National Library of Energy BETA

Sample records for line corridor cxs

  1. Early environmental planning: A process for power line corridor selection

    SciTech Connect (OSTI)

    Haagenstad, T.; Bare, C.M.

    1998-12-01

    Los Alamos National Laboratory (LANL) conducted an environmental planning study in the fall of 1997 to help determine the best alternative for upgrading the Laboratory`s electrical power system. Alternatives considered included an on-site power generation facility and two corridors for a 10-mile-long 115-kV power line. This planning process was conducted prior to the formal National Environmental Policy Act (NEPA) review. The goals were to help select the best proposed action, to recommend modifications and mitigation measures for each alternative for a more environmentally sound project, and to avoid potential delays once the formal Department of Energy review process began. Significant constraints existed from a planning perspective, including operational issues such as existing outdoor high explosives testing areas, as well as environmental issues including threatened and endangered species habitats, multiple archeological sites, contaminated areas, and aesthetics. The study had to be completed within 45 days to meet project schedule needs. The process resulted in a number of important recommendations. While the construction and operation of the on-site power generation facility could have minimal environmental impacts, the need for a new air quality permit would create severe cost and schedule constraints for the project. From an environmental perspective, construction and operation of a power line within either corridor was concluded to be a viable alternative. However, impacts with either corridor would have to be reduced through specific recommended alignment modifications and mitigation measures.

  2. Privatization contractor transfer/feed line corridor obstructions

    SciTech Connect (OSTI)

    Parazin, R.J.

    1998-05-20

    One of the issues that came out of the Tank Waste Remediation System (TWRS) Privatization Interface Control Document (ICD) effort was the need to identify below grade obstructions that exist where the TWRS Privatization Phase 1 transfer/feed corridors pass through the former Grout complex (ICD Issue 9C). Due to the numerous phases of construction at the complex, and the lack of consolidated facility configuration drawings, as-built (or as-recorded) information on the area is difficult to find, let alone decipher. To resolve the issue, this study was commissioned to identify and consolidate the as-recorded information available (drawings and Engineering Change Notices, ECNS).

  3. Proposed Energy Transport Corridors: West-wide energy corridor...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Proposed Energy Transport Corridors: West-wide energy corridor programmatic EIS, Draft Corridors - September 2007. Proposed Energy Transport Corridors: West-wide energy corridor ...

  4. Proposed Energy Transport Corridors: West-wide energy corridor programmatic

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    EIS, Draft Corridors - September 2007. | Department of Energy Proposed Energy Transport Corridors: West-wide energy corridor programmatic EIS, Draft Corridors - September 2007. Proposed Energy Transport Corridors: West-wide energy corridor programmatic EIS, Draft Corridors - September 2007. Map of the area covered by a programmatic environmental impact statement (PEIS), "Designation of Energy Corridors on Federal Land in the 11 Western States" (DOE/EIS-0386) to address the

  5. River Corridor Achievements

    Broader source: Energy.gov [DOE]

    Washington Closure Hanford and previous contractors have completed much of the cleanup work in the River Corridor, shown here.

  6. Southwest Area Corridor Map | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Southwest Area Corridor Map Southwest Area Corridor Map A map of the southwest area corridor. PDF icon Southwest Area Corridor Map More Documents & Publications Southwest Area ...

  7. I-5 Corridor Reinforcement

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Damper Replacement Program Wind Projects I-5 Corridor Reinforcement Current project schedule and activities BPA now expects to release our final EIS early in 2016, followed...

  8. Energy Corridors on Federal Lands

    Office of Energy Efficiency and Renewable Energy (EERE)

    To improve energy delivery and enhance the electric transmission grid for the future, several government agencies currently are working together to establish a coordinated network of Federal energy corridors on Federal lands throughout the United States.

  9. Analysis of Potential Energy Corridors Proposed by the Western Electricity Coordinating Council

    SciTech Connect (OSTI)

    Kuiper, James A.; Cantwell, Brian J.; Hlava, Kevin J.; Moore, H Robert; Orr, Andrew B.; Zvolanek, Emily A.

    2014-02-24

    This report, Analysis of Potential Energy Corridors Proposed by the Western Electricity Coordinating Council (WECC), was prepared by the Environmental Science Division of Argonne National Laboratory (Argonne). The intent of WECC’s work was to identify planning-level energy corridors that the Department of Energy (DOE) and its affiliates could study in greater detail. Argonne was tasked by DOE to analyze the WECC Proposed Energy Corridors in five topic areas for use in reviewing and revising existing corridors, as well as designating additional energy corridors in the 11 western states. In compliance with Section 368 of the Energy Policy Act of 2005 (EPAct), the Secretaries of Energy, Agriculture, and the Interior (Secretaries) published a Programmatic Environmental Impact Statement in 2008 to address the proposed designation of energy transport corridors on federal lands in the 11 western states. Subsequently, Records of Decision designating the corridors were issued in 2009 by the Bureau of Land Management (BLM) and the U.S. Forest Service (USFS). The 2012 settlement of a lawsuit, brought by The Wilderness Society and others against the United States, which identified environmental concerns for many of the corridors requires, among other things, periodic reviews of the corridors to assess the need for revisions, deletions, or additions. A 2013 Presidential Memorandum requires the Secretaries to undertake a continuing effort to identify and designate energy corridors. The WECC Proposed Energy Corridors and their analyses in this report provide key information for reviewing and revising existing corridors, as well as designating additional energy corridors in the 11 western states. Load centers and generation hubs identified in the WECC analysis, particularly as they reflect renewable energy development, would be useful in reviewing and potentially updating the designated Section 368 corridor network. Argonne used Geographic Information System (GIS) technology to analyze the proposed energy corridors in the WECC report in five topic areas: Federal land jurisdiction, Existing Section 368 corridors, Existing transmission lines, Previously studied corridor locations, and Protected areas. Analysis methods are explained and tables and maps are provided to describe the results of the analyses in all five topic areas. WECC used a rational approach to connecting the hubs it identified, although there may be opportunities for adapting some of the proposed WECC routes to previously designated Section 368 corridors, for example: The WECC proposed energy corridors are in fact centerlines of proposed routes connecting hubs of various descriptions related to electric energy transmission. Although the centerlines were sited to avoid sensitive areas, infrastructure proposed within actual pathways or corridors defined by the centerlines would sometimes affect lands where such development would not normally be allowed, such as National Parks and Monuments, National Wildlife Refuges, and Wilderness Areas. Many WECC proposed energy corridors are sited along centerlines of existing roads, including Interstate Highways, where in some cases additional width to accommodate energy transmission infrastructure may not be available. Examples include the WECC Proposed Corridor along Interstate 70 through Glenwood Canyon in Colorado, and along U.S. Highway 89 across Glen Canyon Dam in Arizona. Several WECC proposed energy corridors are parallel to designated Section 368 corridors that have already cleared the preliminary steps to right-of-way approval. In many of these cases, the WECC hub connection objectives can be met more efficiently by routing on the designated Section 368 corridors.

  10. Western Energy Corridor -- Energy Resource Report

    SciTech Connect (OSTI)

    Leslie Roberts; Michael Hagood

    2011-06-01

    The world is facing significant growth in energy demand over the next several decades. Strategic in meeting this demand are the world-class energy resources concentrated along the Rocky Mountains and northern plains in Canada and the U.S., informally referred to as the Western Energy Corridor (WEC). The fossil energy resources in this region are rivaled only in a very few places in the world, and the proven uranium reserves are among the world's largest. Also concentrated in this region are renewable resources contributing to wind power, hydro power, bioenergy, geothermal energy, and solar energy. Substantial existing and planned energy infrastructure, including refineries, pipelines, electrical transmission lines, and rail lines provide access to these resources.

  11. HANFORD SITE RIVER CORRIDOR CLEANUP

    SciTech Connect (OSTI)

    BAZZELL, K.D.

    2006-02-01

    In 2005, the US Department of Energy (DOE) launched the third generation of closure contracts, including the River Corridor Closure (RCC) Contract at Hanford. Over the past decade, significant progress has been made on cleaning up the river shore that bordes Hanford. However, the most important cleanup challenges lie ahead. In March 2005, DOE awarded the Hanford River Corridor Closure Contract to Washington Closure Hanford (WCH), a limited liability company owned by Washington Group International, Bechtel National and CH2M HILL. It is a single-purpose company whose goal is to safely and efficiently accelerate cleanup in the 544 km{sup 2} Hanford river corridor and reduce or eliminate future obligations to DOE for maintaining long-term stewardship over the site. The RCC Contract is a cost-plus-incentive-fee closure contract, which incentivizes the contractor to reduce cost and accelerate the schedule. At $1.9 billion and seven years, WCH has accelerated cleaning up Hanford's river corridor significantly compared to the $3.2 billion and 10 years originally estimated by the US Army Corps of Engineers. Predictable funding is one of the key features of the new contract, with funding set by contract at $183 million in fiscal year (FY) 2006 and peaking at $387 million in FY2012. Another feature of the contract allows for Washington Closure to perform up to 40% of the value of the contract and subcontract the balance. One of the major challenges in the next few years will be to identify and qualify sufficient subcontractors to meet the goal.

  12. From: Carl Daffron To: Congestion Study Comments Subject: National Interest Energy Transmission Corridors

    Energy Savers [EERE]

    Carl Daffron To: Congestion Study Comments Subject: National Interest Energy Transmission Corridors Date: Monday, September 22, 2014 12:47:15 PM I am opposed to the establishment of National Interest Energy Transmission Corridors (NIETC's) for the following reasons. First, the easements place an undue burden on landowners on and near the transmission lines. The compensation cannot begin to cover the all of the losses, tangible and intangible that landowners would suffer. Second, I believe that

  13. From: Carol Johnson To: Congestion Study Comments Subject: Re: National Interest Energy Transmission Corridors

    Energy Savers [EERE]

    Johnson To: Congestion Study Comments Subject: Re: National Interest Energy Transmission Corridors Date: Sunday, October 19, 2014 8:20:41 AM I am opposed to the establishment of National Interest Energy Transmission Corridors (NIETC's) for the following reasons. First, the easements place an undo burden on landowners on and near the transmission lines. The compensation cannot begin to cover the all of the losses, tangible and intangible that landowners would suffer. I am a landowner in the path

  14. From: Noralie Crow To: Congestion Study Comments Subject: National Interest Energy Transmission Corridors (NIETC)

    Energy Savers [EERE]

    Noralie Crow To: Congestion Study Comments Subject: National Interest Energy Transmission Corridors (NIETC) Date: Monday, September 22, 2014 6:50:56 PM I am opposed to the establishment of National Interest Energy Transmission Corridors (NIETC's) for the following reasons. First, the easements place an undo burden on landowners on and near the transmission lines. The compensation cannot begin to cover the all of the losses, tangible and intangible that landowners would suffer. Second, I believe

  15. River Corridor Closure Project Partnering Performance Agreement...

    Office of Environmental Management (EM)

    - March 2009 Voluntary Protection Program Onsite Review, River Corridor Closure Project - June 2012 Indoctrinating Subcontractors into the DOE Safety Culture and Expectations...

  16. Energy Transport Corridor Draft Environmental Impact Statement...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    designate energy transport corridors for oil, gas, and hydrogen pipelines and ... Colorado, Idaho, Montana, Nevada, New Mexico, Oregon, Utah, Washington and Wyoming. ...

  17. MidAtlantic_Corridor_Map091707.pdf | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    MidAtlanticCorridorMap091707.pdf MidAtlanticCorridorMap091707.pdf PDF icon MidAtlanticCorridorMap091707.pdf More Documents & Publications DOE Designates Southwest Area and...

  18. Alternative Fuels Data Center: West Virginia CNG Corridor Now Open

    Alternative Fuels and Advanced Vehicles Data Center [Office of Energy Efficiency and Renewable Energy (EERE)]

    West Virginia CNG Corridor Now Open to someone by E-mail Share Alternative Fuels Data Center: West Virginia CNG Corridor Now Open on Facebook Tweet about Alternative Fuels Data Center: West Virginia CNG Corridor Now Open on Twitter Bookmark Alternative Fuels Data Center: West Virginia CNG Corridor Now Open on Google Bookmark Alternative Fuels Data Center: West Virginia CNG Corridor Now Open on Delicious Rank Alternative Fuels Data Center: West Virginia CNG Corridor Now Open on Digg Find More

  19. Energy Corridors on Federal Lands | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    As the agency-preferred siting locations, the energy transport corridors will provide ... Alaska, and Hawaii (2014) Energy Transport Corridors: The Potential Role of Federal ...

  20. Milford Wind Corridor Phase I (GE Energy) | Open Energy Information

    Open Energy Info (EERE)

    I (GE Energy) Jump to: navigation, search Name Milford Wind Corridor Phase I (GE Energy) Facility Milford Wind Corridor Phase I (GE Energy) Sector Wind energy Facility Type...

  1. Milford Wind Corridor Phase II | Open Energy Information

    Open Energy Info (EERE)

    II Jump to: navigation, search Name Milford Wind Corridor Phase II Facility Milford Wind Corridor Phase II Sector Wind energy Facility Type Commercial Scale Wind Facility Status In...

  2. Milford Wind Corridor Phase I (Clipper) Wind Farm | Open Energy...

    Open Energy Info (EERE)

    Clipper) Wind Farm Jump to: navigation, search Name Milford Wind Corridor Phase I (Clipper) Wind Farm Facility Milford Wind Corridor Phase I (Clipper) Sector Wind energy Facility...

  3. Long Island Smart Energy Corridor

    SciTech Connect (OSTI)

    Mui, Ming

    2015-02-04

    The Long Island Power Authority (LIPA) has teamed with Stony Brook University (Stony Brook or SBU) and Farmingdale State College (Farmingdale or FSC), two branches of the State University of New York (SUNY), to create a “Smart Energy Corridor.” The project, located along the Route 110 business corridor on Long Island, New York, demonstrated the integration of a suite of Smart Grid technologies from substations to end-use loads. The Smart Energy Corridor Project included the following key features: -TECHNOLOGY: Demonstrated a full range of smart energy technologies, including substations and distribution feeder automation, fiber and radio communications backbone, advanced metering infrastructure (AM”), meter data management (MDM) system (which LIPA implemented outside of this project), field tools automation, customer-level energy management including automated energy management systems, and integration with distributed generation and plug-in hybrid electric vehicles. -MARKETING: A rigorous market test that identified customer response to an alternative time-of-use pricing plan and varying levels of information and analytical support. -CYBER SECURITY: Tested cyber security vulnerabilities in Smart Grid hardware, network, and application layers. Developed recommendations for policies, procedures, and technical controls to prevent or foil cyber-attacks and to harden the Smart Grid infrastructure. -RELIABILITY: Leveraged new Smart Grid-enabled data to increase system efficiency and reliability. Developed enhanced load forecasting, phase balancing, and voltage control techniques designed to work hand-in-hand with the Smart Grid technologies. -OUTREACH: Implemented public outreach and educational initiatives that were linked directly to the demonstration of Smart Grid technologies, tools, techniques, and system configurations. This included creation of full-scale operating models demonstrating application of Smart Grid technologies in business and residential settings. Farmingdale State College held three international conferences on energy and sustainability and Smart Grid related technologies and policies. These conferences, in addition to public seminars increased understanding and acceptance of Smart Grid transformation by the general public, business, industry, and municipalities in the Long Island and greater New York region. - JOB CREATION: Provided training for the Smart Grid and clean energy jobs of the future at both Farmingdale and Stony Brook. Stony Brook focused its “Cradle to Fortune 500” suite of economic development resources on the opportunities emerging from the project, helping to create new technologies, new businesses, and new jobs. To achieve these features, LIPA and its sub-recipients, FSC and SBU, each have separate but complementary objectives. At LIPA, the Smart Energy Corridor (1) meant validating Smart Grid technologies; (2) quantifying Smart Grid costs and benefits; and (3) providing insights into how Smart Grid applications can be better implemented, readily adapted, and replicated in individual homes and businesses. LIPA installed 2,550 AMI meters (exceeding the 500 AMI meters in the original plan), created three “smart” substations serving the Corridor, and installed additional distribution automation elements including two-way communications and digital controls over various feeders and capacitor banks. It gathered and analyzed customer behavior information on how they responded to a new “smart” TOU rate and to various levels of information and analytical tools.

  4. PHOENIX ENERGIZES LIGHT RAIL CORRIDOR WITH UPGRADES

    Broader source: Energy.gov [DOE]

    Designed to promote energy efficiency in buildings in Phoenix, Arizona’s 10-mile-long Light Rail Corridor, Energize Phoenix focused on performing energy upgrades and reducing energy use in...

  5. An Inside Look at River Corridor

    Broader source: Energy.gov [DOE]

    In the seventh chapter of The Handford Story, the Energy Department takes a look at the River Corridor -- a 50-mile stretch of the Columbia River that flows through the Hanford site in southeast...

  6. Interstate Clean Transportation Corridor Project Under Way

    Alternative Fuels and Advanced Vehicles Data Center [Office of Energy Efficiency and Renewable Energy (EERE)]

    rucks that travel in the western United States will soon be able to operate clean-burning alternative fuel vehicles (AFVs) along the Interstate Clean Transpor- tation Corridor (ICTC). The ICTC project is the first effort to develop clean transportation corridors to connect Los Angeles, San Bernar- dino, the San Joaquin Valley, Sacra- mento/San Francisco, Salt Lake City, Reno, and Las Vegas along routes 1-15, 1-80, and 1-5/CA-99. The ICTC team, headed by California- based Gladstein and

  7. Washington Closure Hanford: Ten Years of River Corridor Cleanup

    Broader source: Energy.gov [DOE]

    This timeline shows contractor Washington Closure Hanford's accomplishments over the past 10 years through its River Corridor Closure Contract.

  8. EM Update Newsletter Spotlights River Corridor Cleanup at Hanford Site |

    Office of Environmental Management (EM)

    Department of Energy EM Update Newsletter Spotlights River Corridor Cleanup at Hanford Site EM Update Newsletter Spotlights River Corridor Cleanup at Hanford Site December 17, 2015 - 12:40pm Addthis RICHLAND, Wash. - In this issue of the EM Update newsletter, EM marks the many accomplishments the Richland Operations Office and its contractors have achieved in cleanup along the Columbia River corridor at the Hanford Site. This year marked the 10th anniversary of the River Corridor Closure

  9. DOE Issues Two Draft National Interest Electric Transmission Corridor Designations

    Broader source: Energy.gov [DOE]

    U.S. Department of Energy (DOE) Secretary Samuel W. Bodman today announced the issuance of two draft National Interest Electric Transmission Corridor (National Corridor) designations. The Energy Policy Act of 2005 authorizes the Secretary, based on the findings of DOE's National Electric Transmission Congestion Study (Congestion Study), to designate National Corridors.

  10. EIA - Natural Gas Pipeline Network - Natural Gas Transportation Corridors

    U.S. Energy Information Administration (EIA) Indexed Site

    Map Corridors > Major U.S. Natural Gas Transportation Corridors Map About U.S. Natural Gas Pipelines - Transporting Natural Gas based on data through 2007/2008 with selected updates Major U.S. Natural Gas Transportation Corridors, 2008

  11. From: Alex Free To: Congestion Study Comments Subject: National Interest Energy Transmission Corridors

    Energy Savers [EERE]

    05:34 PM I am opposed to the establishment of National Interest Energy Transmission Corridors (NIETC's) for the following reasons. First, the easements place an undo burden on landowners on and near the transmission lines. The compensation cannot begin to cover the all of the losses, tangible and intangible that landowners would suffer. Second, I believe that condemning private property for transmission lines in one state to transport electricity to another is a violation of property rights

  12. From: Alex Free To: Congestion Study Comments Subject: National Interest Energy Transmission Corridors

    Energy Savers [EERE]

    10:45 PM I am opposed to the establishment of National Interest Energy Transmission Corridors (NIETC's) for the following reasons. First, the easements place an undo burden on landowners on and near the transmission lines. The compensation cannot begin to cover the all of the losses, tangible and intangible that landowners would suffer. Second, I believe that condemning private property for transmission lines in one state to transport electricity to another is a violation of property rights

  13. Agencies Publish Final Environmental Impact Statement on Energy Corridor

    Energy Savers [EERE]

    Designation in the West | Department of Energy Final Environmental Impact Statement on Energy Corridor Designation in the West Agencies Publish Final Environmental Impact Statement on Energy Corridor Designation in the West November 26, 2008 - 2:07pm Addthis WASHINGTON, DC - Four Federal agencies today released a Final Programmatic Environmental Impact Statement (Final PEIS) proposing to designate more than 6,000 miles of energy transport corridors on Federal lands in 11 Western States. The

  14. Successful River Corridor Contractor Completes Extra Work Scope, Saving DOE

    Energy Savers [EERE]

    $300 Million | Department of Energy Successful River Corridor Contractor Completes Extra Work Scope, Saving DOE $300 Million Successful River Corridor Contractor Completes Extra Work Scope, Saving DOE $300 Million December 17, 2015 - 12:35pm Addthis A recent photo of the N Reactor in its cocooned state looks sharply different than it did in 2005. A recent photo of the N Reactor in its cocooned state looks sharply different than it did in 2005. RICHLAND, Wash. - The River Corridor Closure

  15. Agencies Publish Final Environmental Impact Statement on Energy Corridor

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Designation in the West | Department of Energy Final Environmental Impact Statement on Energy Corridor Designation in the West Agencies Publish Final Environmental Impact Statement on Energy Corridor Designation in the West November 26, 2008 - 4:58pm Addthis WASHINGTON, DC - Four Federal agencies today released a Final Programmatic Environmental Impact Statement (Final PEIS) proposing to designate more than 6,000 miles of energy transport corridors on Federal lands in 11 Western States. The

  16. Cleaning Up the Hanford River Corridor and Improving Site Operations

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    remedies required by River Corridor and Central Plateau Records of Decision; includes uranium and strontium remediation 4 Richland Cleanup Priorities * Continue remedial...

  17. Vermont Flood Hazard Area and River Corridor General Permit Applicatio...

    Open Energy Info (EERE)

    the developer should provide a map generated from the ANR Natural Resources Atlas showing the river corridor and flood hazard area; A written description of the...

  18. Department of Energy Awards Hanford River Corridor Contract To...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Hanford River Corridor Contract To Washington Closure, LLC Department of Energy Awards ... The five-member team includes the Washington Group International Inc., Bechtel National ...

  19. Department of Energy Awards Hanford River Corridor Contract To...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Inc., Bechtel National Inc., CH2M Hill Inc., Eberline Services Inc., and Integrated Logistics Services Inc. The Columbia River Corridor is composed of roughly 210 square miles...

  20. Strategy for the Identification of an INL Comprehensive Utility Corridor

    SciTech Connect (OSTI)

    John Reisenauer

    2011-05-01

    This report documents the strategy developed to identify a comprehensive utility corridor (CUC) on the Idaho National Laboratory (INL) Site. The strategy established the process for which the Campus Development Office will evaluate land management issues. It is a process that uses geographical information system geospatial technology to layer critical INL mission information in a way that thorough evaluations can be conducted and strategies developed. The objective of the CUC Project was to develop a process that could be implemented to identify potential utility corridor options for consideration. The process had to take into account all the missions occurring on the INL and other land-related issues. The process for developing a CUC strategy consists of the following four basic elements using geographical information system capabilities: 1. Development of an INL base layer map; this base layer map geospatially references all stationary geographical features on INL and sitewide information. 2. Development of current and future mission land-use need maps; this involved working with each directorate to identify current mission land use needs and future land use needs that project 30 years into the future. 3. Development of restricted and potential constraint maps; this included geospatially mapping areas such as wells, contaminated areas, firing ranges, cultural areas, ecological areas, hunting areas, easement, and grazing areas. 4. Development of state highway and power line rights of way map; this included geospatially mapping rights-of-way along existing state highways and power lines running through the INL that support INL operations. It was determined after completing and evaluating the geospatial information that the area with the least impact to INL missions was around the perimeter of the INL Site. Option 1, in this document, identifies this perimeter; however, it does not mean the entire perimeter is viable. Many places along the perimeter corridor cannot be used or are not economically viable. Specific detailed studies will need to be conducted on a case-by-case basis to clearly identify which sections along the perimeter can and cannot be used. Option 2, in this document, identifies areas along existing highways that could be a viable option. However, discussions would have to take place with the State of Idaho to use their easement as part of the corridor and mission impact would need to be evaluated if a specific request was made to the Department of Energy, Idaho Operations Office. Option 3, in this document, is a combination of Options 1 and 2. This option provides the most flexibility to minimize impacts to INL missions. As with the other two options, discussions and agreements with the State of Idaho would be needed and any specific route would need to be thoroughly evaluated for impact, implementation, and operability beyond just a strategy.

  1. DOE Affirms National Interest Electric Transmission Corridor Designations

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy (DOE) today denied requests for rehearing of the Mid-Atlantic and the Southwest Area National Interest Electric Transmission Corridors (National Corridors) designated by DOE in October 2007 as areas of significant electricity congestion and constraint.

  2. ARM - Field Campaign - 1999 Northeast Corridor Ozone & Particulate...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    would love to hear from you Send us a note below or call us at 1-888-ARM-DATA. Send Campaign : 1999 Northeast Corridor Ozone & Particulate Study 1999.07.23 - 1999.08.11 Lead...

  3. West Vero Corridor, Florida: Energy Resources | Open Energy Informatio...

    Open Energy Info (EERE)

    Hide Map This article is a stub. You can help OpenEI by expanding it. West Vero Corridor is a census-designated place in Indian River County, Florida.1...

  4. H.R.S. 277 - Energy Corridors | Open Energy Information

    Open Energy Info (EERE)

    search OpenEI Reference LibraryAdd to library Legal Document- StatuteStatute: H.R.S. 277 - Energy CorridorsLegal Abstract This statute outlines the law pertaining to...

  5. I-65 Clean Corridor: Fall Drive Overview and Media Summary

    Broader source: Energy.gov [DOE]

    At the May 1, 2008 joint quarterly Web conference of DOE's Biomass and Clean Cities programs, Julie Howe (Indiana Office of Energy & Defense Development) described the I-65 Corridor Project.

  6. Voluntary Protection Program Onsite Review, River Corridor Closure...

    Broader source: Energy.gov (indexed) [DOE]

    Evaluation to determine whether River Corridor Closure Project is continuing to perform at a level deserving DOE-VPP Star recognition. The Team conducted its review during June 11...

  7. EIS-0250-S2: Supplemental EIS for a Geologic Repository for the Disposal of Spent Nuclear Fuel and High-Level Radioactive Waste at Yucca Mountain, Nye County, Nevada- Nevada Rail Transportation Corridor

    Broader source: Energy.gov [DOE]

    This SEIS is to evaluate the potential environmental impacts of constructing and operating a railroad for shipments of spent nuclear fuel and high-level radioactive waste from an existing rail line in Nevada to a geologic repository at Yucca Mountain. The purpose of the evaluation is to assist the Department in deciding whether to construct and operate a railroad in Nevada, and if so, in which corridor and along which specific alignment within the selected corridor.

  8. RIVER CORRIDOR BUILDINGS 324 & 327 CLEANUP

    SciTech Connect (OSTI)

    BAZZELL, K.D.; SMITH, B.A.

    2006-02-09

    A major challenge in the recently awarded River Corridor Closure (RCC) Contract at the U.S. Department of Energy's (DOE) Hanford Site is decontaminating and demolishing (D&D) facilities in the 300 Area. Located along the banks of the Columbia River about one mile north of Richland, Washington, the 2.5 km{sup 2} (1 mi{sup 2})300 Area comprises only a small part of the 1517 km{sup 2} (586 mi{sup 2}) Hanford Site. However, with more than 300 facilities ranging from clean to highly contaminated, D&D of those facilities represents a major challenge for Washington Closure Hanford (WCH), which manages the new RCC Project for DOE's Richland Operations Office (RL). A complicating factor for this work is the continued use of nearly a dozen facilities by the DOE's Pacific Northwest National Laboratory (PNNL). Most of the buildings will not be released to WCH until at least 2009--four years into the seven-year, $1.9 billion RCC Contract. The challenge will be to deactivate, decommission, decontaminate and demolish (D4) highly contaminated buildings, such as 324 and 327, without interrupting PNNL's operations in adjacent facilities. This paper focuses on the challenges associated with the D4 of the 324 Building and the 327 Building.

  9. Report to Congress: Corridors and Rights-of-Way on Federal Lands...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    to Congress: Corridors and Rights-of-Way on Federal Lands Report to Congress: Corridors and Rights-of-Way on Federal Lands Authority to grant, issue, or renew electric transmission ...

  10. File:03HIFPermitToCrossOrEnterTheStateEnergyCorridor.pdf | Open...

    Open Energy Info (EERE)

    HIFPermitToCrossOrEnterTheStateEnergyCorridor.pdf Jump to: navigation, search File File history File usage Metadata File:03HIFPermitToCrossOrEnterTheStateEnergyCorridor.pdf Size of...

  11. Cleaning Up the Hanford River Corridor and Improving Site Operations

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Jon Peschong, Deputy Assistant Manager for the River and Plateau, Department of Energy Richland Operations Office September 2014 2 Richland Cleanup Priorities * Maintain safe, secure and compliant activities, facilities and operations * Continue River Corridor cleanup, including remediation of 618-10 Burial Ground * Continue Plutonium Finishing Plant deactivation, decommissioning and demolition * Continue groundwater pump and treat operations, and implement additional groundwater remedies 3

  12. Cleaning Up the Hanford River Corridor and Improving Site Operations

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Stacy Charboneau, Assistant Manager for Safety and Environment, Department of Energy Richland Operations Office June 2014 2 Richland Cleanup Priorities * Maintain safe, secure and compliant activities, facilities and operations * Continue River Corridor cleanup, including remediation of 618-10 Burial Ground * Continue Plutonium Finishing Plant deactivation, decommissioning and demolition * Continue groundwater pump and treat operations, and implement additional groundwater remedies 3 Richland

  13. A survey of endangered waterbirds on Maui and Oahu and assessment of potential impacts to waterbirds from the proposed Hawaii Geothermal Project transmission corridor. Final report

    SciTech Connect (OSTI)

    Evans, K.; Woodside, D.; Bruegmann, M.

    1994-08-01

    A survey of endangered waterbirds on Maui and Oahu was conducted during August and September 1993 to identify potential waterbird habitats within the general area of the proposed Hawaii Geothermal Project transmission corridor and to assess the potential impacts to endangered waterbird of installing and operating a high voltage transmission line from the Island of Hawaii to the islands of Oahu and Maui. Annual waterbird survey information and other literature containing information on specific wetland sites were summarized. Literature describing impacts of overhead transmission lines on birds was used to evaluate potential impacts of the proposed project on endangered waterbirds, resident wading birds, and migratory shorebirds and waterfowl. On Oahu, five wetland habitats supporting endangered Hawaiian waterbirds were identified within 2.5 miles of the proposed transmission line corridor. On Maui, three wetland habitats supporting endangered Hawaiian waterbirds were identified within the general area of the proposed transmission line corridor. Several of the wetlands identified on Oahu and Maui also supported resident wading birds and migratory shorebirds and waterfowl. Endangered waterbirds, resident wading birds, and migratory birds may collide with the proposed transmission lines wires. The frequency and numbers of bird collisions is expected to be greater on Oahu than on Maui because more wetland habitat exists and greater numbers of birds occur in the project area on Oahu. In addition, the endangered Hawaiian goose and the endangered Hawaiian petrel may be impacted by the proposed segment of the Hawaii Geothermal Project transmission line on Maui.

  14. DOE Designates Southwest Area and Mid-Atlantic Area National Interest Electric Transmission Corridors

    Broader source: Energy.gov [DOE]

    U.S. Department of Energy (DOE) Assistant Secretary for Electricity Delivery and Energy Reliability Kevin M. Kolevar today announced the Department's designation of two National Interest Electric Transmission Corridors (National Corridors) -- the Mid-Atlantic Area National Interest Electric Transmission Corridor, and the Southwest Area National Interest Electric Transmission Corridor. These corridors include areas in two of the Nation's most populous regions with growing electricity congestion problems. The Department based its designations on data and analysis showing that persistent transmission congestion exists in these two areas.

  15. Low-altitude remote sensing dataset of DEM and RGB mosaic for AB corridor on July 13 2013 and L2 corridor on July 21 2013

    DOE Data Explorer [Office of Scientific and Technical Information (OSTI)]

    Baptiste Dafflon

    2015-04-07

    Low-altitude remote sensing dataset including DEM and RGB mosaic for AB (July 13 2013) and L2 corridor (July 21 2013)

  16. CX-011689: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Fence Replacement on the Latham Tap Transmission Line Corridor CX(s) Applied: B1.3 Date: 11/29/2013 Location(s): Oregon Offices(s): Bonneville Power Administration

  17. 2011 River Corridor Closure Contractor Revegetation and Mitigation Monitoring Report

    SciTech Connect (OSTI)

    West, W. J.; Lucas, J. G.; Gano, K. A.

    2011-11-14

    This report documents the status of revegetation projects and natural resources mitigation efforts conducted for remediated waste sites and other activities associated with the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 cleanup of National Priorities List waste sites at Hanford. This report contains the vegetation monitoring data that was collected in the spring and summer of 2011 from the River Corridor Closure Contractors revegetation and mitigation areas on the Hanford Site.

  18. 2010 River Corridor Closure Contractor Revegetation and Mitigation Monitoring Report

    SciTech Connect (OSTI)

    C. T. Lindsey, A. L. Johnson

    2010-09-30

    This report documents eh status of revegetation projects and natural resources mitigation efforts conducted for remediated waste sites and other activities associated with CERLA cleanup of National Priorities List waste sites at Hanford. This report contains vegetation monitoring data that were collected in the spring and summer of 2010 from the River Corridor Closure Contracts revegetation and mitigation areas on the Hanford Site.

  19. Type B Accident Investigation Board Report on the July 25, 1997, Contract Brush Cutter Injury on the Ashe-Marion #2 500 kV Line

    Broader source: Energy.gov [DOE]

    On July 25, 1997, at 1205 hours, a contract hand brush cutter was seriously injured when he felled a tree close to a Bonneville Power Administration energized transmission power line, located within a BPA transmission-line corridor.

  20. Landscape corridors can increase invasion by an exotic species and reduce diversity of native species.

    SciTech Connect (OSTI)

    Resasco, Julian; et al,

    2014-04-01

    Abstract. Landscape corridors are commonly used to mitigate negative effects of habitat fragmentation, but concerns persist that they may facilitate the spread of invasive species. In a replicated landscape experiment of open habitat, we measured effects of corridors on the invasive fire ant, Solenopsis invicta, and native ants. Fire ants have two social forms: polygyne, which tend to disperse poorly but establish at high densities, and monogyne, which disperse widely but establish at lower densities. In landscapes dominated by polygyne fire ants, fire ant abundance was higher and native ant diversity was lower in habitat patches connected by corridors than in unconnected patches. Conversely, in landscapes dominated by monogyne fire ants, connectivity had no influence on fire ant abundance and native ant diversity. Polygyne fire ants dominated recently created landscapes, suggesting that these corridor effects may be transient. Our results suggest that corridors can facilitate invasion and they highlight the importance of considering species traits when assessing corridor utility.

  1. Voluntary Protection Program Onsite Review, River Corridor Closure Project- June 2012

    Broader source: Energy.gov [DOE]

    Evaluation to determine whether River Corridor Closure Project is continuing to perform at a level deserving DOE-VPP Star recognition.

  2. EIS-0386: Designation of Energy Corridors on Federal Land in Western States

    Office of Energy Efficiency and Renewable Energy (EERE)

    This EIS analyzes DOE's decision to designatate corridors on Federal land in the eleven Western States for oil, gas and hydrogen pipelines and electricity transmission and distribution facilities.

  3. River Corridor Cleanup Contract Fiscal Year 2006 Detailed Work Plan: DWP Summary, Volume 1

    SciTech Connect (OSTI)

    Project Integration

    2005-09-26

    This detailed work plan provides the scope, cost, and schedule for the Fiscal Year 2006 activities required to support River Corridor cleanup objectives within the directed guidance.

