National Library of Energy BETA

Sample records for initial capital costs

  1. Transmission line capital costs

    SciTech Connect (OSTI)

    Hughes, K.R.; Brown, D.R.

    1995-05-01

    The displacement or deferral of conventional AC transmission line installation is a key benefit associated with several technologies being developed with the support of the U.S. Department of Energy`s Office of Energy Management (OEM). Previous benefits assessments conducted within OEM have been based on significantly different assumptions for the average cost per mile of AC transmission line. In response to this uncertainty, an investigation of transmission line capital cost data was initiated. The objective of this study was to develop a database for preparing preliminary estimates of transmission line costs. An extensive search of potential data sources identified databases maintained by the Bonneville Power Administration (BPA) and the Western Area Power Administration (WAPA) as superior sources of transmission line cost data. The BPA and WAPA data were adjusted to a common basis and combined together. The composite database covers voltage levels from 13.8 to 765 W, with cost estimates for a given voltage level varying depending on conductor size, tower material type, tower frame type, and number of circuits. Reported transmission line costs vary significantly, even for a given voltage level. This can usually be explained by variation in the design factors noted above and variation in environmental and land (right-of-way) costs, which are extremely site-specific. Cost estimates prepared from the composite database were compared to cost data collected by the Federal Energy Regulatory Commission (FERC) for investor-owned utilities from across the United States. The comparison was hampered because the only design specifications included with the FERC data were voltage level and line length. Working within this limitation, the FERC data were not found to differ significantly from the composite database. Therefore, the composite database was judged to be a reasonable proxy for estimating national average costs.

  2. Best Practices for Controlling Capital Costs in Net Zero Energy...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Best Practices for Controlling Capital Costs in Net Zero Energy Design and Construction - 2014 BTO Peer Review Best Practices for Controlling Capital Costs in Net Zero Energy ...

  3. QGESS: Capital Cost Scaling Methodology

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    the tonnes of CO2 utilized. The costs of the process are to include infrastructure, raw materials, processing, byproduct disposal, and utilities costs, as well as any other costs....

  4. LIFE Cost of Electricity, Capital and Operating Costs

    SciTech Connect (OSTI)

    Anklam, T

    2011-04-14

    Successful commercialization of fusion energy requires economic viability as well as technical and scientific feasibility. To assess economic viability, we have conducted a pre-conceptual level evaluation of LIFE economics. Unit costs are estimated from a combination of bottom-up costs estimates, working with representative vendors, and scaled results from previous studies of fission and fusion plants. An integrated process model of a LIFE power plant was developed to integrate and optimize unit costs and calculate top level metrics such as cost of electricity and power plant capital cost. The scope of this activity was the entire power plant site. Separately, a development program to deliver the required specialized equipment has been assembled. Results show that LIFE power plant cost of electricity and plant capital cost compare favorably to estimates for new-build LWR's, coal and gas - particularly if indicative costs of carbon capture and sequestration are accounted for.

  5. Discrete Event Modeling of Algae Cultivation and Harvesting at Commercial Scale: Capital Costs, Operating Costs, and System Bottlenecks

    SciTech Connect (OSTI)

    Lacey, Ph.D, P.E., Ronald E.

    2012-07-16

    Discrete Event Modeling of Algae Cultivation and Harvesting at Commercial Scale: Capital Costs, Operating Costs, and System Bottlenecks

  6. New developments in capital cost estimating

    SciTech Connect (OSTI)

    Stutz, R.A.; Zocher, M.A.

    1988-01-01

    The new developments in cost engineering revolve around the ability to capture information that in the past could not be automated. The purpose of automation is not to eliminate the expert cost engineer. The goal is to use available technology to have more information available to the professionals in the cost engineering field. In that sense, the demand for expertise increases in order to produce the highest quality estimate and project possible from all levels of cost engineers. We cannot overemphasize the importance of using a good source of expert information in building these types of programs. ''Garbage in, garbage out'' still applies in this form of programming. Expert systems technology will become commonplace in many vertical markets; it is important to undersand what can and cannot be accomplished in our field, and where this technology will lead us in the future.

  7. Accessing Low-Cost Capital Through Securitization (Poster)

    SciTech Connect (OSTI)

    Mendelsohn, M.

    2014-10-01

    Poster for Solar Power International conference presents information on NREL's effort to open capital markets through securitization via Solar Access to Public Capital (SAPC) working group's efforts.

  8. Mexico-Capital Markets Climate Initiative | Open Energy Information

    Open Energy Info (EERE)

    Low emission development planning, -LEDS Website http:www.decc.gov.ukencont Country Mexico Central America References CMCI1 World Economic Forum2 The Capital Markets...

  9. Microsoft PowerPoint - Crouther.HumanCapitalInitiatives.042909

    Office of Environmental Management (EM)

    Management Advisory Board (EMAB) By Desi Crouther, Acting Director Office of Human Capital Office of Environmental Management U.S. Department of Energy April 29, 2009 EM's...

  10. Manufacturing R&D Initiative Lowers Costs and Boosts Quality...

    Energy Savers [EERE]

    Manufacturing R&D Initiative Lowers Costs and Boosts Quality Manufacturing R&D Initiative Lowers Costs and Boosts Quality PDF icon mfg-initiativefactsheetjun2015.pdf More...

  11. Power plant capital investment cost estimates: current trends and sensitivity to economic parameters

    SciTech Connect (OSTI)

    Not Available

    1980-06-01

    This report describes power plant capital investment cost studies that were carried out as part of the activities of the Plans and Analysis Division, Office of Nuclear Energy Programs, US Department of Energy. The activities include investment cost studies prepared by an architect-engineer, including trends, effects of environmental and safety requirements, and construction schedules. A computer code used to prepare capital investment cost estimates under varying economic conditions is described, and application of this code is demonstrated by sensitivity studies.

  12. Table 1. Updated estimates of power plant capital and operating costs

    U.S. Energy Information Administration (EIA) Indexed Site

    Updated estimates of power plant capital and operating costs" ,"Plant Characteristics",,,"Plant Costs (2012$)" ,"Nominal Capacity (MW)","Heat Rate (Btu/kWh)",,"Overnight Capital Cost ($/kW)","Fixed O&M Cost ($/kW-yr)","Variable O&M Cost ($/MWh)" ,,,,,,,"NEMS Input" " Coal" "Single Unit Advanced PC",650,8800,,3246,37.8,4.47,"N" "Dual Unit Advanced

  13. Tanzania-Capital Markets Climate Initiative | Open Energy Information

    Open Energy Info (EERE)

    Markets Climate Initiative (CMCI) is a public-private initiative designed to support the scale up of private finance flows for low carbon technologies, solutions and...

  14. South Africa-Capital Markets Climate Initiative | Open Energy...

    Open Energy Info (EERE)

    Markets Climate Initiative (CMCI) is a public-private initiative designed to support the scale up of private finance flows for low carbon technologies, solutions and...

  15. Kenya-Capital Markets Climate Initiative | Open Energy Information

    Open Energy Info (EERE)

    Markets Climate Initiative (CMCI) is a public-private initiative designed to support the scale up of private finance flows for low carbon technologies, solutions and...

  16. India-Capital Markets Climate Initiative | Open Energy Information

    Open Energy Info (EERE)

    Markets Climate Initiative (CMCI) is a public-private initiative designed to support the scale up of private finance flows for low carbon technologies, solutions and...

  17. Philadelphia gas works medium-Btu coal gasification project: capital and operating cost estimate, financial/legal analysis, project implementation

    SciTech Connect (OSTI)

    Not Available

    1981-12-01

    This volume of the final report is a compilation of the estimated capital and operating costs for the project. Using the definitive design as a basis, capital and operating costs were developed by obtaining quotations for equipment delivered to the site. Tables 1.1 and 1.2 provide a summary of the capital and operating costs estimated for the PGW Coal Gasification Project. In the course of its Phase I Feasibility Study of a medium-Btu coal-gas facility, Philadelphia Gas Works (PGW) identified the financing mechanism as having great impact on gas cost. Consequently, PGW formed a Financial/Legal Task Force composed of legal, financial, and project analysis specialists to study various ownership/management options. In seeking an acceptable ownership, management, and financing arrangement, certain ownership forms were initially identified and classified. Several public ownership, private ownership, and third party ownership options for the coal-gas plant are presented. The ownership and financing forms classified as base alternatives involved tax-exempt and taxable financing arrangements and are discussed in Section 3. Project implementation would be initiated by effectively planning the methodology by which commercial operation will be realized. Areas covered in this report are sale of gas to customers, arrangements for feedstock supply and by-product disposal, a schedule of major events leading to commercialization, and a plan for managing the implementation.

  18. DOE Perspective on Budget, Accounting, and Cost-Saving Initiatives

    Broader source: Energy.gov [DOE]

    Joseph Hezir, Chief Financial Officer, DOE presented on the topic DOE Perspective on Budget, Accounting, and Cost-Saving Initiatives. The presentation focuses on FFRDCs, National Lab funding and cost accounting, ICR, and overhead costs.

  19. Updated Capital Cost Estimates for Utility Scale Electricity Generating Plants

    Reports and Publications (EIA)

    2013-01-01

    The current and future projected cost and performance characteristics of new electric generating capacity are a critical input into the development of energy projections and analyses.

  20. Controlling Capital Costs in High Performance Office Buildings: A Review of Best Practices for Overcoming Cost Barriers

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Controlling Capital Costs in High Performance Office Buildings: A Review of Best Practices for Overcoming Cost Barriers Preprint Shanti Pless and Paul Torcellini To be presented at the ACEEE Summer Study on Energy Efficiency in Buildings Pacific Grove, California August 12-17, 2012 Conference Paper NREL/CP-5500-55264 May 2012 NOTICE The submitted manuscript has been offered by an employee of the Alliance for Sustainable Energy, LLC (Alliance), a contractor of the US Government under Contract No.

  1. Developing a Cost Model and Methodology to Estimate Capital Costs for Thermal Energy Storage

    SciTech Connect (OSTI)

    Glatzmaier, G.

    2011-12-01

    This report provides an update on the previous cost model for thermal energy storage (TES) systems. The update allows NREL to estimate the costs of such systems that are compatible with the higher operating temperatures associated with advanced power cycles. The goal of the Department of Energy (DOE) Solar Energy Technology Program is to develop solar technologies that can make a significant contribution to the United States domestic energy supply. The recent DOE SunShot Initiative sets a very aggressive cost goal to reach a Levelized Cost of Energy (LCOE) of 6 cents/kWh by 2020 with no incentives or credits for all solar-to-electricity technologies.1 As this goal is reached, the share of utility power generation that is provided by renewable energy sources is expected to increase dramatically. Because Concentrating Solar Power (CSP) is currently the only renewable technology that is capable of integrating cost-effective energy storage, it is positioned to play a key role in providing renewable, dispatchable power to utilities as the share of power generation from renewable sources increases. Because of this role, future CSP plants will likely have as much as 15 hours of Thermal Energy Storage (TES) included in their design and operation. As such, the cost and performance of the TES system is critical to meeting the SunShot goal for solar technologies. The cost of electricity from a CSP plant depends strongly on its overall efficiency, which is a product of two components - the collection and conversion efficiencies. The collection efficiency determines the portion of incident solar energy that is captured as high-temperature thermal energy. The conversion efficiency determines the portion of thermal energy that is converted to electricity. The operating temperature at which the overall efficiency reaches its maximum depends on many factors, including material properties of the CSP plant components. Increasing the operating temperature of the power generation system leads to higher thermal-to-electric conversion efficiency. However, in a CSP system, higher operating temperature also leads to greater thermal losses. These two effects combine to give an optimal system-level operating temperature that may be less than the upper operating temperature limit of system components. The overall efficiency may be improved by developing materials, power cycles, and system-integration strategies that enable operation at elevated temperature while limiting thermal losses. This is particularly true for the TES system and its components. Meeting the SunShot cost target will require cost and performance improvements in all systems and components within a CSP plant. Solar collector field hardware will need to decrease significantly in cost with no loss in performance and possibly with performance improvements. As higher temperatures are considered for the power block, new working fluids, heat-transfer fluids (HTFs), and storage fluids will all need to be identified to meet these new operating conditions. Figure 1 shows thermodynamic conversion efficiency as a function of temperature for the ideal Carnot cycle and 75% Carnot, which is considered to be the practical efficiency attainable by current power cycles. Current conversion efficiencies for the parabolic trough steam cycle, power tower steam cycle, parabolic dish/Stirling, Ericsson, and air-Brayton/steam Rankine combined cycles are shown at their corresponding operating temperatures. Efficiencies for supercritical steam and carbon dioxide (CO{sub 2}) are also shown for their operating temperature ranges.

  2. Controlling Capital Costs in High Performance Office Buildings: A Review of Best Practices for Overcoming Cost Barriers

    SciTech Connect (OSTI)

    Pless, S.; Torcellini, P.

    2012-05-01

    This paper presents a set of 15 best practices for owners, designers, and construction teams of office buildings to reach high performance goals for energy efficiency, while maintaining a competitive budget. They are based on the recent experiences of the owner and design/build team for the Research Support Facility (RSF) on National Renewable Energy Facility's campus in Golden, CO, which show that achieving this outcome requires each key integrated team member to understand their opportunities to control capital costs.

  3. Manufacturing R&D Initiative Lowers Costs and Boosts Quality

    SciTech Connect (OSTI)

    2015-06-30

    Fact sheet that provides an overview of DOE's Manufacturing R&D Initiative, which supports projects aimed at developing better-performing, lower-cost solid-state lighting while encouraging engineering and manufacturing in the United States.

  4. Next Generation Safeguards Initiative Efforts at Los Alamos National Laboratory: Developing Our Human Capital FY2015

    SciTech Connect (OSTI)

    Stevens, Rebecca S.; Hawkins Erpenbeck, Heather

    2015-10-13

    This report documents the accomplishments of the Safeguards HCD Fiscal Year 2015 (FY15) Project Work Plan, highlighting LANL’s work as well as the accomplishments of our NGSI-sponsored students, graduate and postdoctoral fellows, and mid-career professionals during this past year. While fiscal year 2015 has been a year of transition in the Human Capital Development area for LANL, we are working to revitalize our efforts to promote and develop Human Capital in Safeguards and Non-proliferation and are looking forward to implementing new initiatives in the coming fiscal year and continuing to transition the knowledge of staff who have been on assignment at IAEA and Headquarters to improve our support to HCD.

  5. Access to Capital

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    IPR 2008 Capital Investment Review CIR 2012 Quarterly Business Review Focus 2028 2011 Strategic Capital Discussions Access to Capital Debt Optimization Asset Management Cost...

  6. 2011 Strategic Capital Discussions

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    IPR 2008 Capital Investment Review CIR 2012 Quarterly Business Review Focus 2028 2011 Strategic Capital Discussions Access to Capital Debt Optimization Asset Management Cost...

  7. A heat & mass integration approach to reduce capital and operating costs of a distillation configuration

    SciTech Connect (OSTI)

    Madenoor Ramapriya, Gautham; Jiang, Zheyu; Tawarmalani, Mohit; Agrawal, Rakesh

    2015-11-11

    We propose a general method to consolidate distillation columns of a distillation configuration using heat and mass integration. The proposed method encompasses all heat and mass integrations known till date, and includes many more. Each heat and mass integration eliminates a distillation column, a condenser, a reboiler and the heat duty associated with a reboiler. Thus, heat and mass integration can potentially offer significant capital and operating cost benefits. In this talk, we will study the various possible heat and mass integrations in detail, and demonstrate their benefits using case studies. This work will lay out a framework to synthesize an entire new class of useful configurations based on heat and mass integration of distillation columns.

  8. Major Capital Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    BPA on 242015 and does not contain Agency-approved Financial Information. 1 Includes capital projects authorized at the agency level since August 2007 2 Direct capital costs...

  9. Major Capital Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    BPA on 622014 and does not contain Agency-approved Financial Information. 1 Includes capital projects authorized at the agency level since August 2007 2 Direct capital costs...

  10. Major Capital Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    on 1142014 and does not contain Agency-approved Financial Information. 1 Includes capital projects authorized at the agency level since August 2007 2 Direct capital costs...

  11. Major Capital Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    on 2112014 and does not contain Agency-approved Financial Information. 1 Includes capital projects authorized at the agency level since August 2007 2 Direct capital costs...

  12. 2014 SunShot Initiative Soft Costs Subprogram Overview | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy Soft Costs Subprogram Overview 2014 SunShot Initiative Soft Costs Subprogram Overview These slides correspond to a presentation given by SunShot Initiative Soft Costs Acting Program Manager Dr. Elaine Ulrich at the 2014 SunShot Grand Challenge Summit and Peer Review in Anaheim, CA. This presentation is an overview of the SunShot Initiative's soft costs subprogram research portfolio. PDF icon elaineulrich_softcosts_overview_sunshot2014.pdf More Documents & Publications Download the

  13. Manufacturing R&D Initiative Lowers Costs and Boosts Quality | Department

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    of Energy Manufacturing R&D Initiative Lowers Costs and Boosts Quality Manufacturing R&D Initiative Lowers Costs and Boosts Quality PDF icon mfg-initiative_factsheet_jun2015.pdf More Documents & Publications Manufacturing R&D Initiative Lowers Costs and Boosts Quality Prospects for U.S.-Based Manufacturing in the SSL Industry Solid-State Lighting Commercial Product Development Resulting from DOE-Funded Projects

  14. EXPERT ELICITATION OF ACROSS-TECHNOLOGY CORRELATIONS FOR REACTOR CAPITAL COSTS

    SciTech Connect (OSTI)

    Brent Dixon; Various

    2014-06-01

    Calculations of the uncertainty in the Levelized Cost at Equilibrium (LCAE) of generating nuclear electricity typically assume that the costs of the system component, notably reactors, are uncorrelated. Partial cancellation of independent errors thus gives rise to unrealistically small cost uncertainties for fuel cycles that incorporate multiple reactor technologies. This summary describes an expert elicitation of correlations between overnight reactor construction costs. It also defines a method for combining the elicitations into a single, consistent correlation matrix suitable for use in Monte Carlo LCAE calculations. Both the elicitation and uncertainty propagation methods are demonstrated through a pilot study where cost correlations between eight reactor technologies were elicited from experts in the US DOE Fuel Cycle Research

  15. DOE Pursues SunShot Initiative to Achieve Cost Competitive Solar Energy by

    Energy Savers [EERE]

    2020 | Department of Energy Pursues SunShot Initiative to Achieve Cost Competitive Solar Energy by 2020 DOE Pursues SunShot Initiative to Achieve Cost Competitive Solar Energy by 2020 February 4, 2011 - 12:00am Addthis Washington, D.C. - U.S. Energy Secretary Steven Chu today announced additional details of the Department of Energy's "SunShot" initiative to reduce the total costs of photovoltaic solar energy systems by about 75 percent so that they are cost competitive at large

  16. FGD system capital and operating cost reductions based on improved thiosorbic scrubber system design and latest process innovations

    SciTech Connect (OSTI)

    Smith, K.; Tseng, S.; Babu, M.

    1994-12-31

    Dravo Lime Company has operated the Miami Fort wet scrubber FGD pilot test unit since late 1989 and has continued in-house R&D to improve the economics of the magnesium-enhanced scrubbing process. Areas investigated include the scrubber configuration, flue gas velocity, spray nozzle type, droplet size, mist eliminator design, additives to inhibit oxidation, improved solids dewatering, etc. Also tested was the forced oxidation Thioclear process. The data gathered from the pilot plant and in-house programs were used to evaluate the capital and operating costs for the improved systems. These evaluations were made with eye towards the choices electric utilities will need to make in the near future to meet the Phase II emission limits mandated by the 1990 Clean Air Act. Some of the process modifications investigated, for example, the dewatering improvements apply to potential beneficial retrofit of existing FGD systems today.

  17. Fiscal Year 2014 Annual Report on BNLs Next Generation Safeguards Initiative Human Capital Development Activities

    SciTech Connect (OSTI)

    Pepper S. E.

    2014-10-10

    Brookhaven National Laboratory’s (BNL’s) Nonproliferation and National Security Department contributes to the National Nuclear Security Administration Office of Nonproliferation and International Security Next Generation Safeguards Initiative (NGSI) through university engagement, safeguards internships, safeguards courses, professional development, recruitment, and other activities aimed at ensuring the next generation of international safeguards professionals is adequately prepared to support the U.S. safeguards mission. This report is a summary of BNL s work under the NGSI program in Fiscal Year 2014.

  18. 2014 SunShot Initiative Portfolio Book: Soft Costs | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Soft Costs 2014 SunShot Initiative Portfolio Book: Soft Costs The 2014 SunShot Initiative Portfolio Book outlines the progress towards the goals outlined in the SunShot Vision Study. Contents include overviews of each of SunShot's five subprogram areas, as well as a description of every active project in the SunShot's project portfolio as of May 2014. This section includes a letter from Program Manager Dr. Elaine Ulrich, providing an overview of SunShot's work in the soft costs/balance of

  19. Capital and operating cost estimates. Volume I. Preliminary design and assessment of a 12,500 BPD coal-to-methanol-to-gasoline plant. [Grace C-M-G Plant, Henderson County, Kentucky

    SciTech Connect (OSTI)

    Not Available

    1982-08-01

    This Deliverable No. 18b - Capital and Operating Cost Estimates includes a detailed presentation of the 12,500 BPD coal-to-methanol-to-gasoline plant from the standpoint of capital, preoperations, start-up and operations cost estimation. The base capital cost estimate in June 1982 dollars was prepared by the Ralph M. Parsons Company under the direction of Grace. The escalated capital cost estimate as well as separate estimates for preoperations, startup and operations activities were developed by Grace. The deliverable consists of four volumes. Volume I contains details of methodology used in developing the capital cost estimate, summary information on a base June 1982 capital cost, details of the escalated capital cost estimate and separate sections devoted to preoperations, start-up, and operations cost. The base estimate is supported by detailed information in Volumes II, III and IV. The degree of detail for some units was constrained due to proprietary data. Attempts have been made to exhibit the estimating methodology by including data on individual equipment pricing. Proprietary details are available for inspection upon execution of nondisclosure and/or secrecy agreements with the licensors to whom the data is proprietary. Details of factoring certain pieces of equipment and/or entire modules or units from the 50,000 BPD capital estimate are also included. In the case of the escalated capital estimate, Grace has chosen to include a sensitivity analysis which allows for ready assessment of impacts of escalation rates (inflation), contingency allowances and the construction interest financing rates on the escalated capital cost. Each of the estimates associated with bringing the plant to commercial production rates has as a basis the schedule and engineering documentation found in Deliverable No. 14b - Process Engineering and Mechanical Design Report, No. 28b - Staffing Plans, No. 31b - Construction Plan, and No. 33b - Startup and Operation Plan.

  20. TRANSMISSION AND DISTRIBUTION; POWER SUBSTATIONS; CAPITALIZED...

    Office of Scientific and Technical Information (OSTI)

    AND DISTRIBUTION; POWER SUBSTATIONS; CAPITALIZED COST; CALCULATION METHODS; PLANNING; COST ESTIMATION; MATHEMATICAL MODELS The displacement or deferral of substation...

  1. Cost of Capital

    Broader source: Energy.gov [DOE]

    This presentation summarizes the information given by PV Evolution Labs during the DOE SunShot Grand Challenge: Summit and Technology Forum, June 13-14, 2012.

  2. Capital Project Prioritization

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Capital-Project-Prioritization Sign In About | Careers | Contact | Investors | bpa.gov Search News & Us Expand News & Us Projects & Initiatives Expand Projects &...

  3. Development of surface mine cost estimating equations

    SciTech Connect (OSTI)

    Not Available

    1980-09-26

    Cost estimating equations were developed to determine capital and operating costs for five surface coal mine models in Central Appalachia, Northern Appalachia, Mid-West, Far-West, and Campbell County, Wyoming. Engineering equations were used to estimate equipment costs for the stripping function and for the coal loading and hauling function for the base case mine and for several mines with different annual production levels and/or different overburden removal requirements. Deferred costs were then determined through application of the base case depreciation schedules, and direct labor costs were easily established once the equipment quantities (and, hence, manpower requirements) were determined. The data points were then fit with appropriate functional forms, and these were then multiplied by appropriate adjustment factors so that the resulting equations yielded the model mine costs for initial and deferred capital and annual operating cost. (The validity of this scaling process is based on the assumption that total initial and deferred capital costs are proportional to the initial and deferred costs for the primary equipment types that were considered and that annual operating cost is proportional to the direct labor costs that were determined based on primary equipment quantities.) Initial capital costs ranged from $3,910,470 in Central Appalachia to $49,296,785; deferred capital costs ranged from $3,220,000 in Central Appalachia to $30,735,000 in Campbell County, Wyoming; and annual operating costs ranged from $2,924,148 in Central Appalachia to $32,708,591 in Campbell County, Wyoming. (DMC)

  4. EM Capital Asset Project List

    Broader source: Energy.gov [DOE]

    Read the EM Capital Asset Project List, which includes the project's name, site, current critical decision and current total project cost.

  5. Facilities Initiatives | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Facilities Initiatives Facilities Initiatives The Headquarters Office of Administration, Office of Logistics and Facility Operations, has several energy saving initiatives in place or in progress at their Headquarters' facilities in the Forrestal Building in Washington, DC, and Germantown Maryland. Many of these initiatives are part of their Energy Savings Performance Contract (ESPC). ESPCs allow Federal agencies to accomplish energy savings projects without up-front capital costs and without

  6. Best Practices for Controlling Capital Costs in Net Zero Energy Design and Construction- 2014 BTO Peer Review

    Broader source: Energy.gov [DOE]

    Presenter: Shanti Pless, National Renewable Energy Laboratory For net zero energy (NZE) building performance to become the norm in new commercial construction, it is necessary to demonstrate that NZE can be achieved cost effectively.

  7. An analysis of cost effective incentives for initial commercial deployment of advanced clean coal technologies

    SciTech Connect (OSTI)

    Spencer, D.F.

    1997-12-31

    This analysis evaluates the incentives necessary to introduce commercial scale Advanced Clean Coal Technologies, specifically Integrated Coal Gasification Combined Cycle (ICGCC) and Pressurized Fluidized Bed Combustion (PFBC) powerplants. The incentives required to support the initial introduction of these systems are based on competitive busbar electricity costs with natural gas fired combined cycle powerplants, in baseload service. A federal government price guarantee program for up to 10 Advanced Clean Coal Technology powerplants, 5 each ICGCC and PFBC systems is recommended in order to establish the commercial viability of these systems by 2010. By utilizing a decreasing incentives approach as the technologies mature (plants 1--5 of each type), and considering the additional federal government benefits of these plants versus natural gas fired combined cycle powerplants, federal government net financial exposure is minimized. Annual net incentive outlays of approximately 150 million annually over a 20 year period could be necessary. Based on increased demand for Advanced Clean Coal Technologies beyond 2010, the federal government would be revenue neutral within 10 years of the incentives program completion.

  8. Operating Costs

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    This chapter is focused on capital costs for conventional construction and environmental restoration and waste management projects and examines operating cost estimates to verify that all elements of the project have been considered and properly estimated.

  9. Access to Capital | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Soft Costs Access to Capital Access to Capital Photo of a room full of people seated in rows with a few standing in the background. Two hands in the crowd are holding up sheets ...

  10. Report: EM Human Capital Initiatives

    Office of Environmental Management (EM)

    has been a central tenet of the Assistant Secretary's tenure, reflecting the critical nature of this resource to the achievement of EM's mission. Beginning in Fiscal Year (FY)...

  11. QGESS: Capital Cost Scaling Methodology

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    QUALITY GUIDELINES FOR ENERGY SYSTEM STUDIES Performing a Techno-economic Analysis for Power Generation Plants DOENETL-2010???? DOENETL-20151726 Techno-economic Analysis...

  12. Initial

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Initial operation of a pulse-burst laser system for high-repetition-rate Thomson scattering a... W. S. Harris, 1 D. J. Den Hartog, 1,2 and N. C. Hurst 1 1 Department of Physics, University of Wisconsin-Madison, Madison, Wisconsin 53706, USA 2 Center for Magnetic Self-Organization in Laboratory and Astrophysical Plasmas, University of Wisconsin-Madison, Madison, Wisconsin 53706, USA ͑Presented 17 May 2010; received 12 May 2010; accepted 31 May 2010; published online 1 October 2010͒ A

  13. Human Capital Management | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Management Human Capital Management The strategic management of human capital requires comprehensive planning and analysis in order to develop, implement, and evaluate programs that support every facet of employee work life. DOE human capital initiatives are designed to support continuous improvement and accountability in accordance with the DOE Human Capital Management Accountability Program (HCMAP), which is an internal DOE audit process of servicing human resources offices and addresses those

  14. Microsoft Word - Levelized Cost of Energy Analysis

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    It takes into account all costs of generating electricity, including capital costs, ... - see OK wind capacity factor above o Capital cost - 1.75 mmMW (includes regional ...

  15. Foundation Capital

    Broader source: Energy.gov (indexed) [DOE]

    Foundation Capital EiR1 at ORNL Presentation to EERE May 2010 Narrow EiR IP filter employed  Find a technology that  Promises a 5-10x improvement over status quo - Not incremental  Is covered by unique, defensible, broad IP portfolio - No license patchwork  Addresses a $B market opportunity  Has platform characteristics - Once core product developed, should be leverageable into several applications with small additional R&D resources  Fit for private funding within 12

  16. CAPITAL REGION

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    t 09/20/07 15:28 FAX 301 903 4656 CAPITAL REGION 0 j002 SDOE F 1325.8 (8-89) EFG (0790) Energy United States Government Department of Energy Memorandum DATE. September 18, 2007 Audit Report No.: OAS-L-07-23 REPLY TO: IG-34 (A07TG036) SUBJECT: Evaluation of "The Federal Energy Regulatory Commission's Cyber Security Program-2007" TO: Chairman, Federal Energy Regulatory Commission The purpose of this report is to inform you of the results o Four evaluation of the Federal Energy Regulatory

  17. Sustainable Investments Capital SI Capital | Open Energy Information

    Open Energy Info (EERE)

    Investments Capital SI Capital Jump to: navigation, search Name: Sustainable Investments Capital (SI Capital) Place: Barcelona, Spain Zip: 8021 Sector: Renewable Energy, Services...

  18. Foundation Capital

    Broader source: Energy.gov (indexed) [DOE]

    tech Commercial prototype * For at least 1 sizeable market segment: * Sufficient scale * Ok feature set * Acceptable cost "in sight" Gen 1 product service * 1 st customer(s)...

