Powered by Deep Web Technologies
Note: This page contains sample records for the topic "integrated test plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


1

Integrated test vehicle program plan: revision C  

DOE Green Energy (OSTI)

This edition dated August 26, 1977, is Revision C of the Integrated Test Vehicle, Program Plan, Phase II - Deliverable Item 2-7-1. The original edition was issued on May 27, 1977. Corrections were made and issued as Proposed Modifications for Integrated Test Vehicle, Program Plan, dated July 8, 1977. For the purpose of documenting changes, the July 8, 1977, version is caled Revision A. The edition dated August 5, 1977, is called Revision B. Each paragraph in this edition is marked to indicate technical changes from previous editions.

Not Available

1977-08-26T23:59:59.000Z

2

Test plan  

U.S. Energy Information Administration (EIA)

3.0 TEST PLAN METHODOLOGY 8. 3.1 Assumptions 8. 3.2 Methodology 8. 4.0 COMMENTS ON INITIAL VIEW OF THE DATA 16 1.0 INTRODUCTION. EIA tasked Allied ...

3

Plans for an Integrated Front-End Test Stand at the Spallation Neutron Source  

SciTech Connect

A spare Radio-Frequency Quadrupole (RFQ) is presently being fabricated by industry with delivery to Oak Ridge National Laboratory planned in late 2012. The establishment of a test stand at the Spallation Neutron Source site is underway so that complete acceptance testing can be performed during the winter of 2012-2013. This activity is the first step in the establishment of an integrated front-end test stand that will include an ion source, low-energy beam transport (LEBT), RFQ, medium-energy beam transport, diagnostics, and a beam dump. The test stand will be capable of delivering an H- ion beam of up to 50 mA with a pulse length of 1 ms and a repetition rate of 60 Hz or a proton beam of up to 50 mA, 100us, 1Hz. The test stand will enable the following activities: complete ion source characterization; development of a magnetic LEBT chopper; development of a two-source layout; development of beam diagnostics; and study of beam dynamics of high intensity beam.

Champion, Mark S [ORNL; Aleksandrov, Alexander V [ORNL; Crofford, Mark T [ORNL; Heidenreich, Dale A [ORNL; Kang, Yoon W [ORNL; Moss, John [ORNL; Roseberry, Jr., R Tom [ORNL; Schubert, James Phillip [ORNL

2012-01-01T23:59:59.000Z

4

10-MWe solar-thermal central-receiver pilot plant, solar-facilities design integration: system integration laboratory test plan (RADL item 6-4)  

DOE Green Energy (OSTI)

A general demonstration test plan is provided for the activities to be accomplished at the Systems Integration Laboratory. The Master Control System, Subsystem Distributed Process Control, Representative Signal Conditioning Units, and Redline Units from the Receiver Subsystem and the Thermal Storage Subsystem and other external interface operational functions will be integrated and functionally demonstrated. The Beckman Multivariable Control Unit will be tested for frequency response, static checks, configuration changes, switching transients, and input-output interfaces. Maximum System Integration Laboratory testing will demonstrate the operational readiness of Pilot Plant controls and external interfaces that are available. Minimum System Integration Laboratory testing will be accomplished with reduced set of hardware, which will provide capability for continued development and demonstration of Operational Control System plant control application software. Beam Control System Integration Laboratory testing will demonstrate the operational readiness of the Beam Control System equipment and software. (LEW)

Not Available

1980-10-01T23:59:59.000Z

5

Performance Criteria and Test Plans for Grid Integration of Renewable Generation  

Science Conference Proceedings (OSTI)

Distribution utilities are expected to face challenges in the grid integration of renewable generation as relative numbers and penetration levels increase. This report describes the ongoing development of performance criteria, test protocols and facilities to support the smooth integration of distributed generation (DG). It is specifically aimed at requirements for relatively high penetration of distributed generation, with emphasis on inverters as the primary interfacing device. Brief discussions of exi...

2010-12-31T23:59:59.000Z

6

Primer on gas integrated resource planning  

Science Conference Proceedings (OSTI)

This report discusses the following topics: gas resource planning: need for IRP; gas integrated resource planning: methods and models; supply and capacity planning for gas utilities; methods for estimating gas avoided costs; economic analysis of gas utility DSM programs: benefit-cost tests; gas DSM technologies and programs; end-use fuel substitution; and financial aspects of gas demand-side management programs.

Goldman, C.; Comnes, G.A.; Busch, J.; Wiel, S. [Lawrence Berkeley Lab., CA (United States)

1993-12-01T23:59:59.000Z

7

Integrated formal operations plan  

SciTech Connect

The concept of formal operations (that is, a collection of business practices to assure effective, accountable operations) has vexed the Laboratory for many years. To date most attempts at developing such programs have been based upon rigid, compliance-based interpretations of a veritable mountain of Department of Energy (DOE) orders, directives, notices, and standards. These DOE dictates seldom take the broad view but focus on highly specialized programs isolated from the overall context of formal operations. The result is a confusing array of specific, and often contradictory, requirements that produce a patchwork of overlapping niche programs. This unnecessary duplication wastes precious resources, dramatically increases the complexity of our work processes, and communicates a sense of confusion to our customers and regulators. Coupled with the artificial divisions that have historically existed among the Laboratory`s formal operations organizations (quality assurance, configuration management, records management, training, etc.), this approach has produced layers of increasingly vague and complex formal operations plans, each of which interprets its parent and adds additional requirements of its own. Organizational gridlock ensues whenever an activity attempts to implement these bureaucratic monstrosities. The integrated formal operations plan presented is to establish a set of requirements that must be met by an integrated formal operations program, assign responsibilities for implementation and operation of the program, and specify criteria against which the performance of the program will be measured. The accountable line manager specifies the items, processes, and information (the controlled elements) to which the formal operations program specified applies. The formal operations program is implemented using a graded approach based on the level of importance of the various controlled elements and the scope of the activities in which they are involved.

Cort, G.; Dearholt, W.; Donahue, S.; Frank, J.; Perkins, B.; Tyler, R.; Wrye, J.

1994-01-05T23:59:59.000Z

8

National conference on integrated resource planning: Proceedings  

Science Conference Proceedings (OSTI)

Until recently, state regulators have focused most of their attention on the development of least-cost or integrated resource planning (IRP) processes for electric utilities. A number of commissions are beginning to scrutinize the planning processes of local gas distribution companies (LDCs) because of the increased control that LDCs have over their purchased gas costs (as well as the associated risks) and because of questions surrounding the role and potential of gas end-use efficiency options. Traditionally, resource planning (LDCs) has concentrated on options for purchasing and storing gas. Integrated resource planning involves the creation of a process in which supply-side and demand-side options are integrated to create a resource mix that reliably satisfies customers' short-term and long-term energy service needs at the lowest cost. As applied to gas utilities, an integrated resource plan seeks to balance cost and reliability, and should not be interpreted simply as the search for lowest commodity costs. The National Association of Regulatory Utility Commissioners' (NARUC) Energy Conservation committee asked Lawrence Berkeley Laboratory (LBL) to survey state PUCs to determine the extent to which they have undertaken least cost planning for gas utilities. The survey included the following topics: status of state PUC least-cost planning regulations and practices for gas utilities; type and scope of natural gas DSM programs in effect, including fuel substitution; economic tests and analysis methods used to evaluate DSM programs; relationship between prudency reviews of gas utility purchasing practices and integrated resource planning; key regulatory issued facing gas utilities during the next five years.

Not Available

1991-01-01T23:59:59.000Z

9

National conference on integrated resource planning: Proceedings  

Science Conference Proceedings (OSTI)

Until recently, state regulators have focused most of their attention on the development of least-cost or integrated resource planning (IRP) processes for electric utilities. A number of commissions are beginning to scrutinize the planning processes of local gas distribution companies (LDCs) because of the increased control that LDCs have over their purchased gas costs (as well as the associated risks) and because of questions surrounding the role and potential of gas end-use efficiency options. Traditionally, resource planning (LDCs) has concentrated on options for purchasing and storing gas. Integrated resource planning involves the creation of a process in which supply-side and demand-side options are integrated to create a resource mix that reliably satisfies customers` short-term and long-term energy service needs at the lowest cost. As applied to gas utilities, an integrated resource plan seeks to balance cost and reliability, and should not be interpreted simply as the search for lowest commodity costs. The National Association of Regulatory Utility Commissioners` (NARUC) Energy Conservation committee asked Lawrence Berkeley Laboratory (LBL) to survey state PUCs to determine the extent to which they have undertaken least cost planning for gas utilities. The survey included the following topics: status of state PUC least-cost planning regulations and practices for gas utilities; type and scope of natural gas DSM programs in effect, including fuel substitution; economic tests and analysis methods used to evaluate DSM programs; relationship between prudency reviews of gas utility purchasing practices and integrated resource planning; key regulatory issued facing gas utilities during the next five years.

Not Available

1991-12-31T23:59:59.000Z

10

Integrating Infrastructure Planning: The Role of Schools  

E-Print Network (OSTI)

Integrating Infrastructure Planning: The Role of Schools B Ypolice protection, and infrastructure that makes citiesplan to upgrade critical infrastructure. The plan calls for

McKoy, Deborah; Vincent, Jeffrey M.; Makarewicz, Carrie

2008-01-01T23:59:59.000Z

11

Acceptance Test Plan | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Acceptance Test Plan Acceptance Test Plan This template is used to document the plan for performing the systems acceptance test, the roles and responsibilities of individuals...

12

Integrated Planning and Performance Management  

NLE Websites -- All DOE Office Websites (Extended Search)

DOESC Scientific Facilities Strategic Plan (20 years, major capital projects) * DOE Strategic Plan (7-10 years) * DOE (HEP)Fermilab Strategic Plan (10 years) * FRAFNAL Plan for...

13

Specific test and evaluation plan  

SciTech Connect

The purpose of this Specific Test and Evaluation Plan (STEP) is to provide a detailed written plan for the systematic testing of modifications made to the 241-AX-B Valve Pit by the W-314 Project. The STEP develops the outline for test procedures that verify the system`s performance to the established Project design criteria. The STEP is a lower tier document based on the W-314 Test and Evaluation Plan (TEP). Testing includes Validations and Verifications (e.g., Commercial Grade Item Dedication activities), Factory Acceptance Tests (FATs), installation tests and inspections, Construction Acceptance Tests (CATs), Acceptance Test Procedures (ATPs), Pre-Operational Test Procedures (POTPs), and Operational Test Procedures (OTPs). It should be noted that POTPs are not required for testing of the transfer line addition. The STEP will be utilized in conjunction with the TEP for verification and validation.

Hays, W.H.

1998-03-20T23:59:59.000Z

14

Monitored Geologic Repository Test Evaluation Plan  

SciTech Connect

The Monitored Geologic Repository test & evaluation program will specify tests, demonstrations, examinations, and analyses, and describe procedures to conduct and document testing necessary to verify meeting Monitored Geologic Repository requirements for a safe and effective geologic repository for radioactive waste. This test program will provide assurance that the repository is performing as designed, and that the barriers perform as expected; it will also develop supporting documentation to support the licensing process and to demonstrate compliance with codes, standards, and regulations. This comprehensive program addresses all aspects of verification from the development of test requirements to the performance of tests and reporting of the test results. The ''Monitored Geologic Repository Test & Evaluation Plan'' provides a detailed description of the test program approach necessary to achieve the above test program objectives. This test plan incorporates a set of test phases focused on ensuring repository safety and operational readiness and implements a project-wide integrated product management team approach to facilitate test program planning, analysis, and implementation. The following sections provide a description of the individual test phases, the methodology for test program planning and analyses, and the management approach for implementing these activities.

M.B. Skorska

2002-01-02T23:59:59.000Z

15

Integrated Planning and Performance Management  

NLE Websites -- All DOE Office Websites (Extended Search)

Performance Management (IPPM) Head Program Administrator Planning Coordination Performance Analysis Chief Operating Officer Risk Analysis Lab PlanningGoal Setting Process ...

16

AEP Interoperability Test Plan  

Science Conference Proceedings (OSTI)

To meet consumers' growing electricity demand and society's desire to reduce carbon dioxide emissions from electric generation while ensuring the continued availability of economical and reliable electricity, AEP has partnered with the U.S. Department of Energy (DOE) in the AEP Ohio gridSMARTsm Demonstration Project. The project will integrate commercially available products, new technologies, and new consumer products and services within a single, secure, two-way communication network between the utilit...

2010-08-10T23:59:59.000Z

17

7.0 - Integrated Acquisition Planning Process  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

0 (August 2006) 0 (August 2006) 1 INTEGRATING ACQUISITION PLANNING PROCESSES - AN OVERVIEW REFERENCES 1. FAR Part 7 Acquisition Planning 2. FAR Part 34 Major System Acquisition 3. Acquisition Letter 2005-08R, Small Business Programs 4. Acquisition Guide Chapter 7.1, Acquisition Planning 5. Acquisition Guide Chapter 42.5, Contract Management Planning 6. DOE O 580.1 Department of Energy Property Management Program 7. DOE O 413.3 Program and Project Management for the Acquisition of Capital Assets Guiding Principles n Acquisition planning benefits from integrating independent planning processes and a team approach that includes appropriate representation

18

Heat pipe testing program test plan  

SciTech Connect

A test plan is given which describes the tests to be conducted on several typical solar receiver heat pipes. The hardware to be used, test fixtures and rationale of the test program are discussed. The program objective is to perform life testing under simulated receiver conditions, and to conduct performance tests with selected heat pipes to further map their performance, particularly with regard to their transient behavior. Performance requirements are defined. Test fixtures designed for the program are described in detail, and their capabilities for simulating the receiver conditions and their limitations are discussed. The heat pipe design is given. (LEW)

Bienert, W.B.

1980-03-14T23:59:59.000Z

19

Specific test and evaluation plan  

SciTech Connect

The purpose of this Specific Test and Evaluation Plan (STEP) is to provide a detailed written plan for the systematic testing of modifications made to the 241-AN-A Valve Pit by the W-314 Project. The STEP develops the outline for test procedures that verify the system`s performance to the established Project design criteria. The STEP is a ``lower tier`` document based on the W-314 Test and Evaluation Plan (TEP) This STEP encompasses all testing activities required to demonstrate compliance to the project design criteria as it relates to the modifications of the AN-A valve pit. The Project Design Specifications (PDS) identify the specific testing activities required for the Project. Testing includes Validations and Verifications (e.g., Commercial Grade Item Dedication activities), Factory Acceptance Tests (FATs), installation tests and inspections, Construction Acceptance Tests (CATs), Acceptance Test Procedures (ATPs), Pre-Operational Test Procedures (POTPs), and Operational Test Procedures (OTPs). It should be noted that POTPs are not required for testing of the modifications to the 241-AN-A Valve Pit. The STEP will be utilized in conjunction with the TEP for verification and validation.

Hays, W.H.

1997-12-09T23:59:59.000Z

20

Spent nuclear fuel project integrated schedule plan  

SciTech Connect

The Spent Nuclear Fuel Integrated Schedule Plan establishes the organizational responsibilities, rules for developing, maintain and status of the SNF integrated schedule, and an implementation plan for the integrated schedule. The mission of the SNFP on the Hanford site is to provide safe, economic, environmentally sound management of Hanford SNF in a manner which stages it to final disposition. This particularly involves K Basin fuel.

Squires, K.G.

1995-03-06T23:59:59.000Z

Note: This page contains sample records for the topic "integrated test plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


21

Fermilab | Directorate | Office of Integrated Planning & Performance  

NLE Websites -- All DOE Office Websites (Extended Search)

Office of Integrated Planning & Performance Management (IPPM) Office of Integrated Planning & Performance Management (IPPM) Integrated Planning Diagram Integrated Planning Diagram [Download PPT] Mission: The Office of Integrated Planning and Performance Management (IPPM) within the Fermilab Directorate provides systems and management processes for institutional planning and performance assessment and evaluation. The office of IPPM leads multi-year, forward-looking planning and integration of institutional plans, programs, projects, operations and budgets. In addition it develops, implements and maintains integrated laboratory systems and management processes for strategic planning and goal setting, project and program oversight, enterprise risk management and performance planning and oversight. IPPM Facilitates:

22

Documentation of the Irvine Integrated Corridor Freeway Ramp Metering and Arterial Adaptive Control Field Operational Test  

E-Print Network (OSTI)

Integrated Ramp Metering/Adaptive Signal Control FieldIntegrated Ramp Metering/Adaptive Signal Control FieldTest Plan," Integrated Ramp Metering/Adaptive Signal Control

McNally, M. G.; Moore, II, James E.; MacCarley, C. Arthur

2001-01-01T23:59:59.000Z

23

Integration of Nevada Test Site (NTS) Work Control Programs and Incorporating Integrated Safety Management (ISM) into Activity Level Work Planning and Control  

SciTech Connect

This session will examine a method developed by Federal and Contractor personnel at the Nevada Site Office (NSO) to improve the planning and execution of work activities utilizing an Activity Level Work Control process in response to Defense Nuclear Facilities Safety Board (DNFSB) Recommendation 2004-1, Oversight of Complex, High-Hazard Nuclear Operations. The process was initially developed during Fiscal Year (FY) 2007, and implementation is commencing during the fourth quarter of FY 2008. This process will significantly enhance the flexibility and the appropriate rigor in the performance of work activities.

Mike Kinney and Kevin Breen

2008-08-30T23:59:59.000Z

24

Proactive Renewables Integration for Utility Distribution Planning...  

NLE Websites -- All DOE Office Websites (Extended Search)

Proactive Renewables Integration for Utility Distribution Planning and Operations Speaker(s): Emma Stewart Date: March 5, 2013 - 12:00pm Location: 90-1099 Seminar HostPoint of...

25

Integrated Safety Management (ISM) - Work Planning and Control  

NLE Websites -- All DOE Office Websites (Extended Search)

Work Planning and Control Integrated Safety Management (ISM) ism logo NNSA Activity Level Work Planning & Control Processes - January 2006...

26

Software Component Integration Testing  

Science Conference Proceedings (OSTI)

... a combination of off-the-shelf components, with new components integrated to satisfy ... oriented, that is, it consists of objects with state and behavior. ...

2011-12-02T23:59:59.000Z

27

TEST PLAN - SOLIDS ACCUMULATION SCOUTING STUDIES  

SciTech Connect

This plan documents the highlights of the Solids Accumulations Scouting Studies test; a project, from Washington River Protection Solutions (WRPS), that began on February 1, 2012. During the last 12 weeks considerable progress has been made to design and plan methods that will be used to estimate the concentration and distribution of heavy fissile solids in accumulated solids in the Hanford double-shell tank (DST) 241-AW-105 (AW-105), which is the primary goal of this task. This DST will be one of the several waste feed delivery staging tanks designated to feed the Pretreatment Facility (PTF) of the Waste Treatment and Immobilization Plant (WTP). Note that over the length of the waste feed delivery mission AW-105 is currently identified as having the most fill empty cycles of any DST feed tanks, which is the reason for modeling this particular tank. At SRNL an existing test facility, the Mixing Demonstration Tank, which will be modified for the present work, will use stainless steel particles in a simulant that represents Hanford waste to perform mock staging tanks transfers that will allow solids to accumulate in the tank heel. The concentration and location of the mock fissile particles will be measured in these scoping studies to produce information that will be used to better plan larger scaled tests. Included in these studies is a secondary goal of developing measurement methods to accomplish the primary goal. These methods will be evaluated for use in the larger scale experiments. Included in this plan are the several pretest activities that will validate the measurement techniques that are currently in various phases of construction. Aspects of each technique, e.g., particle separations, volume determinations, topographical mapping, and core sampling, have been tested in bench-top trials, as discussed herein, but the actual equipment to be employed during the full test will need evaluation after fabrication and integration into the test facility.

Duignan, M.; Steeper, T.; Steimke, J.; Fowley, M.

2012-05-10T23:59:59.000Z

28

Test Plan - Solids Accumulation Scouting Studies  

Science Conference Proceedings (OSTI)

This plan documents the highlights of the Solids Accumulations Scouting Studies test; a project, from Washington River Protection Solutions (WRPS), that began on February 1, 2012. During the last 12 weeks considerable progress has been made to design and plan methods that will be used to estimate the concentration and distribution of heavy fissile solids in accumulated solids in the Hanford double-shell tank (DST) 241-AW-105 (AW-105), which is the primary goal of this task. This DST will be one of the several waste feed delivery staging tanks designated to feed the Pretreatment Facility (PTF) of the Waste Treatment and Immobilization Plant (WTP). Note that over the length of the waste feed delivery mission AW-105 is currently identified as having the most fill empty cycles of any DST feed tanks, which is the reason for modeling this particular tank. At SRNL an existing test facility, the Mixing Demonstration Tank, which will be modified for the present work, will use stainless steel particles in a simulant that represents Hanford waste to perform mock staging tanks transfers that will allow solids to accumulate in the tank heel. The concentration and location of the mock fissile particles will be measured in these scoping studies to produce information that will be used to better plan larger scaled tests. Included in these studies is a secondary goal of developing measurement methods to accomplish the primary goal. These methods will be evaluated for use in the larger scale experiments. Included in this plan are the several pretest activities that will validate the measurement techniques that are currently in various phases of construction. Aspects of each technique, e.g., particle separations, volume determinations, topographical mapping, and core sampling, have been tested in bench-top trials, as discussed herein, but the actual equipment to be employed during the full test will need evaluation after fabrication and integration into the test facility.

Duignan, M. R.; Steeper, T. J.; Steimke, J. L.; Fowley, M. D.

2012-05-10T23:59:59.000Z

29

COLD TEST LOOP INTEGRATED TEST LOOP RESULTS  

Science Conference Proceedings (OSTI)

A testing facility (Cold Test Loop) was constructed and operated to demonstrate the efficacy of the Accelerated Waste Retrieval (AWR) Project's planned sluicing approach to the remediation of Silos 1 and 2 at the Fernald Environmental Management Project near Cincinnati, Ohio. The two silos contain almost 10,000 tons of radium-bearing low-level waste, which consists primarily of solids of raffinates from processing performed on ores from the Democratic Republic of Congo (commonly referred to as ''Belgium Congo ores'') for the recovery of uranium. These silos are 80 ft in diameter, 36 ft high to the center of the dome, and 26.75 ft to the top of the vertical side walls. The test facility contained two test systems, each designed for a specific purpose. The first system, the Integrated Test Loop (ITL), a near-full-scale plant including the actual equipment to be installed at the Fernald Site, was designed to demonstrate the sluicing operation and confirm the selection of a slurry pump, the optimal sluicing nozzle operation, and the preliminary design material balance. The second system, the Component Test Loop (CTL), was designed to evaluate many of the key individual components of the waste retrieval system over an extended run. The major results of the initial testing performed during July and August 2002 confirmed that the AWR approach to sluicing was feasible. The ITL testing confirmed the following: (1) The selected slurry pump (Hazleton 3-20 type SHW) performed well and is suitable for AWR application. However, the pump's motor should be upgraded to a 200-hp model and be driven by a 150-hp variable-frequency drive (VFD). A 200-hp VFD is not much more expensive and would allow the pump to operate at full speed. (2) The best nozzle performance was achieved by using 15/16-in. nozzles operated alternately. This configuration appeared to most effectively mine the surrogate. (3) The Solartron densitometer, which was tested as an alternative mass flow measurement device, did not operate effectively. Consequently, it is not suitable for application to the AWR process. (4) Initially, the spray ring (operated at approximately 2300 psi) and the nozzles provided by the pump vendor did not perform acceptably. The nozzles were replaced with a more robust model, and the performance was then acceptable. (5) The average solids concentration achieved in the slurry before Bentogrout addition was approximately 16% by weight. The solids concentration of the slurry after Bentogrout addition ranged from 26% to approximately 40%. The slurry pump and ITL system performed well at every concentration. No line plugging or other problems were noted. The results of the CTL runs and later ITL testing are summarized in an appendix to this report.

Abraham, TJ

2003-10-22T23:59:59.000Z

30

ITS strategic test plan : revision 1.0.  

SciTech Connect

This test plan describes the testing strategy for the ITS (Integrated-TIGER-Series) suite of codes. The processes and procedures for performing both verification and validation tests are described. ITS Version 5.0 was developed under the NNSA's ASC program and supports Sandia's stockpile stewardship mission.

Franke, Brian Claude; Lorence, Leonard Joseph, Jr.; Crawford, Martin James (K-Tech Corporation, Albuquerque, NM); Cordova, Lisa A.; Kensek, Ronald Patrick; Laub, Thomas William

2004-07-01T23:59:59.000Z

31

Buried waste integrated demonstration configuration management plan  

SciTech Connect

This document defines plans for the configuration management requirements for the Buried Waste Integrated Demonstration (BWID) Program. Since BWID is managed programmatically by the Waste Technology Development Department (WTDD), WTDD Program Directive (PD) 1.5 (Document Preparation, Review, Approval, Publication, Management and Change Control) is to be followed for all internal EG&G Idaho, Inc., BWID programmatic documentation. BWID documentation generated by organizations external to EG&G Idaho is not covered by this revision of the Configuration Management Plan (CMP), but will be addressed in subsequent revisions.

Cannon, P.G.

1992-02-01T23:59:59.000Z

32

Buried waste integrated demonstration configuration management plan  

SciTech Connect

This document defines plans for the configuration management requirements for the Buried Waste Integrated Demonstration (BWID) Program. Since BWID is managed programmatically by the Waste Technology Development Department (WTDD), WTDD Program Directive (PD) 1.5 (Document Preparation, Review, Approval, Publication, Management and Change Control) is to be followed for all internal EG G Idaho, Inc., BWID programmatic documentation. BWID documentation generated by organizations external to EG G Idaho is not covered by this revision of the Configuration Management Plan (CMP), but will be addressed in subsequent revisions.

Cannon, P.G.

1992-02-01T23:59:59.000Z

33

AGSD Task 3.5 Test Plan  

NLE Websites -- All DOE Office Websites (Extended Search)

CMC Bench Scale Material Test Plan TOPICAL REPORT Reporting Period Start Date: February 1, 2006 End Date: May 30, 2006 Principal Authors Mark Fitzsimmons Task Development Lead...

34

Buried waste integrated demonstration FY 94 deployment plan  

SciTech Connect

The Buried Waste Integrated Demonstration (BWID) is a program funded by the U.S. Department of Energy Office of Technology Development. BWID supports the applied research, development, demonstration, testing, and evaluation of a suite of advanced technologies that together form a comprehensive remediation system for the effective and efficient remediation of buried waste. The fiscal year (FY) 1994 effort will fund thirty-eight technologies in five areas of buried waste site remediation: site characterization, waste characterization, retrieval, treatment, and containment/stabilization. This document is the basic operational planning document for deployment of all BWID projects. Discussed in this document are the BWID preparations for INEL field demonstrations, INEL laboratory demonstrations, non-INEL demonstrations, and paper studies. Each technology performing tests will prepare a test plan to detail the specific procedures, objectives, and tasks of each test. Therefore, information specific to testing each technology is intentionally omitted from this document.

Hyde, R.A.; Walker, S.; Garcia, M.M.

1994-05-01T23:59:59.000Z

35

Strategy to develop and test a multi-function scarifier end effector with an integral conveyance system for waste tank remediation. Strategy plan  

SciTech Connect

This strategy plan describes a coupled analytical/experimental approach to develop a multi-functional scarifier end effector coupled with a pneumatic conveyance system to retrieve wastes from underground storage tanks. The scarifier uses ultra-high-pressure water jets to rubblize and entrain waste forms such as salt cake, sludge, and viscous liquid that can be transported pneumatically. The three waste types (hard, brittle, salt cake, viscous liquid, and deformable sludge) present increasingly complex challenges for scarification and pneumatic conveyance. Salt cake is anticipated to be the easiest to retrieve because (1) a theoretical model of hydraulic rock fracture can be applied to estimate jet performance to fracture salt cake, and (2) gas-solids transport correlations can be used to predict pneumatic transport. Deformable sludge is anticipated to be the most difficult to retrieve: no theories, correlations, or data exist to predict this performance. However order-of-magnitude gas-solid correlations indicate particulate wastes of prototypic density can be transported to a height of 20 m within allowable pressure limits provided that the volume fraction of the gaseous phase is kept above 95%. Viscous liquid is anticipated to be of intermediate complexity to retrieve. Phenomena that are expected to affect system performance are ranked. Experiments and analyses necessary to evaluate the effects of these phenomena are proposed. Subsequent strategies for experiment test plans, system deployment, and operation and control will need to be developed.

Bamberger, J.A.; Bates, J.M.; Keska, J.K.; Elmore, M.R.; Lombardo, N.J.

1993-08-01T23:59:59.000Z

36

Integrating Pollution Prevention with NEPA Planning Activities  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

DATE: REPLY TO ATTN OF: SUBJECT: TO: October 15, 1992 EH-25 Integrating Pollution Prevention with NEPA Planning Activities NEPA Compliance Officers The purpose of this memorandum is to advise you of the direction that the Environmental Protection Agency (EPA) and Council on Environmental Quality (CEQ) appear to be taking regarding pollution prevention and NEPA, and to encourage you to use the NEPA process to incorporate pollution prevention principles into the DOE planning and decisionmaking process. The Pollution Prevention Act of 1990 affirms Congressional commitment to a new approach in improving environmental quality. The Act establishes as national policy the following hierarchy of actions for environmental protection: 1. prevent or reduce pollution at the source wherever

37

Integrated Resource Planning: A Dialogue with ELCON  

E-Print Network (OSTI)

The oil price shocks of the 1970s were a precursor to some fundamental changes in the way the supply and demand for energy is viewed. One response to the events of that period is the application of integrated resource planning (IRP). IRP is, principally, a regulatory prerogative designed to promote a balance between supply and demand resources in electricity markets. In this paper we provide a definition of that concept and discuss two of its main features: Demand-side Management programs and environmental externalities. We also examine a number of positions taken by ELCON with respect to IRP and provide our responses.

Treadway, N.; Torrent, G.

1992-04-01T23:59:59.000Z

38

Guide to Integrating Renewable Energy in Federal Construction: Planning,  

NLE Websites -- All DOE Office Websites (Extended Search)

Planning, Programming, and Budgeting to someone by E-mail Planning, Programming, and Budgeting to someone by E-mail Share Guide to Integrating Renewable Energy in Federal Construction: Planning, Programming, and Budgeting on Facebook Tweet about Guide to Integrating Renewable Energy in Federal Construction: Planning, Programming, and Budgeting on Twitter Bookmark Guide to Integrating Renewable Energy in Federal Construction: Planning, Programming, and Budgeting on Google Bookmark Guide to Integrating Renewable Energy in Federal Construction: Planning, Programming, and Budgeting on Delicious Rank Guide to Integrating Renewable Energy in Federal Construction: Planning, Programming, and Budgeting on Digg Find More places to share Guide to Integrating Renewable Energy in Federal Construction: Planning, Programming, and Budgeting on

39

CMC Bench Scale Material Test Plan  

SciTech Connect

The test plan detailed in this topical report supports Task 3.5 of the project titled ''Development of Technologies and Capabilities for Coal Energy Resources - Advanced Gasification Systems Development (AGSD)''. The purpose of these tests is to verify that materials planned for use in an advanced gasifier pilot plant will withstand the environments in a commercial gasifier. Pratt & Whitney Rocketdyne (PWR) has developed this test plan with technical assistance from ceramic scientists at the Dept. of Energy Oak Ridge National Laboratory and Albany Research Center who will perform the environmental exposure tests.

Mark Fitzsimmons; Gerard Pelletier; Dave Grimmett

2006-05-30T23:59:59.000Z

40

Integrating transportation conservation with regional conservation planning  

E-Print Network (OSTI)

Multiple Species Conservation Program (MSCP). 1998.Final Multiple Species Conservation Program: MSCP Plan. Sanand Resource Conservation Planning Conservation Banking I

DiGregoria, John; Luciani, Emilie; Wynn, Susan

2005-01-01T23:59:59.000Z

Note: This page contains sample records for the topic "integrated test plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


41

EMERGENCY RESPONSE PLAN DEVINE TEST SITE  

E-Print Network (OSTI)

HSE MANUAL EMERGENCY RESPONSE PLAN DEVINE TEST SITE EXPLORATION GEOPHYSICS LAB FIELD SITE MEDINA THE UNIVERSITY OF TEXAS AT AUSTIN 1 #12;TABLE OF CONTENTS MEMORANDUM PAGE 3 MEDICAL EMERGENCY RESPONSE PLANS PAGE LIST OF CONTACTS ­ SITE MANAGERS AND EMERGENCY RESPONSE PAGE 20 CERTIFICATE OF COMPLETION PAGE 21 2 #12

Texas at Austin, University of

42

Geothermal drill pipe corrosion test plan  

DOE Green Energy (OSTI)

Plans are presented for conducting a field test of drill pipe corrosion, comparing air and nitrogen as drilling fluids. This test will provide data for evaluating the potential of reducing geothermal well drilling costs by extending drill pipe life and reducing corrosion control costs. The 10-day test will take place during fall 1980 at the Baca Location in Sandoval County, New Mexico.

Caskey, B.C.; Copass, K.S.

1980-12-01T23:59:59.000Z

43

CPC thermal collector test plan  

DOE Green Energy (OSTI)

A comprehensive set of test procedures has evolved at Argonne National Laboratory for establishing the performance of compound parabolic and related concentrating thermal collectors with large angular fields of view. The procedures range from separate thermal and optical tests, to overall performance tests. A calorimetric ratio technique has been developed to determine the heat output of a collector without knowledge of the heat transfer fluid's mass flow rate and heat capacity. Sepcial attention is paid to the problem of defining and measuring the incident solar flux with respect to which the collector efficiency is to be calculated.

Reed, K A

1977-01-01T23:59:59.000Z

44

CANMET Gasifier Liner Coupon Material Test Plan  

SciTech Connect

The test plan detailed in this topical report supports Task 1 of the project titled ''Development of Technologies and Capabilities for Coal Energy Resources - Advanced Gasification Systems Development (AGSD)''. The purpose of these tests is to verify that materials planned for use in an advanced gasifier pilot plant will withstand the environments in a commercial gasifier. Pratt & Whitney Rocketdyne (PWR) has developed and designed the cooled liner test assembly article that will be tested at CANMET Energy Technology Centre (CETC-O) in Ottawa, Ontario, Canada (CETC-O). The Test Plan TP-00364 is duplicated in its entirety, with formatting changes to comply with the format required for this Topical Report. The table of contents has been modified to include the additional material required by this topical report. Test Request example and drawings of non-proprietary nature are also included as appendices.

Mark Fitzsimmons; Alan Darby; Fred Widman

2005-10-30T23:59:59.000Z

45

CANMET Gasifier Liner Coupon Material Test Plan  

SciTech Connect

The test plan detailed in this topical report supports Task 1 of the project titled ''Development of Technologies and Capabilities for Coal Energy Resources - Advanced Gasification Systems Development (AGSD)''. The purpose of these tests is to verify that materials planned for use in an advanced gasifier pilot plant will withstand the environments in a commercial gasifier. Pratt & Whitney Rocketdyne (PWR) has developed and designed the cooled liner test assembly article that will be tested at CANMET Energy Technology Centre (CETC-O) in Ottawa, Ontario, Canada (CETC-O). The Test Plan TP-00364 is duplicated in its entirety, with formatting changes to comply with the format required for this Topical Report. The table of contents has been modified to include the additional material required by this topical report. Test Request example and drawings of non-proprietary nature are also included as appendices.

Mark Fitzsimmons; Alan Darby; Fred Widman

2005-10-30T23:59:59.000Z

46

OUTLINE OF DETAILED TEST PLAN  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

0/ 177 0/ 177 Implementation Plan and Initial Development of Nuclear Concrete Materials Database for Light Water Reactor Sustainability Program September 30, 2010 Prepared by Weiju Ren and Dan Naus Oak Ridge National Laboratory Barry Oland XCEL Engineering DOCUMENT AVAILABILITY Reports produced after January 1, 1996, are generally available free via the U.S. Department of Energy (DOE) Information Bridge. Web site http://www.osti.gov/bridge Reports produced before January 1, 1996, may be purchased by members of the public from the following source. National Technical Information Service 5285 Port Royal Road Springfield, VA 22161 Telephone 703-605-6000 (1-800-553-6847) TDD 703-487-4639 Fax 703-605-6900 E-mail info@ntis.gov

47

ORCWM test and evaluaton master plan. Revision 00  

SciTech Connect

The Office of Civilian Radioactive Waste Management (OCRWM) Test and Evaluation Master Plan (TEMP) describes the program Test and Evaluation (T&E) policy, objectives, requirements, general methodology (test flow and description of each T&E phase), responsibilities, and scheduling of test phases for the Civilian Radioactive Waste Management System (CRWMS). This TEMP is a program-level management planning document for al CRWMS T&E activities and will be used in conjunction with Section 11 of the Quality Assurance Requirements and Description (QARD), as appropriate, as a guide for the projects in developing their T&E plans. In the OCRWM document hierarchy, that is described in the OCRWM Systems Engineering Management Plan (SEMP), the TEMP is subordinate to the program SEMP. To ensure CRWMS operates as an integrated system, the plans for verifying the performance and evaluating the operational suitability and effectiveness of the overall system are also described. Test and evaluation is an integral part of the systems engineering process. Key aspects of the systems engineering process, more fully described in the OCRWM SEMP, are discussed in this TEMP to illustrate how T&E supports the overall systems engineering process.

NONE

1995-08-01T23:59:59.000Z

48

Spent Nuclear Fuel project integrated safety management plan  

SciTech Connect

This document is being revised in its entirety and the document title is being revised to ``Spent Nuclear Fuel Project Integrated Safety Management Plan.

Daschke, K.D.

1996-09-17T23:59:59.000Z

49

SchlumbergerRES/Field-Test-Plan.PPT/18/06/00/1 Field Test Plan Michigan  

E-Print Network (OSTI)

1 La ©SchlumbergerRES/Field-Test-Plan.PPT/18/06/00/1 Field Test Plan Michigan QLand, QBorehole, R Camp, Well --- Oil/Gas PL Permit Zone - CONFIDENTIAL - #12;8 La ©SchlumbergerRES/Field-Test-Plan.PPT/18/VSP compiled by Andreas Laake, SLB Project Coordinator Status :October 26, 2000 #12;2 La ©SchlumbergerRES/Field

50

Field test plan: Buried waste technologies, Fiscal Year 1995  

SciTech Connect

The US Department of Energy, Office of Technology Development, supports the applied research, development, demonstration, testing, and evaluation of a suite of advanced technologies that, when integrated with commercially available baseline technologies, form a comprehensive remediation system for the effective and efficient remediation of buried waste. The Fiscal Year 1995 effort is to deploy and test multiple technologies from four functional areas of buried waste remediation: site characterization, waste characterization, retrieval, and treatment. This document is the basic operational planning document for the deployment and testing of the technologies that support the field testing in Fiscal Year 1995. Discussed in this document are the scope of the tests; purpose and objective of the tests; organization and responsibilities; contingency plans; sequence of activities; sampling and data collection; document control; analytical methods; data reduction, validation, and verification; quality assurance; equipment and instruments; facilities and utilities; health and safety; residuals management; and regulatory management.

Heard, R.E.; Hyde, R.A. [Lockheed Idaho Technologies Co., Idaho Falls, ID (United States); Engleman, V.S.; Evans, J.D.; Jackson, T.W. [Science Applications International Corp., San Diego, CA (United States)

1995-06-01T23:59:59.000Z

51

Test Methods Standing Technical Committee Strategic Plan - February...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Test Methods Standing Technical Committee Strategic Plan - February 2012 Test Methods Standing Technical Committee Strategic Plan - February 2012 This document outlines gaps,...

52

Measuring and Test Equipment Assessment Plan,NNSA/Nevada Site...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Measuring and Test Equipment Assessment Plan,NNSANevada Site Office Independent Oversight Division Measuring and Test Equipment Assessment Plan,NNSANevada Site Office Independent...

53

RELAP-7 and PRONGHORN Initial Integration Plan  

SciTech Connect

Modern nuclear reactor safety codes require the ability to solve detailed coupled neutronicthermal fluids problems. For larger cores, this implies fully coupled 3-D spatial dynamics with appropriate feedback models that can provide enough resolution to accurately compute core heat generation and removal during steady and unsteady conditions. The reactor analyis code PRONGHORN is being coupled to RELAP-7 as a first step to extend RELAP's current capabilities. This report details the mathematical models, the type of coupling, and the testing that will be used to produce an integrated system. RELAP-7 is a MOOSE-based application that solves the continuity, momentum, and energy equations in 1-D for a compressible fluid. The pipe and joint capabilities enable it to model parts of the PCU system. The PRONGHORN application, also developed on the MOOSE infrastructure, solves the coupled equations that define the neutron diffusion, fluid flow, and heat transfer in a 3-D core model. Initially, the two systems will be loosely coupled to simplify the transition towards a more complex infrastructure. The integration will be tested with the OECD/NEA MHTGR-350 Coupled Neutronics-Thermal Fluids benchmark model.

J. Ortensi; D. Andrs; A.A. Bingham; R.C. Martineau; J.W. Peterson

2012-05-01T23:59:59.000Z

54

DEEP VADOSE ZONE TREATABILITY TEST PLAN  

Science Conference Proceedings (OSTI)

{sm_bullet} Treatability test plan published in 2008 {sm_bullet} Outlines technology treatability activities for evaluating application of in situ technologies and surface barriers to deep vadose zone contamination (technetium and uranium) {sm_bullet} Key elements - Desiccation testing - Testing of gas-delivered reactants for in situ treatment of uranium - Evaluating surface barrier application to deep vadose zone - Evaluating in situ grouting and soil flushing

GB CHRONISTER; MJ TRUEX

2009-07-02T23:59:59.000Z

55

Process Test Plan Shutdown P16 Exhauster  

Science Conference Proceedings (OSTI)

This Process Test Plan was written to gather temperature data to determine the amount of heat load remaining in tank 241-C-106. This process test plan is being conducted to gather the temperature data necessary to determine how much of the initial heat load is still left in 241-C-106. The heat load will be determined by shutting off the C-106 exhaust system, monitoring the change in tank temperature, and plugging the resulting data into the thermal model for this tank.

PARKMAN, D.B.

2000-01-25T23:59:59.000Z

56

Integrating transportation conservation with regional conservation planning  

E-Print Network (OSTI)

and Wildlife Biologist/Transportation Liaison, U.S. Fish andChapter Integrating Transportation and Resource Conservationon the integration of transportation conservation with the

DiGregoria, John; Luciani, Emilie; Wynn, Susan

2005-01-01T23:59:59.000Z

57

AGR-1 Irradiation Experiment Test Plan  

DOE Green Energy (OSTI)

This document presents the current state of planning for the AGR-1 irradiation experiment, the first of eight planned irradiations for the Advanced Gas Reactor (AGR) Fuel Development and Qualification Program. The objectives of the AGR-1 experiment are: 1. To gain experience with multi-capsule test train design, fabrication, and operation with the intent to reduce the probability of capsule or test train failure in subsequent irradiation tests. 2. To irradiate fuel produced in conjunction with the AGR fuel process development effort. 3. To provide data that will support the development of an understanding of the relationship between fuel fabrication processes, fuel product properties, and irradiation performance. In order to achieve the test objectives, the AGR-1 experiment will be irradiated in the B-10 position of the Advanced Test Reactor (ATR) at the Idaho National Laboratory (INL). The test will contain six independently controlled and monitored capsules. Each capsule will contain a single type, or variant, of the AGR coated fuel. The irradiation is planned for about 700 effective full power days (approximately 2.4 calendar years) with a time-averaged, volume-average temperature of approximately 1050 C. Average fuel burnup, for the entire test, will be greater than 17.7 % FIMA, and the fuel will experience fast neutron fluences between 2.4 and 4.5 x 1025 n/m2 (E>0.18 MeV).

John T. Maki

2009-10-01T23:59:59.000Z

58

Integrating Pollution Prevention with NEPA Planning Activities | Department  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Integrating Pollution Prevention with NEPA Planning Activities Integrating Pollution Prevention with NEPA Planning Activities Integrating Pollution Prevention with NEPA Planning Activities The purpose of this memorandum is to advise you of the direction that the Environmental Protection Agency (EPA) and Council on Environmental Quality (CEQ) appear to be taking regarding pollution prevention and NEPA, and to encourage the use of the NEPA process to incorporate pollution prevention principles into the DOE planning and decisionmaking process. Integrating Pollution Prevention with NEPA Planning Activities More Documents & Publications Memorandum to Heads of Federal Departments and Agencies Regarding Pollution Prevention and the National Environmental Policy Act Guidance Regarding NEPA Regulations DOE NEPA Guidance and Requirements - Search Index - Table of Contents

59

Integration of Biodiversity into National Forestry Planning:...  

Open Energy Info (EERE)

of Biodiversity into National Forestry Planning: An Annotated Bibliography of Web-Based Resources, Methods, Experiences, and Case Studies Jump to: navigation, search...

60

Fermilab | Directorate | Office of Integrated Planning (OIP)...  

NLE Websites -- All DOE Office Websites (Extended Search)

Roles Classifications and Definitions of Managers and Project Managers Realtionship - Job Titles and OHAP Functional Roles Ten Year Planning ExerciseNeeds Analysis FY2011...

Note: This page contains sample records for the topic "integrated test plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


61

Test Plan for Composite Hydrogen Getter Materials  

SciTech Connect

The intent of this test plan is to provide details of the Savannah River Technology Center (SRTC) effort to evaluate composite getter materials for eventual use in expanding the wattage limits for transportation of contact-handled transuranic waste (CH-TRU). This effort is funded by the Mixed Waste Focus Area (MWFA) under Technical Task Plan (TTP) SR-1-9-MW-45 and is the result of a competitive process initiated by a MWFA request for proposals. In response to this request, SRTC presented data on several composite getter materials that demonstrated good potential for application in transportation of transuranic wastes. The tests outlined in the SRTC proposal for composite getter materials should demonstrate compliance with functional requirements provided by the MWFA in a Statement of Work (SOW) which accompanied the request for proposals. Completion of Phase 1 testing, as defined in the TTP, should provide sufficient data to determine if composite getters should progress to Phase s 2 and 3. These test results will provide support for future safety reviews as part of the Transuranic Package Transporter-II (TRUPACT-II) certification process to utilize getter technology. This test plan provides details of the test descriptions, test objectives, required measurements, data quality objectives, data analysis, and schedule information relevant to Phase 1 of the TTP. The results of these tests are expected to help identify any potential weaknesses in the use of composite getter for transportation of CH-TRU wastes. Where a potential weakness is identified, this will be addressed as part of Phase 2 of the proposed effort. It is also important to recognize that these tests are focused on the individual composite getter materials and not the engineered system that would eventually be used in a TRUPACT-II. However, these test results will be very helpful in establishing the requirements for the design of a TRUPACT-II getter system that is included as part of the propo sed Phase 3 effort.

Livingston, R.R.

2000-11-09T23:59:59.000Z

62

Operational test report for LERF Basin 242AL-44 integrity test  

SciTech Connect

This operational test report documents the results of LERF operational testing per operational test procedure (OTP) TFPE-WP-0231, ``LERF Basin Integrity Testing.`` The primary purpose of the OTP was to resolve test exceptions generated as a result of TFPE-WP-0184. The TOP was prepared and performed in accordance with WHC-SD-534-OTP-002, ``Operational Test Plan for the 242-A Evaporator Upgrades and the Liquid Effluent Retention Facility.`` WHC-S-086, ``Specification for Operational Testing of the Liquid Effluent Retention Facility, Basin Integrity Testing,`` identified the test requirements and acceptance criteria. The completed, signed-off test procedure is contained in Appendix A. The test log is contained in Appendix B. Section 2.1 describes all the test exceptions written during performance of the Operational Test Procedure. The test revisions generated during the testing are discussed in Section 2.2. The dispositioned test exception forms are contained in Appendix C.

Galioto, T.M.

1994-11-08T23:59:59.000Z

63

Web based integrated models for participatory planning  

Science Conference Proceedings (OSTI)

The present paper focuses on the development of an integrated assessment model that embeds the web dimension and aims at increasing awareness in society, especially on environmental issues. The model incorporates features that make it capable of promoting ... Keywords: greenhouse gas emissions, increasing awareness, integrated assessment models, web based participatory integrated assessment models

Grammatikogiannis Elias; Maria Giaoutzi

2011-06-01T23:59:59.000Z

64

The Challenge of Testing RFID Integrated Circuits  

Science Conference Proceedings (OSTI)

RFID integrated circuits often involve many of themost leading edge production technologies availabletoday. The complexities involved with integrating thesecomplexities into the backend and test environment areexceptionally challenging. To date, this ...

David Murfett

2004-01-01T23:59:59.000Z

65

Integrating Infrastructure Planning: The Role of Schools  

E-Print Network (OSTI)

of these strategies for schools and communities. Californiainvestments in new public school facilities. Now is the timePlanning: The Role of Schools B Y D E B O R A H M C K O Y, J

McKoy, Deborah; Vincent, Jeffrey M.; Makarewicz, Carrie

2008-01-01T23:59:59.000Z

66

Tonopah Test Range closure sites revegetation plan  

SciTech Connect

This document is a revegetation plan for long-term stabilization (revegetation) of land disturbed by activities associated with the closure of a Bomblet Pit and the Five Points Landfill. Both sites are on the Tonopah Test Range (TTR) located in south-central Nevada. This document contains general reclamation practices and procedures that will be followed during the revegetation of these sites. The revegetation procedures proposed have been developed over several years of research and include the results of reclamation trials at Area 11 and Area 19 on the Nevada Test Site (NTS), and more recently at the Double Tracks (Nellis Air Force Range) reclamation demonstration plots. In addition, the results of reclamation efforts and concurrent research efforts at the Yucca Mountain Project have been considered in the preparation of this revegetation plan.

