National Library of Energy BETA

Sample records for kv line planned

  1. EA-1665: Davis-Kingman 69-kV Transmission Line Rebuild Project, Arizona

    Broader source: Energy.gov [DOE]

    Western plans to rebuild a 26.6-mile-long portion of the existing 27.3-mile-long Davis–Kingman Tap 69-kV Transmission Line within the existing ROW in order to improve the reliability of the transmission service.

  2. ETM (Distribution Network Automation on 10 kV cable line stations...

    Open Energy Info (EERE)

    ETM (Distribution Network Automation on 10 kV cable line stations) (Smart Grid Project) Jump to: navigation, search Project Name ETM (Distribution Network Automation on 10 kV cable...

  3. EIS-0344: Grand Coulee-Bell 500 kV Transmission Line

    Broader source: Energy.gov [DOE]

    This EIS analyzes DOE's proposed action for the construction and operation of the proposed Grand Coulee-Bell 500-kV Transmission Line Project.

  4. Marys Lake 69/115-kV transmission line upgrade and substation expansion projects

    SciTech Connect (OSTI)

    NONE

    1996-05-01

    Western Area Power Administration (Western) and the Platte River Power Authority (Platte River) propose to upgrade portions of the existing electric transmission and substation system that serves the Town of Estes Park, Colorado. The existing transmission lines between the Estes Power Plant Switchyard and the Marys Lake Substation include a 115,000 volt (115-kV) line and 69,000 volt (69-kV) line. Approximately one mile is a double-circuit 115/69-kV line on steel lattice structures, and approximately two miles consists of separate single-circuit 115-kV and a 69-kV lines, constructed on wood H-Frame structures. Both lines were constructed in 1951 by the US Bureau of Reclamation. The existing transmission lines are on rights-of-way (ROW) that vary from 75 feet to 120 feet and are owned by Western. There are 48 landowners adjacent to the existing ROW. All of the houses were built adjacent to the existing ROW after the transmission lines were constructed. Upgrading the existing 69-kV transmission line between the Marys Lake Substation and the Estes Power Plant Switchyard to 115-kV and expanding the Marys Lake Substation was identified as the most effective way in which to improve electric service to Estes Park. The primary purpose and need of the proposed project is to improve the reliability of electric service to the Town of Estes Park. Lack of reliability has been a historical concern, and reliability will always be less than desired until physical improvements are made to the electrical facilities serving Estes Park.

  5. EIS-0107: Mead-Phoenix +500-kV Direct Current Transmission Line

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy’s Western Area Power Administration (WAPA) prepared this statement to analyze the potential environmental and socioeconomic impacts arising from WAPA and regional project sponsors’ proposal to construct a 500 kilovolt (kV) alternating current (AC) transmission line with the capability to be upgraded later to 500kV direct current (DC), connecting the Westwing Substation, located north of Phoenix, Arizona, with a new McCullough II Substation, located approximately 14 miles west of Boulder City, Nevada. This statement modifies a previously prepared federal statement from which the participants' election to proceed had not occurred at the time this statement was prepared.

  6. Sidney-North Yuma 230-kV Transmission Line Project, Colorado and Nebraska

    SciTech Connect (OSTI)

    Not Available

    1991-06-01

    This report describes the need for a 230-kV overhead transmission line to supply power from Sidney, Nebraska to eastern Colorado. The alternative scenario compared to construction of the line is No Action. Rejected alternatives include underground lines and different routing paths, with a possible extension to the Sterling area. Both scenarios are evaluated for environmental effects, cost, and consequences for the eastern Colorado region. The proposed route is determined to be the environmentally preferred choice. 120 refs., 6 figs., 13 tabs. (MHB)

  7. Environmental assessment: Warren Air Force Base 115-kV transmission line, Cheyenne, Wyoming

    SciTech Connect (OSTI)

    Not Available

    1986-03-01

    The Western Area Power Administration (Western), is propsoing to construct a new electrical tranmission line and substation in southeastern Wyoming. This proposed line, called the Warren Air Force Base Tranmission Line, will supply power for Western's system to Francis E.Warren Air Force Base (F.E. Warren AFB) near Cheyenne. It would allow for increased tranmission capacity to the air base. F.E. Warren AFB currently is served electrically be Western via a 13.8-kv line. It is a wood-pole, double-circuit line without an overhead ground wire, which extends from Western's Cheyenne Substation, through an urban area, and onto the air base. The Cheyenne Substation is located on the south side of the city of Cheyenne. The electrical load on the base is increasing from 4 megawatts (MW) to 11 or 12 MW, an approximate three-fold increase. Voltage problems occasionally occur at the base due to the present electrial loads and to the age and inadequacy of the 13.8-kv line, which was placed in service in 1941. The existing line has served beyond its designed service life and requires replacement. Replacement would be necessary even without an increasing load. F.E. Warren AFB has several new and expanding programs, including additional housing, shopping centers, and the Peacekeeper Missile Program. Part of this expansion already has occured; the remainder is expected by early 1988. This expansion has created the need for additional electrical service. The present 13.8-kV line is not capable of supporting the additional load. 28 refs., 4 figs., 2 tabs.

  8. EIS-0505: Vantage to Pomona Heights 230 kV Transmission Line Project; Yakima, Grant, Benton, and Kittitas Counties, Washington

    Broader source: Energy.gov [DOE]

    The Bureau of Land Management is preparing, with DOE’s Bonneville Power Administration (BPA) as a cooperating agency, an EIS that evaluates the potential environmental impacts of a proposal to construct a 230-kV transmission line in Washington State. BPA’s proposed action is to interconnect the proposed transmission line to an existing BPA substation.

  9. Seasonal Patterns of Melatonin, Cortisol, and Progesterone Secretion in Female Lambs Raised Beneath a 500-kV Transmission Line.

    SciTech Connect (OSTI)

    Lee, Jack M.

    1992-06-01

    Although several kinds of biological effects of electric and magnetic fields have been reported from laboratory studies, few have been independently replicated. When this study was being planned, the suppression of nighttime melatonin in rodents was thought to represent one of the strongest known effects of these fields. The effect had been replicated by a single laboratory for 60-Hz electric fields, and by multiple laboratories for d-c magnetic fields. The primary objective of this study was to determine whether the effect of electric and magnetic fields on melatonin would also occur in sheep exposed to a high voltage transmission line. The specific hypothesis tested by this experiment was as follows: The electrical environment produced by a 60-Hz, 500-kV transmission line causes a depression in nocturnal melatonin in chronically exposed female lambs. This may mimic effects of pinealectomy or constant long-day photoperiods, thus delaying the onset of reproductive cycles. Results of the study do not provide evidence to support the hypothesis. Melatonin concentrations in the sheep exposed to the transmission line showed the normal pattern of low daytime and high nighttime serum levels. As compared to the control group, there were no statistically significant group differences in the mean amplitude, phase, or duration of the nighttime melatonin elevation.

  10. EA-1679: Grand Coulee's Third Powerplant 500-kV Transmission Line Replacement Project, Grant and Okanogon Counties, Washington

    Broader source: Energy.gov [DOE]

    This EA evaluates potential environmental impacts from the construction and operation of six new 500-kV overhead transmission lines to replace six existing underground lines at Grand Coulee Dam. DOE’s Bonneville Power Administration (BPA), a cooperating agency, was asked by the U. S. Department of the Interior’s Bureau of Reclamation to design and construct the proposed new transmission lines. A Finding of No Significant Impact was issued by BPA in December 2011.

  11. Big George to Carter Mountain 115-kV transmission line project, Park and Hot Springs Counties, Wyoming. Environmental Assessment

    SciTech Connect (OSTI)

    Not Available

    1994-02-01

    The Western Area Power Administration (Western) is proposing to rebuild, operate, and maintain a 115-kilovolt (kV) transmission line between the Big George and Carter Mountain Substations in northwest Wyoming (Park and Hot Springs Counties). This environmental assessment (EA) was prepared in compliance with the National Environmental Policy Act (NEPA) and the regulations of the Council on Environmental Quality (CEQ) and the Department of Energy (DOE). The existing Big George to Carter Mountain 69-kV transmission line was constructed in 1941 by the US Department of Interior, Bureau of Reclamation, with 1/0 copper conductor on wood-pole H-frame structures without an overhead ground wire. The line should be replaced because of the deteriorated condition of the wood-pole H-frame structures. Because the line lacks an overhead ground wire, it is subject to numerous outages caused by lightning. The line will be 54 years old in 1995, which is the target date for line replacement. The normal service life of a wood-pole line is 45 years. Under the No Action Alternative, no new transmission lines would be built in the project area. The existing 69-kV transmission line would continue to operate with routine maintenance, with no provisions made for replacement.

  12. Environmental Assessment of the Gering-Stegall 115-kV Transmission Line Consolidation Project, Scotts Bluff County, Nebraska

    SciTech Connect (OSTI)

    NONE

    1995-05-01

    The Department of Energy (DOE), Western Area Power Administration (Western) proposes to consolidate segments of two transmission lines near the Gering Substation in Gering, Nebraska. The transmission lines are both located in Scotts Bluff County, Nebraska. The transmission lines are both located in Scotts Bluff County, Nebraska, within the city of Gering. Presently, there are three parallel 115-kilovolt (kV) transmission lines on separate rights-of-way (ROW) that terminate at the Gering Substation. The project would include dismantling the Archer-Gering wood-pole transmission line and rebuilding the remaining two lines on single-pole steel double circuit structures. The project would consolidate the Gering-Stegall North and Gering-Stegall South 115-kV transmission lines on to one ROW for a 1.33-mile segment between the Gering Substation and a point west of the Gering Landfill. All existing wood-pole H-frame structures would be removed, and the Gering-Stegall North and South ROWs abandoned. Western is responsible for the design, construction, operation, and maintenance of the line. Western prepared an environmental assessment (EA) that analyzed the potential environmental impacts of the proposed construction, operation, and maintenance of the 115-kV transmission line consolidation. Based on the analyses in the EA, the DOE finds that the proposed action is not a major Federal action significantly affecting the quality of the human environment, within the meaning of the National Environmental Policy Act of 1969 (NEPA).

  13. EIS-0025: Miles City-New Underwood 230-kV Electrical Transmission Line, Montana, North Dakota, and South Dakota

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy’s Western Area Power Administration prepared this statement to assess the environmental and socioeconomic implications of its proposed action to construct a 3.28-mile, 230-kV transmission line between Miles City and Baker, Montana, Hettinger, North Dakota, and New Underwood, South Dakota, in Custer and Fallon Counties in Montana, Adams, Bowman, and Slope Counties in North Dakota and Meade, Pennington, and Perkins Counties in South Dakota.

  14. EIS-0005-FS: Bonneville Power Administration Proposed FY 1979 Program, Facility Location on Supplement, Southwest Oregon Area Service, Buckley-Summer Lake 500 kV Line, Supplemental

    Broader source: Energy.gov [DOE]

    This Bonneville Power Administration document assesses the environmental impacts of constructing transmission facilities, which will coordinate with the Midpoint-Malin 500-kV line to be constructed by the Pacific Power and Light (PP&L) Company. The proposed action includes the construction of the 1.56-mile Buckley-Summer Lake 500-kV transmission line; the proposed Buckley Substation near Maupin, Oregon; and the proposed Summer Lake Substation near Silver Lake, Oregon.

  15. Increasing the reliability of the shutdown of 500 - 750-kV overhead lines equipped with shunt reactors in an unsuccessful three-phase automatic repeated closure cycle

    SciTech Connect (OSTI)

    Kuz'micheva, K. I.; Merzlyakov, A. S.; Fokin, G. G. [JSC 'R and D Center at Federal Grid Company of the United Power System' (Russian Federation)

    2013-05-15

    The reasons for circuit-breaker failures during repeated disconnection of 500 - 750 kV overhead lines with shunt reactors in a cycle of unsuccessful three-phase automatic reconnection (TARC) are analyzed. Recommendations are made for increasing the operating reliability of power transmission lines with shunt reactors when there is unsuccessful reconnection.

  16. Big Eddy-Knight 500 kV line nears completion with Columbia River...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    mile of line. In the crossing, there are just three towers for 1.2 miles of line with the actual river crossing spanning nine-tenths of a mile. The Oregon suspension tower stands...

  17. EIS-0118: Proposed Eugene-Medford 500-kV Transmission Line

    Broader source: Energy.gov [DOE]

    The U.S. Department of Interior developed this statement to assess the environmental impact of a proposed 500-kilovolt transmission line linking Eugene and Medford, Oregon, that would cross through public lands. The Bonneville Power Administration (BPA) would provide service to the proposed line and is a cooperating agency in the statement. BPA adopted the EIS on 7/10/1985.

  18. EIS-0399: Montana Alberta Tie Ltd. (MATL) 230-KV Transmission Line

    Broader source: Energy.gov [DOE]

    DOE, jointly with the Montana Department of Environmental Quality (MDEQ), prepared an EIS that evaluated the potential environmental impacts of a proposed international transmission line that would cross the U.S.-Canada border in northwest Montana.

  19. Type A Accident Investigation Report on the June 25, 1997, Contractor Inspector Fatality on the Satsop-Aberdeen #2 & #3 230 kV Line

    Broader source: Energy.gov [DOE]

    On June 27, 1997, I established a Type-A Accident Investigation Board to investigate the June 25, 1997 fatal contractor accident which occurred on BPA?s Satsop-Aberdeen #2 and #3 230-kV transmission lines right-of-way.

  20. EIS-0103: New England/Hydro-Quebec 450-kV Direct Current Transmission Line Interconnection

    Broader source: Energy.gov [DOE]

    The Economic Regulatory Administration prepared this statement to evaluate the environmental impacts of the construction, maintenance, and operation of a 57-mile transmission line from Monroe, New Hampshire, to the U.S./Canadian border for the purpose of economic exchange of power and increased reliability. Phase 2 of this project is detailed in EIS-0129.

  1. EA-1551: Montana Alberta Tie Ltd. (MATL) 230-KV Transmission Line

    Broader source: Energy.gov [DOE]

    DOE started to prepare, jointly with the Montana Department of Environmental Quality (MDEQ), an EA that would also serve as a state EIS. The document would evaluate the potential environmental impacts of a proposed international transmission line that would cross the U.S.-Canada border in northwest Montana. Based on comments received on the DOE Draft EA/MDEQ Draft EIS, DOE cancelled preparation of the EA and announced preparation of DOE/EIS-0399 (of the same title).

  2. EIS-0301: NRG Energy Services, Inc., Arizona-Baja California 500 kV Transmission Line

    Broader source: Energy.gov [DOE]

    This EIS analyzes DOE's decision to approve NRG Energy, Inc. (NRG) for a Presidential permit to construct a 500,000-volt transmission line originating at the switchyard of the Palo Verde Nuclear Generating Station near Phoenix, Arizona, and extending approximately 177 miles to the southwest, where it would cross the United States (U.S.) border with Mexico in the vicinity of Calexico, California.

  3. EIS-0112: Rifle to San Juan 345-kV Transmission Line and Associated Facilities

    Broader source: Energy.gov [DOE]

    The U.S. Department of Agriculture - Rural Electrification Administration developed this statement to evaluate the environmental impacts of the Colorado-Ute Electric Association Inc. and the U.s. Department of Energy's Western Area Power Administration (WAPA) constructing and operating a 345-kilovolt transmission line from Rifle, Colorado, to the San Juan Generating Station near Farmington, New Mexico. WAPA served as a cooperating agency in the preparation of this statement and adopted it on 10/30/1984. WAPA assumed the lead role for project implementation after issuance of the final statement.

  4. Development of NS-TACSR with extremely suppressed aeolian noise and its application to 500 kV overhead transmission lines

    SciTech Connect (OSTI)

    Tsujimoto, K.; Furukawa, S. (Kansai Electric Power Co., Inc., Osaka (Japan)); Shimojima, K.; Yamamoto, K. (Hitachi Cable, Ltd., Hitachi (JP))

    1991-10-01

    Recently in Japan, with the unprecedented advance of residential area development in the suburbs of large cities, it has become quite difficult to secure the routes of EHV transmission lines from nuclear power plants in remote places to the suburbs of large cities, urging resolution of environmental problems related to transmission lines. In Japan, aerodynamic sound produced by conductors and insulators frequently caused noise problems. Having an opportunity of constructing a 500 kV transmission line through a residential are, we made a research to resolve this noise problem. This paper describes the characteristics of aeolian noise and preventive measures against it.

  5. Environmental Assessment for Central Power and Light Company`s proposed Military Highway-CFE tie 138/69-kV transmission line project Brownsville, Cameron County, Texas

    SciTech Connect (OSTI)

    Not Available

    1992-04-01

    Central Power and Light Company (CPL) intends to upgrade its existing transmission line ties with the Commision Federal de Electricidad (CFE) system in Mexico. CPL currently has a single 69-kilovolt (kV) transmission line in the Brownsville area which connects CPL`s system with the system of CFE. This existing line runs between the Brownsville Switching Station, located on Laredo Road in Brownsville, Cameron County, Texas, and an existing CFE 69-kV line at the Rusteberg Bend of the Rio Grande in Cameron County. Under current conditions of need, the existing 69-kV line does not possess sufficient capability to engage in appropriate power exchanges. Therefore, CPL is proposing to build a new line to link up with CFE. This proposed line would be a double-circuit line, which would (1) continue (on a slightly relocated route) the existing 69-kV tie from CPL`s Brownsville Switching Station to CFE`s facilities, and (2) add a 138-kV tie from the Military Highway Substation, located on Military Highway (US Highway 281), to CFE`s facilities. The proposed 138/69-kV line, which will be constructed and operated by CPL, will be built primarily on steel single-pole structures within an average 60-foot (ft) wide right-of-way (ROW). It will be approximately 6900--9200 ft (1.3--1.7 miles) in length, depending on the alternative route constructed.

  6. Ethan Burns (UNH) Anticipatory On-line Planning 1 / 22 Anticipatory On-line Planning

    E-Print Network [OSTI]

    Ruml, Wheeler

    Ethan Burns (UNH) Anticipatory On-line Planning ­ 1 / 22 Anticipatory On-line Planning Ethan Burns1 Formalization Hindsight Opt. Experiments Conclusion Ethan Burns (UNH) Anticipatory On-line Planning ­ 2 / 22'd s Contributions Formalization Hindsight Opt. Experiments Conclusion Ethan Burns (UNH) Anticipatory On

  7. Environmental Assessment and Finding of No Significant Impact: Curecanti-Lost Canyon 230-kV Transmission Line Reroute Project, Montrose County, Colorado

    SciTech Connect (OSTI)

    N /A

    2000-03-20

    The Department of Energy (DOE), Western Area Power Administration (Western) is proposing to reroute a section of the Curecanti-Lost Canyon 230-kilovolt (kV) transmission line, in Montrose County, Colorado. A portion of the transmission line, situated 11 miles southeast of Montrose, Colorado, crosses Waterdog Peak, an area of significant geologic surface activity, which is causing the transmission line's lattice steel towers to shift. This increases stress to structure hardware and conductors, and poses a threat to the integrity of the transmission system. Western proposes to relocate the lattice steel towers and line to a more geologically stable area. The existing section of transmission line and the proposed relocation route cross Bureau of Land Management and private land holdings.

  8. Heavy duty insulator assemblies for 500-kV bulk power transmission line with large diameter octagonalbundled conductor

    SciTech Connect (OSTI)

    Tsujimoto, K.; Hayase, I.; Hirai, J.; Inove, M.; Naito, K.; Yukino, T.

    1982-11-01

    This paper describes the design procedure and the results of field tests on mechanical performances of insulator assemblies newly developed to support octagonal-bundled conductors for 500-kV bulk power transmission. Taking account of conductor-motion-induced peak tensile load, fatigue, torsional torque and others, a successful design has been achieved in two prototype assemblies for such heavy mechanical duties as encountered during conductor galloping or swing. This has been proved throughout three years of the field tests.

  9. LLNL line-item construction projects Master Site Plan

    SciTech Connect (OSTI)

    1996-04-15

    This interim submittal is an updated 1996 overview of the Master Plan based on the 1995 LLNL Site Development Plan, illustrating the future land use considerations, and the locations of proposed facilities as documented through the line item development process and keyed to the summary table. The following components in addition to the line-item proposals remain key elements in the implementation strategy of the Master Plan: personnel migration, revitalization, space reduction, classified core contraction, utility systems, and environmental restoration.

  10. Characterization Plan for Soils Around Drain Line PLA-100115

    SciTech Connect (OSTI)

    D. Shanklin

    2006-05-24

    This Characterization Plan supports the Hazardous Waste Management Act/Resource Conservation and Recovery Act (HWMA/RCRA) closure of soils that may have been contaminated by releases from drain line PLA-100115, located within the Idaho Nuclear Technology and Engineering Center at the Idaho National Laboratory Site. The requirements to address the closure of soils contaminated by a potential release from this line in a characterization plan was identified in the "HWMA/RCRA Less Than 90-day Generator Closure Report for the VES-SFE-126."

  11. Type B Accident Investigation Board Report on the July 25, 1997, Contract Brush Cutter Injury on the Ashe-Marion #2 500 kV Line

    Broader source: Energy.gov [DOE]

    On July 25, 1997, at 1205 hours, a contract hand brush cutter was seriously injured when he felled a tree close to a Bonneville Power Administration energized transmission power line, located within a BPA transmission-line corridor.

  12. Draft environmental impact statement for construction and operation of the proposed Bangor Hydro-Electric Company`s second 345-kV transmission tie line to New Brunswick

    SciTech Connect (OSTI)

    1993-10-01

    This Draft Environmental Impact Statement (DEIS) was prepared by the US Department of Energy (US DOE). The proposed action is the issuance of Presidential Permit PP-89 by DOE to Bangor Hydro-Electric Company to construct and operate a new international transmission line interconnection to New Brunswick, Canada that would consist of an 83.8 mile (US portion), 345-kilovolt (kV) alternating current transmission line from the US-Canadian border at Baileyville, Maine to an existing substation at Orrington, Maine. The principal environmental impacts of the construction and operation of the transmission line would be incremental in nature and would include the conversion of forested uplands (mostly commercial timberlands) and wetlands to right-of-way (small trees, shrubs, and herbaceous vegetation). The proposed line would also result in localized minor to moderate visual impacts and would contribute a minor incremental increase in the exposure of some individuals to electromagnetic fields. This DEIS documents the purpose and need for the proposed action, describes the proposed action and alternatives considered and provides a comparison of the proposed and alternatives routes, and provides detailed information on analyses of the environmental consequences of the proposed action and alternatives, as well as mitigative measures to minimize impacts.

  13. Impact Mitigation and Monitoring of the BPA 500-kV Garrison-Taft Transmission Line : Effects on Elk Security and Hunter Opportunity, Final Report.

    SciTech Connect (OSTI)

    Canfield, Jodie E.

    1988-11-01

    This study was conducted by the Montana Department of Fish, Wildlife and Parks from 1984--1988 to assess the impacts of the Garrison-Taft segment of a 500-kV powerline on elk summer-fall habitat. Construction of the powerline began in 1983, and the powerline was energized in 1985. The Garrison-Taft powerline corridor crossed 251 km of mountainous terrain in western Montana; about 465 km of new roads were constructed to provide permanent access to the powerline towers. The objectives of the study were: (1) to monitor the effectiveness of mitigation measures, including timing restrictions on construction activities and road closures on newly-built access roads, and (2) to determine if opening previously-unroaded elk security habitats to hunters by powerline access roads affected elk habitat use, distribution, use of security areas, or elk harvest. In addition, both the potential for accelerated timber harvest in areas crossed by the powerline that would not have otherwise been logged because of marginal economics and lack of haul roads and the potential effect of powerline flashovers on future prescribed burning of elk winter-ranges were evaluated. 83 refs., 88 figs., 15 tabs.

  14. EIS-0365: Draft Environmental Impact Statement for the Imperial-Mexicali 230-kV Transmission Lines, EIS-0365 (May 2004)

    Broader source: Energy.gov [DOE]

    A U.S. Department of Energy (DOE) Presidential permit is required to construct an electric transmission line across the U.S. international border. On February 27, 2001, Baja California Power, Inc. ...

  15. Undersea line planned to transmit to an island

    SciTech Connect (OSTI)

    Not Available

    1993-08-09

    The electric utility serving Nantucket Island in Massachusetts, which until now has generated its own power, plans to lay 25 miles of transmission cable to connect with New England's mainland grid. The line will allow the utility to purchase less costly power and retire several old generators, improving both reliability and air quality on the island. Nantucket Electric Co. says the 33-Mw submarine link, costing at least $23 million, probably will connect with a line near the elbow on Cape Cod. The undersea cable will be as deep as 60 ft. Nantucket Electric plans to form a partnership within a few months with a mainland utility or private producer that would help finance the project and sell the power. The island utility has preliminary approval by the state Industrial Finance Agency for a tax-exempt bond issue to finance the cable, contingent on its finding a partner.

  16. EIS-0067: 230-kV International Transmission Line San Diego County, California to Tijuana, Mexico, San Diego Gas and Electric Company

    Broader source: Energy.gov [DOE]

    The Economic Regulatory Administration and the California Public Utilities Commission jointly prepared this EIS to evaluate the environmental impacts of the construction, maintenance and operation of a 10-mile, 230-kilovolt transmission line across the U.S./Mexico border for the purpose of economic exchange of power and increased reliability.

  17. EIS-0032: 500 kV International Transmission Line NSP-TR-1, Forbes, Minnesota to Manitoba, Canada, Northern States Power Company

    Broader source: Energy.gov [DOE]

    The Economic Regulatory Administration developed this EIS to evaluate the environmental impacts of a 500-kilovolt transmission line proposed by the Northern States Power Company to provide a transmission facility for the exchange of electrical energy between Canada and the United States.

  18. EA-2002: Right-of-Way Application for the Tucson-Apache 115-kV Transmission Line, Pima County, Arizona

    Broader source: Energy.gov [DOE]

    Western Area Power Administration (Western) and the Bureau of Indian Affairs (BIA), as joint lead agencies, prepared an EA that evaluates the potential environmental impacts of a proposal for BIA to grant Western a 150-foot right-of-way across tribal land along the existing Tucson-Apache Transmission Line to replace the previous 100-foot right-of-way, which has expired.

  19. EA-1899: Rerouting and Renovating of Estes-Flatiron Three Transmission Lines to Double Circuit 115-kV, Larimer County, Colorado

    Broader source: Energy.gov [DOE]

    DOE’s Western Area Power Administration started to prepare an EA to evaluate the environmental impacts of a proposal to reroute and renovate the Estes-Flatiron Three Transmission Lines in Larimer County, Colorado. Based on comments received during the scoping period, Western ended preparation of DOE/EA-1899 and announced its intent to prepare and environmental impact statement, DOE/EIS-0483.

  20. Southern Asia future plans feature long-distance lines

    SciTech Connect (OSTI)

    Not Available

    1991-11-01

    This paper reports that although pipe line mileage working, planned and under study has dipped slightly from 47,346 km (29,420 mi) to 44,853 km (27,871 mi), Southern Asia continues to hold a strong position for future projects with some of the most interesting programs in the international market. Two dramatic, long-distance natural gas transmission, gathering and lateral networks continue to hold the future pipe line construction spotlight in Southern Asia. The Association of South East Asian Nations (ASEAN) continues to study a 7,830 km (4,865 mi) gas transmission system. With an estimated cost of $10 billion, the system includes some 6,276 km (3,900 mi) of transmission lines, with 1,094 km (680 mi) offshore. Group members include Brunei, Indonesia, Malaysia, the Philippines, Singapore and Thailand. The second project, the Trans-Asian Pipeline System, involves 3,380 km (2,100 mi) of transmission lines from the Iran's Bandar Abbas gas field across Pakistan to a terminal at Calcutta, India.

  1. AC transmission system planning choosing lines from a discrete set

    E-Print Network [OSTI]

    Gilbertson, Eric W.

    2013-04-24

    Transmission system planning (TSP) is a difficult nonlinear optimization problem involving non-convex quadratic terms, as well as discrete variables. We extend prior results for linear relaxations, drawing on a preliminary ...

  2. Plains and Eastern Clean Line Transmission Line: Federal Register...

    Energy Savers [EERE]

    Clean Line project. The project would include an overhead 600-kilovolt (kv) high voltage, direct current electric transmission system and associated facilities with the capacity to...

  3. Proposed Project: Plains & Eastern Clean Line Transmission Line...

    Energy Savers [EERE]

    & Eastern Clean Line project (the proposed project) would include an overhead +- 600 kV direct current electric transmission system and associated facilities with the capacity to...

  4. Power Line Plan of Development Outline | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on QA:QAsource History ViewMayo, Maryland:NPIProtectio1975) |Texas:Pottawattamie County,River,Generating Inc Jump to:Line

  5. Algorithms for on-line aggregate production plan revision with stochastic autocorrelated demand 

    E-Print Network [OSTI]

    Ding, Zixuan

    1989-01-01

    ALGORITHMS FOR. ON-LINE AGGREGATE PRODUCTION PLAN REVISION WITH STOCHASTIC AUTOCORRELATED DEMAND A Thesis ZIXl'Alf DiiXG Sul&mitted to the Once of Graduate Studies of Texas AI-M T. 'niversity irt partial fulfillment ol' the reqrurements... for the degree of MASTER OF S(IEalGE December 1989 Major Subject: Industrial Engineering ALGORITHMS FOR ON-LINE AGGREGATE PRODUCTION PLAN REVISION WITH STOCHASTIC AUTOCORRELATED DEMAND A Thesis by ZITI'sit't DI'XG Approvecl as to style lad coiit alit...

  6. HWMA/RCRA Closure Plan for the CPP-602 Laboratory Lines

    SciTech Connect (OSTI)

    Idaho Cleanup Project

    2009-09-30

    This Hazardous Waste Management Act/Resource Conservation and Recovery Act Closure (HWMA/RCRA) Plan for the CPP-602 laboratory lines was developed to meet the tank system closure requirements of the Idaho Administrative Procedures Act 58.01.05.008 and 40 Code of Federal Regulations 264, Subpart G. CPP-602 is located at the Idaho Nuclear Technology and Engineering Center at the Idaho National Laboratory Site. The lines in CPP-602 were part of a liquid hazardous waste collection system included in the Idaho Nuclear Technology and Engineering Center Liquid Waste Management System Permit. The laboratory lines discharged to the Deep Tanks System in CPP-601 that is currently being closed under a separate closure plan. This closure plan presents the closure performance standards and the methods for achieving those standards. The closure approach for the CPP-602 laboratory lines is to remove the lines, components, and contaminants to the extent practicable. Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) Site CPP-117 includes the CPP-602 waste trench and the area beneath the basement floor where waste lines are direct-buried. Upon completion of rinsing or mopping to remove contamination to the extent practicable from the waste trench and rinsing the intact buried lines (i.e., stainless steel sections), these areas will be managed as part of CERCLA Site CPP-117 and will not be subject to further HWMA/RCRA closure activities. The CPP-602 building is being decontaminated and decommissioned under CERCLA as a non-time critical removal action in accordance with the Federal Facility Agreement/Consent Order. As such, all waste generated by this CERCLA action, including closure-generated waste, will be managed in coordination with that CERCLA action in substantive compliance with HWMA/RCRA regulations. All waste will be subject to a hazardous waste determination for the purpose of supporting appropriate management and will be managed in accordance with this plan. ii

  7. KV04: Baxter Mountain This route visits

    E-Print Network [OSTI]

    Reiter, Clifford A.

    11 KV04: Baxter Mountain General This route visits Baxter Mountain which is a short hike that has between Hurricane and Green Mountains. The hike is relatively short although there is a good elevation Description The trail begins on Rt9N directly across from Hurricane Mountain Road. From Keene Valley, go north

  8. Libby (FEC)-Troy 115kV Line Rebuild

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    A new runner design will eliminate the need to operate two units at low efficiency during low flow months and allow one unit to run at much higher efficiency. A modern runner...

  9. Libby (FEC)-Troy 115kV Line Rebuild

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Turbine Runner Replacements This project will refurbish the turbines and replace the turbine runners on units 1 - 16 at Chief Joseph. The drivers for this project are reliability...

  10. Libby (FEC)-Troy 115kV Line Rebuild

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Pre-Third Power Plant Overhaul Work This project includes four separate capital investments at the Grand Coulee Third Power Plant (TPP): * Stator core and winding replacement on...

  11. Libby (FEC)-Troy 115kV Line Rebuild

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantityBonneville Power Administration would likeUniverseIMPACTThousand CubicResourcelogo and-E C H N13, 2009 In Liaisons

  12. Libby (FEC)-Troy 115kV Line Rebuild

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantityBonneville Power Administration would likeUniverseIMPACTThousand CubicResourcelogo and-E C H N13, 2009 In LiaisonsPre-Third

  13. Libby (FEC)-Troy 115kV Line Rebuild

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantityBonneville Power Administration would likeUniverseIMPACTThousand CubicResourcelogo and-E C H N13, 2009 In LiaisonsPre-Third#JC

  14. Libby (FEC)-Troy 115kV Line Rebuild

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantityBonneville Power Administration would likeUniverseIMPACTThousand CubicResourcelogo and-E C H N13, 2009 In LiaisonsPre-Third#JCKC

  15. Libby (FEC)-Troy 115kV Line Rebuild

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantityBonneville Power Administration would likeUniverseIMPACTThousand CubicResourcelogo and-E C H N13, 2009 In

  16. Libby (FEC)-Troy 115kV Line Rebuild

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantityBonneville Power Administration would likeUniverseIMPACTThousand CubicResourcelogo and-E C H N13, 2009 InMcNary Main Unit 1-4

  17. Libby (FEC)-Troy 115kV Line Rebuild

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantityBonneville Power Administration would likeUniverseIMPACTThousand CubicResourcelogo and-E C H N13, 2009 InMcNary Main Unit

  18. Libby (FEC)-Troy 115kV Line Rebuild

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantityBonneville Power Administration would likeUniverseIMPACTThousand CubicResourcelogo and-E C H N13, 2009 InMcNary Main UnitTri

  19. Libby (FEC)-Troy 115kV Line Rebuild

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantityBonneville Power Administration would likeUniverseIMPACTThousand CubicResourcelogo and-E C H N13, 2009 InMcNary Main UnitTriof

  20. 500 kV Spare Transformer Procurement

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity ofkandz-cm11 Outreach Home RoomPreservationBio-InspiredAtmosphericdevicesPPONeApril351APPLICATION OF kV Spare Transformer

  1. Simultaneous Planning and Scheduling of Single-Stage Multiproduct Continuous Plants with Parallel Lines

    E-Print Network [OSTI]

    Grossmann, Ignacio E.

