Sample records for kv line planned

  1. Quality Assurance Plan for site electrical replacements at substation line item subproject: 69 KV Substation

    SciTech Connect (OSTI)

    Ohler, C.K.

    1991-05-21T23:59:59.000Z

    The 69 KV Substation Project is based on the recognized need to provide a continuous, reliable source of power and to improve the firm capacity of the electrical service to all production facilities at Mound. The project consists of the following major element: 69 KV Substation: (1) Install a 69 KV Substation and associated equipment with two parallel 18 MVA transformers. (2) Install duct bank as required and provide 15 KV feeder cable from new substation to existing Substation 95 for connection to Mound`s existing primary distribution system. (3) Install duct bank for underground routing of the 15 KV feeder cable from Manhole 5C to the existing power house cable pit. (4) Reconfigure existing Dayton Power and Light Co. 15 KV switchgear in P Building. The purpose of this Quality Assurance Plan (QA Plan) is to assure that the objectives of the United States Department of Energy (D.O.E.) and EG&G Mound Applied Technologies, Miamisburg, Ohio (Mound) are met for this non-weapons project relative to health and safety, protection of the environment, reliability and continuity of operations, and documentation of quality efforts. This QA Plan identifies the activities and responsibilities which are necessary in the design, procurement, fabrication, installation, and start up of this project in order to meet these objectives.

  2. EA-1665: Davis-Kingman 69-kV Transmission Line Rebuild Project, Arizona

    Broader source: Energy.gov [DOE]

    Western plans to rebuild a 26.6-mile-long portion of the existing 27.3-mile-long Davis–Kingman Tap 69-kV Transmission Line within the existing ROW in order to improve the reliability of the transmission service.

  3. Corona performance of a compact 230-kV line

    SciTech Connect (OSTI)

    Chartier, V.L.; Blair, D.E. [Bonneville Power Administration, Vancouver, WA (United States). Division of Laboratories; Easley, M.D.; Raczkowski, R.T. [Puget Sound Power and Light Co., Bellevue, WA (United States)

    1994-12-31T23:59:59.000Z

    Permitting requirements and the acquisition of new rights-of-way for transmission facilities has in recent years become increasingly difficult for most utilities, including Puget Sound Power and Light Company. In order to maintain a high degree of reliability of service while being responsive to public concerns regarding the siting of high voltage (HV) transmission facilities, Puget Power has found it necessary to more heavily rely upon the use of compact lines in franchise corridors. Compaction does, however, precipitant increased levels of audible noise (AN) and radio and TV interference (RI and TVI) due to corona on the conductors and insulator assemblies. Puget Power relies upon the Bonneville Power Administration (BPA) Corona and Field Effects computer program to calculate AN and RI for new lines. Since there was some question of the program`s ability to accurately represent quiet 230-kV compact designs, a joint project was undertaken with BPA to verify the program`s algorithms. Long-term measurements made on an operating Puget Power 230-kV compact line confirmed the accuracy of BPA`s AN model; however, the RI measurements were much lower than predicted by the BPA computer and other programs. This paper also describes how the BPA computer program can be used to calculate the voltage needed to expose insulator assemblies to the correct electric field in single test setups in HV laboratories.

  4. Corona performance of a compact 230-kV line

    SciTech Connect (OSTI)

    Chartier, V.L.; Blair, D.E. [Bonneville Power Administration, Vancouver, WA (United States). Division of Labs.] [Bonneville Power Administration, Vancouver, WA (United States). Division of Labs.; Easley, M.D.; Raczkowski, R.T. [Puget Sound Power and Light Co., Bellevue, WA (United States)] [Puget Sound Power and Light Co., Bellevue, WA (United States)

    1995-01-01T23:59:59.000Z

    Permitting requirements and the acquisition of new rights-of-way for transmission facilities has in recent years become increasingly difficult for most utilities, including Puget Sound Power and Light Company. In order to maintain a high degree of reliability of service while being responsive to public concerns regarding the siting of high voltage (HV) transmission facilities, Puget Power has found it necessary to more heavily rely upon the use of compact lines in franchise corridors. Compaction does, however, precipitate increased levels of audible noise (AN) and radio and TV interference (RI and TVI) due to corona on the conductors and insulator assemblies. Puget Power relies upon the Bonneville Power Administration (BPA) Corona and Field Effects computer program to calculate AN and RI for new lines. Since there was some question of the program`s ability to accurately represent quiet 230-kV compact designs, a joint project was undertaken with BPA to verify the program`s algorithms. Long-term measurements made on an operating Puget Power 230-kV compact line confirmed the accuracy of BPA`s AN model; however, the RI measurements were much lower than predicted by the BPA and other programs. This paper also describes how the BPA computer program can be used to calculate the voltage needed to expose insulator assemblies to the correct electric field in single test setups in HV laboratories.

  5. Wild Horse 69-kV transmission line environmental assessment

    SciTech Connect (OSTI)

    NONE

    1996-12-01T23:59:59.000Z

    Hill County Electric Cooperative Inc. (Hill County) proposes to construct and operate a 69-kV transmission line from its North Gildford Substation in Montana north to the Canadian border. A vicinity project area map is enclosed as a figure. TransCanada Power Corporation (TCP), a Canadian power-marketing company, will own and construct the connecting 69-kV line from the international border to Express Pipeline`s pump station at Wild Horse, Alberta. This Environmental Assessment is prepared for the Department of Energy (DOE) as lead federal agency to comply with the requirements of the National Environmental Policy Act (NEPA), as part of DOE`s review and approval process of the applications filed by Hill County for a DOE Presidential Permit and License to Export Electricity to a foreign country. The purpose of the proposed line is to supply electric energy to a crude oil pump station in Canada, owned by Express Pipeline Ltd. (Express). The pipeline would transport Canadian-produced oil from Hardisty, Alberta, Canada, to Caster, Wyoming. The Express Pipeline is scheduled to be constructed in 1996--97 and will supply crude oil to refineries in Wyoming and the midwest.

  6. Oracle-Saguaro 115-kV Transmission Line Routine Maintenance Project...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Oracle-Saguaro 115-kV Transmission Line Routine Maintenance Project, Mile 6 to Oracle Substation Categorical Exclusion Continuation Sheet Project Description Maintenance work at...

  7. EIS-0344: Grand Coulee-Bell 500 kV Transmission Line

    Broader source: Energy.gov [DOE]

    This EIS analyzes DOE's proposed action for the construction and operation of the proposed Grand Coulee-Bell 500-kV Transmission Line Project.

  8. Survey of Magnetic Fields Near BPA 230-kV and 500-kV Transmission Lines.

    SciTech Connect (OSTI)

    Perrin, Nancy; Aggarwal, Rajinder Pal; Bracken, T. Daniel

    1991-05-20T23:59:59.000Z

    The purpose of this study was to characterize typical levels and variability of 60Hz magnetic fields at the centerline and edge of right-of-way of Bonneville Power Administration (BPA) 230-kV and 500-kV transmission lines. This was accomplished by taking magnetic field measurements at over 800 spans in Oregon and Washington. The spans were sampled using a stratified random sampling procedure with region (East vs. West), voltage (230-kV vs 500-kV), and circuit configuration as strata. There were five different circuit configuration groups for each region/voltage category requiring a total of 200 strata. Magnetic field measurements were taken at 13 locations under each span using an EMDEX-C as a survey meter. Additional information recorded for each span included conductor height (at 10 locations), right-of-way width, longitudinal and lateral slope, time of day, vegetation, terrain, weather conditions, temperature, wind speed, span length and presence of other lines in the corridor. 9 refs., 17 figs., 26 tabs.

  9. Marys Lake 69/115-kV transmission line upgrade and substation expansion projects

    SciTech Connect (OSTI)

    NONE

    1996-05-01T23:59:59.000Z

    Western Area Power Administration (Western) and the Platte River Power Authority (Platte River) propose to upgrade portions of the existing electric transmission and substation system that serves the Town of Estes Park, Colorado. The existing transmission lines between the Estes Power Plant Switchyard and the Marys Lake Substation include a 115,000 volt (115-kV) line and 69,000 volt (69-kV) line. Approximately one mile is a double-circuit 115/69-kV line on steel lattice structures, and approximately two miles consists of separate single-circuit 115-kV and a 69-kV lines, constructed on wood H-Frame structures. Both lines were constructed in 1951 by the US Bureau of Reclamation. The existing transmission lines are on rights-of-way (ROW) that vary from 75 feet to 120 feet and are owned by Western. There are 48 landowners adjacent to the existing ROW. All of the houses were built adjacent to the existing ROW after the transmission lines were constructed. Upgrading the existing 69-kV transmission line between the Marys Lake Substation and the Estes Power Plant Switchyard to 115-kV and expanding the Marys Lake Substation was identified as the most effective way in which to improve electric service to Estes Park. The primary purpose and need of the proposed project is to improve the reliability of electric service to the Town of Estes Park. Lack of reliability has been a historical concern, and reliability will always be less than desired until physical improvements are made to the electrical facilities serving Estes Park.

  10. EA-2007: Groton-Ordway 115-kV Transmission Line, Groton, South Dakota

    Broader source: Energy.gov [DOE]

    DOE’s Western Area Power Administration (Upper Great Plains Region) is preparing an EA that assesses the potential environmental impacts of a proposal to construct a new 115-kV transmission line that would connect Western’s existing Groton and Ordway Substations near Groton, South Dakota.

  11. EIS-0107: Mead-Phoenix +500-kV Direct Current Transmission Line

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy’s Western Area Power Administration (WAPA) prepared this statement to analyze the potential environmental and socioeconomic impacts arising from WAPA and regional project sponsors’ proposal to construct a 500 kilovolt (kV) alternating current (AC) transmission line with the capability to be upgraded later to 500kV direct current (DC), connecting the Westwing Substation, located north of Phoenix, Arizona, with a new McCullough II Substation, located approximately 14 miles west of Boulder City, Nevada. This statement modifies a previously prepared federal statement from which the participants' election to proceed had not occurred at the time this statement was prepared.

  12. Sidney-North Yuma 230-kV Transmission Line Project, Colorado and Nebraska

    SciTech Connect (OSTI)

    Not Available

    1991-06-01T23:59:59.000Z

    This report describes the need for a 230-kV overhead transmission line to supply power from Sidney, Nebraska to eastern Colorado. The alternative scenario compared to construction of the line is No Action. Rejected alternatives include underground lines and different routing paths, with a possible extension to the Sterling area. Both scenarios are evaluated for environmental effects, cost, and consequences for the eastern Colorado region. The proposed route is determined to be the environmentally preferred choice. 120 refs., 6 figs., 13 tabs. (MHB)

  13. EIS-0365: Imperial-Mexicali 230-kV Transmission Lines

    Broader source: Energy.gov [DOE]

    On February 27, 2001, Baja California Power, Inc. (hereafter referred to as Intergen), InterGen Aztec Energy, V.B.V., filed an application with DOE, Office of Fossil Energy, for a Presidential permit that would allow construction and connection of a double-circuit, 230-kV transmission line extending from the Imperial Valley Substation in California for a distance of about 6 mi (10 km) to a point west of Calexico at the U.S.-Mexico border.

  14. EIS-0505: Vantage to Pomona Heights 230 kV Transmission Line Project, Yakima, Grant, Benton and Kittitas Counties, Washington

    Broader source: Energy.gov [DOE]

    The Bureau of Land Management is preparing, with DOE’s Bonneville Power Administration (BPA) as a cooperating agency, an EIS that evaluates the potential environmental impacts of a proposal to construct a 60- to 67-mile long 230-kV transmission line. BPA’s proposed action is to interconnect the transmission line to an existing BPA substation.

  15. Seasonal Patterns of Melatonin, Cortisol, and Progesterone Secretion in Female Lambs Raised Beneath a 500-kV Transmission Line.

    SciTech Connect (OSTI)

    Lee, Jack M.

    1992-06-01T23:59:59.000Z

    Although several kinds of biological effects of electric and magnetic fields have been reported from laboratory studies, few have been independently replicated. When this study was being planned, the suppression of nighttime melatonin in rodents was thought to represent one of the strongest known effects of these fields. The effect had been replicated by a single laboratory for 60-Hz electric fields, and by multiple laboratories for d-c magnetic fields. The primary objective of this study was to determine whether the effect of electric and magnetic fields on melatonin would also occur in sheep exposed to a high voltage transmission line. The specific hypothesis tested by this experiment was as follows: The electrical environment produced by a 60-Hz, 500-kV transmission line causes a depression in nocturnal melatonin in chronically exposed female lambs. This may mimic effects of pinealectomy or constant long-day photoperiods, thus delaying the onset of reproductive cycles. Results of the study do not provide evidence to support the hypothesis. Melatonin concentrations in the sheep exposed to the transmission line showed the normal pattern of low daytime and high nighttime serum levels. As compared to the control group, there were no statistically significant group differences in the mean amplitude, phase, or duration of the nighttime melatonin elevation.

  16. EA-1679: Grand Coulee's Third Powerplant 500-kV Transmission Line Replacement Project, Grant and Okanogon Counties, Washington

    Broader source: Energy.gov [DOE]

    This EA evaluates potential environmental impacts from the construction and operation of six new 500-kV overhead transmission lines to replace six existing underground lines at Grand Coulee Dam. DOE’s Bonneville Power Administration (BPA), a cooperating agency, was asked by the U. S. Department of the Interior’s Bureau of Reclamation to design and construct the proposed new transmission lines. A Finding of No Significant Impact was issued by BPA in December 2011.

  17. Environmental Assessment of the Gering-Stegall 115-kV Transmission Line Consolidation Project, Scotts Bluff County, Nebraska

    SciTech Connect (OSTI)

    NONE

    1995-05-01T23:59:59.000Z

    The Department of Energy (DOE), Western Area Power Administration (Western) proposes to consolidate segments of two transmission lines near the Gering Substation in Gering, Nebraska. The transmission lines are both located in Scotts Bluff County, Nebraska. The transmission lines are both located in Scotts Bluff County, Nebraska, within the city of Gering. Presently, there are three parallel 115-kilovolt (kV) transmission lines on separate rights-of-way (ROW) that terminate at the Gering Substation. The project would include dismantling the Archer-Gering wood-pole transmission line and rebuilding the remaining two lines on single-pole steel double circuit structures. The project would consolidate the Gering-Stegall North and Gering-Stegall South 115-kV transmission lines on to one ROW for a 1.33-mile segment between the Gering Substation and a point west of the Gering Landfill. All existing wood-pole H-frame structures would be removed, and the Gering-Stegall North and South ROWs abandoned. Western is responsible for the design, construction, operation, and maintenance of the line. Western prepared an environmental assessment (EA) that analyzed the potential environmental impacts of the proposed construction, operation, and maintenance of the 115-kV transmission line consolidation. Based on the analyses in the EA, the DOE finds that the proposed action is not a major Federal action significantly affecting the quality of the human environment, within the meaning of the National Environmental Policy Act of 1969 (NEPA).

  18. Big George to Carter Mountain 115-kV transmission line project, Park and Hot Springs Counties, Wyoming. Environmental Assessment

    SciTech Connect (OSTI)

    Not Available

    1994-02-01T23:59:59.000Z

    The Western Area Power Administration (Western) is proposing to rebuild, operate, and maintain a 115-kilovolt (kV) transmission line between the Big George and Carter Mountain Substations in northwest Wyoming (Park and Hot Springs Counties). This environmental assessment (EA) was prepared in compliance with the National Environmental Policy Act (NEPA) and the regulations of the Council on Environmental Quality (CEQ) and the Department of Energy (DOE). The existing Big George to Carter Mountain 69-kV transmission line was constructed in 1941 by the US Department of Interior, Bureau of Reclamation, with 1/0 copper conductor on wood-pole H-frame structures without an overhead ground wire. The line should be replaced because of the deteriorated condition of the wood-pole H-frame structures. Because the line lacks an overhead ground wire, it is subject to numerous outages caused by lightning. The line will be 54 years old in 1995, which is the target date for line replacement. The normal service life of a wood-pole line is 45 years. Under the No Action Alternative, no new transmission lines would be built in the project area. The existing 69-kV transmission line would continue to operate with routine maintenance, with no provisions made for replacement.

  19. EIS-0025: Miles City-New Underwood 230-kV Electrical Transmission Line, Montana, North Dakota, and South Dakota

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy’s Western Area Power Administration prepared this statement to assess the environmental and socioeconomic implications of its proposed action to construct a 3.28-mile, 230-kV transmission line between Miles City and Baker, Montana , Hettinger, North Dakota , and New Underwood , South Dakota , in Custer and Fallon Counties in Montana, Adams , Bowman , and Slope Counties in North Dakota and Meade, Pennington, and Perkins Counties in South Dakota.

  20. EIS-0005-FS: Bonneville Power Administration Proposed FY 1979 Program, Facility Location on Supplement, Southwest Oregon Area Service, Buckley-Summer Lake 500 kV Line, Supplemental

    Broader source: Energy.gov [DOE]

    This Bonneville Power Administration document assesses the environmental impacts of constructing transmission facilities, which will coordinate with the Midpoint-Malin 500-kV line to be constructed by the Pacific Power and Light (PP&L) Company. The proposed action includes the construction of the 1.56-mile Buckley-Summer Lake 500-kV transmission line; the proposed Buckley Substation near Maupin, Oregon; and the proposed Summer Lake Substation near Silver Lake, Oregon.

  1. Retirement Planning TimeLine MPSERS Retirement Plan Participant

    E-Print Network [OSTI]

    early in your career! Your MPSERS retirement pension is based on your best 3 years (MIP plan) or 5 years- it is never too early to plan for your retirement! · Know what plan you are in - MIP or Basic. · Review your1 Retirement Planning TimeLine MPSERS Retirement Plan Participant Retirement planning is essential

  2. Increasing the reliability of the shutdown of 500 - 750-kV overhead lines equipped with shunt reactors in an unsuccessful three-phase automatic repeated closure cycle

    SciTech Connect (OSTI)

    Kuz'micheva, K. I.; Merzlyakov, A. S.; Fokin, G. G. [JSC 'R and D Center at Federal Grid Company of the United Power System' (Russian Federation)

    2013-05-15T23:59:59.000Z

    The reasons for circuit-breaker failures during repeated disconnection of 500 - 750 kV overhead lines with shunt reactors in a cycle of unsuccessful three-phase automatic reconnection (TARC) are analyzed. Recommendations are made for increasing the operating reliability of power transmission lines with shunt reactors when there is unsuccessful reconnection.

  3. EIS-0118: Proposed Eugene-Medford 500-kV Transmission Line

    Broader source: Energy.gov [DOE]

    The U.S. Department of Interior developed this statement to assess the environmental impact of a proposed 500-kilovolt transmission line linking Eugene and Medford, Oregon, that would cross through public lands. The Bonneville Power Administration (BPA) would provide service to the proposed line and is a cooperating agency in the statement. BPA adopted the EIS on 7/10/1985.

  4. Space charge measurements downwind from a monopolar 500 KV HVDC test line

    SciTech Connect (OSTI)

    Carter, P.J.; Johnson, G.B. (General Electric Co., EPRI-High Voltage Transmission, Research Center, Lenox, MA (US))

    1988-10-01T23:59:59.000Z

    One quantity that helps describe the electrical environment in the vicinity of a HVDC line is space charge, a quantity that consists of charged air ions and charged aerosols. This paper describes measurements made at the Electric Power Research Institute's High Voltage Transmission Research Center (HVTRC) in Lenox, MA to determine the concentration of space charge present downwind of a HVDC test line and the influence of wind on the space charge level. The instrumentation used to make the measurements of space charge downwind of the line is also described.

  5. EIS-0159: Flatiron-Erie 115-kV Transmission Line

    Broader source: Energy.gov [DOE]

    "The Western Area Power Administration proposes to build 27 new wood H-frame structures along the line, to replace or modify 45 of the existing structures and to remove 11 of them."

  6. EIS-0078: Jonesboro-Hergett 161-kV Transmission Line

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy's Southwestern Power Administration developed this statement to assess the environmental and socioeconomic impacts of a 161-kilovolt transmission line in Craighead County, Arkansas, including its proposed and alternate routes.

  7. EIS-0399: Montana Alberta Tie Ltd. (MATL) 230-KV Transmission Line

    Broader source: Energy.gov [DOE]

    DOE, jointly with the Montana Department of Environmental Quality (MDEQ), prepared an EIS that evaluated the potential environmental impacts of a proposed international transmission line that would cross the U.S.-Canada border in northwest Montana.

  8. Type A Accident Investigation Report on the June 25, 1997, Contractor Inspector Fatality on the Satsop-Aberdeen #2 & #3 230 kV Line

    Broader source: Energy.gov [DOE]

    On June 27, 1997, I established a Type-A Accident Investigation Board to investigate the June 25, 1997 fatal contractor accident which occurred on BPA?s Satsop-Aberdeen #2 and #3 230-kV transmission lines right-of-way.

  9. Type A Accident Investigation Board Report of the April 25, 1997, Contractor Fatality on the Olympia-White River #1 230 kV Line

    Broader source: Energy.gov [DOE]

    On April 25, 1997, at approximately 1510 hours, a lineman for Great Southwestern Construction Inc. was fatally electrocuted when he came in direct contact with a deenergized 230-kilovolt (kV) transmission power line conductor which contained an induced voltage.

  10. EIS-0103: New England/Hydro-Quebec 450-kV Direct Current Transmission Line Interconnection

    Broader source: Energy.gov [DOE]

    The Economic Regulatory Administration prepared this statement to evaluate the environmental impacts of the construction, maintenance and operation of a 57-mile transmission line from Monroe, New Hampshire, to the U.S./Canadian border for the purpose of economic exchange of power and increased reliability.

  11. EA-1551: Montana Alberta Tie Ltd. (MATL) 230-KV Transmission Line

    Broader source: Energy.gov [DOE]

    DOE started to prepare, jointly with the Montana Department of Environmental Quality (MDEQ), an EA that would also serve as a state EIS. The document would evaluate the potential environmental impacts of a proposed international transmission line that would cross the U.S.-Canada border in northwest Montana. Based on comments received on the DOE Draft EA/MDEQ Draft EIS, DOE cancelled preparation of the EA and announced preparation of DOE/EIS-0399 (of the same title).

  12. EIS-0301: NRG Energy Services, Inc., Arizona-Baja California 500 kV Transmission Line

    Broader source: Energy.gov [DOE]

    This EIS analyzes DOE's decision to approve NRG Energy, Inc. (NRG) for a Presidential permit to construct a 500,000-volt transmission line originating at the switchyard of the Palo Verde Nuclear Generating Station near Phoenix, Arizona, and extending approximately 177 miles to the southwest, where it would cross the United States (U.S.) border with Mexico in the vicinity of Calexico, California.

  13. International 345 kV transmission line to Highgate, Vermont: environmental assessment

    SciTech Connect (OSTI)

    Not Available

    1985-02-01T23:59:59.000Z

    The action under consideration is the issuance of a Presidential permit to the Vermont Electric Power Company, Inc. (VELCO) for the construction, operation, maintenance and connection of a facility that will cross the United States-Canada border for international transmission of electric energy. The proposed transmission facilities will consist of a 7.5 mile, alternating current (ac) transmission line and a 200 MW back-to-back direct current (dc) converter terminal station. None of the facilities will involve any polluting emissions. The construction and maintenance of the proposed converter terminal station and transmission facilities will have little or no impact on the geologic features of the region. The transmission line will have little or no effect on agricultural land. Impacts on commercial forestry in the area will be minimal. The proposed route will require clearing about 36 acres of forest. The proposed transmission line and converter terminal site will have no effect on recreational activities, mining activites, residential, commercial, or industrial land use. The proposed corridor will have a minimal impact on area terrestrial wildlife and plant communities. The proposed project will have little or no impact on future population distribution, the operation of local services, employment and economic benefit, or housing in either Franklin or Highgate. 16 references, 3 figures. (ACR)

  14. EIS-0112: Rifle to San Juan 345-kV Transmission Line and Associated Facilities

    Broader source: Energy.gov [DOE]

    The U.S. Department of Agriculture - Rural Electrification Administration developed this statement to evaluate the environmental impacts of the Colorado-Ute Electric Association Inc. and the U.s. Department of Energy's Western Area Power Administration (WAPA) constructing and operating a 345-kilovolt transmission line from Rifle, Colorado, to the San Juan Generating Station near Farmington, New Mexico. WAPA served as a cooperating agency in the preparation of this statement and adopted it on 10/30/1984. WAPA assumed the lead role for project implementation after issuance of the final statement.

  15. Development of NS-TACSR with extremely suppressed aeolian noise and its application to 500 kV overhead transmission lines

    SciTech Connect (OSTI)

    Tsujimoto, K.; Furukawa, S. (Kansai Electric Power Co., Inc., Osaka (Japan)); Shimojima, K.; Yamamoto, K. (Hitachi Cable, Ltd., Hitachi (JP))

    1991-10-01T23:59:59.000Z

    Recently in Japan, with the unprecedented advance of residential area development in the suburbs of large cities, it has become quite difficult to secure the routes of EHV transmission lines from nuclear power plants in remote places to the suburbs of large cities, urging resolution of environmental problems related to transmission lines. In Japan, aerodynamic sound produced by conductors and insulators frequently caused noise problems. Having an opportunity of constructing a 500 kV transmission line through a residential are, we made a research to resolve this noise problem. This paper describes the characteristics of aeolian noise and preventive measures against it.

  16. Environmental Assessment for Central Power and Light Company`s proposed Military Highway-CFE tie 138/69-kV transmission line project Brownsville, Cameron County, Texas

    SciTech Connect (OSTI)

    Not Available

    1992-04-01T23:59:59.000Z

    Central Power and Light Company (CPL) intends to upgrade its existing transmission line ties with the Commision Federal de Electricidad (CFE) system in Mexico. CPL currently has a single 69-kilovolt (kV) transmission line in the Brownsville area which connects CPL`s system with the system of CFE. This existing line runs between the Brownsville Switching Station, located on Laredo Road in Brownsville, Cameron County, Texas, and an existing CFE 69-kV line at the Rusteberg Bend of the Rio Grande in Cameron County. Under current conditions of need, the existing 69-kV line does not possess sufficient capability to engage in appropriate power exchanges. Therefore, CPL is proposing to build a new line to link up with CFE. This proposed line would be a double-circuit line, which would (1) continue (on a slightly relocated route) the existing 69-kV tie from CPL`s Brownsville Switching Station to CFE`s facilities, and (2) add a 138-kV tie from the Military Highway Substation, located on Military Highway (US Highway 281), to CFE`s facilities. The proposed 138/69-kV line, which will be constructed and operated by CPL, will be built primarily on steel single-pole structures within an average 60-foot (ft) wide right-of-way (ROW). It will be approximately 6900--9200 ft (1.3--1.7 miles) in length, depending on the alternative route constructed.

  17. Heavy duty insulator assemblies for 500-kV bulk power transmission line with large diameter octagonalbundled conductor

    SciTech Connect (OSTI)

    Tsujimoto, K.; Hayase, I.; Hirai, J.; Inove, M.; Naito, K.; Yukino, T.

    1982-11-01T23:59:59.000Z

    This paper describes the design procedure and the results of field tests on mechanical performances of insulator assemblies newly developed to support octagonal-bundled conductors for 500-kV bulk power transmission. Taking account of conductor-motion-induced peak tensile load, fatigue, torsional torque and others, a successful design has been achieved in two prototype assemblies for such heavy mechanical duties as encountered during conductor galloping or swing. This has been proved throughout three years of the field tests.

  18. Proposed amendment to presidential permit PP-63 and associated modifications to 500 kV international transmission line, Forbes, Minnesota to Manitoba, Canada. [Forbes Substation

    SciTech Connect (OSTI)

    Not Available

    1992-10-01T23:59:59.000Z

    This Addendum to the Final Environmental Assessment for the Proposed Amendment to Presidential Permit PP-63 and Associated Modifications to 500 kV International Transmission Line: Forbes, Minnesota to Manitoba, Canada (DOE/EA-587) addresses Northern States Power Company's (NSP) proposed expansion of the Forbes Substation. The applicant has requested that the expansion take place on the west side of the substation, within the existing property line, instead of on the north side as originally proposed. All of the proposed construction would take place on property already owned by NSP. DOE has reviewed the environmental impacts associated with this minor modification and has determined that the conclusions reached in the environmental assessment and Finding of No Significant Impact prepared in connection with NSP's original amendment request remain valid.

  19. Proposed amendment for Presidential Permit PP-63 and associated modifications to 500 kV international transmission line, Forbes, Minnesota to Manitoba, Canada Northern States Power Company. Final Environmental Assessment

    SciTech Connect (OSTI)

    Not Available

    1992-02-01T23:59:59.000Z

    Northern States Power Company, (NSP), a Minnesota investor owned utility has applied to the Office of Fossil Energy, United States Department of Energy, to amend Presidential Permit PP-63 to allow for alterations to the 500 kV transmission line and as sedated facilities currently regulated by this permit. The alterations proposed for the 500 kV line owned by NSP are part of a long term effort sponsored by NSP to upgrade the existing NSP transmission system to allow for increased exchange of electricity with the Manitoba Hydro-Electric Board. Presidential Permit PP-63 authorized NSP to construct, connect, operate and maintain a 500 kV line at the United States/Canadian border approximately seven-and-a-half miles west of Warroad in Roseau County, Minnesota. This line connects with a 500 kV line owned and operated by the Manitoba Hydro-Electric Board (MHEB), which extends from Dorsey, Manitoba, Canada to the United States/Canadian border. NSP proposes to increase the electricity transfer capability of this transmission facility by constructing a new 80-acre substation on the existing 500 kV line in Roseau County, Minnesota, and upgrading the existing substation at Forbes, Minnesota. The proposed Roseau substation would contain two 41.5 ohm series capacitor banks. In addition, static VAR compensators are to be installed at the existing Forbes Substation. Approximately 5 acres would be added to the 30-acre Forbes site to house the additional equipment. No new lines would enter or exit the facility. NSP proposes to place the new Roseau Substation in service in May 1993 and to complete the upgrading of the Forbes Substation in March 1994. The primary, initial purpose of these modifications is to enable NSP to import 400 megawatts of electric power from MHEB during the summer months to meet peak electrical demand in the Minneapolis-St. Paul area. It is expected that this power transfer would begin in 1993.

  20. Performance of a technical and economical feasibility study of an HVDC compressed gas insulated transmission line. [600 kV

    SciTech Connect (OSTI)

    LaBarge, R.L.

    1980-12-15T23:59:59.000Z

    Progress in evaluating the technical feasibility of SF/sub 6/-insulated cables and circuit breakers for HVDC systems is reported. During this reporting period a new test setup was completed. An assembly jig was designed and fabricated. Model cable up to 20-ft length can be assembled complete outside the test tank. Components to extend the test tank to accommodate a 20-ft model cable have been obtained. A report was drafted on the effect of material selection as well as processing into insulators on the long-term dielectric performance of the insulator. The vertical leaf expansion joint design was improved by replacing the Alcuplate copper-to-aluminum transition piece with nickel plating on the aluminum parts. The joint was fatigue tested with condition which simulate almost 2 1/2 cycles of temperature excursions each day for the 40 year design life of the line. Electrical tests of the joint are in progress.

  1. Characterization Plan for Soils Around Drain Line PLA-100115

    SciTech Connect (OSTI)

    D. Shanklin

    2006-05-24T23:59:59.000Z

    This Characterization Plan supports the Hazardous Waste Management Act/Resource Conservation and Recovery Act (HWMA/RCRA) closure of soils that may have been contaminated by releases from drain line PLA-100115, located within the Idaho Nuclear Technology and Engineering Center at the Idaho National Laboratory Site. The requirements to address the closure of soils contaminated by a potential release from this line in a characterization plan was identified in the "HWMA/RCRA Less Than 90-day Generator Closure Report for the VES-SFE-126."

  2. Proposed Amendment to Presidential Permit PP-63 and Associated Modifications to 500-kV International Transmission Line: Forbes, Minnesota to Manitoba, Canada, Northern States Power Company. Addendum to the final Environmental Assessment

    SciTech Connect (OSTI)

    Not Available

    1992-10-01T23:59:59.000Z

    This Addendum to the Final Environmental Assessment for the Proposed Amendment to Presidential Permit PP-63 and Associated Modifications to 500 kV International Transmission Line: Forbes, Minnesota to Manitoba, Canada (DOE/EA-587) addresses Northern States Power Company`s (NSP) proposed expansion of the Forbes Substation. The applicant has requested that the expansion take place on the west side of the substation, within the existing property line, instead of on the north side as originally proposed. All of the proposed construction would take place on property already owned by NSP. DOE has reviewed the environmental impacts associated with this minor modification and has determined that the conclusions reached in the environmental assessment and Finding of No Significant Impact prepared in connection with NSP`s original amendment request remain valid.

  3. Proposed amendment to presidential permit PP-63 and associated modifications to 500 kV international transmission line, Forbes, Minnesota to Manitoba, Canada. Addendum to the final environmental assessment

    SciTech Connect (OSTI)

    Not Available

    1992-10-01T23:59:59.000Z

    This Addendum to the Final Environmental Assessment for the Proposed Amendment to Presidential Permit PP-63 and Associated Modifications to 500 kV International Transmission Line: Forbes, Minnesota to Manitoba, Canada (DOE/EA-587) addresses Northern States Power Company`s (NSP) proposed expansion of the Forbes Substation. The applicant has requested that the expansion take place on the west side of the substation, within the existing property line, instead of on the north side as originally proposed. All of the proposed construction would take place on property already owned by NSP. DOE has reviewed the environmental impacts associated with this minor modification and has determined that the conclusions reached in the environmental assessment and Finding of No Significant Impact prepared in connection with NSP`s original amendment request remain valid.

  4. Type B Accident Investigation Board Report on the July 25, 1997, Contract Brush Cutter Injury on the Ashe-Marion #2 500 kV Line

    Broader source: Energy.gov [DOE]

    On July 25, 1997, at 1205 hours, a contract hand brush cutter was seriously injured when he felled a tree close to a Bonneville Power Administration energized transmission power line, located within a BPA transmission-line corridor.

  5. Draft environmental impact statement for construction and operation of the proposed Bangor Hydro-Electric Company`s second 345-kV transmission tie line to New Brunswick

    SciTech Connect (OSTI)

    NONE

    1993-10-01T23:59:59.000Z

    This Draft Environmental Impact Statement (DEIS) was prepared by the US Department of Energy (US DOE). The proposed action is the issuance of Presidential Permit PP-89 by DOE to Bangor Hydro-Electric Company to construct and operate a new international transmission line interconnection to New Brunswick, Canada that would consist of an 83.8 mile (US portion), 345-kilovolt (kV) alternating current transmission line from the US-Canadian border at Baileyville, Maine to an existing substation at Orrington, Maine. The principal environmental impacts of the construction and operation of the transmission line would be incremental in nature and would include the conversion of forested uplands (mostly commercial timberlands) and wetlands to right-of-way (small trees, shrubs, and herbaceous vegetation). The proposed line would also result in localized minor to moderate visual impacts and would contribute a minor incremental increase in the exposure of some individuals to electromagnetic fields. This DEIS documents the purpose and need for the proposed action, describes the proposed action and alternatives considered and provides a comparison of the proposed and alternatives routes, and provides detailed information on analyses of the environmental consequences of the proposed action and alternatives, as well as mitigative measures to minimize impacts.

  6. EIS-0365: Draft Environmental Impact Statement for the Imperial-Mexicali 230-kV Transmission Lines, EIS-0365 (May 2004)

    Broader source: Energy.gov [DOE]

    A U.S. Department of Energy (DOE) Presidential permit is required to construct an electric transmission line across the U.S. international border. On February 27, 2001, Baja California Power, Inc. ...

  7. El Paso Electric Company Diablo Substation to the US-Mexico border 115kV transmission line project. Final Environmental Assessment

    SciTech Connect (OSTI)

    Not Available

    1992-04-01T23:59:59.000Z

    This Environmental Assessment documents the analysis of alternative corridors for development and operation of a proposed 115 kilovolt transmission line using private lands and transporting power to the US-Mexico international border. The project will require (1) an amendment to El Paso Electric Company`s existing export authorization to transfer power across this border, and (2) a Presidential Permit for construction of the transmission line. The project would be located in Dona Ana county in southern New Mexico, approximately five miles west of El Paso, Texas. The alternative corridors, specific locations within those corridors, and structure types are identified and analyzed in the environmental studies.

  8. EA-2002: Right-of-Way Application for the Tucson-Apache 115-kV Transmission Line, Pima County, Arizona

    Broader source: Energy.gov [DOE]

    Western Area Power Administration (Western) and the Bureau of Indian Affairs (BIA), as joint lead agencies, prepared an EA that evaluates the potential environmental impacts of a proposal for BIA to grant Western a 150-foot right-of-way across tribal land along the existing Tucson-Apache Transmission Line to replace the previous 100-foot right-of-way, which has expired.

  9. EIS-0032: 500 kV International Transmission Line NSP-TR-1, Forbes, Minnesota to Manitoba, Canada, Northern States Power Company

    Broader source: Energy.gov [DOE]

    The Economic Regulatory Administration developed this EIS to evaluate the environmental impacts of a 500-kilovolt transmission line proposed by the Northern States Power Company to provide a transmission facility for the exchange of electrical energy between Canada and the United States.

  10. EIS-0067: 230-kV International Transmission Line San Diego County, California to Tijuana, Mexico, San Diego Gas and Electric Company

    Broader source: Energy.gov [DOE]

    The Economic Regulatory Administration and the California Public Utilities Commission jointly prepared this EIS to evaluate the environmental impacts of the construction, maintenance and operation of a 10-mile, 230-kilovolt transmission line across the U.S./Mexico border for the purpose of economic exchange of power and increased reliability.

  11. EA-1899: Rerouting and Renovating of Estes-Flatiron Three Transmission Lines to Double Circuit 115-kV, Larimer County, Colorado

    Broader source: Energy.gov [DOE]

    DOE’s Western Area Power Administration started to prepare an EA to evaluate the environmental impacts of a proposal to reroute and renovate the Estes-Flatiron Three Transmission Lines in Larimer County, Colorado. Based on comments received during the scoping period, Western ended preparation of DOE/EA-1899 and announced its intent to prepare and environmental impact statement, DOE/EIS-0483.

  12. Waltz Mill testing of 345-kV PPP cable

    SciTech Connect (OSTI)

    Burghardt, R.R. (Westinghouse Electric Corp., Ruffs Dale, PA (United States))

    1991-09-01T23:59:59.000Z

    A 345-kV PPP-insulated cable was subjected to a two-year accelerated life test program at the EPRI Waltz Mill Cable Test Facility. Testing started in November 1985 and was successfully completed in September 1988. The program included conductor temperatures ranging from 85{degrees}C to 105{degrees}C and line-to-line voltages from 362 kV to 474 kV. Cyclic testing was performed during 17 of the 24 months. Dissipation factor measurements were made throughout the program. The measurements indicated no deterioration of the cable or splices as a consequence of the high temperatures and voltages applied to them in this test program. 2 refs., 24 figs.

  13. Africa planned gas lines will meet future demand

    SciTech Connect (OSTI)

    Not Available

    1991-11-01T23:59:59.000Z

    The burgeoning European market for natural gas is expected to create major gas line construction. The potential for North Africa looks particularly promising in 1991. Italy's ENI has proposed a 6,000-km (3,728-mi) gas network in North Africa to connect gas-rich Libya and Algeria with Morocco and Mauritania, making large volumes available to the European market. According to the proposal, a gas line would run from the Sirte Basin in Libya west to Mauritania. Extending the line eastward through Egypt and on to the Arabian Peninsula would provide export access. In this paper initial studies are examine reserve projections for the next 20 years, then based on results, a transmission/distribution network will be designed, including an offshore gathering system.

  14. Power Line Plan of Development Outline | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov YouKizildere I Geothermal PwerPerkins County, Nebraska: EnergyPiratiniEdwards,PoseyPoudre Valley RGenerating Inc Place:Line

  15. Malcolm, N. and Aggarwal, R.k. (2014) An Analysis of Reducing Back Flashover Faults with Surge Arresters on 69/138 kV Double

    E-Print Network [OSTI]

    McCusker, Guy

    Arresters on 69/138 kV Double Circuit Transmission Lines Due to Direct Lightning Strikes on the Shield Wires-EMTP, Back flashover faults, Lightning strokes, Surge arrester, Transmission lines. Abstract Back flashover causes of power interruptions on the double-circuit 69/138 kV overhead transmission lines in Jamaica

  16. HWMA/RCRA Closure Plan for the CPP-602 Laboratory Lines

    SciTech Connect (OSTI)

    Idaho Cleanup Project

    2009-09-30T23:59:59.000Z

    This Hazardous Waste Management Act/Resource Conservation and Recovery Act Closure (HWMA/RCRA) Plan for the CPP-602 laboratory lines was developed to meet the tank system closure requirements of the Idaho Administrative Procedures Act 58.01.05.008 and 40 Code of Federal Regulations 264, Subpart G. CPP-602 is located at the Idaho Nuclear Technology and Engineering Center at the Idaho National Laboratory Site. The lines in CPP-602 were part of a liquid hazardous waste collection system included in the Idaho Nuclear Technology and Engineering Center Liquid Waste Management System Permit. The laboratory lines discharged to the Deep Tanks System in CPP-601 that is currently being closed under a separate closure plan. This closure plan presents the closure performance standards and the methods for achieving those standards. The closure approach for the CPP-602 laboratory lines is to remove the lines, components, and contaminants to the extent practicable. Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) Site CPP-117 includes the CPP-602 waste trench and the area beneath the basement floor where waste lines are direct-buried. Upon completion of rinsing or mopping to remove contamination to the extent practicable from the waste trench and rinsing the intact buried lines (i.e., stainless steel sections), these areas will be managed as part of CERCLA Site CPP-117 and will not be subject to further HWMA/RCRA closure activities. The CPP-602 building is being decontaminated and decommissioned under CERCLA as a non-time critical removal action in accordance with the Federal Facility Agreement/Consent Order. As such, all waste generated by this CERCLA action, including closure-generated waste, will be managed in coordination with that CERCLA action in substantive compliance with HWMA/RCRA regulations. All waste will be subject to a hazardous waste determination for the purpose of supporting appropriate management and will be managed in accordance with this plan. ii

  17. Waltz Mill testing of 765-kV paper-polypropylene-paper (PPP) cable

    SciTech Connect (OSTI)

    Burghardt, R.R. (Westinghouse Electric Corp., Ruffs Dale, PA (United States))

    1992-06-01T23:59:59.000Z

    A 765-kV PPP-insulated cable was subjected to a 27-month accelerated life test program at the EPRI Waltz Mill Cable Test Facility. Testing started in August 1981 and was successfully completed in January 1985. The program included conductor temperatures ranging from 85{degree}C to 105{degree}C and line-to-line voltages from 800 kV to 1050 kV. Cyclic testing was performed during 20 of the 27 months. Dissipation factor measurements were made throughout the program. The measurements indicated no deterioration of the cable or splices as a consequence of the high temperatures and voltages applied to them in this test program.

