National Library of Energy BETA

Sample records for interim corrective measures

  1. SWSA 6 interim corrective measures environmental monitoring: FY 1990 results

    SciTech Connect (OSTI)

    Ashwood, T.L.; Spalding, B.P.

    1991-07-01

    This report presents the results and conclusions from a multifaceted monitoring effort associated with the high-density polyethylene caps installed in Solid Waste Storage Area (SWSA) 6 at Oak Ridge National Laboratory (ORNL) as an interim corrective measure (ICM). The caps were installed between November 1988 and June 1989 to meet Resource Conservation and Recovery Act (RCRA) requirements for closure of those areas of SWSA 6 that had received RCRA-regulated wastes after November 1980. Three separate activities were undertaken to evaluate the performance of the caps: (1) wells were installed in trenches to be covered by the caps, and water levels in these intratrench wells were monitored periodically; (2) samples were taken of the leachate in the intratrench wells and were analyzed for a broad range of radiological and chemical contaminants; and (3) water levels in wells outside the trenches were monitored periodically. With the exception of the trench leachate sampling, each of these activities spanned the preconstruction, construction, and postconstruction periods. Findings of this study have important implications for the ongoing remedial investigation in SWSA 6 and for the design of other ICMs. 51 figs., 2 tabs.

  2. SWSA 6 interim corrective measures environmental monitoring: FY 1990 results. Environmental Restoration Program

    SciTech Connect (OSTI)

    Ashwood, T.L.; Spalding, B.P.

    1991-07-01

    This report presents the results and conclusions from a multifaceted monitoring effort associated with the high-density polyethylene caps installed in Solid Waste Storage Area (SWSA) 6 at Oak Ridge National Laboratory (ORNL) as an interim corrective measure (ICM). The caps were installed between November 1988 and June 1989 to meet Resource Conservation and Recovery Act (RCRA) requirements for closure of those areas of SWSA 6 that had received RCRA-regulated wastes after November 1980. Three separate activities were undertaken to evaluate the performance of the caps: (1) wells were installed in trenches to be covered by the caps, and water levels in these intratrench wells were monitored periodically; (2) samples were taken of the leachate in the intratrench wells and were analyzed for a broad range of radiological and chemical contaminants; and (3) water levels in wells outside the trenches were monitored periodically. With the exception of the trench leachate sampling, each of these activities spanned the preconstruction, construction, and postconstruction periods. Findings of this study have important implications for the ongoing remedial investigation in SWSA 6 and for the design of other ICMs. 51 figs., 2 tabs.

  3. ATVM Interim Final Rule Correction | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    A few corrections to the final rule regarding fuel economy numbers. ATVM Interim Final Rule Correction More Documents & Publications Updated Guidance For Applicants To Advanced...

  4. Corrective Measures Process

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Corrective Measures Process Corrective Measures Process We follow a stringent corrective measures process for legacy cleanup. August 1, 2013 Corrective measures process Corrective measures process

  5. Corrective Measures Process

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Corrective Measures Process Corrective Measures Process We follow a stringent corrective measures process for legacy cleanup. August 1, 2013 Corrective measures process Corrective...

  6. Burn site groundwater interim measures work plan.

    SciTech Connect (OSTI)

    Witt, Jonathan L.; Hall, Kevin A.

    2005-05-01

    This Work Plan identifies and outlines interim measures to address nitrate contamination in groundwater at the Burn Site, Sandia National Laboratories/New Mexico. The New Mexico Environment Department has required implementation of interim measures for nitrate-contaminated groundwater at the Burn Site. The purpose of interim measures is to prevent human or environmental exposure to nitrate-contaminated groundwater originating from the Burn Site. This Work Plan details a summary of current information about the Burn Site, interim measures activities for stabilization, and project management responsibilities to accomplish this purpose.

  7. RCRA corrective action program guide (Interim)

    SciTech Connect (OSTI)

    Not Available

    1993-05-01

    The US Department of Energy (DOE) is responsible for compliance with an increasingly complex spectrum of environmental regulations. One of the most complex programs is the corrective action program proposed by the US Environmental Protection Agency (EPA) under the authority of the Resource Conservation and Recovery Act (RCRA) as amended by the Hazardous and Solid Waste Amendments (HSWA). The proposed regulations were published on July 27, 1990. The proposed Subpart S rule creates a comprehensive program for investigating and remediating releases of hazardous wastes and hazardous waste constituents from solid waste management units (SWMUs) at facilities permitted to treat, store, or dispose of hazardous wastes. This proposed rule directly impacts many DOE facilities which conduct such activities. This guidance document explains the entire RCRA Corrective Action process as outlined by the proposed Subpart S rule, and provides guidance intended to assist those persons responsible for implementing RCRA Corrective Action at DOE facilities.

  8. Quality assurance plan for the Molten Salt Reactor Experiment Remediation Project at the Oak Ridge National Laboratory. Phase 1 -- Interim corrective measures and Phase 2 -- Purge and trap reactive gases

    SciTech Connect (OSTI)

    1995-11-01

    This Quality Assurance Plan (QAP) identifies and describes the systems utilized by the Molten Salt Reactor Experiment Remediation Project (MSRERP) personnel to implement the requirements and associated applicable guidance contained in the Quality Program Description Y/QD-15 Rev. 2 (Energy Systems 1995f). This QAP defines the quality assurance (QA) requirements applicable to all activities and operations in and directly pertinent to the MSRERP Phase 1--Interim Corrective Measures and Phase 2--Purge and Trap objectives. This QAP will be reviewed, revised, and approved as necessary for Phase 3 and Phase 4 activities. This QAP identifies and describes the QA activities and procedures implemented by the various Oak Ridge National Laboratory support organizations and personnel to provide confidence that these activities meet the requirements of this project. Specific support organization (Division) quality requirements, including the degree of implementation of each, are contained in the appendixes of this plan.

  9. DOUBLE TRACKS Test Site interim corrective action plan

    SciTech Connect (OSTI)

    1996-06-01

    The DOUBLE TRACKS site is located on Range 71 north of the Nellis Air Force Range, northwest of the Nevada Test Site (NTS). DOUBLE TRACKS was the first of four experiments that constituted Operation ROLLER COASTER. On May 15, 1963, weapons-grade plutonium and depleted uranium were dispersed using 54 kilograms of trinitrotoluene (TNT) explosive. The explosion occurred in the open, 0.3 m above the steel plate. No fission yield was detected from the test, and the total amount of plutonium deposited on the ground surface was estimated to be between 980 and 1,600 grams. The test device was composed primarily of uranium-238 and plutonium-239. The mass ratio of uranium to plutonium was 4.35. The objective of the corrective action is to reduce the potential risk to human health and the environment and to demonstrate technically viable and cost-effective excavation, transportation, and disposal. To achieve these objectives, Bechtel Nevada (BN) will remove soil with a total transuranic activity greater then 200 pCI/g, containerize the soil in ``supersacks,`` transport the filled ``supersacks`` to the NTS, and dispose of them in the Area 3 Radioactive Waste Management Site. During this interim corrective action, BN will also conduct a limited demonstration of an alternative method for excavation of radioactive near-surface soil contamination.

  10. EA-2005: Chromium Plume Control Interim Measure And Plume-Center...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Control Interim Measure And Plume-Center Characterization, Los Alamos National Laboratory, Los Alamos, NM EA-2005: Chromium Plume Control Interim Measure And Plume-Center ...

  11. Northeast Site Non-Aqueous Phase Liquids Interim Measures Progress...

    Office of Legacy Management (LM)

    Northeast Site Non-Aqueous Phase Liquids Interim Measures Progress Report April 2003 Grand Junction Office U.S. Department of Energy Work Performed Under DOE Contract No. for the ...

  12. Filling the gaps in meteorological continuous data measured at FLUXNET sites with ERA-Interim reanalysis

    SciTech Connect (OSTI)

    Vuichard, N.

    2015-07-13

    In this study, exchanges of carbon, water and energy between the land surface and the atmosphere are monitored by eddy covariance technique at the ecosystem level. Currently, the FLUXNET database contains more than 500 registered sites, and up to 250 of them share data (free fair-use data set). Many modelling groups use the FLUXNET data set for evaluating ecosystem models' performance, but this requires uninterrupted time series for the meteorological variables used as input. Because original in situ data often contain gaps, from very short (few hours) up to relatively long (some months) ones, we develop a new and robust method for filling the gaps in meteorological data measured at site level. Our approach has the benefit of making use of continuous data available globally (ERA-Interim) and a high temporal resolution spanning from 1989 to today. These data are, however, not measured at site level, and for this reason a method to downscale and correct the ERA-Interim data is needed. We apply this method to the level 4 data (L4) from the La Thuile collection, freely available after registration under a fair-use policy. The performance of the developed method varies across sites and is also function of the meteorological variable. On average over all sites, applying the bias correction method to the ERA-Interim data reduced the mismatch with the in situ data by 10 to 36 %, depending on the meteorological variable considered. In comparison to the internal variability of the in situ data, the root mean square error (RMSE) between the in situ data and the unbiased ERA-I (ERA-Interim) data remains relatively large (on average over all sites, from 27 to 76 % of the standard deviation of in situ data, depending on the meteorological variable considered). The performance of the method remains poor for the wind speed field, in particular regarding its capacity to conserve a standard deviation similar to the one measured at FLUXNET stations.

  13. Filling the gaps in meteorological continuous data measured at FLUXNET sites with ERA-Interim reanalysis

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Vuichard, N.; Papale, D.

    2015-07-13

    In this study, exchanges of carbon, water and energy between the land surface and the atmosphere are monitored by eddy covariance technique at the ecosystem level. Currently, the FLUXNET database contains more than 500 registered sites, and up to 250 of them share data (free fair-use data set). Many modelling groups use the FLUXNET data set for evaluating ecosystem models' performance, but this requires uninterrupted time series for the meteorological variables used as input. Because original in situ data often contain gaps, from very short (few hours) up to relatively long (some months) ones, we develop a new and robustmore » method for filling the gaps in meteorological data measured at site level. Our approach has the benefit of making use of continuous data available globally (ERA-Interim) and a high temporal resolution spanning from 1989 to today. These data are, however, not measured at site level, and for this reason a method to downscale and correct the ERA-Interim data is needed. We apply this method to the level 4 data (L4) from the La Thuile collection, freely available after registration under a fair-use policy. The performance of the developed method varies across sites and is also function of the meteorological variable. On average over all sites, applying the bias correction method to the ERA-Interim data reduced the mismatch with the in situ data by 10 to 36 %, depending on the meteorological variable considered. In comparison to the internal variability of the in situ data, the root mean square error (RMSE) between the in situ data and the unbiased ERA-I (ERA-Interim) data remains relatively large (on average over all sites, from 27 to 76 % of the standard deviation of in situ data, depending on the meteorological variable considered). The performance of the method remains poor for the wind speed field, in particular regarding its capacity to conserve a standard deviation similar to the one measured at FLUXNET stations.« less

  14. Interim measure work plan/design for Agra, Kansas.

    SciTech Connect (OSTI)

    LaFreniere, L. M.; Environmental Science Division

    2008-11-18

    This Interim Measure Work Plan/Design (IMWP/D) is supplemental to the Argonne document Interim Measure Conceptual Design for Remediation of Source Area Contamination at Agra, Kansas. The IMWP/D includes information required by Kansas Department of Health and Environment (KDHE) Policy BER-RS-029, Policy and Scope of Work for Interim Measures. Specific to Policy BER-RS-029 is the requirement for several documents that will ensure that an adequate amount and type of data are collected for implementation of the IMWP/D and that data quality and safe conditions are prevailed. Such information is included in the IMWP/D as follows: Appendix A: Data Acquisition Plan--Design Testing Requirements; Appendix B: Basis of Design; Appendix C: Permits; Appendix D: Quality Assurance Project Plan; Appendix E: Health and Safety Plan; and Appendix F: Operations, Maintenance, and Monitoring Schedule. The proposed remedial technology for this project is the installation of five large-diameter boreholes (LDBs) in a source area that has been identified on the property formerly used for grain storage by the Commodity Credit Corporation of the U.S. Department of Agriculture (CCC/USDA). The goal of the LDB technology is the remediation of the source area by removal of mass quantities of contaminated soil from the vadose zone and treatment of any remaining contaminated soils that are adjacent to the source area to achieve a carbon tetrachloride concentration below 200 {micro}g/kg. Secondary to the soil remediation is the remediation of groundwater at and adjacent to the source areas. The LDB technology serves the following purposes: (1) The physical removal of contaminated soil from the identified source area. (2) Replacement of less permeable native materials (silty clay, clayey silt, and silty sand) with more permeable materials to facilitate the capture of volatilized contaminants in the vertical borehole. (3) Removal of contaminants volatilized by air sparging (AS) and extracted from the

  15. Radiosondes Corrected for Inaccuracy in RH Measurements

    DOE Data Explorer [Office of Scientific and Technical Information (OSTI)]

    Miloshevich, Larry

    2008-01-15

    Corrections for inaccuracy in Vaisala radiosonde RH measurements have been applied to ARM SGP radiosonde soundings. The magnitude of the corrections can vary considerably between soundings. The radiosonde measurement accuracy, and therefore the correction magnitude, is a function of atmospheric conditions, mainly T, RH, and dRH/dt (humidity gradient). The corrections are also very sensitive to the RH sensor type, and there are 3 Vaisala sensor types represented in this dataset (RS80-H, RS90, and RS92). Depending on the sensor type and the radiosonde production date, one or more of the following three corrections were applied to the RH data: Temperature-Dependence correction (TD), Contamination-Dry Bias correction (C), Time Lag correction (TL). The estimated absolute accuracy of NIGHTTIME corrected and uncorrected Vaisala RH measurements, as determined by comparison to simultaneous reference-quality measurements from Holger Voemel's (CU/CIRES) cryogenic frostpoint hygrometer (CFH), is given by Miloshevich et al. (2006).

  16. EA-2005: Chromium Plume Control Interim Measure And Plume-Center Characterization, Los Alamos National Laboratory, Los Alamos, NM

    Broader source: Energy.gov [DOE]

    This Environmental Assessment evaluates an interim measure to control chromium plume migration and maintain the 50 parts-per-billion (ppb) and greater chromium contamination level with the Los Alamos National Laboratory (LANL) boundary while long-term corrective action remedies are evaluated and implemented. Concentrations of chromium within the groundwater plume beneath Mortadad Canyon exceed the New Mexico groundwater standard of 50 ppb near the property boundary between LANL and the Pueblo de San Ildefonso and are as high as 1,000 ppb in the plume center.

  17. Correcting radar range measurements for atmospheric propagation...

    Office of Scientific and Technical Information (OSTI)

    Title: Correcting radar range measurements for atmospheric propagation effects. Abstract not provided. Authors: Doerry, Armin Walter Publication Date: 2013-12-01 OSTI Identifier: ...

  18. Northeast Site Non-Aqueous Phase Liquids Interim Measures Progress Report April through June 2003

    Office of Legacy Management (LM)

    7-TAC GJO-PIN 13.5.1-1 U.S. Department of Energy Work Performed Under DOE Contract No. for the U.S. Department of Energy DE-AC13-02GJ79491 Approved for public release; distribution is unlimited. Pinellas Environmental Restoration Project Northeast Site Non-Aqueous Phase Liquids Interim Measures Progress Report April Through June 2003 July 2003 N0063400 GJO- 2003- 467- TAC GJO-PIN 13.5.1-1 Pinellas Environmental Restoration Project Northeast Site Non-Aqueous Phase Liquids Interim Measures

  19. 2010-05 "Interim Measure for Volatile Organic Constituent Contaminant

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Source Removal in MAD-L and MDA-G" | Department of Energy 5 "Interim Measure for Volatile Organic Constituent Contaminant Source Removal in MAD-L and MDA-G" 2010-05 "Interim Measure for Volatile Organic Constituent Contaminant Source Removal in MAD-L and MDA-G" The intent of this recommendation is to remove large volumes of liquid waste VOCs from the ground and to prevent these contaminants from moving into the groundwater or to the atmosphere. The NNMCAB recognizes

  20. Engineering report single-shell tank farms interim measures to limit infiltration through the vadose zone

    SciTech Connect (OSTI)

    HAASS, C.C.

    1999-10-14

    Identifies, evaluates and recommends interim measures for reducing or eliminating water sources and preferential pathways within the vadose zone of the single-shell tank farms. Features studied: surface water infiltration and leaking water lines that provide recharge moisture, and wells that could provide pathways for contaminant migration. An extensive data base, maps, recommended mitigations, and rough order of magnitude costs are included.

  1. Comment Period Extended: EA-2005: Chromium Plume Control Interim Measure and Plume-Center Characterization, Los Alamos National Laboratory, Los Alamos, NM

    Broader source: Energy.gov [DOE]

    The Office of Environmental Management has extended the Public Comment Period on the Draft Environmental Assessment for Chromium Plume Control Interim Measure And Plume-Center Characterization, Los...

  2. ARM - PI Product - Radiosondes Corrected for Inaccuracy in RH Measurements

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    ProductsRadiosondes Corrected for Inaccuracy in RH Measurements ARM Data Discovery Browse Data Comments? We would love to hear from you! Send us a note below or call us at 1-888-ARM-DATA. Send PI Product : Radiosondes Corrected for Inaccuracy in RH Measurements Corrections for inaccuracy in Vaisala radiosonde RH measurements have been applied to ARM SGP radiosonde soundings. The magnitude of the corrections can vary considerably between soundings. The radiosonde measurement accuracy, and

  3. Interim Closure Activities at Corrective Action Unit 114: Area 25 EMAD Facility, Nevada National Security Site, Nevada

    SciTech Connect (OSTI)

    Boehlecke, R. F.

    2011-10-24

    This letter report documents interim activities that have been completed at CAU 114 to support ongoing access and generate information necessary to plan future closure activities. General housekeeping and cleanup of debris was conducted in the EMAD yard, cold bays, support areas of Building 3900, and postmortem cell tunnel area of the hot bay. All non-asbestos ceiling tiles and loose and broken non-friable asbestos floor tiles were removed from support galleries and office areas. Non-radiologically contaminated piping and equipment in the cold areas of the building and in the two 120-ton locomotives in the yard were tapped, characterized, drained, and verified free of contents.

  4. Interim Activities at Corrective Action Unit 114: Area 25 EMAD Facility, Nevada National Security Site, Nevada, for Fiscal Years 2012 and 2013

    SciTech Connect (OSTI)

    Silvas, A J

    2013-10-24

    This letter report documents interim activities that have been completed at CAU 114 in fiscal years 2012 and 2013.

  5. Space Charge Correction on Emittance Measurement of Low Energy...

    Office of Scientific and Technical Information (OSTI)

    of a charged particle beam through an accelerator and measure the emittance under the influence of space charge effects. We demonstrate the method of correctly calculating the...

  6. Spent Fuel Test - Climax: technical measurements. Interim report, fiscal year 1982

    SciTech Connect (OSTI)

    Patrick, W.C.; Ballou, L.B.; Butkovich, T.R.; Carlson, R.C.; Durham, W.B.; Hage, G.L.; Majer, E.L.; Montan, D.N.; Nyholm, R.A.; Rector, N.L.

    1983-02-01

    The Spent Fuel Test - Climax (SFT-C) is located 420 m below surface in the Climax stock granite on the Nevada Test Site. The test is being conducted for the US Department of Energy (DOE) under the technical direction of the Lawrence Livermore National Laboratory (LLNL). Eleven canisters of spent nuclear reactor fuel were emplaced, and six electrical simulators were energized April to May 1980, thus initiating a test with a planned 3- to 5-year fuel storage phase. The SFT-C operational objective of demonstrating the feasibility of packaging, transporting, storing, and retrieving highly radioactive fuel assemblies in a safe and reliable manner has been met. Three exchanges of spent fuel between the SFT-C and a surface storage facility furthered this demonstration. Technical objectives of the test led to development of a technical measurements program, which is the subject of this and two previous interim reports. Geotechnical, seismological, and test status data have been recorded on a continuing basis for the first 2-1/2 years of the test on more than 900 channels. Data continue to be acquired from the test. Some data are now available for analysis and are presented here. Highlights of activities this year include analysis of fracture data obtained during site characterization, laboratory studies of radiation effects and drilling damage in Climax granite, improved calculations of near-field heat transfer and thermomechanical response, a ventilation effects study, and further development of the data acquisition and management systems.

  7. Corrective measures evaluation report for Tijeras Arroyo groundwater.

    SciTech Connect (OSTI)

    Witt, Johnathan L; Orr, Brennon R.; Dettmers, Dana L.; Hall, Kevin A.; Howard, M. Hope

    2005-08-01

    This Corrective Measures Evaluation report was prepared as directed by a Compliance Order on Consent issued by the New Mexico Environment Department to document the process of selecting the preferred remedial alternative for Tijeras Arroyo Groundwater. Supporting information includes background concerning the site conditions and potential receptors and an overview of work performed during the Corrective Measures Evaluation. The evaluation of remedial alternatives included identifying and describing four remedial alternatives, an overview of the evaluation criteria and approach, comparing remedial alternatives to the criteria, and selecting the preferred remedial alternative. As a result of the Corrective Measures Evaluation, monitored natural attenuation of the contaminants of concern (trichloroethene and nitrate) is the preferred remedial alternative for implementation as the corrective measure for Tijeras Arroyo Groundwater. Design criteria to meet cleanup goals and objectives and the corrective measures implementation schedule for the preferred remedial alternative are also presented.

  8. On Correction of Diffuse Radiation Measured by MFRSR

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    On Correction of Diffuse Radiation Measured by MFRSR T. B. Zhuravleva Institute of Atmospheric Optics, SB RAS Tomsk, Russia M. A. Sviridenkov and P. P. Anikin A. M. Obukhov Institute of Atmospheric Physics, RAS Moscow, Russia Introduction The multi-filter rotated shadowband radiometer (MFRSR) provides spectral direct, diffuse, and total horizontal solar irradiance measurements. Because the MFRSR's receiver has a non-Lambertian response, for a correct interpretation of measured radiation an

  9. Corrective measures evaluation report for technical area-v groundwater.

    SciTech Connect (OSTI)

    Witt, Johnathan L; Orr, Brennon R.; Dettmers, Dana L.; Hall, Kevin A.; Howard, Hope

    2005-07-01

    This Corrective Measures Evaluation Report was prepared as directed by the Compliance Order on Consent issued by the New Mexico Environment Department to document the process of selecting the preferred remedial alternative for contaminated groundwater at Technical Area V. Supporting information includes background information about the site conditions and potential receptors and an overview of work performed during the Corrective Measures Evaluation. Evaluation of remedial alternatives included identification and description of four remedial alternatives, an overview of the evaluation criteria and approach, qualitative and quantitative evaluation of remedial alternatives, and selection of the preferred remedial alternative. As a result of the Corrective Measures Evaluation, it was determined that monitored natural attenuation of all contaminants of concern (trichloroethene, tetrachloroethene, and nitrate) was the preferred remedial alternative for implementation as the corrective measure to remediate contaminated groundwater at Technical Area V of Sandia National Laboratories/New Mexico. Finally, design criteria to meet cleanup goals and objectives and the corrective measures implementation schedule for the preferred remedial alternative are presented.

  10. Prediction and measurement of entrained flow coal gasification processes. Interim report, September 8, 1981-September 7, 1983

    SciTech Connect (OSTI)

    Hedman, P.O.; Smoot, L.D.; Fletcher, T.H.; Smith, P.J.; Blackham, A.U.

    1984-01-31

    This volume reports interim experimental and theoretical results of the first two years of a three year study of entrained coal gasification with steam and oxygen. The gasifier facility and testing methods were revised and improved. The gasifier was also modified for high pressure operation. Six successful check-out tests at elevated pressure were performed (55, 75, 100, 130, 170, and 215 psig), and 8 successful mapping tests were performed with the Utah bituminous coal at an elevated pressure of 137.5 psig. Also, mapping tests were performed at atmospheric pressure with a Utah bituminous coal (9 tests) and with a Wyoming subbituminous coal (14 tests). The LDV system was used on the cold-flow facility to make additional nonreactive jets mixing measurements (local mean and turbulent velocity) that could be used to help validate the two-dimensional code. The previously completed two-dimensional entrained coal gasification code, PCGC-2, was evaluated through rigorous comparison with cold-flow, pulverized coal combustion, and entrained coal gasification data. Data from this laboratory were primarily used but data from other laboratories were used when available. A complete set of the data used has been compiled into a Data Book which is included as a supplemental volume of this interim report. A revised user's manual for the two-dimensional code has been prepared and is also included as a part of this interim report. Three technical papers based on the results of this study were published or prepared. 107 references, 57 figures, 35 tables.

  11. 55-Gallon Drum Attenuation Corrections for Waste Assay Measurements

    SciTech Connect (OSTI)

    Casella, V.R.

    2002-04-03

    The present study shows how the percent attenuation for low-level waste (LLW), carbon-steel 55-gallon drums (44 and 46 mil) and for transuranic (TRU) DOT Type 7A 55-gallon drums (approximately 61 mil) changes with gamma energy from 60 keV to 1400 keV. Attenuation for these drums is in the range of 5 to 15 percent at energies from 400 to 1400 keV and from 15 to 35 percent at energies from 120 to 400 keV. At 60 keV, these drums attenuate 70-80 percent of the gamma rays. Correction factors were determined in order to correct for gamma attenuation of a TRU drum if a calibration is performed with a LLW drum. These correction factors increase the activities of the TRU drum by from 10 percent to 2 percent in the energy range of 165 to 1400 keV, with an increase of about 50 percent at 60 keV. Correction factors for TRU drums and for analyses without a drum were used to adjust the percent yield for frequently measured gamma rays, so that the assay libraries could be modified to provide the drum attenuation corrections.

  12. Spatial corrections for pulsed-neutron reactivity measurements.

    SciTech Connect (OSTI)

    Cao, Y.; Lee, J.; Nuclear Engineering Division; Univ. of Michigan

    2010-07-01

    For pulsed-neutron experiments performed in a subcritical reactor, the reactivity obtained from the area-ratio method is sensitive to detector positions. The spatial effects are induced by the presence of both the prompt neutron harmonics and the delayed neutron harmonics in the reactor. The traditional kinetics distortion factor is only limited to correcting the spatial effects caused by the fundamental prompt-{alpha} mode. In this paper, we derive spatial correction factors fp and fd to account for spatial effects induced by the prompt neutron harmonics and the delayed neutron harmonics, respectively. Our numerical simulations with the FX2-TH time-dependent multigroup diffusion code indicate that the high-order prompt neutron harmonics lead to significant spatial effects and cannot be neglected in calculating the spatial correction factors. The prompt spatial correction factor fp can be simply determined by the ratio of the normalized detector responses corresponding to the fundamental k-mode and the prompt neutron flux integrated over the pulse period. Thus, it is convenient to calculate and provides physically intuitive explanations on the spatial dependence of reactivity measured in the MUSE-4 experiments: overestimation of the subcriticality in regions close to the external neutron source and underestimation of the subcriticality away from the source but within the fuel region.

  13. ARM: SIRS: derived, correction of downwelling shortwave diffuse hemispheric measurements using Dutton and full algorithm

    DOE Data Explorer [Office of Scientific and Technical Information (OSTI)]

    Laura Riihimaki

    1997-03-21

    SIRS: derived, correction of downwelling shortwave diffuse hemispheric measurements using Dutton and full algorithm

  14. Method for measuring multiple scattering corrections between liquid scintillators

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Verbeke, J. M.; Glenn, A. M.; Keefer, G. J.; Wurtz, R. E.

    2016-04-11

    In this study, a time-of-flight method is proposed to experimentally quantify the fractions of neutrons scattering between scintillators. An array of scintillators is characterized in terms of crosstalk with this method by measuring a californium source, for different neutron energy thresholds. The spectral information recorded by the scintillators can be used to estimate the fractions of neutrons multiple scattering. With the help of a correction to Feynman's point model theory to account for multiple scattering, these fractions can in turn improve the mass reconstruction of fissile materials under investigation.

  15. CMM Interim Check (U)

    SciTech Connect (OSTI)

    Montano, Joshua Daniel

    2015-03-23

    Coordinate Measuring Machines (CMM) are widely used in industry, throughout the Nuclear Weapons Complex and at Los Alamos National Laboratory (LANL) to verify part conformance to design definition. Calibration cycles for CMMs at LANL are predominantly one year in length. Unfortunately, several nonconformance reports have been generated to document the discovery of a certified machine found out of tolerance during a calibration closeout. In an effort to reduce risk to product quality two solutions were proposed – shorten the calibration cycle which could be costly, or perform an interim check to monitor the machine’s performance between cycles. The CMM interim check discussed makes use of Renishaw’s Machine Checking Gauge. This off-the-shelf product simulates a large sphere within a CMM’s measurement volume and allows for error estimation. Data was gathered, analyzed, and simulated from seven machines in seventeen different configurations to create statistical process control run charts for on-the-floor monitoring.

  16. EIS-0163-S: Supplemental EIS/1993 Interim Columbia and Snake Rivers Flow Improvement Measures for Salmon

    Broader source: Energy.gov [DOE]

    The U.S. Army Corps of Engineers – Walla Walla District has prepared this statement to assess alternatives to improve flows of water in the lower Columbia-Snake rivers in 1993 and future years to assist the migration of juvenile and adult anadromous fish past eight hydropower dams. The U.S. Department of Energy’s Bonneville Power Administration served as a cooperating agency in developing this supplement due to its key role in direct operation of the integrated and coordinated Columbia-Snake River System, and adopted this statement in March of 1993. This statement supplements the 1992 Columbia River Salmon Flow Measures Options Analysis Environmental Impact Statement, which evaluated ways to alter water management operations in 1992 on the lower Columbia and Snake rivers to enhance the survival of wild Snake River salmon.

  17. Interim Columbia and Snake rivers flow improvement measures for salmon: Final Supplemental Environmental Impact Statement (SEIS)

    SciTech Connect (OSTI)

    Not Available

    1993-03-01

    Public comments are sought on this final SEIS, which supplements the 1992 Columbia River Salmon Flow Measures Options Analysis (OA)/Environmental Impact Statement (EIS). The Corps of Engineers, in cooperation with the Bonneville Power Administration and the Bureau of Reclamation proposes five alternatives to improve flows of water in the lower Columbia-Snake rivers in 1993 and future years to assist the migration of juvenile and adult anadromous fish past eight hydropower dams. These are: (1) Without Project (no action) Alternative, (2) the 1992 Operation, (3) the 1992 Operation with Libby/Hungry Horse Sensitivity, (4) a Modified 1992 Operation with Improvements to Salmon Flows from Dworshak, and (5) a Modified 1992 Operation with Upper Snake Sensitivity. Alternative 4, Modified 1992 Operations, has been identified as the preferred alternative.

  18. Spent fuel test - Climax: technical measurements. Interim report, fiscal year 1981

    SciTech Connect (OSTI)

    Patrick, W.C.; Ballou, L.B.; Butkovich, T.R.

    1982-04-30

    The Spent Fuel Test-Climax (SFT-C) is located 420 m below surface in the Climax granite stock on the Nevada Test Site. Eleven canisters of spent nuclear reactor fuel were emplaced, and six electrical simulators were energized from April to May 1980, initiating the 3- to 5-year-duration test. The SFT-C operational objective of demonstrating the feasibility of packaging, transporting, storing, and retrieving highly radioactive fuel assemblies in a safe and reliable manner has been met. Technical objectives of the test led to development of a technical measurements program, which is the subject of this report. Geotechnical, seismological, and test status data have been recorded on a continuing basis for the first 1-1/2 years of the test on more than 900 channels. Much of the acquired data are now available for analysis and are presented here. Highlights of activities this year include completion of site characterization field work, major modifications to the data acquisition and the management systems, and the addition of instrument evaluation as an explicit objective of the test.

  19. Optics measurement and correction during acceleration with beta-squeeze in RHIC

    SciTech Connect (OSTI)

    Liu, C.; Marusic, A.; Minty, M.

    2015-05-03

    In the past, beam optics correction at RHIC has only taken place at injection and at final energy, with interpolation of corrections partially into the acceleration cycle. Recent measurements of the beam optics during acceleration and squeeze have evidenced significant beta-beats that, if corrected, could minimize undesirable emittance dilutions and maximize the spin polarization of polarized proton beams by avoiding the high-order multipole fields sampled by particles within the bunch. We recently demonstrated successful beam optics corrections during acceleration at RHIC. We verified conclusively the superior control of the beam realized via these corrections

  20. Linear optics measurements and corrections using an AC dipole in RHIC

    SciTech Connect (OSTI)

    Wang, G.; Bai, M.; Yang, L.

    2010-05-23

    We report recent experimental results on linear optics measurements and corrections using ac dipole. In RHIC 2009 run, the concept of the SVD correction algorithm is tested at injection energy for both identifying the artificial gradient errors and correcting it using the trim quadrupoles. The measured phase beatings were reduced by 30% and 40% respectively for two dedicated experiments. In RHIC 2010 run, ac dipole is used to measure {beta}* and chromatic {beta} function. For the 0.65m {beta}* lattice, we observed a factor of 3 discrepancy between model and measured chromatic {beta} function in the yellow ring.

  1. Resource Conservation and Recovery Act corrective measures study: Area 6 decontamination pond facility, corrective action unit no. 92

    SciTech Connect (OSTI)

    1997-10-01

    Corrective Action Unit (CAU) No. 92, the Area 6 Decontamination Pond Facility (DPF), is an historic disposal unit located at the Nevada Test Site (NTS) in Nye County, Nevada (Figures 1 - 1, 1-2, and 1-3). The NTS is operated by the U.S. Department of Energy, Nevada Operations Office (DOE/NV), which has been required by the Nevada Division of Environmental Protection (NDEP) to characterize the DPF under the requirements of the Resource Conservation and Recovery Act (RCRA) Part A Permit (NDEP, 1995) for the NTS and Title 40 Code of Federal Regulations (CFR) Part 265 (1996c). The DPF is prioritized in the Federal Facility Agreement and Consent Order (FFACO, 1996) but is governed by the permit. The DPF was characterized through sampling events in 1994, 1996, and 1997. The results of these sampling events are contained in the Final Resource Conservation and Recovery Act Industrial Site Environmental Restoration Site Characterization Report, Area 6 Decontamination Pond Facility, Revision I (DOE/NV, 1997). This Corrective Measures Study (CMS) for the Area 6 DPF has been prepared for the DOE/NV`s Environmental Restoration Project. The CMS has been developed to support the preparation of a Closure Plan for the DPF. Because of the complexities of the contamination and regulatory issues associated with the DPF, DOE/NV determined a CMS would be beneficial to the evaluation and selection of a closure alternative.

  2. Correction of motion measurement errors beyond the range resolution of a synthetic aperture radar

    DOE Patents [OSTI]

    Doerry, Armin W. (Albuquerque, NM); Heard, Freddie E. (Albuquerque, NM); Cordaro, J. Thomas (Albuquerque, NM)

    2008-06-24

    Motion measurement errors that extend beyond the range resolution of a synthetic aperture radar (SAR) can be corrected by effectively decreasing the range resolution of the SAR in order to permit measurement of the error. Range profiles can be compared across the slow-time dimension of the input data in order to estimate the error. Once the error has been determined, appropriate frequency and phase correction can be applied to the uncompressed input data, after which range and azimuth compression can be performed to produce a desired SAR image.

  3. An Improved Daylight Correction for IR Loss in ARM Diffuse SW Measurements

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    An Improved Daylight Correction for IR Loss in ARM Diffuse SW Measurements C. N. Long, K. Younkin, and K. L. Gaustad Pacific Northwest National Laboratory Richland, Washington J. A. Augustine National Oceanic and Atmospheric Administration Air Resources Laboratory Surface Radiation Research Branch Boulder, Colorado Introduction A paper by Cess et al. (2000) notes that some clear-sky diffuse shortwave (SW) measurements they were using from the Atmospheric Radiation Measurement (ARM) Southern

  4. Optics measurement and correction during beam acceleration in the Relativistic Heavy Ion Collider

    SciTech Connect (OSTI)

    Liu, C.; Marusic, A.; Minty, M.

    2014-09-09

    To minimize operational complexities, setup of collisions in high energy circular colliders typically involves acceleration with near constant β-functions followed by application of strong focusing quadrupoles at the interaction points (IPs) for the final beta-squeeze. At the Relativistic Heavy Ion Collider (RHIC) beam acceleration and optics squeeze are performed simultaneously. In the past, beam optics correction at RHIC has taken place at injection and at final energy with some interpolation of corrections into the acceleration cycle. Recent measurements of the beam optics during acceleration and squeeze have evidenced significant beta-beats which if corrected could minimize undesirable emittance dilutions and maximize the spin polarization of polarized proton beams by avoidance of higher-order multipole fields sampled by particles within the bunch. In this report the methodology now operational at RHIC for beam optics corrections during acceleration with simultaneous beta-squeeze will be presented together with measurements which conclusively demonstrate the superior beam control. As a valuable by-product, the corrections have minimized the beta-beat at the profile monitors so reducing the dominant error in and providing more precise measurements of the evolution of the beam emittances during acceleration.

  5. RCRA corrective action and closure

    SciTech Connect (OSTI)

    Not Available

    1995-02-01

    This information brief explains how RCRA corrective action and closure processes affect one another. It examines the similarities and differences between corrective action and closure, regulators` interests in RCRA facilities undergoing closure, and how the need to perform corrective action affects the closure of DOE`s permitted facilities and interim status facilities.

  6. CMM Interim Check Design of Experiments (U)

    SciTech Connect (OSTI)

    Montano, Joshua Daniel

    2015-07-29

    Coordinate Measuring Machines (CMM) are widely used in industry, throughout the Nuclear Weapons Complex and at Los Alamos National Laboratory (LANL) to verify part conformance to design definition. Calibration cycles for CMMs at LANL are predominantly one year in length and include a weekly interim check to reduce risk. The CMM interim check makes use of Renishaw’s Machine Checking Gauge which is an off-the-shelf product simulates a large sphere within a CMM’s measurement volume and allows for error estimation. As verification on the interim check process a design of experiments investigation was proposed to test a couple of key factors (location and inspector). The results from the two-factor factorial experiment proved that location influenced results more than the inspector or interaction.

  7. Development of an EMF Measurements Database, EMF Rapid Program, Project #5, Interim Report: April 1995-December 1996

    SciTech Connect (OSTI)

    T. Dan Bracken, Inc.

    1997-04-01

    The EMF measurement data sets in existence today were compiled with varying goals and techniques. Consequently, they have different information content as well as varying logical and physical structure. Future studies will continue to pursue varying goals and utilize techniques that cannot be known in advance. Primary goals for the EMF Measurements Database developed under the Department of Energy EMF RAPID Program are to develop a database structure that can accommodate the diversity of EMF data sets, provide guidance for production of future EMF data sets, and serve as an accessible repository of EMF measurement data. Specific objectives of the EMF Measurements Database are: o to preserve study descriptions, results and data; o to provide readily accessible, well-documented data; and o to facilitate communication among researchers. In addition, the EMF Measurements Database will encourage additional analysis of existing data sets, facilitate analysis of data from multiple projects, support design of new studies, and permit future issues in EMF exposure assessment to be addressed with existing data. Preservation of study descriptions and data is accomplished with a formal, but open, structure. Specifications have been developed for the various elements of the database. Each data set in the database is formally described by a metadata file. The structured metadata file describes the origin, development, logical and physical structure and distribution mechanism for each data set. The metadata for each data set is generated according to a specification developed for the EMF Measurements Database. The actual measurement data is contained in data Products for each data set. The number and type of data product will vary by data set. Most of the data products in the possession of the EMF Measurements Database are available for download from an Internet site. For some data sets, the data products will be maintained by other parties who may have their own access procedures

  8. A Method of Correcting for Tilt From Horizontal in Downwelling Shortwave Irradiance Measurements on Moving Platforms

    SciTech Connect (OSTI)

    Long, Charles N.; Bucholtz, Anthony; Jonsson, Haf; Schmid, Beat; Vogelmann, A. M.; Wood, John

    2010-04-14

    Significant errors occur in downwelling shortwave irradiance measurements made on moving platforms due to tilt from horizontal because, when the sun is not completely blocked by overhead cloud, the downwelling shortwave irradiance has a prominent directional component from the direct sun. A-priori knowledge of the partitioning between the direct and diffuse components of the total shortwave irradiance is needed to properly apply a correction for tilt. This partitioning information can be adequately provided using a newly available commercial radiometer that produces reasonable measurements of the total and diffuse shortwave irradiance, and by subtraction the direct shortwave irradiance, with no moving parts and regardless of azimuthal orientation. We have developed methodologies for determining the constant pitch and roll offsets of the radiometers for aircraft applications, and for applying a tilt correction to the total shortwave irradiance data. Results suggest that the methodology is for tilt up to +/-10°, with 90% of the data corrected to within 10 Wm-2 at least for clear-sky data. Without a proper tilt correction, even data limited to 5° of tilt as is typical current practice still exhibits large errors, greater than 100 Wm-2 in some cases. Given the low cost, low weight, and low power consumption of the SPN1 total and diffuse radiometer, opportunities previously excluded for moving platform measurements such as small Unmanned Aerial Vehicles and solar powered buoys now become feasible using our methodology. The increase in measurement accuracy is important, given current concerns over long-term climate variability and change especially over the 70% of the Earth’s surface covered by ocean where long-term records of these measurements are sorely needed and must be made on ships and buoys.

  9. Measurement of the $B^-$ lifetime using a simulation free approach for trigger bias correction

    SciTech Connect (OSTI)

    Aaltonen, T.; Adelman, J.; Alvarez Gonzalez, B.; Amerio, S.; Amidei, D.; Anastassov, A.; Annovi, A.; Antos, J.; Apollinari, G.; Appel, J.; Apresyan, A.

    2010-04-01

    The collection of a large number of B hadron decays to hadronic final states at the CDF II detector is possible due to the presence of a trigger that selects events based on track impact parameters. However, the nature of the selection requirements of the trigger introduces a large bias in the observed proper decay time distribution. A lifetime measurement must correct for this bias and the conventional approach has been to use a Monte Carlo simulation. The leading sources of systematic uncertainty in the conventional approach are due to differences between the data and the Monte Carlo simulation. In this paper they present an analytic method for bias correction without using simulation, thereby removing any uncertainty between data and simulation. This method is presented in the form of a measurement of the lifetime of the B{sup -} using the mode B{sup -} {yields} D{sup 0}{pi}{sup -}. The B{sup -} lifetime is measured as {tau}{sub B{sup -}} = 1.663 {+-} 0.023 {+-} 0.015 ps, where the first uncertainty is statistical and the second systematic. This new method results in a smaller systematic uncertainty in comparison to methods that use simulation to correct for the trigger bias.

  10. Interim explosives detection alternatives

    SciTech Connect (OSTI)

    Syler, R.P. )

    1991-01-01

    There is a general concern with insiders smuggling bomb quantities of explosives into sensitive facilities such as nuclear facilities. At this time, there is no single explosives detection device that is suitable for monitoring personnel and their packages for explosives in an operational facility environment. However, there are techniques combining available commercial technologies with procedures and threat analysis that can significantly increase the insiders risk and reduce the population of adversaries. This paper describes the available applicable explosives detection technologies and discusses the techniques that could be implemented on an interim basis. It is important that these techniques be considered, so that some interim level of security against the explosives threat can be established until more sophisticated equipment that is under development becomes available.

  11. Interim Action Determination

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Interim Action Determination Processing of Plutonium Materials from the DOE Standard 3013 Surveillance Program in H-Canyon at the Savannah River Site The Department of Energy (DOE) is preparing the Surplus Plutonium Disposition Supplemental Environmental Impact Statement (SPD SEIS, DOE/EIS-0283-S2). DOE is evaluating alternatives for disposition of non-pit plutonium that is surplus to the national security needs of the United States. Although the Deputy Secretary of Energy approved Critical

  12. A background correction algorithm for Van Allen Probes MagEIS electron flux measurements

    SciTech Connect (OSTI)

    Claudepierre, S. G.; O'Brien, T. P.; Blake, J. B.; Fennell, J. F.; Roeder, J. L.; Clemmons, J. H.; Looper, M. D.; Mazur, J. E.; Mulligan, T. M.; Spence, H. E.; Reeves, G. D.; Friedel, R. H. W.; Henderson, M. G.; Larsen, B. A.

    2015-07-14

    We describe an automated computer algorithm designed to remove background contamination from the Van Allen Probes Magnetic Electron Ion Spectrometer (MagEIS) electron flux measurements. We provide a detailed description of the algorithm with illustrative examples from on-orbit data. We find two primary sources of background contamination in the MagEIS electron data: inner zone protons and bremsstrahlung X-rays generated by energetic electrons interacting with the spacecraft material. Bremsstrahlung X-rays primarily produce contamination in the lower energy MagEIS electron channels (~30–500 keV) and in regions of geospace where multi-M eV electrons are present. Inner zone protons produce contamination in all MagEIS energy channels at roughly L < 2.5. The background-corrected MagEIS electron data produce a more accurate measurement of the electron radiation belts, as most earlier measurements suffer from unquantifiable and uncorrectable contamination in this harsh region of the near-Earth space environment. These background-corrected data will also be useful for spacecraft engineering purposes, providing ground truth for the near-Earth electron environment and informing the next generation of spacecraft design models (e.g., AE9).

  13. A background correction algorithm for Van Allen Probes MagEIS electron flux measurements

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Claudepierre, S. G.; O'Brien, T. P.; Blake, J. B.; Fennell, J. F.; Roeder, J. L.; Clemmons, J. H.; Looper, M. D.; Mazur, J. E.; Mulligan, T. M.; Spence, H. E.; et al

    2015-07-14

    We describe an automated computer algorithm designed to remove background contamination from the Van Allen Probes Magnetic Electron Ion Spectrometer (MagEIS) electron flux measurements. We provide a detailed description of the algorithm with illustrative examples from on-orbit data. We find two primary sources of background contamination in the MagEIS electron data: inner zone protons and bremsstrahlung X-rays generated by energetic electrons interacting with the spacecraft material. Bremsstrahlung X-rays primarily produce contamination in the lower energy MagEIS electron channels (~30–500 keV) and in regions of geospace where multi-M eV electrons are present. Inner zone protons produce contamination in all MagEIS energymore » channels at roughly L < 2.5. The background-corrected MagEIS electron data produce a more accurate measurement of the electron radiation belts, as most earlier measurements suffer from unquantifiable and uncorrectable contamination in this harsh region of the near-Earth space environment. These background-corrected data will also be useful for spacecraft engineering purposes, providing ground truth for the near-Earth electron environment and informing the next generation of spacecraft design models (e.g., AE9).« less

  14. Interim storage study report

    SciTech Connect (OSTI)

    Rawlins, J.K.

    1998-02-01

    High-level radioactive waste (HLW) stored at the Idaho Chemical Processing Plant (ICPP) in the form of calcine and liquid and liquid sodium-bearing waste (SBW) will be processed to provide a stable waste form and prepare the waste to be transported to a permanent repository. Because a permanent repository will not be available when the waste is processed, the waste must be stored at ICPP in an Interim Storage Facility (ISF). This report documents consideration of an ISF for each of the waste processing options under consideration.

  15. THE CALCULATION OF BURNABLE POISON CORRECTION FACTORS FOR PWR FRESH FUEL ACTIVE COLLAR MEASUREMENTS

    SciTech Connect (OSTI)

    Croft, Stephen; Favalli, Andrea; Swinhoe, Martyn T.

    2012-06-19

    {sub 2}O{sub 3} burnable poison on the measurement of fresh pressurized water reactor fuel. To empirically determine the response function over the range of historical and future use we have considered enrichments up to 5 wt% {sup 235}U/{sup tot}U and Gd weight fractions of up to 10 % Gd/UO{sub 2}. Parameterized correction factors are presented.

  16. The main injector chromaticity correction sextupole magnets: Measurements and operating schemes

    SciTech Connect (OSTI)

    Bhat, C.M.; Bogacz, A.; Brown, B.C.; Harding, D.J.; Fang, S.J.; Martin, P.S.; Glass, H.D.; Sim, J.

    1995-05-01

    The Fermilab Main Injector (FMI) is a high intensity proton synchrotron which will be used to accelerate protons and antiprotons from 8.9 GeV/c to 150 GeV/c. The natural chromaticities of the machine for the horizontal and the vertical Planes are {minus}33.6 and {minus}33.9 respectively. The {Delta}p/p of the beam at injection is about 0.002. The chromaticity requirements of the FMI, are primarily decided by the {Delta}p/p = 0.002 of the beam at injection. This limits the final chromaticity of the FMI to be {plus_minus}5 units. To correct the chromaticity in the FMI two families of sextupole magnets will be installed in the lattice, one for each plane. A sextupole magnet suitable for the FMI needs has been designed and a number of them are being built. New chromaticity compensation schemes have been worked out in the light of recently proposed faster acceleration ramps. On an R/D sextupole magnet the low current measurements have been carried out to determine the electrical properties. Also, using a Morgan coil, measurements have been performed to determine the higher ordered multipole components up to 18-poles. An overview of these result are presented here.

  17. Decreasing range resolution of a SAR image to permit correction of motion measurement errors beyond the SAR range resolution

    DOE Patents [OSTI]

    Doerry, Armin W. (Albuquerque, NM); Heard, Freddie E. (Albuquerque, NM); Cordaro, J. Thomas (Albuquerque, NM)

    2010-07-20

    Motion measurement errors that extend beyond the range resolution of a synthetic aperture radar (SAR) can be corrected by effectively decreasing the range resolution of the SAR in order to permit measurement of the error. Range profiles can be compared across the slow-time dimension of the input data in order to estimate the error. Once the error has been determined, appropriate frequency and phase correction can be applied to the uncompressed input data, after which range and azimuth compression can be performed to produce a desired SAR image.

  18. SU-E-T-628: Effect of Dose Rate and Leakage Correction for Dosimetric Leaf Gap Measurement

    SciTech Connect (OSTI)

    Feng, W; Chu, A; Chi, Y; Hu, J

    2014-06-15

    Purpose: To study the dose rate response of Mapcheck and quantify/correct dose rate/leakage effect on IMRT QA. Evaluate the dose rate/leakage effect on dosimetric leaf gap (DLG) measurement. Methods: Varian Truebeam Linac with HD120 MLC was used for all measurement, it is capable to adjust dose rate from 600MU/min to 5MU/min. Fluke Advanced Therapy Doisemter and PTW 30013 Farmer chamber for chamber measurement; SunNuclear Mapcheck2 with 5cm total buildup for diode measurement. DLG was measured with both chamber and diode.Diode response was measured by varies dose rate, while fixed mapcheck setup and total MU. MLC Leakage was measured with both chamber and diode. Mapcheck measurement was saved as movie file (mcm file), which include measurement updated every 50mSec. The difference between intervals can be converted to dose and dose rate and leakage response correction can be applied to them. Results: DLG measurement results with chamber and diode were showed as follows, the DLG value is 0.36 vs. 0.24mm respectively. Diode dose rate response drops from 100% at 600MU/min to 95.5% at 5MU/min as follows. MLC Leakage measured with diode is 1.021%, which is 9% smaller than 1.112% from chamber measurement. By apply the dose rate and leakage correction, the residue error reduced 2/3. Conclusions: Diode has lower response at lower dose rate, as low as 4.5% for 5MU/min; diode has lower energy response for low energy too, 5% lower for Co-60 than 6MV. It partially explains the leakage difference of 9% between chamber and diode. Lower DLG with diode is because of the lower response at narrower gap, in Eclipse however DLG need to increase to makeup lower response, which is over correction for chamber though. Correction can reduce error by 2/3, the rest 1/3 can be corrected by scatter effect, which is under study.

  19. ROTATIONAL CORRECTIONS TO NEUTRON-STAR RADIUS MEASUREMENTS FROM THERMAL SPECTRA

    SciTech Connect (OSTI)

    Baubck, Michi; zel, Feryal; Psaltis, Dimitrios; Morsink, Sharon M.

    2015-01-20

    We calculate the rotational broadening in the observed thermal spectra of neutron stars spinning at moderate rates in the Hartle-Thorne approximation. These calculations accurately account for the effects of the second-order Doppler boosts as well as for the oblate shapes and the quadrupole moments of the neutron stars. We find that fitting the spectra and inferring the bolometric fluxes under the assumption that a star is not rotating causes an underestimate of the inferred fluxes and, thus, radii. The correction depends on the stellar spin, mass, radius, and the observer's inclination. For a 10km, 1.4 M {sub ?} neutron star spinning at 600Hz, the rotational correction to the flux is ?1%-4%, while for a 15km neutron star with the same spin period, the correction ranges from 2% for pole-on sources to 12% for edge-on sources. We calculate the inclination-averaged corrections to inferred radii as a function of the neutron-star radius and mass and provide an empirical formula for the corrections. For realistic neutron-star parameters (1.4 M {sub ?}, 12km, 600Hz), the stellar radius is on the order of 4% larger than the radius inferred under the assumption that the star is not spinning.

  20. Corrective measures technology for shallow land burial at arid sites: field studies of biointrusion barriers and erosion control

    SciTech Connect (OSTI)

    Nyhan, J.W.; Hakonson, T.E.; Lopez, E.A.

    1986-03-01

    The field research program involving corrective measures technologies for arid shallow land burial (SLB) sites is described. Results of field testing of a biointrusion barrier installed at a close-out waste disposal site (Area B) at Los Alamos are presented. Soil erosion and infiltration of water into a simulated trench cap with various surface treatments were measured, and the interaction between erosion control and subsurface water dynamics is discussed relative to waste management.

  1. Improved self-absorption correction for extended x-ray absorption fine-structure measurements

    SciTech Connect (OSTI)

    Booth, C.H.; Bridges, F.

    2003-06-04

    Extended x-ray absorption fine-structure (EXAFS) data collected in the fluorescence mode are susceptible to an apparent amplitude reduction due to the self-absorption of the fluorescing photon by the sample before it reaches a detector. Previous treatments have made the simplifying assumption that the effect of the EXAFS on the correction term is negligible, and that the samples are in the thick limit. We present a nearly exact treatment that can be applied for any sample thickness or concentration, and retains the EXAFS oscillations in the correction term.