    , Carnegie Mellon University, Pittsburgh, Pennsylvania 15213 Key words: Planning; Scheduling; Multi-product integer linear programming model for the simultaneous planning and scheduling of single stage multi-product level the simultaneous planning and scheduling model is solved for a subset of products predicted

  2. Electric Reliability & Hurricane Preparedness Plan

    E-Print Network [OSTI]

    · Clean coal technology · On line ­ May 2014 · Generation mix: Natural gas, coal and lignite · Base load requirements #12;New Gen Mix Nat Gas Coal 3rd Qtr Lignite #12;Stennis Space Center · 115 kV ­ 13.8 kV · 3 MPC

  3. Design and Overview of 100 kV Bushing for the DNB Injector of ITER

    SciTech Connect (OSTI)

    Shah, Sejal; Bandyopadhyay, M.; Rotti, C.; Singh, M. J.; Roopesh, G.; Chakraborty, A. K. [ITER-India, Institute for Plasma Research, Gandhinagar-382025, Gujarat (India); Rajesh, S. [ITER-India, Institute for Plasma Research, Gandhinagar-382025, Gujarat (India); Microelectronics and Materials Physics Labs, P.O.Box 4500, FIN-90014 University of Oulu (Finland); Nishad, S.; Srusti, B. [DesignTech Systems Ltd, Banjara Hills, Hyderabad, Andhra Pradesh-500034 (India); Schunke, B.; Hemsworth, R.; Chareyre, J.; Svensson, L. [ITER Organisation, Route de Vinon, CS 90 046, 13067 St. Paul lez Durance Cedex (France)

    2011-09-26

    The 100 kV bushing is one of the most important and technologically challenging Safety Important Class (SIC) components of the Diagnostic Neutral Beam (DNB) injector of ITER. It forms interface between gas insulated electrical transmission line and torus primary vacuum and acts as a vacuum feedthrough of ITER. Design optimization has been carried out to meet the electric and structural requirements based on its classification. Unlike HNB bushing, single stage bushing is designed to provide 100 kV isolation. Finite Element Analysis (FEA) based optimization has been carried out for electrostatic and structural analysis. Manufacturing assembly sequence is studied and presented in this paper. However validation of the same is foreseen from manufacturer.

  4. EIS-0421: Big Eddy-Knight Transmission Line

    Broader source: Energy.gov [DOE]

    BPA is proposing to build a new 500 kilovolt (kV) transmission line in Wasco County, Oregon and Klickitat County, Washington and a new substation in Klickitat County. The new BPA transmission line...

  5. Manpower planning and cycle-time reduction of a labor-intensive assembly line

    E-Print Network [OSTI]

    Oh, Shao Chong

    2010-01-01

    The demand for Gas Lift Mandrels(GLM) in the oil and gas industry is expected to increase over the next few years, requiring Schlumberger's GLM assembly line to increase their manufacturing capacity. Given the labor-intensive ...

  6. Engineering Management Approach to Software Production Plan, based on the Principles of Software Product Lines

    E-Print Network [OSTI]

    Shetty, Rama

    2005-12-16

    excellence. The principles and practices of Software Product Lines [SPL] can be a catalyst in realizing such a vision. SPL ensembles three elements namely, core asset development, product development, and management to run an efficient and consistent...

  7. Is planning failing? : the impacts of decision making processes on the Green Line Extension

    E-Print Network [OSTI]

    Ciborowski, Matthew A

    2009-01-01

    Research was conducted on the proposed Green Line Extension, a light rail corridor from Cambridge through Somerville and Medford, Massachusetts. The project is being undertaken by the Massachusetts Executive Office of ...

  8. SU-E-J-92: On-Line Cone Beam CT Based Planning for Emergency and Palliative Radiation Therapy

    SciTech Connect (OSTI)

    Held, M; Morin, O; Pouliot, J

    2014-06-01

    Purpose: To evaluate and develop the feasibility of on-line cone beam CT based planning for emergency and palliative radiotherapy treatments. Methods: Subsequent to phantom studies, a case library of 28 clinical megavoltage cone beam CT (MVCBCT) was built to assess dose-planning accuracies on MVCBCT for all anatomical sites. A simple emergency treatment plan was created on the MVCBCT and copied to its reference CT. The agreement between the dose distributions of each image pair was evaluated by the mean dose difference of the dose volume and the gamma index of the central 2D axial plane. An array of popular urgent and palliative cases was also evaluated for imaging component clearance and field-of-view. Results: The treatment cases were categorized into four groups (head and neck, thorax/spine, pelvis and extremities). Dose distributions for head and neck treatments were predicted accurately in all cases with a gamma index of >95% for 2% and 2 mm criteria. Thoracic spine treatments had a gamma index as low as 60% indicating a need for better uniformity correction and tissue density calibration. Small anatomy changes between CT and MVCBCT could contribute to local errors. Pelvis and sacral spine treatment cases had a gamma index between 90% and 98% for 3%/3 mm criteria. The limited FOV became an issue for large pelvis patients. Imaging clearance was difficult for cases where the tumor was positioned far off midline. Conclusion: The MVCBCT based dose planning and delivery approach is feasible in many treatment cases. Dose distributions for head and neck patients are unrestrictedly predictable. Some FOV restrictions apply to other treatment sites. Lung tissue is most challenging for accurate dose calculations given the current imaging filters and corrections. Additional clinical cases for extremities need to be included in the study to assess the full range of site-specific planning accuracies. This work is supported by Siemens.

  9. EIS-0325: Schultz-Hanford Area Transmission Line Project Final Environmental Impact Statement, EIS-0325 (January 2003)

    Broader source: Energy.gov [DOE]

    BPA proposes to construct a new 500-kilovolt (kV) transmission line in central Washington. This project would increase transmission system capacity north of Hanford.

  10. Line-Focus Solar Power Plant Cost Reduction Plan (Milestone Report)

    SciTech Connect (OSTI)

    Kutscher, C.; Mehos, M.; Turchi, C.; Glatzmaier, G.; Moss, T.

    2010-12-01

    Line-focus solar collectors, in particular parabolic trough collectors, are the most mature and proven technology available for producing central electricity from concentrated solar energy. Because this technology has over 25 years of successful operational experience, resulting in a low perceived risk, it is likely that it will continue to be a favorite of investors for some time. The concentrating solar power (CSP) industry is developing parabolic trough projects that will cost billions of dollars, and it is supporting these projects with hundreds of millions of dollars of research and development funding. While this technology offers many advantages over conventional electricity generation -- such as utilizing plentiful domestic renewable fuel and having very low emissions of greenhouse gases and air pollutants -- it provides electricity in the intermediate power market at about twice the cost of its conventional competitor, combined cycle natural gas. The purpose of this document is to define a set of activities from fiscal year 2011 to fiscal year 2016 that will make this technology economically competitive with conventional means.

  11. Activity-Dependent Regulation of the Potassium Channel Subunits Kv1.1

    E-Print Network [OSTI]

    Rubel, Edwin

    Activity-Dependent Regulation of the Potassium Channel Subunits Kv1.1 and Kv3.1 YONG LU, PABLO, 1980; Escobar et al., 1993; Taxi and Eugene, 1995; Desai et al., 1999; Francis and Manis, 2000; Abdulla

  12. Value-based reliability transmission planning

    SciTech Connect (OSTI)

    Dalton, J.G. III; Garrison, D.L.; Fallon, C.M.

    1996-08-01

    This paper presents a new value-based reliability planning (VBRP) process proposed for planning Duke Power Company`s (DPC) regional transmission system. All transmission served customers are fed from DPC`s regional transmission system which consists of a 44-kV predominantly radial system and a 100-kV predominantly non-radial system. In the past, any single contingency that could occur during system peak conditions and cause a thermal overload required the overloaded facility to be upgraded, regardless of the costs or the likelihood of the overload occurring. The new VBRP process is based on transmission system reliability evaluation and includes the following important elements: (1) a ten-year historical data base describing the probabilities of forced outages for lines and transformers; (2) a five-year average load duration curve describing the probability of an overload should a contingency occur; (3) a customer outage cost data base; (4) and probabilistic techniques. The new process attempts to balance the costs of improving service reliability with the benefits or value that these improvements bring to these customers. The objective is to provide the customers their required level of reliability while minimizing the Total Cost of their electric service.

  13. Abstract. We consider the design of line plans in public transport at a min-imal total cost. Both, linear and nonlinear integer programming are adequate

    E-Print Network [OSTI]

    Lübbecke, Marco

    Abstract. We consider the design of line plans in public transport at a min- imal total cost. Both techniques. We derive and compare lower bounds from different lineariza- tions in order to assess the quality of the story, namely service versus cost aspects. While travelers demand for convenient, ideally direct

  14. A multiconductor model for determining the response of power transmission and distribution lines to a high altitude electromagnetic pulse (HEMP)

    SciTech Connect (OSTI)

    Tesche, F.M.; Barnes, P.R.

    1988-01-01

    A calculation model for electromagnetic pulse coupling to transmission and transmission line is discussed. Sample calculations for a 345 kV transmission line are given. 3 refs., 8 figs.

  15. Plan

    National Nuclear Security Administration (NNSA)

    Information P.O. Box 62 Oak Ridge, TN 37831-0062 (423) 576-8401 DOENV-11432-244 Nevada Test Site Routine Radiological Environmental Monitoring Plan December 1998 Work Performed...

  16. Aalborg Universitet Full Scale Test on a 100km, 150kV AC Cable

    E-Print Network [OSTI]

    Bak, Claus Leth

    wind farm Horns Rev 2, located in Denmark west coast, to Denmark's 400 kV transmission network from the electrical measurements on a 99.7 km, 150 kV three-phase AC cable, connecting 215 MW offshore

  17. Proposal for the award of a blanket purchase contract for the supply, installation, commissioning and maintenance of electrical switchgear operating at 18kV and 3.3 kV

    E-Print Network [OSTI]

    2015-01-01

    Proposal for the award of a blanket purchase contract for the supply, installation, commissioning and maintenance of electrical switchgear operating at 18kV and 3.3 kV

  18. Tungsten anode spectral model using interpolating cubic splines: Unfiltered x-ray spectra from 20 kV to 640 kV

    SciTech Connect (OSTI)

    Hernandez, Andrew M. [Biomedical Engineering Graduate Group, University of California Davis, Sacramento, California 95817 (United States)] [Biomedical Engineering Graduate Group, University of California Davis, Sacramento, California 95817 (United States); Boone, John M., E-mail: john.boone@ucdmc.ucdavis.edu [Departments of Radiology and Biomedical Engineering, Biomedical Engineering Graduate Group, University of California Davis, Sacramento, California 95817 (United States)

    2014-04-15

    Purpose: Monte Carlo methods were used to generate lightly filtered high resolution x-ray spectra spanning from 20 kV to 640 kV. Methods: X-ray spectra were simulated for a conventional tungsten anode. The Monte Carlo N-Particle eXtended radiation transport code (MCNPX 2.6.0) was used to produce 35 spectra over the tube potential range from 20 kV to 640 kV, and cubic spline interpolation procedures were used to create piecewise polynomials characterizing the photon fluence per energy bin as a function of x-ray tube potential. Using these basis spectra and the cubic spline interpolation, 621 spectra were generated at 1 kV intervals from 20 to 640 kV. The tungsten anode spectral model using interpolating cubic splines (TASMICS) produces minimally filtered (0.8 mm Be) x-ray spectra with 1 keV energy resolution. The TASMICS spectra were compared mathematically with other, previously reported spectra. Results: Using pairedt-test analyses, no statistically significant difference (i.e., p > 0.05) was observed between compared spectra over energy bins above 1% of peak bremsstrahlung fluence. For all energy bins, the correlation of determination (R{sup 2}) demonstrated good correlation for all spectral comparisons. The mean overall difference (MOD) and mean absolute difference (MAD) were computed over energy bins (above 1% of peak bremsstrahlung fluence) and over all the kV permutations compared. MOD and MAD comparisons with previously reported spectra were 2.7% and 9.7%, respectively (TASMIP), 0.1% and 12.0%, respectively [R. Birch and M. Marshall, “Computation of bremsstrahlung x-ray spectra and comparison with spectra measured with a Ge(Li) detector,” Phys. Med. Biol. 24, 505–517 (1979)], 0.4% and 8.1%, respectively (Poludniowski), and 0.4% and 8.1%, respectively (AAPM TG 195). The effective energy of TASMICS spectra with 2.5 mm of added Al filtration ranged from 17 keV (at 20 kV) to 138 keV (at 640 kV); with 0.2 mm of added Cu filtration the effective energy was 9 keV at 20 kV and 169 keV at 640 kV. Conclusions: Ranging from 20 kV to 640 kV, 621 x-ray spectra were produced and are available at 1 kV tube potential intervals. The spectra are tabulated at 1 keV intervals. TASMICS spectra were shown to be largely equivalent to published spectral models and are available in spreadsheet format for interested users by emailing the corresponding author (JMB)

  19. 130kV 130A High Voltage Switching Mode Power Supply for Neutral Injections – Control Issues and Algorithms

    E-Print Network [OSTI]

    130kV 130A High Voltage Switching Mode Power Supply for Neutral Injections – Control Issues and Algorithms

  20. Deuterium Retention in Beryllium Exposed to a 60kV Deuterium Beam ­ Consequences for Next Step Devices

    E-Print Network [OSTI]

    Deuterium Retention in Beryllium Exposed to a 60kV Deuterium Beam ­ Consequences for Next Step Devices

  1. Multi-Vehicle Path Planning for Non-Line of Sight Communication Tom Schouwenaars, Eric Feron, and Jonathan How

    E-Print Network [OSTI]

    How, Jonathan P.

    line of sight communication to its ground station is lost. Relay helicopters are therefore introduced formulations to model nonconvex obstacles more efficiently. Simulation, hardware in the loop, and flight test by introducing a set of relay helicopters. Indirect communication with the ground station can then be established

  2. Solid-State Fault Current Limiter Development : Design and Testing Update of a 15kV SSCL Power Stack

    SciTech Connect (OSTI)

    Dr. Ram Adapa; Mr. Dante Piccone

    2012-04-30

    ABSTRACT The Solid-State Fault Current Limiter (SSCL) is a promising technology that can be applied to utility power delivery systems to address the problem of increasing fault currents associated with load growth. As demand continues to grow, more power is added to utility system either by increasing generator capacity or by adding distributed generators, resulting in higher available fault currents, often beyond the capabilities of the present infrastructure. The SSCL is power-electronics based equipment designed to work with the present utility system to address this problem. The SSCL monitors the line current and dynamically inserts additional impedance into the line in the event of a fault being detected. The SSCL is based on a modular design and can be configured for 5kV through 69kV systems at nominal current ratings of 1000A to 4000A. Results and Findings This report provides the final test results on the development of 15kV class SSCL single phase power stack. The scope of work included the design of the modular standard building block sub-assemblies, the design and manufacture of the power stack and the testing of the power stack for the key functional tests of continuous current capability and fault current limiting action. Challenges and Objectives Solid-State Current Limiter technology impacts a wide spectrum of utility engineering and operating personnel. It addresses the problems associated with load growth both at Transmission and Distribution class networks. The design concept is pioneering in terms of developing the most efficient and compact power electronics equipment for utility use. The initial test results of the standard building blocks are promising. The independent laboratory tests of the power stack are promising. However the complete 3 phase system needs rigorous testing for performance and reliability. Applications, Values, and Use The SSCL is an intelligent power-electronics device which is modular in design and can provide current limiting or current interrupting capabilities. It can be applied to variety of applications from distribution class to transmission class power delivery grids and networks. It can also be applied to single major commercial and industrial loads and distributed generator supplies. The active switching of devices can be further utilized for protection of substation transformers. The stress on the system can be reduced substantially improving the life of the power system. It minimizes the voltage sag by speedy elimination of heavy fault currents and promises to be an important element of the utility power system. DOE Perspective This development effort is now focused on a 15kV system. This project will help mitigate the challenges of increasing available fault current. DOE has made a major contribution in providing a cost effective SSCL designed to integrate seamlessly into the Transmission and Distribution networks of today and the future. Approach SSCL development program for a 69kV SSCL was initiated which included the use of the Super GTO advanced semiconductor device which won the 2007 R&D100 Award. In the beginning, steps were identified to accomplish the economically viable design of a 69kV class Solid State Current Limiter that is extremely reliable, cost effective, and compact enough to be applied in urban transmission. The prime thrust in design and development was to encompass the 1000A and the 3000A ratings and provide a modular design to cover the wide range of applications. The focus of the project was then shifted to a 15kV class SSCL. The specifications for the 15kV power stack are reviewed. The design changes integrated into the 15kV power stack are discussed. In this Technical Update the complete project is summarized followed by a detailed test report. The power stack independent high voltage laboratory test requirements and results are presented. Keywords Solid State Current Limiter, SSCL, Fault Current Limiter, Fault Current Controller, Power electronics controller, Intelligent power-electronics Device, IED

  3. EIS-0129: New England/Hydro-Quebec 450 kV Transmission Line Interconnection- Phase II

    Office of Energy Efficiency and Renewable Energy (EERE)

    The Economic Regulatory Administration issued this EIS to explore the impacts of amending Presidential Permit PP-76 to allow the Vermont Electrical Company to operate at power levels above those stipulated in the permit and to build additional transmission facilities to distribute the increased power. Phase I of this project is detailed in EIS-0103.

  4. Aalborg Universitet Line Differential Protection Scheme Modelling for Underground 420 kV Cable Systems

    E-Print Network [OSTI]

    Bak, Claus Leth

    Department of Energy Technology Aalborg University Aalborg, Denmark clb@iet.aau.dk Wojciech Wiechowski, Sebastian Dollerup Protection & Control Systems Energinet.dk Fredericia, Denmark sdo@energinet.dk Abstract relay computer model, since relay manufacturers offer their products with a variety of algorithms

  5. EIS-0011: New Melones 230-kV Electrical Transmission Line, Central Valley Project, California

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy's Western Area Power Administration prepared this statement to evaluate the environmental impacts of proposed development of an electrical transmission system for the New Melones Power Plant.

  6. ETM (Distribution Network Automation on 10 kV cable line stations) (Smart

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on QA:QA J-E-1 SECTIONRobertsdale, AlabamaETEC GmbH Jump to: navigation, search Name: ETEC GmbH Place: Germany Sector:Grid

  7. Cameron to Milford-138kV Transmission Line | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on QA:QA J-E-1 SECTION JEnvironmentalBowerbank, Maine:Kansas:Information(RedirectedEnterpriseCounty, Texas:to

  8. EIS-0505: Vantage to Pomona Heights 230 kV Transmission Line Project;

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE:FinancingPetroleum Based|DepartmentStatement |toDepartment of EnergyDepartment ofYakima, Grant,

  9. Second Line of Defense, Port of Buenos Aires and Exolgan Container Terminal Operational Testing and Evaluation Plan, Buenos Aires, Argentina

    SciTech Connect (OSTI)

    Roberts, Bryan W.

    2012-08-23

    The Office of the Second Line of Defense (SLD) Megaports project team for Argentina will conduct operational testing and evaluation (OT&E) at Exolgan Container Terminal at the Port of Dock Sud from July 16-20, 2012; and at the Port of Buenos Aires from September 3-7, 2012. SLD is installing radiation detection equipment to screen export, import, and transshipment containers at these locations. The purpose of OT&E is to validate and baseline an operable system that meets the SLD mission and to ensure the system continues to perform as expected in an operational environment with Argentina Customs effectively adjudicating alarms.

  10. A 25 KV/10A PULSER FOR DRIVING A HIGH-POWER PIERCE ELECTRON GUN

    E-Print Network [OSTI]

    A 25 KV/10A PULSER FOR DRIVING A HIGH-POWER PIERCE ELECTRON GUN J. J. Barroso, J. O. Rossi, H-tube pulser to drive a high-power electron gun. The tube includes a 2.0µF/100kV capacitor bank whose discharge is controlled by a tetrode tube connected to the gun cathode. Typical measured operating parameters are 3

  11. EIS-0005-S2: Bonneville Power Administration Proposed FY 1979 Program Facility Planning Supplement Southwest Oregon Area Service, Supplemental

    Broader source: Energy.gov [DOE]

    This statement, one of a series prepared by the U.S. Department of Energy’s Bonneville Power Administration on various facets of its construction and maintenance activities, addresses the potential impact of a major new facility proposed for fiscal year 1979. To allow power generated in Wyoming to be delivered to Southwest Oregon and to facilitate the exchange of electric power between the Pacific Northwest and the Middle Snake region, two basic plans of service, each with two corridor routing options, have been identified to meet system requirements. BPA proposes construction of the following two transmission facilities: (1) a 500-kV line from Idaho Power Company's Brownlee Substation in Idaho to BPA's Slatt Substation near Arlington, Oregon, and (2) a 500-kV line from Buckley (near Maupin, Oregon) to Malin, Oregon. This statement must be reviewed and used in conjunction with the overall programmatic environmental statement entitled ""The Role of the Bonneville Power Administration in the Pacific Northwest Power Supply System, Including Its Participation in the Hydro-Thermal Power Program: A Program Environmental Statement and Planning Report (The ""Role EIS""), particularly Appendix B - BPA Power Transmission.

  12. Hopi Sustainable Energy Plan

    SciTech Connect (OSTI)

    Norman Honie, Jr.; Margie Schaff; Mark Hannifan

    2004-08-01

    The Hopi Tribal Government as part of an initiative to ?Regulate the delivery of energy and energy services to the Hopi Reservation and to create a strategic business plan for tribal provision of appropriate utility, both in a manner that improves the reliability and cost efficiency of such services,? established the Hopi Clean Air Partnership Project (HCAPP) to support the Tribe?s economic development goals, which is sensitive to the needs and ways of the Hopi people. The Department of Energy (DOE) funded, Formation of Hopi Sustainable Energy Program results are included in the Clean Air Partnership Report. One of the Hopi Tribe?s primary strategies to improving the reliability and cost efficiency of energy services on the Reservation and to creating alternative (to coal) economic development opportunities is to form and begin implementation of the Hopi Sustainable Energy Program. The Hopi Tribe through the implementation of this grant identified various economic opportunities available from renewable energy resources. However, in order to take advantage of those opportunities, capacity building of tribal staff is essential in order for the Tribe to develop and manage its renewable energy resources. As Arizona public utilities such as APS?s renewable energy portfolio increases the demand for renewable power will increase. The Hopi Tribe would be in a good position to provide a percentage of the power through wind energy. It is equally important that the Hopi Tribe begin a dialogue with APS and NTUA to purchase the 69Kv transmission on Hopi and begin looking into financing options to purchase the line.

  13. EA-1960: Townsite Solar Project Transmission Line, Clark County, Nevada

    Broader source: Energy.gov [DOE]

    The Bureau of Land Management, with Western Area Power Administration as a cooperating agency, prepared an EA to evaluate potential impacts of a proposal to build and operate a 180-MW photovoltaic facility; a 220, 230, or 500 kV transmission line; and associated facilities in Clark County, Nevada.

  14. EIS-0090: Fort Peck-Havre Transmission Line Project, Montana

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy’s Western Area Power Administration prepared this statement to assess the potential environmental and socioeconomic implications of its proposed action to construct and operate a 230kV transmission line from Fort Peck to Havre, Montana, with three intermediate interconnecting substations.

  15. EIS-0124: Conrad-Shelby Transmission Line Project, Montana

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy's Western Area Power Administration developed this statement to assess the environmental impact of adding a 230 kV transmission line between Conrad and Shelby, Montana and a new substation near Shelby to update the stressed electrical transmission system.

  16. Docket No. EO-05-01: Further Notice of 230kV Circuit Planned Outages |

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustmentsShirleyEnergy A plug-in electricLaboratoryof EnergyWASHINGTON,Response3, 2013ofDepartment of

  17. Notification of Planned 230kV Outage at Potomac River Generating Station |

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustmentsShirleyEnergy AEnergy Managing853926 News enDepartment of Energy In accordance with DOE

  18. Notification of Planned 230kV Outage at Potomac River Generating Station |

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustmentsShirleyEnergy AEnergy Managing853926 News enDepartment of Energy In accordance with

  19. Notification of Planned 230kV Outage at Potomac River Generating Station

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustmentsShirleyEnergyTher i nAand DOEDepartmentNew JerseyEnergybenefits of6107 /AvailabilityJune

  20. Further Notice of 230kV Circuit Planned Outages | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE:FinancingPetroleum12, 2015ExecutiveFluorescentDanKathyEnergydetailsof EnergyStandard

  1. Notification of Planned 230kV Outage at Potomac River Generating Station |

    Energy Savers [EERE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on DeliciousMathematicsEnergyInterested Parties -DepartmentAvailable forSite |n t e g r8480094626076 Federal7,

  2. Notification of Planned 230kV Outage at Potomac River Generating Station |

    Energy Savers [EERE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on DeliciousMathematicsEnergyInterested Parties -DepartmentAvailable forSite |n t e g r8480094626076

  3. Field Demonstration of a 24-kV Superconducting Cable at Detroit Edison

    SciTech Connect (OSTI)

    Kelley, Nathan; Corsaro, Pietro

    2004-12-01

    Customer acceptance of high temperature superconducting (HTS) cable technology requires a substantial field demonstration illustrating both the system's technical capabilities and its suitability for installation and operation within the utility environment. In this project, the world's first underground installation of an HTS cable using existing ductwork, a 120 meter demonstration cable circuit was designed and installed between the 24 kV bus distribution bus and a 120 kV-24 kV transformer at Detroit Edison's Frisbie substation. The system incorporated cables, accessories, a refrigeration system, and control instrumentation. Although the system was never put in operation because of problems with leaks in the cryostat, the project significantly advanced the state-of-the-art in the design and implementation of Warm Dielectric cable systems in substation applications. Lessons learned in this project are already being incorporated in several ongoing demonstration projects.

  4. EA-1617: Lovell-Yellowtail and Basin-Lovell Transmission Line Rebuild Project, Big Horn County, Wyoming, and Big Horn and Carbon Counties, Montana

    Broader source: Energy.gov [DOE]

    DOE’s Western Area Power Administration prepared this EA and a finding of no significant impact for a proposal to rebuild the Lovell-Yellowtail (LV-YT) No. 1 and No. 2 115-kV transmission lines, located in Big Horn County, Wyoming, and Big Horn and Carbon Counties in Montana, and the Basin-Lovell 115-kV transmission line in Big Horn County, Wyoming.

  5. Electric power high-voltage transmission lines: Design options, cost, and electric and magnetic field levels

    SciTech Connect (OSTI)

    Stoffel, J.B.; Pentecost, E.D.; Roman, R.D.; Traczyk, P.A.

    1994-11-01

    This report provides background information about (1) the electric and magnetic fields (EMFs) of high-voltage transmission lines at typical voltages and line configurations and (2) typical transmission line costs to assist on alternatives in environmental documents. EMF strengths at 0 {+-} 200 ft from centerline were calculated for ac overhead lines, and for 345 and 230-kV ac underground line and for a {+-}450-kV dc overhead line. Compacting and height sensitivity factors were computed for the variation in EMFs when line conductors are moved closer or raised. Estimated costs for the lines are presented and discussed so that the impact of using alternative strategies for reducing EMF strengths and the implications of implementing the strategies can be better appreciated.

  6. Enhancement of Kv1.3 Potassium Conductance by Extremely Low Frequency Electromagnetic Field

    E-Print Network [OSTI]

    Cecchetto, Claudia; Boccaccio, Pasquale; Vassanelli, Stefano

    2015-01-01

    Theoretical and experimental evidences support the hypothesis that extremely low-frequency electromagnetic fields can affect voltage-gated channels. Little is known, however, about their effect on potassium channels. Kv1.3, a member of the voltage-gated potassium channels family originally discovered in the brain, is a key player in important biological processes including antigen-dependent activation of T-cells during the immune response. We report that Kv1.3 expressed in CHO-K1 cells can be modulated in cell subpopulations by extremely low frequency and relatively low intensity electromagnetic fields. In particular, we observed that field exposure can cause an enhancement of Kv1.3 potassium conductance and that the effect lasts for several minutes after field removal. The results contribute to put immune and nervous system responses to extremely low-frequency electromagnetic fields into a new perspective, with Kv1.3 playing a pivotal molecular role. Keywords: immunotherapy, immunomodulation, potassium chann...

  7. Enhancement of Kv1.3 Potassium Conductance by Extremely Low Frequency Electromagnetic Field

    E-Print Network [OSTI]

    Claudia Cecchetto; Marta Maschietto; Pasquale Boccaccio; Stefano Vassanelli

    2015-08-25

    Theoretical and experimental evidences support the hypothesis that extremely low-frequency electromagnetic fields can affect voltage-gated channels. Little is known, however, about their effect on potassium channels. Kv1.3, a member of the voltage-gated potassium channels family originally discovered in the brain, is a key player in important biological processes including antigen-dependent activation of T-cells during the immune response. We report that Kv1.3 expressed in CHO-K1 cells can be modulated in cell subpopulations by extremely low frequency and relatively low intensity electromagnetic fields. In particular, we observed that field exposure can cause an enhancement of Kv1.3 potassium conductance and that the effect lasts for several minutes after field removal. The results contribute to put immune and nervous system responses to extremely low-frequency electromagnetic fields into a new perspective, with Kv1.3 playing a pivotal molecular role. Keywords: immunotherapy, immunomodulation, potassium channels, gating, electromagnetic fields

  8. Compact 180-kV Marx generator triggered in atmospheric air by femtosecond laser filaments

    SciTech Connect (OSTI)

    Arantchouk, L. Larour, J.; Point, G.; Brelet, Y.; Carbonnel, J.; André, Y.-B.; Mysyrowicz, A.; Houard, A.

    2014-03-10

    We developed a compact Marx generator triggered in atmospheric air by a single femtosecond laser beam undergoing filamentation. Voltage pulses of 180?kV could be generated with a subnanosecond jitter. The same laser beam was also used to initiate simultaneously guided discharges up to 21?cm long at the output of the generator.

  9. Design and performance of a 30 KV electron gun with ten independent cathodes & a magnetic lens.

    SciTech Connect (OSTI)

    Rudys, Joseph Matthew; Reed, Kim Warren

    2006-08-01

    Measurements on a 30 kV electron gun with ten independent cathodes, operating in a 6.5 Tesla (T) magnetic field are presented. An earlier paper covered the design of this electron gun [1]. Experimental results are compared to model predictions. Beam current is compared to theoretical space charge limited flow.

  10. DESIGN AND PSPICE SIMULATION OF A 150KV/300A/1S COAXIAL PULSE GENERATOR

    E-Print Network [OSTI]

    DESIGN AND PSPICE SIMULATION OF A 150KV/300A/1µS COAXIAL PULSE GENERATOR J.O. Rossi, M. Ueda, J-mail: rossi@plasma.inpe.br Abstract - Coaxial pulse generators are well-suited devices for high voltage pulse generation in the range of nanoseconds or microseconds. Basically these devices consist of pieces

  11. STANDARD REVIEW PLAN

    Office of Environmental Management (EM)

    Strengthening Line Management Oversight and Federal Monitoring of Nuclear Facilities Standard Review Plan Safety Design Strategy January 2015 OFFICE OF ENVIRONMENTAL MANAGEMENT...

  12. Aalborg Universitet Back-to-Back Energization of a 60kV Cable Network -Inrush Currents Phenomenon

    E-Print Network [OSTI]

    Bak, Claus Leth

    details, and we will remove access to the work immediately and investigate your claim. Downloaded from vbn a risk to the circuit breakers connected to the cables. The Danish utility ENV plans to install a new to political decisions this line has to be an underground cable This work was supported by ENV: Elforsyningen

  13. A 6 kV arbitrary waveform generator for the Tevatron Electron Lens

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Pfeffer, H.; Saewert, G.

    2011-11-09

    This paper reports on a 6 kV modulator built and installed at Fermilab to drive the electron gun anode for the Tevatron Electron Lens (TEL). The TEL was built with the intention of shifting the individual (anti)proton bunch tunes to even out the tune spread among all 36 bunches with the desire of improving Tevatron integrated luminosity. This modulator is essentially a 6 kV arbitrary waveform generator that enables the TEL to define the electron beam intensity on a bunch-by-bunch basis. A voltage waveform is constructed having a 7 ?s duration that corresponds to the tune shift requirements of amore »12-bunch (anti)proton beam pulse train. This waveform is played out for any one or all three bunch trains in the Tevatron. The programmed waveform voltages transition to different levels at time intervals corresponding to the 395 ns bunch spacing. In addition, complex voltage waveforms can be played out at a sustained rate of 143 kHz over the full 6 kV output range. This paper describes the novel design of the inductive adder topology employing five transformers. It describes the design aspects that minimize switching losses for this multi-kilovolt, high repetition rate and high duty factor application.« less

  14. A 120kV IGBT modulator for driving a pierce electron gun

    SciTech Connect (OSTI)

    Earley, L. M.; Brown, R. W.; Carlson, R. L.; Ferguson, P.; Haynes, W. B.; Kirbie, H. C.; Russell, S. J.; Sigler, F. E.; Smirnova, E. I.; Wheat, R. M.

    2004-01-01

    An IGBT modulator has been developed to drive a 120 kV, 23 A Pierce electron gun. The modulator is capable of producing pulses up to 10 {mu}s in width at repetition rates up to 10Hz with no active reset. The pulse rise time on the electron gun will be approximately 2 {mu}s and the remaining 8 {mu}s of flattop is tuned to have a ripple of less than 1 percent rms. The modulator technology was developed from a previous 50 kV prototype. The modulator consists of six boards, each with one EUPEC IGBT that drives a single common step-up transformer wound on METGLAS 2605SC cores. The six transformer cores share a common bi-filar output secondary winding. The modulator uses a fiber optic trigger system and has a high voltage cable output with an epoxy receptacle on the oil end and a ceramic receptacle on the vacuum end. The 120 kV electron gun was manufactured by MDS Co. and will be used to generate sheet electron beams from the standard pencil beam produced by the Pierce electron gun.

  15. A 6 kV arbitrary waveform generator for the Tevatron Electron Lens

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Pfeffer, H.; Saewert, G.

    2011-11-01

    This paper reports on a 6 kV modulator built and installed at Fermilab to drive the electron gun anode for the Tevatron Electron Lens (TEL). The TEL was built with the intention of shifting the individual (anti)proton bunch tunes to even out the tune spread among all 36 bunches with the desire of improving Tevatron integrated luminosity. This modulator is essentially a 6 kV arbitrary waveform generator that enables the TEL to define the electron beam intensity on a bunch-by-bunch basis. A voltage waveform is constructed having a 7 {micro}s duration that corresponds to the tune shift requirements of a 12-bunch (anti)proton beam pulse train. This waveform is played out for any one or all three bunch trains in the Tevatron. The programmed waveform voltages transition to different levels at time intervals corresponding to the 395 ns bunch spacing. Thus, complex voltage waveforms can be played out at a sustained rate of 143 kHz over the full 6 kV output range. This paper describes the novel design of the inductive adder topology employing five transformers. It describes the design aspects that minimize switching losses for this multi-kilovolt, high repetition rate and high duty factor application.

  16. Poster — Thur Eve — 10: Partial kV CBCT, complete kV CBCT and EPID in breast treatment: a dose comparison study for skin, breasts, heart and lungs

    SciTech Connect (OSTI)

    Roussin, E; Archambault, L K; Wierzbicki, W

    2014-08-15

    The advantages of kilovoltage cone beam CT (kV CBCT) imaging over electronic portal imaging device (EPID) such as accurate 3D anatomy, soft tissue visualization, fast rigid registration and enhanced precision on patient positioning has lead to its increasing use in clinics. The benefits of this imaging technique are at the cost of increasing the dose to healthy surrounding organs. Our center has moved toward the use of daily partial rotation kV CBCT to restrict the dose to healthy tissues. This study aims to better quantify radiation doses from different image-guidance techniques such as tangential EPID, complete and partial kV CBCT for breast treatments. Cross-calibrated ionization chambers and kV calibrated Gafchromic films were used to measure the dose to the heart, lungs, breasts and skin. It was found that performing partial kV CBCT decreases the heart dose by about 36%, the lungs dose by 31%, the contralateral breast dose by 41% and the ipsilateral breast dose by 43% when compared to a full rotation CBCT. The skin dose measured for a full rotation CBCT was about 0.8 cGy for the contralateral breast and about 0.3 cGy for the ipsilateral breast. The study is still ongoing and results on skin doses for partial rotation kV CBCT as well as for tangential EPID images are upcoming.