  18. Electric Transmission Lines (Iowa)

    Broader source: Energy.gov [DOE]

    Electric transmission lines capable of operating at 69 kV or greater cannot be constructed along, across, or over any public highways or grounds outside of cities without a franchise from the...

  19. Florida Electric Transmission Line Siting Act (Florida)

    Broader source: Energy.gov [DOE]

    The Transmission Line Siting Act (TLSA) is the state’s centralized process for licensing electrical transmission lines which; (a) are 230 kV or larger; (b) cross a county line; and, (c) are 15...

  20. KV-tOOJHfe Metallurgy Department

    E-Print Network [OSTI]

    »KV-tOOJHfe RisB-R-547 Metallurgy Department Progress Report for the Period 1 January to 31 December 1986 Risř National Laboratory, DK-4000 Roskilde, Denmark April 1987 #12;Risř-R-547 METALLURGY.B. BiIde-Sřrensen Abstract. The activities of the Metallurgy Department at Risř during 1986

  1. EIS-0325: Schultz-Hanford Area Transmission Line Project, WA

    Broader source: Energy.gov [DOE]

    BPA proposes to construct a new 500-kilovolt (kV) transmission line in central Washington. This project would increase transmission system capacity north of Hanford.

  2. The varistor protected series capacitors at the 500 KV broadview substation

    SciTech Connect (OSTI)

    Barcus, J.M. (General Electric Co., Hudson Falls, NY (US)); Miske, S.A. Jr. (General Electric Co., Schenectady, NY (US)); Vitols, A.P. (General Electric Co., Pittsfield, MA (US)); Maynard, H.M. (Montana Power Co., Butte, MT (US)); Peterson, W.G. (Bonneville Power Admin., Portland, OR (US))

    1988-10-01T23:59:59.000Z

    Two 235 Mvar series capacitors have been successfully applied at the 500 kV Broadview substation of the Colstrip Transmission Project. The series capacitors have an overvoltage protection system based on metal oxide varistors. The system provides instantaneous bypass and reinsertion of the capacitors following external line section faults. The excellent performance of the equipment was demonstrated during staged fault tests performed in October, 1985. The banks have been in successful operation since January, 1986.

  3. Commonwealth Edison 345kV L.P.P. splicing school

    SciTech Connect (OSTI)

    Johnsen, D.P. [ComEd, Chicago, IL (United States)

    1996-11-01T23:59:59.000Z

    The ComEd splicing school was held in January 1995 to train the work force for the installation of the first 345kV High Pressure Fluid Filled pipe type L.P.P. (Laminated Paper Polypropylene) insulated cable on the ComEd system. Construction is nearing completion on ComEd`s 345kV underground transmission line 17723 between Burnham TSS 177 and Taylor TSS 153 located just south of the Chicago Loop. Continued development and construction of the down-town Chicago Area and the south Loop has established the need for this line to reinforce the transmission network serving this critical area. 345kV transmission Line 17723 is a combination of overhead facility and HPFF (High Pressure Fluid Filled) pipe type L.P.P. cable with a summer normal rating of 900 MVA and a summer emergency rating of 1,200 MVA. This paper describes the training facility, innovative changes in tooling and the results of the training exercises.

  4. Improvement plans for the RHIC/AGS on-line model environments

    SciTech Connect (OSTI)

    Brown,K.A.; Ahrens, L.; Beebe-Wang, J.; Morris, J.; Nemesure, S.; Robert-Demolaize, G.; Satogata, T.; Schoefer, V.; Tepikian, S.

    2009-08-31T23:59:59.000Z

    The on-line models for Relativistic Ion Collider (RHIC) and the RHIC pre-injectors (the AGS and the AGS Booster) can be thought of as containing our best collective knowledge of these accelerators. As we improve these on-line models we are building the framework to have a sophisticated model-based controls system. Currently the RHIC on-line model is an integral part of the controls system, providing the interface for tune control, chromaticity control, and non-linear chromaticity control. What we discuss in this paper is our vision of the future of the on-line model environment for RHIC and the RHIC preinjectors. Although these on-line models are primarily used as Courant-Snyder parameter calculators using live machine settings, we envision expanding these environments to encompass many other problem domains.

  5. Algorithms for on-line aggregate production plan revision with stochastic autocorrelated demand

    E-Print Network [OSTI]

    Ding, Zixuan

    1989-01-01T23:59:59.000Z

    Comparison -1 3 Components and Total Costs Conrparsson -2 8(l 4 Components and Total Costs Comparsson -3 Components and Total Costs Comparison --I 6 Conrponents and Total Costs Companson ? 5 7 Productson Plan Trajectory Generated by PSH -1 8 Production...-Reference Adapfiye Coutrol Concept 6 The Moslel-Reference Adaptive System 21 40 7 The Production Plan Learning Scheme 45 8 Scheme of the Training; Period . . 9 The Bridging. Period . . 10 Scheme of Planning and Learning Period . 11 Simulated Sales and I...

  6. Design and Overview of 100 kV Bushing for the DNB Injector of ITER

    SciTech Connect (OSTI)

    Shah, Sejal; Bandyopadhyay, M.; Rotti, C.; Singh, M. J.; Roopesh, G.; Chakraborty, A. K. [ITER-India, Institute for Plasma Research, Gandhinagar-382025, Gujarat (India); Rajesh, S. [ITER-India, Institute for Plasma Research, Gandhinagar-382025, Gujarat (India); Microelectronics and Materials Physics Labs, P.O.Box 4500, FIN-90014 University of Oulu (Finland); Nishad, S.; Srusti, B. [DesignTech Systems Ltd, Banjara Hills, Hyderabad, Andhra Pradesh-500034 (India); Schunke, B.; Hemsworth, R.; Chareyre, J.; Svensson, L. [ITER Organisation, Route de Vinon, CS 90 046, 13067 St. Paul lez Durance Cedex (France)

    2011-09-26T23:59:59.000Z

    The 100 kV bushing is one of the most important and technologically challenging Safety Important Class (SIC) components of the Diagnostic Neutral Beam (DNB) injector of ITER. It forms interface between gas insulated electrical transmission line and torus primary vacuum and acts as a vacuum feedthrough of ITER. Design optimization has been carried out to meet the electric and structural requirements based on its classification. Unlike HNB bushing, single stage bushing is designed to provide 100 kV isolation. Finite Element Analysis (FEA) based optimization has been carried out for electrostatic and structural analysis. Manufacturing assembly sequence is studied and presented in this paper. However validation of the same is foreseen from manufacturer.

  7. Is planning failing? : the impacts of decision making processes on the Green Line Extension

    E-Print Network [OSTI]

    Ciborowski, Matthew A

    2009-01-01T23:59:59.000Z

    Research was conducted on the proposed Green Line Extension, a light rail corridor from Cambridge through Somerville and Medford, Massachusetts. The project is being undertaken by the Massachusetts Executive Office of ...

  8. Manpower planning and cycle-time reduction of a labor-intensive assembly line

    E-Print Network [OSTI]

    Oh, Shao Chong

    2010-01-01T23:59:59.000Z

    The demand for Gas Lift Mandrels(GLM) in the oil and gas industry is expected to increase over the next few years, requiring Schlumberger's GLM assembly line to increase their manufacturing capacity. Given the labor-intensive ...

  9. Retirement TimeLine TIAA-CREF/Fidelity Retirement Plan Participant

    E-Print Network [OSTI]

    is essential early in your career! Your TIAA-CREF/Fidelity retirement account is based on the University retirement accounts ­ it is never too early to plan for your retirement! · Review your TIAA you retire? It's important to begin early in researching the types of available pre and post 65

  10. SU-E-J-92: On-Line Cone Beam CT Based Planning for Emergency and Palliative Radiation Therapy

    SciTech Connect (OSTI)

    Held, M; Morin, O; Pouliot, J [UC San Francisco, San Francisco, CA (United States)

    2014-06-01T23:59:59.000Z

    Purpose: To evaluate and develop the feasibility of on-line cone beam CT based planning for emergency and palliative radiotherapy treatments. Methods: Subsequent to phantom studies, a case library of 28 clinical megavoltage cone beam CT (MVCBCT) was built to assess dose-planning accuracies on MVCBCT for all anatomical sites. A simple emergency treatment plan was created on the MVCBCT and copied to its reference CT. The agreement between the dose distributions of each image pair was evaluated by the mean dose difference of the dose volume and the gamma index of the central 2D axial plane. An array of popular urgent and palliative cases was also evaluated for imaging component clearance and field-of-view. Results: The treatment cases were categorized into four groups (head and neck, thorax/spine, pelvis and extremities). Dose distributions for head and neck treatments were predicted accurately in all cases with a gamma index of >95% for 2% and 2 mm criteria. Thoracic spine treatments had a gamma index as low as 60% indicating a need for better uniformity correction and tissue density calibration. Small anatomy changes between CT and MVCBCT could contribute to local errors. Pelvis and sacral spine treatment cases had a gamma index between 90% and 98% for 3%/3 mm criteria. The limited FOV became an issue for large pelvis patients. Imaging clearance was difficult for cases where the tumor was positioned far off midline. Conclusion: The MVCBCT based dose planning and delivery approach is feasible in many treatment cases. Dose distributions for head and neck patients are unrestrictedly predictable. Some FOV restrictions apply to other treatment sites. Lung tissue is most challenging for accurate dose calculations given the current imaging filters and corrections. Additional clinical cases for extremities need to be included in the study to assess the full range of site-specific planning accuracies. This work is supported by Siemens.

  11. EIS-0421: Big Eddy-Knight Transmission Line

    Broader source: Energy.gov [DOE]

    BPA is proposing to build a new 500 kilovolt (kV) transmission line in Wasco County, Oregon and Klickitat County, Washington and a new substation in Klickitat County. The new BPA transmission line...

  12. Lovell-Yellowtail transmission line rebuild project, Western...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    on Flickr. Western is rebuilding the Lovell-to-Yellowtail No. 1 and No. 2 115-kV transmission lines. The 94-circuit-miles of lines are located between Lovell, Wyo., and Yellowtail...

  13. Grand Coulee Transmission Line Replacement Project

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    by the Bureau of Reclamation to design and construct six new 500-kV overhead transmission lines at Grand Coulee Dam. BPA will replace the existing underground transmission...

  14. Second Line of Defense Megaports Initiative Sustainment Plan - Port Klang Malaysia

    SciTech Connect (OSTI)

    King, Curtis A.

    2009-09-29T23:59:59.000Z

    To reduce the risk of illicit trafficking of special nuclear and other radiological materials, the Megaports Initiative installs radiation detection systems at international seaports. Port Klang, Malaysia, is one such seaport identified by the Megaports Initiative as a key area to install equipment to accomplish the mission of preventing the acquisition and smuggling of materials that could be used to create weapons of mass destruction or radiological dispersal devices. Sustainability is a critical factor of all components of the Megaports Initiative. The sustainability plan is developed to assist the partner country in securing the technical, financial, and policy commitments required to develop and implement a country-specific strategy. A robust sustainability plan will define the long-term relationship between the U.S. Department of Energy and the Government of Malaysia as well as promote the ongoing proficient radiation detection system operations at Port Klang, Malaysia.

  15. Second Line of Defense Megaports Initiative Operational Testing and Evaluation Plan Colon Container Terminal (CCT) Panama

    SciTech Connect (OSTI)

    Newhouse, Robert N.

    2010-01-01T23:59:59.000Z

    Report on the Operational Testing and Evaluation to validate and baseline an operable system that meets the Second Line of Defense (SLD) mission requirements. An SLD system is defined as the detection technology and associated equipment, the system operators from the host country, the standard operating procedures (SOPs), and other elements such as training and maintenance which support long-term system sustainment. To this end, the activities conducted during the OT&E phase must demonstrate that the Megaports System can be operated effectively in real-time by Panama Direccion General de Aduanas (DGA Panama Customs) personnel to the standards of the U.S. Department of Energy/National Nuclear Security Administration (DOE/NNSA).

  16. Second Line of Defense Megaports Initiative Operational Testing and Evaluation Plan - Kingston Container Terminal, Port of Kingston, Jamaica

    SciTech Connect (OSTI)

    Deforest, Thomas J.; VanDyke, Damon S.

    2012-03-01T23:59:59.000Z

    Operational Testing and Evaluation Plan - Kingston Container Terminal, Port of Kingston, Jamaica was written for the Second Line of Defense Megaports Initiative. The purpose of the Operational Testing and Evaluation (OT&E) phase of the project is to prepare for turnover of the Megaports system supplied by U.S. Department of Energy/National Nuclear Security Administration (DOE/NNSA) located at the Kingston Container Terminal (KCT) of the Port of Kingston, Jamaica to the Government of Jamaica (GOJ). Activities conducted during the OT&E phase must demonstrate that the Megaports system can be operated effectively in real time by Jamaica Customs and KCT personnel to the satisfaction of the DOE/NNSA. These activities will also determine if the Megaports system, as installed and accepted, is performing according to the Megaports Program objectives such that the system is capable of executing the mission of the Second Line of Defense Megaports Initiative. The OT&E phase of the project also provides an opportunity to consider potential improvements to the system and to take remedial action if performance deficiencies are identified during the course of evaluation. Changes to the system should be considered under an appropriate change-control process. DOE/NNSA will determine that OT&E is complete by examining whether the Megaports system is performing as intended and that the GOJ is fully capable of operating the system independently without continued onsite support from the U.S. team.

  17. Biennial Assessment of the Fifth Power Plan Transmission Issues

    E-Print Network [OSTI]

    unscheduled electricity flows over transmission lines leading to increased risks to electric system by the partners in the Colstrip 500 kV transmission lines (Northwestern Energy, Puget Sound Energy, Portland

  18. EIS-0325: Schultz-Hanford Area Transmission Line Project Final Environmental Impact Statement, EIS-0325 (January 2003)

    Broader source: Energy.gov [DOE]

    BPA proposes to construct a new 500-kilovolt (kV) transmission line in central Washington. This project would increase transmission system capacity north of Hanford.

  19. Line-Focus Solar Power Plant Cost Reduction Plan (Milestone Report)

    SciTech Connect (OSTI)

    Kutscher, C.; Mehos, M.; Turchi, C.; Glatzmaier, G.; Moss, T.

    2010-12-01T23:59:59.000Z

    Line-focus solar collectors, in particular parabolic trough collectors, are the most mature and proven technology available for producing central electricity from concentrated solar energy. Because this technology has over 25 years of successful operational experience, resulting in a low perceived risk, it is likely that it will continue to be a favorite of investors for some time. The concentrating solar power (CSP) industry is developing parabolic trough projects that will cost billions of dollars, and it is supporting these projects with hundreds of millions of dollars of research and development funding. While this technology offers many advantages over conventional electricity generation -- such as utilizing plentiful domestic renewable fuel and having very low emissions of greenhouse gases and air pollutants -- it provides electricity in the intermediate power market at about twice the cost of its conventional competitor, combined cycle natural gas. The purpose of this document is to define a set of activities from fiscal year 2011 to fiscal year 2016 that will make this technology economically competitive with conventional means.

  20. LS Power Associates (ON Line - formerly known as SWIP-S) | Department...

    Office of Environmental Management (EM)

    (ON Line) project, a 235-mile, 500 kV AC transmission line capable of carrying 600 MW of power to the grid, running north-south between Ely, NV and just north of Las Vegas. The...

  1. EA-1891: Alvey-Fairview Transmission Line Rebuild Project, Oregon

    Broader source: Energy.gov [DOE]

    This EA evaluates the environmental impacts of a proposal to rebuild DOE’s Bonneville Power Administration’s Alvey-Fairview No. 1 230-kV transmission line located between Eugene, Oregon, and Coquille, Oregon.

  2. A 50 kV solid state multipulse kicker modulator

    SciTech Connect (OSTI)

    Walstrom, P. L. (Peter L.); Cook, E. G. (Edward G.)

    2003-01-01T23:59:59.000Z

    Performance requirements, design concepts, and test results for a prototype multipulse kicker modulator based on solid-state switches and a voltage-adding transformer topology are described. Tape-wound cores are stacked to form the transformer primary windings and a cylindrical pipe that passes through the circular inner diameters of the cores serves as the secondary winding of the step-up transformer. Boards containing MOSFET switches, trigger circuitry, and energy-storage capacitors plug into the core housings. A 50 kV prototype modulator that meets most of the facility requirements has been designed, fabricated, and tested at LLNL. More recent work has been concerned with designing and testing cores and boards with the full volt-second capability needed for 24-pulse operation. Results of the 50 kV prototype tests, preliminary tests of the full-volt-second cores and boards, and future development needs are described.

  3. CEBAF 200 kV Inverted Electron Gun

    SciTech Connect (OSTI)

    J.M. Grames, P.A. Adderley, J. Clark, J. Hansknecht, M. Poelker, M.L. Stutzman, R. Suleiman, K.E.L. Surles-Law

    2011-03-01T23:59:59.000Z

    Two DC high voltage GaAs photoguns have been built at Jefferson Lab based on a compact inverted insulator design. One photogun provides the polarized electron beam at CEBAF and operates at 130 kV bias voltage. The other gun is used for high average current lifetime studies at a dedicated test facility and has been operated at bias voltage up to 225 kV. The advantages of higher DC voltage for CEBAF include reduced space-charge emittance growth and the potential for prolonged photocathode lifetime. However, a consequence of operating at higher voltages is the increased likelihood of field emission or breakdown, both of which are unacceptable. Highlights of the R&D studies leading toward a production 200keV GaAs photogun for CEBAF will be presented.

  4. The design and construction of a 130 K.V. radio frequency Cockcroft Walton type generator

    E-Print Network [OSTI]

    Robba, William Augustus

    1951-01-01T23:59:59.000Z

    at 30 KV are rather expensive~ and a 500 KV generator of this type would cost several thousand dollars. Sesides thisc the rcgulaticu and efficienoy of suoh a generator leave such to be desired An exanple will nake this c3Alaro Lot v o 1$ f, Vi g x... ourrent~ voltage snd poser for various staok voltages, Steak Voltages (One Stags) 20 K+V+ 15KV 12 K+V+ 10 K Vo 7. $ K. V. 220 Rile 180 Rile 140 ILQs 120 RGs 100 Mile 1500 Stack Plate Current Plato Voltage Poser in Watts QS $0 Varies Set...

  5. A multiconductor model for determining the response of power transmission and distribution lines to a high altitude electromagnetic pulse (HEMP)

    SciTech Connect (OSTI)

    Tesche, F.M.; Barnes, P.R.

    1988-01-01T23:59:59.000Z

    A calculation model for electromagnetic pulse coupling to transmission and transmission line is discussed. Sample calculations for a 345 kV transmission line are given. 3 refs., 8 figs.

  6. Continuous On-Line Learning and Planning in a Pick-and-Place Task Demonstrated Through Body

    E-Print Network [OSTI]

    Paris-Sud XI, Université de

    the robot to plan arm movements according to activated goals. The model is applied to learning a pick always be adapted by the human interacting with it. This ability is demonstrated by teaching the robot of their possibilities for their development. They also should be able to learn from human caregivers or other robots

  7. Multi-Vehicle Path Planning for Non-Line of Sight Communication Tom Schouwenaars, Eric Feron, and Jonathan How

    E-Print Network [OSTI]

    How, Jonathan P.

    line of sight communication to its ground station is lost. Relay helicopters are therefore introduced formulations to model nonconvex obstacles more efficiently. Simulation, hardware in the loop, and flight test by introducing a set of relay helicopters. Indirect communication with the ground station can then be established

  8. CEBAF 200 kV Inverted Electron Gun

    SciTech Connect (OSTI)

    Grames, J M; Clark, J; Hansknecht, J; Poelker, M; Stutzman, M L; Suleiman, R; Surles-Law, K.E.L.; BastaniNejad, M

    2011-03-01T23:59:59.000Z

    Two DC high volt­age GaAs pho­to­guns have been built at Jef­fer­son Lab based on a com­pact in­vert­ed in­su­la­tor de­sign. One pho­to­gun pro­vides the po­lar­ized elec­tron beam at CEBAF and op­er­ates at 130 kV bias volt­age. The other gun is used for high av­er­age cur­rent life­time stud­ies at a ded­i­cat­ed test fa­cil­i­ty and has been op­er­at­ed at bias volt­age up to 225 kV. The ad­van­tages of high­er DC volt­age for CEBAF in­clude re­duced space-charge emit­tance growth and the po­ten­tial for pro­longed pho­to­cath­ode life­time. How­ev­er, a con­se­quence of op­er­at­ing at high­er volt­ages is the in­creased like­li­hood of field emis­sion or break­down, both of which are un­ac­cept­able. High­lights of the R&D stud­ies lead­ing to­ward a pro­duc­tion 200keV GaAs pho­to­gun for CEBAF will be pre­sent­ed.

  9. Proposal for the award of a blanket purchase contract for the supply, installation, commissioning and maintenance of electrical switchgear operating at 18kV and 3.3 kV

    E-Print Network [OSTI]

    2015-01-01T23:59:59.000Z

    Proposal for the award of a blanket purchase contract for the supply, installation, commissioning and maintenance of electrical switchgear operating at 18kV and 3.3 kV

  10. Electrical and mechanical design criteria for EHV and UHV: overhead transmission lines

    SciTech Connect (OSTI)

    Not Available

    1980-06-01T23:59:59.000Z

    The results are presented of a program devoted to the selection of electrical and mechanical design criteria and parameters for overhead power transmission lines for ac systems rated at from 345 to 1100 kV and for dc systems rated at from 600 to 1200 kV. Information is included on the environmental effects, i.e., audible noise and electric fields, of the lines, mechanical and economic requirements, safety, failures, grounding, and lightning protection. (LCL)

  11. Second Line of Defense, Port of Buenos Aires and Exolgan Container Terminal Operational Testing and Evaluation Plan, Buenos Aires, Argentina

    SciTech Connect (OSTI)

    Roberts, Bryan W.

    2012-08-23T23:59:59.000Z

    The Office of the Second Line of Defense (SLD) Megaports project team for Argentina will conduct operational testing and evaluation (OT&E) at Exolgan Container Terminal at the Port of Dock Sud from July 16-20, 2012; and at the Port of Buenos Aires from September 3-7, 2012. SLD is installing radiation detection equipment to screen export, import, and transshipment containers at these locations. The purpose of OT&E is to validate and baseline an operable system that meets the SLD mission and to ensure the system continues to perform as expected in an operational environment with Argentina Customs effectively adjudicating alarms.

  12. EIS-0005-S2: Bonneville Power Administration Proposed FY 1979 Program Facility Planning Supplement Southwest Oregon Area Service, Supplemental

    Broader source: Energy.gov [DOE]

    This statement, one of a series prepared by the U.S. Department of Energy’s Bonneville Power Administration on various facets of its construction and maintenance activities, addresses the potential impact of a major new facility proposed for fiscal year 1979. To allow power generated in Wyoming to be delivered to Southwest Oregon and to facilitate the exchange of electric power between the Pacific Northwest and the Middle Snake region, two basic plans of service, each with two corridor routing options, have been identified to meet system requirements. BPA proposes construction of the following two transmission facilities: (1) a 500-kV line from Idaho Power Company's Brownlee Substation in Idaho to BPA's Slatt Substation near Arlington, Oregon, and (2) a 500-kV line from Buckley (near Maupin, Oregon) to Malin, Oregon. This statement must be reviewed and used in conjunction with the overall programmatic environmental statement entitled ""The Role of the Bonneville Power Administration in the Pacific Northwest Power Supply System, Including Its Participation in the Hydro-Thermal Power Program: A Program Environmental Statement and Planning Report (The ""Role EIS""), particularly Appendix B - BPA Power Transmission.

  13. Tungsten anode spectral model using interpolating cubic splines: Unfiltered x-ray spectra from 20 kV to 640 kV

    SciTech Connect (OSTI)

    Hernandez, Andrew M. [Biomedical Engineering Graduate Group, University of California Davis, Sacramento, California 95817 (United States)] [Biomedical Engineering Graduate Group, University of California Davis, Sacramento, California 95817 (United States); Boone, John M., E-mail: john.boone@ucdmc.ucdavis.edu [Departments of Radiology and Biomedical Engineering, Biomedical Engineering Graduate Group, University of California Davis, Sacramento, California 95817 (United States)

    2014-04-15T23:59:59.000Z

    Purpose: Monte Carlo methods were used to generate lightly filtered high resolution x-ray spectra spanning from 20 kV to 640 kV. Methods: X-ray spectra were simulated for a conventional tungsten anode. The Monte Carlo N-Particle eXtended radiation transport code (MCNPX 2.6.0) was used to produce 35 spectra over the tube potential range from 20 kV to 640 kV, and cubic spline interpolation procedures were used to create piecewise polynomials characterizing the photon fluence per energy bin as a function of x-ray tube potential. Using these basis spectra and the cubic spline interpolation, 621 spectra were generated at 1 kV intervals from 20 to 640 kV. The tungsten anode spectral model using interpolating cubic splines (TASMICS) produces minimally filtered (0.8 mm Be) x-ray spectra with 1 keV energy resolution. The TASMICS spectra were compared mathematically with other, previously reported spectra. Results: Using pairedt-test analyses, no statistically significant difference (i.e., p > 0.05) was observed between compared spectra over energy bins above 1% of peak bremsstrahlung fluence. For all energy bins, the correlation of determination (R{sup 2}) demonstrated good correlation for all spectral comparisons. The mean overall difference (MOD) and mean absolute difference (MAD) were computed over energy bins (above 1% of peak bremsstrahlung fluence) and over all the kV permutations compared. MOD and MAD comparisons with previously reported spectra were 2.7% and 9.7%, respectively (TASMIP), 0.1% and 12.0%, respectively [R. Birch and M. Marshall, “Computation of bremsstrahlung x-ray spectra and comparison with spectra measured with a Ge(Li) detector,” Phys. Med. Biol. 24, 505–517 (1979)], 0.4% and 8.1%, respectively (Poludniowski), and 0.4% and 8.1%, respectively (AAPM TG 195). The effective energy of TASMICS spectra with 2.5 mm of added Al filtration ranged from 17 keV (at 20 kV) to 138 keV (at 640 kV); with 0.2 mm of added Cu filtration the effective energy was 9 keV at 20 kV and 169 keV at 640 kV. Conclusions: Ranging from 20 kV to 640 kV, 621 x-ray spectra were produced and are available at 1 kV tube potential intervals. The spectra are tabulated at 1 keV intervals. TASMICS spectra were shown to be largely equivalent to published spectral models and are available in spreadsheet format for interested users by emailing the corresponding author (JMB)

  14. 130kV 130A High Voltage Switching Mode Power Supply for Neutral Injections – Control Issues and Algorithms

    E-Print Network [OSTI]

    130kV 130A High Voltage Switching Mode Power Supply for Neutral Injections – Control Issues and Algorithms

  15. Deuterium Retention in Beryllium Exposed to a 60kV Deuterium Beam ­ Consequences for Next Step Devices

    E-Print Network [OSTI]

    Deuterium Retention in Beryllium Exposed to a 60kV Deuterium Beam ­ Consequences for Next Step Devices

  16. Hopi Sustainable Energy Plan

    SciTech Connect (OSTI)

    Norman Honie, Jr.; Margie Schaff; Mark Hannifan

    2004-08-01T23:59:59.000Z

    The Hopi Tribal Government as part of an initiative to ?Regulate the delivery of energy and energy services to the Hopi Reservation and to create a strategic business plan for tribal provision of appropriate utility, both in a manner that improves the reliability and cost efficiency of such services,? established the Hopi Clean Air Partnership Project (HCAPP) to support the Tribe?s economic development goals, which is sensitive to the needs and ways of the Hopi people. The Department of Energy (DOE) funded, Formation of Hopi Sustainable Energy Program results are included in the Clean Air Partnership Report. One of the Hopi Tribe?s primary strategies to improving the reliability and cost efficiency of energy services on the Reservation and to creating alternative (to coal) economic development opportunities is to form and begin implementation of the Hopi Sustainable Energy Program. The Hopi Tribe through the implementation of this grant identified various economic opportunities available from renewable energy resources. However, in order to take advantage of those opportunities, capacity building of tribal staff is essential in order for the Tribe to develop and manage its renewable energy resources. As Arizona public utilities such as APS?s renewable energy portfolio increases the demand for renewable power will increase. The Hopi Tribe would be in a good position to provide a percentage of the power through wind energy. It is equally important that the Hopi Tribe begin a dialogue with APS and NTUA to purchase the 69Kv transmission on Hopi and begin looking into financing options to purchase the line.

  17. Solid-State Fault Current Limiter Development : Design and Testing Update of a 15kV SSCL Power Stack

    SciTech Connect (OSTI)

    Dr. Ram Adapa; Mr. Dante Piccone

    2012-04-30T23:59:59.000Z

    ABSTRACT The Solid-State Fault Current Limiter (SSCL) is a promising technology that can be applied to utility power delivery systems to address the problem of increasing fault currents associated with load growth. As demand continues to grow, more power is added to utility system either by increasing generator capacity or by adding distributed generators, resulting in higher available fault currents, often beyond the capabilities of the present infrastructure. The SSCL is power-electronics based equipment designed to work with the present utility system to address this problem. The SSCL monitors the line current and dynamically inserts additional impedance into the line in the event of a fault being detected. The SSCL is based on a modular design and can be configured for 5kV through 69kV systems at nominal current ratings of 1000A to 4000A. Results and Findings This report provides the final test results on the development of 15kV class SSCL single phase power stack. The scope of work included the design of the modular standard building block sub-assemblies, the design and manufacture of the power stack and the testing of the power stack for the key functional tests of continuous current capability and fault current limiting action. Challenges and Objectives Solid-State Current Limiter technology impacts a wide spectrum of utility engineering and operating personnel. It addresses the problems associated with load growth both at Transmission and Distribution class networks. The design concept is pioneering in terms of developing the most efficient and compact power electronics equipment for utility use. The initial test results of the standard building blocks are promising. The independent laboratory tests of the power stack are promising. However the complete 3 phase system needs rigorous testing for performance and reliability. Applications, Values, and Use The SSCL is an intelligent power-electronics device which is modular in design and can provide current limiting or current interrupting capabilities. It can be applied to variety of applications from distribution class to transmission class power delivery grids and networks. It can also be applied to single major commercial and industrial loads and distributed generator supplies. The active switching of devices can be further utilized for protection of substation transformers. The stress on the system can be reduced substantially improving the life of the power system. It minimizes the voltage sag by speedy elimination of heavy fault currents and promises to be an important element of the utility power system. DOE Perspective This development effort is now focused on a 15kV system. This project will help mitigate the challenges of increasing available fault current. DOE has made a major contribution in providing a cost effective SSCL designed to integrate seamlessly into the Transmission and Distribution networks of today and the future. Approach SSCL development program for a 69kV SSCL was initiated which included the use of the Super GTO advanced semiconductor device which won the 2007 R&D100 Award. In the beginning, steps were identified to accomplish the economically viable design of a 69kV class Solid State Current Limiter that is extremely reliable, cost effective, and compact enough to be applied in urban transmission. The prime thrust in design and development was to encompass the 1000A and the 3000A ratings and provide a modular design to cover the wide range of applications. The focus of the project was then shifted to a 15kV class SSCL. The specifications for the 15kV power stack are reviewed. The design changes integrated into the 15kV power stack are discussed. In this Technical Update the complete project is summarized followed by a detailed test report. The power stack independent high voltage laboratory test requirements and results are presented. Keywords Solid State Current Limiter, SSCL, Fault Current Limiter, Fault Current Controller, Power electronics controller, Intelligent power-electronics Device, IED

  18. ETM (Distribution Network Automation on 10 kV cable line stations...

    Open Energy Info (EERE)

    will be equipped by RTUs, to provide remote observability and remote control. The communication (connection) is established via GSM network. References "EU Smart Grid...

  19. Aalborg Universitet Line Differential Protection Scheme Modelling for Underground 420 kV Cable Systems

    E-Print Network [OSTI]

    Bak, Claus Leth

    alternating current) cable system, a detailed approach to EMTDC/PSCAD modelling of protective relays configuration of the protective relaying. The present paper describes modelling methodology on the basis differential protection, XLPE HVAC cable, EMTDC/PSCAD relay model, SIPROTEC 4 7SD522, 7SD610. 1. Introduction

  20. Microsoft Word - Deering Lake-Eckley 115-kV Transmission Line...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    window washing, lawn mowing, trash collection, painting, and snow removal). Routine maintenance activities, corrective (that is, repair), preventive, and predictive, are...

  1. Bouse Hills Pumping Plant to Harcuvar 115-kV Transmission Line

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    areas, and other water sources that are vital in a region); and X (vii) Tundra, coral reefs, or rain forests.; or X (5) Involve genetically engineered organisms, synthetic...

  2. Mead-Liberty 345-kV Transmission Line Access Road Maintenance...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    areas, and other water sources that are vital in a region); and X (vii) Tundra, coral reefs, or rain forests.; or X (5) Involve genetically engineered organisms, synthetic...

  3. EIS-0100: Liberty-Coolidge 230-kV Transmission Line, Arizona

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy’s Western Area Power Administration prepared this statement to assess the potential environmental and socioeconomic implications of various alternatives associated with an upgrade of electrical transmission capability between the Liberty and Coolidge Substations.

  4. EIS-0129: New England/Hydro-Quebec 450 kV Transmission Line Interconnection- Phase II

    Broader source: Energy.gov [DOE]

    The Economic Regulatory Administration issued this EIS to explore the impacts of amending Presidential Permit PP-76 to allow the Vermont Electrical Company to operate at power levels above those stipulated in the permit and to build additional transmission facilities to distribute the increased power.

  5. EIS-0011: New Melones 230-kV Electrical Transmission Line, Central Valley Project, California

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy's Western Area Power Administration prepared this statement to evaluate the environmental impacts of proposed development of an electrical transmission system for the New Melones Power Plant.

  6. EIS-0505: Vantage to Pomona Heights 230 kV Transmission Line Project;

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels DataDepartment of Energy Your Density Isn't Your Destiny:Revised FindingDepartmentDepartmentStatement | Department ofDepartmentDepartment

  7. Cameron to Milford-138kV Transmission Line | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand Jump to:EzfeedflagBiomassSustainableCSL GasPermits Manual Jump to:(RECP) inCounty, Texas:Cameron to

  8. ETM (Distribution Network Automation on 10 kV cable line stations) (Smart

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand JumpConceptual Model,DOE FacilityDimondale,South, NewDyerTier2 Submit

  9. 150-kV, 80-A SOLID STATE POWER SUPPLY FOR NEUTRAL BEAM INJECTION

    E-Print Network [OSTI]

    Owren, H.

    2011-01-01T23:59:59.000Z

    owned rig 150-kV, 80-A SOLID STATE POWER SUPPLY FOR NEUTRALpaper describes an all solid state power supply designed forment and arc power supplies are also solid state. With the

  10. A SCR SWITCHED CAPACITOR VOLTAGE REGULATOR FOR 150 kV NEUTRAL BEAM POWER SUPPLY

    E-Print Network [OSTI]

    Milnes, K.A.

    2011-01-01T23:59:59.000Z

    et a1. , "150-kV, 80-A Solid State Power Supply for Neutral100% solid state and provides 1% regulation at power levelssolid state high voltage re- gulator. The block diagram of the power

  11. Blythe-Knob\t161-kV\tTransmission\tLine Cross\tArm\tReplacements\t...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    9 Blythe-Knob 161-kV Transmission Line Cross Arm Replacements - Continuation Sheet Project Description (continued) The wood cross arms on a number of wood H-frame structures have...

  12. A 25 KV/10A PULSER FOR DRIVING A HIGH-POWER PIERCE ELECTRON GUN

    E-Print Network [OSTI]

    of short-circuits. Since the current capability of the tetrode is of the order of 10 A in the case of a short-circuit, the limit of the charging voltage is up to a maximum of 25 kV. The pulsed system has.0 A current and 10.0 kV beam voltage. Key words hard-tube pulser, Pierce electron gun, microwave tube

  13. SU-E-J-245: Is Off-Line Adaptive Radiotherapy Sufficient for Head and Neck Cancer with IGRT?

    SciTech Connect (OSTI)

    Li, Z [the 6th People's Hospital of Shanghai Jiaotong University, Shanghai, Shanghai (China); Cleveland Clinic, Cleveland, OH (United States); Shang, Q; Liu, H; Greskovich, J; Koyfman, S; Xia, P [Cleveland Clinic, Cleveland, OH (United States)

    2014-06-01T23:59:59.000Z

    Purpose: Radiation doses delivered to patients with head and neck cancer (HN) may deviate from the planned doses because of variations in patient setup and anatomy. This study was to evaluate whether off-line Adaptive Radiotherapy (ART) is sufficient. Methods: Ten HN patients, who received IMRT under daily imaging guidance using CT-on-rail/KV-CBCT, were randomly selected for this study. For each patient, the daily treatment setup was corrected with translational only directions. Sixty weekly verification CTs were retrospectively analyzed. On these weekly verification CTs, the tumor volumes and OAR contours were manually delineated by a physician. With the treatment iso-center placed on the verification CTs, according to the recorded clinical shifts, the treatment beams from the original IMRT plans were then applied to these CTs to calculate the delivered doses. The electron density of the planning CTs and weekly CTs were overridden to 1 g/cm3. Results: Among 60 fractions, D99 of the CTVs in 4 fractions decreased more than 5% of the planned doses. The maximum dose of the spinal cord exceeded 10% of the planned values in 2 fractions. A close examination indicated that the dose discrepancy in these 6 fractions was due to patient rotations, especially shoulder rotations. After registering these 6 CTs with the planning CT allowing six degree of freedoms, the maximum rotations around 3 axes were > 1.5° for these fractions. With rotation setup errors removed, 4 out of 10 patients still required off-line ART to accommodate anatomical changes. Conclusion: A significant shoulder rotations were observed in 10% fractions, requiring patient re-setup. Off-line ART alone is not sufficient to correct for random variations of patient position, although ART is effective to adapt to patients' gradual anatomic changes. Re-setup or on-line ART may be considered for patients with large deviations detected early by daily IGRT images. The study is supported in part by Siemens Medical Solutions.

  14. Further Notice of 230kV Circuit Planned Outages | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels DataDepartment of Energy Your Density Isn't YourTransport inEnergy0.pdfTechnologies ProgramOutfittedof6 * September 2005Further Notice

  15. Notification of Planned 230kV Outage at Potomac River Generating Station

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels DataDepartment of Energy Your Density Isn'tOrigin of Contamination in ManyDepartment of Energy NorthB O N N789266 FederalJuly 6, 2006

  16. Notification of Planned 230kV Outage at Potomac River Generating Station |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels DataDepartment of Energy Your Density Isn'tOrigin of Contamination in ManyDepartment of Energy NorthB O N N789266 FederalJuly 6,

  17. Notification of Planned 230kV Outage at Potomac River Generating Station |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels DataDepartment of Energy Your Density Isn'tOrigin of Contamination in ManyDepartment of Energy NorthB O N N789266 FederalJuly

  18. Notification of Planned 230kV Outage at Potomac River Generating Station |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels DataDepartment of Energy Your Density Isn'tOrigin of Contamination in ManyDepartment of Energy NorthB O N N789266 FederalJulyDepartment

  19. Notification of Planned 230kV Outage at Potomac River Generating Station |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels DataDepartment of Energy Your Density Isn'tOrigin of Contamination in ManyDepartment of Energy NorthB O N N789266

  20. Notification of Planned 230kV Outage at Potomac River Generating Station |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page onYouTube YouTube Note: Since the.pdfBreaking ofOilNEW HAMPSHIREofNewsletterEnergySeptember 16,

  1. Notification of Planned 230kV Outage at Potomac River Generating Station |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page onYouTube YouTube Note: Since the.pdfBreaking ofOilNEW HAMPSHIREofNewsletterEnergySeptember 16,Department of

  2. Notification of Planned 230kV Outage at Potomac River Generating Station |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page onYouTube YouTube Note: Since the.pdfBreaking ofOilNEW HAMPSHIREofNewsletterEnergySeptember 16,Department ofDepartment

  3. Notification of Planned 230kV Outage at Potomac River Generating Station |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page onYouTube YouTube Note: Since the.pdfBreaking ofOilNEW HAMPSHIREofNewsletterEnergySeptember 16,Department

  4. Docket No. EO-05-01: Further Notice of 230kV Circuit Planned Outages |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels DataDepartment of Energy Your Density Isn't Your Destiny:Revised Finding of No53197E T ADRAFTJanuary 2004April 2015 <Department of

  5. Docket No. EO-05-01: Further Notice of 230kV Circuit Planned Outages |

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742Energy China 2015 Business42.1Energy | DepartmenttheFebruary 13, 2013 meeting

  6. Planning and Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Rates Planning Ten-Year Capital Program Projects Lovell-Yellowtail Transmission Line Rebuild project Studies WACM Wind production summary overview (Oct. 2006)...