  2. Systematic corrections to the measured cosmological constant as a result of local inhomogeneity

    SciTech Connect (OSTI)

    Vanderveld, R. Ali; Flanagan, Eanna E.; Wasserman, Ira

    2007-10-15

    We explicitly calculate the lowest order systematic inhomogeneity-induced corrections to the cosmological constant that one would infer from an analysis of the luminosities and redshifts of type Ia supernovae, assuming a homogeneous universe. The calculation entails a post-Newtonian expansion within the framework of second-order perturbation theory, wherein we consider the effects of subhorizon density perturbations in a flat, dust-dominated universe. Within this formalism, we calculate luminosity distances and redshifts along the past light cone of an observer. The luminosity distance-redshift relation is then averaged over viewing angles and ensemble averaged, assuming that density fluctuations at a given cosmic time are a homogeneous random process. The resulting relation is fit to that of a homogeneous model containing dust and a cosmological constant, in order to deduce the best-fit cosmological constant density {omega}{sub {lambda}}. We find that the luminosity distance-redshift relation is indeed modified, even for large sample sizes, but only by a very small fraction, of order 10{sup -5} for z{approx}0.1. This lowest order deviation depends on the peculiar velocities of the source and the observer. However, when fitting this perturbed relation to that of a homogeneous universe, via maximizing a likelihood function, we find that the inferred cosmological constant can be surprisingly large, depending on the range of redshifts sampled. For a sample of supernovae extending from z{sub min}=0.02 out to a limiting redshift z{sub max}=0.15, we find that {omega}{sub {lambda}}{approx_equal}0.004. The value of {omega}{sub {lambda}} has a large variance, and its magnitude tends to get progressively larger as the limiting redshift z{sub max} gets smaller, implying that precision measurements of {omega}{sub {lambda}} from nearby supernova data will require taking this effect into account. This effect has been referred to in the past as the 'fitting problem', and more

  3. Determining initial enrichment, burnup, and cooling time of pressurized-water reactor spent fuel assemblies by analyzing passive gamma spectra measured at the Clab interim-fuel storage facility in Sweden

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Favalli, Andrea; Vo, D.; Grogan, Brandon R.; Jansson, Peter; Liljenfeldt, Henrik; Mozin, Vladimir; Schwalbach, P.; Sjoland, A.; Tobin, Stephen J.; Trellue, Holly; et al

    2016-02-26

    The purpose of the Next Generation Safeguards Initiative (NGSI)–Spent Fuel (SF) project is to strengthen the technical toolkit of safeguards inspectors and/or other interested parties. The NGSI–SF team is working to achieve the following technical goals more easily and efficiently than in the past using nondestructive assay measurements of spent fuel assemblies: (1) verify the initial enrichment, burnup, and cooling time of facility declaration; (2) detect the diversion or replacement of pins; (3) estimate the plutonium mass [which is also a function of the variables in (1)]; (4) estimate the decay heat; and (5) determine the reactivity of spent fuelmore » assemblies. Since August 2013, a set of measurement campaigns has been conducted at the Central Interim Storage Facility for Spent Nuclear Fuel (Clab), in collaboration with Swedish Nuclear Fuel and Waste Management Company (SKB). One purpose of the measurement campaigns was to acquire passive gamma spectra with high-purity germanium and lanthanum bromide scintillation detectors from Pressurized Water Reactor and Boiling Water Reactor spent fuel assemblies. The absolute 137Cs count rate and the 154Eu/137Cs, 134Cs/137Cs, 106Ru/137Cs, and 144Ce/137Cs isotopic ratios were extracted; these values were used to construct corresponding model functions (which describe each measured quantity’s behavior over various combinations of burnup, cooling time, and initial enrichment) and then were used to determine those same quantities in each measured spent fuel assembly. Furthermore, the results obtained in comparison with the operator declared values, as well as the methodology developed, are discussed in detail in the paper.« less

  4. Conversion and correction factors for historical measurements of Iodine-131 in Hanford-area vegetation, 1945--1947: Draft

    SciTech Connect (OSTI)

    Mart, E.I.; Denham, D.H.; Thiede, M.E.

    1993-05-01

    This report is a result of the Hanford Environmental Dose Reconstruction (HEDR) Project whose goal is to estimate the radiation dose that individuals could have received from emissions since 1944 at the US Department of Energy's (DOE) Hanford Site near Richland, Washington. The report describes in detail the reconstructed conversion and correction factors for historical measurements of iodine-131 in Hanford-area vegetation which was collected from the beginning of October 1945 through the end of December 1947.

  5. Erosion Potential of a Burn Site in the Mojave-Great Basin Transition Zone: Interim Summary of One Year of Measurements

    SciTech Connect (OSTI)

    Etyemezian, V.; Shafer, D.; Miller, J.; Kavouras, I.; Campbell, S.; DuBois, D.; King, J.; Nikolich, G.; Zitzer, S.

    2010-05-18

    A historic return interval of 100 years for large fires in deserts in the Southwest U.S. is being replaced by one where fires may reoccur as frequently as every 20 to 30 years. This increase in fires has implications for management of Soil Sub-Project Corrective Action Units (CAUs) for which the Department of Energy, National Nuclear Security Administration Nevada Site office (NNSA/NSO) has responsibility. A series of studies has been initiated at uncontaminated analog sites to better understand the possible impacts of erosion and transport by wind and water should contaminated soil sites burn over to understand technical and perceived risk they might pose to site workers and public receptors in communities around the NTS, TTR, and NTTR; and to develop recommendations for stabilization and restoration after a fire. The first of these studies was undertaken at the Jacob fire, a lightning-caused fire approximately 12 kilometers north of Hiko, Nevada, that burned approximately 200 ha between August 6-8, 2008, and is representative of a transition zone on the NTS between the Mojave and Great Basin Deserts, where the largest number of Soil Sub-Project CAUs/CASs are located.

  6. Memorandum, Interim Procedures During Temporary Suspension of...

    Broader source: Energy.gov (indexed) [DOE]

    hiring, credentialing and eligibility determinations during the period of e-QIP suspension. Memorandum, Interim Procedures During Temporary Suspension of Electronic...

  7. Kathleen Carlson Appointed Interim Acting Deputy Administrator...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Kathleen Carlson Appointed Interim Acting Deputy Administrator for Defense Programs | National Nuclear Security Administration Facebook Twitter Youtube Flickr RSS People Mission...

  8. Interim Guidance Regarding Limitations on CERCLA Liability |...

    Open Energy Info (EERE)

    search OpenEI Reference LibraryAdd to library PermittingRegulatory Guidance - Inner-Office Memorandum: Interim Guidance Regarding Limitations on CERCLA LiabilityPermitting...

  9. Memorandum on the Interim Report of the Commission to Review...

    Office of Environmental Management (EM)

    the Interim Report of the Commission to Review the Effectiveness of the National Energy Laboratories Memorandum on the Interim Report of the Commission to Review the Effectiveness...

  10. VTA Prototype Fuel Cell Bus Evaluation: Interim Results (Presentation...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    VTA Prototype Fuel Cell Bus Evaluation: Interim Results (Presentation) VTA Prototype Fuel Cell Bus Evaluation: Interim Results (Presentation) Details hydrogen fuel cell buses being ...

  11. BLM Interim Competitive Procedures for SEZs | Open Energy Information

    Open Energy Info (EERE)

    Not Provided DOI Not Provided Check for DOI availability: http:crossref.org Online Internet link for BLM Interim Competitive Procedures for SEZs Citation BLM Interim Competitive...

  12. Interim Report on Customer Acceptance, Retention, and Response...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Interim Report on Customer Acceptance, Retention, and Response to Time-Based Rates from the Consumer Behavior Studies (June 2015) Interim Report on Customer Acceptance, Retention, ...

  13. Now Available: Interim Report on Customer Acceptance, Retention...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Interim Report on Customer Acceptance, Retention, and Response to Time-Based Rates from the Consumer Behavior Studies Now Available: Interim Report on Customer Acceptance, ...

  14. Correcting systematic bias and instrument measurement drift with mzRefinery

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Gibbons, Bryson C.; Chambers, Matthew C.; Monroe, Matthew E.; Tabb, David L.; Payne, Samuel H.

    2015-08-04

    Systematic bias in mass measurement adversely affects data quality and negates the advantages of high precision instruments. We introduce the mzRefinery tool into the ProteoWizard package for calibration of mass spectrometry data files. Using confident peptide spectrum matches, three different calibration methods are explored and the optimal transform function is chosen. After calibration, systematic bias is removed and the mass measurement errors are centered at zero ppm. Because it is part of the ProteoWizard package, mzRefinery can read and write a wide variety of file formats. In conclusion, we report on availability; the mzRefinery tool is part of msConvert, availablemore » with the ProteoWizard open source package at http://proteowizard.sourceforge.net/« less

  15. Correcting systematic bias and instrument measurement drift with mzRefinery

    SciTech Connect (OSTI)

    Gibbons, Bryson C.; Chambers, Matthew C.; Monroe, Matthew E.; Tabb, David L.; Payne, Samuel H.

    2015-08-04

    Systematic bias in mass measurement adversely affects data quality and negates the advantages of high precision instruments. We introduce the mzRefinery tool into the ProteoWizard package for calibration of mass spectrometry data files. Using confident peptide spectrum matches, three different calibration methods are explored and the optimal transform function is chosen. After calibration, systematic bias is removed and the mass measurement errors are centered at zero ppm. Because it is part of the ProteoWizard package, mzRefinery can read and write a wide variety of file formats. In conclusion, we report on availability; the mzRefinery tool is part of msConvert, available with the ProteoWizard open source package at http://proteowizard.sourceforge.net/

  16. Correcting systematic bias and instrument measurement drift with mzRefinery

    SciTech Connect (OSTI)

    Gibbons, Bryson C.; Chambers, Matthew C.; Monroe, Matthew E.; Tabb, David L.; Payne, Samuel H.

    2015-12-01

    MOTIVATION: Systematic bias in mass measurement adversely affects data quality and negates the advantages of high precision instruments. RESULTS: We introduce the mzRefinery tool into the ProteoWizard package for calibration of mass spectrometry data files. Using confident peptide spectrum matches, three different calibration methods are explored and the optimal transform function is chosen. After calibration, systematic bias is removed and the mass measurement errors are centered at zero ppm. Because it is part of the ProteoWizard package, mzRefinery can read and write a wide variety of file formats. AVAILABILITY: The mzRefinery tool is part of msConvert, available with the ProteoWizard open source package at http://proteowizard.sourceforge.net/

  17. Solid waste burial grounds interim safety analysis

    SciTech Connect (OSTI)

    Saito, G.H.

    1994-10-01

    This Interim Safety Analysis document supports the authorization basis for the interim operation and restrictions on interim operations for the near-surface land disposal of solid waste in the Solid Waste Burial Grounds. The Solid Waste Burial Grounds Interim Safety Basis supports the upgrade progress for the safety analysis report and the technical safety requirements for the operations in the Solid Waste Burial Grounds. Accident safety analysis scenarios have been analyzed based on the significant events identified in the preliminary hazards analysis. The interim safety analysis provides an evaluation of the operations in the Solid Waste Burial Grounds to determine if the radiological and hazardous material exposures will be acceptable from an overall health and safety standpoint to the worker, the onsite personnel, the public, and the environment.

  18. Oxygen Reduction Reaction Measurements on Platinum Electrocatalysts Utilizing Rotating Disk Electrode Technique: I. Impact of Impurities, Measurement Protocols and Applied Corrections

    SciTech Connect (OSTI)

    Shinozaki, Kazuma; Zack, Jason W.; Richards, Ryan M.; Pivovar, Bryan S.; Kocha, Shyam S.

    2015-07-22

    The rotating disk electrode (RDE) technique is being extensively used as a screening tool to estimate the activity of novel PEMFC electrocatalysts synthesized in lab-scale (mg) quantities. Discrepancies in measured activity attributable to glassware and electrolyte impurity levels, as well as conditioning, protocols and corrections are prevalent in the literature. Moreover, the electrochemical response to a broad spectrum of commercially sourced perchloric acid and the effect of acid molarity on impurity levels and solution resistance were also assessed. Our findings reveal that an area specific activity (SA) exceeding 2.0 mA/cm2 (20 mV/s, 25°C, 100 kPa, 0.1 M HClO4) for polished poly-Pt is an indicator of impurity levels that do not impede the accurate measurement of the ORR activity of Pt based catalysts. After exploring various conditioning protocols to approach maximum utilization of the electrochemical area (ECA) and peak ORR activity without introducing catalyst degradation, an investigation of measurement protocols for ECA and ORR activity was conducted. Down-selected protocols were based on the criteria of reproducibility, duration of experiments, impurity effects and magnitude of pseudo-capacitive background correction. In sum, statistical reproducibility of ORR activity for poly-Pt and Pt supported on high surface area carbon was demonstrated.

  19. Oxygen Reduction Reaction Measurements on Platinum Electrocatalysts Utilizing Rotating Disk Electrode Technique: I. Impact of Impurities, Measurement Protocols and Applied Corrections

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Shinozaki, Kazuma; Zack, Jason W.; Richards, Ryan M.; Pivovar, Bryan S.; Kocha, Shyam S.

    2015-07-22

    The rotating disk electrode (RDE) technique is being extensively used as a screening tool to estimate the activity of novel PEMFC electrocatalysts synthesized in lab-scale (mg) quantities. Discrepancies in measured activity attributable to glassware and electrolyte impurity levels, as well as conditioning, protocols and corrections are prevalent in the literature. Moreover, the electrochemical response to a broad spectrum of commercially sourced perchloric acid and the effect of acid molarity on impurity levels and solution resistance were also assessed. Our findings reveal that an area specific activity (SA) exceeding 2.0 mA/cm2 (20 mV/s, 25°C, 100 kPa, 0.1 M HClO4) for polishedmore » poly-Pt is an indicator of impurity levels that do not impede the accurate measurement of the ORR activity of Pt based catalysts. After exploring various conditioning protocols to approach maximum utilization of the electrochemical area (ECA) and peak ORR activity without introducing catalyst degradation, an investigation of measurement protocols for ECA and ORR activity was conducted. Down-selected protocols were based on the criteria of reproducibility, duration of experiments, impurity effects and magnitude of pseudo-capacitive background correction. In sum, statistical reproducibility of ORR activity for poly-Pt and Pt supported on high surface area carbon was demonstrated.« less

  20. EIS-0283-S2: Interim Action Determination | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    in H-Canyon at the Savannah River Site For more information on this project, see the project webpage: http://energy.gov/node/299815. Download Document EIS-0283-S2: Interim Action Determination (781.29 KB) More Documents & Publications EIS-0283-S2: Interim Action Determination EIS-0283-S2: Interim Action Determination EIS-0283-S2: Interim Action Determination

  1. Interim Approach to the MRS facility design

    SciTech Connect (OSTI)

    Not Available

    1992-01-01

    The purpose is to present the proposed Interim Approach to the Monitored Retrievable Storage (MRS) facility design development. This Interim Approach document fulfills the function allocated to the OCRWM-SEMP (DOE/RW-0051REVlP, March 1990, Section 5.2 Approach to the MRS Design) until the MRS section of the OCRWM-SEMP is approved. Until completion of the OCRWM-SEMP, this Interim Approach document will be approved and controlled according to the Program Change Control Procedure (DOE/RW-0223REV3P). This document discusses the general approach to Conceptual Design (CD), Title I Design, and Title II Design activities.

  2. Interim Final Rule and Proposed Rule | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Interim Final Rule and Proposed Rule Interim Final Rule and Proposed Rule Extracted Pages from the Interim Final Rule and Proposed Rule, September 19, 2008 Interim Final Rule and Proposed Rule (111.06 KB) More Documents & Publications Comments of the Staff of the public utilities commission of the state of California on the interim final rule Comments on Notice of Proposed Rulemaking for Coordination of Federal Authorizations for Electric Transmission Facilities Changes recommended by OIRA

  3. Comparing range data across the slow-time dimension to correct motion measurement errors beyond the range resolution of a synthetic aperture radar

    DOE Patents [OSTI]

    Doerry, Armin W. (Albuquerque, NM); Heard, Freddie E. (Albuquerque, NM); Cordaro, J. Thomas (Albuquerque, NM)

    2010-08-17

    Motion measurement errors that extend beyond the range resolution of a synthetic aperture radar (SAR) can be corrected by effectively decreasing the range resolution of the SAR in order to permit measurement of the error. Range profiles can be compared across the slow-time dimension of the input data in order to estimate the error. Once the error has been determined, appropriate frequency and phase correction can be applied to the uncompressed input data, after which range and azimuth compression can be performed to produce a desired SAR image.

  4. In Situ Validation of a Correction for Time-Lag and Bias Errors in Vaisala RS80-H Radiosonde Humidity Measurements

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    In Situ Validation of a Correction for Time-Lag and Bias Errors in Vaisala RS80-H Radiosonde Humidity Measurements L. M. Miloshevich National Center for Atmospheric Research Boulder, Colorado H. Vömel and S. J. Oltmans National Oceanic and Atmospheric Administration Boulder, Colorado A. Paukkunen Vaisala Oy Helsinki, Finland Introduction Radiosonde relative humidity (RH) measurements are fundamentally important to Atmospheric Radiation Measurement (ARM) Program goals because they are used in a

  5. Methods Data Qualification Interim Report

    SciTech Connect (OSTI)

    R. Sam Alessi; Tami Grimmett; Leng Vang; Dave McGrath

    2010-09-01

    The overall goal of the Next Generation Nuclear Plant (NGNP) Data Management and Analysis System (NDMAS) is to maintain data provenance for all NGNP data including the Methods component of NGNP data. Multiple means are available to access data stored in NDMAS. A web portal environment allows users to access data, view the results of qualification tests and view graphs and charts of various attributes of the data. NDMAS also has methods for the management of the data output from VHTR simulation models and data generated from experiments designed to verify and validate the simulation codes. These simulation models represent the outcome of mathematical representation of VHTR components and systems. The methods data management approaches described herein will handle data that arise from experiment, simulation, and external sources for the main purpose of facilitating parameter estimation and model verification and validation (V&V). A model integration environment entitled ModelCenter is used to automate the storing of data from simulation model runs to the NDMAS repository. This approach does not adversely change the why computational scientists conduct their work. The method is to be used mainly to store the results of model runs that need to be preserved for auditing purposes or for display to the NDMAS web portal. This interim report demonstrates the currently development of NDMAS for Methods data and discusses data and its qualification that is currently part of NDMAS.

  6. Interim Update: Global Automotive Power Electronics R&D Relevant...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Interim Update: Global Automotive Power Electronics R&D Relevant To DOE 2015 and 2020 Cost Targets Interim Update: Global Automotive Power Electronics R&D Relevant To DOE 2015 and ...

  7. Design review report FFTF interim storage cask

    SciTech Connect (OSTI)

    Scott, P.L.

    1995-01-03

    Final Design Review Report for the FFTF Interim Storage Cask. The Interim Storage Cask (ISC) will be used for long term above ground dry storage of FFTF irradiated fuel in Core Component Containers (CCC)s. The CCC has been designed and will house assemblies that have been sodium washed in the IEM Cell. The Solid Waste Cask (SWC) will transfer a full CCC from the IEM Cell to the RSB Cask Loading Station where the ISC will be located to receive it. Once the loaded ISC has been sealed at the RSB Cask Loading Station, it will be transferred by facility crane to the DSWC Transporter. After the ISC has been transferred to the Interim Storage Area (ISA), which is yet to be designed, a mobile crane will be used to place the ISC in its final storage location.

  8. Guidance For Preparatioon of Basis For Interim Operation (BIO) Documents

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    3011-2002 December 2002 Superceding DOE-STD-3011-94 November 1994 DOE STANDARD GUIDANCE FOR PREPARATION OF BASIS FOR INTERIM OPERATION (BIO) DOCUMENTS U.S. Department of Energy AREA SAFT Washington, D.C. 20585 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited. NOT MEASUREMENT SENSITIVE DOE-STD-3011-2002 ii This document has been reproduced directly from the best available copy. Available to DOE and DOE contractors from ES&H Technical Information Services, U.S.

  9. Interim Ventilation System Tie-in Completed

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    , 2016 Interim Ventilation System Tie-in Completed Early this week sub-contractors at the Waste Isolation Pilot Plant (WIPP) completed the "tie in" of the new interim ventilation system (IVS) to the ductwork for the existing underground ventilation system. Following a series of operational tests, the IVS is expected to increase airflow in the WIPP underground by approximately 54,000 cubic feet per minute. The tie-in operation consisted of removal of sections of the existing ductwork

  10. High Temperature Materials Interim Data Qualification Report

    SciTech Connect (OSTI)

    Nancy Lybeck

    2010-08-01

    ABSTRACT Projects for the very high temperature reactor (VHTR) Technology Development Office provide data in support of Nuclear Regulatory Commission licensing of the VHTR. Fuel and materials to be used in the reactor are tested and characterized to quantify performance in high temperature and high fluence environments. The VHTR program has established the NGNP Data Management and Analysis System (NDMAS) to ensure that VHTR data are qualified for use, stored in a readily accessible electronic form, and analyzed to extract useful results. This document focuses on the first NDMAS objective. It describes the High Temperature Materials characterization data stream, the processing of these data within NDMAS, and reports the interim FY2010 qualification status of the data. Data qualification activities within NDMAS for specific types of data are determined by the data qualification category assigned by the data generator. The High Temperature Materials data are being collected under NQA-1 guidelines, and will be qualified data. For NQA-1 qualified data, the qualification activities include: (1) capture testing, to confirm that the data stored within NDMAS are identical to the raw data supplied, (2) accuracy testing to confirm that the data are an accurate representation of the system or object being measured, and (3) documenting that the data were collected under an NQA-1 or equivalent Quality Assurance program. Currently, data from two test series within the High Temperature Materials data stream have been entered into the NDMAS vault: 1. Tensile Tests for Sm (i.e., Allowable Stress) Confirmatory Testing 1,403,994 records have been inserted into the NDMAS database. Capture testing is in process. 2. Creep-Fatigue Testing to Support Determination of Creep-Fatigue Interaction Diagram 918,854 records have been processed and inserted into the NDMAS database. Capture testing is in process.

  11. Effectiveness of interim remedial actions at a radioactive waste facility

    SciTech Connect (OSTI)

    Devgun, J.S.; Beskid, N.J.; Peterson, J.M.; Seay, W.M.; McNamee, E.; USDOE Oak Ridge Operations Office, TN; Bechtel National, Inc., Oak Ridge, TN )

    1989-01-01

    Over the past eight years, several interim remedial actions have been taken at the Niagara Falls Storage Site (NFSS), primarily to reduce radon and gamma radiation exposures and to consolidate radioactive waste into a waste containment facility. Interim remedial actions have included capping of vents, sealing of pipes, relocation of the perimeter fence (to limit radon risk), transfer and consolidation of waste, upgrading of storage buildings, construction of a clay cutoff wall (to limit the potential groundwater transport of contaminants), treatment and release of contaminated water, interim use of a synthetic liner, and emplacement of an interim clay cap. An interim waste containment facility was completed in 1986. 6 refs., 3 figs.

  12. SU-E-T-96: Demonstration of a Consistent Method for Correcting Surface Dose Measurements Using Both Solid State and Ionization Chamber Detectors

    SciTech Connect (OSTI)

    Reynolds, T; Gerbi, B; Higgins, P

    2014-06-01

    Purpose: To compare the surface dose (SD) measured using a PTW 30-360 extrapolation chamber with different commonly used dosimeters (Ds): parallel plate ion chambers (ICs): RMI-449 (Attix), Capintec PS-033, PTW 30-329 (Markus) and Memorial; TLD chips (cTLD), TLD powder (pTLD), optically stimulated (OSLs), radiochromic (EXR2) and radiographic (EDR2) films, and to provide an intercomparison correction to Ds for each of them. Methods: Investigations were performed for a 6 MV x-ray beam (Varian Clinac 2300, 10x10 cm{sup 2} open field, SSD = 100 cm). The Ds were placed at the surface of the solid water phantom and at the reference depth dref=1.7cm. The measurements for cTLD, OSLs, EDR2 and EXR2 were corrected to SD using an extrapolation method (EM) indexed to the baseline PTW 30-360 measurements. A consistent use of the EM involved: 1) irradiation of three Ds stacked on top of each other on the surface of the phantom; 2) measurement of the relative dose value for each layer; and, 3) extrapolation of these values to zero thickness. An additional measurement was performed with externally exposed OSLs (eOSLs), that were rotated out of their protective housing. Results: All single Ds measurements overestimated the SD compared with the extrapolation chamber, except for Attix IC. The closest match to the true SD was measured with the Attix IC (− 0.1%), followed by pTLD (0.5%), Capintec (4.5%), Memorial (7.3%), Markus (10%), cTLD (11.8%), eOSL (12.8%), EXR2 (14%), EDR2 (14.8%) and OSL (26%). The EM method of correction for SD worked well for all Ds, except the unexposed OSLs. Conclusion: This EM cross calibration of solid state detectors with an extrapolation or Attix chamber can provide thickness corrections for cTLD, eOSLs, EXR2, and EDR2. Standard packaged OSLs were not found to be simply corrected.

  13. Conversion and correction factors for historical measurements of Iodine-131 in Hanford-area vegetation, 1945--1947: Draft. Hanford Environmental Dose Reconstruction Project

    SciTech Connect (OSTI)

    Mart, E.I.; Denham, D.H.; Thiede, M.E.

    1993-05-01

    This report is a result of the Hanford Environmental Dose Reconstruction (HEDR) Project whose goal is to estimate the radiation dose that individuals could have received from emissions since 1944 at the US Department of Energy`s (DOE) Hanford Site near Richland, Washington. The report describes in detail the reconstructed conversion and correction factors for historical measurements of iodine-131 in Hanford-area vegetation which was collected from the beginning of October 1945 through the end of December 1947.

  14. Expedited approach to a carbon tetrachloride spill interim remedial action

    SciTech Connect (OSTI)

    Cowdery, C.; Primrose, A.; Uhland, J.; Castaneda, N.

    1998-07-01

    Monitored natural attenuation was selected as an interim measure for a carbon tetrachloride spill site where source removal or in situ treatment cannot currently be implemented due to the surrounding infrastructure. Rather than delay action until the site is more accessible to an interim action, this more expedited approach would support a final action. Individual Hazard Substance Site (IHSS) 118.1 is a former underground storage tank at Rocky Flats Environmental Technology Site (RFETS) that stored carbon tetrachloride for process use. Inadvertent releases associated with filling and failure of the tank system resulted in an accumulation of carbon tetrachloride in a bedrock depression around a group of former process waste tanks. Access to the source of contamination is obstructed by numerous utilities, the process waste tanks, and other components of the site infrastructure that limit the ability to conduct an effective remedial action. A preremedial field investigation was conducted in September 1997 to identify and delineate the extent of the dense nonaqueous phase liquid (DNAPL) in the subsurface. Data collected from the investigation revealed that natural processes might be limiting the migration of contaminants from the source area.

  15. Phase 1 RCRA Facility Investigation & Corrective Measures Study Work Plan for Single Shell Tank (SST) Waste Management Areas

    SciTech Connect (OSTI)

    MCCARTHY, M.M.

    1999-08-01

    This document is the master work plan for the Resource Conservation and Recovery Act of 1976 (RCRA) Corrective Action Program (RCAP) for single-shell tank (SST) farms at the US. Department of Energy's (DOE'S) Hanford Site. The DOE Office of River Protection (ORP) initiated the RCAP to address the impacts of past and potential future tank waste releases to the environment. This work plan defines RCAP activities for the four SST waste management areas (WMAs) at which releases have contaminated groundwater. Recognizing the potential need for future RCAP activities beyond those specified in this master work plan, DOE has designated the currently planned activities as ''Phase 1.'' If a second phase of activities is needed for the WMAs addressed in Phase 1, or if releases are detected at other SST WMAs, this master work plan will be updated accordingly.

  16. Self-corrected Sensors Based On Atomic Absorption Spectroscopy For Atom Flux Measurements In Molecular Beam Epitaxy

    SciTech Connect (OSTI)

    Du, Yingge; Droubay, Timothy C.; Liyu, Andrey V.; Li, Guosheng; Chambers, Scott A.

    2014-04-24

    A high sensitivity atom flux sensor based on atomic absorption spectroscopy has been designed and implemented to control electron beam evaporators and effusion cells in a molecular beam epitaxy system. Using a high-resolution spectrometer and a two-dimensional charge coupled device (CCD) detector in a double-beam configuration, we employ a non-resonant line or a resonant line with lower absorbance from the same hollow cathode lamp as the reference for nearly perfect background correction and baseline drift removal. This setup also significantly shortens the warm-up time needed compared to other sensor technologies and drastically reduces the noise coming from the surrounding environment. In addition, the high-resolution spectrometer allows the most sensitive resonant line to be isolated and used to provide excellent signal-to-noise ratio.

  17. Self-corrected sensors based on atomic absorption spectroscopy for atom flux measurements in molecular beam epitaxy

    SciTech Connect (OSTI)

    Du, Y. E-mail: scott.chambers@pnnl.gov; Liyu, A. V.; Droubay, T. C.; Chambers, S. A. E-mail: scott.chambers@pnnl.gov; Li, G.

    2014-04-21

    A high sensitivity atom flux sensor based on atomic absorption spectroscopy has been designed and implemented to control electron beam evaporators and effusion cells in a molecular beam epitaxy system. Using a high-resolution spectrometer and a two-dimensional charge coupled device detector in a double-beam configuration, we employ either a non-resonant line or a resonant line with low cross section from the same hollow cathode lamp as the reference for nearly perfect background correction and baseline drift removal. This setup also significantly shortens the warm-up time needed compared to other sensor technologies and drastically reduces the noise coming from the surrounding environment. In addition, the high-resolution spectrometer allows the most sensitive resonant line to be isolated and used to provide excellent signal-to-noise ratio.

  18. Corrective Action

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    of Corrective Action Complete is demonstrated by one of the following: Eliminate Exposure (11 SMAs, 16 Sites) SMA SITE Submittal Date Document 2M-SMA-2.2 03-003(k) September...

  19. Now Available: Lakeland Electric SGIG Consumer Behavior Study Interim

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Evaluation Report (February 2015) | Department of Energy Lakeland Electric SGIG Consumer Behavior Study Interim Evaluation Report (February 2015) Now Available: Lakeland Electric SGIG Consumer Behavior Study Interim Evaluation Report (February 2015) March 20, 2015 - 2:17pm Addthis An interim evaluation report summarizing results from the first year of Lakeland Electric's two-year 3-Period Time of Use (TOU) program called "Shift-to-Save" (STS) is now available. The study is part of

  20. Lakeland Electric SGIG Consumer Behavior Study Interim (Year 1) Evaluation

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Report (February 2015) | Department of Energy Lakeland Electric SGIG Consumer Behavior Study Interim (Year 1) Evaluation Report (February 2015) Lakeland Electric SGIG Consumer Behavior Study Interim (Year 1) Evaluation Report (February 2015) This interim evaluation report summarizes results from the first year of Lakeland Electric's two-year 3-Period Time of Use (TOU) program called "Shift-to-Save" (STS). Lakeland Electric has undertaken this study as part of a full system-wide

  1. EIS-0283-S2: Interim Action Determination | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Disposition of Certain Plutonium Materials Stored at the Savannah River Site For more information on this project, see the project webpage: http://energy.gov/node/299815. Download Document EIS-0283-S2: Interim Action Determination (880.28 KB) More Documents & Publications EIS-0283-S2: Interim Action Determination EIS-0283-S2: Interim Action Determination EIS-0283-S2: Second Amended Notice of Intent

  2. Conversion and correction factors for historical measurements of iodine-131 in Hanford-area vegetation, 1945--1947. Hanford Environmental Dose Reconstruction Project

    SciTech Connect (OSTI)

    Mart, E.I.; Denham, D.H.; Thiede, M.E.

    1993-12-01

    This report is a result of the Hanford Environmental Dose Reconstruction (HEDR) Project whose goal is to estimate the radiation dose that individuals could have received from emissions since 1944 at the U.S. Department of Energy`s (DOE) Hanford Site near Richland, Washington. The HEDR Project is conducted by Battelle, Pacific Northwest Laboratories (BNW). One of the radionuclides emitted that would affect the radiation dose was iodine-131. This report describes in detail the reconstructed conversion and correction factors for historical measurements of iodine-131 in Hanford-area vegetation which was collected from the beginning of October 1945 through the end of December 1947.

  3. Interim Final Rule and Request for Comments, Federal Register...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Document displays the interim final rule and request for comments for Energy Conservation Standards for New Federal Commercial and Multi-Family High-Rise Residential Buildings and ...

  4. EIS-0283-S2: Amended Interim Action Determination | Department...

    Broader source: Energy.gov (indexed) [DOE]

    Plutonium Materials from the Department of Energy Standard 3013 Surveillance Program at the Savannah River Site (Amending Interim Action Determination of 12082008) DOE is ...

  5. Comments of NRDC on Department of Energy Interim Final Rule:...

    Broader source: Energy.gov (indexed) [DOE]

    NRDC's comments on Interim Final Rule: Energy Conservation for New Federal Commercial and Multi-Family High-Rise Residential Buildings and New Federal Low-Rise Residential ...

  6. T-TY Tank Farm Interim Surface Barrier Demonstration - Vadose Zone Monitoring FY10 Report

    SciTech Connect (OSTI)

    Zhang, Z. F.; Strickland, Christopher E.; Field, Jim G.; Parker, Danny L.

    2011-01-01

    The U.S. Department of Energy’s Office of River Protection has constructed interim surface barriers over a portion of the T and TY tank farms as part of the Interim Surface Barrier Demonstration Project. The interim surface barriers (hereafter referred to as the surface barriers or barriers) are designed to minimize the infiltration of precipitation into the soil zones containing radioactive contaminants and minimize the movement of the contaminants. As part of the demonstration effort, vadose zone moisture is being monitored to assess the effectiveness of the barriers at reducing soil moisture. Solar-powered systems were installed to continuously monitor soil water conditions at four locations in the T (i.e., instrument Nests TA, TB, TC, and TD) and the TY (i.e., instrument Nests TYA and TYB) Farms beneath the barriers and outside the barrier footprint as well as site meteorological conditions. Nests TA and TYA are placed in the area outside the barrier footprint and serve as controls, providing subsurface conditions outside the influence of the surface barriers. Nest TB provides subsurface measurements to assess surface-barrier edge effects. Nests TC, TD, and TYB are used to assess changes in soil-moisture conditions beneath the interim surface barriers.

  7. Letter on the Interim Report of the Commission to Review the...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Interim Report of the Commission to Review the Effectiveness of the National Energy Laboratories Letter on the Interim Report of the Commission to Review the Effectiveness of the ...

  8. Soil remediation interim measures/interim remedial action (IM/IRA) for Rocky Flats Plant

    SciTech Connect (OSTI)

    Bulgar, L.; Law, J.; Buddy, M.

    1994-12-31

    The accelerated Cleanup Program for Rocky Flats Plant includes a number of subprograms which are being implemented to expedite remediation at the facility. One of these is the Soil Remediation IM/IRA. This paper discusses the objectives, scope, and approach for the Soil Remediation IM/IRA program. The major features of this program are addressed, along with a discussion of its potential benefits relative to the conventional RCRA/CERCLA remediation process. The paper also provides information on the problems encountered and decisions made during the planning and development of this program, its current status, and future plans.

  9. PROJECT W-551 INTERIM PRETREATMENT SYSTEM PRECONCEPTUAL CANDIDATE TECHNOLOGY DESCRIPTIONS

    SciTech Connect (OSTI)

    MAY TH

    2008-08-12

    The Office of River Protection (ORP) has authorized a study to recommend and select options for interim pretreatment of tank waste and support Waste Treatment Plant (WTP) low activity waste (LAW) operations prior to startup of all the WTP facilities. The Interim Pretreatment System (IPS) is to be a moderately sized system which separates entrained solids and 137Cs from tank waste for an interim time period while WTP high level waste vitrification and pretreatment facilities are completed. This study's objective is to prepare pre-conceptual technology descriptions that expand the technical detail for selected solid and cesium separation technologies. This revision includes information on additional feed tanks.

  10. TANK FARM INTERIM SURFACE BARRIER MATERIALS AND RUNOFF ALTERNATIVES STUDY

    SciTech Connect (OSTI)

    HOLM MJ

    2009-06-25

    This report identifies candidate materials and concepts for interim surface barriers in the single-shell tank farms. An analysis of these materials for application to the TY tank farm is also provided.

  11. Stability of Biodiesel and Biodiesel Blends: Interim Report

    SciTech Connect (OSTI)

    McCormick, R. L.; Alleman, T. L.; Waynick, J. A.; Westbrook, S. R.; Porter, S.

    2006-04-01

    This is an interim report for a study of biodiesel oxidative stability. It describes characterization and accelerated stability test results for 19 B100 samples and six diesel fuels.

  12. Technical bases for interim storage of spent nuclear fuel

    SciTech Connect (OSTI)

    Johnson, A.B. Jr.

    1981-06-01

    The experience base for water storage of spent nuclear fuel has evolved since 1943. The technology base includes licensing documentation, standards, technology studies, pool operator experience, and documentation from public hearings. That base reflects a technology which is largely successful and mundane. It projects probable satisfactory water storage of spent water reactor fuel for several decades. Interim dry storage of spent water reactor fuel is not yet licensed in the US, but a data base and documentation have developed. There do not appear to be technological barriers to interim dry storage, based on demonstrations with irradiated fuel. Water storage will continue to be a part of spent fuel management at reactors. Whether dry storage becomes a prominent interim fuel management option depends on licensing and economic considerations. National policies will strongly influence how long the spent fuel remains in interim storage and what its final disposition will be.

  13. Probabilistic Performance Assessment: SCC of SNF Interim Storage...

    Office of Scientific and Technical Information (OSTI)

    Probabilistic Performance Assessment: SCC of SNF Interim Storage Canisters C. Bryan1, C. ... Effect of Initial Heat Load Two alternative cases run, with 4 kW and 10 kW heat ...

  14. Interim report on long range plan for nuclear physics

    SciTech Connect (OSTI)

    1995-04-01

    The interim report on the updated NSAC Long Range Plan for Nuclear Physics will be presented to the community for discussion and comment before submission to the funding agencies. The presentation will be coordinated by E. Moniz chair of NSAC.

  15. Final Environmental Impact Statement Safe Interim Storage Of...

    Office of Environmental Management (EM)

    ... SIS Safe Interim Storage SO2 Sulfur dioxide SR State ... East Area using the same methods described for the ... the 200 East Area thereby reducing the likelihood of waste ...

  16. King County Metro Transit Hybrid Articulated Buses: Interim Evaluation Results

    Alternative Fuels and Advanced Vehicles Data Center [Office of Energy Efficiency and Renewable Energy (EERE)]

    King County Metro Transit Hybrid Articulated Buses: Interim Evaluation Results K. Chandler Battelle K. Walkowicz National Renewable Energy Laboratory Technical Report NREL/TP-540-39742 April 2006 King County Metro Transit Hybrid Articulated Buses: Interim Evaluation Results K. Chandler Battelle K. Walkowicz National Renewable Energy Laboratory Prepared under Task No. FC06.3000 Technical Report NREL/TP-540-39742 April 2006 National Renewable Energy Laboratory 1617 Cole Boulevard, Golden, Colorado

  17. Interim Report on Customer Acceptance, Retention, and Response to

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Time-Based Rates from the Consumer Behavior Studies (June 2015) | Department of Energy Interim Report on Customer Acceptance, Retention, and Response to Time-Based Rates from the Consumer Behavior Studies (June 2015) Interim Report on Customer Acceptance, Retention, and Response to Time-Based Rates from the Consumer Behavior Studies (June 2015) Since 2009, the U.S. Department of Energy, using funds from the American Recovery and Reinvestment Act, and the electric power industry have jointly

  18. TWRS HLW interim storage facility search and evaluation

    SciTech Connect (OSTI)

    Calmus, R.B., Westinghouse Hanford

    1996-05-16

    The purpose of this study was to identify and provide an evaluation of interim storage facilities and potential facility locations for the vitrified high-level waste (HLW) from the Phase I demonstration plant and Phase II production plant. In addition, interim storage facilities for solidified separated radionuclides (Cesium and Technetium) generated during pretreatment of Phase I Low-Level Waste Vitrification Plant feed was evaluated.

  19. K basins interim remedial action health and safety plan

    SciTech Connect (OSTI)

    DAY, P.T.

    1999-09-14

    The K Basins Interim Remedial Action Health and Safety Plan addresses the requirements of the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA), as they apply to the CERCLA work that will take place at the K East and K West Basins. The provisions of this plan become effective on the date the US Environmental Protection Agency issues the Record of Decision for the K Basins Interim Remedial Action, currently planned in late August 1999.

  20. Interim Safety Basis for Fuel Supply Shutdown Facility

    SciTech Connect (OSTI)

    BENECKE, M.W.

    2000-09-07

    This ISB, in conjunction with the IOSR, provides the required basis for interim operation or restrictions on interim operations and administrative controls for the facility until a SAR is prepared in accordance with the new requirements or the facility is shut down. It is concluded that the risks associated with tha current and anticipated mode of the facility, uranium disposition, clean up, and transition activities required for permanent closure, are within risk guidelines.

  1. DOE Interim Guidance on Mercury Management Procedures and Standards |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy Services » Waste Management » Waste Disposition » Long-Term Management and Storage of Elemental Mercury is in the Planning Stages » DOE Interim Guidance on Mercury Management Procedures and Standards DOE Interim Guidance on Mercury Management Procedures and Standards DOE, in consultation with the USEPA and State agencies, prepared this guidance on packaging, transportation, receipt, management, and long-term storage of elemental mercury at a DOE facility or

  2. VTA Prototype Fuel Cell Bus Evaluation: Interim Results (Presentation) |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy VTA Prototype Fuel Cell Bus Evaluation: Interim Results (Presentation) VTA Prototype Fuel Cell Bus Evaluation: Interim Results (Presentation) Details hydrogen fuel cell buses being evaluated in service at AC Transit. Presented at the APTA Bus and Paratransit Conference in Anaheim, California, April 30 through May 3, 2006. 40012.pdf (412.92 KB) More Documents & Publications Santa Clara Valley Transportation Authority and San Mateo County Transit District -- Fuel Cell

  3. Interim Basis for PCB Sampling and Analyses

    SciTech Connect (OSTI)

    BANNING, D.L.

    2001-03-20

    This document was developed as an interim basis for sampling and analysis of polychlorinated biphenyls (PCBs) and will be used until a formal data quality objective (DQO) document is prepared and approved. On August 31, 2000, the Framework Agreement for Management of Polychlorinated Biphenyls (PCBs) in Hanford Tank Waste was signed by the U.S. Department of Energy (DOE), the Environmental Protection Agency (EPA), and the Washington State Department of Ecology (Ecology) (Ecology et al. 2000). This agreement outlines the management of double shell tank (DST) waste as Toxic Substance Control Act (TSCA) PCB remediation waste based on a risk-based disposal approval option per Title 40 of the Code of Federal Regulations 761.61 (c). The agreement calls for ''Quantification of PCBs in DSTs, single shell tanks (SSTs), and incoming waste to ensure that the vitrification plant and other ancillary facilities PCB waste acceptance limits and the requirements of the anticipated risk-based disposal approval are met.'' Waste samples will be analyzed for PCBs to satisfy this requirement. This document describes the DQO process undertaken to assure appropriate data will be collected to support management of PCBs and is presented in a DQO format. The DQO process was implemented in accordance with the U.S. Environmental Protection Agency EPA QA/G4, Guidance for the Data Quality Objectives Process (EPA 1994) and the Data Quality Objectives for Sampling and Analyses, HNF-IP-0842, Rev. 1A, Vol. IV, Section 4.16 (Banning 1999).

  4. Interim Basis for PCB Sampling and Analyses

    SciTech Connect (OSTI)

    BANNING, D.L.

    2001-01-18

    This document was developed as an interim basis for sampling and analysis of polychlorinated biphenyls (PCBs) and will be used until a formal data quality objective (DQO) document is prepared and approved. On August 31, 2000, the Framework Agreement for Management of Polychlorinated Biphenyls (PCBs) in Hanford Tank Waste was signed by the US. Department of Energy (DOE), the Environmental Protection Agency (EPA), and the Washington State Department of Ecology (Ecology) (Ecology et al. 2000). This agreement outlines the management of double shell tank (DST) waste as Toxic Substance Control Act (TSCA) PCB remediation waste based on a risk-based disposal approval option per Title 40 of the Code of Federal Regulations 761.61 (c). The agreement calls for ''Quantification of PCBs in DSTs, single shell tanks (SSTs), and incoming waste to ensure that the vitrification plant and other ancillary facilities PCB waste acceptance limits and the requirements of the anticipated risk-based disposal approval are met.'' Waste samples will be analyzed for PCBs to satisfy this requirement. This document describes the DQO process undertaken to assure appropriate data will be collected to support management of PCBs and is presented in a DQO format. The DQO process was implemented in accordance with the U.S. Environmental Protection Agency EPA QAlG4, Guidance for the Data Quality Objectives Process (EPA 1994) and the Data Quality Objectives for Sampling and Analyses, HNF-IP-0842, Rev. 1 A, Vol. IV, Section 4.16 (Banning 1999).

  5. Interim performance criteria for photovoltaic energy systems. [Glossary included

    SciTech Connect (OSTI)

    DeBlasio, R.; Forman, S.; Hogan, S.; Nuss, G.; Post, H.; Ross, R.; Schafft, H.

    1980-12-01

    This document is a response to the Photovoltaic Research, Development, and Demonstration Act of 1978 (P.L. 95-590) which required the generation of performance criteria for photovoltaic energy systems. Since the document is evolutionary and will be updated, the term interim is used. More than 50 experts in the photovoltaic field have contributed in the writing and review of the 179 performance criteria listed in this document. The performance criteria address characteristics of present-day photovoltaic systems that are of interest to manufacturers, government agencies, purchasers, and all others interested in various aspects of photovoltaic system performance and safety. The performance criteria apply to the system as a whole and to its possible subsystems: array, power conditioning, monitor and control, storage, cabling, and power distribution. They are further categorized according to the following performance attributes: electrical, thermal, mechanical/structural, safety, durability/reliability, installation/operation/maintenance, and building/site. Each criterion contains a statement of expected performance (nonprescriptive), a method of evaluation, and a commentary with further information or justification. Over 50 references for background information are also given. A glossary with definitions relevant to photovoltaic systems and a section on test methods are presented in the appendices. Twenty test methods are included to measure performance characteristics of the subsystem elements. These test methods and other parts of the document will be expanded or revised as future experience and needs dictate.

  6. CERCLA interim action at the Par Pond unit: A case study

    SciTech Connect (OSTI)

    Hickey, H.M.; Matthews, S.S.; Neal, L.W.; Weiss, W.R.

    1993-11-01

    The Par Pond unit designated under CERCLA consists of sediments within a Savannah River Site (SRS) cooling water reservoir. The sediments are contaminated with radionuclides and nonradioactive constituents from nuclear production reactor operations. The mercury in Par Pond is believed to have originated from the Savannah River. Because of Par Pond Dam safety Issues, the water level of the reservoir was drawn down, exposing more than 1300 acres of contaminated sediments and triggering the need for CERCLA interim remedial action. This paper presents the interim action approach taken with Par Pond as a case study. The approach considered the complexity of the Par Pond ecosystem, the large size of Par Pond, the volume of contaminated sediments, and the institutional controls existing at SRS. The Environmental Protection Agency (EPA) considers units with large volumes of low-concentration wastes, as is the case with Par Pond, to be {open_quotes}special sites.{close_quotes} Accordingly, EPA guidance establishes that the range of alternatives developed focus primarily on containment options and other remedial approaches that mitigate potential risks associated with the {open_quotes}special site.{close_quotes} The remedial alternatives, according to EPA, are not to be prohibitively expensive or difficult to implement. This case study also is representative of the types of issues that will need to be addressed within the Department of Energy (DOE) complex as nuclear facilities are transitioned to inactive status and corrective/remedial actions are warranted.

  7. Evaluation of groundwater flow and transport at the Shoal underground nuclear test: An interim report

    SciTech Connect (OSTI)

    Pohll, G.; Chapman, J.; Hassan, A.; Papelis, C.; Andricevic, R.; Shirley, C.

    1998-07-01

    Since 1962, all United States nuclear tests have been conducted underground. A consequence of this testing has been the deposition of large amounts of radioactive materials in the subsurface, sometimes in direct contact with groundwater. The majority of this testing occurred on the Nevada Test Site, but a limited number of experiments were conducted in other locations. One of these is the subject of this report, the Project Shoal Area (PSA), located about 50 km southeast of Fallon, Nevada. The Shoal test consisted of a 12-kiloton-yield nuclear detonation which occurred on October 26, 1963. Project Shoal was part of studies to enhance seismic detection of underground nuclear tests, in particular, in active earthquake areas. Characterization of groundwater contamination at the Project Shoal Area is being conducted by the US Department of Energy (DOE) under the Federal Facility Agreement and Consent Order (FFACO) with the State of Nevada Department of Environmental Protection and the US Department of Defense (DOD). This order prescribes a Corrective Action Strategy (Appendix VI), which, as applied to underground nuclear tests, involves preparing a Corrective Action Investigation Plan (CAIP), Corrective Action Decision Document (CADD), Corrective Action Plan, and Closure Report. The scope of the CAIP is flow and transport modeling to establish contaminant boundaries that are protective of human health and the environment. This interim report describes the current status of the flow and transport modeling for the PSA.

  8. Hazelwood Interim Storage Site annual environmental report for calendar year 1991, Hazelwood, Missouri. [Hazelwood Interim Storage Site

    SciTech Connect (OSTI)

    Not Available

    1992-09-01

    This document describes the environmental monitoring program at the Hazelwood Interim Storage Site (HISS) and surrounding area, implementation of the program, and monitoring results for 1991. Environmental monitoring of HISS began in 1984 when the site was assigned to the US Department of Energy (DOE) as part of the decontamination research and development project authorized by Congress under the 1984 Energy and Water Development Appropriations Act. DOE placed responsibility for HISS under the Formerly Utilized Sites Remedial Action Program (FUSRAP), a DOE program to decontaminate or otherwise control sites where residual radioactive materials remain from the early years of the nation's atomic energy program or from commercial operations causing conditions that Congress has authorized DOE to remedy. The environmental monitoring program at HISS includes sampling networks for radon concentrations in air; external gamma radiation exposure; and radium-226, thorium-230, and total uranium concentrations in surface water, sediment, and groundwater. Additionally, several nonradiological parameters are measured in groundwater. Monitoring results are compared with applicable Environmental Protection Agency standards, DOE derived concentration guides (DCGs), dose limits, and other requirements in DOE orders. Environmental standards and DCGs are established to protect public health and the environment.

  9. Wayne Interim Storage Site annual environmental report for calendar year 1991, Wayne, New Jersey. [Wayne Interim Storage Site

    SciTech Connect (OSTI)

    1992-09-01

    This document describes the envirormental monitoring program at the Wayne Interim Storage Site (WISS) and surrounding area, implementation of the program, and monitoring results for 1991. Environmental monitoring of WISS and surrounding area began in 1984 when Congress added the site to the US Department of Energy's (DOE) Formerly Utilized Sites Remedial Action Program (FUSRAP). FUSRAP is a DOE program to decontaminate or otherwise control sites where residual radioactive materials remain from the early years of the nation's atomic energy program or from commercial operations causing conditions that Congress has authorized DOE to remedy. WISS is a National Priorities List site. The environmental monitoring program at WISS includes sampling networks for radon and thoron concentrations in air; external gamma radiation exposure; and radium-226, radium-228, thorium-232, and total uranium concentrations in surface water, sediment, and groundwater. Several nonradiological parameters are also measured in groundwater. Monitoring results are compared with applicable Environmental Protection Agency standards, DOE derived concentration guides, dose limits, and other requirements in DOE orders. Environmental standards are established to protect public health and the environment.

  10. Chromium Interim Measures Project and Ongoing Plume Investigation...

    Broader source: Energy.gov (indexed) [DOE]

    Topic: Danny Katzman LANL, Provided Information on the Ongoing Characterization of the Chromium Plume in Mortandad Canyon and the Pump and Treat Pilot Test. Chromium Update - March...

  11. Northeast Site Non-Aqueous Phase Liquids Interim Measures Progress...

    Office of Legacy Management (LM)

    5 Figure 3. Energy Balance......7 Figure 7. Treatment System Process Flow Diagram ... sent from there to the LNAPL and DNAPL waste storage tanks. ...

  12. Chromium Interim Measures Project and Ongoing Plume Investigation

    Broader source: Energy.gov [DOE]

    At the March 12, 2015 Committee meeting Danny Katzman LANL, Provided Information on the Ongoing Characterization of the Chromium Plume in Mortandad Canyon and the Pump and Treat Pilot Test.

  13. Permitting plan for the high-level waste interim storage

    SciTech Connect (OSTI)

    Deffenbaugh, M.L.

    1997-04-23

    This document addresses the environmental permitting requirements for the transportation and interim storage of solidified high-level waste (HLW) produced during Phase 1 of the Hanford Site privatization effort. Solidified HLW consists of canisters containing vitrified HLW (glass) and containers that hold cesium separated during low-level waste pretreatment. The glass canisters and cesium containers will be transported to the Canister Storage Building (CSB) in a U.S. Department of Energy (DOE)-provided transportation cask via diesel-powered tractor trailer. Tri-Party Agreement (TPA) Milestone M-90 establishes a new major milestone, and associated interim milestones and target dates, governing acquisition and/or modification of facilities necessary for: (1) interim storage of Tank Waste Remediation Systems (TWRS) immobilized HLW (IHLW) and other canistered high-level waste forms; and (2) interim storage and disposal of TWRS immobilized low-activity tank waste (ILAW). An environmental requirements checklist and narrative was developed to identify the permitting path forward for the HLW interim storage (HLWIS) project (See Appendix B). This permitting plan will follow the permitting logic developed in that checklist.

  14. NEXT GENERATION MELTER OPTIONEERING STUDY - INTERIM REPORT

    SciTech Connect (OSTI)

    GRAY MF; CALMUS RB; RAMSEY G; LOMAX J; ALLEN H

    2010-10-19

    The next generation melter (NOM) development program includes a down selection process to aid in determining the recommended vitrification technology to implement into the WTP at the first melter change-out which is scheduled for 2025. This optioneering study presents a structured value engineering process to establish and assess evaluation criteria that will be incorporated into the down selection process. This process establishes an evaluation framework that will be used progressively throughout the NGM program, and as such this interim report will be updated on a regular basis. The workshop objectives were achieved. In particular: (1) Consensus was reached with stakeholders and technology providers represented at the workshop regarding the need for a decision making process and the application of the D{sub 2}0 process to NGM option evaluation. (2) A framework was established for applying the decision making process to technology development and evaluation between 2010 and 2013. (3) The criteria for the initial evaluation in 2011 were refined and agreed with stakeholders and technology providers. (4) The technology providers have the guidance required to produce data/information to support the next phase of the evaluation process. In some cases it may be necessary to reflect the data/information requirements and overall approach to the evaluation of technology options against specific criteria within updated Statements of Work for 2010-2011. Access to the WTP engineering data has been identified as being very important for option development and evaluation due to the interface issues for the NGM and surrounding plant. WRPS efforts are ongoing to establish precisely data that is required and how to resolve this Issue. It is intended to apply a similarly structured decision making process to the development and evaluation of LAW NGM options.

  15. Report to Congress on Plan for Interim Storage of Spent Nuclear...

    Office of Environmental Management (EM)

    RW-0596 Report to Congress on the Demonstration of the Interim Storage of Spent Nuclear ... D.C. Report to Congress on the Demonstration of the Interim Storage of Spent ...