  17. EA-1967: Hills Creek-Lookout Point Transmission Line Rebuild, Lane County, Oregon

    Broader source: Energy.gov [DOE]

    Bonneville Power Administration is preparing an EA to assess potential environmental impacts of the proposed rebuild of its 26-mile 115 kilovolt (kV) wood-pole Hills Creek-Lookout Point transmission line, which is generally located between Lowell and Oakridge, in Lane County, Oregon.

  18. EA-1961: Kalispell-Kerr Transmission Line Rebuild Project, Kalispell and Polson, Montana

    Broader source: Energy.gov [DOE]

    Bonneville Power Administration is preparing an EA to evaluate potential environmental impacts of rebuilding its 41-mile long 115 kilovolt (kV) wood-pole Kalispell-Kerr transmission line between Kalispell and Polson, Montana. Additional information is available on the project website, http://efw.bpa.gov/environmental_services/Document_Library/KALISPELL_KERR/.

  19. EIS-0079: 300-kV International Submarine Transmission Line- Erie, Pennsylvania to Nanticoke, Ontario, Canada General Public Utilities Corporation

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy Office of Energy Emergency Operations developed this statement to assess the potential environmental and socioeconomic impacts of the construction and operation of 44 miles of cable between the Erie West Substation and the Canadian border.

  20. Vector Analysis of Prostate Patient Setup With Image-Guided Radiation Therapy via kV Cone Beam Computed Tomography

    SciTech Connect (OSTI)

    Perks, Julian, E-mail: julian.perks@ucdmc.ucdavis.ed [Department of Radiation Oncology, University of California, Davis, Sacramento, California (United States); Turnbull, Helen; Liu Tianxiao; Purdy, James; Valicenti, Richard [Department of Radiation Oncology, University of California, Davis, Sacramento, California (United States)

    2011-03-01

    Purpose: To analyze the daily setup variations in a cohort of intensity-modulated radiation therapy (IMRT) prostate cancer patients who had received daily image-guided RT without the use of fiducial markers to determine if daily image guidance is necessary. Methods and Materials: 2134 Kilovoltage (kV) cone beam computed tomography (CBCT) images were analyzed, with three shifts recorded for each image. The number of times that the vector of the combined shifts would have exceeded the planning tumor volume (PTV) margin was tallied. Then, the average scalar shift of the first five images was removed from all subsequent images for a given patient, and the number of days for which the shift vector was greater than the three-dimensional clinical tumor volume-PTV (3D CTV-PTV) margin (8 mm, created with rolling ball technique) was recorded. Additionally, the scalar shifts from every other fraction were studied to determine if the individual patient's shift vector would be adequately sampled if CBCT was not performed daily, thus reducing patient imaging dose without compromising treatment quality. Results: There were 297 cases where the vector shift was initially greater than the PTV margin. By correcting each patient's data set by the average shift of their first five images the total was 248 cases. By considering only every other image of each patient data set (after correction for the first 5 days), only 137 days in which the CTV was outside the PTV would have been seen. Conclusions: Daily imaging is recommended for prostate cancer IMRT patients in order to know the 3D (vector) position of the CTV and to ensure that it is always within the PTV margin. Correcting the data set by the average shift from the first 5 days reduces the overall number of outlier days but does not eliminate them completely.

  1. Operating characteristics and modeling of the LLNL 100-kV electric gun

    SciTech Connect (OSTI)

    Osher, J.E.; Barnes, G.; Chau, H.H.; Lee, R.S.; Lee, C.; Speer, R.; Weingart, R.C.

    1989-06-01

    In the electric gun, the explosion of an electrically heated metal foil and the accompanying magnetic forces drive a thin flyer plate up a short barrel. Flyer velocities of up to 18 km/s make the gun useful for hypervelocity impact studies. The authors briefly review the technological evolution of the exploding-metal circuit elements that power the gun, describe the 100-kV electric gun designed at Lawrence Livermore National Laboratory (LLNL) in some detail, and present the general principles of electric gun operation. They compare the experimental performance of the LLNL gun with a simple model and with predictions of a magnetohydrodynamics code.

  2. KvH Projekt GmbH Co KG | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on QA:QA J-E-1 SECTION J APPENDIXsource History View NewGuam:onItronKanoshKetchikanKlondikeKun Renewables JumpKvH Projekt

  3. Building Work: Allocation of Contract for the Electric Sub-Station 18 kV, NPA Building, Technological Workshop and Lab. 13

    E-Print Network [OSTI]

    1963-01-01

    Building Work: Allocation of Contract for the Electric Sub-Station 18 kV, NPA Building, Technological Workshop and Lab. 13

  4. Proposal for the award of a contract, without competitive tendering, for the design and construction of a new 400 kV transmission feeder bay

    E-Print Network [OSTI]

    2015-01-01

    Proposal for the award of a contract, without competitive tendering, for the design and construction of a new 400 kV transmission feeder bay

  5. Addendum to the Contract for the Supply of 18 kV Switchgear for the North Experimental Area of the 300 GeV Accelerator

    E-Print Network [OSTI]

    1976-01-01

    Addendum to the Contract for the Supply of 18 kV Switchgear for the North Experimental Area of the 300 GeV Accelerator

  6. Proposal to Increase the Amount of the Contract for the Supply of 18 kV Switchgear for the North Experimental Area

    E-Print Network [OSTI]

    1977-01-01

    Proposal to Increase the Amount of the Contract for the Supply of 18 kV Switchgear for the North Experimental Area

  7. Proposal to Take up an Option Provided for in the Order for the Supply of 3.6 kV Switchgear for the LEP Project

    E-Print Network [OSTI]

    1990-01-01

    Proposal to Take up an Option Provided for in the Order for the Supply of 3.6 kV Switchgear for the LEP Project

  8. Proposal for the award of a contract for the supply of 24 kV switchgear for the LEP electrical power distribution

    E-Print Network [OSTI]

    1983-01-01

    Proposal for the award of a contract for the supply of 24 kV switchgear for the LEP electrical power distribution

  9. Adjudication of a Contract for the Supply of 18 kV Switchgear for the North Experimental Area of the 300 GeV Accelerator

    E-Print Network [OSTI]

    1976-01-01

    Adjudication of a Contract for the Supply of 18 kV Switchgear for the North Experimental Area of the 300 GeV Accelerator

  10. Long-term stability and mechanical characteristics of kV digital imaging system for proton radiotherapy

    SciTech Connect (OSTI)

    Zhu, Mingyao, E-mail: mzhu4@mgh.harvard.edu; Botticello, Thomas; Lu, Hsiao-Ming; Winey, Brian [Department of Radiation Oncology, Massachusetts General Hospital, Harvard Medical School, Boston, Massachusetts 02114 (United States)] [Department of Radiation Oncology, Massachusetts General Hospital, Harvard Medical School, Boston, Massachusetts 02114 (United States)

    2014-04-15

    Purpose: To quantitatively evaluate the long-term image panel positioning stability and gantry angle dependence for gantry-mounted kV imaging systems. Methods: For patient setup digital imaging systems in isocentric rotating proton beam delivery facilities, physical crosshairs are commonly inserted into the snout to define the kV x-ray beam isocenter. Utilizing an automatic detection algorithm, the authors analyzed the crosshair center positions in 2744 patient setup kV images acquired with the four imagers in two treatment rooms from January 2012 to January 2013. The crosshair position was used as a surrogate for imaging panel position, and its long-term stability at the four cardinal angles and the panel flex dependency on gantry angle was investigated. Results: The standard deviation of the panel position distributions was within 0.32 mm (with the range of variation less than ± 1.4 mm) in both the X-Z plane and Y direction. The mean panel inplane rotations were not more than 0.51° for the four panels at the cardinal angles, with standard deviations ?0.26°. The panel position variations with gantry rotation due to gravity (flex) were within ±4 mm, and were panel-specific. Conclusions: The authors demonstrated that the kV image panel positions in our proton treatment system were highly reproducible at the cardinal angles over 13 months and also that the panel positions can be correlated to gantry angles. This result indicates that the kV image panel positions are stable over time; the amount of panel sag is predictable during gantry rotation and the physical crosshair for kV imaging may eventually be removed, with the imaging beam isocenter position routinely verified by adequate quality assurance procedures and measurements.

  11. 1.9 kV AlGaN/GaN Lateral Schottky Barrier Diodes on Silicon

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Zhu, Mingda [University of Notre Dame, IN (United States); Song, Bo [Cornell University, Ithaca, NY (United States); Qi, Meng [University of Notre Dame, IN (United States); Hu, Zongyang [University of Notre Dame, IN (United States); Nomoto, Kazuki [University of Notre Dame, IN (United States); Yan, Xiaodong [University of Notre Dame, IN (United States); Cao, Yu [IQE, Westborough, MA (United States); Johnson, Wayne [IQE, Westborough, MA (United States); Kohn, Erhard [University of Notre Dame, IN (United States); Jena, Debdeep [Cornell University, Ithaca, NY (United States); Xing, Grace Huili [Cornell University, Ithaca, NY (United States)

    2015-04-01

    In this letter, we present AlGaN/GaN lateral Schottky barrier diodes on silicon with recessed anodes and dual field plates. A low specific on-resistance RON,SP (5.12 m?{center_dot}cm2), a low turn-on voltage (1.9 kV), were simultaneously achieved in devices with a 25 ?m anode/cathode separation, resulting in a power figure-of-merit (FOM) BV2/RON,SP of 727 MW{center_dot}cm2. The record high breakdown voltage of 1.9 kV is attributed to the dual field plate structure.

  12. 1.9 kV AlGaN/GaN Lateral Schottky Barrier Diodes on Silicon

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Zhu, Mingda; Song, Bo; Qi, Meng; Hu, Zongyang; Nomoto, Kazuki; Yan, Xiaodong; Cao, Yu; Johnson, Wayne; Kohn, Erhard; Jena, Debdeep; et al

    2015-02-16

    In this letter, we present AlGaN/GaN lateral Schottky barrier diodes on silicon with recessed anodes and dual field plates. A low specific on-resistance RON,SP (5.12 m? · cm2), a low turn-on voltage (1.9 kV), were simultaneously achieved in devices with a 25 ?m anode/cathode separation, resulting in a power figure-of-merit (FOM) BV2/RON,SP of 727 MW·cm2. The record high breakdown voltage of 1.9 kV is attributed to the dual field plate structure.

  13. Evaluation of Instrumentation and Dynamic Thermal Ratings for Overhead Lines

    SciTech Connect (OSTI)

    Phillips, A.

    2013-01-31

    In 2010, a project was initiated through a partnership between the Department of Energy (DOE) and the New York Power Authority (NYPA) to evaluate EPRI?s rating technology and instrumentation that can be used to monitor the thermal states of transmission lines and provide the required real-time data for real-time rating calculations. The project included the installation and maintenance of various instruments at three 230 kV line sites in northern New York. The instruments were monitored, and data collection and rating calculations were performed for about a three year period.

  14. A Solid State 100 kV Long Pulse Generator for Klystrons Power Supply

    E-Print Network [OSTI]

    Martins, C A; Simonet, G

    2010-01-01

    A solid state pulsed power generator rated at 100 kV, 2 MWpeak, 0.8 ms/2 Hz suited for klystrons cathode power supply (klystron modulator) is proposed as an alternative to traditional topologies, requiring thyratrons and PFN’s, for long pulse width applications (ms range). Some technological issues and design criteria of the proposed circuit main sub-systems (solid state switch, pulse transformer, undershoot network, droop compensation bouncer) will be presented. The principle of the klystron arc detection electronics and protection strategy is described. An optimization will be developed allowing the achievement of the required pulse flat-top precision (1%) with minimum volume and costs. Finally, experimental results obtained on a resistive dummy load and on a 1.3 MW klystron will be presented and discussed.

  15. BIOMECHANICAL ENGINEERING SubPlan Requirements

    E-Print Network [OSTI]

    Cafarella, Michael J.

    BIOMECHANICAL ENGINEERING SubPlan Requirements Campus: UMICH RG = Requirement Group Career:UENG RQ = Requirement Program: LN = Line Plan: 0880BSE Sub-Plan: BIOMECH RG 6860 BIOMECHANICAL CONCENTRATION

  16. Theoretical investigation of the design and performance of a dual energy (kV and MV) radiotherapy imager

    SciTech Connect (OSTI)

    Liu, Langechuan; Antonuk, Larry E. El-Mohri, Youcef; Zhao, Qihua; Jiang, Hao

    2015-04-15

    Purpose: In modern radiotherapy treatment rooms, megavoltage (MV) portal imaging and kilovoltage (kV) cone-beam CT (CBCT) imaging are performed using various active matrix flat-panel imager (AMFPI) designs. To expand the clinical utility of MV and kV imaging, MV AMFPIs incorporating thick, segmented scintillators and, separately, kV imaging using a beam’s eye view geometry have been investigated by a number of groups. Motivated by these previous studies, it is of interest to explore to what extent it is possible to preserve the benefits of kV and MV imaging using a single AMFPI design, given the considerably different x ray energy spectra used for kV and MV imaging. In this paper, considerations for the design of such a dual energy imager are explored through examination of the performance of a variety of hypothetical AMFPIs based on x ray converters employing segmented scintillators. Methods: Contrast, noise, and contrast-to-noise ratio performances were characterized through simulation modeling of CBCT imaging, while modulation transfer function, Swank factor, and signal performance were characterized through simulation modeling of planar imaging. The simulations were based on a previously reported hybrid modeling technique (accounting for both radiation and optical effects), augmented through modeling of electronic additive noise. All designs employed BGO scintillator material with thicknesses ranging from 0.25 to 4 cm and element-to-element pitches ranging from 0.508 to 1.016 mm. A series of studies were performed under both kV and MV imaging conditions to determine the most advantageous imager configuration (involving front or rear x ray illumination and use of a mirror or black reflector), converter design (pitch and thickness), and operating mode (pitch-binning combination). Results: Under the assumptions of the present study, the most advantageous imager design was found to employ rear illumination of the converter in combination with a black reflector, incorporate a BGO converter with a 0.508 mm pitch and a 2 cm thickness, and operate at full resolution for kV imaging and 2 × 2 binning mode for MV imaging. Such a dual energy imager design should provide soft tissue visualization at low, clinically practical doses under MV conditions, while helping to preserve the high spatial resolution and high contrast offered by kV imaging. Conclusions: The authors’ theoretical investigation suggests that a dual energy imager capable of largely preserving the desirable characteristics of both kV and MV imaging is feasible. Such an imager, when coupled to a dual energy radiation source, could facilitate simplification of current treatment room imaging systems (as well as their associated quality assurance), and facilitate more precise integration of kV and MV imaging information by virtue of reduced geometric uncertainties.

  17. Tesla transformer based 500 kv pulser for low emittance test stand at Paul Scherrer Institute

    E-Print Network [OSTI]

    Paraliev, M; Ivkovic, S

    2011-01-01

    For the Low Emittance Gun (LEG) project at Paul Scherrer Institute a stable and reliable high voltage pulsed generator was needed in order to study low emittance beams generation and transport. The system had to provide variable asymmetric voltage pulse up to -500 kV with amplitude stability better than 1.2 part per thousand (ppt). The pulse should be applied to the cathode of variable gap accelerating diode providing voltage gradients up to more than 100 MV/m. A broad bandwidth electrical connection to the cathode is necessary in order to deliver fast cathode gating signal. The design of the pulser is presented as well as the optimization and implementation of some critical components in the system. A detailed electrical model of the pulsed generator was created in order to optimize and study its electrical behavior. The measured waveforms are compared to the simulated ones and output amplitude stability is discussed. Different electrode materials and surface treatments were studied to ensure breakdown free ...

  18. SU-E-J-214: Comparative Assessment On IGRT On Partial Bladder Cancer Treatment Between CT-On-Rails (CTOR) and KV Cone Beam CT (CBCT)

    SciTech Connect (OSTI)

    Lin, T; Ma, C

    2014-06-01

    Purpose: Image-Guided radiation therapy(IGRT) depends on reliable online patient-specific anatomy information to address random and progressive anatomy changes. Large margins have been suggested to bladder cancer treatment due to large daily bladder anatomy variation. KV Cone beam CT(CBCT) has been used in IGRT localization prevalently; however, its lack of soft tissue contrast makes clinicians hesitate to perform daily soft tissue alignment with CBCT for partial bladder cancer treatment. This study compares the localization uncertainties of bladder cancer IGRT using CTon- Rails(CTOR) and CBCT. Methods: Three T2N0M0 bladder cancer patients (total of 66 Gy to partial bladder alone) were localized daily with either CTOR or CBCT for their entire treatment course. A total of 71 sets of CTOR and 22 sets of CBCT images were acquired and registered with original planning CT scans by radiation therapists and approved by radiation oncologists for the daily treatment. CTOR scanning entailed 2mm slice thickness, 0.98mm axial voxel size, 120kVp and 240mAs. CBCT used a half fan pelvis protocol from Varian OBI system with 2mm slice thickness, 0.98axial voxel size, 125kVp, and 680mAs. Daily localization distribution was compared. Accuracy of CTOR and CBCT on partial bladder alignment was also evaluated by comparing bladder PTV coverage. Results: 1cm all around PTV margins were used in every patient except target superior limit margin to 0mm due to bowel constraint. Daily shifts on CTOR averaged to 0.48, 0.24, 0.19 mms(SI,Lat,AP directions); CBCT averaged to 0.43, 0.09, 0.19 mms(SI,Lat,AP directions). The CTOR daily localization showed superior results of V100% of PTV(102% CTOR vs. 89% CBCT) and bowel(Dmax 69.5Gy vs. 78Gy CBCT). CTOR images showed much higher contrast on bladder PTV alignment. Conclusion: CTOR daily localization for IGRT is more dosimetrically beneficial for partial bladder cancer treatment than kV CBCT localization and provided better soft tissue PTV identification.

  19. EA-1863: Vegetation Management on the Glen Canyon-Pinnacle Peak Transmission Lines Spanning the Coconino National Forest, Coconino County, Arizona

    Broader source: Energy.gov [DOE]

    DOE’s Western Area Power Administration is preparing this EA to evaluate the environmental impacts of updating the vegetation management and right-of-way maintenance program for Western’s Glen Canyon to Pinnacle Peak 345-kV transmission lines, which cross the Coconino National Forest, Coconino County, Arizona.

  20. Budget & Planning Strategic Plan

    E-Print Network [OSTI]

    Harms, Kyle E.

    Budget & Planning Strategic Plan Strategic Goal 1: Maintain a suitably staffed, effective the budget and planning needs of the institution. Strategic Goal 5: Identify ways in which B&P information and training opportunities to remain at the forefront of national trends Strategic Goal 2: Continue to meet

  1. Management Plan Management Plan

    E-Print Network [OSTI]

    Management Plan Management Plan "Management and restoration programs for native salmonids have communities" J. Lichatowich et al. 1998. A Conceptual Foundation for the Management of Native Salmonids in the Deschutes River. The Management Plan consists of five elements described in the Council's program: 1

  2. Sewer Line Planning: Choosing Optimal Routings

    E-Print Network [OSTI]

    Gross, Louis J.

    . Several different criteria such as maximization of the return to KUB, maximization of the fraction. This cost covers both the cost of materials and excavation. 7. Example: for 20 houses, and 4 do not want of like the Communist Party in the old Soviet Union). After the pipes are laid, all new income is revenue

  3. EA-2002: Right-of-Way Application for the Tucson-Apache 115-kV...

    Broader source: Energy.gov (indexed) [DOE]

    the potential environmental impacts of a proposal for BIA to grant Western a 150-foot right-of-way across tribal land along the existing Tucson-Apache Transmission Line to...

  4. A New 500-kV Ion Source Test Stand for HIF

    E-Print Network [OSTI]

    2000-01-01

    including surface, plasma and metal vapor arcs. This paperemitters, RF-driven plasmas and metal vapor arcs. This paperplasma source. Future plans also call for evaluating the properties of a metal vapor arc

  5. Emailed Comments of Elizabeth Chimento RE: Pepco Scheduled Line...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Scheduled Line Repair Dec. 1-20, 2006 Docket No. EO-05-01. Regarding the planned line outage, scheduled for Feb. 20 through Mar. 6, I am requesting that the residents near the...

  6. Proposed Southline Transmission Line Project - Volume 4 of 4...

    Office of Environmental Management (EM)

    2 Appendix J J-1 Southline Transmission Line Project Draft Environmental Impact Statement and Draft Resource Management Plan Amendment BLM LAND USE AUTHORIZATIONS 1...

  7. Section 1222 Program - Proposed Plains & Eastern Clean Line Project...

    Energy Savers [EERE]

    Electricity Policy Coordination and Implementation Transmission Planning Section 1222 of the Energy Policy Act 2005 Proposed Project: Plains & Eastern Clean Line ...

  8. DMBC: Web Planning & Layouts Above the Fold

    E-Print Network [OSTI]

    Stowell, Michael

    DMBC: Web Planning & Layouts Above the Fold · Website width · Website Height · Important content · From an Image Web Layouts Photoshop · Canvas Size · Guide Lines · Shapes #12;· Text (Lorem Ipsum

  9. HUNTER COLLEGE SENATE STRATEGIC PLANNING COMMITTEE

    E-Print Network [OSTI]

    Qiu, Weigang

    HUNTER COLLEGE SENATE STRATEGIC PLANNING COMMITTEE Meeting Minutes: April 7, 2010 Committee Members approved by unanimous consent. II. Overview of Strategic Planning Work Plan and Time Line Anthony Knerr (AK perspective while working at the campus level. The Strategic Planning Committee can help contextualize

  10. High-voltage switchgear and controlgear part 200 : AC metal-enclosed switchgear and controlgear for rated voltages above 1 kV and up to and including 52 kV

    E-Print Network [OSTI]

    International Electrotechnical Commission. Geneva

    2011-01-01

    Specifies requirements for factory-assembled metal-enclosed switchgear and controlgear for alternating current of rated voltages above 1 kV and up to and including 52 kV for indoor and outdoor installation, and for service frequencies up to and including 60 Hz. Enclosures may include fixed and removable components and may be filled with fluid (liquid or gas) to provide insulation. This standard defines several types of metal enclosed switchgear and controlgear which differ due to - the consequences on network service continuity in case of maintenance on the switchgear and controlgear; - the need and convenience of maintenance of the equipment. For metal-enclosed switchgear and controlgear containing gas-filled compartments, the design pressure is limited to a maximum of 300 kPa (relative pressure). Metal-enclosed switchgear and controlgear for special use, for example, in flammable atmospheres, in mines or on board ships, may be subject to additional requirements. Components contained in metal-enclosed switch...

  11. OPERATIONAL RESULTS OF THE SPALLATION NEUTRON SOURCE (SNS) POLYPHASE CONVERTER-MODULATOR FOR THE 140 KV KLYSTRON RF SYSTEMS

    SciTech Connect (OSTI)

    W.A. REASS; J.D. DOSS; ET AL

    2001-06-01

    This paper describes the first operational results of the 140 kV, 1 MW average, 11 MW peak, zero-voltage-switching, 20 kHz polyphase bridge, boost converter-modulator for klystron pulse application. The DC-DC converter derives the buss voltages from a standard 13.8 kV to 2100 Y substation cast-core transformer. Energy storage and filtering is provided by self-clearing metallized hazy polypropylene traction capacitors. Three ''H-Bridge'' Insulated Gate Bipolar Transistor (IGBT) switching networks are used to generate the polyphase 20 kHz transformer primary drive waveforms. The 20 kHz drive waveforms are chirped the appropriate duration to generate the desired klystron pulse width. Pulse-Width Modulation (PWM) of the individual 20 kHz pulses is utilized to provide regulated output waveforms with adaptive feedforward and feedback techniques. The boost transformer design utilizes amorphous nanocrystalline material that provides the required low core loss at design flux levels and switching frequencies. Resonant shunt peaking is used on the transformer secondary to boost output voltage and resonate transformer leakage inductance. With the appropriate transformer leakage inductance and peaking capacitance, zero-voltage-switching of the IGBT's is attained, minimizing switching losses. Reviews of these design parameters and an examination of the first operational results will be performed.

  12. EIS-0400: Granby Pumping Plant Switchyard-Windy Gap Substation Transmission Line Rebuild Project, Grand County, CO

    Broader source: Energy.gov [DOE]

    Western Area Power Administration prepared an EIS, with the U.S. Forest Service, Bureau of Land Management, and Grand County (Colorado) as cooperating agencies, to evaluate the potential environmental impacts of rebuilding a 12-mile, 69 kV electric transmission line in Grand County. The proposed project would rebuild the single-circuit line as a double-circuit transmission line and add a second power transformer. Western identified potentially significant impacts while preparing an EA for this proposal (DOE/EA-1520) and prepared an EIS instead of completing the EA. Further information about the project is available on the project website.

  13. Abstract Number #10041 A 150kV/300A/1s COAXIAL BLUMLEIN PULSER

    E-Print Network [OSTI]

    @plasma.inpe.br Abstract Blumlein pulsers are well-suited devices for high voltage pulse generation in the range of µs voltage of nV for an open end or else nV/2 for the case of a load nZ0 matched to the generator output a construction method that minimizes these losses and reduces the generator size by using coaxial lines coiled up

  14. EIS-0091: Garrison-Spokane 500-kV Transmission Project

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy's Bonneville Power Administration (BPA) developed this statement to evaluate the environmental impacts of constructing between 254 and 271 miles of 500-kilovolt transmission line across western Montana and northern Idaho to the Spokane area in order to reinforce a section of the BPA electric power grid and to permit reliable integration of 1,240 megawatts of power produced by Colstrip Units 3 and 4, for use in Montana and throughout the Northwest.

  15. ENGINEERING PHYSICS BSE Plan Requirements

    E-Print Network [OSTI]

    Cafarella, Michael J.

    ENGINEERING PHYSICS BSE Plan Requirements 1 Campus: UMICH RG = Requirement Group Career: UENG RQ = Requirement Program: LN = Line Plan: 2990BSE RG 6394 ENGINEERING PHYSICS MAJOR REQUIREMENTS Effective FA12/1910 (09/04/2012) RQ 4925 Physics Technical Subjects (C or higher) Effective FA12/1910 (09/04/2012) LN 0010

  16. MUS Pension Taskforce: 401(a) and 403(b) Plan RFP

    E-Print Network [OSTI]

    Maxwell, Bruce D.

    3/19/2014 1 MUS Pension Taskforce: 401(a) and 403(b) Plan RFP rationale and status update MSU of the individual offerings in the plan line-up. They only offer TIAA-CREF funds. 2. The 403(b) plan: Multi with other retirement plans in Big Sky Conference? 5 Constraints on current 401(a) and 403(b) Plans preclude

  17. Experimental investigations of overvoltages in 6kV station service cable networks of thermal power plants

    SciTech Connect (OSTI)

    Vukelja, P.I.; Naumov, R.M.; Drobnjak, G.V.; Mrvic, J.D. [Nikola Tesla Inst., Belgrade (Yugoslavia)

    1996-12-31

    The paper presents the results of experimental investigations of overvoltages on 6kV isolated neutral station service cable networks of thermal power plants. The overvoltages were recorded with capacitive voltage measurement systems made at the Nikola Tesla Institute. Wideband capacitive voltage measurement systems recorded a flat response from below power frequencies to 10MHz. Investigations of overvoltages were performed for appearance and interruption of metal earth faults, intermittent earth faults, switching operation of HV motors switchgear, switching operation of transformers switchgear, and transfer of the network supply from one transformer to another. On the basis of these investigations, certain measures are proposed for limiting overvoltages and for the reliability of station service of thermal power plants.

  18. Task Plans

    Office of Environmental Management (EM)

    Task Plans This page contains links to a tentative listing of active and closed TEC Task Plans. Final status of these task plans will be determined after the July 2000 TEC meeting....

  19. EA-0587: Proposed Amendment to Presidential Permit PP-63 and Associated Modification to 500 kV International Transmission Line: Forbes, Minnesota to Manitoba, Canada

    Broader source: Energy.gov [DOE]

    This EA evaluates the environmental impacts of Northern States Power Company's  proposal to expand the Forbes Substation in Minnesota.

  20. Guidelines for strategic planning

    SciTech Connect (OSTI)

    Not Available

    1991-07-01

    Strategic planning needs to be done as one of the integral steps in fulfilling our overall Departmental mission. The role of strategic planning is to assure that the longer term destinations, goals, and objectives which the programs and activities of the Department are striving towards are the best we can envision today so that our courses can then be set to move in those directions. Strategic planning will assist the Secretary, Deputy Secretary, and Under Secretary in setting the long-term directions and policies for the Department and in making final decisions on near-term priorities and resource allocations. It will assist program developers and implementors by providing the necessary guidance for multi-year program plans and budgets. It is one of the essential steps in the secretary's Strategic Planning Initiative. The operational planning most of us are so familiar with deals with how to get things done and with the resources needed (people, money, facilities, time) to carry out tasks. Operating plans like budgets, capital line item projects, R D budgets, project proposals, etc., are vital to the mission of the Department. They deal, however, with how to carry out programs to achieve some objective or budget assumption. Strategic planning deals with the prior question of what it is that should be attempted. It deals with what objectives the many programs and activities of the Department of Department should be striving toward. The purpose of this document is to provide guidance to those organizations and personnel starting the process for the first time as well as those who have prepared strategic plans in the past and now wish to review and update them. This guideline should not be constructed as a rigid, restrictive or confining rulebook. Each organization is encouraged to develop such enhancements as they think may be useful in their planning. The steps outlined in this document represent a very simplified approach to strategic planning. 9 refs.

  1. NOAA Office of Program Planning and Integration

    E-Print Network [OSTI]

    : · continuing to foster strategic management process among NOAA Line and Staff Offices, Goal Teams, Programs's Strategic Vision by Developing and evolving of NOAA's Strategic Plan Managing designated programs accordingNOAA Office of Program Planning and Integration STRATEGIC PLAN FY 2005 ­ FY 2010 U.S. Department

  2. UW-Milwaukee Strategic Planning Core Team

    E-Print Network [OSTI]

    Saldin, Dilano

    UW-Milwaukee Strategic Planning Core Team Minutes Tuesday, December 18, 2012 Regents Room, Chapman" because there will be further wordsmithing when governance groups weigh in later. 3. Strategic Planning Schematic (attached) Strategic planning and action time line was disseminated to team Explained

  3. NSLS-II Transport Line Progress

    SciTech Connect (OSTI)

    Fliller R. P.; Wahl, W.; Anderson, A.; Benish, B.; DeBoer, W.; Ganetis, G.; Heese, R.; Hseuh, H.-C.; Hu, J.-P.; Johanson, M.P.; Kosciuk, B.N.; Padrazo, D.; Roy, K.; Shaftan, T.; Singh, O.; Tuozzolo, J.; Wang, G.

    2012-05-20

    The National Synchrotron Light Source II (NSLS-II) is a state-of-the-art 3-GeV third generation light source currently under construction at Brookhaven National Laboratory. The NSLS-II injection system consists of a 200 MeV linac, a 3-GeV booster synchrotron and associated transfer lines. The first part of the Linac to Booster Transport (LBT) line has been installed for linac commissioning. This part includes all components necessary to commission the NSLS-II linac. The second part of this transport line is undergoing installation. Initial results of hardware commissioning will be discussed. The Booster to Storage Ring (BSR) transport line underwent a design review. The first part of the BSR transport line, consisting of all components necessary to commission the booster will be installed in 2012 for booster commissioning. We report on the final design of the BSR line along with the plan to commission the booster.

  4. Hemodynamic Monitoring TRANSTHORACIC LINES

    E-Print Network [OSTI]

    Kay, Mark A.

    and with position changes. 5. All lines should have either heparinized saline or D5W infusing. 6. Avoid infusing the line. 9. Never use LA for infusions or bolus medications. 10. Vigilant observation for AIR. B. Line

  5. Incoherence and Incompatibility in Planning Law

    E-Print Network [OSTI]

    Lees, Emma; Shepherd, Edward

    2015-01-01

    , and for the courts to determine. This gives them a double responsibility. Firstly, they may choose to interpret the local plan differently from the local decision-maker so as to artificially or otherwise bring it into line with the NPPF. An alternative tactic... ), “Sustainability: a new vision for the British planning system”, Planning Perspectives, Vol. 15, pp. 123 – 137. ? Fagence, M. (1983), “Ideological fundamentalism in town planning - an exploratory appraisal”, The Environmentalist, Vol. 16, pp. 17 – 27. ? Foley...

  6. Plains and Eastern Clean Line Transmission Line: Comment from...

    Energy Savers [EERE]

    Plains and Eastern Clean Line Transmission Line: Comment from Marshall Hughes Plains and Eastern Clean Line Transmission Line: Comment from Marshall Hughes Comment submitted on...

  7. Plains and Eastern Clean Line Transmission Line: Comment from...

    Office of Environmental Management (EM)

    from Block Plains and Eastern Clean Line: Arkansas and Oklahoma Plains and Eastern Clean Line Transmission Line: Comment from Block Plains and Eastern Clean Line: Arkansas and...

  8. Development of a 33 kV, 20 A long pulse converter modulator for high average power klystron

    SciTech Connect (OSTI)

    Reghu, T.; Mandloi, V.; Shrivastava, Purushottam [Pulsed High Power Microwave Section, Raja Ramanna Centre for Advanced Technology, Indore 452013, M.P. (India)] [Pulsed High Power Microwave Section, Raja Ramanna Centre for Advanced Technology, Indore 452013, M.P. (India)

    2014-05-15

    Research, design, and development of high average power, long pulse modulators for the proposed Indian Spallation Neutron Source are underway at Raja Ramanna Centre for Advanced Technology. With this objective, a prototype of long pulse modulator capable of delivering 33 kV, 20 A at 5 Hz repetition rate has been designed and developed. Three Insulated Gate Bipolar Transistors (IGBT) based switching modules driving high frequency, high voltage transformers have been used to generate high voltage output. The IGBT based switching modules are shifted in phase by 120° with respect to each other. The switching frequency is 25 kHz. Pulses of 1.6 ms pulse width, 80 ?s rise time, and 70 ?s fall time have been achieved at the modulator output. A droop of ±0.6% is achieved using a simple segmented digital droop correction technique. The total fault energy transferred to the load during fault has been measured by conducting wire burn tests and is found to be within 3.5 J.

  9. Canby Area Service Project substation and associated transmission line. Environmental Assessment

    SciTech Connect (OSTI)

    Not Available

    1992-02-01

    Bonneville Power Administration (BPA) provides power to Surprise Valley Electrification Corporation (SVEC) in Modoc County, California. BPA uses PacificCorp`s substation and transmission facilities between Alturas and Canby, California to transfer power to SVEC`s Canby Substation. In the next year, SVEC expects increased industrial, agricultural, and residential electric loads on their 69-kV transmission system south of Canby. SVEC`s substation can accommodate only about 10 percent of the expected additional electric load. BPA`s proposed action is intended to meet SVEC`s increasing electric load. BPA proposes to meet SVEC`s increasing energy load by tapping into BPA`s existing BPA Malin-Warner 230-kV transmission line, and building an 7.9-mile transmission line to a new BPA substation. BPA proposes to build the new substation next to the west side of SVEC`s Canby Substation (Figure 1). This new substation will allow SVEC to move the additional power over their existing transmission or distribution lines. This report is the environmental assessment of the potential impact of the proposed project. The assessment determined that no ``environmental impact statement`` is not required.

  10. Canby Area Service Project : Substation and Associated Transmission Line : Environmental Assessment.

    SciTech Connect (OSTI)

    United States. Bonneville Power Administration.