  7. 15-kV Single-Bias All-Optical ETO Thyristor A. Mojab and S.K. Mazumder

    E-Print Network [OSTI]

    Mazumder, Sudip K.

    15-kV Single-Bias All-Optical ETO Thyristor A. Mojab and S.K. Mazumder Laboratory for Energy 15 kV single bias and a current of 10 A. This ETO is completely controlled by two optical signals, one for the 15 kV SiC gate- turn-off (GTO) thyristor and the other one for a triggering low- voltage

  8. Field Demonstration of a 24-kV Superconducting Cable at Detroit Edison

    SciTech Connect (OSTI)

    Kelley, Nathan; Corsaro, Pietro

    2004-12-01T23:59:59.000Z

    Customer acceptance of high temperature superconducting (HTS) cable technology requires a substantial field demonstration illustrating both the system's technical capabilities and its suitability for installation and operation within the utility environment. In this project, the world's first underground installation of an HTS cable using existing ductwork, a 120 meter demonstration cable circuit was designed and installed between the 24 kV bus distribution bus and a 120 kV-24 kV transformer at Detroit Edison's Frisbie substation. The system incorporated cables, accessories, a refrigeration system, and control instrumentation. Although the system was never put in operation because of problems with leaks in the cryostat, the project significantly advanced the state-of-the-art in the design and implementation of Warm Dielectric cable systems in substation applications. Lessons learned in this project are already being incorporated in several ongoing demonstration projects.

  9. Development of a thyristor valve for next generation 500kV HVDC transmission systems

    SciTech Connect (OSTI)

    Hasegawa, T. [Kansai Electric Power Co., Inc., Osaka (Japan)] [Kansai Electric Power Co., Inc., Osaka (Japan); Yamaji, K. [Shikoku Electric Power Co., Inc., Takamatsu (Japan)] [Shikoku Electric Power Co., Inc., Takamatsu (Japan); Irokawa, H. [Electric Power Development Co., Ltd., Tokyo (Japan)] [Electric Power Development Co., Ltd., Tokyo (Japan); Shirahama, H.; Tanaka, C.; Akabane, K.

    1996-10-01T23:59:59.000Z

    A high voltage thyristor valve is the basic component of an HVDC transmission system. Development of a 500kV valve for next generation HVDC transmission systems is described. First, the power loss of the valve is analyzed to decide a reasonable wafer size for the light triggered thyristor. From these results, a six inch diameter wafer size is selected. The light triggered thyristor, with ratings of 8kV and 3.5kA, is developed using the six inch wafer. The designing of the valve employing the thyristor and test results with the prototype valve prove that a 500kV valve can be realized by the design method.

  10. EA-1960: Townsite Solar Project Transmission Line, Clark County, Nevada

    Broader source: Energy.gov [DOE]

    The Bureau of Land Management, with Western Area Power Administration as a cooperating agency, prepared an EA to evaluate potential impacts of a proposal to build and operate a 180-MW photovoltaic facility; a 220, 230, or 500 kV transmission line; and associated facilities in Clark County, Nevada.

  11. EIS-0124: Conrad-Shelby Transmission Line Project, Montana

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy's Western Area Power Administration developed this statement to assess the environmental impact of adding a 230 kV transmission line between Conrad and Shelby, Montana and a new substation near Shelby to update the stressed electrical transmission system.

  12. EIS-0090: Fort Peck-Havre Transmission Line Project, Montana

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy’s Western Area Power Administration prepared this statement to assess the potential environmental and socioeconomic implications of its proposed action to construct and operate a 230kV transmission line from Fort Peck to Havre, Montana, with three intermediate interconnecting substations.

  13. Kangley-Echo Lake Transmission Line Project Final Environmental Impact Statement

    SciTech Connect (OSTI)

    N /A

    2003-06-20T23:59:59.000Z

    BPA proposes to build a single-circuit 500-kV transmission line from a tap point on an existing 500-kV line near Kangley, Washington, to its Echo Lake Substation near North Bend, Washington. The proposed route for this line, also called Alternative 1, is about nine miles long. About five miles of the proposed route would go through the Cedar River Municipal Watershed. In addition, Echo Lake Substation would be expanded about three acres to the east and new equipment would be installed there to accommodate the new line (common to all transmission alternatives). This alternative was proposed because it would be located immediately parallel to an existing BPA existing 500-kV transmission line, the Raver-Echo Lake Transmission Line. Locating a new line next to an existing one reduces right-of-way (ROW) clearing needed for the new line and reduces the need for additional access roads. Lattice steel transmission towers would support the 500-kV transmission line. These structures average 135 feet high, with the average span between towers of about 1,150 feet.

  14. Development of 275kV gas cooled type gas-insulated power transformer

    SciTech Connect (OSTI)

    Kudo, A.; Nishitani, T.; Yoshikawa, T. (Mitsubishi Electric Corp., Ako (Japan)); Wan, C.T. (Hongkong Electric Co., Ltd. (Hong Kong))

    1993-01-01T23:59:59.000Z

    A world's first 275kV gas cooled type gas insulated power transformer with a low sound level ideal for urban area, which depends on SF6 gas alone for both insulation and cooling, was developed and has been put into commercial service since 1990 in Hong Kong. This paper presents the design philosophy, the principal technical items, the rating and the feature of 275kV 30MVA transformer, the performance test results, and the long term energization test result of the transformer.

  15. Uranium Mill Tailings Remedial Action Project Environmental Line Management Audit Action Plan. Final report. Audit, October 26, 1992--November 6, 1992

    SciTech Connect (OSTI)

    NONE

    1993-07-01T23:59:59.000Z

    This Action Plan contains responses, planned actions, and estimated costs for addressing the findings discovered in the Environmental Management Audit conducted for the U.S. Department of Energy (DOE) Uranium Mill Tailings Remedial Action Project (UMTRA), October 26 through November 6, 1992. This document should be read in conjunction with the Audit Report to ensure the findings addressed in this document are fully understood. The scope of the UMTRA Environmental Management Audit was comprehensive and encompassed all areas of environmental management except environmental programs pertaining to the National Environmental Policy Act (NEPA) compliance. The Audit Report listed 18 findings: 11 were identified as compliance findings, and the remaining 7 were best management practice findings. Root cause analysis was performed on all the findings. The results of the analysis as well as planned corrective actions are summarized in Section 5.0. All planned actions were prioritized using the Tiger Team Assessment Corrective Action Plan system. Based on assigned priorities, all planned actions were costed by fiscal year. This Action Plan contains a description of the organizational and management structures to be used to implement the Action Plan, a brief discussion of root cause analysis and funding, followed by the responses and planned actions for each finding. A member of the UMTRA Project Office (PO) has been assigned responsibility for tracking the progress on each of the findings. The UMTRA PO staff wrote and/or approved all of the corrective actions recorded in this Action Plan.

  16. EA-1617: Lovell-Yellowtail and Basin-Lovell Transmission Line Rebuild Project, Big Horn County, Wyoming, and Big Horn and Carbon Counties, Montana

    Broader source: Energy.gov [DOE]

    DOE’s Western Area Power Administration prepared this EA and a finding of no significant impact for a proposal to rebuild the Lovell-Yellowtail (LV-YT) No. 1 and No. 2 115-kV transmission lines, located in Big Horn County, Wyoming, and Big Horn and Carbon Counties in Montana, and the Basin-Lovell 115-kV transmission line in Big Horn County, Wyoming.

  17. Electric power high-voltage transmission lines: Design options, cost, and electric and magnetic field levels

    SciTech Connect (OSTI)

    Stoffel, J.B.; Pentecost, E.D.; Roman, R.D.; Traczyk, P.A.

    1994-11-01T23:59:59.000Z

    This report provides background information about (1) the electric and magnetic fields (EMFs) of high-voltage transmission lines at typical voltages and line configurations and (2) typical transmission line costs to assist on alternatives in environmental documents. EMF strengths at 0 {+-} 200 ft from centerline were calculated for ac overhead lines, and for 345 and 230-kV ac underground line and for a {+-}450-kV dc overhead line. Compacting and height sensitivity factors were computed for the variation in EMFs when line conductors are moved closer or raised. Estimated costs for the lines are presented and discussed so that the impact of using alternative strategies for reducing EMF strengths and the implications of implementing the strategies can be better appreciated.

  18. A charge-pump 60kV modulator for the ISOLDE target extraction voltage

    E-Print Network [OSTI]

    Barlow, R A; Fowler, A; Gaudillet, H; Gharsa, T; Schipper, J

    2015-01-01T23:59:59.000Z

    The ISOLDE facility at CERN provides radioactive ion beams to a number of experimental stations. These ions are produced by a metal target, floating at 60 kV, which is impacted by a 1.4 GeV high intensity proton beam. The ions are then accelerated by a grounded extraction electrode to 60 keV, before transport to the experimental area. During proton beam impact extremely high ionisation of the volume around the target gives rise to significant leakage current which results in loss of charge on the effective target capacitance of approximately 6 nF. If short life-time isotopes are to be studied, the 60 kV must be re-established within a maximum of 10 ms. Recharging the target capacitance to 60 kV and to the required stability of better than 10-4 precludes a direct charging system and an alternative method of re-establishing the 60 kV is used. The present system [1], in operation since 1991, employs a resonant circuit which is triggered 35 µs prior to beam impact. This circuit transfers the charge on the effec...

  19. EIS-0507: Boardman-Hemingway Transmission Line, Oregon and Idaho

    Broader source: Energy.gov [DOE]

    The Bureau of Land Management and the U.S. Forest Service are preparing, with DOE’s Bonneville Power Administration (BPA) as a cooperating agency, an EIS that evaluates the potential environmental impacts of a proposal to construct about 305 miles of 500-kV transmission line from northeast Oregon to southwest Idaho. BPA’s proposed action is to partially fund part the transmission line.

  20. Management Plan Management Plan

    E-Print Network [OSTI]

    Plan, Management Plan Page MP­ 1 #12;Management Plan water quality standards, instream flows, privateManagement Plan Management Plan "Management and restoration programs for native salmonids have communities" J. Lichatowich et al. 1998. A Conceptual Foundation for the Management of Native Salmonids

  1. Development of 500 kV DC PPLP-insulated oil-filled submarine cable

    SciTech Connect (OSTI)

    Fujimori, A. [Kansai Electric Power Co., Inc., Osaka (Japan)] [Kansai Electric Power Co., Inc., Osaka (Japan); Tanaka, T. [Electric Power Development Co., Ltd., Tokyo (Japan)] [Electric Power Development Co., Ltd., Tokyo (Japan); Takashima, H. [Shikoku Electric Power Co., Inc., Kagawa (Japan)] [Shikoku Electric Power Co., Inc., Kagawa (Japan); Imajo, T. [Central Research Inst. of Electric Power Industry, Tokyo (Japan)] [Central Research Inst. of Electric Power Industry, Tokyo (Japan); Hata, R. [Sumitomo Electric Industries, Ltd., Osaka (Japan)] [Sumitomo Electric Industries, Ltd., Osaka (Japan); Tanabe, T. [Furukawa Electric Co., Ltd., Tokyo (Japan)] [Furukawa Electric Co., Ltd., Tokyo (Japan); Yoshida, S. [Fujikura, Ltd., Tokyo (Japan)] [Fujikura, Ltd., Tokyo (Japan); Kakihana, T. [Hitachi Cable, Ltd., Tokyo (Japan)] [Hitachi Cable, Ltd., Tokyo (Japan)

    1996-01-01T23:59:59.000Z

    This paper outlines the development of a 500 kV DC oil-filled submarine cable capable of transmitting 2,800 MW with {+-} 500 kV 2800A bipole system. Polypropylene Laminated Paper (PPL) was employed as the insulation material, which is the worlds first application to DC cables. The conductor size is 3,000 mm{sup 2}, which is the largest size for submarine cables ever put into practical use. Through various fundamental and prototype tests, the cable proved to have excellent electrical characteristics for DC voltage as well as transient overvoltage. The cable and accessories are currently undergoing a long-term accelerated aging test as the final confirmation of their reliability and stability.

  2. The Cost of Transmission for Wind Energy: A Review of Transmission Planning Studies

    E-Print Network [OSTI]

    Mills, Andrew D.

    2009-01-01T23:59:59.000Z

    500 and 230 kV 765 kV and 800 kV HVDC 500 and 230 kV 500 kVmi) 138 and 345 kV 345 kV 345 kV 345 kV and HVDC 345kV and HVDC 345 kV 345 kV Note: Total transmission cost is

  3. A 6 kV arbitrary waveform generator for the Tevatron Electron Lens

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Pfeffer, H.; Saewert, G.

    2011-11-01T23:59:59.000Z

    This paper reports on a 6 kV modulator built and installed at Fermilab to drive the electron gun anode for the Tevatron Electron Lens (TEL). The TEL was built with the intention of shifting the individual (anti)proton bunch tunes to even out the tune spread among all 36 bunches with the desire of improving Tevatron integrated luminosity. This modulator is essentially a 6 kV arbitrary waveform generator that enables the TEL to define the electron beam intensity on a bunch-by-bunch basis. A voltage waveform is constructed having a 7 {micro}s duration that corresponds to the tune shift requirements of amore »12-bunch (anti)proton beam pulse train. This waveform is played out for any one or all three bunch trains in the Tevatron. The programmed waveform voltages transition to different levels at time intervals corresponding to the 395 ns bunch spacing. Thus, complex voltage waveforms can be played out at a sustained rate of 143 kHz over the full 6 kV output range. This paper describes the novel design of the inductive adder topology employing five transformers. It describes the design aspects that minimize switching losses for this multi-kilovolt, high repetition rate and high duty factor application.« less

  4. Measurements on a FET based 1 MHz, 10 kV pulse generator

    SciTech Connect (OSTI)

    Wait, G.D.; Barnes, M.J.

    1995-08-01T23:59:59.000Z

    A prototype pulser, which incorporates thirty-two 1 kV Field-Effect Transistor (FET) modules, has been built and tested at TRIUMF. The pulser has been developed for application in a scheme for pulsed extraction from the TRIUMF 500 MeV cyclotron. Deflection of the beam will be provided by an electric field between a set of 1 in long deflector plates. The pulser generates a continuous, unipolar, pulse train at a fundamental frequency of approximately 1 MHz and a magnitude of 10 kV. The pulses have 38 ns rise and fall times and are stored on a low-loss coaxial cable which interconnects the pulse generator and the deflector plates. The circuit performance was evaluated with the aid of PSpice in the design stage and confirmed by measurements on the prototype. Temperature measurements have been performed on 1 kV FET modules under DC conditions and compared with temperatures under operating conditions to ensure that switching losses are acceptable. Results of various measurements are presented and compared with simulations.

  5. A 6 kV arbitrary waveform generator for the Tevatron Electron Lens

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Pfeffer, H.; Saewert, G.

    2011-11-01T23:59:59.000Z

    This paper reports on a 6 kV modulator built and installed at Fermilab to drive the electron gun anode for the Tevatron Electron Lens (TEL). The TEL was built with the intention of shifting the individual (anti)proton bunch tunes to even out the tune spread among all 36 bunches with the desire of improving Tevatron integrated luminosity. This modulator is essentially a 6 kV arbitrary waveform generator that enables the TEL to define the electron beam intensity on a bunch-by-bunch basis. A voltage waveform is constructed having a 7 {micro}s duration that corresponds to the tune shift requirements of a 12-bunch (anti)proton beam pulse train. This waveform is played out for any one or all three bunch trains in the Tevatron. The programmed waveform voltages transition to different levels at time intervals corresponding to the 395 ns bunch spacing. Thus, complex voltage waveforms can be played out at a sustained rate of 143 kHz over the full 6 kV output range. This paper describes the novel design of the inductive adder topology employing five transformers. It describes the design aspects that minimize switching losses for this multi-kilovolt, high repetition rate and high duty factor application.

  6. Cost comparison of 138 kV relay at TSS Natoma

    SciTech Connect (OSTI)

    Whetter, A.J. [ComEd, Chicago, IL (United States)

    1996-10-01T23:59:59.000Z

    This paper compares the costs of retro-fitting an electro-mechanical directional comparison blocking scheme with a microprocessor based dual directional comparison and under-reaching direct transfer tripping scheme on an existing panel at a 138 kV substation. Comparison is between the material, fabrication, engineering, drafting, construction, and testing costs. The cost per function of each scheme will be defined and compared. The results of this comparison will demonstrate the advantages of the new microprocessor based schemes in material costs, labor costs, and cost per function.

  7. Failure evaluation of underground high voltage cables (115 kV) in Mazatlan, Sinaloa: Microscopic method

    SciTech Connect (OSTI)

    Valero-Huerta, M.A.; Ramirez-Delgado, R. [Lab. de Pruebas de Equipos y Materiales, Irapuato (Mexico)

    1995-11-01T23:59:59.000Z

    The present paper is a complete analysis of the failure which occurred to the 115 kV power cable installed between the Mazatlan Centro and Mazatlan Norte Substations. Laboratory analysis that established the causes of the failure are included. It was concluded that the failure of the cable was provoked by the entrance of sewage water to the screen, and due to the presence of anaerobic organisms, resulted in the formation of sulfidic acid, which caused the severe corrosion that can be observed in the screen. The resulting loss of conductivity provoked heating capable of melting the isolator until its rupture.

  8. Operating characteristics and modeling of the LLNL 100-kV electric gun

    SciTech Connect (OSTI)

    Osher, J.E.; Barnes, G.; Chau, H.H.; Lee, R.S.; Lee, C.; Speer, R.; Weingart, R.C.

    1989-06-01T23:59:59.000Z

    In the electric gun, the explosion of an electrically heated metal foil and the accompanying magnetic forces drive a thin flyer plate up a short barrel. Flyer velocities of up to 18 km/s make the gun useful for hypervelocity impact studies. The authors briefly review the technological evolution of the exploding-metal circuit elements that power the gun, describe the 100-kV electric gun designed at Lawrence Livermore National Laboratory (LLNL) in some detail, and present the general principles of electric gun operation. They compare the experimental performance of the LLNL gun with a simple model and with predictions of a magnetohydrodynamics code.

  9. KvH Projekt GmbH Co KG | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand Jump to: navigation, searchOf Kilauea Volcano, Hawaii9969995°,I Jump to:Kumagai Gumi CoKuwaitKvH

  10. Emergency Management Lines of Inquiry, April 2008

    Broader source: Energy.gov (indexed) [DOE]

    Inspection Criteria, Activities, and Lines of Inquiry Functional Area: Hazards Survey (HS) and Emergency Planning Hazards Assessment (EPHA) Inspection Criteria: Emergency...

  11. EA-1967: Hills Creek-Lookout Point Transmission Line Rebuild, Lane County, Oregon

    Broader source: Energy.gov [DOE]

    Bonneville Power Administration is preparing an EA to assess potential environmental impacts of the proposed rebuild of its 26-mile 115 kilovolt (kV) wood-pole Hills Creek-Lookout Point transmission line, which is generally located between Lowell and Oakridge, in Lane County, Oregon.

  12. EA-1961: Kalispell-Kerr Transmission Line Rebuild Project, Kalispell and Polson, Montana

    Broader source: Energy.gov [DOE]

    Bonneville Power Administration is preparing an EA to evaluate potential environmental impacts of rebuilding its 41-mile long 115 kilovolt (kV) wood-pole Kalispell-Kerr transmission line between Kalispell and Polson, Montana. Additional information is available on the project website, http://efw.bpa.gov/environmental_services/Document_Library/KALISPELL_KERR/.

  13. EA-1950: Grand Coulee-Creston Transmission Line Rebuild; Grant and Lincoln Counties, Washington

    Broader source: Energy.gov [DOE]

    Bonneville Power Administration prepared this EA to evaluate potential environmental impacts of rebuilding approximately 28 miles of the Grand Coulee-Creston No. 1 115-kilovolt (kV) transmission line between Coulee Dam in Grant County and Creston in Lincoln County, Washington.

  14. Author's Copy: J.B. Bancroft, A. Morrison, G. Lachapelle, Validation of GNSS under 500,000 V Direct Current (DC) transmission lines, Computers and Electronics in Agriculture, Volume 83, April 2012, Pages 58-67, ISSN 0168-1699, 10.1016/j.compag.2012.01.013

    E-Print Network [OSTI]

    Calgary, University of

    masking by the towers. Tests were conducted under a set of three transmission lines, two 500 kV DC lines Current (DC) transmission lines, Computers and Electronics in Agriculture, Volume 83, April 2012, Pages 58 Validation of GNSS under 500,000 Volt Direct Current (DC) Transmission Lines J.B. Bancroft*, A. Morrison

  15. EIS-0079: 300-kV International Submarine Transmission Line- Erie, Pennsylvania to Nanticoke, Ontario, Canada General Public Utilities Corporation

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy Office of Energy Emergency Operations developed this statement to assess the potential environmental and socioeconomic impacts of the construction and operation of 44 miles of cable between the Erie West Substation and the Canadian border.

  16. Commissioning and Operation of 130kV/130A Switched-Mode HV Power Supplies with the Upgraded JET Neutral Beam Injectors

    E-Print Network [OSTI]

    Commissioning and Operation of 130kV/130A Switched-Mode HV Power Supplies with the Upgraded JET Neutral Beam Injectors

  17. 1.9 kV AlGaN/GaN Lateral Schottky Barrier Diodes on Silicon

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Zhu, Mingda [University of Notre Dame, IN (United States); Song, Bo [Cornell University, Ithaca, NY (United States); Qi, Meng [University of Notre Dame, IN (United States); Hu, Zongyang [University of Notre Dame, IN (United States); Nomoto, Kazuki [University of Notre Dame, IN (United States); Yan, Xiaodong [University of Notre Dame, IN (United States); Cao, Yu [IQE, Westborough, MA (United States); Johnson, Wayne [IQE, Westborough, MA (United States); Kohn, Erhard [University of Notre Dame, IN (United States); Jena, Debdeep [Cornell University, Ithaca, NY (United States); Xing, Grace Huili [Cornell University, Ithaca, NY (United States)

    2015-04-01T23:59:59.000Z

    In this letter, we present AlGaN/GaN lateral Schottky barrier diodes on silicon with recessed anodes and dual field plates. A low specific on-resistance RON,SP (5.12 m?{center_dot}cm2), a low turn-on voltage (1.9 kV), were simultaneously achieved in devices with a 25 ?m anode/cathode separation, resulting in a power figure-of-merit (FOM) BV2/RON,SP of 727 MW{center_dot}cm2. The record high breakdown voltage of 1.9 kV is attributed to the dual field plate structure.

  18. Straight-line separation of two polyhedra

    E-Print Network [OSTI]

    Wang, Su-Hua

    1992-01-01T23:59:59.000Z

    1992 ABSTRACT Straight-line Separation of Two Polyhedra. (December 1992) Su-Hua Wang, B. S. , National Chiao Tung University, Taiwan, R. O. C Chair of Advisory Committee: Dr. Jan Wolter The development of automated assembly planning systems has... INTRODUCTION I. A Context Assembly planning is the plan generation problem for assembly tasks and plays an important role in manufacturing systems. The goal of the assembly planning process is to find a plan for moving a set of parts which are initially...

  19. Fort Peck-Havre transmission line project, Hill, Blaine, Phillips, Valley and McCone Counties, Montana

    SciTech Connect (OSTI)

    Not Available

    1982-09-01T23:59:59.000Z

    Construction and operation of a 180-mile, 230-kilovlt (kV) transmission line between Fort Peck and Havre, Montana is proposed to provide a replacement for the 161-kV line that currently runs between the two cities. The new line would be carried on woodpole, H-frame structures. The existing 161-kV line would be removed, and the Richardson Coulee Substation would be relocated. Intermediate facilities to be improved would include the Fort Peck Switchyard and the Richardson Coulee, Malta, Harlem, and Havre substations.Construction of the line would commence in August 1983, and operation would commence in January 1986. The expected life of the transmission system would be 100 years. Estimated cost of the project, in 1983 dollars, is $36.1 million. The project would upgrade an essential element of the Western Area Power Administration's electric power system and the Montana Power Company's interconnected transmission network. Continued electric service reliability would be improved, and safety conditions affecting personnel who maintain the line would be enhanced. Additional transmission capacity would be provided to accommodate future load growth, precluding the need for multiple transmission lines. The line would eleminate seven acres of productive land and create physical conflicts with present and future agricultural activities. The line would traverse areas characterized by concentrations of archaeological resources and cultural resources of importance to native Americans. Transmission structures could mar scenery in areas with historically significant architecture and would interfere with waterfowl.

  20. A New 500-kV Ion Source Test Stand for HIF

    SciTech Connect (OSTI)

    Sangster, T.C.; Ahle, L.E.; Halaxa, E.F.; Karpenko, V.P.; Oldaker, M. E.; Mitchell, J.W.; Beck, D.N.; Bieniosek, F.M.; Henestroza, E.; Kwan, J.W.

    2000-10-05T23:59:59.000Z

    One of the most challenging aspects of ion beam driven inertial fusion energy is the reliable and efficient generation of low emittance, high current ion beams. The primary ion source requirements include a rise time of order 1-msec, a pulse width of at least 20-msec, a flattop ripple of less than 0.1% and a repetition rate of at least 5-Hz. Naturally, at such a repetition rate, the duty cycle of the source must be greater than 108 pulses. Although these specifications do not appear to exceed the state-of-the-art for pulsed power, considerable effort remains to develop a suitable high current ion source. Therefore, we are constructing a 500-kV test stand specifically for studying various ion source concepts including surface, plasma and metal vapor arc. This paper will describe the test stand design specifications as well as the details of the various subsystems and components.

  1. Evaluation of Instrumentation and Dynamic Thermal Ratings for Overhead Lines

    SciTech Connect (OSTI)

    Phillips, A.

    2013-01-31T23:59:59.000Z

    In 2010, a project was initiated through a partnership between the Department of Energy (DOE) and the New York Power Authority (NYPA) to evaluate EPRI?s rating technology and instrumentation that can be used to monitor the thermal states of transmission lines and provide the required real-time data for real-time rating calculations. The project included the installation and maintenance of various instruments at three 230 kV line sites in northern New York. The instruments were monitored, and data collection and rating calculations were performed for about a three year period.

  2. EIS-0450: TransWest Express 600 kV Direct Current Transmission Project in Wyoming, Colorado, Utah, and Nevada

    Broader source: Energy.gov [DOE]

    This EIS, being prepared jointly by DOE’s Western Area Power Administration and the Department of the Interior’s Bureau of Land Management (Wyoming State Office), evaluates the environmental impacts of granting a right-of-way for the TransWest Express 600-kilovolt Direct Current Transmission Project and amending a land use plan. The project consists of an overhead transmission line that would extend approximately 725 miles from south-central Wyoming, through Colorado and Utah. Western proposes to be a joint owner of the project. Additional information is available at http://www.blm.gov/wy/st/en/info/NEPA/documents/hdd/transwest.html.

  3. A novel voltage-gated potassium ion channel gene (Kv5.1): Molecular cloning and characterization

    SciTech Connect (OSTI)

    Beisel, K.W.; Lofton, N.C.; Kelley, P.M. Jr. [Boys Town National Research Hospital, Omaha, NE (United States)] [and others

    1994-09-01T23:59:59.000Z

    Voltage-activated potassium channels comprise a family of genes which play a role in the electrophysiological properties of neurosensory and neuronal tissue. We have recently identified a novel voltage-gated potassium ion channel (designated as Kv5.1) using the both RT-PCR with degenerative oligodeoxynucleotide primers and dideoxy sequence analyses. A full length sequence of the mature transcript was obtained by mRNA walking using gene-specific oligodeoxynucleotide primers. The deduced amino acid sequence suggested that this protein has six hydrophobic membrane spanning regions (S1-S6) and an ion-selective pore (P or H5) located between S5 and S6. This structural motif is found in other members of this gene family. Kv5.1 has an amino acid sequence homology of 55% with the Shab gene, Kv2.1, within the N-terminus and the membrane spanning regions. No sequence homology was found for the C-terminus. Northern analysis using mRNA isolated from a panel of rat tissues demonstrated that a 2.4 kb message was expressed in heart and cochlear tissue. Because of the low sequence homology and the unique tissue distribution, we have tentatively assigned the Kv5.1 gene as a new subfamily. Both the rat and human homologues were sequenced and the nucleotide and amino acid homologies were 88% and 96%, respectively. In the rat, the open reading frame encodes a 540-amino acid protein with a predicted molecular mass of 61,781 daltons. Interestingly, the human homologue is truncated by 83 residues in the C-terminus by a stop codon. We have recently isolated a human genomic {lambda} clone which contains the entire human gene and are now determining chromosomal location of Kv5.1 by in situ hybridization and PCR analysis of DNA from a panel of somatic cell hybrids.

  4. Abstract Number #10041 A 150kV/300A/1s COAXIAL BLUMLEIN PULSER

    E-Print Network [OSTI]

    . They consist of pieces of transmission lines charged in parallel , which discharge synchronously in series generators made of pieces of transmission lines and normally used in a great variety of applications

  5. NASA Benchmarks Communications Assessment Plan - Developed By...

    Broader source: Energy.gov (indexed) [DOE]

    COMMUNICATIONS Assessment Plan NNSANevada Site Office Facility Representative Division Performance Objective: Lines of authority are clearly defined with clear and open...

  6. Low stored energy 100 kV regulator for ion sources at LANSCE

    SciTech Connect (OSTI)

    Jacobson, E.G.; Haffner, R.L.; Ingalls, W.B.; Meyer, B.J.; Stelzer, J.E.

    1998-12-31T23:59:59.000Z

    To minimize accelerating column damage caused by uncontrolled energy release during arc-downs, it is desirable to minimize the available stored electrical energy. For the Los Alamos Neutron Science Center (LANSCE) H{sup {minus}} ion sources, the stored energy includes, in addition to the charge in the power supply output capacitance, the charge on the electronics racks. They are supported and insulated from ground by PVC pipe and have a capacitance to ground of approximately 900 pf. In 1988 (LANSCE) personnel designed a high-voltage current source using a low-stored-energy power supply and planar triode with the goal of eliminating uncontrolled release of charge stored in the power supply. Construction and testing were performed intermittently as resources permitted until 1993. When work on the Short Pulse Spallation Source (SPSS) started on the LANSCE Ion Source Test Stand (ISTS) it was recognized that a higher current power supply would be needed and work resumed on the regulator circuitry. A 120 kV power supply having low output capacitance, and a planar triode have been used to supply 40 mA, 120 Hz, 12% duty-factor current for the ISTS beam. The triode`s cathode current is controlled by circuitry operating both at power-supply voltage level and at ground level via a fiber optic link. Voltage droop is approximately 600 V during the 1 ms beam pulse. The authors present the status of the regulator and its special challenges.

  7. Performance characteristics of the Atlas 60 kV, 60 kJ plastic capacitors

    SciTech Connect (OSTI)

    Reass, W.; Bennet, G.; Bowman, D.; Lopez, E.; Monroe, M.; Parsons, W.

    1997-12-01T23:59:59.000Z

    This paper provides the performance data of Atlas plastic capacitors as supplied by Maxwell Technologies and Aerovox Corporation. The fiberglass cases at 13 inches high by 29 inches wide and 28 inches in depth with a 2 inch by 18 inch bushing on each end. Two styles of the 33.5uF capacitors have been evaluated for Atlas use, a conventional paper-foil and a self-healing metalized-paper and plastic dielectric design. A test program to capacitor failure, is being used to evaluate capacitor lifetime at full voltage (60 kV) and a nominal 15% reversal. With the Atlas parameters, peak currents of {approximately} 340 kA are realized. In anticipation of faults, capacitors are capable, specified, and tested for 700 kA performance. Accurate methods are also utilized to determine capacitor inductance, less than 20 nH. The results of the various capacitor testing programs will be presented in addition to future directives for their R and D efforts.

  8. The 345 kV underground/underwater Long Island Sound cable project

    SciTech Connect (OSTI)

    Grzan, J.; Hahn, E.I. (New York Power Authority, White Plains, NY (United States)); Casalaina, R.V.; Kansog, J.O.C. (Ebasco Services Inc., Lyndhurst, NJ (United States))

    1993-07-01T23:59:59.000Z

    A high voltage underground/underwater cable system was installed to increase the transmission capacity from the mainland of New York to Long Island. In terms of weight and diameter, the self-contained, fluid-filled (SCFF) cable used for the underwater portion of the project is the largest underwater cable in the world. The use of high-pressure, fluid-filled (HPFF) pipe-type cable on the land portion represents the largest application of paper-polypropylene-paper (PPP) insulated cable in the United States. State-of-the-art technologies were implemented in the use of fiber optic cables for relay protection and SCADA/RTU, temperature monitoring and leak detection systems, SF[sub 6] gas-insulated substations, and underwater cable laying and embedment techniques. This paper discusses the design and installation of a 750 MVA, 43 km (26.6 mi), 345 kV underground/underwater electric transmission system installed by the New York Power Authority (NYPA).

  9. ENGINEERING PHYSICS BSE Plan Requirements

    E-Print Network [OSTI]

    Shyy, Wei

    ENGINEERING PHYSICS BSE Plan Requirements 1 Campus: UMICH RG = Requirement Group Career: UENG RQ = Requirement Program: LN = Line Plan: 2990BSE RG 6394 ENGINEERING PHYSICS MAJOR REQUIREMENTS Effective FA12/1910 (09/04/2012) RQ 4925 Physics Technical Subjects (C or higher) Effective FA12/1910 (09/04/2012) LN 0010

  10. The Cost of Transmission for Wind Energy in the United States: A Review of Transmission Planning Studies.

    E-Print Network [OSTI]

    Wiser, Ryan

    2014-01-01T23:59:59.000Z

    kV JCSP 765 kV and 800 kV HVDC Southern California Edison (2 345 kV ERCOT - TOS - 3 345 kV and HVDC ERCOT - TOS - 4345 kV and HVDC Southwest Power Pool (SPP) SPP - 2 345 kV

  11. Development and laboratory testing of a 138-kV PPP-insulated joint for commercial application

    SciTech Connect (OSTI)

    Walldorf, S.P. (MAC Products, Inc., Kearny, NJ (US)); Chu, H.; Elbadaly, H. (Consolidated Edison Co. of New York, Inc., New York, NY (USA))

    1990-04-01T23:59:59.000Z

    This paper describes the design, development and laboratory testing of a high voltage PPP (paper polypropylene/paper laminate) insulated joint for commercial application on 138-kV PPP-insulated cable. The design approach taken is conservative and addresses the typical variations in field conditions and in skill and workmanship of the splicing. Joint construction details, including choice of connector, taping structure, and joint mechanical reinforcement, are discussed. The test criteria are described and results are presented.

  12. Development and practical operation of perfluorocarbon immersed 275kV transformers with compressed SF6 gas insulation

    SciTech Connect (OSTI)

    Hiraishi, K.; Uwano, Y.; Shirakura, K.; Gotanda, Y.; Endoo, K. [Hitachi Ltd. (Japan)] [Hitachi Ltd. (Japan); Higaki, M. [Kyushu Kyoritu Univ., Kitakyushu (Japan)] [Kyushu Kyoritu Univ., Kitakyushu (Japan); Horikoshi, M.; Mizuno, K.; Hora, H. [Chubu Electric Power Co., Inc., Nagoya (Japan)] [Chubu Electric Power Co., Inc., Nagoya (Japan)

    1995-04-01T23:59:59.000Z

    A perfluorocarbon (PFC) immersed 275kV transformer with compressed SF6 gas insulation has been under development. This paper clarified the AC partial discharge inception voltage and time characteristics of PFC immersed insulation and also clarified that a prototype 275kV 100MVA three phase transformer could be worked without any trouble during the long-term over voltage test. This prototype proved that it had the AC partial discharge inception strength of higher than 1.5 times of the AC test voltage and the lightning impulse breakdown strength of 1.5 times of the test voltage. A 275kV 250MVA three phase transformer was developed and practically operated at the outdoor substation of Chubu Electric Power Co., Inc. This transformer has been successfully operated until now and the detailed internal inspection of the transformer was carried out after one year and 9 months of the successful practical operation and no significant abnormal condition was recognized.

  13. hurricane plan UNO HURRICANE PLAN

    E-Print Network [OSTI]

    Li, X. Rong

    hurricane plan #12;UNO HURRICANE PLAN TABLE OF CONTENTS INTRODUCTION....................................................................................................................................................... 1 I. HURRICANE EMERGENCY TEAMS Hurricane Emergency Implementation Team (HEIT)......................................... 2 PPoosstt

  14. To: Mansueti, Lawrence Subject: RE: Pepco Scheduled Line Repair...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Sent: Monday, January 29, 2007 6:28 PM To: Mansueti, Lawrence Subject: RE: Pepco Scheduled Line Repair Dec. 1-20, 2006 Larry, Regarding the planned line outage,...

  15. EA-1863: Vegetation Management on the Glen Canyon-Pinnacle Peak Transmission Lines Spanning the Coconino National Forest, Coconino County, Arizona

    Broader source: Energy.gov [DOE]

    DOE’s Western Area Power Administration is preparing this EA to evaluate the environmental impacts of updating the vegetation management and right-of-way maintenance program for Western’s Glen Canyon to Pinnacle Peak 345-kV transmission lines, which cross the Coconino National Forest, Coconino County, Arizona.

  16. Development and interrupting tests on 250KV 8KA HVDC circuit breaker

    SciTech Connect (OSTI)

    Tokuyama, S.; Arimatsu, K.; Hirata, K.; Kato, Y.; Yoshioka, Y.

    1985-09-01T23:59:59.000Z

    This paper describes the circuit and component selections, development and equivalent circuit test results on an HVDC circuit breaker for an HVDC transmission line. A puffer type SF/sub 6/ gas interrupter for AC circuit breakers is utilized for interrupting DC current with injection of high-frequency inverse current from a commutating capacitor precharged to HVDC line voltage. Also, the effectiveness of application of the HVDC breaker to an HVDC system with two parallel transmission lines is demonstrated through the EMTP simulation.

  17. DESIGN AND PSPICE SIMULATION OF A 150KV/300A/1S COAXIAL PULSE GENERATOR

    E-Print Network [OSTI]

    that contributes to the power loss of the device and the requirement of long lengths of lines for operation, reducing the output current and, thus, contributing less to the overall power loss of the device

  18. Strategic plan for infrastructure optimization

    SciTech Connect (OSTI)

    Donley, C.D.

    1998-05-27T23:59:59.000Z

    This document represents Fluor Daniel Hanford`s and DynCorp`s Tri-Cities Strategic Plan for Fiscal Years 1998--2002, the road map that will guide them into the next century and their sixth year of providing safe and cost effective infrastructure services and support to the Department of Energy (DOE) and the Hanford Site. The Plan responds directly to the issues raised in the FDH/DOE Critical Self Assessment specifically: (1) a strategy in place to give DOE the management (systems) and physical infrastructure for the future; (2) dealing with the barriers that exist to making change; and (3) a plan to right-size the infrastructure and services, and reduce the cost of providing services. The Plan incorporates initiatives from several studies conducted in Fiscal Year 1997 to include: the Systems Functional Analysis, 200 Area Water Commercial Practices Plan, $ million Originated Cost Budget Achievement Plan, the 1OO Area Vacate Plan, the Railroad Shutdown Plan, as well as recommendations from the recently completed Review of Hanford Electrical Utility. These and other initiatives identified over the next five years will result in significant improvements in efficiency, allowing a greater portion of the infrastructure budget to be applied to Site cleanup. The Plan outlines a planning and management process that defines infrastructure services and structure by linking site technical base line data and customer requirements to work scope and resources. The Plan also provides a vision of where Site infrastructure is going and specific initiatives to get there.

  19. OPERATIONAL RESULTS OF THE SPALLATION NEUTRON SOURCE (SNS) POLYPHASE CONVERTER-MODULATOR FOR THE 140 KV KLYSTRON RF SYSTEMS

    SciTech Connect (OSTI)

    W.A. REASS; J.D. DOSS; ET AL

    2001-06-01T23:59:59.000Z

    This paper describes the first operational results of the 140 kV, 1 MW average, 11 MW peak, zero-voltage-switching, 20 kHz polyphase bridge, boost converter-modulator for klystron pulse application. The DC-DC converter derives the buss voltages from a standard 13.8 kV to 2100 Y substation cast-core transformer. Energy storage and filtering is provided by self-clearing metallized hazy polypropylene traction capacitors. Three ''H-Bridge'' Insulated Gate Bipolar Transistor (IGBT) switching networks are used to generate the polyphase 20 kHz transformer primary drive waveforms. The 20 kHz drive waveforms are chirped the appropriate duration to generate the desired klystron pulse width. Pulse-Width Modulation (PWM) of the individual 20 kHz pulses is utilized to provide regulated output waveforms with adaptive feedforward and feedback techniques. The boost transformer design utilizes amorphous nanocrystalline material that provides the required low core loss at design flux levels and switching frequencies. Resonant shunt peaking is used on the transformer secondary to boost output voltage and resonate transformer leakage inductance. With the appropriate transformer leakage inductance and peaking capacitance, zero-voltage-switching of the IGBT's is attained, minimizing switching losses. Reviews of these design parameters and an examination of the first operational results will be performed.