Anderson, D.C.; Hall, D.B.

1997-05-01T23:59:59.000Z

67

Integration of Biodiversity into National Forestry Planning: An Annotated  

Open Energy Info (EERE)

Integration of Biodiversity into National Forestry Planning: An Annotated Integration of Biodiversity into National Forestry Planning: An Annotated Bibliography of Web-Based Resources, Methods, Experiences, and Case Studies Jump to: navigation, search Tool Summary Name: Integration of Biodiversity into National Forestry Planning: An Annotated Bibliography of Web-Based Resources, Methods, Experiences, and Case Studies Agency/Company /Organization: Center for International Forestry Research Partner: United Nations Environment Programme, Global Environment Facility Sector: Land Focus Area: Forestry Resource Type: Lessons learned/best practices Website: www.unep.org/bpsp/forestry/forestry%20annotated%20bibliography/annotat References: Integration of Biodiversity into National Forestry Planning: An Annotated Bibliography of Web-Based Resources, Methods, Experiences, and Case Studies[1]

68

GEOCHEMICAL TESTING AND MODEL DEVELOPMENT - RESIDUAL TANK WASTE TEST PLAN  

SciTech Connect

This Test Plan describes the testing and chemical analyses release rate studies on tank residual samples collected following the retrieval of waste from the tank. This work will provide the data required to develop a contaminant release model for the tank residuals from both sludge and salt cake single-shell tanks. The data are intended for use in the long-term performance assessment and conceptual model development.

CANTRELL KJ; CONNELLY MP

2010-03-09T23:59:59.000Z

69

Integrated Requirements Management System Operations and Maintenance Plan  

Science Conference Proceedings (OSTI)

This document provides a plan for the operations and maintenance of the Integrated Requirements Management Systems (IRMS) database. This document describes the roles and responsibilities for the users of the IRMS. Planning is provided for the configuration management of the DOORS software, hardware and data set. Training consideration for the various categories of users is provided.

ACREE, C.D.

2001-03-26T23:59:59.000Z

70

Integrative path planning and motion control for handling large components  

Science Conference Proceedings (OSTI)

For handling large components a large workspace and high precision are required. In order to simplify the path planning for automated handling systems, this task can be divided into global, regional and local motions. Accordingly, different types of ... Keywords: integrative production, motion control, path planning, robotic assembly application

Rainer Mller; Martin Esser; Markus Janssen

2011-12-01T23:59:59.000Z

71

Phased Startup Initiative Phases 3 and 4 Test Plan and Test Specification (OCRWM)  

SciTech Connect

Construction for the Spent Nuclear Fuel (SNF) Project facilities is continuing per the Level III Baseline Schedule, and installation of the Fuel Retrieval System (FRS) and Integrated Water Treatment System (IWTS) in K West Basin is now complete. In order to accelerate the project, a phased start up strategy to initiate testing of the FRS and IWTS early in the overall project schedule was proposed (Williams 1999). Wilkinson (1999) expands the definition of the original proposal into four functional testing phases of the Phased Startup Initiative (PSI). Phases 1 and 2 are based on performing functional tests using dummy fuel. These tests are described in separate planning documents. This test plan provides overall guidance for Phase 3 and 4 tests, which are performed using actual irradiated N fuel assemblies. The overall objective of the Phase 3 and 4 testing is to verify how the FRS and IWTS respond while processing actual fuel. Conducting these tests early in the project schedule will allow identification and resolution of equipment and process problems before they become activities on the start-up critical path. The specific objectives of this test plan are to: (1) Define the test scope for the FRS and IWTS; (2) Provide detailed test requirements that can be used to write the specific test procedures; (3) Define data required and measurements to be taken. Where existing methods to obtain these do not exist, enough detail will be provided to define required additional equipment; and (4) Define specific test objectives and acceptance criteria.

PITNER, A.L.

2000-02-28T23:59:59.000Z

72

Secondary Waste Cast Stone Waste Form Qualification Testing Plan  

SciTech Connect

The Hanford Tank Waste Treatment and Immobilization Plant (WTP) is being constructed to treat the 56 million gallons of radioactive waste stored in 177 underground tanks at the Hanford Site. The WTP includes a pretreatment facility to separate the wastes into high-level waste (HLW) and low-activity waste (LAW) fractions for vitrification and disposal. The LAW will be converted to glass for final disposal at the Integrated Disposal Facility (IDF). Cast Stone a cementitious waste form, has been selected for solidification of this secondary waste stream after treatment in the ETF. The secondary-waste Cast Stone waste form must be acceptable for disposal in the IDF. This secondary waste Cast Stone waste form qualification testing plan outlines the testing of the waste form and immobilization process to demonstrate that the Cast Stone waste form can comply with the disposal requirements. Specifications for the secondary-waste Cast Stone waste form have not been established. For this testing plan, Cast Stone specifications are derived from specifications for the immobilized LAW glass in the WTP contract, the waste acceptance criteria for the IDF, and the waste acceptance criteria in the IDF Permit issued by the State of Washington. This testing plan outlines the testing needed to demonstrate that the waste form can comply with these waste form specifications and acceptance criteria. The testing program must also demonstrate that the immobilization process can be controlled to consistently provide an acceptable waste form product. This testing plan also outlines the testing needed to provide the technical basis for understanding the long-term performance of the waste form in the disposal environment. These waste form performance data are needed to support performance assessment analyses of the long-term environmental impact of the secondary-waste Cast Stone waste form in the IDF

Westsik, Joseph H.; Serne, R. Jeffrey

2012-09-26T23:59:59.000Z

73

Project development plan for East Mesa Geothermal Test Center  

DOE Green Energy (OSTI)

Plans for a test facility for geothermal energy systems and components designed for moderate temperature/low salinity geothermal fluids available at the East Mesa site in the Imperial Valley of California are discussed. Details of the following phases of development are given: technical plan; management plan; procurement and contracting plan; technology transfer and utilization plan; and resource requirements. (JGB)

Not Available

1975-03-01T23:59:59.000Z

74

Integrated Program of Experimental Diagnostics at the NNSS: An Integrated, Prioritized Work Plan for Diagnostic Development and Maintenance and Supporting Capability  

SciTech Connect

This Integrated Program of Experimental Diagnostics at the NNSS is an integrated prioritized work plan for the Nevada National Security Site (NNSS), formerly the Nevada Test Site (NTS), program that is independent of individual National Security Enterprise Laboratories (Labs) requests or specific Subprograms being supported. This prioritized work plan is influenced by national priorities presented in the Predictive Capability Framework (PCF) and other strategy documents (Primary and Secondary Assessment Technologies Plans and the Plutonium Experiments Plan). This document satisfies completion criteria for FY 2010 MRT milestone #3496: Document an integrated, prioritized work plan for diagnostic development, maintenance, and supporting capability. This document is an update of the 3?year NNSS plan written a year ago, September 21, 2009, to define and understand Lab requests for diagnostic implementation. This plan is consistent with Lab interpretations of the PCF, Primary Assessment Technologies, and Plutonium Experiment plans.

NSTec Mission and Projects Division

2010-09-30T23:59:59.000Z

75

Test Plan: WIPP bin-scale CH TRU waste tests  

SciTech Connect

This WIPP Bin-Scale CH TRU Waste Test program described herein will provide relevant composition and kinetic rate data on gas generation and consumption resulting from TRU waste degradation, as impacted by synergistic interactions due to multiple degradation modes, waste form preparation, long-term repository environmental effects, engineered barrier materials, and, possibly, engineered modifications to be developed. Similar data on waste-brine leachate compositions and potentially hazardous volatile organic compounds released by the wastes will also be provided. The quantitative data output from these tests and associated technical expertise are required by the WIPP Performance Assessment (PA) program studies, and for the scientific benefit of the overall WIPP project. This Test Plan describes the necessary scientific and technical aspects, justifications, and rational for successfully initiating and conducting the WIPP Bin-Scale CH TRU Waste Test program. This Test Plan is the controlling scientific design definition and overall requirements document for this WIPP in situ test, as defined by Sandia National Laboratories (SNL), scientific advisor to the US Department of Energy, WIPP Project Office (DOE/WPO). 55 refs., 16 figs., 19 tabs.

Molecke, M.A.

1990-08-01T23:59:59.000Z

76

AGA 12, Part 2 Performance Test Plan | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

AGA 12, Part 2 Performance Test Plan AGA 12, Part 2 Performance Test Plan Under the guidance and sponsorship of DOE's Office of Electricity Delivery and Energy Reliability, Pacific...

77

100 area excavation treatability test plan  

SciTech Connect

This test plan documents the requirements for a treatability study on field radionuclide analysis and dust control techniques. These systems will be used during remedial actions involving excavation. The data from this treatability study will be used to support the feasibility study (FS) process. Development and screening of remedial alternatives for the 100 Area, using existing data, have been completed and are documented in the 100 Area Feasibility Study, Phases 1 and 2 (DOE-RL 1992a). Based on the results of the FS, the Treatability Study Program Plan (DOE-RL 1992b) identifies and prioritizes treatability studies for the 100 Area. The data from the treatability study program support future focused FS, interim remedial measures (IRM) selection, operable unit final remedy selection, remedial design, and remedial actions. Excavation is one of the high-priority, near-term, treatability study needs identified in the program plan (DOE-RL 1992b). Excavation of contaminated soils and buried solid wastes is included in several of the alternatives identified in the 100 Area FS. Although a common activity, excavation has only been used occasionally at the Hanford Site for waste removal applications.

Not Available

1993-05-01T23:59:59.000Z

78

Generation and transmission expansion planning for renewable energy integration  

SciTech Connect

In recent years the expansion planning problem has become increasingly complex. As expansion planning (sometimes called composite or integrated resource planning) is a non-linear and non-convex optimization problem, researchers have traditionally focused on approximate models of power flows to solve the problem. The problem has also been split into generation expansion planning (GEP) and transmission network expansion planning (TNEP) to improve computational tractability. Until recently these approximations have produced results that are straight-forward to combine and adapt to the more complex and complete problem. However, the power grid is evolving towards a state where the adaptations are no longer easy (e.g. large amounts of limited control, renewable generation, comparable generation and transmission construction costs) and necessitates new approaches. Recent work on deterministic Discrepancy Bounded Local Search (DBLS) has shown it to be quite effective in addressing the TNEP. In this paper, we propose a generalization of DBLS to handle simultaneous generation and transmission planning.

Bent, Russell W [Los Alamos National Laboratory; Berscheid, Alan [Los Alamos National Laboratory; Toole, G. Loren [Los Alamos National Laboratory

2010-11-30T23:59:59.000Z

79

PURADYN Oil Bypass Filtration System Evaluation Test Plan  

NLE Websites -- All DOE Office Websites (Extended Search)

& Infrastructure Department PURADYN OIL BYPASS FILTRATION SYSTEM EVALUATION TEST PLAN October 2002 Reviewed: INEEL Fleet Maintenance Supervisor (Thomas) Date Reviewed:...

80

NETEX Test Master Plan Draft 8/15/02  

E-Print Network (OSTI)

NETEX Test Master Plan Draft 8/15/02 1 The Defense Advanced Research Projects Agency (DARPA) Networking in Extreme Environments (NETEX) Program TEST MASTER PLAN FOR THE NETEX PROGRAM 1.0 INTRODUCTION This document provides a plan for testing a number of selected military systems to determine the susceptibility

Buehrer, R. Michael

Note: This page contains sample records for the topic "integrated test plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


81

Hanford Permanent Isolation Barrier Program: Asphalt technology test plan  

SciTech Connect

The Hanford Permanent Isolation Barriers use engineered layers of natural materials to create an integrated structure with backup protective features. The objective of current designs is to develop a maintenance-free permanent barrier that isolates wastes for a minimum of 1000 years by limiting water drainage to near-zero amounts. Asphalt is being used as an impermeable water diversion layer to provide a redundant layer within the overall barrier design. Data on asphalt barrier properties in a buried environment are not available for the required 100-year time frame. The purpose of this test plan is to outline the activities planned to obtain data with which to estimate performance of the asphalt layers.

Freeman, H.D.; Romine, R.A.

1994-05-01T23:59:59.000Z

82

AFRD EH&S: Integrated Safety Management Plan  

NLE Websites -- All DOE Office Websites (Extended Search)

Integrated Safety Management Integrated Safety Management The AFRD Integrated Safety Management or ISM Plan is the master document that guides AFRD policies and practices in environment, safety, and health. The guiding principles and core functions (below left) are the key to understanding ISM. Below, right are the topically arranged sections of the AFRD ISM Plan. Depending on your workplace and duties, more than one topic may apply to you. The ISM Plan is updated as of October 2013. Please contact us with any feedback. Guiding Principles Line-management responsibility for safety Clear roles and responsibilities Competence commensurate with responsibilities Balanced Priorities Identification of ES&H standards and requirements Hazard controls (including environmental controls) tailored to work being performed

83

Integrated Resource Planning Act (Georgia) | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

You are here You are here Home » Integrated Resource Planning Act (Georgia) Integrated Resource Planning Act (Georgia) < Back Eligibility Commercial Construction Developer General Public/Consumer Industrial Installer/Contractor Investor-Owned Utility Municipal/Public Utility Retail Supplier Rural Electric Cooperative Utility Savings Category Alternative Fuel Vehicles Hydrogen & Fuel Cells Buying & Making Electricity Water Home Weatherization Solar Wind Program Info State Georgia Program Type Industry Recruitment/Support Siting and Permitting Georgia's Integrated Resource Planning Act, which was passed in 1991 and is now Georgia Code § 46-3A, requires that any proposed new electric plant receive certification by the Georgia Public Service Commission (PSC) before construction begins. A utility is entitled to recover pre-approved costs

84

Light Water Reactor Sustainability Program: Integrated Program Plan |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Integrated Program Plan Integrated Program Plan Light Water Reactor Sustainability Program: Integrated Program Plan Nuclear power has safely, reliably, and economically contributed almost 20% of electrical generation in the United States over the past two decades. It remains the single largest contributor (more than 70%) of non-greenhouse-gas- emitting electric power generation in the United States. Domestic demand for electrical energy is expected to grow by more than 30% from 2009 to 2035. At the same time, most of the currently operating nuclear power plants will begin reaching the end of their initial 20-year extension to their original 40-year operating license, for a total of 60 years of operation. Figure E-1 shows projected nuclear energy contribution to the domestic generating capacity. If current operating nuclear power

85

Integrated safeguards and security management plan  

Science Conference Proceedings (OSTI)

Berkeley Lab is committed to scientific excellence and stewardship of its assets. While security principles apply to all work performed at the Laboratory, their implementation is flexible. Berkeley Lab adheres to the following principles: Line management owns security; Security roles and responsibilities are clearly defined and communicated; Security functions are integrated; An open environment supports the Laboratory's Mission; The security program must support the scientific and operational missions of the Laboratory and must be value added; and Security controls are tailored to individual and facility requirements.

Bowen, Sue, editor

2001-04-16T23:59:59.000Z

86

Buried Waste Integrated Demonstration Strategy Plan  

SciTech Connect

The Buried Waste Integrated Demonstration (BWID) supports the applied research, development, demonstration, and evaluation of a suite of advanced technologies that form a comprehensive remediation system for the effective and efficient remediation of buried waste. These efforts are identified and coordinated in support of the US Department of Energy (DOE), Environmental Restoration and Waste Management (ERWM) needs and objectives. The present focus of BWID is to support retrieval and ex situ treatment configuration options. Future activities will explore and support containment and stabilization efforts in addition to the retrieval/ex situ treatment options. Long and short term strategies of the BWID are provided. Processes for identifying technological needs, screening candidate technologies for BWID applicability, researching technical issues, field demonstrating technologies, evaluating demonstration results to determine each technology`s threshold of capability, and commercializing successfully demonstrated technologies for implementation for environmental restoration also are presented in this report.

Kostelnik, K.M.

1993-02-01T23:59:59.000Z

87

Buried Waste Integrated Demonstration Strategy Plan  

SciTech Connect

The Buried Waste Integrated Demonstration (BWID) supports the applied research, development, demonstration, and evaluation of a suite of advanced technologies that form a comprehensive remediation system for the effective and efficient remediation of buried waste. These efforts are identified and coordinated in support of the US Department of Energy (DOE), Environmental Restoration and Waste Management (ERWM) needs and objectives. The present focus of BWID is to support retrieval and ex situ treatment configuration options. Future activities will explore and support containment and stabilization efforts in addition to the retrieval/ex situ treatment options. Long and short term strategies of the BWID are provided. Processes for identifying technological needs, screening candidate technologies for BWID applicability, researching technical issues, field demonstrating technologies, evaluating demonstration results to determine each technology's threshold of capability, and commercializing successfully demonstrated technologies for implementation for environmental restoration also are presented in this report.

Kostelnik, K.M.

1993-02-01T23:59:59.000Z

88

Nevada Test Site Resource Management Plan  

SciTech Connect

The Nevada Test Site (NTS) Resource Management Plan (RMP) describes the NTS Stewardship Mission and how its accomplishment will preserve the resources of the ecoregion while accomplishing the objectives of the mission. The NTS Stewardship Mission is to manage the land and facilities at the NTS as a unique and valuable national resource. The RMP has defined goals for twelve resource areas based on the principles of ecosystem management. These goals were established using an interdisciplinary team of DOE/NV resource specialists with input from surrounding land managers, private parties, and representatives of Native American governments. The overall goal of the RMP is to facilitate improved NTS land use management decisions within the Great Basin and Mojave Desert ecoregions.

NONE

1998-12-01T23:59:59.000Z

89

Field testing plan for unsaturated zone monitoring and field studies  

Science Conference Proceedings (OSTI)

The University of Arizona, in cooperation with the Bureau of Economic Geology at The University of Texas at Austin, and Stephens and Associates in Albuquerque, New Mexico has developed a field testing plan for evaluating subsurface monitoring systems. The U.S. Nuclear Regulatory Commission has requested development of these testing plans for low-level radioactive waste disposal sites (LLW) and for monitoring at decommissioned facilities designated under the {open_quotes}Site Decommissioning Management Plan{close_quotes} (SDMP). The tests are conducted on a 50 m by 50 m plot on the University of Arizona`s Maricopa Agricultural Center. Within the 50 m by 50 m plot one finds: (1) an instrumented buried trench, (2) monitoring islands similar to those proposed for the Ward Valley, California LLW Facility, (3) deep borehole monitoring sites, (4) gaseous transport monitoring, and (5) locations for testing non-invasive geophysical measurement techniques. The various subplot areas are instrumented with commercially available instruments such as neutron probes, time domain reflectometry probes, tensiometers, psychrometers, heat dissipation sensors, thermocouples, solution samplers, and cross-hole geophysics electrodes. Measurement depths vary from ground surface to 15 m. The data from the controlled flow and transport experiments, conducted over the plot, will be used to develop an integrated approach to long-term monitoring of the vadose zone at waste disposal sites. The data will also be used to test field-scale flow and transport models. This report describes in detail the design of the experiment and the methodology proposed for evaluating the data.

Young, M.H.; Wierenga, P.J.; Warrick, A.W. [and others

1996-10-01T23:59:59.000Z

90

Prototype steam generator test at SCTI/ETEC. Acoustic program test plan. [LMFBR  

SciTech Connect

This document is an integrated test plan covering programs at General Electric (ARSD), Rockwell International (RI) and Argonne National Laboratory (CT). It provides an overview of the acoustic leak detection test program which will be completed in conjunction with the prototype LMFBR steam generator at the Energy Technology Engineering Laboratory. The steam generator is installed in the Sodium Components Test Installation (SCTI). Two acoustic detection systems will be used during the test program, a low frequency system developed by GE-ARSD (GAAD system) and a high frequency system developed by RI-AI (HALD system). These systems will be used to acquire data on background noise during the thermal-hydraulic test program. Injection devices were installed during fabrication of the prototype steam generator to provide localized noise sources in the active region of the tube bundle. These injectors will be operated during the steam generator test program, and it will be shown that they are detected by the acoustic systems.

Greene, D.A.; Thiele, A.; Claytor, T.N.

1981-10-01T23:59:59.000Z

91

Light Water Reactor Sustainability Program - Integrated Program Plan |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Light Water Reactor Sustainability Program - Integrated Program Light Water Reactor Sustainability Program - Integrated Program Plan Light Water Reactor Sustainability Program - Integrated Program Plan The Light Water Reactor Sustainability (LWRS) Program is a research and development (R&D) program sponsored by the U. S. Department of Energy (DOE), performed in close collaboration and cooperation with related industry R&D programs. The LWRS Program provides technical foundations for licensing and managing the long-term, safe, and economical operation of current nuclear power plants, utilizing the unique capabilities of the national laboratory system. Sustainability is defined as the ability to maintain safe and economic operation of the existing fleet of nuclear power plants for a longer than-initially-licensed lifetime. It has two facets

92

NREL: Transmission Grid Integration - Transmission Planning and Analysis  

NLE Websites -- All DOE Office Websites (Extended Search)

Transmission Planning and Analysis Transmission Planning and Analysis Thumbnail of map the United States that shows wind resources and transmission lines. Enlarge image This map shows the location of wind resources and transmission lines in the United States. See a larger image or state maps. NREL researchers are engaged in transmission planning and analysis to strengthen the electric power system through the integration of solar and wind power. As demand for electricity increases, electric power system operators must plan for and construct new generation and transmission lines. However, variable generation such as solar and wind power plants are often located far from the loads they serve. They depend on transmission lines to transport the electricity they produce to load centers. NREL is working with industry and utilities to address issues related to

93

Hanford spent nuclear fuel cold vacuum drying test specification and test plan  

SciTech Connect

This document provides the test plan and test specification for SNF cold vacuum drying proof of concept, CVD process equipment validation, and proof of performance testing.

McCracken, K.J., Westinghouse Hanford

1996-07-10T23:59:59.000Z

94

Vitrification Facility integrated system performance testing report  

Science Conference Proceedings (OSTI)

This report provides a summary of component and system performance testing associated with the Vitrification Facility (VF) following construction turnover. The VF at the West Valley Demonstration Project (WVDP) was designed to convert stored radioactive waste into a stable glass form for eventual disposal in a federal repository. Following an initial Functional and Checkout Testing of Systems (FACTS) Program and subsequent conversion of test stand equipment into the final VF, a testing program was executed to demonstrate successful performance of the components, subsystems, and systems that make up the vitrification process. Systems were started up and brought on line as construction was completed, until integrated system operation could be demonstrated to produce borosilicate glass using nonradioactive waste simulant. Integrated system testing and operation culminated with a successful Operational Readiness Review (ORR) and Department of Energy (DOE) approval to initiate vitrification of high-level waste (HLW) on June 19, 1996. Performance and integrated operational test runs conducted during the test program provided a means for critical examination, observation, and evaluation of the vitrification system. Test data taken for each Test Instruction Procedure (TIP) was used to evaluate component performance against system design and acceptance criteria, while test observations were used to correct, modify, or improve system operation. This process was critical in establishing operating conditions for the entire vitrification process.

Elliott, D.

1997-05-01T23:59:59.000Z

95

Modeling renewable energy resources in integrated resource planning  

SciTech Connect

Including renewable energy resources in integrated resource planning (IRP) requires that utility planning models properly consider the relevant attributes of the different renewable resources in addition to conventional supply-side and demand-side options. Otherwise, a utility`s resource plan is unlikely to have an appropriate balance of the various resource options. The current trend toward regulatory set-asides for renewable resources is motivated in part by the perception that the capabilities of current utility planning models are inadequate with regard to renewable resources. Adequate modeling capabilities and utility planning practices are a necessary prerequisite to the long-term penetration of renewable resources into the electric utility industry`s resource mix. This report presents a review of utility planning models conducted for the National Renewable Energy Laboratory (NREL). The review examines the capabilities of utility planning models to address key issues in the choice between renewable resources and other options. The purpose of this review is to provide a basis for identifying high priority areas for advancing the state of the art.

Logan, D.; Neil, C.; Taylor, A. [RCG/Hagler, Bailly, Inc., Boulder, CO (United States)

1994-06-01T23:59:59.000Z

96

Operational test report integrated system test (ventilation upgrade)  

Science Conference Proceedings (OSTI)

Operational Final Test Report for Integrated Systems, Project W-030 (Phase 2 test, RECIRC and HIGH-HEAT Modes). Project W-030 provides a ventilation upgrade for the four Aging Waste Facility tanks, including upgraded vapor space cooling and filtered venting of tanks AY101, Ay102, AZ101, AZ102.

HARTY, W.M.

1999-10-05T23:59:59.000Z

97

Integrated Modeling, Mapping, and Simulation (IMMS) framework for planning exercises.  

SciTech Connect

The Integrated Modeling, Mapping, and Simulation (IMMS) program is designing and prototyping a simulation and collaboration environment for linking together existing and future modeling and simulation tools to enable analysts, emergency planners, and incident managers to more effectively, economically, and rapidly prepare, analyze, train, and respond to real or potential incidents. When complete, the IMMS program will demonstrate an integrated modeling and simulation capability that supports emergency managers and responders with (1) conducting 'what-if' analyses and exercises to address preparedness, analysis, training, operations, and lessons learned, and (2) effectively, economically, and rapidly verifying response tactics, plans and procedures.

Friedman-Hill, Ernest J.; Plantenga, Todd D.

2010-06-01T23:59:59.000Z

98

Proactive Renewables Integration for Utility Distribution Planning and  

NLE Websites -- All DOE Office Websites (Extended Search)

Proactive Renewables Integration for Utility Distribution Planning and Proactive Renewables Integration for Utility Distribution Planning and Operations Speaker(s): Emma Stewart Date: March 5, 2013 - 12:00pm Location: 90-1099 Seminar Host/Point of Contact: Sila Kiliccote The interconnection process can be a laborious and expensive process for both utilities and developers. High PV penetration levels create a number of challenges for the management and operation of the utility grid. This study presents work being completed in Hawaii to improve and innovate the interconnect process, separating perceived issues from real technical concerns. Existing interconnection methods and standards such as IEEE 1547, Hawaii Rule 14H and California Rule 21 are evaluated in emerging high penetration scenarios. These rules define a 15% DG penetration level as a

99

Integrating Energy Efficiency and Demand Response into Utility Resource Plans  

Science Conference Proceedings (OSTI)

This report investigates the methods in which utilities integrate their supply-side and demand-side resources to meet their generating resource requirements. The major steps in developing a resource plan are reviewed, including the alternative methods currently employed. Finally, the report presents the results of a short survey that was administered to the advisors in Energy Utilization. The results show that methods are more sophisticated than 20 years ago, but more could be accomplished in ...

2013-01-14T23:59:59.000Z

100

Integrated Renewable Hydrogen Utility System (IRHUS) business plan  

DOE Green Energy (OSTI)

This business plan is for a proposed legal entity named IRHUS, Inc. which is to be formed as a subsidiary of Energy Partners, L.C. (EP) of West Palm Beach, Florida. EP is a research and development company specializing in hydrogen proton exchange membrane (PEM) fuel cells and systems. A fuel cell is an engine with no moving parts that takes in hydrogen and produces electricity. The purpose of IRHUS, Inc. is to develop and manufacture a self-sufficient energy system based on the fuel cell and other new technology that produces hydrogen and electricity. The product is called the Integrated renewable Hydrogen utility System (IRHUS). IRHUS, Inc. plans to start limited production of the IRHUS in 2002. The IRHUS is a unique product with an innovative concept in that it provides continuous electrical power in places with no electrical infrastructure, i.e., in remote and island locations. The IRHUS is a zero emissions, self-sufficient, hydrogen fuel generation system that produces electricity on a continuous basis by combining any renewable power source with hydrogen technology. Current plans are to produce a 10 kilowatt IRHUS MP (medium power). Future plans are to design and manufacture IRHUS models to provide power for a variety of power ranges for identified attractive market segments. The technological components of the IRHUS include an electrolyzer, hydrogen and oxygen storage subsystems, fuel cell system, and power control system. The IRHUS product is to be integrated with a variety of renewable energy technologies. 5 figs., 10 tabs.

NONE

1999-03-01T23:59:59.000Z

Note: This page contains sample records for the topic "integrated test plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


101

Fast flux test facility, transition project plan  

SciTech Connect

The FFTF Transition Project Plan, Revision 1, provides changes and project baseline for the deactivation activities necessary to transition the FFTF to a radiologically and industrially safe shutdown condition.

Guttenberg, S.

1994-11-15T23:59:59.000Z

102

Checkout, Testing, and Commissioning Plan RM  

Energy.gov (U.S. Department of Energy (DOE))

The CP RM Module is a tool that assists DOE federal project review teams in evaluating the sufficiency of the Commissioning Plan and its implementation. The CP RM can be used by the DOE federal...

103

Test plan for BWID Phase 2 electric arc melter vitrification tests  

SciTech Connect

This test plan describes the Buried Waste Integrated Demonstration (BWID), Phase 2, electric arc melter, waste treatment evaluation tests to be performed at the US Bureau of Mines (USBM) Albany Research Center. The BWID Arc Melter Vitrification Project is being conducted to evaluate and demonstrate existing industrial arc melter technology for thermally treating mixed transuranic-contaminated wastes and soils. Phase 1 baseline tests, performed during fiscal year 1993 at the USBM, were conducted on waste feeds representing incinerated buried mixed wastes and soils. In Phase 2, surrogate feeds will be processed that represent actual as-retrieved buried wastes from the Idaho National Engineering Laboratory`s Subsurface Disposal Area at the Radioactive Waste Management Complex.

Soelberg, N.R.; Turner, P.C.; Oden, L.L.; Anderson, G.L.

1994-10-01T23:59:59.000Z

104

Mixed Waste Integrated Program Quality Assurance requirements plan  

SciTech Connect

Mixed Waste Integrated Program (MWIP) is sponsored by the US Department of Energy (DOE), Office of Technology Development, Waste Management Division. The strategic objectives of MWIP are defined in the Mixed Waste Integrated Program Strategic Plan, and expanded upon in the MWIP Program Management Plan. This MWIP Quality Assurance Requirement Plan (QARP) applies to mixed waste treatment technologies involving both hazardous and radioactive constituents. As a DOE organization, MWIP is required to develop, implement, and maintain a written Quality Assurance Program in accordance with DOE Order 4700.1 Project Management System, DOE Order 5700.6C, Quality Assurance, DOE Order 5820.2A Radioactive Waste Management, ASME NQA-1 Quality Assurance Program Requirements for Nuclear Facilities and ANSI/ASQC E4-19xx Specifications and Guidelines for Quality Systems for Environmental Data Collection and Environmental Technology Programs. The purpose of the MWIP QA program is to establish controls which address the requirements in 5700.6C, with the intent to minimize risks and potential environmental impacts; and to maximize environmental protection, health, safety, reliability, and performance in all program activities. QA program controls are established to assure that each participating organization conducts its activities in a manner consistent with risks posed by those activities.

1994-04-15T23:59:59.000Z

105

Integrated Geothermal Well Testing: Test Objectives and Facilities  

DOE Green Energy (OSTI)

A new and highly integrated geothermal well test program was designed for three geothermal operators in the US (MCR, RGI and Mapco Geothermal). This program required the design, construction and operation of new well test facilities. The main objectives of the test program and facilities are to investigate the critical potential and worst problems associated with the well and produced fluids in a period of approximately 30 days. Field and laboratory investigations are required to determine and quantify the problems of fluid production, utilization and reinjection. The facilities are designed to handle a flow rate from a geothermal well of one million pounds per hour at a wellhead temperature of approximately 268 C (515 F). The facilities will handle an entire spectrum of temperature and rate conditions up to these limits. All pertinent conditions for future fluid exploitations can be duplicated with these facilities, thus providing critical information at the very early stages of field development. The new well test facilities have been used to test high temperature, liquid-dominated geothermal wells in the Imperial Valley of California. The test facilities still have some problems which should be solvable. The accomplishments of this new and highly integrated geothermal well test program are described in this paper.

Nicholson, R. W.; Vetter, O. J.

1981-01-01T23:59:59.000Z

106

Parking and routing information system phase 1 evaluation -- Individual evaluation test plans  

Science Conference Proceedings (OSTI)

A parking and routing information system (PARIS) is being designed and deployed at a test site on the Mountain Home Veterans Administration campus in Johnson City, Tennessee using three sensor technologies. The purpose of the PARIS project is to demonstrate innovative integration of vehicle sensing technologies with parking management strategies to improve mobility and relieve congestion associated with a growing medical/technology complex. This technical memorandum presents the four individual evaluation test plans, System Performance Individual Evaluation Test Plan, User Acceptance Individual Evaluation Test Plan, Institutional and Business Issues Individual Evaluation Test Plan, and Transportation Systems Individual Evaluation Test Plan, which were developed to support ORNL`s responsibilities and functions during the four studies. The plans define the level of effort required to satisfy the data collection, processing, and analysis requirements for the assessment of the system performance, user acceptance, institutional and business issues, and transportation systems components of the PARIS phase 1 evaluation. Each plan is divided into three subsections: executive summary, detailed study design, and study management.

Carter, R.J.

1997-04-01T23:59:59.000Z

107

Fast Flux Test Facility (FFTF) standby plan  

Science Conference Proceedings (OSTI)

The FFTF Standby Plan, Revision 0, provides changes to the major elements and project baselines to maintain the FFTF plant in a standby condition and to continue washing sodium from irradiated reactor fuel. The Plan is consistent with the Memorandum of Decision approved by the Secretary of Energy on January 17, 1997, which directed that FFTF be maintained in a standby condition to permit the Department to make a decision on whether the facility should play a future role in the Department of Energy`s dual track tritium production strategy. This decision would be made in parallel with the intended December 1998 decision on the selection of the primary, long- term source of tritium. This also allows the Department to review the economic and technical feasibility of using the FFTF to produce isotopes for the medical community. Formal direction has been received from DOE-RL and Fluor 2020 Daniel Hanford to implement the FFTF standby decision. The objective of the Plan is maintain the condition of the FFTF systems, equipment and personnel to preserve the option for plant restart within three and one-half years of a decision to restart, while continuing deactivation work which is consistent with the standby mode.

Hulvey, R.K.

1997-03-06T23:59:59.000Z

108

Transmission planning in the era of integrated resource planning: A survey of recent cases  

SciTech Connect

State action is critical to the expansion of the high-voltage transmission network, because regulated utilities must seek approval from utility commissions for proposals to site new lines. It is the purpose of this report to survey the regulatory treatment of issues that are unique to or ubiquitous in transmission planning and use. The authors review recent transmission siting cases to examine how the issues are presented to and resolved by state regulatory commissions and to provide a perspective for more general discussion of transmission policy. Their primary focus is on planning issues. Transmission capacity expansion is not typically treated in integrated resource planning. It is usually assumed that there is adequate transmission to achieve any particular plan. The authors believe that one important reason for this omission is the inherent complexity of transmission system expansion. Regulators and competitors may be at a serious disadvantage in negotiating or adjudicating specific transmission proposals with utilities, who generally have greater knowledge of both general technological considerations and case specifics. This problem of asymmetric information must be addressed at some level in planning or dispute resolution. However, they observe that explicit consideration of the information problem is absent from most regulatory and technical analysis of transmission. The goal of this survey is to share knowledge about the problems facing state regulators over the siting of new transmission facilities, and help to define constructive approaches to them.

Baldick, R.; Kahn, E.P.

1992-09-01T23:59:59.000Z

109

SAPHIRE 8 Software Acceptance Test Plan  

SciTech Connect

This document describe & report the overall SAPHIRE 8 Software acceptance test paln to offically release the SAPHIRE version 8 software to the NRC custoer for distribution.

Ted S. Wood; Curtis L. Smith

2009-07-01T23:59:59.000Z

110

Nevada Test Site Treatment Plan. Revision 2  

SciTech Connect

Treatment Plans (STPS) are required for facilities at which the US Department of Energy (DOE) or stores mixed waste, defined by the Federal Facility Compliance Act (FFCAct) as waste containing both a hazardous waste subject to the Resource Conservation and Recovery Act and a radioactive material subject to the Atomic Energy Act. On April 6, 1993, DOE published a Federal Register notice (58 FR 17875) describing its proposed process for developing the STPs in three phases including a Conceptual, a Draft, and a Proposed Site Treatment Plan (PSTP). All of the DOE Nevada Operations Office STP iterations have been developed with the state of Nevada`s input. The options and schedules reflect a ``bottoms-up`` approach and have been evaluated for impacts on other DOE sites, as well as impacts to the overall DOE program. Changes may have occurred in the preferred option and associated schedules between the PSTP, which was submitted to the state of Nevada and US Environmental Protection Agency April 1995, and the Final STP (hereafter referred to as the STP) as treatment evaluations progressed. The STP includes changes that have occurred since the submittal of the PSTP as a result of state-to-state and DOE-to-state discussions.

1996-03-01T23:59:59.000Z

111

Fast Flux Test Facility project plan. Revision 2  

Science Conference Proceedings (OSTI)

The Fast Flux Test Facility (FFTF) Transition Project Plan, Revision 2, provides changes to the major elements and project baseline for the deactivation activities necessary to transition the FFTF to a radiologically and industrially safe shutdown condition.

Hulvey, R.K.

1995-11-01T23:59:59.000Z

112

Integrated Waste Treatment Unit GFSI Risk Management Plan  

SciTech Connect

This GFSI Risk Management Plan (RMP) describes the strategy for assessing and managing project risks for the Integrated Waste Treatment Unit (IWTU) that are specifically within the control and purview of the U.S. Department of Energy (DOE), and identifies the risks that formed the basis for the DOE contingency included in the performance baseline. DOE-held contingency is required to cover cost and schedule impacts of DOE activities. Prior to approval of the performance baseline (Critical Decision-2) project cost contingency was evaluated during a joint meeting of the Contractor Management Team and the Integrated Project Team for both contractor and DOE risks to schedule and cost. At that time, the contractor cost and schedule risk value was $41.3M and the DOE cost and schedule risk contingency value is $39.0M. The contractor cost and schedule risk value of $41.3M was retained in the performance baseline as the contractor's management reserve for risk contingency. The DOE cost and schedule risk value of $39.0M has been retained in the performance baseline as the DOE Contingency. The performance baseline for the project was approved in December 2006 (Garman 2006). The project will continue to manage to the performance baseline and change control thresholds identified in PLN-1963, ''Idaho Cleanup Project Sodium-Bearing Waste Treatment Project Execution Plan'' (PEP).

W. A. Owca

2007-06-21T23:59:59.000Z

113

Integrated Waste Treatment Unit GFSI Risk Management Plan  

SciTech Connect

This GFSI Risk Management Plan (RMP) describes the strategy for assessing and managing project risks for the Integrated Waste Treatment Unit (IWTU) that are specifically within the control and purview of the U.S. Department of Energy (DOE), and identifies the risks that formed the basis for the DOE contingency included in the performance baseline. DOE-held contingency is required to cover cost and schedule impacts of DOE activities. Prior to approval of the performance baseline (Critical Decision-2) project cost contingency was evaluated during a joint meeting of the Contractor Management Team and the Integrated Project Team for both contractor and DOE risks to schedule and cost. At that time, the contractor cost and schedule risk value was $41.3M and the DOE cost and schedule risk contingency value is $39.0M. The contractor cost and schedule risk value of $41.3M was retained in the performance baseline as the contractor's management reserve for risk contingency. The DOE cost and schedule risk value of $39.0M has been retained in the performance baseline as the DOE Contingency. The performance baseline for the project was approved in December 2006 (Garman 2006). The project will continue to manage to the performance baseline and change control thresholds identified in PLN-1963, ''Idaho Cleanup Project Sodium-Bearing Waste Treatment Project Execution Plan'' (PEP).

W. A. Owca

2007-06-21T23:59:59.000Z

114

Integrated system dynamics toolbox for water resources planning.  

Science Conference Proceedings (OSTI)

Public mediated resource planning is quickly becoming the norm rather than the exception. Unfortunately, supporting tools are lacking that interactively engage the public in the decision-making process and integrate over the myriad values that influence water policy. In the pages of this report we document the first steps toward developing a specialized decision framework to meet this need; specifically, a modular and generic resource-planning ''toolbox''. The technical challenge lies in the integration of the disparate systems of hydrology, ecology, climate, demographics, economics, policy and law, each of which influence the supply and demand for water. Specifically, these systems, their associated processes, and most importantly the constitutive relations that link them must be identified, abstracted, and quantified. For this reason, the toolbox forms a collection of process modules and constitutive relations that the analyst can ''swap'' in and out to model the physical and social systems unique to their problem. This toolbox with all of its modules is developed within the common computational platform of system dynamics linked to a Geographical Information System (GIS). Development of this resource-planning toolbox represents an important foundational element of the proposed interagency center for Computer Aided Dispute Resolution (CADRe). The Center's mission is to manage water conflict through the application of computer-aided collaborative decision-making methods. The Center will promote the use of decision-support technologies within collaborative stakeholder processes to help stakeholders find common ground and create mutually beneficial water management solutions. The Center will also serve to develop new methods and technologies to help federal, state and local water managers find innovative and balanced solutions to the nation's most vexing water problems. The toolbox is an important step toward achieving the technology development goals of this center.

Reno, Marissa Devan; Passell, Howard David; Malczynski, Leonard A.; Peplinski, William J.; Tidwell, Vincent Carroll; Coursey, Don (University of Chicago, Chicago, IL); Hanson, Jason (University of New Mexico, Albuquerque, NM); Grimsrud, Kristine (University of New Mexico, Albuquerque, NM); Thacher, Jennifer (University of New Mexico, Albuquerque, NM); Broadbent, Craig (University of New Mexico, Albuquerque, NM); Brookshire, David (University of New Mexico, Albuquerque, NM); Chemak, Janie (University of New Mexico, Albuquerque, NM); Cockerill, Kristan (Cockeril Consulting, Boone, NC); Aragon, Carlos (New Mexico Univeristy of Technology and Mining (NM-TECH), Socorro, NM); Hallett, Heather (New Mexico Univeristy of Technology and Mining (NM-TECH), Socorro, NM); Vivoni, Enrique (New Mexico Univeristy of Technology and Mining (NM-TECH), Socorro, NM); Roach, Jesse

2006-12-01T23:59:59.000Z

115

Test plan for the 34 meter vertical axis wind turbine test bed located at Bushland, Texas  

DOE Green Energy (OSTI)

A plan is presented for the testing and evaluation of a new 500 kw vertical axis wind turbine test bed. The plan starts with the initial measurements made during construction, proceeds through evaluation of the design, the development of control methods, and finally to the test bed phase where new concepts are evaluated and in-depth studies are performed.

Stephenson, W.A.

1986-12-01T23:59:59.000Z

116

Automated testing as an aid to systems integration  

Science Conference Proceedings (OSTI)

Within BTs Systems Integration department, the integration and testing of large, complex software systems often requires large and complex test regimes. Optimising the activities and time-scales within this part of the life cycle will invariably ...

I. D. Hicks; G. J. South; A. O. Oshisanwo

1997-07-01T23:59:59.000Z

117

Optimization planning systems and their implementation and application in vertically integrated oil companies  

Science Conference Proceedings (OSTI)

The approaches to planning of activities of a vertically integrated oil company by using optimization systems are considered. Development, implementation, and support of such systems are discussed. These problems fall under the APS (Advanced Planning ...

A. S. Khokhlov; A. I. Konnov; A. E. Zel'Din

2012-04-01T23:59:59.000Z

118

In situ vitrification laboratory-scale test work plan  

SciTech Connect

The Buried Waste Program was established in October 1987 to accelerate the studies needed to develop a long-term management plan for the buried mixed waste at the Radioactive Waste Management Complex at Idaho Engineering Laboratory. The In Situ Vitrification Project is being conducted in a Comprehensive Environmental Response, Compensation, and Liability Act feasibility study format to identify methods for the long-term management of mixed buried waste. To support the overall feasibility study, the situ vitrification treatability investigations are proceeding along the three parallel paths: laboratory-scale tests, intermediate field tests, and field tests. Laboratory-scale tests are being performed to provide data to mathematical modeling efforts, which, in turn, will support design of the field tests and to the health and safety risk assessment. This laboratory-scale test work plan provides overall testing program direction to meet the current goals and objectives of the in situ vitrification treatability investigation. 12 refs., 1 fig., 7 tabs.

Nagata, P.K.; Smith, N.L.

1991-05-01T23:59:59.000Z

119

Experimental Test Plan DOE Tidal and River Reference Turbines  

Science Conference Proceedings (OSTI)

Our aim is to provide details of the experimental test plan for scaled model studies in St. Anthony Falls Laboratory (SAFL) Main Channel at the University of Minnesota, including a review of study objectives, descriptions of the turbine models, the experimental set-up, instrumentation details, instrument measurement uncertainty, anticipated experimental test cases, post-processing methods, and data archiving for model developers.

Neary, Vincent S [ORNL; Hill, Craig [St. Anthony Falls Laboratory, 2 Third Avenue SE, Minneapolis, MN 55414; Chamorro, Leonardo [St. Anthony Falls Laboratory, 2 Third Avenue SE, Minneapolis, MN 55414; Gunawan, Budi [ORNL

2012-09-01T23:59:59.000Z

120

Mixer pump test plan for double shell tank AZ-101  

Science Conference Proceedings (OSTI)

Mixer pump systems have been chosen as the method for retrieval of tank wastes contained in double shell tanks at Hanford. This document describes the plan for testing and demonstrating the ability of two 300 hp mixer pumps to mobilize waste in tank AZ-101. The mixer pumps, equipment and instrumentation to monitor the test were installed by Project W-151.

STAEHR, T.W.

1999-05-12T23:59:59.000Z

Note: This page contains sample records for the topic "integrated test plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


121

Flammable gas interlock spoolpiece flow response test plan and procedure  

DOE Green Energy (OSTI)

The purpose of this test plan and procedure is to test the Whittaker electrochemical cell and the Sierra Monitor Corp. flammable gas monitors in a simulated field flow configuration. The sensors are used on the Rotary Mode Core Sampling (RMCS) Flammable Gas Interlock (FGI), to detect flammable gases, including hydrogen and teminate the core sampling activity at a predetermined concentration level.

Schneider, T.C., Fluor Daniel Hanford

1997-02-13T23:59:59.000Z

122

Integrated Monitoring Plan for the Hanford Groundwater Monitoring Project  

SciTech Connect

Groundwater is monitored at the Hanford Site to fulfill a variety of state and federal regulations, including the Atomic Energy Act of 1954; the Resource Conservation and Recovery Act of 1976; the Comprehensive Environmental Response, Compensation, and Liability Act of 1980; and Washington Administrative Code. Separate monitoring plans are prepared for various requirements, but sampling is coordinated and data are shared among users to avoid duplication of effort. The U.S. Department of Energy manages these activities through the Hanford Groundwater Monitoring Project. This document is an integrated monitoring plan for the groundwater project. It documents well and constituent lists for monitoring required by the Atomic Energy Act of 1954 and its implementing orders; includes other, established monitoring plans by reference; and appends a master well/constituent/ frequency matrix for the entire site. The objectives of monitoring fall into three general categories: plume and trend tracking, treatment/ storage/disposal unit monitoring, and remediation performance monitoring. Criteria for selecting Atomic Energy Act of 1954 monitoring networks include locations of wells in relation to known plumes or contaminant sources, well depth and construction, historical data, proximity to the Columbia River, water supplies, or other areas of special interest, and well use for other programs. Constituent lists were chosen based on known plumes and waste histories, historical groundwater data, and, in some cases, statistical modeling. Sampling frequencies were based on regulatory requirements, variability of historical data, and proximity to key areas. For sitewide plumes, most wells are sampled every 3 years. Wells monitoring specific waste sites or in areas of high variability will be sampled more frequently.

MJ Hartman; PE Dresel; JW Lindberg; DR Newcomer; EC Thornton

2000-10-18T23:59:59.000Z

123

Integrated Monitoring Plan for the Hanford Groundwater Monitoring Project  

SciTech Connect

Groundwater is monitored at the Hanford Site to fulfill a variety of state and federal regulations, including the Atomic Energy Act of 1954 the Resource Conservation and Recovery Act of 1976 the Comprehensive Environmental Response, Compensation, and Liability Act of 1980; and Washington Administrative Code. Separate monitoring plans are prepared for various requirements, but sampling is coordinated and data are shared among users to avoid duplication of effort. The US Department of Energy manages these activities through the Hanford Groundwater Monitoring Project. This document is an integrated monitoring plan for the groundwater project. It documents well and constituent lists for monitoring required by the Atomic Energy Act of 1954 and its implementing orders; includes other, established monitoring plans by reference; and appends a master well/constituent/frequency matrix for the entire site. The objectives of monitoring fall into three general categories plume and trend tracking, treatment/storage/disposal unit monitoring, and remediation performance monitoring. Criteria for selecting Atomic Energy Act of 1954 monitoring networks include locations of wells in relation to known plumes or contaminant sources, well depth and construction, historical data, proximity to the Columbia River, water supplies, or other areas of special interest, and well use for other programs. Constituent lists were chosen based on known plumes and waste histories, historical groundwater data, and, in some cases, statistical modeling. Sampling frequencies were based on regulatory requirements, variability of historical data, and proximity to key areas. For sitewide plumes, most wells are sampled every 3 years. Wells monitoring specific waste sites or in areas of high variability will be sampled more frequently.

