Sample records for kv kilovolt kva

  1. EIS-0379- Rebuild of the Libby (FEC) to Troy Section of BPA’s 115-kilovolt Transmission Line in Libby, Lincoln County, Montana

    Broader source: Energy.gov [DOE]

    This Environmental Impact Statement (EIS) assesses the potential environmental impacts that would result from a proposed Department of Energy (DOE) action on the proposed rebuilding, operation, and maintenance of a 17-mile-long portion of BPA’s Libby to Bonners Ferry 115-kilovolt (kV) Transmission Line in Lincoln County, Montana. The portion to be rebuilt would start at Flathead Electric Cooperative’s (FEC) Libby Substation, in the town of Libby, Montana, and proceed west along an existing right-of-way for about 17 miles, terminating at BPA’s Troy Substation just east of the town of Troy, Montana.

  2. Type A Accident Investigation Board Report of the April 25, 1997, Contractor Fatality on the Olympia-White River #1 230 kV Line

    Broader source: Energy.gov [DOE]

    On April 25, 1997, at approximately 1510 hours, a lineman for Great Southwestern Construction Inc. was fatally electrocuted when he came in direct contact with a deenergized 230-kilovolt (kV) transmission power line conductor which contained an induced voltage.

  3. EIS-0107: Mead-Phoenix +500-kV Direct Current Transmission Line

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy’s Western Area Power Administration (WAPA) prepared this statement to analyze the potential environmental and socioeconomic impacts arising from WAPA and regional project sponsors’ proposal to construct a 500 kilovolt (kV) alternating current (AC) transmission line with the capability to be upgraded later to 500kV direct current (DC), connecting the Westwing Substation, located north of Phoenix, Arizona, with a new McCullough II Substation, located approximately 14 miles west of Boulder City, Nevada. This statement modifies a previously prepared federal statement from which the participants' election to proceed had not occurred at the time this statement was prepared.

  4. A 6 kV arbitrary waveform generator for the Tevatron Electron Lens

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Pfeffer, H.; Saewert, G.

    2011-11-01T23:59:59.000Z

    This paper reports on a 6 kV modulator built and installed at Fermilab to drive the electron gun anode for the Tevatron Electron Lens (TEL). The TEL was built with the intention of shifting the individual (anti)proton bunch tunes to even out the tune spread among all 36 bunches with the desire of improving Tevatron integrated luminosity. This modulator is essentially a 6 kV arbitrary waveform generator that enables the TEL to define the electron beam intensity on a bunch-by-bunch basis. A voltage waveform is constructed having a 7 {micro}s duration that corresponds to the tune shift requirements of amore »12-bunch (anti)proton beam pulse train. This waveform is played out for any one or all three bunch trains in the Tevatron. The programmed waveform voltages transition to different levels at time intervals corresponding to the 395 ns bunch spacing. Thus, complex voltage waveforms can be played out at a sustained rate of 143 kHz over the full 6 kV output range. This paper describes the novel design of the inductive adder topology employing five transformers. It describes the design aspects that minimize switching losses for this multi-kilovolt, high repetition rate and high duty factor application.« less

  5. A 6 kV arbitrary waveform generator for the Tevatron Electron Lens

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Pfeffer, H.; Saewert, G.

    2011-11-01T23:59:59.000Z

    This paper reports on a 6 kV modulator built and installed at Fermilab to drive the electron gun anode for the Tevatron Electron Lens (TEL). The TEL was built with the intention of shifting the individual (anti)proton bunch tunes to even out the tune spread among all 36 bunches with the desire of improving Tevatron integrated luminosity. This modulator is essentially a 6 kV arbitrary waveform generator that enables the TEL to define the electron beam intensity on a bunch-by-bunch basis. A voltage waveform is constructed having a 7 {micro}s duration that corresponds to the tune shift requirements of a 12-bunch (anti)proton beam pulse train. This waveform is played out for any one or all three bunch trains in the Tevatron. The programmed waveform voltages transition to different levels at time intervals corresponding to the 395 ns bunch spacing. Thus, complex voltage waveforms can be played out at a sustained rate of 143 kHz over the full 6 kV output range. This paper describes the novel design of the inductive adder topology employing five transformers. It describes the design aspects that minimize switching losses for this multi-kilovolt, high repetition rate and high duty factor application.

  6. Environmental Assessment of the Gering-Stegall 115-kV Transmission Line Consolidation Project, Scotts Bluff County, Nebraska

    SciTech Connect (OSTI)

    NONE

    1995-05-01T23:59:59.000Z

    The Department of Energy (DOE), Western Area Power Administration (Western) proposes to consolidate segments of two transmission lines near the Gering Substation in Gering, Nebraska. The transmission lines are both located in Scotts Bluff County, Nebraska. The transmission lines are both located in Scotts Bluff County, Nebraska, within the city of Gering. Presently, there are three parallel 115-kilovolt (kV) transmission lines on separate rights-of-way (ROW) that terminate at the Gering Substation. The project would include dismantling the Archer-Gering wood-pole transmission line and rebuilding the remaining two lines on single-pole steel double circuit structures. The project would consolidate the Gering-Stegall North and Gering-Stegall South 115-kV transmission lines on to one ROW for a 1.33-mile segment between the Gering Substation and a point west of the Gering Landfill. All existing wood-pole H-frame structures would be removed, and the Gering-Stegall North and South ROWs abandoned. Western is responsible for the design, construction, operation, and maintenance of the line. Western prepared an environmental assessment (EA) that analyzed the potential environmental impacts of the proposed construction, operation, and maintenance of the 115-kV transmission line consolidation. Based on the analyses in the EA, the DOE finds that the proposed action is not a major Federal action significantly affecting the quality of the human environment, within the meaning of the National Environmental Policy Act of 1969 (NEPA).

  7. Big George to Carter Mountain 115-kV transmission line project, Park and Hot Springs Counties, Wyoming. Environmental Assessment

    SciTech Connect (OSTI)

    Not Available

    1994-02-01T23:59:59.000Z

    The Western Area Power Administration (Western) is proposing to rebuild, operate, and maintain a 115-kilovolt (kV) transmission line between the Big George and Carter Mountain Substations in northwest Wyoming (Park and Hot Springs Counties). This environmental assessment (EA) was prepared in compliance with the National Environmental Policy Act (NEPA) and the regulations of the Council on Environmental Quality (CEQ) and the Department of Energy (DOE). The existing Big George to Carter Mountain 69-kV transmission line was constructed in 1941 by the US Department of Interior, Bureau of Reclamation, with 1/0 copper conductor on wood-pole H-frame structures without an overhead ground wire. The line should be replaced because of the deteriorated condition of the wood-pole H-frame structures. Because the line lacks an overhead ground wire, it is subject to numerous outages caused by lightning. The line will be 54 years old in 1995, which is the target date for line replacement. The normal service life of a wood-pole line is 45 years. Under the No Action Alternative, no new transmission lines would be built in the project area. The existing 69-kV transmission line would continue to operate with routine maintenance, with no provisions made for replacement.

  8. Environmental Assessment for Central Power and Light Company`s proposed Military Highway-CFE tie 138/69-kV transmission line project Brownsville, Cameron County, Texas

    SciTech Connect (OSTI)

    Not Available

    1992-04-01T23:59:59.000Z

    Central Power and Light Company (CPL) intends to upgrade its existing transmission line ties with the Commision Federal de Electricidad (CFE) system in Mexico. CPL currently has a single 69-kilovolt (kV) transmission line in the Brownsville area which connects CPL`s system with the system of CFE. This existing line runs between the Brownsville Switching Station, located on Laredo Road in Brownsville, Cameron County, Texas, and an existing CFE 69-kV line at the Rusteberg Bend of the Rio Grande in Cameron County. Under current conditions of need, the existing 69-kV line does not possess sufficient capability to engage in appropriate power exchanges. Therefore, CPL is proposing to build a new line to link up with CFE. This proposed line would be a double-circuit line, which would (1) continue (on a slightly relocated route) the existing 69-kV tie from CPL`s Brownsville Switching Station to CFE`s facilities, and (2) add a 138-kV tie from the Military Highway Substation, located on Military Highway (US Highway 281), to CFE`s facilities. The proposed 138/69-kV line, which will be constructed and operated by CPL, will be built primarily on steel single-pole structures within an average 60-foot (ft) wide right-of-way (ROW). It will be approximately 6900--9200 ft (1.3--1.7 miles) in length, depending on the alternative route constructed.

  9. KV-tOOJHfe Metallurgy Department

    E-Print Network [OSTI]

    »KV-tOOJHfe RisB-R-547 Metallurgy Department Progress Report for the Period 1 January to 31 December 1986 Risø National Laboratory, DK-4000 Roskilde, Denmark April 1987 #12;Risø-R-547 METALLURGY.B. BiIde-Sørensen Abstract. The activities of the Metallurgy Department at Risø during 1986

  10. EIS-0078: Jonesboro-Hergett 161-kV Transmission Line

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy's Southwestern Power Administration developed this statement to assess the environmental and socioeconomic impacts of a 161-kilovolt transmission line in Craighead County, Arkansas, including its proposed and alternate routes.

  11. EIS-0118: Proposed Eugene-Medford 500-kV Transmission Line

    Broader source: Energy.gov [DOE]

    The U.S. Department of Interior developed this statement to assess the environmental impact of a proposed 500-kilovolt transmission line linking Eugene and Medford, Oregon, that would cross through public lands. The Bonneville Power Administration (BPA) would provide service to the proposed line and is a cooperating agency in the statement. BPA adopted the EIS on 7/10/1985.

  12. Waltz Mill testing of 345-kV PPP cable

    SciTech Connect (OSTI)

    Burghardt, R.R. (Westinghouse Electric Corp., Ruffs Dale, PA (United States))

    1991-09-01T23:59:59.000Z

    A 345-kV PPP-insulated cable was subjected to a two-year accelerated life test program at the EPRI Waltz Mill Cable Test Facility. Testing started in November 1985 and was successfully completed in September 1988. The program included conductor temperatures ranging from 85{degrees}C to 105{degrees}C and line-to-line voltages from 362 kV to 474 kV. Cyclic testing was performed during 17 of the 24 months. Dissipation factor measurements were made throughout the program. The measurements indicated no deterioration of the cable or splices as a consequence of the high temperatures and voltages applied to them in this test program. 2 refs., 24 figs.

  13. Survey of Magnetic Fields Near BPA 230-kV and 500-kV Transmission Lines.

    SciTech Connect (OSTI)

    Perrin, Nancy; Aggarwal, Rajinder Pal; Bracken, T. Daniel

    1991-05-20T23:59:59.000Z

    The purpose of this study was to characterize typical levels and variability of 60Hz magnetic fields at the centerline and edge of right-of-way of Bonneville Power Administration (BPA) 230-kV and 500-kV transmission lines. This was accomplished by taking magnetic field measurements at over 800 spans in Oregon and Washington. The spans were sampled using a stratified random sampling procedure with region (East vs. West), voltage (230-kV vs 500-kV), and circuit configuration as strata. There were five different circuit configuration groups for each region/voltage category requiring a total of 200 strata. Magnetic field measurements were taken at 13 locations under each span using an EMDEX-C as a survey meter. Additional information recorded for each span included conductor height (at 10 locations), right-of-way width, longitudinal and lateral slope, time of day, vegetation, terrain, weather conditions, temperature, wind speed, span length and presence of other lines in the corridor. 9 refs., 17 figs., 26 tabs.

  14. Draft environmental impact statement for construction and operation of the proposed Bangor Hydro-Electric Company`s second 345-kV transmission tie line to New Brunswick

    SciTech Connect (OSTI)

    NONE

    1993-10-01T23:59:59.000Z

    This Draft Environmental Impact Statement (DEIS) was prepared by the US Department of Energy (US DOE). The proposed action is the issuance of Presidential Permit PP-89 by DOE to Bangor Hydro-Electric Company to construct and operate a new international transmission line interconnection to New Brunswick, Canada that would consist of an 83.8 mile (US portion), 345-kilovolt (kV) alternating current transmission line from the US-Canadian border at Baileyville, Maine to an existing substation at Orrington, Maine. The principal environmental impacts of the construction and operation of the transmission line would be incremental in nature and would include the conversion of forested uplands (mostly commercial timberlands) and wetlands to right-of-way (small trees, shrubs, and herbaceous vegetation). The proposed line would also result in localized minor to moderate visual impacts and would contribute a minor incremental increase in the exposure of some individuals to electromagnetic fields. This DEIS documents the purpose and need for the proposed action, describes the proposed action and alternatives considered and provides a comparison of the proposed and alternatives routes, and provides detailed information on analyses of the environmental consequences of the proposed action and alternatives, as well as mitigative measures to minimize impacts.

  15. Use of 120 Kilovolt Tube Potential for Digital Subtraction Angiography and Fluoroscopy in an Image-Intensifier Angiographic System: Decrease of Skin Dose in Transarterial Chemoembolization Therapy for Hepatocellular Carcinoma

    SciTech Connect (OSTI)

    Irie, Toshiyuki [Hitachi General Hospital, Department of Radiology (Japan)], E-mail: toshiyuki.irie@ibabyo.hitachi.co.jp; Satou, Ryuta [Hitachi General Hospital, Department of Radiological Technology (Japan)

    2007-09-15T23:59:59.000Z

    In an image-intensifier angiographic system, the tube potential is commonly regulated in ranges from 75 to 90 kV for digital subtraction angiography (DSA) and fluoroscopy in transarterial chemoembolization therapy (TACE) for hepatocellular carcinoma. The purpose of this study was to investigate whether or not a 120-kV tube potential could be used for DSA and fluoroscopy in TACE to decrease the skin dose. Forty-three patients administered TACE were randomly allocated into two groups: TACE was performed using standard-kilovoltage (75- to 90-kV) DSA and fluoroscopy modes (group A; n = 20) or using high-kilovoltage (120-kV) modes (group B; n = 23). The peak skin dose was compared between the groups. One case in group A was excluded from the study because the HCC nodule was not depicted on DSA. The peak skin dose (mGy) for group A was 383.6 {+-} 176.5 and that for group B was 265.1 {+-} 145.1. The peak skin dose was decreased by 31% in the 120-kV mode, a statistically significant difference (t-test, p = 0.022). We conclude that the use of 120 kV tube potential for DSA and fluoroscopy may be one option for performing TACE while decreasing the skin dose.

  16. A 50 kV solid state multipulse kicker modulator

    SciTech Connect (OSTI)

    Walstrom, P. L. (Peter L.); Cook, E. G. (Edward G.)

    2003-01-01T23:59:59.000Z

    Performance requirements, design concepts, and test results for a prototype multipulse kicker modulator based on solid-state switches and a voltage-adding transformer topology are described. Tape-wound cores are stacked to form the transformer primary windings and a cylindrical pipe that passes through the circular inner diameters of the cores serves as the secondary winding of the step-up transformer. Boards containing MOSFET switches, trigger circuitry, and energy-storage capacitors plug into the core housings. A 50 kV prototype modulator that meets most of the facility requirements has been designed, fabricated, and tested at LLNL. More recent work has been concerned with designing and testing cores and boards with the full volt-second capability needed for 24-pulse operation. Results of the 50 kV prototype tests, preliminary tests of the full-volt-second cores and boards, and future development needs are described.

  17. CEBAF 200 kV Inverted Electron Gun

    SciTech Connect (OSTI)

    J.M. Grames, P.A. Adderley, J. Clark, J. Hansknecht, M. Poelker, M.L. Stutzman, R. Suleiman, K.E.L. Surles-Law

    2011-03-01T23:59:59.000Z

    Two DC high voltage GaAs photoguns have been built at Jefferson Lab based on a compact inverted insulator design. One photogun provides the polarized electron beam at CEBAF and operates at 130 kV bias voltage. The other gun is used for high average current lifetime studies at a dedicated test facility and has been operated at bias voltage up to 225 kV. The advantages of higher DC voltage for CEBAF include reduced space-charge emittance growth and the potential for prolonged photocathode lifetime. However, a consequence of operating at higher voltages is the increased likelihood of field emission or breakdown, both of which are unacceptable. Highlights of the R&D studies leading toward a production 200keV GaAs photogun for CEBAF will be presented.

  18. The design and construction of a 130 K.V. radio frequency Cockcroft Walton type generator

    E-Print Network [OSTI]

    Robba, William Augustus

    1951-01-01T23:59:59.000Z

    at 30 KV are rather expensive~ and a 500 KV generator of this type would cost several thousand dollars. Sesides thisc the rcgulaticu and efficienoy of suoh a generator leave such to be desired An exanple will nake this c3Alaro Lot v o 1$ f, Vi g x... ourrent~ voltage snd poser for various staok voltages, Steak Voltages (One Stags) 20 K+V+ 15KV 12 K+V+ 10 K Vo 7. $ K. V. 220 Rile 180 Rile 140 ILQs 120 RGs 100 Mile 1500 Stack Plate Current Plato Voltage Poser in Watts QS $0 Varies Set...

  19. EIS-0091: Garrison-Spokane 500-kV Transmission Project

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy's Bonneville Power Administration (BPA) developed this statement to evaluate the environmental impacts of constructing between 254 and 271 miles of 500-kilovolt transmission line across western Montana and northern Idaho to the Spokane area in order to reinforce a section of the BPA electric power grid and to permit reliable integration of 1,240 megawatts of power produced by Colstrip Units 3 and 4, for use in Montana and throughout the Northwest.

  20. Corona performance of a compact 230-kV line

    SciTech Connect (OSTI)

    Chartier, V.L.; Blair, D.E. [Bonneville Power Administration, Vancouver, WA (United States). Division of Laboratories; Easley, M.D.; Raczkowski, R.T. [Puget Sound Power and Light Co., Bellevue, WA (United States)

    1994-12-31T23:59:59.000Z

    Permitting requirements and the acquisition of new rights-of-way for transmission facilities has in recent years become increasingly difficult for most utilities, including Puget Sound Power and Light Company. In order to maintain a high degree of reliability of service while being responsive to public concerns regarding the siting of high voltage (HV) transmission facilities, Puget Power has found it necessary to more heavily rely upon the use of compact lines in franchise corridors. Compaction does, however, precipitant increased levels of audible noise (AN) and radio and TV interference (RI and TVI) due to corona on the conductors and insulator assemblies. Puget Power relies upon the Bonneville Power Administration (BPA) Corona and Field Effects computer program to calculate AN and RI for new lines. Since there was some question of the program`s ability to accurately represent quiet 230-kV compact designs, a joint project was undertaken with BPA to verify the program`s algorithms. Long-term measurements made on an operating Puget Power 230-kV compact line confirmed the accuracy of BPA`s AN model; however, the RI measurements were much lower than predicted by the BPA computer and other programs. This paper also describes how the BPA computer program can be used to calculate the voltage needed to expose insulator assemblies to the correct electric field in single test setups in HV laboratories.

  1. Corona performance of a compact 230-kV line

    SciTech Connect (OSTI)

    Chartier, V.L.; Blair, D.E. [Bonneville Power Administration, Vancouver, WA (United States). Division of Labs.] [Bonneville Power Administration, Vancouver, WA (United States). Division of Labs.; Easley, M.D.; Raczkowski, R.T. [Puget Sound Power and Light Co., Bellevue, WA (United States)] [Puget Sound Power and Light Co., Bellevue, WA (United States)

    1995-01-01T23:59:59.000Z

    Permitting requirements and the acquisition of new rights-of-way for transmission facilities has in recent years become increasingly difficult for most utilities, including Puget Sound Power and Light Company. In order to maintain a high degree of reliability of service while being responsive to public concerns regarding the siting of high voltage (HV) transmission facilities, Puget Power has found it necessary to more heavily rely upon the use of compact lines in franchise corridors. Compaction does, however, precipitate increased levels of audible noise (AN) and radio and TV interference (RI and TVI) due to corona on the conductors and insulator assemblies. Puget Power relies upon the Bonneville Power Administration (BPA) Corona and Field Effects computer program to calculate AN and RI for new lines. Since there was some question of the program`s ability to accurately represent quiet 230-kV compact designs, a joint project was undertaken with BPA to verify the program`s algorithms. Long-term measurements made on an operating Puget Power 230-kV compact line confirmed the accuracy of BPA`s AN model; however, the RI measurements were much lower than predicted by the BPA and other programs. This paper also describes how the BPA computer program can be used to calculate the voltage needed to expose insulator assemblies to the correct electric field in single test setups in HV laboratories.

  2. Wild Horse 69-kV transmission line environmental assessment

    SciTech Connect (OSTI)

    NONE

    1996-12-01T23:59:59.000Z

    Hill County Electric Cooperative Inc. (Hill County) proposes to construct and operate a 69-kV transmission line from its North Gildford Substation in Montana north to the Canadian border. A vicinity project area map is enclosed as a figure. TransCanada Power Corporation (TCP), a Canadian power-marketing company, will own and construct the connecting 69-kV line from the international border to Express Pipeline`s pump station at Wild Horse, Alberta. This Environmental Assessment is prepared for the Department of Energy (DOE) as lead federal agency to comply with the requirements of the National Environmental Policy Act (NEPA), as part of DOE`s review and approval process of the applications filed by Hill County for a DOE Presidential Permit and License to Export Electricity to a foreign country. The purpose of the proposed line is to supply electric energy to a crude oil pump station in Canada, owned by Express Pipeline Ltd. (Express). The pipeline would transport Canadian-produced oil from Hardisty, Alberta, Canada, to Caster, Wyoming. The Express Pipeline is scheduled to be constructed in 1996--97 and will supply crude oil to refineries in Wyoming and the midwest.

  3. Oracle-Saguaro 115-kV Transmission Line Routine Maintenance Project...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Oracle-Saguaro 115-kV Transmission Line Routine Maintenance Project, Mile 6 to Oracle Substation Categorical Exclusion Continuation Sheet Project Description Maintenance work at...

  4. EIS-0344: Grand Coulee-Bell 500 kV Transmission Line

    Broader source: Energy.gov [DOE]

    This EIS analyzes DOE's proposed action for the construction and operation of the proposed Grand Coulee-Bell 500-kV Transmission Line Project.

  5. EIS-0112: Rifle to San Juan 345-kV Transmission Line and Associated Facilities

    Broader source: Energy.gov [DOE]

    The U.S. Department of Agriculture - Rural Electrification Administration developed this statement to evaluate the environmental impacts of the Colorado-Ute Electric Association Inc. and the U.s. Department of Energy's Western Area Power Administration (WAPA) constructing and operating a 345-kilovolt transmission line from Rifle, Colorado, to the San Juan Generating Station near Farmington, New Mexico. WAPA served as a cooperating agency in the preparation of this statement and adopted it on 10/30/1984. WAPA assumed the lead role for project implementation after issuance of the final statement.

  6. CEBAF 200 kV Inverted Electron Gun

    SciTech Connect (OSTI)

    Grames, J M; Clark, J; Hansknecht, J; Poelker, M; Stutzman, M L; Suleiman, R; Surles-Law, K.E.L.; BastaniNejad, M

    2011-03-01T23:59:59.000Z

    Two DC high volt­age GaAs pho­to­guns have been built at Jef­fer­son Lab based on a com­pact in­vert­ed in­su­la­tor de­sign. One pho­to­gun pro­vides the po­lar­ized elec­tron beam at CEBAF and op­er­ates at 130 kV bias volt­age. The other gun is used for high av­er­age cur­rent life­time stud­ies at a ded­i­cat­ed test fa­cil­i­ty and has been op­er­at­ed at bias volt­age up to 225 kV. The ad­van­tages of high­er DC volt­age for CEBAF in­clude re­duced space-charge emit­tance growth and the po­ten­tial for pro­longed pho­to­cath­ode life­time. How­ev­er, a con­se­quence of op­er­at­ing at high­er volt­ages is the in­creased like­li­hood of field emis­sion or break­down, both of which are un­ac­cept­able. High­lights of the R&D stud­ies lead­ing to­ward a pro­duc­tion 200keV GaAs pho­to­gun for CEBAF will be pre­sent­ed.

  7. Proposal for the award of a blanket purchase contract for the supply, installation, commissioning and maintenance of electrical switchgear operating at 18kV and 3.3 kV

    E-Print Network [OSTI]

    2015-01-01T23:59:59.000Z

    Proposal for the award of a blanket purchase contract for the supply, installation, commissioning and maintenance of electrical switchgear operating at 18kV and 3.3 kV

  8. Tungsten anode spectral model using interpolating cubic splines: Unfiltered x-ray spectra from 20 kV to 640 kV

    SciTech Connect (OSTI)

    Hernandez, Andrew M. [Biomedical Engineering Graduate Group, University of California Davis, Sacramento, California 95817 (United States)] [Biomedical Engineering Graduate Group, University of California Davis, Sacramento, California 95817 (United States); Boone, John M., E-mail: john.boone@ucdmc.ucdavis.edu [Departments of Radiology and Biomedical Engineering, Biomedical Engineering Graduate Group, University of California Davis, Sacramento, California 95817 (United States)

    2014-04-15T23:59:59.000Z

    Purpose: Monte Carlo methods were used to generate lightly filtered high resolution x-ray spectra spanning from 20 kV to 640 kV. Methods: X-ray spectra were simulated for a conventional tungsten anode. The Monte Carlo N-Particle eXtended radiation transport code (MCNPX 2.6.0) was used to produce 35 spectra over the tube potential range from 20 kV to 640 kV, and cubic spline interpolation procedures were used to create piecewise polynomials characterizing the photon fluence per energy bin as a function of x-ray tube potential. Using these basis spectra and the cubic spline interpolation, 621 spectra were generated at 1 kV intervals from 20 to 640 kV. The tungsten anode spectral model using interpolating cubic splines (TASMICS) produces minimally filtered (0.8 mm Be) x-ray spectra with 1 keV energy resolution. The TASMICS spectra were compared mathematically with other, previously reported spectra. Results: Using pairedt-test analyses, no statistically significant difference (i.e., p > 0.05) was observed between compared spectra over energy bins above 1% of peak bremsstrahlung fluence. For all energy bins, the correlation of determination (R{sup 2}) demonstrated good correlation for all spectral comparisons. The mean overall difference (MOD) and mean absolute difference (MAD) were computed over energy bins (above 1% of peak bremsstrahlung fluence) and over all the kV permutations compared. MOD and MAD comparisons with previously reported spectra were 2.7% and 9.7%, respectively (TASMIP), 0.1% and 12.0%, respectively [R. Birch and M. Marshall, “Computation of bremsstrahlung x-ray spectra and comparison with spectra measured with a Ge(Li) detector,” Phys. Med. Biol. 24, 505–517 (1979)], 0.4% and 8.1%, respectively (Poludniowski), and 0.4% and 8.1%, respectively (AAPM TG 195). The effective energy of TASMICS spectra with 2.5 mm of added Al filtration ranged from 17 keV (at 20 kV) to 138 keV (at 640 kV); with 0.2 mm of added Cu filtration the effective energy was 9 keV at 20 kV and 169 keV at 640 kV. Conclusions: Ranging from 20 kV to 640 kV, 621 x-ray spectra were produced and are available at 1 kV tube potential intervals. The spectra are tabulated at 1 keV intervals. TASMICS spectra were shown to be largely equivalent to published spectral models and are available in spreadsheet format for interested users by emailing the corresponding author (JMB)

  9. Final joint environmental assessment for the construction and routine operation of a 12-kilovolt (KV) overhead powerline right-of-way, and formal authorization for a 10-inch and 8-inch fresh water pipeline right-of-way, Naval Petroleum Reserve No. 1, Kern County, California

    SciTech Connect (OSTI)

    Not Available

    1994-10-01T23:59:59.000Z

    The purpose and need of the proposed action, which is the installation of an overhead powerline extension from an Naval Petroleum Reserve No. 1 (NPR-1) power source to the WKWD Station A, is to significantly reduce NPR-1`s overall utility costs. While the proposed action is independently justified on its own merits and is not tied to the proposed NPR-1 Cogeneration Facility, the proposed action would enable DOE to tie the NPR-1 fresh water pumps at Station A into the existing NPR-1 electrical distribution system. With the completion of the cogeneration facility in late 1994 or early 1995, the proposed action would save additional utility costs. This report deals with the environmental impacts of the construction of the powerline and the water pipeline. In addition, information is given about property rights and attaining permission to cross the property of proposed affected owners.

  10. 130kV 130A High Voltage Switching Mode Power Supply for Neutral Injections – Control Issues and Algorithms

    E-Print Network [OSTI]

    130kV 130A High Voltage Switching Mode Power Supply for Neutral Injections – Control Issues and Algorithms

  11. Deuterium Retention in Beryllium Exposed to a 60kV Deuterium Beam ­ Consequences for Next Step Devices

    E-Print Network [OSTI]

    Deuterium Retention in Beryllium Exposed to a 60kV Deuterium Beam ­ Consequences for Next Step Devices

  12. 150-kV, 80-A SOLID STATE POWER SUPPLY FOR NEUTRAL BEAM INJECTION

    E-Print Network [OSTI]

    Owren, H.

    2011-01-01T23:59:59.000Z

    owned rig 150-kV, 80-A SOLID STATE POWER SUPPLY FOR NEUTRALpaper describes an all solid state power supply designed forment and arc power supplies are also solid state. With the

  13. A SCR SWITCHED CAPACITOR VOLTAGE REGULATOR FOR 150 kV NEUTRAL BEAM POWER SUPPLY

    E-Print Network [OSTI]

    Milnes, K.A.

    2011-01-01T23:59:59.000Z

    et a1. , "150-kV, 80-A Solid State Power Supply for Neutral100% solid state and provides 1% regulation at power levelssolid state high voltage re- gulator. The block diagram of the power

  14. A 25 KV/10A PULSER FOR DRIVING A HIGH-POWER PIERCE ELECTRON GUN

    E-Print Network [OSTI]

    of short-circuits. Since the current capability of the tetrode is of the order of 10 A in the case of a short-circuit, the limit of the charging voltage is up to a maximum of 25 kV. The pulsed system has.0 A current and 10.0 kV beam voltage. Key words hard-tube pulser, Pierce electron gun, microwave tube

  15. Quality Assurance Plan for site electrical replacements at substation line item subproject: 69 KV Substation

    SciTech Connect (OSTI)

    Ohler, C.K.