  20. Operational results of the spallation neutron source (SNS) polyphase converter-modulator for the 140 KV klystron RF system

    SciTech Connect (OSTI)

    Reass, W. A. (William A.); Doss, James D.; Gribble, R. F. (Robert F.); Lynch, M. T. (Michael T.); Rees, D. E. (Daniel E.); Tallerico, P. J. (Paul J.); Borovina, D. L.

    2001-01-01T23:59:59.000Z

    This paper describes the first operational results of the 140 kV, 1 MW average, 11 MW peak, zero-voltageswitching, 20 kHz polyphase bridge, boost converter-modulator for klystron pulse application. The DC-DC converter derives the buss voltages from a standard 13.8 kV to 2100 Y substation cast-core transformer. Energy storage and filtering is provided by self-clearing metallized hazy polypropylene traction capacitors. Three 'H-Bridge' Insulated Gate Bipolar Transistor (IGBT) switching networks are used to generate the polyphase 20 kHz transformer primary drive waveforms. The 20 kHz drive waveforms are chirped the appropriate duration to generate the desired klystron pulse width. Pulse-Width Modulation (PWM) of the individual 20 kHz pulses is utilized to provide regulated output waveforms with adaptive feedforward and feedback techniques. The boost transformer design utilizes amorphous nanocrystalline material that provides the required low core loss at design flux levels and switching frequencies. Resonant shunt peaking is used on the transformer secondary to boost output voltage and resonate transformer leakage inductance. With the appropriate transformer leakage inductance and peaking capacitance, zero-voltage-switching of the IGBT's is attained, minimizing switching losses. Reviews of these design parameters and an examination of the first operational results will be performed.

  1. EA-1948: Gila-North Gila Transmission Line Rebuild and Upgrade Project, Yuma County, Arizona

    Broader source: Energy.gov [DOE]

    DOE’s Western Area Power Administration (Western) prepared this EA to analyze the potential environmental impacts of a proposal to rebuild and upgrade two parallel 4.8-mile transmission lines between the Gila and North Gila Substations and take actions in support of portions of Arizona Public Service’s construction of a new, 12.8 mile 230-kV transmission line between North Gila and a proposed substation in Yuma County, Arizona. The U.S. Bureau of Reclamation and U.S. Army Corps of Engineers are cooperating agencies.

  2. EIS-0091: Garrison-Spokane 500-kV Transmission Project

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy's Bonneville Power Administration (BPA) developed this statement to evaluate the environmental impacts of constructing between 254 and 271 miles of 500-kilovolt transmission line across western Montana and northern Idaho to the Spokane area in order to reinforce a section of the BPA electric power grid and to permit reliable integration of 1,240 megawatts of power produced by Colstrip Units 3 and 4, for use in Montana and throughout the Northwest.

  3. EIS-0400: Granby Pumping Plant Switchyard-Windy Gap Substation Transmission Line Rebuild Project, Grand County, CO

    Broader source: Energy.gov [DOE]

    Western Area Power Administration prepared an EIS, with the U.S. Forest Service, Bureau of Land Management, and Grand County (Colorado) as cooperating agencies, to evaluate the potential environmental impacts of rebuilding a 12-mile, 69 kV electric transmission line in Grand County. The proposed project would rebuild the single-circuit line as a double-circuit transmission line and add a second power transformer. Western identified potentially significant impacts while preparing an EA for this proposal (DOE/EA-1520) and prepared an EIS instead of completing the EA. Further information about the project is available on the project website.

  4. FY 2015 Argonne Site Sustainability Plan | Argonne National Laboratory

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    FY 2015 Argonne Site Sustainability Plan Argonne National Laboratory is committed to reducing its environmental footprint. Our site sustainability goals are in line with U.S....

  5. Proactive Planning

    E-Print Network [OSTI]

    Wythe, Kathy

    2008-01-01T23:59:59.000Z

    tx H2O | pg. 20 Landowners and agricultural producers in the Cedar Creek watershed are working with agency representatives and gov- ernment leaders on a proactive plan to help reduce pollution flowing into Cedar Creek Reservoir. The 34...-county watershed have an opportunity to voice their opinions and help draft the watershed protection plan for the reservoir. The plan, which will outline ways to reduce pollution and improve water quality, is an outgrowth of years of water quality monitoring...

  6. Strategic Planning

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    a single BPA data repository * Data quality improvements * Improve model alignment with WECC planning data * Improve WECC base case coordination * Align the BPA data model with...

  7. Uncertain Power Flows and Transmission Planning

    E-Print Network [OSTI]

    capability and quantifying transmission revenues under uncertainty. Illustrative analyses demonstrated potential uses in transmission planning. Part I:Stochastic-Algebraic Evaluation of Available Transfer using a deterministic model for a given system state specified by given loads, generation, line

  8. Materials Sciences Division Integrated Safety Management Plan

    E-Print Network [OSTI]

    Materials Sciences Division Integrated Safety Management Plan Revised: February 9, 2012 Prepared by: signed Feb. 9, 2012 Rick Kelly, Facility/EH&S Manager Submitted by: signed Feb. 9, 2012 Miquel Salmeron.1 RESPONSIBILITY AND AUTHORITY THROUGH LINE MANAGEMENT............................................................5

  9. Development of 500-kV AC cable employing laminar insulation of other than conventional cellulosic paper. Final report

    SciTech Connect (OSTI)

    Bahder, G.; Eager, G.S. Jr.; Walker, J.J.; Dima, A.F.

    1980-09-01T23:59:59.000Z

    The results of an investigation to develop a 500 kV ac laminar dielectric power cable and joint having insulation with lower losses than conventional cellulosic paper insulation are presented. Background information is presented on proposed low-loss synthetic and composite synthetic/cellulosic paper insulations. From these studies, fibrous polypropylene paper tape and cellulosic paper-polypropylene film-cellulosic paper composite paper (PPP) were chosen. Extensive testing of hand-wrapped cable models fabricated with each type of tape served to eliminate the fibrous polypropylene paper tape from further consideration. Cable model tests indicate that the PPP tape is satisfactory for insulation in 500 kV ac cable, and that oil impregnants now used in conventional cellulosic paper insulated cables are unsuitable, but that silicone oil with an additive is satisfactory for PPP tapes. Laboratory data indicate that it may be necessary with the PPP tapes to use a significantly lower viscosity impregnating oil which has a greater tendency to drain from pipe-type cables than conventional oil. This may require a modification of the moisture seal. Four final pipe-type cables having a conventional moisture seal were manufactured for possible future field testing. The dielectric loss of the final cables is one-fifth that of conventional cellulosic paper insulated cables. The estimated installed cost per MVA-mile of the PPP insulated cable, neglecting losses, is higher than cellulosic insulated cables impregnated with conventional mineral oil. However, the capacitance of the cable insulated with PPP tape is 25% lower than conventional cable, and therefore, the reactance necessary to compensate for the cable charging current is significantly reduced.

  10. EA-0587: Proposed Amendment to Presidential Permit PP-63 and Associated Modification to 500 kV International Transmission Line: Forbes, Minnesota to Manitoba, Canada

    Broader source: Energy.gov [DOE]

    This EA evaluates the environmental impacts of Northern States Power Company's  proposal to expand the Forbes Substation in Minnesota.

  11. ACQUISITION PLANNING

    Office of Environmental Management (EM)

    7.1 (May 2010) 1 ACQUISITION PLANNING REFERENCES 1. FAR 4.803(a)(1) Contents of Contract Files 2. FAR 5.405(a) Exchange of Acquisition Information 3. FAR Part 7 Acquisition...

  12. NSLS-II Transport Line Progress

    SciTech Connect (OSTI)

    Fliller R. P.; Wahl, W.; Anderson, A.; Benish, B.; DeBoer, W.; Ganetis, G.; Heese, R.; Hseuh, H.-C.; Hu, J.-P.; Johanson, M.P.; Kosciuk, B.N.; Padrazo, D.; Roy, K.; Shaftan, T.; Singh, O.; Tuozzolo, J.; Wang, G.

    2012-05-20T23:59:59.000Z

    The National Synchrotron Light Source II (NSLS-II) is a state-of-the-art 3-GeV third generation light source currently under construction at Brookhaven National Laboratory. The NSLS-II injection system consists of a 200 MeV linac, a 3-GeV booster synchrotron and associated transfer lines. The first part of the Linac to Booster Transport (LBT) line has been installed for linac commissioning. This part includes all components necessary to commission the NSLS-II linac. The second part of this transport line is undergoing installation. Initial results of hardware commissioning will be discussed. The Booster to Storage Ring (BSR) transport line underwent a design review. The first part of the BSR transport line, consisting of all components necessary to commission the booster will be installed in 2012 for booster commissioning. We report on the final design of the BSR line along with the plan to commission the booster.

  13. MUS Pension Taskforce: 401(a) and 403(b) Plan RFP

    E-Print Network [OSTI]

    Maxwell, Bruce D.

    and manager success · Development of a strategic investment line-up (Security selection and asset allocation of the individual offerings in the plan line-up. They only offer TIAA-CREF funds. 2. The 403(b) plan: Multi ­ individuals have no negotiating power · A coordinated education platform to assist employees in making

  14. Schultz-Hanford Area Transmission Line Project Draft Environmental Impact Statement

    SciTech Connect (OSTI)

    N /A

    2002-02-08T23:59:59.000Z

    This summary covers the major points of the Draft Environmental Impact Statement (EIS) prepared for the BPA Schultz-Hanford Transmission Project proposed by the Bonneville Power Administration (BPA). The project involves constructing a new 500-kilovolt (kV) line in central Washington, north of Hanford. The new line would connect to an existing line at the Schultz Substation near Ellensburg and to a new or existing substation in the Hanford area (see Map 2 in EIS). The project may also involve constructing a new substation to accommodate the new transmission line. As a federal agency, BPA is required by the National Environmental Policy Act (NEPA) to take into account potential environmental consequences of its proposal and take action to protect, restore, and enhance the environment during and after construction. Preparation of this EIS assists in meeting those requirements.

  15. Revised GCFR safety program plan

    SciTech Connect (OSTI)

    Kelley, A.P.; Boyack, B.E.; Torri, A.

    1980-05-01T23:59:59.000Z

    This paper presents a summary of the recently revised gas-cooled fast breeder reactor (GCFR) safety program plan. The activities under this plan are organized to support six lines of protection (LOPs) for protection of the public from postulated GCFR accidents. Each LOP provides an independent, sequential, quantifiable risk barrier between the public and the radiological hazards associated with postulated GCFR accidents. To implement a quantitative risk-based approach in identifying the important technology requirements for each LOP, frequency and consequence-limiting goals are allocated to each. To ensure that all necessary tasks are covered to achieve these goals, the program plan is broken into a work breakdown structure (WBS). Finally, the means by which the plan is being implemented are discussed.

  16. Knowledge based process planning system for electronic assembly

    E-Print Network [OSTI]

    Sabapathy, Arvindh

    1990-01-01T23:59:59.000Z

    the necessary information for the production planning process that follows. 1. 1. 3 Scheduling of Flexible Flow Lines A flexible flow line consists of several banks of identical machines. Several types of products are produced each day. Parts flow from bank... PART DETAILS COMP. LIST LAYOUT SIZE CANDIDATE MACHINES FOR EACH COMPONENT I e. ALTERNATE ROUTES PROCESS TIMES PROCESS PLANNING RELATEDNESS WEEKLY DEMANDS FINALISED ROUTE FOR EACH PART PRODUCTION PLANNING DAILY PRODUC11ON MIX SEQUENCING...

  17. Development of a 33 kV, 20 A long pulse converter modulator for high average power klystron

    SciTech Connect (OSTI)

    Reghu, T.; Mandloi, V.; Shrivastava, Purushottam [Pulsed High Power Microwave Section, Raja Ramanna Centre for Advanced Technology, Indore 452013, M.P. (India)] [Pulsed High Power Microwave Section, Raja Ramanna Centre for Advanced Technology, Indore 452013, M.P. (India)

    2014-05-15T23:59:59.000Z

    Research, design, and development of high average power, long pulse modulators for the proposed Indian Spallation Neutron Source are underway at Raja Ramanna Centre for Advanced Technology. With this objective, a prototype of long pulse modulator capable of delivering 33 kV, 20 A at 5 Hz repetition rate has been designed and developed. Three Insulated Gate Bipolar Transistors (IGBT) based switching modules driving high frequency, high voltage transformers have been used to generate high voltage output. The IGBT based switching modules are shifted in phase by 120° with respect to each other. The switching frequency is 25 kHz. Pulses of 1.6 ms pulse width, 80 ?s rise time, and 70 ?s fall time have been achieved at the modulator output. A droop of ±0.6% is achieved using a simple segmented digital droop correction technique. The total fault energy transferred to the load during fault has been measured by conducting wire burn tests and is found to be within 3.5 J.

  18. A framework for on-line simulation systems

    E-Print Network [OSTI]

    Drake, Glenn Richardson

    1996-01-01T23:59:59.000Z

    Simulation has traditionally been used for off-line planning and design. The advent of computer integrated manufacturing and flexible manufacturing systems has increased interest in shop floor control systems that use simulation technology for real-time...

  19. EA-1931: Keeler to Tillamook Transmission Line Rebuild Project, Washington and Tillamook Counties, Oregon

    Broader source: Energy.gov [DOE]

    Bonneville Power Administration prepared this EA to assess the potential environmental impacts of the proposed rebuild of the Keeler-Forest Grove and Forest Grove-Tillamook 115-kilovolt (kV) transmission lines between the cities of Hillsboro and Tillamook, in Washington and Tillamook Counties, Oregon. The 58-mile-long rebuild would include replacement of all wood-pole structures over 10 years in age. Some existing access roads would be improved to accommodate construction equipment and some new road access would be acquired or constructed in areas where access is not available.

  20. On line chemical composition of analyzer development

    SciTech Connect (OSTI)

    Not Available

    1992-01-01T23:59:59.000Z

    This status report details progress made on the development of an on-line chemical analyzer. Dynamic studies of the distillation column, approval of testing plans, installation of a sample cell and raman analyzer, design of computerized control systems are described. Information on seminars and published papers is also included. (GHH)

  1. Public Opinions of Building Additional High-Voltage Electric Power Lines

    E-Print Network [OSTI]

    Tesfatsion, Leigh

    Public Opinions of Building Additional High-Voltage Electric Power Lines A Report to the National-Voltage Electric Power Lines: A Report to the National Science Foundation and the Electric Power Research Center to build new power lines. Residents living in counties with planned routes for new transmission lines

  2. Canby Area Service Project substation and associated transmission line. Environmental Assessment

    SciTech Connect (OSTI)

    Not Available

    1992-02-01T23:59:59.000Z

    Bonneville Power Administration (BPA) provides power to Surprise Valley Electrification Corporation (SVEC) in Modoc County, California. BPA uses PacificCorp`s substation and transmission facilities between Alturas and Canby, California to transfer power to SVEC`s Canby Substation. In the next year, SVEC expects increased industrial, agricultural, and residential electric loads on their 69-kV transmission system south of Canby. SVEC`s substation can accommodate only about 10 percent of the expected additional electric load. BPA`s proposed action is intended to meet SVEC`s increasing electric load. BPA proposes to meet SVEC`s increasing energy load by tapping into BPA`s existing BPA Malin-Warner 230-kV transmission line, and building an 7.9-mile transmission line to a new BPA substation. BPA proposes to build the new substation next to the west side of SVEC`s Canby Substation (Figure 1). This new substation will allow SVEC to move the additional power over their existing transmission or distribution lines. This report is the environmental assessment of the potential impact of the proposed project. The assessment determined that no ``environmental impact statement`` is not required.

  3. Canby Area Service Project : Substation and Associated Transmission Line : Environmental Assessment.

    SciTech Connect (OSTI)

    United States. Bonneville Power Administration.

    1992-02-01T23:59:59.000Z

    Bonneville Power Administration (BPA) provides power to Surprise Valley Electrification Corporation (SVEC) in Modoc County, California. BPA uses PacificCorp's substation and transmission facilities between Alturas and Canby, California to transfer power to SVEC's Canby Substation. In the next year, SVEC expects increased industrial, agricultural, and residential electric loads on their 69-kV transmission system south of Canby. SVEC's substation can accommodate only about 10 percent of the expected additional electric load. BPA's proposed action is intended to meet SVEC's increasing electric load. BPA proposes to meet SVEC's increasing energy load by tapping into BPA's existing BPA Malin-Warner 230-kV transmission line, and building an 7.9-mile transmission line to a new BPA substation. BPA proposes to build the new substation next to the west side of SVEC's Canby Substation (Figure 1). This new substation will allow SVEC to move the additional power over their existing transmission or distribution lines. This report is the environmental assessment of the potential impact of the proposed project. The assessment determined that no environmental impact statement'' is not required.

  4. Plains and Eastern Clean Line Transmission Line: Comment from...

    Office of Environmental Management (EM)

    from Block Plains and Eastern Clean Line: Arkansas and Oklahoma Plains and Eastern Clean Line Transmission Line: Comment from Block Plains and Eastern Clean Line: Arkansas and...

  5. Energy planning and management plan

    SciTech Connect (OSTI)

    NONE

    1996-01-01T23:59:59.000Z

    This paper contains printed copies of 60FR 53181, October 12, 1995 and 60 FR 54151. This is a record of decision concerning the Western Area Power Administration`s final draft and environmental impact statement, and Energy Planning and Management Program.

  6. Plan Your School Visit

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Plan Your School Visit For Teachers Teachers Visit the Museum We Visit You Teacher Resources Home Schoolers Plan Your School Visit invisible utility element Plan Your School Visit...

  7. Waste minimization and pollution prevention awareness plan

    SciTech Connect (OSTI)

    Not Available

    1991-05-31T23:59:59.000Z

    The purpose of this plan is to document the Lawrence Livermore National Laboratory (LLNL) Waste Minimization and Pollution Prevention Awareness Program. The plan specifies those activities and methods that are or will be employed to reduce the quantity and toxicity of wastes generated at the site. The intent of this plan is to respond to and comply with (DOE's) policy and guidelines concerning the need for pollution prevention. The Plan is composed of a LLNL Waste Minimization and Pollution Prevention Awareness Program Plan and, as attachments, Program- and Department-specific waste minimization plans. This format reflects the fact that waste minimization is considered a line management responsibility and is to be addressed by each of the Programs and Departments. 14 refs.

  8. Plans, Updates, Regulatory Documents

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Stewardship Environmental Protection Obeying Environmental Laws Individual Permit Documents Individual Permit: Plans, Updates, Regulatory Documents1335769200000Plans...

  9. Annual Training Plan Template

    Broader source: Energy.gov [DOE]

    The Annual Training Plan Template is used by an organization's training POC to draft their organization's annual training plan.

  10. Leveraging infrastructure : sustainable bus rapid transit route planning in Beirut, Lebanon

    E-Print Network [OSTI]

    Nabti, Jumana M., 1976-

    2004-01-01T23:59:59.000Z

    This thesis applies the concepts of urban design, public transportation planning, economic development, and sustainability, to the routing and site plan of a two-kilometer bus rapid transit (BRT) line segment into downtown ...

  11. UCSB Lab-specific Chemical Hygiene Plan 1 EH&S, Rev. 1/07

    E-Print Network [OSTI]

    Bigelow, Stephen

    UCSB Lab-specific Chemical Hygiene Plan 1 EH&S, Rev. 1/07 Chemical Hygiene Plan (CPH) UCSB MRL Nanomaterials n) SOP for Using Centrifuge #12;UCSB Lab-specific Chemical Hygiene Plan 2 EH&S, Rev. 1/07 1 Laboratory Chemical Hygiene Plan (CHP) paper copy or on line. If you have any questions, please contact

  12. Number of lightning discharges causing damage to lightning arrester cables for aerial transmission lines in power systems

    SciTech Connect (OSTI)

    Nikiforov, E. P. [Electric Power Scientific Research Institute (VNIIE), branch of OAO 'NTTs Elektroenergetika' (Russian Federation)

    2009-07-15T23:59:59.000Z

    Damage by lightning discharges to lightning arrester cables for 110-175 kV aerial transmission lines is analyzed using data from power systems on incidents with aerial transmission lines over a ten year operating period (1997-2006). It is found that failures of lightning arrester cables occur when a tensile force acts on a cable heated to the melting point by a lightning current. The lightning currents required to heat a cable to this extent are greater for larger cable cross sections. The probability that a lightning discharge will develop decreases as the amplitude of the lightning current increases, which greatly reduces the number of lightning discharges which damage TK-70 cables compared to TK-50 cables. In order to increase the reliability of lightning arrester cables for 110 kV aerial transmission lines, TK-70 cables should be used in place of TK-50 cables. The number of lightning discharges per year which damage lightning arrester cables is lowered when the density of aerial transmission lines is reduced within the territory of electrical power systems. An approximate relationship between these two parameters is obtained.

  13. Disability Plans

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625govInstrumentstdmadapInactiveVisitingContract Management FermiDavidDieselDirectionsDirectorateDisability Plans

  14. Vision Plan

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office of ScienceandMesa del SolStrengthening aTurbulenceUtilize AvailableMedia1.1 The History of theVision Plan

  15. Plans, Procedures

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office of Science (SC)IntegratedSpeeding accessPeptoidLabPhysics Physics Oursources |VisitPlans,

  16. Strategic Plan

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742EnergyOnItemResearch > TheNuclearHomelandMultivariateSiteSeparationsRelevantStrategic Plan

  17. Medical Plans

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office of Science (SC)Integrated Codes |IsLove Your Home andDispositionMechanical R&DMakingMedical Plans

  18. Preplanning Method for Multi-Story Building Construction using Line of Balance Proceedings IGLC '98

    E-Print Network [OSTI]

    Tommelein, Iris D.

    of production control in multi-story building construction. Preplanning using the line of balance technique attempts to solve planning problems by making production process clearer and simpler. A preplanning method planning and scheduling sequencing. Using line of balance concepts also suggests some control tools which

  19. Venus Technology Plan Venus Technology Plan

    E-Print Network [OSTI]

    Rathbun, Julie A.

    Venus Technology Plan May 2014 #12; ii Venus Technology Plan At the Venus Exploration Survey priorities, and (3) develop a Technology Plan for future Venus missions (after a Technology Forum at VEXAG Meeting 11 in November 2013). Here, we present the 2014 Venus Technology Plan

  20. Task Plans

    Office of Environmental Management (EM)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33 1112011 Strategic2Uranium Transferon the PassingRouting TECFinish LineTara Trujillo AboutTask

  1. Development of 230-kV high-pressure, gas-filled, pipe-type cable system: Model test program phase

    SciTech Connect (OSTI)

    Silver, D.A. (Pirelli Cable Corp., Florham Park, NJ (USA))

    1990-09-01T23:59:59.000Z

    The objective of this project was the development of a 230 kV high-pressure gas-filled (HPGF) pipe-type cable employing paper or laminate of paper-polypropylene-paper (PPP) insulation pressurized with N{sub 2} gas or a blend of 15% SF{sub 6}/85% N{sub 2} gas. Heretofore, HPGF pipe-type cables have been restricted to 138 kV ratings due to technical difficulties in achieving higher voltage ratings. In view of the high cost of manufacturing and testing a large number of full size cables, cable models with 2 mm (80 mils) and 2.5 mm (100 mils) wall thicknesses of insulation enclosed in a test fixture capable of withstanding a test pressure of 2070 kPa (300 psig) and high electrical stresses were employed for dissipation factor versus voltage measurements and for ac and impulse breakdown tests at rated and emergency operating temperatures. In addition, a 36 cm (14 in) full wall cable model enclosed in a pressure vessel was utilized for transient pressure response tests. The results of this investigation attest tot he technical feasibility of the design and manufacture of a 230 kV HPGF pipe-type cable employing paper or PPP insulation pressurized with 100% N{sub 2} gas or a blend of 15% SF{sub 6}/85% N{sub 2} gas for operation under normal and 100 hour emergency conditions at conductor temperatures of 85{degree} and 105{degree}C, respectively. The manufacture of a full size PPP insulated cable pressurized with a blend of 15% SF{sub 6}/85% N{sub 2} gas employing pre-impregnated PPP insulating tapes and an annular conductor based on the design stresses defined in this report is recommended for laboratory evaluation and extended life tests. 11 refs., 45 figs., 11 tabs.

  2. Image-Guided Radiotherapy (IGRT) for Prostate Cancer Comparing kV Imaging of Fiducial Markers With Cone Beam Computed Tomography (CBCT)

    SciTech Connect (OSTI)

    Barney, Brandon M., E-mail: barney.brandon@mayo.ed [Department of Radiation Oncology, Mayo Clinic, Rochester, MN (United States); Lee, R. Jeffrey [Department of Radiation Oncology, Intermountain Medical Center, Salt Lake City, UT (United States); Handrahan, Diana [Department of Statistics, Intermountain Medical Center, Salt Lake City, UT (United States); Welsh, Keith T.; Cook, J. Taylor; Sause, William T. [Department of Radiation Oncology, Intermountain Medical Center, Salt Lake City, UT (United States)

    2011-05-01T23:59:59.000Z

    Purpose: To present our single-institution experience with image-guided radiotherapy comparing fiducial markers and cone-beam computed tomography (CBCT) for daily localization of prostate cancer. Methods and Materials: From April 2007 to October 2008, 36 patients with prostate cancer received intensity-modulated radiotherapy with daily localization by use of implanted fiducials. Orthogonal kilovoltage (kV) portal imaging preceded all 1244 treatments. Cone-beam computed tomography images were also obtained before 286 treatments (23%). Shifts in the anterior-posterior (AP), superior-inferior (SI), and left-right (LR) dimensions were made from kV fiducial imaging. Cone-beam computed tomography shifts based on soft tissues were recorded. Shifts were compared by use of Bland-Altman limits of agreement. Mean and standard deviation of absolute differences were also compared. A difference of 5 mm or less was acceptable. Subsets including start date, body mass index, and prostate size were analyzed. Results: Of 286 treatments, 81 (28%) resulted in a greater than 5.0-mm difference in one or more dimensions. Mean differences in the AP, SI, and LR dimensions were 3.4 {+-} 2.6 mm, 3.1 {+-} 2.7 mm, and 1.3 {+-} 1.6 mm, respectively. Most deviations occurred in the posterior (fiducials, 78%; CBCT, 59%), superior (79%, 61%), and left (57%, 63%) directions. Bland-Altman 95% confidence intervals were -4.0 to 9.3 mm for AP, -9.0 to 5.3 mm for SI, and -4.1 to 3.9 mm for LR. The percentages of shift agreements within {+-}5 mm were 72.4% for AP, 72.7% for SI, and 97.2% for LR. Correlation between imaging techniques was not altered by time, body mass index, or prostate size. Conclusions: Cone-beam computed tomography and kV fiducial imaging are similar; however, more than one-fourth of CBCT and kV shifts differed enough to affect target coverage. This was even more pronounced with smaller margins (3 mm). Fiducial imaging requires less daily physician input, is less time-consuming, and is our preferred method for prostate image-guided radiotherapy.

  3. Case Study of the Failure of two 13.8kV Control & Metering Transformers that caused significant Equipment Damage

    SciTech Connect (OSTI)

    Dreifuerst, G R; Chew, D B; Mangonon, H L; Swyers, P W

    2011-08-25T23:59:59.000Z

    The degradation and failure of cast-coil epoxy windings within 13.8kV control power transformers and metering potential transformers has been shown to be dangerous to both equipment and personnel, even though best industrial design practices were followed. Accident scenes will be examined for two events at a U.S. Department of Energy laboratory. Failure modes will be explained and current design practices discussed with changes suggested to prevent a recurrence and to minimize future risk. New maintenance philosophies utilizing partial discharge testing of the transformers as a prediction of end-of-life will be examined.

  4. Concurrent Wind Cooling in Power Transmission Lines

    SciTech Connect (OSTI)

    Jake P Gentle

    2012-08-01T23:59:59.000Z

    Idaho National Laboratory and the Idaho Power Company, with collaboration from Idaho State University, have been working on a project to monitor wind and other environmental data parameters along certain electrical transmission corridors. The combination of both real-time historical weather and environmental data is being used to model, validate, and recommend possibilities for dynamic operations of the transmission lines for power and energy carrying capacity. The planned results can also be used to influence decisions about proposed design criteria for or upgrades to certain sections of the transmission lines.

  5. EC Transmission Line Risk Identification and Analysis

    SciTech Connect (OSTI)

    Bigelow, Tim S [ORNL

    2012-04-01T23:59:59.000Z

    The purpose of this document is to assist in evaluating and planning for the cost, schedule, and technical project risks associated with the delivery and operation of the EC (Electron cyclotron) transmission line system. In general, the major risks that are anticipated to be encountered during the project delivery phase associated with the implementation of the Procurement Arrangement for the EC transmission line system are associated with: (1) Undefined or changing requirements (e.g., functional or regulatory requirements) (2) Underperformance of prototype, first unit, or production components during testing (3) Unavailability of qualified vendors for critical components Technical risks associated with the design and operation of the system are also identified.

  6. State Waste Discharge Permit ST-4502 Implementation Plan

    SciTech Connect (OSTI)

    BROWN, M.J.; LECLAIR, M.D.

    2000-09-27T23:59:59.000Z

    Plan has been developed to demonstrate compliance with regulatory requirements set forth in Permit ST-3502 and as a line management tool for use in maintaining configuration control of permit as well as documentation used to implement permit requirements.

  7. A tactical planning model for a serial flow manufacturing system

    E-Print Network [OSTI]

    Huang, Bin, S.M. Massachusetts Institute of Technology

    2010-01-01T23:59:59.000Z

    This project aims to improve the operation and planning of a specific type of manufacturing system, a serial flow line that entails a sequence of process stages. The objective is to investigate inventory policy, raw material ...

  8. EIS-0231: Navajo Transmission Project

    Broader source: Energy.gov [DOE]

    This EIS evaluates the environmental impacts of a proposal to by Dine Power Authority, a Navajo Nation enterprise, to construct, operate, and maintain a 500 kilovolt (kV) transmission line planned...

  9. Hanford Site Development Plan

    SciTech Connect (OSTI)

    Rinne, C.A.; Curry, R.H.; Hagan, J.W.; Seiler, S.W.; Sommer, D.J. (Westinghouse Hanford Co., Richland, WA (USA)); Yancey, E.F. (Pacific Northwest Lab., Richland, WA (USA))

    1990-01-01T23:59:59.000Z

    The Hanford Site Development Plan (Site Development Plan) is intended to guide the short- and long-range development and use of the Hanford Site. All acquisition, development, and permanent facility use at the Hanford Site will conform to the approved plan. The Site Development Plan also serves as the base document for all subsequent studies that involve use of facilities at the Site. This revision is an update of a previous plan. The executive summary presents the highlights of the five major topics covered in the Site Development Plan: general site information, existing conditions, planning analysis, Master Plan, and Five-Year Plan. 56 refs., 67 figs., 31 tabs.

  10. EIS-0486: Plains & Eastern Clean Line Transmission Project |...

    Broader source: Energy.gov (indexed) [DOE]

    project would include an overhead 600 kilovolt (kV) high voltage direct current (HVDC) electric transmission system and associated facilities with the capacity to deliver...

  11. 2030 OCARTS Plan Report

    E-Print Network [OSTI]

    Association of Central Oklahoma Governments

    ......................................Director of Planning & Program Development Pearlie Tiggs................................................................... Community Planner 2030 OCARTS Plan Report Table of Contents PART 1 INTRODUCTION........................................................................ 1 Federal Legislation.......................................................................... 1 Purpose of the Plan Report and Relationship to other Plan Documents............. 3 Organization of the Transportation Planning Process...

  12. Oscillation of bundle conductors in overhead lines due to turbulent wind

    SciTech Connect (OSTI)

    Diana, G.; Cheli, F. (Politecnico di Milano, Milano (IT)); Manenti, A. (Universita degli Studi di Brescia, Brescia (IT)); Nicolini, P.; Tavano, F. (ENEL/CREI, Milano (IT))

    1990-10-01T23:59:59.000Z

    Due to the wind, the bundle conductors in overhead lines can oscillate and the distance between the phases can be reduced. This kind of movement may be caused by: non expansive oscillations of the phases due to the wind turbulence and to the correlated variations of the bundles aerodynamic coefficients during the movement (buffeting); expansive oscillations, or galloping, of the phases due to the unstable aerodynamic shapes that bundles may assume in presence of ice. This paper presents an analytical methodology to examine the dynamic behaviour of bundles subjected to the above mentioned phenomena. The results obtained during experiments carried out on a span of an energized 420-kV line equipped with triple bundles and subjected to oscillations due to buffeting are exposed. Lastly, the experimental data are compared with the analytical results.

  13. Hazardous Waste Compliance Program Plan

    SciTech Connect (OSTI)

    Potter, G.L.; Holstein, K.A.

    1994-05-01T23:59:59.000Z

    The Hazardous Waste Compliance Program Plan (HWCPP) describes how the Rocky Flats Plant institutes a more effective waste management program designed to achieve and maintain strict adherence to the Resource Conservation and Recovery Act (RCRA) requirements. Emphasis is given to improve integration of line operations with programmatic and functional support activities necessary to achieve physical compliance to RCRA regulated equipment, facilities and operations at the floor level. This program focuses on specific activities occurring or which need to occur within buildings containing RCRA regulated units and activities. The plan describes a new approach to achieving and maintaining compliance. This approach concentrates authority and accountability for compliance with the line operating personnel, with support provided from the programmatic functions. This approach requires a higher degree of integration and coordination between operating and program support organizations. The principal changes in emphases are; (1) increased line operations involvement, knowledge and accountability in compliance activities, (2) improved management systems to identify, correct and/or avoid deficiencies and (3) enhanced management attention and employee awareness of compliance related matters.

  14. PLAN100%DIGITAL PLAN100%DIGITAL

    E-Print Network [OSTI]

    en un conjunto d e servicios digitales. RAZONES DEL PLAN: Existe un nú mero importante de institu tos

  15. BPA line crew puts innovative work plan into aerial action

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    links Newsroom News Releases About Us Freedom of Information Act Investor Relations Library Privacy Publications Tribal Affairs Newsroom Search News Articles... Search BPA...

  16. BPA line crew puts innovative work plan into aerial action

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office511041cloth DocumentationProductsAlternativeOperationalAugustDecade Later: AreAugust 19,1 BPA I-5

  17. Sixth Northwest Conservation and Electric Power Plan Chapter 7: Transmission

    E-Print Network [OSTI]

    Sixth Northwest Conservation and Electric Power Plan Chapter 7: Transmission Summary of Key, both in operating the existing system and in planning for new major transmission lines. Since then transmission system is an integral part of the regional power system. It functions roughly like the highway

  18. ENVIRONMENTAL HEALTH SCIENCES Plan Requirements Campus: UMICH RG = Requirement Group

    E-Print Network [OSTI]

    Shyy, Wei

    ENVIRONMENTAL HEALTH SCIENCES Plan Requirements Campus: UMICH RG = Requirement Group Career: GPH RQ = Requirement Program: 01848 LN = Line Plan: 3200MPH RG 5298 ENVIRONMENTAL HEALTH SCIENCES REQUIREMENTS, 643, 653, 675, 677 or 695 LN 0030 - Environmental Health Sciences: EHS 501, 506, 507 or 508 LN 0040

  19. Motion Planning Using Dynamic Roadmaps Marcelo Kallmann and Maja Mataric

    E-Print Network [OSTI]

    Mataric, Maja J.

    Motion Planning Using Dynamic Roadmaps Marcelo Kallmann and Maja Mataric Interaction Lab, Computer, mataric}@usc.edu Abstract - We evaluate the use of dynamic roadmaps for on- line motion planning and nodes of a precomputed roadmap are updated accordingly. We concentrate in this paper on analyzing

  20. Management Plan Supplement Yakima Subbasin Plan

    E-Print Network [OSTI]

    #12;Management Plan Supplement Yakima Subbasin Plan November 26, 2004 Prepared for the Presented's subbasin planning process is iterative and designed within an adaptive management framework. Management is comprised of elected officials from local governments throughout the subbasin, and meets regularly to work

  1. CHEMICAL HYGIENE PLAN HAZARD COMMUNICATION PLAN

    E-Print Network [OSTI]

    Oliver, Douglas L.

    CHEMICAL HYGIENE PLAN AND HAZARD COMMUNICATION PLAN Occupational Exposures to Hazardous Chemicals Safety 2723 Environmental Health/Safety Chemical Hygiene Officer Radiation Safety Officer Biological (Accident Reports) 2204 Bioengineering 2965 #12;TABLE OF CONTENTS CHEMICAL HYGIENE PLAN (CHP) (4/2007) 1

  2. CHEMICAL HYGIENE PLAN HAZARD COMMUNICATION PLAN

    E-Print Network [OSTI]

    Kim, Duck O.

    CHEMICAL HYGIENE PLAN AND HAZARD COMMUNICATION PLAN Occupational Exposures to Hazardous Chemicals and Safety Numbers Research Safety 2723 Environmental Health/Safety Chemical Hygiene Officer Radiation Safety Human Resources (Accident Reports) 4589 Bioengineering 2965 #12;TABLE OF CONTENTS CHEMICAL HYGIENE PLAN

  3. Series Transmission Line Transformer

    DOE Patents [OSTI]

    Buckles, Robert A. (Livermore, CA); Booth, Rex (Livermore, CA); Yen, Boris T. (El Cerrito, CA)

    2004-06-29T23:59:59.000Z

    A series transmission line transformer is set forth which includes two or more of impedance matched sets of at least two transmissions lines such as shielded cables, connected in parallel at one end ans series at the other in a cascading fashion. The cables are wound about a magnetic core. The series transmission line transformer (STLT) which can provide for higher impedance ratios and bandwidths, which is scalable, and which is of simpler design and construction.

  4. Accidental Death & Dismemberment Plan

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Death & Dismemberment Plan A comprehensive benefits package with plan options for health care and retirement to take care of our employees today and tomorrow. Contact...

  5. Electric Transmission Lines (Nebraska)

    Broader source: Energy.gov [DOE]

    The Public Service Commission has jurisdiction over all electricity transmission lines crossing over or under railroad tracks at public highway crossings. This section contains general regulations...

  6. Institutional plan. FY 1998--2003

    SciTech Connect (OSTI)

    NONE

    1997-07-01T23:59:59.000Z

    This Institutional Plan for Argonne National Laboratory contains central elements of Argonne`s strategic plan. Chapter II of this document discusses the Laboratory`s mission and core competencies. Chapter III presents the Science and Technology Strategic Plan, which summarizes key features of the external environment, presents Argonne`s vision, and describes how the Laboratory`s strategic goals and objectives map onto and support DOE`s four business lines. The balance of the chapter comprises the science and technology area plans, organized by the four DOE business lines. Chapter IV describes the Laboratory`s ten major initiatives, which cover a broad spectrum of science and technology. Our proposal for an Exotic Beam Facility aims at, among other things, increased understanding of the processes of nuclear synthesis during and shortly after the Big Bang. Our Advanced Transportation Technology initiative involves working with US industry to develop cost-effective technologies to improve the fuel efficiency and reduce the emissions of transportation systems. The Laboratory`s plans for the future depend significantly on the success of its major initiatives. Chapter V presents our Operations and Infrastructure Strategic Plan. The main body of the chapter comprises strategic plans for human resources; environmental protection, safety, and health; site and facilities; and information management. The chapter concludes with a discussion of the business and management practices that Argonne is adopting to improve the quality and cost-effectiveness of its operations. The structure and content of this document depart from those of the Institutional Plan in previous years. Emphasis here is on directions for the future; coverage of ongoing activities is less detailed. We hope that this streamlined plan is more direct and accessible.

  7. FY 91 Annual Research Plan

    SciTech Connect (OSTI)

    Not Available

    1990-12-01T23:59:59.000Z

    In line with the Federal Oil Research Program to maximize the economic producibility of the domestic oil resource, the National Institute for Petroleum and Energy Research (NIPER) presents this FY91 Annual Research Plan. NIPER is organized into two research departments -- Energy Production Research (EPR) and Fuels Research (FR). Projects in EPR deal with various aspects of enhanced oil recovery and include reservoir characterization, chemical flooding, gas injection, steam injection, microbial enhanced oil recovery, and the environmental concerns related to these processes. Projects in FR consider the impact of heavy oil and alternative fuels on the processing and end-use of fuels. Projects are briefly described.

  8. Transmission Line Security Monitor

    ScienceCinema (OSTI)

    None

    2013-05-28T23:59:59.000Z

    The Transmission Line Security Monitor is a multi-sensor monitor that mounts directly on high-voltage transmission lines to detect, characterize and communicate terrorist activity, human tampering and threatening conditions around support towers. For more information about INL's critical infrastructure protection research, visit http://www.facebook.com/idahonationallaboratory.

  9. Transmission Line Security Monitor

    SciTech Connect (OSTI)

    None

    2011-01-01T23:59:59.000Z

    The Transmission Line Security Monitor is a multi-sensor monitor that mounts directly on high-voltage transmission lines to detect, characterize and communicate terrorist activity, human tampering and threatening conditions around support towers. For more information about INL's critical infrastructure protection research, visit http://www.facebook.com/idahonationallaboratory.

  10. EA-2002: Right-of-Way Application for the Tucson-Apache 115-kV Transmission

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742Energy China U.S.ContaminationJulySavannah River Site for Use by the State of SouthLine, Pima

  11. Plans, Implementation, and Results

    Broader source: Energy.gov [DOE]

    About the Weatherization and Intergovernmental Programs Office (WIPO) including information on plans, implementations, and results.