  19. Venture Capital Finance

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Venture Capital Finance DOE Biomass Conference July 2014 Priced Out of Oil ... Into What? Energy Source Commodity Price Sun: $0 / GJ Oil (6.2 GJ/bbl) $10/bbl = $1.6 / GJ (late 1990s) Coal: $3 - 6 / GJ Natural Gas (N America) $3 - 4 / GJ Biomass (15 GJ/dt) $60-100/dt = $4 - 6 / GJ Natural Gas (ex N America) $10 - 15 / GJ Oil (6.2 GJ/bbl) $100/bbl = $16 / GJ Corn $4-7/bu= $10 - 20 / GJ 2 * Higher oil prices create a disruptive opportunity for lower cost feedstocks * North American shale gas is a

  20. Capital Asset Project List.xls

    Broader source: Energy.gov (indexed) [DOE]

    as defined by DOE Order 413.3B, Program and Project Management for the Acquisition of Capital Assets. CD0 Approve Mission Need CD1 Approve Alternative Selection and Cost Range CD2...

  1. Solar Access to Public Capital (SAPC) Mock Securitization Project

    SciTech Connect (OSTI)

    Mendelsohn, Michael; Lowder, Travis; Rottman, Mary; Borod, Ronald; Gabig, Nathan; Henne, Stephen; Caplin, Conrad; Notte, Quentin

    2015-12-21

    In late 2012, the National Renewable Energy Laboratory (NREL) initiated the Solar Access to Public Capital (SAPC) working group. Backed by a three-year funding facility from the U.S. Department of Energy (DOE), NREL set out to organize the solar, legal, banking, capital markets, engineering, and other relevant stakeholder communities in order to open lower-cost debt investment for solar asset deployment. SAPC engaged its members to standardize contracts, develop best practices, and comprehend how the rating agencies perceive solar project portfolios as an investment asset class. Rating agencies opine on the future creditworthiness of debt obligations. Issuers often seek investment-grade ratings from the rating agencies in order to satisfy the desires of their investors. Therefore, for the solar industry to access larger pools of capital at a favorable cost, it is critical to increase market participants' understanding of solar risk parameters. The process provided valuable information to address rating agency perceptions of risk that, without such information, could require costly credit enhancement or higher yields to attract institutional investors. Two different securities were developed--one for a hypothetical residential solar portfolio and one for a hypothetical commercial solar portfolio. Five rating agencies (Standard and Poor's, Moody's, KBRA, Fitch, and DBRS) participated and provided extensive feedback, some through conversations that extended several months. The findings represented in this report are a composite summary of that feedback and do not indicate any specific feedback from any single rating agency.

  2. Structural health and prognostics management for offshore wind turbines : case studies of rotor fault and blade damage with initial O&M cost modeling.

    SciTech Connect (OSTI)

    Myrent, Noah J.; Kusnick, Joshua F.; Barrett, Natalie C.; Adams, Douglas E.; Griffith, Daniel Todd

    2013-04-01

    Operations and maintenance costs for offshore wind plants are significantly higher than the current costs for land-based (onshore) wind plants. One way to reduce these costs would be to implement a structural health and prognostic management (SHPM) system as part of a condition based maintenance paradigm with smart load management and utilize a state-based cost model to assess the economics associated with use of the SHPM system. To facilitate the development of such a system a multi-scale modeling approach developed in prior work is used to identify how the underlying physics of the system are affected by the presence of damage and faults, and how these changes manifest themselves in the operational response of a full turbine. This methodology was used to investigate two case studies: (1) the effects of rotor imbalance due to pitch error (aerodynamic imbalance) and mass imbalance and (2) disbond of the shear web; both on a 5-MW offshore wind turbine in the present report. Based on simulations of damage in the turbine model, the operational measurements that demonstrated the highest sensitivity to the damage/faults were the blade tip accelerations and local pitching moments for both imbalance and shear web disbond. The initial cost model provided a great deal of insight into the estimated savings in operations and maintenance costs due to the implementation of an effective SHPM system. The integration of the health monitoring information and O&M cost versus damage/fault severity information provides the initial steps to identify processes to reduce operations and maintenance costs for an offshore wind farm while increasing turbine availability, revenue, and overall profit.

  3. Greenworld Capital | Open Energy Information

    Open Energy Info (EERE)

    Greenworld Capital Jump to: navigation, search Name: Greenworld Capital Place: Pennsylvania Zip: 10000 Sector: Services Product: GreenWorld Capital provides investment banking...

  4. Greencore Capital | Open Energy Information

    Open Energy Info (EERE)

    Greencore Capital Jump to: navigation, search Name: Greencore Capital Place: San Diego, California Zip: 92121 Sector: Services Product: String representation "GreenCore Capit ... s...

  5. Yellowstone Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Logo: Yellowstone Capital Name: Yellowstone Capital Address: 5555 San Felipe, Suite 1650 Place: Houston, Texas Zip: 77056 Region: Texas Area...

  6. Nite Capital | Open Energy Information

    Open Energy Info (EERE)

    Nite Capital Jump to: navigation, search Name: Nite Capital Place: Libertyville, Illinois Zip: 60048 Product: Nite Capital provides private financing for small-cap and micro-cap...

  7. Greener Capital | Open Energy Information

    Open Energy Info (EERE)

    Greener Capital Jump to: navigation, search Name: Greener Capital Place: San Francisco, California Product: San Francisco-based clean technology VC. References: Greener Capital1...

  8. GGV Capital | Open Energy Information

    Open Energy Info (EERE)

    GGV Capital Jump to: navigation, search Name: GGV Capital Place: Menlo Park, California Zip: 94025 Product: String representation "GGV Capital" ... U.S. and China." is too...

  9. CMEA Capital | Open Energy Information

    Open Energy Info (EERE)

    CMEA Capital Jump to: navigation, search Logo: CMEA Capital Name: CMEA Capital Address: 1 Embarcadero Center Place: San Francisco, California Zip: 94111 Region: Bay Area Number of...

  10. Clarey Capital | Open Energy Information

    Open Energy Info (EERE)

    Clarey Capital Jump to: navigation, search Name: Clarey Capital Place: Irvine, California Zip: 92617 Sector: Renewable Energy Product: String representation "Clarey Capital ... of...

  11. BEV Capital | Open Energy Information

    Open Energy Info (EERE)

    BEV Capital Jump to: navigation, search Logo: BEV Capital Name: BEV Capital Address: 263 Tresser Blvd., 9th Floor Place: Stamford, Connecticut Zip: 06901 Region: Northeast - NY NJ...

  12. Infield Capital | Open Energy Information

    Open Energy Info (EERE)

    Infield Capital Jump to: navigation, search Name: Infield Capital Place: Boulder, Colorado Product: Infield Capital was founded in 2008, and is focused on investment in early-stage...

  13. Greenview Capital | Open Energy Information

    Open Energy Info (EERE)

    Greenview Capital Jump to: navigation, search Name: Greenview Capital Place: Libertyville, Illinois Zip: 60048 Product: Greenview Capital is a U.S. based consulting firm and...

  14. Earthrise Capital | Open Energy Information

    Open Energy Info (EERE)

    Earthrise Capital Jump to: navigation, search Logo: Earthrise Capital Name: Earthrise Capital Address: 45 Rockefeller Plaza, 20th Floor Place: New York, New York Zip: 10111 Region:...

  15. Atrium Capital | Open Energy Information

    Open Energy Info (EERE)

    Atrium Capital Jump to: navigation, search Logo: Atrium Capital Name: Atrium Capital Address: 3000 Sand Hill Road, Building 2, Suite 240 Place: Menlo Park, California Zip: 94025...

  16. Commons Capital | Open Energy Information

    Open Energy Info (EERE)

    Commons Capital Jump to: navigation, search Logo: Commons Capital Name: Commons Capital Address: 320 Washington Street, 4th floor Place: Brookline, Massachusetts Zip: 02445 Region:...

  17. Life-cycle cost comparisons of advanced storage batteries and fuel cells for utility, stand-alone, and electric vehicle applications

    SciTech Connect (OSTI)

    Humphreys, K.K.; Brown, D.R.

    1990-01-01

    This report presents a comparison of battery and fuel cell economics for ten different technologies. To develop an equitable economic comparison, the technologies were evaluated on a life-cycle cost (LCC) basis. The LCC comparison involved normalizing source estimates to a standard set of assumptions and preparing a lifetime cost scenario for each technology, including the initial capital cost, replacement costs, operating and maintenance (O M) costs, auxiliary energy costs, costs due to system inefficiencies, the cost of energy stored, and salvage costs or credits. By considering all the costs associated with each technology over its respective lifetime, the technology that is most economical to operate over any given period of time can be determined. An analysis of this type indicates whether paying a high initial capital cost for a technology with low O M costs is more or less economical on a lifetime basis than purchasing a technology with a low initial capital cost and high O M costs. It is important to realize that while minimizing cost is important, the customer will not always purchase the least expensive technology. The customer may identify benefits associated with a more expensive option that make it the more attractive over all (e.g., reduced construction lead times, modularity, environmental benefits, spinning reserve, etc.). The LCC estimates presented in this report represent three end-use applications: utility load-leveling, stand-alone power systems, and electric vehicles.

  18. Solar Access to Public Capital | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Solar Access to Public Capital Solar Access to Public Capital The Solar Access to Public Capital (SAPC) working group has developed standard residential lease and commercial power purchase agreement (PPA) contracts available for use by solar developers, customers, and third-party finance providers. These documents are designed to improve consumer transparency, reduce transaction costs in the solar asset contracting process, and facilitate the pooling of associated cash flows so that they may be

  19. Capital Reporting Company Quadrennial ...

    Broader source: Energy.gov (indexed) [DOE]

    2014 1 QUADRENNIAL ENERGY REVIEW PUBLIC MEETING 6 MONDAY, JULY 21, ... Capital Reporting Company Quadrennial Energy Review Public Meeting 07-21-2014 (866) ...

  20. Capital Reporting Company Quadrennial ...

    Broader source: Energy.gov (indexed) [DOE]

    2014 1 QUADRENNIAL ENERGY REVIEW STAKEHOLDER MEETING 3 PETROLEUM ... Capital Reporting Company Quadrennial Energy Review Stakeholder Meeting 3 05-27-2014 ...

  1. Capital Reporting Company Quadrennial ...

    Broader source: Energy.gov (indexed) [DOE]

    2014 1 QUADRENNIAL ENERGY REVIEW PUBLIC MEETING 10: Infrastructure ... Capital Reporting Company Quadrennial Energy Review 08-11-2014 (866) 448 - DEPO ...

  2. CAPITAL PROJECT PROPOSAL

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Non-Discretionary, please provide explanation: 07 Approval for: Ongoing Program 08 Investment Type: Capital Replacement 09 Emergency? YES NO 09A If "YES", please provide...

  3. Capital Reporting Company

    Broader source: Energy.gov (indexed) [DOE]

    11 08-21-2014 (866) 448 - DEPO www.CapitalReportingCompany.com © 2014 1 QUADRENNIAL ENERGY REVIEW PUBLIC MEETING #11: Infrastructure Siting Thursday, August 21, 2014 Little America Conference Center Cheyenne, Wyoming Reported by: Roger Meyers, Capital Reporting Company Capital Reporting Company Quadrennial Energy Review Public Meeting # 11 08-21-2014 (866) 448 - DEPO www.CapitalReportingCompany.com © 2014 2 1 A P P E A R A N C E S 2 Dr. Karen Wayland, Deputy Director for State, Local and

  4. Capital Reporting Company

    National Nuclear Security Administration (NNSA)

    Commerce Matthew Shruhan, U.S.-India Business Council 21 Brooke Smith, Nuclear Regulatory Commission Gretchen Smith, DOENNSA 22 Carlton Stoiber, Talisman International Capital ...

  5. A Review of Cost Estimation in New Technologies - Implications...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    This report reviews literature on cost estimation in several areas involving major capital ... projects, and cost estimating techniques and problems for chemical process plants. ...

  6. Energy Department Report Calculates Emissions and Costs of Power...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    does not consider other factors such as capital costs of construction for wind, solar, fossil-fueled power plants, or transmission. These costs are significant, but outside the...

  7. BG Capital | Open Energy Information

    Open Energy Info (EERE)

    BG Capital Jump to: navigation, search Name: BG-Capital Place: Spain Zip: 8860 Product: BG-capital designs, installs and invests in PV medium scale (100-500kW) systems,...

  8. Hazel Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Hazel Capital Place: London, England, United Kingdom Zip: WC2A 1AL Sector: Efficiency, Renewable Energy Product: Hazel Capital is an asset...

  9. 2015-09-25 Capital Asset Project List.xls

    Broader source: Energy.gov (indexed) [DOE]

    as defined by DOE Order 413.3B, Program and Project Management for the Acquisition of Capital Assets. CD-0 Approve Mission Need CD-1 Approve Alternative Selection and Cost Range...

  10. Copy of Capitalized Property RO23_120213_1.xlsx

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Capitalized Property 1 RO BARCODE DESCRIPTION MANUF. MODEL SN COST BLDG ROOM INVTDATE 23 C5508 PRECISION ION POLISH GATAN INC 691 UNIT 427 01070301 50,626.00 28 113 24-Sep-13 23...

  11. DOE Strategic Human Capital Plan

    Broader source: Energy.gov [DOE]

    The Strategic Human Capital Plan sets forth the framework for managing the Department of Energy’s (DOE) human capital system through 2015.

  12. Carbon Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Carbon Capital Place: United Kingdom Sector: Carbon Product: Manages a carbon fund specialised in forestry projects References: Carbon...

  13. Gaian Capital | Open Energy Information

    Open Energy Info (EERE)

    Gaian Capital Jump to: navigation, search Name: Gaian Capital Place: Greater London, United Kingdom Product: London-based privately held firm aimed at assisting climate change...

  14. Arborview Capital | Open Energy Information

    Open Energy Info (EERE)

    Arborview Capital Jump to: navigation, search Name: Arborview Capital Place: Chevy Chase, Maryland Zip: 20815 Product: Maryland-based private equity firm that provides growth...

  15. Greenrock Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Greenrock Capital Place: San Francisco, California Zip: 94111 Sector: Renewable Energy Product: San Francisco-based, investment firm....

  16. Dragonfly Capital | Open Energy Information

    Open Energy Info (EERE)

    Dragonfly Capital Jump to: navigation, search Name: Dragonfly Capital Place: Charlotte, North Carolina Zip: 28203 Sector: Renewable Energy, Services Product: Charlotte-based...

  17. Principal Associate Director - Capital Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Principal Associate Director - Capital Projects As Principal Associate Director for Capital Projects (interim), Larry Simmons is responsible for institutional large-project...

  18. Renewable Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Renewable Capital Place: Las Vegas, Nevada Zip: 89109 Sector: Solar Product: Investment vehicle of Ed Stevenson, founder of Solar...

  19. Cascadia Capital | Open Energy Information

    Open Energy Info (EERE)

    Cascadia Capital Jump to: navigation, search Name: Cascadia Capital Address: 701 Fifth Avenue Place: Seattle, Washington Zip: 98104 Region: Pacific Northwest Area Product:...

  20. Capital Connections | Open Energy Information

    Open Energy Info (EERE)

    Connections Jump to: navigation, search Name: Capital Connections Place: United Kingdom Product: Supplies fuel cell systems. References: Capital Connections1 This article is a...

  1. Peony Capital | Open Energy Information

    Open Energy Info (EERE)

    Peony Capital Jump to: navigation, search Name: Peony Capital Place: Dongcheng District Beijing, Beijing Municipality, China Zip: 100027 Product: Manages a fund dedicated to...

  2. Capital Point | Open Energy Information

    Open Energy Info (EERE)

    Point Jump to: navigation, search Name: Capital Point Place: Israel Sector: Services Product: General Financial & Legal Services ( Joint Venture Consortium ) References: Capital...

  3. Cost Contributors to Geothermal Power Production

    SciTech Connect (OSTI)

    Nathwani, Jay; Mines, Greg

    2011-07-01

    The US Department of Energy Geothermal Technologies Office (DOE-GTO) has developed the tool Geothermal Electricity Technologies Evaluation Model (GETEM) to assess the levelized cost of electricity (LCOE) of power produced from geothermal resources. Recently modifications to GETEM allow the DOE-GTO to better assess how different factors impact the generation costs, including initial project risk, time required to complete a development, and development size. The model characterizes the costs associated with project risk by including the costs to evaluate and drill those sites that are considered but not developed for commercial power generation, as well as to assign higher costs to finance those activities having more risk. This paper discusses how the important parameters impact the magnitude project costs for different project scenarios. The cost distributions presented include capital cost recovery for the exploration, confirmation, well field completion and power plant construction, as well as the operation and maintenance (O&M) costs. The paper will present these cost distributions for both EGS and hydrothermal resources.

  4. Capital Reporting Company Quadrennial ...

    Broader source: Energy.gov (indexed) [DOE]

    Meeting No. 4 06-19-2014 (866) 448 - DEPO www.CapitalReportingCompany.com 2014 1 UNITED STATES DEPARTMENT OF ENERGY OFFICE OF ENERGY POLICY AND SYSTEMS ANALYSIS QUADRENNIAL ...

  5. Capital Reporting Company Quadrenntial ...

    Broader source: Energy.gov (indexed) [DOE]

    Energy Review 04-21-2014 (866) 448 - DEPO www.CapitalReportingCompany.com 2014 1 NEW ENGLAND REGIONAL INFRASTRUCTURE CONSTRAINTS A Public Meeting on the Quadrennial Energy ...

  6. Capital Project Authorization

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    This policy applies to capital projects in these asset categories: 1. Transmission investment in assets owned or leased by BPA, whether funded by bonds issued to the U.S....

  7. Non-Hardware ("Soft") Cost-Reduction Roadmap for Residential and Small Commercial Solar Photovoltaics, 2013-2020

    SciTech Connect (OSTI)

    Ardani, K.; Seif, D.; Margolis, R.; Morris, J.; Davidson, C.; Truitt, S.; Torbert, R.

    2013-08-01

    The objective of this analysis is to roadmap the cost reductions and innovations necessary to achieve the U.S. Department of Energy (DOE) SunShot Initiative's total soft-cost targets by 2020. The roadmap focuses on advances in four soft-cost areas: (1) customer acquisition; (2) permitting, inspection, and interconnection (PII); (3) installation labor; and (4) financing. Financing cost reductions are in terms of the weighted average cost of capital (WACC) for financing PV system installations, with real-percent targets of 3.0% (residential) and 3.4% (commercial).

  8. Capital intensity of photovoltaics manufacturing: Barrier to scale and opportunity for innovation

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Powell, Douglas M.; Fu, Ran; Horowitz, Kelsey; Basore, Paul A.; Woodhouse, Michael; Buonassisi, Tonio

    2015-09-07

    In this study, using a bottom-up cost model, we assess the impact of initial factory capital expenditure (capex) on photovoltaic (PV) module minimum sustainable price (MSP) and industry-wide trends. We find capex to have two important impacts on PV manufacturing. First, capex strongly influences the per-unit MSP of a c-Si module: we calculate that the capex-related elements sum to 22% of MSP for an integrated wafer, cell, and module manufacturer. This fraction provides a significant opportunity to reduce MSP toward the U.S. DOE SunShot module price target through capex innovation.

  9. Energy Efficient Schools Initiative- Loans

    Broader source: Energy.gov [DOE]

    The Energy Efficient Schools Initiative (EESI) was created in May 2008 to provide grants and loans to Tennessee school systems for capital outlay projects that meet energy efficient design and te...

  10. Green Capital Management | Open Energy Information

    Open Energy Info (EERE)

    Capital Management Jump to: navigation, search Name: Green Capital Management Place: London, United Kingdom Zip: SW10 0BB Sector: Services Product: The Green Capital Management...

  11. Human Capital Management Accountability Program (HCMAP) | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Human Capital Management Accountability Program (HCMAP) Human Capital Management Accountability Program (HCMAP) Human Capital Management Accountability Program (HCMAP) is an online ...

  12. Walnut Capital Acquisitions | Open Energy Information

    Open Energy Info (EERE)

    Walnut Capital Acquisitions Jump to: navigation, search Name: Walnut Capital Acquisitions Place: Pittsburgh, Pennsylvania Zip: 15232 Product: Walnut Capital Acquisitions is the...

  13. American Wind Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: American Wind Capital Place: Essex, Connecticut Zip: 64260 Sector: Wind energy Product: Connecticut-based American Wind Capital buys wind...

  14. Sustainable Technology Capital, LP | Open Energy Information

    Open Energy Info (EERE)

    Capital, LP Jump to: navigation, search Logo: Sustainable Technology Capital, LP Name: Sustainable Technology Capital, LP Address: 625 Liberty Ave., Suite 3200 Place: Pittsburgh,...

  15. Long Branch Capital | Open Energy Information

    Open Energy Info (EERE)

    Branch Capital Jump to: navigation, search Name: Long Branch Capital Place: Austin, Texas Zip: 78744 Sector: Efficiency, Renewable Energy Product: Long Branch Capital makes...

  16. Tonga Capital Corporation | Open Energy Information

    Open Energy Info (EERE)

    Tonga Capital Corporation Jump to: navigation, search Name: Tonga Capital Corporation Place: Arvada, Colorado Sector: Biofuels Product: Capital pool company, which ran out of...

  17. Hereford Capital Advisors | Open Energy Information

    Open Energy Info (EERE)

    Hereford Capital Advisors Jump to: navigation, search Name: Hereford Capital Advisors Place: Denver, Colorado Product: US-based firm offering PV project management and capital...

  18. Prospect Capital Corporation | Open Energy Information

    Open Energy Info (EERE)

    Prospect Capital Corporation Jump to: navigation, search Logo: Prospect Capital Corporation Name: Prospect Capital Corporation Address: 10 East 40th Street, 44th Floor Place: New...

  19. Energy Capital Solutions | Open Energy Information

    Open Energy Info (EERE)

    Capital Solutions Jump to: navigation, search Logo: Energy Capital Solutions Name: Energy Capital Solutions Address: 2651 North Harwood Street, Suite 410 Place: Dallas, Texas Zip:...

  20. Beetle Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    Beetle Capital Partners Jump to: navigation, search Logo: Beetle Capital Partners Name: Beetle Capital Partners Address: Medici Court, 67-69 New Bond Street Place: London, United...

  1. KRK Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    KRK Capital Partners Jump to: navigation, search Name: KRK Capital Partners Place: Washington DC, Washington, DC Zip: 20002 Product: String representation "KRK Capital Par ......

  2. Chrysalix Energy Venture Capital | Open Energy Information

    Open Energy Info (EERE)

    Chrysalix Energy Venture Capital Jump to: navigation, search Logo: Chrysalix Energy Venture Capital Name: Chrysalix Energy Venture Capital Address: 1367 West Broadway, Suite 400...

  3. Temple Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    Temple Capital Partners Jump to: navigation, search Name: Temple Capital Partners Place: United Kingdom Product: Fund manager of Clean Energy Brazil. References: Temple Capital...

  4. New Energy Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Logo: New Energy Capital Name: New Energy Capital Address: 53 South Main Street, Third Floor Place: Hanover, New Hampshire Zip: 03755 Product:...

  5. Applied Intellectual Capital AIC | Open Energy Information

    Open Energy Info (EERE)

    Intellectual Capital AIC Jump to: navigation, search Name: Applied Intellectual Capital (AIC) Place: California Zip: 94501-1010 Product: Applied Intellectual Capital (AIC) was...

  6. Booner Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Booner Capital LLC Jump to: navigation, search Name: Booner Capital LLC Place: Florida Sector: Wind energy Product: Booner Capital LLC is PE investor in wind power companies....

  7. Chestnut Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Capital LLC Jump to: navigation, search Name: Chestnut Capital LLC Place: West Newton, Massachusetts Zip: 2465 Sector: Wind energy Product: Chestnut Capital is a wind energy...

  8. Cora Capital Advisors | Open Energy Information

    Open Energy Info (EERE)

    Cora Capital Advisors Jump to: navigation, search Logo: Cora Capital Advisors Name: Cora Capital Advisors Address: 445 Park Avenue, 9th Floor Place: New York Zip: 10022 Region:...

  9. The Capital Intensity of Photovoltaics Manufacturing

    SciTech Connect (OSTI)

    Basore, Paul

    2015-10-19

    Factory capital expenditure (capex) for photovoltaic (PV) module manufacturing strongly influences the per-unit cost of a c-Si module. This provides a significant opportunity to address the U.S. DOE SunShot module price target through capex innovation. Innovation options to reduce the capex of PV manufacturing include incremental and disruptive process innovation with c-Si, platform innovations, and financial approaches. and financial approaches.

  10. Greentech Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Place: Sao Paulo, Sao Paulo, Brazil Zip: 04536-001 Product: Brazilian investment group. References: Greentech Capital1 This article is a stub. You can help OpenEI...

  11. Osmosis Capital | Open Energy Information

    Open Energy Info (EERE)

    Osmosis Capital Jump to: navigation, search Name: Osmosis Capital Place: London, United Kingdom Zip: EC4M 9DN Sector: Carbon Product: An investment firm seeking low carbon economy...

  12. Ardour Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Ardour Capital Investments LLC Address: 350 5th ave Place: New York, New York Zip: 10118 Region: Northeast - NY NJ CT PA Area Number of...

  13. Survey Results and Analysis of the Cost and Efficiency of Various Operating Hydrogen Fueling Stations

    SciTech Connect (OSTI)

    Cornish, John

    2011-03-05

    Existing Hydrogen Fueling Stations were surveyed to determine capital and operational costs. Recommendations for cost reduction in future stations and for research were developed.

  14. US nuclear power plant operating cost and experience summaries

    SciTech Connect (OSTI)

    Kohn, W.E.; Reid, R.L.; White, V.S.

    1998-02-01

    NUREG/CR-6577, U.S. Nuclear Power Plant Operating Cost and Experience Summaries, has been prepared to provide historical operating cost and experience information on U.S. commercial nuclear power plants. Cost incurred after initial construction are characterized as annual production costs, representing fuel and plant operating and maintenance expenses, and capital expenditures related to facility additions/modifications which are included in the plant capital asset base. As discussed in the report, annual data for these two cost categories were obtained from publicly available reports and must be accepted as having different degrees of accuracy and completeness. Treatment of inconclusive and incomplete data is discussed. As an aid to understanding the fluctuations in the cost histories, operating summaries for each nuclear unit are provided. The intent of these summaries is to identify important operating events; refueling, major maintenance, and other significant outages; operating milestones; and significant licensing or enforcement actions. Information used in the summaries is condensed from annual operating reports submitted by the licensees, plant histories contained in Nuclear Power Experience, trade press articles, and the Nuclear Regulatory Commission (NRC) web site (www.nrc.gov).

  15. Replacement Cost of Domestic Crude

    Energy Science and Technology Software Center (OSTI)

    1994-12-01

    The DEEPWATER model forecasts the replacement cost of domestic crude oil for 13 offshore regions in the lower 48 states. The replacement cost of domestic crude oil is the constant or levelized selling price that will recover the full expense of exploration, development, and productions with a reasonable return on capital.

  16. Swiftsure Capital | Open Energy Information

    Open Energy Info (EERE)

    Place: San Francisco, California Product: Swiftsure Capital, US-based private investment corporation focusing on the financing of early-stage businesses in the software,...

  17. Lab announces selection of partner for venture acceleration initiative

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    venture capital fund that invests in seed-stage, high-growth ventures in New Mexico. "The Venture Acceleration Initiative is an innovative program in a comprehensive...

  18. Workplace Charging Challenge Partner: Capital One Financial Corporatio...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Capital One Financial Corporation Workplace Charging Challenge Partner: Capital One Financial Corporation Workplace Charging Challenge Partner: Capital One Financial Corporation ...

  19. Financing U.S. Renewable Energy Projects Through Public Capital Vehicles: Qualitative and Quantitative Benefits

    SciTech Connect (OSTI)

    Mendelsohn, M.; Feldman, D.

    2013-04-01

    This paper explores the possibility of financing renewable energy projects through raising capital in the public markets. It gives an overview of the size, structure, and benefits of public capital markets, as well as showing how renewable energy projects might take advantage of this source of new funds to lower the cost of electricity.

  20. Human Capital Management Accountability Program

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2008-08-01

    The Order establishes requirements, roles and responsibilities for the Human Capital Management Accountability Program (HCMAP) for human resources programs and personnel and ensures that human capital activities are regulatory and procedurally compliant with Federal statutes and Departmental policies. Does not cancel other directives.

  1. Workplace Charging Installation Costs

    Broader source: Energy.gov [DOE]

    Installation costs and services vary considerably, so employers are encouraged to obtain a number of quotes before moving forward with any installation. An initial site investigation should include:

  2. Levelized Power Generation Cost Codes

    Energy Science and Technology Software Center (OSTI)

    1996-04-30

    LPGC is a set of nine microcomputer programs for estimating power generation costs for large steam-electric power plants. These programs permit rapid evaluation using various sets of economic and technical ground rules. The levelized power generation costs calculated may be used to compare the relative economics of nuclear and coal-fired plants based on life-cycle costs. Cost calculations include capital investment cost, operation and maintenance cost, fuel cycle cost, decommissioning cost, and total levelized power generationmore » cost. These programs can be used for quick analyses of power generation costs using alternative economic parameters, such as interest rate, escalation rate, inflation rate, plant lead times, capacity factor, fuel prices, etc. The two major types of electric generating plants considered are pressurized water reactor (PWR) and pulverized coal-fired plants. Data are also provided for the Large Scale Prototype Breeder (LSPB) type liquid metal reactor.« less

  3. Mont Vista Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Vista Capital LLC Jump to: navigation, search Name: Mont Vista Capital LLC Place: New York, New York Zip: 10167 Sector: Services Product: Mont Vista Capital is a leading global...

  4. EnerTech Capital | Open Energy Information

    Open Energy Info (EERE)

    EnerTech Capital Jump to: navigation, search Logo: EnerTech Capital Name: EnerTech Capital Address: 625 W. Ridge Pike, Building D, Suite 105 Place: Conshohocken, Pennsylvania Zip:...

  5. GreenCore Capital | Open Energy Information

    Open Energy Info (EERE)

    GreenCore Capital Jump to: navigation, search Logo: GreenCore Capital Name: GreenCore Capital Address: 10509 Vista Sorrento Parkway Place: San Diego, California Zip: 92121 Region:...

