Powered by Deep Web Technologies
Note: This page contains sample records for the topic "icm interim corrective" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


1

RCRA corrective action program guide (Interim)  

SciTech Connect (OSTI)

The US Department of Energy (DOE) is responsible for compliance with an increasingly complex spectrum of environmental regulations. One of the most complex programs is the corrective action program proposed by the US Environmental Protection Agency (EPA) under the authority of the Resource Conservation and Recovery Act (RCRA) as amended by the Hazardous and Solid Waste Amendments (HSWA). The proposed regulations were published on July 27, 1990. The proposed Subpart S rule creates a comprehensive program for investigating and remediating releases of hazardous wastes and hazardous waste constituents from solid waste management units (SWMUs) at facilities permitted to treat, store, or dispose of hazardous wastes. This proposed rule directly impacts many DOE facilities which conduct such activities. This guidance document explains the entire RCRA Corrective Action process as outlined by the proposed Subpart S rule, and provides guidance intended to assist those persons responsible for implementing RCRA Corrective Action at DOE facilities.

Not Available

1993-05-01T23:59:59.000Z

2

DOUBLE TRACKS Test Site interim corrective action plan  

SciTech Connect (OSTI)

The DOUBLE TRACKS site is located on Range 71 north of the Nellis Air Force Range, northwest of the Nevada Test Site (NTS). DOUBLE TRACKS was the first of four experiments that constituted Operation ROLLER COASTER. On May 15, 1963, weapons-grade plutonium and depleted uranium were dispersed using 54 kilograms of trinitrotoluene (TNT) explosive. The explosion occurred in the open, 0.3 m above the steel plate. No fission yield was detected from the test, and the total amount of plutonium deposited on the ground surface was estimated to be between 980 and 1,600 grams. The test device was composed primarily of uranium-238 and plutonium-239. The mass ratio of uranium to plutonium was 4.35. The objective of the corrective action is to reduce the potential risk to human health and the environment and to demonstrate technically viable and cost-effective excavation, transportation, and disposal. To achieve these objectives, Bechtel Nevada (BN) will remove soil with a total transuranic activity greater then 200 pCI/g, containerize the soil in ``supersacks,`` transport the filled ``supersacks`` to the NTS, and dispose of them in the Area 3 Radioactive Waste Management Site. During this interim corrective action, BN will also conduct a limited demonstration of an alternative method for excavation of radioactive near-surface soil contamination.

NONE

1996-06-01T23:59:59.000Z

3

ICM, Incorporated  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE:YearRound-UpHeatMulti-Dimensionalthe U.S. Department of EnergyKickoff Meeting Agenda:15,10-11,ICM,

4

ATVM Interim Final Rule Correction | Department of Energy  

Energy Savers [EERE]

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious RankCombustionImprovement3 Beryllium-Associated6-05.pdfATTENDEEES: Ashley Armstrong, DOE Laura BarhydtInterim

5

Consideration of Ecosystem for ICME  

SciTech Connect (OSTI)

As the Integrated Computational Materials Engineering (ICME) emerges as a hot topic, computation, experimentation, and digital database are identified as its three major components. Efforts are being actively made from various aspects to bring ICME to reality. However, many factors that would affect ICEM development still remain vague. This paper is an attempt to discuss the needs for establishing a database centered ecosystem to facilitate ICEM development.

Ren, Weiju [ORNL

2013-01-01T23:59:59.000Z

6

Biomass IBR Fact Sheet: ICM, Inc.  

Broader source: Energy.gov (indexed) [DOE]

technology coupled with a robust C5C6 co-fermenting organism to refine cellulosic biomass into fuel ethanol and co- products. ICM's process addresses pretreatment, hydrolysis,...

7

Integrated Computational Materials Engineering (ICME) for Mg...  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

Project (Part 1) Integrated Computational Materials Engineering (ICME) for Mg: International Pilot Project (Part 1) 2010 DOE Vehicle Technologies and Hydrogen Programs Annual Merit...

8

ICM Inc | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data CenterFranconia, Virginia: Energy Resources Jump to: navigation,Ohio:GreerHiCalifornia: Energythe SecondInformation 3 -2ICE SolarICM

9

Interim Activities at Corrective Action Unit 114: Area 25 EMAD Facility, Nevada National Security Site, Nevada, for Fiscal Years 2012 and 2013  

SciTech Connect (OSTI)

This letter report documents interim activities that have been completed at CAU 114 in fiscal years 2012 and 2013.

Silvas, A J

2013-10-24T23:59:59.000Z

10

ICME & MGI Big Area Additive Manufacturing  

E-Print Network [OSTI]

ICME & MGI · Big Area Additive Manufacturing · Neutron Characterization for AM · Materials problems in additive manu- facturing (AM). Additive manufacturing, or three-dimensional (3-D) printing of the world's most advanced neu- tron facilities, the HFIR and SNS, to characterize additive manufactured

11

Interim report  

SciTech Connect (OSTI)

This Interim Report summarizes the research and development activities of the Superconducting Super Collider project carried out from the completion of the Reference Designs Study (May 1984) to June 1985. It was prepared by the SSC Central Design Group in draft form on the occasion of the DOE Annual Review, June 19--21, 1985. Now largely organized by CDG Divisions, the bulk of each chapter documents the progress and accomplishments to date, while the final section(s) describe plans for future work. Chapter 1, Introduction, provides a basic brief description of the SSC, its physics justification, its origins, and the R&D organization set up to carry out the work. Chapter 2 gives a summary of the main results of the R&D program, the tasks assigned to the four magnet R&D centers, and an overview of the future plans. The reader wishing a quick look at the SSC Phase I effort can skim Chapter 1 and read Chapter 2. Subsequent chapters discuss in more detail the activities on accelerator physics, accelerator systems, magnets and cryostats, injector, detector R&D, conventional facilities, and project planning and management. The magnet chapter (5) documents in text and photographs the impressive progress in successful construction of many model magnets, the development of cryostats with low heat leaks, and the improvement in current-carrying capacity of superconducting strand. Chapter 9 contains the budgets and schedules of the COG Divisions, the overall R&D program, including the laboratories, and also preliminary projections for construction. Appendices provide information on the various panels, task forces and workshops held by the CDG in FY 1985, a bibliography of COG and Laboratory reports on SSC and SSC-related work, and on private industrial involvement in the project.

NONE

1985-06-01T23:59:59.000Z

12

The Heating of the ICM: Energy Crisis and viable solutions  

E-Print Network [OSTI]

X-ray observations indicate that non-gravitational processes play a key role in the thermodynamics of the Intra Cluster Medium (ICM). The effect of non-gravitational processes is imprinted in the ICM as an entropy minimum, whose effects are visible in the Luminosity-Temperature relation and in the Entropy-Temperature relation. However, the X-ray emission alone cannot discriminate between different mechanisms and sources of heating. There are no answers at present to the following questions: how much non-gravitational energy per baryons is present in the ICM? When was this energy injected? Which are the sources of heating? The embarrassment in front of these questions is amplified by the fact that the most viable sources of heating, SNae and stellar winds, seem to be inefficient in bringing the ICM to the observed entropy level. We may call it the energy crisis. Here we review the main aspects of this crisis, listing possible solutions, including other sources, like AGNs and Radio Galaxies, or other mechanisms, like large scale shocks and selective cooling.

Paolo Tozzi

2001-09-05T23:59:59.000Z

13

INTERIM POLICY JANUARY 9, 2004  

E-Print Network [OSTI]

INTERIM POLICY JANUARY 9, 2004 CORNELL UNIVERSITY POLICY LIBRARY Health and Safety POLICY 2 _________________________________________________________________________________________________________________________________________________ POLICY STATEMENT. _________________________________________________________________________________________________________________________________________________ REASON FOR POLICY

Chen, Tsuhan

14

Policy Statement and Interim  

E-Print Network [OSTI]

1 Policy Statement and Interim Procedures CORNELL UNIVERSITY POLICY LIBRARY POLICY 8.3 Volume: 8 Emergency Planning POLICY STATEMENT Cornell University organizes, coordinates, and directs available of this effort is dependent on the development of periodic review of comprehensive plans. This policy includes

Hemami, Sheila S.

15

Interim storage study report  

SciTech Connect (OSTI)

High-level radioactive waste (HLW) stored at the Idaho Chemical Processing Plant (ICPP) in the form of calcine and liquid and liquid sodium-bearing waste (SBW) will be processed to provide a stable waste form and prepare the waste to be transported to a permanent repository. Because a permanent repository will not be available when the waste is processed, the waste must be stored at ICPP in an Interim Storage Facility (ISF). This report documents consideration of an ISF for each of the waste processing options under consideration.

Rawlins, J.K.

1998-02-01T23:59:59.000Z

16

Faculty of Science Interim Dean  

E-Print Network [OSTI]

Faculty of Science Interim Dean: Prof DE Rawlings BScHons, PhD (Rhodes) CALENDAR 2013 PART 5 #12;Science 1 Table of Contents General Information........................................................................................................... 3 The Faculty of Science

Geldenhuys, Jaco

17

Characterization of interim reference shales  

SciTech Connect (OSTI)

Measurements have been made on the chemical and physical properties of two oil shales designated as interim reference oil shales by the Department of Energy. One oil shale is a Green River Formation, Parachute Creek Member, Mahogany Zone Colorado oil shale from the Anvil Points mine and the other is a Clegg Creek Member, New Albany shale from Kentucky. Material balance Fischer assays, kerogen concentrates, carbon aromaticities, thermal properties, and bulk mineralogic properties have been determined for the oil shales. The measured properties of the interim reference shales are comparable to results obtained from previous studies on similar shales. The western interim reference shale has a low carbon aromaticity, high Fischer assay conversion to oil, and a dominant carbonate mineralogy. The eastern interim reference shale has a high carbon aromaticity, low Fischer assay conversion to oil, and a dominant silicate mineralogy. Chemical and physical properties, including ASTM distillations, have been determined for shale oils produced from the interim reference shales. The distillation data were used in conjunction with API correlations to calculate a large number of shale oil properties that are required for computer models such as ASPEN. The experimental determination of many of the shale oil properties was beyond the scope of this study. Therefore, direct comparison between calculated and measured values of many properties could not be made. However, molecular weights of the shale oils were measured. In this case, there was poor agreement between measured molecular weights and those calculated from API and other published correlations. 23 refs., 12 figs., 15 tabs.

Miknis, F.P.; Sullivan, S.; Mason, G.

1986-03-01T23:59:59.000Z

18

OCTOBER/NOVEMBER 2003 ICMEs: ACE/EPAM SOLAR ENERGETIC PARTICLE OBSERVATIONS  

E-Print Network [OSTI]

1 OCTOBER/NOVEMBER 2003 ICMEs: ACE/EPAM SOLAR ENERGETIC PARTICLE OBSERVATIONS O. E. Malandraki1 Bell Laboratories, Lucent Technologies, Murray Hill, New Jersey, USA 5 NJ Institute of Technology, Center for Solar-Terrestrial Research, Newark, New Jersey, USA #12;2 Abstract In late October and early

19

ST. LOUIS AIRPORT/ HAZELWOOD INTERIM  

E-Print Network [OSTI]

International Airport County: St. Louis County Other Names: Hazelwood Interim Storage & Vicinity, Latty Avenue radioactively-contaminated sites are part of the Formerly Utilized Sites Remedial Action Program (FUSRAP the Formerly Utilized Site Remedial Action Program (FUSRAP). Site information and updates #12;can be found

20

Burn site groundwater interim measures work plan.  

SciTech Connect (OSTI)

This Work Plan identifies and outlines interim measures to address nitrate contamination in groundwater at the Burn Site, Sandia National Laboratories/New Mexico. The New Mexico Environment Department has required implementation of interim measures for nitrate-contaminated groundwater at the Burn Site. The purpose of interim measures is to prevent human or environmental exposure to nitrate-contaminated groundwater originating from the Burn Site. This Work Plan details a summary of current information about the Burn Site, interim measures activities for stabilization, and project management responsibilities to accomplish this purpose.

Witt, Jonathan L. (North Wind, Inc., Idaho Falls, ID); Hall, Kevin A. (North Wind, Inc., Idaho Falls, ID)

2005-05-01T23:59:59.000Z

Note: This page contains sample records for the topic "icm interim corrective" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


21

Vehicle Technologies Office Merit Review 2014: ICME Guided Development of Advanced Cast Aluminum Alloys For Automotive Engine Applications  

Broader source: Energy.gov [DOE]

Presentation given by Ford at 2014 DOE Hydrogen and Fuel Cells Program and Vehicle Technologies Office Annual Merit Review and Peer Evaluation Meeting about ICME guided development of advanced cast...

22

Tritium APEX Interim Report November, 1999  

E-Print Network [OSTI]

Tritium APEX Interim Report November, 1999 16-1 CHAPTER 16: TRITIUM Contributors Lead Author: Dai Kai Sze #12;Tritium APEX Interim Report November, 1999 16-2 16. TRITIUM 16.1 Design constraints Tritium recovery and containment are some of the key issues associated with breeding blanket design

California at Los Angeles, University of

23

UC SANTA BARBARA POLICY AND PROCEDURE Interim Food Service Policy  

E-Print Network [OSTI]

UC SANTA BARBARA POLICY AND PROCEDURE Interim Food Service Policy Contact: Environmental Health & Safety or Housing and Auxiliary Services Supersedes: Food Services Interim Policy 6005, February 2001 Technical Update: June 2010 Pages: 2 Interim Food Service Policy I. Scope The Interim Food Service Policy

Bigelow, Stephen

24

Optimization Using Metamodeling in the Context of Integrated Computational Materials Engineering (ICME)  

SciTech Connect (OSTI)

Predictive Design Technologies, LLC (PDT) proposed to employ Integrated Computational Materials Engineering (ICME) tools to help the manufacturing industry in the United States regain the competitive advantage in the global economy. ICME uses computational materials science tools within a holistic system in order to accelerate materials development, improve design optimization, and unify design and manufacturing. With the advent of accurate modeling and simulation along with significant increases in high performance computing (HPC) power, virtual design and manufacturing using ICME tools provide the means to reduce product development time and cost by alleviating costly trial-and-error physical design iterations while improving overall quality and manufacturing efficiency. To reduce the computational cost necessary for the large-scale HPC simulations and to make the methodology accessible for small and medium-sized manufacturers (SMMs), metamodels are employed. Metamodels are approximate models (functional relationships between input and output variables) that can reduce the simulation times by one to two orders of magnitude. In Phase I, PDT, partnered with Mississippi State University (MSU), demonstrated the feasibility of the proposed methodology by employing MSU?s internal state variable (ISV) plasticity-damage model with the help of metamodels to optimize the microstructure-process-property-cost for tube manufacturing processes used by Plymouth Tube Company (PTC), which involves complicated temperature and mechanical loading histories. PDT quantified the microstructure-property relationships for PTC?s SAE J525 electric resistance-welded cold drawn low carbon hydraulic 1010 steel tube manufacturing processes at seven different material states and calibrated the ISV plasticity material parameters to fit experimental tensile stress-strain curves. PDT successfully performed large scale finite element (FE) simulations in an HPC environment using the ISV plasticity model in Abaqus FE analyses of the tube forming, sizing, drawing, welding, and normalizing processes. The simulation results coupled with the manufacturing cost data were used to develop prototype metamodeling (quick response) codes which could be used to predict and optimize the microstructure-process-property-cost relationships. The developed ICME metamodeling toolkits are flexible enough to be applied to other manufacturing processes (e.g. forging, forming, casting, extrusion, rolling, stamping, and welding/joining) and metamodeling codes can run on laptop computers. Based on the work completed in Phase I, in Phase II, PDT proposes to continue to refine the ISV model by correlating and incorporating the uncertainties in the microstructure, mechanical testing, and modeling. Following the model refinement, FE analyses will be simulated and will provide even more realistic predictions as they include an appropriate window of uncertainty. Using the HPC output (FE analyses) as input, the quick-response metamodel codes will more accurately predict and optimize the microstructure-process-property-cost relationships. Furthermore, PDT propose to employ the ICME metamodeling toolkits to help develop a new tube product using entirely new high strength steel. The modeling of the high strength steel manufacturing process will replace the costly and time consuming trial-and-error methods that were used in the tubing industry previously. This simulation-based process prototyping will greatly benefit our industrial partners by opening up new market spaces due to new products with greater capabilities.

Hammi, Youssef; Horstemeyer, Mark F; Wang, Paul; David, Francis; Carino, Ricolindo

2013-11-18T23:59:59.000Z

25

Kinematics of ICMEs/shocks: blast wave reconstruction using type II emissions  

E-Print Network [OSTI]

We present a physical methodology to reconstruct the trajectory of interplanetary shocks using type II radio emission data. This technique calculates the shock trajectory assuming that the disturbance propagates as a blast wave in the interplanetary medium. We applied this Blast Wave Reconstruction (BWR) technique to analyze eight fast Earth-directed ICMEs/shocks associated with type II emissions. The technique deduces a shock trajectory that reproduces the type II frequency drifts, and calculates shock onset speed, shock transit time and shock speed at 1~AU. There were good agreements comparing the BWR results with the type II spectra, with data from coronagraph images, {\\it in situ} measurements, and interplanetary scintillation (IPS) observations. Perturbations on the type II data affect the accuracy of the BWR technique. This methodology could be applied to track interplanetary shocks causing TII emissions in real-time, to predict the shock arrival time and shock speed at 1~AU.

Corona-Romero, P; Aguilar-Rodriguez, E; de-la-Luz, V; Mejia-Ambriz, J C

2015-01-01T23:59:59.000Z

26

INTERIM SEXUAL AND GENDER-BASED HARASSMENT POLICY AND PROCEDURES  

E-Print Network [OSTI]

8/7/14 INTERIM SEXUAL AND GENDER-BASED HARASSMENT POLICY AND PROCEDURES FOR THE FACULTY OF ARTS Relationships Between Staff IV. Interim Procedures for Implementing Interim Sexual and Gender-Based Harassment Policy Including for Discipline A. Introduction B. Requests for Information and Advice C. Procedures

Paulsson, Johan

27

Design review report FFTF interim storage cask  

SciTech Connect (OSTI)

Final Design Review Report for the FFTF Interim Storage Cask. The Interim Storage Cask (ISC) will be used for long term above ground dry storage of FFTF irradiated fuel in Core Component Containers (CCC)s. The CCC has been designed and will house assemblies that have been sodium washed in the IEM Cell. The Solid Waste Cask (SWC) will transfer a full CCC from the IEM Cell to the RSB Cask Loading Station where the ISC will be located to receive it. Once the loaded ISC has been sealed at the RSB Cask Loading Station, it will be transferred by facility crane to the DSWC Transporter. After the ISC has been transferred to the Interim Storage Area (ISA), which is yet to be designed, a mobile crane will be used to place the ISC in its final storage location.

Scott, P.L.

1995-01-03T23:59:59.000Z

28

CSUF A.S. Bylaws Interim UPS 100.001 Interim UPS 100.001 Cover Page  

E-Print Network [OSTI]

CSUF A.S. Bylaws ­ Interim UPS 100.001 Interim UPS 100.001 Cover Page Effective Date: 1-2-13 UPS 100.001 ACADEMIC SENATE BYLAWS Interim UPS 100.001 includes sections moved from UPS 100 faculty in a special election held spring 2011 (ASD 11-64). UPS 100.001 (BYLAWS) to be edited

de Lijser, Peter

29

340 waste handling facility interim safety basis  

SciTech Connect (OSTI)

This document presents an interim safety basis for the 340 Waste Handling Facility classifying the 340 Facility as a Hazard Category 3 facility. The hazard analysis quantifies the operating safety envelop for this facility and demonstrates that the facility can be operated without a significant threat to onsite or offsite people.

VAIL, T.S.

1999-04-01T23:59:59.000Z

30

340 Waste handling facility interim safety basis  

SciTech Connect (OSTI)

This document presents an interim safety basis for the 340 Waste Handling Facility classifying the 340 Facility as a Hazard Category 3 facility. The hazard analysis quantifies the operating safety envelop for this facility and demonstrates that the facility can be operated without a significant threat to onsite or offsite people.

Stordeur, R.T.

1996-10-04T23:59:59.000Z

31

Graduate School of Journalism Interim Grievance Procedures  

E-Print Network [OSTI]

Graduate School of Journalism Interim Grievance Procedures Introduction The following procedures the Dean to conduct a hearing under the formal grievance procedures described in this statement. Those procedures, like the procedures of other schools, provide for a final appeal to the University Provost

Qian, Ning

32

Interim Process Agreement Proposal June 3, 2003  

E-Print Network [OSTI]

Interim Process Agreement Proposal June 3, 2003 Overview For the near term, the Columbia Basin Fish) return to the planning and budget management process patterned after the 1996-2001 Bonneville Power implementation of the Fish and Wildlife Program (Program) through a quarterly review process, 3) establishing

33

Corrective Action  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Corrective Action Individual Permit: Corrective Action Certifications If confirmation monitoring sample results demonstrate that one or more TALs are exceeded at a Site, the...

34

Heating of Heavy Ions by Interplanetary Coronal Mass Ejection (ICME) Driven Collisionless Shocks  

E-Print Network [OSTI]

Shock heating and particle acceleration processes are some of the most fundamental physical phenomena of plasma physics with countless applications in laboratory physics, space physics, and astrophysics. This study is motivated by previous observations of non-thermal heating of heavy ions in astrophysical shocks (Korreck et al. 2004). Here, we focus on shocks driven by Interplanetary Coronal Mass Ejections (ICMEs) which heat the solar wind and accelerate particles. This study focuses specifically on the heating of heavy ions caused by these shocks. Previous studies have focused only on the two dynamically dominant species, H+ and He2+ . This study utilizes thermal properties measured by the Solar Wind Ion Composition Spectrometer (SWICS) aboard the Advanced Composition Explorer (ACE) spacecraft to examine heavy ion heating. This instrument provides data for many heavy ions not previously available for detailed study, such as Oxygen (O6+, O7+), Carbon (C5+, C6+), and Iron (Fe10+). The ion heating is found to depend critically on the upstream plasma

K. E. Korreck; T. H. Zurbuchen; S. T. Lepri; J. M . Raines

2006-12-28T23:59:59.000Z

35

Interim Vice President/CFO Administration and Finance  

E-Print Network [OSTI]

Interim Vice President/CFO Administration and Finance Stephen G. Garcia Associate Vice President Project Management Tinnah Medina Director Facilities Operations Willem van der Pol Manager Finance & Admin

de Lijser, Peter

36

Comments of NRDC on Department of Energy Interim Final Rule:...  

Broader source: Energy.gov (indexed) [DOE]

NRDC's comments on Interim Final Rule: Energy Conservation for New Federal Commercial and Multi-Family High-Rise Residential Buildings and New Federal Low-Rise Residential...

37

RCRA corrective action definitions under Subpart F and proposed Subpart S. RCRA Information Brief  

SciTech Connect (OSTI)

If EPA or the authorized State determines there has been a release of a hazardous waste or hazardous waste constituent at an interim status facility, RCRA Section 3008(h)(1) authorizes EPA or the authorized State to issue an administrative order requiring corrective action or other measures. There are no regulations specifically addressing corrective action orders under Subpart F. However, while an interim status facility is seeking a RCRA permit, the facility is required by 40 CFR 265 Subpart F to monitor ground water and report the results of this monitoring program to the regulatory agency. If a release of a hazardous waste or hazardous waste constituent occurs, the facility may be issued a RCRA Section 3008(h) Order to conduct corrective action. While the proposed Subpart S regulations apply specifically to SWMUs at permitted TSDFs, EPA intends to use similar corrective action requirements at interim status facilities where there has been a release of a hazardous waste or hazardous waste constituent. The specific requirements for corrective action at an interim status facility will be specified in a RCRA Section 3008(h) Order. Alternatively, EPA may compel corrective action under proposed Subpart S through a permit Schedule of Compliance, especially if the permit is expected to be issued in the near term. This information Brief discusses the terminology used in the two corrective action programs and discusses both the proposed Subpart S rule and the final CAMU and TU rule.

Not Available

1994-03-01T23:59:59.000Z

38

Materials Considerations and Data Base APEX Interim Report November, 1999  

E-Print Network [OSTI]

Materials Considerations and Data Base APEX Interim Report November, 1999 13-1 CHAPTER 13: MATERIALS CONSIDERATIONS AND DATA BASE Contributors Lead Author: S.J. Zinkle S. Majumdar N.M. Ghoniem S. Sharafat. #12;Materials Considerations and Data Base APEX Interim Report November, 1999 13-2 13. MATERIALS

California at Los Angeles, University of

39

Interim Solution 2.0 Files  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr May JunDatastreamsmmcrcalgovInstrumentsruc DocumentationP-SeriesFlickrinformation for and NovelFEG-SEM with0,InterconnectingInterim

40

PROJECT W-551 INTERIM PRETREATMENT SYSTEM PRECONCEPTUAL CANDIDATE TECHNOLOGY DESCRIPTIONS  

SciTech Connect (OSTI)

The Office of River Protection (ORP) has authorized a study to recommend and select options for interim pretreatment of tank waste and support Waste Treatment Plant (WTP) low activity waste (LAW) operations prior to startup of all the WTP facilities. The Interim Pretreatment System (IPS) is to be a moderately sized system which separates entrained solids and 137Cs from tank waste for an interim time period while WTP high level waste vitrification and pretreatment facilities are completed. This study's objective is to prepare pre-conceptual technology descriptions that expand the technical detail for selected solid and cesium separation technologies. This revision includes information on additional feed tanks.

MAY TH

2008-08-12T23:59:59.000Z

Note: This page contains sample records for the topic "icm interim corrective" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


41

Electroweak Corrections  

E-Print Network [OSTI]

The test of the electroweak corrections has played a major role in providing evidence for the gauge and the Higgs sectors of the Standard Model. At the same time the consideration of the electroweak corrections has given significant indirect information on the masses of the top and the Higgs boson before their discoveries and important orientation/constraints on the searches for new physics, still highly valuable in the present situation.The progression of these contributions is reviewed.

Barbieri, Riccardo

2015-01-01T23:59:59.000Z

42

AGR-1 Data Qualification Interim Report  

SciTech Connect (OSTI)

Projects for the very-high-temperature reactor (VHTR) program provide data in support of Nuclear Regulatory Commission licensing of the VHTR. Fuel and materials to be used in the reactor are tested and characterized to quantify performance in high temperature and high fluence environments. The VHTR Program has established the NGNP Data Management and Analysis System (NDMAS) to ensure that VHTR data are (1) qualified for use, (2) stored in a readily accessible electronic form, and (3) analyzed to extract useful results. This document focuses on the first NDMAS objective. It describes the data streams associated with the first Advanced Gas Reactor (AGR-1) experiment, the processing of these data within NDMAS, and reports the interim FY09 qualification status of the AGR-1 data to date. Data qualification activities within NDMAS for specific types of data are determined by the data qualification category, which is assigned by the data generator, and include: (1) capture testing, to confirm that the data stored within NDMAS are identical to the raw data supplied, (2) accuracy testing, to confirm that the data are an accurate representation of the system or object being measured, and (3) documentation that the data were collected under an NQA-1 or equivalent QA program. The interim qualification status of the following four data streams is reported in this document: (1) fuel fabrication data, (2) fuel irradiation data, (3) fission product monitoring system (FPMS) data, and (4) Advanced Test Reactor (ATR) operating conditions data. A final report giving the NDMAS qualification status of all AGR-1 data (including cycle 145A) is planned for February 2010.

Machael Abbott

2009-08-01T23:59:59.000Z

43

area interim storage: Topics by E-print Network  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Spot Height Northern British Columbia, University of 3 In Situ Bioremediation Interim Remedial Action Report, Test Area North, Operable Unit 1-07B CiteSeer Summary: This...

