Powered by Deep Web Technologies
Note: This page contains sample records for the topic "improvement project plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


1

SNF project engineering process improvement plan  

SciTech Connect (OSTI)

This Engineering Process Improvement Plan documents the activities and plans to be taken by the SNF Project to support its engineering process and to produce a consolidated set of engineering procedures that are fully compliant with the requirements of HNF-PRO-1819. All new procedures will be issued and implemented by September 30, 1999.

DESAI, S.P.

1999-07-13T23:59:59.000Z

2

SNF project engineering process improvement plan  

SciTech Connect (OSTI)

This Engineering Process Improvement Plan documents the activities and plans to be taken by the SNF Project (the Project) to support its engineering process and to produce a consolidated set of engineering procedures that are fully compliant with the requirements of HNF-PRO-1819 (1819). These requirements are imposed on all engineering activities performed for the Project and apply to all life-cycle stages of the Project's systems, structures and components (SSCs). This Plan describes the steps that will be taken by the Project during the transition period to ensure that new procedures are effectively integrated into the Project's work process as these procedures are issued. The consolidated procedures will be issued and implemented by September 30, 1999.

KELMENSON, R.L.

1999-05-24T23:59:59.000Z

3

SNF Project Engineering Process Improvement Plan  

SciTech Connect (OSTI)

This plan documents the SNF Project activities and plans to support its engineering process. It describes five SNF Project Engineering initiatives: new engineering procedures, qualification cards process; configuration management, engineering self assessments, and integrated schedule for engineering activities.

DESAI, S.P.

2000-02-09T23:59:59.000Z

4

Project Hanford management contract quality improvement project management plan  

SciTech Connect (OSTI)

On July 13, 1998, the U.S. Department of Energy, Richland Operations Office (DOE-RL) Manager transmitted a letter to Fluor Daniel Hanford, Inc. (FDH) describing several DOE-RL identified failed opportunities for FDH to improve the Quality Assurance (QA) Program and its implementation. In addition, DOE-RL identified specific Quality Program performance deficiencies. FDH was requested to establish a periodic reporting mechanism for the corrective action program. In a July 17, 1998 response to DOE-RL, FDH agreed with the DOE concerns and committed to perform a comprehensive review of the Project Hanford Management Contract (PHMC) QA Program during July and August, 1998. As a result, the Project Hanford Management Contract Quality Improvement Plan (QIP) (FDH-3508) was issued on October 21, 1998. The plan identified corrective actions based upon the results of an in-depth Quality Program Assessment. Immediately following the scheduled October 22, 1998, DOE Office of Enforcement and Investigation (EH-10) Enforcement Conference, FDH initiated efforts to effectively implement the QIP corrective actions. A Quality Improvement Project (QI Project) leadership team was assembled to prepare a Project Management Plan for this project. The management plan was specifically designed to engage a core team and the support of representatives from FDH and the major subcontractors (MSCs) to implement the QIP initiatives; identify, correct, and provide feedback as to the root cause for deficiency; and close out the corrective actions. The QI Project will manage and communicate progress of the process.

ADAMS, D.E.

1999-03-25T23:59:59.000Z

5

Columbia River Channel Improvement Project Rock Removal Blasting: Monitoring Plan  

SciTech Connect (OSTI)

This document provides a monitoring plan to evaluate take as outlined in the National Marine Fisheries Service 2002 Biological Opinion for underwater blasting to remove rock from the navigation channel for the Columbia River Channel Improvement Project. The plan was prepared by the Pacific Northwest National Laboratory (PNNL) for the U.S. Army Corps of Engineers (USACE), Portland District.

Carlson, Thomas J.; Johnson, Gary E.

2010-01-29T23:59:59.000Z

6

2010 Quality Assurance Improvement Project Plan | Department of Energy  

Energy Savers [EERE]

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious RankCombustionImprovement Awardflash2007-42attachment1.pdfmodule 4Department0 Quality Assurance Improvement

7

2012 Quality Assurance Improvement Project Plan | Department of Energy  

Energy Savers [EERE]

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious RankCombustionImprovement Awardflash2007-42attachment1.pdfmodule(EE)2012 Nuclear Energy2012 Quality Assurance

8

2014 Quality Assurance Improvement Project Plan | Department of Energy  

Energy Savers [EERE]

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious RankCombustionImprovement3 Beryllium-Associated Worker2014 House Nuclear Cleanup Caucus Oak RidgeLoadthe4

9

2015 Quality Assurance Improvement Project Plan | Department of Energy  

Energy Savers [EERE]

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious RankCombustionImprovement3 Beryllium-Associated Worker2014 HouseCoveredAirDepartment ofof EnergyEvents

10

Milestone Plan Process Improvement  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

Milestone Plan Process Improvement Milestone Plan Process Improvement Background In response to our community's concern over the milestone plan (MP) process within the system, the...

11

Improving DOE Project Performance Using the DOD Integrated Master Plan - 12481  

SciTech Connect (OSTI)

DOE O 413 measures a project's progress to plan by the consumption of funding, the passage of time, and the meeting of milestones. In March of 2003, then Under Secretary, Energy, Science, Card received a memo directing the implementation of Project Management and the Project Management Manual, including the Integrated Master Plan and Integrated Master Schedule. This directive states 'the integrated master plan and schedule tie together all project tasks by showing their logical relationships and any constraints controlling the start or finish of each task. This process results in a hierarchy of related functional and layered schedules derived from the Work Breakdown Structure that can be used for monitoring and controlling project progress'. This paper shows how restoring the IMP/IMS paradigm to DOE program management increases the probability of program success in ways not currently available using DOD O 413 processes alone. Using DOE O 413 series guidance, adding the Integrated Master Plan and Integrated Master Schedule paradigm would provide a hierarchical set of performance measures for each 'package of work,' that provides measurable visibility to the increasing maturity of the project. This measurable maturity provides the mechanism to forecast future performance of cost, schedule, and technical outcomes in ways not available using just the activities in DOE O 413. With this information project managers have another tool available to address the issues identified in GAO-07-336 and GAO-09-406. (authors)

Alleman, Glen B. [DOD Programs, Project Time and Cost (United States); Nosbisch, Michael R. [Managing Principle, Western Region, Project Time and Cost (United States)

2012-07-01T23:59:59.000Z

12

Planning the Project Meeting  

E-Print Network [OSTI]

Project group meetings must be planned well in advance. Members should be involved in completing some type of work before the next meeting. This helps the leader plan the next project meeting and makes efficient use of time....

Howard, Jeff W.

2005-05-10T23:59:59.000Z

13

DAF Glovebox Project Plan  

SciTech Connect (OSTI)

This document defines how the glovebox project will be managed and executed. It provides a path forward for establishing a glovebox capability in Building 341 of the DAF in time to meet JASPER programmatic requirements as the first user. Note that some elements of the glovebox project have been under way for some time and are more mature than others; other elements are being worked concurrently. This plan serves the following purposes: Assign organizational and individual responsibilities for bringing the glovebox capability online; Coordinate activities between organizations; Facilitate communication between project members and management; and Identify the mechanisms used to manage and control the project. The scope of this plan includes all activities conducted to achieve project objectives, culminating in DOE/NV approval to operate. This plan does not address the issues associated with the steady-state operation of the glovebox.

Martinez, M.W.; Higgs, R.L.

2000-11-14T23:59:59.000Z

14

Project Management Plans | Department of Energy  

Broader source: Energy.gov (indexed) [DOE]

Management Plans Project Management Plans The purpose here is to assist project managers and project planners in creating a project plan by providing examples and pointing to...

15

DIGITAL ARCHITECTURE PROJECT PLAN  

SciTech Connect (OSTI)

The objective of this project is to develop an industry consensus document on how to scope and implement the underlying information technology infrastructure that is needed to support a vast array of real-time digital technologies to improve NPP work efficiency, to reduce human error, to increase production reliability and to enhance nuclear safety. A consensus approach is needed because: • There is currently a wide disparity in nuclear utility perspectives and positions on what is prudent and regulatory-compliant for introducing certain digital technologies into the plant environment. For example, there is a variety of implementation policies throughout the industry concerning electromagnetic compatibility (EMC), cyber security, wireless communication coverage, mobile devices for workers, mobile technology in the control room, and so forth. • There is a need to effectively share among the nuclear operating companies the early experience with these technologies and other forms of lessons-learned. There is also the opportunity to take advantage of international experience with these technologies. • There is a need to provide the industry with a sense of what other companies are implementing, so that each respective company can factor this into their own development plans and position themselves to take advantage of new work methods as they are validated by the initial implementing companies. In the nuclear power industry, once a better work practice has been proven, there is a general expectation that the rest of the industry will adopt it. However, the long-lead time of information technology infrastructure could prove to be a delaying factor. A secondary objective of this effort is to provide a general understanding of the incremental investment that would be required to support the targeted digital technologies, in terms of an incremental investment over current infrastructure. This will be required for business cases to support the adoption of these new technologies.

Thomas, Ken

2014-09-01T23:59:59.000Z

16

Project Management Plan  

SciTech Connect (OSTI)

The mission of the Uranium Mill Tailings Remedial Action (UMTRA) Project is explicitly stated and directed in the Uranium Mill Tailings Radiation Control Act of 1978, Public Law 95-604, 42 USC 7901 (hereinafter referred to as the Act''). Title I of the Act authorizes the Department of Energy (DOE) to undertake remedial actions at 24 designated inactive uranium processing sites and associated vicinity properties containing uranium mill tailings and other residual radioactive materials derived from the processing sites. The Act, amended in January 1983, by Public Law 97-415, also authorizes DOE to perform remedial actions at vicinity properties in Edgemont, South Dakota. Cleanup of the Edgemont processing site is the responsibility of the Tennessee Valley Authority. This document describes the plan, organization, system, and methodologies used to manage the design, construction, and other activities required to clean up the designated sites and associated vicinity properties in accordance with the Act. The plan describes the objectives of the UMTRA Project, defines participants' roles and responsibilities, outlines the technical approach for accomplishing the objectives, and describes the planning and managerial controls to be used in integrating and performing the Project mission. 21 figs., 21 tabs.

Not Available

1988-01-01T23:59:59.000Z

17

NSTX Upgrade Project Project Execution Plan  

E-Print Network [OSTI]

NSTX Upgrade Project Project Execution Plan 6 PPPL Laboratory Director S.Prager Deputy Director.Gentile Centerstack Dsgn & Fab J. Chrzanowski NSTX Upgrade Project Manager R. Strykowsky Deputy and Construction Manager E. Perry Project Controls S. Langish NSTXCenterstack Manager L. Dudek NSTXNeutral Beam Manager T

Princeton Plasma Physics Laboratory

18

NSTX Upgrade Project Project Execution Plan  

E-Print Network [OSTI]

NSTX Upgrade Project Project Execution Plan Appendix 1 - WBS Dictionary 25 Appendix 1 - NSTX Upgrade Project Work Breakdown Structure This Work Breakdown Structure (WBS) organizes and defines the scope of the NSTX Upgrade using the WBS as established by the original NSTX project and modified

Princeton Plasma Physics Laboratory

19

NSTX Upgrade Project Execution Plan NSTX Upgrade Project  

E-Print Network [OSTI]

NSTX Upgrade Project Execution Plan NSTX Upgrade Project Project Execution Plan National Spherical Torus Experiment (NSTX) Upgrade Project Execution Plan Revision 1 October 6, 2011 Submitted by: R. Strykowsky NSTX Upgrade Project Manager _____________________________ M. Williams Associate Director, PPPL

Princeton Plasma Physics Laboratory

20

NSTX Upgrade Project Execution Plan NSTX Upgrade Project  

E-Print Network [OSTI]

NSTX Upgrade Project Execution Plan NSTX Upgrade Project Project Execution Plan National Spherical Torus Experiment (NSTX) Upgrade Project Execution Plan Revision 3 October 12, 2012 Administrative Change Submitted by: ______________________________ R. Strykowsky NSTX Upgrade Project Manager Anthony Indelicato

Princeton Plasma Physics Laboratory

Note: This page contains sample records for the topic "improvement project plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


21

Project Management Plan Solution Stabilization  

SciTech Connect (OSTI)

This plan presents the overall objectives, description, justification and planning for the Plutonium Finishing Plant (PFP) Solutions Stabilization subproject. The intent of this plan is to describe how this project will be managed and integrated with other facility stabilization and deactivation activities. This plan supplements the overall integrated plan presented in the Integrated Project Management Plan (IPMP) for the Plutonium Finishing Plant Stabilization and Deactivation Project, HNF-3617. This project plan is the top-level definitive project management document for the PFP Solution Stabilization subproject. It specifies the technical, schedule, requirements and the cost baselines to manage the execution of the Solution Stabilization subproject. Any deviations to the document must be authorized through the appropriate change control process.

SATO, P.K.

1999-08-31T23:59:59.000Z

22

SOFTWARE QUALITY & SYSTEMS ENGINEERING PROGRAM: Project Planning...  

Broader source: Energy.gov (indexed) [DOE]

PROGRAM: Project Planning Checklist SOFTWARE QUALITY & SYSTEMS ENGINEERING PROGRAM: Project Planning Checklist The following checklist is intended to provide system owners, project...

23

National Ignition Facility project execution plan  

SciTech Connect (OSTI)

This project execution plan covers: Justification of Mission Need; Project Description; Management Roles and Responsibilities; Project Execution; Method of Accomplishment.

Paisner, J., LLNL

1997-08-01T23:59:59.000Z

24

NSTX Upgrade Project Execution Plan NSTX Upgrade Project  

E-Print Network [OSTI]

#12;#12;NSTX Upgrade Project Execution Plan NSTX Upgrade Project Project Execution Plan i Record;NSTX Upgrade Project Execution Plan NSTX Upgrade Project Project Execution Plan ii Table of Contents 1 ..............................................................................................................................1 1.2.1 DOE-approved project documents

Princeton Plasma Physics Laboratory

25

NSTX Upgrade Project Execution Plan NSTX Upgrade Project  

E-Print Network [OSTI]

#12;NSTX Upgrade Project Execution Plan NSTX Upgrade Project Project Execution Plan i Record/schedule baseline updates #12;NSTX Upgrade Project Execution Plan NSTX Upgrade Project Project Execution Plan ii ..............................................................................................................................1 1.2.1 DOE-approved project documents

Princeton Plasma Physics Laboratory

26

Roadway Improvement Project Cost Allocation  

E-Print Network [OSTI]

Roadway Improvement Project Cost Allocation CTS 21st Annual Transportation Research Conference costs #12;Potential Applications · Roadway Project Feasibility Studies ­ Identified potential roadway infrastructure improvement ­ Documentation of estimated project costs ­ Determine property assessments

Minnesota, University of

27

Material Stabilization Project Management Plan  

SciTech Connect (OSTI)

This plan presents the overall objectives, description, justification and planning for the plutonium Finishing Plant (PFP) Materials Stabilization project. The intent of this plan is to describe how this project will be managed and integrated with other facility stabilization and deactivation activities. This plan supplements the overall integrated plan presented in the Plutonium Finishing Plant Integrated Project Management Plan (IPMP), HNF-3617, Rev. 0. This is the top-level definitive project management document that specifies the technical (work scope), schedule, and cost baselines to manager the execution of this project. It describes the organizational approach and roles/responsibilities to be implemented to execute the project. This plan is under configuration management and any deviations must be authorized by appropriate change control action. Materials stabilization is designated the responsibility to open and stabilize containers of plutonium metal, oxides, alloys, compounds, and sources. Each of these items is at least 30 weight percent plutonium/uranium. The output of this project will be containers of materials in a safe and stable form suitable for storage pending final packaging and/or transportation offsite. The corrosion products along with oxides and compounds will be stabilized via muffle furnaces to reduce the materials to high fired oxides.

SPEER, D.R.

1999-09-01T23:59:59.000Z

28

River Protection Project (RPP) Environmental Program Plan  

SciTech Connect (OSTI)

This Environmental Program Plan was developed in support of the Integrated Environment, Safety, and Health Management System Plan (ISMS) (RPP-MP-003), which establishes a single, defined environmental, safety, and health management system that integrates requirements into the work planning and execution processes to protect workers, the public, and the environment. The ISMS also provides mechanisms for increasing worker involvement in work planning, including hazard and environmental impact identification, analysis, and control; work execution; and feedback/improvement processes. The ISMS plan consists of six core functions. Each section of this plan describes the activities of the River Protection Project (RPP) (formerly known as the Tank Waste Remediation System) Environmental organization according to the following core functions: Establish Environmental Policy; Define the Scope of Work; Identify Hazards, Environmental Impacts, and Requirements; Analyze Hazards and Environmental Impacts and Implement Controls; Perform Work within Controls; and Provide Feedback and Continuous Improvement.

POWELL, P.A.

2000-03-29T23:59:59.000Z

29

PROJECT PLANNING TEMPLATE  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

on public affairs efforts, which includes public information activities, press and media services, DOE home-page content, speaking engagements, special projects, internal...

30

Renewable Energy Project Planning and Implementation | Department...  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

Planning and Implementation Renewable Energy Project Planning and Implementation Federal renewable energy projects can be large or small and managed by a third-party or the agency....

31

Project Management Plan Resident Management System (RMS)  

E-Print Network [OSTI]

1 Project Management Plan Resident Management System (RMS) And Quality Control System (QCS Resident Management System.........................................................................................................3 Project Management Plan - Purpose

US Army Corps of Engineers

32

Business Continuity Project Project Summary: Develop Business Continuity Plans for all critical functional areas of  

E-Print Network [OSTI]

Business Continuity Project Project Summary: Develop Business Continuity Plans for all critical functional areas of the corporation. Project Requirements: Individual and Corporate plans that allow organization- · Integrate stand-by generator into plans- · Improve evacuation procedures- · Integrate other

33

River Protection Project (RPP) Project Management Plan  

SciTech Connect (OSTI)

The Office of River Protection (ORP) Project Management Plan (PMP) for the River Protection Project (RPP) describes the process for developing and operating a Waste Treatment Complex (WTC) to clean up Hanford Site tank waste. The Plan describes the scope of the project, the institutional setting within which the project must be completed, and the management processes and structure planned for implementation. The Plan is written from the perspective of the ORP as the taxpayers' representative. The Hanford Site, in southeastern Washington State, has one of the largest concentrations of radioactive waste in the world, as a result of producing plutonium for national defense for more than 40 years. Approximately 53 million gallons of waste stored in 177 aging underground tanks represent major environmental, social, and political challenges for the U.S. Department of Energy (DOE). These challenges require numerous interfaces with state and federal environmental officials, Tribal Nations, stakeholders, Congress, and the US Department of Energy-Headquarters (DOE-HQ). The cleanup of the Site's tank waste is a national issue with the potential for environmental and economic impacts to the region and the nation.

NAVARRO, J.E.

2001-03-07T23:59:59.000Z

34

NSTX Upgrade Project Execution Plan NSTX Upgrade Project  

E-Print Network [OSTI]

#12;NSTX Upgrade Project Execution Plan NSTX Upgrade Project Project Execution Plan i Record 10/12/2012 Update to WBS Level 2 Threshold (top of page 20), Change DOE Federal Project Director and Deputy Federal Project Director. Various OBS changes. #12;NSTX Upgrade Project Execution Plan NSTX

Princeton Plasma Physics Laboratory

35

Project Execution Plan, Rev. 3  

SciTech Connect (OSTI)

This plan addresses project activities encompassed by the U.S. Department of Energy's (DOE's), National Nuclear Security Administration Nevada Operations Office, Environmental Restoration Division and conforms to the requirements contained in the Life-Cycle Asset Management, DOE Order 430.1A; The Joint Program Office Policy on Project Management in Support of DOE Order 430.1; Program and Project Management for the Acquisition of Capital Assets, DOE Order 413.3; the Project Execution and Engineering Management Planning Guide, GPG-FM-010; and other applicable Good Practice Guides; and the FY 2001 Integrated Planning, Accountability, and Budgeting System Policy Guidance. The plan also reflects the milestone philosophies of the Federal Facility Agreement and Consent Order, as agreed to by the State of Nevada, the DOE, and the U.S. Department of Defense; and traditional project management philosophies such as the development of life-cycle costs, schedules, and work scope; identification o f roles and responsibilities; and baseline management and controls.

IT Corporation, Las Vegas

2002-08-01T23:59:59.000Z

36

RIVER PROTECTION PROJECT SYSTEM PLAN  

SciTech Connect (OSTI)

The U.S. Department of Energy (DOE), Office of River Protection (ORP) manages the River Protection Project (RPP). The RPP mission is to retrieve and treat Hanford's tank waste and close the tank farms to protect the Columbia River. As a result, ORP is responsible for the retrieval, treatment, and disposal of approximately 57 million gallons 1 of radioactive waste contained in the Hanford Site waste tanks and closure2 of all the tanks and associated facilities. The previous revision of the System Plan was issued in May 2008. ORP has made a number of changes to the tank waste treatment strategy and plans since the last revision of this document, and additional changes are under consideration. ORP has contracts in place to implement the strategy for completion of the mission and establish the capability to complete the overall mission. The current strategl involves a number of interrelated activities. ORP will reduce risk to the environment posed by tank wastes by the following: (1) Retrieving the waste from the single-shell tanks (SST) to double-shell tanks (DST) and delivering the waste to the Waste Treatment and Immobilization Plant (WTP). (2) Constructing and operating the WTP, which will safely treat all of the high-level waste (HLW) fraction contained in the tank farms. About one-third of the low-activity waste (LAW) fraction separated from the HLW fraction in the WTP will be immobilized in the WTP LAW Vitrification Facility. (3) Developing and deploying supplemental treatment capability assumed to be a second LAW vitrification facility that can safely treat about two-thirds of the LAW contained in the tank farms. (4) Developing and deploying supplemental pretreatment capability currently assumed to be an Aluminum Removal Facility (ARF) using a lithium hydrotalcite process to mitigate sodium management issues. (5) Developing and deploying treatment and packaging capability for contact-handled transuranic (CH-TRU) tank waste for possible shipment to and disposal at the Waste Isolation Pilot Plant (WIPP) in New Mexico. (6) Deploying interim storage capacity for the immobilized high-level waste (IHLW) pending determination of the final disposal pathway. (7) Closing the SST and DST tank farms, ancillary facilities, and all associated waste management and treatment facilities. (8) Optimizing the overall mission by resolution of technical and programmatic uncertainties, configuring the tank farms to provide a steady, well-balanced feed to the WTP, and performing trade-offs of the required amount and type of supplemental treatment and of the amount of HLW glass versus LAW glass. ORP has made and continues to make modifications to the WTP contract as needed to improve projected plant performance and address known or emerging risks. Key elements needed to implement the strategy described above are included within the scope of the Tank Operations Contract (TOC). Interim stabilization of the SSTs was completed in March 2004. As of April 2009, retrieval of seven SSTs has been completed and retrieval of four additional SSTs has been completed to the limits of technology. Demonstration of supplemental LAW treatment technologies has stopped temporarily pending revision of mission need requirements. Award of a new contract for tank operations (TOC), the ongoing tank waste retrieval experience, HLW disposal issues, and uncertainties in waste feed delivery and waste treatment led to the revision of the Performance Measurement Baseline (PM B), which is currently under review prior to approval. 6 This System Plan is aligned with the current WTP schedule, with hot commissioning beginning in 2018, and full operations beginning in late 2019. Major decisions regarding the use of supplemental treatment and the associated technology, the ultimate needed capacity, and its relationship to the WTP have not yet been finalized. This System Plan assumes that the outcome of these decisions will be to provide a second LAW vitrification facility. No final implementation decisions regarding supplemental technology can be made until the Tank Closure and

CERTA PJ; KIRKBRIDE RA; HOHL TM; EMPEY PA; WELLS MN

2009-09-15T23:59:59.000Z

37

RIVER PROTECTION PROJECT SYSTEM PLAN  

SciTech Connect (OSTI)

The U.S. Department of Energy (DOE), Office of River Protection (ORP) manages the River Protection Project (RPP). The RPP mission is to retrieve and treat Hanford's tank waste and close the tank farms to protect the Columbia River. As a result, the ORP is responsible for the retrieval, treatment, and disposal of the approximately 57 million gallons of radioactive waste contained in the Hanford Site waste tanks and closure of all the tanks and associated facilities. The previous revision of the System Plan was issued in September 2003. ORP has approved a number of changes to the tank waste treatment strategy and plans since the last revision of this document, and additional changes are under consideration. The ORP has established contracts to implement this strategy to establish a basic capability to complete the overall mission. The current strategy for completion of the mission uses a number of interrelated activities. The ORP will reduce risk to the environment posed by tank wastes by: (1) Retrieving the waste from the single-shell tanks (SST) to double-shell tanks (DST) for treatment and disposal; (2) Constructing and operating the WTP, which will safely treat all of the high-level waste (HLW) and about half of the low-activity waste (LAW) contained in the tank farms, and maximizing its capability and capacity; (3) Developing and deploying supplemental treatment capability or a second WTP LAW Facility that can safely treat about half of the LAW contained in the tank farms; (4) Developing and deploying treatment and packaging capability for transuranic (TRU) tank waste for shipment to and disposal at the Waste Isolation Pilot Plant (WIPP); (5) Deploying interim storage capacity for the immobilized HLW and shipping that waste to Yucca Mountain for disposal; (6) Operating the Integrated Disposal Facility for the disposal of immobilized LAW, along with the associated secondary waste, (7) Closing the SST and DST tank farms, ancillary facilities, and al1 waste management and treatment facilities, (8) Developing and implementing technical solutions to mitigate the impact from substantial1y increased estimates of Na added during the pretreatment of the tank waste solids, This involves a combination of: (1) refining or modifying the flowsheet to reduce the required amount of additional sodium, (2) increasing the overall LAW vitrification capacity, (3) increasing the incorporation of sodium into the LAW glass, or (4) accepting an increase in mission duration, ORP has made and continues to make modifications to the WTP contract as needed to improve projected plant performance and address known or emerging risks, Key elements of the implementation of this strategy are included within the scope of the Tank Operations Contract, currently in procurement Since 2003, the ORP has conducted over 30 design oversight assessments of the Waste Treatment and Immobilization Plant (WTP). The estimated cost at completion has increased and the schedule for construction and commissioning of the WTP has extended, The DOE, Office of Environmental Management (EM), sanctioned a comprehensive review of the WTP flowsheet, focusing on throughput. In 2005, the TFC completed interim stabilization of the SSTs and as of March 2007, has completed the retrieval of seven selected SSTs. Demonstration of supplemental treatment technologies continues. The ongoing tank waste retrieval experience, progress with supplemental treatment technologies, and changes in WTP schedule led to the FY 2007 TFC baseline submittal in November 2006. The TFC baseline submittal was developed before the WTP schedule was fully understood and approved by ORP, and therefore reflects an earlier start date for the WTP facilities. This System Plan is aligned with the current WTP schedule with hot commissioning beginning in 2018 and full operations beginning in 2019. Major decisions regarding the use of supplemental treatment and the associated technology, the ultimate needed capacity, and its relationship to the WTP have not yet been finalized. This System Plan assumes that the outcome of

CERTA PJ

2008-07-10T23:59:59.000Z

38

PROJECT PLANNING TEMPLATE | Department of Energy  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

PLANNING TEMPLATE PROJECT PLANNING TEMPLATE More Documents & Publications Proposed Data Elements for PARS II Web Application Slide 1 Critical Decision 2 (CD-2) Approval Template...

39

UMTRA Project value engineering plan  

SciTech Connect (OSTI)

The objective of value engineering (VE) on the Uranium MILL Tailings Remedial Action (UMTRA) Project is to ensure that remedial action at the UMTRA Project sites is performed to meet the US Environmental Protection Agency (EPA) standards for inactive uranium mill tailings sites at the lowest cost, while maintaining a high quality of work. Through review of designs and consideration of reasonable, less expensive alternatives, VE can be an effective cost reduction tool and a means to improve the design. The UMTRA Project products are the design and construction of stabilized tailings embankments.

Not Available

1990-06-01T23:59:59.000Z

40

Project Execution Plan Electron Beam Ion Source Project  

E-Print Network [OSTI]

Project Execution Plan for the Electron Beam Ion Source Project (EBIS) Project # 07-SC-02 at Brookhaven National Laboratory Upton, NY For the U.S. Department of Energy Office of Science Office of Nuclear Physics (SC ­ 26) Rev. 1 May 2008 #12;#12;#12;4 Project Execution Plan for the Electron Beam Ion

Note: This page contains sample records for the topic "improvement project plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


41

SAPHIRE 8 Software Project Plan  

SciTech Connect (OSTI)

This project is being conducted at the request of the DOE and the NRC. The INL has been requested by the NRC to improve and maintain the Systems Analysis Programs for Hands-on Integrated Reliability Evaluation (SAPHIRE) tool set concurrent with the changing needs of the user community as well as staying current with new technologies. Successful completion will be upon NRC approved release of all software and accompanying documentation in a timely fashion. This project will enhance the SAPHIRE tool set for the user community (NRC, Nuclear Power Plant operations, Probabilistic Risk Analysis (PRA) model developers) by providing improved Common Cause Failure (CCF), External Events, Level 2, and Significance Determination Process (SDP) analysis capabilities. The SAPHIRE development team at the Idaho National Laboratory is responsible for successful completion of this project. The project is under the supervision of Curtis L. Smith, PhD, Technical Lead for the SAPHIRE application. All current capabilities from SAPHIRE version 7 will be maintained in SAPHIRE 8. The following additional capabilities will be incorporated: • Incorporation of SPAR models for the SDP interface. • Improved quality assurance activities for PRA calculations of SAPHIRE Version 8. • Continue the current activities for code maintenance, documentation, and user support for the code.

Curtis L.Smith; Ted S. Wood

2010-03-01T23:59:59.000Z

42

Industrial Energy Efficiency Projects Improve Competitiveness...  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

Industrial Energy Efficiency Projects Improve Competitiveness and Protect Jobs Industrial Energy Efficiency Projects Improve Competitiveness and Protect Jobs U.S. Department of...

43

Quality Assurance Project Plan for Facility Effluent Monitoring Plan activities  

SciTech Connect (OSTI)

This Quality Assurance Project Plan addresses the quality assurance requirements for the Facility Monitoring Plans of the overall site-wide environmental monitoring plan. This plan specifically applies to the sampling and analysis activities and continuous monitoring performed for all Facility Effluent Monitoring Plan activities conducted by Westinghouse Hanford Company. It is generic in approach and will be implemented in conjunction with the specific requirements of individual Facility Effluent Monitoring Plans. This document is intended to be a basic road map to the Facility Effluent Monitoring Plan documents (i.e., the guidance document for preparing Facility Effluent Monitoring Plans, Facility Effluent Monitoring Plan determinations, management plan, and Facility Effluent Monitoring Plans). The implementing procedures, plans, and instructions are appropriate for the control of effluent monitoring plans requiring compliance with US Department of Energy, US Environmental Protection Agency, state, and local requirements. This Quality Assurance Project Plan contains a matrix of organizational responsibilities, procedural resources from facility or site manuals used in the Facility Effluent Monitoring Plans, and a list of the analytes of interest and analytical methods for each facility preparing a Facility Effluent Monitoring Plan. 44 refs., 1 figs., 2 tabs.

Nickels, J.M.

1991-06-01T23:59:59.000Z

44

The CHPRC Columbia River Protection Project Quality Assurance Project Plan  

SciTech Connect (OSTI)

Pacific Northwest National Laboratory researchers are working on the CHPRC Columbia River Protection Project (hereafter referred to as the Columbia River Project). This is a follow-on project, funded by CH2M Hill Plateau Remediation Company, LLC (CHPRC), to the Fluor Hanford, Inc. Columbia River Protection Project. The work scope consists of a number of CHPRC funded, related projects that are managed under a master project (project number 55109). All contract releases associated with the Fluor Hanford Columbia River Project (Fluor Hanford, Inc. Contract 27647) and the CHPRC Columbia River Project (Contract 36402) will be collected under this master project. Each project within the master project is authorized by a CHPRC contract release that contains the project-specific statement of work. This Quality Assurance Project Plan provides the quality assurance requirements and processes that will be followed by the Columbia River Project staff.

Fix, N. J.

2008-11-30T23:59:59.000Z

45

Uranium Mill Tailings Remedial Action Project surface project management plan  

SciTech Connect (OSTI)

This Project Management Plan describes the planning, systems, and organization that shall be used to manage the Uranium Mill Tailings Remedial Action Project (UMTRA). US DOE is authorized to stabilize and control surface tailings and ground water contamination at 24 inactive uranium processing sites and associated vicinity properties containing uranium mill tailings and related residual radioactive materials.

Not Available

1994-09-01T23:59:59.000Z

46

UMTRA Project: Environment, Safety, and Health Plan  

SciTech Connect (OSTI)

The US Department of Energy has prepared this UMTRA Project Environment, Safety, and Health (ES and H) Plan to establish the policy, implementing requirements, and guidance for the UMTRA Project. The requirements and guidance identified in this plan are designed to provide technical direction to UMTRA Project contractors to assist in the development and implementation of their ES and H plans and programs for UMTRA Project work activities. Specific requirements set forth in this UMTRA Project ES and H Plan are intended to provide uniformity to the UMTRA Project`s ES and H programs for processing sites, disposal sites, and vicinity properties. In all cases, this UMTRA Project ES and H Plan is intended to be consistent with applicable standards and regulations and to provide guidance that is generic in nature and will allow for contractors` evaluation of site or contract-specific ES and H conditions. This plan specifies the basic ES and H requirements applicable to UMTRA Project ES and H programs and delineates responsibilities for carrying out this plan. DOE and contractor ES and H personnel are expected to exercise professional judgment and apply a graded approach when interpreting these guidelines, based on the risk of operations.

Not Available

1995-02-01T23:59:59.000Z

47

Project Plan UC Online Education (UCOE)  

E-Print Network [OSTI]

of Contents I. PROJECT DESCRIPTION II. COST REVENUE MODEL AND FINANCIAL FORECAST III. INCENTIVES1 Project Plan UC Online Education (UCOE) March 24, 2011 Office of the President SUPPORTING CAMPUS AND FACULTY PARTICIPATION IV. RISKS AND RISK MANAGEMENT V. PROJECT ORGANIZATION

Becker, Luann

48

FIRE Project Action Plan in Response to  

E-Print Network [OSTI]

. The project should review other mission statements from the Office of Science in order to understand better, the Next Generation Space Telescope, etc. The project will also solicit input from the science community1 FIRE Project Action Plan in Response to Next Step Options Program Advisory Committee Report (PAC1

49

Project Management Plan Examples 1- 80  

Broader source: Energy.gov [DOE]

The following material has been extracted from several project management plans. The order in which it is presented is arbitrary. The descriptions below should be used to navigate to the subject of...

50

River Protection Project System Plan  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

gallons (Mgal) 1 closure of radioactive waste contained in the Hanford Site waste tanks and 2 This version of the RPP System Plan (Rev. 6) is a major update of the previous...

51

2011 ANNUAL PLANNING SUMMARY FOR ADVANCED RESEARCH AND PROJECTS...  

Office of Environmental Management (EM)

1 ANNUAL PLANNING SUMMARY FOR ADVANCED RESEARCH AND PROJECTS AGENCY WESTERN AREA POWER ADMINISTRATION 2011 ANNUAL PLANNING SUMMARY FOR ADVANCED RESEARCH AND PROJECTS AGENCY WESTERN...

52

Improving Lives. Improving Texas. Agency Strategic Plan  

E-Print Network [OSTI]

. Williams Administration Building 7101 TAMU September 2009 College Station, TX 77843-7101 Phone: 979. In the context of this broad mission, the priorities for Extension education are: Ensure a sustainable and management. Build local capacity for economic development in Texas communities. Improve the health

53

24 Command Fire Improvement Action Program Plan  

SciTech Connect (OSTI)

Fluor Hanford (FH) is responsible for providing support to the Department of Energy Richland Operations Office (RL) in the implementation of the Hanford Emergency Preparedness (EP) program. During fiscal year 2000, a number of program improvements were identified from various sources including a major range fire (24 Command Fire). Evaluations of the emergency preparedness program have confirmed that it currently meets all requirements and that performance of personnel involved is good, however the desire to effect continuous improvement resulted in the development of this improvement program plan. This program plan defines the activities that will be performed in order to achieve the desired performance improvements.

GRIFFIN, G.B.

2000-12-01T23:59:59.000Z

54

Audio-Visual Biofeedback Does Not Improve the Reliability of Target Delineation Using Maximum Intensity Projection in 4-Dimensional Computed Tomography Radiation Therapy Planning  

SciTech Connect (OSTI)

Purpose: To investigate whether coaching patients' breathing would improve the match between ITV{sub MIP} (internal target volume generated by contouring in the maximum intensity projection scan) and ITV{sub 10} (generated by combining the gross tumor volumes contoured in 10 phases of a 4-dimensional CT [4DCT] scan). Methods and Materials: Eight patients with a thoracic tumor and 5 patients with an abdominal tumor were included in an institutional review board-approved prospective study. Patients underwent 3 4DCT scans with: (1) free breathing (FB); (2) coaching using audio-visual (AV) biofeedback via the Real-Time Position Management system; and (3) coaching via a spirometer system (Active Breathing Coordinator or ABC). One physician contoured all scans to generate the ITV{sub 10} and ITV{sub MIP}. The match between ITV{sub MIP} and ITV{sub 10} was quantitatively assessed with volume ratio, centroid distance, root mean squared distance, and overlap/Dice coefficient. We investigated whether coaching (AV or ABC) or uniform expansions (1, 2, 3, or 5 mm) of ITV{sub MIP} improved the match. Results: Although both AV and ABC coaching techniques improved frequency reproducibility and ABC improved displacement regularity, neither improved the match between ITV{sub MIP} and ITV{sub 10} over FB. On average, ITV{sub MIP} underestimated ITV{sub 10} by 19%, 19%, and 21%, with centroid distance of 1.9, 2.3, and 1.7 mm and Dice coefficient of 0.87, 0.86, and 0.88 for FB, AV, and ABC, respectively. Separate analyses indicated a better match for lung cancers or tumors not adjacent to high-intensity tissues. Uniform expansions of ITV{sub MIP} did not correct for the mismatch between ITV{sub MIP} and ITV{sub 10}. Conclusions: In this pilot study, audio-visual biofeedback did not improve the match between ITV{sub MIP} and ITV{sub 10}. In general, ITV{sub MIP} should be limited to lung cancers, and modification of ITV{sub MIP} in each phase of the 4DCT data set is recommended.

Lu, Wei, E-mail: wlu@umm.edu [Department of Radiation Oncology, University of Maryland School of Medicine, Baltimore, Maryland (United States); Neuner, Geoffrey A.; George, Rohini; Wang, Zhendong; Sasor, Sarah [Department of Radiation Oncology, University of Maryland School of Medicine, Baltimore, Maryland (United States); Huang, Xuan [Research and Development, Care Management Department, Johns Hopkins HealthCare LLC, Glen Burnie, Maryland (United States); Regine, William F.; Feigenberg, Steven J.; D'Souza, Warren D. [Department of Radiation Oncology, University of Maryland School of Medicine, Baltimore, Maryland (United States)

2014-01-01T23:59:59.000Z

55

Wind Forecast Improvement Project Southern Study Area Final Report...  

Office of Environmental Management (EM)

Wind Forecast Improvement Project Southern Study Area Final Report Wind Forecast Improvement Project Southern Study Area Final Report Wind Forecast Improvement Project Southern...

56

Project Management Plan (PMP) for International Atomic Energy Agency (IAEA) Safeguards Project  

SciTech Connect (OSTI)

This plan presents the overall objectives, description, justification and planning for the PFP IAEA project. The intent of this plan is to describe how this project will be managed and integrated with other facility stabilization and deactivation activities. This plan supplements the overall integrated plan presented in the Plutonium Finishing Plant Integrated Project Management Plan (IPMP) HNF-3617 Rev 0.

BARTLETT, W.D.

1999-09-14T23:59:59.000Z

57

The Groundwater Performance Assessment Project Quality Assurance Plan  

SciTech Connect (OSTI)

U.S. Department of Energy (DOE) has monitored groundwater on the Hanford Site since the 1940s to help determine what chemical and radiological contaminants have made their way into the groundwater. As regulatory requirements for monitoring increased in the 1980s, there began to be some overlap between various programs. DOE established the Groundwater Performance Assessment Project (groundwater project) in 1996 to ensure protection of the public and the environment while improving the efficiency of monitoring activities. The groundwater project is designed to support all groundwater monitoring needs at the site, eliminate redundant sampling and analysis, and establish a cost-effective hierarchy for groundwater monitoring activities. This document provides the quality assurance guidelines that will be followed by the groundwater project. This QA Plan is based on the QA requirements of DOE Order 414.1C, Quality Assurance, and 10 CFR 830, Subpart A--General Provisions/Quality Assurance Requirements as delineated in Pacific Northwest National Laboratory’s Standards-Based Management System. In addition, the groundwater project is subject to the Environmental Protection Agency (EPA) Requirements for Quality Assurance Project Plans (EPA/240/B-01/003, QA/R-5). The groundwater project has determined that the Hanford Analytical Services Quality Assurance Requirements Documents (HASQARD, DOE/RL-96-68) apply to portions of this project and to the subcontractors. HASQARD requirements are discussed within applicable sections of this plan.

Luttrell, Stuart P.

2006-05-11T23:59:59.000Z

58

Energy Strategic Planning & Sufficiency Project  

SciTech Connect (OSTI)

This report provides information regarding options available, their advantages and disadvantages, and the costs for pursuing activities to advance Smith River Rancheria toward an energy program that reduces their energy costs, allows greater self-sufficiency and stimulates economic development and employment opportunities within and around the reservation. The primary subjects addressed in this report are as follows: (1) Baseline Assessment of Current Energy Costs--An evaluation of the historical energy costs for Smith River was conducted to identify the costs for each component of their energy supply to better assess changes that can be considered for energy cost reductions. (2) Research Viable Energy Options--This includes a general description of many power generation technologies and identification of their relative costs, advantages and disadvantages. Through this research the generation technology options that are most suited for this application were identified. (3) Project Development Considerations--The basic steps and associated challenges of developing a generation project utilizing the selected technologies are identified and discussed. This included items like selling to third parties, wheeling, electrical interconnections, fuel supply, permitting, standby power, and transmission studies. (4) Energy Conservation--The myriad of federal, state and utility programs offered for low-income weatherization and utility bill payment assistance are identified, their qualification requirements discussed, and the subsequent benefits outlined. (5) Establishing an Energy Organization--The report includes a high level discussion of formation of a utility to serve the Tribal membership. The value or advantages of such action is discussed along with some of the challenges. (6) Training--Training opportunities available to the Tribal membership are identified.

Retziaff, Greg

2005-03-30T23:59:59.000Z

59

Project L-070, ``300 Area process sewer piping system upgrade`` Project Management Plan  

SciTech Connect (OSTI)

This document is the project management plan for Project L-070, 300 Area process sewer system upgrades.

Wellsfry, H.E.

1994-09-16T23:59:59.000Z

60

National Ignition Facility project acquisition plan  

SciTech Connect (OSTI)

The purpose of this National Ignition Facility Acquisition Plan is to describe the overall procurement strategy planned for the National Ignition Facility (NIF) Project. The scope of the plan describes the procurement activities and acquisition strategy for the following phases of the NIF Project, each of which receives either plant and capital equipment (PACE) or other project cost (OPC) funds: Title 1 and 2 design and Title 3 engineering (PACE); Optics manufacturing facilitization and pilot production (OPC); Convention facility construction (PACE); Procurement, installation, and acceptance testing of equipment (PACE); and Start-up (OPC). Activities that are part of the base Inertial Confinement Fusion (ICF) Program are not included in this plan. The University of California (UC), operating Lawrence Livermore National Laboratory (LLNL) and Los Alamos National Laboratory, and Lockheed-Martin, which operates Sandia National Laboratory (SNL) and the University of Rochester Laboratory for Laser Energetics (UR-LLE), will conduct the acquisition of needed products and services in support of their assigned responsibilities within the NIF Project structure in accordance with their prime contracts with the Department of Energy (DOE). LLNL, designated as the lead Laboratory, will have responsibility for all procurements required for construction, installation, activation, and startup of the NIF.

Callaghan, R.W.

1996-04-01T23:59:59.000Z

Note: This page contains sample records for the topic "improvement project plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


61

PROJECT SCHEDULING: IMPROVED APPROACH TO INCORPORATE  

E-Print Network [OSTI]

] project scheduling inevitably involves uncertainty. The basic inputs (i.e., time, cost, and resourcesPROJECT SCHEDULING: IMPROVED APPROACH TO INCORPORATE UNCERTAINTY USINC BAYESIAN NETWORKS VAHID, there is a causal relationship between these uncertainty sources and project parameters; this causality

Neil, Martin

62

FY 1991 project plan for the Hanford Environmental Dose Reconstruction Project, Phase 2  

SciTech Connect (OSTI)

Phase 1 of the Hanford Environmental Dose Reconstruction Project was designed to develop and demonstrate a method for estimating radiation doses people may have received from Hanford Site operations since 1944. The method researchers developed relied on a variety of measured and reconstructed data as input to a modular computer model that generates dose estimates and their uncertainties. As part of Phase 1, researchers used the reconstructed data and computer model to calculate preliminary dose estimates for populations in a limited geographical area and time period. Phase 2, now under way, is designed to evaluate the Phase 1 data and model and improve them to calculate more accurate and precise dose estimates. Phase 2 will also be used to obtain preliminary estimates of two categories of doses: for Native American tribes and for individuals included in the pilot phase of the Hanford Thyroid Disease Study (HTDS). TSP Directive 90-1 required HEDR staff to develop Phase 2 task plans for TSP approval. Draft task plans for Phase 2 were submitted to the TSP at the October 11--12, 1990 public meeting, and, after discussions of each activity and associated budget needs, the TSP directed HEDR staff to proceed with a slate of specific project activities for FY 1991 of Phase 2. This project plan contains detailed information about those activities. Phase 2 is expected to last 15--18 months. In mid-FY 1991, project activities and budget will be reevaluated to determine whether technical needs or priorities have changed. Separate from, but related to, this project plan, will be an integrated plan for the remainder of the project. HEDR staff will work with the TSP to map out a strategy that clearly describes end products'' for the project and the work necessary to complete them. This level of planning will provide a framework within which project decisions in Phases 2, 3, and 4 can be made.

Not Available

1991-02-01T23:59:59.000Z

63

Project management plan for Project W-320, Tank 241-C-106 sluicing  

SciTech Connect (OSTI)

This Project Management Plan establishes the organization, plans, and systems for management of Project W-320 as defined in DOE Order 4700.1, Project Management System (DOE 1987).

Phillips, D.R.

1994-12-01T23:59:59.000Z

64

Department of Energy Guide for Project Execution Plans  

Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

This directive provides guidance for the federal project director to produce a useful and flexible plan. No cancellation.

2008-09-12T23:59:59.000Z

65

Continuous Improvement Energy Projects Reduce Energy Consumption  

E-Print Network [OSTI]

Continuous Improvement Energy Projects Reduce Energy Consumption Eric Niemeyer, Operations Superintendent Drilling Specialties Company A division of Chevron Phillips Chemical Company LP ESL-IE-14-05-31 Proceedings of the Thrity...