  6. EarthRise Capital | Open Energy Information

    Open Energy Info (EERE)

    EarthRise Capital Jump to: navigation, search Name: EarthRise Capital Place: New York, New York Zip: NY 10111 Sector: Efficiency Product: Venture capital fund focused on new...

  7. Where might I find simplified Data on Capital, O&M, and fuel...

    Open Energy Info (EERE)

    Where might I find simplified Data on Capital, O&M, and fuel costs? Home I teach math to high school seniors. My students are studying energy in all their classes. I have just...

  8. Capital Energy Offshore | Open Energy Information

    Open Energy Info (EERE)

    Sector: Wind energy Product: JV between Gamesa and Capital Energy to develop offshore wind farms References: Capital Energy Offshore1 This article is a stub. You can help...

  9. Carbon Credit Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Carbon Credit Capital Place: New York, New York Zip: 10012 Sector: Carbon, Services Product: Project Advisory Services and Carbon...

  10. Ethanol Capital Funding | Open Energy Information

    Open Energy Info (EERE)

    Ethanol Capital Funding Jump to: navigation, search Name: Ethanol Capital Funding Place: Atlanta, Georgia Zip: 30328 Product: Provides funding for ethanol and biodiesel plants....

  11. Atlantic Ethanol Capital | Open Energy Information

    Open Energy Info (EERE)

    Ethanol Capital Jump to: navigation, search Name: Atlantic Ethanol Capital Place: Washington, Washington, DC Product: Biofuel Investor in Caribbean and Central American region....

  12. Blue Green Capital | Open Energy Information

    Open Energy Info (EERE)

    Green Capital Jump to: navigation, search Name: Blue Green Capital Place: Spain Zip: 8860 Sector: Renewable Energy, Solar Product: String representation "Spanish develop ... their...

  13. Green Energy Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    Capital Partners Jump to: navigation, search Name: Green Energy Capital Partners Place: Plymouth Meeting, Pennsylvania Zip: 19462 Sector: Wind energy Product: Pennsylvania-based...

  14. MVP Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    navigation, search Logo: MVP Capital Partners Name: MVP Capital Partners Address: 201 King of Prussia Road, Suite 240 Place: Radnor, Pennsylvania Zip: 19087 Region: Northeast -...

  15. L A Investment Capital | Open Energy Information

    Open Energy Info (EERE)

    A Investment Capital Jump to: navigation, search Name: L.A. Investment Capital Place: Beverly Hills, California Zip: CA 90210 Sector: Biofuels Product: Investment firm with funds...

  16. Marathon Capital LLC (California) | Open Energy Information

    Open Energy Info (EERE)

    Marathon Capital LLC (California) Name: Marathon Capital LLC (California) Address: 42 Miller Avenue Place: Mill Valley, California Zip: 94941 Region: Bay Area Product: Investment...

  17. Jane Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    search Logo: Jane Capital Partners Name: Jane Capital Partners Address: 505 Montgomery, 2nd Floor Place: San Francisco, California Zip: 94111 Region: Bay Area Product:...

  18. Nature Elements Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Nature Elements Capital Place: Beijing, Beijing Municipality, China Zip: 100125 Product: Beijing-based private equity firm investing in...

  19. Capital Sources and Providers | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Capital Sources and Providers Capital Sources and Providers An image of a blue diagram showing an arrow labeled "Lender" pointing to a rectangle labeled "Borrower" with a curved ...

  20. Viresco International Capital Management | Open Energy Information

    Open Energy Info (EERE)

    International Capital Management Jump to: navigation, search Name: Viresco International Capital Management Place: San Diego, California Zip: 92130 Product: San Diego-based hedge...

  1. Greenwood Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    Greenwood Capital Partners Jump to: navigation, search Name: Greenwood Capital Partners Place: Charlotte, North Carolina Zip: 28266 Product: Corporate finance boutique working on...

  2. Montauk Energy Capital | Open Energy Information

    Open Energy Info (EERE)

    Montauk Energy Capital Jump to: navigation, search Name: Montauk Energy Capital Place: Pittsburg, Pennsylvania Zip: 15220 Product: Owns and operates landfill gas plants across the...

  3. New Energy Capital Corp | Open Energy Information

    Open Energy Info (EERE)

    Capital Corp Jump to: navigation, search Name: New Energy Capital Corp. Place: Hanover, New Hampshire Zip: 3755 Sector: Renewable Energy Product: Private equity fund focused on...

  4. Quadrant Capital Advisors Inc | Open Energy Information

    Open Energy Info (EERE)

    Quadrant Capital Advisors Inc Jump to: navigation, search Name: Quadrant Capital Advisors Inc. Place: New York, New York Zip: 10022 Sector: Hydro, Wind energy Product: US based...

  5. Arctas Capital Group | Open Energy Information

    Open Energy Info (EERE)

    Arctas Capital Group Jump to: navigation, search Name: Arctas Capital Group Place: Houston, Texas Zip: 77056 Sector: Geothermal energy, Renewable Energy, Wind energy Product: A...

  6. Krass Capital Group AG | Open Energy Information

    Open Energy Info (EERE)

    Krass Capital Group AG Jump to: navigation, search Name: Krass Capital Group AG Place: Grfelfing, Bulgaria Zip: 82166 Sector: Renewable Energy Product: Grafelfing-based firm...

  7. North Cove Capital Advisors | Open Energy Information

    Open Energy Info (EERE)

    Cove Capital Advisors Jump to: navigation, search Name: North Cove Capital Advisors Place: Connecticut Sector: Carbon Product: North Cove is an advisory firm that works...

  8. Starlight Capital Advisors | Open Energy Information

    Open Energy Info (EERE)

    Starlight Capital Advisors Jump to: navigation, search Name: Starlight Capital Advisors Place: Carlsbad, California Zip: 92011 Sector: Renewable Energy Product: California-based...

  9. Climate Human Capital | Open Energy Information

    Open Energy Info (EERE)

    Human Capital Jump to: navigation, search Name: Climate Human Capital Place: London, United Kingdom Zip: W1K 6NG Sector: Carbon, Renewable Energy, Services Product: Green executive...

  10. Digital Power Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Capital LLC Jump to: navigation, search Name: Digital Power Capital LLC Place: Greenwich, Connecticut Zip: 6830 Product: A private equity firm focused on new technologies that...

  11. Solution Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    Solution Capital Partners Jump to: navigation, search Name: Solution Capital Partners Place: New York Zip: NY 10036 Product: A New York-based investment firm active in the...

  12. American Capital Energy | Open Energy Information

    Open Energy Info (EERE)

    Energy Jump to: navigation, search Logo: American Capital Energy Name: American Capital Energy Address: 15 Tyngsboro Rd. Suite 4A Place: North Chelmsford, Massachusetts Zip: 01863...

  13. Cape Verde Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Cape Verde Capital Place: Leatherhead, United Kingdom Zip: KT22 7SW Sector: Renewable Energy Product: The renewable energy investment arm...

  14. Greentech Capital Advisors GCA | Open Energy Information

    Open Energy Info (EERE)

    Capital Advisors GCA Jump to: navigation, search Name: Greentech Capital Advisors (GCA) Place: New York, New York Zip: 10017 Sector: Renewable Energy Product: New York-based...

  15. Transmission Capital Limited | Open Energy Information

    Open Energy Info (EERE)

    Transmission Capital Limited Jump to: navigation, search Name: Transmission Capital Limited Place: London, United Kingdom Zip: EC2V 7HR Sector: Renewable Energy, Services Product:...

  16. Sustainable Development Capital LLP | Open Energy Information

    Open Energy Info (EERE)

    Capital LLP Jump to: navigation, search Name: Sustainable Development Capital LLP Place: London, United Kingdom Zip: W1S 3AT Product: Investment bank working with financial...

  17. Conservation Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Conservation Capital LLC Jump to: navigation, search Name: Conservation Capital LLC Place: Houston, Texas Zip: 77018 Product: Houston-based land investment and consulting company...

  18. Longboard Capital Advisors | Open Energy Information

    Open Energy Info (EERE)

    Longboard Capital Advisors Jump to: navigation, search Name: Longboard Capital Advisors Place: Santa Monica, California Zip: 90405 Product: Longboard is a small hedge fund focused...

  19. Haywood Dorland Energy Capital | Open Energy Information

    Open Energy Info (EERE)

    Dorland Energy Capital Jump to: navigation, search Name: Haywood Dorland Energy Capital Place: New York, New York Sector: Renewable Energy Product: New York-based private equity...

  20. Energy Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    LLC Jump to: navigation, search Name: Energy Capital LLC Place: Ketchum, Idaho Zip: ID 83340 Sector: Renewable Energy Product: Energy Capital LLc is a financial catalyst focusing...

  1. Wind Farm Capital | Open Energy Information

    Open Energy Info (EERE)

    Farm Capital Jump to: navigation, search Name: Wind Farm Capital Place: Connecticut Sector: Wind energy Product: US-based company that buys wind leases from farmers and landowners,...

  2. Beijing Capital International Airport | Open Energy Information

    Open Energy Info (EERE)

    International Airport Jump to: navigation, search Name: Beijing Capital International Airport Place: Beijing, Beijing Municipality, China Zip: 100621 Product: Beijing Capital...

  3. Nimes Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Nimes Capital LLC Jump to: navigation, search Name: Nimes Capital LLC Place: Los Angeles, California Zip: 90067 Product: Los Angeles-based private equity firm that provides growth...

  4. Clean Earth Capital LLP | Open Energy Information

    Open Energy Info (EERE)

    Capital LLP Jump to: navigation, search Name: Clean Earth Capital LLP Place: EDINBURGH, United Kingdom Zip: EH6 4NW Sector: Renewable Energy Product: Edinburgh-based corporate...

  5. Sequoia Capital Ltda | Open Energy Information

    Open Energy Info (EERE)

    Capital Ltda Jump to: navigation, search Name: Sequoia Capital Ltda Place: Sao Paulo, Sao Paulo, Brazil Sector: Wind energy Product: Brazilian-based wind project developer....

  6. Wind Capital Group | Open Energy Information

    Open Energy Info (EERE)

    Capital Group Jump to: navigation, search Name: Wind Capital Group Place: St. Louis, Missouri Zip: 63101 Sector: Wind energy Product: Missouri-based wind project developer, focused...

  7. Impact Capital Partners Limited | Open Energy Information

    Open Energy Info (EERE)

    Capital Partners Limited Jump to: navigation, search Name: Impact Capital Partners Limited Place: Los Angeles, California Zip: CA 90067-1509 Product: Los Angeles-based, investment...

  8. Ambata Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    Ambata Capital Partners Jump to: navigation, search Name: Ambata Capital Partners Place: New York, New York Zip: 10169 Product: New York-based global investment and advisory firm...

  9. Strategic Capital Investments LLC | Open Energy Information

    Open Energy Info (EERE)

    Capital Investments LLC Jump to: navigation, search Name: Strategic Capital Investments LLC Place: Short Hills, New Jersey Zip: 7078 Product: New Jersey-based, project development...

  10. Black Coral Capital | Open Energy Information

    Open Energy Info (EERE)

    Coral Capital Jump to: navigation, search Name: Black Coral Capital Address: 55 Union Street, 3rd Floor Place: Boston, Massachusetts Zip: 02108 Region: Greater Boston Area Product:...

  11. James Monroe Capital Corporation | Open Energy Information

    Open Energy Info (EERE)

    Monroe Capital Corporation Jump to: navigation, search Name: James Monroe Capital Corporation Place: United States Sector: Services Product: General Financial & Legal Services (...

  12. Birch Tree Capital | Open Energy Information

    Open Energy Info (EERE)

    Birch Tree Capital Jump to: navigation, search Name: Birch Tree Capital Place: Framingham, Massachusetts Zip: 1701 Sector: Renewable Energy Product: Financial advisory service with...

  13. American Capital Energy Inc | Open Energy Information

    Open Energy Info (EERE)

    Capital Energy Inc Jump to: navigation, search Name: American Capital Energy Inc Place: North Chelmsford, Massachusetts Zip: 1863 Sector: Services Product: Full-service PV...

  14. Bannockburn Capital LTD | Open Energy Information

    Open Energy Info (EERE)

    Bannockburn Capital LTD Jump to: navigation, search Name: Bannockburn Capital, LTD. Place: Newport Beach, California Zip: 92657 Sector: Carbon, Renewable Energy Product: String...

  15. Sustainable World Capital | Open Energy Information

    Open Energy Info (EERE)

    World Capital Jump to: navigation, search Name: Sustainable World Capital Place: Atlanta, Georgia Zip: 30326 Product: Atlanta-based firm that connects companies with institutional...

  16. West Mountain Energy Capital | Open Energy Information

    Open Energy Info (EERE)

    Energy Capital Jump to: navigation, search Name: West Mountain Energy Capital Place: Salisbury, Connecticut Zip: 6070 Sector: Renewable Energy Product: Provides renewable resource...

  17. Marathon Capital LLC (Illinois) | Open Energy Information

    Open Energy Info (EERE)

    Logo: Marathon Capital LLC (Illinois) Name: Marathon Capital LLC (Illinois) Address: 2801 Lakeside Drive, Suite 210 Place: Bannockburn, Illinois Zip: 60015 Product: Investment...

  18. Cate Street Capital Inc | Open Energy Information

    Open Energy Info (EERE)

    Cate Street Capital Inc Jump to: navigation, search Name: Cate Street Capital, Inc. Place: Portsmouth, New Hampshire Zip: 3801 Sector: Renewable Energy Product: New Hampshire-based...

  19. New Cycle Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Cycle Capital LLC Jump to: navigation, search Name: New Cycle Capital, LLC. Place: San Francisco, California Zip: 94103 Product: San Francisco-based venture capitalist firm...

  20. Microsoft PowerPoint - Cost Escalation.ppt

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Hydroelectric Design Center Hydroelectric Design Center " " Cost Trends for Cost Trends for Hydropower Capital Hydropower Capital Replacements" Replacements" Presentation Outline Presentation Outline A little about HDC A little about HDC Cost Escalation of materials Cost Escalation of materials Issues impacting interest & bids Issues impacting interest & bids Discussion Discussion HDC Expertise HDC Expertise Mission Mission The Hydroelectric Design Center performs The

  1. Mr. Walter Huber, Director Capital Improvements Division National Capital Region

    Office of Legacy Management (LM)

    Walter Huber, Director Capital Improvements Division National Capital Region 7th & D Streets, N.W. Washington, D.C. 20407 Dear Mr. Huber: As you may know, the Department of Energy (DOE) is evaluating the radiological condition of sites that were utilized under the Manhattan Engineer District (MED) and the Atomic Energy Commission (AEC) during the early years of nuclear development to determine whether they need remedial action and whether the Department has authority to perform such action.

  2. Riba Capital | Open Energy Information

    Open Energy Info (EERE)

    Place: Spain Sector: Renewable Energy Product: Riba Capital is a fund developed to invest in renewable projects in Iberia. It raised 800 million euros of financing in 2003 and...

  3. Capital Solar | Open Energy Information

    Open Energy Info (EERE)

    Solar Jump to: navigation, search Name: Capital Solar Place: Lecce, Italy Sector: Solar Product: Lecce-based solar project developer. Coordinates: 40.357955, 18.16801 Show Map...

  4. Human Capital Organization | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Human Capital Organization Human Capital Organization HC Organizational Chart HC Organizational Chart Printable Version The Office of the Chief Human Capital Officer provides leadership to the Department of Energy (DOE) on the impact and use of policies, proposals, programs, and partnerships related to all aspects of Human Capital Management (HCM).

  5. Startup Costs

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    This chapter discusses startup costs for construction and environmental projects, and estimating guidance for startup costs.

  6. Electricity Generation Cost Simulation Model

    Energy Science and Technology Software Center (OSTI)

    2003-04-25

    The Electricity Generation Cost Simulation Model (GENSIM) is a user-friendly, high-level dynamic simulation model that calculates electricity production costs for variety of electricity generation technologies, including: pulverized coal, gas combustion turbine, gas combined cycle, nuclear, solar (PV and thermal), and wind. The model allows the user to quickly conduct sensitivity analysis on key variables, including: capital, O&M, and fuel costs; interest rates; construction time; heat rates; and capacity factors. The model also includes consideration ofmore » a wide range of externality costs and pollution control options for carbon dioxide, nitrogen oxides, sulfur dioxide, and mercury. Two different data sets are included in the model; one from the U.S. Department of Energy (DOE) and the other from Platt's Research Group. Likely users of this model include executives and staff in the Congress, the Administration and private industry (power plant builders, industrial electricity users and electric utilities). The model seeks to improve understanding of the economic viability of various generating technologies and their emission trade-offs. The base case results using the DOE data, indicate that in the absence of externality costs, or renewable tax credits, pulverized coal and gas combined cycle plants are the least cost alternatives at 3.7 and 3.5 cents/kwhr, respectively. A complete sensitivity analysis on fuel, capital, and construction time shows that these results coal and gas are much more sensitive to assumption about fuel prices than they are to capital costs or construction times. The results also show that making nuclear competitive with coal or gas requires significant reductions in capital costs, to the $1000/kW level, if no other changes are made. For renewables, the results indicate that wind is now competitive with the nuclear option and is only competitive with coal and gas for grid connected applications if one includes the federal production tax credit of 1.8 cents/kwhr.« less

  7. IT Capital Planning | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    IT Capital Planning IT Capital Planning IT7 (003).jpg What is Capital Planning? The Office of Management and Budget (OMB) Circular A-11, defines capital planning as "a decision-making process for ensuring IT investments integrate strategic planning, budgeting, procurement, and IT management in support of agency missions and business needs." Who's Responsible for DOE Capital Planning? The Office of the Chief Information Officer (OCIO) oversees the DOE IT portfolio, while the Information

  8. EGov PMA Scorecard Cost, Schedule & Performance Standard.tif | Department

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    of Energy EGov PMA Scorecard Cost, Schedule & Performance Standard.tif EGov PMA Scorecard Cost, Schedule & Performance Standard.tif PDF icon EGov PMA Scorecard Cost, Schedule & Performance Standard.tif More Documents & Publications Program & Project Management For The Acquisition Of Capital Assets Program & Project Management For The Acquisition Of Capital Assets Program & Project Management For The Acquisition Of Capital Assets

  9. ErgyCapital SpA formerly Greenergy Capital | Open Energy Information

    Open Energy Info (EERE)

    SpA formerly Greenergy Capital Jump to: navigation, search Name: ErgyCapital SpA (formerly Greenergy Capital) Place: Milan, Italy Zip: 20121 Sector: Efficiency, Renewable Energy...

  10. Trends in U.S. Oil and Natural Gas Upstream Costs - Energy Information...

    U.S. Energy Information Administration (EIA) Indexed Site

    The IHS report assesses capital and operating costs associated with drilling, completing, and operating wells and facilities. The report focuses on five onshore regions, including ...

  11. RESULTS FROM THE U.S. DOE 2006 SAVE ENERGY NOW ASSESSMENT INITIATIVE: DOE's Partnership with U.S. Industry to Reduce Energy Consumption, Energy Costs, and Carbon Dioxide Emissions

    SciTech Connect (OSTI)

    Wright, Anthony L; Martin, Michaela A; Gemmer, Bob; Scheihing, Paul; Quinn, James

    2007-09-01

    In the wake of Hurricane Katrina and other severe storms in 2005, natural gas supplies were restricted, prices rose, and industry sought ways to reduce its natural gas use and costs. In October 2005, U.S. Department of Energy (DOE) Energy Secretary Bodman launched his Easy Ways to Save Energy campaign with a promise to provide energy assessments to 200 of the largest U.S. manufacturing plants. A major thrust of the campaign was to ensure that the nation's natural gas supplies would be adequate for all Americans, especially during home heating seasons. In a presentation to the National Press Club on October 3, 2005, Secretary Bodman said: 'America's businesses, factories, and manufacturing facilities use massive amounts of energy. To help them during this period of tightening supply and rising costs, our Department is sending teams of qualified efficiency experts to 200 of the nation's most energy-intensive factories. Our Energy Saving Teams will work with on-site managers on ways to conserve energy and use it more efficiently.' DOE's Industrial Technologies Program (ITP) responded to the Secretary's campaign with its Save Energy Now initiative, featuring a new and highly cost-effective form of energy assessments. The approach for these assessments drew heavily on the existing resources of ITP's Technology Delivery component. Over the years, ITP-Technology Delivery had worked with industry partners to assemble a suite of respected software decision tools, proven assessment protocols, training curricula, certified experts, and strong partnerships for deployment. Because of the program's earlier activities and the resources that had been developed, ITP was prepared to respond swiftly and effectively to the sudden need to promote improved industrial energy efficiency. Because of anticipated supply issues in the natural gas sector, the Save Energy Now initiative strategically focused on natural gas savings and targeted the nation's largest manufacturing plants--those that consume a total of 1 trillion British thermal units (Btu) or more annually. The approximately 6800 U.S. facilities that fall into this category collectively account for about 53% of all energy consumed by industry in the United States. The 2006 Save Energy Now energy assessments departed from earlier DOE plant assessments by concentrating solely on steam and process heating systems, which are estimated to account for approximately 74% of all natural gas use for manufacturing. The assessments also integrated a strong training component designed to teach industrial plant personnel how to use DOE's steam or process heating opportunity assessment software tools. This approach had the advantages of promoting strong buy-in of plant personnel for the assessment and its outcomes and preparing them better to independently replicate the assessment process at the company's other facilities. The Save Energy Now initiative also included provisions to help plants that applied for but did not qualify for assessments (based on the 1 trillion Btu criterion). Services offered to these plants included (1) an assessment by one of DOE's 26 university-based Industrial Assessment Centers (IACs), (2) a telephone consultation with a systems expert at the DOE's Energy Efficiency and Renewable Energy Information Center, or (3) other technical materials and services available through ITP (e.g., the Save Energy Now CD). By the end of 2006, DOE had completed all 200 of the promised assessments, identifying potential natural gas savings of more than 50 trillion Btu and energy cost savings of about $500 million. These savings, if fully implemented, could reduce CO2 emissions by 4.04 million metric tons annually. These results, along with the fact that a large percentage of U.S. energy is used by a relatively small number of very large plants, clearly suggest that assessments are an expedient and cost-effective way to significantly affect large amounts of energy use. Building on the success of the 2006 initiative, ITP has expanded the effort in 2007 with the goal of conducting 250 more asse

  12. Wind-To-Hydrogen Project: Electrolyzer Capital Cost Study

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    2008 Technical Report Wind-To-Hydrogen Project: NREL... H271.3730 National Renewable Energy Laboratory 1617 Cole ... hydrogen on a scale much greater than current production. ...

  13. Updated Capital Cost Estimates for Utility Scale Electricity...

    U.S. Energy Information Administration (EIA) Indexed Site

    ... produce an output of 60 Hz, three-phase 480 volt ("V") AC electric power voltage. The inverters also provide power quality control and protection when designed to IEEE Standards. ...

  14. Capital Projects Estimated >$7 Million in Direct Costs Business

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Transformer Replacement G1, G3,G5-8 Federal Hydro *-- Sustain Replace the existing transformers. Black Canyon Units 1 & 2 Upgrades Federal Hydro *-- Sustain Upgrades to increase...

  15. RockPort Capital Partners (California) | Open Energy Information

    Open Energy Info (EERE)

    RockPort Capital Partners (California) Jump to: navigation, search Logo: RockPort Capital Partners (California) Name: RockPort Capital Partners (California) Address: 3000 Sand Hill...

  16. Sindicatum Carbon Capital SCC | Open Energy Information

    Open Energy Info (EERE)

    Sindicatum Carbon Capital SCC Jump to: navigation, search Name: Sindicatum Carbon Capital (SCC) Place: London, United Kingdom Zip: W1S 1HX Product: SCC is a specialist end-to-end...

  17. Carbon Capital Markets | Open Energy Information

    Open Energy Info (EERE)

    Capital Markets Jump to: navigation, search Name: Carbon Capital Markets Place: London, United Kingdom Zip: W1J 8DY Sector: Carbon Product: London-based fund manager and trader...

  18. Capital Cooking: Order (2014-CE-23008)

    Broader source: Energy.gov [DOE]

    DOE ordered Capital Cooking Equipment, Inc. to pay a $8,000 civil penalty after finding Capital Cooking had failed to certify that certain models of cooking products comply with the applicable energy conservation standards.

  19. Eco Drive Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    Capital Partners Jump to: navigation, search Name: Eco-Drive Capital Partners Place: New York Product: New York-based Eco-Drive is a European-American investment consortium,...

  20. Absolute Energy Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Absolute Energy Capital Place: London, United Kingdom Zip: SW1Y 5NQ Product: London-based private equity firm. Coordinates: 51.506325,...

  1. Englefield Capital LLP | Open Energy Information

    Open Energy Info (EERE)

    Englefield Capital LLP Jump to: navigation, search Name: Englefield Capital LLP Place: London, Greater London, United Kingdom Zip: SW3 6RD Product: London-based private equity fund...

  2. Emerging Edge Capital EEC | Open Energy Information

    Open Energy Info (EERE)

    Edge Capital EEC Jump to: navigation, search Name: Emerging Edge Capital (EEC) Place: London, United Kingdom Zip: SW1Y 4RS Sector: Renewable Energy Product: London-based company...

  3. Cinergy Capital & Trading, Inc | Open Energy Information

    Open Energy Info (EERE)

    Cinergy Capital & Trading, Inc Jump to: navigation, search Name: Cinergy Capital & Trading, Inc Place: Indiana Phone Number: (704) 382-3747 or (513) 287-2226 or (317) 838-1338...

  4. Eco Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Capital LLC Jump to: navigation, search Name: Eco Capital LLC Place: New York, New York Zip: 10166 Sector: Carbon, Renewable Energy Product: New York-based advisory and investment...

  5. Plane Tree Capital LLP | Open Energy Information

    Open Energy Info (EERE)

    Plane Tree Capital LLP Jump to: navigation, search Name: Plane Tree Capital LLP Place: London, United Kingdom Zip: W1J 8DY Sector: Carbon Product: London-based investment...

  6. Absolut Energy Capital | Open Energy Information

    Open Energy Info (EERE)

    Absolut Energy Capital Jump to: navigation, search Name: Absolut Energy Capital Place: London, England, United Kingdom Zip: W1H - 6HN Sector: Renewable Energy Product: London-based...

  7. Post-2011 Review Workgroup 1 Initial Analysis of Funding Alternatives...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    is understood Doesn't fully address some customers' concerns about BPA incurring capital costs on their behalf Doesn't provide an option for 100% self-management of...

  8. Clean Energy and Bond Finance Initiative

    Broader source: Energy.gov [DOE]

    Provides information on Clean Energy and Bond Finance Initiative (CE+BFI). CE+BFI brings together public infrastructure finance agencies, clean energy public fund managers and institutional investors across the country to explore how to raise capital at scale for clean energy development through bond financing. Author: Clean Energy and Bond Finance Initiative

  9. Venture Capital Finance | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Venture Capital Finance Venture Capital Finance Plenary III: Project Finance and Investment Venture Capital Finance Brian Baynes, Partner, Flagship Ventures PDF icon baynes_biomass_2014.pdf More Documents & Publications Biomass 2011 Conference Agenda U.S. Biofuels Industry: Mind the Gap Review of Recent Pilot Scale Cellulosic Ethanol Demonstration

  10. Managing Large Capital Projects | Department of Energy

    Energy Savers [EERE]

    Managing Large Capital Projects Managing Large Capital Projects Presentation from the 2015 DOE National Cleanup Workshop by Ken Picha, Deputy Assistant Secretary for Tank Waste and Nuclear Material, Office of Environmental Management. PDF icon Managing Large Capital Projects More Documents & Publications Waste Treatment Plant Project Construction of Salt Waste Processing Facility (SWPF) 2013 Congressional Nuclear Cleanup Caucus Briefings

  11. EA-355 Scotia Capital Energy, Inc. | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    5 Scotia Capital Energy, Inc. EA-355 Scotia Capital Energy, Inc. Order authorizing Scotia Capital Energy, Inc. to export electric energy to Canada PDF icon EA-355 Scotia Capital ...

  12. Life Cycle Cost (LCC) Handbook Final Version 9-30-14

    Broader source: Energy.gov [DOE]

    This handbook provides procedures, information, examples, and tools to develop consistent and defensible life-cycle cost estimates (LCCE) and perform appropriate life-cycle cost analyses (LCCA) for capital projects. LCC Handbook – Final, September 2014

  13. A Review of Cost Estimation in New Technologies- Implications for Energy Process Plants

    Broader source: Energy.gov [DOE]

    This report reviews literature on cost estimation in several areas involving major capital expenditure programs: energy process plants, major weapons systems acquisition, public works and larger construction projects, and cost estimating techniques and problems for chemical process plants.

  14. National Lab Uses OGJ Data to Develop Cost Equations

    SciTech Connect (OSTI)

    Brown, Daryl R.; Cabe, James E.; Stout, Tyson E.

    2011-01-03

    For the past 30 years, the Oil and Gas Journal (OGJ) has published data on the costs of onshore and offshore oil and gas pipelines and related equipment. This article describes the methodology employed and resulting equations developed for conceptual capital cost estimating of onshore pipelines. Also described are cost trends uncovered during the course of the analysis.

  15. Offshore Wind Balance-of-System Cost Modeling

    SciTech Connect (OSTI)

    Maness, Michael; Stehly, Tyler; Maples, Ben; Mone, Christopher

    2015-09-29

    Offshore wind balance-of-system (BOS) costs contribute up to 70% of installed capital costs. Thus, it is imperative to understand the impact of these costs on project economics as well as potential cost trends for new offshore wind technology developments. As a result, the National Renewable Energy Laboratory (NREL) developed and recently updated a BOS techno-economic model using project cost estimates created from wind energy industry sources.

  16. Program and Project Management for the Acquisition of Capital Assets

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2010-11-29

    The purpose of this Order is to a) provide the Department of Energy (DOE) Elements, including the National Nuclear Security Administration (NNSA), with program and project management direction for the acquisition of capital assets with the goal of delivering projects within the original performance baseline (PB), cost and schedule, and fully capable of meeting mission performance, safeguards and security, and environmental, safety, and health requirements unless impacted by a directed change; and b) implement Office of Management and Budget (OMB) Circulars to include: A-11, Part 7, Capital Programming Guide, which prescribes new requirements and leading practices for project and acquisition management; A-123, Management's Responsibility for Internal Control, which defines management's responsibility for internal control in Federal agencies; and A-131, Value Engineering, which requires that all Federal agencies use Value Engineering (VE) as a management tool.