  16. Ultrasonic Characterization of Cast Austenitic Stainless Steel Microstructure: Discrimination between Equiaxed- and Columnar-Grain Material – An Interim Study

    SciTech Connect (OSTI)

    Ramuhalli, Pradeep; Good, Morris S.; Diaz, Aaron A.; Anderson, Michael T.; Watson, Bruce E.; Peters, Timothy J.; Dixit, Mukul; Bond, Leonard J.

    2009-10-27

    Ultrasonic nondestructive evaluation (NDE) and inspection of cast austenitic stainless steel (CASS) components used in the nuclear power industry is neither as effective nor reliable as is needed due to detrimental effects upon the interrogating ultrasonic beam and interference from ultrasonic backscatter. The root cause is the coarse-grain microstructure inherent to this class of materials. Some ultrasonic techniques perform better for particular microstructural classifications and this has led to the hypothesis that an ultrasonic inspection can be optimized for a particular microstructural class, if a technique exists to reliably classify the microstructure for feedback to the inspection. This document summarizes scoping experiments of in-situ ultrasonic methods for classification and/or characterization of the material microstructures in CASS components from the outside surface of a pipe. The focus of this study was to evaluate ultrasonic methods and provide an interim report that documents results and technical progress. An initial set of experiments were performed to test the hypothesis that in-service characterization of cast austenitic stainless steel (CASS) is feasible, and that, if reliably performed, such data would provide real-time feedback to optimize in-service inspections in the field. With this objective in mind, measurements for the experiment were restricted to techniques that should be robust if carried forward to eventual field implementation. Two parameters were investigated for their ability to discriminate between different microstructures in CASS components. The first parameter was a time-of-flight ratio of a normal incidence shear wave to that of a normal incidence longitudinal wave (TOFRSL). The ratio removed dependency on component thickness which may not be accurately reported in the field. The second parameter was longitudinal wave attenuation. The selected CASS specimens provided five equiaxed-grain material samples and five columnar

  17. ATVM Loan Program Interim Final Rule (November 12, 2008) | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy Loan Program Interim Final Rule (November 12, 2008) ATVM Loan Program Interim Final Rule (November 12, 2008) Advanced Technology Vehicles Manufacturing Incentive Program ATVM Loan Program Interim Final Rule (130.09 KB) More Documents & Publications Automotive Trade Policy Council: Proposed Interim Final Rule Updated Guidance For Applicants To Advanced Technology Vehicles Manufacturing Loan Program ATVM Guidance for Applicants 11.4.14

  18. ANALYSIS OF DOSE RATES DURING REPLACEMENT OF MANIPULATORS IN THE FFTF INTERIM EXAMINATION & MAINTENANCE (IEM) CELL

    SciTech Connect (OSTI)

    NELSON, J.V.

    2002-01-23

    Replacement of a master-slave manipulator in the Interim Examination and Maintenance Cell at the Fast Flux Test Facility was carried out in August 2001. This operation created a 178-mm opening in the thick concrete wall of the hot cell. To aid in radiological work planning, dose rates outside the penetration in the wall were predicted using MCNP{trademark} photon transport calculations. The predicted dose rate was 7.7 mrem/h, which was reasonably close to the value of 10.4 mrem/h inferred from measurements.

  19. A review of proposed Glen Canyon Dam interim operating criteria

    SciTech Connect (OSTI)

    LaGory, K.; Hlohowskyj, I.; Tomasko, D.; Hayse, J.; Durham, L.

    1992-04-01

    Three sets of interim operating criteria for Glen Canyon Dam on the Colorado River have been proposed for the period of November 1991, to the completion of the record of decision for the Glen Canyon Dam environmental impact statement (about 1993). These criteria set specific limits on dam releases, including maximum and minimum flows, up-ramp and down-ramp rates, and maximum daily fluctuation. Under the proposed interim criteria, all of these parameters would be reduced relative to historical operating criteria to protect downstream natural resources, including sediment deposits, threatened and endangered fishes, trout, the aquatic food base, and riparian plant communities. The scientific bases of the three sets of proposed operating criteria are evaluated in the present report:(1) criteria proposed by the Research/Scientific Group, associated with the Glen Canyon Environmental Studies (GCES); (2) criteria proposed state and federal officials charged with managing downstream resources; and (3) test criteria imposed from July 1991, to November 1991. Data from Phase 1 of the GCES and other sources established that the targeted natural resources are affected by dam operations, but the specific interim criteria chosen were not supported by any existing studies. It is unlikely that irreversible changes to any of the resources would occur over the interim period if historical operating criteria remained in place. It is likely that adoption of any of the sets of proposed interim operating criteria would reduce the levels of sediment transport and erosion below Glen Canyon Dam; however, these interim criteria could result in some adverse effects, including the accumulation of debris at tributary mouths, a shift of new high-water-zone vegetation into more flood-prone areas, and further declines in vegetation in the old high water zone.

  20. Single-shell tank interim stabilization project plan

    SciTech Connect (OSTI)

    Ross, W.E.

    1998-03-27

    Solid and liquid radioactive waste continues to be stored in 149 single-shell tanks at the Hanford Site. To date, 119 tanks have had most of the pumpable liquid removed by interim stabilization. Thirty tanks remain to be stabilized. One of these tanks (C-106) will be stabilized by retrieval of the tank contents. The remaining 29 tanks will be interim stabilized by saltwell pumping. In the summer of 1997, the US Department of Energy (DOE) placed a moratorium on the startup of additional saltwell pumping systems because of funding constraints and proposed modifications to the Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) milestones to the Washington State Department of Ecology (Ecology). In a letter dated February 10, 1998, Final Determination Pursuant to Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) in the Matter of the Disapproval of the DOE`s Change Control Form M-41-97-01 (Fitzsimmons 1998), Ecology disapproved the DOE Change Control Form M-41-97-01. In response, Fluor Daniel Hanford, Inc. (FDH) directed Lockheed Martin Hanford Corporation (LNMC) to initiate development of a project plan in a letter dated February 25, 1998, Direction for Development of an Aggressive Single-Shell Tank (SST) Interim Stabilization Completion Project Plan in Support of Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement). In a letter dated March 2, 1998, Request for an Aggressive Single-Shell Tank (SST) Interim Stabilization Completion Project Plan, the DOE reaffirmed the need for an aggressive SST interim stabilization completion project plan to support a finalized Tri-Party Agreement Milestone M-41 recovery plan. This project plan establishes the management framework for conduct of the TWRS Single-Shell Tank Interim Stabilization completion program. Specifically, this plan defines the mission needs and requirements; technical objectives and approach; organizational structure, roles, responsibilities

  1. Now Available: Interim Report on Customer Acceptance, Retention, and

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Response to Time-Based Rates from the Consumer Behavior Studies | Department of Energy Interim Report on Customer Acceptance, Retention, and Response to Time-Based Rates from the Consumer Behavior Studies Now Available: Interim Report on Customer Acceptance, Retention, and Response to Time-Based Rates from the Consumer Behavior Studies June 26, 2015 - 5:30pm Addthis Since 2009, the U.S. Department of Energy, using funds from the American Recovery and Reinvestment Act, and the electric power

  2. RTD Biodiesel (B20) Transit Bus Evaluation: Interim Review Summary

    Alternative Fuels and Advanced Vehicles Data Center [Office of Energy Efficiency and Renewable Energy (EERE)]

    RTD Biodiesel (B20) Transit Bus Evaluation: Interim Review Summary K. Proc, R. Barnitt, and R.L. McCormick Technical Report NREL/TP-540-38364 August 2005 RTD Biodiesel (B20) Transit Bus Evaluation: Interim Review Summary K. Proc, R. Barnitt, and R.L. McCormick Prepared under Task No. FC05.9400 Technical Report NREL/TP-540-38364 August 2005 National Renewable Energy Laboratory 1617 Cole Boulevard, Golden, Colorado 80401-3393 303-275-3000 * www.nrel.gov Operated for the U.S. Department of Energy

  3. Monticello Mill Tailings Site Operable Unit Ill Interim Remedial Action

    Office of Legacy Management (LM)

    Site Operable Unit Ill Interim Remedial Action Mark Perfxmed Under DOE Contrici No. DE-AC13-96CJ873.35 for th3 U.S. De[:ar!menf of Energy app~oveJioi'ptiL#ic re1ease;dCinWlionis Unlimilra' This page intentionally left blank Monticello Mill Tailings Site Operable Unit I11 Interim Remedial Action Annual Status Report August 1999 Prepared for U.S. Department of Energy Albuquerque Operations Office Grand Junction Office Project Number MSG-035-0011-00-000 Document Number Q0017700 Work Performed Under

  4. Canister Storage Building and Interim Storage Area - Hanford Site

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Canister Storage Building and Interim Storage Area About Us About Hanford Cleanup Hanford History Hanford Site Wide Programs Contact Us 100 Area 118-K-1 Burial Ground 200 Area 222-S Laboratory 242-A Evaporator 300 Area 324 Building 325 Building 400 Area/Fast Flux Test Facility 618-10 and 618-11 Burial Grounds 700 Area B Plant B Reactor C Reactor Canister Storage Building and Interim Storage Area Canyon Facilities Cold Test Facility D and DR Reactors Effluent Treatment Facility Environmental

  5. Status of Corrective Actions

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    WIPP AIB Report Status of Corrective Actions Status of Corrective Actions at LANL Department of Energy Issues Accident Investigation Board (AIB) Report on February 14 Incident ...

  6. High Temperature Materials Interim Data Qualification Report FY 2011

    SciTech Connect (OSTI)

    Nancy Lybeck

    2011-08-01

    Projects for the very high temperature reactor (VHTR) Technology Development Office provide data in support of Nuclear Regulatory Commission licensing of the VHTR. Fuel and materials to be used in the reactor are tested and characterized to quantify performance in high temperature and high fluence environments. The VHTR program has established the Next Generation Nuclear Plant (NGNP) Data Management and Analysis System (NDMAS) to ensure that VHTR data are qualified for use, stored in a readily accessible electronic form, and analyzed to extract useful results. This document focuses on the first NDMAS objective. It describes the High Temperature Materials characterization data stream, the processing of these data within NDMAS, and reports the interim fiscal year (FY) 2011 qualification status of the data. Data qualification activities within NDMAS for specific types of data are determined by the data qualification category assigned by the data generator. The High Temperature Materials data are being collected under the Nuclear Quality Assurance (NQA)-1 guidelines and will be qualified data. For NQA-1 qualified data, the qualification activities include: (1) capture testing to confirm that the data stored within NDMAS are identical to the raw data supplied, (2) accuracy testing to confirm that the data are an accurate representation of the system or object being measured, and (3) documenting that the data were collected under an NQA-1 or equivalent Quality Assurance program. Currently, data from seven test series within the High Temperature Materials data stream have been entered into the NDMAS vault, including tensile tests, creep tests, and cyclic tests. Of the 5,603,682 records currently in the vault, 4,480,444 have been capture passed, and capture testing is in process for the remaining 1,123,238.

  7. Evapotranspiration Cover for the 92-Acre Area Retired Mixed Waste Pits:Interim CQA Report

    SciTech Connect (OSTI)

    The Delphi Groupe, Inc., and J. A. Cesare and Associates, Inc.

    2011-06-20

    This Interim Construction Quality Assurance (CQA) Report is for the 92-Acre Evapotranspiration Cover, Area 5 Waste Management Division (WMD) Retired Mixed Waste Pits, Nevada National Security Site, Nevada for the period of January 20, 2011 to May 12, 2011. This Interim Construction Quality Assurance (CQA) Report is for the 92-Acre Evapotranspiration Cover, Area 5 Waste Management Division (WMD) Retired Mixed Waste Pits, Nevada National Security Site, Nevada for the period of January 20, 2011 to May 12, 2011. Construction was approved by the Nevada Division of Environmental Protection (NDEP) under the Approval of Corrective Action Decision Document/Corrective Action Plan (CADD/CAP) for Corrective Action Unit (CAU) 111: Area 5 WMD Retired Mixed Waste Pits, Nevada National Security Site, Nevada, on January 6, 2011, pursuant to Subpart XII.8a of the Federal Facility Agreement and Consent Order. The project is located in Area 5 of the Radioactive Waste Management Complex (RWMC) at the Nevada National Security Site (NNSS), formerly known as the Nevada Test Site, located in southern Nevada, approximately 65 miles northwest of Las Vegas, Nevada, in Nye County. The project site, in Area 5, is located in a topographically closed basin approximately 14 additional miles north of Mercury Nevada, in the north-central part of Frenchman Flat. The Area 5 RWMS uses engineered shallow-land burial cells to dispose of packaged waste. The 92-Acre Area encompasses the southern portion of the Area 5 RWMS, which has been designated for the first final closure operations. This area contains 13 Greater Confinement Disposal (GCD) boreholes, 16 narrow trenches, and 9 broader pits. With the exception of two active pits (P03 and P06), all trenches and pits in the 92-Acre Area had operational covers approximately 2.4 meters thick, at a minimum, in most areas when this project began. The units within the 92-Acre Area are grouped into the following six informal categories based on physical location

  8. System Specification for Immobilized High-Level Waste Interim Storage

    SciTech Connect (OSTI)

    CALMUS, R.B.

    2000-12-27

    This specification establishes the system-level functional, performance, design, interface, and test requirements for Phase 1 of the IHLW Interim Storage System, located at the Hanford Site in Washington State. The IHLW canisters will be produced at the Hanford Site by a Selected DOE contractor. Subsequent to storage the canisters will be shipped to a federal geologic repository.

  9. Single-shell tank interim stabilization project plan

    SciTech Connect (OSTI)

    Ross, W.E.

    1998-05-11

    This project plan establishes the management framework for conduct of the TWRS Single-Shell Tank Interim Stabilization completion program. Specifically, this plan defines the mission needs and requirements; technical objectives and approach; organizational structure, roles, responsibilities, and interfaces; and operational methods. This plan serves as the project executional baseline.

  10. Single Shell Tank (SST) Interim Stabilization Project Plan

    SciTech Connect (OSTI)

    VLADIMIROFF, D.T.; BOYLES, V.C.

    2000-05-22

    This project plan establishes the management framework for the conduct of the CHG Single-Shell Tank Interim Stabilization completion program. Specifically, this plan defines the mission needs and requirements; technical objectives and approach; organization structure, roles, responsibilities, and interfaces; and operational methods. This plan serves as the project executional baseline.

  11. SLIGHTLY IRRADIATED FUEL (SIF) INTERIM DISPOSITION PROJECT

    SciTech Connect (OSTI)

    NORTON SH

    2010-02-23

    CH2M HILL Plateau Remediation Company (CH2M HILL PRC) is proud to submit the Slightly Irradiated Fuel (SIF) Interim Disposition Project for consideration by the Project Management Institute as Project of the Year for 2010. The SIF Project was a set of six interrelated sub-projects that delivered unique stand-alone outcomes, which, when integrated, provided a comprehensive and compliant system for storing high risk special nuclear materials. The scope of the six sub-projects included the design, construction, testing, and turnover of the facilities and equipment, which would provide safe, secure, and compliant Special Nuclear Material (SNM) storage capabilities for the SIF material. The project encompassed a broad range of activities, including the following: Five buildings/structures removed, relocated, or built; Two buildings renovated; Structural barriers, fencing, and heavy gates installed; New roadways and parking lots built; Multiple detection and assessment systems installed; New and expanded communication systems developed; Multimedia recording devices added; and A new control room to monitor all materials and systems built. Project challenges were numerous and included the following: An aggressive 17-month schedule to support the high-profile Plutonium Finishing Plant (PFP) decommissioning; Company/contractor changeovers that affected each and every project team member; Project requirements that continually evolved during design and construction due to the performance- and outcome-based nature ofthe security objectives; and Restrictions imposed on all communications due to the sensitive nature of the projects In spite of the significant challenges, the project was delivered on schedule and $2 million under budget, which became a special source of pride that bonded the team. For years, the SIF had been stored at the central Hanford PFP. Because of the weapons-grade piutonium produced and stored there, the PFP had some of the tightest security on the Hanford

  12. Corrective Actions Process

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Community, Environment » Environmental Stewardship » Environmental Cleanup » Corrective Actions Corrective Actions Process The general process for evaluating and remediating potential release sites is called the corrective action process. Contact Environmental Communication & Public Involvement P.O. Box 1663 MS M996 Los Alamos, NM 87545 (505) 667-0216 Email Corrective actions The Laboratory's corrective actions process refers to the way in which the Laboratory investigates, stabilizes,

  13. Maywood Interim Storage Site environmental report for calendar year 1989, Maywood, New Jersey

    SciTech Connect (OSTI)

    Not Available

    1990-05-01

    The environmental monitoring program, which began in 1984, was continued in 1989 at the Maywood Interim Storage Site (MISS), a US Department of Energy (DOE) facility located in the Borough of Maywood and the Township of Rochelle Park, New Jersey. MISS is currently used for storage of soils contaminated with low-level radioactivity. MISS is part of the Formerly Utilized Sites Remedial Action Program (FUSRAP), a DOE program to identify and decontaminate or otherwise control sites where residual radioactive materials are present. The monitoring program at MISS measures thoron and radon concentrations in air; external gamma radiation levels; and thorium, uranium, and radium concentrations in surface water, groundwater, and sediment. Additionally, several nonradiological parameters are measured in groundwater. The radiation dose was calculated for a hypothetical maximally exposed individual to verify that the site is in compliance with the DOE radiation protection standard (100 mrem/yr) and to assess its potential effects on public health. This report presents the results of the environmental monitoring program conducted at the US Department of Energy's (DOE) Maywood Interim Storage Site (MISS) during calendar year 1989. Environmental monitoring began at MISS in 1984. 19 refs., 23 figs., 14 tabs.

  14. First interim examination of defected BWR and PWR rods tested in unlimited air at 229/sup 0/C

    SciTech Connect (OSTI)

    Einziger, R.E.; Cook, J.A.

    1983-01-01

    A five-year whole rod test was initiated to investigate the long-term stability of spent fuel rods under a variety of possible dry storage conditions. Both PWR and BWR rods were included in the test. The first interim examination was conducted after three months of testing to determine if there was any degradation in those defected rods stored in an unlimited air atmosphere. Visual observations, diametral measurements and radiographic smears were used to assess the degree of cladding deformation and particulate dispersal. The PWR rod showed no measurable change from the pre-test condition. The two original artificial defects had not changed in appearance and there was no diametral growth of the cladding. One of the defects in BWR rod showed significant deformation. There was approximately 10% cladding strain at the defect site and a small axial crack had formed. The fuel in the defect did not appear to be friable. The second defect showed no visible change and no cladding strain. Following examination, the test was continued at 230/sup 0/C. Another interim examination is planned during the summer of 1983. This paper discusses the details and meaning of the data from the first interim examination.

  15. Small fields output factors measurements and correction factors determination for several detectors for a CyberKnife{sup Registered-Sign} and linear accelerators equipped with microMLC and circular cones

    SciTech Connect (OSTI)

    Bassinet, C.; Huet, C.; Derreumaux, S.; Baumann, M.; Trompier, F.; Roch, P.; Clairand, I.; Brunet, G.; Gaudaire-Josset, S.; Chea, M.; Boisserie, G.

    2013-07-15

    Purpose: The use of small photon fields is now an established practice in stereotactic radiosurgery and radiotherapy. However, due to a lack of lateral electron equilibrium and high dose gradients, it is difficult to accurately measure the dosimetric quantities required for the commissioning of such systems. Moreover, there is still no metrological dosimetric reference for this kind of beam today. In this context, the first objective of this work was to determine and to compare small fields output factors (OF) measured with different types of active detectors and passive dosimeters for three types of facilities: a CyberKnife{sup Registered-Sign} system, a dedicated medical linear accelerator (Novalis) equipped with m3 microMLC and circular cones, and an adaptive medical linear accelerator (Clinac 2100) equipped with an additional m3 microMLC. The second one was to determine the k{sub Q{sub c{sub l{sub i{sub n,Q{sub m{sub s{sub r}{sup f{sub c}{sub l}{sub i}{sub n},f{sub m}{sub s}{sub r}}}}}}}}} correction factors introduced in a recently proposed small field dosimetry formalism for different active detectors.Methods: Small field sizes were defined either by microMLC down to 6 Multiplication-Sign 6 mm{sup 2} or by circular cones down to 4 mm in diameter. OF measurements were performed with several commercially available active detectors dedicated to measurements in small fields (high resolution diodes: IBA SFD, Sun Nuclear EDGE, PTW 60016, PTW 60017; ionizing chambers: PTW 31014 PinPoint chamber, PTW 31018 microLion liquid chamber, and PTW 60003 natural diamond). Two types of passive dosimeters were used: LiF microcubes and EBT2 radiochromic films.Results: Significant differences between the results obtained by several dosimetric systems were observed, particularly for the smallest field size for which the difference in the measured OF reaches more than 20%. For passive dosimeters, an excellent agreement was observed (better than 2%) between EBT2 and LiF microcubes

  16. T Tank Farm Interim Surface Barrier Demonstration--Vadose Zone Monitoring Plan

    SciTech Connect (OSTI)

    Zhang, Z. F.; Keller, Jason M.; Strickland, Christopher E.

    2007-04-01

    The Hanford Site has 149 underground single-shell tanks that store hazardous radioactive waste. Many of these tanks and their associated infrastructure (e.g., pipelines, diversion boxes) have leaked. Some of the leaked waste has entered the groundwater. The largest known leak occurred from the T-106 Tank in 1973. Many of the contaminants from that leak still reside within the vadose zone beneath the T Tank Farm. CH2M Hill Hanford Group, Inc. seeks to minimize movement of this residual contaminant plume by placing an interim barrier on the surface. Such a barrier is expected to prevent infiltrating water from reaching the plume and moving it further. A plan has been prepared to monitor and determine the effectiveness of the interim surface barrier. Soil water content and water pressure will be monitored using off-the-shelf equipment that can be installed by the hydraulic hammer technique. In fiscal year 2006, two instrument nests were installed. Each instrument nest contains a neutron probe access tube, a capacitance probe, four heat-dissipation units, and a drain gauge to measure soil water flux. A meteorological station has been installed outside of the fence. In fiscal year 2007, two additional instrument nests are planned to be installed beneath the proposed barrier.

  17. T Tank Farm Interim Surface Barrier Demonstration - Vadose Zone Monitoring FY08 Report

    SciTech Connect (OSTI)

    Zhang, Z. F.; Strickland, Christopher E.; Field, Jim G.; Parker, Danny L.

    2009-02-01

    DOE’s Office of River Protection constructed a temporary surface barrier over a portion of the T Tank Farm as part of the T Farm Interim Surface Barrier Demonstration Project. The surface barrier is designed to minimize the infiltration of precipitation into the contaminated soil zone created by the Tank T-106 leak and minimize movement of the contamination. As part of the demonstration effort, vadose zone moisture is being monitored to assess the effectiveness of the barrier at reducing soil moisture. A solar-powered system was installed to continuously monitor soil water conditions at four locations (i.e., instrument Nests A, B, C, and D) beneath the barrier and outside the barrier footprint as well as site meteorological conditions. Nest A is placed in the area outside the barrier footprint and serves as a control, providing subsurface conditions outside the influence of the surface barrier. Nest B provides subsurface measurements to assess surface-barrier edge effects. Nests C and D are used to assess changes in soil-moisture conditions beneath the interim surface barrier.

  18. Plutonium Finishing Plant. Interim plutonium stabilization engineering study

    SciTech Connect (OSTI)

    Sevigny, G.J.; Gallucci, R.H.; Garrett, S.M.K.; Geeting, J.G.H.; Goheen, R.S.; Molton, P.M.; Templeton, K.J.; Villegas, A.J.; Nass, R.

    1995-08-01

    This report provides the results of an engineering study that evaluated the available technologies for stabilizing the plutonium stored at the Plutonium Finishing Plant located at the hanford Site in southeastern Washington. Further processing of the plutonium may be required to prepare the plutonium for interim (<50 years) storage. Specifically this document provides the current plutonium inventory and characterization, the initial screening process, and the process descriptions and flowsheets of the technologies that passed the initial screening. The conclusions and recommendations also are provided. The information contained in this report will be used to assist in the preparation of the environmental impact statement and to help decision makers determine which is the preferred technology to process the plutonium for interim storage.

  19. FRACTIONAL CRYSTALLIZATION LABORATORY TESTING WITH INTERIM PRETREATMENT SYSTEM FEEDS

    SciTech Connect (OSTI)

    HERTING DL

    2008-09-17

    The fractional crystallization process was developed as a pretreatment method for saltcake waste retrieved from Hanford single-shell tanks (SST). The process separates the retrieved SST waste into a high-level waste stream containing the bulk of the radionuclides and a low-activity waste stream containing the bulk of the nonradioactive sodium salts. The Interim Pretreatment System project shifted the focus on pretreatment planning from SST waste to double-shell tank waste.

  20. DOE Names Interim Manager for Idaho Operations Office

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Energy NNSA Site Facility Management Contracts - June 2016 DOE NNSA Site Facility Management Contracts - June 2016 DOE NNSA Site Facility Management Contracts - June 2016.pdf (58.05 KB) More Documents & Publications DOEfacilitymgt_contractsownership_01052011.pdf Chapter 1 - Acquisition Regulations System Class Patent Waiver W(C)2008-001

    DOE Names Interim Manager for Idaho Operations Office Dennis Miotla, the Office of Nuclear Energy's Deputy Assistant Secretary Dennis Miotla for

  1. Interim Stabilization Equipment Essential and Support Drawing Plan

    SciTech Connect (OSTI)

    KOCH, M.R.

    1999-10-22

    The purpose of this document is to list the Interim Stabilization equipment drawings that are classified as Essential or Support drawings. Essential Drawings: Those drawings identified by the facility staff as necessary to directly support the safe operation of the facility or equipment. Support Drawings: Those drawings identified by the facility staff that further describe the design details of structures, systems or components shown on essential drawings.

  2. Method of preparing nuclear wastes for tansportation and interim storage

    DOE Patents [OSTI]

    Bandyopadhyay, Gautam (Naperville, IL); Galvin, Thomas M. (Darien, IL)

    1984-01-01

    Nuclear waste is formed into a substantially water-insoluble solid for temporary storage and transportation by mixing the calcined waste with at least 10 weight percent powdered anhydrous sodium silicate to form a mixture and subjecting the mixture to a high humidity environment for a period of time sufficient to form cementitious bonds by chemical reaction. The method is suitable for preparing an interim waste form from dried high level radioactive wastes.

  3. 105-H Reactor Interim Safe Storage Project Final Report

    SciTech Connect (OSTI)

    E.G. Ison

    2008-11-08

    The following information documents the decontamination and decommissioning of the 105-H Reactor facility, and placement of the reactor core into interim safe storage. The D&D of the facility included characterization, engineering, removal of hazardous and radiologically contaminated materials, equipment removal, decontamination, demolition of the structure, and restoration of the site. The ISS work also included construction of the safe storage enclosure, which required the installation of a new roofing system, power and lighting, a remote monitoring system, and ventilation components.

  4. Report on interim storage of spent nuclear fuel

    SciTech Connect (OSTI)

    Not Available

    1993-04-01

    The report on interim storage of spent nuclear fuel discusses the technical, regulatory, and economic aspects of spent-fuel storage at nuclear reactors. The report is intended to provide legislators state officials and citizens in the Midwest with information on spent-fuel inventories, current and projected additional storage requirements, licensing, storage technologies, and actions taken by various utilities in the Midwest to augment their capacity to store spent nuclear fuel on site.

  5. Report to Congress on Plan for Interim Storage of Spent Nuclear Fuel from

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Decommissioned Reactors | Department of Energy Report to Congress on Plan for Interim Storage of Spent Nuclear Fuel from Decommissioned Reactors Report to Congress on Plan for Interim Storage of Spent Nuclear Fuel from Decommissioned Reactors Report to Congress on Plan for Interim Storage of Spent Nuclear Fuel from Decommissioned Reactors (229.88 KB) More Documents & Publications Information Request, "THE REPORT TO THE PRESIDENT AND THE CONGRESS BY THE SECRETARY OF ENERGY ON THE

  6. Interim Test Procedures for Evaluating Electrical Performance and Grid Integration of Vehicle-to-Grid Applications

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    of Energy Interim Report of the Task Force on Nuclear Nonproliferation Interim Report of the Task Force on Nuclear Nonproliferation The SEAB Task Force on Nuclear Nonproliferation (TFNN) was established by the Secretary of Energy on December 20, 2014 to advise the Department of Energy (DOE) on future areas of emphasis for its nuclear nonproliferation activities. This interim report of the Task Force sets forth its findings and recommendations to date in five timely and important areas: (I)

  7. Interim Report of the Commission to Review the Effectiveness of the

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    National Energy Laboratories | Department of Energy Interim Report of the Commission to Review the Effectiveness of the National Energy Laboratories Interim Report of the Commission to Review the Effectiveness of the National Energy Laboratories This Interim Report presents the preliminary observations and recommendations gleaned from Phase I of the study by the Commission to Review the Effectiveness of the National Energy Laboratories (Commission). Key issues of the report focus on the

  8. Report to Congress on Plan for Interim Storage of Spent Nuclear...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Nuclear Fuel from Decommissioned Reactors Report to Congress on Plan for Interim Storage of Spent Nuclear Fuel from Decommissioned Reactors PDF icon Report to Congress on Plan ...

  9. Definition of the base analysis case of the interim performance assessment

    SciTech Connect (OSTI)

    Mann, F.M.

    1995-12-01

    The base analysis case for the ``Hanford Low-Level Tank Waste Interim Performance Assessment`` is defined. Also given are brief description of the sensitivity cases.

  10. Evaluation of 2004 Toyota Prius Hybrid Electric Drive System Interim Report

    SciTech Connect (OSTI)

    Ayers, C.W.

    2004-11-23

    Laboratory tests were conducted to evaluate the electrical and mechanical performance of the 2004 Toyota Prius and its hybrid electric drive system. As a hybrid vehicle, the 2004 Prius uses both a gasoline-powered internal combustion engine and a battery-powered electric motor as motive power sources. Innovative algorithms for combining these two power sources results in improved fuel efficiency and reduced emissions compared to traditional automobiles. Initial objectives of the laboratory tests were to measure motor and generator back-electromotive force (emf) voltages and determine gearbox-related power losses over a specified range of shaft speeds and lubricating oil temperatures. Follow-on work will involve additional performance testing of the motor, generator, and inverter. Information contained in this interim report summarizes the test results obtained to date, describes preliminary conclusions and findings, and identifies additional areas for further study.

  11. Fuel cell flooding detection and correction

    DOE Patents [OSTI]

    DiPierno Bosco, Andrew; Fronk, Matthew Howard

    2000-08-15

    Method and apparatus for monitoring an H.sub.2 -O.sub.2 PEM fuel cells to detect and correct flooding. The pressure drop across a given H.sub.2 or O.sub.2 flow field is monitored and compared to predetermined thresholds of unacceptability. If the pressure drop exists a threshold of unacceptability corrective measures are automatically initiated.

  12. Dispersion corrections to parity violating electron scattering

    SciTech Connect (OSTI)

    Gorchtein, M.; Horowitz, C. J. [Nuclear Theory Center, Indiana University, Bloomington, IN 47408 (United States); Ramsey-Musolf, M. J. [University of Wisconsin-Madison, Madison, WI 53706 (United States)

    2010-08-04

    We consider the dispersion correction to elastic parity violating electron-proton scattering due to {gamma}Z exchange. In a recent publication, this correction was reported to be substantially larger than the previous estimates. In this paper, we study the dispersion correction in greater detail. We confirm the size of the disperion correction to be {approx}6% for the QWEAK experiment designed to measure the proton weak charge. We enumerate parameters that have to be constrained to better than relative 30% in order to keep the theoretical uncertainty for QWEAK under control.

  13. Interim Guidance on DOE Personal Property Foreign Transactions

    Broader source: Energy.gov [DOE]

    The attached Acquisition Letter provides interim direction and procedural guidance to DOE and NNSA on proper protocol for personal property transactions executed with foreign entities, to include property title transfers, loans and abandonments and pertains to personal property in the hand of the Federal government, contractor or a third party. Direction and guidance is specific to accountable personal property, as defined in DOE Order 580.1. Guidance in this Acquisition Letter shall be followed until DOE Order 580.1 is updated to include foreign transactions.

  14. EIS-0283-S2: Interim Action Determination | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Use of H-Canyon/HB-Line to Prepare Feed for the Mixed Oxide Fuel Fabrication at the Savannah River Site) During Fiscal Year 2012, DOE will initiate activities in the H-Canyon and HB-Line to support plutonium oxide production. The purpose and need for this action is to ensure sufficient early feedstock will be readily available when the MFFF begin operations. For more information on this project, see the project webpage: http://energy.gov/node/299815. Download Document EIS-0283-S2: Interim Action

  15. Hanford Advisory Board Fiscal Year 2015 Interim Work Plan

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    5 Interim Work Plan Adopted by consensus September 5, 2014; comments from October committee discussions 1 Proposed additions from October TWC and RAP committee discussions in RED Topic Quarter 1 10/ 2014 - 12/2014 Quarter 2 01/2015- 03/2015 Quarter 3 04/2015 - 06/2015 Quarter 4 07/2015 - 09 2015 Committee Assignment (lead in Bold) Deferred Maintenance Plan Agency Lead: Kyle Rankin, DOE-RL Chief Engineer Action: Policy discussion Potential HAB Action: _____ Context: The status of structures on

  16. Conceptual design report for immobilized high-level waste interim storage facility (Phase 1)

    SciTech Connect (OSTI)

    Burgard, K.C.

    1998-06-02

    The Hanford Site Canister Storage Building (CSB Bldg. 212H) will be utilized to interim store Phase 1 HLW products. Project W-464, Immobilized High-Level Waste Interim Storage, will procure an onsite transportation system and retrofit the CSB to accommodate the Phase 1 HLW products. The Conceptual Design Report establishes the Project W-464 technical and cost basis.

  17. PROJECT W-551 INTERIM PRETREATMENT SYSTEM TECHNOLOGY SELECTION SUMMARY DECISION REPORT AND RECOMMENDATION

    SciTech Connect (OSTI)

    CONRAD EA

    2008-08-12

    This report provides the conclusions of the tank farm interim pretreatment technology decision process. It documents the methodology, data, and results of the selection of cross-flow filtration and ion exchange technologies for implementation in project W-551, Interim Pretreatment System. This selection resulted from the evaluation of specific scope criteria using quantitative and qualitative analyses, group workshops, and technical expert personnel.

  18. Guidance Regarding Actions That May Proceed During the NEPA Process: Interim Actions (DOE, 2003)

    Broader source: Energy.gov [DOE]

    DOE guidance to provide assistance in determining whether an action within the scope of an EIS may be taken before a record of decision is issued. The guidance reviews applicable requirements, gives examples of the types of actions that may proceed as interim actions, describes case studies, and outlines the steps in the EIS process for interim actions.

  19. Guidance Regarding Actions That May Proceed During the NEPA Process: Interim Actions

    Broader source: Energy.gov [DOE]

    DOE guidance to provide assistance in determining whether an action within the scope of an EIS may be taken before a record of decision is issued. The guidance reviews applicable requirements, gives examples of the types of actions that may proceed as interim actions, describes case studies, and outlines the steps in the EIS process for interim actions.

  20. Machine plumbness criteria: Interim technology release

    SciTech Connect (OSTI)

    Not Available

    1987-06-01

    The objective of this technology release is to define the maximum allowable deviation from plumb of the centrifuge machine and to recommend machine installation techniques to achieve the specified criteria. The centrifuge feature used as a reference for plumbness is the casing centerline as defined by a line drawn between the theoretical centers of the top and bottom flange faces. In practice, this measurement is accomplished by using specified casing flange diameters or bolt patterns as the reference points. The criterion adopted for GCEP is that each machine shall be plumb within 0.5 in. over the length of the casing as initially installed. Over a long period of time the plumbness is allowed to degrade to 1.0 in. This standard should be achievable using the currently planned installation techniques and within a time limit consistent with GCEP operational objectives. For development testing, centrifuge machines are meticulously adjusted using a plumb bob to achieve a plumbness with 1/8 in. About one to two days are required to complete the installation. This level of effort is justified for a development machine especially where baseline data is being gathered. A more reasonable standard with a corresponding reduction in installation time is required for GCEP. The specified criteria of 0.5 in. maximum out-of-plumb at time of installation and 1.0 in., ultimate, are believed to be a reasonable compromise. Machine design features or operating modes that are dependent on vertical alignment were examined to assess the impact of the selected plumbness criteria. Machine performance and design requirements are defined in the applicable technology release documents.

  1. Interim Storage of Plutonium in Existing Facilities

    SciTech Connect (OSTI)

    Woodsmall, T.D.

    1999-05-10

    'In this era of nuclear weapons disarmament and nonproliferation treaties, among many problems being faced by the Department of Energy is the safe disposal of plutonium. There is a large stockpile of plutonium at the Rocky Flats Environmental Technology Center and it remains politically and environmentally strategic to relocate the inventory closer to a processing facility. Savannah River Site has been chosen as the final storage location, and the Actinide Packaging and Storage Facility (APSF) is currently under construction for this purpose. With the ability of APSF to receive Rocky Flats material an estimated ten years away, DOE has decided to use the existing reactor building in K-Area of SRS as temporary storage to accelerate the removal of plutonium from Rocky Flats. There are enormous cost savings to the government that serve as incentive to start this removal as soon as possible, and the KAMS project is scheduled to receive the first shipment of plutonium in January 2000. The reactor building in K-Area was chosen for its hardened structure and upgraded seismic qualification, both resulting from an effort to restart the reactor in 1991. The KAMS project has faced unique challenges from Authorization Basis and Safety Analysis perspectives. Although modifying a reactor building from a production facility to a storage shelter is not technically difficult, the nature of plutonium has caused design and safety analysis engineers to make certain that the design of systems, structures and components included will protect the public, SRS workers, and the environment. A basic overview of the KAMS project follows. Plutonium will be measured and loaded into DOT Type-B shipping packages at Rocky Flats. The packages are 35-gallon stainless steel drums with multiple internal containment boundaries. DOE transportation vehicles will be used to ship the drums to the KAMS facility at SRS. They will then be unloaded, stacked and stored in specific locations throughout the

  2. Improving Ventilation and Saving Energy: Relocatable ClassroomField Study Interim Report

    SciTech Connect (OSTI)

    Apte, Michael G.; Buchanan, Ian S.; Faulkner, David; Hotchi,Toshifumi; Spears,Michael; Sullivan, Douglas P.; Wang, Duo

    2005-09-01

    The primary goals of this research effort are to develop, evaluate, and demonstrate a very practical HVAC system for classrooms that consistently provides classrooms with the quantity of ventilation in current minimum standards, while saving energy, and reducing HVAC-related noise levels. This research is motivated by the public benefits of energy efficiency, evidence that many classrooms are under-ventilated, and public concerns about indoor environmental quality in classrooms. This report presents an interim status update and preliminary findings from energy and indoor environmental quality (IEQ) measurements in sixteen relocatable classrooms in California. The field study includes measurements of HVAC energy use, ventilation rates, and IEQ conditions. Ten of the classrooms were equipped with a new HVAC technology and six control classrooms were equipped with a standard HVAC system. Energy use and many IEQ parameters have been monitored continuously, while unoccupied acoustic measurements were measured in one of four planned seasonal measurement campaigns. Continuously monitored data are remotely accessed via a LonWorks{reg_sign} network and stored in a relational database at LBNL. Preliminary results are presented here.

  3. Status of Corrective Actions

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Report on February 14 Incident at the Waste Isolation Pilot Project in Carlsbad, New Mexico April 12, 2012 x x Contact Communication Office (505) 667-7000 Corrective Actions...

  4. Corrective Action Program Guide

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2006-03-02

    This Guide was developed to assist the Department of Energy (DOE) organizations and contractors in the development, implementation, and followup of corrective action programs utilizing the feedback and improvement core safety function within DOE's Integrated Safety Management System. This Guide outlines some of the basic principles, concepts, and lessons learned that DOE managers and contractors might consider when implementing corrective action programs based on their specific needs. Canceled by DOE G 414.1-2B. Does not cancel other directives.

  5. Environmental Assessment and Corrective Measures Study Report...

    Office of Environmental Management (EM)

    2.1 PHYSIOGRAPHY AND SURFACE WATER HYDROLOGY ......20 2.2 GEOLOGY AND ... Facility Investigation RWQCB Regional Water Quality Control Board SVE Soil Vapor ...

  6. Realization of the German Concept for Interim Storage of Spent Nuclear Fuel - Current Situation and Prospects

    SciTech Connect (OSTI)

    Thomauske, B. R.

    2003-02-25

    The German government has determined a phase out of nuclear power. With respect to the management of spent fuel it was decided to terminate transports to reprocessing plants by 2005 and to set up interim storage facilities on power plant sites. This paper gives an overview of the German concept for spent fuel management focused on the new on-site interim storage concept and the applied interim storage facilities. Since the end of the year 1998, the utilities have applied for permission of on-site interim storage in 13 storage facilities and 5 storage areas; one application for the interim storage facility Stade was withdrawn due to the planned final shut down of Stade nuclear power plant in autumn 2003. In 2001 and 2002, 3 on-site storage areas and 2 on-site storage facilities for spent fuel were licensed by the Federal Office for Radiation Protection (BfS). A main task in 2002 and 2003 has been the examination of the safety and security of the planned interim storage facilities and the verification of the licensing prerequisites. In the aftermath of September 11, 2001, BfS has also examined the attack with a big passenger airplane. Up to now, these aircraft crash analyses have been performed for three on-site interim storage facilities; the fundamental results will be presented. It is the objective of BfS to conclude the licensing procedures for the applied on-site interim storage facilities in 2003. With an assumed construction period for the storage buildings of about two years, the on-site interim storage facilities could then be available in the year 2005.

  7. Interim Final Rule and Request for Comments, Federal Register, 71 FR 70275,

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    10 CFR Part 433, 434, and 435, December 4, 2006 | Department of Energy Interim Final Rule and Request for Comments, Federal Register, 71 FR 70275, 10 CFR Part 433, 434, and 435, December 4, 2006 Interim Final Rule and Request for Comments, Federal Register, 71 FR 70275, 10 CFR Part 433, 434, and 435, December 4, 2006 Document displays the interim final rule and request for comments for Energy Conservation Standards for New Federal Commercial and Multi-Family High-Rise Residential Buildings

  8. Advanced nuclear reactor public opinion project. Interim report

    SciTech Connect (OSTI)

    Benson, B.

    1991-07-25

    This Interim Report summarizes the findings of our first twenty in-depth interviews in the Advanced Nuclear Reactor Public Opinion Project. We interviewed 6 industry trade association officials, 3 industry attorneys, 6 environmentalists/nuclear critics, 3 state officials, and 3 independent analysts. In addition, we have had numerous shorter discussions with various individuals concerned about nuclear power. The report is organized into the four categories proposed at our April, 1991, Advisory Group meeting: safety, cost-benefit analysis, science education, and communications. Within each category, some change of focus from that of the Advisory Group has been required, to reflect the findings of our interviews. This report limits itself to describing our findings. An accompanying memo draws some tentative conclusions.

  9. SNF Interim Storage Canister Corrosion and Surface Environment Investigations

    SciTech Connect (OSTI)

    Bryan, Charles R.; Enos, David G.

    2015-09-01

    This progress report describes work being done at Sandia National Laboratories (SNL) to assess the localized corrosion performance of container/cask materials used in the interim storage of spent nuclear fuel (SNF). Of particular concern is stress corrosion cracking (SCC), by which a through-wall crack could potentially form in a canister outer wall over time intervals that are shorter than possible dry storage times. In order for SCC to occur, three criteria must be met. A corrosive environment must be present on the canister surface, the metal must susceptible to SCC, and sufficient tensile stress to support SCC must be present through the entire thickness of the canister wall. SNL is currently evaluating the potential for each of these criteria to be met.

  10. Method of absorbance correction in a spectroscopic heating value sensor

    DOE Patents [OSTI]

    Saveliev, Alexei; Jangale, Vilas Vyankatrao; Zelepouga, Sergeui; Pratapas, John

    2013-09-17

    A method and apparatus for absorbance correction in a spectroscopic heating value sensor in which a reference light intensity measurement is made on a non-absorbing reference fluid, a light intensity measurement is made on a sample fluid, and a measured light absorbance of the sample fluid is determined. A corrective light intensity measurement at a non-absorbing wavelength of the sample fluid is made on the sample fluid from which an absorbance correction factor is determined. The absorbance correction factor is then applied to the measured light absorbance of the sample fluid to arrive at a true or accurate absorbance for the sample fluid.

  11. Correction coil cable

    DOE Patents [OSTI]

    Wang, S.T.

    1994-11-01

    A wire cable assembly adapted for the winding of electrical coils is taught. A primary intended use is for use in particle tube assemblies for the Superconducting Super Collider. The correction coil cables have wires collected in wire array with a center rib sandwiched therebetween to form a core assembly. The core assembly is surrounded by an assembly housing having an inner spiral wrap and a counter wound outer spiral wrap. An alternate embodiment of the invention is rolled into a keystoned shape to improve radial alignment of the correction coil cable on a particle tube in a particle tube assembly. 7 figs.

  12. Dead-time Corrected Disdrometer Data

    DOE Data Explorer [Office of Scientific and Technical Information (OSTI)]

    Bartholomew, Mary Jane

    2008-03-05

    Original and dead-time corrected disdrometer results for observations made at SGP and TWP. The correction is based on the technique discussed in Sheppard and Joe, 1994. In addition, these files contain calculated radar reflectivity factor, mean Doppler velocity and attenuation for every measurement for both the original and dead-time corrected data at the following wavelengths: 0.316, 0.856, 3.2, 5, and 10cm (W,K,X,C,S bands). Pavlos Kollias provided the code to do these calculations.

  13. Sample results from the interim salt disposition program macrobatch 9 tank 21H qualification samples

    SciTech Connect (OSTI)

    Peters, T. B.

    2015-11-01

    Savannah River National Laboratory (SRNL) analyzed samples from Tank 21H in support of qualification of Macrobatch (Salt Batch) 9 for the Interim Salt Disposition Program (ISDP). This document reports characterization data on the samples of Tank 21H.

  14. Immobilized low-activity waste interim storage facility, Project W-465 conceptual design report

    SciTech Connect (OSTI)

    Pickett, W.W.

    1998-03-02

    This report outlines the design and total estimated cost to modify the four unused grout vaults for the remote handling and interim storage of immobilized low-activity waste (ILAW).

  15. DQO Summary Report for 105-N/109-N Interim Safe Storage Project Waste Characterization

    SciTech Connect (OSTI)

    T. A. Lee

    2005-09-15

    The DQO summary report provides the results of the DQO process completed for waste characterization activities for the 105-N/109-N Reactor Interim Safe Storage Project including decommission, deactivate, decontaminate, and demolish activities for six associated buildings.

  16. N Reactor Placed In Interim Safe Storage: Largest Hanford Reactor Cocooning Project Now Complete

    Broader source: Energy.gov [DOE]

    RICHLAND, WASH. – The U.S. Department of Energy’s (DOE’s) River Corridor contractor, Washington Closure Hanford, has completed placing N Reactor in interim safe storage, a process also known as “cocooning.”

  17. King County Metro Transit Hybrid Articulated Transit Buses: Interim Evaluation Results

    SciTech Connect (OSTI)

    Chandler, K.; Walkowicz, K.

    2006-04-01

    Interim technical report compares and evaluates new diesel and diesel hybrid-electric articulated buses operated as part of the King County Metro Transit (KC Metro) fleet in Seattle, Washington.

  18. New York City Transit Hybrid and CNG Transit Buses: Interim Evaluation Results

    Alternative Fuels and Advanced Vehicles Data Center [Office of Energy Efficiency and Renewable Energy (EERE)]

    New York City Transit Hybrid and CNG Transit Buses: Interim Evaluation Results K. Chandler and E. Eberts Battelle L. Eudy National Renewable Energy Laboratory Technical Report NREL/TP-540-38843 January 2006 New York City Transit Hybrid and CNG Transit Buses: Interim Evaluation Results K. Chandler and E. Eberts Battelle L. Eudy National Renewable Energy Laboratory Prepared under Task No. FC06.3000 Technical Report NREL/TP-540-38843 January 2006 National Renewable Energy Laboratory 1617 Cole

  19. Comments of NRDC on Department of Energy Interim Final Rule: Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Conservation for New Federal Commercial and Multi-Family High-Rise Residential Buildings and New Federal Low-Rise Residential Buildings | Department of Energy NRDC on Department of Energy Interim Final Rule: Energy Conservation for New Federal Commercial and Multi-Family High-Rise Residential Buildings and New Federal Low-Rise Residential Buildings Comments of NRDC on Department of Energy Interim Final Rule: Energy Conservation for New Federal Commercial and Multi-Family High-Rise

  20. Request for Rehearing and Request for Interim Clarification by David K.

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Paylor, Director of the Virginia Department of Environmental Quality | Department of Energy Rehearing and Request for Interim Clarification by David K. Paylor, Director of the Virginia Department of Environmental Quality Request for Rehearing and Request for Interim Clarification by David K. Paylor, Director of the Virginia Department of Environmental Quality Docket No. EO-05-01: Pursuant to Federal Power Act § 313, David K. Paylor, Director of the Virginia Department of Environmental

  1. Final Environmental Impact Statement Safe Interim Storage Of Hanford Tank Wastes

    Office of Environmental Management (EM)

    Summary-1995.html[6/27/2011 12:58:00 PM] FINAL ENVIRONMENTAL IMPACT STATEMENT SAFE INTERIM STORAGE OF HANFORD TANK WASTES SUMMARY The Safe Interim Storage of Hanford Tank Wastes Environmental Impact Statement has been prepared according to requirements of the National Environmental Policy Act and the Washington State Environmental Policy Act. In accordance with these Acts, a Draft Environmental Impact Statement was issued on August 5, 1994, (DOE 1994) and it was revised in response to public,

  2. Interim Report of the Task Force on DOE National Laboratories | Department

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    of Energy Interim Report of the Task Force on DOE National Laboratories Interim Report of the Task Force on DOE National Laboratories The SEAB Task Force on DOE National Laboratories was established by the Secretary of Energy on June 16, 2014, to provide advice, guidance, and recommendations on important issues related to improving the health and management of the labs. The Task Force has been charged to review past studies, Congressional reports and direction, and Departmental deliberations

  3. Environmental surveillance results for 1995 for the Hazelwood Interim Storage Site

    SciTech Connect (OSTI)

    McCague, J.C.

    1996-06-01

    This memorandum presents and interprets analytical results and measurements obtained as part of the 1995 environmental surveillance program for the Hazelwood Interim Storage Site (HISS) under the Formerly Utilized Sites Remedial Action Program (FUSRAP). The discussion provides a comparative analysis of average historical background conditions and applicable regulatory criteria to the 1995 results reported for external gamma radiation and for samples from the media investigated (air, surface water, sediment, groundwater, and stormwater). Results from the 1995 environmental surveillance program at HISS indicate that, with the exception of thorium-230 in streambed sediment, applicable US Department of Energy (DOE) guidelines were not exceeded for any measured parameter or for any dose calculated for potentially exposed members of the general public. In the absence of sediment guidelines, DOE soil guidelines serve as a standard of comparison for data obtained from stream bed sediment; two samples from downstream locations contained concentrations of thorium-230 that exceeded DOE soil guidelines. All stormwater sample results were in compliance with permit-specified limits. Other radioactive materials include radium 226 and natural uranium.

  4. Hazelwood Interim Storage Site environmental report for calendar year 1989, Hazelwood, Missouri

    SciTech Connect (OSTI)

    Not Available

    1990-05-01

    The environmental monitoring program, begun in 1984, was continued during 1989 at the Hazelwood Interim Storage Site (HISS), a US Department of Energy (DOE) facility located in the City of Hazelwood, Missouri. HISS is currently used for storage of soils contaminated with residual radioactive material. HISS is part of the Formerly Utilized Sites Remedial Action Program (FUSRAP), a DOE program to decontaminate or otherwise control sites where residual radioactive material remains from the early years of the nation's atomic energy program or from commercial operations causing conditions that Congress has authorized DOE to remedy. The monitoring program at HISS measures radon concentrations in air; external gamma radiation levels; and uranium, radium, and thorium concentrations in surface water, groundwater, and sediment. Additionally, several nonradiological parameters are measured in groundwater. To verify that the site is in compliance with the DOE radiation protection standard (100 mrem/yr) and assess its potential effect on public health, the radiation dose was calculated for a hypothetical maximally exposed individual. This report presents the findings of the environmental monitoring conducted at HISS during calendar year 1989. 19 refs., 14 figs., 13 tabs.

  5. National climate change action plans: Interim report for developing and transition countries

    SciTech Connect (OSTI)

    Benioff, R.; Ness, E.; Hirst, J.

    1997-10-01

    Under its Support for National Action Plans (SNAP) initiative, the U.S. Country Studies Program is providing financial and technical assistance to 18 countries for the development of climate change action plans. Although most of the countries have not yet completed their plans, the important lessons learned thus far are valuable and should be shared with other countries and international institutions that have an interest in the process of action plan development. This interim report describes the experience of 11 countries that are the furthest along in their planning activity and who have offered to share their results to date with the larger community of interested nations. These action plans delineate specific mitigation and adaptation measures that the countries will implement and integrate into their ongoing development programs. This report focuses on the measures the countries have selected and the methods they used to prepare their action plans. This executive summary presents key lessons and common themes using a structure similar to that used in the individual country chapters.

  6. Appendix VI Corrective Action Strategy

    National Nuclear Security Administration (NNSA)

    ......... 15 3.0 Underground Test Area............ 13 3-1 Underground Test Area Corrective Action ...

  7. Correction coil cable

    DOE Patents [OSTI]

    Wang, Sou-Tien

    1994-11-01

    A wire cable assembly (10, 310) adapted for the winding of electrical coils is taught. A primary intended use is for use in particle tube assemblies (532) for the superconducting super collider. The correction coil cables (10, 310) have wires (14, 314) collected in wire arrays (12, 312) with a center rib (16, 316) sandwiched therebetween to form a core assembly (18, 318 ). The core assembly (18, 318) is surrounded by an assembly housing (20, 320) having an inner spiral wrap (22, 322) and a counter wound outer spiral wrap (24, 324). An alternate embodiment (410) of the invention is rolled into a keystoned shape to improve radial alignment of the correction coil cable (410) on a particle tube (733) in a particle tube assembly (732).

  8. Finding of no significant impact. Consolidation and interim storage of special nuclear material at Rocky Flats Environmental Technology Site

    SciTech Connect (OSTI)

    1995-06-01

    The Department of Energy (DOE) has prepared an environmental assessment (EA), DOE/EA -- 1060, for the consolidation, processing, and interim storage of Category I and II special nuclear material (SNM) in Building 371 at the Rocky Flats Environmental Technology Site (hereinafter referred to as Rocky Flats or Site), Golden, Colorado. The scope of the EA included alternatives for interim storage including the no action alternative, the construction of a new facility for interim storage at Rocky Flats, and shipment to other DOE facilities for interim storage.

  9. Safe Advantage on Dry Interim Spent Nuclear Fuel Storage

    SciTech Connect (OSTI)

    Romanato, L.S.

