmon in the Grand Ronde Basin through hatchery intervention. Adult salmon from the Lostine River, Catherine Creek, and the Upper Grande Ronde River are used for a conventional supplementation program in the basin. The Nez Perce program currently operates under the ESA Section 10 Permit 1149.

  10. Upper Rio Grande Simulation Model (URGSiM)

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Upper Rio Grande Simulation Model (URGSiM) - Sandia Energy Energy Search Icon Sandia Home Locations Contact Us Employee Locator Energy & Climate Secure & Sustainable Energy Future Stationary Power Energy Conversion Efficiency Solar Energy Wind Energy Water Power Supercritical CO2 Geothermal Natural Gas Safety, Security & Resilience of the Energy Infrastructure Energy Storage Nuclear Power & Engineering Grid Modernization Battery Testing Nuclear Fuel Cycle Defense Waste Management

  11. Chattanooga Eagle Ford Rio Grande Embayment Texas- Louisiana-

    Gasoline and Diesel Fuel Update (EIA)

    Chattanooga Eagle Ford Rio Grande Embayment Texas- Louisiana- Mississippi Salt Basin Uinta Basin Appa lachia n Basin Utica Marcellus Devonian (Ohio) Antrim Barnett Bend New Albany Woodford Barnett- Woodford Lewis Hilliard- Baxter- Mancos Excello- Mulky Fayetteville Floyd- Neal Gammon Cody Haynesville Hermosa Mancos Pierre Conasauga Woodford- Caney Pearsall- Eagle Ford Michigan Basin Ft. Worth Basin Palo Duro Basin Permian Basin Illinois Basin Anadarko Basin Greater Green River Basin Cherokee

  12. Electrolyte pore/solution partitioning by expanded grand canonical ensemble

    Office of Scientific and Technical Information (OSTI)

    Monte Carlo simulation (Journal Article) | SciTech Connect This content will become publicly available on March 27, 2016 Title: Electrolyte pore/solution partitioning by expanded grand canonical ensemble Monte Carlo simulation Authors: Moucka, Filip [1] ; Bratko, Dusan [2] ; Luzar, Alenka [2] Search SciTech Connect for author "Luzar, Alenka" Search SciTech Connect for ORCID "000000031640191X" Search orcid.org for ORCID "000000031640191X" + Show Author

  13. EV Everywhere Grand Challenge - Charge to the Breakout Groups

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    EV Everywhere Grand Challenge Charge to the Breakout Groups July 26, 2012 David Howell Team Lead, Hybrid & Electric Systems Vehicle Technologies Program U.S. Department of Energy 1000 Independence Avenue Washington DC 20585 eere.energy.gov BREAKOUT GROUPS Breakout Group Room Facilitator Color Code Next-Generation Li-Ion Batteries Othello Room mezzanine Jeff Chamberlain (ANL) green Beyond Li-Ion Batteries Winchester Room mezzanine Frank McClarnon (LBNL) blue Manufacturing and Processing

  14. SunShot Grand Challenge Summit | Department of Energy

    Energy Savers [EERE]

    SunShot Grand Challenge Summit Online registration is now closed Online registration is now closed Limited onsite registration is available. Learn more. Read more Resources for Summit Attendees Resources for Summit Attendees Plan your Summit experience today by accessing event schedules, venue information and more. Read more Exciting Keynotes, Plenary Sessions, Industry Workshops, Technology Forum and Peer Review Exciting Keynotes, Plenary Sessions, Industry Workshops, Technology Forum and Peer

  15. EV Everywhere Grand Challenge Road to Success | Department of Energy

    Office of Environmental Management (EM)

    Road to Success EV Everywhere Grand Challenge Road to Success Initial progress report for EV Everywhere. The report highlights the significant cost reduction in batteries this year, which will enable increased PEV affordability for consumers. Also, the efforts on increasing the convenience of PEVs through the Workplace Charging Challenge, which calls on U.S. employers to help develop the nation's charging infrastructure. PDF icon eveverywhere_road_to_success.pdf More Documents & Publications

  16. Public Involvment Plan - Rifle, Colorado

    Office of Legacy Management (LM)

    4-TAR MAC-GWRIF 7.1 UMTRA Ground Water Project Public Involvement Plan for the Environmental Assessment of Ground Water Compliance at the New and Old Rifle, Colorado, Uranium Mill Tailings Sites May 1999 Prepared by U.S. Department of Energy Grand Junction Office Grand Junction, Colorado Work performed under DOE Contract No. DE-AC13-96GJ87335 Public Involvement Plan for the Rifle UMTRA Sites Page 2 Introduction This Public Involvement Plan is tiered to the Uranium Mill Tailings Remedial Action

  17. Traveling waves and their tails in locally resonant granular systems

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Xu, H.; Kevrekidis, P. G.; Stefanov, A.

    2015-04-22

    In the present study, we revisit the theme of wave propagation in locally resonant granular crystal systems, also referred to as mass-in-mass systems. We use three distinct approaches to identify relevant traveling waves. In addition, the first consists of a direct solution of the traveling wave problem. The second one consists of the solution of the Fourier tranformed variant of the problem, or, more precisely, of its convolution reformulation (upon an inverse Fourier transform) in real space. Finally, our third approach will restrict considerations to a finite domain, utilizing the notion of Fourier series for important technical reasons, namely themore » avoidance of resonances, which will be discussed in detail. All three approaches can be utilized in either the displacement or the strain formulation. Typical resulting computations in finite domains result in the solitary waves bearing symmetric non-vanishing tails at both ends of the computational domain. Importantly, however, a countably infinite set of anti-resonance conditions is identified for which solutions with genuinely rapidly decaying tails arise.« less

  18. Wind Resource Assessment Report: Mille Lacs Indian Reservation, Minnesota

    SciTech Connect (OSTI)

    Jimenez, A. C.

    2013-12-01

    The U.S. Environmental Protection Agency (EPA) launched the RE-Powering America's Land initiative to encourage development of renewable energy on potentially contaminated land and mine sites. EPA collaborated with the U.S. Department of Energy's (DOE's) National Renewable Energy Laboratory (NREL) and the Mille Lacs Band of Chippewa Indians to evaluate the wind resource and examine the feasibility of a wind project at a contaminated site located on the Mille Lacs Indian Reservation in Minnesota. The wind monitoring effort involved the installation of a 60-m met tower and the collection of 18 months of wind data at multiple heights above the ground. This report focuses on the wind resource assessment, the estimated energy production of wind turbines, and an assessment of the economic feasibility of a potential wind project sited this site.

  19. Environmental assessment of facility operations at the U.S. Department of Energy Grand Junction Projects Office, Grand Junction, Colorado

    SciTech Connect (OSTI)

    1996-06-01

    The US Department of Energy (DOE) has prepared a sitewide environmental assessment (EA) of the proposed action to continue and expand present-day activities on the DOE Grand Junction Projects Office (GJPO) facility in Grand Junction, Colorado. Because DOE-GJPO regularly proposes and conducts many different on-site activities, DOE decided to evaluate these activities in one sitewide EA rather than in multiple, activity-specific documents. On the basis of the information and analyses presented in the EA, DOE has determined that the proposed action does not constitute a major Federal action significantly affecting the quality of the human environment, as defined by the National Environmental Policy Act (NEPA) of 1969. Therefore, preparation of an environmental impact statement is not required for facility operations, and DOE is issuing this Finding of No Significant Impact (FONSI).

  20. Multiscale MonteCarlo equilibration: Pure Yang-Mills theory

    SciTech Connect (OSTI)

    Endres, Michael G.; Brower, Richard C.; Orginos, Kostas; Detmold, William; Pochinsky, Andrew V.

    2015-12-29

    In this study, we present a multiscale thermalization algorithm for lattice gauge theory, which enables efficient parallel generation of uncorrelated gauge field configurations. The algorithm combines standard Monte Carlo techniques with ideas drawn from real space renormalization group and multigrid methods. We demonstrate the viability of the algorithm for pure Yang-Mills gauge theory for both heat bath and hybrid Monte Carlo evolution, and show that it ameliorates the problem of topological freezing up to controllable lattice spacing artifacts.

  1. From: Mills, Pamela To: Congestion Study Comments Cc: Strack, Jan

    Office of Environmental Management (EM)

    Mills, Pamela To: Congestion Study Comments Cc: Strack, Jan Subject: National Electric Transmission Congestion Study - Draft for Public Comment Date: Friday, October 17, 2014 6:18:37 PM Attachments: SDGE Comments on the National Electric Transmission Congestion Study - Draft for Public Comment.docx Please find attached SDG&E's comments on the National Electric Transmission Congestion Study - Draft for Public Comment. Any questions or comments regarding the attached document should be

  2. Deconfinement in Yang-Mills Theory through Toroidal Compactification

    SciTech Connect (OSTI)

    Simic, Dusan; Unsal, Mithat; /Stanford U., Phys. Dept. /SLAC

    2011-08-12

    We introduce field theory techniques through which the deconfinement transition of four-dimensional Yang-Mills theory can be moved to a semi-classical domain where it becomes calculable using two-dimensional field theory. We achieve this through a double-trace deformation of toroidally compactified Yang-Mills theory on R{sup 2} x S{sub L}{sup 1} x S{sub {beta}}{sup 1}. At large N, fixed-L, and arbitrary {beta}, the thermodynamics of the deformed theory is equivalent to that of ordinary Yang-Mills theory at leading order in the large N expansion. At fixed-N, small L and a range of {beta}, the deformed theory maps to a two-dimensional theory with electric and magnetic (order and disorder) perturbations, analogs of which appear in planar spin-systems and statistical physics. We show that in this regime the deconfinement transition is driven by the competition between electric and magnetic perturbations in this two-dimensional theory. This appears to support the scenario proposed by Liao and Shuryak regarding the magnetic component of the quark-gluon plasma at RHIC.

  3. Remedial Action Plan and site design for stabilization of the inactive uranium mill tailings site at Gunnison, Colorado. Attachment 2, Geology report: Final report

    SciTech Connect (OSTI)

    Not Available

    1992-10-01

    Detailed investigations of geologic, geomorphic, and seismic conditions at the Landfill disposal site were conducted. The purpose of these studies was basic site characterization and identification of potential geologic hazards that could affect long-term site stability. Subsequent engineering studies, such as analyses of hydrologic and liquefaction hazards, used the data developed in these studies. The geomorphic analysis was employed in the design of effective erosion protection. Studies of the regional and local seismotectonic setting, which included a detailed search for possible capable faults within a 65-kilometer (km) (40-mile) radius of the site, provided the basis for seismic design parameters. The scope of work performed included the following: Compilation and analysis of previous published and unpublished geologic literature and maps. Review of historical and instrumental earthquake data. Review of site-specific subsurface geologic data, including lithologic and geophysical logs of exploratory boreholes advanced in the site area. Photogeologic interpretations of existing conventional aerial photographs. Ground reconnaissance and mapping of the site region.

  4. Remedial action plan and site design for stabilization of the inactive Uranium Mill Tailings Site at Lowman, Idaho. Attachment 4, Water resources protection strategy: Final report

    SciTech Connect (OSTI)

    Not Available

    1991-09-01

    The DOE proposes to achieve compliance with the proposed EPA groundwater protection standards (Subparts A and B of 40 CFR 192) by meeting the EPA maximum concentration limits (MCLs) or background concentrations for designated hazardous constituents in groundwater in the uppermost aquifer (alluvium/weathered granodiorite) at the point of compliance (POC) at the Lowman disposal site near Lowman, Idaho. The proposed remedial action in conjunction with existing hydrogeological conditions at the Lowman site will ensure sufficient protection of human health and the environment. The DOE has concluded that the EPA groundwater protection standards will be met at the POC because, with the exception of antimony, none of the hazardous constituents that exceed laboratory method detection limits within the radioactive sand pore fluids were above the proposed concentration limits. The DOE has demonstrated that antimony will meet the proposed concentration limits at the POC through attenuation in subsoils beneath the disposal cell and by dilution in groundwater underflow. The Lowman processing site is in compliance with Subpart B of 40 CFR 192 because statistical analyses of groundwater samples indicate no groundwater contamination.

  5. Remedial Action Plan and final design for stabilization of the inactive uranium mill tailings at Green River, Utah. Volume 1, Text, Appendices A, B, and C: Final report

    SciTech Connect (OSTI)

    Matthews, M.L.; Alkema, K.