    1992-02-01

    Bonneville Power Administration (BPA) provides power to Surprise Valley Electrification Corporation (SVEC) in Modoc County, California. BPA uses PacificCorp's substation and transmission facilities between Alturas and Canby, California to transfer power to SVEC's Canby Substation. In the next year, SVEC expects increased industrial, agricultural, and residential electric loads on their 69-kV transmission system south of Canby. SVEC's substation can accommodate only about 10 percent of the expected additional electric load. BPA's proposed action is intended to meet SVEC's increasing electric load. BPA proposes to meet SVEC's increasing energy load by tapping into BPA's existing BPA Malin-Warner 230-kV transmission line, and building an 7.9-mile transmission line to a new BPA substation. BPA proposes to build the new substation next to the west side of SVEC's Canby Substation (Figure 1). This new substation will allow SVEC to move the additional power over their existing transmission or distribution lines. This report is the environmental assessment of the potential impact of the proposed project. The assessment determined that no environmental impact statement'' is not required.

  11. Standard Review Plan Preparation for Facility Operations Strengthening...

    Office of Environmental Management (EM)

    Facility Operations Strengthening Line Management Oversight and Federal Monitoring of Nuclear Facilities August 2013 2 OFFICE OF ENVIRONMENTAL MANAGEMENT Standard Review Plan...

  12. Proactive Planning 

    E-Print Network [OSTI]

    Wythe, Kathy

    2008-01-01

    an opportunity to voice their opinions and help draft the watershed protection plan for the reservoir. The plan, which will outline ways to reduce pollution and improve water quality, is an outgrowth of years of water quality monitoring and research by TRWD... in stakeholder-based watershed protection planning focused on holistic solutions to water pollution by exam- ining the impacts of upstream activities. Watershed-based planning is a relatively new approach to pollution reduction in all sizes of water bodies...

  13. A framework for on-line simulation systems 

    E-Print Network [OSTI]

    Drake, Glenn Richardson

    1996-01-01

    Simulation has traditionally been used for off-line planning and design. The advent of computer integrated manufacturing and flexible manufacturing systems has increased interest in shop floor control systems that use ...

  14. Public Opinions of Building Additional High-Voltage Electric Power Lines

    E-Print Network [OSTI]

    Tesfatsion, Leigh

    Public Opinions of Building Additional High-Voltage Electric Power Lines A Report to the National-Voltage Electric Power Lines: A Report to the National Science Foundation and the Electric Power Research Center to build new power lines. Residents living in counties with planned routes for new transmission lines

  15. DC power supply for charging of a 12 KV 200 KJ energy storage capacitor battery of a 500 KA pulse system for the magnetic horn and reflectors of the CERN neutrino beam

    E-Print Network [OSTI]

    Langeseth, B

    1968-01-01

    DC power supply for charging of a 12 KV 200 KJ energy storage capacitor battery of a 500 KA pulse system for the magnetic horn and reflectors of the CERN neutrino beam

  16. Racing line optimization

    E-Print Network [OSTI]

    Xiong, Ying, S.M. Massachusetts Institute of Technology

    2010-01-01

    Although most racers are good at controlling their cars, world champions are always talented at choosing the right racing line while others mostly fail to do that. Optimal racing line selection is a critical problem in car ...

  17. Number of lightning discharges causing damage to lightning arrester cables for aerial transmission lines in power systems

    SciTech Connect (OSTI)

    Nikiforov, E. P. [Electric Power Scientific Research Institute (VNIIE), branch of OAO 'NTTs Elektroenergetika' (Russian Federation)

    2009-07-15

    Damage by lightning discharges to lightning arrester cables for 110-175 kV aerial transmission lines is analyzed using data from power systems on incidents with aerial transmission lines over a ten year operating period (1997-2006). It is found that failures of lightning arrester cables occur when a tensile force acts on a cable heated to the melting point by a lightning current. The lightning currents required to heat a cable to this extent are greater for larger cable cross sections. The probability that a lightning discharge will develop decreases as the amplitude of the lightning current increases, which greatly reduces the number of lightning discharges which damage TK-70 cables compared to TK-50 cables. In order to increase the reliability of lightning arrester cables for 110 kV aerial transmission lines, TK-70 cables should be used in place of TK-50 cables. The number of lightning discharges per year which damage lightning arrester cables is lowered when the density of aerial transmission lines is reduced within the territory of electrical power systems. An approximate relationship between these two parameters is obtained.

  18. EIS-0486: Plains & Eastern Clean Line Transmission Project |...

    Broader source: Energy.gov (indexed) [DOE]

    Project. The proposed project would include an overhead 600 kilovolt (kV) high voltage direct current (HVDC) electric transmission system and associated facilities with the...

  19. Case Study of the Failure of two 13.8kV Control & Metering Transformers that caused significant Equipment Damage

    SciTech Connect (OSTI)

    Dreifuerst, G R; Chew, D B; Mangonon, H L; Swyers, P W

    2011-08-25

    The degradation and failure of cast-coil epoxy windings within 13.8kV control power transformers and metering potential transformers has been shown to be dangerous to both equipment and personnel, even though best industrial design practices were followed. Accident scenes will be examined for two events at a U.S. Department of Energy laboratory. Failure modes will be explained and current design practices discussed with changes suggested to prevent a recurrence and to minimize future risk. New maintenance philosophies utilizing partial discharge testing of the transformers as a prediction of end-of-life will be examined.

  20. EC Transmission Line Risk Identification and Analysis

    SciTech Connect (OSTI)

    Bigelow, Tim S

    2012-04-01

    The purpose of this document is to assist in evaluating and planning for the cost, schedule, and technical project risks associated with the delivery and operation of the EC (Electron cyclotron) transmission line system. In general, the major risks that are anticipated to be encountered during the project delivery phase associated with the implementation of the Procurement Arrangement for the EC transmission line system are associated with: (1) Undefined or changing requirements (e.g., functional or regulatory requirements) (2) Underperformance of prototype, first unit, or production components during testing (3) Unavailability of qualified vendors for critical components Technical risks associated with the design and operation of the system are also identified.

  1. Concurrent Wind Cooling in Power Transmission Lines

    SciTech Connect (OSTI)

    Jake P Gentle

    2012-08-01

    Idaho National Laboratory and the Idaho Power Company, with collaboration from Idaho State University, have been working on a project to monitor wind and other environmental data parameters along certain electrical transmission corridors. The combination of both real-time historical weather and environmental data is being used to model, validate, and recommend possibilities for dynamic operations of the transmission lines for power and energy carrying capacity. The planned results can also be used to influence decisions about proposed design criteria for or upgrades to certain sections of the transmission lines.

  2. Building Registration Plans (Plan Ahead)

    E-Print Network [OSTI]

    Pavlov, Ronnie

    or edit plans you've already created. #12;Now enter your course search requirements. Then click the Search not be offered in the term you are creating. You can search by Subject, Course Number, Keyword, Title, Level to the Registration Screen, click on Plan Ahead. Next, you need to select the term for which you wish to create

  3. Series Transmission Line Transformer

    DOE Patents [OSTI]

    Buckles, Robert A. (Livermore, CA); Booth, Rex (Livermore, CA); Yen, Boris T. (El Cerrito, CA)

    2004-06-29

    A series transmission line transformer is set forth which includes two or more of impedance matched sets of at least two transmissions lines such as shielded cables, connected in parallel at one end ans series at the other in a cascading fashion. The cables are wound about a magnetic core. The series transmission line transformer (STLT) which can provide for higher impedance ratios and bandwidths, which is scalable, and which is of simpler design and construction.

  4. ENVIRONMENTAL ENGINEERING BSE PLAN REQUIREMENTS Campus: UMICH RG = Requirement Group

    E-Print Network [OSTI]

    Cafarella, Michael J.

    ENVIRONMENTAL ENGINEERING BSE PLAN REQUIREMENTS Campus: UMICH RG = Requirement Group Career: UENG RQ = Requirement Program: LN = Line Plan: 3170BSE Sub-Plan: RG 10370 ENVIRONMENTAL ENGINEERING MAJOR LN 0020 CEE 481 or 581 LN 0030 CEE 482 or 582 RQ 6790 Environmental Engineering Design Effective FA12

  5. BIOMEDICAL ENGINEERING BSE PLAN REQUIREMENTS Campus: UMICH RG = Requirement Group

    E-Print Network [OSTI]

    Cafarella, Michael J.

    BIOMEDICAL ENGINEERING BSE PLAN REQUIREMENTS Campus: UMICH RG = Requirement Group Career: UENG RQ = Requirement Program: LN = Line Plan: 0880BSE Sub-Plan: RG 6856 BIOMEDICAL ENGINEERING MAJOR REQUIREMENTS Effective FA05/1560 (09/06/2005) RQ 4996 Program Subjects Effective FA05/1560 (09/06/2005) LN 0010 BIOMEDE

  6. Transmission Line Security Monitor

    ScienceCinema (OSTI)

    None

    2013-05-28

    The Transmission Line Security Monitor is a multi-sensor monitor that mounts directly on high-voltage transmission lines to detect, characterize and communicate terrorist activity, human tampering and threatening conditions around support towers. For more information about INL's critical infrastructure protection research, visit http://www.facebook.com/idahonationallaboratory.

  7. Transmission Line Security Monitor

    SciTech Connect (OSTI)

    2011-01-01

    The Transmission Line Security Monitor is a multi-sensor monitor that mounts directly on high-voltage transmission lines to detect, characterize and communicate terrorist activity, human tampering and threatening conditions around support towers. For more information about INL's critical infrastructure protection research, visit http://www.facebook.com/idahonationallaboratory.

  8. Palouse Subbasin Management Plan 3. Management Plan

    E-Print Network [OSTI]

    Palouse Subbasin Management Plan 3. Management Plan FINAL DRAFT ~ May 2004 Project Lead: Palouse-Rock Lake Conservation District Trevor Cook, Project Manager PO Box 438 St. John WA 99171 (509) 648;Palouse Subbasin Plan: MANAGEMENT PLAN Management Plan: Page 3 - 1 3. Management Plan 3.1 Background

  9. 1 Introduction Nowadays more people are in favor of removing the

    E-Print Network [OSTI]

    Bak, Claus Leth

    the changes in the reactive power balance in the grid and save cost of switchgear for the reactor is a planned 18,5 km underground cable line from 60 kV substation Ålbæk to 60 kV substation Hedebo in ENV

  10. Coherent soliton communication lines

    SciTech Connect (OSTI)

    Yushko, O. V. Redyuk, A. A.; Fedoruk, M. P.; Turitsyn, S. K.

    2014-11-15

    The data transmission in coherent fiber-optical communication lines using solitons with a variable phase is studied. It is shown that nonlinear coherent structures (solitons) can be applied for effective signal transmission over a long distance using amplitude and optical-phase keying of information. The optimum ratio of the pulse width to the bit slot at which the spectral efficiency (transmitted bits per second and hertz) is maximal is determined. It is shown that soliton fiber-optical communication lines can ensure data transmission at a higher spectral efficiency as compared to traditional communication lines and at a high signal-to-noise ratio.

  11. Power line detection system

    DOE Patents [OSTI]

    Latorre, V.R.; Watwood, D.B.

    1994-09-27

    A short-range, radio frequency (RF) transmitting-receiving system that provides both visual and audio warnings to the pilot of a helicopter or light aircraft of an up-coming power transmission line complex. Small, milliwatt-level narrowband transmitters, powered by the transmission line itself, are installed on top of selected transmission line support towers or within existing warning balls, and provide a continuous RF signal to approaching aircraft. The on-board receiver can be either a separate unit or a portion of the existing avionics, and can also share an existing antenna with another airborne system. Upon receipt of a warning signal, the receiver will trigger a visual and an audio alarm to alert the pilot to the potential power line hazard. 4 figs.

  12. Platzhalter Logo/Schriftzug (Anpassung im Folienmaster: Men Ansicht Folienmaster) 18.06.2015Christian M. Franck 1

    E-Print Network [OSTI]

    Grabner, Helmut

    infrastructure · Voltage increase 220kV 380kV 380kV 500kV · PMU / FACTS ­ devices [abb.com] #12;|| PlatzhalterV 380kV 380kV 500kV · PMU / FACTS ­ devices · High Temperature Conductors [abb.com] [3m.com] #12V 380kV 380kV 500kV · PMU / FACTS ­ devices · High Temperature Conductors · Dynamic Line Rating

  13. Leveraging infrastructure : sustainable bus rapid transit route planning in Beirut, Lebanon

    E-Print Network [OSTI]

    Nabti, Jumana M., 1976-

    2004-01-01

    This thesis applies the concepts of urban design, public transportation planning, economic development, and sustainability, to the routing and site plan of a two-kilometer bus rapid transit (BRT) line segment into downtown ...

  14. Transmission line capital costs

    SciTech Connect (OSTI)

    Hughes, K.R.; Brown, D.R.

    1995-05-01

    The displacement or deferral of conventional AC transmission line installation is a key benefit associated with several technologies being developed with the support of the U.S. Department of Energy`s Office of Energy Management (OEM). Previous benefits assessments conducted within OEM have been based on significantly different assumptions for the average cost per mile of AC transmission line. In response to this uncertainty, an investigation of transmission line capital cost data was initiated. The objective of this study was to develop a database for preparing preliminary estimates of transmission line costs. An extensive search of potential data sources identified databases maintained by the Bonneville Power Administration (BPA) and the Western Area Power Administration (WAPA) as superior sources of transmission line cost data. The BPA and WAPA data were adjusted to a common basis and combined together. The composite database covers voltage levels from 13.8 to 765 W, with cost estimates for a given voltage level varying depending on conductor size, tower material type, tower frame type, and number of circuits. Reported transmission line costs vary significantly, even for a given voltage level. This can usually be explained by variation in the design factors noted above and variation in environmental and land (right-of-way) costs, which are extremely site-specific. Cost estimates prepared from the composite database were compared to cost data collected by the Federal Energy Regulatory Commission (FERC) for investor-owned utilities from across the United States. The comparison was hampered because the only design specifications included with the FERC data were voltage level and line length. Working within this limitation, the FERC data were not found to differ significantly from the composite database. Therefore, the composite database was judged to be a reasonable proxy for estimating national average costs.

  15. BPA line crew puts innovative work plan into aerial action

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    links Newsroom News Releases About Us Freedom of Information Act Investor Relations Library Privacy Publications Tribal Affairs Newsroom Search News Articles... Search BPA...

  16. The Cost of Transmission for Wind Energy: A Review of Transmission Planning Studies

    E-Print Network [OSTI]

    Mills, Andrew D.

    2009-01-01

    Certificates of Need for Transmission Lines to Support theand Preference in Transmission Service. ” Washington, D.C. :Integrating Wind into Transmission Planning: The Rocky

  17. Waste minimization and pollution prevention awareness plan

    SciTech Connect (OSTI)

    Not Available

    1991-05-31

    The purpose of this plan is to document the Lawrence Livermore National Laboratory (LLNL) Waste Minimization and Pollution Prevention Awareness Program. The plan specifies those activities and methods that are or will be employed to reduce the quantity and toxicity of wastes generated at the site. The intent of this plan is to respond to and comply with (DOE's) policy and guidelines concerning the need for pollution prevention. The Plan is composed of a LLNL Waste Minimization and Pollution Prevention Awareness Program Plan and, as attachments, Program- and Department-specific waste minimization plans. This format reflects the fact that waste minimization is considered a line management responsibility and is to be addressed by each of the Programs and Departments. 14 refs.

  18. Planning while Executing: a Constraint-based R. Barru , M. Milano, and P. Torroni

    E-Print Network [OSTI]

    Torroni, Paolo

    Planning while Executing: a Constraint-based Approach R. Barru , M. Milano, and P. Torroni DEIS 2093073 frbarruffi, mmilano, ptorronig@deis.unibo.it Abstract. We propose a planning architecture where domain. According to the deferred planning strategy proposed in 14 , a plan schema is produced o -line

  19. Strategic Planning for Landowners 

    E-Print Network [OSTI]

    Johnson, Jason; Polk, Wade

    2008-09-16

    Strategic planning is crucial to the success of any business. This publication explains the planning process, from establishing the mission, to setting goals, to developing a business plan....

  20. Guidance for Planning Exercises

    Office of Environmental Management (EM)

    blank table of contents Transportation Emergency Preparedness Program (TEPP) planning tools planning tools Guidance f Guidance f Guidance f Guidance f Guidance for Planning,...

  1. Walkability Planning in Jakarta

    E-Print Network [OSTI]

    Lo, Ria S. Hutabarat

    2011-01-01

    key goals in relation to pedestrian planning? What trends dotransportation and planning in Jakarta in the future?pedestrian research or planning in Indonesia, the notion of

  2. Adaptation Plan 

    E-Print Network [OSTI]

    Durnbaugh, A.

    2011-01-01

    Response Update the extreme weather operation plan, focusing on vulnerable populations. Add climate-sensitive disease surveillance. Roads Pilot & implement new road materials to manage stormwater, decrease urban heat island effect, & maintain... and dry summers Source: Hayhoe et al. Journal of Great Lakes Research, 2010. Summers % changes relative to a 1961-1990 average ESL-KT-11-11-16 6 What is CCAP? Our goals to reduce Chicago?s greenhouse gas emissions and prepare for climate change?s...

  3. STRATEGIC PLAN

    Energy Savers [EERE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on DeliciousMathematics AndBeryllium Disease |Records Management FieldSOLANA SOLANA SOLANA SOLANA-2020 STRATEGIC PLAN and

  4. Plan Execution Failure Analysis Using Plan Deconstruction 

    E-Print Network [OSTI]

    McNeill, F.; Bundy, Alan; Walton, Ch.; Schorlemmer, Marco

    We consider the challenges that arise when plans are based on an incorrect representation of the domain in which they are executed. We describe how information about plan formation, and how the way in which each plan step ...

  5. VOLUME 4$, NUMBER 10 PHYSICAL RKVI K%V LKTTKRS $ SEPTEMBER 1979 Low-Energy Pion Production at 0' with Heavy Ions from 125 to 400 MeV/Nucleon

    E-Print Network [OSTI]

    Bertsch George F.

    VOLUME 4$, NUMBER 10 PHYSICAL RKVI K%V LKTTKRS $ SEPTEMBER 1979 Low-Energy Pion Production at 0 studies of pion production in such collisions with beam energies below 1 GeV/ nucleon are currently being meas- urements of pion-production cross sections at heavy-ion-beam energies much lower than pre

  6. GENERATION OF A 5A, 10kV HOLLOW ELECTRON BEAM BY A PIERCE GUN J.J. BARROSO, P.J. CASTRO, J.O. ROSSI, J.A.N. GONALVES, and H. PATIRE JR.

    E-Print Network [OSTI]

    GENERATION OF A 5A, 10kV HOLLOW ELECTRON BEAM BY A PIERCE GUN J.J. BARROSO, P.J. CASTRO, J.O. ROSSI experienced by the electron beam propagating across the cavity. Here we describe a Pierce gun used of short-circuits. PULSE GENERATOR VIEW GUN OPERATION The gun cathode voltage is fixed at the nominal value

  7. Pipe line companies to install 14,766 miles of lines in 1994

    SciTech Connect (OSTI)

    Ives, G. Jr.

    1994-01-01

    This paper reviews the historical and projected pipeline construction activities in the US and around the world. It gives mileage values for all types of oil and gas transmission lines, both on and offshore. Tables provides information on the diameters of these pipelines and information on compressor stations planned and constructed. Known major construction projects are listed by company name with a brief description of the proposed project.

  8. CHEMICAL HYGIENE PLAN HAZARD COMMUNICATION PLAN

    E-Print Network [OSTI]

    Kim, Duck O.

    Biological Safety Officer Ergonomic Specialist 2723 Radiation Safety 2250 Facilities Management Office 2125. ANNUAL REVIEW AND EVALUATION OF EFFECTIVENESS OF THE CHEMICAL HYGIENE PLAN 9. HAZARD COMMUNICATION PLAN

  9. Business Services Strategic Plan

    E-Print Network [OSTI]

    Pittendrigh, Barry

    Business Services Strategic Plan Updated September 2008 New Synergies: Launching Tomorrow's Leaders. Facilitate implementation of the University Strategic Plan 2. Analyze, plan, and manage University finances, processes, and contracts in global and strategic partnerships 3. Review existing capital financing plans

  10. Introduction to Transportation Planning

    E-Print Network [OSTI]

    Tipple, Brett

    Introduction to Transportation Planning CMP 4710/6710 Fall 2012 3 Credit Hours Room: ARCH 229 of City & Metropolitan Planning; Associate Dean, College of Architecture + Planning; former associate, social equity, fiscal health, and public health. Unfortunately, most transportation planning processes

  11. EIS-0379- Rebuild of the Libby (FEC) to Troy Section of BPA’s 115-kilovolt Transmission Line in Libby, Lincoln County, Montana

    Broader source: Energy.gov [DOE]

    This Environmental Impact Statement (EIS) assesses the potential environmental impacts that would result from a proposed Department of Energy (DOE) action on the proposed rebuilding, operation, and maintenance of a 17-mile-long portion of BPA’s Libby to Bonners Ferry 115-kilovolt (kV) Transmission Line in Lincoln County, Montana. The portion to be rebuilt would start at Flathead Electric Cooperative’s (FEC) Libby Substation, in the town of Libby, Montana, and proceed west along an existing right-of-way for about 17 miles, terminating at BPA’s Troy Substation just east of the town of Troy, Montana.

  12. State Waste Discharge Permit ST-4502 Implementation Plan

    SciTech Connect (OSTI)

    BROWN, M.J.; LECLAIR, M.D.

    2000-09-27

    Plan has been developed to demonstrate compliance with regulatory requirements set forth in Permit ST-3502 and as a line management tool for use in maintaining configuration control of permit as well as documentation used to implement permit requirements.

  13. Strategic Plan

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of NaturalDukeWakefieldSulfateSciTechtail.Theory ofDidDevelopment TopMetathesis and Oxidation of MetalStrategic Plan

  14. Dental Plan

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity ofkandz-cm11 Outreach Home Room NewsInformation Current HAB Packet HanfordDOEDanielDe novo DesignNeudeckerDental Plan Dental

  15. Work Plan

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantityBonneville Power AdministrationRobust,Field-effectWorking WithTelecentricNCubictheThepresented in the7 Table7Work &Work Plan

  16. Retirement Plans

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity ofkandz-cm11 Outreach Home RoomPreservation of Fe(II) byMultiday ProductionDesigningResources Thomas JeffersonRetirement Plan

  17. Retirement Plans

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity ofkandz-cm11 Outreach Home RoomPreservation of Fe(II) byMultiday ProductionDesigningResources Thomas JeffersonRetirement Plan

  18. Plans, Procedures

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity ofkandz-cm11 Outreach Home Room NewsInformationJesseworkSURVEYI/OPerformancePi Day Pi Day Pi Day isPlanning for Life On

  19. Printed circuit dispersive transmission line

    DOE Patents [OSTI]

    Ikezi, H.; Lin-Liu, Y.R.; DeGrassie, J.S.

    1991-08-27

    A printed circuit dispersive transmission line structure is disclosed comprising an insulator, a ground plane formed on one surface of the insulator, a first transmission line formed on a second surface of the insulator, and a second transmission line also formed on the second surface of the insulator and of longer length than the first transmission line and periodically intersecting the first transmission line. In a preferred embodiment, the transmission line structure exhibits highly dispersive characteristics by designing the length of one of the transmission line between two adjacent periodic intersections to be longer than the other. 5 figures.

  20. Printed circuit dispersive transmission line

    DOE Patents [OSTI]

    Ikezi, Hiroyuki (Rancho Santa Fe, CA); Lin-Liu, Yuh-Ren (San Diego, CA); DeGrassie, John S. (Encinitas, CA)

    1991-01-01

    A printed circuit dispersive transmission line structure is disclosed comprising an insulator, a ground plane formed on one surface of the insulator, a first transmission line formed on a second surface of the insulator, and a second transmission line also formed on the second surface of the insulator and of longer length than the first transmission line and periodically intersecting the first transmission line. In a preferred embodiment, the transmission line structure exhibits highly dispersive characteristics by designing the length of one of the transmission line between two adjacent periodic intersections to be longer than the other.

  1. Venus Technology Plan Venus Technology Plan

    E-Print Network [OSTI]

    Rathbun, Julie A.

    Venus Technology Plan May 2014 #12; ii Venus Technology Plan At the Venus Exploration Survey priorities, and (3) develop a Technology Plan for future Venus missions (after a Technology Forum at VEXAG Meeting 11 in November 2013). Here, we present the 2014 Venus Technology Plan

  2. Strategic Plan Strategic Plan 20102015 1

    E-Print Network [OSTI]

    Strategic Plan 2010­2015 #12;#12;#12;#12;Strategic Plan 2010­2015 1 Table of Contents Message from. . . . . . . . 36 #12;2 College of Geosciences Message from the Dean This strategic plan has come together in an era and #12;Strategic Plan 2010­2015 3 human capital. With respect to research it is clear that the College

  3. Strategic Plan update Strategic Plan 201020

    E-Print Network [OSTI]

    Rambaut, Andrew

    Strategic Plan update Strategic Plan 2010­20: Two-year update February 2012 #12;1 Strategic-year Wellcome Trust Strategic Plan for 2010­20. It describes how we will work to further our vision of achieving in our Annual Review and Assessment Framework Reports. Implementing our Strategic Plan ­ highlights

  4. Privacy Management Plan 1 Privacy Management Plan

    E-Print Network [OSTI]

    University of Technology, Sydney

    Privacy Management Plan 1 Privacy Management Plan Abstract The Privacy Management Plan outlines how Impact Assessment Tool (.docm) (staff only) Records Management Vice-Chancellor's Directive Handling Management Plan 2 Legislation Privacy and Personal Information Protection Act 1998 (NSW) (PPIPIA) Health

  5. Drill string transmission line

    DOE Patents [OSTI]

    Hall, David R. (Provo, UT); Hall, Jr., H. Tracy (Provo, UT); Pixton, David S. (Lehi, UT); Bradford, Kline (Orem, UT); Fox, Joe (Spanish Fork, UT)

    2006-03-28

    A transmission line assembly for transmitting information along a downhole tool comprising a pin end, a box end, and a central bore traveling between the pin end and the box end, is disclosed in one embodiment of the invention as including a protective conduit. A transmission line is routed through the protective conduit. The protective conduit is routed through the central bore and the ends of the protective conduit are routed through channels formed in the pin end and box end of the downhole tool. The protective conduit is elastically forced into a spiral or other non-linear path along the interior surface of the central bore by compressing the protective conduit to a length within the downhole tool shorter than the protective conduit.

  6. Probabilistic on-line transportation problems with carrying-capacity constraints

    E-Print Network [OSTI]

    Treleaven, Kyle (Kyle Ballantyne)

    2014-01-01

    This thesis presents new insights and techniques for the analysis and design of autonomous or technology-assisted ("intelligent") transportation systems. The focus is on cooperative, on-line planning and control, of a fleet ...

  7. NPIP: A skew line needle configuration optimization system for HDR brachytherapy

    E-Print Network [OSTI]

    Goldberg, Ken

    NPIP: A skew line needle configuration optimization system for HDR brachytherapy Timmy Siauwa) brachytherapy and needle planning by integer program (NPIP), a computational method for generat- ing needles than the current HDR brachytherapy workflow. Combined with robot assisted brachytherapy

  8. 6-Month Work Plan

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity ofkandz-cm11 Outreach Home RoomPreservationBio-InspiredAtmosphericdevicesPPONeApril351APPLICATION OF kV Spare|LiMessage

  9. Motion Planning Using Dynamic Roadmaps Marcelo Kallmann and Maja Mataric

    E-Print Network [OSTI]

    Kallmann, Marcelo

    Motion Planning Using Dynamic Roadmaps Marcelo Kallmann and Maja Mataric Interaction Lab, Computer, mataric}@usc.edu Abstract - We evaluate the use of dynamic roadmaps for on- line motion planning and nodes of a precomputed roadmap are updated accordingly. We concentrate in this paper on analyzing

  10. Biennial Assessment of the Fifth Power Plan Transmission Issues

    E-Print Network [OSTI]

    unscheduled electricity flows over transmission lines leading to increased risks to electric system-construction alternatives to transmission; · Inability to effectively monitor the wholesale electricity market, identifyBiennial Assessment of the Fifth Power Plan Transmission Issues INTRODUCTION The Fifth Power Plan

  11. Atomic and electronic structures of SrTiO3/GaAs heterointerfaces: An 80-kV atomic-resolution electron energy-loss spectroscopy study

    SciTech Connect (OSTI)

    Qiao, Q.; Klie, Robert F; Ogut, Serdar; Idrobo Tapia, Juan C

    2012-01-01

    We have examined the atomic and electronic structures of epitaxially grown, ultrathin SrTiO{sub 3} (100) films on GaAs (001) using 80-kV aberration-corrected atomic-resolution Z-contrast imaging and electron energy-loss spectroscopy (EELS) to develop a fundamental understanding of the interfacial structure-property relationships. We find that the interface is atomically abrupt and no surface reconstruction of the GaAs (001) surface is observed. Using atomic-column resolved EELS, we examine the oxygen vacancy and Ti concentrations in the SrTiO{sub 3} film and across the heterointerface. We show that Ti diffuses into the first few monolayers of GaAs. Using a combination of EELS and first-principles calculations, we present evidence for the formation of As oxides at the interface depending on the thin-film growth conditions. These findings are used to explain the differences in the transport behavior of the films.

  12. Hanford Site Development Plan

    SciTech Connect (OSTI)

    Rinne, C.A.; Curry, R.H.; Hagan, J.W.; Seiler, S.W.; Sommer, D.J. ); Yancey, E.F. )

    1990-01-01

    The Hanford Site Development Plan (Site Development Plan) is intended to guide the short- and long-range development and use of the Hanford Site. All acquisition, development, and permanent facility use at the Hanford Site will conform to the approved plan. The Site Development Plan also serves as the base document for all subsequent studies that involve use of facilities at the Site. This revision is an update of a previous plan. The executive summary presents the highlights of the five major topics covered in the Site Development Plan: general site information, existing conditions, planning analysis, Master Plan, and Five-Year Plan. 56 refs., 67 figs., 31 tabs.

  13. Wesbrook Place Neighbourhood Plan

    E-Print Network [OSTI]

    .4 The Approach to Plan Making 1.4.1 Planning Objectives that Support the University Vision 1.4.2 Planning Objectives from Guiding Land Use Planning Documents 1.4.3 Planning Objectives from Public Consultation 1.4.5 Interface with Green Academic Lands 2.5 Circulation and Transportation 2.5.1 Transportation Objectives 2

  14. Holes in Spectral Lines

    E-Print Network [OSTI]

    Fontana, Peter R.; Srivastava, Rajendra P.

    1973-06-01

    at E = 0 is 2le I' Ib/(t)I = @~ R~R~~»nh'(IRlyt)e"'" (13)a ylal 0 5 '7 FIG. 3. Probabilities of photon emission as a function of time. The frequency corresponds to the energy differ- ence between the unperturbed degenerate excited states and the ground... states 6 is 0. 5 ey. For V= 0 the emission line is Lorentzian, but for V0 a "hole" appears at the frequency equal to the frequency difference between the excited nondecay- ing state and the ground state. The position of the "hole" is independent...

  15. The Line Verifier GVERIFY1

    E-Print Network [OSTI]

    Griffith, Arnold K.

    1971-01-01

    A line verifier is presented which, given the co-ordinates of the end points of the hypothesized line, returns a (possibly) more accurate version of the end points, together with an estimate of the probability that there ...

  16. 2011 Strategic Plan Computing Services 2011 Strategic Plan 2

    E-Print Network [OSTI]

    Spirtes, Peter

    2011 Strategic Plan #12;Computing Services 2011 Strategic Plan 2 #12;3 Computing Services 2011 Strategic Plan Contents Introduction ................................................................................................................ 7 The 2011 Strategic Plan

  17. DRAFT Fifteenmile Management Plan 5. Fifteenmile Subbasin Management Plan

    E-Print Network [OSTI]

    DRAFT Fifteenmile Management Plan 5. Fifteenmile Subbasin Management Plan DRAFT May 25 2004 Group 5. FIFTEENMILE SUBBASIN MANAGEMENT PLAN Management Plans

  18. Transmission Line Circuit Alexander Glasser

    E-Print Network [OSTI]

    Anlage, Steven

    Chaos in a Transmission Line Circuit Alexander Glasser Marshal Miller With... Prof. Edward Ott Prof times become shorter, circuit connections behave more and more like transmission lines. Theoretical(t) - Transmission Line (Zo, T) #12;5 Cf/Cr 1000 Vf Capacitance Voltage Cf Cr Model for Nonlinear Capacitor

  19. Plan Merging & Plan Reuse As Satis ability

    E-Print Network [OSTI]

    Mali, Amol D.

    Plan Merging & Plan Reuse As Satis#12;ability #3; Amol Dattatraya Mali Dept. of Elect. Engg. & Computer Science, P.O.Box 784 University of Wisconsin, Milwaukee, WI 53201, USA mali@miller.cs.uwm.edu July

  20. Institutional plan. FY 1998--2003

    SciTech Connect (OSTI)

    NONE

    1997-07-01

    This Institutional Plan for Argonne National Laboratory contains central elements of Argonne`s strategic plan. Chapter II of this document discusses the Laboratory`s mission and core competencies. Chapter III presents the Science and Technology Strategic Plan, which summarizes key features of the external environment, presents Argonne`s vision, and describes how the Laboratory`s strategic goals and objectives map onto and support DOE`s four business lines. The balance of the chapter comprises the science and technology area plans, organized by the four DOE business lines. Chapter IV describes the Laboratory`s ten major initiatives, which cover a broad spectrum of science and technology. Our proposal for an Exotic Beam Facility aims at, among other things, increased understanding of the processes of nuclear synthesis during and shortly after the Big Bang. Our Advanced Transportation Technology initiative involves working with US industry to develop cost-effective technologies to improve the fuel efficiency and reduce the emissions of transportation systems. The Laboratory`s plans for the future depend significantly on the success of its major initiatives. Chapter V presents our Operations and Infrastructure Strategic Plan. The main body of the chapter comprises strategic plans for human resources; environmental protection, safety, and health; site and facilities; and information management. The chapter concludes with a discussion of the business and management practices that Argonne is adopting to improve the quality and cost-effectiveness of its operations. The structure and content of this document depart from those of the Institutional Plan in previous years. Emphasis here is on directions for the future; coverage of ongoing activities is less detailed. We hope that this streamlined plan is more direct and accessible.

  1. STRATEGIC PLAN PREAMBLE:...................................................................................... 6

    E-Print Network [OSTI]

    2014­2019 STRATEGIC PLAN #12; 2 CONTENTS PREAMBLE.......................................... 29 THE STRATEGIC PLANNING PROCESS............................................. 30 Topic Committees................................................................ 32 OLD DOMINION UNIVERSITY STRATEGIC PLAN 2014-2019 GOALS, OBJECTIVES AND ACTION ITEMS

  2. FY 91 Annual Research Plan

    SciTech Connect (OSTI)

    Not Available

    1990-12-01

    In line with the Federal Oil Research Program to maximize the economic producibility of the domestic oil resource, the National Institute for Petroleum and Energy Research (NIPER) presents this FY91 Annual Research Plan. NIPER is organized into two research departments -- Energy Production Research (EPR) and Fuels Research (FR). Projects in EPR deal with various aspects of enhanced oil recovery and include reservoir characterization, chemical flooding, gas injection, steam injection, microbial enhanced oil recovery, and the environmental concerns related to these processes. Projects in FR consider the impact of heavy oil and alternative fuels on the processing and end-use of fuels. Projects are briefly described.

  3. 2.3-MW Medium-Voltage, Three-Level Wind Energy Inverter Applying a Unique Bus Structure and 4.5-kV Si/SiC Hybrid Isolated Power Modules: Preprint

    SciTech Connect (OSTI)

    Erdman, W.; Keller, J.; Grider, D.; VanBrunt, E.