44

Fire Hazards Analysis for the 200 Area Interim Storage Area  

SciTech Connect (OSTI)

This documents the Fire Hazards Analysis (FHA) for the 200 Area Interim Storage Area. The Interim Storage Cask, Rad-Vault, and NAC-1 Cask are analyzed for fire hazards and the 200 Area Interim Storage Area is assessed according to HNF-PRO-350 and the objectives of DOE Order 5480 7A. This FHA addresses the potential fire hazards associated with the Interim Storage Area (ISA) facility in accordance with the requirements of DOE Order 5480 7A. It is intended to assess the risk from fire to ensure there are no undue fire hazards to site personnel and the public and to ensure property damage potential from fire is within acceptable limits. This FHA will be in the form of a graded approach commensurate with the complexity of the structure or area and the associated fire hazards.

JOHNSON, D.M.

2000-01-06T23:59:59.000Z

45

Electromagnetically Restrained Lithium Blanket APEX Interim Report November, 1999  

E-Print Network [OSTI]

to avoid corrosion or fire. Lithium's high electrical conductivity may possibly permit efficient, compactElectromagnetically Restrained Lithium Blanket APEX Interim Report November, 1999 6-1 CHAPTER 6: ELECTROMAGNETICALLY RESTRAINED LITHIUM BLANKET Contributors Robert Woolley #12;Electromagnetically Restrained Lithium

California at Los Angeles, University of

46

TANK FARM INTERIM SURFACE BARRIER MATERIALS AND RUNOFF ALTERNATIVES STUDY  

SciTech Connect (OSTI)

This report identifies candidate materials and concepts for interim surface barriers in the single-shell tank farms. An analysis of these materials for application to the TY tank farm is also provided.

HOLM MJ

2009-06-25T23:59:59.000Z

47

Stability of Biodiesel and Biodiesel Blends: Interim Report  

SciTech Connect (OSTI)

This is an interim report for a study of biodiesel oxidative stability. It describes characterization and accelerated stability test results for 19 B100 samples and six diesel fuels.

McCormick, R. L.; Alleman, T. L.; Waynick, J. A.; Westbrook, S. R.; Porter, S.

2006-04-01T23:59:59.000Z

48

Final Environmental Impact Statement Safe Interim Storage Of...  

Broader source: Energy.gov (indexed) [DOE]

transfer actions can contribute to the interim stabilization of older single-shell tanks to help reduce the risk of leaks from those tanks. Many of the single-shell tanks have...

49

SAHP Faculty Assembly Resolution 04-01 Commendation of Performance of Jimmy Cairo, Ph.D. as Interim Dean  

E-Print Network [OSTI]

SAHP Faculty Assembly Resolution 04-01 Commendation of Performance of Jimmy Cairo, Ph.D. as Interim the performance of Jimmy Cairo, Ph.D. while he has served as Interim Dean for the SAHP. While serving as Interim

50

Evaluation of groundwater flow and transport at the Shoal underground nuclear test: An interim report  

SciTech Connect (OSTI)

Since 1962, all United States nuclear tests have been conducted underground. A consequence of this testing has been the deposition of large amounts of radioactive materials in the subsurface, sometimes in direct contact with groundwater. The majority of this testing occurred on the Nevada Test Site, but a limited number of experiments were conducted in other locations. One of these is the subject of this report, the Project Shoal Area (PSA), located about 50 km southeast of Fallon, Nevada. The Shoal test consisted of a 12-kiloton-yield nuclear detonation which occurred on October 26, 1963. Project Shoal was part of studies to enhance seismic detection of underground nuclear tests, in particular, in active earthquake areas. Characterization of groundwater contamination at the Project Shoal Area is being conducted by the US Department of Energy (DOE) under the Federal Facility Agreement and Consent Order (FFACO) with the State of Nevada Department of Environmental Protection and the US Department of Defense (DOD). This order prescribes a Corrective Action Strategy (Appendix VI), which, as applied to underground nuclear tests, involves preparing a Corrective Action Investigation Plan (CAIP), Corrective Action Decision Document (CADD), Corrective Action Plan, and Closure Report. The scope of the CAIP is flow and transport modeling to establish contaminant boundaries that are protective of human health and the environment. This interim report describes the current status of the flow and transport modeling for the PSA.

Pohll, G.; Chapman, J.; Hassan, A.; Papelis, C.; Andricevic, R.; Shirley, C.

1998-07-01T23:59:59.000Z

51

Single-shell tank interim stabilization project plan  

SciTech Connect (OSTI)

Solid and liquid radioactive waste continues to be stored in 149 single-shell tanks at the Hanford Site. To date, 119 tanks have had most of the pumpable liquid removed by interim stabilization. Thirty tanks remain to be stabilized. One of these tanks (C-106) will be stabilized by retrieval of the tank contents. The remaining 29 tanks will be interim stabilized by saltwell pumping. In the summer of 1997, the US Department of Energy (DOE) placed a moratorium on the startup of additional saltwell pumping systems because of funding constraints and proposed modifications to the Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) milestones to the Washington State Department of Ecology (Ecology). In a letter dated February 10, 1998, Final Determination Pursuant to Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) in the Matter of the Disapproval of the DOE`s Change Control Form M-41-97-01 (Fitzsimmons 1998), Ecology disapproved the DOE Change Control Form M-41-97-01. In response, Fluor Daniel Hanford, Inc. (FDH) directed Lockheed Martin Hanford Corporation (LNMC) to initiate development of a project plan in a letter dated February 25, 1998, Direction for Development of an Aggressive Single-Shell Tank (SST) Interim Stabilization Completion Project Plan in Support of Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement). In a letter dated March 2, 1998, Request for an Aggressive Single-Shell Tank (SST) Interim Stabilization Completion Project Plan, the DOE reaffirmed the need for an aggressive SST interim stabilization completion project plan to support a finalized Tri-Party Agreement Milestone M-41 recovery plan. This project plan establishes the management framework for conduct of the TWRS Single-Shell Tank Interim Stabilization completion program. Specifically, this plan defines the mission needs and requirements; technical objectives and approach; organizational structure, roles, responsibilities, and interfaces; and operational methods. The plan is based on realistic assumptions and addresses three separate funding scenarios.

Ross, W.E.

1998-03-27T23:59:59.000Z

52

Effectiveness Monitoring Report, MWMF Tritium Phytoremediation Interim Measures.  

SciTech Connect (OSTI)

This report describes and presents the results of monitoring activities during irrigation operations for the calendar year 2001 of the MWMF Interim Measures Tritium Phytoremediation Project. The purpose of this effectiveness monitoring report is to provide the information on instrument performance, analysis of CY2001 measurements, and critical relationships needed to manage irrigation operations, estimate efficiency and validate the water and tritium balance model.

Hitchcock, Dan; Blake, John, I.

2003-02-10T23:59:59.000Z

53

Public Interest Energy Research (PIER) Program INTERIM REPORT  

E-Print Network [OSTI]

Public Interest Energy Research (PIER) Program INTERIM REPORT SOLAR REFLECTANCES OF ROOFS: California Energy Commission Heather Bird Contract Manager Virginia Lew Office Manager Energy Efficiency/Agricultural/Water EndUse Energy Efficiency · Renewable Energy Technologies · Transportation Solar Reflectances

54

Division of Residential and Campus Communities Review Interim Report  

E-Print Network [OSTI]

Division of Residential and Campus Communities Review Interim Report December 2013 As stressed in the University's strategic plan ANU by 2020, the residential experience is a key aspect of the holistic ANU experience of all students by providing a richer residential experience for on-campus students and more

Botea, Adi

55

SLIGHTLY IRRADIATED FUEL (SIF) INTERIM DISPOSITION PROJECT  

SciTech Connect (OSTI)

CH2M HILL Plateau Remediation Company (CH2M HILL PRC) is proud to submit the Slightly Irradiated Fuel (SIF) Interim Disposition Project for consideration by the Project Management Institute as Project of the Year for 2010. The SIF Project was a set of six interrelated sub-projects that delivered unique stand-alone outcomes, which, when integrated, provided a comprehensive and compliant system for storing high risk special nuclear materials. The scope of the six sub-projects included the design, construction, testing, and turnover of the facilities and equipment, which would provide safe, secure, and compliant Special Nuclear Material (SNM) storage capabilities for the SIF material. The project encompassed a broad range of activities, including the following: Five buildings/structures removed, relocated, or built; Two buildings renovated; Structural barriers, fencing, and heavy gates installed; New roadways and parking lots built; Multiple detection and assessment systems installed; New and expanded communication systems developed; Multimedia recording devices added; and A new control room to monitor all materials and systems built. Project challenges were numerous and included the following: An aggressive 17-month schedule to support the high-profile Plutonium Finishing Plant (PFP) decommissioning; Company/contractor changeovers that affected each and every project team member; Project requirements that continually evolved during design and construction due to the performance- and outcome-based nature ofthe security objectives; and Restrictions imposed on all communications due to the sensitive nature of the projects In spite of the significant challenges, the project was delivered on schedule and $2 million under budget, which became a special source of pride that bonded the team. For years, the SIF had been stored at the central Hanford PFP. Because of the weapons-grade piutonium produced and stored there, the PFP had some of the tightest security on the Hanford nuclear reservation. Workers had to pass through metal detectors when they arrived at the plant and materials leaving the plant had to be scanned for security reasons. Whereas other high-security nuclear materials were shipped from the PFP to Savannah River, S.C. as part ofa Department of Energy (DOE) program to consolidate weapons-grade plutonium, it was determined that the SIF should remain onsite pending disposition to a national repository. Nevertheless, the SIF still requires a high level of security that the PFP complex has always provided. With the 60-year PFP mission of producing and storing plutonium concluded, the environmental cleanup plans for Hanford call for the demolition of the 63-building PFP complex. Consequently, if the SIF remained at PFP it not only would have interfered with the environmental cleanup plans, but would have required $100 million in facility upgrades to meet increased national security requirements imposed after the 9/11 terrorist attacks. A new smaller and more cost-effective area was needed to store this material, which led to the SIF Project. Once the SIF project was successfully completed and the SIF was safely removed from PFP, the existing Protected Area at PFP could be removed, and demolition could proceed more quickly without being encumbered by restrictive security requirements that an active Protected Area requires. The lightened PFP security level brought by safely removing and storing the SIF would also yield lowered costs for deactivation and demolition, as well as reduce overall life-cycle costs.

NORTON SH

2010-02-23T23:59:59.000Z

56

Plutonium Finishing Plant. Interim plutonium stabilization engineering study  

SciTech Connect (OSTI)

This report provides the results of an engineering study that evaluated the available technologies for stabilizing the plutonium stored at the Plutonium Finishing Plant located at the hanford Site in southeastern Washington. Further processing of the plutonium may be required to prepare the plutonium for interim (<50 years) storage. Specifically this document provides the current plutonium inventory and characterization, the initial screening process, and the process descriptions and flowsheets of the technologies that passed the initial screening. The conclusions and recommendations also are provided. The information contained in this report will be used to assist in the preparation of the environmental impact statement and to help decision makers determine which is the preferred technology to process the plutonium for interim storage.

Sevigny, G.J.; Gallucci, R.H.; Garrett, S.M.K.; Geeting, J.G.H.; Goheen, R.S.; Molton, P.M.; Templeton, K.J.; Villegas, A.J. [Pacific Northwest Lab., Richland, WA (United States); Nass, R. [Nuclear Fuel Services, Inc. (United States)

1995-08-01T23:59:59.000Z

57

105-H Reactor Interim Safe Storage Project Final Report  

SciTech Connect (OSTI)

The following information documents the decontamination and decommissioning of the 105-H Reactor facility, and placement of the reactor core into interim safe storage. The D&D of the facility included characterization, engineering, removal of hazardous and radiologically contaminated materials, equipment removal, decontamination, demolition of the structure, and restoration of the site. The ISS work also included construction of the safe storage enclosure, which required the installation of a new roofing system, power and lighting, a remote monitoring system, and ventilation components.

E.G. Ison

2008-11-08T23:59:59.000Z

58

Method of preparing nuclear wastes for tansportation and interim storage  

DOE Patents [OSTI]

Nuclear waste is formed into a substantially water-insoluble solid for temporary storage and transportation by mixing the calcined waste with at least 10 weight percent powdered anhydrous sodium silicate to form a mixture and subjecting the mixture to a high humidity environment for a period of time sufficient to form cementitious bonds by chemical reaction. The method is suitable for preparing an interim waste form from dried high level radioactive wastes.

Bandyopadhyay, Gautam (Naperville, IL); Galvin, Thomas M. (Darien, IL)

1984-01-01T23:59:59.000Z

59

Interim Storage of Hanford Spent Fuel & Associated Sludge  

SciTech Connect (OSTI)

The Hanford site is currently dealing with a number of types of Spent Nuclear Fuel. The route to interim dry storage for the various fuel types branches along two different paths. Fuel types such as metallic N reactor fuel and Shippingport Core 2 Blanket assemblies are being placed in approximately 4 m long canisters which are then stored in tubes below grade in a new canister storage building. Other fuels such as TRIGA{trademark} and Light Water Reactor fuel will be relocated and stored in stand-alone casks on a concrete pad. Varying degrees of sophistication are being applied with respect to the drying and/or evacuation of the fuel interim storage canisters depending on the reactivity of the fuel, the degree of damaged fuel and the previous storage environment. The characterization of sludge from the Hanford K Basins is nearly complete and canisters are being designed to store the sludge (including uranium particles from fuel element cleaning) on an interim basis.

MAKENAS, B.J.

2002-07-01T23:59:59.000Z

60

Report to Congress on Plan for Interim Storage of Spent Nuclear...  

Broader source: Energy.gov (indexed) [DOE]

Report to Congress on Plan for Interim Storage of Spent Nuclear Fuel from Decommissioned Reactors More Documents & Publications Information Request, "THE REPORT TO THE PRESIDENT...

Note: This page contains sample records for the topic "icm interim corrective" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


61

Management of corrective action wastes pursuant to proposed Subpart S  

SciTech Connect (OSTI)

Under Section 3004(u) of the Resource Conservation and Recovery Act (RCRA), owners/operators of permitted or interim status treatment, storage, and disposal facilities (TSDFs) are required to perform corrective action to address releases of hazardous waste or hazardous constituents from solid waste management units (SWMUs). On July 27, 1990, the Environmental Protection Agency (EPA) proposed specific corrective action requirements under Part 264, Subpart S of Title 40 of the code of Federal Regulations (CFR). One portion of this proposed rule, addressing requirements applicable to corrective action management units (CAMUs) and temporary units (TUs), was finalized on February 16, 1993 (58 FR 8658 et seq.). (CAMUs and TUs are RCRA waste management units that are specifically designated for the management of corrective action wastes). Portions of the proposed Subpart S rule that address processes for the investigation and cleanup of releases to environmental media have not yet been finalized. EPA and authorized State agencies, however, are currently using the investigation and cleanup procedures of the proposed rule as a framework for implementation of RCRA`s corrective action requirements. The performance of corrective action cleanup activities generates wastes that have to be characterized and managed in accordance with applicable RCRA requirements. This Information Brief describes these requirements. It is one of a series of information Briefs on RCRA Corrective Action.

Not Available

1995-02-01T23:59:59.000Z

62

Environmental Assessment and Finding of No Significant Impact: Interim Measures for the Mixed Waste Management Facility Groundwater at the Burial Ground Complex at the Savannah River Site  

SciTech Connect (OSTI)

The U. S. Department of Energy (DOE) prepared this environmental assessment (EA) to analyze the potential environmental impacts associated with the proposed interim measures for the Mixed Waste Management Facility (MW) groundwater at the Burial Ground Complex (BGC) at the Savannah River Site (SRS), located near Aiken, South Carolina. DOE proposes to install a small metal sheet pile dam to impound water around and over the BGC groundwater seepline. In addition, a drip irrigation system would be installed. Interim measures will also address the reduction of volatile organic compounds (VOCS) from ''hot-spot'' regions associated with the Southwest Plume Area (SWPA). This action is taken as an interim measure for the MWMF in cooperation with the South Carolina Department of Health and Environmental Control (SCDHEC) to reduce the amount of tritium seeping from the BGC southwest groundwater plume. The proposed action of this EA is being planned and would be implemented concurrent with a groundwater corrective action program under the Resource Conservation and Recovery Act (RCRA). On September 30, 1999, SCDHEC issued a modification to the SRS RCRA Part B permit that adds corrective action requirements for four plumes that are currently emanating from the BGC. One of those plumes is the southwest plume. The RCRA permit requires SRS to submit a corrective action plan (CAP) for the southwest plume by March 2000. The permit requires that the initial phase of the CAP prescribe a remedy that achieves a 70-percent reduction in the annual amount of tritium being released from the southwest plume area to Fourmile Branch, a nearby stream. Approval and actual implementation of the corrective measure in that CAP may take several years. As an interim measure, the actions described in this EA would manage the release of tritium from the southwest plume area until the final actions under the CAP can be implemented. This proposed action is expected to reduce the release of tritium from the southwest plume area to Fourmile Branch between 25 to 35 percent. If this proposed action is undertaken and its effectiveness is demonstrated, it may become a component of the final action in the CAP. This document was prepared in compliance with the National Environmental Policy Act (NEPA) of 1969, as amended; the requirements of the Council on Environmental Quality Regulations for Implementing NEPA (40 CFR 1500-1508); and the DOE Regulations for Implementing NEPA (10 CFR 1021). NEPA requires the assessment of environmental consequences of Federal actions that may affect the quality of the human environment. Based on the potential for impacts described herein, DOE will either publish a Finding of No Significant Impact (FONSI) or prepare an environmental impact statement (EM).

N /A

1999-12-08T23:59:59.000Z

63

TPX correction coil studies  

SciTech Connect (OSTI)

Error correction coils are planned for the TPX (Tokamak Plasma Experiment) in order to avoid error field induced locked modes and disruption. The FT (Fix Tokamak) code is used to evaluate the ability of these correction coils to remove islands caused by symmetry breaking magnetic field errors. The proposed correction coils are capable of correcting a variety of error fields.

Hanson, J.D.

1994-11-03T23:59:59.000Z

64

Green River Lake and Dam interim plan benefits ecosystem By John Hickey  

E-Print Network [OSTI]

11 Green River Lake and Dam interim plan benefits ecosystem By John Hickey Hydrologic Engineering that water is released from Green River Dam in Kentucky. In May 2006, the interim plan was approved shown that operation of Green River Dam can be changed in ways that improve ecosystems while continuing

US Army Corps of Engineers

65

Conceptual design report for immobilized high-level waste interim storage facility (Phase 1)  

SciTech Connect (OSTI)

The Hanford Site Canister Storage Building (CSB Bldg. 212H) will be utilized to interim store Phase 1 HLW products. Project W-464, Immobilized High-Level Waste Interim Storage, will procure an onsite transportation system and retrofit the CSB to accommodate the Phase 1 HLW products. The Conceptual Design Report establishes the Project W-464 technical and cost basis.

Burgard, K.C.

1998-04-09T23:59:59.000Z

66

Conceptual design report for immobilized high-level waste interim storage facility (Phase 1)  

SciTech Connect (OSTI)

The Hanford Site Canister Storage Building (CSB Bldg. 212H) will be utilized to interim store Phase 1 HLW products. Project W-464, Immobilized High-Level Waste Interim Storage, will procure an onsite transportation system and retrofit the CSB to accommodate the Phase 1 HLW products. The Conceptual Design Report establishes the Project W-464 technical and cost basis.

Burgard, K.C.

1998-06-02T23:59:59.000Z

67

June 8, 2006 15.7 ACTING OR INTERIM DEPARTMENT HEAD/DIVISION DIRECTOR ADDENDUM  

E-Print Network [OSTI]

June 8, 2006 15.7 ACTING OR INTERIM DEPARTMENT HEAD/DIVISION DIRECTOR ADDENDUM THIS ACTING OR INTERIM DEPARTMENT HEAD / DIVISION DIRECTOR ADDENDUM, hereinafter the "Addendum," is entered as a temporary or short-term replacement for his or her Department Head/Division Director, who is temporarily

68

PROJECT W-551 INTERIM PRETREATMENT SYSTEM TECHNOLOGY SELECTION SUMMARY DECISION REPORT AND RECOMMENDATION  

SciTech Connect (OSTI)

This report provides the conclusions of the tank farm interim pretreatment technology decision process. It documents the methodology, data, and results of the selection of cross-flow filtration and ion exchange technologies for implementation in project W-551, Interim Pretreatment System. This selection resulted from the evaluation of specific scope criteria using quantitative and qualitative analyses, group workshops, and technical expert personnel.

CONRAD EA

2008-08-12T23:59:59.000Z

69

Li2O Particulate Flow Concept, APPLE APEX Interim Report November, 1999  

E-Print Network [OSTI]

Li2O Particulate Flow Concept, APPLE APEX Interim Report November, 1999 9-1 CHAPTER 9: Li2O PARTICULATE FLOW CONCEPT ­ APPLE DESIGN Contributors Lead Author: Dai Kai Sze Dai Kai Sze, Zhanhe Wang (ANL Particulate Flow Concept, APPLE APEX Interim Report November, 1999 9-2 9. LI2O PARTICULATE FLOW CONCEPT

California at Los Angeles, University of

70

Fast Flux Test Facility interim examination and maintenance cell: Past, present, and future  

SciTech Connect (OSTI)

The Fast Flux Test Facility Interim Examination and Maintenance Cell was designed to perform interim examination and/or disassembly of experimental core components for final analysis elsewhere, as well as maintenance of sodium-wetted or neutron-activated internal reactor parts and plant support hardware. The Interim Examination and Maintenance Cell equipment developed and used for the first ten years of operation has been primarily devoted to the disassembly and examination of core component test assemblies. While no major reactor equipment has required remote repair or maintenance, the Interim Examina Examination and Maintenance Cell has served as the remote repair facility for its own in-cell equipment, and several innovative remote repairs have been accomplished. The Interim Examination and Maintenance Cell's demonstrated versatility has shown its capability to support a challenging future. 12 refs., 9 figs.

Vincent, J.R.

1990-09-01T23:59:59.000Z

71

Hanford low-level tank waste interim performance assessment  

SciTech Connect (OSTI)

The Hanford Low-Level Tank Waste Interim Performance Assessment examines the long-term environmental and human health effects associated with the disposal of the low-level fraction of the Hanford single and double-shell tank waste in the Hanford Site 200 East Area. This report was prepared as a good management practice to provide needed information about the relationship between the disposal system design and performance early in the disposal system project cycle. The calculations in this performance assessment show that the disposal of the low-level fraction can meet environmental and health performance objectives.

Mann, F.M.

1997-09-12T23:59:59.000Z

72

Hanford low-level tank waste interim performance assessment  

SciTech Connect (OSTI)

The Hanford Low-Level Tank Waste Interim Performance Assessment examines the long-term environmental and human health effects associated with the disposal of the low-level fraction of the Hanford single- and double-shell tank waste in the Hanford Site 200 East Area. This report was prepared as a good management practice to provide needed information about the relationship between the disposal system design and its performance as early as possible in the project cycle. The calculations in this performance assessment show that the disposal of the low-level fraction can meet environmental and health performance objectives.

Mann, F.M.

1996-09-16T23:59:59.000Z

73

US PRACTICE FOR INTERIM WET STORAGE OF RRSNF  

SciTech Connect (OSTI)

Aluminum research reactor spent nuclear fuel is currently being stored or is anticipated to be returned to the United States and stored at Department of Energy storage facilities at the Savannah River Site and the Idaho Nuclear Technology and Engineering Center. This paper summarizes the current practices to provide for continued safe interim wet storage in the U.S. Aluminum fuel stored in poor quality water is subject to aggressive corrosion attack and therefore water chemistry control systems are essential to maintain water quality. Fuel with minor breaches are safely stored directly in the basin. Fuel pieces and heavily damaged fuel is safely stored in isolation canisters.

Vinson, D.

2010-08-05T23:59:59.000Z

74

Interim Final Rule and Proposed Rule | Department of Energy  

Office of Environmental Management (EM)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr May Jun Jul(Summary) "of EnergyEnergyENERGY TAX POLICIES7.pdfFuel2007 | Department7 U.S. Department ofAboutWAPAInterimInterim

75

Corrective Action Management Units and Temporary Units. RCRA Information Brief  

SciTech Connect (OSTI)

On February 16, 1993 the EPA published a final rule that allows either the EPA Regional Administrator or the authorized State to designate areas as corrective action management units (CAMUs) at hazardous waste management facilities for the specific purpose of managing remediation waste that has been generated as part of the facility`s corrective action activities. According to the rule, placement of remediation wastes into or within a CAMU does not constitute land disposal of hazardous waste and is not subject to RCRA land disposal restrictions. In addition, waste disposal units located within CAMUs are not required to be designed in accordance with RCRA minimum technological requirements applicable to land disposal units. This Information Brief explains the advantages of a CAMU designation, defines a Temporary Unit (TU) and explains the advantages of a TU designation. The process for initiating a CAMU or TU designation is described for DOE sites and interim status facilities.

Not Available

1994-03-01T23:59:59.000Z

76

Realization of the German Concept for Interim Storage of Spent Nuclear Fuel - Current Situation and Prospects  

SciTech Connect (OSTI)

The German government has determined a phase out of nuclear power. With respect to the management of spent fuel it was decided to terminate transports to reprocessing plants by 2005 and to set up interim storage facilities on power plant sites. This paper gives an overview of the German concept for spent fuel management focused on the new on-site interim storage concept and the applied interim storage facilities. Since the end of the year 1998, the utilities have applied for permission of on-site interim storage in 13 storage facilities and 5 storage areas; one application for the interim storage facility Stade was withdrawn due to the planned final shut down of Stade nuclear power plant in autumn 2003. In 2001 and 2002, 3 on-site storage areas and 2 on-site storage facilities for spent fuel were licensed by the Federal Office for Radiation Protection (BfS). A main task in 2002 and 2003 has been the examination of the safety and security of the planned interim storage facilities and the verification of the licensing prerequisites. In the aftermath of September 11, 2001, BfS has also examined the attack with a big passenger airplane. Up to now, these aircraft crash analyses have been performed for three on-site interim storage facilities; the fundamental results will be presented. It is the objective of BfS to conclude the licensing procedures for the applied on-site interim storage facilities in 2003. With an assumed construction period for the storage buildings of about two years, the on-site interim storage facilities could then be available in the year 2005.

Thomauske, B. R.

2003-02-25T23:59:59.000Z

77

Radiation site cleanup regulation: An interim progress report  

SciTech Connect (OSTI)

On October 18 and 19, 1993, the 13 members of the National Advisory Council on Environmental Policy and Technology (NACEPT) Subcommittee on Radiation Site Cleanup Regulations met in Washington D.C. at the invitation of EPA. The Subcommittee discussed a variety of topics relevant to the cleanup of sites contaminated with radiation, and to the regulations which EPA will promulgate to establish cleanup levels for radioactive sites. This Interim Progress Report: condenses and summarizes the major themes, issues, and concerns brought up during the NACEPT Subcommittee meeting in October; Provides a brief description of current Agency thinking regarding each of the major topic areas discussed by the NACEPT Subcommittee; and Serves as a discussion guide for NACEPT Subcommittee members. Four major topics were discussed by the NACEPT Subcommittee members during their first meeting in October 1993: Common Themes; Risk (or Cleanup Levels and Risk Levels); Future Land Use and Local Statutes; and Site-Specific Public Involvement.

Not Available

1994-02-01T23:59:59.000Z

78

Waste Encapsulation and Storage Facility (WESF) Interim Status Closure Plan  

SciTech Connect (OSTI)

This document describes the planned activities and performance standards for closing the Waste Encapsulation and Storage Facility (WESF). WESF is located within the 225B Facility in the 200 East Area on the Hanford Facility. Although this document is prepared based on Title 40 Code of Federal Regulations (CFR), Part 265, Subpart G requirements, closure of the storage unit will comply with Washington Administrative Code (WAC) 173-303-610 regulations pursuant to Section 5.3 of the Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) Action Plan (Ecology et al. 1996). Because the intention is to clean close WESF, postclosure activities are not applicable to this interim status closure plan. To clean close the storage unit, it will be demonstrated that dangerous waste has not been left onsite at levels above the closure performance standard for removal and decontamination. If it is determined that clean closure is not possible or environmentally is impracticable, the interim status closure plan will be modified to address required postclosure activities. WESF stores cesium and strontium encapsulated salts. The encapsulated salts are stored in the pool cells or process cells located within 225B Facility. The dangerous waste is contained within a double containment system to preclude spills to the environment. In the unlikely event that a waste spill does occur outside the capsules, operating methods and administrative controls require that waste spills be cleaned up promptly and completely, and a notation made in the operating record. Because dangerous waste does not include source, special nuclear, and by-product material components of mixed waste, radionuclides are not within the scope of this documentation. The information on radionuclides is provided only for general knowledge.