  12. Climate change action plan

    E-Print Network [OSTI]

    Delivery Climate change action plan 2009-2011 #12;2 | Climate change action plan ©istockphoto.com #12;Climate Change Action Plan Climate change action plan | 3 Contents Overview 4 Preface and Introduction 5 Climate change predictions for Scotland 6 The role of forestry 7 Protecting and managing

  13. Intrinsic AGN Absorption Lines

    E-Print Network [OSTI]

    Fred Hamann

    2000-06-12T23:59:59.000Z

    Strong absorption lines are common in rest-frame UV spectra of AGNs due to a variety of resonant transitions, for example the HI Lyman series lines (most notably Ly-alpha 1216) and high-ionization doublets like CIV 1549,1551. The lines are called ``intrinsic'' if the absorbing gas is physically related to the AGN, e.g. if the absorber resides broadly within the radius of the AGN's surrounding ``host'' galaxy. Intrinsic absorption lines are thus valuable probes of the kinematics, physical conditions and elemental abundances in the gas near AGNs. Studies of intrinsic absorbers have historically emphasized the broad absorption lines (BALs) in quasars. Today we recognize a wider variety of intrinsic lines in a wider range of objects. For example, we now know that Seyfert 1 galaxies (the less luminous cousins of quasars) have intrinsic absorption. We also realize that intrinsic lines can form in a range of AGN environments --- from the dynamic inner regions like the BALs, to the more quiescent outer host galaxies >10 kpc away. This article provides a brief introduction to current observational and theoretical work on intrinsic AGN absorbers.

  14. TRANSMISSION EXPANSION PLANNING WITH RE-DESIGN A Greedy Randomized Adaptive Search Procedure

    E-Print Network [OSTI]

    Paris-Sud XI, Université de

    for the managing entity to change the electrical power system, adding new transmission lines and power generatorsTRANSMISSION EXPANSION PLANNING WITH RE-DESIGN A Greedy Randomized Adaptive Search Procedure Rosa: TRANSMISSION EXPANSION PLANNING: NETWORK DESIGN: GRASP. Abstract: Transmission expansion planning with re

  15. Coherent soliton communication lines

    SciTech Connect (OSTI)

    Yushko, O. V., E-mail: olesya.yushko@gmail.com; Redyuk, A. A.; Fedoruk, M. P.; Turitsyn, S. K. [Novosibirsk State University (Russian Federation)

    2014-11-15T23:59:59.000Z

    The data transmission in coherent fiber-optical communication lines using solitons with a variable phase is studied. It is shown that nonlinear coherent structures (solitons) can be applied for effective signal transmission over a long distance using amplitude and optical-phase keying of information. The optimum ratio of the pulse width to the bit slot at which the spectral efficiency (transmitted bits per second and hertz) is maximal is determined. It is shown that soliton fiber-optical communication lines can ensure data transmission at a higher spectral efficiency as compared to traditional communication lines and at a high signal-to-noise ratio.

  16. Holes in Spectral Lines

    E-Print Network [OSTI]

    Fontana, Peter R.; Srivastava, Rajendra P.

    1973-06-01T23:59:59.000Z

    The decay of an atom in the presence of a static perturbation is investigated. The perturbation couples a decaying state with a nondecaying state. A "hole" appears in the emission line at a frequency equal to the frequency difference between...

  17. Line Extension Alternatives

    Broader source: Energy.gov [DOE]

    The Public Service Board (PSB) of Vermont developed rules regarding utility line extension requests. While the majority of the rules focus on the procedure followed (and associated fees) for the...

  18. Power line detection system

    DOE Patents [OSTI]

    Latorre, V.R.; Watwood, D.B.

    1994-09-27T23:59:59.000Z

    A short-range, radio frequency (RF) transmitting-receiving system that provides both visual and audio warnings to the pilot of a helicopter or light aircraft of an up-coming power transmission line complex. Small, milliwatt-level narrowband transmitters, powered by the transmission line itself, are installed on top of selected transmission line support towers or within existing warning balls, and provide a continuous RF signal to approaching aircraft. The on-board receiver can be either a separate unit or a portion of the existing avionics, and can also share an existing antenna with another airborne system. Upon receipt of a warning signal, the receiver will trigger a visual and an audio alarm to alert the pilot to the potential power line hazard. 4 figs.

  19. Power line detection system

    DOE Patents [OSTI]

    Latorre, Victor R. (Tracy, CA); Watwood, Donald B. (Tracy, CA)

    1994-01-01T23:59:59.000Z

    A short-range, radio frequency (RF) transmitting-receiving system that provides both visual and audio warnings to the pilot of a helicopter or light aircraft of an up-coming power transmission line complex. Small, milliwatt-level narrowband transmitters, powered by the transmission line itself, are installed on top of selected transmission line support towers or within existing warning balls, and provide a continuous RF signal to approaching aircraft. The on-board receiver can be either a separate unit or a portion of the existing avionics, and can also share an existing antenna with another airborne system. Upon receipt of a warning signal, the receiver will trigger a visual and an audio alarm to alert the pilot to the potential power line hazard.

  20. 65 Contingency Planning Issues CONTINGENCY PLANNING ISSUES

    E-Print Network [OSTI]

    . The plan relies on a mixed strategy response to an energy shortage. The plan uses a free market approach to local jurisdic- tions, economic considerations, revisions to the California Energy Shortage Contingency multiple jurisdictions or agencies. LOCAL GOVERNMENT ASSISTANCE PROGRAM The purpose of the Energy

  1. CHEMICAL HYGIENE PLAN HAZARD COMMUNICATION PLAN

    E-Print Network [OSTI]

    Kim, Duck O.

    CHEMICAL HYGIENE PLAN AND HAZARD COMMUNICATION PLAN Occupational Exposures to Hazardous Chemicals and Safety Numbers Research Safety 2723 Environmental Health/Safety Chemical Hygiene Officer Radiation Safety Human Resources (Accident Reports) 4589 Clinical Engineering 2964 #12;TABLE OF CONTENTS CHEMICAL HYGIENE

  2. Regulations for Gas Transmission Lines Less than Ten Miles Long (New York)

    Broader source: Energy.gov [DOE]

    Any person who wishes to construct a gas transmission line that is less than ten miles long must file documents describing the construction plans and potential land use and environmental impacts of...

  3. Probabilistic on-line transportation problems with carrying-capacity constraints

    E-Print Network [OSTI]

    Treleaven, Kyle (Kyle Ballantyne)

    2014-01-01T23:59:59.000Z

    This thesis presents new insights and techniques for the analysis and design of autonomous or technology-assisted ("intelligent") transportation systems. The focus is on cooperative, on-line planning and control, of a fleet ...

  4. Regulations for Electric Transmission and Fuel Gas Transmission Lines Ten or More Miles Long (New York)

    Broader source: Energy.gov [DOE]

    Any person who wishes to construct an electric or gas transmission line that is more than ten miles long must file documents describing the construction plans and potential land use and...

  5. Climate Change Adaptation Planning

    Office of Energy Efficiency and Renewable Energy (EERE)

    This course provides an introduction to planning for climate change impacts, with examples of tribes that have been going through the adaptation planning process. The course is intended for tribal...

  6. Virginia Energy Plan (Virginia)

    Broader source: Energy.gov [DOE]

    The 2010 Virginia Energy Plan affirms the state's support for the development of renewable energy. The Plan assesses the state’s energy picture through an examination of the state’s primary energy...

  7. Sustainabiliity Sustainability Plan

    E-Print Network [OSTI]

    Heller, Barbara

    Sustainabiliity IIT Campus Sustainability Plan 2010­2020 Published Fall Semester 2010 www.iit.edu/campus_sustainability #12;IIT Campus Sustainability Plan 2010-2020 Fall Semester 2010 1 Section I: Background Sustainability ...................................................................................................................................................................8 IIT Academic Entities on Sustainability

  8. Hoisting & Rigging Lift Plan

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Plan Stanford Synchrotron Radiation Laboratory May 16, 2005 SSRL-HRLP-000-R0 Page 3 of 3 Guidelines for Generating a Rigging Sketch The lift plan required a rigging sketch or...

  9. Strategic Plan Environmental Assessment

    E-Print Network [OSTI]

    Strategic Plan Environmental Assessment 2009 Clinical Center National Institutes of Health U Institutes of Health Strategic Plan ­ Environmental Assessment 2009 Contents Executive Summary environmental assessment to determine Clinical Center strengths, weaknesses, opportunities, and threats

  10. EIS-0379- Rebuild of the Libby (FEC) to Troy Section of BPA’s 115-kilovolt Transmission Line in Libby, Lincoln County, Montana

    Broader source: Energy.gov [DOE]

    This Environmental Impact Statement (EIS) assesses the potential environmental impacts that would result from a proposed Department of Energy (DOE) action on the proposed rebuilding, operation, and maintenance of a 17-mile-long portion of BPA’s Libby to Bonners Ferry 115-kilovolt (kV) Transmission Line in Lincoln County, Montana. The portion to be rebuilt would start at Flathead Electric Cooperative’s (FEC) Libby Substation, in the town of Libby, Montana, and proceed west along an existing right-of-way for about 17 miles, terminating at BPA’s Troy Substation just east of the town of Troy, Montana.

  11. Computing Criticality of Lines in Power Systems Computational Research Div.

    E-Print Network [OSTI]

    Geddes, Cameron Guy Robinson

    Computing Criticality of Lines in Power Systems Ali Pinar Computational Research Div. Lawrence. Planning and operating criteria are designed so that "the interconnected power system shall be operated a vulnerability in the a power system is im- portant, however, system robustness requires identifying all

  12. Argonne National Laboratory institutional plan FY 2001--FY 2006.

    SciTech Connect (OSTI)

    Beggs, S.D.

    2000-12-07T23:59:59.000Z

    This Institutional Plan describes what Argonne management regards as the optimal future development of Laboratory activities. The document outlines the development of both research programs and support operations in the context of the nation's R and D priorities, the missions of the Department of Energy (DOE) and Argonne, and expected resource constraints. The Draft Institutional Plan is the product of many discussions between DOE and Argonne program managers, and it also reflects programmatic priorities developed during Argonne's summer strategic planning process. That process serves additionally to identify new areas of strategic value to DOE and Argonne, to which Laboratory Directed Research and Development funds may be applied. The Draft Plan is provided to the Department before Argonne's On-Site Review. Issuance of the final Institutional Plan in the fall, after further comment and discussion, marks the culmination of the Laboratory's annual planning cycle. Chapter II of this Institutional Plan describes Argonne's missions and roles within the DOE laboratory system, its underlying core competencies in science and technology, and six broad planning objectives whose achievement is considered critical to the future of the Laboratory. Chapter III presents the Laboratory's ''Science and Technology Strategic Plan,'' which summarizes key features of the external environment, presents Argonne's vision, and describes how Argonne's strategic goals and objectives support DOE's four business lines. The balance of Chapter III comprises strategic plans for 23 areas of science and technology at Argonne, grouped according to the four DOE business lines. The Laboratory's 14 major initiatives, presented in Chapter IV, propose important advances in key areas of fundamental science and technology development. The ''Operations and Infrastructure Strategic Plan'' in Chapter V includes strategic plans for human resources; environmental protection, safety, and health; site and facilities; security, export control, and counterintelligence; information management; communications, outreach, and community affairs; performance-based management; and productivity improvement and overhead cost reduction. Finally, Chapter VI provides resource projections that are a reasonable baseline for planning the Laboratory's future.

  13. Greensburg Sustainable Comprehensive Plan

    High Performance Buildings Database

    Greensburg, KS In October 2007, the architectural and planning firm, BNIM, was selected formally by the City of Greensburg, with support from the USDA, to prepare the first phase of a comprehensive master plan to rebuild the city, which provides a framework for the rebuilding of Greensburg based around the principles of economic, social and environmental sustainability. The BNIM Planning team presented the final draft of Greensburg's Comprehensive Plan to the City Council and to a public hearing on January 16, 2008.

  14. Environmental Management System Plan

    E-Print Network [OSTI]

    Fox, Robert

    2009-01-01T23:59:59.000Z

    and locations chemicals are used as well as information about emergency plans and procedures. The current Hazardous

  15. Business Planning Resources

    Broader source: Energy.gov [DOE]

    Business Planning Resources, a presentation of the U.S. Department of Energy's Better Buildings Neighborhood Program.

  16. Waste Management Quality Assurance Plan

    E-Print Network [OSTI]

    Waste Management Group

    2006-01-01T23:59:59.000Z

    Revision 6 Waste Management Quality Assurance Plan Waste6 WM QA Plan Waste Management Quality Assurance Plan LBNL/4 Management Quality Assurance

  17. Corporate and Business Plan

    E-Print Network [OSTI]

    Corporate and Business Plan 2010-2011 #12;Main addresses Forest Research Alice Holt Lodge Farnham Research's Business Plan 2010-2011 ..........................12 Table Contents Table 1 - Income This Corporate and Business Plan sets out FR's aims and strategic objectives. It describes the Key Performance

  18. Multiperiod Refinery Planning Optimization

    E-Print Network [OSTI]

    Grossmann, Ignacio E.

    Multiperiod Refinery Planning Optimization with Nonlinear CDU Models Abdulrahman Alattas, Advisor #12;Refinery Planning Model Development 2 Extension to Multiperiod Planning #12;3 Multiperiod Refinery: refinery configuration Determine · What crude oil to process and in which time period? · The quantities

  19. University of Operations Plan

    E-Print Network [OSTI]

    Firestone, Jeremy

    Management Plan Office of Campus and Public Safety University of Delaware Critical Incident Management Plan Management Plan Office of Campus and Public Safety - 4 - University of Delaware Critical Incident Management and Public Safety - 5 - County of New Castle CD-30 911 Center/Communications CD-31 Department of Police CD-32

  20. University Libraries Technology Plan

    E-Print Network [OSTI]

    Moore, Paul A.

    Libraries Bowling Green State University #12;Table of Contents Introduction ..................................................................19 Page 2 of 19 Technology Plan, 2003-2005 University Libraries Bowling Green State University #12University Libraries Technology Plan 2003-2005 Page 1 of 19 Technology Plan, 2003-2005 University

  1. UCSB Lab-specific Chemical Hygiene Plan 1 EH&S, Rev. 1/07

    E-Print Network [OSTI]

    Akhmedov, Azer

    UCSB Lab-specific Chemical Hygiene Plan 1 EH&S, Rev. 1/07 Chemical Hygiene Plan (CPH) UCSB MRL for Using Engineered Nanomaterials n) SOP for Using Centrifuge #12;UCSB Lab-specific Chemical Hygiene Plan 2://www.mrl.ucsb.edu/mrl/info/administration/mrlsafety.html 2. The Polymer Laboratory Chemical Hygiene Plan (CHP) paper copy or on line. If you have any

  2. Resource-Optimal Planning For An Autonomous Planetary Vehicle

    E-Print Network [OSTI]

    Della Penna, Giuseppe; Magazzeni, Daniele; Mercorio, Fabio; 10.5121/ijaia.2010.1302

    2010-01-01T23:59:59.000Z

    Autonomous planetary vehicles, also known as rovers, are small autonomous vehicles equipped with a variety of sensors used to perform exploration and experiments on a planet's surface. Rovers work in a partially unknown environment, with narrow energy/time/movement constraints and, typically, small computational resources that limit the complexity of on-line planning and scheduling, thus they represent a great challenge in the field of autonomous vehicles. Indeed, formal models for such vehicles usually involve hybrid systems with nonlinear dynamics, which are difficult to handle by most of the current planning algorithms and tools. Therefore, when offline planning of the vehicle activities is required, for example for rovers that operate without a continuous Earth supervision, such planning is often performed on simplified models that are not completely realistic. In this paper we show how the UPMurphi model checking based planning tool can be used to generate resource-optimal plans to control the engine of ...

  3. Lafayette Metropolitan Planning Organization 2030 Transportation Plan

    E-Print Network [OSTI]

    Lafayette Metropolitan Planning Organization

    2010-10-31T23:59:59.000Z

    of Carencro Byron Breaux City-Parish Council Designee John Broussard City-Parish President Designee Vernal Comeaux City-Parish Council Designee Bill Fontenot La Dept of Transportation and Development Lucien Gastineau City-Parish Planning Commission...

  4. Omega Transmission Lines

    E-Print Network [OSTI]

    Vehmas, Joni

    2013-01-01T23:59:59.000Z

    In this paper, we show how bi-anisotropic media with omega-type response can be realized using periodically loaded transmission lines. General conditions for the needed unit cell circuit block are derived. Also, an implementation is shown and analyzed.

  5. Business Plans for Agricultural Producers

    E-Print Network [OSTI]

    McCorkle, Dean; Bevers, Stan

    2008-10-17T23:59:59.000Z

    Natural resources Z Strengths, weaknesses, opportunities ? and threats (SWOT) Mission statement ? Objectives and goals ? Production plan ? Financial plan ? Market plan ? Legal and liability issues ? Insurance ? Succession and estate planning...

  6. Command Line Tools Cloud Computing

    E-Print Network [OSTI]

    Ferrara, Katherine W.

    Command Line Tools Cloud Computing #12;Everybody (or nearly everybody) loves GUI. AWS Command Line of advanced features. After surviving the cloud computing class till now, Your are almost a command line guru! You need AWS command line tools, ec2-api-tools, to maximize the power of AWS cloud computing. Plugging

  7. Printed circuit dispersive transmission line

    DOE Patents [OSTI]

    Ikezi, H.; Lin-Liu, Y.R.; DeGrassie, J.S.

    1991-08-27T23:59:59.000Z

    A printed circuit dispersive transmission line structure is disclosed comprising an insulator, a ground plane formed on one surface of the insulator, a first transmission line formed on a second surface of the insulator, and a second transmission line also formed on the second surface of the insulator and of longer length than the first transmission line and periodically intersecting the first transmission line. In a preferred embodiment, the transmission line structure exhibits highly dispersive characteristics by designing the length of one of the transmission line between two adjacent periodic intersections to be longer than the other. 5 figures.

  8. EA-1843: Imperial Solar Energy Center West, California

    Broader source: Energy.gov [DOE]

    This Environmental Impact Report / Environmental Assessment (EIR/EA), prepared by Bureau of Land Management , evaluates the potential environmental impacts from the CSOLAR Development, LLC, right-of-way (ROW) application to construct, operate, and maintain a 230-kV transmission line. The electric generating facility would connect to the Imperial Valley Substation via a 230-kV transmission line. DOE is a cooperating agency and plans to adopt the EA.

  9. Formation depths of Fraunhofer lines

    E-Print Network [OSTI]

    Gurtovenko, E A

    2015-01-01T23:59:59.000Z

    We have summed up our investigations performed in 1970--1993. The main task of this paper is clearly to show processes of formation of spectral lines as well as their distinction by validity and by location. For 503 photospheric lines of various chemical elements in the wavelength range 300--1000 nm we list in Table the average formation depths of the line depression and the line emission for the line centre and on the half-width of the line, the average formation depths of the continuum emission as well as the effective widths of the layer of the line depression formation. Dependence of average depths of line depression formation on excitation potential, equivalent widths, and central line depth are demonstrated by iron lines.

  10. WECC Variable Generation Planning Reference Book: Appendices

    SciTech Connect (OSTI)

    Makarov, Yuri V.; Du, Pengwei; Etingov, Pavel V.; Ma, Jian; Vyakaranam, Bharat

    2013-05-13T23:59:59.000Z

    The document titled “WECC Variable Generation Planning Reference Book”. This book is divided into two volumes; one is the main document (volume 1)and the other is appendices (volume 2). The main document is a collection of the best practices and the information regarding the application and impact of variables generation on power system planning. This volume (appendices) has additional information on the following topics: Probabilistic load flow problems. 2. Additional useful indices. 3. high-impact low-frequency (HILF) events. 4. Examples of wide-area nomograms. 5. Transmission line ratings, types of dynamic rating methods. 6. Relative costs per MW-km of different electric power transmission technologies. 7. Ultra-high voltage (UHV) transmission. 8.High voltage direct current (VSC-HVDC). 9. HVDC. 10. Rewiring of existing transmission lines. 11. High-temperature low sag (HTLS) conductors. 12. The direct method and energy functions for transient stability analysis in power systems. 13.Blackouts caused by voltage instability. 14. Algorithm for parameter continuation predictor-corrector methods. 15. Approximation techniques available for security regions. 16. Impacts of wind power on power system small signals stability. 17. FIDVR. 18. FACTS. 19. European planning standard and practices. 20. International experience in wind and solar energy sources. 21. Western Renewable Energy Zones (WREZ). 22. various energy storage technologies. 23. demand response. 24. BA consolidation and cooperation options. 25. generator power management requirements and 26. European planning guidelines.

  11. Tucson Electric Power Company Sahuarita-Nogales Transmission Line Draft Environmental Impact Statement

    SciTech Connect (OSTI)

    N /A

    2003-08-27T23:59:59.000Z

    Tucson Electric Power Company (TEP) has applied to the U.S. Department of Energy (DOE) for a Presidential Permit to construct and operate a double-circuit, 345,000-volt (345-kV) electric transmission line across the United States border with Mexico. Under Executive Order (EO) 10485 of September 3, 1953, as amended by EO 12038 of February 3, 1978, a Presidential Permit is required to construct, connect, operate, or maintain facilities at the U.S. international border for the transmission of electric energy between the United States and a foreign country. DOE has determined that the issuance of a Presidential Permit to TEP for the proposed project would constitute a major Federal action that may have a significant impact on the environment within the meaning of the ''National Environmental Policy Act of 1969'' (NEPA) 42 United States Code (U.S.C.) {section}4321 et seq. For this reason, DOE has prepared this Draft Environmental Impact Statement (EIS) to evaluate potential environmental impacts from the proposed Federal action (granting a Presidential Permit for the proposed transmission facilities) and reasonable alternatives, including the No Action Alternative. This EIS was prepared in accordance with Section 102(2)(c) of NEPA, Council of Environmental Quality (CEQ) regulations (40 Code of Federal Regulations [CFR] 1500-1508), and DOE NEPA Implementing Procedures (10 CFR 1021). DOE is the lead Federal Agency, as defined by 40 CFR 1501.5. The U.S. Department of Agriculture Forest Service (USFS), the Bureau of Land Management (BLM) of the U.S. Department of the Interior, and the U.S. Section of the International Boundary and Water Commission, U.S. and Mexico (USIBWC), are cooperating agencies. Each of these organizations will use the EIS for its own NEPA purposes, as described in the Federal Agencies' Purpose and Need and Authorizing Actions section of this summary. The 345-kV double-circuit transmission line would consist of twelve transmission line wires, or conductors, and two neutral ground wires that would provide both lightning protection and fiber optic communications, on a single set of support structures. The transmission line would originate at TEP's existing South Substation (which TEP would expand), in the vicinity of Sahuarita, Arizona, and interconnect with the Citizens Communications (Citizens) system at a Gateway Substation that TEP would construct west of Nogales, Arizona. The double-circuit transmission line would continue from the Gateway Substation south to cross the U.S.-Mexico border and extend approximately 60 miles (mi) (98 kilometers [km]) into the Sonoran region of Mexico, connecting with the Comision Federal de Electricidad (CFE, the national electric utility of Mexico) at CFE's Santa Ana Substation.

  12. Operation of Lanzhou all permanent electron cyclotron resonance ion source No. 2 on 320 kV platform with highly charged ions

    SciTech Connect (OSTI)

    Lu, W., E-mail: luwang@impcas.ac.cn [Institute of Modern Physics, CAS, Lanzhou 730000 (China); University of Chinese Academy of Sciences, Beijing 100049 (China); Li, J. Y.; Kang, L.; Liu, H. P.; Li, H.; Li, J. D.; Sun, L. T.; Ma, X. W. [Institute of Modern Physics, CAS, Lanzhou 730000 (China)] [Institute of Modern Physics, CAS, Lanzhou 730000 (China)

    2014-02-15T23:59:59.000Z

    The 320 kV platform for multi-discipline research with highly charged ions is a heavy ion beam acceleration instrument developed by Institute of Modern Physics, which is dedicated to basic scientific researches such as plasma, atom, material physics, and astrophysics, etc. The platform has delivered ion beams of 400 species for 36?000 h. The average operation time is around 5000 h/year. With the beams provided by the platform, lots of outstanding progresses were made in various research fields. The ion source of the platform is an all-permanent magnet electron cyclotron resonance ion source, LAPECR2 (Lanzhou All Permanent ECR ion source No. 2). The maximum axial magnetic fields are 1.28 T at injection and 1.07 T at extraction, and the radial magnetic field is up to 1.21 T at the inner wall of the plasma chamber. The ion source is capable to produce low, medium, and high charge state gaseous and metallic ion beams, such as H{sup +}, {sup 40}Ar{sup 8+}, {sup 129}Xe{sup 30+}, {sup 209}Bi{sup 33+}, etc. This paper will present the latest result of LAPECR2 and the routine operation status for the high voltage platform.

  13. Drill string transmission line

    DOE Patents [OSTI]

    Hall, David R. (Provo, UT); Hall, Jr., H. Tracy (Provo, UT); Pixton, David S. (Lehi, UT); Bradford, Kline (Orem, UT); Fox, Joe (Spanish Fork, UT)

    2006-03-28T23:59:59.000Z

    A transmission line assembly for transmitting information along a downhole tool comprising a pin end, a box end, and a central bore traveling between the pin end and the box end, is disclosed in one embodiment of the invention as including a protective conduit. A transmission line is routed through the protective conduit. The protective conduit is routed through the central bore and the ends of the protective conduit are routed through channels formed in the pin end and box end of the downhole tool. The protective conduit is elastically forced into a spiral or other non-linear path along the interior surface of the central bore by compressing the protective conduit to a length within the downhole tool shorter than the protective conduit.

  14. Transmission line: design manual

    SciTech Connect (OSTI)

    Farr, H.H.

    1980-01-01T23:59:59.000Z

    The purpose of this manual is to outline the various requirements for, and the procedures to be followed in the design of power transmission lines by the Bureau of Reclamation, US Department of the Interior. Numerous design studies, which have been made on specific aspects of transmission line design, are included with explanations of their applications. Information is presented concerning such aspects as selection of type of construction, conductor sags and tensions, insulation, lightning protection, clearance patterns, galloping conductors, structure limitation and guying charts, and structure spotting. Structure design examples are limited to wood-pole construction. Interpretations of the National Electrical Safety Code and other codes are made as required. Some of the example problems were developed when the sixth edition of NESC was current, and are so noted; however, most examples use the 1977 edition of NESC.

  15. IDC Integrated Master Plan.

    SciTech Connect (OSTI)

    Clifford, David J.; Harris, James M.

    2014-12-01T23:59:59.000Z

    This is the IDC Re-Engineering Phase 2 project Integrated Master Plan (IMP). The IMP presents the major accomplishments planned over time to re-engineer the IDC system. The IMP and the associate Integrated Master Schedule (IMS) are used for planning, scheduling, executing, and tracking the project technical work efforts. REVISIONS Version Date Author/Team Revision Description Authorized by V1.0 12/2014 IDC Re- engineering Project Team Initial delivery M. Harris

  16. Community Relations Plan

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    the Permittees and the public are documented during the Hazardous Waste Facility Permit Community Relations Plan development. Contact Environmental Communication & Public...

  17. MITG Test Plan

    SciTech Connect (OSTI)

    Eck, Marshall B.

    1981-08-01T23:59:59.000Z

    The plan presented is for the testing of a prototypical slice of the Modular Isotopic Thermoelectric Generator (MITG). Cross Reference T48-1.

  18. Climate Action Plan (Virginia)

    Broader source: Energy.gov [DOE]

    Governor Timothy M. Kaine established the Governor's Commission on Climate Change in December 2007. The commission prepared a plan for Virginia that identified ways to reduce greenhouse gas...

  19. State Energy Strategic Planning

    Broader source: Energy.gov [DOE]

    U.S. Department of Energy (DOE) Technical Assistance Program (TAP) presentation at a TAP webinar held on April 3, 2013 and dealing with state energy strategic planning.

  20. Navajo Marketing Plan Process

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    River Basin Project Act General Power Contract Provisions (GCPC) - 090107 Hoover Power Plant Act of 1984 Navajo Marketing Plan Area Map Navajo Sales Enabling Agreement FINAL -...

  1. Environmental Protection Implementation Plan

    SciTech Connect (OSTI)

    Brekke, D.D.

    1995-11-01T23:59:59.000Z

    This Environmental Protection Implementation Plan is intended to ensure that the environmental program objectives of Department of Energy Order 5400.1 are achieved at SNL/California. This document states SNL/California`s commitment to conduct its operations in an environmentally safe and responsible manner. The Environmental Protection Implementation Plan helps management and staff comply with applicable environmental responsibilities. This report focuses on the following: notification of environmental occurrences; general planning and reporting; special programs and plans; environmental monitoring program; and quality assurance and data verification.

  2. Strategic Health Workforce Planning

    E-Print Network [OSTI]

    2013-05-11T23:59:59.000Z

    May 11, 2013 ... linked to long-term workforce management plans of doctors, nurses and .... survey [53] particularly highlight the need to research long-term ...

  3. Individual Development Plan

    Broader source: Energy.gov [DOE]

    To be effective, training decisions made at the organizational and departmental levels must be informed by the needs of the individual. An individual development plan (IDP) is cooperatively...

  4. 2.3-MW Medium-Voltage, Three-Level Wind Energy Inverter Applying a Unique Bus Structure and 4.5-kV Si/SiC Hybrid Isolated Power Modules: Preprint

    SciTech Connect (OSTI)

    Erdman, W.; Keller, J.; Grider, D.; VanBrunt, E.

    2014-11-01T23:59:59.000Z

    A high-efficiency, 2.3-MW, medium-voltage, three-level inverter utilizing 4.5-kV Si/SiC (silicon carbide) hybrid modules for wind energy applications is discussed. The inverter addresses recent trends in siting the inverter within the base of multimegawatt turbine towers. A simplified split, three-layer laminated bus structure that maintains low parasitic inductances is introduced along with a low-voltage, high-current test method for determining these inductances. Feed-thru bushings, edge fill methods, and other design features of the laminated bus structure provide voltage isolation that is consistent with the 10.4-kV module isolation levels. Inverter efficiency improvement is a result of the (essential) elimination of the reverse recovery charge present in 4.5-kV Si PIN diodes, which can produce a significant reduction in diode turn-off losses as well as insulated-gate bipolar transistor (IGBT) turn-on losses. The hybrid modules are supplied in industry-standard 140 mm x 130 mm and 190 mm x 130 mm packages to demonstrate direct module substitution into existing inverter designs. A focus on laminated bus/capacitor-bank/module subassembly level switching performance is presented.

  5. COMMUNITY INVOLVEMENT PLAN APRIL 15, 1999.

    SciTech Connect (OSTI)

    GEIGER,K.

    1999-04-15T23:59:59.000Z

    This Community Involvement Plan has been prepared by the Brookhaven National Laboratory's Community Involvement Office with the input of the community, Laboratory employees and representatives of the U.S. Department of Energy. The process to develop the plan began with the formation of a focus group consisting of representatives from: the community at large; special interest groups within the community; the business community; Laboratory retirees; senior and line management from the Laboratory; and the U.S. Department of Energy. The focus group reviewed an initial outline developed by the Office of Community involvement, held in-depth roundtable discussions of community involvement needs, and created a draft plan based on their discussions. A workshop was held to present the draft Community Involvement Plan to a wider audience for their input and insights on how Brookhaven should involve the community in decision making. This workshop was advertised in local newspapers and within the Laboratory. It was attended by community members, special interest group representatives, Laboratory employees and managers, U.S. Department of Energy-Brookhaven Group management, and members of the Laboratory's Community Advisory Council. The results of the workshop discussions are incorporated in this plan.

  6. Recent Developments in the Regulation of Electric Utility Resource Planning in Texas

    E-Print Network [OSTI]

    Totten, J.; Adib, P.; Matlock, R.; Treadway, N.

    The Texas Legislature has charged the Public Utility Commission of Texas with the responsibility to license utility power plants and transmission lines, and develop a statewide electrical energy plan. Related duties include the encouragement...

  7. Utility Lines and Facilities (Montana)

    Broader source: Energy.gov [DOE]

    These regulations apply to the construction of utility and power lines and facilities. They address the use of public right-of-ways for such construction, underground power lines, and construction...

  8. NIF Projects Controls and Information Systems Software Quality Assurance Plan

    SciTech Connect (OSTI)

    Fishler, B

    2011-03-18T23:59:59.000Z

    Quality achievement for the National Ignition Facility (NIF) and the National Ignition Campaign (NIC) is the responsibility of the NIF Projects line organization as described in the NIF and Photon Science Directorate Quality Assurance Plan (NIF QA Plan). This Software Quality Assurance Plan (SQAP) is subordinate to the NIF QA Plan and establishes quality assurance (QA) activities for the software subsystems within Controls and Information Systems (CIS). This SQAP implements an activity level software quality assurance plan for NIF Projects as required by the LLNL Institutional Software Quality Assurance Program (ISQAP). Planned QA activities help achieve, assess, and maintain appropriate quality of software developed and/or acquired for control systems, shot data systems, laser performance modeling systems, business applications, industrial control and safety systems, and information technology systems. The objective of this SQAP is to ensure that appropriate controls are developed and implemented for management planning, work execution, and quality assessment of the CIS organization's software activities. The CIS line organization places special QA emphasis on rigorous configuration control, change management, testing, and issue tracking to help achieve its quality goals.

  9. Implementing Motor Decision Plans

    E-Print Network [OSTI]

    Elliott, R. N.

    The first step to reducing energy costs and increasing reliability in motors is to establish a motor plan. A motor plan allows decisions to be made in advance of motor failure, and increases the options available. By contrast, most motor decisions...

  10. Environmental protection Implementation Plan

    SciTech Connect (OSTI)

    R. C. Holland

    1999-12-01T23:59:59.000Z

    This ``Environmental Protection Implementation Plan'' is intended to ensure that the environmental program objectives of Department of Energy Order 5400.1 are achieved at SNL/California. This document states SNL/California's commitment to conduct its operations in an environmentally safe and responsible manner. The ``Environmental Protection Implementation Plan'' helps management and staff comply with applicable environmental responsibilities.

  11. Supporting Document Strategic Plan

    E-Print Network [OSTI]

    Auckland, University of

    1 Supporting Document Strategic Plan 2013­2020 #12;2 Supporting Document Strategic Plan 2013 more critical to the University's future than was the case in 2005. The purpose of this document are summarised via a SWOT analysis in Appendix 1. This document should therefore be read in conjunction

  12. Maersk Line Equipment guide

    National Nuclear Security Administration (NNSA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742EnergyOn AprilA Approved:AdministrationAnalysisDarby/%2AOU1a ComplexMaersk Line Equipment

  13. Transportation Institutional Plan

    SciTech Connect (OSTI)

    Not Available

    1986-08-01T23:59:59.000Z

    This Institutional Plan is divided into three chapters. Chapter 1 provides background information, discusses the purposes of the Plan and the policy guidance for establishing the transportation system, and describes the projected system and the plans for its integrated development. Chapter 2 discusses the major participants who must interact to build the system. Chapter 3 suggests mechanisms for interaction that will foster wide participation in program planning and implementation and provides a framework for managing and resolving the issues related to development and operation of the transportation system. A list of acronyms and a glossary are included for the reader's convenience. Also included in this Plan are four appendices. Of particular importance is Appendix A, which includes detailed discussion of specific transportation issues. Appendices B, C, and D provide supporting material to assist the reader in understanding the roles of the involved institutions.

  14. The Sellafield Plan - 12458

    SciTech Connect (OSTI)

    Irving, Iain [Stakeholder Relations Director, Sellafield Ltd, Cumbria (United Kingdom)

    2012-07-01T23:59:59.000Z

    The Sellafield Performance Plan represents the start of a new era for the Sellafield site. It is a key driver in the Nuclear Management Partners mission to make Sellafield safer, cleaner, more productive, more cost effective and a better neighbour. When published in summer 2011, the Sellafield Performance Plan set out exactly what work would be completed at Sellafield between 2010/11 and 2025/26, how all of the facilities on the site interact, and what new facilities would be needed in order to deliver the risk and hazard reduction mission. The plan is the first credible and underpinned lifetime plan for the Sellafield site - the most complex part of the UK's civil nuclear estate. Under the Sellafield Performance Plan there are projected to be more jobs longer creating opportunities for the site, its workforce and the economic stability of West Cumbria. The Sellafield Ltd performance plan sets out how NMP will apply their global experience to improve operations, generate efficiencies and deliver detailed programmes of work with the aim of accelerating decommissioning and providing value for money. Successful delivery of the plan will also ensure the site continues to effectively operate critical national infrastructure that supports the UK's energy programme, and maintains the safe and secure management and storage of nuclear materials. The NDA and UK Government have demonstrated their confidence in NMP and Sellafield Ltd's capability to deliver this plan by providing the highest-ever Annual Site Funding Limit for the site in 2011/12. The Sellafield Performance Plan also creates both the foundation and the environment for a vibrant West Cumbrian economy through significant opportunities for the local supply chain and real prospects for further inward investment. By working flexibly and accelerating the decommissioning programme, the plan provides the opportunity for significant retraining to adapt to future challenges on the site and for other potential new nuclear missions in West Cumbria. (authors)

  15. Wyss Institute Chemical Hygiene Plan CHEMICAL HYGIENE PLAN

    E-Print Network [OSTI]

    Napp, Nils

    Wyss Institute Chemical Hygiene Plan CHEMICAL HYGIENE PLAN The Wyss Institute for Biologically Inspired Engineering June 2014 #12;Wyss Institute Chemical Hygiene Plan TABLE OF CONTENTS 1.0 POLICY.......................................................................................... 2 2.1 CHEMICAL HYGIENE OFFICER

  16. DRAFT Fifteenmile Management Plan 5. Fifteenmile Subbasin Management Plan

    E-Print Network [OSTI]

    DRAFT Fifteenmile Management Plan 5. Fifteenmile Subbasin Management Plan DRAFT May 25 2004 Group 5. FIFTEENMILE SUBBASIN MANAGEMENT PLAN............................................... 38 5.5.2. Consistency with the Clean Water Act, Total Maximum Daily Loads and Existing Water Quality

  17. A long-pulse repetitive operation magnetically insulated transmission line oscillator

    SciTech Connect (OSTI)

    Fan, Yu-Wei; Zhong, Hui-Huang; Zhang, Jian-De; Shu, Ting; Liu, Jin Liang [College of Optoelectric Science and Engineering, National University of Defense Technology, Changsha 410073 (China)

    2014-05-15T23:59:59.000Z

    The improved magnetically insulated transmission line oscillator (MILO) is a gigawatt-class L-band high power microwave tube. It has allowed us to generate 3.1 GW pulse of 40 ns duration in the single-pulse operation and 500 MW pulse of 25 ns duration in the repetition rate operation. However, because of the severe impedance mismatch, the power conversion efficiency is only about 4% in the repetition rate operation. In order to eliminate the impedance mismatch and obtain repetitive long-pulse high-power microwave (HPM), a series of experiments are carried out and the recent progress is presented in this paper. In the single-pulse operation, when the diode voltage is 466 kV and current is 41.6 kA, the radiated microwave power is above 2.2 GW, the pulse duration is above 102 ns, the microwave frequency is about 1.74 GHz, and the power conversion efficiency is about 11.5%. In the repetition rate operation, under the condition of the diode voltage about 400 kV, beam current about 38 kA, the radiated microwave power is about 1.0 GW, the pulse duration is about 85 ns. Moreover, the radiated microwave power and the pulse duration decline little by little when the shot numbers increase gradually. The experimental results show that the impedance matching is a vital factor for HPM systems and one of the major technical challenges is to improve the cathode for the repetition rate operation MILO.

  18. BUILDING A RISK MANAGEMENT PLAN BUILDING A RISK MANAGEMENT PL LDING A RISK MANAGEMENT PLAN BUILDING A RISK MANAGEMENT PLAN

    E-Print Network [OSTI]

    Florida, University of

    BUILDING A RISK MANAGEMENT PLAN BUILDING A RISK MANAGEMENT PL LDING A RISK MANAGEMENT PLAN BUILDING A RISK MANAGEMENT PLAN MANAGEMENT PLAN BUILDING A RISK MANAGEMENT PLAN BUILDING A R RISK MANAGEMENT PLAN BUILDING A RISK MANAGEMENT PLAN BUILDIN T PLAN BUILDING A RISK MANAGEMENT PLAN BUILDING A RISK MANAGEM

  19. Public affairs plan

    SciTech Connect (OSTI)

    Not Available

    1994-09-01T23:59:59.000Z

    The purpose of the Uranium Mill Tailings Remedial Action (UMTRA) Project Public Affairs Plan is to establish goals for the Fiscal Year 1995 UMTRA public affairs program and identify specific activities to be conducted during the year. It also describes the roles of various agencies involved in the conduct of the public affairs program and defines the functions of the Technical Assistance Contractor (TAC) Public Affairs Department. It integrates and replaces the Public Participation Plan (DOE/AL/62350-47D) and Public Information Plan (DOE/AL/623590-71). The plan describes the US Department of Energy`s (DOE) plans to keep stakeholders and other members of the public informed about project policies, plans, and activities, and provide opportunities for stakeholders and interested segments of the public to participate in project decision-making processes. The plan applies to the UMTRA Project Office; the DOE Albuquerque Operations Office, Office of Intergovernmental and External Affairs (OIEA); the UMTRA TAC; the UMTRA Remedial Action Contractor (RAC); and other cooperating agencies.