    2014-11-01

    A high-efficiency, 2.3-MW, medium-voltage, three-level inverter utilizing 4.5-kV Si/SiC (silicon carbide) hybrid modules for wind energy applications is discussed. The inverter addresses recent trends in siting the inverter within the base of multimegawatt turbine towers. A simplified split, three-layer laminated bus structure that maintains low parasitic inductances is introduced along with a low-voltage, high-current test method for determining these inductances. Feed-thru bushings, edge fill methods, and other design features of the laminated bus structure provide voltage isolation that is consistent with the 10.4-kV module isolation levels. Inverter efficiency improvement is a result of the (essential) elimination of the reverse recovery charge present in 4.5-kV Si PIN diodes, which can produce a significant reduction in diode turn-off losses as well as insulated-gate bipolar transistor (IGBT) turn-on losses. The hybrid modules are supplied in industry-standard 140 mm x 130 mm and 190 mm x 130 mm packages to demonstrate direct module substitution into existing inverter designs. A focus on laminated bus/capacitor-bank/module subassembly level switching performance is presented.

  4. Improvement in the statistical operation of a Blumlein pulse forming line in bipolar pulse mode

    SciTech Connect (OSTI)

    Pushkarev, A. I., E-mail: aipush@mail.ru; Isakova, Y. I.; Khaylov, I. P. [Laboratory of Beam and Plasma Technologies, Tomsk Polytechnic University, 2a Lenin Ave., Tomsk 634028 (Russian Federation)

    2014-07-15

    The paper presents the results of studies on shot-to-shot performance of a water Blumlein pulse forming line of 1–1.2 kJ of stored energy. The experiments were carried using the TEMP-4M pulsed ion beam accelerator during its operation in both unipolar pulse mode (150 ns, 250–300 kV) and bipolar-pulse mode with the first negative (300–600 ns, 100–150 kV) followed by a second positive (120 ns, 250–300 kV) pulse. The analysis was carried out for two cases when the Blumlein was terminated with a resistive load and with a self-magnetically insulated ion diode. It was found that in bipolar pulse mode the shot-to-shot variation in breakdown voltage of a preliminary spark gap is small, the standard deviation (1?) does not exceed 2%. At the same time, the shot-to-shot variation in the breakdown voltage of the main spark gap in both bipolar-pulse and unipolar pulse mode is 3–4 times higher than that for the preliminary spark gap. To improve the statistical performance of the main spark gap we changed the regime of its operation from a self-triggered mode to an externally triggered mode. In the new arrangement the first voltage pulse at the output of Blumlein was used to trigger the main spark gap. The new trigatron-type regime of the main spark gap operation showed a good stability of breakdown voltage and thus allowed to stabilize the duration of the first pulse. The standard deviation of the breakdown voltage and duration of the first pulse did not exceed 2% for a set of 50 pulses. The externally triggered mode of the main gap operation also allowed for a decrease in the charging voltage of the Blumlein to a 0.9–0.95 of self-breakdown voltage of the main spark gap while the energy stored in Marx generator was decreased from 4 kJ to 2.5 kJ. At the same time the energy stored in Blumlein remained the same.

  5. ACQUISITION PLANNING | Department of Energy

    Energy Savers [EERE]

    ACQUISITION PLANNING ACQUISITION PLANNING ACQUISITION PLANNING More Documents & Publications ACQUISITION PLANNING Attachment FY2011-13 Attachment FY2011-40(3)...

  6. Malcolm, N. and Aggarwal, R.k. (2014) An Analysis of Reducing Back Flashover Faults with Surge Arresters on 69/138 kV Double

    E-Print Network [OSTI]

    McCusker, Guy

    2014-01-01

    Malcolm, N. and Aggarwal, R.k. (2014) An Analysis of Reducing Back Flashover Faults with Surge-EMTP, Back flashover faults, Lightning strokes, Surge arrester, Transmission lines. Abstract Back flashover-EMTP) simulations was performed on a section of the affected lines to identify the main factors causing back

  7. Report: Strategic Planning Impacts

    Office of Environmental Management (EM)

    Strategic Planning Impacts September 30, 2009 Submitted by the EMAB ARRA Implementation and Oversight Subcommittee Background: EM plans to use the influx of stimulus funding from...

  8. Digital Data Management Plans

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Digital Data Management Plans Digital Data Management Plans Investigating the field of high energy physics through experiments that strengthen our fundamental understanding of...

  9. LDRD Program Plan master

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    LDRD plan and supporting documents: our LDRD Proposal Guidance, Proposal Template, and Budget Template. The final plan will be subject to DOE site office for concurrence. LDRD...

  10. Plans, Updates, Regulatory Documents

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Permit for Storm Water Documents Individual Permit NPDES No. NM0030759 (pdf) Storm Water Plans Site Discharge Pollution Prevention Plan (SDPPP) Volume 1 - Los AlamosPueblo...

  11. A long-pulse repetitive operation magnetically insulated transmission line oscillator

    SciTech Connect (OSTI)

    Fan, Yu-Wei; Zhong, Hui-Huang; Zhang, Jian-De; Shu, Ting; Liu, Jin Liang [College of Optoelectric Science and Engineering, National University of Defense Technology, Changsha 410073 (China)

    2014-05-15

    The improved magnetically insulated transmission line oscillator (MILO) is a gigawatt-class L-band high power microwave tube. It has allowed us to generate 3.1 GW pulse of 40 ns duration in the single-pulse operation and 500 MW pulse of 25 ns duration in the repetition rate operation. However, because of the severe impedance mismatch, the power conversion efficiency is only about 4% in the repetition rate operation. In order to eliminate the impedance mismatch and obtain repetitive long-pulse high-power microwave (HPM), a series of experiments are carried out and the recent progress is presented in this paper. In the single-pulse operation, when the diode voltage is 466 kV and current is 41.6 kA, the radiated microwave power is above 2.2 GW, the pulse duration is above 102 ns, the microwave frequency is about 1.74 GHz, and the power conversion efficiency is about 11.5%. In the repetition rate operation, under the condition of the diode voltage about 400 kV, beam current about 38 kA, the radiated microwave power is about 1.0 GW, the pulse duration is about 85 ns. Moreover, the radiated microwave power and the pulse duration decline little by little when the shot numbers increase gradually. The experimental results show that the impedance matching is a vital factor for HPM systems and one of the major technical challenges is to improve the cathode for the repetition rate operation MILO.

  12. Strategic Plan Core strategies

    E-Print Network [OSTI]

    Oxford, University of

    Strategic Plan 2013­18 Vision Priorities Core strategies Enabling strategies #12;Strategic Plan on the Strategic Plan, ensuring that it continues to meet academic needs, enables us to respond to the external the framework for making the Strategic Plan operational at divisional and service level. ©UniversityofOxford #12

  13. Business Services Strategic Plan

    E-Print Network [OSTI]

    Pittendrigh, Barry

    Business Services Strategic Plan 2008-2014 New Synergies: Launching Tomorrow's Leaders Discovery implementation of the University Strategic Plan Analyze, plan, and manage University finances, processes, and contracts in global and strategic partnerships Review existing capital financing plans and the process

  14. Strategic Plan November 2011

    E-Print Network [OSTI]

    Johnson Jr.,, Ray

    Strategic Plan 2012­2016 #12;November 2011 Dear Friends, I am pleased to present the Graduate Center Strategic Plan for 2012­2016. This plan is the result of a broadly consultative process that began in Spring 2010 when I convened the Strategic Planning Council, which included faculty, students, staff

  15. 6 Management Plan Introduction

    E-Print Network [OSTI]

    147 6 Management Plan Introduction The management plan integrates the vision for the White Salmon for restoration of fish and wildlife habitat and populations which form the bulk of the management plan is derived from that input. The scope of the management plan is somewhat narrower than the scope of the assessment

  16. Climate change action plan

    E-Print Network [OSTI]

    Delivery Climate change action plan 2009-2011 #12;2 | Climate change action plan ©istockphoto.com #12;Climate Change Action Plan Climate change action plan | 3 Contents Overview 4 Preface and Introduction 5 Climate change predictions for Scotland 6 The role of forestry 7 Protecting and managing

  17. Proposal of a gigawatt-class L/Ku dual-band magnetically insulated transmission line oscillator

    SciTech Connect (OSTI)

    Ju, J.-C. Fan, Y.-W.; Shu, T.; Zhong, H.-H.

    2014-10-15

    We present a gigawatt (GW)-class magnetically insulated transmission line oscillator (MILO) which is capable of generating dual-band high power microwaves (HPMs). The proposed device, deriving from previously studied complex MILO and dual-frequency MILO, is designed to produce two HPMs in L-band and Ku-band, respectively. It is found in particle-in-cell (PIC) simulation that when the diode voltage is 610?kV, HPMs with frequencies of 1.72 GHz and 14.6?GHz can be achieved with powers of 3.3?GW and 2.4?GW, respectively. The corresponding total power conversion efficiency is approximately 12.8%. Power difference of the two generated HPMs is approximately 1.4?dB, and frequency difference of them reaches a level as high as ?10?dB.

  18. EIS-0116-S1: Final Supplemental Environmental Impact Statement for the Blue River-Gore Pass Portion of the Hayden-Blue River Transmission Line Project, Grand and Summit Counties, Colorado

    Broader source: Energy.gov [DOE]

    This supplemental environmental impact statement by the Western Area Power Administration assesses the environmental effects of constructing, operating, and maintaining about 30 miles of 230/345-kV transmission line between the existing Gore Pass Substation northwest of Kremmling, Colorado, and a proposed new substation (not part of this action) near the Ute Pass Road. Alternatives assessed included routing and design alternatives plus the alternatives addressed in the Hayden-Blue River Final EIS, issued by the Rural Electrification Administration in July 1982 and adopted by DOE in June 1985 (see DOE/EIS-0116).

  19. Bipolar pulse forming line

    DOE Patents [OSTI]

    Rhodes, Mark A. (Pleasanton, CA)

    2008-10-21

    A bipolar pulse forming transmission line module for linear induction accelerators having first, second, third, fourth, and fifth planar conductors which form an interleaved stack with dielectric layers between the conductors. Each conductor has a first end, and a second end adjacent an acceleration axis. The first and second planar conductors are connected to each other at the second ends, the fourth and fifth planar conductors are connected to each other at the second ends, and the first and fifth planar conductors are connected to each other at the first ends via a shorting plate adjacent the first ends. The third planar conductor is electrically connectable to a high voltage source, and an internal switch functions to short a high voltage from the first end of the third planar conductor to the first end of the fourth planar conductor to produce a bipolar pulse at the acceleration axis with a zero net time integral. Improved access to the switch is enabled by an aperture through the shorting plate and the proximity of the aperture to the switch.

  20. EC Transmission Line Materials

    SciTech Connect (OSTI)

    Bigelow, Tim S

    2012-05-01

    The purpose of this document is to identify materials acceptable for use in the US ITER Project Office (USIPO)-supplied components for the ITER Electron cyclotron Heating and Current Drive (ECH&CD) transmission lines (TL), PBS-52. The source of material property information for design analysis shall be either the applicable structural code or the ITER Material Properties Handbook. In the case of conflict, the ITER Material Properties Handbook shall take precedence. Materials selection, and use, shall follow the guidelines established in the Materials Assessment Report (MAR). Materials exposed to vacuum shall conform to the ITER Vacuum Handbook. [Ref. 2] Commercial materials shall conform to the applicable standard (e.g., ASTM, JIS, DIN) for the definition of their grade, physical, chemical and electrical properties and related testing. All materials for which a suitable certification from the supplier is not available shall be tested to determine the relevant properties, as part of the procurement. A complete traceability of all the materials including welding materials shall be provided. Halogenated materials (example: insulating materials) shall be forbidden in areas served by the detritiation systems. Exceptions must be approved by the Tritium System and Safety Section Responsible Officers.

  1. Emergency pipe line repair connects subsea pipe lines

    SciTech Connect (OSTI)

    Lerique, M.P.; Thiberge, P. ); Wright, N. )

    1990-11-01

    Emergency repair of any subsea line pipe must form a high-integrity, metal-to-metal seal. This paper presents a remote, diverless repair system that utilizes master flanges, a connector and a spool piece to repair line pipe in deep offshore waters.

  2. Qualitative vs. Quantitative Plan Diversity in Case-Based Planning

    E-Print Network [OSTI]

    Muñoz-Avila, Héctor

    Qualitative vs. Quantitative Plan Diversity in Case-Based Planning Alexandra Coman, Héctor Muñoz 18015 {alc308, hem4}@lehigh.edu Abstract. Plan diversity has practical value in multiple planning domains, including travel planning, military planning and game planning. Existing methods for obtaining

  3. Argonne National Laboratory institutional plan FY 2001--FY 2006.

    SciTech Connect (OSTI)

    Beggs, S.D.

    2000-12-07

    This Institutional Plan describes what Argonne management regards as the optimal future development of Laboratory activities. The document outlines the development of both research programs and support operations in the context of the nation's R and D priorities, the missions of the Department of Energy (DOE) and Argonne, and expected resource constraints. The Draft Institutional Plan is the product of many discussions between DOE and Argonne program managers, and it also reflects programmatic priorities developed during Argonne's summer strategic planning process. That process serves additionally to identify new areas of strategic value to DOE and Argonne, to which Laboratory Directed Research and Development funds may be applied. The Draft Plan is provided to the Department before Argonne's On-Site Review. Issuance of the final Institutional Plan in the fall, after further comment and discussion, marks the culmination of the Laboratory's annual planning cycle. Chapter II of this Institutional Plan describes Argonne's missions and roles within the DOE laboratory system, its underlying core competencies in science and technology, and six broad planning objectives whose achievement is considered critical to the future of the Laboratory. Chapter III presents the Laboratory's ''Science and Technology Strategic Plan,'' which summarizes key features of the external environment, presents Argonne's vision, and describes how Argonne's strategic goals and objectives support DOE's four business lines. The balance of Chapter III comprises strategic plans for 23 areas of science and technology at Argonne, grouped according to the four DOE business lines. The Laboratory's 14 major initiatives, presented in Chapter IV, propose important advances in key areas of fundamental science and technology development. The ''Operations and Infrastructure Strategic Plan'' in Chapter V includes strategic plans for human resources; environmental protection, safety, and health; site and facilities; security, export control, and counterintelligence; information management; communications, outreach, and community affairs; performance-based management; and productivity improvement and overhead cost reduction. Finally, Chapter VI provides resource projections that are a reasonable baseline for planning the Laboratory's future.

  4. Solving radiative transfer with line overlaps using Gauss Seidel algorithms

    E-Print Network [OSTI]

    F. Daniel; J. Cernicharo

    2008-07-11

    The improvement in observational facilities requires refining the modelling of the geometrical structures of astrophysical objects. Nevertheless, for complex problems such as line overlap in molecules showing hyperfine structure, a detailed analysis still requires a large amount of computing time and thus, misinterpretation cannot be dismissed due to an undersampling of the whole space of parameters. We extend the discussion of the implementation of the Gauss--Seidel algorithm in spherical geometry and include the case of hyperfine line overlap. We first review the basics of the short characteristics method that is used to solve the radiative transfer equations. Details are given on the determination of the Lambda operator in spherical geometry. The Gauss--Seidel algorithm is then described and, by analogy to the plan--parallel case, we see how to introduce it in spherical geometry. Doing so requires some approximations in order to keep the algorithm competitive. Finally, line overlap effects are included. The convergence speed of the algorithm is compared to the usual Jacobi iterative schemes. The gain in the number of iterations is typically factors of 2 and 4 for the two implementations made of the Gauss--Seidel algorithm. This is obtained despite the introduction of approximations in the algorithm. A comparison of results obtained with and without line overlaps for N2H+, HCN, and HNC shows that the J=3-2 line intensities are significantly underestimated in models where line overlap is neglected.

  5. 65 Contingency Planning Issues CONTINGENCY PLANNING ISSUES

    E-Print Network [OSTI]

    Energy Shortage Contingency Plan is activated in the event of a shortage of electrical energy or fuel.). For planning purposes, the Energy Commission considers a shortage to mean an actual or potential loss of supply which significantly impacts the state's energy systems and economy. In a natural disaster

  6. EMERGENCY OPERATIONS PLAN //Original Base Plan//

    E-Print Network [OSTI]

    Frantz, Kyle J.

    EMERGENCY OPERATIONS PLAN //Original Base Plan// Draft Date: March 24, 2008 Review By: Emergency: Emergency Management Policy (original dated 02/06/08) Responsible Officer for Implementation: Director of Emergency Management Any person who requires assistance in understanding any aspect of this document should

  7. Product Lines for Service Oriented Applications - PL for SOA

    E-Print Network [OSTI]

    ter Beek, Maurice H; Njima, Mercy N; 10.4204/EPTCS.61.3

    2011-01-01

    PL for SOA proposes, formally, a software engineering methodology, development techniques and support tools for the provision of service product lines. We propose rigorous modeling techniques for the specification and verification of formal notations and languages for service computing with inclinations of variability. Through these cutting-edge technologies, increased levels of flexibility and adaptivity can be achieved. This will involve developing semantics of variability over behavioural models of services. Such tools will assist organizations to plan, optimize and control the quality of software service provision, both at design and at run time by making it possible to develop flexible and cost-effective software systems that support high levels of reuse. We tackle this challenge from two levels. We use feature modeling from product line engineering and, from a services point of view, the orchestration language Orc. We introduce the Smart Grid as the service product line to apply the techniques to.

  8. Electric and magnetic field reduction by alternative transmission line options

    SciTech Connect (OSTI)

    Stewart, J.R. (Power Technologies, Inc., Schenectady, NY (United States)); Dale, S.J. (Oak Ridge National Lab., TN (United States)); Klein, K.W. (Energetics, Inc., Columbia, MD (United States))

    1991-01-01

    Ground level electric, and more recently magnetic, fields from overhead power transmission lines are increasingly important considerations in right of way specification, with states setting or planning to set edge of right of way limits. Research has been conducted in high phase order power transmission wherein six of twelve phases are used to transmit power in less physical space and with reduced electrical environmental effects than conventional designs. The first magnetic field testing, as reported in this paper, has verified predictive methods for determination of magnetic fields from high phase order lines. Based on these analytical methods, field profiles have been determined for lines of different phase order of comparable power capacity. Potential advantages of high phase order as a means of field mitigation are discussed. 10 refs., 12 figs., 3 tabs.

  9. Sample Project Execution Plan

    Broader source: Energy.gov [DOE]

    The project execution plan (PEP) is the governing document that establishes the means to execute, monitor, and control projects.  The plan serves as the main communication vehicle to ensure that...

  10. Dynamic Latent Plan Models

    E-Print Network [OSTI]

    Choudhury, Charisma F.

    Planning is an integral part of many behavioural aspects related to transportation: residential relocation, activity and travel scheduling, route choice, etc. People make plans and then select actions to execute those ...

  11. Sustainabiliity Sustainability Plan

    E-Print Network [OSTI]

    Heller, Barbara

    Sustainabiliity IIT Campus Sustainability Plan 2010­2020 Published Fall Semester 2010 www.iit.edu/campus_sustainability #12;IIT Campus Sustainability Plan 2010-2020 Fall Semester 2010 1 Section I: Background Sustainability ...................................................................................................................................................................8 IIT Academic Entities on Sustainability

  12. Planning the Project Meeting 

    E-Print Network [OSTI]

    Howard, Jeff W.

    2005-05-10

    Project group meetings must be planned well in advance. Members should be involved in completing some type of work before the next meeting. This helps the leader plan the next project meeting and makes efficient use of time.

  13. Climate Change Adaptation Planning

    Office of Energy Efficiency and Renewable Energy (EERE)

    This course provides an introduction to planning for climate change impacts, with examples of tribes that have been going through the adaptation planning process. The course is intended for tribal...

  14. Environmental Management System Plan

    E-Print Network [OSTI]

    Fox, Robert

    2009-01-01

    and locations chemicals are used as well as information about emergency plans and procedures. The current Hazardous

  15. Business Planning Resources

    Broader source: Energy.gov [DOE]

    Business Planning Resources, a presentation of the U.S. Department of Energy's Better Buildings Neighborhood Program.

  16. Pulse shaping with transmission lines

    DOE Patents [OSTI]

    Wilcox, Russell B. (Oakland, CA)

    1987-01-01

    A method and apparatus for forming shaped voltage pulses uses passive reflection from a transmission line with nonuniform impedance. The impedance of the reflecting line varies with length in accordance with the desired pulse shape. A high voltage input pulse is transmitted to the reflecting line. A reflected pulse is produced having the desired shape and is transmitted by pulse removal means to a load. Light activated photoconductive switches made of silicon can be utilized. The pulse shaper can be used to drive a Pockels cell to produce shaped optical pulses.

  17. Electrical transmission line diametrical retainer

    DOE Patents [OSTI]

    Hall, David R. (Provo, UT); Hall, Jr., H. Tracy (Provo, UT); Pixton, David (Lehi, UT); Dahlgren, Scott (Provo, UT); Sneddon, Cameron (Provo, UT); Briscoe, Michael (Lehi, UT); Fox, Joe (Spanish Fork, UT)

    2004-12-14

    The invention is a mechanism for retaining an electrical transmission line. In one embodiment of the invention it is a system for retaining an electrical transmission line within down hole components. In accordance with one aspect of the invention, the system includes a plurality of downhole components, such as sections of pipe in a drill string. The system also includes a coaxial cable running between the first and second end of a drill pipe, the coaxial cable having a conductive tube and a conductive core within it. The invention allows the electrical transmission line to with stand the tension and compression of drill pipe during routine drilling cycles.

  18. Windward Community College Strategic Plan

    E-Print Network [OSTI]

    i Windward Community College Strategic Plan Action Outcomes November 2008 #12;ii ©2008 Windward. The Strategic Planning Committee...............................................................................3 B. The Strategic Plan

  19. INTERIOR WETLANDS PROGRAM STRATEGIC PLAN

    E-Print Network [OSTI]

    #12;INTERIOR WETLANDS PROGRAM STRATEGIC PLAN 1993 -1997 July 1993 FRASER RIVER ACTION PLAN CANADA'S GREEN PLAN ENVIRONMENT CANADA DUCKS UNLIMITED CANADA GOVERNMENT OF BRITISH COLUMBIA #12;Table

  20. Essays in Collaborative Wildfire Planning

    E-Print Network [OSTI]

    Smith, Rachel Carolyn

    2011-01-01

    Planners 44, 274-285. American Planning Association. (2002).Chicago, IL: American Planning Association. Babbie, E. (Journal of the American Planning Association 63, 329-344.

  1. Waste Management Quality Assurance Plan

    E-Print Network [OSTI]

    Waste Management Group

    2006-01-01

    LBNL/PUB-5352, Revision 6 Waste Management QualityAssurance Plan Waste Management Group Environment, HealthRev. 6 WM QA Plan Waste Management Quality Assurance Plan

  2. Library Services Strategic Plan

    E-Print Network [OSTI]

    Applebaum, David

    1 Library Services Strategic Plan 2013 - 2016 Contents 1. Overview 2. Mission Statements 3. Vision provided by Library Services will be integral to the College's success; therefore this strategic plan defines a vision of how the service will contribute to the achievement of the King's strategic plan over

  3. Strategic Plan December 2013

    E-Print Network [OSTI]

    Hill, Jeffrey E.

    Strategic Plan December 2013 Prepared by: Bud Crouch Principal Consultant budcrouch · www.tecker.com Page | 2 Overview On October 21, 2013, a strategic planning group consisting strategic direction. Likewise, on December 10, 2013, a strategic planning group consisting of faculty

  4. STRATEGIC PLAN FOR RESEARCH

    E-Print Network [OSTI]

    Meunier, Michel

    STRATEGIC PLAN FOR RESEARCH AND INNOVATION Committed to Progress / 2011-2016 #12;#12;Contributions . . . . . . . . . . . . . . . . . . . . . . . . . 13 INDEx #12;MEMbERS OF THE STRATEGIC PLANNING TASk FORCE CONTRIbuTIONS Carl-Éric Aubin / Professor engineering Jean-Yves trépanier / Professor, department of mechanical engineering 4 strategic Plan

  5. Cummings 2015 Strategic Plan

    E-Print Network [OSTI]

    Dennett, Daniel

    Cummings 2015 Strategic Plan Cummings School of Veterinary Medicine at Tufts University January 2, 2012 #12;1 Table of Contents I. Executive Summary 2 II. Introduction 3 III. Strategic Planning Process University developed the Cummings 2015: Strategic Plan to identify areas of focus, goals, and strategic

  6. 2010 -2013 Strategic Plan

    E-Print Network [OSTI]

    Sin, Peter

    2010 - 2013 Strategic Plan College of Liberal Arts and Sciences DISCOVER. TEACH. ENGAGE. #12;The strategy for these new and challenging times, I initiated a year-long strategic planning process. Paul D'Anieri, Dean Introduction College of Liberal Arts and Sciences Strategic Plan1 #12;College

  7. SFU SUSTAINABILITY STRATEGIC PLAN

    E-Print Network [OSTI]

    Kavanagh, Karen L.

    SFU SUSTAINABILITY STRATEGIC PLAN #12;GOAL 1 ENGAGING STUDENTS 1 Outcome 1 Outcome 2 4 Outcome 1 the SUSTAINABILITY STRATEGIC PLANINTRODUCTION SFU SUSTAINABILITY PLAN -- REVISED JULY 2, 2013i #12;carrying capacity Plan marks a major milestone in SFU's commitment to advance the wide array of goals, outcomes

  8. Forest Research Coporate Plan

    E-Print Network [OSTI]

    Forest Research Coporate Plan 2006­2009 The research agency of the Forestry Commission #12;Forest Research Corporate Plan 2006­2009 1Corporate Plan 2006­2009 #12;Chief Executive Professor Jim Lynch Forest Research Alice Holt Lodge Farnham Surrey GU10 4LH Tel: 01420 22255 E-mail: research

  9. Proof Planning Coinduction 

    E-Print Network [OSTI]

    Dennis, Louise

    . This automation is based on the ideas of proof planning [Bundy 88]. Proof planning as the name suggests, plans the higher level steps in a proof without performing the formal checking which is also required for a verification. The automation has focused on the use...

  10. 8 Management Plan Introduction

    E-Print Network [OSTI]

    312 8 Management Plan Introduction The management plan integrates the vision for the Lower Mid and populations which form the bulk of the management plan is derived from that input. The scope of the management and inventory are designed and may be used to guide restoration and management actions by many parties under

  11. WECC Variable Generation Planning Reference Book: Appendices

    SciTech Connect (OSTI)

    Makarov, Yuri V.; Du, Pengwei; Etingov, Pavel V.; Ma, Jian; Vyakaranam, Bharat

    2013-05-13

    The document titled “WECC Variable Generation Planning Reference Book”. This book is divided into two volumes; one is the main document (volume 1)and the other is appendices (volume 2). The main document is a collection of the best practices and the information regarding the application and impact of variables generation on power system planning. This volume (appendices) has additional information on the following topics: Probabilistic load flow problems. 2. Additional useful indices. 3. high-impact low-frequency (HILF) events. 4. Examples of wide-area nomograms. 5. Transmission line ratings, types of dynamic rating methods. 6. Relative costs per MW-km of different electric power transmission technologies. 7. Ultra-high voltage (UHV) transmission. 8.High voltage direct current (VSC-HVDC). 9. HVDC. 10. Rewiring of existing transmission lines. 11. High-temperature low sag (HTLS) conductors. 12. The direct method and energy functions for transient stability analysis in power systems. 13.Blackouts caused by voltage instability. 14. Algorithm for parameter continuation predictor-corrector methods. 15. Approximation techniques available for security regions. 16. Impacts of wind power on power system small signals stability. 17. FIDVR. 18. FACTS. 19. European planning standard and practices. 20. International experience in wind and solar energy sources. 21. Western Renewable Energy Zones (WREZ). 22. various energy storage technologies. 23. demand response. 24. BA consolidation and cooperation options. 25. generator power management requirements and 26. European planning guidelines.

  12. EIS-0339: Presidential Permit Application, GenPower 500 kV Submarine Electric Transmission Cable from Nova Scotia to New York

    Broader source: Energy.gov [DOE]

    The Department of Energy (DOE) announced its intent to prepare an Environmental Impact Statement (EIS) in accordance with the National Environmental Policy Act of 1969 (NEPA) for GenPower New York, L.L.C.’s (GenPower) request for a Presidential permit for a proposed international electric transmission line.

  13. Design and Construction of a150kV/300A/1s Blumlein Pulser J.O. ROSSI, M. UEDA and J.J. BARROSO

    E-Print Network [OSTI]

    suited devices for high voltage pulse generation in the range of nanoseconds or microseconds carried out in our laboratory, including a PSPICE simulation of the output pulse voltage of the generator. Key-words: - Blumlein, pulse generator, transmission line, high voltage, coaxial cable, switch tube 1

  14. University Planning Framework Prepared By: University Planning Committee

    E-Print Network [OSTI]

    Kavanagh, Karen L.

    University Planning Framework Prepared By: University Planning Committee Date Prepared: July 2014 Contact: Scott Penney, Director, Planning & Analysis scott_penney@sfu.ca | 778-782-7513 #12;University Planning Framework Page 1 Contents Contents

  15. Plans are nothing ... Planning is everything | Jefferson Lab

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Plans are nothing ... Planning is everything May 12, 2009 It was Dwight D. Eisenhower who said, "Plans are nothing; planning is everything." I believe that the way he meant it to...

  16. User Experiment Time-Line

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    User Experiment Time-Line Event Target Call for proposal 2 months before proposals are due PAC Proposals Due 7 weeks before PAC meeting TAC Report for PAC Proposals (includes...

  17. The beauty of laser lines

    E-Print Network [OSTI]

    Kim, Sue-Mie

    1993-01-01

    A line, the simplest way to express an artist's feelings or interpretation of an object, has its own emotions that an artist can employ for her purpose. Laser light, the most self-concentrated, self-sustained and directed, ...

  18. Fin-line horn antenna

    DOE Patents [OSTI]

    Reindel, John (San Diego, CA)

    1990-01-01

    A fin line circuit card containing a fin line slot feeds a dipole antenna ich extends a quarterwave outside the waveguide and provides an energy beam focal point at or near the open end of the waveguide. The dipole antenna thus maintains a wide and nearly constant beamwidth, low VSWR and a circular symmetric radiation pattern for use in electronic warfare direction finding and surveillance applications.

  19. The Silver Lining of Downsizing

    E-Print Network [OSTI]

    Reeve, Allison C.; McCray Pearson, Joyce A.

    2014-01-01

    ? EFFICIENCIES IN PROCESSES ? REDUCES REDUNDANCY ? Drafting the plan ?What we envisioned ? Editing ? Stakeholders ? Implementation ? New organization chart ?What did not change ? Its all OK ? Repurposing space for efficient workflow ? Project/task oriented...! ?Working outside your comfort zone ?The art of anticipating change ?5-year plan ?E-books ?Implementing new staff ?Idyllic organization chart ?Acknowledging the positive ?Keeping calm ?Not getting stuck ?Anticipating future change Simon Canick, Library...

  20. Extending the Classical AI Planning Paradigm to Robotic Assembly Planning

    E-Print Network [OSTI]

    Hutchinson, Seth

    Extending the Classical AI Planning Paradigm to Robotic Assembly Planning * S . A. Hutchinson and A is capable of formulating manipulation plans to meet specified assembly goals; these mani- pulation plans that extends classical AI plan- ning methods to create plans for automated assembly tasks to be executed

  1. From Planning to Searching for the Shortest Plan

    E-Print Network [OSTI]

    Kreinovich, Vladik

    From Planning to Searching for the Shortest Plan: An Optimal Transition R. Trejo, J. Galloway C frtrejo,vladikg@cs.utep.edu Abstract If we want to find the shortest plan, then usually, we try plans of length 1, 2, . . . , until we find the first length for which such a plan exists. When the planning

  2. A Temporal Planning System for Time-Optimal Planning

    E-Print Network [OSTI]

    Garrido, Antonio

    the utility of our system for dealing with temporal planning problems. Key words: planning, temporal planningA Temporal Planning System for Time-Optimal Planning Antonio Garrido, Eva Onaindía and Federico with temporality on actions presents an important challenge to AI planning. Unlike Graphplan-based planners which

  3. Operating plan FY 1998

    SciTech Connect (OSTI)

    NONE

    1997-10-01

    This document is the first edition of Argonne`s new Operating Plan. The Operating Plan complements the strategic planning in the Laboratory`s Institutional Plan by focusing on activities that are being pursued in the immediate fiscal year, FY 1998. It reflects planning that has been done to date, and it will serve in the future as a resource and a benchmark for understanding the Laboratory`s performance. The heart of the Institutional Plan is the set of major research initiatives that the Laboratory is proposing to implement in future years. In contrast, this Operating Plan focuses on Argonne`s ongoing R&D programs, along with cost-saving measures and other improvements being implemented in Laboratory support operations.

  4. Marketing Plan for Transmission Planning Services

    E-Print Network [OSTI]

    Tu, Linh

    2006-12-15

    in the non-consulting side of the firm, the following are services provided on the consulting side, still known as Consultation Company: ? Cogeneration services ? Energy facilities planning ? Energy supply management ? Transmission ? Utility formation... Consultation Company?s competitive advantage in the electrical industry is their experience and expertise in the energy market. The company has been working with companies and individuals to help plan, develop and build power plants for over twenty years...

  5. Improving sales and operations planning in an engineer-to-order environment

    E-Print Network [OSTI]

    Christogiannis, Andreas

    2014-01-01

    A pragmatic approach is taken at analyzing and improving Sales and Operations Planning in a project based, engineer-to-order product line. Variability of product and components configurations and long lead times of the ...

  6. Recent Developments in the Regulation of Electric Utility Resource Planning in Texas 

    E-Print Network [OSTI]

    Totten, J.; Adib, P.; Matlock, R.; Treadway, N.

    1993-01-01

    The Texas Legislature has charged the Public Utility Commission of Texas with the responsibility to license utility power plants and transmission lines, and develop a statewide electrical energy plan. Related duties include the encouragement...

  7. Development of Improved Traveler Survey Methods for High-Speed Intercity Passenger Rail Planning 

    E-Print Network [OSTI]

    Sperry, Benjamin

    2012-07-16

    in this dissertation, ridership estimates for new high-speed intercity passenger rail lines that are planned to serve intermediate communities should not assume that residents of these communities have similar characteristics and values. The d-efficient stated...

  8. Multiple gamma lines from semi-annihilation

    E-Print Network [OSTI]

    D'Eramo, Francesco

    Hints in the Fermi data for a 130 GeV gamma line from the galactic center have ignited interest in potential gamma line signatures of dark matter. Explanations of this line based on dark matter annihilation face a parametric ...

  9. The Pulse Line Ion Accelerator Concept

    E-Print Network [OSTI]

    Briggs, Richard J.

    2006-01-01

    field model of the pulse- line accelerator; relationship to3, 2006 LBNL-59492 The pulse line ion accelerator conceptCalifornia, 94507 The Pulse Line Ion Accelerator concept was

  10. The COMPTEL instrumental line background

    E-Print Network [OSTI]

    G. Weidenspointner; M. Varendorff; U. Oberlack; D. Morris; S. Plueschke; R. Diehl; S. C. Kappadath; M. McConnell; J. Ryan; V. Schoenfelder; H. Steinle

    2000-12-14

    The instrumental line background of the Compton telescope COMPTEL onboard the Compton Gamma-Ray Observatory is due to the activation and/or decay of many isotopes. The major components of this background can be attributed to eight individual isotopes, namely 2D, 22Na, 24Na, 28Al, 40K, 52Mn, 57Ni, and 208Tl. The identification of instrumental lines with specific isotopes is based on the line energies as well as on the variation of the event rate with time, cosmic-ray intensity, and deposited radiation dose during passages through the South-Atlantic Anomaly. The characteristic variation of the event rate due to a specific isotope depends on its life-time, orbital parameters such as the altitude of the satellite above Earth, and the solar cycle. A detailed understanding of the background contributions from instrumental lines is crucial at MeV energies for measuring the cosmic diffuse gamma-ray background and for observing gamma-ray line emission in the interstellar medium or from supernovae and their remnants. Procedures to determine the event rate from each background isotope are described, and their average activity in spacecraft materials over the first seven years of the mission is estimated.