Niemeyer, E.

2014-01-01T23:59:59.000Z

66

Project management improves well control events  

SciTech Connect (OSTI)

During a well control operation, the efficient use of personnel and equipment, through good project management techniques, contributes to increased safety and ensures a quality project. The key to a successful blowout control project is to use all resources in the most efficient manner. Excessive use of resources leads to unnecessary expenditures and delays in bringing the project under control. The Kuwait well control project, which involved more than 700 blowouts, was accomplished in a much shorter time (8 months) than first estimated (5 years). This improvement partly resulted from the application of sound project management techniques. These projects were prime examples of the need for a formal project management approach to handling wild well projects. There are many examples of projects that were successful in controlling wells but were economic disasters. Only through the effective application of project management can complex well control projects be completed in reasonable time frames at reasonable cost. The paper describes team management, project scope, organizational structures, scheduling, tracking models, critical path method, and decision trees.

Oberlender, G.D. [Oklahoma State Univ., Stillwater, OK (United States); Abel, L.W. [Wild Well Control Inc., Spring, TX (United States)

1995-07-10T23:59:59.000Z

67

Improving supply chain performance by implementing weekly demand planning processes in the consumer packaged goods industry  

E-Print Network [OSTI]

This thesis examines how simple weekly demand planning process can improve inventory levels and customers service levels at the Gillette Company. The processes designed by the project team has been tested and executed in ...

Rah, Myung-Hyun Elisa

2006-01-01T23:59:59.000Z

68

CAMPUS PLANNING COMMITTEE PLANNING AND REVIEW PROCESS FOR MAJOR CAPITAL PROJECTS  

E-Print Network [OSTI]

a detailed cost estimate. F. PROJECT PLANNING GUIDE (PPG): This document is required for all State fundedCAMPUS PLANNING COMMITTEE PLANNING AND REVIEW PROCESS FOR MAJOR CAPITAL PROJECTS (Revised June 2011) ___________________________________________________________________________________________ I. INTRODUCTION An effective major capital planning and review process will: Encourage appropriate

California at Santa Barbara, University of

69

Page 1 of 1 PSD FY 2014 ESH IMPROVEMENT PLAN  

E-Print Network [OSTI]

Page 1 of 1 PSD FY 2014 ESH IMPROVEMENT PLAN PREPARED BY ANDREW ACKERMAN This document defines the actions planned for FY 2014 for improving the PSD ESH programs beyond the primary goal of controlling

Ohta, Shigemi

70

Security Improvements Project Completed Ahead of Schedule, $20...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Field Offices Welcome to the NNSA Production Office NPO News Releases Security Improvements Project Completed Ahead of Schedule, ... Security Improvements Project Completed...

71

Smart Grid Projects Are Improving Performance and Helping Consumers...  

Energy Savers [EERE]

Smart Grid Projects Are Improving Performance and Helping Consumers Better Manage their Energy Use Smart Grid Projects Are Improving Performance and Helping Consumers Better Manage...

72

PROJECT INITIATION FORM FACILITY SERVICES PLANNING, DESIGN AND CONSTRUCTION  

E-Print Network [OSTI]

PROJECT INITIATION FORM FACILITY SERVICES ­ PLANNING, DESIGN AND CONSTRUCTION 202 Facility Services would like an appointment to discuss the project. Department: College: Requestor's Name: E-mail : Phone: Project Contact: (if other than requestor): E-mail : Phone: B. PROJECT INFORMATION Project Location

Stephens, Jacqueline

73

UMTRA Project Office Records Management Plan  

SciTech Connect (OSTI)

The Uranium Mill Tailings Remedial Action (UMTRA) Project Office maintains two distinct records handling areas. One of the areas is maintained by a Technical Assistance Contractor (TAC), and is referred to as the UMTRA Project Document Control Center (UPDCC). The UPDCC manages all UMTRA records except those dealing with contracts, personnel, budgeting, finance, and any other documents which are of a purely administrative nature. The second area, the UMTRA Project Administrative Files Collection (UPAFC), contains all those records listed above that are not managed by the UPDCC. This Records Management Plan (RMP) for the UPAFC will be the framework for identifying the elements and activities that relate to the management and operational aspects involved in the handling of UPAFC. Guidelines for the program will be obtained from US Department of Energy (DOE) Orders. DOE Orders implement the guidelines issued by the National Archives and Records Administration (NARA), the final authority for records management. The RMP will address the life cycle of records, including their creation, maintenance, use, and disposition.

Not Available

1993-06-01T23:59:59.000Z

74

Project X Accelerator R&D Plan  

SciTech Connect (OSTI)

Project X is a high intensity proton facility conceived to support a world-leading program in neutrino and flavor physics over the next two decades at Fermilab. Project X is an integral part of the Fermilab Roadmap as described in the Fermilab Steering Group Report. Project X is based on an 8 GeV superconducting H-linac, paired with the existing (but modified) Main Injector and Recycler Ring, to provide in excess of 2 MW of beam power throughout the energy range 60-120 GeV, simultaneous with at least 100 kW of beam power at 8 GeV. The linac utilizes technology in common with the ILC over the energy range 0.6-8.0 GeV. Beam current parameters can be made identical to ILC resulting in identical rf generation and distribution systems. This alignment of ILC and Project X technologies allows for a shared development effort. The initial 0.6 GeV of the linac draws heavily on technology developed by Argonne National Laboratory for a facility for rare isotope beams. It is anticipated that the exact configuration and operating parameters of the linac will be defined through the R&D program and will retain alignment with the ILC plan as it evolves over this period. Utilization of the Recycler Ring as an H{sup -} stripper and accumulator ring is the key element that provides the flexibility to operate the linac with the same beam parameters as the ILC. The linac operates at 5 Hz with a total of 5.6 x 10{sup 13} H{sup -} ions delivered per pulse. H{sup -} are stripped at injection into the Recycler in a manner that 'paints' the beam both transversely and longitudinally to reduce space charge forces. Following the 1 ms injection, the orbit moves off the stripping foil and circulates for 200 msec, awaiting the next injection. Following three such injections a total of 1.7 x 10{sup 14} protons are transferred in a single turn to the Main Injector. These protons are then accelerated to 120 GeV and fast extracted to a neutrino target. The Main Injector cycle takes 1.4 seconds, producing approximately 2.3 MW of beam power at 120 GeV. At lower proton energies Main Injector cycle times can be shorter, allowing a beam power above 2 MW in the range of proton energy between 60 GeV and 120 GeV. In parallel, because the loading of the Recycler only requires 0.6 seconds, up to four linac cycles are available for accumulation and distribution of 8 GeV protons from the Recycler. Total available 8 GeV beam power lies in the range of 100-200 kW, depending on the energy in the Main Injector. Primary modifications to the existing accelerator complex to support Project X include integration of an H{sup -} injection system, a new RF system, a new extraction system, and measures to mitigate electron cloud effects, in the Recycler Ring. The Main Injector would need a new RF system, measures to preserve beam stability through transition, and measures to mitigate electron cloud effects. Finally, substantial modifications to the existing NuMI target station will be required to support >2 MW operations. It is anticipated that Project X configured as described above would initially support high intensity neutrino beams to the NOvA experiment, in parallel with at least one new 8 GeV based flavor/rare decay experiment. Depending upon future directions flexibility is retained for delivering neutrinos toward the DUSEL site and/or protons into the Tevatron. The purpose of this document is to describe an R&D plan that would position the U.S. to initiate construction of Project X in the 2012 time frame, assuming a go ahead decision in roughly 2010. The organization of this document is as follows: (1) Goals - Describes goals of the R&D and preliminary design period (2008-2011). Included are design, technical development, project documentation, and organizational goals. These are described in the context of an overall set of performance goals for Project X. (2) R&D Plan Elements - Describes the essential technical elements of the plan, including major subsystem performance requirements, associated accelerator and technology issues, and the plans for add

Not Available

2008-01-31T23:59:59.000Z

75

National Ignition Facility project acquisition plan revision 1  

SciTech Connect (OSTI)

The purpose of this National Ignition Facility Acquisition Plan is to describe the overall procurement strategy planned for the National Ignition Facility M Project. It was prepared for the NIP Prood Office by the NIF Procurement Manager.

Clobes, A.R.

1996-10-01T23:59:59.000Z

76

Strategies and Project Delivery Methods for Captial Improvement Projects  

E-Print Network [OSTI]

Conference, Dallas, Texas Nov. 18-20 Access to Capital FUNDING/FINANCING OPTION PUBLIC AGENCY PRIVATE COMPANY Utility Rebates X X Incentives X X Tax Exempt Bonds X Not for Profit only KOs X LoanSTAR X Tax Exempt Lease X Commercial Loans X X Shared Savings... of selected improvement measures • Establish energy baseline • Pursue grants and rebates, secure financing • Complete construction schedule • Determine commissioning and M&V plan • Select and manage subcontractors • Secure permits • Procure...

White, D.

2014-01-01T23:59:59.000Z

77

Spent Nuclear Fuel project integrated safety management plan  

SciTech Connect (OSTI)

This document is being revised in its entirety and the document title is being revised to ``Spent Nuclear Fuel Project Integrated Safety Management Plan.

Daschke, K.D.

1996-09-17T23:59:59.000Z

78

BPA to share costs with PUDs in regional planning project  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

BPA to share costs with PUDs in regional planning project Portland, Ore. - Three public utility districts and the Bonneville Power Administration signed an agreement today that...

79

Nuclear Fuels Storage and Transportation Planning Project (NFST...  

Office of Environmental Management (EM)

Nuclear Fuel Storage and Transportation Planning Project Overview DOE Office of Nuclear Energy Task Force for Strategic Developments to Blue Ribbon Commission Recommendations...

80

assurance project plans: Topics by E-print Network  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

and water resources, while supporting the Pecos River Compact by delivering water to Texas 4. Project Objectives: Planning for a possible candidate conservation agreement will...

Note: This page contains sample records for the topic "improvement project plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


81

assurance project plan: Topics by E-print Network  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

and water resources, while supporting the Pecos River Compact by delivering water to Texas 4. Project Objectives: Planning for a possible candidate conservation agreement will...

82

E-Print Network 3.0 - agreement planning project Sample Search...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

planning project Search Powered by Explorit Topic List Advanced Search Sample search results for: agreement planning project Page: << < 1 2 3 4 5 > >> 1 FACILITIES PLANNING, DESIGN...

83

QA program plan plutonium stabilization and handling project W-460  

SciTech Connect (OSTI)

This Quality Assurance Program Plan (QAPP) identifies Project Quality Assurance (QA) program requirements for all parties participating in the design, procurement, demolition, construction, installation, inspection and testing for Project W-460.

SCHULTZ, J.W.

1999-09-02T23:59:59.000Z

84

Global Threat Reduction Initiative Africa and Middle East Project Plan 2012  

SciTech Connect (OSTI)

GTRI Africa and Middle East Project Plan submitted for school project to American Graduate University.

Jamison, Jeremy D.

2012-02-01T23:59:59.000Z

85

Project plan international atomic energy agency (IAEA) safeguards project plutonium finishing plant  

SciTech Connect (OSTI)

This plan presents the overall objectives, description, justification and planning for the Plutonium Finishing Plant (PFP) International Atomic Energy Agency (IAEA) project. The intent of this plan is to describe how this project will be managed and integrated with other facility stabilization and deactivation activities. This plan supplements the overall integrated plan presented in the PFP Integrated Project Management Plan (PMP), HNF-3617, Rev. 0. This project plan is the top-level definitive project management document for the PFP IAEA project. It specifies the technical, schedule, requirements and the cost baselines to manage the execution of the IAEA project. Any deviations to the document must be authorized through the appropriate change control process.

BARTLETT, W.D.

1999-05-13T23:59:59.000Z

86

Tank waste remediation system privatization phase 1 infrastructure project W-519, project execution plan  

SciTech Connect (OSTI)

This Project Execution Plan (PEP) defines the overall strategy, objectives, and contractor management requirements for the execution phase of Project W-519 (98-D403), Privatization Phase 1 Infrastructure Support, whose mission is to effect the required Hanford site infrastructure physical changes to accommodate the Privatization Contractor facilities. This plan provides the project scope, project objectives and method of performing the work scope and achieving objectives. The plan establishes the work definitions, the cost goals, schedule constraints and roles and responsibilities for project execution. The plan also defines how the project will be controlled and documented.

Parazin, R.J.

1998-08-28T23:59:59.000Z

87

2012 Quality Assurance Improvement Project Plan  

Office of Environmental Management (EM)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr May Jun Jul(Summary) "of Energy Power Systems Engineering ResearchServices4/08VirginiaOsuna- FLIGHTTEPPDepartment2012 NuclearDOE

88

2010 Quality Assurance Improvement Project Plan  

Office of Environmental Management (EM)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr May Jun Jul(Summary) "of Energy Power Systems Engineering ResearchServices4/08VirginiaOsuna- FLIGHT - -July05 WaysSmart0

89

automated improvement of radiation therapy treatment plans by ...  

E-Print Network [OSTI]

The potential suboptimality of IMRT treatment plans has inspired methods for ... plans, which resulted in much improved planning efficiency. ...... Collapsed cone convolution of radiant energy for photon dose calculation in ... IMRT commissioning: multiple institution planning and dosimetry comparisons, a report from.

2012-11-06T23:59:59.000Z

90

Advanced Seismic Probabilistic Risk Assessment Demonstration Project Plan  

SciTech Connect (OSTI)

Idaho National Laboratories (INL) has an ongoing research and development (R&D) project to remove excess conservatism from seismic probabilistic risk assessments (SPRA) calculations. These risk calculations should focus on providing best estimate results, and associated insights, for evaluation and decision-making. This report presents a plan for improving our current traditional SPRA process using a seismic event recorded at a nuclear power plant site, with known outcomes, to improve the decision making process. SPRAs are intended to provide best estimates of the various combinations of structural and equipment failures that can lead to a seismic induced core damage event. However, in general this approach has been conservative, and potentially masks other important events (for instance, it was not the seismic motions that caused the Fukushima core melt events, but the tsunami ingress into the facility).

Justin Coleman

2014-09-01T23:59:59.000Z

91

Project plan remove special nuclear material from PFP project plutonium finishing plant  

SciTech Connect (OSTI)

This plan presents the overall objectives, description, justification and planning for the Plutonium Finishing Plant (PFP) Remove Special Nuclear Material (SNM) Materials. The intent of this plan is to describe how this project will be managed and integrated with other facility stabilization and deactivation activities. This plan supplements the overall integrated plan presented in the Plutonium Finishing Plant Integrated Project Management Plan (IPMP), HNF-3617, Rev. 0. This project plan is the top-level definitive project management document for PFP Remove SNM Materials project. It specifies the technical, schedule, requirements and the cost baselines to manage the execution of the Remove SNM Materials project. Any deviations to the document must be authorized through the appropriate change control process.

BARTLETT, W.D.

1999-05-13T23:59:59.000Z

92

Health and Safety Plan for NSTX Upgrade Project Tasks  

E-Print Network [OSTI]

describes the structure and implementation of the Health and Safety Plan for the NSTX Upgrade Project work Safety Management Objective of this project is: 1. To integrate safety into all work management and work to Work Being Performed Operations Authorization This Integrated Safety Management Plan describes

Princeton Plasma Physics Laboratory

93

Automated transportation management system (ATMS) software project management plan (SPMP)  

SciTech Connect (OSTI)

The Automated Transportation Management System (ATMS) Software Project Management plan (SPMP) is the lead planning document governing the life cycle of the ATMS and its integration into the Transportation Information Network (TIN). This SPMP defines the project tasks, deliverables, and high level schedules involved in developing the client/server ATMS software.

Weidert, R.S., Westinghouse Hanford

1996-05-20T23:59:59.000Z

94

Final Hanford Site Transuranic (TRU) Waste Characterization QA Project Plan  

SciTech Connect (OSTI)

The Transuranic Waste Characterization Quality Assurance Program Plan required each U.S. Department of Energy (DOE) site that characterizes transuranic waste to be sent the Waste Isolation Pilot Plan that addresses applicable requirements specified in the quality assurance project plan (QAPP).

GREAGER, T.M.

1999-12-14T23:59:59.000Z

95

Operational efficiency through resource planning optimization and work process improvement  

E-Print Network [OSTI]

This thesis covers work done at National Grid to improve resource planning and the execution of pipeline construction and maintenance work carried out at the yards. Resource Planning, the art of picking the right jobs for ...

Balwani, Siddharth (Siddharth Vashdev)

2012-01-01T23:59:59.000Z

96

Project management plan for project W-320, tank 241-C-106 sluicing  

SciTech Connect (OSTI)

This Project Management Plan establishes the organization, plans, and systems for management of Project W-320 as defined in DOE Order 4700.1, Project Management System (DOE 1987). The sluicing is for retrieving high-heat waste from single shell tank 241-C-106.

Leliefeld, K.W.

1996-02-02T23:59:59.000Z

97

Licensing plan for UMTRA project disposal sites. Final [report  

SciTech Connect (OSTI)

The Uranium Mill Tailings Remedial Action (UMTRA) Project Office developed a plan to define UMTRA Project licensing program objectives and establish a process enabling the DOE to document completion of remedial actions in compliance with 40 CFR 1 92 and the requirements of the NRC general license. This document supersedes the January 1987 Project Licensing Plan (DOE, 1987). The plan summarizes the legislative and regulatory basis for licensing, identifies participating agencies and their roles and responsibilities, defines key activities and milestones in the licensing process, and details the coordination of these activities. This plan provides an overview of the UMTRA Project from the end of remedial actions through the NRC`s acceptance of a disposal site under the general license. The licensing process integrates large phases of the UMTRA Project. Other programmatic UMTRA Project documents listed in Section 6.0 provide supporting information.

Not Available

1993-09-01T23:59:59.000Z

98

Preliminary Project Execution Plan for the Remote-Handled Low-Level Waste Disposal Project  

SciTech Connect (OSTI)

This preliminary project execution plan (PEP) defines U.S. Department of Energy (DOE) project objectives, roles and responsibilities of project participants, project organization, and controls to effectively manage acquisition of capital funds for construction of a proposed remote-handled low-level waste (LLW) disposal facility at the Idaho National Laboratory (INL). The plan addresses the policies, requirements, and critical decision (CD) responsibilities identified in DOE Order 413.3B, 'Program and Project Management for the Acquisition of Capital Assets.' This plan is intended to be a 'living document' that will be periodically updated as the project progresses through the CD process to construction and turnover for operation.

David Duncan

2011-05-01T23:59:59.000Z

99

Revised Date September 18, 2013 Capital Project Planning  

E-Print Network [OSTI]

. Identify Funding Funding Source(s) 2. Cost Estimate Information (from preliminary estimate form): 3_- Project Name Cost Estimate Low Range High Range #12;Revised Date ­ January 25, 2013 Priority RankingRevised Date ­ September 18, 2013 Capital Project Planning Project Approval Form All capital

100

University of Nebraska Lincoln Capital Project Planning Decision Flowchart  

E-Print Network [OSTI]

originator and CPC provides general sizing, implications, cost estimate, etc. for project. Consistency of continuing? Yes No1 Project proposal with costs estimates provided to Chancellor and Senior AdministrativeUniversity of Nebraska ­ Lincoln Capital Project Planning Decision Flowchart 1. Program Concept 2

Farritor, Shane

Note: This page contains sample records for the topic "improvement project plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


101

Risk Management Plan Electron Beam Ion Source Project  

E-Print Network [OSTI]

Risk Management Plan for the Electron Beam Ion Source Project (EBIS) Project # 06-SC-002 at Brookhaven National Laboratory Upton, NY For the U.S. Department of Energy Office of Science Office of Nuclear Physics (SC ­ 26) #12;1. Background and References 1.1 Background The EBIS Project will manage

102

Technology Transfer Expansion Planned UTCA is conducting a major project  

E-Print Network [OSTI]

Technology Transfer Expansion Planned UTCA is conducting a major project to evaluate and extend its technology transfer activities (UTCA project 03217). Steven Jones and David Eckhoff of UAB are working to expand the current technology transfer program to showcase the successes of the UTCA projects. Samples

Carver, Jeffrey C.

103

Detailed Execution Planning for Large Oil and Gas Construction Projects  

E-Print Network [OSTI]

Detailed Execution Planning for Large Oil and Gas Construction Projects Presented by James Lozon, University of Calgary There is currently 55.8 billion dollars worth of large oil and gas construction projects scheduled or underway in the province of Alberta. Recently, large capital oil and gas projects

Calgary, University of

104

Improving Remedial Planning Performance: The Rattlesnake Creek Experience  

SciTech Connect (OSTI)

The U.S. Army Corps of Engineers (USACE), Buffalo District, has responsibility for characterizing and remediating radiologically contaminated properties under the Formerly Utilized Sites Remedial Action Program (FUSRAP). Most of these FUSRAP sites include radionuclide contamination in soils where excavation and offsite disposal is the selected remedial action. For many FUSRAP soil remediation projects completed to date, the excavated contaminated soil volumes have significantly exceeded the pre-excavation volume estimates that were developed for project planning purposes. The exceedances are often attributed to limited and sparse datasets that are used to calculate the initial volume estimates. These volume exceedances complicate project budgeting and planning. Building on these experiences, the USACE took a different approach in the remediation of Rattlesnake Creek, located adjacent to the Ashland 2 site, in Tonawanda, New York. This approach included a more extensive pre-design data collection effort to improve and reduce the uncertainty in the pre-excavation volume estimates, in addition to formalizing final status survey data collection strategies prior to excavation. The final status survey sampling was fully integrated with the pre-design data collection, allowing dual use of the pre-design data that was collected (i.e., using the data to close out areas where contamination was not found, and feeding the data into volume estimates when contamination was encountered). The use of real-time measurement techniques (e.g., X-ray fluorescence [XRF] and gamma walkover surveys) during pre-excavation data collection allowed the USACE to identify and respond to unexpected contamination by allocating additional data collection to characterizing new areas of concern. The final result was an estimated soil volume and excavation footprint with a firm technical foundation and a reduction in uncertainty. However, even with extensive pre-design data collection, additional contamination was found during the excavation that led to an increase in the soil volume requiring offsite disposal. This paper describes the lessons learned regarding improving remedial planning performance from the Rattlesnake Creek experience and evaluates the level of project uncertainty reduction achieved through pre-design data collection. (authors)

Rieman, C.R.; Spector, H.L.; Andrews, S.M. [U.S. Army Corps of Engineers, Buffalo District, 1776 Niagara St., Buffalo, NY 14207 (United States); Durham, L. A.; Johnson, R. L. [Argonne National Laboratory, 9700 S. Cass Ave., EVS 900, Argonne, IL 60439 (United States); Racino, R. R. [Cabrera Services, Inc., 29 Railroad Avenue, Middletown, NY 10940 (United States)

2006-07-01T23:59:59.000Z

105

Uranium Mill Tailings Remedial Action (UMTRA) Surface Project: Project plan. Revision 1  

SciTech Connect (OSTI)

The Uranium Mill Tailings Radiation Control Act of 1978 (UMTRCA) [Public Law (PL) 95-604, 42 United States Code (USC) 7901], hereinafter referred to as the ``Act,`` authorizes the US Department of Energy (DOE) to stabilize and control surface tailings and ground water contamination. To fulfill this mission, the DOE has established two projects under the Uranium Mill Tailings Remedial Action (UMTRA) Project Office. The Ground Water Project was established in April 1991 as a major project and a separate project plan will be prepared for that portion of the mission. This project plan covers the UMTRA Surface Project, a major system acquisition (MSA).

Not Available

1993-08-11T23:59:59.000Z

106

Improving Project Management | Department of Energy  

Office of Environmental Management (EM)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr May Jun Jul(Summary) "of Energy Power.pdf11-161-LNG | Department ofHTS CableDepartment ofDepartment of EnergyImproving Project

107

Joint transmission system projects to improve system reliability  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

County PUD, 425-783-8444 Joint transmission system projects to improve system reliability First major regional electric grid improvements in decades prepare the area for the...

108

The Wind Forecast Improvement Project (WFIP): A Public/Private...  

Energy Savers [EERE]

The Wind Forecast Improvement Project (WFIP): A PublicPrivate Partnership for Improving Short Term Wind Energy Forecasts and Quantifying the Benefits of Utility Operations The...

109

Finance and supply management project execution plan  

SciTech Connect (OSTI)

As a subproject of the HANDI 2000 project, the Finance and Supply Management system is intended to serve FDH and Project Hanford major subcontractor with financial processes including general ledger, project costing, budgeting, and accounts payable, and supply management process including purchasing, inventory and contracts management. Currently these functions are performed with numerous legacy information systems and suboptimized processes.

BENNION, S.I.

1999-02-10T23:59:59.000Z

110

Infrastructure and Operations Improvement Project Director |...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

project risks. -Ensure that required and effective project management and control systems are developed, deployed and implemented to successfully manage and assess the project...

111

The Columbia River Protection Supplemental Technologies Quality Assurance Project Plan  

SciTech Connect (OSTI)

Pacific Northwest National Laboratory researchers are working on the Columbia River Protection Supplemental Technologies Project. This project is a U. S. Department of Energy, Office of Environmental Management-funded initiative designed to develop new methods, strategies, and technologies for characterizing, modeling, remediating, and monitoring soils and groundwater contaminated with metals, radionuclides, and chlorinated organics. This Quality Assurance Project Plan provides the quality assurance requirements and processes that will be followed by the Technologies Project staff.

Fix, N. J.

2008-03-12T23:59:59.000Z

112

West Virginia Smart Grid Implementation Plan (WV SGIP) Project  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

WV DoE-NRCCE-APERC DRAFT February 16, 2009 1 West Virginia Smart Grid Implementation Plan (WV SGIP) Project APERC Report on Customer Complaints to WV PSC about Electric Power...

113

HTI retrieval demonstration project execution plan  

SciTech Connect (OSTI)

This plan describes the process for demonstrating the retrieval of difficult Hanford tank waste forms utilizing commercial technologies and the private sector to conduct the operations. The demonstration is to be conducted in Tank 241-C-106.

Ellingson, D.R.

1997-09-04T23:59:59.000Z

114

DOE plan for UMTRA Project water protection standards  

SciTech Connect (OSTI)

This plan was developed to define DOE`s implementation of water protection standards for the UMTRA Project, on an interim basis, until the EPA promulgates revised standards in response to the September, 1985, decision by the Tenth Circuit Court of Appeals. This plan presents the historical background of the development of the Title I standards and the rationale for the DOE implementation approach.

Not Available

1986-07-01T23:59:59.000Z

115

DOE plan for UMTRA Project water protection standards  

SciTech Connect (OSTI)

This plan was developed to define DOE's implementation of water protection standards for the UMTRA Project, on an interim basis, until the EPA promulgates revised standards in response to the September, 1985, decision by the Tenth Circuit Court of Appeals. This plan presents the historical background of the development of the Title I standards and the rationale for the DOE implementation approach.

Not Available

1986-07-01T23:59:59.000Z

116

Master Plan For Improving Energy Efficiency  

E-Print Network [OSTI]

Presidential Executive Order 12003, dated July 1977, directed all government owned or leased facilities to develop and execute a 10-year Energy Conservation Plan. With facilities in seven states totaling 15 million square feet, the Albuquerque...

Johnson, W. H.

117

Project Management Plan - Small Producers Program  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr MayAtmosphericNuclear Security Administration the1 - SeptemberMicroneedles for4-16Hamada winsProgress ReportProjectProjectProjectRPSEA

118

ERD UMTRA Project quality assurance program plan, Revision 7  

SciTech Connect (OSTI)

This document is the revised Quality Assurance Program Plan (QAPP) dated September, 1995 for the Environmental Restoration Division (ERD) Uranium Mill Tailings Remedial Action Project (UMTRA). Quality Assurance requirements for the ERD UMTRA Project are based on the criteria outlined in DOE Order 5700.6C or applicable sections of 10 CFR 830.120. QA requirements contained in this QAPP shall apply to all personnel, processes, and activities, including planning, scheduling, and cost control, performed by the ERD UMTRA Project and its contractors.

NONE

1995-09-01T23:59:59.000Z

119

Uranium mill tailings remedial action project real estate management plan  

SciTech Connect (OSTI)

This plan summarizes the real estate requirements of the US Department of Energy`s (DOE) Uranium Mill Tailings Action (UMTRA) Project, identifies the roles and responsibilities of project participants involved in real estate activities, and describes the approaches used for completing these requirements. This document is intended to serve as a practical guide for all project participants. It is intended to be consistent with all formal agreements, but if a conflict is identified, the formal agreements will take precedence.

Not Available

1994-09-01T23:59:59.000Z

120

DMP Planning for Big Science Projects  

E-Print Network [OSTI]

This report exists to provide high-level guidance for the strategic and engineering development of Data Management and Preservation plans for 'Big Science' data. Although the report's nominal audience is therefore rather narrow, we intend the document to be of use to other planners and data architects who wish to implement good practice in this area. For the purposes of this report, we presume that the reader is broadly persuaded (by external fiat if nothing else) of the need to preserve research data appropriately, and that they have both sophisticated technical support and the budget to support developments. The goal of the document is not to provide mechanically applicable recipes, but to allow the user to develop and lead a high-level plan which is appropriate to their organisation. Throughout, the report is informed where appropriate by the OAIS reference model.

Juan Bicarregui; Norman Gray; Rob Henderson; Roger Jones; Simon Lambert; Brian Matthews

2012-08-18T23:59:59.000Z

Note: This page contains sample records for the topic "improvement project plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


121

Final Report for the Soboba Strategic Tribal Energy Planning Project  

SciTech Connect (OSTI)

In 2011 the Tribe was awarded funds from the Department of Energy to formulate the Soboba Strategic Tribal Energy Plan. This will be a guiding document used throughout the planning of projects focused on energy reduction on the Reservation. The Soboba Strategic Tribal Energy Plan's goal is to create a Five Year Energy Plan for the Soboba Band of Luiseno Indians in San Jacinto, California. This plan will guide the decision making process towards consistent progress leading to the Tribal goal of a 25% reduction in energy consumption in the next five years. It will additionally outline energy usage/patterns and will edentify areas the Tribe can decrease energy use and increase efficiency. The report documents activities undertaken under the grant, as well as incldues the Tribe's strategif energy plan.

Miller, Kim [EPA Specialist] [EPA Specialist

2013-09-17T23:59:59.000Z

122

Single-shell tank interim stabilization project plan  

SciTech Connect (OSTI)

Solid and liquid radioactive waste continues to be stored in 149 single-shell tanks at the Hanford Site. To date, 119 tanks have had most of the pumpable liquid removed by interim stabilization. Thirty tanks remain to be stabilized. One of these tanks (C-106) will be stabilized by retrieval of the tank contents. The remaining 29 tanks will be interim stabilized by saltwell pumping. In the summer of 1997, the US Department of Energy (DOE) placed a moratorium on the startup of additional saltwell pumping systems because of funding constraints and proposed modifications to the Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) milestones to the Washington State Department of Ecology (Ecology). In a letter dated February 10, 1998, Final Determination Pursuant to Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) in the Matter of the Disapproval of the DOE`s Change Control Form M-41-97-01 (Fitzsimmons 1998), Ecology disapproved the DOE Change Control Form M-41-97-01. In response, Fluor Daniel Hanford, Inc. (FDH) directed Lockheed Martin Hanford Corporation (LNMC) to initiate development of a project plan in a letter dated February 25, 1998, Direction for Development of an Aggressive Single-Shell Tank (SST) Interim Stabilization Completion Project Plan in Support of Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement). In a letter dated March 2, 1998, Request for an Aggressive Single-Shell Tank (SST) Interim Stabilization Completion Project Plan, the DOE reaffirmed the need for an aggressive SST interim stabilization completion project plan to support a finalized Tri-Party Agreement Milestone M-41 recovery plan. This project plan establishes the management framework for conduct of the TWRS Single-Shell Tank Interim Stabilization completion program. Specifically, this plan defines the mission needs and requirements; technical objectives and approach; organizational structure, roles, responsibilities, and interfaces; and operational methods. The plan is based on realistic assumptions and addresses three separate funding scenarios.

Ross, W.E.

1998-03-27T23:59:59.000Z

123

Spent Nuclear Fuel (SNF) Project Execution Plan  

SciTech Connect (OSTI)

The Spent Nuclear Fuel (SNF) Project supports the Hanford Site Mission to cleanup the Site by providing safe, economic, environmentally sound management of Site spent nuclear fuel in a manner that reduces hazards by staging it to interim onsite storage and deactivates the 100 K Area facilities.

LEROY, P.G.

2000-11-03T23:59:59.000Z

124

UMTRA Project Office quality assurance program plan. Revision 6  

SciTech Connect (OSTI)

The Uranium Mill Tailings Remedial Action (UMTRA) Project was established to accomplish remedial actions at inactive uranium mill tailings sites. The UMTRA Project`s mission is to stabilize and control the residual radioactive materials at designated sites in a safe and environmentally sound manner so as to minimize or eliminate radiation health hazards to the public. Because these efforts may involve possible risks to public health and safety, a quality assurance (QA) program that conforms to the applicable criteria has been established to control the quality of the work. This document, the Quality Assurance Program Plan (QAPP), brings into one document the essential criteria to be applied on a selective basis, depending upon the nature of the activity being conducted, and describes how those criteria shall be applied to the UMTRA Project. QA requirements contained in this QAPP shall apply to all personnel, processes, and activities, including planning, scheduling, and cost control, performed by the UMTRA Project Office and its contractors.

Not Available

1994-09-01T23:59:59.000Z

125

The Columbia River Protection Supplemental Technologies Quality Assurance Project Plan  

SciTech Connect (OSTI)

The U.S. Department of Energy (DOE) has conducted interim groundwater remedial activities on the Hanford Site since the mid-1990s for several groundwater contamination plumes. DOE established the Columbia River Protection Supplemental Technologies Project (Technologies Project) in 2006 to evaluate alternative treatment technologies. The objectives for the technology project are as follows: develop a 300 Area polyphosphate treatability test to immobilize uranium, design and test infiltration of a phosphate/apatite technology for Sr-90 at 100-N, perform carbon tetrachloride and chloroform attenuation parameter studies, perform vadose zone chromium characterization and geochemistry studies, perform in situ biostimulation of chromium studies for a reducing barrier at 100-D, and perform a treatability test for phytoremediation for Sr-90 at 100-N. This document provides the quality assurance guidelines that will be followed by the Technologies Project. This Quality Assurance Project Plan is based on the quality assurance requirements of DOE Order 414.1C, Quality Assurance, and 10 CFR 830, Subpart A--Quality Assurance Requirements as delineated in Pacific Northwest National Laboratory’s Standards-Based Management System. In addition, the technology project is subject to the Environmental Protection Agency (EPA) Requirements for Quality Assurance Project Plans (EPA/240/B-01/003, QA/R-5). The Hanford Analytical Services Quality Assurance Requirements Documents (HASQARD, DOE/RL-96-68) apply to portions of this project and to the subcontractors. HASQARD requirements are discussed within applicable sections of this plan.

Fix, N. J.

2007-01-10T23:59:59.000Z

126

Developing an Evaluation Measurement and Verification Plan for Your Energy Efficiency Project/Program  

Broader source: Energy.gov [DOE]

Developing an Evaluation Measurement and Verification Plan for Your Energy Efficiency Project/Program

127

UMTRA Project Office Quality Assurance Program Plan. Revision 5  

SciTech Connect (OSTI)

The Uranium Mill Tailings Remedial Action (UMTRA) Project was established to accomplish remedial actions at inactive uranium mill tailings sites in accordance with Public Law 95-604, the Uranium Mill Tailings Radiation Control Act of 1978 (UMTRCA). The UMTRA Project`s mission is to stabilize and control the residual radioactive materials at designated sites in a safe and environmentally sound manner so as to minimize or eliminate radiation health hazards to the public. The US Department of Energy (DOE) UMTRA Project Office directs the overall Project. Because these efforts may involve possible risks to public health and safety, a quality assurance (QA) program that conforms to the applicable criteria (set forth in the reference documents) has been established to control the quality of the work. This document, the Quality Assurance Program Plan (QAPP), brings into one document the essential criteria to be applied on a selective basis, depending upon the nature of the activity being conducted, and describes how those criteria shall be applied to the UMTRA Project. The UMTRA Project Office shall require each Project contractor to prepare and submit for approval a more detailed QAPP that is based on the applicable criteria of this QAPP and the referenced documents. All QAPPs on the UMTRA Project shall fit within the framework of this plan or an industry standard format that has been approved by the DOE Project Office.

Not Available

1993-11-01T23:59:59.000Z

128

Advanced Hybrid Particulate Collector Project Management Plan  

SciTech Connect (OSTI)

As the consumption of energy increases, its impact on ambient air quality has become a significant concern. Recent studies indicate that fine particles from coal combustion cause health problems as well as atmospheric visibility impairment. These problems are further compounded by the concentration of hazardous trace elements such as mercury, cadmium, selenium, and arsenic in fine particles. Therefore, a current need exists to develop superior, but economical, methods to control emissions of fine particles. Since most of the toxic metals present in coal will be in particulate form, a high level of fine- particle collection appears to be the best method of overall air toxics control. However, over 50% of mercury and a portion of selenium emissions are in vapor form and cannot be collected in particulate control devices. Therefore, this project will focus on developing technology not only to provide ultrahigh collection efficiency of particulate air toxic emissions, but also to capture vapor- phase trace metals such as mercury and selenium. Currently, the primary state-of-the-art technologies for particulate control are fabric filters (baghouses) and electrostatic precipitators (ESPs). However, they both have limitations that prevent them from achieving ultrahigh collection of fine particulate matter and vapor-phase trace metals. The objective of this project is to develop a highly reliable advanced hybrid particulate collector (AHPC) that can provide > 99.99 % particulate collection efficiency for all particle sizes between 0.01 and 50 14m, is applicable for use with all U.S. coals, and is cost-0443competitive with existing technologies. Phase I of the project is organized into three tasks: Task I - Project Management, Reporting, and Subcontract Consulting Task 2 - Modeling, Design, and Construction of 200-acfm AHPC Model Task 3 - Experimental Testing and Subcontract Consulting

Miller, S.J.

1995-11-01T23:59:59.000Z

129

UMTRA project water sampling and analysis plan, Tuba City, Arizona  

SciTech Connect (OSTI)

Planned, routine ground water sampling activities at the U.S. Department of Energy (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project site in Tuba City, Arizona, are described in the following sections of this water sampling and analysis plan (WSAP). This plan identifies and justifies the sampling locations, analytical parameters, detection limits, and sampling frequency for the stations routinely monitored at the site. The ground water data are used for site characterization and risk assessment. The regulatory basis for routine ground water monitoring at UMTRA Project sites is derived from the U.S. Environmental Protection Agency (EPA) regulations in 40 CFR Part 192 (1994) and the final EPA standards of 1995 (60 FR 2854). Sampling procedures are guided by the UMTRA Project standard operating procedures (SOP) (JEG, n.d.), and the most effective technical approach for the site.

NONE

1996-02-01T23:59:59.000Z

130

Evolution of project planning tools in a matrix organization  

SciTech Connect (OSTI)

Until recently, the Corporate Construction Program at Sandia was experiencing difficulties in managing projects: poor planning and cost estimating caused schedule and budget problems. The first step taken was a Microsoft {reg_sign} Project schedule that provides a standard template for scheduling individual construction projects. It is broken down according to the life cycle of the project and prevents the project team from leaving out an important item. A WBS (work breakdown structure) dictionary was also developed that describes how capital and operating funds are used to develop, design, construct, equip, and manage projects. We also developed a matrix chart that maps the planning guide against the major types of construction projects at Sandia. The guide, dictionary, and matrix chart offer enough flexibility that the project manager can make choices about how to structure work, yet ensure that all work rolls up to the cost categories and key DOE WBS elements. As requirements change, the tools can be updated; they also serve as training tools for new project team members.

Furaus, J.P.; Figueroa-McInteer, C.; McKeever, P.S.; Wisler, D.B. [Sandia National Labs., Albuquerque, NM (United States); Zavadil, J.T. [Infomatrix (United States)

1996-10-01T23:59:59.000Z

131

Construction Project Safety and Health Plan RM  

Office of Environmental Management (EM)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr May Jun Jul(Summary) "of Energy Power Systems EngineeringDepartmentSmart Grid RFI:FresnoM-WG Idaho,Construction Project Safety and

132

Socio-economic benefits in Plan Vivo projects: Trees for Global Benefits, Uganda 1 Socio-economic benefits in Plan Vivo projects  

E-Print Network [OSTI]

Socio-economic benefits in Plan Vivo projects: Trees for Global Benefits, Uganda 1 Socio-economic benefits in Plan Vivo projects: Trees for Global Benefits, Uganda Sarah Carter 2009 #12;Socio-economic benefits in Plan Vivo projects: Trees for Global Benefits, Uganda 2 Version control: V2 Date: 1tst August

133

Independent Verification and Validation Of SAPHIRE 8 Software Project Plan Project Number: N6423 U.S. Nuclear Regulatory Commission  

SciTech Connect (OSTI)

This report provides an evaluation of the Project Plan. The Project Plan is intended to provide the high-level direction that documents the required software activities to meet the contractual commitments prepared by the sponsor; the Nuclear Regulatory Commission.

Carl Wharton; Kent Norris

2009-12-01T23:59:59.000Z

134

Sampling and Analysis Plan - Waste Treatment Plant Seismic Boreholes Project  

SciTech Connect (OSTI)

This sampling and analysis plan (SAP) describes planned data collection activities for four entry boreholes through the sediment overlying the basalt, up to three new deep rotary boreholes through the basalt and sedimentary interbeds, and one corehole through the basalt and sedimentary interbeds at the Waste Treatment Plant (WTP) site. The SAP will be used in concert with the quality assurance plan for the project to guide the procedure development and data collection activities needed to support borehole drilling, geophysical measurements, and sampling. This SAP identifies the American Society of Testing Materials standards, Hanford Site procedures, and other guidance to be followed for data collection activities.

Reidel, Steve P.

2006-05-26T23:59:59.000Z

135

Quality assurance program plan for cesium legacy project  

SciTech Connect (OSTI)

This Quality Assurance Program Plan (QAPP) provides information on how the Quality Assurance Program is implemented for the Cesium Legacy Project. It applies to those items and tasks which affect the completion of activities identified in the work breakdown structure of the Project Management Plan (PMP). These activities include all aspects of cask transportation, project related operations within the 324 Building, and waste management as it relates to the specific activities of this project. General facility activities (i.e. 324 Building Operations, Central Waste Complex Operations, etc.) are covered in other appropriate QAPPs. The 324 Building is currently transitioning from being a Pacific Northwest National Laboratory (PNNL) managed facility to a B and W Hanford Company (BWHC) managed facility. During this transition process existing PNNL procedures and documents will be utilized until replaced by BWHC procedures and documents.

Tanke, J.M.

1997-05-22T23:59:59.000Z

136

NIF Projects Controls and Information Systems Software Quality Assurance Plan  

SciTech Connect (OSTI)

Quality achievement for the National Ignition Facility (NIF) and the National Ignition Campaign (NIC) is the responsibility of the NIF Projects line organization as described in the NIF and Photon Science Directorate Quality Assurance Plan (NIF QA Plan). This Software Quality Assurance Plan (SQAP) is subordinate to the NIF QA Plan and establishes quality assurance (QA) activities for the software subsystems within Controls and Information Systems (CIS). This SQAP implements an activity level software quality assurance plan for NIF Projects as required by the LLNL Institutional Software Quality Assurance Program (ISQAP). Planned QA activities help achieve, assess, and maintain appropriate quality of software developed and/or acquired for control systems, shot data systems, laser performance modeling systems, business applications, industrial control and safety systems, and information technology systems. The objective of this SQAP is to ensure that appropriate controls are developed and implemented for management planning, work execution, and quality assessment of the CIS organization's software activities. The CIS line organization places special QA emphasis on rigorous configuration control, change management, testing, and issue tracking to help achieve its quality goals.

Fishler, B

2011-03-18T23:59:59.000Z

137

Energy Strategic Planning & Self-Sufficiency Project  

SciTech Connect (OSTI)

This report provides information regarding options available, their advantages and disadvantages, and the costs for pursuing activities to advance Smith River Rancheria toward an energy program that reduces their energy costs, allows greater self-sufficiency and stimulates economic development and employment opportunities within and around the reservation. The primary subjects addressed in this report are as follow: (1) Baseline Assessment of Current Energy Costs--An evaluation of the historical energy costs for Smith River was conducted to identify the costs for each component of their energy supply to better assess changes that can be considered for energy cost reductions. (2) Research Viable Energy Options--This includes a general description of many power generation technologies and identification of their relative costs, advantages and disadvantages. Through this research the generation technology options that are most suited for this application were identified. (3) Project Development Considerations--The basic steps and associated challenges of developing a generation project utilizing the selected technologies are identified and discussed. This included items like selling to third parties, wheeling, electrical interconnections, fuel supply, permitting, standby power, and transmission studies. (4) Energy Conservation--The myriad of federal, state and utility programs offered for low-income weatherization and utility bill payment assistance are identified, their qualification requirements discussed, and the subsequent benefits outlined. (5) Establishing an Energy Organization--The report includes a high level discussion of formation of a utility to serve the Tribal membership. The value or advantages of such action is discussed along with some of the challenges. (6) Training--Training opportunities available to the Tribal membership are identified.

Greg Retzlaff

2005-03-30T23:59:59.000Z

138

Health and Safety Plan for NSTX Upgrade Project Tasks  

E-Print Network [OSTI]

Safety Policies, PPPL ES&H Respiratory Protection Directive, the Work Control Center Procedure and the DOE Hoisting and Rigging Manual. Herein is our site specific Health and Safety Plan for the work The Integrated Safety Management Objectives of this project are: 1. To integrate safety into all work management

Princeton Plasma Physics Laboratory

139

Digital Radiography and Computed Tomography (DRCT) Product Improvement Plan (PIP)  

SciTech Connect (OSTI)

The Idaho National Laboratory (INL) has been developing and deploying x-ray inspection systems for chemical weapons containers for the past 12 years under the direction of the Project Manager for Non-Stockpile Chemical Materiel (PMNSCM). In FY-10 funding was provided to advance the capabilities of these systems through the DRCT (Digital Radiography and Computed Tomography) Product Improvement Plan (PIP), funded by the PMNSCM. The DRCT PIP identified three research tasks; end user study, detector evaluation and DRCT/PINS integration. Work commenced in February, 2010. Due to the late start and the schedule for field inspection of munitions at various sites, it was not possible to spend sufficient field time with operators to develop a complete end user study. We were able to interact with several operators, principally Mr. Mike Rowan who provided substantial useful input through several discussions and development of a set of field notes from the Pueblo, CO field mission. We will be pursuing ongoing interactions with field personnel as opportunities arise in FY-11.