  17. Credit Enhancements and Capital Markets to Fund Solar Deployment: Leveraging Public Funds to Open Private Sector Investment

    SciTech Connect (OSTI)

    Mendelsohn, M.; Urdanick, M.; Joshi, J.

    2015-02-01

    Credit enhancements represent a variety of financial support structures that are designed to reduce risk to those holding the debt, including debt raised via a securitization process, and thus lower the required yield associated with the security. The purpose of all forms of credit enhancement is to increase the collateral against which notes are secured (Lin,1999). The following section evaluates is not guaranteed. Perceived risks of the solar asset class--including those related to technology, offtaker creditworthiness, and regulatory policy--can increase the required yield, increase probability of investor loss of interest and/or principal, or both. In many cases, this is a cyclical phenomenon: risk perception is fed by lack of historical knowledge, which is in turn fed by risk perception. Therefore, successful access to capital market investment in order to spur low-cost solar deployment depends on the success of this initial fledgling period.

  18. Next Generation Safeguards Initiatives at Los Alamos National Laboratory

    National Nuclear Security Administration (NNSA)

    Next Generation Safeguards Initiatives at Los Alamos National Laboratory Strengthening Human Capital for International Safeguards - 2009 * In October 2007, NNSA's Office of Nonproliferation and International Security (NA-24) urged the national laboratories to create projects devoted to improving human capital and training for nuclear safeguards as part of the Next Generation Safeguards Initiative (NGSI). * To meet this need, Los Alamos National Laboratory (LANL), Lawrence Livermore National

  19. Heliostat cost reduction study.

    SciTech Connect (OSTI)

    Jones, Scott A.; Lumia, Ronald. (University of New Mexico, Albuquerque, NM); Davenport, Roger (Science Applications International Corporation, San Diego, CA); Thomas, Robert C. (Advanced Thermal Systems, Centennial, CO); Gorman, David (Advanced Thermal Systems, Larkspur, CO); Kolb, Gregory J.; Donnelly, Matthew W.

    2007-06-01

    Power towers are capable of producing solar-generated electricity and hydrogen on a large scale. Heliostats are the most important cost element of a solar power tower plant. Since they constitute {approx} 50% of the capital cost of the plant it is important to reduce heliostat cost as much as possible to improve the economic performance of power towers. In this study we evaluate current heliostat technology and estimate a price of $126/m{sup 2} given year-2006 materials and labor costs for a deployment of {approx}600 MW of power towers per year. This 2006 price yields electricity at $0.067/kWh and hydrogen at $3.20/kg. We propose research and development that should ultimately lead to a price as low as $90/m{sup 2}, which equates to $0.056/kWh and $2.75/kg H{sup 2}. Approximately 30 heliostat and manufacturing experts from the United States, Europe, and Australia contributed to the content of this report during two separate workshops conducted at the National Solar Thermal Test Facility.

  20. Persimmon Tree Capital | Open Energy Information

    Open Energy Info (EERE)

    Renewable Energy Product: Persimmon is a private equity fund established in 2008 to invest in renewable energy firms. References: Persimmon Tree Capital1 This article is a...

  1. Ethanol Capital Management | Open Energy Information

    Open Energy Info (EERE)

    Management Jump to: navigation, search Name: Ethanol Capital Management Place: Tucson, Arizona Zip: 85711 Product: Manages funds investing in Ethanol plants in the US Coordinates:...

  2. Capital Energy SL | Open Energy Information

    Open Energy Info (EERE)

    search Name: Capital Energy SL Place: Madrid, Spain Zip: 28016 Sector: Solar, Wind energy Product: Offshore wind farm, solar and biodiesel plant developer. Coordinates:...

  3. Capital Cooking: Proposed Penalty (2014-CE-23008)

    Broader source: Energy.gov [DOE]

    DOE alleged in a Notice of Proposed Civil Penalty that Capital Cooking Equipment, Inc. failed to certify cooking products as compliant with the applicable energy conservation standards.

  4. Human Capital Management Accountability Program (HCMAP)

    Broader source: Energy.gov [DOE]

    Human Capital Management Accountability Program (HCMAP) is an online program which serves as the vehicle for identifying and measuring these three factors, effectiveness, efficiency, and timeliness...

  5. Environmental Capital Partners LLC | Open Energy Information

    Open Energy Info (EERE)

    Partners LLC Jump to: navigation, search Name: Environmental Capital Partners LLC Place: New York, New York Zip: 10017 Sector: Services Product: Private equity firm funded with USD...

  6. Global Capital Finance | Open Energy Information

    Open Energy Info (EERE)

    Finance Jump to: navigation, search Name: Global Capital Finance Place: Purchase, New York Zip: 10577 Sector: Renewable Energy, Services Product: New York-based international...

  7. Environmental Capital Group LLC | Open Energy Information

    Open Energy Info (EERE)

    Group LLC Jump to: navigation, search Name: Environmental Capital Group LLC Place: Grass Valley, California Zip: 95945 Product: String representation "Environmental C ... tartup...

  8. Report: Human Capital Discussion and Observations

    Office of Environmental Management (EM)

    Human Capital Discussion, Observations, and Recommendations August 24, 2006 Submitted by: Mr. A. James Barnes and Mr. Dennis Ferrigno Background: During the March 23-24, 2006 EMAB...

  9. Energy Capital Investments | Open Energy Information

    Open Energy Info (EERE)

    Investments Jump to: navigation, search Name: Energy Capital Investments Place: Phoenix, Arizona Zip: 85016 Product: An investment firm established by Najafi Companies with the...

  10. Solar Capital Inc | Open Energy Information

    Open Energy Info (EERE)

    Inc Jump to: navigation, search Name: Solar Capital Inc Place: Benicia, California Zip: 94510 Sector: Solar Product: Start-up investment firm seeking control positions in companies...

  11. Capital Electric Coop, Inc | Open Energy Information

    Open Energy Info (EERE)

    Capital Electric Coop, Inc Place: North Dakota Phone Number: 1.701.223.1513 Website: capitalelec.com Facebook: https:www.facebook.comcapitalelectricnd?refhl Outage Hotline:...

  12. RAM Capital Management Group | Open Energy Information

    Open Energy Info (EERE)

    Hydrogen Product: Private VC fund and investment banking advisory firm investing in fuel cells and hydrogen. References: RAM Capital Management Group1 This article is a...

  13. Expansion Capital Partners LLC | Open Energy Information

    Open Energy Info (EERE)

    Area Product: Venture capital firm that invests in expansion-stage, clean technology enterprises Year Founded: 2001 Phone Number: (415) 788-8802 Website: www.expansioncapital.com...

  14. Soft Costs | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Soft Costs Soft Costs The U.S. Department of Energy (DOE) SunShot Initiative accelerates the adoption of solar energy technologies in the marketplace. In support of SunShot Initiative goals, the solar office partners with manufacturers, communities, universities, utilities, and other stakeholders to: Reduce non-hardware costs Lower barriers Foster growth. These focus areas ensure that solar energy systems continue to become more affordable and accessible for Americans. Current Efforts DOE issues

  15. HTGR Cost Model Users' Manual

    SciTech Connect (OSTI)

    A.M. Gandrik

    2012-01-01

    The High Temperature Gas-Cooler Reactor (HTGR) Cost Model was developed at the Idaho National Laboratory for the Next Generation Nuclear Plant Project. The HTGR Cost Model calculates an estimate of the capital costs, annual operating and maintenance costs, and decommissioning costs for a high-temperature gas-cooled reactor. The user can generate these costs for multiple reactor outlet temperatures; with and without power cycles, including either a Brayton or Rankine cycle; for the demonstration plant, first of a kind, or nth of a kind project phases; for a single or four-pack configuration; and for a reactor size of 350 or 600 MWt. This users manual contains the mathematical models and operating instructions for the HTGR Cost Model. Instructions, screenshots, and examples are provided to guide the user through the HTGR Cost Model. This model was design for users who are familiar with the HTGR design and Excel. Modification of the HTGR Cost Model should only be performed by users familiar with Excel and Visual Basic.

  16. Workplace Charging Challenge Partner: Capital One Financial Corporation |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy Capital One Financial Corporation Workplace Charging Challenge Partner: Capital One Financial Corporation Workplace Charging Challenge Partner: Capital One Financial Corporation Capital One's Environmental Program seeks to reduce greenhouse gas (GHG) emissions throughout the organization's facilities and business practices. Since business travel and associate commuting contribute to these emissions, Capital One developed a Sustainable Transportation Demand Management

  17. Project Cost Profile Spreadsheet | Department of Energy

    Energy Savers [EERE]

    Project Cost Profile Spreadsheet Project Cost Profile Spreadsheet Under DOE O 413.3B, Program and Project Management for the Acquisition of Capital Assets, the Office of Acquisition and Project Management (OAPM) must perform a Performance Baseline External Independent Review (EIR) prior to Critical Decision (CD) 2, and a Construction/Execution Readiness EIR for all Major System projects prior to CD-3. The EIR Standard Operating Procedures (SOP) discuss all elements of EIRs including review

  18. Petascale Initiative

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Petascale Initiative Alice Koniges (third from left) led the Computational Science and ... (OSF), NERSC's operations center and was led by principal investigator Alice Koniges. ...

  19. Projects & Initiatives

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Expand Finance & Rates Involvement & Outreach Expand Involvement & Outreach Doing Business Expand Doing Business Skip navigation links Initiatives Columbia River Treaty Non...

  20. Pulsar Energy Capital L L P | Open Energy Information

    Open Energy Info (EERE)

    Pulsar Energy Capital L L P Jump to: navigation, search Name: Pulsar Energy Capital L.L.P. Place: London, United Kingdom Zip: SW20 0PU Product: Pulsar Energy Capital LLP is a...

  1. EA-184-B MORGAN STANLEY CAPITAL GROUP | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    -B MORGAN STANLEY CAPITAL GROUP EA-184-B MORGAN STANLEY CAPITAL GROUP Order authorizing Morgan Stanley Capital Group to export electric energy to Mexico. PDF icon EA-184-B MSCG ...

  2. EA-185 Morgan Stanley Capital Group Inc. | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Morgan Stanley Capital Group Inc. EA-185 Morgan Stanley Capital Group Inc. Order authorizing Morgan Stanley Capital Group Inc. to export electric energy to Canada. PDF icon EA-185 ...

  3. EA-184 Morgan Stanley Capital Group Inc. | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Morgan Stanley Capital Group Inc. EA-184 Morgan Stanley Capital Group Inc. Order authorizing Morgan Stanley Capital Group Inc. to export electric energy to Mexico. PDF icon EA-184 ...

  4. Agri capital GmbH | Open Energy Information

    Open Energy Info (EERE)

    capital GmbH Jump to: navigation, search Name: agri.capital GmbH Place: Muenster, North Rhine-Westphalia, Germany Zip: 48155 Product: Muenster-based agri.capital develops and...

  5. BluePlanet Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    BluePlanet Capital LLC Jump to: navigation, search Name: BluePlanet Capital LLC Place: Washington, Connecticut Zip: 6793 Sector: Services Product: BluePlanet Capital is an...

  6. Carbon Credit Capital and Feedback Ventures JV | Open Energy...

    Open Energy Info (EERE)

    Capital and Feedback Ventures JV Jump to: navigation, search Name: Carbon Credit Capital and Feedback Ventures JV Place: India Sector: Carbon Product: String representation "Carbon...

  7. Grupo Maris Capital ethanol refinery | Open Energy Information

    Open Energy Info (EERE)

    Maris Capital ethanol refinery Jump to: navigation, search Name: Grupo Maris (Capital ethanol refinery) Place: Nuporanga, Brazil Product: 32,000 m3 ethanol refinery owner...

  8. TianDi Growth Capital | Open Energy Information

    Open Energy Info (EERE)

    Venture capital investor interested in projects in Wind energy, Electric vehicles, Energy-efficient lighting, Biodiesel and Clean water. References: TianDi Growth Capital1...

  9. Low Capital Photovoltaic Panel Electrical Output-Booster System...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Low Capital Photovoltaic Panel Electrical Output-Booster System Low Capital Photovoltaic Panel Electrical Output-Booster System This presentation summarizes the information given ...

  10. Guide to IT Capital Planning and Investment Control

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    IT Capital Planning and Investment Control April 2014 i TABLE OF CONTENTS TABLE OF ......... 2 2.1 Capital Planning and Investment Control ...

  11. Chief Human Capital Officer Memo on Improving DOE Recruitment...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Chief Human Capital Officer Memo on Improving DOE Recruitment and Hiring Processes Chief Human Capital Officer Memo on Improving DOE Recruitment and Hiring Processes This is a ...

  12. Tribal Renewable Energy Webinar: Accessing Capital for Tribal...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Accessing Capital for Tribal Energy and Economic Development Tribal Renewable Energy Webinar: Accessing Capital for Tribal Energy and Economic Development October 26, 2016 11:00AM ...

  13. Human Capital Policy Division (HC-11) | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    About Us Organization Policy, Accountability, and Technology (HC-10) Human Capital Policy Division (HC-11) Human Capital Policy Division (HC-11) Mission Statement This ...

  14. Office of Executive Resources Office of the Chief Human Capital...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Executive Resources Office of the Chief Human Capital Officer U.S. Department of Energy ... and performance awards. c. Chief Human Capital Officer (CHCO) and Office of Executive ...

  15. Maryland-National Capital Building Industry Association Regulatory...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Maryland-National Capital Building Industry Association Regulatory Burden RFI (Federal Register August 8, 2012) Maryland-National Capital Building Industry Association Regulatory ...

  16. Manager's Desk Reference on Human Capital Management Flexibilities...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Manager's Desk Reference on Human Capital Management Flexibilities Manager's Desk Reference on Human Capital Management Flexibilities The purpose of this document is to provide DOE ...

  17. Energy and Environmental Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Capital LLC Jump to: navigation, search Name: Energy and Environmental Capital LLC Place: Washington, DC Sector: Carbon Product: The company focuses on carbon trading in ex-Soviet...

  18. BlueWave Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    BlueWave Capital LLC Jump to: navigation, search Name: BlueWave Capital LLC Place: Boston, Massachusetts Sector: Renewable Energy Product: Knowledge-based investment firm focused...

  19. Ricmore Capital PLC Formerly Energy Asset Management Plc | Open...

    Open Energy Info (EERE)

    Ricmore Capital PLC Formerly Energy Asset Management Plc Jump to: navigation, search Name: Ricmore Capital PLC (Formerly Energy Asset Management Plc) Place: United Kingdom Sector:...

  20. MissionPoint Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    MissionPoint Capital Partners Jump to: navigation, search Name: MissionPoint Capital Partners Place: Norwalk, Connecticut Zip: CT 06854 Product: Private Investment company...

  1. Sustainable Energy Capital Partners SECP | Open Energy Information

    Open Energy Info (EERE)

    Capital Partners SECP Jump to: navigation, search Name: Sustainable Energy Capital Partners (SECP) Place: Santa Ana, California Zip: 92705 Sector: Renewable Energy Product:...

  2. Program & Project Management For The Acquisition Of Capital Assets...

    Broader source: Energy.gov (indexed) [DOE]

    More Documents & Publications Program & Project Management For The Acquisition Of Capital Assets Program & Project Management For The Acquisition Of Capital Assets PARS II...

  3. DTE Energy Venture formerly EdVenture Capital Corporation | Open...

    Open Energy Info (EERE)

    Venture formerly EdVenture Capital Corporation Jump to: navigation, search Name: DTE Energy Venture (formerly EdVenture Capital Corporation) Place: Detroit, Michigan Zip: 48226...

  4. Noventi Venture Capital formerly CIR Ventures | Open Energy Informatio...

    Open Energy Info (EERE)

    Noventi Venture Capital formerly CIR Ventures Jump to: navigation, search Name: Noventi Venture Capital (formerly CIR Ventures) Place: Menlo Park, California Zip: CA 94025 Product:...

  5. RockPort Capital Partners (Massachusetts) | Open Energy Information

    Open Energy Info (EERE)

    RockPort Capital Partners (Massachusetts) Name: RockPort Capital Partners (Massachusetts) Address: 160 Federal Street, 18th Floor Place: Boston, Massachusetts Zip: 02110 Region:...

  6. Sinopec Beijing Capital Sci Tech Group JV | Open Energy Information

    Open Energy Info (EERE)

    Sinopec Beijing Capital Sci Tech Group JV Jump to: navigation, search Name: Sinopec & Beijing Capital Sci Tech Group JV Place: Beijing Municipality, China Product: China-based...

  7. Acro Energy Technologies formerly Lonestar Capital | Open Energy...

    Open Energy Info (EERE)

    Energy Technologies formerly Lonestar Capital Jump to: navigation, search Name: Acro Energy Technologies (formerly Lonestar Capital) Place: Oakdale, California Zip: 95361 Sector:...

  8. Green Capital Consulting Company GCCC | Open Energy Information

    Open Energy Info (EERE)

    Consulting Company GCCC Jump to: navigation, search Name: Green Capital Consulting Company (GCCC) Place: Beijing, China Zip: 100022 Product: Green Capital Consulting Company (GCCC)...

  9. IFCI Venture Capital Funds Ltd | Open Energy Information

    Open Energy Info (EERE)

    IFCI Venture Capital Funds Ltd Jump to: navigation, search Name: IFCI Venture Capital Funds Ltd Place: New Delhi, Delhi (NCT), India Zip: 110019 Product: Manager of several funds...

  10. Clean World Capital A S | Open Energy Information

    Open Energy Info (EERE)

    World Capital A S Jump to: navigation, search Name: Clean World Capital AS Place: Lyngby, Denmark Sector: Carbon Product: A cleantech finance house based in Copenhagen and London....

  11. CE2 Capital Partners LLC | Open Energy Information

    Open Energy Info (EERE)

    Capital Partners LLC Jump to: navigation, search Name: CE2 Capital Partners LLC Place: Solana Beach, California Zip: 92075 Sector: Carbon, Renewable Energy Product:...

  12. Free Stream Capital Partners Limited | Open Energy Information

    Open Energy Info (EERE)

    Capital Partners Limited Jump to: navigation, search Name: Free Stream Capital Partners Limited Place: London, Greater London, United Kingdom Zip: SW1Y 4AA Sector: Wind energy...

  13. BPA's Costs

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    links Financial Information Financial Public Processes Asset Management Cost Verification Process Rate Cases BP-18 Rate Case Related Publications Meetings and Workshops Customer...

  14. Parametric Analysis of the Factors Controlling the Costs of Sedimentary Geothermal Systems - Preliminary Results (Poster), NREL (National Renewable Energy Laboratory)

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Studies Several additional studies were conducted to explore the sensitivity of sedimentary geothermal system costs to key assumptions in the base case model. 1. Decreased Drilling Costs Assumed that drilling costs were 75% of those in the base case. * Total well field costs account for ~30%-50% of the total project costs in base case. * Assuming a 25% reduction in drilling costs reduces overall project capital costs by 8%-14%. * Impact increases with increasing reservoir depth (drilling costs

  15. Beyond Human Capital Development: Balanced Safeguards Workforce Metrics and the Next Generation Safeguards Workforce

    SciTech Connect (OSTI)

    Burbank, Roberta L.; Frazar, Sarah L.; Gitau, Ernest TN; Shergur, Jason M.; Scholz, Melissa A.; Undem, Halvor A.

    2014-03-28

    Since its establishment in 2008, the Next Generation Safeguards Initiative (NGSI) has achieved a number of objectives under its five pillars: concepts and approaches, policy development and outreach, international nuclear safeguards engagement, technology development, and human capital development (HCD). As a result of these efforts, safeguards has become much more visible as a critical U.S. national security interest across the U.S. Department of Energy (DOE) complex. However, limited budgets have since created challenges in a number of areas. Arguably, one of the more serious challenges involves NGSIs ability to integrate entry-level staff into safeguards projects. Laissez fair management of this issue across the complex can lead to wasteful project implementation and endanger NGSIs long-term sustainability. The authors provide a quantitative analysis of this problem, focusing on the demographics of the current safeguards workforce and compounding pressures to operate cost-effectively, transfer knowledge to the next generation of safeguards professionals, and sustain NGSI safeguards investments.

  16. Hydrogen Fuel Initiative | Open Energy Information

    Open Energy Info (EERE)

    Hydrogen Fuel Initiative Jump to: navigation, search Contents 1 Introduction 2 Cost 3 Hydrogen Production Strategy 4 Objectives 5 Manufacturing Challenges 6 References Introduction...

  17. 2011-2015 Human Capital Management Plan

    Broader source: Energy.gov [DOE]

    The Office of Legacy Management (LM) needs skilled and engaged staff to accomplish our mission and carry out our responsibilities to the American people. This Human Capital Management Plan (HCMP or...

  18. Beetle Capital Partners BCP | Open Energy Information

    Open Energy Info (EERE)

    Partners BCP Jump to: navigation, search Name: Beetle Capital Partners (BCP) Place: London, United Kingdom Zip: W1S 1UA Sector: Carbon Product: London-based asset management...

  19. Capital Equity Partners LLC | Open Energy Information

    Open Energy Info (EERE)

    Partners LLC Jump to: navigation, search Name: Capital Equity Partners LLC Address: 410 Park Avenue Place: New York, New York Zip: 10022 Region: Northeast - NY NJ CT PA Area...

  20. GE Capital Partnership | GE Global Research

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Global Research and GE Capital: Middle Market Collaboration Click to email this to a friend (Opens in new window) Share on Facebook (Opens in new window) Click to share (Opens in...

  1. Capital Equipment Validation Form | The Ames Laboratory

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Capital Equipment Validation Form Version Number: 2.0 Document Number: Form 48100.001 Effective Date: 022015 File (public): Office spreadsheet icon form48100.001rev2.xls...

  2. Cora Capital Advisors LLC | Open Energy Information

    Open Energy Info (EERE)

    Advisors LLC Jump to: navigation, search Name: Cora Capital Advisors LLC Place: New York, New York Zip: 10022 Sector: Renewable Energy Product: New York-based investment bank and...

  3. How three smart managers control steam costs

    SciTech Connect (OSTI)

    Kendall, R.

    1982-11-01

    Three steam-intensive companies report innovative ways to reduce steam-production costs. Goodyear Tire and Rubber Co. concentrated on regular maintenance, process modifications, and heat recovery, but also has an on-going policy of seeking further cost savings. Future efforts will explore computer-based boiler controls. Zenith Radio Corporation's color picture tube-making process uses 12% less steam after 700 mechanical steam traps were replaced with fixed-orifice traps. Petro-Tex Chemical Corp. reduced steam costs by monitoring and optimizing process units and by making capital investments to improve steam management. (DCK)

  4. Realistic costs of carbon capture

    SciTech Connect (OSTI)

    Al Juaied, Mohammed . Belfer Center for Science and International Affiaris); Whitmore, Adam )

    2009-07-01

    There is a growing interest in carbon capture and storage (CCS) as a means of reducing carbon dioxide (CO2) emissions. However there are substantial uncertainties about the costs of CCS. Costs for pre-combustion capture with compression (i.e. excluding costs of transport and storage and any revenue from EOR associated with storage) are examined in this discussion paper for First-of-a-Kind (FOAK) plant and for more mature technologies, or Nth-of-a-Kind plant (NOAK). For FOAK plant using solid fuels the levelised cost of electricity on a 2008 basis is approximately 10 cents/kWh higher with capture than for conventional plants (with a range of 8-12 cents/kWh). Costs of abatement are found typically to be approximately US$150/tCO2 avoided (with a range of US$120-180/tCO2 avoided). For NOAK plants the additional cost of electricity with capture is approximately 2-5 cents/kWh, with costs of the range of US$35-70/tCO2 avoided. Costs of abatement with carbon capture for other fuels and technologies are also estimated for NOAK plants. The costs of abatement are calculated with reference to conventional SCPC plant for both emissions and costs of electricity. Estimates for both FOAK and NOAK are mainly based on cost data from 2008, which was at the end of a period of sustained escalation in the costs of power generation plant and other large capital projects. There are now indications of costs falling from these levels. This may reduce the costs of abatement and costs presented here may be 'peak of the market' estimates. If general cost levels return, for example, to those prevailing in 2005 to 2006 (by which time significant cost escalation had already occurred from previous levels), then costs of capture and compression for FOAK plants are expected to be US$110/tCO2 avoided (with a range of US$90-135/tCO2 avoided). For NOAK plants costs are expected to be US$25-50/tCO2. Based on these considerations a likely representative range of costs of abatement from CCS excluding transport and storage costs appears to be US$100-150/tCO2 for first-of-a-kind plants and perhaps US$30-50/tCO2 for nth-of-a-kind plants.The estimates for FOAK and NOAK costs appear to be broadly consistent in the light of estimates of the potential for cost reductions with increased experience. Cost reductions are expected from increasing scale, learning on individual components, and technological innovation including improved plant integration. Innovation and integration can both lower costs and increase net output with a given cost base. These factors are expected to reduce abatement costs by approximately 65% by 2030. The range of estimated costs for NOAK plants is within the range of plausible future carbon prices, implying that mature technology would be competitive with conventional fossil fuel plants at prevailing carbon prices.

  5. EM Contractors for Capital Asset Projects | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Contractors for Capital Asset Projects EM Contractors for Capital Asset Projects Read the EM Contractors for Capital Asset Projects list, which includes the project name, number, site, and contractor. PDF icon EM Contractor List More Documents & Publications EM Capital Asset Project List EM Current Project Performance December 2015 Project Dashboard

  6. Renewable Energy Cost Optimization Spreadsheet

    Energy Science and Technology Software Center (OSTI)

    2007-12-31

    The Software allow users to determine the optimum combination of renewable energy technologies to minimize life cycle cost for a facility by employing various algorithms which calculate initial and operating cost, energy delivery, and other attributes associated with each technology as a function of size.

  7. Ocean Thermal Energy Conversion Life Cycle Cost Assessment, Final Technical Report, 30 May 2012

    SciTech Connect (OSTI)

    Martel, Laura; Smith, Paul; Rizea, Steven; Van Ryzin, Joe; Morgan, Charles; Noland, Gary; Pavlosky, Rick; Thomas, Michael

    2012-06-30

    The Ocean Thermal Energy Conversion (OTEC) Life Cycle Cost Assessment (OLCCA) is a study performed by members of the Lockheed Martin (LM) OTEC Team under funding from the Department of Energy (DOE), Award No. DE-EE0002663, dated 01/01/2010. OLCCA objectives are to estimate procurement, operations and maintenance, and overhaul costs for two types of OTEC plants: -Plants moored to the sea floor where the electricity produced by the OTEC plant is directly connected to the grid ashore via a marine power cable (Grid Connected OTEC plants) -Open-ocean grazing OTEC plant-ships producing an energy carrier that is transported to designated ports (Energy Carrier OTEC plants) Costs are developed using the concept of levelized cost of energy established by DOE for use in comparing electricity costs from various generating systems. One area of system costs that had not been developed in detail prior to this analysis was the operations and sustainment (O&S) cost for both types of OTEC plants. Procurement costs, generally referred to as capital expense and O&S costs (operations and maintenance (O&M) costs plus overhaul and replacement costs), are assessed over the 30 year operational life of the plants and an annual annuity calculated to achieve a levelized cost (constant across entire plant life). Dividing this levelized cost by the average annual energy production results in a levelized cost of electricity, or LCOE, for the OTEC plants. Technical and production efficiency enhancements that could result in a lower value of the OTEC LCOE were also explored. The thermal OTEC resource for Oahu, Hawai’i and projected build out plan were developed. The estimate of the OTEC resource and LCOE values for the planned OTEC systems enable this information to be displayed as energy supplied versus levelized cost of the supplied energy; this curve is referred to as an Energy Supply Curve. The Oahu Energy Supply Curve represents initial OTEC deployment starting in 2018 and demonstrates the predicted economies of scale as technology and efficiency improvements are realized and larger more economical plants deployed. Utilizing global high resolution OTEC resource assessment from the Ocean Thermal Extractable Energy Visualization (OTEEV) project (an independent DOE project), Global Energy Supply Curves were generated for Grid Connected and Energy Carrier OTEC plants deployed in 2045 when the predicted technology and efficiencies improvements are fully realized. The Global Energy Supply Curves present the LCOE versus capacity in ascending order with the richest, lowest cost resource locations being harvested first. These curves demonstrate the vast ocean thermal resource and potential OTEC capacity that can be harvested with little change in LCOE.

  8. Understanding Cost Growth and Performance Shortfalls in Pioneer Process

    Office of Environmental Management (EM)

    Plants | Department of Energy Cost Growth and Performance Shortfalls in Pioneer Process Plants Understanding Cost Growth and Performance Shortfalls in Pioneer Process Plants This report presents an empirical and quantitative analysis of the misestimation of the capital costs and performance of innovative energy process plants and other chemical process facilities that create fundamental problems for government and industry in planning the development and commercialization of such plants. PDF

  9. Building Life Cycle Cost Programs | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Building Life Cycle Cost Programs Building Life Cycle Cost Programs The National Institute of Standards and Technology (NIST) developed the Building Life Cycle Cost (BLCC) Programs to provide computational support for the analysis of capital investments in buildings. They include BLCC5, the Energy Escalation Rate Calculator, Handbook 135, and the Annual Supplement to Handbook 135. BLCC5 Program Register and download. BLCC 5.3-15 (for Windows or Mac OS X). BLCC version 5.3-15 contains the

  10. Saving Clams in the Halibut Capital of the World | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Clams in the Halibut Capital of the World Saving Clams in the Halibut Capital of the World December 20, 2011 - 10:44am Addthis Homer, population 5,364, known far and wide for its importance to Alaska's commercial fishing industry, spent $847,000 to conduct an initial energy audit and implement energy efficiency improvements that will drop the city's energy bill by $100,000 annually -- a reduction of approximately 14 percent. | Photo courtesy of Wikimedia Commons. Homer, population 5,364, known

  11. SCB initiator

    DOE Patents [OSTI]

    Bickes Jr., Robert W.; Renlund, Anita M.; Stanton, Philip L.

    1994-11-01

    A detonator for high explosives initiated by mechanical impact includes a cylindrical barrel, a layer of flyer material mechanically covering the barrel at one end, and a semiconductor bridge ignitor including a pair of electrically conductive pads connected by a semiconductor bridge. The bridge is in operational contact with the layer, whereby ignition of said bridge forces a portion of the layer through the barrel to detonate the explosive. Input means are provided for igniting the semiconductor bridge ignitor.