    1991-03-01

    This Remedial Action Plan (RAP) has been developed to serve a threefold purpose. It presents the series of activities that are proposed by the US Department of Energy (DOE) to accomplish long-term stabilization and control of radioactive materials at the inactive uranium processing site located near Green River, Utah. It provides a characterization of the present conditions of the site. It also serves to document the concurrence of the state of Utah and the US Nuclear Regulatory Commission (NRC) in the remedial action. This agreement, upon execution by the DOE and the state of Utah, and concurrence by the NRC, becomes Appendix 8 of the Cooperative Agreement.

  6. Remedial Action Plan for the codisposal and stabilization of the Monument Valley and Mexican Hat uranium mill tailings at Mexican Hat, Utah: Appendices C--E. Final report

    SciTech Connect (OSTI)

    1993-02-01

    This document provides appendices C, D, and E this Remedial Action Plan (RAP) which is a revision of the original Mexican Hat Remedial Action Plan and RAP Modification submitted in July 1988 and January 1989, respectively, along with updated design documents. Appendix C provide the Radiological Support Plan, Appendix D provides the Site Characterization, and Appendix E provides the Water Resources Protection Strategy.

  7. Remedial Action Plan and site design for stabilization of the inactive uranium mill tailings site at Mexican Hat, Utah: Text, Appendices A--C. Final report

    SciTech Connect (OSTI)

    1988-07-01

    This Remedial Action Plan (RAP) has been developed to serve a two- fold purpose. It presents the activities proposed by the Department of Energy (DOE) to accomplish long-term stabilization and control of the residual radioactive materials (RRM) from Monument Valley Arizona, and Mexican Hat, Utah, at the Mexican Hat disposal site. It also serves to document the concurrence of both the Navajo Nation and the Nuclear Regulatory Commission (NRC) in the remedial action. This agreement, upon execution by DOE and the Navajo Nation and concurrence by the NRC, becomes Appendix B of the Cooperative Agreement. This document has been structured to provide a comprehensive understanding of the remedial action proposed for the Monument Valley and Mexican Hat sites. It includes specific design and construction requirements for the remedial action. Pertinent information and data are included with reference given to the supporting documents. Appendices A,B, and C are provided as part of this document. Appendix A presents regulatory compliance issues, Appendix B provides details of the engineering design, and Appendix C presents the radiological support plan.

  8. Remedial Action Plan for the codisposal and stabilization of the Monument Valley and Mexican Hat uranium mill tailings at Mexican Hat, Utah

    SciTech Connect (OSTI)

    1993-02-01

    This document is a revision of the original Mexiacan Hat Remedial Action Plan (RAP) and RAP Modification submitted in July 1988 and January 1989, respectively, along with updated design documents. This RAP has been developed to serve a two-fold purpose. It presents the activities proposed by the Department of Energy (DOE) to accomplish long-term stabilization and control of the residual radioactive materials (RRM) from Monument Valley, Arizona, and Mexican Hat, Utah, at the Mexican Hat disposal site. It also serves to document the concurrence of both the Navajo Nation and the Nuclear Regulatory Commission (NRC) in the remedial action. This agreement, upon execution by DOE and the Navajo Nation and concurrence by the NRC, becomes Appendix B of the Cooperative Agreement. This document has been structured to provide a comprehensive understanding of the remedial action proposed for the Monument Valley and Mexican Hat sites. It includes specific design and construction requirements for the remedial action. Pertinent information and data are included with reference given to the supporting documents. Section 2.0 presents the EPA standards, including a discussion of their objectives. Section 3. 0 summarizes the present site characteristics and provides a definition of site-specific problems. Section 4.0 is the site design for the proposed action. Section 5.0 presents the water resources protection strategy. Section 6.0 summarizes the plan for ensuring health and safety protection for the surrounding community and the on- site workers. Section 7.0 lists the responsibilities of the project participants. Section 8.0 describes the features of the long-term surveillance and maintenance plan.

  9. Remedial action plan and site design for stabilization of the inactive uranium mill tailings site at Tuba City, Arizona. Text, Appendices A, B, and C: Final report

    SciTech Connect (OSTI)

    Not Available

    1989-08-01

    This Remedial Action Plan (RAP) has been developed to serve a threefold purpose. It presents the series of activities which are proposed by the US Department of Energy (DOE) to accomplish long-term stabilization and control of radioactive materials at the inactive uranium processing site near Tuba City, Arizona. It provides a characterization of the present conditions of the site. It also serves to document the concurrence of the Navajo Nation, the Hopi Tribe, US Bureau of Indian Affairs (BIA), and the US Nuclear Regulatory Commission (NRC) in the remedial action. This agreement, upon execution by DOE, the Navajo Nation, and the Hopi Tribe, and concurrence by NRC, becomes Appendix B of the Cooperative Agreement. Following the introduction, contents are as follows: Section 2.0 presents the EPA standards, including a discussion of their objectives. Section 3.0 summarizes the present site characteristics and provides a definition of site-specific problems. Section 4.0 is the site design for the proposed action. Section 5.0 summarizes the plan for ensuring environmental, health, and safety protection for the surrounding community and the on-site workers. Section 6.0 presents a detailed listing of the responsibilities of the project participants. Section 7.0 describes the features of the long-term surveillance and maintenance plan. Section 8.0 presents the quality assurance aspects of the project. Section 9.0 documents the ongoing activities to keep the public informed and participating in the project.

  10. Type B Accident Investigation Board Report on the November 1, 1999, Construction Injury at the Monticello Mill Tailings Remedial Action Site, Monticello, Utah

    Broader source: Energy.gov [DOE]

    This report is an independent product of the Type B accident investigation board appointed by R. E. Glass, Manager, Albuquerque Operations Office.

  11. Remedial actions at the former Climax Uranium Company, Uranium Mill site, Grand Junction, Mesa County, Colorado. Volume 2, Appendices: Final environmental impact statement

    SciTech Connect (OSTI)

    1986-12-01

    This volume contains Appendix F--hydrology report, and Appendix G--flood plain and wetland assessment. Contents of the hydrology report include: surface water; ground water; potentially affected hydrogeologic environment-processing site; potentially affected hydrogeologic environment-Cheney reservoir site; potentially affected hydrogeologic environment-Two Road site; and conclusions-ground water.

  12. Reviewing the success of intentional flooding of the Grand Canyon

    SciTech Connect (OSTI)

    Wirth, B.D.

    1997-04-01

    A description and evaluation of the results of an intentional flooding experiment at the Grand Canyon are described. The purpose of the 7-day release of flood waters from the Glen Canyon Dam was to determine if managed floods have the ability to predictably restore the riverine environment. A summary of environmental conditions leading to the experiment is provided and flood results are listed. Initial results showed significant improvement in the size and number of the river`s beaches, creation of backwater habitat for endangered species, and no adverse impact to the trout fishery, Indian cultural sites, and other resources.

  13. Low energy milling method, low crystallinity alloy, and negative electrode composition

    DOE Patents [OSTI]

    Le, Dihn B; Obrovac, Mark N; Kube, Robert Y; Landucci, James R

    2012-10-16

    A method of making nanostructured alloy particles includes milling a millbase in a pebble mill containing milling media. The millbase comprises: (i) silicon, and (ii) at least one of carbon or a transition metal, and wherein the nanostructured alloy particles are substantially free of crystalline domains greater than 50 nanometers in size. A method of making a negative electrode composition for a lithium ion battery including the nanostructured alloy particles is also disclosed.

  14. Inter-Tribal Council of Michigan, Inc. - Bay Mills Indian Community Energy Reduction Feasibility Study

    Office of Environmental Management (EM)

    --Tribal Council of Michigan, Inc. Environmental Services Division Bay Mills Indian Community Energy Reduc<on Feasibility Study Chris K ushman Thank You *DOE Tribal Energy Program *Tribal Energy Program Review presenters *Bay Mills Indian Community Bay Mills Indian Community * Upper Peninsula of Michigan - Cold temperatures - Prolonged exposure to strong north winds off Lake Superior - Short winter daylight * Fishing and fish consuming community * Electricity largely supplied by coal fired

  15. DOE - Office of Legacy Management -- Falls City Mill Site - TX 04

    Office of Legacy Management (LM)

    Mill Site - TX 04 FUSRAP Considered Sites Site: Falls City Mill Site (TX.04 ) Designated Name: Alternate Name: Location: Evaluation Year: Site Operations: Site Disposition: Radioactive Materials Handled: Primary Radioactive Materials Handled: Radiological Survey(s): Site Status: Also see Falls City, Texas, Disposal Site Documents Related to Falls City Mill Site Data Validation Package for the April 2009 Groundwater Sampling at the Falls City, Texas, Disposal Site. June 2009 2014 Annual Site

  16. DOE - Office of Legacy Management -- Green River Mill Site - UT 0-01

    Office of Legacy Management (LM)

    Green River Mill Site - UT 0-01 FUSRAP Considered Sites Site: Green River Mill Site (UT.0-01 ) Designated Name: Alternate Name: Location: Evaluation Year: Site Operations: Site Disposition: Radioactive Materials Handled: Primary Radioactive Materials Handled: Radiological Survey(s): Site Status: Also see Green River, Utah, Disposal Site Documents Related to Green River Mill Site Data Validation Package for the June 2009 Groundwater and Surface Water Sampling at the Green River, Utah, Disposal

  17. DOE - Office of Legacy Management -- Monument Valley Mill Site - AZ 0-01

    Office of Legacy Management (LM)

    Monument Valley Mill Site - AZ 0-01 FUSRAP Considered Sites Site: Monument Valley Mill Site (AZ.0-01) Designated Name: Alternate Name: Location: Evaluation Year: Site Operations: Site Disposition: Radioactive Materials Handled: Primary Radioactive Materials Handled: Radiological Survey(s): Site Status: Also see Monument Valley, Arizona, Processing Site Documents Related to Monument Valley Mill Site Data Validation Package for the June 2009 Water Sampling at the Monument Valley, Arizona,

  18. DOE - Office of Legacy Management -- Naturita Mill Site - CO 0-08

    Office of Legacy Management (LM)

    Naturita Mill Site - CO 0-08 FUSRAP Considered Sites Site: Naturita Mill Site (CO.0-08) Designated Name: Alternate Name: Location: Evaluation Year: Site Operations: Site Disposition: Radioactive Materials Handled: Primary Radioactive Materials Handled: Radiological Survey(s): Site Status: Also see Naturita, Colorado, Processing Site Documents Related to Naturita Mill Site Data Validation Package for the July and October 2008 Water Sampling at the Naturita Processing and Disposal Sites Data

  19. DOE - Office of Legacy Management -- Rifle Mill Site - CO 0-11

    Office of Legacy Management (LM)

    Rifle Mill Site - CO 0-11 FUSRAP Considered Sites Site: Rifle Mill Site (CO.0-11 ) Designated Name: Alternate Name: Location: Evaluation Year: Site Operations: Site Disposition: Radioactive Materials Handled: Primary Radioactive Materials Handled: Radiological Survey(s): Site Status: Also see Rifle, Colorado, New Processing Site Rifle, Colorado, Old Processing Site Documents Related to Rifle Mill Site 2009 Verification Monitoring Report for the Old and New Rifle, Colorado, Processing Sites;

  20. Steel Mill Powered by Waste Heat Recovery System | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Steel Mill Powered by Waste Heat Recovery System Steel Mill Powered by Waste Heat Recovery System May 16, 2013 - 12:00am Addthis EERE worked with ArcelorMittal USA, Inc. to install an efficient recovery boiler to burn blast furnace gases generated during iron-making operations to produce electricity and steam onsite at the company's Indiana Harbor Steel Mill in East Chicago, Indiana. The steam is being used to drive existing turbogenerators onsite, creating enough electricity to power the

  1. The U.S. Dry-Mill Ethanol Industry: Biobased Products and Bioenergy Initiative Success Stories

    SciTech Connect (OSTI)

    2009-10-28

    This fact sheet provides an overview of the history of ethanol production in the United States and describes innovations in dry-mill ethanol production.