Newcomer, D.R.; Thornton, E.C.; Hartman, M.J.; Dresel, P.E.

1999-10-06T23:59:59.000Z

124

Tank waste remediation system integrated technology plan. Revision 2  

SciTech Connect

The Hanford Site, located in southeastern Washington State, is operated by the US Department of Energy (DOE) and its contractors. Starting in 1943, Hanford supported fabrication of reactor fuel elements, operation of production reactors, processing of irradiated fuel to separate and extract plutonium and uranium, and preparation of plutonium metal. Processes used to recover plutonium and uranium from irradiated fuel and to recover radionuclides from tank waste, plus miscellaneous sources resulted in the legacy of approximately 227,000 m{sup 3} (60 million gallons) of high-level radioactive waste, currently in storage. This waste is currently stored in 177 large underground storage tanks, 28 of which have two steel walls and are called double-shell tanks (DSTs) an 149 of which are called single-shell tanks (SSTs). Much of the high-heat-emitting nuclides (strontium-90 and cesium-137) has been extracted from the tank waste, converted to solid, and placed in capsules, most of which are stored onsite in water-filled basins. DOE established the Tank Waste Remediation System (TWRS) program in 1991. The TWRS program mission is to store, treat, immobilize and dispose, or prepare for disposal, the Hanford tank waste in an environmentally sound, safe, and cost-effective manner. Technology will need to be developed or improved to meet the TWRS program mission. The Integrated Technology Plan (ITP) is the high-level consensus plan that documents all TWRS technology activities for the life of the program.

Eaton, B.; Ignatov, A.; Johnson, S.; Mann, M.; Morasch, L.; Ortiz, S.; Novak, P. [eds.] [Pacific Northwest Lab., Richland, WA (United States)

1995-02-28T23:59:59.000Z

125

Field Testing of Automated Demand Response for Integration of...  

NLE Websites -- All DOE Office Websites (Extended Search)

Field Testing of Automated Demand Response for Integration of Renewable Resources in California's Ancillary Services Market for Regulation Products Title Field Testing of Automated...

126

Building system integration research: recommendations for a US Department of Energy multiyear program plan  

SciTech Connect

This plan describes the scope, technical content, and resources required to conduct the Building System Integration (BSI) research program during FY 1987 through 1991. System integration research is defined, the need for the research is discussed, its benefits are outlined, and the history of building system integration research is summarized. The program scope, the general approach taken in developing this program plan, and the plan's contents are also described.

1986-01-01T23:59:59.000Z

127

IFE Chamber Technology Testing Program In NIF and Chamber Development Test Plan Mohamed A. Abdou  

E-Print Network (OSTI)

IFE Chamber Technology Testing Program In NIF and Chamber Development Test Plan Mohamed A. Abdou chamber technology testing program in NIF involoving: criteria for evaluation prior to NIF testing were addressed in this paper. In order to maximize the benefits of testing program

Abdou, Mohamed

128

Decision support for integrated water-energy planning.  

SciTech Connect

Currently, electrical power generation uses about 140 billion gallons of water per day accounting for over 39% of all freshwater withdrawals thus competing with irrigated agriculture as the leading user of water. Coupled to this water use is the required pumping, conveyance, treatment, storage and distribution of the water which requires on average 3% of all electric power generated. While water and energy use are tightly coupled, planning and management of these fundamental resources are rarely treated in an integrated fashion. Toward this need, a decision support framework has been developed that targets the shared needs of energy and water producers, resource managers, regulators, and decision makers at the federal, state and local levels. The framework integrates analysis and optimization capabilities to identify trade-offs, and 'best' alternatives among a broad list of energy/water options and objectives. The decision support framework is formulated in a modular architecture, facilitating tailored analyses over different geographical regions and scales (e.g., national, state, county, watershed, NERC region). An interactive interface allows direct control of the model and access to real-time results displayed as charts, graphs and maps. Ultimately, this open and interactive modeling framework provides a tool for evaluating competing policy and technical options relevant to the energy-water nexus.

Tidwell, Vincent Carroll; Malczynski, Leonard A.; Kobos, Peter Holmes; Castillo, Cesar; Hart, William Eugene; Klise, Geoffrey T.

2009-10-01T23:59:59.000Z

129

Hydrogen Posture Plan: An Integrated Research, Development and...  

NLE Websites -- All DOE Office Websites (Extended Search)

PLAN . . United States Department of Energy February 2004 ix DOE Hydrogen Posture Plan A National Commitment In his State of the Union address, President Bush announced a...

130

Test Plan for K Basin floor sludge consolidated sampling equipment  

SciTech Connect

The purpose of this document is to provide the test procedure for the function and acceptance testing of the K Basin Floor Sludge Consolidated Sampling Equipment. This equipment will be used to transfer K Basin floor sludge to a sludge sampling container for subsequent shipment to an analysis or testing facility. This equipment will provide sampling consistent with data quality objectives and sampling plans currently being developed.

OLIVER, J.W.

1998-10-30T23:59:59.000Z

131

Tips for Planning, Building, and Testing a Model Car  

NLE Websites -- All DOE Office Websites (Extended Search)

Tips for Planning, Building, and Testing Your Lithium- Ion Battery Powered Car CONTENTS:  Teacher Overview  What Teachers Can Do To Help  Student Design Plan  Brainstorming  Materials  Chassis Design  Transmission  Gear Ratio  Wheels and Bearings  Battery  Testing  Trouble Shooting TEACHER OVERVIEW  The Lithium-ion battery powered car competition is designed to be an engineering challenge for middle school students.  Students will be exploring the following concepts while planning, building and testing their cars:  Alternative energy sources  Engineering design  Aerodynamics  Force and motion  Teamwork  Problem solving  Teams who do not have a completed car at the

132

PROPERTIES IMPORTANT TO MIXING FOR WTP LARGE SCALE INTEGRATED TESTING  

Science Conference Proceedings (OSTI)

Large Scale Integrated Testing (LSIT) is being planned by Bechtel National, Inc. to address uncertainties in the full scale mixing performance of the Hanford Waste Treatment and Immobilization Plant (WTP). Testing will use simulated waste rather than actual Hanford waste. Therefore, the use of suitable simulants is critical to achieving the goals of the test program. External review boards have raised questions regarding the overall representativeness of simulants used in previous mixing tests. Accordingly, WTP requested the Savannah River National Laboratory (SRNL) to assist with development of simulants for use in LSIT. Among the first tasks assigned to SRNL was to develop a list of waste properties that matter to pulse-jet mixer (PJM) mixing of WTP tanks. This report satisfies Commitment 5.2.3.1 of the Department of Energy Implementation Plan for Defense Nuclear Facilities Safety Board Recommendation 2010-2: physical properties important to mixing and scaling. In support of waste simulant development, the following two objectives are the focus of this report: (1) Assess physical and chemical properties important to the testing and development of mixing scaling relationships; (2) Identify the governing properties and associated ranges for LSIT to achieve the Newtonian and non-Newtonian test objectives. This includes the properties to support testing of sampling and heel management systems. The test objectives for LSIT relate to transfer and pump out of solid particles, prototypic integrated operations, sparger operation, PJM controllability, vessel level/density measurement accuracy, sampling, heel management, PJM restart, design and safety margin, Computational Fluid Dynamics (CFD) Verification and Validation (V and V) and comparison, performance testing and scaling, and high temperature operation. The slurry properties that are most important to Performance Testing and Scaling depend on the test objective and rheological classification of the slurry (i.e., Newtonian or non-Newtonian). The most important properties for testing with Newtonian slurries are the Archimedes number distribution and the particle concentration. For some test objectives, the shear strength is important. In the testing to collect data for CFD V and V and CFD comparison, the liquid density and liquid viscosity are important. In the high temperature testing, the liquid density and liquid viscosity are important. The Archimedes number distribution combines effects of particle size distribution, solid-liquid density difference, and kinematic viscosity. The most important properties for testing with non-Newtonian slurries are the slurry yield stress, the slurry consistency, and the shear strength. The solid-liquid density difference and the particle size are also important. It is also important to match multiple properties within the same simulant to achieve behavior representative of the waste. Other properties such as particle shape, concentration, surface charge, and size distribution breadth, as well as slurry cohesiveness and adhesiveness, liquid pH and ionic strength also influence the simulant properties either directly or through other physical properties such as yield stress.

Koopman, D.; Martino, C.; Poirier, M.

2012-04-26T23:59:59.000Z

133

Integrating the principles of strategic environmental assessment into local comprehensive land use plans in California  

E-Print Network (OSTI)

The lack of early integration with the planning and decision-making process has been a major problem in environmental assessment. Traditional project-based environmental impact assessment has inadequate incentives and capacities to incorporate critical environmental impacts at a broader temporal or spatial scale. While many applications have been geared towards implementing project-level environmental assessments, comparatively little research has been done to determine how to incorporate strategically critical environmental impacts into local planning. Although the principles of strategic environmental assessment (SEA) are not yet required in local planning in the United States, these principles create a theoretical framework for local environmental assessment. The objective of this study is to examine the ability of local plans to integrate and implement the key SEA principles. This study focuses on increasing the understanding of how and where to integrate environmental impacts into the local planning and decision-making process by converting the principles of SEA into specific planning tools, policies, and implementation strategies. This study develops a protocol with 112 indicators to measure the strengths and weaknesses of integrating strategic environmental assessment into local comprehensive land use plans. A random sample of 40 California local comprehensive land use plans and associated planning processes is evaluated based on this plan quality evaluation protocol. Statistical analysis and multiple regression models identify the factors affecting the quality of plans with respect to their ability to assess environmental impacts. The results identify the relative strengths and weaknesses of the ability of local jurisdictions to integrate the SEA principles. The results show that many strategically important environmental issues and tools are rarely adopted by current local plans. The regression analysis results further identify the effects of planning capacity, environmental assessment capacity, public participation and contextual variables on environmental assessment plan quality. The findings extend established planning theory and practice by incorporating strategic environmental considerations into the existing framework of what constitutes a high quality local land use comprehensive plan and suggest ways to improve plan quality.

Tang, Zhenghong

2007-05-01T23:59:59.000Z

134

Test Methods Standing Technical Committee Strategic Plan - February 2012  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Test Methods Standing Technical Committee Test Methods Standing Technical Committee 2011 Strategic Plan V1.1 - Draft 2/24/2012 Committee Chair: 2011-2012 Dane Christensen National Renewable Energy Laboratory 2 Prioritization of Gaps, Barriers and Needs The following table prioritizes the Gaps, Barriers and Needs described in this document. Rank Description Estimated Priority Effort 1 Heat Pump Water Heater Field Test Protocol H M 2a Method for infinitely variable fan airflow measurement H H 2b Non-Intrusive Natural Gas Flow Measurement H H 3 Data Logger with Increased Data Capabilities M M 4 Room Air Mixing Analysis M H Contents Summary of Test Methods STC Strategic Plan .......................................................................................................... 3

135

The role of competitive forces in integrated resource planning  

SciTech Connect

In this report, we study the potential for competitive forces to enhance the efficiency of integrated resource planning and produce consumer cost reductions. We examine the efficiency gains from competition in the private power market, and ask whether similar forces can be successful on the demand-side of the market. The goal of this analysis is to identify and elucidate options available to state Public Utility Commissions (PUCs) to support competition in utility demand-side management programs to achieve efficiencies similar to those being achieved through development of competitive forces on the supply-side of the industry. We consider the entire market structure from upstream suppliers to distribution intermediaries to ultimate consumers. The market structure differs substantially between the demand-side and the supply-side of the electricity market. Demand-site electricity markets have a longer distribution chain and more intermediaries than the supply-side, which is attributable in part to the ultimately retail nature of demand and the wholesale nature of supply, and in part indicates market failures.

Kahn, E.; Goldman, C.

1991-10-01T23:59:59.000Z

136

Environment, Safety, Health, and Quality Plan for the Buried Waste Integrated Demonstration Program  

SciTech Connect

The Buried Waste Integrated Demonstration (BWID) is a program funded by the US Department of Energy Office of Technology Development. BWID supports the applied research, development, demonstration, testing, and evaluation of a suite of advanced technologies that together form a comprehensive remediation system for the effective and efficient remediation of buried waste. This document describes the Environment, Safety, Health, and Quality requirements for conducting BWID activities at the Idaho National Engineering Laboratory. Topics discussed in this report, as they apply to BWID operations, include Federal, State of Idaho, and Environmental Protection Agency regulations, Health and Safety Plans, Quality Program Plans, Data Quality Objectives, and training and job hazard analysis. Finally, a discussion is given on CERCLA criteria and System and Performance audits as they apply to the BWID Program.

Walker, S.

1994-05-01T23:59:59.000Z

137

Integrated plan for LArTPC neutrino detectors in the US  

SciTech Connect

We present an integrated R&D plan aimed at demonstrating the ability to build a very large Liquid Argon Time Projection Chamber (LArTPC), on a scale suitable for use as a Far Detector for the LBNE neutrino oscillation experiment. This plan adopts current LArTPC R&D-related activities and proposes new ones to address questions that go beyond those being answered by the current efforts. We have employed a risk evaluation strategy to identify questions that can be answered (or risks that can be mitigated) through one or more R&D steps. In summary form, the plan consists of the following pre-existing components: (1) The Materials Test Stand program, now in operation at Fermilab, addressing questions pertaining to maintenance of argon purity; (2) Existing electronics test stands at FNAL and BNL; (3) The Liquid Argon Purity Demonstrator (LAPD) now being assembled at Fermilab; (4) The ArgoNeuT prototype LArTPC, now running in the NuMI beam; (5) The MicroBooNE experiment, proposed as a physics experiment that will advance our understanding of the LArTPC technology, now completing its conceptual design phase; (6) A software development effort that is well integrated across present and planned LArTPC detectors. We are proposing to add to these efforts the following: (1) A membrane cryostat mechanical prototype to evaluate and gain expertise with this technology; (2) An installation and integration prototype, to understand issues pertaining to detector assembly, particularly in an underground environment; (3) A {approx} 5% scale electronics systems test to understand system-wide issues as well as individual component reliability. (4) A calibration test stand that would consist of a small TPC to be exposed to a test beam for calibration studies, relevant for evaluation of physics sensitivities. We have developed a timeline and milestones for achieving these goals as discussed in Section 4. The proposed activities necessary for the final design of LAr20 are complete by CD3 in 2014.

Baller, B.; Fleming, B.; /Fermilab

2009-11-01T23:59:59.000Z

138

Mobility in environmental planning: an integrated multi-agent approach  

Science Conference Proceedings (OSTI)

Mobility infrastructure planning is an increasingly crucial aspect of environmental planning, essential to boost regional economies and social relations, as well as critical for environmental impacts involved. Structuring inherently complex issues and ...

D. Borri; D. Camarda; A. De Liddo

2005-09-01T23:59:59.000Z

139

Hanford Integrated Planning Process: 1993 Hanford Site-specific science and technology plan  

Science Conference Proceedings (OSTI)

This document is the FY 1993 report on Hanford Site-specific science and technology (S&T) needs for cleanup of the Site as developed via the Hanford Integrated Planning Process (HIPP). It identifies cleanup problems that lack demonstrated technology solutions and technologies that require additional development. Recommendations are provided regarding allocation of funding to address Hanford`s highest-priority technology improvement needs, technology development needs, and scientific research needs, all compiled from a Sitewide perspective. In the past, the S&T agenda for Hanford Site cleanup was sometimes driven by scientists and technologists, with minimal input from the ``problem owners`` (i.e., Westinghouse Hanford Company [WHC] staff who are responsible for cleanup activities). At other times, the problem-owners made decisions to proceed with cleanup without adequate scientific and technological inputs. Under both of these scenarios, there was no significant stakeholder involvement in the decision-making process. One of the key objectives of HIPP is to develop an understanding of the integrated S&T requirements to support the cleanup mission, (a) as defined by the needs of the problem owners, the values of the stakeholders, and the technology development expertise that exists at Hanford and elsewhere. This requires a periodic, systematic assessment of these needs and values to appropriately define a comprehensive technology development program and a complementary scientific research program. Basic to our success is a methodology that is defensible from a technical perspective and acceptable to the stakeholders.

Not Available

1993-12-01T23:59:59.000Z

140

NETL: PPII - Integration of Low-NOx Burners with an Optimization Plan for  

NLE Websites -- All DOE Office Websites (Extended Search)

Integration of Low-NOx Burners with an Optimization Plan for Boiler Combustion Integration of Low-NOx Burners with an Optimization Plan for Boiler Combustion - Project Brief [PDF-72KB] Sunflower Electric Power Corp., Garden City, Finney County, KS PROJECT FACT SHEET Achieving New Source Performance Standards (NSPS) Through Integration of Low-NOx Burners with an Optimization Plan for Boiler Combustion [PDF-260KB] (Oct 2008) PROGRAM PUBLICATIONS Final Report Achieving NSPS Emission Standards Through Integration of Low NOx Burners with an Optimization Plan for Boiler Combustion [PDF-3.4MB] (June 2006) CCT Reports: Project Performance Summaries, Post-Project Assessments, & Topical Reports Achieving New Source Performance Standards (NSPS) Emission Standards through Integration of Low-NOx Burners with an Optimization Plan for Boiler Combustion: A DOE Assessment [PDF-1.4MB] (Nov 2006)

Note: This page contains sample records for the topic "integrated test plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


141

A flexible IT infrastructure for integrated urban planning  

Science Conference Proceedings (OSTI)

This paper presents an IT infrastructure based on an event driven architecture with the objective to decrease the turnaround time for urban planning. Most urban planning takes a long time, not only to get all stakeholders involved, but also to assess ... Keywords: Urban planning, event driven architecture, flexibility, infrastructure, interoperability

Wout Hofman; Walter Lohman; Ab Schelling

2011-04-01T23:59:59.000Z

142

Renewable Electrolysis Integrated Systems Development and Testing...  

NLE Websites -- All DOE Office Websites (Extended Search)

integrated renewable hydrogen demonstration project to support industry innovation and DOE Technology Validation goals. Technical Barriers This project addresses the following...

143

Test Plan: Sludge Treatment Project Corrosion Process Chemistry Follow-on Testing  

DOE Green Energy (OSTI)

This test plan was prepared by the Pacific Northwest National Laboratory (PNNL) under contract with Fluor Hanford (FH). The test plan describes the scope and conditions to be used to perform laboratory-scale testing of the Sludge Treatment Project (STP) hydrothermal treatment of K Basin sludge. The STP, managed for the U. S. Department of Energy (DOE) by FH, was created to design and operate a process to eliminate uranium metal from the sludge prior to packaging for Waste Isolation Pilot Plant (WIPP) by using high temperature liquid water to accelerate the reaction, produce uranium dioxide from the uranium metal, and safely discharge the hydrogen. The proposed testing builds on the approach and laboratory test findings for both K Basin sludge and simulated sludge garnered during prior testing from September 2006 to March 2007. The outlined testing in this plan is designed to yield further understanding of the nature of the chemical reactions, the effects of compositional and process variations and the effectiveness of various strategies to mitigate the observed high shear strength phenomenon observed during the prior testing. These tests are designed to provide process validation and refinement vs. process development and design input. The expected outcome is to establish a level of understanding of the chemistry such that successful operating strategies and parameters can be implemented within the confines of the existing STP corrosion vessel design. In July 2007, the DOE provided direction to FH regarding significant changes to the scope of the overall STP. As a result of the changes, FH directed PNNL to stop work on most of the planned activities covered in this test plan. Therefore, it is unlikely the testing described here will be performed. However, to preserve the test strategy and details developed to date, the test plan has been published.

Delegard, Calvin H.; Schmidt, Andrew J.; Poloski, Adam P.

2007-08-17T23:59:59.000Z

144

Vibration test plan for a space station heat pipe subassembly  

SciTech Connect

This test plan describes the Sundstrand portion of task two of Los Alamos National Laboratory (LANL) contract 9-x6H-8102L-1. Sundstrand Energy Systems was awarded a contract to investigate the performance capabilities of a potassium liquid metal heat pipe as applied to the Organic Rankine Cycle (ORC) solar dynamic power system for the Space Station. The test objective is to expose the heat pipe subassembly to the random vibration environment which simulates the space shuttle launch condition. The results of the test will then be used to modify as required future designs of the heat pipe.

Parekh, M.B. [Sundstrand Energy Systems, Rockford, IL (United States)

1987-09-29T23:59:59.000Z

145

Test Plan: Phase 1, Hanford LLW melter tests, GTS Duratek, Inc.  

SciTech Connect

This document provides a test plan for the conduct of vitrification testing by a vendor in support of the Hanford Tank Waste Remediation System (TWRS) Low-Level Waste (LLW) Vitrification Program. The vendor providing this test plan and conducting the work detailed within it [one of seven selected for glass melter testing under Purchase Order MMI-SVV-384215] is GTS Duratek, Inc., Columbia, Maryland. The GTS Duratek project manager for this work is J. Ruller. This test plan is for Phase I activities described in the above Purchase Order. Test conduct includes melting of glass with Hanford LLW Double-Shell Slurry Feed waste simulant in a DuraMelter{trademark} vitrification system.

Eaton, W.C.

1995-06-14T23:59:59.000Z

146

Job Applicant Faking of Overt Integrity Tests: Fact or Fantasy?.  

E-Print Network (OSTI)

??Integrity tests are among the least utilized pre-employment selection instruments due, at least in part, to concern regarding the ease at which applicants can successfully (more)

Stewart, Caitlin

2004-01-01T23:59:59.000Z

147

Fluor Hanford, Inc. Groundwater and Technical Integration Support (Master Project) Quality Assurance Management Plan  

SciTech Connect

The scope of the Fluor Hanford, Inc. Groundwater and Technical Integration Support (Master Project) is to provide technical and integration support to Fluor Hanford, Inc., including operable unit investigations at 300-FF-5 and other groundwater operable units, strategic integration, technical integration and assessments, remediation decision support, and science and technology. This Quality Assurance Management Plan provides the quality assurance requirements and processes that will be followed by the Fluor Hanford, Inc. Groundwater and Technical Integration Support (Master Project).

Fix, N. J.

2008-02-20T23:59:59.000Z

148

Hanford Tank Farms Waste Certification Flow Loop Test Plan  

Science Conference Proceedings (OSTI)

A future requirement of Hanford Tank Farm operations will involve transfer of wastes from double shell tanks to the Waste Treatment Plant. As the U.S. Department of Energy contractor for Tank Farm Operations, Washington River Protection Solutions anticipates the need to certify that waste transfers comply with contractual requirements. This test plan describes the approach for evaluating several instruments that have potential to detect the onset of flow stratification and critical suspension velocity. The testing will be conducted in an existing pipe loop in Pacific Northwest National Laboratorys facility that is being modified to accommodate the testing of instruments over a range of simulated waste properties and flow conditions. The testing phases, test matrix and types of simulants needed and the range of testing conditions required to evaluate the instruments are described

Bamberger, Judith A.; Meyer, Perry A.; Scott, Paul A.; Adkins, Harold E.; Wells, Beric E.; Blanchard, Jeremy; Denslow, Kayte M.; Greenwood, Margaret S.; Morgen, Gerald P.; Burns, Carolyn A.; Bontha, Jagannadha R.

2010-01-01T23:59:59.000Z

149

Vadose zone transport field study: Detailed test plan for simulated leak tests  

Science Conference Proceedings (OSTI)

The US Department of Energy (DOE) Groundwater/Vadose Zone Integration Project Science and Technology initiative was created in FY 1999 to reduce the uncertainty associated with vadose zone transport processes beneath waste sites at DOE's Hanford Site near Richland, Washington. This information is needed not only to evaluate the risks from transport, but also to support the adoption of measures for minimizing impacts to the groundwater and surrounding environment. The principal uncertainties in vadose zone transport are the current distribution of source contaminants and the natural heterogeneity of the soil in which the contaminants reside. Oversimplified conceptual models resulting from these uncertainties and limited use of hydrologic characterization and monitoring technologies have hampered the understanding contaminant migration through Hanford's vadose zone. Essential prerequisites for reducing vadose transport uncertainly include the development of accurate conceptual models and the development or adoption of monitoring techniques capable of delineating the current distributions of source contaminants and characterizing natural site heterogeneity. The Vadose Zone Transport Field Study (VZTFS) was conceived as part of the initiative to address the major uncertainties confronting vadose zone fate and transport predictions at the Hanford Site and to overcome the limitations of previous characterization attempts. Pacific Northwest National Laboratory (PNNL) is managing the VZTFS for DOE. The VZTFS will conduct field investigations that will improve the understanding of field-scale transport and lead to the development or identification of efficient and cost-effective characterization methods. Ideally, these methods will capture the extent of contaminant plumes using existing infrastructure (i.e., more than 1,300 steel-cased boreholes). The objectives of the VZTFS are to conduct controlled transport experiments at well-instrumented field sites at Hanford to: identify mechanisms controlling transport processes in soils typical of the hydrogeologic conditions of Hanford's waste disposal sites; reduce uncertainty in conceptual models; develop a detailed and accurate database of hydraulic and transport parameters for validation of three-dimensional numerical models; identify and evaluate advanced, cost-effective characterization methods with the potential to assess changing conditions in the vadose zone, particularly as surrogates of currently undetectable high-risk contaminants. This plan provides details for conducting field tests during FY 2000 to accomplish these objectives. Details of additional testing during FY 2001 and FY 2002 will be developed as part of the work planning process implemented by the Integration Project.

AL Ward; GW Gee

2000-06-23T23:59:59.000Z

150

INEL test plan for evaluating waste assay systems  

SciTech Connect

A test bed is being established at the Idaho National Engineering Laboratory (INEL) Radioactive Waste Management Complex (RWMC). These tests are currently focused on mobile or portable radioassay systems. Prior to disposal of TRU waste at the Waste Isolation Pilot Plant (WIPP), radioassay measurements must meet the quality assurance objectives of the TRU Waste Characterization Quality Assurance Program Plan. This test plan provides technology holders with the opportunity to assess radioassay system performance through a three-tiered test program that consists of: (a) evaluations using non-interfering matrices, (b) surrogate drums with contents that resemble the attributes of INEL-specific waste forms, and (c) real waste tests. Qualified sources containing a known mixture and range of radionuclides will be used for the non-interfering and surrogate waste tests. The results of these tests will provide technology holders with information concerning radioassay system performance and provide the INEL with data useful for making decisions concerning alternative or improved radioassay systems that could support disposal of waste at WIPP.

Mandler, J.W.; Becker, G.K.; Harker, Y.D.; Menkhaus, D.E.; Clements, T.L. Jr.

1996-09-01T23:59:59.000Z

151

Gearbox Reliability Collaborative Phase 3 Gearbox 2 Test Plan  

NLE Websites -- All DOE Office Websites (Extended Search)

Gearbox Reliability Collaborative Gearbox Reliability Collaborative Phase 3 Gearbox 2 Test Plan H. Link, J. Keller, and Y. Guo National Renewable Energy Laboratory B. McNiff McNiff Light Industry Technical Report NREL/TP-5000-58190 April 2013 NREL is a national laboratory of the U.S. Department of Energy, Office of Energy Efficiency & Renewable Energy, operated by the Alliance for Sustainable Energy, LLC. National Renewable Energy Laboratory 15013 Denver West Parkway Golden, Colorado 80401 303-275-3000 * www.nrel.gov Contract No. DE-AC36-08GO28308 Gearbox Reliability Collaborative Phase 3 Gearbox 2 Test Plan H. Link, J. Keller, and Y. Guo National Renewable Energy Laboratory B. McNiff McNiff Light Industry Prepared under Task No. WE11.0301 Technical Report

152

Selenide isotope generator for the Galileo Mission: safety test plan  

DOE Green Energy (OSTI)

The intent of this safety test plan is to outline particular kinds of safety tests designed to produce information which would be useful in the safety analysis process. The program deals primarily with the response of the RTG to accident environments; accordingly two criteria were established: (1) safety tests should be performed for environments which are the most critical in terms of risk contribution; and (2) tests should be formulated to determine failure conditions for critical heat source components rather than observe heat source response in reference accident environments. To satisfy criterion 1. results of a recent safety study were used to rank various accidents in terms of expected source terms. Six kinds of tests were then proposed which would provide information meeting the second criterion.

Not Available

1979-01-31T23:59:59.000Z

153

In situ redox manipulation treatability test -- waste management plan  

DOE Green Energy (OSTI)

This Waste Management Plan provides guidance for the management of waste generated from groundwater well installations in the 100-HR-3 Operable Unit. The well installations are necessary to implement the In Situ Redox Manipulation Treatability Test to determine methods for in situ remedial efforts to prevent discharge of hexavalent chromium at levels above those considered protective of aquatic life in the Columbia River and riverbed sediments

A. J. Knepp

1997-12-31T23:59:59.000Z

154

Test plan : reducing soft costs of rooftop solar installations attributed to structural considerations.  

SciTech Connect

This test plan is a document that provides a systematic approach to the planned testing of rooftop structures to determine their actual load carrying capacity. This document identifies typical tests to be performed, the responsible parties for testing, the general feature of the tests, the testing approach, test deliverables, testing schedule, monitoring requirements, and environmental and safety compliance.

Dwyer, Stephen F.

2013-05-01T23:59:59.000Z

155

Closure Plan for the Area 5 Radioactive Waste Management Site at the Nevada Test Site  

SciTech Connect

The Area 5 Radioactive Waste Management Site (RMWS) at the Nevada Test Site (NTS) is managed and operated by National Security Technologies, LLC (NSTec), for the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office (NNSA/NSO). This document is the first update of the preliminary closure plan for the Area 5 RWMS at the NTS that was presented in the Integrated Closure and Monitoring Plan (DOE, 2005a). The major updates to the plan include a new closure schedule, updated closure inventory, updated site and facility characterization data, the Title II engineering cover design, and the closure process for the 92-Acre Area of the RWMS. The format and content of this site-specific plan follows the Format and Content Guide for U.S. Department of Energy Low-Level Waste Disposal Facility Closure Plans (DOE, 1999a). This interim closure plan meets closure and post-closure monitoring requirements of the order DOE O 435.1, manual DOE M 435.1-1, Title 40 Code of Federal Regulations (CFR) Part 191, 40 CFR 265, Nevada Administrative Code (NAC) 444.743, and Resource Conservation and Recovery Act (RCRA) requirements as incorporated into NAC 444.8632. The Area 5 RWMS accepts primarily packaged low-level waste (LLW), low-level mixed waste (LLMW), and asbestiform low-level waste (ALLW) for disposal in excavated disposal cells.

NSTec Environmental Management

2008-09-01T23:59:59.000Z

156

The Mixed Waste Management Facility. Design basis integrated operations plan (Title I design)  

SciTech Connect

The Mixed Waste Management Facility (MWMF) will be a fully integrated, pilotscale facility for the demonstration of low-level, organic-matrix mixed waste treatment technologies. It will provide the bridge from bench-scale demonstrated technologies to the deployment and operation of full-scale treatment facilities. The MWMF is a key element in reducing the risk in deployment of effective and environmentally acceptable treatment processes for organic mixed-waste streams. The MWMF will provide the engineering test data, formal evaluation, and operating experience that will be required for these demonstration systems to become accepted by EPA and deployable in waste treatment facilities. The deployment will also demonstrate how to approach the permitting process with the regulatory agencies and how to operate and maintain the processes in a safe manner. This document describes, at a high level, how the facility will be designed and operated to achieve this mission. It frequently refers the reader to additional documentation that provides more detail in specific areas. Effective evaluation of a technology consists of a variety of informal and formal demonstrations involving individual technology systems or subsystems, integrated technology system combinations, or complete integrated treatment trains. Informal demonstrations will typically be used to gather general operating information and to establish a basis for development of formal demonstration plans. Formal demonstrations consist of a specific series of tests that are used to rigorously demonstrate the operation or performance of a specific system configuration.

NONE

1994-12-01T23:59:59.000Z

157

A good integrated resource plan: Guidelines for electric utilities and regulators  

SciTech Connect

Integrated resource planning helps utilities and state regulatory commissions consistently assess a broad range of demand and supply resources to meet customer energy-service needs cost-effectively. Key characteristics of this planning approach include: explicit consideration and fair treatment of a wide variety of demand and supply options, consideration of the environmental and other social costs of providing energy services, public participation in the development of the resource plan, and analysis of the uncertainties associated with different external factors and resource options. Integrated resource planning differs from traditional planning in the types and scope of resources considered, the owners of the resources, the organizations involved in resource planning, and the criteria for resource selection. This report presents suggestions to utilities on how to conduct such planning and what to include in their resource-planning reports. These suggestions are based on a review of about 50 resource plans as well as discussions with and presentations to regulators and utilities. The suggestions cover four broad topics; the technical competence with which the plan was developed; the adequacy, detail, and consistency (with the long-term plan) of the short-term action plan; the extent to which the interests of various stakeholders was considered, both in public participation in plan development and in the variety of resource plans developedand assessed; and the clarity and comprehensiveness of the utility`s report on its plan. Technical competence includes energy and demand forecasts, assessment of supply and demand resources, resource integration, and treatment of uncertainty. Issues associated with forecasts include forecasting approaches; links between the forecasts of energy use and peak demands; and links between the forecasts and the effects of past, present, and future demand-side management programs.

Hirst, E.

1992-12-01T23:59:59.000Z

158

A good integrated resource plan: Guidelines for electric utilities and regulators  

SciTech Connect

Integrated resource planning helps utilities and state regulatory commissions consistently assess a broad range of demand and supply resources to meet customer energy-service needs cost-effectively. Key characteristics of this planning approach include: explicit consideration and fair treatment of a wide variety of demand and supply options, consideration of the environmental and other social costs of providing energy services, public participation in the development of the resource plan, and analysis of the uncertainties associated with different external factors and resource options. Integrated resource planning differs from traditional planning in the types and scope of resources considered, the owners of the resources, the organizations involved in resource planning, and the criteria for resource selection. This report presents suggestions to utilities on how to conduct such planning and what to include in their resource-planning reports. These suggestions are based on a review of about 50 resource plans as well as discussions with and presentations to regulators and utilities. The suggestions cover four broad topics; the technical competence with which the plan was developed; the adequacy, detail, and consistency (with the long-term plan) of the short-term action plan; the extent to which the interests of various stakeholders was considered, both in public participation in plan development and in the variety of resource plans developedand assessed; and the clarity and comprehensiveness of the utility's report on its plan. Technical competence includes energy and demand forecasts, assessment of supply and demand resources, resource integration, and treatment of uncertainty. Issues associated with forecasts include forecasting approaches; links between the forecasts of energy use and peak demands; and links between the forecasts and the effects of past, present, and future demand-side management programs.

Hirst, E.

1992-12-01T23:59:59.000Z

159

Experimental Test Plan for Grouting H-3 Calcine  

Science Conference Proceedings (OSTI)

Approximately 4400 cubic meters of solid high-level waste called calcine are stored at the Idaho Nuclear Technology and Engineering Center. Under the Idaho Cleanup Project, dual disposal paths are being investigated. The first path includes calcine retrieval, package "as-is", and ship to the Monitored Geological Repository (MGR). The second path involves treatment of the calcine with such methods as vitrification or grouting. This test plan outlines the hot bench scale tests to grout actual calcine and verify that the waste form properties meet the waste acceptance criteria. This is a necessary sequential step in the process of qualifying a new waste form for repository acceptance. The archive H-3 calcine samples at the Contaminated Equipment Maintenance Building attached to New Waste Calcining Facility will be used in these tests at the Remote Analytical Laboratory. The tests are scheduled for the second quarter of fiscal year 2007.

Alan K. Herbst

2006-01-01T23:59:59.000Z

160

Test plan for demonstration of Rapid Transuranic Monitoring Laboratory  

Science Conference Proceedings (OSTI)

This plan describes tests to demonstrate the capability of the Rapid Transuranic Monitoring Laboratory (RTML) to monitor airborne alpha-emitting radionuclides and analyze soil, smear, and filter samples for alpha- and gamma-emitting radionuclides under field conditions. The RTML will be tested during June 1993 at a site adjacent to the Cold Test Pit at the Radioactive Waste Management Complex at the Idaho National Engineering Laboratory. Measurement systems installed in the RTML that will be demonstrated include two large-area ionization chamber alpha spectrometers, an x-ray/gamma-ray spectrometer, and four alpha continuous air monitors. Test objectives, requirements for data quality, experimental apparatus and procedures, and safety and logistics issues are described.

McIsaac, C.V.; Sill, C.W.; Gehrke, R.J.; Killian, E.W.; Watts, K.D.

1993-06-01T23:59:59.000Z

Note: This page contains sample records for the topic "integrated test plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


161

Acceptance Test Plan for Fourth-Generation Corrosion Monitoring Cabinet  

SciTech Connect

This Acceptance Test Plan (ATP) will document the satisfactory operation of the third-generation corrosion monitoring cabinet (Hiline Engineering Part No.0004-CHM-072-C01). This ATP will be performed by the manufacturer of the cabinet prior to delivery to the site. The objective of this procedure is to demonstrate and document the acceptance of the corrosion monitoring cabinet. The test will consist of a continuity test of the cabinet wiring from the end of cable to be connected to corrosion probe, through the appropriate intrinsic safety barriers and out to the 15 pin D-shell connectors to be connected to the corrosion monitoring instrument. Additional testing will be performed using a constant current and voltage source provided by the corrosion monitoring hardware manufacturer to verify proper operation of corrosion monitoring instrumentation.

NORMAN, E.C.

2000-10-23T23:59:59.000Z

162

Hydrologic test plan for the Environmental Remediation Disposal Facility  

SciTech Connect

Hydrologic tests are planned at seven wells that will be drilled at the proposed Environmental Remediation Disposal Facility (ERDF). These wells are supporting hydrologic, geologic, and hydrochemical characterization at this new facility. Hydrologic testing will consist of instantaneous slug tests, slug interference tests, step-drawdown tests, and constant rate discharge tests (generally single-well). These test results and later groundwater monitoring data will be used to determine groundwater flow directions, flow rates, and the chemical makeup of the groundwater below the proposed ERDF. The seven wells will be drilled in two phases. In Phase I four wells will be drilled and tested: Two to the top of the uppermost aquifer (water table) and two as characterization boreholes to the top of basalt. The Phase I wells are located in the northern portion of the proposed ERDF site (699-32-72, 699-SDF-6, -7 and -8) (Figure 1). If Phase II drilling proceeds, the remaining three wells will be installed and tested (two deep and one shallow). A phased approach to drilling is warranted because of current uncertainty in the land use requirements at the proposed ERDF.

Swanson, L.C.

1993-09-30T23:59:59.000Z

163

Planning for Variable Generation Integration through Balancing Authorities Consolidation  

Science Conference Proceedings (OSTI)

As more and more variable generation is integrated into power grids, many challenges and concerns arise for an individual balancing authority (BA) to balance the system with limited resources. Consolidating balancing authorities provides a promising method to mitigate these problems by enabling the sharing of resources through operating different BAs as a single BA. The diversity in load and renewable generation over a wide area can be effectively leveraged, which makes it possible to achieve significant savings in balancing requirements. This paper develops a detailed procedure to compute savings in load following and regulation service requirements due to BAs consolidation. It proposes several evaluation metrics for demonstrating the benefits of BA consolidation. Several study scenarios are designed for a set of BAs in the western United States to test the proposed procedure. Results have shown significant savings in the capacity, ramp rate, and energy of balancing service requirements. Important factors affecting the savings, such as forecast accuracy and cross correlation between forecast errors, are also discussed.

Diao, Ruisheng; Samaan, Nader A.; Makarov, Yuri V.; Hafen, Ryan P.; Ma, Jian

2012-11-10T23:59:59.000Z

164

OECD 2-D Core Concrete Interaction (CCI) tests : CCI-2 test plan, Rev. 0 January 31, 2004.  

Science Conference Proceedings (OSTI)

The Melt Attack and Coolability Experiments (MACE) program addressed the issue of the ability of water to cool and thermally stabilize a molten core-concrete interaction when the reactants are flooded from above. These tests provided data regarding the nature of corium interactions with concrete, the heat transfer rates from the melt to the overlying water pool, and the role of noncondensable gases in the mixing processes that contribute to melt quenching. As a follow-on program to MACE, The Melt Coolability and Concrete Interaction Experiments (MCCI) project is conducting reactor material experiments and associated analysis to achieve the following objectives: (1) resolve the ex-vessel debris coolability issue through a program that focuses on providing both confirmatory evidence and test data for the coolability mechanisms identified in MACE integral effects tests, and (2) address remaining uncertainties related to long-term two-dimensional molten core-concrete interactions under both wet and dry cavity conditions. Achievement of these two program objectives will demonstrate the efficacy of severe accident management guidelines for existing plants, and provide the technical basis for better containment designs for future plants. In terms of satisfying these objectives, the Management Board (MB) approved the conduct of two long-term 2-D Core-Concrete Interaction (CCI) experiments designed to provide information in several areas, including: (i) lateral vs. axial power split during dry core-concrete interaction, (ii) integral debris coolability data following late phase flooding, and (iii) data regarding the nature and extent of the cooling transient following breach of the crust formed at the melt-water interface. The first of these two tests, CCI-1, was conducted on December 19, 2003. This test investigated the interaction of a fully oxidized 400 kg PWR core melt, initially containing 8 wt % calcined siliceous concrete, with a specially designed two-dimensional siliceous concrete test section with an initial cross-sectional area of 50 cm x 50 cm. The second of these two planned tests, CCI-2, will be conducted with a nearly identical test facility and experiment boundary conditions, but with a Limestone/Common Sand (LCS) concrete test section to investigate the effect of concrete type on the two-dimensional core-concrete interaction and debris cooling behavior. The objective of this report is to provide the overall test plan for CCI-2 to enable pretest calculations to be carried out. The report begins by providing a summary description of the CCI-2 test apparatus, followed by a description of the planned test operating procedure. Overall specifications for CCI-2 are provided in Table 1-1.

Farmer, M. T.; Kilsdonk, D. J.; Lomperski, S.; Aeschlimann, R. W.; Basu, S. (Nuclear Engineering Division)

2011-05-23T23:59:59.000Z

165

Hydrogen Posture Plan: An Integrated Research, Development and...  

NLE Websites -- All DOE Office Websites (Extended Search)

Energy Policy, the Energy Policy Act of 2005, and the U.S. Department of Energy (DOE) Strategic Plan call for expanding the development of diverse domestic energy supplies. In...

166

Fiscal Year 2003 Integrated Monitoring Plan for the Hanford Groundwater Monitoring Project  

SciTech Connect

This document is an integrated monitoring plan for the Groundwater Monitoring Project. It documents well and constituent lists for the monitoring required by the Atomic Energy Act of 1954 and its implementing orders.

Hartman, Mary J.; Dresel, P. EVAN; Lindberg, Jon W.; McDonald, John P.; Newcomer, Darrell R.; Thornton, Edward C.

2002-11-01T23:59:59.000Z

167

Vietnam-Integrated Action Plan to Reduce Vehicle Emissions | Open Energy  

Open Energy Info (EERE)

Vietnam-Integrated Action Plan to Reduce Vehicle Emissions Vietnam-Integrated Action Plan to Reduce Vehicle Emissions Jump to: navigation, search Name Vietnam-Integrated Action Plan to Reduce Vehicle Emissions Agency/Company /Organization Asian Development Bank Focus Area Transportation Topics Implementation, Policies/deployment programs, Background analysis Resource Type Guide/manual Website http://www.adb.org/documents/o Program Start 2002 Country Vietnam UN Region South-Eastern Asia References Vietnam-Integrated Action Plan to Reduce Vehicle Emissions[1] Background "A major goal of this strategy is to reduce mobile sources of air pollution in Viet Nam's largest cities. According to this strategy, industry, business units, management agencies and the transport sector must carefully control pollutant emissions such as carbon monoxide (CO), carbon dioxide

168

Comprehensive integrated planning: A process for the Oak Ridge Reservation, Oak Ridge, Tennessee  

Science Conference Proceedings (OSTI)

The Oak Ridge Comprehensive Integrated Plan is intended to assist the US Department of Energy (DOE) and contractor personnel in implementing a comprehensive integrated planning process consistent with DOE Order 430.1, Life Cycle Asset Management and Oak Ridge Operations Order 430. DOE contractors are charged with developing and producing the Comprehensive Integrated Plan, which serves as a summary document, providing information from other planning efforts regarding vision statements, missions, contextual conditions, resources and facilities, decision processes, and stakeholder involvement. The Comprehensive Integrated Plan is a planning reference that identifies primary issues regarding major changes in land and facility use and serves all programs and functions on-site as well as the Oak Ridge Operations Office and DOE Headquarters. The Oak Ridge Reservation is a valuable national resource and is managed on the basis of the principles of ecosystem management and sustainable development and how mission, economic, ecological, social, and cultural factors are used to guide land- and facility-use decisions. The long-term goals of the comprehensive integrated planning process, in priority order, are to support DOE critical missions and to stimulate the economy while maintaining a quality environment.

NONE

1998-05-01T23:59:59.000Z

169

Integrated Disposal Facility FY2011 Glass Testing Summary Report  

SciTech Connect

Pacific Northwest National Laboratory was contracted by Washington River Protection Solutions, LLC to provide the technical basis for estimating radionuclide release from the engineered portion of the disposal facility (e.g., source term). Vitrifying the low-activity waste at Hanford is expected to generate over 1.6 x 10{sup 5} m{sup 3} of glass (Certa and Wells 2010). The volume of immobilized low-activity waste (ILAW) at Hanford is the largest in the DOE complex and is one of the largest inventories (approximately 8.9 x 10{sup 14} Bq total activity) of long-lived radionuclides, principally {sup 99}Tc (t{sub 1/2} = 2.1 x 10{sup 5}), planned for disposal in a low-level waste (LLW) facility. Before the ILAW can be disposed, DOE must conduct a performance assessment (PA) for the Integrated Disposal Facility (IDF) that describes the long-term impacts of the disposal facility on public health and environmental resources. As part of the ILAW glass testing program PNNL is implementing a strategy, consisting of experimentation and modeling, in order to provide the technical basis for estimating radionuclide release from the glass waste form in support of future IDF PAs. The purpose of this report is to summarize the progress made in fiscal year (FY) 2011 toward implementing the strategy with the goal of developing an understanding of the long-term corrosion behavior of low-activity waste glasses.

Pierce, Eric M.; Bacon, Diana H.; Kerisit, Sebastien N.; Windisch, Charles F.; Cantrell, Kirk J.; Valenta, Michelle M.; Burton, Sarah D.; Westsik, Joseph H.

2011-09-29T23:59:59.000Z

170

FY 2002 Integrated Monitoring Plan for the Hanford Groundwater Monitoring Project  

SciTech Connect

This document is an integrated monitoring plan for the groundwater project and contains: well and constituent lists for monitoring required by the Atomic Energy Act of 1954 and its implementing orders (''surveillance monitoring''); other, established monitoring plans by reference; and a master well/ constituent/frequency matrix for the entire Hanford Site.

Hartman, Mary J; Dresel, P Evan; Lindberg, Jon W; Newcomer, Darrell R; Thornton, Edward C

2001-10-31T23:59:59.000Z

171

FY 2002 Integrated Monitoring Plan for the Hanford Groundwater Monitoring Project  

SciTech Connect

This document is an integrated monitoring plan for the groundwater project and contains: well and constituent lists for monitoring required by the Atomic Energy Act of 1954 and its implementing orders ("surveillance monitoring"); other, established monitoring plans by reference; and a master well/ constituent/frequency matrix for the entire Hanford Site.

Hartman, Mary J.; Dresel, P Evan; Lindberg, Jonathan W.; Newcomer, Darrell R.; Thornton, Edward C.

2001-10-31T23:59:59.000Z

172

TEST PLAN CHARACTERIZATION OF JET FORCES UPON WASTE TANK COMPONENTS  

Science Conference Proceedings (OSTI)

Westinghouse Hanford Company plans to install mixer pumps in double-shell waste tanks to mobilize and suspend settled sludge to allow eventual retrieval for treatment and permanent storage. The mixer pumps produce high momentum, horizontally directed jets that impact and mobilize the sludge and mix it into slurry for removal. There is concern that the force of the jet may damage tank internal components in its path. This test plan describes scaled experiments designed to characterize the velocity profiles of a near floor jet and to quantify the impact farces and drag coefficients of three tank components: radiation dry well, airlift circulator, and steam coil. The experiments will be conducted in water, at approximately 1/6-scale, using one stationary nozzle to simulate the jet. To measure and confirm the velocity profile of the free, submerged jet, the horizontal and vertical velocity profiles will be measured at several distances from the nozzle. The profile will also be measured after the jet impinges upon the tank floor to determine theextent of the change in the profile caused by impingement. The jet forces upon the test articles will be measured at a maximum of four velocities and a variety of test article orientations. Each orientation will represent a unique position of the test article relative to the jet and the tank floor. In addition, the steam coil will be tested in three rotational orientations because it is not symmetric. The highest jet velocity will be selected so that the Reynolds number of the test article in the model will match that of the prototype when operating at design conditions. The forces measured upon the model components will be used to calculate the force on the prototype components using geometric scaling factors. In addition, the model force measurements will be used to calculate the component's drag coefficient as a function of the component Reynolds number.

Bamberger, J. A.