  4. Low-altitude remote sensing dataset of DEM and RGB mosaic for AB corridor on July 13 2013 and L2 corridor on July 21 2013

    DOE Data Explorer [Office of Scientific and Technical Information (OSTI)]

    Baptiste Dafflon

    2015-04-07

    Low-altitude remote sensing dataset including DEM and RGB mosaic for AB (July 13 2013) and L2 corridor (July 21 2013).Processing flowchart for each corridor:Ground control points (GCP, 20.3 cm square white targets, every 20 m) surveyed with RTK GPS. Acquisition of RGB pictures using a Kite-based platform. Structure from Motion based reconstruction using hundreds of pictures and GCP coordinates. Export of DEM and RGB mosaic in geotiff format (NAD 83, 2012 geoid, UTM zone 4 north) with pixel resolution of about 2 cm, and x,y,z accuracy in centimeter range (less than 10 cm). High-accuracy and high-resolution inside GCPs zone for L2 corridor (500x20m), AB corridor (500x40) DEM will be updated once all GCPs will be measured. Only zones between GCPs are accurate although all the mosaic is provided.

  5. DOE Announces Additional Public Comment Meetings for Draft National Corridor Designations

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy (DOE) today announced that it will hold four additional public meetings for the two draft National Interest Electric Transmission Corridors (National Corridors) during the 60-day public comment period, which will close on July 6, 2007.

  6. ORNL Trusted Corridors Project: Watts Bar Dam Inland Waterway Project

    SciTech Connect (OSTI)

    Walker, Randy M; Gross, Ian G; Smith, Cyrus M; Hill, David E

    2011-11-01

    Radiation has existed everywhere in the environment since the Earth's formation - in rocks, soil, water, and plants. The mining and processing of naturally occurring radioactive materials for use in medicine, power generation, consumer products, and industry inevitably generate emissions and waste. Radiological measuring devices have been used by industry for years to measure for radiation in undesired locations or simply identify radioactive materials. Since the terrorist attacks on the United States on 9-11-01 these radiation measuring devices have proliferated in many places in our nation's commerce system. DOE, TVA, the Army Corps and ORNL collaborated to test the usefulness of these devices in our nation's waterway system on this project. The purpose of the Watts Bar Dam ORNL Trusted Corridors project was to investigate the security, safety and enforcement needs of local, state and federal government entities for state-of-the-art sensor monitoring in regards to illegal cargo including utilization of the existing infrastructure. TVA's inland waterways lock system is a recognized and accepted infrastructure by the commercial carrier industry. Safety Monitoring activities included tow boat operators, commercial barges and vessels, recreational watercraft and their cargo, identification of unsafe vessels and carriers, and, monitoring of domestic and foreign commercial vessels and cargo identification. Safety Enforcement activities included cargo safety, tracking, identification of hazardous materials, waterway safety regulations, and hazardous materials regulations. Homeland Security and Law Enforcement Applications included Radiological Dispersive Devices (RDD) identification, identification of unsafe or illicit transport of hazardous materials including chemicals and radiological materials, and screening for shipments of illicit drugs. In the Fall of 2005 the SensorNet funding for the project expired. After several unsuccessful attempts to find a Federal sponsor to continue with the project, the Watts Bar Dam Project was canceled and the Exploranium radiation monitors were removed from the doors of Watts Bar Dam in early 2006. The DHS Domestic Nuclear Detection Office decided to proceed with a Pilot building on the ORNL work performed at the TN and SC weigh stations in the highway sector of the Trusted Corridors project and eventually expanded it to other southern states under the name of Southeastern Corridor Pilot Project (SETCP). Many of the Phase I goals were achieved however real-world test data of private watercraft and barges was never obtained.

  7. El Paso Electric Company Diablo Substation to the US-Mexico border 115kV transmission line project. Final Environmental Assessment

    SciTech Connect (OSTI)

    Not Available

    1992-04-01

    This Environmental Assessment documents the analysis of alternative corridors for development and operation of a proposed 115 kilovolt transmission line using private lands and transporting power to the US-Mexico international border. The project will require (1) an amendment to El Paso Electric Company`s existing export authorization to transfer power across this border, and (2) a Presidential Permit for construction of the transmission line. The project would be located in Dona Ana county in southern New Mexico, approximately five miles west of El Paso, Texas. The alternative corridors, specific locations within those corridors, and structure types are identified and analyzed in the environmental studies.

  8. Department of Energy Awards Hanford River Corridor Contract To Washington Closure, LLC

    Broader source: Energy.gov [DOE]

    WASHINGTON, DC U.S. Energy Secretary Samuel Bodman today announced that Washington Closure, LLC has been awarded the contract to manage the clean up and remediation of the Columbia River Corridor...

  9. Workers Demolish Reactor Support Facility as Part of River Corridor Contract

    Broader source: Energy.gov [DOE]

    RICHLAND, Wash. – EM’s Richland Operations Office and cleanup contractor Washington Closure Hanford recently completed the cleanout and demolition of the last reactor support facility as part of the River Corridor Closure Contract.

  10. I-65, America's First BioFuels Corridor: Timeline and Map

    Office of Energy Efficiency and Renewable Energy (EERE)

    At the May 1, 2008 joint quarterly Web conference of DOE's Biomass and Clean Cities programs, Julie Howe (Indiana Office of Energy & Defense Development) described the I-65 Corridor Project.

  11. EIS-0406: Designation of Energy Corridors on Federal Land in 39 States

    Broader source: Energy.gov [DOE]

    DOE has canceled this EIS, which was to evaluate the environmental impacts of the designation, under Section 368(b) of the Energy Policy Act of 2005, of energy corridors on federal lands in 39 nonwestern states. The corridors, which were to be jointly identified by the Secretaries of Agriculture, Commerce, Defense, Energy, and the Interior, might have been used for oil, gas, and hydrogen pipelines and electricity transmission and distribution facilities.

  12. Microsoft PowerPoint - Columbia_River_Corridor_Rev_2_v2.ppt [Compatibility Mode]

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    9 Columbia River Corridor The Columbia River Corridor projects selected for Recovery A t f di i l d d li hi f iliti di ti Act funding include demolishing facilities, remediating waste sites, and containing and treating contamination in groundwater. The projects support completing cleanup along the Columbia River and shrinking the active area of cleanup to the center of the Hanford Site (the Central Plateau) by 2015 1 of the Hanford Site (the Central Plateau) by 2015. May 2009 Shrinking the

  13. Microsoft Word - Agencies Publish Final Environmental Impact Statement on Energy Corridor Designation in the West

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    FOR IMMEDIATE RELEASE: Jill Moran, BLM (202) 452-5068 Wednesday, November 26, 2008 Bethany Shively, DOE (202) 586-4940 Joe Walsh, USFS (202) 205-1134 Agencies Publish Final Environmental Impact Statement on Energy Corridor Designation in the West WASHINGTON, DC - Four Federal agencies today released a Final Programmatic Environmental Impact Statement (Final PEIS) proposing to designate more than 6,000 miles of energy transport corridors on Federal lands in 11 Western States. The Department of

  14. From: Austin Bird To: Congestion Study Comments Subject: Citizen Comment: National Interest Energy Transmission Corridors (NIETC"s)

    Energy Savers [EERE]

    Austin Bird To: Congestion Study Comments Subject: Citizen Comment: National Interest Energy Transmission Corridors (NIETC"s) Date: Monday, October 06, 2014 10:00:01 AM To Whomever It May Concern; I am writing in support of the establishment of National Interest Energy Transmission Corridors (NIETCs). The establishment of these corridors would further the progress of the budding alternative energy sector in the Midwest, particularly in my state, Iowa. I am a resident of Davenport, Iowa, and

  15. Environmental Survey Report for the ETTP: Environmental Management Waste Management Facility (EMWMF) Haul Road Corridor, Oak Ridge, Tennessee

    SciTech Connect (OSTI)

    Peterson, M.J.

    2005-12-20

    This report summarizes the results of environmental surveys conducted within the corridor of a temporary haul road (''Haul Road'') to be constructed from East Tennessee Technology Park (ETTP) to the Environmental Management Waste Management Facility (EMWMF) located just west of the Y-12 National Security Complex (Y-12). Environmental surveys were conducted by natural resource experts at Oak Ridge National Laboratory who routinely assess the significance of various project activities on the Oak Ridge Reservation (ORR). ORNL assistance to the Haul Road Project included environmental assessments necessary to determine the best route for minimizing impacts to sensitive resources such as wetlands or rare plants. Once the final route was chosen, environmental surveys were conducted within the corridor to evaluate the impacts to sensitive resources that could not be avoided. The final Haul Road route follows established roads and a power-line corridor to the extent possible (Fig. 1). Detailed explanation regarding the purpose of the Haul Road and the regulatory context associated with its construction is provided in at least two major documents and consequently is not presented here: (1) Explanation of Significant Differences for the Record of Decision for the Disposal of Oak Ridge Reservation Comprehensive Environmental Response, Compensation, and Liability Act of 1980 Waste, Oak Ridge, Tennessee (January 2005, DOE/OR/01-2194&D2), and (2) Environmental Monitoring Plan for The ETTP to EMWMF Haul Road for the Disposal of Oak Ridge Reservation Comprehensive Environmental Response, Compensation, and Liability Act of 1980 Waste, Oak Ridge, Tennessee (April 2005, BJC/OR-2152). The focus of this report is a description of the sensitive resources to be impacted by Haul Road construction. Following a short description of the methods used for the environmental surveys, results and observations are presented in the following subsections: (1) General description of the affected environment; (2) Rare plants and vegetation assemblages; (3) Rare wildlife and their habitat; (4) Rare aquatic species; and (5) Wetlands/Floodplains. A summary of project actions taken or planned in order to avoid, minimize, or mitigate the environmental impacts associated with this project are summarized in the conclusion section of this report.

  16. Assessment of Critical Events Corridors through Multivariate Cascading Outages Analysis

    SciTech Connect (OSTI)

    Makarov, Yuri V.; Samaan, Nader A.; Diao, Ruisheng; Kumbale, Murali; Chen, Yousu; Singh, Ruchi; Green, Irina; Morgan, Mark P.

    2011-10-17

    Massive blackouts of electrical power systems in North America over the past decade has focused increasing attention upon ways to identify and simulate network events that may potentially lead to widespread network collapse. This paper summarizes a method to simulate power-system vulnerability to cascading failures to a supplied set of initiating events synonymously termed as Extreme Events. The implemented simulation method is currently confined to simulating steady state power-system response to a set of extreme events. The outlined method of simulation is meant to augment and provide a new insight into bulk power transmission network planning that at present remains mainly confined to maintaining power system security for single and double component outages under a number of projected future network operating conditions. Although one of the aims of this paper is to demonstrate the feasibility of simulating network vulnerability to cascading outages, a more important goal has been to determine vulnerable parts of the network that may potentially be strengthened in practice so as to mitigate system susceptibility to cascading failures. This paper proposes to demonstrate a systematic approach to analyze extreme events and identify vulnerable system elements that may be contributing to cascading outages. The hypothesis of critical events corridors is proposed to represent repeating sequential outages that can occur in the system for multiple initiating events. The new concept helps to identify system reinforcements that planners could engineer in order to 'break' the critical events sequences and therefore lessen the likelihood of cascading outages. This hypothesis has been successfully validated with a California power system model.

  17. Successful River Corridor Contractor Completes Extra Work Scope...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... concrete-lined drums containing highly contaminated liquids were recovered; several chromium waste sites reached groundwater at a depth of 85 feet; workers removed unexploded ...

  18. An Optimal Deployment of Wireless Charging Lane for Electric Vehicles on Highway Corridors

    SciTech Connect (OSTI)

    Huang, Yongxi

    2016-01-01

    We propose an integrated modeling framework to optimally locate wireless charging facilities along a highway corridor to provide sufficient in-motion charging. The integrated model consists of a master, Infrastructure Planning Model that determines best locations with integrated two sub-models that explicitly capture energy consumption and charging and the interactions between electric vehicle and wireless charging technologies, geometrics of highway corridors, speed, and auxiliary system. The model is implemented in an illustrative case study of a highway corridor of Interstate 5 in Oregon. We found that the cost of establishing the charging lane is sensitive and increases with the speed to achieve. Through sensitivity analyses, we gain better understanding on the extent of impacts of geometric characteristics of highways and battery capacity on the charging lane design.

  19. Digging Begins at Hazardous Hanford Burial Ground- River Corridor Contractor Spent Two Years Preparing to Remediate 618-10

    Broader source: Energy.gov [DOE]

    RICHLAND, WASH. — After careful preparation and characterization, the Department of Energy’s (DOE) River Corridor contractor, Washington Closure Hanford, has begun remediation of one of the most hazardous burial grounds tackled to date on the Hanford Site’s River Corridor.

  20. Concurrent Wind Cooling in Power Transmission Lines

    SciTech Connect (OSTI)

    Jake P Gentle

    2012-08-01

    Idaho National Laboratory and the Idaho Power Company, with collaboration from Idaho State University, have been working on a project to monitor wind and other environmental data parameters along certain electrical transmission corridors. The combination of both real-time historical weather and environmental data is being used to model, validate, and recommend possibilities for dynamic operations of the transmission lines for power and energy carrying capacity. The planned results can also be used to influence decisions about proposed design criteria for or upgrades to certain sections of the transmission lines.

  1. EIS-0436: I-5 Corridor Reinforcement Project; Multnomah County...

    Office of Environmental Management (EM)

    proposal to build a 500-kilovolt (kV) lattice-steel-tower transmission line that would run from a new 500-kV substation near Castle Rock, Washington, to a new 500-kV substation...

  2. Lessons Learned during Creation of the I-65 Biofuels Corridor (White Paper)

    SciTech Connect (OSTI)

    Not Available

    2009-06-01

    A team of Clean Cities coalitions and state agencies worked together to create a biofuels corridor along I-65 between Indiana and Alabama. The team built relationships with stakeholders and learned the value of strong partnerships, good communication, marketing, and preparation.

  3. Department of Energy Announces Plans for Additional Comment Period on National Interest Electric Transmission Corridors

    Broader source: Energy.gov [DOE]

    The Department has decided that, prior to issuing a report that designates any national interest electric transmission corridor, the Department will first issue any designation that it is considering in draft form, so as to allow additional opportunities for review and comment by affected States, regional entities, and the general public.

  4. Placing power linres : GIS helps site energy corridors.

    SciTech Connect (OSTI)

    Kuiper, J. A.; Cantwell, B.; Hlohowskyj, I.; Moore, H. R.

    2011-08-01

    Turn the lights on when you enter a room, then turn the lights off when you leave. Most of us repeat this sequence many times each day, and never give it another thought. But that seemingly simple light switch on the wall connects us to one of the most complex systems in the world: the electrical grid. Most of the United States is served by a highly reliable and adequate supply of electrical power, which is distributed through a grid of thousands of miles of electricity-transmission lines. However, as the electricity-supply infrastructure ages and consumer demand for electricity grows, the capacity to deliver electrical power hasn't kept pace with demand, and upgrading the electrical-transmission grid has become a more pressing need. From 1988-1998, demand for transmission grew by 30 percent while transmission grew by only 15 percent. From 1999-2009, demand grew by 20 percent and transmission by only 3 percent Despite a short-term decline related to the economic downturn and improved efficiency, U.S. energy consumption is expected to increase by 14 percent between 2008 and 2035. This growth will drive the need to develop viable routes for new transmission lines. Because transmission lines extend over large distances, they typically cross many federal, tribal, state, local and private land jurisdictions, each with a complex and varying set of siting issues and land-management practices. And as the existing grid needs improvement to meet growing demand, the U.S. is rapidly developing renewable energy sources, particularly solar and wind energy, often in areas far removed from existing electricity-transmission infrastructure and energy-consumption areas.

  5. River Corridor Baseline Risk Assessment (RCBRA) Human Health Risk Assessment (Volume 2)

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Sands Jim Hansen U.S. Department of Energy - Richland Operations Office October 12, 2011 River Corridor Baseline Risk Assessment (RCBRA) Human Health Risk Assessment (Volume 2) * RCBRA Human Health Risk Assessment is final - Response provided to HAB advice #246 * RCBRA Ecological Risk Assessment (Draft C) was transmitted to regulators September 27 * Columbia River Component - Draft Ecological Screening Level Risk Assessment ready for regulator review - Draft Human health risk assessment will be

  6. Road-corridor planning in the EIA procedure in Spain. A review of case studies

    SciTech Connect (OSTI)

    Loro, Manuel [Department of Urban and Regional Planning and Environment, Civil Engineering School, Universidad Politcnica de Madrid, Prof. Aranguren s Transport Research Centre Universidad Politcnica de Madrid, ETSI Caminos, Canales y Puertos, Prof. Aranguren s Centro de investigacin del transporte, TRANSyT-UPM, ETSI Caminos, Canales y Puertos, Universidad Politcnica de Madrid, Prof. Aranguren s Arce, Rosa M. [Department of Urban and Regional Planning and Environment, Civil Engineering School, Universidad Politcnica de Madrid, Prof. Aranguren s Transport Research Centre Universidad Politcnica de Madrid, ETSI Caminos, Canales y Puertos, Prof. Aranguren s Centro de investigacin del transporte, TRANSyT-UPM, ETSI Caminos, Canales y Puertos, Universidad Politcnica de Madrid, Prof. Aranguren s Ortega, Emilio [Transport Research Centre Universidad Politcnica de Madrid, ETSI Caminos, Canales y Puertos, Prof. Aranguren s Centro de investigacin del transporte, TRANSyT-UPM, ETSI Caminos, Canales y Puertos, Universidad Politcnica de Madrid, Prof. Aranguren s Department of Construction and Rural Roads, Forestry Engineering School, Universidad Politcnica de Madrid, Ciudad Universitaria s and others

    2014-01-15

    The assessment of different alternatives in road-corridor planning must be based on a number of well-defined territorial variables that serve as decision making criteria, and this requires a high-quality preliminary environmental assessment study. In Spain the formal specifications for the technical requirements stipulate the constraints that must be considered in the early stages of defining road corridors, but not how they should be analyzed and ranked. As part of the feasibility study of a new road definition, the most common methodology is to establish different levels of Territorial Carrying Capacity (TCC) in the study area in order to summarize the territorial variables on thematic maps and to ease the tracing process of road-corridor layout alternatives. This paper explores the variables used in 22 road-construction projects conducted by the Ministry of Public Works that were subject to the Spanish EIA regulation and published between 2006 and 2008. The aim was to evaluate the quality of the methods applied and the homogeneity and suitability of the variables used for defining the TCC. The variables were clustered into physical, environmental, land-use and cultural constraints for the purpose of comparing the TCC values assigned in the studies reviewed. We found the average quality of the studies to be generally acceptable in terms of the justification of the methodology, the weighting and classification of the variables, and the creation of a synthesis map. Nevertheless, the methods for assessing the TCC are not sufficiently standardized; there is a lack of uniformity in the cartographic information sources and methodologies for the TCC valuation. -- Highlights: We explore 22 road-corridor planning studies subjected to the Spanish EIA regulation. We analyze the variables selected for defining territorial carrying capacity. The quality of the studies is acceptable (methodology, variable weighting, mapping). There is heterogeneity in the methods for territorial carrying capacity valuation.

  7. Usage of Electric Vehicle Supply Equipment Along the Corridors between the EV Project Major Cities

    SciTech Connect (OSTI)

    Mindy Kirkpatrick

    2012-05-01

    The report explains how the EVSE are being used along the corridors between the EV Project cities. The EV Project consists of a nationwide collaboration between Idaho National Laboratory (INL), ECOtality North America, Nissan, General Motors, and more than 40 other city, regional and state governments, and electric utilities. The purpose of the EV Project is to demonstrate the deployment and use of approximately 14,000 Level II (208-240V) electric vehicle supply equipment (EVSE) and 300 fast chargers in 16 major cities. This research investigates the usage of all currently installed EV Project commercial EVSE along major interstate corridors. ESRI ArcMap software products are utilized to create geographic EVSE data layers for analysis and visualization of commercial EVSE usage. This research locates the crucial interstate corridors lacking sufficient commercial EVSE and targets locations for future commercial EVSE placement. The results and methods introduced in this research will be used by INL for the duration of the EV Project.

  8. From: Laurie Smith To: Congestion Study Comments Subject: Taking of Private Property for Overhead Transmission Lines

    Energy Savers [EERE]

    Taking of Private Property for Overhead Transmission Lines Date: Friday, September 19, 2014 9:18:01 AM Scores of people in my area are opposed to the establishment of National Interest Energy Transmission Corridors (NIETC's) for the following reasons: First, the easements place an undo burden on landowners on and near the transmission lines. The compensation cannot begin to cover the all of the losses, tangible and intangible that landowners would suffer. The easements prevent the landowner from

  9. Transmission Line Security Monitor: Final Report

    SciTech Connect (OSTI)

    John Svoboda

    2011-04-01

    The Electric Power Transmission Line Security Monitor System Operational Test is a project funded by the Technical Support Working Group (TSWG). TSWG operates under the Combating Terrorism Technical Support Office that functions under the Department of Defense. The Transmission Line Security Monitor System is based on technology developed by Idaho National Laboratory. The technology provides a means for real-time monitoring of physical threats and/or damage to electrical transmission line towers and conductors as well as providing operational parameters to transmission line operators to optimize transmission line operation. The end use is for monitoring long stretches of transmission lines that deliver electrical power from remote generating stations to cities and industry. These transmission lines are generally located in remote transmission line corridors where security infrastructure may not exist. Security and operational sensors in the sensor platform on the conductors take power from the transmission line and relay security and operational information to operations personnel hundreds of miles away without relying on existing infrastructure. Initiated on May 25, 2007, this project resulted in pre-production units tested in realistic operational environments during 2010. A technology licensee, Lindsey Manufacturing of Azusa California, is assisting in design, testing, and ultimately production. The platform was originally designed for a security monitoring mission, but it has been enhanced to include important operational features desired by electrical utilities.

  10. mhtml:file://H:\CATX\APPROVED-CXS\EERE FOA 1201 - Rankine Cycle

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    . ., . . BNL-68599 PRODUCTION OF RADIOACTIVE IODINE David J. Schlyer Iodine-123 Probably the most 'widely used cyclotron produced radiohalogen is 1-123. It has gradually replaced I-13 1 as the isotope of choice for diagnostic radiopharmaceuticals containing radioiodine. It gives a much lower radiation dose to the patient and the gamma ray energy of 159 keV is ideally suited for use in a gamma camera. The gamma ray will penetrate tissue very effectively without excessive radiation dose. For this

  11. Line Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Grand Coulee Transmission Line Replacement Project Hooper Springs McNary-John Day Montana-to-Washington Transmission System Upgrade Project - M2W Olympia-Grand Coulee No. 1...

  12. A Geophysical Characterization & Monitoring Strategy for Determining Hydrologic Processes in the Hyporheic Corridor at the Hanford 300-Area

    SciTech Connect (OSTI)

    Slater, Lee; Day-Lewis, Frederick; Lane, John; Versteeg, Roelof; Ward, Anderson; Binley, Andrew; Johnson, Timothy; Ntarlagiannis, Dimitrios

    2011-08-31

    The primary objective of this research was to advance the prediction of solute transport between the Uranium contaminated Hanford aquifer and the Columbia River at the Hanford 300 Area by improving understanding of how fluctuations in river stage, combined with subsurface heterogeneity, impart spatiotemporal complexity to solute exchange along the Columbia River corridor. Our work explored the use of continuous waterborne electrical imaging (CWEI), in conjunction with fiber-optic distributed temperature sensor (FO-DTS) and time-lapse resistivity monitoring, to improve the conceptual model for how groundwater/surface water exchange regulates uranium transport. We also investigated how resistivity and induced polarization can be used to generate spatially rich estimates of the variation in depth to the Hanford-Ringold (H-R) contact between the river and the 300 Area Integrated Field Research Challenge (IFRC) site. Inversion of the CWEI datasets (a data rich survey containing {approx}60,000 measurements) provided predictions of the distributions of electrical resistivity and polarizability, from which the spatial complexity of the primary hydrogeologic units along the river corridor was reconstructed. Variation in the depth to the interface between the overlying coarse-grained, high permeability Hanford Formation and the underlying finer-grained, less permeable Ringold Formation, an important contact that limits vertical migration of contaminants, has been resolved along {approx}3 km of the river corridor centered on the IFRC site in the Hanford 300 Area. Spatial variability in the thickness of the Hanford Formation captured in the CWEI datasets indicates that previous studies based on borehole projections and drive-point and multi-level sampling likely overestimate the contributing area for uranium exchange within the Columbia River at the Hanford 300 Area. Resistivity and induced polarization imaging between the river and the 300 Area IFRC further imaged spatial variability in the depth to the Hanford-Ringold inland over a critical region where borehole information is absent, identifying evidence for a continuous depression in the H-R contact between the IFRC and the river corridor. Strong natural contrasts in temperature and specific conductance of river water compared to groundwater at this site, along with periodic river stage fluctuations driven by dam operations, were exploited to yield new insights into the dynamics of groundwater-surface water interaction. Whereas FO-DTS datasets have provided meter-scale measurements of focused groundwater discharge at the riverbed along the corridor, continuous resistivity monitoring has non-invasively imaged spatiotemporal variation in the resistivity inland driven by river stage fluctuations. Time series and time-frequency analysis of FO-DTS and 3D resistivity datasets has provided insights into the role of forcing variables, primarily daily dam operations, in regulating the occurrence of focused exchange at the riverbed and its extension inland. High amplitudes in the DTS and 3D resistivity signals for long periods that dominate the stage time series identify regions along the corridor where stage-driven exchange is preferentially focused. Our work has demonstrated how time-series analysis of both time-lapse resistivity and DTS datasets, in conjunction with resistivity/IP imaging of lithology, can improve understanding of groundwater-surface water exchange along river corridors, offering unique opportunities to connect stage-driven groundwater discharge observed with DTS on the riverbed to stage-driven groundwater and solute fluctuations captured with resistivity inland.

  13. Strategy for the Integration of Hydrogen as a Vehicle Fuel into the Existing Natural Gas Vehicle Fueling Infrastructure of the Interstate Clean Transportation Corridor Project: 22 April 2004--31 August 2005

    SciTech Connect (OSTI)

    Gladstein, Neandross and Associates

    2005-09-01

    Evaluates opportunities to integrate hydrogen into the fueling stations of the Interstate Clean Transportation Corridor--an existing network of LNG fueling stations in California and Nevada.

  14. Energy transport corridors: the potential role of Federal lands in states identified by the Energy Policy Act of 2005, section 368(b).

    SciTech Connect (OSTI)

    Krummel, J.; Hlohowskyj, I.; Kuiper, J.; Kolpa, R.; Moore, R.; May, J.; VanKuiken, J.C.; Kavicky, J.A.; McLamore, M.R.; Shamsuddin, S.

    2011-09-01

    On August 8, 2005, the President signed the Energy Policy Act of 2005 (EPAct) into law. In Subtitle F of EPAct, Congress set forth various provisions that would change the way certain federal agencies (Agencies) coordinate to authorize the use of land for a variety of energy-related purposes. As part of Subtitle F of EPAct, Section 368 addresses the issue of energy transportation corridors on federal land for oil, gas, and hydrogen pipelines, as well as electricity transmission and distribution facilities. Because of the critical importance of improving the nation's electrical transmission grid, Congress recognized that electricity transmission issues should receive added attention when the Agencies address corridor location and analysis issues. In Section 368, Congress specifically directed the Agencies to consider the need for upgraded and new facilities to deliver electricity: In carrying out [Section 368], the Secretaries shall take into account the need for upgraded and new electricity transmission and distribution facilities to (1) improve reliability; (2) relieve congestion; and (3) enhance capability of the national grid to deliver electricity. Section 368 does not require the Agencies to consider or approve specific projects, applications for rights-of-way (ROWs), or other permits within designated energy corridors. Importantly, Section 368 does not direct, license, or otherwise permit any on-the-ground activity of any sort. If an applicant is interested in obtaining an authorization to develop a project within any corridor designated under Section 368, the applicant would have to apply for a ROW authorization and applicable permits. The Agencies would consider each application by applying appropriate project-specific reviews under requirements of laws and related regulations, including, but not limited to, the National Environmental Policy Act (NEPA), the Clean Water Act, the Clean Air Act, Section 7 of the Endangered Species Act (ESA), and Section 106 of the National Historic Preservation Act (NHPA). Under Section 368, Congress divided the United States into two groups of states: the 11 contiguous western states and the remaining states. Direction for energy transportation corridor analysis and selection in the 11 western states was addressed in Section 368(a) of EPAct, while direction for energy transportation corridor analysis and selection in all other states was addressed under Section 368(b) of EPAct. It was clearly the priority of Congress to conduct corridor location studies and designation first on federal lands in the western states. Under Section 368(a), the Agencies produced a programmatic environmental impact statement (EIS), Designation of Energy Corridors on Federal Land in the 11 Western States (DOE and DOI 2008), that was used in part as the basis for designating more than 6,000 mi (9,656 km) of energy transportation corridors on federal land in 11 western states. Under Section 368(a) of EPAct, Congress clearly stated the Agencies needed to (1) designate energy transportation corridors on federal land, (2) conduct the necessary environmental review of the designated corridors, and (3) incorporate the designated corridors into the appropriate land use plans. Congressional direction under Section 368(b) of EPAct differs from that provided under Section 368(a). Specifically, Section 368(b) requires the secretaries of the Agencies, in consultation with the Federal Energy Regulatory Commission (FERC), affected utility industries, and other interested persons, to jointly: (1) Identify corridors for oil, gas, and hydrogen pipelines and electricity transmission and distribution facilities on federal land in states other than the 11 western states identified under Section 368(a) of EPAct, and (2) Schedule prompt action to identify, designate, and incorporate the corridors into the applicable land use plans. While Section 368(a) clearly directs designation as a necessary first step for energy transportation corridors in the 11 western states, Section 368(b) directs the Agencies to first identify corridors and then schedule prompt action to identify, designate, and incorporate the corridors into applicable land use plans. To comply with the congressional direction provided in Section 368(b), the Agencies investigated corridor identification issues in the Section 368(b) states; this report to Congress provides information that could be relevant to possible future designation of energy corridors. Future designations, if appropriate and necessary, would occur when the Agencies undertake revisions and/or updates to land use plans that guide management decisions on lands located within individual administrative units, such as specific National Forests, National Parks, or Wildlife Refuges. At this time, the Agencies are not proposing any actions or decisions related directly or indirectly to designating energy corridors on federal land under Section 368(b) of EPAct.

  15. A First Preliminary Look: Are Corridor Charging Stations Used to Extend the Range of Electric Vehicles in The EV Project?

    SciTech Connect (OSTI)

    John Smart

    2013-01-01

    A preliminary analysis of data from The EV Project was performed to begin answering the question: are corridor charging stations used to extend the range of electric vehicles? Data analyzed were collected from Blink brand electric vehicle supply equipment (EVSE) units based in California, Washington, and Oregon. Analysis was performed on data logged between October 1, 2012 and January 1, 2013. It should be noted that as additional AC Level 2 EVSE and DC fast chargers are deployed, and as drivers become more familiar with the use of public charging infrastructure, future analysis may have dissimilar conclusions.

  16. Integrated survey and design for transmission lines

    SciTech Connect (OSTI)

    Miller, M.A.; Simpson, K.D.

    1994-12-31

    Gathering and compiling information on the features and uses of the land within a proposed corridor provides the basis for selecting a route, obtaining easements, and designing and constructing a transmission line. Traditionally, gathering this information involved searches of existing maps and records to obtain the available information, which would then be supplemented with aerial photography to record current conditions. Ground surveys were performed to collect topographic data for design purposes. This information was manually transferred to drawings and other documents to show the terrain, environmentally sensitive areas, property ownership, and existing facilities. These drawing served as the base to which the transmission line right-of-way, structures, and other design information were added. As the design was completed, these drawings became the source of information for constructing the line and ultimately, the record of the facility. New technologies and the every growing need for instantly accessible information have resulted in changes in almost every step of gathering, storing and using information. Electronic data collection, global positioning systems (GPS), digitized terrain models, computerized design techniques, development of drawings using CAD, and graphical information systems (GIS) have individually resulted in significant advancements in this process. Combining these components into an integrated system, however, is truly revolutionizing transmission line engineering. This paper gives an overview of the survey and mapping information that is required for transmission line projects, review the traditional techniques that have been employed to obtain and utilize this information, and discuss the recent advances in the technology. Additionally, a system is presented that integrates the components in this process to achieve efficiency, minimize chances of errors, and provide improved access to project information.

  17. FY-09 Summary Report to the Office of Petroleum Reserves on the Western Energy Corridor Initiative Activities and Accomplishments

    SciTech Connect (OSTI)

    Thomas R. Wood

    2010-01-01

    To meet its programmatic obligations under the Energy Policy Act of 2005, the Office of Naval Petroleum and Shale Oil Reserves (NPSOR) has initiated the Western Energy Corridor Initiative (WECI). The WECI will implement the Unconventional Strategic Fuels Task Force recommendations for accelerating and promoting the development of domestic unconventional fuels to help meet the nations’ energy needs. The mission of the WECI is to bolster America’s future fuel security by facilitating socially and environmentally responsible development of unconventional fuels resources in the Western Energy Corridor, using sound engineering principles and science-based methods to define and assess benefits, impacts, uncertainties, and mitigation options and to resolve impediments. The Task Force proposed a three-year program in its commercialization plan. The work described herein represents work performed by Idaho National Laboratory (INL) in support of the DOE’s WECI. This effort represents an interim phase of work, designed to initiate only select portions of the initiative, limited by available funding resources within NPOSR. Specifically, the work presented here addresses what was accomplished in FY-09 with the remaining carryover (~$420K) from NPOSR FY-08 funds. It was the intent of the NPOSR program to seek additional funding for full implementation of the full scope of work; however, the original tasks were reduced in scope, terminated, or eliminated (as noted below). An effort is ongoing to obtain funding to continue the tasks initiated under this project. This study will focus on the integrated development of multiple energy resources in a carbon-neutral and environmentally acceptable manner. Emphasis will be placed on analyses of the interrelationships of various energy-resource development plans and the infrastructure, employment, training, fiscal, and economic demands placed on the region as a result of various development scenarios. The interactions at build-out during the design, permitting, and construction of individual and multiple energy developments are not fully considered at the local, state, regional, or national levels. The net impacts to the Western Energy Corridor cannot be understood and the design optimized under the current approach. A regional development plan is needed to model cumulative impacts, determine the carrying capacity of the basin, and provide valuable technically based information to both skeptics and advocates. The INL scope of work for FY-09 involved six tasks: 1. Evaluation of the ASPEN Code as a dynamic systems model for application and use under the WECI and communications with Alberta Oil Sands Research Institutions as an “analog” resource development in the Western Energy Corridor 2. Application of the Aspen Plus computer model to several oil shale processes to consider energy balances and inputs and outputs (e.g. water consumption, CO2 production, etc.) 3. Development of a regulatory roadmap for oil shale developments 4. Defining of the physiographic extent of the natural resource reserves that comprise the Western Energy Corridor 5. A review of the Unconventional Fuels Task Force Report to Congress for ideas, concepts and recommendations that crosscutting plans 6. Program development with stakeholders, including industry, academics, state and federal agencies, and non government organizations. This task also includes project management, strategic development and reporting.

  18. CX-011788: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    I-75 Green Corridor Project CX(s) Applied: A1 Date: 02/10/2014 Location(s): Tennessee Offices(s): National Energy Technology Laboratory

  19. CX-007095: Categorical Exclusion Determination | Department of...

    Office of Environmental Management (EM)

    Determination CX-007095: Categorical Exclusion Determination Paving the Way with Propane: The AutoGas Corridor Development Program CX(s) Applied: B5.1 Date: 10132011...

  20. CX-007096: Categorical Exclusion Determination | Department of...

    Office of Environmental Management (EM)

    Determination CX-007096: Categorical Exclusion Determination Paving the Way with Propane: The AutoGas Corridor Development Program CX(s) Applied: B5.1 Date: 10132011...