    1991-05-21T23:59:59.000Z

    The 69 KV Substation Project is based on the recognized need to provide a continuous, reliable source of power and to improve the firm capacity of the electrical service to all production facilities at Mound. The project consists of the following major element: 69 KV Substation: (1) Install a 69 KV Substation and associated equipment with two parallel 18 MVA transformers. (2) Install duct bank as required and provide 15 KV feeder cable from new substation to existing Substation 95 for connection to Mound`s existing primary distribution system. (3) Install duct bank for underground routing of the 15 KV feeder cable from Manhole 5C to the existing power house cable pit. (4) Reconfigure existing Dayton Power and Light Co. 15 KV switchgear in P Building. The purpose of this Quality Assurance Plan (QA Plan) is to assure that the objectives of the United States Department of Energy (D.O.E.) and EG&G Mound Applied Technologies, Miamisburg, Ohio (Mound) are met for this non-weapons project relative to health and safety, protection of the environment, reliability and continuity of operations, and documentation of quality efforts. This QA Plan identifies the activities and responsibilities which are necessary in the design, procurement, fabrication, installation, and start up of this project in order to meet these objectives.

  16. CX-005419: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    Bonneville Power Administration is proposing to swap three 500-kilovolt (kV) transmission lines in Clackamas County, Oregon. DOCUMENT(S) AVAILABLE FOR DOWNLOAD CX-005419.pdf...

  17. EIS-0325: Schultz-Hanford Area Transmission Line Project, WA

    Broader source: Energy.gov [DOE]

    BPA proposes to construct a new 500-kilovolt (kV) transmission line in central Washington. This project would increase transmission system capacity north of Hanford.

  18. EIS-0294: Final Environmental Impact Statement | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    interconnection with Western's Keswick-ElvertaOlinda-Elverta 230-kilovolt (kV) transmission lines. Calpine proposed to construct and operate of the Sutter Power Project. Sutter...

  19. EIS-0325: Schultz-Hanford Area Transmission Line Project Final Environmental Impact Statement, EIS-0325 (January 2003)

    Broader source: Energy.gov [DOE]

    BPA proposes to construct a new 500-kilovolt (kV) transmission line in central Washington. This project would increase transmission system capacity north of Hanford.

  20. EIS-0486: Plains & Eastern Clean Line Transmission Project |...

    Broader source: Energy.gov (indexed) [DOE]

    project would include an overhead 600 kilovolt (kV) high voltage direct current (HVDC) electric transmission system and associated facilities with the capacity to deliver...

  1. EIS-0486-NOI-2012.pdf

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    project would include an overhead 600 kilovolt (kV) high voltage direct current (HVDC) electric transmission system and associated facilities with the capacity to deliver...

  2. Marys Lake 69/115-kV transmission line upgrade and substation expansion projects

    SciTech Connect (OSTI)

    NONE

    1996-05-01T23:59:59.000Z

    Western Area Power Administration (Western) and the Platte River Power Authority (Platte River) propose to upgrade portions of the existing electric transmission and substation system that serves the Town of Estes Park, Colorado. The existing transmission lines between the Estes Power Plant Switchyard and the Marys Lake Substation include a 115,000 volt (115-kV) line and 69,000 volt (69-kV) line. Approximately one mile is a double-circuit 115/69-kV line on steel lattice structures, and approximately two miles consists of separate single-circuit 115-kV and a 69-kV lines, constructed on wood H-Frame structures. Both lines were constructed in 1951 by the US Bureau of Reclamation. The existing transmission lines are on rights-of-way (ROW) that vary from 75 feet to 120 feet and are owned by Western. There are 48 landowners adjacent to the existing ROW. All of the houses were built adjacent to the existing ROW after the transmission lines were constructed. Upgrading the existing 69-kV transmission line between the Marys Lake Substation and the Estes Power Plant Switchyard to 115-kV and expanding the Marys Lake Substation was identified as the most effective way in which to improve electric service to Estes Park. The primary purpose and need of the proposed project is to improve the reliability of electric service to the Town of Estes Park. Lack of reliability has been a historical concern, and reliability will always be less than desired until physical improvements are made to the electrical facilities serving Estes Park.

  3. EIS-0032: 500 kV International Transmission Line NSP-TR-1, Forbes, Minnesota to Manitoba, Canada, Northern States Power Company

    Broader source: Energy.gov [DOE]

    The Economic Regulatory Administration developed this EIS to evaluate the environmental impacts of a 500-kilovolt transmission line proposed by the Northern States Power Company to provide a transmission facility for the exchange of electrical energy between Canada and the United States.

  4. EIS-0067: 230-kV International Transmission Line San Diego County, California to Tijuana, Mexico, San Diego Gas and Electric Company

    Broader source: Energy.gov [DOE]

    The Economic Regulatory Administration and the California Public Utilities Commission jointly prepared this EIS to evaluate the environmental impacts of the construction, maintenance and operation of a 10-mile, 230-kilovolt transmission line across the U.S./Mexico border for the purpose of economic exchange of power and increased reliability.

  5. 15-kV Single-Bias All-Optical ETO Thyristor A. Mojab and S.K. Mazumder

    E-Print Network [OSTI]

    Mazumder, Sudip K.

    15-kV Single-Bias All-Optical ETO Thyristor A. Mojab and S.K. Mazumder Laboratory for Energy 15 kV single bias and a current of 10 A. This ETO is completely controlled by two optical signals, one for the 15 kV SiC gate- turn-off (GTO) thyristor and the other one for a triggering low- voltage

  6. Waltz Mill testing of 765-kV paper-polypropylene-paper (PPP) cable

    SciTech Connect (OSTI)

    Burghardt, R.R. (Westinghouse Electric Corp., Ruffs Dale, PA (United States))

    1992-06-01T23:59:59.000Z

    A 765-kV PPP-insulated cable was subjected to a 27-month accelerated life test program at the EPRI Waltz Mill Cable Test Facility. Testing started in August 1981 and was successfully completed in January 1985. The program included conductor temperatures ranging from 85{degree}C to 105{degree}C and line-to-line voltages from 800 kV to 1050 kV. Cyclic testing was performed during 20 of the 27 months. Dissipation factor measurements were made throughout the program. The measurements indicated no deterioration of the cable or splices as a consequence of the high temperatures and voltages applied to them in this test program.

  7. Field Demonstration of a 24-kV Superconducting Cable at Detroit Edison

    SciTech Connect (OSTI)

    Kelley, Nathan; Corsaro, Pietro

    2004-12-01T23:59:59.000Z

    Customer acceptance of high temperature superconducting (HTS) cable technology requires a substantial field demonstration illustrating both the system's technical capabilities and its suitability for installation and operation within the utility environment. In this project, the world's first underground installation of an HTS cable using existing ductwork, a 120 meter demonstration cable circuit was designed and installed between the 24 kV bus distribution bus and a 120 kV-24 kV transformer at Detroit Edison's Frisbie substation. The system incorporated cables, accessories, a refrigeration system, and control instrumentation. Although the system was never put in operation because of problems with leaks in the cryostat, the project significantly advanced the state-of-the-art in the design and implementation of Warm Dielectric cable systems in substation applications. Lessons learned in this project are already being incorporated in several ongoing demonstration projects.

  8. Development of a thyristor valve for next generation 500kV HVDC transmission systems

    SciTech Connect (OSTI)

    Hasegawa, T. [Kansai Electric Power Co., Inc., Osaka (Japan)] [Kansai Electric Power Co., Inc., Osaka (Japan); Yamaji, K. [Shikoku Electric Power Co., Inc., Takamatsu (Japan)] [Shikoku Electric Power Co., Inc., Takamatsu (Japan); Irokawa, H. [Electric Power Development Co., Ltd., Tokyo (Japan)] [Electric Power Development Co., Ltd., Tokyo (Japan); Shirahama, H.; Tanaka, C.; Akabane, K.

    1996-10-01T23:59:59.000Z

    A high voltage thyristor valve is the basic component of an HVDC transmission system. Development of a 500kV valve for next generation HVDC transmission systems is described. First, the power loss of the valve is analyzed to decide a reasonable wafer size for the light triggered thyristor. From these results, a six inch diameter wafer size is selected. The light triggered thyristor, with ratings of 8kV and 3.5kA, is developed using the six inch wafer. The designing of the valve employing the thyristor and test results with the prototype valve prove that a 500kV valve can be realized by the design method.

  9. Development of 275kV gas cooled type gas-insulated power transformer

    SciTech Connect (OSTI)

    Kudo, A.; Nishitani, T.; Yoshikawa, T. (Mitsubishi Electric Corp., Ako (Japan)); Wan, C.T. (Hongkong Electric Co., Ltd. (Hong Kong))

    1993-01-01T23:59:59.000Z

    A world's first 275kV gas cooled type gas insulated power transformer with a low sound level ideal for urban area, which depends on SF6 gas alone for both insulation and cooling, was developed and has been put into commercial service since 1990 in Hong Kong. This paper presents the design philosophy, the principal technical items, the rating and the feature of 275kV 30MVA transformer, the performance test results, and the long term energization test result of the transformer.

  10. EIS-0450: TransWest Express 600 kV Direct Current Transmission Project in Wyoming, Colorado, Utah, and Nevada

    Broader source: Energy.gov [DOE]

    This EIS, being prepared jointly by DOE’s Western Area Power Administration and the Department of the Interior’s Bureau of Land Management (Wyoming State Office), evaluates the environmental impacts of granting a right-of-way for the TransWest Express 600-kilovolt Direct Current Transmission Project and amending a land use plan. The project consists of an overhead transmission line that would extend approximately 725 miles from south-central Wyoming, through Colorado and Utah. Western proposes to be a joint owner of the project. Additional information is available at http://www.blm.gov/wy/st/en/info/NEPA/documents/hdd/transwest.html.

  11. EA-1665: Davis-Kingman 69-kV Transmission Line Rebuild Project, Arizona

    Broader source: Energy.gov [DOE]

    Western plans to rebuild a 26.6-mile-long portion of the existing 27.3-mile-long Davis–Kingman Tap 69-kV Transmission Line within the existing ROW in order to improve the reliability of the transmission service.

  12. EA-2007: Groton-Ordway 115-kV Transmission Line, Groton, South Dakota

    Broader source: Energy.gov [DOE]

    DOE’s Western Area Power Administration (Upper Great Plains Region) is preparing an EA that assesses the potential environmental impacts of a proposal to construct a new 115-kV transmission line that would connect Western’s existing Groton and Ordway Substations near Groton, South Dakota.

  13. A charge-pump 60kV modulator for the ISOLDE target extraction voltage

    E-Print Network [OSTI]

    Barlow, R A; Fowler, A; Gaudillet, H; Gharsa, T; Schipper, J

    2015-01-01T23:59:59.000Z

    The ISOLDE facility at CERN provides radioactive ion beams to a number of experimental stations. These ions are produced by a metal target, floating at 60 kV, which is impacted by a 1.4 GeV high intensity proton beam. The ions are then accelerated by a grounded extraction electrode to 60 keV, before transport to the experimental area. During proton beam impact extremely high ionisation of the volume around the target gives rise to significant leakage current which results in loss of charge on the effective target capacitance of approximately 6 nF. If short life-time isotopes are to be studied, the 60 kV must be re-established within a maximum of 10 ms. Recharging the target capacitance to 60 kV and to the required stability of better than 10-4 precludes a direct charging system and an alternative method of re-establishing the 60 kV is used. The present system [1], in operation since 1991, employs a resonant circuit which is triggered 35 µs prior to beam impact. This circuit transfers the charge on the effec...

  14. Microsoft Word - LSN_FiberInstall_CX.docx

    Broader source: Energy.gov (indexed) [DOE]

    BPA's Ponderosa-Pilot Butte 230-kilovolt (kV) and Redmond-Pilot Butte 230-kV transmission lines in Deschutes County, Oregon. BPA has determined that the fiber would not...

  15. CX-010107: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    Exclusion Determination Curecanti-Morrow Point 230 Kilovolt (kV) and 12.47-kV Transmission Lines Access Road Maintenance CX(s) Applied: B1.3 Date: 04122013 Location(s):...

  16. EA-1456: Final Environmental Assessment | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    Cheyenne- Miracle Mile (CH-MM) and Ault-Cheyenne (AU-CH) 115 kilovolt (115-kV ) transmission lines to 230-kV. The proposed project consists of rebuilding these transmission lines...

  17. Design and Overview of 100 kV Bushing for the DNB Injector of ITER

    SciTech Connect (OSTI)

    Shah, Sejal; Bandyopadhyay, M.; Rotti, C.; Singh, M. J.; Roopesh, G.; Chakraborty, A. K. [ITER-India, Institute for Plasma Research, Gandhinagar-382025, Gujarat (India); Rajesh, S. [ITER-India, Institute for Plasma Research, Gandhinagar-382025, Gujarat (India); Microelectronics and Materials Physics Labs, P.O.Box 4500, FIN-90014 University of Oulu (Finland); Nishad, S.; Srusti, B. [DesignTech Systems Ltd, Banjara Hills, Hyderabad, Andhra Pradesh-500034 (India); Schunke, B.; Hemsworth, R.; Chareyre, J.; Svensson, L. [ITER Organisation, Route de Vinon, CS 90 046, 13067 St. Paul lez Durance Cedex (France)

    2011-09-26T23:59:59.000Z

    The 100 kV bushing is one of the most important and technologically challenging Safety Important Class (SIC) components of the Diagnostic Neutral Beam (DNB) injector of ITER. It forms interface between gas insulated electrical transmission line and torus primary vacuum and acts as a vacuum feedthrough of ITER. Design optimization has been carried out to meet the electric and structural requirements based on its classification. Unlike HNB bushing, single stage bushing is designed to provide 100 kV isolation. Finite Element Analysis (FEA) based optimization has been carried out for electrostatic and structural analysis. Manufacturing assembly sequence is studied and presented in this paper. However validation of the same is foreseen from manufacturer.

  18. Development of 500 kV DC PPLP-insulated oil-filled submarine cable

    SciTech Connect (OSTI)

    Fujimori, A. [Kansai Electric Power Co., Inc., Osaka (Japan)] [Kansai Electric Power Co., Inc., Osaka (Japan); Tanaka, T. [Electric Power Development Co., Ltd., Tokyo (Japan)] [Electric Power Development Co., Ltd., Tokyo (Japan); Takashima, H. [Shikoku Electric Power Co., Inc., Kagawa (Japan)] [Shikoku Electric Power Co., Inc., Kagawa (Japan); Imajo, T. [Central Research Inst. of Electric Power Industry, Tokyo (Japan)] [Central Research Inst. of Electric Power Industry, Tokyo (Japan); Hata, R. [Sumitomo Electric Industries, Ltd., Osaka (Japan)] [Sumitomo Electric Industries, Ltd., Osaka (Japan); Tanabe, T. [Furukawa Electric Co., Ltd., Tokyo (Japan)] [Furukawa Electric Co., Ltd., Tokyo (Japan); Yoshida, S. [Fujikura, Ltd., Tokyo (Japan)] [Fujikura, Ltd., Tokyo (Japan); Kakihana, T. [Hitachi Cable, Ltd., Tokyo (Japan)] [Hitachi Cable, Ltd., Tokyo (Japan)

    1996-01-01T23:59:59.000Z

    This paper outlines the development of a 500 kV DC oil-filled submarine cable capable of transmitting 2,800 MW with {+-} 500 kV 2800A bipole system. Polypropylene Laminated Paper (PPL) was employed as the insulation material, which is the worlds first application to DC cables. The conductor size is 3,000 mm{sup 2}, which is the largest size for submarine cables ever put into practical use. Through various fundamental and prototype tests, the cable proved to have excellent electrical characteristics for DC voltage as well as transient overvoltage. The cable and accessories are currently undergoing a long-term accelerated aging test as the final confirmation of their reliability and stability.

  19. EIS-0365: Imperial-Mexicali 230-kV Transmission Lines

    Broader source: Energy.gov [DOE]

    On February 27, 2001, Baja California Power, Inc. (hereafter referred to as Intergen), InterGen Aztec Energy, V.B.V., filed an application with DOE, Office of Fossil Energy, for a Presidential permit that would allow construction and connection of a double-circuit, 230-kV transmission line extending from the Imperial Valley Substation in California for a distance of about 6 mi (10 km) to a point west of Calexico at the U.S.-Mexico border.

  20. The varistor protected series capacitors at the 500 KV broadview substation

    SciTech Connect (OSTI)

    Barcus, J.M. (General Electric Co., Hudson Falls, NY (US)); Miske, S.A. Jr. (General Electric Co., Schenectady, NY (US)); Vitols, A.P. (General Electric Co., Pittsfield, MA (US)); Maynard, H.M. (Montana Power Co., Butte, MT (US)); Peterson, W.G. (Bonneville Power Admin., Portland, OR (US))

    1988-10-01T23:59:59.000Z

    Two 235 Mvar series capacitors have been successfully applied at the 500 kV Broadview substation of the Colstrip Transmission Project. The series capacitors have an overvoltage protection system based on metal oxide varistors. The system provides instantaneous bypass and reinsertion of the capacitors following external line section faults. The excellent performance of the equipment was demonstrated during staged fault tests performed in October, 1985. The banks have been in successful operation since January, 1986.

  1. Measurements on a FET based 1 MHz, 10 kV pulse generator

    SciTech Connect (OSTI)

    Wait, G.D.; Barnes, M.J.

    1995-08-01T23:59:59.000Z

    A prototype pulser, which incorporates thirty-two 1 kV Field-Effect Transistor (FET) modules, has been built and tested at TRIUMF. The pulser has been developed for application in a scheme for pulsed extraction from the TRIUMF 500 MeV cyclotron. Deflection of the beam will be provided by an electric field between a set of 1 in long deflector plates. The pulser generates a continuous, unipolar, pulse train at a fundamental frequency of approximately 1 MHz and a magnitude of 10 kV. The pulses have 38 ns rise and fall times and are stored on a low-loss coaxial cable which interconnects the pulse generator and the deflector plates. The circuit performance was evaluated with the aid of PSpice in the design stage and confirmed by measurements on the prototype. Temperature measurements have been performed on 1 kV FET modules under DC conditions and compared with temperatures under operating conditions to ensure that switching losses are acceptable. Results of various measurements are presented and compared with simulations.

  2. Commonwealth Edison 345kV L.P.P. splicing school

    SciTech Connect (OSTI)

    Johnsen, D.P. [ComEd, Chicago, IL (United States)

    1996-11-01T23:59:59.000Z

    The ComEd splicing school was held in January 1995 to train the work force for the installation of the first 345kV High Pressure Fluid Filled pipe type L.P.P. (Laminated Paper Polypropylene) insulated cable on the ComEd system. Construction is nearing completion on ComEd`s 345kV underground transmission line 17723 between Burnham TSS 177 and Taylor TSS 153 located just south of the Chicago Loop. Continued development and construction of the down-town Chicago Area and the south Loop has established the need for this line to reinforce the transmission network serving this critical area. 345kV transmission Line 17723 is a combination of overhead facility and HPFF (High Pressure Fluid Filled) pipe type L.P.P. cable with a summer normal rating of 900 MVA and a summer emergency rating of 1,200 MVA. This paper describes the training facility, innovative changes in tooling and the results of the training exercises.

  3. Cost comparison of 138 kV relay at TSS Natoma

    SciTech Connect (OSTI)

    Whetter, A.J. [ComEd, Chicago, IL (United States)

    1996-10-01T23:59:59.000Z

    This paper compares the costs of retro-fitting an electro-mechanical directional comparison blocking scheme with a microprocessor based dual directional comparison and under-reaching direct transfer tripping scheme on an existing panel at a 138 kV substation. Comparison is between the material, fabrication, engineering, drafting, construction, and testing costs. The cost per function of each scheme will be defined and compared. The results of this comparison will demonstrate the advantages of the new microprocessor based schemes in material costs, labor costs, and cost per function.

  4. Failure evaluation of underground high voltage cables (115 kV) in Mazatlan, Sinaloa: Microscopic method

    SciTech Connect (OSTI)

    Valero-Huerta, M.A.; Ramirez-Delgado, R. [Lab. de Pruebas de Equipos y Materiales, Irapuato (Mexico)

    1995-11-01T23:59:59.000Z

    The present paper is a complete analysis of the failure which occurred to the 115 kV power cable installed between the Mazatlan Centro and Mazatlan Norte Substations. Laboratory analysis that established the causes of the failure are included. It was concluded that the failure of the cable was provoked by the entrance of sewage water to the screen, and due to the presence of anaerobic organisms, resulted in the formation of sulfidic acid, which caused the severe corrosion that can be observed in the screen. The resulting loss of conductivity provoked heating capable of melting the isolator until its rupture.

  5. Operating characteristics and modeling of the LLNL 100-kV electric gun

    SciTech Connect (OSTI)

    Osher, J.E.; Barnes, G.; Chau, H.H.; Lee, R.S.; Lee, C.; Speer, R.; Weingart, R.C.

    1989-06-01T23:59:59.000Z

    In the electric gun, the explosion of an electrically heated metal foil and the accompanying magnetic forces drive a thin flyer plate up a short barrel. Flyer velocities of up to 18 km/s make the gun useful for hypervelocity impact studies. The authors briefly review the technological evolution of the exploding-metal circuit elements that power the gun, describe the 100-kV electric gun designed at Lawrence Livermore National Laboratory (LLNL) in some detail, and present the general principles of electric gun operation. They compare the experimental performance of the LLNL gun with a simple model and with predictions of a magnetohydrodynamics code.

  6. Sidney-North Yuma 230-kV Transmission Line Project, Colorado and Nebraska

    SciTech Connect (OSTI)

    Not Available

    1991-06-01T23:59:59.000Z

    This report describes the need for a 230-kV overhead transmission line to supply power from Sidney, Nebraska to eastern Colorado. The alternative scenario compared to construction of the line is No Action. Rejected alternatives include underground lines and different routing paths, with a possible extension to the Sterling area. Both scenarios are evaluated for environmental effects, cost, and consequences for the eastern Colorado region. The proposed route is determined to be the environmentally preferred choice. 120 refs., 6 figs., 13 tabs. (MHB)

  7. KvH Projekt GmbH Co KG | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand Jump to: navigation, searchOf Kilauea Volcano, Hawaii9969995°,I Jump to:Kumagai Gumi CoKuwaitKvH

  8. Commissioning and Operation of 130kV/130A Switched-Mode HV Power Supplies with the Upgraded JET Neutral Beam Injectors

    E-Print Network [OSTI]

    Commissioning and Operation of 130kV/130A Switched-Mode HV Power Supplies with the Upgraded JET Neutral Beam Injectors

  9. 1.9 kV AlGaN/GaN Lateral Schottky Barrier Diodes on Silicon

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Zhu, Mingda [University of Notre Dame, IN (United States); Song, Bo [Cornell University, Ithaca, NY (United States); Qi, Meng [University of Notre Dame, IN (United States); Hu, Zongyang [University of Notre Dame, IN (United States); Nomoto, Kazuki [University of Notre Dame, IN (United States); Yan, Xiaodong [University of Notre Dame, IN (United States); Cao, Yu [IQE, Westborough, MA (United States); Johnson, Wayne [IQE, Westborough, MA (United States); Kohn, Erhard [University of Notre Dame, IN (United States); Jena, Debdeep [Cornell University, Ithaca, NY (United States); Xing, Grace Huili [Cornell University, Ithaca, NY (United States)

    2015-04-01T23:59:59.000Z

    In this letter, we present AlGaN/GaN lateral Schottky barrier diodes on silicon with recessed anodes and dual field plates. A low specific on-resistance RON,SP (5.12 m?{center_dot}cm2), a low turn-on voltage (1.9 kV), were simultaneously achieved in devices with a 25 ?m anode/cathode separation, resulting in a power figure-of-merit (FOM) BV2/RON,SP of 727 MW{center_dot}cm2. The record high breakdown voltage of 1.9 kV is attributed to the dual field plate structure.

  10. El Paso Electric Company Diablo Substation to the US-Mexico border 115kV transmission line project. Final Environmental Assessment

    SciTech Connect (OSTI)

    Not Available

    1992-04-01T23:59:59.000Z

    This Environmental Assessment documents the analysis of alternative corridors for development and operation of a proposed 115 kilovolt transmission line using private lands and transporting power to the US-Mexico international border. The project will require (1) an amendment to El Paso Electric Company`s existing export authorization to transfer power across this border, and (2) a Presidential Permit for construction of the transmission line. The project would be located in Dona Ana county in southern New Mexico, approximately five miles west of El Paso, Texas. The alternative corridors, specific locations within those corridors, and structure types are identified and analyzed in the environmental studies.

  11. A New 500-kV Ion Source Test Stand for HIF

    SciTech Connect (OSTI)

    Sangster, T.C.; Ahle, L.E.; Halaxa, E.F.; Karpenko, V.P.; Oldaker, M. E.; Mitchell, J.W.; Beck, D.N.; Bieniosek, F.M.; Henestroza, E.; Kwan, J.W.

    2000-10-05T23:59:59.000Z

    One of the most challenging aspects of ion beam driven inertial fusion energy is the reliable and efficient generation of low emittance, high current ion beams. The primary ion source requirements include a rise time of order 1-msec, a pulse width of at least 20-msec, a flattop ripple of less than 0.1% and a repetition rate of at least 5-Hz. Naturally, at such a repetition rate, the duty cycle of the source must be greater than 108 pulses. Although these specifications do not appear to exceed the state-of-the-art for pulsed power, considerable effort remains to develop a suitable high current ion source. Therefore, we are constructing a 500-kV test stand specifically for studying various ion source concepts including surface, plasma and metal vapor arc. This paper will describe the test stand design specifications as well as the details of the various subsystems and components.

  12. Malcolm, N. and Aggarwal, R.k. (2014) An Analysis of Reducing Back Flashover Faults with Surge Arresters on 69/138 kV Double

    E-Print Network [OSTI]

    McCusker, Guy

    Arresters on 69/138 kV Double Circuit Transmission Lines Due to Direct Lightning Strikes on the Shield Wires-EMTP, Back flashover faults, Lightning strokes, Surge arrester, Transmission lines. Abstract Back flashover causes of power interruptions on the double-circuit 69/138 kV overhead transmission lines in Jamaica

  13. A Simple Measurement Technique for Characterizing Active Antennas

    E-Print Network [OSTI]

    York, Robert A.

    -in amplifiers are then used to sample the mixer IF outputs, and should record only the modulated signal arriving = VDC f kvA cos@a +kVB cos@b (1) v,fl= VDC f kVA cos@a where IC is the proportionality constant between

  14. EIS-0505: Vantage to Pomona Heights 230 kV Transmission Line Project, Yakima, Grant, Benton and Kittitas Counties, Washington

    Broader source: Energy.gov [DOE]

    The Bureau of Land Management is preparing, with DOE’s Bonneville Power Administration (BPA) as a cooperating agency, an EIS that evaluates the potential environmental impacts of a proposal to construct a 60- to 67-mile long 230-kV transmission line. BPA’s proposed action is to interconnect the transmission line to an existing BPA substation.

  15. A novel voltage-gated potassium ion channel gene (Kv5.1): Molecular cloning and characterization

    SciTech Connect (OSTI)

    Beisel, K.W.; Lofton, N.C.; Kelley, P.M. Jr. [Boys Town National Research Hospital, Omaha, NE (United States)] [and others

    1994-09-01T23:59:59.000Z

    Voltage-activated potassium channels comprise a family of genes which play a role in the electrophysiological properties of neurosensory and neuronal tissue. We have recently identified a novel voltage-gated potassium ion channel (designated as Kv5.1) using the both RT-PCR with degenerative oligodeoxynucleotide primers and dideoxy sequence analyses. A full length sequence of the mature transcript was obtained by mRNA walking using gene-specific oligodeoxynucleotide primers. The deduced amino acid sequence suggested that this protein has six hydrophobic membrane spanning regions (S1-S6) and an ion-selective pore (P or H5) located between S5 and S6. This structural motif is found in other members of this gene family. Kv5.1 has an amino acid sequence homology of 55% with the Shab gene, Kv2.1, within the N-terminus and the membrane spanning regions. No sequence homology was found for the C-terminus. Northern analysis using mRNA isolated from a panel of rat tissues demonstrated that a 2.4 kb message was expressed in heart and cochlear tissue. Because of the low sequence homology and the unique tissue distribution, we have tentatively assigned the Kv5.1 gene as a new subfamily. Both the rat and human homologues were sequenced and the nucleotide and amino acid homologies were 88% and 96%, respectively. In the rat, the open reading frame encodes a 540-amino acid protein with a predicted molecular mass of 61,781 daltons. Interestingly, the human homologue is truncated by 83 residues in the C-terminus by a stop codon. We have recently isolated a human genomic {lambda} clone which contains the entire human gene and are now determining chromosomal location of Kv5.1 by in situ hybridization and PCR analysis of DNA from a panel of somatic cell hybrids.

  16. Data:F7b8506d-5d3e-4ce0-abc9-a4a383eda56e | Open Energy Information

    Open Energy Info (EERE)

    than 1000 kVA connected transformer capacity, delivered from the 12.57.2 or 24.914.4 kV distribution system. Power Factor Charge A power factor charge will be assessed to...

  17. Data:D910241b-216d-4f54-988b-4a2c5087218a | Open Energy Information

    Open Energy Info (EERE)

    Utility name: Lincoln Electric System Effective date: End date if known: Rate name: Cogeneration 35kV Backup Sector: Description: Excess kVA Source or reference: http:...

  18. Low stored energy 100 kV regulator for ion sources at LANSCE

    SciTech Connect (OSTI)

    Jacobson, E.G.; Haffner, R.L.; Ingalls, W.B.; Meyer, B.J.; Stelzer, J.E.

    1998-12-31T23:59:59.000Z

    To minimize accelerating column damage caused by uncontrolled energy release during arc-downs, it is desirable to minimize the available stored electrical energy. For the Los Alamos Neutron Science Center (LANSCE) H{sup {minus}} ion sources, the stored energy includes, in addition to the charge in the power supply output capacitance, the charge on the electronics racks. They are supported and insulated from ground by PVC pipe and have a capacitance to ground of approximately 900 pf. In 1988 (LANSCE) personnel designed a high-voltage current source using a low-stored-energy power supply and planar triode with the goal of eliminating uncontrolled release of charge stored in the power supply. Construction and testing were performed intermittently as resources permitted until 1993. When work on the Short Pulse Spallation Source (SPSS) started on the LANSCE Ion Source Test Stand (ISTS) it was recognized that a higher current power supply would be needed and work resumed on the regulator circuitry. A 120 kV power supply having low output capacitance, and a planar triode have been used to supply 40 mA, 120 Hz, 12% duty-factor current for the ISTS beam. The triode`s cathode current is controlled by circuitry operating both at power-supply voltage level and at ground level via a fiber optic link. Voltage droop is approximately 600 V during the 1 ms beam pulse. The authors present the status of the regulator and its special challenges.

  19. Performance characteristics of the Atlas 60 kV, 60 kJ plastic capacitors

    SciTech Connect (OSTI)

    Reass, W.; Bennet, G.; Bowman, D.; Lopez, E.; Monroe, M.; Parsons, W.