SIMMONS, F.M.

2000-12-01T23:59:59.000Z

79

ICPP radioactive liquid and calcine waste technologies evaluation. Interim report  

SciTech Connect (OSTI)

The Department of Energy (DOE) has received spent nuclear fuel (SNF) at the Idaho Chemical Processing Plant (ICPP) for interim storage since 1951 and reprocessing since 1953. Until recently, the major activity of the ICPP has been the reprocessing of SNF to recover fissile uranium; however, changing world events have raised questions concerning the need to recover and recycle this material. In April 1992, DOE chose to discontinue reprocessing SNF for uranium recovery and shifted its focus toward the management and disposition of radioactive wastes accumulated through reprocessing activities. Currently, 1.8 million gallons of radioactive liquid wastes (1.5 million gallons of radioactive sodium-bearing liquid wastes and 0.3 million gallons of high-level liquid waste) and 3,800 cubic meters (m{sup 3}) of calcine waste are in inventory at the ICPP. Legal drivers and agreements exist obligating the INEL to develop, demonstrate, and implement technologies for safe and environmentally sound treatment and interim storage of radioactive liquid and calcine waste. Candidate treatment processes and waste forms are being evaluated using the Technology Evaluation and Analysis Methodology (TEAM) Model. This process allows decision makers to (1) identify optimum radioactive waste treatment and disposal form alternatives; (2) assess tradeoffs between various optimization criteria; (3) identify uncertainties in performance parameters; and (4) focus development efforts on options that best satisfy stakeholder concerns. The Systems Analysis technology evaluation presented in this document supports the DOE in selecting the most effective radioactive liquid and calcine waste management plan to implement in compliance with established regulations, court orders, and agreements.

Murphy, J.A.; Pincock, L.F.; Christiansen, I.N.

1994-06-01T23:59:59.000Z

80

King County Metro Transit Hybrid Articulated Transit Buses: Interim Evaluation Results  

SciTech Connect (OSTI)

Interim technical report compares and evaluates new diesel and diesel hybrid-electric articulated buses operated as part of the King County Metro Transit (KC Metro) fleet in Seattle, Washington.

Chandler, K.; Walkowicz, K.

2006-04-01T23:59:59.000Z

Note: This page contains sample records for the topic "icm interim corrective" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


81

Interim Report on Thermal Cycling Model Development for Representative Unisolable Piping Configurations (MRP-81)  

SciTech Connect (OSTI)

Thermal fatigue can lead to cracking in dead-ended branch lines attached to PWR primary coolant piping. This interim report describes the results of on-going research to provide an improved screening tool for identification of susceptible piping.

J. Keller, A. Bilanin

2002-11-30T23:59:59.000Z

82

TO: Deans, Directors and Department Heads FROM: Charles Eaton, Interim Controller and Director of Accounting  

E-Print Network [OSTI]

TO: Deans, Directors and Department Heads FROM: Charles Eaton, Interim Controller and Director in the current fiscal year. Purchase Requisitions: Purchases under $10,000 (Includes Corporate Express) June 11

Holsinger, Kent

83

Basis for Interim Operation for the K-Reactor in Cold Standby  

SciTech Connect (OSTI)

The Basis for Interim Operation (BIO) document for K Reactor in Cold Standby and the L- and P-Reactor Disassembly Basins was prepared in accordance with the draft DOE standard for BIO preparation (dated October 26, 1993).

Shedrow, B.

1998-10-19T23:59:59.000Z

84

Calculating Energy and Demand Retrofit Savings for Victoria High School: Interim Report  

E-Print Network [OSTI]

ESL-TR-92/12-03 Calculating Energy and Demand Retrofit Savings For Victoria High School Yue Liu, T. Agami Reddy, S. Katipamula and David E. Claridge. Interim Report Energy Systems Laboratory Texas A&M University College Station, TX 77843 December... 1992 Calculating Energy and Demand Retrofit Savings For Victoria High School Yue Liu, T. Agami Reddy, S. Katipamula and David E. Claridge. Interim Report Energy Systems Laboratory Texas A&M University College Station, TX 77843 December 1992 Abstract...

Liu, Y.; Reddy, T. A.; Katipamula, S.; Claridge, D. E.

1992-01-01T23:59:59.000Z

85

Corrections for Water Resources Engineering  

E-Print Network [OSTI]

Corrections for Water Resources Engineering (Fourth printing) By Larry W. Mays Corrections as of 4 subcritical flow ..." Chapter

Mays, Larry W.

86

Finding of no significant impact. Consolidation and interim storage of special nuclear material at Rocky Flats Environmental Technology Site  

SciTech Connect (OSTI)

The Department of Energy (DOE) has prepared an environmental assessment (EA), DOE/EA -- 1060, for the consolidation, processing, and interim storage of Category I and II special nuclear material (SNM) in Building 371 at the Rocky Flats Environmental Technology Site (hereinafter referred to as Rocky Flats or Site), Golden, Colorado. The scope of the EA included alternatives for interim storage including the no action alternative, the construction of a new facility for interim storage at Rocky Flats, and shipment to other DOE facilities for interim storage.

NONE

1995-06-01T23:59:59.000Z

87

Corrective Action Decision Document/Corrective Action Plan for Corrective Action Unit 447: Project Shoal Area, Subsurface, Nevada, Rev. No.: 3 with Errata Sheet  

SciTech Connect (OSTI)

This Corrective Action Decision Document/Corrective Action Plan (CADD/CAP) has been prepared for Corrective Action Unit (CAU) 447, Project Shoal Area (PSA)-Subsurface, Nevada, in accordance with the ''Federal Facility Agreement and Consent Order'' (FFACO) (1996). Corrective Action Unit 447 is located in the Sand Springs Mountains in Churchill County, Nevada, approximately 48 kilometers (30 miles) southeast of Fallon, Nevada. The CADD/CAP combines the decision document (CADD) with the Corrective Action Plan (CAP) and provides or references the specific information necessary to recommend corrective actions for CAU 447, as provided in the FFACO. Corrective Action Unit 447 consists of two corrective action sites (CASs): CAS 57-49-01, Emplacement Shaft, and CAS 57-57-001, Cavity. The emplacement shaft (CAS-57-49-01) was backfilled and plugged in 1996 and will not be evaluated further. The purpose of the CADD portion of the document (Section 1.0 to Section 4.0) is to identify and provide a rationale for the selection of a recommended corrective action alternative for the subsurface at PSA. To achieve this, the following tasks were required: (1) Develop corrective action objectives. (2) Identify corrective action alternative screening criteria. (3) Develop corrective action alternatives. (4) Perform detailed and comparative evaluations of the corrective action alternatives in relation to the corrective action objectives and screening criteria. (5) Recommend a preferred corrective action alternative for the subsurface at PSA. The original Corrective Action Investigation Plan (CAIP) for the PSA was approved in September 1996 and described a plan to drill and test four characterization wells, followed by flow and transport modeling (DOE/NV, 1996). The resultant drilling is described in a data report (DOE/NV, 1998e) and the data analysis and modeling in an interim modeling report (Pohll et al., 1998). After considering the results of the modeling effort, the U.S. Department of Energy (DOE) determined that the degree of uncertainty in transport predictions for PSA remained unacceptably large. As a result, a second CAIP was developed by DOE and approved by the Nevada Division of Environmental Protection (NDEP) in December 1998 (DOE/NV, 1998a). This plan prescribed a rigorous analysis of uncertainty in the Shoal model and quantification of methods of reducing uncertainty through data collection. This analysis is termed a Data Decision Analysis (Pohll et al., 1999a) and formed the basis for a second major characterization effort at PSA (Pohll et al., 1999b). The details for this second field effort are presented in an Addendum to the CAIP, which was approved by NDEP in April 1999 (DOE/NV, 1999a). Four additional characterization wells were drilled at PSA during summer and fall of 1999; details of the drilling and well installation are in IT Corporation (2000), with testing reported in Mihevc et al. (2000). A key component of the second field program was a tracer test between two of the new wells (Carroll et al., 2000; Reimus et al., 2003). Based on the potential exposure pathways, two corrective action objectives were identified for CAU 447: Prevent or mitigate exposure to groundwater contaminants of concern at concentrations exceeding regulatory maximum contaminant levels or risk-based levels; and Reduce the risk to human health and the environment to the extent practicable. Based on the review of existing data, the results of the modeling, future use, and current operations at PSA, the following alternatives have been developed for consideration at CAU 447: Alternative 1--No Further Action; Alternative 2--Proof-of-Concept and Monitoring with Institutional Controls; and Alternative 3--Contaminant Control. The corrective action alternatives were evaluated based on the approach outlined in the ''Focused Evaluation of Selected Remedial Alternatives for the Underground Test Area'' (DOE/NV, 1998b). Each alternative was assessed against nine evaluation criteria. These criteria include overall protection of human health and the environment;

Tim Echelard

2006-03-01T23:59:59.000Z

88

Interim measure work plan/design for Agra, Kansas.  

SciTech Connect (OSTI)

This Interim Measure Work Plan/Design (IMWP/D) is supplemental to the Argonne document Interim Measure Conceptual Design for Remediation of Source Area Contamination at Agra, Kansas. The IMWP/D includes information required by Kansas Department of Health and Environment (KDHE) Policy BER-RS-029, Policy and Scope of Work for Interim Measures. Specific to Policy BER-RS-029 is the requirement for several documents that will ensure that an adequate amount and type of data are collected for implementation of the IMWP/D and that data quality and safe conditions are prevailed. Such information is included in the IMWP/D as follows: Appendix A: Data Acquisition Plan--Design Testing Requirements; Appendix B: Basis of Design; Appendix C: Permits; Appendix D: Quality Assurance Project Plan; Appendix E: Health and Safety Plan; and Appendix F: Operations, Maintenance, and Monitoring Schedule. The proposed remedial technology for this project is the installation of five large-diameter boreholes (LDBs) in a source area that has been identified on the property formerly used for grain storage by the Commodity Credit Corporation of the U.S. Department of Agriculture (CCC/USDA). The goal of the LDB technology is the remediation of the source area by removal of mass quantities of contaminated soil from the vadose zone and treatment of any remaining contaminated soils that are adjacent to the source area to achieve a carbon tetrachloride concentration below 200 {micro}g/kg. Secondary to the soil remediation is the remediation of groundwater at and adjacent to the source areas. The LDB technology serves the following purposes: (1) The physical removal of contaminated soil from the identified source area. (2) Replacement of less permeable native materials (silty clay, clayey silt, and silty sand) with more permeable materials to facilitate the capture of volatilized contaminants in the vertical borehole. (3) Removal of contaminants volatilized by air sparging (AS) and extracted from the vadose zone by soil vapor extraction (SVE). (4) Volatilization of contaminants from portions of the affected aquifer that can be accessed from the former CCC/USDA property. The primary objective of the proposed removal action is removal of mass quantities of carbon tetrachloride from the vadose zone and treatment of any remaining contaminated soils that are adjacent to the source area, to achieve a carbon tetrachloride concentration below 200 {micro}g/kg. This objective will be the basis for evaluating system performance. The scope of action outlined in the IMWP/D is limited to the five treatment zones defined by the LDB/SVE/AS locations. Surrounding soils and groundwater will benefit; however, remedial benefits to groundwater will be limited to the area of influence associated with the five treatment zones. While treatment should be aggressive in the vicinity of the LDB locations, the heterogeneity, clay content, and low permeability of the soils will place inherent limits on the area of influence.

LaFreniere, L. M.; Environmental Science Division

2008-11-18T23:59:59.000Z

89

National Ignition Facility Cryogenic Target Systems Interim Management Plan  

SciTech Connect (OSTI)

Restricted availability of funding has had an adverse impact, unforeseen at the time of the original decision to projectize the National Ignition Facility (NIF) Cryogenic Target Handling Systems (NCTS) Program, on the planning and initiation of these efforts. The purpose of this document is to provide an interim project management plan describing the organizational structure and management processes currently in place for NCTS. Preparation of a Program Execution Plan (PEP) for NCTS has been initiated, and a current draft is provided as Attachment 1 to this document. The National Ignition Facility is a multi-megajoule laser facility being constructed at Lawrence Livermore National Laboratory (LLNL) by the National Nuclear Security Administration (NNSA) in the Department of Energy (DOE). Its primary mission is to support the Stockpile Stewardship Program (SSP) by performing experiments studying weapons physics, including fusion ignition. NIF also supports the missions of weapons effects, inertial fusion energy, and basic science in high-energy-density physics. NIF will be operated by LLNL under contract to the University of California (UC) as a national user facility. NIF is a low-hazard, radiological facility, and its operation will meet all applicable federal, state, and local Environmental Safety & Health (ES&H) requirements. The NCTS Interim Management Plan provides a summary of primary design criteria and functional requirements, current organizational structure, tracking and reporting procedures, and current planning estimates of project scope, cost, and schedule. The NIF Director controls the NIF Cryogenic Target Systems Interim Management Plan. Overall scope content and execution schedules for the High Energy Density Physics Campaign (SSP Campaign 10) are currently undergoing rebaselining and will be brought into alignment with resources expected to be available throughout the NNSA Future Years National Security Plan (FYNSP). The revised schedule for delivering this system will be decided at the national level, based on experiment campaign requirement dates that will be derived through this process. The current milestone date for achieving indirect-drive ignition on the NIF is December 2010. Maintaining this milestone requires that the cryogenic systems be complete and available for fielding experiments early enough that the planned experimental campaigns leading up to ignition can be carried out. The capability of performing non-ignition cryogenic experiments is currently required by March 2006, when the NIF's first cluster of beams is operational. Plans for cryogenic and non-cryogenic experiments on the NIF are contained in NNSA's Campaign 10 Program Plans for Ignition (MTE 10.1) and High Energy Density Sciences (MTE 10.2). As described in this document, the NCTS Program Manager is responsible for managing NIF Cryogenic Target Systems development, engineering, and deployment. Through the NIF Director, the NCTS Program Manager will put in place an appropriate Program Execution Plan (draft attached) at a later time consistent with the maturing and funding these efforts. The PEP will describe management methods for carrying out these activities.

Warner, B

2002-04-25T23:59:59.000Z

90

Laser correcting mirror  

DOE Patents [OSTI]

An improved laser correction mirror (10) for correcting aberrations in a laser beam wavefront having a rectangular mirror body (12) with a plurality of legs (14, 16, 18, 20, 22, 24, 26, 28) arranged into opposing pairs (34, 36, 38, 40) along the long sides (30, 32) of the mirror body (12). Vector force pairs (49, 50, 52, 54) are applied by adjustment mechanisms (42, 44, 46, 48) between members of the opposing pairs (34, 36, 38, 40) for bending a reflective surface 13 of the mirror body 12 into a shape defining a function which can be used to correct for comatic aberrations.

Sawicki, Richard H. (Danville, CA)

1994-01-01T23:59:59.000Z

91

Safe Advantage on Dry Interim Spent Nuclear Fuel Storage  

SciTech Connect (OSTI)

This paper aims to present the advantages of dry cask storage in comparison with the wet storage (cooling water pools) for SNF. When the nuclear fuel is removed from the core reactor, it is moved to a storage unit and it wait for a final destination. Generally, the spent nuclear fuel (SNF) remains inside water pools within the reactors facility for the radioactive activity decay. After some period of time in pools, SNF can be sent to a definitive deposition in a geological repository and handled as radioactive waste or to reprocessing facilities, or still, wait for a future solution. Meanwhile, SNF remains stored for a period of time in dry or wet facilities, depending on the method adopted by the nuclear power plant or other plans of the country. Interim storage, up to 20 years ago, was exclusively wet and if the nuclear facility had to be decommissioned another storage solution had to be found. At the present time, after a preliminary cooling of the SNF elements inside the water pool, the elements can be stored in dry facilities. This kind of storage does not need complex radiation monitoring and it is safer then wet one. Casks, either concrete or metallic, are safer, especially on occurrence of earthquakes, like that occurred at Kashiwazaki-Kariwa nuclear power plant, in Japan on July 16, 2007. (authors)

Romanato, L.S. [Centro Tecnologico da Marinha em S.Paulo, Brazilian Navy Technological Center, Sao Paulo (Brazil)

2008-07-01T23:59:59.000Z

92

Lamar Low-Level Jet Program Interim Report  

SciTech Connect (OSTI)

This interim report presents the results to date from the Lamar Low-Level Jet Program (LLLJP) that has been established as joint effort among the U.S. Department of Energy (DOE), the National Wind Technology Center (NWTC) of the National Renewable Energy Laboratory (NREL), and General Electric Wind Energy (GE Wind). The purpose of this project is to develop an understanding of the influence of nocturnal low-level jet streams on the inflow turbulence environment and the documenting of any potential operating impacts on current large wind turbines and the Low Wind Speed Turbine (LWST) designs of the future. A year's record of detailed nocturnal turbulence measurements has been collected from NREL instrumentation installed on the GE Wind 120-m tower in southeastern Colorado and supplemented with mean wind profile data collected using an acoustic wind profiler or SODAR (Sound Detection and Ranging). The analyses of measurements taken as part of a previous program conducted at the NWTC have been used to aid in the interpretation of the results of representative case studies of data collected from the GE Wind tower.

Kelley, N.; Shirazi, M.; Jager, D.; Wilde, S.; Adams, J.; Buhl, M.; Sullivan, P.; Patton, E.

2004-01-01T23:59:59.000Z

93

Corrective Action Program Guide  

Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

This Guide was developed to assist the Department of Energy (DOE) organizations and contractors in the development, implementation, and followup of corrective action programs utilizing the feedback and improvement core safety function within DOE's Integrated Safety Management System. This Guide outlines some of the basic principles, concepts, and lessons learned that DOE managers and contractors might consider when implementing corrective action programs based on their specific needs. Canceled by DOE G 414.1-2B. Does not cancel other directives.

2006-03-02T23:59:59.000Z

94

Wayne Interim Storage Site annual environmental report for calendar year 1991, Wayne, New Jersey. [Wayne Interim Storage Site  

SciTech Connect (OSTI)

This document describes the envirormental monitoring program at the Wayne Interim Storage Site (WISS) and surrounding area, implementation of the program, and monitoring results for 1991. Environmental monitoring of WISS and surrounding area began in 1984 when Congress added the site to the US Department of Energy's (DOE) Formerly Utilized Sites Remedial Action Program (FUSRAP). FUSRAP is a DOE program to decontaminate or otherwise control sites where residual radioactive materials remain from the early years of the nation's atomic energy program or from commercial operations causing conditions that Congress has authorized DOE to remedy. WISS is a National Priorities List site. The environmental monitoring program at WISS includes sampling networks for radon and thoron concentrations in air; external gamma radiation exposure; and radium-226, radium-228, thorium-232, and total uranium concentrations in surface water, sediment, and groundwater. Several nonradiological parameters are also measured in groundwater. Monitoring results are compared with applicable Environmental Protection Agency standards, DOE derived concentration guides, dose limits, and other requirements in DOE orders. Environmental standards are established to protect public health and the environment.

none,

1992-09-01T23:59:59.000Z

95

High Temperature Materials Interim Data Qualification Report FY 2011  

SciTech Connect (OSTI)

Projects for the very high temperature reactor (VHTR) Technology Development Office provide data in support of Nuclear Regulatory Commission licensing of the VHTR. Fuel and materials to be used in the reactor are tested and characterized to quantify performance in high temperature and high fluence environments. The VHTR program has established the Next Generation Nuclear Plant (NGNP) Data Management and Analysis System (NDMAS) to ensure that VHTR data are qualified for use, stored in a readily accessible electronic form, and analyzed to extract useful results. This document focuses on the first NDMAS objective. It describes the High Temperature Materials characterization data stream, the processing of these data within NDMAS, and reports the interim fiscal year (FY) 2011 qualification status of the data. Data qualification activities within NDMAS for specific types of data are determined by the data qualification category assigned by the data generator. The High Temperature Materials data are being collected under the Nuclear Quality Assurance (NQA)-1 guidelines and will be qualified data. For NQA-1 qualified data, the qualification activities include: (1) capture testing to confirm that the data stored within NDMAS are identical to the raw data supplied, (2) accuracy testing to confirm that the data are an accurate representation of the system or object being measured, and (3) documenting that the data were collected under an NQA-1 or equivalent Quality Assurance program. Currently, data from seven test series within the High Temperature Materials data stream have been entered into the NDMAS vault, including tensile tests, creep tests, and cyclic tests. Of the 5,603,682 records currently in the vault, 4,480,444 have been capture passed, and capture testing is in process for the remaining 1,123,238.

Nancy Lybeck

2011-08-01T23:59:59.000Z

96

Idaho Waste Vitrification Facilities Project Vitrified Waste Interim Storage Facility  

SciTech Connect (OSTI)

This feasibility study report presents a draft design of the Vitrified Waste Interim Storage Facility (VWISF), which is one of three subprojects of the Idaho Waste Vitrification Facilities (IWVF) project. The primary goal of the IWVF project is to design and construct a treatment process system that will vitrify the sodium-bearing waste (SBW) to a final waste form. The project will consist of three subprojects that include the Waste Collection Tanks Facility, the Waste Vitrification Facility (WVF), and the VWISF. The Waste Collection Tanks Facility will provide for waste collection, feed mixing, and surge storage for SBW and newly generated liquid waste from ongoing operations at the Idaho Nuclear Technology and Engineering Center. The WVF will contain the vitrification process that will mix the waste with glass-forming chemicals or frit and turn the waste into glass. The VWISF will provide a shielded storage facility for the glass until the waste can be disposed at either the Waste Isolation Pilot Plant as mixed transuranic waste or at the future national geological repository as high-level waste glass, pending the outcome of a Waste Incidental to Reprocessing determination, which is currently in progress. A secondary goal is to provide a facility that can be easily modified later to accommodate storage of the vitrified high-level waste calcine. The objective of this study was to determine the feasibility of the VWISF, which would be constructed in compliance with applicable federal, state, and local laws. This project supports the Department of Energy’s Environmental Management missions of safely storing and treating radioactive wastes as well as meeting Federal Facility Compliance commitments made to the State of Idaho.

Bonnema, Bruce Edward

2001-09-01T23:59:59.000Z

97

E-Area Performance Assessment Interim Measures Assessment FY2005  

SciTech Connect (OSTI)

After major changes to the limits for various disposal units of the E-Area Low Level Waste Facility (ELLWF) last year, no major changes have been made during FY2005. A Special Analysis was completed which removes the air pathway {sup 14}C limit from the Intermediate Level Vault (ILV). This analysis will allow the disposal of reactor moderator deionizers which previously had no pathway to disposal. Several studies have also been completed providing groundwater transport input for future special analyses. During the past year, since Slit Trenches No.1 and No.2 were nearing volumetric capacity, they were operationally closed under a preliminary closure analysis. This analysis was performed using as-disposed conditions and data and showed that concrete rubble from the demolition of 232-F was acceptable for disposal in the STs even though the latest special analysis for the STs had reduced the tritium limits so that the inventory in the rubble exceeded limits. A number of special studies are planned during the next years; perhaps the largest of these will be revision of the Performance Assessment (PA) for the ELLWF. The revision will be accomplished by incorporating special analyses performed since the last PA revision as well as revising analyses to include new data. Projected impacts on disposal limits of more recent studies have been estimated. No interim measures will be applied during this year. However, it is being recommended that tritium disposals to the Components-in-Grout (CIG) Trenches be suspended until a limited Special Analysis (SA) currently in progress is completed. This SA will give recommendations for optimum placement of tritiated D-Area tower waste. Further recommendations for tritiated waste placement in the CIG Trenches will be given in the upcoming PA revision.

Stallings, M

2006-01-31T23:59:59.000Z

98

Corrective Feedback and Teacher Development  

E-Print Network [OSTI]

types of corrective feedback on ESL student writing. Journaland implicit negative feedback: An empirical study of theof written corrective feedback types. English Language

Ellis, Rod

2009-01-01T23:59:59.000Z

99

Correction coil cable  

DOE Patents [OSTI]

A wire cable assembly adapted for the winding of electrical coils is taught. A primary intended use is for use in particle tube assemblies for the Superconducting Super Collider. The correction coil cables have wires collected in wire array with a center rib sandwiched therebetween to form a core assembly. The core assembly is surrounded by an assembly housing having an inner spiral wrap and a counter wound outer spiral wrap. An alternate embodiment of the invention is rolled into a keystoned shape to improve radial alignment of the correction coil cable on a particle tube in a particle tube assembly. 7 figs.

Wang, S.T.

1994-11-01T23:59:59.000Z

100

ICM, Incorporated | Department of Energy  

Broader source: Energy.gov (indexed) [DOE]

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr May Jun Jul(Summary) "ofEarly Career Scientists'Montana.ProgramJulietip sheetK-4In 2013DepartmentAgendaAllison Casey-6,10-11, 2013,One

Note: This page contains sample records for the topic "icm interim corrective" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


101

ICM, Incorporated | Department of Energy  

Broader source: Energy.gov (indexed) [DOE]

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr May Jun Jul(Summary) "ofEarly Career Scientists'Montana.ProgramJulietip sheetK-4In 2013DepartmentAgendaAllison Casey-6,10-11,

102

ICM, Incorporated | Department of Energy  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE:YearRound-UpHeatMulti-Dimensionalthe U.S. Department of EnergyKickoff Meeting

103

NGNP-NHS 100-RXBLDG 0 Final 091608.doc  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Production System HSS Helium Service System HTGR High Temperature Gas Cooled Reactor HVAC Heating, Ventilation, and Air Conditioning IBC International Building Code ICM Interim...

104

Biennial Assessment of the Fifth Power Plan Interim Report on Fuel Price Assumptions  

E-Print Network [OSTI]

. In addition, the delivered price of coal to power plants located in the region will be affected by diesel fuelBiennial Assessment of the Fifth Power Plan Interim Report on Fuel Price Assumptions Summary The Fifth Power Plan includes price forecasts for natural gas, oil, and coal. Natural gas prices have by far

105

Biennial Assessment of the Fifth Power Plan Interim Report on Electric Price Forecasts  

E-Print Network [OSTI]

Biennial Assessment of the Fifth Power Plan Interim Report on Electric Price Forecasts Electricity prices in the Council's Power Plan are forecast using the AURORATM Electricity Market Model of the entire and 2006 actual electric prices have been more volatile than the Aurora forecast. This is expected because

106

Safety and Environmental Considerations and Analysis APEX Interim Report November, 1999  

E-Print Network [OSTI]

Safety and Environmental Considerations and Analysis APEX Interim Report November, 1999 14-1 CHAPTER 14: SAFETY AND ENVIRONMENT CONSIDERATIONS AND ANALYSIS Contributors Lead Author: K.A. McCarthy H. Khater L. C. Cadwallader B. J. Merrill R.L. Moore D.A. Petti S. T. Schuetz #12;Safety and Environmental

California at Los Angeles, University of

107

Sample Results From The Interim Salt Disposition Program Macrobatch 6 Tank 21H Qualification Samples  

SciTech Connect (OSTI)

Savannah River National Laboratory (SRNL) analyzed samples from Tank 21H in support of qualification of Macrobatch (Salt Batch) 6 for the Interim Salt Disposition Project (ISDP). This document reports partial results of the analyses of samples of Tank 21H. No issues with the projected Salt Batch 6 strategy are identified.

Peters, T. B.; Fink, S. D.