  1. CX-009753: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Propane Corridor Development Program CX(s) Applied: B5.22 Date: 12/06/2012 Location(s): Georgia Offices(s): National Energy Technology Laboratory

  2. From: Laurie Smith To: Congestion Study Comments Subject: High Voltage Transmission Lines

    Energy Savers [EERE]

    High Voltage Transmission Lines Date: Sunday, September 21, 2014 10:02:26 AM To Whom it May Concern DOE: For the following reasons I am opposed to the establishment of National Interest Energy Transmission Corridors (NIETC's): Before the authority of eminent domain should be granted to an energy corp., that corp. should have to prove necessity to the exact locations that the energy is to be transported and that the recipients NEED and WANT that energy and that the region cannot produce their own

  3. EIS-0436: I-5 Corridor Reinforcement Project; Multnomah County, Oregon, and Cowlitz and Clark Counties, Washington

    Broader source: Energy.gov [DOE]

    DOE’s Bonneville Power Administration (BPA) prepared an EIS that evaluates the potential environmental impacts of a BPA proposal to build a 500-kilovolt (kV) lattice-steel-tower transmission line that would run from a new 500-kV substation near Castle Rock, Washington, to a new 500-kV substation near Troutdale, Oregon.

  4. Plains and Eastern Clean Line Transmission Line: Comment from...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Plains and Eastern Clean Line Transmission Line: Comment from Mr. Dyer Plains and Eastern Clean Line Transmission Line: Comment from Sheila Beck Plains and Eastern Clean Line ...

  5. Plains and Eastern Clean Line Transmission Line: Comment from...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Plains and Eastern Clean Line Transmission Line: Comment from Change.org Plains and Eastern Clean Line Transmission Line: Comment from Mr. Leftwich Plains and Eastern Clean Line ...

  6. FINAL PROJECT REPORT: A Geophysical Characterization & Monitoring Strategy for Determining Hydrologic Processes in the Hyporheic Corridor at the Hanford 300-Area

    SciTech Connect (OSTI)

    Lee Slater

    2011-08-15

    The primary objective of this research was to advance the prediction of solute transport between the Uranium contaminated Hanford aquifer and the Columbia River at the Hanford 300 Area by improving understanding of how fluctuations in river stage, combined with subsurface heterogeneity, impart spatiotemporal complexity to solute exchange along the Columbia River corridor. Our work explored the use of continuous waterborne electrical imaging (CWEI), in conjunction with fiber-optic distributed temperature sensor (FO-DTS) and time-lapse resistivity monitoring, to improve the conceptual model for how groundwater/surface water exchange regulates uranium transport. We also investigated how resistivity and induced polarization can be used to generate spatially rich estimates of the variation in depth to the Hanford-Ringold (H-R) contact between the river and the 300 Area Integrated Field Research Challenge (IFRC) site. Inversion of the CWEI datasets (a data rich survey containing ~60,000 measurements) provided predictions of the distributions of electrical resistivity and polarizability, from which the spatial complexity of the primary hydrogeologic units along the river corridor was reconstructed. Variation in the depth to the interface between the overlying coarse-grained, high permeability Hanford Formation and the underlying finer-grained, less permeable Ringold Formation, an important contact that limits vertical migration of contaminants, has been resolved along ~3 km of the river corridor centered on the IFRC site in the Hanford 300 Area. Spatial variability in the thickness of the Hanford Formation captured in the CWEI datasets indicates that previous studies based on borehole projections and drive-point and multi-level sampling likely overestimate the contributing area for uranium exchange within the Columbia River at the Hanford 300 Area. Resistivity and induced polarization imaging between the river and the 300 Area IFRC further imaged spatial variability in the depth to the Hanford-Ringold inland over a critical region where borehole information is absent, identifying evidence for a continuous depression in the H-R contact between the IFRC and the river corridor. Strong natural contrasts in temperature and specific conductance of river water compared to groundwater at this site, along with periodic river stage fluctuations driven by dam operations, were exploited to yield new insights into the dynamics of groundwater-surface water interaction. Whereas FO-DTS datasets have provided meter-scale measurements of focused groundwater discharge at the riverbed along the corridor, continuous resistivity monitoring has non-invasively imaged spatiotemporal variation in the resistivity inland driven by river stage fluctuations. Time series and time-frequency analysis of FO-DTS and 3D resistivity datasets has provided insights into the role of forcing variables, primarily daily dam operations, in regulating the occurrence of focused exchange at the riverbed and its extension inland. High amplitudes in the DTS and 3D resistivity signals for long periods that dominate the stage time series identify regions along the corridor where stage-driven exchange is preferentially focused. Our work has demonstrated how time-series analysis of both time-lapse resistivity and DTS datasets, in conjunction with resistivity/IP imaging of lithology, can improve understanding of groundwater-surface water exchange along river corridors, offering unique opportunities to connect stage-driven groundwater discharge observed with DTS on the riverbed to stage-driven groundwater and solute fluctuations captured with resistivity inland.

  7. Plains and Eastern Clean Line Transmission Line: Comment from...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Comment from Downwind, LLC Plains and Eastern Clean Line Transmission Line: Comment from Sheila Beck Plains and Eastern Clean Line Transmission Line: Comment from Crystal Yarbrough

  8. Plains and Eastern Clean Line Transmission Line: Comment from...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Clean Line: Arkansas and Oklahoma Plains and Eastern Clean Line Transmission Line: Comment from Block Plains and Eastern Clean Line: Arkansas and Oklahoma Comment submitted on ...

  9. Plains and Eastern Clean Line Transmission Line: Comment from...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Plains and Eastern Clean Line Transmission Line: Comment from Fallon Sanford Plains and Eastern Clean Line Transmission Line: Comment from Mr. Leftwich Plains and Eastern Clean ...

  10. Nuclear reactor overflow line

    DOE Patents [OSTI]

    Severson, Wayne J.

    1976-01-01

    The overflow line for the reactor vessel of a liquid-metal-cooled nuclear reactor includes means for establishing and maintaining a continuous bleed flow of coolant amounting to 5 to 10% of the total coolant flow through the overflow line to prevent thermal shock to the overflow line when the reactor is restarted following a trip. Preferably a tube is disposed concentrically just inside the overflow line extending from a point just inside the reactor vessel to an overflow tank and a suction line is provided opening into the body of liquid metal in the reactor vessel and into the annulus between the overflow line and the inner tube.

  11. Anonymous Help Line

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Anonymous Help Line Ombuds Anonymous Help Line Committed to the fair and equitable treatment of all employees, contractors, and persons doing business with the Laboratory. Contact Ombuds Office (505)665-2837 Email Help Line (505) 667-9370 Fax (505) 667-3119 Map & Hours Anonymous Help Line: (505) 667-9370 As an option to visiting the Ombuds office, we provide service through a telephone Help Line and email. The telephone Help Line is useful for individuals who have concerns and want advice or

  12. Integrating spatial support tools into strategic planning-SEA of the GMS North-South Economic Corridor Strategy and Action Plan

    SciTech Connect (OSTI)

    Ramachandran, Pavit; Linde, Lothar

    2011-11-15

    The GMS countries, supported by the Asian Development Bank, have adopted a holistic, multidimensional approach to strengthen infrastructural linkages and facilitate cross border trade through (i) the establishment of a trans-boundary road connecting two economic nodes across marginalised areas, followed by 2) facilitation of environmentally and socially sound investments in these newly connected areas as a means to develop livelihoods. The North-South Economic Corridor is currently in its second phase of development, with investment opportunities to be laid out in the NSEC Strategy and Action Plan (SAP). It targets the ecologically and culturally sensitive border area between PR China's Yunnan Province, Northern Lao PDR, and Thailand. A trans-boundary, cross-sectoral Strategic Environmental Assessment was conducted to support the respective governments in assessing potential environmental and social impacts, developing alternatives and mitigation options, and feeding the findings back into the SAP writing process. Given the spatial dimension of corridor development-both with regard to opportunities and risks-particular emphasis was put in the application of spatial modelling tools to help geographically locate and quantify impacts as a means to guide interventions and set priorities.

  13. River Corridor - Hanford Site

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    B Reactor 300 Area 324 Building 618-10 and 618-11 Burial Grounds C Reactor D and DR Reactors F Reactor H Reactor N Reactor Environmental Restoration Disposal Facility K East and...

  14. River Corridor - Hanford Site

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    300 Area 324 Building 325 Building 400 AreaFast Flux Test Facility 618-10 and 618-11 Burial Grounds 700 Area B Plant B Reactor C Reactor Canister Storage Building and Interim ...

  15. Series Transmission Line Transformer

    DOE Patents [OSTI]

    Buckles, Robert A.; Booth, Rex; Yen, Boris T.

    2004-06-29

    A series transmission line transformer is set forth which includes two or more of impedance matched sets of at least two transmissions lines such as shielded cables, connected in parallel at one end ans series at the other in a cascading fashion. The cables are wound about a magnetic core. The series transmission line transformer (STLT) which can provide for higher impedance ratios and bandwidths, which is scalable, and which is of simpler design and construction.

  16. Transmission Business Line

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Transmission Business Line Non-Federal Financing of Transmission Projects - March 2004 Critical paths on the Northwest transmission grid are congested and the system is near or at...

  17. Plains and Eastern Clean Line Transmission Line: Comment from Chantel |

    Energy Savers [EERE]

    Department of Energy from Chantel Plains and Eastern Clean Line Transmission Line: Comment from Chantel Comment submitted on updated Part 2 application. PDF icon Comment from Chantel 06-09-15.pdf More Documents & Publications Plains and Eastern Clean Line Transmission Line: Comment from Mr. Garrett Plains and Eastern Clean Line Transmission Line: Comment from Ms. Rutherford Plains and Eastern Clean Line Transmission Line: Comment from Ms. Campbell

  18. Plains and Eastern Clean Line Transmission Line: Comment from Marshall

    Energy Savers [EERE]

    Hughes | Department of Energy from Marshall Hughes Plains and Eastern Clean Line Transmission Line: Comment from Marshall Hughes Comment submitted on updated Part 2 application. PDF icon Comment from Marshall Hughes 07-10-15.pdf More Documents & Publications Plains and Eastern Clean Line Transmission Line: Comment from Mr. Dyer Plains and Eastern Clean Line Transmission Line: Comment from Sheila Beck Plains and Eastern Clean Line Transmission Line: Comment from Patti McCutchen

  19. Transmission Line Security Monitor

    ScienceCinema (OSTI)

    None

    2013-05-28

    The Transmission Line Security Monitor is a multi-sensor monitor that mounts directly on high-voltage transmission lines to detect, characterize and communicate terrorist activity, human tampering and threatening conditions around support towers. For more information about INL's critical infrastructure protection research, visit http://www.facebook.com/idahonationallaboratory.

  20. Transmission Line Security Monitor

    SciTech Connect (OSTI)

    2011-01-01

    The Transmission Line Security Monitor is a multi-sensor monitor that mounts directly on high-voltage transmission lines to detect, characterize and communicate terrorist activity, human tampering and threatening conditions around support towers. For more information about INL's critical infrastructure protection research, visit http://www.facebook.com/idahonationallaboratory.

  1. Hawaii Geothermal Project annotated bibliography: Biological resources of the geothermal subzones, the transmission corridors and the Puna District, Island of Hawaii

    SciTech Connect (OSTI)

    Miller, S.E.; Burgett, J.M.

    1993-10-01

    Task 1 of the Hawaii Geothermal Project Interagency Agreement between the Fish and Wildlife Service and the Department of Energy-Oak Ridge National Laboratory (DOE) includes an annotated bibliography of published and unpublished documents that cover biological issues related to the lowland rain forest in Puna, adjacent areas, transmission corridors, and in the proposed Hawaii Geothermal Project (HGP). The 51 documents reviewed in this report cover the main body of biological information for these projects. The full table of contents and bibliography for each document is included along with two copies (as requested in the Interagency Agreement) of the biological sections of each document. The documents are reviewed in five main categories: (1) geothermal subzones (29 documents); (2) transmission cable routes (8 documents); (3) commercial satellite launching facility (Spaceport; 1 document); (4) manganese nodule processing facility (2 documents); (5) water resource development (1 document); and (6) ecosystem stability and introduced species (11 documents).

  2. Coherent soliton communication lines

    SciTech Connect (OSTI)

    Yushko, O. V. Redyuk, A. A.; Fedoruk, M. P.; Turitsyn, S. K.

    2014-11-15

    The data transmission in coherent fiber-optical communication lines using solitons with a variable phase is studied. It is shown that nonlinear coherent structures (solitons) can be applied for effective signal transmission over a long distance using amplitude and optical-phase keying of information. The optimum ratio of the pulse width to the bit slot at which the spectral efficiency (transmitted bits per second and hertz) is maximal is determined. It is shown that soliton fiber-optical communication lines can ensure data transmission at a higher spectral efficiency as compared to traditional communication lines and at a high signal-to-noise ratio.

  3. Flow line sampler

    DOE Patents [OSTI]

    Nicholls, Colin I.

    1992-07-14

    An on-line product sampling apparatus and method for measuring product samples from a product stream (12) in a flow line (14) having a sampling aperture (11), includes a sampling tube (18) for containing product samples removed from flow line (14). A piston (22) removes product samples from the product stream (12) through the sampling aperture (11) and returns samples to product stream (12). A sensor (20) communicates with sample tube (18), and senses physical properties of samples while the samples are within sample tube (18). In one embodiment, sensor (20) comprises a hydrogen transient nuclear magnetic resonance sensor for measuring physical properties of hydrogen molecules.

  4. Maersk Line Equipment guide

    National Nuclear Security Administration (NNSA)

    Maersk Line containers has an average age of less than six years and a stringent maintenance programme ensures they are always ready for service. Each container in our fleet...

  5. Line Extension Alternatives

    Broader source: Energy.gov [DOE]

    The Public Service Board (PSB) of Vermont developed rules regarding utility line extension requests. While the majority of the rules focus on the procedure followed (and associated fees) for the...

  6. Power line detection system

    DOE Patents [OSTI]

    Latorre, V.R.; Watwood, D.B.

    1994-09-27

    A short-range, radio frequency (RF) transmitting-receiving system that provides both visual and audio warnings to the pilot of a helicopter or light aircraft of an up-coming power transmission line complex. Small, milliwatt-level narrowband transmitters, powered by the transmission line itself, are installed on top of selected transmission line support towers or within existing warning balls, and provide a continuous RF signal to approaching aircraft. The on-board receiver can be either a separate unit or a portion of the existing avionics, and can also share an existing antenna with another airborne system. Upon receipt of a warning signal, the receiver will trigger a visual and an audio alarm to alert the pilot to the potential power line hazard. 4 figs.

  7. Power line detection system

    DOE Patents [OSTI]

    Latorre, Victor R.; Watwood, Donald B.

    1994-01-01

    A short-range, radio frequency (RF) transmitting-receiving system that provides both visual and audio warnings to the pilot of a helicopter or light aircraft of an up-coming power transmission line complex. Small, milliwatt-level narrowband transmitters, powered by the transmission line itself, are installed on top of selected transmission line support towers or within existing warning balls, and provide a continuous RF signal to approaching aircraft. The on-board receiver can be either a separate unit or a portion of the existing avionics, and can also share an existing antenna with another airborne system. Upon receipt of a warning signal, the receiver will trigger a visual and an audio alarm to alert the pilot to the potential power line hazard.

  8. Transmission line capital costs

    SciTech Connect (OSTI)

    Hughes, K.R.; Brown, D.R.

    1995-05-01

    The displacement or deferral of conventional AC transmission line installation is a key benefit associated with several technologies being developed with the support of the U.S. Department of Energy`s Office of Energy Management (OEM). Previous benefits assessments conducted within OEM have been based on significantly different assumptions for the average cost per mile of AC transmission line. In response to this uncertainty, an investigation of transmission line capital cost data was initiated. The objective of this study was to develop a database for preparing preliminary estimates of transmission line costs. An extensive search of potential data sources identified databases maintained by the Bonneville Power Administration (BPA) and the Western Area Power Administration (WAPA) as superior sources of transmission line cost data. The BPA and WAPA data were adjusted to a common basis and combined together. The composite database covers voltage levels from 13.8 to 765 W, with cost estimates for a given voltage level varying depending on conductor size, tower material type, tower frame type, and number of circuits. Reported transmission line costs vary significantly, even for a given voltage level. This can usually be explained by variation in the design factors noted above and variation in environmental and land (right-of-way) costs, which are extremely site-specific. Cost estimates prepared from the composite database were compared to cost data collected by the Federal Energy Regulatory Commission (FERC) for investor-owned utilities from across the United States. The comparison was hampered because the only design specifications included with the FERC data were voltage level and line length. Working within this limitation, the FERC data were not found to differ significantly from the composite database. Therefore, the composite database was judged to be a reasonable proxy for estimating national average costs.

  9. Plains and Eastern Clean Line Transmission Line: Comment from...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    from Dr. Contreras Plains and Eastern Clean Line Transmission Line: Comment from Dr. Contreras Comment submitted on updated Part 2 application. PDF icon Comment from Dr. Contreras ...

  10. International 345 kV transmission line to Highgate, Vermont: environmental assessment

    SciTech Connect (OSTI)

    Not Available

    1985-02-01

    The action under consideration is the issuance of a Presidential permit to the Vermont Electric Power Company, Inc. (VELCO) for the construction, operation, maintenance and connection of a facility that will cross the United States-Canada border for international transmission of electric energy. The proposed transmission facilities will consist of a 7.5 mile, alternating current (ac) transmission line and a 200 MW back-to-back direct current (dc) converter terminal station. None of the facilities will involve any polluting emissions. The construction and maintenance of the proposed converter terminal station and transmission facilities will have little or no impact on the geologic features of the region. The transmission line will have little or no effect on agricultural land. Impacts on commercial forestry in the area will be minimal. The proposed route will require clearing about 36 acres of forest. The proposed transmission line and converter terminal site will have no effect on recreational activities, mining activites, residential, commercial, or industrial land use. The proposed corridor will have a minimal impact on area terrestrial wildlife and plant communities. The proposed project will have little or no impact on future population distribution, the operation of local services, employment and economic benefit, or housing in either Franklin or Highgate. 16 references, 3 figures. (ACR)

  11. Bonneville upgrades lines

    SciTech Connect (OSTI)

    Not Available

    1993-08-30

    A stretch of Bonneville Power Administration transmission line between Spokane and the Grand Coulee Dam is an 82-mile bottleneck as it is the last 115-kv section of [open quotes]road[close quotes] along a 500-kv transmission [open quotes]highway[close quotes]. Soon the administration will change all that. A number of independent and utility powerplants have been proposed in Idaho, Montana and the Spokane, Wash., area during the 1990s. As the operators will need to move their power, Bonneville is planning to build a $144-million, 500-kv line to upgrade the 115-kv section. The agency is planning to use its existing right-of-way.

  12. ONE NEVADA LINE | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ONE NEVADA LINE ONE NEVADA LINE ONE NEVADA LINE ONE NEVADA LINE ONE NEVADA LINE ONE NEVADA LINE ONE NEVADA LINE ONE NEVADA LINE ONE NEVADA LINE ONE NEVADA LINE ONE NEVADA LINE ONE NEVADA LINE ONE NEVADA LINE ONE NEVADA LINE ONE NEVADA LINE PROJECT SUMMARY In February 2011, the Department of Energy issued a $343 million loan guarantee to finance the One Nevada Transmission Line (ON Line) project, a 235-mile, 500 kV AC transmission line capable of carrying 600 MW of power to the grid running

  13. Strategy for the Integration of Hydrogen as a Vehicle Fuel into the Existing Natural Gas Vehicle Fueling Infrastructure of the Interstate Clean Transportation Corridor Project: 22 April 2004--31 August 2005

    Alternative Fuels and Advanced Vehicles Data Center [Office of Energy Efficiency and Renewable Energy (EERE)]

    national laboratory of the U.S. Department of Energy Office of Energy Efficiency & Renewable Energy National Renewable Energy Laboratory Innovation for Our Energy Future Subcontract Report Strategy for the Integration of NREL/SR-540-38720 Hydrogen as a Vehicle Fuel into September 2005 the Existing Natural Gas Vehicle Fueling Infrastructure of the Interstate Clean Transportation Corridor Project April 22, 2004 - August 31, 2005 Gladstein, Neandross & Associates Santa Monica, California

  14. PLAINS & EASTERN CLEAN LINE TRANSMISSION LINE | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Section 1222 of the Energy Policy Act 2005 » PLAINS & EASTERN CLEAN LINE TRANSMISSION LINE PLAINS & EASTERN CLEAN LINE TRANSMISSION LINE On March 25, 2016, U.S. Secretary of Energy Dr. Ernest Moniz announced that the Department of Energy (DOE) will participate in the development of the Plains & Eastern Clean Line project (Project), a major clean energy infrastructure project. Through section 1222 of the Energy Policy Act of 2005, Congress authorized DOE to promote electric

  15. Plains & Eastern Clean Line Transmission Line - Part 2 Application |

    Energy Savers [EERE]

    Department of Energy Transmission Line - Part 2 Application Plains & Eastern Clean Line Transmission Line - Part 2 Application In addition to conducting a NEPA review of the proposed Plains & Eastern Clean Line Transmission Line project, DOE will also conduct due diligence on non-NEPA factors such as the project's technical and financial feasibility and whether the project is in the public interest. DOE will conduct a thorough review that includes making all required statutory

  16. Printed circuit dispersive transmission line

    DOE Patents [OSTI]

    Ikezi, H.; Lin-Liu, Y.R.; DeGrassie, J.S.

    1991-08-27

    A printed circuit dispersive transmission line structure is disclosed comprising an insulator, a ground plane formed on one surface of the insulator, a first transmission line formed on a second surface of the insulator, and a second transmission line also formed on the second surface of the insulator and of longer length than the first transmission line and periodically intersecting the first transmission line. In a preferred embodiment, the transmission line structure exhibits highly dispersive characteristics by designing the length of one of the transmission line between two adjacent periodic intersections to be longer than the other. 5 figures.

  17. Printed circuit dispersive transmission line

    DOE Patents [OSTI]

    Ikezi, Hiroyuki (Rancho Santa Fe, CA); Lin-Liu, Yuh-Ren (San Diego, CA); DeGrassie, John S. (Encinitas, CA)

    1991-01-01

    A printed circuit dispersive transmission line structure is disclosed comprising an insulator, a ground plane formed on one surface of the insulator, a first transmission line formed on a second surface of the insulator, and a second transmission line also formed on the second surface of the insulator and of longer length than the first transmission line and periodically intersecting the first transmission line. In a preferred embodiment, the transmission line structure exhibits highly dispersive characteristics by designing the length of one of the transmission line between two adjacent periodic intersections to be longer than the other.

  18. Drill string transmission line

    DOE Patents [OSTI]

    Hall, David R.; Hall, Jr., H. Tracy; Pixton, David S.; Bradford, Kline; Fox, Joe

    2006-03-28

    A transmission line assembly for transmitting information along a downhole tool comprising a pin end, a box end, and a central bore traveling between the pin end and the box end, is disclosed in one embodiment of the invention as including a protective conduit. A transmission line is routed through the protective conduit. The protective conduit is routed through the central bore and the ends of the protective conduit are routed through channels formed in the pin end and box end of the downhole tool. The protective conduit is elastically forced into a spiral or other non-linear path along the interior surface of the central bore by compressing the protective conduit to a length within the downhole tool shorter than the protective conduit.

  19. CRUCIBLE LINING METHOD

    DOE Patents [OSTI]

    Bone, W.H.; Schmidt, W.W.

    1958-11-01

    A method is presented for forming refractory liners in cylindrical reaction vessels used for the reductlon of uranium tetrafluoride to metallic uranium. A preliminary form, having positioning lugs attached thereto, is inserted into the reaction vessel and the refractory powder, usually CaO, is put in the annular space between the form and the inner wall of the reaction vessel. A jolting table is used to compact this charge of liner material ln place, and after thls has been done, the preliminary form is removed and the flnal form or plug is lnserted without disturbing the partially completed lining. The remainder of the lining charge is then introduced and compacted by jolting, after which the form is removed.

  20. Pipeline corridors through wetlands - summary of seventeen plant-community studies at ten wetland crossings. Topical report, February 1990--August 1994

    SciTech Connect (OSTI)

    Van Dyke, G.D. |; Shem, L.M.; Wilkey, P.L.; Zimmerman, R.E.; Alsum, S.K.

    1994-12-01

    As part of the Gas Research Institute Wetland Corridors Program, Argonne National Laboratory conducted field studies on 10 wetland crossings located in six states to document impacts of natural gas pipeline rights-of-way (ROWS) on 15 wetland plant communities. This study is unique in the number, range, ages, and variety of wetland crossings surveyed and compared. Vegetation data and recorded observations were analyzed to reveal patterns associated with age, installation technology, maintenance practices, and wetland type. This report summarizes the findings of this study. Results revealed that ROWs of pipelines installed according to recent wetland regulations rapidly revegetated with dense and diverse plant communities. The ROW plant communities were similar to those in the adjacent natural areas in species richness, wetland indicator values, and percentages of native species. The ROW plant communities developed from naturally available propagules without fertilization, liming, or artificial seeding. ROWs contributed to increased habitat and plant species diversity in the wetland. There was little evidence that they degrade the wetland by providing avenues for the spread of invasive and normative plant species. Most impacts are temporal in nature, decreasing rapidly during the first several years and more slowly thereafter to the extent permitted by maintenance and other ROW activities.

  1. Pipeline corridors through wetlands -- Impacts on plant communities: Little Timber Creek Crossing, Gloucester County, New Jersey. Topical report, August 1991--January 1993

    SciTech Connect (OSTI)

    Shem, L.M.; Zimmerman, R.E.; Alsum, S.K.; Van Dyke, G.D. |

    1994-12-01

    The goal of the Gas Research Institute Wetland Corridors Program is to document impacts of existing pipelines on the wetlands they traverse. To accomplish this goal, 12 existing wetland crossings were surveyed. These sites varied in elapsed time since pipeline construction, wetland type, pipeline installation techniques, and right-of-way (ROW) management practices. This report presents results of a survey conducted over the period of August 5--7, 1991, at the Little Timber Creek crossing in Gloucester County, New Jersey, where three pipelines, constructed in 1950, 1960, and 1990, cross the creek and associated wetlands. The old side of the ROW, created by the installation of the 1960 pipeline, was designed to contain a raised peat bed over the 1950 pipeline and an open-water ditch over the 1960 pipeline. The new portion of the ROW, created by installation of the 1990 pipeline, has an open-water ditch over the pipeline (resulting from settling of the backfill) and a raised peat bed (resulting from rebound of compacted peat). Both the old and new ROWs contain dense stands of herbs; the vegetation on the old ROW was more similar to that in the adjacent natural area than was vegetation in the new ROW. The ROW increased species and habitat diversity in the wetlands. It may contribute to the spread of purple loosestrife and affect species sensitive to habitat fragmentation.

  2. CX-011283: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    I-75 Green Corridor Project CX(s) Applied: A1, B5.2, B5.22 Date: 09/26/2013 Location(s): Florida Offices(s): National Energy Technology Laboratory

  3. CX-011800: Categorical Exclusion Determination

    Office of Energy Efficiency and Renewable Energy (EERE)

    I-75 Green Corridor Project CX(s) Applied: A1, A9, B5.22 Date: 01/29/2014 Location(s): Tennessee, Georgia, Florida Offices(s): National Energy Technology Laboratory

  4. CX-012269: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    I-75 Green Corridor Project CX(s) Applied: B5.22 Date: 06/25/2014 Location(s): Florida Offices(s): National Energy Technology Laboratory

  5. CX-008304: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Installation of Retail Biofuel Infrastructure Supporting I-75 Green Corridor Project CX(s) Applied: A1, B5.22 Date: 04/25/2012 Location(s): Michigan Offices(s): National Energy Technology Laboratory

  6. CX-007453: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Paving the Way with Propane: The AutoGas Corridor Development Program CX(s) Applied: B5.1 Date: 12/20/2011 Location(s): Georgia Offices(s): National Energy Technology Laboratory

  7. CX-007586: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Paving the Way with Propane: The AutoGas Corridor Development Program CX(s) Applied: B5.1 Date: 12/29/2011 Location(s): Mississippi Offices(s): National Energy Technology Laboratory

  8. CX-009843: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Installation of Retail Biofuel Infrastructure Supporting I-75 Green Corridor Project CX(s) Applied: A1, B5.22 Date: 01/30/2013 Location(s): Florida Offices(s): National Energy Technology Laboratory

  9. CX-008306: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Installation of Retail Biofuel Infrastructure Supporting I-75 Green Corridor Project CX(s) Applied: A1, B5.22 Date: 04/25/2012 Location(s): Georgia Offices(s): National Energy Technology Laboratory

  10. CX-008315: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Installation of Retail Biofuel Infrastructure Supporting I-75 Green Corridor Project CX(s) Applied: A1, B5.22 Date: 04/18/2012 Location(s): Georgia Offices(s): National Energy Technology Laboratory

  11. CX-009305: Categorical Exclusion Determination

    Office of Energy Efficiency and Renewable Energy (EERE)

    Long Island Smart Energy Corridor - Farmingdale Wind Turbines CX(s) Applied: B5.18 Date: 08/31/2012 Location(s): New York Offices(s): National Energy Technology Laboratory

  12. second line of defense | National Nuclear Security Administration

    National Nuclear Security Administration (NNSA)

    second line of defense

  13. EIS-0285-SA-134: Supplement Analysis | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    System Vegetation Management Program Vegetation Management for the Bandon-Rogue-Gold Beach transmission line corridor. This corridor includes the Bandon-Rogue 1 115...

  14. EC Transmission Line Materials

    SciTech Connect (OSTI)

    Bigelow, Tim S

    2012-05-01

    The purpose of this document is to identify materials acceptable for use in the US ITER Project Office (USIPO)-supplied components for the ITER Electron cyclotron Heating and Current Drive (ECH&CD) transmission lines (TL), PBS-52. The source of material property information for design analysis shall be either the applicable structural code or the ITER Material Properties Handbook. In the case of conflict, the ITER Material Properties Handbook shall take precedence. Materials selection, and use, shall follow the guidelines established in the Materials Assessment Report (MAR). Materials exposed to vacuum shall conform to the ITER Vacuum Handbook. [Ref. 2] Commercial materials shall conform to the applicable standard (e.g., ASTM, JIS, DIN) for the definition of their grade, physical, chemical and electrical properties and related testing. All materials for which a suitable certification from the supplier is not available shall be tested to determine the relevant properties, as part of the procurement. A complete traceability of all the materials including welding materials shall be provided. Halogenated materials (example: insulating materials) shall be forbidden in areas served by the detritiation systems. Exceptions must be approved by the Tritium System and Safety Section Responsible Officers.

  15. Bipolar pulse forming line

    DOE Patents [OSTI]

    Rhodes, Mark A.

    2008-10-21

    A bipolar pulse forming transmission line module for linear induction accelerators having first, second, third, fourth, and fifth planar conductors which form an interleaved stack with dielectric layers between the conductors. Each conductor has a first end, and a second end adjacent an acceleration axis. The first and second planar conductors are connected to each other at the second ends, the fourth and fifth planar conductors are connected to each other at the second ends, and the first and fifth planar conductors are connected to each other at the first ends via a shorting plate adjacent the first ends. The third planar conductor is electrically connectable to a high voltage source, and an internal switch functions to short a high voltage from the first end of the third planar conductor to the first end of the fourth planar conductor to produce a bipolar pulse at the acceleration axis with a zero net time integral. Improved access to the switch is enabled by an aperture through the shorting plate and the proximity of the aperture to the switch.

  16. NETL LINES OF DEMARCATION 09282012

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    LINES OF DEMARCATION September 28, 2012 Contact: Site Operations Division or ESS&H Division with Questions The oversight, upkeep, and segregation of NETL infrastructure components, including lines of demarcation between ORD and OIO, will be as follows: 1. Common utility headers including gas compression systems that enter or exit the site will be maintained by the Office of Institutional Operations (OIO). A line of responsibility demarcation between OIO and ORD will be established at the

  17. Emergency pipe line repair connects subsea pipe lines

    SciTech Connect (OSTI)

    Lerique, M.P.; Thiberge, P. ); Wright, N. )

    1990-11-01

    Emergency repair of any subsea line pipe must form a high-integrity, metal-to-metal seal. This paper presents a remote, diverless repair system that utilizes master flanges, a connector and a spool piece to repair line pipe in deep offshore waters.

  18. SunLine Transit Agency

    Broader source: Energy.gov [DOE]

    SunLine Transit Agency provides public transit and community services to California's Coachella Valley. The service area is more than 1,100 square miles and includes nine member cities, as well as Riverside County. Over the years, SunLine has pursued an aggressive strategy for implementing clean technologies into its fleet.

  19. The Hanford Story: River Corridor

    Broader source: Energy.gov [DOE]

    This is the seventh chapter of The Hanford Story, a multimedia presentation that provides an overview of the Hanford Site—its history, today's cleanup activities, and a glimpse into the possibilities of future uses of the 586-square-mile government site in southeast Washington State.

  20. Pulse shaping with transmission lines

    DOE Patents [OSTI]

    Wilcox, R.B.

    1985-08-15

    A method and apparatus for forming shaped voltage pulses uses passive reflection from a transmission line with nonuniform impedance. The impedance of the reflecting line varies with length in accordance with the desired pulse shape. A high voltage input pulse is transmitted to the reflecting line. A reflected pulse is produced having the desired shape and is transmitted by pulse removal means to a load. Light activated photoconductive switches made of silicon can be utilized. The pulse shaper can be used to drive a Pockels cell to produce shaped optical pulses.

  1. Pulse shaping with transmission lines

    DOE Patents [OSTI]

    Wilcox, Russell B.

    1987-01-01

    A method and apparatus for forming shaped voltage pulses uses passive reflection from a transmission line with nonuniform impedance. The impedance of the reflecting line varies with length in accordance with the desired pulse shape. A high voltage input pulse is transmitted to the reflecting line. A reflected pulse is produced having the desired shape and is transmitted by pulse removal means to a load. Light activated photoconductive switches made of silicon can be utilized. The pulse shaper can be used to drive a Pockels cell to produce shaped optical pulses.

  2. Electrical transmission line diametrical retainer

    DOE Patents [OSTI]

    Hall, David R.; Hall, Jr., H. Tracy; Pixton, David; Dahlgren, Scott; Sneddon, Cameron; Briscoe, Michael; Fox, Joe

    2004-12-14

    The invention is a mechanism for retaining an electrical transmission line. In one embodiment of the invention it is a system for retaining an electrical transmission line within down hole components. In accordance with one aspect of the invention, the system includes a plurality of downhole components, such as sections of pipe in a drill string. The system also includes a coaxial cable running between the first and second end of a drill pipe, the coaxial cable having a conductive tube and a conductive core within it. The invention allows the electrical transmission line to with stand the tension and compression of drill pipe during routine drilling cycles.

  3. SSRL Beam Lines Map | Stanford Synchrotron Radiation Lightsource

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    SSRL Beam Lines Map Beam Line by Number | Beam Line by Techniques | Photon Source Parameters

  4. Research/Evaluate Restoration of NE Oregon Streams: Effects of Livestock Exclosures (Corridor Fencing) on Riparian Vegetation, Stream Geomorphic Features and Fish Populations; Final Report 2002.

    SciTech Connect (OSTI)

    Kauffman, J. Boone

    2002-09-17

    The Pacific Northwest Electric Power Planning and Conservation Act of 1980 indicated ''The council shall properly develop and adopt a program to protect, mitigate, and enhance fish and wildlife, including related spawning grounds and habitat on the Columbia River and its tributaries.'' As a result, the Bonneville Power Administration (BPA) has spent millions of dollars on various instream projects throughout the Columbia Basin with the goal of increasing system-wide production of anadromous fisheries through a combination of habitat restoration and enhancement measures. For two decades, numerous BPA-funded projects have been initiated in the upper Columbia River Basin for the express intent of improving the aquatic habitats of anadromous salmonids. Largely missing from most of these projects has been any rigorous evaluation of project success or failure. Some field reviews of some habitat projects have been undertaken (e.g., Beschta et al. 1991, Kauffman et al. 1993) and provide an overview of major problems and opportunities associated with selected projects. However, there continues to be a lack of quantifiable information, collected in a systematic manner that could be used as the basis for scientifically assessing the effects of individual projects on riparian/aquatic habitats, functions, or processes. Recent publications (e.g., NRC 1992, ISG 1996, NRC 1996, Beschta 1997, and Kauffman et al. 1997) have identified and summarized important concepts associated with the restoration and improvement of aquatic ecosystems. While such conceptual approaches provide an important structure for those undertaking restoration efforts, there remains a paucity of basic information throughout the upper Columbia Basin on the hydrologic, geomorphic, and biologic responses that occur from various enhancement approaches. Basic data on the spatial and temporal responses of restoration approaches would provide: (1) a better understanding of project effects upon aquatic habitats and associated riparian functions; (2) a means of determining rates of aquatic habitat improvement; and (3) a basis for projecting future trends of habitat recovery. The proposed research is intended to provide an improved understanding of both the effects and effectiveness of a commonly used habitat enhancement approach in the upper Columbia River Basin. This is the exclusion of domestic livestock from streamside communities and streams via corridor fencing (exclosures). This final report is broken into three separate chapters. The first chapter covers the vegetation change associated with livestock exclusion. The second chapter focuses on the physical geomorphic changes to the streambank and channel. The final chapter covers the response of salmonids and warmwater fishes to livestock exclusion at the spatial scales of exclosures as is commonly constructed today. It is expected that this study will provide an important scientific basis, currently lacking, for understanding the ecological principles of restoration/enhancement of sustainable aquatic habitats for salmonids. Thus, the results of this work are likely to have important ramifications for habitat improvement projects within and beyond the general geographic region of northeastern Oregon.