    1997-12-01T23:59:59.000Z

    This paper provides the performance data of Atlas plastic capacitors as supplied by Maxwell Technologies and Aerovox Corporation. The fiberglass cases at 13 inches high by 29 inches wide and 28 inches in depth with a 2 inch by 18 inch bushing on each end. Two styles of the 33.5uF capacitors have been evaluated for Atlas use, a conventional paper-foil and a self-healing metalized-paper and plastic dielectric design. A test program to capacitor failure, is being used to evaluate capacitor lifetime at full voltage (60 kV) and a nominal 15% reversal. With the Atlas parameters, peak currents of {approximately} 340 kA are realized. In anticipation of faults, capacitors are capable, specified, and tested for 700 kA performance. Accurate methods are also utilized to determine capacitor inductance, less than 20 nH. The results of the various capacitor testing programs will be presented in addition to future directives for their R and D efforts.

  20. The 345 kV underground/underwater Long Island Sound cable project

    SciTech Connect (OSTI)

    Grzan, J.; Hahn, E.I. (New York Power Authority, White Plains, NY (United States)); Casalaina, R.V.; Kansog, J.O.C. (Ebasco Services Inc., Lyndhurst, NJ (United States))

    1993-07-01T23:59:59.000Z

    A high voltage underground/underwater cable system was installed to increase the transmission capacity from the mainland of New York to Long Island. In terms of weight and diameter, the self-contained, fluid-filled (SCFF) cable used for the underwater portion of the project is the largest underwater cable in the world. The use of high-pressure, fluid-filled (HPFF) pipe-type cable on the land portion represents the largest application of paper-polypropylene-paper (PPP) insulated cable in the United States. State-of-the-art technologies were implemented in the use of fiber optic cables for relay protection and SCADA/RTU, temperature monitoring and leak detection systems, SF[sub 6] gas-insulated substations, and underwater cable laying and embedment techniques. This paper discusses the design and installation of a 750 MVA, 43 km (26.6 mi), 345 kV underground/underwater electric transmission system installed by the New York Power Authority (NYPA).

  1. Development and laboratory testing of a 138-kV PPP-insulated joint for commercial application

    SciTech Connect (OSTI)

    Walldorf, S.P. (MAC Products, Inc., Kearny, NJ (US)); Chu, H.; Elbadaly, H. (Consolidated Edison Co. of New York, Inc., New York, NY (USA))

    1990-04-01T23:59:59.000Z

    This paper describes the design, development and laboratory testing of a high voltage PPP (paper polypropylene/paper laminate) insulated joint for commercial application on 138-kV PPP-insulated cable. The design approach taken is conservative and addresses the typical variations in field conditions and in skill and workmanship of the splicing. Joint construction details, including choice of connector, taping structure, and joint mechanical reinforcement, are discussed. The test criteria are described and results are presented.

  2. EA-1679: Grand Coulee's Third Powerplant 500-kV Transmission Line Replacement Project, Grant and Okanogon Counties, Washington

    Broader source: Energy.gov [DOE]

    This EA evaluates potential environmental impacts from the construction and operation of six new 500-kV overhead transmission lines to replace six existing underground lines at Grand Coulee Dam. DOE’s Bonneville Power Administration (BPA), a cooperating agency, was asked by the U. S. Department of the Interior’s Bureau of Reclamation to design and construct the proposed new transmission lines. A Finding of No Significant Impact was issued by BPA in December 2011.

  3. EIS-0025: Miles City-New Underwood 230-kV Electrical Transmission Line, Montana, North Dakota, and South Dakota

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy’s Western Area Power Administration prepared this statement to assess the environmental and socioeconomic implications of its proposed action to construct a 3.28-mile, 230-kV transmission line between Miles City and Baker, Montana , Hettinger, North Dakota , and New Underwood , South Dakota , in Custer and Fallon Counties in Montana, Adams , Bowman , and Slope Counties in North Dakota and Meade, Pennington, and Perkins Counties in South Dakota.

  4. Heavy duty insulator assemblies for 500-kV bulk power transmission line with large diameter octagonalbundled conductor

    SciTech Connect (OSTI)

    Tsujimoto, K.; Hayase, I.; Hirai, J.; Inove, M.; Naito, K.; Yukino, T.

    1982-11-01T23:59:59.000Z

    This paper describes the design procedure and the results of field tests on mechanical performances of insulator assemblies newly developed to support octagonal-bundled conductors for 500-kV bulk power transmission. Taking account of conductor-motion-induced peak tensile load, fatigue, torsional torque and others, a successful design has been achieved in two prototype assemblies for such heavy mechanical duties as encountered during conductor galloping or swing. This has been proved throughout three years of the field tests.

  5. Development and practical operation of perfluorocarbon immersed 275kV transformers with compressed SF6 gas insulation

    SciTech Connect (OSTI)

    Hiraishi, K.; Uwano, Y.; Shirakura, K.; Gotanda, Y.; Endoo, K. [Hitachi Ltd. (Japan)] [Hitachi Ltd. (Japan); Higaki, M. [Kyushu Kyoritu Univ., Kitakyushu (Japan)] [Kyushu Kyoritu Univ., Kitakyushu (Japan); Horikoshi, M.; Mizuno, K.; Hora, H. [Chubu Electric Power Co., Inc., Nagoya (Japan)] [Chubu Electric Power Co., Inc., Nagoya (Japan)

    1995-04-01T23:59:59.000Z

    A perfluorocarbon (PFC) immersed 275kV transformer with compressed SF6 gas insulation has been under development. This paper clarified the AC partial discharge inception voltage and time characteristics of PFC immersed insulation and also clarified that a prototype 275kV 100MVA three phase transformer could be worked without any trouble during the long-term over voltage test. This prototype proved that it had the AC partial discharge inception strength of higher than 1.5 times of the AC test voltage and the lightning impulse breakdown strength of 1.5 times of the test voltage. A 275kV 250MVA three phase transformer was developed and practically operated at the outdoor substation of Chubu Electric Power Co., Inc. This transformer has been successfully operated until now and the detailed internal inspection of the transformer was carried out after one year and 9 months of the successful practical operation and no significant abnormal condition was recognized.

  6. EIS-0323-S1: Sacramento Area Voltage Support Project Supplemental Environmental Impact Statement and Environmental Impact Report, Placer, Sacramento, and Sutter Counties, California

    Broader source: Energy.gov [DOE]

    Construction and operation has been proposed of approximately 31 to 38 miles of new, double-circuit, 230-kilovolt (kV) transmission line between Western's O'Banion Substation and the area just south of SMUD's Elverta Substation and the reconstruciton of SMUD's existing 230-kV/115kV transmission line between SMUD's Elverta and Natomas substations.

  7. EIS-0436: I-5 Corridor Reinforcement Project; Multnomah County, Oregon, and Cowlitz and Clark Counties, Washington

    Broader source: Energy.gov [DOE]

    DOE’s Bonneville Power Administration (BPA) is preparing an EIS that will evaluate the potential environmental impacts of a BPA proposal to build a 500-kilovolt (kV) lattice-steel-tower transmission line that would run from a new 500-kV substation near Castle Rock, Washington, to a new 500-kV substation near Troutdale, Oregon.

  8. PADHDR Reroute

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    the existing Parker Dam-Headgate Rock and Parker Dam-Bouse 161-kilovolt (kV) transmission lines along the Colorado River in western Arizona and eastern California due to the...

  9. CX-003611: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    Exclusion Determination Schultz - Raver Number 3 and 4 500-kilovolt (kV) Transmission Lines Spacer Replacement CX(s) Applied: B1.3 Date: 08252010 Location(s): King...

  10. EIS-0421: Big Eddy-Knight Transmission Line

    Broader source: Energy.gov [DOE]

    BPA is proposing to build a new 500 kilovolt (kV) transmission line in Wasco County, Oregon and Klickitat County, Washington and a new substation in Klickitat County. The new BPA transmission line...

  11. CX-003624: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    Replacement of twenty 22-L structures on the Satsop-Aberdeen Number 2 230-kilovolt (kV) transmission line. The project work would involve removal of the existing towers and...

  12. CX-010686: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Cheyenne Substation KV2A 115-kilovolt Tie Line Installation CX(s) Applied: B4.6 Date: 07/02/2013 Location(s): Wyoming Offices(s): Western Area Power Administration-Rocky Mountain Region

  13. EA-1791: Final Environmental Assessment | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    to design, permit, construct, and operate a 2.5-Megawatt (MW) Clipper Liberty wind turbine and an associated 34.5-kilovolt (kV) low-voltage transmission line at the...

  14. EIS-0231: Navajo Transmission Project

    Broader source: Energy.gov [DOE]

    This EIS evaluates the environmental impacts of a proposal to by Dine Power Authority, a Navajo Nation enterprise, to construct, operate, and maintain a 500 kilovolt (kV) transmission line planned...

  15. EIS-0005-FS: Bonneville Power Administration Proposed FY 1979 Program, Facility Location on Supplement, Southwest Oregon Area Service, Buckley-Summer Lake 500 kV Line, Supplemental

    Broader source: Energy.gov [DOE]

    This Bonneville Power Administration document assesses the environmental impacts of constructing transmission facilities, which will coordinate with the Midpoint-Malin 500-kV line to be constructed by the Pacific Power and Light (PP&L) Company. The proposed action includes the construction of the 1.56-mile Buckley-Summer Lake 500-kV transmission line; the proposed Buckley Substation near Maupin, Oregon; and the proposed Summer Lake Substation near Silver Lake, Oregon.

  16. Solid-State Fault Current Limiter Development : Design and Testing Update of a 15kV SSCL Power Stack

    SciTech Connect (OSTI)

    Dr. Ram Adapa; Mr. Dante Piccone

    2012-04-30T23:59:59.000Z

    ABSTRACT The Solid-State Fault Current Limiter (SSCL) is a promising technology that can be applied to utility power delivery systems to address the problem of increasing fault currents associated with load growth. As demand continues to grow, more power is added to utility system either by increasing generator capacity or by adding distributed generators, resulting in higher available fault currents, often beyond the capabilities of the present infrastructure. The SSCL is power-electronics based equipment designed to work with the present utility system to address this problem. The SSCL monitors the line current and dynamically inserts additional impedance into the line in the event of a fault being detected. The SSCL is based on a modular design and can be configured for 5kV through 69kV systems at nominal current ratings of 1000A to 4000A. Results and Findings This report provides the final test results on the development of 15kV class SSCL single phase power stack. The scope of work included the design of the modular standard building block sub-assemblies, the design and manufacture of the power stack and the testing of the power stack for the key functional tests of continuous current capability and fault current limiting action. Challenges and Objectives Solid-State Current Limiter technology impacts a wide spectrum of utility engineering and operating personnel. It addresses the problems associated with load growth both at Transmission and Distribution class networks. The design concept is pioneering in terms of developing the most efficient and compact power electronics equipment for utility use. The initial test results of the standard building blocks are promising. The independent laboratory tests of the power stack are promising. However the complete 3 phase system needs rigorous testing for performance and reliability. Applications, Values, and Use The SSCL is an intelligent power-electronics device which is modular in design and can provide current limiting or current interrupting capabilities. It can be applied to variety of applications from distribution class to transmission class power delivery grids and networks. It can also be applied to single major commercial and industrial loads and distributed generator supplies. The active switching of devices can be further utilized for protection of substation transformers. The stress on the system can be reduced substantially improving the life of the power system. It minimizes the voltage sag by speedy elimination of heavy fault currents and promises to be an important element of the utility power system. DOE Perspective This development effort is now focused on a 15kV system. This project will help mitigate the challenges of increasing available fault current. DOE has made a major contribution in providing a cost effective SSCL designed to integrate seamlessly into the Transmission and Distribution networks of today and the future. Approach SSCL development program for a 69kV SSCL was initiated which included the use of the Super GTO advanced semiconductor device which won the 2007 R&D100 Award. In the beginning, steps were identified to accomplish the economically viable design of a 69kV class Solid State Current Limiter that is extremely reliable, cost effective, and compact enough to be applied in urban transmission. The prime thrust in design and development was to encompass the 1000A and the 3000A ratings and provide a modular design to cover the wide range of applications. The focus of the project was then shifted to a 15kV class SSCL. The specifications for the 15kV power stack are reviewed. The design changes integrated into the 15kV power stack are discussed. In this Technical Update the complete project is summarized followed by a detailed test report. The power stack independent high voltage laboratory test requirements and results are presented. Keywords Solid State Current Limiter, SSCL, Fault Current Limiter, Fault Current Controller, Power electronics controller, Intelligent power-electronics Device, IED

  17. OPERATIONAL RESULTS OF THE SPALLATION NEUTRON SOURCE (SNS) POLYPHASE CONVERTER-MODULATOR FOR THE 140 KV KLYSTRON RF SYSTEMS

    SciTech Connect (OSTI)

    W.A. REASS; J.D. DOSS; ET AL

    2001-06-01T23:59:59.000Z

    This paper describes the first operational results of the 140 kV, 1 MW average, 11 MW peak, zero-voltage-switching, 20 kHz polyphase bridge, boost converter-modulator for klystron pulse application. The DC-DC converter derives the buss voltages from a standard 13.8 kV to 2100 Y substation cast-core transformer. Energy storage and filtering is provided by self-clearing metallized hazy polypropylene traction capacitors. Three ''H-Bridge'' Insulated Gate Bipolar Transistor (IGBT) switching networks are used to generate the polyphase 20 kHz transformer primary drive waveforms. The 20 kHz drive waveforms are chirped the appropriate duration to generate the desired klystron pulse width. Pulse-Width Modulation (PWM) of the individual 20 kHz pulses is utilized to provide regulated output waveforms with adaptive feedforward and feedback techniques. The boost transformer design utilizes amorphous nanocrystalline material that provides the required low core loss at design flux levels and switching frequencies. Resonant shunt peaking is used on the transformer secondary to boost output voltage and resonate transformer leakage inductance. With the appropriate transformer leakage inductance and peaking capacitance, zero-voltage-switching of the IGBT's is attained, minimizing switching losses. Reviews of these design parameters and an examination of the first operational results will be performed.

  18. Operational results of the spallation neutron source (SNS) polyphase converter-modulator for the 140 KV klystron RF system

    SciTech Connect (OSTI)

    Reass, W. A. (William A.); Doss, James D.; Gribble, R. F. (Robert F.); Lynch, M. T. (Michael T.); Rees, D. E. (Daniel E.); Tallerico, P. J. (Paul J.); Borovina, D. L.

    2001-01-01T23:59:59.000Z

    This paper describes the first operational results of the 140 kV, 1 MW average, 11 MW peak, zero-voltageswitching, 20 kHz polyphase bridge, boost converter-modulator for klystron pulse application. The DC-DC converter derives the buss voltages from a standard 13.8 kV to 2100 Y substation cast-core transformer. Energy storage and filtering is provided by self-clearing metallized hazy polypropylene traction capacitors. Three 'H-Bridge' Insulated Gate Bipolar Transistor (IGBT) switching networks are used to generate the polyphase 20 kHz transformer primary drive waveforms. The 20 kHz drive waveforms are chirped the appropriate duration to generate the desired klystron pulse width. Pulse-Width Modulation (PWM) of the individual 20 kHz pulses is utilized to provide regulated output waveforms with adaptive feedforward and feedback techniques. The boost transformer design utilizes amorphous nanocrystalline material that provides the required low core loss at design flux levels and switching frequencies. Resonant shunt peaking is used on the transformer secondary to boost output voltage and resonate transformer leakage inductance. With the appropriate transformer leakage inductance and peaking capacitance, zero-voltage-switching of the IGBT's is attained, minimizing switching losses. Reviews of these design parameters and an examination of the first operational results will be performed.

  19. Development of 500-kV AC cable employing laminar insulation of other than conventional cellulosic paper. Final report

    SciTech Connect (OSTI)

    Bahder, G.; Eager, G.S. Jr.; Walker, J.J.; Dima, A.F.

    1980-09-01T23:59:59.000Z

    The results of an investigation to develop a 500 kV ac laminar dielectric power cable and joint having insulation with lower losses than conventional cellulosic paper insulation are presented. Background information is presented on proposed low-loss synthetic and composite synthetic/cellulosic paper insulations. From these studies, fibrous polypropylene paper tape and cellulosic paper-polypropylene film-cellulosic paper composite paper (PPP) were chosen. Extensive testing of hand-wrapped cable models fabricated with each type of tape served to eliminate the fibrous polypropylene paper tape from further consideration. Cable model tests indicate that the PPP tape is satisfactory for insulation in 500 kV ac cable, and that oil impregnants now used in conventional cellulosic paper insulated cables are unsuitable, but that silicone oil with an additive is satisfactory for PPP tapes. Laboratory data indicate that it may be necessary with the PPP tapes to use a significantly lower viscosity impregnating oil which has a greater tendency to drain from pipe-type cables than conventional oil. This may require a modification of the moisture seal. Four final pipe-type cables having a conventional moisture seal were manufactured for possible future field testing. The dielectric loss of the final cables is one-fifth that of conventional cellulosic paper insulated cables. The estimated installed cost per MVA-mile of the PPP insulated cable, neglecting losses, is higher than cellulosic insulated cables impregnated with conventional mineral oil. However, the capacitance of the cable insulated with PPP tape is 25% lower than conventional cable, and therefore, the reactance necessary to compensate for the cable charging current is significantly reduced.

  20. Type A Accident Investigation Report on the June 25, 1997, Contractor Inspector Fatality on the Satsop-Aberdeen #2 & #3 230 kV Line

    Broader source: Energy.gov [DOE]

    On June 27, 1997, I established a Type-A Accident Investigation Board to investigate the June 25, 1997 fatal contractor accident which occurred on BPA?s Satsop-Aberdeen #2 and #3 230-kV transmission lines right-of-way.

  1. Increasing the reliability of the shutdown of 500 - 750-kV overhead lines equipped with shunt reactors in an unsuccessful three-phase automatic repeated closure cycle

    SciTech Connect (OSTI)

    Kuz'micheva, K. I.; Merzlyakov, A. S.; Fokin, G. G. [JSC 'R and D Center at Federal Grid Company of the United Power System' (Russian Federation)

    2013-05-15T23:59:59.000Z

    The reasons for circuit-breaker failures during repeated disconnection of 500 - 750 kV overhead lines with shunt reactors in a cycle of unsuccessful three-phase automatic reconnection (TARC) are analyzed. Recommendations are made for increasing the operating reliability of power transmission lines with shunt reactors when there is unsuccessful reconnection.

  2. U.S. Department of Energy Categorical Exclusion ...

    Broader source: Energy.gov (indexed) [DOE]

    bank consisting of (3) three - 13.8kV-208Y120, 1-Phase, 50 kVA pole mounted transformers to provide such power. A new pole will be placed in line with the existing 13.8kV...

  3. CX-007736: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Rutgers University - First in Class Demonstration of Completely New type of SiC Bipolar Switch (15 kilovolt (kV)-20kV) for Utility Scale Inverters CX(s) Applied: A9, B3.6 Date: 12/08/2011 Location(s): New Jersey Offices(s): Advanced Research Projects Agency-Energy

  4. Development of a 33 kV, 20 A long pulse converter modulator for high average power klystron

    SciTech Connect (OSTI)

    Reghu, T.; Mandloi, V.; Shrivastava, Purushottam [Pulsed High Power Microwave Section, Raja Ramanna Centre for Advanced Technology, Indore 452013, M.P. (India)] [Pulsed High Power Microwave Section, Raja Ramanna Centre for Advanced Technology, Indore 452013, M.P. (India)

    2014-05-15T23:59:59.000Z

    Research, design, and development of high average power, long pulse modulators for the proposed Indian Spallation Neutron Source are underway at Raja Ramanna Centre for Advanced Technology. With this objective, a prototype of long pulse modulator capable of delivering 33 kV, 20 A at 5 Hz repetition rate has been designed and developed. Three Insulated Gate Bipolar Transistors (IGBT) based switching modules driving high frequency, high voltage transformers have been used to generate high voltage output. The IGBT based switching modules are shifted in phase by 120° with respect to each other. The switching frequency is 25 kHz. Pulses of 1.6 ms pulse width, 80 ?s rise time, and 70 ?s fall time have been achieved at the modulator output. A droop of ±0.6% is achieved using a simple segmented digital droop correction technique. The total fault energy transferred to the load during fault has been measured by conducting wire burn tests and is found to be within 3.5 J.

  5. Seasonal Patterns of Melatonin, Cortisol, and Progesterone Secretion in Female Lambs Raised Beneath a 500-kV Transmission Line.

    SciTech Connect (OSTI)

    Lee, Jack M.

    1992-06-01T23:59:59.000Z

    Although several kinds of biological effects of electric and magnetic fields have been reported from laboratory studies, few have been independently replicated. When this study was being planned, the suppression of nighttime melatonin in rodents was thought to represent one of the strongest known effects of these fields. The effect had been replicated by a single laboratory for 60-Hz electric fields, and by multiple laboratories for d-c magnetic fields. The primary objective of this study was to determine whether the effect of electric and magnetic fields on melatonin would also occur in sheep exposed to a high voltage transmission line. The specific hypothesis tested by this experiment was as follows: The electrical environment produced by a 60-Hz, 500-kV transmission line causes a depression in nocturnal melatonin in chronically exposed female lambs. This may mimic effects of pinealectomy or constant long-day photoperiods, thus delaying the onset of reproductive cycles. Results of the study do not provide evidence to support the hypothesis. Melatonin concentrations in the sheep exposed to the transmission line showed the normal pattern of low daytime and high nighttime serum levels. As compared to the control group, there were no statistically significant group differences in the mean amplitude, phase, or duration of the nighttime melatonin elevation.

  6. Development of 230-kV high-pressure, gas-filled, pipe-type cable system: Model test program phase

    SciTech Connect (OSTI)

    Silver, D.A. (Pirelli Cable Corp., Florham Park, NJ (USA))

    1990-09-01T23:59:59.000Z

    The objective of this project was the development of a 230 kV high-pressure gas-filled (HPGF) pipe-type cable employing paper or laminate of paper-polypropylene-paper (PPP) insulation pressurized with N{sub 2} gas or a blend of 15% SF{sub 6}/85% N{sub 2} gas. Heretofore, HPGF pipe-type cables have been restricted to 138 kV ratings due to technical difficulties in achieving higher voltage ratings. In view of the high cost of manufacturing and testing a large number of full size cables, cable models with 2 mm (80 mils) and 2.5 mm (100 mils) wall thicknesses of insulation enclosed in a test fixture capable of withstanding a test pressure of 2070 kPa (300 psig) and high electrical stresses were employed for dissipation factor versus voltage measurements and for ac and impulse breakdown tests at rated and emergency operating temperatures. In addition, a 36 cm (14 in) full wall cable model enclosed in a pressure vessel was utilized for transient pressure response tests. The results of this investigation attest tot he technical feasibility of the design and manufacture of a 230 kV HPGF pipe-type cable employing paper or PPP insulation pressurized with 100% N{sub 2} gas or a blend of 15% SF{sub 6}/85% N{sub 2} gas for operation under normal and 100 hour emergency conditions at conductor temperatures of 85{degree} and 105{degree}C, respectively. The manufacture of a full size PPP insulated cable pressurized with a blend of 15% SF{sub 6}/85% N{sub 2} gas employing pre-impregnated PPP insulating tapes and an annular conductor based on the design stresses defined in this report is recommended for laboratory evaluation and extended life tests. 11 refs., 45 figs., 11 tabs.

  7. Image-Guided Radiotherapy (IGRT) for Prostate Cancer Comparing kV Imaging of Fiducial Markers With Cone Beam Computed Tomography (CBCT)

    SciTech Connect (OSTI)

    Barney, Brandon M., E-mail: barney.brandon@mayo.ed [Department of Radiation Oncology, Mayo Clinic, Rochester, MN (United States); Lee, R. Jeffrey [Department of Radiation Oncology, Intermountain Medical Center, Salt Lake City, UT (United States); Handrahan, Diana [Department of Statistics, Intermountain Medical Center, Salt Lake City, UT (United States); Welsh, Keith T.; Cook, J. Taylor; Sause, William T. [Department of Radiation Oncology, Intermountain Medical Center, Salt Lake City, UT (United States)

    2011-05-01T23:59:59.000Z

    Purpose: To present our single-institution experience with image-guided radiotherapy comparing fiducial markers and cone-beam computed tomography (CBCT) for daily localization of prostate cancer. Methods and Materials: From April 2007 to October 2008, 36 patients with prostate cancer received intensity-modulated radiotherapy with daily localization by use of implanted fiducials. Orthogonal kilovoltage (kV) portal imaging preceded all 1244 treatments. Cone-beam computed tomography images were also obtained before 286 treatments (23%). Shifts in the anterior-posterior (AP), superior-inferior (SI), and left-right (LR) dimensions were made from kV fiducial imaging. Cone-beam computed tomography shifts based on soft tissues were recorded. Shifts were compared by use of Bland-Altman limits of agreement. Mean and standard deviation of absolute differences were also compared. A difference of 5 mm or less was acceptable. Subsets including start date, body mass index, and prostate size were analyzed. Results: Of 286 treatments, 81 (28%) resulted in a greater than 5.0-mm difference in one or more dimensions. Mean differences in the AP, SI, and LR dimensions were 3.4 {+-} 2.6 mm, 3.1 {+-} 2.7 mm, and 1.3 {+-} 1.6 mm, respectively. Most deviations occurred in the posterior (fiducials, 78%; CBCT, 59%), superior (79%, 61%), and left (57%, 63%) directions. Bland-Altman 95% confidence intervals were -4.0 to 9.3 mm for AP, -9.0 to 5.3 mm for SI, and -4.1 to 3.9 mm for LR. The percentages of shift agreements within {+-}5 mm were 72.4% for AP, 72.7% for SI, and 97.2% for LR. Correlation between imaging techniques was not altered by time, body mass index, or prostate size. Conclusions: Cone-beam computed tomography and kV fiducial imaging are similar; however, more than one-fourth of CBCT and kV shifts differed enough to affect target coverage. This was even more pronounced with smaller margins (3 mm). Fiducial imaging requires less daily physician input, is less time-consuming, and is our preferred method for prostate image-guided radiotherapy.

  8. Development of NS-TACSR with extremely suppressed aeolian noise and its application to 500 kV overhead transmission lines

    SciTech Connect (OSTI)

    Tsujimoto, K.; Furukawa, S. (Kansai Electric Power Co., Inc., Osaka (Japan)); Shimojima, K.; Yamamoto, K. (Hitachi Cable, Ltd., Hitachi (JP))

    1991-10-01T23:59:59.000Z

    Recently in Japan, with the unprecedented advance of residential area development in the suburbs of large cities, it has become quite difficult to secure the routes of EHV transmission lines from nuclear power plants in remote places to the suburbs of large cities, urging resolution of environmental problems related to transmission lines. In Japan, aerodynamic sound produced by conductors and insulators frequently caused noise problems. Having an opportunity of constructing a 500 kV transmission line through a residential are, we made a research to resolve this noise problem. This paper describes the characteristics of aeolian noise and preventive measures against it.

  9. Case Study of the Failure of two 13.8kV Control & Metering Transformers that caused significant Equipment Damage

    SciTech Connect (OSTI)

    Dreifuerst, G R; Chew, D B; Mangonon, H L; Swyers, P W

    2011-08-25T23:59:59.000Z

    The degradation and failure of cast-coil epoxy windings within 13.8kV control power transformers and metering potential transformers has been shown to be dangerous to both equipment and personnel, even though best industrial design practices were followed. Accident scenes will be examined for two events at a U.S. Department of Energy laboratory. Failure modes will be explained and current design practices discussed with changes suggested to prevent a recurrence and to minimize future risk. New maintenance philosophies utilizing partial discharge testing of the transformers as a prediction of end-of-life will be examined.

  10. Proposed amendment to presidential permit PP-63 and associated modifications to 500 kV international transmission line, Forbes, Minnesota to Manitoba, Canada. [Forbes Substation

    SciTech Connect (OSTI)

    Not Available

    1992-10-01T23:59:59.000Z

    This Addendum to the Final Environmental Assessment for the Proposed Amendment to Presidential Permit PP-63 and Associated Modifications to 500 kV International Transmission Line: Forbes, Minnesota to Manitoba, Canada (DOE/EA-587) addresses Northern States Power Company's (NSP) proposed expansion of the Forbes Substation. The applicant has requested that the expansion take place on the west side of the substation, within the existing property line, instead of on the north side as originally proposed. All of the proposed construction would take place on property already owned by NSP. DOE has reviewed the environmental impacts associated with this minor modification and has determined that the conclusions reached in the environmental assessment and Finding of No Significant Impact prepared in connection with NSP's original amendment request remain valid.

  11. ccsd00001869, Multi-ion-species e ects on magnetosonic waves and energy

    E-Print Network [OSTI]

    , besides ! ' kvA mode, numerous waves are present near many di#11;erent ion cyclotron frequencies disturbance is investigated. In a multi-ion-species plasma, this disturbance is damped. The energy in a collisionless plasma [11], where i is the ion cyclotron frequency and n is the integer. In a single

  12. Proposed amendment for Presidential Permit PP-63 and associated modifications to 500 kV international transmission line, Forbes, Minnesota to Manitoba, Canada Northern States Power Company. Final Environmental Assessment

    SciTech Connect (OSTI)

    Not Available

    1992-02-01T23:59:59.000Z

    Northern States Power Company, (NSP), a Minnesota investor owned utility has applied to the Office of Fossil Energy, United States Department of Energy, to amend Presidential Permit PP-63 to allow for alterations to the 500 kV transmission line and as sedated facilities currently regulated by this permit. The alterations proposed for the 500 kV line owned by NSP are part of a long term effort sponsored by NSP to upgrade the existing NSP transmission system to allow for increased exchange of electricity with the Manitoba Hydro-Electric Board. Presidential Permit PP-63 authorized NSP to construct, connect, operate and maintain a 500 kV line at the United States/Canadian border approximately seven-and-a-half miles west of Warroad in Roseau County, Minnesota. This line connects with a 500 kV line owned and operated by the Manitoba Hydro-Electric Board (MHEB), which extends from Dorsey, Manitoba, Canada to the United States/Canadian border. NSP proposes to increase the electricity transfer capability of this transmission facility by constructing a new 80-acre substation on the existing 500 kV line in Roseau County, Minnesota, and upgrading the existing substation at Forbes, Minnesota. The proposed Roseau substation would contain two 41.5 ohm series capacitor banks. In addition, static VAR compensators are to be installed at the existing Forbes Substation. Approximately 5 acres would be added to the 30-acre Forbes site to house the additional equipment. No new lines would enter or exit the facility. NSP proposes to place the new Roseau Substation in service in May 1993 and to complete the upgrading of the Forbes Substation in March 1994. The primary, initial purpose of these modifications is to enable NSP to import 400 megawatts of electric power from MHEB during the summer months to meet peak electrical demand in the Minneapolis-St. Paul area. It is expected that this power transfer would begin in 1993.