    2008-07-01

    This paper aims to present the advantages of dry cask storage in comparison with the wet storage (cooling water pools) for SNF. When the nuclear fuel is removed from the core reactor, it is moved to a storage unit and it wait for a final destination. Generally, the spent nuclear fuel (SNF) remains inside water pools within the reactors facility for the radioactive activity decay. After some period of time in pools, SNF can be sent to a definitive deposition in a geological repository and handled as radioactive waste or to reprocessing facilities, or still, wait for a future solution. Meanwhile, SNF remains stored for a period of time in dry or wet facilities, depending on the method adopted by the nuclear power plant or other plans of the country. Interim storage, up to 20 years ago, was exclusively wet and if the nuclear facility had to be decommissioned another storage solution had to be found. At the present time, after a preliminary cooling of the SNF elements inside the water pool, the elements can be stored in dry facilities. This kind of storage does not need complex radiation monitoring and it is safer then wet one. Casks, either concrete or metallic, are safer, especially on occurrence of earthquakes, like that occurred at Kashiwazaki-Kariwa nuclear power plant, in Japan on July 16, 2007. (authors)

  10. Process safety management and interim or remedial action plans

    SciTech Connect (OSTI)

    Boss, M.J.; Henney, D.A.; Heitzman, V.K. [HWS Consulting Group, Inc., Omaha, NE (United States); Day, D.W. [Army Corps of Engineers, Omaha, NE (United States)

    1996-12-31

    Remedial Actions, including Interim Remedial Activities, often require the use of treatment facilities or stabilization techniques using on-site chemical processes. As such, the 29 CFR 1910.119 Process Safety Management (PSM) of Highly Hazardous Chemicals (PSM Standard) and the USEPA regulations for Risk Management Planning require that these chemicals and their attendant potential hazards be identified. A Hazard and Operation (HAZOP) study, Failure Mode and Effect Analysis (FMEA), Fault Tree Analysis, or equivalent graphic presentation of processes must be completed. These studies form a segment of the Process Hazard Analysis (PHA). HAZOP addresses each system and each element of a system that could deviate from normal operations and thus cause a hazard. A full assessment of each process is produced by looking at the hazards, consequences, causes and personnel protection needed. Many variables must be considered when choosing the appropriate PHA technique including the size of the plant, the number of processes, the types of processes, and the types of chemicals used. A mixture of these techniques may be required to adequately transmit information about the process being evaluated.

  11. Uranium exploration of the Colorado Plateau: interim staff report

    SciTech Connect (OSTI)

    Not Available

    1980-10-01

    This report is an issue of the original draft copy of the Interim Staff Report on Uranium Exploration on the Colorado Plateau, dated June 1951. The original draft copy was only recently located and is being published at this time because of the interest in the contained historical content. The table of contents of this report lists: history of uranium mining; geology; proposed program for the geologic investigations section; general activities of industry and government; and future exploration of sedimentary uranium deposits and anticipated results. Under the proposed program section are: future of the copper-uranium deposits as a source of uranium; uraniferous asphaltite deposits; and commission exploration and future possibilities. The section on general activities of industry and government includes: exploratory and development drilling; field investigations and mapping; early geologic investigations and investigations by the US geological survey; and geophysical exploration. Tables are also presented on: uranium production by districts; US Geological survey drilling statistics; Colorado Exploration Branch drilling statistics; summary of drilling projects; and comparative yearly core-drill statistics on the Colorado Plateau.

  12. Hazelwood Interim Storage Site annual environmental report for calendar year 1991, Hazelwood, Missouri

    SciTech Connect (OSTI)

    Not Available

    1992-09-01

    This document describes the environmental monitoring program at the Hazelwood Interim Storage Site (HISS) and surrounding area, implementation of the program, and monitoring results for 1991. Environmental monitoring of HISS began in 1984 when the site was assigned to the US Department of Energy (DOE) as part of the decontamination research and development project authorized by Congress under the 1984 Energy and Water Development Appropriations Act. DOE placed responsibility for HISS under the Formerly Utilized Sites Remedial Action Program (FUSRAP), a DOE program to decontaminate or otherwise control sites where residual radioactive materials remain from the early years of the nation`s atomic energy program or from commercial operations causing conditions that Congress has authorized DOE to remedy. The environmental monitoring program at HISS includes sampling networks for radon concentrations in air; external gamma radiation exposure; and radium-226, thorium-230, and total uranium concentrations in surface water, sediment, and groundwater. Additionally, several nonradiological parameters are measured in groundwater. Monitoring results are compared with applicable Environmental Protection Agency standards, DOE derived concentration guides (DCGs), dose limits, and other requirements in DOE orders. Environmental standards and DCGs are established to protect public health and the environment.

  13. Hazelwood interim storage site: Annual site environmental report, Hazelwood, Missouri, Calendar Year 1988

    SciTech Connect (OSTI)

    Not Available

    1989-04-01

    The monitoring program at Hazelwood Interim Storage Site (HISS) measures radon concentrations in air; external gamma radiation levels; and uranium, radium, and thorium, concentrations in surface water, groundwater and sediment. To verify that the site is in compliance with the DOE radiation protection standard (100 mrem/yr) and assess its potential effect or public health, the radiation dose was calculated for a hypothetical maximally exposed individual. Based on the scenario described in this report, this hypothetical individual at HISS would receive an annual external exposure approximately equivalent to 1 percent of the DOE radiation protection standard. This exposure is less than the exposure a person receives during a flight from New York to Los Angeles (because of the greater amounts of cosmic radiation at higher altitudes). The cumulative dose to the population within an 80-km (50-mi) radius of HISS that results from radioactive materials present at the site is indistinguishable from the dose that the same population receives from naturally occurring radioactive sources. The results of 1988 monitoring show that HISS is in compliance with the DOE radiation protection standard. 15 refs., 16 figs., 13 tabs.

  14. Safe interim storage of Hanford tank wastes, draft environmental impact statement, Hanford Site, Richland, Washington

    SciTech Connect (OSTI)

    Not Available

    1994-07-01

    This Draft EIS is prepared pursuant to the National Environmental Policy Act (NEPA) and the Washington State Environmental Policy Act (SEPA). DOE and Ecology have identified the need to resolve near-term tank safety issues associated with Watchlist tanks as identified pursuant to Public Law (P.L.) 101-510, Section 3137, ``Safety Measures for Waste Tanks at Hanford Nuclear Reservation,`` of the National Defense Authorization Act for Fiscal Year 1991, while continuing to provide safe storage for other Hanford wastes. This would be an interim action pending other actions that could be taken to convert waste to a more stable form based on decisions resulting from the Tank Waste Remediation System (TWRS) EIS. The purpose for this action is to resolve safety issues concerning the generation of unacceptable levels of hydrogen in two Watchlist tanks, 101-SY and 103-SY. Retrieving waste in dilute form from Tanks 101-SY and 103-SY, hydrogen-generating Watchlist double shell tanks (DSTs) in the 200 West Area, and storage in new tanks is the preferred alternative for resolution of the hydrogen safety issues.

  15. Measurement

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    magnetic fluctuation-induced particle flux "invited... a... W. X. Ding, D. L. Brower, and T. Y. Yates Department of Physics and Astronomy, University of California-Los Angeles, Los Angeles, California 90095, USA ͑Presented 13 May 2008; received 12 May 2008; accepted 16 May 2008; published online 31 October 2008͒ Magnetic field fluctuation-induced particle transport has been directly measured in the high-temperature core of the MST reversed field pinch plasma. Measurement of radial

  16. Interim site characterization report and ground-water monitoring program for the Hanford site solid waste landfill

    SciTech Connect (OSTI)

    Fruland, R.M.; Hagan, R.A.; Cline, C.S.; Bates, D.J.; Evans, J.C.; Aaberg, R.L.

    1989-07-01

    Federal and state regulations governing the operation of landfills require utilization of ground-water monitoring systems to determine whether or not landfill operations impact ground water at the point of compliance (ground water beneath the perimeter of the facility). A detection-level ground-water monitoring system was designed, installed, and initiated at the Hanford Site Solid Waste Landfill (SWL). Chlorinated hydrocarbons were detected at the beginning of the ground-water monitoring program and continue to be detected more than 1 year later. The most probable source of the chlorinated hydrocarbons is washwater discharged to the SWL between 1985 and 1987. This is an interim report and includes data from the characterization work that was performed during well installation in 1987, such as field observations, sediment studies, and geophysical logging results, and data from analyses of ground-water samples collected in 1987 and 1988, such as field parameter measurements and chemical analyses. 38 refs., 27 figs., 8 tabs.

  17. Radiation camera motion correction system

    DOE Patents [OSTI]

    Hoffer, P.B.

    1973-12-18

    The device determines the ratio of the intensity of radiation received by a radiation camera from two separate portions of the object. A correction signal is developed to maintain this ratio at a substantially constant value and this correction signal is combined with the camera signal to correct for object motion. (Official Gazette)

  18. Idaho Waste Vitrification Facilities Project Vitrified Waste Interim Storage Facility

    SciTech Connect (OSTI)

    Bonnema, Bruce Edward

    2001-09-01

    This feasibility study report presents a draft design of the Vitrified Waste Interim Storage Facility (VWISF), which is one of three subprojects of the Idaho Waste Vitrification Facilities (IWVF) project. The primary goal of the IWVF project is to design and construct a treatment process system that will vitrify the sodium-bearing waste (SBW) to a final waste form. The project will consist of three subprojects that include the Waste Collection Tanks Facility, the Waste Vitrification Facility (WVF), and the VWISF. The Waste Collection Tanks Facility will provide for waste collection, feed mixing, and surge storage for SBW and newly generated liquid waste from ongoing operations at the Idaho Nuclear Technology and Engineering Center. The WVF will contain the vitrification process that will mix the waste with glass-forming chemicals or frit and turn the waste into glass. The VWISF will provide a shielded storage facility for the glass until the waste can be disposed at either the Waste Isolation Pilot Plant as mixed transuranic waste or at the future national geological repository as high-level waste glass, pending the outcome of a Waste Incidental to Reprocessing determination, which is currently in progress. A secondary goal is to provide a facility that can be easily modified later to accommodate storage of the vitrified high-level waste calcine. The objective of this study was to determine the feasibility of the VWISF, which would be constructed in compliance with applicable federal, state, and local laws. This project supports the Department of Energys Environmental Management missions of safely storing and treating radioactive wastes as well as meeting Federal Facility Compliance commitments made to the State of Idaho.

  19. Immobilized High Level Waste (HLW) Interim Storage Alternative Generation and analysis and Decision Report 2nd Generation Implementing Architecture

    SciTech Connect (OSTI)

    CALMUS, R.B.

    2000-09-14

    Two alternative approaches were previously identified to provide second-generation interim storage of Immobilized High-Level Waste (IHLW). One approach was retrofit modification of the Fuel and Materials Examination Facility (FMEF) to accommodate IHLW. The results of the evaluation of the FMEF as the second-generation IHLW interim storage facility and subsequent decision process are provided in this document.

  20. Hazelwood Interim Storage Site: Annual site environment report, Calendar year 1985

    SciTech Connect (OSTI)

    Not Available

    1986-11-01

    The Hazelwood Interim Storage Site (HISS) is presently used for the storage of low-level radioactively contaminated soils. Monitoring results show that the HISS is in compliance with DOE Derived Concentration Guides (DCGs) and radiation protection standards. During 1985, annual average radon concentrations ranged from 10 to 23% of the DCG. The highest external dose rate at the HISS was 287 mrem/yr. The measured background dose rate for the HISS area is 99 mrem/yr. The highest average annual concentration of uranium in surface water monitored in the vicinity of the HISS was 0.7% of the DOE DCG; for /sup 226/Ra it was 0.3% of the applicable DCG, and for /sup 230/Th it was 1.7%. In groundwater, the highest annual average concentration of uranium was 12% of the DCG; for /sup 226/Ra it was 3.6% of the applicable DCG, and for /sup 230/Th it was 1.8%. While there are no concentration guides for stream sediments, the highest concentration of total uranium was 19 pCi/g, the highest concentration of /sup 226/Ra was 4 pCi/g, and the highest concentration of /sup 230/Th was 300 pCi/g. Radon concentrations, external gamma dose rates, and radionuclide concentrations in groundwater at the site were lower than those measured in 1984; radionuclide concentrations in surface water were roughly equivalent to 1984 levels. For sediments, a meaningful comparison with 1984 concentrations cannot be made since samples were obtained at only two locations and were only analyzed for /sup 230/Th. The calculated radiation dose to the maximally exposed individual at the HISS, considering several exposure pathways, was 5.4 mrem, which is 5% of the radiation protection standard.

  1. Measurement

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Neutrino Induced, Charged Current, Charged Pion Production by Michael Joseph Wilking B.Ch.E., University of Minnesota, 2001 M.S., University of Colorado, 2007 A thesis submitted to the Faculty of the Graduate School of the University of Colorado in partial fulfillment of the requirements for the degree of Doctor of Philosophy Department of Physics 2009 This thesis entitled: Measurement of Neutrino Induced, Charged Current, Charged Pion Production written by Michael Joseph Wilking has been

  2. Measurement

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    core velocity fluctuations and the dynamo in a reversed-field pinch * D. J. Den Hartog, †,a) J. T. Chapman, b) D. Craig, G. Fiksel, P. W. Fontana, S. C. Prager, and J. S. Sarff Department of Physics, University of Wisconsin-Madison, 1150 University Avenue, Madison, Wisconsin 53706 ͑Received 16 November 1998; accepted 20 January 1999͒ Plasma flow velocity fluctuations have been directly measured in the high-temperature magnetically confined plasma in the Madison Symmetric Torus ͑MST͒

  3. Measurement

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    1 H( 7 Be, 8 B)γ cross section by Ryan P. Fitzgerald A dissertation submitted to the faculty of the University of North Carolina at Chapel Hill in partial fulfillment of the requirements for the degree of Doctor of Philosophy in the Department of Physics & Astronomy. Chapel Hill 2005 Approved: A. E. Champagne, Advisor J. C. Blackmon, Reader C. Iliadis, Reader ABSTRACT Ryan P. Fitzgerald: Measurement of the 1 H( 7 Be, 8 B)γ cross section (Under the Direction of A. E. Champagne) The fusion

  4. Measurement

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    interpretation of micro benchmark and application energy use on the Cray XC30 Brian Austin, and Nicholas J. Wright ⇤ August 29, 2014 Abstract Understanding patterns of application energy use is key to reaching future HPC e ciency goals. We have measured the sensitivity of en- ergy use to CPU frequency for several microbenchmarks and applications on a Cray XC30. First order fits to the performance and power data are su cient to describe the energy used by these applications. Exam- ination of

  5. Measurement

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Electronegative Contaminants and Drift Electron Lifetime in the MicroBooNE Experiment The MicroBooNE Collaboration May 19, 2016 Abstract High-purity liquid argon is critical for the operation of a liquid argon time projec- tion chamber (LArTPC). At MicroBooNE, we have achieved an electron drift lifetime of at least 6 ms without evacuation of the detector vessel. Measurements of the elec- tronegative contaminants oxygen and water are described and shown as the gas and liquid argon stages of

  6. Corrective Action Investigation Plan for Corrective Action Unit...

    Office of Legacy Management (LM)

    ... Number Title Page 1-1 Process Flow Diagram for Underground Test Area Corrective Action ... NPDES National Pollutant Discharge Elimination System NTS Nevada Test Site pdf Probability ...

  7. Hazelwood Interim Storage Site annual site environmental report: Calendar year 1986

    SciTech Connect (OSTI)

    Not Available

    1987-06-01

    During 1986, the environmental monitoring program was continued at the Hazelwood Interim Storage Site (HISS), a US Department of Energy (DOE) facility located in the City of Hazelwood, Missouri. Originally known as the Cotter Corporation site on Latty Avenue in Hazelwood, the HISS is presently used for the storage of soils contaminated with residual radioactive material. As part of the decontamination research and development project authorized by Congress under the 1984 Energy and Water Appropriations Act, remedial action and environmental monitoring program are being conducted at the site and at vicinity properties by Bechtel National, Inc., Project Management Contractor for FUSRAP. The monitoring program at the HISS measures radon gas concentrations in air; external gamma radiation levels; and uranium, radium, and thorium concentrations in surface water, groundwater, and sediment. To verify that the site is in compliance with the DOE radiation protection standard (100 mrem/yr) and assess its potential effect on public health, the radiation dose was calculated for the maximally exposed individual. Based on the scenario described in this report, the maximally exposed individual at the HISS would receive an annual external exposure approximately equivalent to 2% of the DOE radiation protection standard of 100 mrem/yr. This exposure is less than the exposure a person would receive during a round-trip flight from New York to Los Angeles. The cumulative dose to the population within an 80-km (50-mi) radius of the HISS that would result from radioactive materials present at the site would be indistinguishable from the dose that the same population would receive from naturally occurring radioactive sources. Results of the 1986 monitoring show that the HISS is in compliance with the DOE radiation protection standard. 11 refs., 6 figs., 10 tabs.

  8. Evaluation of 2004 Toyota Prius Hybrid Electic Drive System Interim Report - Revised

    SciTech Connect (OSTI)

    Ayers, C.W.; Hsu, J.S.; Marlino, L.D.; Miller, C.W.; Ott, G.W., Jr.; Oland, C.B.; Burress, T.A.

    2007-07-31

    The 2004 Toyota Prius is a hybrid automobile equipped with a gasoline engine and a battery-powered electric motor. Both of these motive power sources are capable of providing mechanical drive power for the vehicle. The engine can deliver a peak power output of 57 kilowatts (kW) at 5000 revolutions per minute (rpm) while the motor can deliver a peak power output of 50 kW at 1300 rpm. Together, this engine-motor combination has a specified peak power output of 82 kW at a vehicle speed of 85 kilometers per hour (km/h). In operation, the 2004 Prius exhibits superior fuel economy compared to conventionally powered automobiles. Laboratory tests were conducted to evaluate the electrical and mechanical performance of the 2004 Toyota Prius and its hybrid electric drive system. As a hybrid vehicle, the 2004 Prius uses both a gasoline-powered internal combustion engine and a battery-powered electric motor as motive power sources. Innovative algorithms for combining these two power sources results in improved fuel efficiency and reduced emissions compared to traditional automobiles. Initial objectives of the laboratory tests were to measure motor and generator back-electromotive force (emf) voltages and determine gearbox-related power losses over a specified range of shaft speeds and lubricating oil temperatures. Follow-on work will involve additional performance testing of the motor, generator, and inverter. Information contained in this interim report summarizes the test results obtained to date, describes preliminary conclusions and findings, and identifies additional areas for further study.

  9. Corrective Action Decision Document/Corrective Action Plan for Corrective Action Unit 447: Project Shoal Area, Subsurface, Nevada, Rev. No.: 3 with Errata Sheet

    SciTech Connect (OSTI)

    Tim Echelard

    2006-03-01

    This Corrective Action Decision Document/Corrective Action Plan (CADD/CAP) has been prepared for Corrective Action Unit (CAU) 447, Project Shoal Area (PSA)-Subsurface, Nevada, in accordance with the ''Federal Facility Agreement and Consent Order'' (FFACO) (1996). Corrective Action Unit 447 is located in the Sand Springs Mountains in Churchill County, Nevada, approximately 48 kilometers (30 miles) southeast of Fallon, Nevada. The CADD/CAP combines the decision document (CADD) with the Corrective Action Plan (CAP) and provides or references the specific information necessary to recommend corrective actions for CAU 447, as provided in the FFACO. Corrective Action Unit 447 consists of two corrective action sites (CASs): CAS 57-49-01, Emplacement Shaft, and CAS 57-57-001, Cavity. The emplacement shaft (CAS-57-49-01) was backfilled and plugged in 1996 and will not be evaluated further. The purpose of the CADD portion of the document (Section 1.0 to Section 4.0) is to identify and provide a rationale for the selection of a recommended corrective action alternative for the subsurface at PSA. To achieve this, the following tasks were required: (1) Develop corrective action objectives. (2) Identify corrective action alternative screening criteria. (3) Develop corrective action alternatives. (4) Perform detailed and comparative evaluations of the corrective action alternatives in relation to the corrective action objectives and screening criteria. (5) Recommend a preferred corrective action alternative for the subsurface at PSA. The original Corrective Action Investigation Plan (CAIP) for the PSA was approved in September 1996 and described a plan to drill and test four characterization wells, followed by flow and transport modeling (DOE/NV, 1996). The resultant drilling is described in a data report (DOE/NV, 1998e) and the data analysis and modeling in an interim modeling report (Pohll et al., 1998). After considering the results of the modeling effort, the U.S. Department

  10. Sample Results from the Interim Salt Disposition Program Macrobatch 6 Tank 21H Qualification Samples

    SciTech Connect (OSTI)

    Peters, T. B.; Fink, S. D.

    2012-12-11

    Savannah River National Laboratory (SRNL) analyzed samples from Tank 21H in support of qualification of Macrobatch (Salt Batch) 6 for the Interim Salt Disposition Project (ISDP). This document reports partial results of the analyses of samples of Tank 21H. No issues with the projected Salt Batch 6 strategy are identified.

  11. Sample Results From The Interim Salt Disposition Program Macrobatch 6 Tank 21H Qualification Samples

    SciTech Connect (OSTI)

    Peters, T. B.; Fink, S. D.

    2012-12-20

    Savannah River National Laboratory (SRNL) analyzed samples from Tank 21H in support of qualification of Macrobatch (Salt Batch) 6 for the Interim Salt Disposition Project (ISDP). This document reports partial results of the analyses of samples of Tank 21H. No issues with the projected Salt Batch 6 strategy are identified.

  12. Evaluation of Hose in Hose Transfer Line Service Life for Hanford's Interim Stabilization Program

    SciTech Connect (OSTI)

    TORRES, T.D.

    2000-08-24

    RPP-6153, Engineering Task Plan for Hose-in-Hose Transfer System for the Interim Stabilization Program, defines the programmatic goals, functional requirements, and technical criteria for the development and subsequent installation of transfer line equipment to support Hanford's Interim Stabilization Program. RPP-6028, Specification for Hose in Hose Transfer Lines for Hanford's Interim Stabilization Program, has been issued to define the specific requirements for the design, manufacture, and verification of transfer line assemblies for specific waste transfer applications. Included in RPP-6028 are tables defining the chemical constituents of concern to which transfer lines will be exposed. Current Interim Stabilization Program planning forecasts that the at-grade transfer lines will be required to convey pumpable waste for as much as three years after commissioning. Prudent engineering dictates that the equipment placed in service have a working life in excess of this forecasted time period, with some margin to allow for future adjustments to the planned schedule. This document evaluates the effective service life of the Hose-in-Hose Transfer Lines, based on information submitted by the manufacturer and published literature. The effective service life of transfer line assemblies is a function of several factors. Foremost among these are process fluid characteristics, ambient environmental conditions, and the manufacturer's stated shelf life. This evaluation examines the manufacturer's certification of shelf life, the manufacturer's certifications of chemical compatibility with waste, and published literature on the effects of exposure to ionizing radiation on the mechanical properties of elastomeric materials to evaluate transfer line service life.

  13. Barometric and Earth Tide Correction

    Energy Science and Technology Software Center (OSTI)

    2005-11-10

    BETCO corrects for barometric and earth tide effects in long-term water level records. A regression deconvolution method is used ot solve a series of linear equations to determine an impulse response function for the well pressure head. Using the response function, a pressure head correction is calculated and applied.

  14. Annex D-200 Area Interim Storage Area Final Safety Analysis Report [FSAR] [Section 1 & 2

    SciTech Connect (OSTI)

    CARRELL, R D

    2002-07-16

    The 200 Area Interim Storage Area (200 Area ISA) at the Hanford Site provides for the interim storage of non-defense reactor spent nuclear fuel (SNF) housed in aboveground dry cask storage systems. The 200 Area ISA is a relatively simple facility consisting of a boundary fence with gates, perimeter lighting, and concrete and gravel pads on which to place the dry storage casks. The fence supports safeguards and security and establishes a radiation protection buffer zone. The 200 Area ISA is nominally 200,000 ft{sup 2} and is located west of the Canister Storage Building (CSB). Interim storage at the 200 Area ISA is intended for a period of up to 40 years until the materials are shipped off-site to a disposal facility. This Final Safety Analysis Report (FSAR) does not address removal from storage or shipment from the 200 Area ISA. Three different SNF types contained in three different dry cask storage systems are to be stored at the 200 Area ISA, as follows: (1) Fast Flux Test Facility Fuel--Fifty-three interim storage casks (ISC), each holding a core component container (CCC), will be used to store the Fast Flux Test Facility (FFTF) SNF currently in the 400 Area. (2) Neutron Radiography Facility (NRF) TRIGA'--One Rad-Vault' container will store two DOT-6M3 containers and six NRF TRIGA casks currently stored in the 400 Area. (3) Commercial Light Water Reactor Fuel--Six International Standards Organization (ISO) containers, each holding a NAC-I cask4 with an inner commercial light water reactor (LWR) canister, will be used for commercial LWR SNF from the 300 Area. An aboveground dry cask storage location is necessary for the spent fuel because the current storage facilities are being shut down and deactivated. The spent fuel is being transferred to interim storage because there is no permanent repository storage currently available.

  15. T Tank Farm Interim Surface Barrier Demonstration - Vadose Zone Monitoring FY09 Report

    SciTech Connect (OSTI)

    Zhang, Z. F.; Strickland, Christopher E.; Field, Jim G.; Parker, Danny L.

    2010-01-01

    DOEs Office of River Protection constructed a temporary surface barrier over a portion of the T Tank Farm as part of the T Farm Interim Surface Barrier Demonstration Project. As part of the demonstration effort, vadose zone moisture is being monitored to assess the effectiveness of the barrier at reducing soil moisture. A solar-powered system was installed to continuously monitor soil water conditions at four locations (i.e., instrument Nests A, B, C, and D) beneath the barrier and outside the barrier footprint as well as site meteorological conditions. Nest A is placed in the area outside the barrier footprint and serves as a control, providing subsurface conditions outside the influence of the surface barrier. Nest B provides subsurface measurements to assess surface-barrier edge effects. Nests C and D are used to assess changes in soil-moisture conditions beneath the interim surface barrier. Each instrument nest is composed of a capacitance probe (CP) with multiple sensors, multiple heat-dissipation units (HDUs), and a neutron probe (NP) access tube. The monitoring results in FY09 are summarized below. The solar panels functioned normally and could provide sufficient power to the instruments. The CP in Nest C after September 20, 2009, was not functional. The CP sensors in Nest B after July 13 and the 0.9-m CP sensor in Nest D before June 10 gave noisy data. Other CPs were functional normally. All the HDUs were functional normally but some pressure-head values measured by HDUs were greater than the upper measurement-limit. The higher-than-upper-limit values might be due to the very wet soil condition and/or measurement error but do not imply the malfunction of the sensors. Similar to FY07 and FY08, in FY09, the soil under natural conditions (Nest A) was generally recharged during the winter period (October-March) and discharged during the summer period (April-September). Soil water conditions above about 1.5-m to 2-m depth from all three types of measurements (i

  16. RCRA corrective action: Work plans

    SciTech Connect (OSTI)

    Not Available

    1995-02-01

    This Information Brief describes the work plans that owners/operators may have to prepare in conjunction with the performance of corrective action for compliance with RCRA guidelines. In general, the more complicated the performance of corrective action appears from the remedial investigation and other analyses, the more likely it is that the regulator will impose work plan requirements. In any case, most owner/operators will prepare work plans in conjunction with the performance of corrective action processes as a matter of best engineering management practices.

  17. Caustic-Side Solvent-Extraction Modeling for Hanford Interim Pretreatment System

    SciTech Connect (OSTI)

    Moyer, B.A.; Birdwell, J.F.; Delmau, L. H.; McFarlane, J.

    2008-06-01

    The purpose of this work is to examine the applicability of the Caustic-Side Solvent Extraction (CSSX) process for the removal of cesium from Hanford tank-waste supernatant solutions in support of the Hanford Interim Pretreatment System (IPS). The Hanford waste types are more challenging than those at the Savannah River Site (SRS) in that they contain significantly higher levels of potassium, the chief competing ion in the extraction of cesium. It was confirmed by use of the CSSX model that the higher levels of potassium depress the cesium distribution ratio (DCs), as validated by measurement of DCs values for four of eight specified Hanford waste-simulant compositions. The model predictions were good to an apparent standard error of 11%. It is concluded from batch distribution experiments, physical-property measurements, equilibrium modeling, flowsheet calculations, and contactor sizing that the CSSX process as currently employed for cesium removal from alkaline salt waste at the SRS is capable of treating similar Hanford tank feeds. For the most challenging waste composition, 41 stages would be required to provide a cesium decontamination factor (DF) of 5000 and a concentration factor (CF) of 5. Commercial contacting equipment with rotor diameters of 10 in. for extraction and 5 in. for stripping should have the capacity to meet throughput requirements, but testing will be required to confirm that the needed efficiency and hydraulic performance are actually obtainable. Markedly improved flowsheet performance was calculated for a new solvent formulation employing the more soluble cesium extractant BEHBCalixC6 used with alternative scrub and strip solutions, respectively 0.1 M NaOH and 10 mM boric acid. The improved system can meet minimum requirements (DF = 5000 and CF = 5) with 17 stages or more ambitious goals (DF = 40,000 and CF = 15) with 19 stages. Potential benefits of further research and development are identified that would lead to reduced costs, greater

  18. Method for correcting imperfections on a surface

    DOE Patents [OSTI]

    Sweatt, William C.; Weed, John W.

    1999-09-07

    A process for producing near perfect optical surfaces. A previously polished optical surface is measured to determine its deviations from the desired perfect surface. A multi-aperture mask is designed based on this measurement and fabricated such that deposition through the mask will correct the deviations in the surface to an acceptable level. Various mask geometries can be used: variable individual aperture sizes using a fixed grid for the apertures or fixed aperture sizes using a variable aperture spacing. The imperfections are filled in using a vacuum deposition process with a very thin thickness of material such as silicon monoxide to produce an amorphous surface that bonds well to a glass substrate.

  19. Letter on the Interim Report of the Commission to Review the Effectiveness of the National Energy Laboratories

    Broader source: Energy.gov [DOE]

    SEAB's comments on the findings and recommendations in the interim report of the Congressionally mandated Commission to Review the Effectiveness of the National Energy Laboratories, chaired by T.J. Glauthier and Jared Cohon.

  20. Memorandum on the Interim Report of the Commission to Review the Effectiveness of the National Energy Laboratories

    Broader source: Energy.gov [DOE]

    SEAB's comments on the findings and recommendations in the interim report of the Congressionally mandated Commission to Review the Effectiveness of the National Energy Laboratories, chaired by T.J. Glauthier and Jared Cohon.

  1. Entropic corrections to Einstein equations

    SciTech Connect (OSTI)

    Hendi, S. H. [Physics Department, College of Sciences, Yasouj University, Yasouj 75914 (Iran, Islamic Republic of); Research Institute for Astronomy and Astrophysics of Maragha (RIAAM), Maragha (Iran, Islamic Republic of); Sheykhi, A. [Research Institute for Astronomy and Astrophysics of Maragha (RIAAM), Maragha (Iran, Islamic Republic of); Department of Physics, Shahid Bahonar University, P.O. Box 76175-132, Kerman (Iran, Islamic Republic of)

    2011-04-15

    Considering the general quantum corrections to the area law of black hole entropy and adopting the viewpoint that gravity interprets as an entropic force, we derive the modified forms of Modified Newtonian dynamics (MOND) theory of gravitation and Einstein field equations. As two special cases we study the logarithmic and power-law corrections to entropy and find the explicit form of the obtained modified equations.

  2. Report on the performance monitoring system for the interim waste containment at the Niagara Falls Storage Site, Lewiston, New York

    SciTech Connect (OSTI)

    Not Available

    1985-10-01

    The Niagara Falls Storage Site (NFSS) is an interim storage site for low-level radioactive waste, established by the US Department of Energy (DOE) at Lewiston, New York. The waste containment structure for encapsulating low-level radioactive waste at the NFSS has been designed to minimize infiltration of rainfall, prevent pollution of groundwater, preclude formation of leachate, and prevent radon emanation. Accurately determining the performance of the main engineered elements of the containment structure will be important in establishing confidence in the ability of the structure to retain the wastes. For this purpose, a waste containment performance monitoring system has been developed to verify that these elements are functioning as intended. The key objective of the performance monitoring system is the early detection of trends that could be indicative of weaknesses developing in the containment structure so that corrective action can be taken before the integrity of the structure is compromised. Consequently, subsurface as well as surface monitoring techniques will be used. After evaluating several types of subsurface instrumentation, it was determined that vibrating wire pressure transducers, in combination with surface monitoring techniques, would satisfactorily monitor the parameters of concern, such as water accumulation inside the containment facility, waste settlement, and shrinkage of the clay cover. Surface monitoring will consist of topographic surveys based on predetermined gridlines, walkover surveys, and aerial photography to detect vegetative stress or other changes not evident at ground level. This report details the objectives of the performance monitoring system, identifies the elements of the containment design whose performance will be monitored, describes the monitoring system recommended, and outlines the costs associated with the monitoring system. 5 refs., 4 figs., 3 tabs.

  3. Weather-Corrected Performance Ratio

    SciTech Connect (OSTI)

    Dierauf, T.; Growitz, A.; Kurtz, S.; Cruz, J. L. B.; Riley, E.; Hansen, C.

    2013-04-01

    Photovoltaic (PV) system performance depends on both the quality of the system and the weather. One simple way to communicate the system performance is to use the performance ratio (PR): the ratio of the electricity generated to the electricity that would have been generated if the plant consistently converted sunlight to electricity at the level expected from the DC nameplate rating. The annual system yield for flat-plate PV systems is estimated by the product of the annual insolation in the plane of the array, the nameplate rating of the system, and the PR, which provides an attractive way to estimate expected annual system yield. Unfortunately, the PR is, again, a function of both the PV system efficiency and the weather. If the PR is measured during the winter or during the summer, substantially different values may be obtained, making this metric insufficient to use as the basis for a performance guarantee when precise confidence intervals are required. This technical report defines a way to modify the PR calculation to neutralize biases that may be introduced by variations in the weather, while still reporting a PR that reflects the annual PR at that site given the project design and the project weather file. This resulting weather-corrected PR gives more consistent results throughout the year, enabling its use as a metric for performance guarantees while still retaining the familiarity this metric brings to the industry and the value of its use in predicting actual annual system yield. A testing protocol is also presented to illustrate the use of this new metric with the intent of providing a reference starting point for contractual content.

  4. Spectral and temperature correction of silicon photovoltaic solar radiation detectors

    SciTech Connect (OSTI)

    Michalsky, J.J.; Perez, R.; Harrison, L. ); LeBaron, B.A. )

    1991-01-01

    Silicon photovoltaic sensors are an inexpensive alternative to standard thermopile sensors for the measurement of solar radiation. However, their temperature and spectral response render them less accurate for global horizontal irradiance and unsuitable for direct beam and diffuse horizontal irradiance unless they can be reliably corrected. A correction procedure for the rotating shadowband radiometer, which measures all three components, based on a three-way parameterization of the solar position and sky conditions is proposed. After correction, root-mean-square errors for the global and diffuse horizontal irradiance and the direct normal irradiance are about 10, 12, and 13 W/m{sup 2} in comparison with coincident, 5-minute thermopile measurements. While the numerical results are specific to the rotating shadowband instrument, the correction algorithm should apply universally.

  5. Proposed decision document, other contamination sources, interim response action, South Tank Farm Plume

    SciTech Connect (OSTI)

    Not Available

    1990-08-23

    The South Tank Farm Plume (STFP) is listed under the 'Remediation of Other Contamination Sources' Interim Response Action (IRA) sites under the Final Technical Program Plan FY88-FY92 and the Federal Facility Agreement. The process and guidelines used to assess alternatives, produce this Proposed Decision Document, and implement this IRA are specified in and conducted in accordance with the Federal Facility Agreement. The purposes of the Proposed Decision Document for Other Contamination Sources IRAs are to: (a) state the objective of the IRA; (b) discuss Interim Response Action alternatives, if any, that were considered; (c) provide the rationale for the alternative selected; (d) present the final ARAR decision; (e) summarize the significant comments received regarding the IRA and responses to those comments; and (f) establish an IRA Deadline for completion of the IRA, if appropriate. Each of the above mentioned issues is addressed in this document.

  6. Criticality safety evaluation for long term storage of FFTF fuel in interim storage casks

    SciTech Connect (OSTI)

    Richard, R.F.

    1995-05-11

    It has been postulated that a degradation phenomenon, referred to as ``hot cell rot``, may affect irradiated FFTF mixed plutonium-uranium oxide (MOX) fuel during dry interim storage. ``Hot cell rot`` refers to a variety of phenomena that degrade fuel pin cladding during exposure to air and inert gas environments. It is thought to be a form of caustic stress corrosion cracking or environmentally assisted cracking. Here, a criticality safety analysis was performed to address the effect of the ``hot cell rot`` phenomenon on the long term storage of irradiated FFTF fuel in core component containers. The results show that seven FFTF fuel assemblies or six Ident-69 pin containers stored in core component containers within interim storage casks will remain safely subcritical.

  7. The Time Needed to Implement the Blue Ribbon Commission Recommendation on Interim Storage - 13124

    SciTech Connect (OSTI)

    Voegele, Michael D.; Vieth, Donald

    2013-07-01

    The report of the Blue Ribbon Commission on America's Nuclear Future [1] makes a number of important recommendations to be considered if Congress elects to redirect U.S. high-level radioactive waste disposal policy. Setting aside for the purposes of this discussion any issues related to political forces leading to stopping progress on the Yucca Mountain project and driving the creation of the Commission, an important recommendation of the Commission was to institute prompt efforts to develop one or more consolidated storage facilities. The Blue Ribbon Commission noted that this recommended strategy for future storage and disposal facilities and operations should be implemented regardless of what happens with Yucca Mountain. It is too easy, however, to focus on interim storage as an alternative to geologic disposal. The Blue Ribbon Commission report does not go far enough in addressing the magnitude of the contentious problems associated with reopening the issues of relative authorities of the states and federal government with which Congress wrestled in crafting the Nuclear Waste Policy Act [2]. The Blue Ribbon Commission recommendation for prompt adoption of an interim storage program does not appear to be fully informed about the actions that must be taken, the relative cost of the effort, or the realistic time line that would be involved. In essence, the recommendation leaves to others the details of the systems engineering analyses needed to understand the nature and details of all the operations required to reach an operational interim storage facility without derailing forever the true end goal of geologic disposal. The material presented identifies a number of impediments that must be overcome before the country could develop a centralized federal interim storage facility. In summary, and in the order presented, they are: 1. Change the law, HJR 87, PL 107-200, designating Yucca Mountain for the development of a repository. 2. Bring new nuclear waste

  8. FedEx Gasoline Hybrid Electric Delivery Truck Evaluation: 6-Month Interim Report

    SciTech Connect (OSTI)

    Barnitt, R.

    2010-05-01

    This interim report presents partial (six months) results for a technology evaluation of gasoline hybrid electric parcel delivery trucks operated by FedEx in and around Los Angeles, CA. A 12 month in-use technology evaluation comparing in-use fuel economy and maintenance costs of GHEVs and comparative diesel parcel delivery trucks was started in April 2009. Comparison data was collected and analyzed for in-use fuel economy and fuel costs, maintenance costs, total operating costs, and vehicle uptime. In addition, this interim report presents results of parcel delivery drive cycle collection and analysis activities as well as emissions and fuel economy results of chassis dynamometer testing of a gHEV and a comparative diesel truck at the National Renewable Energy Laboratory's (NREL) ReFUEL laboratory. A final report will be issued when 12 months of in-use data have been collected and analyzed.

  9. Microsoft Word - SEAB Lab Task Force Interim Report Final.docx

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    of the Secretary of Energy Task Force on DOE National Laboratories June 17, 2015 This page intentionally left blank 1 EXECUTIVE SUMMARY This interim report of the Secretary of Energy Advisory Board (SEAB) National Laboratory Task Force (TF) identifies the constraints on and evaluates the effectiveness of laboratory operations that impact the performance and efficiency of the DOE national laboratories. The TF stresses the overriding importance of two actions: clarifying the authorities and

  10. Operations and Maintenance Concept Plan for the Immobilized High Level Waste (IHLW) Interim Storage Facility

    SciTech Connect (OSTI)

    JANIN, L.F.

    2000-08-30

    This O&M Concept looks at the future operations and maintenance of the IHLW/CSB interim storage facility. It defines the overall strategy, objectives, and functional requirements for the portion of the building to be utilized by Project W-464. The concept supports the tasks of safety basis planning, risk mitigation, alternative analysis, decision making, etc. and will be updated as required to support the evolving design.

  11. Decision document for the sanitary sewer system interim response action at Rocky Mountain Arsenal. Final report

    SciTech Connect (OSTI)

    Not Available

    1989-03-01

    The Interim Response Action (IRA) for the Sanitary Sewer System at the Rocky Mountain Arsenal (RMA) is being conducted as part of the IRA process for RMA in accordance with the June 5, 1987 report to the court in United States v. Shell Oil Co. and the proposed modified Consent Decree. This IRA project will consist of 'remediation of certain priority portions of the sanitary sewer to minimize the potential pathway of contaminant flow' (para 9.1(j), Consent Decree, 1988).

  12. Preliminary engineering design package for the north boundary system improvements interim response action

    SciTech Connect (OSTI)

    1989-08-01

    This interim response action consists of the design and construction of improvements to the North Boundary Containment System. The purpose of this document is to outline the main elements developed in the preliminary design phase of the IRA. The following elements of the IRA are discussed: (1) recharge trenches; (2) well closure; (3) design flow rate; (4) existing ground water treatment process; (5) treatment system modifications; (6) additional carbon storage; (7) Building modifications; and (8) treatment plant operational improvements.

  13. Preparation of Documented Safety Analysis for Interim Operations at DOE Nuclear Facilities

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    3011-2016 January 2016 DOE STANDARD PREPARATION OF DOCUMENTED SAFETY ANALYSIS FOR INTERIM OPERATIONS AT DOE NUCLEAR FACILITIES U.S. Department of Energy AREA SAFT Washington, DC 20585 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited. DOE-STD-3011-2016 ii FOREWORD 1. This Department of Energy (DOE) Standard (STD) has been approved to be used by DOE, including the National Nuclear Security Administration, and their contractors. 2. Beneficial comments

  14. Report on interim storage of spent nuclear fuel. Midwestern high-level radioactive waste transportation project

    SciTech Connect (OSTI)

    Not Available

    1993-04-01

    The report on interim storage of spent nuclear fuel discusses the technical, regulatory, and economic aspects of spent-fuel storage at nuclear reactors. The report is intended to provide legislators state officials and citizens in the Midwest with information on spent-fuel inventories, current and projected additional storage requirements, licensing, storage technologies, and actions taken by various utilities in the Midwest to augment their capacity to store spent nuclear fuel on site.

  15. Microsoft Word - Interim Work Authorization Form rev 2-9.doc

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    rev. 2/9/05 * Submit original form to M. Montalvo, MS 69, promptly on completion of work. INTERIM Work Authorization Process for Activities by Non-SSRL Workers at SSRL This Work Authorization Process applies to all maintenance, repair, and installation work performed at SSRL by non-SSRL workers. All work must be initiated by a technically qualified SSRL staff person (e.g. accelerator system manager, shop manager, facilities staff member, beam line engineer, etc.) who will serve as the

  16. Interim Status Report for Risk Management for SFRs

    SciTech Connect (OSTI)

    Jankovsky, Zachary Kyle; Denman, Matthew R.; Groth, Katrina; Wheeler, Timothy A.

    2015-10-01

    Accident management is an important component to maintaining risk at acceptable levels for all complex systems, such as nuclear power plants. With the introduction of passive, or inherently safe, reactor designs the focus has shifted from management by operators to allowing the system's design to take advantage of natural phenomena to manage the accident. Inherently and passively safe designs are laudable, but nonetheless extreme boundary conditions can interfere with the design attributes which facilitate inherent safety, thus resulting in unanticipated and undesirable end states. This report examines an inherently safe and small sodium fast reactor experiencing a variety of beyond design basis events with the intent of exploring the utility of a Dynamic Bayesian Network to infer the state of the reactor to inform the operator's corrective actions. These inferences also serve to identify the instruments most critical to informing an operator's actions as candidates for hardening against radiation and other extreme environmental conditions that may exist in an accident. This reduction in uncertainty serves to inform ongoing discussions of how small sodium reactors would be licensed and may serve to reduce regulatory risk and cost for such reactors.

  17. Lessons learned from the Siting Process of an Interim Storage Facility in Spain - 12024

    SciTech Connect (OSTI)

    Lamolla, Meritxell Martell

    2012-07-01

    On 29 December 2009, the Spanish government launched a site selection process to host a centralised interim storage facility for spent fuel and high-level radioactive waste. It was an unprecedented call for voluntarism among Spanish municipalities to site a controversial facility. Two nuclear municipalities, amongst a total of thirteen municipalities from five different regions, presented their candidatures to host the facility in their territories. For two years the government did not make a decision. Only in November 30, 2011, the new government elected on 20 November 2011 officially selected a non-nuclear municipality, Villar de Canas, for hosting this facility. This paper focuses on analysing the factors facilitating and hindering the siting of controversial facilities, in particular the interim storage facility in Spain. It demonstrates that involving all stakeholders in the decision-making process should not be underestimated. In the case of Spain, all regional governments where there were candidate municipalities willing to host the centralised interim storage facility, publicly opposed to the siting of the facility. (author)

  18. Low-level waste management program and interim waste operations technologies

    SciTech Connect (OSTI)

    Mezga, L.J.

    1983-01-01

    The Department of Energy currently supports an integrated technology development and transfer program aimed at ensuring that the technology necessary for the safe management and disposal of LLW by the commercial and defense sectors is available. The program focuses on five technical areas: (1) corrective measures technology, (2) improved shallow land burial technology, (3) greater confinement disposal technology, (4) model development and validation, and (5) treatment methods for problem wastes. The results of activities in these areas are reported in the open literature and the Proceedings of the LLWMP Annual Participants Information Meeting.

  19. Litchfield Correctional Center District Heating Low Temperature...

    Open Energy Info (EERE)

    Litchfield Correctional Center District Heating Low Temperature Geothermal Facility Jump to: navigation, search Name Litchfield Correctional Center District Heating Low Temperature...

  20. Re: Corrected Memorandum Summarizing Ex Parte Communication

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    via email) Re: Corrected Memorandum Summarizing Ex Parte Communication This memorandum is submitted to revise and correct our earlier memorandum submitted on September 23 rd . ...

  1. A background correction algorithm for Van Allen Probes MagEIS...

    Office of Scientific and Technical Information (OSTI)

    Title: A background correction algorithm for Van Allen Probes MagEIS electron flux measurements We describe an automated computer algorithm designed to remove background ...

  2. Diesel Emission Control -- Sulfur Effects (DECSE) Program; Phase I Interim Date Report No. 3: Diesel Fuel Sulfur Effects on Particulate Matter Emissions

    SciTech Connect (OSTI)

    DOE; ORNL; NREL; EMA; MECA

    1999-11-15

    The Diesel Emission Control-Sulfur Effects (DECSE) is a joint government/industry program to determine the impact of diesel fuel sulfur levels on emission control systems whose use could lower emissions of nitrogen oxides (NO{sub x}) and particulate matter (PM) from on-highway trucks in the 2002--2004 model years. Phase 1 of the program was developed with the following objectives in mind: (1) evaluate the effects of varying the level of sulfur content in the fuel on the emission reduction performance of four emission control technologies; and (2) measure and compare the effects of up to 250 hours of aging on selected devices for multiple levels of fuel sulfur content. This interim report covers the effects of diesel fuel sulfur level on particulate matter emissions for four technologies.

  3. T-TY Tank Farm Interim Surface Barrier Demonstration—Vadose Zone Monitoring Plan

    SciTech Connect (OSTI)

    Zhang, Z. F.; Strickland, Christopher E.; Field, Jim G.; Parker, Danny L.

    2010-09-27

    The Hanford Site has 149 underground single-shell tanks that store hazardous radioactive waste. Many of these tanks and their associated infrastructure (e.g., pipelines, diversion boxes) have leaked. Some of the leaked waste has entered the groundwater. The largest known leak occurred from the T-106 Tank of the 241-T Tank Farm in 1973. Five tanks are assumed to have leaked in the TY Farm. Many of the contaminants from those leaks still reside within the vadose zone within the T and TY Tank Farms. The Department of Energy’s Office of River Protection seeks to minimize the movement of these contaminant plumes by placing interim barriers on the ground surface. Such barriers are expected to prevent infiltrating water from reaching the plumes and moving them further. The soil water regime is monitored to determine the effectiveness of the interim surface barriers. Soil-water content and water pressure are monitored using off-the-shelf equipment that can be installed by the hydraulic hammer technique. Four instrument nests were installed in the T Farm in fiscal year (FY) 2006 and FY2007; two nests were installed in the TY Farm in FY2010. Each instrument nest contains a neutron probe access tube, a capacitance probe, and four heat-dissipation units. A meteorological station has been installed at the north side of the fence of the T Farm. This document summarizes the monitoring methods, the instrument calibration and installation, and the vadose zone monitoring plan for interim barriers in T farm and TY Farm.

  4. Emulytics for Cyber-Enabled Physical Attack Scenarios: Interim LDRD Report of Year One Results.

    SciTech Connect (OSTI)

    Clem, John; Urias, Vincent; Atkins, William Dee; Symonds, Christopher J.

    2015-12-08

    Sandia National Laboratories has funded the research and development of a new capability to interactively explore the effects of cyber exploits on the performance of physical protection systems. This informal, interim report of progress summarizes the project’s basis and year one (of two) accomplishments. It includes descriptions of confirmed cyber exploits against a representative testbed protection system and details the development of an emulytics capability to support live, virtual, and constructive experiments. This work will support stakeholders to better engineer, operate, and maintain reliable protection systems.

  5. Operable Unit 3: Proposed Plan/Environmental Assessment for interim remedial action

    SciTech Connect (OSTI)

    Not Available

    1993-12-01

    This document presents a Proposed Plan and an Environmental Assessment for an interim remedial action to be undertaken by the US Department of Energy (DOE) within Operable Unit 3 (OU3) at the Fernald Environmental Management Project (FEMP). This proposed plan provides site background information, describes the remedial alternatives being considered, presents a comparative evaluation of the alternatives and a rationnale for the identification of DOE`s preferred alternative, evaluates the potential environmental and public health effects associated with the alternatives, and outlines the public`s role in helping DOE and the EPA to make the final decision on a remedy.

  6. Groundwater intercept and treatment system north of Rocky Mountain Arsenal, interim response action. Final report

    SciTech Connect (OSTI)

    1989-07-01

    The objectives of the Off-Post interim response action are to: (1) Continue ground water monitoring and provide an alternative drinking water supply (2) Mitigate migration of contaminants in alluvial ground water (3) Treat contaminated alluvial ground water. This final decision document provides summaries of: (1) Alternatives considered (2) Significant events leading to the initiation of the IRA (3) The IRA Project (4) The applicable or relevant and appropriate requirements, standards, criteria, and limitations (ARAR`s) associated with the project. The selected IRA program will consists of: (1) Continued monitoring (2) Ground water extraction and recharge, but no physical barrier.

  7. Interim long-term surveillance plan for the Cheney disposal site near, Grand Junction, Colorado

    SciTech Connect (OSTI)

    1997-08-01

    This interim long-term surveillance plan (LTSP) describes the U.S. Department of Energy`s (DOE) long-term care program for the Uranium Mill Tailings Remedial Action (UMTRA) Project Cheney Disposal Site in Mesa County near Grand Junction, Colorado. This LSTP describes the long-term surveillance program the DOE will implement to ensure the Cheney disposal site performs as designed and is cared for in a manner that protects the public health and safety and the environment. Before each disposal site is licensed for custody and long-term care, the Nuclear Regulatory Commission (NRC) requires the DOE to submit such a site-specific LTSP.

  8. Carbonyl sulfide/carbon chemistry: Interim report, July 1, 1985-February 28, 1986

    SciTech Connect (OSTI)

    Hinckley, C.C.; Shiley, R.H.

    1986-05-01

    This interim report describes work performed during the first eight months of a continuing project, including descriptions of sample preparations and analyses. The objective of the study is to determine the effects of carbonyl sulfide, a product of the carbon monoxide/ethanol desulfurization process, on coal. A coal is first treated with carbon monoxide to reduce pyrite, and is then reacted with OCS and N/sub 2/ under various conditions. OCS is a potent resulfurization agent and appears to affect the formation of mesophase in chars derived from the coal. 8 refs., 1 fig., 8 tabs.

  9. 2006 Annual Operations Report for INTEC Operable Unit 3-13, Group 1, Tank Farm Interim Action

    SciTech Connect (OSTI)

    D. E. Shanklin

    2007-02-14

    This annual operations report describes the requirements followed and activities conducted to inspect, monitor, and maintain the items installed during performance of the Waste Area Group 3, Operable Unit 3-13, Group 1, Tank Farm Interim Action, at the Idaho Nuclear Technology and Engineering Center. This report covers the time period from January 1 through December 31, 2006, and describes inspection and monitoring activities for the surface-sealed areas within the tank farm, concrete-lined ditches and culverts in and around the tank farm, the lift station, and the lined evaporation pond. These activities are intended to assure that the interim action is functioning adequately to meet the objectives stated in the Operable Unit 3-13, Record of Decision for the Group 1, Tank Farm Interim Action (DOE/ID-10660) as described in the Group 1 Remedial Design/Remedial Action Work Plan (DOE/ID-10772).

  10. Formerly Utilized Sites Remedial Action Program (FUSRAP) Hazelwood Interim Storage Site annual site environmental report. Calendar year 1985. [FUSRAP

    SciTech Connect (OSTI)

    Not Available

    1986-04-01

    The Hazelwood Interim Storage Site (HISS) is presently used for the storage of low-level radioactively contaminated soils. Monitoring results show that the HISS is in compliance with DOE concentration guides and radiation protection standards. Derived Concentration Guides (DCGs) represent the concentrations of radionuclides in air or water that would limit the radiation dose to 100 mrem/y. The applicable limits have been revised since the 1984 environmental monitoring report was published. The limits applied in 1984 were based on a radiation protection standard of 500 mrem/y; the limits applied for 1985 are based on a standard of 100 mrem/y. The HISS is part of the Formerly Utilized Sites Remedial Action Program (FUSRAP), a DOE program to decontaminate or otherwise control sites where low-level radioactive contamination remains from the early years of the nation's atomic energy program. To determine whether the site is in compliance with DOE standards, environmental measurements are expressed as percentages of the applicable DCG, while the calculated doses to the public are expressed as percentages of the applicable radiation protection standard. The monitoring program at the HISS measures uranium, radium, and thorium concentrations in surface water, groundwater, and sediment; radon gas concentrations in air; and external gamma radiation exposure rates. Potential radiation doses to the public are also calculated. The HISS was designated for remedial action under FUSRAP because radioactivity above applicable limits was found to exist at the site and its vicinity. Elevated levels of radiation still exist in areas where remedial action has not yet been completed.