  5. Fin-line horn antenna

    DOE Patents [OSTI]

    Reindel, John

    1990-01-01

    A fin line circuit card containing a fin line slot feeds a dipole antenna ich extends a quarterwave outside the waveguide and provides an energy beam focal point at or near the open end of the waveguide. The dipole antenna thus maintains a wide and nearly constant beamwidth, low VSWR and a circular symmetric radiation pattern for use in electronic warfare direction finding and surveillance applications.

  6. Letter from Deputy Secretary Poneman to Clean Line Energy Regarding...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Line: Comment from Ms. Schroeder Plains and Eastern Clean Line Transmission Line: Comment from Mr. Zuniga Plains and Eastern Clean Line Transmission Line: Comment from Mr. Cain...

  7. EA-1629:Southwestern Power Administration Utility Corridor and Tower Site Vegetation Management; Ozark-St. Francis National Forest, Pope and Searcy Counties, Arkansas

    Broader source: Energy.gov [DOE]

    U.S. Forest Service prepared an EA that evaluated the potential environmental impacts of amending a Southwestern Area Power Administration (SWPA) permit to allow herbicide application within SWPA transmission line rights-of-way in the Ozark-St. Francis National Forest. SWPA initially was a cooperating agency, and later ended its involvement in preparing the EA.

  8. ONE NEVADA LINE | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ONE NEVADA LINE ONE NEVADA LINE PDF icon DOE-LPO_Project-Posters_STOR-TRSM_One-Nevada-Line.pdf More Documents & Publications STEPHENTOWN SPINDLE CX-011989: Categorical Exclusion Determination CRESCENT DUNES

  9. X-ray line polarization spectroscopy of Li-like satellite line...

    Office of Scientific and Technical Information (OSTI)

    X-ray line polarization spectroscopy of Li-like satellite line spectra Citation Details In-Document Search Title: X-ray line polarization spectroscopy of Li-like satellite line ...

  10. Plains and Eastern Clean Line Transmission Line: Comment from Block Plains

    Energy Savers [EERE]

    and Eastern Clean Line: Arkansas and Oklahoma | Department of Energy from Block Plains and Eastern Clean Line: Arkansas and Oklahoma Plains and Eastern Clean Line Transmission Line: Comment from Block Plains and Eastern Clean Line: Arkansas and Oklahoma Comment submitted on updated Part 2 application. PDF icon Comment from Block Plains & Eastern Clean Line Arkansas and Oklahoma 06-08-15.pdf More Documents & Publications Plains and Eastern Clean Line Transmission Line: Comment from

  11. Plains and Eastern Clean Line Transmission Line: Comment from Dr. Contreras

    Energy Savers [EERE]

    | Department of Energy from Dr. Contreras Plains and Eastern Clean Line Transmission Line: Comment from Dr. Contreras Comment submitted on updated Part 2 application. PDF icon Comment from Dr. Contreras 6-10-15.pdf More Documents & Publications Plains and Eastern Clean Line Transmission Line: Comment from Dr. Contreras Plains and Eastern Clean Line Transmission Line: Comment from Dr. Contreras Plains and Eastern Clean Line Transmission Line: Comment from Dr. Contreras

  12. Plains and Eastern Clean Line Transmission Line: Comment from Ms. Callahan

    Energy Savers [EERE]

    | Department of Energy Ms. Callahan Plains and Eastern Clean Line Transmission Line: Comment from Ms. Callahan Comment submitted on updated Part 2 application. PDF icon Comment from Ms. Callahan 07-13-15.pdf More Documents & Publications Plains and Eastern Clean Line Transmission Line: Comment from Cynthia Blansett (COE) Plains and Eastern Clean Line Transmission Line: Comment from Dr. Contreras Plains and Eastern Clean Line Transmission Line: Comment from Simon Mahan (SWEA)

  13. Coiled transmission line pulse generators

    DOE Patents [OSTI]

    McDonald, Kenneth Fox

    2010-11-09

    Methods and apparatus are provided for fabricating and constructing solid dielectric "Coiled Transmission Line" pulse generators in radial or axial coiled geometries. The pour and cure fabrication process enables a wide variety of geometries and form factors. The volume between the conductors is filled with liquid blends of monomers, polymers, oligomers, and/or cross-linkers and dielectric powders; and then cured to form high field strength and high dielectric constant solid dielectric transmission lines that intrinsically produce ideal rectangular high voltage pulses when charged and switched into matched impedance loads. Voltage levels may be increased by Marx and/or Blumlein principles incorporating spark gap or, preferentially, solid state switches (such as optically triggered thyristors) which produce reliable, high repetition rate operation. Moreover, these Marxed pulse generators can be DC charged and do not require additional pulse forming circuitry, pulse forming lines, transformers, or an a high voltage spark gap output switch. The apparatus accommodates a wide range of voltages, impedances, pulse durations, pulse repetition rates, and duty cycles. The resulting mobile or flight platform friendly cylindrical geometric configuration is much more compact, light-weight, and robust than conventional linear geometries, or pulse generators constructed from conventional components. Installing additional circuitry may accommodate optional pulse shape improvements. The Coiled Transmission Lines can also be connected in parallel to decrease the impedance, or in series to increase the pulse length.

  14. In-line thermoelectric module

    DOE Patents [OSTI]

    Pento, Robert; Marks, James E.; Staffanson, Clifford D.

    2000-01-01

    A thermoelectric module with a plurality of electricity generating units each having a first end and a second end, the units being arranged first end to second end along an in-line axis. Each unit includes first and second elements each made of a thermoelectric material, an electrically conductive hot member arranged to heat one side of the first element, and an electrically conductive cold member arranged to cool another side of the first element and to cool one side of the second element. The hot member, the first element, the cold member and the second element are supported in a fixture, are electrically connected respectively to provide an electricity generating unit, and are arranged respectively in positions along the in-line axis. The individual components of each generating unit and the respective generating units are clamped in their in-line positions by a loading bolt at one end of the fixture and a stop wall at the other end of the fixture. The hot members may have a T-shape and the cold members an hourglass shape to facilitate heat transfer. The direction of heat transfer through the hot members may be perpendicular to the direction of heat transfer through the cold members, and both of these heat transfer directions may be perpendicular to the direction of current flow through the module.

  15. In-Line Thermoelectric Module

    SciTech Connect (OSTI)

    Pento, Robert; Marks, James E.; Staffanson, Clifford D.

    1998-07-28

    A thermoelectric module with a plurality of electricity generating units each having a first end and a second end, the units being arranged first end to second end along an-in-line axis. Each unit includes first and second elements each made of a thermoelectric material, an electrically conductive hot member arranged to heat one side of the first element, and an electrically conductive cold member arranged to cool another side of the first element and to cool one side of the second element. The hot member, the first element, the cold member and the second element are supported in a fixture, are electrically connected respectively to provide an electricity generating unit, and are arranged respectively in positions along the in-line axis. The individual components of each generating unit and the respective generating units are clamped in their in-line positions by a loading bolt at one end of the fixture and a stop wall at the other end of the fixture. The hot members may have a T-shape and the cold members an hourglass shape to facilitate heat transfer. The direction of heat transfer through the hot members may be perpendicular to the direction of heat transfer through the cold members, and both of these heat transfer directions maybe perpendicular to the direction-of current flow through the module.

  16. X-ray line polarization spectroscopy of Li-like satellite line...

    Office of Scientific and Technical Information (OSTI)

    spectroscopy of Li-like satellite line spectra Citation Details In-Document Search Title: X-ray line polarization spectroscopy of Li-like satellite line spectra We apply the ...

  17. Plains and Eastern Clean Line Transmission Line: Comment from Save The

    Energy Savers [EERE]

    Ozarks | Department of Energy Save The Ozarks Plains and Eastern Clean Line Transmission Line: Comment from Save The Ozarks Comment submitted on updated Part 2 application. PDF icon Comment by Save the Ozarks 07-13-15.pdf More Documents & Publications Plains & Eastern Clean Line Transmission Line - Part 2 Application Plains & Eastern Clean Line Project Proposal for New or Upgraded Transmission Line Projects Under Section 1222 of the Energy Policy Act of 2005 Plains and Eastern

  18. CXD 4601, Line Yard Fence Project (4601)

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Line Yard Fence Project (4601) Y-12 Site Office Oak Ridge, Anderson County, Tennessee The proposed action is to install fencing around the Old Line Yard to provide protected...

  19. EIS-0285-SA-84: Supplement Analysis | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    No. 2 500kV and the Arlington-Bellingham 230kV transmission line corridors which run parallel to the subject transmission line. Corridor width varies from 140 to 825 feet....

  20. O.A.R. 734-055 - Pole Lines, Buried Cables, Pipe lines, Signs...

    Open Energy Info (EERE)

    rules outline the requirements for location, installation, construction, maintenance and use of pole lines, buried cables, pipe lines, signs miscellaneous operations...

  1. Capillary electrophoresis-fluorescence line narrowing system (CE-FLNS) for on-line structural characterization

    DOE Patents [OSTI]

    Jankowiak, R.J.; Small, G.J.; Shields, P.A.

    1999-04-27

    Capillary electrophoresis (CE) is interfaced with low temperature fluorescence line-narrowing (FLN) spectroscopy for on-line structural characterization of separated molecular analytes. 21 figs.

  2. Capillary electrophoresis-fluorescence line narrowing system (CE-FLNS) for on-line structural characterization

    DOE Patents [OSTI]

    Jankowiak, Ryszard J.; Small, Gerald J.; Shields, Peter A.

    1999-04-27

    Capillary electrophoresis (CE) is interfaced with low temperature fluorescence line-narrowing (FLN) spectroscopy for on-line structural characterization of separated molecular analytes.

  3. Superconducting transmission line particle detector

    DOE Patents [OSTI]

    Gray, K.E.

    1988-07-28

    A microvertex particle detector for use in a high energy physic collider including a plurality of parallel superconducting thin film strips separated from a superconducting ground plane by an insulating layer to form a plurality of superconducting waveguides. The microvertex particle detector indicates passage of a charged subatomic particle by measuring a voltage pulse measured across a superconducting waveguide caused by the transition of the superconducting thin film strip from a superconducting to a non- superconducting state in response to the passage of a charged particle. A plurality of superconducting thin film strips in two orthogonal planes plus the slow electromagnetic wave propagating in a superconducting transmission line are used to resolve N/sup 2/ ambiguity of charged particle events. 6 figs.

  4. Unsplit bipolar pulse forming line

    DOE Patents [OSTI]

    Rhodes, Mark A.

    2011-05-24

    A bipolar pulse forming transmission line module and system for linear induction accelerators having first, second, third, and fourth planar conductors which form a sequentially arranged interleaved stack having opposing first and second ends, with dielectric layers between the conductors. The first and second planar conductors are connected to each other at the first end, and the first and fourth planar conductors are connected to each other at the second end via a shorting plate. The third planar conductor is electrically connectable to a high voltage source, and an internal switch functions to short at the first end a high voltage from the third planar conductor to the fourth planar conductor to produce a bipolar pulse at the acceleration axis with a zero net time integral. Improved access to the switch is enabled by an aperture through the shorting plate and the proximity of the aperture to the switch.

  5. Superconducting transmission line particle detector

    DOE Patents [OSTI]

    Gray, Kenneth E.

    1989-01-01

    A microvertex particle detector for use in a high energy physic collider including a plurality of parallel superconducting thin film strips separated from a superconducting ground plane by an insulating layer to form a plurality of superconducting waveguides. The microvertex particle detector indicates passage of a charged subatomic particle by measuring a voltage pulse measured across a superconducting waveguide caused by the transition of the superconducting thin film strip from a superconducting to a non-superconducting state in response to the passage of a charged particle. A plurality of superconducting thin film strips in two orthogonal planes plus the slow electromagnetic wave propogating in a superconducting transmission line are used to resolve N.sup.2 ambiguity of charged particle events.

  6. Magnetically insulated transmission line oscillator

    DOE Patents [OSTI]

    Bacon, Larry D.; Ballard, William P.; Clark, M. Collins; Marder, Barry M.

    1988-01-01

    A magnetically insulated transmission line oscillator employs self-generated magnetic fields to generate microwave energy. An anode of the oscillator includes slow-wave structures which are formed of a plurality of thin conductive vanes defining cavities therebetween, and a gap is formed between the anode and a cathode of the oscillator. In response to a pulsed voltage applied to the anode and cathode, self-generated magnetic fields arfe produced in a cross-field orientation with respect to the orientation of the electric field between the anode and the cathode. The cross-field magnetic fields insulate the flow of electrons in the gap and confine the flow of electrons within the gap.

  7. Magnetically insulated transmission line oscillator

    DOE Patents [OSTI]

    Bacon, L.D.; Ballard, W.P.; Clark, M.C.; Marder, B.M.

    1987-05-19

    A magnetically insulated transmission line oscillator employs self-generated magnetic fields to generate microwave energy. An anode of the oscillator includes slow-wave structures which are formed of a plurality of thin conductive vanes defining cavities therebetween, and a gap is formed between the anode and a cathode of the oscillator. In response to a pulsed voltage applied to the anode and cathode, self-generated magnetic fields are produced in a cross-field orientation with respect to the orientation of the electric field between the anode and the cathode. The cross-field magnetic fields insulate the flow of electrons in the gap and confine the flow of electrons within the gap. 11 figs.

  8. Transmission SEAB Presentation

    Broader source: Energy.gov (indexed) [DOE]

    Market Power 368 Corridors ... evaluation of transmission applications Increase efficiency in administration ... MATL Project New t-line Financier Minority ...

  9. CX-012647: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Kalispell District 2014 Transmission Line Maintenance - Multiple Lines CX(s) Applied: B1.3Date: 41862 Location(s): MontanaOffices(s): Bonneville Power Administration

  10. CX-012645: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Wenatchee District 2014 Transmission Line Maintenance - Multiple Lines CX(s) Applied: B1.3Date: 41862 Location(s): WashingtonOffices(s): Bonneville Power Administration

  11. NSLS-II Transport Line Progress

    SciTech Connect (OSTI)

    Fliller R. P.; Wahl, W.; Anderson, A.; Benish, B.; DeBoer, W.; Ganetis, G.; Heese, R.; Hseuh, H.-C.; Hu, J.-P.; Johanson, M.P.; Kosciuk, B.N.; Padrazo, D.; Roy, K.; Shaftan, T.; Singh, O.; Tuozzolo, J.; Wang, G.

    2012-05-20

    The National Synchrotron Light Source II (NSLS-II) is a state-of-the-art 3-GeV third generation light source currently under construction at Brookhaven National Laboratory. The NSLS-II injection system consists of a 200 MeV linac, a 3-GeV booster synchrotron and associated transfer lines. The first part of the Linac to Booster Transport (LBT) line has been installed for linac commissioning. This part includes all components necessary to commission the NSLS-II linac. The second part of this transport line is undergoing installation. Initial results of hardware commissioning will be discussed. The Booster to Storage Ring (BSR) transport line underwent a design review. The first part of the BSR transport line, consisting of all components necessary to commission the booster will be installed in 2012 for booster commissioning. We report on the final design of the BSR line along with the plan to commission the booster.

  12. Single transmission line data acquisition system

    DOE Patents [OSTI]

    Fasching, George E.

    1984-01-01

    A single transmission line interrogated multiple channel data acquisition system is provided in which a plurality of remote station/sensors monitor specific process variables and transmit measurement values over the single transmission line to a master station when addressed by the master station. Power for all remote stations (up to 980) is provided by driving the line with constant voltage supplied from the master station and automatically maintained independent of the number of remote stations directly connected to the line. The transmission line can be an RG-62 coaxial cable with lengths up to about 10,000 feet with branches up to 500 feet. The remote stations can be attached randomly along the line. The remote stations can be scanned at rates up to 980 channels/second.

  13. Microsoft Word - STO Comments on Clean Line Application under...

    Broader source: Energy.gov (indexed) [DOE]

    Clean Line Transmission Line Project ("Clean Line Project" or "Project"). ... "objective of integrating more renewable resources onto the grid," 1 However, after reviewing Section ...

  14. Strengthening Line Management Oversight and Federal Monitoring...

    Office of Environmental Management (EM)

    5 iii Acronyms DOE U.S. Department of Energy DSA Documented Safety Analysis HA Hazard Analysis LOI Line of Inquiry SAC Specific Administrative Control SRP Standard...

  15. Michael Skelly President Clean Line Energy Partners

    Broader source: Energy.gov (indexed) [DOE]

    on nearly 200 U.S. Power & Utility engagements ... very familiar with Clean Line, its transmission projects and the ... Plan for Energy Efficiency; actual cost for ...

  16. Detonator comprising a nonlinear transmission line

    DOE Patents [OSTI]

    Elizondo-Decanini, Juan M

    2014-12-30

    Detonators are described herein. In a general embodiment, the detonator includes a nonlinear transmission line that has a variable capacitance. Capacitance of the nonlinear transmission line is a function of voltage on the nonlinear transmission line. The nonlinear transmission line receives a voltage pulse from a voltage source and compresses the voltage pulse to generate a trigger signal. Compressing the voltage pulse includes increasing amplitude of the voltage pulse and decreasing length of the voltage pulse in time. An igniter receives the trigger signal and detonates an explosive responsive to receipt of the trigger signal.

  17. DOE Sustainability Reporting Open Line Help Call

    Broader source: Energy.gov [DOE]

    The Sustainability Performance Office (SPO) sponsors open line help calls to assist DOE sites and national laboratories with the annual sustainability reporting process. Representatives from the...

  18. Increasing the Capacity of Existing Power Lines

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... Improved line capacity forecasting The research team continues to validate and refine its weather simulation model to run faster and generate increasingly more accurate results for ...

  19. Northern Pass Transmission Line Project Environmental Impact...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Northern Pass Transmission Line Project Environmental Impact Statement: Announcement of Change in Public Meeting Location: Federal Register Notice Volume 78, No. 181 - September ...

  20. Supervisory Transmission Lines and Substation Maintenance Manager

    Broader source: Energy.gov [DOE]

    (See Frequently Asked Questions for more information). Where would I be working? Western Area Power Administration Desert Southwest Region Transmission Lines and Substation Maintenance (G5200) 615...

  1. X-ray line polarization spectroscopy of Li-like satellite line spectra

    Office of Scientific and Technical Information (OSTI)

    (Journal Article) | SciTech Connect Journal Article: X-ray line polarization spectroscopy of Li-like satellite line spectra Citation Details In-Document Search Title: X-ray line polarization spectroscopy of Li-like satellite line spectra We apply the magnetic-sublevel atomic kinetics model POLAR to the calculation of polarization properties of satellite lines in Li-like Si driven by subpicosecond-duration laser pulses. We identify spectral lines whose polarization can serve as a marker of

  2. Soliton production with nonlinear homogeneous lines

    SciTech Connect (OSTI)

    Elizondo-Decanini, Juan M.; Coleman, Phillip D.; Moorman, Matthew W.; Petney, Sharon Joy Victor; Dudley, Evan C.; Youngman, Kevin; Penner, Tim Dwight; Fang, Lu; Myers, Katherine M.

    2015-11-24

    Low- and high-voltage Soliton waves were produced and used to demonstrate collision and compression using diode-based nonlinear transmission lines. Experiments demonstrate soliton addition and compression using homogeneous nonlinear lines. We built the nonlinear lines using commercially available diodes. These diodes are chosen after their capacitance versus voltage dependence is used in a model and the line design characteristics are calculated and simulated. Nonlinear ceramic capacitors are then used to demonstrate high-voltage pulse amplification and compression. The line is designed such that a simple capacitor discharge, input signal, develops soliton trains in as few as 12 stages. We also demonstrated output voltages in excess of 40 kV using Y5V-based commercial capacitors. The results show some key features that determine efficient production of trains of solitons in the kilovolt range.

  3. Soliton production with nonlinear homogeneous lines

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Elizondo-Decanini, Juan M.; Coleman, Phillip D.; Moorman, Matthew W.; Petney, Sharon Joy Victor; Dudley, Evan C.; Youngman, Kevin; Penner, Tim Dwight; Fang, Lu; Myers, Katherine M.

    2015-11-24

    Low- and high-voltage Soliton waves were produced and used to demonstrate collision and compression using diode-based nonlinear transmission lines. Experiments demonstrate soliton addition and compression using homogeneous nonlinear lines. We built the nonlinear lines using commercially available diodes. These diodes are chosen after their capacitance versus voltage dependence is used in a model and the line design characteristics are calculated and simulated. Nonlinear ceramic capacitors are then used to demonstrate high-voltage pulse amplification and compression. The line is designed such that a simple capacitor discharge, input signal, develops soliton trains in as few as 12 stages. We also demonstrated outputmore » voltages in excess of 40 kV using Y5V-based commercial capacitors. The results show some key features that determine efficient production of trains of solitons in the kilovolt range.« less

  4. Computing Criticality of Lines in Power Systems

    SciTech Connect (OSTI)

    Pinar, Ali; Reichert, Adam; Lesieutre, Bernard

    2006-10-13

    We propose a computationally efficient method based onnonlinear optimization to identify critical lines, failure of which cancause severe blackouts. Our method computes criticality measure for alllines at a time, as opposed to detecting a single vulnerability,providing a global view of the system. This information on criticality oflines can be used to identify multiple contingencies by selectivelyexploring multiple combinations of broken lines. The effectiveness of ourmethod is demonstrated on the IEEE 30 and 118 bus systems, where we canvery quickly detect the most critical lines in the system and identifysevere multiple contingencies.

  5. Temperatures in the blast furnace refractory lining

    SciTech Connect (OSTI)

    Hebel, R.; Streuber, C.; Steiger, R.; Jeschar, R.

    1995-12-01

    The campaign life duration of a blast furnace is mainly determined by the condition of the refractory lining in heavy-duty zones such as the hearth, bosh, belly and lower stack. To achieve a desired lifetime, the temperature of the lining in these areas thereby proved to be the decisive controllable parameter. Low operating temperatures result in prolonged service life and are attained through high cooling efficiency. Besides the refractory grade chosen, the wear profile is mainly determined by the type of cooling system applied and the cooling intensity. Therefore, an appropriate compromise between long service life and energy losses has to be found in each case. In order to predict the service life of a lining it is important to know the wear condition at all times during the campaign. The paper describes the approaches the authors have made so far on European blast furnaces, on a theoretical and practical basis, on how to analyze the lining wear.

  6. Electrician - Foreman II (Transmission Lines & Substations) ...

    Broader source: Energy.gov (indexed) [DOE]

    Region Transmission Lines and Substation Maintenance (G5200) 615 S. 43rd Avenue Phoenix, AZ 85009 Duty Location is Page, AZ Find out more about living conditions at this...

  7. Ames Lab 101: Next Generation Power Lines

    ScienceCinema (OSTI)

    Russell, Alan

    2012-08-29

    Ames Laboratory scientist Alan Russell discusses the need to develop new power lines that are stronger and more conductive as a way to address the problem of the nation's aging and inadequate power grid.

  8. On-line chemical composition analyzer development

    SciTech Connect (OSTI)

    Garrison, A.A.

    1993-01-01

    This report relates to the development of an on-line Raman analyzer for control of a distillation column. It is divided into: program issues, experimental control system evaluation, energy savings analysis, and reliability analysis. (DLC)

  9. factsheet - trees and power lines - July 2008

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Trees and power lines July 2008 This summer, BPA maintenance crews are inspecting and clearing high-growing vegetation from all 8,500- miles (15,000 circuit miles) of our...

  10. Electrical Transmission Line Diametrical Retention Mechanism

    DOE Patents [OSTI]

    Hall, David R.; Hall, Jr., H. Tracy; Pixton, David; Dahlgren, Scott; Sneddon, Cameron; Briscoe, Michael; Fox, Joe

    2006-01-03

    The invention is a mechanism for retaining an electrical transmission line. In one embodiment of the invention it is a system for retaining an electrical transmission line within downhole components. The invention allows a transmission line to be attached to the internal diameter of drilling components that have a substantially uniform drilling diameter. In accordance with one aspect of the invention, the system includes a plurality of downhole components, such as sections of pipe in a drill string, drill collars, heavy weight drill pipe, and jars. The system also includes a coaxial cable running between the first and second end of a drill pipe, the coaxial cable having a conductive tube and a conductive core within it. The invention allows the electrical transmission line to withstand the tension and compression of drill pipe during routine drilling cycles.

  11. DNA Assembly Line for Nano-Construction

    ScienceCinema (OSTI)

    Oleg Gang

    2010-01-08

    Building on the idea of using DNA to link up nanoparticles scientists at Brookhaven National Lab have designed a molecular assembly line for high-precision nano-construction. Nanofabrication is essential for exploiting the unique properties of nanoparticl

  12. Line Environment, Safety and Health Oversight

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-06-26

    Sets forth the Department's expectations line management environment, safety and health (ES&H) oversight and for the use of contractor self-assessment programs as the cornerstone for this oversight. Canceled by DOE O 226.1.

  13. Design of the ILC RTML Extraction Lines

    SciTech Connect (OSTI)

    Seletskiy, S.; Tenenbaum, P.; Walz, D.; Solyak, N.; /Fermilab

    2011-10-17

    The ILC [1] Damping Ring to the Main Linac beamline (RTML) contains three extraction lines (EL). Each EL can be used both for an emergency abort dumping of the beam and tune-up continual train-by-train extraction. Two of the extraction lines are located downstream of the first and second stages of the RTML bunch compressor, and must accept both compressed and uncompressed beam with energy spreads of 2.5% and 0.15%, respectively. In this paper we report on an optics design that allowed minimizing the length of the extraction lines while offsetting the beam dumps from the main line by the distance required for acceptable radiation levels in the service tunnel. The proposed extraction lines can accommodate beams with different energy spreads while at the same time providing the beam size acceptable for the aluminum dump window. The RTML incorporates three extraction lines, which can be used for either an emergency beam abort or for a train-by-train extraction. The first EL is located downstream of the Damping Ring extraction arc. The other two extraction lines are located downstream of each stage of the two-stage bunch compressor. The first extraction line (EL1) receives 5GeV beam with an 0.15% energy spread. The extraction line located downstream of the first stage of bunch compressor (ELBC1) receives both compressed and uncompressed beam, and therefore must accept beam with both 5 and 4.88GeV energy, and 0.15% and 2.5% energy spread, respectively. The extraction line located after the second stage of the bunch compressor (ELBC2) receives 15GeV beam with either 0.15 or 1.8% energy spread. Each of the three extraction lines is equipped with the 220kW aluminum ball dump, which corresponds to the power of the continuously dumped beam with 5GeV energy, i.e., the beam trains must be delivered to the ELBC2 dump at reduced repetition rate.

  14. LINE Commission Visits Idaho National Laboratory

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    LINE Commission Visits Idaho National Laboratory Members of the state of Idaho�s Leadership in Nuclear Energy (LINE) Commission recently visited the Idaho National Laboratory and related DOE-Idaho cleanup facilities. These photos show commission members at the Materials and Fuels Complex, where Steve Marschman from INL talks to the commission members, and the Advanced Mixed Waste Treatment Facility. At the AMWTP, members saw the supercompactor as Facility Manager Jeremy Hampton explained how

  15. River Corridor Closure Contract Section J, Attachment...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    2 Contract No. DE-AC06-05RL14655 A000 1 ATTACHMENT J-12 GOVERNMENT-FURNISHED SERVICES AND INFORMATION (GFSI) GFSI Item Scope Description GFSI Description C.4 Hanford Site...

  16. DOE Affirms National Interest Electric Transmission Corridor...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    data analysis conducted in its 2006 National Interest Electric Transmission study, ... DOE also highlighted that its approach to defining the geographic boundaries of the ...

  17. River Corridor Closure Contract Section J, Attachment...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    use (i.e., use outside the employees regular schedule) of government property (such as computers, telephones, copiers, fax machines or other office equipment) or commercially...

  18. River Corridor Closure Contract Section J, Attachment...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    the Government and Washington Closure LLC (Contractor), the undersigned, Washington Group International, Inc. (Guarantor), a corporation incorporated in the State of Delaware with...

  19. Alternative Fuels Data Center: Pennsylvania's Ethanol Corridor...

    Alternative Fuels and Advanced Vehicles Data Center [Office of Energy Efficiency and Renewable Energy (EERE)]

    A few years ago, this fuel was only known in the Midwest. In the interest of our national ... "What a fantastic day for Pennsylvania," said AMERIgreen's Seth Obetz "A few years ago, ...

  20. River Corridor Closure Project Partnering Performance Agreement

    Office of Environmental Management (EM)

  1. BPA releases I-5 Corridor Reinforcement Project

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    cost or highest-cost alternative. However, the preferred alternative avoids many small, rural parcels of private land by crossing significant lengths of land held by large public...

  2. CX-008818: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Utility Corridor Extension CX(s) Applied: B4.7, B4.11, B5.2, B5.5 Date: 06/13/2012 Location(s): Pennsylvania Offices(s): Naval Nuclear Propulsion Program, Bettis Site

  3. CX-011175: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Access Road Maintenance on the Chehalis-Centralia Number 1, Chehalis-Covington Number 1, Paul-Allston Number 2, and Paul-Napavine Number 1 Transmission Corridors CX(s) Applied: B1.3 Date: 09/13/2013 Location(s): Washington Offices(s): Bonneville Power Administration

  4. Load-resistant coaxial transmission line

    DOE Patents [OSTI]

    Hall, David R.; Fox, Joe

    2006-01-03

    A transmission line for downhole tools that make up all or part of a tool string for drilling and production of oil, gas, and geothermal wells that can withstand the dynamic gravitational forces and other accelerations associated with downhole excavations. The transmission line has a metal tube, or outer conductor, that houses a coaxial wire inner conductor. A non-metallic dielectric material is interposed between the inner and outer conductors. The outer and inner conductors and the dielectric are sufficiently compressed together so that independent motion between them is abated. Compression of the components of the transmission line may be achieved by drawing the transmission through one or more dies in order to draw down the outer conductor onto the dielectric, or by expanding the inner conductor against the dielectric using a mandrel or hydraulic pressure. Non-metallic bead segments may be used in aid of the compression necessary to resist the dynamic forces and accelerations of drilling.

  5. Dynamic Line Rating: Research and Policy Evaluation

    SciTech Connect (OSTI)

    Jake P. Gentle; Kurt S. Myers; Michael R. West

    2014-07-01

    Dynamic Line Rating (DLR) is a smart grid technology that allows the rating of electrical conductors to be increased based on local weather conditions. Overhead lines are conventionally given a conservative rating based on worst case scenarios. We demonstrate that observing the conditions in real time leads to additional capacity and safer operation. This paper provides a report of a pioneering scheme in the United States of America in which DLR has been applied. Thereby, we demonstrate that observing the local weather conditions in real time leads to additional capacity and safer operation. Secondly, we discuss limitations involved. In doing so, we arrive at novel insights which will inform and improve future DLR projects. Third, we provide a policy background and discussion to clarify the technology’s potential and identifies barriers to the imminent adoption of dynamic line rating systems. We provide suggestions for regulatory bodies about possible improvements in policy to encourage adoption of this beneficial technology.

  6. EC Transmission Line Risk Identification and Analysis

    SciTech Connect (OSTI)

    Bigelow, Tim S

    2012-04-01

    The purpose of this document is to assist in evaluating and planning for the cost, schedule, and technical project risks associated with the delivery and operation of the EC (Electron cyclotron) transmission line system. In general, the major risks that are anticipated to be encountered during the project delivery phase associated with the implementation of the Procurement Arrangement for the EC transmission line system are associated with: (1) Undefined or changing requirements (e.g., functional or regulatory requirements) (2) Underperformance of prototype, first unit, or production components during testing (3) Unavailability of qualified vendors for critical components Technical risks associated with the design and operation of the system are also identified.

  7. 1 and 2-Dimensional Line Transfer Package

    Energy Science and Technology Software Center (OSTI)

    1990-07-01

    LXF1D is a one dimensional steady-state line transfer package designed to handle: overlapping and or interacting lines, planar, cylindrical, spherical (and special) geometries, doppler shifts, complete redistribution (CRD), partial redistribution (PRD). PRD requires the use of REDIST or some other package to produce emission profiles. LXF2D is a two dimensional version of LXF1D for xy and rz geometries. Both LXF1D and LXF2D are designed to be added to existing non-local thermodynamic equilibrium (NLTE) codes withmore » a minimum of effort.« less

  8. Botas line repaired ahead of schedule

    SciTech Connect (OSTI)

    Not Available

    1991-11-01

    This paper reports on damaged sections of Botas' dual 30-in. gas line carrying USSR gas across the Marmara Sea to Turkey that were replaced 30 days ahead of contract schedule. Tefken Construction and Installation Co., Inc., Istanbul, working under a $4-million contract, replaced two sections on one of the dual lines near Ambarli, Turkey, within a two-month period. The offshore system stretches 33-mi under the Marmara Sea with some pipe laid at 262-ft maximum water depths. The scope of the project was to replace a 426-ft offshore approach to the northern shoreline and a 984-ft onshore section, which were damaged by a submarine landslide.

  9. Plains & Eastern Clean Line Transmission Line- Part 2 Application: Comments Received on the Updated Application

    Broader source: Energy.gov [DOE]

    In December 2014, DOE requested additional information from Clean Line Energy Partners, LLC to supplement and update its original Plains and Eastern Clean Line application. The updated Part 2 application and other documentation were available for a public comment period that closed on July 13, 2015. Comments were posted as they were received.

  10. Sandia Energy - Experts Call for Triple Bottom Line Approach...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Experts Call for Triple Bottom Line Approach to National Energy Policy Home Energy News News & Events Mission VisionMission Experts Call for Triple Bottom Line Approach to...

  11. Changes to the Transfer Line Collimation System for the High...

    Office of Scientific and Technical Information (OSTI)

    The transfer line optics will have to be adjusted for the new collimator locations and ... with its implications on transfer line optics and powering, maintainability, protection ...

  12. PVM Lines and Services LLC aka PVML Photovoltaics | Open Energy...

    Open Energy Info (EERE)

    PVM Lines and Services LLC aka PVML Photovoltaics Jump to: navigation, search Name: PVM Lines and Services LLC (aka PVML Photovoltaics) Place: Princeton, New Jersey Zip: 8540...

  13. Insulate Steam Distribution and Condensate Return Lines | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Insulate Steam Distribution and Condensate Return Lines This tip sheet on insulating steam ... STEAM TIP SHEET 2 PDF icon Insulate Steam Distribution and Condensate Return Lines ...

  14. Self-Aligning Mirror Mechanism for Transmission Line Offset Correction...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Self-Aligning Mirror Mechanism for Transmission Line Offset Correction The Self-Aligning Mirror Mechanism for Transmission Line Offset Correction is a self-aligning mechanism which...

  15. Development of aerogel-lined targets for inertial confinement...

    Office of Scientific and Technical Information (OSTI)

    ThesisDissertation: Development of aerogel-lined targets for inertial confinement fusion experiments Citation Details In-Document Search Title: Development of aerogel-lined ...

  16. EA-1967: Hills Creek-Lookout Point Transmission Line Rebuild...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    967: Hills Creek-Lookout Point Transmission Line Rebuild, Lane County, Oregon EA-1967: Hills Creek-Lookout Point Transmission Line Rebuild, Lane County, Oregon Summary Bonneville ...