  20. Alex Linares UPP 502, Planning Skills, Fall 2012

    E-Print Network [OSTI]

    Illinois at Chicago, University of

    and brickyards. In 1852, the opening of the Rock Island railroad also contributed to Blue Island's growth. Blue to block traffic on the Rock Island rail line. On June 30th , 1894, two workers blocked the Rock Island. Source: 2005 Land Use Inventory, Version 1.0, CMAP #12;Alex Linares UPP 502, Planning Skills, Fall 2012

  1. Texas Tech University Hygiene Plan

    E-Print Network [OSTI]

    Rock, Chris

    Texas Tech University Chemical Hygiene Plan (Laboratory Safety Manual) January 2013 #12;TABLE C ­ Chemical Hygiene Checklist #12;TEXAS TECH UNIVERSITY CHEMICAL HYGIENE PLAN January 2013 1 PURPOSE OF THIS PLAN It is the desire

  2. EIS-0116-S1: Final Supplemental Environmental Impact Statement for the Blue River-Gore Pass Portion of the Hayden-Blue River Transmission Line Project, Grand and Summit Counties, Colorado

    Broader source: Energy.gov [DOE]

    This supplemental environmental impact statement by the Western Area Power Administration assesses the environmental effects of constructing, operating, and maintaining about 30 miles of 230/345-kV transmission line between the existing Gore Pass Substation northwest of Kremmling, Colorado, and a proposed new substation (not part of this action) near the Ute Pass Road. Alternatives assessed included routing and design alternatives plus the alternatives addressed in the Hayden-Blue River Final EIS, issued by the Rural Electrification Administration in July 1982 and adopted by DOE in June 1985 (see DOE/EIS-0116).

  3. PREVIOUS GEOSCIENCES INTERNSHIP EXPERIENCES CITY PLANNING

    E-Print Network [OSTI]

    Kurapov, Alexander

    PREVIOUS GEOSCIENCES INTERNSHIP EXPERIENCES CITY PLANNING TRANSPORTATION PLANNING LAND USE (HIGHER EDUCATION) LAND USE PLANNING INTERNSHIPS CH2M-HILL PLANNING AND ENGINEERING CITY OF ANAHEIM

  4. Unification of the a priori inconsistencies checking among assembly constraints in assembly sequence planning

    E-Print Network [OSTI]

    Paris-Sud XI, Université de

    sequence planning Christophe Perrard UMR CNRS 6174 AS2M Department, University, 54010 Nancy Cedex, France e-mail: eric.bonjour@univ-lorraine.fr Abstract Sequence planning generation is an important problem in assembly line design. A good assembly sequence can help to reduce

  5. Waste Management Plan for the Oak Ridge National Remedial Investigation/Feasibility Study

    SciTech Connect (OSTI)

    Not Available

    1988-04-01T23:59:59.000Z

    In accordance with the requirements of the Remedial Investigation/Feasibility Study (RI/FS) Project Quality Assurance Plan, this Waste Management Plan establishes clear lines of responsibility and authority, documentation requirements, and operational guidance for the collection, identification, segregation, classification, packaging, certification, and storage/disposal of wastes. These subjects are discussed in the subsequent sections of this document.

  6. Proposal of a gigawatt-class L/Ku dual-band magnetically insulated transmission line oscillator

    SciTech Connect (OSTI)

    Ju, J.-C., E-mail: jujinchuan@126.com; Fan, Y.-W.; Shu, T.; Zhong, H.-H. [College of Optoelectronic Science and Engineering, National University of Defense Technology, Changsha 410073 (China)

    2014-10-15T23:59:59.000Z

    We present a gigawatt (GW)-class magnetically insulated transmission line oscillator (MILO) which is capable of generating dual-band high power microwaves (HPMs). The proposed device, deriving from previously studied complex MILO and dual-frequency MILO, is designed to produce two HPMs in L-band and Ku-band, respectively. It is found in particle-in-cell (PIC) simulation that when the diode voltage is 610?kV, HPMs with frequencies of 1.72 GHz and 14.6?GHz can be achieved with powers of 3.3?GW and 2.4?GW, respectively. The corresponding total power conversion efficiency is approximately 12.8%. Power difference of the two generated HPMs is approximately 1.4?dB, and frequency difference of them reaches a level as high as ?10?dB.

  7. Community Energy Stategic Planning Resources

    Broader source: Energy.gov (indexed) [DOE]

    Community Energy Strategic Planning Resources Technical Assistance Program January 24 th , 2013 2 Agenda 1. Welcome & overview 2. What is a community energy strategic plan and why...

  8. Environmental Monitoring Plan

    SciTech Connect (OSTI)

    Holland, R.C. [Science Applications International Corp., San Diego, CA (United States)

    1993-07-01T23:59:59.000Z

    This Environmental Monitoring Plan was written to fulfill the requirements of Department of Energy (DOE) Order 5400.1 and DOE Environmental Regulatory Guide DOE/EH 0173T. This Plan documents the background, organizational structure, and methods used for effluent monitoring and environmental surveillance at Sandia National Laboratories/California. The design, rationale, and historical results of the environmental monitoring system are discussed in detail. Throughout the Plan, recommendations for improvements to the monitoring system are made. This revision to the Environmental Monitoring Plan was written to document the changes made to the Monitoring Program during 1992. Some of the data (most notably the statistical analyses of past monitoring data) has not been changed.

  9. Constraints and AI Planning 

    E-Print Network [OSTI]

    Nareyek, A; Freuder, E C; Fourer, R; Giunchiglia, R P; Kautz, H; Rintanen, J; Tate, Austin

    2005-01-01T23:59:59.000Z

    Tackling real-world problems often requires to take various types of constraints into account. Such constraint types range from simple numerical comparators to complex resources. This article describes how planning techniques ...

  10. Conservation Plan Issues

    E-Print Network [OSTI]

    : Capacity Base Plan - Least Cost January Sustained Peak Reserve 0% 10% 20% 30% 40% 50% 60% 2010 2011 2012 Sustained Peak Reserve 0% 10% 20% 30% 40% 50% 60% 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

  11. Planning a Prescribed Burn

    E-Print Network [OSTI]

    Hanselka, C. Wayne

    2009-04-01T23:59:59.000Z

    This leaflet explains how to plan for adequate fuel for a prescribed burn, control the fire, notify the proper authority, manage the burn itself, and conduct follow-up management. A ranch checklist for prescribed burning is included....

  12. Environmental Implementation Plan

    SciTech Connect (OSTI)

    Not Available

    1993-03-15T23:59:59.000Z

    The purpose of the Environmental Implementation Plan (EIP) is to show the current and future (five years) environmental plans from individual site organizations and divisions, as well as site environmental programs and initiatives which are designed to protect the environment and meet or exceed changing environmental/regulatory requirements. Communicating with site organizations, departments, and committees is essential in making the site`s environmental-planning process work. The EIP gives the site the what, when, how, and why for environmental requirements. Through teamwork and proactive planning, a partnership for environmental excellence is formed to achieve the site vision for SRS to become the recognized model for Environmental Excellence in the Department of Energy`s Nuclear Weapons Complex.

  13. Environmental Implementation Plan

    SciTech Connect (OSTI)

    Not Available

    1993-03-15T23:59:59.000Z

    The purpose of the Environmental Implementation Plan (EIP) is to show the current and future (five years) environmental plans from individual site organizations and divisions, as well as site environmental programs and initiatives which are designed to protect the environment and meet or exceed changing environmental/regulatory requirements. Communicating with site organizations, departments, and committees is essential in making the site's environmental-planning process work. The EIP gives the site the what, when, how, and why for environmental requirements. Through teamwork and proactive planning, a partnership for environmental excellence is formed to achieve the site vision for SRS to become the recognized model for Environmental Excellence in the Department of Energy's Nuclear Weapons Complex.

  14. Technical Planning Basis

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2007-07-11T23:59:59.000Z

    The Guide assists DOE/NNSA field elements and operating contractors in identifying and analyzing hazards at facilities and sites to provide the technical planning basis for emergency management programs. Cancels DOE G 151.1-1, Volume 2.

  15. Developing a Marketing Plan

    E-Print Network [OSTI]

    Bevers, Stan; Waller, Mark L.; Amosson, Stephen H.; McCorkle, Dean

    2009-03-02T23:59:59.000Z

    Developing a good marketing plan will help you identify and quantify costs, set price goals, determine potential price outlook, examine production and price risk, and develop a strategy for marketing your crop. This publication describes...

  16. Quality Assurance Project Plan

    SciTech Connect (OSTI)

    Holland, R. C.

    1998-06-01T23:59:59.000Z

    This Quality Assurance Project Plan documents the quality assurance activities for the Wastewater/Stormwater/Groundwater and Environmental Surveillance Programs. This QAPP was prepared in accordance with DOE guidance on compliance with 10CFR830.120.

  17. Hygiene Plan ENVIRONMENTAL

    E-Print Network [OSTI]

    Firestone, Jeremy

    Chemical Hygiene Plan ENVIRONMENTAL HEALTH & SAFETY #12;University Of Delaware Chemical Hygiene/oshaweb/owadisp.show_document?p_table=STANDARDS&p_id=10106 · National Research Council Recommendations Concerning Chemical Hygiene in Laboratories (Non

  18. Developing a Marketing Plan 

    E-Print Network [OSTI]

    Bevers, Stan; Waller, Mark L.; Amosson, Stephen H.; McCorkle, Dean

    2009-03-02T23:59:59.000Z

    Developing a good marketing plan will help you identify and quantify costs, set price goals, determine potential price outlook, examine production and price risk, and develop a strategy for marketing your crop. This publication describes...

  19. AWARD FEE PLAN

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AWARD FEE PLAN FOR LAT A Environmental Services of Kentucky, LLC Paducah Remediation Contract DE-AC30-10CC40020 CONCUR: Rob Seifert, Paducah Re e iation Engineer and Deputy...

  20. Metropolitan Transportation Plan 2035

    E-Print Network [OSTI]

    Tyler Area Metropolitan Planning Organization

    2009-12-04T23:59:59.000Z

    Adopted by the Tyler Area MPO Policy Committee December 4, 2009 METROPOLITAN TRANSPORTATION PLAN 2035 Revised April 22, 2010 Adopted by the Tyler Area MPO Policy Committee December 4, 2009 Amended/Revised April 22, 2010 Prepared by: Bucher..., Willis, and Ratliff Corporation 1828 East Southeast Loop 323, Suite 202 Tyler, Texas 75701 903.581.7844 This Document Serves as an Update to the Tyler Area Metropolitan Transportation Plan 2030. Portions of that Document were Unchanged and Appear...

  1. LCLS Undulator Fiducialization Plan

    SciTech Connect (OSTI)

    Wolf, Zachary

    2010-11-24T23:59:59.000Z

    This note presents the LCLS undulator fiducialization plan. The undulators will be fiducialized in the Magnetic Measurement Facility at SLAC. The note begins by summarizing the requirements for the fiducialization. A brief discussion of the measurement equipment is presented, followed by the methods used to perform the fiducialization and check the results. This is followed by the detailed fiducialization plan in which each step is enumerated. Finally, the measurement results and data storage format are presented.

  2. Environmental implementation plan

    SciTech Connect (OSTI)

    Peterson, G.L.

    1994-10-04T23:59:59.000Z

    In this document, the Savannah River site environmental programs and plans from DOE contractors and Westinghouse Savannah River Company divisions/departments are presented along with the environmental coordinator for each program. The objectives are to enhase communication of existing or planned programs to do the following: identify activities required for meeting environmental needs; identify needing resources and a schedule to accomplish those activities; promote share-savings and consistency in those activities.

  3. SEA effectiveness for landscape and master planning: An investigation in Sardinia

    SciTech Connect (OSTI)

    De Montis, Andrea, E-mail: andreadm@uniss.it [Dipartimento di Agraria, Sezione Ingegneria del Territorio, Universitŕ degli Studi di Sassari, Viale Italia, 39, 07100 Sassari (Italy); Ledda, Antonio, E-mail: antonioledda@gmail.com [Dipartimento di Agraria, Sezione Ingegneria del Territorio, Universitŕ degli Studi di Sassari, Viale Italia, 39, 07100 Sassari (Italy); Caschili, Simone, E-mail: s.caschili@ucl.ac.uk [UCL QASER Lab and Centre for Advanced Spatial Analysis, University College London, Gower Street, London WC1E 7HB (United Kingdom); Ganciu, Amedeo, E-mail: dott.amedeoganciu@gmail.com [Dipartimento di Agraria, Sezione Ingegneria del Territorio, Universitŕ degli Studi di Sassari, Viale Italia, 39, 07100 Sassari (Italy); Barra, Mario, E-mail: barra@uniss.it [Dipartimento di Agraria, Sezione Ingegneria del Territorio, Universitŕ degli Studi di Sassari, Viale Italia, 39, 07100 Sassari (Italy)

    2014-07-01T23:59:59.000Z

    The Italian administrative bodies and planning agencies have embraced with mixed feedbacks the introduction of Strategic Environmental Assessment (SEA) through the European Directive 2001/42/EC. Concurrently, regional and local spatial planning practice have been characterized by a new approach inspired by landscape planning. The Italian region of Sardinia has been one of the pioneering administrative bodies in the Italian and European arena that has adopted landscape principles for the construction of its regional master plan (PPR, Piano Paesaggistico Regionale). Municipalities are now carrying out the review of their master plans to the PPR's prescriptions and indications. Against this background, the aim of this paper is to assess the level of SEA implementation in the municipal master plans of Sardinia, six years after the approval of the PPR. Rooted in the SEA international literature we construct a modular and adaptable on-line survey for officers involved in the review of municipal master plans. The results show that many Sardinian municipalities have not reviewed their master plans to the PPR's regulations yet and only a few municipalities have started this review process according to the SEA procedure. - Highlights: • We study strategic environmental assessment (SEA) effectiveness on land use plans • Four SEA implementation key issues are drawn from international literature • Data collection has included an on-line survey with close and open questions • Results indicate that SEA has been poorly implemented in landscape and master plans • Weak aspects include planning alternatives, financial resources, and monitoring.

  4. Intern experience at Electricity Directorate of Bahrain: an internship report

    E-Print Network [OSTI]

    Aljamea, Najeeb Ahmad

    2013-03-13T23:59:59.000Z

    n ......................................27 8. A VDU Picture of a Substation .............................................................. 35 9. A VDU Picutre of the Alarm List................................................................ 38 10... consists of : - Over-head lines : 33kv &66kv - Underground cables : 33kv & 66kv & 220kv - Substations: 33 /llkv & 66 /llkv & 220/66kv. Associated with this equipment is a protection system which utilises a network of pilot cables. The transmission...

  5. Public affairs plan

    SciTech Connect (OSTI)

    NONE

    1995-09-01T23:59:59.000Z

    The purpose of the Uranium Mill Tailings Remedial Action (UMTRA) Project Public Affairs Plan is to establish goals for the fiscal year (FY) 1996 UMTRA Project public affairs program and to identify specific activities to be conducted during the year. It describes the roles of various agencies involved in the public affairs program and defines the functions of the UMTRA Project Technical Assistance Contractor (TAC) Public Affairs Department. It replaces the FY 1995 Public Affairs Plan (DOE/AL/62350-154). The plan also describes the US Department of Energy`s (DOE) plans to keep stakeholders and other members of the public informed about UMTRA Project policies, plans, and activities, and provide opportunities for stakeholders and interested segments of the public to participate in UMTRA Project decision-making processes. The plan applies to the UMTRA Project Team; the DOE Grand Junction Projects Office (GJPO); the DOE Albuquerque Operations Office, Office of Public Affairs (OPA); the TAC; the UMTRA Project Remedial Action Contractor (RAC); and other cooperating agencies.

  6. Part I: Overall Plan 2008 Cornell Master Plan

    E-Print Network [OSTI]

    Chen, Tsuhan

    Plan 79 Primary Open Space Network Plan 83 Movement Plan 149 Development Opportunity Sites and Areas master plan 176 5 ImplementationLand Use 4.11 Concentrate academic buildings in Core Campus 59 4.12 Create a second academic hub in the core 62 4.13 Protect outdoor teaching and research facilities 64 4

  7. Rulison Monitoring Plan

    SciTech Connect (OSTI)

    None

    2010-07-01T23:59:59.000Z

    The Project Rulison Monitoring Plan has been developed as part of the U.S. Department of Energy (DOE) Office of Legacy Management's mission to protect human health and the environment. The purpose of the plan is to monitor fluids from gas wells for radionuclides that would indicate contamination is migrating from the Rulison detonation zone to producing gas wells, allowing action to be taken before the contamination could pose a risk. The Monitoring Plan (1) lists the contaminants present and identifies those that have the greatest potential to migrate from the detonation zone (radionuclide source term), (2) identifies locations that monitor the most likely transport pathways, (3) identifies which fluids will be sampled (gas and liquid) and why, (4) establishes the frequency of sampling, and (5) specifies the most practical analyses and where the analysis results will be reported. The plan does not affect the long-term hydrologic sampling conducted by DOE since 1972, which will continue for the purpose of sampling shallow groundwater and surface water near the site. The Monitoring Plan was developed in anticipation of gas wells being drilled progressively nearer the Rulison site. DOE sampled 10 gas wells in 1997 and 2005 at distances ranging from 2.7 to 7.6 miles from the site to establish background concentrations for radionuclides. In a separate effort, gas industry operators and the Colorado Oil and Gas Conservation Commission (COGCC) developed an industry sampling and analysis plan that was implemented in 2007. The industry plan requires the sampling of gas wells within 3 miles of the site, with increased requirements for wells within 1 mile of the site. The DOE plan emphasizes the sampling of wells near the site (Figure 1), specifically those with a bottom-hole location of 1 mile or less from the detonation, depending on the direction relative to the natural fracture trend of the producing formation. Studies indicate that even the most mobile radionuclides created by the test are unlikely to migrate appreciable distances (hundreds of feet) from the detonation zone (Cooper et al. 2007, 2009). The Monitoring Plan was developed to provide a cautious and comprehensive approach for detecting any potential contaminant migration from the Rulison test site. It also provides an independent confirmation of results from the industry sampling and analysis plan while effectively increasing the sampling frequency of wells near the site.

  8. Bipolar pulse forming line

    DOE Patents [OSTI]

    Rhodes, Mark A. (Pleasanton, CA)

    2008-10-21T23:59:59.000Z

    A bipolar pulse forming transmission line module for linear induction accelerators having first, second, third, fourth, and fifth planar conductors which form an interleaved stack with dielectric layers between the conductors. Each conductor has a first end, and a second end adjacent an acceleration axis. The first and second planar conductors are connected to each other at the second ends, the fourth and fifth planar conductors are connected to each other at the second ends, and the first and fifth planar conductors are connected to each other at the first ends via a shorting plate adjacent the first ends. The third planar conductor is electrically connectable to a high voltage source, and an internal switch functions to short a high voltage from the first end of the third planar conductor to the first end of the fourth planar conductor to produce a bipolar pulse at the acceleration axis with a zero net time integral. Improved access to the switch is enabled by an aperture through the shorting plate and the proximity of the aperture to the switch.

  9. EC Transmission Line Materials

    SciTech Connect (OSTI)

    Bigelow, Tim S [ORNL

    2012-05-01T23:59:59.000Z

    The purpose of this document is to identify materials acceptable for use in the US ITER Project Office (USIPO)-supplied components for the ITER Electron cyclotron Heating and Current Drive (ECH&CD) transmission lines (TL), PBS-52. The source of material property information for design analysis shall be either the applicable structural code or the ITER Material Properties Handbook. In the case of conflict, the ITER Material Properties Handbook shall take precedence. Materials selection, and use, shall follow the guidelines established in the Materials Assessment Report (MAR). Materials exposed to vacuum shall conform to the ITER Vacuum Handbook. [Ref. 2] Commercial materials shall conform to the applicable standard (e.g., ASTM, JIS, DIN) for the definition of their grade, physical, chemical and electrical properties and related testing. All materials for which a suitable certification from the supplier is not available shall be tested to determine the relevant properties, as part of the procurement. A complete traceability of all the materials including welding materials shall be provided. Halogenated materials (example: insulating materials) shall be forbidden in areas served by the detritiation systems. Exceptions must be approved by the Tritium System and Safety Section Responsible Officers.

  10. Treatment of biodiversity issues in impact assessment of electricity power transmission lines: A Finnish case review

    SciTech Connect (OSTI)

    Soederman, Tarja [Senior Researcher, Lic. Phil., Finnish Environment Institute, Nature Division, P.O. Box 140, FIN-00251 Helsinki (Finland)]. E-mail: tarja.soderman@ymparisto.fi

    2006-05-15T23:59:59.000Z

    The Environmental Impact Assessment (EIA) process concerning the route of a 400 kV power transmission line between Loviisa and Hikiae in southern Finland was reviewed in order to assess how biodiversity issues are treated and to provide suggestions on how to improve the effectiveness of treatment of biodiversity issues in impact assessment of linear development projects. The review covered the whole assessment process, including interviews of stakeholders, participation in the interest group meetings and review of all documents from the project. The baseline studies and assessment of direct impacts in the case study were detailed but the documentation, both the assessment programme and the assessment report, only gave a partial picture of the assessment process. All existing information, baseline survey and assessment methods should be addressed in the scoping phase in order to promote interaction between all stakeholders. In contrast to the assessment of the direct effects, which first emphasized impacts on the nationally important and protected flying squirrel but later expanded to deal with the assessment of impacts on ecologically important sites, the indirect and cumulative impacts of the power line were poorly addressed. The public was given the opportunity to become involved in the EIA process. However, they were more concerned with impacts on their properties and less so on biodiversity and species protection issues. This suggests that the public needs to become more informed about locally important features of biodiversity.

  11. Forestry Commission England Corporate Plan

    E-Print Network [OSTI]

    Forestry Commission England Corporate Plan 2011-15 This is the Corporate Plan for the Forestry Commission in England. It is one of a suite of plans including those for Forestry Commission (GB) and Forest Research. Page 1Forestry Commission England Corporate Plan 2011-15 #12;Page 2Forestry Commission England

  12. TWRS retrieval and disposal mission, immobilized high-level waste storage plan

    SciTech Connect (OSTI)

    Calmus, R.B.

    1998-01-07T23:59:59.000Z

    This project plan has a two fold purpose. First, it provides a plan specific to the Hanford Tank Waste Remediation System (TWRS) Immobilized High-Level Waste (EMW) Storage Subproject for the Washington State Department of Ecology (Ecology) that meets the requirements of Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) milestone M-90-01 (Ecology et al. 1996) and is consistent with the project plan content guidelines found in Section 11.5 of the Tri-Party Agreement action plan. Second, it provides an upper tier document that can be used as the basis for future subproject line item construction management plans. The planning elements for the construction management plans are derived from applicable U.S. Department of Energy (DOE) planning guidance documents (DOE Orders 4700.1 (DOE 1992a) and 430.1 (DOE 1995)). The format and content of this project plan are designed to accommodate the plan`s dual purpose. A cross-check matrix is provided in Appendix A to explain where in the plan project planning elements required by Section 11.5 of the Tri-Party Agreement are addressed.

  13. EIS-0365: EPA Notice of Availability of the Draft Environmental...

    Broader source: Energy.gov (indexed) [DOE]

    of the Draft Environmental Impact Statement Imperial-Mexicali 230-kV Transmission Lines Imperial-Mexicali 230-kV Transmission Lines, Construct a Double-Circuit 230-kV...

  14. User Interfaces 1 Command Line Interfaces

    E-Print Network [OSTI]

    Verschelde, Jan

    User Interfaces 1 Command Line Interfaces getting arguments of the command line a command line 2013 1 / 39 #12;User Interfaces 1 Command Line Interfaces getting arguments of the command line a command line interface to store points fitting points with polyfit of numpy 2 Encapsulation by Object

  15. Environmental Implementation Plan

    SciTech Connect (OSTI)

    Not Available

    1994-02-01T23:59:59.000Z

    The Environmental Implementation Plan (EIP) is a dynamic long-range environmental-protection plan for SRS. The EIP communicates the current and future (five year) environmental plans from individual organizations and divisions as well as site environmental initiatives which are designed to protect the environment and meet or exceed compliance with changing environmental/ regulatory requirements. Communication with all site organizations is essential for making the site environmental planning process work. Demonstrating environmental excellence is a high priority embodied in DOE and WSRC policy. Because of your support and participation in the three EIP initiatives; Reflections, Sectional Revision, and Integrated Planning, improvements are being made to the EIP and SRS environmental protection programs. I appreciate the ``Partnership in Environmental Excellence`` formed by the environmental coordinators and professionals who work daily toward our goal of compliance and environmental excellence. I look forward to seeing continued success and improvement in our environmental protection programs through combined efforts of all site organizations to protect our employees, the public health, and the environment. Together, we will achieve our site vision for SRS to be the recognized model for Environmental Excellence in the DOE Nuclear Weapons Complex.

  16. Integrated Planning: Consolidating Annual Facility Planning - More Time for Execution

    SciTech Connect (OSTI)

    Nelson, J. G.; R., L. Morton; Ramirez, C.; Morris, P. S.; McSwain, J. T.

    2011-02-02T23:59:59.000Z

    Previously, annual planning for Readiness in Technical Base and Facilities (RTBF) at the Nevada National Security Site (NNSS) was fragmented, disconnected, circular, and occurred constantly throughout the fiscal year (FY) comprising 9 of the 12 months, reducing the focus on implementation and execution. This required constant “looking back” instead of “looking forward.” In FY 2009, annual planning was consolidated into one comprehensive integrated plan (IP) for each facility/project, which comprised annual task planning/outyear budgeting, AMPs, and investment planning (i.e., TYIP). In FY 2010, the Risk Management Plans were added to the IPs. The integrated planning process achieved the following: 1) Eliminated fragmented, circular, planning and moved the plan to be more forward-looking; 2) Achieved a 90% reduction in schedule planning timeframe from 40 weeks (9 months) to 6 weeks; 3) Achieved an 80% reduction in cost from just under $1.0M to just over $200K, for a cost savings of nearly $800K (reduced combined effort from over 200 person-weeks to less than 40); 4) Reduced the number of plans generated from 21 plans (1 per facility per plan) per year to 8 plans per year (1 per facility plus 1 program-level IP); 5) Eliminated redundancy in common content between plans and improved consistency and overall quality; 6) Reduced the preparation time and cost of the FY 2010 SEP by 50% due to information provided in the IP; 7) Met the requirements for annual task planning, annual maintenance planning, ten-year investment planning, and risk management plans.

  17. Optimal Model-Based Production Planning

    E-Print Network [OSTI]

    Grossmann, Ignacio E.

    1 Optimal Model-Based Production Planning for Refinery Operation Abdulrahman Alattas Advisor;2 Outline Introduction Problem Statement Refinery Planning Model Development LP Planning Models NLP Planning Models Conclusion #12;3 Introduction Refinery production planning models Optimizing refinery

  18. Energy Organizational Planning

    SciTech Connect (OSTI)

    Gina C. Paradis; James Yockey; Tracey LeBeau

    2009-04-17T23:59:59.000Z

    As the Seneca Nation of Indians (SNI) continues to refine and finalize its Strategic Energy Plan, it became necessary to insure that a sustainable organization structure was developed through which the energy program and its initiatives could be nurtured and managed. To that end, SNI undertook a study to thoroughly evaluate the existing organizational structures and assess the requisite changes and/or additions to that framework that would complement the mission of the Strategic Plan. The goal of this study was to analyze, work with staff and leadership and recommend the most effective plan for the development of an organizational framework within which the Seneca could more effectively exercise energy sovereignty – control and manage their natural resource assets – i.e. develop its own energy resources, meet the current and projected energy needs of their community, and “sit at the table” with other regional energy providers to deal with issues on a peer-to-peer basis.

  19. EIS-0339: Presidential Permit Application, GenPower 500 kV Submarine Electric Transmission Cable from Nova Scotia to New York

    Broader source: Energy.gov [DOE]

    The Department of Energy (DOE) announced its intent to prepare an Environmental Impact Statement (EIS) in accordance with the National Environmental Policy Act of 1969 (NEPA) for GenPower New York, L.L.C.’s (GenPower) request for a Presidential permit for a proposed international electric transmission line.

  20. Guam Strategic Energy Plan

    SciTech Connect (OSTI)

    Conrad, M. D.

    2013-07-01T23:59:59.000Z

    Describes various energy strategies available to Guam to meet the territory's goal of diversifying fuel sources and reducing fossil energy consumption 20% by 2020.The information presented in this strategic energy plan will be used by the Guam Energy Task Force to develop an energy action plan. Available energy strategies include policy changes, education and outreach, reducing energy consumption at federal facilities, and expanding the use of a range of energy technologies, including buildings energy efficiency and conservation, renewable electricity production, and alternative transportation. The strategies are categorized based on the time required to implement them.

  1. Performance expectation plan

    SciTech Connect (OSTI)

    Ray, P.E.

    1998-09-04T23:59:59.000Z

    This document outlines the significant accomplishments of fiscal year 1998 for the Tank Waste Remediation System (TWRS) Project Hanford Management Contract (PHMC) team. Opportunities for improvement to better meet some performance expectations have been identified. The PHMC has performed at an excellent level in administration of leadership, planning, and technical direction. The contractor has met and made notable improvement of attaining customer satisfaction in mission execution. This document includes the team`s recommendation that the PHMC TWRS Performance Expectation Plan evaluation rating for fiscal year 1998 be an Excellent.

  2. Strategic Planning for Landowners

    E-Print Network [OSTI]

    Johnson, Jason; Polk, Wade

    2008-09-16T23:59:59.000Z

    Strategic Planning for Landowners Risk Management E-146 RM3-12.0 09-08 *Assistant Professor and Extension Economist?Management, and Extension Specialist?Risk Management, The Texas A&M System Strategic planning is a process that provides direction... the bottom up. Managers are also responsible for Jason L. Johnson and Wade Polk* 2 carrying out those required daily tasks. Land- owners are often both manager and employee, which demands a combination of vision and technical aptitude. Steps for Setting...

  3. Environmental protection implementation plan

    SciTech Connect (OSTI)

    Holland, R.C.

    1998-03-01T23:59:59.000Z

    This Environmental Protection Implementation Plan is intended to ensure that the environmental program objectives of Department of Energy Order 5400.1 are achieved at SNL/California. This document states SNL/California`s commitment to conduct its operations in an environmentally safe and responsible manner. The Environmental Protection Implementation Plan helps management and staff comply with applicable environmental responsibilities. SNL is committed to operating in full compliance with the letter and spirit of applicable environmental laws, regulations, and standards. Furthermore, SNL/California strives to go beyond compliance with legal requirements by making every effort practical to reduce impacts to the environment to levels as low as reasonably achievable.

  4. Enhanced radiological work planning

    SciTech Connect (OSTI)

    DECKER, W.A.

    1999-05-21T23:59:59.000Z

    The purpose of this standard is to provide Project Hanford Management Contractors (PHMC) with guidance for ensuring radiological considerations are adequately addressed throughout the work planning process. Incorporating radiological controls in the planning process is a requirement of the Hanford Site Radiological Control Manual (HSRCM-I), Chapter 3, Part 1. This standard is applicable to all PHMC contractors and subcontractors. The essential elements of this standard will be incorporated into the appropriate site level work control standard upon implementation of the anticipated revision of the PHMC Administration and Procedure System.

  5. Plutonium Vulnerability Management Plan

    SciTech Connect (OSTI)

    NONE

    1995-03-01T23:59:59.000Z

    This Plutonium Vulnerability Management Plan describes the Department of Energy`s response to the vulnerabilities identified in the Plutonium Working Group Report which are a result of the cessation of nuclear weapons production. The responses contained in this document are only part of an overall, coordinated approach designed to enable the Department to accelerate conversion of all nuclear materials, including plutonium, to forms suitable for safe, interim storage. The overall actions being taken are discussed in detail in the Department`s Implementation Plan in response to the Defense Nuclear Facilities Safety Board (DNFSB) Recommendation 94-1. This is included as Attachment B.

  6. Electric Reliability & Hurricane Preparedness Plan

    E-Print Network [OSTI]

    · Clean coal technology · On line ­ May 2014 · Generation mix: Natural gas, coal and lignite · Base load

  7. PNNL Campus Master Plan

    SciTech Connect (OSTI)

    Mosey, Whitney LC

    2012-09-07T23:59:59.000Z

    The Plan is used as a guide for PNNL in making facility and infrastructure decisions essential to supporting the PNNL vision: to establish a modern, collaborative, flexible, and sustainable campus while optimizing the efficiency of operations in support of courageous discovery and innovation.

  8. Business Services Strategic Plan

    E-Print Network [OSTI]

    Holland, Jeffrey

    Business Services Strategic Plan Updated September 2008 New Synergies: Launching Tomorrow's Leaders Discovery with Delivery Meeting Global Challenges Excellence in Business and Support Services #12;Introduction The mission of Business Services at Purdue University is to enable, serve, and support others

  9. Environmental Education Strategic Plan

    SciTech Connect (OSTI)

    none,

    1991-12-01T23:59:59.000Z

    This document is designed to guide the Environmental Education and Development Branch (EM-522) of the EM Office of Technology (OTD) Development, Technology Integration and Environmental Education Division (EM-52) in planning and executing its program through EM staff, Operations Offices, National Laboratories, contractors, and others.

  10. Aerocapacitor commercialization plan

    SciTech Connect (OSTI)

    NONE

    1995-09-12T23:59:59.000Z

    The purpose of the Power-One Aerocapacitor Commercialization Plan is to communicate to members of management and to all employees the overall objectives of the corporation. Power-One, Inc., has participated in a US Federal Government Technology Reinvestment Project (TRP), entitled {open_quotes}Advanced Power Conversion based on the Aerocapacitor{close_quotes}: the project is a group effort, with Lawrence Livermore National Labs, GenCorp/Aerojet, PolyStor Corp. (a start-up company), and Power-One forming the consortium. The expected resulting technology is the {open_quotes}Aerocapacitor{close_quotes}, which possesses much higher performance levels than the usual capacitors on the market today. Power-One hopes to incorporate the Aerocapacitor into some of its products, hence enhancing their performance, as well as market privately-labeled aerocapacitors through its distribution channels. This document describes the details of Power-One`s plan to bring to market and commercialize the Aerocapacitor and Aerocapacitor-based products. This plan was formulated while Power-One was part of the Oerocap project. It has since pulled out of this project. What is presented in this plan is the work which was developed prior to the business decision to terminate this work.

  11. PENSION PLAN INFORMATION SESSION

    E-Print Network [OSTI]

    Kambhampati, Patanjali

    %)* QPP (20%) Personal Savings RRSP, TFSA Company Pension Plan (49%)** Government Benefits Personal.lastname@mcgill.ca). If you forget your McGill Username or McGill Password, try logging into Minerva with your 9-digit McGill ID number and PIN. Once you have logged in successfully, go to the Personal Menu > Password for Mc

  12. Gonzales Comprehensive Plan

    E-Print Network [OSTI]

    Bright, Elise; Cutaia, Louis; Barrios, Nair; Brinkman, Travis; Caraballo, Stephany; Chen, Long; Coleman, Alex; Crosby, Kevin; Dai, Boya; Espinoza, Carlos; Han, Dondjin; Hansen, Todd; Hyde, Allison; Lazaro, Cristopher; Lin, Rosie; Lopez, Michael; Martin, Michael; Masterson, Jaimie Hicks; Medina, Izel; Peackock, Walter M; Sengupta, Koly; Shelnutt, Andrew; Su, Jin; Tan, Shuman; Tang, Taoi; Tran, Tho

    2013-01-01T23:59:59.000Z

    Program’s (NFIP) Community Rat- ing System (CRS) which reduces the premiums for policy holders within the municipality. In terms of improving the human environment, the plan addresses the impacts of the oil and gas industry as well as improving trails...…………………..………………………………………………...…………………...….242 Environment…………………….……………………………………………………………………….……..….245 Future Environment………………...……………………………………………..…………...…..283 Policy Table……………………..……………………………………………………...…...………….288 Appendix………………….…………………………………………………………...…………………292 Urban Design...

  13. LCLS Undulator Test Plan

    SciTech Connect (OSTI)

    Wolf, Zachary

    2010-11-24T23:59:59.000Z

    This note presents the test plan for the LCLS undulators. The undulators will be measured and tuned in the Magnetic Measurement Facility at SLAC. The requirements for tuning are well established and are summarized. A brief discussion of the measurement equipment is presented. This is followed by the detailed test plan in which each step is enumerated. Finally, the measurement results and storage format are presented. The LCLS consists of 33 undulator segments, hereafter referred to as undulators, plus 6 spares and one reference undulator. The undulators must be tuned to meet strict requirements. They must also be fiducialized to allow alignment with other components. This note details the plan for tuning and fiducializing the LCLS undulators. The note begins with the list of tuning and fiducialization requirements. The laboratory in which the work will be performed and the relevant equipment is then briefly described. This is followed by a detailed test plan in which all the steps of tuning and fiducialization are enumerated.

  14. Motion Planning ! Jana Kosecka!

    E-Print Network [OSTI]

    Kosecka, Jana

    ­ transform continuous space to discrete! · Roadmap methods! ­ Visibility graph! ­ Cell decomposition;6! Roadmap Methods! roadmap! Capture the connectivity of Cfree with a roadmap (graph or network) of one-dimensional curves! difficult! part! Roadmap Methods! Path Planning with a Roadmap! Input: configurations qinit

  15. Student Health Benefit Plan

    E-Print Network [OSTI]

    Massachusetts at Amherst, University of

    and programs tailored to the needs of students. The SHBP coordinates care with University Health Services (UHS), UMass Amherst's fully accredited health center. UHS provides comprehensive primary care, walk-in care2 2013-2014 Student Health Benefit Plan (SHBP) Designed for the Students of Policy Period: August 1

  16. Search Criteria Health Plan

    E-Print Network [OSTI]

    Gleeson, Joseph G.

    Search Criteria Location: Distance: Health Plan: Provider Type: San Diego, CA 92103 Within 10 miles another provider, you are seeking care from that provider, not from Anthem Blue Cross. The provider benefit decisions only and are not the provision of medical care. Anthem Blue Cross is not responsible for

  17. Plans, Implementation, and Results

    Broader source: Energy.gov [DOE]

    The Bioenergy Technologies Office carries out technology research, development, and deployment through an ongoing process of planning and analysis, implementation, and review. This Web page includes links to documents that support and document the program management process, and the results and public benefits that derive from it.

  18. Impacted material placement plans

    SciTech Connect (OSTI)

    Hickey, M.J.

    1997-01-29T23:59:59.000Z

    Impacted material placement plans (IMPP) are documents identifying the essential elements in placing remediation wastes into disposal facilities. Remediation wastes or impacted material(s) are those components used in the construction of the disposal facility exclusive of the liners and caps. The components might include soils, concrete, rubble, debris, and other regulatory approved materials. The IMPP provides the details necessary for interested parties to understand the management and construction practices at the disposal facility. The IMPP should identify the regulatory requirements from applicable DOE Orders, the ROD(s) (where a part of a CERCLA remedy), closure plans, or any other relevant agreements or regulations. Also, how the impacted material will be tracked should be described. Finally, detailed descriptions of what will be placed and how it will be placed should be included. The placement of impacted material into approved on-site disposal facilities (OSDF) is an integral part of gaining regulatory approval. To obtain this approval, a detailed plan (Impacted Material Placement Plan [IMPP]) was developed for the Fernald OSDF. The IMPP provides detailed information for the DOE, site generators, the stakeholders, regulatory community, and the construction subcontractor placing various types of impacted material within the disposal facility.

  19. Introduction to Transportation Planning

    E-Print Network [OSTI]

    Tipple, Brett

    Introduction to Transportation Planning CMP 4710/6710 Fall 2012 3 Credit Hours Room: ARCH 229 on a Saturday night, transportation is not an objective in and of itself, but a means to carry out the functions of daily living (i.e., it's a "derived good"). As a consequence, the transportation systems we build

  20. Climate Change Scoping Plan

    E-Print Network [OSTI]

    Climate Change Scoping Plan a amework for change Prepared by the California Air Resources BoardBackgroundBackgroundBackground ............................................................................................................................................................................................................................................................................................................................................................................................................ 4444 1. Climate Change Policy in California1. Climate Change Policy in California1. Climate Change Policy in California1. Climate Change Policy in California

  1. Climate Change Scoping Plan

    E-Print Network [OSTI]

    Climate Change Scoping Plan a amework for change as approved Prepared by the California AirBackgroundBackgroundBackground ............................................................................................................................................................................................................................................................................................................................................................................................................ 4444 1. Climate Change Policy in California1. Climate Change Policy in California1. Climate Change Policy in California1. Climate Change Policy in California

  2. Gonzales Comprehensive Plan 

    E-Print Network [OSTI]

    Bright, Elise; Cutaia, Louis; Barrios, Nair; Brinkman, Travis; Caraballo, Stephany; Chen, Long; Coleman, Alex; Crosby, Kevin; Dai, Boya; Espinoza, Carlos; Han, Dondjin; Hansen, Todd; Hyde, Allison; Lazaro, Cristopher; Lin, Rosie; Lopez, Michael; Martin, Michael; Masterson, Jaimie Hicks; Medina, Izel; Peackock, Walter M; Sengupta, Koly; Shelnutt, Andrew; Su, Jin; Tan, Shuman; Tang, Taoi; Tran, Tho

    2013-01-01T23:59:59.000Z

    Program’s (NFIP) Community Rat- ing System (CRS) which reduces the premiums for policy holders within the municipality. In terms of improving the human environment, the plan addresses the impacts of the oil and gas industry as well as improving trails...…………………..………………………………………………...…………………...….242 Environment…………………….……………………………………………………………………….……..….245 Future Environment………………...……………………………………………..…………...…..283 Policy Table……………………..……………………………………………………...…...………….288 Appendix………………….…………………………………………………………...…………………292 Urban Design...

  3. Action Plan Materials Science

    E-Print Network [OSTI]

    Fitze, Patrick

    sense, including all strata) has available to it a wide range of con- venient products which improve, improving companies' pros- pects and generating wealth without harming the environment. And allAction Plan 2010-2013 Materials Science Area EXECUTIVE SUMMARY #12;N.B.: If you require any further

  4. Pulse shaping with transmission lines

    DOE Patents [OSTI]

    Wilcox, Russell B. (Oakland, CA)

    1987-01-01T23:59:59.000Z

    A method and apparatus for forming shaped voltage pulses uses passive reflection from a transmission line with nonuniform impedance. The impedance of the reflecting line varies with length in accordance with the desired pulse shape. A high voltage input pulse is transmitted to the reflecting line. A reflected pulse is produced having the desired shape and is transmitted by pulse removal means to a load. Light activated photoconductive switches made of silicon can be utilized. The pulse shaper can be used to drive a Pockels cell to produce shaped optical pulses.