2012-12-20T23:59:59.000Z

108

Sample Results from the Interim Salt Disposition Program Macrobatch 6 Tank 21H Qualification Samples  

SciTech Connect (OSTI)

Savannah River National Laboratory (SRNL) analyzed samples from Tank 21H in support of qualification of Macrobatch (Salt Batch) 6 for the Interim Salt Disposition Project (ISDP). This document reports partial results of the analyses of samples of Tank 21H. No issues with the projected Salt Batch 6 strategy are identified.

Peters, T. B.; Fink, S. D.

2012-12-11T23:59:59.000Z

109

Interfacial Mixing in Viscous Pipe Flows Interim report to Imperial Oil  

E-Print Network [OSTI]

Interfacial Mixing in Viscous Pipe Flows Interim report to Imperial Oil D. Van Vliet and B. R. Introduction The cost of energy to pump oil through a pipe line is greatly reduced if the ow is not turbulent but laminar. This is because turbulence results in greater energy losses and drag. Although new pipe lines

Sutherland, Bruce

110

Engineering report single-shell tank farms interim measures to limit infiltration through the vadose zone  

SciTech Connect (OSTI)

Identifies, evaluates and recommends interim measures for reducing or eliminating water sources and preferential pathways within the vadose zone of the single-shell tank farms. Features studied: surface water infiltration and leaking water lines that provide recharge moisture, and wells that could provide pathways for contaminant migration. An extensive data base, maps, recommended mitigations, and rough order of magnitude costs are included.

HAASS, C.C.

1999-10-14T23:59:59.000Z

111

Public Interest Energy Research (PIER) Program INTERIM/FINAL PROJECT REPORT  

E-Print Network [OSTI]

Public Interest Energy Research (PIER) Program INTERIM/FINAL PROJECT REPORT Maximum Power Point Inverter for Photovoltaic Systems With Energy Storage and Dispatchability is the final report for the SMUD Tracker Inverter for Photovoltaic Systems with Energy Storage and Dispatchability DECEMBER 2011 CEC

112

UMBC Policy # III-1.11.02 Page 1 of 4 UMBC INTERIM POLICY ON  

E-Print Network [OSTI]

UMBC Policy # III-1.11.02 Page 1 of 4 UMBC INTERIM POLICY ON INDIVIDUAL FINANCIAL CONFLICTS OF INTEREST IN PHS RESEARCH UMBC # III-1.11.02 I. POLICY STATEMENT Externally sponsored research is a vital FOR POLICY UMBC strives for excellence and academic integrity in its research enterprise while also promoting

Adali, Tulay

113

The development of a management strategy for interim storage and final disposal of nuclear wastes  

SciTech Connect (OSTI)

The overall waste management strategy for alternative routes from reactor to final disposal, including dry interim storage, is discussed. Within the framework of a preliminary structure plan possible technical solutions must be investigated, and with sufficient relevant information available the future progress of the project, can be addressed on the base of a decision analysis.

Engelmann, H.J.; Popp, F.W. [Deutsche Gesellschaft zum Bau and Betrieb von Endglagern fuer Abfallostofe mbH, Peine (Germany); Arntzen, P.; Botzem, W. [NUKEM GmbH, Alzenau (Germany); Soucek, B. [Czech Power Board, Prague (Czech Republic)

1993-12-31T23:59:59.000Z

114

Interim-status groundwater monitoring plan for the 216-B-63 trench  

SciTech Connect (OSTI)

This document outlines the groundwater monitoring plan, under RCRA regulations in 40 CFR 265 Subpart F and WAC173-300-400, for the 216-B-63 Trench. This interim status facility is being sampled under detection monitoring criteria and this plan provides current program conditions and requirements.

Sweeney, M.D.

1995-02-09T23:59:59.000Z

115

Safety evaluation for the interim stabilization of Tank 241-C-103  

SciTech Connect (OSTI)

This document provides the basis for interim stabilization of tank 241-C-103. The document covers the removal of the organic liquid layer and the aqueous supernatant from tank 241-C-103. Hazards are identified, consequences are calculated and controls to mitigate or prevent potential accidents are developed.

Geschke, G.R.

1995-03-01T23:59:59.000Z

116

Annex D-200 Area Interim Storage Area Final Safety Analysis Report [FSAR] [Section 1 & 2  

SciTech Connect (OSTI)

The 200 Area Interim Storage Area (200 Area ISA) at the Hanford Site provides for the interim storage of non-defense reactor spent nuclear fuel (SNF) housed in aboveground dry cask storage systems. The 200 Area ISA is a relatively simple facility consisting of a boundary fence with gates, perimeter lighting, and concrete and gravel pads on which to place the dry storage casks. The fence supports safeguards and security and establishes a radiation protection buffer zone. The 200 Area ISA is nominally 200,000 ft{sup 2} and is located west of the Canister Storage Building (CSB). Interim storage at the 200 Area ISA is intended for a period of up to 40 years until the materials are shipped off-site to a disposal facility. This Final Safety Analysis Report (FSAR) does not address removal from storage or shipment from the 200 Area ISA. Three different SNF types contained in three different dry cask storage systems are to be stored at the 200 Area ISA, as follows: (1) Fast Flux Test Facility Fuel--Fifty-three interim storage casks (ISC), each holding a core component container (CCC), will be used to store the Fast Flux Test Facility (FFTF) SNF currently in the 400 Area. (2) Neutron Radiography Facility (NRF) TRIGA'--One Rad-Vault' container will store two DOT-6M3 containers and six NRF TRIGA casks currently stored in the 400 Area. (3) Commercial Light Water Reactor Fuel--Six International Standards Organization (ISO) containers, each holding a NAC-I cask4 with an inner commercial light water reactor (LWR) canister, will be used for commercial LWR SNF from the 300 Area. An aboveground dry cask storage location is necessary for the spent fuel because the current storage facilities are being shut down and deactivated. The spent fuel is being transferred to interim storage because there is no permanent repository storage currently available.

CARRELL, R.D.

2002-07-16T23:59:59.000Z

117

Corrective Action Investigation Plan for Corrective Action Unit...  

Office of Scientific and Technical Information (OSTI)

Plan for Corrective Action Unit 541: Small Boy Nevada National Security Site and Nevada Test and Training Range, Nevada Re-direct Destination: Corrective Action Unit (CAU) 541 is...

118

Assessment of Stormflow and Water Quality from Undisturbed and Site Prepared Forest Land in East Texas (Interim Report)  

E-Print Network [OSTI]

TR- 117 1981 Assessment of Stormflow and Water Quality from Undisturbed and Site Prepared Forest Land in East Texas, Interim Report M.G. DeHaven W.H. Blackburn R.W. Knight A.T. Weichert...

DeHaven, M. G.; Blackburn, W. H.; Knight, R. W.; Weichert, A. T.

119

Corrections for Water Resources Engineering  

E-Print Network [OSTI]

Corrections for Water Resources Engineering (Second printing) By Larry W. Mays Corrections as of 4, a supercritical flow ..." should read "Because yn subcritical flow ..." #12;Chapter 6 Page 141

Mays, Larry W.

120

Corrections for Water Resources Engineering  

E-Print Network [OSTI]

Corrections for Water Resources Engineering (Third printing) By Larry W. Mays Corrections as of 4, a subcritical flow ..." Chapter 6 Page 141 Section 6.1, sixth line, "slit" should be "silt" #12;Page 148 Fourth

Mays, Larry W.

Note: This page contains sample records for the topic "icm interim corrective" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


121

Functions and requirements document for interim store solidified high-level and transuranic waste  

SciTech Connect (OSTI)

The functions, requirements, interfaces, and architectures contained within the Functions and Requirements (F{ampersand}R) Document are based on the information currently contained within the TWRS Functions and Requirements database. The database also documents the set of technically defensible functions and requirements associated with the solidified waste interim storage mission.The F{ampersand}R Document provides a snapshot in time of the technical baseline for the project. The F{ampersand}R document is the product of functional analysis, requirements allocation and architectural structure definition. The technical baseline described in this document is traceable to the TWRS function 4.2.4.1, Interim Store Solidified Waste, and its related requirements, architecture, and interfaces.

Smith-Fewell, M.A., Westinghouse Hanford

1996-05-17T23:59:59.000Z

122

FedEx Gasoline Hybrid Electric Delivery Truck Evaluation: 6-Month Interim Report  

SciTech Connect (OSTI)

This interim report presents partial (six months) results for a technology evaluation of gasoline hybrid electric parcel delivery trucks operated by FedEx in and around Los Angeles, CA. A 12 month in-use technology evaluation comparing in-use fuel economy and maintenance costs of GHEVs and comparative diesel parcel delivery trucks was started in April 2009. Comparison data was collected and analyzed for in-use fuel economy and fuel costs, maintenance costs, total operating costs, and vehicle uptime. In addition, this interim report presents results of parcel delivery drive cycle collection and analysis activities as well as emissions and fuel economy results of chassis dynamometer testing of a gHEV and a comparative diesel truck at the National Renewable Energy Laboratory's (NREL) ReFUEL laboratory. A final report will be issued when 12 months of in-use data have been collected and analyzed.

Barnitt, R.

2010-05-01T23:59:59.000Z

123

The Time Needed to Implement the Blue Ribbon Commission Recommendation on Interim Storage - 13124  

SciTech Connect (OSTI)

The report of the Blue Ribbon Commission on America's Nuclear Future [1] makes a number of important recommendations to be considered if Congress elects to redirect U.S. high-level radioactive waste disposal policy. Setting aside for the purposes of this discussion any issues related to political forces leading to stopping progress on the Yucca Mountain project and driving the creation of the Commission, an important recommendation of the Commission was to institute prompt efforts to develop one or more consolidated storage facilities. The Blue Ribbon Commission noted that this recommended strategy for future storage and disposal facilities and operations should be implemented regardless of what happens with Yucca Mountain. It is too easy, however, to focus on interim storage as an alternative to geologic disposal. The Blue Ribbon Commission report does not go far enough in addressing the magnitude of the contentious problems associated with reopening the issues of relative authorities of the states and federal government with which Congress wrestled in crafting the Nuclear Waste Policy Act [2]. The Blue Ribbon Commission recommendation for prompt adoption of an interim storage program does not appear to be fully informed about the actions that must be taken, the relative cost of the effort, or the realistic time line that would be involved. In essence, the recommendation leaves to others the details of the systems engineering analyses needed to understand the nature and details of all the operations required to reach an operational interim storage facility without derailing forever the true end goal of geologic disposal. The material presented identifies a number of impediments that must be overcome before the country could develop a centralized federal interim storage facility. In summary, and in the order presented, they are: 1. Change the law, HJR 87, PL 107-200, designating Yucca Mountain for the development of a repository. 2. Bring new nuclear waste legislation to the floor of the Senate, overcoming existing House support for Yucca Mountain; 3. Change the longstanding focus of Congress from disposal to storage; 4. Change the funding concepts embodied in the Nuclear Waste Policy Act to allow the Nuclear Waste fund to be used to pay for interim storage; 5. Reverse the Congressional policy not to give states or tribes veto or consent authority, and to reserve to Congress the authority to override a state or tribal disapproval; 6. Promulgate interim storage facility siting regulations to reflect the new policies after such changes to policy and law; 7. Complete already underway changes to storage and transportation regulations, possibly incorporating changes to reflect changes to waste disposal law; 8. Promulgate new repository siting regulations if the interim storage facility is to support repository development; 9. Identify volunteer sites, negotiate agreements, and get Congressional approval for negotiated benefits packages; 10. Design, License and develop the interim storage facility. The time required to accomplish these ten items depends on many factors. The estimate developed assumes that certain of the items must be completed before other items are started; given past criticisms of the current program, such an assumption appears appropriate. Estimated times for completion of individual items are based on historical precedent. (authors)

Voegele, Michael D. [Consultant, Nye County Nuclear Waste Repository Project Office, 7404 Oak Grove Ave, Las Vegas, NV 89117 (United States)] [Consultant, Nye County Nuclear Waste Repository Project Office, 7404 Oak Grove Ave, Las Vegas, NV 89117 (United States); Vieth, Donald [1154 Chelttenham Place, Maineville, OH 45039 (United States)] [1154 Chelttenham Place, Maineville, OH 45039 (United States)

2013-07-01T23:59:59.000Z

124

Seismic Safety Margins Research Program. Phase I. Interim definition of terms  

SciTech Connect (OSTI)

This report documents interim definitions of terms in the Seismic Safety Margins Research Program (SSMRP). Intent is to establish a common-based terminology integral to the probabilistic methods that predict more realistically the behavior of nuclear power plants during an earthquake. These definitions are a response to a request by the Nuclear Regulatory Commission Advisory Committee on Reactor Safeguards at its meeting held November 15-16, 1979.

Smith, P.D.; Dong, R.G.

1980-12-19T23:59:59.000Z

125

Design requirements document for project W-465, immobilized low activity waste interim storage  

SciTech Connect (OSTI)

The scope of this design requirements document is to identify the functions and associated requirements that must be performed to accept, transport, handle, and store immobilized low-activity waste produced by the privatized Tank Waste Remediation System treatment contractors. The functional and performance requirements in this document provide the basis for the conceptual design of the Tank Waste Remediation System Immobilized low-activity waste interim storage facility project and provides traceability from the program level requirements to the project design activity.

Burbank, D.A.

1997-01-27T23:59:59.000Z

126

Application of NUREG/CR-5999 interim fatigue curves to selected nuclear power plant components  

SciTech Connect (OSTI)

Recent test data indicate that the effects of the light water reactor (LWR) environment could significantly reduce the fatigue resistance of materials used in the reactor coolant pressure boundary components of operating nuclear power plants. Argonne National Laboratory has developed interim fatigue curves based on test data simulating LWR conditions, and published them in NUREG/CR-5999. In order to assess the significance of these interim fatigue curves, fatigue evaluations of a sample of the components in the reactor coolant pressure boundary of LWRs were performed. The sample consists of components from facilities designed by each of the four U.S. nuclear steam supply system vendors. For each facility, six locations were studied, including two locations on the reactor pressure vessel. In addition, there are older vintage plants where components of the reactor coolant pressure boundary were designed to codes that did not require an explicit fatigue analysis of the components. In order to assess the fatigue resistance of the older vintage plants, an evaluation was also conducted on selected components of three of these plants. This report discusses the insights gained from the application of the interim fatigue curves to components of seven operating nuclear power plants.

Ware, A.G.; Morton, D.K.; Nitzel, M.E. [Idaho National Engineering Lab., Idaho Falls, ID (United States)

1995-03-01T23:59:59.000Z

127

Corrective Action Investigation Plan for Corrective Action Unit...  

Office of Scientific and Technical Information (OSTI)

Plan for Corrective Action Unit 541: Small Boy Nevada National Security Site and Nevada Test and Training Range, Nevada Re-direct Destination: Temp Data Fields Matthews, Patrick...

128

Ultrasonic Characterization of Cast Austenitic Stainless Steel Microstructure: Discrimination between Equiaxed- and Columnar-Grain Material – An Interim Study  

SciTech Connect (OSTI)

Ultrasonic nondestructive evaluation (NDE) and inspection of cast austenitic stainless steel (CASS) components used in the nuclear power industry is neither as effective nor reliable as is needed due to detrimental effects upon the interrogating ultrasonic beam and interference from ultrasonic backscatter. The root cause is the coarse-grain microstructure inherent to this class of materials. Some ultrasonic techniques perform better for particular microstructural classifications and this has led to the hypothesis that an ultrasonic inspection can be optimized for a particular microstructural class, if a technique exists to reliably classify the microstructure for feedback to the inspection. This document summarizes scoping experiments of in-situ ultrasonic methods for classification and/or characterization of the material microstructures in CASS components from the outside surface of a pipe. The focus of this study was to evaluate ultrasonic methods and provide an interim report that documents results and technical progress. An initial set of experiments were performed to test the hypothesis that in-service characterization of cast austenitic stainless steel (CASS) is feasible, and that, if reliably performed, such data would provide real-time feedback to optimize in-service inspections in the field. With this objective in mind, measurements for the experiment were restricted to techniques that should be robust if carried forward to eventual field implementation. Two parameters were investigated for their ability to discriminate between different microstructures in CASS components. The first parameter was a time-of-flight ratio of a normal incidence shear wave to that of a normal incidence longitudinal wave (TOFRSL). The ratio removed dependency on component thickness which may not be accurately reported in the field. The second parameter was longitudinal wave attenuation. The selected CASS specimens provided five equiaxed-grain material samples and five columnar-grain material samples for a two-class discrimination problem. Qualitative TOFRSL estimates and a threshold algorithm classified all 10 material samples correctly and indicated a reliable and robust technique. Qualitative longitudinal wave attenuation estimates and a threshold algorithm also classified all 10 materials samples correctly; however, the technique was not as robust as TOFRSL. The experiments provided promising results and demonstrated that good potential exists for future development of techniques to implement real-time classification of CASS material. However, the reported measurements need to be substantiated with measurements on additional specimens.

Ramuhalli, Pradeep; Good, Morris S.; Diaz, Aaron A.; Anderson, Michael T.; Watson, Bruce E.; Peters, Timothy J.; Dixit, Mukul; Bond, Leonard J.

2009-10-27T23:59:59.000Z

129

Nested Quantum Error Correction Codes  

E-Print Network [OSTI]

The theory of quantum error correction was established more than a decade ago as the primary tool for fighting decoherence in quantum information processing. Although great progress has already been made in this field, limited methods are available in constructing new quantum error correction codes from old codes. Here we exhibit a simple and general method to construct new quantum error correction codes by nesting certain quantum codes together. The problem of finding long quantum error correction codes is reduced to that of searching several short length quantum codes with certain properties. Our method works for all length and all distance codes, and is quite efficient to construct optimal or near optimal codes. Two main known methods in constructing new codes from old codes in quantum error-correction theory, the concatenating and pasting, can be understood in the framework of nested quantum error correction codes.

Zhuo Wang; Kai Sun; Hen Fan; Vlatko Vedral

2009-09-28T23:59:59.000Z

130

Gravitational Correction in Neutrino Oscillations  

E-Print Network [OSTI]

We investigate the quantum mechanical oscillations of neutrinos propagating in weak gravitational field. The correction to the result in the flat space-time is derived.

Yasufumi Kojima

1996-12-17T23:59:59.000Z

131

Corrections for Water Resources Engineering  

E-Print Network [OSTI]

Corrections for Water Resources Engineering (First printing) By Larry W. Mays Corrections as of 4.8.2 should read, "Water flows in a rectangular channel ..." Chapter 3 Page 46 Delete second equal sign 5.3.1, steep S1 the type of flow is "subcritical" not "supercritical" Page 110 Figure 5

Mays, Larry W.

132

DEMONSTRATION OF THE DOE INTERIM ENERGY CONSERVATION STANDARDS FOR NEW FEDERAL RESIDENTIAL BUILDINGS  

SciTech Connect (OSTI)

In accordance with federal legislation, the U.S. Department of Energy (DOE) has sponsored a study to demonstrate use of its Interim Energy Conservation Standards for New Federal Residential Buildings. The demonstration study was conducted by DOE and the Pacific Northwest Laboratory (PNL). The demonstration is the second step in a three-step process: I) development of interim standards, 2) demonstration of the interim standards, and 3) development of final standards. The standards are mandatory for federal agency housing procurements. Nevertheless, PNL found at the start of the demonstration that agency use of the interim standards had been minimal. The purpose of the standards is to improve the energy efficiency of federal housing and increase the use of nondepletable energy sources. In accordance with the legislation, the standards were to be performance-based rather than prescribing specific energy conservation measures. To fulfill this aspect of the legislation, the standards use a computer software program called COSTSAFR which generates a point system that individualizes the standards to specific projects based on climate, housing type, and fuel costs. The standards generate minimum energy-efficiency requirements by applying the life-cycle cost methodology developed for federal projects. For the demonstration, PNL and DOE chose five federal agency housing projects which had been built in diverse geographic and climate regions. Participating agencies were the Air Force, the Army (which provided two case studies), the Navy, and the Department of Health and Human Services. PNL worked with agency housing procurement officials and designers/architects to hypothetically apply the interim standards to the procurement and design of each housing project. The demonstration started at the point in the project where agencies would establish their energyefficiency requirements for the project and followed the procurement process through the designers' use of the point system to develop a design which would comply with the standards. PNL conducted extensive interviews with the federal agencies and design contractors to determine what impacts the standards would have on the existing agency procurement process as well as on designers. Overall, PNL found that the interim standards met the basic intent of the law. Specific actions were identified, however, that DOE could take to improve the standards and encourage the agencies to implement them. Agency personnel found the minimum efficiency levels established by the standards to be lower than expected, and lower than their existing requirements. Generally, this was because the standards factor in fuel costs, as well as energy savings due to various conservation measures such as insulation, when they determine the minimum efficiency levels required. The demonstration showed that federal agencies often pay low prices for heating fuel and electricity; these lower costs "tipped the scales," allowing designers to meet the efficiency target with designs that were relatively inefficient. It appeared, however, that the low prices paid by agencies directly to suppliers did not capture the agencies' full costs of providing energy, such as the costs of distribution and storage. Agency personnel expressed some concern about the standards' ability to incorporate new energy-efficient technologies and renewable resource technologies like solar heating systems. An alternative compliance procedure was developed to incorporate new technologies; however, demonstration participants said the procedure was not well documented and was difficult and time consuming to use. Despite these concerns, most agency personnel thought that the standards would fit into current procurement procedures with no big changes or cost increases. Many said use of the standards would decrease the time and effort they now spend to establish energy-efficiency requirements and to confirm that proposed designs comply. Personnel praised the software and documentation for being easy to use and providing energ

Lee, A. D.; Baechler, H. C.; Di Massa, F. V.; Lucas, R. G.; Shankle, D. L.

1992-01-01T23:59:59.000Z

133

RCRA/UST, superfund, and EPCRA hotline training module. Introduction to: Permits and interim status (40 CFR part 270) updated as of July 1995  

SciTech Connect (OSTI)

The module presents an overview of the RCRA permitting process and the requirements that apply to treatment, storage, and disposal facilities (TSDFs) operating under interim status until a permit is issued. It lists the types of activities that do and do not require a permit. It provides CFR cites for definitions of existing hazardous waste facility and new hazardous waste facility and identifies CFR sections relevant to Part A and Part B permit information requirements and describes the difference between them. It outlines steps in the process from interim status to receipt of permit. It identifies the differences among permit modification classes, and lists the special forms of permits. It lists the permit-by-rule applications, status and eligibility requirements for interim status and the conditions for termination of interim status and lists the conditions for changes during interim status.

NONE

1995-11-01T23:59:59.000Z

134

T-TY Tank Farm Interim Surface Barrier Demonstration—Vadose Zone Monitoring Plan  

SciTech Connect (OSTI)

The Hanford Site has 149 underground single-shell tanks that store hazardous radioactive waste. Many of these tanks and their associated infrastructure (e.g., pipelines, diversion boxes) have leaked. Some of the leaked waste has entered the groundwater. The largest known leak occurred from the T-106 Tank of the 241-T Tank Farm in 1973. Five tanks are assumed to have leaked in the TY Farm. Many of the contaminants from those leaks still reside within the vadose zone within the T and TY Tank Farms. The Department of Energy’s Office of River Protection seeks to minimize the movement of these contaminant plumes by placing interim barriers on the ground surface. Such barriers are expected to prevent infiltrating water from reaching the plumes and moving them further. The soil water regime is monitored to determine the effectiveness of the interim surface barriers. Soil-water content and water pressure are monitored using off-the-shelf equipment that can be installed by the hydraulic hammer technique. Four instrument nests were installed in the T Farm in fiscal year (FY) 2006 and FY2007; two nests were installed in the TY Farm in FY2010. Each instrument nest contains a neutron probe access tube, a capacitance probe, and four heat-dissipation units. A meteorological station has been installed at the north side of the fence of the T Farm. This document summarizes the monitoring methods, the instrument calibration and installation, and the vadose zone monitoring plan for interim barriers in T farm and TY Farm.

Zhang, Z. F.; Strickland, Christopher E.; Field, Jim G.; Parker, Danny L.

2010-09-27T23:59:59.000Z

135

Software Verification & Validation Report for the 244-AR Vault Interim Stabilization Ventilation System  

SciTech Connect (OSTI)

This document reports on the analysis, testing and conclusions of the software verification and validation for the 244-AR Vault Interim Stabilization ventilation system. Automation control system will use the Allen-Bradley software tools for programming and programmable logic controller (PLC) configuration. The 244-AR Interim Stabilization Ventilation System will be used to control the release of radioactive particles to the environment in the containment tent, located inside the canyon of the 244-AR facility, and to assist the waste stabilization efforts. The HVAC equipment, ducts, instruments, PLC hardware, the ladder logic executable software (documented code), and message display terminal are considered part of the temporary ventilation system. The system consists of a supply air skid, temporary ductwork (to distribute airflow), and two skid-mounted, 500-cfm exhausters connected to the east filter building and the vessel vent system. The Interim Stabilization Ventilation System is a temporary, portable ventilation system consisting of supply side and exhaust side. Air is supplied to the containment tent from an air supply skid. This skid contains a constant speed fan, a pre-filter, an electric heating coil, a cooling coil, and a constant flow device (CFD). The CFD uses a passive component that allows a constant flow of air to pass through the device. Air is drawn out of the containment tent, cells, and tanks by two 500-cfm exhauster skids running in parallel. These skids are equipped with fans, filters, stack, stack monitoring instrumentation, and a PLC for control. The 500CFM exhaust skids were fabricated and tested previously for saltwell pumping activities. The objective of the temporary ventilation system is to maintain a higher pressure to the containment tent, relative to the canyon and cell areas, to prevent contaminants from reaching the containment tent.

YEH, T.

2002-11-20T23:59:59.000Z

136

Hydrogen combustion in an MCO during interim storage (fauske and associates report 99-14)  

SciTech Connect (OSTI)

Flammable conditions are not expected to develop in an MCO during interim storage. This report considers potential phenomena which, although not expected t o occur, could lead t o flammable conditions. For example, reactions of hydrogen w i t h fuel over decades a r e postulated t o lead t o flammable atmospheric mixtures. For the extreme cases considered in this report, the highest attainable post-combustion pressure is about 13 atmospheres absolute, almost a factor of two and a half below the MCO design pressure of 31 atmospheres.

PLYS, M.G.

1999-05-12T23:59:59.000Z

137

Interim Final Rule and Request for Comments, Federal Register, 71 FR 70275,  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE:YearRound-UpHeatMulti-Dimensionalthe U.S.IndianaofPilotControlPresentation fromInterim Final Rule10

138

Interim Report of the Commission to Review the Effectiveness of the  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE:YearRound-UpHeatMulti-Dimensionalthe U.S.IndianaofPilotControlPresentation fromInterim Final

139

Interim Update: Global Automotive Power Electronics R&D Relevant To DOE  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE:YearRound-UpHeatMulti-Dimensionalthe U.S.IndianaofPilotControlPresentation fromInterim Final2015

140

Approaches to Quantum Error Correction  

E-Print Network [OSTI]

The purpose of this little survey is to give a simple description of the main approaches to quantum error correction and quantum fault-tolerance. Our goal is to convey the necessary intuitions both for the problems and their solutions in this area. After characterising quantum errors we present several error-correction schemes and outline the elements of a full fledged fault-tolerant computation, which works error-free even though all of its components can be faulty. We also mention alternative approaches to error-correction, so called error-avoiding or decoherence-free schemes. Technical details and generalisations are kept to a minimum.

Julia Kempe

2006-12-21T23:59:59.000Z

Note: This page contains sample records for the topic "icm interim corrective" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


141

Environmental surveillance results for 1994 for the Hazelwood Interim Storage Site. FUSRAP technical memorandum Number 140-95-011  

SciTech Connect (OSTI)

This report presents analytical results and an interpretation of the results for samples collected as part of the 1994 environmental surveillance program for the Hazelwood Interim Storage Site (HISS) for the interim storage of radiologically contaminated soils. The discussion provides a comparative analysis of local background conditions and applicable regulatory criteria to results reported for external gamma radiation and for samples from the media investigated (air, surface water, sediment, groundwater, and stormwater). Results from the 1994 environmental surveillance program at HISS indicate that Department of Energy (DOE) guidelines were not exceeded for the calculated airborne particulate dose or for the monitored constituents.