  2. Bioenergy Pumps New Life into Pulp and Paper Mills | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Bioenergy Pumps New Life into Pulp and Paper Mills Bioenergy Pumps New Life into Pulp and Paper Mills December 13, 2011 - 4:12pm Addthis Old Town Fuel and Fiber, a former pulp mill, converts a portion of the wood chips used to make pulp to biofuels. | Energy Department photo. Old Town Fuel and Fiber, a former pulp mill, converts a portion of the wood chips used to make pulp to biofuels. | Energy Department photo. Neil Rossmeissl General Engineer What does this project do? Breathes new life into

  3. From Flour to Grits, a Water-Powered Mill Keeps on Grinding | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy From Flour to Grits, a Water-Powered Mill Keeps on Grinding From Flour to Grits, a Water-Powered Mill Keeps on Grinding July 7, 2015 - 12:15pm Addthis From Flour to Grits, a Water-Powered Mill Keeps on Grinding By 1913, the old mill had become structurally unsound and was demolished and later rebuilt. The family also replaced the water wheel with more efficient twin hydropower turbine and generator units, boosting their local electric supply. As the family-owned business-Weisenberger

  4. Geomorphology of plutonium in the Northern Rio Grande

    SciTech Connect (OSTI)

    Graf, W.L.

    1993-03-01

    Nearly all of the plutonium in the natural environment of the Northern Rio Grande is associated with soils and sediment, and river processes account for most of the mobility of these materials. A composite regional budget for plutonium based on multi-decadal averages for sediment and plutonium movement shows that 90 percent of the plutonium moving into the system is from atmospheric fallout. The remaining 10 percent is from releases at Los Alamos. Annual variation in plutonium flux and storage exceeds 100 percent. The contribution to the plutonium budget from Los Alamos is associated with relatively coarse sediment which often behaves as bedload in the Rio Grande. Infusion of these materials into the main stream were largest in 1951, 1952, 1957, and 1968. Because of the schedule of delivery of plutonium to Los Alamos for experimentation and weapons manufacturing, the latter two years are probably the most important. Although the Los Alamos contribution to the entire plutonium budget was relatively small, in these four critical years it constituted 71--86 percent of the plutonium in bedload immediately downstream from Otowi.

  5. Width of the Confining String in Yang-Mills Theory

    SciTech Connect (OSTI)

    Gliozzi, F.; Pepe, M.; Wiese, U.-J.

    2010-06-11

    We investigate the transverse fluctuations of the confining string connecting two static quarks in (2+1)D SU(2) Yang-Mills theory using Monte Carlo calculations. The exponentially suppressed signal is extracted from the large noise by a very efficient multilevel algorithm. The resulting width of the string increases logarithmically with the distance between the static quark charges. Corrections at intermediate distances due to universal higher-order terms in the effective string action are calculated analytically. They accurately fit the numerical data.

  6. Evapotranspiration And Geochemical Controls On Groundwater Plumes At Arid Sites: Toward Innovative Alternate End-States For Uranium Processing And Tailings Facilities

    SciTech Connect (OSTI)

    Looney, Brian B.; Denham, Miles E.; Eddy-Dilek, Carol A.; Millings, Margaret R.; Kautsky, Mark

    2014-01-08

    Management of legacy tailings/waste and groundwater contamination are ongoing at the former uranium milling site in Tuba City AZ. The tailings have been consolidated and effectively isolated using an engineered cover system. For the existing groundwater plume, a system of recovery wells extracts contaminated groundwater for treatment using an advanced distillation process. The ten years of pump and treat (P&T) operations have had minimal impact on the contaminant plume primarily due to geochemical and hydrological limits. A flow net analysis demonstrates that groundwater contamination beneath the former processing site flows in the uppermost portion of the aquifer and exits the groundwater as the plume transits into and beneath a lower terrace in the landscape. The evaluation indicates that contaminated water will not reach Moenkopi Wash, a locally important stream. Instead, shallow groundwater in arid settings such as Tuba City is transferred into the vadose zone and atmosphere via evaporation, transpiration and diffuse seepage. The dissolved constituents are projected to precipitate and accumulate as minerals such as calcite and gypsum in the deep vadose zone (near the capillary fringe), around the roots of phreatophyte plants, and near seeps. The natural hydrologic and geochemical controls common in arid environments such as Tuba City work together to limit the size of the groundwater plume, to naturally attenuate and detoxify groundwater contaminants, and to reduce risks to humans, livestock and the environment. The technical evaluation supports an alternative beneficial reuse (brownfield) scenario for Tuba City. This alternative approach would have low risks, similar to the current P&T scenario, but would eliminate the energy and expense associated with the active treatment and convert the former uranium processing site into a resource for future employment of local citizens and ongoing benefit to the Native American Nations.

  7. Students from Grand Junction High School Triumph in Colorado Science Bowl

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Grand Junction High School Triumph in Colorado Science Bowl For more information contact: e:mail: Public Affairs Golden, Colo., Feb. 12, 2000 - Students from Grand Junction High School won top honors at the Colorado Science Bowl today at the Colorado School of Mines in Golden. In the final round of rapid-fire questions about physics, math, biology, astronomy, chemistry, computers and the earth sciences, students from Grand Junction were victorious over one of two teams from Douglas County High

  8. Statement by Energy Secretary Steven Chu on Today's Grand Opening of the

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Nordex Manufacturing Facility in Jonesboro, Arkansas | Department of Energy Today's Grand Opening of the Nordex Manufacturing Facility in Jonesboro, Arkansas Statement by Energy Secretary Steven Chu on Today's Grand Opening of the Nordex Manufacturing Facility in Jonesboro, Arkansas October 29, 2010 - 12:00am Addthis WASHINGTON, D.C. - U.S. Energy Secretary Steven Chu issued the following statement on today's grand opening of the Nordex wind turbine manufacturing facility in Jonesboro. The

  9. Secretary Chu to Deliver Keynote on EV Everywhere Grand Challenge at

    Energy Savers [EERE]

    Washington Auto Show | Department of Energy Keynote on EV Everywhere Grand Challenge at Washington Auto Show Secretary Chu to Deliver Keynote on EV Everywhere Grand Challenge at Washington Auto Show January 30, 2013 - 1:37pm Addthis NEWS MEDIA CONTACT (202) 586-4940 WASHINGTON - Tomorrow, Thursday, January 31, 2013, Secretary Chu will deliver the government keynote address at the Washington Auto Show's Public Policy Day. His remarks will focus on the Energy Department's EV Everywhere Grand

  10. Monitoring of the Airport Calibration Pads at Walker Field, Grand Junction,

    Office of Environmental Management (EM)

    Colorado, for Long-Term Radiation Variations (August 1978) | Department of Energy of the Airport Calibration Pads at Walker Field, Grand Junction, Colorado, for Long-Term Radiation Variations (August 1978) Monitoring of the Airport Calibration Pads at Walker Field, Grand Junction, Colorado, for Long-Term Radiation Variations (August 1978) Monitoring of the Airport Calibration Pads at Walker Field, Grand Junction, Colorado, for Long-Term Radiation Variations (August 1978) PDF icon Monitoring

  11. EIS-0519: Rio Grande LNG Project and Rio Bravo Pipeline Project...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Kenedy, Willacy, and Cameron Counties, Texas EIS-0519: Rio Grande LNG Project and Rio Bravo Pipeline Project; Kleberg, Kenedy, Willacy, and Cameron Counties, Texas Summary ...

  12. EIS-0344: Grand Coulee-Bell 500 kV Transmission Line

    Broader source: Energy.gov [DOE]

    This EIS analyzes DOE's proposed action for the construction and operation of the proposed Grand Coulee-Bell 500-kV Transmission Line Project.

  13. EV Everywhere Battery Workshop: Setting the Stage for the EV Everywhere Grand Challenge

    Broader source: Energy.gov [DOE]

    Presentation given at the EV Everywhere Grand Challenge: Battery Workshop by EERE Assistant Secretary David Danielson on July 26, 2012 at the Doubletree O'Hare, Chicago, IL.

  14. Feasibility for Reintroducing Sockeye and Coho Salmon in the Grande Ronde Basin, 1998 Final Report.

    SciTech Connect (OSTI)

    Cramer, Steven P.; Witty, Kenneth L.

    1998-07-01

    A report concerning the feasibility of reintroducing Sockeye Salmon into Wallowa Lake and Coho Salmon into the Grande Ronde River Basin.

  15. SunShot Grand Challenge Highlights Ambitious Efforts along the Entire Solar Spectrum

    Broader source: Energy.gov [DOE]

    Today at the SunShot Grand Challenge Summit in Denver, Energy Secretary Steven Chu lauded progress in driving down the cost of solar.

  16. Media Invitation: 2014 SunShot Grand Challenge Summit and Peer Review |

    Office of Environmental Management (EM)

    Department of Energy Media Invitation: 2014 SunShot Grand Challenge Summit and Peer Review Media Invitation: 2014 SunShot Grand Challenge Summit and Peer Review April 14, 2014 - 4:27pm Addthis Media Invitation: 2014 SunShot Grand Challenge Summit and Peer Review You're Invited: 2014 SunShot Grand Challenge Summit and Peer Review Hear from solar's brightest visionaries about what's on the horizon for the U.S. solar energy industry WASHINGTON, D.C. -- Members of the media are invited to attend

  17. Site-specific study on stabilization of acid-generating mine tailings using coal fly ash

    SciTech Connect (OSTI)

    Shang, J.Q.; Wang, H.L.; Kovac, V.; Fyfe, J.

    2006-03-15

    A site-specific study on stabilizing acid-generating mine tailings from Sudbury Mine using a coal fly ash from Nanticoke Generating Station is presented in this paper. The objective of the study is to evaluate the feasibility of codisposal of the fly ash and mine tailings to reduce environmental impacts of Sudbury tailings disposal sites. The study includes three phases, i.e., characterization of the mine tailings, and coal fly ash, oxidation tests on the mine tailings and kinetic column permeation tests. The results of the experiments indicate that when permeated with acid mine drainage, the hydraulic conductivity of Nanticoke coal fly ash decreased more than three orders of magnitude (from 1 x 10{sup -6} to 1 x 10{sup -9} cm/s), mainly due to chemical reactions between the ash solids and acid mine drainage. Furthermore, the hydraulic gradient required for acid mine drainage to break through the coal fly ash is increased up to ten times (from 17 to 150) as compared with that for water. The results also show that the leachate from coal fly ash neutralizes the acidic pore fluid of mine tailings. The concentrations of trace elements in effluents from all kinetic column permeation tests indicated that coplacement of coal fly ash with mine tailings has the benefit of immobilizing trace elements, especially heavy metals. All regulated element concentrations from effluent during testing are well below the leachate quality criteria set by the local regulatory authority.

  18. Precision welding cuts downtime at Grand Coulee Dam

    SciTech Connect (OSTI)

    Light, S.; White, E.

    1997-03-01

    The three large 700-MW generators at Grand Coulee Dam--originally built and installed by Canadian General Electric in the late 1970s--are being upgraded using precision welding techniques and leading edge installation technology. These generators suffered from numerous water leaks at and around the bar water connections, resulting in a significant number of forced repair outages that were increasing in frequency. The US Bureau of Reclamation, in conjunction with the Bonneville Power Administration, decided to overhaul these machines. The design from Siemens Power Corp. provided state-of-the-art materials and included a rating increase from 700 to 805 MW, which would make these three machines the highest output single-unit hydrogenerators in the world. The upgrade was to be accomplished with only the replacement of the stator components; there would be no changes to the rotating element. The cost for all three machines is approximately $27.5 million. This project is described in this paper.

  19. Grande Ronde Basin Fish Habitat Enhancement Project : 2007 Annual Report.

    SciTech Connect (OSTI)

    McGowan, Vance R.; Morton, Winston H.