  13. EA-1671: Big River Substation to Poston Substation 69-Kilovolt Transmission Line Project, Arizona and California

    Broader source: Energy.gov [DOE]

    The Department of the Interior’s Bureau of Indian Affairs considered preparing this EA, with DOE’s Western Area Power Administration as a cooperating agency. This project has been canceled.

  14. The Bonneville Power Administration is proposing to build a 500-kilovolt transmi

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office of ScienceandMesa del SolStrengthening a solidSynthesis of 2Dand Water |1Benefits of 3D vs. 2Dtransmis-

  15. The Bonneville Power Administration is proposing to build a 500-kilovolt transmi

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office of ScienceandMesa del SolStrengthening a solidSynthesis of 2Dand Water |1Benefits of 3D vs.

  16. EIS-0443: Project Financing for Southwest Intertie Project- South, Clark, Lincoln, Nye, and White Pine Counties, Nevada

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy (DOE), Western Area Power Administration, is considering whether to provide partial financing of the southern portion of the Southwest lntertie Project (SWIP-South) which consists of approximately 235 miles of 500- kilovolt (kV) transmission line.

  17. EIS-0296: South Oregon Coast Reinforcement Project, Coos Bay/North Bend, Oregon

    Broader source: Energy.gov [DOE]

    Bonneville Power Administration proposes to build a 500- kilovolt (kV) transmission line and new substation to reinforce electrical service to the southern coast of the state of Oregon. Nucor Steel, a division of Nucor Corporation, may build a new steel mill in the Coos Bay/North Bend, Oregon, area.

  18. EIS-0296: South Oregon Coast Reinforcement Project, Coos Bay/North Bend, Oregon

    Broader source: Energy.gov [DOE]

    This EIS analyzes BPA's proposed action to build a 500- kilovolt (kV) transmission line and new substation to reinforce electrical service to the southern coast of the state of Oregon. Nucor Steel, a division of Nucor Corporation, may build a new steel mill in the Coos Bay/North Bend, Oregon, area.

  19. EA-1967: Hills Creek-Lookout Point Transmission Line Rebuild, Lane County, Oregon

    Broader source: Energy.gov [DOE]

    Bonneville Power Administration is preparing an EA to assess potential environmental impacts of the proposed rebuild of its 26-mile 115 kilovolt (kV) wood-pole Hills Creek-Lookout Point transmission line, which is generally located between Lowell and Oakridge, in Lane County, Oregon.

  20. EA-1961: Kalispell-Kerr Transmission Line Rebuild Project, Kalispell and Polson, Montana

    Broader source: Energy.gov [DOE]

    Bonneville Power Administration is preparing an EA to evaluate potential environmental impacts of rebuilding its 41-mile long 115 kilovolt (kV) wood-pole Kalispell-Kerr transmission line between Kalispell and Polson, Montana. Additional information is available on the project website, http://efw.bpa.gov/environmental_services/Document_Library/KALISPELL_KERR/.

  1. EIS-0294: Sutter Power Project, Sutter County, California

    Broader source: Energy.gov [DOE]

    This EIS analyzes Western Area Power Administration's (Western) decision to support Calpine Corporation (Calpine) to construct an electric generating facility and associated 230-kilovolt (kV) transmission line, approximately 3.5 miles in length, known as the Sutter Power Plant (SPP).

  2. 898 Federal Register / Vol. 74, No. 6 / Friday, January 9, 2009 / Notices the time needed to review instructions;

    E-Print Network [OSTI]

    and semiannually. Estimated Total Annual Hour Burden: 0. Estimated Total Annual Cost: $0. Changes in the Estimates.g. landfills, rather than replacing existing OSWI units. No respondent or agency burdens or costs have been kilovolt (kV) Electric Transmission Line from Imperial Valley Substation (in Imperial Co. near the City

  3. CX-009197: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    2012 Spacer and Insulator Replacement Program; Hatwai-Dworshak No. 1 500-kilovolt (kV) Transmission Line Spacer Replacement Project CX(s) Applied: B1.3 Date: 09/24/2012 Location(s): Idaho, Idaho Offices(s): Bonneville Power Administration

  4. EA-1950: Grand Coulee-Creston Transmission Line Rebuild; Grant and Lincoln Counties, Washington

    Broader source: Energy.gov [DOE]

    Bonneville Power Administration prepared this EA to evaluate potential environmental impacts of rebuilding approximately 28 miles of the Grand Coulee-Creston No. 1 115-kilovolt (kV) transmission line between Coulee Dam in Grant County and Creston in Lincoln County, Washington.

  5. CX-008716: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Bonneville Power Administration (BPA) Tacoma Power Chehalis- Covington 230-Kilovolt (kV) Line/Convert Microwave Signals From Analog To Digital CX(s) Applied: B1.7 Date: 05/21/2012 Location(s): Washington, Washington, Washington Offices(s): Bonneville Power Administration

  6. An active system for the detection of special fissile material in small watercraft 

    E-Print Network [OSTI]

    Johansen, Norman Alfan, III

    2006-10-30T23:59:59.000Z

    FM Fissile material HEU Highly enriched uranium IAEA International Atomic Energy Agency keV kiloelectronvolt kV kilovolt MCNP Monte Carlo N-Particle MeV Megaelectronvolt NAA Neutron activation analysis NDA Non-destructive analysis PNG....5.1. Required source strength for HEU.....................................................................61 IV.5.2. Required source strength for plutonium............................................................64 IV.6. Passive plutonium...

  7. Operation of Lanzhou all permanent electron cyclotron resonance ion source No. 2 on 320 kV platform with highly charged ions

    SciTech Connect (OSTI)

    Lu, W., E-mail: luwang@impcas.ac.cn [Institute of Modern Physics, CAS, Lanzhou 730000 (China); University of Chinese Academy of Sciences, Beijing 100049 (China); Li, J. Y.; Kang, L.; Liu, H. P.; Li, H.; Li, J. D.; Sun, L. T.; Ma, X. W. [Institute of Modern Physics, CAS, Lanzhou 730000 (China)] [Institute of Modern Physics, CAS, Lanzhou 730000 (China)

    2014-02-15T23:59:59.000Z

    The 320 kV platform for multi-discipline research with highly charged ions is a heavy ion beam acceleration instrument developed by Institute of Modern Physics, which is dedicated to basic scientific researches such as plasma, atom, material physics, and astrophysics, etc. The platform has delivered ion beams of 400 species for 36?000 h. The average operation time is around 5000 h/year. With the beams provided by the platform, lots of outstanding progresses were made in various research fields. The ion source of the platform is an all-permanent magnet electron cyclotron resonance ion source, LAPECR2 (Lanzhou All Permanent ECR ion source No. 2). The maximum axial magnetic fields are 1.28 T at injection and 1.07 T at extraction, and the radial magnetic field is up to 1.21 T at the inner wall of the plasma chamber. The ion source is capable to produce low, medium, and high charge state gaseous and metallic ion beams, such as H{sup +}, {sup 40}Ar{sup 8+}, {sup 129}Xe{sup 30+}, {sup 209}Bi{sup 33+}, etc. This paper will present the latest result of LAPECR2 and the routine operation status for the high voltage platform.

  8. 2.3-MW Medium-Voltage, Three-Level Wind Energy Inverter Applying a Unique Bus Structure and 4.5-kV Si/SiC Hybrid Isolated Power Modules: Preprint

    SciTech Connect (OSTI)

    Erdman, W.; Keller, J.; Grider, D.; VanBrunt, E.

    2014-11-01T23:59:59.000Z

    A high-efficiency, 2.3-MW, medium-voltage, three-level inverter utilizing 4.5-kV Si/SiC (silicon carbide) hybrid modules for wind energy applications is discussed. The inverter addresses recent trends in siting the inverter within the base of multimegawatt turbine towers. A simplified split, three-layer laminated bus structure that maintains low parasitic inductances is introduced along with a low-voltage, high-current test method for determining these inductances. Feed-thru bushings, edge fill methods, and other design features of the laminated bus structure provide voltage isolation that is consistent with the 10.4-kV module isolation levels. Inverter efficiency improvement is a result of the (essential) elimination of the reverse recovery charge present in 4.5-kV Si PIN diodes, which can produce a significant reduction in diode turn-off losses as well as insulated-gate bipolar transistor (IGBT) turn-on losses. The hybrid modules are supplied in industry-standard 140 mm x 130 mm and 190 mm x 130 mm packages to demonstrate direct module substitution into existing inverter designs. A focus on laminated bus/capacitor-bank/module subassembly level switching performance is presented.

  9. Royal Swedish Academy of Sciences 2005 http://www.ambio.kva.se

    E-Print Network [OSTI]

    the environment from acidification and eutrophication and to reduce exposures to ground-level ozone. However) described the effects of shipping emissions on acidification, eutrophication, and ground-level ozone

  10. July 25, 2012 PRE-BID MEETING FOR SUPPLY AND INSTALLATION OF 2 x 320 KVA

    E-Print Network [OSTI]

    Souradeep, Tarun

    with the tender conditions mentioned therein. The vendors had a site visit of location where the D.G. set Battery Charger as we will give better services Answer : Vendor to verify that tender specification confirms the NHP make battery Charger & to provide the details for consideration. However vendor to quote

  11. Proposed Amendment to Presidential Permit PP-63 and Associated Modifications to 500-kV International Transmission Line: Forbes, Minnesota to Manitoba, Canada, Northern States Power Company. Addendum to the final Environmental Assessment

    SciTech Connect (OSTI)

    Not Available

    1992-10-01T23:59:59.000Z

    This Addendum to the Final Environmental Assessment for the Proposed Amendment to Presidential Permit PP-63 and Associated Modifications to 500 kV International Transmission Line: Forbes, Minnesota to Manitoba, Canada (DOE/EA-587) addresses Northern States Power Company`s (NSP) proposed expansion of the Forbes Substation. The applicant has requested that the expansion take place on the west side of the substation, within the existing property line, instead of on the north side as originally proposed. All of the proposed construction would take place on property already owned by NSP. DOE has reviewed the environmental impacts associated with this minor modification and has determined that the conclusions reached in the environmental assessment and Finding of No Significant Impact prepared in connection with NSP`s original amendment request remain valid.

  12. Proposed amendment to presidential permit PP-63 and associated modifications to 500 kV international transmission line, Forbes, Minnesota to Manitoba, Canada. Addendum to the final environmental assessment

    SciTech Connect (OSTI)

    Not Available

    1992-10-01T23:59:59.000Z

    This Addendum to the Final Environmental Assessment for the Proposed Amendment to Presidential Permit PP-63 and Associated Modifications to 500 kV International Transmission Line: Forbes, Minnesota to Manitoba, Canada (DOE/EA-587) addresses Northern States Power Company`s (NSP) proposed expansion of the Forbes Substation. The applicant has requested that the expansion take place on the west side of the substation, within the existing property line, instead of on the north side as originally proposed. All of the proposed construction would take place on property already owned by NSP. DOE has reviewed the environmental impacts associated with this minor modification and has determined that the conclusions reached in the environmental assessment and Finding of No Significant Impact prepared in connection with NSP`s original amendment request remain valid.

  13. Progress on the 140 KV, 10 Megawatt Peak, 1 Megawatt Average Polyphase Quasi-Resonant Bridge, Boost Converter/Modulator for the Spallation Neutron Source (SNS) Klystron Power System

    E-Print Network [OSTI]

    Reass, W A; Gribble, R F; Lynch, M T; Tallerico, P J; Reass, William A.; Doss, James D.; Gribble, Robert F.; Lynch, Michael T.; Tallerico, Paul J.

    2000-01-01T23:59:59.000Z

    This paper describes electrical design and operational characteristics of a zero-voltage-switching 20 kHz polyphase bridge, boost converter/modulator for klystron pulse application. The DC-DC converter derives the buss voltages from a standard 13.8 kV to 2300 Y substation cast-core transformer. Energy storage and filtering is provided by self-clearing metallized hazy polypropylene traction capacitors. Three "H-Bridge" IGBT switching networks are used to generate the polyphase 20 kHz transformers primary drive waveforms. The 20 kHz drive waveforms are chirped the appropriate duration to generate the desired klystron pulse width. PWM (pulse width modulation) of the individual 20 kHz pulses is utilized to provide regulated output waveforms with adaptive feedforward and feedback techniques. The boost transformer design utilizes amorphous nanocrystalline material that provides the required low core loss at design flux levels and switching frequencies. Resonant shunt peaking is used on the transformer secondary to ...

  14. 13Ambio Vol. 32 No. 1, Feb. 2003 Royal Swedish Academy of Sciences 2003 http://www.ambio.kva.se

    E-Print Network [OSTI]

    ), including nutrient pollution and subsequent eutrophication of lakes (4­6). Eutrophication of lakes refers the urban fringe suffer more from eutrophication remains unanswered. Lakes in urban centers may be more eutrophic because they have higher densities of humans and associated human impacts (4, 5, 14). If so

  15. 471Ambio Vol. 31 No. 6, Sept. 2002 Royal Swedish Academy of Sciences 2002 http://www.ambio.kva.se

    E-Print Network [OSTI]

    Ardö, Jonas

    ) per year (Gt yr­1 ) as a re- sult of combustion of fossil fuel, tropical deforestation and other land and to alleviate poverty in the affected regions, the UN Convention to Combat Desertification (UNCCD) strives

  16. 463Ambio Vol. 32 No 7, Nov. 2003 Royal Swedish Academy of Sciences 2003 http://www.ambio.kva.se

    E-Print Network [OSTI]

    Ardö, Jonas

    and biopesticides is expcted to increase. However, chemical pesticides will continue to be the main weapon against are essentially the same. They have a broad- spectrum activity and a rapid effect. They work mainly by Article

  17. 104 Royal Swedish Academy of Sciences 2001 Ambio Vol. 30 No. 2, March 2001 http://www.ambio.kva.se

    E-Print Network [OSTI]

    Thomas, Valerie

    of used lead-acid batteries. Environmen- tal data and measurements of lead are of very poor quality. How Union through a case study of lead pollu- tion, which shows a more complex and multi-faceted situation than what is typically reported as the Soviet environmental legacy. Some aspects of lead pollution

  18. 500-kV Central Ferry Substation ...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Substation Y Y Central Ferry Substation T u c a n n o n R i v e r S n a k e R i v e r 12 U V 127 U V 127 U V 260 U V 261 12 Starbuck Starbuck W h i t m a n W h i t m a...

  19. Klondike III/Biglow Canyon Wind Integration Project; Record of Decision, October 25, 2006.

    SciTech Connect (OSTI)

    United States. Bonneville Power Administration

    2006-10-25T23:59:59.000Z

    The Bonneville Power Administration (BPA) has decided to implement the Proposed Action identified in the Klondike III/Biglow Canyon Wind Integration Project Final Environmental Impact Statement (FEIS) (DOE/EIS-0374, September 2006). Under the Proposed Action, BPA will offer PPM Energy, Inc. (PPM) contract terms for interconnection of the proposed Klondike III Wind Project, located in Sherman County, Oregon, with the Federal Columbia River Transmission System (FCRTS). BPA will also offer Portland General Electric (PGE)1 contract terms for interconnection of its proposed Biglow Canyon Wind Farm, also located in Sherman County, Oregon, with the FCRTS, as proposed in the FEIS. To interconnect these wind projects, BPA will build and operate a 12-mile long, 230-kilovolt (kV) double-circuit transmission line between the wind projects and BPA's new 230-kV John Day Substation in Sherman County, Oregon. BPA will also expand its existing 500-kV John Day Substation.

  20. SU-E-I-81: Assessment of CT Radiation Dose and Image Quality for An Automated Tube Potential Selection Algorithm Using Adult Anthropomorphic and ACR Phantoms

    SciTech Connect (OSTI)

    Mahmood, U; Erdi, Y; Wang, W [Memorial Sloan Kettering Cancer Center, NY, NY (United States)

    2014-06-01T23:59:59.000Z

    Purpose: To assess the impact of General Electrics (GE) automated tube potential algorithm, kV assist (kVa) on radiation dose and image quality, with an emphasis on optimizing protocols based on noise texture. Methods: Radiation dose was assessed by inserting optically stimulated luminescence dosimeters (OSLs) throughout the body of an adult anthropomorphic phantom (CIRS). The baseline protocol was: 120 kVp, Auto mA (180 to 380 mA), noise index (NI) = 14, adaptive iterative statistical reconstruction (ASiR) of 20%, 0.8s rotation time. Image quality was evaluated by calculating the contrast to noise ratio (CNR) and noise power spectrum (NPS) from the ACR CT accreditation phantom. CNRs were calculated according to the steps described in ACR CT phantom testing document. NPS was determined by taking the 3D FFT of the uniformity section of the ACR phantom. NPS and CNR were evaluated with and without kVa and for all available adaptive iterative statistical reconstruction (ASiR) settings, ranging from 0 to 100%. Each NPS was also evaluated for its peak frequency difference (PFD) with respect to the baseline protocol. Results: The CNR for the adult male was found to decrease from CNR = 0.912 ± 0.045 for the baseline protocol without kVa to a CNR = 0.756 ± 0.049 with kVa activated. When compared against the baseline protocol, the PFD at ASiR of 40% yielded a decrease in noise magnitude as realized by the increase in CNR = 0.903 ± 0.023. The difference in the central liver dose with and without kVa was found to be 0.07%. Conclusion: Dose reduction was insignificant in the adult phantom. As determined by NPS analysis, ASiR of 40% produced images with similar noise texture to the baseline protocol. However, the CNR at ASiR of 40% with kVa fails to meet the current ACR CNR passing requirement of 1.0.

  1. SU-E-I-89: Assessment of CT Radiation Dose and Image Quality for An Automated Tube Potential Selection Algorithm Using Pediatric Anthropomorphic and ACR Phantoms

    SciTech Connect (OSTI)

    Mahmood, U; Erdi, Y; Wang, W [Memorial Sloan Kettering Cancer Center, NY, NY (United States)

    2014-06-01T23:59:59.000Z

    Purpose: To assess the impact of General Electrics automated tube potential algorithm, kV assist (kVa) on radiation dose and image quality, with an emphasis on optimizing protocols based on noise texture. Methods: Radiation dose was assessed by inserting optically stimulated luminescence dosimeters (OSLs) throughout the body of a pediatric anthropomorphic phantom (CIRS). The baseline protocol was: 120 kVp, 80 mA, 0.7s rotation time. Image quality was assessed by calculating the contrast to noise ratio (CNR) and noise power spectrum (NPS) from the ACR CT accreditation phantom. CNRs were calculated according to the steps described in ACR CT phantom testing document. NPS was determined by taking the 3D FFT of the uniformity section of the ACR phantom. NPS and CNR were evaluated with and without kVa and for all available adaptive iterative statistical reconstruction (ASiR) settings, ranging from 0 to 100%. Each NPS was also evaluated for its peak frequency difference (PFD) with respect to the baseline protocol. Results: For the baseline protocol, CNR was found to decrease from 0.460 ± 0.182 to 0.420 ± 0.057 when kVa was activated. When compared against the baseline protocol, the PFD at ASiR of 40% yielded a decrease in noise magnitude as realized by the increase in CNR = 0.620 ± 0.040. The liver dose decreased by 30% with kVa activation. Conclusion: Application of kVa reduces the liver dose up to 30%. However, reduction in image quality for abdominal scans occurs when using the automated tube voltage selection feature at the baseline protocol. As demonstrated by the CNR and NPS analysis, the texture and magnitude of the noise in reconstructed images at ASiR 40% was found to be the same as our baseline images. We have demonstrated that 30% dose reduction is possible when using 40% ASiR with kVa in pediatric patients.

  2. EA-1931: Keeler to Tillamook Transmission Line Rebuild Project, Washington and Tillamook Counties, Oregon

    Broader source: Energy.gov [DOE]

    Bonneville Power Administration prepared this EA to assess the potential environmental impacts of the proposed rebuild of the Keeler-Forest Grove and Forest Grove-Tillamook 115-kilovolt (kV) transmission lines between the cities of Hillsboro and Tillamook, in Washington and Tillamook Counties, Oregon. The 58-mile-long rebuild would include replacement of all wood-pole structures over 10 years in age. Some existing access roads would be improved to accommodate construction equipment and some new road access would be acquired or constructed in areas where access is not available.

  3. Data:E1bf36dc-a90f-4994-9da6-35da49c75453 | Open Energy Information

    Open Energy Info (EERE)

    0.024 per KWH. Next 140 KWH per KVA @ 0.021 per KWH. Over 470 KWH per KVA @ 0.018 per KWH. Power Cost Adjustment: 0.0001 Primary Service Discount: 0.040 per KVA When...

  4. Data:Eec227ff-726f-49ed-9b24-041ea06d27a1 | Open Energy Information

    Open Energy Info (EERE)

    will provide as standard service up to 200 Amp capacity for the base rate. Over 200 Amp service will be 6.00 per KVA for each KVA in excess of 15 KVA plus base rate. Line...

  5. North Steens 230kV Transmission | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand Jump to: navigation, searchOfRoseConcerns Jumpsource History View New PagesRiver Shores,North

  6. Alvey-Fairview No.1, 230 kV Rebuild

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office511041cloth DocumentationProductsAlternative FuelsSanta Fe Metro

  7. EIS-0159: Record of Decision

    Broader source: Energy.gov [DOE]

    Flatiron-Erie 115-kilovolt Transmission Line Project, Larimer County, Boulder County, Weld County, Colorado

  8. Development of Toroidal Core Transformers

    SciTech Connect (OSTI)

    Leon, Francisco

    2014-05-31T23:59:59.000Z

    The original objective of this project was to design, build and test a few prototypes of singlephase dry-type distribution transformers of 25 kVA, 2.4 kV primary to 120 V transformers using cores made of a continuous steel strip shaped like a doughnut (toroid). At different points during the development of the project, the scope was enhanced to include the more practical case of a 25 kVA transformer for a 13.8 kV primary system voltage. Later, the scope was further expanded to design and build a 50 kVA unit to transformer voltage from 7.62 kV to 2x120 V. This is a common transformer used by Con Edison of New York and they are willing to test it in the field. The project officially started in September 2009 and ended in May 2014. The progress was reported periodically to DOE in eighteen quarterly reports. A Continuation Application was submitted to DOE in June 2010. In May 2011 we have requested a non-cost extension of the project. In December 2011, the Statement of Project Objectives (SOPO) was updated to reflect the real conditions and situation of the project as of 2011. A second Continuation Application was made and funding was approved in 2013 by DOE and the end date was extended to May 2014. The technical challenges that were overcome in this project include: the development of the technology to pass the impulse tests, derive a model for the thermal performance, produce a sound mechanical design, and estimate the inrush current. However, the greatest challenge that we faced during the development of the project was the complications of procuring the necessary parts and materials to build the transformers. The actual manufacturing process is relatively fast, but getting all parts together is a very lengthy process. The main products of this project are two prototypes of toroidal distribution transformers of 7.62 kV (to be used in a 13.8 kV system) to 2x120 V secondary (standard utilization voltage); one is rated at 25 kVA and the other at 50 kVA. The 25 kVA transformer passed the impulse test in KEMA high-voltage laboratories. Additional products include: nine papers published in the IEEE Transactions on Power Delivery, one patent has been filed, three PhD students weresupported from beginning to graduation, five postdoctoral fellows, and three MSc students were partially supported. The electrical characteristics of our dry-type toroidal transformers are similar to those of the oil-immersed pole mounted transformers currently in use by many utilities, but toroids have higher efficiency. The no-load losses of the 50 kVA prototype are only 45 W. A standard transformer has no-load losses between 90 and 240 W. Thus, even the finest transformer built today with standard technology has double the amount of no-load losses than the prototype toroidal transformer. When the manufacturing process is prepared for mass production, the cost of a dry-type toroidal transformer would be similar to the price of an oil-filed standard design. However, because of the greatly reduced losses, the total ownership cost of a toroidal transformer could be about half of a traditional design. We got a grant from Power Bridge NY in the amount of $149,985 from June 2014 to May 2015 to continue developing the transformer with commercialization objectives. We are considering the possibility to incorporate a company to manufacture the transformers and have contacted investors. The current status of the real life testing is as follows: after several months of silence, Con Edison has re-started conversations and has shown willingness to test the transformer. Other companies, PSE&G and National Grid have recently also shown interest and we will present our product to them soon.

  9. EA-0962: Construction and Routine Operation of a 12-kilovolt Overhead Powerline and Formal Authorization for a 10-inch and 8-inch Fresh Water Pipeline Right-of-Way at Naval Petroleum Reserve No. 1, Kern County, California

    Broader source: Energy.gov [DOE]

    This EA evaluates the environmental impacts of the proposal to install an overhead powerline extension from the U.S. Department of Energy's Naval Petroleum Reserve No. 1 (NPR-1) power source to the...

  10. Record of Decision for the Electrical Interconnection of the Windy Point Wind Energy Project.

    SciTech Connect (OSTI)

    United States. Bonneville Power Administration.

    2006-11-01T23:59:59.000Z

    The Bonneville Power Administration (BPA) has decided to offer contract terms for interconnection of 250 megawatts (MW) of power to be generated by the proposed Windy Point Wind Energy Project (Wind Project) into the Federal Columbia River Transmission System (FCRTS). Windy Point Partners, LLC (WPP) propose to construct and operate the proposed Wind Project and has requested interconnection to the FCRTS. The Wind Project will be interconnected at BPA's Rock Creek Substation, which is under construction in Klickitat County, Washington. The Rock Creek Substation will provide transmission access for the Wind Project to BPA's Wautoma-John Day No.1 500-kilovolt (kV) transmission line. BPA's decision to offer terms to interconnect the Wind Project is consistent with BPA's Business Plan Final Environmental Impact Statement (BP EIS) (DOE/EIS-0183, June 1995), and the Business Plan Record of Decision (BP ROD, August 15, 1995). This decision thus is tiered to the BP ROD.

  11. Telephone Flat Geothermal Development Project Environmental Impact Statement Environmental Impact Report. Final

    SciTech Connect (OSTI)

    None

    1999-02-01T23:59:59.000Z

    This Final Environmental Impact Statement and Environmental Impact Report (Final EIS/EIR) has been prepared to meet the requirements of the National Environmental Policy Act (NEPA) and the California Environmental Quality Act (CEQA). The Proposed Action includes the construction, operation, and decommissioning of a 48 megawatt (gross) geothermal power plant with ancillary facilities (10-12 production well pads and 3-5 injection well pads, production and injection pipelines), access roads, and a 230-kilovolt (kV) transmission line in the Modoc National Forest in Siskiyou County, California. Alternative locations for the power plant site within a reasonable distance of the middle of the wellfield were determined to be technically feasible. Three power plant site alternatives are evaluated in the Final EIS/EIR.

  12. Schultz-Hanford Area Transmission Line Project Draft Environmental Impact Statement

    SciTech Connect (OSTI)

    N /A

    2002-02-08T23:59:59.000Z

    This summary covers the major points of the Draft Environmental Impact Statement (EIS) prepared for the BPA Schultz-Hanford Transmission Project proposed by the Bonneville Power Administration (BPA). The project involves constructing a new 500-kilovolt (kV) line in central Washington, north of Hanford. The new line would connect to an existing line at the Schultz Substation near Ellensburg and to a new or existing substation in the Hanford area (see Map 2 in EIS). The project may also involve constructing a new substation to accommodate the new transmission line. As a federal agency, BPA is required by the National Environmental Policy Act (NEPA) to take into account potential environmental consequences of its proposal and take action to protect, restore, and enhance the environment during and after construction. Preparation of this EIS assists in meeting those requirements.

  13. Data:Ff62a462-e80f-4d19-8ed4-ea1b110e6341 | Open Energy Information

    Open Energy Info (EERE)

    name: Meeker Coop Light & Power Assn Effective date: End date if known: Rate name: Large Power Peak Alert: 50 KVA to 350 KVA- Non Control Sector: Commercial Description: Source or...

  14. Data:E7101117-ac86-4860-b08b-f043c5e88676 | Open Energy Information

    Open Energy Info (EERE)

    0.028 per KWH. Next 140 KWH per KVA @ 0.024 per KWH. Over 470 KWH per KVA @ 0.021 per KWH. Power Cost Adjustment: 0.0001 Source or reference: Rate Binder Kelly 11 ISU...

  15. Data:5f97368e-9814-4f0c-9bcb-c9f7fb6e0b23 | Open Energy Information

    Open Energy Info (EERE)

    0.035 per KWH. Next 140 KWH per KVA @ 0.029 per KWH. Over 470 KWH per KVA @ 0.023 per KWH. Power Cost Adjustment: 0.0001 Source or reference: Rate Binder Kelly 11 ISU...

  16. Data:B1bc8c49-742b-4298-bf5e-c693012c631f | Open Energy Information

    Open Energy Info (EERE)

    0.026 per KWH. Next 140 KWH per KVA @ 0.022 per KWH. Over 470 KWH per KVA @ 0.019 per KWH. Power Cost Adjustment: 0.0001 Source or reference: Rate Binder Kelly 11 ISU...

  17. Data:6aaf3bd3-a593-4012-9a64-d50af6aae37b | Open Energy Information

    Open Energy Info (EERE)

    0.022 per KWH. Next 140 KWH per KVA @ 0.019 per KWH. Over 470 KWH per KVA @ 0.016 per KWH. Power Cost Adjustment: 0.0001 Source or reference: Rate Binder Kelly 11 ISU...

  18. Data:86569193-360e-4643-9a4c-99f318741e1e | Open Energy Information

    Open Energy Info (EERE)

    0.028 per KWH. Next 140 KWH per KVA @ 0.024 per KWH. Over 470 KWH per KVA @ 0.021 per KWH. Power Cost Adjustment: 0.0001 Source or reference: Rate Binder Kelly 11 ISU...

  19. Data:6a97852e-2512-4b61-8526-b1079d3221fd | Open Energy Information

    Open Energy Info (EERE)

    0.024 per KWH. Next 140 KWH per KVA @ 0.021 per KWH. Over 470 KWH per KVA @ 0.018 per KWH. Power Cost Adjustment: 0.0001 When Consumer's building or structure is sufficiently...

  20. Data:58db9e4d-6785-4e0c-bb85-793d68fc3702 | Open Energy Information

    Open Energy Info (EERE)

    0.026 per KWH. Next 140 KWH per KVA @ 0.022 per KWH. Over 470 KWH per KVA @ 0.019 per KWH. Power Cost Adjustment: 0.0001 Source or reference: Rate Binder Kelly 11 ISU...