  5. Pulse shaping with transmission lines

    DOE Patents [OSTI]

    Wilcox, R.B.

    1985-08-15T23:59:59.000Z

    A method and apparatus for forming shaped voltage pulses uses passive reflection from a transmission line with nonuniform impedance. The impedance of the reflecting line varies with length in accordance with the desired pulse shape. A high voltage input pulse is transmitted to the reflecting line. A reflected pulse is produced having the desired shape and is transmitted by pulse removal means to a load. Light activated photoconductive switches made of silicon can be utilized. The pulse shaper can be used to drive a Pockels cell to produce shaped optical pulses.

  6. Electrical transmission line diametrical retainer

    DOE Patents [OSTI]

    Hall, David R. (Provo, UT); Hall, Jr., H. Tracy (Provo, UT); Pixton, David (Lehi, UT); Dahlgren, Scott (Provo, UT); Sneddon, Cameron (Provo, UT); Briscoe, Michael (Lehi, UT); Fox, Joe (Spanish Fork, UT)

    2004-12-14T23:59:59.000Z

    The invention is a mechanism for retaining an electrical transmission line. In one embodiment of the invention it is a system for retaining an electrical transmission line within down hole components. In accordance with one aspect of the invention, the system includes a plurality of downhole components, such as sections of pipe in a drill string. The system also includes a coaxial cable running between the first and second end of a drill pipe, the coaxial cable having a conductive tube and a conductive core within it. The invention allows the electrical transmission line to with stand the tension and compression of drill pipe during routine drilling cycles.

  7. Planning support systems for spatial planning through social learning

    E-Print Network [OSTI]

    Goodspeed, Robert (Robert Charles)

    2013-01-01T23:59:59.000Z

    This dissertation examines new professional practices in urban planning that utilize new types of spatial planning support systems (PSS) based on geographic information systems (GIS) software. Through a mixed-methods ...

  8. Plan generation strategies for a knowledge based process planning system

    E-Print Network [OSTI]

    Hari, Umesh

    1993-01-01T23:59:59.000Z

    August 1993 Major Subject: Industrial Engineering PLAN GENERATION STRATEGIES FOR A KNOWLEDGE BASED PROCESS PLANNING SYSTEM A Thesis by UMESH HARI Approved as to style and content by: Ri ar . Maye (Chair of Committee) / i en ember) Newton C... valuable comments on the thesis work. I am indebted to Dr. C. J. Su for arousing my interest in process planning. I have learned a lot about process planning and solid modeling from him. I also thank him for directing me to relevant literature...

  9. Transmission Lines Emulating Moving Media

    E-Print Network [OSTI]

    Vehmas, Joni; Tretyakov, Sergei

    2014-01-01T23:59:59.000Z

    In this paper, we show how the electromagnetic phenomena in moving magnetodielectric media can be emulated using artificial composite structures at rest. In particular, we introduce nonreciprocal periodically loaded transmission lines which support waves obeying the same rules as plane electromagnetic waves in moving media. Because the actual physical structure is at rest, in these transmission lines there are no fundamental limitations on the velocity values, which may take values larger than the speed of light or even complex values (considering complex amplitudes in the time-harmonic regime). An example circuit of a unit cell of a "moving" transmission line is presented and analyzed both numerically and experimentally. The special case of composite right/left handed host line is also studied numerically. Besides the fundamental interest, the study is relevant for potential applications in realizing engineered materials for various transformations of electromagnetic fields.

  10. The beauty of laser lines

    E-Print Network [OSTI]

    Kim, Sue-Mie

    1993-01-01T23:59:59.000Z

    A line, the simplest way to express an artist's feelings or interpretation of an object, has its own emotions that an artist can employ for her purpose. Laser light, the most self-concentrated, self-sustained and directed, ...

  11. Authorization of Line Extension (Nebraska)

    Broader source: Energy.gov [DOE]

    Any entity permitted to establish an electric light and power plant, and/or transmission or distribution lines within a city, village, or public electric light and power district, may also extend...

  12. VISAR: Line-imaging interferometer

    SciTech Connect (OSTI)

    Hemsing, W.F.; Mathews, A.R.; Warnes, R.H.; George, M.J.; Whittemore, G.R.

    1991-01-01T23:59:59.000Z

    A line-imaging Velocity Interferometer System for Any Reflector (VISAR) was applied to measure velocity across the diameter of a metal plate explosively accelerated to 5.5 km/s. Amplified, single- frequency laser light was focused to illuminate a line on the metal surface. The line's image was focused through the interferometer to a streak camera that swept in time and recorded directly on film. During the experiment, the Doppler-shift caused motion of the interference fringes. Analysis of the digitized film record yielded a continuum of time-resolved velocity histories. Velocity gradients across the plate that first swept radially inward, then reflected outward, were clearly measured. Increased power provided by the laser amplifier greatly improved the signal-to-noise ratio compared to our previous line VISAR experiments. 5 refs., 8 figs.

  13. Site Maintenance Plan: Part 2, Site Maintenance Action Plan for FY 1994

    SciTech Connect (OSTI)

    Fisk, E.L.

    1994-06-01T23:59:59.000Z

    This Fiscal Year (FY) 1994 Site Maintenance Action Plan (SMAP) is Part II of the Site Maintenance Plan, and has been written by Westinghouse Hanford Company (WHC) to outline the requirements stated in DOE Order 4330.4B, Maintenance Management Program, Chapter 1, Paragraph 3.3.1. The SMAP provides an annual status of maintenance initiatives completed and planned, a summary of performance indicators, a summary of maintenance backlog, a listing of real property and capital equipment maintenance cost estimates that were used to create the FY 1996 infrastructure and maintenance budget input, and a listing of proposed line item and general plant projects. Additionally, assumptions for various Site programs are listed to bring the Site Maintenance Plan into focus with overall Site activities. The primary mission at Hanford is to clean up the Site. In this cleanup process WHC will provide scientific and technological expertise to meet global needs, and partnership with stakeholders in the region to develop regional economic diversification. Other missions at the Hanford Site include energy research and development, and waste management and disposal activities. Their primary mission has a 30-year projected life span and will direct the shutting down and cleanup of defense production facilities and the Fast Flux Test Facility. This long-term mission requires continuous maintenance and in many instances, replacement of existing basic infrastructure, support facilities, and utilities. Without adequate maintenance and capital funding these infrastructure, support facilities, and utilities will continue to deteriorate causing an increase in backlogged work.

  14. Analysis of interconnect microstrip lines

    E-Print Network [OSTI]

    Luong, Giam-Minh

    1992-01-01T23:59:59.000Z

    of the return loss of the slot-coupled microstrip dipole. Section C presents two simulations of the return loss on the slot- coupled rectangular patch antenna. A. Interconnect of Microstrip Lines Several circuits with the geometry of Figure 1 were fabricated.... Experimental and Theoretical Results of the Interconnect Two circuits were designed and fabricated. Each circuit consists of two substrates as shown in Figure 9. One substrate has an open microstrip line etched in one side and an aperture etched...

  15. Fin-line horn antenna

    DOE Patents [OSTI]

    Reindel, John (San Diego, CA)

    1990-01-01T23:59:59.000Z

    A fin line circuit card containing a fin line slot feeds a dipole antenna ich extends a quarterwave outside the waveguide and provides an energy beam focal point at or near the open end of the waveguide. The dipole antenna thus maintains a wide and nearly constant beamwidth, low VSWR and a circular symmetric radiation pattern for use in electronic warfare direction finding and surveillance applications.

  16. Massachusetts Ocean Management Plan (Massachusetts)

    Broader source: Energy.gov [DOE]

    The Massachusetts Ocean Act of 2008 required the state’s Secretary of Energy and Environmental Affairs to develop a comprehensive ocean management plan for the state by the end of 2009. That plan...

  17. Climate Action Plan (Ontario, Canada)

    Broader source: Energy.gov [DOE]

    Climate Ready, Ontario's Adaptation Strategy and Action Plan, outlines the problems, goals, and key strategies for the province's approach to climate change and the problems it poses. The Plan...

  18. Accessibility-based transit planning

    E-Print Network [OSTI]

    Busby, Jeffrey R

    2004-01-01T23:59:59.000Z

    A method for evaluating transit planning proposals using accessibility metrics is advanced in this research. A transit-accessibility model is developed intended for use by in-house transit agency planning staff as a ...

  19. LOCAL GOVERNMENT EMERGENCY PLANNING HANDBOOK

    E-Print Network [OSTI]

    management system and communications plan consistent with existing state and federal energy emergencyCALIFORNIA ENERGY COMMISSION LOCAL GOVERNMENT EMERGENCY PLANNING HANDBOOK April 2004 PUBLICATION and authorities, and to integrate their management and communications systems with both the California Energy

  20. Climate Action Plan (Manitoba, Canada)

    Broader source: Energy.gov [DOE]

    Manitoba's Climate Action Plan centers around energy efficiency, although it includes mandates and initiatives for renewable sources of energy.

  1. Planning for Years to Come

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Enlarge Create a Sustainable Future: Planning LANL's Governing Policy on the Environment Environmental Sustainability Goals Environmental Management System Regulatory...

  2. Strategic Energy Planning | Department of Energy

    Office of Environmental Management (EM)

    Resources Energy Resource Library Strategic Energy Planning Strategic Energy Planning Below are resources for Tribes on strategic energy planning. Alaska Strategic Energy...

  3. Space Conditioning Standing Technical Committee Strategic Plan...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Committee Strategic Plan Space Conditioning Standing Technical Committee Strategic Plan This strategic plan document outlines the gaps, barriers, and opportunities identified by...

  4. Best Management Practice #1: Water Management Planning

    Broader source: Energy.gov [DOE]

    A successful water management program starts with developing a comprehensive water management plan. This plan should be included within existing facility operating plans.

  5. Planning, Budget, and Analysis | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Planning, Budget, and Analysis Planning, Budget, and Analysis Presentation on Planning, Budget, and Analysis to the DOE Systems Analysis Workshop held in Washington, D.C. July...

  6. Guam Energy Action Plan

    SciTech Connect (OSTI)

    Conrad, M. D.; Ness, J. E.

    2013-07-01T23:59:59.000Z

    Describes the four near-term strategies selected by the Guam Energy Task Force during action planning workshops conducted in March 2013, and outlines the steps being taken to implement those strategies. Each strategy addresses one of the energy sectors identified in the earlier Guam strategic energy plan as being an essential component of diversifying Guam's fuel sources and reducing fossil energy consumption 20% by 2020. The four energy strategies selected are: (1) expanding public outreach on energy efficiency and conservation, (2) establishing a demand-side management revolving loan program, (3) exploring waste-to-energy options, and (4) influencing the transportation sector via anti-idling legislation, vehicle registration fees, and electric vehicles.

  7. SAVEnergy Action Plans

    SciTech Connect (OSTI)

    Mayo, K.; Westby, R. [National Renewable Energy Lab., Golden, CO (United States)] [National Renewable Energy Lab., Golden, CO (United States); deMonsabert, S. [George Mason Univ., Fairfax, VA (United States)] [George Mason Univ., Fairfax, VA (United States); Ginsberg, M. [USDOE, Washington, DC (United States)] [USDOE, Washington, DC (United States)

    1994-04-01T23:59:59.000Z

    The Department of Energy`s Federal Energy Management Program (FEMP) is charged with carrying out key sections of EPACT and Executive Order 12903, to make the Federal government operate more efficiently. A congressionally mandated energy and water conservation audit program is one component of this growing DOE program. This paper traces the SAVEnergy Action Plan program throughout its development from (1) identifying projects and Agency champions, (2) establishing a protocol and fitting auditors into the program, (3) developing a data base to track the audits and measure their success, and (4) evaluating the process, learning from mistakes, and charting and transferring successes. A major tenet of the SAVEnergy program is to proactively prescreen all audit activities to ensure that -- where audits are done and Action Plans completed -- projects will be done.

  8. CIPS Validation Data Plan

    SciTech Connect (OSTI)

    Nam Dinh

    2012-03-01T23:59:59.000Z

    This report documents analysis, findings and recommendations resulted from a task 'CIPS Validation Data Plan (VDP)' formulated as an POR4 activity in the CASL VUQ Focus Area (FA), to develop a Validation Data Plan (VDP) for Crud-Induced Power Shift (CIPS) challenge problem, and provide guidance for the CIPS VDP implementation. The main reason and motivation for this task to be carried at this time in the VUQ FA is to bring together (i) knowledge of modern view and capability in VUQ, (ii) knowledge of physical processes that govern the CIPS, and (iii) knowledge of codes, models, and data available, used, potentially accessible, and/or being developed in CASL for CIPS prediction, to devise a practical VDP that effectively supports the CASL's mission in CIPS applications.

  9. Verification of Gamma Knife extend system based fractionated treatment planning using EBT2 film

    SciTech Connect (OSTI)

    Natanasabapathi, Gopishankar; Bisht, Raj Kishor [Gamma Knife Unit, Department of Neurosurgery, Neurosciences Centre, All India Institute of Medical Sciences, Ansari Nagar, New Delhi 110029 (India)] [Gamma Knife Unit, Department of Neurosurgery, Neurosciences Centre, All India Institute of Medical Sciences, Ansari Nagar, New Delhi 110029 (India)

    2013-12-15T23:59:59.000Z

    Purpose: This paper presents EBT2 film verification of fractionated treatment planning with the Gamma Knife (GK) extend system, a relocatable frame system for multiple-fraction or serial multiple-session radiosurgery.Methods: A human head shaped phantom simulated the verification process for fractionated Gamma Knife treatment. Phantom preparation for Extend Frame based treatment planning involved creating a dental impression, fitting the phantom to the frame system, and acquiring a stereotactic computed tomography (CT) scan. A CT scan (Siemens, Emotion 6) of the phantom was obtained with following parameters: Tube voltage—110 kV, tube current—280 mA, pixel size—0.5 × 0.5 and 1 mm slice thickness. A treatment plan with two 8 mm collimator shots and three sectors blocking in each shot was made. Dose prescription of 4 Gy at 100% was delivered for the first fraction out of the two fractions planned. Gafchromic EBT2 film (ISP Wayne, NJ) was used as 2D verification dosimeter in this process. Films were cut and placed inside the film insert of the phantom for treatment dose delivery. Meanwhile a set of films from the same batch were exposed from 0 to 12 Gy doses for calibration purposes. An EPSON (Expression 10000 XL) scanner was used for scanning the exposed films in transparency mode. Scanned films were analyzed with inhouse written MATLAB codes.Results: Gamma index analysis of film measurement in comparison with TPS calculated dose resulted in high pass rates >90% for tolerance criteria of 1%/1 mm. The isodose overlay and linear dose profiles of film measured and computed dose distribution on sagittal and coronal plane were in close agreement.Conclusions: Through this study, the authors propose treatment verification QA method for Extend frame based fractionated Gamma Knife radiosurgery using EBT2 film.

  10. STRATEGIC PLAN PROGRESS REPORT 2014

    E-Print Network [OSTI]

    Shahriar, Selim

    STRATEGIC PLAN PROGRESS REPORT 2014 NORTHWESTERN WILL #12;#12;Dear members of the Northwestern by the progress already made and the impact that the plan continues to have on Northwestern. The plan provides Professor of Molecular Biol- ogy and Biochemistry at the Feinberg School of Medicine. · Ground broken

  11. Planning and Search Exam format

    E-Print Network [OSTI]

    Alechina, Natasha

    is the frame problem. Revision 5 #12;Exam topics: planning Classical planning. How the problem definitionPlanning and Search Revision Revision 1 #12;Outline Exam format Exam topics How to revise Revision 2 #12;Exam format 4 questions out of 6 same format as 2010-2011 and 2011-2012 exams (on G52PAS

  12. BUSINESS PLAN SCHOLARSHIP COMPETITION ANNOUNCEMENT

    E-Print Network [OSTI]

    California at Davis, University of

    BUSINESS PLAN SCHOLARSHIP COMPETITION ANNOUNCEMENT Established in late 2001, My Sister's House Sister's House is offering a business plan competition to local college and graduate students to identify. The business plan which should be conducted under the approval of a business or business related professor

  13. McKinney Sustainability Plan 

    E-Print Network [OSTI]

    Smith, J.

    2011-01-01T23:59:59.000Z

    CATEE Conference: Planning for Sustainability McKinney?s Draft Community Sustainability Plan: Shaping Our Sustainable Future Julie Smith Office of Environmental Stewardship November 8, 2011 Sustainability Planning ? Why bother? ? Who has... aspect of sustainability ? Created the Green Advisory Committee (GAC) ? November 2008: Green Sustainability Initiative Report ? Recommended forming a comprehensive, sustainability program to coordinate the sustainability agenda for the city...

  14. Energy Management and Conservation Plan

    E-Print Network [OSTI]

    Energy Management and Conservation Plan December 2005 #12;Texas Transportation Institute December 2005 Energy Management and Conservation Plan Page 2 of 24 Table of Contents Section One: Executive: Reporting Progress #12;Texas Transportation Institute December 2005 Energy Management and Conservation Plan

  15. Lubbock Metropolitan Transportation Plan

    E-Print Network [OSTI]

    Lubbock Metropolitan Planning Organization

    2007-09-18T23:59:59.000Z

    for Users (SAFETEA-LU) and its predecessors, the Transportation Equity Act for the 21st Century (TEA-21) and the Intermodal Surface Transportation Efficiency Act (ISTEA) of 1991, specified the transportation systems on which certain federal funds can... in Chapter 5 ? Streets and Highways; Chapter 6 ? Public Transportation; Chapter 7 ? Bicycle and Pedestrian Plan; Chapter 8 ? Lubbock International Airport and Chapter 9 ? Railroads and Trucking. Federally funded transit projects were developed...

  16. Plans, Updates, Regulatory Documents

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What's Possible for RenewableSpeedingBiomassPPPOPetroleum ReservesThrustBonnevillePlans are nothingand

  17. Mobile systems capability plan

    SciTech Connect (OSTI)

    NONE

    1996-09-01T23:59:59.000Z

    This plan was prepared to initiate contracting for and deployment of these mobile system services. 102,000 cubic meters of retrievable, contact-handled TRU waste are stored at many sites around the country. Also, an estimated 38,000 cubic meters of TRU waste will be generated in the course of waste inventory workoff and continuing DOE operations. All the defense TRU waste is destined for disposal in WIPP near Carlsbad NM. To ship TRU waste there, sites must first certify that the waste meets WIPP waste acceptance criteria. The waste must be characterized, and if not acceptable, subjected to additional processing, including repackaging. Most sites plan to use existing fixed facilities or open new ones between FY1997-2006 to perform these functions; small-quantity sites lack this capability. An alternative to fixed facilities is the use of mobile systems mounted in trailers or skids, and transported to sites. Mobile systems will be used for all characterization and certification at small sites; large sites can also use them. The Carlsbad Area Office plans to pursue a strategy of privatization of mobile system services, since this offers a number of advantages. To indicate the possible magnitude of the costs of deploying mobile systems, preliminary estimates of equipment, maintenance, and operating costs over a 10-year period were prepared and options for purchase, lease, and privatization through fixed-price contracts considered.

  18. Project Management Plan

    SciTech Connect (OSTI)

    Not Available

    1988-01-01T23:59:59.000Z

    The mission of the Uranium Mill Tailings Remedial Action (UMTRA) Project is explicitly stated and directed in the Uranium Mill Tailings Radiation Control Act of 1978, Public Law 95-604, 42 USC 7901 (hereinafter referred to as the Act''). Title I of the Act authorizes the Department of Energy (DOE) to undertake remedial actions at 24 designated inactive uranium processing sites and associated vicinity properties containing uranium mill tailings and other residual radioactive materials derived from the processing sites. The Act, amended in January 1983, by Public Law 97-415, also authorizes DOE to perform remedial actions at vicinity properties in Edgemont, South Dakota. Cleanup of the Edgemont processing site is the responsibility of the Tennessee Valley Authority. This document describes the plan, organization, system, and methodologies used to manage the design, construction, and other activities required to clean up the designated sites and associated vicinity properties in accordance with the Act. The plan describes the objectives of the UMTRA Project, defines participants' roles and responsibilities, outlines the technical approach for accomplishing the objectives, and describes the planning and managerial controls to be used in integrating and performing the Project mission. 21 figs., 21 tabs.

  19. A study of IMRT planning parameters on planning efficiency, delivery efficiency, and plan quality

    SciTech Connect (OSTI)

    Mittauer, Kathryn [Department of Radiation Oncology, College of Medicine, University of Florida, Gainesville, Florida 32603 and J. Crayton Pruitt Family Department of Biomedical Engineering, University of Florida, Gainesville, Florida 32611 (United States); Lu Bo; Yan Guanghua; Kahler, Darren; Amdur, Robert; Liu Chihray [Department of Radiation Oncology, College of Medicine, University of Florida, Gainesville, Florida 32603 (United States); Gopal, Arun [Department of Radiation Oncology, New York-Presbyterian Hospital, Columbia University, New York, New York 10032 (United States)

    2013-06-15T23:59:59.000Z

    Purpose: To improve planning and delivery efficiency of head and neck IMRT without compromising planning quality through the evaluation of inverse planning parameters.Methods: Eleven head and neck patients with pre-existing IMRT treatment plans were selected for this retrospective study. The Pinnacle treatment planning system (TPS) was used to compute new treatment plans for each patient by varying the individual or the combined parameters of dose/fluence grid resolution, minimum MU per segment, and minimum segment area. Forty-five plans per patient were generated with the following variations: 4 dose/fluence grid resolution plans, 12 minimum segment area plans, 9 minimum MU plans, and 20 combined minimum segment area/minimum MU plans. Each plan was evaluated and compared to others based on dose volume histograms (DVHs) (i.e., plan quality), planning time, and delivery time. To evaluate delivery efficiency, a model was developed that estimated the delivery time of a treatment plan, and validated through measurements on an Elekta Synergy linear accelerator. Results: The uncertainty (i.e., variation) of the dose-volume index due to dose calculation grid variation was as high as 8.2% (5.5 Gy in absolute dose) for planning target volumes (PTVs) and 13.3% (2.1 Gy in absolute dose) for planning at risk volumes (PRVs). Comparison results of dose distributions indicated that smaller volumes were more susceptible to uncertainties. The grid resolution of a 4 mm dose grid with a 2 mm fluence grid was recommended, since it can reduce the final dose calculation time by 63% compared to the accepted standard (2 mm dose grid with a 2 mm fluence grid resolution) while maintaining a similar level of dose-volume index variation. Threshold values that maintained adequate plan quality (DVH results of the PTVs and PRVs remained satisfied for their dose objectives) were 5 cm{sup 2} for minimum segment area and 5 MU for minimum MU. As the minimum MU parameter was increased, the number of segments and delivery time were decreased. Increasing the minimum segment area parameter decreased the plan MU, but had less of an effect on the number of segments and delivery time. Our delivery time model predicted delivery time to within 1.8%. Conclusions: Increasing the dose grid while maintaining a small fluence grid allows for improved planning efficiency without compromising plan quality. Delivery efficiency can be improved by increasing the minimum MU, but not the minimum segment area. However, increasing the respective minimum MU and/or the minimum segment area to any value greater than 5 MU and 5 cm{sup 2} is not recommended because it degrades plan quality.

  20. TWRS Retrieval and Storage Mission and Immobilized Low Activity Waste (ILAW) Disposal Plan

    SciTech Connect (OSTI)

    BURBANK, D.A.

    1999-09-01T23:59:59.000Z

    This project plan has a twofold purpose. First, it provides a waste stream project plan specific to the River Protection Project (RPP) (formerly the Tank Waste Remediation System [TWRS] Project) Immobilized Low-Activity Waste (LAW) Disposal Subproject for the Washington State Department of Ecology (Ecology) that meets the requirements of Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) Milestone M-90-01 (Ecology et al. 1994) and is consistent with the project plan content guidelines found in Section 11.5 of the Tri-Party Agreement action plan (Ecology et al. 1998). Second, it provides an upper tier document that can be used as the basis for future subproject line-item construction management plans. The planning elements for the construction management plans are derived from applicable U.S. Department of Energy (DOE) planning guidance documents (DOE Orders 4700.1 [DOE 1992] and 430.1 [DOE 1995a]). The format and content of this project plan are designed to accommodate the requirements mentioned by the Tri-Party Agreement and the DOE orders. A cross-check matrix is provided in Appendix A to explain where in the plan project planning elements required by Section 11.5 of the Tri-Party Agreement are addressed.

  1. Unvented Drum Handling Plan

    SciTech Connect (OSTI)

    MCDONALD, K.M.

    2000-08-01T23:59:59.000Z

    This drum-handling plan proposes a method to deal with unvented transuranic drums encountered during retrieval of drums. Finding unvented drums during retrieval activities was expected, as identified in the Transuranic (TRU) Phase I Retrieval Plan (HNF-4781). However, significant numbers of unvented drums were not expected until excavation of buried drums began. This plan represents accelerated planning for management of unvented drums. A plan is proposed that manages unvented drums differently based on three categories. The first category of drums is any that visually appear to be pressurized. These will be vented immediately, using either the Hanford Fire Department Hazardous Materials (Haz. Mat.) team, if such are encountered before the facilities' capabilities are established, or using internal capabilities, once established. To date, no drums have been retrieved that showed signs of pressurization. The second category consists of drums that contain a minimal amount of Pu isotopes. This minimal amount is typically less than 1 gram of Pu, but may be waste-stream dependent. Drums in this category are assayed to determine if they are low-level waste (LLW). LLW drums are typically disposed of without venting. Any unvented drums that assay as TRU will be staged for a future venting campaign, using appropriate safety precautions in their handling. The third category of drums is those for which records show larger amounts of Pu isotopes (typically greater than or equal to 1 gram of Pu). These are assumed to be TRU and are not assayed at this point, but are staged for a future venting campaign. Any of these drums that do not have a visible venting device will be staged awaiting venting, and will be managed under appropriate controls, including covering the drums to protect from direct solar exposure, minimizing of container movement, and placement of a barrier to restrict vehicle access. There are a number of equipment options available to perform the venting. The preferred option is to use equipment provided by a commercial vendor during the first few years of retrieval and venting. This is based on a number of reasons. First, retrieval funding is uncertain. Using a commercial vendor will allow DOE-RL to avoid the investment and maintenance costs if retrieval is not funded. Second, when funding can be identified, retrieval will likely be performed with minimal initial throughput and intermittent operations. Again, costs can be saved by using contracted vendor services only as needed, rather than supporting Hanford equipment full time. When full-scale retrieval begins and the number of drums requiring venting increases significantly, then use of the Hanford container venting system (CVS) should be considered.

  2. ON LINE HOUSING APPLICATION PROCESS SUMMARY Required steps to access online housing application

    E-Print Network [OSTI]

    McConnell, Terry

    ON LINE HOUSING APPLICATION PROCESS SUMMARY Required steps to access online housing application Admission to the University Return Intent to Register & make advance Tuition Payment Make advance housing payment if planning to live on-campus Activate your NetID Receive an e-mail from the Housing Office

  3. On line chemical composition of analyzer development. Status report, February 1, 1992--April 30, 1992

    SciTech Connect (OSTI)

    Not Available

    1992-07-01T23:59:59.000Z

    This status report details progress made on the development of an on-line chemical analyzer. Dynamic studies of the distillation column, approval of testing plans, installation of a sample cell and raman analyzer, design of computerized control systems are described. Information on seminars and published papers is also included. (GHH)

  4. What can emission lines tell us?

    E-Print Network [OSTI]

    G. Stasinska

    2007-04-03T23:59:59.000Z

    1 Generalities 2 Empirical diagnostics based on emission lines 3 Photoionization modelling 4 Pending questions 5 Appendix: Lists of useful lines and how to deal with them

  5. Dumbarton Express Line DB heading to Stanford Oval. AC Transit Line U on Palm Drive.

    E-Print Network [OSTI]

    Dumbarton Express Line DB heading to Stanford Oval. AC Transit Line U on Palm Drive. Photo: Karl Nielsen Photo: Dong Wang Schedules: AC Transit Line U Dumbarton Express Line DB Connections with BART Transit Line U Line U provides express service between Stanford and the Fremont BART station. Other East

  6. NIF Title III engineering plan

    SciTech Connect (OSTI)

    Deis, G

    1998-06-01T23:59:59.000Z

    The purpose of this document is to define the work that must be accomplished by the NIF Project during Title III Engineering. This definition is intended to be sufficiently detailed to provide a framework for yearly planning, to clearly identify the specific deliverables so that the Project teams can focus on them, and to provide a common set of objectives and processes across the Project. This plan has been preceded by similar documents for Title I and Title II design and complements the Site Management Plan, the Project Control Manual, the Quality Assurance Program Plan, the RM Parsons NIF Title III Configuration Control Plan, the Integrated Project Schedule, the Preliminary Safety Analysis Report, the Configuration Management Plan, and the Transition Plan.

  7. FY 1994 Annual Work Plan

    SciTech Connect (OSTI)

    Not Available

    1993-09-30T23:59:59.000Z

    In accordance with the Inspector General`s Strategic Planning Policy directive, the Office of Inspector General (OIG) annually updates its Strategic Plan with budgetary and program guidance for the next fiscal year. The program guidance identifies and establishes priorities for OIG coverage of important DOE issues and operations, provides the basis for assigning OIG resources, and is the source for issues covered in Assistant Inspectors General annual work plans. The Office of the Assistant Inspector General for Audits (AIGA) publishes an Annual Work Plan in September of each year. The plan includes the OIG program guidance and shows the commitment of resources necessary to accomplish the assigned work and meet our goals. The program guidance provides the framework within which the AIGA work will be planned and accomplished. Audits included in this plan are designed to help insure that the requirements of our stakeholders have been considered and blended into a well balanced audit program.

  8. Project Management Plan Solution Stabilization

    SciTech Connect (OSTI)

    SATO, P.K.

    1999-08-31T23:59:59.000Z

    This plan presents the overall objectives, description, justification and planning for the Plutonium Finishing Plant (PFP) Solutions Stabilization subproject. The intent of this plan is to describe how this project will be managed and integrated with other facility stabilization and deactivation activities. This plan supplements the overall integrated plan presented in the Integrated Project Management Plan (IPMP) for the Plutonium Finishing Plant Stabilization and Deactivation Project, HNF-3617. This project plan is the top-level definitive project management document for the PFP Solution Stabilization subproject. It specifies the technical, schedule, requirements and the cost baselines to manage the execution of the Solution Stabilization subproject. Any deviations to the document must be authorized through the appropriate change control process.

  9. 1 INTRODUCTION We consider network protection (NP) by line switch-

    E-Print Network [OSTI]

    Paris-Sud XI, Université de

    phenomenon due to avalanches of node outages. The rest of the paper is organized as follows. Section 2 & Marchiori 2005, Duenas-Osorio & Vemuru 2009, Zio & Sansavini 2010). Optimization of electrical grid that minimizes the consequences of cascading failures on an electrical grid. The 380 kV Italian power

  10. Columbia Campus Emergency Management Plan

    E-Print Network [OSTI]

    Almor, Amit

    .......................................................................5 VII Recovery and Deactivation.........................................................7 IX Responsibilities of Academic and Administrative Units..................................8 · Steam Line Failure................................................................................30

  11. NATIONAL INSTITUTES OF Chemical Hygiene Plan

    E-Print Network [OSTI]

    Bandettini, Peter A.

    NATIONAL INSTITUTES OF HEALTH Chemical Hygiene Plan Division of Occupational Health Chemical Hygiene Plan Evaluation and Record Keeping

  12. 1997 U.S. Department of Energy Strategic Plan

    SciTech Connect (OSTI)

    None,

    1997-09-01T23:59:59.000Z

    With the end of the Cold War and the election of President Clinton, the Department of Energy (DOE) set a new course which began with the publication of its first departmental strategic plan in April 1994. Entitled ``Fueling a Competitive Economy, it provided the framework and shared vision for meeting responsibilities in energy, national security, environmental quality, and science and technology. The strategic plan was the guidepost for the formulation of the Department`s FY 1996, FY 1997, and FY 1998 budgets and was critical to the development of the Department`s Strategic Alignment Initiative, designed to save $1.7 billion over five years. This current plan, which has been significantly improved through a very close consultation process with Congress and customers stakeholders, takes DOE to the next important performance level by being more directly linked to actions and results. It defines a strategic goal for each of the Department`s four business lines and, in the spirit of the Government Performance and Results Act and the National Performance Review, identifies a fifth goal addressing corporate management. Reengineering the business practices, managing for results, being open with neighbors and stakeholders, and ensuring the safety and health of DOE workers and the public are, and will continue to be, among the highest of priorities. Over the coming years, DOE plans to achieve their strategic goals through specific identifiable strategies. Each business line has clear objectives and straightforward ways of defining whether DOE has succeeded in meeting those objectives.

  13. Environmental Management System Plan

    SciTech Connect (OSTI)

    Fox, Robert; Thorson, Patrick; Horst, Blair; Speros, John; Rothermich, Nancy; Hatayama, Howard

    2009-03-24T23:59:59.000Z

    Executive Order 13423, Strengthening Federal Environmental, Energy, and Transportation Management establishes the policy that Federal agencies conduct their environmental, transportation, and energy-related activities in a manner that is environmentally, economically and fiscally sound, integrated, continually improving, efficient, and sustainable. The Department of Energy (DOE) has approved DOE Order 450.1A, Environmental Protection Program and DOE Order 430.2B, Departmental Energy, Renewable Energy and Transportation Management as the means of achieving the provisions of this Executive Order. DOE Order 450.1A mandates the development of Environmental Management Systems (EMS) to implement sustainable environmental stewardship practices that: (1) Protect the air, water, land, and other natural and cultural resources potentially impacted by facility operations; (2) Meet or exceed applicable environmental, public health, and resource protection laws and regulations; and (3) Implement cost-effective business practices. In addition, the DOE Order 450.1A mandates that the EMS must be integrated with a facility's Integrated Safety Management System (ISMS) established pursuant to DOE P 450.4, 'Safety Management System Policy'. DOE Order 430.2B mandates an energy management program that considers energy use and renewable energy, water, new and renovated buildings, and vehicle fleet activities. The Order incorporates the provisions of the Energy Policy Act of 2005 and Energy Independence and Security Act of 2007. The Order also includes the DOE's Transformational Energy Action Management initiative, which assures compliance is achieved through an Executable Plan that is prepared and updated annually by Lawrence Berkeley National Laboratory (LBNL, Berkeley Lab, or the Laboratory) and then approved by the DOE Berkeley Site Office. At the time of this revision to the EMS plan, the 'FY2009 LBNL Sustainability Executable Plan' represented the most current Executable Plan. These DOE Orders and associated policies establish goals and sustainable stewardship practices that are protective of environmental, natural, and cultural resources, and take a life cycle approach that considers aspects such as: (1) Acquisition and use of environmentally preferable products; (2) Electronics stewardship; (3) Energy conservation, energy efficiency, and renewable energy; (4) Pollution prevention, with emphasis on toxic and hazardous chemical and material reduction; (5) Procurement of efficient energy and water consuming materials and equipment; (6) Recycling and reuse; (7) Sustainable and high-performance building design; (8) Transportation and fleet management; and (9) Water conservation. LBNL's approach to sustainable environmental stewardship required under Order 450.1A poses the challenge of implementing its EMS in a compliance-based, performance-based, and cost-effective manner. In other words, the EMS must deliver real and tangible business value at a minimal cost. The purpose of this plan is to describe Berkeley Lab's approach for achieving such an EMS, including an overview of the roles and responsibilities of key Laboratory parties. This approach begins with a broad-based environmental policy consistent with that stated in Chapter 11 of the LBNL Health and Safety Manual (PUB-3000). This policy states that Berkeley Lab is committed to the following: (1) Complying with applicable environmental, public health, and resource conservation laws and regulations. (2) Preventing pollution, minimizing waste, and conserving natural resources. (3) Correcting environmental hazards and cleaning up existing environmental problems, and (4) Continually improving the Laboratory's environmental performance while maintaining operational capability and sustaining the overall mission of the Laboratory. A continual cycle of planning, implementing, evaluating, and improving processes will be performed to achieve goals, objectives, and targets that will help LBNL carry out this policy. Each year, environmental aspects will be identified and their impacts to the environm

  14. Quasistellar Objects: Intervening Absorption Lines

    E-Print Network [OSTI]

    Jane C. Charlton; Christopher W. Churchill

    2000-05-31T23:59:59.000Z

    We briefly review, at a level appropriate for graduate students and non-specialists, the field of quasar absorption lines (QALs). Emphasis is on the intervening absorbers. We present the anatomy of a quasar spectrum due to various classes of intervening absorption systems, and a brief historical review of each absorber class (Lyman-alpha forest and Lyman limit systems, and metal-line and damped Lyman-alpha absorbers). We also provide several heuristic examples on how the physical properties of both the intergalactic medium and the gaseous environments associated with earlier epoch galaxies can be inferred from QALs. The evolution of these environments from z=4 are discussed.

  15. ESnet Program Plan 1994

    SciTech Connect (OSTI)

    Merola, S.

    1994-11-01T23:59:59.000Z

    This Program Plan characterizes ESnet with respect to the current and future needs of Energy Research programs for network infrastructure, services, and development. In doing so, this document articulates the vision and recommendations of the ESnet Steering Committee regarding ESnet`s development and its support of computer networking facilities and associated user services. To afford the reader a perspective from which to evaluate the ever-increasing utility of networking to the Energy Research community, we have also provided a historical overview of Energy Research networking. Networking has become an integral part of the work of DOE principal investigators, and this document is intended to assist the Office of Scientific Computing in ESnet program planning and management, including prioritization and funding. In particular, we identify the new directions that ESnet`s development and implementation will take over the course of the next several years. Our basic goal is to ensure that the networking requirements of the respective scientific programs within Energy Research are addressed fairly. The proliferation of regional networks and additional network-related initiatives by other Federal agencies is changing the process by which we plan our own efforts to serve the DOE community. ESnet provides the Energy Research community with access to many other peer-level networks and to a multitude of other interconnected network facilities. ESnet`s connectivity and relationship to these other networks and facilities are also described in this document. Major Office of Energy Research programs are managed and coordinated by the Office of Basic Energy Sciences, the Office of High Energy and Nuclear Physics, the Office of Magnetic Fusion Energy, the Office of Scientific Computing, and the Office of Health and Environmental Research. Summaries of these programs are presented, along with their functional and technical requirements for wide-area networking.

  16. Navy Geothermal Plan

    SciTech Connect (OSTI)

    Not Available

    1984-12-01T23:59:59.000Z

    Domestic geothermal resources with the potential for decreasing fossil fuel use and energy cost exist at a significant number of Navy facilities. The Geothermal Plan is part of the Navy Energy R and D Program that will evaluate Navy sites and provide a technical, economic, and environmental base for subsequent resource use. One purpose of the program will be to provide for the transition of R and D funded exploratory efforts into the resource development phase. Individual Navy geothermal site projects are described as well as the organizational structure and Navy decision network. 2 figs.

  17. ARM - Lesson Plans

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625govInstrumentstdmadap Documentation TDMADAP : XDC documentationBarrow, Alaska Outreach Home RoomPlans Outreach Home

  18. LDRD Program Plan master

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOEThe Bonneville PowerCherries 82981-1cnHigh SchoolIn12electron 9 5 - -/e),,s - 1 2 3 4 5 6 7 8 9 104 Program Plan

  19. Plan Your Visit

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office of Science (SC)IntegratedSpeeding accessPeptoidLabPhysics Physics Oursources |Visit Plan your

  20. Guidance for Planning Exercises

    Office of Environmental Management (EM)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33Frequently Asked Questions for DOE FYAffairs, and InternationalPlanning, Conducting and Evaluating

  1. Draft Closure Plan

    Office of Environmental Management (EM)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33 1112011 Strategic Plan Department ofNotices | Department of Energy 29DepartmentNatural

  2. Draft Closure Plan

    Office of Environmental Management (EM)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33 1112011 Strategic Plan Department ofNotices | Department of Energy 29DepartmentNatural8

  3. Draft Closure Plan

    Office of Environmental Management (EM)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33 1112011 Strategic Plan Department ofNotices | Department of Energy 29DepartmentNatural89

  4. Draft Closure Plan

    Office of Environmental Management (EM)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33 1112011 Strategic Plan Department ofNotices | Department of Energy 29DepartmentNatural890

  5. Draft Closure Plan

    Office of Environmental Management (EM)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33 1112011 Strategic Plan Department ofNotices | Department of Energy 29DepartmentNatural8902

  6. Draft Closure Plan

    Office of Environmental Management (EM)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33 1112011 Strategic Plan Department ofNotices | Department of Energy 29DepartmentNatural89026

  7. Draft Closure Plan

    Office of Environmental Management (EM)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33 1112011 Strategic Plan Department ofNotices | Department of Energy 29DepartmentNatural890261

  8. Draft Closure Plan

    Office of Environmental Management (EM)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33 1112011 Strategic Plan Department ofNotices | Department of Energy 29DepartmentNatural890261

  9. TransBorder 2035 Metropolitan Transportation Plan

    E-Print Network [OSTI]

    El Paso Metropolitan Planning Organization

    2007-11-16T23:59:59.000Z

    i TransBorder 2035 Metropolitan Transportation Plan November 16, 2007 El Paso Metropolitan Planning Organization www.elpasompo.org ii TransBorder 2035 Metropolitan Transportation Plan November 16, 2007... El Paso Metropolitan Planning Organization www.elpasompo.org iii TransBorder 2035 Metropolitan Transportation Plan November 16, 2007 El Paso Metropolitan Planning Organization www.elpasompo.org iv Trans...