  11. Grand Coulee Transmission Line Replacement Project

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    & Reliability Projects Expand Projects Skip navigation links Line Projects Big Eddy-Knight Central Ferry Lower Monumental Grand Coulee Transmission Line Replacement...

  12. Transmission Line MTF: Magnetized Target Fusion

    E-Print Network [OSTI]

    Transmission Line MTF: Magnetized Target Fusion Initial target: preheated & magnetized Subsequent for the FRC. Abstract Block Diagram theta coil transmission line Bias cap. bank maincapacitor inductor PI cap

  13. What can emission lines tell us?

    E-Print Network [OSTI]

    G. Stasinska

    2007-04-03

    1 Generalities 2 Empirical diagnostics based on emission lines 3 Photoionization modelling 4 Pending questions 5 Appendix: Lists of useful lines and how to deal with them

  14. Strengthening Line Management Oversight and Federal Monitoring...

    Office of Environmental Management (EM)

    and Decommissioning EG Evaluation Guideline EPHA Emergency Planning Hazards Assessment EPP Emergency Preparedness Plan FHA Fire Hazard Analysis HA Hazard Analysis ICRP...

  15. Draft Closure Plan

    Office of Environmental Management (EM)

    analyzed to determine if residual hazardous constituents remain in the drain lines or sumps at the permitted unit. Liquid samples will be collected using glass or plastic tubes,...

  16. IDC Integrated Master Plan.

    SciTech Connect (OSTI)

    Clifford, David J.; Harris, James M.

    2014-12-01

    This is the IDC Re-Engineering Phase 2 project Integrated Master Plan (IMP). The IMP presents the major accomplishments planned over time to re-engineer the IDC system. The IMP and the associate Integrated Master Schedule (IMS) are used for planning, scheduling, executing, and tracking the project technical work efforts. REVISIONS Version Date Author/Team Revision Description Authorized by V1.0 12/2014 IDC Re- engineering Project Team Initial delivery M. Harris

  17. NIF Projects Controls and Information Systems Software Quality Assurance Plan

    SciTech Connect (OSTI)

    Fishler, B

    2011-03-18

    Quality achievement for the National Ignition Facility (NIF) and the National Ignition Campaign (NIC) is the responsibility of the NIF Projects line organization as described in the NIF and Photon Science Directorate Quality Assurance Plan (NIF QA Plan). This Software Quality Assurance Plan (SQAP) is subordinate to the NIF QA Plan and establishes quality assurance (QA) activities for the software subsystems within Controls and Information Systems (CIS). This SQAP implements an activity level software quality assurance plan for NIF Projects as required by the LLNL Institutional Software Quality Assurance Program (ISQAP). Planned QA activities help achieve, assess, and maintain appropriate quality of software developed and/or acquired for control systems, shot data systems, laser performance modeling systems, business applications, industrial control and safety systems, and information technology systems. The objective of this SQAP is to ensure that appropriate controls are developed and implemented for management planning, work execution, and quality assessment of the CIS organization's software activities. The CIS line organization places special QA emphasis on rigorous configuration control, change management, testing, and issue tracking to help achieve its quality goals.

  18. Planning, Budget, and Analysis

    Broader source: Energy.gov [DOE]

    Presentation on Planning, Budget, and Analysis to the DOE Systems Analysis Workshop held in Washington, D.C. July 28-29, 2004.

  19. ORISE: Exercise Planning

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    exercises to test disaster preparedness plans, including full-function exercises, drills and tabletops to ready the U.S. Department of Energy (DOE) and other government...

  20. PROJECT MANGEMENT PLAN EXAMPLES

    Energy Savers [EERE]

    required to support S&M and D&D Certified vendor information Chemical and hazardous substance inventory Deactivation work plans Descriptionphotos of spaces...

  1. Community Relations Plan

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    and disagreements between the Permittees and the public are documented during the Hazardous Waste Facility Permit Community Relations Plan development. Contact Environmental...

  2. State Energy Strategic Planning

    Office of Energy Efficiency and Renewable Energy (EERE)

    U.S. Department of Energy (DOE) Technical Assistance Program (TAP) presentation at a TAP webinar held on April 3, 2013 and dealing with state energy strategic planning.

  3. Milestone Plan Process Improvement

    Office of Environmental Management (EM)

    community's concern over the milestone plan (MP) process within the system, the STRIPES Project Office initiated an in-depth evaluation of the required steps and issues...

  4. Environmental Management System Plan

    E-Print Network [OSTI]

    Fox, Robert

    2009-01-01

    OIA/OCA/assurance-sys/IA/index.html Management Program, R-3 • Environmental Management System Plan References 30.targets, and Environmental Management Programs 6. Structure

  5. Carver Retirement Plans

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    File Storage Software and Tools Performance and Optimization Retirement Plans PDSF Genepool Testbeds Retired Systems Storage & File Systems Data & Analytics Connecting to NERSC...

  6. Medial Axis Local Planner: Local Planning for Medial Axis Roadmaps 

    E-Print Network [OSTI]

    Manavi, Kasra Mehron

    2012-07-16

    implemented this local planner and have tested it in 2D and 3D rigid body and 8D and 16D fixed base articulated linkage environments. We compare MALP with a straight-line local planner (SL), a typical local planer used in motion planning that interpolated...

  7. Multi-Agent Planning and Crowd Simulation Background and Challenge

    E-Print Network [OSTI]

    Pollefeys, Marc

    collision- free paths for 1,000 agents at 22 fps. Adaptive Elastic Roadmaps We have developed a novel roadmap data structure to plan the motion of large number of agents in dynamic environments. The roadmap representation, called Adaptive Elastic Roadmap (AERO), replaces straight-line links with bands that deform based

  8. Online Housing Application, Room Selection & Dining Plan Instructions

    E-Print Network [OSTI]

    Cantlon, Jessica F.

    1 Online Housing Application, Room Selection & Dining Plan Instructions 2014-15 Table of Contents Financial Clearance 3 On Campus Housing Requirements 4 Selecting Alone 4 Selecting as a Group 4 Mutual Requests 4 Lottery Days and Times 4 Kinds of Housing 5 On-line Application Process 6 Room Selection Process

  9. Forecast-driven tactical planning models for manufacturing systems

    E-Print Network [OSTI]

    Chhaochhria, Pallav

    2011-01-01

    Our work is motivated by real-world planning challenges faced by a manufacturer of industrial products. In the first part of the thesis, we study a multi-product serial-flow production line that operates in a low-volume, ...

  10. Coiled transmission line pulse generators

    DOE Patents [OSTI]

    McDonald, Kenneth Fox (Columbia, MO)

    2010-11-09

    Methods and apparatus are provided for fabricating and constructing solid dielectric "Coiled Transmission Line" pulse generators in radial or axial coiled geometries. The pour and cure fabrication process enables a wide variety of geometries and form factors. The volume between the conductors is filled with liquid blends of monomers, polymers, oligomers, and/or cross-linkers and dielectric powders; and then cured to form high field strength and high dielectric constant solid dielectric transmission lines that intrinsically produce ideal rectangular high voltage pulses when charged and switched into matched impedance loads. Voltage levels may be increased by Marx and/or Blumlein principles incorporating spark gap or, preferentially, solid state switches (such as optically triggered thyristors) which produce reliable, high repetition rate operation. Moreover, these Marxed pulse generators can be DC charged and do not require additional pulse forming circuitry, pulse forming lines, transformers, or an a high voltage spark gap output switch. The apparatus accommodates a wide range of voltages, impedances, pulse durations, pulse repetition rates, and duty cycles. The resulting mobile or flight platform friendly cylindrical geometric configuration is much more compact, light-weight, and robust than conventional linear geometries, or pulse generators constructed from conventional components. Installing additional circuitry may accommodate optional pulse shape improvements. The Coiled Transmission Lines can also be connected in parallel to decrease the impedance, or in series to increase the pulse length.

  11. Knowledge and plan execution management in planning fire fighting operations

    E-Print Network [OSTI]

    Fernández Olivares, Juan

    Knowledge and plan execution management in planning fire fighting operations Marc de la Asunci to assist human experts in the design of forest fire fighting plans. Issues about how to engineer planning knowledge for such a system, how to monitor the execution of fighting plans and how to patch unfeasible

  12. Health Education Lesson Plans Health Education Lesson Plans

    E-Print Network [OSTI]

    de Lijser, Peter

    Health Education Lesson Plans Health Education Lesson Plans (Healthy Kids Resource Center; no lesson plans to download, but library of health curriculum http://www.hkresources.org/ Dairy Council://www.epa.gov/teachers For Lesson Plans http://www.forlessonplans.com Health Lessons Plans Web Quest http://www.edhelper.com/cat55

  13. Waste Management Plan for the Oak Ridge National Remedial Investigation/Feasibility Study

    SciTech Connect (OSTI)

    Not Available

    1988-04-01

    In accordance with the requirements of the Remedial Investigation/Feasibility Study (RI/FS) Project Quality Assurance Plan, this Waste Management Plan establishes clear lines of responsibility and authority, documentation requirements, and operational guidance for the collection, identification, segregation, classification, packaging, certification, and storage/disposal of wastes. These subjects are discussed in the subsequent sections of this document.

  14. World pipeline construction patterns shifting away from big North American gas lines

    SciTech Connect (OSTI)

    Koen, A.D.; True, W.R.

    1992-02-10

    The pattern of world pipeline construction has begun to shift away from large diameter gas lines in North America. Total miles of gas pipelines planned this year and beyond have registered big increases in Europe and Asia- Pacific regions, more than offsetting decreased mileage of planned U.S. and Canadian gas projects. World products pipeline construction planned in 1992 and beyond shows the largest year to year gain, paced by projects in Latin America. Those are among highlights of this article. Many projects only under study or unlikely to be built are excluded from final mileage tallies.

  15. Implementing Motor Decision Plans 

    E-Print Network [OSTI]

    Elliott, R. N.

    2001-01-01

    The first step to reducing energy costs and increasing reliability in motors is to establish a motor plan. A motor plan allows decisions to be made in advance of motor failure, and increases the options available. By contrast, most motor decisions...

  16. EMERGENCY RESPONSE EVACUATION PLAN

    E-Print Network [OSTI]

    Nicholson, Bruce J.

    EMERGENCY RESPONSE AND EVACUATION PLAN #12;Emergency Response and Evacuation Plan ­ June 2010 i EMERGENCY RESPONSE PHONE NUMBERS 2 PROCEDURES FOR REPORTING FIRE OR OTHER EMERGENCIES 3 RESPONSIBILITIES (EMPLOYEE/SUPERVISOR) 4 EMERGENCY EVACUATION PROCEDURES OVERVIEW 5 PROCEDURES FOR EVACUATING MOBILITY

  17. Emergency Evacuation Operations Plan

    E-Print Network [OSTI]

    Eberhard, Marc O.

    Emergency Evacuation Operations Plan Civil and Environmental Engineering More Hall 2015 #12;1 Introduction Environmental Health and Safety (EH&S) developed this model Emergency Evacuation and Operations Plan (EEOP) to assist departments in preparing for building emergencies as expected and required

  18. The Sellafield Plan - 12458

    SciTech Connect (OSTI)

    Irving, Iain [Stakeholder Relations Director, Sellafield Ltd, Cumbria (United Kingdom)

    2012-07-01

    The Sellafield Performance Plan represents the start of a new era for the Sellafield site. It is a key driver in the Nuclear Management Partners mission to make Sellafield safer, cleaner, more productive, more cost effective and a better neighbour. When published in summer 2011, the Sellafield Performance Plan set out exactly what work would be completed at Sellafield between 2010/11 and 2025/26, how all of the facilities on the site interact, and what new facilities would be needed in order to deliver the risk and hazard reduction mission. The plan is the first credible and underpinned lifetime plan for the Sellafield site - the most complex part of the UK's civil nuclear estate. Under the Sellafield Performance Plan there are projected to be more jobs longer creating opportunities for the site, its workforce and the economic stability of West Cumbria. The Sellafield Ltd performance plan sets out how NMP will apply their global experience to improve operations, generate efficiencies and deliver detailed programmes of work with the aim of accelerating decommissioning and providing value for money. Successful delivery of the plan will also ensure the site continues to effectively operate critical national infrastructure that supports the UK's energy programme, and maintains the safe and secure management and storage of nuclear materials. The NDA and UK Government have demonstrated their confidence in NMP and Sellafield Ltd's capability to deliver this plan by providing the highest-ever Annual Site Funding Limit for the site in 2011/12. The Sellafield Performance Plan also creates both the foundation and the environment for a vibrant West Cumbrian economy through significant opportunities for the local supply chain and real prospects for further inward investment. By working flexibly and accelerating the decommissioning programme, the plan provides the opportunity for significant retraining to adapt to future challenges on the site and for other potential new nuclear missions in West Cumbria. (authors)

  19. Strategic Planning Thursday Commons Update

    E-Print Network [OSTI]

    Minnesota, University of

    Strategic Planning Thursday Commons Update October 2, 2014 #12;Real-Time Strategic Planning · Model for non-profit strategic planning · Tools and process to develop strategies and action plans in a short, Fieldstone Alliance, p. 31 #12;UMC's Strategic Planning www.umcrookston.edu/stratplan · Since the April

  20. Strategic Plan National Ocean Service

    E-Print Network [OSTI]

    Strategic Plan of the National Ocean Service 2005-2010 U.S. Department of Commerce National Oceanic Strategic Plan for 2005 to 2010. This Plan heralds a new era for the ocean and coasts as NOS responds these challenges. The NOS Strategic Plan is synchronous with the NOAA Strategic Plan -- one NOAA, one workforce

  1. Probabilistically Reusing Plans in Deterministic Planning DANIEL BORRAJO

    E-Print Network [OSTI]

    Veloso, Manuela M.

    and the goals. As an example, LPG-ADAPT (Fox et al. 2006) focuses on re- planning with minimum changes to previous plans using the LPG planner. They adapted LPG plan-modification heuris- tics, trying to maximize

  2. Wyss Institute Chemical Hygiene Plan CHEMICAL HYGIENE PLAN

    E-Print Network [OSTI]

    Napp, Nils

    Wyss Institute Chemical Hygiene Plan CHEMICAL HYGIENE PLAN The Wyss Institute for Biologically Inspired Engineering June 2015 #12;Wyss Institute Chemical Hygiene Plan TABLE OF CONTENTS 1.0 POLICY..........................................................................................2 2.1 CHEMICAL HYGIENE OFFICER

  3. Multiple Query Probabilistic Roadmap Planning using Single Query Planning Primitives

    E-Print Network [OSTI]

    Chen, Brian Y.

    Multiple Query Probabilistic Roadmap Planning using Single Query Planning Primitives Kostas E query planners. Our implementation uses a probabilistic roadmap method (PRM) with bidirec- tional the strengths of both is obtained. The probabilistic roadmap method (PRM) approach to motion planning

  4. South Texas Planning Region Public Transportation Coordination Plan 

    E-Print Network [OSTI]

    South Texas Development Council Economic Development Program

    2006-12-15

    stream_source_info SOUTH TEXAS PLANNING REGION PUBLIC TRANSPORTATION COORDINATION PLAN.pdf.txt stream_content_type text/plain stream_size 58851 Content-Encoding ISO-8859-1 stream_name SOUTH TEXAS PLANNING REGION PUBLIC TRANSPORTATION... COORDINATION PLAN.pdf.txt Content-Type text/plain; charset=ISO-8859-1 KFH GROUP, INC. SOUTH TEXAS PLANNING REGION PUBLIC TRANSPORTATION COORDINATION PLAN Developed for the: SOUTH TEXAS DEVELOPMENT COUNCIL ECONOMIC...

  5. Quality Assurance Project Plan for Facility Effluent Monitoring Plan activities

    SciTech Connect (OSTI)

    Frazier, T.P.

    1994-10-20

    This Quality Assurance Project Plan addresses the quality assurance requirements for the activities associated with the Facility Effluent Monitoring Plans, which are part of the overall Hanford Site Environmental Protection Plan. This plan specifically applies to the sampling and analysis activities and continuous monitoring performed for all Facility Effluent Monitoring Plan activities conducted by Westinghouse Hanford Company. It is generic in approach and will be implemented in conjunction with the specific requirements of the individual Facility Effluent Monitoring Plans.

  6. BUILDING A RISK MANAGEMENT PLAN BUILDING A RISK MANAGEMENT PL LDING A RISK MANAGEMENT PLAN BUILDING A RISK MANAGEMENT PLAN

    E-Print Network [OSTI]

    Florida, University of

    BUILDING A RISK MANAGEMENT PLAN BUILDING A RISK MANAGEMENT PL LDING A RISK MANAGEMENT PLAN BUILDING A RISK MANAGEMENT PLAN MANAGEMENT PLAN BUILDING A RISK MANAGEMENT PLAN BUILDING A R RISK MANAGEMENT PLAN BUILDING A RISK MANAGEMENT PLAN BUILDIN T PLAN BUILDING A RISK MANAGEMENT PLAN BUILDING A RISK MANAGEM

  7. Preplanning Method for Multi-Story Building Construction using Line of Balance Proceedings IGLC '98

    E-Print Network [OSTI]

    Tommelein, Iris D.

    of the method support lean construction concepts, such as waste elimination, variances minimization, flexible ones, which have float time. It means that the planning construction incorporates wastes whatPreplanning Method for Multi-Story Building Construction using Line of Balance Proceedings IGLC '98

  8. Plan generation strategies for a knowledge based process planning system 

    E-Print Network [OSTI]

    Hari, Umesh

    1993-01-01

    by the meta-knowledge entities called as meta-goals, meta-plans and meta-themes. These planning elements are then encapsulated into a plan generation mechanism within the master planner. The planning activity is stratified into four modules based... . 4. I Introduction 4. 2 Planning Mechanism 4. 3 Ontology of Planning Modes 4. 4 Meta-Planning Knowledge 4. 5 Architecture of the Master Planner V IDEFO MODELS OF PROCESS PLANNING ACTIVITIES Page 59 59 59 63 66 68 70 5. I Introduction 5...

  9. Interconnection-Wide Transmission Planning Initiative - Meeting...

    Energy Savers [EERE]

    Recovery Act Interconnection Transmission Planning Interconnection-Wide Transmission Planning Initiative - Meeting Calendars Interconnection-Wide Transmission Planning...

  10. ES H action plan

    SciTech Connect (OSTI)

    Not Available

    1991-01-01

    This document contains planned actions to correct the deficiencies identified in the Pre-Tiger Team Self-Assessment (PTTSA), January 1991, of Sandia National Laboratories (SNL -- Albuquerque, New Mexico; Tonopah, Nevada; and Kauai, Hawaii). The Self-Assessment was conducted by a Self-Assessment Working Group consisting of 19 department managers, with support from Environment, Safety, and Health (ES H) professionals, from October through December 1990. Findings from other past audits, dating back to 1985, were reviewed and compared with the PTTSA findings to determine if additional findings, key findings, or root causes were warranted. The resulting ES H Action Plan and individual planned actions were prepared by the ES H Action Plan Project Group with assistance from the Program owners/authors during February and March 1991. The plan was reviewed by SNL Management in April 1991. This document serves as a planning instrument for the Laboratories to aid in the scoping and sizing of activities related to ES H compliance for the coming five years. It will be modified as required to ensure a workload/funding balance and to address the findings resulting from the Tiger Team assessment at SNL, Albuquerque. The process of producing this document has served well to prepare SNL, Albuquerque, for the coming task of producing the required post-Tiger Team action plan document. 8 tabs.

  11. Public affairs plan

    SciTech Connect (OSTI)

    Not Available

    1994-09-01

    The purpose of the Uranium Mill Tailings Remedial Action (UMTRA) Project Public Affairs Plan is to establish goals for the Fiscal Year 1995 UMTRA public affairs program and identify specific activities to be conducted during the year. It also describes the roles of various agencies involved in the conduct of the public affairs program and defines the functions of the Technical Assistance Contractor (TAC) Public Affairs Department. It integrates and replaces the Public Participation Plan (DOE/AL/62350-47D) and Public Information Plan (DOE/AL/623590-71). The plan describes the US Department of Energy`s (DOE) plans to keep stakeholders and other members of the public informed about project policies, plans, and activities, and provide opportunities for stakeholders and interested segments of the public to participate in project decision-making processes. The plan applies to the UMTRA Project Office; the DOE Albuquerque Operations Office, Office of Intergovernmental and External Affairs (OIEA); the UMTRA TAC; the UMTRA Remedial Action Contractor (RAC); and other cooperating agencies.

  12. Automated Planning RW Theory RW Search Application Plan Improvement Systems Conclusions Random Walk Planning: Theory, Practice,

    E-Print Network [OSTI]

    Müller, Martin

    Automated Planning RW Theory RW Search Application Plan Improvement Systems Conclusions Random Walk Planning: Theory, Practice, and Application Hootan Nakhost University of Alberta, Canada Google Canada since May 2013 May 9, 2012 #12;Automated Planning RW Theory RW Search Application Plan Improvement

  13. 2015 -2021 ARCHITECTURE, PLANNING & PRESERVATION

    E-Print Network [OSTI]

    Turro, Nicholas J.

    1 2015 - 2021 #12;2 ARCHITECTURE, PLANNING & PRESERVATION Spring 2015 Registration Dates Monday Incoming Architecture, Planning & Preservation Students Tuesday, September 1 - Thursday, September 3 All Returning Architecture, Planning & Preservation Students Monday, April 13 - Friday, April 17 Tuesday

  14. DepartmentofHorticulture Strategic Plan

    E-Print Network [OSTI]

    DepartmentofHorticulture Strategic Plan 20132019 CollegeofAgricultureandLifeSciences #12; Department of Horticulture Strategic Plan 20132019 2 Contents Department of Horticulture .................................................................................................................................................. 16 #12; Department of Horticulture Strategic Plan 20132019 3 Letterfromthe

  15. Bottom-Up Strategic Planning

    E-Print Network [OSTI]

    Williams, Jeff; Dearie, Tammy; Schottlaender, Brian E.C.

    2013-01-01

    and Hiram Davis, “Strategic-Planning as a Catalyst forD. Hensley, “A New Strategic-Planning Model for Academic-Academic Libraries: Should Strategic Planning Be Renewed? ,”

  16. Climate Action Plan 2009 Sustainability

    E-Print Network [OSTI]

    Capogna, Luca

    Climate Action Plan September 2009 Sustainability Council This plan outlines methods by which. This document is publicly available at http://sustainability.uark.edu. #12;2 University of Arkansas Climate....................................................................................................................................7 Climate Action Plan Committee

  17. In-line thermoelectric module

    DOE Patents [OSTI]

    Pento, Robert (Algonquin, IL); Marks, James E. (Glenville, NY); Staffanson, Clifford D. (S. Glens Falls, NY)

    2000-01-01

    A thermoelectric module with a plurality of electricity generating units each having a first end and a second end, the units being arranged first end to second end along an in-line axis. Each unit includes first and second elements each made of a thermoelectric material, an electrically conductive hot member arranged to heat one side of the first element, and an electrically conductive cold member arranged to cool another side of the first element and to cool one side of the second element. The hot member, the first element, the cold member and the second element are supported in a fixture, are electrically connected respectively to provide an electricity generating unit, and are arranged respectively in positions along the in-line axis. The individual components of each generating unit and the respective generating units are clamped in their in-line positions by a loading bolt at one end of the fixture and a stop wall at the other end of the fixture. The hot members may have a T-shape and the cold members an hourglass shape to facilitate heat transfer. The direction of heat transfer through the hot members may be perpendicular to the direction of heat transfer through the cold members, and both of these heat transfer directions may be perpendicular to the direction of current flow through the module.

  18. Phase II Planning for Niall Gaffney

    E-Print Network [OSTI]

    Phase II Planning for the HET Niall Gaffney March 6, 1997 #12;#12;Phase II Planning for the HET 3 ................................................................................................................................. 38 Plan Templates .............................................................................................................................................. 47 Example Plans

  19. Phase II Planning for Niall Gaffney

    E-Print Network [OSTI]

    Phase II Planning for the HET Niall Gaffney March 6, 1997 #12; #12; Phase II Planning for the HET 3 ................................................................................................................................. 38 Plan Templates .............................................................................................................................................. 47 Example Plans

  20. Alaska Strategic Energy Plan and Planning Handbook

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE: Alternative FuelsofProgram:Y-12 Beta-3AUDITLeslie PezzulloAgendaChampion:Plans GeothermalAEA

  1. Planning for Years to Come

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Planning for Years to Come Planning for Years to Come LANL's Governing Policy on the Environment August 1, 2013 Water sampling tour for the Association of Experiential Education...

  2. Southeast Washington Subbasin Planning Ecoregion

    E-Print Network [OSTI]

    Southeast Washington Subbasin Planning Ecoregion Wildlife Assessment Paul R. Ashley and Stacey H. Stovall 2004 #12;SOUTHEAST WASHINGTON SUBBASIN PLANNING ECOREGION WILDLIFE ASSESSMENT i Table of Contents

  3. Attachment C ? Waste Analysis Plan

    Office of Environmental Management (EM)

    PLAN 1 Los Alamos National Laboratory Hazardous Waste Permit December 2013 TABLE OF CONTENTS LIST OF TABLES 2 WASTE ANALYSIS PLAN......

  4. Climate Action Plan 2013 Update

    E-Print Network [OSTI]

    Rose, Michael R.

    UC Irvine Climate Action Plan 2013 Update #12;CLIMATE ACTION PLAN - 2013 UPDATE 1 TABLE OF CONTENTS CLIMATE PROTECTION GOALS...............................................................18 OPPORTUNITIES-2050 CLIMATE NEUTRALITY.........................................................29 MEDICALCENTER IMPLEMENTATION

  5. Draft Closure Plan

    Office of Environmental Management (EM)

    Waste Permit December 2014 If there is liquid found in either the drain lines or the sumps at the time of the assessment liquid samples will be collected in accordance with...

  6. Site Sustainability Plan

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    water for non- contact and fire protection purposes in the event that the D&R Canal Pump House is off-line. Thus, operational conditions may result in dramatic annual...

  7. Environmental Implementation Plan

    SciTech Connect (OSTI)

    Not Available

    1993-03-15

    The purpose of the Environmental Implementation Plan (EIP) is to show the current and future (five years) environmental plans from individual site organizations and divisions, as well as site environmental programs and initiatives which are designed to protect the environment and meet or exceed changing environmental/regulatory requirements. Communicating with site organizations, departments, and committees is essential in making the site`s environmental-planning process work. The EIP gives the site the what, when, how, and why for environmental requirements. Through teamwork and proactive planning, a partnership for environmental excellence is formed to achieve the site vision for SRS to become the recognized model for Environmental Excellence in the Department of Energy`s Nuclear Weapons Complex.

  8. Environmental Implementation Plan

    SciTech Connect (OSTI)

    Not Available

    1993-03-15

    The purpose of the Environmental Implementation Plan (EIP) is to show the current and future (five years) environmental plans from individual site organizations and divisions, as well as site environmental programs and initiatives which are designed to protect the environment and meet or exceed changing environmental/regulatory requirements. Communicating with site organizations, departments, and committees is essential in making the site's environmental-planning process work. The EIP gives the site the what, when, how, and why for environmental requirements. Through teamwork and proactive planning, a partnership for environmental excellence is formed to achieve the site vision for SRS to become the recognized model for Environmental Excellence in the Department of Energy's Nuclear Weapons Complex.

  9. Developing a Marketing Plan 

    E-Print Network [OSTI]

    Bevers, Stan; Waller, Mark L.; Amosson, Stephen H.; McCorkle, Dean

    2009-03-02

    Developing a good marketing plan will help you identify and quantify costs, set price goals, determine potential price outlook, examine production and price risk, and develop a strategy for marketing your crop. This publication describes...

  10. Technical Planning Basis

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2007-07-11

    The Guide assists DOE/NNSA field elements and operating contractors in identifying and analyzing hazards at facilities and sites to provide the technical planning basis for emergency management programs. Supersedes DOE G 151.1-1, Volume 2.

  11. Planning for the future

    SciTech Connect (OSTI)

    Lesh, Pamela

    2009-06-15

    Four changes to integrated resource planning could significantly improve alignment between future utility spending and the forces and changes that are upending past preconceptions of how to predict future load. (author)

  12. Comprehensive Plan Navasota, Texas 

    E-Print Network [OSTI]

    Pugh, David; Butler, Christopher; Stover, Robin; Blanchard, Kathlyn; Butler, Cristopher; Cardenas, Angela; Carrasco, Virginia; Dewey, Michael; Duncan, Sean; Dyke, Jennifer; Dyke, Michael; Highfield, Wesley; Johnson, Laura; Kansara, Suhag; Kukadia, Nishant; Linenschmidt, Mark; Mohinder, Ruchi; Stover, Robin; Thornton, Sara

    2004-01-01

    In total, over the years, eleven courses have worked in the city of Navasota. These plans have assessed the conditions of the city and have made recommendations for economic growth, downtown revitalization, land use ...

  13. Planning with Templates 

    E-Print Network [OSTI]

    Dyer, D; Cross, S; Knoblock, C.A; Minton, S; Tate, Austin

    2005-01-01

    When we talk about planning with templates,we mean standard operating procedures we've learned or been trained to use for solving typical problems and as a starting point for solving novel problems. These structures ...

  14. Transmission planning in the era of integrated resource planning: A survey of recent cases

    SciTech Connect (OSTI)

    Baldick, R.; Kahn, E.P.

    1992-09-01

    State action is critical to the expansion of the high-voltage transmission network, because regulated utilities must seek approval from utility commissions for proposals to site new lines. It is the purpose of this report to survey the regulatory treatment of issues that are unique to or ubiquitous in transmission planning and use. The authors review recent transmission siting cases to examine how the issues are presented to and resolved by state regulatory commissions and to provide a perspective for more general discussion of transmission policy. Their primary focus is on planning issues. Transmission capacity expansion is not typically treated in integrated resource planning. It is usually assumed that there is adequate transmission to achieve any particular plan. The authors believe that one important reason for this omission is the inherent complexity of transmission system expansion. Regulators and competitors may be at a serious disadvantage in negotiating or adjudicating specific transmission proposals with utilities, who generally have greater knowledge of both general technological considerations and case specifics. This problem of asymmetric information must be addressed at some level in planning or dispute resolution. However, they observe that explicit consideration of the information problem is absent from most regulatory and technical analysis of transmission. The goal of this survey is to share knowledge about the problems facing state regulators over the siting of new transmission facilities, and help to define constructive approaches to them.

  15. Environmental implementation plan

    SciTech Connect (OSTI)

    Peterson, G.L.

    1994-10-04

    In this document, the Savannah River site environmental programs and plans from DOE contractors and Westinghouse Savannah River Company divisions/departments are presented along with the environmental coordinator for each program. The objectives are to enhase communication of existing or planned programs to do the following: identify activities required for meeting environmental needs; identify needing resources and a schedule to accomplish those activities; promote share-savings and consistency in those activities.

  16. TWRS safety management plan

    SciTech Connect (OSTI)

    Popielarczyk, R.S., Westinghouse Hanford

    1996-08-01

    The Tank Waste Remediation System (TWRS) Safety Management Program Plan for development, implementation and maintenance of the tank farm authorization basis is described. The plan includes activities and procedures for: (a) Updating the current Interim Safety Basis, (b) Development,implementation and maintenance of a Basis for Interim Operations, (c) Development, implementation and maintenance of the Final Safety Analyses Report, (d) Development and implementation of a TWRS information Management System for monitoring the authorization basis.

  17. Public affairs plan

    SciTech Connect (OSTI)

    NONE

    1995-09-01

    The purpose of the Uranium Mill Tailings Remedial Action (UMTRA) Project Public Affairs Plan is to establish goals for the fiscal year (FY) 1996 UMTRA Project public affairs program and to identify specific activities to be conducted during the year. It describes the roles of various agencies involved in the public affairs program and defines the functions of the UMTRA Project Technical Assistance Contractor (TAC) Public Affairs Department. It replaces the FY 1995 Public Affairs Plan (DOE/AL/62350-154). The plan also describes the US Department of Energy`s (DOE) plans to keep stakeholders and other members of the public informed about UMTRA Project policies, plans, and activities, and provide opportunities for stakeholders and interested segments of the public to participate in UMTRA Project decision-making processes. The plan applies to the UMTRA Project Team; the DOE Grand Junction Projects Office (GJPO); the DOE Albuquerque Operations Office, Office of Public Affairs (OPA); the TAC; the UMTRA Project Remedial Action Contractor (RAC); and other cooperating agencies.

  18. TWRS retrieval and disposal mission, immobilized high-level waste storage plan

    SciTech Connect (OSTI)

    Calmus, R.B.

    1998-01-07

    This project plan has a two fold purpose. First, it provides a plan specific to the Hanford Tank Waste Remediation System (TWRS) Immobilized High-Level Waste (EMW) Storage Subproject for the Washington State Department of Ecology (Ecology) that meets the requirements of Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) milestone M-90-01 (Ecology et al. 1996) and is consistent with the project plan content guidelines found in Section 11.5 of the Tri-Party Agreement action plan. Second, it provides an upper tier document that can be used as the basis for future subproject line item construction management plans. The planning elements for the construction management plans are derived from applicable U.S. Department of Energy (DOE) planning guidance documents (DOE Orders 4700.1 (DOE 1992a) and 430.1 (DOE 1995)). The format and content of this project plan are designed to accommodate the plan`s dual purpose. A cross-check matrix is provided in Appendix A to explain where in the plan project planning elements required by Section 11.5 of the Tri-Party Agreement are addressed.

  19. NETL LINES OF DEMARCATION 09282012

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantityBonneville Power Administration wouldMass map shines light on771/6/14 Contact: Janet Lambert Reviewed: 3/5/14 Page 1 of 178LINES

  20. Rulison Monitoring Plan

    SciTech Connect (OSTI)

    2010-07-01

    The Project Rulison Monitoring Plan has been developed as part of the U.S. Department of Energy (DOE) Office of Legacy Management's mission to protect human health and the environment. The purpose of the plan is to monitor fluids from gas wells for radionuclides that would indicate contamination is migrating from the Rulison detonation zone to producing gas wells, allowing action to be taken before the contamination could pose a risk. The Monitoring Plan (1) lists the contaminants present and identifies those that have the greatest potential to migrate from the detonation zone (radionuclide source term), (2) identifies locations that monitor the most likely transport pathways, (3) identifies which fluids will be sampled (gas and liquid) and why, (4) establishes the frequency of sampling, and (5) specifies the most practical analyses and where the analysis results will be reported. The plan does not affect the long-term hydrologic sampling conducted by DOE since 1972, which will continue for the purpose of sampling shallow groundwater and surface water near the site. The Monitoring Plan was developed in anticipation of gas wells being drilled progressively nearer the Rulison site. DOE sampled 10 gas wells in 1997 and 2005 at distances ranging from 2.7 to 7.6 miles from the site to establish background concentrations for radionuclides. In a separate effort, gas industry operators and the Colorado Oil and Gas Conservation Commission (COGCC) developed an industry sampling and analysis plan that was implemented in 2007. The industry plan requires the sampling of gas wells within 3 miles of the site, with increased requirements for wells within 1 mile of the site. The DOE plan emphasizes the sampling of wells near the site (Figure 1), specifically those with a bottom-hole location of 1 mile or less from the detonation, depending on the direction relative to the natural fracture trend of the producing formation. Studies indicate that even the most mobile radionuclides created by the test are unlikely to migrate appreciable distances (hundreds of feet) from the detonation zone (Cooper et al. 2007, 2009). The Monitoring Plan was developed to provide a cautious and comprehensive approach for detecting any potential contaminant migration from the Rulison test site. It also provides an independent confirmation of results from the industry sampling and analysis plan while effectively increasing the sampling frequency of wells near the site.