    2008-12-30

    On July 1, 1984 the Bonneville Power Administration and the Oregon Department of Fish and Wildlife entered into an intergovernmental contract to initiate fish habitat enhancement work in the Joseph Creek subbasin of the Grande Ronde River Basin in northeast Oregon. In 1985 the Upper and Middle Grande Ronde River, and Catherine Creek subbasins were included in the contract, and in 1996 the Wallowa River subbasin was added. The primary goal of 'The Grande Ronde Basin Fish Habitat Enhancement Project' is to create, protect, and restore riparian and instream habitat for anadromous salmonids, thereby maximizing opportunities for natural fish production within the basin. This project provided for implementation of Program Measure 703 (C)(1), Action Item 4.2 of the Northwest Power Planning Council's Columbia River Basin Fish and Wildlife Program (NPPC, 1987), and continues to be implemented as offsite mitigation for mainstem fishery losses caused by the Columbia River hydro-electric system. All work conducted by the Oregon Department of Fish and Wildlife and partners is on private lands and therefore requires that considerable time be spent developing rapport with landowners to gain acceptance of, and continued cooperation with this program throughout 10-15 year lease periods. Both passive and active restoration treatment techniques are used. Passive regeneration of habitat, using riparian exclosure fencing and alternate water sources are the primary method to restore degraded streams when restoration can be achieved primarily through changes in management. Active restoration techniques using plantings, bioengineering, site-specific instream structures, or whole stream channel alterations are utilized when streams are more severely degraded and not likely to recover in a reasonable timeframe. Individual projects contribute to and complement ecosystem and basin-wide watershed restoration efforts that are underway by state, federal, and tribal agencies, and coordinated by the Grande Ronde Model Watershed Program (Project. No.199202601). Work undertaken during 2007 included: (1) Starting 1 new fencing project in the NFJD subbasin that will protect an additional 1.82 miles of stream and 216.2 acres of habitat; (2) Constructing 0.47 miles of new channel on the Wallowa River to enhance habitat, restore natural channel dimensions, pattern and profile and reconnect approximately 18 acres of floodplain and wetland habitat; (3) Planting 22,100 plants along 3 streams totaling 3.6 stream miles; (4) Establishing 34 new photopoints on 5 projects and retaking 295 existing photopoint pictures; (5) Monitoring stream temperatures at 10 locations on 5 streams and conducting other monitoring activities; (6) Completing riparian fence, water gap and other maintenance on 116.8 miles of project fences; (7) Initiated writing of a comprehensive project summary report that will present a summary of conclusions of the benefits to focal species and management recommendations for the future. Since initiation of this program 56 individual projects have been implemented, monitored and maintained along 84.8 miles of anadromous fish bearing streams that protect and enhance 3,501 acres of riparian and instream habitat.

  20. DOE - Office of Legacy Management -- Bodo Canyon Cell - 006

    Office of Legacy Management (LM)

    Bodo Canyon Cell - 006 FUSRAP Considered Sites Site: Bodo Canyon Cell (006) Designated Name: Alternate Name: Location: Evaluation Year: Site Operations: Site Disposition: Radioactive Materials Handled: Primary Radioactive Materials Handled: Radiological Survey(s): Site Status: All of the uranium mill tailings and other residual radioactive materials from the Durango mill site were disposed of in this dedicated disposal cell. The Department of Energy¿s Grand Junction Office is responsible for

  1. DOE - Office of Legacy Management -- Cheney Disposal Cell - 008

    Office of Legacy Management (LM)

    Cheney Disposal Cell - 008 FUSRAP Considered Sites Site: Cheney Disposal Cell (008) Designated Name: Alternate Name: Location: Evaluation Year: Site Operations: Site Disposition: Radioactive Materials Handled: Primary Radioactive Materials Handled: Radiological Survey(s): Site Status: All of the uranium mill tailings and other residual radioactive materials from the former Grand Junction uranium mill site were disposed of in this dedicated disposal cell. The cell is authorized to remain open

  2. Moab Project Exceeds 5 Years of Operations Without Lost-Time Injury, Illness

    Broader source: Energy.gov [DOE]

    GRAND JUNCTION, Colo. – It has been more than five years since workers on the Moab Uranium Mill Tailings Remedial Action Project in Utah had a lost-time injury or illness. This represents roughly 2.2 million hours of safe work.

  3. Moab Project Logs 2 Million Work Hours Without Lost-Time Injury or Illness

    Broader source: Energy.gov [DOE]

    GRAND JUNCTION, Colo. – The number 1,584 may not mean much to most people, but for the workers on EM’s Moab Uranium Mill Tailings Remedial Action Project, it represents the number of days without a work-related, lost-time injury or illness, as defined by the Occupational Safety and Health Administration.

  4. Scientific Grand Challenges Workshop Series | U.S. DOE Office of Science

    Office of Science (SC) Website

    (SC) Scientific Grand Challenges Workshop Series Advanced Scientific Computing Research (ASCR) ASCR Home About Research Facilities Science Highlights Benefits of ASCR Funding Opportunities Advanced Scientific Computing Advisory Committee (ASCAC) Community Resources ASCR Discovery Monthly News Roundup News Archives ASCR Program Documents ASCR Workshops and Conferences Workshops & Conferences Archive DOE Simulations Summit Scientific Grand Challenges Workshop Series SciDAC Conferences HPC

  5. Low Probability Tail Event Analysis and Mitigation in the BPA Control Area

    SciTech Connect (OSTI)

    Lu, Shuai; Brothers, Alan J.; McKinstry, Craig A.; Jin, Shuangshuang; Makarov, Yuri V.

    2010-10-31

    This report investigated the uncertainties with the operations of the power system and their contributions to tail events, especially under high penetration of wind. A Bayesian network model is established to quantify the impact of these uncertainties on system imbalance. The framework is presented for a decision support tool, which can help system operators better estimate the need for balancing reserves and prepare for tail events.

  6. Model for Eukaryotic Tail-anchored Protein Binding Based on the Structure

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    of Get3 Model for Eukaryotic Tail-anchored Protein Binding Based on the Structure of Get3 Targeting of newly synthesized membrane proteins to the endoplasmic reticulum (ER) is an important cellular process. Most membrane proteins are recognized and targeted co-translationally by the signal recognition particle (SRP). A number of membrane proteins (eg. SNAREs, apoptosis factors, and protein translocation components) are 'tail-anchored' by a single carboxy-terminal transmembrane domain. Due to

  7. shippip.PDF

    Office of Legacy Management (LM)

    6-TAR MAC-GWSHP 7.1 Public Involvement Plan for the Environmental Assessment of Ground Water Compliance at the Shiprock, New Mexico, Uranium Mill Tailings Remedial Action (UMTRA) Project Site February 2001 Prepared by U.S. Department of Energy Grand Junction Office Grand Junction, Colorado Work performed under DOE Contract No. DE-AC13-96GJ8733 Public Involvement Plan for the Shiprock UMTRA Site Page ii Contents Regulatory

  8. Microsoft Word - U0159200June.doc

    Office of Legacy Management (LM)

    U0159200 GJO-2002-312-TAR GWMON-28.7-1 U.S. Department of Energy UMTRA Ground Water Research Project Phytoremediation of Nitrogen Contamination in Subpile Soils and in the Alluvial Aquifer at the Monument Valley, Arizona, Uranium Mill Tailings Site June 2002 Environmental Research Laboratory University of Arizona, Tucson, Arizona Environmental Sciences Laboratory U.S. Department of Energy Grand Junction Office Grand Junction, Colorado This page intentionally left blank Acknowledgements This

  9. DOE - Office of Legacy Management -- GJD

    Office of Legacy Management (LM)

    Disposal Site UMTRCA Title I site gjd_map The Grand Junction disposal site is a Uranium Mill Tailings Radiation Control Act (UMTRCA) Title I site. Responsibility for custody and long-term management of the site transferred to DOE's Office of Legacy Management in 2003. Management responsibilities include routine inspection and maintenance of the disposal site, records-related activities, and stakeholder support. For more information about the Grand Junction disposal site, view the fact sheet.

  10. DOE - Office of Legacy Management -- GJP

    Office of Legacy Management (LM)

    Processing Site UMTRCA Title I site gjp_map The Grand Junction processing site is a Uranium Mill Tailings Radiation Control Act (UMTRCA) Title I site. Responsibility for management and long-term custody of the site's contaminated groundwater transferred to DOE's Office of Legacy Management in 2003. Management requirements include routine inspection and maintenance of groundwater monitoring wells, records-related activities, and stakeholder support. For more information about the Grand Junction

  11. F:\SHARE\SE\Web_Origs\Wrk_Jan\00-082\PIP2FCT.PDF

    Office of Legacy Management (LM)

    GWFCT 11.6.2 Public Involvement Plan for the Environmental Assessment of Ground Water Compliance Activities at the Uranium Mill Tailings Site, Falls City, Texas November 1997 Prepared for U.S. Department of Energy Albuquerque Operations Office Grand Junction Office Prepared by MACTEC Environmental Restoration Services, L.L.C. Grand Junction, Colorado Work performed under DOE Contract No. DE-AC13-96GJ87335 1 Public Involvement Plan for the Environmental Assessment of Ground Water Compliance

  12. DISCLAIMER

    Office of Legacy Management (LM)

    DOEIEA-1313 Rev. 0 Environmental Assessment of Ground Water Compliance at the Monument Valley Uranium Mill Tailings Site Draft September 1999 Prepared by U.S. Department of Energy Grand Junction Office Grand Junction, Colorado Work Performed Under DOE Contract No. DE-AC13-96GJ87335 for the U.S. Department of Energy Document Number UW69700 This Page Intentionally Blank Contents Page . . ................................... ................................................................ Acronyms

  13. DOE - Office of Legacy Management -- GJD

    Office of Legacy Management (LM)

    Disposal Site Key Documents and Links All documents are Adobe Acrobat files. pdf_icon Key Documents Fact Sheet 2014 Annual Site Inspection and Monitoring Report for Uranium Mill Tailings Radiation Control Act Title I Disposal Sites-Grand Junction, Colorado, Disposal Site August 2015 Groundwater Sampling at the Grand Junction, Colorado, Disposal Site Long-Term Surveillance Plan Please be green. Do not print these documents unless absolutely necessary. Submit a FOIA Request for documents not

  14. EA-1312: Final Environmental Assessment | Department of Energy

    Office of Environmental Management (EM)

    2: Final Environmental Assessment EA-1312: Final Environmental Assessment Ground Water Compliance at the Grand Junction UMTRA Project Site (Climax Uranium Millsite) This document is the Environmental Assessment (EA) for the proposed action to address ground water contamination at the Uranium Mill Tailings Remedial Action (UMTRA) Project site in Grand Junction, Colorado. This site is also known as the former Climax uranium millsite. The purpose of this EA is to present the proposed action and

  15. Fluctuations destroying long-range order in SU(2) Yang-Mills theory

    Office of Scientific and Technical Information (OSTI)

    (Journal Article) | SciTech Connect Fluctuations destroying long-range order in SU(2) Yang-Mills theory Citation Details In-Document Search Title: Fluctuations destroying long-range order in SU(2) Yang-Mills theory We study lattice SU(2) Yang-Mills theory with dimension d{>=}4. The model can be expressed as a (d-1)-dimensional O(4) nonlinear {sigma} model in a d-dimensional heat bath. As is well known, the nonlinear {sigma} model alone shows a phase transition. If the quark confinement is

  16. EERE Success Story-Steel Mill Powered by Waste Heat Recovery System |

    Office of Environmental Management (EM)

    Department of Energy Steel Mill Powered by Waste Heat Recovery System EERE Success Story-Steel Mill Powered by Waste Heat Recovery System May 16, 2013 - 12:00am Addthis EERE worked with ArcelorMittal USA, Inc. to install an efficient recovery boiler to burn blast furnace gases generated during iron-making operations to produce electricity and steam onsite at the company's Indiana Harbor Steel Mill in East Chicago, Indiana. The steam is being used to drive existing turbogenerators onsite,

  17. Top 5 Reasons to Attend the SunShot Grand Challenge Solar Summit |

    Broader source: Energy.gov (indexed) [DOE]

    Department of Energy <a href="http://energy.gov/eere/sunshot-summit/registration">Register by May 9</a> to attend the SunShot Grand Challenge Summit, May 19-22, 2014. Register by May 9 to attend the SunShot Grand Challenge Summit, May 19-22, 2014. Minh Le Minh Le Director, Solar Energy Technologies Office Anticipation for the second SunShot Grand Challenge Summit is heating up. The four-day event in sunny Anaheim, California will bring together hundreds of private- and

  18. Solar Community Comes Out in Full Force for SunShot Grand Challenge Summit

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    | Department of Energy Community Comes Out in Full Force for SunShot Grand Challenge Summit Solar Community Comes Out in Full Force for SunShot Grand Challenge Summit May 22, 2014 - 10:13am Addthis Packed House 1 of 12 Packed House An energetic crowd of hundreds of leaders throughout the solar community gathered for the 2014 SunShot Grand Challenge Summit to work together to reduce the costs of solar energy technologies. Image: SunShot Initiative, Energy Department. Solar Tech Forum 2 of 12

  19. SunShot Grand Challenge Summit and Peer Review 2014 | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    SunShot Grand Challenge Summit and Peer Review 2014 SunShot Grand Challenge Summit and Peer Review 2014 May 19, 2014 4:00PM PDT to May 22, 2014 8:00PM PDT The 2014 SunShot Grand Challenge Summit and Peer Review brought together more than 800 members of the solar energy community to review the progress made toward the SunShot Initiative's 2014 affordability goal and discuss the challenges ahead to make solar energy more affordable and widespread across America. Media Resources Press Release:

  20. Grand challenge problems in environmental modeling and remediation: Groundwater contaminant transport. Final project report 1998

    SciTech Connect (OSTI)

    1998-04-01

    The over-reaching goal of the Groundwater Grand Challenge component of the Partnership in Computational Science (PICS) was to develop and establish the massively parallel approach for the description of groundwater flow and transport and to address the problem of uncertainties in the data and its interpretation. This necessitated the development of innovative algorithms and the implementation of massively parallel computational tools to provide a suite of simulators for groundwater flow and transport in heterogeneous media. This report summarizes the activities and deliverables of the Groundwater Grand Challenge project funded through the High Performance Computing grand challenge program of the Department of Energy from 1995 through 1997.