1992-01-01T23:59:59.000Z

173

100 Area excavation treatability test plan. Revision 1  

SciTech Connect

This test plan documents the requirements for a treatability study on field radionuclide analysis and dust control techniques. These systems will be used during remedial actions involving excavation. The data from this treatability study will be used to support the feasibility study (FS) process. Excavation is one of the high-priority, near-term, treatability study needs identified in the program plan (DOE-RL 1992f). Excavation of contaminated soils and buried solid wastes is included in several of the alternatives identified in the 100 Area FS. Although a common activity, excavation has only been used occasionally at the Hanford Site for waste removal applications. The most recent applications are excavation of the 618-9 burial ground and partial remediation of the 316-5 process trenches (DOE-RL 1992a, 1992b). Both projects included excavation of soil and dust control (using water sprays). Excavation is a well-developed technology and equipment is readily available; however, certain aspects of the excavation process require testing before use in full-scale operations. These include the following: Measurement and control of excavation-generated dust and airborne contamination; verification of field analytical system capabilities; demonstration of soil removal techniques specific to the 100 Area waste site types and configurations. The execution of this treatability test may produce up to 500 yd{sub 3} of contaminated soil, which will be used for future treatability tests. These tests may include soil washing with vitrification of the soil washing residuals. Other tests will be conducted if soil washing is not a viable alternative.

Not Available

1993-08-01T23:59:59.000Z

174

The CHPRC Groundwater and Technical Integration Support (Master Project) Quality Assurance Management Plan  

SciTech Connect

The scope of the CH2M Hill Plateau Remediation Company, LLC (CHPRC) Groundwater and Technical Integration Support (Master Project) is for Pacific Northwest National Laboratory staff to provide technical and integration support to CHPRC. This work includes conducting investigations at the 300-FF-5 Operable Unit and other groundwater operable units, and providing strategic integration, technical integration and assessments, remediation decision support, and science and technology. The projects under this Master Project will be defined and included within the Master Project throughout the fiscal year, and will be incorporated into the Master Project Plan. This Quality Assurance Management Plan provides the quality assurance requirements and processes that will be followed by the CHPRC Groundwater and Technical Integration Support (Master Project) and all releases associated with the CHPRC Soil and Groundwater Remediation Project. The plan is designed to be used exclusively by project staff.

Fix, N. J.

2009-04-03T23:59:59.000Z

175

TRUPACT-II Hydrogen G-Valve Program Test Plan  

DOE Green Energy (OSTI)

This test plan describes the objectives, scope, participants, and components of the Transuranic Package Transporter-II (TRUPACT-II) Hydrogen G-Value Program (GH2P). The GH2P builds on the experience, results, and experimental setup of the TRUPACT-II Matrix Depletion Program (MDP) to establish effective hydrogen G-values (G-values) for additional waste matrices. This plan details the experimental design and test matrices for experiments to measure the G-value for additional waste matrices, including first- and second-stage sludges at the Idaho National Engineering and Environmental Laboratory, and molten salt extraction residues with varying amounts of residual moisture (i.e., unbound water). Data collected from the GH2P will be used to support an application to the US Nuclear Regulatory Commission for G-values and corresponding wattage limits for the TRUPACT-II payloads containing these waste matrices. The testing will also evaluate the ability to determine G-values on a waste stream basis.

Mroz, Eugene J.

1999-01-01T23:59:59.000Z

176

Updated FY12 Ceramic Fuels Irradiation Test Plan  

SciTech Connect

The Fuel Cycle Research and Development program is currently devoting resources to study of numerous fuel types with the aim of furthering understanding applicable to a range of reactors and fuel cycles. In FY11, effort within the ceramic fuels campaign focused on planning and preparation for a series of rabbit irradiations to be conducted at the High Flux Isotope Reactor located at Oak Ridge National Laboratory. The emphasis of these planned tests was to study the evolution of thermal conductivity in uranium dioxide and derivative compositions as a function of damage induced by neutron damage. Current fiscal realities have resulted in a scenario where completion of the planned rabbit irradiations is unlikely. Possibilities for execution of irradiation testing within the ceramic fuels campaign in the next several years will thus likely be restricted to avenues where strong synergies exist both within and outside the Fuel Cycle Research and Development program. Opportunities to augment the interests and needs of modeling, advanced characterization, and other campaigns present the most likely avenues for further work. These possibilities will be pursued with the hope of securing future funding. Utilization of synthetic microstructures prepared to better understand the most relevant actors encountered during irradiation of ceramic fuels thus represents the ceramic fuel campaign's most efficient means to enhance understanding of fuel response to burnup. This approach offers many of the favorable attributes embraced by the Separate Effects Testing paradigm, namely production of samples suitable to study specific, isolated phenomena. The recent success of xenon-imbedded thick films is representative of this approach. In the coming years, this strategy will be expanded to address a wider range of problems in conjunction with use of national user facilities novel characterization techniques to best utilize programmatic resources to support a science-based research program.

Nelson, Andrew T. [Los Alamos National Laboratory

2012-05-24T23:59:59.000Z

177

Flow reference method testing and analysis: Field test plan, Texas Utilities Decordova Steam Electric Station  

SciTech Connect

This report describes the experimental design and test plan for the first of three field tests that the US Environmental Protection Agency (EPA) conducted in 1997 as part of a major study to evaluate potential improvements to Method 2, EPA`s test method for measuring flue gas volumetric flow in stacks. The experimental design involved four test teams taking concurrent in-stack measurements with velocity sensing probes. Seven types of probes were included in the study. Three test matrices were used to gather data for inter-probe and inter-team comparisons and to assess the impact of velocity decline near the stack wall on volumetric flow measurements.

Lieberman, E.; Werner, A.S.

1997-05-30T23:59:59.000Z

178

DOE/OE National SCADA Test Bed Fiscal Year 2009 Work Plan | Department...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

OE National SCADA Test Bed Fiscal Year 2009 Work Plan DOEOE National SCADA Test Bed Fiscal Year 2009 Work Plan This document is designed to help guide and strengthen the DOEOE...

179

Integrated resource planning Electric and gas utilities in the USA  

E-Print Network (OSTI)

acquisitions will be the important criteria. Resource planning at gas utilities IRP is just beginning to be applied to the natural gas industry. At gas utilities, called local distribution companies (LDCs and regulated differently. Natural gas is produced, transported, and distributed by three different sets

180

Integrated Environment and Safety and Health Management System (ISMS) Implementation Project Plan  

SciTech Connect

The Integrated Environment, Safety and Health Management System (ISMS) Implementation Project Plan serves as the project document to guide the Fluor Hanford, Inc (FHI) and Major Subcontractor (MSC) participants through the steps necessary to complete the integration of environment, safety, and health into management and work practices at all levels.

MITCHELL, R.L.

2000-01-10T23:59:59.000Z

Note: This page contains sample records for the topic "integrated test plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


181

Leveraging enterprise architecture to enable integrated test and evaluation sustainability  

E-Print Network (OSTI)

An analysis was performed to investigate how enterprise architecting methods can be applied to an integrate test and evaluation enterprise and make it a more sustainable enterprise to provide continuous value in the face ...

Sheets, Arlan C. (Arlan Christopher)

2011-01-01T23:59:59.000Z

182

OTEC-1 Power System Test Program: test plan for first deployment  

DOE Green Energy (OSTI)

This report describes in detail all tests planned for the first eight-month deployment of OTEC-1, a test facility constructed by the US Department of Energy in order to test heat exchangers for closed-cycle power plants using ocean thermal energy. Tests to be performed during the first-deployment period are aimed primarily at determining (1) the effectiveness of countermeasures in preventing biofouling of the heat exchanters, (2) the extent of environmental impacts associated with operation of an OTEC facility, and (3) the performance of a 1-MWe, titanium shell-and-tube evaporator and condenser pair. The condenser to be tested has plain tubes, and the evaporator employs the Linde High Flux surface on the working-fluid (ammonia) side to enhance the heat-transfer rate. This plan provides a statement of the objectives and priorities of the test program, describes the test equipment, gives a detailed account of all tests to be performed and the test schedule, and discusses provisions for management of the test program.

None

1980-03-01T23:59:59.000Z

183

Advanced Planning Method for Integrating Large-Scale Variable Generation  

Science Conference Proceedings (OSTI)

As the penetration and size of renewable generation resources increase, the industry must expand transmission infrastructure to accommodate increasing renewable resource output. Conventional transmission expansion planning requires sufficient transmission capacities to transfer the full name plate capacity of all power plants to load centers at the same time. However, renewable resources, such as wind and solar, have highly variable output and are spatially diversified. Thus, transmission expansion plann...

2009-12-22T23:59:59.000Z

184

Planning for People: Integrating Social Issues and Processes into Planning Practice  

E-Print Network (OSTI)

CASE 2 Cumulative Social Impact of the Athabasca Oil Sandsmanagement of the social impacts of oil sands development onresulted in a host of social impacts, re- quiring a planning

Hoernig, Heidi; Leahy, Danielle; Zhuang, Zhi Xi; Early, Robert; Randall, Lynn; Whitelaw, Graham

2005-01-01T23:59:59.000Z

185

DOE National SCADA Test Bed Program Multi-Year Plan | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

National SCADA Test Bed Program Multi-Year Plan National SCADA Test Bed Program Multi-Year Plan DOE National SCADA Test Bed Program Multi-Year Plan This document presents the National SCADA Test Bed Program Multi-Year Plan, a coherent strategy for improving the cyber security of control systems in the energy sector. The NSTB Program is conducted within DOE's Office of Electricity Delivery and Energy Reliability (OE), which leads national efforts to modernize the electric grid, enhance the security and reliability of the energy infrastructure, and facilitate recovery from disruptions to the energy supply. The Plan covers the planning period of fiscal year 2008 to 2013. DOE National SCADA Test Bed Program Multi-Year Plan More Documents & Publications DOE/OE National SCADA Test Bed Fiscal Year 2009 Work Plan

186

Achieving New Source Performance Standards (NSPS) Through Integration of Low-NOx Burners with an Optimization Plan for Boiler Combustion  

NLE Websites -- All DOE Office Websites (Extended Search)

Improvement Improvement Initiative (PPII) CONTACTS Brad Tomer Director Office of Major Demonstrations National Energy Technology Laboratory 3610 Collins Ferry Road P.O. Box 880 Morgantown, WV 26507-0880 304-285-4692 brad.tomer@netl.doe.gov PARTNER Sunflower Electric Power Corporation Garden City, KS Sunflower's 360 MWe Wall-fired Holcomb Station Achieving new Source PerformAnce StAndArdS (nSPS) through integrAtion of Low-no X BurnerS with An oPtimizAtion PLAn for BoiLer comBuStion (comPLeted) A unique combination of high-tech combustion modifications and sophisticated control systems was planned to be tested on a coal-fired boiler at Sunflower Electric's Holcomb Power Station in Finney County, Kansas, to demonstrate how new technology can reduce air emissions and save costs for ratepayers. However, due to larger than anticipated costs

187

US Department of Energy Integrated Resource Planning Program: Accomplishments and opportunities  

SciTech Connect

The US Department of Energy Integrated Resource Planning Program supports many activities and projects that enhance the process by which utilities assess demand and supply options and, subsequently, evaluate and select resources. The US Department of Energy program coordinates integrated resource planning in risk and regulatory analysis; utility and regional planning; evaluation and verification; information transfer/technological assistance; and demand-side management. Professional staff from the National Renewable Energy Laboratory, Oak Ridge National Laboratory, Lawrence Berkeley Laboratory, and Pacific Northwest Laboratories collaborate with peers and stakeholders, in particular, the National Association of Regulatory Utility Commissioners, and conduct research and activities for the US Department of Energy. Twelve integrated resource planning activities and projects are summarized in this report. The summaries reflect the diversity of planning and research activities supported by the Department. The summaries also reflect the high levels of collaboration and teaming that are required by the Program and practiced by the researchers. It is concluded that the Program is achieving its objectives by encouraging innovation and improving planning and decision making. Furthermore, as the Department continues to implement planned improvements in the Program, the Department is effectively positioned to attain its ambitious goals.

White, D.L. [Oak Ridge National Lab., TN (United States); Mihlmester, P.E. [Aspen Systems Corp., Oak Ridge, TN (United States)

1993-12-17T23:59:59.000Z

188

WORLD TRADE CENTER INDOOR DUST TEST AND CLEAN PROGRAM PLAN  

E-Print Network (OSTI)

Background: This Test and Clean Program plan is the result of ongoing efforts to monitor the current environmental conditions for residents and workers impacted by the collapse of the World Trade Center (WTC) towers. In March 2004, EPA convened an expert technical review panel to provide individual guidance and assistance to the Agency in its use of available exposure and health surveillance databases and registries to characterize any remaining exposures and risks, identify unmet public health needs, and to individually recommend steps to further minimize the risks associated with the aftermath of the WTC attack. The WTC Expert Technical Review Panel (WTC Panel) members met periodically in open meetings to interact with EPA and the public about plans to monitor for the presence of WTC dust in indoor environments and to individually suggest additional measures that could be undertaken by EPA and others to evaluate the dispersion of the plume and the geographic extent of environmental impact from the collapse of the WTC towers. The WTC Panel members were charged, in part, with reviewing data from post-cleaning verification sampling to be done by EPA in the residential areas included in EPA Region 2's 2002-3 Indoor Air Residential Assistance Program to verify that recontamination has not

unknown authors

2005-01-01T23:59:59.000Z

189

LOWER MANHATTAN INDOOR DUST TEST AND CLEAN PROGRAM PLAN  

E-Print Network (OSTI)

Background: This Test and Clean Program plan is the result of ongoing efforts to respond to concerns of residents and workers impacted by the collapse of the World Trade Center (WTC) towers. In March 2004, EPA convened an expert technical review panel to provide individual guidance and assistance to the Agency in its use of available exposure and health surveillance databases and registries to characterize any remaining exposures and risks, identify unmet public health needs, and individually recommend steps to further minimize the risks associated with the aftermath of the WTC attack. The WTC Expert Technical Review Panel (WTC Panel) members met periodically in open meetings to interact with EPA and the public about plans to monitor for the presence of WTC dust in indoor environments and to individually suggest additional measures that could be undertaken by EPA and others to evaluate the dispersion of the plume and the geographic extent of environmental impact from the collapse of the WTC towers. The WTC Panel members were charged, in part, with reviewing data from post-cleaning verification sampling to be done by EPA in the residential areas included in EPA Region 2's 2002-2003 Indoor Air Residential Assistance Program to verify that recontamination has not

unknown authors

2006-01-01T23:59:59.000Z

190

Beam Physics of Integrable Optics Test Accelerator at Fermilab  

SciTech Connect

Fermilab's Integrable Optics Test Accelerator (IOTA) is an electron storage ring designed for testing advanced accelerator physics concepts, including implementation of nonlinear integrable beam optics and experiments on optical stochastic cooling. The machine is currently under construction at the Advanced Superconducting Test Accelerator facility. In this report we present the goals and the current status of the project, and describe the details of machine design. In particular, we concentrate on numerical simulations setting the requirements on the design and supporting the choice of machine parameters.

Nagaitsev, S.; Valishev, A.; /Fermilab; Danilov, V.V.; /Oak Ridge; Shatilov, D.N.; /Novosibirsk, IYF

2012-05-01T23:59:59.000Z

191

Resource Planning Model: An Integrated Resource Planning and Dispatch Tool for Regional Electric Systems  

Science Conference Proceedings (OSTI)

This report introduces a new capacity expansion model, the Resource Planning Model (RPM), with high spatial and temporal resolution that can be used for mid- and long-term scenario planning of regional power systems. Although RPM can be adapted to any geographic region, the report describes an initial version of the model adapted for the power system in Colorado. It presents examples of scenario results from the first version of the model, including an example of a 30%-by-2020 renewable electricity penetration scenario.

Mai, T.; Drury, E.; Eurek, K.; Bodington, N.; Lopez, A.; Perry, A.

2013-01-01T23:59:59.000Z

192

We have developed an integrated plan to guide implementation  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Budget Overview Budget Overview 14 February, 2011 1 Winning the Future "We know what it takes to compete for the jobs and industries of our time. "We need to out-innovate, out-educate, and out-build the rest of the world. We have to make America the best place on Earth to do business. We need to take responsibility for our deficit and reform our government. "That's how our people will prosper. That's how we'll win the future." -- President Obama, 2011 State of the Union 2 Supporting the President's Plan to Win the Future 3 "Some of the most promising innovation is happening in the area of clean energy technology -- technology that is creating jobs, reducing

193

Valuation of Renewable and Distributed Resources: Implications for the Integrated Resource Planning  

Science Conference Proceedings (OSTI)

Over the last two decades, traditional integrated resource planning (IRP) has proven to be a valuable tool for evaluating the tradeoffs between supply-side generation and demand-side efficiency resources. However, there has been increasing focus on the incorporation of renewable, distributed, and demand-side resources into utility planning, which requires new methodologies to assess the value of these resources. Traditional IRP is generation-centric and typically fails to take into account the operationa...

2007-06-18T23:59:59.000Z

194

The integrated tank waste management plan at Oak Ridge National Laboratory  

SciTech Connect

DOE`s Environmental Management Program at Oak Ridge has developed an integrated tank waste management plan that combines the accelerated deployment of innovative technologies with an aggressive waste transfer schedule. Oak Ridge is cleaning out waste from aging underground storage tanks in preparation of waste processing, packaging and final safe disposal. During remediation this plan will reduce the risk of environmental, worker, and civilian exposure, save millions of dollars, and cut years off of tank remediation schedules at Oak Ridge.

Billingsley, K. [STEP, Inc., Oak Ridge, TN (United States); Mims, C. [Dept. of Energy, Oak Ridge, TN (United States). Oak Ridge Operations Office; Robinson, S. [Oak Ridge National Lab., TN (United States)

1998-06-01T23:59:59.000Z

195

Test plan/procedure for the SPM-1 shipping container system. Revision 0  

SciTech Connect

The 49 CFR 173.465 Type A packaging tests will verify that SPM-1 will provide adequate protection and pass as a Type A package. Test will determine that the handle of the Pig will not penetrate through the plywood spacer and rupture the shipping container. Test plan/procedure provides planning, pre-test, setup, testing, and post-testing guidelines and procedures for conducting the {open_quotes}Free Drop Test{close_quotes} procedure for the SPM-1 package.

Flanagan, B.D.

1995-07-01T23:59:59.000Z

196

Develop Standard Method of Test for Integrated Heat Pump  

NLE Websites -- All DOE Office Websites (Extended Search)

Integrated Integrated Heat Pump (IHP) Wayne Reedy Oak Ridge National Laboratory wreedy2@comcast.net 574-583-5487 April 2, 2013 Develop Standard Method of Test (MOT) for IHP 2 | Building Technologies Office eere.energy.gov Purpose & Objectives Problem Statement: * IHP → ≥50% savings in energy used for space conditioning and water heating - C. K. Rice, V. D. Baxter, S. A. Hern, T. P. McDowell, J. D. Munk, and B. Shen, 2013. "Development of a Residential Ground- Source Integrated Heat Pump", 2013 ASHRAE Winter Conference Paper, Dallas, TX., January. * No generally accepted MOT or rating standard exists

197

Develop Standard Method of Test for Integrated Heat Pump  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Integrated Integrated Heat Pump (IHP) Wayne Reedy Oak Ridge National Laboratory wreedy2@comcast.net 574-583-5487 April 2, 2013 Develop Standard Method of Test (MOT) for IHP 2 | Building Technologies Office eere.energy.gov Purpose & Objectives Problem Statement: * IHP → ≥50% savings in energy used for space conditioning and water heating - C. K. Rice, V. D. Baxter, S. A. Hern, T. P. McDowell, J. D. Munk, and B. Shen, 2013. "Development of a Residential Ground- Source Integrated Heat Pump", 2013 ASHRAE Winter Conference Paper, Dallas, TX., January. * No generally accepted MOT or rating standard exists

198

Integrated Disposal Facility FY2010 Glass Testing Summary Report  

SciTech Connect

Pacific Northwest National Laboratory was contracted by Washington River Protection Solutions, LLC to provide the technical basis for estimating radionuclide release from the engineered portion of the disposal facility (e.g., source term). Vitrifying the low-activity waste at Hanford is expected to generate over 1.6 105 m3 of glass (Puigh 1999). The volume of immobilized low-activity waste (ILAW) at Hanford is the largest in the DOE complex and is one of the largest inventories (approximately 0.89 1018 Bq total activity) of long-lived radionuclides, principally 99Tc (t1/2 = 2.1 105), planned for disposal in a low-level waste (LLW) facility. Before the ILAW can be disposed, DOE must conduct a performance assessement (PA) for the Integrated Disposal Facility (IDF) that describes the long-term impacts of the disposal facility on public health and environmental resources. As part of the ILAW glass testing program PNNL is implementing a strategy, consisting of experimentation and modeling, in order to provide the technical basis for estimating radionuclide release from the glass waste form in support of future IDF PAs. The purpose of this report is to summarize the progress made in fiscal year (FY) 2010 toward implementing the strategy with the goal of developing an understanding of the long-term corrosion behavior of low-activity waste glasses. The emphasis in FY2010 was the completing an evaluation of the most sensitive kinetic rate law parameters used to predict glass weathering, documented in Bacon and Pierce (2010), and transitioning from the use of the Subsurface Transport Over Reactive Multi-phases to Subsurface Transport Over Multiple Phases computer code for near-field calculations. The FY2010 activities also consisted of developing a Monte Carlo and Geochemical Modeling framework that links glass composition to alteration phase formation by 1) determining the structure of unreacted and reacted glasses for use as input information into Monte Carlo calculations, 2) compiling the solution data and alteration phases identified from accelerated weathering tests conducted with ILAW glass by PNNL and Viteous State Laboratory/Catholic University of America as well as other literature sources for use in geochemical modeling calculations, and 3) conducting several initial calculations on glasses that contain the four major components of ILAW-Al2O3, B2O3, Na2O, and SiO2.

Pierce, Eric M.; Bacon, Diana H.; Kerisit, Sebastien N.; Windisch, Charles F.; Cantrell, Kirk J.; Valenta, Michelle M.; Burton, Sarah D.; Serne, R Jeffrey; Mattigod, Shas V.

2010-09-30T23:59:59.000Z

199

Light Water Reactor Sustainability Program Integrated Program Plan  

SciTech Connect

Nuclear power has safely, reliably, and economically contributed almost 20% of electrical generation in the United States over the past two decades. It remains the single largest contributor (more than 70%) of non-greenhouse-gas-emitting electric power generation in the United States. Domestic demand for electrical energy is expected to experience a 31% growth from 2009 to 2035. At the same time, most of the currently operating nuclear power plants will begin reaching the end of their initial 20-year extension to their original 40-year operating license for a total of 60 years of operation. Figure E-1 shows projected nuclear energy contribution to the domestic generating capacity. If current operating nuclear power plants do not operate beyond 60 years, the total fraction of generated electrical energy from nuclear power will begin to declineeven with the expected addition of new nuclear generating capacity. The oldest commercial plants in the United States reached their 40th anniversary in 2009. The U.S. Department of Energy Office of Nuclear Energys Research and Development Roadmap (Nuclear Energy Roadmap) organizes its activities around four objectives that ensure nuclear energy remains a compelling and viable energy option for the United States. The four objectives are as follows: (1) develop technologies and other solutions that can improve the reliability, sustain the safety, and extend the life of the current reactors; (2) develop improvements in the affordability of new reactors to enable nuclear energy to help meet the Administrations energy security and climate change goals; (3) develop sustainable nuclear fuel cycles; and (4) understand and minimize the risks of nuclear proliferation and terrorism. The Light Water Reactor Sustainability (LWRS) Program is the primary programmatic activity that addresses Objective 1. This document summarizes the LWRS Programs plans.

Kathryn McCarthy; Jeremy Busby; Bruce Hallbert; Shannon Bragg-Sitton; Curtis Smith; Cathy Barnard

2013-04-01T23:59:59.000Z

200

Light Water Reactor Sustainability Program Integrated Program Plan  

Science Conference Proceedings (OSTI)

Nuclear power has safely, reliably, and economically contributed almost 20% of electrical generation in the United States over the past two decades. It remains the single largest contributor (more than 70%) of non-greenhouse-gas-emitting electric power generation in the United States. Domestic demand for electrical energy is expected to experience a 31% growth from 2009 to 2035. At the same time, most of the currently operating nuclear power plants will begin reaching the end of their initial 20-year extension to their original 40-year operating license for a total of 60 years of operation. Figure E-1 shows projected nuclear energy contribution to the domestic generating capacity. If current operating nuclear power plants do not operate beyond 60 years, the total fraction of generated electrical energy from nuclear power will begin to decline - even with the expected addition of new nuclear generating capacity. The oldest commercial plants in the United States reached their 40th anniversary in 2009. The U.S. Department of Energy Office of Nuclear Energy's Research and Development Roadmap (Nuclear Energy Roadmap) organizes its activities around four objectives that ensure nuclear energy remains a compelling and viable energy option for the United States. The four objectives are as follows: (1) develop technologies and other solutions that can improve the reliability, sustain the safety, and extend the life of the current reactors; (2) develop improvements in the affordability of new reactors to enable nuclear energy to help meet the Administration's energy security and climate change goals; (3) develop sustainable nuclear fuel cycles; and (4) understand and minimize the risks of nuclear proliferation and terrorism. The Light Water Reactor Sustainability (LWRS) Program is the primary programmatic activity that addresses Objective 1. This document summarizes the LWRS Program's plans.

George Griffith; Robert Youngblood; Jeremy Busby; Bruce Hallbert; Cathy Barnard; Kathryn McCarthy

2012-01-01T23:59:59.000Z

Note: This page contains sample records for the topic "integrated test plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


201

Integrating Energy Planning and Techno-Economic Development: A Solid Basis for the . . .  

E-Print Network (OSTI)

This paper started by explaining the major issues of energy system in developing countries and their constraints for energy planning and policy making. It then proceeded to introduce a comprehensive approach for integrating energy planning and techno-economic development which can provide a solid context for to energy technology transfer to under-developed countries. 16 Through the analysis was made in this paper it was highlighted that energy system development should consider four major components: energy policy, energy planning, energy pricing and energy technology. They are interrelated to facilitate energy system development depending upon the integration of energy management and development perspective. It also became clear that individual energy demand (or energy supply) planning in these countries, is not effective while an interrelated planning based on energy demand, energy supply and substitutability of energy seems to be more accurate. This view within an integrated energy planning and technoeconomic development approach will address an appropriate context in which energy technology transfer can be effectively analysed. In this context, the assessment of energy technology depending on country's technological capability and local dominant, qualitative, and quantitative factors can broadly implement. The paper described how we can integrate these different variables (qualitative, quantitative, and knowledge-based) through the Analytic Hierarchy Process with respect to energy policy and energy technology factors in the Third World. The Analytic Hierarchy Process as an appropriate technique can be applied to define the energy planning objectives and also to assess candidate energy technology(ies). As it was pointed out, through a proposed nine-step framework, ...

Goel Kahen

1995-01-01T23:59:59.000Z

202

MWTF jumper connector integral seal block development and leak testing  

SciTech Connect

In fiscal year 1993, tests of an o-ring/tetraseal retainer designed to replace a gasket-type seal used in PUREX-type process jumper connectors encouraged the design of an improved seal block. This new seal block combines several parts into one unitized component called an integral seal block. This report summarizes development and leak testing of the new integral seal block. The integral seal block uses a standard o-ring nested in a groove to accomplish leak tightness. This seal block eliminates the need to machine acme threads into the lower skirt casting and seal retainers, eliminates tolerance stack-up, reduces parts inventory, and eliminates an unnecessary leak path in the jumper connector assembly. This report also includes test data on various types of o-ring materials subjected to heat and pressure. Materials tested included Viton, Kalrez, and fluorosilicone, with some incidental data on teflon coated silicone o-rings. Test experience clearly demonstrates the need to test each seal material for temperature and pressure in its intended application. Some materials advertised as being {open_quotes}better{close_quotes} at higher temperatures did not perform up to expectations. Inspection of the fluorosilicone and Kalrez seals after thermal testing indicates that they are much more susceptible to heat softening than Viton.

Ruff, E.S.; Jordan, S.R.

1995-01-01T23:59:59.000Z

203

Risk Impact Assessment of Extended Integrated Leak Rate Testing Intervals  

Science Conference Proceedings (OSTI)

This report presents a risk impact assessment for extending integrated leak rate test (ILRT) surveillance intervals to 15 years. The assessment demonstrates that on an industry-wide basis there is small risk associated with the extension, provided that the performance bases and defense-in-depth are maintained. There is an obvious benefit in not performing costly, critical-path, time-consuming tests that provide a limited benefit from a risk perspective.

2008-10-31T23:59:59.000Z

204

Testing for market integration crude oil, coal, and natural gas  

SciTech Connect

Prompted by the contemporaneous spike in coal, oil, and natural gas prices, this paper evaluates the degree of market integration both within and between crude oil, coal, and natural gas markets. Our approach yields parameters that can be readily tested against a priori conjectures. Using daily price data for five very different crude oils, we conclude that the world oil market is a single, highly integrated economic market. On the other hand, coal prices at five trading locations across the United States are cointegrated, but the degree of market integration is much weaker, particularly between Western and Eastern coals. Finally, we show that crude oil, coal, and natural gas markets are only very weakly integrated. Our results indicate that there is not a primary energy market. Despite current price peaks, it is not useful to think of a primary energy market, except in a very long run context.

Bachmeier, L.J.; Griffin, J.M. [Texas A& amp; M Univ, College Station, TX (United States)

2006-07-01T23:59:59.000Z

205

Generating custom test plans for CASE{sup *}Dictionary 5.0  

Science Conference Proceedings (OSTI)

Most database development organizations use a formal software development methodology that requires a certain amount of formal testing. The amount of formal testing that will be performed will vary from methodology to methodology and from site to site. If a very detailed formal test plan is required for each module in a system, the work involved to produce the test plan can be tedious and costly. After a system has been designed and developed using Oracle*CASE, there is much useful information in the CASE*Dictionary repository. If this information could be tied to specific test requirements, a test plan could be generated automatically, saving much time and resources. This paper shows how CASE*Dictionary can be used to store test plan information that can then be used to generate a specific test plan for each module based on it`s detailed data usage.

Atkins, K.D. [Boeing Computer Services, Richland, WA (United States)

1994-04-01T23:59:59.000Z

206

Integration plan required by performance agreement SM 7.2.1  

SciTech Connect

Fluor Daniel Hanford, Inc. and its major subcontractors are in agreement that environmental monitoring performed under the Project Hanford Management Contract is to be done in accordance with a single, integrated program. The purpose of this Integration Plan for Environmental Monitoring is to document the policies, systems, and processes being put in place to meet one key objective: manage and integrate a technically competent, multi-media ambient environmental monitoring program, in an efficient, cost effective manner. Fluor Daniel Hanford, Inc. and its major subcontractors also commit to conducting business in a manner consistent with the International Standards Organization 14000 Environmental Management System concepts. Because the integration of sitewide groundwater monitoring activities is managed by the Environmental Restoration Contractor, groundwater monitoring it is outside the scope of this document. Therefore, for the purpose of this Integration Plan for Environmental Monitoring, the Integrated Environmental Monitoring Program is defined as applicable to all environmental media except groundwater. This document provides recommendations on future activities to better integrate the overall environmental monitoring program, with emphasis on the near-field program. In addition, included is the Fluor Daniel Hanford, Inc. team review of the environmental monitoring activities on the Hanford Site, with concurrence of Pacific Northwest National Laboratory and Bechtel Hanford, Inc. (The narrative provided later in the Discussion Section describes the review and consideration given to each topic.) This document was developed to meet the requirements of the Project Hanford Management Contract performance agreement (SM7.2) and the tenets of the U.S. Department of Energy's Effluent and Environmental Monitoring Planning Process. This Plan is prepared for the U.S. Department of Energy, Richland Operations Office, Environmental Assurance, Permits, and Policy Division to complete the requirements specified in the Performance Expectation 7.2.1, within the SM7 Environmental, Safety, and Health section of the Project Hanford Management Contract.

Diediker, L.P.

1997-03-28T23:59:59.000Z

207

A long-term investment planning model for mixed energy infrastructure integrated with renewable  

E-Print Network (OSTI)

A long-term investment planning model for mixed energy infrastructure integrated with renewable- mental friendly. Compared with fossil energy, it is expensive to transport renewable energy for a long distance. Another problem of renewable energy is fluctuation and it is not so stable as fossil energy

208

Integrated Google Maps and Smooth Street View Videos for Route Planning National Taiwan University  

E-Print Network (OSTI)

Integrated Google Maps and Smooth Street View Videos for Route Planning Chi Peng National Taiwan that takes start and end points as the input, and will automatically connect to the Google Maps with Street a smooth scenic video from the starting point to the destination, which combines the Google Maps to provide

Ouhyoung, Ming

209

ART CCIM Phase II-A Off-Gas System Evaluation Test Plan  

Science Conference Proceedings (OSTI)

This test plan defines testing to be performed using the Idaho National Laboratory (INL) engineering-scale cold crucible induction melter (CCIM) test system for Phase II-A of the Advanced Remediation Technologies (ART) CCIM Project. The multi-phase ART-CCIM Project is developing a conceptual design for replacing the joule-heated melter (JHM) used to treat high level waste (HLW) in the Defense Waste Processing Facility (DWPF) at the Savannah River Site (SRS) with a cold crucible induction melter. The INL CCIM test system includes all feed, melter off-gas control, and process control subsystems needed for fully integrated operation and testing. Testing will include operation of the melter system while feeding a non-radioactive slurry mixture prepared to simulate the same type of waste feed presently being processed in the DWPF. Process monitoring and sample collection and analysis will be used to characterize the off-gas composition and properties, and to show the fate of feed constituents, to provide data that shows how the CCIM retrofit conceptual design can operate with the existing DWPF off-gas control system.

Nick Soelberg; Jay Roach

2009-01-01T23:59:59.000Z

210

Mound Isotope Power Systems; AMTEC Integral Cell Wall Compression Test  

DOE Green Energy (OSTI)

An AMTEC (Alkali Metal Thermal-to-Electric Conversion) device is tested under a compression load at a rate of 0.0025 inches/minute. The integral cell wall is made of Haynes Alloy 25. The wall buckled at 724 pounds load.

None

1997-11-05T23:59:59.000Z

211

Integrated Assessment Plan Template and Operational Demonstration for SPIDERS Phase 2: Fort Carson  

Science Conference Proceedings (OSTI)

This document contains the Integrated Assessment Plan (IAP) for the Phase 2 Operational Demonstration (OD) of the Smart Power Infrastructure Demonstration for Energy Reliability (SPIDERS) Joint Capability Technology Demonstration (JCTD) project. SPIDERS will be conducted over a three year period with Phase 2 being conducted at Fort Carson, Colorado. This document includes the Operational Demonstration Execution Plan (ODEP) and the Operational Assessment Execution Plan (OAEP), as approved by the Operational Manager (OM) and the Integrated Management Team (IMT). The ODEP describes the process by which the OD is conducted and the OAEP describes the process by which the data collected from the OD is processed. The execution of the OD, in accordance with the ODEP and the subsequent execution of the OAEP, will generate the necessary data for the Quick Look Report (QLR) and the Utility Assessment Report (UAR). These reports will assess the ability of the SPIDERS JCTD to meet the four critical requirements listed in the Implementation Directive (ID).

Barr, Jonathan L.; Tuffner, Francis K.; Hadley, Mark D.; Kreyling, Sean J.; Schneider, Kevin P.

2013-09-01T23:59:59.000Z

212

Simplifying documentation while approaching site closure: integrated health & safety plans as documented safety analysis  

Science Conference Proceedings (OSTI)

At the Fernald Closure Project (FCP) near Cincinnati, Ohio, environmental restoration activities are supported by Documented Safety Analyses (DSAs) that combine the required project-specific Health and Safety Plans, Safety Basis Requirements (SBRs), and Process Requirements (PRs) into single Integrated Health and Safety Plans (I-HASPs). By isolating any remediation activities that deal with Enriched Restricted Materials, the SBRs and PRs assure that the hazard categories of former nuclear facilities undergoing remediation remain less than Nuclear. These integrated DSAs employ Integrated Safety Management methodology in support of simplified restoration and remediation activities that, so far, have resulted in the decontamination and demolition (D&D) of over 150 structures, including six major nuclear production plants. This paper presents the FCP method for maintaining safety basis documentation, using the D&D I-HASP as an example.

Brown, Tulanda

2003-06-01T23:59:59.000Z

213

Glovebox characterization and barrier integrity testing using fluorescent powder  

SciTech Connect

This paper presents a method for characterizing the spread of contamination and testing the barrier integrity of a new glovebox during material transfer operations and glove change-outs using fluorescent powder. Argonne National Laboratory-West has performed this test on several new gloveboxes prior to putting them into service. The test is performed after the glovebox has been leak tested and all systems have been verified to be operational. The purpose of the test is to show that bag-in/bag-out operations and glove change-outs can be accomplished without spreading the actual contaminated material to non-contaminated areas. The characterization test also provides information as to where contamination might be expected to build-up during actual operations. The fluorescent powder is used because it is easily detectable using an ultra-violet light and disperses in a similar fashion to radioactive material. The characterization and barrier integrity test of a glovebox using fluorescent powder provides a visual method of determining areas of potential contamination accumulation and helps evaluate the ability to perform clean transfer operations and glove change-outs.

Wahlquist, D.R. [Argonne National Lab., Idaho Falls, ID (United States). Technology Development Div.

1996-07-01T23:59:59.000Z

214

Nuclear fuels technologies fiscal year 1998 research and development test plan  

Science Conference Proceedings (OSTI)

A number of research and development (R and D) activities are planned at Los Alamos National Laboratory (LANL) in FY98 in support of the Department of Energy Office of Fissile Materials Disposition (DOE-MD). During the past few years, the ability to fabricate mixed oxide (MOX) nuclear fuel using surplus-weapons plutonium has been researched, and various experiments have been performed. This research effort will be continued in FY98 to support further development of the technology required for MOX fuel fabrication for reactor-based plutonium disposition. R and D activities for FY98 have been divided into four major areas: (1) feed qualification/supply, (2) fuel fabrication development, (3) analytical methods development, and (4) gallium removal. Feed qualification and supply activities encompass those associated with the production of both PuO{sub 2} and UO{sub 2} feed materials. Fuel fabrication development efforts include studies with a new UO{sub 2} feed material, alternate sources of PuO{sub 2}, and determining the effects of gallium on the sintering process. The intent of analytical methods development is to upgrade and improve several analytical measurement techniques in support of other R and D and test fuel fabrication tasks. Finally, the purpose of the gallium removal system activity is to develop and integrate a gallium removal system into the Pit Disassembly and Conversion Facility (PDCF) design and the Phase 2 Advanced Recovery and Integrated Extraction System (ARIES) demonstration line. These four activities will be coordinated and integrated appropriately so that they benefit the Fissile Materials Disposition Program. This plan describes the activities that will occur in FY98 and presents the schedule and milestones for these activities.

Alberstein, D.; Blair, H.T.; Buksa, J.J. [and others

1998-06-01T23:59:59.000Z

215

Apparatus and method for defect testing of integrated circuits  

DOE Patents (OSTI)

An apparatus and method for defect and failure-mechanism testing of integrated circuits (ICs) is disclosed. The apparatus provides an operating voltage, V.sub.DD, to an IC under test and measures a transient voltage component, V.sub.DDT, signal that is produced in response to switching transients that occur as test vectors are provided as inputs to the IC. The amplitude or time delay of the V.sub.DDT signal can be used to distinguish between defective and defect-free (i.e. known good) ICs. The V.sub.DDT signal is measured with a transient digitizer, a digital oscilloscope, or with an IC tester that is also used to input the test vectors to the IC. The present invention has applications for IC process development, for the testing of ICs during manufacture, and for qualifying ICs for reliability.

Cole, Jr., Edward I. (Albuquerque, NM); Soden, Jerry M. (Placitas, NM)

2000-01-01T23:59:59.000Z

216

Ice-making heat exchanger evaluation and test plan  

DOE Green Energy (OSTI)

Several approaches to making ice for district cooling are identified and their current status discussed. Recommendations for future work are given, with a detailed plan for one phase of the work. 13 refs., 5 figs.

Andrews, J.W.; Leigh, R.W.; Piraino, M.W.

1990-01-01T23:59:59.000Z

217

Method of and apparatus for testing the integrity of filters  

DOE Patents (OSTI)

A method of and apparatus are disclosed for testing the integrity of individual filters or filter stages of a multistage filtering system including a diffuser permanently mounted upstream and/or downstream of the filter stage to be tested for generating pressure differentials to create sufficient turbulence for uniformly dispersing trace agent particles within the airstream upstream and downstream of such filter stage. Samples of the particle concentration are taken upstream and downstream of the filter stage for comparison to determine the extent of particle leakage past the filter stage. 5 figs.

Herman, R.L.

1985-05-07T23:59:59.000Z

218

Method of and apparatus for testing the integrity of filters  

DOE Patents (OSTI)

A method of and apparatus for testing the integrity of individual filters or filter stages of a multistage filtering system including a diffuser permanently mounted upstream and/or downstream of the filter stage to be tested for generating pressure differentials to create sufficient turbulence for uniformly dispersing trace agent particles within the airstream upstream and downstream of such filter stage. Samples of the particle concentration are taken upstream and downstream of the filter stage for comparison to determine the extent of particle leakage past the filter stage.

Herman, Raymond L. (Richland, WA)

1985-01-01T23:59:59.000Z

219

Methods of and apparatus for testing the integrity of filters  

DOE Patents (OSTI)

A method of and apparatus for testing the integrity of individual filters or filter stages of a multistage filtering system including a diffuser permanently mounted upstream and/or downstream of the filter stage to be tested for generating pressure differentials to create sufficient turbulence for uniformly dispersing trace agent particles within the airstram upstream and downstream of such filter stage. Samples of the particel concentration are taken upstream and downstream of the filter stage for comparison to determine the extent of particle leakage past the filter stage.

Herman, R.L.

1984-01-01T23:59:59.000Z

220

The Optimized Integration of the Decontamination Plan and the Radwaste Management Plan into Decommissioning Plan to the VVR-S Research Reactor from Romania  

SciTech Connect

The paper presents the progress of the Decontamination Plan and Radioactive Waste Management Plan which accompanies the Decommissioning Plan for research reactor VVR-S located in Magurele, Ilfov, near Bucharest, Romania. The new variant of the Decommissioning Plan was elaborated taking into account the IAEA recommendation concerning radioactive waste management. A new feasibility study for VVR-S decommissioning was also elaborated. The preferred safe management strategy for radioactive wastes produced by reactor decommissioning is outlined. The strategy must account for reactor decommissioning, as well as rehabilitation of the existing Radioactive Waste Treatment Plant and the upgrade of the Radioactive Waste Disposal Facility at Baita-Bihor. Furthermore, the final rehabilitation of the laboratories and reusing of cleaned reactor building is envisaged. An inventory of each type of radioactive waste is presented. The proposed waste management strategy is selected in accordance with the IAEA assistance. Environmental concerns are a part of the radioactive waste management strategy. In conclusion: The current version 8 of the Draft Decommissioning Plan which include the Integrated concept of Decontamination and Decommissioning and Radwaste Management, reflects the substantial work that has been incorporated by IFIN-HH in collaboration with SITON, which has resulted in substantial improvement in document The decommissioning strategy must take into account costs for VVR-S Reactor decommissioning, as well as costs for much needed refurbishments to the radioactive waste treatment plant and the Baita-Bihor waste disposal repository. Several improvements to the Baita-Bihor repository and IFIN-HH waste treatment facility were proposed. The quantities and composition of the radioactive waste generated by VVR-S Reactor dismantling were again estimated by streams and the best demonstrated practicable processing solution was proposed. The estimated quantities of materials to be managed in the near future raise some issues that need to be solved swiftly, such as treatment of aluminum and lead and graphite management. It is envisaged that these materials to be treated to Subsidiary for Nuclear Research (SCN) Pitesti. (authors)

Barariu, G. [National Authority for Nuclear Activity-Subsidiary of Technology and Engineering for Nuclear Projects (Romania)

2008-07-01T23:59:59.000Z

Note: This page contains sample records for the topic "integrated test plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


221

Interim Test Procedures for Evaluating Electrical Performance and Grid Integration of Vehicle-to-Grid Applications  

DOE Green Energy (OSTI)

The objective of this report is to provide a test plan for V2G testing. The test plan is designed to test and evaluate the vehicle's power electronics capability to provide power to the grid, and to evaluate the vehicle's ability to connect and disconnect from the utility according to a subset of the IEEE Std. 1547 tests.

Chakraborty, S.; Kramer, W.; Kroposki, B.; Martin, G.; McNutt, P.; Kuss, M.; Markel, T.; Hoke, A.

2011-06-01T23:59:59.000Z

222

Planning and design of additional East Mesa Geothermal Test Facilities. Phase 1B. Volume I. Final report  

DOE Green Energy (OSTI)

The planning and design of additions to the ERDA East Mesa Geothermal Component Test Facility are discussed. The ERDA East Mesa Geothermal Component Test Facility will provide moderate temperature/low salinity fluids to facilitate comprehensive testing of conversion systems and components under realistic field conditions. The project objectives included development of designs of new wells and modifications to existing wells to improve definitive reservoir evaluations and design of additional test facilities integrated with the limited-scale facilities to accommodate diverse commercial utilization technology experiments. A reservoir utilization evaluation was conducted to establish locations and design drilling programs for three new wells and modifications to existing wells to improve reservoir definition and provide a comprehensive inventory of geothermal well fluids for testing. Ten test facility additions were developed as individual procurement packages of specifications and drawings to facilitate near term construction activation.

Pearson, R.O.

1976-10-01T23:59:59.000Z

223

Landscape ecological planning: Integrating land use and wildlife conservation for biomass crops  

DOE Green Energy (OSTI)

What do a mussel shoat, a zoo, and a biomass plantation have in common? Each can benefit from ecology-based landscape planning. This paper provides examples of landscape ecological planning from some diverse projects the author has worked on, and discusses how processes employed and lessons learned from these projects are being used to help answer questions about the effects of biomass plantings (hardwood tree crops and native grasses) on wildlife habitat. Biomass environmental research is being designed to assess how plantings of different acreage, composition and landscape context affect wildlife habitat value, and is addressing the cumulative effect on wildlife habitat of establishing multiple biomass plantations across the landscape. Through landscape ecological planning, answers gleaned from research can also help guide biomass planting site selection and harvest strategies to improve habitat for native wildlife species within the context of economically viable plantation management - thereby integrating the needs of people with those of the environment.

Schiller, A.

1995-12-31T23:59:59.000Z

224

Development and Test Plans for a small Vertical Axis Turbine...  

NLE Websites -- All DOE Office Websites (Extended Search)

and Transport Urban and Regional Air Quality Research Facilities Advanced Windows Test Facility BATT Fabrication Laboratory Cookstove Efficiency and Emissions Testing...

225

Electric utility system planning studies for OTEC power integration. Final report  

DOE Green Energy (OSTI)

Florida Power Corporation (FPC) conducted an evaluation of the possible integration of OTEC into the FPC system. Existing system planning procedures, assumptions, and corporate financial criteria for planning new generating capacity were used without modification. A baseline configuration for an OTEC plant was developed for review with standard planning procedures. The OTEC plant characteristics and costs were incorporated in considerable detail. These basic inputs were examined using the FPC system planning methods. It was found that with the initial set of conditions, OTEC would not be economically viable. Using the same system planning procedures, a number of adjustments were made to the key study assumptions. It was found that two considerations dominate the analysis; the assumed rate of fuel cost escalation, and the projected capital cost of the OTEC plant. The analysis produced a parametric curve: on one hand, if fuel costs were to escalate at a rate greater than assumed (12% vs the assumed 5% for coal), and if no change were made to the OTEC input assumptions, the basic economic competitive criteria would be equivalent to the principal alternative, coal fueled plants. Conversely, if the projected cost of the OTEC plant were to be reduced from the assumed $2256/kW to $1450/kW, the economic competitiveness criterion would be satisfied. After corporate financial analysis, it was found that even if the cost competitive criterion were to be reached, the plan including OTEC could not be financed by Florida Power Corporation. Since, under the existing set of conditions for financing new plant capital requirements, FPC could not construct an OTEC plant, some other means of ownership would be necessary to integrate OTEC into the FPC system. An alternative such as a third party owning the plant and selling power to FPC, might prove attractive. (WHK)

None

1980-11-30T23:59:59.000Z

226

STREAMLINED APPROACH FOR ENVIRONMENTAL RESTORATION PLAN FOR CORRECTIVE ACTION UNIT 116: AREA 25 TEST CELL C FACILITYNEVADA TEST SITE, NEVADA  

SciTech Connect

This Streamlined Approach for Environmental Restoration Plan identifies the activities required for the closure of Corrective Action Unit 116, Area 25 Test Cell C Facility. The Test Cell C Facility is located in Area 25 of the Nevada Test Site approximately 25 miles northwest of Mercury, Nevada.