  12. SCB initiator

    DOE Patents [OSTI]

    Bickes, Jr., Robert W. (Albuquerque, NM); Renlund, Anita M. (Albuquerque, NM); Stanton, Philip L. (Albuquerque, NM)

    1994-01-01

    A detonator for high explosives initiated by mechanical impact includes a cylindrical barrel, a layer of flyer material mechanically covering the barrel at one end, and a semiconductor bridge ignitor including a pair of electrically conductive pads connected by a semiconductor bridge. The bridge is in operational contact with the layer, whereby ignition of said bridge forces a portion of the layer through the barrel to detonate the explosive. Input means are provided for igniting the semiconductor bridge ignitor.

  13. WREF 2012: THE PAST AND FUTURE COST OF WIND ENERGY

    SciTech Connect (OSTI)

    NREL,; Wiser, Ryan; Lantz, Eric; Hand, Maureen

    2012-03-26

    The future of wind power will depend on the ability of the industry to continue to achieve cost reductions. To better understand the potential for cost reductions, this report provides a review of historical costs, evaluates near-term market trends, and summarizes the range of projected costs. It also notes potential sources of future cost reductions. Our findings indicate that steady cost reductions were interrupted between 2004 and 2010, but falling turbine prices and improved turbine performance are expected to drive a historically low LCOE for current installations. In addition, the majority of studies indicate continued cost reductions on the order of 20%-30% through 2030. Moreover, useful cost projections are likely to benefit from stronger consideration of the interactions between capital cost and performance as well as trends in the quality of the wind resource where projects are located, transmission, grid integration, and other cost variables.

  14. Load Leveling Battery System Costs

    Energy Science and Technology Software Center (OSTI)

    1994-10-12

    SYSPLAN evaluates capital investment in customer side of the meter load leveling battery systems. Such systems reduce the customer's monthly electrical demand charge by reducing the maximum power load supplied by the utility during the customer's peak demand. System equipment consists of a large array of batteries, a current converter, and balance of plant equipment and facilities required to support the battery and converter system. The system is installed on the customer's side of themore » meter and controlled and operated by the customer. Its economic feasibility depends largely on the customer's load profile. Load shape requirements, utility rate structures, and battery equipment cost and performance data serve as bases for determining whether a load leveling battery system is economically feasible for a particular installation. Life-cycle costs for system hardware include all costs associated with the purchase, installation, and operation of battery, converter, and balance of plant facilities and equipment. The SYSPLAN spreadsheet software is specifically designed to evaluate these costs and the reduced demand charge benefits; it completes a 20 year period life cycle cost analysis based on the battery system description and cost data. A built-in sensitivity analysis routine is also included for key battery cost parameters. The life cycle cost analysis spreadsheet is augmented by a system sizing routine to help users identify load leveling system size requirements for their facilities. The optional XSIZE system sizing spreadsheet which is included can be used to identify a range of battery system sizes that might be economically attractive. XSIZE output consisting of system operating requirements can then be passed by the temporary file SIZE to the main SYSPLAN spreadsheet.« less

  15. SunShot Photovoltaic Manufacturing Initiative | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Technology to Market » SunShot Photovoltaic Manufacturing Initiative SunShot Photovoltaic Manufacturing Initiative The SunShot Photovoltaic Manufacturing Initiative (PVMI) invests in manufacturing-focused research projects that strengthen the competitiveness of the U.S. PV module industry and supply chain. PVMI funding also establishes manufacturing development facilities that provide infrastructure for demonstrating, testing, optimizing, and manufacturing new technologies with reduced capital

  16. Hanford tanks initiative plan

    SciTech Connect (OSTI)

    McKinney, K.E.

    1997-07-01

    Abstract: The Hanford Tanks Initiative (HTI) is a five-year project resulting from the technical and financial partnership of the U.S. Department of Energy`s Office of Waste Management (EM-30) and Office of Science and Technology Development (EM-50). The HTI project accelerates activities to gain key technical, cost performance, and regulatory information on two high-level waste tanks. The HTI will provide a basis for design and regulatory decisions affecting the remainder of the Tank Waste Remediation System`s tank waste retrieval Program.

  17. 2011 Cost of Wind Energy Review

    SciTech Connect (OSTI)

    Tegen, S.; Lantz, E.; Hand, M.; Maples, B.; Smith, A.; Schwabe, P.

    2013-03-01

    This report describes the levelized cost of energy (LCOE) for a typical land-based wind turbine installed in the United States in 2011, as well as the modeled LCOE for a fixed-bottom offshore wind turbine installed in the United States in 2011. Each of the four major components of the LCOE equation are explained in detail, such as installed capital cost, annual energy production, annual operating expenses, and financing, and including sensitivity ranges that show how each component can affect LCOE. These LCOE calculations are used for planning and other purposes by the U.S. Department of Energy's Wind Program.

  18. Wind turbine reliability : understanding and minimizing wind turbine operation and maintenance costs.

    SciTech Connect (OSTI)

    Not Available

    2004-11-01

    Wind turbine system reliability is a critical factor in the success of a wind energy project. Poor reliability directly affects both the project's revenue stream through increased operation and maintenance (O&M) costs and reduced availability to generate power due to turbine downtime. Indirectly, the acceptance of wind-generated power by the financial and developer communities as a viable enterprise is influenced by the risk associated with the capital equipment reliability; increased risk, or at least the perception of increased risk, is generally accompanied by increased financing fees or interest rates. Cost of energy (COE) is a key project evaluation metric, both in commercial applications and in the U.S. federal wind energy program. To reflect this commercial reality, the wind energy research community has adopted COE as a decision-making and technology evaluation metric. The COE metric accounts for the effects of reliability through levelized replacement cost and unscheduled maintenance cost parameters. However, unlike the other cost contributors, such as initial capital investment and scheduled maintenance and operating expenses, costs associated with component failures are necessarily speculative. They are based on assumptions about the reliability of components that in many cases have not been operated for a complete life cycle. Due to the logistical and practical difficulty of replacing major components in a wind turbine, unanticipated failures (especially serial failures) can have a large impact on the economics of a project. The uncertainty associated with long-term component reliability has direct bearing on the confidence level associated with COE projections. In addition, wind turbine technology is evolving. New materials and designs are being incorporated in contemporary wind turbines with the ultimate goal of reducing weight, controlling loads, and improving energy capture. While the goal of these innovations is reduction in the COE, there is a potential impact on reliability whenever new technologies are introduced. While some of these innovations may ultimately improve reliability, in the short term, the technology risks and the perception of risk will increase. The COE metric used by researchers to evaluate technologies does not address this issue. This paper outlines the issues relevant to wind turbine reliability for wind turbine power generation projects. The first sections describe the current state of the industry, identify the cost elements associated with wind farm O&M and availability and discuss the causes of uncertainty in estimating wind turbine component reliability. The latter sections discuss the means for reducing O&M costs and propose O&M related research and development efforts that could be pursued by the wind energy research community to reduce COE.

  19. Working Capital for Contractors | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    Financing Peer Exchange Call: Working Capital for Contractors, Call Slides and Discussion Summary, August 30, 2012. PDF icon Call Slides and Discussion Summary More Documents & Publications Streamline Service Delivery via Customer Communication and Contractor Coordination Focus Series: OREGON-On Bill Financing Program: On-Bill Financing Brings Lenders and Homeowners On Board Lessons from On-Bill Financing and Repayment Programs

  20. CE2 Carbon Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Carbon Capital LLC Jump to: navigation, search Name: CE2 Carbon Capital LLC Place: California Sector: Carbon, Renewable Energy Product: US-based carbon trader that looks to take...

  1. Program & Project Management For The Acquisition Of Capital Assets |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy More Documents & Publications Program & Project Management For The Acquisition Of Capital Assets Program & Project Management For The Acquisition Of Capital Assets PARS II Enhancements - Igor Pedan, MA-63

  2. Energy Department and GSA Assist in Capital Solar Challenge Industry...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    and GSA Assist in Capital Solar Challenge Industry Day Energy Department and GSA Assist in Capital Solar Challenge Industry Day October 21, 2014 - 4:43pm Addthis The White House ...

  3. Office of Executive Resources Office of the Chief Human Capital...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Office of Executive Resources Office of the Chief Human Capital Officer U.S. Department of ... and performance awards. c. Chief Human Capital Officer (CHCO) and Office of Executive ...

  4. Marathon Capital LLC (New York) | Open Energy Information

    Open Energy Info (EERE)

    Marathon Capital LLC (New York) Name: Marathon Capital LLC (New York) Address: 245 Park Avenue, 24th Floor Place: New York, New York Zip: 10167 Region: Northeast - NY NJ CT PA Area...

  5. FreshTracks Capital LP | Open Energy Information

    Open Energy Info (EERE)

    FreshTracks Capital LP Jump to: navigation, search Name: FreshTracks Capital LP Address: 29 Harbor Road, Suite 200 Place: Shelburne, New Hampshire Zip: 05482 Product: Venture...

  6. NewWorld Capital Group LLC | Open Energy Information

    Open Energy Info (EERE)

    NewWorld Capital Group LLC Jump to: navigation, search Name: NewWorld Capital Group LLC Place: New York, New York Zip: 10022 Sector: Efficiency Product: New York-based private...

  7. BioLogical Capital BLC | Open Energy Information

    Open Energy Info (EERE)

    BioLogical Capital BLC Jump to: navigation, search Name: BioLogical Capital (BLC) Place: Denver, Colorado Zip: 80202 Product: Denver Colorado-based group focusing on generating...

  8. CO2e Capital Limited | Open Energy Information

    Open Energy Info (EERE)

    e Capital Limited Jump to: navigation, search Name: CO2e Capital Limited Place: New York City, New York Zip: 10022 Product: New York based merchant bank focused on reducing global...

  9. Morgan Stanley Capital Grp Inc | Open Energy Information

    Open Energy Info (EERE)

    Capital Grp Inc Jump to: navigation, search Name: Morgan Stanley Capital Grp Inc Place: New York References: EIA Form EIA-861 Final Data File for 2010 - File1a1 EIA Form 861...

  10. Guide to IT Capital Planning and Investment Control

    Energy Savers [EERE]

    Guide to IT Capital Planning and Investment Control April 2014 i TABLE OF CONTENTS TABLE OF CONTENTS ......

  11. Capitalizing on Multibenefits of Energy Upgrades at Multifamily Housing (301)

    Broader source: Energy.gov [DOE]

    Buildings Residential Network Peer Exchange Call Series: Capitalizing on Multi-benefits of Energy Upgrades at Multifamily Housing (301).

  12. Program and Project Management for the Acquisition of Capital Assets |

    Energy Savers [EERE]

    Department of Energy Program and Project Management for the Acquisition of Capital Assets Program and Project Management for the Acquisition of Capital Assets This Order provides project management direction for the acquisition of capital assets that are delivered on schedule, within budget, and capable of meeting mission performance and environmental safety and health standards. Program and Project Management for the Acquisition of Capital Assets More Documents & Publications Guiding

  13. A Venture Capital Perspective on Technology Transfer and Alternative Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Venture Capital Perspective on Technology Transfer and Alternative Energy Presentation to the State Energy Advisory Board (STEAB) April 9, 2008 2 Private and Confidential Page 2 Discussion Agenda z Venture Capital 101 z Investing in Alternative Energy z Technology Transfer and Venture Capital 3 Private and Confidential Page 3 z Goal: successful sale to public or private investors in 5 to 7 years What Is Venture Capital? z Money provided by investors to high potential private companies - Can be

  14. Hydrogen production and delivery analysis in US markets : cost, energy and greenhouse gas emissions.

    SciTech Connect (OSTI)

    Mintz, M.; Gillette, J.; Elgowainy, A.

    2009-01-01

    Hydrogen production cost conclusions are: (1) Steam Methane Reforming (SMR) is the least-cost production option at current natural gas prices and for initial hydrogen vehicle penetration rates, at high production rates, SMR may not be the least-cost option; (2) Unlike coal and nuclear technologies, the cost of natural gas feedstock is the largest contributor to SMR production cost; (3) Coal- and nuclear-based hydrogen production have significant penalties at small production rates (and benefits at large rates); (4) Nuclear production of hydrogen is likely to have large economies of scale, but because fixed O&M costs are uncertain, the magnitude of these effects may be understated; and (5) Given H2A default assumptions for fuel prices, process efficiencies and labor costs, nuclear-based hydrogen is likely to be more expensive to produce than coal-based hydrogen. Carbon taxes and caps can narrow the gap. Hydrogen delivery cost conclusions are: (1) For smaller urban markets, compressed gas delivery appears most economic, although cost inputs for high-pressure gas trucks are uncertain; (2) For larger urban markets, pipeline delivery is least costly; (3) Distance from hydrogen production plant to city gate may change relative costs (all results shown assume 100 km); (4) Pipeline costs may be reduced with system 'rationalization', primarily reductions in service pipeline mileage; and (5) Liquefier and pipeline capital costs are a hurdle, particularly at small market sizes. Some energy and greenhouse gas Observations: (1) Energy use (per kg of H2) declines slightly with increasing production or delivery rate for most components (unless energy efficiency varies appreciably with scale, e.g., liquefaction); (2) Energy use is a strong function of production technology and delivery mode; (3) GHG emissions reflect the energy efficiency and carbon content of each component in a production-delivery pathway; (4) Coal and natural gas production pathways have high energy consumption and significant GHG emissions (in the absence of carbon caps, taxes or sequestration); (5) Nuclear pathway is most favorable from energy use and GHG emissions perspective; (6) GH2 Truck and Pipeline delivery have much lower energy use and GHG emissions than LH2 Truck delivery; and (7) For LH2 Truck delivery, the liquefier accounts for most of the energy and GHG emissions.

  15. Improving Capital Assets Project Documentation | Department of Energy

    Office of Environmental Management (EM)

    Improving Capital Assets Project Documentation Improving Capital Assets Project Documentation Memorandum from Deputy Secretary Poneman 4-22-2013 PDF icon Improving Capital Asset Project Documentation.pdf More Documents & Publications Smith Electric Vehicles: Advanced Vehicle Electrification + Transportation Sector Electrification Policy Flash 2015-10 - Acquisition Letter Notice 2015-10 Before House Committee on Oversight and Government Reform

  16. An examination of the costs and critical characteristics of electric utility distribution system capacity enhancement projects

    SciTech Connect (OSTI)

    Balducci, Patrick J.; Schienbein, Lawrence A.; Nguyen, Tony B.; Brown, Daryl R.; Fathelrahman, Eihab M.

    2004-06-01

    This report classifies and analyzes the capital and total costs (e.g., income tax, property tax, depreciation, centralized power generation, insurance premiums, and capital financing) associated with 130 electricity distribution system capacity enhancement projects undertaken during 1995-2002 or planned in the 2003-2011 time period by three electric power utilities operating in the Pacific Northwest. The Pacific Northwest National Laboratory (PNNL), in cooperation with participating utilities, has developed a large database of over 3,000 distribution system projects. The database includes brief project descriptions, capital cost estimates, the stated need for each project, and engineering data. The database was augmented by additional technical (e.g., line loss, existing substation capacities, and forecast peak demand for power in the area served by each project), cost (e.g., operations, maintenance, and centralized power generation costs), and financial (e.g., cost of capital, insurance premiums, depreciations, and tax rates) data. Though there are roughly 3,000 projects in the database, the vast majority were not included in this analysis because they either did not clearly enhance capacity or more information was needed, and not available, to adequately conduct the cost analyses. For the 130 projects identified for this analysis, capital cost frequency distributions were constructed, and expressed in terms of dollars per kVA of additional capacity. The capital cost frequency distributions identify how the projects contained within the database are distributed across a broad cost spectrum. Furthermore, the PNNL Energy Cost Analysis Model (ECAM) was used to determine the full costs (e.g., capital, operations and maintenance, property tax, income tax, depreciation, centralized power generation costs, insurance premiums and capital financing) associated with delivering electricity to customers, once again expressed in terms of costs per kVA of additional capacity. The projects were sorted into eight categories (capacitors, load transfer, new feeder, new line, new substation, new transformer, reconductoring, and substation capacity increase) and descriptive statistics (e.g., mean, total cost, number of observations, and standard deviation) were constructed for each project type. Furthermore, statistical analysis has been performed using ordinary least squares regression analysis to identify how various project variables (e.g., project location, the primary customer served by the project, the type of project, the reason for the upgrade, size of the upgrade) impact the unit cost of the project.

  17. Microdrill Initiative - Initial Market Evaluation

    SciTech Connect (OSTI)

    Spears & Associates, Inc

    2003-07-01

    The U.S. Department of Energy (DOE) is launching a major research and development initiative to create a small, fast, inexpensive and environmentally friendly rig for drilling 5000 feet boreholes to investigate potential oil and gas reservoirs. DOE wishes to get input from petroleum industry operators, service companies and equipment suppliers on the operation and application of this coiled-tubing-based drilling unit. To that end, DOE has asked Spears & Associates, Inc. (SAI) to prepare a special state-of-the-market report and assist during a DOE-sponsored project-scoping workshop in Albuquerque near the end of April 2003. The scope of the project is four-fold: (1) Evaluate the history, status and future of demand for very small bore-hole drilling; (2) Measure the market for coiled tubing drilling and describe the state-of-the-art; (3) Identify companies and individuals who should have an interest in micro drilling and invite them to the DOE workshop; and (4) Participate in 3 concurrent workshop sessions, record and evaluate participant comments and report workshop conclusions.

  18. Advanced Fuel Cycle Cost Basis

    SciTech Connect (OSTI)

    D. E. Shropshire; K. A. Williams; W. B. Boore; J. D. Smith; B. W. Dixon; M. Dunzik-Gougar; R. D. Adams; D. Gombert; E. Schneider

    2008-03-01

    This report, commissioned by the U.S. Department of Energy (DOE), provides a comprehensive set of cost data supporting a cost analysis for the relative economic comparison of options for use in the Advanced Fuel Cycle Initiative (AFCI) Program. The report describes the AFCI cost basis development process, reference information on AFCI cost modules, a procedure for estimating fuel cycle costs, economic evaluation guidelines, and a discussion on the integration of cost data into economic computer models. This report contains reference cost data for 25 cost modules—23 fuel cycle cost modules and 2 reactor modules. The cost modules were developed in the areas of natural uranium mining and milling, conversion, enrichment, depleted uranium disposition, fuel fabrication, interim spent fuel storage, reprocessing, waste conditioning, spent nuclear fuel (SNF) packaging, long-term monitored retrievable storage, near surface disposal of low-level waste (LLW), geologic repository and other disposal concepts, and transportation processes for nuclear fuel, LLW, SNF, transuranic, and high-level waste.

  19. Advanced Fuel Cycle Cost Basis

    SciTech Connect (OSTI)

    D. E. Shropshire; K. A. Williams; W. B. Boore; J. D. Smith; B. W. Dixon; M. Dunzik-Gougar; R. D. Adams; D. Gombert

    2007-04-01

    This report, commissioned by the U.S. Department of Energy (DOE), provides a comprehensive set of cost data supporting a cost analysis for the relative economic comparison of options for use in the Advanced Fuel Cycle Initiative (AFCI) Program. The report describes the AFCI cost basis development process, reference information on AFCI cost modules, a procedure for estimating fuel cycle costs, economic evaluation guidelines, and a discussion on the integration of cost data into economic computer models. This report contains reference cost data for 26 cost modules—24 fuel cycle cost modules and 2 reactor modules. The cost modules were developed in the areas of natural uranium mining and milling, conversion, enrichment, depleted uranium disposition, fuel fabrication, interim spent fuel storage, reprocessing, waste conditioning, spent nuclear fuel (SNF) packaging, long-term monitored retrievable storage, near surface disposal of low-level waste (LLW), geologic repository and other disposal concepts, and transportation processes for nuclear fuel, LLW, SNF, and high-level waste.

  20. Advanced Fuel Cycle Cost Basis

    SciTech Connect (OSTI)

    D. E. Shropshire; K. A. Williams; W. B. Boore; J. D. Smith; B. W. Dixon; M. Dunzik-Gougar; R. D. Adams; D. Gombert; E. Schneider

    2009-12-01

    This report, commissioned by the U.S. Department of Energy (DOE), provides a comprehensive set of cost data supporting a cost analysis for the relative economic comparison of options for use in the Advanced Fuel Cycle Initiative (AFCI) Program. The report describes the AFCI cost basis development process, reference information on AFCI cost modules, a procedure for estimating fuel cycle costs, economic evaluation guidelines, and a discussion on the integration of cost data into economic computer models. This report contains reference cost data for 25 cost modules—23 fuel cycle cost modules and 2 reactor modules. The cost modules were developed in the areas of natural uranium mining and milling, conversion, enrichment, depleted uranium disposition, fuel fabrication, interim spent fuel storage, reprocessing, waste conditioning, spent nuclear fuel (SNF) packaging, long-term monitored retrievable storage, near surface disposal of low-level waste (LLW), geologic repository and other disposal concepts, and transportation processes for nuclear fuel, LLW, SNF, transuranic, and high-level waste.

  1. Estimated Cost Description Determination Date:

    Office of Environmental Management (EM)

    Revised and posted 2/10/2011 *Title, Location Estimated Cost Description Determination Date: uncertain Transmittal to State: uncertain EA Approval: uncertain $50,000 FONSI: uncertain Determination Date: uncertain Transmittal to State: uncertain EA Approval: uncertain FONSI: uncertain Total Estimated Cost $70,000 Attachment: Memo, Moody to Marcinowski, III, SUBJECT: NEPA 2011 APS for DOE-SRS, Dated: Annual NEPA Planning Summary Environmental Assessments (EAs) Expected to be Initiated in the Next

  2. Nuclear Energy Research Initiative Project No. 02 103 Innovative Low Cost Approaches to Automating QA/QC of Fuel Particle Production Using On Line Nondestructive Methods for Higher Reliability Final Project Report

    SciTech Connect (OSTI)

    Ahmed, Salahuddin; Batishko, Charles R.; Flake, Matthew; Good, Morris S.; Mathews, Royce; Morra, Marino; Panetta, Paul D.; Pardini, Allan F.; Sandness, Gerald A.; Tucker, Brian J.; Weier, Dennis R.; Hockey, Ronald L.; Gray, Joseph N.; Saurwein, John J.; Bond, Leonard J.; Lowden, Richard A.; Miller, James H.

    2006-02-28

    This Nuclear Energy Research Initiative (NERI) project was tasked with exploring, adapting, developing and demonstrating innovative nondestructive test methods to automate nuclear coated particle fuel inspection so as to provide the United States (US) with necessary improved and economical Quality Assurance and Control (QA/QC) that is needed for the fuels for several reactor concepts being proposed for both near term deployment [DOE NE & NERAC, 2001] and Generation IV nuclear systems. Replacing present day QA/QC methods, done manually and in many cases destructively, with higher speed automated nondestructive methods will make fuel production for advanced reactors economically feasible. For successful deployment of next generation reactors that employ particle fuels, or fuels in the form of pebbles based on particles, extremely large numbers of fuel particles will require inspection at throughput rates that do not significantly impact the proposed manufacturing processes. The focus of the project is nondestructive examination (NDE) technologies that can be automated for production speeds and make either: (I) On Process Measurements or (II) In Line Measurements. The inspection technologies selected will enable particle quality qualification as a particle or group of particles passes a sensor. A multiple attribute dependent signature will be measured and used for qualification or process control decisions. A primary task for achieving this objective is to establish standard signatures for both good/acceptable particles and the most problematic types of defects using several nondestructive methods.

  3. Estimating Specialty Costs

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    Specialty costs are those nonstandard, unusual costs that are not typically estimated. Costs for research and development (R&D) projects involving new technologies, costs associated with future regulations, and specialty equipment costs are examples of specialty costs. This chapter discusses those factors that are significant contributors to project specialty costs and methods of estimating costs for specialty projects.

  4. Clean Energy Manufacturing Initiative | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy Manufacturing Initiative Clean Energy Manufacturing Initiative Clean Energy Manufacturing Initiative Industrial Efficiency and Energy Productivity Video Clean Energy Manufacturing Initiative Industrial Efficiency and Energy Productivity Video Industrial efficiency and low-cost energy resources are key components to increasing U.S. energy productivity and makes the U.S. manufacturing sector more competitive. Companies find a competitive advantage in implementing efficiency technologies and

  5. NPR (New Production Reactor) capacity cost evaluation

    SciTech Connect (OSTI)

    1988-07-01

    The ORNL Cost Evaluation Technical Support Group (CETSG) has been assigned by DOE-HQ Defense Programs (DP) the task defining, obtaining, and evaluating the capital and life-cycle costs for each of the technology/proponent/site/revenue possibilities envisioned for the New Production Reactor (NPR). The first part of this exercise is largely one of accounting, since all NPR proponents use different accounting methodologies in preparing their costs. In order to address this problem of comparing ''apples and oranges,'' the proponent-provided costs must be partitioned into a framework suitable for all proponents and concepts. If this is done, major cost categories can then be compared between concepts and major cost differences identified. Since the technologies proposed for the NPR and its needed fuel and target support facilities vary considerably in level of technical and operational maturity, considerable care must be taken to evaluate the proponent-derived costs in an equitable manner. The use of cost-risk analysis along with derivation of single point or deterministic estimates allows one to take into account these very real differences in technical and operational maturity. Chapter 2 summarizes the results of this study in tabular and bar graph form. The remaining chapters discuss each generic reactor type as follows: Chapter 3, LWR concepts (SWR and WNP-1); Chapter 4, HWR concepts; Chapter 5, HTGR concept; and Chapter 6, LMR concept. Each of these chapters could be a stand-alone report. 39 refs., 36 figs., 115 tabs.

  6. Rough order of magnitude cost estimate for immobilization of 18.2 MT of plutonium using existing facilities at the Savannah River site: alternatives 3A/5A/6A/6B/7A/9A

    SciTech Connect (OSTI)

    DiSabatino, A., LLNL

    1998-06-01

    The purpose of this Cost Estimate Report is to identify preliminary capital and operating costs for a facility to immobilize 18.2 metric tons (nominal) of plutonium using ceramic in a new facility at Savannah River Site (SRS).

  7. Benchmarking for Cost Improvement. Final report

    SciTech Connect (OSTI)

    Not Available

    1993-09-01

    The US Department of Energy`s (DOE) Office of Environmental Restoration and Waste Management (EM) conducted the Benchmarking for Cost Improvement initiative with three objectives: Pilot test benchmarking as an EM cost improvement tool; identify areas for cost improvement and recommend actions to address these areas; provide a framework for future cost improvement. The benchmarking initiative featured the use of four principal methods (program classification, nationwide cost improvement survey, paired cost comparison and component benchmarking). Interested parties contributed during both the design and execution phases. The benchmarking initiative was conducted on an accelerated basis. Of necessity, it considered only a limited set of data that may not be fully representative of the diverse and complex conditions found at the many DOE installations. The initiative generated preliminary data about cost differences and it found a high degree of convergence on several issues. Based on this convergence, the report recommends cost improvement strategies and actions. This report describes the steps taken as part of the benchmarking initiative and discusses the findings and recommended actions for achieving cost improvement. The results and summary recommendations, reported below, are organized by the study objectives.

  8. Program and Project Management for the Acquisition of Capital Assets (Informational Purposes Only)

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2016-01-11

    The purpose of this Order is to a) provide the Department of Energy (DOE) Elements, including the National Nuclear Security Administration (NNSA), with program and project management direction for the acquisition of capital assets with the goal of delivering projects within the original performance baseline (PB), cost and schedule, and fully capable of meeting mission performance, safeguards and security, and environmental, safety, and health requirements unless impacted by a directed change; and b) implement Office of Management and Budget (OMB) Circulars to include: A-11, Part 7, Capital Programming Guide, which prescribes new requirements and leading practices for project and acquisition management; A-123, Management's Responsibility for Internal Control, which defines management's responsibility for internal control in Federal agencies; and A-131, Value Engineering, which requires that all Federal agencies use Value Engineering (VE) as a management tool. The Page Change is a limited update to incorporate recent Secretarial policies and issues raised by external stakeholders.

  9. Instrumented Pipeline Initiative

    SciTech Connect (OSTI)

    Thomas Piro; Michael Ream

    2010-07-31

    This report summarizes technical progress achieved during the cooperative agreement between Concurrent Technologies Corporation (CTC) and U.S. Department of Energy to address the need for a for low-cost monitoring and inspection sensor system as identified in the Department of Energy (DOE) National Gas Infrastructure Research & Development (R&D) Delivery Reliability Program Roadmap.. The Instrumented Pipeline Initiative (IPI) achieved the objective by researching technologies for the monitoring of pipeline delivery integrity, through a ubiquitous network of sensors and controllers to detect and diagnose incipient defects, leaks, and failures. This report is organized by tasks as detailed in the Statement of Project Objectives (SOPO). The sections all state the objective and approach before detailing results of work.

  10. Cost and Performance Assumptions for Modeling Electricity Generation Technologies

    SciTech Connect (OSTI)

    Tidball, R.; Bluestein, J.; Rodriguez, N.; Knoke, S.

    2010-11-01

    The goal of this project was to compare and contrast utility scale power plant characteristics used in data sets that support energy market models. Characteristics include both technology cost and technology performance projections to the year 2050. Cost parameters include installed capital costs and operation and maintenance (O&M) costs. Performance parameters include plant size, heat rate, capacity factor or availability factor, and plant lifetime. Conventional, renewable, and emerging electricity generating technologies were considered. Six data sets, each associated with a different model, were selected. Two of the data sets represent modeled results, not direct model inputs. These two data sets include cost and performance improvements that result from increased deployment as well as resulting capacity factors estimated from particular model runs; other data sets represent model input data. For the technologies contained in each data set, the levelized cost of energy (LCOE) was also evaluated, according to published cost, performance, and fuel assumptions.

  11. Chemical coal cleaning process and costs refinement for coal-water slurry manufacture. Semi-annual progress report

    SciTech Connect (OSTI)

    Bhasin, A.K.; Berggren, M.H.; Smit, F.J.; Ames, L.B.; Ronzio, N.J.