  17. EA-1981: Bonneville-Hood River Transmission Line Rebuild, Multnomah...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    81: Bonneville-Hood River Transmission Line Rebuild, Multnomah and Hood River Counties, Oregon EA-1981: Bonneville-Hood River Transmission Line Rebuild, Multnomah and Hood River ...

  18. EA-1961: Kalispell-Kerr Transmission Line Rebuild Project, Kalispell...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    1: Kalispell-Kerr Transmission Line Rebuild Project, Kalispell and Polson, Montana EA-1961: Kalispell-Kerr Transmission Line Rebuild Project, Kalispell and Polson, Montana SUMMARY ...

  19. Atomic line emission analyzer for hydrogen isotopes (Patent)...

    Office of Scientific and Technical Information (OSTI)

    Atomic line emission analyzer for hydrogen isotopes Title: Atomic line emission analyzer for hydrogen isotopes Apparatus for isotopic analysis of hydrogen comprises a low pressure ...

  20. Strengthening the Front Lines: Sales Training and Continuing...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    the Front Lines: Sales Training and Continuing Education for Contractors Strengthening the Front Lines: Sales Training and Continuing Education for Contractors Better Buildings ...

  1. Inductive gas line for pulsed lasers (Patent) | DOEPatents

    Office of Scientific and Technical Information (OSTI)

    through the inlet gas feed line. A ferrite core extends through the coil to increase the ... laser; inlet; gas; feed; line; ferrite; core; extends; coil; increase; inductance; ...

  2. Arizona Transmission Line Siting Committee | Open Energy Information

    Open Energy Info (EERE)

    Line Siting Committee Jump to: navigation, search Name: Arizona Transmission Line Siting Committee Abbreviation: TLSC Address: 1200 West Washington Street Place: Phoenix, Arizona...

  3. Independent Oversight Evaluation of Line Self-Assessments of...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Evaluation of Line Self-Assessments of Safety Conscious Work Environment - February 2014 Independent Oversight Evaluation of Line Self-Assessments of Safety Conscious Work...

  4. Salt Waste Processing Facility, Line Management Review Board...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Line Management Review Board Charter Salt Waste Processing Facility, Line Management ... processes and associated deliverables for the Salt Waste Processing Facility (SWPF). ...

  5. In-line beam current monitor

    DOE Patents [OSTI]

    Ekdahl, C.A. Jr.; Frost, C.A.

    1984-11-13

    An intense relativistic electron beam current monitor for a gas neutralized beam transport line includes a first foil for conducting plasma current to the wall where it is measured as it traverses an inductive loop formed by a cavity in the wall. An insulator foil separates the first foil from a second conducting foil which returns the current to the plasma environment.

  6. In-line beam current monitor

    DOE Patents [OSTI]

    Ekdahl, Jr., Carl A.; Frost, Charles A.

    1986-01-01

    An intense relativistic electron beam current monitor for a gas neutralized beam transport line includes a first foil for conducting plasma current to the wall where it is measured as it traverses an inductive loop formed by a cavity in the wall. An insulator foil separates the first foil from a second conducting foil which returns the current to the plasma environment.

  7. DOE Sustainability Reporting Open Line Help Call

    Broader source: Energy.gov [DOE]

    The Sustainability Performance Office (SPO) sponsors open line help calls to assist DOE sites and national laboratories with the annual sustainability reporting process. Representatives from the SPO will be available on the call to answer specific questions with respect to Site Sustainability Plans (SSP) and the Consolidated Energy Data Report (CEDR).

  8. High temperature lined conduits, elbows and tees

    DOE Patents [OSTI]

    De Feo, Angelo (Passaic, NJ); Drewniany, Edward (Bergen, NJ)

    1982-01-01

    A high temperature lined conduit comprising, a liner, a flexible insulating refractory blanket around and in contact with the liner, a pipe member around the blanket and spaced therefrom, and castable rigid refractory material between the pipe member and the blanket. Anchors are connected to the inside diameter of the pipe and extend into the castable material. The liner includes male and female slip joint ends for permitting thermal expansion of the liner with respect to the castable material and the pipe member. Elbows and tees of the lined conduit comprise an elbow liner wrapped with insulating refractory blanket material around which is disposed a spaced elbow pipe member with castable refractory material between the blanket material and the elbow pipe member. A reinforcing band is connected to the elbow liner at an intermediate location thereon from which extend a plurality of hollow tubes or pins which extend into the castable material to anchor the lined elbow and permit thermal expansion. A method of fabricating the high temperature lined conduit, elbows and tees is also disclosed which utilizes a polyethylene layer over the refractory blanket after it has been compressed to maintain the refractory blanket in a compressed condition until the castable material is in place. Hot gases are then directed through the interior of the liner for evaporating the polyethylene and setting the castable material which permits the compressed blanket to come into close contact with the castable material.

  9. CX-008144: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Planned Repair of Flow Lines CX(s) Applied: B5.4 Date: 08/09/2011 Location(s): Wyoming Offices(s): RMOTC

  10. Categorical Exclusion Determinations: B1.24 | Department of Energy

    Office of Environmental Management (EM)

    Offices(s): Bonneville Power Administration October 23, ... Grizzly Captain Jack Transmission Line Access Road ... Acquisition of Access Road Easements CX(s) Applied: B1.24 ...

  11. CX-012791: Categorical Exclusion Determination

    Office of Energy Efficiency and Renewable Energy (EERE)

    Grizzly Captain Jack Transmission Line Access Road Acquisition CX(s) Applied: B1.24Date: 41935 Location(s): OregonOffices(s): Bonneville Power Administration

  12. CX-010091: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Power Line Configuration 2013-1 CX(s) Applied: B4.13 Date: 04/15/2012 Location(s): Idaho Offices(s): Nuclear Energy

  13. CX-010398: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Power Line Configuration CX(s) Applied: B4.13 Date: 04/25/2013 Location(s): Idaho Offices(s): Idaho Operations Office

  14. CX-010727: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Dayton Tap Line Retirement CX(s) Applied: B4.10 Date: 08/13/2013 Location(s): Washington Offices(s): Bonneville Power Administration

  15. CX-010341: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Chandler Tap Line Reconductoring CX(s) Applied: B4.6 Date: 05/17/2013 Location(s): Washington Offices(s): Bonneville Power Administration

  16. CX-012587: Categorical Exclusion Determination

    Office of Energy Efficiency and Renewable Energy (EERE)

    HB-Line Security Upgrades CX(s) Applied: B1.3Date: 41835 Location(s): South CarolinaOffices(s): Savannah River Operations Office

  17. CX-011626: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Line Yard Fence Project CX(s) Applied: B1.11 Date: 06/05/2013 Location(s): Tennessee Offices(s): Y-12 Site Office

  18. CX-012795: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    North Bonneville Substation 23- Kilovolt Line Retermination CX(s) Applied: B4.11Date: 41926 Location(s): WashingtonOffices(s): Bonneville Power Administration

  19. CX-005846: Categorical Exclusion Determination | Department of...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    CX-005846: Categorical Exclusion Determination Wood Pole Replacement and Minor Access Road Maintenance Along Various Transmission Line Rights-Of-Way in the Wenatchee District CX(s) ...

  20. CX-012637: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    LURR 20140521 - David King - Sewer Line Installation CX(s) Applied: B4.9Date: 41876 Location(s): OregonOffices(s): Bonneville Power Administration

  1. CX-012371: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Hawkins-Alvey Line Impairment CX(s) Applied: B1.3 Date: 05/08/2014 Location(s): Oregon Offices(s): Bonneville Power Administration

  2. In-line real time air monitor

    DOE Patents [OSTI]

    Wise, Marcus B.; Thompson, Cyril V.

    1998-01-01

    An in-line gas monitor capable of accurate gas composition analysis in a continuous real time manner even under strong applied vacuum conditions operates by mixing an air sample with helium forming a sample gas in two complementary sample loops embedded in a manifold which includes two pairs of 3-way solenoid valves. The sample gas is then analyzed in an ion trap mass spectrometer on a continuous basis. Two valve drivers actuate the two pairs of 3-way valves in a reciprocating fashion, so that there is always flow through the in-line gas monitor via one or the other of the sample loops. The duty cycle for the two pairs of 3-way valves is varied by tuning the two valve drivers to a duty cycle typically between 0.2 to 0.7 seconds.

  3. Line-of-sight deposition method

    DOE Patents [OSTI]

    Patten, James W.; McClanahan, Edwin D.; Bayne, Michael A.

    1981-01-01

    A line-of-sight method of depositing a film having substantially 100% of theoretical density on a substrate. A pressure vessel contains a target source having a surface thereof capable of emitting particles therefrom and a substrate with the source surface and the substrate surface positioned such that the source surface is substantially parallel to the direction of the particles impinging upon the substrate surface, the distance between the most remote portion of the substrate surface receiving the particles and the source surface emitting the particles in a direction parallel to the substrate surface being relatively small. The pressure in the vessel is maintained less than about 5 microns to prevent scattering and permit line-of-sight deposition. By this method the angles of incidence of the particles impinging upon the substrate surface are in the range of from about 45.degree. to 90.degree. even when the target surface area is greatly expanded to increase the deposition rate.

  4. Line-of-sight deposition method

    DOE Patents [OSTI]

    Patten, J.W.; McClanahan, E.D.; Bayne, M.A.

    1980-04-16

    A line-of-sight method of depositing a film having substantially 100% of theoretical density on a substrate. A pressure vessel contains a target source having a surface thereof capable of emitting particles therefrom and a substrate with the source surface and the substrate surface positioned such that the source surface is substantially parallel to the direction of the particles impinging upon the substrate surface, the distance between the most remote portion of the substrate surface receiving the particles and the source surface emitting the particles in a direction parallel to the substrate surface being relatively small. The pressure in the vessel is maintained less than about 5 microns to prevent scattering and permit line-of-sight deposition. By this method the angles of incidence of the particles impinging upon the substrate surface are in the range of from about 45/sup 0/ to 90/sup 0/ even when the target surface area is greatly expanded to increase the deposition rate.

  5. Boron-10 Lined Proportional Counter Model Validation

    SciTech Connect (OSTI)

    Lintereur, Azaree T.; Siciliano, Edward R.; Kouzes, Richard T.

    2012-06-30

    The Department of Energy Office of Nuclear Safeguards (NA-241) is supporting the project “Coincidence Counting With Boron-Based Alternative Neutron Detection Technology” at Pacific Northwest National Laboratory (PNNL) for the development of an alternative neutron coincidence counter. The goal of this project is to design, build and demonstrate a boron-lined proportional tube-based alternative system in the configuration of a coincidence counter. This report discusses the validation studies performed to establish the degree of accuracy of the computer modeling methods current used to simulate the response of boron-lined tubes. This is the precursor to developing models for the uranium neutron coincidence collar under Task 2 of this project.

  6. Rectangular Dielectric-lined Accelerator Structure

    SciTech Connect (OSTI)

    Wang Changbiao; Yakovlev, V.P.; Hirshfield, J.L.

    2004-12-07

    Results are reported from analysis of a rectangular X-band dielectric-lined accelerator structure operating in the symmetric LSM-11 mode that has a number of favorable attributes, by comparison with dielectric-lined cylindrical structures. These attributes include use of two planar one-piece precision-ground TiN coated dielectric slabs free of joints, open slots along two opposing metallic faces to suppress all anti-symmetric higher-order modes and to facilitate high-speed pumping, and significant reduction of wall losses by use of evanescent vacuum gaps beyond the dielectric slabs. It is shown that a structure operating at 11.424 GHz can be built with a shunt impedance > 60 M{omega}/m using low-loss alumina as the dielectric.

  7. In-line real time air monitor

    DOE Patents [OSTI]

    Wise, M.B.; Thompson, C.V.

    1998-07-14

    An in-line gas monitor capable of accurate gas composition analysis in a continuous real time manner even under strong applied vacuum conditions operates by mixing an air sample with helium forming a sample gas in two complementary sample loops embedded in a manifold which includes two pairs of 3-way solenoid valves. The sample gas is then analyzed in an ion trap mass spectrometer on a continuous basis. Two valve drivers actuate the two pairs of 3-way valves in a reciprocating fashion, so that there is always flow through the in-line gas monitor via one or the other of the sample loops. The duty cycle for the two pairs of 3-way valves is varied by tuning the two valve drivers to a duty cycle typically between 0.2 to 0.7 seconds. 3 figs.

  8. Strain monitoring averts line failure in Rockies

    SciTech Connect (OSTI)

    Miller, B.; Bukovansky, M.

    1987-08-10

    The case history of a landslide in the U.S. Rocky Mountains shows that the potential for pipeline monitoring in geologically sensitive areas, those subject to landslides and subsidence, for example. A properly installed monitoring system monitored by the pipeline operator, Western Gas Supply Co. (West Gas), Denver, provided an early warning of increasing line strains. The problem was complicated by rugged topography which is described here. Stability analysis was the key technique utilized in the process.

  9. Heavy rains hamper Louisiana gas line

    SciTech Connect (OSTI)

    Horner, C.

    1983-06-01

    Despite heavy rains and flooding a 36-mile gas pipeline loop for Transcontinental Gas Pipe Line Corp. was completed from north of Starks (at the end of Transco's south Louisiana lateral) to the Lake Charles area. Somastic-coated, 42-in. grade X-60 pipe comprises 90% of the route. The contract included multiple 30-42 in. fabrications, installation of six 42-in. gate valves, and expansion of the Gillis compressor station.

  10. Transmission line environmental assessment guidance document

    SciTech Connect (OSTI)

    Jackson, J.; Pentecost, E.; Muzzarelli, J.

    1994-01-01

    Since 1939, U.S. utility companies have been required to obtain a Presidential Permit to construct electric transmission lines that cross a U.S. border and connect with a foreign utility. The purpose of this document is to provide Presidential Permit applicants with two types of guidance: (1) on the type of environmental and project descriptive information needed to assess the potential impacts of the proposed and alternative actions and (2) on compliance with applicable federal and state regulations. The main three chapters present information on the purpose and content of this document (Chapter 1); legislative, regulatory, and consultation requirements for transmission line interconnect projects (Chapter 2); and identification of basic transmission system design parameters and environmental data requirements for analysis of potential impacts of the proposed action (Chapter 3). Chapter 3 also includes information on possible techniques or measures to mitigate impacts. Appendix A presents an overview of NEPA requirements and DOE`s implementing procedures. Appendix B summarizes information on legislation that may be applicable to transmission line projects proposed in Presidential Permit applications.

  11. Gas lines chasing huge northeastern market

    SciTech Connect (OSTI)

    Watts, J.

    1982-03-01

    Gas for the Northeastern US market is the driving force behind three proposed projects to bring Canadian gas to the New England-New York area: the 360-mile New England States pipeline (Algonquin Gas Transmission Co., Transcontinental Gas Pipe Line Corp., Texas Eastern Transmission Corp., and Nova, an Alberta Corp.); the 261-mile Boundary Gas project (with Boundary Gas Inc., a consortium of 14 gas utilities with Tennessee Gas Pipeline Co. providing transportation); and the 158-mile Niagara pipeline (Transcontinental Gas Pipe Line Corp.). Although none has yet received government (US and Canadian) approval, at least one project - the New England States line - is expected to be operational by 1984, bringing 305 million CF of natural gas daily for US residential and industrial markets. Both countries stand to benefit from the three projects. For Canada, the sale of gas to New England provides a steady market for massive quantities of gas makes building a pipeline from gas-rich Alberta (that will also serve eastern Canada) economically feasible, and ensures the existence of a transportation network in the Maritime provinces for use when production begins off Newfoundland and Nova Scotia. For the US, the gas from Canada will help reduce the nation's dependence on foreign oil and provide additional supplies during the peakload winter season.

  12. http://www

    Energy Savers [EERE]

    Proposed Energy Transport Corridors

  13. Stand-off transmission lines and method for making same

    DOE Patents [OSTI]

    Tuckerman, David B.

    1991-01-01

    Standoff transmission lines in an integrated circuit structure are formed by etching away or removing the portion of the dielectric layer separating the microstrip metal lines and the ground plane from the regions that are not under the lines. The microstrip lines can be fabricated by a subtractive process of etching a metal layer, an additive process of direct laser writing fine lines followed by plating up the lines or a subtractive/additive process in which a trench is etched over a nucleation layer and the wire is electrolytically deposited. Microstrip lines supported on freestanding posts of dielectric material surrounded by air gaps are produced. The average dielectric constant between the lines and ground plane is reduced, resulting in higher characteristic impedance, less crosstalk between lines, increased signal propagation velocities, and reduced wafer stress.

  14. Stand-off transmission lines and method for making same

    DOE Patents [OSTI]

    Tuckerman, D.B.

    1991-05-21

    Standoff transmission lines in an integrated circuit structure are formed by etching away or removing the portion of the dielectric layer separating the microstrip metal lines and the ground plane from the regions that are not under the lines. The microstrip lines can be fabricated by a subtractive process of etching a metal layer, an additive process of direct laser writing fine lines followed by plating up the lines or a subtractive/additive process in which a trench is etched over a nucleation layer and the wire is electrolytically deposited. Microstrip lines supported on freestanding posts of dielectric material surrounded by air gaps are produced. The average dielectric constant between the lines and ground plane is reduced, resulting in higher characteristic impedance, less crosstalk between lines, increased signal propagation velocities, and reduced wafer stress. 16 figures.

  15. Fluid properties determine flow line blockage potential

    SciTech Connect (OSTI)

    Hunt, A.

    1996-07-15

    A thorough understanding of fluid properties helps in determining the potential of hydrates, paraffins, or asphaltenes to block subsea flow lines. Thermal, chemical, and mechanical methods are the main ways for preventing deposition. Already in both the North Sea and the Gulf of Mexico, blockages have led to significant losses in production and reserves recovery. This first article in a two-part series discusses thermal and chemical methods in overcoming fluid behavior problems caused by hydrate and other fluid constituents in subsea multiphase flow. The paper discusses subsea production, possible problems, nucleation, growth, deposition, preventing deposition, hydrate predictions, multiphase flow, and hydrate inhibition.

  16. On-line subsea multiphase flow measurement

    SciTech Connect (OSTI)

    High, G.; Frantzen, K.H.; Marshall, M.

    1995-12-31

    This paper describes the final detailed design, engineering, and installation phase of a Joint Industry Program to qualify a robust subsea multiphase flowmeter module for long-term installation on a North Sea manifold tie-in. Multiphase subsea production has become a common method of hydrocarbon recovery in all areas of offshore E and P. In the North Sea, many developments are subsea satellites with multiphase well-fluids being comingled prior to processing. The system described meets this challenge by offering a cost effective solution to real-time well monitoring as an alternative to the conventional test separator, removing the need for test lines and shutting in wells for testing. The multiphase instrument allows on-line well fluid analysis, and is also an important tool for reservoir management and field analysis, and provides a means of implementing field allocation metering thereby simplifying small marginal field developments. This project is one of the first subsea multiphase flowmeter installations engineered for long-term subsea service, and designed as an integrated component of the subsea production control system.

  17. A radial transmission line material measurement apparatus

    SciTech Connect (OSTI)

    Warne, L.K.; Moyer, R.D.; Koontz, T.E.; Morris, M.E.

    1993-05-01

    A radial transmission line material measurement sample apparatus (sample holder, offset short standards, measurement software, and instrumentation) is described which has been proposed, analyzed, designed, constructed, and tested. The purpose of the apparatus is to obtain accurate surface impedance measurements of lossy, possibly anisotropic, samples at low and intermediate frequencies (vhf and low uhf). The samples typically take the form of sections of the material coatings on conducting objects. Such measurements thus provide the key input data for predictive numerical scattering codes. Prediction of the sample surface impedance from the coaxial input impedance measurement is carried out by two techniques. The first is an analytical model for the coaxial-to-radial transmission line junction. The second is an empirical determination of the bilinear transformation model of the junction by the measurement of three full standards. The standards take the form of three offset shorts (and an additional lossy Salisbury load), which have also been constructed. The accuracy achievable with the device appears to be near one percent.

  18. Mitsui O S K Lines Ltd | Open Energy Information

    Open Energy Info (EERE)

    O S K Lines Ltd Jump to: navigation, search Name: Mitsui O.S.K. Lines Ltd Place: Tokyo, Japan Zip: 1058688 Sector: Services Product: A shipping company, with services including...

  19. Updated Web Tool Focuses on Bottom Line for Distributed Wind...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Updated Web Tool Focuses on Bottom Line for Distributed Wind Turbines Updated Web Tool Focuses on Bottom Line for Distributed Wind Turbines January 10, 2013 - 2:43pm Addthis This...

  20. Updated Web Tool Focuses on Bottom Line for Distributed Wind...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Updated Web Tool Focuses on Bottom Line for Distributed Wind Turbines Updated Web Tool Focuses on Bottom Line for Distributed Wind Turbines January 10, 2013 - 2:43pm Addthis This ...

  1. File:08HIATransmissionLineApproval.pdf | Open Energy Information

    Open Energy Info (EERE)

    8HIATransmissionLineApproval.pdf Jump to: navigation, search File File history File usage Metadata File:08HIATransmissionLineApproval.pdf Size of this preview: 463 599 pixels....

  2. Plains & Eastern Clean Line Project Proposal for New or Upgraded...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    of the Energy Policy Act of 2005 Plains & Eastern Clean Line Project Proposal for New or Upgraded Transmission Line Projects Under Section 1222 of the Energy Policy Act of 2005 ...

  3. To: Mansueti, Lawrence Subject: RE: Pepco Scheduled Line Repair...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    January 29, 2007 6:28 PM To: Mansueti, Lawrence Subject: RE: Pepco Scheduled Line Repair Dec. 1-20, 2006 Larry, Regarding the planned line outage, scheduled for Feb. 20 through Mar...

  4. Emailed Comments of Elizabeth Chimento RE: Pepco Scheduled Line...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Emailed Comments of Elizabeth Chimento RE: Pepco Scheduled Line Repair Dec. 1-20, 2006 Docket No. EO-05-01. Regarding the planned line outage, scheduled for Feb. 20 through Mar. 6, ...

  5. Power Line Plan of Development Outline | Open Energy Information

    Open Energy Info (EERE)

    Line Plan of Development Outline Jump to: navigation, search OpenEI Reference LibraryAdd to library Legal Document- OtherOther: Power Line Plan of Development OutlineLegal...

  6. Changes to the Transfer Line Collimation System for the High...

    Office of Scientific and Technical Information (OSTI)

    Changes to the Transfer Line Collimation System for the High-Luminosity LHC Beams Citation Details In-Document Search Title: Changes to the Transfer Line Collimation System for the ...

  7. EIS-0465: Mid-Atlantic Power Pathway Transmission Line Project...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    5: Mid-Atlantic Power Pathway Transmission Line Project in Maryland and Delaware EIS-0465: Mid-Atlantic Power Pathway Transmission Line Project in Maryland and Delaware March 4, ...

  8. EIS-0507: Boardman-Hemingway Transmission Line, Oregon and Idaho...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    7: Boardman-Hemingway Transmission Line, Oregon and Idaho EIS-0507: Boardman-Hemingway Transmission Line, Oregon and Idaho Summary The Bureau of Land Management and the U.S. Forest ...

  9. EM, County Install Sewer Line for Development | Department of...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    EM, County Install Sewer Line for Development EM, County Install Sewer Line for Development April 29, 2014 - 3:53pm Addthis The Pike County Commissioners recently toured the ...

  10. EIS-0421: Big Eddy-Knight Transmission Line

    Broader source: Energy.gov [DOE]

    BPA is proposing to build a new 500 kilovolt (kV) transmission line in Wasco County, Oregon and Klickitat County, Washington and a new substation in Klickitat County. The new BPA transmission line...

  11. Green Power Transmission Line Given New Life | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Power Transmission Line Given New Life Green Power Transmission Line Given New Life March 11, 2010 - 4:34pm Addthis Poles for the Montana-Alberta Tie Line are unloaded outside Shelby, Mont. | Photo courtesy of Tonbridge Power Poles for the Montana-Alberta Tie Line are unloaded outside Shelby, Mont. | Photo courtesy of Tonbridge Power Stephen Graff Former Writer & editor for Energy Empowers, EERE Thanks to funds from the American Recovery and Reinvestment Act, construction of a green power

  12. Federal Line Management Oversight of Department of Energy Nuclear

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Facilities | Department of Energy Federal Line Management Oversight of Department of Energy Nuclear Facilities Federal Line Management Oversight of Department of Energy Nuclear Facilities This Guide provides U.S. Department of Energy (DOE) line management organizations with guidance that may be useful to them in effectively and efficiently implementing the requirements of DOE O 226.1B, Implementation of Department of Energy Oversight Policy, dated April 25, 2011, as applied to Federal line

  13. Advance Funding and Development Agreement: Plains & Eastern Clean Line

    Energy Savers [EERE]

    Transmission Project (September 20, 2012) | Department of Energy Advance Funding and Development Agreement: Plains & Eastern Clean Line Transmission Project (September 20, 2012) Advance Funding and Development Agreement: Plains & Eastern Clean Line Transmission Project (September 20, 2012) PDF icon Advance Funding and Development Agreement: Plains & Eastern Clean Line Transmission Project (September 20, 2012) More Documents & Publications Plains and Eastern Clean Line

  14. Energy Jobs: Utility Line Worker | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Utility Line Worker Energy Jobs: Utility Line Worker November 19, 2014 - 10:07am Addthis Line workers get hands-on experience with an electrical pole as part of their training. | Photo courtesy of David Weaver. Line workers get hands-on experience with an electrical pole as part of their training. | Photo courtesy of David Weaver. Allison Lantero Allison Lantero Digital Content Specialist, Office of Public Affairs How can I participate? Check out our Infographic on Understanding the Grid. Send

  15. Atomic line emission analyzer for hydrogen isotopes

    DOE Patents [OSTI]

    Kronberg, J.W.

    1993-03-30

    Apparatus for isotopic analysis of hydrogen comprises a low pressure chamber into which a sample of hydrogen is introduced and then exposed to an electrical discharge to excite the electrons of the hydrogen atoms to higher energy states and thereby cause the emission of light on the return to lower energy states, a Fresnel prism made at least in part of a material anomalously dispersive to the wavelengths of interest for dispersing the emitted light, and a photodiode array for receiving the dispersed light. The light emitted by the sample is filtered to pass only the desired wavelengths, such as one of the lines of the Balmer series for hydrogen, the wavelengths of which differ slightly from one isotope to another. The output of the photodiode array is processed to determine the relative amounts of each isotope present in the sample. Additionally, the sample itself may be recovered using a metal hydride.

  16. Atomic line emission analyzer for hydrogen isotopes

    DOE Patents [OSTI]

    Kronberg, James W.

    1993-01-01

    Apparatus for isotopic analysis of hydrogen comprises a low pressure chamber into which a sample of hydrogen is introduced and then exposed to an electrical discharge to excite the electrons of the hydrogen atoms to higher energy states and thereby cause the emission of light on the return to lower energy states, a Fresnel prism made at least in part of a material anomalously dispersive to the wavelengths of interest for dispersing the emitted light, and a photodiode array for receiving the dispersed light. The light emitted by the sample is filtered to pass only the desired wavelengths, such as one of the lines of the Balmer series for hydrogen, the wavelengths of which differ slightly from one isotope to another. The output of the photodiode array is processed to determine the relative amounts of each isotope present in the sample. Additionally, the sample itself may be recovered using a metal hydride.

  17. On-line tritium production monitor

    DOE Patents [OSTI]

    Mihalczo, J.T.

    1993-11-23

    A scintillation optical fiber system for the on-line monitoring of nuclear reactions in an event-by-event manner is described. In the measurement of tritium production one or more optical fibers are coated with enriched {sup 6}Li and connected to standard scintillation counter circuitry. A neutron generated {sup 6}Li(n)T reaction occurs in the coated surface of {sup 6}Li-coated fiber to produce energetic alpha and triton particles one of which enters the optical fiber and scintillates light through the fiber to the counting circuit. The coated optical fibers can be provided with position sensitivity by placing a mirror at the free end of the fibers or by using pulse counting circuits at both ends of the fibers. 5 figures.

  18. On-line process control monitoring system

    DOE Patents [OSTI]

    O'Rourke, Patrick E.; Van Hare, David R.; Prather, William S.

    1992-01-01

    An on-line, fiber-optic based apparatus for monitoring the concentration of a chemical substance at a plurality of locations in a chemical processing system comprises a plurality of probes, each of which is at a different location in the system, a light source, optic fibers for carrying light to and from the probes, a multiplexer for switching light from the source from one probe to the next in series, a diode array spectrophotometer for producing a spectrum from the light received from the probes, and a computer programmed to analyze the spectra so produced. The probes allow the light to pass through the chemical substance so that a portion of the light is absorbed before being returned to the multiplexer. A standard and a reference cell are included for data validation and error checking.

  19. On-line tritium production monitor

    DOE Patents [OSTI]

    Mihalczo, John T.

    1993-01-01

    A scintillation optical fiber system for the on-line monitoring of nuclear reactions in an event-by-event manner is described. In the measurement of tritium production one or more optical fibers are coated with enriched .sup.6 Li and connected to standard scintillation counter circuitry. A neutron generated .sup.6 Li(n )T reaction occurs in the coated surface of .sup.6 Li-coated fiber to produce energetic alpha and triton particles one of which enters the optical fiber and scintillates light through the fiber to the counting circuit. The coated optical fibers can be provided with position sensitivity by placing a mirror at the free end of the fibers or by using pulse counting circuits at both ends of the fibers.

  20. Spectral line broadening in magnetized black holes

    SciTech Connect (OSTI)

    Frolov, Valeri P.; Shoom, Andrey A.; Tzounis, Christos E-mail: ashoom@ualberta.ca

    2014-07-01

    We consider weakly magnetized non-rotating black holes. In the presence of a regular magnetic field the motion of charged particles in the vicinity of a black hole is modified. As a result, the position of the innermost stable circular orbit (ISCO) becomes closer to the horizon. When the Lorentz force is repulsive (directed from the black hole) the ISCO radius can reach the gravitational radius. In the process of accretion charged particles (ions) of the accreting matter can be accumulated near their ISCO, while neutral particles fall down to the black hole after they reach 6M radius. The sharp spectral line Fe α, emitted by iron ions at such orbits, is broadened when the emission is registered by a distant observer. In this paper we study this broadening effect and discuss how one can extract information concerning the strength of the magnetic field from the observed spectrum.

  1. Atomic line emission analyzer for hydrogen isotopes

    DOE Patents [OSTI]

    Kronberg, J.W.

    1991-05-08

    Apparatus for isotopic analysis of hydrogen comprises a low pressure chamber into which a sample of hydrogen is introduced and then exposed to an electrical discharge to excite the electrons of the hydrogen atoms to higher energy states and thereby cause the emission of light on the return to lower energy states, a Fresnel prism made at least in part of a material anomalously dispersive to the wavelengths of interest for dispersing the emitted light, and a photodiode array for receiving the dispersed light. The light emitted by the sample is filtered to pass only the desired wavelengths, such as one of the lines of the Balmer series for hydrogen, the wavelengths of which differ slightly from one isotope to another. The output of the photodiode array is processed to determine the relative amounts of each isotope present in the sample. Additionally, the sample itself may be recovered using, a metal hydride.

  2. Dispersion-free radial transmission lines

    DOE Patents [OSTI]

    Caporaso, George J.; Nelson, Scott D.

    2011-04-12

    A dispersion-free radial transmission line ("DFRTL") preferably for linear accelerators, having two plane conductors each with a central hole, and an electromagnetically permeable material ("EPM") between the two conductors and surrounding a channel connecting the two holes. At least one of the material parameters of relative magnetic permeability, relative dielectric permittivity, and axial width of the EPM is varied as a function of radius, so that the characteristic impedance of the DFRTL is held substantially constant, and pulse transmission therethrough is substantially dispersion-free. Preferably, the EPM is divided into concentric radial sections, with the varied material parameters held constant in each respective section but stepwise varied between sections as a step function of the radius. The radial widths of the concentric sections are selected so that pulse traversal time across each section is the same, and the varied material parameters of the concentric sections are selected to minimize traversal error.

  3. Second Line of Defense Spares Program Assessment

    SciTech Connect (OSTI)

    Henderson, Dale L.; Muller, George; Mercier, Theresa M.; Brigantic, Robert T.; Perkins, Casey J.; Cooley, Scott K.

    2012-11-20

    The Office of the Second Line of Defense (SLD) is part of the Department of Energy‘s (DOE) National Nuclear Security Administration (NNSA). The SLD Program accomplishes its critical global security mission by forming cooperative relationships with partner countries to install passive radiation detection systems that augment traditional inspection and law enforcement measures by alerting border officials to the presence of special nuclear or other radiological materials in cross-border traffic. An important tenet of the program is to work collaboratively with these countries to establish the necessary processes, procedures, infrastructure and conditions that will enable them to fully assume the financial and technical responsibilities for operating the equipment. As the number of operational deployments grows, the SLD Program faces an increasingly complex logistics process to promote the timely and efficient supply of spare parts.

  4. Method for bonding a transmission line to a downhole tool

    DOE Patents [OSTI]

    Hall, David R.; Fox, Joe

    2007-11-06

    An apparatus for bonding a transmission line to the central bore of a downhole tool includes a pre-formed interface for bonding a transmission line to the inside diameter of a downhole tool. The pre-formed interface includes a first surface that substantially conforms to the outside contour of a transmission line and a second surface that substantially conforms to the inside diameter of a downhole tool. In another aspect of the invention, a method for bonding a transmission line to the inside diameter of a downhole tool includes positioning a transmission line near the inside wall of a downhole tool and placing a mold near the transmission line and the inside wall. The method further includes injecting a bonding material into the mold and curing the bonding material such that the bonding material bonds the transmission line to the inside wall.

  5. Pipe line companies to install 14,766 miles of lines in 1994

    SciTech Connect (OSTI)

    Ives, G. Jr.

    1994-01-01

    This paper reviews the historical and projected pipeline construction activities in the US and around the world. It gives mileage values for all types of oil and gas transmission lines, both on and offshore. Tables provides information on the diameters of these pipelines and information on compressor stations planned and constructed. Known major construction projects are listed by company name with a brief description of the proposed project.

  6. Contingency Analysis of Cascading Line Outage Events

    SciTech Connect (OSTI)

    Thomas L Baldwin; Magdy S Tawfik; Miles McQueen

    2011-03-01

    As the US power systems continue to increase in size and complexity, including the growth of smart grids, larger blackouts due to cascading outages become more likely. Grid congestion is often associated with a cascading collapse leading to a major blackout. Such a collapse is characterized by a self-sustaining sequence of line outages followed by a topology breakup of the network. This paper addresses the implementation and testing of a process for N-k contingency analysis and sequential cascading outage simulation in order to identify potential cascading modes. A modeling approach described in this paper offers a unique capability to identify initiating events that may lead to cascading outages. It predicts the development of cascading events by identifying and visualizing potential cascading tiers. The proposed approach was implemented using a 328-bus simplified SERC power system network. The results of the study indicate that initiating events and possible cascading chains may be identified, ranked and visualized. This approach may be used to improve the reliability of a transmission grid and reduce its vulnerability to cascading outages.

  7. Boron-Lined Neutron Detector Measurements

    SciTech Connect (OSTI)

    Lintereur, Azaree T.; Kouzes, Richard T.; Ely, James H.; Erikson, Luke E.; Siciliano, Edward R.; Woodring, Mitchell L.

    2010-03-07

    PNNL-18938 Revision Radiation portal monitors used for interdiction of illicit materials at borders include highly sensitive neutron detection systems. The main reason for having neutron detection capability is to detect fission neutrons from plutonium. The currently deployed radiation portal monitors (RPMs) from Ludlum and Science Applications International Corporation (SAIC) use neutron detectors based upon 3He-filled gas proportional counters, which are the most common large neutron detector. There is a declining supply of 3He in the world, and thus, methods to reduce the use of this gas in RPMs with minimal changes to the current system designs and sensitivity to cargo-borne neutrons are being investigated. Four technologies have been identified as being currently commercially available, potential alternative neutron detectors to replace the use of 3He in RPMs. Reported here are the results of tests of a newly designed boron-lined proportional counter option. This testing measured the neutron detection efficiency and gamma ray rejection capabilities of two successive prototypes of a system manufactured by GE Reuter Stokes.