  1. Capillary electrophoresis-fluorescence line narrowing system (CE-FLNS) for on-line structural characterization

    DOE Patents [OSTI]

    Jankowiak, Ryszard J. (Ames, IA); Small, Gerald J. (Ames, IA); Shields, Peter A. (Reading, MA)

    1999-04-27

    Capillary electrophoresis (CE) is interfaced with low temperature fluorescence line-narrowing (FLN) spectroscopy for on-line structural characterization of separated molecular analytes.

  2. Capillary electrophoresis-fluorescence line narrowing system (CE-FLNS) for on-line structural characterization

    DOE Patents [OSTI]

    Jankowiak, R.J.; Small, G.J.; Shields, P.A.

    1999-04-27

    Capillary electrophoresis (CE) is interfaced with low temperature fluorescence line-narrowing (FLN) spectroscopy for on-line structural characterization of separated molecular analytes. 21 figs.

  3. Coordination of Transmission Line Transfer Capabilities

    E-Print Network [OSTI]

    Coordination of Transmission Line Transfer Capabilities Final Project Report Power Systems since 1996 PSERC #12;Power Systems Engineering Research Center Coordination of Transmission Line Industry Representative Richard Goddard Portland General Electric Research Team Students Yuan Li Yonghong

  4. Nondestructive Testing of Rail Tunnel Linings 

    E-Print Network [OSTI]

    Williams, Nathan Douglas

    2014-11-14

    potential problems and then test those areas with slow, detailed methods. This would provide a more thorough investigation of the tunnel lining’s health. Infrared thermography (IRT), ground penetrating radar (GPR), and ultrasonic tomography (UST) techniques...

  5. Environmental Restoration Quality Program Plan

    SciTech Connect (OSTI)

    Colley, J.S.

    1992-08-01

    The Martin Marietta Energy Systems, Inc., Environmental Restoration (ER) Program was initially chartered on October 1, 1989, as a entral Environmental Restoration Division'' to manage the investigation and remediation of inactive sites and facilities that have been declared surplus and have no further programmatic use. The Energy Systems ER Division was established to support the DOE Oak Ridge Field Office (DOE-OR) consolidated ER Program. The DOE-OR Assistant Manager for Environmental Restoration and Waste Management provides program and budget direction to the Energy Systems ER Program for environmental restoration activities at the sites operated by Energy Systems (Oak Ridge K-25 Site, Oak Ridge National Laboratory, Oak Ridge Y-12 Plant, Paducah Gaseous Diffusion Plant, Portsmouth Gaseous Diffusion Plant) and at the off-site locations. The Energy Systems ER Division is specifically charged with assessing these sites for potential contamination and managing the cleanup processes. The Energy Systems Environmental Restoration Division was chartered on October 1, 1989, as a central organization to manage the Remedial Action (RA) Program. The purpose of this document is to ensure that: senior ER management provides planning, organization, direction, control, and support to achieve the organization's objectives; the line organization achieves quality; and overall performance is reviewed and evaluated using a rigorous assessment process.

  6. World-line approach to Sign Problems

    E-Print Network [OSTI]

    Aarts, Gert

    World-line approach to Sign Problems Shailesh Chandrasekharan Duke University #12;Outline XY model + chemical potential world-line approach solving the silver blaze problem! Two component bosons + Abelian world-line approach solving the silver blaze problem! more flavors + solving sign problems

  7. Linear rotary optical delay lines Maksim Skorobogatiy*

    E-Print Network [OSTI]

    Skorobogatiy, Maksim

    Linear rotary optical delay lines Maksim Skorobogatiy* Department of Engineering Physics, École of analytical and semi-analytical solutions for the design of high-speed rotary optical delay lines that use of optical delay. Finally, two prototypes of rotary delay lines were fabricated using CNC machining

  8. Strategic Planning 12 June 2009

    E-Print Network [OSTI]

    Arnold, Jonathan

    Strategic Planning 20102020 12 June 2009 1 #12;Faculty Survey May 2009May 2009 #12;Methodology Other 13 #12;Are you aware of current UGA Strategic Plan?Are you aware of current UGA Strategic Plan? #12;Strategic Plan ­ Faculty Survey Do you feel UGA has met the goals of the 20002010Do you feel UGA

  9. STRATEGIC PLAN Sir Moir Lockhead

    E-Print Network [OSTI]

    Neri, Peter

    STRATEGIC PLAN 2011-2015 #12;Contents Foreword 3 Sir Moir Lockhead Global Ambitions 5 Professor Ian Delivering our Academic Vision Strategic Targets 20 University of Aberdeen | Strategic Plan 2011-2015 1 #12;3University of Aberdeen | Strategic Plan 2011-2015 In taking the Plan forward, the University's staff can

  10. STRATEGIC PLAN Board of Trustees

    E-Print Network [OSTI]

    Kunkle, Tom

    STRATEGIC PLAN Board of Trustees October 16, 2009 #12;1 | strategic plan INTRODUCTION F ollowing and identification of our peer institutions (all available on the College's Strategic Planning website), the College of Charleston is poised to launch this Strategic Plan aimed at growth and development over the next decade

  11. Business Continuity Planning Schools, Departments

    E-Print Network [OSTI]

    Nicholson, Bruce J.

    failures · Loss of facilities or utilities · Deliberate acts of disruption Business continuity planningBusiness Continuity Planning for Schools, Departments & Support Units 1 #12;What is Business Continuity Planning? Planning for an adverse, major or catastrophic event that would cause a disruption

  12. Environmental Implementation Plan

    SciTech Connect (OSTI)

    Not Available

    1994-02-01

    The Environmental Implementation Plan (EIP) is a dynamic long-range environmental-protection plan for SRS. The EIP communicates the current and future (five year) environmental plans from individual organizations and divisions as well as site environmental initiatives which are designed to protect the environment and meet or exceed compliance with changing environmental/ regulatory requirements. Communication with all site organizations is essential for making the site environmental planning process work. Demonstrating environmental excellence is a high priority embodied in DOE and WSRC policy. Because of your support and participation in the three EIP initiatives; Reflections, Sectional Revision, and Integrated Planning, improvements are being made to the EIP and SRS environmental protection programs. I appreciate the ``Partnership in Environmental Excellence`` formed by the environmental coordinators and professionals who work daily toward our goal of compliance and environmental excellence. I look forward to seeing continued success and improvement in our environmental protection programs through combined efforts of all site organizations to protect our employees, the public health, and the environment. Together, we will achieve our site vision for SRS to be the recognized model for Environmental Excellence in the DOE Nuclear Weapons Complex.

  13. Introduction Multi-hypothesis Planning Tracking by Planning Experiments Multi-hypothesis Motion Planning for Visual

    E-Print Network [OSTI]

    Plotkin, Joshua B.

    Introduction Multi-hypothesis Planning Tracking by Planning Experiments Multi-hypothesis Motion Planning for Visual Object Tracking Haifeng Gong, Jiwoong Sim and Jianbo Shi hfgong@seas.upenn.edu August 17, 2011 H. Gong hfgong@seas.upenn.edu Tracking by Planning #12;Introduction Multi

  14. Energy Organizational Planning

    SciTech Connect (OSTI)

    Gina C. Paradis; James Yockey; Tracey LeBeau

    2009-04-17

    As the Seneca Nation of Indians (SNI) continues to refine and finalize its Strategic Energy Plan, it became necessary to insure that a sustainable organization structure was developed through which the energy program and its initiatives could be nurtured and managed. To that end, SNI undertook a study to thoroughly evaluate the existing organizational structures and assess the requisite changes and/or additions to that framework that would complement the mission of the Strategic Plan. The goal of this study was to analyze, work with staff and leadership and recommend the most effective plan for the development of an organizational framework within which the Seneca could more effectively exercise energy sovereignty – control and manage their natural resource assets – i.e. develop its own energy resources, meet the current and projected energy needs of their community, and “sit at the table” with other regional energy providers to deal with issues on a peer-to-peer basis.

  15. Mode propagation and attenuation in lined ducts

    E-Print Network [OSTI]

    BI, Wenping

    2014-01-01

    Optimal impedance for each mode is an important concept in an infinitely long duct lined with uniform absorption material. However it is not valid for finite length linings. This is because that the modes in lined ducts are not power-orthogonal; the total sound power is not equal to the sum of the sound power of each mode; cross-power terms may play important roles. In this paper, we study sound propagation and attenuation in an infinite rigid duct lined with a finite length of lining impedance. The lining impedance may be axial segments and circumferentially non-uniform. We propose two new physical quantities Kp and S to describe the self-overlap of the left eigenfunction and right eigenfunction of one mode and the normalized overlap between modes, respectively. The two new physical quantities describe totally the mode behaviors in lined ducts.

  16. Unsplit bipolar pulse forming line

    DOE Patents [OSTI]

    Rhodes, Mark A. (Pleasanton, CA)

    2011-05-24

    A bipolar pulse forming transmission line module and system for linear induction accelerators having first, second, third, and fourth planar conductors which form a sequentially arranged interleaved stack having opposing first and second ends, with dielectric layers between the conductors. The first and second planar conductors are connected to each other at the first end, and the first and fourth planar conductors are connected to each other at the second end via a shorting plate. The third planar conductor is electrically connectable to a high voltage source, and an internal switch functions to short at the first end a high voltage from the third planar conductor to the fourth planar conductor to produce a bipolar pulse at the acceleration axis with a zero net time integral. Improved access to the switch is enabled by an aperture through the shorting plate and the proximity of the aperture to the switch.

  17. Magnetically insulated transmission line oscillator

    DOE Patents [OSTI]

    Bacon, L.D.; Ballard, W.P.; Clark, M.C.; Marder, B.M.

    1987-05-19

    A magnetically insulated transmission line oscillator employs self-generated magnetic fields to generate microwave energy. An anode of the oscillator includes slow-wave structures which are formed of a plurality of thin conductive vanes defining cavities therebetween, and a gap is formed between the anode and a cathode of the oscillator. In response to a pulsed voltage applied to the anode and cathode, self-generated magnetic fields are produced in a cross-field orientation with respect to the orientation of the electric field between the anode and the cathode. The cross-field magnetic fields insulate the flow of electrons in the gap and confine the flow of electrons within the gap. 11 figs.

  18. Superconducting transmission line particle detector

    DOE Patents [OSTI]

    Gray, Kenneth E. (Naperville, IL)

    1989-01-01

    A microvertex particle detector for use in a high energy physic collider including a plurality of parallel superconducting thin film strips separated from a superconducting ground plane by an insulating layer to form a plurality of superconducting waveguides. The microvertex particle detector indicates passage of a charged subatomic particle by measuring a voltage pulse measured across a superconducting waveguide caused by the transition of the superconducting thin film strip from a superconducting to a non-superconducting state in response to the passage of a charged particle. A plurality of superconducting thin film strips in two orthogonal planes plus the slow electromagnetic wave propogating in a superconducting transmission line are used to resolve N.sup.2 ambiguity of charged particle events.

  19. Magnetically insulated transmission line oscillator

    DOE Patents [OSTI]

    Bacon, Larry D. (Albuquerque, NM); Ballard, William P. (Albuquerque, NM); Clark, M. Collins (Albuquerque, NM); Marder, Barry M. (Albuquerque, NM)

    1988-01-01

    A magnetically insulated transmission line oscillator employs self-generated magnetic fields to generate microwave energy. An anode of the oscillator includes slow-wave structures which are formed of a plurality of thin conductive vanes defining cavities therebetween, and a gap is formed between the anode and a cathode of the oscillator. In response to a pulsed voltage applied to the anode and cathode, self-generated magnetic fields arfe produced in a cross-field orientation with respect to the orientation of the electric field between the anode and the cathode. The cross-field magnetic fields insulate the flow of electrons in the gap and confine the flow of electrons within the gap.

  20. Gamma-Ray Burst Lines

    E-Print Network [OSTI]

    Michael S. Briggs

    1999-10-20

    The evidence for spectral features in gamma-ray bursts is summarized. As a guide for evaluating the evidence, the properties of gamma-ray detectors and the methods of analyzing gamma-ray spectra are reviewed. In the 1980's, observations indicated that absorption features below 100 keV were present in a large fraction of bright gamma-ray bursts. There were also reports of emission features around 400 keV. During the 1990's the situation has become much less clear. A small fraction of bursts observed with BATSE have statistically significant low-energy features, but the reality of the features is suspect because in several cases the data of the BATSE detectors appear to be inconsistent. Furthermore, most of the possible features appear in emission rather than the expected absorption. Analysis of data from other instruments has either not been finalized or has not detected lines.

  1. Microlensing induced absorption line variability

    E-Print Network [OSTI]

    Geraint F. Lewis; Rodrigo A. Ibata

    2002-12-02

    Gravitational microlensing has proven to be a powerful probe of both the structure at the heart of quasars and the mass function of compact objects in foreground lenses. This paper examines the potential of gravitational microlensing in probing the scale of structure in absorbing material within the lensing galaxy. We find that, in this high optical depth regime, significant variations in the equivalent width of absorption features can be induced, although the details of these are dependent upon the scale of structure of the absorbing material. The paper concludes with an examination of the absorption line variability observed in the gravitationally lensed quasar PKS1830-211, demonstrating how this may indicate the presence of small scale structure in the cold molecular gas present within the lensing galaxy.

  2. Superconducting transmission line particle detector

    DOE Patents [OSTI]

    Gray, K.E.

    1988-07-28

    A microvertex particle detector for use in a high energy physic collider including a plurality of parallel superconducting thin film strips separated from a superconducting ground plane by an insulating layer to form a plurality of superconducting waveguides. The microvertex particle detector indicates passage of a charged subatomic particle by measuring a voltage pulse measured across a superconducting waveguide caused by the transition of the superconducting thin film strip from a superconducting to a non- superconducting state in response to the passage of a charged particle. A plurality of superconducting thin film strips in two orthogonal planes plus the slow electromagnetic wave propagating in a superconducting transmission line are used to resolve N/sup 2/ ambiguity of charged particle events. 6 figs.

  3. Supplemental On-Line Materials Supplemental on line materials 1 of 12

    E-Print Network [OSTI]

    Bishop, James K.B.

    Supplemental On-Line Materials Supplemental on line materials 1 of 12 Robotic ObservationsX: Enhanced Carbon Biomass and Export at 55S Supplemental on line materials 2 of 12 Carbon Explorer / Patch to NZ B #12;Bishop et al. SOFeX: Enhanced Carbon Biomass and Export at 55S Supplemental on line

  4. Plan and Investment Notice JOHNS HOPKINS UNIVERSITY 403(B) PLAN & JOHNS HOPKINS UNIVERSITY INCOME DEFERRAL

    E-Print Network [OSTI]

    1 Plan and Investment Notice JOHNS HOPKINS UNIVERSITY 403(B) PLAN & JOHNS HOPKINS UNIVERSITY INCOME employer's plan which includes: · JOHNS HOPKINS UNIVERSITY 403(B) PLAN ­ Plan ID 103250 ·­ ­ Plan ID 103

  5. Guam Strategic Energy Plan

    SciTech Connect (OSTI)

    Conrad, M. D.

    2013-07-01

    Describes various energy strategies available to Guam to meet the territory's goal of diversifying fuel sources and reducing fossil energy consumption 20% by 2020.The information presented in this strategic energy plan will be used by the Guam Energy Task Force to develop an energy action plan. Available energy strategies include policy changes, education and outreach, reducing energy consumption at federal facilities, and expanding the use of a range of energy technologies, including buildings energy efficiency and conservation, renewable electricity production, and alternative transportation. The strategies are categorized based on the time required to implement them.

  6. Planning a Prescribed Burn 

    E-Print Network [OSTI]

    Hanselka, C. Wayne

    2009-04-01

    , the size of the burn, and its impact on wildlife habitat. If you burned using this plan, you would probably never burn rangeland again on purpose because of the risks taken and the potential for disappointing results. Effective planning well in advance...-leaved herbaceous plants other than grass, may look rank (vigorous) and dense enough to burn, but by midwinter they often have broken down. Woody debris and standing dead trees help little in spreading a fire. The grass fuel also needs to be ready at the right...

  7. Risk communications & emergency planning

    SciTech Connect (OSTI)

    Baranski, S.C. [EQUINOX Environmental, Inc., Shushan, NY (United States)

    1995-12-31

    This talk outlines the interface between good risk communication and emergency planning. The major topics include the following: What is risk communication and how is it applied to emergency planning; crisis communication and the need to know and how to integrate crisis communication and risk communication; the face of the emergency: spokespersons, public information; The Media`s role in emergency Public information and risk communication; Developing the risk communication message; How to respond to continuing need for 24 hours communications; the EAS and Risk communication and Crisis communication; and finally where is risk communication heading and how it can help.

  8. United States Conservation Plan

    E-Print Network [OSTI]

    Gray, Matthew

    United States Shorebird Conservation Plan M A N O M E T C E N T E R F O R C O N S E R V A T I O N T I O N #12;United States Shorebird Conservation Plan Council Organizations #12;1 U n i t e d S t a t e s S h o r e b i r d C o n s e r v a t i o n P l a n 2 0 0 1 The United States Shorebird

  9. Plutonium Vulnerability Management Plan

    SciTech Connect (OSTI)

    1995-03-01

    This Plutonium Vulnerability Management Plan describes the Department of Energy`s response to the vulnerabilities identified in the Plutonium Working Group Report which are a result of the cessation of nuclear weapons production. The responses contained in this document are only part of an overall, coordinated approach designed to enable the Department to accelerate conversion of all nuclear materials, including plutonium, to forms suitable for safe, interim storage. The overall actions being taken are discussed in detail in the Department`s Implementation Plan in response to the Defense Nuclear Facilities Safety Board (DNFSB) Recommendation 94-1. This is included as Attachment B.

  10. Performance expectation plan

    SciTech Connect (OSTI)

    Ray, P.E.

    1998-09-04

    This document outlines the significant accomplishments of fiscal year 1998 for the Tank Waste Remediation System (TWRS) Project Hanford Management Contract (PHMC) team. Opportunities for improvement to better meet some performance expectations have been identified. The PHMC has performed at an excellent level in administration of leadership, planning, and technical direction. The contractor has met and made notable improvement of attaining customer satisfaction in mission execution. This document includes the team`s recommendation that the PHMC TWRS Performance Expectation Plan evaluation rating for fiscal year 1998 be an Excellent.

  11. Construction plans jump; operations skid in 1996

    SciTech Connect (OSTI)

    True, W.R.

    1997-08-04

    Federally regulated oil and gas pipelines turned in mixed performances in 1996, a review of annual reports filed with the US Federal Energy Regulatory Commission (FERC) shows. Plans for new pipeline construction, filed with both the FERC and Canadian regulatory bodies, increased during a 12-month period ending June 30, 1997. Natural-gas pipeline operating companies increased their operating revenues but saw their incomes fall; oil pipelines saw both revenues and incomes fall sharply as deliveries were flat. Major natural-gas pipelines slightly increased the amounts of gas they moved for a fee and decreased gas sold out of their systems. In 1996, liquids pipelines moved fewer barrels than a year earlier and reduced in all categories the miles of line operated. Each year in this exclusive report, Oil and Gas Journal tracks revenues and incomes earned from operations along with volumes moved, as submitted to the FERC by US regulated interstate pipeline companies. Data are presented on the following: pipeline revenues, incomes--1996; North American pipeline-construction costs; US pipeline costs--estimated vs. actual; North American compressor construction costs; US compressor costs--estimated vs. actual; Canadian pipeline-construction costs, actual; US interstate mileage; investment in liquids pipelines; 10 years of land-construction costs; top 10 interstate liquids lines; top 10 interstate gas lines; liquids pipeline companies; and gas pipeline companies.

  12. Progress on the 140 KV, 10 Megawatt Peak, 1 Megawatt Average Polyphase Quasi-Resonant Bridge, Boost Converter/Modulator for the Spallation Neutron Source (SNS) Klystron Power System

    E-Print Network [OSTI]

    Reass, W A; Gribble, R F; Lynch, M T; Tallerico, P J; Reass, William A.; Doss, James D.; Gribble, Robert F.; Lynch, Michael T.; Tallerico, Paul J.

    2000-01-01

    This paper describes electrical design and operational characteristics of a zero-voltage-switching 20 kHz polyphase bridge, boost converter/modulator for klystron pulse application. The DC-DC converter derives the buss voltages from a standard 13.8 kV to 2300 Y substation cast-core transformer. Energy storage and filtering is provided by self-clearing metallized hazy polypropylene traction capacitors. Three "H-Bridge" IGBT switching networks are used to generate the polyphase 20 kHz transformers primary drive waveforms. The 20 kHz drive waveforms are chirped the appropriate duration to generate the desired klystron pulse width. PWM (pulse width modulation) of the individual 20 kHz pulses is utilized to provide regulated output waveforms with adaptive feedforward and feedback techniques. The boost transformer design utilizes amorphous nanocrystalline material that provides the required low core loss at design flux levels and switching frequencies. Resonant shunt peaking is used on the transformer secondary to ...

  13. CAMPO Mobility 2030 Plan 

    E-Print Network [OSTI]

    Capital Area Metropolitan Planning Organization

    2005-06-06

    lines; ? 1,014 additional lane miles of freeways, parkways, or toll ways, including completion of SH 45 (N), SH 45 (S), SH 130, and US 183 A and upgrades or improvements to IH-35, US 183 (N), US 183 (S), US 290 (E), US 290 (W), SH 71 (E), SH 71 (W...

  14. Site Maintenance Plan: Part 2, Site Maintenance Action Plan for FY 1994

    SciTech Connect (OSTI)

    Fisk, E.L.

    1994-06-01

    This Fiscal Year (FY) 1994 Site Maintenance Action Plan (SMAP) is Part II of the Site Maintenance Plan, and has been written by Westinghouse Hanford Company (WHC) to outline the requirements stated in DOE Order 4330.4B, Maintenance Management Program, Chapter 1, Paragraph 3.3.1. The SMAP provides an annual status of maintenance initiatives completed and planned, a summary of performance indicators, a summary of maintenance backlog, a listing of real property and capital equipment maintenance cost estimates that were used to create the FY 1996 infrastructure and maintenance budget input, and a listing of proposed line item and general plant projects. Additionally, assumptions for various Site programs are listed to bring the Site Maintenance Plan into focus with overall Site activities. The primary mission at Hanford is to clean up the Site. In this cleanup process WHC will provide scientific and technological expertise to meet global needs, and partnership with stakeholders in the region to develop regional economic diversification. Other missions at the Hanford Site include energy research and development, and waste management and disposal activities. Their primary mission has a 30-year projected life span and will direct the shutting down and cleanup of defense production facilities and the Fast Flux Test Facility. This long-term mission requires continuous maintenance and in many instances, replacement of existing basic infrastructure, support facilities, and utilities. Without adequate maintenance and capital funding these infrastructure, support facilities, and utilities will continue to deteriorate causing an increase in backlogged work.

  15. Professions Planning Guide

    E-Print Network [OSTI]

    Thomas, Andrew

    Health Professions Planning Guide 2015-2016 #12;Chapter 1 Applying to Medical School This section profession, health related community service leadership experience and a personal interview in which maturity professions school, but they are VERY important. Your grades reflect your ability to learn; to some extent

  16. Aerocapacitor commercialization plan

    SciTech Connect (OSTI)

    NONE

    1995-09-12

    The purpose of the Power-One Aerocapacitor Commercialization Plan is to communicate to members of management and to all employees the overall objectives of the corporation. Power-One, Inc., has participated in a US Federal Government Technology Reinvestment Project (TRP), entitled {open_quotes}Advanced Power Conversion based on the Aerocapacitor{close_quotes}: the project is a group effort, with Lawrence Livermore National Labs, GenCorp/Aerojet, PolyStor Corp. (a start-up company), and Power-One forming the consortium. The expected resulting technology is the {open_quotes}Aerocapacitor{close_quotes}, which possesses much higher performance levels than the usual capacitors on the market today. Power-One hopes to incorporate the Aerocapacitor into some of its products, hence enhancing their performance, as well as market privately-labeled aerocapacitors through its distribution channels. This document describes the details of Power-One`s plan to bring to market and commercialize the Aerocapacitor and Aerocapacitor-based products. This plan was formulated while Power-One was part of the Oerocap project. It has since pulled out of this project. What is presented in this plan is the work which was developed prior to the business decision to terminate this work.

  17. Plans, Implementation, and Results

    Broader source: Energy.gov [DOE]

    The Bioenergy Technologies Office carries out technology research, development, and deployment through an ongoing process of planning and analysis, implementation, and review. This Web page includes links to documents that support and document the program management process, and the results and public benefits that derive from it.

  18. Marketing Plan Company Description

    E-Print Network [OSTI]

    Dahl, David B.

    Marketing Plan Company Description: Consumer company that provides a product to helps boost Marketing Swat Team Project Description and Deliverables: The team will Identify the best online vehicles of promotions from YouTube celebs, co- marketing with related businesses, affiliate marketing, cross marketing

  19. PLANNING YOUR BIOCHEMISTRY AND

    E-Print Network [OSTI]

    Northern British Columbia, University of

    PLANNING YOUR BIOCHEMISTRY AND MOLECULAR BIOLOGY MAJOR #12;Outline · Course changes · New Pre in Biochemistry and Molecular Biology BCMB499-1-6 Independent Study BCMB430-6 Undergraduate Thesis #12;New pre-requisites · BCMB340-3 Physical Biochemistry (CHEM330) ­ Pre-requisites: PHYS 101 or PHYS 111, and CHEM 204

  20. PNNL Campus Master Plan

    SciTech Connect (OSTI)

    Mosey, Whitney LC

    2012-09-07

    The Plan is used as a guide for PNNL in making facility and infrastructure decisions essential to supporting the PNNL vision: to establish a modern, collaborative, flexible, and sustainable campus while optimizing the efficiency of operations in support of courageous discovery and innovation.

  1. TUBERCULOSIS EXPOSURE CONTROL PLAN

    E-Print Network [OSTI]

    Nicholson, Bruce J.

    Biosafety Committee, the Infection Policy and Education Committee or the Environmental Health and Safety and Education Committee and Environmental Health and Safety. June 2013: Summary of Document Changes The major Provided by: Environmental Health &Safety Department June 2013 #12;TB Exposure Control Plan Environmental

  2. Motion Planning ! Jana Kosecka!

    E-Print Network [OSTI]

    Kosecka, Jana

    ­ transform continuous space to discrete! · Roadmap methods! ­ Visibility graph! ­ Cell decomposition;6! Roadmap Methods! roadmap! Capture the connectivity of Cfree with a roadmap (graph or network) of one-dimensional curves! difficult! part! Roadmap Methods! Path Planning with a Roadmap! Input: configurations qinit

  3. Planning cogeneration systems

    SciTech Connect (OSTI)

    Limaye, D.

    1984-01-01

    Major factors and considerations in the planning and evaluation of cogeneration systems are explained here. Coverage is provided of prefeasibility assessment, technical and economic feasibility evaluation, computerized systems design, cogeneration technologies and applications, and non-conventional technologies. Also discussed are fuel availability and price trends, financing and risk management in cogeneration projects, and practical considerations in cogeneration implementation.

  4. FOOD SYSTEM PLANNING FOR

    E-Print Network [OSTI]

    Delaware, University of

    justice, conservation and renewable energy options, integrated resource planning, and technology with an overview of the efficiency and environmental benefits associated local food systems. The Center for Energy of Delaware Center for Energy & Environmental Policy University of Delaware February 2011 #12;Mailing Address

  5. Plan de Cooperacin Universitaria

    E-Print Network [OSTI]

    educación superior y la investigación para el desarrollo humano sostenible 14 Formación 15 Las universidadesPlan de Cooperación Universitaria para el Desarrollo 2011/2015 University Development Cooperation'educació superior i la recerca per al desenvolupament humà sostenible 14 Formació 15 Les universitats com

  6. Climate Change Scoping Plan

    E-Print Network [OSTI]

    Climate Change Scoping Plan a amework for change as approved Prepared by the California AirBackgroundBackgroundBackground ............................................................................................................................................................................................................................................................................................................................................................................................................ 4444 1. Climate Change Policy in California1. Climate Change Policy in California1. Climate Change Policy in California1. Climate Change Policy in California

  7. Climate Change Scoping Plan

    E-Print Network [OSTI]

    Climate Change Scoping Plan a amework for change Prepared by the California Air Resources BoardBackgroundBackgroundBackground ............................................................................................................................................................................................................................................................................................................................................................................................................ 4444 1. Climate Change Policy in California1. Climate Change Policy in California1. Climate Change Policy in California1. Climate Change Policy in California

  8. DEPARTMENT OF STRATEGIC PLAN

    E-Print Network [OSTI]

    Virginia Tech

    to effectively manage forest and allied natural resources. This revised strategic plan reiterates our commitment is to educate foresters and natural resource managers, and to discover and disseminate the knowledge needed has matured and grown and is now one of four departments in the College of Natural Resources

  9. Comprehensive facilities plan

    SciTech Connect (OSTI)

    1997-09-01

    The Ernest Orlando Lawrence Berkeley National Laboratory`s Comprehensive Facilities Plan (CFP) document provides analysis and policy guidance for the effective use and orderly future development of land and capital assets at the Berkeley Lab site. The CFP directly supports Berkeley Lab`s role as a multiprogram national laboratory operated by the University of California (UC) for the Department of Energy (DOE). The CFP is revised annually on Berkeley Lab`s Facilities Planning Website. Major revisions are consistent with DOE policy and review guidance. Facilities planing is motivated by the need to develop facilities for DOE programmatic needs; to maintain, replace and rehabilitate existing obsolete facilities; to identify sites for anticipated programmatic growth; and to establish a planning framework in recognition of site amenities and the surrounding community. The CFP presents a concise expression of the policy for the future physical development of the Laboratory, based upon anticipated operational needs of research programs and the environmental setting. It is a product of the ongoing planning processes and is a dynamic information source.

  10. Theoretical hot methane line lists up to T = 2000 K for astrophysical applications

    SciTech Connect (OSTI)

    Rey, M.; Tyuterev, Vl. G.; Nikitin, A. V.

    2014-07-01

    The paper describes the construction of complete sets of hot methane lines based on accurate ab initio potential and dipole moment surfaces and extensive first-principle calculations. Four line lists spanning the [0-5000] cm{sup –1} infrared region were built at T = 500, 1000, 1500, and 2000 K. For each of these four temperatures, we have constructed two versions of line lists: a version for high-resolution applications containing strong and medium lines and a full version appropriate for low-resolution opacity calculations. A comparison with available empirical databases is discussed in detail for both cold and hot bands giving a very good agreement for line positions, typically <0.1-0.5 cm{sup –1} and ?5% for intensities of strong lines. Together with numerical tests using various basis sets, this confirms the computational convergence of our results for the most important lines, which is the major issue for theoretical spectra predictions. We showed that transitions with lower state energies up to 14,000 cm{sup –1} could give significant contributions to the methane opacity and have to be systematically taken into account. Our list at 2000 K calculated up to J = 50 contains 11.5 billion transitions for I > 10{sup –29} cm mol{sup –1}. These new lists are expected to be quantitatively accurate with respect to the precision of available and currently planned observations of astrophysical objects with improved spectral resolution.

  11. Planning support systems for spatial planning through social learning

    E-Print Network [OSTI]

    Goodspeed, Robert (Robert Charles)

    2013-01-01

    This dissertation examines new professional practices in urban planning that utilize new types of spatial planning support systems (PSS) based on geographic information systems (GIS) software. Through a mixed-methods ...

  12. Architecture & Urban Planning College of Architecture & Urban Planning

    E-Print Network [OSTI]

    Cafarella, Michael J.

    &AB Junghans Wind and Architecture 33454 P LEC 005 T 330-630PM 2108 A&AB Kim Bioclimatic Bldg Enclosure Sys 506Architecture & Urban Planning College of Architecture & Urban Planning Architecture (ARCH) 201

  13. Abilene Metropolitan Area Metropolitan Transportation Plan 2010-2035 

    E-Print Network [OSTI]

    Abilene Metropolitan Planning Organization

    2010-01-12

    Lindley, former Abilene City Engineer MPO Staff (Non-Voting) Robert Allen, Abilene MPO Transportation Planning Director Dyess AFB SH 351 SH 351 FM 10 82 Jones County JonesCounty Jones County Jones County Jones County Te xt Jones County Jones... Area Urbanized Area Boundary county lines City Limits Freeways and Expressways Major Streets and Highways Railroad 0241Miles Tye Potosi Caps Dyess AFB Abilene Regional Airport Abilene ??? 20 ??? 20 ??? 20 Hamby State Prisons Lake Fort Phantom Hill...

  14. Single transmission line data acquisition system

    DOE Patents [OSTI]

    Fasching, George E. (Morgantown, WV)

    1984-01-01

    A single transmission line interrogated multiple channel data acquisition system is provided in which a plurality of remote station/sensors monitor specific process variables and transmit measurement values over the single transmission line to a master station when addressed by the master station. Power for all remote stations (up to 980) is provided by driving the line with constant voltage supplied from the master station and automatically maintained independent of the number of remote stations directly connected to the line. The transmission line can be an RG-62 coaxial cable with lengths up to about 10,000 feet with branches up to 500 feet. The remote stations can be attached randomly along the line. The remote stations can be scanned at rates up to 980 channels/second.

  15. Wilson Line Integrals in the Unparticle Action

    E-Print Network [OSTI]

    A. Lewis Licht

    2008-05-25

    We consider the unparticle action that is made gauge invariant by inclusion of an open Wilson line factor. In deriving vertexes from such an action it has been customary to use a form of differentiating the Wilson line originally proposed by Mandelstam. Using a simple example, we show that the Mandelstam derivative is mathematically inconsistent. We show that there are two ways to define differentiation of the Wilson line. The mathematically consistent method is to differentiate the explicit dependence of the line on the endpoint. The other method is a functional derivative and corresponds in a limiting case to the Mandelstam derivative. We also show that the only path that can be used in the Wilson line integral that leaves the unparticle action both Poincare and scale invariant is the straight line.

  16. CHEIBA Trust Employee Benefit Plan 2014 PlanYear

    E-Print Network [OSTI]

    CHEIBA Trust Employee Benefit Plan 2014 PlanYear Sponsored by - Colorado Higher Education Insurance 4 CHEIBA Trust Members #12;2013 EMPLOYEE BENEFIT INSURANCE PLAN CONTACTS Health Insurance Anthem ................................................................................................................................1-800-542-9402 Provider Directories for Health and Dental

  17. M-Planning: A Mobile Tool to Support Collaborative Planning 

    E-Print Network [OSTI]

    Lino, N; Tate, Austin

    This paper presents M-Planning, a mobile tool to support collaborative planning, and its conjunction use with the IX Process Panels. M-Planning works like an intelligent mobile panel for agents on the move. The tool permits agents’ interaction...