Tim Roney; Bob Pink; Karen Wendt; Robert Seifert; Mike Smith

2010-12-01T23:59:59.000Z

140

An Experiment to Improve Cost Estimation and Project Tracking for Software and Systems Integration Projects  

E-Print Network [OSTI]

An Experiment to Improve Cost Estimation and Project Tracking for Software and Systems Integration to improve cost estimation and project tracking. 1. Introduction In order to remain competitive, ICL (as well for integration projects, to reduce time to market and to reduce costs without detriment to the quality

Henderson, Peter

Note: This page contains sample records for the topic "improvement project plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


141

BOSTON HARBOR, MASSACHUSETTS DEEP DRAFT NAVIGATION IMPROVEMENT PROJECT  

E-Print Network [OSTI]

BOSTON HARBOR, MASSACHUSETTS DEEP DRAFT NAVIGATION IMPROVEMENT PROJECT Civil Works Review Board Re-Presentation - 26 April 2013 ABSTRACT: The Boston Harbor Deep Draft Navigation Improvement Project consists entrance channels connecting Massachusetts Bay to the harbor, deep water anchorages in the harbor, a main

US Army Corps of Engineers

142

Recycling Campaign Award Prizes for best project proposal to improve  

E-Print Network [OSTI]

Recycling Campaign Award Prizes for best project proposal to improve waste recycling. Recycling bins contain inappropriate waste that cannot be recycled and thus are not picked up. THE REASON for picking up the waste. 60% of the waste budget. Your task: - To develop a new project to improve recycling

van der Torre, Leon

143

Development of Facilities Master Plan and Laboratory Renovation Project  

SciTech Connect (OSTI)

Funding from this grant has allowed Morehouse School of Medicine to complete its first professionally developed, comprehensive campus master plan that is in alignment with the recently completed strategic plan. In addition to master planning activities, funds were used for programming and designing research renovations, and also to supplement other research facility upgrades by providing lighting and equipment. The activities funded by this grant will provide the catalyst for substantial improvement in the Schoolâ??s overall facilities for biomedical education and research, and will also provide much of the information needed to conduct a successful campaign to raise funds for proposed buildings and renovations.

Andrea D. Fox

2011-10-03T23:59:59.000Z

144

Unit 1: Project Planning and Scheduling To provide a brief introduction to project planning  

E-Print Network [OSTI]

is not the project manager it is essential that he or she has a good understanding of project management task #12 be considered under the general title Critical Path Scheduling (CPS) ÂĄ CPS is a management control tool machine #12;5 Activity List ÂĄ The initial step in applying CPS is to break the project down into its

Finkelstein, Anthony

145

Uranium Mill Tailings Remedial Action Project Environmental Protection Implementation Plan  

SciTech Connect (OSTI)

The Uranium Mill Tailings Remedial Action (UMTRA) Project Environmental Protection Implementation Plan (EPIP) has been prepared in accordance with the requirements of the US Department of Energy (DOE) Order 5400.1. The UMTRA EPIP covers the time period of November 9, 1993, through November 8, 1994. It will be updated annually. Its purpose is to provide management direction to ensure that the UMTRA Project is operated and managed in a manner that will protect, maintain, and where necessary, restore environmental quality, minimize potential threats to public health and the environment, and comply with environmental regulations and DOE policies. Contents of this report are: (1) general description of the UMTRA project environmental protection program; (2) notifications; (3) planning and reporting; (4) special programs; (5) environmental monitoring programs; (6) quality assurance and data verification; and (7) references.

Vollmer, A.T.

1993-10-01T23:59:59.000Z

146

Project Title Improved Emission Models for Project Evaluation (MOVES-Matrix) University Georgia Institute of Technology  

E-Print Network [OSTI]

Project Title Improved Emission Models for Project Evaluation (MOVES-Matrix) University Georgia or organization) DOT - $92,292.15 Total Project Cost $92,292.15 Agency ID or Contract Number DTRT13-G-UTC29 Start and End Dates November 2013 - June 2015 Brief Description of Research Project Local governments are using

California at Davis, University of

147

Project Information Form Project Title Innovative Data Collection to Improve Transit Service Assessment  

E-Print Network [OSTI]

(s) and Amounts Provided (by each agency or organization) DOT - $102,971.57 Total Project Cost $102,971.57 AgencyProject Information Form Project Title Innovative Data Collection to Improve Transit Service of Research Project Mobile information technology will be used to compare travel behavior of populations

California at Davis, University of

148

Project Information Form Project Title Managing Roadway Systems to Reduce GHG Emissions and Improve  

E-Print Network [OSTI]

or organization) $25,217 Total Project Cost $25,217 Agency ID or Contract Number DTRT13-G-UTC29 Start and EndProject Information Form Project Title Managing Roadway Systems to Reduce GHG Emissions and Improve Dates 4/1/14 ­ 3/30/15 Brief Description of Research Project There have been a variety of traffic

California at Davis, University of

149

E-Print Network 3.0 - assurance plan project Sample Search Results  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

for NRDA followed standard operating procedure (SOP), water sampling plans, Summary: procedures, and NOAA's Analytical Quality Assurance Project Plan (QAPP). Samples were sent...

150

Project Information Form Project Title Reducing Truck Emissions and Improving Truck Fuel Economy via ITS  

E-Print Network [OSTI]

Project Information Form Project Title Reducing Truck Emissions and Improving Truck Fuel Economy new traffic flow and traffic light control concepts with respect to emissions and fuel economy. Some

California at Davis, University of

151

UMTRA project technical assistance contractor quality assurance implementation plan  

SciTech Connect (OSTI)

The Uranium Mill Tailings Remedial Action (UMTRA) Project Technical Assistance contractor (TAC) Quality Assurance Implementation Plan (QAIP) outlines the primary requirements for integrating quality functions for TAC technical activities applied to the surface and ground water phases of the UMTRA Project. The QAIP is subordinate to the latest issue of the UMTRA Project TAC Quality Assurance Program Plan (QAPP) (DOE, 1993a), which was developed using US Department of Energy (DOE) Order 5700.6C quality assurance (QA) criteria. The QAIP addresses technical aspects of the TAC UMTRA Project surface and ground water programs. All QA issues in the QAIP shall comply with requirements contained in the TAC QAPP (DOE, 1933a). Because industry standards for data acquisition and data control are not addressed in DOE Order 5700.6C, the QAIP has been formatted to the 14 US Environmental Protection Agency (EPA) Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) QA requirements. DOE Order 5700.6C criteria that are not contained in the CERCLA requirements are added to the QAIP as additional requirements in Sections 15.0 through 18.0. Project documents that contain CERCLA requirements and 5700.6 criteria shall be referenced in this document to avoid duplication. Referenced documents are not included in this QAIP but are available through the UMTRA Project Document Control Center.

Not Available

1994-03-01T23:59:59.000Z

152

Final Hanford Site Transuranic (TRU) Waste Characterization QA Project Plan  

SciTech Connect (OSTI)

The Quality Assurance Project Plan (QAPjP) has been prepared for waste characterization activities to be conducted by the Transuranic (TRU) Project at the Hanford Site to meet requirements set forth in the Waste Isolation Pilot Plan (WIPP) Hazardous Waste Facility Permit, 4890139088-TSDF, Attachment B, including Attachments B1 through B6 (WAP) (DOE, 1999a). The QAPjP describes the waste characterization requirements and includes test methods, details of planned waste sampling and analysis, and a description of the waste characterization and verification process. In addition, the QAPjP includes a description of the quality assurance/quality control (QA/QC) requirements for the waste characterization program. Before TRU waste is shipped to the WIPP site by the TRU Project, all applicable requirements of the QAPjP shall be implemented. Additional requirements necessary for transportation to waste disposal at WIPP can be found in the ''Quality Assurance Program Document'' (DOE 1999b) and HNF-2600, ''Hanford Site Transuranic Waste Certification Plan.'' TRU mixed waste contains both TRU radioactive and hazardous components, as defined in the WLPP-WAP. The waste is designated and separately packaged as either contact-handled (CH) or remote-handled (RH), based on the radiological dose rate at the surface of the waste container. RH TRU wastes are not currently shipped to the WIPP facility.

GREAGER, T.M.

2000-12-06T23:59:59.000Z

153

Intermediate evaluation of USAID/Cairo energy policy planning project  

SciTech Connect (OSTI)

Three years ago, a team from the Oak Ridge National Laboratory and the Oak Ridge Associated Universities, supplemented by an expert from the US Department of Energy and a senior Egyptian energy professional, carried out what was termed an intermediate evaluation'' of a major energy policy project in Egypt. Supported by USAID/Cairo, the project had concentrated on developing and strengthening an Organization for Energy Planning (OEP) within the Government of India, and it was actually scheduled to end less than a year after this evaluation. The evaluation was submitted to USAID/Cairo and circulated elsewhere in the US Agency for International Development and the Government of Egypt as an internal report. Over the next several years, the USAID energy planning project ended and the functions performed by OEP were merged with planning capabilities in the electric power sector. Now that the major issues addressed by the evaluation report have been resolved, we are making it available to a broader audience as a contribution to the general literature on development project evaluation and institution-building.

Wilbanks, T.J.; Wright, S.B. (Oak Ridge National Lab., TN (United States)); Barron, W.F. (Hong Kong Univ. (Hong Kong)); Kamel, A.M. (Ain Shams Univ., Cairo (Egypt)); Santiago, H.T. (USDOE, Washington, DC (United States))

1992-01-01T23:59:59.000Z

154

Intermediate evaluation of USAID/Cairo energy policy planning project  

SciTech Connect (OSTI)

Three years ago, a team from the Oak Ridge National Laboratory and the Oak Ridge Associated Universities, supplemented by an expert from the US Department of Energy and a senior Egyptian energy professional, carried out what was termed an ``intermediate evaluation`` of a major energy policy project in Egypt. Supported by USAID/Cairo, the project had concentrated on developing and strengthening an Organization for Energy Planning (OEP) within the Government of India, and it was actually scheduled to end less than a year after this evaluation. The evaluation was submitted to USAID/Cairo and circulated elsewhere in the US Agency for International Development and the Government of Egypt as an internal report. Over the next several years, the USAID energy planning project ended and the functions performed by OEP were merged with planning capabilities in the electric power sector. Now that the major issues addressed by the evaluation report have been resolved, we are making it available to a broader audience as a contribution to the general literature on development project evaluation and institution-building.

Wilbanks, T.J.; Wright, S.B. [Oak Ridge National Lab., TN (United States); Barron, W.F. [Hong Kong Univ. (Hong Kong); Kamel, A.M. [Ain Shams Univ., Cairo (Egypt); Santiago, H.T. [USDOE, Washington, DC (United States)

1992-09-01T23:59:59.000Z

155

Communicating in a multi-project environment with a single-sheet project plan  

SciTech Connect (OSTI)

In June 1992, the Corporate Construction Program Office was formed to provide single-point accountability for managing all corporate-sponsored construction projects at Sandia, answering to upper Sandia management as well as Sandia`s primary external customer, the U.S. DOE. CCPO had 3 major areas of responsibility: Congressional line-item projects (>$2 million), general plant projects (<$2 million), and corporate-funded major rearrangements (renovations). A single-sheet project plan (``summary sheet``), with monthly updates, was developed for every project. Each month, the sheets are duplicated and placed in a ``project summary book`` that is distributed through various communication channels at Sandia. Despite many modifications, the summary sheet has remained simple and useful to a broad range of project stakeholders. This paper describes how the sheet`s design and implementation enhances communication across Sandia`s complex, multi-program environment.

Furaus, J.P.; Figueroa-McInteer, C.; Glidewell, D.D.; McKeever, P.S.; Hendrick, W.E.; Wisler, D.B.; Zavadil, J.T.

1995-07-01T23:59:59.000Z

156

Uranium Mill Tailings Remedial Action Project Environmental Protection Implementation Plan  

SciTech Connect (OSTI)

The Uranium Mill Tallings Remedial Action (UMTRA) Project Environmental Protection Implementation Plan (EPIP) has been prepared in accordance with the requirements of the US Department of Energy (DOE) Order 5400.1 (Chapter 3, paragraph 2). The UMTRA EPIP covers the time period of November 9, 1992, through November 8, 1993. It will be updated annually. Its purpose is to provide management direction to ensure that the UMTRA Project is operated and managed in a manner that will protect, maintain, and where necessary, restore environmental quality, minimize potential threats to public health and the environment, and comply with environmental regulations and DOE policies.

Not Available

1992-10-01T23:59:59.000Z

157

Uranium Mill Tailings Remedial Action Project environmental protection implementation plan  

SciTech Connect (OSTI)

The Uranium Mill Tailings Remedial Action (UMTRA) Project Environmental Protection Implementation Plan (EPIP) has been prepared in accordance with the requirements of the U.S. Department of Energy (DOE) Order 5400.1. The UMTRA EPIP is updated annually. This version covers the time period of 9 November 1994, through 8 November 1995. Its purpose is to provide management direction to ensure that the UMTRA Project is operated and managed in a manner that will protect, maintain, and where necessary, restore environmental quality, minimize potential threats to public health and the environment, and comply with environmental regulations and DOE policies.

Not Available

1994-10-01T23:59:59.000Z

158

UMTRA project water sampling and analysis plan, Maybell, Colorado  

SciTech Connect (OSTI)

This water sampling and analysis plan (WSAP) describes planned water sampling activities and provides the regulatory and technical basis for ground water sampling in 1994 at the US Department of Energy`s (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project site in Maybell, Colorado. The WSAP identifies and justifies sampling locations, analytical parameters, and sampling frequencies at the site. The ground water data will be used for site characterization and risk assessment. The regulatory basis for the ground water and surface water monitoring activities is derived from the EPA regulations in 40 CFR Part 192 (1993) and the proposed EPA standards of 1987 (52 FR 36000). Sampling procedures are guided by the UMTRA Project standard operating procedures (SOP) (JEG, n.d.), the Technical Approach Document (TAD) (DOE, 1989), and the most effective technical approach for the site. This WSAP also includes a summary and the results of water sampling activities from 1989 through 1992 (no sampling was performed in 1993).

Not Available

1994-06-01T23:59:59.000Z

159

La Jolla Children's Pool Beach Management and Water Quality Improvement Project  

E-Print Network [OSTI]

POOL BEACH MANAGEMENT AND WATER QUALITY IMPROVEMENT PROJECTPool Beach Management and Water Quality Improvements ProjectPool Beach Management and Water Quality Improvements Project

Elwany, Hany; Flick, Reinhard; Nichols, Jean; Lindquist, Anne-Lise

1998-01-01T23:59:59.000Z

160

Integrated project management plan for the Plutonium Finishing Plant stabilization and deactivation project  

SciTech Connect (OSTI)

This document sets forth the plans, organization, and control systems for managing the PFP Stabilization and Deactivation Project, and includes the top level cost and schedule baselines. The project includes the stabilization of Pu-bearing materials, storage, packaging, and transport of these and other nuclear materials, surveillance and maintenance of facilities and systems relied upon for storage of the materials, and transition of the facilities in the PFP Complex.

SINCLAIR, J.C.

1999-05-03T23:59:59.000Z

Note: This page contains sample records for the topic "improvement project plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


161

Management and operating contractor plan for transition to the project Hanford Management Contractor  

SciTech Connect (OSTI)

This is Revision 1 to the M{ampersand}O Contractor Plan for Transition to the Project Hanford Management Contractor.

Waite, J.L., Westinghouse Hanford

1996-06-27T23:59:59.000Z

162

Reliability improvement project decision making : water cooling system redesign  

E-Print Network [OSTI]

Deciding on which reliability & performance improvement projects to launch or to reject has historically been an extremely challenging responsibility of Teradyne management. Incorrect decisions can lead to major customer ...

Devine, Paul (Paul S.)

2006-01-01T23:59:59.000Z

163

NREL Releases RFP for Distributed Wind Turbine Competitiveness Improvement Projects  

Broader source: Energy.gov [DOE]

In support of DOE's efforts to further develop distributed wind technology, NREL's National Wind Technology Center has released a Request for Proposal for the following Distributed Wind Turbine Competitiveness Improvement Projects on the Federal Business

164

J.R. Simplot: Burner Upgrade Project Improves Performance and...  

Broader source: Energy.gov (indexed) [DOE]

Company saved energy and money by increasing the efficiency of the steam system in its potato processing plant in Caldwell, Idaho. J.R. Simplot: Burner Upgrade Project Improves...

165

NREL Announces Two New Competitiveness Improvement Project Awards...  

Energy Savers [EERE]

Improvement Project (CIP) awards. Northern Power Systems of Barre, Vermont, and Urban Green Energy of New York City, New York, will receive a portion of the 1.27 million...

166

Acquisition and Project Management Continuous Improvement Presentation |  

Energy Savers [EERE]

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious RankCombustionImprovement3-- ------------------------------Chapter 39.2 (June 2005) 1Director, Office

167

PORTSMOUTH HARBOR AND PISCATAQUA RIVER, NH & ME NAVIGATION IMPROVEMENT PROJECT  

E-Print Network [OSTI]

on the terminals located above Interstate 95. Cargoes include petroleum fuels, cement, gypsum, and liquid propane. The study evaluated project benefits based on reduction in transportation costs generated from a shift. The Recommended Plan will generate significant economic benefits for the nation, and is the National Economic

US Army Corps of Engineers

168

Up-Stream Dissolved Oxygen TMDL Project Quality Assurance ProjectPlan  

SciTech Connect (OSTI)

A quality assurance project plan (QAPP) for the execution of an ecosystem level monitoring and research program examining algal ecology in highly impaired rivers. Procedures for executing both field and laboratory surface water quality and flow analysis are described. The procedures described here are compatible with the California Surface Water Ambient Monitoring program (SWAMP).

Stringfellow, William T.

2005-05-13T23:59:59.000Z

169

Integrated development and testing plan for the plutonium immobilization project  

SciTech Connect (OSTI)

This integrated plan for the DOE Office of Fissile Materials Disposition (MD) describes the technology development and major project activities necessary to support the deployment of the immobilization approach for disposition of surplus weapons-usable plutonium. The plan describes details of the development and testing (D&T) tasks needed to provide technical data for design and operation of a plutonium immobilization plant based on the ceramic can-in-canister technology (''Immobilization Fissile Material Disposition Program Final Immobilization Form Assessment and Recommendation'', UCRL-ID-128705, October 3, 1997). The plan also presents tasks for characterization and performance testing of the immobilization form to support a repository licensing application and to develop the basis for repository acceptance of the plutonium form. Essential elements of the plant project (design, construction, facility activation, etc.) are described, but not developed in detail, to indicate how the D&T results tie into the overall plant project. Given the importance of repository acceptance, specific activities to be conducted by the Office of Civilian Radioactive Waste Management (RW) to incorporate the plutonium form in the repository licensing application are provided in this document, together with a summary of how immobilization D&T activities provide input to the license activity. The ultimate goal of the Immobilization Project is to develop, construct, and operate facilities that will immobilize from about 18 to 50 tonnes (MT) of U.S. surplus weapons usable plutonium materials in a manner that meets the ''spent fuel'' standard (Fissile Materials Storage and Disposition Programmatic Environmental Impact Statement Record of Decision, ''Storage and Disposition Final PEIS'', issued January 14, 1997, 62 Federal Register 3014) and is acceptable for disposal in a geologic repository. In the can-in-canister technology, this is accomplished by encapsulating the plutonium-containing ceramic forms within large canisters of high level waste (HLW) glass. Deployment of the immobilization capability should occur by 2006 and be completed within 10 years.

Kan, T.

1998-07-01T23:59:59.000Z

170

Sampling and Analysis Plan Waste Treatment Plant Seismic Boreholes Project.  

SciTech Connect (OSTI)

This sampling and analysis plan (SAP) describes planned data collection activities for four entry boreholes through the sediment overlying the Saddle Mountains Basalt, up to three new deep rotary boreholes through the Saddle Mountains Basalt and sedimentary interbeds, and one corehole through the Saddle Mountains Basalt and sedimentary interbeds at the Waste Treatment Plant (WTP) site. The SAP will be used in concert with the quality assurance plan for the project to guide the procedure development and data collection activities needed to support borehole drilling, geophysical measurements, and sampling. This SAP identifies the American Society of Testing Materials standards, Hanford Site procedures, and other guidance to be followed for data collection activities. Revision 3 incorporates all interim change notices (ICN) that were issued to Revision 2 prior to completion of sampling and analysis activities for the WTP Seismic Boreholes Project. This revision also incorporates changes to the exact number of samples submitted for dynamic testing as directed by the U.S. Army Corps of Engineers. Revision 3 represents the final version of the SAP.

Brouns, Thomas M.

2007-07-15T23:59:59.000Z

171

STORM WATER POLLUTION PREVENTION PLAN BUILDING B51 AND BEVATRON DEMOLITION PROJECT  

E-Print Network [OSTI]

STORM WATER POLLUTION PREVENTION PLAN FOR: BUILDING B51 AND BEVATRON DEMOLITION PROJECT PROJECT NO;Storm Water Pollution Prevention Plan (SWPPP) Building B51 and Bevatron Demolition Project Lawrence............................................................................................300-3 300.4 Project Schedule/Water Pollution Control Schedule

172

Uranium Mill Tailings Remedial Action Project (UMTRAP) Public Participation Plan  

SciTech Connect (OSTI)

The purpose of this Public Participation Plan is to explain the Department of Energy`s plan for involving the public in the decision-making process related to the Uranium Mill Tailings Remedial Action (UMTRA) Project. This project was authorized by Congress in the Uranium Mill Tailings Radiation Control Act of 1978. The Act provides for a cooperative effort with affected states and Indian tribes for the eventual cleanup of abandoned or inactive uranium mill tailings sites, which are located in nine western states and in Pennsylvania. Section 111 of the Act states, ``in carrying out the provisions of this title, including the designation of processing sites, establishing priorities for such sites, the selection of remedial actions and the execution of cooperative agreements, the Secretary (of Energy), the Administrator (of the Environmental Protection Agency), and the (Nuclear Regulatory) Commission shall encourage public participation and, where appropriate, the Secretary shall hold public hearings relative to such matters in the States where processing sites and disposal sites are located.`` The objective of this document is to show when, where, and how the public will be involved in this project.

NONE

1981-05-01T23:59:59.000Z

173

Large hadron collider (LHC) project quality assurance plan  

SciTech Connect (OSTI)

The LHC Quality Assurance Plan is a set of operating principles, requirements, and practices used to support Berkeley Lab's participation in the Large Hadron Collider Project. The LHC/QAP is intended to achieve reliable, safe, and quality performance in the LHC project activities. The LHC/QAP is also designed to fulfill the following objectives: (1) The LHC/QAP is Berkeley Lab's QA program document that describes the elements necessary to integrate quality assurance, safety management, and conduct of operations into the Berkeley Lab's portion of the LHC operations. (2) The LHC/QAP provides the framework for Berkeley Lab LHC Project administrators, managers, supervisors, and staff to plan, manage, perform, and assess their Laboratory work. (3) The LHC/QAP is the compliance document that conforms to the requirements of the Laboratory's Work Smart Standards for quality assurance (DOE O 414.1, 10 CFR 830.120), facility operations (DOE O 5480.19), and safety management (DOE P 450.4).

Gullo, Lisa; Karpenko, Victor; Robinson, Kem; Turner, William; Wong, Otis

2002-09-30T23:59:59.000Z

174

PUREX/UO{sub 3} deactivation project management plan  

SciTech Connect (OSTI)

From 1955 through 1990, the Plutonium-Uranium Extraction Plant (PUREX) provided the United States Department of Energy Hanford Site with nuclear fuel reprocessing capability. It operated in sequence with the Uranium Trioxide (UO{sub 3}) Plant, which converted the PUREX liquid uranium nitrate product to solid UO{sub 3} powder. Final UO{sub 3} Plant operation ended in 1993. In December 1992, planning was initiated for the deactivation of PUREX and UO{sub 3} Plant. The objective of deactivation planning was to identify the activities needed to establish a passively safe, environmentally secure configuration at both plants, and ensure that the configuration could be retained during the post-deactivation period. The PUREX/UO{sub 3} Deactivation Project management plan represents completion of the planning efforts. It presents the deactivation approach to be used for the two plants, and the supporting technical, cost, and schedule baselines. Deactivation activities concentrate on removal, reduction, and stabilization of the radioactive and chemical materials remaining at the plants, and the shutdown of the utilities and effluents. When deactivation is completed, the two plants will be left unoccupied and locked, pending eventual decontamination and decommissioning. Deactivation is expected to cost $233.8 million, require 5 years to complete, and yield $36 million in annual surveillance and maintenance cost savings.

Washenfelder, D.J.

1993-12-01T23:59:59.000Z

175

California Energy Commission Public Interest EnergyResearch/Energy System Integration -- Transmission-Planning Research&Development Scoping Project  

SciTech Connect (OSTI)

The objective of this Public Interest Energy Research (PIER)scoping project is to identify options for public-interest research and development (R&D) to improve transmission-planning tools, techniques, and methods. The information presented was gathered through a review of current California utility, California Independent System Operator (ISO), and related western states electricity transmission-planning activities and emerging needs. This report presents the project teams findings organized under six topic areas and identifies 17 distinct R&D activities to improve transmission-planning in California and the West. The findings in this report are intended for use, along with other materials, by PIER staff, to facilitate discussions with stakeholders that will ultimately lead to development of a portfolio of transmission-planning R&D activities for the PIER program.

Eto, Joseph H.; Lesieutre, Bernard; Widergren, Steven

2004-07-01T23:59:59.000Z

176

Project Execution Plan for Project W-211 Initial Tank Retrieval Systems (ITRS)  

SciTech Connect (OSTI)

This Project Execution Plan documents the methodology for managing Project W-211. Project W-211, Initial Tank Retrieval Systems (ITRS), is a fiscal year 1994 Major Systems Acquisition that will provide systems for retrieval of radioactive wastes from selected double-shell tanks (DST). The contents of these tanks are a combination of supernatant liquids and settled solids. To retrieve waste from the tanks, it is first necessary to mix the liquid and solids prior to transferring the slurry to alternative storage or treatment facilities. The ITRS will provide systems to mobilize the settled solids and transfer the wastes out of the tanks. In so doing, ITRS provides feed for the future waste treatment plant, allows for consolidation of tank solids to manage space within existing DST storage capacity, and supports continued safe storage of tank waste. The ITRS scope has been revised to include waste retrieval systems for tanks AP-102, AP-104, AN-102, AN-103, AN-104, AN-105, AY-102, AZ-102, and SY-102. This current tank selection and sequence provides retrieval systems supporting the River Protection Project (RF'P) Waste Treatment Facility and sustains the ability to provide final remediation of several watch list DSTs via treatment. The ITRS is configured to support changing program needs, as constrained by available budget, by maintaining the flexibility for exchanging tanks requiring mixer pump-based retrieval systems and shifting the retrieval sequence. Preliminary design was configured such that an adequate basis exists for initiating Title II design of a mixer pump-based retrieval system for any DST. This Project Execution Plan (PEP), derived from the predecessor Project Management Plan, documents the methodology for managing the ITRS, formalizes organizational responsibilities and interfaces, and identifies project requirements such as change control, design verification, systems engineering, and human factors engineering.

VAN BEEK, J.E.

2000-04-19T23:59:59.000Z

177

Investigation of Project Management Planning Practices for Renovation of Historical Buildings in Urban Contexts Located in Texas  

E-Print Network [OSTI]

This study investigated the relationship between Project Management Planning (PMP) practices and project success for preservation projects of historical significance located in an urban context. The planning for these projects was also emphasized...

Escamilla, Edelmiro

2012-07-16T23:59:59.000Z

178

UMTRA project water sampling and analysis plan -- Shiprock, New Mexico  

SciTech Connect (OSTI)

Water sampling and analysis plan (WSAP) is required for each U.S. Department of Energy (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project site to provide a basis for ground water and surface water sampling at disposal and former processing sites. This WSAP identifies and justifies the sampling locations, analytical parameters, detection limits, and sampling frequency for the monitoring stations at the Navaho Reservation in Shiprock, New Mexico, UMTRA Project site. The purposes of the water sampling at Shiprock for fiscal year (FY) 1994 are to (1) collect water quality data at new monitoring locations in order to build a defensible statistical data base, (2) monitor plume movement on the terrace and floodplain, and (3) monitor the impact of alluvial ground water discharge into the San Juan River. The third activity is important because the community of Shiprock withdraws water from the San Juan River directly across from the contaminated alluvial floodplain below the abandoned uranium mill tailings processing site.

Not Available

1994-02-01T23:59:59.000Z

179

Healy Clean Coal Project, Healy, Alaska final Environmental Monitoring Plan  

SciTech Connect (OSTI)

This Environmental Monitoring Plan (EMP) provides the mechanism to evaluate the integrated coal combustion/emission control system being demonstrated by the Healy Clean Coal Project (HCCP) as part-of the third solicitation of the US Department of Energy (DOE) Clean Coal Technology Demonstration Program (CCT-III). The EMP monitoring is intended to satisfy two objectives: (1) to develop the information base necessary for identification, assessment, and mitigation of potential environmental problems arising from replication of the technology and (2) to identify and quantify project-specific and site-specific environmental impacts predicted in the National Environmental Policy Act (NEPA) documents (Environmental Impact Statement and Record of Decision). The EMP contains a description of the background and history of development of the project technologies and defines the processes that will take place in the combustion and spray dryer absorber systems, including the formation of flash-calcined material (FCM) and its use in sulfur dioxide (SO{sub 2}) removal from the flue gases. It also contains a description of the existing environmental resources of the project area. The EMP includes two types of environmental monitoring that are to be used to demonstrate the technologies of the HCCP: compliance monitoring and supplemental monitoring. Compliance monitoring activities include air emissions, wastewater effluents, and visibility. Monitoring of these resources provide the data necessary to demonstrate that the power plant can operate under the required state and federal statutes, regulations, and permit requirements.

Not Available

1994-06-14T23:59:59.000Z

180

River Protection Project (RPP) Dangerous Waste Training Plan  

SciTech Connect (OSTI)

This supporting document contains the training plan for dangerous waste management at River Protection Project TSD Units. This document outlines the dangerous waste training program developed and implemented for all Treatment, Storage, and Disposal (TSD) Units operated by River Protection Project (RPP) in the Hanford 200 East, 200 West and 600 Areas and the <90 Day Accumulation Area at 209E. Operating TSD Units managed by RPP are: the Double-Shell Tank (DST) System, 204-AR Waste Unloading Facility, Grout, and the Single-Shell Tank (SST) System. The program is designed in compliance with the requirements of Washington Administrative Code (WAC) 173-303-330 and Title 40 Code of Federal Regulations (CFR) 265.16 for the development of a written dangerous waste training program and the Hanford Facility Permit. Training requirements were determined by an assessment of employee duties and responsibilities. The RPP training program is designed to prepare employees to operate and maintain the Tank Farms in a safe, effective, efficient, and environmentally sound manner. In addition to preparing employees to operate and maintain the Tank Farms under normal conditions, the training program ensures that employees are prepared to respond in a prompt and effective manner should abnormal or emergency conditions occur. Emergency response training is consistent with emergency responses outlined in the following Building Emergency Plans: HNF-IP-0263-TF and HNF-=IP-0263-209E.

POHTO, R.E.

2000-03-09T23:59:59.000Z

Note: This page contains sample records for the topic "improvement project plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


181

UMTRA project water sampling and analysis plan, Monument Valley, Arizona  

SciTech Connect (OSTI)

The Monument Valley Uranium Mill Tailings Remedial Action (UMTRA) Project site in Cane Valley is a former uranium mill that has undergone surface remediation in the form of tailings and contaminated materials removal. Contaminated materials from the Monument Valley (Arizona) UMTRA Project site have been transported to the Mexican Hat (Utah) UMTRA Project site for consolidation with the Mexican Hat tailings. Tailings removal was completed in February 1994. Three geologic units at the site contain water: the unconsolidated eolian and alluvial deposits (alluvial aquifer), the Shinarump Conglomerate (Shinarump Member), and the De Chelly Sandstone. Water quality analyses indicate the contaminant plume has migrated north of the site and is mainly in the alluvial aquifer. An upward hydraulic gradient in the De Chelly Sandstone provides some protection to that aquifer. This water sampling and analysis plan recommends sampling domestic wells, monitor wells, and surface water in April and September 1994. The purpose of sampling is to continue periodic monitoring for the surface program, evaluate changes to water quality for site characterization, and provide data for the baseline risk assessment. Samples taken in April will be representative of high ground water levels and samples taken in September will be representative of low ground water levels. Filtered and nonfiltered samples will be analyzed for plume indicator parameters and baseline risk assessment parameters.

Not Available

1994-04-01T23:59:59.000Z

182

Project Specific Quality Assurance Plan Project (QAPP) W-211 Initial Tank Retrieval Systems (ITRS)  

SciTech Connect (OSTI)

This Quality Assurance Program Plan (QAPP) provides information on how the Project Hanford Quality Assurance Program is implemented by CH2M HILL Hanford Group Inc (CHG) for managing the Initial Tank Retrieval Systems (ITRS), Project W-211. This QAPP is responsive to the CHG Quality Assurance Program Description (QAPD) (LMH-MP-599) which provides direction for compliance to 10 CFR 830 120, ''Nuclear Safety Management, Quality Assurance Requirements'', and DOE Order 5700 6C, ''Quality Assurance'' Project W-211 modifies existing facilities and provides systems for retrieval of radioactive wastes from selected double-shell tanks (DST). The contents of these tanks are a combination of supernatant liquids and settled solids. To retrieve waste from the tanks, it is first necessary to mix the liquid and solids prior to transferring the slurry to alternative storage or treatment facilities. The ITRS will provide systems to mobilize the settled solids and transfer the wastes out of the tanks. In so doing, ITRS provides feed for future processing plants, allows for consolidation of tank solids to manage space within existing DST storage capacity, and supports continued safe storage of tank waste. This project includes the design, procurement, construction, startup and turnover of these retrieval systems This QAPP identifies organizational structures and responsibilities. Implementing procedures used by CHG project management can be found in the CHG Quality Assurance Program (CHG QAP) Implementation Matrix located in HNF-IP-0842, Volume XI, Attachment Proposed verification and inspection activities for critical items within the scope of project W-211 are identified in Attachment 1 W-211. Project participants will identify the implementing procedures used by their organization within their QAF'Ps. This project specific QAPP is used to identify requirements in addition to the QAPD and provide, by reference, additional information to other project documents.

HALL, L.R.

2000-02-01T23:59:59.000Z

183

RNR, 4/2010 Faculty/Project Documents/Communication/FASIS Communication Plan.docx  

E-Print Network [OSTI]

RNR, 4/2010 Faculty/Project Documents/Communication/FASIS Communication Plan.docx FASIS Communication Plan This document is to be used as a tool to plan and track distributed information about. Plan Outline 1. Target Audiences 2. Communication Media 3. Specific Communication Events 1. Target

Shull, Kenneth R.

184

Department of Energy Report and Agency Improvement Plan  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE:Year in Review: TopEnergy DOEDealing WithDevelopmentReport and Agency Improvement Plan For

185

U.S. Department of Energy Uranium Mill Tailings Remedial Action Ground Water Project: Project plan  

SciTech Connect (OSTI)

The scope of the Project is to develop and implement a ground water compliance strategy for all 24 UMTRA Project processing sites. The compliance strategy for the processing sites must satisfy the proposed EPA ground water cleanup standards in 40 CFR Part 192, Subparts B and C (1987). This scope of work will entail the following activities on a site-specific basis: Develop a compliance strategy based on modification of the UMTRA Surface Project RAPs or develop Ground Water Project RAPs with NRC concurrence on the RAP and full participation of the affected states and tribes. Implement the RAP to include institutional controls, where appropriate, as an interim measure until compliance with the standards is achieved. Institute long-term verification monitoring for transfer to a separate long-term surveillance program on or before the Project end date. Prepare certification or confirmation reports and modify the long-term surveillance plan (LTSP), where needed, on those sites completed prior to the Project end date.

Not Available

1994-09-01T23:59:59.000Z

186

Renewal project improves scrubbers' long-term corrosion resistance  

SciTech Connect (OSTI)

This article describes a five-year scrubber renewal plan aimed at reducing corrosion-induced maintenance costs at its Gibbons Creek plant. Texas Municipal Power Agency (TMPA) owns and operates the 443-MW Gibbons Creek Station. The scrubber system started up in 1982, but by late 1990 TMPA found it necessary to develop a 5-year scrubber renewal plan to improve its reliability and reduce operation and maintenance costs. Upgrading the system's original construction materials became an important component of the plan. The Gibbons Creek Steam Electric Station, located near Carlos, Texas, consists of a single, lignite-fired unit. Fuel is supplied from a captive mine located adjacent to the plant site. Air pollution control equipment serving the plant includes an electrostatic precipitator and a wet limestone scrubber system.

Weilert, C.V.; Ashton, S.M.; Campbell, F.W.; Norton, R.D.; Hamilton, R.

1994-12-01T23:59:59.000Z

187

Cover sheet: Web Improvement Project: Preliminary Business Case  

E-Print Network [OSTI]

UEC on a number of priorities, models and questions to inform the development of a full business caseCover sheet: Web Improvement Project: Preliminary Business Case Aims of Preliminary Business Case This preliminary business case is intended to update the University Executive Committee on progress to

Wirosoetisno, Djoko

188

Environmental permits and approvals plan for high-level waste interim storage, Project W-464  

SciTech Connect (OSTI)

This report discusses the Permitting Plan regarding NEPA, SEPA, RCRA, and other regulatory standards and alternatives, for planning the environmental permitting of the Canister Storage Building, Project W-464.

Deffenbaugh, M.L.

1998-05-28T23:59:59.000Z

189

Tank waste remediation system privatization phase I infrastructure and project W-519 and QA implementation plan  

SciTech Connect (OSTI)

This document has been prepared to identify the quality requirements for all products/activities developed by or for Project W-519. This plan is responsive to the Numatec Hanford Corporation, Quality Assurance Program Plan, NHC-MP-001.

HUSTON, J.J.

1999-08-19T23:59:59.000Z

190

Performance improvement plan use in implementing conduct of operations  

SciTech Connect (OSTI)

The Nuclear Materials Processing and Waste Management and Environmental Restoration Divisions (NMPD/WMER) of the Westinghouse Savannah River Company (WSRC) operate nineteen individual facilities at Savannah River Site (SRS). These facilities produce the fuel and target assemblies for the SRS Reactors: extract Tritium, Plutonium, Uranium and other isotopes from the irradiated fuel and targets; safely store the radioactive waste from ongoing operations; and encapsulate the waste in a final waste form for long term disposal. Continuous improvement in the operation of all facilities and in the conduct of business at SRS is the goal embodied in the NMPD/WMER Performance Improvement Plan (PIP) discussed in this document. The NMPD/WMER PIP is the mechanism used to establish a basis for operations that will lead to achievement of a performance level that will meet or exceed the standards developed and used in the commercial nuclear power industry.

Baumhardt, R.J.

1992-06-01T23:59:59.000Z

191

Performance improvement plan use in implementing conduct of operations  

SciTech Connect (OSTI)

The Nuclear Materials Processing and Waste Management and Environmental Restoration Divisions (NMPD/WMER) of the Westinghouse Savannah River Company (WSRC) operate nineteen individual facilities at Savannah River Site (SRS). These facilities produce the fuel and target assemblies for the SRS Reactors: extract Tritium, Plutonium, Uranium and other isotopes from the irradiated fuel and targets; safely store the radioactive waste from ongoing operations; and encapsulate the waste in a final waste form for long term disposal. Continuous improvement in the operation of all facilities and in the conduct of business at SRS is the goal embodied in the NMPD/WMER Performance Improvement Plan (PIP) discussed in this document. The NMPD/WMER PIP is the mechanism used to establish a basis for operations that will lead to achievement of a performance level that will meet or exceed the standards developed and used in the commercial nuclear power industry.

Baumhardt, R.J.

1992-01-01T23:59:59.000Z

192

Fluid management plan for the Project Shoal Area Offsites Subproject  

SciTech Connect (OSTI)

The US Department of Energy, Nevada Operations Office (DOE/NV) has initiated the Offsites Subproject to characterize the hazards posed to human health and the environment as a result of underground nuclear testing activities at facilities other than the Nevada Test Site (NTS). A primary Subproject objective is to gather adequate data to characterize the various Subproject sites through the collection of surface and subsurface soil samples and by drilling several wells for the collection of groundwater data. The Project Shoal Area (PSA) is one of the Subproject`s Nevada sites and is subject to the requirements set forth in the Federal Facility Compliance Agreement and Consent Order (FFACO) (DOE, 1996a). In accordance with the FFACO, a Corrective Action Investigation Plan (CAIP) has been developed for work at the PSA (designated as Corrective Action Unit Number 416). This Fluid Management Plan (FMP) provides guidance for the management of fluids generated from wells constructed at the PSA. Long-term monitoring and future activities at the site, if required, will be set forth in additional documents as required by the FFACO. The ultimate method for disposition of fluids generated by site operations depends upon sample analysis and process knowledge in relation to fluid management criteria. Section 2 describes well site operations; Section 3 discusses fluid management criteria; Section 4 includes the fluid monitoring program; Section 5 presents the fluid management strategy; Section 6 provides for fluid management during routine well monitoring; and Section 7 contains reporting criteria.

NONE

1996-08-01T23:59:59.000Z

193

Socio-economic benefits in Plan Vivo projects: Trees for Global Benefits, Uganda 50 Appendix 6.6  

E-Print Network [OSTI]

for the Socio-economic study of a carbon offset Plan Vivo project. The methodology has been developed initially in the Jindal studies 2004 and 2008 (on the Nhambita Community Carbon Project, Envirotrade Plan Vivo project

194

E-Print Network 3.0 - application project planning Sample Search...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

R0 Page 1 of 42 Summary: are initiated and documented according to applicable ERSS procedures. 12;QA Project Plan Los Alamos National... with applicable procedures....

195

Data Management Plan for The Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project  

Broader source: Energy.gov [DOE]

The Data Management Plan describes how DOE will handle data submitted by recipients as deliverables under the Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project.

196

Quality Assurance Program Plan (QAPP) Waste Management Project  

SciTech Connect (OSTI)

This document is the Quality Assurance Program Plan (QAPP) for Waste Management Federal Services of Hanford, Inc. (WMH), that implements the requirements of the Project Hanford Management Contract (PHMC), HNF-MP-599, Project Hanford Quality Assurance Program Description (QAPD) document, and the Hanford Federal Facility Agreement with Consent Order (Tri-Party Agreement), Sections 6.5 and 7.8. WHM is responsible for the treatment, storage, and disposal of liquid and solid wastes generated at the Hanford Site as well as those wastes received from other US Department of Energy (DOE) and non-DOE sites. WMH operations include the Low-Level Burial Grounds, Central Waste Complex (a mixed-waste storage complex), a nonradioactive dangerous waste storage facility, the Transuranic Storage Facility, T Plant, Waste Receiving and Processing Facility, 200 Area Liquid Effluent Facility, 200 Area Treated Effluent Disposal Facility, the Liquid Effluent Retention Facility, the 242-A Evaporator, 300 Area Treatment Effluent Disposal Facility, the 340 Facility (a radioactive liquid waste handling facility), 222-S Laboratory, the Waste Sampling and Characterization Facility, and the Hanford TRU Waste Program.

VOLKMAN, D.D.

1999-10-27T23:59:59.000Z

197

Chernobyl shelter implementation plan -- project development and planning: Setting the stage for progress  

SciTech Connect (OSTI)

On April 26, 1986, the Chernobyl nuclear power plant (NPP) experienced a devastating accident. This accident left much of the plant and its safety systems destroyed with widespread radioactive waste contamination from the damaged nuclear fuel. In the 6 months following the accident, heroic measures were taken to stabilize the situation and erect a temporary confinement shelter over the damaged unit 4. Since that time the shelter and the contained radioactive materials and debris have begun to deteriorate. Lack of funding and staff has allowed only minor improvements to occur on-site, resulting in an existing shelter that is unstable and deteriorating. International aid has been provided to develop a comprehensive plan for the safe and environmentally sound conversion of the damaged Chernobyl reactor. These efforts are being performed in conjunction with US experts, European experts, and local Chernobyl NPP personnel. This plan is discussed here.

Johnson, W. [Parsons Infrastructure and Technology Group, Richland, WA (United States); Kreid, D. [Pacific Northwest National Lab., Richland, WA (United States); DeFranco, W. [Science Applications International Corp., Oak Ridge, TN (United States)

1998-09-01T23:59:59.000Z

198

Project plan, Hazardous Materials Management and Emergency Response Training Center: Project 95L-EWT-100  

SciTech Connect (OSTI)

The Hazardous Materials Management and Emergency Response (HAMMER) Training Center will provide for classroom lectures and hands-on practical training in realistic situations for workers and emergency responders who are tasked with handling and cleanup of toxic substances. The primary objective of the HAMMER project is to provide hands-on training and classroom facilities for hazardous material workers and emergency responders. This project will also contribute towards complying with the planning and training provisions of recent legislation. In March 1989 Title 29 Code of Federal Regulations Occupational Safety and Health Administration 1910 Rules and National Fire Protection Association Standard 472 defined professional requirements for responders to hazardous materials incidents. Two general types of training are addressed for hazardous materials: training for hazardous waste site workers and managers, and training for emergency response organizations.

Borgeson, M.E.

1994-11-09T23:59:59.000Z

199

Computer Science MS degree Plan C Certification of Project, Report, and Oral Presentation Requirements  

E-Print Network [OSTI]

Computer Science MS degree Plan C Certification of Project, Report, and Oral Presentation of Project or Activity Course Instructor Initial here ___ Project: ____ Half - (50-99 hours expected effort *************************************************************************************************************** Term/Yr Course Number Course Name Instructor Grade Brief Description of Project or Activity Course

Minnesota, University of

200

Configuration Management Plan for Tank Farm Restoration and Safe Operations Project W-314  

SciTech Connect (OSTI)

The Configuration Management Plan for Project W-314 describes the systems, processes and procedures for implementation of applicable configuration management practices described in HNF-0842, Volume 111, Section 3.1, ''Configuration Management Implementation''. This plan is tailored specifically for use by Project W-314.

MCGREW, D.L.

2000-04-19T23:59:59.000Z

Note: This page contains sample records for the topic "improvement project plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


201

Risk Management Plan for Tank Farm Restoration and Safe Operations Project W-314  

SciTech Connect (OSTI)

The Risk Management Plan for Project W-314 describes the systems, processes and procedures for implementation of applicable risk management practices described in HNF-0842, Volume IV, Section 2.6, ''Risk Management''. This plan is tailored specifically for use by Project W-314.

MCGREW, D.L.