  1. Data:F40fc4c9-0e02-428b-b96d-bcfb5222116e | Open Energy Information

    Open Energy Info (EERE)

    0.024 per KWH. Next 140 KWH per KVA @ 0.021 per KWH. Over 470 KWH per KVA @ 0.018 per KWH. Power Cost Adjustment: 0.0001 Source or reference: Rate Binder Kelly 11 ISU...

  2. Data:3775b1a9-cb0a-4487-bbdf-c461b085a357 | Open Energy Information

    Open Energy Info (EERE)

    0.033 per KWH. Next 140 KWH per KVA @ 0.027 per KWH. Over 470 KWH per KVA @ 0.021 per KWH. Power Cost Adjustment: 0.0001 Source or reference: Rate Binder Kelly 11 ISU...

  3. U.S. Department of Energy Categorical Exclusion Determination

    Broader source: Energy.gov (indexed) [DOE]

    would prepare the facility for replacement of two older 500 KVA government-owned transformers (which are excessively sized) with a single 500 to 700 KVA transformer that would...

  4. Data:Ac6a66e7-9a41-4b96-bcd8-9b7caf435c56 | Open Energy Information

    Open Energy Info (EERE)

    water heater load control. An additional .02 per day per kVa will be applied for transformers over 75 kVa. Source or reference: ISU Documentation Source Parent: Comments fixed...

  5. Data:0867fdac-a2f9-4bc2-997b-ec2684d056d5 | Open Energy Information

    Open Energy Info (EERE)

    average demands less than 1,000 kVA. Customer's monthly billing demands under this tariff shall not be less than 60 kVA. Customers may continue to qualify for service under...

  6. Data:A384e673-627e-4c3b-bf30-287829ad2cc7 | Open Energy Information

    Open Energy Info (EERE)

    will provide as standard service, up to 200 Amp capacity for the base rate. Over 200 Amp service will be .50 per KVA in excess of 15 KVA plus the base rate. Line extension...

  7. Data:98df1814-468a-4015-8176-c54a7a737b28 | Open Energy Information

    Open Energy Info (EERE)

    will provide as standard service, up to 200 Amp capacity for the base rate. Over 200 Amp service will be .50 per KVA in excess of 15 KVA plus the base rate. Line extension...

  8. Data:E43ada81-47c3-4830-a717-6cb806a5e67e | Open Energy Information

    Open Energy Info (EERE)

    will provide as standard service, up to 200 Amp capacity for the base rate. Over 200 Amp service will be .50 per KVA in excess of 15 KVA plus the base rate. Line extension...

  9. Data:B4d0cb8d-1da8-4ab7-84df-80c581a1e2a0 | Open Energy Information

    Open Energy Info (EERE)

    will provide as standard service, up to 200 Amp capacity for the base rate. Over 200 Amp service will be .50 per KVA in excess of 15 KVA plus the base rate. Line extension...

  10. Data:829f535d-4378-468f-b5f9-c767185bde0f | Open Energy Information

    Open Energy Info (EERE)

    0.028 per KWH. Next 140 KWH per KVA @ 0.024 per KWH. Over 470 KWH per KVA @ 0.021 per KWH. Power Cost Adjustment: 0.0001 Primary Meter Discount: 0.40 per KVA. Source or...

  11. Data:E93fa523-f6c5-4240-82b5-3a3e396ee3eb | Open Energy Information

    Open Energy Info (EERE)

    0.022 per KWH. Next 140 KWH per KVA @ 0.019 per KWH. Over 470 KWH per KVA @ 0.016 per KWH. Power Cost Adjustment: 0.0001 Primary Service Discount: 0.040 per KVA Source or...

  12. Data:1aec8d19-b9f5-4f22-9b66-46275858d5a8 | Open Energy Information

    Open Energy Info (EERE)

    0.026 per KWH. Next 140 KWH per KVA @ 0.022 per KWH. Over 470 KWH per KVA @ 0.019 per KWH. Power Cost Adjustment: 0.0001 Primary Meter Discount: 0.40 per KVA Source or...

  13. CX-007665: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    of (3) three - 13.8kilovolt-208Y120, 1-Phase, 50 kilovolt-amphere pole mounted transformers to provide such power. A new pole will be placed in line with the existing 13.8...

  14. Electric Power Delivery Testing Feasibility Study Task 6 Final Report

    SciTech Connect (OSTI)

    Thomas Tobin

    2009-07-01T23:59:59.000Z

    This Final Report is covers the completion of the Electric Power Delivery Testing Feasibility Study. The objective of this project was to research, engineer, and demonstrate high-power laboratory testing protocols to accurately reproduce the conditions on the electric power grid representing both normal load switching and abnormalities such as short-circuit fault protection. Test circuits, equipment, and techniques were developed and proven at reduced power levels to determine the feasibility of building a large-scale high-power testing laboratory capable of testing equipment and systems at simulated high-power conditions of the U.S. power grid at distribution levels up through 38 kiloVolts (kV) and transmission levels up through 230 kV. The project delivered demonstrated testing techniques, high-voltage test equipment for load testing and synthetic short-circuit testing, and recommended designs for future implementation of a high-power testing laboratory to test equipment and systems, enabling increased reliability of the electric transmission and distribution grid.

  15. EA-1551: Montana Alberta Tie Ltd. (MATL) 230-KV Transmission Line

    Broader source: Energy.gov [DOE]

    DOE started to prepare, jointly with the Montana Department of Environmental Quality (MDEQ), an EA that would also serve as a state EIS. The document would evaluate the potential environmental impacts of a proposed international transmission line that would cross the U.S.-Canada border in northwest Montana. Based on comments received on the DOE Draft EA/MDEQ Draft EIS, DOE cancelled preparation of the EA and announced preparation of DOE/EIS-0399 (of the same title).

  16. EIS-0301: NRG Energy Services, Inc., Arizona-Baja California 500 kV Transmission Line

    Broader source: Energy.gov [DOE]

    This EIS analyzes DOE's decision to approve NRG Energy, Inc. (NRG) for a Presidential permit to construct a 500,000-volt transmission line originating at the switchyard of the Palo Verde Nuclear Generating Station near Phoenix, Arizona, and extending approximately 177 miles to the southwest, where it would cross the United States (U.S.) border with Mexico in the vicinity of Calexico, California.

  17. Abstract Number #10041 A 150kV/300A/1s COAXIAL BLUMLEIN PULSER

    E-Print Network [OSTI]

    . They consist of pieces of transmission lines charged in parallel , which discharge synchronously in series generators made of pieces of transmission lines and normally used in a great variety of applications

  18. Gain Measurement of Antennas using RFID Pavel V. Nikitin and K.V. S. Rao

    E-Print Network [OSTI]

    Hochberg, Michael

    modulation [4-6], using fixed impedance loads [7], and special small battery operated RF transceivers [8 impedance) and could not be replaced with an arbitrary 50 Ohm antenna. Here, we propose a method to measure includes the effect of impedance mismatch for a particular load (chip assembly). First, a measurement

  19. 2008. The Cartographic Section, Dept. of Geography, UWO /#19-09/kv To Spencer Hall

    E-Print Network [OSTI]

    Lennard, William N.

    Perth Hall University Child Care Centre UWO Books Plus Platt's Lane Estates TD Waterhouse Stadium Wind 367363357 UNIVERSITY PLATT'SLANE LAMBTON OXFORD KENT UNIVERSITY PERTH SARNIA ROAD BURNLEA WALK BRESCIALANE's University College at UWO HURON WINDERMERE ROAD GLENMORE ELGIN WESTERN ROAD PLATT'SLANE UNIVERSITY HILL

  20. ETM (Distribution Network Automation on 10 kV cable line stations...

    Open Energy Info (EERE)

    will be equipped by RTUs, to provide remote observability and remote control. The communication (connection) is established via GSM network. References "EU Smart Grid...

  1. DESIGN AND PSPICE SIMULATION OF A 150KV/300A/1S COAXIAL PULSE GENERATOR

    E-Print Network [OSTI]

    that contributes to the power loss of the device and the requirement of long lengths of lines for operation, reducing the output current and, thus, contributing less to the overall power loss of the device

  2. ac 66-1100 kv: Topics by E-print Network

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    limits. The models are used to estimate the benefits of electricity locational marginal pricing (LMP) that arise from de Gispert, Adri 403 www.eprg.group.cam.ac.uk...

  3. Aalborg Universitet Line Differential Protection Scheme Modelling for Underground 420 kV Cable Systems

    E-Print Network [OSTI]

    Bak, Claus Leth

    alternating current) cable system, a detailed approach to EMTDC/PSCAD modelling of protective relays configuration of the protective relaying. The present paper describes modelling methodology on the basis differential protection, XLPE HVAC cable, EMTDC/PSCAD relay model, SIPROTEC 4 7SD522, 7SD610. 1. Introduction

  4. Gating Currents from Kv7 Channels Carrying Neuronal Hyperexcitability Mutations in the Voltage-Sensing Domain

    E-Print Network [OSTI]

    Bezanilla, Francisco

    unable to provide a detailed assessment of the structural rearrangements underlying channel gating.2 channels both functionally and structurally, were used for these experiments. The data obtained showed activation of gating-pore currents at depolarized potentials. These results reveal that distinct molecular

  5. High speed transfer switch with 50 kA and 50 kV

    SciTech Connect (OSTI)

    Reass, W.A.; Kasik, R.J.; Wilds, W.A.

    1989-01-01T23:59:59.000Z

    This paper gives the mechanical design and electrical parameters of a pneumatically operated transfer switch. This design is used to switch 3-second 50-kA current pulses, and is easily capable of 75 kA operation (2 {times} 10{sup 10} I{sup 2}t); with water-cooled versions capable of 20 kA continuously. Although the switch is not specifically designed to make or break 50 kA, it is provided with auxiliary Elkonite arcing contacts have proven their value in protecting the main electrodes even under repetitive (50 kA) fault conditions. Included in this presentation will be the results of extensive life testing and associated criteria. 6 figs., 1 tab.

  6. Revised Biological Assessment for the Carrizo-Midway 230kV Reconductor...

    Broader source: Energy.gov (indexed) [DOE]

    (CAISO) has determined that transmission upgrades will be required to deliver the energy generated by proposed the Topaz Solar Farm Project on the Carrizo Plain....

  7. Microsoft Word - Deering Lake-Eckley 115-kV Transmission Line...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    window washing, lawn mowing, trash collection, painting, and snow removal). Routine maintenance activities, corrective (that is, repair), preventive, and predictive, are...

  8. EIS-0159: Flatiron-Erie 115-kV Transmission Line

    Broader source: Energy.gov [DOE]

    "The Western Area Power Administration proposes to build 27 new wood H-frame structures along the line, to replace or modify 45 of the existing structures and to remove 11 of them."

  9. Bouse Hills Pumping Plant to Harcuvar 115-kV Transmission Line

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    areas, and other water sources that are vital in a region); and X (vii) Tundra, coral reefs, or rain forests.; or X (5) Involve genetically engineered organisms, synthetic...

  10. Mead-Liberty 345-kV Transmission Line Access Road Maintenance...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    areas, and other water sources that are vital in a region); and X (vii) Tundra, coral reefs, or rain forests.; or X (5) Involve genetically engineered organisms, synthetic...

  11. International 345 kV transmission line to Highgate, Vermont: environmental assessment

    SciTech Connect (OSTI)

    Not Available

    1985-02-01T23:59:59.000Z

    The action under consideration is the issuance of a Presidential permit to the Vermont Electric Power Company, Inc. (VELCO) for the construction, operation, maintenance and connection of a facility that will cross the United States-Canada border for international transmission of electric energy. The proposed transmission facilities will consist of a 7.5 mile, alternating current (ac) transmission line and a 200 MW back-to-back direct current (dc) converter terminal station. None of the facilities will involve any polluting emissions. The construction and maintenance of the proposed converter terminal station and transmission facilities will have little or no impact on the geologic features of the region. The transmission line will have little or no effect on agricultural land. Impacts on commercial forestry in the area will be minimal. The proposed route will require clearing about 36 acres of forest. The proposed transmission line and converter terminal site will have no effect on recreational activities, mining activites, residential, commercial, or industrial land use. The proposed corridor will have a minimal impact on area terrestrial wildlife and plant communities. The proposed project will have little or no impact on future population distribution, the operation of local services, employment and economic benefit, or housing in either Franklin or Highgate. 16 references, 3 figures. (ACR)

  12. ESS 2012 Peer Review - 15 kV Phase Leg Power Modules with SiC...

    Broader source: Energy.gov (indexed) [DOE]

    +1 703 996 8200 43670 Trade Center Pl 155; Dulles VA 20166 September 27, 2012 Acknowledgement: The authors thank Dr. Imre Gyuk for funding this work and Dr. Stan Atcitty for...

  13. Development and interrupting tests on 250KV 8KA HVDC circuit breaker

    SciTech Connect (OSTI)

    Tokuyama, S.; Arimatsu, K.; Hirata, K.; Kato, Y.; Yoshioka, Y.

    1985-09-01T23:59:59.000Z

    This paper describes the circuit and component selections, development and equivalent circuit test results on an HVDC circuit breaker for an HVDC transmission line. A puffer type SF/sub 6/ gas interrupter for AC circuit breakers is utilized for interrupting DC current with injection of high-frequency inverse current from a commutating capacitor precharged to HVDC line voltage. Also, the effectiveness of application of the HVDC breaker to an HVDC system with two parallel transmission lines is demonstrated through the EMTP simulation.

  14. Space charge measurements downwind from a monopolar 500 KV HVDC test line

    SciTech Connect (OSTI)

    Carter, P.J.; Johnson, G.B. (General Electric Co., EPRI-High Voltage Transmission, Research Center, Lenox, MA (US))

    1988-10-01T23:59:59.000Z

    One quantity that helps describe the electrical environment in the vicinity of a HVDC line is space charge, a quantity that consists of charged air ions and charged aerosols. This paper describes measurements made at the Electric Power Research Institute's High Voltage Transmission Research Center (HVTRC) in Lenox, MA to determine the concentration of space charge present downwind of a HVDC test line and the influence of wind on the space charge level. The instrumentation used to make the measurements of space charge downwind of the line is also described.

  15. EIS-0399: Montana Alberta Tie Ltd. (MATL) 230-KV Transmission Line

    Broader source: Energy.gov [DOE]

    DOE, jointly with the Montana Department of Environmental Quality (MDEQ), prepared an EIS that evaluated the potential environmental impacts of a proposed international transmission line that would cross the U.S.-Canada border in northwest Montana.

  16. EIS-0103: New England/Hydro-Quebec 450-kV Direct Current Transmission Line Interconnection

    Broader source: Energy.gov [DOE]

    The Economic Regulatory Administration prepared this statement to evaluate the environmental impacts of the construction, maintenance and operation of a 57-mile transmission line from Monroe, New Hampshire, to the U.S./Canadian border for the purpose of economic exchange of power and increased reliability.

  17. EIS-0100: Liberty-Coolidge 230-kV Transmission Line, Arizona

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy’s Western Area Power Administration prepared this statement to assess the potential environmental and socioeconomic implications of various alternatives associated with an upgrade of electrical transmission capability between the Liberty and Coolidge Substations.

  18. EIS-0129: New England/Hydro-Quebec 450 kV Transmission Line Interconnection- Phase II

    Broader source: Energy.gov [DOE]

    The Economic Regulatory Administration issued this EIS to explore the impacts of amending Presidential Permit PP-76 to allow the Vermont Electrical Company to operate at power levels above those stipulated in the permit and to build additional transmission facilities to distribute the increased power.

  19. EIS-0011: New Melones 230-kV Electrical Transmission Line, Central Valley Project, California

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy's Western Area Power Administration prepared this statement to evaluate the environmental impacts of proposed development of an electrical transmission system for the New Melones Power Plant.

  20. EIS-0505: Vantage to Pomona Heights 230 kV Transmission Line Project;

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels DataDepartment of Energy Your Density Isn't Your Destiny:Revised FindingDepartmentDepartmentStatement | Department ofDepartmentDepartment

  1. Back-to-Back Energization of a 60kV Cable Network -Inrush Currents Phenomenon

    E-Print Network [OSTI]

    Silva, Filipe Faria Da

    is with the Institute of Energy Technology, Aalborg University, 9220 Aalborg, Demark (e-mail: clb@iet.aau.dk). M. Lind was supported by ENV: Elforsyningen Nordvendsyssel F. F. da Silva is a PhD student at the Institute of Energy Technology, Aalborg University, 9220 Aalborg, Denmark (e-mail: ffs@iet.aau.dk). C. L. Bak

  2. Cameron to Milford-138kV Transmission Line | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand Jump to:EzfeedflagBiomassSustainableCSL GasPermits Manual Jump to:(RECP) inCounty, Texas:Cameron to

  3. Further Notice of 230kV Circuit Planned Outages | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels DataDepartment of Energy Your Density Isn't YourTransport inEnergy0.pdfTechnologies ProgramOutfittedof6 * September 2005Further Notice

  4. Notification of Planned 230kV Outage at Potomac River Generating Station

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels DataDepartment of Energy Your Density Isn'tOrigin of Contamination in ManyDepartment of Energy NorthB O N N789266 FederalJuly 6, 2006

  5. Notification of Planned 230kV Outage at Potomac River Generating Station |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels DataDepartment of Energy Your Density Isn'tOrigin of Contamination in ManyDepartment of Energy NorthB O N N789266 FederalJuly 6,

  6. Notification of Planned 230kV Outage at Potomac River Generating Station |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels DataDepartment of Energy Your Density Isn'tOrigin of Contamination in ManyDepartment of Energy NorthB O N N789266 FederalJuly

  7. Notification of Planned 230kV Outage at Potomac River Generating Station |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels DataDepartment of Energy Your Density Isn'tOrigin of Contamination in ManyDepartment of Energy NorthB O N N789266 FederalJulyDepartment

  8. Notification of Planned 230kV Outage at Potomac River Generating Station |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels DataDepartment of Energy Your Density Isn'tOrigin of Contamination in ManyDepartment of Energy NorthB O N N789266

  9. Notification of Planned 230kV Outage at Potomac River Generating Station |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page onYouTube YouTube Note: Since the.pdfBreaking ofOilNEW HAMPSHIREofNewsletterEnergySeptember 16,

  10. Notification of Planned 230kV Outage at Potomac River Generating Station |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page onYouTube YouTube Note: Since the.pdfBreaking ofOilNEW HAMPSHIREofNewsletterEnergySeptember 16,Department of

  11. Notification of Planned 230kV Outage at Potomac River Generating Station |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page onYouTube YouTube Note: Since the.pdfBreaking ofOilNEW HAMPSHIREofNewsletterEnergySeptember 16,Department ofDepartment

  12. Notification of Planned 230kV Outage at Potomac River Generating Station |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page onYouTube YouTube Note: Since the.pdfBreaking ofOilNEW HAMPSHIREofNewsletterEnergySeptember 16,Department

  13. 0.4 kV remote control (Smart Grid Project) | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand Jump to:Ezfeedflag JumpID-fTriWildcat 1 Wind Projectsource HistorykV remote control (Smart Grid

  14. 220 kV SSSC device for power flow control (Smart Grid Project) | Open

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand Jump to:Ezfeedflag JumpID-fTriWildcat 1 Wind ProjectsourceInformationColorado School of Home

  15. Docket No. EO-05-01: Further Notice of 230kV Circuit Planned Outages |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels DataDepartment of Energy Your Density Isn't Your Destiny:Revised Finding of No53197E T ADRAFTJanuary 2004April 2015 <Department of

  16. ETM (Distribution Network Automation on 10 kV cable line stations) (Smart

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand JumpConceptual Model,DOE FacilityDimondale,South, NewDyerTier2 Submit

  17. Docket No. EO-05-01: Further Notice of 230kV Circuit Planned Outages |

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742Energy China 2015 Business42.1Energy | DepartmenttheFebruary 13, 2013 meeting

  18. Ashland Area Support Substation Project : Environmental Assessment.

    SciTech Connect (OSTI)

    United States. Bonneville Power Administration.

    1992-06-01T23:59:59.000Z

    The Bonneville Power Administration (BPA) provides wholesale electric service to the City of Ashland (the City) by transferring power over Pacific Power & Light Company`s (PP&L) 115-kilovolt (kV) transmission lines and through PP&L`s Ashland and Oak Knoll Substations. The City distributes power over a 12.5-kV system which is heavily loaded during winter peak periods and which has reached the limit of its ability to serve peak loads in a reliable manner. Peak loads under normal winter conditions have exceeded the ratings of the transformers at both the Ashland and Oak Knoll Substations. In 1989, the City modified its distribution system at the request of PP&L to allow transfer of three megawatts (MW`s) of electric power from the overloaded Ashland Substation to the Oak Knoll Substation. In cooperation with PP&L, BPA installed a temporary 6-8 megavolt-amp (MVA) 115-12.5-kV transformer for this purpose. This additional transformer, however, is only a temporary remedy. BPA needs to provide additional, reliable long-term service to the Ashland area through additional transformation in order to keep similar power failures from occurring during upcoming winters in the Ashland area. The temporary installation of another 20-MVA mobile transformer at the Ashland Substation and additional load curtailment are currently being studied to provide for sustained electrical service by the peak winter period 1992. Two overall electrical plans-of-service are described and evaluated in this report. One of them is proposed for action. Within that proposed plan-of-service are location options for the substation. Note that descriptions of actions that may be taken by the City of Ashland are based on information provided by them.

  19. Ashland Area Support Substation Project

    SciTech Connect (OSTI)

    Not Available

    1992-06-01T23:59:59.000Z

    The Bonneville Power Administration (BPA) provides wholesale electric service to the City of Ashland (the City) by transferring power over Pacific Power Light Company's (PP L) 115-kilovolt (kV) transmission lines and through PP L's Ashland and Oak Knoll Substations. The City distributes power over a 12.5-kV system which is heavily loaded during winter peak periods and which has reached the limit of its ability to serve peak loads in a reliable manner. Peak loads under normal winter conditions have exceeded the ratings of the transformers at both the Ashland and Oak Knoll Substations. In 1989, the City modified its distribution system at the request of PP L to allow transfer of three megawatts (MW's) of electric power from the overloaded Ashland Substation to the Oak Knoll Substation. In cooperation with PP L, BPA installed a temporary 6-8 megavolt-amp (MVA) 115-12.5-kV transformer for this purpose. This additional transformer, however, is only a temporary remedy. BPA needs to provide additional, reliable long-term service to the Ashland area through additional transformation in order to keep similar power failures from occurring during upcoming winters in the Ashland area. The temporary installation of another 20-MVA mobile transformer at the Ashland Substation and additional load curtailment are currently being studied to provide for sustained electrical service by the peak winter period 1992. Two overall electrical plans-of-service are described and evaluated in this report. One of them is proposed for action. Within that proposed plan-of-service are location options for the substation. Note that descriptions of actions that may be taken by the City of Ashland are based on information provided by them.

  20. Data:D754b30b-7d5d-495a-9e52-45d3534e5870 | Open Energy Information

    Open Energy Info (EERE)

    Sector: Commercial Description: less than 300 kVA transformer capacity, less than 10 HP motor capacity Source or reference: http:navopache.coopwebbuilder.comsites...

  1. Data:5936b333-a9b4-44f1-a058-5243cadb8162 | Open Energy Information

    Open Energy Info (EERE)

    Sector: Commercial Description: less than 300 kVA transformer capacity, less than 10 HP motor capacity Source or reference: http:navopache.coopwebbuilder.comsites...

  2. Data:95ff90db-93d5-4889-b78f-41d6a03f9cb7 | Open Energy Information

    Open Energy Info (EERE)

    name: Meeker Coop Light & Power Assn Effective date: End date if known: Rate name: Large Power Peak Alert: 350 KVA or Greater- Non Control Sector: Commercial Description: Source...

  3. Data:20521eb5-df30-4d5b-8667-c0d7a294fe26 | Open Energy Information

    Open Energy Info (EERE)

    Coop Effective date: 20131001 End date if known: Rate name: Small Commercial- Demand Management Rate Sector: Commercial Description: A facility charge of .5 per kVa is...

  4. Data:A76418ec-a1b6-4db0-88e7-c75c03da8782 | Open Energy Information

    Open Energy Info (EERE)

    date: 20131001 End date if known: Rate name: Large Commercial and Industrial Demand Management Rate Sector: Commercial Description: A facility charge of .5 per kVa is...

  5. Data:67287d5f-720f-4190-a363-a5410d844835 | Open Energy Information

    Open Energy Info (EERE)

    Electric Coop Effective date: End date if known: Rate name: Large Agricultural Demand Management Rate Sector: Commercial Description: A facility charge of .5 per kVa is...

  6. Data:49e3bbf7-3193-4f07-a3b7-1111318cfd0f | Open Energy Information

    Open Energy Info (EERE)

    consumers including existing single-phase consumers located within the utility's New Mexico service area , requiring transformer capacity in excess of 350 KVA, for all types of...

  7. Data:C2370aa6-d913-4bb9-b9ff-f74bd981ea03 | Open Energy Information

    Open Energy Info (EERE)

    consumers including existing single-phase consumers located within the utility's New Mexico service area , requiring transformer capacity in excess of 50 KVA, but not more than...

  8. Data:Eb8eebee-35e8-47ae-b054-03168c73bda5 | Open Energy Information

    Open Energy Info (EERE)

    consumers including existing single-phase consumers located within the utility's New Mexico service area , requiring transformer capacity in excess of 50 KVA, but not more than...

  9. Data:1f727004-a035-4343-962e-5a5fd675c789 | Open Energy Information

    Open Energy Info (EERE)

    transformer capacity of 50 KVA or less, for all uses within the utility's New Mexico service area. Purchased Power Cost Adjustment (PPCA) The utility shall, if purchased...

  10. Data:F8001f40-3db9-42c4-b666-0da3a93c535d | Open Energy Information

    Open Energy Info (EERE)

    voltages. Consumers receiving service under this schedule will provide all transformers and take service at 300 KVA or greater. Northern Lights, Inc. will meter accounts...

  11. Data:50bda05d-aad7-4341-8671-3618b3cc6b86 | Open Energy Information

    Open Energy Info (EERE)

    voltages. Consumers receiving service under this schedule will provide all transformers and take service at 300 KVA or greater. Northern Lights, Inc. will meter accounts...

  12. accelerator center part: Topics by E-print Network

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    racks, including transformerpower to the data center computer racks through four 225 kVA transformers, Xu, Tengfang; Greenberg, Steve 2007-01-01 17 Data Center Energy...

  13. Data:63640aea-a408-4b10-bb94-7a1c43a5d0a0 | Open Energy Information

    Open Energy Info (EERE)

    Indiana (Utility Company) Effective date: 20080701 End date if known: Rate name: Tariff F1: 75 to 400 KVA Three Phase Commercial Sector: Commercial Description: The charges...

  14. Data:2bdd1457-2829-42c6-94bf-d9f55280ce21 | Open Energy Information

    Open Energy Info (EERE)

    Public Power Dist Effective date: 20130101 End date if known: Rate name: CROP DRYING Sector: Commercial Description: kVA Charge Source or reference: http:...

  15. Microsoft Word - PR-10085844 NEPA.docx

    Broader source: Energy.gov (indexed) [DOE]

    PR-10085844 Title: Replace BC 500 KVA Power Transformer Description: Subcontractor shall provide all labor, supervision, tools, equipment, and transportation required to procure,...

  16. Data:Bdffb5a8-253d-4921-be61-29efb22e35ab | Open Energy Information

    Open Energy Info (EERE)

    SERVICE (CONSUMER OWNED) Sector: Commercial Description: Available to all irrigation pumping consumers within the utility's service area, requiring 50kVA and over of transformer...

  17. Data:E4ef5533-822e-4638-9706-4e2a7283d889 | Open Energy Information

    Open Energy Info (EERE)

    and use incidental thereto, including service to phase converters used to power pivot irrigation systems, supplied through one meter and requiring 50 kVA or less transformer...

  18. Type A Accident Investigation Board report on the January 17, 1996, electrical accident with injury in Technical Area 21 Tritium Science and Fabrication Facility Los Alamos National Laboratory. Final report

    SciTech Connect (OSTI)

    NONE

    1996-04-01T23:59:59.000Z

    An electrical accident was investigated in which a crafts person received serious injuries as a result of coming into contact with a 13.2 kilovolt (kV) electrical cable in the basement of Building 209 in Technical Area 21 (TA-21-209) in the Tritium Science and Fabrication Facility (TSFF) at Los Alamos National Laboratory (LANL). In conducting its investigation, the Accident Investigation Board used various analytical techniques, including events and causal factor analysis, barrier analysis, change analysis, fault tree analysis, materials analysis, and root cause analysis. The board inspected the accident site, reviewed events surrounding the accident, conducted extensive interviews and document reviews, and performed causation analyses to determine the factors that contributed to the accident, including any management system deficiencies. Relevant management systems and factors that could have contributed to the accident were evaluated in accordance with the guiding principles of safety management identified by the Secretary of Energy in an October 1994 letter to the Defense Nuclear Facilities Safety Board and subsequently to Congress.

  19. Final environmental impact statement, Washington Water Power/B.C. Hydro Transmission Interconnection Project

    SciTech Connect (OSTI)

    Not Available

    1992-10-01T23:59:59.000Z

    Washington Water Power (WWP) proposes to construct and operate an electric transmission line that would connect with the electrical system of the British Columbia Hydro and Power Authority (B.C. Hydro). The project would be composed of a double-circuit, 230-kilovolt (kV) transmission line from WWP`s existing Beacon Substation located northeast of Spokane, Washington to the international border located northwest of Metaline Falls, Washington. The original Presidential permit application and associated proposed route presented in the draft environmental impact statement (DEIS) have been modified to terminate at the Beacon Substation, instead of WWP`s initially proposed termination point at the planned Marshall Substation located southwest of Spokane. A supplemental draft EIS was prepared and submitted for review to not only examine the new proposed 5.6 miles of route, but to also compare the new Proposed Route to the other alternatives previously analyzed in the DEIS. This final EIS (FEIS) assesses the environmental effects of the proposed transmission line through construction, operation, maintenance, and abandonment activities and addresses the impacts associated with the Proposed Action, Eastern Alternative, Western Alternative, Northern Crossover Alternative, Southern Crossover Alternative, and No Action Alternative. The FEIS also contains the comments received and the responses to these comments submitted on the DEIS and Supplemental DEIS.