  8. Boron-Lined Neutron Detector Measurements

    SciTech Connect (OSTI)

    Lintereur, Azaree T.; Kouzes, Richard T.; Ely, James H.; Erikson, Luke E.; Siciliano, Edward R.

    2009-11-02

    Radiation portal monitors used for interdiction of illicit materials at borders include highly sensitive neutron detection systems. The main reason for having neutron detection capability is to detect fission neutrons from plutonium. The currently deployed radiation portal monitors (RPMs) from Ludlum and Science Applications International Corporation (SAIC) use neutron detectors based upon 3He-filled gas proportional counters, which are the most common large neutron detector. There is a declining supply of 3He in the world, and thus, methods to reduce the use of this gas in RPMs with minimal changes to the current system designs and sensitivity to cargo-borne neutrons are being investigated. Four technologies have been identified as being currently commercially available, potential alternative neutron detectors to replace the use of 3He in RPMs. Reported here are the results of tests of a newly designed boron-lined proportional counter option. This testing measured the neutron detection efficiency and gamma ray rejection capabilities of a system manufactured by Reuter Stokes.

  9. Second Line of Defense Spares Program

    SciTech Connect (OSTI)

    Henderson, Dale L.; Holmes, Aimee E.; Muller, George; Mercier, Theresa M.; Brigantic, Robert T.; Perkins, Casey J.; Cooley, Scott K.; Thorsen, Darlene E.

    2012-11-20

    During Fiscal Year 2012, a team from the Pacific Northwest National Laboratory (PNNL) conducted an assessment and analysis of the Second Line of Defense (SLD) Sustainability spare parts program. Spare parts management touches many aspects of the SLD Sustainability Program including contracting and integration of Local Maintenance Providers (LMP), equipment vendors, analyses and metrics on program performance, system state of health, and maintenance practices. Standardized spares management will provide better data for decisions during site transition phase and will facilitate transition to host country sustainability ownership. The effort was coordinated with related SLD Sustainability Program initiatives, including a configuration items baselining initiative, a metrics initiative, and a maintenance initiative. The spares study has also led to pilot programs for sourcing alternatives that include regional intermediate inventories and partnering agreements that leverage existing supply chains. Many partners from the SLD Sustainability program contributed to and were consulted in the course of the study. This document provides a description of the findings, recommendations, and implemented solutions that have resulted from the study.

  10. EIS-0285-SA-451: Supplement Analysis

    Broader source: Energy.gov [DOE]

    Supplement Analysis for the Transmission System Vegetation Management Program FEIS (DOE/EIS- 0285/SA-451 Carlton-Tillamook Transmission Line Corridor, PP&A-2068)

  11. Email to Congestionstudy.comments@hq.doe.gov

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    lines. I urge you to consider these reasons and please do not establish any National Interest Energy Transmission Corridor. Thank you, Doris Brown 1017 Timberline Moberly, MO 65270

  12. OVAI Contract Report #2012-43 PHASE II ARCHAEOLOGICAL EVALUATION...

    Energy Savers [EERE]

    ... the center of the farm complex following the power line corridor that crosscuts the site. ... Portsmouth Area Project Real Estate Easements map, and the 1952 AEC topography maps ...

  13. EIS-0285-SA-449: Supplement Analysis | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    EIS-0285-SA-449: Supplement Analysis Transmission System Vegetation Management Program, Kalispell-Kerr 1 Transmission Line Corridor PDF icon EIS-0285-SA-449-2011.pdf More ...

  14. From: Deb Long To: Congestion Study Comments Subject:

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Deb Long To: Congestion Study Comments Subject: Transmission lines Date: Friday, September ... Transmission Corridors. Thank you, Deborah Long 25271 Hwy 11 Brunswick, Missouri 65236 ...

  15. The transcriptional diversity of 25 Drosophila cell lines

    SciTech Connect (OSTI)

    Cherbas, Lucy; Willingham, Aarron; Zhang, Dayu; Yang, Li; Zou, Yi; Eads, Brian D.; Carlson, Joseph W.; Landolin, Jane M.; Kapranov, Philipp; Dumais, Jacqueline; Samsonova, Anastasia; Choi, Jeong-Hyeon; Roberts, Johnny; Davis, Carrie A.; Tang, Haixu; van Baren, Marijke J.; Ghosh, Srinka; Dobin, Alexander; Bell, Kim; Lin, Wei; Langton, Laura; Duff, Michael O.; Tenney, Aaron E.; Zaleski, Chris; Brent, Michael R.; Hoskins, Roger A.; Kaufman, Thomas C.; Andrews, Justen; Graveley, Brenton R.; Perrimon, Norbert; Celniker, Susan E.; Gingeras, Thomas R.; Cherbas, Peter

    2010-11-15

    Drosophila melanogaster cell lines are important resources for cell biologists. Here, we catalog the expression of exons, genes, and unannotated transcriptional signals for 25 lines. Unannotated transcription is substantial (typically 19% of euchromatic signal). Conservatively, we identify 1405 novel transcribed regions; 684 of these appear to be new exons of neighboring, often distant, genes. Sixty-four percent of genes are expressed detectably in at least one line, but only 21% are detected in all lines. Each cell line expresses, on average, 5885 genes, including a common set of 3109. Expression levels vary over several orders of magnitude. Major signaling pathways are well represented: most differentiation pathways are off and survival/growth pathways on. Roughly 50% of the genes expressed by each line are not part of the common set, and these show considerable individuality. Thirty-one percent are expressed at a higher level in at least one cell line than in any single developmental stage, suggesting that each line is enriched for genes characteristic of small sets of cells. Most remarkable is that imaginal discderived lines can generally be assigned, on the basis of expression, to small territories within developing discs. These mappings reveal unexpected stability of even fine-grained spatial determination. No two cell lines show identical transcription factor expression. We conclude that each line has retained features of an individual founder cell superimposed on a common cell line gene expression pattern. Wereport the transcriptional profiles of 25 Drosophila melanogaster cell lines, principally by whole-genome tiling microarray analysis of total RNA, carried out as part of the modENCODE project. The data produced in this study add to our knowledge of the cell lines and of the Drosophila transcriptome in several ways. We summarize the expression of previously annotated genes in each of the 25 lines with emphasis on what those patterns reveal about the origins of the lines and the stability of spatial expression patterns. We also offer an initial analysis of previously unannotated transcripts in the cell lines.

  16. Radio frequency communication system utilizing radiating transmission lines

    DOE Patents [OSTI]

    Struven, Warren C.

    1984-01-01

    A radio communication system for use in tunnels, mines, buildings or other shielded locations in which a pair of radiating transmission lines (30), (31) extend through such location in spaced coextensive relation to each other. Each transmission line (30), (31) has at least one unidirectional amplifier (32), (33) interposed therein with the sense of the unidirectional amplifier (32) of one transmission line (30) being opposite to the sense of the unidirectional amplifier (33) of the other transmission line (31). Each of the amplifiers (32), (33) has a gain which is less than the coupling loss between the transmission lines (30), (31). Two or more mobile transceivers (35) in the location served by the system are coupled to the transmission lines (30), (31) by electromagnetic wave propagation in space in order to communicate directly with each other at a given radio frequency within the frequency range of the system.

  17. Sensor, method and system of monitoring transmission lines

    DOE Patents [OSTI]

    Syracuse, Steven J.; Clark, Roy; Halverson, Peter G.; Tesche, Frederick M.; Barlow, Charles V.

    2012-10-02

    An apparatus, method, and system for measuring the magnetic field produced by phase conductors in multi-phase power lines. The magnetic field measurements are used to determine the current load on the conductors. The magnetic fields are sensed by coils placed sufficiently proximate the lines to measure the voltage induced in the coils by the field without touching the lines. The x and y components of the magnetic fields are used to calculate the conductor sag, and then the sag data, along with the field strength data, can be used to calculate the current load on the line and the phase of the current. The sag calculations of this invention are independent of line voltage and line current measurements. The system applies a computerized fitter routine to measured and sampled voltages on the coils to accurately determine the values of parameters associated with the overhead phase conductors.

  18. Living and Working Safely Around High-Voltage Power Lines.

    SciTech Connect (OSTI)

    United States. Bonneville Power Administration.

    2001-06-01

    High-voltage transmission lines can be just as safe as the electrical wiring in the homes--or just as dangerous. The crucial factor is ourselves: they must learn to behave safely around them. This booklet is a basic safety guide for those who live and work around power lines. It deals primarily with nuisance shocks due to induced voltages, and with potential electric shock hazards from contact with high-voltage lines. References on possible long-term biological effects of transmission lines are shown. In preparing this booklet, the Bonneville Power Administration has drawn on more than 50 years of experience with high-voltage transmission. BPA operates one of the world`s largest networks of long-distance, high-voltage lines. This system has more than 400 substations and about 15,000 miles of transmission lines, almost 4,400 miles of which are operated at 500,000 volts.

  19. In-line phase shift tomosynthesis

    SciTech Connect (OSTI)

    Hammonds, Jeffrey C.; Price, Ronald R.; Pickens, David R.; Donnelly, Edwin F.

    2013-08-15

    Purpose: The purpose of this work is to (1) demonstrate laboratory measurements of phase shift images derived from in-line phase-contrast radiographs using the attenuation-partition based algorithm (APBA) of Yan et al.[Opt. Express 18(15), 1607416089 (2010)], (2) verify that the APBA reconstructed images obey the linearity principle, and (3) reconstruct tomosynthesis phase shift images from a collection of angularly sampled planar phase shift images.Methods: An unmodified, commercially available cabinet x-ray system (Faxitron LX-60) was used in this experiment. This system contains a tungsten anode x-ray tube with a nominal focal spot size of 10 ?m. The digital detector uses CsI/CMOS with a pixel size of 50 50 ?m. The phantoms used consisted of one acrylic plate, two polystyrene plates, and a habanero pepper. Tomosynthesis images were reconstructed from 51 images acquired over a 25 arc. All phase shift images were reconstructed using the APBA.Results: Image contrast derived from the planar phase shift image of an acrylic plate of uniform thickness exceeded the contrast of the traditional attenuation image by an approximate factor of two. Comparison of the planar phase shift images from a single, uniform thickness polystyrene plate with two polystyrene plates demonstrated an approximate linearity of the estimated phase shift with plate thickness (?1600 rad vs ?2970 rad). Tomographic phase shift images of the habanero pepper exhibited acceptable spatial resolution and contrast comparable to the corresponding attenuation image.Conclusions: This work demonstrated the feasibility of laboratory-based phase shift tomosynthesis and suggests that phase shift imaging could potentially provide a new imaging biomarker. Further investigation will be needed to determine if phase shift contrast will be able to provide new tissue contrast information or improved clinical performance.

  20. Clean Line Plains and Eastern Section 1222 Decision Documents | Department

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    of Energy Clean Line Plains and Eastern Section 1222 Decision Documents Clean Line Plains and Eastern Section 1222 Decision Documents On March 25, 2016, U.S. Secretary of Energy Dr. Ernest Moniz announced that the Department of Energy (DOE) will participate in the development of the Plains & Eastern Clean Line project (Project), a major clean energy infrastructure project. Through section 1222 of the Energy Policy Act of 2005, Congress authorized DOE to promote electric transmission

  1. Comments on RFI on Permitting of Transmission Lines Available | Department

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    of Energy Comments on RFI on Permitting of Transmission Lines Available Comments on RFI on Permitting of Transmission Lines Available April 3, 2012 - 2:12pm Addthis On October 5, 2011, the White House announced the creation of a Rapid Response Team for Transmission (RRTT). In support of the RRTT the Department of Energy's Office of Electricity Delivery and Energy Reliability released a Federal Register Notice seeking information on questions related to permitting of transmission lines. The

  2. EIS-0474: Southline Transmission Line Project; Arizona and New Mexico |

    Energy Savers [EERE]

    Department of Energy 474: Southline Transmission Line Project; Arizona and New Mexico EIS-0474: Southline Transmission Line Project; Arizona and New Mexico Summary The Bureau of Land Management and Western Area Power Administration are preparing an EIS as joint lead agencies to evaluate the potential environmental impacts of the proposed Southline Transmission Project and address associated potential land use plan amendments. The project would consist of a new 225-mile transmission line

  3. Inertial confinement fusion method producing line source radiation fluence

    DOE Patents [OSTI]

    Rose, Ronald P.

    1984-01-01

    An inertial confinement fusion method in which target pellets are imploded in sequence by laser light beams or other energy beams at an implosion site which is variable between pellet implosions along a line. The effect of the variability in position of the implosion site along a line is to distribute the radiation fluence in surrounding reactor components as a line source of radiation would do, thereby permitting the utilization of cylindrical geometry in the design of the reactor and internal components.

  4. Monolithic torpedo bottle lining at Weirton Steel Corporation

    SciTech Connect (OSTI)

    Baker, R.; Griffith, E.

    1996-12-31

    In late 1992 and early 1993 Weirton Steel burned through three torpedo bottles in a three-month period. To determine the cause of the burn throughs, a thorough review of bottle maintenance practices was initiated. Upon identification of contributing factors, changes in operating practices were made. In an effort to increase bottle reliability, lining trials were initiated. Among the trials, a monolithic lining was installed and this paper will discuss results of the lining to date.

  5. DOE Seeking Information on Transmission Line Permitting | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy Seeking Information on Transmission Line Permitting DOE Seeking Information on Transmission Line Permitting February 27, 2012 - 3:25pm Addthis The Department of Energy's Office of Electricity Delivery and Energy Reliability is seeking information on the questions related to permitting of transmission lines. Infrastructure projects - such as high voltage, long distance, electric transmission facilities - often involve multiple Federal, State, local, and Tribal authorizations and are

  6. TRANSPORT OF WASTE SIMULANTS IN PJM VENT LINES

    SciTech Connect (OSTI)

    Qureshi, Z

    2007-02-21

    The experimental work was conducted to determine whether there is a potential for waste simulant to transport or 'creep' up the air link line and contaminate the pulse jet vent system, and possibly cause long term restriction of the air link line. Additionally, if simulant creep occurred, establish operating parameters for washing down the line. The amount of the addition of flush fluids and mixer downtime must be quantified.

  7. Increasing the Capacity of Existing Power Lines | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Increasing the Capacity of Existing Power Lines Increasing the Capacity of Existing Power Lines The capacity of the grid has been largely unchanged for decades and needs to expand to accommodate new power plants and renewable energy projects. The difference in time and cost between using existing transmission lines or the construction of new ones can make or break plans for new wind or solar farms. PDF icon inl_powerline_cooling_factsheet.pdf More Documents & Publications EIS-0183: Record of

  8. Strengthening the Front Lines: Sales Training and Continuing Education for

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Contractors | Department of Energy the Front Lines: Sales Training and Continuing Education for Contractors Strengthening the Front Lines: Sales Training and Continuing Education for Contractors Better Buildings Residential Network Peer Exchange Call Series: Strengthening the Front Lines: Sales Training and Continuing Education for Contractors, call slides and discussion summary. PDF icon Call Slides and Discussion Summary More Documents & Publications Staged Upgrades - Homeowner-focused

  9. DOE-EPRI On-Line Monitoring Implementation Guidelines

    SciTech Connect (OSTI)

    E. Davis, R. Bickford

    2003-01-02

    Industry and EPRI experience at several plants has shown on-line monitoring to be very effective in identifying out-of-calibration instrument channels or indications of equipment-degradation problems. The EPRI implementation project for on-line monitoring has demonstrated the feasability of on-line monitoring at several participating nuclear plants. The results have been very enouraging, and substantial progress is anticipated in the coming years.

  10. EM Recovery Act Top Line Messages | Department of Energy

    Energy Savers [EERE]

    Top Line Messages EM Recovery Act Top Line Messages The lastest Recovery Act performance related information and metrics. PDF icon EM Recovery Act Top Line Messages - April, 2013 More Documents & Publications Workers at Hanford Site Achieve Recovery Act Legacy Cleanup Goals Ahead of Schedule Audit Report: IG-0426 Testimony of Mark Whitney Principal Deputy Assistant Secretary for Environmental Management Before the Subcommittee on Environment and the Economy House Energy and Commerce

  11. Atmospheric Line of Site Experiment (ALOSE) Final Campaign Summary

    Office of Scientific and Technical Information (OSTI)

    (Technical Report) | SciTech Connect Atmospheric Line of Site Experiment (ALOSE) Final Campaign Summary Citation Details In-Document Search Title: Atmospheric Line of Site Experiment (ALOSE) Final Campaign Summary The Atmospheric Line of Site Experiment (ALOSE) was a project to produce best-estimate atmospheric state measurements at the: 1. DOE Atmospheric Radiation Measurement (ARM) Clouds and Radiation Test-bed (CART) site located in Lamont, Oklahoma (11-14 December 2012) 2. Poker Flat

  12. Historical Time Line and Information About the Hanford Site

    SciTech Connect (OSTI)

    Briggs, James D.

    2001-03-07

    Historical time line of the Hanford Site spanning from 1940 through 1997, including photographs and other information regarding the town sites and living conditions.

  13. EIS-0483: Estes to Flatiron Substation Transmission Lines Rebuild...

    Energy Savers [EERE]

    Colorado. EIS-0483: Estes to Flatiron Substation Transmission Lines Rebuild Project Public Comment Opportunities No public comment opportunities available at this time....

  14. Appendix S-51 - Transmission Line Approval - Public Utilities...

    Open Energy Info (EERE)

    from "http:en.openei.orgwindex.php?titleAppendixS-51-TransmissionLineApproval-PublicUtilitiesCommission&oldid800735" Feedback Contact needs updating Image needs...

  15. EIS-0325: Schultz-Hanford Area Transmission Line Project, WA

    Broader source: Energy.gov [DOE]

    BPA proposes to construct a new 500-kilovolt (kV) transmission line in central Washington. This project would increase transmission system capacity north of Hanford.

  16. A simple line wave generator using commercial explosives

    SciTech Connect (OSTI)

    Morris, John S; Jackson, Scott I; Hill, Larry G

    2009-01-01

    We present a simple and inexpensive explosive line wave generator has been designed using commercial sheet explosive and plane wave lens concepts. The line wave generator is constructed using PETN and RDX based sheet explosive for the slow and fast components respectively. The design permits the creation of any desired line width. A series of experiments were performed on a 100 mm design, measuring the detonation arrival time at the output of the generator using a streak camera. An iterative technique was used to adjust the line wave generator's slow and fast components, so as to minimize the arrival time deviation. Designs, test results, and concepts for improvements will be discussed.

  17. Presentation title: This can be up to 2 lines

    U.S. Energy Information Administration (EIA) Indexed Site

    ... Note: Dashed line represents previous 10-year average (2006-2015). Source: Short-Term Energy Outlook, April 2016 16 2016 Summer Fuels Outlook Change in residential electricity ...

  18. Line spectrum and ion temperature measurements from tungsten...

    Office of Scientific and Technical Information (OSTI)

    Doppler broadening of a tungsten candidate line was successfully measured and the ion ... TO NUCLEAR SCIENCE AND TECHNOLOGY; DOPPLER BROADENING; ION TEMPERATURE; IONIZATION; ...

  19. Hawaii Clean Energy Initiative - Transmission Line Approval Permit...

    Open Energy Info (EERE)

    Reference LibraryAdd to library PermittingRegulatory Guidance - Instructions: Hawaii Clean Energy Initiative - Transmission Line Approval Permit PacketPermittingRegulatory...

  20. Office of Enterprise Assessments Review of Field Element Line...

    Office of Environmental Management (EM)

    SNL Sandia National Laboratories ii Office of Enterprise Assessments Review of Field Element Line Management Oversight at Sandia National Laboratories EXECUTIVE SUMMARY The...

  1. Wireless Sensor Network for Electric Transmission Line Monitoring...

    Office of Scientific and Technical Information (OSTI)

    Technical Report: Wireless Sensor Network for Electric Transmission Line Monitoring Citation Details In-Document Search Title: Wireless Sensor Network for Electric Transmission ...

  2. NYDOCS01/1646893 Plains and Eastern Clean Line Participation...

    Office of Environmental Management (EM)

    ... or owning new electric power transmission facilities and ... with the Clean Line Entities in the design, ... The project will seek 150 - 200 foot wide easements in which ...

  3. Lane-Wendson No. 1 Transmission Line Rebuild Project

    Office of Environmental Management (EM)

    No. 1 Transmission Line Rebuild Project Finding of ... OF ENERGY Bonneville Power Administration DOEEA-1952 ... right-of-way and easements to minimize impacts to ...

  4. Request for Information on Permitting of Transmission Lines:...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Permitting of Transmission Lines: Federal Register Notice Volume 77, No. 38 - Feb. 27, ... wide array of processes and procedural requirements in order to obtain all necessary ...

  5. Magnetic Field Line Tracing Calculations for Conceptual PFC Design...

    Office of Scientific and Technical Information (OSTI)

    PFC Design in the National Compact Stellarator Experiment Citation Details In-Document Search Title: Magnetic Field Line Tracing Calculations for Conceptual PFC Design in the ...

  6. Salt Waste Processing Facility, Line Management Review Board Charter

    Broader source: Energy.gov [DOE]

    The Line Management Review Board (LMRB) serves an important oversight function to monitor the readiness processes and associated deliverables for the Salt Waste Processing Facility (SWPF). The...

  7. EIS-0499: Great Northern Transmission Line Project, Minnesota...

    Broader source: Energy.gov (indexed) [DOE]

    and connect a new 883-megawatt electric transmission system across the U.S.-Canada border. The proposed 220 mile transmission line would cross the border near Roseau,...

  8. Electrical and Biological Effects of Transmission Lines: A Review.

    SciTech Connect (OSTI)

    Lee, Jack M.

    1989-06-01

    This review describes the electrical properties of a-c and d-c transmission lines and the resulting effects on plants, animals, and people. Methods used by BPA to mitigate undesirable effects are also discussed. Although much of the information in this review pertains to high-voltage transmission lines, information on distribution lines and electrical appliances is included. The electrical properties discussed are electric and magnetic fields and corona: first for alternating-current (a-c) lines, then for direct current (d-c).

  9. Development of aerogel-lined targets for inertial confinement...

    Office of Scientific and Technical Information (OSTI)

    aerogel-lined targets for inertial confinement fusion experiments Braun, T 36 MATERIALS SCIENCE Abstract not provided Lawrence Livermore National Laboratory (LLNL), Livermore, CA...

  10. Magnetic Field Line Tracing Calculations for Conceptual PFC Design...

    Office of Scientific and Technical Information (OSTI)

    enabling the investigation of high beta physics in a compact stellarator geometry. ... In this paper, we report on the magnetic field line tracing calculations used to evaluate ...

  11. EIS-0502: Hot Springs to Anaconda Transmission Line Rebuild Project...

    Energy Savers [EERE]

    Springs to Anaconda Transmission Line Rebuild Project, Montana SUMMARY DOE's Bonneville Power Administration (BPA) is preparing an EIS that will analyze the potential environmental...

  12. EIS-0317: Kangley-Echo Lake Transmission Line Project

    Broader source: Energy.gov [DOE]

    This EIS analyzes BPA's proposal to build a new transmission line to accommodate increasing demand for electricity and ensure reliability in the Puget Sound area.

  13. Suggested Practices for Avian Protection on Power Lines | Open...

    Open Energy Info (EERE)

    with federal laws protecting and enhancing avian populations, and maintaining the reliability of electric power networds. Author Avian Power Line Interaction Committee...

  14. Guide to Permitting Electric Transmission Lines in Wyoming |...

    Open Energy Info (EERE)

    search OpenEI Reference LibraryAdd to library PermittingRegulatory Guidance - GuideHandbook: Guide to Permitting Electric Transmission Lines in WyomingPermitting...

  15. EIS-0474: Southline Transmission Line Project; Arizona and New...

    Broader source: Energy.gov (indexed) [DOE]

    consist of a new 225-mile transmission line between existing substations at Afton, New Mexico, and Apache, Arizona, and improvements to approximately 130 miles of existing...

  16. Proposed Southline Transmission Line Project - Volume 4 of 4...

    Office of Environmental Management (EM)

    2 Appendix J J-1 Southline Transmission Line Project Draft Environmental Impact Statement and Draft Resource Management Plan Amendment BLM LAND USE AUTHORIZATIONS 1...

  17. Comparison of line-imaging VISAR inferences of spalled sample...

    Office of Scientific and Technical Information (OSTI)

    distension with metallographic analysis of spalled samples. Citation Details In-Document Search Title: Comparison of line-imaging VISAR inferences of spalled sample distension ...

  18. Plains & Eastern Clean Line Project Proposal for New or Upgraded...

    Broader source: Energy.gov (indexed) [DOE]

    ... Act NERC North American Electric Reliability Corporation ... for New or Upgraded Transmission Line Projects Under Section ... Due to its lower losses and more efficient use of right ...

  19. Section 1222 Program - Proposed Plains & Eastern Clean Line Project...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Section 1222 Program - Proposed Plains & Eastern Clean Line ... through the Southwestern Power Administration ... NEPA Website, and through other channels of communication. ...

  20. Secretary Chu Visits Russian Seaport, Checks Out Second Line...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Part of our effort to secure vulnerable nuclear material around the world, the Second Line of Defense program works to crack down on nuclear smuggling by installing radiation ...

  1. Sandia Energy - Digital In-Line Holography Helps Researchers...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    droplets of fuel are generated and behave in such cases. Sandia researchers developed 3-D measurement techniques based on digital in-line holography (DIH). Sandia advanced DIH...

  2. Situ soil sampling probe system with heated transfer line

    DOE Patents [OSTI]

    Robbat, Jr., Albert

    2002-01-01

    The present invention is directed both to an improved in situ penetrometer probe and to a heated, flexible transfer line. The line and probe may be implemented together in a penetrometer system in which the transfer line is used to connect the probe to a collector/analyzer at the surface. The probe comprises a heater that controls a temperature of a geologic medium surrounding the probe. At least one carrier gas port and vapor collection port are located on an external side wall of the probe. The carrier gas port provides a carrier gas into the geologic medium, and the collection port captures vapors from the geologic medium for analysis. In the transfer line, a flexible collection line that conveys a collected fluid, i.e., vapor, sample to a collector/analyzer. A flexible carrier gas line conveys a carrier gas to facilitate the collection of the sample. A system heating the collection line is also provided. Preferably the collection line is electrically conductive so that an electrical power source can generate a current through it so that the internal resistance generates heat.

  3. Yield Line Evaluation Methodology for Reinforced Concrete Structures

    Energy Science and Technology Software Center (OSTI)

    1998-12-30

    Yield line theory is an analytical technique that can be used to determine the ultimate bending capacity of flat reinforced concrete plates subject to distributed and concentrated loadings. Alternately, yield line theory, combined with rotation limits can be used to determine the energy absorption capacity of plates subject to impulsive and impact loadings. Typical components analyzed by yield line theory are basemats, floor and roof slabs subject to vertical loads along with walls subject tomore » out of plane loadings. One limitation of yield line theory is that it is computationally difficult to evaluate some mechanisms. This problem is aggravated by the complex geometry and reinforcing layouts commonly found in practice. The program has the capability to either evaluate a single user defined mechanism or to iterate over a range of mechanisms to determine the minimum ultimate capacity. The program is verified by comparison to a series of yield line mechanisms with known solutions.« less

  4. Non-coherent continuum scattering as a line polarization mechanism

    SciTech Connect (OSTI)

    Del Pino Alemán, T.; Manso Sainz, R.; Trujillo Bueno, J. E-mail: rsainz@iac.es

    2014-03-20

    Line scattering polarization can be strongly affected by Rayleigh scattering at neutral hydrogen and Thomson scattering at free electrons. Often a depolarization of the continuum results, but the Doppler redistribution produced by the continuum scatterers, which are light (hence, fast), induces more complex interactions between the polarization in spectral lines and in the continuum. Here we formulate and solve the radiative transfer problem of scattering line polarization with non-coherent continuum scattering consistently. The problem is formulated within the spherical tensor representation of atomic and light polarization. The numerical method of solution is a generalization of the Accelerated Lambda Iteration that is applied to both the atomic system and the radiation field. We show that the redistribution of the spectral line radiation due to the non-coherence of the continuum scattering may modify the shape of the emergent fractional linear polarization patterns significantly, even yielding polarization signals above the continuum level in intrinsically unpolarizable lines.

  5. Continuous human cell lines and method of making same

    DOE Patents [OSTI]

    Stampfer, M.R.

    1985-07-01

    Substantially genetically stable continuous human cell lines derived from normal human mammary epithelial cells (HMEC) and processes for making and using the same. In a preferred embodiment, the cell lines are derived by treating normal human mammary epithelial tissue with a chemical carcinogen such as benzo(a)pyrene. The novel cell lines serve as useful substrates for elucidating the potential effects of a number of toxins, carcinogens and mutagens as well as of the addition of exogenous genetic material. The autogenic parent cells from which the cell lines are derived serve as convenient control samples for testing. The cell lines are not neoplastically transformed, although they have acquired several properties which distinguish them from their normal progenitors. 2 tabs.

  6. Continuous human cell lines and method of making same

    DOE Patents [OSTI]

    Stampfer, Martha R.

    1989-01-01

    Substantially genetically stable continuous human cell lines derived from normal human mammary epithelial cells (HMEC) and processes for making and using the same. In a preferred embodiment, the cell lines are derived by treating normal human mammary epithelial tissue with a chemical carcinogen such as benzo[a]pyrene. The novel cell lines serve as useful substrates for elucidating the potential effects of a number of toxins, carcinogens and mutagens as well as of the addition of exogenous genetic material. The autogenic parent cells from which the cell lines are derived serve as convenient control samples for testing. The cell lines are not neoplastically transformed, although they have acquired several properties which distinguish them from their normal progenitors.

  7. Profiled spectral lines generated in the field of Kerr superspinars

    SciTech Connect (OSTI)

    Schee, Jan; Stuchlk, Zdenek E-mail: zdenek.stuchlik@fpf.slu.cz

    2013-04-01

    String Theory suggests existence of primordial Kerr superspinars, extremely compact objects with external spacetime described by the Kerr naked singularity geometry. The primordial Kerr superspinars have to be converted to a near-extreme black hole due to accretion, but they could survive to the era of highly redshifted quasars. We study the shape of the profiled spectral lines generated by radiating rings or the innermost parts of Keplerian discs orbiting the Kerr superspinars. Influence of the superspinar surface location on the profiled lines is also considered. We demonstrate strong difference of the character of the profiled lines generated by radiating rings for all values of the superspinar spin and all values of the inclination angles of the observer when compared to those generated in the field of Kerr black holes. For small and mediate inclination angles there are large quantitative differences in the extension and position of the lines. For large inclination angles even strong qualitative difference appears as the profiled lines have a clear doubled character. The smaller, redshifted region of the profiled line is related to the photons reaching the regions near the superspinar surface. Strong differences are obtained also for profiled lines generated by the innermost parts of Keplerian discs especially in the shape of the line. The influence of the superspinar surface location is reflected in the intermediate parts of the the profiled lines. The line profiles can give a clear signature of the presence of a Kerr superspinar and in principle enable estimates of its surface location since the signatures of the superspinar surface location are of different character as those corresponding to the presence of the black hole horizon.

  8. Thermal Properties of Starch From New Corn Lines as Impacted by Environment and During Line Development

    SciTech Connect (OSTI)

    Elizabeth M. Lenihan

    2003-12-12

    The objectives of this research were to further characterize exotic by adapted corn inbreds by studying the impact of environment on their starch thermal properties, and investigating the development of starch thermal properties during kernel maturation by using differential scanning calorimetry (DSC). A method to expedite identification of unusual starch thermal traits was investigated by examining five corn kernels at a time, instead of one kernel, which the previous screening methods used. Corn lines with known thermal functions were blended with background starch (control) in ratios of unique starch to control starch, and analyzed by using DSC. Control starch was representative of typical corn starch. The values for each ratio within a mutant type were unique ({alpha} < 0.01) for most DSC measurements. These results supported the five-kernel method for rapidly screening large amounts of corn germplasm to identify unusual starch traits. The effects of 5 growing locations on starch thermal properties from exotic by adapted corn and Corn Belt lines were studied using DSC. The warmest location, Missouri, generally produced starch with greater gelatinization onset temperature (T{sub oG}), narrower range of gelatinization (R{sub G}), and greater enthalpy of gelatinization ({Delta}H{sub G}). The coolest location, Illinois, generally resulted in starch with lower T{sub oG}, wider R{sub G}, and lower {Delta}H{sub G}. Starch from the Ames 1 farm had thermal properties similar to those of Illinois, whereas starch from the Ames 2 farm had thermal properties similar to those of Missouri. The temperature at Ames 2 may have been warmer since it was located near a river; however, soil type and quality also were different. Final corn starch structure and function change during development and maturity. Thus, the changes in starch thermal properties during 5 stages of endosperm development from exotic by adapted corn and Corn Belt lines at two locations were studied by using DSC. The T{sub oG} tended to decrease during maturation of the kernel, whereas the {Delta}H{sub G} tended not to change. Retrogradation parameters did not vary greatly among days after pollination (DAP) and between locations. Genotypes were affected differently by environments and significant interactions were found between genotype, environment,and DAP.

  9. Plains and Eastern Clean Line Transmission Line: Federal Register Notice, Volume 80, No. 81- April 28, 2015

    Broader source: Energy.gov [DOE]

    In December 2014, DOE requested additional information from Clean Line Energy Partners, LLC to supplement and update its original Plains and Eastern Clean Line application. The updated Part 2 application and other documentation are now available for a 45-day public comment period.

  10. Laboratory Measurements of White Dwarf Photospheric Spectral Lines. Hβ

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Falcon, Ross Edward; Sandia National Lab.; Rochau, Gregory A.; Bailey, James E.; Gomez, Thomas; Sandia National Lab.; Montgomery, Michael Houston; Winget, Donald E; Nagayama, Taisuke

    2015-06-18

    We spectroscopically measure multiple hydrogen Balmer line profiles from laboratory plasmas to investigate the theoretical line profiles used in white dwarf (WD) atmosphere models. X-ray radiation produced at the Z Pulsed Power Facility at Sandia National Laboratories initiates plasma formation in a hydrogen-filled gas cell, replicating WD photospheric conditions. We also present time-resolved measurements of Hβ and fit this line using different theoretical line profiles to diagnose electron density, ne, and n = 2 level population, n2. Aided by synthetic tests, we characterize the validity of our diagnostic method for this experimental platform. During a single experiment, we infer amore » continuous range of electron densities increasing from ne ~ 4 to ~30 × 1016 cm-3 throughout a 120-ns evolution of our plasma. Also, we observe n2 to be initially elevated with respect to local thermodynamic equilibrium (LTE); it then equilibrates within ~55 ns to become consistent with LTE. This also supports our electron-temperature determination of Te ~ 1.3 eV (~15,000 K) after this time. At ne≲ 1017 cm-3, we find that computer-simulation-based line-profile calculations provide better fits (lower reduced χ2) than the line profiles currently used in the WD astronomy community. The inferred conditions, however, are in good quantitative agreement. This work establishes an experimental foundation for the future investigation of relative shapes and strengths between different hydrogen Balmer lines.« less

  11. Applying a Modified Triad Approach to Investigate Wastewater lines

    SciTech Connect (OSTI)

    Pawlowicz, R.; Urizar, L.; Blanchard, S.; Jacobsen, K.; Scholfield, J.

    2006-07-01

    Approximately 20 miles of wastewater lines are below grade at an active military Base. This piping network feeds or fed domestic or industrial wastewater treatment plants on the Base. Past wastewater line investigations indicated potential contaminant releases to soil and groundwater. Further environmental assessment was recommended to characterize the lines because of possible releases. A Remedial Investigation (RI) using random sampling or use of sampling points spaced at predetermined distances along the entire length of the wastewater lines, however, would be inefficient and cost prohibitive. To accomplish RI goals efficiently and within budget, a modified Triad approach was used to design a defensible sampling and analysis plan and perform the investigation. The RI task was successfully executed and resulted in a reduced fieldwork schedule, and sampling and analytical costs. Results indicated that no major releases occurred at the biased sampling points. It was reasonably extrapolated that since releases did not occur at the most likely locations, then the entire length of a particular wastewater line segment was unlikely to have contaminated soil or groundwater and was recommended for no further action. A determination of no further action was recommended for the majority of the waste lines after completing the investigation. The modified Triad approach was successful and a similar approach could be applied to investigate wastewater lines on other United States Department of Defense or Department of Energy facilities. (authors)

  12. Methods and apparatus for reducing corrosion in refractory linings

    DOE Patents [OSTI]

    Poeppel, Roger B.; Greenberg, Sherman; Diercks, Dwight R.