2000-04-19T23:59:59.000Z

202

Legacy Management CERCLA Sites. Quality Assurance Project Plan  

SciTech Connect (OSTI)

S.M. Stoller Corporation is the contractor for the Technical Assistance Contract (TAC) for the U.S. Department of Energy (DOE) Office of Legacy Management (LM) operations. Stoller employs a management system that applies to all programs, projects, and business management systems funded through DOE-LM task orders. The management system incorporates the philosophy, policies, and requirements of health and safety, environmental compliance, and quality assurance (QA) in all aspects of project planning and implementation. Health and safety requirements are documented in the Health and Safety Manual (STO 2), the Radiological Control Manual (STO 3), the Integrated Safety Management System Description (STO 10), and the Drilling Health and Safety Requirements (STO 14). Environmental compliance policy and requirements are documented in the Environmental Management Program Implementation Manual (STO 11). The QA Program is documented in the Quality Assurance Manual (STO 1). The QA Manual (STO 1) implements the specific requirements and philosophy of DOE Order 414.1C, Quality Assurance. This manual also includes the requirements of other standards that are regularly imposed by customers, regulators, or other DOE orders. Title 10 Code of Federal Regulations Part 830, “Quality Assurance Requirements,” ANSI/ASQC E4-2004, “Quality Systems for Environmental Data and Technology Programs – Requirements with Guidance for Use,” and ISO 14001-2004, “Environmental Management Systems,” have been included. These standards are similar in content. The intent of the QA Manual (STO 1) is to provide a QA management system that incorporates the requirements and philosophy of DOE and other customers within the QA Manual. Criterion 1, “Quality Assurance Program,” identifies the fundamental requirements for establishing and implementing the QA management system; QA Instruction (QAI) 1.1, “QA Program Implementation,” identifies the TAC organizations that have responsibility for implementing the QA program requirements; and Appendix C of the QA Manual provides comparison tables that identify where the requirements of other standards are addressed in the QA Manual.

None

2007-05-03T23:59:59.000Z

203

Recommendations for improvements to program and project management  

SciTech Connect (OSTI)

Oak Ridge National Laboratory (ORNL) has operated with a balanced matrix organization for over sixteen years. Much of the work at the Laboratory is accomplished with good customer satisfaction through programs, projects, and matrix management. During the past several years concerns about program and project management at ORNL have been expressed by both the Department of Energy and ORNL staff. In May 1993 the ORNL Division/Program/Office Directors Caucus chartered a ``fox team`` to identity and to recommend improvements to matrix management that would lead to resolution of these concerns. Nine experienced ORNL staff members served on this Matrix Management Upgrade Solutions Team (MMUST). The MMUST adopted a four-phase approach in which they first gathered information and then developed and proposed recommended actions. In the fourth phase the team was available to support implementation of the recommendations. They began work in June 1993, gathering and evaluating information in biweekly meetings for six months. Recommendations developed in October and November 1993 were presented to ORNL management in December. The MMUST issued three principal recommendations based on their evaluation of the information gathered. They are: Renew and enhance the ORNL management commitment to matrix management, program managers, and project managers; Implement actions to ensure career path parity between the program/project manager family of positions and the technical line manager family of positions across all directorates and divisions; and Clarify and document program/project manager roles, responsibilities, and authorities.

Not Available

1994-01-01T23:59:59.000Z

204

Quality Assurance Program Plan (QAPP) Waste Management Project  

SciTech Connect (OSTI)

The Waste Management Project (WMP) is committed to excellence in our work and to delivering quality products and services to our customers, protecting our employees and the public and to being good stewards of the environment. We will continually strive to understand customer requirements, perform services, and activities that meet or exceed customer expectations, and be cost-effective in our performance. The WMP maintains an environment that fosters continuous improvement in our processes, performance, safety and quality. The achievement of quality will require the total commitment of all WMP employees to our ethic that Quality, Health and Safety, and Regulatory Compliance must come before profits. The successful implementation of this policy and ethic requires a formal, documented management quality system to ensure quality standards are established and achieved in all activities. The following principles are the foundation of our quality system. Senior management will take full ownership of the quality system and will create an environment that ensures quality objectives are met, standards are clearly established, and performance is measured and evaluated. Line management will be responsible for quality system implementation. Each organization will adhere to all quality system requirements that apply to their function. Every employee will be responsible for their work quality, to work safely and for complying with the policies, procedures and instructions applicable to their activities. Quality will be addressed and verified during all phases of our work scope from proposal development through closeout including contracts or projects. Continuous quality improvement will be an ongoing process. Our quality ethic and these quality principles constantly guide our actions. We will meet our own quality expectations and exceed those of our customers with vigilance, commitment, teamwork, and persistence.

HORHOTA, M.J.

2000-12-21T23:59:59.000Z

205

The CHPRC Groundwater and Technical Integration Support (Master Project) Quality Assurance Management Plan  

SciTech Connect (OSTI)

The scope of the CH2M Hill Plateau Remediation Company, LLC (CHPRC) Groundwater and Technical Integration Support (Master Project) is for Pacific Northwest National Laboratory staff to provide technical and integration support to CHPRC. This work includes conducting investigations at the 300-FF-5 Operable Unit and other groundwater operable units, and providing strategic integration, technical integration and assessments, remediation decision support, and science and technology. The projects under this Master Project will be defined and included within the Master Project throughout the fiscal year, and will be incorporated into the Master Project Plan. This Quality Assurance Management Plan provides the quality assurance requirements and processes that will be followed by the CHPRC Groundwater and Technical Integration Support (Master Project) and all releases associated with the CHPRC Soil and Groundwater Remediation Project. The plan is designed to be used exclusively by project staff.

Fix, N. J.

2009-04-03T23:59:59.000Z

206

Standard Measurement and Verification Plan for Lighting Retrofit Projects for Buildings and Building Sites  

SciTech Connect (OSTI)

This document provides a framework for standard measurement and verification (M&V) of lighting retrofit and replacement projects. It was developed to provide site owners, contractors, and other involved organizations with the essential elements of a robust M&V plan for lighting projects. It includes details on all aspects of effectively measuring light levels of existing and post-retrofit projects, conducting power measurement, and developing cost-effectiveness analysis. This framework M&V plan also enables consistent comparison among similar lighting projects, and may be used to develop M&V plans for non--lighting-technology retrofits and new installations.

Richman, Eric E.

2012-10-31T23:59:59.000Z

207

Project W-314 Specific Test and Evaluation Plan 241-AN-A Valve Pit  

SciTech Connect (OSTI)

The purpose of this Specific Test and Evaluation Plan (STEP) is to provide a detailed written plan for the systematic testing of modifications made to the 241-AN-A Valve Pit by the W-314 Project. The STEP develops the outline for test procedures that verify the system's performance to the established Project design criteria. The STEP is a lower tier document based on the W-314 Test and Evaluation Plan (TEP).

HAMMERS, J.S.

1999-08-25T23:59:59.000Z

208

Final Hanford Site Transuranic (TRU) Waste Characterization QA Project Plan  

SciTech Connect (OSTI)

The Transuranic Waste Characterization Quality Assurance Program Plan required each US Department of Energy (DOE) site that characterizes transuranic waste to be sent the Waste Isolation Pilot Plan that addresses applicable requirements specified in the QAPP.

GREAGER, T.M.

1999-09-09T23:59:59.000Z

209

FTEP teaching improvement project '04. S. Pollock, N. Finkelstein, and M. Dubson. Summary: The FTEP summer teaching improvement project provided support for three  

E-Print Network [OSTI]

of this summer project: (See also the "Primer on Tutorials for CU Faculty" ) A) Available materials developedFTEP teaching improvement project '04. S. Pollock, N. Finkelstein, and M. Dubson. Summary: The FTEP summer teaching improvement project provided support for three faculty members to devote significant time

Colorado at Boulder, University of

210

NIST Mobility and Manipulation Project Needs and Plans The NIST Mobility and Manipulation (MM) Project is seeking government, industry  

E-Print Network [OSTI]

. The project testbed includes an industrial robot mounted on a linear rail. The MM Project also plans characterizing components of the new NIST robot testbed, which includes a six-axis industrial robot arm under that are of concern to industry. Real world applications are also highly beneficial for developing and evaluating

Perkins, Richard A.

211

The Groundwater Performance Assessment Project Quality Assurance Plan  

SciTech Connect (OSTI)

This document provides the quality assurance guidelines that will be followed by the groundwater project.

Walker, Thomas G.

2005-01-26T23:59:59.000Z

212

Classroom HVAC: Improving ventilation and saving energy -- field study plan  

E-Print Network [OSTI]

in this study. Classroom HVAC: Improving Ventilation andV8doc.sas.com/sashtml. Classroom HVAC: Improving VentilationBerkeley, CA 94720. Classroom HVAC: Improving Ventilation

Apte, Michael G.; Faulkner, David; Hodgson, Alfred T.; Sullivan, Douglas P.

2004-01-01T23:59:59.000Z

213

Design and implementation of a financial planning and tracking system for the Nova Project  

SciTech Connect (OSTI)

The Nova project is a 185 million dollar DOE funded project to build an experimental facility to demonstrate the thermonuclear ignition of laser fusion targets. This paper describes the design and implementation considerations for the project's computerized performance measurement financial planning and tracking system and critiques its actual operation.

Holcomb, F.

1982-01-01T23:59:59.000Z

214

Friday February 20, 2004 Three compromise plans eyed for fusion project site  

E-Print Network [OSTI]

Friday February 20, 2004 Three compromise plans eyed for fusion project site A team of experts on an international nuclear fusion project has drawn up three compromise proposals in a bid to resolve the row over said. The six parties involved in the Thermonuclear Experimental Reactor (ITER) project have been

215

Standard Measurement & Verification Plan for Lighting Equipment Retrofit or Replacement Projects  

SciTech Connect (OSTI)

This document provides a framework for a standard Measurement and Verification (M&V) plan for lighting projects. It was developed to support cost-effective retrofits (partial and complete replacements) of lighting systems and is intended to provide a foundation for an M&V plan for a lighting retrofit utilizing a "best practice" approach, and to provide guidance to site owners, contractors, and other involved organizations on what is essential for a robust M&V plan for lighting projects. This document provides examples of appropriate elements of an M&V plan, including the calculation of expected energy savings. The standard M&V plan, as provided, also allows for consistent comparison with other similar lighting projects. Although intended for lighting retrofit applications, M&V plans developed per this framework document may also be used for other non-lighting technology retrofits and new installations.

Richman, Eric E.

2009-11-04T23:59:59.000Z

216

Lake Roosevelt Rainbow Trout Habitat/Passage Improvement Project, Annual Report 2002-2003.  

SciTech Connect (OSTI)

The construction of Chief Joseph and Grand Coulee Dams completely and irrevocably blocked anadromous fish migrations to the Upper Columbia River. Historically this area hosted vast numbers of salmon returning to their natal waters to reproduce and die. For the native peoples of the region, salmon and steelhead were a principle food source, providing physical nourishment and spiritual sustenance, and contributing to the religious practices and the cultural basis of tribal communities. The decaying remains of spawned-out salmon carcasses contributed untold amounts of nutrients into the aquatic, aerial, and terrestrial ecosystems of tributary habitats in the upper basin. Near the present site of Kettle Falls, Washington, the second largest Indian fishery in the state existed for thousands of years. Returning salmon were caught in nets and baskets or speared on their migration to the headwater of the Columbia River in British Columbia. Catch estimates at Kettle Falls range from 600,000 in 1940 to two (2) million around the turn of the century (UCUT, Report No.2). The loss of anadromous fish limited the opportunities for fisheries management and enhancement exclusively to those actions addressed to resident fish. The Lake Roosevelt Rainbow Trout Habitat/Passage Improvement Project is a mitigation project intended to enhance resident fish populations and to partially mitigate for anadromous fish losses caused by hydropower system impacts. This substitution of resident fish for anadromous fish losses is considered in-place and out-of-kind mitigation. Upstream migration and passage barriers limit the amount of spawning and rearing habitat that might otherwise be utilized by rainbow trout. The results of even limited stream surveys and habitat inventories indicated that a potential for increased natural production exists. However, the lack of any comprehensive enhancement measures prompted the Upper Columbia United Tribes Fisheries Center (UCUT), Colville Confederated Tribes (CCT), Spokane Tribe of Indians (STI) and Washington Department of Fish and Wildlife (WDFW) to develop and propose a comprehensive fishery management plan for Lake Roosevelt. The Rainbow Trout Habitat/Passage Improvement Project (LRHIP) was designed with goals directed towards increasing natural production while maintaining genetic integrity among current tributary stocks. The initial phase of the Lake Roosevelt Habitat Improvement Project (Phase I, baseline data collection: 1990-91) was focused on the assessment of limiting factors, including the quality and quantity of available spawning gravel, identification of passage barriers, and assessment of other constraints. After the initial assessment of stream parameters, five streams meeting specific criteria were selected for habitat/passage improvement projects (Phase II, implementation -1992-1995). Four of these projects were on the Colville Indian Reservation South Nanamkin, North Nanamkin, Louie and Iron Creeks and one Blue Creek was on the Spokane Indian Reservation. At the completion of project habitat improvements, the final phase (Phase III, monitoring-1996-2000) began. This phase assessed the changes and determined the success achieved through the improvements. Data analysis showed that passage improvements are successful for increasing habitat availability and use. The results of in-stream habitat improvements were inconclusive. Project streams, to the last monitoring date, have shown increases in fish density following implementation of the improvements. In 2000 Bridge Creek, on the Colville Reservation was selected for the next phase of improvements. Data collection, including baseline stream survey and population data collection, was carried out during 2001 in preparation for the design and implementation of stream habitat/passage improvements. Agencies cooperating on the project include the Colville Confederated Tribes (CCT), Natural Resource Conservation Service (NRCS, Ferry County District), Ferry County Conservation District, and Ferry County. The Bonneville Power Administration (BPA) provided

Sears, Sheryl

2004-01-01T23:59:59.000Z

217

Lake Roosevelt Rainbow Trout Habitat/Passage Improvement Project, Annual Report 2001-2002.  

SciTech Connect (OSTI)

The construction of Chief Joseph and Grand Coulee Dams completely and irrevocably blocked anadromous fish migrations to the Upper Columbia River. Historically this area hosted vast numbers of salmon returning to their natal waters to reproduce and die. For the native peoples of the region, salmon and steelhead were a principle food source, providing physical nourishment and spiritual sustenance, and contributing to the religious practices and the cultural basis of tribal communities. The decaying remains of spawned-out salmon carcasses contributed untold amounts of nutrients into the aquatic, aerial, and terrestrial ecosystems of tributary habitats in the upper basin. Near the present site of Kettle Falls, Washington, the second largest Indian fishery in the state existed for thousands of years. Returning salmon were caught in nets and baskets or speared on their migration to the headwater of the Columbia River in British Columbia. Catch estimates at Kettle Falls range from 600,000 in 1940 to two (2) million around the turn of the century (UCUT, Report No.2). The loss of anadromous fish limited the opportunities for fisheries management and enhancement exclusively to those actions addressed to resident fish. The Lake Roosevelt Rainbow Trout Habitat/Passage Improvement Project is a mitigation project intended to enhance resident fish populations and to partially mitigate for anadromous fish losses caused by hydropower system impacts. This substitution of resident fish for anadromous fish losses is considered in-place and out-of-kind mitigation. Upstream migration and passage barriers limit the amount of spawning and rearing habitat that might otherwise be utilized by rainbow trout. The results of even limited stream surveys and habitat inventories indicated that a potential for increased natural production exists. However, the lack of any comprehensive enhancement measures prompted the Upper Columbia United Tribes Fisheries Center (UCUT), Colville Confederated Tribes (CCT), Spokane Tribe of Indians (STI) and Washington Department of Fish and Wildlife (WDFW) to develop and propose a comprehensive fishery management plan for Lake Roosevelt. The Rainbow Trout Habitat/Passage Improvement Project (LRHIP) was designed with goals directed towards increasing natural production while maintaining genetic integrity among current tributary stocks. The initial phase of the Lake Roosevelt Habitat Improvement Project (Phase I, baseline data collection: 1990-91) was focused on the assessment of limiting factors, including the quality and quantity of available spawning gravel, identification of passage barriers, and assessment of other constraints. After the initial assessment of stream parameters, five streams meeting specific criteria were selected for habitat/passage improvement projects (Phase II, implementation -1992-1995). Four of these projects were on the Colville Indian Reservation South Nanamkin, North Nanamkin, Louie and Iron Creeks and one Blue Creek was on the Spokane Indian Reservation. At the completion of project habitat improvements, the final phase (Phase III, monitoring-1996-2000) began. This phase assessed the changes and determined the success achieved through the improvements. Data analysis showed that passage improvements are successful for increasing habitat availability and use. The results of in-stream habitat improvements were inconclusive. Project streams, to the last monitoring date, have shown increases in fish density following implementation of the improvements. In 2000 Bridge Creek, on the Colville Reservation was selected for the next phase of improvements. Data collection, including baseline stream survey and population data collection, was carried out during 2001 in preparation for the design and implementation of stream habitat/passage improvements. Agencies cooperating on the project include the Colville Confederated Tribes (CCT), Natural Resource Conservation Service (NRCS, Ferry County District), Ferry County Conservation District, and Ferry County. The Bonneville Power Administration (BPA) provided

Sears, Sheryl

2003-01-01T23:59:59.000Z

218

Columbia Basin Wildlife Mitigation Project : Rainwater Wildlife Area Final Management Plan.  

SciTech Connect (OSTI)

This Draft Management Plan has been developed by the Confederated Tribes of the Umatilla Indian Reservation (CTUIR) to document how the Rainwater Wildlife Area (formerly known as the Rainwater Ranch) will be managed. The plan has been developed under a standardized planning process developed by the Bonneville Power Administration (BPA) for Columbia River Basin Wildlife Mitigation Projects (See Appendix A and Guiding Policies Section below). The plan outlines the framework for managing the project area, provides an assessment of existing conditions and key resource issues, and presents an array of habitat management and enhancement strategies. The plan culminates into a 5-Year Action Plan that will focus our management actions and prioritize funding during the Fiscal 2001-2005 planning period. This plan is a product of nearly two years of field studies and research, public scoping, and coordination with the Rainwater Advisory Committee. The committee consists of representatives from tribal government, state agencies, local government, public organizations, and members of the public. The plan is organized into several sections with Chapter 1 providing introductory information such as project location, purpose and need, project goals and objectives, common elements and assumptions, coordination efforts and public scoping, and historical information about the project area. Key issues are presented in Chapter 2 and Chapter 3 discusses existing resource conditions within the wildlife area. Chapter 4 provides a detailed presentation on management activities and Chapter 5 outlines a monitoring and evaluation plan for the project that will help assess whether the project is meeting the intended purpose and need and the goals and objectives. Chapter 6 displays the action plan and provides a prioritized list of actions with associated budget for the next five year period. Successive chapters contain appendices, references, definitions, and a glossary.

Childs, Allen

2002-03-01T23:59:59.000Z

219

Riding the Clean Energy Wave: New Projects Aim to Improve Water...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Riding the Clean Energy Wave: New Projects Aim to Improve Water Power Devices Riding the Clean Energy Wave: New Projects Aim to Improve Water Power Devices April 16, 2014 - 1:56pm...

220

One of EM's Last Recovery Act Projects at Oak Ridge Improves...  

Office of Environmental Management (EM)

One of EM's Last Recovery Act Projects at Oak Ridge Improves Safety at Laboratory One of EM's Last Recovery Act Projects at Oak Ridge Improves Safety at Laboratory November 26,...

Note: This page contains sample records for the topic "improvement project plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


221

EV Community Readiness projects: South Florida Regional Planning...  

Broader source: Energy.gov (indexed) [DOE]

3 Clean Cities EV Community Readiness Florida Gold Coast Sustainable Community Planning for Electric Vehicle and Charging Infrastructure PI: Christine Heshmati, South Florida...

222

Project Execution Plan for Project W-211 Initial Tank Retrieval Systems (ITRS)  

SciTech Connect (OSTI)

Project W-211, Initial Tank Retrieval Systems (ITRS), is a fiscal year 1994 Major Systems Acquisition that will provide systems for retrieval of radioactive wastes from selected double-shell tanks (DST). The contents of these tanks are a combination of supernatant liquids and settled solids. To retrieve waste from the tanks, it is first necessary to mix the liquid and solids prior to transferring the slurry to alternative storage or treatment facilities. The ITRS will provide systems to mobilize the settled solids and transfer the wastes out of the tanks. In so doing, ITRS provides feed for future processing plants, allows for consolidation of tank solids to manage space within existing DST storage capacity, and supports continued safe storage of tank waste. The ITRS scope has been revised to include waste retrieval systems for tanks AP-102, AP-104, AP-108, AN-103, AN-104, AN-105, AY-102, AZ-102, and SY-102. This current tank selection and sequence provides retrieval systems supporting the Privatized waste processing plant and sustains the ability to provide final remediation of several watch list DSTs via treatment. The ITRS is configured to support changing program needs, as constrained by available budget, by maintaining the flexibility for exchanging tanks requiring mixer pump-based retrieval systems and shifting the retrieval sequence. Preliminary design was configured such that an adequate basis exists for initiating Title II design of a mixer pump based retrieval system for any DST. This Project Management Plan (PMP) documents the methodology for managing the ITRS, formalizes organizational responsibilities and interfaces, and identifies project requirements such as change control, design verification, systems engineering, and human factors engineering.

VAN BEEK, J.E.

1999-09-02T23:59:59.000Z

223

Rainwater Wildlife Area, Watershed Management Plan, A Columbia Basin Wildlife Mitigation Project, 2002.  

SciTech Connect (OSTI)

This Management Plan has been developed by the Confederated Tribes of the Umatilla Indian Reservation (CTUIR) to document how the Rainwater Wildlife Area (formerly known as the Rainwater Ranch) will be managed. The plan has been developed under a standardized planning process developed by the Bonneville Power Administration (BPA) for Columbia River Basin Wildlife Mitigation Projects (See Appendix A and Guiding Policies Section below). The plan outlines the framework for managing the project area, provides an assessment of existing conditions and key resource issues, and presents an array of habitat management and enhancement strategies. The plan culminates into a 5-Year Action Plan that will focus our management actions and prioritize funding during the Fiscal 2001-2005 planning period. This plan is a product of nearly two years of field studies and research, public scoping, and coordination with the Rainwater Advisory Committee. The committee consists of representatives from tribal government, state agencies, local government, public organizations, and members of the public. The plan is organized into several sections with Chapter 1 providing introductory information such as project location, purpose and need, project goals and objectives, common elements and assumptions, coordination efforts and public scoping, and historical information about the project area. Key issues are presented in Chapter 2 and Chapter 3 discusses existing resource conditions within the wildlife area. Chapter 4 provides a detailed presentation on management activities and Chapter 5 outlines a monitoring and evaluation plan for the project that will help assess whether the project is meeting the intended purpose and need and the goals and objectives. Chapter 6 displays the action plan and provides a prioritized list of actions with associated budget for the next five year period. Successive chapters contain appendices, references, definitions, and a glossary. The purpose of the project is to protect, enhance, and mitigate fish and wildlife resources impacted by Columbia River Basin hydroelectric development. The effort is one of several wildlife mitigation projects in the region developed to compensate for terrestrial habitat losses resulting from the construction of McNary and John Day Hydroelectric facilities located on the mainstem Columbia River. While this project is driven primarily by the purpose and need to mitigate for wildlife habitat losses, it is also recognized that management strategies will also benefit many other non-target fish and wildlife species and associated natural resources. The Rainwater project is much more than a wildlife project--it is a watershed project with potential to benefit resources at the watershed scale. Goals and objectives presented in the following sections include both mitigation and non-mitigation related goals and objectives.

Childs, Allen B.

2002-03-01T23:59:59.000Z

224

Title of Project: Systemwide Information for Transportation Assessment: Economic Impacts and ITS Deployment Planning  

E-Print Network [OSTI]

in the Northeastern Illinois area are to improve safety, improve service level (efficiency), reduce energy Deployment Planning Sponsors: Illinois Department of Transportation (IDOT) and Federal Highway Administration plans with a complete economic impact. Using this tool, the six-county Northeastern Illinois region

Illinois at Chicago, University of

225

UMTRA Project-Level Cost Reduction/Productivity Improvement Program manual  

SciTech Connect (OSTI)

Mission of the Uranium Mill Tailings Remedial Action (UMTRA) Project Cost Reduction/Productivity Improvement Program (CR/PIP) is to contribute to the UMTRA Project`s environmental restoration mission by providing the means to achieve and recognize continuous improvements and cost savings. This manual includes program definition, description of UMTRA project organizational responsibilities and interfaces with existing project functions, guidance to contractors, and definition of project-level functions.

NONE

1995-06-01T23:59:59.000Z

226

Software Verification and Validation Plan Activities, 2011, Project Number: N6423, SAPHIRE Version 8  

SciTech Connect (OSTI)

The SV&V Plan experienced changes over the past year to bring it into the operational software life cycle of SAPHIRE 8 and to maintain its sections on design features. Peer review of the SVVP with the former IV&V members identified the need for the operational use of metrics as a tool for quality maintenance and improvement. New tests were added to the SVVP to verify the operation of the new design features incorporated into SAPHIRE 8. Other additions to the SVVP were the addition of software metrics and the PDR and CDR processes. Audit support was provided for the NRC Technical Manager and Project Manager for the NRC OIG Audit performed throughout 2011. The SVVP is considered to be an up to date reference and useful roadmap of verification and validation activities going forward.

Kurt G. Vedros; Curtis L. Smith

2011-11-01T23:59:59.000Z

227

Materials Development Program, Ceramic Technology Project addendum to program plan: Cost effective ceramics for heat engines  

SciTech Connect (OSTI)

This is a new thrust in the Ceramic Technology project. This effort represents an expansion of the program and an extension through FY 1997. Moderate temperature applications in conventional automobile and truck engines will be included along with high-temp. gas turbine and low heat rejection diesel engines. The reliability goals are expected to be met on schedule by end of FY 1993. Ceramic turbine rotors have been run (in DOE`s ATTAP program) for 1000 h at 1370C and full speed. However, the cost of ceramic components is a deterrrent to near-term commercialization. A systematic approach to reducing this cost includes the following elements: economic cost modeling, ceramic machining, powder synthesis, alternative forming and densification processes, yield improvement, system design studies, standards development, and testing and data base development. A draft funding plan is outlined. 6 figs, 1 tab.

Not Available

1992-08-01T23:59:59.000Z

228

Materials Development Program, Ceramic Technology Project addendum to program plan: Cost effective ceramics for heat engines  

SciTech Connect (OSTI)

This is a new thrust in the Ceramic Technology project. This effort represents an expansion of the program and an extension through FY 1997. Moderate temperature applications in conventional automobile and truck engines will be included along with high-temp. gas turbine and low heat rejection diesel engines. The reliability goals are expected to be met on schedule by end of FY 1993. Ceramic turbine rotors have been run (in DOE's ATTAP program) for 1000 h at 1370C and full speed. However, the cost of ceramic components is a deterrrent to near-term commercialization. A systematic approach to reducing this cost includes the following elements: economic cost modeling, ceramic machining, powder synthesis, alternative forming and densification processes, yield improvement, system design studies, standards development, and testing and data base development. A draft funding plan is outlined. 6 figs, 1 tab.

Not Available

1992-08-01T23:59:59.000Z

229

OPUC Flexibility Planning Guidelines Pacific Northwest Demand Response Project  

E-Print Network [OSTI]

) · Demand management ­ smart grid controllable "withdrawal" and "recharge" #12;Jim Hicks Energy Strategies Jim Hicks Energy Strategies West, LLC #12;OPUC's New IRP Guidelines* · Integrated Resource Plans operational view of planning, including comprehensive multi-faceted VER integration strategy #12;Daily Wind

230

Improved Load Plan Design Through Integer Programming Based ...  

E-Print Network [OSTI]

The fundamental building block in load planning is a direct trailer, or a direct. ... of shipment and trailer dispatching; (2) integrated consideration of the movement ...

2011-12-21T23:59:59.000Z

231

Wildlife and Wildlife Habitat Mitigation Plan for Hungry Horse Hydroelectric Project, Final Report.  

SciTech Connect (OSTI)

This report describes the proposed mitigation plan for wildlife losses attributable to the construction of the Hungry Horse hydroelectric project. In this report, mitigation objectives and alternatives, the recommended mitigation projects, and the crediting system for each project are described by each target species. Mitigation objectives for each species (group) were established based on the loss estimates but tailored to the recommended projects. 13 refs., 3 figs., 19 tabs.

Bissell, Gael

1985-01-01T23:59:59.000Z

232

Wildlife and Wildlife Habitat Mitigation Plan for Libby Hydroelectric Project, Final Report.  

SciTech Connect (OSTI)

This report describes the proposed mitigation plan for wildlife losses attributable to the construction of the Libby hydroelectric project. Mitigation objectives and alternatives, the recommended mitigation projects, and the crediting system for each project are described by each target species. The report describes mitigation that has already taken place and 8 recommended mitigation projects designed to complete total wildlife mitigation. 8 refs., 2 figs., 12 tabs.

Mundinger, John

1985-01-01T23:59:59.000Z

233

Manufacturing improvements in the Photovoltaic Manufacturing Technology (PVMaT) Project  

SciTech Connect (OSTI)

The Photovoltaic Manufacturing Technology Project (PVMaT) is a government/industry research and development (R and D) partnership between the US federal government (through the US Department of Energy [DOE]) and members of the US PV industry. The goals of PVMaT are to help the US PV industry improve module manufacturing processes and equipment; accelerate manufacturing cost reductions for PV modules, balance-of-systems components, and integrated systems; increase commercial product performance and reliability; and enhance the investment opportunities for substantial scale-ups of US-based PV manufacturing plant capacities. The approach for PVMaT has been to cost-share risk taking by industry as it explores new manufacturing options and ideas for improved PV modules and other components, advances system and product integration, and develops new system designs, all of which will lead to overall reduced system life-cycle costs for reliable PV end products. The PVMaT Phase 4A module manufac turing R and D projects are just being completed, and initial results for the work directed primarily to module manufacture are reported in this paper. Fourteen new Phase 5A subcontracts have also just been awarded, and planned R and D areas for the ten focused on module manufacture are described. Finally, government funding, subcontractor cost-sharing, and a comparison of the relative efforts by PV technology throughout the PVMaT project are presented.

Witt, C.E.; Mitchell, R.L.; Thomas, H.P.; Symko, M.I. [National Renewable Energy Lab., Golden, CO (United States); King, R. [Dept. of Energy, Washington, DC (United States); Ruby, D.S. [Sandia National Labs., Albuquerque, NM (United States)

1998-08-01T23:59:59.000Z

234

Making European Fisheries Ecosystem Plans Operational EC FP7 project # 212881  

E-Print Network [OSTI]

.2.1.4 Deep Water................................................................................................. 143 1.2.3.4 Deep WaterMEFEPO Making European Fisheries Ecosystem Plans Operational EC FP7 project # 212881 Work Package 1

Hansen, René Rydhof

235

Quality assurance program plan for FRG sealed isotopic heat sources project (C-229)  

SciTech Connect (OSTI)

This QAPP implements the Quality Assurance Program Plan for the FRG Sealed Isotopic Heat Sources Project (C-229). The heat source will be relocated from the 324 Building and placed in interim storage at the Central Waste Complex (CWC).

Tanke, J.M.

1997-05-16T23:59:59.000Z

236

The Commonwealth Electric Open Planning Project : final report  

E-Print Network [OSTI]

This report describes the development, application and results of an Open Planning Process performed by the M.I.T. Energy Laboratory's Analysis Group for Regional Electricity Alternatives (AGREA) for, and with the support ...

Andrews, Clinton J.

1991-01-01T23:59:59.000Z

237

UMTRA project technical assistance contractor quality assurance implementation plan for surface and ground water  

SciTech Connect (OSTI)

The Uranium Mill Tailings Remedial Action (UMTRA) Project Technical Assistance Contractor (TAC) Quality Assurance Implementation Plan (QAIP) outlines the primary requirements for integrating quality functions for TAC technical activities applied to the surface and ground water phases of the UMTRA Project. The QAIP is subordinate to the latest issue of the UMTRA Project TAC Quality Assurance Program Plan (QAPP). The QAIP addresses technical aspects of the TAC UMTRA Project surface and ground water programs. The QAIP is authorized and approved by the TAC Project Manager and QA manager. The QA program is designed to use monitoring, audit, and surveillance functions as management tools to ensure that all Project organization activities are carried out in a manner that will protect public health and safety, promote the success of the UMTRA Project and meet or exceed contract requirements.

Not Available

1994-09-01T23:59:59.000Z

238

Landlord project multi-year work plan fiscal year 1998  

SciTech Connect (OSTI)

The mission of Landlord Project is to preserve, upgrade, maintain, and forecast cost effective general infrastructure activities to facilitate the Hanford Site cleanup mission. Specific functions and services provided by Landlord Project include utilities (i.e. steam, water, sanitary sewer, solid waste disposal, electrical and telecommunication distribution), transportation, general purpose facilities (includes general support shops and laboratories), services, and energy and land use management. All Landlord Project activities will be performed in an environmentally sound, safe, economical, prudent, and reliable manner. The Hanford Site Landlord Project will be competitive with commercially provided services to offer the best price, quality, and service available.

Knollmeyer, P.M., Westinghouse Hanford, Richland, WA

1997-09-19T23:59:59.000Z

239

Safety Planning Guidance for Hydrogen and Fuel Cell Projects  

Fuel Cell Technologies Publication and Product Library (EERE)

This guidance document provides information on safety requirements for hydrogen and fuel cell projects funded by the U.S. Department of Energy Fuel Cell Technologies Program.

240

FY 2013 Major Capital Outlay Project Request and Five-Year Comprehensive Master Plan  

E-Print Network [OSTI]

in the following specific areas: Transmission & Distribution (smart grids technology, cyber-security) GenerationFY 2013 Major Capital Outlay Project Request and Five-Year Comprehensive Master Plan September 2011 ____ No _X__ Is There a Five-Year Capital Outlay Plan Available? Yes _X__ No ____ Are Professionally

Note: This page contains sample records for the topic "improvement project plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


241

Uranium Mill Tailings remedial action project waste minimization and pollution prevention awareness program plan  

SciTech Connect (OSTI)

The purpose of this plan is to establish a waste minimization and pollution prevention awareness (WM/PPA) program for the U.S. Department of Energy`s (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project. The program satisfies DOE requirements mandated by DOE Order 5400.1. This plan establishes planning objectives and strategies for conserving resources and reducing the quantity and toxicity of wastes and other environmental releases.

Not Available

1994-07-01T23:59:59.000Z

242

Underground Test Area Quality Assurance Project Plan Nevada National Security Site, Nevada, Revision 0  

SciTech Connect (OSTI)

This Quality Assurance Project Plan (QAPP) provides the overall quality assurance (QA) program requirements and general quality practices to be applied to the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office (NNSA/NSO) Underground Test Area (UGTA) Sub-Project (hereafter the Sub-Project) activities. The requirements in this QAPP are consistent with DOE Order 414.1C, Quality Assurance (DOE, 2005); U.S. Environmental Protection Agency (EPA) Guidance for Quality Assurance Project Plans for Modeling (EPA, 2002); and EPA Guidance on the Development, Evaluation, and Application of Environmental Models (EPA, 2009). The QAPP Revision 0 supersedes DOE--341, Underground Test Area Quality Assurance Project Plan, Nevada Test Site, Nevada, Revision 4.

Irene Farnham

2011-05-01T23:59:59.000Z

243

Central and South Florida Project, Comprehensive Everglades Restoration Plan  

E-Print Network [OSTI]

-related resource needs of the region, including water supply and flood protection. The recommended project. Scientists have established that a mosaic of uplands, freshwater marsh, deep water sloughs, and estuarine significantly declined in remaining natural system areas due to water management projects and practices

US Army Corps of Engineers

244

Science and Technology Roadmapping to Support Project Planning  

SciTech Connect (OSTI)

Disciplined science and technology roadmapping provides a framework to coordinate research and development activities with project objectives. This case-history paper describes initial project technology needs identification, assessment and R&D ranking activities supporting characterization of 781 waste tanks requiring a 'hazardous waste determination' or 'verification of empty' decision to meet an Idaho state Voluntary Consent Order.

Mc Carthy, Jeremiah Justin; Haley, Daniel Joseph; Dixon, Brent Wayne

2001-07-01T23:59:59.000Z

245

Energy Department Announces Five Research Projects to Improve...  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

an experimental model to test four dewatering strategies. The project team leader is West Virginia University, Morgantown, W.V. Partners in this project are: Luscar Ltd.,...

246

Project plans for transuranic waste at small quantity sites in the Department of Energy comples-10522  

SciTech Connect (OSTI)

Los Alamos National Laboratory, Carlsbad Office (LANL-CO), has been tasked to write Project Plans for all of the Small Quantity Sites (SQS) with defense related Transuranic (TRU) waste in the Department of Energy (DOE) complex. Transuranic Work-Off Plans were precursors to the Project Plans. LANL-CO prepared a Work-Off Plan for each small quantity site. The Work-Off Plan that identified issues, drivers, schedules, and inventory. Eight sites have been chosen to deinventory their legacy TRU waste; Bettis Atomic Power Laboratory, General Electric-Vallecitos Nuclear Center, Lawrence Berkeley National Laboratory, Lawrence Livermore National Laboratory-Area 300, Nevada Test Site, Nuclear Radiation Development, Sandia National Laboratory, and the Separations Process Research Unit. Each plan was written for contact and/or remote handled waste if present at the site. These project plans will assist the small quantity sites to ship legacy TRU waste offsite and de-inventory the site of legacy TRU waste. The DOE is working very diligently to reduce the nuclear foot print in the United States. Each of the eight SQSs will be de-inventoried of legacy TRU waste during a campaign that ends September 2011. The small quantity sites have a fraction of the waste that large quantity sites possess. During this campaign, the small quantity sites will package all of the legacy TRU waste and ship to Idaho or directly to the Waste Isolation Pilot Plant (WIPP) in Carlsbad, New Mexico. The sites will then be removed from the Transuranic Waste Inventory if they are de-inventoried of all waste. Each Project Plan includes the respective site inventory report, schedules, resources, drivers and any issues. These project plans have been written by the difficult waste team and will be approved by each site. Team members have been assigned to each site to write site specific project plans. Once the project plans have been written, the difficult team members will visit the sites to ensure nothing has been overlooked and to verify the inventory. After each site has approved their project plan, the site will begin writing procedures and packaging/repackaging their waste. In some cases the sites have already begun the process. The waste will be shipped after all of the waste has been characterized and approved.

Mctaggart, Jerri Lynne [Los Alamos National Laboratory; Lott, Sheila [Los Alamos National Laboratory; Gadbury, Casey [DOE

2009-01-01T23:59:59.000Z

247

Moab Mill Tailings Removal Project Plans to Resume Train Shipments...  

Energy Savers [EERE]

result in a cost savings to the project over the long term. Made of -inch durable plastic, the liners will prevent the tailings material, which tends to be sticky, from...

248

Implementation of a Project Management System for Improvement to City, State's Design and Construction Capital Project Delivery  

E-Print Network [OSTI]

management, process improvement suggestions as well as staff supplements necessary for the completion of the backlog. This included the development of standard processes and procedures for the use by the combined City and consultant staff. The initial... combination of full time staff and consultant supplementary staff funded by the project?s individual budgets. In addition to completing the project backlog, this staff has documented the processes and procedures EMGT 835 Field Project 21 Chad Thompson...

Thompson, Chad C.

2007-05-18T23:59:59.000Z

249

Recovery Act: Hydroelectric Facility Improvement Project - Replacement of Current Mechanical Seal System with Rope Packing System  

SciTech Connect (OSTI)

On January 27, 2010 the City of North Little Rock, Arkansas received notification of the awarding of a Department of Energy (DOE) grant totaling $450,000 in funding from the American Recovery and Reinvestment Act (ARRA) under the Project Title: Recovery Act: Hydroelectric Facility Improvement Project – Automated Intake Clearing Equipment and Materials Management. The purpose of the grant was for improvements to be made at the City’s hydroelectric generating facility located on the Arkansas River. Improvements were to be made through the installation of an intake maintenance device (IMD) and the purchase of a large capacity wood grinder. The wood grinder was purchased in order to receive the tree limbs, tree trunks, and other organic debris that collects at the intake of the plant during high flow. The wood grinder eliminates the periodic burning of the waste material that is cleared from the intake and reduces any additional air pollution to the area. The resulting organic mulch has been made available to the public at no charge. Design discussion and planning began immediately and the wood grinder was purchased in July of 2010 and immediately put to work mulching debris that was gathered regularly from the intake of the facility. The mulch is currently available to the public for free. A large majority of the design process was spent in discussion with the Corps of Engineers to obtain approval for drawings, documents, and permits that were required in order to make changes to the structure of the powerhouse. In April of 2011, the City’s Project Engineer, who had overseen the application, resigned and left the City’s employ. A new Systems Mechanical Engineer was hired and tasked with overseeing the project. The transfer of responsibility led to a re-examination of the original assumptions and research upon which the grant proposal was based. At that point, the project went under review and a trip was booked for July 2011 to visit facilities that currently had an IMD installed. This further study of facilities revealed that the implementation of the project as originally described, while proving the benefits described in the original grant application, would likely intensify sand intake. Increased sand intake would lead to an increase in required shutdowns for maintenance and more rapid depreciation of key equipment which would result in a loss of generation capacity. A better solution to the problem, one that continued to meet the criteria for the original grant and ARRA standards, was developed. A supporting day trip was planned to visit other facilities located on the Arkansas River to determine how they were coping with the same strong amounts of sand, silt, and debris. Upon returning from the trip to other Arkansas River facilities it was extremely clear what direction to go in order to most efficiently address the issue of generator capacity and efficiency. Of the plants visited on the Arkansas River, every one of them was running what is called a rope packing shaft sealing system as opposed to mechanical shaft seals, which the facility was running. Rope packing is a time proven sealing method that has been around for centuries. It has proved to perform very well in dirty water situations just like that of the Arkansas River. In April of 2012 a scope change proposal was submitted to the DOE for approval. In August of 2012 the City received word that the change of scope had been approved. Plans were immediately set in motion to begin the conversion from mechanical seals to a packing box at the facility. Contractors arrived on October 1st, 2012 and the project team began unwatering the unit for disassembly. The seal conversion was completed on February 29th, 2013 with start-up of the unit. Further testing and adjusting was done throughout the first two weeks of March.

Stephens, Jessica D.

2013-05-29T23:59:59.000Z

250

Groundwater protection management program plan. [Uranium Mill Tailings Remedial Action (UMTRA) Project  

SciTech Connect (OSTI)

US Department of Energy (DOE) Order 5400.1 requires the establishment of a groundwater protection management program to ensure compliance with DOE requirements and applicable Federal, state, and local laws and regulations. The Uranium Mill Tailings Remedial Action (UMTRA) Project Office has prepared a Groundwater Protection Management Program Plan'' (groundwater protection plan) of sufficient scope and detail to reflect the program's significance and address the seven activities required in DOE Order 5400.1, Chapter 3, for special program planning. The groundwater protection plan highlights the methods designed to preserve, protect, and monitor groundwater resources at UMTRA Project processing and disposal sites. The plan includes an overview of the remedial action status at the 24 designated processing sites and identifies project technical guidance documents and site-specific documents for the UMTRA groundwater protection management program. In addition, the groundwater protection plan addresses the general information required to develop a water resources protection strategy at the permanent disposal sites. Finally, the plan describes ongoing activities that are in various stages of development at UMTRA sites (long-term care at disposal sites and groundwater restoration at processing sites). This plan will be reviewed annually and updated every 3 years in accordance with DOE Order 5400.1.

Not Available

1992-06-01T23:59:59.000Z

251

Solanaceae Coordinated Agricultural Project Dedicated to the Improvement of Potato and Tomato  

E-Print Network [OSTI]

SolCAP Solanaceae Coordinated Agricultural Project Dedicated to the Improvement of Potato are dedicated to the improvement of the Solanaceae crops: potato and tomato. Through innovative researchCAP Project Participants #12;SolCAP Project OverviewResearch - Education - Extension [Potato Example] mRNA > c

Douches, David S.

252

Root Cause Analysis (RCA) & Corrective Action Plan (CAP) | Department...  

Energy Savers [EERE]

Root Cause Analysis (RCA) & Corrective Action Plan (CAP) Root Cause Analysis (RCA) & Corrective Action Plan (CAP) Improving the Department of Energy's project and contract...

253

The Soils and Groundwater – EM-20 S&T Roadmap Quality Assurance Project Plan  

SciTech Connect (OSTI)

The Soils and Groundwater – EM-20 Science and Technology Roadmap Project is a U.S. Department of Energy, Office of Environmental Management-funded initiative designed to develop new methods, strategies and technology for characterizing, modeling, remediating, and monitoring soils and groundwater contaminated with metals, radionuclides, and chlorinated organics. This Quality Assurance Project Plan provides the quality assurance requirements and processes that will be followed by EM-20 Roadmap Project staff.

Fix, N. J.

2008-02-11T23:59:59.000Z

254

Removal Action Plan for the Accelerated Retrieval Project for a Described Area within Pit 4  

SciTech Connect (OSTI)

This Removal Action Plan documents the plan for implementation of the Comprehensive Environmental Response, Compenstion, and Liability Act non-time-critical removal action to be performed by the Accelerated Retrieval Project. The focus of the action is the limited excavation and retrieval of selected waste streams from a designated portion of the Radioactive Waste Management Complex Subsurface Disposal Area that are contaminated with volatile organic compounds, isotopes of uranium, or transuranic radionuclides. The selected retrieval area is approximately 0.2 ha (1/2 acre) and is located in the eastern portion of Pit 4. The proposed project is referred to as the Accelerated Retrieval Project. This Removal Action Plan details the major work elements, operations approach, and schedule, and summarizes the environmental, safety and health, and waste management considerations associated with the project.

A. M. Tyson

2006-08-01T23:59:59.000Z

255

US Department of Energy Uranium Mill Tailings Remedial Action ground water Project. Revision 1, Version 1: Final project plan  

SciTech Connect (OSTI)

The scope of the Project is to develop and implement a ground water compliance strategy for all 24 UMTRA processing sites. The compliance strategy for the processing sites must satisfy requirements of the proposed EPA ground water cleanup standards in 40 CFR Part 192, Subparts B and C (1988). This scope of work will entail the following activities, on a site-specific basis: Development of a compliance strategy based upon modification of the UMTRA Surface Project remedial action plans (RAP) or development of Ground Water Project RAPs with NRC and state or tribal concurrence on the RAP; implementation of the RAP to include establishment of institutional controls, where appropriate; institution of long-term verification monitoring for transfer to a separate DOE program on or before the Project end date; and preparation of completion reports and final licensing on those sites that will be completed prior to the Project end date.

Not Available

1993-12-21T23:59:59.000Z

256

Bosque River Environmental Infrastructure Improvement Plan: Phase I Final Report  

E-Print Network [OSTI]

watershed health. This report is the first phase of a project that is focused on developing and employing a strategic approach to identifying priority areas in the watershed where field investigations should begin to investigate the need to reduce pollution...

Srinivasan, Raghavan

257

EA-1941: Boyer-Tillamook Access Road Improvement Project, Tillamook and Yamhill Counties, Oregon  

Broader source: Energy.gov [DOE]

BPA prepared an EA, FONSI, and Mitigation Action Plan to assess the potential environmental impacts of proposed improvements to 13 miles of access roads for its existing 115-kV Boyer-Tillamook No. 1 Transmission Line in Tillamook and Yamhill counties, Oregon. Associated activities would include resurfacing roads, adding drainage, widening 3 miles of road, constructing 0.1 mile of new road, maintaining culverts, and constructing outlet ditches and retaining walls. In addition, new bridges would be built, and culverts that currently block fish passage for anadromous and resident fish would be replaced. Additional information is available at the project website: http://efw.bpa.gov/environmental_services/Document_Library/Boyer-Tillamook/.