  11. Hanford Tank Farm interim storage phase probabilistic risk assessment outline

    SciTech Connect (OSTI)

    Not Available

    1994-05-19

    This report is the second in a series examining the risks for the high level waste (HLW) storage facilities at the Hanford Site. The first phase of the HTF PSA effort addressed risks from Tank 101-SY, only. Tank 101-SY was selected as the initial focus of the PSA because of its propensity to periodically release (burp) a mixture of flammable and toxic gases. This report expands the evaluation of Tank 101-SY to all 177 storage tanks. The 177 tanks are arranged into 18 farms and contain the HLW accumulated over 50 years of weapons material production work. A centerpiece of the remediation activity is the effort toward developing a permanent method for disposing of the HLW tank`s highly radioactive contents. One approach to risk based prioritization is to perform a PSA for the whole HLW tank farm complex to identify the highest risk tanks so that remediation planners and managers will have a more rational basis for allocating limited funds to the more critical areas. Section 3 presents the qualitative identification of generic initiators that could threaten to produce releases from one or more tanks. In section 4 a detailed accident sequence model is developed for each initiating event group. Section 5 defines the release categories to which the scenarios are assigned in the accident sequence model and presents analyses of the airborne and liquid source terms resulting from different release scenarios. The conditional consequences measured by worker or public exposure to radionuclides or hazardous chemicals and economic costs of cleanup and repair are analyzed in section 6. The results from all the previous sections are integrated to produce unconditional risk curves in frequency of exceedance format.

  12. Environmental surveillance results for 1994 for the Hazelwood Interim Storage Site. FUSRAP technical memorandum Number 140-95-011

    SciTech Connect (OSTI)

    Szojka, S.

    1995-06-01

    This report presents analytical results and an interpretation of the results for samples collected as part of the 1994 environmental surveillance program for the Hazelwood Interim Storage Site (HISS) for the interim storage of radiologically contaminated soils. The discussion provides a comparative analysis of local background conditions and applicable regulatory criteria to results reported for external gamma radiation and for samples from the media investigated (air, surface water, sediment, groundwater, and stormwater). Results from the 1994 environmental surveillance program at HISS indicate that Department of Energy (DOE) guidelines were not exceeded for the calculated airborne particulate dose or for the monitored constituents.

  13. Synthesis and characterization of metal hydride electrodes. Interim report

    SciTech Connect (OSTI)

    McBreen, J.; Reilly, J.J.

    1995-10-01

    The objective of this project is to elucidate the compositional and structural parameters that affect the thermodynamics, kinetics and stability of alloy hydride electrodes and to use this information in the development of new high capacity long life hydride electrodes for rechargeable batteries. The work focuses on the development of AB{sub 5} alloys and the application of in situ methods, at NSLS, such as x-ray absorption (XAS), to elucidate the role of the alloying elements in hydrogen storage and corrosion inhibition. The most significant results to date are: The decay of electrode capacity on cycling was directly related to alloy corrosion. The rate of corrosion depended in part on both the alloy composition and the partial molar volume of hydrogen, V{sub H}. The corrosion rate depended on the composition of the A component in AB{sub 5} (LaNi{sub 5} type) alloys. Partial substitution of La with Ce in AB{sub 5} alloys substantially inhibits electrode corrosion on cycling. Recent results indicate that Co also greatly inhibits electrode corrosion, possibly by minimizing V{sub H}. The AB{sub 5} alloys investigated included LaNi{sub 5}, ternary alloys (e.g. LaN{sub 4.8}Sn{sub 0.2} and La{sub 0.8}Ce{sub 0.2}Ni{sub 5}), alloys with various substitutions for both La and Ni (e.g. La{sub 0.8}Ce{sub 0.2}Ni{sub 4.8}Sn{sub 0.2}) and mischmetal (Mm) alloys of the type normally used in batteries, such as MmB{sub 5} (B = Ni{sub 3.55}Mn{sub 0.4}A1{sub 0.3}Co{sub 0.75}). A major effort was devoted to the effects of La substitution in the A component. Both in situ and ex situ XAS measurements are used to study the electronic effects that occur on the addition of various metal substitutions and on the ingress of hydrogen.

  14. Bunch mode specific rate corrections for PILATUS3 detectors

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Trueb, P.; Dejoie, C.; Kobas, M.; Pattison, P.; Peake, D. J.; Radicci, V.; Sobott, B. A.; Walko, D. A.; Broennimann, C.

    2015-04-09

    PILATUS X-ray detectors are in operation at many synchrotron beamlines around the world. This article reports on the characterization of the new PILATUS3 detector generation at high count rates. As for all counting detectors, the measured intensities have to be corrected for the dead-time of the counting mechanism at high photon fluxes. The large number of different bunch modes at these synchrotrons as well as the wide range of detector settings presents a challenge for providing accurate corrections. To avoid the intricate measurement of the count rate behaviour for every bunch mode, a Monte Carlo simulation of the counting mechanismmore » has been implemented, which is able to predict the corrections for arbitrary bunch modes and a wide range of detector settings. This article compares the simulated results with experimental data acquired at different synchrotrons. It is found that the usage of bunch mode specific corrections based on this simulation improves the accuracy of the measured intensities by up to 40% for high photon rates and highly structured bunch modes. For less structured bunch modes, the instant retrigger technology of PILATUS3 detectors substantially reduces the dependency of the rate correction on the bunch mode. The acquired data also demonstrate that the instant retrigger technology allows for data acquisition up to 15 million photons per second per pixel.« less

  15. Bunch mode specific rate corrections for PILATUS3 detectors

    SciTech Connect (OSTI)

    Trueb, P.; Dejoie, C.; Kobas, M.; Pattison, P.; Peake, D. J.; Radicci, V.; Sobott, B. A.; Walko, D. A.; Broennimann, C.

    2015-04-09

    PILATUS X-ray detectors are in operation at many synchrotron beamlines around the world. This article reports on the characterization of the new PILATUS3 detector generation at high count rates. As for all counting detectors, the measured intensities have to be corrected for the dead-time of the counting mechanism at high photon fluxes. The large number of different bunch modes at these synchrotrons as well as the wide range of detector settings presents a challenge for providing accurate corrections. To avoid the intricate measurement of the count rate behaviour for every bunch mode, a Monte Carlo simulation of the counting mechanism has been implemented, which is able to predict the corrections for arbitrary bunch modes and a wide range of detector settings. This article compares the simulated results with experimental data acquired at different synchrotrons. It is found that the usage of bunch mode specific corrections based on this simulation improves the accuracy of the measured intensities by up to 40% for high photon rates and highly structured bunch modes. For less structured bunch modes, the instant retrigger technology of PILATUS3 detectors substantially reduces the dependency of the rate correction on the bunch mode. The acquired data also demonstrate that the instant retrigger technology allows for data acquisition up to 15 million photons per second per pixel.

  16. Interim data quality objectives for waste pretreatment and vitrification. Revision 1

    SciTech Connect (OSTI)

    Kupfer, M.J.; Conner, J.M.; Kirkbride, R.A.; Mobley, J.R.

    1994-09-15

    The Tank Waste Remediation System (TWRS) is responsible for storing, processing, and immobilizing the Hanford Site tank wastes. Characterization information on the tank wastes is needed so that safety concerns can be addressed, and retrieval, pretreatment, and immobilization processes can be designed, permitted, and implemented. This document describes the near-term tank waste sampling and characterization needs of the Pretreatment, High-Level Waste (HLW) Disposal, and Low-Level Waste (LLW) Disposal Programs to support the TWRS disposal mission. The final DQO (Data Quality Objective) will define specific waste tanks to be sampled, sample timing requirements, an appropriate analytical scheme, and a list of required analytes. This interim DQO, however, focuses primarily on the required analytes since the tanks to be sampled in FY 1994 and early FY 1995 are being driven most heavily by other considerations, particularly safety. The major objective of this Interim DQO is to provide guidance for tank waste characterization requirements for samples taken before completion of the final DQO. The characterization data needs defined herein will support the final DQO to help perform the following: Support the TWRS technical strategy by identification of the chemical and physical composition of the waste in the tanks and Guide development efforts to define waste pretreatment processes, which will in turn define HLW and LLW feed to vitrification processes.

  17. Hazelwood Interim Storage Site environmental monitoring summary, Hazelwood, Missouri, calendar year 1984

    SciTech Connect (OSTI)

    Not Available

    1985-07-01

    The Hazelwood Interim Storage Site (HISS) is located at 9200 Latty Avenue, Hazelwood, Missouri. The property on which the HISS is situated is owned by the Jarboe Realty and Investment Company and is leased to Futura Coatings, Inc. Radiological surveys in 1977 and 1982 indicated uranium and thorium contamination and elevated radiation levels in the soil on this property and several others in the immediate vicinity. As part of the research and development program authorized by Congress under the 1984 Energy and Water Appropriations Act, Bechtel National, Inc. (BNI) is conducting remedial action on-site and at the vicinity properties. The work is being performed as part of the US Department of Energy (DOE) Formerly Utilized Sites Remedial Action Program (FUSRAP). Jarboe Realty and Investment Company has agreed to permit DOE to store contaminated material from the FY 1984 and 1985 Latty Avenue cleanup on its property. The contaminated material will be added to the existing pile created during the earlier site cleanup. The pile will then be covered to prevent erosion or migration of contamination. The property will be maintained as the HISS by DOE until final disposition for these materials is determined. BNI is conducting a surveillance monitoring program at the HISS during the interim storage period to detect potential migration of contaminants from the storage pile via air, water, and sediment. This summary provides these monitoring data for calendar year 1984. 6 refs., 4 tabs.

  18. INTERIM BARRIER AT HANFORDS TY FARM TO PROTECT GROUNDWATER AT THE HANFORD SITE WASHINGTON USA

    SciTech Connect (OSTI)

    PARKER DL; HOLM MJ; HENDERSON JC; LOBER RW

    2011-01-13

    An innovative interim surface barrier was constructed as a demonstration project at the Hanford Site's TY Tank Farm. The purpose of the demonstration barrier is to stop rainwater and snowmelt from entering the soils within the tank farm and driving contamination from past leaks and spills toward the ground water. The interim barrier was constructed using a modified asphalt material with very low permeability developed by MatCon{reg_sign}. Approximately 2,400 cubic yards of fill material were added to the tank farm to create a sloped surface that will gravity drain precipitation to collection points where it will be routed through buried drain lines to an evapotranspiration basin adjacent to the farm. The evapotranspiration basin is a lined basin with a network of perforated drain lines covered with soil and planted with native grasses. The evapotranspiration concept was selected because it prevents the runoff from percolating into the soil column and also avoids potential monitoring and maintenance issues associated with standing water in a traditional evaporation pond. Because of issues associated with using standard excavation and earth moving equipment in the farm a number of alternate construction approaches were utilized to perform excavations and prepare the site for the modified asphalt.

  19. INTERIM STORAGE AND LONG TERM DISPOSAL OF RESEARCH REACTOR SPENT FUEL

    SciTech Connect (OSTI)

    Vinson, D

    2006-08-22

    Aluminum clad research reactor spent nuclear fuel (SNF) is currently being consolidated in wet storage basins (pools). Approximately 20 metric tons (heavy metal) of aluminum-based spent nuclear fuel (Al-SNF) is being consolidated for treatment, packaging, interim storage, and preparation for ultimate disposal in a geologic repository. The storage and disposal of Al-SNF are subject to requirements that provide for safety and acceptable radionuclide release. The options studied for interim storage of SNF include wet storage and dry storage. Two options have also been studied to develop the technical basis for the qualification and repository disposal of aluminum spent fuel. The two options studied include Direct Disposal and Melt-Dilute treatment. The implementation of these options present relative benefits and challenges. Both the Direct Disposal and the Melt-Dilute treatment options have been developed and their technical viability assessed. Adaptation of the melt-dilute technology for the treatment of spent fuel offers the benefits of converting the spent fuel into a proliferation resistant form and/or significantly reducing the volume of the spent fuel. A Mobile Melt-Dilute system concept has emerged to realize these benefits and a prototype system developed. The application of the melt-dilute technology for the treatment of legacy nuclear materials has been evaluated and also offers the promise for the safe disposal of these materials.

  20. COMPLETION OF THE FIRST INTEGRATED SPENT NUCLEAR FUEL TRANSSHIPMENT/INTERIM STORAGE FACILITY IN NW RUSSIA

    SciTech Connect (OSTI)

    Dyer, R.S.; Barnes, E.; Snipes, R.L.; Hoeibraaten, S.; Gran, H.C.; Foshaug, E.; Godunov, V.

    2003-02-27

    Northwest and Far East Russia contain large quantities of unsecured spent nuclear fuel (SNF) from decommissioned submarines that potentially threaten the fragile environments of the surrounding Arctic and North Pacific regions. The majority of the SNF from the Russian Navy, including that from decommissioned nuclear submarines, is currently stored in on-shore and floating storage facilities. Some of the SNF is damaged and stored in an unstable condition. Existing Russian transport infrastructure and reprocessing facilities cannot meet the requirements for moving and reprocessing this amount of fuel. Additional interim storage capacity is required. Most of the existing storage facilities being used in Northwest Russia do not meet health and safety, and physical security requirements. The United States and Norway are currently providing assistance to the Russian Federation (RF) in developing systems for managing these wastes. If these wastes are not properly managed, they could release significant concentrations of radioactivity to these sensitive environments and could become serious global environmental and physical security issues. There are currently three closely-linked trilateral cooperative projects: development of a prototype dual-purpose transport and storage cask for SNF, a cask transshipment interim storage facility, and a fuel drying and cask de-watering system. The prototype cask has been fabricated, successfully tested, and certified. Serial production is now underway in Russia. In addition, the U.S. and Russia are working together to improve the management strategy for nuclear submarine reactor compartments after SNF removal.

  1. Energy policy act transportation study: Interim report on natural gas flows and rates

    SciTech Connect (OSTI)

    1995-11-17

    This report, Energy Policy Act Transportation Study: Interim Report on Natural Gas Flows and Rates, is the second in a series mandated by Title XIII, Section 1340, ``Establishment of Data Base and Study of Transportation Rates,`` of the Energy Policy Act of 1992 (P.L. 102--486). The first report Energy Policy Act Transportation Study: Availability of Data and Studies, was submitted to Congress in October 1993; it summarized data and studies that could be used to address the impact of legislative and regulatory actions on natural gas transportation rates and flow patterns. The current report presents an interim analysis of natural gas transportation rates and distribution patterns for the period from 1988 through 1994. A third and final report addressing the transportation rates and flows through 1997 is due to Congress in October 2000. This analysis relies on currently available data; no new data collection effort was undertaken. The need for the collection of additional data on transportation rates will be further addressed after this report, in consultation with the Congress, industry representatives, and in other public forums.

  2. Lead-based paint: Interim guidelines for hazard identification and abatement in public and Indian housing

    SciTech Connect (OSTI)

    Not Available

    1990-09-01

    The interim Guidelines provide information on the need for and appropriate methods of identifying and abating lead-based paint (LBP) in the Department of Housing and Urban Development's (HUD's) Public and Indian Housing program. It should be noted that these are interim Guidelines and are subject to change as new information becomes available. All requirements for Public Housing Authorities (PHAs) are considered to apply to Indian Housing Authorities (IHAs), except where specifically excluded by statute. Thus, these Guidelines apply to PHAs and IHAs inclusively. These Guidelines have been prepared by a panel of distinguished experts in the field of LBP and are an outgrowth of the National Institute of Building Sciences (NIBS) effort, which developed the first draft of these guidelines under contract to HUD. These Guidelines represent the first national compilation of technical protocols, practices, and procedures on testing, abatement, worker protection, clean-up, and disposal of LBP in residential structures. These Guidelines should be used in conjunction with the requirements of any State or local codes and regulations which may apply to the specific project under consideration.

  3. CORRECTIVE ACTION PLAN FOR CORRECTIVE ACTION UNIT 543: LIQUID DISPOSAL UNITS, NEVADA TEST SITE, NEVADA

    SciTech Connect (OSTI)

    2006-09-01

    The purpose of this Corrective Action Plan is to provide the detailed scope of work required to implement the recommended corrective actions as specified in the approved Corrective Action Decision Document.

  4. Program Course Corrections Based on Evaluation Results

    Broader source: Energy.gov [DOE]

    Better Buildings Neighborhood Program Data and Evaluation Peer Exchange Call: Program Course Corrections Based on Evaluation Results, Call Slides and Discussion Summary, April 12, 2012, This call discussed using evaluation results as the basis for course corrections.

  5. Environmental Management Headquarters Corrective Action Plan...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    II Environmental Management Headquarters Corrective Action Plan - Radiological Release ... actions for addressing Office of Environmental Management (EM) Headquarters (HQ) ...

  6. Clothes Washer Test Cloth Correction Factor Information

    Broader source: Energy.gov [DOE]

    This page contains the information used to determine the test cloth correction factors for each test cloth lot.

  7. Request for Correction | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Request for Correction Request for Correction In the Department of Energy's correction request process, the burden of proof rests with the requester. An affected person who believes that information the Department disseminates does not adhere to the information quality guidelines of OMB or the Department, or who would like to request correction of specific information, needs to provide the following information within 60 calendar days of the initial information dissemination: Requester

  8. Interim Report on Consumer Acceptance, Retention, and response to Time-based rates from the Consumer Behavior Studies

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    U.S. Department of Energy |June 2015 Interim Report on Impacts from the Consumer Behavior Studies | Page ii Table of Contents Executive Summary .............................................................................................................. iv 1. Introduction ................................................................................................................... 1 1.1 Background about Time-Based Rates and Advanced Metering Infrastructure ............ 1 1.2 Overview of

  9. Streamlined approach for environmental restoration (SAFER) plan for corrective action unit 412: clean slate I plutonium dispersion (TTR) tonopah test range, Nevada, revision 0

    SciTech Connect (OSTI)

    Matthews, Patrick K.

    2015-04-01

    This Streamlined Approach for Environmental Restoration (SAFER) Plan addresses the actions needed to achieve closure for Corrective Action Unit (CAU) 412. CAU 412 is located on the Tonopah Test Range and consists of a single corrective action site (CAS), TA-23-01CS, Pu Contaminated Soil. There is sufficient information and historical documentation from previous investigations and the 1997 interim corrective action to recommend closure of CAU 412 using the SAFER process. Based on existing data, the presumed corrective action for CAU 412 is clean closure. However, additional data will be obtained during a field investigation to document and verify the adequacy of existing information and determine whether the CAU 412 closure objectives have been achieved. This SAFER Plan provides the methodology to gather the necessary information for closing the CAU.The following summarizes the SAFER activities that will support the closure of CAU 412:• Collect environmental samples from designated target populations to confirm or disprove the presence of contaminants of concern (COCs) as necessary to supplement existing information.• If no COCs are present, establish clean closure as the corrective action. • If COCs are present, the extent of contamination will be defined and further corrective actions will be evaluated with the stakeholders (NDEP, USAF).• Confirm the preferred closure option is sufficient to protect human health and the environment.

  10. Space Charge Correction on Emittance Measurement of Low Energy...

    Office of Scientific and Technical Information (OSTI)

    in the calculation of beam emittance. We present below the preliminary results of a MATLAB code built to model the transport of a charged particle beam through an accelerator...

  11. Intracavity adaptive correction of a 10 kW, solid-state, heat-capacity laser.

    SciTech Connect (OSTI)

    LaFortune, K N; Hurd, R L; Johansson, E M; Dane, C B; Fochs, S N; Brase, J M

    2004-01-12

    The Solid-State, Heat-Capacity Laser (SSHCL), under development at Lawrence Livermore National Laboratory is a large aperture (100 cm{sup 2}), confocal, unstable resonator requiring near-diffraction-limited beam quality. There are two primary sources of the aberrations in the system: residual, static aberrations from the fabrication of the optical components and predictable, time-dependent, thermally-induced index gradients within the gain medium. A deformable mirror placed within the cavity is used to correct the aberrations that are sensed externally with a Shack-Hartmann wavefront sensor. Although it is more challenging than external correction, intracavity correction enables control of the mode growth within the resonator, resulting in the ability to correct a more aberrated system longer. The overall system design, measurement techniques and correction algorithms are discussed. Experimental results from initial correction of the static aberrations and dynamic correction of the time-dependent aberrations are presented.

  12. Scalable error correction in distributed ion trap computers

    SciTech Connect (OSTI)

    Oi, Daniel K. L.; Devitt, Simon J.; Hollenberg, Lloyd C. L.

    2006-11-15

    A major challenge for quantum computation in ion trap systems is scalable integration of error correction and fault tolerance. We analyze a distributed architecture with rapid high-fidelity local control within nodes and entangled links between nodes alleviating long-distance transport. We demonstrate fault-tolerant operator measurements which are used for error correction and nonlocal gates. This scheme is readily applied to linear ion traps which cannot be scaled up beyond a few ions per individual trap but which have access to a probabilistic entanglement mechanism. A proof-of-concept system is presented which is within the reach of current experiment.

  13. Coincidence corrected efficiency calibration of Compton-suppressed HPGe detectors

    SciTech Connect (OSTI)

    Aucott, T.

    2015-04-20

    The authors present a reliable method to calibrate the full-energy efficiency and the coincidence correction factors using a commonly-available mixed source gamma standard. This is accomplished by measuring the peak areas from both summing and non-summing decay schemes and simultaneously fitting both the full-energy efficiency, as well as the total efficiency, as functions of energy. By using known decay schemes, these functions can then be used to provide correction factors for other nuclides not included in the calibration standard.

  14. Rockwell International Hot Laboratory decontamination and dismantlement interim progress report 1987-1996

    SciTech Connect (OSTI)

    1997-05-06

    OAK A271 Rockwell International Hot Laboratory decontamination and dismantlement interim progress report 1987-1996. The Rockwell International Hot Laboratory (RIHL) is one of a number of former nuclear facilities undergoing decontamination and decommissioning (D&D) at the Santa Susana Field Laboratory (SSFL). The RIHL facility is in the later stages of dismantlement, with the final objective of returning the site location to its original natural state. This report documents the decontamination and dismantlement activities performed at the facility over the time period 1988 through 1996. At this time, the support buildings, all equipment associated with the facility, and the entire above-ground structure of the primary facility building (Building 020) have been removed. The basement portion of this building and the outside yard areas (primarily asphalt and soil) are scheduled for D&D activities beginning in 1997.

  15. PROJECT W-551 SUMMARY INFORMATION FOR EARLY LAW INTERIM PRETREATMENT SYSTEM SELECTION

    SciTech Connect (OSTI)

    AR, TEDESCHI

    2008-08-11

    This report provides summary data for use by the decision board to assess and select the final technology for project W-551, Interim Pretreatment System. This project will provide early pretreated low activity waste feed to the Waste Treatment Plant to allow Waste Treatment Plan Low Activity Waste facility operation prior to construction completion of the Pretreatment and High Level Waste facilities. The candidate solids separations technologies are rotary microfiltration and crossflow filtration, and the candidate cesium separation technologies are fractional crystallization, caustic-side solvent extraction, and ion-exchange using spherical resorcinol-fonnaldebyde resin. This document provides a summary of comparative data against prior weighted criteria to support technology selection. Supporting details and background for this summary are documented in the separate report, RPP-RPT-37741.

  16. The design of a Phase I non site-specific Centralized Interim Storage Facility

    SciTech Connect (OSTI)

    Stringer, J.; Kane, D.

    1997-10-28

    The Department of Energy (DOE), Office of Civilian Radioactive Waste Management (OCRWM) recently completed a Topical Safety Analysis Report (TSAR) for a Phase 1 non site specific Centralized Interim Storage Facility (CISF). The TSAR will be used in licensing the CISF when and if a site is designated. The combined Phase 1 and Phase 2 CISF will provide federal storage capability for 40,000 metric tons of uranium (MTU) Spent Nuclear Fuel (SNF) under the oversight of the DOE. The Phase 1 TSAR was submitted to the NRC on May 1, 1997 and is currently under review having been docketed on June 10, 1997. This paper generally describes the Phase 1 CISF design and its operations as presented in the CISF TSAR.

  17. Alternative fuel transit buses: Interim results from the National Renewable Energy Laboratory (NREL) Vehicle Evaluation Program

    SciTech Connect (OSTI)

    Motta, R.; Norton, P.; Kelly, K.J.; Chandler, K.

    1995-05-01

    The transit bus program is designed to provide a comprehensive study of the alternative fuels currently used by the transit bus industry. The study focuses on the reliability, fuel economy, operating costs, and emissions of vehicles running on the various fuels and alternative fuel engines. The alternative fuels being tested are methanol, ethanol, biodiesel and natural gas. The alternative fuel buses in this program use the most common alternative fuel engines from the heavy-duty engine manufacturers. Data are collected in four categories: Bus and route descriptions; Bus operating data; Emissions data; and, Capital costs. The goal is to collect 18 months of data on each test bus. This report summarizes the interim results from the project to date. The report addresses performance and reliability, fuel economy, costs, and emissions of the busses in the program.

  18. Final decision document for other contamination sources, interim response action, shell section 36 trenches, RMA

    SciTech Connect (OSTI)

    1990-04-01

    The shell section 36 trenches were used from 1952 to 1966 for land disposal of liquid and solid wastes generated from pesticide manufacture. They have been shown to be a source of soil and ground water contamination for volatile and semivolatile compounds. A dense non-aqueous phase liquid (DNAPL) is also believed to have originated from the area. The objective of the interim response action is to reduce the lateral migration of contaminants emanating from the trenches. The preferred IRA alternative consists of (1) A physical barrier encircling the trenches and (2) a soil and vegetative cover to eliminate recharge. This final decision document provides summaries of: (1). Alternatives considered (2). Significant events leading to the initiation of the IRA (3). The IRA project (4). Applicable or relevant and appropriate requirements, standards.

  19. Interim Safe Storage of Plutonium Production Reactors at the US DOE Hanford Site - 13438

    SciTech Connect (OSTI)

    Schilperoort, Daryl L.; Faulk, Darrin

    2013-07-01

    Nine plutonium production reactors located on DOE's Hanford Site are being placed into an Interim Safe Storage (ISS) period that extends to 2068. The Environmental Impact Statement (EIS) for ISS [1] was completed in 1993 and proposed a 75-year storage period that began when the EIS was finalized. Remote electronic monitoring of the temperature and water level alarms inside the safe storage enclosure (SSE) with visual inspection inside the SSE every 5 years are the only planned operational activities during this ISS period. At the end of the ISS period, the reactor cores will be removed intact and buried in a landfill on the Hanford Site. The ISS period allows for radioactive decay of isotopes, primarily Co-60 and Cs-137, to reduce the dose exposure during disposal of the reactor cores. Six of the nine reactors have been placed into ISS by having an SSE constructed around the reactor core. (authors)

  20. Verification of maximum impact force for interim storage cask for the Fast Flux Testing Facility

    SciTech Connect (OSTI)

    Chen, W.W.; Chang, S.J.

    1996-06-01

    The objective of this paper is to perform an impact analysis of the Interim Storage Cask (ISC) of the Fast Flux Test Facility (FFTF) for a 4-ft end drop. The ISC is a concrete cask used to store spent nuclear fuels. The analysis is to justify the impact force calculated by General Atomics (General Atomics, 1994) using the ILMOD computer code. ILMOD determines the maximum force developed by the concrete crushing which occurs when the drop energy has been absorbed. The maximum force, multiplied by the dynamic load factor (DLF), was used to determine the maximum g-level on the cask during a 4-ft end drop accident onto the heavily reinforced FFTF Reactor Service Building`s concrete surface. For the analysis, this surface was assumed to be unyielding and the cask absorbed all the drop energy. This conservative assumption simplified the modeling used to qualify the cask`s structural integrity for this accident condition.

  1. Considerations of the effects of high winds on a low-level radioactive interim storage pile

    SciTech Connect (OSTI)

    Smith, D.E. )

    1991-11-01

    On Wednesday, March 27, 1991, the St. Louis area experienced high winds that damaged a synthetic cover of a low-level radioactive waste storage pile at the US Department of Energy's (DOE's) Hazelwood Interim Storage Site (HISS) in Hazelwood, Missouri. Winds in the St. Louis area at the time of the incident were reported to be 35 mi/h with gusts up to 50 mi/h. Tornado warnings were in effect at the time. The purpose of this summary is to analyze the effects of uplift forces on a synthetic pile cover because of high winds. Consideration is given to anchoring the synthetic cover, type and placement of ballast on the pile, and the type of synthetic membranes best suited to this application. Discussion also includes the emergency procedures used in responding to the incident.

  2. Contaminant transport in unconfined aquifer, input to low-level tank waste interim performance assessment

    SciTech Connect (OSTI)

    Lu, A.H., Westinghouse Hanford

    1996-08-14

    This report describes briefly the Hanford sitewide groundwater model and its application to the Low-Level Tank Waste Disposal (LLTWD) interim Performance Assessment (PA). The Well Intercept Factor (WIF) or dilution factor from a given areal flux entering the aquifer released from the LLTWD site are calculated for base case and various sensitivity cases. In conjunction with the calculation for released fluxes through vadose zone transport,the dose at the compliance point can be obtained by a simple multiplication. The relative dose contribution from the upstream sources was also calculated and presented in the appendix for an equal areal flux at the LLTWD site. The results provide input for management decisions on remediation action needed for reduction of the released fluxes from the upstream facilities to the allowed level to meet the required dose criteria.

  3. PROJECT W-551 DETERMINATION DATA FOR EARLY LAW INTERIM PRETREATMENT SYSTEM SELECTION

    SciTech Connect (OSTI)

    TEDESCHI AR

    2008-08-11

    This report provides the detailed assessment forms and data for selection of the solids separation and cesium separation technology for project W-551, Interim Pretreatment System. This project will provide early pretreated low activity waste feed to the Waste Treatment Plant to allow Waste Treatment Plan Low Activity Waste facility operation prior to construction completion of the Pretreatment and High Level Waste facilities. The candidate solids separations technologies are rotary microfiltration and crossflow filtration, and the candidate cesium separation technologies are fractional crystallization, caustic-side solvent extraction, and ion-exchange using spherical resorcinol-formaldehyde resin. This data was used to prepare a cross-cutting technology summary, reported in RPP-RPT-37740.

  4. 40 CFR 265 interim-status ground-water monitoring plan for the 2101-M pond

    SciTech Connect (OSTI)

    Chamness, M.A.; Luttrell, S.P.; Dudziak, S.

    1989-03-01

    This report outlines a ground-water monitoring plan for the 2101-M pond, located in the southwestern part of the 200-East Area on the Hanford Site in south-central Washington State. It has been determined that hazardous materials may have been discharged to the pond. Installation of an interim-status ground-water monitoring system is required under the Resource Conservation and Recovery Act to determine if hazardous chemicals are moving out of the pond. This plan describes the location of new wells for the monitoring system, how the wells are to be completed, the data to be collected, and how those data can be used to determine the source and extent of any ground-water contamination from the 2101-M pond. Four new wells are planned, one upgradient and three downgradient. 35 refs., 12 figs., 9 tabs.

  5. Interim Status Closure Plan Open Burning Treatment Unit Technical Area 16-399 Burn Tray

    SciTech Connect (OSTI)

    Vigil-Holterman, Luciana R.

    2012-05-07

    This closure plan describes the activities necessary to close one of the interim status hazardous waste open burning treatment units at Technical Area (TA) 16 at the Los Alamos National Laboratory (LANL or the Facility), hereinafter referred to as the 'TA-16-399 Burn Tray' or 'the unit'. The information provided in this closure plan addresses the closure requirements specified in the Code of Federal Regulations (CFR), Title 40, Part 265, Subparts G and P for the thermal treatment units operated at the Facility under the Resource Conservation and Recovery Act (RCRA) and the New Mexico Hazardous Waste Act. Closure of the open burning treatment unit will be completed in accordance with Section 4.1 of this closure plan.

  6. Design requirements document for Project W-465, immobilized low-activity waste interim storage

    SciTech Connect (OSTI)

    Burbank, D.A.

    1998-05-19

    The scope of this Design Requirements Document (DRD) is to identify the functions and associated requirements that must be performed to accept, transport, handle, and store immobilized low-activity waste (ILAW) produced by the privatized Tank Waste Remediation System (TWRS) treatment contractors. The functional and performance requirements in this document provide the basis for the conceptual design of the TWRS ILAW Interim Storage facility project and provides traceability from the program level requirements to the project design activity. Technical and programmatic risk associated with the TWRS planning basis are discussed in the Tank Waste Remediation System Decisions and Risk Assessment (Johnson 1994). The design requirements provided in this document will be augmented by additional detailed design data documented by the project.

  7. Deep Vadose Zone Treatability Test for the Hanford Central Plateau: Interim Post-Desiccation Monitoring Results

    SciTech Connect (OSTI)

    Truex, Michael J.; Oostrom, Martinus; Strickland, Christopher E.; Johnson, Timothy C.; Johnson, Christian D.; Clayton, Ray E.; Chronister, Glen B.

    2013-09-01

    A field test of desiccation is being conducted as an element of the deep vadose zone treatability test program. Desiccation technology relies on removal of water from a portion of the subsurface such that the resultant low moisture conditions inhibit downward movement of water and dissolved contaminants. Previously, a field test report (Truex et al. 2012a) was prepared describing the active desiccation portion of the test and initial post-desiccation monitoring data. Additional monitoring data have been collected at the field test site during the post-desiccation period and is reported herein along with interpretation with respect to desiccation performance. This is an interim report including about 2 years of post-desiccation monitoring data.

  8. Engineering evaluation/cost analysis-environmental assessment for the proposed decontamination of properties in the vicinity of the Hazelwood Interim Storage Site, Hazelwood, Missouri

    SciTech Connect (OSTI)

    Picel, M.H.; Peterson, J.M. . Environmental Assessment and Information Sciences Div.); Williams, M.J. )

    1992-03-01

    The US Department of Energy (DOE), under its Formerly Utilized Sites Remedial Action Program (FUSRAP), is implementing a cleanup program for three groups of properties in the St. Louis, Missouri, area. None of the properties is owned by DOE, but each property contains radioactive residues from federal uranium-processing activities conducted at the SLDS during and after World War II. This engineering evaluation/cost analysis (EE/CA) report has been prepared to support the interim cleanup measures for the contaminated properties in the Hazelwood and Berkeley, Missouri area. The near-term cleanup measures that may be necessary at the vicinity properties are evaluated in the main body of this report. Because of the range of active land uses in the Hazelwood and Berkeley areas and because of the extent of contamination on public and private properties, the potential exists for disturbance and spreading of soil contamination. Specifically, implementation of the proposed action would allow DOE to remove, transport, and safely store contaminated soils from properties where other activities (not involving DOE) are likely to result in either spreading contamination or otherwise complicating ultimate cleanup measures.

  9. Engineering evaluation/cost analysis for the proposed decontamination of properties in the vicinity of the Hazelwood Interim Storage Site, Hazelwood, Missouri -- environment assessment

    SciTech Connect (OSTI)

    Picel, M.H.; Peterson, J.M. . Environmental Assessment and Information Sciences Div.); Williams, M.J. )

    1991-05-01

    The US Department of Energy (DOE), under its Formerly Utilized Sites Remedial Action Program (FUSRAP), is implementing a cleanup program for three groups of properties in the St. Louis, Missouri, area. None of the properties is owned by DOE, but each property contains radioactive residues from federal uranium-processing activities conducted at the SLDS during and after World War II. This engineering evaluation/cost analysis (EE/CA) report has been prepared to support the interim cleanup measures for the contaminated properties in the Hazelwood and Berkeley, Missouri area. The near-term cleanup measures that may be necessary at the vicinity properties are evaluated in the main body of this report. Because of the range of active land uses in the Hazelwood and Berkeley areas and because of the extent of contamination on public and private properties, the potential exists for disturbance and spreading of soil contamination. Specifically, implementation of the proposed action would allow DOE to remove, transport, and safely store contaminated soils from properties where other activities (not involving DOE) are likely to result in either spreading contamination or otherwise complicating ultimate cleanup measures. 25 refs., 4 figs., 6 tabs.

  10. Engineering evaluation/cost analysis-environmental assessment for the proposed decontamination of properties in the vicinity of the Hazelwood Interim Storage Site, Hazelwood, Missouri. Revision 1

    SciTech Connect (OSTI)

    Picel, M.H.; Peterson, J.M.; Williams, M.J.

    1992-03-01

    The US Department of Energy (DOE), under its Formerly Utilized Sites Remedial Action Program (FUSRAP), is implementing a cleanup program for three groups of properties in the St. Louis, Missouri, area. None of the properties is owned by DOE, but each property contains radioactive residues from federal uranium-processing activities conducted at the SLDS during and after World War II. This engineering evaluation/cost analysis (EE/CA) report has been prepared to support the interim cleanup measures for the contaminated properties in the Hazelwood and Berkeley, Missouri area. The near-term cleanup measures that may be necessary at the vicinity properties are evaluated in the main body of this report. Because of the range of active land uses in the Hazelwood and Berkeley areas and because of the extent of contamination on public and private properties, the potential exists for disturbance and spreading of soil contamination. Specifically, implementation of the proposed action would allow DOE to remove, transport, and safely store contaminated soils from properties where other activities (not involving DOE) are likely to result in either spreading contamination or otherwise complicating ultimate cleanup measures.

  11. Rulison Site corrective action report

    SciTech Connect (OSTI)

    1996-09-01

    Project Rulison was a joint US Atomic Energy Commission (AEC) and Austral Oil Company (Austral) experiment, conducted under the AEC`s Plowshare Program, to evaluate the feasibility of using a nuclear device to stimulate natural gas production in low-permeability gas-producing geologic formations. The experiment was conducted on September 10, 1969, and consisted of detonating a 40-kiloton nuclear device at a depth of 2,568 m below ground surface (BGS). This Corrective Action Report describes the cleanup of petroleum hydrocarbon- and heavy-metal-contaminated sediments from an old drilling effluent pond and characterization of the mud pits used during drilling of the R-EX well at the Rulison Site. The Rulison Site is located approximately 65 kilometers (40 miles) northeast of Grand Junction, Colorado. The effluent pond was used for the storage of drilling mud during drilling of the emplacement hole for the 1969 gas stimulation test conducted by the AEC. This report also describes the activities performed to determine whether contamination is present in mud pits used during the drilling of well R-EX, the gas production well drilled at the site to evaluate the effectiveness of the detonation in stimulating gas production. The investigation activities described in this report were conducted during the autumn of 1995, concurrent with the cleanup of the drilling effluent pond. This report describes the activities performed during the soil investigation and provides the analytical results for the samples collected during that investigation.

  12. Phase and birefringence aberration correction

    DOE Patents [OSTI]

    Bowers, M.; Hankla, A.

    1996-07-09

    A Brillouin enhanced four wave mixing phase conjugate mirror corrects phase aberrations of a coherent electromagnetic beam and birefringence induced upon that beam. The stimulated Brillouin scattering (SBS) phase conjugation technique is augmented to include Brillouin enhanced four wave mixing (BEFWM). A seed beam is generated by a main oscillator which arrives at the phase conjugate cell before the signal beams in order to initiate the Brillouin effect. The signal beam which is being amplified through the amplifier chain is split into two perpendicularly polarized beams. One of the two beams is chosen to be the same polarization as some component of the seed beam, the other orthogonal to the first. The polarization of the orthogonal beam is then rotated 90{degree} such that it is parallel to the other signal beam. The three beams are then focused into cell containing a medium capable of Brillouin excitation. The two signal beams are focused such that they cross the seed beam path before their respective beam waists in order to achieve BEFWM or the two signal beams are focused to a point or points contained within the focused cone angle of the seed beam to achieve seeded SBS, and thus negate the effects of all birefringent and material aberrations in the system. 5 figs.

  13. Phase and birefringence aberration correction

    DOE Patents [OSTI]

    Bowers, Mark; Hankla, Allen

    1996-01-01

    A Brillouin enhanced four wave mixing phase conjugate mirror corrects phase aberrations of a coherent electromagnetic beam and birefringence induced upon that beam. The stimulated Brillouin scattering (SBS) phase conjugation technique is augmented to include Brillouin enhanced four wave mixing (BEFWM). A seed beam is generated by a main oscillator which arrives at the phase conjugate cell before the signal beams in order to initiate the Brillouin effect. The signal beam which is being amplified through the amplifier chain is split into two perpendicularly polarized beams. One of the two beams is chosen to be the same polarization as some component of the seed beam, the other orthogonal to the first. The polarization of the orthogonal beam is then rotated 90.degree. such that it is parallel to the other signal beam. The three beams are then focused into cell containing a medium capable of Brillouin excitation. The two signal beams are focused such that they cross the seed beam path before their respective beam waists in order to achieve BEFWM or the two signal beams are focused to a point or points contained within the focused cone angle of the seed beam to achieve seeded SBS, and thus negate the effects of all birefringent and material aberrations in the system.

  14. Corrective Action Decision Document/Corrective Action Plan for the 92-Acre Area and Corrective Action Unit 111: Area 5 WMD Retired Mixed Waste Pits, Nevada National Security Site, Nevada

    SciTech Connect (OSTI)

    NSTec Environmental Restoration

    2010-11-22

    This Corrective Action Decision Document/Corrective Action Plan (CADD/CAP) has been prepared for the 92-Acre Area, the southeast quadrant of the Radioactive Waste Management Site, located in Area 5 of the Nevada National Security Site (NNSS). The 92-Acre Area includes Corrective Action Unit (CAU) 111, 'Area 5 WMD Retired Mixed Waste Pits.' Data Quality Objectives (DQOs) were developed for the 92-Acre Area, which includes CAU 111. The result of the DQO process was that the 92-Acre Area is sufficiently characterized to provide the input data necessary to evaluate corrective action alternatives (CAAs) without the collection of additional data. The DQOs are included as Appendix A of this document. This CADD/CAP identifies and provides the rationale for the recommended CAA for the 92-Acre Area, provides the plan for implementing the CAA, and details the post-closure plan. When approved, this CADD/CAP will supersede the existing Pit 3 (P03) Closure Plan, which was developed in accordance with Title 40 Code of Federal Regulations (CFR) Part 265, 'Interim Status Standards for Owners and Operators of Hazardous Waste Treatment, Storage, and Disposal Facilities.' This document will also serve as the Closure Plan and the Post-Closure Plan, which are required by 40 CFR 265, for the 92-Acre Area. After closure activities are complete, a request for the modification of the Resource Conservation and Recovery Act Permit that governs waste management activities at the NNSS will be submitted to the Nevada Division of Environmental Protection to incorporate the requirements for post-closure monitoring. Four CAAs, ranging from No Further Action to Clean Closure, were evaluated for the 92-Acre Area. The CAAs were evaluated on technical merit focusing on performance, reliability, feasibility, safety, and cost. Based on the evaluation of the data used to develop the conceptual site model; a review of past, current, and future operations at the site; and the detailed and comparative

  15. Corrective Action Decision Document/Corrective Action Plan for the 92-Acre Area and Corrective Action Unit 111: Area 5 WMD Retired Mixed Waste Pits, Nevada Test Site, Nevada

    SciTech Connect (OSTI)

    NSTec Environmental Restoration

    2009-07-31

    This Corrective Action Decision Document/Corrective Action Plan (CADD/CAP) has been prepared for the 92-Acre Area, the southeast quadrant of the Radioactive Waste Management Site, located in Area 5 of the Nevada Test Site (NTS). The 92-Acre Area includes Corrective Action Unit (CAU) 111, 'Area 5 WMD Retired Mixed Waste Pits.' Data Quality Objectives (DQOs) were developed for the 92-Acre Area, which includes CAU 111. The result of the DQO process was that the 92-Acre Area is sufficiently characterized to provide the input data necessary to evaluate corrective action alternatives (CAAs) without the collection of additional data. The DQOs are included as Appendix A of this document. This CADD/CAP identifies and provides the rationale for the recommended CAA for the 92-Acre Area, provides the plan for implementing the CAA, and details the post-closure plan. When approved, this CADD/CAP will supersede the existing Pit 3 (P03) Closure Plan, which was developed in accordance with Title 40 Code of Federal Regulations (CFR) Part 265, 'Interim Status Standards for Owners and Operators of Hazardous Waste Treatment, Storage, and Disposal Facilities.' This document will also serve as the Closure Plan and the Post-Closure Plan, which are required by 40 CFR 265, for the 92-Acre Area. After closure activities are complete, a request for the modification of the Resource Conservation and Recovery Act Permit that governs waste management activities at the NTS will be submitted to the Nevada Division of Environmental Protection to incorporate the requirements for post-closure monitoring. Four CAAs, ranging from No Further Action to Clean Closure, were evaluated for the 92-Acre Area. The CAAs were evaluated on technical merit focusing on performance, reliability, feasibility, safety, and cost. Based on the evaluation of the data used to develop the conceptual site model; a review of past, current, and future operations at the site; and the detailed and comparative analysis of the

  16. Los Alamos National Laboratory Accident Investigation Board Corrective...

    Office of Environmental Management (EM)

    Accident Investigation Board Corrective Action Plan Update Los Alamos National Laboratory Accident Investigation Board Corrective Action Plan Update Topic: Status of the Corrective ...

  17. Proposed Rule Correction, Federal Register, 75 FR 66008, October...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Proposed Rule Correction, Federal Register, 75 FR 66008, October 27, 2010 Proposed Rule Correction, Federal Register, 75 FR 66008, October 27, 2010 Document displays a correction ...

  18. Segmentation-free empirical beam hardening correction for CT

    SciTech Connect (OSTI)

    Schller, Sren; Sawall, Stefan; Stannigel, Kai; Hlsbusch, Markus; Ulrici, Johannes; Hell, Erich; Kachelrie, Marc

    2015-02-15

    Purpose: The polychromatic nature of the x-ray beams and their effects on the reconstructed image are often disregarded during standard image reconstruction. This leads to cupping and beam hardening artifacts inside the reconstructed volume. To correct for a general cupping, methods like water precorrection exist. They correct the hardening of the spectrum during the penetration of the measured object only for the major tissue class. In contrast, more complex artifacts like streaks between dense objects need other techniques of correction. If using only the information of one single energy scan, there are two types of corrections. The first one is a physical approach. Thereby, artifacts can be reproduced and corrected within the original reconstruction by using assumptions in a polychromatic forward projector. These assumptions could be the used spectrum, the detector response, the physical attenuation and scatter properties of the intersected materials. A second method is an empirical approach, which does not rely on much prior knowledge. This so-called empirical beam hardening correction (EBHC) and the previously mentioned physical-based technique are both relying on a segmentation of the present tissues inside the patient. The difficulty thereby is that beam hardening by itself, scatter, and other effects, which diminish the image quality also disturb the correct tissue classification and thereby reduce the accuracy of the two known classes of correction techniques. The herein proposed method works similar to the empirical beam hardening correction but does not require a tissue segmentation and therefore shows improvements on image data, which are highly degraded by noise and artifacts. Furthermore, the new algorithm is designed in a way that no additional calibration or parameter fitting is needed. Methods: To overcome the segmentation of tissues, the authors propose a histogram deformation of their primary reconstructed CT image. This step is essential for the

  19. Weighted SVD algorithm for close-orbit correction and 10 Hz feedback in RHIC

    SciTech Connect (OSTI)

    Liu C.; Hulsart, R.; Marusic, A.; Michnoff, R.; Minty, M.; Ptitsyn, V.

    2012-05-20

    Measurements of the beam position along an accelerator are typically treated equally using standard SVD-based orbit correction algorithms so distributing the residual errors, modulo the local beta function, equally at the measurement locations. However, sometimes a more stable orbit at select locations is desirable. In this paper, we introduce an algorithm for weighting the beam position measurements to achieve a more stable local orbit. The results of its application to close-orbit correction and 10 Hz orbit feedback are presented.

  20. Monthly Progress Report for Corrective Actions 2016

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Progress Reports for Corrective Actions 2016 Monthly Progress Report for Corrective Actions Prescribed in Attachment A of the Settlement Agreement and Stipulated Final Order, Dated January 22, 2016, NO. HWB-14-21 (CO) Waste Isolation Pilot Plant EPA I.D. Number: NM4890139088-TSDF dated August 31, 2016 Monthly Progress Report for Corrective Actions Prescribed in Attachment A of the Settlement Agreement and Stipulated Final Order, Dated January 22, 2016, NO. HWB-14-21 (CO) Waste Isolation Pilot

  1. U.S. Department of Energy Provides Report to Congress on the Demonstration of the Interim Storage of Spent Nuclear Fuel from Decommissioned Nuclear Power Reactor Sites

    Broader source: Energy.gov [DOE]

    Washington D.C. - The U.S. Department of Energy (DOE) today released its Report to Congress on the Demonstration of the Interim Storage of Spent Nuclear Fuel from Decommissioned Nuclear Power...

  2. ARM - Evaluation Product - Corrected Precipitation Radar Moments...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    ProductsCorrected Precipitation Radar Moments in Antenna Coordinates Documentation Use the Data File Inventory tool to view data availability at the file level. Comments? We would...

  3. Model Requests for Access or Correction

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Model-Requests-for-Access-or-Correction Sign In About | Careers | Contact | Investors | bpa.gov Search News & Us Expand News & Us Projects & Initiatives Expand Projects &...

  4. Linux Kernel Error Detection and Correction

    Energy Science and Technology Software Center (OSTI)

    2007-04-11

    EDAC-utils consists fo a library and set of utilities for retrieving statistics from the Linux Kernel Error Detection and Correction (EDAC) drivers.

  5. Electroweak Corrections at the LHC with MCFM

    SciTech Connect (OSTI)

    Campbell, John M.; Wackeroth, Doreen; Zhou, Jia

    2015-07-10

    Electroweak (EW) corrections at the LHC can be enhanced at high energies due to soft/collinear radiation of W and Z bosons, being dominated by Sudakov-like corrections in the form of $\\alpha_W^l\\log^n(Q^2/M_W^2)$ $(n \\le 2l, \\alpha_W = \\alpha/(4\\pi\\sin\\theta_W^2))$ when the energy scale $Q$ enters the TeV regime. Thus, the inclusion of EW corrections in LHC predictions is important for the search of possible signals of new physics in tails of kinematic distributions. EW corrections should also be taken into account in virtue of their comparable size ($\\mathcal{O}(\\alpha)$) to that of higher order QCD corrections ($\\mathcal{O}(\\alpha_s^2)$). We calculated the next-to-leading-order (NLO) weak corrections to the neutral-current (NC) Drell-Yan process, top-quark pair production and di-jet producion, and implemented them in the Monte-Carlo program MCFM. This enables a combined study with the corresponding NLO QCD corrections. We provide both the full NLO weak corrections and their weak Sudakov approximation valid at high energies. The latter is often used for a fast evaluation of weak effects, and having the exact result available as well allows to quantify the validity of the Sudakov approximation.

  6. Detector signal correction method and system

    DOE Patents [OSTI]

    Carangelo, Robert M.; Duran, Andrew J.; Kudman, Irwin

    1995-07-11

    Corrective factors are applied so as to remove anomalous features from the signal generated by a photoconductive detector, and to thereby render the output signal highly linear with respect to the energy of incident, time-varying radiation. The corrective factors may be applied through the use of either digital electronic data processing means or analog circuitry, or through a combination of those effects.

  7. Deep Vadose Zone Treatability Test for the Hanford Central Plateau. Interim Post-Desiccation Monitoring Results, Fiscal Year 2015

    SciTech Connect (OSTI)

    Truex, Michael J.; Strickland, Christopher E.; Oostrom, Martinus; Johnson, Christian D.; Tartakovsky, Guzel D.; Johnson, Timothy C.; Clayton, Ray E.; Chronister, Glen B.

    2015-09-01

    A field test of desiccation is being conducted as an element of the Deep Vadose Zone Treatability Test Program. The active desiccation portion of the test has been completed. Monitoring data have been collected at the field test site during the post-desiccation period and are reported herein. This is an interim data summary report that includes about 4 years of post-desiccation monitoring data. The DOE field test plan proscribes a total of 5 years of post-desiccation monitoring.

  8. BWR Spent Nuclear Fuel Integrity Research and Development Survey for UKABWR Spent Fuel Interim Storage

    SciTech Connect (OSTI)

    Bevard, Bruce Balkcom; Mertyurek, Ugur; Belles, Randy; Scaglione, John M.

    2015-10-01

    The objective of this report is to identify issues and support documentation and identify and detail existing research on spent fuel dry storage; provide information to support potential R&D for the UKABWR (United Kingdom Advanced Boiling Water Reactor) Spent Fuel Interim Storage (SFIS) Pre-Construction Safety Report; and support development of answers to questions developed by the regulator. Where there are gaps or insufficient data, Oak Ridge National Laboratory (ORNL) has summarized the research planned to provide the necessary data along with the schedule for the research, if known. Spent nuclear fuel (SNF) from nuclear power plants has historically been stored on site (wet) in spent fuel pools pending ultimate disposition. Nuclear power users (countries, utilities, vendors) are developing a suite of options and set of supporting analyses that will enable future informed choices about how best to manage these materials. As part of that effort, they are beginning to lay the groundwork for implementing longer-term interim storage of the SNF and the Greater Than Class C (CTCC) waste (dry). Deploying dry storage will require a number of technical issues to be addressed. For the past 4-5 years, ORNL has been supporting the U.S. Department of Energy (DOE) in identifying these key technical issues, managing the collection of data to be used in issue resolution, and identifying gaps in the needed data. During this effort, ORNL subject matter experts (SMEs) have become expert in understanding what information is publicly available and what gaps in data remain. To ensure the safety of the spent fuel under normal and frequent conditions of wet and subsequent dry storage, intact fuel must be shown to: 1.Maintain fuel cladding integrity; 2.Maintain its geometry for cooling, shielding, and subcriticality; 3.Maintain retrievability, and damaged fuel with pinhole or hairline cracks must be shown not to degrade further. Where PWR (pressurized water reactor) information is

  9. Breast tissue decomposition with spectral distortion correction: A postmortem study

    SciTech Connect (OSTI)

    Ding, Huanjun; Zhao, Bo; Baturin, Pavlo; Behroozi, Farnaz; Molloi, Sabee

    2014-10-15

    Purpose: To investigate the feasibility of an accurate measurement of water, lipid, and protein composition of breast tissue using a photon-counting spectral computed tomography (CT) with spectral distortion corrections. Methods: Thirty-eight postmortem breasts were imaged with a cadmium-zinc-telluride-based photon-counting spectral CT system at 100 kV. The energy-resolving capability of the photon-counting detector was used to separate photons into low and high energy bins with a splitting energy of 42 keV. The estimated mean glandular dose for each breast ranged from 1.8 to 2.2 mGy. Two spectral distortion correction techniques were implemented, respectively, on the raw images to correct the nonlinear detector response due to pulse pileup and charge-sharing artifacts. Dual energy decomposition was then used to characterize each breast in terms of water, lipid, and protein content. In the meantime, the breasts were chemically decomposed into their respective water, lipid, and protein components to provide a gold standard for comparison with dual energy decomposition results. Results: The accuracy of the tissue compositional measurement with spectral CT was determined by comparing to the reference standard from chemical analysis. The averaged root-mean-square error in percentage composition was reduced from 15.5% to 2.8% after spectral distortion corrections. Conclusions: The results indicate that spectral CT can be used to quantify the water, lipid, and protein content in breast tissue. The accuracy of the compositional analysis depends on the applied spectral distortion correction technique.