    1985-03-01

    The Department of Energy, through the Morgantown Energy Technology Center (METC), has initiated a program to determine the feasibility and potential applications for direct firing of coal and coal-derived fuels in heat engines, specifically gas turbines and diesel engines. AMAX Extractive Research and Development, Inc. supplied METC with two lots of highly beneficiated coal slurry fuel for use in the Heat Engines programs. One of the lots was of ultra-clean coal-water slurry fuel (UCCSF) for which a two-stage caustic and acid leaching procedure was developed to chemically clean the coal. As a part of the contract, AMAX R and D developed a conceptual design and preliminary cost estimate for a commercial-scale process for UCCSF manufacture. The contract was extended to include the following objectives: define chemical cleaning and slurry preparation process conditions and costs more precisely; investigate methods to reduce the product cost; and determine the relationship, in dollars per million Btu, between product cost and fuel quality. Laboratory investigations have been carried out to define the chemical cleaning process conditions required to generate fuels containing from 0.17 to 1.0% ash. Capital and operating cost refinements are to be performed on the basis of the preferred process operating conditions identified during the laboratory investigations. Several such areas for cost reductions have been identified. Caustic strengths from 2 to 7% NaOH are currently anticipated while 25% NaOH was used as the basis for the preliminary cost estimate. In addition, leaching times for each of the process steps have been reduced to half or less of the times used for the preliminary cost estimate. Improvement of fuel quality has been achieved by use of a proprietary hot-water leaching step to reduce the residual alkali content to less than 250 ppM (Na/sub 2/O plus K/sub 2/O) on a dry coal basis. 2 refs., 3 figs., 24 tabs.

  12. Evaluation of the Total Cost of Ownership of Fuel Cell-Powered Material Handling Equipment

    SciTech Connect (OSTI)

    Ramsden, T.

    2013-04-01

    This report discusses an analysis of the total cost of ownership of fuel cell-powered and traditional battery-powered material handling equipment (MHE, or more typically 'forklifts'). A number of fuel cell MHE deployments have received funding support from the federal government. Using data from these government co-funded deployments, DOE's National Renewable Energy Laboratory (NREL) has been evaluating the performance of fuel cells in material handling applications. NREL has assessed the total cost of ownership of fuel cell MHE and compared it to the cost of ownership of traditional battery-powered MHE. As part of its cost of ownership assessment, NREL looked at a range of costs associated with MHE operation, including the capital costs of battery and fuel cell systems, the cost of supporting infrastructure, maintenance costs, warehouse space costs, and labor costs. Considering all these costs, NREL found that fuel cell MHE can have a lower overall cost of ownership than comparable battery-powered MHE.

  13. Capital requirements and fuel-cycle energy and emissions impacts of potential PNGV fuels.

    SciTech Connect (OSTI)

    Johnson, L.; Mintz, M.; Singh, M.; Stork, K.; Vyas, A.; Wang, M.

    1999-03-11

    Our study reveals that supplying gasoline-equivalent demand for the low-market-share scenario requires a capital investment of less than $40 billion for all fuels except H{sub 2}, which will require a total cumulative investment of $150 billion. By contrast, cumulative capital investments under the high-market-share scenario are $50 billion for LNG, $90 billion for ethanol, $100 billion for methanol, $160 billion for CNG and DME, and $560 billion for H{sub 2}. Although these substantial capital requirements are spread over many years, their magnitude could pose a challenge to the widespread introduction of 3X vehicles. Fossil fuel use by US light-duty vehicles declines significantly with introduction of 3X vehicles because of fuel-efficiency improvements for 3X vehicles and because of fuel substitution (which applies to the nonpetroleum-fueled alternatives). Petroleum use for light-duty vehicles in 2030 is reduced by as much as 45% relative to the reference scenario. GHG emissions follow a similar pattern. Total GHG emissions decline by 25-30% with most of the propulsion system/fuel alternatives. For those using renewable fuels (i.e., ethanol and H{sub 2} from solar energy), GHG emissions drop by 33% (H{sub 2}) and 45% (ethanol). Among urban air pollutants, urban NOX emissions decline slightly for 3X vehicles using CIDI and SIDI engines and drop substantially for fuel-cell vehicles. Urban CO emissions decline for CIDI and FCV alternatives, while VOC emissions drop significantly for all alternatives except RFG-, methanol-, and ethanol-fueled SIDI engines. With the exception of CIDI engines fueled by RFD, FT50, or B20 (which increase urban PM{sub 10} emissions by over 30%), all propulsion system/fuel alternatives reduce urban PM{sub 10} emissions. Reductions are approximately 15-20% for fuel cells and for methanol-, ethanol-, CNG-, or LPG-fueled SIDI engines. Table 3 qualitatively summarizes impacts of the 13 alternatives on capital requirements and on energy use and emissions relative to the reference scenario. The table clearly shows the trade-off between costs and benefits. For example, while H{sub 2} FCVs have the greatest incremental capital needs, they offer the largest energy and emissions benefits. On the basis of the cost and benefit changes shown, methanol and gasoline FCVs appear to have particularly promising benefits-to-costs ratios.

  14. Retrofit costs for lime/limestone FGD and lime spray drying at coal-fired utility boilers

    SciTech Connect (OSTI)

    Emmel, T.E.; Jones, J.W.

    1990-01-01

    The paper gives results of a research program the objective of which was to significantly improve engineering cost estimates currently being used to evaluate the economic effects of applying SO2 controls to existing coal-fired utility boilers. The costs of retrofitting conventional lime/limestone wet flue gas desulfurization (L/LS FGD) and lime spray drying (LSD) FGD at 100-200 coal-fired power plants are being estimated under this program. The retrofit capital cost estimating procedures used for L/LS FGD and LSD FGD make two cost adjustments to current procedures used to estimate FGD costs: cost adders (for items not normally included in FGD system costs; e.g., demolition and relocation of existing facilities) and cost multipliers (to adjust capital costs for site access, congestion, and underground obstructions).

  15. Maryland-National Capital Building Industry Association Regulatory Burden

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    RFI (Federal Register August 8, 2012) | Department of Energy Maryland-National Capital Building Industry Association Regulatory Burden RFI (Federal Register August 8, 2012) Maryland-National Capital Building Industry Association Regulatory Burden RFI (Federal Register August 8, 2012) On behalf of the Maryland-National Capital Building Industry Association, I am providing the following comments and information in response to DOE's request. The Association represents residential builders,

  16. Office of the Chief Human Capital Officer | Department of Energy

    Broader source: All U.S. Department of Energy (DOE) Office Webpages

    Human Capital Officer Search Search form Search Office of the Chief Human Capital Officer Office of the Chief Human Capital Officer Services Services Home Benefits Benefits Home DOE Workers' Compensation Program Insurance Military/Reservist Retirement Telework Thrift Savings Plan (TSP) Wellness Programs Executive Resources Learning and Workforce Development New Employee Orientation Policy and Guidance Policy and Guidance Home Compensation Employment/Staffing Employment/Staffing Home Recruitment

  17. Program and Project Management for the Acquisition of Capital...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    3.3B, Program and Project Management for the Acquisition of Capital Assets by Jay Glascock Functional areas: Acquisition, Defense Nuclear Facility Safety and Health Requirement,...

  18. Webinar Announcement: Accessing Private Capital for Clean Energy...

    Open Energy Info (EERE)

    Webinar Announcement: Accessing Private Capital for Clean Energy Investments in Developing Countries (Webinar) Home > Groups > OpenEI Community Central Graham7781's picture...

  19. Former SULI student participates in Research in the Capital ...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Former SULI student participates in Research in the Capital With research on sciatic nerve regeneration, the implications of marginal tax rates on housing prices, honey bee...

  20. Delegation of Acquisition Executive Authority for Capital Asset...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Idaho Cleanup Project by cooper DelegationAcquisitionExecAuthorityCapitalAssetProjectsIDCleanupProject-CooperEM.pdf -- PDF Document, 256 KB ID: NA Type: Organizations' Assignment...

  1. Global Capital Finance Americas LLC | Open Energy Information

    Open Energy Info (EERE)

    Finance Americas LLC Jump to: navigation, search Name: Global Capital Finance Americas LLC Place: Purchase, New York Zip: 10577 Sector: Renewable Energy, Services Product: An...

  2. Hanford tanks initiative (HTI) work breakdown structure (WBS)dictionary

    SciTech Connect (OSTI)

    Mckinney, K.E.

    1997-03-31

    This dictionary lists the scope, deliverables, and interfaces for the various work elements of the Hanford Tanks Initiative. Cost detail is included for information only.

  3. OSIRIS and the Collaborative Modeling Initiative on REDD Economics...

    Open Energy Info (EERE)

    RelatedTo: Open Source Impacts of REDD Incentives Spreadsheet (OSIRIS) Cost: Free Language: English OSIRIS and the Collaborative Modeling Initiative on REDD Economics...

  4. Analysis of Cycling Costs in Western Wind and Solar Integration Study

    SciTech Connect (OSTI)

    Jordan, G.; Venkataraman, S.

    2012-06-01

    The Western Wind and Solar Integration Study (WWSIS) examined the impact of up to 30% penetration of variable renewable generation on the Western Electricity Coordinating Council system. Although start-up costs and higher operating costs because of part-load operation of thermal generators were included in the analysis, further investigation of additional costs associated with thermal unit cycling was deemed worthwhile. These additional cycling costs can be attributed to increases in capital as well as operations and maintenance costs because of wear and tear associated with increased unit cycling. This analysis examines the additional cycling costs of the thermal fleet by leveraging the results of WWSIS Phase 1 study.

  5. Cost reduction ideas for LNG terminals

    SciTech Connect (OSTI)

    Habibullah, A.; Weldin, F.

    1999-07-01

    LNG projects are highly capital intensive and this has long been regarded as being inevitable. However, recent developments are forcing the LNG industry to aggressively seek cost reductions. For example, the gas-to-liquids (GTL) process is increasingly seen as a potential rival technology and is often being touted as an economically superior alternative fuel source. Another strong driving force behind needed cost reductions is the low crude oil price which seems to have settled in the $10--13/bb. range. LNG is well positioned as the fuel of choice for environmentally friendly new power projects. As a result of the projected demand for power especially in the Pacific Rim countries several LNG terminal projects are under consideration. Such projects will require a new generation of LNG terminal designs emphasizing low cost, small scale and safe and fully integrated designs from LNG supply to power generation. The integration of the LNG terminal with the combined cycle gas turbine (CCGT) power plant offers substantial cost savings opportunities for both plants. Various cost reduction strategies and their impact on the terminal design are discussed including cost reduction due to integration.

  6. Cost Model and Cost Estimating Software

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    This chapter discusses a formalized methodology is basically a cost model, which forms the basis for estimating software.

  7. Oak Ridge National Laboratory Next-Generation Safeguards Initiative: Human Capital Development

    SciTech Connect (OSTI)

    Gilligan, Kimberly

    2014-01-01

    In 2007, the US Department of Energy National Nuclear Security Administration (DOE/NNSA) Office of Nonproliferation and International Security (NA-24) completed a comprehensive review of the current and potential future challenges facing the international safeguards system. The review examined: trends and events that have an effect on the mission of international safeguards; the implications of expanding and evolving mission requirements of the legal authorities and institutions that serve as the foundation of the international safeguards system; and, the technological, financial, and human resources required for effective safeguards implementation. The review’s findings and recommendations were summarized in the report International Safeguards: Challenges and Opportunities for the 21st Century (October 2007). The executive summary is available at the following link: http://nnsa.energy.gov/sites/default/files/nnsa/inlinefiles/NGSI_Report.pdf.

  8. Meeting the Human Capital Management Challenge

    Office of Environmental Management (EM)

    A A M M A A N N A A G G E E R R ' ' S S D D E E S S K K R R E E F F E E R R E E N N C C E E O O N N H H U U M M A A N N C C A A P P I I T T A A L L M M A A N N A A G G E E M M E E N N T T F F L L E E X X I I B B I I L L I I T T I I E E S S © Microsoft Office Online ClipArt October 2010 Office of the Chief Human Capital Officer 2 Table of Contents INTRODUCTION --------------------------------------------------------------------------------------- 3 RECRUITMENT INCENTIVE

  9. Incorporating psychological influences in probabilistic cost analysis

    SciTech Connect (OSTI)

    Kujawski, Edouard; Alvaro, Mariana; Edwards, William

    2004-01-08

    Today's typical probabilistic cost analysis assumes an ''ideal'' project that is devoid of the human and organizational considerations that heavily influence the success and cost of real-world projects. In the real world ''Money Allocated Is Money Spent'' (MAIMS principle); cost underruns are rarely available to protect against cost overruns while task overruns are passed on to the total project cost. Realistic cost estimates therefore require a modified probabilistic cost analysis that simultaneously models the cost management strategy including budget allocation. Psychological influences such as overconfidence in assessing uncertainties and dependencies among cost elements and risks are other important considerations that are generally not addressed. It should then be no surprise that actual project costs often exceed the initial estimates and are delivered late and/or with a reduced scope. This paper presents a practical probabilistic cost analysis model that incorporates recent findings in human behavior and judgment under uncertainty, dependencies among cost elements, the MAIMS principle, and project management practices. Uncertain cost elements are elicited from experts using the direct fractile assessment method and fitted with three-parameter Weibull distributions. The full correlation matrix is specified in terms of two parameters that characterize correlations among cost elements in the same and in different subsystems. The analysis is readily implemented using standard Monte Carlo simulation tools such as {at}Risk and Crystal Ball{reg_sign}. The analysis of a representative design and engineering project substantiates that today's typical probabilistic cost analysis is likely to severely underestimate project cost for probability of success values of importance to contractors and procuring activities. The proposed approach provides a framework for developing a viable cost management strategy for allocating baseline budgets and contingencies. Given the scope and magnitude of the cost-overrun problem, the benefits are likely to be significant.

  10. EA-185-A Morgan Stanley Capital Group Inc. | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    -A Morgan Stanley Capital Group Inc. EA-185-A Morgan Stanley Capital Group Inc. Order authorizing Morgan Stanley Capital Group Inc. to export electric energy to Canada. PDF icon ...

  11. EA-184-A Morgan Stanley Capital Group Inc. | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    4-A Morgan Stanley Capital Group Inc. EA-184-A Morgan Stanley Capital Group Inc. Order authorizing Morgan Stanley Capital Group Inc. to export electric energy to Mexico. PDF icon ...

  12. EA-185-C Morgan Stanley Capital Group Inc. | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    C Morgan Stanley Capital Group Inc. EA-185-C Morgan Stanley Capital Group Inc. Order authorizing Morgan Stanley Capital Group Inc. to export electric energy to Canada. PDF icon ...

  13. EA-260-A EPCOR Merchant and Capital (US) Inc | Department of...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    -A EPCOR Merchant and Capital (US) Inc EA-260-A EPCOR Merchant and Capital (US) Inc Order authorizing EPCOR Merchant and Capital (US) Inc to export electric energy to Canada. PDF ...

  14. EA-185-D Morgan Stanley Capital Group Inc. | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    D Morgan Stanley Capital Group Inc. EA-185-D Morgan Stanley Capital Group Inc. Order authorizing MSCG to export electric energy to Canada. PDF icon EA-185-D Morgan Stanley Capital ...

  15. EA-260 EPCOR Merchant and Capital (US) Inc | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    EPCOR Merchant and Capital (US) Inc EA-260 EPCOR Merchant and Capital (US) Inc Order authorizing EPCOR Merchant and Capital (US) Inc to export electric energy to Canada. PDF icon ...

  16. EA-185-B Morgan Stanley Capital Group Inc. | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    B Morgan Stanley Capital Group Inc. EA-185-B Morgan Stanley Capital Group Inc. Order authorizing Morgan Stanley Capital Group Inc. to export electric energy to Canada. PDF icon ...

  17. DOE Guide to IT Capital Planning and Investment Control BY 2016...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Guide to IT Capital Planning and Investment Control BY 2016 DOE Guide to IT Capital Planning and Investment Control BY 2016 DOE Guide to IT Capital Planning and Investment Control...

  18. Cost and code study of underground buildings

    SciTech Connect (OSTI)

    Sterling, R.L.

    1981-01-01

    Various regulatory and financial implications for earth-sheltered houses and buildings are discussed. Earth-sheltered houses are covered in the most detail including discussions of building-code restrictions, HUD Minimum Property Standards, legal aspects, zoning restrictions, taxation, insurance, and home financing. Examples of the initial-cost elements in earth-sheltered houses together with projected life-cycle costs are given and compared to more-conventional energy-conserving houses. For larger-scale underground buildings, further information is given on building code, fire protection, and insurance provisions. Initial-cost information for five large underground buildings is presented together with energy-use information where available.

  19. Activity Based Costing

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    Activity Based Costing (ABC) is method for developing cost estimates in which the project is subdivided into discrete, quantifiable activities or a work unit. This chapter outlines the Activity Based Costing method and discusses applicable uses of ABC.

  20. DOE Strategic Human Capital Plan (FY 2011 - 2015) | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Strategic Human Capital Plan (FY 2011 - 2015) DOE Strategic Human Capital Plan (FY 2011 - 2015) The Strategic Human Capital Plan sets forth the framework for managing the Department of Energy's (DOE) human capital system through 2015. This Plan, which supersedes the 2006 Strategic Human Capital Management Plan and the 2008 Strategic Human Capital Management Addendum, aligns with the following priority of the Management Excellence Agenda from the DOE Strategic Plan and the DOE Operations

  1. EA-260-C EPCOR Merchant and Capital (US) Inc | Department of Energy

    Office of Environmental Management (EM)

    60-C EPCOR Merchant and Capital (US) Inc EA-260-C EPCOR Merchant and Capital (US) Inc Order authorizing EPCOR Merchant and Capital (US) Inc to export electric energy to Canada. PDF icon EA-260-C EPCOR Merchant and Capital (US) Inc More Documents & Publications EA-260-A EPCOR Merchant and Capital (US) Inc EA-260 EPCOR Merchant and Capital (US) Inc Application to export electric energy OE Docket No. EA-260-C EPCOR Energy Marketing (U.S) Inc

  2. Land-Based Wind Plant Balance-of-System Cost Drivers and Sensitivities (Poster)

    SciTech Connect (OSTI)

    Mone, C.; Maples, B.; Hand, M.

    2014-04-01

    With Balance of System (BOS) costs contributing up to 30% of the installed capital cost, it is fundamental to understand the BOS costs for wind projects as well as potential cost trends for larger turbines. NREL developed a BOS model using project cost estimates developed by industry partners. Aspects of BOS covered include engineering and permitting, foundations for various wind turbines, transportation, civil work, and electrical arrays. The data introduce new scaling relationships for each BOS component to estimate cost as a function of turbine parameters and size, project parameters and size, and geographic characteristics. Based on the new BOS model, an analysis to understand the non?turbine wind plant costs associated with turbine sizes ranging from 1-6 MW and wind plant sizes ranging from 100-1000 MW has been conducted. This analysis establishes a more robust baseline cost estimate, identifies the largest cost components of wind project BOS, and explores the sensitivity of the capital investment cost and the levelized cost of energy to permutations in each BOS cost element. This presentation shows results from the model that illustrate the potential impact of turbine size and project size on the cost of energy from US wind plants.

  3. Hydrogen Threshold Cost Calculation

    Broader source: Energy.gov [DOE]

    DOE Hydrogen Program Record number11007, Hydrogen Threshold Cost Calculation, documents the methodology and assumptions used to calculate that threshold cost.

  4. Hydrogen Threshold Cost Calculation

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    record documents the methodology and assumptions used to calculate that threshold cost. ... Calculation Methodology and Results: The consumer's cost per mile for the FCEV is set to ...

  5. U.S. Department of Energy Selects Venture Capital Firms to Accelerate...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Venture Capital Firms to Accelerate Adoption of Advanced Energy Technologies U.S. Department of Energy Selects Venture Capital Firms to Accelerate Adoption of Advanced Energy ...

  6. MicroPlanet Technology Corp formerly HF Capital Corp | Open Energy...

    Open Energy Info (EERE)

    Technology Corp formerly HF Capital Corp Jump to: navigation, search Name: MicroPlanet Technology Corp (formerly HF Capital Corp) Place: Seattle, Washington Zip: 98104 Sector:...

  7. Integration of Variable Generation and Cost-Causation (Fact Sheet)

    SciTech Connect (OSTI)

    Not Available

    2012-09-01

    Variable renewable energy generation sources, such as wind and solar energy, provide benefits such as reduced environmental impact, zero fuel consumption, and low and stable costs. Advances in both technologies can reduce capital costs and provide significant control capabilities. However, their variability and uncertainty - which change with weather conditions, time of day, and season - can cause an increase in power system operating costs compared to a fully controllable power plant. Although a number of studies have assessed integration costs, calculating them correctly is challenging because it is difficult to accurately develop a baseline scenario without variable generation that properly accounts for the energy value. It is also difficult to appropriately allocate costs given the complex, nonlinear interactions between resources and loads.

  8. Cost estimate for muddy water palladium production facility at Mound

    SciTech Connect (OSTI)

    McAdams, R.K.

    1988-11-30

    An economic feasibility study was performed on the ''Muddy Water'' low-chlorine content palladium powder production process developed by Mound. The total capital investment and total operating costs (dollars per gram) were determined for production batch sizes of 1--10 kg in 1-kg increments. The report includes a brief description of the Muddy Water process, the process flow diagram, and material balances for the various production batch sizes. Two types of facilities were evaluated--one for production of new, ''virgin'' palladium powder, and one for recycling existing material. The total capital investment for virgin facilities ranged from $600,000 --$1.3 million for production batch sizes of 1--10 kg, respectively. The range for recycle facilities was $1--$2.3 million. The total operating cost for 100% acceptable powder production in the virgin facilities ranged from $23 per gram for a 1-kg production batch size to $8 per gram for a 10-kg batch size. Similarly for recycle facilities, the total operating cost ranged from $34 per gram to $5 per gram. The total operating cost versus product acceptability (ranging from 50%--100% acceptability) was also evaluated for both virgin and recycle facilities. Because production sizes studied vary widely and because scale-up factors are unknown for batch sizes greater than 1 kg, all costs are ''order-of-magnitude'' estimates. All costs reported are in 1987 dollars.

  9. Geothermal Heat Pumps as a Cost Saving and Capital Renewal Too!

    SciTech Connect (OSTI)

    Hughes, P.J.

    1998-11-06

    An independent evaluation of the Fort Polk, Louisiana energy savings performance contract (ESPC) has verified the financial value of geothermal heat pump (GHP)-centered ESPCS to the federal government. The Department of Energy (DOE) Federal Energy Management Program (FEMP) has responded by issuing an RFP for the "National GHP-Technology-Specific Super ESPC Procurement." Federal agency sites anywhere in the nation will be able to implement GHP-centered ESPC projects as delivery orders against the awarded contracts.

  10. Wind Turbine Control Design to Reduce Capital Costs: 7 January 2009 - 31 August 2009

    SciTech Connect (OSTI)

    Darrow, P. J.

    2010-01-01

    This report first discusses and identifies which wind turbine components can benefit from advanced control algorithms and also presents results from a preliminary loads case analysis using a baseline controller. Next, it describes the design, implementation, and simulation-based testing of an advanced controller to reduce loads on those components. The case-by-case loads analysis and advanced controller design will help guide future control research.

  11. Florida Hydrogen Initiative

    SciTech Connect (OSTI)

    Block, David L

    2013-06-30

    The Florida Hydrogen Initiative (FHI) was a research, development and demonstration hydrogen and fuel cell program. The FHI program objectives were to develop Florida?s hydrogen and fuel cell infrastructure and to assist DOE in its hydrogen and fuel cell activities The FHI program funded 12 RD&D projects as follows: Hydrogen Refueling Infrastructure and Rental Car Strategies -- L. Lines, Rollins College This project analyzes strategies for Florida's early stage adaptation of hydrogen-powered public transportation. In particular, the report investigates urban and statewide network of refueling stations and the feasibility of establishing a hydrogen rental-car fleet based in Orlando. Methanol Fuel Cell Vehicle Charging Station at Florida Atlantic University ? M. Fuchs, EnerFuel, Inc. The project objectives were to design, and demonstrate a 10 kWnet proton exchange membrane fuel cell stationary power plant operating on methanol, to achieve an electrical energy efficiency of 32% and to demonstrate transient response time of less than 3 milliseconds. Assessment of Public Understanding of the Hydrogen Economy Through Science Center Exhibits, J. Newman, Orlando Science Center The project objective was to design and build an interactive Science Center exhibit called: ?H2Now: the Great Hydrogen Xchange?. On-site Reformation of Diesel Fuel for Hydrogen Fueling Station Applications ? A. Raissi, Florida Solar Energy Center This project developed an on-demand forecourt hydrogen production technology by catalytically converting high-sulfur hydrocarbon fuels to an essentially sulfur-free gas. The removal of sulfur from reformate is critical since most catalysts used for the steam reformation have limited sulfur tolerance. Chemochromic Hydrogen Leak Detectors for Safety Monitoring ? N. Mohajeri and N. Muradov, Florida Solar Energy Center This project developed and demonstrated a cost-effective and highly selective chemochromic (visual) hydrogen leak detector for safety monitoring at any facility engaged in transport, handling and use of hydrogen. Development of High Efficiency Low Cost Electrocatalysts for Hydrogen Production and PEM Fuel Cell Applications ? M. Rodgers, Florida Solar Energy Center The objective of this project was to decrease platinum usage in fuel cells by conducting experiments to improve catalyst activity while lowering platinum loading through pulse electrodeposition. Optimum values of several variables during electrodeposition were selected to achieve the highest electrode performance, which was related to catalyst morphology. Understanding Mechanical and Chemical Durability of Fuel Cell Membrane Electrode Assemblies ? D. Slattery, Florida Solar Energy Center The objective of this project was to increase the knowledge base of the degradation mechanisms for membranes used in proton exchange membrane fuel cells. The results show the addition of ceria (cerium oxide) has given durability improvements by reducing fluoride emissions by an order of magnitude during an accelerated durability test. Production of Low-Cost Hydrogen from Biowaste (HyBrTec?) ? R. Parker, SRT Group, Inc., Miami, FL This project developed a hydrogen bromide (HyBrTec?) process which produces hydrogen bromide from wet-cellulosic waste and co-produces carbon dioxide. Eelectrolysis dissociates hydrogen bromide producing recyclable bromine and hydrogen. A demonstration reactor and electrolysis vessel was designed, built and operated. Development of a Low-Cost and High-Efficiency 500 W Portable PEMFC System ? J. Zheng, Florida State University, H. Chen, Bing Energy, Inc. The objectives of this project were to develop a new catalyst structures comprised of highly conductive buckypaper and Pt catalyst nanoparticles coated on its surface and to demonstrate fuel cell efficiency improvement and durability and cell cost reductions in the buckypaper based electrodes. Development of an Interdisciplinary Hydrogen and Fuel Cell Technology Academic Program ? J. Politano, Florida Institute of Technology, Melbourne, FL This project developed a hydrogen and fuel cell technology academic program at Florida Institute of Technology in Melbourne, Florida. Design and Development of an Advanced Hydrogen Storage System using Novel Materials ? E. Stefanakos, University of South Florida The goal of this project was to design and develop novel conducting polymeric nanomaterials for on-board hydrogen storage. The project approach was to examine synthesis of polyaniline solid state hydrogen storage materials. Advanced HiFoil ? Bipolar Plates ? J. Braun, M. Fuchs, EnerFuel, Inc. The goal of this project was to provide a durable, low cost bipolar plate for high temperature proton exchange membrane fuel cells. The project results produced a durable, low cost bipolar plate with very high in-plane thermal conductivity.

  12. 2007 Wholesale Power Rate Case Initial Proposal : Revenue Requirement Study.

    SciTech Connect (OSTI)

    United States. Bonneville Power Administration.

    2005-11-01

    The purpose of this Study is to establish the level of revenues from wholesale power rates necessary to recover, in accordance with sound business principles, the Federal Columbia River Power System (FCRPS) costs associated with the production, acquisition, marketing, and conservation of electric power. The generation revenue requirement includes: recovery of the Federal investment in hydro generation, fish and wildlife and conservation costs; Federal agencies' operations and maintenance (O&M) expenses allocated to power; capitalized contract expenses associated with non-Federal power suppliers such as Energy Northwest (EN); other power purchase expenses, such as short-term power purchases; power marketing expenses; cost of transmission services necessary for the sale and delivery of FCRPS power; and all other generation-related costs incurred by the Administrator pursuant to law.

  13. WCI - World Consensus Initiative

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    World Consensus Initiative 2005 Workshop Recap WCI 2004 Website WCI Book Contributed Papers

  14. A chronicle of costs

    SciTech Connect (OSTI)

    Elioff, T.

    1994-04-01

    This report contains the history of all estimated costs associated with the superconducting super collider.

  15. Cost Estimation Package

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    This chapter focuses on the components (or elements) of the cost estimation package and their documentation.

  16. Life Cycle Cost Estimate

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    Life-cycle costs (LCCs) are all the anticipated costs associated with a project or program alternative throughout its life. This includes costs from pre-operations through operations or to the end of the alternative.This chapter discusses life cycle costs and the role they play in planning.

  17. SunShot Initiative | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    SunShot Initiative Technology to Market Awards Announced Technology to Market Awards Announced The Energy Department today announced $22.7 million for 23 projects that will significantly reduce the costs for solar energy systems across a variety of technologies. The new projects will promote the next generation of products, services, and manufacturing processes to help accelerate the deployment and reduce the cost of solar energy across the United States. Read more National Community Solar

  18. INDEPENDENT COST REVIEW (ICR) and INDEPENDENT COST ESTIMATE ...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    INDEPENDENT COST REVIEW (ICR) and INDEPENDENT COST ESTIMATE (ICE) Standard Operating Procedures INDEPENDENT COST REVIEW (ICR) and INDEPENDENT COST ESTIMATE (ICE) Standard Operating...

  19. Life cycle cost study for coated conductor manufacture by metal organic chemical vapor deposition

    SciTech Connect (OSTI)

    Chapman, J.N.

    1999-07-13

    The purpose of this report is to calculate the cost of producing high temperature superconducting wire by the Metal Organic Chemical Vapor Deposition (MOCVD) process. The technology status is reviewed from the literature and a plant conceptual design is assumed for the cost calculation. The critical issues discussed are the high cost of the metal organic precursors, the material utilization efficiency and the capability of the final product as measured by the critical current density achieved. Capital, operating and material costs are estimated and summed as the basis for calculating the cost per unit length of wire. Sensitivity analyses of key assumptions are examined to determine their effects on the final wire cost. Additionally, the cost of wire on the basis of cost per kiloampere per meter is calculated for operation at lower temperatures than the liquid nitrogen boiling temperature. It is concluded that this process should not be ruled out on the basis of high cost of precursors alone.

  20. Women in engineering conference: capitalizing on today`s challenges

    SciTech Connect (OSTI)

    Metz, S.S.; Martins, S.M.