258

IT Capital Planning Corporate Management Improvement Program (CMIP)  

Broader source: Energy.gov [DOE]

The Corporate Management Improvement Program (CMIP) was initiated by the Department in recognition of the fact that corporate legacy systems that support administrative functions were nearing the...

259

Project Execution Plan Project 98L-EWW-460 Plutonium Stabilization and Handling DOE 98-D-453  

SciTech Connect (OSTI)

This Project Execution Plan (PEP) describes the management methods and responsibilities of the project participants. Project W-460 is sufficiently large to warrant a stand alone PEP. This project specific PEP describes the relationships and responsibilities of the project team and identifies the technical, schedule, and cost baselines that have been established for the project. The Department of Energy (DOE), Hanford Works (Hanford), at Richland, Wa. currently does not have a system capable of stabilizing or packaging large quantities of plutonium-bearing solids to meet DOE technical standard DOE-STD-3013-99. This project will allow Hanford to meet this standard by installing stabilization and packaging equipment (SPE). The SPE is capable of stabilizing and packaging the current inventory of greater than 30 percent plutonium-bearing materials currently stored in the Plutonium Finishing Plant's (PFP) vaults into 3013 storage containers. The scope of this project is to procure and install the SPE via a Hanford contract and coordination with the Savannah River Site. In addition, the project will modify PFP vaults and upgrade the PFP Laboratory measurement systems. The Facility infrastructure will be modified to support the new SPE system and the new standardized storage container configuration.

MCGRATH, G.M.

2000-06-21T23:59:59.000Z

260

Project Execution Plan Project 98L-EWW-460 Plutonium Stabilization and Handling DOE 98-D-453  

SciTech Connect (OSTI)

This Project Execution Plan (PEP) describes the management methods and responsibilities of the project participants. Project W-460 is sufficiently large to warrant a stand alone PEP. This project specific PEP describes the relationships and responsibilities of the project team and identifies the technical, schedule, and cost baselines that have been established for the project. The Department of Energy (DOE), Hanford Works (Hanford), at Richland Wa. currently does not have a system capable of stabilizing or packaging large quantities of plutonium-bearing solids to meet DOE technical standard DOE-STD-3013-96. This project will allow Hanford to meet this standard by installing stabilization and packaging equipment (SPE). The SPE is capable of stabilizing and packaging the current inventory of greater than 50 percent plutonium-bearing materials currently stored in the Plutonium Finishing Plant's (PFP) vaults into 3013 storage containers. The scope of this project is to procure and install the SPE via a Hanford contract and coordination with the Savannah River Site. In addition, the project will modify PFP vaults and upgrade the PFP Laboratory measurement systems. The Facility infrastructure will be modified to support the new SPE system and the new standardized storage container configuration.

HOLSTEIN, W.A.

1999-08-01T23:59:59.000Z

Note: This page contains sample records for the topic "improvement project plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


261

Project Execution Plan for the Remote Handled Low-Level Waste Disposal Project  

SciTech Connect (OSTI)

As part of ongoing cleanup activities at the Idaho National Laboratory (INL), closure of the Radioactive Waste Management Complex (RWMC) is proceeding under the Comprehensive Environmental Response, Compensation, and Liability Act (42 USC 9601 et seq. 1980). INL-generated radioactive waste has been disposed of at RWMC since 1952. The Subsurface Disposal Area (SDA) at RWMC accepted the bulk of INL’s contact and remote-handled low-level waste (LLW) for disposal. Disposal of contact-handled LLW and remote-handled LLW ion-exchange resins from the Advanced Test Reactor in the open pit of the SDA ceased September 30, 2008. Disposal of remote-handled LLW in concrete disposal vaults at RWMC will continue until the facility is full or until it must be closed in preparation for final remediation of the SDA (approximately at the end of fiscal year FY 2017). The continuing nuclear mission of INL, associated ongoing and planned operations, and Naval spent fuel activities at the Naval Reactors Facility (NRF) require continued capability to appropriately dispose of contact and remote handled LLW. A programmatic analysis of disposal alternatives for contact and remote-handled LLW generated at INL was conducted by the INL contractor in Fiscal Year 2006; subsequent evaluations were completed in Fiscal Year 2007. The result of these analyses was a recommendation to the Department of Energy (DOE) that all contact-handled LLW generated after September 30, 2008, be disposed offsite, and that DOE proceed with a capital project to establish replacement remote-handled LLW disposal capability. An analysis of the alternatives for providing replacement remote-handled LLW disposal capability has been performed to support Critical Decision-1. The highest ranked alternative to provide this required capability has been determined to be the development of a new onsite remote-handled LLW disposal facility to replace the existing remote-handled LLW disposal vaults at the SDA. Several offsite DOE and commercial disposal options exist for contact-handled LLW; however, offsite disposal options are either not currently available (i.e., commercial disposal facilities), practical, or cost-effective for all remote-handled LLW streams generated at INL. Offsite disposal of all INL and tenant-generated remote-handled waste is further complicated by issues associated with transporting highly radioactive waste in commerce; and infrastructure and processing changes at the generating facilities, specifically NRF, that would be required to support offsite disposal. The INL Remote-Handled LLW Disposal Project will develop a new remote handled LLW disposal facility to meet mission-critical, remote-handled LLW disposal needs. A formal DOE decision to proceed with the project has been made in accordance with the requirements of National Environmental Policy Act (42 USC§ 4321 et seq.). Remote-handled LLW is generated from nuclear programs conducted at INL, including spent nuclear fuel handling and operations at NRF and operations at the Advanced Test Reactor. Remote-handled LLW also will be generated by new INL programs and from segregation and treatment (as necessary) of remote handled scrap and waste currently stored in the Radioactive Scrap and Waste Facility at the Materials and Fuels Complex.

Danny Anderson

2014-07-01T23:59:59.000Z

262

Renewable Energy Project Planning and Implementation | Department of Energy  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE: AlternativeEnvironment,Institutes and LaunchesRelated FinancialUtility DistrictAssistancePlanning

263

Cypress Creek Project Building A Watershed Protection Plan  

E-Print Network [OSTI]

projections · No regional water/WWTP services · Good water quality with some degrading trends · Lack on Environmental Quality www.cypresscreekproject.org #12;#12;#12;#12;#12;#12;WHISKEY IS FOR DRINKIN'& WATER 97,589 (2000) 437,000 (2050) · Water demand ­ Total water use 17% 1990-2004 ­ Withdrawals from

264

Alaska Native Community Energy Planning and Projects (Fact Sheet)  

SciTech Connect (OSTI)

This fact sheet provides information on the Alaska Native villages selected to receive assistance from the U.S. Department of Energy Office of Indian Energy 2013 Strategic Technical Assistance Response Team (START) Program, which provides technical expertise to support the development of next-generation energy projects on tribal lands.

Not Available

2013-06-01T23:59:59.000Z

265

The Attitudes of Teachers in One County in Kansas Toward Their School Improvement Plan Assessments  

E-Print Network [OSTI]

regarding their attitudes toward seven types of assessments used in school improvement plans: standardized norm-referenced tests, criterion-referenced tests, the Kansas Reading Assessment, portfolio assessment, the Kansas Writing Assessment, publishers...

Ubel, Renita Kathleen Pohl

1998-03-01T23:59:59.000Z

266

Improved Swing-Cut Modeling for Planning and Scheduling of Oil-Refinery Distillation Units  

E-Print Network [OSTI]

, Pennsylvania 15213, United States. Crude-oil assays, Distillation, Fractionation, Swing-cuts, Temperature cut with in the nonlinear optimization. 1. INTRODUCTION Distillation or fractionation models for planning and scheduling1 Improved Swing-Cut Modeling for Planning and Scheduling of Oil-Refinery Distillation Units Brenno

Grossmann, Ignacio E.

267

Methods and computer readable medium for improved radiotherapy dosimetry planning  

DOE Patents [OSTI]

Methods and computer readable media are disclosed for ultimately developing a dosimetry plan for a treatment volume irradiated during radiation therapy with a radiation source concentrated internally within a patient or incident from an external beam. The dosimetry plan is available in near "real-time" because of the novel geometric model construction of the treatment volume which in turn allows for rapid calculations to be performed for simulated movements of particles along particle tracks therethrough. The particles are exemplary representations of alpha, beta or gamma emissions emanating from an internal radiation source during various radiotherapies, such as brachytherapy or targeted radionuclide therapy, or they are exemplary representations of high-energy photons, electrons, protons or other ionizing particles incident on the treatment volume from an external source. In a preferred embodiment, a medical image of a treatment volume irradiated during radiotherapy having a plurality of pixels of information is obtained.

Wessol, Daniel E.; Frandsen, Michael W.; Wheeler, Floyd J.; Nigg, David W.

2005-11-15T23:59:59.000Z

268

Classroom HVAC: Improving ventilation and saving energy -- field study plan  

SciTech Connect (OSTI)

The primary goals of this research effort are to develop, evaluate, and demonstrate a very practical HVAC system for classrooms that consistently provides classrooms (CRs) with the quantity of ventilation in current minimum standards, while saving energy, and reducing HVAC-related noise levels. This research is motivated by the public benefits of energy efficiency, evidence that many CRs are under-ventilated, and public concerns about indoor environmental quality in CRs. This document provides a summary of the detailed plans developed for the field study that will take place in 2005 to evaluate the energy and IAQ performance of a new classroom HVAC technology. The field study will include measurements of HVAC energy use, ventilation rates, and IEQ conditions in 10 classrooms with the new HVAC technology and in six control classrooms with a standard HVAC system. Energy use and many IEQ parameters will be monitored continuously, while other IEQ measurements will be will be performed seasonally. Continuously monitored data will be remotely accessed via a LonWorks network. Instrument calibration plans that vary with the type of instrumentation used are established. Statistical tests will be employed to compare energy use and IEQ conditions with the new and standard HVAC systems. Strengths of this study plan include the collection of real time data for a full school year, the use of high quality instrumentation, the incorporation of many quality control measures, and the extensive collaborations with industry that limit costs to the sponsors.

Apte, Michael G.; Faulkner, David; Hodgson, Alfred T.; Sullivan, Douglas P.

2004-10-14T23:59:59.000Z

269

Federal Renewable Energy Project Planning and Implementation | Department  

Office of Environmental Management (EM)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr May Jun Jul(Summary) "of EnergyEnergyENERGY TAX POLICIES ANDIndustrialEnergy FederalFLASHof Energy Planning and

270

Safety Planning Guidance for Hydrogen and Fuel Cell Projects | Department  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE:YearRound-Up from the Gridwise Global Forum Round-UpSTATE ENERGYof Energy Safety Planning

271

Independent Verification and Validation Of SAPHIRE 8 Software Quality Assurance Plan Project Number: N6423 U.S. Nuclear Regulatory Commission  

SciTech Connect (OSTI)

This report provides an evaluation of the Software Quality Assurance Plan. The Software Quality Assurance Plan is intended to ensure all actions necessary for the software life cycle; verification and validation activities; documentation and deliverables; project management; configuration management, nonconformance reporting and corrective action; and quality assessment and improvement have been planned and a systematic pattern of all actions necessary to provide adequate confidence that a software product conforms to established technical requirements; and to meet the contractual commitments prepared by the sponsor; the Nuclear Regulatory Commission.

Kent Norris

2010-02-01T23:59:59.000Z

272

UMTRA project technical assistance contractor quality assurance implementation plan for surface and ground water, Revision 2  

SciTech Connect (OSTI)

This document contains the Technical Assistance Contractor (TAC) Quality Assurance Implementation Plan (QAIP) for the Uranium Mill Tailings Remedial Action (UMTRA) Project. The QAIP outlines the primary requirements for integrating quality functions for TAC technical activities applied to the surface and ground water phases of the UMTRA Project. The QA program is designed to use monitoring, audit, and surveillance activities as management tools to ensure that UMTRA Project activities are carried out in amanner to protect public health and safety, promote the success of the UMTRA Project, and meet or exceed contract requirements.

NONE

1995-11-01T23:59:59.000Z

273

UMTRA project water sampling and analysis plan, Naturita, Colorado. Revision 1  

SciTech Connect (OSTI)

Planned, routine ground water sampling activities for calendar year 1995 to 1997 at the US Department of Energy (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project site near Naturita, Colorado, are described in this water sampling and analysis plan. The following plan identifies and justifies the sampling locations, analytical parameters, detection limits, sampling frequency, and specific rationale for each routine monitoring station at the site. The regulatory basis for routine ground water monitoring at UMTRA Project sites is derived from the US Environmental Protection Agency (EPA) regulations in 40 CFR Part 192. Sampling procedures are guided by the UMTRA Project standard operating procedures (SOP) (JEG, n.d.), the Technical Approach Document (TAD) (DOE, 1989), and the most effective technical approach for the site.

NONE

1995-09-01T23:59:59.000Z

274

UMTRA Project water sampling and analysis plan, Durango, Colorado. Revision 1  

SciTech Connect (OSTI)

Planned, routine ground water sampling activities at the US Department of Energy (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project site in Durango, Colorado, are described in this water sampling and analysis plan. The plan identifies and justifies the sampling locations, analytical parameters, detection limits, and sampling frequency for the routine monitoring stations at the site. The ground water data are used to characterize the site ground water compliance strategies and to monitor contaminants of potential concern identified in the baseline risk assessment (DOE, 1995a). Regulatory basis for routine ground water monitoring at UMTRA Project sites is derived from the US EPA regulations in 40 CFR Part 192 (1994) and EPA standards of 1995 (60 FR 2854). Sampling procedures are guided by the UMTRA Project standard operating procedures (SOP) (JEG, n.d.), the Technical Approach Document (TAD) (DOE, 1989), and the most effective technical approach for the site.

NONE

1995-09-01T23:59:59.000Z

275

Program and Project Management Policy for the Planning, Programming, Budgeting, and Acquisition of Capital Assets  

Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

To establish Department of Energy (DOE) program and project management policy for the planning, programming, budgeting, and acquisition of capital assets consistent with the following Office of Management and Budget (OMB) circulars: OMB Circular A-11, Part 3, Planning, Budgeting, and Acquisition of Capital Assets, and the supplement to Part 3, Capital Programming Guide; OMB Circular A-123; OMB Circular A-127; and OMB Circular A-130. Does not cancel other directives. Canceled by DOE N 251.99

2000-06-10T23:59:59.000Z

276

UMTRA project water sampling and analysis plan, Durango, Colorado  

SciTech Connect (OSTI)

Surface remedial action has been completed at the Uranium Mill Tailings Remedial Action Project in Durango, Colorado. Contaminated soil and debris have been removed from the former processing site and placed in the Bodo Canyon disposal cell. Ground water at the former uranium mill/tailings site and raffinate pond area has been contaminated by the former milling operations. The ground water at the disposal site was not impacted by the former milling operations at the time of the cell`s construction. Activities for fiscal 1994 involve ground water sampling and site characterization of the disposal site.

Not Available

1994-01-01T23:59:59.000Z

277

River Protection Project FY 2000 Multi Year Work Plan Summary  

SciTech Connect (OSTI)

The River Protection Project (RPP), formerly the Tank Waste Remediation System (TWRS), is a major part of the U.S. Department of Energy's (DOE) Office of River Protection (ORP). The ORP was established as directed by Congress in Section 3139 of the Strom Thurmond National Defense Authorization Act for Fiscal Year (FY) 1999. The ORP was established to elevate the reporting and accountability for the RPP to the DOE-Headquarters level. This was done to gain Congressional visibility and obtain support for a major $10 billion high-level liquid waste vitrification effort.

LENSEIGNE, D.L.

1999-08-27T23:59:59.000Z

278

Project Execution Plan Review Module (RM) | Department of Energy  

Office of Environmental Management (EM)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr May Jun Jul(Summary) "of Energy Power Systems Engineering Research and Development (PSEEnergy ProgressProject

279

2011 Annual Planning Summary for Advanced Research and Projects Agency  

Energy Savers [EERE]

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious RankCombustionImprovement Awardflash2007-42attachment1.pdfmodule 4Department02010nuclearfuture_memo.pdf1

280

2014 Annual Planning Summary for the West Valley Demonstration Project |  

Energy Savers [EERE]

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious RankCombustionImprovement3 Beryllium-Associated Worker RegistryDepartment ofEnergyofDepartment

Note: This page contains sample records for the topic "improvement project plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


281

Hanford River Protection Project Life cycle Cost Modeling Tool to Enhance Mission Planning - 13396  

SciTech Connect (OSTI)

The Life cycle Cost Model (LCM) Tool is an overall systems model that incorporates budget, and schedule impacts for the entire life cycle of the River Protection Project (RPP) mission, and is replacing the Hanford Tank Waste Operations Simulator (HTWOS) model as the foundation of the RPP system planning process. Currently, the DOE frequently requests HTWOS simulations of alternative technical and programmatic strategies for completing the RPP mission. Analysis of technical and programmatic changes can be performed with HTWOS; however, life cycle costs and schedules were previously generated by manual transfer of time-based data from HTWOS to Primavera P6. The LCM Tool automates the preparation of life cycle costs and schedules and is needed to provide timely turnaround capability for RPP mission alternative analyses. LCM is the simulation component of the LCM Tool. The simulation component is a replacement of the HTWOS model with new capability to support life cycle cost modeling. It is currently deployed in G22, but has been designed to work in any full object-oriented language with an extensive feature set focused on networking and cross-platform compatibility. The LCM retains existing HTWOS functionality needed to support system planning and alternatives studies going forward. In addition, it incorporates new functionality, coding improvements that streamline programming and model maintenance, and capability to input/export data to/from the LCM using the LCM Database (LCMDB). The LCM Cost/Schedule (LCMCS) contains cost and schedule data and logic. The LCMCS is used to generate life cycle costs and schedules for waste retrieval and processing scenarios. It uses time-based output data from the LCM to produce the logic ties in Primavera P6 necessary for shifting activities. The LCM Tool is evolving to address the needs of decision makers who want to understand the broad spectrum of risks facing complex organizations like DOE-RPP to understand how near-term programmatic decisions affect life cycle costs and commitments. (authors)

Dunford, Gary [AEM Consulting, LLC, 1201 Jadwin Avenue, Richland, WA 99352 (United States)] [AEM Consulting, LLC, 1201 Jadwin Avenue, Richland, WA 99352 (United States); Williams, David [WIT, Inc., 11173 Oak Fern Court, San Diego, CA 92131 (United States)] [WIT, Inc., 11173 Oak Fern Court, San Diego, CA 92131 (United States); Smith, Rick [Knowledge Systems Design, Inc., 13595 Quaker Hill Cross Rd, Nevada City, CA 95959 (United States)] [Knowledge Systems Design, Inc., 13595 Quaker Hill Cross Rd, Nevada City, CA 95959 (United States)

2013-07-01T23:59:59.000Z

282

Fluor Hanford, Inc. Groundwater and Technical Integration Support (Master Project) Quality Assurance Management Plan  

SciTech Connect (OSTI)

The scope of the Fluor Hanford, Inc. Groundwater and Technical Integration Support (Master Project) is to provide technical and integration support to Fluor Hanford, Inc., including operable unit investigations at 300-FF-5 and other groundwater operable units, strategic integration, technical integration and assessments, remediation decision support, and science and technology. This Quality Assurance Management Plan provides the quality assurance requirements and processes that will be followed by the Fluor Hanford, Inc. Groundwater and Technical Integration Support (Master Project).

Fix, N. J.

2008-02-20T23:59:59.000Z

283

2012 Annual Planning Summary for Portsmouth Paducah Project Office |  

Energy Savers [EERE]

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious RankCombustionImprovement Awardflash2007-42attachment1.pdfmodule(EE) |theDepartment ofOak RidgeDepartment of

284

2012 Annual Planning Summary for West Valley Demonstration Project |  

Energy Savers [EERE]

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious RankCombustionImprovement Awardflash2007-42attachment1.pdfmodule(EE) |theDepartment ofOakDepartmentDepartment

285

2013 Annual Planning Summary for the Advanced Research Projects Agency -  

Energy Savers [EERE]

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious RankCombustionImprovement Awardflash2007-42attachment1.pdfmodule(EE)2012 NuclearDepartment of3 ANNUALEnergy |

286

[Uranium Mill Tailings Remedial Action Project Office Quality Assurance Program Plan]. Revision 4  

SciTech Connect (OSTI)

The Uranium Mill Tailings Remedial Action (UMTRA) Project was established to accomplish remedial actions at inactive uranium mill tailings sites in accordance with Public Law 95-604, the Uranium Mill Tailings Radiation Control Act of 1978 (UMTRCA). The UMTRA Project`s mission is to stabilize and control the residual radioactive materials at designated sites in a safe and environmentally sound manner so as to minimize or eliminate radiation health hazards to the public. The US Department of Energy (DOE) UMTRA Project Office (UMTRA PO) directs the overall project. Since these efforts may involve possible risks to public health and safety, a quality assurance (QA) program that conforms to the applicable criteria (set forth in the reference documents) has been established to control the quality of the work. This document, the Quality Assurance Program Plan (QAPP), brings into one document the essential criteria to be applied on a selective basis, depending upon the nature of the activity being conducted, and describes how those criteria shall be applied to the UMTRA Project. The UMTRA PO shall require each Project contractor to prepare and submit for approval a more detailed QAPP that is based on the applicable criteria of this QAPP and the referenced documents. All QAPPs on the UMTRA Project shall fit within the framework of this plan.

Not Available

1992-06-01T23:59:59.000Z

287

High Burnup Dry Storage Cask Research and Development Project, Final Test Plan  

SciTech Connect (OSTI)

EPRI is leading a project team to develop and implement the first five years of a Test Plan to collect data from a SNF dry storage system containing high burnup fuel.12 The Test Plan defined in this document outlines the data to be collected, and the storage system design, procedures, and licensing necessary to implement the Test Plan.13 The main goals of the proposed test are to provide confirmatory data14 for models, future SNF dry storage cask design, and to support license renewals and new licenses for ISFSIs. To provide data that is most relevant to high burnup fuel in dry storage, the design of the test storage system must mimic real conditions that high burnup SNF experiences during all stages of dry storage: loading, cask drying, inert gas backfilling, and transfer to the ISFSI for multi-year storage.15 Along with other optional modeling, SETs, and SSTs, the data collected in this Test Plan can be used to evaluate the integrity of dry storage systems and the high burnup fuel contained therein over many decades. It should be noted that the Test Plan described in this document discusses essential activities that go beyond the first five years of Test Plan implementation.16 The first five years of the Test Plan include activities up through loading the cask, initiating the data collection, and beginning the long-term storage period at the ISFSI. The Test Plan encompasses the overall project that includes activities that may not be completed until 15 or more years from now, including continued data collection, shipment of the Research Project Cask to a Fuel Examination Facility, opening the cask at the Fuel Examination Facility, and examining the high burnup fuel after the initial storage period.

none,

2014-02-27T23:59:59.000Z

288

TOWSON'S PHYSTEC COURSE IMPROVEMENT PROJECT, YEARS 1 AND 2: RESULTS AND LESSONS LEARNED  

E-Print Network [OSTI]

TOWSON'S PHYSTEC COURSE IMPROVEMENT PROJECT, YEARS 1 AND 2: RESULTS AND LESSONS LEARNED Cody. Lastly, the project team has learned numerous lessons about large-scale course reform with respect to include lessons learned by the project team about effective course structure, different forms of inquiry

Sandifer, Cody

289

Permitting plan for the immobilized low-activity waste project  

SciTech Connect (OSTI)

This document addresses the environmental permitting requirements for the transportation and interim storage of the Immobilized Low-Activity Waste (ILAW) produced during Phase 1 of the Hanford Site privatization effort. Tri-Party Agreement (TPA) Milestone M-90 establishes a new major milestone, and associated interim milestones and target dates, governing acquisition and/or modification of facilities necessary for: (1) interim storage and disposal of Tank Waste Remediation Systems (TWRS) immobilized low-activity tank waste (ILAW) and (2) interim storage of TWRS immobilized HLW (IHLW) and other canistered high-level waste forms. Low-activity waste (LAW), low-level waste (LLW), and high-level waste (HLW) are defined by the TWRS, Hanford Site, Richland, Washington, Final Environmental Impact Statement (EIS) DOE/EIS-0189, August 1996 (TWRS, Final EIS). By definition, HLW requires permanent isolation in a deep geologic repository. Also by definition, LAW is ``the waste that remains after separating from high-level waste as much of the radioactivity as is practicable that when solidified may be disposed of as LLW in a near-surface facility according to the NRC regulations.`` It is planned to store/dispose of (ILAW) inside four empty vaults of the five that were originally constructed for the Group Program. Additional disposal facilities will be constructed to accommodate immobilized LLW packages produced after the Grout Vaults are filled. The specifications for performance of the low-activity vitrified waste form have been established with strong consideration of risk to the public. The specifications for glass waste form performance are being closely coordinated with analysis of risk. RL has pursued discussions with the NRC for a determination of the classification of the Hanford Site`s low-activity tank waste fraction. There is no known RL action to change law with respect to onsite disposal of waste.

Deffenbaugh, M.L.

1997-09-04T23:59:59.000Z

290

The Two-Column Aerosol Project (TCAP) Science Plan  

SciTech Connect (OSTI)

The Two-Column Aerosol Project (TCAP) field campaign will provide a detailed set of observations with which to (1) perform radiative and cloud condensation nuclei (CCN) closure studies, (2) evaluate a new retrieval algorithm for aerosol optical depth (AOD) in the presence of clouds using passive remote sensing, (3) extend a previously developed technique to investigate aerosol indirect effects, and (4) evaluate the performance of a detailed regional-scale model and a more parameterized global-scale model in simulating particle activation and AOD associated with the aging of anthropogenic aerosols. To meet these science objectives, the Atmospheric Radiation Measurement (ARM) Climate Research Facility will deploy the ARM Mobile Facility (AMF) and the Mobile Aerosol Observing System (MAOS) on Cape Cod, Massachusetts, for a 12-month period starting in the summer of 2012 in order to quantify aerosol properties, radiation, and cloud characteristics at a location subject to both clear and cloudy conditions, and clean and polluted conditions. These observations will be supplemented by two aircraft intensive observation periods (IOPs), one in the summer and a second in the winter. Each IOP will deploy one, and possibly two, aircraft depending on available resources. The first aircraft will be equipped with a suite of in situ instrumentation to provide measurements of aerosol optical properties, particle composition and direct-beam irradiance. The second aircraft will fly directly over the first and use a multi-wavelength high spectral resolution lidar (HSRL) and scanning polarimeter to provide continuous optical and cloud properties in the column below.

Berkowitz, CM; Berg, LK; Cziczo, DJ; Flynn, CJ; Kassianov, EI; Fast, JD; Rasch, PJ; Shilling, JE; Zaveri, RA; Zelenyuk, A; Ferrare, RA; Hostetler, CA; Cairns, B; Russell, PB; Ervens, B

2011-07-27T23:59:59.000Z

291

EM Focuses on Contract, Project Management Improvements in Three...  

Broader source: Energy.gov (indexed) [DOE]

EM, as well as best practices from EM sites such as Paducah and Oak Ridge," said Jack Surash, EM Deputy Assistant Secretary for Acquisition and Project Management. "The goal was...

292

Project W-211, initial tank retrieval systems, retrieval control system software configuration management plan  

SciTech Connect (OSTI)

This Software Configuration Management Plan (SCMP) provides the instructions for change control of the W-211 Project, Retrieval Control System (RCS) software after initial approval/release but prior to the transfer of custody to the waste tank operations contractor. This plan applies to the W-211 system software developed by the project, consisting of the computer human-machine interface (HMI) and programmable logic controller (PLC) software source and executable code, for production use by the waste tank operations contractor. The plan encompasses that portion of the W-211 RCS software represented on project-specific AUTOCAD drawings that are released as part of the C1 definitive design package (these drawings are identified on the drawing list associated with each C-1 package), and the associated software code. Implementation of the plan is required for formal acceptance testing and production release. The software configuration management plan does not apply to reports and data generated by the software except where specifically identified. Control of information produced by the software once it has been transferred for operation is the responsibility of the receiving organization.

RIECK, C.A.

1999-02-23T23:59:59.000Z

293

Savannah River Site Salt Processing Project: FY2002 Research and Development Program Plan  

SciTech Connect (OSTI)

This Plan describes the technology development program for alpha/strontium removal and Caustic Side Solvent Extraction cesium removal in FY2002. Crystalline Silicotitanate and Small Tank Tetratphenylborate Precipitation are discussed as possible backup technologies. Previous results are summarized in the Savannah River Site Salt Processing Project Research and Development Summary Report

Harmon, Harry D.; Leugemors, Robert K.; Schlahta, Stephan N.; Fink, Samuel D.; Thompson, Major C.; Walker, Darrell D.

2001-10-31T23:59:59.000Z

294

Project Plan Field Assessment of the Effectiveness of DiazaConTM on Reducing Gray  

E-Print Network [OSTI]

Project Plan Field Assessment of the Effectiveness of DiazaConTM on Reducing Gray Squirrel that the contraceptive was effective in preventing reproduction in both male and female squirrels. However, the cost of capturing and vaccinating individual EGS with GonaConTM was $15/squirrel and proved to be cost prohibitive

Bolding, M. Chad

295

Mitigation and monitoring plan for impacted wetlands at the Gunnison UMTRA Project site, Gunnison, Colorado  

SciTech Connect (OSTI)

The U.S Department of Energy (DOE) administers the Uranium Mill Tailings Remedial Action (UMTRA) Project. The UMTRA Project is the result of the Uranium Mill Tailings Radiation Control Act(UMTRA) which was passed in response to the public`s concern over the potential public health hazards related to uranium mill tailings and associated contaminated material at abandoned or otherwise uncontrolled inactive processing sites throughout the United States. The Gunnison, Colorado abandoned uranium mill site is one of the sites slated for cleanup by the DOE under authority of UMTRA. The contaminated material at this site will be transported to a disposal site on US Bureau of Land Management (BLM) land east of Gunnison. Remedial action activities will temporarily disturb 0.8 acre and permanently eliminate 5.1 acres of wetlands. This report describes the proposed mitigation plan for the 5.9 acres of impacted wetlands. In conjunction with the mitigation of the permanently impacted wetlands through the enhancement of wetland and adjacent riparian areas, impacts to wildlife as a result of this project will also be mitigated. However, wildlife mitigation is not the focus of this document and is covered in relevant BLM permits for this project. This plan proposes the enhancement of a 3:1 ratio of impacted wetlands in accordance with US Environmental Protection Agency guidelines, plus the enhancement of riparian areas for wildlife mitigation. Included in this mitigation plan is a monitoring plan to ensure that the proposed measures are working and being maintained.

Not Available

1992-06-01T23:59:59.000Z

296

Underground Test Area Project Waste Management Plan (Rev. No. 2, April 2002)  

SciTech Connect (OSTI)

The U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Operations Office (NNSA/NV) initiated the UGTA Project to characterize the risk posed to human health and the environment as a result of underground nuclear testing activities at the Nevada Test Site (NTS). The UGTA Project investigation sites have been grouped into Corrective Action Units (CAUs) in accordance with the most recent version of the Federal Facility Agreement and Consent Order. The primary UGTA objective is to gather data to characterize the groundwater aquifers beneath the NTS and adjacent lands. The investigations proposed under the UGTA program may involve the drilling and sampling of new wells; recompletion, monitoring, and sampling of existing wells; well development and hydrologic/ aquifer testing; geophysical surveys; and subsidence crater recharge evaluation. Those wastes generated as a result of these activities will be managed in accordance with existing federal and state regulations, DOE Orders, and NNSA/NV waste minimization and pollution prevention objectives. This Waste Management Plan provides a general framework for all Underground Test Area (UGTA) Project participants to follow for the characterization, storage/accumulation, treatment, and disposal of wastes generated by UGTA Project activities. The objective of this waste management plan is to provide guidelines to minimize waste generation and to properly manage wastes that are produced. Attachment 1 to this plan is the Fluid Management Plan and details specific strategies for management of fluids produced under UGTA operations.

IT Corporation, Las Vegas

2002-04-24T23:59:59.000Z

297

Pacific Northwest National Laboratory Apatite Investigation at the 100-NR-2 Quality Assurance Project Plan  

SciTech Connect (OSTI)

This Quality Assurance Project Plan provides the quality assurance requirements and processes that will be followed by staff working on the 100-NR-2 Apatite Project. The U.S. Department of Energy, Fluor Hanford, Inc., Pacific Northwest National Laboratory, and the Washington Department of Ecology agreed that the long-term strategy for groundwater remediation at 100-N would include apatite sequestration as the primary treatment, followed by a secondary treatment. The scope of this project covers the technical support needed before, during, and after treatment of the targeted subsurface environment using a new high-concentration formulation.

Fix, N. J.

2008-03-28T23:59:59.000Z

298

Project plan for resolution of the organic waste tank safety issues at the Hanford Site  

SciTech Connect (OSTI)

A multi-year project plan for the Organic Safety Project has been developed with the objective of resolving the organic safety issues associated with the High Level Waste (HLW) in Hanford`s single-shell tanks (SSTS) and double-shell tanks (DSTs). The objective of the Organic Safety Project is to ensure safe interim storage until retrieval for pretreatment and disposal operations begins, and to resolve the organic safety issues by September 2001. Since the initial identification of organics as a tank waste safety issue, progress has been made in understanding the specific aspects of organic waste combustibility, and in developing and implementing activities to resolve the organic safety issues.

Meacham, J.E.

1996-10-03T23:59:59.000Z

299

2030 Transportation and Mobility Plan  

E-Print Network [OSTI]

sections are as follows: 1. Introduction 2. Bi-State MPO Area Description 3. Planning Horizon Description and Data Projections 4. Long Range Plan Presentation 5. Plan Implementation and Monitoring Procedures 6. Bi-State MPO 2030 Transportation..., improved access at the Leigh Avenue/I-540 interchange, and the deployment of appropriate Intelligent Transportation Systems (ITS) projects. The Airport Master Plan Update has estimated a total airport improvement cost of $ 74,170,000 over a Three (3...

Bi-State Metropolitan Planning Organization

2006-08-11T23:59:59.000Z

300

NAPA Collaboration Project: Worker Dialogue to Improve Worker...  

Office of Environmental Management (EM)

will host A Worker Dialogue: Improving Health, Safety and Security at DOE. This web-based "conversation" will engage the DOE workforce in an open, online dialogue to...

Note: This page contains sample records for the topic "improvement project plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


301

Boyer-Tillamook Access Road Improvement Project 1 Finding of...  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

dangerous. In addition, improvements to access road stream crossings would facilitate fish passage. Construction is expected to last from 2 to 4 months, although work may need to...

302

Uncertainty and Sensitivity Analyses Plan. Draft for Peer Review: Hanford Environmental Dose Reconstruction Project  

SciTech Connect (OSTI)

Hanford Environmental Dose Reconstruction (HEDR) Project staff are developing mathematical models to be used to estimate the radiation dose that individuals may have received as a result of emissions since 1944 from the US Department of Energy`s (DOE) Hanford Site near Richland, Washington. An uncertainty and sensitivity analyses plan is essential to understand and interpret the predictions from these mathematical models. This is especially true in the case of the HEDR models where the values of many parameters are unknown. This plan gives a thorough documentation of the uncertainty and hierarchical sensitivity analysis methods recommended for use on all HEDR mathematical models. The documentation includes both technical definitions and examples. In addition, an extensive demonstration of the uncertainty and sensitivity analysis process is provided using actual results from the Hanford Environmental Dose Reconstruction Integrated Codes (HEDRIC). This demonstration shows how the approaches used in the recommended plan can be adapted for all dose predictions in the HEDR Project.

Simpson, J.C.; Ramsdell, J.V. Jr.

1993-04-01T23:59:59.000Z

303

FY 2015 OFFICE OF BUDGET & FINANCE STRATEGIC PLAN Strategic Plan Items & Projects  

E-Print Network [OSTI]

Reports Uniform Guidance Review Spreadsheet Journal process improvements Three New Quality Assurance Balance Reporting Combination Editing Rule Review Budget Deficit Summer Workshop 3.3.1.3. Payroll Work

O'Toole, Alice J.

304

[Uranium Mill Tailings Remedial Action Project Office Quality Assurance Program Plan  

SciTech Connect (OSTI)

The Uranium Mill Tailings Remedial Action (UMTRA) Project was established to accomplish remedial actions at inactive uranium mill tailings sites in accordance with Public Law 95-604, the Uranium Mill Tailings Radiation Control Act of 1978 (UMTRCA). The UMTRA Project's mission is to stabilize and control the residual radioactive materials at designated sites in a safe and environmentally sound manner so as to minimize or eliminate radiation health hazards to the public. The US Department of Energy (DOE) UMTRA Project Office (UMTRA PO) directs the overall project. Since these efforts may involve possible risks to public health and safety, a quality assurance (QA) program that conforms to the applicable criteria (set forth in the reference documents) has been established to control the quality of the work. This document, the Quality Assurance Program Plan (QAPP), brings into one document the essential criteria to be applied on a selective basis, depending upon the nature of the activity being conducted, and describes how those criteria shall be applied to the UMTRA Project. The UMTRA PO shall require each Project contractor to prepare and submit for approval a more detailed QAPP that is based on the applicable criteria of this QAPP and the referenced documents. All QAPPs on the UMTRA Project shall fit within the framework of this plan.

Not Available

1992-06-01T23:59:59.000Z

305

UMTRA Project Office Federal Employee Occupational Safety and Health Program Plan. Final draft  

SciTech Connect (OSTI)

This document establishes the Federal Employee Occupational Safety and Health (FEOSH) Program for the US Department of Energy (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project Office. This program will ensure compliance with the applicable requirements of DOE Order 3790.1 B and DOE Albuquerque Operations Office (AL) Order 3790.1A. FEOSH Program responsibilities delegated by the DOE-AL to the UMTRA Project Office by AL Order 3790.1A also are assigned. The UMTRA Project Office has developed the UMTRA Project Environmental, Safety, and Health (ES&H) Plan (DOE, 1992), which establishes the basic programmatic ES&H requirements for all participants on the UMTRA Project. The ES&H plan is designed primarily to cover remedial action activities at UMTRA sites, and defines the ES&H responsibilities of both the UMTRA Project Office and its contractors. The UMTRA FEOSH Program described herein is a subset of the overall UMTRA ES&H program and covers only the federal employees working on the UMTRA Project.

Young, B.H.

1994-02-01T23:59:59.000Z

306

UMTRA project office federal employee occupational safety and health program plan. Revision 1  

SciTech Connect (OSTI)

This document establishes the Federal Employee Occupational Safety and Health (FEOSH) Program for the US Department of Energy (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project Office. This program will ensure compliance with applicable requirements of DOE Order 3790.1B and DOE Albuquerque Operations Office (AL) Order 3790.lA. FEOSH Program responsibilities delegated by the DOE-AL to the UMTRA Project Office by AL Order 3790.1A also are assigned. The UMTRA Project Office has developed the UMTRA Project Environmental, Safety, and Health (ES&H) Plan (DOE, 1992), which establishes the basic programmatic ES&H requirements for all participants on the UMTRA Project. The ES&H plan is designed primarily to cover remedial action activities at UMTRA sites and defines the ES&H responsibilities of both the UMTRA Project Office and its contractors. The UMTRA FEOSH Program described herein is a subset of the overall UMTRA ES&H program and covers only federal employees working on the UMTRA Project.

Not Available

1994-06-01T23:59:59.000Z

307

Report on the planning workshop on cost-effective ceramic machining. Ceramic Technology Project  

SciTech Connect (OSTI)

A workshop on ``Cost Effective Ceramic Machining`` (CECM) was held at Oak Ridge Associated Universities Pollard Auditorium, Oak Ridge, Tennessee, May 1991. The purpose of this workshop was to present a preliminary project plan for industry critique and to identify specific components and cost-reduction targets for a new project on Cost Effective Ceramic Machining. The CECM project is an extension of the work on the Ceramic Technology for Advanced Heat Engines (CTAHE) Program sponsored by the Department of Energy, Office of Transportation Materials. The workshop consisted of fifteen invited papers, discussions, a survey of the attendee`s opinions, and a tour of the High Temperature Materials Laboratory at ORNL. The total number of registrants was sixty-seven, including thirty-three from industry or private sector organizations, seven from universities, three from industry groups, fourteen from DOE laboratories (including ORNL, Y-12, and Lawrence Livermore Laboratory), three from trade associations, and three from other government organizations. Forty- one survey forms, which critiqued the proposed project plan, were completed by attendees, and the results are presented in this report. Valves, cam roller followers, water pump seals, and diesel engine head plates were rated highest fro application of ceramic machining concepts to reduce cost. Coarse grinding, abrasives and wheel technology, and fine grinding were most highly rated as regards their impact on cost reduction. Specific cost-reduction targets for given parts varied greatly in the survey results and were not felt to be useful for the purposes for the CECM plan development. A range of individual comments were obtained and are listed in an appendix. As a result of the workshop and subsequent discussions, a modified project plan, different in certain aspects from the original CECM plan, has been developed.

Blau, P.J.

1991-11-01T23:59:59.000Z

308

The project RTPPP (Development of a realtime PPP processing facility) is planned to be a followup project of RAPPP (Innovative Algorithms for Rapid Precise Point Positioning),  

E-Print Network [OSTI]

RTPPP The project RTPPP (Development of a realtime PPP processing facility) is planned to be a followup project of RAPPP (Innovative Algorithms for Rapid Precise Point Positioning), which has RAPPP, the proposed project RTPPP concentrates on the possibilities of the PPP technique within a real

Schuh, Harald

309

PNNL Apatite Investigation at 100-NR-2 Quality Assurance Project Plan  

SciTech Connect (OSTI)

In 2004, the U.S. Department of Energy, Fluor Hanford, Inc., Pacific Northwest National Laboratory (PNNL), and the Washington Department of Ecology agreed that the long-term strategy for groundwater remediation at the 100-N Area would include apatite sequestration as the primary treatment, followed by a secondary treatment if necessary. Since then, the agencies have worked together to agree on which apatite sequestration technology has the greatest chance of reducing strontium-90 flux to the Columbia River. This Quality Assurance Project Plan provides the quality assurance requirements and processes that will be followed by staff working on the PNNL Apatite Investigation at 100-NR-2 Project. The plan is designed to be used exclusively by project staff.

Fix, N. J.

2009-04-02T23:59:59.000Z

310

Nez Perce Tribal Hatchery Project; Operations and Maintenance and Planning and Design, 2002 Annual Report.  

SciTech Connect (OSTI)

This report fulfills the contract obligations based on the Statement of Work (SOW) for the project as contracted with Bonneville Power Administration (BPA). Nez Perce Tribal Hatchery (NPTH) Year-2002 annual report combines information from two contracts with a combined value of $3,036,014. Bonneville Power Administration identifies them as follows; (1) Part I--Operations and Maintenance--Project No. 1983-350-00, Contract No. 4504, and $2,682,635 which includes--Equipment costs of $1,807,105. (2) Part II--Planning and Design--Project No. 1983-35-04, Contract No. 4035, $352,379 for Clearwater Coho Restoration Master Plan development Based on NPPC authorization for construction and operation of NPTH, the annual contracts were negotiated for the amounts shown above under (1) and (2). Construction contracts were handled by BPA until all facilities are completed and accepted.

Larson, Roy Edward; Walker, Grant W.; Penney, Aaron K. (Nez Perce Tribe, Lapwai, ID)

2005-12-01T23:59:59.000Z

311

Socio-economic benefits in Plan Vivo projects: Trees for Global Benefits, Uganda 61 Appendix 6.7  

E-Print Network [OSTI]

Socio-economic benefits in Plan Vivo projects: Trees for Global Benefits, Uganda 61 Appendix 6 for Global Benefits, Uganda 62 Appendix 6.7 16. What size (ha) are they: Farm 1. ____________ Farm 2 if necessary #12;Socio-economic benefits in Plan Vivo projects: Trees for Global Benefits, Uganda 63 Appendix 6

312

Project Hanford management contract quality assurance program implementation plan for nuclear facilities  

SciTech Connect (OSTI)

During transition from the Westinghouse Hanford Company (WHC) Management and Operations (M and O) contract to the Fluor Daniel Hanford (FDH) Management and Integration (M and I) contract, existing WHC policies, procedures, and manuals were reviewed to determine which to adopt on an interim basis. Both WHC-SP-1131,Hanford Quality Assurance Program and Implementation Plan, and WHC-CM-4-2, Quality Assurance Manual, were adopted; however, it was recognized that revisions were required to address the functions and responsibilities of the Project Hanford Management Contract (PHMC). This Quality Assurance Program Implementation Plan for Nuclear Facilities (HNF-SP-1228) supersedes the implementation portion of WHC-SP-1 13 1, Rev. 1. The revised Quality Assurance (QA) Program is documented in the Project Hanford Quality Assurance Program Description (QAPD), HNF-MP-599. That document replaces the QA Program in WHC-SP-1131, Rev. 1. The scope of this document is limited to documenting the nuclear facilities managed by FDH and its Major Subcontractors (MSCS) and the status of the implementation of 10 CFR 830.120, Quality Assurance Requirements, at those facilities. Since the QA Program for the nuclear facilities is now documented in the QAPD, future updates of the information provided in this plan will be by letter. The layout of this plan is similar to that of WHC-SP-1 13 1, Rev. 1. Sections 2.0 and 3.0 provide an overview of the Project Hanford QA Program. A list of Project Hanford nuclear facilities is provided in Section 4.0. Section 5.0 provides the status of facility compliance to 10 CFR 830.120. Sections 6.0, 7.0, and 8.0 provide requested exemptions, status of open items, and references, respectively. The four appendices correspond to the four projects that comprise Project Hanford.

Bibb, E.K.

1997-10-15T23:59:59.000Z

313

Improving the Approximation and Convergence Capabilities of Projection Pursuit Learning  

E-Print Network [OSTI]

. Projection pursuit learning (PPL) proposed by Hwang et al. formulates PPR using a two­layer feedforward neural network. One of the main differences between PPR and PPL is that the smoothers in PPR are nonparametric, whereas those in PPL are based on Hermite functions of some predefined highest order R. While

Kwok, James Tin-Yau

314

CAMPUS PLANNING COMMITTEE PLANNING AND REVIEW PROCESS FOR MAJOR CAPITAL PROJECTS  

E-Print Network [OSTI]

, efficient and cost effective manner; · Maximize the capital dollars available to UCSB from all sources with other campuses for scarce resources.); · Optimize the use of capital dollars; · Establish a clear; whose total cost is over $400,000. #12;B. 5-YEAR STATE-FUNDED MAJOR CAPITAL IMPROVEMENT PROGRAM

California at Santa Barbara, University of

315

Los Alamos National Laboratory transuranic waste quality assurance project plan. Revision 1  

SciTech Connect (OSTI)

This Transuranic (TRU) Waste Quality Assurance Project Plan (QAPjP) serves as the quality management plan for the characterization of transuranic waste in preparation for certification and transportation. The Transuranic Waste Characterization/Certification Program (TWCP) consists of personnel who sample and analyze waste, validate and report data; and provide project management, quality assurance, audit and assessment, and records management support, all in accordance with established requirements for disposal of TRU waste at the Waste Isolation Pilot Plant (WIPP) facility. This QAPjP addresses how the TWCP meets the quality requirements of the Carlsbad Area Office (CAO) Quality Assurance Program Description (QAPD) and the technical requirements of the Transuranic Waste Characterization Quality Assurance Program Plan (QAPP). The TWCP characterizes and certifies retrievably stored and newly generated TRU waste using the waste selection, testing, sampling, and analytical techniques and data quality objectives (DQOs) described in the QAPP, the Los Alamos National Laboratory Transuranic Waste Certification Plan (Certification Plan), and the CST Waste Management Facilities Waste Acceptance Criteria and Certification [Los Alamos National Laboratory (LANL) Waste Acceptance Criteria (WAC)]. At the present, the TWCP does not address remote-handled (RH) waste.