  1. Grand Opening for Project LIBERTY: Nation's First Plant to Use Corn Waste

    Office of Environmental Management (EM)

    as a Feedstock | Department of Energy Grand Opening for Project LIBERTY: Nation's First Plant to Use Corn Waste as a Feedstock Grand Opening for Project LIBERTY: Nation's First Plant to Use Corn Waste as a Feedstock August 28, 2014 - 12:33pm Addthis POET-DSM's Project LIBERTY in Emmetsburg, Iowa, will celebrate its grand opening September 3, 2014, becoming the first commercial-scale cellulosic ethanol plant to use corn waste as a feedstock. Developed through a joint venture between POET LLC

  2. Highlights from the 2014 SunShot Grand Challenge Summit | Department of

    Office of Environmental Management (EM)

    Energy Highlights from the 2014 SunShot Grand Challenge Summit Highlights from the 2014 SunShot Grand Challenge Summit Addthis Packed House 1 of 12 Packed House An energetic crowd of hundreds of leaders throughout the solar community gathered for the 2014 SunShot Grand Challenge Summit to work together to reduce the costs of solar energy technologies. Image: SunShot Initiative, Energy Department. Solar Tech Forum 2 of 12 Solar Tech Forum Attendees enter the SunShot Summit Technology forum --

  3. Solar Community Comes Out in Full Force for SunShot Grand Challenge Summit

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    | Department of Energy Solar Community Comes Out in Full Force for SunShot Grand Challenge Summit Solar Community Comes Out in Full Force for SunShot Grand Challenge Summit May 22, 2014 - 9:58am Addthis This week in sunny Anaheim, California, more than 800 solar industry leaders gathered for the 2014 SunShot Grand Challenge Summit. The Summit, launched by the Energy Department's SunShot Initiative, brings together the solar community to network, share ideas and develop strategies to make

  4. From Flour to Grits, a Water-Powered Mill Keeps on Grinding

    Broader source: Energy.gov [DOE]

    A mill owned and operated for six generations by the Weisenberger family has been grinding grains in the heart of Kentucky since the Civil War. In 1862, August Weisenberger emigrated from Baden,...

  5. EERE Success Story—From Flour to Grits, a Water-Powered Mill Keeps on Grinding

    Broader source: Energy.gov [DOE]

    By 1913, the old mill had become structurally unsound and was demolished and later rebuilt. The family also replaced the water wheel with more efficient twin hydropower turbine and generator units,...

  6. Longest-Serving Active Paper Mill in the Western United States...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Western United States Uncovers New Ways to Save Energy This case study describes how West Linn Paper Company's coated paper mill in West Linn, Oregon, saved nearly 58,200 MMBtu...

  7. Subject: Proposed 216(h) Regulations To: Brian.Mills@hq.doe...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    February 12, 2012 Subject: Proposed 216(h) Regulations To: Brian.Mills@hq.doe.gov and Lot.Cooke@hq.doe.gov. We appreciate the opportunity to review the Proposed Regulation for ...

  8. A GRAND DESIGN FOR GALAXY CLUSTERS: CONNECTIONS AND PREDICTIONS

    SciTech Connect (OSTI)

    Cavaliere, A.; Lapi, A.; Fusco-Femiano, R.

    2011-11-20

    We analyze with our entropy-based Supermodel a library of 12 galaxy clusters featuring extended X-ray observations of their intracluster plasma (ICP). The few intrinsic parameters of the model-basically, the central level and the outer slope of the entropy profile-enable us to uniformly derive not only robust snapshots of the ICP thermal state, but also the 'concentration' parameter marking the age of the host dark matter (DM) halo. We test these profiles for consistency with numerical simulations and observations. We find the central and the outer entropy correlate, so that these clusters split into two main classes defined on the basis of low (LE) or high entropy (HE) conditions prevailing throughout the ICP. We also find inverse correlations between the central/outer entropy and the halo concentration. We interpret these in terms of mapping the ICP progress on timescales around 5 Gyr toward higher concentrations, under the drive of the DM halo development. The progress proceeds from HE clusters to LE clusters, toward states of deeper entropy erosion by radiative cooling in the inner regions and of decreasing outer entropy production as the accretion peters out. We propose these radial and time features constitute a cluster Grand Design that we use here to derive a number of predictions. For HE clusters we predict sustained outer temperature profiles. For LEs we expect the outer entropy ramp to bend over; hence the temperature declines before steepening at low z; this feature goes together with an increasing turbulent support, a condition that can be directly probed with the Sunyaev-Zel'dovich effect. We finally discuss the looming out of two intermediate subsets: a wiggled HE-tilde at low z that features central temperature profiles retaining imprints of entropy discharged by active galactic nuclei or deep mergers and high-z LEs where the cosmogony/cosmology had little time to enforce a sharp outer entropy bending.

  9. High performance computing and communications grand challenges program

    SciTech Connect (OSTI)

    Solomon, J.E.; Barr, A.; Chandy, K.M.; Goddard, W.A., III; Kesselman, C.

    1994-10-01

    The so-called protein folding problem has numerous aspects, however it is principally concerned with the {ital de novo} prediction of three-dimensional (3D) structure from the protein primary amino acid sequence, and with the kinetics of the protein folding process. Our current project focuses on the 3D structure prediction problem which has proved to be an elusive goal of molecular biology and biochemistry. The number of local energy minima is exponential in the number of amino acids in the protein. All current methods of 3D structure prediction attempt to alleviate this problem by imposing various constraints that effectively limit the volume of conformational space which must be searched. Our Grand Challenge project consists of two elements: (1) a hierarchical methodology for 3D protein structure prediction; and (2) development of a parallel computing environment, the Protein Folding Workbench, for carrying out a variety of protein structure prediction/modeling computations. During the first three years of this project, we are focusing on the use of two proteins selected from the Brookhaven Protein Data Base (PDB) of known structure to provide validation of our prediction algorithms and their software implementation, both serial and parallel. Both proteins, protein L from {ital peptostreptococcus magnus}, and {ital streptococcal} protein G, are known to bind to IgG, and both have an {alpha} {plus} {beta} sandwich conformation. Although both proteins bind to IgG, they do so at different sites on the immunoglobin and it is of considerable biological interest to understand structurally why this is so. 12 refs., 1 fig.

  10. SURVEY OF ROLLING MILL USED BY BETHLEHEM STEEL CORPORATION LACKAWANNA, NEW YORK

    Office of Legacy Management (LM)

    SURVEY OF ROLLING MILL USED BY BETHLEHEM STEEL CORPORATION LACKAWANNA, NEW YORK Work performed by the Health and Safety Research Division Gak Ridge fiational Laboratory Oak Ridge, Tennessee 37830 September 1980 OAK RIDGE NATIONAL LABORATORY operated by UNION CARBIDE CORPORATION for the DEPARTMENT OF ENERGY as part of the Formerly Utilized Sites!- Remedial Action Program SURVEY OF ROLLING MILL USED BY BETHLEHEM STEEL CORPORATION LACKAWANNA, NEW YORK A radiological survey was conducted at the

  11. Structural and microstructural changes in monoclinic ZrO{sub 2} during the ball-milling with stainless steel assembly

    SciTech Connect (OSTI)

    Stefanic, G. . E-mail: stefanic@irb.hr; Music, S.; Gajovic, A.

    2006-04-13

    High-energy ball-milling of monoclinic ZrO{sub 2} was performed in air using the planetary ball mill with a stainless steel milling assembly. Structural and microstructural changes during the ball-milling were monitored using X-ray powder diffraction, Raman spectroscopy, Moessbauer spectroscopy, field emission scanning electron microscopy and energy dispersive X-ray spectrometry. The results of line broadening analysis indicated a decrease in the crystallite size and an increase in the microstrains with the ball-milling time increased up to {approx}150 min. The results of quantitative phase analysis indicated the presence of a very small amount of tetragonal ZrO{sub 2} phase in this early stage of ball-milling. The onset of m-ZrO{sub 2} {sup {yields}} t-ZrO{sub 2} transition occurred between 10 and 15 h of ball-milling, which resulted in a complete transition after 20 h of ball-milling. Further ball-milling caused a decrease of the t-ZrO{sub 2} lattice parameters followed by a probable transition into c-ZrO{sub 2}. It was concluded that the stabilization of t- and c-ZrO{sub 2} polymorphs at RT can be attributed to the incorporation of aliovalent cations (Fe{sup 2+}, Fe{sup 3+} and Cr{sup 3+}) introduced into the sample due to the wear and oxidation of the milling media.

  12. Save the Date: 2014 SunShot Grand Challenge Summit, May 19-22...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    January 9, 2014 - 10:02am Addthis The SunShot Initiative at the U.S. Department of Energy (DOE) will host the second 2014 SunShot Grand Challenge Summit and Peer Review from May ...

  13. EIS-0485: Interconnection of the Grande Prairie Wind Farm, Holt County, Nebraska

    Broader source: Energy.gov [DOE]

    DOE’s Western Area Power Administration prepared an EIS to evaluate the environmental impacts of interconnecting the proposed Grande Prairie Wind Farm, in Holt County, near O’Neill, Nebraska, to Western’s power transmission system.

  14. Grand Challenges in Energy by Secretary Steven Chu | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    PDF icon Grand Challenges in Energy by Secretary Steven Chu More Documents & Publications Secretary Chu Speaks at SLAC National Accelerator Laboratory Growing the Future Bioeconomy Is the Energy Race our new "Sputnik" Moment?

  15. Monitoring Fine Sediment; Grande Ronde and John Day Rivers, 1999 Annual Report.

    SciTech Connect (OSTI)

    Rhodes, Jonathan J.; Greene, M. Jonas; Purser, Michael D.

    2000-01-01

    This project was initiated to monitor surface fine sediment levels and overwinter intrusion of fine sediment in spring chinook salmon spawning habitat in the North Folk John Day and Grande Ronde Rivers, for five years.

  16. DOE/Grand Junction Office Bluewater LTSP July 1997 Doc. No. S00012AA, Page iii

    Office of Legacy Management (LM)

    DOE/Grand Junction Office Bluewater LTSP July 1997 Doc. No. S00012AA, Page iii Contents Page 1.0 Introduction .........................................................................................................................................1 1.1 Purpose ................................................................................................................................1 1.2 Legal and Regulatory Requirements

  17. Save the Date: 2014 SunShot Grand Challenge Summit, May 19-22, Anaheim, CA

    Broader source: Energy.gov [DOE]

    The SunShot Initiative at the U.S. Department of Energy (DOE) will host the second 2014 SunShot Grand Challenge Summit and Peer Review from May 19-22 in Anaheim, California.