  10. Corrective Action Plan for Corrective Action Unit 424: Area 3 Landfill Complex, Tonopah Test Range, Nevada

    SciTech Connect (OSTI)

    Bechtel Nevada

    1998-08-31

    This corrective action plan provides the closure implementation methods for the Area 3 Landfill Complex, Corrective Action Unit (CAU) 424, located at the Tonopah Test Range. The Area 3 Landfill Complex consists of 8 landfill sites, each designated as a separate corrective action site.

  11. A two-dimensional matrix correction for off-axis portal dose prediction errors

    SciTech Connect (OSTI)

    Bailey, Daniel W.; Kumaraswamy, Lalith; Bakhtiari, Mohammad; Podgorsak, Matthew B.

    2013-05-15

    Purpose: This study presents a follow-up to a modified calibration procedure for portal dosimetry published by Bailey et al. ['An effective correction algorithm for off-axis portal dosimetry errors,' Med. Phys. 36, 4089-4094 (2009)]. A commercial portal dose prediction system exhibits disagreement of up to 15% (calibrated units) between measured and predicted images as off-axis distance increases. The previous modified calibration procedure accounts for these off-axis effects in most regions of the detecting surface, but is limited by the simplistic assumption of radial symmetry. Methods: We find that a two-dimensional (2D) matrix correction, applied to each calibrated image, accounts for off-axis prediction errors in all regions of the detecting surface, including those still problematic after the radial correction is performed. The correction matrix is calculated by quantitative comparison of predicted and measured images that span the entire detecting surface. The correction matrix was verified for dose-linearity, and its effectiveness was verified on a number of test fields. The 2D correction was employed to retrospectively examine 22 off-axis, asymmetric electronic-compensation breast fields, five intensity-modulated brain fields (moderate-high modulation) manipulated for far off-axis delivery, and 29 intensity-modulated clinical fields of varying complexity in the central portion of the detecting surface. Results: Employing the matrix correction to the off-axis test fields and clinical fields, predicted vs measured portal dose agreement improves by up to 15%, producing up to 10% better agreement than the radial correction in some areas of the detecting surface. Gamma evaluation analyses (3 mm, 3% global, 10% dose threshold) of predicted vs measured portal dose images demonstrate pass rate improvement of up to 75% with the matrix correction, producing pass rates that are up to 30% higher than those resulting from the radial correction technique alone. As in

  12. Evaluation of Shear Strength Threshold of Concern for Retrieval of Interim-Stored K-Basin Sludge in the Hanford Site

    SciTech Connect (OSTI)

    Onishi, Yasuo; Yokuda, Satoru T.; Schmidt, Andrew J.

    2010-11-01

    K-Basin sludge will be recovered into the Sludge Transport and Storage Containers (STSCs) and will be stored in the T Plant for interim storage (at least 10 years). Long-term sludge storage tests conducted by Pacific Northwest National Laboratory show that high uranium content K Basin sludge can self-cement and form a strong sludge with a bulk shear strength of up to 65 kPa. Some of this sludge has "paste" and "chunks" with shear strengths of approximately 3~5 kPa and 380 ~ 770 kPa, respectively. High uranium content sludge samples subjected to hydrothermal testing (e.g., 185°C, 10 h) have been observed to form agglomerates with a shear strength up to 170 kPa. After interim storage at T Plant, the sludge in the STSCs will be mobilized by water jets impinging the sludge. The objective of the evaluation was to determine the range of sludge shear strength for which there is high confidence that a water-jet retrieval system can mobilize stored K-Basin sludge from STSCs. The shear strength at which the sludge can be retrieved is defined as the "shear strength threshold of concern." If the sludge shear strength is greater than the value of the shear strength threshold of concern, a water-jet retrieval system will be unlikely to mobilize the sludge up to the container’s walls. The shear strength threshold of concern can be compared with the range of possible shear strengths of K-Basin stored sludge to determine if the current post interim-storage, water-jet retrieval method is adequate. Fourteen effective cleaning radius (ECR) models were reviewed, and their validity was examined by applying them to Hanford 241-SY-101 and 241-AZ-101 Tanks to reproduce the measured ECR produced by the mixer pumps. The validation test identified that the Powell-3 and Crowe-2 ECR models are more accurate than other ECR models reviewed. These ECR models were used to address a question as to whether the effective cleaning radius of a water jet is sufficient or if it can be readily expanded

  13. RCRA corrective action determination of no further action

    SciTech Connect (OSTI)

    1996-06-01

    On July 27, 1990, the U.S. Environmental Protection Agency (EPA) proposed a regulatory framework (55 FR 30798) for responding to releases of hazardous waste and hazardous constituents from solid waste management units (SWMUs) at facilities seeking permits or permitted under the Resource Conservation and Recovery Act (RCRA). The proposed rule, `Corrective Action for Solid Waste Management Units at Hazardous Waste Facilities`, would create a new Subpart S under the 40 CFR 264 regulations, and outlines requirements for conducting RCRA Facility Investigations, evaluating potential remedies, and selecting and implementing remedies (i.e., corrective measures) at RCRA facilities. EPA anticipates instances where releases or suspected releases of hazardous wastes or constituents from SWMUs identified in a RCRA Facility Assessment, and subsequently addressed as part of required RCRA Facility Investigations, will be found to be non-existent or non-threatening to human health or the environment. Such releases may require no further action. For such situations, EPA proposed a mechanism for making a determination that no further corrective action is needed. This mechanism is known as a Determination of No Further Action (DNFA) (55 FR 30875). This information Brief describes what a DNFA is and discusses the mechanism for making a DNFA. This is one of a series of Information Briefs on RCRA corrective action.

  14. Environmental monitoring plan for the Niagara Falls Storage Site and the Interim Waste Containment Facility

    SciTech Connect (OSTI)

    Not Available

    1986-04-01

    As part of the US Department of Energy's (DOE) Surplus Facility Management Program (SFMP), the Niagara Falls Storage Site (NFSS) is undergoing remedial action. Vicinity properties adjacent to and near the site are being cleaned up as part of DOE's Formerly Utilized Sites Remedial Action Program (FUSRAP). These programs are a DOE effort to clean up low-level radioactive waste resulting from the early days of the nation's atomic energy program. Radioactively contaminated waste from these remedial action activities are being stored at the NFSS in an interim waste containment facility (IWCF). When the remedial actions and IWCF are completed in 1986, activities at the site will be limited to waste management. The monitoring program was prepared in accordance with DOE Order 5484.1 and is designed to determine the contribution of radioactivity from the site to the environs and to demonstrate compliance with applicable criteria. Major elements of this program will also supplement other monitoring requirements including the performance monitoring system for the IWCF and the closure/post-closure plan. Emphasis will be directed toward the sampling and analysis of groundwater, surface water, air and sediment for parameters which are known to be present in the material stored at the site. The monitoring program will employ a phased approach whereby the first 5 years of data will be evaluated, and the program will be reviewed and modified as necessary. 17 refs., 10 figs., 3 tabs.

  15. Evaluation of Dynamic Behavior of Pile Foundations for Interim Storage Facilities Through Geotechnical Centrifuge Tests

    SciTech Connect (OSTI)

    Shizuo Tsurumaki; Hiroyuki Watanabe; Akira Tateishi; Kenichi Horikoshi; Shunichi Suzuki

    2002-07-01

    In Japan, there is a possibility that interim storage facilities for recycled nuclear fuel resources may be constructed on quaternary layers, rather than on hard rock. In such a case, the storage facilities need to be supported by pile foundations or spread foundations to meet the required safety level. The authors have conducted a series of experimental studies on the dynamic behavior of storage facilities supported by pile foundations. A centrifuge modeling technique was used to satisfy the required similitude between the reduced size model and the prototype. The centrifuge allows a high confining stress level equivalent to prototype deep soils to be generated (which is considered necessary for examining complex pile-soil interactions) as the soil strength and the deformation are highly dependent on the confining stress. The soil conditions were set at as experimental variables, and the results are compared. Since 2000, the Nuclear Power Engineering Corporation (NUPEC) has been conducting these research tests under the auspices on the Ministry of Economy, Trade and Industry of Japan. (authors)

  16. Power Transfer Potential to the Southeast in Response to a Renewable Portfolio Standard: Interim Report 1

    SciTech Connect (OSTI)

    Hadley, Stanton W; Key, Thomas S

    2009-03-01

    The power transfer potential for bringing renewable energy into the Southeast in response to a renewable portfolio standard (RPS) will depend not only on available transmission capacity but also on electricity supply and demand factors. This interim report examines how the commonly used EIA NEMS and EPRI NESSIE energy equilibrium models are considering such power transfers. Using regional estimates of capacity expansion and demand, a base case for 2008, 2020 and 2030 are compared relative to generation mix, renewable deployments, planned power transfers, and meeting RPS goals. The needed amounts of regional renewable energy to comply with possible RPS levels are compared to inter-regional transmission capacities to establish a baseline available for import into the Southeast and other regions. Gaps in the renewable generation available to meet RPS requirements are calculated. The initial finding is that the physical capability for transferring renewable energy into the SE is only about 10% of what would be required to meet a 20% RPS. Issues that need to be addressed in future tasks with respect to modeling are the current limitations for expanding renewable capacity and generation in one region to meet the demand in another and the details on transmission corridors required to deliver the power.

  17. Hazelwood Interim Storage Site environmental surveillance report for calendar year 1993

    SciTech Connect (OSTI)

    Not Available

    1994-06-01

    This report summarizes the results of environmental surveillance activities conducted at the Hazelwood Interim Storage Site (HISS) during calendar year 1993. It includes an overview of site operations, the basis for monitoring for radioactive and non-radioactive parameters, summaries of environmental program at HISS, a summary of the results, and the calculated hypothetical radiation dose to the offsite population. Environmental surveillance activities were conducted in accordance with the site environmental monitoring plan, which describes the rationale and design criteria for the surveillance program, the frequency of sampling and analysis, specific sampling and analysis procedures, and quality assurance requirements. The US Department of Energy (DOE) began environmental monitoring of HISS in 1984, when the site was assigned to DOE by Congress through the energy and Water Development Appropriations Act and subsequent to DOE`s Formerly Utilized Sites Remediation Action Program (FUSRAP). Contamination at HISS originated from uranium processing work conducted at Mallinckrodt Chemical Works at the St. Louis Downtown Site (SLDS) from 1942 through 1957.

  18. Interim report:feasibility of microscale glucose reforming for renewable hydrogen.

    SciTech Connect (OSTI)

    Norman, Kirsten (New Mexico Institute of Mining and Technology, Socorro, NM)

    2007-03-01

    Micro-scale aqueous steam reforming of glucose is suggested as a novel method of H{sub 2} production for micro fuel cells. Compact fuel cell systems are a viable alternative to batteries as a portable electrical power source. Compared with conventional lithium polymer batteries, hydrocarbon powered fuel cells are smaller, weigh less, and have a much higher energy density. The goal of this project is to develop a hydrocarbon powered microfuel processor capable of driving an existing microfuel cell, and this interim report provides a summary of the engineering information for microscale reforming of carbohydrates and the summarizes the work completed as of September 2006. Work on this program will continue. Gas analysis of the gas evolved from glucose breakdown using a quadrupole mass spectrometer is now possible due do significant modifications to the vacuum chamber and to the mass spectrometer electronics. Effective adhesion of Pt/Al{sub 2}O{sub 3} to 316SS microstructured catalyst plates is still under investigation. Electrophoretic and dip coat methods of catalyst deposition have produced coatings with poor adhesion and limited available Pt surface area.

  19. Hydrogeology of the 200 Areas low-level burial grounds: An interim report: Volume 1, Text

    SciTech Connect (OSTI)

    Last, G.V.; Bjornstad, B.N.; Bergeron, M.P.; Wallace, D.W.; Newcomer, D.R.; Schramke, J.A.; Chamness, M.A.; Cline, C.S.; Airhart, S.P.; Wilbur, J.S.

    1989-01-01

    This report presents information derived from the installation of 35 ground-water monitoring wells around six low-level radioactive/hazardous waste burial grounds located in the 200 Areas of the Hanford Site in southeastern Washington State. This information was collected between May 20, 1987 and August 1, 1988. The contents of this report have been divided into two volumes. This volume contains the main text. Volume 2 contains the appendixes, including data and supporting information that verify content and results found in the main text. This report documents information collected by the Pacific Northwest Laboratory at the request of Westinghouse Hanford Company. Presented in this report are the preliminary interpretations of the hydrogeologic environment of six low-level burial grounds, which comprise four waste management areas (WMAs) located in the 200 Areas of the Hanford Site. This information and its accompanying interpretations were derived from sampling and testing activities associated with the construction of 35 ground-water monitoring wells as well as a multitude of previously existing boreholes. The new monitoring wells were installed as part of a ground-water monitoring program initiated in 1986. This ground-water monitoring program is based on requirements for interim status facilities in compliance with the Resource Conservation and Recovery Act (1976).

  20. OVERVIEW OF CRITERIA FOR INTERIM WET & DRY STORAGE OF RESEARCH REACTOR SPENT NUCLEAR FUEL

    SciTech Connect (OSTI)

    Sindelar, R.; Vinson, D.; Iyer, N.; Fisher, D.

    2010-11-03

    Following discharge from research reactors, spent nuclear fuel may be stored 'wet' in water pools or basins, or it may be stored 'dry' in various configurations including non-sealed or sealed containers until retrieved for ultimate disposition. Interim safe storage practices are based on avoiding degradation to the fuel that would impact functions related to safety. Recommended practices including environmental controls with technical bases, are outlined for wet storage and dry storage of aluminum-clad, aluminum-based research reactor fuel. For wet storage, water quality must be maintained to minimize corrosion degradation of aluminum fuel. For dry storage, vented canister storage of aluminum fuel readily provides a safe storage configuration. For sealed dry storage, drying must be performed so as to minimize water that would cause additional corrosion and hydrogen generation. Consideration must also be given to the potential for radiolytically-generated hydrogen from the bound water in the attendant oxyhydroxides on aluminum fuel from reactor operation for dry storage systems.

  1. Hazelwood Interim Storage Site annual environmental report for calendar year 1990, Hazelwood, Missouri

    SciTech Connect (OSTI)

    Not Available

    1991-08-01

    Environmental monitoring of the US Department of Energy's (DOE) Hazelwood Interim Storage Site (HISS) and surrounding area began in 1984. This document describes the environmental monitoring program, the program's implementation, and the monitoring results for 1990. HISS was assigned to DOE as part of the decontamination research and development project authorized by Congress under the 1984 Energy and Water Appropriations Act. DOE placed responsibility for HISS under the Formerly Utilized Sites Remedial Action Program, a DOE program to decontaminate or otherwise control sites where residual radioactive materials remain from the early years of the nation's atomic energy program or from commercial operations causing conditions that Congress has authorized DOE to remedy. Environmental monitoring programs have been established at DOE-managed sites to confirm adherence to DOE environmental protection policies; to monitor the potential effects of site operations on human health and the environment; and to ensure compliance with legal and regulatory requirements imposed by federal, state, and local agencies. Environmental monitoring programs are developed and implemented on a site-specific basis to reflect facility characteristics, applicable regulations, hazard potential, quantities and concentrations of materials released, extent and use of affected land and water, and local public interest or concern.

  2. SAMPLE RESULTS FROM THE INTERIM SALT DISPOSITION PROGRAM MACROBATCH 8 TANK 21H QUALIFICATION SAMPLES

    SciTech Connect (OSTI)

    Peters, T. B.; Washington, A. L.

    2015-01-13

    Savannah River National Laboratory (SRNL) analyzed samples from Tank 21H in support of qualification of Macrobatch (Salt Batch) 8 for the Interim Salt Disposition Program (ISDP). An Actinide Removal Process (ARP) and several Extraction-Scrub- Strip (ESS) tests were also performed. This document reports characterization data on the samples of Tank 21H as well as simulated performance of ARP and the Modular Caustic Side Solvent Extraction (CSSX) Unit (MCU). No issues with the projected Salt Batch 8 strategy are identified. A demonstration of the monosodium titanate (MST) (0.2 g/L) removal of strontium and actinides provided acceptable average decontamination factors for plutonium of 2.62 (4 hour) and 2.90 (8 hour); and average strontium decontamination factors of 21.7 (4 hour) and 21.3 (8 hour). These values are consistent with results from previous salt batch ARP tests. The two ESS tests also showed acceptable performance with extraction distribution ratios (D{sub (Cs)}) values of 52.5 and 50.4 for the Next Generation Solvent (NGS) blend (from MCU) and NGS (lab prepared), respectively. These values are consistent with results from previous salt batch ESS tests. Even though the performance is acceptable, SRNL recommends that a model for predicting extraction behavior for cesium removal for the blended solvent and NGS be developed in order to improve our predictive capabilities for the ESS tests.

  3. Resource Conservation and Recovery Act (RCRA) Closure Plan Summary for Interim reasctive Waste Treatment Area (IRWTA)

    SciTech Connect (OSTI)

    Collins, E.T.

    1997-07-01

    This closure plan has been prepared for the interim Reactive Waste Treatment Area (IRWT'A) located at the Y-12 Pkmt in oak Ridge, Tennessee (Environmental Protection Agency [EPA] Identification TN 389-009-0001). The actions required to achieve closure of the IRWTA are outlined in this plan, which is being submitted in accordance with Tennessee Ruie 1200- 1-1 1-.0S(7) and Title 40, Code of Federal Regulations (CFR), Part 265, Subpart G. The IRWTA was used to treat waste sodium and potassium (NaK) that are regulated by the Resource Conservation and Recovery Act (RCRA). The location of the IRWT'A is shown in Figures 1 and 2, and a diagram is shown in Figure 3. This pkm details all steps that wdi be petiormed to close the IRWTA. Note that this is a fmai ciosure.and a diagram is shown in Figure 3. This pkm details all steps that wdi be petiormed to close the IRWTA. Note that this is a fmai ciosure.

  4. Online Monitoring Technical Basis and Analysis Framework for Emergency Diesel Generators - Interim Report for FY 2013

    SciTech Connect (OSTI)

    Binh T. Pham; Nancy J. Lybeck; Vivek Agarwal

    2012-12-01

    The Light Water Reactor Sustainability program at Idaho National Laboratory is actively conducting research to develop and demonstrate online monitoring capabilities for active components in existing nuclear power plants. Idaho National Laboratory and the Electric Power Research Institute are working jointly to implement a pilot project to apply these capabilities to emergency diesel generators and generator step-up transformers. The Electric Power Research Institute Fleet-Wide Prognostic and Health Management Software Suite will be used to implement monitoring in conjunction with utility partners: Braidwood Generating Station (owned by Exelon Corporation) for emergency diesel generators, and Shearon Harris Nuclear Generating Station (owned by Duke Energy Progress) for generator step-up transformers. This report presents monitoring techniques, fault signatures, and diagnostic and prognostic models for emergency diesel generators. Emergency diesel generators provide backup power to the nuclear power plant, allowing operation of essential equipment such as pumps in the emergency core coolant system during catastrophic events, including loss of offsite power. Technical experts from Braidwood are assisting Idaho National Laboratory and Electric Power Research Institute in identifying critical faults and defining fault signatures associated with each fault. The resulting diagnostic models will be implemented in the Fleet-Wide Prognostic and Health Management Software Suite and tested using data from Braidwood. Parallel research on generator step-up transformers was summarized in an interim report during the fourth quarter of fiscal year 2012.

  5. Improved NLDAS-2 Noah-simulated Hydrometeorological Products with an Interim Run

    SciTech Connect (OSTI)

    Xia, Youlong; Peter-Lidard, Christa; Huang, Maoyi; Wei, Helin; Ek, Michael

    2015-02-28

    In NLDAS-2 Noah simulation, the NLDAS team introduced an intermediate fix suggested by Slater et al. (2007) and Livneh et al. (2010) to reduce large sublimation. The fix is used to constraint surface exchange coefficient (CH) using CH =CHoriginal x max (1.0-RiB/0.5, 0.05) when atmospheric boundary layer is stable. RiB is Richardson number. In NLDAS-2 Noah version, this fix was used for all stable cases including snow-free grid cells. In this study, we simply applied this fix to the grid cells in which both stable atmospheric boundary layer and snow exist simultaneously excluding the snow-free grid cells as we recognize that the fix constraint in NLDAS-2 is too strong. We make a 31-year (1979-2009) Noah NLDAS-2 interim (NoahI) run. We use observed streamflow, evapotranspiration, land surface temperature, soil temperature, and ground heat flux to evaluate the results simulated from NoahI and make the reasonable comparison with those simulated from NLDAS-2 Noah (Xia et al., 2012). The results show that NoahI has the same performance as Noah does for snow water equivalent simulation. However, NoahI significantly improved the other hydrometeorological products simulation as described above when compared to Noah and the observations. This simple modification is being installed to the next Noah version. The hydrometeorological products simulated from NoahI will be staged on NCEP public server for the public in future.

  6. Interim Report of the Commission to Review the Effectiveness of the National Energy Laboratories

    SciTech Connect (OSTI)

    Cohon, Jared L.; Glauthier, T. J.; Augustine, Norman R.; Austin, Wanda M.; Elachi, Charles; Fleury, Paul A.; Hockfield, Susan J.; Meserve, Richard A.; Murray, Cherry A.

    2015-02-27

    The Commission to Review the Effectiveness of the National Energy Laboratories was charged by Congress in January 2014 to evaluate the mission, capabilities, size, performance, governance, and agency oversight of the 17 Department of Energy (DOE) laboratories. Given the incredibly broad scope and aggressive timeline (the original deadline was February 2015), the Secretary of Energy and Congress agreed to split the task into two phases. This interim report contains the preliminary observations and recommendations gleaned from Phase 1 of the study, which consisted of a literature review; visits to five of the National Laboratories; semi-structured interviews with staff from across the National Laboratories, DOE, other Federal agencies, companies, other non-governmental organizations, and additional interested parties; and presentations at monthly public Commission meetings. The Commission notes that the purpose of the National Laboratories is to provide critical capabilities and facilities in service of DOE’s mission and the needs of the broader national and international science and technology (S&T) community, including other Federal agencies, academia, and private industry. The National Laboratories are successfully fulfilling that mission today. While the Commission believes significant improvements can be made to many aspects of DOE management and governance of the laboratories, those issues do not detract from the National Laboratories’ remarkable contributions to the American public. In Phase 2 the Commission will focus on ways to make the process of carrying out their missions more efficient and effective.

  7. Hazelwood Interim Storage Site environmental report for calendar year 1992, 9200 Latty Avenue, Hazelwood, Missouri

    SciTech Connect (OSTI)

    Not Available

    1993-05-01

    This report describes the environmental surveillance program at the Hazelwood Interim storage Site (HISS) and surrounding area, provides the results for 1992, and discusses applicable environmental standards and requirements with which the results were compared. HISS is located in eastern Missouri in the City of Hazelwood (St. Louis County) and occupies approximately 2.2 ha (5.5 acres). Environmental monitoring of HISS began in 1984 when the site was assigned to the US Department of Energy (DOE) as part of the decontamination research and development project authorized by Congress under the 1984 Energy and Water Development Appropriations Act. DOE placed responsibility for HISS under the Formerly Utilized Sites Remedial Action Program (FUSRAP), which was established to identify and decontaminate or otherwise control sites where residual radioactive materials remain from the early years of the nation`s atomic energy program or from commercial operations causing conditions that Congress has authorized DOE to remedy. In 1992 there were no environmental occurrences or unplanned contaminant releases as defined in DOE requirements and in the Superfund Amendment and Reauthorization Act (SARA) Title III of CERCLA.

  8. Online Monitoring Technical Basis and Analysis Framework for Large Power Transformers; Interim Report for FY 2012

    SciTech Connect (OSTI)

    Nancy J. Lybeck; Vivek Agarwal; Binh T. Pham; Heather D. Medema; Kirk Fitzgerald

    2012-09-01

    The Light Water Reactor Sustainability program at Idaho National Laboratory (INL) is actively conducting research to develop and demonstrate online monitoring (OLM) capabilities for active components in existing Nuclear Power Plants. A pilot project is currently underway to apply OLM to Generator Step-Up Transformers (GSUs) and Emergency Diesel Generators (EDGs). INL and the Electric Power Research Institute (EPRI) are working jointly to implement the pilot project. The EPRI Fleet-Wide Prognostic and Health Management (FW-PHM) Software Suite will be used to implement monitoring in conjunction with utility partners: the Shearon Harris Nuclear Generating Station (owned by Duke Energy for GSUs, and Braidwood Generating Station (owned by Exelon Corporation) for EDGs. This report presents monitoring techniques, fault signatures, and diagnostic and prognostic models for GSUs. GSUs are main transformers that are directly connected to generators, stepping up the voltage from the generator output voltage to the highest transmission voltages for supplying electricity to the transmission grid. Technical experts from Shearon Harris are assisting INL and EPRI in identifying critical faults and defining fault signatures associated with each fault. The resulting diagnostic models will be implemented in the FW-PHM Software Suite and tested using data from Shearon-Harris. Parallel research on EDGs is being conducted, and will be reported in an interim report during the first quarter of fiscal year 2013.

  9. Perimeter security for Minnesota correctional facilities

    SciTech Connect (OSTI)

    Crist, D.; Spencer, D.D.

    1996-12-31

    For the past few years, the Minnesota Department of Corrections, assisted by Sandia National Laboratories, has developed a set of standards for perimeter security at medium, close, and maximum custody correctional facilities in the state. During this process, the threat to perimeter security was examined and concepts about correctional perimeter security were developed. This presentation and paper will review the outcomes of this effort, some of the lessons learned, and the concepts developed during this process and in the course of working with architects, engineers and construction firms as the state upgraded perimeter security at some facilities and planned new construction at other facilities.

  10. Wayne Interim Storage Site environmental report for calendar year 1992, 868 Black Oak Ridge Road, Wayne, New Jersey. Formerly Utilized Sites Remedial Action Program (FUSRAP)

    SciTech Connect (OSTI)

    Not Available

    1993-05-01

    This report describes the environmental surveillance program at the Wayne Interim Storage Site (WISS) and provides the results for 1992. The fenced, site, 32 km (20 mi) northwest of Newark, New Jersey, was used between 1948 and 1971 for commercial processing of monazite sand to separate natural radioisotopes - predominantly thorium. Environmental surveillance of WISS began in 1984 in accordance with Department of Energy (DOE) Order 5400.1 when Congress added the site to DOE`s Formerly Utilized Sites Remedial Action Program (FUSRAP). The environmental surveillance program at WISS includes sampling networks for radon and thoron in air; external gamma radiation exposure; radium-226, radium-228, thorium-230, thorium-232, total uranium, and several chemicals in surface water and sediment; and total uranium, radium-226, radium-228, thorium-230, thorium-232, and organic and inorganic chemicals in groundwater. Monitoring results are compared with applicable Environmental Protection Agency (EPA) and state standards, DOE derived concentration guides (DCGs), dose limits, and other DOE requirements. This monitoring program assists in fulfilling the DOE policy of measuring and monitoring effluents from DOE activities and calculating hypothetical doses. Results for environmental surveillance in 1992 show that the concentrations of all radioactive and most chemical contaminants were below applicable standards.

  11. Assessing the Security Vulnerabilities of Correctional Facilities

    SciTech Connect (OSTI)

    Morrison, G.S.; Spencer, D.S.

    1998-10-27

    The National Institute of Justice has tasked their Satellite Facility at Sandia National Laboratories and their Southeast Regional Technology Center in Charleston, South Carolina to devise new procedures and tools for helping correctional facilities to assess their security vulnerabilities. Thus, a team is visiting selected correctional facilities and performing vulnerability assessments. A vulnerability assessment helps to identi~ the easiest paths for inmate escape, for introduction of contraband such as drugs or weapons, for unexpected intrusion fi-om outside of the facility, and for the perpetration of violent acts on other inmates and correctional employees, In addition, the vulnerability assessment helps to quantify the security risks for the facility. From these initial assessments will come better procedures for performing vulnerability assessments in general at other correctional facilities, as well as the development of tools to assist with the performance of such vulnerability assessments.

  12. Quantum error-correcting codes and devices

    DOE Patents [OSTI]

    Gottesman, Daniel

    2000-10-03

    A method of forming quantum error-correcting codes by first forming a stabilizer for a Hilbert space. A quantum information processing device can be formed to implement such quantum codes.

  13. Corrective Action Investigation Plan for Corrective Action Unit 371: Johnnie Boy Crater and Pin Stripe Nevada Test Site, Nevada, Revision 0

    SciTech Connect (OSTI)

    Patrick Matthews

    2009-02-01

    Corrective Action Unit (CAU) 371 is located in Areas 11 and 18 of the Nevada Test Site, which is approximately 65 miles northwest of Las Vegas, Nevada. Corrective Action Unit 371 is comprised of the two corrective action sites (CASs) listed below: • 11-23-05, Pin Stripe Contamination Area • 18-45-01, U-18j-2 Crater (Johnnie Boy) These sites are being investigated because existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend corrective action alternatives. Additional information will be obtained by conducting a corrective action investigation before evaluating corrective action alternatives and selecting the appropriate corrective action for each CAS. The results of the field investigation will support a defensible evaluation of viable corrective action alternatives that will be presented in the Corrective Action Decision Document. The sites will be investigated based on the data quality objectives (DQOs) developed on November 19, 2008, by representatives of the Nevada Division of Environmental Protection; U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office; Stoller-Navarro Joint Venture; and National Security Technologies, LLC. The DQO process was used to identify and define the type, amount, and quality of data needed to develop and evaluate appropriate corrective actions for CAU 371. Appendix A provides a detailed discussion of the DQO methodology and the DQOs specific to each CAS. The scope of the corrective action investigation for CAU 371 includes the following activities: • Move surface debris and/or materials, as needed, to facilitate sampling. • Conduct radiological surveys. • Measure in situ external dose rates using thermoluminescent dosimeters or other dose measurement devices. • Collect and submit environmental samples for laboratory analysis to determine internal dose rates. • Combine internal and external dose rates to determine whether total

  14. Corrective Action Plan for Environmenta' Management Headquarters

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Corrective Action Plan for Environmenta' Management Headquarters Phase 2: Radiological Release Event at the Waste Isolation Pilot Plant on February 14~ 2014 Washington, DC 20585 August 2015 Corrective Action Plan for Environmental Management Headquarters Phase 2: Radiological Release Event at the Waste Isolation Pilot Plant on February 14, 2014 Deputy Assistant Secretary for Safety, Security, and Quality Programs Environmental Management Approved by: Monica Regalbuto Assistant Secretary for

  15. Detector signal correction method and system

    DOE Patents [OSTI]

    Carangelo, R.M.; Duran, A.J.; Kudman, I.

    1995-07-11

    Corrective factors are applied so as to remove anomalous features from the signal generated by a photoconductive detector, and to thereby render the output signal highly linear with respect to the energy of incident, time-varying radiation. The corrective factors may be applied through the use of either digital electronic data processing means or analog circuitry, or through a combination of those effects. 5 figs.

  16. Re: Corrected Memorandum Summarizing Ex Parte Communication

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    September 25, 2014 To: expartecommunication@hq.doe.gov (sent via email) Re: Corrected Memorandum Summarizing Ex Parte Communication This memorandum is submitted to revise and correct our earlier memorandum submitted on September 23 rd . On September 12, 2014, representatives of the American Gas Association (AGA) met with staff of the U.S. Department of Energy (DOE) to share and discuss the results of a national survey of builders and contractors designed to identify the likely rates of fuel

  17. Environmental Management Headquarters Corrective Action Plan - Radiological

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Release Phase II | Department of Energy II Environmental Management Headquarters Corrective Action Plan - Radiological Release Phase II The purpose of this Corrective Action Plan (CAP) is to specify U.S. Department of Energy (DOE) actions for addressing Office of Environmental Management (EM) Headquarters (HQ) issues identified in the Accident Investigation Report for the Phase 2: Radiological Release Event at the Waste Isolation Pilot Plant (WIPP) on February 14, 2014. The report identified

  18. CORRECTION SYSTEMS UPGRADE FOR THE SNS RING.

    SciTech Connect (OSTI)

    PAPAPHILIPPOU,Y.; GARDNER,C.J.; LEE,Y.Y.; WEI,J.

    2001-06-18

    In view of the changes in the design of the SNS ring from the original FODO lattice [l] to the 220m hybrid lattice [2] and finally 1.3GeV compatible 248m ring [3], complementary studies have been undertaken, in order to upgrade its correction packages. We review the evolution of the correction systems and present the accelerator physics studies for the adopted schemes and powering plan.

  19. Real time detection and correction of distribution feeder operational problems

    SciTech Connect (OSTI)

    Subramanian, A.K.; Huang, J.C.

    1995-12-31

    The paper presents a new technique that detects and corrects distribution operational problems using closed loop control of substation transformers, capacitors and reactors by an online computer. This allows the distribution system to be operated close to its capacity without sacrificing the quality of power supply. Such operations help defer the additional cost of installing new substations. The technique integrates the Distribution Feeder Analysis (DFA) and the Distribution Substation Control (DSC) functions to achieve this. The DFA function provides the topology and power flow results for the feeders using the substation real time measurements. It does not require feeder section measurements. The realtime feeder results are used in detecting any currently existing feeder operational problems such as feeder section voltages and currents outside their limits. The detected feeder problems are transformed into substation distribution bus objectives and then corrected by the DSC function using controls available at the substation. The DSC function has been performing successfully for several years at Potomac Electric Power Company (PEPCO) in Washington, D.C. It uses a closed loop control scheme that controls the substation transformer taps and shunt capacitor and reactor breakers and optimizes the substation operation. By combining the DFA and DSC functions into a single function and with proper transformation of feeder problems into substation objectives, a new closed loop control scheme for the substation controls is achieved. This scheme corrects the detected feeder problems and optimizes the substation operation. This technique is implemented and tested using the actual substation and feeder models of PEPCO.

  20. The correction of linear lattice gradient errors using an AC dipole

    SciTech Connect (OSTI)

    Wang,G.; Bai, M.; Litvinenko, V.N.; Satogata, T.

    2009-05-04

    Precise measurement of optics from coherent betatron oscillations driven by ac dipoles have been demonstrated at RHIC and the Tevatron. For RHIC, the observed rms beta-beat is about 10%. Reduction of beta-beating is an essential component of performance optimization at high energy colliders. A scheme of optics correction was developed and tested in the RHIC 2008 run, using ac dipole optics for measurement and a few adjustable trim quadruples for correction. In this scheme, we first calculate the phase response matrix from the. measured phase advance, and then apply singular value decomposition (SVD) algorithm to the phase response matrix to find correction quadruple strengths. We present both simulation and some preliminary experimental results of this correction.

  1. Sample Results From The Interim Salt Disposition Program Macrobatch 7 Tank 21H Qualification Samples

    SciTech Connect (OSTI)

    Peters, T. B.; Washington, A. L. II

    2013-08-08

    Savannah River National Laboratory (SRNL) analyzed samples from Tank 21H in support of qualification of Macrobatch (Salt Batch) 7 for the Interim Salt Disposition Program (ISDP). An ARP and several ESS tests were also performed. This document reports characterization data on the samples of Tank 21H as well as simulated performance of ARP/MCU. No issues with the projected Salt Batch 7 strategy are identified, other than the presence of visible quantities of dark colored solids. A demonstration of the monosodium titanate (0.2 g/L) removal of strontium and actinides provided acceptable 4 hour average decontamination factors for Pu and Sr of 3.22 and 18.4, respectively. The Four ESS tests also showed acceptable behavior with distribution ratios (D(Cs)) values of 15.96, 57.1, 58.6, and 65.6 for the MCU, cold blend, hot blend, and Next Generation Solvent (NGS), respectively. The predicted value for the MCU solvent was 13.2. Currently, there are no models that would allow a prediction of extraction behavior for the other three solvents. SRNL recommends that a model for predicting extraction behavior for cesium removal for the blended solvent and NGS be developed. While no outstanding issues were noted, the presence of solids in the samples should be investigated in future work. It is possible that the solids may represent a potential reservoir of material (such as potassium) that could have an impact on MCU performance if they were to dissolve back into the feed solution. This salt batch is intended to be the first batch to be processed through MCU entirely using the new NGS-MCU solvent.

  2. Interim report spent nuclear fuel retrieval system fuel handling development testing

    SciTech Connect (OSTI)

    Ketner, G.L.; Meeuwsen, P.V.; Potter, J.D.; Smalley, J.T.; Baker, C.P.; Jaquish, W.R.

    1997-06-01

    Fuel handling development testing was performed in support of the Fuel Retrieval System (FRS) Sub-Project at the Hanford Site. The project will retrieve spent nuclear fuel, clean and remove fuel from canisters, repackage fuel into baskets, and load fuel into a multi-canister overpack (MCO) for vacuum drying and interim dry storage. The FRS is required to retrieve basin fuel canisters, clean fuel elements sufficiently of uranium corrosion products (or sludge), empty fuel from canisters, sort debris and scrap from whole elements, and repackage fuel in baskets in preparation for MCO loading. The purpose of fuel handling development testing was to examine the systems ability to accomplish mission activities, optimization of equipment layouts for initial process definition, identification of special needs/tools, verification of required design changes to support performance specification development, and validation of estimated activity times/throughput. The test program was set up to accomplish this purpose through cold development testing using simulated and prototype equipment; cold demonstration testing using vendor expertise and systems; and graphical computer modeling to confirm feasibility and throughput. To test the fuel handling process, a test mockup that represented the process table was fabricated and installed. The test mockup included a Schilling HV series manipulator that was prototypic of the Schilling Hydra manipulator. The process table mockup included the tipping station, sorting area, disassembly and inspection zones, fuel staging areas, and basket loading stations. The test results clearly indicate that the Schilling Hydra arm cannot effectively perform the fuel handling tasks required unless it is attached to some device that can impart vertical translation, azimuth rotation, and X-Y translation. Other test results indicate the importance of camera locations and capabilities, and of the jaw and end effector tool design. 5 refs., 35 figs., 3 tabs.

  3. 1986 Federal Interim Storage fee study: a technical and economic analysis

    SciTech Connect (OSTI)

    Not Available

    1986-09-01

    JAI examined alternative methods for structuring charges for federal interim storage (FIS) services and concluded that the combined interests of the Department and the users would be best served, and costs most appropriately recovered, by a two-part fee involving an Initial Payment upon execution of a contract for FIS services followed by a Final Payment upon delivery of the spent fuel to the Department. The Initial Payment would be an advance payment covering the pro rata share of preoperational costs, including (1) the capital costs of the required transfer facilities and storage area, (2) development costs, (3) government administrative costs including storage fund management, (4) impact aid payments made in accordance with Section 136(e) of the Act, and (5) module costs (i.e., storage casks, drywells or silos). The Final Payment would be made at the time of delivery of the spent fuel to the Department and would be calculated to cover the sum of the following: (1) any under- or over-estimation in the costs used to calculate the Initial Payment of the fee (including savings due to rod consolidation), and (2) the total estimated cost of operation and decommissioning of the FIS facilities (including government administrative costs, storage fund management and impact aid). The module costs were included in the Initial Payment to preclude the possible need to obtain appropriations for federal funds to support the purchase of the modules in advance of receipt of the Final Payment. Charges for the transport of spent fuel from the reactor site to FIS facilities would be separately assessed at actual cost since these will be specific to each reactor site and destination.

  4. Interim report on the Global Design Effort Global International Linear Collider (ILC) R&D

    SciTech Connect (OSTI)

    Harrison, M.

    2011-04-30

    The International Linear Collider: A Technical Progress Report marks the halfway point towards the Global Design Effort fulfilling its mandate to follow up the ILC Reference Design Report with a more optimised Technical Design Report (TDR) by the end of 2012. The TDR will be based on much of the work reported here and will contain all the elements needed to propose the ILC to collaborating governments, including a technical design and implementation plan that are realistic and have been better optimised for performance, cost and risk. We are on track to develop detailed plans for the ILC, such that once results from the Large Hadron Collider (LHC) at CERN establish the main science goals and parameters of the next machine, we will be in good position to make a strong proposal for this new major global project in particle physics. The two overriding issues for the ILC R&D programme are to demonstrate that the technical requirements for the accelerator are achievable with practical technologies, and that the ambitious physics goals can be addressed by realistic ILC detectors. This GDE interim report documents the impressive progress on the accelerator technologies that can make the ILC a reality. It highlights results of the technological demonstrations that are giving the community increased confidence that we will be ready to proceed with an ILC project following the TDR. The companion detector and physics report document likewise demonstrates how detector designs can meet the ambitious and detailed physics goals set out by the ILC Steering Committee. LHC results will likely affect the requirements for the machine design and the detectors, and we are monitoring that very closely, intending to adapt our design as those results become available.

  5. Preparation of waste analysis plans under the Resource Conservation and Recovery Act (Interim guidance)

    SciTech Connect (OSTI)

    Not Available

    1993-03-01

    This document is organized to coincide with the suggested structure of the actual Waste Analysis Plans (WAP) discussed in the previous section. The contents of the remaining eleven chapters and appendices that comprise this document are described below: Chapter 2 addresses waste streams, test parameters, and rationale for sampling and analytical method selection; test methods for analyzing parameters; proceduresfor collecting representative samples; and frequency of sample collection and analyses. These are the core WAP requirements. Chapter 3 addresses analysis requirements for waste received from off site. Chapter 4addresses additional requirements for ignitable, reactive, or incompatible wastes. Chapter 5 addresses unit-specific requirements. Chapter 6 addresses special procedures for radioactive mixed waste. Chapter 7 addresses wastes subject to the land disposal restrictions. Chapter 8 addresses QA/QC procedures. Chapter 9 compares the waste analysis requirements of an interim status facility with those of a permitted facility. Chapter 10 describes the petition process required for sampling and analytical procedures to deviate from accepted methods, such as those identified in promulgated regulations. Chapter 11 reviews the process for modification of WAPs as waste type or handling practices change at a RCRA permitted TSDF. Chapter 12 is the list of references that were used in the preparation of this guidance. Appendix A is a sample WAP addressing physical/chemical treatment and container storage. Appendix B is a sample WAP addressing an incinerator and tank systems. Appendix C discusses the relationship of the WAP to other permitting requirements and includes specific examples of how waste analysis is used to comply with certain parts of a RCRA permit. Appendix D contains the exact wording for the notification/certification requirements under theland disposal restrictions.

  6. PM Motor Parametric Design Analyses for Hybrid Electric Vehicle Traction Drive Application: Interim Report

    SciTech Connect (OSTI)

    Staunton, R.H.

    2004-08-11

    The Department of Energy's (DOE) Office of FreedomCAR (Cooperative Automotive Research) and Vehicle Technologies has a strong interest in making rapid progress in permanent magnet (PM) machine development. The program is directing various technology development projects that will advance the technology and lead to request for proposals (RFP) for manufacturer prototypes. This aggressive approach is possible because the technology is clearly within reach and the approach is deemed essential, based on strong market demand, escalating fuel prices, and competitive considerations. In response, this study began parallel development paths that included a literature search/review, development and utilization of multiple parametric models to determine the effects of design parameters, verification of the modeling methodology, development of an interior PM (IPM) machine baseline design, development of alternative machine baseline designs, and cost analyses for several candidate machines. This interim progress report summarizes the results of these activities as of June 2004. This report provides background and summary information for recent machine parametric studies and testing programs that demonstrate both the potential capabilities and technical limitations of brushless PM machines (axial gap and radial gap), the IPM machine, the surface-mount PM machines (interior or exterior rotor), induction machines, and switched reluctance machines. The FreedomCAR program, while acknowledging the progress made by Oak Ridge National Laboratory, Delphi, Delco-Remy International, and others in these programs, has redirected efforts toward a ''short path'' to a marketable and competitive PM motor for hybrid electric vehicle traction applications. The program has developed a set of performance targets for the type of traction machine desired. The short-path approach entails a comprehensive design effort focusing on the IPM machine and meeting the performance targets. The selection of the

  7. CORRECTIVE ACTION PLAN FOR CORRECTIVE ACTION UNIT 528: POLYCHLORINATED BIPHENYLS CONTAMINATION NEVADA TEST SITE, NEVADA

    SciTech Connect (OSTI)

    BECHTEL NEVADA

    2005-06-01

    Corrective Action Unit (CAU) 528: Polychlorinated Biphenyls Contamination is listed in Appendix III of the Federal Facility Agreement and Consent Order (FFACO, 1996) and is located in Area 25 of the Nevada Test Site. CAU 528 was created to address polychlorinated biphenyl (PCB) contamination identified during the CAU 262 corrective action investigation. CAU 528 consists of one Corrective Action Site (CAS): CAS 25-27-03, Polychlorinated Biphenyls Surface Contamination.

  8. The contour method cutting assumption: error minimization and correction

    SciTech Connect (OSTI)

    Prime, Michael B; Kastengren, Alan L

    2010-01-01

    The recently developed contour method can measure 2-D, cross-sectional residual-stress map. A part is cut in two using a precise and low-stress cutting technique such as electric discharge machining. The contours of the new surfaces created by the cut, which will not be flat if residual stresses are relaxed by the cutting, are then measured and used to calculate the original residual stresses. The precise nature of the assumption about the cut is presented theoretically and is evaluated experimentally. Simply assuming a flat cut is overly restrictive and misleading. The critical assumption is that the width of the cut, when measured in the original, undeformed configuration of the body is constant. Stresses at the cut tip during cutting cause the material to deform, which causes errors. The effect of such cutting errors on the measured stresses is presented. The important parameters are quantified. Experimental procedures for minimizing these errors are presented. An iterative finite element procedure to correct for the errors is also presented. The correction procedure is demonstrated on experimental data from a steel beam that was plastically bent to put in a known profile of residual stresses.

  9. Draft final decision document for the north boundary system improvements interim response action at the Rocky Mountain Arsenal

    SciTech Connect (OSTI)

    Not Available

    1989-04-01

    The interim response action consists of the design and construction or installation of improvements at the North Boundary alluvial ground water intercept and treatment system. This draft final decision document provides summaries of: alternatives considered; significant events leading to the initiation of the IRA ; the IRA project; The applicable or relevant and appropriate requirements, standards, criteria, or limitations (ARAR's) associated with the program; The following improvements are planned: recharge units in areas not covered by the new recharge trenches; treatment system modifications to reduce carbon fines in plant effluent.

  10. Final decision document for the interim response action at the Motor Pool Area, Rocky Mountain Arsenal, version 4. 0

    SciTech Connect (OSTI)

    Not Available

    1990-02-01

    The objective of the interim response action at the motor pool area is to mitigate the threat of releases of TRCLE. The proposal IRA will consist of the installation of a vapor extraction system to remove and treat the soil contamination at an identified source of TRCLE at the motor pool. A ground water extraction and treatment system will be installed to contain the TRCLE plume emanating from the area. This decision document provides summaries of: (1) alternative technologies considered; (2) significant events leading to the initiation of the IRA; (3) the IRA project; and (4) applicable or relevant and appropriate requirements, standards, criteria, and limitations (ARAR's) associated with the program.

  11. Final decision document for the interim response action at the lime settling basins, Rocky Mountain Arsenal, version 4.0

    SciTech Connect (OSTI)

    1990-03-01

    The objective of the interim response action at the lime settling basins is to mitigate the threat of releases from the basins. The proposed IRA consists of: (1) relocation of sludge material to the settling basin; (2) construction of a 360 degree subsurface barrier around the basins; (3) construction of a soil and vegetative cover over the material; and (4) installation of a ground water extraction system. This decision document provides summaries of: (1) alternative technologies considered, (2) significant events leading to the initiation of the IRA, (3) the IRA Project, and (4) applicable or relevant and appropriate requirements, standards, criteria, and limitations (ARAR`s) associated with the program.

  12. Housekeeping category corrective action unit work plan

    SciTech Connect (OSTI)

    1996-08-01

    The purpose of this Corrective Action Unit (CAU) Work Plan is to provide a strategy to be used by the US Department of Energy Nevada Operations Office (DOE/NV), the US Department of Defense (DoD) Defense Special Weapons Agency (DSWA) (formerly the Defense Nuclear Agency), and contractor personnel for conducting corrective actions at the Nevada Test Site (NTS) and Nevada off-site locations including the Tonopah Test Range (TTR), the Project Shoal Area, and the Central Nevada Test Area. This Work Plan applies to housekeeping category CAUs already listed in the Federal Facility Agreement and Consent Order (FFACO) Appendices (FFACO, 1996) as well as newly identified Corrective Action Sites (CASs) that will follow the housekeeping process.

  13. Streamlined Approach for Environmental Restoration (SAFER) Plan for Corrective Action Unit 411. Double Tracks Plutonium Dispersion (Nellis), Nevada Test and Training Range, Nevada, Revision 0

    SciTech Connect (OSTI)

    Matthews, Patrick K.

    2015-03-01

    This Streamlined Approach for Environmental Restoration (SAFER) Plan addresses the actions needed to achieve closure for Corrective Action Unit (CAU) 411, Double Tracks Plutonium Dispersion (Nellis). CAU 411 is located on the Nevada Test and Training Range and consists of a single corrective action site (CAS), NAFR-23-01, Pu Contaminated Soil. There is sufficient information and historical documentation from previous investigations and the 1996 interim corrective action to recommend closure of CAU 411 using the SAFER process. Based on existing data, the presumed corrective action for CAU 411 is clean closure. However, additional data will be obtained during a field investigation to document and verify the adequacy of existing information, and to determine whether the CAU 411 closure objectives have been achieved. This SAFER Plan provides the methodology to gather the necessary information for closing the CAU. The results of the field investigation will be presented in a closure report that will be prepared and submitted to the Nevada Division of Environmental Protection (NDEP) for review and approval. The site will be investigated based on the data quality objectives (DQOs) developed on November 20, 2014, by representatives of NDEP, the U.S. Air Force (USAF), and the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Field Office. The DQO process was used to identify and define the type, amount, and quality of data needed to determine whether CAU 411 closure objectives have been achieved. The following text summarizes the SAFER activities that will support the closure of CAU 411; Collect environmental samples from designated target populations to confirm or disprove the presence of contaminants of concern (COCs) as necessary to supplement existing information; If COCs are no longer present, establish clean closure as the corrective action; If COCs are present, the extent of contamination will be defined and further corrective actions

  14. QCD Corrections to Heavy Quarkonium Production

    SciTech Connect (OSTI)

    Artoisenet, P.

    2008-08-29

    I discuss J/{psi} and {upsilon} production at the Tevatron. Working in the framework of NRQCD, I review the current theoretical status. Motivated by the polarization puzzle at the Tevatron, I present the brand-new computation of higher-order {alpha}{sub s} corrections to the color-singlet production and discuss the impact of these corrections both on the differential cross section and on the polarization of the quarkonium state. I finally comment on the relative importance of the various transitions that feed quarkonium hadroproduction.

  15. Mixed-Precision Spectral Deferred Correction: Preprint

    SciTech Connect (OSTI)

    Grout, Ray W. S.

    2015-09-02

    Convergence of spectral deferred correction (SDC), where low-order time integration methods are used to construct higher-order methods through iterative refinement, can be accelerated in terms of computational effort by using mixed-precision methods. Using ideas from multi-level SDC (in turn based on FAS multigrid ideas), some of the SDC correction sweeps can use function values computed in reduced precision without adversely impacting the accuracy of the final solution. This is particularly beneficial for the performance of combustion solvers such as S3D [6] which require double precision accuracy but are performance limited by the cost of data motion.

  16. Cylinder yard inspections and corrective actions

    SciTech Connect (OSTI)

    Barlow, C.R.; Ziehlke, K.T.; Pryor, W.A.

    1990-07-31

    Inspection of valves on stored uranium hexafluoride (UF{sub 6}) cylinders was initiated at the three diffusion plant sites in Oak Ridge, Tennessee, Paducah, Kentucky, and Portsmouth, Ohio as the result of the discovery of valve defects and evidence of valve leaks at the Oak Ridge K-25 plant. The coordinated inspection culminated in the identification of additional factors related to long-term safe storage of UF{sub 6}, and plans for correction of such deficiencies are presently being developed and implemented. These corrective actions supplement existing programs aimed at assurance of safe storage as summarized in the report.

  17. Simulating Wavefront Correction via Deformable Mirrors at X-Ray...

    Office of Scientific and Technical Information (OSTI)

    Conference: Simulating Wavefront Correction via Deformable Mirrors at X-Ray Beamlines Citation Details In-Document Search Title: Simulating Wavefront Correction via Deformable ...

  18. 2014-10-14 Issuance: Test Procedures Correction for Fluorescent...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    4 Issuance: Test Procedures Correction for Fluorescent Lamp Ballasts; Notice of Proposed Rulemaking 2014-10-14 Issuance: Test Procedures Correction for Fluorescent Lamp Ballasts; ...

  19. Corrective Action Investigation Plan for the Central Nevada Test...

    Office of Legacy Management (LM)

    CORRECTIVE ACTION INVESTIGATION PLAN FOR THE CENTRAL NEVADA TEST AREA SUBSURFACE SITES ... CORRECTIVE ACTION INVESTIGATION PLAN FOR THE CENTRAL NEVADA TEST AREA SUBSURFACE SITES ...

  20. Tonopah Test Range Environmental Restoration Corrective Action Sites

    SciTech Connect (OSTI)

    NSTec Environmental Restoration

    2010-08-04

    This report describes the status (closed, closed in place, or closure in progress) of the Corrective Action Sites and Corrective Action Units at the Tonopah Test Range

  1. Carlsbad Field Office (CBFO) Corrective Action Plan - Truck Fire...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    This consolidated CAP specifies the CBFO corrective actions responsive to the three Accident Investigation Boards' reports. Each corrective action includes the associated JON, the ...

  2. Environmental Management Los Alamos Field Corrective Action Plan...

    Energy Savers [EERE]

    Los Alamos Field Corrective Action Plan - Radiological Release Phase II Environmental Management Los Alamos Field Corrective Action Plan - Radiological Release Phase II On March...

  3. Corrective Action Tracking System User's Guide | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    September 07, 2004 Corrective Action Tracking System (CATS) User's Guide for Direct Web Access The Department of Energy (DOE) Corrective Action Management Program (CAMP) prescribes...

  4. Nuclear Waste Partnership (NWP) Corrective Action Plan - Truck...

    Office of Environmental Management (EM)

    Nuclear Waste Partnership (NWP) Corrective Action Plan - Truck Fire and Radiological ... Corrective Action Plan under Nuclear Waste Partnership LLC Contract DE-EM0001971. ...