NONE

1997-04-14T23:59:59.000Z

316

UMTRA Project water sampling and analysis plan, Canonsburg, Pennsylvania. Revision 1  

SciTech Connect (OSTI)

Surface remedial action was completed at the US Department of Energy (DOE) Canonsburg and Burrell Uranium Mill Tailings Remedial Action (UMTRA) Project sites in southwestern Pennsylvania in 1985 and 1987, respectively. The Burrell disposal site, included in the UMTRA Project as a vicinity property, was remediated in conjunction with the remedial action at Canonsburg. On 27 May 1994, the Nuclear Regulatory Commission (NRC) accepted the DOE final Long-Term Surveillance Plan (LTSP) (DOE, 1993) for Burrell thus establishing the site under the general license in 10 CFR {section}40.27 (1994). In accordance with the DOE guidance document for long-term surveillance (DOE, 1995), all NRC/DOE interaction on the Burrell site`s long-term care now is conducted with the DOE Grand Junction Projects Office in Grand Junction, Colorado, and is no longer the responsibility of the DOE UMTRA Project Team in Albuquerque, New Mexico. Therefore, the planned sampling activities described in this water sampling and analysis plan (WSAP) are limited to the Canonsburg site. This WSAP identifies and justifies the sampling locations, analytical parameters, detection limits, and sampling frequencies for routine monitoring at the Canonsburg site for calendar years 1995 and 1996. Currently, the analytical data further the site characterization and demonstrate that the disposal cell`s initial performance is in accordance with design requirements.

NONE

1995-09-01T23:59:59.000Z

317

Project management plan for Project W-320, Tank 241-C-106 sluicing. Revision 2  

SciTech Connect (OSTI)

A major mission of the US Department of Energy (DOE) is the permanent disposal of Hanford Site defense wastes by utilizing safe, environmentally acceptable, and cost-effective disposal methods that meet applicable regulations. The Tank Waste Remediation System (TWRS) Program was established at the Hanford Site to manage and control activities specific to the remediation of safety watch list tanks, including high-heat-producing tanks, and for the ultimate characterization, retrieval, pretreatment, and disposal of the low- and high-level fractions of the tank waste. Project W-320, Tank 241-C-106 Sluicing, provides the methodology, equipment, utilities, and facilities necessary for retrieving the high-heat waste from single-shell tank (SST) 24-C-106. Project W-320 is a fiscal year (FY) 1993 expense-funded major project, and has a design life of 2 years. Retrieval of the waste in tank 241-C-106 will be accomplished through mobilization of the sludge into a pumpable slurry using past-practice sluicing. The waste is then transferred directly to a double-shell tank for interim storage, subsequent pretreatment, and eventual disposal. A detailed description of the management organization and responsibilities of all participants is presented in this document.

Phillips, D.R.

1994-07-01T23:59:59.000Z

318

Improving customer order visibility to enable improved planning and decision making  

E-Print Network [OSTI]

The General Purpose Drives organization of ABB Switzerland does not capture sufficient data on the movement of customer orders through the production process to make efficient decisions on where to allocate improvement ...

Krause, Karla M. (Karla Margarete)

2011-01-01T23:59:59.000Z

319

Management and overview Quality Assurance Program Plan. [Uranium Mill Tailings Remedial Action (UMTRA) Project  

SciTech Connect (OSTI)

The Uranium Mill Tailings Remedial Action (UMTRA) Project Office (DOE/ UMTRA-PO) is the US Department of Energy (DOE) Albuquerque Operations Office (AL) organization charged with the responsibility of managing and coordinating the activities of the various participating organizations and support contractors working on the UMTRA Project. This Quality Assurance Program Plan (QAPP) describes how the DOE/UMTRA-PO, as assisted by the Technical Assistance Contractor (TAC), performs the quality assurance (QA) aspects of managing and coordinating UMTRA Project activities. This QAPP was developed to comply with DOE Order 5700.6A, August, 1981, and AL Order 5700.6B, April, 1984, which contain the criteria applicable to Project QA activities.

Not Available

1986-08-01T23:59:59.000Z

320

Idaho National Laboratory Ten-Year Site Plan Project Description Document  

SciTech Connect (OSTI)

This document describes the currently active and proposed infrastructure projects listed in Appendix B of the Idaho National Laboratory 2013-2022 Ten Year Site Plan (DOE/ID-11449). It was produced in accordance with Contract Data Requirements List I.06. The projects delineated in this document support infrastructure needs at INL's Research and Education Campus, Materials and Fuels Complex, Advanced Test Reactor Complex and the greater site-wide area. The projects provide critical infrastructure needed to meet current and future INL opereational and research needs. Execution of these projects will restore, rebuild, and revitalize INL's physical infrastructure; enhance program execution, and make a significant contribution toward reducing complex-wide deferred maintenance.

Not Listed

2012-03-01T23:59:59.000Z

Note: This page contains sample records for the topic "improvement project plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


321

Waste minimization plan construction and operation of the replacement cross-site transfer system, project W-058  

SciTech Connect (OSTI)

This report addresses the research and development of a waste minimization plan for the construction and operation of Project W-058, Replacement of the Cross-Site Transfer System, on the Hanford Site. The plan is based on Washington Administrative Code (WAC) 173-307, Plans. The waste minimization plan identifies areas where pollution prevention/waste minimization principles can be incorporated into the construction and operation of the cross-site transfer system.

Boucher, T.D.

1996-04-01T23:59:59.000Z

322

Global Threat Reduction Initiative Fuel Thermo-Physical Characterization Project: Sample Management Plan  

SciTech Connect (OSTI)

This sample management plan provides guidelines for sectioning, preparation, acceptance criteria, analytical path, and end-of-life disposal for the fuel element segments utilized in the Global Threat Reduction Initiative (GTRI), Fuel Thermo-Physical Characterization Project. The Fuel Thermo-Physical Characterization Project is tasked with analysis of irradiated Low Enriched Uranium (LEU) Molybdenum (U-Mo) fuel element samples to support the GTRI conversion program. Sample analysis may include optical microscopy (OM), scanning electron microscopy (SEM) fuel-surface interface analysis, gas pycnometry (density) measurements, laser flash analysis (LFA), differential scanning calorimetry (DSC), thermogravimetry and differential thermal analysis with mass spectroscopy (TG /DTA-MS), Inductively Coupled Plasma Spectrophotometry (ICP), alpha spectroscopy, and Thermal Ionization Mass Spectroscopy (TIMS). The project will utilize existing Radiochemical Processing Laboratory (RPL) operating, technical, and administrative procedures for sample receipt, processing, and analyses. Test instructions (TIs), which are documents used to provide specific details regarding the implementation of an existing RPL approved technical or operational procedure, will also be used to communicate to staff project specific parameters requested by the Principal Investigator (PI). TIs will be developed, reviewed, and issued in accordance with the latest revision of the RPL-PLN-700, RPL Operations Plan. Additionally, the PI must approve all project test instructions and red-line changes to test instructions.

Casella, Amanda J.; Pereira, Mario M.; Steen, Franciska H.

2013-01-01T23:59:59.000Z

323

Improving Project Management at the Department of Energy | Department of  

Office of Environmental Management (EM)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr May Jun Jul(Summary) " ,"ClickPipelinesProvedDecember 2005DepartmentDecemberGlossaryEnergyImportant FilingEnergy Project

324

EXTERNAL PEER REVIEW REPORT Sabine-Neches Waterway (SNWW) Channel Improvement Plan (CIP) Draft Feasibility  

E-Print Network [OSTI]

FINAL EXTERNAL PEER REVIEW REPORT for Sabine-Neches Waterway (SNWW) Channel Improvement Plan (CIP Review Comments from the SNWW CIP Feasibility Study and DEIS External Peer Review Panel................ 3 Table 3. External Peer Reviewer Panel for the SNWW CIP Feasibility Study and DEIS: Technical

US Army Corps of Engineers

325

IEEE TRANSACTIONS ON ROBOTICS / SHORT PAPER 1 Improving Motion Planning Algorithms by Efficient  

E-Print Network [OSTI]

IEEE TRANSACTIONS ON ROBOTICS / SHORT PAPER 1 Improving Motion Planning Algorithms by Efficient-neighbor queries in Cartesian products of R, S1 and RP3 , the most common topological spaces in the context), which are designed for efficient nearest-neighbor generation in Rd . These techniques, however

LaValle, Steven M.

326

Building indicator groups based on species characteristics can improve conservation planning  

E-Print Network [OSTI]

is in identifying important areas for the conservation of biodiversity. As networks of areas encompassing biodiversity to select networks of areas for conservation? In the literature, reliable indicator groupsBuilding indicator groups based on species characteristics can improve conservation planning

Manne, Lisa

327

Uranium Mill Tailings Remedial Action Project, Surface Project Management Plan. Revision 1  

SciTech Connect (OSTI)

Title I of the Uranium Mill Tailings Radiation Control Act (UMTRCA) authorizes the US Department of Energy (DOE) to undertake remedial action at 24 designated inactive uranium processing sites and associated vicinity properties (VP) containing uranium mill tailings and related residual radioactive materials. The purpose of the Uranium Mill Tailings Remedial Action (UMTRA) Surface Project is to minimize or eliminate radiation health hazards to the public and the environment at the 24 sites and related VPs. This document describes the management organization, system, and methods used to manage the design, construction, and other activities required to clean up the designated sites and associated VPs, in accordance with the UMTRCA.

Not Available

1994-12-01T23:59:59.000Z

328

Project W-314 specific test and evaluation plan for AZ tank farm upgrades  

SciTech Connect (OSTI)

The purpose of this Specific Test and Evaluation Plan (STEP) is to provide a detailed written plan for the systematic testing of modifications made by the addition of the SN-631 transfer line from the AZ-O1A pit to the AZ-02A pit by the W-314 Project. The STEP develops the outline for test procedures that verify the system`s performance to the established Project design criteria. The STEP is a lower tier document based on the W-314 Test and Evaluation P1 an (TEP). Testing includes Validations and Verifications (e.g., Commercial Grade Item Dedication activities, etc), Factory Tests and Inspections (FTIs), installation tests and inspections, Construction Tests and Inspections (CTIs), Acceptance Test Procedures (ATPs), Pre-Operational Test Procedures (POTPs), and Operational Test Procedures (OTPs). The STEP will be utilized in conjunction with the TEP for verification and validation.

Hays, W.H.

1998-08-12T23:59:59.000Z

329

Project plan for the background soils project for the Paducah Gaseous Diffusion Plant, Paducah, Kentucky  

SciTech Connect (OSTI)

The Background Soils Project for the Paducah Gaseous Diffusion Plant (BSPP) will determine the background concentration levels of selected naturally occurring metals, other inorganics, and radionuclides in soils from uncontaminated areas in proximity to the Paducah Gaseous Diffusion Plant (PGDP) in Paducah, Kentucky. The data will be used for comparison with characterization and compliance data for soils, with significant differences being indicative of contamination. All data collected as part of this project will be in addition to other background databases established for the PGDP. The BSPP will address the variability of surface and near-surface concentration levels with respect to (1) soil taxonomical types (series) and (2) soil sampling depths within a specific soil profile. The BSPP will also address the variability of concentration levels in deeper geologic formations by collecting samples of geologic materials. The BSPP will establish a database, with recommendations on how to use the data for contaminated site assessment, and provide data to estimate the potential human and health and ecological risk associated with background level concentrations of potentially hazardous constituents. BSPP data will be used or applied as follows.

NONE

1995-09-01T23:59:59.000Z

330

Site Observational Work Plan for the UMTRA Project Site at Shiprock, New Mexico. Revision  

SciTech Connect (OSTI)

The site observational work plan (SOWP) for the Shiprock, New Mexico, Uranium Mill Tailings Remedial Action (UMTRA) Project Site is one of the first documents for developing an approach for achieving ground water compliance at the site. This SOWP applies Shiprock site information to a regulatory compliance framework, which identifies strategies for meeting ground water compliance at the site. The compliance framework was developed in the UMTRA ground water programmatic environmental impact statement.

NONE

1995-07-01T23:59:59.000Z

331

Implementation Plan for Tank Farm Transition Projects Suspect and Counterfeit Items  

SciTech Connect (OSTI)

This plan is designed to provide an appropriate level of confidence that Tank Farm Transition Projects (TFTP) facilities will be evaluated to assess the presence of suspect/counterfeit items. It is intended to identify suspect/counterfeit items that are presently in inventory and provide for the reporting and disposition of those items. Items which have been installed will also receive appropriate evaluation using a graded approach to achieve optimum results balanced against safety considerations and cost effectiveness.

TRUE, R.R.

2000-03-16T23:59:59.000Z

332

Program management plan for the Molten Salt Reactor Experiment Remediation Project at Oak Ridge National Laboratory, Oak Ridge, Tennessee  

SciTech Connect (OSTI)

The primary mission of the Molten Salt Reactor Experiment (MSRE) Remediation Project is to effectively implement the risk-reduction strategies and technical plans to stabilize and prevent further migration of uranium within the MSRE facility, remove the uranium and fuel salts from the system, and dispose of the fuel and flush salts by storage in appropriate depositories to bring the facility to a surveillance and maintenance condition before decontamination and decommissioning. This Project Management Plan (PMP) for the MSRE Remediation Project details project purpose; technical objectives, milestones, and cost objectives; work plan; work breakdown structure (WBS); schedule; management organization and responsibilities; project management performance measurement planning, and control; conduct of operations; configuration management; environmental, safety, and health compliance; quality assurance; operational readiness reviews; and training.

NONE

1996-09-01T23:59:59.000Z

333

UMTRA project water sampling and analysis plan, Falls City, Texas. Revision 1  

SciTech Connect (OSTI)

Planned, routine ground water sampling activities at the US Department of Energy (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project site near Falls City, Texas, are described in this water sampling and analysis plan (WSAP). The following plan identifies and justifies the sampling locations, analytical parameters, and sampling frequency for the routine monitoring stations at the site. The ground water data are used for site characterization and risk assessment. The regulatory basis for routine ground water monitoring at UMTRA Project sites is derived from the US Environmental Protection Agency (EPA) regulations in 40 CFR Part 192. Sampling procedures are guided by the UMTRA Project standard operating procedures (SOP) (JEG, n.d.), the Technical Approach Document (TAD) (DOE, 1989), and the most effective technical approach for the site. The Falls City site is in Karnes County, Texas, approximately 8 miles [13 kilometers southwest of the town of Falls City and 46 mi (74 km) southeast of San Antonio, Texas. Before surface remedial action, the tailings site consisted of two parcels. Parcel A consisted of the mill site, one mill building, five tailings piles, and one tailings pond south of Farm-to-Market (FM) Road 1344 and west of FM 791. A sixth tailings pile designated Parcel B was north of FM 791 and east of FM 1344.

NONE

1995-09-01T23:59:59.000Z

334

UMTRA Project value engineering plan. [Design and construction of stabilized tailings embankments  

SciTech Connect (OSTI)

The objective of value engineering (VE) on the Uranium MILL Tailings Remedial Action (UMTRA) Project is to ensure that remedial action at the UMTRA Project sites is performed to meet the US Environmental Protection Agency (EPA) standards for inactive uranium mill tailings sites at the lowest cost, while maintaining a high quality of work. Through review of designs and consideration of reasonable, less expensive alternatives, VE can be an effective cost reduction tool and a means to improve the design. The UMTRA Project products are the design and construction of stabilized tailings embankments.

Not Available

1990-06-01T23:59:59.000Z

335

Quality Assurance (QA) Program Plan Conceptual Design Phase of Project W-521 Waste Feed Delivery Systems [SUPERSEDED BY RPP-6649 Rev. 0  

SciTech Connect (OSTI)

The Quality Assurance Program Plan (QAPP) describes the quality assurance implementation strategy for Project W-521 during conceptual design.

WHITE, K.A.

2000-08-02T23:59:59.000Z

336

Rainwater Wildlife Area Management Plan Executive Summary : A Columbia Basin Wildlife Mitigation Project.  

SciTech Connect (OSTI)

This Executive Summary provides an overview of the Draft Rainwater Wildlife Area Management Plan. The comprehensive plan can be viewed on the Confederated Tribes of the Umatilla Indian Reservation (CTUIR) website at: www.umatilla.nsn.us or requested in hard copy from the CTUIR at the address below. The wildlife area was established in September 1998 when the CTUIR purchased the Rainwater Ranch through Bonneville Power Administration (BPA) for purposes of fish and wildlife mitigation for the McNary and John Day dams. The Management Plan has been developed under a standardized planning process developed by BPA for Columbia River Basin Wildlife Mitigation Projects (See Guiding Policies Section below). The plan outlines the framework for managing the project area, provides an assessment of existing conditions and key resource issues, and presents an array of habitat management and enhancement strategies. The plan culminates into a 5-Year Action Plan that will focus management actions and prioritize funding during the 2002-2006 planning period. Since acquisition of the property in late 1998, the CTUIR has conducted an extensive baseline resource assessment in preparation for the management plan, initiated habitat restoration in the Griffin Fork drainage to address road-related resource damage caused by roads constructed for forest practices and an extensive flood event in 1996, and initiated infrastructure developments associated with the Access and Travel Management Plan (i.e., installed parking areas, gates, and public information signs). In addition to these efforts, the CTUIR has worked to set up a long-term funding mechanism with BPA through the NPPC Fish and Wildlife Program. The CTUIR has also continued to coordinate closely with local and state government organizations to ensure consistency with local land use laws and maintain open lines of communication regarding important issues such as big game hunting, tribal member exercise of treaty rights, and public access. During the past two years, non-Indian public concern over big game hunting issues has at times overwhelmed other issues related to the wildlife area. In 2001, the CTUIR Fish and Wildlife Committee closed the wildlife area to tribal branch antlered bull elk harvest in response to harvest data that indicated harvest rates were greater than expected. In addition, illegal harvest of mature bull elk in southeastern Washington during the 2001 season exceeded the legal tribal and nontribal harvest combined which has created a potential significant regression in the bull;cow ratio in the Blue Mountain Elk herd. CTUIR Fish and Wildlife Committee and staff and Washington Department of Fish and Wildlife Regional Director and staff have been coordinating regularly to develop strategies to address harvest rates and ensure protection of viable big game herds in southeastern Washington. The CTUIR Fish and Wildlife Committee and WDFW has jointly agreed to continue close coordination on this and other issues and continue working together to ensure the long-term vigor of the elk herd on the Rainwater Wildlife Area. The purpose of the project is to protect, enhance, and mitigate fish and wildlife resources impacted by Columbia River Basin hydroelectric development. The effort is one of several wildlife mitigation projects in the region developed to compensate for terrestrial habitat losses resulting from the construction of McNary and John Day Hydroelectric facilities located on the mainstem Columbia River. While this project is driven primarily by the purpose and need to mitigate for wildlife habitat losses, it is also recognized that management strategies will also benefit many other non-target fish and wildlife species and associated natural resources.

Childs, Allen B.

2002-02-01T23:59:59.000Z

337

The 300 Area Integrated Field Research Challenge Quality Assurance Project Plan  

SciTech Connect (OSTI)

Pacific Northwest National Laboratory and a group of expert collaborators are using the U.S. Department of Energy Hanford Site 300 Area uranium plume within the footprint of the 300-FF-5 groundwater operable unit as a site for an Integrated Field-Scale Subsurface Research Challenge (IFRC). The IFRC is entitled Multi-Scale Mass Transfer Processes Controlling Natural Attenuation and Engineered Remediation: An IFRC Focused on the Hanford Site 300 Area Uranium Plume Project. The theme is investigation of multi-scale mass transfer processes. A series of forefront science questions on mass transfer are posed for research that relate to the effect of spatial heterogeneities; the importance of scale; coupled interactions between biogeochemical, hydrologic, and mass transfer processes; and measurements/approaches needed to characterize and model a mass transfer-dominated system. This Quality Assurance Project Plan provides the quality assurance requirements and processes that will be followed by the 300 Area IFRC Project. This plan is designed to be used exclusively by project staff.

Fix, N. J.

2009-04-29T23:59:59.000Z

338

Supplement to the UMTRA Project water sampling and analysis plan, Riverton, Wyoming  

SciTech Connect (OSTI)

This water sampling and analysis plan (WSAP) supplement supports the regulatory and technical basis for water sampling at the Riverton, Wyoming, Uranium Mill Tailings Remedial Action (UMTRA) Project site, as defined in the 1994 WSAP document for Riverton (DOE, 1994). Further, the supplement serves to confirm the Project`s present understanding of the site relative to the hydrogeology and contaminant distribution as well as the intent to continue to use the sampling strategy as presented in the 1994 WSAP document for Riverton. Ground water and surface water monitoring activities are derived from the US Environmental Protection Agency regulations in 40 CFR Part 192 and 60 FR 2854. Sampling procedures are guided by the UMTRA Project standard operating procedures (JEG, n.d.), the Technical Approach Document (DOE, 1989), and the most effective technical approach for the site. Additional site-specific documents relevant to the Riverton site are the Riverton Baseline Risk Assessment (BLRA) (DOE, 1995a) and the Riverton Site Observational Work Plan (SOWP) (DOE, 1995b).

NONE

1995-09-01T23:59:59.000Z

339

Supplement to the UMTRA Project water sampling and analysis plan, Monument Valley, Arizona  

SciTech Connect (OSTI)

This water sampling and analysis plan (WSAP) supplement supports the regulatory and technical basis for water sampling at the Riverton, Wyoming, Uranium Mill Tailings Remedial Action (UMTRA) Project site, as defined in the 1994 WSAP document for Riverton (DOE, 1994). Further, the supplement serves to confirm the Project`s present understanding of the site relative to the hydrogeology and contaminant distribution as well as the intent to continue to use the sampling strategy as presented in the 1994 WSAP document for Riverton. Ground water and surface water monitoring activities are derived from the US Environmental Protection Agency regulations in 40 CFR Part 192 and 60 FR 2854. Sampling procedures are guided by the UMTRA Project standard operating procedures (JEG, n.d.), the Technical Approach Document (DOE, 1989), and the most effective technical approach for the site. Additional site-specific documents relevant to the Riverton site are the Riverton Baseline Risk Assessment (BLRA) (DOE, 1995a) and the Riverton Site Observational Work Plan (SOWP) (DOE, 1995b).

NONE

1995-09-01T23:59:59.000Z

340

Global Threat Reduction Initiative Fuel-Thermo-Physical Characterization Project Quality Assurance Plan  

SciTech Connect (OSTI)

The charter of the Fuel Thermo-Physical Characterization Project is to ready Pacific Northwest National Laboratory (PNNL) facilities and processes for the receipt of unirradiated and irradiated low enriched uranium (LEU) molybdenum (U-Mo) fuel element samples, and to perform analysis to support the Global Threat Reduction Initiative conversion program. PNNL’s support for the program will include the establishment of post-irradiation examination processes, including thermo-physical properties, unique to the U.S. Department of Energy laboratories. These processes will ultimately support the submission of the base fuel qualification (BFQ) to the U.S. Nuclear Regulatory Commission (NRC) and revisions to High Performance Research Reactor Safety Analysis Reports to enable conversion from highly enriched uranium to LEU fuel. This quality assurance plan (QAP) provides the quality assurance requirements and processes that support the NRC BFQ. This QAP is designed to be used by project staff, and prescribes the required management control elements that are to be met and how they are implemented. Additional controls are captured in Fuel Thermo-Physical Characterization Project plans, existing procedures, and procedures to be developed that provide supplemental information on how work is conducted on the project.

Pereira, Mario M.; Slonecker, Bruce D.

2012-06-01T23:59:59.000Z

Note: This page contains sample records for the topic "improvement project plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


341

Implementation of UMTRA Project Environmental Audit Action Plan status report for period ending September 30, 1992  

SciTech Connect (OSTI)

This report provides the status of implementation of corrective actions for findings made in an Environmental Audit conducted by DOE Headquarters, Office of Environmental Audit, in June 1991. An Action Plan, dated December 1991, was developed to address the findings. The Action Plan was approved by DOE Headquarters, Office of Environment, Safety and Health, in July 1992. This report provides status for each activity listed in the approved Action Plan. Of 48 findings identified in the August 1991 Environmental Audit Report, 4 required no action, 5 were combined with others and actions to correct 19 are complete. Although it appears no progress has been made since the last status report was issued, UMTRA has completed 89% of the findings identified, compared to 72% identified in the last status report. The table below lists the 20 findings where actions are still underway, the current projected completion date, the organization(s) responsible for taking action on the finding, and the UMTRA Project Off ice staff member assigned responsibility for the finding.

Not Available

1992-09-01T23:59:59.000Z

342

Supplement to the UMTRA Project water sampling and analysis plan, Mexican Hat, Utah  

SciTech Connect (OSTI)

This water sampling and analysis plan (WSAP) supplement supports the regulatory and technical basis for water sampling at the Mexican Hat, Utah, Uranium Mill Tailings Remedial Action (UMTRA) Project site, as defined in the 1994 WSAP document for Mexican Hat (DOE, 1994). Further, the supplement serves to confirm our present understanding of the site relative to the hydrogeology and contaminant distribution as well as our intention to continue to use the sampling strategy as presented in the 1994 WSAP document for Mexican Hat. Ground water and surface water monitoring activities are derived from the US Environmental Protection Agency regulations in 40 CFR Part 192 (1991) and 60 FR 2854 (1995). Sampling procedures are guided by the UMTRA Project standard operating procedures (JEG, n.d.), the Technical Approach Document (DOE, 1989), and the most effective technical approach for the site. Additional site-specific documents relevant to the Mexican Hat site are the Mexican Hat Long-Term Surveillance Plan (currently in progress), and the Mexican Hat Site Observational Work Plan (currently in progress).

NONE

1995-09-01T23:59:59.000Z

343

Test Plan: Sludge Treatment Project Corrosion Process Chemistry Follow-on Testing  

SciTech Connect (OSTI)

This test plan was prepared by the Pacific Northwest National Laboratory (PNNL) under contract with Fluor Hanford (FH). The test plan describes the scope and conditions to be used to perform laboratory-scale testing of the Sludge Treatment Project (STP) hydrothermal treatment of K Basin sludge. The STP, managed for the U. S. Department of Energy (DOE) by FH, was created to design and operate a process to eliminate uranium metal from the sludge prior to packaging for Waste Isolation Pilot Plant (WIPP) by using high temperature liquid water to accelerate the reaction, produce uranium dioxide from the uranium metal, and safely discharge the hydrogen. The proposed testing builds on the approach and laboratory test findings for both K Basin sludge and simulated sludge garnered during prior testing from September 2006 to March 2007. The outlined testing in this plan is designed to yield further understanding of the nature of the chemical reactions, the effects of compositional and process variations and the effectiveness of various strategies to mitigate the observed high shear strength phenomenon observed during the prior testing. These tests are designed to provide process validation and refinement vs. process development and design input. The expected outcome is to establish a level of understanding of the chemistry such that successful operating strategies and parameters can be implemented within the confines of the existing STP corrosion vessel design. In July 2007, the DOE provided direction to FH regarding significant changes to the scope of the overall STP. As a result of the changes, FH directed PNNL to stop work on most of the planned activities covered in this test plan. Therefore, it is unlikely the testing described here will be performed. However, to preserve the test strategy and details developed to date, the test plan has been published.

Delegard, Calvin H.; Schmidt, Andrew J.; Poloski, Adam P.

2007-08-17T23:59:59.000Z

344

DECHEM: A remedial planning tool for metallic contaminants in soil at UMTRA Project sites  

SciTech Connect (OSTI)

The DECHEM (DEcontamination of CHEMicals) method was developed for the Uranium Mill Tailings Remedial Action (UMTRA) Project to guide characterization and remedial planning for metals contamination in soils. This is necessary because non-radiological hazardous constituents may be more mobile than radium-226 (Ra-226), and hence may migrate more deeply into subpile soils (beneath tailings that are to be relocated) or into adjacent contaminated soils at UMTRA Project sites. The result is that remedial action to the Ra-226 excavation limit, as specified in the US Environmental Protection Agency (EPA) standards, may not adequately remove hazardous non-radiological contamination. Unmitigated, these contaminants in soil may cause health risks because of their presence in resuspended particles, their uptake by crops or fodder their seepage into aquifers used for drinking water or other possible exposure pathways. The DECHEM method was developed in response to the need for advanced planning for the remediation of chemical contaminants at UMTRA Project sites, and includes the following elements: Establishment of acceptable exposure rates for humans to chemicals, based on EPA guidelines or other toxicological literature. Modeling of chemical migration through environmental pathways from a remediated UMTRA Project site to humans. Determination of allowable residual concentrations (i.e., cleanup guidelines) for chemicals in soils that results in doses to humans that are below established acceptable exposure rates. The initial development and application of the DECHEM method has focused upon hazardous metallic contaminants such as arsenic, lead, molybdenum, and selenium, which are known to occur in elevated concentrations at some UMTRA Project sites.

Not Available

1989-03-01T23:59:59.000Z

345

Yakima/Klickitat Fisheries Project; Washington Department of Fish and Wildlife Policy/Technical Involvement and Planning, 2001-2002 Annual Report.  

SciTech Connect (OSTI)

The Yakima/Klickitat Fisheries Project (YKFP) is a supplementation project sponsored by the Northwest Power Planning Council (Columbia River Basin Fish and Wildlife Program 1994, Measure 7.4K). The objectives of the YKFP are: (1) to test the hypothesis that new supplementation techniques can be used in the Yakima River Basin to increase natural production and to improve harvest opportunities while maintaining the long-term genetic fitness of the wild and native salmonid populations and keeping adverse ecological interactions within acceptable limits (Yakima Fisheries Project Final Environment Impact Statement, 1996); (2) provide knowledge about the use of supplementation, so that it may be used to mitigate effects on anadromous fisheries throughout the Columbia River Basin; (3) to maintain and improve the quantity and productivity of salmon and steelhead habitat, including those areas made accessible by habitat improvements; (4) to ensure that Project implementation remains consistent with the Council's Fish and Wildlife Program; and (5) to implement the Project in a prudent and environmentally sound manner. Current YKFP operations have been designed to test the principles of supplementation (Busack et al. 1997). The Project's experimental design has focused on the following critical uncertainties affecting supplementation: (1) The survival and reproductive success of hatchery fish after release from the hatchery; (2) The impacts of hatchery fish as they interact with non-target species and stocks; and, (3) The effects of supplementation on the long-term genetic fitness of fish stocks. The YKFP endorses an adaptive management policy applied through a project management framework as described in the Yakima/Klickitat Fisheries Project Planning Status Report (1995), Fast and Craig (1997), Clune and Dauble 1991. The project is managed by a Policy Group consisting of a representative of the Yakama Nation (YN, lead agency) and a representative of the Washington Department of Fish and Wildlife (WDFW). The functions of the parties are described in an MOU between the YN and the WDFW. A Scientific and Technical Advisory Committee (STAC) consisting of one representative from each management entity reports to the Policy Group and provides technical input on policy and other issues. Additional committee's, such as the Monitoring Implementation and Planning Team (MIPT), serve as the discretion of STAC. The Policy Group and STAC meet periodically (usually monthly) to conduct the business of the YKFP. Although the YKFP is an all stocks initiative (BPA 1996), most effort to date has been directed at spring chinook salmon and coho salmon. This report is a compilation of the year's activities between August 1, 2001 and July 31, 2002. All findings should be considered preliminary until data collection is completed or the information is published in a peer-reviewed journal.

Easterbrooks, John A.; Pearsons, Todd N. (Washington Department of Fish and Wildlife, Olympia, WA)

2003-03-01T23:59:59.000Z

346

Site observational work plan for the UMTRA Project site at Falls City, Texas  

SciTech Connect (OSTI)

Produced by the US Department of Energy (DOE), this site observational work plan (SOWP) will be used to determine site-specific activities to comply with the US Environmental Protection Agency (EPA) ground water standards at this Uranium Mill Tailings Remedial Action (UMTRA) Project site. The purpose of the SOWP is to recommend a site-specific ground water compliance strategy at the Falls City UMTRA Project site. The Falls City SOWP presents a comprehensive summary of site hydrogeological data, delineates a conceptual model of the aquifer system, and discusses the origins of milling-related ground water contamination. It also defines the magnitude of ground water contamination, potential environmental and health risks associated with ground water contamination and data gaps, and targets a proposed compliance strategy.

NONE

1995-06-01T23:59:59.000Z

347

Getting the most D and D ''know how'' before starting to plan your decommissioning project.  

SciTech Connect (OSTI)

Over the last 20 years, the Decommissioning Program of the ANL-East Site has successfully decommissioned numerous facilities including: three research reactors (a 100 MW BWR, a smaller 250 kW biological irradiation reactor and a 10 kW research reactor), a critical assembly, a suite of 61 plutonium gloveboxes in 9 laboratories, a fuels fabrication facility and several non-reactor (waste management and operations) facilities. In addition, extensive decontamination work was performed on 5 hot cells formerly used in a joint ANL/US Navy R&D program. Currently the D&D of the CP-5 research reactor is underway as is planning for several other future D&D projects. The CP-5 facility was also used as a test bed for the evaluation of select evolving D&D technologies to ascertain their value for use in future D&D projects.

Boing, L. E.

1999-06-23T23:59:59.000Z

348

Site Observational Work Plan for the UMTRA project site at Ambrosia Lake, New Mexico  

SciTech Connect (OSTI)

Ground water compliance for the Uranium Mill Tailings Remedial Action (UMTRA) Project sites, including the Ambrosia Lake, New Mexico, site, is governed by the Uranium Mills Tailings Radiation Control Act (42 USC {section}7901 et seq.) and the U.S. Environmental Protection Agency`s Health and Environmental Protection Standards for Uranium and Thorium Mill Tailings (40 CFR Part 192; 60 FR 2854). The EPA standards describe specific conditions for which the U.S. Department of Energy (DOE) may apply for supplemental standards for contaminated ground water rather than meeting background levels or numerical standards. To achieve compliance with Subpart A of the EPA standards the residual radioactive materials are currently being consolidated on the site by the DOE in a disposal cell, isolating them from direct human or ecological contact and further dispersion into the environment. Completion of the disposal cell is scheduled for early 1995. An environmental assessment and a Finding of No Significant Impact (FONSI) were completed in 1987. Concurrence with the UMTRA Surface Project Ambrosia Lake remedial action plan (RAP) was granted by the U.S. Nuclear Regulatory Commission (NRC) and state of New Mexico in 1990. The DOE deferred compliance with Subpart B of the EPA standards in the Surface Project RAP. This site observational work plan (SOWP) is the first document to address ground water compliance under Subpart B at the Ambrosia Lake site. The Ambrosia Lake UMTRA Project site is within the Grants Mineral Belt and was one of numerous uranium mills supplied by many local mines. Ground water contamination at the site occurred as a result of uranium mill operations. Contamination of ground water resulted from discharge of waste water, infiltration of water through the tailings pile, hydraulic placement of mill tailings in nearby mines, and water pumped from mine shafts.

NONE

1995-02-01T23:59:59.000Z

349

Maintenance and operations contractor plan for transition to the project Hanford management contract (PHMC)  

SciTech Connect (OSTI)

This plan has been developed by Westinghouse Hanford Company (WHC), and its subcontractors ICF Kaiser Hanford (ICF KH) and BCS Richland, Inc. (BCSR), at the direction of the US Department of Energy (DOE), Richland Operations Office (RL). WHC and its subcontractors are hereafter referred to as the Maintenance and Operations (M and O) Contractor. The plan identifies actions involving the M and O Contractor that are critical to (1) prepare for a smooth transition to the Project Hanford Management Contractor (PHMC), and (2) support and assist the PHMC and RL in achieving transition as planned, with no or minimal impact to ongoing baseline activities. The plan is structured around two primary phases. The first is the pre-award phase, which started in mid-February 1996 and is currently scheduled to be completed on June 1, 1996, at which time the contract is currently planned to be awarded. The second is the follow-on four-month post-award phase from June 1, 1996, until October 1, 1996. Considering the magnitude and complexity of the scope of work being transitioned, completion in four months will require significant effort by all parties. To better ensure success, the M and O Contractor has developed a pre-award phase that is intended to maximize readiness for transition. Priority is given to preparation for facility assessments and processing of personnel, as these areas are determined to be on the critical path for transition. In addition, the M and O Contractor will put emphasis during the pre-award phase to close out open items prior to contract award, to include grievances, employee concerns, audit findings, compliance issues, etc.

Waite, J.L.

1996-04-12T23:59:59.000Z

350

Light oil yield improvement project at Granite City Division Coke/By-Product Plant  

SciTech Connect (OSTI)

Light oil removal from coke oven gas is a process that has long been proven and utilized throughout many North American Coke/By-Products Plants. The procedures, processes, and equipment requirements to maximize light oil recovery at the Granite City By-Products Plant will be discussed. The Light Oil Yield Improvement Project initially began in July, 1993 and was well into the final phase by February, 1994. Problem solving techniques, along with utilizing proven theoretical recovery standards were applied in this project. Process equipment improvements and implementation of Operator/Maintenance Standard Practices resulted in an average yield increase of 0.4 Gals./NTDC by the end of 1993.

Holloran, R.A. [National Steel Corp., Granite City, IL (United States). Granite City Div.

1995-12-01T23:59:59.000Z

351

Integrated Task Plans for the Hanford Environmental Dose Reconstruction Project, FY 1992 through May 1994  

SciTech Connect (OSTI)

The purpose of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate radiation doses from Hanford Site operations since 1944 to populations and individuals. The primary objective of work to be performed through May 1994 is to (1) determine the project's appropriate scope (space, time, radionuclides, pathways and individuals/population groups), (2) determine the project's appropriate level of accuracy (level of uncertainty in dose estimates) for the project, (3) complete model and data development, and (4) estimate doses for the Hanford Thyroid Disease Study (HTDS), representative individuals, and special populations as described herein. The plan for FY 1992 through May 1994 has been prepared based on activities and budgets approved by the Technical Steering Panel (TSP) at its meetings on August 19--20, 1991, and April 23--25, 1992. The activities can be divided into four broad categories: (1) model and data evaluation activities, (2)additional dose estimates, (3) model and data development activities, and (4)technical and communication support.

Shipler, D.B.

1992-09-01T23:59:59.000Z

352

Supplement to the UMTRA Project water sampling and analysis plan, Maybell, Colorado  

SciTech Connect (OSTI)

This water sampling and analysis plan (WSAP) supplement supports the regulatory and technical basis for water sampling at the Maybell, Colorado, Uranium Mill Tailings Remedial Action (UMTRA) Project site, as defined in the 1994 WSAP document for Maybell (DOE, 1994a). Further, this supplement serves to confirm our present understanding of the site relative to the hydrogeology and contaminant distribution as well as our intention to continue to use the sampling strategy as presented in the 1994 WSAP document for Maybell. Ground water and surface water monitoring activities are derived from the US Environmental Protection Agency regulations in 40 CFR Part 192 (1994) and 60 CFR 2854 (1 995). Sampling procedures are guided by the UMTRA Project standard operating procedures (JEG, n.d.), the Technical Approach Document (DOE, 1989), and the most effective technical approach for the site. Additional site-specific documents relevant to the Maybell site are the Maybell Baseline Risk Assessment (currently in progress), the Maybell Remedial Action Plan (RAP) (DOE, 1994b), and the Maybell Environmental Assessment (DOE, 1995).

NONE

1995-09-01T23:59:59.000Z

353

We have only listed Oklahoma Hatcheries as they appear in the National Poultry Improvement Plan. For a listing of hatcheries in your state, contact your state USDA  

E-Print Network [OSTI]

We have only listed Oklahoma Hatcheries as they appear in the National Poultry Improvement Plan-55-040 National Poultry Improvement Plan. A hatchery appearing on this list in no way constitutes endorsement

Balasundaram, Balabhaskar "Baski"

354

The Woodlands Metro Center energy study. Case studies of project planning and design for energy conservation  

SciTech Connect (OSTI)

The Woodlands is a HUD Title VII New Town located near Houston, including 22,000 acres; the plan for the new town consists of 6 residential villages, a town center (Metro), and a Trade Center for larger-scale industrial use. Included within the program for each village are schools and commercial activities, as well as employment activities. The Woodlands is planned to be developed over a 26-year period (commenced in 1972) with an ultimate population of 150,000. Following a summary chapter, Chapter II presents background material on The Woodlands and results of the study are summarized. Chapter III describes the project team and its organizational structure. Chapter IV outlines and documents the methodology that was employed in developing, analyzing, and evaluating the case study. The next chapter describes and analyzes the conventional plan, documents the process by which energy-conserving methods were selected, and evaluates the application of these methods to the Metro Center Study area. Chapter VI discusses constraints to implementation and is followed by a final chapter that presents the general conclusions from the case study and suggests directions for further investigation.

Not Available

1980-03-01T23:59:59.000Z

355

Sandia National Laboratories, California Quality Assurance Project Plan for Environmental Monitoring Program.  

SciTech Connect (OSTI)

This Quality Assurance Project Plan (QAPP) applies to the Environmental Monitoring Program at the Sandia National Laboratories/California. This QAPP follows DOE Quality Assurance Management System Guide for Use with 10 CFR 830 Subpart A, Quality Assurance Requirements, and DOE O 414.1C, Quality Assurance (DOE G 414.1-2A June 17, 2005). The Environmental Monitoring Program is located within the Environmental Operations Department. The Environmental Operations Department is responsible for ensuring that SNL/CA operations have minimal impact on the environment. The Department provides guidance to line organizations to help them comply with applicable environmental regulations and DOE orders. To fulfill its mission, the department has groups responsible for waste management; pollution prevention, air quality; environmental planning; hazardous materials management; and environmental monitoring. The Environmental Monitoring Program is responsible for ensuring that SNL/CA complies with all Federal, State, and local regulations and with DOE orders regarding the quality of wastewater and stormwater discharges. The Program monitors these discharges both visually and through effluent sampling. The Program ensures that activities at the SNL/CA site do not negatively impact the quality of surface waters in the vicinity, or those of the San Francisco Bay. The Program verifies that wastewater and stormwater discharges are in compliance with established standards and requirements. The Program is also responsible for compliance with groundwater monitoring, and underground and above ground storage tanks regulatory compliance. The Program prepares numerous reports, plans, permit applications, and other documents that demonstrate compliance.

Holland, Robert C.

2005-09-01T23:59:59.000Z

356

Steam Pressure-Reducing Station Safety and Energy Efficiency Improvement Project  

SciTech Connect (OSTI)

The Facilities and Operations (F&O) Directorate is sponsoring a continuous process improvement (CPI) program. Its purpose is to stimulate, promote, and sustain a culture of improvement throughout all levels of the organization. The CPI program ensures that a scientific and repeatable process exists for improving the delivery of F&O products and services in support of Oak Ridge National Laboratory (ORNL) Management Systems. Strategic objectives of the CPI program include achieving excellence in laboratory operations in the areas of safety, health, and the environment. Identifying and promoting opportunities for achieving the following critical outcomes are important business goals of the CPI program: improved safety performance; process focused on consumer needs; modern and secure campus; flexibility to respond to changing laboratory needs; bench strength for the future; and elimination of legacy issues. The Steam Pressure-Reducing Station (SPRS) Safety and Energy Efficiency Improvement Project, which is under the CPI program, focuses on maintaining and upgrading SPRSs that are part of the ORNL steam distribution network. This steam pipe network transports steam produced at the ORNL steam plant to many buildings in the main campus site. The SPRS Safety and Energy Efficiency Improvement Project promotes excellence in laboratory operations by (1) improving personnel safety, (2) decreasing fuel consumption through improved steam system energy efficiency, and (3) achieving compliance with applicable worker health and safety requirements. The SPRS Safety and Energy Efficiency Improvement Project being performed by F&O is helping ORNL improve both energy efficiency and worker safety by modifying, maintaining, and repairing SPRSs. Since work began in 2006, numerous energy-wasting steam leaks have been eliminated, heat losses from uninsulated steam pipe surfaces have been reduced, and deficient pressure retaining components have been replaced. These improvements helped ORNL reduce its overall utility costs by decreasing the amount of fuel used to generate steam. Reduced fuel consumption also decreased air emissions. These improvements also helped lower the risk of burn injuries to workers and helped prevent shrapnel injuries resulting from missiles produced by pressurized component failures. In most cases, the economic benefit and cost effectiveness of the SPRS Safety and Energy Efficiency Improvement Project is reflected in payback periods of 1 year or less.

Lower, Mark D [ORNL; Christopher, Timothy W [ORNL; Oland, C Barry [ORNL

2011-06-01T23:59:59.000Z

357

Development of a Pavement Maintenance and Rehabilitation Project Formation and Prioritization Methodology that Reflects Agency Priorities and Improves Network Condition  

E-Print Network [OSTI]

crucial step in pavement management is the formation and prioritization of maintenance and rehabilitation (M&R) projects that compete for limited funding for inclusion in the agency’s multiyear pavement management plan (PMPs). In general, many highway...

Narciso, Paul John Ross

2013-07-22T23:59:59.000Z

358

Stormwater Pollution Prevention Plan (SWPPP) for Coal Storage Area Stabilization Project  

SciTech Connect (OSTI)

The scope of this project is to stabilize the abandoned coal storage area and redirect the storm water runoff from sanitary sewer system to the storm drain system. Currently, the existing storm water runoff is directed to a perimeter concrete drainage swale and collected in a containment basin. The collected water is then pumped to a treatment facility and after treatment, is discharged to the Y-12 sanitary sewer system. The existing drainage swale and collection basin along with silt fencing will be used during aggregate placement and grading to provide erosion and sediment control. Inlet protection will also be installed around existing structures during the storm water diversion construction. This project scope will include the installation of a non-woven geotextile fabric and compacted mineral aggregate base (paving optional) to stabilize the site. The geotextile specifications are provided on the vendor cut sheets in Appendix B. The installation of a storm water collection/retention area will also be installed on the southern side of the site in accordance with EPA Technical Guidance on Implementing the Stormwater Runoff Requirements for federal Projects under Section 438 of the Energy Independence and Security Act. The total area to be disturbed is approximately 2.5 acres. The order of activities for this Stormwater Pollution Prevention Plan (SWPPP) will be: (1) post notice of coverage (NOC) in a prominent display near entrance of the site; (2) install rain gauge on site or contact Y-12 Plant Shift Superintendent daily for Met tower rain gauge readings; (3) install stabilized construction exit on site; (4) install silt fencing along perimeter as indicated on the attached site plan; (5) regrade site; (6) install geotextile fabric and compacted mineral aggregate base; (7) install catch basin inlet protection where required; (8) excavate and lower existing catch basin tops, re-grade and asphalt to drain; and (9) when all disturbed areas are re-stabilized, remove silt fencing and any other temporary erosion control.