    1996-06-01

    This document contains the conference proceedings of the Women in Engineering Conference: Capitalizing on Today`s Challenges, held June 1-4, 1996 in Denver, Colorado. Topics included engineering and science education, career paths, workplace issues, and affirmative action.

  1. ErgyCapital Beghelli JV | Open Energy Information

    Open Energy Info (EERE)

    & Beghelli JV Place: Italy Product: Italy-based JV, formed to design and install photovoltaic systems. References: ErgyCapital & Beghelli JV1 This article is a stub. You can...

  2. Three State Capitals to Receive Green Design Assistance from EPA

    Broader source: Energy.gov [DOE]

    The U.S. Environmental Protection Agency (EPA) on January 9 announced urban planning design assistance to help the capital cities of Michigan, Washington, and Wisconsin develop greener designs, including the use of renewable energy technologies.

  3. Project Management for the Acquisition of Capital Assets

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2003-03-28

    The purpose of this Manual is to provide requirements and guidance to Department of Energy (DOE) employees, including National Nuclear Security Administration (NNSA) employees on the planning and acquisition of capital assets. Does not cancel other directives.

  4. Program and Project Management for the Acquisition of Capital...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    13.B, Chg 1 (PgChg), Program and Project Management for the Acquisition of Capital Assets by Jay Glascock Functional areas: Acquisition, Defense Nuclear Facility Safety and Health...

  5. Delegation of Acquisition Executive Authority for Capital Asset...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    the Oak Ridge Office by whitney Delegation-AcquisitionExecAuthorityforCapitalAsset Projects-OR-WhitneyEM.pdf -- PDF Document, 627 KB ID: NA Type: Organizations' Assignment of...

  6. Program and Project Management for the Acquisition of Capital...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    ARCHIVED DOE O 413.3A Chg 1, Program and Project Management for the Acquisition of Capital Assets by John Makepeace Functional areas: Acquisition, Defense Nuclear Facility Safety...

  7. Delegation of Acquisition Executive Authority for Capital Asset...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Related to: DOE O 413.3B, Program and Project Management for the Acquisition of Capital Assets There is no history to display for this document. Document Actions Print this...

  8. Tribal Renewable Energy Webinar: Accessing Capital for Tribal Energy and

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Economic Development | Department of Energy Accessing Capital for Tribal Energy and Economic Development Tribal Renewable Energy Webinar: Accessing Capital for Tribal Energy and Economic Development October 26, 2016 11:00AM to 12:30PM MDT Understand available financing mechanisms that can be used to make energy efficiency and renewable energy projects economically feasible, including utility community solar models, third-party vendors, green bonds, energy savings performance contracts, and

  9. Low Capital Photovoltaic Panel Electrical Output-Booster System |

    Office of Environmental Management (EM)

    Department of Energy Low Capital Photovoltaic Panel Electrical Output-Booster System Low Capital Photovoltaic Panel Electrical Output-Booster System This presentation summarizes the information given during the DOE SunShot Grand Challenge: Summit and Technology Forum, June 13-14, 2012. PDF icon ssgrandchallenge_finance_schrag.pdf More Documents & Publications The SunShot Vision Study SunShot Vision Study: February 2012 (Book), SunShot, Energy Efficiency & Renewable Energy (EERE) 2014

  10. Office of the Chief Human Capital Officer | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Office of the Chief Human Capital Officer Office of the Chief Human Capital Officer Most Requested Open Season 2015 Career Development Programs CHRIS (DOE Only) DOE & Headquarters Awards DOE Info (DOE Only) DOE Jobs Employee Viewpoint Survey Entry-Level/Student Jobs ESS Grade & Pay Retention HC Strategic Plan Mentoring Program Military and Reservist Online Learning Center Policy Guidance Memorandum Retirement Recruitment Policies and Sources SEET Telework Voluntary Leave Transfer

  11. commercial buildings initiative | netl.doe.gov

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Commercial Buildings Initiative The DOE Building Technologies Office works with the commercial building industry to accelerate the use of energy efficiency technologies in both existing and new commercial buildings. The DOE Building Technologies Office strives to reduce energy consumption across the commercial building sector by developing, demonstrating and deploying cost-effective solutions. Commercial Buildings Initiative: http://www1.eere.energy.gov/buildings/commercial/index.html

  12. Keck Futures Initiative

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    National Academies Keck Futures Initiative Complex Systems Conference, November 12 - 15, 2008 Challa Kumar(second from left) was invited to attend 1st National Academies Keck Futures Initiative Complex Systems Conference

  13. Ohio Fuel Cell Initiative

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Top 5 Fuel Cell States: Why Local Policies Mean Green Growth Jun 21 st , 2011 2 * Ohio Fuel Cell Initiative * Ohio Fuel Cell Coalition * Accomplishments * Ohio Successes Discussion Areas 3 Ohio's Fuel Cell Initiative * Announced on 5/9/02 * Part of Ohio Third Frontier Initiative * $85 million investment to date * Core focus areas: 1) Expand the state's research capabilities; 2) Participate in demonstration projects; and 3) Expand the fuel cell industry in Ohio 4 OHIO'S FUEL CELL INITIATIVE

  14. Wind Integration Initiatives

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Expand Projects & Initiatives Finance & Rates Expand Finance & Rates Involvement & Outreach Expand Involvement & Outreach Doing Business Expand Doing Business...

  15. APEC Smart Grid Initiative

    SciTech Connect (OSTI)

    Bloyd, Cary N.

    2012-03-01

    This brief paper describes the activities of the Asia Pacific Economic Cooperation (APEC) Smart Grid Initiative (ASGI) which is being led by the U.S. and developed by the APEC Energy Working Group. In the paper, I describe the origin of the initiative and briefly mention the four major elements of the initiative along with existing APEC projects which support it.

  16. Carbon Capture Simulation Initiative

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Capture Simulation Initiative Fact sheet More Information Research Team Members Key Contacts Carbon Capture Simulation Initiative The Carbon Capture Simulation Initiative (CCSI) is a partnership among national laboratories, industry, and academic institutions that is developing, demonstrating and deploying state-of-the-art computational modeling and simulation tools to accelerate the development of carbon capture technologies from discovery to development, demonstration, and ultimately the

  17. Application to Export Electric Energy OE Docket No. EA-355 Scotia Capital

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy | Department of Energy 5 Scotia Capital Energy Application to Export Electric Energy OE Docket No. EA-355 Scotia Capital Energy Application from Scotia Capital Energyto export electric energy to Canada PDF icon Application to Export Electric Energy OE Docket No EA-355 Scotia Capital Energy More Documents & Publications EA-355 Scotia Capital Energy, Inc. Application to Export Electric Energy OE Docket No. EA-407 Vitol Inc.: Federal Register Notice, Volume 80, No. 42 - March 4, 2015

  18. Direct/Indirect Costs

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    This chapter provides recommended categories for direct and indirect elements developed by the Committee for Cost Methods Development (CCMD) and describes various estimating techniques for direct and indirect costs.

  19. PEM Electrolyzer Incorporating an Advanced Low-Cost Membrane

    SciTech Connect (OSTI)

    Hamdan, Monjid

    2013-08-29

    The Department of Energy (DOE) has identified hydrogen production by electrolysis of water at forecourt stations as a critical technology for transition to the hydrogen economy; however, the cost of hydrogen produced by present commercially available electrolysis systems is considerably higher than the DOE 2015 and 2020 cost targets. Analyses of proton-exchange membrane (PEM) electrolyzer systems indicate that reductions in electricity consumption and electrolyzer stack and system capital cost are required to meet the DOE cost targets. The primary objective is to develop and demonstrate a cost-effective energy-based system for electrolytic generation of hydrogen. The goal is to increase PEM electrolyzer efficiency and to reduce electrolyzer stack and system capital cost to meet the DOE cost targets for distributed electrolysis. To accomplish this objective, work was conducted by a team consisting of Giner, Inc. (Giner), Virginia Polytechnic Institute & University (VT), and domnick hunter group, a subsidiary of Parker Hannifin (Parker). The project focused on four (4) key areas: (1) development of a high-efficiency, high-strength membrane; (2) development of a long-life cell-separator; (3) scale-up of cell active area to 290 cm2 (from 160 cm); and (4) development of a prototype commercial electrolyzer system. In each of the key stack development areas Giner and our team members conducted focused development in laboratory-scale hardware, with analytical support as necessary, followed by life-testing of the most promising candidate materials. Selected components were then scaled up and incorporated into low-cost scaled-up stack hardware. The project culminated in the fabrication and testing of a highly efficient electrolyzer system for production of 0.5 kg/hr hydrogen and validation of the stack and system in testing at the National Renewable Energy Laboratory (NREL).

  20. Power Plant Cycling Costs

    SciTech Connect (OSTI)

    Kumar, N.; Besuner, P.; Lefton, S.; Agan, D.; Hilleman, D.

    2012-07-01

    This report provides a detailed review of the most up to date data available on power plant cycling costs. The primary objective of this report is to increase awareness of power plant cycling cost, the use of these costs in renewable integration studies and to stimulate debate between policymakers, system dispatchers, plant personnel and power utilities.

  1. Low Cost High Concentration PV Systems for Utility Power Generation |

    Office of Environmental Management (EM)

    Department of Energy Low Cost High Concentration PV Systems for Utility Power Generation An overview of the Low Cost High Concentration PV Systems for Utility Power Generation project to transition Amonix's concentrating photovoltaic (PV) systems from low-volume to high-volume production. PDF icon Low Cost High Concentration PV Systems for Utility Power Generation More Documents & Publications Solar America Initiative Low Cost High Concentration PV Systems for Utility Power Generation

  2. Capital investment requirements for greenhouse gas emissions mitigation in power generation on near term to century time scales and global to regional spatial scales

    SciTech Connect (OSTI)

    Chaturvedi, Vaibhav; Clarke, Leon E.; Edmonds, James A.; Calvin, Katherine V.; Kyle, G. Page

    2014-11-01

    Electrification plays a crucial role in cost-effective greenhouse gas emissions mitigation strategies. Such strategies in turn carry implications for financial capital markets. This paper explores the implication of climate mitigation policy for capital investment demands by the electric power sector on decade to century time scales. We go further to explore the implications of technology performance and the stringency of climate policy for capital investment demands by the power sector. Finally, we discuss the regional distribution of investment demands. We find that stabilizing GHG emissions will require additional investment in the electricity generation sector over and above investments that would be need in the absence of climate policy, in the range of 16 to 29 Trillion US$ (60-110%) depending on the stringency of climate policy during the period 2015 to 2095 under default technology assumptions. This increase reflects the higher capital intensity of power systems that control emissions. Limits on the penetration of nuclear and carbon capture and storage technology could increase costs substantially. Energy efficiency improvements can reduce the investment requirement by 8 to21 Trillion US$ (default technology assumptions), depending on climate policy scenario with higher savings being obtained under the most stringent climate policy. The heaviest investments in power generation were observed in the China, India, SE Asia and Africa regions with the latter three regions dominating in the second half of the 21st century.

  3. Comparison of financing costs for wind turbine and fossil powerplants

    SciTech Connect (OSTI)

    Kahn, E.

    1995-02-01

    This paper compares the financing costs of wind turbine powerplants with those of fossil powerplants. The goal of this examination is to determine the extent to which these costs differ and what the sources of such differences may be. The discussion is organized in the following fashion. Section 2 introduces basic terminology and concepts from finance, as they apply in the powerplant setting. Section 3 reviews available data from a variety of sources to estimate the magnitude of the variables identified in Section 2. In Section 4 we examine the effect of the production tax credit enacted in the Energy Policy Act of 1992 on the financing of wind turbine projects. Conclusions are offered in Section 5. In the past two years there have been only two wind turbine projects that have been financed, so the basis for broad conclusions is limited. Nonetheless, there appears to be a significant advantage in financing costs for conventional projects compared to wind turbines. The two sources of disadvantage to wind power are first, the cost of equity capital is significantly more expensive, and second, the capital structure of wind projects has a much greater fraction of expensive equity than conventional alternatives.

  4. Low Cost Lithography Tool for High Brightness LED Manufacturing

    SciTech Connect (OSTI)

    Andrew Hawryluk; Emily True

    2012-06-30

    The objective of this activity was to address the need for improved manufacturing tools for LEDs. Improvements include lower cost (both capital equipment cost reductions and cost-ofownership reductions), better automation and better yields. To meet the DOE objective of $1- 2/kilolumen, it will be necessary to develop these highly automated manufacturing tools. Lithography is used extensively in the fabrication of high-brightness LEDs, but the tools used to date are not scalable to high-volume manufacturing. This activity addressed the LED lithography process. During R&D and low volume manufacturing, most LED companies use contact-printers. However, several industries have shown that these printers are incompatible with high volume manufacturing and the LED industry needs to evolve to projection steppers. The need for projection lithography tools for LED manufacturing is identified in the Solid State Lighting Manufacturing Roadmap Draft, June 2009. The Roadmap states that Projection tools are needed by 2011. This work will modify a stepper, originally designed for semiconductor manufacturing, for use in LED manufacturing. This work addresses improvements to yield, material handling, automation and throughput for LED manufacturing while reducing the capital equipment cost.

  5. Maximizing productivity & profitability through best cost shift schedules

    SciTech Connect (OSTI)

    Coleman, R.

    1996-12-31

    If you have the right equipment and employees at the right place, the fight time, and the right cost, you have the perfect business schedule. But, if you`re like most mines, you can probably improve your schedule, improvements that will reach all the way to the bottom line. And unlike adding employees, materials, or capital equipment, better scheduling is a cost-free way improve profitability. A good schedule can save millions. A bad schedule will cost money every year. A shift schedule is not a day off pattern or shift length. A shift schedule is a complete system deploying personnel and capital equipment. Most mining schedules are either copied from another operation, based on tradition or the result of a contract negotiation made far from the mine site. Unfortunately, most mine managers don`t give much thought to schedules until a crisis develops; at which point the tendency is to implement the first solution that comes along as quickly as possible. Costly mistakes are made.

  6. Processing Cost Analysis for Biomass Feedstocks

    SciTech Connect (OSTI)

    Badger, P.C.

    2002-11-20

    The receiving, handling, storing, and processing of woody biomass feedstocks is an overlooked component of biopower systems. The purpose of this study was twofold: (1) to identify and characterize all the receiving, handling, storing, and processing steps required to make woody biomass feedstocks suitable for use in direct combustion and gasification applications, including small modular biopower (SMB) systems, and (2) to estimate the capital and operating costs at each step. Since biopower applications can be varied, a number of conversion systems and feedstocks required evaluation. In addition to limiting this study to woody biomass feedstocks, the boundaries of this study were from the power plant gate to the feedstock entry point into the conversion device. Although some power plants are sited at a source of wood waste fuel, it was assumed for this study that all wood waste would be brought to the power plant site. This study was also confined to the following three feedstocks (1) forest residues, (2) industrial mill residues, and (3) urban wood residues. Additionally, the study was confined to grate, suspension, and fluidized bed direct combustion systems; gasification systems; and SMB conversion systems. Since scale can play an important role in types of equipment, operational requirements, and capital and operational costs, this study examined these factors for the following direct combustion and gasification system size ranges: 50, 20, 5, and 1 MWe. The scope of the study also included: Specific operational issues associated with specific feedstocks (e.g., bark and problems with bridging); Opportunities for reducing handling, storage, and processing costs; How environmental restrictions can affect handling and processing costs (e.g., noise, commingling of treated wood or non-wood materials, emissions, and runoff); and Feedstock quality issues and/or requirements (e.g., moisture, particle size, presence of non-wood materials). The study found that over the years the industry has shown a good deal of ingenuity and, as a result, has developed several cost effective methods of processing and handling wood. SMB systems usually cannot afford to perform much onsite processing and therefore usually purchase fuels processed to specification. Owners of larger systems try to minimize onsite processing to minimize processing costs. Whole truck dumpers are expensive, but allow for faster and easier unloading, which reduces labor costs and charges by the haulers. Storage costs are a major factor in overall costs, thus the amount of fuel reserve is an important consideration. Silos and bins are relatively expensive compared to open piles used for larger facilities, but may be required depending on space available, wood characteristics, and amount of wood to be stored. For larger systems, a front-end loader has a lot of flexibility in use and is an essential piece of equipment for moving material. Few opportunities appear to exist for improving the cost effectiveness of these systems.

  7. Progress in Initiator Modeling

    SciTech Connect (OSTI)

    Hrousis, C A; Christensen, J S

    2009-05-04

    There is great interest in applying magnetohydrodynamic (MHD) simulation techniques to the designs of electrical high explosive (HE) initiators, for the purpose of better understanding a design's sensitivities, optimizing its performance, and/or predicting its useful lifetime. Two MHD-capable LLNL codes, CALE and ALE3D, are being used to simulate the process of ohmic heating, vaporization, and plasma formation in the bridge of an initiator, be it an exploding bridgewire (EBW), exploding bridgefoil (EBF) or slapper type initiator. The initiation of the HE is simulated using Tarver Ignition & Growth reactive flow models. 1-D, 2-D and 3-D models have been constructed and studied. The models provide some intuitive explanation of the initiation process and are useful for evaluating the potential impact of identified aging mechanisms (such as the growth of intermetallic compounds or powder sintering). The end product of this work is a simulation capability for evaluating margin in proposed, modified or aged initiation system designs.

  8. Industrial Carbon Management Initiative

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Industrial Carbon Management Initiative Fact Sheets Research Team Members Key Contacts Industrial Carbon Management Initiative (ICMI) Background The ICMI project is part of a larger program called Carbon Capture Simulation and Storage Initiative (C2S2I). The C2S2I has a goal of expanding the DOE's focus on Carbon Capture Utilization and Storage (CCUS) for advanced coal power systems and other applications, including the use of petroleum coke as a feedstock for the industrial sector. The American

  9. Initiatives | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Initiatives Initiatives Through a variety of cross-cutting program initiatives, the Office of International Affairs (IA) responds to the most pressing global energy challenges, ranging from energy security and market volatility to long-term efforts to reduce carbon pollution and the impacts of climate change. IA has the primary responsibility for coordinating the efforts of diverse elements in the Department to ensure a unified voice in our international energy policy. This page highlights some

  10. About the Initiative

    SciTech Connect (OSTI)

    Not Available

    2007-06-01

    This factsheet gives an overview of the Solar America Initiative (SAI), including goals, research and development strategy, market transformation strategy, and benefits to nation.

  11. Salt Waste Processing Initiatives

    Office of Environmental Management (EM)

    Patricia Suggs Salt Processing Team Lead Assistant Manager for Waste Disposition Project Office of Environmental Management Savannah River Site Salt Waste Processing Initiatives 2 ...

  12. TVA- Solar Solutions Initiative

    Broader source: Energy.gov [DOE]

    Solar Solutions Initiative (SSI) is a pilot program that offers additional financial incentives for Solar PV systems participating in the Renewable Standard Offer program. Applications for new...

  13. National Laboratory Impact Initiative

    Broader source: Energy.gov [DOE]

    The National Laboratory Impact Initiative supports the relationship between the Office of Energy Efficiency & Renewable Energy and the national laboratory enterprise.  The national laboratories...

  14. SunShot Initiative Mission | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    About » SunShot Initiative Mission SunShot Initiative Mission Photo of a male silhouetted against a solar array. The SunShot Initiative's mission is to make solar energy fully cost-competitive with traditional energy sources before the end of this decade, making this clean renewable energy resource more affordable and accessible to Americans. Vision The SunShot Initiative vision is to make the total cost of solar energy fully economically-viable for everyday use, so that all Americans will

  15. Capital Planning for DOE O 413.3B, Chicago | Department of Energy

    Energy Savers [EERE]

    Capital Planning for DOE O 413.3B, Chicago Capital Planning for DOE O 413.3B, Chicago March 30, 2016 8:00AM EDT to March 31, 2016 5:00PM EDT Capital Planning for DOE O 413.3B Capital Asset Projects Level 1 Elective Course 2 days / 16 CLPs In this course, participants review capital planning questions they should ask when a non-information technology capital asset project under the DOE O 413.3B is in each phase of the project's acquisition. The course reviews the documents and reports from the

  16. High Energy Cost Grants

    Broader source: Energy.gov [DOE]

    The High Energy Cost Grant Program provides financial assistance for the improvement of energy generation, transmission, and distribution facilities servicing eligible rural communities with home...

  17. SOFT COST GRAND CHALLENGE

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    energycenter.org California Center for Sustainable Energy Soft Cost Grand Challenge May 22, 2014 Accelerating the transition to a sustainable world powered by clean energy 2...

  18. Vehicle Cost Calculator

    Alternative Fuels and Advanced Vehicles Data Center [Office of Energy Efficiency and Renewable Energy (EERE)]

    Choose a vehicle to compare fuel cost and emissions with a conventional vehicle. Select Fuel/Technology Electric Hybrid Electric Plug-in Hybrid Electric Natural Gas (CNG) Flex Fuel (E85) Biodiesel (B20) Propane (LPG) Next Vehicle Cost Calculator Vehicle 0 City 0 Hwy (mi/gal) 0 City 0 Hwy (kWh/100m) Gasoline Vehicle 0 City 0 Hwy (mi/gal) Normal Daily Use 30.5 Total miles/day City 55 % Hwy 45 % Other Trips 3484 Total miles/year City 20 % Hwy 80 % Fuel Cost Emissions Annual Fuel Cost $ $/gal Annual

  19. Cost-Effective Consolidation of Fine Aluminum Scrap for Increased Remelting Effieciency

    SciTech Connect (OSTI)

    William Van Geertruyden

    2005-09-22

    The main objective of this research was to develop a new re-melting process for fine or light gauge aluminum scrap products that exhibits dramatic improvements in energy efficiency. Light gauge aluminum scrap in the form of chips, turnings, and borings has historically been underutilized in the aluminum recycling process due to its high surface area to volume ratio resulting in low melt recovery. Laboratory scale consolidation experiments were performed using loose aluminum powder as a modeling material as well as shredded aluminum wire scrap. The processing parameters necessary to create consolidated aluminum material were determined. Additionally, re-melting experiments using consolidated and unconsolidated aluminum powder confirmed the hypothesis that metal recovery using consolidated material will significantly improve by as much as 20%. Based on this research, it is estimated that approximately 495 billion Btu/year can be saved by implementation of this technology in one domestic aluminum rolling plant alone. The energy savings are realized by substituting aluminum scrap for primary aluminum, which requires large amounts of energy to produce. While there will be an initial capital investment, companies will benefit from the reduction of dependence on primary aluminum thus saving considerable costs. Additionally, the technology will allow companies to maintain in-house alloy scrap, rather than purchasing from other vendors and eliminate the need to discard the light gauge scrap to landfills.

  20. Manufacturing Cost Levelization Model – A User’s Guide

    SciTech Connect (OSTI)

    Morrow, William R.; Shehabi, Arman; Smith, Sarah Josephine

    2015-08-01

    The Manufacturing Cost Levelization Model is a cost-performance techno-economic model that estimates total large-scale manufacturing costs for necessary to produce a given product. It is designed to provide production cost estimates for technology researchers to help guide technology research and development towards an eventual cost-effective product. The model presented in this user’s guide is generic and can be tailored to the manufacturing of any product, including the generation of electricity (as a product). This flexibility, however, requires the user to develop the processes and process efficiencies that represents a full-scale manufacturing facility. The generic model is comprised of several modules that estimate variable costs (material, labor, and operating), fixed costs (capital & maintenance), financing structures (debt and equity financing), and tax implications (taxable income after equipment and building depreciation, debt interest payments, and expenses) of a notional manufacturing plant. A cash-flow method is used to estimate a selling price necessary for the manufacturing plant to recover its total cost of production. A levelized unit sales price ($ per unit of product) is determined by dividing the net-present value of the manufacturing plant’s expenses ($) by the net present value of its product output. A user defined production schedule drives the cash-flow method that determines the levelized unit price. In addition, an analyst can increase the levelized unit price to include a gross profit margin to estimate a product sales price. This model allows an analyst to understand the effect that any input variables could have on the cost of manufacturing a product. In addition, the tool is able to perform sensitivity analysis, which can be used to identify the key variables and assumptions that have the greatest influence on the levelized costs. This component is intended to help technology researchers focus their research attention on tasks that offer the greatest opportunities for cost reduction early in the research and development stages of technology invention.

  1. SunShot Initiative Fact Sheet

    SciTech Connect (OSTI)

    DOE Solar Energy Technologies Office

    2015-04-01

    The U.S. Department of Energy (DOE) SunShot Initiative is a collaborative national effort launched in 2011 that aggressively drives innovation to make solar energy fully cost competitive with traditional energy sources before the end of the decade. The SunShot fact sheet outlines goals and successes of the program as it works with private companies, universities, non-profit organizations, state and local governments, and national laboratories to drive down the cost of solar electricity to $0.06 per kilowatt-hour, without incentives, by the year 2020.

  2. Program & Project Management For The Acquisition Of Capital Assets |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy PDF icon Program & Project Management For The Acquisition Of Capital Assets More Documents & Publications "Paper" Energy Systems Acquisition Advisory Board Process ESAAB Standard Operating Procedure - July 2014 Microsoft PowerPoint - 01 Bosco PM Workshop BOSCO Feb22_2010PB final rcvd 5 Mar [Compatibility Mode]

  3. Statement on Department of Energy's Major System Capital Asset Projects

    National Nuclear Security Administration (NNSA)

    before the House Committee on Appropriations Subcommittee on Energy & Water Development | National Nuclear Security Administration Department of Energy's Major System Capital Asset Projects before the House Committee on Appropriations Subcommittee on Energy & Water Development | National Nuclear Security Administration Facebook Twitter Youtube Flickr RSS People Mission Managing the Stockpile Preventing Proliferation Powering the Nuclear Navy Emergency Response Recapitalizing Our

  4. Augmenting Probabilistic Risk Assesment with Malevolent Initiators

    SciTech Connect (OSTI)

    Curtis Smith; David Schwieder

    2011-11-01

    As commonly practiced, the use of probabilistic risk assessment (PRA) in nuclear power plants only considers accident initiators such as natural hazards, equipment failures, and human error. Malevolent initiators are ignored in PRA, but are considered the domain of physical security, which uses vulnerability assessment based on an officially specified threat (design basis threat). This paper explores the implications of augmenting and extending existing PRA models by considering new and modified scenarios resulting from malevolent initiators. Teaming the augmented PRA models with conventional vulnerability assessments can cost-effectively enhance security of a nuclear power plant. This methodology is useful for operating plants, as well as in the design of new plants. For the methodology, we have proposed an approach that builds on and extends the practice of PRA for nuclear power plants for security-related issues. Rather than only considering 'random' failures, we demonstrated a framework that is able to represent and model malevolent initiating events and associated plant impacts.

  5. Decommissioning Unit Cost Data

    SciTech Connect (OSTI)

    Sanford, P. C.; Stevens, J. L.; Brandt, R.

    2002-02-26

    The Rocky Flats Closure Site (Site) is in the process of stabilizing residual nuclear materials, decommissioning nuclear facilities, and remediating environmental media. A number of contaminated facilities have been decommissioned, including one building, Building 779, that contained gloveboxes used for plutonium process development but did little actual plutonium processing. The actual costs incurred to decommission this facility formed much of the basis or standards used to estimate the decommissioning of the remaining plutonium-processing buildings. Recent decommissioning activities in the first actual production facility, Building 771, implemented a number of process and procedural improvements. These include methods for handling plutonium contaminated equipment, including size reduction, decontamination, and waste packaging, as well as management improvements to streamline planning and work control. These improvements resulted in a safer working environment and reduced project cost, as demonstrated in the overall project efficiency. The topic of this paper is the analysis of how this improved efficiency is reflected in recent unit costs for activities specific to the decommissioning of plutonium facilities. This analysis will allow the Site to quantify the impacts on future Rocky Flats decommissioning activities, and to develop data for planning and cost estimating the decommissioning of future facilities. The paper discusses the methods used to collect and arrange the project data from the individual work areas within Building 771. Regression and data correlation techniques were used to quantify values for different types of decommissioning activities. The discussion includes the approach to identify and allocate overall project support, waste management, and Site support costs based on the overall Site and project costs to provide a ''burdened'' unit cost. The paper ultimately provides a unit cost basis that can be used to support cost estimates for decommissioning at other facilities with similar equipment and labor costs. It also provides techniques for extracting information from limited data using extrapolation and interpolation techniques.

  6. Microsoft Word - DOE Human Capital Strategic Plan 2011-2015.docx

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    DOE HUMAN CAPITAL STRATEGIC PLAN FY 2011 - FY 2015 DOE HUMAN CAPITAL STRATEGIC PLAN FY 2011 - FY 2015 TABLE OF CONTENTS EXECUTIVE SUMMARY .................................................................................................................................... 1 SECTION I: MISSION, STRATEGIC PLAN AND PRIORITIES .............................................................................. 2 MISSION

  7. Delegation Order No. 00-002.13-01 to the Deputy Chief Human Capital...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    CURRENT 002.13-01, Delegation Order No. 00-002.13-01 to the Deputy Chief Human Capital Officer by Diane Johnson Functional areas: Human Capital 00-00213-01HC-DepChfHCO.pdf -- PDF...

  8. Green Button Initiative Growing

    Broader source: Energy.gov [DOE]

    The Green Button initiative, which is the common-sense idea that electricity customers should be able to securely download their own energy usage information from their utility websites, is continuing to gain traction across the country.