  5. Los Alamos National Security Corrective Action Plan - Radiological...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Partnership (NWP) Corrective Action Plan - Truck Fire and Radiological Release Phase I Carlsbad Field Office (CBFO) Corrective Action Plan - Truck Fire and Radiological Release

  6. ROOT CAUSE ANALYSIS AND CORRECTIVE ACTION PLAN CLOSURE REPORT...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ROOT CAUSE ANALYSIS AND CORRECTIVE ACTION PLAN CLOSURE REPORT ROOT CAUSE ANALYSIS AND CORRECTIVE ACTION PLAN CLOSURE REPORT The Department conducted a root cause analysis (RCA) ...

  7. High-energy electrons from the muon decay in orbit: Radiative corrections

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Szafron, Robert; Czarnecki, Andrzej

    2015-12-07

    We determine the Ο(α) correction to the energy spectrum of electrons produced in the decay of muons bound in atoms. We focus on the high-energy end of the spectrum that constitutes a background for the muon-electron conversion and will be precisely measured by the upcoming experiments Mu2e and COMET. As a result, the correction suppresses the background by about 20%.

  8. High-energy electrons from the muon decay in orbit: Radiative corrections

    SciTech Connect (OSTI)

    Szafron, Robert; Czarnecki, Andrzej

    2015-05-19

    We determine the ?(?) correction to the energy spectrum of electrons produced in the decay of muons bound in atoms. We focus on the high-energy end of the spectrum that constitutes a background for the muon-electron conversion and will be precisely measured by the upcoming experiments Mu2e and COMET. As a result, the correction suppresses the background by about 20%.

  9. Technical energy audit of the Rifle Correctional Facility

    SciTech Connect (OSTI)

    Not Available

    1980-01-01

    This energy audit was initiated to pinpoint the reasons for the disproportionate budget share of energy costs at the Rifle Correctional Facility, one of Colorado's newest prisons. Conservation options and retrofits are discussed in detail as are the economics of improvements and rising energy costs. Because of the site's geographic situation, techniques of solar adaptation are discussed, although emphasis is on conservation strategies. Partial wood heating is also considered. Rifle's particular security system may also work to its advantage through the use of inmate labor as a cost-saving measure both during the improvements and as a long-term strategy.

  10. REVIEW OF FAST FLUX TEST FACILITY (FFTF) FUEL EXPERIMENTS FOR STORAGE IN INTERIM STORAGE CASKS (ISC)

    SciTech Connect (OSTI)

    CHASTAIN, S.A.

    2005-10-24

    Appendix H, Section H.3.3.10.11 of the Final Safety Analysis Report (FSAR), provides the limits to be observed for fueled components authorized for storage in the Fast Flux Test Facility (FFTF) spent fuel storage system. Currently, the authorization basis allows standard driver fuel assemblies (DFA), as described in the FSAR Chapter 17, Section 17.5.3.1, to be stored provided decay power per assembly is {le} 250 watts, post-irradiation time is four years minimum, average assembly burn-up is 150,000 MWD/MTHM maximum and the pre-irradiation enrichment is 29.3% maximum (per H.3.3.10.11). In addition, driver evaluation (DE), core characterizer assemblies (CCA), and run-to-cladding-breach (RTCB) assemblies are included based on their similarities to a standard DFA. Ident-69 pin containers with fuel pins from these DFAs can also be stored. Section H.3.3.10.11 states that fuel types outside the specification criteria above will be addressed on a case-by-case basis. There are many different types of fuel and blanket experiments that were irradiated in the FFTF which now require offload to the spent fuel storage system. Two reviews were completed for a portion of these special type fuel components to determine if placement into the Core Component Container (CCC)/Interim Storage Cask (ISC) would require any special considerations or changes to the authorization basis. Project mission priorities coupled with availability of resources and analysts prevented these evaluations from being completed as a single effort. Areas of review have included radiological accident release consequences, radiological shielding adequacy, criticality safety, thermal limits, confinement, and stress. The results of these reviews are available in WHC-SD-FF-RPT-005, Rev. 0 and 1, ''Review of FFTF Fuel Experiments for Storage at ISA'', (Reference I), which subsequently allowed a large portion of these components to be included in the authorization basis (Table H.3.3-21). The report also identified

  11. Interim Report: Air-Cooled Condensers for Next Generation Geothermal Power Plants Improved Binary Cycle Performance

    SciTech Connect (OSTI)

    Daniel S. Wendt; Greg L. Mines

    2010-09-01

    As geothermal resources that are more expensive to develop are utilized for power generation, there will be increased incentive to use more efficient power plants. This is expected to be the case with Enhanced Geothermal System (EGS) resources. These resources will likely require wells drilled to depths greater than encountered with hydrothermal resources, and will have the added costs for stimulation to create the subsurface reservoir. It is postulated that plants generating power from these resources will likely utilize the binary cycle technology where heat is rejected sensibly to the ambient. The consumptive use of a portion of the produced geothermal fluid for evaporative heat rejection in the conventional flash-steam conversion cycle is likely to preclude its use with EGS resources. This will be especially true in those areas where there is a high demand for finite supplies of water. Though they have no consumptive use of water, using air-cooling systems for heat rejection has disadvantages. These systems have higher capital costs, reduced power output (heat is rejected at the higher dry-bulb temperature), increased parasitics (fan power), and greater variability in power generation on both a diurnal and annual basis (larger variation in the dry-bulb temperature). This is an interim report for the task ‘Air-Cooled Condensers in Next- Generation Conversion Systems’. The work performed was specifically aimed at a plant that uses commercially available binary cycle technologies with an EGS resource. Concepts were evaluated that have the potential to increase performance, lower cost, or mitigate the adverse effects of off-design operation. The impact on both cost and performance were determined for the concepts considered, and the scenarios identified where a particular concept is best suited. Most, but not all, of the concepts evaluated are associated with the rejection of heat. This report specifically addresses three of the concepts evaluated: the use of

  12. INDEPENDENT TECHNICAL REVIEW OF THE C-400 INTERIM REMEDIAL PROJECT PHASE I RESULTS, PADUCAH, KENTUCKY

    SciTech Connect (OSTI)

    Looney, B.; Rossabi, J.; Stewart,L.; Richards, W.

    2010-10-29

    The groundwater and soil in the vicinity of the C-400 Building at the Paducah Gaseous Diffusion Plant (PGDP), is contaminated with substantial quantities of industrial solvents, primarily trichoroethene (TCE). This solvent 'source' is recognized as a significant challenge and an important remediation target in the overall environmental cleanup strategy for PGDP. Thus, the cleanup of the C-400 TCE Source is a principal focus for the Department of Energy (DOE) and its contractors, and for PGDP regulators and stakeholders. Using a formal investigation, feasibility study and decision process, Electrical Resistance Heating (ERH) was selected for the treatment of the soil and groundwater in the vicinity of C-400. ERH was selected as an interim action to remove 'a significant portion of the contaminant mass of TCE at the C-400 Cleaning Building area through treatment' with the longer term goal of reducing 'the period the TCE concentration in groundwater remains above its Maximum Contaminant Level (MCL).' ERH is a thermal treatment that enhances the removal of TCE and related solvents from soil and groundwater. The heterogeneous conditions at PGDP, particularly the high permeability regional gravel aquifer (RGA), are challenging to ERH. Thus, a phased approach is being followed to implement this relatively expensive and complex remediation technology. Conceptually, the phased approach encourages safety and efficiency by providing a 'lessons learned' process and allowing appropriate adjustments to be identified and implemented prior to follow-on phase(s) of treatment. More specifically, early deployment targeted portions of the challenging RGA treatment zone with relatively little contamination reducing the risk of adverse collateral impacts from underperformance in terms of heating and capture. Because of the importance and scope of the C-400 TCE source remediation activities, DOE chartered an Independent Technical Review (ITR) in 2007 to assess the C-400 ERH plans prior

  13. Options in the Eleventh Year for Interim Standard Offer Number Four Contracts

    SciTech Connect (OSTI)

    Hinrichs, Thomas C.

    1992-03-24

    The Interim Standard Offer Number Four Contracts (ISM), under which most of the geothermal industry is selling power (outside of The Geysers), has an initial ten year period of known fixed energy payments. In the eleventh year, the price goes to the Avoided Cost of the buying utility. The specific contract language is ''Seller will be paid at a rate equal to the utilities' published avoided cost of energy as updated and authorized by the Commission (CPUC)''. The first geothermal contract will reach the end of the initial 10 year period in early 1994, a few will end in 1995 and 1996, and the majority will end in the 1997-2000 period. This is beginning to be focused upon by the utilities, lenders and, of course, the operators themselves. The prime reason for focusing on the issue is that avoided costs of the utilities directly track the delivered cost of the natural gas, and most forecasts are showing that the price of gas in the eleventh year of the contracts will be significantly lower than the last year of the fixed period of energy payments. There are many forums in which the predication of natural gas prices are discussed. In the State of California, the agency responsible for the official forecast is the California Energy Commission. Every two years, the CEC holds hearings for input into its biennial Fuels Report (FR) which establishes the forecast of natural gas prices in addition to other parameters which are used in the planning process. The attached Exhibit I is an excerpt out of the 1991 Fuels Report (FR91). Figure 1 compares the forecast of FR89 and FR91 for the Utility Electric Generation (UEG) in PG&E's service area, and Figure 2, the forecast in the SOCAL service area. The FR91 SOCAL service area forecast indicates a bottoming of the gas price in 1994 at $2.50/mmbtu. Recent prices in 1992 are already at these levels. Converting this to an avoided energy cost brings about a price of 2 to 2-1/2 Cents/kWh. The 1992 energy price in the IS04 contract is 9

  14. FTCP Corrective Action Plan- Revision 2

    Broader source: Energy.gov [DOE]

    March 2009 FTCP Corrective Action Plan, Revision 2, which is Deliverable B for Commitment 13 in the Department of Energy (DOE) Implementation Plan to Improve Oversight of Nuclear Operations, issued in response to Defense Nuclear Facilities Safety Board Recommendation 2004-1, Oversight of Complex, High-Hazard Nuclear Operations

  15. FTCP Corrective Action Plan- Revision 1

    Broader source: Energy.gov [DOE]

    January 2007 FTCP Corrective Action Plan, Revision 1, which is Deliverable B for Commitment 13 in the Department of Energy (DOE) Implementation Plan to Improve Oversight of Nuclear Operations, issued in response to Defense Nuclear Facilities Safety Board Recommendation 2004- 1, Oversight of Complex, High-Hazard Nuclear Operations

  16. Errata Corrections as of February 7, 2012

    Gasoline and Diesel Fuel Update (EIA)

    February 7, 2012 1. On Table 21 of the Scenario Case Data spreadsheet files for the Credit Cap 2.1 and Credit Cap 3.0 tables, data for "Total Penalty" (line 2846) and "CES Payments" (lines 2867 through 2875) were corrected

  17. NSA AERI Hatch Correction Data Set

    SciTech Connect (OSTI)

    Turner, David

    2012-03-23

    From 2000-2008, the NSA AERI hatch was determined to be indicated as open too frequently. Analysis suggests that the hatch was actually opening and closing properly but that its status was not being correctly reported by the hatch controller to the datastream. An algorithm was written to determine the hatch status from the observed

  18. Corrective Action Decision Document (CADD), Area 12 fleet operations steam cleaning discharge area, Nevada Test Site Corrective Action Unit 339

    SciTech Connect (OSTI)

    Bonn, J.F.

    1996-12-01

    This Corrective Action Decision Document (CADD) incorporates the methodology used for evaluating the remedial alternatives completed for a former steam cleaning discharge area at the Nevada Test Site (NTS). The former steam cleaning site is located in Area 12, east of the Fleet Operations Building 12-16. The discharge area has been impacted by Resource Conservation and Recovery Act (RCRA) F Listed volatile organic compounds (VOCs) and petroleum hydrocarbons waste. Based upon these findings, resulting from Phase 1 and Phase 2 site investigations, corrective action is required at the site. To determine the appropriate corrective action to be proposed, an evaluation of remedial alternatives was completed. The evaluation was completed using a Corrective Measures Study (CMS). Based on the results of the CMS, the favored closure alternative for the site is plugging the effluent discharge line, removing the sandbagged barrier, completing excavation of VOC impacted soils, and fencing the soil area impacted by total petroleum hydrocarbons (TPH), east of the discharge line and west of the soil berm. Management of the F Listed VOCs are dictated by RCRA. Due to the small volume of impacted soil, excavation and transportation to a Treatment Storage and Disposal Facility (TSDF) is the most practical method of management. It is anticipated that the TPH (as oil) impacted soils will remain in place based upon; the A through K Analysis, concentrations detected (maximum 8,600 milligrams per kilogram), expected natural degradation of the hydrocarbons over time, and the findings of the Phase 2 Investigation that vertical migration has been minimal.

  19. Sampling and analysis plan for the gunite and associated tanks interim remedial action, wall coring and scraping at Oak Ridge National Laboratory, Oak Ridge, Tennessee

    SciTech Connect (OSTI)

    NONE

    1998-02-01

    This Sampling and Analysis Plan documents the procedures for collecting and analyzing wall core and wall scraping samples from the Gunite and Associated Tanks. These activities are being conducted to support the Comprehensive Environmental Response, Compensation, and Liability Act at the gunite and associated tanks interim remedial action at Oak Ridge National Laboratory in Oak Ridge, Tennessee. The sampling and analysis activities will be performed in concert with sludge retrieval and sluicing of the tanks. Wall scraping and/or wall core samples will be collected from each quadrant in each tank by using a scraping sampler and/or a coring drill deployed by the Houdini robot vehicle. Each sample will be labeled, transported to the Radioactive Materials Analytical Laboratory, and analyzed for physical and radiological characteristics, including total activity, gross alpha, gross beta, radioactive strontium and cesium, and other alpha- and gamma-emitting radionuclides. The data quality objectives process, based on US Environmental Protection Agency guidance, was applied to identify the objectives of this sampling and analysis. The results of the analysis will be used to (1) validate predictions of a strontium concrete diffusion model, (2) estimate the amount of radioactivity remaining in the tank shells, (3) provide information to correlate with measurements taken by the Gunite Tank Isotope Mapping Probe and the Characterization End Effector, and (4) estimate the performance of the wall cleaning system. This revision eliminates wall-scraping samples from all tanks, except Tank W-3. The Tank W-3 experience indicated that the wall scrapper does not collect sufficient material for analysis.

  20. A nonlinear lag correction algorithm for a-Si flat-panel x-ray detectors

    SciTech Connect (OSTI)

    Starman, Jared; Star-Lack, Josh; Virshup, Gary; Shapiro, Edward; Fahrig, Rebecca

    2012-10-15

    Purpose: Detector lag, or residual signal, in a-Si flat-panel (FP) detectors can cause significant shading artifacts in cone-beam computed tomography reconstructions. To date, most correction models have assumed a linear, time-invariant (LTI) model and correct lag by deconvolution with an impulse response function (IRF). However, the lag correction is sensitive to both the exposure intensity and the technique used for determining the IRF. Even when the LTI correction that produces the minimum error is found, residual artifact remains. A new non-LTI method was developed to take into account the IRF measurement technique and exposure dependencies. Methods: First, a multiexponential (N = 4) LTI model was implemented for lag correction. Next, a non-LTI lag correction, known as the nonlinear consistent stored charge (NLCSC) method, was developed based on the LTI multiexponential method. It differs from other nonlinear lag correction algorithms in that it maintains a consistent estimate of the amount of charge stored in the FP and it does not require intimate knowledge of the semiconductor parameters specific to the FP. For the NLCSC method, all coefficients of the IRF are functions of exposure intensity. Another nonlinear lag correction method that only used an intensity weighting of the IRF was also compared. The correction algorithms were applied to step-response projection data and CT acquisitions of a large pelvic phantom and an acrylic head phantom. The authors collected rising and falling edge step-response data on a Varian 4030CB a-Si FP detector operating in dynamic gain mode at 15 fps at nine incident exposures (2.0%-92% of the detector saturation exposure). For projection data, 1st and 50th frame lag were measured before and after correction. For the CT reconstructions, five pairs of ROIs were defined and the maximum and mean signal differences within a pair were calculated for the different exposures and step-response edge techniques. Results: The LTI

  1. Interim Control Strategy for the Test Area North/Technical Support Facility Sewage Treatment Facility Disposal Pond - Two-year Update

    SciTech Connect (OSTI)

    L. V. Street

    2007-04-01

    The Idaho Cleanup Project has prepared this interim control strategy for the U.S. Department of Energy Idaho Operations Office pursuant to DOE Order 5400.5, Chapter 11.3e (1) to support continued discharges to the Test Area North/Technical Support Facility Sewage Treatment Facility Disposal Pond. In compliance with DOE Order 5400.5, a 2-year review of the Interim Control Strategy document has been completed. This submittal documents the required review of the April 2005 Interim Control Strategy. The Idaho Cleanup Project's recommendation is unchanged from the original recommendation. The Interim Control Strategy evaluates three alternatives: (1) re-route the discharge outlet to an uncontaminated area of the TSF-07; (2) construct a new discharge pond; or (3) no action based on justification for continued use. Evaluation of Alternatives 1 and 2 are based on the estimated cost and implementation timeframe weighed against either alternative's minimal increase in protection of workers, the public, and the environment. Evaluation of Alternative 3, continued use of the TSF-07 Disposal Pond under current effluent controls, is based on an analysis of four points: - Record of Decision controls will protect workers and the public - Risk of increased contamination is low - Discharge water will be eliminated in the foreseeable future - Risk of contamination spread is acceptable. The Idaho Cleanup Project recommends Alternative 3, no action other than continued implementation of existing controls and continued deactivation, decontamination, and dismantlement efforts at the Test Area North/Technical Support Facility.

  2. Corrective Action Investigation Plan for Corrective Action Unit 550: Smoky Contamination Area Nevada National Security Site, Nevada, Revision 0

    SciTech Connect (OSTI)

    Grant Evenson

    2012-05-01

    on January 31, 2012, by representatives of the Nevada Division of Environmental Protection and the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office. The DQO process was used to identify and define the type, amount, and quality of data needed to develop and evaluate appropriate corrective actions for CAU 550. The potential contamination sources associated with the study groups are from nuclear testing activities conducted at CAU 550. The DQO process resulted in an assumption that the total effective dose (TED) within the default contamination boundary of CAU 550 exceeds the final action level and requires corrective action. The presence and nature of contamination outside the default contamination boundary at CAU 550 will be evaluated based on information collected from a field investigation. Radiological contamination will be evaluated based on a comparison of the TED at sample locations to the dose-based final action level. The TED will be calculated as the total of separate estimates of internal and external dose. Results from the analysis of soil samples will be used to calculate internal radiological dose. Thermoluminescent dosimeters placed at the center of each sample location will be used to measure external radiological dose. Appendix A provides a detailed discussion of the DQO methodology and the DQOs specific to each group of CASs.

  3. Los Alamos National Security Corrective Action Plan - Radiological Release

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Phase II | Department of Energy Security Corrective Action Plan - Radiological Release Phase II Los Alamos National Security Corrective Action Plan - Radiological Release Phase II Los Alamos National Security Corrective Action Plan - Radiological Release Phase II Los Alamos National Security Corrective Action Plan - Radiological Release Phase II (7.59 MB) More Documents & Publications Environmental Management Los Alamos Field Office Corrective Action Plan - Radiological Release Phase II

  4. NINTH INTERIM STATUS REPORT: MODEL 9975 PCV O-RING FIXTURE LONG-TERM LEAK PERFORMANCE

    SciTech Connect (OSTI)

    Daugherty, W.

    2014-08-06

    -ring fixtures aging at 350 and 400 F. No failures have yet been observed in GLT-S O-ring fixtures aging at 200 - 300 F for 54 - 57 months. No additional O-ring failures have been observed since the last interim report was issued. Aging and periodic leak testing will continue for the remaining PCV fixtures. Additional irradiation of several fixtures is recommended to maintain a balance between thermal and radiation exposures similar to that experienced in storage, and to show the degree of consistency of radiation response between GLT and GLT-S O-rings.

  5. Method and apparatus for providing pulse pile-up correction in charge quantizing radiation detection systems

    DOE Patents [OSTI]

    Britton, Jr., Charles L.; Wintenberg, Alan L.

    1993-01-01

    A radiation detection method and system for continuously correcting the quantization of detected charge during pulse pile-up conditions. Charge pulses from a radiation detector responsive to the energy of detected radiation events are converted to voltage pulses of predetermined shape whose peak amplitudes are proportional to the quantity of charge of each corresponding detected event by means of a charge-sensitive preamplifier. These peak amplitudes are sampled and stored sequentially in accordance with their respective times of occurrence. Based on the stored peak amplitudes and times of occurrence, a correction factor is generated which represents the fraction of a previous pulses influence on a preceding pulse peak amplitude. This correction factor is subtracted from the following pulse amplitude in a summing amplifier whose output then represents the corrected charge quantity measurement.

  6. Sample Results From The Interim Salt Disposition Program Macrobatch 7 Tank 21H Qualification MST Solids Sample

    SciTech Connect (OSTI)

    Washington, A. L. II; Peters, T. B.

    2013-09-19

    Savannah River National Laboratory (SRNL) performed experiments on qualification material for use in the Interim Salt Disposition Program (ISDP) Batch 7 processing. The Marcrobatch 7 material was received with visible fine particulate solids, atypical for these samples. The as received material was allowed to settle for a period greater than 24 hours. The supernatant was then decanted and utilized as our clarified feed material. As part of this qualification work, SRNL performed an Actinide Removal Process (ARP) test using the clarified feed material. From this test, the residual monosodium titanate (MST) was analyzed for radionuclide uptake after filtration from H-Tank Farm (HTF) feed salt solution. The results of these analyses are reported and are within historical precedent.

  7. Methane conversion for highway fuel (Methanol Plantship Project), interim report. Resource materials. Report for November 1991-May 1992

    SciTech Connect (OSTI)

    Fink, C.; Jackson, I.; Wright, S.; Booras, P.; Linaweaver, P.

    1997-01-01

    The report presents partial results of a study undertaken to respond to PL 101-516; that law provided funding for `phase II of the development/design work on a floating methanol production plantship to advance work already completed under phase I of the project, which was authorized by section 152 of the Surface Transportation Act of 1982.` Phase I determined the feasibility of producing large volumes of low-cost methanol aboard a plantship. The interim report includes: an examination of the impact of recent permitting, licensing, and environmental regulations on methanol plantship (MPS) design and operation; analysis of other recent MPS design studies and updating of the process technology; and revision and updating of an economic analysis which continues to demonstrate the project`s viability.

  8. Statement of work for conceptual design of solidified high-level waste interim storage system project (phase I)

    SciTech Connect (OSTI)

    Calmus, R.B., Westinghouse Hanford

    1996-12-17

    The U.S. Department of Energy (DOE) has embarked upon a course to acquire Hanford Site tank waste treatment and immobilization services using privatized facilities. This plan contains a two phased approach. Phase I is a ``proof-of-principle/commercial demonstration- scale`` effort and Phase II is a full-scale production effort. In accordance with the planned approach, interim storage (IS) and disposal of various products from privatized facilities are to be DOE furnished. The path forward adopted for Phase I solidification HLW IS entails use of Vaults 2 and 3 in the Spent Nuclear Fuel Canister Storage Building, to be located in the Hanford Site 200 East Area. This Statement of Work describes the work scope to be performed by the Architect-Engineer to prepare a conceptual design for the solidified HLW IS System.

  9. Albany Interim Landfill gas extraction and mobile power system: Using landfill gas to produce electricity. Final report

    SciTech Connect (OSTI)

    1997-06-01

    The Albany Interim Landfill Gas Extraction and Mobile Power System project served three research objectives: (1) determination of the general efficiency and radius of influence of horizontally placed landfill gas extraction conduits; (2) determination of cost and effectiveness of a hydrogen sulfide gas scrubber utilizing Enviro-Scrub{trademark} liquid reagent; and (3) construction and evaluation of a dual-fuel (landfill gas/diesel) 100 kW mobile power station. The horizontal gas extraction system was very successful; overall, gas recovery was high and the practical radius of influence of individual extractors was about 50 feet. The hydrogen sulfide scrubber was effective and its use appears feasible at typical hydrogen sulfide concentrations and gas flows. The dual-fuel mobile power station performed dependably and was able to deliver smooth power output under varying load and landfill gas fuel conditions.

  10. Technical Competencies for the Safe Interim Storage and Management of 233U at U.S. Department of Energy Facilities

    SciTech Connect (OSTI)

    Campbell, D.O.; Krichinsky, A.M.; Laughlin, S.S.; Van Essen, D.C.; Yong, L.K.

    1999-02-17

    Uranium-233 (with concomitant {sup 232}U) is a man-made fissile isotope of uranium with unique nuclear characteristics which require high-integrity alpha containment biological shielding, and remote handling. The special handling considerations and the fact that much of the {sup 233}U processing and large-scale handling was performed over a decade ago underscore the importance of identifying the people within the DOE complex who are currently working with or have worked with {sup 233}U. The availability of these key personnel is important in ensuring safe interim storage, management and ultimate disposition of {sup 233}U at DOE facilities. Significant programs are ongoing at several DOE sites with actinides. The properties of these actinide materials require many of the same types of facilities and handling expertise as does {sup 233}U.

  11. Technical considerations related to interim source-term assumptions for emergency planning and equipment qualification. [PWR; BWR

    SciTech Connect (OSTI)

    Niemczyk, S.J.; McDowell-Boyer, L.M.

    1982-09-01

    The source terms recommended in the current regulatory guidance for many considerations of light water reactor (LWR) accidents were developed a number of years ago when understandings of many of the phenomena pertinent to source term estimation were relatively primitive. The purpose of the work presented here was to develop more realistic source term assumptions which could be used for interim regulatory purposes for two specific considerations, namely, equipment qualification and emergency planning. The overall approach taken was to adopt assumptions and models previously proposed for various aspects of source term estimation and to modify those assumptions and models to reflect recently gained insights into, and data describing, the release and transport of radionuclides during and after LWR accidents. To obtain illustrative estimates of the magnitudes of the source terms, the results of previous calculations employing the adopted assumptions and models were utilized and were modified to account for the effects of the recent insights and data.

  12. Interim storage of dismantled nuclear weapon components at the U.S. Department of Energy Pantex Plant

    SciTech Connect (OSTI)

    Guidice, S.J.; Inlow, R.O.

    1995-12-31

    Following the events of 1989 and the subsequent cessation of production of new nuclear weapons by the US, the mission of the Department of Energy (DOE) Nuclear Weapons Complex has shifted from production to dismantlement of retired weapons. The sole site in the US for accomplishing the dismantlement mission is the DOE Pantex Plant near Amarillo, Texas. Pending a national decision on the ultimate storage and disposition of nuclear components form the dismantled weapons, the storage magazines within the Pantex Plant are serving as the interim storage site for pits--the weapon plutonium-bearing component. The DOE has stipulated that Pantex will provide storage for up to 12,000 pits pending a Record of Decision on a comprehensive site-wide Environmental Impact Statement in November 1996.

  13. Interim Results from a Study of the Impacts of Tin (II) Based Mercury Treatment in a Small Stream Ecosystem: Tims Branch, Savannah River Site

    SciTech Connect (OSTI)

    Looney, Brian; BryanJr., Larry; Mathews, Teresa J; Peterson, Mark J; Roy, W Kelly; Jett, Robert T; Smith, John G

    2012-03-01

    A research team is assessing the impacts of an innovative mercury treatment system in Tims Branch, a small southeastern stream. The treatment system, installed in 2007, reduces and removes inorganic mercury from water using tin(II) (stannous) chloride addition followed by air stripping. The system results in discharge of inorganic tin to the ecosystem. This screening study is based on historical information combined with measurements of contaminant concentrations in water, fish, sediment, biofilms and invertebrates. Initial mercury data indicate that first few years of mercury treatment resulted in a significant decrease in mercury concentration in an upper trophic level fish, redfin pickerel, at all sampling locations in the impacted reach. For example, the whole body mercury concentration in redfin pickerel collected from the most impacted pond decreased approximately 72% between 2006 (pre-treatment) and 2010 (post-treatment). Over this same period, mercury concentrations in the fillet of redfin pickerel in this pond were estimated to have decreased from approximately 1.45 {micro}g/g (wet weight basis) to 0.45 {micro}g/g - a decrease from 4.8x to 1.5x the current EPA guideline concentration for mercury in fillet (0.3 {micro}g/g). Thermodynamic modeling, scanning electron microscopy, and other sampling data for tin suggest that particulate tin (IV) oxides are a significant geochemical species entering the ecosystem with elevated levels of tin measured in surficial sediments and biofilms. Detectable increases in tin in sediments and biofilms extended approximately 3km from the discharge location. Tin oxides are recalcitrant solids that are relatively non-toxic and resistant to dissolution. Work continues to develop and validate methods to analyze total tin in the collected biota samples. In general, the interim results of this screening study suggest that the treatment process has performed as predicted and that the concentration of mercury in upper trophic level

  14. Corrective Action Plan for Corrective Action Unit 417: Central Nevada Test Area Surface, Nevada

    SciTech Connect (OSTI)

    K. Campbell

    2000-04-01

    This Corrective Action Plan provides methods for implementing the approved corrective action alternative as provided in the Corrective Action Decision Document for the Central Nevada Test Area (CNTA), Corrective Action Unit (CAU) 417 (DOE/NV, 1999). The CNTA is located in the Hot Creek Valley in Nye County, Nevada, approximately 137 kilometers (85 miles) northeast of Tonopah, Nevada. The CNTA consists of three separate land withdrawal areas commonly referred to as UC-1, UC-3, and UC-4, all of which are accessible to the public. CAU 417 consists of 34 Corrective Action Sites (CASs). Results of the investigation activities completed in 1998 are presented in Appendix D of the Corrective Action Decision Document (DOE/NV, 1999). According to the results, the only Constituent of Concern at the CNTA is total petroleum hydrocarbons (TPH). Of the 34 CASs, corrective action was proposed for 16 sites in 13 CASs. In fiscal year 1999, a Phase I Work Plan was prepared for the construction of a cover on the UC-4 Mud Pit C to gather information on cover constructibility and to perform site management activities. With Nevada Division of Environmental Protection concurrence, the Phase I field activities began in August 1999. A multi-layered cover using a Geosynthetic Clay Liner as an infiltration barrier was constructed over the UC-4 Mud Pit. Some TPH impacted material was relocated, concrete monuments were installed at nine sites, signs warning of site conditions were posted at seven sites, and subsidence markers were installed on the UC-4 Mud Pit C cover. Results from the field activities indicated that the UC-4 Mud Pit C cover design was constructable and could be used at the UC-1 Central Mud Pit (CMP). However, because of the size of the UC-1 CMP this design would be extremely costly. An alternative cover design, a vegetated cover, is proposed for the UC-1 CMP.

  15. Corrective Action Plan for Corrective Action Unit 139: Waste Disposal Sites, Nevada Test Site, Nevada

    SciTech Connect (OSTI)

    NSTec Environmental Restoration

    2007-07-01

    Corrective Action Unit (CAU) 139, Waste Disposal Sites, is listed in the Federal Facility Agreement and Consent Order (FFACO) of 1996 (FFACO, 1996). CAU 139 consists of seven Corrective Action Sites (CASs) located in Areas 3, 4, 6, and 9 of the Nevada Test Site (NTS), which is located approximately 65 miles (mi) northwest of Las Vegas, Nevada (Figure 1). CAU 139 consists of the following CASs: CAS 03-35-01, Burn Pit; CAS 04-08-02, Waste Disposal Site; CAS 04-99-01, Contaminated Surface Debris; CAS 06-19-02, Waste Disposal Site/Burn Pit; CAS 06-19-03, Waste Disposal Trenches; CAS 09-23-01, Area 9 Gravel Gertie; and CAS 09-34-01, Underground Detection Station. Details of the site history and site characterization results for CAU 139 are provided in the approved Corrective Action Investigation Plan (CAIP) (U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office [NNSA/NSO], 2006) and in the approved Corrective Action Decision Document (CADD) (NNSA/NSO, 2007). The purpose of this Corrective Action Plan (CAP) is to present the detailed scope of work required to implement the recommended corrective actions as specified in Section 4.0 of the approved CADD (NNSA/NSO, 2007). The approved closure activities for CAU 139 include removal of soil and debris contaminated with plutonium (Pu)-239, excavation of geophysical anomalies, removal of surface debris, construction of an engineered soil cover, and implementation of use restrictions (URs). Table 1 presents a summary of CAS-specific closure activities and contaminants of concern (COCs). Specific details of the corrective actions to be performed at each CAS are presented in Section 2.0 of this report.

  16. CX-010370: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Interim Corrective Measures to Control Migration of Contaminated Groundwater CX(s) Applied: B6.9 Date: 09/19/2012 Location(s): California Offices(s): Berkeley Site Office

  17. Corrective Action Plan for Corrective Action Unit 562: Waste Systems, Nevada National Security Site, Nevada

    SciTech Connect (OSTI)

    NSTec Environmental Restoration

    2011-04-30

    This Corrective Action Plan has been prepared for Corrective Action Unit (CAU) 562, Waste Systems, in accordance with the Federal Facility Agreement and Consent Order (1996; as amended March 2010). CAU 562 consists of 13 Corrective Action Sites (CASs) located in Areas 2, 23, and 25 of the Nevada National Security Site. Site characterization activities were performed in 2009 and 2010, and the results are presented in Appendix A of the Corrective Action Decision Document for CAU 562. The scope of work required to implement the recommended closure alternatives is summarized. (1) CAS 02-26-11, Lead Shot, will be clean closed by removing shot. (2) CAS 02-44-02, Paint Spills and French Drain, will be clean closed by removing paint and contaminated soil. As a best management practice (BMP), asbestos tile will be removed. (3) CAS 02-59-01, Septic System, will be clean closed by removing septic tank contents. As a BMP, the septic tank will be removed. (4) CAS 02-60-01, Concrete Drain, contains no contaminants of concern (COCs) above action levels. No further action is required; however, as a BMP, the concrete drain will be removed. (5) CAS 02-60-02, French Drain, was clean closed. Corrective actions were completed during corrective action investigation activities. As a BMP, the drain grates and drain pipe will be removed. (6) CAS 02-60-03, Steam Cleaning Drain, will be clean closed by removing contaminated soil. As a BMP, the steam cleaning sump grate and outfall pipe will be removed. (7) CAS 02-60-04, French Drain, was clean closed. Corrective actions were completed during corrective action investigation activities. (8) CAS 02-60-05, French Drain, will be clean closed by removing contaminated soil. (9) CAS 02-60-06, French Drain, contains no COCs above action levels. No further action is required. (10) CAS 02-60-07, French Drain, requires no further action. The french drain identified in historical documentation was not located during corrective action investigation

  18. Corrective Action Investigation Plan for Corrective Action Unit 563: Septic Systems, Nevada Test Site, Nevada, with Errata Sheet, Revision 0

    SciTech Connect (OSTI)

    Alfred Wickline

    2007-01-01

    Corrective Action Unit 563, Septic Systems, is located in Areas 3 and 12 of the Nevada Test Site, which is 65 miles northwest of Las Vegas, Nevada. Corrective Action Unit 563 is comprised of the four corrective action sites (CASs) below: • 03-04-02, Area 3 Subdock Septic Tank • 03-59-05, Area 3 Subdock Cesspool • 12-59-01, Drilling/Welding Shop Septic Tanks • 12-60-01, Drilling/Welding Shop Outfalls These sites are being investigated because existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend corrective action alternatives. Additional information will be obtained by conducting a corrective action investigation (CAI) before evaluating corrective action alternatives and selecting the appropriate corrective action for each CAS. The results of the field investigation will support a defensible evaluation of viable corrective action alternatives that will be presented in the Corrective Action Decision Document.

  19. Measurement of $\

    SciTech Connect (OSTI)

    Aguilar-Arevalo, A.A.; Anderson, C.E.; Bazarko, A.O.; Brice, S.J.; Brown, B.C.; Bugel, L.; Cao, J.; Coney, L.; Conrad, J.M.; Cox, D.C.; Curioni, A.; /Yale U. /Columbia U.

    2010-10-01

    MiniBooNE reports the first absolute cross sections for neutral current single {pi}{sup 0} production on CH{sub 2} induced by neutrino and antineutrino interactions measured from the largest sets of NC {pi}{sup 0} events collected to date. The principal result consists of differential cross sections measured as functions of {pi}{sup 0} momentum and {pi}{sup 0} angle averaged over the neutrino flux at MiniBooNE. We find total cross sections of (4.76 {+-} 0.05{sub stat} {+-} 0.76{sub sys}) x 10{sup -40} cm{sup 2}/nucleon at a mean energy of E{sub {nu}} = 808 MeV and (1.48 {+-} 0.05{sub stat} {+-} 0.23{sub sys}) x 10{sup -40} cm{sup 2}/nucleon at a mean energy of E{sub {nu}} = 664 MeV for {nu}{sub {mu}} and {bar {nu}}{sub {mu}} induced production, respectively. In addition, we have included measurements of the neutrino and antineutrino total cross sections for incoherent exclusive NC 1{pi}{sup 0} production corrected for the effects of final state interactions to compare to prior results.

  20. Guidelines for Correctly Using the DOE Zero Energy Ready Home...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Guidelines for Correctly Using the DOE Zero Energy Ready Home Name and Logo Guidelines for Correctly Using the DOE Zero Energy Ready Home Name and Logo PDF icon ZERH Logo Use ...

  1. Tonopah Test Range Summary of Corrective Action Units

    SciTech Connect (OSTI)

    Ronald B. Jackson

    2007-05-01

    Corrective Action Sites (CASs) and Corrective Action Units (CAUs) at the Tonopah Test Range (TTR) may be placed into three categories: Clean Closure/No Further Action, Closure in Place, or Closure in Progress.

  2. Merged and corrected 915 MHz Radar Wind Profiler moments (Dataset...

    Office of Scientific and Technical Information (OSTI)

    Merged and corrected 915 MHz Radar Wind Profiler moments Title: Merged and corrected 915 MHz Radar Wind Profiler moments The radar wind profiler (RWP) present at the SGP central ...

  3. Electroweak and QCD corrections to top-pair hadroproduction in...

    Office of Scientific and Technical Information (OSTI)

    Electroweak and QCD corrections to top-pair hadroproduction in association with heavy bosons Citation Details In-Document Search Title: Electroweak and QCD corrections to top-pair ...

  4. Corrective Action Tracking System (CATS) | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    The CATS web-based database is used to enter, track, and report the status of corrective actions developed and implemented in the DOE Corrective Action Management Program (CAMP) to...

  5. Corrective Action Plan for Corrective Action Unit 490: Station 44 Burn Area, Tonopah Test Range, Nevada

    SciTech Connect (OSTI)

    K. B. Campbell

    2002-04-01

    Corrective Action Unit (CAU) 490, Station 44 Burn Area is located on the Tonopah Test Range (TTR). CAU 490 is listed in the Federal Facility Agreement and Consent Order (FFACO, 1996) and includes for Corrective Action Sites (CASs): (1) Fire Training Area (CAS 03-56-001-03BA); (2) Station 44 Burn Area (CAS RG-56-001-RGBA); (3) Sandia Service Yard (CAS 03-58-001-03FN); and (4) Gun Propellant Burn Area (CAS 09-54-001-09L2).

  6. Nuclear Waste Partnership (NWP) Corrective Action Plan - Truck Fire and

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Radiological Release Phase I | Department of Energy - Truck Fire and Radiological Release Phase I Nuclear Waste Partnership (NWP) Corrective Action Plan - Truck Fire and Radiological Release Phase I Submittal of the Underground Salt Haul Truck Fire Corrective Action Plan and the Radiological Release Event Corrective Action Plan under Nuclear Waste Partnership LLC Contract DE-EM0001971. Nuclear Waste Partnership (NWP) Corrective Action Plan - Truck Fire and Radiological Release Phase I (4.46

  7. Corrections Notice, Federal Register, 71 FR 10097, February 28, 2006 |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy Corrections Notice, Federal Register, 71 FR 10097, February 28, 2006 Corrections Notice, Federal Register, 71 FR 10097, February 28, 2006 Document displays a correction notice pertaining to Energy Conservation Standards for New Federal Commercial and Multi-Family High-Rise Residential Buildings and New Federal Low-Rise Residential Buildings, which was published in the Federal Register on February 28, 2006. Download the corrections notice document. (33.34 KB) More

  8. Federal Correctional Institution - Phoenix, Arizona | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Federal Correctional Institution - Phoenix, Arizona Federal Correctional Institution - Phoenix, Arizona Photo of a Parabolic-Trough Solar Water-Heating System Installed at the Federal Correctional Institution Facility north of Phoenix, Arizona A parabolic-trough solar water-heating system was installed at the Federal Correctional Institution (FCI) facility north of Phoenix, Arizona. This medium security prison for males has a current population of about 1,200 inmates and uses an average of

  9. Earned Value Management System (EVMS) Corrective Action Standard Operating Procedure

    Office of Environmental Management (EM)

    Corrective Action Standard Operating Procedure (ECASOP) Issued by Office of Project Management, Oversight, and Assessments (PMOA) PM-1 September 21, 2015 DEPARTMENT OF ENERGY EVMS CORRECTIVE ACTION SOP SEPTEMBER 21, 2015 ii Earned Value Management System (EVMS) Corrective Action (CA) Standard Operating Procedure (ECASOP) OPR: PM-30 Issue Date: September 21, 2015 1. PURPOSE. This EVMS Corrective Action Standard Operating Procedure (ECASOP) serves as a primary reference for PMOA PM-1 for

  10. Corrective Action Plan (CAP) 2008 | Department of Energy

    Energy Savers [EERE]

    Corrective Action Plan (CAP) 2008 Corrective Action Plan (CAP) 2008 The Root Cause Analysis Corrective Action Plan ensures that the root causes identified in the Root Cause Analysis report are addressed with meaningful and lasting solutions in order to improve contract and project management performance. Corrective Action Plan (CAP) 2008 (5.93 MB) Key Resources PMCDP EVMS PARS IIe FPD Resource Center PM Newsletter Forms and Templates More Documents & Publications National Defense

  11. Equations for plutonium and americium-241 decay corrections ...

    Office of Scientific and Technical Information (OSTI)

    PLUTONIUM; ACCOUNTING; CORRECTIONS; DIFFERENTIAL EQUATIONS; ISOTOPE RATIO; NUCLEAR MATERIALS MANAGEMENT; TIME DEPENDENCE; ACTINIDE ISOTOPES; ACTINIDE NUCLEI; ACTINIDES; ALPHA ...

  12. Enterprise Assessments Operational Awareness Record of Observations of the Design and Modification Progress of the Waste Isolation Pilot Plant Underground Interim Ventilation System and Supplemental Ventilation System November 2015

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    WIPP-IVS/SVS-2015-11-15 Site: Waste Isolation Pilot Plant (WIPP) Subject: Observations of the design and modification progress of the WIPP Underground Interim Ventilation System and Supplemental Ventilation System Dates of Activity: 11/15/2015 - 11/19/2015 Report Preparer: Jeff Snook Activity Description / Purpose: The Office of Environment, Safety and Health Assessments within the Office of Enterprise Assessments (EA) is reviewing the design, installation, and startup of the WIPP Interim

  13. Quantum Mechanical Corrections to Simulated Shock Hugoniot Temperatures

    SciTech Connect (OSTI)

    Goldman, N; Reed, E; Fried, L E

    2009-07-17

    The authors present a straightforward method for the inclusion of quantum nuclear vibrational effects in molecular dynamics calculations of shock Hugoniot temperatures. Using a grueneisen equation of state and a quasi-harmonic approximation to the vibrational energies, they derive a simple, post-processing method for calculation of the quantum corrected Hugoniot temperatures. They have used our novel technique on ab initio simulations of both shock compressed water and methane. Our results indicate significantly closer agreement with all available experimental temperature data for these two systems. Our formalism and technique can be easily applied to a number of different shock compressed molecular liquids or covalent solids, and has the potential to decrease the large uncertainties inherent in many experimental Hugoniot temperature measurements of these systems.

  14. Intensity inhomogeneity correction for magnetic resonance imaging of human brain at 7T

    SciTech Connect (OSTI)

    Uwano, Ikuko; Yamashita, Fumio; Higuchi, Satomi; Ito, Kenji; Sasaki, Makoto; Kudo, Kohsuke Goodwin, Jonathan; Harada, Taisuke; Ogawa, Akira

    2014-02-15

    Purpose: To evaluate the performance and efficacy for intensity inhomogeneity correction of various sequences of the human brain in 7T MRI using the extended version of the unified segmentation algorithm. Materials: Ten healthy volunteers were scanned with four different sequences (2D spin echo [SE], 3D fast SE, 2D fast spoiled gradient echo, and 3D time-of-flight) by using a 7T MRI system. Intensity inhomogeneity correction was performed using the “New Segment” module in SPM8 with four different values (120, 90, 60, and 30 mm) of full width at half maximum (FWHM) in Gaussian smoothness. The uniformity in signals in the entire white matter was evaluated using the coefficient of variation (CV); mean signal intensities between the subcortical and deep white matter were compared, and contrast between subcortical white matter and gray matter was measured. The length of the lenticulostriate (LSA) was measured on maximum intensity projection (MIP) images in the original and corrected images. Results: In all sequences, the CV decreased as the FWHM value decreased. The differences of mean signal intensities between subcortical and deep white matter also decreased with smaller FWHM values. The contrast between white and gray matter was maintained at all FWHM values. LSA length was significantly greater in corrected MIP than in the original MIP images. Conclusions: Intensity inhomogeneity in 7T MRI can be successfully corrected using SPM8 for various scan sequences.

  15. CORRECTIVE ACTION PLAN FOR CORRECTIVE ACTION UNIT 224: DECON PAD AND SEPTIC SYSTEMS NEVADA TEST SITE, NEVADA

    SciTech Connect (OSTI)

    2006-07-01

    The purpose of this Corrective Action Plan is to provide the detailed scope of work required to implement the recommended corrective actions as specified in the approved CAU 224 CADD.

  16. Corrective Action Decision Document/ Corrective Action Plan for Corrective Action Unit 443: Central Nevada Test Area-Subsurface Central Nevada Test Area, Nevada, Rev. No. 0

    SciTech Connect (OSTI)

    Susan Evans

    2004-11-01

    This Corrective Action Decision Document/Corrective Action Plan (CADD/CAP) has been prepared for the subsurface at the Central Nevada Test Area (CNTA) Corrective Action Unit (CAU) 443, CNTA - Subsurface, Nevada, in accordance with the ''Federal Facility Agreement and Consent Order'' (FFACO) (1996). CAU 443 is located in Hot Creek Valley in Nye County, Nevada, north of U.S. Highway 6, about 48 kilometers north of Warm Springs, Nevada. The CADD/CAP combines the decision document (CADD) with the corrective action plan (CAP) and provides or references the specific information necessary to recommend corrective actions for the UC-1 Cavity (Corrective Action Site 58-57-001) at CAU 443, as provided in the FFACO. The purpose of the CADD portion of the document (Section 1.0 to Section 4.0) is to identify and provide a rationale for the selection of a recommended corrective action alternative for the subsurface at CNTA. To achieve this, the following tasks were required: (1) Develop corrective action objectives; (2) Identify corrective action alternative screening criteria; (3) Develop corrective action alternatives; (4) Perform detailed and comparative evaluations of the corrective action alternatives in relation to the corrective action objectives and screening criteria; and (5) Recommend a preferred corrective action alternative for the subsurface at CNTA. A Corrective Action Investigation (CAI) was performed in several stages from 1999 to 2003, as set forth in the ''Corrective Action Investigation Plan for the Central Nevada Test Area Subsurface Sites (Corrective Action Unit No. 443)'' (DOE/NV, 1999). Groundwater modeling was the primary activity of the CAI. Three phases of modeling were conducted for the Faultless underground nuclear test. The first involved the gathering and interpretation of geologic and hydrogeologic data into a three-dimensional numerical model of groundwater flow, and use of the output of the flow model for a transport model of radionuclide release

  17. Anisotropic determination and correction for ultrasonic flaw detection by spectral analysis

    DOE Patents [OSTI]

    Adler, Laszlo; Von Cook, K.; Simpson, Jr., William A.; Lewis, D. Kent

    1978-01-01

    The anisotropic nature of a material is determined by measuring the velocity of an ultrasonic longitudinal wave and a pair of perpendicular ultrasonic shear waves through a sample of the material each at a plurality of different angles in three planes orthogonal to each other. The determined anisotropic nature is used as a correction factor in a spectral analyzing system of flaw determination.

  18. RCRA corrective action for underground storage tanks -- Subtitle C for Subtitle I

    SciTech Connect (OSTI)

    1995-08-01

    The purpose of this report is to provide guidance to DOE and DOE contractor personnel responsible for planning and implementation of corrective measures addressing cleanup of releases of hazardous materials or regulated substances from underground storage tanks regulated under RCRA Subtitle C or Subtitle I.

  19. ARM - Measurements

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    govMeasurementsAerosols

  20. ARM - Measurements

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    govMeasurementsRadiometric

  1. Final Report: Correctness Tools for Petascale Computing

    SciTech Connect (OSTI)

    Mellor-Crummey, John

    2014-10-27

    In the course of developing parallel programs for leadership computing systems, subtle programming errors often arise that are extremely difficult to diagnose without tools. To meet this challenge, University of Maryland, the University of Wisconsin—Madison, and Rice University worked to develop lightweight tools to help code developers pinpoint a variety of program correctness errors that plague parallel scientific codes. The aim of this project was to develop software tools that help diagnose program errors including memory leaks, memory access errors, round-off errors, and data races. Research at Rice University focused on developing algorithms and data structures to support efficient monitoring of multithreaded programs for memory access errors and data races. This is a final report about research and development work at Rice University as part of this project.

  2. Chiral corrections to hyperon axial form factors

    SciTech Connect (OSTI)

    Jiang Fujiun; Tiburzi, B. C.

    2008-05-01

    We study the complete set of flavor-changing hyperon axial-current matrix elements at small momentum transfer. Using partially quenched heavy baryon chiral perturbation theory, we derive the chiral and momentum behavior of the axial and induced pseudoscalar form factors. The meson pole contributions to the latter posses a striking signal for chiral physics. We argue that the study of hyperon axial matrix elements enables a systematic lattice investigation of the efficacy of three-flavor chiral expansions in the baryon sector. This can be achieved by considering chiral corrections to SU(3) symmetry predictions, and their partially quenched generalizations. In particular, despite the presence of eight unknown low-energy constants, we are able to make next-to-leading order symmetry breaking predictions for two linear combinations of axial charges.

  3. Superdense coding interleaved with forward error correction

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Humble, Travis S.; Sadlier, Ronald J.

    2016-05-12

    Superdense coding promises increased classical capacity and communication security but this advantage may be undermined by noise in the quantum channel. We present a numerical study of how forward error correction (FEC) applied to the encoded classical message can be used to mitigate against quantum channel noise. By studying the bit error rate under different FEC codes, we identify the unique role that burst errors play in superdense coding, and we show how these can be mitigated against by interleaving the FEC codewords prior to transmission. As a result, we conclude that classical FEC with interleaving is a useful methodmore » to improve the performance in near-term demonstrations of superdense coding.« less

  4. Figure correction of multilayer coated optics

    DOE Patents [OSTI]

    Chapman; Henry N. , Taylor; John S.

    2010-02-16

    A process is provided for producing near-perfect optical surfaces, for EUV and soft-x-ray optics. The method involves polishing or otherwise figuring the multilayer coating that has been deposited on an optical substrate, in order to correct for errors in the figure of the substrate and coating. A method such as ion-beam milling is used to remove material from the multilayer coating by an amount that varies in a specified way across the substrate. The phase of the EUV light that is reflected from the multilayer will be affected by the amount of multilayer material removed, but this effect will be reduced by a factor of 1-n as compared with height variations of the substrate, where n is the average refractive index of the multilayer.

  5. Revised RCRA closure plan for the Interim Drum Yard (S-030) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee

    SciTech Connect (OSTI)

    Smith, C.M.

    1994-09-01

    The Interim Drum Yard (IDY) facility is a containerized waste storage area located in the Y-12 exclusion area. It was used to store waste materials which are regulated by RCRA (Resource Conservation and Recovery Act); uranyl nitrate solutions were also stored there. The closure plan outlines the actions required to achieve closure of IDY and is being submitted in accordance with TN Rule 1200-1-11.05(7) and 40 CFR 265.110.

  6. Scheme for precise correction of orbit variation caused by dipole error field of insertion device

    SciTech Connect (OSTI)

    Nakatani, T.; Agui, A.; Aoyagi, H.; Matsushita, T.; Takao, M.; Takeuchi, M.; Yoshigoe, A.; Tanaka, H.

    2005-05-15

    We developed a scheme for precisely correcting the orbit variation caused by a dipole error field of an insertion device (ID) in a storage ring and investigated its performance. The key point for achieving the precise correction is to extract the variation of the beam orbit caused by the change of the ID error field from the observed variation. We periodically change parameters such as the gap and phase of the specified ID with a mirror-symmetric pattern over the measurement period to modulate the variation. The orbit variation is measured using conventional wide-frequency-band detectors and then the induced variation is extracted precisely through averaging and filtering procedures. Furthermore, the mirror-symmetric pattern enables us to independently extract the orbit variations caused by a static error field and by a dynamic one, e.g., an error field induced by the dynamical change of the ID gap or phase parameter. We built a time synchronization measurement system with a sampling rate of 100 Hz and applied the scheme to the correction of the orbit variation caused by the error field of an APPLE-2-type undulator installed in the SPring-8 storage ring. The result shows that the developed scheme markedly improves the correction performance and suppresses the orbit variation caused by the ID error field down to the order of submicron. This scheme is applicable not only to the correction of the orbit variation caused by a special ID, the gap or phase of which is periodically changed during an experiment, but also to the correction of the orbit variation caused by a conventional ID which is used with a fixed gap and phase.

  7. Local-Level Prognostics Health Management Systems Framework for Passive AdvSMR Components. Interim Report

    SciTech Connect (OSTI)

    Ramuhalli, Pradeep; Roy, Surajit; Hirt, Evelyn H.; Pardini, Allan F.; Jones, Anthony M.; Deibler, John E.; Pitman, Stan G.; Tucker, Joseph C.; Prowant, Matthew S.; Suter, Jonathan D.

    2014-09-12

    This report describes research results to date in support of the integration and demonstration of diagnostics technologies for prototypical AdvSMR passive components (to establish condition indices for monitoring) with model-based prognostics methods. The focus of the PHM methodology and algorithm development in this study is at the localized scale. Multiple localized measurements of material condition (using advanced nondestructive measurement methods), along with available measurements of the stressor environment, enhance the performance of localized diagnostics and prognostics of passive AdvSMR components and systems.

  8. Design requirements document for the interim store phase I solidified high-level waste function 4.2.4.1.2

    SciTech Connect (OSTI)

    Calmus, R.B.