Project and Design Engineering

2011-03-01T23:59:59.000Z

359

Phase 1 Characterization sampling and analysis plan West Valley demonstration project.  

SciTech Connect (OSTI)

The Phase 1 Characterization Sampling and Analysis Plan (CSAP) provides details about environmental data collection that will be taking place to support Phase 1 decommissioning activities described in the Phase 1 Decommissioning Plan for the West Valley Demonstration Project, Revision 2 (Phase I DP; DOE 2009). The four primary purposes of CSAP data collection are: (1) pre-design data collection, (2) remedial support, (3) post-remediation status documentation, and (4) Phase 2 decision-making support. Data collection to support these four main objectives is organized into two distinct data collection efforts. The first is data collection that will take place prior to the initiation of significant Phase 1 decommissioning activities (e.g., the Waste Management Area [WMA] 1 and WMA 2 excavations). The second is data collection that will occur during and immediately after environmental remediation in support of remediation activities. Both data collection efforts have a set of well-defined objectives that encompass the data needs of the four main CSAP data collection purposes detailed in the CSAP. The main body of the CSAP describes the overall data collection strategies that will be used to satisfy data collection objectives. The details of pre-remediation data collection are organized by WMA. The CSAP contains an appendix for each WMA that describes the details of WMA-specific pre-remediation data collection activities. The CSAP is intended to expand upon the data collection requirements identified in the Phase 1 Decommissioning Plan. The CSAP is intended to tightly integrate with the Phase 1 Final Status Survey Plan (FSSP). Data collection described by the CSAP is consistent with the FSSP where appropriate and to the extent possible.

Johnson, R. L. (Environmental Science Division)

2011-06-30T23:59:59.000Z

360

An Overview of Project Planning for Hot-Isostatic Pressure Treatment of High-Level Waste Calcine for the Idaho Cleanup Project - 12289  

SciTech Connect (OSTI)

The Calcine Disposition Project is responsible for retrieval, treatment by hot-isostatic pressure, packaging, and disposal of highly radioactive calcine stored at the Idaho Nuclear Technology and Engineering Center at the Idaho National Laboratory Site in southeast Idaho. In the 2009 Amended Record of Decision: Idaho High-Level Waste and Facilities Disposition Final Environmental Impact Statement the Department of Energy documented the selection of hot-isostatic pressure as the technology to treat the calcine. The Record of Decision specifies that the treatment results in a volume-reduced, monolithic waste form suitable for transport outside of Idaho by a target date of December 31, 2035. That target date is specified in the 1995 Idaho Settlement Agreement to treat and prepare the calcine for transport out of Idaho in exchange for allowing storage of Navy spent nuclear fuel at the INL Site. The project is completing the design of the calcine-treatment process and facility to comply with Record of Decision, Settlement Agreement, Idaho Department of Environmental Quality, and Department of Energy requirements. A systems engineering approach is being used to define the project mission and requirements, manage risks, and establish the safety basis for decision making in compliance with DOE O 413.3B, 'Program and Project Management for the Acquisition of Capital Assets'. The approach draws heavily on 'design-for-quality' tools to systematically add quality, predict design reliability, and manage variation in the earliest possible stages of design when it is most efficient. Use of these tools provides a standardized basis for interfacing systems to interact across system boundaries and promotes system integration on a facility-wide basis. A mass and energy model was developed to assist in the design of process equipment, determine material-flow parameters, and estimate process emissions. Data generated from failure modes and effects analysis and reliability, availability, maintainability, and inspectability analysis were incorporated into a time and motion model to validate and verify the capability to complete treatment of the calcine within the required schedule. The Calcine Disposition Project systems engineering approach, including use of industry-proven design-for-quality tools and quantitative assessment techniques, has strengthened the project's design capability to meet its intended mission in a safe, cost-effective, and timely manner. Use of these tools has been particularly helpful to the project in early design planning to manage variation; improve requirements and high-consequence risk management; and more effectively apply alternative, interface, failure mode, RAMI, and time and motion analyses at the earliest possible stages of design when their application is most efficient and cost effective. The project is using these tools to design and develop HIP treatment of highly radioactive calcine to produce a volume-reduced, monolithic waste form with immobilization of hazardous and radioactive constituents. (authors)

Nenni, Joseph A.; Thompson, Theron J. [CH2M-WG Idaho, LLC, Idaho Cleanup Project, Idaho Falls, Idaho 83403 (United States)

2012-07-01T23:59:59.000Z

Note: This page contains sample records for the topic "improvement project plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


361

Site observational work plan for the UMTRA Project Site at Grand Junction, Colorado  

SciTech Connect (OSTI)

The U.S. Department of Energy (DOE) has prepared this initial site observational work plan (SOWP) for the Uranium Mill Tailings Remedial Action (UMTRA) Project site in Grand Junction, Colorado. This SOWP is one of the first UMTRA Ground Water Project documents developed to select a compliance strategy that meets the UMTRA ground water standards (40 CFR Part 192, as amended by 60 FR 2854) for the Grand Junction site. This SOWP applies information about the Grand Junction site to the compliance strategy selection framework developed in the UMTRA Ground Water Project draft programmatic environmental impact statement (PEIS). This risk-based, decision-making framework identifies the decision logic for selecting compliance strategies that could be used to meet the ground water standards. The DOE goal is to use the observational method to implement a cost-effective site strategy that complies with the ground water standards and protects human health and the environment. Based on an evaluation of the site characterization and risk assessment data available for the preparation of this SOWP, DOE proposes that the most likely compliance strategy for the Grand Junction site is no remediation based on the application of supplemental standards. This proposed strategy is based on a conceptual site model that indicates site-related contamination is confined to a limited-use aquifer as defined in the ground water standards.

NONE

1996-03-01T23:59:59.000Z

362

Mitigation and monitoring plan for impacted wetlands at the Gunnison UMTRA Project site, Gunnison, Colorado. [Uranium Mill Tailings Remedial Action (UMTRA) Project  

SciTech Connect (OSTI)

The U.S Department of Energy (DOE) administers the Uranium Mill Tailings Remedial Action (UMTRA) Project. The UMTRA Project is the result of the Uranium Mill Tailings Radiation Control Act(UMTRA) which was passed in response to the public's concern over the potential public health hazards related to uranium mill tailings and associated contaminated material at abandoned or otherwise uncontrolled inactive processing sites throughout the United States. The Gunnison, Colorado abandoned uranium mill site is one of the sites slated for cleanup by the DOE under authority of UMTRA. The contaminated material at this site will be transported to a disposal site on US Bureau of Land Management (BLM) land east of Gunnison. Remedial action activities will temporarily disturb 0.8 acre and permanently eliminate 5.1 acres of wetlands. This report describes the proposed mitigation plan for the 5.9 acres of impacted wetlands. In conjunction with the mitigation of the permanently impacted wetlands through the enhancement of wetland and adjacent riparian areas, impacts to wildlife as a result of this project will also be mitigated. However, wildlife mitigation is not the focus of this document and is covered in relevant BLM permits for this project. This plan proposes the enhancement of a 3:1 ratio of impacted wetlands in accordance with US Environmental Protection Agency guidelines, plus the enhancement of riparian areas for wildlife mitigation. Included in this mitigation plan is a monitoring plan to ensure that the proposed measures are working and being maintained.

Not Available

1992-06-01T23:59:59.000Z

363

Estimated Entrainment of Dungeness Crab During Dredging For The Columbia River Channel Improvement Project  

SciTech Connect (OSTI)

The studies reported here focus on issues regarding the entrainment of Dungeness crab related to the proposed Columbia River Channel Improvement Project and provided direct measurements of crab entrainment rates at three locations (Desdomona Shoals, Upper Sands, and Miller Sands) from RM4 to RM24 during summer 2002. Entrainment rates for all age classes of crabs ranged from zero at Miller Sands to 0.224 crabs per cy at Desdemona Shoals in June 2002. The overall entrainment rate at Desdomona Shoals in September was 0.120 crabs per cy. A modified Dredge Impact Model (DIM) used the summer 2002 entrainment rates to project crab entrainment and adult equivalent loss and loss to the fishery for the Channel Improvement Project. To improve the projections, entrainment data from Flavel Bar is needed. The literature, analyses of salinity intrusion scenarios, and the summer 2002 site-specific data on entrainment and salinity all indicate that bottom salinity influences crab distribution and entrainment, especially at lower salinities. It is now clear from field measurements of entrainment rates and salinity during a period of low river flow (90-150 Kcfs) and high salinity intrusion that entrainment rates are zero where bottom salinity is less than 16 o/oo most of the time. Further, entrainment rates of 2+ and older crab fall with decreasing salinity in a clear and consistent manner. More elaboration of the crab distribution- salinity model, especially concerning salinity and the movements of 1+ crab, is needed.

Pearson, Walter H.; Williams, Greg D.; Skalski, John R.

2002-12-01T23:59:59.000Z

364

Front-end planning and evaluation for West Valley Demonstration Project completion  

SciTech Connect (OSTI)

In December 1988, the U.S. Department of Energy and the New York State Energy Research and Development Authority announced their intent to prepare a joint environmental impact statement (EIS) to evaluate alternatives for West Valley Demonstration Project (WVDP) completion and closure and/or long-term maintenance of the Western New York Nuclear Service Center (WNYNSC) in West Valley, New York. Planning was initiated for the eventual closure of the site, even though vitrification of the high-level waste (HLW) stored at the site was, at that time, a number of years in the future. West Valley Nuclear Services Company (WVNSC), the WVDP management and operations contractor, and their architect/engineer, Raytheon Nuclear Incorporated, were authorized to develop characterization studies and engineering evaluations of closure alternatives for the various facilities of the WNYNSC. This paper presents a summary of the status of that effort, including the resolution of unique problems.

Gramling, J.; Sharma, V. [West Valley Nuclear Services Company, West Valley, NY (United States); Marschke, S. [Raytheon Nuclear, Inc., New York, NY (United States)

1995-12-31T23:59:59.000Z

365

Quality Assurance Project Plan for radioactive airborne emissions data compilation and reporting  

SciTech Connect (OSTI)

This Quality Assurance Project Plan addresses the quality assurance requirements for compiling data from radioactie aiborne emissions. These data will be reported to the US Environmental Protection Agency, the US Department of Energy, and the Washington State Department of Health. Hanford Site radioactive airborne emissions are reported to the US Environmental Protection Agency in compliance with Title 40, Protection of the Environment, Code of Federal Regulations, Part 61, ``National Emissions Standards for Hazardous Air Pollutants , ``Subpart H, ``National Emissions Standards for Emissions of Radionuclides Other Than Radon From Department of Energy Facilities`` (EPA 1989a). Reporting to US Department of Energy is performed in compliance with requirements of US Department of Energy Order 5400.1, General Environmental Protection Program (DOE 1988a).

Burris, S.A.; Thomas, S.P.

1994-02-01T23:59:59.000Z

366

Site observational work plan for the UMTRA Project site at Monument Valley, Arizona  

SciTech Connect (OSTI)

The site observational work plan (SOWP) for the Monument Valley, Arizona, US Department of Energy (DOE) Uranium Mill Tailings Remedial Action(UMTRA) Project site is one of the first site-specific documents developed to achieve ground water compliance at the site. This SOWP applies information about the Monument Valley site to a regulatory compliance framework that identifies strategies that could be used to meet ground water compliance. The compliance framework was developed in the UMTRA Ground Water programmatic environmental impact statement (DOE, 1996). The DOE`s goal is to implement a cost-effective site strategy that complies with the US Environmental Protection Agency (EPA) ground water standards and protects human health and the environment. The compliance strategy that emerges in the final version of the SOWP will be evaluated in the site-specific environmental assessment to determine potential environmental impacts and provide stakeholders a forum for review and comment. When the compliance strategy is acceptable, it will be detailed in a remedial action plan that will be subject to review by the state and/or tribe and concurrence by the US Nuclear Regulatory Commission (NRC). Information for the preparation of this SOWP indicates active remediation is the most likely compliance strategy for the Monument Valley site. Additional data are needed to determine the most effective remediation technology.

NONE

1996-03-01T23:59:59.000Z

367

Site observational work plan for the UMTRA Project site at Monument Valley, Arizona  

SciTech Connect (OSTI)

The site observational work plan (SOWP) for the Monument Valley, Arizona, US Department of Energy (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project site is one of the first site-specific documents developed to achieve ground water compliance at the site. This SOWP applies information about the Monument Valley site to a regulatory compliance framework that identifies strategies that could be used to meet ground water compliance. The compliance framework was developed in the UMTRA Ground Water programmatic environmental impact statement (DOE, 1995). The DOE`s goal is to implement a cost-effective site strategy that complies with the US Environmental Protection Agency (EPA) ground water standards and protects human health and the environment. The compliance strategy that emerges in the final version of the SOWP will assess potential environmental impacts and provide stakeholder a forum for review and comment. When the compliance strategy is acceptable, it will be detailed in a remedial action plan that will be subject to review by the state and/or tribe and concurrence by the US Nuclear Regulatory Commission (NRC). Information available for the preparation of this SOWP indicates active remediation is the most likely compliance strategy for the Monument Valley site. Additional data are needed to determine the most effective remediation technology.

NONE

1995-09-01T23:59:59.000Z

368

Asian Tracer Experiment and Atmospheric Modeling (TEAM) Project: Draft Field Work Plan for the Asian Long-Range Tracer Experiment  

SciTech Connect (OSTI)

This report provides an experimental plan for a proposed Asian long-range tracer study as part of the international Tracer Experiment and Atmospheric Modeling (TEAM) Project. The TEAM partners are China, Japan, South Korea and the United States. Optimal times of year to conduct the study, meteorological measurements needed, proposed tracer release locations, proposed tracer sampling locations and the proposed durations of tracer releases and subsequent sampling are given. Also given are the activities necessary to prepare for the study and the schedule for completing the preparation activities leading to conducting the actual field operations. This report is intended to provide the TEAM members with the information necessary for planning and conducting the Asian long-range tracer study. The experimental plan is proposed, at this time, to describe the efforts necessary to conduct the Asian long-range tracer study, and the plan will undoubtedly be revised and refined as the planning goes forward over the next year.

Allwine, K Jerry; Flaherty, Julia E.

2007-08-01T23:59:59.000Z

369

Project Management Plan for the Idaho National Engineering Laboratory Waste Isolation Pilot Plant Experimental Test Program  

SciTech Connect (OSTI)

EG&G Idaho, Inc. and Argonne National Laboratory-West (ANL-W) are participating in the Idaho National Engineering Laboratory`s (INEL`s) Waste Isolation Pilot Plant (WIPP) Experimental Test Program (WETP). The purpose of the INEL WET is to provide chemical, physical, and radiochemical data on transuranic (TRU) waste to be stored at WIPP. The waste characterization data collected will be used to support the WIPP Performance Assessment (PA), development of the disposal No-Migration Variance Petition (NMVP), and to support the WIPP disposal decision. The PA is an analysis required by the Code of Federal Regulations (CFR), Title 40, Part 191 (40 CFR 191), which identifies the processes and events that may affect the disposal system (WIPP) and examines the effects of those processes and events on the performance of WIPP. A NMVP is required for the WIPP by 40 CFR 268 in order to dispose of land disposal restriction (LDR) mixed TRU waste in WIPP. It is anticipated that the detailed Resource Conservation and Recovery Act (RCRA) waste characterization data of all INEL retrievably-stored TRU waste to be stored in WIPP will be required for the NMVP. Waste characterization requirements for PA and RCRA may not necessarily be identical. Waste characterization requirements for the PA will be defined by Sandia National Laboratories. The requirements for RCRA are defined in 40 CFR 268, WIPP RCRA Part B Application Waste Analysis Plan (WAP), and WIPP Waste Characterization Program Plan (WWCP). This Project Management Plan (PMP) addresses only the characterization of the contact handled (CH) TRU waste at the INEL. This document will address all work in which EG&G Idaho is responsible concerning the INEL WETP. Even though EG&G Idaho has no responsibility for the work that ANL-W is performing, EG&G Idaho will keep a current status and provide a project coordination effort with ANL-W to ensure that the INEL, as a whole, is effectively and efficiently completing the requirements for WETP.

Connolly, M.J.; Sayer, D.L.

1993-11-01T23:59:59.000Z

370

Supplement to the UMTRA project water sampling and analysis plan, Slick Rock, Colorado  

SciTech Connect (OSTI)

The water sampling and analysis plan (WSAP) provides the regulatory and technical basis for ground water and surface water sampling at the Uranium Mill Tailings Remedial Action (UMTRA) Project Union Carbide (UC) and North Continent (NC) processing sites and the Burro Canyon disposal site near Slick Rock, Colorado. The initial WSAP was finalized in August 1994 and will be completely revised in accordance with the WSAP guidance document (DOE, 1995) in late 1996. This version supplements the initial WSAP, reflects only minor changes in sampling that occurred in 1995, covers sampling scheduled for early 1996, and provides a preliminary projection of the next 5 years of sampling and monitoring activities. Once surface remedial action is completed at the former processing sites, additional and more detailed hydrogeologic characterization may be needed to develop the Ground Water Program conceptual ground water model and proposed compliance strategy. In addition, background ground water quality needs to be clearly defined to ensure that the baseline risk assessment accurately estimated risks from the contaminants of potential concern in contaminated ground water at the UC and NC sites.

NONE

1995-09-01T23:59:59.000Z

371

Site observational work plan for the UMTRA Project site at Spook, Wyoming  

SciTech Connect (OSTI)

The Spook, Wyoming, site observational work plan proposes site-specific activities to achieve compliance with Subpart B of 40 CFR Part 192 (1994) of the final US Environmental Protection Agency (EPA) ground water protection standards 60 FR 2854 (1995) at this Uranium Mill Tailing Remedial Action (UMTRA) Project site. This draft SOWP presents a comprehensive summary of existing site characterization data, a conceptual site model of the nature and extent of ground water contamination, exposure pathways, and potential impact to human health and the environment. Section 2.0 describes the requirements for meeting ground water standards at UMTRA Project sites. Section 3.0 defines past and current conditions, describes potential environmental and human health risks, and provides site-specific data that supports the selection of a proposed ground water compliance strategy. Section 4.0 provides the justification for selecting the proposed ground water compliance strategy based on the framework defined in the ground water programmatic environmental impact statement (PEIS).

NONE

1995-05-01T23:59:59.000Z

372

Site observational work plan for the UMTRA project site at Grand Junction, Colorado  

SciTech Connect (OSTI)

This site observational work plan (SOWP) is one of the first Uranium Mill Tailings Remedial Action (UMTRA) Ground Water Project documents developed to select a compliance strategy that meets the UMTRA ground water standards for the Grand Junction site. This SOWP applies information about the Grand Junction site to the compliance strategy selection framework developed in the UMTRA Ground Water Project draft programmatic environmental impact statement. This risk-based, decision-making framework identifies the decision logic for selecting compliance strategies that could be used to meet the ground water standards. The US Department of Energy (DOE) goal is to implement a cost-effective site strategy that complies with the ground water standards and protects human health and the environment. Based on an evaluation of the site characterization and risk assessment data available for the preparation of this SOWP, DOE proposes that the most likely compliance strategy for the Grand Junction site is no remediation with the application of supplemental standards. This proposed strategy is based on a conceptual site model that indicates site-related contamination is confined to a limited-use aquifer as defined in the ground water standards. The conceptual model demonstrates that the uranium processing-related contamination at the site has affected the unconfined alluvial aquifer, but not the deeper confined aquifer.

NONE

1996-01-01T23:59:59.000Z

373

Planning and Implementation of an Alkali-Surfactant-Polymer (ASP) Field Project  

SciTech Connect (OSTI)

The Warden ASP project has progressed from the initial planning stage to construction of an injection plant. An ASP chemical system was designed based on laboratory evaluations that included interfacial tension, mobility requirements, rock-alkali interaction, fluid capabilities, and core tests. Field cores were obtained from the Permian No. 5 and No. 6 sands on the Warden lease in Sho-Vel-Tum oil field. A separate tank battery for the pilot pattern area was installed, and a field tracer test is currently being evaluated. Tracer test results to date indicate that there is no major fracturing in the No. 5 sand. There is indication, however, of some channeling through high permeability sand. The field injection plant was designed, and construction is in progress. Several variations of injection plant design have been evaluated. Some plant design details, such as alkali storage, were found to be dependent on the availability of use equipment and project budget. The surfactant storage facility design was shown to be dependent on surfactant rheology.

French, T.

1999-03-05T23:59:59.000Z

374

assessment palisades project: Topics by E-print Network  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

planning initiatives to improve the information base and facilitate integrative marine resource management1 PROJECT BRIEF SPATIAL ASSESSMENT OF COASTAL SPORT FISHERIES...

375

Site observational work plan for the UMTRA Project site at Riverton, Wyoming  

SciTech Connect (OSTI)

The site observational work plan (SOWP) for the Riverton, Wyoming, Uranium Mill Tailings Remedial Action (UMTRA) Project Site is the first document for the UMTRA Ground Water Project to address site-specific activities to meet compliance with the U.S. Environmental Protection Agency (EPA) proposed ground water standards (52 FR 36000 (1987)). In support of the activities the regulatory framework and drivers are presented along with a discussion of the relationship of this SOWP to other UMTRA Ground Water Project programmatic documents. A combination of the two compliance strategies that will be recommended for this site are no remediation with the application of alternate concentration levels (ACL) and natural flushing in conjunction with institutional controls. ACLs are to be applied to constituents that occur at concentrations above background levels but which are essential nutrients and occur within nutritional ranges and/or have very low toxicity and high dietary intake rates compared to the levels detected in the ground water. The essential premise of natural flushing is that ground water movement and natural attenuation processes will reduce the detected contamination to background levels within 1 00 years. These two recommended compliance strategies were evaluated by applying Riverton site-specific data to the compliance framework developed in the UMTRA Ground Water programmatic environmental impact statement. There are three aquifers beneath the site: a surficial unconfined aquifer, a middle semiconfined aquifer, and a deeper confined aquifer. The milling-related contamination at the site has affected both the surficial and semiconfined aquifers, although the leaky shale aquifers separating these units limits the downward migration of contamination into the semiconfined aquifer. A shale aquitard separates the semiconfined aquifer from the underlying confined aquifer which has not been contaminated by milling-related constituents.

Not Available

1994-09-01T23:59:59.000Z

376

Site observational work plan for the UMTRA project site at Shiprock, New Mexico  

SciTech Connect (OSTI)

The site observational work plan (SOWP) for the Shiprock, New Mexico, Uranium Mill Tailings Remedial Action (UMTRA) Project Site is the initial document for developing site-specific activities to achieve regulatory compliance in the UMTRA Ground Water Project. The regulatory framework used to select the proposed ground water compliance strategies is presented along with a discussion of the relationship of this SOWP to other UMTRA Ground Water Project programmatic documents. The Shiprock site consists of two, interconnected hydrogeologic systems: the terrace system and the floodplain system. Separate compliance strategies are proposed for these two systems. The compliance strategy for the terrace aquifer is no remediation with the application of supplemental standards based on classification of the terrace aquifer as having Class III (limited-use) ground water. The compliance strategy for the floodplain aquifer is active remediation using a subsurface biological barrier. These strategies were selected by applying site-specific data to the compliance framework developed in the UMTRA Ground Water programmatic environmental impact statement (PEIS) (DOE, 1994a). The site conceptual model indicates that milling-related contamination has impacted the ground water in the terrace and floodplain aquifers. Ground water occurs in both aquifers in alluvium and in fractures in the underlying Cretaceous age Mancos Shale. A mound of ground water related to fluids from the milling operations is thought to exist in the terrace aquifer below the area where settling ponds were in use during the mill operations. Most of the water occurring in the floodplain aquifer is from recharge from the San Juan River.

Not Available

1994-09-01T23:59:59.000Z

377

Recovery Efficiency Test Project: Phase 1, Activity report. Volume 1: Site selection, drill plan preparation, drilling, logging, and coring operations  

SciTech Connect (OSTI)

The recovery Efficiency Test well project addressed a number of technical issues. The primary objective was to determine the increased efficiency gas recovery of a long horizontal wellbore over that of a vertical wellbore and, more specifically, what improvements can be expected from inducing multiple hydraulic fractures from such a wellbore. BDM corporation located, planned, and drilled a long radius turn horizontal well in the Devonian shale Lower Huron section in Wayne County, West Virginia, demonstrating that state-of-the-art technology is capable of drilling such wells. BDM successfully tested drilling, coring, and logging in a horizontal well using air as the circulating medium; conducted reservoir modeling studies to protect flow rates and reserves in advance of drilling operations; observed two phase flow conditions in the wellbore not observed previously; cored a fracture zone which produced gas; observed that fractures in the core and the wellbore were not systematically spaced (varied from 5 to 68 feet in different parts of the wellbore); observed that highest gas show rates reported by the mud logger corresponded to zone with lowest fracture spacing (five feet) or high fracture frequency. Four and one-half inch casting was successfully installed in the borehole and was equipped to isolate the horizontal section into eight (8) zones for future testing and stimulation operations. 6 refs., 48 figs., 10 tabs.

Overbey, W.K. Jr.; Carden, R.S.; Kirr, J.N.

1987-04-01T23:59:59.000Z

378

Proposed IMS infrastructure improvement project, Seward, Alaska. Final environmental impact statement  

SciTech Connect (OSTI)

This Environmental Impact Statement (EIS) examines a proposal for improvements at the existing University of Alaska, Fairbanks, Institute of Marine Science (IMS), Seward Marine Center. The Exxon Valdez Oil Spill (EVOS) Trustee Council is proposing to improve the existing research infrastructure to enhance the EVOS Trustee Council`s capabilities to study and rehabilitate marine mammals, marine birds, and the ecosystem injured by the Exxon Valdez oil spill. The analysis in this document focuses on the effects associated with construction and operation of the proposed project and its proposed alternatives. The EIS gives a detailed description of all major elements of the proposed project and its alternatives; identifies resources of major concern that were raised during the scoping process; describes the environmental background conditions of those resources; defines and analyzes the potential effects of the proposed project and its alternatives on these conditions; and identifies mitigating measures that are part of the project design as well as those proposed to minimize or reduce the adverse effects. Included in the EIS are written and oral comments received during the public comment period.

Not Available

1994-09-01T23:59:59.000Z

379

Configuration Management Plan for Tank Farm Restoration and Safe Operations Project W-314 [CANCELLED  

SciTech Connect (OSTI)

The W-314 configuration management (CM) plan describes the systems, processes and procedures for implementing CM.

MCGREW, D.L.

2001-01-12T23:59:59.000Z

380

Spent nuclear fuel project multi-year work plan WBS {number_sign}1.4.1  

SciTech Connect (OSTI)

The Spent Nuclear Fuel (SNF) Project Multi-Year Work Plan (MYWP) is a controlled living document that contains the current SNF Project Technical, Schedule and Cost Baselines. These baselines reflect the current Project execution strategies and are controlled via the change control process. Other changes to the MYWP document will be controlled using the document control process. These changes will be processed as they are approved to keep the MYWP a living document. The MYWP will be maintained continuously as the project baseline through the life of the project and not revised annually. The MYWP is the one document which summarizes and links these three baselines in one place. Supporting documentation for each baseline referred to herein may be impacted by changes to the MYWP, and must also be revised through change control to maintain consistency.

Wells, J.L.

1997-03-01T23:59:59.000Z

Note: This page contains sample records for the topic "improvement project plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


381

U.S. to Participate in Fusion Project Thursday, January 30, 2003 http://www.nytimes.com/aponline/national/AP-Fusion-Energy-Plan.html?pagewanted=  

E-Print Network [OSTI]

States plan to build a $5 billion fusion reactor, called the International Thermonuclear ExperimentalU.S. to Participate in Fusion Project Thursday, January 30, 2003 http://www.nytimes.com/aponline/national/AP-Fusion-Energy-Plan.html?pagewanted= print&position=top Page: 1 January 30, 2003 U.S. to Participate in Fusion Project By THE ASSOCIATED

382

Quality assurance project plan for the Chestnut Ridge Fly Ash Pond Stabilization Project at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee  

SciTech Connect (OSTI)

The Chestnut Ridge Fly Ash Pond Stabilization (CRFAPS) Project will stabilize a 19-m-high (62-ft-high) earthen embankment across Upper McCoy Branch situated along the southern slope of Chestnut Ridge. This task will be accomplished by raising the crest of the embankment, reinforcing the face of the embankment, removing trees from the face and top of the embankment, and repairing the emergency spillway. The primary responsibilities of the team members are: Lockheed Martin Energy Systems, Inc., (Energy Systems) will be responsible for project integration, technical support, Title 3 field support, environmental oversight, and quality assurance (QA) oversight of the project; Foster Wheeler Environmental Corporation (FWENC) will be responsible for design and home office Title 3 support; MK-Ferguson of Oak Ridge Company (MK-F) will be responsible for health and safety, construction, and procurement of construction materials. Each of the team members has a QA program approved by the US Department of Energy (DOE) Oak Ridge Operations. This project-specific QA project plan (QAPP), which is applicable to all project activities, identifies and integrates the specific QA requirements from the participant`s QA programs that are necessary for this project.

NONE

1996-07-01T23:59:59.000Z

383

Strategic Planning  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

a single BPA data repository * Data quality improvements * Improve model alignment with WECC planning data * Improve WECC base case coordination * Align the BPA data model with...

384

Water-Level Monitoring Plan for the Hanford Groundwater Monitoring Project  

SciTech Connect (OSTI)

This document presents the water-level monitoring plan for the Hanford Groundwater Monitoring Project, conducted by the Pacific Northwest National Laboratory (PNNL). Water-level monitoring of the groundwater system beneath the Hanford Site is performed to fulfill the requirements of various state and federal regulations, orders, and agreements. The primary objective of this monitoring is to determine groundwater flow rates and directions. To meet this and other objectives, water-levels are measured annually in monitoring wells completed within the unconfined aquifer system, the upper basalt-confined aquifer system, and in the lower basalt-confined aquifers for surveillance monitoring. At regulated waste units, water levels are taken monthly, quarterly, semi-annually, or annually, depending on the hydrogeologic conditions and regulatory status of a given site. The techniques used to collect water-level data are described in this document along with the factors that affect the quality of the data and the strategies employed by the project to minimize error in the measurement and interpretation of water levels. Well networks are presented for monitoring the unconfined aquifer system, the upper basalt-confined aquifer system, and the lower basalt-confined aquifers, all at a regional scale (surveillance monitoring), as well as the local-scale well networks for each of the regulated waste units studied by this project (regulated-unit monitoring). The criteria used to select wells for water-table monitoring are discussed. It is observed that poor well coverage for surveillance water-table monitoring exists south and west of the 200-West Area, south of the 100-F Area, and east of B Pond and the Treated Effluent Disposal Facility (TEDF). This poor coverage results from a lack of wells suitable for water-table monitoring, and causes uncertainty in representation of the regional water-table in these areas. These deficiencies are regional in scale and apply to regions outside of the operational areas, so these deficiencies do not in anyway reflect on the adequacy of the local-scale well networks used for regulated-unit monitoring. The sediments comprising the unconfined aquifer system have been subdivided into nine hydro-geologic units. The specific hydrogeologic units present within the saturated open interval of each onsite well used for water-level measurements are identified. This was accomplished by geologic interpretation at individual wells combined with extrapolation to nearby wells using a three-dimensional, regional-scale conceptual model of the Hanford Site hydrostratigraphy.

D.R. Newcomer; J.P. McDonald; M.A. Chamness

1999-09-30T23:59:59.000Z

385

Yakima/Klickitat Fisheries Project; Washington Department of Fish and Wildlife Policy/Technical Involvement and Planning, 2002-2003 Annual Report.  

SciTech Connect (OSTI)

The Yakima/Klickitat Fisheries Project (YKFP) is a supplementation project sponsored by the Northwest Power Planning Council and funded by the Bonneville Power Administration. The YKFP has adopted the definition of supplementation described by Regional Assessment of Supplementation Program (1992), which is ''the use of artificial propagation in an attempt to maintain or increase natural production while maintaining the long-term fitness of the target population, and keeping the ecological and genetic impacts on nontarget populations within specified biological limits''. Recent scientific reviews of hatchery supplementation continue to highlight the experimental nature and risk of supplementation (Independent Scientific Group 1996; National Research Council 1996; Lichatowich 1999; Independent Multidisciplinary Science Team 2000; Independent Scientific Advisory Board 2003; Hatchery Scientific Review Group 2003). In addition, many of these reviews included recommendations about the best ways to operate a supplementation program. Most of these recommendations were already being done or have been incorporated into the YKFP. The objectives of the YKFP are: (1) to test the hypothesis that new supplementation techniques can be used in the Yakima River Basin to increase natural production and to improve harvest opportunities while maintaining the long-term genetic fitness of the wild and native salmonid populations and keeping adverse ecological interactions within acceptable limits (Yakima Fisheries Project Final Environment Impact Statement, 1996); (2) provide knowledge about the use of supplementation, so that it may be used to mitigate effects on anadromous fisheries throughout the Columbia River Basin; (3) to maintain and improve the quantity and productivity of salmon and steelhead habitat, including those areas made accessible by habitat improvements; (4) to ensure that Project implementation remains consistent with the Council's Fish and Wildlife Program; and (5) to implement the Project in a prudent and environmentally sound manner. Current YKFP operations have been designed to test the principles of supplementation (Busack et al. 1997). The Project's experimental design has focused on the following critical uncertainties affecting supplementation: (1) The survival and reproductive success of hatchery fish after release from the hatchery; (2) The impacts of hatchery fish as they interact with non-target species and stocks; and, (3) The effects of supplementation on the long-term genetic fitness of fish stocks. The YKFP endorses an adaptive management policy applied through a project management framework as described in the Yakima/Klickitat Fisheries Project Planning Status Report (1995), Fast and Craig (1997), and Clune and Dauble 1991. The project is managed by a Policy Group consisting of a representative of the Yakama Nation (YN, lead agency) and a representative of the Washington Department of Fish and Wildlife (WDFW). The functions of the parties are described in an MOU between the YN and the WDFW. A Scientific and Technical Advisory Committee (STAC) consisting of one representative from each management entity reports to the Policy Group and provides technical input on policy and other issues. Additional committee's, such as the Monitoring Implementation and Planning Team (MIPT), serve at the discretion of STAC. The Policy Group and STAC meet periodically (usually monthly) to conduct the business of the YKFP. Although the YKFP is an all stocks initiative (BPA 1996), most effort to date has been directed at spring chinook salmon and coho salmon. This report is a compilation of the year's activities between August 1, 2002 and July 31, 2003. The Yakama Nation's portion of the YKFP is presented in another report. All findings should be considered preliminary until data collection is completed or the information is published in a peer-reviewed journal. Pearsons and Easterbrooks (2003) described last year's activities.

Pearsons, Todd N.; Easterbrooks, John A. (Washington Department of Fish and Wildlife, Olympia, WA)

2003-09-01T23:59:59.000Z

386

Projections, politics, and practice in regional planning : a case study of MetroFuture  

E-Print Network [OSTI]

This thesis describes the comprehensive planning effort undertaken by the Metropolitan Area Planning Council in the Boston area. This effort engaged over 4,000 of the area's residents between 2002 and 2009 and produced a ...

Paul, Evan Thomas

2010-01-01T23:59:59.000Z

387

Handbook for Planning and Conducting Charrettes for High-Performance Projects: Second Edition  

SciTech Connect (OSTI)

This handbook furnishes guidance for planning and conducting a high-performance building charrette, sometimes called a "greening charrette."

Lindsay, G.; Todd, J. A.; Hayter, S. J.; Ellis, P. G.

2009-09-01T23:59:59.000Z

388

Become a Project Eye-to-Eye Coordinator! Project Eye-To-Eye's mission is to improve the life of every person with a learning disability. We fulfill our  

E-Print Network [OSTI]

Become a Project Eye-to-Eye Coordinator! Mission: Project Eye-To-Eye's mission is to improve: Awesome for your resume and work experience Networking with the Project Eye-to-Eye national community

Holland, Jeffrey

389

Engineers for a Sustainable World, Are you interested in working on projects aimed at improving sustainability on our  

E-Print Network [OSTI]

Engineers for a Sustainable World, UCSD Are you interested in working on projects aimed at improving sustainability on our campus, around San Diego, even around the world? Are you interested

Gille, Sarah T.

390

Implementation of UMTRA Project Environmental Audit Action Plan status report for period ending September 30, 1992. [Uranium Mill Tailings Remedial Action (UMTRA) Project  

SciTech Connect (OSTI)

This report provides the status of implementation of corrective actions for findings made in an Environmental Audit conducted by DOE Headquarters, Office of Environmental Audit, in June 1991. An Action Plan, dated December 1991, was developed to address the findings. The Action Plan was approved by DOE Headquarters, Office of Environment, Safety and Health, in July 1992. This report provides status for each activity listed in the approved Action Plan. Of 48 findings identified in the August 1991 Environmental Audit Report, 4 required no action, 5 were combined with others and actions to correct 19 are complete. Although it appears no progress has been made since the last status report was issued, UMTRA has completed 89% of the findings identified, compared to 72% identified in the last status report. The table below lists the 20 findings where actions are still underway, the current projected completion date, the organization(s) responsible for taking action on the finding, and the UMTRA Project Off ice staff member assigned responsibility for the finding.

Not Available

1992-09-01T23:59:59.000Z

391

Quality Assurance Project Plan for the HWMA/RCRA Closure Certification of the TRA-731 Caustic and Acid Storage Tank System - 1997 Notice of Violation Consent Order  

SciTech Connect (OSTI)

This Quality Assurance Project Plan for the HWMA/RCRA Closure Certification of the TRA- 731 Caustic and Acid Storage Tank System is one of two documents that comprise the Sampling and Analysis Plan for the HWMA/RCRA closure certification of the TRA-731 caustic and acid storage tank system at the Idaho National Engineering and Environmental Laboratory. This plan, which provides information about the project description, project organization, and quality assurance and quality control procedures, is to be used in conjunction with the Field Sampling Plan for the HWMA/RCRA Closure Certification of the TRA-731 Caustic and Acid Storage Tank System. This Quality Assurance Project Plan specifies the procedures for obtaining the data of known quality required by the closure activities for the TRA-731 caustic and acid storage tank system.

Evans, S.K.

2002-01-31T23:59:59.000Z

392

Quality Assurance Project Plan for the HWMA/RCRA Closure Certification of the TRA-731 Caustic and Acid Storage Tank System - 1997 Notice of Violation Consent Order  

SciTech Connect (OSTI)

This Quality Assurance Project Plan for the HWMA/RCRA Closure Certification of the TRA-731 Caustic and Acid Storage Tank System is one of two documents that comprise the Sampling and Analysis Plan for the HWMA/RCRA closure certification of the TRA-731 caustic and acid storage tank system at the Idaho National Engineering and Environmental Laboratory. This plan, which provides information about the project description, project organization, and quality assurance and quality control procedures, is to be used in conjunction with the Field Sampling Plan for the HWMA/RCRA Closure Certification of the TRA-731 Caustic and Acid Storage Tank System. This Quality Assurance Project Plan specifies the procedures for obtaining the data of known quality required by the closure activities for the TRA-731 caustic and acid storage tank system.

Evans, Susan Kay; Orchard, B. J.

2002-01-01T23:59:59.000Z

393

Project risk and appeals in U.S. Forest Service planning  

SciTech Connect (OSTI)

The National Environmental Policy Act (NEPA) requires U.S. Forest Service planning processes to be conducted by interdisciplinary teams of resource specialists to analyze and disclose the likely environmental impacts of proposed natural resource management actions on Forest Service lands. Multiple challenges associated with these processes have been a source of frustration for the agency. One of these challenges involves administrative appeals through which public entities can challenge a Forest Service decision following a NEPA process. These appeals instigate an internal review process and can result in an affirmation of the Forest Service decision, a reversal of that decision, or additional work that re-initiates all or part of the NEPA process. We examine the best predictors of appeals and their outcomes on a representative sample of 489 Forest Service NEPA processes that were decided between 2007 and 2009. While certain factors associated with pre-existing social contexts (such as a history of controversy) or pre-determined elements of a proposed action (such as the extraction of forest products) predispose certain processes to a higher risk of appeals, other practices and process-related strategies within the control of the agency also appear to bear meaningful influence on the occurrence of appeals and their outcomes. Appeals and their outcomes were most strongly related to programmatic, structural (turnover of personnel in particular), and relationship risks (both internal and external) within the processes, suggesting the need for greater focus within the agency on cultivating positive internal and external relationships to manage the risk of appeals. -- Highlights: ? We examined appeals and their outcomes on 489 U.S. Forest Service NEPA processes. ? Project type, context, team turnover, and personal relationships predicted appeals. ? External relationship management and staff turnover best predicted appeal outcomes. ? Positive internal and external relationships appear to reduce appeal risks.

Stern, Marc J., E-mail: mjstern@vt.edu [Department of Forest Resources and Environmental Conservation, Virginia Tech, 304 Cheatham Hall (0324), Blacksburg, VA 24061 (United States); Predmore, S. Andrew, E-mail: spred2@uis.edu [Department of Environmental Studies, University of Illinois-Springfield, Public Affairs Center, Room 314, Springfield, IL 62703 (United States); Morse, Wayde C., E-mail: morsewc@auburn.edu [School of Forestry and Wildlife Sciences, Auburn University, 3301 Forestry and Wildlife Bldg., Auburn, AL 36849 (United States); Seesholtz, David N., E-mail: dseesholtz@fs.fed.us [Focused Science Delivery Program, Pacific Northwest Research Station, USDA Forest Service, 1249S Vinnell Way, Suite 200, Boise, ID 83709 (United States)

2013-09-15T23:59:59.000Z

394

Improving the effectiveness of planning EIA (PEIA) in China: Integrating planning and assessment during the preparation of Shenzhen's Master Urban Plan  

SciTech Connect (OSTI)

The enactment and implementation of the 2003 EIA Law in China institutionalised the role of plan environmental impact assessment (PEIA). While the philosophy, methodology and mechanisms of PEIA have gradually permeated through the various levels of government with a positive effect on the process and outcome of urban planning, only a few cities in China have so far carried out PEIA as a Strategic Environmental Assessment (SEA)-type procedure. One such case is the southern city of Shenzhen. During the past three decades, Shenzhen has grown from a small town to a large and booming city as China has successfully and rapidly developed its economy by adopting the 'reform and open door' policy. In response to the challenges arising from the generally divergent processes of rapid urbanisation, economic transformation and environment protection, Shenzhen has incrementally adopted the SEA concept in developing the city's Master Urban Plan. As such, this paper reviews the effectiveness of PEIA in three ways: {center_dot}as a tool and process for achieving more sustainable and strategic planning; {center_dot}to determine the level of integration of SEA within the planning system; and, {center_dot}its effectiveness vis-a-vis implementation. The implementation of PEIA within Shenzhen's Master Urban Plan offers important insights into the emergence of innovative practices in undertaking PEIA as well as theoretical contributions to the field, especially in exploring the relationship between PEIA and SEA and highlighting the central role of local governing institutions in SEA development.

Che Xiuzhen, E-mail: chexiuzhen@sohu.com [Shenzhen Academy of Environmental Science, Shenzhen, Guangdong (China); English, Alex [Centre for Strategic Economic Studies, Victoria University (Australia); Lu Jia [Shenzhen Urban Planning and Research Center, Shenzhen, Guangdong (China); Chen, Yongqin David [Department of Geography and Resource Management, Chinese University of Hong Kong, Hong Kong (Hong Kong); Centre of Strategic Environmental Assessment for China, Chinese University of Hong Kong, Hong Kong (Hong Kong)

2011-11-15T23:59:59.000Z

395

Mitigation and Monitoring Plan for impacted wetlands at the Gunnison UMTRA Project site, Gunnison, Colorado. Revision 1  

SciTech Connect (OSTI)

The Gunnison, Colorado, abandoned uranium mill site is one site being cleaned up by the DOE under UMTRCA authority. This site`s contaminated material is being transported to a disposal site on US Bureau of Land Management (BLM) land east of Gunnison. Remedial action activities have temporarily disturbed 0.8 acre (ac) (0.3 hectares [ha]) of wetlands and permanently eliminated 4.3 ac (1.7 ha). As required by the Clean Water Act, the US Army Corps of Engineers (USACE) prepared a Section 404 Permit that addresses the loss of wetlands as a result of remedial action at the Gunnison UMTRA Project site. The 404 permit includes this report as an attachment and it describes the wetland mitigation and monitoring plan. The DOE formulated this plan in consultation with the BLM and the USACE. This report represents a revised version of the mitigation and monitoring plan (DOE, 1992b).

Not Available

1994-12-01T23:59:59.000Z

396

Oregon Trust Agreement Planning Project : Potential Mitigations to the Impacts on Oregon Wildlife Resources Associated with Relevant Mainstem Columbia River and Willamette River Hydroelectric Projects.  

SciTech Connect (OSTI)

A coalition of the Oregon wildlife agencies and tribes (the Oregon Wildlife Mitigation Coalition) have forged a cooperative effort to promote wildlife mitigation from losses to Oregon wildlife resources associated with the four mainstream Columbia River and the eight Willamette River Basin hydroelectric projects. This coalition formed a Joint Advisory Committee, made up of technical representatives from all of the tribes and agencies, to develop this report. The goal was to create a list of potential mitigation opportunities by priority, and to attempt to determine the costs of mitigating the wildlife losses. The information and analysis was completed for all projects in Oregon, but was gathered separately for the Lower Columbia and Willamette Basin projects. The coalition developed a procedure to gather information on potential mitigation projects and opportunities. All tribes, agencies and interested parties were contacted in an attempt to evaluate all proposed or potential mitigation. A database was developed and minimum criteria were established for opportunities to be considered. These criteria included the location of the mitigation site within a defined area, as well as other criteria established by the Northwest Power Planning Council. Costs were established for general habitats within the mitigation area, based on estimates from certified appraisers. An analysis of the cost effectiveness of various types of mitigation projects was completed. Estimates of operation and maintenance costs were also developed. The report outlines strategies for gathering mitigation potentials, evaluating them, determining their costs, and attempting to move towards their implementation.

United States. Bonneville Power Administration.

1993-10-01T23:59:59.000Z

397

INL-Site Idaho Completion Project Long Term Stewardship Strategic Plan  

SciTech Connect (OSTI)

This Strategic Plan provides a brief historical overview of ICP long-term stewardship at the INL Site and the major goals and strategies that will drive the continued implementation of long-term stewardship in the future. The specific activities and processes that will be required to implement these goals should be outlined within an implementation plan and within implementing procedures and work plans.

Olaveson, B.

2007-09-17T23:59:59.000Z

398

Creating an urban deer-vehicle accident management plan using information from a town's GIS project  

E-Print Network [OSTI]

AN URBAN DEER-VEHICLE ACCIDENT MANAGEMENT PLAN USINGincrease in deer vehicle accidents. Given the Town'sof increased deer vehicle accidents which, in the past 10

Premo, Dean B.; Rogers, Elizabeth I.