Szojka, S.

1995-06-01T23:59:59.000Z

142

Entropic corrections to Einstein equations  

SciTech Connect (OSTI)

Considering the general quantum corrections to the area law of black hole entropy and adopting the viewpoint that gravity interprets as an entropic force, we derive the modified forms of Modified Newtonian dynamics (MOND) theory of gravitation and Einstein field equations. As two special cases we study the logarithmic and power-law corrections to entropy and find the explicit form of the obtained modified equations.

Hendi, S. H. [Physics Department, College of Sciences, Yasouj University, Yasouj 75914 (Iran, Islamic Republic of); Research Institute for Astronomy and Astrophysics of Maragha (RIAAM), Maragha (Iran, Islamic Republic of); Sheykhi, A. [Research Institute for Astronomy and Astrophysics of Maragha (RIAAM), Maragha (Iran, Islamic Republic of); Department of Physics, Shahid Bahonar University, P.O. Box 76175-132, Kerman (Iran, Islamic Republic of)

2011-04-15T23:59:59.000Z

143

T Tank Farm Interim Surface Barrier Demonstration--Vadose Zone Monitoring Plan  

SciTech Connect (OSTI)

The Hanford Site has 149 underground single-shell tanks that store hazardous radioactive waste. Many of these tanks and their associated infrastructure (e.g., pipelines, diversion boxes) have leaked. Some of the leaked waste has entered the groundwater. The largest known leak occurred from the T-106 Tank in 1973. Many of the contaminants from that leak still reside within the vadose zone beneath the T Tank Farm. CH2M Hill Hanford Group, Inc. seeks to minimize movement of this residual contaminant plume by placing an interim barrier on the surface. Such a barrier is expected to prevent infiltrating water from reaching the plume and moving it further. A plan has been prepared to monitor and determine the effectiveness of the interim surface barrier. Soil water content and water pressure will be monitored using off-the-shelf equipment that can be installed by the hydraulic hammer technique. In fiscal year 2006, two instrument nests were installed. Each instrument nest contains a neutron probe access tube, a capacitance probe, four heat-dissipation units, and a drain gauge to measure soil water flux. A meteorological station has been installed outside of the fence. In fiscal year 2007, two additional instrument nests are planned to be installed beneath the proposed barrier.

Zhang, Z. F.; Keller, Jason M.; Strickland, Christopher E.

2007-04-01T23:59:59.000Z

144

INTERIM BARRIER AT HANFORDS TY FARM TO PROTECT GROUNDWATER AT THE HANFORD SITE WASHINGTON USA  

SciTech Connect (OSTI)

An innovative interim surface barrier was constructed as a demonstration project at the Hanford Site's TY Tank Farm. The purpose of the demonstration barrier is to stop rainwater and snowmelt from entering the soils within the tank farm and driving contamination from past leaks and spills toward the ground water. The interim barrier was constructed using a modified asphalt material with very low permeability developed by MatCon{reg_sign}. Approximately 2,400 cubic yards of fill material were added to the tank farm to create a sloped surface that will gravity drain precipitation to collection points where it will be routed through buried drain lines to an evapotranspiration basin adjacent to the farm. The evapotranspiration basin is a lined basin with a network of perforated drain lines covered with soil and planted with native grasses. The evapotranspiration concept was selected because it prevents the runoff from percolating into the soil column and also avoids potential monitoring and maintenance issues associated with standing water in a traditional evaporation pond. Because of issues associated with using standard excavation and earth moving equipment in the farm a number of alternate construction approaches were utilized to perform excavations and prepare the site for the modified asphalt.

PARKER DL; HOLM MJ; HENDERSON JC; LOBER RW

2011-01-13T23:59:59.000Z

145

COMPLETION OF THE FIRST INTEGRATED SPENT NUCLEAR FUEL TRANSSHIPMENT/INTERIM STORAGE FACILITY IN NW RUSSIA  

SciTech Connect (OSTI)

Northwest and Far East Russia contain large quantities of unsecured spent nuclear fuel (SNF) from decommissioned submarines that potentially threaten the fragile environments of the surrounding Arctic and North Pacific regions. The majority of the SNF from the Russian Navy, including that from decommissioned nuclear submarines, is currently stored in on-shore and floating storage facilities. Some of the SNF is damaged and stored in an unstable condition. Existing Russian transport infrastructure and reprocessing facilities cannot meet the requirements for moving and reprocessing this amount of fuel. Additional interim storage capacity is required. Most of the existing storage facilities being used in Northwest Russia do not meet health and safety, and physical security requirements. The United States and Norway are currently providing assistance to the Russian Federation (RF) in developing systems for managing these wastes. If these wastes are not properly managed, they could release significant concentrations of radioactivity to these sensitive environments and could become serious global environmental and physical security issues. There are currently three closely-linked trilateral cooperative projects: development of a prototype dual-purpose transport and storage cask for SNF, a cask transshipment interim storage facility, and a fuel drying and cask de-watering system. The prototype cask has been fabricated, successfully tested, and certified. Serial production is now underway in Russia. In addition, the U.S. and Russia are working together to improve the management strategy for nuclear submarine reactor compartments after SNF removal.

Dyer, R.S.; Barnes, E.; Snipes, R.L.; Hoeibraaten, S.; Gran, H.C.; Foshaug, E.; Godunov, V.

2003-02-27T23:59:59.000Z

146

Energy policy act transportation study: Interim report on natural gas flows and rates  

SciTech Connect (OSTI)

This report, Energy Policy Act Transportation Study: Interim Report on Natural Gas Flows and Rates, is the second in a series mandated by Title XIII, Section 1340, ``Establishment of Data Base and Study of Transportation Rates,`` of the Energy Policy Act of 1992 (P.L. 102--486). The first report Energy Policy Act Transportation Study: Availability of Data and Studies, was submitted to Congress in October 1993; it summarized data and studies that could be used to address the impact of legislative and regulatory actions on natural gas transportation rates and flow patterns. The current report presents an interim analysis of natural gas transportation rates and distribution patterns for the period from 1988 through 1994. A third and final report addressing the transportation rates and flows through 1997 is due to Congress in October 2000. This analysis relies on currently available data; no new data collection effort was undertaken. The need for the collection of additional data on transportation rates will be further addressed after this report, in consultation with the Congress, industry representatives, and in other public forums.

NONE

1995-11-17T23:59:59.000Z

147

Interim Action Proposed Plan for the old radioactive waste burial ground (643-E)  

SciTech Connect (OSTI)

This Interim Action Proposed (IAPP) is issued by the U.S. Department of Energy (DOE), which functions as the lead agency for SRS remedial activities, and with concurrence by the U.S. Environmental Protection Agency (EPA) and the South Carolina Department of Health and Environmental Control (SCDHEC). The purpose of this IAPP is to describe the preferred interim remedial action for addressing the Old Radioactive Waste Burial Ground (ORWBG) unit located in the Burial Ground Complex (BGC) at the Savannah River Site (SRS) in Aiken, South Carolina. On December 21, 1989, SRS was included on the National Priorities List (NPL). In accordance with Section 120 of the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), DOE has negotiated a Federal Facility Agreement (FFA, 1993) with EPA and SCDHEC to coordinate remedial activities at SRS. Public participation requirements are listed in Sections 113 and 117 of CERCLA. These requirements include establishment of an Administrative Record File that documents the selection of remedial alternatives and allows for review and comment by the public regarding those alternatives. The SRS Public Involvement Plan (PIP) (DOE, 1994) is designed to facilitate public involvement in the decision-making process for permitting closure, and the selection of remedial alternatives. Section 117(a) of CERCLA, 1980, as amended, requires publication of a notice of any proposed remedial action.

McFalls, S.

1995-12-01T23:59:59.000Z

148

Maywood Interim Storage Site environmental report for calendar year 1989, Maywood, New Jersey  

SciTech Connect (OSTI)

The environmental monitoring program, which began in 1984, was continued in 1989 at the Maywood Interim Storage Site (MISS), a US Department of Energy (DOE) facility located in the Borough of Maywood and the Township of Rochelle Park, New Jersey. MISS is currently used for storage of soils contaminated with low-level radioactivity. MISS is part of the Formerly Utilized Sites Remedial Action Program (FUSRAP), a DOE program to identify and decontaminate or otherwise control sites where residual radioactive materials are present. The monitoring program at MISS measures thoron and radon concentrations in air; external gamma radiation levels; and thorium, uranium, and radium concentrations in surface water, groundwater, and sediment. Additionally, several nonradiological parameters are measured in groundwater. The radiation dose was calculated for a hypothetical maximally exposed individual to verify that the site is in compliance with the DOE radiation protection standard (100 mrem/yr) and to assess its potential effects on public health. This report presents the results of the environmental monitoring program conducted at the US Department of Energy's (DOE) Maywood Interim Storage Site (MISS) during calendar year 1989. Environmental monitoring began at MISS in 1984. 19 refs., 23 figs., 14 tabs.

Not Available

1990-05-01T23:59:59.000Z

149

Hazelwood Interim Storage Site environmental monitoring summary, Hazelwood, Missouri, calendar year 1984  

SciTech Connect (OSTI)

The Hazelwood Interim Storage Site (HISS) is located at 9200 Latty Avenue, Hazelwood, Missouri. The property on which the HISS is situated is owned by the Jarboe Realty and Investment Company and is leased to Futura Coatings, Inc. Radiological surveys in 1977 and 1982 indicated uranium and thorium contamination and elevated radiation levels in the soil on this property and several others in the immediate vicinity. As part of the research and development program authorized by Congress under the 1984 Energy and Water Appropriations Act, Bechtel National, Inc. (BNI) is conducting remedial action on-site and at the vicinity properties. The work is being performed as part of the US Department of Energy (DOE) Formerly Utilized Sites Remedial Action Program (FUSRAP). Jarboe Realty and Investment Company has agreed to permit DOE to store contaminated material from the FY 1984 and 1985 Latty Avenue cleanup on its property. The contaminated material will be added to the existing pile created during the earlier site cleanup. The pile will then be covered to prevent erosion or migration of contamination. The property will be maintained as the HISS by DOE until final disposition for these materials is determined. BNI is conducting a surveillance monitoring program at the HISS during the interim storage period to detect potential migration of contaminants from the storage pile via air, water, and sediment. This summary provides these monitoring data for calendar year 1984. 6 refs., 4 tabs.

Not Available

1985-07-01T23:59:59.000Z

150

DEMONSTRATION OF THE DOE INTERIM ENERGY CONSERVATION STANDARDS FOR NEW FEDERAL RESIDENTIAL BUILDINGS: EXECUTIVE SUMMARY  

SciTech Connect (OSTI)

In accordance with federal legislation, the U.S. Department of Energy (DOE) bas conducted a project to demonstrate use of its Interim Energy Conservation Standards for New Federal Residential Buildings. The demonstration is the second step in a three-step process: development of interim standards, demonstration of the interim standards, and development of final standards. Pacific Northwest Laboratory (PNL) collected information from the demonstration project and prepared this report under a contract with DOE. The purpose of the standards is to improve the energy efficiency of federal housing and increase the use of nondepletable energy sources. In accordance with the legislation, the standards were to be performance-based rather than prescribing specific energy conservation measures. The standards use a computer software program called COSTSAFR which individualizes the standards based on climate, housing type, and fuel costs. The standards generate minimum energy-efficiency requirements by applying the life-cycle cost methodology developed for federal projects, For the demonstration, the DOE chose live federal agency housing projects: four military housing projects and one project for the Department of Health and Human Services. DOE and PNL worked with agency housing procurement officials and designers/architects to hypothetically apply the interim standards to each housing project. PNL conducted extensive interviews with the federal agencies and design contractors to determine what impacts the standards would have on the existing agency procurement process as well as on designers. Overall, PNL found that the interim standards met the basic intent of the law. Specific actions were identified, however, that DOE could take to improve the standards and encourage the agencies to implement them. Agency personnel and designers expressed similar concerns about the standards: the minimum efficiency levels established by the standards were lower than expected and the standards did not provide an easy way to incorporate new energy-efficient and renewable resource tec.:hnolog:ies like solar heating systems. Agency personnel said the standards would fit into current procurement procedures with no big changes or cost increases, Many said the standards would decrease the time and effort they now spend to establish energy-efficiency requirements and to confirm that proposed designs comply with those requirements. Agency personnel praised the software and documentation for being easy to use and providing energy-efficiency requirements in energy dollars. Housing designers agreed that the DOE standards were easy to use to determine that their designs meet energy-efficiency goals. Many felt the information provided by the standards could be useful in the design process. Based on the demonstration, PNL recommends establishing task forces that will actively involve agency personnel and others in future revisions and development of the final standards. PNL also recommends that DOE and federal agencies investigate the use of market fuel and energy prices in the standards, rather than the prices paid by the agencies, to better reflect actual costs. A number of recommendations are made for improving communications between DOE and the users of the standards and for enhancing tools to implement the standards. Several recommendations are made for increasing the number of renewable resources that are included in the standards. Finally, PNL recommends ongoing monitoring activities to continue to identify ways in which the standards can be improved.

Lee, A. D.; Baechler, M / C.; Di Massa, F. V.; Lucas, R. G.; Shankle, D. L.

1992-01-01T23:59:59.000Z

151

Arellano, Tatum, Stark, Horvath, Leshchinsky 1 Interim Design Guideline for EPS-Block Geofoam in Slope Stabilization and Repair  

E-Print Network [OSTI]

Arellano, Tatum, Stark, Horvath, Leshchinsky 1 Interim Design Guideline for EPS-Block Geofoam of expanded polystyrene (EPS)-block geofoam3 for slope stabilization and repair based on the National for the use of EPS-block geofoam6 for the function of lightweight fill in slope stability applications

152

The Women in Science (WiSci) Project Stage 1 interim report: academic staff survey and focus groups  

E-Print Network [OSTI]

The Women in Science (WiSci) Project Stage 1 interim report: academic staff survey and focus groups The WiSci project The Women in Science (WiSci) project was initiated by Professor David Day, Dean. The project's goals are: to identify the obstacles that prevent women achieving senior roles in the sciences

Du, Jie

153

A Comparison of Extra-tropical Cyclones in Recent Re-analyses; ERA-INTERIM, NASA-MERRA,  

E-Print Network [OSTI]

separation of the identically same cyclones is typically less than 20 geodesic in both hemispheresA Comparison of Extra-tropical Cyclones in Recent Re-analyses; ERA-INTERIM, NASA-MERRA, NCEP Corresponding author: Kevin Hodges email: kih@mail.nerc-essc.ac.uk #12;Abstract Extra-tropical cyclones

Hodges, Kevin

154

Re: Corrected Memorandum Summarizing Ex Parte Communication  

Broader source: Energy.gov (indexed) [DOE]

(sent via email) Re: Corrected Memorandum Summarizing Ex Parte Communication This memorandum is submitted to revise and correct our earlier memorandum...

155

Litchfield Correctional Center District Heating Low Temperature...  

Open Energy Info (EERE)

Correctional Center District Heating Low Temperature Geothermal Facility Jump to: navigation, search Name Litchfield Correctional Center District Heating Low Temperature Geothermal...

156

Corrections APPLIED PHYSICAL SCIENCES, BIOPHYSICS AND  

E-Print Network [OSTI]

Corrections APPLIED PHYSICAL SCIENCES, BIOPHYSICS AND COMPUTATIONAL BIOLOGY Correction gene, MyHC-IIb, which is thought under most circumstances not to be expressed. The physiological

Spudich, James A.

157

Plutonium Surveillance Destructive Examination Requirements at Savannah River National Laboratory for K-Area Interim Surveillance  

SciTech Connect (OSTI)

The DOE 3013 storage standard requires nested, welded 300 series stainless steel containers to store plutonium-bearing materials for up to 50 years. Packaged contents include stabilized plutonium-bearing residues that contain chloride salts and a low (< 0.5 weight %) water content. The DOE 3013 STD requires surveillance of the packages over the 50 year lifetime. These surveillance requirements have been further defined by the Integrated Surveillance Program to include both non-destructive examination (NDE) and destructive examination (DE) of the 3013 container. The DE portion of surveillance involves examining the 3013 nested containers, analyzing the head space gas, and evaluating the plutonium oxide chemistry. At SRS, the stored 3013 containers will undergo preparation for the DE surveillance activities in facilities located in K-Area. The actual DE surveillance will be performed in SRNL. This report provides preliminary functional requirements for the destructive examination (DE) of plutonium-bearing oxide materials and containers in support of K-Area Interim Surveillance (KIS). The KIS project will install interim facilities to prepare the samples for analysis in SRNL. This document covers the requirements for the interim period beginning in 2007, and lasting until the Container Storage and Surveillance Capability (CSSC) project provides the permanent facilities in K-Area to perform sampling and repackaging operations associated with the 3013 container storage and surveillance program. Initial requirements for the CSSC project have been previously defined in WSRC-TR-2004-00584 ''Plutonium Surveillance Destructive Examination Requirements at Savannah River National Laboratory''. As part of the Plutonium Surveillance Program of 3013 Containers at the Savannah River Site (SRS), the Savannah River National Laboratory (SRNL) will receive the emptied 3013 container components, plutonium oxide samples and headspace gas samples from K-Area. The DE program scope includes chemical and metallurgical analyses for a maximum of 25 DE sets a year to provide essential data in support of the SRS Plutonium Surveillance Program. The normal operation is expected to be approximately 15 DE sets a year.

Stefek, T. M.

2005-09-29T23:59:59.000Z

158

Correction  

E-Print Network [OSTI]

ERRATUM. A.E. Eremenko: Meromorphic solutions of algebraic differential equations. Russian Mathematical Surveys 37:4, 61 -95. The author has sent the ...

2005-11-08T23:59:59.000Z

159

Fluid inflation with brane correction  

E-Print Network [OSTI]

In this paper, we have investigated the possibility to have inflation from inhomogeneous viscous fluids by taking into account the brane correction coming from string-inspired five dimensional Einsten's gravity. We have realized several kinds of viable solutions for early-time acceleration. At the end of inflation, the classical Einstein's gravity is recovered and fluids produce decelerated expansion.

Ratbay Myrzakulov; Lorenzo Sebastiani

2014-11-03T23:59:59.000Z

160

Interim Status Closure Plan Open Burning Treatment Unit Technical Area 16-399 Burn Tray  

SciTech Connect (OSTI)

This closure plan describes the activities necessary to close one of the interim status hazardous waste open burning treatment units at Technical Area (TA) 16 at the Los Alamos National Laboratory (LANL or the Facility), hereinafter referred to as the 'TA-16-399 Burn Tray' or 'the unit'. The information provided in this closure plan addresses the closure requirements specified in the Code of Federal Regulations (CFR), Title 40, Part 265, Subparts G and P for the thermal treatment units operated at the Facility under the Resource Conservation and Recovery Act (RCRA) and the New Mexico Hazardous Waste Act. Closure of the open burning treatment unit will be completed in accordance with Section 4.1 of this closure plan.

Vigil-Holterman, Luciana R. [Los Alamos National Laboratory

2012-05-07T23:59:59.000Z

Note: This page contains sample records for the topic "icm interim corrective" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


161

Diesel Emission Control -- Sulfur Effects (DECSE) Program; Phase I Interim Data Report No. 1  

SciTech Connect (OSTI)

The Diesel Emission Control-Sulfur Effects (DECSE) is a joint government/industry program to determine the impact of diesel fuel sulfur levels on emission control systems whose use could lower emissions of nitrogen oxides (NO{sub x}) and particulate matter (PM) from on-highway trucks in the 2002--2004 model years. Phase 1 of the program was developed with the following objectives in mind: (1) evaluate the effects of varying the level of sulfur content in the fuel on the emission reduction performance of four emission control technologies; and (2) measure and compare the effects of up to 250 hours of aging on selected devices for multiple levels of fuel sulfur content. This interim data report summarizes results as of August, 1999, on the status of the test programs being conducted on three technologies: lean-NO{sub x} catalysts, diesel particulate filters and diesel oxidation catalysts.

DOE; ORNL; NREL; EMA; MECA

1999-08-15T23:59:59.000Z

162

Deep Vadose Zone Treatability Test for the Hanford Central Plateau: Interim Post-Desiccation Monitoring Results  

SciTech Connect (OSTI)

A field test of desiccation is being conducted as an element of the deep vadose zone treatability test program. Desiccation technology relies on removal of water from a portion of the subsurface such that the resultant low moisture conditions inhibit downward movement of water and dissolved contaminants. Previously, a field test report (Truex et al. 2012a) was prepared describing the active desiccation portion of the test and initial post-desiccation monitoring data. Additional monitoring data have been collected at the field test site during the post-desiccation period and is reported herein along with interpretation with respect to desiccation performance. This is an interim report including about 2 years of post-desiccation monitoring data.

Truex, Michael J.; Oostrom, Martinus; Strickland, Christopher E.; Johnson, Timothy C.; Johnson, Christian D.; Clayton, Ray E.; Chronister, Glen B.

2013-09-01T23:59:59.000Z

163

Interim report on updated microarray probes for the LLNL Burkholderia pseudomallei SNP array  

SciTech Connect (OSTI)

The overall goal of this project is to forensically characterize 100 unknown Burkholderia isolates in the US-Australia collaboration. We will identify genome-wide single nucleotide polymorphisms (SNPs) from B. pseudomallei and near neighbor species including B. mallei, B. thailandensis and B. oklahomensis. We will design microarray probes to detect these SNP markers and analyze 100 Burkholderia genomic DNAs extracted from environmental, clinical and near neighbor isolates from Australian collaborators on the Burkholderia SNP microarray. We will analyze the microarray genotyping results to characterize the genetic diversity of these new isolates and triage the samples for whole genome sequencing. In this interim report, we described the SNP analysis and the microarray probe design for the Burkholderia SNP microarray.

Gardner, S; Jaing, C

2012-03-27T23:59:59.000Z

164

Interim storage cask (ISC), a concrete and steel dry storage cask  

SciTech Connect (OSTI)

General Atomics (GA) has designed and is currently fabricating the Interim Storage Cask (ISC) for Westinghouse Hanford Company (WHC). The ISC is a dry storage cask that will safely store a Core Component Container (CCC) with Fast Flux Test Facility (FFTF) spent fuel assemblies or fuel pin containers for a period of up to 50 years at the US Department of Energy (DOE) Hanford site. The cask may also be used to transfer the fuel to different areas within the Hanford site. The ISC is designed to stringent criteria from both 10CFR71 and 10CFR72 for safe storage and on-site transportation of FFTF spent fuel and fuel pin containers. The cask design uses a combination of steel and concrete materials to achieve a cost-effective means of storing spent fuel. The casks will be extensively tested before use to verify that the design and construction meet the design requirements.

Grenier, R.M.; Koploy, M.A. [General Atomics, San Diego, CA (United States)

1995-12-31T23:59:59.000Z

165

Energy conservation potential of the US Department of Energy interim commercial building standards  

SciTech Connect (OSTI)

This report describes a project conducted to demonstrate the whole-building energy conservation potential achievable from full implementation of the US Department of Energy (DOE) Interim Energy Conservation Performance Standards for New Commercial and Multi-Family High Rise Residential Buildings. DOE`s development and implementation of energy performance standards for commercial buildings were established by the Energy Conservation Standards for New Buildings Act of 1976, as amended, Public Law (PL) 94-385, 42 USC 6831 et seq., hereinafter referred to as the Act. In accordance with the Act, DOE was to establish performance standards for both federal and private sector buildings ``to achieve the maximum practicable improvements in energy efficiency and use of non-depletable resources for all new buildings``.

Hadley, D.L.; Halverson, M.A.

1993-12-01T23:59:59.000Z

166

PROJECT W-551 SUMMARY INFORMATION FOR EARLY LAW INTERIM PRETREATMENT SYSTEM SELECTION  

SciTech Connect (OSTI)

This report provides summary data for use by the decision board to assess and select the final technology for project W-551, Interim Pretreatment System. This project will provide early pretreated low activity waste feed to the Waste Treatment Plant to allow Waste Treatment Plan Low Activity Waste facility operation prior to construction completion of the Pretreatment and High Level Waste facilities. The candidate solids separations technologies are rotary microfiltration and crossflow filtration, and the candidate cesium separation technologies are fractional crystallization, caustic-side solvent extraction, and ion-exchange using spherical resorcinol-fonnaldebyde resin. This document provides a summary of comparative data against prior weighted criteria to support technology selection. Supporting details and background for this summary are documented in the separate report, RPP-RPT-37741.

TEDESCHI AR

2008-08-11T23:59:59.000Z

167

PROJECT W-551 DETERMINATION DATA FOR EARLY LAW INTERIM PRETREATMENT SYSTEM SELECTION  

SciTech Connect (OSTI)

This report provides the detailed assessment forms and data for selection of the solids separation and cesium separation technology for project W-551, Interim Pretreatment System. This project will provide early pretreated low activity waste feed to the Waste Treatment Plant to allow Waste Treatment Plan Low Activity Waste facility operation prior to construction completion of the Pretreatment and High Level Waste facilities. The candidate solids separations technologies are rotary microfiltration and crossflow filtration, and the candidate cesium separation technologies are fractional crystallization, caustic-side solvent extraction, and ion-exchange using spherical resorcinol-formaldehyde resin. This data was used to prepare a cross-cutting technology summary, reported in RPP-RPT-37740.

TEDESCHI AR

2008-08-11T23:59:59.000Z

168

Design requirements document for Project W-465, immobilized low-activity waste interim storage  

SciTech Connect (OSTI)

The scope of this Design Requirements Document (DRD) is to identify the functions and associated requirements that must be performed to accept, transport, handle, and store immobilized low-activity waste (ILAW) produced by the privatized Tank Waste Remediation System (TWRS) treatment contractors. The functional and performance requirements in this document provide the basis for the conceptual design of the TWRS ILAW Interim Storage facility project and provides traceability from the program level requirements to the project design activity. Technical and programmatic risk associated with the TWRS planning basis are discussed in the Tank Waste Remediation System Decisions and Risk Assessment (Johnson 1994). The design requirements provided in this document will be augmented by additional detailed design data documented by the project.

Burbank, D.A.

1998-05-19T23:59:59.000Z

169

40 CFR 265 interim-status ground-water monitoring plan for the 2101-M pond  

SciTech Connect (OSTI)

This report outlines a ground-water monitoring plan for the 2101-M pond, located in the southwestern part of the 200-East Area on the Hanford Site in south-central Washington State. It has been determined that hazardous materials may have been discharged to the pond. Installation of an interim-status ground-water monitoring system is required under the Resource Conservation and Recovery Act to determine if hazardous chemicals are moving out of the pond. This plan describes the location of new wells for the monitoring system, how the wells are to be completed, the data to be collected, and how those data can be used to determine the source and extent of any ground-water contamination from the 2101-M pond. Four new wells are planned, one upgradient and three downgradient. 35 refs., 12 figs., 9 tabs.

Chamness, M.A.; Luttrell, S.P.; Dudziak, S.

1989-03-01T23:59:59.000Z

170

Interim-status groundwater monitoring plan for the 216-B-63 trench. Revision 1  

SciTech Connect (OSTI)

This document outlines the groundwater monitoring plan for interim-status detection-level monitoring of the 216-B-63 Trench. This is a revision of the initial groundwater monitoring plan prepared for Westinghouse Hanford Company (WHC) by Bjornstad and Dudziak (1989). The 216-B-63 Trench, located at the Hanford Site in south-central Washington State, is an open, unlined, earthern trench approximately 1.2 m (4 ft) wide at the bottom, 427 m (1400 ft) long, and 3 m (10 ft) deep that received wastewater containing hazardous waste and radioactive materials from B Plant, located in the 200 East Area. Liquid effluent discharge to the 216-B-63 Trench began in March 1970 and ceased in February 1992. The trench is now managed by Waste Tank Operations.

Sweeney, M.D.