NONE

2006-07-01T23:59:59.000Z

227

NISTIR 7297-A FS-TST 2.0: Forensic Software Testing Support Tools Test Plan, Test Design Specifications, and Test Case Specification  

E-Print Network (OSTI)

imaging tools typically used in forensic investigations. The package includes programs that initialize disk drives, detect changes in disk content, and compare pairs of disks. This Internal Report consists of three parts. This is Part A, Test Plan, Test Design Specifications, and Test Case Specification. It covers the planning, design, and specification of testing of FS-TST 2.0. The setup of disk drives and the testing is to be performed in the Linux environment; however, some tests will require interaction with the MS-DOS operating system. Part B, Test Summary Report, is a companion document. It reports the result of testing the FS-TST 2.0 package according to Part A. Two programs might have had slightly more convenient behavior in erroneous cases, but no anomalies were found in testing. Part C, Code Review Report, is an additional companion document. It covers the planning and specification of reviewing all the source code in the package and reports the results of the code reviews. Nothing was found in the code reviews that should cause invalid results, that is, that should lead to an imaging tool with systematic errors being incorrectly passed as adhering to the assertions. The intended audience for this document should be familiar with the Linux operating system, computer operation, and computer hardware components such as hard drives.

Serban I. Gavrila

2005-01-01T23:59:59.000Z

228

Autoquan 3, version 3.11, MIDAC Corporation Computer Software Test Plan  

SciTech Connect

This test plan will be performed in conjunction with or prior to HNF-6936, ''HA-53 Supercritical Fluid Extraction System Acceptance Test Plan'', to operate the Fourier transform infrared spectrophotometer (FTIR) and to perform analyses for water. The test will ensure that the software can be installed properly, will operate the FTIR correctly and will generate a text file with analytical data.

HURLBUT, S.T.

2000-10-24T23:59:59.000Z

229

Opportunities for integrating deliberate and time-sensitive joint depolyment planning in USTRANSCOM component commands  

Science Conference Proceedings (OSTI)

The Decision System Research Section of the Oak Ridge National Laboratory (ORNL) is assisting the Deployment Directorate (formerly the Joint Deployment Agency) of the US Transportation Command (USTRANSCOM) in identifying and evaluating opportunities for improving the automation support used in deliberate and time-critical deployment planning. USTRANSCOM, which is a unified command (i.e., personnel are drawn from all services), was created in the fall of 1987 to consolidate the functions of the former Military Transportation Operating Agencies (the Military Airlift Command, the Military Traffic Management Command, and the Military Sealift Command). An important factor justifying creation of USTRANSCOM, was the possibility of combining and improving coordination in deployment planning between the organizations responsible for strategic transportation activities during times of crisis. This report, the second in a series to be produced in the course of the ORNL study, presents three possibilities for integrating deliberate and time-sensitive planning. Two proposals recommended for use by MTMC and MSC build on cooperative planning initiatives already in progress in the two commands. A unique application of relative probabilistic measures is a key element in a proposal for improving MTMC/MAC airlift planning. 35 refs., 1 tab.

Edwards, R.

1988-05-02T23:59:59.000Z

230

Testing operations plan: Coso Geothermal Exploratory Hole No. 1 (CGEH-1) |  

Open Energy Info (EERE)

operations plan: Coso Geothermal Exploratory Hole No. 1 (CGEH-1) operations plan: Coso Geothermal Exploratory Hole No. 1 (CGEH-1) Jump to: navigation, search GEOTHERMAL ENERGYGeothermal Home Report: Testing operations plan: Coso Geothermal Exploratory Hole No. 1 (CGEH-1) Details Activities (1) Areas (1) Regions (0) Abstract: Coso Geothermal Exploratory Hole No. 1 (CGEH-1) was drilled to investigate the potential of the Coso Hot Springs Known Geothermal Resource Area (KGRA) in southeastern California. Detailed background information is contained in the drilling plan, Coso Geothermal Exploratory Hole No. 1 (CGEH-1), NVO-184, dated June 1977. The purpose of this supplement to NVO-184 is to establish a plan of operations for testing the resource after completion of well drilling activities. Major elements of this plan include

231

Test plan for the irradiation of nonmetallic materials.  

SciTech Connect

A comprehensive test program to evaluate nonmetallic materials use in the Hanford tank farms is described in detail. This test program determines the effects of simultaneous multiple stressors at reasonable conditions on in-service configuration components by engineering performance testing.

Brush, Laurence H.; Farnum, Cathy Ottinger; Dahl, M. [ARES Corporation, Richland, WA; Joslyn, C. C. [Washington River Protection Solutions, Richland, WA; Venetz, T. J. [Washington River Protection Solutions, Richland, WA

2013-05-01T23:59:59.000Z

232

Test plan for the irradiation of nonmetallic materials.  

SciTech Connect

A comprehensive test program to evaluate nonmetallic materials use in the Hanford Tank Farms is described in detail. This test program determines the effects of simultaneous multiple stressors at reasonable conditions on in-service configuration components by engineering performance testing.

Brush, Laurence H.; Farnum, Cathy Ottinger; Gelbard, Fred; Dahl, M. [ARES Corporation, Richland, WA; Joslyn, C. C. [Washington River Protection Solutions, Richland, WA; Venetz, T. J. [Washington River Protection Solutions, Richland, WA

2013-03-01T23:59:59.000Z

233

Closure Plan for the Area 3 Radioactive Waste Management Site at the Nevada Test Site  

Science Conference Proceedings (OSTI)

The Area 3 Radioactive Waste Management Site (RMWS) at the Nevada Test Site (NTS) is managed and operated by National Security Technologies, LLC (NSTec) for the U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office (NNSA/NSO). This document is the first update of the interim closure plan for the Area 3 RWMS, which was presented in the Integrated Closure and Monitoring Plan (ICMP) (DOE, 2005). The format and content of this plan follows the Format and Content Guide for U.S. Department of Energy Low-Level Waste Disposal Facility Closure Plans (DOE, 1999a). The major updates to the plan include a new closure date, updated closure inventory, the new institutional control policy, and the Title II engineering cover design. The plan identifies the assumptions and regulatory requirements, describes the disposal sites and the physical environment in which they are located, presents the design of the closure cover, and defines the approach and schedule for both closing and monitoring the site. The Area 3 RWMS accepts low-level waste (LLW) from across the DOE Complex in compliance with the NTS Waste Acceptance Criteria (NNSA/NSO, 2006). The Area 3 RWMS accepts both packaged and unpackaged unclassified bulk LLW for disposal in subsidence craters that resulted from deep underground tests of nuclear devices in the early 1960s. The Area 3 RWMS covers 48 hectares (119 acres) and comprises seven subsidence craters--U-3ax, U-3bl, U-3ah, U-3at, U-3bh, U-3az, and U-3bg. The area between craters U-3ax and U-3bl was excavated to form one large disposal unit (U-3ax/bl); the area between craters U-3ah and U-3at was also excavated to form another large disposal unit (U-3ah/at). Waste unit U-3ax/bl is closed; waste units U-3ah/at and U-3bh are active; and the remaining craters, although currently undeveloped, are available for disposal of waste if required. This plan specifically addresses the closure of the U-3ah/at and the U-3bh LLW units. A final closure cover has been placed on unit U-3ax/bl (Corrective Action Unit 110) at the Area 3 RWMS. Monolayer-evapotranspirative closure cover designs for the U-3ah/at and U-3bh units are provided in this plan. The current-design closure cover thickness is 3 meters (10 feet). The final design cover will have an optimized cover thickness, which is expected to be less than 3 m (10 ft). Although waste operations at the Area 3 RWMS have ceased at the end of June 2006, disposal capacity is available for future disposals at the U-3ah/at and U-3bh units. The Area 3 RWMS is expected to start closure activities in fiscal year 2025, which include the development of final performance assessment and composite analysis documents, closure plan, closure cover design for construction, cover construction, and initiation of the post-closure care and monitoring activities. Current monitoring at the Area 3 RWMS includes monitoring the cover of the closed mixed waste unit U-3ax/bl as required by the Nevada Department of Environmental Protection, and others required under federal regulations and DOE orders. Monitoring data, collected via sensors and analysis of samples, are needed to evaluate radiation doses to the general public, for performance assessment maintenance, to demonstrate regulatory compliance, and to evaluate the actual performance of the RWMSs. Monitoring provides data to ensure the integrity and performance of waste disposal units. The monitoring program is designed to forewarn management and regulators of any failure and need for mitigating actions. The plan describes the program for monitoring direct radiation, air, vadose zone, biota, groundwater, meteorology, and subsidence. The requirements of post-closure cover maintenance and monitoring will be determined in the final closure plan.

NSTec Environmental Management

2007-09-01T23:59:59.000Z

234

Testing, planning, and redrilling of Geothermal Test Hole GT-2, Phases IV and V. Progress report  

DOE Green Energy (OSTI)

Holes GT-2 and EE-1 comprise the two deep drill holes of the Los Alamos Hot Dry Rock Geothermal Energy Extraction Experiment. EE-1 had been directionally drilled to intersect a hydraulic fracture extending outward from near the bottom of GT-2, thus completing the underground circulation loop. After the drilling of EE-1, a 16-month period of experimental testing ensued to determine the characteristics of the reservoir. This period is designated as Phase IV and includes work done in GT-2 and EE-1. As a result of this testing, it was determined that parallel fracture zones existed at the bottoms of both holes, and that the impedance to flow between the holes was too high for a meaningful flow experiment. A plan was then adopted to directionally drill out of GT-2 at a depth of about 2600 m (8500 ft) to intersect the fracture zone near the bottom of EE-1 to create a better connection. The directional drilling strategy, cementing practices, bit selections, coring procedures, and logging results comprise the Phase V work.

Pettitt, R.A.

1978-12-01T23:59:59.000Z

235

INEL/Snake River plain geothermal drilling and testing plan - INEL - 1 well  

DOE Green Energy (OSTI)

A plan for drilling a 7500 ft exploratory hole is described. This hole would be drilled at the Idaho National Engineering Laboratory, so that it could be immediately used by one of the government facilties. The plan details the hole design, describes the drilling program, proposes a testing program, and estimates costs. (MHR)

Miller, L.G.; Prestwich, S.M.; Griffith, J.L.

1978-12-01T23:59:59.000Z

236

Deflagration studies on waste Tank 101-SY: Test plan  

DOE Green Energy (OSTI)

This report discusses test procedures and calibration of equipment to study the flammability and deflagration of hydrogen, nitrous oxide, and air in waste tanks. (JL)

Cashdollar, K.L.; Zlochower, I.A.; Hertzberg, M.

1991-06-01T23:59:59.000Z

237

Microsoft Word - AGA12 TestPlan 2-6-07.doc  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

AGA 12, Part 2 AGA 12, Part 2 Performance Test Plan U.S. Department of Energy Office of Electricity Delivery and Energy Reliability Enhancing control systems security in the energy sector NSTB Mark Hadley, Kristy Huston Pacific Northwest National Laboratories November 2006 Acknowledgements The authors wish to thank Bill Rush and Aakash Shah of the Gas Technology Institute as well as the members of the NERC Control Systems Security Working Group and Sandia National Laboratory for their contributions towards the development of this test plan. NSTB AGA 12, Part 2 Performance Test Plan i EXECUTIVE SUMMARY Under the guidance and sponsorship of DOE's Office of Electricity Delivery and Energy Reliability, Pacific Northwest National Laboratory (PNNL) developed a test plan for AGA 12, Part 2 compliant

238

Fuel Cell Technologies Program Multi-Year Research, Development and Demonstration Plan - Section 5.0 Systems Integration  

NLE Websites -- All DOE Office Websites (Extended Search)

Page 3.8 Page 3.8 2012 Systems Integration Multi-Year Research, Development and Demonstration Plan Page 5 - 1 5.0 Systems Integration The Systems Integration function of the DOE Hydrogen and Fuel Cells Program (the Program) provides independent, strategic, systems-level expertise and processes to enable system-level planning, data-driven decision-making, effective portfolio management, and program integration. System Integration ensures that system-level targets are developed, verified, and met and that the sub- programs are well-coordinated. Systems Integration provides tailored technical and programmatic support to ensure a disciplined approach to the research, design, development, and validation of complex systems. Systems Integration provides

239

River Protection Project Integrated safety management system phase II verification review plan - 7/29/99  

Science Conference Proceedings (OSTI)

The purpose of this review is to verify the implementation status of the Integrated Safety Management System (ISMS) for the River Protection Project (RPP) facilities managed by Fluor Daniel Hanford, Inc. (FDH) and operated by Lockheed Martin Hanford Company (LMHC). This review will also ascertain whether within RPP facilities and operations the work planning and execution processes are in place and functioning to effectively protect the health and safety of the workers, public, environment, and federal property over the RPP life cycle. The RPP ISMS should support the Hanford Strategic Plan (DOERL-96-92) to safely clean up and manage the site's legacy waste and deploy science and technology while incorporating the ISMS central theme to ''Do work safely'' and protect human health and the environment.

SHOOP, D.S.

1999-09-10T23:59:59.000Z

240

300 Area Integrated Field-Scale Subsurface Research Challenge (IFRC) Field Site Management Plan  

Science Conference Proceedings (OSTI)

Pacific Northwest National Laboratory (PNNL) has established the 300 Area Integrated Field-Scale Subsurface Research Challenge (300 Area IFRC) on the Hanford Site in southeastern Washington State for the U.S. Department of Energys (DOE) Office of Biological and Environmental Research (BER) within the Office of Science. The project is funded by the Environmental Remediation Sciences Division (ERSD). The purpose of the project is to conduct research at the 300 IFRC to investigate multi-scale mass transfer processes associated with a subsurface uranium plume impacting both the vadose zone and groundwater. The management approach for the 300 Area IFRC requires that a Field Site Management Plan be developed. This is an update of the plan to reflect the installation of the well network and other changes.

Freshley, Mark D.

2008-12-31T23:59:59.000Z

Note: This page contains sample records for the topic "integrated test plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


241

Gearbox Reliability Collaborative Phase 3 Gearbox 2 Test Plan  

SciTech Connect

Gearboxes in wind turbines have not been achieving their expected design life even though they commonly meet or exceed the design criteria specified in current design standards. One of the basic premises of the National Renewable Energy Laboratory (NREL) Gearbox Reliability Collaborative (GRC) is that the low gearbox reliability results from the absence of critical elements in the design process or insufficient design tools. Key goals of the GRC are to improve design approaches and analysis tools and to recommend practices and test methods resulting in improved design standards for wind turbine gearboxes that lower the cost of energy (COE) through improved reliability. The GRC uses a combined gearbox testing, modeling and analysis approach, along with a database of information from gearbox failures collected from overhauls and investigation of gearbox condition monitoring techniques to improve wind turbine operations and maintenance practices. Testing of Gearbox 2 (GB2) using the two-speed turbine controller that has been used in prior testing. This test series will investigate non-torque loads, high-speed shaft misalignment, and reproduction of field conditions in the dynamometer. This test series will also include vibration testing using an eddy-current brake on the gearbox's high speed shaft.

Link, H.; Keller, J.; Guo, Y.; McNiff, B.

2013-04-01T23:59:59.000Z

242

Gearbox Reliability Collaborative Phase 3 Gearbox 2 Test Plan  

DOE Green Energy (OSTI)

Gearboxes in wind turbines have not been achieving their expected design life even though they commonly meet or exceed the design criteria specified in current design standards. One of the basic premises of the National Renewable Energy Laboratory (NREL) Gearbox Reliability Collaborative (GRC) is that the low gearbox reliability results from the absence of critical elements in the design process or insufficient design tools. Key goals of the GRC are to improve design approaches and analysis tools and to recommend practices and test methods resulting in improved design standards for wind turbine gearboxes that lower the cost of energy (COE) through improved reliability. The GRC uses a combined gearbox testing, modeling and analysis approach, along with a database of information from gearbox failures collected from overhauls and investigation of gearbox condition monitoring techniques to improve wind turbine operations and maintenance practices. Testing of Gearbox 2 (GB2) using the two-speed turbine controller that has been used in prior testing. This test series will investigate non-torque loads, high-speed shaft misalignment, and reproduction of field conditions in the dynamometer. This test series will also include vibration testing using an eddy-current brake on the gearbox's high speed shaft.

Link, H.; Keller, J.; Guo, Y.; McNiff, B.

2013-04-01T23:59:59.000Z

243

Standard Test Methods for Wet Insulation Integrity Testing of Photovoltaic Modules  

E-Print Network (OSTI)

1.1 These test methods provide procedures to determine the insulation resistance of a photovoltaic (PV) module, i.e. the electrical resistance between the module's internal electrical components and its exposed, electrically conductive, non-current carrying parts and surfaces. 1.2 The insulation integrity procedures are a combination of wet insulation resistance and wet dielectric voltage withstand test procedures. 1.3 These procedures are similar to and reference the insulation integrity test procedures described in Test Methods E 1462, with the difference being that the photovoltaic module under test is immersed in a wetting solution during the procedures. 1.4 These test methods do not establish pass or fail levels. The determination of acceptable or unacceptable results is beyond the scope of these test methods. 1.5 The values stated in SI units are to be regarded as the standard. 1.6 There is no similar or equivalent ISO standard. 1.7 This standard does not purport to address all of the safety conce...

American Society for Testing and Materials. Philadelphia

2007-01-01T23:59:59.000Z

244

Victor J. Daniel Jr. CO2 Injection Test Site Plan  

NLE Websites -- All DOE Office Websites (Extended Search)

Mississippi Test Site JAF02664.PPT 1 1.1 SITE BACKGROUND 1.2 GENERAL IDENTIFICATION DATA 1.3 REGULATORY CLASSIFICATION 1.4 WELL DATA - INJECTION WELL NO. 1 1.5 WELL DATA -...

245

Corrective Action Investigation Plan for the Central Nevada Test...  

Office of Legacy Management (LM)

focus on the subset of the test related contaminants that are found to be critical in terms of health and safety (e.g., 3 H, 90 Sr, 137 Cs). The uncertainty of the composite (4...

246

Pig shipping container test sequence  

SciTech Connect

This test plan outlines testing of the integrity of the pig shipping container. It is divided into four sections: (1) drop test requirements; (2) test preparations; (3) perform drop test; and (4) post-test examination.

Adkins, H.E. Jr.

1995-01-13T23:59:59.000Z

247

Test plan for the Parallex CANDU-MOX irradiation  

Science Conference Proceedings (OSTI)

One of several options being considered by the United States and the Russian Federation for the disposition of excess plutonium from dismantled weapons is to convert it to mixed-oxide (MOX) fuel for use in Canadian uranium-deuterium (CANDU) reactors. This report describes an irradiation test demonstrating the feasibility of this concept with laboratory quantities of MOX fuel placed in the pressurized loops of the National Research Universal test reactor at the Atomic Energy of Canada, Ltd., Chalk River Laboratories. The objective of the Parallex (for parallel experiment) test is to simultaneously test laboratory-produced quantities of US and R.F. MOX fuel in a test reactor under heat generation rates representing those expected in the CANDU reactors. The MOX fuel will be produced with plutonium from disassembled weapons at the Los Alamos National Laboratory in the United States and at the Bochvar Institute in the Russian Federation. Thus, the test will serve to demonstrate the accomplishment of many parts of the disposition mission: disassembly of weapons, conversion of the plutonium to oxide, fabrication of MOX fuel, assembly of fuel elements and bundles, shipment to a reactor, irradiation, and finally, storage of the spent fuel elements awaiting eventual disposition in a geologic repository in Canada.

Copeland, G.L.

1997-06-01T23:59:59.000Z

248

Vadose Zone Transport Field Study: Detailed Test Plan for Simulated Leak Tests  

Science Conference Proceedings (OSTI)

This report describes controlled transport experiments at well-instrumented field tests to be conducted during FY 2000 in support of DOE?s Vadose Zone Transport Field Study (VZTFS). The VZTFS supports the Groundwater/Vadose Zone Integration Project Science and Technology Initiative. The field tests will improve understanding of field-scale transport and lead to the development or identification of efficient and cost-effective characterization methods. These methods will capture the extent of contaminant plumes using existing steel-cased boreholes. Specific objectives are to 1) identify mechanisms controlling transport processes in soils typical of the hydrogeologic conditions of Hanford?s waste disposal sites; 2) reduce uncertainty in conceptual models; 3) develop a detailed and accurate data base of hydraulic and transport parameters for validation of three-dimensional numerical models; and 4) identify and evaluate advanced, cost-effective characterization methods with the potential to assess changing conditions in the vadose zone, particularly as surrogates of currently undetectable high-risk contaminants. Pacific Northwest National Laboratory (PNNL) manages the VZTFS for DOE.

Ward, Anderson L.; Gee, Glendon W.

2000-06-23T23:59:59.000Z

249

Fiscal Year 2005 Integrated Monitoring Plan for the Hanford Groundwater Performance Assessment Project  

Science Conference Proceedings (OSTI)

Groundwater is monitored in hundreds of wells at the Hanford Site to fulfill a variety of requirements. Separate monitoring plans are prepared for various purposes, but sampling is coordinated and data are shared among users. DOE manages these activities through the Hanford Groundwater Performance Assessment Project, which is the responsibility of Pacific Northwest National Laboratory. The groundwater project integrates monitoring for various objectives into a single sampling schedule to avoid redundancy of effort and to improve efficiency of sample collection.This report documents the purposes and objectives of groundwater monitoring at the DOE Hanford Site in southeastern Washington State.

Rieger, JoAnne T.; Hartman, Mary J.

2005-06-16T23:59:59.000Z

250

Report of the Integrated Program Planning Activity for the DOE Fusion Energy Sciences Program  

SciTech Connect

This report of the Integrated Program Planning Activity (IPPA) has been prepared in response to a recommendation by the Secretary of Energy Advisory Board that, ''Given the complex nature of the fusion effort, an integrated program planning process is an absolute necessity.'' We, therefore, undertook this activity in order to integrate the various elements of the program, to improve communication and performance accountability across the program, and to show the inter-connectedness and inter-dependency of the diverse parts of the national fusion energy sciences program. This report is based on the September 1999 Fusion Energy Sciences Advisory Committee's (FESAC) report ''Priorities and Balance within the Fusion Energy Sciences Program''. In its December 5,2000, letter to the Director of the Office of Science, the FESAC has reaffirmed the validity of the September 1999 report and stated that the IPPA presents a framework and process to guide the achievement of the 5-year goals listed in the 1999 report. The National Research Council's (NRC) Fusion Assessment Committee draft final report ''An Assessment of the Department of Energy's Office of Fusion Energy Sciences Program'', reviewing the quality of the science in the program, was made available after the IPPA report had been completed. The IPPA report is, nevertheless, consistent with the recommendations in the NRC report. In addition to program goals and the related 5-year, 10-year, and 15-year objectives, this report elaborates on the scientific issues associated with each of these objectives. The report also makes clear the relationships among the various program elements, and cites these relationships as the reason why integrated program planning is essential. In particular, while focusing on the science conducted by the program, the report addresses the important balances between the science and energy goals of the program, between the MFE and IFE approaches, and between the domestic and international aspects of the program. The report also outlines a process for establishing a database for the fusion research program that will indicate how each research element fits into the overall program. This database will also include near-term milestones associated with each research element, and will facilitate assessments of the balance within the program at different levels. The Office of Fusion Energy Sciences plans to begin assembling and using the database in the Spring of 2001 as we receive proposals from our laboratories and begin to prepare our budget proposal for Fiscal Year 2003.

None

2000-12-01T23:59:59.000Z

251

Plan  

NLE Websites -- All DOE Office Websites (Extended Search)

Methane Hydrate Multi-Year R&D Program Plan NATIONAL METHANE HYDRATE MULTI-YEAR R&D PROGRAM PLAN U.S. Department of Energy Office of Fossil Energy Federal Energy Technology Center...

252

Performance test plan for a space station toluene heater tube  

DOE Green Energy (OSTI)

Sundstrand Energy Systems was awarded a contract to investigate the performance capabilities of a toluene heater tube integral to a heat pipe as applied to the Organic Rankine Cycle (ORC) solar dynamic power system for the Space Station. This heat pipe is a subassembly of the heat receiver. The heat receiver, the heat absorption component of the ORC solar dynamic power system, consists of forty liquid metal heat pipes located circumferentially around the heat receiver`s outside diameter. Each heat pipe contains a toluene heater, two thermal energy storage (TES) canisters and potassium. The function of the heater tube is to heat the supercritical toluene to the required turbine inlet temperature. During the orbit of the space station, the heat receiver and thereby the heat pipe and heater tube will be subjected to variable heat input. The design of the heater must be such that it can accommodate the thermal and hydraulic variations that will be imposed upon it.

Parekh, M.B. [Sundstrand Energy Systems, Rockford, IL (United States)

1987-10-01T23:59:59.000Z

253

Interim Test Procedures for Evaluating Electrical Performance and Grid Integration of Vehicle-to-Grid Applications  

SciTech Connect

The objective of this report is to provide a test plan for V2G testing. The test plan is designed to test and evaluate the vehicle's power electronics capability to provide power to the grid, and to evaluate the vehicle's ability to connect and disconnect from the utility according to a subset of the IEEE Std. 1547 tests.

Chakraborty, S.; Kramer, W.; Kroposki, B.; Martin, G.; McNutt, P.; Kuss, M.; Markel, T.; Hoke, A.

2011-06-01T23:59:59.000Z

254

Incorporating qualitative objectives in integrated resource planning: Application of analytic hierarchy process and compromise programming  

SciTech Connect

This article proposes a multiobjective methodology for the integrated resource planning (IRP) problem using a combined analytic hierarchy process (AHP)-compromise programming (CP) model. Six objectives, of which five are qualitative in nature, have been considered to select demand and supply-side resources for meeting future electricity demand. The quantitative objective (viz., cost) is employed directly in the CP model. AHP priorities are derived for the qualitative objectives (e.g., technological maturity) after eliciting expert judgments. These priorities are employed as coefficients of the decision variables in the objective functions corresponding to the qualitative objectives of the model. The two distinct advantages of this method are (1) explicit consideration of all important qualitative and quantitative aspects of demand-side management (DSM) and supply-side options, and (2) consideration of specific characteristics of various types of DSM options. An illustrative application is provided for an Indian utility (Maharashtra State Electricity System) for its integrated resource plan for the period 1990--2000. The results show that the AHP-CP model incorporating qualitative objectives selects a different portfolio of DSM and supply options, as compared with single-criterion solutions. Compromise among the conflicting objectives leads to significant cost savings as well as qualitative benefits like improved system reliability, reduced environmental impact, fewer problems related to fuel supply, and shorter project installation times.

Koundinya, S.; Chattopadhyay, D.; Ramanathan, R. [Indira Gandhi Inst. of Development Research, Bombay (India)

1995-09-01T23:59:59.000Z

255

Test Plan for Hydrogen Getters Project - Phase II  

DOE Green Energy (OSTI)

Hydrogen levels in many transuranic (TRU) waste drums are above the compliance threshold, therefore deeming the drums non-shippable to the Waste Isolation Pilot Plant (WIPP). Hydrogen getters (alkynes and dialkynes) are known to react irreversibly with hydrogen in the presence of certain catalysts. The primary purpose of this investigation is to ascertain the effectiveness of a hydrogen getter in an environment that contains gaseous compounds commonly found in the headspace of drums containing TRU waste. It is not known whether the volatile organic compounds (VOCs) commonly found in the headspace of TRU waste drums will inhibit (''poison'') the effectiveness of the hydrogen getter. The result of this study will be used to assess the feasibility of a hydrogen-getter system, which is capable of removing hydrogen from the payload containers or the Transuranic Package Transporter-II (TRUPACT-II) inner containment vessel to increase the quantity of TRU waste that can be shipped to the WIPP. Phase II for the Hydrogen Getters Project will focus on four primary objectives: Conduct measurements of the relative permeability of hydrogen and chlorinated VOCs through Tedlar (and possibly other candidate packaging materials) Test alternative getter systems as alternatives to semi-permeable packaging materials. Candidates include DEB/Pd/Al2O3 and DEB/Cu-Pd/C. Develop, test, and deploy kinetic optimization model Perform drum-scale test experiments to demonstrate getter effectiveness

Mroz, G.

1999-02-05T23:59:59.000Z

256

Corrective Action Investigation Plan for Corrective Action Unit 500: Test Cell A Septic System, Nevada Test Site, Nevada  

SciTech Connect

This Corrective Action Investigation Plan (CAIP) has been developed in accordance with the Federal Facility Agreement and Consent Order (FFACO) that was agreed to by the US Department of Energy, Nevada Operations Office (DOE/NV); the State of Nevada Division of Environmental Protection (NDEP); and the US Department of Defense (FFACO, 1996). The CAIP is a document that provides or references all of the specific information for investigation activities associated with Corrective Action Units (CAUs) or Corrective Action Sites (CASs). According to the FFACO (1996), CASs are sites potentially requiring corrective action(s), and may include solid waste management units, individual disposal sites, or release sites. Corrective Action Units consist of one or more CASs grouped together based on geography, technical similarity, or agency responsibility for the purpose of determining corrective actions. This CAIP will be used in conjunction with the Work Plan for Leachfield Corrective Action Units: Nevada Test Site and Tonopah Test Range, Nevada (DOE/NV, 1998c), hereafter referred to as the Leachfield Work Plan. Under the FFACO, a work plan is an optional planning document that provides information for a CAU or group of CAUs where significant commonality exists. This CAIP contains CAU-specific information including a facility description, environmental sample collection objectives, and the criteria for conducting site investigation activities at CAU 500. This CAIP addresses one of three leachfield systems associated with Test Cell A, which is located in Area 25 at the Nevada Test Site (NTS). The NTS is approximately 105 kilometers (km) (65 miles [mi]) northwest of Las Vegas, Nevada (see Leachfield Work Plan Figure 1-1). Corrective Action Unit 500 is comprised of the Test Cell A Septic System (CAS 25-04-05) and the associated leachfield system presented in Figure 1-1 (FFACO, 1996).

IT Las Vegas

1999-01-27T23:59:59.000Z

257

Integration of renewable energy sources: reliability-constrained power system planning and operations using computational intelligence  

E-Print Network (OSTI)

Renewable sources of energy such as wind turbine generators and solar panels have attracted much attention because they are environmentally friendly, do not consume fossil fuels, and can enhance a nations energy security. As a result, recently more significant amounts of renewable energy are being integrated into conventional power grids. The research reported in this dissertation primarily investigates the reliability-constrained planning and operations of electric power systems including renewable sources of energy by accounting for uncertainty. The major sources of uncertainty in these systems include equipment failures and stochastic variations in time-dependent power sources. Different energy sources have different characteristics in terms of cost, power dispatchability, and environmental impact. For instance, the intermittency of some renewable energy sources may compromise the system reliability when they are integrated into the traditional power grids. Thus, multiple issues should be considered in grid interconnection, including system cost, reliability, and pollutant emissions. Furthermore, due to the high complexity and high nonlinearity of such non-traditional power systems with multiple energy sources, computational intelligence based optimization methods are used to resolve several important and challenging problems in their operations and planning. Meanwhile, probabilistic methods are used for reliability evaluation in these reliability-constrained planning and design. The major problems studied in the dissertation include reliability evaluation of power systems with time-dependent energy sources, multi-objective design of hybrid generation systems, risk and cost tradeoff in economic dispatch with wind power penetration, optimal placement of distributed generators and protective devices in power distribution systems, and reliability-based estimation of wind power capacity credit. These case studies have demonstrated the viability and effectiveness of computational intelligence based methods in dealing with a set of important problems in this research arena.

Wang, Lingfeng

2008-12-01T23:59:59.000Z

258

Comprehensive Test Ban Treaty research and development FY95-96 program plan  

SciTech Connect

The Department of Energy (DOE) is responsible for the United States Government`s (USG) research and development (R&D) functions for monitoring nuclear explosions in the context of a Comprehensive Test Ban Treaty (CTBT). This responsibility includes the November 1993 transfer of the Department of Defense`s (DoD) CTBT R&D responsibility to DOE. The DOE research program builds on the broad base of USG expertise developed historically and includes R&D for detecting, locating, identifying, and characterizing nuclear explosions in all environments. The Office of Research and Development (NN-20), within the Department of Energy`s Office of Nonproliferation and National Security, formulates and executes the efforts necessary to meet the Department`s responsibilities. The following DOE laboratories as a team will support NN-20 in implementing the program plan: Lawrence Livermore National Laboratory, Los Alamos National Laboratory, Pacific Northwest Laboratory, and Sandia National Laboratories. DOE has committed to a cooperative program that draws upon the core competencies of the national laboratories and upon the strengths of other government agencies and the private sector (academia and industry). The integration of resources under a common direction will allow the program to be flexible and responsive to changing technical and policy requirements while maximizing the effectiveness of funding appropriations. DOE will develop and demonstrate appropriate technologies, algorithms, procedures, and integrated systems in a cost-effective and timely manner. The program comprises seismic, radionuclide, hydroacoustic, and infrasound monitoring; on-site inspection; space-based monitoring; and automated data processing elements.

1994-11-01T23:59:59.000Z

259

Test plan for phase II of the Retained Gas Sampler system  

DOE Green Energy (OSTI)

The Retained Gas Sampler (RGS) system is being developed to permit characterization of the gas phase component of waste tank core samples. Several laboratory experiments have been conducted which have affirmed the proof-of-principle for separating the gas phase materials from waste tank material in a quantitative manner. However, experiments conducted thus far have dealt only with representative materials and simulated hardware mock-ups. This test plan deals with the operation and testing of actual devices in the hot cell environment. This test plan coves all aspects of the RGS system including: sampler load-in, extrusion, gas extraction, quantitative separation, sample collection, and quantitative analysis. Sample material used in this test plan will be waste tank simulants and will not be radioactive. The work environment, however, will be an operating hot cell facility and will have radioactive contaminated surfaces. Operation of the system will therefore require an official radiation work permit (RWP).

Hey, B.E.

1995-06-19T23:59:59.000Z

260

TEST SYSTEM FOR EVALUATING SPENT NUCLEAR FUEL BENDING STIFFNESS AND VIBRATION INTEGRITY  

SciTech Connect

Transportation packages for spent nuclear fuel (SNF) must meet safety requirements specified by federal regulations. For normal conditions of transport, vibration loads incident to transport must be considered. This is particularly relevant for high-burnup fuel (>45 GWd/MTU). As the burnup of the fuel increases, a number of changes occur that may affect the performance of the fuel and cladding in storage and during transportation. The mechanical properties of high-burnup de-fueled cladding have been previously studied by subjecting defueled cladding tubes to longitudinal (axial) tensile tests, ring-stretch tests, ring-compression tests, and biaxial tube burst tests. The objective of this study is to investigate the mechanical properties and behavior of both the cladding and the fuel in it under vibration/cyclic loads similar to the sustained vibration loads experienced during normal transport. The vibration loads to SNF rods during transportation can be characterized by dynamic, cyclic, bending loads. The transient vibration signals in a specified transport environment can be analyzed, and frequency, amplitude and phase components can be identified. The methodology being implemented is a novel approach to study the vibration integrity of actual SNF rod segments through testing and evaluating the fatigue performance of SNF rods at defined frequencies. Oak Ridge National Laboratory (ORNL) has developed a bending fatigue system to evaluate the response of the SNF rods to vibration loads. A three-point deflection measurement technique using linear variable differential transformers is used to characterize the bending rod curvature, and electromagnetic force linear motors are used as the driving system for mechanical loading. ORNL plans to use the test system in a hot cell for SNF vibration testing on high burnup, irradiated fuel to evaluate the pellet-clad interaction and bonding on the effective lifetime of fuel-clad structure bending fatigue performance. Technical challenges include pure bending implementation, remote installation and detachment of the SNF test specimen, test specimen deformation measurement, and identification of a driving system suitable for use in a hot cell. Surrogate test specimens have been used to calibrate the test setup and conduct systematic cyclic tests. The calibration and systematic cyclic tests have been used to identify test protocol issues prior to implementation in the hot cell. In addition, cyclic hardening in unidirectional bending and softening in reverse bending were observed in the surrogate test specimens. The interface bonding between the surrogate clad and pellets was found to impact the bending response of the surrogate rods; confirming this behavior in the actual spent fuel segments will be an important aspect of the hot cell test implementation,

Wang, Jy-An John [ORNL; Wang, Hong [ORNL; Bevard, Bruce Balkcom [ORNL; Howard, Rob L [ORNL; Flanagan, Michelle [U.S. Nuclear Regulatory Commission

2013-01-01T23:59:59.000Z

Note: This page contains sample records for the topic "integrated test plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


261

Deflagration studies on waste Tank 101-SY: Test plan  

DOE Green Energy (OSTI)

Waste slurries produced during the recovery of plutonium and uranium from irradiated fuel are stored in underground storage tanks. While a variety of waste types have been generated, of particular concern are the wastes stored in Tank 101-SY. A slurry growth-gas evolution cycle has been observed since 1981. The waste consists of a thick slurry, consisting of a solution high in NaOH, NaNO{sub 3}, NaAlO{sub 2}, dissolved organic complexants (EDTA, HEDTA, NTA, and degradation products), other salts (sulfates and phosphates), and radionuclides (primarily cesium and strontium). During a gas release the major gaseous species identified include: hydrogen and nitrous oxide (N{sub 2}O). Significant amounts of nitrogen may also be present. Traces of ammonia, carbon oxides, and other nitrogen oxides are also detected. Air and water vapor are also present in the tank vapor space. The purpose of the deflagration study is to determine risks of the hydrogen, nitrous oxide, nitrogen, and oxygen system. To be determined are pressure and temperature as a function of composition of reacting gases and the concentration of gases before and after the combustion event. Analyses of gases after the combustion event will be restricted to those tests that had an initial concentration of {le}8% hydrogen. This information will be used to evaluate safety issues related to periodic slurry growth and flammable gas releases from Tank 101-SY. the conditions to be evaluated will simulate gases in the vapor space above the salt cake as well as gases that potentially are trapped in pockets within/under the waste. The deflagration study will relate experimental laboratory results to conditions in the existing tanks.

Cashdollar, K.L.; Zlochower, I.A.; Hertzberg, M.

1991-07-01T23:59:59.000Z

262

Underground Test Area Quality Assurance Project Plan Nevada National Security Site, Nevada, Revision 0  

SciTech Connect

This Quality Assurance Project Plan (QAPP) provides the overall quality assurance (QA) program requirements and general quality practices to be applied to the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office (NNSA/NSO) Underground Test Area (UGTA) Sub-Project (hereafter the Sub-Project) activities. The requirements in this QAPP are consistent with DOE Order 414.1C, Quality Assurance (DOE, 2005); U.S. Environmental Protection Agency (EPA) Guidance for Quality Assurance Project Plans for Modeling (EPA, 2002); and EPA Guidance on the Development, Evaluation, and Application of Environmental Models (EPA, 2009). The QAPP Revision 0 supersedes DOE--341, Underground Test Area Quality Assurance Project Plan, Nevada Test Site, Nevada, Revision 4.

Irene Farnham

2011-05-01T23:59:59.000Z

263

Integrated PEV Charging Solutions and Reduced Energy for Occupant Comfort (Brochure), Vehicle Testing and Integration Facility (VTIF)  

NLE Websites -- All DOE Office Websites (Extended Search)

Vehicle Testing and Integration Facility Vehicle Testing and Integration Facility Integrated PEV Charging Solutions and Reduced Energy for Occupant Comfort Plug-in electric vehicles (PEVs) offer the opportunity to shift transportation energy demands from petroleum to electricity, but broad adoption will require integration with other systems. While automotive experts work to reduce the cost of PEVs, fossil- fueled cars and trucks continue to burn hundreds of billions of gallons of petroleum each year-not only to get from point A to point B, but also to keep passengers comfortable with air condi- tioning and heat. At the National Renewable Energy Laboratory (NREL), three instal- lations form a research laboratory known as the Vehicle Testing and Integration Facility (VTIF). At the VTIF, engineers are develop-

264

HEATER TEST PLANNING FOR THE NEAR SURFACE TEST FACILITY AT THE HANFORD RESERVATION  

E-Print Network (OSTI)

B. C. , 1978. Report on Hydrofracturing Tests for In SituStress Measurements, Near Surface Test Facility, Hole DC-11,Layout for Hanford Near-Surface Test Facility. Submitted to

DuBois, A.

2010-01-01T23:59:59.000Z

265

The 300 Area Integrated Field Research Challenge Quality Assurance Project Plan  

Science Conference Proceedings (OSTI)

Pacific Northwest National Laboratory and a group of expert collaborators are using the U.S. Department of Energy Hanford Site 300 Area uranium plume within the footprint of the 300-FF-5 groundwater operable unit as a site for an Integrated Field-Scale Subsurface Research Challenge (IFRC). The IFRC is entitled Multi-Scale Mass Transfer Processes Controlling Natural Attenuation and Engineered Remediation: An IFRC Focused on the Hanford Site 300 Area Uranium Plume Project. The theme is investigation of multi-scale mass transfer processes. A series of forefront science questions on mass transfer are posed for research that relate to the effect of spatial heterogeneities; the importance of scale; coupled interactions between biogeochemical, hydrologic, and mass transfer processes; and measurements/approaches needed to characterize and model a mass transfer-dominated system. This Quality Assurance Project Plan provides the quality assurance requirements and processes that will be followed by the 300 Area IFRC Project. This plan is designed to be used exclusively by project staff.

Fix, N. J.

2009-04-29T23:59:59.000Z

266

Conceptual design and analysis of a 100-MWe line focus solar central power plant. Test plan  

DOE Green Energy (OSTI)

Plans for a test program are presented whose objectives are: to verify the overall efficiency of a linear parabolic trough solar collector with varied receiver tube subsystem configurations; to compare surface temperatures, and efficiency values to derived values from an analytical model; and to identify the optimal receivr tube and annulus combination as determined by economical, optical, and thermal efficiency. The test facility to be used is described with the aid ofnumerous photographs. The range in conditions under which testing is to be done is briefly described. The instrumentation and measurement plans for the tests are described, and include thermal, flow, and meteorological data. Th data acquisition and processing system is outlined. Means are discussed for calculating efficiency and thermal loss, and requirements for statistical data are given. The test schedule is diagrammed and discussed. (LEW)

Semmens, M.G.; Fong, A.; Collaros, G.J.; Dascher, R.E.; Grassberger, R.E.; Griego, D.B.; Suteber, T.F.

267

iCycle: Integrated, multicriterial beam angle, and profile optimization for generation of coplanar and noncoplanar IMRT plans  

SciTech Connect

Purpose: To introduce iCycle, a novel algorithm for integrated, multicriterial optimization of beam angles, and intensity modulated radiotherapy (IMRT) profiles. Methods: A multicriterial plan optimization with iCycle is based on a prescription called wish-list, containing hard constraints and objectives with ascribed priorities. Priorities are ordinal parameters used for relative importance ranking of the objectives. The higher an objective priority is, the higher the probability that the corresponding objective will be met. Beam directions are selected from an input set of candidate directions. Input sets can be restricted, e.g., to allow only generation of coplanar plans, or to avoid collisions between patient/couch and the gantry in a noncoplanar setup. Obtaining clinically feasible calculation times was an important design criterium for development of iCycle. This could be realized by sequentially adding beams to the treatment plan in an iterative procedure. Each iteration loop starts with selection of the optimal direction to be added. Then, a Pareto-optimal IMRT plan is generated for the (fixed) beam setup that includes all so far selected directions, using a previously published algorithm for multicriterial optimization of fluence profiles for a fixed beam arrangement Breedveld et al.[Phys. Med. Biol. 54, 7199-7209 (2009)]. To select the next direction, each not yet selected candidate direction is temporarily added to the plan and an optimization problem, derived from the Lagrangian obtained from the just performed optimization for establishing the Pareto-optimal plan, is solved. For each patient, a single one-beam, two-beam, three-beam, etc. Pareto-optimal plan is generated until addition of beams does no longer result in significant plan quality improvement. Plan generation with iCycle is fully automated. Results: Performance and characteristics of iCycle are demonstrated by generating plans for a maxillary sinus case, a cervical cancer patient, and a liver patient treated with SBRT. Plans generated with beam angle optimization did better meet the clinical goals than equiangular or manually selected configurations. For the maxillary sinus and liver cases, significant improvements for noncoplanar setups were seen. The cervix case showed that also in IMRT with coplanar setups, beam angle optimization with iCycle may improve plan quality. Computation times for coplanar plans were around 1-2 h and for noncoplanar plans 4-7 h, depending on the number of beams and the complexity of the site. Conclusions: Integrated beam angle and profile optimization with iCycle may result in significant improvements in treatment plan quality. Due to automation, the plan generation workload is minimal. Clinical application has started.

Breedveld, Sebastiaan; Storchi, Pascal R. M.; Voet, Peter W. J.; Heijmen, Ben J. M. [Department of Radiation Oncology, Erasmus MC Rotterdam, Groene Hilledijk 301, 3075 EA Rotterdam (Netherlands)

2012-02-15T23:59:59.000Z

268

Intertechnology Corporation proposed test and evaluation plan, commercial buildings. National Solar Demonstration Program  

DOE Green Energy (OSTI)

This report has three major parts. The first of these derives the requirements for the Test and Evaluation plan from the System Level Plan which is summarized in Section II. The second part contains the proposed plan to fill these requirements and includes hardware and software recommendations as well as procedures and management considerations. Primary emphasis has been given to the remote site because this is the area in which the commercial part of the demonstration is most unique. Finally, some pre-demonstration activities are described. The pilot program is intended to resolve a number of issues which arose in the course of the T and E plan. These relate to choice of scan frequencies, compression algorithms, etc. It is also intended to confirm performance and cost effectiveness of the site data collection package. The base line measurements of attitudes, etc. provide a reference mark against which one can measure the non-technical effectiveness of the demonstration program. (WDM)

None

1976-09-01T23:59:59.000Z

269

Migrating data from TcSE to DOORS : an evaluation of the T-Plan Integrator software application.  

SciTech Connect

This report describes our evaluation of the T-Plan Integrator software application as it was used to transfer a real data set from the Teamcenter for Systems Engineering (TcSE) software application to the DOORS software application. The T-Plan Integrator was evaluated to determine if it would meet the needs of Sandia National Laboratories to migrate our existing data sets from TcSE to DOORS. This report presents the struggles of migrating data and focuses on how the Integrator can be used to map a data set and its data architecture from TcSE to DOORS. Finally, this report describes how the bulk of the migration can take place using the Integrator; however, about 20-30% of the data would need to be transferred from TcSE to DOORS manually. This report does not evaluate the transfer of data from DOORS to TcSE.

Post, Debra S. (Sandia National Laboratories, Livermore, CA); Manzanares, David A.; Taylor, Jeffrey L.

2011-02-01T23:59:59.000Z

270

The effect of an integrated catchment management plan on the greenhouse gas balance of the Mangaotama catchment of the Whatawhata Hill Country Research Station.  

E-Print Network (OSTI)

??An integrated catchment management plan implemented in the Mangaotama catchment of the Whatawhata Research Station in 2001 demonstrated that Pinus radiata forestry on marginal land, (more)

Smiley, Daniel

2012-01-01T23:59:59.000Z

271

Utility Integrated Resource Planning: An Emerging Driver of New Renewable Generation in the Western United States  

E-Print Network (OSTI)

understanding that wind integration costs are manageable,higher levels of wind integration is also critical if windanalysis of wind powers integration costs and capacity

Bolinger, Mark; Wiser, Ryan

2005-01-01T23:59:59.000Z

272

Development and Test Plans for a small Vertical Axis Turbine Designed and  

NLE Websites -- All DOE Office Websites (Extended Search)

Development and Test Plans for a small Vertical Axis Turbine Designed and Development and Test Plans for a small Vertical Axis Turbine Designed and Built by the Russian State Rocket Center under Berkeley Lab auspices Speaker(s): Anthony Radspieler Jr. Glen Dahlbacka Joseph Rasson Date: March 4, 2010 - 12:00pm Location: 90-3122 Berkeley Lab Engineering Division teamed with Empire Magnetics, Rohnert Park and the Makeyev State Rocket Center under a DOE NNSA non-proliferation project to develop and test a series of small wind turbines of vertical axis design. Over the years, about 100 Russian scientists and engineers worked on the project and the hydrodynamic, aerodynamic and mechanical test facilities of the SRC were used. The objective was to create a highly manufacturable Darieus unit with a modest Tip Speed Ratio (quiet and low

273

Underground Test Area Project Waste Management Plan (Rev. No. 2, April 2002)  

Science Conference Proceedings (OSTI)

The U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Operations Office (NNSA/NV) initiated the UGTA Project to characterize the risk posed to human health and the environment as a result of underground nuclear testing activities at the Nevada Test Site (NTS). The UGTA Project investigation sites have been grouped into Corrective Action Units (CAUs) in accordance with the most recent version of the Federal Facility Agreement and Consent Order. The primary UGTA objective is to gather data to characterize the groundwater aquifers beneath the NTS and adjacent lands. The investigations proposed under the UGTA program may involve the drilling and sampling of new wells; recompletion, monitoring, and sampling of existing wells; well development and hydrologic/ aquifer testing; geophysical surveys; and subsidence crater recharge evaluation. Those wastes generated as a result of these activities will be managed in accordance with existing federal and state regulations, DOE Orders, and NNSA/NV waste minimization and pollution prevention objectives. This Waste Management Plan provides a general framework for all Underground Test Area (UGTA) Project participants to follow for the characterization, storage/accumulation, treatment, and disposal of wastes generated by UGTA Project activities. The objective of this waste management plan is to provide guidelines to minimize waste generation and to properly manage wastes that are produced. Attachment 1 to this plan is the Fluid Management Plan and details specific strategies for management of fluids produced under UGTA operations.

IT Corporation, Las Vegas

2002-04-24T23:59:59.000Z

274

Corrective Action Plan for Corrective Action Unit 424: Area 3 Landfill Complex, Tonopah Test Range, Nevada  

SciTech Connect

This corrective action plan provides the closure implementation methods for the Area 3 Landfill Complex, Corrective Action Unit (CAU) 424, located at the Tonopah Test Range. The Area 3 Landfill Complex consists of 8 landfill sites, each designated as a separate corrective action site.