  18. Moab Project Safely Logs 2 Million Work Hours | Department of Energy

    Energy Savers [EERE]

    Safely Logs 2 Million Work Hours Moab Project Safely Logs 2 Million Work Hours March 12, 2014 - 12:00pm Addthis Empty containers on haul trucks are being loaded with mill tailings. Empty containers on haul trucks are being loaded with mill tailings. Media Contacts Donald Metzler, Moab Federal Project Director, (970) 257-2115 Wendee Ryan, S&K Aerospace Public Affairs Manager, (970) 257-2145 (Grand Junction, CO) - The number 1,584 may not mean much to most people, but for the workers on the

  19. Microsoft Word - S02459_2006Annual GW Rpt.doc

    Office of Legacy Management (LM)

    312-2006 Monticello Mill Tailings Site Operable Unit III Annual Ground Water Report October 2005 through April 2006 September 2006 Work Performed by S.M. Stoller Corporation under DOE Contract No. DE-AC01-02GJ79491 for the U.S. Department of Energy, Grand Junction, Colorado This page intentionally left blank U.S. Department of Energy Monticello Mill Tailings Site OU III Annual Ground Water Report October 2005-April 2006 September 2006 Doc. No. S0245900 Page iii Contents 1.0

  20. PartialDeletion for web.cdr

    Office of Legacy Management (LM)

    States Department of Energy Grand Junction Office F A C T S H E E T Partial Deletion of Monticello Mill Tailings Site From the National Priorities List July 2003 The U.S. Department of Energy has completed the cleanup of the Non-Surface and Ground-Water Impacted Peripheral Properties that are part of Operable Unit II of the Monticello (Utah) Mill Tailings Site. These properties can now be removed from the U.S. Environmental Protection Agency's National Priorities List. This fact sheet provides a

  1. DOE/EIS-0485 Final Environmental Impact Statement Grande Prairie Wind Farm

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    5 Final Environmental Impact Statement Interconnection of the Grande Prairie Wind Farm Holt County, Nebraska December 2014 COVER SHEET LEAD FEDERAL AGENCY: U.S. Department of Energy (DOE), Western Area Power Administration (Western) TITLE: Interconnection of the Grande Prairie Wind Farm, Holt County, Nebraska, DOE/EIS- 0485 CONTACT: For additional information on this Final Environmental Impact Statement (FEIS), contact: Matt Marsh Environmental Protection Specialist Western Area Power

  2. EV Everywhere Grand Challenge Kick-off Parameters and Analysis | Department

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    of Energy off Parameters and Analysis EV Everywhere Grand Challenge Kick-off Parameters and Analysis Presentation at the EV Everywhere Grand Challenge Kick-Off meeting held on June 21, 2012 at the Hyatt Regency, Dearborn, MI. PDF icon 4-jake.pdf More Documents & Publications EV Everywhere Electric Drive Workshop: Preliminary Target-Setting Framework EV Everywhere Battery Workshop: Preliminary Target-Setting Framework EV Everywhere Consumer/Charging Workshop: Target-Setting Framework and

  3. The emerging multi-polar world and China's grand game (Journal Article) |

    Office of Scientific and Technical Information (OSTI)

    SciTech Connect Journal Article: The emerging multi-polar world and China's grand game Citation Details In-Document Search Title: The emerging multi-polar world and China's grand game This talk outlines a scenario describing an emerging multipolar world that is aligned with geographical regions. The stability and security of this multipolar world is examined with respect to demographics, trade (economics), resource constraints, and development. In particular I focus on Asia which has two

  4. Grand Traverse Band of Ottawa & Chippewa Indians - Renewable Energy Feasibility Study

    Office of Environmental Management (EM)

    DOE Tribal Energy Program Review DOE Tribal Energy Program Review Denver, Colorado Denver, Colorado November 5 November 5 - - 8, 2007 8, 2007 Final Report Final Report December 2007 December 2007 Grand Traverse Band Grand Traverse Band * * 4,023 Members 4,023 Members * * 2,370 Acres 2,370 Acres - - Checkerboard Checkerboard * * Six Six - - County Service Area County Service Area * * EDC: 2 Casinos, Resort (424 Rooms), EDC: 2 Casinos, Resort (424 Rooms), Gas Station, etc. Gas Station, etc. * *

  5. Grand Traverse Band of Ottawa and Chippewa Indians - Renewable Energy Feasibility Study

    Office of Environmental Management (EM)

    DOE Tribal Energy Forum DOE Tribal Energy Forum October 25, 2006 October 25, 2006 Grand Traverse Band Grand Traverse Band * * 3,988 Members 3,988 Members * * 2,370 Acres 2,370 Acres - - Checkerboard Checkerboard * * Six Six - - County Service Area County Service Area * * EDC: 2 Casinos, Resort (424 Rooms), Gas EDC: 2 Casinos, Resort (424 Rooms), Gas Station, etc. Station, etc. * * Gov Gov ' ' t: Administration, Housing, Medicine t: Administration, Housing, Medicine Lodge, Strong Heart Center,

  6. Grand Traverse Band of Ottawa and Chippewa Indians - Renewable Energy Feasibility Study

    Office of Environmental Management (EM)

    Renewable Energy & Energy Efficiency Feasibility Study DOE Tribal Energy Program Review Denver, Colorado November 14 - 20, 2008 November 2008 Grand Traverse Band * 3,988 Members * 2,370 Acres - Checkerboard * Six-County Service Area * EDC: 2 Casinos, Resort Hotels (600 Rooms), Gas Station, etc. * Gov't: Administration, Housing, Medicine Lodge, Strong Heart Center, Day Care, etc. Grand Traverse Resort and Spa Turtle Creek Casino Hotel (June 08) GTB Energy Vision & Plan Three Focus Areas:

  7. EIS-0519: Rio Grande LNG Project and Rio Bravo Pipeline Project; Kleberg,

    Office of Environmental Management (EM)

    Kenedy, Willacy, and Cameron Counties, Texas | Department of Energy 9: Rio Grande LNG Project and Rio Bravo Pipeline Project; Kleberg, Kenedy, Willacy, and Cameron Counties, Texas EIS-0519: Rio Grande LNG Project and Rio Bravo Pipeline Project; Kleberg, Kenedy, Willacy, and Cameron Counties, Texas Summary The Federal Energy Regulatory Commission (FERC), with DOE as a cooperating agency, is preparing an EIS that analyzes the potential environmental impacts of a proposal to construct and

  8. A measurement of the cosmic microwave background damping tail from the

    Office of Scientific and Technical Information (OSTI)

    2500-square-degree SPT-SZ survey (Journal Article) | SciTech Connect A measurement of the cosmic microwave background damping tail from the 2500-square-degree SPT-SZ survey Citation Details In-Document Search Title: A measurement of the cosmic microwave background damping tail from the 2500-square-degree SPT-SZ survey We present a measurement of the cosmic microwave background (CMB) temperature power spectrum using data from the recently completed South Pole Telescope Sunyaev-Zel'dovich

  9. Moab Marks 6-Million-Ton Cleanup Milestone | Department of Energy

    Office of Environmental Management (EM)

    Moab Marks 6-Million-Ton Cleanup Milestone Moab Marks 6-Million-Ton Cleanup Milestone June 20, 2013 - 12:00pm Addthis At Tuesday's Grand County Council meeting in Utah, Moab Federal Project Director Donald Metzler, center, moves a piece from a plaque representing Moab’s uranium mill tailings pile to a plaque representing the disposal cell in recognition of the site achieving a milestone by shipping 6 million tons of the tailings. Grand County Council Chair Gene Ciarus is on the left and

  10. Geochemical Weathering Increases Lead Bioaccessibility in Semi-Arid Mine Tailings

    SciTech Connect (OSTI)

    Hayes, Sarah M.; Webb, Sam M.; Bargar, John R.; O?Day, Peggy A.; Maier, Raina M.; Chorover, Jon

    2012-09-05

    Mine tailings can host elevated concentrations of toxic metal(loid)s that represent a significant hazard to surrounding communities and ecosystems. Eolian transport, capable of translocating small (micrometer-sized) particles, can be the dominant mechanism of toxic metal dispersion in arid or semiarid landscapes. Human exposure to metals can then occur via direct inhalation or ingestion of particulates. The fact that measured doses of total lead (Pb) in geomedia correlate poorly with blood Pb levels highlights a need to better resolve the precise distribution of molecularly speciated metal-bearing phases in the complex particle mixtures. Species distribution controls bioaccessibility, thereby directly impacting health risk. This study seeks to correlate Pb-containing particle size and mineral composition with lability and bioaccessibility in mine tailings subjected to weathering in a semiarid environment. We employed X-ray absorption spectroscopy (XAS) and X-ray fluorescence (XRF), coupled with sequential chemical extractions, to study Pb speciation in tailings from the semiarid Arizona Klondyke State Superfund Site. Representative samples ranging in pH from 2.6 to 5.4 were selected for in-depth study of Pb solid-phase speciation. The principle lead-bearing phase was plumbojarosite (PbFe{sub 6}(SO{sub 4}){sub 4}(OH){sub 12}), but anglesite (PbSO{sub 4}) and iron oxide-sorbed Pb were also observed. Anglesite, the most bioavailable mineral species of lead identified in this study, was enriched in surficial tailings samples, where Pb concentrations in the clay size fraction were 2-3 times higher by mass relative to bulk. A mobile and bioaccessible Pb phase accumulates in surficial tailings, with a corresponding increase in risk of human exposure to atmospheric particles.

  11. Grande Ronde Basin Spring Chinook Salmon Captive Broodstock Program, 1995-2002 Summary Report.

    SciTech Connect (OSTI)

    Hoffnagle, Timothy; Carmichael, Richard; Noll, William

    2003-12-01

    The Grande Ronde Basin once supported large runs of chinook salmon Oncorhynchus tshawytscha and estimated peak escapements in excess of 10,000 occurred as recently as the late 1950's (U.S. Army Corps of Engineers 1975). Natural escapement declines in the Grande Ronde Basin have been severe and parallel those of other Snake River populations. Reduced productivity has primarily been attributed to increased mortality associated with downstream and upstream migration past eight dams and reservoirs in the Snake and Columbia rivers. Reduced spawner numbers, combined with human manipulation of previously important spawning and rearing habitat in the Grande Ronde Basin, have resulted in decreased spawning distribution and population fragmentation of chinook salmon in the Grande Ronde Basin (Figure 1; Table 1). Escapement of spring/summer chinook salmon in the Snake River basin included 1,799 adults in 1995, less than half of the previous record low of 3,913 adults in 1994. Catherine Creek, Grande Ronde River and Lostine River were historically three of the most productive populations in the Grande Ronde Basin (Carmichael and Boyce 1986). However, productivity of these populations has been poor for recent brood years. Escapement (based on total redd counts) in Catherine Creek and Grande Ronde and Lostine rivers dropped to alarmingly low levels in 1994 and 1995. A total of 11, 3 and 16 redds were observed in 1994 in Catherine Creek, upper Grande Ronde River and Lostine River, respectively, and 14, 6 and 11 redds were observed in those same streams in 1995. In contrast, the maximum number of redds observed in the past was 505 in Catherine Creek (1971), 304 in the Grande Ronde River (1968) and 261 in 1956 in the Lostine River (Tranquilli et al 2003). Redd counts for index count areas (a standardized portion of the total stream) have also decreased dramatically for most Grande Ronde Basin streams from 1964-2002, dropping to as low as 37 redds in the 119.5 km in the index survey areas in 1995 from as high as 1,205 redds in the same area in 1969 (Table 1). All streams reached low points (0-6 redds in the index areas) in the 1990's, except those in which no redds were found for several years and surveys were discontinued, such as Spring, Sheep and Indian creeks which had a total of 109 redds in 1969. The Minam and Wenaha rivers are tributaries of the Grande Ronde River located primarily in wilderness areas. Chinook salmon numbers in these two streams (based on redd counts) also decreased dramatically beginning in the early 1970's (Table 1). Since then there have been a few years of increasing numbers of redds but counts have generally been 25-40% of the number seen in the 1960's. No hatchery fish have been released into either of these streams and we monitor them during spawning ground surveys for the presence of hatchery strays. These populations will be used as a type of control for evaluating our supplementation efforts in Catherine Creek, upper Grande Ronde River and Lostine River. In this way, we can attempt to filter out the effects of downstream variables, over which we have no control, when we interpret the results of the captive broodstock program as the F1 and F2 generations spawn and complete their life cycles in the wild. The Grande Ronde Basin Captive Broodstock Program was initiated because these chinook salmon populations had reached critical levels where dramatic and unprecedented efforts were needed to prevent extinction and preserve any future options for use of endemic fish for artificial propagation programs for recovery and mitigation. This program was designed to quickly increase numbers of returning adults, while maintaining the genetic integrity of each endemic population.