  9. Initiatives | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Initiatives Initiatives The Office of Energy Policy & Systems Analysis (EPSA) responds to the most pressing domestic energy challenges, delivering unbiased energy analysis to the Department of Energy's leadership on existing and prospective energy-related policies, focusing in part on integrative analysis of energy systems. EPSA also includes the Secretariat of the Quadrennial Energy Review, which has primary responsibility for supporting the White House interagency process and providing to

  10. Energy Department and GSA Assist in Capital Solar Challenge Industry Day |

    Office of Environmental Management (EM)

    Department of Energy and GSA Assist in Capital Solar Challenge Industry Day Energy Department and GSA Assist in Capital Solar Challenge Industry Day October 21, 2014 - 4:43pm Addthis The White House launched the Capital Solar Challenge (CSC), which directs Federal agencies, military installations, and Federally subsidized complexes to identify opportunities to deploy solar renewable energy at Federal locations across the national capital region. The Energy Department and the General Services

  11. EM Capital and Major Operating Project Standard Review Plan Edition Two |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy EM Capital and Major Operating Project Standard Review Plan Edition Two EM Capital and Major Operating Project Standard Review Plan Edition Two This memorandum introduces the Second Edition of the Capital and Major Operations Projects Standard Review Plan (SRP). PDF icon Memo Issuance of EM Capital and Major Operating Project Standard Review Plan Edition Two More Documents & Publications Standard Review Plan - Overview EM Quality Assurance Assessment Schedule FY 2010

  12. Office of the Chief Human Capital Officer (HC-1) | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    the Chief Human Capital Officer (HC-1) Office of the Chief Human Capital Officer (HC-1) HC-1 Mission and Function Statement The Office of the Chief Human Capital Officer (HC) provides leadership to the Department of Energy (DOE) on the impact and use of policies, proposals, programs, and partnership agreements/relationships related to all aspects of Human Capital Management (HCM). Within the framework of the organization, HCM is an integrated approach that links human resources,

  13. Human Capital: The Role of Ombudsmen in Dispute Resolution | Department of

    Office of Environmental Management (EM)

    Energy Human Capital: The Role of Ombudsmen in Dispute Resolution Human Capital: The Role of Ombudsmen in Dispute Resolution PDF icon Human Capital: The Role of Ombudsmen in Dispute Resolution More Documents & Publications The Role of Ombudsmen in Dispute Resolution ADR Revised Policy TT Coordinator Ltr dated May 13 2010

  14. Sunshot Initiative High Penetration Solar Portal

    DOE Data Explorer [Office of Scientific and Technical Information (OSTI)]

    The DOE SunShot Initiative is a collaborative national initiative to make solar energy cost-competitive with other forms of energy by the end of the decade. Reducing the installed cost of solar energy systems by about 75% will drive widespread large-scale adoption of this renewable energy and restore U.S. leadership in the global clean energy race. The High Penetration Solar Portal was created as a resource to aggregate the most relevant and timely information related to high penetration solar scenarios and integrating solar into the grid. The site is designed so that utilities, grant awardees, regulators, researchers, and other solar professionals can easily share data, case studies, lessons learned, and demonstration project findings. [from https://solarhighpen.energy.gov/about_the_high_penetration_solar_portal

  15. Renewable Energy Planning: Multiparametric Cost Optimization

    SciTech Connect (OSTI)

    Walker, A.

    2008-01-01

    This paper describes a method for determining the combination of renewable energy technologies that minimize life-cycle cost at a facility, often with a specified goal regarding percent of energy use from renewable sources. Technologies include: photovoltaics (PV); wind; solar thermal heat and electric; solar ventilation air preheating; solar water heating; biomass heat and electric (combustion, gasification, pyrolysis, anaerobic digestion); and daylighting. The method rests upon the National Renewable Energy Laboratory's (NREL's) capabilities in characterization of technology cost and performance, geographic information systems (GIS) resource assessment, and life-cycle cost analysis. The paper discusses how to account for the way candidate technologies interact with each other, and the solver routine used to determine the combination that minimizes life-cycle cost. Results include optimal sizes of each technology, initial cost, operating cost, and life-cycle cost, including incentives from utilities or governments. Results inform early planning to identify and prioritize projects at a site for subsequent engineering and economic feasibility study.

  16. Renewable Energy Planning: Multiparametric Cost Optimization; Preprint

    SciTech Connect (OSTI)

    Walker, A.

    2008-05-01

    This paper describes a method for determining the combination of renewable energy technologies that minimize life-cycle cost at a facility, often with a specified goal regarding percent of energy use from renewable sources. Technologies include: photovoltaics (PV); wind; solar thermal heat and electric; solar ventilation air preheating; solar water heating; biomass heat and electric (combustion, gasification, pyrolysis, anaerobic digestion); and daylighting. The method rests upon the National Renewable Energy Laboratory's (NREL's) capabilities in characterization of technology cost and performance, geographic information systems (GIS) resource assessment, and life-cycle cost analysis. The paper discusses how to account for the way candidate technologies interact with each other, and the solver routine used to determine the combination that minimizes life-cycle cost. Results include optimal sizes of each technology, initial cost, operating cost, and life-cycle cost, including incentives from utilities or governments. Results inform early planning to identify and prioritize projects at a site for subsequent engineering and economic feasibility study.

  17. Initiative for Clean Energy | Photosynthetic Antenna Research Center

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Initiative for Clean Energy July 25, 2012 Initiative for Clean Energy Engineers at Washington University will work on low-cost solar cells and systems, while other partners will be deploying the technology in India http://news.wustl.edu/news/Pages/24049.aspx In the News

  18. SunShot Initiative | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    SunShot Initiative Solar Ready Vets Adds New Training Locations Solar Ready Vets Adds New Training Locations The Solar Ready Vets program announced new training locations and a look ahead in a blog post from Deputy Secretary Elizabeth Sherwood Randall. Read more Technology to Market Awards Announced Technology to Market Awards Announced The Energy Department today announced $22.7 million for 23 projects that will significantly reduce the costs for solar energy systems across a variety of

  19. Vehicle Cost Calculator

    Alternative Fuels and Advanced Vehicles Data Center [Office of Energy Efficiency and Renewable Energy (EERE)]

    Annual GHG Emissions (lbs of CO2) Vehicle Cost Calculator See Assumptions and Methodology Back Next U.S. Department of Energy Energy Efficiency and Renewable Energy Get Widget Code...

  20. Workplace Charging Equipment Costs

    Broader source: Energy.gov [DOE]

    Charging stations are available from a variety of manufacturers in a range of models for all charging applications. For a single port charging station, Level 1 hardware costs range from $300-$1,500...

  1. Estimating Renewable Energy Costs

    Office of Energy Efficiency and Renewable Energy (EERE)

    Some renewable energy measures, such as daylighting, passive solar heating, and cooling load avoidance, do not add much to the cost of a building. However, renewable energy technologies typically...

  2. INDEPENDENT COST REVIEW (ICR)

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... Report SOP Standard Operating Procedure TEC Total Estimated Cost TIPR Technical ... FY13 FY14 FY15 FY16 Total PED Construction TEC OPC TPC Note: above values include MR...

  3. System Cost Model

    Energy Science and Technology Software Center (OSTI)

    1996-03-27

    SCM is used for estimation of the life-cycle impacts (costs, health and safety risks) of waste management facilities for mixed low-level, low-level, and transuranic waste. SCM uses parametric cost functions to estimate life-cycle costs for various treatment, storage, and disposal modules which reflect planned and existing waste management facilities at Department of Energy (DOE) installations. SCM also provides transportation costs for intersite transfer of DOE wastes. SCM covers the entire DOE waste management complex tomore » allow system sensitivity analysis including: treatment, storage, and disposal configuration options; treatment technology selection; scheduling options; transportation options; waste stream and volume changes; and site specific conditions.« less

  4. Cost Estimating Guide

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2011-05-09

    This Guide provides uniform guidance and best practices that describe the methods and procedures that could be used in all programs and projects at DOE for preparing cost estimates. No cancellations.

  5. Cost Estimating Guide

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2011-05-09

    This Guide provides uniform guidance and best practices that describe the methods and procedures that could be used in all programs and projects at DOE for preparing cost estimates.

  6. Vehicle Cost Calculator

    Alternative Fuels and Advanced Vehicles Data Center [Office of Energy Efficiency and Renewable Energy (EERE)]

    Choose a vehicle to compare fuel cost and emissions with a conventional vehicle. Select Fuel/Technology Electric Hybrid Electric Plug-in Hybrid Electric Natural Gas (CNG) Flex Fuel (E85) Biodiesel (B20) Next Vehicle Cost Calculator Update Your Widget Code This widget version will stop working on March 31. Update your widget code. × Widget Code Select All Close U.S. Department of Energy Energy Efficiency and Renewable Energy

  7. RCRA facility stabilization initiative

    SciTech Connect (OSTI)

    Not Available

    1995-02-01

    The RCRA Facility Stabilization Initiative was developed as a means of implementing the Corrective Action Program`s management goals recommended by the RIS for stabilizing actual or imminent releases from solid waste management units that threaten human health and the environment. The overall goal of stabilization is to, as situations warrant, control or abate threats to human health and/or the environment from releases at RCRA facilities, and/or to prevent or minimize the further spread of contamination while long-term remedies are pursued. The Stabilization initiative is a management philosophy and should not be confused with stabilization technologies.

  8. 2007 Initial Allocation Awards

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    7 Awards 2007 Initial Allocation Awards The following table lists the initial allocation awards for NERSC for the 2007 allocation year (Jan 9, 2007 through Jan 7, 2008). The list is in alphabetical order by the last name of the Principal Investigator. Note - Letters following the repository name indicate the following: 'I' DOE ASCR INCITE award 'S' NERSC Startup award A B C D E F G H I J K L M N O P Q R S T U V W X Y Z Principal Site Request Repo SP HPSS Project Title Investigator Id Hours SRUs

  9. Clean Coal Power Initiative

    SciTech Connect (OSTI)

    Doug Bartlett; Rob James; John McDermott; Neel Parikh; Sanjay Patnaik; Camilla Podowski

    2006-03-31

    This report is the fifth quarterly Technical Progress Report submitted by NeuCo, Incorporated, under Award Identification Number, DE-FC26-04NT41768. This award is part of the Clean Coal Power Initiative (''CCPI''), the ten-year, $2B initiative to demonstrate new clean coal technologies in the field. This report is one of the required reports listed in Attachment B Federal Assistance Reporting Checklist, part of the Cooperative Agreement. The report covers the award period January 1, 2006 - March 31, 2006 and NeuCo's efforts within design, development, and deployment of on-line optimization systems during that period.

  10. Innovative Manufacturing Initiative Recognition Day | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Innovative Manufacturing Initiative Recognition Day Innovative Manufacturing Initiative Recognition Day June 20, 2012 The Innovative Manufacturing Initiative (IMI) Recognition Day (held in Washington, DC on June 20, 2012) showcased IMI projects selected by the Energy Department to help American manufacturers dramatically increase the energy efficiency of their operations and reduce costs. Each project will advance transformational technologies and materials that can benefit a broad cross-section

  11. SunShot Initiative Fact Sheet | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Initiative Fact Sheet SunShot Initiative Fact Sheet The U.S. Department of Energy (DOE) SunShot Initiative is a collaborative national effort launched in 2011 that aggressively drives innovation to make solar energy fully cost competitive with traditional energy sources before the end of the decade. The SunShot fact sheet outlines goals and successes of the program as it works with private companies, universities, non-profit organizations, state and local governments, and national laboratories

  12. About the SunShot Initiative | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    About the SunShot Initiative About the SunShot Initiative The U.S. Department of Energy (DOE) Solar Energy Technologies Office focuses on achieving the goals of the SunShot Initiative, which seeks to make solar energy cost-competitive with other forms of electricity by the end of the decade. What We Do SunShot funds cooperative research, development, demonstration, and deployment projects by private companies, universities, state and local governments, nonprofit organizations, and national

  13. Monolithic exploding foil initiator

    DOE Patents [OSTI]

    Welle, Eric J; Vianco, Paul T; Headley, Paul S; Jarrell, Jason A; Garrity, J. Emmett; Shelton, Keegan P; Marley, Stephen K

    2012-10-23

    A monolithic exploding foil initiator (EFI) or slapper detonator and the method for making the monolithic EFI wherein the exploding bridge and the dielectric from which the flyer will be generated are integrated directly onto the header. In some embodiments, the barrel is directly integrated directly onto the header.

  14. Clean Energy Manufacturing Initiative

    SciTech Connect (OSTI)

    2013-04-01

    The initiative will strategically focus and rally EEREs clean energy technology offices and Advanced Manufacturing Office around the urgent competitive opportunity for the United States to be the leader in the clean energy manufacturing industries and jobs of today and tomorrow.

  15. U.S. Balance-of-Station Cost Drivers and Sensitivities (Presentation)

    SciTech Connect (OSTI)

    Maples, B.

    2012-10-01

    With balance-of-system (BOS) costs contributing up to 70% of the installed capital cost, it is fundamental to understanding the BOS costs for offshore wind projects as well as potential cost trends for larger offshore turbines. NREL developed a BOS model using project cost estimates developed by GL Garrad Hassan. Aspects of BOS covered include engineering and permitting, ports and staging, transportation and installation, vessels, foundations, and electrical. The data introduce new scaling relationships for each BOS component to estimate cost as a function of turbine parameters and size, project parameters and size, and soil type. Based on the new BOS model, an analysis to understand the non?turbine costs has been conducted. This analysis establishes a more robust baseline cost estimate, identifies the largest cost components of offshore wind project BOS, and explores the sensitivity of the levelized cost of energy to permutations in each BOS cost element. This presentation shows results from the model that illustrates the potential impact of turbine size and project size on the cost of energy from U.S. offshore wind plants.

  16. Retail Infrastructure Costs Comparison for Hydrogen and Electricity for Light-Duty Vehicles: Preprint

    SciTech Connect (OSTI)

    Melaina, M.; Sun, Y.; Bush, B.

    2014-08-01

    Both hydrogen and plug-in electric vehicles offer significant social benefits to enhance energy security and reduce criteria and greenhouse gas emissions from the transportation sector. However, the rollout of electric vehicle supply equipment (EVSE) and hydrogen retail stations (HRS) requires substantial investments with high risks due to many uncertainties. We compare retail infrastructure costs on a common basis - cost per mile, assuming fueling service to 10% of all light-duty vehicles in a typical 1.5 million person city in 2025. Our analysis considers three HRS sizes, four distinct types of EVSE and two distinct EVSE scenarios. EVSE station costs, including equipment and installation, are assumed to be 15% less than today's costs. We find that levelized retail capital costs per mile are essentially indistinguishable given the uncertainty and variability around input assumptions. Total fuel costs per mile for battery electric vehicle (BEV) and plug-in hybrid vehicle (PHEV) are, respectively, 21% lower and 13% lower than that for hydrogen fuel cell electric vehicle (FCEV) under the home-dominant scenario. Including fuel economies and vehicle costs makes FCEVs and BEVs comparable in terms of costs per mile, and PHEVs are about 10% less than FCEVs and BEVs. To account for geographic variability in energy prices and hydrogen delivery costs, we use the Scenario Evaluation, Regionalization and Analysis (SERA) model and confirm the aforementioned estimate of cost per mile, nationally averaged, but see a 15% variability in regional costs of FCEVs and a 5% variability in regional costs for BEVs.

  17. Offshore Wind Plant Balance-of-Station Cost Drivers and Sensitivities (Poster)

    SciTech Connect (OSTI)

    Saur, G.; Maples, B.; Meadows, B.; Hand, M.; Musial, W.; Elkington, C.; Clayton, J.

    2012-09-01

    With Balance of System (BOS) costs contributing up to 70% of the installed capital cost, it is fundamental to understanding the BOS costs for offshore wind projects as well as potential cost trends for larger offshore turbines. NREL developed a BOS model using project cost estimates developed by GL Garrad Hassan. Aspects of BOS covered include engineering and permitting, ports and staging, transportation and installation, vessels, foundations, and electrical. The data introduce new scaling relationships for each BOS component to estimate cost as a function of turbine parameters and size, project parameters and size, and soil type. Based on the new BOS model, an analysis to understand the non-turbine costs associated with offshore turbine sizes ranging from 3 MW to 6 MW and offshore wind plant sizes ranging from 100 MW to 1000 MW has been conducted. This analysis establishes a more robust baseline cost estimate, identifies the largest cost components of offshore wind project BOS, and explores the sensitivity of the levelized cost of energy to permutations in each BOS cost element. This presentation shows results from the model that illustrates the potential impact of turbine size and project size on the cost of energy from US offshore wind plants.

  18. Program and Project Management for the Acquisition of Capital Assets

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2006-07-28

    The Order provides project management direction for the acquisition of capital assets that are delivered on schedule, within budget, and capable of meeting mission performance and environmental safety and health standards. The page change incorporates requirements of DOE-STD-1189-2008, Integration of Safety into the Design Process, mandatory for Hazard Category 1, 2 and 3 nuclear facilities. Cancels DOE O 413.3. Canceled by DOE O 413.3B dated 11-29-10.

  19. Program and Project Management for the Acquisition of Capital Assets

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2011-05-18

    To provide the Department of Energy (DOE), including the National Nuclear Security Administration, with project management direction for the acquisition of capital assets with the goal of delivering projects on schedule, within budget, and fully capable of meeting mission performance, safeguards and security, and environmental, safety, and health standards. Cancels DOE O 413.3. Canceled by DOE O 413.3A Chg 1.

  20. NREL Technology Transfer: Facilitating Capital Investment in Clean Energy Technology

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Technology Transfer Facilitating Capital Investment in Clean Energy Technology Tom A. Williams Director, Technology Transfer Office National Renewable Energy Laboratory We Are Unique * Only national laboratory dedicated to renewable energy and energy efficiency R&D * Research spans fundamental science to technology solutions * Collaboration with industry, university and international partners is a hallmark * Research is market relevant because of a systems focus and global perspective and

  1. Human Capital: The Role of Ombudsmen in Dispute Resolution

    Broader source: Energy.gov (indexed) [DOE]

    the Ranking Member, Subcommittee on International Security, Proliferation, and Federal Services, Committee on Government Affairs, U.S. Senate United States General Accounting Office GAO April 2001 HUMAN CAPITAL The Role of Ombudsmen in Dispute Resolution GAO-01-466 Page i GAO-01-466 The Role of Ombudsmen in Dispute Resolution Letter 1 Results in Brief 2 Background 5 Objectives, Scope, and Methodology 12 Some Agencies Use Ombudsmen to Deal With Workplace Issues 14 The Case Illustrations: Varied

  2. The Dog Days of Summer - Capitalizing on the Pet Market

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Dog Days of Summer - Capitalizing on the Pet Market July 9, 2015 Call Slides and Discussion Summary Agenda  Call Logistics and Opening Poll #1  Introductions  Residential Network and Peer Exchange Call Overview  Opening Poll #2 and #3  Setting the Stage: Pet Market Statistics  Featured Speaker  Julie Saporito, Program Administrator, City and County of Denver (Network Member)  Discussion  What opportunities exist for leveraging the pet market to promote residential

  3. Human Capital: The Role of Ombudsmen in Dispute Resolution

    Office of Environmental Management (EM)

    Report to the Ranking Member, Subcommittee on International Security, Proliferation, and Federal Services, Committee on Government Affairs, U.S. Senate United States General Accounting Office GAO April 2001 HUMAN CAPITAL The Role of Ombudsmen in Dispute Resolution GAO-01-466 Page i GAO-01-466 The Role of Ombudsmen in Dispute Resolution Letter 1 Results in Brief 2 Background 5 Objectives, Scope, and Methodology 12 Some Agencies Use Ombudsmen to Deal With Workplace Issues 14 The Case

  4. IDC RP2 & 3 US Industry Standard Cost Estimate Summary.

    SciTech Connect (OSTI)

    Harris, James M.; Huelskamp, Robert M.

    2015-01-01

    Sandia National Laboratories has prepared a ROM cost estimate for budgetary planning for the IDC Reengineering Phase 2 & 3 effort, using a commercial software cost estimation tool calibrated to US industry performance parameters. This is not a cost estimate for Sandia to perform the project. This report provides the ROM cost estimate and describes the methodology, assumptions, and cost model details used to create the ROM cost estimate. ROM Cost Estimate Disclaimer Contained herein is a Rough Order of Magnitude (ROM) cost estimate that has been provided to enable initial planning for this proposed project. This ROM cost estimate is submitted to facilitate informal discussions in relation to this project and is NOT intended to commit Sandia National Laboratories (Sandia) or its resources. Furthermore, as a Federally Funded Research and Development Center (FFRDC), Sandia must be compliant with the Anti-Deficiency Act and operate on a full-cost recovery basis. Therefore, while Sandia, in conjunction with the Sponsor, will use best judgment to execute work and to address the highest risks and most important issues in order to effectively manage within cost constraints, this ROM estimate and any subsequent approved cost estimates are on a 'full-cost recovery' basis. Thus, work can neither commence nor continue unless adequate funding has been accepted and certified by DOE.

  5. Factory Cost Model

    Energy Science and Technology Software Center (OSTI)

    1996-12-17

    The Factory Cost Model (FCM) is an economic analysis tool intended to provide flat panel display (FPD) and other similar discrete component manufacturers with the ability to make first-order estimates of the cost of unit production. This software has several intended uses. Primary among these is the ability to provide first-order economic analysis for future factories. Consequently, the model requires a minimal level of input detail, and accomodates situations where actual production data are notmore » available. This software is designed to be activity based such that most of the calculated direct costs are associated with the steps of a manufacturibg process. The FCM architecture has the ability to accomodate the analysis of existing manufacturing facilities. The FCM can provide assistance with strategic economic decisions surrounding production related matters. For instance, the program can project the effect on costs and resources of a new product''s introduction, or it can assess the potential cost reduction produced by step yield improvements in the manufacturing process.« less

  6. SunShot: Making Solar Energy Cost Competitive Throughout the United States (Fact Sheet)

    SciTech Connect (OSTI)

    Not Available

    2011-06-01

    The U.S. Department of Energy's SunShot Initiative focuses on making solar energy cost competitive throughout the United States.

  7. SunShot: Making Solar Energy Cost Competitive Throughout the United States (Fact Sheet)

    SciTech Connect (OSTI)

    McCamey, D.

    2011-03-01

    The U.S. Department of Energy's SunShot Initiative focuses on making solar energy cost competitive throughout the United States.

  8. Opportunities for market-based programs worldwide that reduce greenhouse gas emissions: Initial Observations from Missions to the Philippines, South Africa, and Mexico

    SciTech Connect (OSTI)

    Stanton-Hoyle, D.R.

    1998-07-01

    Globally, governments and industries are implementing innovative voluntary programs to reduce greenhouse gas emissions. Often these programs encourage groups to use cost effective technologies that capture market-based forces. These programs are successful because they capitalize on existing opportunities where both the environment and the participants can benefit (i.e., win-win opportunities). This paper documents efforts to investigate these kinds of win-win opportunities in three developing countries: the Philippines, South Africa, and Mexico. Initial observations are provided as fresh information from the field, drawing on six missions during the last nine months. Utility costs, interest rates, and overall economic health appear to critically affect opportunities in each country. By contrast, details of heating, ventilating and air-conditioning (HVAC) design and local climate were often important differences between countries. These affect opportunities, for example, to achieve significant savings from cooling systems or not. Looking at the success of ESCOs was somewhat surprising. One might expect to see the most successful ESCO activity where utility costs are high and upgrade opportunities are plentiful (such as in the Philippines). This was not the case, however, as research in the Philippines did not reveal even one active ESCO contract yet. Design practices for new construction were in need of the same thing that helps US design teams do a better job of energy-efficient design, better communications between design team members. Finally, industrial firms were doing a variety of EE upgrades in each country, but this level of activity was relatively small compared to what should be cost effective.

  9. Technical efforts focus on cutting LNG plant costs

    SciTech Connect (OSTI)

    Aoki, Ichizo; Kikkawa, Yoshitsugi

    1995-07-03

    LNG demand is growing due to the nuclear setback and environmental issues spurred by concern about the greenhouse effect and acid rain, especially in the Far East. However, LNG is expensive compared with other energy sources. Efforts continue to minimize capital and operating costs and to increase LNG plant availability and safety. Technical trends in the LNG industry aim at reducing plant costs in pursuit of a competitive LNG price on an energy value basis against the oil price. This article reviews key areas of technical development. Discussed are train size, liquefaction processes, acid gas removal, heavy end removal, nitrogen rejection, refrigeration compressor and drivers, expander application, cooling media selection, LNG storage and loading system, and plant availability.

  10. Salt Waste Processing Initiatives

    Office of Environmental Management (EM)

    Patricia Suggs Salt Processing Team Lead Assistant Manager for Waste Disposition Project Office of Environmental Management Savannah River Site Salt Waste Processing Initiatives 2 Overview * Current SRS Liquid Waste System status * Opportunity to accelerate salt processing - transformational technologies - Rotary Microfiltration (RMF) and Small Column Ion Exchange (SCIX) - Actinide Removal Process/Modular Caustic Side Solvent Extraction (ARP/MCU) extension with next generation extractant - Salt

  11. Asset Revitalization Initiative ARI

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Asset Revitalization Initiative ( ARI ) Mission * Community * Reuse ARI is a DOE-wide effort to advance the beneficial reuse of the agency's unique and diverse mix of assets, including land, facilities, infrastructure, equipment, technologies, natural resources, and highly skilled workforce. ARI promotes an efficient business environment to encourage collaboration between public and private resources. ARI integrates DOE missions with community interests. ARI is... Our Vision By 2020: Operations

  12. Nuclear Workforce Initiative - SRSCRO

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    nuclear Nuclear Workforce Initiative The SRSCRO region of Georgia and South Carolina has the most unique nuclear industry capabilities in the nation. This region is at the forefront of new nuclear power production, environmental stewardship, innovative technology and national security. Long-term nuclear workforce demand is growing in the region as new nuclear reactors are under construction at the V.C Summer Nuclear Station in Fairfield County, SC and at Plant Vogtle in Waynesboro, GA. New

  13. OSM's reforestation initiative

    SciTech Connect (OSTI)

    Boyce, J.S.

    1999-07-01

    Implementation of the Surface Mining Control and Reclamation Act (SMCRA) has discouraged reforestation in some situations where reforestation would be desirable. OSM is engaged in an initiative to increase the amount of mined land reclaimed to forest where appropriate. The authors are seeking to determine those elements of the Federal/State regulator programs that discourage reforestation and find ways to offset these impacts. Potential factors militating against reforestation are identified and possible solutions are discussed.

  14. Global Threat Reduction Initiative

    Office of Environmental Management (EM)

    The Current Status of Gap and U.S.-Origin Nuclear Fuel Removals 2011 Jeff Galan, Deputy Project Manager U.S.-Origin Nuclear Remove Program National Nuclear Security Administration Global Threat Reduction Initiative Defense Nuclear Nonproliferation U.S. DEPARTMENT OF ENERGY 2 GTRI Mission and Goals GTRI is: A part of President Obama's comprehensive strategy to prevent nuclear terrorism; and The key organization responsible for implementing the U.S. HEU minimization policy. GTRI MISSION Reduce

  15. Green Initiatives and Contracting

    Office of Environmental Management (EM)

    GSA Is Now Training Contracting Officers In Green Purchasing Green Purchasing for the Federal Acquisition Work Force * introduction to the federal green purchasing program * assists learners with identifying green products * discusses factors that shape federal green purchasing initiatives https://cae.gsa.gov 2 "There's some challenges here" "Environmental Aisle" in the GSA Advantage electronic-purchasing website for federal buyers to find green products Environmental

  16. Factors Impacting Decommissioning Costs - 13576

    SciTech Connect (OSTI)

    Kim, Karen; McGrath, Richard

    2013-07-01

    The Electric Power Research Institute (EPRI) studied United States experience with decommissioning cost estimates and the factors that impact the actual cost of decommissioning projects. This study gathered available estimated and actual decommissioning costs from eight nuclear power plants in the United States to understand the major components of decommissioning costs. Major costs categories for decommissioning a nuclear power plant are removal costs, radioactive waste costs, staffing costs, and other costs. The technical factors that impact the costs were analyzed based on the plants' decommissioning experiences. Detailed cost breakdowns by major projects and other cost categories from actual power plant decommissioning experiences will be presented. Such information will be useful in planning future decommissioning and designing new plants. (authors)

  17. Low Cost, Durable Seal

    SciTech Connect (OSTI)

    Roberts, George; Parsons, Jason; Friedman, Jake

    2010-12-17

    Seal durability is critical to achieving the 2010 DOE operational life goals for both stationary and transportation PEM fuel cell stacks. The seal material must be chemically and mechanically stable in an environment consisting of aggressive operating temperatures, humidified gases, and acidic membranes. The seal must also be producible at low cost. Currentlyused seal materials do not meet all these requirements. This project developed and demonstrated a high consistency hydrocarbon rubber seal material that was able to meet the DOE technical and cost targets. Significant emphasis was placed on characterization of the material and full scale molding demonstrations.

  18. Gulf Petro Initiative

    SciTech Connect (OSTI)

    Fathi Boukadi

    2011-02-05

    In this report, technologies for petroleum production and exploration enhancement in deepwater and mature fields are developed through basic and applied research by: (1) Designing new fluids to efficiently drill deepwater wells that can not be cost-effectively drilled with current technologies. The new fluids will be heavy liquid foams that have low-density at shallow dept to avoid formation breakdown and high density at drilling depth to control formation pressure. The goal of this project is to provide industry with formulations of new fluids for reducing casing programs and thus well construction cost in deepwater development. (2) Studying the effects of flue gas/CO{sub 2} huff n puff on incremental oil recovery in Louisiana oilfields bearing light oil. An artificial neural network (ANN) model will be developed and used to map recovery efficiencies for candidate reservoirs in Louisiana. (3) Arriving at a quantitative understanding for the three-dimensional controlled-source electromagnetic (CSEM) geophysical response of typical Gulf of Mexico hydrocarbon reservoirs. We will seek to make available tools for the qualitative, rapid interpretation of marine CSEM signatures, and tools for efficient, three-dimensional subsurface conductivity modeling.

  19. Parabolic Trough Reference Plant for Cost Modeling with the Solar Advisor Model (SAM)

    SciTech Connect (OSTI)

    Turchi, C.

    2010-07-01

    This report describes a component-based cost model developed for parabolic trough solar power plants. The cost model was developed by the National Renewable Energy Laboratory (NREL), assisted by WorleyParsons Group Inc., for use with NREL's Solar Advisor Model (SAM). This report includes an overview and explanation of the model, two summary contract reports from WorleyParsons, and an Excel spreadsheet for use with SAM. The cost study uses a reference plant with a 100-MWe capacity and six hours of thermal energy storage. Wet-cooling and dry-cooling configurations are considered. The spreadsheet includes capital and operating cost by component to allow users to estimate the impact of changes in component costs.

  20. Reducing the High Energy Costs of Alaska's Rural Water Systems

    Energy Savers [EERE]

    Reducing the High Energy Costs of Alaska's Rural Water Systems Gavin Dixon Senior Project Manager ANTHC Rural Energy Initiative The Alaska Native Tribal Health Consortium's (ANTHC) Rural Energy Initiative works with communities to implement innovative energy efficiency and renewable energy solutions to make public sanitation affordable for the people we serve across Alaska. Our Purpose ANTHC Rural Energy Initiative We believe basic sanitation should be efficient, sustainable and affordable The