Bechtel Nevada

1998-08-31T23:59:59.000Z

275

Test Plan for Long-Term Operation of a Ten-Cell High Temperature Electrolysis Stack  

DOE Green Energy (OSTI)

This document defines a test plan for a long-term (2500 Hour) test of a ten-cell high-temperature electrolysis stack to be performed at INL during FY09 under the Nuclear Hydrogen Initiative. This test was originally planned for FY08, but was removed from our work scope as a result of the severe budget cuts in the FY08 NHI Program. The purpose of this test is to evaluate stack performance degradation over a relatively long time period and to attempt to identify some of the degradation mechanisms via post-test examination. This test will be performed using a planar ten-cell Ceramatec stack, with each cell having dimensions of 10 cm 10 cm. The specific makeup of the stack will be based on the results of a series of shorter duration ten-cell stack tests being performed during FY08, funded by NGNP. This series of tests was aimed at evaluating stack performance with different interconnect materials and coatings and with or without brazed edge rails. The best performing stack from the FY08 series, in which five different interconnect/coating/edge rail combinations were tested, will be selected for the FY09 long-term test described herein.

James E. O'Brien; Carl M. Stoots; J. Stephen Herring

2008-07-01T23:59:59.000Z

276

ERDA Geothermal Component Test Facility (GCTF), East Mesa, Imperial Valley, California. Test operations management plan  

DOE Green Energy (OSTI)

Discussion of the operation of the Geothermal Component Test Facility (GCTF), established for testing heat extraction and energy conversion equipment and materials, is presented under the following section headings: purposes of the facility; operating policies: service, conflicts, safety and environmental, investigator activities, shops and equipment, and test certification; organization: chart; Lawrence Berkely Laboratory: organization, responsibilities, individual responsibilities, and funding; Bureau of Reclamation: organization, responsibilities, and funding; operations contractor: contract, qualifications, and personnel; Test Operations Advisory Board; experiment processing: test acceptance, scheduling and priorities, cost reimbursement, and activities flow chart.

Not Available

1976-01-01T23:59:59.000Z

277

Integrating Wildlife Crossing into Transportation Plans and Projects in North America  

E-Print Network (OSTI)

Improvement Program (STIP) process? and 3. . . .duringbridges and the long range and STIP transportation plans can

Cramer, Patricia C.; Bissonette, John

2007-01-01T23:59:59.000Z

278

Advanced Nuclear Technology: Final Test Results on 80% Service Test and Implementation Plans  

Science Conference Proceedings (OSTI)

Current practice within the nuclear power industry is to use performance discharge tests for condition monitoring to determine when a battery has reached 80% of its rated capacity, which is considered the end of its service life. A service test is now used every refueling outage to verify that a battery can satisfy its design basis function as defined by the battery duty cycle. A modified performance test is used at ...

2013-04-03T23:59:59.000Z

279

HEATER TEST PLANNING FOR THE NEAR SURFACE TEST FACILITY AT THE HANFORD RESERVATION  

E-Print Network (OSTI)

Heater Experiment at Hanford. Berkeley, Lawre ;e BerkeleyTest Facility, Hole DC-11, Hanford Reservation. Prepared forof Gable Mountain Basalt Cores, Hanford Nuclear Reservation.

DuBois, A.

2010-01-01T23:59:59.000Z

280

CoalFleet RD&D augmentation plan for integrated gasification combined cycle (IGCC) power plants  

SciTech Connect

To help accelerate the development, demonstration, and market introduction of integrated gasification combined cycle (IGCC) and other clean coal technologies, EPRI formed the CoalFleet for Tomorrow initiative, which facilitates collaborative research by more than 50 organizations from around the world representing power generators, equipment suppliers and engineering design and construction firms, the U.S. Department of Energy, and others. This group advised EPRI as it evaluated more than 120 coal-gasification-related research projects worldwide to identify gaps or critical-path activities where additional resources and expertise could hasten the market introduction of IGCC advances. The resulting 'IGCC RD&D Augmentation Plan' describes such opportunities and how they could be addressed, for both IGCC plants to be built in the near term (by 2012-15) and over the longer term (2015-25), when demand for new electric generating capacity is expected to soar. For the near term, EPRI recommends 19 projects that could reduce the levelized cost-of-electricity for IGCC to the level of today's conventional pulverized-coal power plants with supercritical steam conditions and state-of-the-art environmental controls. For the long term, EPRI's recommended projects could reduce the levelized cost of an IGCC plant capturing 90% of the CO{sub 2} produced from the carbon in coal (for safe storage away from the atmosphere) to the level of today's IGCC plants without CO{sub 2} capture. EPRI's CoalFleet for Tomorrow program is also preparing a companion RD&D augmentation plan for advanced-combustion-based (i.e., non-gasification) clean coal technologies (Report 1013221). 7 refs., 30 figs., 29 tabs., 4 apps.

2007-01-15T23:59:59.000Z

Note: This page contains sample records for the topic "integrated test plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


281

THE INTEGRATED EQUIPMENT TEST FACILITY AT OAK RIDGE AS A NONPROLIFERATION TEST LOOP  

Science Conference Proceedings (OSTI)

The apparent renaissance in nuclear power has resulted in a new focus on nonproliferation measures. There is a lot of activity in development of new measurement technologies and methodologies for nonproliferation assessment. A need that is evolving in the United States is for facilities and test loops for demonstration of new technologies. In the late 1970s, the Fuel Recycle Division at Oak Ridge National Laboratory (ORNL) was engaged in advanced reprocessing technology development. As part of the program, the Integrated Equipment Test (IET) facility was constructed as a test bed for advanced technology. The IET was a full-scale demonstration facility, operable on depleted uranium, with a throughput capacity for 0.5 Mt/d. At the front end, the facility had a feed surge vessel, input accountability tank, and feed vessel for the single cycle of solvent extraction. The basic solvent extraction system was configured to use centrifugal contactors for extraction and scrub and a full-size pulsed column for strip. A surge tank received the solvent extraction product solution and fed a continuous operating thermo-syphon-type product evaporator. Product receiving and accountability vessels were available. Feed material could be prepared using a continuous rotary dissolve or by recycling the product with adjustment as new feed. Continuous operations 24/7 could be realized with full chemical recovery and solvent recycle systems in operation. The facility was fully instrumented for process control and operation, and a full solution monitoring application had been implemented for safeguards demonstrations, including actual diversion tests for sensitivity evaluation. A significant effort for online instrument development was a part of the program at the time. The fuel recycle program at Oak Ridge ended in the early 1990s, and the IET facility was mothballed. However, the equipment and systems remain and could be returned to service to support nonproliferation demonstrations. This paper discusses the status of the facility and operations.

Ehinger, Michael H [ORNL

2010-01-01T23:59:59.000Z

282

Computer integrated manufacturing implementation at the Oak Ridge Y-12 Plant: The sixth year of a ten-year plan  

SciTech Connect

The strategic and operational plans for the computer integrated manufacturing (CIM) program in the Y-12 Plant are providing for the evolution of the plant's CIM infrastructure from today's environment to the integrated, highly flexible, and more responsive manufacturing systems planned for the 1990s. The program is committed to meeting the CIM directives established by the US Department of Energy and providing the means by which operations can improve the manufacturing performance of the Y-12 Plant. The plant's CIM program charter is a commitment to coordinating efforts to implement and integrate CIM technologies to improve manufacturing performance and thus significantly enhance the plant's ability to meet current and future manufacturing objectives. To achieve these objectives, CIM technologies are being applied to automate manufacturing processes and information systems. 1 ref., 1 fig.

Bowers, G.L.; Harper, H.E.

1987-10-07T23:59:59.000Z

283

Computer integrated manufacturing implementation at the Oak Ridge Y-12 Plant: The sixth year of a ten-year plan  

SciTech Connect

The strategic and operational plans for the computer integrated manufacturing (CIM) program in the Y-12 Plant are providing for the evolution of the plant's CIM infrastructure from today's environment to the integrated, highly flexible, and more responsive manufacturing systems planned for the 1990s. The program is committed to meeting the CIM directives established by the US Department of Energy and providing the means by which operations can improve the manufacturing performance of the Y-12 Plant. The plant's CIM program charter is a commitment to coordinating efforts to implement and integrate CIM technologies to improve manufacturing performance and thus significantly enhance the plant's ability to meet current and future manufacturing objectives. To achieve these objectives, CIM technologies are being applied to automate manufacturing processes and informations systems.

Davenport, C.M.; Bowers, G.L.

1987-10-07T23:59:59.000Z

284

Demonstration testing and evaluation of in situ soil heating. Management Plan, Revision 2  

SciTech Connect

This is the second revision to the Management Plan for US DOE contract entitled, ``Demonstration Testing and Evaluation of In Situ Soil Heating,`` Contract Number DE-AC05-93OR22160, IITRI Project Number C06787. The cost plan and schedule have been revised herein. The Management Plan was revised once before, in March 1994. In this project IITRI will demonstrate its in situ soil heating and decontamination technology which uses 60 Hz AC power to heat soil to a temperature of about 900C. This technology is aimed at the decontamination of soil by the removal of organic hazardous constituents by the action of heat and a vacuum gas collection system.

Dev, H.

1995-03-06T23:59:59.000Z

285

A hybrid electron and photon IMRT planning technique that lowers normal tissue integral patient dose using standard hardware  

SciTech Connect

Purpose: To present a mixed electron and photon IMRT planning technique using electron beams with an energy range of 6-22 MeV and standard hardware that minimizes integral dose to patients for targets as deep as 7.5 cm. Methods: Ten brain cases, two lung, a thyroid, an abdominal, and a parotid case were planned using two planning techniques: a photon-only IMRT (IMRT) versus a mixed modality treatment (E + IMRT) that includes an enface electron beam and a photon IMRT portion that ensures a uniform target coverage. The electron beam is delivered using a regular cutout placed in an electron cone. The electron energy was chosen to provide a good trade-off between minimizing integral dose and generating a uniform, deliverable plan. The authors choose electron energies that cover the deepest part of PTV with the 65%-70% isodose line. The normal tissue integral dose, the dose for ring structures around the PTV, and the volumes of the 75%, 50%, and 25% isosurfaces were used to compare the dose distributions generated by the two planning techniques. Results: The normal tissue integral dose was lowered by about 20% by the E + IMRT plans compared to the photon-only IMRT ones for most studied cases. With the exception of lungs, the dose reduction associated to the E + IMRT plans was more pronounced further away from the target. The average dose ratio delivered to the 0-2 cm and the 2-4 cm ring structures for brain patients for the two planning techniques were 89.6% and 70.8%, respectively. The enhanced dose sparing away from the target for the brain patients can also be observed in the ratio of the 75%, 50%, and 25% isodose line volumes for the two techniques, which decreases from 85.5% to 72.6% and further to 65.1%, respectively. For lungs, the lateral electron beams used in the E + IMRT plans were perpendicular to the mostly anterior/posterior photon beams, generating much more conformal plans. Conclusions: The authors proved that even using the existing electron delivery hardware, a mixed electron/photon planning technique (E + IMRT) can decrease the normal tissue integral dose compared to a photon-only IMRT plan. Different planning approaches can be enabled by the use of an electron beam directed toward organs at risk distal to the target, which are still spared due the rapid dose fall-off of the electron beam. Examples of such cases are the lateral electron beams in the thoracic region that do not irradiate the heart and contralateral lung, electron beams pointed toward kidneys in the abdominal region, or beams treating brain lesions pointed toward the brainstem or optical apparatus. For brain, electron vertex beams can also be used without irradiating the whole body. Since radiation retreatments become more and more common, minimizing the normal tissue integral dose and the dose delivered to tissues surrounding the target, as enabled by E + IMRT type techniques, should receive more attention.

Rosca, Florin [Department of Radiation Oncology, Massachusetts General Hospital, Danvers, Massachusetts 01923 (United States)

2012-06-15T23:59:59.000Z

286

241-AZ-101 Mixer Pump Demonstration Test Gamma Cart Acceptance Test Procedure and Quality Test Plan (ATP and QTP)  

Science Conference Proceedings (OSTI)

Shop Test of the Gamma Cart System to be used in the AZ-101 Mixer Pump Demonstration Test. Tests hardware and software. This procedure involves testing the Instrumentation involved with the Gamma Cart System, local and remote, including: depth indicators, speed controls, interface to data acquisition software and the raising and lowering functions. This Procedure will be performed twice, once for each Gamma Cart System. This procedure does not test the accuracy of the data acquisition software.

WHITE, D.A.

2000-03-01T23:59:59.000Z

287

241-AZ-101 Mixer Pump Demonstration Test Gamma Cart Acceptance Test Procedure and Quality Test Plan (ATP and QTP)  

SciTech Connect

Shop test of the sludge mobilization cart system to be used in the AZ-101 Mixer Pump Demonstration Test Tests hardware and software. This procedure involves testing the Instrumentation involved with the Gamma Cart System, local and remote, including depth indicators, speed controls, interface to data acquisition software and the raising and lowering functions. This Procedure will be performed twice, once for each Gamma Cart System. This procedure does not test the accuracy of the data acquisition software.

WHITE, D.A.

2000-01-27T23:59:59.000Z

288

Integrating Wind into Transmission Planning: The Rocky Mountain Area Transmission Study (RMATS): Preprint  

DOE Green Energy (OSTI)

Plans to expand the western grid are now underway. Bringing power from low-cost remote resources--including wind--to load centers could reduce costs for all consumers. But many paths appear to be already congested. Locational marginal price-based modeling is designed to identify the most cost-effective paths to be upgraded. The ranking of such paths is intended as the start of a process of political and regulatory approvals that are expected to result in the eventual construction of new and upgraded lines. This paper reviews the necessary data and analytical tasks to accurately represent wind in such modeling, and addresses some policy and regulatory issues that can help with wind integration into the grid. Providing wind fair access to the grid also (and more immediately) depends on tariff and regulatory changes. Expansion of the Rocky Mountain Area Transmission Study (RMATS) study scope to address operational issues supports the development of transmission solutions that enable wind to connect and deliver power in the next few years--much sooner than upgrades can be completed.

Hamilton, R.; Lehr, R.; Olsen, D.; Nielsen, J.; Acker, T.; Milligan, M.; Geller, H.

2004-03-01T23:59:59.000Z

289

Integrated resource planning for local gas distribution companies: A critical review of regulatory policy issues  

SciTech Connect

According to the report, public utility commissions (PUCs) are increasingly adopting, or considering the adoption of integrated resource planning (IRP) for local gas distribution companies (LDCs). The Energy Policy Act of 1992 (EPAct) requires PUCs to consider IRP for gas LDCs. This study has two major objectives: (1) to help PUCs develop appropriate regulatory approaches with regard to IRP for gas LDCs; and (2) to help PUCs respond to the EPAct directive. The study finds that it is appropriate for PUCs to pursue energy efficiency within the traditional regulatory framework of minimizing private costs of energy production and delivery; and PUCs should play a limited role in addressing environmental externalities. The study also finds that in promoting energy efficiency, PUCs should pursue policies that are incentive-based, procompetitive, and sensitive to rate impacts. The study evaluates a number of traditional and nontraditional ratemaking mechanisms on the basis of cost minimization, energy efficiency, competitiveness, and other criteria. The mechanisms evaluated include direct recovery of DSM expenses, lost revenue adjustments for DSM options, revenue decoupling mechanisms, sharing of DSM cost savings, performance-based rate of return for DSM, provision of DSM as a separate service, deregulation of DSM service, price caps, and deregulation of the noncore gas market. The study concludes with general recommendations for regulatory approaches and ratemaking mechanisms that PUCs may wish to consider in advancing IRP objectives.

Harunuzzaman, M.; Islam, M.

1994-08-01T23:59:59.000Z

290

Selenide isotope generator for the Galileo mission. ETG acceptance test plan  

DOE Green Energy (OSTI)

Electrically-Heated Thermoelectric Generators (ETGs) shall be subjected to a flight level acceptance test program to certify the design of the SIG/Galileo flight generator. Each test in the test program is designed to simulate critical conditions and environments associated with generator ground handling, spacecraft launch and in-space operations. Successful completion of the test program shall be evidenced by the satisfactory performance of the ETG during and after the application of the various test environments. The ETG Acceptance Test Plan is designed to specify the testing sequence, the severity of the applied test environments and the acceptance criteria for assessing generator performance. Two test facilities shall be required for the execution of the proposed test program. The Teledyne Energy Systems (TES) facility in Timonium, Maryland shall be the site for the ETG thermal performance evaluation testing; and the Naval Surface Weapons Center (NSWC) facility in White Oak, Maryland, shall be the site of the dynamic, mass-properties and magnetic properties testing.

Not Available

1978-12-01T23:59:59.000Z

291

Thermal Energy Storage Evaluation Program: 1986 annual report. [Economic planning, technical assessment, field tests  

DOE Green Energy (OSTI)

The Thermal Energy Storage Evaluation Program activities were initiated to provide economic planning, technical assessment and field testing support for the thermal energy storage program, as well as management of the overall program for the DOE. Economic planning included two assessment studies. In technical assessment, issues that might affect an assessment were outlined for the development of a standard methodology to conduct assessments; work is underway to establish ''market-based'' cost and performance goals for cool storage technologies in residential applications; planning has begun for investigation of benefits in incorporating aquifer thermal energy storage with heat pumps; and plans are being formulated to evaluate the potential benefit of using aquifer thermal energy storage to augment power plant cooling. Field testing to develop technologies for the recovery and reuse of industrial waste heat began with the instrumentation design for the ceramic/salt matrix in an operating brick-making plant. Work in advanced studies by Lawrence Berkeley Laboratory continued on thermochemical conversion and storage using small particles as the heat exchanger catalyst. In SO/sub 3/ dissociation experiments at 645/sup 0/C using light and dark conditions, results clearly demonstrated the benefit in directly radiantly heating the catalyst to accomplish the endothermic step of a thermochemical storage reaction.

Drost, M.K.; Bates, J.M.; Brown, D.R.; Weijo, R.O.

1987-07-01T23:59:59.000Z

292

Current status of the Run-Beyond-Cladding Breach (RBCB) tests for the Integral Fast Reactor (IFR). Metallic Fuels Program  

Science Conference Proceedings (OSTI)

This paper describes the results from the Integral Fast Reactor (IFR) metallic fuel Run-Beyond-Cladding-Breach (RBCB) experiments conducted in the Experimental Breeder Reactor II (EBR-II). Included in the report are scoping test results and the data collected from the prototypical tests as well as the exam results and discussion from a naturally occurring breach of one of the lead IFR fuel tests. All results showed a characteristic delayed neutron and fission gas release pattern that readily allows for identification and evaluation of cladding breach events. Also, cladding breaches are very small and do not propagate during extensive post breach operation. Loss of fuel from breached cladding was found to be insignificant. The paper will conclude with a brief description of future RBCB experiments planned for irradiation in EBR-II.

Batte, G.L.; Pahl, R.G. [Argonne National Lab., Idaho Falls, ID (United States); Hofman, G.L. [Argonne National Lab., IL (United States)

1993-09-01T23:59:59.000Z

293

INTEGRATED FIELD TESTING OF FUEL CELLS AND MICRO-TURBINES  

DOE Green Energy (OSTI)

This is a report of the Phase I effort for this project, which is to conduct a technical and economic evaluation of the prospects for the deployment of DG on Long Beach Island. The work in this phase consists of five tasks: (1) Circuit data compilation and model development, (2) Development of the base case, (3) Development of the alternative cases, (4) Technical evaluations through a comprehensive power flow analysis, and (5) Economic analysis of the various cases over a 10-year planning horizon. Each of these tasks has been completed and the results are presented in this report along with pertinent details of some of the key analysis.

Unknown

2002-02-28T23:59:59.000Z

294

Geopressured-Geothermal Drilling and Testing Plan, Volume II, Testing Plan; Dow Chemical Co. - Dept. of Energy Dow-DOE Sweezy No. 1 Well, Vermilion Parish, Louisiana  

DOE Green Energy (OSTI)

The Dow/D.O.E. L. R. Sweezy No. 1 geopressured geothermal production well was completed in August of 1981. The well was perforated and gravel packed in approximately 50 feet of sand from 13,344 feet to 13,395 feet. Permeabilities of 6 to 914 millidarcies were measured with porosity of 25 to 36%. Static surface pressure after well clean-up was 5000 psi. At 1000 B/D flow rate the drawdown was 50 psi. The water produced in clean-up contained 100,000 ppm TDS. This report details the plan for testing this well with the goal of obtaining sufficient data to define the total production curve of the small, 939 acre, reservoir. A production time of six to nine months is anticipated. The salt water disposal well is expected to be completed and surface equipment installed such that production testing will begin by April 1, 1982. The program should be finished and reports written by February 28, 1983. The brine will be produced from the No.1 well, passed through a separator where the gas is removed, then reinjected into the No.2 (SWD) well under separator pressure. Flow rates of up to 25,000 B/D are expected. The tests are divided into a two-week short-term test and six to nine-month long-term tests with periodic downhole measurement of drawdown and buildup rates. Data obtained in the testing will be relayed by phoneline computer hookup to Otis Engineering in Dallas, Texas, where the reservoir calculations and modeling will be done. At the point where sufficient data has been obtained to reach the objectives of the program, production will be ended, the wells plugged and abandoned, and a final report will be issued.

None

1982-02-01T23:59:59.000Z

295

Application of pressure and pressure integral functions for the analysis of well test data  

E-Print Network (OSTI)

The analysis of well test data by methods which only use the pressure change can be ambiguous, and analysis using the derivative of the pressure change is often distorted by random error in the data or data noise. Although various "smoothing" techniques have been used to reduce data noise, some concern exists that smoothing procedures may alter the basic character of the data. In this work, we use pressure integral and pressure integral derivative functions to reduce the data noise. First, we perform the conventional semilog analysis on the well test data using the pressure integral functions. Then, we demonstrate the applicability of the pressure change integral and derivative of pressure change integral functions. In this manner we couple the integral functions with the pressure change and pressure change derivative functions to derive useful qualitative and quantitative information from these test data. We also analyze well test data with these methods without the use of superposition time functions such as, Horner time and Agarwal "effective time" functions. In addition, we introduce a numerical technique to generate the pressure integral functions. Thus, we integrate the pressure analysis approach with the pressure integral analysis approach and develop a consistent and applicable method for the analysis of well test data.

Samad, Zahid

1994-01-01T23:59:59.000Z

296

Test Plan for Heat Cycle Research Program, Phase I Supercritical Cycle Tests  

DOE Green Energy (OSTI)

The 60 kW Heat Cycle Research Facility (HCRF) provides a means of examining different concepts and components associated with the generation of electrical power from a geothermal resource using a binary power cycle. In this power cycle the heat or energy in a hot geothermal fluid is transferred to a secondary working fluid. This working fluid is vaporized in the heat exchange process and the vapor is in turn expanded through a turbine which drives a generator producing electrical power. the heat or energy in the vapor leaving the turbine is transferred to a circulating cooling water in the condenser where the working fluid is condensed to a liquid which can be pumped back to the heaters, completing the cycle. This waste heat load in the condenser is in turn transferred from the cooling water to the atmosphere in a cooling tower. The HCRF allows the different components described in the cycle above to be tested as well as the basic cycle itself. This cycle may vary in that the heaters, condenser, cooling system, pumps, etc. may differ in number and type, however the basic cycle does not change significantly. During this sequence of tests, the HCRF is operated using a supercritical vapor generator and a vertical condenser where the condensation occurs inside of the tubes as opposed to the shell side more commonly used in these applications. In addition to providing the data to be used to evaluate the design of these heat exchangers, these supercritical tests provide cycle and component performance data with both single component working fluids and working fluids comprised of different mixtures of hydrocarbons. The use of these mixtures promises to improve cycle performance, in terms of watt-hours per pound of geothermal fluid, provided the countercurrent flow paths can be maintained between the fluids in both the condenser and the heaters. The supercritical heaters and the condenser to be used in this series of tests were designed to provide the desired countercurrent flow paths.

Mines, Greg L.

1983-06-01T23:59:59.000Z

297

Corrective action investigation plan for CAU Number 453: Area 9 Landfill, Tonopah Test Range  

SciTech Connect

This Corrective Action Investigation Plan (CAIP) contains the environmental sample collection objectives and criteria for conducting site investigation activities at the Area 9 Landfill, Corrective Action Unit (CAU) 453/Corrective Action (CAS) 09-55-001-0952, which is located at the Tonopah Test Range (TTR). The TTR, included in the Nellis Air Force Range, is approximately 255 kilometers (140 miles) northwest of Las Vegas, Nevada. The Area 9 Landfill is located northwest of Area 9 on the TTR. The landfill cells associated with CAU 453 were excavated to receive waste generated from the daily operations conducted at Area 9 and from range cleanup which occurred after test activities.

NONE

1997-05-14T23:59:59.000Z

298

New York City Energy-Water Integrated Planning: A Pilot Study  

Science Conference Proceedings (OSTI)

The New York City Energy-Water Integrated Planning Pilot Study is one of several projects funded by Sandia National Laboratories under the U.S. Department of Energy Energy-Water Nexus Program. These projects are intended to clarify some key issues and research needs identified during the Energy-Water Nexus Roadmapping activities. The objectives of the New York City Pilot Project are twofold: to identify energy-water nexus issues in an established urban area in conjunction with a group of key stakeholders and to define and apply an integrated energy and water decision support tool, as proof-of-concept, to one or more of these issues. During the course of this study, the Brookhaven National Laboratory project team worked very closely with members of a Pilot Project Steering Committee. The Steering Committee members brought a breadth of experience across the energy, water and climate disciplines, and all are well versed in the particular issues faced by an urban environment, and by New York City in particular. The first task was to identify energy-water issues of importance to New York City. This exercise was followed by discussion of the qualities and capabilities that an ideal decision support tool should display to address these issues. The decision was made to start with an existing energy model, the New York City version of the MARKAL model, developed originally at BNL and now used globally by many groups for energy analysis. MARKAL has the virtue of being well-vetted, transparent, and capable of calculating 'material' flows, such as water use by the energy system and energy requirements of water technology. The Steering Committee members defined five scenarios of interest, representing a broad spectrum of New York City energy-water issues. Brookhaven National Laboratory researchers developed a model framework (Water-MARKAL) at the desired level of detail to address the scenarios, and then attempted to gather the New York City-specific information required to analyze the scenarios using Water-MARKAL. This report describes the successes and challenges of defining and demonstrating the decision tool, Water-MARKAL. The issues that the stakeholders perceive for New York City are listed and the difficulties in gathering required information for Water-MARKAL to analyze these issues at the desired level of detail are described.

Bhatt,V.; Crosson, K. M.; Horak, W.; Reisman, A.

2008-12-16T23:59:59.000Z

299

Aircraft Integration and Flight Testing of 4STAR  

SciTech Connect

Under funding from the U.S. Dept. of Energy, in conjunction with a funded NASA 2008 ROSES proposal, with internal support from Battelle Pacific Northwest Division (PNWD), and in collaboration with NASA Ames Research Center, we successfully integrated the Spectrometer for Sky-Scanning, Sun-Tracking Atmospheric Research (4STAR-Air) instrument for flight operation aboard Battelles G-1 aircraft and conducted a series of airborne and ground-based intensive measurement campaigns (hereafter referred to as intensives) for the purpose of maturing the initial 4STAR-Ground prototype to a flight-ready science-ready configuration.

Flynn, CJ; Kassianov, E; Russell, P; Redemann, J; Dunagan, S; Holben, B

2012-10-12T23:59:59.000Z

300

Assembly and method for testing the integrity of stuffing tubes  

DOE Patents (OSTI)

A stuffing tube integrity checking assembly includes first and second annular seals, with each seal adapted to be positioned about a stuffing tube penetration component. An annular inflation bladder is provided, the bladder having a slot extending longitudinally there along and including a separator for sealing the slot. A first valve is in fluid communication with the bladder for introducing pressurized fluid to the space defined by the bladder when mounted about the tube. First and second releasible clamps are provided. Each clamp assembly is positioned about the bladder for securing the bladder to one of the seals for thereby establishing a fluid-tight chamber about the tube.

Morrison, E.F.

1996-12-31T23:59:59.000Z

Note: This page contains sample records for the topic "integrated test plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


301

Issues and methods in incorporating environmental externalities into the integrated resource planning process  

Science Conference Proceedings (OSTI)

This report is a review of current practices and policies in considering environmental externalities in the integrated resource planning and performance based regulation (IRP/PBR) process. The following issues are presented and examined: What are the pros and cons of treating environmental externalities in the IRP process? How are potential future environmental regulations being treated? Are externalities being qualitatively or quantitatively considered, or monetized? Are offsets being allowed? How are externality policies being coordinated among different levels and branches of governments? Should environmental externalities be considered in dispatching a utility`s existing resources? What are the procedures for addressing uncertainty in incorporating environmental externalities into IRP? How are externalities valued? What are other approaches to addressing environmental externalities. This report describes seven major approaches for addressing environmental externalities in the IRP process: qualitative treatment, weighting and ranking, cost of control, damage function, percentage adders, monetization by emission, and multiattribute trade-off analysis. The discussion includes a taxonomy of the full range of alternative methods for addressing environmental externalities, a summary of state PUC actions, the role of state laws, the debate on environmental adders, and the choice of methodologies. In addition, this report characterizes the interests of stakeholders such as the electric industry, fuel suppliers, energy consumers, governmental agencies, public interest groups, consultants, and others. It appears that the views, positions, and interests of these stakeholders are affected by their perceptions of the potential impacts on their economic interests or the viability of their position on environmental policy, by the societal perspective they take, and by the orientation of the analysts toward market competition and their respective accumulated expertise.

Fang, J.M.; Galen, P.S.

1994-11-01T23:59:59.000Z

302

Test Plan for Characterization Testing of SO2-depolarized Electrolyzer Cell Designs  

DOE Green Energy (OSTI)

SRNL received funding in FY 2005 to test the Hybrid Sulfur (HyS) Process for generating hydrogen. This technology employs an electrolyzer that uses a sulfur dioxide depolarized anode to greatly reduce the electrical energy requirement. The required current is the same as for conventional electrolysis of water, but the required cell voltage is reduced. The electrolyzer is a key part of HyS technology. Completing the material loop for HyS requires a high temperature decomposition of sulfuric acid to regenerate the sulfur dioxide gas needed for the anode reaction. Oxygen is also produced and could be sold. The decomposition of sulfuric acid is being studied by others in a separately funded task. It is not included in this SRNL task.

Steimke, J. L.

2006-02-15T23:59:59.000Z

303

Integrating Habitat Fragmentation Analysis into Transportation Planning Using the Effective Mesh Size Landscape Metric  

E-Print Network (OSTI)

due to planned future transportation projects (Thorne et al.impact of these future transportation projects on habitatthe effects of transportation infrastructure. In the future,

Girvetz, Evan H; Thorne, James H.; Berry, Alison M; Jaeger, Jochen A.G.

2007-01-01T23:59:59.000Z

304

Utility Integrated Resource Planning: An Emerging Driver of New Renewable Generation in the Western United States  

E-Print Network (OSTI)

Risk: The Treatment of Renewable Energy in Western UtilityEmerging Driver of New Renewable Generation in the WesternEnergy Efficiency and Renewable Energy (Office of Planning,

Bolinger, Mark; Wiser, Ryan

2005-01-01T23:59:59.000Z

305

Resource Conservation and Recovery Act Industrial Sites quality assurance project plan: Nevada Test Site, Nevada  

SciTech Connect

This quality assurance project plan (QAPjP) describes the measures that shall be taken to ensure that the environmental data collected during characterization and closure activities of Resource Conservation and Recovery Act (RCRA) Industrial Sites at the Nevada Test Site (NTS) are meaningful, valid, defensible, and can be used to achieve project objectives. These activities are conducted by the US Department of Energy Nevada Operations Office (DOE/NV) under the Nevada Environmental Restoration (ER) Project. The Nevada ER Project consists of environmental restoration activities on the NTS, Tonopah Test Range, Nellis Air Force Range, and eight sites in five other states. The RCRA Industrial Sites subproject constitutes a component of the Nevada ER Project. Currently, this QAPjP is limited to the seven RCRA Industrial Sites identified within this document that are to be closed under an interim status and pertains to all field-investigation, analytical-laboratory, and data-review activities in support of these closures. The information presented here supplements the RCRA Industrial Sites Project Management Plan and is to be used in conjunction with the site-specific subproject sampling and analysis plans.

Not Available

1994-06-01T23:59:59.000Z

306

Original article: Bootstrap tests for fractional integration and cointegration: A comparison study  

Science Conference Proceedings (OSTI)

There are few methods in the literature to test for integration and cointegration in the traditional framework, i.e. using the I(0)-I(1) paradigm. In the first case, the most known are the Dickey-Fuller (DF), the Augmented Dickey-Fuller (ADF) and the ... Keywords: ARFIMA model, Bootstrap, Classical unit root tests, EG and Johansen tests, Semiparametric estimator

G. C. Franco; V. A. Reisen; F. A. Alves

2013-01-01T23:59:59.000Z

307

ENERGY SMART SCHOOLS APPLIED RESEARCH, FIELD TESTING, AND TECHNOLOGY INTEGRATION  

SciTech Connect

This multi-state collaborative project brings together federal, state, and private sector resources in order to move the design and use of high-performance energy technologies in schools to the forefront. NASEO and its contractors continue to make progress on completion of the statement of work. The high watermark for this period is the installation and operation of the micro-turbine in the Canton School District. The school is pleased to begin the monitoring phase of the project and looks forward to a ribbon cutting this Spring. The other projects continue to move forward and NYSERDA has now begun work in earnest. We expect the NASEO/NYSERDA workshop sometime this Spring as well. By the time the next Annual Technical Progress Report is submitted, we plan to have finished all of the work. The next year should be filled with dissemination of information to interested parties on the success of the project in an effort to get others to duplicate the high performance, and energy smart schools initiatives. We expect all of the deliverables to be completed with the possible exception of the high-performance schools retrofits in California. We expect that 2 of the 3 campuses undergoing retrofits will be complete and the third will be nearly complete. All other activities are on schedule for 10/1/03 completion at this time.

Frank Bishop

2003-04-01T23:59:59.000Z

308

Evaluation of Integrated High Temperature Component Testing Needs  

Science Conference Proceedings (OSTI)

This paper describes the requirements for a large-scale component test capability to support the development of advanced nuclear reactor technology and their adaptation to commercial applications that advance U.S. energy economy, reliability, and security and reduce carbon emissions.

Rafael Soto; David Duncan; Vincent Tonc

2009-05-01T23:59:59.000Z

309

Demonstration testing and evaluation of in situ soil heating: Management Plan  

Science Conference Proceedings (OSTI)

This document is the Management Plan for US DOE contract entitled, {open_quotes}Demonstration, Testing and Evaluation of In Situ Soil Heating,{close_quotes} Contract No. DE-AC05-93OR22160, IITRI Project No. C06787. In this project IITRI will demonstrate an in situ soil heating technology for the removal of hazardous organic contaminants present in the soil. In situ heating will be accomplished by the application of 60 Hz ac power to the soil. The soil will be heated to a temperature of about 90{degrees}C. This technology is suited for the removal of those organic compounds which have a normal boiling point in the range of 100{degrees} to 210{degrees}C, or else for those which exhibit a pure component vapor pressure of at least 10 mm Hg in the 90{degrees} to 100{degrees}C temperature range. For example, perchloroethylene, dichlorobenzene, trichlorobenzene, etc. may be removed by in situ ac heating. It is planned to demonstrate the technology by heating approximately 400 tons of soil in the K-1070 Classified Burial Ground located at DOE`s K-25 Site located in Oak Ridge, TN. It is estimated that the heating portion of the demonstration will take approximately 3 weeks at an average power input rate of 150 to 175 kW. IITRI expects to spend considerable time in the front end reviewing site characteristics, preparing detail design, developing Health and Safety Plans and other documents needed to obtain regulatory approval for the demonstration, arranging for site sampling, infrastructure development and document preparation. It is anticipated that site activities will begin in approximately 5 to 6 months. This contract was signed on September 30, 1993. IITRI started work on it in October 1993. It is planned to complete the demonstration and submit approved final reports by September 30, 1994. This project has 12 tasks and four major milestones. The major milestones and their planned completion dates are shown.

Dev, H.

1993-12-31T23:59:59.000Z

310

DOE/NETL's Phase II Plans for Full-Scale Mercury Removal Technology Field-Testing  

NLE Websites -- All DOE Office Websites (Extended Search)

Phase II Plans for Full-Scale Phase II Plans for Full-Scale Mercury Removal Technology Field-Testing Air Quality III September 12, 2002 Arlington, Va Scott Renninger, Project Manager for Mercury Control Technology Enviromental Projects Division Presentation Outline * Hg Program goals & objectives * Focus on Future Hg control R&D * Q&As President Bush's Clear Skies Initiative Current Mid-Term 2008-2010 2018 SO 2 11 million tons 4.5 million tons 3 million tons NOx 5 million tons 2.1 million tons 1.7 million tons Mercury 48 tons 26 tons 15 tons Annual U.S. Power Plant Emissions Mercury Control * Developing technologies ready for commercial demonstration: - By 2005, reduce emissions 50-70% - By 2010, reduce emissions by 90% - Cost 25-50% less than current estimates 2000 Year 48 Tons $2 - 5 Billion @ 90% Removal w/Activated

311

Test Plan to Evaluate the Relationship Among IAQ, Comfort, Moisture, and Ventilation in Humid Climates  

Science Conference Proceedings (OSTI)

This experimental plan describes research being conducted by Pacific Northwest National Laboratory (PNNL), in coordinatation with Florida Solar Energy Center (FSEC), Florida HERO, and Lawrence Berkeley National Laboratory (LBNL) to evaluate the impact of ventilation rate on interior moisture levels, temperature distributions, and indoor air contaminant concentrations. Specifically, the research team will measure concentrations of indoor air contaminants, ventilation system flow rates, energy consumption, and temperature and relative humidity in ten homes in Gainesville, FL to characterize indoor pollutant levels and energy consumption associated with the observed ventilation rates. PNNL and FSEC have collaboratively prepared this experimental test plan, which describes background and context for the proposed study; the experimental design; specific monitoring points, including monitoring equipment, and sampling frequency; key research questions and the associated data analysis approach; experimental logistics, including schedule, milestones, and team member contact information; and clearly identifies the roles and responsibilities of each team in support of project objectives.

Widder, Sarah H.; Martin, Eric

2013-03-15T23:59:59.000Z

312

Detailed technical plan for Test Program Element-III (TPE-III) of the first wall/blanket shield engineering test program  

Science Conference Proceedings (OSTI)

The experimental requirements, test-bed design, and computational requirements are reviewed and updated. Next, in Sections 3, 4 and 5, the experimental plan, instrumentation, and computer plan, respectively, are described. Finally, Section 6 treats other considerations, such as personnel, outside participation, and distribution of results.

Turner, L.R.; Praeg, W.F.

1982-03-01T23:59:59.000Z

313

Wave Tank Testing and Model Validation … An Integrated Approach  

NLE Websites -- All DOE Office Websites (Extended Search)

Wave Tank Testing and Model Validation - Lessons Learned Wave Tank Testing and Model Validation - Lessons Learned Mirko Previsic 7-7-12 2 Representing the Full-Scale System P, V qv q T u q Generator Guide vanes Turbine Blades Configuration 3 Appropriate Modeling of Physics Run-time is important to make a model useful as an engineering and/or optimization tool. * Have to be selective about how the physics is represented in the model * Different physical phenomena are important to different WEC devices Subscale modeling allows to help us understand and validate the models physics. * Ideally we can isolate physical phenomena to properly debug theoretical model * Focus is on validating fluid-structure interaction * Scaling of mechanical systems needs to represent the physics of the full- scale system (i.e. mooring, power-take-off, control system).

314

Testing and evaluation aspects of integration of unmanned air systems into the national air space  

Science Conference Proceedings (OSTI)

Current developments show that the integration of Unmanned Aerial Systems (UAS) into the National Airspace System (NAS) is a process that will inevitably happen. Arguably, it may be viewed as one of the key milestones in the history of aviation. Whereas ... Keywords: NAS integration, modeling and simulation, test and evaluation, unmanned aerial systems, verification and validation

Mauricio Castillo-Effen; Nikita Visnevski

2010-09-01T23:59:59.000Z

315

Develop Standard Method of Test for Integrated Heat Pumps Research Project  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Develop Standard Method of Test for Develop Standard Method of Test for Integrated Heat Pumps Research Project Develop Standard Method of Test for Integrated Heat Pumps Research Project The U.S. Department of Energy is currently conducting research into the development of standard Method of Test (MOT) for integrated heat pumps (IHPs). No active, recognized test procedure or rating standard exists for IHPs. Generating a rating standard with supporting test procedure that is approved by the American Society of Heating, Refrigerating, and Air Conditioning (ASHRAE) and the Air Conditioning, Heating, and Refrigeration Institute (AHRI) is necessary for these products to be viably marketed. The primary market segment for IHPs is residential buildings, both single-family and small, low-rise multifamily dwellings.

316

Integrating preference analysis and balanced scorecard to product planning house of quality  

Science Conference Proceedings (OSTI)

Product planning house of quality (PPHOQ) is of fundamental and strategic importance in quality function deployment (QFD). Determining the aggregated priority ratings (PRs) of engineering characteristics (ECs) is a crucial step of constructing PPHOQ. ... Keywords: Balanced scorecard, Engineering characteristic, Priority rating, Product planning house of quality, Quality function deployment

Yan-Lai Li; Min Huang; Kwai-Sang Chin; Xing-Gang Luo; Yi Han

2011-03-01T23:59:59.000Z

317

Survey and analysis of multimodal sensor planning and integration for wide area surveillance  

Science Conference Proceedings (OSTI)

Although sensor planning in computer vision has been a subject of research for over two decades, a vast majority of the research seems to concentrate on two particular applications in a rather limited context of laboratory and industrial workbenches, ... Keywords: Sensor planning, cooperative sensing, multimodal sensing, persistent surveillance, threat object recognition, ubiquitous surveillance, wireless sensor network

Besma R. Abidi; Nash R. Aragam; Yi Yao; Mongi A. Abidi

2008-12-01T23:59:59.000Z

318

Design and component integration of a T63-A-700 gas turbine engine test facility ; .  

E-Print Network (OSTI)

??A gas turbine engine test cell was developed integrating an Allison T63-A-700 helicopter engine with a superflow water brake dynamometer power absorber. Design specifications were (more)

Eckerle, Brian P.

1995-01-01T23:59:59.000Z

319

Coordinating, integrating, and synchronizing disaster response : use of an emergency response synchronization matrix in emergency planning, exercises, and operations.  

SciTech Connect

The Chemical Stockpile Emergency Preparedness (CSEP) Program is a wide-ranging activity in support of a national initiative involving the U.S. Army Chemical Materiel Command (CMA), the Federal Emergency Management Agency (FEMA), 9 states, and 37 counties. Established in 1988, the CSEP Program enhances emergency planning for the unlikely event of a release of hazardous chemical weapons agent from one of the Army's chemical weapons storage installations currently storing chemical weapons. These obsolete weapons are scheduled to be destroyed; meanwhile, however, they pose a threat to installation workers and residents of the surrounding communities. Argonne's CSEP Program includes a variety of components that serve the needs of multiple program participants. Among the major activities are: (1) Development of the Emergency Planning Synchronization Matrix to facilitate integration of multi-jurisdictional emergency plans: (a) Coordinating, Integrating, and Synchronizing Disaster Response: Use of an Emergency Response Synchronization Matrix in Emergency Planning, Exercises, and Operations. A graphical depiction of the entire emergency response process via a synchronization matrix is an effective management tool for optimizing the design, exercise, and real-life implementation of emergency plans. This system-based approach to emergency planning depicts how a community organizes its response tasks across space and time. It gives responders the opportunity to make real-time adjustments to maximizing the often limited resources in protecting area residents. An effective response to any natural or technological hazard must involve the entire community and must not be limited by individual jurisdictions and organizations acting on their own without coordination, integration, and synchronization. An emergency response to an accidental release of chemical warfare agents from one of this nation's eight chemical weapons stockpile sites, like any other disaster response, is complex. It requires the rapid coordination, integration, and synchronization of multiple levels of governmental and nongovernmental organizations from numerous jurisdictions, each with varying response capabilities, into a unified community response. The community response actions occur in an area extending from an on-site storage location to points 25 or more miles away. Actions are directed and controlled by responding local governments and agencies situated within the response area, as well as by state and federal operations centers quite removed from the area of impact. Time is critical and the protection action decision-making process is greatly compressed. To ensure an effective response with minimal confusion, given the potential catastrophic nature of such releases, the response community must carefully synchronize response operations.

Hewett, P. L., Jr.; Mitrani, J. E.; Metz, W. C.; Vercellone, J. J.; Decision and Information Sciences

2001-11-01T23:59:59.000Z

320

Measuring and Testing Equipment Assessment plan - Developed By NNSA/Nevada Site Office Facility Representative Division  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Measuring and Test Equipment Measuring and Test Equipment Assessment Plan NNSA/Nevada Site Office Independent Oversight Division Performance Objective: The objective of this assessment is to determine whether a program is in place which assures that Measuring and Test Equipment (M&TE) used in activities affecting quality and safety are properly controlled, calibrated, and adjusted at specified times to maintain accuracy within necessary limits. Criteria: All M&TE is uniquely identified, calibrated, controlled, and provides accuracy traceability. A recall program maintains the total inventory and status of all M&TE. Out-of-tolerance M&TE is removed from service. Plant equipment calibrated with out-of-tolerance M&TE is evaluated in a timely manner for impact on previous output, current operability and is re-

Note: This page contains sample records for the topic "integrated test plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


321

Measuring and Testing Equipment Assessment plan - Developed By NNSA/Nevada Site Office Facility Representative Division  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Measuring and Test Equipment Measuring and Test Equipment Assessment Plan NNSA/Nevada Site Office Independent Oversight Division Performance Objective: The objective of this assessment is to determine whether a program is in place which assures that Measuring and Test Equipment (M&TE) used in activities affecting quality and safety are properly controlled, calibrated, and adjusted at specified times to maintain accuracy within necessary limits. Criteria: All M&TE is uniquely identified, calibrated, controlled, and provides accuracy traceability. A recall program maintains the total inventory and status of all M&TE. Out-of-tolerance M&TE is removed from service. Plant equipment calibrated with out-of-tolerance M&TE is evaluated in a timely manner for impact on previous output, current operability and is re-

322

Quality Assurance Program Plan for TRUPACT-II Gas Generation Test Program  

Science Conference Proceedings (OSTI)

The Gas Generation Test Program (GGTP), referred to as the Program, is designed to establish the concentration of flammable gases and/or gas generation rates in a test category waste container intended for shipment in the Transuranic Package Transporter-II (TRUPACT-II). The phrase "gas generationtesting" shall refer to any activity that establishes the flammable gas concentration or the flammable gas generation rate. This includes, but is not limited to, measurements performed directly on waste containers or during tests performed on waste containers. This Quality Assurance Program Plan (QAPP) documents the quality assurance (QA) and quality control (QC) requirements that apply to the Program. The TRUPACT-II requirements and technical bases for allowable flammable gas concentration and gas generation rates are described in the TRUPACT-II Authorized Methods for Payload Control (TRAMPAC).

Carlsbad Field Office

2002-03-01T23:59:59.000Z

323

Status and Plans for an SRF Accelerator Test Facility at Fermilab  

SciTech Connect

A superconducting RF accelerator test facility is currently under construction at Fermilab. The accelerator will consist of an electron gun, 40 MeV injector, beam acceleration section consisting of 3 TTF-type or ILC-type cryomodules, and multiple downstream beam lines for testing diagnostics and performing beam experiments. With 3 cryomodules installed this facility will initially be capable of generating an 810 MeV electron beam with ILC beam intensity. The facility can accommodate up to 6 cryomodules for a total beam energy of 1.5 GeV. This facility will be used to test SRF cryomodules under high intensity beam conditions, RF power equipment, instrumentation, and LLRF and controls systems for future SRF accelerators such as the ILC and Project-X. This paper describes the current status and overall plans for this facility.

Church, M.; Leibfritz, J.; Nagaitsev, S.; /Fermilab

2011-07-29T23:59:59.000Z

324

Evaluation of Packaging Film Mechanical Integrity Using a Standardized Scratch Test  

E-Print Network (OSTI)

Polymeric packaging films see widespread use in the food packaging industry, and their mechanical integrity is paramount to maintaining product appearance, freshness, and overall food safety. Current testing methods, such as tensile or puncture tests, do not necessarily correlate well with field damages that are observed to be scratch-like. The standardized linearly increasing load scratch test is investigated as a new means of evaluating the mechanical integrity of packaging films. Mechanical clamp and vacuum fixtures were considered for securing the films to a set of backing materials and tested under various testing rates and film orientation conditions. Film performance was evaluated according to their puncture load. Based on the above study, the vacuum fixture offers the most consistent and meaningful results by providing a more intimate contact between film and backing and minimizing uncontrolled buckling of the film during testing. Additional testing was also carried out on a commercial film to confirm similarity between damage observed in the scratched films and that from the field. The scratch test gives good correlation between field performance and scratch test results on a set of commercial films. The usefulness of the scratch test methodology for packaging film mechanical integrity evaluation is discussed. Scratch-induced damages on multi-layer commercial packaging films are investigated using cross- and longitudinal-sectioning. Scratch test results show clear distinction between the two tested systems on both the inside and outside surfaces. Microscopy was performed to investigate the feasibility of utilizing this methodology as a tool for packaging film structure evaluation by determining the effect each layer has on the resistance of scratch damages. It is shown that the film showing superior scratch test results also shows significantly better stress distribution through its layers during the scratch test, as well as better layer adhesion during severe deformation. The scratch test shows good ability to provide more in-depth film mechanical integrity testing by allowing for layer-by-layer analysis of damages and layer adhesion after testing.