1995-06-13T23:59:59.000Z

171

Evaluation of 2004 Toyota Prius Hybrid Electric Drive System Interim Report  

SciTech Connect (OSTI)

Laboratory tests were conducted to evaluate the electrical and mechanical performance of the 2004 Toyota Prius and its hybrid electric drive system. As a hybrid vehicle, the 2004 Prius uses both a gasoline-powered internal combustion engine and a battery-powered electric motor as motive power sources. Innovative algorithms for combining these two power sources results in improved fuel efficiency and reduced emissions compared to traditional automobiles. Initial objectives of the laboratory tests were to measure motor and generator back-electromotive force (emf) voltages and determine gearbox-related power losses over a specified range of shaft speeds and lubricating oil temperatures. Follow-on work will involve additional performance testing of the motor, generator, and inverter. Information contained in this interim report summarizes the test results obtained to date, describes preliminary conclusions and findings, and identifies additional areas for further study.

Ayers, C.W.

2004-11-23T23:59:59.000Z

172

Interim Safe Storage of Plutonium Production Reactors at the US DOE Hanford Site - 13438  

SciTech Connect (OSTI)

Nine plutonium production reactors located on DOE's Hanford Site are being placed into an Interim Safe Storage (ISS) period that extends to 2068. The Environmental Impact Statement (EIS) for ISS [1] was completed in 1993 and proposed a 75-year storage period that began when the EIS was finalized. Remote electronic monitoring of the temperature and water level alarms inside the safe storage enclosure (SSE) with visual inspection inside the SSE every 5 years are the only planned operational activities during this ISS period. At the end of the ISS period, the reactor cores will be removed intact and buried in a landfill on the Hanford Site. The ISS period allows for radioactive decay of isotopes, primarily Co-60 and Cs-137, to reduce the dose exposure during disposal of the reactor cores. Six of the nine reactors have been placed into ISS by having an SSE constructed around the reactor core. (authors)

Schilperoort, Daryl L.; Faulk, Darrin [Washington Closure Hanford, 2620 Fermi Avenue, Richland, Washington 99352 (United States)] [Washington Closure Hanford, 2620 Fermi Avenue, Richland, Washington 99352 (United States)

2013-07-01T23:59:59.000Z

173

1999 Annual Mixed Waste Management Facility Groundwater Correction - Action Report (Volumes I, II, and III)  

SciTech Connect (OSTI)

This Corrective Action Report (CAR) for the Mixed Waste Management Facility (MWMF) is being prepared to comply with the Resource Conservation and Recovery Act (RCRA) Permit Number SC1 890 008 989, dated October 31, 1999. This CAR compiles and presents all groundwater sampling and monitoring activities that are conducted at the MWMF. As set forth in previous agreements with South Carolina Department of Health and Environmental Control (SCDHEC), all groundwater associated with the Burial Ground Complex (BGC) (comprised of the MWMF, Low-Level Radioactive Waste Disposal Facility, and Old Radioactive Waste Burial Ground) will be addressed under this RCRA Permit. This CAR is the first to be written for the MWMF and presents monitoring activities and results as an outcome of Interim Status and limited Permitted Status activities. All 1999 groundwater monitoring activities were conducted while the MWMF was operated during Interim Status. Changes to the groundwater monitoring program were made upon receipt of the RCRA Permit, where feasible. During 1999, 152 single-screened and six multi-screened groundwater monitoring wells at the BGC monitored groundwater quality in the uppermost aquifer as required by the South Carolina Hazardous Waste Management Regulations (SCHWMR), settlement agreements 87-52-SW and 91-51-SW, and RCRA Permit SC1 890 008 989. However, overall compliance with the recently issued RCRA Permit could not be implemented until the year 2000 due to the effective date of the RCRA Permit and scheduling of groundwater monitoring activities. Changes have been made to the groundwater monitoring network to meet Permit requirements for all 2000 sampling events.

Chase, J.

2000-06-14T23:59:59.000Z

174

K-corrections and extinction corrections for Type Ia supernovae  

SciTech Connect (OSTI)

The measurement of the cosmological parameters from Type Ia supernovae hinges on our ability to compare nearby and distant supernovae accurately. Here we present an advance on a method for performing generalized K-corrections for Type Ia supernovae which allows us to compare these objects from the UV to near-IR over the redshift range 0 < z < 2. We discuss the errors currently associated with this method and how future data can improve upon it significantly. We also examine the effects of reddening on the K-corrections and the light curves of Type Ia supernovae. Finally, we provide a few examples of how these techniques affect our current understanding of a sample of both nearby and distant supernovae.

Nugent, Peter; Kim, Alex; Perlmutter, Saul

2002-05-21T23:59:59.000Z

175

Radiosondes Corrected for Inaccuracy in RH Measurements  

DOE Data Explorer [Office of Scientific and Technical Information (OSTI)]

Corrections for inaccuracy in Vaisala radiosonde RH measurements have been applied to ARM SGP radiosonde soundings. The magnitude of the corrections can vary considerably between soundings. The radiosonde measurement accuracy, and therefore the correction magnitude, is a function of atmospheric conditions, mainly T, RH, and dRH/dt (humidity gradient). The corrections are also very sensitive to the RH sensor type, and there are 3 Vaisala sensor types represented in this dataset (RS80-H, RS90, and RS92). Depending on the sensor type and the radiosonde production date, one or more of the following three corrections were applied to the RH data: Temperature-Dependence correction (TD), Contamination-Dry Bias correction (C), Time Lag correction (TL). The estimated absolute accuracy of NIGHTTIME corrected and uncorrected Vaisala RH measurements, as determined by comparison to simultaneous reference-quality measurements from Holger Voemel's (CU/CIRES) cryogenic frostpoint hygrometer (CFH), is given by Miloshevich et al. (2006).

Miloshevich, Larry

176

NNWSI PROJECT ELEMENT WBS-1.2.6.9.4.6.1.B INTERIM REPORT ON DUST CONTROL PROPOSALS  

SciTech Connect (OSTI)

This report presents interim findings of studies conducted to evaluate dust control equipment during prototype drilling. Based on available data on silica content, type, particle size, and on proposed dry drilling operations, it is estimated that allowable exposures to free silica will range from 0.07 to 1.5 mg/cu meter. They have concluded that airborne concentrations of dust may approach or exceed these values during normal operations, based on studies conducted as part of this task.

D.J. Burton

2005-09-06T23:59:59.000Z

177

RCRA, superfund and EPCRA hotline training module. Introduction to: Permits and interim status (40 cfr part 270) updated July 1996  

SciTech Connect (OSTI)

Owners/operators of facilities that treat, store, or dispose of hazardous waste must obtain an operating permit, as required by Subtitle C of the Resource Conservation and Recovery Act (RCRA). The module presents an overview of the RCRA permitting process and the requirements that apply to TSDFs operating under interim status until a permit is issued. The regulations governing the permit process are found in 40 CFR Parts 124 through 270.

NONE

1996-07-01T23:59:59.000Z

178

Interim Status Groundwater Monitoring Plan for Low-Level Waste Management Areas 1 to 4, RCRA Facilities, Hanford,Washington  

SciTech Connect (OSTI)

This document describes the monitoring plan to meet the requirements for interim status groundwater monitoring at Hanford Site low-level waste burial grounds as specified by 40 CFR 265, incorporated by reference in WAC 173-303-400. The monitoring will take place at four separate low-level waste management areas in the 200-West and 200-East Areas, in the central part of the site. This plan replaces the previous monitoring plan.

Dresel, P Evan

2004-10-25T23:59:59.000Z

179

CORRECTIVE ACTION PLAN FOR CORRECTIVE ACTION UNIT 543: LIQUID DISPOSAL UNITS, NEVADA TEST SITE, NEVADA  

SciTech Connect (OSTI)

The purpose of this Corrective Action Plan is to provide the detailed scope of work required to implement the recommended corrective actions as specified in the approved Corrective Action Decision Document.

NONE

2006-09-01T23:59:59.000Z

180

Helioseismic determination of opacity corrections  

E-Print Network [OSTI]

We investigate the effect of localized opacity modifications on the sound-speed profile of solar models. The sound-speed difference between the Sun and a solar model is used to deduce the opacity correction that would be required to bring the model into agreement with the Sun. We test this procedure on artificial data for a pair of solar models and apply it to the solar sound speed as inferred from inversion of LOWL observed frequencies. We show that a solar model constructed with the appropriately modified opacity has a sound-speed profile very similar to that of the Sun.

S. C. Tripathy; Sarbani Basu; J. Christensen-Dalsgaard

1997-03-28T23:59:59.000Z

Note: This page contains sample records for the topic "icm interim corrective" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


181

Integrated Computational Materials Engineering (ICME) for Mg...  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

2 DOE Hydrogen and Fuel Cells Program and Vehicle Technologies Program Annual Merit Review and Peer Evaluation Meeting lm012li2012...

182

Integrated Computational Materials Engineering (ICME) for Mg...  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

1 DOE Hydrogen and Fuel Cells Program, and Vehicle Technologies Program Annual Merit Review and Peer Evaluation lm012li2011...

183

Diffusion Databases for ICME | Department of Energy  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE:YearRound-UpHeat Pump Models |Conduct, Parent(CRADA and DOW Automotive) |and DPF | Department

184

Corrective Action Decision Document/Corrective Action Plan for the 92-Acre Area and Corrective Action Unit 111: Area 5 WMD Retired Mixed Waste Pits, Nevada Test Site, Nevada  

SciTech Connect (OSTI)

This Corrective Action Decision Document/Corrective Action Plan (CADD/CAP) has been prepared for the 92-Acre Area, the southeast quadrant of the Radioactive Waste Management Site, located in Area 5 of the Nevada Test Site (NTS). The 92-Acre Area includes Corrective Action Unit (CAU) 111, 'Area 5 WMD Retired Mixed Waste Pits.' Data Quality Objectives (DQOs) were developed for the 92-Acre Area, which includes CAU 111. The result of the DQO process was that the 92-Acre Area is sufficiently characterized to provide the input data necessary to evaluate corrective action alternatives (CAAs) without the collection of additional data. The DQOs are included as Appendix A of this document. This CADD/CAP identifies and provides the rationale for the recommended CAA for the 92-Acre Area, provides the plan for implementing the CAA, and details the post-closure plan. When approved, this CADD/CAP will supersede the existing Pit 3 (P03) Closure Plan, which was developed in accordance with Title 40 Code of Federal Regulations (CFR) Part 265, 'Interim Status Standards for Owners and Operators of Hazardous Waste Treatment, Storage, and Disposal Facilities.' This document will also serve as the Closure Plan and the Post-Closure Plan, which are required by 40 CFR 265, for the 92-Acre Area. After closure activities are complete, a request for the modification of the Resource Conservation and Recovery Act Permit that governs waste management activities at the NTS will be submitted to the Nevada Division of Environmental Protection to incorporate the requirements for post-closure monitoring. Four CAAs, ranging from No Further Action to Clean Closure, were evaluated for the 92-Acre Area. The CAAs were evaluated on technical merit focusing on performance, reliability, feasibility, safety, and cost. Based on the evaluation of the data used to develop the conceptual site model; a review of past, current, and future operations at the site; and the detailed and comparative analysis of the potential CAAs, Closure in Place with Administrative Controls is the preferred CAA for the 92-Acre Area. Closure activities will include the following: (1) Constructing an engineered evapotranspiration cover over the 92-Acre Area; (2) Installing use restriction (UR) warning signs, concrete monuments, and subsidence survey monuments; (3) Establishing vegetation on the cover; (4) Implementing a UR; and (5) Implementing post-closure inspections and monitoring. The Closure in Place with Administrative Controls alternative meets all requirements for the technical components evaluated, fulfills all applicable federal and state regulations for closure of the site, and will minimize potential future exposure pathways to the buried waste at the site.

NSTec Environmental Restoration

2009-07-31T23:59:59.000Z

185

Corrective Action Decision Document/Corrective Action Plan for the 92-Acre Area and Corrective Action Unit 111: Area 5 WMD Retired Mixed Waste Pits, Nevada National Security Site, Nevada  

SciTech Connect (OSTI)

This Corrective Action Decision Document/Corrective Action Plan (CADD/CAP) has been prepared for the 92-Acre Area, the southeast quadrant of the Radioactive Waste Management Site, located in Area 5 of the Nevada National Security Site (NNSS). The 92-Acre Area includes Corrective Action Unit (CAU) 111, 'Area 5 WMD Retired Mixed Waste Pits.' Data Quality Objectives (DQOs) were developed for the 92-Acre Area, which includes CAU 111. The result of the DQO process was that the 92-Acre Area is sufficiently characterized to provide the input data necessary to evaluate corrective action alternatives (CAAs) without the collection of additional data. The DQOs are included as Appendix A of this document. This CADD/CAP identifies and provides the rationale for the recommended CAA for the 92-Acre Area, provides the plan for implementing the CAA, and details the post-closure plan. When approved, this CADD/CAP will supersede the existing Pit 3 (P03) Closure Plan, which was developed in accordance with Title 40 Code of Federal Regulations (CFR) Part 265, 'Interim Status Standards for Owners and Operators of Hazardous Waste Treatment, Storage, and Disposal Facilities.' This document will also serve as the Closure Plan and the Post-Closure Plan, which are required by 40 CFR 265, for the 92-Acre Area. After closure activities are complete, a request for the modification of the Resource Conservation and Recovery Act Permit that governs waste management activities at the NNSS will be submitted to the Nevada Division of Environmental Protection to incorporate the requirements for post-closure monitoring. Four CAAs, ranging from No Further Action to Clean Closure, were evaluated for the 92-Acre Area. The CAAs were evaluated on technical merit focusing on performance, reliability, feasibility, safety, and cost. Based on the evaluation of the data used to develop the conceptual site model; a review of past, current, and future operations at the site; and the detailed and comparative analysis of the potential CAAs, Closure in Place with Administrative Controls is the preferred CAA for the 92-Acre Area. Closure activities will include the following: (1) Constructing an engineered evapotranspiration cover over the 92-Acre Area; (2) Installing use restriction (UR) warning signs, concrete monuments, and subsidence survey monuments; (3) Establishing vegetation on the cover; (4) Implementing a UR; and (5) Implementing post-closure inspections and monitoring. The Closure in Place with Administrative Controls alternative meets all requirements for the technical components evaluated, fulfills all applicable federal and state regulations for closure of the site, and will minimize potential future exposure pathways to the buried waste at the site.

NSTec Environmental Restoration

2010-11-22T23:59:59.000Z

186

Online Monitoring Technical Basis and Analysis Framework for Large Power Transformers; Interim Report for FY 2012  

SciTech Connect (OSTI)

The Light Water Reactor Sustainability program at Idaho National Laboratory (INL) is actively conducting research to develop and demonstrate online monitoring (OLM) capabilities for active components in existing Nuclear Power Plants. A pilot project is currently underway to apply OLM to Generator Step-Up Transformers (GSUs) and Emergency Diesel Generators (EDGs). INL and the Electric Power Research Institute (EPRI) are working jointly to implement the pilot project. The EPRI Fleet-Wide Prognostic and Health Management (FW-PHM) Software Suite will be used to implement monitoring in conjunction with utility partners: the Shearon Harris Nuclear Generating Station (owned by Duke Energy for GSUs, and Braidwood Generating Station (owned by Exelon Corporation) for EDGs. This report presents monitoring techniques, fault signatures, and diagnostic and prognostic models for GSUs. GSUs are main transformers that are directly connected to generators, stepping up the voltage from the generator output voltage to the highest transmission voltages for supplying electricity to the transmission grid. Technical experts from Shearon Harris are assisting INL and EPRI in identifying critical faults and defining fault signatures associated with each fault. The resulting diagnostic models will be implemented in the FW-PHM Software Suite and tested using data from Shearon-Harris. Parallel research on EDGs is being conducted, and will be reported in an interim report during the first quarter of fiscal year 2013.

Nancy J. Lybeck; Vivek Agarwal; Binh T. Pham; Heather D. Medema; Kirk Fitzgerald

2012-09-01T23:59:59.000Z

187

Online Monitoring Technical Basis and Analysis Framework for Emergency Diesel Generators - Interim Report for FY 2013  

SciTech Connect (OSTI)

The Light Water Reactor Sustainability program at Idaho National Laboratory is actively conducting research to develop and demonstrate online monitoring capabilities for active components in existing nuclear power plants. Idaho National Laboratory and the Electric Power Research Institute are working jointly to implement a pilot project to apply these capabilities to emergency diesel generators and generator step-up transformers. The Electric Power Research Institute Fleet-Wide Prognostic and Health Management Software Suite will be used to implement monitoring in conjunction with utility partners: Braidwood Generating Station (owned by Exelon Corporation) for emergency diesel generators, and Shearon Harris Nuclear Generating Station (owned by Duke Energy Progress) for generator step-up transformers. This report presents monitoring techniques, fault signatures, and diagnostic and prognostic models for emergency diesel generators. Emergency diesel generators provide backup power to the nuclear power plant, allowing operation of essential equipment such as pumps in the emergency core coolant system during catastrophic events, including loss of offsite power. Technical experts from Braidwood are assisting Idaho National Laboratory and Electric Power Research Institute in identifying critical faults and defining fault signatures associated with each fault. The resulting diagnostic models will be implemented in the Fleet-Wide Prognostic and Health Management Software Suite and tested using data from Braidwood. Parallel research on generator step-up transformers was summarized in an interim report during the fourth quarter of fiscal year 2012.

Binh T. Pham; Nancy J. Lybeck; Vivek Agarwal

2012-12-01T23:59:59.000Z

188

Accelerated alpha radiation damage in a ceramic waste form, interim results  

SciTech Connect (OSTI)

Interim results are presented on the alpha-decay damage study of a {sup 238}Pu-loaded ceramic waste form (CWF). The waste form was developed to immobilize fission products and transuranic species accumulated from the electrometallurgical treatment of spent nuclear fuel. To evaluate the effects of {alpha}-decay damage on the waste form the {sup 238}Pu-loaded material was analyzed by (1) x-ray diffraction (XRD), (2) microstructure characterization by scanning electron microscopy (SEM) and transmission electron microscopy (TEM) with energy and wavelength dispersive spectroscopy (EDS/WDS) and electron diffraction, (3) bulk density measurements and (4) waste form durability, performed by the product consistency test (PCT). While the predominate phase of plutonium in the CWF, PuO{sub 2}, shows the expected unit cell expansion due to {alpha}-decay damage, currently no significant change has occurred to the macro- or microstructure of the material. The major phase of the waste form is sodalite and contains very little Pu, although the exact amount is unknown. Interestingly, measurement of the sodalite phase unit cell is also showing very slight expansion; again, presumably from {alpha}-decay damage.

Frank, S. M.; Johnson, S. G.; Moschetti, T. L.; O'Holleran, T. P.; Sinkler, W.; Esh, D.; Goff, K. M.

1999-11-11T23:59:59.000Z

189

Interim report:feasibility of microscale glucose reforming for renewable hydrogen.  

SciTech Connect (OSTI)

Micro-scale aqueous steam reforming of glucose is suggested as a novel method of H{sub 2} production for micro fuel cells. Compact fuel cell systems are a viable alternative to batteries as a portable electrical power source. Compared with conventional lithium polymer batteries, hydrocarbon powered fuel cells are smaller, weigh less, and have a much higher energy density. The goal of this project is to develop a hydrocarbon powered microfuel processor capable of driving an existing microfuel cell, and this interim report provides a summary of the engineering information for microscale reforming of carbohydrates and the summarizes the work completed as of September 2006. Work on this program will continue. Gas analysis of the gas evolved from glucose breakdown using a quadrupole mass spectrometer is now possible due do significant modifications to the vacuum chamber and to the mass spectrometer electronics. Effective adhesion of Pt/Al{sub 2}O{sub 3} to 316SS microstructured catalyst plates is still under investigation. Electrophoretic and dip coat methods of catalyst deposition have produced coatings with poor adhesion and limited available Pt surface area.

Norman, Kirsten (New Mexico Institute of Mining and Technology, Socorro, NM)

2007-03-01T23:59:59.000Z

190

Resource Conservation and Recovery Act (RCRA) Closure Plan Summary for Interim reasctive Waste Treatment Area (IRWTA)  

SciTech Connect (OSTI)

This closure plan has been prepared for the interim Reactive Waste Treatment Area (IRWT'A) located at the Y-12 Pkmt in oak Ridge, Tennessee (Environmental Protection Agency [EPA] Identification TN 389-009-0001). The actions required to achieve closure of the IRWTA are outlined in this plan, which is being submitted in accordance with Tennessee Ruie 1200- 1-1 1-.0S(7) and Title 40, Code of Federal Regulations (CFR), Part 265, Subpart G. The IRWTA was used to treat waste sodium and potassium (NaK) that are regulated by the Resource Conservation and Recovery Act (RCRA). The location of the IRWT'A is shown in Figures 1 and 2, and a diagram is shown in Figure 3. This pkm details all steps that wdi be petiormed to close the IRWTA. Note that this is a fmai ciosure.and a diagram is shown in Figure 3. This pkm details all steps that wdi be petiormed to close the IRWTA. Note that this is a fmai ciosure.

Collins, E.T.

1997-07-01T23:59:59.000Z

191

National climate change action plans: Interim report for developing and transition countries  

SciTech Connect (OSTI)

Under its Support for National Action Plans (SNAP) initiative, the U.S. Country Studies Program is providing financial and technical assistance to 18 countries for the development of climate change action plans. Although most of the countries have not yet completed their plans, the important lessons learned thus far are valuable and should be shared with other countries and international institutions that have an interest in the process of action plan development. This interim report describes the experience of 11 countries that are the furthest along in their planning activity and who have offered to share their results to date with the larger community of interested nations. These action plans delineate specific mitigation and adaptation measures that the countries will implement and integrate into their ongoing development programs. This report focuses on the measures the countries have selected and the methods they used to prepare their action plans. This executive summary presents key lessons and common themes using a structure similar to that used in the individual country chapters.

Benioff, R.; Ness, E.; Hirst, J. [eds.

1997-10-01T23:59:59.000Z

192

Safe interim storage of Hanford tank wastes, draft environmental impact statement, Hanford Site, Richland, Washington  

SciTech Connect (OSTI)

This Draft EIS is prepared pursuant to the National Environmental Policy Act (NEPA) and the Washington State Environmental Policy Act (SEPA). DOE and Ecology have identified the need to resolve near-term tank safety issues associated with Watchlist tanks as identified pursuant to Public Law (P.L.) 101-510, Section 3137, ``Safety Measures for Waste Tanks at Hanford Nuclear Reservation,`` of the National Defense Authorization Act for Fiscal Year 1991, while continuing to provide safe storage for other Hanford wastes. This would be an interim action pending other actions that could be taken to convert waste to a more stable form based on decisions resulting from the Tank Waste Remediation System (TWRS) EIS. The purpose for this action is to resolve safety issues concerning the generation of unacceptable levels of hydrogen in two Watchlist tanks, 101-SY and 103-SY. Retrieving waste in dilute form from Tanks 101-SY and 103-SY, hydrogen-generating Watchlist double shell tanks (DSTs) in the 200 West Area, and storage in new tanks is the preferred alternative for resolution of the hydrogen safety issues.

Not Available

1994-07-01T23:59:59.000Z

193

Performance testing of aged hydrogen getters against criteria for interim safe storage of plutonium bearing materials.  

SciTech Connect (OSTI)

Hydrogen getters were tested for use in storage of plutonium-bearing materials in accordance with DOE's Criteria for Interim Safe Storage of Plutonium Bearing Materials. The hydrogen getter HITOP was aged for 3 months at 70 C and tested under both recombination and hydrogenation conditions at 20 and 70 C; partially saturated and irradiated aged getter samples were also tested. The recombination reaction was found to be very fast and well above the required rate of 45 std. cc H2h. The gettering reaction, which is planned as the backup reaction in this deployment, is slower and may not meet the requirements alone. Pressure drop measurements and {sup 1}H NMR analyses support these conclusions. Although the experimental conditions do not exactly replicate the deployment conditions, the results of our conservative experiments are clear: the aged getter shows sufficient reactivity to maintain hydrogen concentrations below the flammability limit, between the minimum and maximum deployment temperatures, for three months. The flammability risk is further reduced by the removal of oxygen through the recombination reaction. Neither radiation exposure nor thermal aging sufficiently degrades the getter to be a concern. Future testing to evaluate performance for longer aging periods is in progress.

Shepodd, Timothy J.; Nissen, April; Buffleben, George M.

2006-01-01T23:59:59.000Z

194

Hydrogeology of the 200 Areas low-level burial grounds: An interim report: Volume 1, Text  

SciTech Connect (OSTI)

This report presents information derived from the installation of 35 ground-water monitoring wells around six low-level radioactive/hazardous waste burial grounds located in the 200 Areas of the Hanford Site in southeastern Washington State. This information was collected between May 20, 1987 and August 1, 1988. The contents of this report have been divided into two volumes. This volume contains the main text. Volume 2 contains the appendixes, including data and supporting information that verify content and results found in the main text. This report documents information collected by the Pacific Northwest Laboratory at the request of Westinghouse Hanford Company. Presented in this report are the preliminary interpretations of the hydrogeologic environment of six low-level burial grounds, which comprise four waste management areas (WMAs) located in the 200 Areas of the Hanford Site. This information and its accompanying interpretations were derived from sampling and testing activities associated with the construction of 35 ground-water monitoring wells as well as a multitude of previously existing boreholes. The new monitoring wells were installed as part of a ground-water monitoring program initiated in 1986. This ground-water monitoring program is based on requirements for interim status facilities in compliance with the Resource Conservation and Recovery Act (1976).

Last, G.V.; Bjornstad, B.N.; Bergeron, M.P.; Wallace, D.W.; Newcomer, D.R.; Schramke, J.A.; Chamness, M.A.; Cline, C.S.; Airhart, S.P.; Wilbur, J.S.

1989-01-01T23:59:59.000Z

195

Hazelwood Interim Storage Site environmental surveillance report for calendar year 1993  

SciTech Connect (OSTI)

This report summarizes the results of environmental surveillance activities conducted at the Hazelwood Interim Storage Site (HISS) during calendar year 1993. It includes an overview of site operations, the basis for monitoring for radioactive and non-radioactive parameters, summaries of environmental program at HISS, a summary of the results, and the calculated hypothetical radiation dose to the offsite population. Environmental surveillance activities were conducted in accordance with the site environmental monitoring plan, which describes the rationale and design criteria for the surveillance program, the frequency of sampling and analysis, specific sampling and analysis procedures, and quality assurance requirements. The US Department of Energy (DOE) began environmental monitoring of HISS in 1984, when the site was assigned to DOE by Congress through the energy and Water Development Appropriations Act and subsequent to DOE`s Formerly Utilized Sites Remediation Action Program (FUSRAP). Contamination at HISS originated from uranium processing work conducted at Mallinckrodt Chemical Works at the St. Louis Downtown Site (SLDS) from 1942 through 1957.

Not Available

1994-06-01T23:59:59.000Z

196

Environmental surveillance results for 1995 for the Hazelwood Interim Storage Site  

SciTech Connect (OSTI)

This memorandum presents and interprets analytical results and measurements obtained as part of the 1995 environmental surveillance program for the Hazelwood Interim Storage Site (HISS) under the Formerly Utilized Sites Remedial Action Program (FUSRAP). The discussion provides a comparative analysis of average historical background conditions and applicable regulatory criteria to the 1995 results reported for external gamma radiation and for samples from the media investigated (air, surface water, sediment, groundwater, and stormwater). Results from the 1995 environmental surveillance program at HISS indicate that, with the exception of thorium-230 in streambed sediment, applicable US Department of Energy (DOE) guidelines were not exceeded for any measured parameter or for any dose calculated for potentially exposed members of the general public. In the absence of sediment guidelines, DOE soil guidelines serve as a standard of comparison for data obtained from stream bed sediment; two samples from downstream locations contained concentrations of thorium-230 that exceeded DOE soil guidelines. All stormwater sample results were in compliance with permit-specified limits. Other radioactive materials include radium 226 and natural uranium.