    1987-01-01

    Methods and apparatus are provided for reducing corrosion in a refractory lining of a liquid-containing vessel used in direct steelmaking processes. The vessel operates at between about 1600.degree. C. and about 1800.degree. C. and an oxygen partial pressure of about 10.sup.-12 atmospheres, creating slag which is rich in FeO. The refractory lining includes a significant level of chromium oxide (Cr.sub.2 O.sub.3), and has small interconnected pores which may be filled with a gas mixture having a higher total pressure and oxygen partial pressure than the total pressure and oxygen partial pressure associted with the liquid against the lining of the vessel. The gas mixture is forced through the pores of the lining so that the pores are continuously filled with the mixture. In this manner, the gas mixture creates a blanket which increases the oxygen partial pressure at the lining enough to maintain the chromium in the lining in a selected valence state in which the chromium has decreased solubility in the FeO slag, thereby reducing corrosion by the FeO and increasing the useful life of the refractory lining.

  13. Phase II beam lines at the National Synchrotron Light Source

    SciTech Connect (OSTI)

    Thomlinson, W.

    1984-06-01

    The expansion of the National Synchrotron Light Source has been funded by the US Department of Energy. The Phase II program consists of both increased conventional facilities and six new beam lines. In this paper, an overview of the six beam lines which will be constructed during Phase II is presented. For five of the lines special radiation sources are necessary and the designs of four of the devices are complete. The relevant parameters of the insertion devices under construction and development are presented.

  14. Phone Numbers for Beam Lines and Other Services | Stanford Synchrotron

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Radiation Lightsource Phone Numbers for Beam Lines and Other Services The local area code for SSRL is 650. All numbers listed below should be dialed as 650-926-xxxx from other area codes. When calling an onsite location from within SSRL simply dial the 4-digit extension. When calling an offsite number within the 650 area code dial, dial 9 plus the 7-digit number. To call a number in another area code dial 9-1-area code - phone number. Beam Lines Beam Line Extension 1-4 5214 1-5 5215 2-1 5221

  15. CX-011183: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Line Upgrade on Bonneville Power Administration’s Walla Walla-Pendleton Number 1 Transmission Line CX(s) Applied: B1.3 Date: 08/30/2013 Location(s): Washington, Oregon Offices(s): Bonneville Power Administration

  16. CX-011717: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Line 3002 and 3002A Electrical Transmission Line Reconductoring Project CX(s) Applied: B2.5 Date: 05/22/2013 Location(s): Missouri, Missouri Offices(s): Southwestern Power Administration

  17. CX-011996: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Line Tap Construction on the East Ellensburg Tap to Columbia-Ellensburg Transmission Line CX(s) Applied: B4.6 Date: 04/11/2014 Location(s): Washington, Washington Offices(s): Bonneville Power Administration

  18. Polymer delineation system. [Patent application: traffic lane lines

    DOE Patents [OSTI]

    Woolman, S.; Steinberg, M.

    1975-06-24

    A delineation system (traffic lane lines) for highways is described in which polymerizable substances are applied to existing or newly prepared highway pavements. The substances would contain a suitable pigment and may incorporate reflective elements.

  19. Erratum: ''Titanium and germanium lined hohlraums and halfraums...

    Office of Scientific and Technical Information (OSTI)

    Title: Erratum: ''Titanium and germanium lined hohlraums and halfraums as multi-keV x-ray radiators'' Phys. Plasmas 16, 052704 (2009) No abstract prepared. Authors: Girard, F. ; ...

  20. Titanium and germanium lined hohlraums and halfraums as multi...

    Office of Scientific and Technical Information (OSTI)

    Title: Titanium and germanium lined hohlraums and halfraums as multi-keV X-ray radiators Authors: Girard, F ; Primout, M ; Fournier, K B ; Villette, B ; Stemmler, P ; Jacquet, L ; ...

  1. Internal-integral sodium return line for sodium heat engine

    DOE Patents [OSTI]

    Hunt, Thomas K.

    1985-01-01

    A thermoelectric generator device which converts heat energy to electrical energy. An alkali metal is used with a solid electrolyte and a portion of the return line for the alkali metal is located within the generator vacuum space.

  2. Libby (FEC)-Troy 115kV Line Rebuild

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    of McNary Group 2 - Big Eddy to Knight The Big Eddy - Knight 500 kV line and new substation (WOMR Group 2) project is one of five projects recommended out of the 2008 Cluster...

  3. Titanium and germanium lined hohlraums and halfraums as multi...

    Office of Scientific and Technical Information (OSTI)

    Titanium and germanium lined hohlraums and halfraums as multi-keV X-ray radiators Citation ... You are accessing a document from the Department of Energy's (DOE) SciTech Connect. This ...

  4. EIS-0106: Great Falls-Conrad Transmission Line Project, Montana

    Broader source: Energy.gov [DOE]

    The Western Area Power Administration prepared this EIS to evaluate the environmental impacts of the construction and operation of a 230-kilovolt transmission line from Great Falls, Montana, to Conrad, Montana.

  5. Using Weather Data to Improve Capacity of Existing Power Lines

    Broader source: Energy.gov [DOE]

    When it comes to increasing the efficiency of 160,000 miles of U.S. high-voltage transmission lines, the answer might be blowing in the wind.

  6. Presentation title: This can be up to 2 lines

    U.S. Energy Information Administration (EIA) Indexed Site

    ... 2010 2011 2012 2013 2014 2015 change from prior year forecast Source: Short-Term Energy Outlook, April 2015 16 2015 Summer Fuels Outlook Dashed line represents prior 10-year ...

  7. Presentation title: This can be up to 2 lines

    U.S. Energy Information Administration (EIA) Indexed Site

    ... 2009 2010 2011 2012 2013 2014 change from prior year Forecast Source: Short-Term Energy Outlook, April 2014 15 2014 Summer Fuels Outlook Dashed line represents prior 10-year ...

  8. Wireless Sensor Network for Electric Transmission Line Monitoring

    SciTech Connect (OSTI)

    Alphenaar, Bruce

    2009-06-30

    Generally, federal agencies tasked to oversee power grid reliability are dependent on data from grid infrastructure owners and operators in order to obtain a basic level of situational awareness. Since there are many owners and operators involved in the day-to-day functioning of the power grid, the task of accessing, aggregating and analyzing grid information from these sources is not a trivial one. Seemingly basic tasks such as synchronizing data timestamps between many different data providers and sources can be difficult as evidenced during the post-event analysis of the August 2003 blackout. In this project we investigate the efficacy and cost effectiveness of deploying a network of wireless power line monitoring devices as a method of independently monitoring key parts of the power grid as a complement to the data which is currently available to federal agencies from grid system operators. Such a network is modeled on proprietary power line monitoring technologies and networks invented, developed and deployed by Genscape, a Louisville, Kentucky based real-time energy information provider. Genscape measures transmission line power flow using measurements of electromagnetic fields under overhead high voltage transmission power lines in the United States and Europe. Opportunities for optimization of the commercial power line monitoring technology were investigated in this project to enable lower power consumption, lower cost and improvements to measurement methodologies. These optimizations were performed in order to better enable the use of wireless transmission line monitors in large network deployments (perhaps covering several thousand power lines) for federal situational awareness needs. Power consumption and cost reduction were addressed by developing a power line monitor using a low power, low cost wireless telemetry platform known as the ''Mote''. Motes were first developed as smart sensor nodes in wireless mesh networking applications. On such a platform, it has been demonstrated in this project that wireless monitoring units can effectively deliver real-time transmission line power flow information for less than $500 per monitor. The data delivered by such a monitor has during the course of the project been integrated with a national grid situational awareness visualization platform developed by Oak Ridge National Laboratory. Novel vibration energy scavenging methods based on piezoelectric cantilevers were also developed as a proposed method to power such monitors, with a goal of further cost reduction and large-scale deployment. Scavenging methods developed during the project resulted in 50% greater power output than conventional cantilever-based vibrational energy scavenging devices typically used to power smart sensor nodes. Lastly, enhanced and new methods for electromagnetic field sensing using multi-axis magnetometers and infrared reflectometry were investigated for potential monitoring applications in situations with a high density of power lines or high levels of background 60 Hz noise in order to isolate power lines of interest from other power lines in close proximity. The goal of this project was to investigate and demonstrate the feasibility of using small form factor, highly optimized, low cost, low power, non-contact, wireless electric transmission line monitors for delivery of real-time, independent power line monitoring for the US power grid. The project was divided into three main types of activity as follows; (1) Research into expanding the range of applications for non-contact power line monitoring to enable large scale low cost sensor network deployments (Tasks 1, 2); (2) Optimization of individual sensor hardware components to reduce size, cost and power consumption and testing in a pilot field study (Tasks 3,5); and (3) Demonstration of the feasibility of using the data from the network of power line monitors via a range of custom developed alerting and data visualization applications to deliver real-time information to federal agencies and others tasked with grid reliability (Tasks 6,8).

  9. Single transmission line interrogated multiple channel data acquisition system

    DOE Patents [OSTI]

    Fasching, George E. (Morgantown, WV); Keech, Jr., Thomas W. (Morgantown, WV)

    1980-01-01

    A single transmission line interrogated multiple channel data acquisition system is provided in which a plurality of remote station/sensor circuits each monitors a specific process variable and each transmits measurement values over a single transmission line to a master interrogating station when addressed by said master interrogating station. Typically, as many as 330 remote stations may be parallel connected to the transmission line which may exceed 7,000 feet. The interrogation rate is typically 330 stations/second. The master interrogating station samples each station according to a shared, charging transmit-receive cycle. All remote station address signals, all data signals from the remote stations/sensors and all power for all of the remote station/sensors are transmitted via a single continuous terminated coaxial cable. A means is provided for periodically and remotely calibrating all remote sensors for zero and span. A provision is available to remotely disconnect any selected sensor station from the main transmission line.

  10. Secretary Chu Thanks Utility Staff and Line Workers For Their...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    in the Wake of Hurricane Sandy Secretary Chu Thanks Utility Staff and Line Workers For Their Efforts to Restore Power in the Wake of Hurricane Sandy November 2, 2012 - 11:32am ...

  11. Microsoft Word - WIPP Water Line _2_ _2_ _2_

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Announces the Transfer of the WIPP Water Line to the City of Carlsbad CARLSBAD, N.M., June 18, 2009-The U.S. Department of Energy announced today that the Carlsbad Field Office...

  12. Microsoft Word - News Release -- Annual Reports now on line 2...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    5 15 BONNEVILLE POWER ADMINISTRATION Friday, Feb. 20, 2015 CONTACT: Mike Hansen, BPA 503-230-4328 or 503-230-5131 All 77 of BPA's annual reports now on line Portland, Ore. - The...

  13. Glosten Associates Tests Innovative High-Strength Mooring Lines...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    The TLPs use vertical high-tension mooring lines known as tendons to minimize vertical platform motions. Traditional TLPs use tendons comprised of tubular steel with universal-join...

  14. CRAD, NNSA- Evaluation Site Office Line Oversight Programs

    Broader source: Energy.gov [DOE]

    CRAD for Evaluation Site Office Line Oversight Programs. Criteria Review and Approach Documents (CRADs) that can be used to conduct a well-organized and thorough assessment of elements of safety and health programs.

  15. DOE Sustainability Reporting Open Line Help Call | Department...

    Broader source: Energy.gov (indexed) [DOE]

    November 18, 2015 2:00PM to 3:00PM EST The Sustainability Performance Office (SPO) sponsors open line help calls to assist DOE sites and national laboratories with the annual...

  16. DOE Sustainability Reporting Open Line Help Call | Department...

    Broader source: Energy.gov (indexed) [DOE]

    November 4, 2015 2:00PM to 3:00PM EST The Sustainability Performance Office (SPO) sponsors open line help calls to assist DOE sites and national laboratories with the annual...

  17. DOE Sustainability Reporting Open Line Help Call | Department...

    Broader source: Energy.gov (indexed) [DOE]

    October 28, 2015 2:00PM to 3:00PM EDT The Sustainability Performance Office (SPO) sponsors open line help calls to assist DOE sites and national laboratories with the annual...

  18. Soliton communication lines based on spectrally efficient modulation formats

    SciTech Connect (OSTI)

    Yushko, O V; Redyuk, A A

    2014-06-30

    We report the results of mathematical modelling of optical-signal propagation in soliton fibre-optic communication lines (FOCLs) based on spectrally efficient signal modulation formats. We have studied the influence of spontaneous emission noise, nonlinear distortions and FOCL length on the data transmission quality. We have compared the characteristics of a received optical signal for soliton and conventional dispersion compensating FOCLs. It is shown that in the presence of strong nonlinearity long-haul soliton FOCLs provide a higher data transmission performance, as well as allow higher order modulation formats to be used as compared to conventional communication lines. In the context of a coherent data transmission, soliton FOCLs allow the use of phase modulation with many levels, thereby increasing the spectral efficiency of the communication line. (optical communication lines)

  19. Grand Valley Rrl Pwr Line, Inc | Open Energy Information

    Open Energy Info (EERE)

    Valley Rrl Pwr Line, Inc Place: Colorado Website: www.gvp.org Twitter: @GVRuralPower Outage Hotline: 970-242-0040 Outage Map: www.gvp.orgcontentoutage-map References: EIA Form...

  20. DOE Sustainability Reporting Open Line Help Call | Department...

    Broader source: Energy.gov (indexed) [DOE]

    the SPO will be available on the call to answer specific questions with respect to Site Sustainability Plans (SSP) and the Consolidated Energy Data Report (CEDR). The Open Line...

  1. Guide to good practices for line and training manager activities

    SciTech Connect (OSTI)

    1998-06-01

    The purpose of this guide is to provide direction for line and training managers in carrying out their responsibilities for training and qualifying personnel and to verify that existing training activities are effective.

  2. EA-1891: Alvey-Fairview Transmission Line Rebuild Project, Oregon

    Broader source: Energy.gov [DOE]

    This EA evaluates the environmental impacts of a proposal to rebuild DOE’s Bonneville Power Administration’s Alvey-Fairview No. 1 230-kV transmission line located between Eugene, Oregon, and Coquille, Oregon.

  3. Metal Insertion in a Microporous Metal-Organic Framework Lined...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Metal Insertion in a Microporous Metal-Organic Framework Lined with 2,2 '-Bipyridine Previous Next List E. D. Bloch, D. Britt, C. Lee, C. J. Doonan, F. J. Uribe-Romo, H. Furukawa,...

  4. Federal Line Management Oversight of Department of Energy Nuclear...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    CURRENT DOE G 226.1-2A, Federal Line Management Oversight of Department of Energy Nuclear Facilities by David Weitzman Functional areas: Safety, Oversight The Guide was developed...

  5. Federal Line Management Oversight of Department of Energy Nuclear Facilities

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2013-04-04

    The Guide was developed in support of DOE O 226.1B to provide guidance that may be useful to DOE line management organizations in meeting the provisions of that order when applied to nuclear facilities.

  6. EIS-0507: Boardman-Hemingway Transmission Line, Oregon and Idaho

    Broader source: Energy.gov [DOE]

    The Bureau of Land Management and the U.S. Forest Service are preparing, with DOE’s Bonneville Power Administration (BPA) as a cooperating agency, an EIS that evaluates the potential environmental impacts of a proposal to construct about 305 miles of 500-kV transmission line from northeast Oregon to southwest Idaho. BPA’s proposed action is to partially fund part the transmission line.

  7. Federal Line Management Oversight of Department of Energy Nuclear Facilities

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2011-04-25

    The purpose of this Guide is to provide U.S. Department of Energy (DOE) line management with guidance that may be useful to them in effectively and efficiently implementing the requirements of DOE O 226.1B, Implementation of Department of Energy Oversight Policy, date April 25, 2011, as applied to Federal line management of hazard category 1, 2, and 3 nuclear facilities.

  8. Final Report - Integrated Glass Coating Manufacturing Line | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy Integrated Glass Coating Manufacturing Line Final Report - Integrated Glass Coating Manufacturing Line Awardee: Enki Technology Location: San Jose, CA Subprogram: Technology to Market Funding Program: Solar Manufacturing Technology 2 This project aims to enable US module manufacturers to coat glass with Enki's state of the art tunable functionalized AR coatings at the lowest possible cost and highest possible performance by encapsulating Enki's coating process in an integrated tool

  9. Jefferson Lab announces Fall Science Series line up | Jefferson Lab

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Fall Science Series line up Jefferson Lab announces Fall Science Series line up September 5, 2003 Jefferson Lab hosts Fall and Spring Science Series to engage the public in a range of current scientific topics. Guest speakers from across the nation are invited to the Lab to present their sometimes entertaining or thought-provoking, but always informative lectures or demonstrations. The Jefferson Lab Fall Science Series kicks off on Tuesday, October 7, with Michael Henchman, a chemistry professor

  10. Energy Department Announces Participation in Clean Line's Large-Scale

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy Transmission Project | Department of Energy Participation in Clean Line's Large-Scale Energy Transmission Project Energy Department Announces Participation in Clean Line's Large-Scale Energy Transmission Project March 25, 2016 - 12:59pm Addthis News Media Contact 202-586-4940 DOENews@hq.doe.gov WASHINGTON - Building on the Department of Energy's (DOE) ongoing efforts to modernize the grid and accelerate the deployment of renewable energy, today U.S. Secretary of Energy Ernest Moniz

  11. Gas insulated transmission line having tapered particle trapping ring

    DOE Patents [OSTI]

    Cookson, Alan H. (Pittsburgh, PA)

    1982-01-01

    A gas-insulated transmission line includes an outer sheath, an inner conductor, insulating supports and an insulating gas. A particle-trapping ring is secured to each insulating support, and it is comprised of a central portion and two tapered end portions. The ends of the particle trapping ring have a smaller diameter than the central portion of the ring, so as to enable the use of the particle trapping ring in a curved transmission line.

  12. The 2mrad Crossing Angle Interaction Region and Extraction Line

    SciTech Connect (OSTI)

    Appleby, R.; U., Manchester; Angal-Kalinin, D.; Dadoun, O.; Bambade, P.; Parker, B.; Keller, L.; Moffeit, K.; Nosochkov, Y.; Seryi, A.; Spencer, C.; Carter, J.; Royal Holloway, U.of London; Napoly, O.; /DAPNIA, Saclay

    2006-07-12

    A complete optics design for the 2mrad crossing angle interaction region and extraction line was presented at Snowmass 2005. Since this time, the design task force has been working on developing and improving the performance of the extraction line. The work has focused on optimizing the final doublet parameters and on reducing the power losses resulting from the disrupted beam transport. In this paper, the most recent status of the 2mrad layout and the corresponding performance are presented.

  13. Development of aerogel-lined targets for inertial confinement fusion

    Office of Scientific and Technical Information (OSTI)

    experiments (Thesis/Dissertation) | SciTech Connect Thesis/Dissertation: Development of aerogel-lined targets for inertial confinement fusion experiments Citation Details In-Document Search Title: Development of aerogel-lined targets for inertial confinement fusion experiments Authors: Braun, T Publication Date: 2013-03-05 OSTI Identifier: 1077169 Report Number(s): LLNL-TH-631353 DOE Contract Number: W-7405-ENG-48 Resource Type: Thesis/Dissertation Research Org: Lawrence Livermore National

  14. Corrugated outer sheath gas-insulated transmission line

    DOE Patents [OSTI]

    Kemeny, George A.; Cookson, Alan H.

    1981-01-01

    A gas-insulated transmission line includes two transmission line sections each of which are formed of a corrugated outer housing enclosing an inner high-voltage conductor disposed therein, with insulating support means supporting the inner conductor within the outer housing and an insulating gas providing electrical insulation therebetween. The outer housings in each section have smooth end sections at the longitudinal ends thereof which are joined together by joining means which provide for a sealing fixed joint.

  15. LLNL line-item construction projects Master Site Plan

    SciTech Connect (OSTI)

    1996-04-15

    This interim submittal is an updated 1996 overview of the Master Plan based on the 1995 LLNL Site Development Plan, illustrating the future land use considerations, and the locations of proposed facilities as documented through the line item development process and keyed to the summary table. The following components in addition to the line-item proposals remain key elements in the implementation strategy of the Master Plan: personnel migration, revitalization, space reduction, classified core contraction, utility systems, and environmental restoration.

  16. VERNIER CHRONOTRON UTILIZING AT LEAST TWO SHORTED DELAY LINES

    DOE Patents [OSTI]

    Rufer, R.P.

    1964-02-25

    An improved vernier chronotron featuring pulse-forming circuits of a ringing'' or back and forth'' oscillatory type is described. A delay line shorted at both ends together with transistor circuitry to introduce a pulse into that line and also to provide reinforcement of the pulse as it oscillates between the pulse-reflective extremities is provided. A transistorized coincidence circuit is also provided. Enhanced measurement of time intervals in the nanosecond range is afforded. (AEC)

  17. Device For Trapping Laser Pulses In An Optical Delay Line

    DOE Patents [OSTI]

    Yu, David U. L.; Bullock, Donald L.

    1997-12-23

    A device for maintaining a high-energy laser pulse within a recirculating optical delay line for a period time to optimize the interaction of the pulse with an electron beam pulse train comprising closely spaced electron micropulses. The delay line allows a single optical pulse to interact with many of the electron micropulses in a single electron beam macropulse in sequence and for the introduction of additional optical pulses to interact with the micropulses of additional electron beam macropulses. The device comprises a polarization-sensitive beam splitter for admitting an optical pulse to and ejecting it from the delay line according to its polarization state, a Pockels cell to control the polarization of the pulse within the delay line for the purpose of maintaining it within the delay line or ejecting it from the delay line, a pair of focusing mirrors positioned so that a collimated incoming optical pulse is focused by one of them to a focal point where the pulse interacts with the electron beam and then afterwards the pulse is recollimated by the second focusing mirror, and a timing device which synchronizes the introduction of the laser pulse into the optical delay line with the arrival of the electron macropulse at the delay line to ensure the interaction of the laser pulse with a prescribed number of electron micropulses in sequence. In a first embodiment of the invention, the principal optical elements are mounted with their axes collinear. In a second embodiment, all principal optical elements are mounted in the configuration of a ring.

  18. The effect of bright lines in environmental risk communication

    SciTech Connect (OSTI)

    Wilson, K.N.; Desvousges, W.H.; Smith, K.V.; Payne, J. )

    1993-01-01

    Bright lines in environmental risk communication refer to the specific levels at which an environmental risk becomes a serious health threat and action should be taken to mitigate its effects. This study examined the effect of bright lines'' in risk communication by emphasizing the radon exposure threshold level of 4 picocuries per liter. Specifically, the authors developed a computer-assisted interview containing bright-line versions of risk information. The bright-line version contained a range of possible radon levels, the corresponding number of estimated lung cancer cases, the relative health risk from radon compared to other health risks, and the EPA guidelines for mitigating levels above 4 picocuries in the home. The non-bright line version was identical to the bright-line version, except it did not include the EPA's mitigation recommendations. Effect measures included respondents' change in perceived risk after reading their materials, intended testing behavior, and advice to their neighbor for a specified radon level either above or below the 4 picocury threshold level. This paper discusses broader policy implications for designing effective risk communication programs.

  19. Optical emission line monitor with background observation and cancellation

    DOE Patents [OSTI]

    Goff, David R.; Notestein, John E.

    1986-01-01

    A fiber optics based optical emission line monitoring system is provided in which selected spectral emission lines, such as the sodium D-line emission in coal combustion, may be detected in the presence of interferring background or blackbody radiation with emissions much greater in intensity than that of the emission line being detected. A bifurcated fiber optic light guide is adapted at the end of one branch to view the combustion light which is guided to a first bandpass filter, adapted to the common trunk end of the fiber. A portion of the light is reflected back through the common trunk portion of the fiber to a second bandpass filter adapted to the end of the other branch of the fiber. The first filter bandpass is centered at a wavelength corresponding to the emission line to be detected with a bandwidth of about three nanometers (nm). The second filter is centered at the same wavelength but having a width of about 10 nm. First and second light detectors are located to view the light passing through the first and second filters respectively. Thus, the second detector is blind to the light corresponding to the emission line of interest detected by the first detector and the difference between the two detector outputs is uniquely indicative of the intensity of only the combustion flame emission of interest. This instrument can reduce the effects of interferring blackbody radiation by greater than 20 dB.

  20. Optical emission line monitor with background observation and cancellation

    DOE Patents [OSTI]

    Goff, D.R.; Notestein, J.E.

    1985-01-04

    A fiber optics based optical emission line monitoring system is provided in which selected spectral emission lines, such as the sodium D-line emission in coal combustion, may be detected in the presence of interferring background or blackbody radiation with emissions much greater in intensity than that of the emission line being detected. A bifurcated fiber optic light guide is adapted at the end of one branch to view the combustion light which is guided to a first bandpass filter, adapted to the common trunk end of the fiber. A portion of the light is reflected back through the common trunk portion of the fiber to a second bandpass filter adapted to the end of the other branch of the fiber. The first filter bandpass is centered at a wavelength corresponding to the emission line to be detected with a bandwidth of about three nanometers (nm). The second filter is centered at the same wavelength but having a width of about 10 nm. First and second light detectors are located to view the light passing through the first and second filters respectively. Thus, the second detector is blind to the light corresponding to the emission line of interest detected by the first detector and the difference between the two detector outputs is uniquely indicative of the intensity of only the combustion flame emission of interest. This instrument can reduce the effects of interfering blackbody radiation by greater than 20 dB.

  1. Investigation Of In-Line Monitoring Options At H Canyon/HB Line For Plutonium Oxide Production

    SciTech Connect (OSTI)

    Sexton, L.

    2015-10-14

    H Canyon and HB Line have a production goal of 1 MT per year of plutonium oxide feedstock for the MOX facility by FY17 (AFS-2 mission). In order to meet this goal, steps will need to be taken to improve processing efficiency. One concept for achieving this goal is to implement in-line process monitoring at key measurement points within the facilities. In-line monitoring during operations has the potential to increase throughput and efficiency while reducing costs associated with laboratory sample analysis. In the work reported here, we mapped the plutonium oxide process, identified key measurement points, investigated alternate technologies that could be used for in-line analysis, and initiated a throughput benefit analysis.

  2. HB-Line Plutonium Oxide Data Collection Strategy

    SciTech Connect (OSTI)

    Watkins, R.; Varble, J.; Jordan, J.

    2015-05-26

    HB-Line and H-Canyon will handle and process plutonium material to produce plutonium oxide for feed to the Mixed Oxide Fuel Fabrication Facility (MFFF). However, the plutonium oxide product will not be transferred to the MFFF directly from HB-Line until it is packaged into a qualified DOE-STD-3013-2012 container. In the interim, HB-Line will load plutonium oxide into an inner, filtered can. The inner can will be placed in a filtered bag, which will be loaded into a filtered outer can. The outer can will be loaded into a certified 9975 with getter assembly in compliance with onsite transportation requirement, for subsequent storage and transfer to the K-Area Complex (KAC). After DOE-STD-3013-2012 container packaging capabilities are established, the product will be returned to HB-Line to be packaged into a qualified DOE-STD-3013-2012 container. To support the transfer of plutonium oxide to KAC and then eventually to MFFF, various material and packaging data will have to be collected and retained. In addition, data from initial HB-Line processing operations will be needed to support future DOE-STD-3013-2012 qualification as amended by the HB-Line DOE Standard equivalency. As production increases, the volume of data to collect will increase. The HB-Line data collected will be in the form of paper copies and electronic media. Paper copy data will, at a minimum, consist of facility procedures, nonconformance reports (NCRs), and DCS print outs. Electronic data will be in the form of Adobe portable document formats (PDFs). Collecting all the required data for each plutonium oxide can will be no small effort for HB-Line, and will become more challenging once the maximum annual oxide production throughput is achieved due to the sheer volume of data to be collected. The majority of the data collected will be in the form of facility procedures, DCS print outs, and laboratory results. To facilitate complete collection of this data, a traveler form will be developed which identifies the required facility procedures, DCS print outs, and laboratory results needed to assemble a final data package for each HB-Line plutonium oxide interim oxide can. The data traveler may identify the specific values (data) required to be extracted from the collected facility procedures and DCS print outs. The data traveler may also identify associated criteria to be checked. Inevitably there will be procedure anomalies during the course of the HB-Line plutonium oxide campaign that will have to be addressed in a timely manner.

  3. Laboratory Measurements of White Dwarf Photospheric Spectral Lines. Hβ

    SciTech Connect (OSTI)

    Falcon, Ross Edward; Rochau, Gregory A.; Bailey, James E.; Gomez, Thomas; Montgomery, Michael Houston; Winget, Donald E; Nagayama, Taisuke

    2015-06-18

    We spectroscopically measure multiple hydrogen Balmer line profiles from laboratory plasmas to investigate the theoretical line profiles used in white dwarf (WD) atmosphere models. X-ray radiation produced at the Z Pulsed Power Facility at Sandia National Laboratories initiates plasma formation in a hydrogen-filled gas cell, replicating WD photospheric conditions. We also present time-resolved measurements of Hβ and fit this line using different theoretical line profiles to diagnose electron density, ne, and n = 2 level population, n2. Aided by synthetic tests, we characterize the validity of our diagnostic method for this experimental platform. During a single experiment, we infer a continuous range of electron densities increasing from ne ~ 4 to ~30 × 1016 cm-3 throughout a 120-ns evolution of our plasma. Also, we observe n2 to be initially elevated with respect to local thermodynamic equilibrium (LTE); it then equilibrates within ~55 ns to become consistent with LTE. This also supports our electron-temperature determination of Te ~ 1.3 eV (~15,000 K) after this time. At ne≲ 1017 cm-3, we find that computer-simulation-based line-profile calculations provide better fits (lower reduced χ2) than the line profiles currently used in the WD astronomy community. The inferred conditions, however, are in good quantitative agreement. This work establishes an experimental foundation for the future investigation of relative shapes and strengths between different hydrogen Balmer lines.

  4. HIGH-n HYDROGEN RECOMBINATION LINES FROM THE FIRST GALAXIES

    SciTech Connect (OSTI)

    Rule, E.; Loeb, A.; Strelnitski, V. S.

    2013-09-20

    We investigate the prospects of blind and targeted searches in the radio domain (10 MHz to 1 THz) for high-n hydrogen recombination lines from the first generation of galaxies, at z ?< 10. The expected optically thin spontaneous ?-line luminosities are calculated as a function of the absolute AB magnitude of a galaxy at 1500 . For a blind search, semi-empirical luminosity functions are used to calculate the number of galaxies whose expected flux densities exceed an assumed detectability threshold. Plots of the minimum sky area, within which at least one detectable galaxy is expected at a given observing frequency, in the fiducial instantaneous passband of 10{sup 4} km s{sup 1}, allow us to assess the blind search time necessary for detection by a given facility. We show that the chances for detection are the highest in the millimeter and submillimeter domains, but finding spontaneous emission in a blind search, especially from redshifts z >> 1, is a challenge even with powerful facilities, such as the Actama Large Millimeter/Submillimeter Array and Square Kilometre Array. The probability of success is higher for a targeted search of lines with principal quantum number n ? 10 in Lyman-break galaxies amplified by gravitational lensing. Detection of more than one hydrogen line in such a galaxy will allow for line identification and a precise determination of the galaxy's redshift.

  5. LineVISAR. A fringe-trace data analysis program

    SciTech Connect (OSTI)

    Furnish, Michael D.

    2014-02-01

    The line-imaging ORVIS or VISAR provides velocity as a function of position and time for a line on an experimental setup via a streak camera record of interference fringes. This document describes a Matlab-based program which guides the user through the process of converting these fringe data to a velocity surface. The data reduction is of the "fringe trace" type, wherein the changes in velocity at a given position on the line are calculated based on fringe motion past that point. The analyst must establish the fringe behavior up front, aided by peak-finding routines in the program. However, the later work of using fringe jumps to compensate for phase problems in other analysis techniques is greatly reduced. This program is not a standard GUI construction, and is prescriptive. At various points it saves the progress, allowing later restarts from those points.

  6. SSRL Beam Lines by Technique | Stanford Synchrotron Radiation Lightsource

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Beam Lines by Technique Beam Lines by Number | SPEAR3 Parameters Supported Technique(s) Beam Line X-ray Absorption Spectroscopy Biological x-ray absorption spectroscopy 2-2, 4-3, 7-3, 9-3, 14-3 Materials / catalysis / chemistry x-ray absorption spectroscopy 2-2, 4-1, 4-3, 11-2, 14-3 MEIS x-ray absorption spectroscopy 2-2, 4-1, 4-3, 11-2, 14-3 X-ray absorption spectroscopy imaging 2-2, 2-3, 6-2a, 10-2a,14-3 Single crystal x-ray absorption spectroscopy 9-3 Grazing incidence x-ray absorption

  7. Present state-of-the-art of transmission line icing

    SciTech Connect (OSTI)

    Pohlman, J.C.; Landers, P.

    1982-08-01

    Icing of overhead power lines is a serious problem for electric utilities. The loads resulting from iced conductors take many forms. Existing Codes and Guides offer little help in establishing adequate design criteria. Each transmission line designer must, therefore, rely heavily on intuitive judgment to set performance levels for transmission lines to be built within his particular service area. A special study was undertaken by author Pohlman in behalf of the Electric Power Research Institute (EPRI) to accomplish the following objectives: Improve the general understanding of the total problem; Sample utility perceptions and experience with the problem; Accumulate and review professional opinion on the subject; Inventory past and on-going research activities; Consolidate the above into a definition of the present state-of-the-art to define the need for future research.

  8. CONTINUOUS EXTRACTED BEAM IN THE AGS FAST EXTERNAL BEAM LINE.

    SciTech Connect (OSTI)

    GLENN,J.W.; TSOUPAS,N.; BROWN,K.A.; BIRYUKOV,V.M.

    2001-06-18

    A method to split off a few percent of the 6 x 10{sup 13} AGS beam delivered to the Slow External Beam (SEB) lines and send it down the Fast External Beam line (FEB) has been developed. The mission is to feed a counter experiment off the FEB that directly measures the neutrino mass using the muon storage ring. The use of normal thin septum splitters would have an excessive loss overhead and been optically difficult. The AGS Slow Extraction uses a third integer resonance with sextuple strength so the resonance width is a few percent of the beam width. This results in a low density tail which will be clipped by a bent crystal and deflected into the FEB channel. This clipping off of the tail should reduce losses in the SEB transport line. Details of modeled orbits, particle distribution and extraction trajectories into and out off the crystal will be given.

  9. Electric and magnetic field reduction by alternative transmission line options

    SciTech Connect (OSTI)

    Stewart, J.R. (Power Technologies, Inc., Schenectady, NY (United States)); Dale, S.J. (Oak Ridge National Lab., TN (United States)); Klein, K.W. (Energetics, Inc., Columbia, MD (United States))

    1991-01-01

    Ground level electric, and more recently magnetic, fields from overhead power transmission lines are increasingly important considerations in right of way specification, with states setting or planning to set edge of right of way limits. Research has been conducted in high phase order power transmission wherein six of twelve phases are used to transmit power in less physical space and with reduced electrical environmental effects than conventional designs. The first magnetic field testing, as reported in this paper, has verified predictive methods for determination of magnetic fields from high phase order lines. Based on these analytical methods, field profiles have been determined for lines of different phase order of comparable power capacity. Potential advantages of high phase order as a means of field mitigation are discussed. 10 refs., 12 figs., 3 tabs.

  10. EIS-0486: Plains & Eastern Clean Line Transmission Project

    Broader source: Energy.gov [DOE]

    This EIS will evaluate the potential environmental impacts of participating with Clean Line Energy Partners LLC (Clean Line) in the proposed Plains & Eastern Project. The proposed project would include an overhead ± 600 kilovolt (kV) high voltage direct current (HVDC) electric transmission system and associated facilities with the capacity to deliver approximately 3,500 megawatts (MW) primarily from renewable energy generation facilities in the Oklahoma Panhandle region to load-serving entities in the Mid-South and Southeast via an interconnection with the Tennessee Valley Authority (TVA).