2001-01-01T23:59:59.000Z

399

Waste management project fiscal year 1998 multi-year work plan WBS 1.2  

SciTech Connect (OSTI)

The MYWP technical baseline describes the work to be accomplished by the Project and the technical standards which govern that work. The Waste Management Project manages and integrates (non-TWRS) waste management activities at the site. Activities include management of Hanford wastes as well as waste transferred to Hanford from other DOE, Department of Defense, or other facilities. This work includes handling, treatment, storage, and disposition of radioactive, nonradioactive, hazardous, and mixed solid and liquid wastes. Major Waste Management Projects are the Solid Waste Project (SW), Liquid Effluents Project (LEP), and Analytical Services. Existing facilities (e.g., grout vaults and canyons) shall be evaluated for reuse for these purposes to the maximum extent possible. The paper tabulates the major facilities that interface with this Project, identifying the major facilities that generate waste, materials, or infrastructure for this Project and the major facilities that will receive waste and materials from this Project.

Slaybaugh, R.R.

1997-08-29T23:59:59.000Z

400

Boyer-Tillamook Access Road Improvement Project 1 Mitigation Action Plan for Final Environmental Assessment  

Broader source: Energy.gov (indexed) [DOE]

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr May Jun Jul(Summary) "ofEarly Career Scientists' ResearchTheMarketing,Energy andNews and updatesStudy | Department ofBoyer-Tillamook

Note: This page contains sample records for the topic "improvement project plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


401

Objective 1: Extend Life, Improve Performance, and Maintain Safety of the Current Fleet Implementation Plan  

SciTech Connect (OSTI)

Nuclear power has reliably and economically contributed almost 20% of electrical generation in the United States over the past two decades. It remains the single largest contributor (more than 70%) of non-greenhouse-gas-emitting electric power generation in the United States. By the year 2030, domestic demand for electrical energy is expected to grow to levels of 16 to 36% higher than 2007 levels. At the same time, most currently operating nuclear power plants will begin reaching the end of their 60 year operating licenses. Figure E 1 shows projected nuclear energy contribution to the domestic generating capacity. If current operating nuclear power plants do not operate beyond 60 years, the total fraction of generated electrical energy from nuclear power will begin to decline—even with the expected addition of new nuclear generating capacity. The oldest commercial plants in the United States reached their 40th anniversary in 2009. The U.S. Department of Energy Office of Nuclear Energy’s Research and Development (R&D) Roadmap has organized its activities in accordance with four objectives that ensure nuclear energy remains a compelling and viable energy option for the United States. The objectives are as follows: (1) develop technologies and other solutions that can improve the reliability, sustain the safety, and extend the life of the current reactors; (2) develop improvements in the affordability of new reactors to enable nuclear energy to help meet the Administration’s energy security and climate change goals; (3) develop sustainable nuclear fuel cycles; and (4) understand and minimize risks of nuclear proliferation and terrorism. The Light Water Reactor Sustainability (LWRS) Program is the primary programmatic activity that addresses Objective 1. This document describes how Objective 1 and the LWRS Program will be implemented. The existing U.S. nuclear fleet has a remarkable safety and performance record and today accounts for 70% of the low greenhouse gas emitting domestic electricity production. Extending the operating lifetimes of current plants beyond 60 years and, where possible, making further improvements in their productivity will generate early benefits from research, development, and demonstration investments in nuclear power. DOE’s role in Objective 1 is to partner with industry and the Nuclear Regulatory Commission in appropriate ways to support and conduct the long-term research needed to inform major component refurbishment and replacement strategies, performance enhancements, plant license extensions, and age-related regulatory oversight decisions. The DOE research, development, and demonstration role will focus on aging phenomena and issues that require long-term research and are generic to reactor type. Cost-shared demonstration activities will be conducted when appropriate.

Robert Youngblood

2011-01-01T23:59:59.000Z

402

Advanced reservoir characterization for improved oil recovery in a New Mexico Delaware basin project  

SciTech Connect (OSTI)

The Nash Draw Brushy Canyon Pool in Eddy County, New Mexico is a field demonstration site in the Department of Energy Class III program. The basic problem at the Nash Draw Pool is the low recovery typically observed in similar Delaware fields. By comparing a control area using standard infill drilling techniques to a pilot area developed using advanced reservoir characterization methods, the goal of the project is to demonstrate that advanced technology can significantly improve oil recovery. During the first year of the project, four new producing wells were drilled, serving as data acquisition wells. Vertical seismic profiles and a 3-D seismic survey were acquired to assist in interwell correlations and facies prediction. Limited surface access at the Nash Draw Pool, caused by proximity of underground potash mining and surface playa lakes, limits development with conventional drilling. Combinations of vertical and horizontal wells combined with selective completions are being evaluated to optimize production performance. Based on the production response of similar Delaware fields, pressure maintenance is a likely requirement at the Nash Draw Pool. A detailed reservoir model of pilot area was developed, and enhanced recovery options, including waterflooding, lean gas, and carbon dioxide injection, are being evaluated.

Martin, F.D.; Kendall, R.P.; Whitney, E.M. [Dave Martin and Associates, Inc., Socorro, NM (United States)] [and others

1997-08-01T23:59:59.000Z

403

Lift-and-Project Relaxations of AC Microgrid Distribution System Planning  

E-Print Network [OSTI]

We apply relaxation procedures to polynomial optimization problems that originate in transmission system planning, and obtain new convex formulations for the AC case. The approach is novel because the optimization is ...

Taylor, Joshua A.

2011-01-01T23:59:59.000Z

404

2012 Annual Workforce Analysis and Staffing Plan Report- West Valley Demonstration Project  

Broader source: Energy.gov [DOE]

Managers perform an annual workforce analysis of their organization and develop staffing plans that identify technical capabilities and positions they need to ensure safe operation of defense nuclear facilities.

405

Integrated Project Management Planning for the Deactivation of the Savannah River Site F-Canyon Complex  

SciTech Connect (OSTI)

This paper explains the planning process that is being utilized by the Westinghouse Savannah River Company to take the F-Canyon Complex facilities from operations to a deactivated condition awaiting final decommissioning.

Clark, T.G.

2000-12-01T23:59:59.000Z

406

2010 Annual Workforce Analysis and Staffing Plan Report- Portsmouth Paducah Project Office  

Broader source: Energy.gov [DOE]

Managers perform an annual workforce analysis of their organization and develop staffing plans that identify technical capabilities and positions they need to ensure safe operation of defense nuclear facilities.

407

2011 Annual Workforce Analysis and Staffing Plan Report- Portsmouth Paducah Project Office  

Broader source: Energy.gov [DOE]

Managers perform an annual workforce analysis of their organization and develop staffing plans that identify technical capabilities and positions they need to ensure safe operation of defense nuclear facilities.

408

2012 Annual Workforce Analysis and Staffing Plan Report- Portsmouth Paducah Project Office  

Broader source: Energy.gov [DOE]

Managers perform an annual workforce analysis of their organization and develop staffing plans that identify technical capabilities and positions they need to ensure safe operation of defense nuclear facilities.

409

2013 Annual Workforce Analysis and Staffing Plan Report- Portsmouth Paducah Project Office  

Broader source: Energy.gov [DOE]

Managers perform an annual workforce analysis of their organization and develop staffing plans that identify technical capabilities and positions they need to ensure safe operation of defense nuclear facilities.

410

Using a town’s GIS project to create a deer-vehicle accident management plan  

E-Print Network [OSTI]

TO CREATE A DEER-VEHICLE ACCIDENT MANAGEMENT PLAN Elizabethhigh numbers of deer-vehicle accidents (DVAs) on a landscapeto provide an assessment of accident risk in time and space.

Rogers, Elizabeth I.

2003-01-01T23:59:59.000Z

411

Contractor Work Planning and Control Lessons Learned from DOE and International Projects  

Broader source: Energy.gov [DOE]

Slide Presentation by Bob McQuinn; URS Global Management and Operations Services; Frank McCoy and Rick Runnels; URS - Professional Solutions. Contractor Work Planning and Control-URS Lessons Learned.

412

Waste Management Project fiscal year 1998 multi-year work plan, WBS 1.2  

SciTech Connect (OSTI)

The Waste Management Project manages and integrates (non-TWRS) waste management activities at the site. Activities include management of Hanford wastes as well as waste transferred to Hanford from other DOE, Department of Defense, or other facilities. This work includes handling, treatment, storage, and disposal of radioactive, nonradioactive, hazardous, and mixed solid and liquid wastes. Major Waste Management Projects are the Solid Waste Project, Liquid Effluents Project, and Analytical Services. Existing facilities (e.g., grout vaults and canyons) shall be evaluated for reuse for these purposes to the maximum extent possible.

Jacobsen, P.H.

1997-09-23T23:59:59.000Z

413

DECHEM: A remedial planning tool for metallic contaminants in soil at UMTRA Project sites. Final report and users` guide  

SciTech Connect (OSTI)

The DECHEM (DEcontamination of CHEMicals) method was developed for the Uranium Mill Tailings Remedial Action (UMTRA) Project to guide characterization and remedial planning for metals contamination in soils. This is necessary because non-radiological hazardous constituents may be more mobile than radium-226 (Ra-226), and hence may migrate more deeply into subpile soils (beneath tailings that are to be relocated) or into adjacent contaminated soils at UMTRA Project sites. The result is that remedial action to the Ra-226 excavation limit, as specified in the US Environmental Protection Agency (EPA) standards, may not adequately remove hazardous non-radiological contamination. Unmitigated, these contaminants in soil may cause health risks because of their presence in resuspended particles, their uptake by crops or fodder their seepage into aquifers used for drinking water or other possible exposure pathways. The DECHEM method was developed in response to the need for advanced planning for the remediation of chemical contaminants at UMTRA Project sites, and includes the following elements: Establishment of acceptable exposure rates for humans to chemicals, based on EPA guidelines or other toxicological literature. Modeling of chemical migration through environmental pathways from a remediated UMTRA Project site to humans. Determination of allowable residual concentrations (i.e., cleanup guidelines) for chemicals in soils that results in doses to humans that are below established acceptable exposure rates. The initial development and application of the DECHEM method has focused upon hazardous metallic contaminants such as arsenic, lead, molybdenum, and selenium, which are known to occur in elevated concentrations at some UMTRA Project sites.

Not Available

1989-03-01T23:59:59.000Z

414

Cold test plan for the Old Hydrofracture Facility tank contents removal project, Oak Ridge National Laboratory, Oak Ridge, Tennessee  

SciTech Connect (OSTI)

This Old Hydrofracture Facility (OHF) Tanks Contents Removal Project Cold Test Plan describes the activities to be conducted during the cold test of the OHF sluicing and pumping system at the Tank Technology Cold Test Facility (TTCTF). The TTCTF is located at the Robotics and Process Systems Complex at the Oak Ridge National Laboratory (ORNL). The cold test will demonstrate performance of the pumping and sluicing system, fine-tune operating instructions, and train the personnel in the actual work to be performed. After completion of the cold test a Technical Memorandum will be prepared documenting completion of the cold test, and the equipment will be relocated to the OHF site.

NONE

1997-11-01T23:59:59.000Z

415

Facility Effluent Monitoring Plan for the Spent Nuclear Fuel (SNF) Project  

SciTech Connect (OSTI)

A facility effluent monitoring plan is required by the US. Department of Energy in DOE Order 5400.1 for any operations that involve hazardous materials and radioactive substances that could impact employee or public safety or the environment. This document was prepared using the specific guidelines identified in Westinghouse Hanford Company (WHC)-EP-0438-1, ''A Guide for Preparing Hanford Site Facility Effluent Monitoring Plans'', and assesses effluent monitoring systems and evaluates whether they are adequate to ensure the public health and safety as specified in applicable federal, state, and local requirements. This facility effluent monitoring plan is the third revision to the original annual report. This document is reviewed annually even if there are no operational changes, and it is updated as necessary.

HUNACEK, G.S.

2000-08-01T23:59:59.000Z

416

UBC Social Ecological Economic Development Studies (SEEDS) Student Report The Sustainability of the UBC Food System Project: A Sustainable Business Plan for  

E-Print Network [OSTI]

of the UBC Food System Project: A Sustainable Business Plan for Agora David Coney, Sandra Jacob, Yee Wah Lee should bear in mind that this is a student project/report and is not an official document of UBC. Furthermore readers should bear in mind that these reports may not reflect the current status of activities

417

QoS for Personal Networks at Home page 1 of 10 Project Plan, Public Version, September 16, 2003, Editor I.G. Niemegeers / G. Heijenk  

E-Print Network [OSTI]

, typically between portable and mobile computing devices such as laptops, personal digital assistants (PDA foreign devices Home environment 1 Figure 1: Example of a Personal Network This project focuses on QoQoS for Personal Networks at Home page 1 of 10 Project Plan, Public Version, September 16, 2003

Boucherie, Richard J.

418

FY 1992 revised task plans for the Hanford Environmental Dose Reconstruction Project  

SciTech Connect (OSTI)

The purpose of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate radiation doses from Hanford Site operations since 1944 to populations and individuals. The primary objectives of work to be performed in FY 1992 is to determine the appropriate scope (space, time, and radionuclides, pathways and individuals/population groups) and accuracy (level of uncertainty in dose estimates) for the project. Another objective is to use a refined computer model to estimate Native American tribal doses and individual doses for the Hanford Thyroid Disease Study (HTDS). Project scope and accuracy requirements defined in FY 1992 can translated into model and data requirements that must be satisfied during FY 1993.

Shipler, D.B.

1992-04-01T23:59:59.000Z

419

FY 1992 revised task plans for the Hanford Environmental Dose Reconstruction Project. Revision 1  

SciTech Connect (OSTI)

The purpose of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate radiation doses from Hanford Site operations since 1944 to populations and individuals. The primary objectives of work to be performed in FY 1992 is to determine the appropriate scope (space, time, and radionuclides, pathways and individuals/population groups) and accuracy (level of uncertainty in dose estimates) for the project. Another objective is to use a refined computer model to estimate Native American tribal doses and individual doses for the Hanford Thyroid Disease Study (HTDS). Project scope and accuracy requirements defined in FY 1992 can translated into model and data requirements that must be satisfied during FY 1993.

Shipler, D.B.

1992-04-01T23:59:59.000Z

420

Final report on the Background Soil Characterization Project at the Oak Ridge Reservation, Oak Ridge, Tennessee. Volume 3: Project Plan  

SciTech Connect (OSTI)

The Background Soil Characterization Project (BSCP) will provide background concentration levels of selected metals, organic compounds, and radionuclides in soils from uncontaminated on-site areas at the Oak Ridge Reservation (ORR), and off-site in the western part of Roane County and the eastern part of Anderson County. The BSCP will establish a database, recommend how to use the data for contaminated site assessment, and provide estimates of the potential human health and environmental risks associated with the background level concentrations of potentially hazardous constituents. ORR background soil characterization data will be used for two purposes. The first application will be in differentiating between naturally occurring constituents and site-related contamination. This is a very important step in a risk assessment because if sufficient background data are not available, no constituent known to be a contaminant can be eliminated from the assessment even if the sampled concentration is measured at a minimum level. The second use of the background data will be in calculating baseline risks against which site-specific contamination risks can be compared.

Hatmaker, T.L.; Hook, L.A.; Jackson, B.L. [and others

1993-10-01T23:59:59.000Z

Note: This page contains sample records for the topic "improvement project plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


421

Uranium Mill Tailings Remedial Action Project Environmental Line Management Audit Action Plan. Final report. Audit, October 26, 1992--November 6, 1992  

SciTech Connect (OSTI)

This Action Plan contains responses, planned actions, and estimated costs for addressing the findings discovered in the Environmental Management Audit conducted for the U.S. Department of Energy (DOE) Uranium Mill Tailings Remedial Action Project (UMTRA), October 26 through November 6, 1992. This document should be read in conjunction with the Audit Report to ensure the findings addressed in this document are fully understood. The scope of the UMTRA Environmental Management Audit was comprehensive and encompassed all areas of environmental management except environmental programs pertaining to the National Environmental Policy Act (NEPA) compliance. The Audit Report listed 18 findings: 11 were identified as compliance findings, and the remaining 7 were best management practice findings. Root cause analysis was performed on all the findings. The results of the analysis as well as planned corrective actions are summarized in Section 5.0. All planned actions were prioritized using the Tiger Team Assessment Corrective Action Plan system. Based on assigned priorities, all planned actions were costed by fiscal year. This Action Plan contains a description of the organizational and management structures to be used to implement the Action Plan, a brief discussion of root cause analysis and funding, followed by the responses and planned actions for each finding. A member of the UMTRA Project Office (PO) has been assigned responsibility for tracking the progress on each of the findings. The UMTRA PO staff wrote and/or approved all of the corrective actions recorded in this Action Plan.

NONE

1993-07-01T23:59:59.000Z

422

Ground-water sample collection and analysis plan for the ground-water surveillance project  

SciTech Connect (OSTI)

The Pacific Northwest Laboratory performs ground-water sampling activities at the US Department of Energy`s (DOE`s) Hanford Site in support of DOE`s environmental surveillance responsibilities. The purpose of this document is to translate DOE`s General Environmental Protection Program (DOE Order 5400.1) into a comprehensive ground-water sample collection and analysis plan for the Hanford Site. This sample collection and analysis plan sets forth the environmental surveillance objectives applicable to ground water, identifies the strategy for selecting sample collection locations, and lists the analyses to be performed to meet those objectives.

Bryce, R.W.; Evans, J.C.; Olsen, K.B.

1991-12-01T23:59:59.000Z

423

Ground-water sample collection and analysis plan for the ground-water surveillance project  

SciTech Connect (OSTI)

The Pacific Northwest Laboratory performs ground-water sampling activities at the US Department of Energy's (DOE's) Hanford Site in support of DOE's environmental surveillance responsibilities. The purpose of this document is to translate DOE's General Environmental Protection Program (DOE Order 5400.1) into a comprehensive ground-water sample collection and analysis plan for the Hanford Site. This sample collection and analysis plan sets forth the environmental surveillance objectives applicable to ground water, identifies the strategy for selecting sample collection locations, and lists the analyses to be performed to meet those objectives.

Bryce, R.W.; Evans, J.C.; Olsen, K.B.

1991-12-01T23:59:59.000Z

424

REGENERATIVE STORMWATER CONVEYANCE (RSC) AS AN INTEGRATED APPROACH TO SUSTAINABLE STORMWATER PLANNING ON LINEAR PROJECTS  

E-Print Network [OSTI]

vernal pool wetland area, improved water quality treatment,treatment for road runoff to a receiving depression, wetland,wetland and stream ecosystem function. The collection, treatment and

Berg, Joe; Underwood, Keith

2009-01-01T23:59:59.000Z

425

Title of Project: Ramp High Occupancy Vehicle (HOV) Sponsors: Chicago Metropolitan Agency for Planning  

E-Print Network [OSTI]

: reduced travel delay, value of travel time saved, fuel volume savings, fuel cost savings, reduced vehicle the scope of work: 1. Determine appropriate set of parallel streets to be modeled as alternative routes using planning agency data 7. Input traffic data to the FREQ traffic simulation model for the 2030

Illinois at Chicago, University of

426

CSMRI Site Remediation Quality Assurance Project Plan March 30, 2004 TABLE OF CONTENTS  

E-Print Network [OSTI]

and stockpiling of material from a former settling pond, off-site disposal of the stockpile, building cleanup 2004) was published that specified the off-site disposal of the affected material. The purpose of this Task Plan is to control the remediation process for the off-site disposal of the metals

427

Olkiluoto 1 and 2 - Plant efficiency improvement and lifetime extension-project (PELE) implemented during outages 2010 and 2011  

SciTech Connect (OSTI)

Teollisuuden Voima Oyj (TVO) is a non-listed public company founded in 1969 to produce electricity for its stakeholders. TVO is the operator of the Olkiluoto nuclear power plant. TVO follows the principle of continuous improvement in the operation and maintenance of the Olkiluoto plant units. The PELE project (Plant Efficiency Improvement and Lifetime Extension), mainly completed during the annual outages in 2010 and 2011, and forms one part of the systematic development of Olkiluoto units. TVO maintains a long-term development program that aims at systematically modernizing the plant unit systems and equipment based on the latest technology. According to the program, the Olkiluoto 1 and Olkiluoto 2 plant units are constantly renovated with the intention of keeping them safe and reliable, The aim of the modernization projects is to improve the safety, reliability, and performance of the plant units. PELE project at Olkiluoto 1 was done in 2010 and at Olkiluoto 2 in 2011. The outage length of Olkiluoto 1 was 26 d 12 h 4 min and Olkiluoto 2 outage length was 28 d 23 h 46 min. (Normal service-outage is about 14 days including refueling and refueling-outage length is about seven days. See figure 1) The PELE project consisted of several single projects collected into one for coordinated project management. Some of the main projects were as follows: - Low pressure turbines: rotor, stator vane, casing and turbine instrumentation replacement. - Replacement of Condenser Cooling Water (later called seawater pumps) pumps - Replacement of inner isolation valves on the main steam lines. - Generator and the generator cooling system replacement. - Low voltage switchgear replacement. This project will continue during future outages. PELE was a success. 100 TVO employees and 1500 subcontractor employees participated in the project. The execution of the PELE projects went extremely well during the outages. The replacement of the low pressure turbines and seawater pumps improved the efficiency of the plant units, and a power increase of nearly 20 MW was achieved at both plant units. PELE wonderfully manifests one of the strategic goals of our company; developing the competence of our in-house personnel by working in projects. (authors)

Kosonen, M.; Hakola, M. [Teollisuuden Voima Oyj, F- 27160 Eurajoki (Finland)

2012-07-01T23:59:59.000Z

428

Strategic Plan 2010-2015 Strategy Task Force Objective(s) Tactics  

E-Print Network [OSTI]

Master Plan Identify opportunities for physical improvement (estimate costs) VP for Administration Metrics Resources Expense Allocation Baseline Metric Target Target Completion Date Progress Toward Target projects Money spent Fund allocation FY11 Capital Project List Prioritized list Community #2: Nick

Bieber, Michael

429

Identification of potential strategies, methods, and tools for improving cost estimating practices for highway projects  

E-Print Network [OSTI]

Project cost escalation is a major problem for State Highway Agencies (SHA). This problem is evident in cost estimating procedures that may not promote consistency and accuracy of costs over the project development process. The research proposes...

Donnell, Kelly Elaine

2005-08-29T23:59:59.000Z

430

Implementation of advanced LCNG fueling infrastructure in Texas along the I-35/NAFTA Clean Corridor Project. Final report  

SciTech Connect (OSTI)

This report documents the process of planning, siting, and permitting recent LCNG station projects; identifying existing constraints in these processes, and recommendations for improvements; LCNG operating history.

Taylor, Stan; Hightower, Jared; Knight, Koby

2001-05-01T23:59:59.000Z

431

Spent nuclear fuels project: FY 1995 multi-year program plan, WBS {number_sign}1.4  

SciTech Connect (OSTI)

The mission of the Spent Nuclear Fuel (SNF) program is to safely, reliably, and efficiently manage, condition, transport, and store Department of Energy (DOE)-owned SNF, so that it meets acceptance criteria for disposal in a permanent repository. The Hanford Site Spent Nuclear Fuel strategic plan for accomplishing the project mission is: Establish near-term safe storage in the 105-K Basins; Complete national Environmental Policy Act (NEPA) process to obtain a decision on how and where spent nuclear fuel will be managed on the site; Define and establish alternative interim storage on site or transport off site to support implementation of the NEPA decision; and Define and establish a waste package qualified for final disposition. This report contains descriptions of the following: Work Breakdown Structure; WBS Dictionary; Responsibility Assignment Matrix; Program Logic Diagrams; Program Master Baseline Schedule; Program Performance Baseline Schedule; Milestone List; Milestone Description Sheets; Cost Baseline Summary by Year; Basis of Estimate; Waste Type Data; Planned Staffing; and Fiscal Year Work Plan.

Denning, J.L.

1994-09-01T23:59:59.000Z

432

Developing a monitoring and verification plan with reference to the Australian Otway CO2 pilot project  

SciTech Connect (OSTI)

The Australian Cooperative Research Centre for Greenhouse Gas Technologies (CO2CRC) is currently injecting 100,000 tons of CO{sub 2} in a large-scale test of storage technology in a pilot project in southeastern Australia called the CO2CRC Otway Project. The Otway Basin, with its natural CO{sub 2} accumulations and many depleted gas fields, offers an appropriate site for such a pilot project. An 80% CO{sub 2} stream is produced from a well (Buttress) near the depleted gas reservoir (Naylor) used for storage (Figure 1). The goal of this project is to demonstrate that CO{sub 2} can be safely transported, stored underground, and its behavior tracked and monitored. The monitoring and verification framework has been developed to monitor for the presence and behavior of CO{sub 2} in the subsurface reservoir, near surface, and atmosphere. This monitoring framework addresses areas, identified by a rigorous risk assessment, to verify conformance to clearly identifiable performance criteria. These criteria have been agreed with the regulatory authorities to manage the project through all phases addressing responsibilities, liabilities, and to assure the public of safe storage.

Dodds, K.; Daley, T.; Freifeld, B.; Urosevic, M.; Kepic, A.; Sharma, S.

2009-05-01T23:59:59.000Z

433

Development of Improved Traveler Survey Methods for High-Speed Intercity Passenger Rail Planning  

E-Print Network [OSTI]

High-speed passenger rail is seen by many in the U.S. transportation policy and planning communities as an ideal solution for fast, safe, and resource-efficient mobility in high-demand intercity corridors. To expand the body of knowledge for high...

Sperry, Benjamin

2012-07-16T23:59:59.000Z

434

River Protection Project (RPP) Immobilized High Level Waste (HLW) Interim Storage Plan  

SciTech Connect (OSTI)

This document replaces HNF-1751, Revision 1. It incorporates updates to reflect changes in programmatic direction associated with the vitrification plant contract and associated DOE-ORP guidance. In addition it includes planning associated with failed/used melter and sample handling and disposition work scope. The document also includes format modifications and section numbering update consistent with CH2M HILL Hanford Group, Inc. procedures.

BRIGGS, M.G.

2000-09-22T23:59:59.000Z

435

Final Report for the portion performed in the University of Illinois on the project entitled "Optimizing the Cloud-Aerosol-Radiation Ensemble Modeling System to Improve Future Climate Change Projections at Regional to Local Scales"  

SciTech Connect (OSTI)

This is the final report for the closure of the research tasks on the project that have performed during the entire reporting period in the University of Illinois. It contains a summary of the achievements and details of key results as well as the future plan for this project to be continued in the University of Maryland.

Liang, Xin-Zhong

2011-01-31T23:59:59.000Z

436

Final Technical Report for Project "Improving the Simulation of Arctic Clouds in CCSM3"  

SciTech Connect (OSTI)

This project has focused on the simulation of Arctic clouds in CCSM3 and how the modeled cloud amount (and climate) can be improved substantially by altering the parameterized low cloud fraction. The new formula, dubbed 'freeezedry', alleviates the bias of excessive low clouds during polar winter by reducing the cloud amount under very dry conditions. During winter, freezedry decreases the low cloud amount over the coldest regions in high latitudes by over 50% locally and more than 30% averaged across the Arctic (Fig. 1). The cloud reduction causes an Arctic-wide drop of 15 W m{sup -2} in surface cloud radiative forcing (CRF) during winter and about a 50% decrease in mean annual Arctic CRF. Consequently, wintertime surface temperatures fall by up to 4 K on land and 2-8 K over the Arctic Ocean, thus significantly reducing the model's pronounced warm bias (Fig. 1). While improving the polar climate simulation in CCSM3, freezedry has virtually no influence outside of very cold regions (Fig. 2) or during summer (Fig. 3), which are space and time domains that were not targeted. Furthermore, the simplicity of this parameterization allows it to be readily incorporated into other GCMs, many of which also suffer from excessive wintertime polar cloudiness, based on the results from the CMIP3 archive (Vavrus et al., 2008). Freezedry also affects CCSM3's sensitivity to greenhouse forcing. In a transient-CO{sub 2} experiment, the model version with freezedry warms up to 20% less in the North Polar and South Polar regions (1.5 K and 0.5 K smaller warming, respectively) (Fig. 4). Paradoxically, the muted high-latitude response occurs despite a much larger increase in cloud amount with freezedry during non-summer months (when clouds warm the surface), apparently because of the colder modern reference climate. These results of the freezedry parameterization have recently been published (Vavrus and D. Waliser, 2008: An improved parameterization for simulating Arctic cloud amount in the CCSM3 climate model. J. Climate, 21, 5673-5687.). The article also provides a novel synthesis of surface- and satellite-based Arctic cloud observations that show how much the new freezedry parameterization improves the simulated cloud amount in high latitudes (Fig. 3). Freezedry has been incorporated into the CCSM3.5 version, in which it successfully limits the excessive polar clouds, and may be used in CCSM4. Material from this work is also appearing in a synthesis article on future Arctic cloud changes (Vavrus, D. Waliser, J. Francis, and A. Schweiger, 'Simulations of 20th and 21st century Arctic cloud amount in the global climate models assessed in the IPCC AR4', accepted in Climate Dynamics) and was used in a collaborative paper on Arctic cloud-sea ice coupling (Schweiger, A., R. Lindsay, S. Vavrus, and J. Francis, 2008: Relationships between Arctic sea ice and clouds during autumn. J. Climate, 21, 4799-4810.). This research was presented at the 2007 CCSM Annual Workshop, as well as the CCSM's 2007 Atmospheric Model Working Group and Polar Working Group Meetings. The findings were also shown at the 2007 Climate Change Prediction Program's Science Team Meeting. In addition, I served as an instructor at the International Arctic Research Center's (IARC) Summer School on Arctic Climate Modeling in Fairbanks this summer, where I presented on the challenges and techniques used in simulating polar clouds. I also contributed to the development of a new Arctic System Model by attending a workshop in Colorado this summer on this fledgling project. Finally, an outreach activity for the general public has been the development of an interactive web site () that displays Arctic cloud amount in the CMIP3 climate model archive under present and future scenarios. This site allows users to make polar and global maps of a variety of climate variables to investigate the individual and ensemble-mean GCM response to greenhouse warming and the extent to which models adequately represent Arctic clouds in the modern clima

Stephen J. Vavrus

2008-11-15T23:59:59.000Z

437

Riding the Clean Energy Wave: New Projects Aim to Improve Water Power Devices  

Broader source: Energy.gov [DOE]

The Energy Department announces two projects as part of a larger effort to deploy innovative technologies for clean, domestic power generation from water power resources.

438

An R&D Guide and Multiyear Plan for Improving Energy Use in  

E-Print Network [OSTI]

to acknowledge the support and contributions of the Commercial Buildings Team, at the US Department of Energy An Introduction to the Guide: A Brief Glossary of Terms 1 PART TWO DOE's vision for existing commercial buildings in 2015 3 PART THREE DOE's criteria for selecting R&D projects in existing commercial building 4 PART FOUR

439

California Commissioning Collaborative: 2007 Program Plan  

E-Print Network [OSTI]

California Commissioning Collaborative: 2007 Program Plan Presented by: Jim Parks, Chair CCC Board of Directors November 1, 2007 © California Commissioning Collaborative © California Commissioning Collaborative Mission and Organization • Improve... and RCx as a strategy for meeting efficiency goals • CCC projects provide support and resources © California Commissioning Collaborative 2007 Program Plan • Support for Retrocommissioning Programs – Verification of Savings • Retrocommissioning Market...

Parks, J.

2007-01-01T23:59:59.000Z

440

Supplement to the UMTRA Project water sampling and analysis plan, Ambrosia Lake, New Mexico  

SciTech Connect (OSTI)

The Ambrosia Lake Uranium Mill Tailings Remedial Action (UMTRA) Project site is in McKinley County, New Mexico. As part of UMTRA surface remediation, residual radioactive materials were consolidated on the site in a disposal cell that was completed July 1995. The need for ground water monitoring was evaluated and found not to be necessary beyond the completion of the remedial action because the ground water in the uppermost aquifer is classified as limited use.

NONE

1995-08-01T23:59:59.000Z

Note: This page contains sample records for the topic "improvement project plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


441

Post-Cleanup Communication and Records Plan for Project Chariot, Alaska  

SciTech Connect (OSTI)

The Project Chariot Site resides in a remote and isolated area in the Cape Thompson region of northwest Alaska (Figure 1-1). The Project Chariot Site was a proposed test location for the U.S. Atomic Energy Commission (AEC) Plowshare Program in 1958. In 1962, the United States Geological Survey (USGS) conducted environmental studies using less than 30 mCi of short-lived mixed fission products. The location of the studies was about 0.75 mile (1.2 km) north of the Project Chariot Site base camp. Radioactive material was spread over the 12 test plots: 10 were used for overland transport tracer tests, one for a sediment transport experiment, and one for an 18-hour percolation test. The 11 test plots constituted an area less than 0.9 percent of an acre. At the conclusion of the August 1962 tracer test, USGS scraped the ground surface of the test plots and the percolation test location. The scraped soil and vegetation were mixed with native soil, deposited in a mound on two of the plots, and covered with 4 ft (1.22 m) of uncontaminated soil (DOE 1993).

None

2005-01-01T23:59:59.000Z

442

A study of the future water requirements of the state of Texas and the projected plan to meet them as presented by the United States Study Commission - Texas  

E-Print Network [OSTI]

that my education could be continued. G. W. August, 1963 111 CONTENTS Page List of Tables List of Plates Chapter vi I. Introduction II. Water Resources I II. Water Requirements IV. The Water Development Plan 15 31 34 V. Views and Comments... University in partial fulfillment of the requirements for the degree of MASTER OF BUSINESS ADMINISTRATION Sanuary, 1964 Major Subject Business Adzninistration A STUDY OF THE FUTURE WATER REQUIREMENTS. OF THE STATE OF TEXAS AND THE PROJECTED PLAN TO MEET...

Wortham, Gene Rye

1964-01-01T23:59:59.000Z

443

2033 Long Range Transportation Plan and FY 2010-2013 Transportation Improvement Program  

E-Print Network [OSTI]

was adopted in June 2005 by the MPO and prepared under the guidelines of the Transportation Equity Act for the 21st Century (TEA-21). The 2033 LRP reaffirms the basic issues and goals of the previous plans while considering additional matters of concern.... The two landmark bills that brought surface transportation into the 21 st century?the Intermodal Surface Transportation Efficiency Act of 1991 (ISTEA) and the Transportation Equity Act for the 21 st Century (TEA-21)?shaped the highway program to meet...

The West-Memphis Metropolitan Planning Organization

444

Project plan: Procedure system design for the Rocky Flats Plant Emergency Preparedness Program  

SciTech Connect (OSTI)

This procedure system is being designed for the Rocky Flats Plant Emergency Preparedness Program (EPP) to: assess the procedural needs of the Emergency Preparedness Program in light of the existing Rocky Flats Plant policies, plans, procedures, and applicable DOE orders; design the structure of the Emergency Preparedness Program procedural system based on the classes of procedures needed, the types of procedures (procedures vs job outline), the sections of procedures required, and the timetable for procedure maintenance; develop boiler plate formats for the various authors in writing the necessary standardized procedures; develop a list of all the necessary procedures that must be produced for Emergency Preparedness Program; and provide consistency for department-wide activities relating to the quality control in writing, distribution, and revising procedures for Emergency Preparedness Program. 23 refs., 18 figs.

Hodgin, C.R.; Brown-Strattan, M.

1989-10-01T23:59:59.000Z

445

The Ohio River Valley CO2 Storage Project AEP Mountaineer Plan, West Virginia  

SciTech Connect (OSTI)

This report includes an evaluation of deep rock formations with the objective of providing practical maps, data, and some of the issues considered for carbon dioxide (CO{sub 2}) storage projects in the Ohio River Valley. Injection and storage of CO{sub 2} into deep rock formations represents a feasible option for reducing greenhouse gas emissions from coal-burning power plants concentrated along the Ohio River Valley area. This study is sponsored by the U.S. Department of Energy (DOE) National Energy Technology Laboratory (NETL), American Electric Power (AEP), BP, Ohio Coal Development Office, Schlumberger, and Battelle along with its Pacific Northwest Division. An extensive program of drilling, sampling, and testing of a deep well combined with a seismic survey was used to characterize the local and regional geologic features at AEP's 1300-megawatt (MW) Mountaineer Power Plant. Site characterization information has been used as part of a systematic design feasibility assessment for a first-of-a-kind integrated capture and storage facility at an existing coal-fired power plant in the Ohio River Valley region--an area with a large concentration of power plants and other emission sources. Subsurface characterization data have been used for reservoir simulations and to support the review of the issues relating to injection, monitoring, strategy, risk assessment, and regulatory permitting. The high-sulfur coal samples from the region have been tested in a capture test facility to evaluate and optimize basic design for a small-scale capture system and eventually to prepare a detailed design for a capture, local transport, and injection facility. The Ohio River Valley CO{sub 2} Storage Project was conducted in phases with the ultimate objectives of demonstrating both the technical aspects of CO{sub 2} storage and the testing, logistical, regulatory, and outreach issues related to conducting such a project at a large point source under realistic constraints. The site characterization phase was completed, laying the groundwork for moving the project towards a potential injection phase. Feasibility and design assessment activities included an assessment of the CO{sub 2} source options (a slip-stream capture system or transported CO{sub 2}); development of the injection and monitoring system design; preparation of regulatory permits; and continued stakeholder outreach.

Neeraj Gupta

2009-01-07T23:59:59.000Z

446

Sarah McCarthy, FULD Fellow Cohort II The goal of the Hourly Rounding project focuses on techniques to improve safety and patient  

E-Print Network [OSTI]

to improve my place of employment. I hope to instill a culture of safety, openness and communication wherever to improve safety and patient satisfaction. This project was initiated after learning patient satisfaction is directly affected by nurse responsiveness and patient safety. The initiation of the project created

von der Heydt, RĂĽdiger

447

2012 Annual Planning Summary for Advanced Research Projects Agency-Energy |  

Energy Savers [EERE]

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious RankCombustionImprovement Awardflash2007-42attachment1.pdfmodule(EE) |the Fuel Cell(Septemberof

448

Color intensity projections: A rapid approach for evaluating four-dimensional CT scans in treatment planning  

SciTech Connect (OSTI)

Purpose: Four-dimensional computerized tomography scans (4DCT) enable intrafractional motion to be determined. Because more than 1500 images can be generated with each 4DCT study, tools for efficient data visualization and evaluation are needed. We describe the use of color intensity projections (CIP) for visualizing mobility. Methods: Four-dimensional computerized tomography images of each patient slice were combined into a CIP composite image. Pixels largely unchanged over the component images appear unchanged in the CIP image. However, pixels whose intensity changes over the phases of the 4DCT appear in the CIP image as colored pixels, and the hue encodes the percentage of time the tissue was in each location. CIPs of 18 patients were used to study tumor and surrogate markers, namely the diaphragm and an abdominal marker block. Results: Color intensity projections permitted mobility of high-contrast features to be quickly visualized and measured. In three selected expiratory phases ('gating phases') that were reviewed in the sagittal plane, gating would have reduced mean tumor mobility from 6.3 {+-} 2.0 mm to 1.4 {+-} 0.5 mm. Residual tumor mobility in gating phases better correlated with residual mobility of the marker block than that of the diaphragm. Conclusion: CIPs permit immediate visualization of mobility in 4DCT images and simplify the selection of appropriate surrogates for gated radiotherapy.

Cover, Keith S. [Department of Radiation Oncology, VU University Medical Center, Amsterdam (Netherlands); Lagerwaard, Frank J. [Department of Radiation Oncology, VU University Medical Center, Amsterdam (Netherlands); Senan, Suresh [Department of Radiation Oncology, VU University Medical Center, Amsterdam (Netherlands)]. E-mail: s.senan@vumc.nl

2006-03-01T23:59:59.000Z

449

Factors to improve project performance : lessons from a Chilean urban agriculture program  

E-Print Network [OSTI]

This thesis investigates a Chilean urban agriculture project that has been underway for more than twenty years in Tome, a small coastal town located near the regional capital of Concepcion. Initiated in the early 1980s by ...

Scott, Maggie, 1975-

2003-01-01T23:59:59.000Z

450

Results From The Salt Disposition Project Next Generation Solvent Demonstration Plan  

SciTech Connect (OSTI)

Strip Effluent Hold Tank (SEHT), Decontaminated Salt Solution Hold Tank (DSSHT), Caustic Wash Tank (CWT) and Solvent Hold Tank (SHT) samples were taken throughout the Next Generation Solvent (NGS) Demonstration Plan. These samples were analyzed and the results are reported. SHT: The solvent behaved as expected, with no bulk changes in the composition over time, with the exception of the TOA and TiDG. The TiDG depletion is higher than expected, and consideration must be taken on the required rate of replenishment. Monthly sampling of the SHT is warranted. If possible, additional SHT samples for TiDG analysis (only) would help SRNL refine the TiDG degradation model. CWT: The CWT samples show the expected behavior in terms of bulk chemistry. The 137Cs deposited into the CWT varies somewhat, but generally appears to be lower than during operations with the BOBCalix solvent. While a few minor organic components were noted to be present in the Preliminary sample, at this time these are thought to be artifacts of the sample preparation or may be due to the preceding solvent superwash. DSSHT: The DSSHT samples show the predicted bulk chemistry, although they point towards significant dilution at the front end of the Demonstration. The 137Cs levels in the DSSHT are much lower than during the BOBCalix operations, which is the expected observation. SEHT: The SEHT samples represent the most different output of all four of the outputs from MCU. While the bulk chemistry is as expected, something is causing the pH of the SEHT to be higher than what would be predicted from a pure stream of 0.01 M boric acid. There are several possible different reasons for this, and SRNL is in the process of investigating. Other than the pH issue, the SEHT is as predicted. In summary, the NGS Demonstration Plan samples indicate that the MCU system, with the Blend Solvent, is operating as expected. The only issue of concern regards the pH of the SEHT, and SRNL is in the process of investigating this. SRNL results support the transition to routine operations.

Peters, T. B.; Fondeur, F. F.; Taylor-Pashow, K. M.L.

2014-04-02T23:59:59.000Z

451

Site observational work plan for the UMTRA Project site at Ambrosia Lake, New Mexico  

SciTech Connect (OSTI)

The Ambrosia Lake Uranium Mill Tailings Remedial Action (UMTRA) Project site is within the Grants Mineral Belt and was one of numerous uranium mills supplied by many local mines. Ground water contamination at the site occurred as a result of uranium mill operations. The potential for impacts to human health and the environment from contaminated ground water currently does not exist. No domestic or livestock wells accessing ground water from the uppermost aquifer have been identified within a 5 mile radius from the site. Therefore, no current exposure pathways to humans, livestock, or wildlife exist, nor are any foreseen. The proposed ground water compliance strategy under consideration for application at the Ambrosia Lake site is to perform no remediation, based on the application of supplemental standards because the ground water has ``limited use.``

Not Available

1994-09-01T23:59:59.000Z

452

2010 Annual Planning Summary for Advanced Research Projects Agency-Energy  

Energy Savers [EERE]

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious RankCombustionImprovement Awardflash2007-42attachment1.pdfmodule 4 module51:11|ofConference9(ARPA-E) |

453

2014 Annual Planning Summary for the Office of Advanced Research Projects  

Energy Savers [EERE]

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious RankCombustionImprovement3 Beryllium-Associated Worker RegistryDepartment ofEnergy NavalofAgency - Energy

454

2014 Annual Planning Summary for the Portsmouth/Paducah Project Office |  

Energy Savers [EERE]

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious RankCombustionImprovement3 Beryllium-Associated Worker RegistryDepartment ofEnergyof Energy

455

Conceptual Site Treatment Plan Laboratory for Energy-Related Health Research Environmental Restoration Project  

SciTech Connect (OSTI)

The Federal Facilities Compliance Act (the Act) of 1992 waives sovereign immunity for federal facilities for fines and penalties under the provisions of the Resource Recovery and Conservation Act, state, interstate, and local hazardous and solid waste management requirements. However, for three years the Act delays the waiver for violations involving US Department of Energy (DOE) facilities. The Act, however, requires that the DOE prepare a Conceptual Site Treatment Plan (CSTP) for each of its sites that generate or store mixed wastes (MWs). The purpose of the CSTP is to present DOE`s preliminary evaluations of the development of treatment capacities and technologies for treating a site`s MW. This CSTP presents the preliminary capacity and technology evaluation for the Laboratory for Energy-Related Health Research (LEHR). The five identified MW streams at LEHR are evaluated to the extent possible given available information. Only one MW stream is sufficiently well defined to permit a technology evaluation to be performed. Two other MW streams are in the process of being characterized so that an evaluation can be performed. The other two MW streams will be generated by the decommissioning of inactive facilities onsite within the next five years.

Chapman, T.E.

1993-10-01T23:59:59.000Z

456

Project Fact Sheet Project Brief  

E-Print Network [OSTI]

Project Fact Sheet Project Brief: In the first phase of the Union Building re.union.ic.ac.uk/marketing/building Construction Project Team: Project Facts & Figures: Budget: ÂŁ1,400,000 Funding Source: Capital Plan and Imperial College Union reserves Construction Project Programme: Start on Site: August 2006 End Date: March

457

Productivity improvement in downstream EPC projects using value streams based organization  

E-Print Network [OSTI]

Productivity improvements in manufacturing facilities have been studied in detail and there are many standardized tools and frameworks readily available to the industry for implementation. However the concept of productivity ...

Raghunathan, Krishnan

2006-01-01T23:59:59.000Z

458

Improving the representation of terrestrial ecosystem processes in Earth system models to increase the quality of climate model projections and inform DOE's energy decisions  

E-Print Network [OSTI]

Improving the representation of terrestrial ecosystem processes in Earth system models to increase results are incorporated into Earth system models to improve climate projections. e overarching goal of TES is to improve the representation of terrestrial ecosystem processes in Earth system models

459

Evaluation of the effects of a highway improvement project on Key deer  

E-Print Network [OSTI]

assessed the potential impacts of the US 1 corridor project to Key deer movements by comparing (1) radio-collared Key deer annual ranges (2) radio-collared deer corridor movements, and (3) assessing Key deer underpass and corridor use. Female and male...

Braden, Anthony Wayne

2006-10-30T23:59:59.000Z

460

Project W-314 specific test and evaluation plan for transfer line SN-633 (241-AX-B to 241-AY-02A)  

SciTech Connect (OSTI)

The purpose of this Specific Test and Evaluation Plan (STEP) is to provide a detailed written plan for the systematic testing of modifications made by the addition of the SN-633 transfer line by the W-314 Project. The STEP develops the outline for test procedures that verify the system`s performance to the established Project design criteria. The STEP is a lower tier document based on the W-314 Test and Evaluation Plan (TEP). This STEP encompasses all testing activities required to demonstrate compliance to the project design criteria as it relates to the addition of transfer line SN-633. The Project Design Specifications (PDS) identify the specific testing activities required for the Project. Testing includes Validations and Verifications (e.g., Commercial Grade Item Dedication activities), Factory Acceptance Tests (FATs), installation tests and inspections, Construction Acceptance Tests (CATs), Acceptance Test Procedures (ATPs), Pre-Operational Test Procedures (POTPs), and Operational Test Procedures (OTPs). It should be noted that POTPs are not required for testing of the transfer line addition. The STEP will be utilized in conjunction with the TEP for verification and validation.

Hays, W.H.

1998-03-20T23:59:59.000Z

First Page Previous Page 1 2 3 4 5 6 7