  20. (Bradfield Electric and Alaska Power Authority Presidential permit): Finding of no significant impact (FONSI)

    SciTech Connect (OSTI)

    Not Available

    1988-01-01T23:59:59.000Z

    The Economic Regulatory Administration (ERA) of the Department of Energy (DOE) is considering an application by Bradfield Electric, Inc. (Bradfield), and the Alaska Power Authority (APA) for a Presidential permit to construct, operate, maintain and connect a 69-kilovolt (kV) transmission line which would extend from the APA's Tyee Lake Hydroelectric Power Project located near Wrangell, Alaska, to a point on the US-Canadian international border just east of the South Fork Craig River. The DOE has reviewed an environmental assessment (EA) prepared by the US Forest Service (USFS) in connection with its issuance of a special use permit to construct the proposed line through the Tongass National Forest. Based on this EA, the USFS issued a decision notice and a finding of no significant impact (FONSI) for the proposed project on May 9, 1988. The DOE is adopting this EA as DOE/EA-0375 in partial satisfaction of its responsibilities under the National Environmental Policy Act of 1969 (NEPA) regarding the issuance of a Presidential permit.

  1. The Cost of Transmission for Wind Energy: A Review of Transmission Planning Studies

    E-Print Network [OSTI]

    Mills, Andrew D.

    2009-01-01T23:59:59.000Z

    500 and 230 kV 765 kV and 800 kV HVDC 500 and 230 kV 500 kVmi) 138 and 345 kV 345 kV 345 kV 345 kV and HVDC 345kV and HVDC 345 kV 345 kV Note: Total transmission cost is

  2. CX-009514: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    the Franklin-Badger Canyon No. 2 and Grandview-Red Mountain No. 1 115 kilovolt transmission lines. CX-009514.pdf More Documents & Publications CX-005673: Categorical Exclusion...

  3. CX-000200: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    the Chandler Municipal Court with high efficiency windows, Installation of LED (light-emitting diode) Exterior Parking Lot, Walkilowattay and Area Lighting, Install kilovolt AR...

  4. EIS-0422: EPA Notice of Availability of the Draft Environmental...

    Broader source: Energy.gov (indexed) [DOE]

    Line, Garfield, Columbia and Walla Walla Counties, Washington. Notice of Availability of the Draft Environmental Impact Statement Central Ferry-Lower Monumental 500-kilovolt...

  5. EIS-0389: EPA Notice of Availability of the Final Environmental...

    Broader source: Energy.gov (indexed) [DOE]

    60-Kilovolt Power Transmission Facilities, Trinity County, California Notice of Availability for the Final Environmental Impact Statement for the Trinity Public Utilities...

  6. Categorical Exclusion Determinations: Western Area PowerAdministratio...

    Energy Savers [EERE]

    Mountain Region May 1, 2014 CX-012073: Categorical Exclusion Determination Big George-Heart Mountain 69-Kilovolt Transmission Line Glendale Tap Replacement (Amended) CX(s)...

  7. EIS-0285-SA-62: Supplement Analysis | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    Rocky Reach - Maple Valley No. 1 Transmission Line Right of Way from structure 982 to structure 1101. The transmission line is a 500 kilovolt line (April 2002). Supplement...

  8. CX-011621: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    Determination CX-011621: Categorical Exclusion Determination Windy Gap-Granby Pumping Plant and Granby Pumping Plant-Mary's Lake (West Portal) 69-kilovolt Transmission...

  9. New Switches for Utility-Scale Inverters: First In-Class Demonstration of a Completely New Type of SiC Bipolar Switch (15kV-20kV) for Utility-Scale Inverters

    SciTech Connect (OSTI)

    None

    2011-12-31T23:59:59.000Z

    Solar ADEPT Project: The SiCLAB is developing a new power switch for utility-scale PV inverters that would improve the performance and significantly reduce the size, weight, and energy loss of PV systems. A power switch controls the electrical energy flowing through an inverter, which takes the electrical current from a PV solar panel and converts it into the type and amount of electricity that is compatible with the electric grid. SiCLAB is using silicon carbide (SiC) semiconductors in its new power switches, which are more efficient than the silicon semiconductors used to conduct electricity in most conventional power switches today. Switches with SiC semiconductors can operate at much higher temperatures, as well as higher voltage and power levels than silicon switches. SiC-based power switches are also smaller than those made with silicon alone, so they result in much smaller and lighter electrical devices. In addition to their use in utility-scale PV inverters, SiCLAB’s new power switches can also be used in wind turbines, railways, and other smart grid applications.

  10. Full expandable model of parallel self-excited induction generators

    E-Print Network [OSTI]

    Simões, Marcelo Godoy

    possibilities for incorporating advanced control to monitor and optimise a parallel installation of SEIGs and small induction motors. Typically, generators rated 15kVA are cost effective; but 100kVA [4] was found, the trend has changed from installing a few wind turbines to planning large wind farm installations

  11. Structure of a Ca 2+ /CaM:Kv7.4 (KCNQ4) B-Helix

    E-Print Network [OSTI]

    Lim, Wendell

    Qiang Xu1 , Aram Chang1 , Alexandra Tolia1 and Daniel L. Minor Jr.1,2,3,4 1 - Cardiovascular Research 94720, USA Correspondence to Daniel L. Minor: daniel.minor@ucsf.edu http://dx.doi.org/10.1016/j.jmb.2012 elusive. Here, we show that both apo-CaM and Ca2+ /CaM bind to the C-terminal tail of the neuronal channel

  12. Performance of a technical and economical feasibility study of an HVDC compressed gas insulated transmission line. [600 kV

    SciTech Connect (OSTI)

    LaBarge, R.L.

    1980-12-15T23:59:59.000Z

    Progress in evaluating the technical feasibility of SF/sub 6/-insulated cables and circuit breakers for HVDC systems is reported. During this reporting period a new test setup was completed. An assembly jig was designed and fabricated. Model cable up to 20-ft length can be assembled complete outside the test tank. Components to extend the test tank to accommodate a 20-ft model cable have been obtained. A report was drafted on the effect of material selection as well as processing into insulators on the long-term dielectric performance of the insulator. The vertical leaf expansion joint design was improved by replacing the Alcuplate copper-to-aluminum transition piece with nickel plating on the aluminum parts. The joint was fatigue tested with condition which simulate almost 2 1/2 cycles of temperature excursions each day for the 40 year design life of the line. Electrical tests of the joint are in progress.

  13. Evaluation of 230 kV HPFF pipe-type cable with wrinkled and creased insulating tapes

    SciTech Connect (OSTI)

    Seman, G.W.; Katz, C. [Cable Technology Labs., Inc., New Brunswick, NJ (United States)] [Cable Technology Labs., Inc., New Brunswick, NJ (United States); Pancholi, S.V. [Potomac Electric Power Co., Washington, DC (United States)] [Potomac Electric Power Co., Washington, DC (United States)

    1995-01-01T23:59:59.000Z

    Severe collapse wrinkles and circumferential creases were discovered in the cellulose paper insulating tapes of a newly installed IIPFF pipe-type cable during splicing and terminating. An evaluation program was developed to assess the electrical and mechanical integrity of the cable having wrinkled and creased insulating tapes. The test results indicated that the cable would perform satisfactorily in service.

  14. THE INSTITUTE FOR SOLID STATE PHYSICS 2013 51.3MW 2.7kV

    E-Print Network [OSTI]

    Katsumoto, Shingo

    A picture of the largest flywheel DC generator. This generator can supply the maximum energy of 210 MJ

  15. EIS-0079: 300-kV International Submarine Transmission Line- Erie, Pennsylvania to Nanticoke, Ontario, Canada General Public Utilities Corporation

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy Office of Energy Emergency Operations developed this statement to assess the potential environmental and socioeconomic impacts of the construction and operation of 44 miles of cable between the Erie West Substation and the Canadian border.

  16. EA-2002: Right-of-Way Application for the Tucson-Apache 115-kV Transmission

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742Energy China U.S.ContaminationJulySavannah River Site for Use by the State of SouthLine, Pima

  17. EIS-0101: Thermopolis, Alcova, Casper Transmission Line Project

    Broader source: Energy.gov [DOE]

    The Western Area Power Administration developed this statement to evaluate the environmental impacts of constructing, operating and maintaining a 230-kilovolt transmission line between Thermopolis, Wyoming, and Alcova, Wyoming, and a 230/345-kilovolt transmission line between Alcova, Wyoming, and Casper, Wyoming.

  18. The Cost of Transmission for Wind Energy in the United States: A Review of Transmission Planning Studies.

    E-Print Network [OSTI]

    Wiser, Ryan

    2014-01-01T23:59:59.000Z

    kV JCSP 765 kV and 800 kV HVDC Southern California Edison (2 345 kV ERCOT - TOS - 3 345 kV and HVDC ERCOT - TOS - 4345 kV and HVDC Southwest Power Pool (SPP) SPP - 2 345 kV

  19. SU-E-J-103: Setup Errors Analysis by Cone-Beam CT (CBCT)-Based Imaged-Guided Intensity Modulated Radiotherapy for Esophageal Cancer

    SciTech Connect (OSTI)

    Yang, H; Wang, W; Hu, W; Chen, X; Wang, X; Yu, C [Taizhou Hospital, Wenzhou Medical College, Taizhou, Zhejiang (China)

    2014-06-01T23:59:59.000Z

    Purpose: To quantify setup errors by pretreatment kilovolt cone-beam computed tomography(KV-CBCT) scans for middle or distal esophageal carcinoma patients. Methods: Fifty-two consecutive middle or distal esophageal carcinoma patients who underwent IMRT were included this study. A planning CT scan using a big-bore CT simulator was performed in the treatment position and was used as the reference scan for image registration with CBCT. CBCT scans(On-Board Imaging v1. 5 system, Varian Medical Systems) were acquired daily during the first treatment week. A total of 260 CBCT scans was assessed with a registration clip box defined around the PTV-thorax in the reference scan based on(nine CBCTs per patient) bony anatomy using Offline Review software v10.0(Varian Medical Systems). The anterior-posterior(AP), left-right(LR), superiorinferior( SI) corrections were recorded. The systematic and random errors were calculated. The CTV-to-PTV margins in each CBCT frequency was based on the Van Herk formula (2.5?+0.7?). Results: The SD of systematic error (?) was 2.0mm, 2.3mm, 3.8mm in the AP, LR and SI directions, respectively. The average random error (?) was 1.6mm, 2.4mm, 4.1mm in the AP, LR and SI directions, respectively. The CTV-to-PTV safety margin was 6.1mm, 7.5mm, 12.3mm in the AP, LR and SI directions based on van Herk formula. Conclusion: Our data recommend the use of 6 mm, 8mm, and 12 mm for esophageal carcinoma patient setup in AP, LR, SI directions, respectively.

  20. HEMP-induced transients in electric power substations

    SciTech Connect (OSTI)

    Wiggins, C.M.; Thomas, D.E.; Salas, T.M. (BDM International, Inc., Albuquerque, NM (United States))

    1992-02-01T23:59:59.000Z

    A nuclear detonation in or above the earth's atmosphere produces an intense electromagnetic pulse (EMP). A large portion of the EMP electromagnetic energy is within the RF spectrum. A detonation at high altitudes above 40 km produces an EMP called high-altitude EMP (HEMP). HEMP is a steep-front short duration transient with a rise time on the order of a few nanoseconds which decays to near zero in less than a microsecond. A single high-altitude burst can subject much of the continental United States to intense HEMP electric fields on the order of tens of kilovolts per meter. The intense transient HEMP will induce fast transients in high-voltage transmission lines and bus structures, instrumentation cables, and control wires in power transmission and distribution (T D) substations. A system of traveling wave coupling models for a 500 kV substation, including models for the high voltage primary bus, components (circuit breakers, disconnect switches, power transformers, and current and voltage instrument transformers), low voltage control wiring circuits, and a number of conducted and radiated interference coupling modes, had been developed earlier by EPRI. These EPRI served as the baseline for the present HEMP coupling investigations. The HEMP effects on protective relays were assessed for a nominal HEMP environment using several new field coupling models merged with the switching transient data. It is found that a representative solid state relay is unlikely to be damaged or to misoperate by the nominal HEMP threat with a peak field strength of 50 kV/m. However, it is possible for both DC control wires to flash over to ground simultaneously, causing fuses to blow and placing the relay in an inoperative state.

  1. HEMP-induced transients in electric power substations. Final report

    SciTech Connect (OSTI)

    Wiggins, C.M.; Thomas, D.E.; Salas, T.M. [BDM International, Inc., Albuquerque, NM (United States)

    1992-02-01T23:59:59.000Z

    A nuclear detonation in or above the earth`s atmosphere produces an intense electromagnetic pulse (EMP). A large portion of the EMP electromagnetic energy is within the RF spectrum. A detonation at high altitudes above 40 km produces an EMP called high-altitude EMP (HEMP). HEMP is a steep-front short duration transient with a rise time on the order of a few nanoseconds which decays to near zero in less than a microsecond. A single high-altitude burst can subject much of the continental United States to intense HEMP electric fields on the order of tens of kilovolts per meter. The intense transient HEMP will induce fast transients in high-voltage transmission lines and bus structures, instrumentation cables, and control wires in power transmission and distribution (T & D) substations. A system of traveling wave coupling models for a 500 kV substation, including models for the high voltage primary bus, components (circuit breakers, disconnect switches, power transformers, and current and voltage instrument transformers), low voltage control wiring circuits, and a number of conducted and radiated interference coupling modes, had been developed earlier by EPRI. These EPRI served as the baseline for the present HEMP coupling investigations. The HEMP effects on protective relays were assessed for a nominal HEMP environment using several new field coupling models merged with the switching transient data. It is found that a representative solid state relay is unlikely to be damaged or to misoperate by the nominal HEMP threat with a peak field strength of 50 kV/m. However, it is possible for both DC control wires to flash over to ground simultaneously, causing fuses to blow and placing the relay in an inoperative state.

  2. Environmental Assessment and Finding of No Significant Impact: Wind Energy Center Edgeley/Kulm Project, North Dakota

    SciTech Connect (OSTI)

    N /A

    2003-04-15T23:59:59.000Z

    The proposed Edgeley/Kulm Project is a 21-megawatt (MW) wind generation project proposed by Florida Power and Light (FPL) Energy North Dakota Wind LLC (Dakota Wind) and Basin Electric Power Cooperative (Basin). The proposed windfarm would be located in La Moure County, south central North Dakota, near the rural farming communities of Kulm and Edgeley. The proposed windfarm is scheduled to be operational by the end of 2003. Dakota Wind and other project proponents are seeking to develop the proposed Edgeley/Kulm Project to provide utilities and, ultimately, electric energy consumers with electricity from a renewable energy source at the lowest possible cost. A new 115-kilovolt (kV) transmission line would be built to transmit power generated by the proposed windfarm to an existing US Department of Energy Western Area Power Administration (Western) substation located near Edgeley. The proposed interconnection would require modifying Western's Edgeley Substation. Modifying the Edgeley Substation is a Federal proposed action that requires Western to review the substation modification and the proposed windfarm project for compliance with Section 102(2) of the National Environmental Policy Act (NEPA) of 1969, 42 U.S.C. 4332, and Department of Energy NEPA Implementing Procedures (10 CFR Part 1021). Western is the lead Federal agency for preparation of this Environmental Assessment (EA). The US Fish and Wildlife Service (USFWS) is a cooperating agency with Western in preparing the EA. This document follows regulation issued by the Council on Environmental Quality (CEQ) for implementing procedural provisions of NEPA (40 CFR 1500-1508), and is intended to disclose potential impacts on the quality of the human environment resulting from the proposed project. If potential impacts are determined to be significant, preparation of an Environmental Impact Statement would be required. If impacts are determined to be insignificant, Western would complete a Finding of No Significant Impact (FONSI). Environmental protection measures that would be included in the design of the proposed project are included.

  3. Microsoft Word - CX_McNaryEquipmentAcquisition.doc

    Broader source: Energy.gov (indexed) [DOE]

    disconnect switches; one set of three 230-kV rod gaps, one set of three 230-kV transformers, one single phase 230-kV voltage transformer, and one 230-kV dead-end tower; ...

  4. Data:A4f836c3-dfd7-4306-ac1f-4b7c8a65d34e | Open Energy Information

    Open Energy Info (EERE)

    350kVA or more of transformer capacity; located on or near the Cooperative's transmission lines for all types of commercial usage; subject to the established rules and...

  5. Data:74b61b34-dce2-429a-92e7-ef15b5c8880a | Open Energy Information

    Open Energy Info (EERE)

    requiring 50kVA or more of transformer capacity. This rate is not applicable to CBM compression loads with individual motors of 1000HP or greater. Demand Charge: First 50kW...

  6. Data:Ecbd7933-8804-446e-a809-8cbba6f34984 | Open Energy Information

    Open Energy Info (EERE)

    requiring 50kVA or more of transformer capacity. This rate is not applicable to CBM compression loads with individual motors of 1000HP or greater. Demand Charge: First 50kW...

  7. Data:910e19eb-ab7d-4314-b115-eec540d3e0b0 | Open Energy Information

    Open Energy Info (EERE)

    voltage, or single phase when three phase is not readily available, and 50 KVA or more of installed transformer capacity is required, subject to the rules and regulations of the...

  8. Data:B71b46ca-7967-4ad4-8940-8369d98fd91a | Open Energy Information

    Open Energy Info (EERE)

    three-phase lines requiring >50 KVA and where the starting current of the largest motor does not exceed 260 amperes for all uses, subject to the rules and regulations and...

  9. Data:0115b145-e9cb-4de7-b2a4-a3fb994175e8 | Open Energy Information

    Open Energy Info (EERE)

    capacity does not exceed 75 KVA and where the starting current of the largest motor does not exceed 260 amperes for all uses, and subject to the rules, regulations and...

  10. Data:6ba75dd9-3248-4d00-b56f-31cd3927d356 | Open Energy Information

    Open Energy Info (EERE)

    capacity does not exceed 75 KVA and where the starting current of the largest motor does not exceed 260 amperes for all uses, and subject to the rules, regulations and...

  11. Data:B6999398-d83a-479b-9cd3-061c4491fed3 | Open Energy Information

    Open Energy Info (EERE)

    Sector: Commercial Description: To single-phase farm service with a total connected motor capacity not to exceed 10 HP and to single-phase church service under 25 kVA. Source...

  12. Data:D58b8819-886b-489c-95b0-988754992fe3 | Open Energy Information

    Open Energy Info (EERE)

    farm installations requiring >50 KVA and where the starting current of the largest motor does not exceed 260 amperes for all uses, subject to the rules and regulations and...

  13. Data:0318c2f2-e1f7-453c-b78d-7be37aca21e1 | Open Energy Information

    Open Energy Info (EERE)

    50 KVA or less of transformer capacity and the starting current of the largest motor does not exceed 260 amperes. Source or reference: www.cceci.com Source Parent:...

  14. Data:82d535e4-c2ee-45f2-a514-e1e2dafa8c68 | Open Energy Information

    Open Energy Info (EERE)

    Description: Available in OTEC service territory for non-residential service requiring 50 kVA or less of transformer capacity, subject to policies as established by the Board of...

  15. Language Socialization and Linguistic Ideologies Among Israeli Emissaries in the United States

    E-Print Network [OSTI]

    Kattan, Shlomy

    2010-01-01T23:59:59.000Z

    ze lo nira li tiv(i ledabe! itam anglit. ani lo xo&evet &ehatxala kva! hitxaltem ledabe! itam al ha ma(ava! ve le&atef

  16. Data:A8480fe7-91e9-4770-adf4-6789c6331ecb | Open Energy Information

    Open Energy Info (EERE)

    electric service and monthly demand less than one hundred kilowatts. Applicable to rate codes 330, 380, 383, 385, 386 and 390. The minimum monthly rate shall be 90.00 where KVA...

  17. 2009 Wind Technologies Market Report

    E-Print Network [OSTI]

    Wiser, Ryan

    2010-01-01T23:59:59.000Z

    generating sets. Wind turbine blades, hubs, generators,wind turbine components that include towers (trade category is “towers and lattice masts”), generators (“AC generators from 750 to 10,000 kVA”), blades

  18. Data:027dd384-9b6e-4868-922a-59fba76330c2 | Open Energy Information

    Open Energy Info (EERE)

    Charge shall be the higher of: 1) the basic charge 2) 0.80 per KVA of installed transformer capacity 3) contract minimum kWh << Previous 1 2 3 Next >> Category:Categories...

  19. Data:936f8c8a-61c8-4359-bb84-e5ffd58bd024 | Open Energy Information

    Open Energy Info (EERE)

    Sector: Industrial Description: Rayburn Country Electric Co-op Rate Wholesale Power Cost (WPC). 3000 kVa or greater. No kWh fee. Source or reference: Rates Binder A Source...

  20. Data:Cf9a88ed-a6a8-464b-bb9c-9a11291d8f7e | Open Energy Information

    Open Energy Info (EERE)

    to the established Service Rules and Regulations of the Corporation. Subject to wholesale power cost adjustment. Facilities Charge @ 75.0 per kVA of required transformer capacity...

  1. Data:61694012-c5fc-471a-9956-7079918634eb | Open Energy Information

    Open Energy Info (EERE)

    20140401 End date if known: Rate name: Commercial Single-Phase Up To 200 Amps Sector: Commercial Description: *Non-residential buildings drawing up to 200 Amps 100 kVa and...

  2. Data:E96ffce4-411e-44e0-bf12-ed3b14542919 | Open Energy Information

    Open Energy Info (EERE)

    50 KVA of transformer capacity, for all rural and town uses within the utility's New Mexico service area. The capacity of individual motors served under this schedule shall not...

  3. Data:2e4d1360-a722-4a11-8b49-7ac13fbd2e0b | Open Energy Information

    Open Energy Info (EERE)

    50 KVA of transformer capacity, for all rural and town uses within the utility's New Mexico service area. The capacity of individual motors served under this schedule shall not...

  4. Data:12ff2eb2-e571-4dae-a172-de4af0d12da4 | Open Energy Information

    Open Energy Info (EERE)

    with 100 KVA or more of installed capacity, the measured KWH shall be increased by 0.5% for each 1% by which the average monthly power factor is less than 90% lagging. kWh <<...

  5. Data:9728c02f-8f21-46f6-b45c-c1f9ddf58f4b | Open Energy Information

    Open Energy Info (EERE)

    kVA or less of required transformer capacity, within the District's service area that use electricity as the exclusive source of energy for all normal uses. Qualification for this...

  6. Data:7d633875-30f9-4b39-ad8e-dc7963ccbbf7 | Open Energy Information

    Open Energy Info (EERE)

    kVA, the electrical energy furnished is metered on the primary side of the service transformers at NineStar Connect's option, and NineStar Connect owns the service transformers....

  7. Data:8c9cbc1e-63fd-4837-bbd9-6b92ab85d252 | Open Energy Information

    Open Energy Info (EERE)

    kVA, the electrical energy furnished is metered on the primary side of the service transformers at NineStar Connect's option, and NineStar Connect owns the service transformers....

  8. Data:8b36a8ae-e653-4d6b-82e9-2ad633a4b458 | Open Energy Information

    Open Energy Info (EERE)

    to all existing large power off peak customers as of the date of approval of this tariff and new customers requiring 300 kVA or less of transformer capacity with a monthly...

  9. Data:57a1d5e6-ade3-43dd-8317-aab9ead27fc8 | Open Energy Information

    Open Energy Info (EERE)

    Available for general service customers. Customer's monthly billing demands under this tariff shall not be less than 600 kVA. The customer shall contract for a sufficient capacity...

  10. Data:1de7908a-39f3-461c-a223-d1c2ef630ee9 | Open Energy Information

    Open Energy Info (EERE)

    Available for general service customers. Customer's monthly billing demands under this tariff shall not be less than 600 kVA. The customer shall contract for a sufficient capacity...

  11. Data:186ae1fe-40c1-41b6-8407-2a2c9ce45702 | Open Energy Information

    Open Energy Info (EERE)

    Available for general service customers. Customer's monthly billing demands under this tariff shall not be less than 600 kVA. The customer shall contract for a sufficient capacity...

  12. Data:19e67ce4-bbf3-483f-bb6a-cf52c3c6095a | Open Energy Information

    Open Energy Info (EERE)

    County Rural E M C Effective date: 20120201 End date if known: Rate name: Schedule LP3- Electric general Power Service Sector: Commercial Description: upto 500 kVA Source or...

  13. Data:77d51886-cf69-4292-b552-dda45624b306 | Open Energy Information

    Open Energy Info (EERE)

    20140101 End date if known: Rate name: Small Time-of-Use (STU) Single Phase, (200 amp15 kVA or less) Sector: Residential Description: Min. 10 kW storage heating equipment...

  14. Data:Cccda483-92ff-44ee-99e7-046c25d034a7 | Open Energy Information

    Open Energy Info (EERE)

    Up To 200 Amps Sector: Residential Description: *applies to homes with up to a 200 Amp service 100 kVa and under Source or reference: http:www.co-mo.coopbusOurRates.aspx...

  15. Data:D1ed09af-4519-42b2-9073-dc7fce0fd819 | Open Energy Information

    Open Energy Info (EERE)

    date: 20140101 End date if known: Rate name: Small Time-of-Use (STU) Three Phase, (200 amp30 kVA or less) Sector: Residential Description: Min. 10 kW storage heating equipment -...

  16. Data:8d9e38f5-6312-4ef0-a7ea-9f7c24286287 | Open Energy Information

    Open Energy Info (EERE)

    name: Three-Phase (Under 100 kva) Sector: Description: Source or reference: ISU Documentation Source Parent: Comments Applicability Demand (kW) Minimum (kW): Maximum (kW):...

  17. Data:8f232e3e-55e1-4ebc-98d8-af654c7bde08 | Open Energy Information

    Open Energy Info (EERE)

    Single-Phase Service (Under 100 kva) Sector: Description: Source or reference: ISU Documentation Source Parent: Comments Applicability Demand (kW) Minimum (kW): Maximum (kW):...

  18. Data:01cd329c-2121-43e7-a055-2a524e953500 | Open Energy Information

    Open Energy Info (EERE)

    Non-residential with monthly demand under 125 kVa. Source or reference: ISU Documentation Rate Binder Ted 12 Source Parent: Comments Applicability Demand (kW) Minimum...

  19. Intern experience at Electricity Directorate of Bahrain: an internship report

    E-Print Network [OSTI]

    Aljamea, Najeeb Ahmad

    2013-03-13T23:59:59.000Z

    n ......................................27 8. A VDU Picture of a Substation .............................................................. 35 9. A VDU Picutre of the Alarm List................................................................ 38 10... consists of : - Over-head lines : 33kv &66kv - Underground cables : 33kv & 66kv & 220kv - Substations: 33 /llkv & 66 /llkv & 220/66kv. Associated with this equipment is a protection system which utilises a network of pilot cables. The transmission...

  20. Volume II solicitation package for solicitation no. 522887-5422 {open_quotes}site electrical replacements & substation{close_quotes} subproject: 69 KV substation

    SciTech Connect (OSTI)

    NONE

    1991-05-03T23:59:59.000Z

    This solicitation is for the U.S. Department of Energy under Prime Contract No. DE-AC04-88-DP43495 with EG&G Mound Applied Technologies. Ohio Sales or Use taxes are not to be included in the proposal price. Applicable taxes due or owing to the State of Ohio will be paid by the buyer under Direct Payment Permit No. 98-002230. Refer to Form ML-2487, General Provisions, Article 24, {open_quotes}Federal, State & Local Taxes{close_quotes}. Sellers are advised that purchases of building and construction materials for incorporation into a structure or improvement to a real property which is accepted for ownership by the United States or one of its agencies are exempt from Ohio Sales and Use taxes. Unnecessarily elaborate brochures or other presentations beyond those sufficient to present a complete and effective response to this solicitation are not desired and may be construed as an indication of the seller`s lack of cost consciousness. Elaborate art work, expensive paper and binding, and expensive visual and other presentation aids are neither necessary nor wanted.

  1. Mutation in the Kv3.3 Voltage-Gated Potassium Channel Causing Spinocerebellar Ataxia 13 Disrupts Sound-Localization Mechanisms

    E-Print Network [OSTI]

    2013-01-01T23:59:59.000Z

    generation III) and grand-children (generation IV) [11].19 members of generations II, III, and IV, 13 of whom were

  2. Design and Construction of a150kV/300A/1s Blumlein Pulser J.O. ROSSI, M. UEDA and J.J. BARROSO

    E-Print Network [OSTI]

    of the shield cable impedance that contributes to the power loss of the device and the requirement of long of the jacket be larger, reducing the output current and, thus, #12;contributing less to the overall power loss

  3. EA-0587: Proposed Amendment to Presidential Permit PP-63 and Associated Modification to 500 kV International Transmission Line: Forbes, Minnesota to Manitoba, Canada

    Broader source: Energy.gov [DOE]

    This EA evaluates the environmental impacts of Northern States Power Company's  proposal to expand the Forbes Substation in Minnesota.

  4. Type B Accident Investigation Board Report on the July 25, 1997, Contract Brush Cutter Injury on the Ashe-Marion #2 500 kV Line

    Broader source: Energy.gov [DOE]

    On July 25, 1997, at 1205 hours, a contract hand brush cutter was seriously injured when he felled a tree close to a Bonneville Power Administration energized transmission power line, located within a BPA transmission-line corridor.

  5. high-resolution transmission electron microscope operating at 200 kV; and photoluminescence (PL) spectra recorded on a Renishaw 2000 with an Ar ion

    E-Print Network [OSTI]

    Zubarev, Eugene

    , 40, 1861. [11] J. Hu, L.-S. Li, W. Yang, L. Manna, L.-W. Wang, A. P. Alivisatos, Science 2001, 292. [13] V. F. Puntes, K. M. Krishnan, A. P. Alivisatos, Science 2001, 291, 2115. [14] X. Duan, Y. Huang, 1389. [19] X. Peng, L. Manna, W. Yang, J. Wickham, E. Scher, A. Kadavanich, A. P. Alivisatos, Nature

  6. EIS-0339: Presidential Permit Application, GenPower 500 kV Submarine Electric Transmission Cable from Nova Scotia to New York

    Broader source: Energy.gov [DOE]

    The Department of Energy (DOE) announced its intent to prepare an Environmental Impact Statement (EIS) in accordance with the National Environmental Policy Act of 1969 (NEPA) for GenPower New York, L.L.C.’s (GenPower) request for a Presidential permit for a proposed international electric transmission line.

  7. EA-1899: Rerouting and Renovating of Estes-Flatiron Three Transmission Lines to Double Circuit 115-kV, Larimer County, Colorado

    Broader source: Energy.gov [DOE]

    DOE’s Western Area Power Administration started to prepare an EA to evaluate the environmental impacts of a proposal to reroute and renovate the Estes-Flatiron Three Transmission Lines in Larimer County, Colorado. Based on comments received during the scoping period, Western ended preparation of DOE/EA-1899 and announced its intent to prepare and environmental impact statement, DOE/EIS-0483.