McCague, J.C.

1996-06-01T23:59:59.000Z

197

Hazelwood Interim Storage Site environmental report for calendar year 1992, 9200 Latty Avenue, Hazelwood, Missouri  

SciTech Connect (OSTI)

This report describes the environmental surveillance program at the Hazelwood Interim storage Site (HISS) and surrounding area, provides the results for 1992, and discusses applicable environmental standards and requirements with which the results were compared. HISS is located in eastern Missouri in the City of Hazelwood (St. Louis County) and occupies approximately 2.2 ha (5.5 acres). Environmental monitoring of HISS began in 1984 when the site was assigned to the US Department of Energy (DOE) as part of the decontamination research and development project authorized by Congress under the 1984 Energy and Water Development Appropriations Act. DOE placed responsibility for HISS under the Formerly Utilized Sites Remedial Action Program (FUSRAP), which was established to identify and decontaminate or otherwise control sites where residual radioactive materials remain from the early years of the nation`s atomic energy program or from commercial operations causing conditions that Congress has authorized DOE to remedy. In 1992 there were no environmental occurrences or unplanned contaminant releases as defined in DOE requirements and in the Superfund Amendment and Reauthorization Act (SARA) Title III of CERCLA.

Not Available

1993-05-01T23:59:59.000Z

198

Power Transfer Potential to the Southeast in Response to a Renewable Portfolio Standard: Interim Report 1  

SciTech Connect (OSTI)

The power transfer potential for bringing renewable energy into the Southeast in response to a renewable portfolio standard (RPS) will depend not only on available transmission capacity but also on electricity supply and demand factors. This interim report examines how the commonly used EIA NEMS and EPRI NESSIE energy equilibrium models are considering such power transfers. Using regional estimates of capacity expansion and demand, a base case for 2008, 2020 and 2030 are compared relative to generation mix, renewable deployments, planned power transfers, and meeting RPS goals. The needed amounts of regional renewable energy to comply with possible RPS levels are compared to inter-regional transmission capacities to establish a baseline available for import into the Southeast and other regions. Gaps in the renewable generation available to meet RPS requirements are calculated. The initial finding is that the physical capability for transferring renewable energy into the SE is only about 10% of what would be required to meet a 20% RPS. Issues that need to be addressed in future tasks with respect to modeling are the current limitations for expanding renewable capacity and generation in one region to meet the demand in another and the details on transmission corridors required to deliver the power.

Hadley, Stanton W [ORNL; Key, Thomas S [Electric Power Research Institute (EPRI)

2009-03-01T23:59:59.000Z

199

Impacts of the extended-weight coal haul road system (interim report). Research report  

SciTech Connect (OSTI)

The Extended-Weight Coal Haul Road System, created by Kentucky`s Legislature in 1986, consists of all roads which carry over 50,000 tons of coal in a calendar year. Trucks hauling coal on this system are authorized to exceed normal weight limits through the payment of an annual decal fee. A research study was initiated in July of 1992 to analyze the impacts of the extended-weight system. This interim report prepared after one year of a three-year study, describes the analyses performed thus far and presents preliminary findings, recommendations, and a discussion of future work. Analyses in this report are based on: historical data on coal production and transportation; data from coal decal applications; interviews of legislators, transportation officials, coal company representatives, and coal trucking representatives: newspaper articles; vehicle classification data; a pavement cost analysis; and accident data. Preliminary conclusions include: (1) The extended-weight system has apparently been somewhat successful in accomplishing the primary objectives: to enhance the competitiveness and economic viability of Kentucky`s coal industry and to eliminate the perceived need for cal haulers to violate the law in order to be competitive; (2) Overall accident rates are no higher on the extended-weight system than on other comparable routes, but the fatal accident rate is significantly higher on the extended-weight system; (3) The coal-decal fee structure results in a net annual loss in Road Fund revenue of approximately $2 million; (4) Forty percent of the revenue from decal sales is allocated to the counties, although less than ten percent of the extended-weight system in county-maintained; (5) The heavier weights of coal-decal trucks add approximately $9 million annually to pavement overlay costs and increase other highway costs. (6) Road users throughout the state are subsidizing the movement of Kentucky coal by underwriting the increased costs.

Crabtree, J.D.; Pigman, J.G.; Deacon, J.A.; Agent, K.R.

1993-10-01T23:59:59.000Z

200

Sample Results From The Interim Salt Disposition Program Macrobatch 7 Tank 21H Qualification Samples  

SciTech Connect (OSTI)

Savannah River National Laboratory (SRNL) analyzed samples from Tank 21H in support of qualification of Macrobatch (Salt Batch) 7 for the Interim Salt Disposition Program (ISDP). An ARP and several ESS tests were also performed. This document reports characterization data on the samples of Tank 21H as well as simulated performance of ARP/MCU. No issues with the projected Salt Batch 7 strategy are identified, other than the presence of visible quantities of dark colored solids. A demonstration of the monosodium titanate (0.2 g/L) removal of strontium and actinides provided acceptable 4 hour average decontamination factors for Pu and Sr of 3.22 and 18.4, respectively. The Four ESS tests also showed acceptable behavior with distribution ratios (D(Cs)) values of 15.96, 57.1, 58.6, and 65.6 for the MCU, cold blend, hot blend, and Next Generation Solvent (NGS), respectively. The predicted value for the MCU solvent was 13.2. Currently, there are no models that would allow a prediction of extraction behavior for the other three solvents. SRNL recommends that a model for predicting extraction behavior for cesium removal for the blended solvent and NGS be developed. While no outstanding issues were noted, the presence of solids in the samples should be investigated in future work. It is possible that the solids may represent a potential reservoir of material (such as potassium) that could have an impact on MCU performance if they were to dissolve back into the feed solution. This salt batch is intended to be the first batch to be processed through MCU entirely using the new NGS-MCU solvent.

Peters, T. B.; Washington, A. L. II

2013-08-08T23:59:59.000Z

Note: This page contains sample records for the topic "icm interim corrective" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


201

Development of Thermal Analysis Capability of Dry Storage Cask for Spend Fuel Interim Storage  

SciTech Connect (OSTI)

As most of the nuclear power plants, on-site spent fuel pools (SFP) of Taiwan's plants were not originally designed with a storage capacity for all the spent fuel generated over the operating life by their reactors. For interim spent fuel storage, dry casks are one of the most reliable measures to on-site store over-filled assemblies from SFPs. The NUHOMS{sup R}-52B System consisting of a canister stored horizontally in a concrete module is selected for thermal evaluation in this paper. The performance of each cask in criticality, radioactive, material and thermal needs to be carefully addressed to ensure its enduring safety. Regarding the thermal features of dry storage casks, three different kinds of heat transfer mechanisms are involved, which include natural convection heat transfer outside and/or inside the canister, radiation heat transfer inside and outside the canister, and conduction heat transfer inside the canister. To analyze the thermal performance of dry storage casks, RELAP5-3D is adopted to calculate the natural air convection and radiation heat transfer outside the canister to the ambient environment, and ANSYS is applied to calculate the internal conduction and radiation heat transfer. During coupling iteration between codes, the heat energy across the canister wall needs to be conserved, and the inner wall temperature of the canister needs to be converged. By the coupling of RELAP5-3D and ANSYS, the temperature distribution within each fuel assembly inside canisters can be calculated and the peaking cladding temperature can be identified. (authors)

Fu-Kuang Ko; Liang, Thomas K.S.; Chung-Yu Yang [Institute of Nuclear Energy Research P.O. Box 3-3, Longtan, 32500, Taiwan (China)

2002-07-01T23:59:59.000Z

202

Interim measure conceptual design for remediation of source area contamination at Agra, Kansas.  

SciTech Connect (OSTI)

This document presents a conceptual design for the implementation of a non-emergency interim measure (IM) at the site of the grain storage facility formerly operated by the Commodity Credit Corporation of the U.S. Department of Agriculture (CCC/USDA) in Agra, Kansas. The IM is recommended to mitigate localized carbon tetrachloride contamination in the vadose zone soils at the former CCC/USDA facility and eliminate ongoing soil-to-groundwater contamination. The objectives of this IM conceptual design report include the following: 1. Obtain written acknowledgement from the Kansas Department of Health and the Environment (KDHE) that remediation on the former CCC/USDA property is required. 2. Provide information (IM description, justification for the IM, and project schedule) that the KDHE can include in a pending fact sheet. 3. Obtain KDHE approval for the IM conceptual design, so that the CCC/USDA can initiate a formal request for access to the privately owned property and proceed with preparation of a remedial design plan (RDP). Investigations conducted on behalf of the CCC/USDA by Argonne National Laboratory (Argonne 2006) have demonstrated that soil and groundwater at the Agra site are contaminated with carbon tetrachloride. The levels in groundwater exceed the Kansas Tier 2 Risk-Based Screening Level (RBSL) and the U.S. Environmental Protection Agency (EPA) maximum contaminant level (MCL) of 5.0 {micro}g/L for this compound. The soil and groundwater contamination identified at the former CCC/USDA facility currently poses no unacceptable health risks.

LaFreniere, L. M.; Environmental Science Division

2007-07-31T23:59:59.000Z

203

Plutonium uranium extraction (PUREX) end state basis for interim operation (BIO) for surveillance and maintenance  

SciTech Connect (OSTI)

This Basis for Interim Operation (BIO) was developed for the PUREX end state condition following completion of the deactivation project. The deactivation project has removed or stabilized the hazardous materials within the facility structure and equipment to reduce the hazards posed by the facility during the surveillance and maintenance (S and M) period, and to reduce the costs associated with the S and M. This document serves as the authorization basis for the PUREX facility, excluding the storage tunnels, railroad cut, and associated tracks, for the deactivated end state condition during the S and M period. The storage tunnels, and associated systems and areas, are addressed in WHC-SD-HS-SAR-001, Rev. 1, PUREX Final Safety Analysis Report. During S and M, the mission of the facility is to maintain the conditions and equipment in a manner that ensures the safety of the workers, environment, and the public. The S and M phase will continue until the final decontamination and decommissioning (D and D) project and activities are begun. Based on the methodology of DOE-STD-1027-92, Hazards Categorization and Accident Analysis Techniques for Compliance with DOE Order 5480.23, Nuclear Safety Analysis Reports, the final facility hazards category is identified as hazards category This considers the remaining material inventories, form and distribution of the material, and the energies present to initiate events of concern. Given the current facility configuration, conditions, and authorized S and M activities, there are no operational events identified resulting in significant hazard to any of the target receptor groups (e.g., workers, public, environment). The only accident scenarios identified with consequences to the onsite co-located workers were based on external natural phenomena, specifically an earthquake. The dose consequences of these events are within the current risk evaluation guidelines and are consistent with the expectations for a hazards category 2 facility.

DODD, E.N.

1999-05-12T23:59:59.000Z

204

Low-temperature catalytic gasification of wet industrial wastes. FY 1991--1992 interim report  

SciTech Connect (OSTI)

A catalytic gasification system operating in a pressurized water environment has been developed and refined at Pacific Northwest Laboratory (PNL) for over 12 years. Initial experiments were aimed at developing kinetics information for steam gasification of biomass in the presence of catalysts. The combined use of alkali and metal catalysts was reported for gasification of biomass and its components at low temperatures (350{degrees}C to 450{degrees}C). From the fundamental research evolved the concept of a pressurized, catalytic gasification system for converting wet biomass feedstocks to fuel gas. Extensive batch reactor testing and limited continuous reactor system (CRS) testing were undertaken in the development of this system under sponsorship of the US Department of Energy. A wide range of biomass feedstocks were tested, and the importance of the nickel metal catalyst was identified. Specific use of this process for treating food processing wastes was also studied. The concept application was further expanded to encompass cleanup of hazardous wastewater streams, and results were reported for batch reactor tests and continuous reactor tests. Ongoing work at PNL focuses on refining the catalyst and scaling the system to long-term industrial needs. The process is licensed as the Thermochemical Environmental Energy System (TEES{reg_sign}) to Onsite*Ofsite, Inc., of Duarte, California. This report is a follow-on to the 1989--90 interim report [Elliott et al. 1991], which reviewed the results of the studies conducted with a fixed-bed, continuous-feed, tubular reactor. The discussion here provides an overview of experiments on the wide range of potential feedstock materials conducted in a batch reactor; development of new catalyst materials; and tests performed in continuous-flow reactors at three scales. The appendices contain the history and background of the process development, as well as more detailed descriptions and results of the recent studies.

Elliott, D.C.; Neuenschwander, G.G.; Hart, T.R.; Phelps, M.R.; Sealock, L.J. Jr.

1993-07-01T23:59:59.000Z

205

Hazelwood Interim Storage Site annual site environmental report: Calendar year 1986  

SciTech Connect (OSTI)

During 1986, the environmental monitoring program was continued at the Hazelwood Interim Storage Site (HISS), a US Department of Energy (DOE) facility located in the City of Hazelwood, Missouri. Originally known as the Cotter Corporation site on Latty Avenue in Hazelwood, the HISS is presently used for the storage of soils contaminated with residual radioactive material. As part of the decontamination research and development project authorized by Congress under the 1984 Energy and Water Appropriations Act, remedial action and environmental monitoring program are being conducted at the site and at vicinity properties by Bechtel National, Inc., Project Management Contractor for FUSRAP. The monitoring program at the HISS measures radon gas concentrations in air; external gamma radiation levels; and uranium, radium, and thorium concentrations in surface water, groundwater, and sediment. To verify that the site is in compliance with the DOE radiation protection standard (100 mrem/yr) and assess its potential effect on public health, the radiation dose was calculated for the maximally exposed individual. Based on the scenario described in this report, the maximally exposed individual at the HISS would receive an annual external exposure approximately equivalent to 2% of the DOE radiation protection standard of 100 mrem/yr. This exposure is less than the exposure a person would receive during a round-trip flight from New York to Los Angeles. The cumulative dose to the population within an 80-km (50-mi) radius of the HISS that would result from radioactive materials present at the site would be indistinguishable from the dose that the same population would receive from naturally occurring radioactive sources. Results of the 1986 monitoring show that the HISS is in compliance with the DOE radiation protection standard. 11 refs., 6 figs., 10 tabs.

Not Available

1987-06-01T23:59:59.000Z

206

PM Motor Parametric Design Analyses for Hybrid Electric Vehicle Traction Drive Application: Interim Report  

SciTech Connect (OSTI)

The Department of Energy's (DOE) Office of FreedomCAR (Cooperative Automotive Research) and Vehicle Technologies has a strong interest in making rapid progress in permanent magnet (PM) machine development. The program is directing various technology development projects that will advance the technology and lead to request for proposals (RFP) for manufacturer prototypes. This aggressive approach is possible because the technology is clearly within reach and the approach is deemed essential, based on strong market demand, escalating fuel prices, and competitive considerations. In response, this study began parallel development paths that included a literature search/review, development and utilization of multiple parametric models to determine the effects of design parameters, verification of the modeling methodology, development of an interior PM (IPM) machine baseline design, development of alternative machine baseline designs, and cost analyses for several candidate machines. This interim progress report summarizes the results of these activities as of June 2004. This report provides background and summary information for recent machine parametric studies and testing programs that demonstrate both the potential capabilities and technical limitations of brushless PM machines (axial gap and radial gap), the IPM machine, the surface-mount PM machines (interior or exterior rotor), induction machines, and switched reluctance machines. The FreedomCAR program, while acknowledging the progress made by Oak Ridge National Laboratory, Delphi, Delco-Remy International, and others in these programs, has redirected efforts toward a ''short path'' to a marketable and competitive PM motor for hybrid electric vehicle traction applications. The program has developed a set of performance targets for the type of traction machine desired. The short-path approach entails a comprehensive design effort focusing on the IPM machine and meeting the performance targets. The selection of the IPM machine reflects industry's confidence in this market-proven design that exhibits a power density surpassed by no other machine design.

Staunton, R.H.

2004-08-11T23:59:59.000Z

207

Interim report on the Global Design Effort Global International Linear Collider (ILC) R&D  

SciTech Connect (OSTI)

The International Linear Collider: A Technical Progress Report marks the halfway point towards the Global Design Effort fulfilling its mandate to follow up the ILC Reference Design Report with a more optimised Technical Design Report (TDR) by the end of 2012. The TDR will be based on much of the work reported here and will contain all the elements needed to propose the ILC to collaborating governments, including a technical design and implementation plan that are realistic and have been better optimised for performance, cost and risk. We are on track to develop detailed plans for the ILC, such that once results from the Large Hadron Collider (LHC) at CERN establish the main science goals and parameters of the next machine, we will be in good position to make a strong proposal for this new major global project in particle physics. The two overriding issues for the ILC R&D programme are to demonstrate that the technical requirements for the accelerator are achievable with practical technologies, and that the ambitious physics goals can be addressed by realistic ILC detectors. This GDE interim report documents the impressive progress on the accelerator technologies that can make the ILC a reality. It highlights results of the technological demonstrations that are giving the community increased confidence that we will be ready to proceed with an ILC project following the TDR. The companion detector and physics report document likewise demonstrates how detector designs can meet the ambitious and detailed physics goals set out by the ILC Steering Committee. LHC results will likely affect the requirements for the machine design and the detectors, and we are monitoring that very closely, intending to adapt our design as those results become available.

Harrison, M.

2011-04-30T23:59:59.000Z

208

Phase and birefringence aberration correction  

DOE Patents [OSTI]

A Brillouin enhanced four wave mixing phase conjugate mirror corrects phase aberrations of a coherent electromagnetic beam and birefringence induced upon that beam. The stimulated Brillouin scattering (SBS) phase conjugation technique is augmented to include Brillouin enhanced four wave mixing (BEFWM). A seed beam is generated by a main oscillator which arrives at the phase conjugate cell before the signal beams in order to initiate the Brillouin effect. The signal beam which is being amplified through the amplifier chain is split into two perpendicularly polarized beams. One of the two beams is chosen to be the same polarization as some component of the seed beam, the other orthogonal to the first. The polarization of the orthogonal beam is then rotated 90.degree. such that it is parallel to the other signal beam. The three beams are then focused into cell containing a medium capable of Brillouin excitation. The two signal beams are focused such that they cross the seed beam path before their respective beam waists in order to achieve BEFWM or the two signal beams are focused to a point or points contained within the focused cone angle of the seed beam to achieve seeded SBS, and thus negate the effects of all birefringent and material aberrations in the system.

Bowers, Mark (Modesto, CA); Hankla, Allen (Livermore, CA)

1996-01-01T23:59:59.000Z

209

Weather-Corrected Performance Ratio  

SciTech Connect (OSTI)

Photovoltaic (PV) system performance depends on both the quality of the system and the weather. One simple way to communicate the system performance is to use the performance ratio (PR): the ratio of the electricity generated to the electricity that would have been generated if the plant consistently converted sunlight to electricity at the level expected from the DC nameplate rating. The annual system yield for flat-plate PV systems is estimated by the product of the annual insolation in the plane of the array, the nameplate rating of the system, and the PR, which provides an attractive way to estimate expected annual system yield. Unfortunately, the PR is, again, a function of both the PV system efficiency and the weather. If the PR is measured during the winter or during the summer, substantially different values may be obtained, making this metric insufficient to use as the basis for a performance guarantee when precise confidence intervals are required. This technical report defines a way to modify the PR calculation to neutralize biases that may be introduced by variations in the weather, while still reporting a PR that reflects the annual PR at that site given the project design and the project weather file. This resulting weather-corrected PR gives more consistent results throughout the year, enabling its use as a metric for performance guarantees while still retaining the familiarity this metric brings to the industry and the value of its use in predicting actual annual system yield. A testing protocol is also presented to illustrate the use of this new metric with the intent of providing a reference starting point for contractual content.

Dierauf, T.; Growitz, A.; Kurtz, S.; Cruz, J. L. B.; Riley, E.; Hansen, C.

2013-04-01T23:59:59.000Z

210

CORRECTIVE ACTION PLAN FOR CORRECTIVE ACTION UNIT 300: SURFACE RELEASE AREAS NEVADA TEST SITE, NEVADA  

SciTech Connect (OSTI)

The purpose of this Corrective Action Plan (CAP) is to provide the detailed scope of work required to implement the recommended corrective actions as specified in the approved CAU 300 CADD.

NONE

2006-07-01T23:59:59.000Z

211

A Variational Approach to MR Bias Correction  

E-Print Network [OSTI]

A Variational Approach to MR Bias Correction Ayres Fan Stochastic Systems Group July 17, 2003 With W. Wells, J. Fisher, M. Cetin, S. Haker, R. Mulkern, C. Tempany, A. Willsky #12;Outline 1 inhomogeneity that corrupts magnetic resonance (MR) images. Correcting for the bias field makes both human

Willsky, Alan S.

212

A Variational Approach to MR Bias Correction  

E-Print Network [OSTI]

sequences, the MR signal is given by: We can target , T1, and T2 measurements through appropriate selectionA Variational Approach to MR Bias Correction Ayres Fan Stochastic Systems Group Research Qualifying Exam June 10, 2003 #12;Outline 1. Introduction to bias correction 2. Magnetic resonance imaging 3

Willsky, Alan S.

213

A Variational Approach to MR Bias Correction  

E-Print Network [OSTI]

A Variational Approach to MR Bias Correction Ayres Fan, W. Wells, J. Fisher, M. Cetin, S. Haker, A that corrupts magnetic resonance (MR) images. Correcting for the bias field makes both human analysis (e that encourages smoothness in b and piecewise smoothness in f: We generally choose p 1 to help preserve edges D

Willsky, Alan S.

214

The Politically Correct Nuclear Energy Plant  

E-Print Network [OSTI]

The Politically Correct Nuclear Energy Plant Andrew C. Kadak Massachusetts Institute of Technology - Small is Beautiful · Nuclear Energy - But Getting Better #12;Politically Correct ! · Natural Safety is a bad idea. · There is no new nuclear energy plant that is competitive at this time. · De-regulation did

215

Fuel cell flooding detection and correction  

DOE Patents [OSTI]

Method and apparatus for monitoring an H.sub.2 -O.sub.2 PEM fuel cells to detect and correct flooding. The pressure drop across a given H.sub.2 or O.sub.2 flow field is monitored and compared to predetermined thresholds of unacceptability. If the pressure drop exists a threshold of unacceptability corrective measures are automatically initiated.

DiPierno Bosco, Andrew (Rochester, NY); Fronk, Matthew Howard (Honeoye Falls, NY)

2000-08-15T23:59:59.000Z

216

Electromagnetic Corrections in Staggered Chiral Perturbation Theory  

E-Print Network [OSTI]

Electromagnetic Corrections in Staggered Chiral Perturbation Theory C. Bernard and E.D. Freeland perturbation theory including electromagnetism, and discuss the extent to which quenched-photon simulations can-lat]17Nov2010 #12;Electromagnetic Corrections in Staggered Chiral Perturbation Theory E.D. Freeland 1

Bernard, Claude

217

Quantum Error Correction Beyond Completely Positive Maps  

E-Print Network [OSTI]

By introducing an operator sum representation for arbitrary linear maps, we develop a generalized theory of quantum error correction (QEC) that applies to any linear map, in particular maps that are not completely positive (CP). This theory of "linear quantum error correction" is applicable in cases where the standard and restrictive assumption of a factorized initial system-bath state does not apply.

A. Shabani; D. A. Lidar

2009-10-21T23:59:59.000Z

218

Detector signal correction method and system  

DOE Patents [OSTI]

Corrective factors are applied so as to remove anomalous features from the signal generated by a photoconductive detector, and to thereby render the output signal highly linear with respect to the energy of incident, time-varying radiation. The corrective factors may be applied through the use of either digital electronic data processing means or analog circuitry, or through a combination of those effects.

Carangelo, Robert M. (Glastonbury, CT); Duran, Andrew J. (Oviedo, FL); Kudman, Irwin (Boca Raton, FL)

1995-07-11T23:59:59.000Z

219

RH-TRU Waste Shipments from Battelle Columbus Laboratories to the Hanford Nuclear Facility for Interim Storage  

SciTech Connect (OSTI)

Battelle Columbus Laboratories (BCL), located in Columbus, Ohio, must complete decontamination and decommissioning (D&D) activities for nuclear research buildings and grounds by 2006, as directed by Congress. Most of the resulting waste (approximately 27 cubic meters [m3]) is remote-handled (RH) transuranic (TRU) waste destined for disposal at the Waste Isolation Pilot Plant (WIPP). The BCL, under a contract to the U.S. Department of Energy (DOE) Ohio Field Office, has initiated a plan to ship the TRU waste to the DOE Hanford Nuclear Facility (Hanford) for interim storage pending the authorization of WIPP for the permanent disposal of RH-TRU waste. The first of the BCL RH-TRU waste shipments was successfully completed on December 18, 2002. This BCL shipment of one fully loaded 10-160B Cask was the first shipment of RH-TRU waste in several years. Its successful completion required a complex effort entailing coordination between different contractors and federal agencies to establish necessary supporting agreements. This paper discusses the agreements and funding mechanisms used in support of the BCL shipments of TRU waste to Hanford for interim storage. In addition, this paper presents a summary of the efforts completed to demonstrate the effectiveness of the 10-160B Cask system. Lessons learned during this process are discussed and may be applicable to other TRU waste site shipment plans.

Eide, J.; Baillieul, T. A.; Biedscheid, J.; Forrester, T,; McMillan, B.; Shrader, T.; Richterich, L.

2003-02-26T23:59:59.000Z

220

Quantum Error Correction for Quantum Memories  

E-Print Network [OSTI]

Active quantum error correction using qubit stabilizer codes has emerged as a promising, but experimentally challenging, engineering program for building a universal quantum computer. In this review we consider the formalism of qubit stabilizer and subsystem stabilizer codes and their possible use in protecting quantum information in a quantum memory. We review the theory of fault-tolerance and quantum error-correction, discuss examples of various codes and code constructions, the general quantum error correction conditions, the noise threshold, the special role played by Clifford gates and the route towards fault-tolerant universal quantum computation. The second part of the review is focused on providing an overview of quantum error correction using two-dimensional (topological) codes, in particular the surface code architecture. We discuss the complexity of decoding and the notion of passive or self-correcting quantum memories. The review does not focus on a particular technology but discusses topics that will be relevant for various quantum technologies.