Hare, Brian

2011-08-01T23:59:59.000Z

325

HWMA/RCRA CLOSURE PLAN FOR THE MATERIALS TEST REACTOR WING (TRA-604) LABORATORY COMPONENTS VOLUNTARY CONSENT ORDER ACTION PLAN VCO-5.8 D REVISION2  

SciTech Connect

This Hazardous Waste Management Act/Resource Conservation and Recovery Act closure plan was developed for the laboratory components of the Test Reactor Area Catch Tank System (TRA-630) that are located in the Materials Test Reactor Wing (TRA-604) at the Reactor Technology Complex, Idaho National Laboratory Site, to meet a further milestone established under Voluntary Consent Order Action Plan VCO-5.8.d. The TRA-604 laboratory components addressed in this closure plan were deferred from the TRA-630 Catch Tank System closure plan due to ongoing laboratory operations in the areas requiring closure actions. The TRA-604 laboratory components include the TRA-604 laboratory warm wastewater drain piping, undersink drains, subheaders, and the east TRA-604 laboratory drain header. Potentially contaminated surfaces located beneath the TRA-604 laboratory warm wastewater drain piping and beneath the island sinks located in Laboratories 126 and 128 (located in TRA-661) are also addressed in this closure plan. The TRA-604 laboratory components will be closed in accordance with the interim status requirements of the Hazardous Waste Management Act/Resource Conservation and Recovery Act as implemented by the Idaho Administrative Procedures Act 58.01.05.009 and 40 Code of Federal Regulations 265, Subparts G and J. This closure plan presents the closure performance standards and the methods for achieving those standards.

KIRK WINTERHOLLER

2008-02-25T23:59:59.000Z

326

Uncertainty Quantification of Hypothesis Testing for the Integrated Knowledge Engine  

SciTech Connect

The Integrated Knowledge Engine (IKE) is a tool of Bayesian analysis, based on Bayesian Belief Networks or Bayesian networks for short. A Bayesian network is a graphical model (directed acyclic graph) that allows representing the probabilistic structure of many variables assuming a localized type of dependency called the Markov property. The Markov property in this instance makes any node or random variable to be independent of any non-descendant node given information about its parent. A direct consequence of this property is that it is relatively easy to incorporate new evidence and derive the appropriate consequences, which in general is not an easy or feasible task. Typically we use Bayesian networks as predictive models for a small subset of the variables, either the leave nodes or the root nodes. In IKE, since most applications deal with diagnostics, we are interested in predicting the likelihood of the root nodes given new observations on any of the children nodes. The root nodes represent the various possible outcomes of the analysis, and an important problem is to determine when we have gathered enough evidence to lean toward one of these particular outcomes. This document presents criteria to decide when the evidence gathered is sufficient to draw a particular conclusion or decide in favor of a particular outcome by quantifying the uncertainty in the conclusions that are drawn from the data. The material in this document is organized as follows: Section 2 presents briefly a forensics Bayesian network, and we explore evaluating the information provided by new evidence by looking first at the posterior distribution of the nodes of interest, and then at the corresponding posterior odds ratios. Section 3 presents a third alternative: Bayes Factors. In section 4 we finalize by showing the relation between the posterior odds ratios and Bayes factors and showing examples these cases, and in section 5 we conclude by providing clear guidelines of how to use these for the type of Bayesian networks used in IKE.

Cuellar, Leticia [Los Alamos National Laboratory

2012-05-31T23:59:59.000Z

327

Demonstration testing and evaluation of in situ soil heating. Treatability study work plan (Revision 2)  

SciTech Connect

A Treatability Study planned for the demonstration of the in situ electromagnetic (EM) heating process to remove organic solvents is described in this Work Plan. The treatability study will be conducted by heating subsurface vadose-zone soils in an organic plume adjacent to the Classified Burial Ground K-1070-D located at K-25 Site, Oak Ridge. The test is scheduled to start during the fourth quarter of FY94 and will be completed during the first quarter of FY95. Over the last nine years, a number of Government agencies (EPA, Army, AF, and DOE) and industries sponsored further development and testing of the in situ heating and soil decontamination process for the remediation of soils containing hazardous organic contaminants. In this process the soil is heated in situ using electrical energy. The contaminants are removed from the soil due to enhanced vaporization, steam distillation and stripping. IITRI will demonstrate the EM Process for in situ soil decontamination at K-25 Site under the proposed treatability study. Most of the contaminants of concern are volatile organics which can be removed by heating the soil to a temperature range of 85{degrees} to 95{degrees}C. The efficiency of the treatment will be determined by comparing the concentration of contaminants in soil samples. Samples will be obtained before and after the demonstration for a measurement of the concentration of contaminants of concern. This document is a Treatability Study Work Plan for the demonstration program. The document contains a description of the proposed treatability study, background of the EM heating process, description of the field equipment, and demonstration test design.

Sresty, G.C.

1994-12-30T23:59:59.000Z

328

Corrective Action Plan for Corrective Action Unit 261: Area 25 Test Cell A Leachfield System, Nevada Test Site, Nevada  

Science Conference Proceedings (OSTI)

This Corrective Action Plan (CAP) has been prepared for the Corrective Action Unit (CAU)261 Area 25 Test Cell A Leachfield System in accordance with the Federal Facility and Consent Order (Nevada Division of Environmental Protection [NDEP] et al., 1996). This CAP provides the methodology for implementing the approved corrective action alternative as listed in the Corrective Action Decision Document (U.S. Department of Energy, Nevada Operations Office, 1999). Investigation of CAU 261 was conducted from February through May of 1999. There were no Constituents of Concern (COCs) identified at Corrective Action Site (CAS) 25-05-07 Acid Waste Leach Pit (AWLP). COCs identified at CAS 25-05-01 included diesel-range organics and radionuclides. The following closure actions will be implemented under this plan: Because COCs were not found at CAS 25-05-07 AWLP, no action is required; Removal of septage from the septic tank (CAS 25-05-01), the distribution box and the septic tank will be filled with grout; Removal of impacted soils identified near the initial outfall area; and Upon completion of this closure activity and approval of the Closure Report by NDEP, administrative controls, use restrictions, and site postings will be used to prevent intrusive activities at the site.

T. M. Fitzmaurice

2000-08-01T23:59:59.000Z

329

Integrated DWPF Melter System (IDMS) campaign report: Hanford Waste Vitrification Plan (HWVP) process demonstration  

Science Conference Proceedings (OSTI)

Vitrification facilities are being developed worldwide to convert high-level nuclear waste to a durable glass form for permanent disposal. Facilities in the United States include the Department of Energy`s Defense Waste Processing Facility (DWPF) at the Savannah River Site, the Hanford Waste Vitrification Plant (HWVP) at the Hanford Site and the West Valley Demonstration Project (WVDP) at West Valley, NY. At each of these sites, highly radioactive defense waste will be vitrified to a stable borosilicate glass. The DWPF and WVDP are near physical completion while the HWVP is in the design phase. The Integrated DWPF Melter System (IDMS) is a vitrification test facility at the Savannah River Technology Center (SRTC). It was designed and constructed to provide an engineering-scale representation of the DWPF melter and its associated feed preparation and off-gas treatment systems. Because of the similarities of the DWPF and HWVP processes, the IDMS facility has also been used to characterize the processing behavior of a reference NCAW simulant. The demonstration was undertaken specifically to determine material balances, to characterize the evolution of offgas products (especially hydrogen), to determine the effects of noble metals, and to obtain general HWVP design data. The campaign was conducted from November, 1991 to February, 1992.

Hutson, N.D.

1992-08-10T23:59:59.000Z

330

Test plan for long-term, low-temperature oxidation of BWR spent fuel  

Science Conference Proceedings (OSTI)

Preliminary studies indicated the need for more spent fuel oxidation data in order to determine the probable behavior of spent fuel in a tuff repository. Long-term, low-temperature testing was recommended in a comprehensive technical approach to (1) confirm the findings of the short-term thermogravimetric analysis tests; (2) evaluate the effects of variables such as burnup, atmospheric moisture,and fuel type on the oxidation rate; and (3) extend the oxidation data base to representative repository temperatures and better define the temperature dependence of the operative oxidation mechanisms. This document presents the test plan to study the effects of atmospheric moisture and temperature on oxidation rate and phase formation using a large number of boiling-water reactor fuel samples. Tests will run for up to two years, use characterized fragmented and pulverized fuel samples, cover a temperature range of 110{degree}C to 175{degree}C, and be conducted with an atmospheric moisture content ranging from <{minus}55{degree}C to {approximately}80{degree}C dew point. After testing, the samples will be examined and made available for leaching testing. 15 refs., 2 figs., 2 tabs.

Einziger, R.E.

1988-12-01T23:59:59.000Z

331

Status and Plans for a Superconducting RF Accelerator Test Facility at Fermilab  

Science Conference Proceedings (OSTI)

The Advanced Superconducting Test Accelerator (ASTA) is being constructed at Fermilab. The existing New Muon Lab (NML) building is being converted for this facility. The accelerator will consist of an electron gun, injector, beam acceleration section consisting of 3 TTF-type or ILC-type cryomodules, multiple downstream beam lines for testing diagnostics and conducting various beam tests, and a high power beam dump. When completed, it is envisioned that this facility will initially be capable of generating a 750 MeV electron beam with ILC beam intensity. An expansion of this facility was recently completed that will provide the capability to upgrade the accelerator to a total beam energy of 1.5 GeV. Two new buildings were also constructed adjacent to the ASTA facility to house a new cryogenic plant and multiple superconducting RF (SRF) cryomodule test stands. In addition to testing accelerator components, this facility will be used to test RF power systems, instrumentation, and control systems for future SRF accelerators such as the ILC and Project-X. This paper describes the current status and overall plans for this facility.

Leibfritz, J.; Andrews, R.; Baffes, C.M.; Carlson, K.; Chase, B.; Church, M.D.; Harms, E.R.; Klebaner, A.L.; Kucera, M.; Martinez, A.; Nagaitsev, S.; /Fermilab

2012-05-01T23:59:59.000Z

332

Streamlined Approach for Environmental Restoration Plan for Corrective Action Unit 496: Buried Rocket Site, Antelope Lake, Tonopah Test Range  

SciTech Connect

This Streamlined Approach for Environmental Restoration (SAFER) plan details the activities necessary to close Corrective Action Unit 496: Buried Rocket Site, Antelope Lake. CAU 496 consists of one site located at the Tonopah Test Range, Nevada.

U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office; Bechtel Nevada

2004-05-01T23:59:59.000Z

333

Joint Test Plan to Identify the Gaseous By-Products of CH3I Loading on AgZ  

SciTech Connect

The objective of this test plan is to describe research to determine the gaseous by-products of the adsorption of CH3I on hydrogen reduced silver exchanged mordenite (AgZ).

R. T. Jubin; N. R. Soelberg; D. M. Strachan; T. M. Nenoff; B. B. Spencer

2012-12-01T23:59:59.000Z

334

Test Planning for Mixed-Signal SOCs with Wrapped Analog Cores Anuja Sehgal, Fang Liu, Sule Ozev and Krishnendu Chakrabarty  

E-Print Network (OSTI)

Test Planning for Mixed-Signal SOCs with Wrapped Analog Cores Anuja Sehgal, Fang Liu, Sule Ozev. Even though the test cost for such mixed-signal SOCs is significantly higher than that for digital SOCs, most prior research in this area has focused exclusively on digital cores. We propose a low-cost test

Paris-Sud XI, Université de

335

Introducing the use of integrated Decision Support System in Natural Resources Planning  

E-Print Network (OSTI)

The target subject of Natural Resources Planning (NRP) includes various systems and their elements, all of which are centered around the natural resource system. Given this characteristic complexity and a high degree of ...

Park, Hye Yeon, S.M. Massachusetts Institute of Technology

2008-01-01T23:59:59.000Z

336

Integrated method to create optimal dynamic strategic plans for corporate technology start-ups  

E-Print Network (OSTI)

This thesis presents an innovative method for evaluating and dynamically planning the development of uncertain technology investments. Its crux centers on a paradigm shift in the way managers assess investments, toward an ...

Mikati, Samir Omar

2009-01-01T23:59:59.000Z

337

Integrating regional strategic transportation planning and supply chain management : along the path to sustainability  

E-Print Network (OSTI)

A systems perspective for regional strategic transportation planning (RSTP) for freight movements involves an understanding of Supply Chain Management (SCM). This thesis argues that private sector freight shippers and ...

Sgouridis, Sgouris P

2005-01-01T23:59:59.000Z

338

Planning to learn: Integrating model learning into a trajectory planner for mobile robots  

E-Print Network (OSTI)

For a mobile robot that performs online model learning, the learning rate is a function of the robot's trajectory. The tracking errors that arise when the robot executes a motion plan depend on how well the robot has learned ...

Hover, Franz S.

339

Design and Experimental Test Plan for Hybrid Sulfur Single Cell Pressurized Electrolyzer  

DOE Green Energy (OSTI)

The Hybrid Sulfur (HyS) process is one of the leading thermochemical cycles being studied as part of the DOE Nuclear Hydrogen Initiative (NHI). SRNL is conducting analyses and research and development for the Department of Energy on the HyS process. A conceptual design report and development plan for the HyS process was issued on April 1, 2005 [Buckner, et. al., 2005] , and a report on atmospheric testing of a sulfur dioxide depolarized electrolyzer (SDE), a major component of the HyS process, was issued on August 1, 2005 [Steimke, 2005]. The purpose of this report is to document work related to the design and experimental test plan for a pressurized SDE. Pressurized operation of the SDE is a key requirement for development of an efficient and cost-effective HyS process. The HyS process, a hybrid thermochemical cycle proposed and investigated in the 1970s and early 1980s by Westinghouse Electric Corporation, is a high priority candidate for NHI due to the potential for high efficiency and its relatively high level of technical maturity. It was demonstrated in laboratory experiments by Westinghouse in 1978. Process improvements and component advancements that build on that work are being pursued. One of the objectives of the current work is to develop the SDE in order to permit the demonstration of a closed-loop laboratory model of the HyS process. The heart of the HyS process for generating hydrogen is a bank of electrolyzers incorporating sulfur dioxide depolarized anodes. SRNL planned, designed, built and operated a facility for testing single cell electrolyzers at ambient temperature and near atmospheric pressure during the spring and summer of 2005. The major contribution of the SRNL work was the establishment of the proof-of-concept for utilizing the proton-exchange-membrane (PEM) cell design for the SDE operation. Since PEM cells are being extensively developed for automotive fuel cell use, they offer significant potential for cost-effective application for the HyS Process. This report discusses the modifications necessary to the existing SRNL sulfur dioxide depolarized electrolyzer test facility to allow testing at up to 80 C and 90 psig. Because of the need for significant additional equipment and the ability to infer performance results to higher pressures, it recommends delaying further modifications to support testing at up to 300 psig (the commercial goal) until other, higher priority technical issues are addressed. These issues include membrane material selection, component designs, catalyst type and loading, etc. The factors and rationale that should be considered in developing and executing a detailed test matrix for pressurized operation are also discussed. In addition, an electrolyzer assembly design has been developed to allow the testing of different Membrane Electrode Assemblies (MEA's) as part of the planned FY06 HyS Development Program to complete selection of component design specifications for the HyS electrolyzer. MEA's are used in PEM cells to allow intimate contact and minimal resistance between the electrodes and the electrolyte layer. The pressurized electrolyzer assembly presented in this report will facilitate rapid change-out and testing of various MEA designs as part of the electrolyzer development effort.

Steeper, T. J.; Steimke, J. L.

2005-09-01T23:59:59.000Z

340

One Degree Micro-Macro Manipulator Integration Test  

E-Print Network (OSTI)

The Carderock Division of the Naval Surface Warfare Center is developing the Automated Paint Application, Containment, and Treatment System (APACTS) to apply anticorrosive and anti-fouling paints in an environmentally sound manner. To provide accurate motion over a very large volume, the APACTS motion system employs a selfpropelled base carrying a long reach macro-manipulator which in turn carries a quick response micro-manipulator to maneuver the paint nozzle and containment device along the ship hull. The manipulators run separate but coordinated trajectories whose combination is the path of the paint nozzle. Based on sensors and feedback from the operator's observations, the micro-manipulator's trajectory is shifted to keep the paint nozzle at the appropriate position relative to the surface being painted. The micromanipulator communicates the shift to the macro-manipulator, which adjusts its trajectory to remove the error and re-center the micro-manipulator. This report investigates the minimum requirements for the interface between the macro and micromanipulators. The investigation includes experiments that test the micro-macro interface by observing the system's response to induced errors. The results indicate an interface reporting the size of the shift and the frequency of the report is sufficient to control the manipulator system, but may not be sufficient for the APACTS application. The report includes possible improvements to the interface. DRAFT iv Table of Contents 1 Summary................................................................................................5 2

Richard J. Norcross

2000-01-01T23:59:59.000Z

Note: This page contains sample records for the topic "integrated test plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


341

Corrective Action Plan for Corrective Action Unit 453: Area 9 UXO Landfill, Tonopah Test Range, Nevada  

Science Conference Proceedings (OSTI)

This corrective action plan proposes the closure method for the area 9 unexploded Ordnance landfill, corrective action unit 453 located at the Tonopah Test Range. The area 9 UXO landfill consists of corrective action site no. 09-55-001-0952 and is comprised of three individual landfill cells designated as A9-1, A9-2, and A9-3. The three landfill cells received wastes from daily operations at area 9 and from range cleanups which were performed after weapons testing. Cell locations and contents were not well documented due to the unregulated disposal practices commonly associated with early landfill operations. However, site process knowledge indicates that the landfill cells were used for solid waste disposal, including disposal of UXO.

Bechtel Nevada

1998-09-30T23:59:59.000Z

342

Tank 241-AZ-101 Mixer Pump Test Vapor Sampling and Analysis Plan  

Science Conference Proceedings (OSTI)

This sampling and analysis plan (SAP) identifies characterization objectives pertaining to sample collection, laboratory analytical evaluation, and reporting requirements for vapor samples obtained during the operation of mixer pumps in tank 241-AZ-101. The primary purpose of the mixer pump test (MPT) is to demonstrate that the two 300 horsepower mixer pumps installed in tank 241-AZ-101 can mobilize the settled sludge so that it can be retrieved for treatment and vitrification. Sampling will be performed in accordance with Tank 241-AZ-101 Mixer Pump Test Data Quality Objective (Banning 1999) and Data Quality Objectives for Regulatory Requirements for Hazardous and Radioactive Air Emissions Sampling and Analysis (Mulkey 1999). The sampling will verify if current air emission estimates used in the permit application are correct and provide information for future air permit applications.

TEMPLETON, A.M.

2000-03-06T23:59:59.000Z

343

Tank 241-AZ-101 Mixer Pump Test Vapor Sampling and Analysis Plan  

Science Conference Proceedings (OSTI)

This sampling and analysis plan (SAP) identifies characterization objectives pertaining to sample collection, laboratory analytical evaluation, and reporting requirements for vapor samples obtained during the operation of mixer pumps in tank 241-AZ-101. The primary purpose of the mixer pump test (MPT) is to demonstrate that the two 300 horsepower mixer pumps installed in tank 241-AZ-101 can mobilize the settled sludge so that it can be retrieved for treatment and vitrification. Sampling will be performed in accordance with Tank 241-AZ-101 Mixer Pump Test Data Quality Objective (Banning 1999) and Data Quality Objectives for Regulatory Requirements for Hazardous and Radioactive Air Emissions Sampling and Analysis (Mulkey 1999). The sampling will verify if current air emission estimates used in the permit application are correct and provide information for future air permit applications.

TEMPLETON, A.M.

2000-04-10T23:59:59.000Z

344

Tank 241-AZ-101 Mixer Pump Test Vapor Sampling and Analysis Plan  

SciTech Connect

This sampling and analysis plan (SAP) identifies characterization objectives pertaining to sample collection, laboratory analytical evaluation, and reporting requirements for vapor samples obtained during the operation of mixer pumps in tank 241-AZ-101. The primary purpose of the mixer pump test (MPT) is to demonstrate that the two 300 horsepower mixer pumps installed in tank 241-AZ-101 can mobilize the settled sludge so that it can be retrieved for treatment and vitrification Sampling will be performed in accordance with Tank 241-AZ-101 Mixer Pump Test Data Quality Objective (Banning 1999) and Data Quality Objectives for Regulatory Requirements for Hazardous and Radioactive Air Emissions Sampling and Analysis (Mulkey 1999). The sampling will verify if current air emission estimates used in the permit application are correct and provide information for future air permit applications.

TEMPLETON, A.M.

2000-01-31T23:59:59.000Z

345

Supplemental Investigation Plan for FFACO Use Restrictions, Nevada Test Site, Nevada, Revision 0  

SciTech Connect

This document is part of an effort to re-evaluate all FFACO URs against the current RBCA criteria (referred to in this document as the Industrial Sites [IS] RBCA process) as defined in the Industrial Sites Project Establishment of Final Action Levels (NNSA/NSO, 2006a). After reviewing all of the existing FFACO URs, the 12 URs addressed in this Supplemental Investigation Plan (SIP) could not be evaluated against the current RBCA criteria as sufficient information about the contamination at each site was not available. This document presents the plan for conducting field investigations to obtain the needed information. This SIP includes URs from Corrective Action Units (CAUs) 326, 339, 358, 452, 454, 464, and 1010, located in Areas 2, 6, 12, 19, 25, and 29 of the Nevada Test Site, which is approximately 65 miles northwest of Las Vegas, Nevada; and CAU 403, located in Area 3 of the Tonopah Test Range, which is approximately 165 miles north of Las Vegas, Nevada.

Lynn Kidman

2008-02-01T23:59:59.000Z

346

Planning the transition to the CIM (computer-integrated manufacturing) environment at the Oak Ridge Y-12 Plant  

SciTech Connect

Formalized efforts have been ongoing within the Oak Ridge Y-12 Plant since 1982 to plan and implement a computer-integrated manufacturing (CIM) environment. This presentation addresses activities past and present that are enabling the Y-12 facility to make the transition into the CIM environment. Specific issues addressed are: (1) present and future modeling for manufacturing process, business model, data architecture, and information systems architecture; (2) establishing a formal CIM organization to be responsible for CIM planning and implementation; (3) establishing specific Plant performance goals relating to CIM objectives; (4) conducting CIM needs analysis with the production organizations to foster a basic understanding of the CIM concept and to identify CIM opportunities; and (5) CIM Program status.

Bowers, G.L.; Murphy, S.M. Jr.

1987-03-24T23:59:59.000Z

347

Spent Nuclear Fuel (SNF) project Integrated Safety Management System phase I and II Verification Review Plan  

Science Conference Proceedings (OSTI)

The U.S. Department of Energy (DOE) commits to accomplishing its mission safely. To ensure this objective is met, DOE issued DOE P 450.4, Safety Management System Policy, and incorporated safety management into the DOE Acquisition Regulations ([DEAR] 48 CFR 970.5204-2 and 90.5204-78). Integrated Safety Management (ISM) requires contractors to integrate safety into management and work practices at all levels so that missions are achieved while protecting the public, the worker, and the environment. The contractor is required to describe the Integrated Safety Management System (ISMS) to be used to implement the safety performance objective.

CARTER, R.P.

1999-11-19T23:59:59.000Z

348

Sixth Northwest Conservation and Electric Power Plan Appendix M: Integrating Fish & Wildlife and  

E-Print Network (OSTI)

below Libby Dam. The reservoir operation in spring largely works toward project refill while otherwise operations in the mid-Columbia River to support fall Chinook spawning and rearing in the Hanford Reach to fish. Action item F&W-2 (see the Action Plan) calls for the Council to work with fish and wildlife

349

Integrating planning and control for single-bodied wheeled mobile robots  

Science Conference Proceedings (OSTI)

This paper presents an approach to couple path planning and control for mobile robot navigation in a hybrid control framework. We build upon an existing hybrid control approach called sequential composition, in which a set of feedback control ... Keywords: Hybrid controls, Mobile robots, Sequential composition

David C. Conner; Howie Choset; Alfred A. Rizzi

2011-04-01T23:59:59.000Z

350

Office of River Protection Integrated Safety Management System Phase 1 Verification Corrective Action Plan  

SciTech Connect

The purpose of this Corrective Action Plan is to demonstrate the OW planned and/or completed actions to implement ISMS as well as prepare for the RPP ISMS Phase II Verification scheduled for August, 1999. This Plan collates implied or explicit ORP actions identified in several key ISMS documents and aligns those actions and responsibilities perceived necessary to appropriately disposition all ISM Phase II preparation activities specific to the ORP. The objective will be to complete or disposition the corrective actions prior to the commencement of the ISMS Phase II Verification. Improvement products/tasks not slated for completion prior to the RPP Phase II verification will be incorporated as corrective actions into the Strategic System Execution Plan (SSEP) Gap Analysis. Many of the business and management systems that were reviewed in the ISMS Phase I verification are being modified to support the ORP transition and are being assessed through the SSEP. The actions and processes identified in the SSEP will support the development of the ORP and continued ISMS implementation as committed to be complete by end of FY-2000.

CLARK, D.L.

1999-08-09T23:59:59.000Z

351

ESTER, Enel integrated System for TEsts on stoRage (Smart Grid Project) |  

Open Energy Info (EERE)

ESTER, Enel integrated System for TEsts on stoRage (Smart Grid Project) ESTER, Enel integrated System for TEsts on stoRage (Smart Grid Project) Jump to: navigation, search Project Name ESTER, Enel integrated System for TEsts on stoRage Country Italy Headquarters Location Livorno, Italy Coordinates 43.551876°, 10.308011° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[{"text":"","title":"","link":null,"lat":43.551876,"lon":10.308011,"alt":0,"address":"","icon":"","group":"","inlineLabel":"","visitedicon":""}]}

352

Laboratory development of sludge washing and alkaline leaching processes: Test plan for FY 1994  

Science Conference Proceedings (OSTI)

The US Department of Energy plans to vitrify (as borosilicate glass) the large volumes of high-level radioactive wastes at the Hanford site. To reduce costs, pretreatment processes will be used to reduce the volume of borosilicate glass required for disposal. Several options are being considered for the pretreatment processes: (1) sludge washing with water or dilute hydroxide: designed to remove most of the Na from the sludge, thus significantly reducing the volume of waste to be vitrified; (2) sludge washing plus caustic leaching and/or metathesis (alkaline sludge leaching): designed to dissolve large quantities of certain nonradioactive elements, such as Al, Cr and P, thus reducing the volume of waste even more; (3) sludge washing, sludge dissolution, and separation of radionuclides from the dissolved sludge solutions (advanced processing): designed to remove all radionuclides for concentration into a minimum waste volume. This report describes a test plan for work that will be performed in FY 1994 under the Sludge Washing and Caustic Leaching Studies Task (WBS 0402) of the Tank Waste Remediation System (TWRS) Pretreatment Project. The objectives of the work described here are to determine the effects of sludge washing and alkaline leaching on sludge composition and the physical properties of the washed sludge and to evaluate alkaline leaching methods for their impact on the volume of borosilicate glass required to dispose of certain Hanford tank sludges.

Rapko, B.M.; Lumetta, G.J.

1994-07-01T23:59:59.000Z

353

Independent Verification and Validation Of SAPHIRE 8 System Test Plan Project Number: N6423 U.S. Nuclear Regulatory Commission  

Science Conference Proceedings (OSTI)

The purpose of the Independent Verification and Validation (IV&V) role in the evaluation of the SAPHIRE System Test Plan is to assess the approach to be taken for intended testing activities associated with the SAPHIRE software product. The IV&V team began this endeavor after the software engineering and software development of SAPHIRE had already been in production.

Kent Norris

2010-02-01T23:59:59.000Z

354

Streamlined Approach for Environmental Restoration Plan for Corrective Action Unit 489: WWII UXO Sites, Tonopah Test Range, Nevada; May 2005  

Science Conference Proceedings (OSTI)

This Streamlined Approach for Environmental Restoration Plan provides the details for the closure of Corrective Action Unit (CAU) 489: WWII UXO Sites, Tonopah Test Range. CAU 489 is located at the Tonopah Test Range and is currently listed in Appendix III of the Federal Facility Agreement and Consent Order of 1996.

Bechtel Nevada; U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office

2005-05-01T23:59:59.000Z

355

DOE-STD-3026-99; DOE Standard Filter Test Facility Quality Program Plan  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

6-99 6-99 February 1999 Superseding DOE NE F 3-44 July 1986 DOE STANDARD FILTER TEST FACILITY QUALITY PROGRAM PLAN U.S. Department of Energy FSC 4460 Washington, D.C. 20585 DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. This document has been reproduced from the best available copy. Available to DOE and DOE contractors from ES&H Technical Information Services, U.S. Department of Energy, (800) 473-4375, fax: (301) 903-9823. Available to the public from the U.S. Department of Commerce, Technology Administration, National Technical Information Service, Springfield, VA 22161; (703) 605-6000. DOE-STD-3026-99 iii FOREWORD This Department of Energy standard supercedes DOE NE F 3-44 and is approved for use by all DOE components and their contractors.

356

Corrective action investigation plan for CAU No. 424: Area 3 Landfill Complex, Tonopah Test Range, Nevada  

Science Conference Proceedings (OSTI)

This Correction Action Investigation Plan contains the environmental sample collection objectives and the criteria for conducting site investigation activities at the Area 3 Landfill Complex, CAU No. 424, which is located at the Tonopah Test Range (TTR). The TTR, included in the Nellis Air Force Range, is approximately 255 kilometers (140 miles) northwest of Las Vegas, nevada. The CAU 424 is comprised of eight individual landfill sites that are located around and within the perimeter of the Area 3 Compound. Due to the unregulated disposal activities commonly associated with early landfill operations, an investigation will be conducted at each CAS to complete the following tasks: identify the presence and nature of possible contaminant migration from the landfills; determine the vertical and lateral extent of possible contaminant migration; ascertain the potential impact to human health and the environment; and provide sufficient information and data to develop and evaluate appropriate corrective action strategies for each CAS.

NONE

1997-04-01T23:59:59.000Z

357

Closure plan for CAU No. 93: Area 6 steam cleaning effluent ponds, Nevada Test Site  

SciTech Connect

The steam cleaning effluent ponds (SCEP) waste unit is located in Area 6 at the Nevada Test Site (NTS). Nevada Operations Office operates the NTS and has entered into a trilateral agreement with the State of Nevada and the Defense Special Weapons Agency (DSWA). The trilateral agreement provides a framework for identifying, characterizing, remediating, and closing environmental sites on the NTS and associated bombing ranges. The SCEP waste unit consists of: two steam cleaning effluent ponds; layout pad and associated grease trap; Building 6-623 steam cleaning pad; test pad; Building 6-623 grease trap; Building 6-800 steam cleaning pad; Building 6-800 separator; Building 6-621 sump; and the concrete asbestos piping connecting these components to both SCEPs. Clean closure is the recommended closure strategy for the majority of the components within this CAU. Four components of the unit (Building 6-621 Sump, Test Pad Grease Trap, Building 6-623 Steam Cleaning Pad, and North SCEP pipeline) are recommended to be closed in place. This closure plan provides the strategy and backup information necessary to support the clean closure of each of the individual components within CAU 93. Analytical data generated during the characterization field work and earlier sampling events indicates the majority of CAU 93 soil and infrastructure is non-hazardous (i.e., impacted primarily with petroleum hydrocarbons).

NONE

1997-04-01T23:59:59.000Z

358

Design and Simulation of IOTA - a Novel Concept of Integrable Optics Test Accelerator  

Science Conference Proceedings (OSTI)

The use of nonlinear lattices with large betatron tune spreads can increase instability and space charge thresholds due to improved Landau damping. Unfortunately, the majority of nonlinear accelerator lattices turn out to be nonintegrable, producing chaotic motion and a complex network of stable and unstable resonances. Recent advances in finding the integrable nonlinear accelerator lattices have led to a proposal to construct at Fermilab a test accelerator with strong nonlinear focusing which avoids resonances and chaotic particle motion. This presentation will outline the main challenges, theoretical design solutions and construction status of the Integrable Optics Test Accelerator (IOTA) underway at Fermilab.

Nagaitsev, S.; Valishev, A.; /Fermilab; Danilov, V.V.; /Oak Ridge; Shatilov, D.N.; /Novosibirsk, IYF

2012-05-01T23:59:59.000Z

359

Demonstration testing and evaluation of in situ soil heating. Treatability study work plan, Revision 1  

SciTech Connect

A Treatability Study planned for the demonstration of the in situ electromagnetic (EM) heating process to remove organic solvents is described in this Work Plan. The treatability study will be conducted by heating subsurface vadose-zone soils in an organic plume adjacent to the Classified Burial Ground K-1070-D located at K-25 Site, Oak Ridge. The test is scheduled to start during the fourth quarter of FY94 and will be completed during the first quarter of FY95. The EM heating process for soil decontamination is based on volumetric heating technologies developed during the `70s for the recovery of fuels from shale and tar sands by IIT Research Institute (IITRI) under a co-operative program with the US Department of Energy (DOE). Additional modifications of the technology developed during the mid `80s are currently used for the production of heavy oil and waste treatment. Over the last nine years, a number of Government agencies (EPA, Army, AF, and DOE) and industries sponsored further development and testing of the in situ heating and soil decontamination process for the remediation of soils containing hazardous organic contaminants. In this process the soil is heated in situ using electrical energy. The contaminants are removed from the soil due to enhanced vaporization, steam distillation and stripping. IITRI will demonstrate the EM Process for in situ soil decontamination at K-25 Site under the proposed treatability study. Most of the contaminants of concern are volatile organics which can be removed by heating the soil to a temperature range of 85 to 95 C. The efficiency of the treatment will be determined by comparing the concentration of contaminants in soil samples. Samples will be obtained before and after the demonstration for a measurement of the concentration of contaminants of concern.

Sresty, G.C.

1994-07-07T23:59:59.000Z

360

Integrated project management plan for the Plutonium Finishing Plant stabilization and deactivation project  

Science Conference Proceedings (OSTI)

This document sets forth the plans, organization, and control systems for managing the PFP Stabilization and Deactivation Project, and includes the top level cost and schedule baselines. The project includes the stabilization of Pu-bearing materials, storage, packaging, and transport of these and other nuclear materials, surveillance and maintenance of facilities and systems relied upon for storage of the materials, and transition of the facilities in the PFP Complex.

SINCLAIR, J.C.

1999-05-03T23:59:59.000Z

Note: This page contains sample records for the topic "integrated test plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


361

Molten-Caustic-Leaching (Gravimelt) System Integration Project, Phase 2. Topical report for test circuit operation  

SciTech Connect

The objective of the task (Task 6) covered in this document was to operate the refurbished/modified test circuit of the Gravimeh Process in a continuous integrated manner to obtain the engineering and operational data necessary to assess the technical performance and reliability of the circuit. This data is critical to the development of this technology as a feasible means of producing premium clean burning fuels that meet New Source Performance Standards (NSPS). Significant refurbishments and design modifications had been made to the facility (in particular to the vacuum filtration and evaporation units) during Tasks 1 and 2, followed by off-line testing (Task 3). Two weeks of continuous around-the-clock operation of the refurbished/modified MCL test circuit were performed. During the second week of testing, all sections of the plant were operated in an integrated fashion for an extended period of time, including a substantial number of hours of on-stream time for the vacuum filters and the caustic evaporation unit. A new process configuration was tested in which centrate from the acid wash train (without acid addition) was used as the water makeup for the water wash train, thus-eliminating the one remaining process waste water stream. A 9-inch centrifuge was tested at various solids loadings and at flow rates up to 400 lbs/hr of coal feed to obtain a twenty-fold scaleup factor over the MCL integrated test facility centrifuge performance data.

Not Available

1993-02-01T23:59:59.000Z

362

Cold test plan for the Old Hydrofracture Facility tank contents removal project, Oak Ridge National Laboratory, Oak Ridge, Tennessee  

SciTech Connect

This Old Hydrofracture Facility (OHF) Tanks Contents Removal Project Cold Test Plan describes the activities to be conducted during the cold test of the OHF sluicing and pumping system at the Tank Technology Cold Test Facility (TTCTF). The TTCTF is located at the Robotics and Process Systems Complex at the Oak Ridge National Laboratory (ORNL). The cold test will demonstrate performance of the pumping and sluicing system, fine-tune operating instructions, and train the personnel in the actual work to be performed. After completion of the cold test a Technical Memorandum will be prepared documenting completion of the cold test, and the equipment will be relocated to the OHF site.

1997-11-01T23:59:59.000Z

363

Standard Test Method for Wet Insulation Integrity Testing of Photovoltaic Arrays  

E-Print Network (OSTI)

1.1 This test method covers a procedure to determine the insulation resistance of a photovoltaic (PV) array (or its component strings), that is, the electrical resistance between the array's internal electrical components and is exposed, electrically conductive, non-current carrying parts and surfaces of the array. 1.2 This test method does not establish pass or fail levels. The determination of acceptable or unacceptable results is beyond the scope of this test method. 1.3 The values stated in SI units are to be regarded as standard. No other units of measurement are included in this standard. 1.4 This standard does not purport to address all of the safety concerns, if any, associated with its use. It is the responsibility of the user of this standard to establish appropriate safety and health practices and determine the applicability of regulatory limitations prior to use.

American Society for Testing and Materials. Philadelphia

2010-01-01T23:59:59.000Z

364

Developing a holistic strategy for integrated waste management within municipal planning: Challenges, policies, solutions and perspectives for Hellenic municipalities in the zero-waste, low-cost direction  

SciTech Connect

The present position paper addresses contemporary waste management options, weaknesses and opportunities faced by Hellenic local authorities. It focuses on state-of-the-art, tested as well as innovative, environmental management tools on a municipal scale and identifies a range of different collaboration schemes between local authorities and related service providers. Currently, a policy implementation gap is still experienced among Hellenic local authorities; it appears that administration at the local level is inadequate to manage and implement many of the general policies proposed; identify, collect, monitor and assess relevant data; and safeguard efficient and effective implementation of MSWM practices in the framework of integrated environmental management as well. This shortfall is partly due to the decentralisation of waste management issues to local authorities without a parallel substantial budgetary and capacity support, thus resulting in local activity remaining often disoriented and isolated from national strategies, therefore yielding significant planning and implementation problems and delays against pressing issues at hand as well as loss or poor use of available funds. This paper develops a systemic approach for MSWM at both the household and the non-household level, summarizes state-of-the-art available tools and compiles a set of guidelines for developing waste management master plans at the municipal level. It aims to provide a framework in the MSWM field for municipalities in Greece as well as other countries facing similar problems under often comparable socioeconomic settings.

Zotos, G. [Division of Business Studies, Dept. of Economics, Aristotle University, GR-54124, Thessaloniki (Greece); Karagiannidis, A. [Laboratory of Heat Transfer and Environmental Engineering, Dept. of Mechanical Engineering, Aristotle University, GR-54124, Thessaloniki (Greece); Zampetoglou, S. [Municipal Development Company of Kalamaria, GR-55132 (Greece); Malamakis, A. [Laboratory of Heat Transfer and Environmental Engineering, Dept. of Mechanical Engineering, Aristotle University, GR-54124, Thessaloniki (Greece)], E-mail: amalama@aix.meng.auth.gr; Antonopoulos, I.-S.; Kontogianni, S. [Laboratory of Heat Transfer and Environmental Engineering, Dept. of Mechanical Engineering, Aristotle University, GR-54124, Thessaloniki (Greece); Tchobanoglous, G. [Department of civil and environmental Engineering, University of California, Davis (United States)

2009-05-15T23:59:59.000Z

365

Industrial Sites Work Plan for Leachfield Corrective Action Units: Nevada Test Site and Tonopah Test Range, Nevada (including Record of Technical Change Nos. 1, 2, 3, and 4)  

SciTech Connect

This Leachfield Corrective Action Units (CAUs) Work Plan has been developed in accordance with the Federal Facility Agreement and Consent Order (FFACO) that was agreed to by the U.S. Department of Energy, Nevada Operations Office (DOE/NV); the State of Nevada Division of Environmental Protection (NDEP); and the U.S. Department of Defense (FFACO, 1996). Under the FFACO, a work plan is an optional planning document that provides information for a CAU or group of CAUs where significant commonality exists. A work plan may be developed that can be referenced by leachfield Corrective Action Investigation Plans (CAIPs) to eliminate redundant CAU documentation. This Work Plan includes FFACO-required management, technical, quality assurance (QA), health and safety, public involvement, field sampling, and waste management documentation common to several CAUs with similar site histories and characteristics, namely the leachfield systems at the Nevada Test Site (NTS) and the Tonopah Test Range (TT R). For each CAU, a CAIP will be prepared to present detailed, site-specific information regarding contaminants of potential concern (COPCs), sampling locations, and investigation methods.

DOE /NV

1998-12-18T23:59:59.000Z

366

An integrated reception?plate inverse?force structure?borne noise source characterization test method.  

Science Conference Proceedings (OSTI)

An integrated reception?plate inverse?force method for vibration power and force transmitted from a mounted vibration source measurement has been prototyped and evaluated. The tests developed data to aid in understanding the repeatability and reproducibility of the method

Kevin H. Lai

2011-01-01T23:59:59.000Z

367

NREL Vehicle Testing and Integration Facility (VTIF): Rotating Shadowband Radiometer (RSR); Golden, Colorado (Data)  

DOE Data Explorer (OSTI)

This measurement station at NREL's Vehicle Testing and Integration Facility (VTIF) monitors global horizontal, direct normal, and diffuse horizontal irradiance to define the amount of solar energy that hits this particular location. The solar measurement instrumentation is also accompanied by meteorological monitoring equipment.

Lustbader, J.; Andreas, A.

368

NREL Vehicle Testing and Integration Facility (VTIF): Rotating Shadowband Radiometer (RSR); Golden, Colorado (Data)  

DOE Green Energy (OSTI)

This measurement station at NREL's Vehicle Testing and Integration Facility (VTIF) monitors global horizontal, direct normal, and diffuse horizontal irradiance to define the amount of solar energy that hits this particular location. The solar measurement instrumentation is also accompanied by meteorological monitoring equipment.

Lustbader, J.; Andreas, A.

2012-04-01T23:59:59.000Z

369

Oak Ridge Y-12 Plant Computer Integrated Manufacturing Strategic Plan (FY 1986-1992): a working document  

SciTech Connect

The Y-12 Computer-Integrated Manufacturing (CIM) Program is managing the migration of the plant's CIM infrastructure from today's environment to an integrated, highly flexible, and more responsive manufacturing architecture planned for the 1990s. The program is committed to: (1) meeting DOE CIM directives, and (2) improving the manufacturing performance of the Y-12 Plant. The CIM Program charter in Y-12 is to improve manufacturing performance through integrated computer and communication technologies such that the plant's ability to meet its current and future manufacturing objectives is significantly enhanced. To achieve this goal, CIM technologies are being applied in two primary areas: (1) automation of manufacturing processes, and (2) automation of information of information systems. The objectives of the CIM Program are as follows: Meet DOE CIM directives; Reduce product cost; Meet production schedules with minimum contingency costs; Improve product quality via quality assurance at the point of origin; Minimize in-process inventory and improve inventory control; Reduce product lead time; Improve production flexibility.

Not Available

1985-09-01T23:59:59.000Z

370

Corrective Action Plan for Corrective Action Unit 417: Central Nevada Test Area Surface, Nevada  

Science Conference Proceedings (OSTI)

This Corrective Action Plan provides methods for implementing the approved corrective action alternative as provided in the Corrective Action Decision Document for the Central Nevada Test Area (CNTA), Corrective Action Unit (CAU) 417 (DOE/NV, 1999). The CNTA is located in the Hot Creek Valley in Nye County, Nevada, approximately 137 kilometers (85 miles) northeast of Tonopah, Nevada. The CNTA consists of three separate land withdrawal areas commonly referred to as UC-1, UC-3, and UC-4, all of which are accessible to the public. CAU 417 consists of 34 Corrective Action Sites (CASs). Results of the investigation activities completed in 1998 are presented in Appendix D of the Corrective Action Decision Document (DOE/NV, 1999). According to the results, the only Constituent of Concern at the CNTA is total petroleum hydrocarbons (TPH). Of the 34 CASs, corrective action was proposed for 16 sites in 13 CASs. In fiscal year 1999, a Phase I Work Plan was prepared for the construction of a cover on the UC-4 Mud Pit C to gather information on cover constructibility and to perform site management activities. With Nevada Division of Environmental Protection concurrence, the Phase I field activities began in August 1999. A multi-layered cover using a Geosynthetic Clay Liner as an infiltration barrier was constructed over the UC-4 Mud Pit. Some TPH impacted material was relocated, concrete monuments were installed at nine sites, signs warning of site conditions were posted at seven sites, and subsidence markers were installed on the UC-4 Mud Pit C cover. Results from the field activities indicated that the UC-4 Mud Pit C cover design was constructable and could be used at the UC-1 Central Mud Pit (CMP). However, because of the size of the UC-1 CMP this design would be extremely costly. An alternative cover design, a vegetated cover, is proposed for the UC-1 CMP.

K. Campbell

2000-04-01T23:59:59.000Z

371

Corrective Action Plan for Corrective Action Unit 407: Roller Coaster RADSAFE Area, Tonopah Test Range, Nevada  

Science Conference Proceedings (OSTI)

This Corrective Action Plan (CAP) has been prepared for the Roller Coaster RADSAFE Area Corrective Action Unit 407 in accordance with the Federal Facility and Consent Order (Nevada Division of Environmental Protection [NDEP] et al., 1996). This CAP provides the methodology for implementing the approved Corrective Action Alternative as listed in the Corrective Action Decision Document (U.S. Department of Energy, Nevada Operations Office, 1999). The RCRSA was used during May and June of 1963 to decontaminate vehicles, equipment, and personnel from the Clean Slate tests. The Constituents of Concern (COCs) identified during the site characterization include plutonium, uranium, and americium. No other COCS were identified. The following closure actions will be implemented under this plan: (1) Remove and dispose of surface soils which are over three times background for the area. Soils identified for removal will be disposed of at an approved disposal facility. Excavated areas will be backfilled with clean borrow soil fi-om a nearby location. (2) An engineered cover will be constructed over the waste disposal pit area where subsurface COCS will remain. (3) Upon completion of the closure and approval of the Closure Report by NDEP, administrative controls, use restrictions, and site postings will be used to prevent intrusive activities at the site. Barbed wire fencing will be installed along the perimeter of this unit. Post closure monitoring will consist of site inspections to determine the condition of the engineered cover. Any identified maintenance and repair requirements will be remedied within 90 working days of discovery and documented in writing at the time of repair. Results of all inspections/repairs for a given year will be addressed in a single report submitted annually to the NDEP.

T. M. Fitzmaurice

2000-05-01T23:59:59.000Z

372

Corrective Action Plan for Corrective Action Unit 139: Waste Disposal Sites, Nevada Test Site, Nevada  

SciTech Connect

Corrective Action Unit (CAU) 139, Waste Disposal Sites, is listed in the Federal Facility Agreement and Consent Order (FFACO) of 1996 (FFACO, 1996). CAU 139 consists of seven Corrective Action Sites (CASs) located in Areas 3, 4, 6, and 9 of the Nevada Test Site (NTS), which is located approximately 65 miles (mi) northwest of Las Vegas, Nevada (Figure 1). CAU 139 consists of the following CASs: CAS 03-35-01, Burn Pit; CAS 04-08-02, Waste Disposal Site; CAS 04-99-01, Contaminated Surface Debris; CAS 06-19-02, Waste Disposal Site/Burn Pit; CAS 06-19-03, Waste Disposal Trenches; CAS 09-23-01, Area 9 Gravel Gertie; and CAS 09-34-01, Underground Detection Station. Details of the site history and site characterization results for CAU 139 are provided in the approved Corrective Action Investigation Plan (CAIP) (U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office [NNSA/NSO], 2006) and in the approved Corrective Action Decision Document (CADD) (NNSA/NSO, 2007). The purpose of this Corrective Action Plan (CAP) is to present the detailed scope of work required to implement the recommended corrective actions as specified in Section 4.0 of the approved CADD (NNSA/NSO, 2007). The approved closure activities for CAU 139 include removal of soil and debris contaminated with plutonium (Pu)-239, excavation of geophysical anomalies, removal of surface debris, construction of an engineered soil cover, and implementation of use restrictions (URs). Table 1 presents a summary of CAS-specific closure activities and contaminants of concern (COCs). Specific details of the corrective actions to be performed at each CAS are presented in Section 2.0 of this report.