  8. EA-2002: Right-of-Way Application for the Tucson-Apache 115-kV Transmission Line, Pima County, Arizona

    Broader source: Energy.gov [DOE]

    Western Area Power Administration (Western) and the Bureau of Indian Affairs (BIA), as joint lead agencies, prepared an EA that evaluates the potential environmental impacts of a proposal for BIA to grant Western a 150-foot right-of-way across tribal land along the existing Tucson-Apache Transmission Line to replace the previous 100-foot right-of-way, which has expired.

  9. EIS-0365: Draft Environmental Impact Statement for the Imperial-Mexicali 230-kV Transmission Lines, EIS-0365 (May 2004)

    Broader source: Energy.gov [DOE]

    A U.S. Department of Energy (DOE) Presidential permit is required to construct an electric transmission line across the U.S. international border. On February 27, 2001, Baja California Power, Inc. ...

  10. CX-008389: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    Danger Tree Management on Estes-Pole Hill and Pole Hill-Flatiron 115 Kilovolt Transmission Lines CX(s) Applied: B1.3 Date: 03092012 Location(s): Colorado Offices(s): Western...

  11. CX-008719: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    No. 1, Holcomb- Naselle No. 1, and Raymond-Willapa River No. 1, 115 Kilovolt Transmission Lines CX(s) Applied: B1.3 Date: 05162012 Location(s): Washington Offices(s):...

  12. CX-008708: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    on the Chehalis-Olympia No. 1 and Chehalis-Mayfield No. 1, 115 Kilovolt Transmission Lines CX(s) Applied: B1.3 Date: 05252012 Location(s): Washington, Washington...

  13. Tracking Progress Last updated 06/18/2014 Transmission Expansion 1

    E-Print Network [OSTI]

    issues certificates of public convenience and necessity (CPCNs) for transmission lines at 200 kilovolts of existing transmission lines are issued a notice of exempt construction (NOC) and are exempt from CPUC CEQA

  14. CX-011855: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Henderson 230 Kilovolt Switchyard (Erosion Control) CX(s) Applied: B1.3 Date: 02/06/2014 Location(s): Nevada Offices(s): Western Area Power Administration-Desert Southwest Region

  15. CX-011614: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Curecanti-Blue Mesa 115-kilovolt Transmission Line Danger Tree Management CX(s) Applied: B1.3 Date: 12/04/2013 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  16. CX-011616: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Gore Pass-Kremmling 138-kilovolt Transmission Line Danger Tree Management CX(s) Applied: B1.3 Date: 11/21/2013 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  17. CX-011618: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Kremmling-Windy Gap 138-kilovolt Transmission Line Danger Tree Management CX(s) Applied: B1.3 Date: 11/21/2013 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  18. CX-011208: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Danger Tree Management on Malta-Mount Elbert 230-Kilovolt Transmission Line CX(s) Applied: B1.3 Date: 09/09/2013 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  19. CX-011619: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Muddy Pass-Walden 69-kilovolt Transmission Line Danger Tree Management CX(s) Applied: B1.3 Date: 11/21/2013 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  20. CX-011209: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Archer-North Park 230-Kilovolt Transmission Line Danger Tree Management CX(s) Applied: B1.3 Date: 09/10/2013 Location(s): Colorado, Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  1. CX-010411: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Parker Substation 161 Kilovolt 2013 Breaker Replacement CX(s) Applied: B4.6 Date: 05/17/2013 Location(s): California Offices(s): Western Area Power Administration-Desert Southwest Region

  2. CX-010891: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Archer-Stegall 230-Kilovolt Fiber Optic Ground Wire Addition CX(s) Applied: B4.7 Date: 08/20/2013 Location(s): Nebraska, Nebraska Offices(s): Western Area Power Administration-Rocky Mountain Region

  3. CX-011723: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Happy Jack 230 Kilovolt Substation Fiber Optic Installation in Laramie County, Wyoming CX(s) Applied: B4.7 Date: 12/31/2013 Location(s): Wyoming Offices(s): Western Area Power Administration-Rocky Mountain Region

  4. CX-002435: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Redmond Substation 230-115-Kilovolt Transformer AdditionCX(s) Applied: B4.6Date: 05/07/2010Location(s): Deschutes County, OregonOffice(s): Bonneville Power Administration

  5. CX-008382: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Bridgeport-Sidney 115 Kilovolt Line Rejected Pole Replacement CX(s) Applied: B1.3 Date: 03/16/2012 Location(s): Nebraska Offices(s): Western Area Power Administration-Rocky Mountain Region

  6. EIS-0106: Great Falls-Conrad Transmission Line Project, Montana

    Broader source: Energy.gov [DOE]

    The Western Area Power Administration prepared this EIS to evaluate the environmental impacts of the construction and operation of a 230-kilovolt transmission line from Great Falls, Montana, to Conrad, Montana.

  7. Data:A563ad4a-6f47-40bd-9bfa-d67a6d66a93d | Open Energy Information

    Open Energy Info (EERE)

    which may interfere with service to other customers, or all transformer-type welding machines larger than 25 kilo-volt amperes, will not be served on this rate. Source or...

  8. Data:84e2fa36-5dd3-49d9-9563-8f646c3f8450 | Open Energy Information

    Open Energy Info (EERE)

    which may interfere with service to other customers, or all transformer-type welding machines larger than 25 kilo-volt amperes, will not be served on this rate. Source or...

  9. Data:D03881dc-aa48-4478-8a88-2dfaa2c15d71 | Open Energy Information

    Open Energy Info (EERE)

    equipment which may interfere with service to other customers and all transformer-type welding machines larger than 25 kilovolt amperes will not be served on this rate. Source or...

  10. CX-010889: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Ault-Craig 345-Kilovolt WCMO Danger Tree Management CX(s) Applied: B1.3 Date: 08/14/2013 Location(s): Colorado, Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  11. CX-011204: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Hayden-North Park 230-Kilovolt Transmission Lane Danger Tree Management CX(s) Applied: B1.3 Date: 08/30/2013 Location(s): Colorado, Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  12. CX-012092: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Tucson-Apache 115-Kilovolt Transmission Line Structure Stabilization Project CX(s) Applied: B1.3 Date: 09/06/2013 Location(s): Arizona, Arizona Offices(s): Western Area Power Administration-Desert Southwest Region

  13. CX-008381: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Big Thompson to Flatiron 13.8 Kilovolt Transmission Line Structure Replacement CX(s) Applied: B1.3 Date: 05/09/2012 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  14. CX-011854: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Glen Canyon Substation 345 Kilovolt - Sulfur Hexafluoride and Concrete Pad Installation CX(s) Applied: B4.6 Date: 02/06/2014 Location(s): Arizona Offices(s): Western Area Power Administration-Desert Southwest Region

  15. Quadrennial Energy Review comments

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    345-kilovolt line. It will help move more of our baseload electricity to western North Dakota - and it will help keep the lights on. We started planning for this in 2011 because it...

  16. CX-007985: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Acquisition of Cowlitz County Public Utility District's 115-Kilovolt Transmission Line CX(s) Applied: B1.24 Date: 02/24/2012 Location(s): Washington Offices(s): Bonneville Power Administration

  17. CX-011180: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Shelton-Fairmont Number 2 115-Kilovolt Tap CX(s) Applied: B4.11 Date: 09/12/2013 Location(s): Washington Offices(s): Bonneville Power Administration

  18. CX-012077: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Danger Tree Management on Craig to Hayden 230-Kilovolt Transmission Line CX(s) Applied: B1.3 Date: 04/21/2014 Location(s): Colorado, Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  19. CX-012086: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Wray-Wray Tap 115-Kilovolt Transmission Line Construction CX(s) Applied: B4.12 Date: 02/28/2014 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  20. CX-012078: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Danger Tree Management on the Great Cut Tap 115-Kilovolt Transmission Line CX(s) Applied: B1.3 Date: 02/20/2014 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  1. CX-012072: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Archer-Cheyenne North/South 115-kilovolt Transmission Line Structure Replacement CX(s) Applied: B4.13 Date: 03/18/2014 Location(s): Wyoming Offices(s): Western Area Power Administration-Rocky Mountain Region

  2. CX-012084: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Snowy Range-Happy Jack 115-Kilovolt Transmission Line Structure Replacements CX(s) Applied: B1.3 Date: 03/10/2014 Location(s): Wyoming Offices(s): Western Area Power Administration-Rocky Mountain Region

  3. EA-0962: Final Environmental Assessment

    Broader source: Energy.gov [DOE]

    Construction and Routine Operation of a 12-kilovolt Overhead Powerline and Formal Authorization for a 10-inch and 8-inch Fresh Water Pipeline Right-of-Way at Naval Petroleum Reserve No. 1, Kern County, California

  4. CX-006303: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Interconnection of the Pronghorn Gas Plant 115 Kilovolt Transmission LineCX(s) Applied: B4.11Date: 07/14/2011Location(s): MontanaOffice(s): Western Area Power Administration-Upper Great Plains Region

  5. EIS-0332: McNary-John Day Transmission Line Project, OR

    Broader source: Energy.gov [DOE]

    This EIS analyzes BPA's decision to construct, operate, and maintain a 79-mile-long 500-kilovolt transmission line in Benton and Klickitat Counties, Washington, and Umatilla and Sherman counties, Oregon.

  6. CX-008685: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Big Eddy – Troutdale No. 1 230 Kilovolt Transmission Line Upgrade CX(s) Applied: B4.13 Date: 07/11/2012 Location(s): Oregon, Oregon, Oregon Offices(s): Bonneville Power Administration

  7. CX-008704: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Grand Coulee-Bell No. 3 Double Circuit 230 Kilovolt Transmission Line Reconductoring Project CX(s) Applied: B1.3 Date: 05/31/2012 Location(s): Washington, Washington, Washington Offices(s): Bonneville Power Administration

  8. EIS-0398: Delta-Mendota Canal/California Aqueduct Intertie (DCI) Project

    Broader source: Energy.gov [DOE]

    This EIS analyzes WAPA's decision to authorize a new interconnection and design, construct, operate, and maintain a new 69-kilovolt transmission line as part of the Delta-Mendota Canal Intertie Project.

  9. CX-012735: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Davis Dam Maintenance Building Installation at the old Davis Dam 69 Kilovolt West Switchyard CX(s) Applied: B4.11Date: 41820 Location(s): ArizonaOffices(s): Western Area Power Administration-Desert Southwest Region

  10. CX-012741: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Liberty-Westwing 230 Kilovolt Transmission Line Insulator Replacement CX(s) Applied: B1.3Date: 41795 Location(s): ArizonaOffices(s): Western Area Power Administration-Desert Southwest Region

  11. CX-012734: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Bouse Hills Pumping Plant to Harcuvar 115 Kilovolt Transmission Line, Inset Structure Installation CX(s) Applied: B4.6Date: 41878 Location(s): ArizonaOffices(s): Western Area Power Administration-Desert Southwest Region

  12. CX-011644: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Bryan Mound Substation Upgrade to 138 Kilovolts CX(s) Applied: B1.3 Date: 12/17/2013 Location(s): Texas Offices(s): Strategic Petroleum Reserve Field Office

  13. CX-010098: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Phoenix to Lone Butte 230 Kilovolt Transmission Line, Bird Diverter Installation CX(s) Applied: B1.3 Date: 04/08/2013 Location(s): CX: none Offices(s): Western Area Power Administration-Desert Southwest Region

  14. CX-004258: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Replace Spacer Dampers Along the Ostrander-McLaughlin Number 1 500-Kilovolt Transmission LineCX(s) Applied: B1.3Date: 09/29/2010Location(s): Clackamas County, OregonOffice(s): Bonneville Power Administration

  15. CX-005131: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Spacer-Damper Replacements on the Captain Jack-Malin 500-kilovolt Transmission LineCX(s) Applied: B1.3Date: 01/24/2011Location(s): Klamath County, OregonOffice(s): Bonneville Power Administration

  16. CX-004256: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Replace Spacer Dampers Along the Dworshak PH-Dworshak Number 1 500-Kilovolt Transmission LineCX(s) Applied: B1.3Date: 10/05/2010Location(s): Clearwater County, IdahoOffice(s): Bonneville Power Administration

  17. CX-001944: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Replace Spacer Dampers Along the Grizzly - Captain Jack No. 1 500 Kilovolt Transmission LineCX(s) Applied: B1.3Date: 04/21/2010Location(s): Crook County, OregonOffice(s): Bonneville Power Administration

  18. CX-004257: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Replace Spacer Dampers Along the Slatt-John Day Number 1 500-Kilovolt Transmission LineCX(s) Applied: B1.3Date: 10/04/2010Location(s): Sherman County, OregonOffice(s): Bonneville Power Administration

  19. CX-010886: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Curecanti-Lost Canyon 230-Kilovolt Emergency Repairs of Downed Conductor CX(s) Applied: B1.3 Date: 08/06/2013 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  20. CX-011648: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Davis-Parker 230 Kilovolt Transmission Line- Marker Ball(s) Replacement CX(s) Applied: B1.3 Date: 12/17/2013 Location(s): Arizona Offices(s): Western Area Power Administration-Desert Southwest Region

  1. EIS-0457: Albany-Eugene Rebuild Project, Lane and Linn Counties, OR

    Broader source: Energy.gov [DOE]

    This EIS evaluates the environmental impacts of a proposal by BPA to rebuild a 32-mile section of the Albany-Eugene 115-kilovolt No. 1 Transmission Line in Lane and Linn Counties, OR.

  2. CX-012194: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Santiam Substation 230 Kilovolt Shunt Reactor Replacement CX(s) Applied: B4.11 Date: 05/05/2014 Location(s): Oregon Offices(s): Bonneville Power Administration

  3. CX-009409: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Gering-Gering Valley 34.5 Kilovolt Transmission Line Underground Installation CX(s) Applied: B4.13 Date: 10/02/2012 Location(s): Nebraska Offices(s): Western Area Power Administration

  4. EIS-0365: EPA Notice of Availability of the Draft Environmental...

    Broader source: Energy.gov (indexed) [DOE]

    of the Draft Environmental Impact Statement Imperial-Mexicali 230-kV Transmission Lines Imperial-Mexicali 230-kV Transmission Lines, Construct a Double-Circuit 230-kV...

  5. L8-28 R. L. Kus tom

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    coaxial cavity in L8-26. The effective peak voltage including transit time is 200 kV, while the actual peak voltage is 204.7 kV. The cavity power required for 200 kV...

  6. Categorical Exclusion (CX) Determination Proposed Action: Elliot...

    Broader source: Energy.gov (indexed) [DOE]

    Elliot 115kV43.8kV Transmission Substation Construction and Elliot 43.8kV Transmission Line. Description of Proposed Action: The Central Power Electric Cooperative (Central Power)...

  7. Bonneville Power Administration is investigating wide-area stability and voltage control. The control provides a flexible

    E-Print Network [OSTI]

    Venkatasubramanian, Mani V.

    consists of a ±500-kV, 3100 MW bipolar HVDC link, and a 500-kV AC intertie of 4800 MW capacity. Measures

  8. College of Engineering and Architecture Evolution of Control for the

    E-Print Network [OSTI]

    HVDC 3 HVDC 1 500kV AC 2 parallel 500 kV AC 1 HVDC Tibet #12;College of Engineering and Architecture

  9. imulation und Optimierung der Standort- und Kapazit¨atsauswahl in der Planung von Ladeinfrastruktur fur batterieelektrische Fahrzeug?otten

    E-Print Network [OSTI]

    Siefen, Kostja

    2012-01-01T23:59:59.000Z

    Key Performance Indicator kV . . . . . . . . . . . .Index oder Key Performance Indicator (KPI) bezeichnet. 3.5

  10. ENVIRONMENTAL REVIEW FOR CATEGORICAL EXCLUSION DETERMINATION

    Broader source: Energy.gov (indexed) [DOE]

    166.7 MVA transformer KV1A is composed of three single phase 220115-kV 55.5 MV A transformers. The A-phase (KV1A3) failed, but with the use of the mobile transformer KV1A still...

  11. Utility-Scale Solar Power Converter: Agile Direct Grid Connect Medium Voltage 4.7-13.8 kV Power Converter for PV Applications Utilizing Wide Band Gap Devices

    SciTech Connect (OSTI)

    None

    2012-01-25T23:59:59.000Z

    Solar ADEPT Project: Satcon is developing a compact, lightweight power conversion device that is capable of taking utility-scale solar power and outputting it directly into the electric utility grid at distribution voltage levels—eliminating the need for large transformers. Transformers “step up” the voltage of the power that is generated by a solar power system so it can be efficiently transported through transmission lines and eventually “stepped down” to usable voltages before it enters homes and businesses. Power companies step up the voltage because less electricity is lost along transmission lines when the voltage is high and current is low. Satcon’s new power conversion devices will eliminate these heavy transformers and connect a utility-scale solar power system directly to the grid. Satcon’s modular devices are designed to ensure reliability—if one device fails it can be bypassed and the system can continue to run.

  12. Arnold Schwarzenegger CERTS MICROGRID

    E-Print Network [OSTI]

    Arnold Schwarzenegger Governor CERTS MICROGRID LABORATORY TEST BED Test Bed Design Schematics Park Waitsfield, VT 05673 802-496-2955 www.northernpower.com CERTS Test Bed Schematic - PRELIMINARY (including Relay 1) T11 500kVA L11A,B,C CB12 CB13 Feeder C 75 yds cable Load Bank Zone 6 (Sheet 16, 17) A12 B

  13. DESIGN OF A MOBILE LABORATORY FOR VENTILATION STUDIES AND INDOOR AIR POLLUTION MONITORING

    E-Print Network [OSTI]

    Berk, James V.

    2011-01-01T23:59:59.000Z

    i co i 2KVA sou reg. X Instrument regulated pwr 20A 20AInstrument non-regulated pwr 30A twist lock tool box 30 Alock ( __J~ v x-k \\^_J~ Pump pwr 30A Zero gas generated pwr

  14. Double Side Control of Wound Rotor Induction Machine for Wind Energy Application Employing Half Controlled

    E-Print Network [OSTI]

    Lipo, Thomas

    the cost of a wind generator system, a new configuration using half controlled converters for both the required KVA rating of both machine side and line side converters, improves the efficiency of the wind generator, helps operating over a wide speed range and supports near unity power factor interface

  15. Testing and Evaluation of a Power Factor Correction for Power-Savings Potential

    E-Print Network [OSTI]

    Alotaibi, A.

    2011-01-01T23:59:59.000Z

    was then reduced from 13.9 to 3.0 kVAR (kilo volts amps reactive), the apparent power was decreased from 17.5 to 11.0 kVA (kilo volts amps). and the current was reduced from 23.4 to 14.5 amps. The Ministry of Electricity & Water (MEW) in Kuwait is expected...

  16. Scofield, et al, 29 IEEE PVSC, May 20-24, 2002 5P4.9

    E-Print Network [OSTI]

    Scofield, John H.

    inverter and a 15- kVA Square-D isolation transformer. The PV array produced 59,000 kW-hr of energy in its FOR THE ROOF-MOUNTED, 45-KW PV-ARRAY ON OBERLIN COLLEGE'S ADAM JOSEPH LEWIS CENTER John H. Scofield and David for modules, inverters, and transformers, combined with TMY2 weather data for Cleveland, project

  17. Microsoft Word - PVSC 2014 Final-JJ.docx

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    2 6---Apr---2010 2 for S max 30 k VA No (Transformerless) Floating kVA k mA Trip t ime (s) 5 The l arger r esistance of 100 k or 1 k * V max 300 continuous 0.30 30...

  18. Data:F8ee8537-c581-4d31-89a7-1f544328b139 | Open Energy Information

    Open Energy Info (EERE)

    of less than 100 kVA. Source or reference: https:docs.google.comviewer?av&pidsites&srcidcnJ2cmVhLmNvbXxycnZyZWF8Z3g6NWNiMWFkNmUyNzRkODFh Source Parent: http:...

  19. Data:E908a735-13ff-4c76-99f1-f77ff3c9ad00 | Open Energy Information

    Open Energy Info (EERE)

    of less than 100 kVA. Source or reference: https:docs.google.comviewer?av&pidsites&srcidcnJ2cmVhLmNvbXxycnZyZWF8Z3g6NWNiMWFkNmUyNzRkODFh Source Parent: http:...

  20. Event-Triggered Optimal Power Dispatch M.D. Lemmon, University of Notre Dame

    E-Print Network [OSTI]

    Lemmon, Michael

    can also be accomplished through small microturbines and gas/diesel generators. Storage devices Microgrids [14] [11] [9] are power generation/distribution systems in which users and gen- erators are in close proximity. This results in relatively low voltage grids (few hundred kVA). Generation is often

  1. CX-012113: Categorical Exclusion Determination

    Office of Energy Efficiency and Renewable Energy (EERE)

    NREL National Wind Technology Center Offsite 115 Kilovolt Tramsmission Line - Planning, Preliminary Design, and Environmental Surveys CX(s) Applied: A9, B3.1 Date: 05/20/2014 Location(s): Colorado Offices(s): Golden Field Office

  2. CX-012090: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Henderson-Mead Number 2 230-Kilovolt Transmission Line, Erosion Repair at Structure 2/4 CX(s) Applied: B1.3 Date: 09/11/2013 Location(s): Nevada, Nevada Offices(s): Western Area Power Administration-Desert Southwest Region

  3. CX-011718: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Electrical District 2 to Saguaro #2 115 Kilovolt Transmission Line, Marker Ball Installation at Structure 26-10. CX(s) Applied: B1.3 Date: 01/09/2014 Location(s): Arizona Offices(s): Western Area Power Administration-Desert Southwest Region

  4. EIS-0114: Fall River/Lower Valley Transmission System Reinforcement

    Broader source: Energy.gov [DOE]

    The Bonneville Power Administration developed this EIS to explore reinforcing the electrical transmission system in southeastern Idaho by adding a 161-kilovolt partly single- and double-circuit line from the Goshen to Drummond Substations in order to maintain reliable electric service in the area.

  5. CX-010406: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Davis Dam to Kingman Tap 69 Kilovolt Transmission Line, Overhead Optical Power Ground Wire Installation CX(s) Applied: B4.7 Date: 05/16/2013 Location(s): Arizona Offices(s): Western Area Power Administration-Desert Southwest Region

  6. CX-008783: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Fiber Optic Installation at the Stegall 230 Kilovolt Substation Scotts Bluff County, Nebraska CX(s) Applied: B4.7 Date: 06/20/2012 Location(s): Nebraska Offices(s): Western Area Power Administration-Rocky Mountain Region

  7. CX-010888: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Great Cut-McPhee 12.5-Kilovolt Fiber Optic Line Replacement CX(s) Applied: B1.3, B4.7 Date: 08/08/2013 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  8. CX-011721: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Gore Pass-Muddy Pass 69 Kilovolt Transmission Line Danger Tree Management in Grand and Jackson Counties, Colorado CX(s) Applied: B1.3 Date: 12/31/2013 Location(s): Colorado, Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  9. CX-008399: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Erosion Control Measures Structure No. 110-3 Dave Johnston to Stegall 230 Kilovolt Transmission Line CX(s) Applied: B1.3 Date: 03/29/2012 Location(s): Wyoming Offices(s): Western Area Power Administration-Rocky Mountain Region

  10. CX-005009: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Modify Two Structures Along the Vera Tap to Trentwood-Valley Way #1, 115 Kilovolt Transmission LineCX(s) Applied: B1.3, B4.6Date: 01/10/2011Location(s): Spokane County, WashingtonOffice(s): Bonneville Power Administration

  11. CX-012747: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Alcova-Miracle Mile East 115 Kilovolt Transmission Line Fiber Optic Ground Wire and Structure Replacement Project Natrona and Carbon Counties, Wyoming CX(s) Applied: B1.3, B4.7Date: 41855 Location(s): WyomingOffices(s): Western Area Power Administration-Rocky Mountain Region

  12. CX-010882: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Liberty-Parker Dam #2 230-Kilovolt Transmission Line, Optical Power Ground Wire Repair CX(s) Applied: B4.7 Date: 08/22/2013 Location(s): Arizona Offices(s): Western Area Power Administration-Desert Southwest Region

  13. CX-010675: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Parker Dam to Gila 161-kilovolt Transmission Line, Cross Arm Replacement at Structure 0/7 CX(s) Applied: B1.3 Date: 07/22/2013 Location(s): California Offices(s): Western Area Power Administration-Desert Southwest Region

  14. CX-010885: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Kiowa Creek-Weld 115-Kilovolt Transmission Line Culvert Replacement CX(s) Applied: B1.3, B1.33 Date: 08/06/2013 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  15. CX-011858: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Beaver Creek-Sterling 115 Kilovolt Transmission Line Structure Relocation, Morgan County, Colorado CX(s) Applied: B4.13 Date: 01/21/2014 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  16. CX-009227: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Beaver Creek- Big Sandy 115 Kilovolt Transmission Line Structure Replacements - Last Chance Fire CX(s) Applied: B4.13 Date: 08/31/2012 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  17. CX-012083: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Rosedale-Willowby-Kiowa Creek 115-Kilovolt Transmission Line Wood H-Structure Replacement CX(s) Applied: B1.3 Date: 04/10/2014 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  18. CX-007359: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    McNary-Horse Heaven 230-kilovolt Transmission Line Raise (Structures 15/2 to 16/3) CX(s) Applied: B1.3 Date: 12/01/2011 Location(s): Washington Offices(s): Bonneville Power Administration

  19. CX-012757: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Danger Tree Management on Curecanti-Lost Canyon 230 Kilovolt Transmission Line Phase II Montezuma County, Colorado CX(s) Applied: B1.3Date: 41838 Location(s): ColoradoOffices(s): Western Area Power Administration-Rocky Mountain Region

  20. CX-012758: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Danger Tree Management on Curecanti to South Canal and South Canal to Montrose 115 Kilovolt Transmission Lines, Gunnison County, Colorado CX(s) Applied: B1.3Date: 41855 Location(s): ColoradoOffices(s): Western Area Power Administration-Rocky Mountain Region

  1. CX-012759: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Danger Tree Management on Hayden-Gore Pass 230 Kilovolt Transmission Line Grand and Routt Counties, Colorado CX(s) Applied: B1.3Date: 41866 Location(s): ColoradoOffices(s): Western Area Power Administration-Rocky Mountain Region

  2. CX-011233: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Curecanti-Morrow Point 230 Kilovolt Transmission Line Danger Tree Management, Montrose County, Colorado CX(s) Applied: B1.3 Date: 10/17/2013 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  3. CX-010108: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Danger Tree Management on Curecanti-Crystal, 115 Kilovolt Transmission Line Danger Tree and Vegetation Management CX(s) Applied: B1.3 Date: 04/25/2013 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  4. CX-012216: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Danger Tree Management on Curecanti-Morrow Point 230 Kilovolt Transmission Line (Amended), Montrose County, Colorado CX(s) Applied: B1.3 Date: 05/16/2014 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  5. CX-011207: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Ault-Craig 345-Kilovolt Transmission Line Eastern Colorado Maintenance Office Danger Tree Management CX(s) Applied: B1.3 Date: 09/09/2013 Location(s): Colorado, Colorado, Colorado, Wyoming Offices(s): Western Area Power Administration-Rocky Mountain Region

  6. CX-010550: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Upper Molina-Lower Molina 115 Kilovolt Danger Tree Management Mesa County, Colorado CX(s) Applied: B1.3 Date: 06/14/2013 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  7. CX-012760: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Danger Tree Management on Hesperus-Montrose 345 Kilovolt Transmission Line, Phase II Montezuma County, Colorado CX(s) Applied: B1.3Date: 41838 Location(s): ColoradoOffices(s): Western Area Power Administration-Rocky Mountain Region

  8. CX-011230: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Artesia Tap- Southwest Rangely 138 Kilovolt Transmission Line Danger Tree and Herbicide Treatment for Vegetation Management CX(s) Applied: B1.3 Date: 09/26/2013 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  9. CX-006816: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Line and Load Interconnection of Coos-Curry Electric Cooperative?s New Substation to Bonneville Power Administration?s Fairview-Bandon 115-Kilovolt Transmission LineCX(s) Applied: B4.6, B4.10Date: 09/26/2011Location(s): Coos County, OregonOffice(s): Bonneville Power Administration

  10. EIS-0060: Bonneville Power Administration Proposed FY 1981 Program

    Broader source: Energy.gov [DOE]

    The Bonneville Power Administration developed this statement to evaluate environmental impacts of the proposed fiscal year 1981 construction and maintenance program to construct system additions and modifications including 303–326 miles of new 500 kilovolt transmission lines, approximately 131 miles of upgraded existing lines, 6 new substations, and facility additions at 7–8 existing substations.

  11. EIS-0077-S: Bonneville Power Administration Crow Butte Slough Crossing

    Broader source: Energy.gov [DOE]

    The Bonneville Power Administration developed this SEIS to evaluate potential impacts resulting from construction of a 4,700 -foot segment of the Ashe-Slatt transmission line at Crow Butte Slough, overhead on towers on the existing right-of-way. This SEIS is a supplement to DOE/EIS-0077, Ashe-Slatt (Pebble Springs) 500-kilovolt Transmission Line.