    1996-09-30

    The U.S. Department of Energy (DOE) has embarked upon a course to acquire Hanford site.t,,nk waste tr:atment and immobilization services using privatized facilities. This plan contains a two-phased approach. Phase I is a ``proof-of-principle/commercial demonstration-scale`` effort and Phase II is a full-scale production effort. In accordance with the planned approach, interim storage and disposal of various products from privatized facilities are to be DOE furnished. The path forward adopted for Phase I solidified high-level waste (HLW) interim storage entails use of Vaut 2 and 3 in the Hanford Site Spent Nuclear Fuels Canister Storage Building (CSB), to be located in the Hanford Site 200 East Area. This design requirements document establishes the functions, with associated requirements, allocated to the Phase I solidified HLW interim storage system. These requirements will be used as the basis for conceptual design of the CSB and supporting systems. This document will also provide the basis for preparation of a performance specification for design and construction activities necessary to achieve the overall project mission.

  9. Interim remedial action work plan for the cesium plots at Waste Area Grouping 13 at Oak Ridge National Laboratory, Oak Ridge, Tennessee

    SciTech Connect (OSTI)

    Not Available

    1993-07-01

    This remedial action work plan (RAWP) is issued under the Federal Facility Agreement to provide a basic approach for implementing the interim remedial action (IRA) described in Interim Record of Decision for the Oak Ridge National Laboratory Waste Area Grouping 13 Cesium Plots, Oak Ridge, Tennessee. This RAWP summarizes the interim record of decision (IROD) requirements and establishes the strategy for the implementation of the field activities. As documented in the IROD document, the primary goal of this action is to reduce the risk to human health and the environment resulting from current elevated levels of gamma radiation on the site and at areas accessible to the public adjacent to the site. The major steps of this IRA are to: Excavate cesium-contaminated soil; place the excavated soils in containers and transport to Waste Area Grouping (WAG) 6; and backfill excavated plots with clean fill materials. The actual remedial action will be performed by Department of Energy prime contractor, MK-Ferguson of Oak Ridge Company. Remediation of the cesium plots will require approximately 60 days to complete. During this time, all activities will be performed according to this RAWP and the applicable specifications, plans, and procedures referred to in this document. The IRA on WAG 13 will prevent a known source of cesium-contaminated soil from producing elevated levels of gamma radiation in areas accessible to the public, eliminate sources of contamination to the environment, and reduce the risks associated with surveillance and maintenance of the WAG 13 site.

  10. 90-day Interim Report on Shale Gas Production- Secretary of Energy Advisory Board

    Broader source: Energy.gov [DOE]

    The Shale Gas Subcommittee of the Secretary of Energy Advisory Board is charged with identifying measures that can be taken to reduce the environmental impact and improve the safety of shale gas...

  11. Correcting radiation survey data to account for increased leakage during intensity modulated radiotherapy treatments

    SciTech Connect (OSTI)

    Kairn, T.; Crowe, S. B.; Trapp, J. V.

    2013-11-15

    Purpose: Intensity modulated radiotherapy (IMRT) treatments require more beam-on time and produce more linac head leakage to deliver similar doses to conventional, unmodulated, radiotherapy treatments. It is necessary to take this increased leakage into account when evaluating the results of radiation surveys around bunkers that are, or will be, used for IMRT. The recommended procedure of applying a monitor-unit based workload correction factor to secondary barrier survey measurements, to account for this increased leakage when evaluating radiation survey measurements around IMRT bunkers, can lead to potentially costly overestimation of the required barrier thickness. This study aims to provide initial guidance on the validity of reducing the value of the correction factor when applied to different radiation barriers (primary barriers, doors, maze walls, and other walls) by evaluating three different bunker designs.Methods: Radiation survey measurements of primary, scattered, and leakage radiation were obtained at each of five survey points around each of three different radiotherapy bunkers and the contribution of leakage to the total measured radiation dose at each point was evaluated. Measurements at each survey point were made with the linac gantry set to 12 equidistant positions from 0 to 330, to assess the effects of radiation beam direction on the results.Results: For all three bunker designs, less than 0.5% of dose measured at and alongside the primary barriers, less than 25% of the dose measured outside the bunker doors and up to 100% of the dose measured outside other secondary barriers was found to be caused by linac head leakage.Conclusions: Results of this study suggest that IMRT workload corrections are unnecessary, for survey measurements made at and alongside primary barriers. Use of reduced IMRT workload correction factors is recommended when evaluating survey measurements around a bunker door, provided that a subset of the measurements used in

  12. Absolute Cavity Pyrgeometer to Measure the Absolute Outdoor Longwave Irradiance with Traceability to International System of Units, SI

    SciTech Connect (OSTI)

    Reda, I.; Zeng, J.; Scheuch, J.; Hanssen, L.; Wilthan, B.; Myers, D.; Stoffel, T.

    2012-03-01

    This article describes a method of measuring the absolute outdoor longwave irradiance using an absolute cavity pyrgeometer (ACP), U.S. Patent application no. 13/049, 275. The ACP consists of domeless thermopile pyrgeometer, gold-plated concentrator, temperature controller, and data acquisition. The dome was removed from the pyrgeometer to remove errors associated with dome transmittance and the dome correction factor. To avoid thermal convection and wind effect errors resulting from using a domeless thermopile, the gold-plated concentrator was placed above the thermopile. The concentrator is a dual compound parabolic concentrator (CPC) with 180{sup o} view angle to measure the outdoor incoming longwave irradiance from the atmosphere. The incoming irradiance is reflected from the specular gold surface of the CPC and concentrated on the 11 mm diameter of the pyrgeometer's blackened thermopile. The CPC's interior surface design and the resulting cavitation result in a throughput value that was characterized by the National Institute of Standards and Technology. The ACP was installed horizontally outdoor on an aluminum plate connected to the temperature controller to control the pyrgeometer's case temperature. The responsivity of the pyrgeometer's thermopile detector was determined by lowering the case temperature and calculating the rate of change of the thermopile output voltage versus the changing net irradiance. The responsivity is then used to calculate the absolute atmospheric longwave irradiance with an uncertainty estimate (U{sub 95}) of {+-}3.96 W m{sup 02} with traceability to the International System of Units, SI. The measured irradiance was compared with the irradiance measured by two pyrgeometers calibrated by the World Radiation Center with traceability to the Interim World Infrared Standard Group, WISG. A total of 408 readings were collected over three different nights. The calculated irradiance measured by the ACP was 1.5 W/m{sup 2} lower than that

  13. Method and apparatus for reconstructing in-cylinder pressure and correcting for signal decay

    DOE Patents [OSTI]

    Huang, Jian

    2013-03-12

    A method comprises steps for reconstructing in-cylinder pressure data from a vibration signal collected from a vibration sensor mounted on an engine component where it can generate a signal with a high signal-to-noise ratio, and correcting the vibration signal for errors introduced by vibration signal charge decay and sensor sensitivity. The correction factors are determined as a function of estimated motoring pressure and the measured vibration signal itself with each of these being associated with the same engine cycle. Accordingly, the method corrects for charge decay and changes in sensor sensitivity responsive to different engine conditions to allow greater accuracy in the reconstructed in-cylinder pressure data. An apparatus is also disclosed for practicing the disclosed method, comprising a vibration sensor, a data acquisition unit for receiving the vibration signal, a computer processing unit for processing the acquired signal and a controller for controlling the engine operation based on the reconstructed in-cylinder pressure.

  14. A proposed interim improvement to the Tevatron beam position monitors with narrow band crystal filters

    SciTech Connect (OSTI)

    Cheng-Yang Tan

    2003-08-25

    Since the start of Run II, we have found that we are unable to reliably and accurately measure the beam position with the present BPM system during high energy physics (HEP). This problem can be traced back to the analogue frontend called the AM/PM module which has trouble handling coalesced beam, but works well with uncoalesced beam. In this paper, we propose a simple fix to the AM/PM module so that we can measure the beam position during HEP. The idea is to use narrow band crystal filters which ring when pinged by coalesced beam so that the AM/PM module is tricked into thinking that it is measuring uncoalesced beam.

  15. Corrective action decision document, Second Gas Station, Tonopah test range, Nevada (Corrective Action Unit No. 403)

    SciTech Connect (OSTI)

    1997-11-01

    This Corrective Action Decision Document (CADD) for Second Gas Station (Corrective Action Unit [CAU] No. 403) has been developed for the U.S. Department of Energy`s (DOE) Nevada Environmental Restoration Project to meet the requirements of the Federal Facility Agreement and Consent Order (FFACO) of 1996 as stated in Appendix VI, {open_quotes}Corrective Action Strategy{close_quotes} (FFACO, 1996). The Second Gas Station Corrective Action Site (CAS) No. 03-02-004-0360 is the only CAS in CAU No. 403. The Second Gas Station CAS is located within Area 3 of the Tonopah Test Range (TTR), west of the Main Road at the location of former Underground Storage Tanks (USTs) and their associated fuel dispensary stations. The TTR is approximately 225 kilometers (km) (140 miles [mi]) northwest of Las Vegas, Nevada, by air and approximately 56 km (35 mi) southeast of Tonopah, Nevada, by road. The TTR is bordered on the south, east, and west by the Nellis Air Force Range and on the north by sparsely populated public land administered by the Bureau of Land Management and the U.S. Forest Service. The Second Gas Station CAS was formerly known as the Underground Diesel Tank Site, Sandia Environmental Restoration Site Number 118. The gas station was in use from approximately 1965 to 1980. The USTs were originally thought to be located 11 meters (m) (36 feet [ft]) east of the Old Light Duty Shop, Building 0360, and consisted of one gasoline UST (southern tank) and one diesel UST (northern tank) (DOE/NV, 1996a). The two associated fuel dispensary stations were located northeast (diesel) and southeast (gasoline) of Building 0360 (CAU 423). Presently the site is used as a parking lot, Building 0360 is used for mechanical repairs of vehicles.

  16. Measurement and Verification for Federal Energy Savings Performance...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Measurement and verification (M&V) activities help agencies confirm that legally and ... When done correctly, M&V: Appropriately allocates risks Reduces uncertainty of savings ...

  17. 40 CFR 265 interim status indicator-evaluation ground-water monitoring plan for the 216-B-63 trench

    SciTech Connect (OSTI)

    Bjornstad, B.N.; Dudziak, S.

    1989-03-01

    This document outlines a ground-water monitoring plan for the 216-B-63 trench located in the northeast corner of the 200-East Area on the Hanford Site in southeastern Washington State. It has been determined that hazardous materials (corrosives) were disposed of to the trench during past operations. Installation of an interim-status ground-water monitoring system is required to determine whether hazardous chemicals are leaching to the ground water from beneath the trench. This document summarizes the existing data that are available from near the 216-B-63 trench and presents a plan to determine the extent of ground-water contamination, if any, derived from the trench. The plan calls for the installation of four new monitoring wells located near the west end of the trench. These wells will be used to monitor ground-water levels and water quality immediately adjacent to the trench. Two existing RCRA monitoring wells, which are located near the trench and hydraulically upgradient of it, will be used as background wells. 46 refs., 15 figs., 12 tabs.

  18. Evaluation of tuff as a medium for a nuclear waste repository: interim status report on the properties of tuff

    SciTech Connect (OSTI)

    Johnstone, J.K.; Wolfsberg, K.

    1980-07-01

    This report is the second in a series of summary briefings to the National Academy of Science`s (NAS) Committee on Radioactive Waste Management dealing with feasibility of disposal of heat-producing radioactive waste in silicic tuff. The interim status of studies of tuff properties determined on samples obtained from Yucca Mountain and Rainier Mesa (G-tunnel) located on the Nevada Test Site (NTS) are discussed. In particular, progress is described on resolving issues identified during the first briefing to the NAS which include behavior of water in tuff when heated, the effect of the presence or absence of water and joints on the thermal/physical properties of tuff and the detailed/complex sorptive properties of highly altered and unaltered tuff. Initial correlations of thermal/physical and sorptive properties with the highly variable porosity and mineralogy are described. Three in-situ, at-depth field experiments, one nearly completed and two just getting underway are described. In particular, the current status of mineralogy and petrology, geochemistry, thermal and mechanical, radiation effects and water behavior studies are described. The goals and initial results of a Mine Design Working Group are discussed. Regional factors such as seismicity, volcanism and hydrology are not discussed.

  19. A NEW METHOD TO CORRECT FOR FIBER COLLISIONS IN GALAXY TWO-POINT STATISTICS

    SciTech Connect (OSTI)

    Guo Hong; Zehavi, Idit; Zheng Zheng

    2012-09-10

    In fiber-fed galaxy redshift surveys, the finite size of the fiber plugs prevents two fibers from being placed too close to one another, limiting the ability to study galaxy clustering on all scales. We present a new method for correcting such fiber collision effects in galaxy clustering statistics based on spectroscopic observations. The target galaxy sample is divided into two distinct populations according to the targeting algorithm of fiber placement, one free of fiber collisions and the other consisting of collided galaxies. The clustering statistics are a combination of the contributions from these two populations. Our method makes use of observations in tile overlap regions to measure the contributions from the collided population, and to therefore recover the full clustering statistics. The method is rooted in solid theoretical ground and is tested extensively on mock galaxy catalogs. We demonstrate that our method can well recover the projected and the full three-dimensional (3D) redshift-space two-point correlation functions (2PCFs) on scales both below and above the fiber collision scale, superior to the commonly used nearest neighbor and angular correction methods. We discuss potential systematic effects in our method. The statistical correction accuracy of our method is only limited by sample variance, which scales down with (the square root of) the volume probed. For a sample similar to the final SDSS-III BOSS galaxy sample, the statistical correction error is expected to be at the level of 1% on scales {approx}0.1-30 h {sup -1} Mpc for the 2PCFs. The systematic error only occurs on small scales, caused by imperfect correction of collision multiplets, and its magnitude is expected to be smaller than 5%. Our correction method, which can be generalized to other clustering statistics as well, enables more accurate measurements of full 3D galaxy clustering on all scales with galaxy redshift surveys.

  20. Explanation of Significant Differences for the Record of Decision for Interim Actions in Zone 1, East Tennessee Technology Park, Oak Ridge, Tennessee

    SciTech Connect (OSTI)

    Bechtel Jacobs

    2011-02-01

    Zone 1 is a 1400-acre area outside the fence of the main plant at The East Tennessee Technology Park (ETTP) in Oak Ridge, Tennessee. The Record of Decision for Interim Actions in Zone, ETTP (Zone 1 Interim ROD) (DOE 2002) identifies the remedial actions for contaminated soil, buried waste, and subsurface infrastructure necessary to protect human health and to limit further contamination of groundwater. Since the Zone 1 Interim Record of Decision (ROD) was signed, new information has been obtained that requires the remedy to be modified as follows: (1) Change the end use in Contractor's Spoil Area (CSA) from unrestricted industrial to recreational; (2) Remove Exposure Units (EU5) ZI-50, 51, and 52 from the scope of the Zone I Interim ROD; (3) Change the end use of the duct bank corridor from unrestricted industrial to restricted industrial; and (4) Remove restriction for the disturbance of soils below 10 feet in Exposure Unit (EU) Z1-04. In accordance with 40 Code of Federal Regulations (CFR) 300.435, these scope modifications are a 'significant' change to the Zone 1 Interim ROD. In accordance with CERCLA Sect. 117 (c) and 40 CFR 300.435 (c)(2)(i), such a significant change is documented with an Explanation of Significant Differences (ESD). The purpose of this ESD is to make the changes listed above. This ESD is part of the Administrative Record file, and it, and other information supporting the selected remedy, can be found at the DOE Information Center, 475 Oak Ridge Turnpike, Oak Ridge, Tennessee 37830, from 8:00 a.m. to 5:00 p.m., Monday through Friday. The ORR is located in Roane and Anderson counties, within and adjacent to the corporate city limits of Oak Ridge, Tennessee. ETTP is located in Roane County near the northwest corner of the ORR. ETTP began operation during World War II as part of the Manhattan Project. The original mission of ETTP was to produce enriched uranium for use in atomic weapons. The plant produced enriched uranium from 1945 until 1985

  1. Detector-Response Correction of Two-Dimensional γ -Ray Spectra from Neutron Capture

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Rusev, G.; Jandel, M.; Arnold, C. W.; Bredeweg, T. A.; Couture, A.; Mosby, S. M.; Ullmann, J. L.

    2015-05-28

    The neutron-capture reaction produces a large variety of γ-ray cascades with different γ-ray multiplicities. A measured spectral distribution of these cascades for each γ-ray multiplicity is of importance to applications and studies of γ-ray statistical properties. The DANCE array, a 4π ball of 160 BaF2 detectors, is an ideal tool for measurement of neutron-capture γ-rays. The high granularity of DANCE enables measurements of high-multiplicity γ-ray cascades. The measured two-dimensional spectra (γ-ray energy, γ-ray multiplicity) have to be corrected for the DANCE detector response in order to compare them with predictions of the statistical model or use them in applications. Themore » detector-response correction problem becomes more difficult for a 4π detection system than for a single detector. A trial and error approach and an iterative decomposition of γ-ray multiplets, have been successfully applied to the detector-response correction. Applications of the decomposition methods are discussed for two-dimensional γ-ray spectra measured at DANCE from γ-ray sources and from the 10B(n, γ) and 113Cd(n, γ) reactions.« less

  2. Corrective Action Investigation Plan for Corrective Action Unit 560: Septic Systems, Nevada Test Site, Nevada with ROTC1, Revision 0

    SciTech Connect (OSTI)

    Grant Evenson

    2008-05-01

    Corrective Action Unit (CAU) 560 is located in Areas 3 and 6 of the Nevada Test Site, which is approximately 65 miles northwest of Las Vegas, Nevada. Corrective Action Unit 560 is comprised of the seven corrective action sites (CASs) listed below: • 03-51-01, Leach Pit • 06-04-02, Septic Tank • 06-05-03, Leach Pit • 06-05-04, Leach Bed • 06-59-03, Building CP-400 Septic System • 06-59-04, Office Trailer Complex Sewage Pond • 06-59-05, Control Point Septic System These sites are being investigated because existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend corrective action alternatives. Additional information will be obtained by conducting a corrective action investigation before evaluating corrective action alternatives and selecting the appropriate corrective action for each CAS. The results of the field investigation will support a defensible evaluation of viable corrective action alternatives that will be presented in the Corrective Action Decision Document. The sites will be investigated based on the data quality objectives (DQOs) developed on January 22, 2008, by representatives from the Nevada Division of Environmental Protection; U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office; Stoller-Navarro Joint Venture; and National Security Technologies, LLC. The DQO process was used to identify and define the type, amount, and quality of data needed to develop and evaluate appropriate corrective actions for CAU 560.

  3. Corrective Action Investigation plan for Corrective Action Unit 546: Injection Well and Surface Releases, Nevada Test Site, Nevada, Revision 0

    SciTech Connect (OSTI)

    Alfred Wickline

    2008-03-01

    Corrective Action Unit (CAU) 546 is located in Areas 6 and 9 of the Nevada Test Site, which is approximately 65 miles northwest of Las Vegas, Nevada. Corrective Action Unit 546 is comprised of two Corrective Action Sites (CASs) listed below: •06-23-02, U-6a/Russet Testing Area •09-20-01, Injection Well These sites are being investigated because existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend corrective action alternatives. Additional information will be obtained by conducting a corrective action investigation (CAI) before evaluating corrective action alternatives and selecting the appropriate corrective action for each CAS. The results of the field investigation will support a defensible evaluation of viable corrective action alternatives that will be presented in the Corrective Action Decision Document. The sites will be investigated based on the data quality objectives (DQOs) developed on November 8, 2007, by representatives of the Nevada Division of Environmental Protection and U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office. The DQO process has been used to identify and define the type, amount, and quality of data needed to develop and evaluate appropriate corrective actions for CAU 546.

  4. Carlsbad Field Office (CBFO) Corrective Action Plan - Truck Fire and

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Radiological Release | Department of Energy Carlsbad Field Office (CBFO) Corrective Action Plan - Truck Fire and Radiological Release Carlsbad Field Office (CBFO) Corrective Action Plan - Truck Fire and Radiological Release The purpose of this Corrective Action Plan (CAP) is to specify U.S. Department of Energy (DOE) Carlsbad Field Office (CBFO) actions for addressing issues identified in the March 2014, accident investigation report for the Underground Salt Haul Truck Fire at the Waste

  5. ARM - Measurements

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    govMeasurementsCloud Properties

  6. ARM - Measurements

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    govMeasurementsSurface Properties

  7. Corrections Notice, Federal Register, 71 FR 10097, February 28...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Document displays a correction notice pertaining to Energy Conservation Standards for New Federal Commercial and Multi-Family High-Rise Residential Buildings and New Federal ...

  8. ARM - Evaluation Product - MPL Corrected for Ship Motion (MPLPOLFSSHIP...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    is provided as an evaluation product for the MAGIC and ACAPEX campaigns. The signal return values and the rangebinwidth are corrected to account for the motion (pitch,...

  9. Using ARM data to correct plane-parallel satellite retrievals...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Using ARM data to correct plane-parallel satellite retrievals of cloud properties Dong, Xiquan University of North Dakota Minnis, Patrick NASA Langley Research Center Xi, Baike...

  10. Internal Audit Management of Corrective Action Plans | The Ames...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Internal Audit Management of Corrective Action Plans Version Number: 1.0 Document Number: Procedure 10300.001 Effective Date: 01...

  11. ARM - PI Product - Dead-time Corrected Disdrometer Data

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    ProductsDead-time Corrected Disdrometer Data ARM Data Discovery Browse Data Comments? We would love to hear from you! Send us a note below or call us at 1-888-ARM-DATA. Send PI Product : Dead-time Corrected Disdrometer Data Original and dead-time corrected disdrometer results for observations made at SGP and TWP. The correction is based on the technique discussed in Sheppard and Joe, 1994. In addition, these files contain calculated radar reflectivity factor, mean Doppler velocity and

  12. Viscous corrections to the resistance of nanojunctions: A dispersion...

    Office of Scientific and Technical Information (OSTI)

    SciTech Connect Search Results Journal Article: Viscous corrections to the resistance of nanojunctions: A dispersion relation approach Citation Details In-Document Search Title: ...

  13. Internal Audit Management of Corrective Action Plans | The Ames Laboratory

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Internal Audit Management of Corrective Action Plans Version Number: 1.0 Document Number: Procedure 10300.001 Effective Date: 01

  14. Feed-forward digital phase and amplitude correction system

    DOE Patents [OSTI]

    Yu, D.U.L.; Conway, P.H.

    1994-11-15

    Phase and amplitude modifications in repeatable RF pulses at the output of a high power pulsed microwave amplifier are made utilizing a digital feed-forward correction system. A controlled amount of the output power is coupled to a correction system for processing of phase and amplitude information. The correction system comprises circuitry to compare the detected phase and amplitude with the desired phase and amplitude, respectively, and a digitally programmable phase shifter and attenuator and digital logic circuitry to control the phase shifter and attenuator. The phase and amplitude of subsequent are modified by output signals from the correction system. 11 figs.

  15. Feed-forward digital phase and amplitude correction system

    DOE Patents [OSTI]

    Yu, David U. L.; Conway, Patrick H.

    1994-01-01

    Phase and amplitude modifications in repeatable RF pulses at the output of a high power pulsed microwave amplifier are made utilizing a digital feed-forward correction system. A controlled amount of the output power is coupled to a correction system for processing of phase and amplitude information. The correction system comprises circuitry to compare the detected phase and amplitude with the desired phase and amplitude, respectively, and a digitally programmable phase shifter and attenuator and digital logic circuitry to control the phase shifter and attenuator. The Phase and amplitude of subsequent are modified by output signals from the correction system.

  16. Earned Value Management System (EVMS) Corrective Action Standard...

    Broader source: Energy.gov (indexed) [DOE]

    EVMS Corrective Action Standard Operating Procedure (ECASOP) serves as PM's primary ... Action Plans (CAPs) in accordance with the EIA-748 (current version) EVMS standard. ...

  17. Simultaneous linear optics and coupling correction for storage...

    Office of Scientific and Technical Information (OSTI)

    Journal Article: Simultaneous linear optics and coupling correction for storage rings with turn-by-turn beam position monitor data Citation Details In-Document Search Title:...

  18. Nuclear Waste Partnership (NWP) Corrective Action Plan Addendum...

    Office of Environmental Management (EM)

    Addendum Radiological Release Event Phase II Nuclear Waste Partnership (NWP) Corrective ... the underground (UG) repository at the Waste Isolation Pilot Plant (WIPP), which ...

  19. Passive and Active Neutron Matrix Correction for Heterogeneous Distributions Utilizing the Neutron Imaging Technique

    SciTech Connect (OSTI)

    Villani, M.F.; Croft, St.; Alvarez, E.; Wilkins, C.G.; Stamp, D.; Fisher, J.; Ambrifi, A.; Simone, G.; Bourva, L.C.

    2008-07-01

    Classical Non-Destructive Assay (NDA) Passive Neutron Coincidence Counting (PNCC) and Differential Die-Away (DDA) active neutron interrogation techniques [1, 2] are well suited for determining the gross matrix correction factors for homogenous mass distributions of Special Nuclear Material (SNM) within an interfering waste drum matrix. These measured passive and active matrix correction factors are crucial in quantifying the SNM mass, associated Total Measurement Uncertainty (TMU), and Minimum Detectable Activity (MDA) within the drum. When heterogeneous SNM mass distributions are encountered, the measured SNM mass, TMU and MDA biases introduced may be 100%, or greater, especially for dense hydrogenous matrices. The standard matrix correction factors can be adjusted if a coarse spatial image of the SNM mass, relative to the matrix, is available. The image can then be analyzed to determine the spatially-adjusted, matrix correction factors case by case. This image analysis approach was accomplished by modifying the standard Passive-Active Neutron (PAN) counter design [3] to accommodate a unique data acquisition architecture that supports a newly developed image acquisition and analysis application called the Neutron Imaging Technique (NIT). The NIT functionality supports both PNCC and DDA acquisition and analysis modes and exploits the symmetry between a stored set of factory acquired NIT images with those from the unknown PAN assay. The NIT result is then an adjustment to the classical correction factor reducing, if not removing, the SNM mass bias and revealing the true TMU and MDA values. In this paper we describe the NIT for the PAN design from the software and algorithmic perspectives and how this technique accommodates waste matrix drums that are difficult, from the classical standpoint, if not impossible, to extract meaningful SNM mass, TMU and MDA results. (authors)

  20. Characterizing the marker-dye correction for Gafchromic EBT2 film: A comparison of three analysis methods

    SciTech Connect (OSTI)

    McCaw, Travis J.; Micka, John A.; DeWerd, Larry A.

    2011-10-15

    Purpose: Gafchromic EBT2 film has a yellow marker dye incorporated into the active layer of the film that can be used to correct the film response for small variations in thickness. This work characterizes the effect of the marker-dye correction on the uniformity and uncertainty of dose measurements with EBT2 film. The effect of variations in time postexposure on the uniformity of EBT2 is also investigated. Methods: EBT2 films were used to measure the flatness of a {sup 60}Co field to provide a high-spatial resolution evaluation of the film uniformity. As a reference, the flatness of the {sup 60}Co field was also measured with Kodak EDR2 films. The EBT2 films were digitized with a flatbed document scanner 24, 48, and 72 h postexposure, and the images were analyzed using three methods: (1) the manufacturer-recommended marker-dye correction, (2) an in-house marker-dye correction, and (3) a net optical density (OD) measurement in the red color channel. The field flatness was calculated from orthogonal profiles through the center of the field using each analysis method, and the results were compared with the EDR2 measurements. Uncertainty was propagated through a dose calculation for each analysis method. The change in the measured field flatness for increasing times postexposure was also determined. Results: Both marker-dye correction methods improved the field flatness measured with EBT2 film relative to the net OD method, with a maximum improvement of 1% using the manufacturer-recommended correction. However, the manufacturer-recommended correction also resulted in a dose uncertainty an order of magnitude greater than the other two methods. The in-house marker-dye correction lowered the dose uncertainty relative to the net OD method. The measured field flatness did not exhibit any unidirectional change with increasing time postexposure and showed a maximum change of 0.3%. Conclusions: The marker dye in EBT2 can be used to improve the response uniformity of the film

  1. Advanced Fuels for LWRs: Fully-Ceramic Microencapsulated and Related Concepts FY 2012 Interim Report

    SciTech Connect (OSTI)

    R. Sonat Sen; Brian Boer; John D. Bess; Michael A. Pope; Abderrafi M. Ougouag

    2012-03-01

    This report summarizes the progress in the Deep Burn project at Idaho National Laboratory during the first half of fiscal year 2012 (FY2012). The current focus of this work is on Fully-Ceramic Microencapsulated (FCM) fuel containing low-enriched uranium (LEU) uranium nitride (UN) fuel kernels. UO2 fuel kernels have not been ruled out, and will be examined as later work in FY2012. Reactor physics calculations confirmed that the FCM fuel containing 500 mm diameter kernels of UN fuel has positive MTC with a conventional fuel pellet radius of 4.1 mm. The methodology was put into place and validated against MCNP to perform whole-core calculations using DONJON, which can interpolate cross sections from a library generated using DRAGON. Comparisons to MCNP were performed on the whole core to confirm the accuracy of the DRAGON/DONJON schemes. A thermal fluid coupling scheme was also developed and implemented with DONJON. This is currently able to iterate between diffusion calculations and thermal fluid calculations in order to update fuel temperatures and cross sections in whole-core calculations. Now that the DRAGON/DONJON calculation capability is in place and has been validated against MCNP results, and a thermal-hydraulic capability has been implemented in the DONJON methodology, the work will proceed to more realistic reactor calculations. MTC calculations at the lattice level without the correct burnable poison are inadequate to guarantee zero or negative values in a realistic mode of operation. Using the DONJON calculation methodology described in this report, a startup core with enrichment zoning and burnable poisons will be designed. Larger fuel pins will be evaluated for their ability to (1) alleviate the problem of positive MTC and (2) increase reactivity-limited burnup. Once the critical boron concentration of the startup core is determined, MTC will be calculated to verify a non-positive value. If the value is positive, the design will be changed to require

  2. Corrective Action Plan for Corrective Action Unit 563: Septic Systems, Nevada Test Site, Nevada

    SciTech Connect (OSTI)

    NSTec Environmental Restoration

    2009-03-31

    This Corrective Action Plan (CAP) has been prepared for Corrective Action Unit (CAU) 563, Septic Systems, in accordance with the Federal Facility Agreement and Consent Order. CAU 563 consists of four Corrective Action Sites (CASs) located in Areas 3 and 12 of the Nevada Test Site. CAU 563 consists of the following CASs: CAS 03-04-02, Area 3 Subdock Septic Tank CAS 03-59-05, Area 3 Subdock Cesspool CAS 12-59-01, Drilling/Welding Shop Septic Tanks CAS 12-60-01, Drilling/Welding Shop Outfalls Site characterization activities were performed in 2007, and the results are presented in Appendix A of the CAU 563 Corrective Action Decision Document. The scope of work required to implement the recommended closure alternatives is summarized below. CAS 03-04-02, Area 3 Subdock Septic Tank, contains no contaminants of concern (COCs) above action levels. No further action is required for this site; however, as a best management practice (BMP), all aboveground features (e.g., riser pipes and bumper posts) will be removed, the septic tank will be removed, and all open pipe ends will be sealed with grout. CAS 03-59-05, Area 3 Subdock Cesspool, contains no COCs above action levels. No further action is required for this site; however, as a BMP, all aboveground features (e.g., riser pipes and bumper posts) will be removed, the cesspool will be abandoned by filling it with sand or native soil, and all open pipe ends will be sealed with grout. CAS 12-59-01, Drilling/Welding Shop Septic Tanks, will be clean closed by excavating approximately 4 cubic yards (yd3) of arsenic- and chromium-impacted soil. In addition, as a BMP, the liquid in the South Tank will be removed, the North Tank will be removed or filled with grout and left in place, the South Tank will be filled with grout and left in place, all open pipe ends will be sealed with grout or similar material, approximately 10 yd3 of chlordane-impacted soil will be excavated, and debris within the CAS boundary will be removed. CAS 12

  3. Corrective Action Plan for Corrective Action Unit 543: Liquid Disposal Units, Nevada Test Site, Nevada

    SciTech Connect (OSTI)

    NSTec Environmental Restoration

    2007-04-01

    Corrective Action Unit (CAU) 543: Liquid Disposal Units is listed in Appendix III of the ''Federal Facility Agreement and Consent Order'' (FFACO) which was agreed to by the state of Nevada, the U.S. Department of Energy (DOE), and the U.S. Department of Defense (FFACO, 1996). CAU 543 sites are located in Areas 6 and 15 of the Nevada Test Site (NTS), which is approximately 65 miles northwest of Las Vegas, Nevada. CAU 543 consists of the following seven Corrective Action Sites (CASs) (Figure 1): CAS 06-07-01, Decon Pad; CAS 15-01-03, Aboveground Storage Tank; CAS 15-04-01, Septic Tank; CAS 15-05-01, Leachfield; CAS 15-08-01, Liquid Manure Tank; CAS 15-23-01, Underground Radioactive Material Area; and CAS 15-23-03, Contaminated Sump, Piping. All Area 15 CASs are located at the former U.S. Environmental Protection Agency (EPA) Farm, which operated from 1963 to 1981 and was used to support animal experiments involving the uptake of radionuclides. Each of the Area 15 CASs, except CAS 15-23-01, is associated with the disposal of waste effluent from Building 15-06, which was the primary location of the various tests and experiments conducted onsite. Waste effluent disposal from Building 15-06 involved piping, sumps, outfalls, a septic tank with leachfield, underground storage tanks, and an aboveground storage tank (AST). CAS 15-23-01 was associated with decontamination activities of farm equipment potentially contaminated with radiological constituents, pesticides, and herbicides. While the building structures were removed before the investigation took place, all the original tanks, sumps, piping, and concrete building pads remain in place. The Area 6 CAS is located at the Decontamination Facility in Area 6, a facility which operated from 1971 to 2001 and was used to decontaminate vehicles, equipment, clothing, and other materials that had become contaminated during nuclear testing activities. The CAS includes the effluent collection and distribution systems for Buildings

  4. The CASTOR-V/21 PWR spent-fuel storage cask: Testing and analyses: Interim report

    SciTech Connect (OSTI)

    Dziadosz, D.; Moore, E.V.; Creer, J.M.; McCann, R.A.; McKinnon, M.A.; Tanner, J.E.; Gilbert, E.R.; Goodman, R.L.; Schoonen, D.H.; Jensen, M.

    1986-11-01

    A performance test of a Gesellschaft fuer Nuklear Service CASTOR-V/21 pressurized water reactor (PWR) spent fuel storage cask was performed. The test was the first of a series of cask performance tests planned under a cooperative agreement between Virginia Power and the US Department of Energy. The performance test consisted of loading the CASTOR-V/21 cask with 21 PWR spent fuel assemblies from Virginia Power's Surry reactor. Cask surface and fuel assembly guide tube temperatures, and cask surface gamma and neutron dose rates were measured. Testing was performed with vacuum, nitrogen, and helium backfill environments in both vertical and horizontal cask orientations. Limited spent fuel integrity data were also obtained. Results of the performance test indicate the CASTOR-V/21 cask exhibited exceptionally good heat transfer performance which exceeded design expectations. Peak cladding temperatures with helium and nitrogen backfills in a vertical cast orientation and with helium in a horizontal orientation were less than the allowable of 380/sup 0/C with a total cask heat load of 28 kW. Significant convection heat transfer was present in vertical nitrogen and helium test runs as indicated by peak temperatures occurring in the upper regions of the fuel assemblies. Pretest temperature predictions of the HYDRA heat transfer computer program were in good agreement with test data, and post-test predictions agreed exceptionally well (25/sup 0/C) with data. Cask surface gamma and neutron dose rates were measured to be less than the design goal of 200 mrem/h. Localized peaks as high as 163 mrem/h were measured on the side of the cask, but peak dose rates of <75 mrem/h can easily be achieved with minor refinements to the gamma shielding design. From both heat transfer and shielding perspectives, the CASTOR-V/21 cask can, with minor refinements, be effectively implemented at reactor sites and central storage facilities for safe storage of spent fuel.

  5. Corrective Action Decision Document/Closure Report for Corrective Action Unit 567: Miscellaneous Soil Sites - Nevada National Security Site, Nevada

    SciTech Connect (OSTI)

    Matthews, Patrick

    2014-12-01

    This Corrective Action Decision Document/Closure Report presents information supporting the closure of Corrective Action Unit (CAU) 567: Miscellaneous Soil Sites, Nevada National Security Site, Nevada. The purpose of this Corrective Action Decision Document/Closure Report is to provide justification and documentation supporting the recommendation that no further corrective action is needed for CAU 567 based on the implementation of the corrective actions. The corrective actions implemented at CAU 567 were developed based on an evaluation of analytical data from the CAI, the assumed presence of COCs at specific locations, and the detailed and comparative analysis of the CAAs. The CAAs were selected on technical merit focusing on performance, reliability, feasibility, safety, and cost. The implemented corrective actions meet all requirements for the technical components evaluated. The CAAs meet all applicable federal and state regulations for closure of the site. Based on the implementation of these corrective actions, the DOE, National Nuclear Security Administration Nevada Field Office provides the following recommendations: • No further corrective actions are necessary for CAU 567. • The Nevada Division of Environmental Protection issue a Notice of Completion to the DOE, National Nuclear Security Administration Nevada Field Office for closure of CAU 567. • CAU 567 be moved from Appendix III to Appendix IV of the FFACO.

  6. Corrective Action Investigation Plan for Corrective Action Unit 552: Area 12 Muckpile and Ponds, Nevada Test Site, Nevada: Revision 0

    SciTech Connect (OSTI)

    U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office

    2004-04-06

    This Corrective Action Investigation Plan contains the U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office's approach for collecting the data necessary to evaluate corrective action alternatives appropriate for the closure of Corrective Action Unit (CAU) 552: Area 12 Muckpile and Ponds, Nevada Test Site (NTS), Nevada, under the Federal Facility Agreement and Consent Order. Located in Area 12 on the NTS, CAU 552 consists of two Corrective Action Sites (CASs): 12-06-04, Muckpile; 12-23-05, Ponds. Corrective Action Site 12-06-04 in Area 12 consists of the G-Tunnel muckpile, which is the result of tunneling activities. Corrective Action Site 12-23-05 consists of three dry ponds adjacent to the muckpile. The toe of the muckpile extends into one of the ponds creating an overlap of two CASs. The purpose of the investigation is to ensure that adequate data are collected to provide sufficient and reliable information to identify, evaluate, and select technic ally viable corrective actions. The results of the field investigation will support a defensible evaluation of corrective action alternatives in the corrective action decision document.

  7. New Surface Meteorological Measurements at SGP,

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    NM, March 22 - 26, 2004 1 New Surface Meteorological Measurements at SGP, and Their Use ... Work is in progress to combine the MWR-scaling and time-lag corrections into a new ARM ...

  8. Robotic real-time translational and rotational head motion correction during frameless stereotactic radiosurgery

    SciTech Connect (OSTI)

    Liu, Xinmin; Belcher, Andrew H.; Grelewicz, Zachary; Wiersma, Rodney D.

    2015-06-15

    Purpose: To develop a control system to correct both translational and rotational head motion deviations in real-time during frameless stereotactic radiosurgery (SRS). Methods: A novel feedback control with a feed-forward algorithm was utilized to correct for the coupling of translation and rotation present in serial kinematic robotic systems. Input parameters for the algorithm include the real-time 6DOF target position, the frame pitch pivot point to target distance constant, and the translational and angular Linac beam off (gating) tolerance constants for patient safety. Testing of the algorithm was done using a 4D (XY Z + pitch) robotic stage, an infrared head position sensing unit and a control computer. The measured head position signal was processed and a resulting command was sent to the interface of a four-axis motor controller, through which four stepper motors were driven to perform motion compensation. Results: The control of the translation of a brain target was decoupled with the control of the rotation. For a phantom study, the corrected position was within a translational displacement of 0.35 mm and a pitch displacement of 0.15° 100% of the time. For a volunteer study, the corrected position was within displacements of 0.4 mm and 0.2° over 98.5% of the time, while it was 10.7% without correction. Conclusions: The authors report a control design approach for both translational and rotational head motion correction. The experiments demonstrated that control performance of the 4D robotic stage meets the submillimeter and subdegree accuracy required by SRS.

  9. Large-Actuator-Number Horizontal Path Correction of Atmospheric Turbulence utilizing an Interferometric Phase Conjugate Engine

    SciTech Connect (OSTI)

    Baker, K L; Stappaerts, E A; Gavel, D; Tucker, J; Silva, D A; Wilks, S C; Olivier, S S; Olsen, J

    2004-08-25

    An adaptive optical system used to correct horizontal beam propagation paths has been demonstrated. This system utilizes an interferometric wave-front sensor and a large-actuator-number MEMS-based spatial light modulator to correct the aberrations incurred by the beam after propagation along the path. Horizontal path correction presents a severe challenge to adaptive optics systems due to the short atmospheric transverse coherence length and the high degree of scintillation incurred by laser propagation along these paths. Unlike wave-front sensors that detect phase gradients, however, the interferometric wave-front sensor measures the wrapped phase directly. Because the system operates with nearly monochromatic light and uses a segmented spatial light modulator, it does not require that the phase be unwrapped to provide a correction and it also does not require a global reconstruction of the wave-front to determine the phase as required by gradient detecting wave-front sensors. As a result, issues with branch points are eliminated. Because the atmospheric probe beam is mixed with a large amplitude reference beam, it can be made to operate in a photon noise limited regime making its performance relatively unaffected by scintillation. The MEMS-based spatial light modulator in the system contains 1024 pixels and is controlled to speeds in excess of 800 Hz, enabling its use for correction of horizontal path beam propagation. In this article results are shown of both atmospheric characterization with the system and open loop horizontal path correction of a 1.53 micron laser by the system. To date Strehl ratios of greater than 0.5 have been achieved.

  10. Device for wavefront correction in an ultra high power laser

    DOE Patents [OSTI]

    Ault, Earl R. (Livermore, CA); Comaskey, Brian J. (Walnut Creek, CA); Kuklo, Thomas C. (Oakdale, CA)

    2002-01-01

    A system for wavefront correction in an ultra high power laser. As the laser medium flows past the optical excitation source and the fluid warms its index of refraction changes creating an optical wedge. A system is provided for correcting the thermally induced optical phase errors.

  11. Self-interaction corrections in density functional theory

    SciTech Connect (OSTI)

    Tsuneda, Takao; Hirao, Kimihiko

    2014-05-14

    Self-interaction corrections for Kohn-Sham density functional theory are reviewed for their physical meanings, formulations, and applications. The self-interaction corrections get rid of the self-interaction error, which is the sum of the Coulomb and exchange self-interactions that remains because of the use of an approximate exchange functional. The most frequently used self-interaction correction is the Perdew-Zunger correction. However, this correction leads to instabilities in the electronic state calculations of molecules. To avoid these instabilities, several self-interaction corrections have been developed on the basis of the characteristic behaviors of self-interacting electrons, which have no two-electron interactions. These include the von Weizsäcker kinetic energy and long-range (far-from-nucleus) asymptotic correction. Applications of self-interaction corrections have shown that the self-interaction error has a serious effect on the states of core electrons, but it has a smaller than expected effect on valence electrons. This finding is supported by the fact that the distribution of self-interacting electrons indicates that they are near atomic nuclei rather than in chemical bonds.

  12. The effects of interim flow operations from Glen Canyon Dam on Colorado River sand bars in the Grand Canyon, Arizona

    SciTech Connect (OSTI)

    Kaplinski, M.A.; Hazel, J.E.; Beus, S.S. . Geology Dept.); Stevens, L.E. . NPS Cooperative Parks Studies Unit); Mayes, H.B. )

    1993-04-01

    Discharges from Glen Canyon Dam (GCD) affect the geomorphology and stability of downstream alluvial sediment deposits. To protect downstream resources, the US DOI mandated interim flow criteria (IFC) on 1 August, 1991. The IFC consist of reduced daily fluctuations (226--566 m[sup 3]/s) and reduced ramping rates (42.5--57 m[sup 3]/s/hr), the primary objective of which is to maintain sediment storage in the river system by minimizing sediment transport. This study was initiated to determine the effectiveness of the IFC in achieving this objective. The authors examined whether reduced daily fluctuations lead to subaerial sand bar erosion and increased subaqueous sediment storage. They collected and analyzed topographic and bathymetric survey data from sand bars throughout the Colorado River corridor in Sept/Oct, 1991 and in Oct/Nov, 1992 to compare changes in sand bar morphology. They examined changing topography due to GCD operation in what they termed the hydrologically active zone (HAZ), that portion of the sand bar exposed to daily dam operations (142--900 m[sup 3]/s stage elevations). Volumes within the HAZ and profiles across this zone were generated from these sediment deposits. Their preliminary results show that, in general, erosion of sediment at higher bar elevations was coincident with deposition along lower parts of the bar platform. The observed response to IFC elevation in order to maintain sediment deposits for Colorado River corridor bio-diversity (e.g., fisheries habitats). 88% of sand bars that showed significant volume gain were preceded by significant volume loss, implying that antecedent conditions are an important factor in sand bar response to GCD operations. Sediment transport capacity was reduced as evidenced by increased sediment storage in recirculation zones and sediment infilling of eddy return channels. The authors conclude that IFC are achieving their primary objective of maintaining sediment storage within the river corridor.

  13. Deep Vadose Zone Treatability Test for the Hanford Central Plateau: Interim Post-Desiccation Monitoring Results, Fiscal Year 2014

    SciTech Connect (OSTI)

    Truex, Michael J.; Strickland, Christopher E.; Johnson, Christian D.; Johnson, Timothy C.; Clayton, Ray E.; Chronister, Glen B.

    2014-09-01

    Over decades of operation, the U.S. Department of Energy (DOE) and its predecessors have released nearly 2 trillion L (450 billion gal.) of liquid into the vadose zone at the Hanford Site. Much of this discharge of liquid waste into the vadose zone occurred in the Central Plateau, a 200 km2 (75 mi2) area that includes approximately 800 waste sites. Some of the inorganic and radionuclide contaminants in the deep vadose zone at the Hanford Site are at depths below the limit of direct exposure pathways, but may need to be remediated to protect groundwater. The Tri-Party Agencies (DOE, U.S. Environmental Protection Agency, and Washington State Department of Ecology) established Milestone M 015 50, which directed DOE to submit a treatability test plan for remediation of technetium-99 (Tc-99) and uranium in the deep vadose zone. These contaminants are mobile in the subsurface environment and have been detected at high concentrations deep in the vadose zone, and at some locations have reached groundwater. Testing technologies for remediating Tc-99 and uranium will also provide information relevant for remediating other contaminants in the vadose zone. A field test of desiccation is being conducted as an element of the DOE test plan published in March 2008 to meet Milestone M 015 50. The active desiccation portion of the test has been completed. Monitoring data have been collected at the field test site during the post-desiccation period and are reported herein. This is an interim data summary report that includes about 3 years of post-desiccation monitoring data. The DOE field test plan proscribes a total of 5 years of post-desiccation monitoring.

  14. Corrective Action Investigation Plan for Corrective Action Unit 106: Areas 5, 11 Frenchman Flat Atmospheric Sites, Nevada Test Site, Nevada, Revision 0

    SciTech Connect (OSTI)

    Patrick Matthews

    2010-04-01

    -based final action level. The TED will be calculated as the total of separate estimates of internal and external doses. Results from the analysis of soil samples collected from sample plots will be used to calculate internal radiological dose. Thermoluminescent dosimeters placed at the center of each sample plot will be used to measure external radiological dose. The presence and nature of contamination from other types of releases (such as migration and excavation as well as any potential releases discovered during the investigation) will be evaluated using soil samples collected from the locations most likely containing contamination, if present. Appendix A provides a detailed discussion of the DQO methodology and the DQOs specific to each CAS. The scope of the corrective action investigation for CAU 106 includes the following activities: •Conduct radiological surveys. •Collect and submit environmental samples for laboratory analysis to determine internal dose rates and the presence of contaminants of concern. •If contaminants of concern are present, collect additional samples to define the extent of the contamination and determine the area where TED at the site exceeds final action levels (i.e., corrective action boundary). •Collect samples of investigation-derived waste, as needed, for waste management purposes.

  15. Determining Remaining Useful Life of Aging Cables in Nuclear Power Plants – Interim Study FY13

    SciTech Connect (OSTI)

    Simmons, Kevin L.; Fifield, Leonard S.; Westman, Matthew P.; Ramuhalli, Pradeep; Pardini, Allan F.; Tedeschi, Jonathan R.; Jones, Anthony M.

    2013-09-27

    The most important criterion for cable performance is its ability to withstand a design-basis accident. With nearly 1000 km of power, control, instrumentation, and other cables typically found in an NPP, it would be a significant undertaking to inspect all of the cables. Degradation of the cable jacket, electrical insulation, and other cable components is a key issue that is likely to affect the ability of the currently installed cables to operate safely and reliably for another 20 to 40 years beyond the initial operating life. The development of one or more nondestructive evaluation (NDE) techniques and supporting models that could assist in determining the remaining life expectancy of cables or their current degradation state would be of significant interest. The ability to nondestructively determine material and electrical properties of cable jackets and insulation without disturbing the cables or connections has been deemed essential. Currently, the only technique accepted by industry to measure cable elasticity (the gold standard for determining cable insulation degradation) is the indentation measurement. All other NDE techniques are used to find flaws in the cable and do not provide information to determine the current health or life expectancy. There is no single NDE technique that can satisfy all of the requirements needed for making a life-expectancy determination, but a wide range of methods have been evaluated for use in NPPs as part of a continuous evaluation program. The commonly used methods are indentation and visual inspection, but these are only suitable for easily accessible cables. Several NDE methodologies using electrical techniques are in use today for flaw detection but there are none that can predict the life of a cable. There are, however, several physical and chemical ptoperty changes in cable insulation as a result of thermal and radiation damage. In principle, these properties may be targets for advanced NDE methods to provide early

  16. Conversion of forest residues to a methane-rich gas: Interim Report

    SciTech Connect (OSTI)

    Feldmann, H.G.; Paisley, M.A.; Appelbaum, H.R.

    1986-03-01

    A process is being developed that produces a fuel gas with a heating value of 500 Btu/SCF from diverse forms of biomass, including shredded bark, wood chips, and sawdust. The system uses a high throughput, non-oxygen gasifier that employs sand circulation to supply process heat. Results obtained with a 10-inch I.D. gasifier are presented and compared with those in a 6-inch I.D. reactor. Feed rates up to 12 tons/day (dry) have been achieved corresponding to a specific wood throughput of 2000 lbs/ft/sup 2/-hr. Gas compositions in the two reactors are in excellent agreement and performance in the larger reactor, as measured by carbon conversion, is significantly improved. Cost projections comparing this process with direct combustion are presented that indicate gasification technology should have very significant cost advantages for both generation of plant steam and cogeneration of electricity. 5 refs., 14 figs., 5 tabs.

  17. Stress corrosion cracking of Alloys 600 and 182 in BWR environments. Interim report

    SciTech Connect (OSTI)

    Ljungberg, L.G.; Hofling, C.G.; Sahlberg, A.; Moeller, J.

    1992-05-01

    Wrought Alloy 600 and weldments of Alloy 182 are being tested for initiation and propagation of intergranular stress corrosion cracking (IGSCC). Crack initiation is tested on compact tension (CT) specimens with U-notches of various radii under enhanced crevice conditions, in a test loop in a Swedish BWR. After one year exposure there was initiation of IGSCC in a large portion of the Alloy 182 specimens, but nearly no initiation in Alloy 600. Crack propagation was measured in a laboratory loop on CT specimens under constant or cyclic load. Low carbon Alloy 600, or Alloy 182 high in titanium and niobium versus carbon, cracked at lower rates than material with high carbon activity. Materials with low concentrations of phosphorus and sulfur cracked slower than those high in these elements in clean environment, but no such effect was found in environment with sulfate. Alloy 182 weld metal generally cracked at higher rates than Alloy 600.

  18. Corrective Action Investigation plan for Corrective Action Unit 263: Area 25 Building 4839 Leachfield, Nevada Test Site, Nevada, March 1999

    SciTech Connect (OSTI)

    ITLV

    1999-03-01

    The Corrective Action Investigation Plan for Corrective Action Unit 263, the Area 25 Building 4839 Leachfield, has been developed in accordance with the Federal Facility Agreement and Consent Order that was agreed to by the US Department of Energy, Nevada Operations Office; the Nevada Division of Environmental Protection; and the US Department of Defense. Corrective Action Unit 263 is comprised of the Corrective Action Site 25-05-04 sanitary leachfield and associated collection system. This Corrective Action Investigation Plan is used in combination with the Work Plan for Leachfield Corrective Action Units: Nevada Test Site and Tonopah Test Range, Nevada (DOE/NV, 1998d). The Leachfield Work Plan was developed to streamline investigations at Leachfield Corrective Action Units by incorporating management, technical, quality assurance, health and safety, public involvement, field sampling, and waste management information common to a set of Corrective Action Units with similar site histories and characteristics into a single document that can be referenced. This Corrective Action Investigation Plan provides investigative details specific to Corrective Action Unit 263. Corrective Action Unit 263 is located southwest of Building 4839, in the Central Propellant Storage Area. Operations in Building 4839 from 1968 to 1996 resulted in effluent releases to the leachfield and associated collection system. In general, effluent released to the leachfield consisted of sanitary wastewater from a toilet, urinal, lavatory, and drinking fountain located within Building 4839. The subsurface soils in the vicinity of the collection system and leachfield may have been impacted by effluent containing contaminants of potential concern generated by support activities associated with the Building 4839 operations.

  19. Two loop correction to interference in $$gg \\to ZZ$$

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Campbell, John M.; Ellis, R. Keith; Czakon, Michal; Kirchner, Sebastian

    2016-08-01

    Here, we present results for the production of a pair of on-shell Z bosons via gluon-gluon fusion. This process occurs both through the production and decay of the Higgs boson, and through continuum production where the Z boson couples to a loop of massless quarks or to a massive quark. We calculate the interference of the two processes and its contribution to the cross section up to and including order O(αmore » $$_{s}^{3}$$ ). The two-loop contributions to the amplitude are all known analytically, except for the continuum production through loops of top quarks of mass m. The latter contribution is important for the invariant mass of the two Z bosons, (as measured by the mass of their leptonic decay products, m$$_{4l}$$), in a regime where m$$_{4l}$$ ≥ 2m because of the contributions of longitudinal bosons. We examine all the contributions to the virtual amplitude involving top quarks, as expansions about the heavy top quark limit combined with a conformal mapping and Padé approximants. Comparison with the analytic results, where known, allows us to assess the validity of the heavy quark expansion, and it extensions. We give results for the NLO corrections to this interference, including both real and virtual radiation.« less

  20. Microsoft Word - corr measures addendum.doc

    Office of Legacy Management (LM)

    DOE-LM/GJ1241-2006 Pinellas Environmental Restoration Project Building 100 Area Corrective Measures Study Report Addendum July 2006 Work Performed by S.M. Stoller Corporation under DOE Contract No. DE-AC01-02GJ79491 for the U.S. Department of Energy Office of Legacy Management, Grand Junction, Colorado This page intentionally left blank U.S. Department of Energy Building 100 Area Corrective Measures Study Report Addendum July 2006 Page iii Contents Acronyms and Abbreviations