NSTec Environmental Restoration

2007-07-01T23:59:59.000Z

373

Project Management Plan for the Idaho National Engineering Laboratory Waste Isolation Pilot Plant Experimental Test Program  

SciTech Connect

EG&G Idaho, Inc. and Argonne National Laboratory-West (ANL-W) are participating in the Idaho National Engineering Laboratory`s (INEL`s) Waste Isolation Pilot Plant (WIPP) Experimental Test Program (WETP). The purpose of the INEL WET is to provide chemical, physical, and radiochemical data on transuranic (TRU) waste to be stored at WIPP. The waste characterization data collected will be used to support the WIPP Performance Assessment (PA), development of the disposal No-Migration Variance Petition (NMVP), and to support the WIPP disposal decision. The PA is an analysis required by the Code of Federal Regulations (CFR), Title 40, Part 191 (40 CFR 191), which identifies the processes and events that may affect the disposal system (WIPP) and examines the effects of those processes and events on the performance of WIPP. A NMVP is required for the WIPP by 40 CFR 268 in order to dispose of land disposal restriction (LDR) mixed TRU waste in WIPP. It is anticipated that the detailed Resource Conservation and Recovery Act (RCRA) waste characterization data of all INEL retrievably-stored TRU waste to be stored in WIPP will be required for the NMVP. Waste characterization requirements for PA and RCRA may not necessarily be identical. Waste characterization requirements for the PA will be defined by Sandia National Laboratories. The requirements for RCRA are defined in 40 CFR 268, WIPP RCRA Part B Application Waste Analysis Plan (WAP), and WIPP Waste Characterization Program Plan (WWCP). This Project Management Plan (PMP) addresses only the characterization of the contact handled (CH) TRU waste at the INEL. This document will address all work in which EG&G Idaho is responsible concerning the INEL WETP. Even though EG&G Idaho has no responsibility for the work that ANL-W is performing, EG&G Idaho will keep a current status and provide a project coordination effort with ANL-W to ensure that the INEL, as a whole, is effectively and efficiently completing the requirements for WETP.

Connolly, M.J.; Sayer, D.L.

1993-11-01T23:59:59.000Z

374

Utility Integrated Resource Planning: An Emerging Driver of NewRenewable Generation in the Western United States  

DOE Green Energy (OSTI)

In the United States, markets for renewable generation--especially wind power--have grown substantially in recent years. This growth is typically attributed to technology improvements and resulting cost reductions, the availability of federal tax incentives, and aggressive state policy efforts. But another less widely recognized driver of new renewable generation is poised to play a major role in the coming years: utility integrated resource planning (IRP). Common in the late-1980s to mid-1990s, but relegated to lesser importance as many states took steps to restructure their electricity markets in the late-1990s, IRP has re-emerged in recent years as an important tool for utilities and regulators, particularly in regions such as the western United States, where retail competition has failed to take root. As practiced in the United States, IRP is a formal process by which utilities analyze the costs, benefits, and risks of all resources available to them--both supply- and demand-side--with the ultimate goal of identifying a portfolio of resources that meets their future needs at lowest cost and/or risk. Though the content of any specific utility IRP is unique, all are built on a common basic framework: (1) development of peak demand and load forecasts; (2) assessment of how these forecasts compare to existing and committed generation resources; (3) identification and characterization of various resource portfolios as candidates to fill a projected resource deficiency; (4) analysis of these different ''candidate'' resource portfolios under base-case and alternative future scenarios; and finally, (5) selection of a preferred portfolio, and creation of a near-term action plan to begin to move towards that portfolio. Renewable resources were once rarely considered seriously in utility IRP. In the western United States, however, the most recent resource plans call for a significant amount of new wind power capacity. These planned additions appear to be motivated by the improved economics of wind power, an emerging understanding that wind integration costs are manageable, and a growing acceptance of wind by electric utilities. Equally important, utility IRPs are increasingly recognizing the inherent risks in fossil-based generation portfolios--especially natural gas price risk and the financial risk of future carbon regulation--and the benefits of renewable energy in mitigating those risks. This article, which is based on a longer report from Berkeley Lab,i examines how twelve investor-owned utilities (IOUs) in the western United States--Avista, Idaho Power, NorthWestern Energy (NWE), Portland General Electric (PGE), Puget Sound Energy (PSE), PacifiCorp, Public Service Company of Colorado (PSCo), Nevada Power, Sierra Pacific, Pacific Gas & Electric (PG&E), Southern California Edison (SCE), and San Diego Gas & Electric (SDG&E)--treat renewable energy in their most recent resource plans (as of July 2005). In aggregate, these twelve utilities supply approximately half of all electricity demand in the western United States. In reviewing these plans, our purpose is twofold: (1) to highlight the growing importance of utility IRP as a current and future driver of renewable generation in the United States, and (2) to suggest possible improvements to the methods used to evaluate renewable generation as a resource option. As such, we begin by summarizing the amount and types of new renewable generation planned as a result of these twelve IRPs. We then offer observations about the IRP process, and how it might be improved to more objectively evaluate renewable resources.

Bolinger, Mark; Wiser, Ryan

2005-09-25T23:59:59.000Z

375

An Integrated Computer Modeling Environment For Regional Land Use, Air Quality, And Transportation Planning  

E-Print Network (OSTI)

The Land Use, Air Quality, and Transportation Integrated Modeling Environment (LATIME) represents an integrated approach to computer modeling and simulation of land use allocation, travel demand, and mobile source emissions for the Albuquerque, New Mexico, area. This environment provides predictive capability combined with a graphical and geographical interface. The graphical interface shows the causal relationships between data and policy scenarios and supports alternative model formulations. Scenarios are launched from within a Geographic Information System (GIS), and data produced by each model component at each time step within a simulation is stored in the GIS. A menudriven query system is utilized to review link-based results and regional and areawide results. These results can also be compared across time or between alternative land use scenarios. Using this environment, policies can be developed and implemented based on comparative analysis, rather than on single-step future pr...

Charles Hanley Renewable; Norman L. Marshall; Charles J. Hanley; Charles J. Hanley

1997-01-01T23:59:59.000Z

376

CoalFleet RD&D Augmentation Plan for Integrated Gasification Combined Cycle (IGCC) Power Plants  

Science Conference Proceedings (OSTI)

Advanced, clean coal technologies such as integrated gasification combined cycle (IGCC) offer societies around the world the promise of efficient, affordable power generation at markedly reduced levels of emissions8212including "greenhouse gases" linked to global climate change8212relative to today's current fleet of coal-fired power plants. To help accelerate the development, demonstration, and market introduction of IGCC and other clean coal technologies, EPRI formed the CoalFleet for Tomorrow initiati...

2007-01-24T23:59:59.000Z

377

Integrating short-term demand response into long-term investment planning  

E-Print Network (OSTI)

mentioned sources of flexibility are offered by the supply-side of the power system. However, integration of smart grid technologies in the electric power system [5], for example though smart meters, creates opportunities to more efficiently balance... Cedric.DeJonghe@esat.kuleuven.be, Tel. +32 16 32 17 22, Fax +32 16 32 19 85 - University of Leuven (K.U.Leuven) Energy Institute, ELECTA branch (Electric Energy and Computer Architectures), Kasteelpark Arenberg 10 box 2445 / B-3001 Heverlee / Belgium...

De Jonghe, Cedric; Hobbs, Benjamin F.; Belmans, Ronnie

2011-03-20T23:59:59.000Z

378

Coupled hydrodynamic-structural analysis of an integral flowing sodium test loop in the TREAT reactor  

SciTech Connect

A hydrodynamic-structural response analysis of the Mark-IICB loop was performed for the TREAT (Transient Reactor Test Facility) test AX-1. Test AX-1 is intended to provide information concerning the potential for a vapor explosion in an advanced-fueled LMFBR. The test will be conducted in TREAT with unirradiated uranium-carbide fuel pins in the Mark-IICB integral flowing sodium loop. Our analysis addressed the ability of the experimental hardware to maintain its containment integrity during the reference accident postulated for the test. Based on a thermal-hydraulics analysis and assumptions for fuel-coolant interaction in the test section, a pressure pulse of 144 MPa maximum pressure and pulse width of 1.32 ms has been calculated as the reference accident. The response of the test loop to the pressure transient was obtained with the ICEPEL and STRAW codes. Modelling of the test section was completed with STRAW and the remainder of the loop was modelled by ICEPEL.

Zeuch, W.R.; A-Moneim, M.T.

1979-01-01T23:59:59.000Z

379

Interim Test Procedures for Evaluating Electrical Performance and Grid Integration of Vehicle-to-Grid Applications  

NLE Websites -- All DOE Office Websites (Extended Search)

Interim Test Procedures for Interim Test Procedures for Evaluating Electrical Performance and Grid Integration of Vehicle-to-Grid Applications S. Chakraborty, W. Kramer, B. Kroposki, G. Martin, P. McNutt, M. Kuss, T. Markel, and A. Hoke Technical Report NREL/TP-5500-51001 June 2011 NREL is a national laboratory of the U.S. Department of Energy, Office of Energy Efficiency & Renewable Energy, operated by the Alliance for Sustainable Energy, LLC. National Renewable Energy Laboratory 1617 Cole Boulevard Golden, Colorado 80401 303-275-3000 * www.nrel.gov Contract No. DE-AC36-08GO28308 Interim Test Procedures for Evaluating Electrical Performance and Grid Integration of Vehicle-to-Grid Applications S. Chakraborty, W. Kramer, B. Kroposki, G. Martin, P. McNutt, M. Kuss, T. Markel,

380

DOE/EA-1371; Integrated Natural Resources Management Plan, Environmental Assessment, and Finding of No Significant Impacts for Rock Creek Reserve (5/2001)  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

INTEGRATED NATURAL RESOURCES MANAGEMENT PLAN, ENVIRONMENTAL ASSESSMENT and Finding Of No Significant Impacts for ROCK CREEK RESERVE 2001-Closure DOE/EA - 1371 Department of Energy Rocky Flats Environmental Technology Site and The U.S. Fish & Wildlife Service May, 2001 Dear Stakeholder: Enclosed is the Final Rock Creek Reserve Integrated Natural Resources Management Plan (Plan), Environmental Assessment (EA), and Finding Of No Significant Impacts (FONSI). The Rock Creek Reserve was dedicated on May 17, 1999, to be jointly managed by the US Fish and Wildlife Service and US Department of Energy. This Plan/EA was developed in accordance with the National Environmental Policy Act (NEPA) process. Through cooperation with the U.S. Fish and Wildlife Service for joint

Note: This page contains sample records for the topic "integrated test plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


381

Comparative risk analysis for the Rocky Flats Plant integrated project planning  

Science Conference Proceedings (OSTI)

The Rocky Flats Plant is developing, with active stakeholder a comprehensive planning strategy that will support transition of the Rocky Flats Plant from a nuclear weapons production facility to site cleanup and final disposition. Final disposition of the Rocky Flats Plant materials and contaminants requires consideration of the interrelated nature of sitewide problems, such as material movement and disposition, facility and land use endstates, costs relative risks to workers and the public, and waste disposition. Comparative Risk Analysis employs both incremental risk and cumulative risk evaluations to compare risks from postulated options or endstates. These postulated options or endstates can be various remedial alternatives, or future endstate uses of federal agency land. Currently, there does not exist any approved methodology that aggregates various incremental risk estimates. Comparative Risk Analysis has been developed to aggregate various incremental risk estimates to develop a site cumulative risk estimate. This paper discusses development of the Comparative Risk Analysis methodology, stakeholder participation and lessons learned from these challenges.

Jones, M.E.; Shain, D.I.

1994-05-01T23:59:59.000Z

382

W-026 integrated engineering cold run operational test report for balance of plant (BOP)  

SciTech Connect

This Cold Run test is designed to demonstrate the functionality of systems necessary to move waste drums throughout the plant using approved procedures, and the compatibility of these systems to function as an integrated process. This test excludes all internal functions of the gloveboxes. In the interest of efficiency and support of the facility schedule, the initial revision of the test (rev 0) was limited to the following: Receipt and storage of eight overpacked drums, four LLW and four TRU; Receipt, routing, and staging of eleven empty drums to the process area where they will be used later in this test; Receipt, processing, and shipping of two verification drums (Route 9); Receipt, processing, and shipping of two verification drums (Route 1). The above listed operations were tested using the rev 0 test document, through Section 5.4.25. The document was later revised to include movement of all staged drums to and from the LLW and TRU process and RWM gloveboxes. This testing was performed using Sections 5.5 though 5.11 of the rev 1 test document. The primary focus of this test is to prove the functionality of automatic operations for all mechanical and control processes listed. When necessary, the test demonstrates manual mode operations as well. Though the gloveboxes are listed, only waste and empty drum movement to, from, and between the gloveboxes was tested.

Kersten, J.K.

1998-02-24T23:59:59.000Z

383

Developing an integrated ecological resource management and monitoring plan as part of an environmental management system  

SciTech Connect

Recent interest in defining the appropriate content of an Environmental Management System (EMS) as specified by ISO 14001 prompted a study to determine how ecological concerns should be integrated into an EMS and subsequently implemented. This paper describes an approach for developing objectives, targets, and processes for ecological resource management at those Department of Energy (DOE) facilities where an ecological resource management approach that goes beyond simple regulatory compliance is warranted. A major goal of this approach is to position DOE facilities so that they can proactively address ecological concerns, rather than being forced to respond retroactively to damage claims, restoration requirements, and/or bad publicity. Although DOE is not requiring ISO 14001 implementation at its facilities, it is recommending ISO 14001 as a voluntary approach to encourage good environmental practices, such as pollution prevention and sustainable development, by adopting an integrated systems approach. The DOE position is that existing DOE orders and policy statements are consistent with, and have elements of, the ISO 14001 EMS approach.

Michael, D.; Hooten, M. [Neptune and Co., Inc., Los Alamos, NM (United States); Kelly, E. [Los Alamos National Lab., NM (United States); Roy-Harrison, W. [USDOE, Washington, DC (United States)

1997-04-01T23:59:59.000Z

384

EBR-2 (Experimental Breeder Reactor-2), IFR (Integral Fast Reactor) prototype testing programs  

SciTech Connect

The Experimental Breeder Reactor-2 (EBR-2) is a sodium cooled power reactor supplying about 20 MWe to the Idaho National Engineering Laboratory (INEL) grid and, in addition, is the key component in the development of the Integral Fast Reactor (IFR). EBR-2's testing capability is extensive and has seen four major phases: (1) demonstration of LMFBR power plant feasibility, (2) irradiation testing for fuel and material development. (3) testing the off-normal performance of fuel and plant systems and (4) operation as the IFR prototype, developing and demonstrating the IFR technology associated with fuel and plant design. Specific programs being carried out in support of the IFR include advanced fuels and materials development and component testing. This paper discusses EBR-2 as the IFR prototype and the associated testing programs. 29 refs.

Lehto, W.K.; Sackett, J.I.; Lindsay, R.W. (Argonne National Lab., Idaho Falls, ID (USA). EBR-II Div. Argonne National Lab., IL (USA)); Planchon, H.P.; Lambert, J.D.B. (Argonne National Lab., IL (USA))

1990-01-01T23:59:59.000Z

385

ERRATA SHEET for Corrective Action Plan for Corrective Action Unit 490: Station 44 Burn Area, Tonopah Test Range, Nevada  

SciTech Connect

Section 2.1.1.3 of the Table of Contents reference on Page v and on Page 12 of the Corrective Action Plan for Corrective Action Unit 490: Station 44 Burn Area, Tonopah Test Range, Nevada erroneously refers to the Nevada Environmental Policy Act Determination. The correct title of the referenced document is the National Environmental Policy Act Determination.

K. B. Campbell

2002-04-01T23:59:59.000Z

386

Geopressured-geothermal drilling and testing plan: Magma Gulf/Technadril-Dept. of Energy MGT-DOE AMOCO Fee No. 1 well, Cameron Parish, Lousiana  

DOE Green Energy (OSTI)

The following topics are covered: generalized site activities, occupational health and safety, drilling operations, production testing, environmental assessment and monitoring plan, permits, program management, reporting, and schedule. (MHR)

Not Available

1980-07-01T23:59:59.000Z

387

Corrective Action Plan for Corrective Action Unit 543: Liquid Disposal Units, Nevada Test Site, Nevada  

Science Conference Proceedings (OSTI)

Corrective Action Unit (CAU) 543: Liquid Disposal Units is listed in Appendix III of the ''Federal Facility Agreement and Consent Order'' (FFACO) which was agreed to by the state of Nevada, the U.S. Department of Energy (DOE), and the U.S. Department of Defense (FFACO, 1996). CAU 543 sites are located in Areas 6 and 15 of the Nevada Test Site (NTS), which is approximately 65 miles northwest of Las Vegas, Nevada. CAU 543 consists of the following seven Corrective Action Sites (CASs) (Figure 1): CAS 06-07-01, Decon Pad; CAS 15-01-03, Aboveground Storage Tank; CAS 15-04-01, Septic Tank; CAS 15-05-01, Leachfield; CAS 15-08-01, Liquid Manure Tank; CAS 15-23-01, Underground Radioactive Material Area; and CAS 15-23-03, Contaminated Sump, Piping. All Area 15 CASs are located at the former U.S. Environmental Protection Agency (EPA) Farm, which operated from 1963 to 1981 and was used to support animal experiments involving the uptake of radionuclides. Each of the Area 15 CASs, except CAS 15-23-01, is associated with the disposal of waste effluent from Building 15-06, which was the primary location of the various tests and experiments conducted onsite. Waste effluent disposal from Building 15-06 involved piping, sumps, outfalls, a septic tank with leachfield, underground storage tanks, and an aboveground storage tank (AST). CAS 15-23-01 was associated with decontamination activities of farm equipment potentially contaminated with radiological constituents, pesticides, and herbicides. While the building structures were removed before the investigation took place, all the original tanks, sumps, piping, and concrete building pads remain in place. The Area 6 CAS is located at the Decontamination Facility in Area 6, a facility which operated from 1971 to 2001 and was used to decontaminate vehicles, equipment, clothing, and other materials that had become contaminated during nuclear testing activities. The CAS includes the effluent collection and distribution systems for Buildings 6-605, 6-606, and 6-607, which consists of septic tanks, sumps, piping, floor drains, drain trenches, cleanouts, and a concrete foundation. Additional details of the site history are provided in the CAU 543 Corrective Action Investigation Plan (CAIP) (U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office [NNSA/NSO], 2004a), and the CAU 543 Corrective Action Decision Document (CADD) (NNSA/NSO, 2005).

NSTec Environmental Restoration

2007-04-01T23:59:59.000Z

388

California Energy Commission Public Interest Energy Research/Energy System Integration -- Transmission-Planning Research & Development Scoping Project  

E-Print Network (OSTI)

Energy Research/ Energy System Integration Transmission-Research Program Energy System Integration Public InterestCommissions PIER Energy Systems Integration program for

Eto, Joseph H.; Lesieutre, Bernard; Widergren, Steven

2004-01-01T23:59:59.000Z

389

Use of Frequency Response Metrics to Assess the Planning and Operating Requirements for Reliable Integration of Variable Renewable Generation  

E-Print Network (OSTI)

Report - 2006 Minnesota Wind Integration Study Volume I.NREL). 2010. Eastern Wind Integration and TransmissionAvista Corporation Wind Integration Study. March. http://

Eto, Joseph H.

2011-01-01T23:59:59.000Z

390

Use of Frequency Response Metrics to Assess the Planning and Operating Requirements for Reliable Integration of Variable Renewable Generation  

E-Print Network (OSTI)

Integration of Variable Renewable Generation The report isISO (CAISO). 2007. Integration of Renewable Resources.recommendations for integrating renewable resources on the

Eto, Joseph H.

2011-01-01T23:59:59.000Z

391

Integral Benchmark Data for Nuclear Data Testing Through the ICSBEP & IRPhEP  

Science Conference Proceedings (OSTI)

The status of the International Criticality Safety Benchmark Evaluation Project (ICSBEP) and International Reactor Physics Experiment Evaluation Project (IRPhEP) was last discussed directly with the nuclear data community at ND2007. Since ND2007, integral benchmark data that are available for nuclear data testing have increased significantly. The status of the ICSBEP and the IRPhEP is discussed and selected benchmark configurations that have been added to the ICSBEP and IRPhEP Handbooks since ND2007 are highlighted.

J. Blair Briggs; John D. Bess; Jim Gulliford; Ian Hill

2013-10-01T23:59:59.000Z

392

Reversible Bending Fatigue Test System for Investigating Vibration Integrity of Spent Nuclear Fuel during Transportation  

SciTech Connect

Transportation packages for spent nuclear fuel (SNF) must meet safety requirements under normal and accident conditions as specified by federal regulations. During transportation, SNF experiences unique conditions and challenges to cladding integrity due to the vibrational and impact loading during road or rail shipment. Oak Ridge National Laboratory (ORNL) has been developing testing capabilities that can be used to improve the understanding of the impacts on SNF integrity due to vibration loading, especially for high burn-up SNF in normal transportation operation conditions. This information can be used to meet the nuclear industry and U.S. Nuclear Regulatory Commission needs in the area of safety and security of spent nuclear fuel storage and transport operations. The ORNL developed test system can perform reversible-bending fatigue testing to evaluate both the static and dynamic mechanical response of SNF rods under simulated loads. The testing apparatus is also designed to meet the challenges of hot-cell operation, including remote installation and detachment of the SNF test specimen, in-situ test specimen deformation measurement, and implementation of a driving system suitable for use in a hot cell. The system contains a U-frame set-up equipped with uniquely designed grip rigs, to protect SNF rod and to ensure valid test results, and use of 3 specially designed LVDTs to obtain the in-situ curvature measurement. A variety of surrogate test rods have been used to develop and calibrate the test system as well as in performing a series of systematic cyclic fatigue tests. The surrogate rods include stainless steel (SS) cladding, SS cladding with cast epoxy, and SS cladding with alumina pellets inserts simulating fuel pellets. Testing to date has shown that the interface bonding between the SS cladding and the alumina pellets has a significant impact on the bending response of the test rods as well as their fatigue strength. The failure behaviors observed from tested surrogate rods provides a fundamental understanding of the underlying failure mechanisms of the SNF surrogate rod under vibration which has not been achieved previously. The newly developed device is scheduled to be installed in the hot-cell in summer 2013 to test high burnup SNF.

Wang, Jy-An John [ORNL; Wang, Hong [ORNL; Bevard, Bruce Balkcom [ORNL; Howard, Rob L [ORNL; Flanagan, Michelle [U.S. Nuclear Regulatory Commission

2013-01-01T23:59:59.000Z

393

Corrective Action Investigation Plan for Corrective Action Unit 232: Area 25 Sewage Lagoons, Nevada Test Site, Nevada, Revision 0  

Science Conference Proceedings (OSTI)

The Corrective Action Investigation Plan for Corrective Action Unit 232, Area 25 Sewage Lagoons, has been developed in accordance with the Federal Facility Agreement and Consent Order that was agreed to by the U.S. Department of Energy, Nevada Operations Office; the State of Nevada Division of Environmental Protection; and the U. S. Department of Defense. Corrective Action Unit 232 consists of Corrective Action Site 25-03-01, Sewage Lagoon. Corrective Action Unit 232, Area 25 Sewage Lagoons, received sanitary effluent from four buildings within the Test Cell ''C'' Facility from the mid-1960s through approximately 1996. The Test Cell ''C'' Facility was used to develop nuclear propulsion technology by conducting nuclear test reactor studies. Based on the site history collected to support the Data Quality Objectives process, contaminants of potential concern include volatile organic compounds, semivolatile organic compounds, Resource Conservation and Recovery Act metals, petroleum hydrocarbons, polychlorinated biphenyls, pesticides, herbicides, gamma emitting radionuclides, isotopic plutonium, isotopic uranium, and strontium-90. A detailed conceptual site model is presented in Section 3.0 and Appendix A of this Corrective Action Investigation Plan. The conceptual model serves as the basis for the sampling strategy. Under the Federal Facility Agreement and Consent Order, the Corrective Action Investigation Plan will be submitted to the Nevada Division of Environmental Protection for approval. Field work will be conducted following approval of the plan. The results of the field investigation will support a defensible evaluation of corrective action alternatives in the Corrective Action Decision Document.

USDOE /NV

1999-05-01T23:59:59.000Z

394

Barrier erosion control test plan: Gravel mulch, vegetation, and soil water interactions  

Science Conference Proceedings (OSTI)

Soil erosion could reduce the water storage capacity of barriers that have been proposed for the disposal of near-surface waste at the US Department of Energy's Hanford Site. Gravel mixed into the top soil surface may create a self-healing veneer that greatly retards soil loss. However, gravel admixtures may also enhance infiltration of rainwater, suppress plant growth and water extraction, and lead to the leaching of underlying waste. This report describes plans for two experiments that were designed to test hypotheses concerning the interactive effects of surface gravel admixtures, revegetation, and enhanced precipitation on soil water balance and plant abundance. The first experiment is a factorial field plot set up on the site selected as a soil borrow area for the eventual construction of barriers. The treatments, arranged in a a split-split-plot design structure, include two densities of gravel admix, a mixture of native and introduced grasses, and irrigation to simulate a wetter climate. Changes in soil water storage and plant cover are monitored with neutron moisture probes and point intercept sampling, respectively. The second experiment consists of an array of 80 lysimeters containing several different barrier prototypes. Surface treatments are similar to the field-plot experiment. Drainage is collected from a valve at the base of each lysimeter tube, and evapotranspiration is estimated by subtraction. The lysimeters are also designed to be coupled to a whole-plant gas exchange system that will be used to conduct controlled experiments on evapotranspiration for modeling purposes. 56 refs., 6 figs., 8 tabs.

Waugh, W.J.; Link, S.O. (Pacific Northwest Lab., Richland, WA (USA))

1988-07-01T23:59:59.000Z

395

Mt. Hood geothermal exploratory drilling and testing plan. Old Maid Flat holes No. 1 and No. 7A  

DOE Green Energy (OSTI)

This plan has been prepared to establish the objectives and set forth the procedures and guidelines for conducting geothermal exploratory drilling and testing operations in the Old Maid Flat area of Mt. Hood, Oregon, approximately 50 miles east of Portland. The project will be conducted on lands within the Mt. Hood National Forest, which are currently under Federal Lease OR 13994 to the Northwest Geothermal Corporation. The exploratory geothermal operations will consist of (1) testing an existing 4,000-foot temperature gradient hole to determine the quality of geothermal fluids, and (2) drilling and testing a new 5,000-foot hole to determine overall geothermal reservoir characteristics.

Not Available

1980-05-01T23:59:59.000Z

396

Plans for Crash-Tested Bridge Railings for Longitudinal Wood Decks on Low-Volume Roads  

E-Print Network (OSTI)

The plans for crashworthy bridge railings for low-volume roads were developed through a cooperative research program involving the USDA Forest Service, Forest Products Laboratory (FPL); the Midwest Roadside Safety Facility, University of Nebraska-Lincoln

United States; Forest Service; Michael A. Ritter; Ronald K. Faller; Steve Bunnell; Paula D. Hilbrich Lee; Barry T. Rosson Abstract

1998-01-01T23:59:59.000Z

397

DOE/EA-1371; Integrated Natural Resources Management Plan, Environmental Assessment, and Finding of No Significant Impacts for Rock Creek Reserve (5/2001)  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Finding of No Significant Impact Finding of No Significant Impact Integrated Natural Resources Management Plan and Environmental Assessment for Rock Creek Reserve Summary: The Department of Energy (DOE) with the assistance and cooperation of the US. Fish and Wildlife Service, prepared an Integrated Natural Resources Management Plan and Environmental Assessment (Plan)(DOE/EA-1371) for the Rock Creek Reserve at the Rocky Flats Environmental Technology Site (Site) located north of Golden, Colorado. The Rock Creek Reserve was established in May 1999 in recognition of the area's biological significance. Although still under the ownership of the DOE, the Rock Creek Reserve will be co- managed with the U. S. Fish and Wildlife Service as part of an interagency agreement signed by these two

398

Test plan for evaluation of plasma melter technology for vitrification of high-sodium content low-level radioactive liquid wastes  

SciTech Connect

This document provides a test plan for the conduct of plasma arc vitrification testing by a vendor in support of the Hanford Tank Waste Remediation System (TWRS) Low-Level Waste (LLW) Vitrification Program. The vendor providing this test plan and conducting the work detailed within it [one of seven selected for glass melter testing under Purchase Order MMI-SVV-384212] is the Westinghouse Science and Technology Center (WSTC) in Pittsburgh, PA. WSTC authors of the test plan are D. F. McLaughlin, E. J. Lahoda, W. R. Gass, and N. D`Amico. The WSTC Program Manager for this test is D. F. McLaughlin. This test plan is for Phase I activities described in the above Purchase Order. Test conduct includes melting of glass frit with Hanford LLW Double-Shell Slurry Feed waste simulant in a plasma arc fired furnace.

McLaughlin, D.F.; Lahoda, E.J.; Gass, W.R.; D`Amico, N. [ed.

1994-10-20T23:59:59.000Z

399

Test plan for glass melter system technologies for vitrification of high-sodium content low-level radioactive liquid waste, Project No. RDD-43288  

Science Conference Proceedings (OSTI)

This document provides a test plan for the conduct of combustion fired cyclone vitrification testing by a vendor in support of the Hanford Tank Waste Remediation System, Low-Level Waste Vitrification Program. The vendor providing this test plan and conducting the work detailed within it is the Babcock & Wilcox Company Alliance Research Center in Alliance, Ohio. This vendor is one of seven selected for glass melter testing.

Higley, B.A.

1995-03-15T23:59:59.000Z

400

W-026 acceptance test plan plant control system software (submittal {number_sign} 216)  

Science Conference Proceedings (OSTI)

Acceptance Testing of the WRAP 1 Plant Control System software will be conducted throughout the construction of WRAP 1 with final testing on the glovebox software being completed in December 1996. The software tests will be broken out into five sections; one for each of the four Local Control Units and one for the supervisory software modules. The acceptance test report will contain completed copies of the software tests along with the applicable test log and completed Exception Test Reports.

Watson, T.L., Fluor Daniel Hanford

1997-02-14T23:59:59.000Z

Note: This page contains sample records for the topic "integrated test plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


401

Work plan for transition of SY-101 hydrogen mitigation test project data acquisition and control system (DACS-1)  

DOE Green Energy (OSTI)

The purpose of this effort is to transfer operating and maintenance responsibility for the 241-SY-101 data acquisition and control system (DACS-1) from Los Alamos National Laboratory to Westinghouse Hanford Company. This work plan defines the tasks required for a successful turnover. It identifies DACS-1 transition, deliverables, responsible organizations and individuals, interfaces, cost, and schedule. The transition plan will discuss all required hardware, software, documentation, maintenance, operations, and training for use at Hanford Waste Tank 241-SY-101. The transfer of responsibilities for DACS-1 to WHC is contingent on final approval of applicable Acceptance for Beneficial Use documentation by Waste Tank Operations. The DACS-1 was designed to provide data monitoring, display, and storage for Tank 241-SY-101. The DACS-1 also provides alarm and control of all the hydrogen mitigation testing systems, as well as ancillary systems and equipment (HVAC, UPS, etc.) required to achieve safe and reliable operation of the testing systems in the tank.

McClees, J.; Truitt, R.W.

1994-10-12T23:59:59.000Z

402

An experimental test plan for the characterization of molten salt thermochemical properties in heat transport systems  

SciTech Connect

Molten salts are considered within the Very High Temperature Reactor program as heat transfer media because of their intrinsically favorable thermo-physical properties at temperatures starting from 300 C and extending up to 1200 C. In this context two main applications of molten salt are considered, both involving fluoride-based materials: as primary coolants for a heterogeneous fuel reactor core and as secondary heat transport medium to a helium power cycle for electricity generation or other processing plants, such as hydrogen production. The reference design concept here considered is the Advanced High Temperature Reactor (AHTR), which is a large passively safe reactor that uses solid graphite-matrix coated-particle fuel (similar to that used in gas-cooled reactors) and a molten salt primary and secondary coolant with peak temperatures between 700 and 1000 C, depending upon the application. However, the considerations included in this report apply to any high temperature system employing fluoride salts as heat transfer fluid, including intermediate heat exchangers for gas-cooled reactor concepts and homogenous molten salt concepts, and extending also to fast reactors, accelerator-driven systems and fusion energy systems. The purpose of this report is to identify the technical issues related to the thermo-physical and thermo-chemical properties of the molten salts that would require experimental characterization in order to proceed with a credible design of heat transfer systems and their subsequent safety evaluation and licensing. In particular, the report outlines an experimental R&D test plan that would have to be incorporated as part of the design and operation of an engineering scaled facility aimed at validating molten salt heat transfer components, such as Intermediate Heat Exchangers. This report builds on a previous review of thermo-physical properties and thermo-chemical characteristics of candidate molten salt coolants that was generated as part of the same project [1]. However, this work focuses on two materials: the LiF-BeF2 eutectic (67 and 33 mol%, respectively, also known as flibe) as primary coolant and the LiF-NaF-KF eutectic (46.5, 11.5, and 52 mol%, respectively, also known as flinak) as secondary heat transport fluid. At first common issues are identified, involving the preparation and purification of the materials as well as the development of suitable diagnostics. Than issues specific to each material and its application are considered, with focus on the compatibility with structural materials and the extension of the existing properties database.

Pattrick Calderoni

2010-09-01T23:59:59.000Z

403

Corrective Action Plan for Corrective Action Unit 563: Septic Systems, Nevada Test Site, Nevada  

SciTech Connect

This Corrective Action Plan (CAP) has been prepared for Corrective Action Unit (CAU) 563, Septic Systems, in accordance with the Federal Facility Agreement and Consent Order. CAU 563 consists of four Corrective Action Sites (CASs) located in Areas 3 and 12 of the Nevada Test Site. CAU 563 consists of the following CASs: #2; CAS 03-04-02, Area 3 Subdock Septic Tank #2; CAS 03-59-05, Area 3 Subdock Cesspool #2; CAS 12-59-01, Drilling/Welding Shop Septic Tanks #2; CAS 12-60-01, Drilling/Welding Shop Outfalls Site characterization activities were performed in 2007, and the results are presented in Appendix A of the CAU 563 Corrective Action Decision Document. The scope of work required to implement the recommended closure alternatives is summarized below. #2; CAS 03-04-02, Area 3 Subdock Septic Tank, contains no contaminants of concern (COCs) above action levels. No further action is required for this site; however, as a best management practice (BMP), all aboveground features (e.g., riser pipes and bumper posts) will be removed, the septic tank will be removed, and all open pipe ends will be sealed with grout. #2; CAS 03-59-05, Area 3 Subdock Cesspool, contains no COCs above action levels. No further action is required for this site; however, as a BMP, all aboveground features (e.g., riser pipes and bumper posts) will be removed, the cesspool will be abandoned by filling it with sand or native soil, and all open pipe ends will be sealed with grout. #2; CAS 12-59-01, Drilling/Welding Shop Septic Tanks, will be clean closed by excavating approximately 4 cubic yards (yd3) of arsenic- and chromium-impacted soil. In addition, as a BMP, the liquid in the South Tank will be removed, the North Tank will be removed or filled with grout and left in place, the South Tank will be filled with grout and left in place, all open pipe ends will be sealed with grout or similar material, approximately 10 yd3 of chlordane-impacted soil will be excavated, and debris within the CAS boundary will be removed. #2; CAS 12-60-01, Drilling/Welding Shop Outfalls, contains no COCs above action levels. No further action is required for this site; however, as a BMP, three drain pipe openings will be sealed with grout.

NSTec Environmental Restoration

2009-03-31T23:59:59.000Z

404

Generation IV Reactors Integrated Materials Technology Program Plan: Focus on Very High Temperature Reactor Materials  

Science Conference Proceedings (OSTI)

Since 2002, the Department of Energy's (DOE's) Generation IV Nuclear Energy Systems (Gen IV) Program has addressed the research and development (R&D) necessary to support next-generation nuclear energy systems. The six most promising systems identified for next-generation nuclear energy are described within this roadmap. Two employ a thermal neutron spectrum with coolants and temperatures that enable hydrogen or electricity production with high efficiency (the Supercritical Water Reactor-SCWR and the Very High Temperature Reactor-VHTR). Three employ a fast neutron spectrum to enable more effective management of actinides through recycling of most components in the discharged fuel (the Gas-cooled Fast Reactor-GFR, the Lead-cooled Fast Reactor-LFR, and the Sodium-cooled Fast Reactor-SFR). The Molten Salt Reactor (MSR) employs a circulating liquid fuel mixture that offers considerable flexibility for recycling actinides and may provide an alternative to accelerator-driven systems. At the inception of DOE's Gen IV program, it was decided to significantly pursue five of the six concepts identified in the Gen IV roadmap to determine which of them was most appropriate to meet the needs of future U.S. nuclear power generation. In particular, evaluation of the highly efficient thermal SCWR and VHTR reactors was initiated primarily for energy production, and evaluation of the three fast reactor concepts, SFR, LFR, and GFR, was begun to assess viability for both energy production and their potential contribution to closing the fuel cycle. Within the Gen IV Program itself, only the VHTR class of reactors was selected for continued development. Hence, this document will address the multiple activities under the Gen IV program that contribute to the development of the VHTR. A few major technologies have been recognized by DOE as necessary to enable the deployment of the next generation of advanced nuclear reactors, including the development and qualification of the structural materials needed to ensure their safe and reliable operation. The focus of this document will be the overall range of DOE's structural materials research activities being conducted to support VHTR development. By far, the largest portion of material's R&D supporting VHTR development is that being performed directly as part of the Next-Generation Nuclear Plant (NGNP) Project. Supplementary VHTR materials R&D being performed in the DOE program, including university and international research programs and that being performed under direct contracts with the American Society for Mechanical Engineers (ASME) Boiler and Pressure Vessel Code, will also be described. Specific areas of high-priority materials research that will be needed to deploy the NGNP and provide a basis for subsequent VHTRs are described, including the following: (1) Graphite: (a) Extensive unirradiated materials characterization and assessment of irradiation effects on properties must be performed to qualify new grades of graphite for nuclear service, including thermo-physical and mechanical properties and their changes, statistical variations from billot-to-billot and lot-to-lot, creep, and especially, irradiation creep. (b) Predictive models, as well as codification of the requirements and design methods for graphite core supports, must be developed to provide a basis for licensing. (2) Ceramics: Both fibrous and load-bearing ceramics must be qualified for environmental and radiation service as insulating materials. (3) Ceramic Composites: Carbon-carbon and SiC-SiC composites must be qualified for specialized usage in selected high-temperature components, such as core stabilizers, control rods, and insulating covers and ducting. This will require development of component-specific designs and fabrication processes, materials characterization, assessment of environmental and irradiation effects, and establishment of codes and standards for materials testing and design requirements. (4) Pressure Vessel Steels: (a) Qualification of short-term, high-temperature properties of light water rea

Corwin, William R [ORNL; Burchell, Timothy D [ORNL; Katoh, Yutai [ORNL; McGreevy, Timothy E [ORNL; Nanstad, Randy K [ORNL; Ren, Weiju [ORNL; Snead, Lance Lewis [ORNL; Wilson, Dane F [ORNL

2008-08-01T23:59:59.000Z

405

Solar test of an integrated sodium reflux heat pipe receiver/reactor for thermochemical energy transport  

DOE Green Energy (OSTI)

A chemical reactor for carbon dioxide reforming of methane was integrated into a sodium reflux heat pipe receiver and tested in the solar furnace of the Weizmann Institute of Science, Rehovot, Israel. The receiver/reactor was a heat pipe with seven tubes inside an evacuated metal box containing sodium. The catalyst, 0.5 wt% Rh on alumina, filled two of the tubes with the front surface of the box serving as the solar absorber. In operation, concentrated sunlight heated the front plate and vaporized sodium from a wire mesh wick attached to other side. Sodium vapor condensed on the reactor tubes, releasing latent heat and returning to the wick by gravity. The receiver system performed satisfactorily in many tests under varying flow conditions. The maximum power absorbed was 7.5 kW at temperatures above 800C. The feasibility of operating a heat pipe receiver/reactor under solar conditions was proven, and the advantages of reflux devices confirmed.

Diver, R.B.; Fish, J.D. (Sandia National Labs., Albuquerque, NM (United States)); Levitan, R.; Levy, M.; Meirovitch, E.; Rosin, H. (Weizmann Inst. of Science, Rehovot (Israel)); Paripatyadar, S.A.; Richardson, J.T. (Univ. of Houston, TX (United States))

1992-01-01T23:59:59.000Z

406

Streamlined Approach for Environmental Restoration Work Plan for Corrective Action Unit 461: Joint Test Assembly Sites and Corrective Action Unit 495: Unconfirmed Joint Test Assembly Sites Tonopah Test Range, Nevada  

SciTech Connect

This Streamlined Approach for Environmental Restoration plan addresses the action necessary for the clean closure of Corrective Action Unit 461 (Test Area Joint Test Assembly Sites) and Corrective Action Unit 495 (Unconfirmed Joint Test Assembly Sites). The Corrective Action Units are located at the Tonopah Test Range in south central Nevada. Closure for these sites will be completed by excavating and evaluating the condition of each artillery round (if found); detonating the rounds (if necessary); excavating the impacted soil and debris; collecting verification samples; backfilling the excavations; disposing of the impacted soil and debris at an approved low-level waste repository at the Nevada Test Site

Jeff Smith

1998-08-01T23:59:59.000Z

407

Acceptance Test Plan for Fourth-Generation Hanford Corrosion Probe Tree Assembly  

SciTech Connect

This Acceptance Test Procedure (ATP) will document the satisfactory operation of the corrosion probe tree assembly. This ATP will be performed by the manufacturer prior to delivery to the site. The objective of this procedure is to demonstrate and document the acceptance of the corrosion probe tree assembly. The test will consist of a pressure test to verify leak tightness of the probe tree body, a continuity test of the probe tree wiring, a test of the high level detector wiring, and a test of the operation of the Type K thermocouples.

NORMAN, E.C.

2000-10-17T23:59:59.000Z

408

W-026 acceptance test plan plant control system hardware (submittal {number_sign} 216)  

SciTech Connect

Acceptance Testing of the WRAP 1 Plant Control System Hardware will be conducted throughout the construction of WRAP I with the final testing on the Process Area hardware being completed in November 1996. The hardware tests will be broken out by the following functional areas; Local Control Units, Operator Control Stations in the WRAP Control Room, DMS Server, PCS Server, Operator Interface Units, printers, DNS terminals, WRAP Local Area Network/Communications, and bar code equipment. This document will contain completed copies of each of the hardware tests along with the applicable test logs and completed test exception reports.

Watson, T.L., Fluor Daniel Hanford

1997-02-14T23:59:59.000Z

409

Corrective Action Investigation Plan for Corrective Action Unit 528: Polychlorinated Biphenyls Contamination, Nevada Test Site, Nevada, Rev. 0  

DOE Green Energy (OSTI)

This Corrective Action Investigation Plan contains the U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office's approach to collect the data necessary to evaluate corrective action alternatives appropriate for the closure of Corrective Action Unit (CAU) 528, Polychlorinated Biphenyls Contamination (PCBs), Nevada Test Site (NTS), Nevada, under the Federal Facility Agreement and Consent Order. Located in the southwestern portion of Area 25 on the NTS in Jackass Flats (adjacent to Test Cell C [TCC]), CAU 528 consists of Corrective Action Site 25-27-03, Polychlorinated Biphenyls Surface Contamination. Test Cell C was built to support the Nuclear Rocket Development Station (operational between 1959 and 1973) activities including conducting ground tests and static firings of nuclear engine reactors. Although CAU 528 was not considered as a direct potential source of PCBs and petroleum contamination, two potential sources of contamination have nevertheless been identified from an unknown source in concentrations that could potentially pose an unacceptable risk to human health and/or the environment. This CAU's close proximity to TCC prompted Shaw to collect surface soil samples, which have indicated the presence of PCBs extending throughout the area to the north, east, south, and even to the edge of the western boundary. Based on this information, more extensive field investigation activities are being planned, the results of which are to be used to support a defensible evaluation of corrective action alternatives in the corrective action decision document.

U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office

2003-05-08T23:59:59.000Z

410

Constructing optimal drug-testing plans using a Bayesian acceptance sampling model  

Science Conference Proceedings (OSTI)

Drug testing has become an accepted strategy for controlling drug use, particularly among individuals in the custody of the criminal justice system. Emphasis has been placed on testing those free in the community, either on pretrial release, probation, ...

Joanna R Baker; Pamela K Lattimore; Lance A Matheson

1993-01-01T23:59:59.000Z

411

Management Plan: Demonstration testing and evaluation of in situ soil heating  

Science Conference Proceedings (OSTI)

In this project IITRI will demonstrate an in situ soil heating technology for the removal of hazardous organic contaminants present in the soil. In Situ heating will be accomplished by the application of 60 Hz AC power to the soil. The soil will be heated to a temperature of about 90{degree}C. This technology is suited for the removal of those organic compounds which have a normal boiling point in the range of 100{degree} to 210{degree}C, or else for those which exhibit a pure component vapor pressure of at least 10 mm Hg in the 90{degree} to 100{degree}C temperature range. For example, perchloroethylene, dichlorobenzene, trichlorobenzene, etc. may be removed by in situ AC heating. It is planned to demonstrate the technology by heating approximately 400 tons of soil in the K-1070 Classified Burial Ground located at DOE`s K-25 Site located in Oak Ridge, TN. It is estimated that the heating portion of the demonstration will take approximately 3 weeks at an average power input rate of 150 to 175 kill. IITRI expects to spend considerable time in the front end reviewing site characteristics, preparing detail design, developing Health and Safety Plans and other documents needed to obtain regulatory approval for the demonstration, arranging for site sampling, infrastructure development and document preparation. It is anticipated that site activities will begin in approximately 5 to 6 months. This contract was signed on September 30, 1993. IITRI started work on it in October 1993. It is planned to complete the demonstration and submit approved final reports by September 30, 1994. This project has 12 tasks and four major milestones. The major milestones and their planned completion dates are presented.

Dev, H.

1993-11-01T23:59:59.000Z

412

Common Information Model (CIM) 2012 Update: EPRI Development, Testing Activity, and Plans  

Science Conference Proceedings (OSTI)

This report provides a synopsis of the Electric Power Research Institutes (EPRIs) plan for Common Information Model (CIM) support going forward. This report also includes the activity of the International Electrotechnical Commission (IEC) Technical Committee (TC) Working Groups 13 and 14 for the year 2012. Additionally, it incorporates the proceedings of the two CIM International User Group meetings in Windsor, England, and New Orleans, Louisiana, in 2012. Finally, executive summaries ...

2013-03-20T23:59:59.000Z

413

Generalized beta prior models on fraction defective in reliability test planning  

Science Conference Proceedings (OSTI)

In many reliability analyses, the probability of obtaining a defective unit in a production process should not be considered constant even though the process is stable and in control. Engineering experience or previous data of similar or related products ... Keywords: 62N03, 62N05, Average producer and consumer risks, Generalized beta distribution, Maximum entropy prior, Quantiles, Reliability demonstration sampling plan, Shifted exponential distribution

Arturo J. Fernndez; Carlos J. Prez-Gonzlez

2012-07-01T23:59:59.000Z

414

Work plan for upgrade of SY-101 Hydrogen Mitigation Test Project Data Acquisition and Control System (DACS-1)  

DOE Green Energy (OSTI)

The purpose of this effort is to upgrade the existing DACS-1 used for control and data acquisition in support of the hydrogen mitigation program for tank 101-SY. The planned upgrades will enhance the system capabilities to support additional mitigation projects and improve the system operability by implementing changes identified during operation of the system to date. Once the upgrades have been implemented, the DACS-1 system should operate as it did prior to the upgrade, but with greatly increased speed and capability. No retraining of Test Engineers will be required; the upgrade is designed to be transparent to those who operate it, with only a noticeable increase in the speed of the system. This work plan defines the tasks required for implementing the upgrade. It identifies deliverables, responsible organizations and individuals, interfaces, and schedule. This upgrade effort employs system engineering principles wherever applicable.

Truitt, R.W.

1994-08-01T23:59:59.000Z

415

Verification/acceptance test plan/procedure for Acromag calibration system  

SciTech Connect

The purpose of this document is to describe and document the test of the Acromag calibration system software. The purpose of this test is to verify that the Acromag Calibration System (ACS) will reliably test the Acromag thermocouple (TC) type input modules and provide a file showing the temperatures at which the modules are tested, the response rom the Acromag station, instrument data, technician data, and date and time of the test. The ACS consists of a thermocouple calibration unit (TCU), a DOS based computer, a hand held resistance temperature detector (RTD) surface probe and connects to a field installed or a bench Acromag unit.

Fordham, C.R.

1994-12-01T23:59:59.000Z

416

Test Planning for Mixed-Signal SOCs with Wrapped Analog Cores  

E-Print Network (OSTI)

Many SOCs today contain both digital and analog embedded cores. Even though the test cost for such mixed-signal SOCs is significantly higher than that for digital SOCs, most prior research in this area has focused exclusively on digital cores. We propose a low-cost test development methodology for mixed-signal SOCs that allows the analog and digital cores to be tested in a unified manner, thereby minimizing the overall test cost. The analog cores in the SOC are wrapped such that they can be accessed using a digital test access mechanism (TAM). We evaluate the impact of the use of analog test wrappers on area overhead and test time. To reduce area overhead, we present an analog test wrapper optimization technique, which is then combined with TAM optimization in a cost-oriented heuristic approach for test scheduling. We also demonstrate the feasibility of using analog wrappers by presenting transistor-level simulations for an analog wrapper and a representative core. We present experimental results on test sche...

Sehgal, Anuja; Ozev, Sule; Chakrabarty, Krishnendu

2011-01-01T23:59:59.000Z