  12. CX-005936: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Erie to Terry Street and Lyons to Longmont Northwest 115 Kilovolt Transmission Line Structure Replacements, Boulder and Broomfield Counties, ColoradoCX(s) Applied: B4.6Date: 05/16/2011Location(s): Boulder County, ColoradoOffice(s): Western Area Power Administration-Rocky Mountain Region

  13. CX-008166: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Amended: Acquisition of a Portion of Cowlitz County Public Utility District’s 115-Kilovolt Transmission Line Washington Way Substation CX(s) Applied: B1.24 Date: 03/22/2012 Location(s): Washington Offices(s): Bonneville Power Administration

  14. CX-011857: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Archer-Cheyenne North/South 115 Kilovolt Transmission Line Structure Replacement, Laramie County, Wyoming CX(s) Applied: B4.13 Date: 01/28/2014 Location(s): Wyoming Offices(s): Western Area Power Administration-Rocky Mountain Region

  15. CX-012353: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Green Mountain-Kremmling 69-kilovolt Transmission Line Maintenance, Grand and Summit Counties, Colorado CX(s) Applied: B1.3 Date: 07/02/2014 Location(s): Colorado, Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  16. CX-009235: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Willow Creek - Granby Tap 2.4 Kilovolt Distribution Line Structure 0/3A Pole Replacement Project CX(s) Applied: B4.6 Date: 09/20/2012 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  17. CX-009088: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Curecanti-Crystal 115 Kilovolt Transmission Line Routine Maintenance of Existing Access Roads and Right-of-Ways CX(s) Applied: B1.3 Date: 08/07/2012 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  18. CX-012347: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Danger Tree Management on Craig-Rifle 230-kilovolt Transmission Line, Moffat, Rio Blanco, and Garfield Counties, Colorado CX(s) Applied: B1.3 Date: 06/02/2014 Location(s): Colorado, Colorado, Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  19. CX-012351: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Danger Tree Management on Green Mountain-Blue Ridge Repeater 2.4-kilovolt Distribution Line (Amended), Grand County, Colorado CX(s) Applied: B1.3 Date: 06/23/2014 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  20. CX-008782: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Danger Tree Management on North Gunnison to Skito 115 Kilovolt Transmission Line Gunnison County, Colorado CX(s) Applied: B1.3 Date: 07/02/2012 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  1. CX-012346: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Danger Tree Management on Blue River-Gore Pass 230-kilovolt Transmission Line (Amended), Grand County, Colorado CX(s) Applied: B1.3 Date: 06/02/2014 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  2. CX-008781: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Danger Tree Management on Curecanti to Blue Mesa 115 Kilovolt Transmission Line Gunnison County, Colorado CX(s) Applied: B1.3 Date: 07/02/2012 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  3. CX-012356: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Lovell-Yellowtail No. 1 115-kilovolt Transmission Line Culvert Replacement Project, Big Horn County, Wyoming CX(s) Applied: B1.3 Date: 07/01/2014 Location(s): Wyoming Offices(s): Western Area Power Administration-Rocky Mountain Region

  4. CX-012214: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Copper Mountain-Pilot Butte 34.5 Kilovolt Transmission Line Structure Pole Replacement Project, Fremont County, Wyoming CX(s) Applied: B1.3 Date: 05/05/2014 Location(s): Wyoming Offices(s): Western Area Power Administration-Rocky Mountain Region

  5. CX-012348: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Danger Tree Management on Curecanti to Poncha 230-kilovolt Transmission Line, Gunnison County, Colorado CX(s) Applied: B1.3 Date: 07/02/2014 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  6. CX-011859: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Big George-Heart Mountain 69 Kilovolt Transmission Line Glendale Tap Replacement, Park County, Wyoming CX(s) Applied: B4.6 Date: 01/21/2014 Location(s): Wyoming Offices(s): Western Area Power Administration-Rocky Mountain Region

  7. CX-012073: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Big George-Heart Mountain 69-Kilovolt Transmission Line Glendale Tap Replacement (Amended) CX(s) Applied: B4.13 Date: 05/01/2014 Location(s): Wyoming Offices(s): Western Area Power Administration-Rocky Mountain Region

  8. CX-008787: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Midway Substation 230 Kilovolt Upgrades El Paso County, Colorado CX(s) Applied: B4.6, B4.11 Date: 07/25/2012 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  9. CX-012349: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Danger Tree Management on Gore Pass-Hayden 138-kilovolt Transmission Line, Grand and Routt Counties, Colorado CX(s) Applied: B1.3 Date: 06/02/2014 Location(s): Colorado, Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  10. CX-012350: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Danger Tree Management on Gore Pass-Kremmling 138-kilovolt Transmission Line (Amended), Grand County, Colorado CX(s) Applied: B1.3 Date: 07/01/2014 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  11. C A L I F O R N I A E N E R G Y C O M M I S S I O N B L U E P R I N T

    E-Print Network [OSTI]

    to conservation. Conservation! Conservation! Conservation! ... Conservation is something that we can do right now transmission line.The upgrade adds a new 500 kilovolt power line to the transmission corridor that links and I meant it in more ways than just one." You can listen to the full speech at: http

  12. CX-010881: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Glen Canyon to Flagstaff #2 345-Kilovolt Transmission Line, Access Road Maintenance from Structure 45/5 to 46/1 CX(s) Applied: B1.3 Date: 08/08/2013 Location(s): Arizona Offices(s): Western Area Power Administration-Desert Southwest Region

  13. EA-1987: Parker-Headgate Rock and Parker-Bouse Rebuild Project, Arizona and California

    Broader source: Energy.gov [DOE]

    DOE’s Western Area Power Administration is preparing an EA that will assess the potential environmental impacts of a proposal to rebuild the existing Parker Dam-Headgate Rock and Parker Dam-Bouse 161-kilovolt transmission lines along the Colorado River in western Arizona and eastern California.

  14. CX-012751: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Casper-Seminoe (Retired) 69 Kilovolt Transmission Line Emergency Conductor Removal Carbon and Natrona Counties, Wyoming CX(s) Applied: B4.10Date: 41858 Location(s): WyomingOffices(s): Western Area Power Administration-Rocky Mountain Region

  15. CX-010883: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    PHX-LOB and LIB-LOB 230-Kilovolt Double-Circuit- Replace Insulators at Structure No. 28-2 With NCI Type Polymers CX(s) Applied: B1.3 Date: 08/12/2013 Location(s): Arizona Offices(s): Western Area Power Administration-Desert Southwest Region

  16. EIS-0141: Washington Water Power/B.C. Hydro Transmission Interconnection Project

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy developed this statement to evaluate the environmental impacts of constructing and operating a double-circuit 230-kilovolt electrical transmission line that would link the electrical systems of the Washington Water Power Company and the British Columbia Hydro and Power Authority.

  17. CX-010559: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Silicon Power Corporation - Optically-Switched 15-kilovolt SiC Single-Bias High-Frequency Thyristor CX(s) Applied: B3.6 Date: 05/07/2013 Location(s): New York, Pennsylvania, North Carolina, Illinois Offices(s): Advanced Research Projects Agency-Energy

  18. CX-011722: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Green Mountain-Blue Ridge Repeater 2.4 Kilovolt Distribution Line Danger Tree Management in Grand County, Colorado CX(s) Applied: B1.3 Date: 12/31/2013 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  19. CX-011720: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Blue River-Gore Pass 230 Kilovolt Transmission Line Danger Tree Management in Grand County, Colorado CX(s) Applied: B1.3 Date: 01/06/2014 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  20. CX-008378: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Archer 230 Kilovolt Bay Addition for New Point of Delivery - Stage 07 CX(s) Applied: B4.6 Date: 03/08/2012 Location(s): CX: none Offices(s): Western Area Power Administration-Rocky Mountain Region

  1. CX-008403: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Multiple Structure Replacement Flaming Gorge to Vernal No. 1 138 Kilovolt Transmission Line CX(s) Applied: B1.3 Date: 03/29/2012 Location(s): Utah Offices(s): Western Area Power Administration-Rocky Mountain Region

  2. CX-001185: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Replace Spacer Dampers Along the Wautoma-Rock Creek Number 1 500 Kilovolt Transmission LineCX(s) Applied: B1.3Date: 03/03/2010Location(s): Benton County, Yakima County, Office(s): Bonneville Power Administration

  3. CX-004255: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Replace Spacer Dampers Along the Chief Joseph PH-Chief Joseph Number 6 500-Kilovolt Transmission LineCX(s) Applied: B1.3Date: 10/05/2010Location(s): Douglas County, WashingtonOffice(s): Bonneville Power Administration

  4. CX-011232: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Gore Pass-Hayden 138 Kilovolt Transmission Line Emergency Repairs of Downed Conductor Grand County, Colorado CX(s) Applied: B1.3 Date: 10/09/2013 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  5. CX-011228: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Structure 112-4 LIBPAD1 230-kilovolt Transmission Line "Live Line" Maintenance Training CX(s) Applied: B1.2 Date: 10/25/2013 Location(s): Arizona Offices(s): Western Area Power Administration-Desert Southwest Region

  6. CX-007741: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Satcon Technology Corp. - Agile Direct Grid Connect Medium Voltage 4.7-13.8 Kilovolt Power Converter for Photovoltaic Applications Utilizing Advanced Wide Band Gap Devices CX(s) Applied: A9, B3.6 Date: 12/09/2011 Location(s): Massachusetts, New Mexico, North Carolina, Pennsylvania Offices(s): Advanced Research Projects Agency-Energy

  7. CX-006819: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Replace Aging Wood Poles on Trans Alta?s Centralia Tap to Chehalis-Covington No. 1 230-Kilovolt Transmission LineCX(s) Applied: B1.3Date: 09/16/2011Location(s): Lewis County, WashingtonOffice(s): Bonneville Power Administration

  8. Data:Fe13feff-11f2-49b2-9b4e-01d99d3a03c2 | Open Energy Information

    Open Energy Info (EERE)

    Description: Customers on this rate who are metered on the primary side at 4.16 KV or 24.9 KV receive a discount. A discount is also available for customers who own and...

  9. Contribution of potassium channels to myogenic response in skeletal muscle arterioles: effects of age and fiber type

    E-Print Network [OSTI]

    Kim, Se Jeong

    2006-10-30T23:59:59.000Z

    channels and voltage-dependent (Kv) potassium channels; these channels have a role in the negativefeedback pathways that modulate depolarization and myogenic constriction. We tested the hypothesis that increased KCa channel and Kv channel activity...

  10. Optically Isolated HVIGBT Based MW Cascade Inverter Building...

    Broader source: Energy.gov (indexed) [DOE]

    Sensor 22.5KV 3" Solid Conductor Sensor 34.5KV Overhead Sensor Pole-Mounted Electro-Optics Benefits for Customer: - Complete Data Acquisition, Processing, Storage (up to 1...

  11. ATF Plasma Sources for Wakefield Electron Acceleration ATF User...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Plasma Sources at ATF Ablative discharge capillary Gas-filled capillary Gas jet Plasma Sources: Ablative discharge capillary +20 kV DC 1k 1M HV generator (20kV,...

  12. SANDIA REPORT

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    ranging from 12.47 kV-13.8 kV. Utilizing the reactive power control capabilities of the PV inverters provided the added benefit of imposing no added cost to the utility company...

  13. Microsoft Word - GrantPUD-CX.docx

    Broader source: Energy.gov (indexed) [DOE]

    Public Utility District (Grant PUD), BPA proposes to interconnect Grant's new 230-kV transmission line into bay 7 within the BPA owned 230-kV Columbia Substation. In addition,...

  14. Microsoft Word - Cover Page - Exhibit 5

    Broader source: Energy.gov (indexed) [DOE]

    115 120 125 130 135 140 145 150 155 Structure Quantity Structure Height EXHIBIT 5 Project Structure Height Breakdown - HVDC & 345-kV HVDC Structures 345-kV Structures 27-JUN-2013...

  15. FINAL PROJECT REPORT LOAD MODELING TRANSMISSION RESEARCH

    E-Print Network [OSTI]

    Lesieutre, Bernard

    2013-01-01T23:59:59.000Z

    communications in the substation Example Costs: Instrument115-kV “B” Substations SVC Unit Cost ($ Millions) Total115-kV “B” Substations SVC Unit Cost ($ Millions) Total SVC

  16. Letter from the Department of Energy to the District of Columbia...

    Broader source: Energy.gov (indexed) [DOE]

    . PEPCO has informed DOE that the first new 230 kV line is expected to be completed by June 2, 2007. The outage for the second new 230 kV line is expected to begin immediately...

  17. EIS-0484: Notice of Intent to Prepare an Environmental Impact...

    Energy Savers [EERE]

    of a proposal to replace roughly 12 miles of transmission line on the Taft-Dworshak 500-kV transmission line, install new series capacitors on the Garrison-Taft 500-kV...

  18. Robotic Platform for Monitoring Underground Cable Systems

    E-Print Network [OSTI]

    Mamishev, Alexander

    . to traverse and monitor fiber-optic overhead ground transmission wires (OPGW) above 66kV power transmission

  19. EIS-0025: Final Environmental Impact Statement

    Broader source: Energy.gov [DOE]

    Miles City-New Underwood 230-kV Electrical Transmission Line, Montana, North Dakota, and South Dakota

  20. EIS-0079: Final Environmental Impact Statement

    Broader source: Energy.gov [DOE]

    300-kV International Submarine Transmission Line - Erie, Pennsylvania to Nanticoke, Ontario, Canada General Public Utilities Corporation

  1. EIS-0032: Final Environmental Impact Statement

    Broader source: Energy.gov [DOE]

    500 kV International Transmission Line NSP-TR-1, Forbes, Minnesota to Manitoba, Canada, Northern States Power Company

  2. EIS-0505: Supplemental Draft Environmental Impact Statement

    Broader source: Energy.gov [DOE]

    Vantage to Pomona Heights 230 kV Transmission Line Project, Yakima, Grant, Benton, and Kittitas Counties, Washington

  3. Marted 17 dicembre 2013 Il Mnemosyne Ensemble esegue

    E-Print Network [OSTI]

    Robbiano, Lorenzo

    Academici Cantores eseguono Wolfgang Amadeus Mozart (1756-1791) Sonata da chiesa KV278 - Allegro Scande o pignora" - Allegro Sonata da chiesa KV69 - Allegro Te Deum KV141 (66b) - "Te Deum laudamus" - Allegro "Te ergo quaesumus" - Adagio "Aeterna fac cum sanctis tuis"- Allegro "In te Domine speravi

  4. Wind Power Systems 1. Overview

    E-Print Network [OSTI]

    Ding, Yu

    or non-renewable 3 #12;Electricity basics1 Step-up transmission substation(155-765kV) · Step-down transmission substation (69 kV) · Distribution substations (19.9-24kV) Generation Transmission Distribution 4 1, Connecticut, Delaware, District of Columbia, Illinois, Maine, Maryland, Massachusetts, Michigan, Montana

  5. Fakultt fr Informations-Medien-und Elektrotechnik

    E-Print Network [OSTI]

    Noé, Reinhold

    Energietechnik Prof. Dr.-Ing. habil. Ingo Stadler Electricity Transmission and Distribution, Today Power plants.-Ing. habil. Ingo Stadler Electricity Transmission and Distribution Power plants~ ~ ~ ~ ~ 380kV 220kV 110kV 10 further guidelines. VDEW guidelines for parallel operation of electricity generation units in the low

  6. EIS-0008-S: Supplement, Dickey-Lincoln School Lakes Transmission Project, Maine, New Hampshire, and Vermont

    Broader source: Energy.gov [DOE]

    The Bonneville Power Administration developed this SEIS to evaluate the environmental impacts of construction of a steel double-circuit 345-kilovolt transmission line from Moore Substation near Littleton, New Hampshire, to Comerford Substation near Monroe, New Hampshire and a 345-kilovolt wood pole transmission line from Comerford Substation to Webster Substation near Franklin, New Hampshire, as part of the Dickey-Lincoln School Lakes Transmission Project. The Final SEIS consists entirely of Section 9 (Consultation and Coordination), which incorporates public and agency comments on the Draft SEIS and responses to those comments, as well as all necessary errata and addenda to the Draft SEIS. This SEIS is a supplement to DOE/EIS-008, Dickey-Lincoln School Lakes Transmission Project.

  7. Electrohydrodynamically enhanced condensation heat transfer

    E-Print Network [OSTI]

    Wawzyniak, Markus

    1993-01-01T23:59:59.000Z

    kV (electrode ?1). . . .. . . . . . . Fig. 4. 3 Photograph of liquid bridging &om the helical wire to the condensation surface at 20 kV (electrode ?1) . Fig. 4. 4 Photograph removal of liquid at 20 kV (electrode ?1) . .. Fig. 4. 5 Electrode ?2... . . . . . 32 Fig. 4. 8 Electrode ?3 . Fig. 4. 9 Photograph of liquid extraction (detail A), and liquid removal (detail B) at 15 kV (electrode ?3) . . Fig. 4. 10 Electrode ?4. Fig. 4. 11 Electrode ?5. Fig. 4. 12 Photograph of electrode ?5 at 12 kV...

  8. EIS-0483: Estes to Flatiron Substation Transmission Lines Rebuild Project, Larimer County, Colorado

    Broader source: Energy.gov [DOE]

    Western Area Power Administration (Western) – with USDA Forest Service, Arapaho and Roosevelt National Forest, as a cooperating agency – is preparing an EIS that analyzes the potential environmental impacts of a proposal to rebuild and upgrade two 115-kilovolt single-circuit transmission lines between the Flatiron Substation and the intersection of Mall Road and U.S. Highway 36 in Estes Park, Larimer County, Colorado. Additional information is available on Western’s project website.

  9. EIS-0440: Quartzsite Solar Energy Project, La Paz County, AZ

    Broader source: Energy.gov [DOE]

    This EIS evaluates the environmental impacts of interconnecting a proposed 100-megawatt concentrating solar power plant to Western’s Bouse-Kofa 161-kilovolt transmission line. The proposal includes amending the Bureau of Land Management Resource Management Plan. Cooperating agencies in the preparation of this EIS are Bureau of Land Management (Yuma Field Office ), U.S. Army Corps of Engineers, U.S. Army Garrison (Yuma Proving Grounds), Arizona Game and Fish Department, and the Arizona Department of Environmental Quality.

  10. EA-1981: Bonneville-Hood River Transmission Line Rebuild, Multnomah and Hood River Counties, Oregon

    Broader source: Energy.gov [DOE]

    Bonneville Power Administration (BPA) is preparing an EA to assess potential environmental impacts of a proposal to rebuild its 24-mile long, 115 kilovolt Bonneville-Hood River transmission line. The existing line runs between the Bonneville Powerhouse at Bonneville Dam in Multnomah County, Oregon, and BPA's existing Hood River Substation in Hood River County, Oregon. The project would include replacing structures and conductor wires, improving access roads, and constructing new access roads or trails where needed.

  11. Type A Accident Investigation Report – Western Area Power Administration Investigation of the June 7, 2004, Construction Contractor Electrical Accident at Double-Circuit Structure 38/1, Watertown-Granite Falls 230-kV Transmission Line East of Watertown, S

    Broader source: Energy.gov [DOE]

    This report is an independent product of the Type A Accident Investigation board appointed by Timothy J. Meeks, Chief Operating Officer, Western Area Power Administration.

  12. Optimizing the CEBAF Injector for Beam Operation with a Higher Voltage Electron Gun

    E-Print Network [OSTI]

    Hannon, F E; Kazimi, R

    2011-01-01T23:59:59.000Z

    Recent developments in the DC gun technology used at CEBAF have allowed an increase in operational voltage from 100kV to 130kV. In the near future this will be extended further to 200kV with the purchase of a new power supply. The injector components and layout at this time have been designed specifically for 100kV operation. It is anticipated that with an increase in gun voltage and optimization of the layout and components for 200kV operation, that the electron bunch length and beam brightness can be improved upon. This paper explores some upgrade possibilities for a 200kV gun CEBAF injector through beam dynamic simulations.

  13. Optimizing the CEBAF Injector for Beam Operation with a Higher Voltage Electron Gun

    SciTech Connect (OSTI)

    F.E. Hannon, A.S. Hofler, R. Kazimi

    2011-03-01T23:59:59.000Z

    Recent developments in the DC gun technology used at CEBAF have allowed an increase in operational voltage from 100kV to 130kV. In the near future this will be extended further to 200kV with the purchase of a new power supply. The injector components and layout at this time have been designed specifically for 100kV operation. It is anticipated that with an increase in gun voltage and optimization of the layout and components for 200kV operation, that the electron bunch length and beam brightness can be improved upon. This paper explores some upgrade possibilities for a 200kV gun CEBAF injector through beam dynamic simulations.

  14. 33 EMSI 2013 New Insight into the Fundamental Physics of Low-Dimensional

    E-Print Network [OSTI]

    Dunin-Borkowski, Rafal E.

    particles on C, demonstrating the ability to record 80 and 65 pm detail at 80 and 300 kV, respectively. When, S. Uhlemann, U. Loebau, J. Zach and H. Rose, J. Electron Microsc., Vol. 58, 147- 155 (2009). Figure. The smallest spacing at 80 kV (left) is ~80 pm and at 300 kV (right) is ~65 pm. PL­9 #12;

  15. Recent Progress in Chromatic Aberration Corrected High-Resolution and Lorentz Transmission Electron Microscopy

    E-Print Network [OSTI]

    Dunin-Borkowski, Rafal E.

    80 and 65 pm detail at 80 and 300 kV, respectively. Figure 2 shows CC and CS corrected energy. 58 (2009) 147. [3] R. Leary and R. Brydson. Advances in Imaging and Electron Physics 165 (2011) 73. The smallest detected image spacing at 80 kV (left) is ~80 pm and at 300 kV (right) is ~65 pm. FIG. 2. Atomic

  16. TU Delft has made an important contribution to the ongoing

    E-Print Network [OSTI]

    Langendoen, Koen

    converter. M3C's market potential As M3C can be used in HVDC systems, it has huge market potential, considering the HVDC transmission market is expected to at least double within the next five years. The new distribution grids (e.g. 600V/5kV), HVDC-UHVDC DC/DC converters (300kV/800kV, electrostatic systems and battery

  17. Preventing Electrical Shock

    E-Print Network [OSTI]

    Smith, David

    2004-09-16T23:59:59.000Z

    closer to un- guarded energized overhead lines than the following distances: 1) For voltages to ground 50 kV or less?10 feet; 2) For voltages to ground more than 50 kV ?10 feet plus 4 inches for every 10 kV over 50 kV. ? Make sure all electric motors... attempt to unplug the cord, move an energized line with any object, or grab the person to free him. Once the person is free, administer CPR immedi- ately, if necessary, to try to resuscitate the individual. In case of an electrical fi re, turn off...

  18. EIS-0100: Final Environmental Impact Statement | Department of...

    Energy Savers [EERE]

    100: Final Environmental Impact Statement EIS-0100: Final Environmental Impact Statement Liberty-Coolidge 230-kV Transmission Line, Arizona EIS-0100: Final Environmental Impact...

  19. EIS-0011: Final Environmental Impact Statement | Department of...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    1: Final Environmental Impact Statement EIS-0011: Final Environmental Impact Statement New Melones 230-kV Electrical Transmission Line, Central Valley Project, California<...

  20. Data:9b7e3ffc-f95e-43b3-a9c3-e990ac62c383 | Open Energy Information

    Open Energy Info (EERE)

    Service Area. For delivery to wholesale (sales for resale) customers over MKEC's 34.5 Kv (or other available lower primary voltage) subtransmissiondistribution system. Source...

  1. Essays in Applied Microeconomics

    E-Print Network [OSTI]

    Severnini, Edson Roberto

    2013-01-01T23:59:59.000Z

    electric power plants for commercial electricity sale __50s: Construction of High-Voltage (230kV or more) Transmission Lines

  2. Bureau of Land Management’s Environmental Assessment

    Broader source: Energy.gov [DOE]

    T G Power LLC Hot Sulphur Springs Transmission Line, 120 kV Electric Power Line, Northern Independence Valley, Elko County, Nevada

  3. Real Time Grid Reliability Management 2005

    E-Print Network [OSTI]

    Eto, Joe

    2008-01-01T23:59:59.000Z

    California, Mexico. 15. US Western Interconnection BlackoutMexico Border, and via the SONGS 230kV switchyard – SDG&E’s only direct interconnection

  4. ENV IRONMENTA L REV

    Broader source: Energy.gov (indexed) [DOE]

    and control equipment; one (I) revenue meter; and 230-kV revenue quality instrument transformers. All new equipment and facilities installations lay within the footprint of the...

  5. Microsoft Word - CX_Memo_Fairmount.docx

    Broader source: Energy.gov (indexed) [DOE]

    circuit breaker, three 1600 ampere disconnect switch sets, three 115-kV current transformers and associated digital relaying. The transfer in ownership to BPA would not change...

  6. EIS-0374: EPA Notice of Availability of the Draft Environmental...

    Broader source: Energy.gov (indexed) [DOE]

    Day 500-kV Substation. DOEEIS-0374, Environmental Protection Agency, Notice of Availability of the Department of Energy, Bonneville Power Administration, Draft Environmental...

  7. EA-1665: Final Environmental Assessment and Finding of No Significant...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Final Environmental Assessment and Finding of No Significant Impact EA-1665: Final Environmental Assessment and Finding of No Significant Impact Davis-Kingman Tap 69-kV...

  8. STATEMENT OF CONSIDERATIONS REQUEST BY SUPERPOWER, INC. FOR AN...

    Broader source: Energy.gov (indexed) [DOE]

    design, build, install, test and operate a 138kv class prototype high temperature superconducting (HTS) fault current limiter (FCL) at a utility transmission substation. The...

  9. EIS-0285-SA-59: Supplement Analysis | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    System Vegetation Management Program Vegetation Management along the Chehalis Covington Raver Paul Paul Alston 230 and 500 kV Transmission line Corridor ROW 482 to...

  10. Presentation to the EAC - Philadelphia Navy Yard - Will Agate

    Broader source: Energy.gov (indexed) [DOE]

    expansion * Incremental build out-PECO 13 KV line extensions Demand Reduction Programs * Demand-response with Navy and large commercial customers * On-site peak generation *...

  11. ALTERNATE POWER AND ENERGY STORAGE/REUSE FOR DRILLING RIGS: REDUCED COST AND LOWER EMISSIONS PROVIDE LOWER FOOTPRINT FOR DRILLING OPERATIONS 

    E-Print Network [OSTI]

    Verma, Ankit

    2010-07-14T23:59:59.000Z

    Hz, 3000 KVA. Two transformers convert this into 690 V, 60 Hz and feed it to the invertors which then convert it into DC and supply to the main bus where all major consumers are mounted. Regenerated power is dissipated in the brake resistors... to be a better version of LOC-250. Also this is one of the reasons why there is no efficiency loss in LOC-400 when converting the regenerative power from hydraulic to mechanical and then electrical which is the case with LOC-250. The single line diagram...

  12. Optimizing Power Factor Correction

    E-Print Network [OSTI]

    Phillips, R. K.; Burmeister, L. C.

    = energy charge from 5 above, $/mo c) $0.024 per kWh for the next 250 kWh per kVA 7. The bill is then adjusted for times the billing capacity; plus a) fuel and purchased energy under the energy d) $0.022 per kWh for all remaining kWh. cost adjustment... are neglected. A linear capacitor cost model is assumed that has an initial cost plus a cost per kVAR of .? ESL-IE-86-06-132 Proceedings from the Eighth Annual Industrial Energy Technology Conference, Houston, TX, June 17-19, 1986 capacitance. Although...

  13. Applying Improved Efficiency Transformers

    E-Print Network [OSTI]

    Haggerty, N. K.; Malone, T. P.

    primary and secondary windings, and vary significantly with transformer loading. Load or conductor losses vary with the square of the per unit load. Average full load losses of a 1500 kVA transformer can range from 11 to 21 kW. Manufacturers can... to meet the requirements of a particular transformer specification. These designs will have varying amounts of core steel and copper or aluminum conductors with differing no-load and load losses. The lowest cost design that meets all the applicable...

  14. EIS-0433-S1: Keystone XL Pipeline SEIS (Montana, South Dakota, and Nebraska)

    Broader source: Energy.gov [DOE]

    This EIS analyzes the potential environmental impacts of a revised proposal for the Keystone XL pipeline and related facilities. The proposed facilities would transport crude oil from the Western Canadian Sedimentary Basin and the Williston Basin to existing pipeline facilities near Steele City, Nebraska, for onward transport to markets in the Texas Gulf Coast area. DOE is a cooperating agency. DOE's Western Area Power Administration has jurisdiction over certain proposed transmission facilities relating to the proposal, including construction and operation of a portion of a 230-kilovolt transmission line and construction and operation of two new substations and the expansion of six existing substations.

  15. EIS-0477: San Juan Basin Energy Connect Project, San Juan County, New Mexico and La Plata County, Colorado

    Broader source: Energy.gov [DOE]

    The Department of the Interior’s Bureau of Land Management is preparing an EIS to evaluate the potential environmental impacts of a proposal to construct a 230-kilovolt transmission line from the Farmington area in northwest New Mexico to Ignacio, Colorado, to relieve transmission constraints, serve new loads, and offer economic development through renewable energy development in the San Juan Basin. DOE’s Western Area Power Administration is a cooperating agency; the proposed transmission line would require an interconnection with Western's Shiprock Substation, near Farmington, and a new Three Rivers Substation on Western's reserved lands.

  16. Jeudi 3 octobre 2013 Grid integration of REN

    E-Print Network [OSTI]

    Canet, Léonie

    of Smartgrids Nouredine Hadjsaid, Grenoble INP/ENSE3, laboratoire G2ELAB, CNRS #12;MV/LV 20kV/400V HV/MV 63kV/20 de distribution Opérateur Système Production Transport Distribution SmartGrids Evolution: Value chain and implication SmartGrids value chain Interface des c Interface des c #12;Tools for managing complexity ICT

  17. A LINEARIZATION METHOD FOR A UWB VCO-BASED CHIRP GENERATOR USING DUAL COMPENSATION

    E-Print Network [OSTI]

    Gomez-Garcia Alvestegui, Daniel

    2011-12-31T23:59:59.000Z

    79 Figure 3-23: Simulated Bode Plots for Compensated Open Loop Transfer Function for Final Loop Filter Design (KV=600MHz/V) .................................................................................... 80 Figure 3-24: Simulated Bode Plots... for Compensated Open Loop Transfer Function for Final Loop Filter Design (KV=450MHz/V) .................................................................................... 80 Figure 3-25: Simulated Bode Plots for Compensated Open Loop Transfer Function for Final...

  18. Published: June 22, 2011 r 2011 American Chemical Society 8732 dx.doi.org/10.1021/jp2001964 |J. Phys. Chem. B 2011, 115, 87328738

    E-Print Network [OSTI]

    White, Stephen

    - ary of biological cells and compartmentalizes them by providing a permeability barrier. Membrane is bound to arise. Here, as a first step toward a detailed understanding as to why Kv channels do simulations. Kv channels help generate action potentials along the cell membrane of excitable neurons

  19. Programaci primer trimestre curs 2009-2010

    E-Print Network [OSTI]

    Geffner, Hector

    , (Salzburg, 1756 - Viena, 1791) Serenata núm. 13 en sol major, Kv 525 "Eine Kleine nachtmusik" Allegro per a dos violins Op.3 núm. 8 "L'Estro Armonico" Allegro Larghetto e spiritoso Allegro Solistes: Júlia major, Kv 525 "Eine Kleine nachtmusik" Allegro Romance Menuetto Rondo Franz Schubert (Viena, 1797

  20. Utility Power Network Systems This research addresses the issues of security, system behavior, and socio-economic

    E-Print Network [OSTI]

    Shinozuka, Masanobu

    to the LADWP power system through two 500kV AC transmission lines and one 500kV DC transmission line. From Fig- economic component. July, 2003. Website_ResearchActivities1 #12;Background LADWP's power transmission probabilistic systems analysis of societal interests. Fig.1. Service areas of LADWP Fig.2. Electric power output