  10. My PhD Plan Completed Work

    E-Print Network [OSTI]

    Ruina, Andy L.

    Background My PhD Plan Completed Work Planned Work Hierarchical Biped Control A Exam Matthew Kelly August 4, 2014 Matthew Kelly Hierarchical Biped Control 1 / 34 #12;Background My PhD Plan Completed Work Planned Work Table of Contents 1 Background 2 My PhD Plan 3 Completed Work 4 Planned Work Push Hold Free

  11. Split-Volume Treatment Planning of Multiple Consecutive Vertebral Body Metastases for Cyberknife Image-Guided Robotic Radiosurgery

    SciTech Connect (OSTI)

    Sahgal, Arjun [Department of Radiation Oncology, University of California San Francisco, San Francisco, CA (United States)], E-mail: arjunsahgal@yahoo.com; Chuang, Cynthia; Larson, David; Huang, Kim; Petti, Paula [Department of Radiation Oncology, University of California San Francisco, San Francisco, CA (United States); Weinstein, Phil [Department of Neurologic Surgery, University of California San Francisco, San Francisco, CA (United States); Ma Lijun [Department of Radiation Oncology, University of California San Francisco, San Francisco, CA (United States)

    2008-10-01T23:59:59.000Z

    Cyberknife treatment planning of multiple consecutive vertebral body metastases is challenging due to large target volumes adjacent to critical normal tissues. A split-volume treatment planning technique was developed to improve the treatment plan quality of such lesions. Treatment plans were generated for 1 to 5 consecutive thoracic vertebral bodies (CVBM) prescribing a total dose of 24 Gy in 3 fractions. The planning target volume (PTV) consisted of the entire vertebral body(ies). Treatment plans were generated considering both the de novo clinical scenario (no prior radiation), imposing a dose limit of 8 Gy to 1 cc of spinal cord, and the retreatment scenario (prior radiation) with a dose limit of 3 Gy to 1 cc of spinal cord. The split-volume planning technique was compared with the standard full-volume technique only for targets ranging from 2 to 5 CVBM in length. The primary endpoint was to obtain best PTV coverage by the 24 Gy prescription isodose line. A total of 18 treatment plans were generated (10 standard and 8 split-volume). PTV coverage by the 24-Gy isodose line worsened consistently as the number of CVBM increased for both the de novo and retreatment scenario. Split-volume planning was achieved by introducing a 0.5-cm gap, splitting the standard full-volume PTV into 2 equal length PTVs. In every case, split-volume planning resulted in improved PTV coverage by the 24-Gy isodose line ranging from 4% to 12% for the de novo scenario and, 8% to 17% for the retreatment scenario. We did not observe a significant trend for increased monitor units required, or higher doses to spinal cord or esophagus, with split-volume planning. Split-volume treatment planning significantly improves Cyberknife treatment plan quality for CVBM, as compared to the standard technique. This technique may be of particular importance in clinical situations where stringent spinal cord dose limits are required.

  12. Institutional Plan FY 2003 - 2007

    SciTech Connect (OSTI)

    Chartock, Michael; Hansen, Todd

    2003-01-27T23:59:59.000Z

    The Fiscal Year (FY) 2003-2007 Institutional Plan describes the strategic directions and key issues that Lawrence Berkeley National Laboratory management must address with the Department of Energy (DOE) in charting its future as a multiprogram national laboratory. The Plan provides an overview of the Laboratory's mission, strategic plan, initiatives, and the resources required to fulfill its role in support of national needs in fundamental science and technology, energy resources, and environmental quality. The Plan facilitates the Department of Energy's ongoing efforts to strengthen the Integrated Laboratory System. Preparation and review of the Institutional Plan is one element of the Department of Energy's strategic management planning activities, implemented through an annual planning process. The Plan supports the President's Management Agenda and the Government Performance and Results Act of 1993. The Plan complements the current performance-based contract between the Department of Energy and the Regents of the University of California, and summarizes Best Management Practices for a potential future results-based contract as a basis for achieving DOE goals and the Laboratory's scientific and operations objectives. It identifies technical and administrative directions in the context of national energy policy and research needs and the Department of Energy's program planning initiatives. Preparation of the Plan is coordinated by the Planning and Strategic Development Office from information contributed by Berkeley Lab's scientific and support divisions and DOE comments on prior years' plans. The Laboratory Mission section identifies the specific strengths of Berkeley Lab that contribute to the mission in general and the Integrated Laboratory System in particular. The Laboratory Strategic Plan section identifies the existing activities in support of DOE Office of Science and other sponsors; support for DOE goals; and the Laboratory Scientific Vision and operations goals. The Initiatives section describes some of the specific new research programs representing major long-term opportunities for the Department of Energy and Berkeley Lab. The Operations Strategic Planning section describes our strategic thinking in the areas of human resources; site and cyber security; workforce diversity; communications and trust; integrated safety management; and technology transfer activities. The Infrastructure Strategic Planning section describes Berkeley Lab's facilities planning process and our site and facility needs. The Summary of Major Issues section provides context for discussions at the Institutional Planning On-Site Review. The Resource Projections are estimates of required budgetary authority for Berkeley Lab's research programs.

  13. Hot Springs Metropolitan Planning Organization 2030 Long Range Transportation Plan

    E-Print Network [OSTI]

    Hot Springs Metropolitan Planning Organization

    2005-11-03T23:59:59.000Z

    Federal Highway Administration Federal Transit Administration 2030 Long Range Transportation Plan for the Hot Springs Area Metropolitan Planning Organization This LRTP has been funded with federal Metropolitan Planning (PL) funds through... the Federal Highway Administration, Section 5303 funds through the Federal Transit Administration, the State of Arkansas, and participating agency local match funds. HSA-MPO 100 Broadway Terrace Hot Springs, AR 71901 501-321-4804 HSA...

  14. South Texas Planning Region Public Transportation Coordination Plan

    E-Print Network [OSTI]

    South Texas Development Council Economic Development Program

    2006-12-15T23:59:59.000Z

    KFH GROUP, INC. SOUTH TEXAS PLANNING REGION PUBLIC TRANSPORTATION COORDINATION PLAN Developed for the: SOUTH TEXAS DEVELOPMENT COUNCIL ECONOMIC DEVELOPMENT PROGRAM By: KFH Group, Incorporated December... that will permit increased levels of service; and 3. To further the state?s efforts to reduce air pollution? (HB3588, Article 13, Chapter 461, Section 461.001). In 2005, the TxDOT Draft Strategic Plan called for the development of regional public transportation...

  15. Waste classification sampling plan

    SciTech Connect (OSTI)

    Landsman, S.D.

    1998-05-27T23:59:59.000Z

    The purpose of this sampling is to explain the method used to collect and analyze data necessary to verify and/or determine the radionuclide content of the B-Cell decontamination and decommissioning waste stream so that the correct waste classification for the waste stream can be made, and to collect samples for studies of decontamination methods that could be used to remove fixed contamination present on the waste. The scope of this plan is to establish the technical basis for collecting samples and compiling quantitative data on the radioactive constituents present in waste generated during deactivation activities in B-Cell. Sampling and radioisotopic analysis will be performed on the fixed layers of contamination present on structural material and internal surfaces of process piping and tanks. In addition, dose rate measurements on existing waste material will be performed to determine the fraction of dose rate attributable to both removable and fixed contamination. Samples will also be collected to support studies of decontamination methods that are effective in removing the fixed contamination present on the waste. Sampling performed under this plan will meet criteria established in BNF-2596, Data Quality Objectives for the B-Cell Waste Stream Classification Sampling, J. M. Barnett, May 1998.

  16. Coiled transmission line pulse generators

    DOE Patents [OSTI]

    McDonald, Kenneth Fox (Columbia, MO)

    2010-11-09T23:59:59.000Z

    Methods and apparatus are provided for fabricating and constructing solid dielectric "Coiled Transmission Line" pulse generators in radial or axial coiled geometries. The pour and cure fabrication process enables a wide variety of geometries and form factors. The volume between the conductors is filled with liquid blends of monomers, polymers, oligomers, and/or cross-linkers and dielectric powders; and then cured to form high field strength and high dielectric constant solid dielectric transmission lines that intrinsically produce ideal rectangular high voltage pulses when charged and switched into matched impedance loads. Voltage levels may be increased by Marx and/or Blumlein principles incorporating spark gap or, preferentially, solid state switches (such as optically triggered thyristors) which produce reliable, high repetition rate operation. Moreover, these Marxed pulse generators can be DC charged and do not require additional pulse forming circuitry, pulse forming lines, transformers, or an a high voltage spark gap output switch. The apparatus accommodates a wide range of voltages, impedances, pulse durations, pulse repetition rates, and duty cycles. The resulting mobile or flight platform friendly cylindrical geometric configuration is much more compact, light-weight, and robust than conventional linear geometries, or pulse generators constructed from conventional components. Installing additional circuitry may accommodate optional pulse shape improvements. The Coiled Transmission Lines can also be connected in parallel to decrease the impedance, or in series to increase the pulse length.

  17. Camera Calibration Using Line Correspondences

    E-Print Network [OSTI]

    Hartley, Richard

    Camera Calibration Using Line Correspondences Richard I. Hartley G.E. CRD, Schenectady, NY, 12301. The three cameras may have different unknown calibrations, and the essential matrices corresponding to each, camera calibration and scene reconstruction. In the case where all the three cameras are assumed to have

  18. Fuel Fabrication Capability Research and Development Plan

    SciTech Connect (OSTI)

    Senor, David J.; Burkes, Douglas

    2014-04-17T23:59:59.000Z

    The purpose of this document is to provide a comprehensive review of the mission of the Fuel Fabrication Capability (FFC) within the Global Threat Reduction Initiative Convert Program, along with research and development (R&D) needs that have been identified as necessary to ensuring mission success. The design and fabrication of successful nuclear fuels must be closely linked endeavors. Therefore, the overriding motivation behind the FFC R&D program described in this plan is to foster closer integration between fuel design and fabrication to reduce programmatic risk. These motivating factors are all interrelated, and progress addressing one will aid understanding of the others. The FFC R&D needs fall into two principal categories, 1) baseline process optimization, to refine the existing fabrication technologies, and 2) manufacturing process alternatives, to evaluate new fabrication technologies that could provide improvements in quality, repeatability, material utilization, or cost. The FFC R&D Plan examines efforts currently under way in regard to coupon, foil, plate, and fuel element manufacturing, and provides recommendations for a number of R&D topics that are of high priority but not currently funded (i.e., knowledge gaps). The plan ties all FFC R&D efforts into a unified vision that supports the overall Convert Program schedule in general, and the fabrication schedule leading up to the MP-1 and FSP-1 irradiation experiments specifically. The fabrication technology decision gates and down-selection logic and schedules are tied to the schedule for fabricating the MP-1 fuel plates, which will provide the necessary data to make a final fuel fabrication process down-selection. Because of the short turnaround between MP-1 and the follow-on FSP-1 and MP-2 experiments, the suite of specimen types that will be available for MP-1 will be the same as those available for FSP-1 and MP-2. Therefore, the only opportunity to explore parameter space and alternative processing is between now and 2016 when the candidate processes are down-selected in preparation for the MP-1, FSP-1, and MP-2 plate manufacturing campaigns. A number of key risks identified by the FFC are discussed in this plan, with recommended mitigating actions for those activities within FFC, and identification of risks that are impacted by activities in other areas of the Convert Program. The R&D Plan does not include discussion of FFC initiatives related to production-scale manufacturing of fuel (e.g., establishment of the Pilot Line Production Facility), rather, the goal of this plan is to document the R&D activities needed ultimately to enable high-quality and cost-effective production of the fuel by the commercial fuel fabricator. The intent is for this R&D Plan to be a living document that will be reviewed and updated on a regular basis (e.g., annually) to ensure that FFC R&D activities remain properly aligned to the needs of the Convert Program. This version of the R&D Plan represents the first annual review and revision.

  19. Hanford 200 Areas Development Plan

    SciTech Connect (OSTI)

    Rinne, C.A.; Daly, K.S.

    1993-08-01T23:59:59.000Z

    The purpose of the Hanford 200 Areas Development Plan (Development Plan) is to guide the physical development of the 200 Areas (which refers to the 200 East Area, 200 West Area, and 200 Area Corridor, located between the 200 East and 200 West Areas) in accordance with US Department of Energy (DOE) Order 4320.lB (DOE 1991a) by performing the following: Establishing a land-use plan and setting land-use categories that meet the needs of existing and proposed activities. Coordinating existing, 5-year, and long-range development plans and guiding growth in accordance with those plans. Establishing development guidelines to encourage cost-effective development and minimize conflicts between adjacent activities. Identifying site development issues that need further analysis. Integrating program plans with development plans to ensure a logical progression of development. Coordinate DOE plans with other agencies [(i.e., Washington State Department of Ecology (Ecology) and US Environmental Protection Agency (EPA)]. Being a support document to the Hanford Site Development Plan (DOE-RL 1990a) (parent document) and providing technical site information relative to the 200 Areas.

  20. Groundwater Protection Plan (West Virginia)

    Broader source: Energy.gov [DOE]

    Groundwater Protection Plans (GPPs) are required for all facilities having the potential to impact groundwater. They are “preventive maintenance” documents that cover all processes and materials at...

  1. PHYSICS DIVISION CHEMICAL HYGIENE PLAN

    E-Print Network [OSTI]

    Kemner, Ken

    PHYSICS DIVISION CHEMICAL HYGIENE PLAN 2008 Prepared by _________________________________________________ T. Mullen Physics Division Chemical Hygiene Officer Reviewed by ___________________________________________________ J. Woodring Site Chemical Hygiene Officer Approved

  2. National Grid Energy Efficiency Plans

    Broader source: Energy.gov [DOE]

    Presentation covers the National Grid Energy Efficiency plans and is given at the Spring 2010 Federal Utility Partnership Working Group (FUPWG) meeting in Providence, Rhode Island.

  3. Chemical Hygiene and Safety Plan

    E-Print Network [OSTI]

    Ricks Editor, R.

    2009-01-01T23:59:59.000Z

    Preventive Maintenance .and Safet_l Plan 6. Preventive Maintenance Hazard ControlE-12, E-13, D-3 preventive maintenance, B-7, F-16 to F-18,

  4. Community Energy Strategic Planning Resources

    Broader source: Energy.gov [DOE]

    Presentation for the Community Energy Stategic Planning Resources webinar, presented on January 24, 2013 as part of the U.S. Department of Energy's Technical Assistance Program (TAP).

  5. Planning Water Use in California

    E-Print Network [OSTI]

    Eisenstein, William; Kondolf, G. Mathias

    2008-01-01T23:59:59.000Z

    the University of Maryland Water Policy Collaborative, 2006.FURTH ER READ ING California Department of Water Resources.California Water Plan Update 2005: A Framework for Action.

  6. Emergency Readiness Assurance Plans (ERAPs)

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-08-21T23:59:59.000Z

    This volume describes the assessments and documentation that would ensure that stated response capabilities are sufficient to implement emergency plans. Canceled by DOE G 151.1-3.

  7. Computer aided architectural space planning

    E-Print Network [OSTI]

    Schramek, Charles Wayne

    1971-01-01T23:59:59.000Z

    f' or introducing me to the space planning aspect of ar chitecture. TARLL ilF CUNTCIUTS Ci(RVTI R I CHAI'TCR II INTRODUCTION. ARCHITECTURAL SPACE PLANNING. . CHAPTCR III TIRE SPACL PLANNING PROCESS. . 12 C I I A I ' I C I/ I U CHAI'TF. R U... L I-I A PT F' R U I THE IrlTERREI ATIONS ANALYSIS MODEL. . . THE SPACE ALLOCATION PROGRAM. . . . . . . . FLITLIRE PLANNING AND DEVELOPMENT. . . . . S(1 40 CI-IRPTER UI I THE SUMIMIARY LITERATURE CITEU. Al'Pi: NDICES SAI'IPLE DATA SHEETS II...

  8. Categorical Exclusion (CX) Determination Proposed Action: Elliot...

    Broader source: Energy.gov (indexed) [DOE]

    Elliot 115kV43.8kV Transmission Substation Construction and Elliot 43.8kV Transmission Line. Description of Proposed Action: The Central Power Electric Cooperative (Central Power)...

  9. Test Series 2. 3 detailed test plan

    SciTech Connect (OSTI)

    Not Available

    1983-12-01T23:59:59.000Z

    Test Series 2.3 is chronologically the second of the five sub-series of tests which comprise Test Series 2, the second major Test Series as part of the combustion research phase to be carried out at the Grimethorpe Experimental Pressurised Fluidised Bed Combustion Facility. Test Series 2.3 will consist of 700 data gathering hours which is expected to require some 1035 coal burning hours. The tests will be performed using US supplied coal and dolomite. This will be the first major series of tests on the Facility with other than the UK datum coal and dolomite. The document summarises the background to the facility and the experimental program. Described are modifications which have been made to the facility following Test Series 2.1 and a series of Screening Tests. Detailed test objectives are specified as are the test conditions for the experiments which comprise the test series. The test results will provide information on the effects of the bed temperature, excess air level, Ca/S ratio, number of coal feed lines, and combustion efficiency and sulphur retention. A significant aspect of the test series will be part load tests which will investigate the performance of the facility under conditions of turn down which simulate load following concepts specified for two combined cycle concepts, i.e., their CFCC combined cycle and a turbo charged combined cycle. The material test plan is also presented. The principal feature of the materials programme is the planned exposure of a set of static turbine blade specimens in a cascade test loop to the high temperature, high pressure flue gas. A schedule for the programme is presented as are contingency plans.

  10. Thermal Stabilization Blend Plan

    SciTech Connect (OSTI)

    RISENMAY, H.R.

    2000-05-02T23:59:59.000Z

    This Blend Plan documents the feed material items that are stored in 2736-2 vaults, the 2736-ZB 638 cage, the 192C vault, and the 225 vault that will be processed through the thermal stabilization furnaces. The purpose of thermal stabilization is to heat the material to 1000 degrees Celsius to drive off all water and leave the plutonium and/or uranium as oxides. The stabilized material will be sampled to determine the Loss On Ignition (LOI) or percent water. The stabilized material must meet water content or LOI of less than 0.5% to be acceptable for storage under DOE-STD-3013-99 specifications. Out of specification material will be recycled through the furnaces until the water or LOI limits are met.

  11. GEND planning report

    SciTech Connect (OSTI)

    None

    1980-10-01T23:59:59.000Z

    The Three Mile Island (TMI) Unit 2 accident on March 28, 1979 was and is of great concern to the nuclear industry; electric power generating companies and their customers, regulatory and other government agencies, the entire nuclear community, and to the country as a whole. While the accident resulted in only limited external plant radiation exposure, the plant itself suffered extensive damage with high radiation contamination within the reactor and auxiliary system facilities. The GEND Planning Report for cleanup activities at TMI-2 covers the areas of: instrumentation and electrical equipment survivability; fission product transport; decontamination/radiation dose reduction technology; data bank organization and sample archive facility; characterization of primary system pressure boundary and mechanical components; core damage assessment; and fuel handling, removal, examination and disposal.

  12. A reservoir management plan

    SciTech Connect (OSTI)

    Allis, R.G.

    1989-06-16T23:59:59.000Z

    There are numerous documented cases of extraction of fluids from the ground causing surface subsidence. The cases include groundwater, oil and gas, as well as geothermal fluid withdrawal. A recent comprehensive review of all types of man-induced land subsidence was published by the Geological Survey of America. At the early stages of a geothermal power development project it is standard practice in most countries for an environmental impact report to be required. The possibility of geothermal subsidence has to be addressed, and usually it falls on the geophysicists and/or geologists to make some predictions. The advice given is vital for planning the power plant location and the borefield pipe and drain layout. It is not so much the vertical settlement that occurs with subsidence but the accompanying horizontal ground strains that can do the most damage to any man-made structure.

  13. Mitigation Action Plan

    SciTech Connect (OSTI)

    Not Available

    1994-02-01T23:59:59.000Z

    This Mitigation Action Plan (MAP) focuses on mitigation commitments stated in the Supplemental Environmental Impact Statement (SEIS) and the Record of Decision (ROD) for the Naval Petroleum Reserve No. 1 (NPR-1). Specific commitments and mitigation implementation actions are listed in Appendix A-Mitigation Actions, and form the central focus of this MAP. They will be updated as needed to allow for organizational, regulatory, or policy changes. It is the intent of DOE to comply with all applicable federal, state, and local environmental, safety, and health laws and regulations. Eighty-six specific commitments were identified in the SEIS and associated ROD which pertain to continued operation of NPR-1 with petroleum production at the Maximum Efficient Rate (MER). The mitigation measures proposed are expected to reduce impacts as much as feasible, however, as experience is gained in actual implementation of these measures, some changes may be warranted.

  14. Human Service Transportation PlanHuman Service Transportation Plan UPDATEUPDATE

    E-Print Network [OSTI]

    Illinois at Chicago, University of

    , Princeton Regions 1 and 3: full-time Bi-state Regional Commission, Rock Island Region 2: Part-time Tri-County Regional Planning Commission, Peoria (also MPO) Region 5: Part-time Champaign County Regional Planning, Macomb & Springfield- Sangamon County RPC, Springfield Region 4 and 7: full-time (by WIRC) South Central

  15. Lesson Plan Lesson plan: Haiti in the elementary classroom

    E-Print Network [OSTI]

    Lesson Plan Lesson plan: Haiti in the elementary classroom Rationale On January 12, 2010, tragedy struck Haiti when a 7.0 magnitude earthquake rocked the country. The Haitian government reported as the poorest country in the western hemisphere, Haiti is now trying more than ever to get back on its feet

  16. Heat Plan DenmarkHeat Plan Denmark Anders Dyrelundy

    E-Print Network [OSTI]

    the supply and the demand side · An eye-opener for the Danish politicians · Could be a model for otherHeat Plan DenmarkHeat Plan Denmark Anders Dyrelundy Market Manager for Energy and Climate Rambøll Möller · The first study in Denmark, really to integrate the energy and building sectors ­ to combine

  17. Feasibility of an image planning system for kilovoltage image-guided radiation therapy

    SciTech Connect (OSTI)

    Thapa, Bishnu B.; Molloy, Janelle A. [Department of Radiation Medicine, University of Kentucky, Lexington, Kentucky 40536-0293 (United States)

    2013-06-15T23:59:59.000Z

    Purpose: Image guidance has become a standard of care for many treatment scenarios in radiation therapy. This is most typically accomplished by use of kV x-ray devices mounted onto the linear accelerator (Linac) gantry that yield planar, fluoroscopic, and cone-beam computed tomography (CBCT) images. Image acquisition parameters are chosen via preset techniques that rely on broad categorizations in patient anatomy and imaging goal. However, the optimal imaging technique results in detectability of the features of interest while exposing the patient to minimum dose. Herein, the authors present an investigation into the feasibility of developing an image planning system (IPS) for radiotherapy.Methods: In this first phase, the authors focused on developing an algorithm to predict tissue contrast produced by a common radiotherapy planar imaging chain. Input parameters include a CT dataset and simulated planar imaging technique settings that include kV and mAs. Energy-specific attenuation through each voxel of the CT dataset was calculated in the algorithm to derive a net transmitted intensity. The response of the flat panel detector was integrated into the image simulation algorithm. Verification was conducted by comparing simulated and measured images using four phantoms. Comparisons were made in both high and low contrast settings, as well as changes in the geometric appearance due to image saturation. Results: The authors studied a lung nodule test object to assess the planning system's ability to predict object contrast and detectability. Verification demonstrated that the slope of the pixel intensities is similar, the presence of the nodule is evident, and image saturation at high mAs values is evident in both images. The appearance of the lung nodule is a function of the image detector saturation. The authors assessed the dimensions of the lung nodule in measured and simulated images. Good quantitative agreement affirmed the algorithm's predictive capabilities. The invariance of contrast with kVp and mAs prior to saturation was predicted, as well as the gradual loss of object detectability as saturation was approached. Small changes in soft tissue density were studied using a mammography step wedge phantom. Data were acquired at beam qualities of 80 and 120 kVp and over exposure values ranging from 0.04 to 500 mAs. The data showed good agreement in terms of the absolute value of pixel intensities predicted, as well as small variations across the step wedge pattern. The saturation pixel intensity was consistent between the two beam qualities studied. Boney tissue contrast was assessed using two abdominal phantoms. Measured and calculated values agree in terms of predicting the mAs value at which detector saturation, and subsequent loss of contrast occurs. The lack of variation in contrast over mAs values lower than 10 suggests that there is wide latitude for minimizing patient dose. Conclusions: The authors developed and tested an algorithm that can be used to assist in kV imaging technique selection during localization for radiotherapy. Phantom testing demonstrated the algorithm's predictive accuracy for both low and high contrast imaging scenarios. Detector saturation with subsequent loss of imaging detail, both in terms of object size and contrast were accurately predicted by the algorithm.

  18. Efficient generic on-line/off-line (threshold) signatures without key exposure q

    E-Print Network [OSTI]

    Kim, Kwangjo

    security requirements. Ó 2008 Elsevier Inc. All rights reserved. 1. Introduction The notion of on-line/off-line manufacturing process or as a background computation whenever the card is connected to power, and the on-lineEfficient generic on-line/off-line (threshold) signatures without key exposure q Xiaofeng Chen a

  19. Who plans for health improvement? SEA, HIA and the separation of spatial planning and health planning

    SciTech Connect (OSTI)

    Bond, Alan, E-mail: alan.bond@uea.ac.uk [InteREAM (Interdisciplinary Research in Environmental Assessment and Management), School of Environmental Sciences, University of East Anglia, Norwich, NR4 7TJ (United Kingdom)] [InteREAM (Interdisciplinary Research in Environmental Assessment and Management), School of Environmental Sciences, University of East Anglia, Norwich, NR4 7TJ (United Kingdom); Cave, Ben, E-mail: ben.cave@bcahealth.co.uk [Ben Cave Associates Ltd., Leeds (United Kingdom)] [Ben Cave Associates Ltd., Leeds (United Kingdom); Ballantyne, Rob, E-mail: robdballantyne@gmail.com [Planning and Health Consultant, Oxfordshire (United Kingdom)] [Planning and Health Consultant, Oxfordshire (United Kingdom)

    2013-09-15T23:59:59.000Z

    This study examines whether there is active planning for health improvement in the English spatial planning system and how this varies across two regions using a combination of telephone surveys and focus group interviews in 2005 and 2010. The spatial planning profession was found to be ill-equipped to consider the health and well-being implications of its actions, whilst health professionals are rarely engaged and have limited understanding and aspirations when it comes to influencing spatial planning. Strategic Environmental Assessment was not considered to be successful in integrating health into spatial plans, given it was the responsibility of planners lacking the capacity to do so. For their part, health professionals have insufficient knowledge and understanding of planning and how to engage with it to be able to plan for health gains rather than simply respond to health impacts. HIA practice is patchy and generally undertaken by health professionals outside the statutory planning framework. Thus, whilst appropriate assessment tools exist, they currently lack a coherent context within which they can function effectively and the implementation of the Kiev protocol requiring the engagement of health professionals in SEA is not to likely improve the consideration of health in planning while there continues to be separation of functions between professions and lack of understanding of the other profession. -- Highlights: ? Health professionals have limited aspirations for health improvement through the planning system. ? Spatial planners are ill-equipped to understand the health and well-being implications of their activities. ? SEA and HIA currently do not embed health consideration in planning decisions. ? The separation of health and planning functions is problematic for the effective conduct of SEA and/or HIA.

  20. Multicriteria optimization informed VMAT planning

    SciTech Connect (OSTI)

    Chen, Huixiao; Craft, David L.; Gierga, David P., E-mail: dgierga@partners.org

    2014-04-01T23:59:59.000Z

    We developed a patient-specific volumetric-modulated arc therapy (VMAT) optimization procedure using dose-volume histogram (DVH) information from multicriteria optimization (MCO) of intensity-modulated radiotherapy (IMRT) plans. The study included 10 patients with prostate cancer undergoing standard fractionation treatment, 10 patients with prostate cancer undergoing hypofractionation treatment, and 5 patients with head/neck cancer. MCO-IMRT plans using 20 and 7 treatment fields were generated for each patient on the RayStation treatment planning system (clinical version 2.5, RaySearch Laboratories, Stockholm, Sweden). The resulting DVH of the 20-field MCO-IMRT plan for each patient was used as the reference DVH, and the extracted point values of the resulting DVH of the MCO-IMRT plan were used as objectives and constraints for VMAT optimization. Weights of objectives or constraints of VMAT optimization or both were further tuned to generate the best match with the reference DVH of the MCO-IMRT plan. The final optimal VMAT plan quality was evaluated by comparison with MCO-IMRT plans based on homogeneity index, conformity number of planning target volume, and organ at risk sparing. The influence of gantry spacing, arc number, and delivery time on VMAT plan quality for different tumor sites was also evaluated. The resulting VMAT plan quality essentially matched the 20-field MCO-IMRT plan but with a shorter delivery time and less monitor units. VMAT plan quality of head/neck cancer cases improved using dual arcs whereas prostate cases did not. VMAT plan quality was improved by fine gantry spacing of 2 for the head/neck cancer cases and the hypofractionation-treated prostate cancer cases but not for the standard fractionation–treated prostate cancer cases. MCO-informed VMAT optimization is a useful and valuable way to generate patient-specific optimal VMAT plans, though modification of the weights of objectives or constraints extracted from resulting DVH of MCO-IMRT or both is necessary.

  1. The MICE Muon Beam Line

    SciTech Connect (OSTI)

    Apollonio, Marco [High Energy Physics Group, Department of Physics, Imperial College London SW7 2AZ (United Kingdom)

    2011-10-06T23:59:59.000Z

    In the Muon Ionization Cooling Experiment (MICE) at RAL, muons are produced and transported in a dedicated beam line connecting the production point (target) to the cooling channel. We discuss the main features of the beamline, meant to provide muons with momenta between 140 MeV/c and 240 MeV/c and emittances up to 10 mm rad, which is accomplished by means of a diffuser. Matching procedures to the MICE cooling channel are also described. In summer 2010 we performed an intense data taking campaign to finalize the calibration of the MICE Particle Identification (PID) detectors and the understanding of the beam line, which completes the STEPI phase of MICE. We highlight the main results from these data.

  2. Planning Tool for Strategic Evaluation of Facility Plans - 13570

    SciTech Connect (OSTI)

    Magoulas, Virginia; Cercy, Michael [Savannah River National Laboratory, Savannah River Site, Aiken, SC 29808 (United States)] [Savannah River National Laboratory, Savannah River Site, Aiken, SC 29808 (United States); Hall, Irin [Newport News Shipbuilding, 4101 Washington Ave., Newport News, VA 23607 (United States)] [Newport News Shipbuilding, 4101 Washington Ave., Newport News, VA 23607 (United States)

    2013-07-01T23:59:59.000Z

    Savannah River National Laboratory (SRNL) has developed a strategic planning tool for the evaluation of the utilization of its unique resources for processing and research and development of nuclear materials. The Planning Tool is a strategic level tool for assessing multiple missions that could be conducted utilizing the SRNL facilities and showcasing the plan. Traditional approaches using standard scheduling tools and laying out a strategy on paper tended to be labor intensive and offered either a limited or cluttered view for visualizing and communicating results. A tool that can assess the process throughput, duration, and utilization of the facility was needed. SRNL teamed with Newport News Shipbuilding (NNS), a division of Huntington Ingalls Industries, to create the next generation Planning Tool. The goal of this collaboration was to create a simulation based tool that allows for quick evaluation of strategies with respect to new or changing missions, and clearly communicates results to the decision makers. This tool has been built upon a mature modeling and simulation software previously developed by NNS. The Planning Tool provides a forum for capturing dependencies, constraints, activity flows, and variable factors. It is also a platform for quickly evaluating multiple mission scenarios, dynamically adding/updating scenarios, generating multiple views for evaluating/communicating results, and understanding where there are areas of risks and opportunities with respect to capacity. The Planning Tool that has been developed is useful in that it presents a clear visual plan for the missions at the Savannah River Site (SRS). It not only assists in communicating the plans to SRS corporate management, but also allows the area stakeholders a visual look at the future plans for SRS. The design of this tool makes it easily deployable to other facility and mission planning endeavors. (authors)

  3. Planning your business: The Business Plan A business plan is like a road map for your business. Careful

    E-Print Network [OSTI]

    Planning your business: The Business Plan A business plan is like a road map for your business. Careful planning is key to any successful business. A business plan ensures that resources are available, including (time, money, and opportunities). It helps you decide where you want to go with the business

  4. In-line thermoelectric module

    DOE Patents [OSTI]

    Pento, Robert (Algonquin, IL); Marks, James E. (Glenville, NY); Staffanson, Clifford D. (S. Glens Falls, NY)

    2000-01-01T23:59:59.000Z

    A thermoelectric module with a plurality of electricity generating units each having a first end and a second end, the units being arranged first end to second end along an in-line axis. Each unit includes first and second elements each made of a thermoelectric material, an electrically conductive hot member arranged to heat one side of the first element, and an electrically conductive cold member arranged to cool another side of the first element and to cool one side of the second element. The hot member, the first element, the cold member and the second element are supported in a fixture, are electrically connected respectively to provide an electricity generating unit, and are arranged respectively in positions along the in-line axis. The individual components of each generating unit and the respective generating units are clamped in their in-line positions by a loading bolt at one end of the fixture and a stop wall at the other end of the fixture. The hot members may have a T-shape and the cold members an hourglass shape to facilitate heat transfer. The direction of heat transfer through the hot members may be perpendicular to the direction of heat transfer through the cold members, and both of these heat transfer directions may be perpendicular to the direction of current flow through the module.

  5. FY 1994 Annual Work Plan

    SciTech Connect (OSTI)

    Not Available

    1993-10-01T23:59:59.000Z

    This is the third Office of Inspector General (OIG)Annual Work Plan. Its purpose is to summarize work completed in Fiscal Year (FY) 1993, identify ongoing projects from previous fiscal years which the OIG intends to continue into FY 1994, and announce planned projects which the OIG intends to begin in FY 19994.

  6. Choosing between Blue Cross plans...

    E-Print Network [OSTI]

    Burke, Peter

    Choosing between Blue Cross plans... ...when you have Medicare PresentedPresented By Glenn. Medicare and UC II. Medicare and Anthem Blue Cross III. Plan Comparisons · Pros/Cons · Medical coverage will automatically be enrolled in Part D by Blue Cross No additional Part D premium · Blue Cross members have

  7. Business Plan Development Company Description

    E-Print Network [OSTI]

    Dahl, David B.

    by the establishment of additional work stations. Raw materials purchasing and subsequent manufacturing need to be done purchasing and manufacturing under my personal name to-date. The concept of the device I patented market, marketing plan, web development, manufacturing plan to allow for maximum profit margin while

  8. FORESTRY BUILDING: BUILDING EMERGENCY PLAN

    E-Print Network [OSTI]

    FORESTRY BUILDING: BUILDING EMERGENCY PLAN Date Adopted: August 18, 2009 Date Revised June 17, 2013 Prepared By: Diana Evans and Jennifer Meyer #12;PURDUE UNIVERSITY BUILDING EMERGENCY PLAN VERSION 3 2 Table Suspension or Campus Closure SECTION 3: BUILDING INFORMATION 3.1 Building Deputy/Alternate Building Deputy

  9. Y-12 Site Sustainability Plan

    SciTech Connect (OSTI)

    none,; Erhart, S C; Spencer, C G

    2013-12-01T23:59:59.000Z

    This plan addresses: Greenhouse Gas Reduction and Comprehensive Greenhouse Gas Inventory; Buildings, ESPC Initiative Schedule, and Regional and Local Planning; Fleet Management; Water Use Efficiency and Management; Pollution Prevention and Waste Reduction; Sustainable Acquisition; Electronic Stewardship and Data Centers; Renewable Energy; Climate Change; and Budget and Funding.

  10. BIOMASS ACTION PLAN FOR SCOTLAND

    E-Print Network [OSTI]

    BIOMASS ACTION PLAN FOR SCOTLAND #12; #12;© Crown copyright 2007 ISBN: 978 0 7559 6506 9 Scottish% recyclable. #12;A BIOMASS ACTION PLAN FOR SCOTLAND #12;#12;1 CONTENTS FOREWORD 3 1. EXECUTIVE SUMMARY 5 2. INTRODUCTION 9 3. WIDER CONTEXT 13 4. SCOTLAND'S ROLE IN THE UK BIOMASS STRATEGY 17 5. BIOMASS HEATING 23 6

  11. A Sustainability Plan for Princeton

    E-Print Network [OSTI]

    A Sustainability Plan for Princeton #12;Princeton University adopted its Sustainability Plan and environmental degradation, Princeton has a responsibility to shape the national sustainability agenda and alternative energy sources. The campus can serve as both a model for advanced sustainability practices

  12. TECHNOLOGY MASTER PLAN 2013 2015

    E-Print Network [OSTI]

    TECHNOLOGY MASTER PLAN 2013 ­ 2015 Endorsed by Academic Senate On October 25, 2013 & College Council On November 8, 2013 #12;Information Technology Strategic Plan 2013-2015 Prepared by Willie Pritchard & Gene Spencer, Higher Education Technology Consultants on behalf of the many participants

  13. APPLIED TECHNOLOGY Strategic Plan Summary

    E-Print Network [OSTI]

    Heller, Barbara

    and collaborative technology-based support for the proposed Innovation Center and the Entrepreneurship Academy. We research centers­CNR, CPI, and CSP. Establish a food safety and processing technology hub/incubator/innovationSCHOOL OF APPLIED TECHNOLOGY Strategic Plan Summary #12;School of Applied Technology Strategic Plan

  14. LDRD FY 2014 Program Plan

    SciTech Connect (OSTI)

    Anita Gianotto; Dena Tomchak

    2013-08-01T23:59:59.000Z

    As required by DOE Order 413.2B the FY 2014 Program Plan is written to communicate ares of investment and approximate amounts being requested for the upcoming fiscal year. The program plan also includes brief highlights of current or previous LDRD projects that have an opportunity to impact our Nation's current and future energy challenges.

  15. REGIONAL WATER SUPPLY PLANNING AND

    E-Print Network [OSTI]

    Mays, Larry W.

    CHAPTER 3 REGIONAL WATER SUPPLY PLANNING AND CAPACITY EXPANSION MODELS Messele Z. Ejeta California Department of Water Resources Sacramento, California Larry W. Mays Department of Civil and Environmental Engineering Arizona State University Tempe, Arizona 3.1 INTRODUCTION Water supply planning on a regional scale

  16. COMMISSION REPORT 20122013 INVESTMENT PLAN

    E-Print Network [OSTI]

    , and diesel substitute fuels. State investment is necessary to fill the gap and fund the differential cost COMMISSION REPORT 20122013 INVESTMENT PLAN UPDATE FOR THE ALTERNATIVE AND RENEWABLE FUEL the Energy Commission to adopt an investment plan that describes how funding will complement existing public

  17. GENERAL PENSION PLAN INFORMATION SESSION

    E-Print Network [OSTI]

    Kambhampati, Patanjali

    rates · Age 30 · Earning $50,000 · Retiring at age 65 · Salary Increase: 3% · Investment Return: 5% Cost is intended to inform you about the McGill Pension Plan & the importance of integrating pension investmentGill University Pension Plan; Familiarize yourself with investment basics; Understand the importance

  18. Groundwater protection management program plan

    SciTech Connect (OSTI)

    Not Available

    1992-06-01T23:59:59.000Z

    US Department of Energy (DOE) Order 5400.1 requires the establishment of a groundwater protection management program to ensure compliance with DOE requirements and applicable Federal, state, and local laws and regulations. The Uranium Mill Tailings Remedial Action (UMTRA) Project Office has prepared a ``Groundwater Protection Management Program Plan`` (groundwater protection plan) of sufficient scope and detail to reflect the program`s significance and address the seven activities required in DOE Order 5400.1, Chapter 3, for special program planning. The groundwater protection plan highlights the methods designed to preserve, protect, and monitor groundwater resources at UMTRA Project processing and disposal sites. The plan includes an overview of the remedial action status at the 24 designated processing sites and identifies project technical guidance documents and site-specific documents for the UMTRA groundwater protection management program. In addition, the groundwater protection plan addresses the general information required to develop a water resources protection strategy at the permanent disposal sites. Finally, the plan describes ongoing activities that are in various stages of development at UMTRA sites (long-term care at disposal sites and groundwater restoration at processing sites). This plan will be reviewed annually and updated every 3 years in accordance with DOE Order 5400.1.

  19. 2030 Transportation and Mobility Plan

    E-Print Network [OSTI]

    Bi-State Metropolitan Planning Organization

    2006-08-11T23:59:59.000Z

    The Bi-State MPO 2030 T RANSPORTATION A N D MOBILITY PLAN Transport t at t i i on Invest t ment t s f f... 2030 Transportation and Mobility Plan Prepared by: The Bi-State MPO Staff In cooperation with: The Cities and Towns of Alma Arkoma Barling Bonanza Fort Smith Greenwood Kibler Lavaca Moffett Muldrow Pocola Roland Rudy Spiro...

  20. Climate Change Proposed Scoping Plan

    E-Print Network [OSTI]

    Climate Change Proposed Scoping Plan a amework for change Prepared by the California Air Resources #12;CLIMATE CHANGE SCOPING PLAN State of California Air Resources Board Resolution 08-47 December 11 greenhouse gas (GHG) emissions that cause global warming; WHEREAS, the adverse impacts of climate change