  18. Gamma-Ray Line Observations with RHESSI

    E-Print Network [OSTI]

    David M. Smith

    2004-04-30

    The Reuven Ramaty High Energy Solar Spectroscopic Imager (RHESSI) has been observing gamma-ray lines from the Sun and the Galaxy since its launch in February 2002. Here I summarize the status of RHESSI observations of solar lines (nuclear de-excitation, neutron capture, and positron annihilation), the lines of $^{26}$Al and $^{60}$Fe from the inner Galaxy, and the search for positron annihilation in novae.

  19. Comprehensive Plan 2020 Silsbee, Texas 

    E-Print Network [OSTI]

    Pugh, David; Ellis, David; Kindrick, Stephen; Adams, Gregory; Shannon, Van Zandt; Butorac, Marc; Estes, Brett; Patterson, J. Christopher; Phoopraset, Jaruret; Rogers, Scott; Schrank, David; Spooner-Mueller, Nancy; Stephenson, Amy; Ekroth, David; Pike, Amy; Pustejovsky, Kenneth; Ramos, Adam; Sung Rim, Chong; Smith, Ronald; Thompson, Blakeley; Waldrop, Sam; Wiethorn, Ronny; Willeke, Whitney; Zavala, Blanca; Ziolkowski, Rebecca

    1997-01-01

    Acquired data and analyzed in preparation for the comprehensive plan. Formulation of plan objectives was developed with a citizen survey, polling residents about their needs and desires for city growth and development. The ...

  20. Massachusetts Ocean Management Plan (Massachusetts)

    Broader source: Energy.gov [DOE]

    The Massachusetts Ocean Act of 2008 required the state’s Secretary of Energy and Environmental Affairs to develop a comprehensive ocean management plan for the state by the end of 2009. That plan...

  1. Continuous Improvement Plan Mechanical Engineering

    E-Print Network [OSTI]

    Fernandez, Eduardo

    Continuous Improvement Plan Mechanical Engineering Undergraduate Curriculum #12;Plan for the Assessment and Continuous Improvement of the Mechanical Engineering Undergraduate Curriculum Department of Ocean and Mechanical Engineering Florida Atlantic University April 4, 2001 (latest modification 3

  2. Celebrating the idea of planning

    E-Print Network [OSTI]

    Sanyal, Bishwapriya

    The Royal Town Planning Institute (RTPI) should be proud that it was one of the first organizations to introduce the idea that good cities require public planning by qualified professionals. It is not that no one had ...

  3. Northern Pass Transmission Line Project Environmental Impact...

    Broader source: Energy.gov (indexed) [DOE]

    the location of the September 26 public scoping meeting for the Northern Pass Transmission Line Project to Colebrook Elementary School, 27 Dumont Street, Colebrook, NH. On...

  4. Transmission Line Security Monitor: Final Report

    SciTech Connect (OSTI)

    John Svoboda

    2011-04-01

    The Electric Power Transmission Line Security Monitor System Operational Test is a project funded by the Technical Support Working Group (TSWG). TSWG operates under the Combating Terrorism Technical Support Office that functions under the Department of Defense. The Transmission Line Security Monitor System is based on technology developed by Idaho National Laboratory. The technology provides a means for real-time monitoring of physical threats and/or damage to electrical transmission line towers and conductors as well as providing operational parameters to transmission line operators to optimize transmission line operation. The end use is for monitoring long stretches of transmission lines that deliver electrical power from remote generating stations to cities and industry. These transmission lines are generally located in remote transmission line corridors where security infrastructure may not exist. Security and operational sensors in the sensor platform on the conductors take power from the transmission line and relay security and operational information to operations personnel hundreds of miles away without relying on existing infrastructure. Initiated on May 25, 2007, this project resulted in pre-production units tested in realistic operational environments during 2010. A technology licensee, Lindsey Manufacturing of Azusa California, is assisting in design, testing, and ultimately production. The platform was originally designed for a security monitoring mission, but it has been enhanced to include important operational features desired by electrical utilities.

  5. Detonator comprising a nonlinear transmission line

    DOE Patents [OSTI]

    Elizondo-Decanini, Juan M

    2014-12-30

    Detonators are described herein. In a general embodiment, the detonator includes a nonlinear transmission line that has a variable capacitance. Capacitance of the nonlinear transmission line is a function of voltage on the nonlinear transmission line. The nonlinear transmission line receives a voltage pulse from a voltage source and compresses the voltage pulse to generate a trigger signal. Compressing the voltage pulse includes increasing amplitude of the voltage pulse and decreasing length of the voltage pulse in time. An igniter receives the trigger signal and detonates an explosive responsive to receipt of the trigger signal.

  6. DOE Sustainability Reporting Open Line Help Call

    Broader source: Energy.gov [DOE]

    The Sustainability Performance Office (SPO) sponsors open line help calls to assist DOE sites and national laboratories with the annual sustainability reporting process. Representatives from the...

  7. Strategic Planning A PRACTICAL GUIDE FOR

    E-Print Network [OSTI]

    Brownstone, Rob

    Strategic Planning A PRACTICAL GUIDE FOR UNITS AND DEPARTMENTS #12;STRATEGIC PLANNING: A PRACTICAL GUIDE FOR UNITS AND DEPARTMENTS 1 Contents 1. What is strategic planning

  8. NERSC Strategic Plan Is Now Online

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    by the DOE Office of Advanced Scientific Computing Research as input for ASCR's long-term planning, the strategic plan discusses NERSC's mission, goals, science drivers, planned...

  9. STRATEGIC RESEARCH PLAN TABLE OF CONTENTS

    E-Print Network [OSTI]

    Kavanagh, Karen L.

    SFU STRATEGIC RESEARCH PLAN 2010-2015 #12;TABLE OF CONTENTS Introduction........................................................................................ 2 Major Objectives of the Strategic Research Plan (SRP.................................................................................................27 Impact of the Strategic Research Plan

  10. Roadmap from our Strategic Planning Sessions

    E-Print Network [OSTI]

    Motai, Yuichi

    Roadmap from our Strategic Planning Sessions Winter 2013 Developed #12;VCU School of Engineering Strategic Plan Development Methodology: Step 1: Logis1cs planning Dec 2012

  11. Space Conditioning Standing Technical Committee Strategic Plan...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Space Conditioning Standing Technical Committee Strategic Plan Space Conditioning Standing Technical Committee Strategic Plan This strategic plan document outlines the gaps,...

  12. Interconnection-Wide Transmission Planning Initiative: Topic...

    Office of Environmental Management (EM)

    A, Interconnection-Level Analysis and Planning Interconnection-Wide Transmission Planning Initiative: Topic A, Interconnection-Level Analysis and Planning A description of the...

  13. Plans and Reports | Department of Energy

    Office of Environmental Management (EM)

    Plans and Reports Plans and Reports The U.S. Department of Energy (DOE) Sustainability Performance Office (SPO) tracks, plans, and reports progress on sustainability metrics set by...

  14. Best Management Practice #1: Water Management Planning

    Office of Energy Efficiency and Renewable Energy (EERE)

    A successful water management program starts with developing a comprehensive water management plan. This plan should be included within existing facility operating plans.

  15. Planning The Home Landscape. 

    E-Print Network [OSTI]

    Welch, William C.

    1979-01-01

    more functional and attractive home landscapes by utilizing native plants. Plant Grouping. Plants are basically used as specimens, in lines, in groups or in masses. Each method creates a different effect. Most landscapes will use all four types... tures and edging materials are not only attractive but also reduce routine mainte nance. If possible, when selecting building materials for the landscape, repeat mate rials and colors already used on the home. Weathered wood, natural stains, concrete...

  16. CIPS Validation Data Plan

    SciTech Connect (OSTI)

    Nam Dinh

    2012-03-01

    This report documents analysis, findings and recommendations resulted from a task 'CIPS Validation Data Plan (VDP)' formulated as an POR4 activity in the CASL VUQ Focus Area (FA), to develop a Validation Data Plan (VDP) for Crud-Induced Power Shift (CIPS) challenge problem, and provide guidance for the CIPS VDP implementation. The main reason and motivation for this task to be carried at this time in the VUQ FA is to bring together (i) knowledge of modern view and capability in VUQ, (ii) knowledge of physical processes that govern the CIPS, and (iii) knowledge of codes, models, and data available, used, potentially accessible, and/or being developed in CASL for CIPS prediction, to devise a practical VDP that effectively supports the CASL's mission in CIPS applications.

  17. Guam Energy Action Plan

    SciTech Connect (OSTI)

    Conrad, M. D.; Ness, J. E.

    2013-07-01

    Describes the four near-term strategies selected by the Guam Energy Task Force during action planning workshops conducted in March 2013, and outlines the steps being taken to implement those strategies. Each strategy addresses one of the energy sectors identified in the earlier Guam strategic energy plan as being an essential component of diversifying Guam's fuel sources and reducing fossil energy consumption 20% by 2020. The four energy strategies selected are: (1) expanding public outreach on energy efficiency and conservation, (2) establishing a demand-side management revolving loan program, (3) exploring waste-to-energy options, and (4) influencing the transportation sector via anti-idling legislation, vehicle registration fees, and electric vehicles.

  18. STRATEGIC PLAN (Updated December 2009)

    E-Print Network [OSTI]

    Daume III, Hal

    STRATEGIC PLAN 2008­2013 May 2009 (Updated December 2009) #12; 2 CONTENTS I. Introduction: Graduate School Strategic Planning II. Graduate School Mission, Objectives, and Vision III. Advancing STRATEGIC PLANNING A. History The Graduate School of the University of Maryland was established in 1919

  19. Strategic Plan Atlantic Oceanographic and

    E-Print Network [OSTI]

    Strategic Plan Atlantic Oceanographic and Meteorological Laboratory FY2010-2015 www.aoml.noaa.gov U the Director Dr. Robert Atlas, AOML Director #12;This version of the AOML Strategic Plan was updated in March of this strategic plan, please contact AOML's Communications Office at 305-361-4451 or visit us on the web at www

  20. APPLIED TECHNOLOGY Strategic Plan Summary

    E-Print Network [OSTI]

    Heller, Barbara

    SCHOOL OF APPLIED TECHNOLOGY Strategic Plan Summary #12;School of Applied Technology Strategic Plan Summary | 1 SCHOOL OF APPLIED TECHNOLOGY STRATEGIC PLAN SUMMARY MISSION STATEMENT The mission Technology and Management program to achieve national visibility. #12;School of Applied Technology Strategic

  1. Strategic Plan Updated April 2014

    E-Print Network [OSTI]

    Strategic Plan 2013-16 Updated April 2014 www.cam.ac.uk/museums #12;University of Cambridge Museums Strategic Plan 2013-16 Foreword By Dr Jennifer Barnes, Pro-Vice-Chancellor (International Strategy), Chair Group, focusing on the particular contribution of University museums to the sector. UCM Strategic Plan

  2. Strategic Plan ATLANTIC OCEANOGRAPHIC AND

    E-Print Network [OSTI]

    Strategic Plan ATLANTIC OCEANOGRAPHIC AND METEOROLOGICAL LABORATORY ATLANTIC OCEANOGRAPHIC comments concerning this strategic plan and the future of our Laboratory. Sincerely yours, Kristina B of the Laboratory to have a clear vision of AOML, a context for interaction and a plan for the future. However

  3. STRATEGIC PLAN PROGRESS REPORT 2015

    E-Print Network [OSTI]

    Goldman, Robert D.

    A STRATEGIC PLAN PROGRESS REPORT 2015 NORTHWESTERN WILL #12;Dear members of the Northwestern on the University's progress in implementing the Northwestern Will strategic plan. As this report makes clear on cumulative progress in the key areas since the strategic plan commenced. This progress has been made possible

  4. STRATEGIC PLAN July 1, 2014

    E-Print Network [OSTI]

    Gustafsson, Torgny

    STRATEGIC PLAN July 1, 2014 INTRODUCTION Academic libraries are undergoing reinvention. Today present a strategic plan Mission Statement The Rutgers University Libraries support and enrich resource for the state and beyond. #12;Rutgers University Libraries Strategic Plan 2 that articulates our

  5. Strategic Planning MissionMission

    E-Print Network [OSTI]

    Arnold, Jonathan

    Strategic Planning 20102020 8 May 2009 1 #12;MissionMission The University of Georgia, a landgrant research universities in the worldworld. 3 #12;20002010 Strategic Plan2000 2010 Strategic Plan · Building, economic development, and technical assistance activities designed to address the strategic needs

  6. Clean Energy Business Plan Competition

    ScienceCinema (OSTI)

    Maxted, Sara Jane; Lojewski, Brandon; Scherson, Yaniv;

    2013-05-29

    Top Students Pitch Clean Energy Business Plans The six regional finalists of the National Clean Energy Business Plan Competition pitched their business plans to a panel of judges June 13 in Washington, D.C. The expert judges announced NuMat Technologies from Northwestern University as the grand prize winner.

  7. Building Emergency Plan Summer 2012

    E-Print Network [OSTI]

    Building Emergency Plan Project Summer 2012 #12;Building Emergency Plan Project We will be going over: · Introductions · What a Building Emergency Plan (BEP) is · The project and goals · Why? · Gives instructions and guidance to building tenants · Lets tenants know what to do in any emergency

  8. Clean Energy Business Plan Competition

    SciTech Connect (OSTI)

    Maxted, Sara Jane; Lojewski, Brandon; Scherson, Yaniv;

    2012-01-01

    Top Students Pitch Clean Energy Business Plans The six regional finalists of the National Clean Energy Business Plan Competition pitched their business plans to a panel of judges June 13 in Washington, D.C. The expert judges announced NuMat Technologies from Northwestern University as the grand prize winner.

  9. Energy Management and Conservation Plan

    E-Print Network [OSTI]

    Energy Management and Conservation Plan December 2005 #12;Texas Transportation Institute December 2005 Energy Management and Conservation Plan Page 2 of 24 Table of Contents Section One: Executive: Reporting Progress #12;Texas Transportation Institute December 2005 Energy Management and Conservation Plan

  10. 1997 U.S. Department of Energy Strategic Plan

    SciTech Connect (OSTI)

    None,

    1997-09-01

    With the end of the Cold War and the election of President Clinton, the Department of Energy (DOE) set a new course which began with the publication of its first departmental strategic plan in April 1994. Entitled ``Fueling a Competitive Economy, it provided the framework and shared vision for meeting responsibilities in energy, national security, environmental quality, and science and technology. The strategic plan was the guidepost for the formulation of the Department`s FY 1996, FY 1997, and FY 1998 budgets and was critical to the development of the Department`s Strategic Alignment Initiative, designed to save $1.7 billion over five years. This current plan, which has been significantly improved through a very close consultation process with Congress and customers stakeholders, takes DOE to the next important performance level by being more directly linked to actions and results. It defines a strategic goal for each of the Department`s four business lines and, in the spirit of the Government Performance and Results Act and the National Performance Review, identifies a fifth goal addressing corporate management. Reengineering the business practices, managing for results, being open with neighbors and stakeholders, and ensuring the safety and health of DOE workers and the public are, and will continue to be, among the highest of priorities. Over the coming years, DOE plans to achieve their strategic goals through specific identifiable strategies. Each business line has clear objectives and straightforward ways of defining whether DOE has succeeded in meeting those objectives.

  11. Future land use plan

    SciTech Connect (OSTI)

    NONE

    1995-08-31

    The US Department of Energy`s (DOE) changing mission, coupled with the need to apply appropriate cleanup standards for current and future environmental restoration, prompted the need for a process to determine preferred Future Land Uses for DOE-owned sites. DOE began the ``Future Land Use`` initiative in 1994 to ensure that its cleanup efforts reflect the surrounding communities` interests in future land use. This plan presents the results of a study of stakeholder-preferred future land uses for the Brookhaven National Laboratory (BNL), located in central Long Island, New York. The plan gives the Laboratory`s view of its future development over the next 20 years, as well as land uses preferred by the community were BNL ever to cease operations as a national laboratory (the post-BNL scenario). The plan provides an overview of the physical features of the site including its history, topography, geology/hydrogeology, biological inventory, floodplains, wetlands, climate, and atmosphere. Utility systems and current environmental operations are described including waste management, waste water treatment, hazardous waste management, refuse disposal and ground water management. To complement the physical descriptions of the site, demographics are discussed, including overviews of the surrounding areas, laboratory population, and economic and non-economic impacts.

  12. Project Management Plan

    SciTech Connect (OSTI)

    Not Available

    1988-01-01

    The mission of the Uranium Mill Tailings Remedial Action (UMTRA) Project is explicitly stated and directed in the Uranium Mill Tailings Radiation Control Act of 1978, Public Law 95-604, 42 USC 7901 (hereinafter referred to as the Act''). Title I of the Act authorizes the Department of Energy (DOE) to undertake remedial actions at 24 designated inactive uranium processing sites and associated vicinity properties containing uranium mill tailings and other residual radioactive materials derived from the processing sites. The Act, amended in January 1983, by Public Law 97-415, also authorizes DOE to perform remedial actions at vicinity properties in Edgemont, South Dakota. Cleanup of the Edgemont processing site is the responsibility of the Tennessee Valley Authority. This document describes the plan, organization, system, and methodologies used to manage the design, construction, and other activities required to clean up the designated sites and associated vicinity properties in accordance with the Act. The plan describes the objectives of the UMTRA Project, defines participants' roles and responsibilities, outlines the technical approach for accomplishing the objectives, and describes the planning and managerial controls to be used in integrating and performing the Project mission. 21 figs., 21 tabs.

  13. TRUPACT-1 implementation plan

    SciTech Connect (OSTI)

    Hurley, J.D.; Tappen, J.J. . Joint Integration Office); Christensen, D.S. )

    1985-09-01

    TRUPACT-1, the TRansUranic PACkage Transporter is a packaging designed to transport defense contact handled transuranic (CH-TRU) waste from generating and interim TRU waste storage facilities to the Waste Isolation Pilot Plant (WIPP). Prior to fabrication and procurement of a full fleet, an initial design (TRUPACT-1) will be introduced to the defense TRU waste complex through use in an operational prototype fleet which will consist of Units 1, 2, and 3. In an effort to provide a relatively smooth introduction of the TRUPACT-1, the TRUPACT Technical Team (TTT) has developed the following implementation plan. The plan provides detailed information on user handling opportunities, schedules, equipment, responsibilities, reporting and data collection activities to be performed. The intent of this document is to provide users of the TRUPACT-1 with a guidance document, complete with references, that will allow the smooth introduction of this new transportation system by providing the information necessary for collecting operational, performance and cost data. These data will be used in modeling and full fleet design and procurement activities. In addition, these data will help fine tune procedures in the inspection and maintenance document and the operational document. Additional objectives of this plan are to aid in the establishment of site operational, inspection and maintenance procedures as well as training of site operators and briefing state and local officials.

  14. Terahertz Quantum-Cascade Transmission-Line Metamaterials

    E-Print Network [OSTI]

    Tavallaee, Amir Ali

    2012-01-01

    Transmission-Line Metamaterials . . . . . . . Terahertz CRLHCRLH Transmission-Line Metamaterials . . . . . . . 112losses in negative-index metamaterials by optical parametric

  15. Planning for the Future: Climate Adaptation in Hazard Mitigation Plans and Comprehensive Water Resource Management Plans

    E-Print Network [OSTI]

    Bailey, Gregory

    This project investigated whether hazard mitigation plans (HMPs) and comprehensive water resource management plans (CWRMPs) completed by cities and towns in Massachusetts account for the long term effects of climate change. ...

  16. 2015 403(b) Plan Universal Availability Notice Florida Atlantic University ("FAU") sponsors Florida Atlantic University 403(b) Plan (the "Plan").

    E-Print Network [OSTI]

    Fernandez, Eduardo

    2015 403(b) Plan Universal Availability Notice Florida Atlantic University ("FAU") sponsors Florida Atlantic University 403(b) Plan (the "Plan"). Eligible employees of the University can voluntarily elect enroll in the FAU 403(b) Plan. Please see: http

  17. An after-market, five-port vertical beam line extension for the PETtrace

    SciTech Connect (OSTI)

    Barnhart, T. E.; Engle, J. W.; Severin, G. W.; Valdovinos, H. F.; Gagnon, K.; Nickles, R. J.

    2012-12-19

    Most commercial cyclotrons intended for medical isotope production provide a limited number of beam ports crowded into a minimal vault space. Taking advantage of our new lab construction, we planned and installed a beam-line on port Music-Sharp-Sign 2 of our GEMS PETtrace to bring beam to an additional 5 target positions. These are oriented in the vertical plane, with the downward directed beam well suited for molten target substrates.

  18. Unvented Drum Handling Plan

    SciTech Connect (OSTI)

    MCDONALD, K.M.

    2000-08-01

    This drum-handling plan proposes a method to deal with unvented transuranic drums encountered during retrieval of drums. Finding unvented drums during retrieval activities was expected, as identified in the Transuranic (TRU) Phase I Retrieval Plan (HNF-4781). However, significant numbers of unvented drums were not expected until excavation of buried drums began. This plan represents accelerated planning for management of unvented drums. A plan is proposed that manages unvented drums differently based on three categories. The first category of drums is any that visually appear to be pressurized. These will be vented immediately, using either the Hanford Fire Department Hazardous Materials (Haz. Mat.) team, if such are encountered before the facilities' capabilities are established, or using internal capabilities, once established. To date, no drums have been retrieved that showed signs of pressurization. The second category consists of drums that contain a minimal amount of Pu isotopes. This minimal amount is typically less than 1 gram of Pu, but may be waste-stream dependent. Drums in this category are assayed to determine if they are low-level waste (LLW). LLW drums are typically disposed of without venting. Any unvented drums that assay as TRU will be staged for a future venting campaign, using appropriate safety precautions in their handling. The third category of drums is those for which records show larger amounts of Pu isotopes (typically greater than or equal to 1 gram of Pu). These are assumed to be TRU and are not assayed at this point, but are staged for a future venting campaign. Any of these drums that do not have a visible venting device will be staged awaiting venting, and will be managed under appropriate controls, including covering the drums to protect from direct solar exposure, minimizing of container movement, and placement of a barrier to restrict vehicle access. There are a number of equipment options available to perform the venting. The preferred option is to use equipment provided by a commercial vendor during the first few years of retrieval and venting. This is based on a number of reasons. First, retrieval funding is uncertain. Using a commercial vendor will allow DOE-RL to avoid the investment and maintenance costs if retrieval is not funded. Second, when funding can be identified, retrieval will likely be performed with minimal initial throughput and intermittent operations. Again, costs can be saved by using contracted vendor services only as needed, rather than supporting Hanford equipment full time. When full-scale retrieval begins and the number of drums requiring venting increases significantly, then use of the Hanford container venting system (CVS) should be considered.

  19. Magnetic Field Line Stickiness in Tokamaks

    E-Print Network [OSTI]

    Martins, Caroline G L; Caldas, I L

    2013-01-01

    We present simulated figures of the diverted magnetic field lines of the tokamak ITER, obtained by numerically integrating a Hamiltonian model with electrical currents in five wire loops and control coils. We show evidences of a sticky island embedded in the chaotic region near the divertor plates, which traps magnetic field lines for many toroidal turns increasing their connection lengths to these plates.

  20. Line geometry and electromagnetism I: basic structures

    E-Print Network [OSTI]

    D. H. Delphenich

    2013-09-11

    Some key notions of line geometry are recalled, along with their application to mechanics. It is then shown that most of the basic structures that one introduces in the pre-metric formulation of electromagnetism can be interpreted directly in terms of corresponding concepts in line geometry. The results are summarized in a table.

  1. Cesium D Line Data Daniel Adam Steck

    E-Print Network [OSTI]

    Steck, Daniel A.

    Cesium D Line Data Daniel Adam Steck Oregon Center for Optics and Department of Physics, University 1998. This is revision 2.1.4, 23 December 2010. Cite this document as: Daniel A. Steck, "Cesium D Line and optical properties of cesium that are relevant to various quantum optics experiments. In particular, we

  2. Migrating Automotive Product Lines: a Case Study

    E-Print Network [OSTI]

    Cordy, James R.

    . Software Product Lines (SPL) are widely used to manage variability in the automotive industry. In a rapidly study from an automotive domain, that it is tractable to lift industrial-grade transforma- tionsMigrating Automotive Product Lines: a Case Study Michalis Famelis1 , Levi L´ucio2 , Gehan Selim3

  3. Doering 6/2004 Freezing Cell Lines

    E-Print Network [OSTI]

    Doering, Tamara

    Doering 6/2004 Freezing Cell Lines Overview: This is crucial for maintaining important cell lines in the lab!!! Please freeze down any strain you or others might use in the future, whether that is a crypto personnel won't spend time reconstructing plasmids or strains that weren't kept. Instructions for freezing

  4. Speed-line for 3D animation 

    E-Print Network [OSTI]

    Song, Won Chan

    2007-04-25

    My thesis describes a tool which creates speed-lines automatically in 3D computer animations. Speed-lines are usually used in comic books to express fast motions in a still image. They are also used in 2D animations. Although animations don't need...

  5. Small Businesses Save Big: A Borrower's Guide To Increase the Bottom Line Using Energy Efficiency (Fact Sheet)

    SciTech Connect (OSTI)

    Not Available

    2015-01-01

    Dollars saved through energy efficiency can directly impact your bottom line. Whether you are planning for a major renovation or upgrading individual pieces of building equipment, these improvements can help reduce operating costs, save on utility bills, and boost profits. This fact sheet provides a guide for small businesses to find the resources to increase the energy efficiency of their buildings.

  6. Broad iron lines in Active Galactic Nuclei

    E-Print Network [OSTI]

    A. C. Fabian; K. Iwasawa; C. S. Reynolds; A. J. Young

    2000-04-26

    An intrinsically narrow line emitted by an accretion disk around a black hole appears broadened and skewed as a result of the Doppler effect and gravitational redshift. The fluorescent iron line in the X-ray band at 6.4-6.9keV is the strongest such line and is seen in the X-ray spectrum of many active galactic nuclei and, in particular, Seyfert galaxies. It is an important diagnostic with which to study the geometry and other properties of the accretion flow very close to the central black hole. The broad iron line indicates the presence of a standard thin accretion disk in those objects, often seen at low inclination. The broad iron line has opened up strong gravitational effects around black holes to observational study with wide-reaching consequences for both astrophysics and physics.

  7. FY 1994 Annual Work Plan

    SciTech Connect (OSTI)

    Not Available

    1993-09-30

    In accordance with the Inspector General`s Strategic Planning Policy directive, the Office of Inspector General (OIG) annually updates its Strategic Plan with budgetary and program guidance for the next fiscal year. The program guidance identifies and establishes priorities for OIG coverage of important DOE issues and operations, provides the basis for assigning OIG resources, and is the source for issues covered in Assistant Inspectors General annual work plans. The Office of the Assistant Inspector General for Audits (AIGA) publishes an Annual Work Plan in September of each year. The plan includes the OIG program guidance and shows the commitment of resources necessary to accomplish the assigned work and meet our goals. The program guidance provides the framework within which the AIGA work will be planned and accomplished. Audits included in this plan are designed to help insure that the requirements of our stakeholders have been considered and blended into a well balanced audit program.

  8. NIF Title III engineering plan

    SciTech Connect (OSTI)

    Deis, G

    1998-06-01

    The purpose of this document is to define the work that must be accomplished by the NIF Project during Title III Engineering. This definition is intended to be sufficiently detailed to provide a framework for yearly planning, to clearly identify the specific deliverables so that the Project teams can focus on them, and to provide a common set of objectives and processes across the Project. This plan has been preceded by similar documents for Title I and Title II design and complements the Site Management Plan, the Project Control Manual, the Quality Assurance Program Plan, the RM Parsons NIF Title III Configuration Control Plan, the Integrated Project Schedule, the Preliminary Safety Analysis Report, the Configuration Management Plan, and the Transition Plan.

  9. Ten Year Site Plans | Department of Energy

    Energy Savers [EERE]

    Ten Year Site Plans Ten Year Site Plans A Ten Year Site Plan (TYSP) is the essential planning document linking a site's real property requirements to its mission in support of the...

  10. Work Plan FY 2015 | Department of Energy

    Energy Savers [EERE]

    Work Plan FY 2015 Work Plan FY 2015 Planned Audits and Inspections for FY 2015 A list of audits and inspections planned for FY 2015 by the U.S. Department of Energy, Office of...

  11. Through the Looking Glass: Off-Line Versus On-Line Coverage of Planar Environments by

    E-Print Network [OSTI]

    Rimon, Elon

    is demonstrated. Due to its many applications, on-line coverage is a highly researched topic in the mobile robotThrough the Looking Glass: Off-Line Versus On-Line Coverage of Planar Environments by a Battery Powered Autonomous Mobile Robot Iddo Shnaps and Elon Rimon Dept. of ME, Technion, Israel Institute

  12. A Heritage Development Plan for Nacogdoches 

    E-Print Network [OSTI]

    Ellis, David R.

    1998-01-01

    This innovative plan examined historical resources in the community and developed a plan to optimize assets and strengthen weaknesses.

  13. Environmental Management System Plan

    SciTech Connect (OSTI)

    Fox, Robert; Thorson, Patrick; Horst, Blair; Speros, John; Rothermich, Nancy; Hatayama, Howard

    2009-03-24

    Executive Order 13423, Strengthening Federal Environmental, Energy, and Transportation Management establishes the policy that Federal agencies conduct their environmental, transportation, and energy-related activities in a manner that is environmentally, economically and fiscally sound, integrated, continually improving, efficient, and sustainable. The Department of Energy (DOE) has approved DOE Order 450.1A, Environmental Protection Program and DOE Order 430.2B, Departmental Energy, Renewable Energy and Transportation Management as the means of achieving the provisions of this Executive Order. DOE Order 450.1A mandates the development of Environmental Management Systems (EMS) to implement sustainable environmental stewardship practices that: (1) Protect the air, water, land, and other natural and cultural resources potentially impacted by facility operations; (2) Meet or exceed applicable environmental, public health, and resource protection laws and regulations; and (3) Implement cost-effective business practices. In addition, the DOE Order 450.1A mandates that the EMS must be integrated with a facility's Integrated Safety Management System (ISMS) established pursuant to DOE P 450.4, 'Safety Management System Policy'. DOE Order 430.2B mandates an energy management program that considers energy use and renewable energy, water, new and renovated buildings, and vehicle fleet activities. The Order incorporates the provisions of the Energy Policy Act of 2005 and Energy Independence and Security Act of 2007. The Order also includes the DOE's Transformational Energy Action Management initiative, which assures compliance is achieved through an Executable Plan that is prepared and updated annually by Lawrence Berkeley National Laboratory (LBNL, Berkeley Lab, or the Laboratory) and then approved by the DOE Berkeley Site Office. At the time of this revision to the EMS plan, the 'FY2009 LBNL Sustainability Executable Plan' represented the most current Executable Plan. These DOE Orders and associated policies establish goals and sustainable stewardship practices that are protective of environmental, natural, and cultural resources, and take a life cycle approach that considers aspects such as: (1) Acquisition and use of environmentally preferable products; (2) Electronics stewardship; (3) Energy conservation, energy efficiency, and renewable energy; (4) Pollution prevention, with emphasis on toxic and hazardous chemical and material reduction; (5) Procurement of efficient energy and water consuming materials and equipment; (6) Recycling and reuse; (7) Sustainable and high-performance building design; (8) Transportation and fleet management; and (9) Water conservation. LBNL's approach to sustainable environmental stewardship required under Order 450.1A poses the challenge of implementing its EMS in a compliance-based, performance-based, and cost-effective manner. In other words, the EMS must deliver real and tangible business value at a minimal cost. The purpose of this plan is to describe Berkeley Lab's approach for achieving such an EMS, including an overview of the roles and responsibilities of key Laboratory parties. This approach begins with a broad-based environmental policy consistent with that stated in Chapter 11 of the LBNL Health and Safety Manual (PUB-3000). This policy states that Berkeley Lab is committed to the following: (1) Complying with applicable environmental, public health, and resource conservation laws and regulations. (2) Preventing pollution, minimizing waste, and conserving natural resources. (3) Correcting environmental hazards and cleaning up existing environmental problems, and (4) Continually improving the Laboratory's environmental performance while maintaining operational capability and sustaining the overall mission of the Laboratory. A continual cycle of planning, implementing, evaluating, and improving processes will be performed to achieve goals, objectives, and targets that will help LBNL carry out this policy. Each year, environmental aspects will be identified and their impacts to the environm

  14. ESnet Program Plan 1994

    SciTech Connect (OSTI)

    Merola, S.

    1994-11-01

    This Program Plan characterizes ESnet with respect to the current and future needs of Energy Research programs for network infrastructure, services, and development. In doing so, this document articulates the vision and recommendations of the ESnet Steering Committee regarding ESnet`s development and its support of computer networking facilities and associated user services. To afford the reader a perspective from which to evaluate the ever-increasing utility of networking to the Energy Research community, we have also provided a historical overview of Energy Research networking. Networking has become an integral part of the work of DOE principal investigators, and this document is intended to assist the Office of Scientific Computing in ESnet program planning and management, including prioritization and funding. In particular, we identify the new directions that ESnet`s development and implementation will take over the course of the next several years. Our basic goal is to ensure that the networking requirements of the respective scientific programs within Energy Research are addressed fairly. The proliferation of regional networks and additional network-related initiatives by other Federal agencies is changing the process by which we plan our own efforts to serve the DOE community. ESnet provides the Energy Research community with access to many other peer-level networks and to a multitude of other interconnected network facilities. ESnet`s connectivity and relationship to these other networks and facilities are also described in this document. Major Office of Energy Research programs are managed and coordinated by the Office of Basic Energy Sciences, the Office of High Energy and Nuclear Physics, the Office of Magnetic Fusion Energy, the Office of Scientific Computing, and the Office of Health and Environmental Research. Summaries of these programs are presented, along with their functional and technical requirements for wide-area networking.

  15. Navy Geothermal Plan

    SciTech Connect (OSTI)

    Not Available

    1984-12-01

    Domestic geothermal resources with the potential for decreasing fossil fuel use and energy cost exist at a significant number of Navy facilities. The Geothermal Plan is part of the Navy Energy R and D Program that will evaluate Navy sites and provide a technical, economic, and environmental base for subsequent resource use. One purpose of the program will be to provide for the transition of R and D funded exploratory efforts into the resource development phase. Individual Navy geothermal site projects are described as well as the organizational structure and Navy decision network. 2 figs.

  16. Integrated rural energy planning

    SciTech Connect (OSTI)

    El Mahgary, Y.; Biswas, A.K.

    1985-01-01

    This book presents papers on integrated community energy systems in developing countries. Topics considered include an integrated rural energy system in Sri Lanka, rural energy systems in Indonesia, integrated rural food-energy systems and technology diffusion in India, bringing energy to the rural sector in the Philippines, the development of a new energy village in China, the Niaga Wolof experimental rural energy center, designing a model rural energy system for Nigeria, the Basaisa village integrated field project, a rural energy project in Tanzania, rural energy development in Columbia, and guidelines for the planning, development and operation of integrated rural energy projects.

  17. Community Relations Plan

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantityBonneville Power Administration would like submit the following comments responseScienceCommunity Relations Plan Community

  18. Tax-Advantaged Plans

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity ofkandz-cm11 Outreach Home RoomPreservationBio-Inspired Solar Fuel ProductionRecoverable User GuideTax-Advantaged Plans

  19. ARM - Lesson Plans

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity ofkandz-cm11 Comments?govInstrumentsnoaacrnBarrow, Alaska Outreach Home Room News Publications TraditionalPlans Outreach Home

  20. Planning a visit?

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantityBonneville Power Administration wouldMass mapSpeeding access| DepartmentPeerFederal FleetUpSmall Wind Electric System Planning