  12. Radiating black holes in Einstein-Yang-Mills theory and cosmic censorship

    SciTech Connect (OSTI)

    Ghosh, Sushant G.; Dadhich, Naresh

    2010-08-15

    Exact nonstatic spherically symmetric black-hole solutions of the higher dimensional Einstein-Yang-Mills equations for a null dust with Yang-Mills gauge charge are obtained by employing Wu-Yang ansatz, namely, HD-EYM Vaidya solution. It is interesting to note that gravitational contribution of Yang-Mills (YM) gauge charge for this ansatz is indeed opposite (attractive rather than repulsive) that of Maxwell charge. It turns out that the gravitational collapse of null dust with YM gauge charge admits strong curvature shell focusing naked singularities violating cosmic censorship. However, there is significant shrinkage of the initial data space for a naked singularity of the HD-Vaidya collapse due to presence of YM gauge charge. The effect of YM gauge charge on structure and location of the apparent and event horizons is also discussed.

  13. Grand Challenges in Modeling, Simulation and Analysis: Extraction and Visualization of Power Systems

    SciTech Connect (OSTI)

    Fernandez, Steven J; Omitaomu, Olufemi A

    2010-01-01

    Threats to the national electric power grid often require the coupling of real-time state data with look-ahead or forecasting models to provide timely disruption warnings. However, successful accomplishment of this capability presents a grand challenge in modeling, simulation, and analysis. Analysis of inter-area oscillatory modes may provide a new path to anticipate power system stability and address this grand challenge. An algorithm is presented for the identification and analysis of such modes from high resolution phasor measurement data that might indicate a pathway to meet this grand challenge. The process outlined includes data collection, conditioning, extraction of the primary oscillatory frequency, and determination of participating areas of the system.

  14. Grande Ronde Endemic Spring Chinook Salmon Supplementation Program : Facility Operation and Maintenance Facilities, Annual Report 2003.

    SciTech Connect (OSTI)

    McLean, Michael L.; Seeger, Ryan; Hewitt, Laurie

    2004-01-01

    Anadromous salmonid stocks have declined in both the Grande Ronde River Basin (Lower Snake River Compensation Plan (LSRCP) Status Review Symposium 1998) and in the entire Snake River Basin (Nehlsen et al. 1991), many to the point of extinction. The Grande Ronde River Basin historically supported large populations of fall and spring chinook (Oncorhynchus tshawytscha), sockeye (O. nerka), and coho (O. kisutch) salmon and steelhead trout (O. mykiss) (Nehlsen et al. 1991). The decline of chinook salmon and steelhead populations and extirpation of coho and sockeye salmon in the Grande Ronde River Basin was, in part, a result of construction and operation of hydroelectric facilities, over fishing, and loss and degradation of critical spawning and rearing habitat in the Columbia and Snake River basins (Nehlsen et al. 1991). Hatcheries were built in Oregon, Washington and Idaho under the Lower Snake River Compensation Plan (LSRCP) to compensate for losses of anadromous salmonids due to the construction and operation of the lower four Snake River dams. Lookingglass Hatchery (LGH) on Lookingglass Creek, a tributary of the Grande Ronde River, was completed under LSRCP in 1982 and has served as the main incubation and rearing site for chinook salmon programs for Grande Ronde and Imnaha rivers in Oregon. Despite these hatchery programs, natural spring chinook populations continued to decline resulting in the National Marine Fisheries Service (NMFS) listing Snake River spring/summer chinook salmon as ''threatened'' under the federal Endangered Species Act (1973) on 22 April 1992. Continuing poor escapement levels and declining population trends indicated that Grande Ronde River basin spring chinook salmon were in imminent danger of extinction. These continuing trends led fisheries co-managers in the basin to initiate the Grande Ronde Endemic Spring Chinook Salmon Supplementation Program (GRESCSSP) in order to prevent extinction and preserve options for use of endemic fish stocks in future artificial propagation programs. The GRESCSSP was implemented in three Grande Ronde River basin tributaries; the Lostine and upper Grande Ronde rivers and Catherine Creek. The GRESCSSP employs two broodstock strategies utilizing captive and conventional brood sources. The captive brood program began in 1995, with the collection of parr from the three tributary areas. The conventional broodstock component of the program began in 1997 with the collection of natural adults returning to these tributary areas. Although LGH was available as the primary production facility for spring chinook programs in the Grande Ronde Basin, there were never any adult or juvenile satellite facilities developed in the tributary areas that were to be supplemented. An essential part of the GRESCSSP was the construction of adult traps and juvenile acclimation facilities in these tributary areas. Weirs were installed in 1997 for the collection of adult broodstock for the conventional component of the program. Juvenile facilities were built in 2000 for acclimation of the smolts produced by the captive and conventional broodstock programs and as release sites within the natural production areas of their natal streams. The Confederated Tribes of the Umatilla Indian Reservation (CTUIR) operate both the juvenile acclimation and adult trapping facilities located on Catherine Creek and the upper Grande Ronde River under this project. The Nez Perce Tribe (NPT) operate the facilities on the Lostine River under a sister project. Hatcheries were also built in Oregon, Washington and Idaho under the LSRCP to compensate for losses of summer steelhead due to the construction and operation of the lowest four Snake River dams. Despite these harvest-driven hatchery programs, natural summer steelhead populations continued to decline as evidenced by declining counts at Lower Granite Dam since 1995 (Columbia River Data Access in Real Time, DART) and low steelhead redd counts on index streams in the Grande Ronde Basin. Because of low escapement the Snake River summer steelhead were listed as threat

  15. Vibration mills in the manufacturing technology of slurry fuel from unbeneficiated coal sludge

    SciTech Connect (OSTI)

    E.G. Gorlov; A.I. Seregin; G.S. Khodakov [Institute for Fossil Fuels, Moscow (Russia)

    2008-08-15

    Coal-water slurry fuel (CWSF) is economically viable provided that its ash content does not exceed 30% and the amount water in the fuel is at most 45%. Two impoundments were revealed that have considerable reserves of waste coal useful for commercial manufacture of CWSF without the beneficiation step. One of the CWSF manufacture steps is the comminution of coal sludge to have a particle size required by the combustion conditions. Vibration mills, which are more compact and energy-intensive that drum mills, can be used in the CWSG manufacture process. The rheological characteristics of CWSF obtained from unbeneficiated waste coal were determined.

  16. Wildlife Mitigation and Restoration for Grand Coulee Dam: Blue Creek Project, Phase 1.

    SciTech Connect (OSTI)

    Merker, Christopher

    1993-04-01

    This report is a recommendation from the Spokane Tribe to the Northwest Power Planning Council (NPPC) for partial mitigation for the extensive wildlife and wildlife habitat losses on the Spokane Indian Reservation caused by the construction of Grand Coulee Dam. NPPC`s interim wildlife goal over the next 7 years for the Columbia hydropower system, is to protect, mitigate and enhance approximately 35% basin wide of the lost habitat units. Grand Coulee Dam had the greatest habitat losses of any Dams of the Wildlife Rule.

  17. Grande Ronde Basin Chinook Salmon Captive Brood and Conventional Supplementation Program, 2000 Annual Report.

    SciTech Connect (OSTI)

    Carmichael, Richard W.

    2003-03-01

    Endangered Species Permit Number 1011 (formerly Permit No. 973) authorizes ODFW to take listed spring chinook salmon juveniles from Catherine Creek (CC), Lostine River (LR) and Grande Ronde River (GR) for research and enhancement purposes. Modification 2 of this permit authorizes ODFW to take adults for spawning and the production and release of smolts for the Captive and Conventional broodstock programs. This report satisfies the requirement that an annual report be submitted. Herein we report on activities conducted and provide cursory data analyses for the Grande Ronde spring chinook salmon Captive and Conventional broodstock projects from 1 January-31 December 2000.

  18. 2014 SunShot Grand Challenge Summit Day Two Photos | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    2014 SunShot Grand Challenge Summit Day Two Photos 2014 SunShot Grand Challenge Summit Day Two Photos Addthis Day 2 Subprogram Overviews 9 1 of 39 Day 2 Subprogram Overviews 9 Photo Credit: SunShot Date taken: 2014-05-20 14:41 Day 2 Subprogram Overviews 8 2 of 39 Day 2 Subprogram Overviews 8 Photo Credit: SunShot Date taken: 2014-05-20 14:37 Day 2 Subprogram Overviews 7 3 of 39 Day 2 Subprogram Overviews 7 Photo Credit: SunShot Date taken: 2014-05-20 14:36 Day 2 Subprogram Overviews 6 4 of 39

  19. Energy Secretary Steven Chu to Attend Grand Opening of Recovery Act-Funded

    Energy Savers [EERE]

    A123 Systems Battery Plant | Department of Energy to Attend Grand Opening of Recovery Act-Funded A123 Systems Battery Plant Energy Secretary Steven Chu to Attend Grand Opening of Recovery Act-Funded A123 Systems Battery Plant September 10, 2010 - 12:00am Addthis Washington D.C. - This Monday, U.S. Energy Secretary Steven Chu will speak at the dedication ceremony for the largest lithium-ion automotive battery production facility in North America. Funded in part by $249 million from the

  20. Grand Junction Office Founder Honored at the Philip C. Leahy Memorial Park

    Broader source: Energy.gov (indexed) [DOE]

    Dedication and Open House | Department of Energy 4. Optimize the use of land and assets. plaque.png The memorial plaque was unveiled at the event. The U.S. Department of Energy (DOE) Office of Legacy Management (LM) held an open house and park dedication at the Grand Junction, Colorado, Office to commemorate its place in the Manhattan Project and Cold War histories. The park, located in the middle of the Grand Junction Office campus, was dedicated to Army Major (retired) Philip C. Leahy.

  1. Restoring The Azimuthal Symmetry Of Charged Particle Lateral Density In The Range Of KASCADE-Grande

    SciTech Connect (OSTI)

    Sima, O.; Rebel, H.; Apel, W. D.; Bekk, K.; Bozdog, H.; Daumiller, K.; Doll, P.; Engel, R.; Engler, J.; Finger, M.; Gils, H. J.; Haungs, A.; Heck, D.; Huege, T.; Isar, P. G.; Klages, H. O.; Mathes, H. J.; Mayer, H. J.; Milke, J.; Nehls, S.

    2010-11-24

    KASCADE-Grande, an extension of the former KASCADE experiment, is a multi-component Extensive Air Shower (EAS) experiment located in Karlsruhe Institute of Technology (Campus North), Germany. An important observable for analyzing the EAS is the lateral density of charged particles in the intrinsic shower plane. This observable is deduced from the basic information provided by the Grande scintillators - the energy deposit - first in the observation plane, by using a Lateral Energy Correction Function (LECF), then in the intrinsic shower plane, by applying an adequate mapping procedure. In both steps azimuthal.

  2. SunShot Shoots for the Moon with First Grand Challenge Event | Department

    Energy Savers [EERE]

    of Energy SunShot Shoots for the Moon with First Grand Challenge Event SunShot Shoots for the Moon with First Grand Challenge Event May 23, 2012 - 11:40am Addthis The Energy Department's SunShot Initiative focuses on making solar electricity cost-competitive by the end of the decade. | Photo courtesy of Dennis Schroeder/NREL. The Energy Department's SunShot Initiative focuses on making solar electricity cost-competitive by the end of the decade. | Photo courtesy of Dennis Schroeder/NREL.