  11. Erratum: ''Titanium and germanium lined hohlraums and halfraums as

    Office of Scientific and Technical Information (OSTI)

    multi-keV x-ray radiators'' [Phys. Plasmas 16, 052704 (2009)] (Journal Article) | SciTech Connect Erratum: ''Titanium and germanium lined hohlraums and halfraums as multi-keV x-ray radiators'' [Phys. Plasmas 16, 052704 (2009)] Citation Details In-Document Search Title: Erratum: ''Titanium and germanium lined hohlraums and halfraums as multi-keV x-ray radiators'' [Phys. Plasmas 16, 052704 (2009)] No abstract prepared. Authors: Girard, F. ; Primout, M. ; Villette, B. ; Stemmler, Ph. ; Jacquet,

  12. DOE - NNSA/NSO -- SiteLines Web Edition

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Calendar NTS Public Tours Factsheets Speakers Bureau Acronyms Mailing List Information Request Publishing Information Questions/Contact Masthead Archives FAQs/QUESTIONS SUBJECT INDEX SITEMAP SEARCH CONTACT US ABOUT US HELP ACRONYMS FOIA PRIVACY ACT WEBSITE POLICIES HOMEPAGE Home > Library > SiteLines U.S. DOE/NNSA - Nevada Site Office December 2007/January 2008 - Issue 129 A publication for all members of the NNSA/NSO family SiteLines looks back at 2007 2007 was a busy and productive year

  13. Characterization Plan for Soils Around Drain Line PLA-100115

    SciTech Connect (OSTI)

    D. Shanklin

    2006-05-24

    This Characterization Plan supports the Hazardous Waste Management Act/Resource Conservation and Recovery Act (HWMA/RCRA) closure of soils that may have been contaminated by releases from drain line PLA-100115, located within the Idaho Nuclear Technology and Engineering Center at the Idaho National Laboratory Site. The requirements to address the closure of soils contaminated by a potential release from this line in a characterization plan was identified in the "HWMA/RCRA Less Than 90-day Generator Closure Report for the VES-SFE-126."

  14. Self-monitoring high voltage transmission line suspension insulator

    DOE Patents [OSTI]

    Stemler, Gary E. (Vancouver, WA); Scott, Donald N. (Vancouver, WA)

    1981-01-01

    A high voltage transmission line suspension insulator (18 or 22) which monitors its own dielectric integrity. A dielectric rod (10) has one larger diameter end fitting attachable to a transmission line and another larger diameter end fitting attachable to a support tower. The rod is enclosed in a dielectric tube (14) which is hermetically sealed to the rod's end fittings such that a liquidtight space (20) is formed between the rod and the tube. A pressurized dielectric liquid is placed within that space. A discoloring dye placed within this space is used to detect the loss of the pressurized liquid.

  15. SiteLines Looks at NNSS Successes in 2011

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    SiteLines Looks at NNSS Successes in 2011 It was a big year at the Nevada National Security Site (NNSS) for the Nevada Site Office and its contractors. From returning to nuclear operations at the Joint Actinide Shock Physics Experimental Research (JASPER) facility to the formation of the National Center for Nuclear Security to the implementation of Governance Reform, the NNSS had one of its most successful years in FY2011. Now, with its sights set on 2012, SiteLines takes a closer look at the

  16. Phase Transitions above the Yrast Line in {sup 154}Dy

    SciTech Connect (OSTI)

    Ma, W. C.; Martin, V.; Khoo, T. L.; Lauritsen, T.; Egido, J. L.; Ahmad, I.; Bhattacharyya, P.; Carpenter, M. P.; Daly, P. J.; Grabowski, Z. W.

    2000-06-26

    Spectra of the E2 quasicontinuum {gamma} rays feeding different spin regions of the {sup 154}Dy yrast line have been extracted. These are compared with corresponding theoretical spectra obtained by numerical simulations based on temperature-dependent Hartree-Fock theory, with thermal shape fluctuations. In this manner, different regions of the spin-energy plane can be examined. The results support the predictions of a smeared-out phase transition at high spin above the yrast line. (c) 2000 The American Physical Society.

  17. Cast-stone sectors for lining bends in pipework

    SciTech Connect (OSTI)

    Chechulin, V.A.; Novikov, A.I.; Karpov, V.M.; Sotnik, A.A.; Sedyshev, B.L.

    1987-03-01

    The authors disclose an efficient method for lining the bends of pipelines used to deliver coal dust to the burners of coal-fired power plants or to transport coal slurries in mining and preparation enterprises. The method consists of melting a wear-resistant silicate compound and casting it in the form of rings whose increased width on the outboard side accounts for the angle of the bend when the rings are installed consecutively inside the pipe. Enhanced service life estimations and cost benefit analyses are given for pipe bends thus lined in both of the above applications.

  18. Dynamic Line Rating Oncor Electric Delivery Smart Grid Program

    SciTech Connect (OSTI)

    Johnson, Justin; Smith, Cale; Young, Mike; Donohoo, Ken; Owen, Ross; Clark, Eddit; Espejo, Raul; Aivaliotis, Sandy; Stelmak, Ron; Mohr, Ron; Barba, Cristian; Gonzalez, Guillermo; Malkin, Stuart; Dimitrova, Vessela; Ragsdale, Gary; Mitchem, Sean; Jeirath, Nakul; Loomis, Joe; Trevino, Gerardo; Syracuse, Steve; Hurst, Neil; Mereness, Matt; Johnson, Chad; Bivens, Carrie

    2013-05-04

    Electric transmission lines are the lifeline of the electric utility industry, delivering its product from source to consumer. This critical infrastructure is often constrained such that there is inadequate capacity on existing transmission lines to efficiently deliver the power to meet demand in certain areas or to transport energy from high-generation areas to high-consumption regions. When this happens, the cost of the energy rises; more costly sources of power are used to meet the demand or the system operates less reliably. These economic impacts are known as congestion, and they can amount to substantial dollars for any time frame of reference: hour, day or year. There are several solutions to the transmission constraint problem, including: construction of new generation, construction of new transmission facilities, rebuilding and reconductoring of existing transmission assets, and Dynamic Line Rating (DLR). All of these options except DLR are capital intensive, have long lead times and often experience strong public and regulatory opposition. The Smart Grid Demonstration Program (SGDP) project co-funded by the Department of Energy (DOE) and Oncor Electric Delivery Company developed and deployed the most extensive and advanced DLR installation to demonstrate that DLR technology is capable of resolving many transmission capacity constraint problems with a system that is reliable, safe and very cost competitive. The SGDP DLR deployment is the first application of DLR technology to feed transmission line real-time dynamic ratings directly into the system operation’s State Estimator and load dispatch program, which optimizes the matching of generation with load demand on a security, reliability and economic basis. The integrated Dynamic Line Rating (iDLR)1 collects transmission line parameters at remote locations on the lines, calculates the real-time line rating based on the equivalent conductor temperature, ambient temperature and influence of wind and solar radiation on the stringing section, transmits the data to the Transmission Energy Management System, validates its integrity and passes it on to Oncor and ERCOT (Electric Reliability Council of Texas) respective system operations. The iDLR system is automatic and transparent to ERCOT System Operations, i.e., it operates in parallel with all other system status telemetry collected through Supervisory Control and Data Acquisition (SCADA) employed across the company.

  19. Evaluation of Instrumentation and Dynamic Thermal Ratings for Overhead Lines

    SciTech Connect (OSTI)

    Phillips, A.

    2013-01-31

    In 2010, a project was initiated through a partnership between the Department of Energy (DOE) and the New York Power Authority (NYPA) to evaluate EPRI�s rating technology and instrumentation that can be used to monitor the thermal states of transmission lines and provide the required real-time data for real-time rating calculations. The project included the installation and maintenance of various instruments at three 230 kV line sites in northern New York. The instruments were monitored, and data collection and rating calculations were performed for about a three year period.

  20. Letter from Deputy Secretary Poneman to Clean Line Energy Regarding the

    Energy Savers [EERE]

    Plains & Eastern Clean Line Project Under Section 1222 of EPAct 2005 (April 5, 2012) | Department of Energy Letter from Deputy Secretary Poneman to Clean Line Energy Regarding the Plains & Eastern Clean Line Project Under Section 1222 of EPAct 2005 (April 5, 2012) Letter from Deputy Secretary Poneman to Clean Line Energy Regarding the Plains & Eastern Clean Line Project Under Section 1222 of EPAct 2005 (April 5, 2012) PDF icon Letter from Deputy Secretary Poneman to Clean Line

  1. Rapidity evolution of Wilson lines at the next-to-leading order

    SciTech Connect (OSTI)

    Balitsky, Ian; Chirilli, Giovanni

    2013-12-01

    At high energies particles move very fast so the proper degrees of freedom for the fast gluons moving along the straight lines are Wilson-line operators - infinite gauge factors ordered along the line. In the framework of operator expansion in Wilson lines the energy dependence of the amplitudes is determined by the rapidity evolution of Wilson lines. We present the next-to-leading order hierarchy of the evolution equations for Wilson-line operators.

  2. Plains & Eastern Clean Line Project Proposal for New or Upgraded

    Energy Savers [EERE]

    Transmission Line Projects Under Section 1222 of the Energy Policy Act of 2005 | Department of Energy Project Proposal for New or Upgraded Transmission Line Projects Under Section 1222 of the Energy Policy Act of 2005 Plains & Eastern Clean Line Project Proposal for New or Upgraded Transmission Line Projects Under Section 1222 of the Energy Policy Act of 2005 PDF icon Plains & Eastern Clean Line Project Proposal for New or Upgraded Transmission Line Projects Under Section 1222 of the

  3. EIS-0505: Vantage to Pomona Heights 230 kV Transmission Line...

    Energy Savers [EERE]

    Line Project; Yakima, Grant, Benton, and Kittitas Counties, Washington EIS-0505: Vantage to Pomona Heights 230 kV Transmission Line Project; Yakima, Grant, Benton, and Kittitas ...

  4. WAC - 468-34 - Utility Lines-Franchises and Permits | Open Energy...

    Open Energy Info (EERE)

    Lines-Franchises and PermitsLegal Abstract This section outlines the rules and procedures for granting franchises and permits for utility lines in the state. Published NA...

  5. EA-1972: Electric District 2 to Saguaro No. 2 Transmission Line...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    2: Electric District 2 to Saguaro No. 2 Transmission Line Rebuild; Pinal County, Arizona EA-1972: Electric District 2 to Saguaro No. 2 Transmission Line Rebuild; Pinal County, ...

  6. From:

    Energy Savers [EERE]

    server24.15@gmail.com To: Congestion Study Comments Subject: Energy Transmission Corridors Date: Sunday, September 21, 2014 9:31:28 AM I am opposed to the establishment of National Interest Energy Transmission Corridors (NIETC's) for the following reasons. First, the easements place an undo burden on landowners on and near the transmission lines. The compensation cannot begin to cover the all of the losses, tangible and intangible that landowners would suffer. If the corridors are approved the

  7. River Corridor Closure Contract Section J, Attachment J-15

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    by DOE-RL on 111010 (Reference 11-OOD- 0007) Yes DOE-0342, Rev. 0 Hanford Site Chronic Beryllium Disease Prevention Program (CBDPP) (as required by 10 CFR 850) Approved by...

  8. River Corridor Closure Contract Section J, Attachment J-13

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    3 Contract No. DE-AC06-08RL14655 A000 1 ATTACHMENT J-13 HANFORD SITE SERVICES Hanford Site Services are divided into three categories: Category 1: DOE will provide these Mandatory...

  9. Streamlining Transportation Corridor Planning Processess: Freight and Traffic Information

    SciTech Connect (OSTI)

    Franzese, Oscar

    2010-08-01

    The traffic investigation is one of the most important parts of an Environmental Impact Statement of projects involving the construction of new roadway facilities and/or the improvement of existing ones. The focus of the traffic analysis is on the determination of anticipated traffic flow characteristics of the proposed project, by the application of analytical methods that can be grouped under the umbrella of capacity analysis methodologies. In general, the main traffic parameter used in EISs to describe the quality of traffic flow is the Level of Service (LOS). The current state of the practice in terms of the traffic investigations for EISs has two main shortcomings. The first one is related to the information that is necessary to conduct the traffic analysis, and specifically to the lack of integration among the different transportation models and the sources of information that, in general, reside in GIS databases. A discussion of the benefits of integrating CRS&SI technologies and the transportation models used in the EIS traffic investigation is included. The second shortcoming is in the presentation of the results, both in terms of the appearance and formatting, as well as content. The presentation of traffic results (current and proposed) is discussed. This chapter also addresses the need of additional data, in terms of content and coverage. Regarding the former, other traffic parameters (e.g., delays) that are more meaningful to non-transportation experts than LOS, as well as additional information (e.g., freight flows) that can impact traffic conditions and safety are discussed. Spatial information technologies can decrease the negative effects of, and even eliminate, these shortcomings by making the relevant information that is input to the models more complete and readily available, and by providing the means to communicate the results in a more clear and efficient manner. The benefits that the application and use of CRS&SI technologies can provide to improve and expedite the traffic investigation part of the EIS process are presented.

  10. Cleaning Up the Hanford River Corridor and Improving Site Operations

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    activities: * Removed HC-17 (HC-17P, HC-17DC, HC-17SBB) in March * Completed HA-40F, in room 166, during the month of March * Completed HA-7A (in room 235-A3) and HC-4...

  11. River Corridor Closure Contract Section J, Attachment J-14

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Cost of Work Performed BCWS Budgeted Cost of Work Scheduled BHI Bechtel Hanford, Inc. BMS Business Management System BRC Budget and Reporting Classification CAS Cost Accounting...

  12. Hanford_story_poster_river_corridor_large.pdf

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

  13. UPS Ontario - Las Vegas LNG Corridor Extension Project: Bridging...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    0 DOE Vehicle Technologies and Hydrogen Programs Annual Merit Review and Peer Evaluation Meeting, June 7-11, 2010 -- Washington D.C. tiarravt047saito2010p...

  14. Washington Closure Hanford: Cleanup Progress Along Hanford's River Corridor

    Office of Environmental Management (EM)

    Department of Energy Want a Tax Credit for a Small Wind System? Be Sure It's Certified! Want a Tax Credit for a Small Wind System? Be Sure It's Certified! August 3, 2015 - 3:54pm Addthis A small wind turbine can produce enough energy to cover the electricity costs of the average American home. | Photo from Bergey Windpower Co., Inc.; NREL 13830 A small wind turbine can produce enough energy to cover the electricity costs of the average American home. | Photo from Bergey Windpower Co., Inc.;

  15. Cleanup Performance Prompts Contract Changes at Hanford's River Corridor

    Office of Environmental Management (EM)

    Cleaning Up Coal Cleaning Up Coal August 13, 2010 - 4:57pm Addthis Pete McGrail, a Laboratory Fellow at Pacific Northwest National Laboratory, is part of a team studying basalts to determine how carbon dioxide can be safely and permanently stored in these massive, deep underground rock formations. | Photo courtesy of Pacific Northwest National Laboratory. Pete McGrail, a Laboratory Fellow at Pacific Northwest National Laboratory, is part of a team studying basalts to determine how carbon dioxide

  16. Cleaning Up the Hanford River Corridor and Improving Site Operations

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    D&D - Fast Flux Test Facility Project 2,542 2,562 2,562 2,562 RL-0100 Richland Community and Regulatory Support 19,701 14,701 19,701 14,701 RL-TD-0100 Technology Development...

  17. Polychlorinated Biphenyl Presence in the Columbia River Corridor

    SciTech Connect (OSTI)

    R. M. Hermann

    2007-09-06

    The U. S. Department of Energy (DOE) is required by Comprehensive Environmental Response, Compensation, and Liability Act of 1980 regulations to develop a conceptual understanding of potential contaminant releases from the Hanford Site based on an evaluation of existing data and known historical practices. Polychlorinated biphenyls (PCBs) are one environmental contaminant potentially released through leaks, spills, or disposal. This document presents a summary of selected relevant existing information, including environmental studies and Hanford Site analytical data.

  18. River Corridor Closure Contract Section J, Attachment J-2 Contract...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    ... the Office of Inspector General CRD O 225.1A (Supplemented Rev. 0) Accident Investigations CRD O 226.1B Implementation of Department of Energy Oversight Policy CRD O 227.1 (Supp. ...

  19. Cleaning Up the Hanford River Corridor and Improving Site Operations

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Americium Recovery Facility (The "McCluskey Room") Presented to River and Plateau Committee Hanford Advisory Board John Silko U.S Department of Energy Richland Operations Office 1...

  20. Vermont Flood Hazard Area and River Corridor Protection Procedure...

    Open Energy Info (EERE)

    other jurisdictions on the regulatory measures necessary to avoid the endangerment of the health, safety, and welfare of the public and of riparian owners during flooding2; (5)...

  1. Cleaning Up the Hanford River Corridor and Improving Site Operations

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    7.4 Hanford Beryllium Work History BeCAP Product January 2015 2 1.7.4 Hanford Beryllium Work History BeCAP Product * Completed Beryllium Affected Worker History questionnaire *...

  2. I-5 Corridor Reinforcement Project Fact Sheet -- Keeping the...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Minnehaha Salmon Creek Camas Troutdale Troutdale Oak Park Filbert Rainier Vancouver Shipyard Clatskanie Trojan Thatcher Junction Rivergate Mill Plain Fishers Road Chelatchie...

  3. Cleaning Up the Hanford River Corridor and Improving Site Operations

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    * History and Regulatory Background * Permitting Background * Proposed Permit ... Administrative Code (WAC) regulatory requirements for public involvement (WAC ...

  4. River Corridor Closure Contract Section J, Attachment J-10

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    0 Contract No. DE-AC06-05RL14655 A000 1 SECTION J, ATTACHMENT J-10 RCC SUBCONTRACTS EXISTING AT TIME OF SOLICITATION The following subcontracts are/were available for assignment to the Contractor at the time Solicitation No. DE-RP06-04RL14655 was issued: End Date Current Value Description Supplier 02/28/05 $ 5,994,091 100 B/C AREA PIPELINES RCI ENVIRONMENTAL, INC. 10/31/06 $ 1,324,615 100-BC BURIAL GROUNDS AND REMAINING SITES FEDERAL ENGINEERS & CONSTRUCTORS 12/31/05 $ 3,400,000 116-N-1 CRIB

  5. River Corridor Closure Contract Section J, Attachment J-11

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    1 Contract No. DE-AC06-05RL14655 Modification 398 1 SECTION J, ATTACHMENT J-11 RCC FUNDING PROFILE In accordance with the Section B clause entitled Changes to Target Cost, Target Fee, and Schedule, the following is the projected funding profile for this Contract: Fiscal Year Annual Budget Authority ($1M)* Cumulative Budget Authority ($1M)* 2005** $ 107** $ 107 2006 183 290 2007 212 502 2008 232 734 2009 242 976 2010 297 1,273 2011 376 1,649 2012 302 1,951 2013 300 2,251 2014 280 2,531 2015 201

  6. River Corridor Closure Contract Section J, Attachment J-4

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    4 Contract No. DE-AC06-05RL14655 A000 SECTION J, ATTACHMENT J-4 SMALL BUSINESS SUBCONTRACTING PLAN The Washington Closure LLC Small Business Subcontracting Plan is on file at the Richland Operations Office and will be available at www.hanford.gov/rl The Washington Smalll Business Subcontracting Goals are as follows (as a percent of total subcontracting effort): Small Business (SB): 65.0% Small Disadvantaged Business: 22.0% Women-Owned SB: 13.0% HUBZone SB: 4.5% Veteran-Owned SB: 3.0%

  7. River Corridor Closure Contract Section J, Attachment J-5

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    5 Contract No. DE-AC06-05RL14655 A000 1 SECTION J, ATTACHMENT J-5 SMALL DISADVANTAGED BUSINESS PARTICIPATION PROGRAM TARGETS (A) Washington Closure NAICS Code Description of NAICS Major Group SDB Dollars Percentage** Subtotal (B) Subcontractors NAICS Code Description of NAICS Major Group SDB Dollars Percentage** 238 Specialty Trade Contractors 37,352,000 1.92 423 Merchant Wholesalers, Durable Goods* 43,104,000 2.21 541 Professional, scientific, & tech srvcs* 13,931,000 0.72 562 Waste mgt

  8. River Corridor Closure Contract Section J, Attachment J-6

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    6 Contract No. DE-AC06-05RL14655 Mod 459 1 ATTACHMENT J-6 ADVANCE AGREEMENT, PERSONNEL, AND RELATED COSTS This attachment will be prepared subsequent to Contract award pursuant to Clause H.15, Advance Understanding on Costs. The advance understandings listed below are subject to the specific limitations, conditions, and exclusions of subpart 31.2 of FAR as supplemented by Department of Energy Acquisition Regulation (DEAR) 931.2. TYPE OF COST ALLOWABILITY CLARIFICATION Beryllium Testing/Travel

  9. River Corridor Closure Contract Section J, Attachment J-8

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    8 Contract No. DE-AC06-05RL14655 A000 1 ATTACHMENT J-8 EMPLOYEE BENEFITS AND PENSION PLANS Pursuant to application employee benefit and pension requirements in Contract Section H, Special Contract Requirement, the Contractor shall annually submit the Report of Contractor Expenditures for Employee Supplemental Compensation

  10. Cleaning Up the Hanford River Corridor and Improving Site Operations

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Project Recent Accomplishments * Began removing sections of contaminated ventilation ducts and filters * Met FY2015 Key Performance Goal for dispositioning 31 pencil tank...

  11. 2009 River Corridor Closure Contractor Revegetation and Mitigation Monitoring Report

    SciTech Connect (OSTI)

    C. T. Lindsey; K. A. Gano; R. D. Teel

    2009-09-30

    This document details the results of revegetation and mitigation monitoring conducted in 2009, including 25 revegetation/restoration projects, one revegetation/mitigation project, and three bat mitigation projects.

  12. UPS Ontario - Las Vegas LNG Corridor Extension Project: Bridging...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    2 DOE Hydrogen and Fuel Cells Program and Vehicle Technologies Program Annual Merit Review and Peer Evaluation Meeting PDF icon arravt047tiwatkins2012o

  13. UPS Ontario - Las Vegas LNG Corridor Extension Project: Bridging...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    1 DOE Hydrogen and Fuel Cells Program, and Vehicle Technologies Program Annual Merit Review and Peer Evaluation PDF icon arravt047tisaito2011p

  14. Cleaning Up the Hanford River Corridor and Improving Site Operations

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Cleaning Up Coal Cleaning Up Coal August 13, 2010 - 4:57pm Addthis Pete McGrail, a Laboratory Fellow at Pacific Northwest National Laboratory, is part of a team studying basalts to determine how carbon dioxide can be safely and permanently stored in these massive, deep underground rock formations. | Photo courtesy of Pacific Northwest National Laboratory. Pete McGrail, a Laboratory Fellow at Pacific Northwest National Laboratory, is part of a team studying basalts to determine how carbon dioxide

  15. Cleaning Up the Hanford River Corridor and Improving Site Operations

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Stacy Charboneau, Manager February 3, 2016 2 3 Continue Cleanup of the Central Plateau * Plutonium Finishing Plant - Grouted Plutonium Reclamation Facility canyon floor - Working on last glove box (HA-9A) - Respiratory equipment Removal of high-hazard glove box in progress Grouting canyon floor in Plutonium Reclamation Facility 4 K Basin Sludge Transfer * External, independent review of cost and schedule completed * Plan for 2016 - Continue installing equipment in K West Reactor basin and annex

  16. Cleaning Up the Hanford River Corridor and Improving Site Operations

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    DOE Richland Operations Office June 2012 2 2012 HAB Membership Package * HAB Membership package is under review at DOE-HQ - 16 members and 22 alternatives are up for reappointment or appointment (8 new appointments) * Appointment letters will not be issued by June 8, 2012 - DOE is seeking approval for limited travel reimbursement to support July committee meetings. 3 Membership Diversity (November 2011 HAB Meeting) * DOE policy calls for ethnic and gender diversity in Environmental Management

  17. Cleaning Up the Hanford River Corridor and Improving Site Operations

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Doug Shoop, Deputy Manager April 13, 2016 2 3 Continue Cleanup of the Central Plateau * Plutonium Finishing Plant (PFP) - Completed last glove box (HA-9A) - Re-sequenced high-hazard work at PFP to focus on one project at a time using "Level B" suits - Grouted Plutonium Reclamation Facility canyon floor, began decontaminating walls Glove box HA-9A before (left) and after (right) Vacuuming "strongbacks" (left) and painting canyon floor (right) 4 K Basin Sludge Transfer * All

  18. West-wide Energy Corridors | Open Energy Information

    Open Energy Info (EERE)

    site to form a crust on the outside of the piles. * Cover storage piles at concrete batch plants, if they are sources of fugitive dust. Mitigation measures for clearing and...

  19. 2008 River Corridor Closure Contractor Revegetation and Mitigation Monitoring Report

    SciTech Connect (OSTI)

    C. T. Lindsey; K. A. Gano

    2008-09-30

    The purpose of this report is to document the status of revegetation projects and natural resources mitigation efforts that have been conducted for remediated waste sites and other activities associated with the Comprehensive Environmental Response, Compensation, and Liability Act cleanup of National Priorities List waste sites at Hanford. This report documents the results of revegetation and mitigation monitoring conducted in 2008 and includes 22 revegetation/restoration projects, one revegetation/mitigation project, and two bat habitat mitigation projects.

  20. 2007 River Corridor Closure Contractor Revegetation and Mitigation Monitoring Report

    SciTech Connect (OSTI)

    K. A. Gano; C. T. Lindsey

    2007-09-27

    The purpose of this report is to document the status of revegetation projects and natural resources mitigation efforts that have been conducted for remediated waste sites and other activities associated with the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) cleanup of National Priorities List waste sites at Hanford. This report documents the results of revegetation and mitigation monitoring conducted in 2007 and includes 11 revegetation/restoration projects, one revegetation/mitigation project, and 3 bat habitat mitigation projects.

  1. PHOENIX ENERGIZES LIGHT RAIL CORRIDOR WITH UPGRADES | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... network of energy professionals already in place, Energize Phoenix and APS built upon this foundation by offering contractor training and continuing education opportunities. ...

  2. Energy Transport Corridor Draft Environmental Impact Statement Available

    Energy Savers [EERE]

    Transformation in the U.S. Virgin Islands Energy Transformation in the U.S. Virgin Islands Click on the graphic to learn more the USVI's progress toward its 60% by 2025 goal. Click on the graphic to learn more the USVI's progress toward its 60% by 2025 goal. Location U.S. Virgin Islands Partners National Renewable Energy Laboratory Virgin Islands Water and Power Authority Virgin Islands Energy Office The U.S. Virgin Islands (USVI) worked with the U.S. Department of Energy (DOE) from 2009 to 2013

  3. EIS-0250: Notice of Preferred Nevada Rail Corridor

    Broader source: Energy.gov [DOE]

    Geologic Repository for the Disposal of Spent Nuclear Fuel and High-level Radioactive Waste at Yucca Mountain, Nye County, Nevada

  4. Vermont Flood Hazard Area and River Corridor Rule | Open Energy...

    Open Energy Info (EERE)

    compliance with National Flood Insurance Program (NFIP) criteria and enhance flood resilience. (b) Avoid and minimize the loss of life and property, the disruption of commerce,...

  5. EM Richland Operations Office Manager Reflects on River Corridor...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... We'll be looking at the success of this contract as we begin the process for the next round of big contracts at Hanford. 5. You're now looking ahead to the next phase of cleanup at ...

  6. EIS-0124: Conrad-Shelby Transmission Line Project, Montana

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy's Western Area Power Administration developed this statement to assess the environmental impact of adding a 230 kV transmission line between Conrad and Shelby, Montana and a new substation near Shelby to update the stressed electrical transmission system.

  7. EIS-0090: Fort Peck-Havre Transmission Line Project, Montana

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy’s Western Area Power Administration prepared this statement to assess the potential environmental and socioeconomic implications of its proposed action to construct and operate a 230kV transmission line from Fort Peck to Havre, Montana, with three intermediate interconnecting substations.

  8. Federal Line Management Oversight of Department of Energy Nuclear Facilities

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2014-04-14

    The Guide was developed in support of DOE O 226.1B to provide guidance that may be useful to DOE line management organizations in meeting the provisions of that order when applied to nuclear facilities. Supersedes DOE G 226.1-2

  9. A Laser-Wire System at the ATF Extraction Line

    SciTech Connect (OSTI)

    Boogert, S.T.; Blair, G.; Boorman, G.; Bosco, A.; Deacon, L.; Driouichi, C.; Karataev, P.; /Royal Holloway, U. of London; Kamps, T.; /BESSY, Berlin; Delerue, N.; Dixit, S.; Foster, B.; Gannaway, F.; Howell, D.F.; Qureshi, M.; Reichold, A.; Senanayake, R.; /Oxford U.; Aryshev, A.; Hayano, H.; Kubo, K.; Terunuma, N.; Urakawa, J.; /KEK, Tsukuba /Liverpool

    2007-02-12

    A new laser-wire (LW) system has been installed at the ATF extraction line at KEK, Tsukuba. The system aims at a micron-scale laser spot size and employs a mode-locked laser system. The purpose-built interaction chamber, light delivery optics, and lens systems are described, and the first results are presented.

  10. SNOW LINES AS PROBES OF TURBULENT DIFFUSION IN PROTOPLANETARY DISKS

    SciTech Connect (OSTI)

    Owen, James E. [Canadian Institute for Theoretical Astrophysics, 60 St George Street, Toronto, M5S 3H8, ON (Canada)

    2014-07-20

    Sharp chemical discontinuities can occur in protoplanetary disks, particularly at ''snow lines'' where a gas-phase species freezes out to form ice grains. Such sharp discontinuities will diffuse out due to the turbulence suspected to drive angular momentum transport in accretion disks. We demonstrate that the concentration gradientin the vicinity of the snow lineof a species present outside a snow line but destroyed inside is strongly sensitive to the level of turbulent diffusion (provided the chemical and transport timescales are decoupled) and provides a direct measurement of the radial ''Schmidt number'' (the ratio of the angular momentum transport to radial turbulent diffusion). Taking as an example the tracer species N{sub 2}H{sup +}, which is expected to be destroyed inside the CO snow line (as recently observed in TW Hya) we show that ALMA observations possess significant angular resolution to constrain the Schmidt number. Since different turbulent driving mechanisms predict different Schmidt numbers, a direct measurement of the Schmidt number in accretion disks would allow inferences to be made about the nature of the turbulence.

  11. Gamma ray lines from a universal extra dimension

    SciTech Connect (OSTI)

    Bertone, G.; Jackson, C. B.; Shaughnessy, G.; Tait, T. M.P.; Vallinotto, A.

    2012-03-01

    Indirect Dark Matter searches are based on the observation of secondary particles produced by the annihilation or decay of Dark Matter. Among them, gamma-rays are perhaps the most promising messengers, as they do not suffer deflection or absorption on Galactic scales, so their observation would directly reveal the position and the energy spectrum of the emitting source. Here, we study the detailed gamma-ray energy spectrum of Kaluza--Klein Dark Matter in a theory with 5 Universal Extra Dimensions. We focus in particular on the two body annihilation of Dark Matter particles into a photon and another particle, which produces monochromatic photons, resulting in a line in the energy spectrum of gamma rays. Previous calculations in the context of the five dimensional UED model have computed the line signal from annihilations into \\gamma \\gamma, but we extend these results to include \\gamma Z and \\gamma H final states. We find that these spectral lines are subdominant compared to the predicted \\gamma \\gamma signal, but they would be important as follow-up signals in the event of the observation of the \\gamma \\gamma line, in order to distinguish the 5d UED model from other theoretical scenarios.

  12. 241-AY-102 Leak Detection Pit Drain Line Inspection Report

    SciTech Connect (OSTI)

    Boomer, Kayle D.; Engeman, Jason K.; Gunter, Jason R.; Joslyn, Cameron C.; Vazquez, Brandon J.; Venetz, Theodore J.; Garfield, John S.

    2014-01-20

    This document provides a description of the design components, operational approach, and results from the Tank AY-102 leak detection pit drain piping visual inspection. To perform this inspection a custom robotic crawler with a deployment device was designed, built, and operated by IHI Southwest Technologies, Inc. for WRPS to inspect the 6-inch leak detection pit drain line.

  13. Operating Experience Level 3, Danger! Equipment Hits Overhead Lines

    Broader source: Energy.gov [DOE]

    OE-3 2016-01: This Operating Experience Level 3 (OE-3) document provides information about a safety concern related to workers and operations at Department of Energy (DOE) facilities where equipment has struck overhead communication cables and energized power lines.

  14. EIS-0499: Great Northern Transmission Line Project, Minnesota

    Broader source: Energy.gov [DOE]

    This EIS will evaluate the potential environmental impacts of a DOE proposal to grant a Presidential permit to Minnesota Power to construct, operate, maintain, and connect a new 883-megawatt electric transmission system across the U.S.-Canada border. The proposed 220 mile transmission line would cross the border near Roseau, Minnesota, and continue to Grand Rapids, Minnesota.

  15. High voltage gas insulated transmission line with continuous particle trapping

    DOE Patents [OSTI]

    Cookson, Alan H. (Pittsburgh, PA); Dale, Steinar J. (Monroeville, PA)

    1983-01-01

    This invention provides a novel high voltage gas insulated transmission line utilizing insulating supports spaced at intervals with snap-in means for supporting a continuous trapping apparatus and said trapping apparatus having perforations and cutouts to facilitate trapping of contaminating particles and system flexibility.

  16. Rotating superconductor magnet for producing rotating lobed magnetic field lines

    DOE Patents [OSTI]

    Hilal, Sadek K.; Sampson, William B.; Leonard, Edward F.

    1978-01-01

    This invention provides a rotating superconductor magnet for producing a rotating lobed magnetic field, comprising a cryostat; a superconducting magnet in the cryostat having a collar for producing a lobed magnetic field having oppositely directed adjacent field lines; rotatable support means for selectively rotating the superconductor magnet; and means for energizing the superconductor magnet.

  17. Southern Asia future plans feature long-distance lines

    SciTech Connect (OSTI)

    Not Available

    1991-11-01

    This paper reports that although pipe line mileage working, planned and under study has dipped slightly from 47,346 km (29,420 mi) to 44,853 km (27,871 mi), Southern Asia continues to hold a strong position for future projects with some of the most interesting programs in the international market. Two dramatic, long-distance natural gas transmission, gathering and lateral networks continue to hold the future pipe line construction spotlight in Southern Asia. The Association of South East Asian Nations (ASEAN) continues to study a 7,830 km (4,865 mi) gas transmission system. With an estimated cost of $10 billion, the system includes some 6,276 km (3,900 mi) of transmission lines, with 1,094 km (680 mi) offshore. Group members include Brunei, Indonesia, Malaysia, the Philippines, Singapore and Thailand. The second project, the Trans-Asian Pipeline System, involves 3,380 km (2,100 mi) of transmission lines from the Iran's Bandar Abbas gas field across Pakistan to a terminal at Calcutta, India.

  18. Replacement of alloy 800H superheated steam line

    SciTech Connect (OSTI)

    Barbier, R.A.; Bullock, J.W. [Sterling Chemicals, Texas City, TX (United States)

    1996-07-01

    Sterling Chemicals utilizes alloy 800HT (UNS N08811) piping for superheated steam service in its styrene dehydrogenation unit. An engineering project to replace these lines was recently completed. Material acquisition, shop fabrication, inspection requirements, and field erection will be highlighted in this paper.

  19. QER- Comment of Clean Line Energy Partners LLC

    Broader source: Energy.gov [DOE]

    Hello, Clean Line Energy Partners would like to submit the attached written comments to the QER task force, in conjunction with the verbal comments Jimmy Glotfelty provided today in Newark. Thank you for your consideration, and please let us know if you would like any additional information. Sincerely, Diana Rivera

  20. Safety and Health Regulatory and Policy Response Line- General Information

    Broader source: Energy.gov [DOE]

    The DOE Worker Safety and Health Standards Response Line, established in 1992, is a service that responds to questions DOE, DOE contractor, and DOE subcontractor personnel regarding DOE-adopted and -prescribed standards and directives. These responses may not represent official OSHA policies.