  3. Energy Secretary Steven Chu to Attend Grand Opening of Recovery Act-Funded

    Office of Environmental Management (EM)

    A123 Systems Battery Plant | Department of Energy to Attend Grand Opening of Recovery Act-Funded A123 Systems Battery Plant Energy Secretary Steven Chu to Attend Grand Opening of Recovery Act-Funded A123 Systems Battery Plant September 10, 2010 - 12:00am Addthis Washington D.C. - This Monday, U.S. Energy Secretary Steven Chu will speak at the dedication ceremony for the largest lithium-ion automotive battery production facility in North America. Funded in part by $249 million from the

  4. SunShot Grand Challenge Summit: Bright Outlook to Achieve SunShot Goal |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy Grand Challenge Summit: Bright Outlook to Achieve SunShot Goal SunShot Grand Challenge Summit: Bright Outlook to Achieve SunShot Goal May 30, 2014 - 2:15pm Addthis Watch the video above to learn more about the Energy Department's SunShot Initiative, a national collaborative effort to make solar energy cost-competitive with other forms of electricity. Minh Le Minh Le Director, Solar Energy Technologies Office Last week, hundreds of solar energy leaders gathered in

  5. DuPont's Cellulosic Ethanol Grand Opening Marks a Milestone for the

    Office of Environmental Management (EM)

    Advanced Biofuels Industry | Department of Energy DuPont's Cellulosic Ethanol Grand Opening Marks a Milestone for the Advanced Biofuels Industry DuPont's Cellulosic Ethanol Grand Opening Marks a Milestone for the Advanced Biofuels Industry November 20, 2015 - 12:49pm Addthis DuPont’s cellulosic ethanol biorefinery in Nevada, Iowa, opened on October 30, 2015. | Photo courtesy of DuPont DuPont's cellulosic ethanol biorefinery in Nevada, Iowa, opened on October 30, 2015. | Photo courtesy

  6. F:\SHARE\SE\Web_Origs\Wrk_Jan\00-083\U00321.PDF

    Office of Legacy Management (LM)

    27 Rev. 0 Environmental Assessment of Ground-Water Compliance at the Falls City, Texas, Uranium Mill Tailings Site Final March 1998 Prepared for U.S. Department of Energy Albuquerque Operations Office Grand Junction Office Prepared by U.S. Department of Energy Grand Junction Office Grand Junction, Colorado Work Performed Under DOE Contract No. DE-AC13-96GJ87335 for the U.S. Department of Energy Note: Some of the section page numbers in the Table of Contents may not correspond to the page on

  7. Microsoft Word - GRJ 2008-final.doc

    Office of Legacy Management (LM)

    Grand Junction, Colorado Page 6-1 6.0 Grand Junction, Colorado, Disposal Site 6.1 Compliance Summary The Grand Junction, Colorado, Uranium Mill Tailings Radiation Control Act (UMTRCA) Title I Disposal Site, was inspected on March 21 and 26, 2008. The disposal cell and all associated surface water diversion and drainage structures were in good condition and functioning as designed. A portion of the disposal cell remains open and is operated by DOE to receive additional low-level radioactive waste

  8. Calculation of the fast ion tail distribution for a spherically symmetric hot spot

    SciTech Connect (OSTI)

    McDevitt, C. J.; Tang, X.-Z.; Guo, Z.; Berk, H. L.

    2014-10-15

    The fast ion tail for a spherically symmetric hot spot is computed via the solution of a simplified Fokker-Planck collision operator. Emphasis is placed on describing the energy scaling of the fast ion distribution function in the hot spot as well as the surrounding cold plasma throughout a broad range of collisionalities and temperatures. It is found that while the fast ion tail inside the hot spot is significantly depleted, leading to a reduction of the fusion yield in this region, a surplus of fast ions is observed in the neighboring cold plasma region. The presence of this surplus of fast ions in the neighboring cold region is shown to result in a partial recovery of the fusion yield lost in the hot spot.

  9. A HYDRODYNAMICAL SOLUTION FOR THE ''TWIN-TAILED'' COLLIDING GALAXY CLUSTER ''EL GORDO''

    SciTech Connect (OSTI)

    Molnar, Sandor M.; Broadhurst, Tom

    2015-02-10

    The distinctive cometary X-ray morphology of the recently discovered massive galaxy cluster ''El Gordo'' (ACT-CT J01024915; z= 0.87) indicates that an unusually high-speed collision is ongoing between two massive galaxy clusters. A bright X-ray ''bullet'' leads a ''twin-tailed'' wake, with the Sunyaev-Zel'dovich (SZ) centroid at the end of the northern tail. We show how the physical properties of this system can be determined using our FLASH-based, N-body/hydrodynamic model, constrained by detailed X-ray, SZ, and Hubble lensing and dynamical data. The X-ray morphology and the location of the two dark matter components and the SZ peak are accurately described by a simple binary collision viewed about 480 million years after the first core passage. We derive an impact parameter of ?300kpc, and a relative initial infall velocity of ?2250km s{sup 1} when separated by the sum of the two virial radii assuming an initial total mass of 2.15 10{sup 15} M {sub ?} and a mass ratio of 1.9. Our model demonstrates that tidally stretched gas accounts for the northern X-ray tail along the collision axis between the mass peaks, and that the southern tail lies off axis, comprising compressed and shock heated gas generated as the less massive component plunges through the main cluster. The challenge for ?CDM will be to find out if this physically extreme event can be plausibly accommodated when combined with the similarly massive, high-infall-velocity case of the Bullet cluster and other such cases being uncovered in new SZ based surveys.

  10. Environmental control technology for mining and milling low-grade uranium resources

    SciTech Connect (OSTI)

    Weakley, S.A.; Blahnik, D.E.; Long, L.W.; Bloomster, C.H.

    1981-04-01

    This study examined the type and level of wastes that would be generated in the mining and milling of U/sub 3/O/sub 8/ from four potential domestic sources of uranium. The estimated costs of the technology to control these wastes to different degrees of stringency are presented.

  11. MIL-L-87177 and CLT:X-10 Lubricants Improve Electrical Connector Fretting Corrosion Behavior

    SciTech Connect (OSTI)

    AUKLAND,NEIL R.; HANLON,JAMES T.

    1999-10-12

    We have conducted a fretting research project using MIL-L-87177 and CLT: X-10 lubricants on Nano-miniature connectors. When they were fretted without lubricant, individual connectors first exceeded our 0.5 ohm failure criteria from 2,341 to 45,238 fretting cycles. With additional fretting, their contact resistance increased to more than 100,000 ohms. Unmodified MIL-L-87177 lubricant delayed the onset of first failure to between 430,000 and over 20,000,000 fretting cycles. MIL-L-87177 modified by addition of Teflon powder delayed first failure to beyond 5 million fretting cycles. Best results were obtained when Teflon was used and also when both the straight and modified lubricants were poured into and then out of the connector. CLT: X-10 lubricant delayed the onset of first failure to beyond 55 million cycles in one test where a failure was actually observed and to beyond 20 million cycles in another that was terminated without failure. CLT: X-10 recovered an unlubricated connector driven deeply into failure, with six failed pins recovering immediately and four more recovering during an additional 420 thousand fretting cycles. MIL-L-87177 was not able to recover a connector under similar conditions.

  12. Grand Coulee Dam Wildlife Mitigation Program : Pygmy Rabbit Programmatic Management Plan, Douglas County, Washington.

    SciTech Connect (OSTI)

    Ashley, Paul

    1992-06-01

    The Northwest Power Planning Council and the Bonneville Power Administration approved the pygmy rabbit project as partial mitigation for impacts caused by the construction of Grand Coulee Dam. The focus of this project is the protection and enhancement of shrub-steppe/pygmy rabbit habitat in northeastern Washington.

  13. Comparative flow measurements: Grand Coulee pumping-generating plant unit P/G9. Final report

    SciTech Connect (OSTI)

    Heigel, L.; Lewey, A.B.; Greenwood, J.B.

    1986-10-01

    In extensive testing, two acoustic flow measurement systems compared well in accuracy and repeatability with conventional methods at a power plant at Grand Coulee Dam. Acoustic flow measurement systems offer utilities an inexpensive, real-time method for optimizing hydro plant efficiency.

  14. Grande Ronde Basin Chinook Salmon Captive Brood and Conventional Supplementation Programs, 1999 Annual Report.

    SciTech Connect (OSTI)

    Carmichael, Richard W.

    2003-03-01

    Permit Number 1011 (formerly Permit No. 973) authorized ODFW to take listed spring chinook salmon juveniles from Catherine Creek and the Lostine and Grande Ronde rivers for scientific research and enhancement purposes. Special condition 2a specified the need for an annual report prior to initiation of next year's work.

  15. EA-1950: Grand Coulee-Creston Transmission Line Rebuild; Grant and Lincoln Counties, Washington

    Broader source: Energy.gov [DOE]

    Bonneville Power Administration prepared this EA to evaluate potential environmental impacts of rebuilding approximately 28 miles of the Grand Coulee-Creston No. 1 115-kilovolt (kV) transmission line between Coulee Dam in Grant County and Creston in Lincoln County, Washington.

  16. Biofuels and Sustainable Development: An Executive Session on the Grand Challenges of the Sustainability Transition

    SciTech Connect (OSTI)

    Lee, Henry; Clark, William C.; Devereaux, Charan

    2008-05-20

    This report is the result of the second in a series of intense workshops and study sessions on Grand Challenges of the Sustainability Transition, organized by the Sustainability Science Program at Harvard University, hosted by Venice International University, and supported by the Italian Ministry of Environment, Land and Sea.

  17. EV Everywhere Grand Challenge: DOE's 10-Year Vision for Plug-in Electric Vehicles

    Broader source: Energy.gov [DOE]

    EV Everywhere is a Clean Energy Grand Challenge to have the U.S. become the first nation in the world to produce plug-in electric vehicles that are as affordable for the average American family as today's gasoline-powered vehicles within the next 10 years.

  18. Project Reports for Grand Traverse Band of Ottawa and Chippewa Indians- 2005 Project

    Broader source: Energy.gov [DOE]

    The Grand Traverse Band of Ottawa and Chippewa Indians (GTB) will conduct a feasibility study to determine the cost effectiveness and other economic, environmental, cultural, and social benefits of maximizing the diversity of energy sources used at GTB facilities. This includes an assessment of energy conservation measures as well as renewable energy sources such as wind, solar, and biomass.

  19. Recovery sequences for a station blackout accident at the Grand Gulf Nuclear Station

    SciTech Connect (OSTI)

    Carbajo, J.J. [Martin Marietta Energy Systems, Oak Ridge, TN (United States)

    1995-12-31

    Recovery sequences for a low-pressure, short term, station blackout severe accident at the Grand Gulf power plant have been investigated using the computer code MELCOR, version 1.8.3 PN. This paper investigates the effect of reflood timing and mass flow rate on accident recovery.

  20. Energy Efficiency Feasibility Study and Resulting Plan for the Bay Mills Indian Community

    SciTech Connect (OSTI)

    Kushman, Chris

    2014-02-03

    In 2011 the Inter-Tribal Council of Michigan, Inc. was awarded an Energy Efficiency Development and Deployment in Indian Country grant from the U.S. Department of Energy’s Tribal Energy Program. This grant aimed to study select Bay Mills Indian Community community/government buildings to determine what is required to reduce each building’s energy consumption by 30%. The Bay Mills Indian Community (BMIC) buildings with the largest expected energy use were selected for this study and included the Bay Mills Ellen Marshall Health Center building, Bay Mills Indian Community Administration Building, Bay Mills Community College main campus, Bay Mills Charter School and the Waishkey Community Center buildings. These five sites are the largest energy consuming Community buildings and comprised the study area of this project titled “Energy Efficiency Feasibility Study and Resulting Plan for the Bay Mills Indian Community”. The end objective of this study, plan and the Tribe is to reduce the energy consumption at the Community’s most energy intensive buildings that will, in turn, reduce emissions at the source of energy production, reduce energy expenditures, create long lasting energy conscious practices and positively affect the quality of the natural environment. This project’s feasibility study and resulting plan is intended to act as a guide to the Community’s first step towards planned energy management within its buildings/facilities. It aims to reduce energy consumption by 30% or greater within the subject facilities with an emphasis on energy conservation and efficiency. The energy audits and related power consumption analyses conducted for this study revealed numerous significant energy conservation and efficiency opportunities for all of the subject sites/buildings. In addition, many of the energy conservation measures require no cost and serve to help balance other measures requiring capital investment. Reoccurring deficiencies relating to heating, cooling, thermostat setting inefficiencies, powering computers, lighting, items linked to weatherization and numerous other items were encountered that can be mitigated with the energy conservation measures developed and specified during the course of this project.