Barbara M. Terhal

2015-01-20T23:59:59.000Z

Note: This page contains sample records for the topic "icm interim corrective" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


221

Corrections to "Proving Safety Properties of the Steam Boiler Controller" Correction Sheet  

E-Print Network [OSTI]

Corrections to "Proving Safety Properties of the Steam Boiler Controller" 1 Correction Sheet After our paper "Proving Safety Properties of the Steam Boiler Controller" went already to print, Myla address http://theory.lcs.mit.edu/tds/boiler.html. Following are the corrections to these errors and some

Lynch, Nancy

222

Interim Report: Air-Cooled Condensers for Next Generation Geothermal Power Plants Improved Binary Cycle Performance  

SciTech Connect (OSTI)

As geothermal resources that are more expensive to develop are utilized for power generation, there will be increased incentive to use more efficient power plants. This is expected to be the case with Enhanced Geothermal System (EGS) resources. These resources will likely require wells drilled to depths greater than encountered with hydrothermal resources, and will have the added costs for stimulation to create the subsurface reservoir. It is postulated that plants generating power from these resources will likely utilize the binary cycle technology where heat is rejected sensibly to the ambient. The consumptive use of a portion of the produced geothermal fluid for evaporative heat rejection in the conventional flash-steam conversion cycle is likely to preclude its use with EGS resources. This will be especially true in those areas where there is a high demand for finite supplies of water. Though they have no consumptive use of water, using air-cooling systems for heat rejection has disadvantages. These systems have higher capital costs, reduced power output (heat is rejected at the higher dry-bulb temperature), increased parasitics (fan power), and greater variability in power generation on both a diurnal and annual basis (larger variation in the dry-bulb temperature). This is an interim report for the task ‘Air-Cooled Condensers in Next- Generation Conversion Systems’. The work performed was specifically aimed at a plant that uses commercially available binary cycle technologies with an EGS resource. Concepts were evaluated that have the potential to increase performance, lower cost, or mitigate the adverse effects of off-design operation. The impact on both cost and performance were determined for the concepts considered, and the scenarios identified where a particular concept is best suited. Most, but not all, of the concepts evaluated are associated with the rejection of heat. This report specifically addresses three of the concepts evaluated: the use of recuperation, the use of turbine reheat, and the non-consumptive use of EGS make-up water to supplement heat rejection

Daniel S. Wendt; Greg L. Mines

2010-09-01T23:59:59.000Z

223

INDEPENDENT TECHNICAL REVIEW OF THE C-400 INTERIM REMEDIAL PROJECT PHASE I RESULTS, PADUCAH, KENTUCKY  

SciTech Connect (OSTI)

The groundwater and soil in the vicinity of the C-400 Building at the Paducah Gaseous Diffusion Plant (PGDP), is contaminated with substantial quantities of industrial solvents, primarily trichoroethene (TCE). This solvent 'source' is recognized as a significant challenge and an important remediation target in the overall environmental cleanup strategy for PGDP. Thus, the cleanup of the C-400 TCE Source is a principal focus for the Department of Energy (DOE) and its contractors, and for PGDP regulators and stakeholders. Using a formal investigation, feasibility study and decision process, Electrical Resistance Heating (ERH) was selected for the treatment of the soil and groundwater in the vicinity of C-400. ERH was selected as an interim action to remove 'a significant portion of the contaminant mass of TCE at the C-400 Cleaning Building area through treatment' with the longer term goal of reducing 'the period the TCE concentration in groundwater remains above its Maximum Contaminant Level (MCL).' ERH is a thermal treatment that enhances the removal of TCE and related solvents from soil and groundwater. The heterogeneous conditions at PGDP, particularly the high permeability regional gravel aquifer (RGA), are challenging to ERH. Thus, a phased approach is being followed to implement this relatively expensive and complex remediation technology. Conceptually, the phased approach encourages safety and efficiency by providing a 'lessons learned' process and allowing appropriate adjustments to be identified and implemented prior to follow-on phase(s) of treatment. More specifically, early deployment targeted portions of the challenging RGA treatment zone with relatively little contamination reducing the risk of adverse collateral impacts from underperformance in terms of heating and capture. Because of the importance and scope of the C-400 TCE source remediation activities, DOE chartered an Independent Technical Review (ITR) in 2007 to assess the C-400 ERH plans prior to deployment and a second ITR to evaluate Phase I performance in September 2010. In this report, these ITR efforts are referenced as the '2007 ITR' and the 'current ITR', respectively. The 2007 ITR document (Looney et al., 2007) provided a detailed technical evaluation that remains relevant and this report builds on that analysis. The primary objective of the current ITR is to provide an expedited assessment of the available Phase I data to assist the PGDP team as they develop the lessons learned from Phase I and prepare plans for Phase II.

Looney, B.; Rossabi, J.; Stewart,L.; Richards, W.

2010-10-29T23:59:59.000Z

224

REVIEW OF FAST FLUX TEST FACILITY (FFTF) FUEL EXPERIMENTS FOR STORAGE IN INTERIM STORAGE CASKS (ISC)  

SciTech Connect (OSTI)

Appendix H, Section H.3.3.10.11 of the Final Safety Analysis Report (FSAR), provides the limits to be observed for fueled components authorized for storage in the Fast Flux Test Facility (FFTF) spent fuel storage system. Currently, the authorization basis allows standard driver fuel assemblies (DFA), as described in the FSAR Chapter 17, Section 17.5.3.1, to be stored provided decay power per assembly is {le} 250 watts, post-irradiation time is four years minimum, average assembly burn-up is 150,000 MWD/MTHM maximum and the pre-irradiation enrichment is 29.3% maximum (per H.3.3.10.11). In addition, driver evaluation (DE), core characterizer assemblies (CCA), and run-to-cladding-breach (RTCB) assemblies are included based on their similarities to a standard DFA. Ident-69 pin containers with fuel pins from these DFAs can also be stored. Section H.3.3.10.11 states that fuel types outside the specification criteria above will be addressed on a case-by-case basis. There are many different types of fuel and blanket experiments that were irradiated in the FFTF which now require offload to the spent fuel storage system. Two reviews were completed for a portion of these special type fuel components to determine if placement into the Core Component Container (CCC)/Interim Storage Cask (ISC) would require any special considerations or changes to the authorization basis. Project mission priorities coupled with availability of resources and analysts prevented these evaluations from being completed as a single effort. Areas of review have included radiological accident release consequences, radiological shielding adequacy, criticality safety, thermal limits, confinement, and stress. The results of these reviews are available in WHC-SD-FF-RPT-005, Rev. 0 and 1, ''Review of FFTF Fuel Experiments for Storage at ISA'', (Reference I), which subsequently allowed a large portion of these components to be included in the authorization basis (Table H.3.3-21). The report also identified additional components and actions in Section 3.0 and Table 3 that require further evaluation. The purpose of this report is to evaluate another portion of the remaining inventory (i.e., delayed neutron signal fuel, blanket assemblies, highly enriched assemblies, newly loaded Ident-69 pin containers, and returned fuel) to ensure it can be safely off loaded to the FFTF spent fuel storage system.

CHASTAIN, S.A.

2005-10-24T23:59:59.000Z

225

Caustic-Side Solvent-Extraction Modeling for Hanford Interim Pretreatment System  

SciTech Connect (OSTI)

The purpose of this work is to examine the applicability of the Caustic-Side Solvent Extraction (CSSX) process for the removal of cesium from Hanford tank-waste supernatant solutions in support of the Hanford Interim Pretreatment System (IPS). The Hanford waste types are more challenging than those at the Savannah River Site (SRS) in that they contain significantly higher levels of potassium, the chief competing ion in the extraction of cesium. It was confirmed by use of the CSSX model that the higher levels of potassium depress the cesium distribution ratio (DCs), as validated by measurement of DCs values for four of eight specified Hanford waste-simulant compositions. The model predictions were good to an apparent standard error of ±11%. It is concluded from batch distribution experiments, physical-property measurements, equilibrium modeling, flowsheet calculations, and contactor sizing that the CSSX process as currently employed for cesium removal from alkaline salt waste at the SRS is capable of treating similar Hanford tank feeds. For the most challenging waste composition, 41 stages would be required to provide a cesium decontamination factor (DF) of 5000 and a concentration factor (CF) of 5. Commercial contacting equipment with rotor diameters of 10 in. for extraction and 5 in. for stripping should have the capacity to meet throughput requirements, but testing will be required to confirm that the needed efficiency and hydraulic performance are actually obtainable. Markedly improved flowsheet performance was calculated for a new solvent formulation employing the more soluble cesium extractant BEHBCalixC6 used with alternative scrub and strip solutions, respectively 0.1 M NaOH and 10 mM boric acid. The improved system can meet minimum requirements (DF = 5000 and CF = 5) with 17 stages or more ambitious goals (DF = 40,000 and CF = 15) with 19 stages. Potential benefits of further research and development are identified that would lead to reduced costs, greater adaptability of the process to DOE alkaline salt wastes, and greater readiness for implementation. Such benefits accrue from optimal sizing of centrifugal contactors for application of the CSSX process for the IPS; more accurate modeling of cesium extraction with greater flexibility and applicability to a variety of feeds and flowsheet conditions; and further improving and optimizing the alternative CSSX solvent and scrub/strip system.

Moyer, B.A.; Birdwell, J.F.; Delmau, L. H.; McFarlane, J.

2008-06-01T23:59:59.000Z

226

Interim Control Strategy for the Test Area North/Technical Support Facility Sewage Treatment Facility Disposal Pond - Two-year Update  

SciTech Connect (OSTI)

The Idaho Cleanup Project has prepared this interim control strategy for the U.S. Department of Energy Idaho Operations Office pursuant to DOE Order 5400.5, Chapter 11.3e (1) to support continued discharges to the Test Area North/Technical Support Facility Sewage Treatment Facility Disposal Pond. In compliance with DOE Order 5400.5, a 2-year review of the Interim Control Strategy document has been completed. This submittal documents the required review of the April 2005 Interim Control Strategy. The Idaho Cleanup Project's recommendation is unchanged from the original recommendation. The Interim Control Strategy evaluates three alternatives: (1) re-route the discharge outlet to an uncontaminated area of the TSF-07; (2) construct a new discharge pond; or (3) no action based on justification for continued use. Evaluation of Alternatives 1 and 2 are based on the estimated cost and implementation timeframe weighed against either alternative's minimal increase in protection of workers, the public, and the environment. Evaluation of Alternative 3, continued use of the TSF-07 Disposal Pond under current effluent controls, is based on an analysis of four points: - Record of Decision controls will protect workers and the public - Risk of increased contamination is low - Discharge water will be eliminated in the foreseeable future - Risk of contamination spread is acceptable. The Idaho Cleanup Project recommends Alternative 3, no action other than continued implementation of existing controls and continued deactivation, decontamination, and dismantlement efforts at the Test Area North/Technical Support Facility.

L. V. Street

2007-04-01T23:59:59.000Z

227

Nonperturbative QCD corrections to electroweak observables  

SciTech Connect (OSTI)

Nonperturbative QCD corrections are important to many low-energy electroweak observables, for example the muon magnetic moment. However, hadronic corrections also play a significant role at much higher energies due to their impact on the running of standard model parameters, such as the electromagnetic coupling. Currently, these hadronic contributions are accounted for by a combination of experimental measurements and phenomenological modeling but ideally should be calculated from first principles. Recent developments indicate that many of the most important hadronic corrections may be feasibly calculated using lattice QCD methods. To illustrate this, we will examine the lattice computation of the leading-order QCD corrections to the muon magnetic moment, paying particular attention to a recently developed method but also reviewing the results from other calculations. We will then continue with several examples that demonstrate the potential impact of the new approach: the leading-order corrections to the electron and tau magnetic moments, the running of the electromagnetic coupling, and a class of the next-to-leading-order corrections for the muon magnetic moment. Along the way, we will mention applications to the Adler function, the determination of the strong coupling constant and QCD corrections to muonic-hydrogen.

Dru B Renner, Xu Feng, Karl Jansen, Marcus Petschlies

2011-12-01T23:59:59.000Z

228

Neutrinoless double beta decay and QCD corrections  

E-Print Network [OSTI]

We consider one loop QCD corrections and renormalization group running of the neutrinoless double beta decay amplitude focusing on the short-range part of the amplitude (without the light neutrino exchange) and find that these corrections can be sizeable. Depending on the operator under consideration, there can be moderate to large cancellations or significant enhancements. We discuss several specific examples in this context. Such large corrections will lead to significant shifts in the half-life estimates which currently are known to be plagued with the uncertainties due to nuclear physics inputs to the physical matrix elements.

Namit Mahajan

2014-01-30T23:59:59.000Z

229

Perimeter security for Minnesota correctional facilities  

SciTech Connect (OSTI)

For the past few years, the Minnesota Department of Corrections, assisted by Sandia National Laboratories, has developed a set of standards for perimeter security at medium, close, and maximum custody correctional facilities in the state. During this process, the threat to perimeter security was examined and concepts about correctional perimeter security were developed. This presentation and paper will review the outcomes of this effort, some of the lessons learned, and the concepts developed during this process and in the course of working with architects, engineers and construction firms as the state upgraded perimeter security at some facilities and planned new construction at other facilities.

Crist, D. [Minnesota Department of Corrections, St. Paul, MN (United States); Spencer, D.D. [Sandia National Labs., Albuquerque, NM (United States)

1996-12-31T23:59:59.000Z

230

Second Order Geodesic Corrections to Cosmic Shear  

E-Print Network [OSTI]

We consider the impact of second order corrections to the geodesic equation governing gravitational lensing. We start from the full second order metric, including scalar, vector and tensor perturbations, and retain all relevant contributions to the cosmic shear corrections that are second order in the gravitational potential. The relevant terms are: the nonlinear evolution of the scalar gravitational potential, the Born correction, and lens-lens coupling. No other second order terms contribute appreciably to the lensing signal. Since ray-tracing algorithims currently include these three effects, this derivation serves as rigorous justification for the numerical predictions.

S. Dodelson; E. W. Kolb; S. Matarrese; A. Riotto; P. Zhang

2005-03-07T23:59:59.000Z

231

Quadratic electroweak corrections for polarized Moller scattering  

SciTech Connect (OSTI)

The paper discusses the two-loop (NNLO) electroweak radiative corrections to the parity violating electron-electron scattering asymmetry induced by squaring one-loop diagrams. The calculations are relevant for the ultra-precise 11 GeV MOLLER experiment planned at Jefferson Laboratory and experiments at high-energy future electron colliders. The imaginary parts of the amplitudes are taken into consideration consistently in both the infrared-finite and divergent terms. The size of the obtained partial correction is significant, which indicates a need for a complete study of the two-loop electroweak radiative corrections in order to meet the precision goals of future experiments.

A. Aleksejevs, S. Barkanova, Y. Kolomensky, E. Kuraev, V. Zykunov

2012-01-01T23:59:59.000Z

232

Assessing the Security Vulnerabilities of Correctional Facilities  

SciTech Connect (OSTI)

The National Institute of Justice has tasked their Satellite Facility at Sandia National Laboratories and their Southeast Regional Technology Center in Charleston, South Carolina to devise new procedures and tools for helping correctional facilities to assess their security vulnerabilities. Thus, a team is visiting selected correctional facilities and performing vulnerability assessments. A vulnerability assessment helps to identi~ the easiest paths for inmate escape, for introduction of contraband such as drugs or weapons, for unexpected intrusion fi-om outside of the facility, and for the perpetration of violent acts on other inmates and correctional employees, In addition, the vulnerability assessment helps to quantify the security risks for the facility. From these initial assessments will come better procedures for performing vulnerability assessments in general at other correctional facilities, as well as the development of tools to assist with the performance of such vulnerability assessments.

Morrison, G.S.; Spencer, D.S.

1998-10-27T23:59:59.000Z

233

Proving Correctness of Modular Functional Programs   

E-Print Network [OSTI]

One reason for studying and programming in functional programming languages is that they are easy to reason about, yet there is surprisingly little work on proving the correctness of large functional programs. In this dissertation I show how...

Owens, Christopher

234

Correcting Iron Deficiencies in Grain Sorghum  

E-Print Network [OSTI]

Until grain sorghum develops an extensive root system, young plants may be unable to obtain enough ferrous iron to maintain normal growth. This publication offers strategies for avoiding, identifying and correcting iron deficiencies....

Livingston, Stephen; Coffman, Cloyce G.; Unruh, L. G.

1996-02-20T23:59:59.000Z

235

Quantum error-correcting codes and devices  

DOE Patents [OSTI]

A method of forming quantum error-correcting codes by first forming a stabilizer for a Hilbert space. A quantum information processing device can be formed to implement such quantum codes.

Gottesman, Daniel (Los Alamos, NM)

2000-10-03T23:59:59.000Z

236

Detector signal correction method and system  

DOE Patents [OSTI]

Corrective factors are applied so as to remove anomalous features from the signal generated by a photoconductive detector, and to thereby render the output signal highly linear with respect to the energy of incident, time-varying radiation. The corrective factors may be applied through the use of either digital electronic data processing means or analog circuitry, or through a combination of those effects. 5 figs.

Carangelo, R.M.; Duran, A.J.; Kudman, I.

1995-07-11T23:59:59.000Z

237

NINTH INTERIM STATUS REPORT: MODEL 9975 PCV O-RING FIXTURE LONG-TERM LEAK PERFORMANCE  

SciTech Connect (OSTI)

A series of experiments to monitor the aging performance of Viton® GLT O-rings used in the Model 9975 package has been ongoing since 2004 at the Savannah River National Laboratory. One approach has been to periodically evaluate the leak performance of O-rings being aged in mock-up 9975 Primary Containment Vessels (PCVs) at elevated temperatures. Other methods such as compression-stress relaxation (CSR) tests and field surveillance are also on-going to evaluate O-ring behavior. Seventy tests using PCV mock-ups were assembled and heated to temperatures ranging from 200 to 450 ºF. They were leak-tested initially and have been tested periodically to determine if they continue to meet the leak-tightness criterion defined in ANSI standard N14.5-97. Due to material substitution, fourteen additional tests were initiated in 2008 with GLT-S O-rings heated to temperatures ranging from 200 to 400 ºF. High temperature aging continues for 23 GLT O-ring fixtures at 200 – 270 ºF. Room temperature leak test failures have been experienced in all of the GLT O-ring fixtures aging at 350 ºF and higher temperatures, and in 8 fixtures aging at 300 ºF. The earliest 300 °F GLT O-ring fixture failure was observed at 34 months. The remaining GLT O-ring fixtures aging at 300 ºF have been retired from testing following more than 5 years at temperature without failure. No failures have yet been observed in GLT O-ring fixtures aging at 200 ºF for 72 - 96 months, which bounds O-ring temperatures anticipated during storage in K-Area Complex (KAC). Based on expectations that the 200 ºF fixtures will remain leak-tight for a significant period yet to come, 2 additional fixtures began aging in 2011 at 270 ºF, with hopes that they may reach a failure condition before the 200 ºF fixtures, thus providing additional time to failure data. High temperature aging continues for 6 GLT-S O-ring fixtures at 200 – 300 ºF. Room temperature leak test failures have been experienced in all 8 of the GLT-S O-ring fixtures aging at 350 and 400 ºF. No failures have yet been observed in GLT-S O-ring fixtures aging at 200 - 300 ºF for 54 - 57 months. No additional O-ring failures have been observed since the last interim report was issued. Aging and periodic leak testing will continue for the remaining PCV fixtures. Additional irradiation of several fixtures is recommended to maintain a balance between thermal and radiation exposures similar to that experienced in storage, and to show the degree of consistency of radiation response between GLT and GLT-S O-rings.

Daugherty, W.

2014-08-06T23:59:59.000Z

238

Technical Competencies for the Safe Interim Storage and Management of 233U at U.S. Department of Energy Facilities  

SciTech Connect (OSTI)

Uranium-233 (with concomitant {sup 232}U) is a man-made fissile isotope of uranium with unique nuclear characteristics which require high-integrity alpha containment biological shielding, and remote handling. The special handling considerations and the fact that much of the {sup 233}U processing and large-scale handling was performed over a decade ago underscore the importance of identifying the people within the DOE complex who are currently working with or have worked with {sup 233}U. The availability of these key personnel is important in ensuring safe interim storage, management and ultimate disposition of {sup 233}U at DOE facilities. Significant programs are ongoing at several DOE sites with actinides. The properties of these actinide materials require many of the same types of facilities and handling expertise as does {sup 233}U.

Campbell, D.O.; Krichinsky, A.M.; Laughlin, S.S.; Van Essen, D.C.; Yong, L.K.

1999-02-17T23:59:59.000Z

239

Diesel Emission Control -- Sulfur Effects (DECSE) Program; Phase I Interim Data Report No. 2: NO{sub x} Adsorber Catalysts  

SciTech Connect (OSTI)

The Diesel Emission Control-Sulfur Effects (DECSE) is a joint government/industry program to determine the impact of diesel fuel sulfur levels on emission control systems whose use could lower emissions of nitrogen oxides (NOx) and particulate matter (PM) from on-highway trucks in the 2002--2004 model years. Phase 1 of the program was developed with the following objectives in mind: (1) evaluate the effects of varying the level of sulfur content in the fuel on the emission reduction performance of four emission control technologies; and (2) measure and compare the effects of up to 250 hours of aging on selected devices for multiple levels of fuel sulfur content. This interim report discusses the results of the DECSE test program that demonstrates the potential of NOx adsorber catalyst technology across the range of diesel engine operation with a fuel economy penalty less than 4%.

DOE; ORNL; NREL; EMA; MECA

1999-10-15T23:59:59.000Z

240

Interim site characterization report and ground-water monitoring program for the Hanford site solid waste landfill  

SciTech Connect (OSTI)

Federal and state regulations governing the operation of landfills require utilization of ground-water monitoring systems to determine whether or not landfill operations impact ground water at the point of compliance (ground water beneath the perimeter of the facility). A detection-level ground-water monitoring system was designed, installed, and initiated at the Hanford Site Solid Waste Landfill (SWL). Chlorinated hydrocarbons were detected at the beginning of the ground-water monitoring program and continue to be detected more than 1 year later. The most probable source of the chlorinated hydrocarbons is washwater discharged to the SWL between 1985 and 1987. This is an interim report and includes data from the characterization work that was performed during well installation in 1987, such as field observations, sediment studies, and geophysical logging results, and data from analyses of ground-water samples collected in 1987 and 1988, such as field parameter measurements and chemical analyses. 38 refs., 27 figs., 8 tabs.

Fruland, R.M.; Hagan, R.A.; Cline, C.S.; Bates, D.J.; Evans, J.C.; Aaberg, R.L.

1989-07-01T23:59:59.000Z

Note: This page contains sample records for the topic "icm interim corrective" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


241

Sample Results From The Interim Salt Disposition Program Macrobatch 7 Tank 21H Qualification MST Solids Sample  

SciTech Connect (OSTI)

Savannah River National Laboratory (SRNL) performed experiments on qualification material for use in the Interim Salt Disposition Program (ISDP) Batch 7 processing. The Marcrobatch 7 material was received with visible fine particulate solids, atypical for these samples. The as received material was allowed to settle for a period greater than 24 hours. The supernatant was then decanted and utilized as our clarified feed material. As part of this qualification work, SRNL performed an Actinide Removal Process (ARP) test using the clarified feed material. From this test, the residual monosodium titanate (MST) was analyzed for radionuclide uptake after filtration from H-Tank Farm (HTF) feed salt solution. The results of these analyses are reported and are within historical precedent.

Washington, A. L. II; Peters, T. B.

2013-09-19T23:59:59.000Z

242

Tonopah Test Range Environmental Restoration Corrective Action Sites  

SciTech Connect (OSTI)

This report describes the status (closed, closed in place, or closure in progress) of the Corrective Action Sites and Corrective Action Units at the Tonopah Test Range

NSTec Environmental Restoration

2010-08-04T23:59:59.000Z

243

Self-corrected Sensors Based On Atomic Absorption Spectroscopy...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

corrected Sensors Based On Atomic Absorption Spectroscopy For Atom Flux Measurements In Molecular Beam Epitaxy. Self-corrected Sensors Based On Atomic Absorption Spectroscopy For...

244

attenuation correction techniques: Topics by E-print Network  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Frank Silvio 3 Fuzzy clustering-based segmented attenuation correction in whole-body PET CERN Preprints Summary: Segmented-based attenuation correction is now a widely accepted...

245

attenuation correction technique: Topics by E-print Network  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Frank Silvio 3 Fuzzy clustering-based segmented attenuation correction in whole-body PET CERN Preprints Summary: Segmented-based attenuation correction is now a widely accepted...

246

Root Cause Analysis (RCA) & Corrective Action Plan (CAP) | Department...  

Energy Savers [EERE]

Root Cause Analysis (RCA) & Corrective Action Plan (CAP) Root Cause Analysis (RCA) & Corrective Action Plan (CAP) Improving the Department of Energy's project and contract...

247

Harmonic distortion correction in pipelined analog to digital converters  

E-Print Network [OSTI]

Background Correction of Harmonic Distortion in PipelinedBackground Correction of Harmonic Distortion in PipelinedADC with 69dB SNDR Enabled by Digital Harmonic Distortion

Panigada, Andrea

2009-01-01T23:59:59.000Z

248

Quantum corrections to eta/s  

E-Print Network [OSTI]

We consider corrections to the ratio of the shear viscosity to the entropy density in strongly coupled nonabelian plasmas using the AdS/CFT correspondence. In particular, higher derivative terms with the five-form RR flux, which have been ignored in all previous calculations, are included. This provides the first reliable calculation of the leading order correction in the inverse 't Hooft coupling to the celebrated result eta/s=1/4pi. The leading correction in inverse powers of the number of colours is computed. Our results hold very generally for quiver gauge theories with an internal manifold L_pqr in the holographic dual. Our analysis implies that the thermal properties of these theories will not be affected by the five-form flux terms at this order.

Robert C. Myers; Miguel F. Paulos; Aninda Sinha

2008-06-18T23:59:59.000Z

249

Relativistic corrections to radiative transitions in quarkonium  

SciTech Connect (OSTI)

In this work estimates are made of (v/c/sup 2/) corrections to E1 radiative decay rates in the psi and T systems. Siegert's theorem is used to reduce the problem of finding these corrections to one of finding (v/c)/sup 2/ corrections to quarkonium bound state wavefunctions. A Breit-Fermi equation is used to describe the c anti c and b anti b systems. Numerical calculations are carried out in two potential models. Each of these potentials consists of a linear confining piece and a Coulomb-like piece which incorporates a short distance cutoff. The short distance cutoff simplifies the calculation of bound state wavefunctions. In these models the best fit to the charmonium fine structure occurs when the confining potential is assumed to be a Lorentz scalar and the Coulomb-like potential is assumed to be a Lorentz vector. Quarkonium bound state wavefunctions which include spin dependent and spin independent (v/c)/sup 2/ corrections are found by solving the Breit-Fermi equation. These wavefunctions are used to calculate quarkonium E1 decay rates. It is found that the node in the 2S radial wavefunction makes the psi' ..-->.. ..gamma.. chi/sub J/ decays sensitive to relativistic effects, especially the fine structure. In particular, the psi' ..-->.. ..gamma.. chi/sub 0/ decay rate is reduced by more than a factor of two compared to the nonrelativistic estimate. The chi/sub J/ ..-->.. ..gamma.. psi decay widths are not sensitive to relativistic effects since neither the initial nor the final c anti c radial wavefunctions have nodes. Relativistic corrections to radiative E1 decay rates in the b anti b system are generally smaller than in the c anti c system. However, estimates of some decay rates, for example those for 2 /sup 3/P/sub J/ ..-->.. ..gamma..T, are very sensitive to wavefunction corrections. These estimates differ substantially from nonrelativistic predictions.

McClary, R.L.

1982-01-01T23:59:59.000Z

250

Hardware-efficient autonomous quantum error correction  

E-Print Network [OSTI]

We propose a new method to autonomously correct for errors of a logical qubit induced by energy relaxation. This scheme encodes the logical qubit as a multi-component superposition of coherent states in a harmonic oscillator, more specifically a cavity mode. The sequences of encoding, decoding and correction operations employ the non-linearity provided by a single physical qubit coupled to the cavity. We layout in detail how to implement these operations in a practical system. This proposal directly addresses the task of building a hardware-efficient and technically realizable quantum memory.

Zaki Leghtas; Gerhard Kirchmair; Brian Vlastakis; Robert Schoelkopf; Michel Devoret; Mazyar Mirrahimi

2013-01-16T23:59:59.000Z

251

FTCP Corrective Action Plan- Revision 1  

Broader source: Energy.gov [DOE]

January 2007 FTCP Corrective Action Plan, Revision 1, which is Deliverable B for Commitment 13 in the Department of Energy (DOE) Implementation Plan to Improve Oversight of Nuclear Operations, issued in response to Defense Nuclear Facilities Safety Board Recommendation 2004- 1, Oversight of Complex, High-Hazard Nuclear Operations

252

NSA AERI Hatch Correction Data Set  

DOE Data Explorer [Office of Scientific and Technical Information (OSTI)]

From 2000-2008, the NSA AERI hatch was determined to be indicated as open too frequently. Analysis suggests that the hatch was actually opening and closing properly but that its status was not being correctly reported by the hatch controller to the datastream. An algorithm was written to determine the hatch status from the observed

Turner, David

253

Image Fusion for MR Bias Correction  

E-Print Network [OSTI]

. For example, for fast-spin echo (FSE) pulse sequences, the MR signal is given by this equation: · Target T1Image Fusion for MR Bias Correction Ayres Fan Stochastic Systems Group Joint work with W. Wells, J strength · Spatially varying field strength encodes spatial location in the frequency domain #12;MR Imaging

Willsky, Alan S.

254

NSA AERI Hatch Correction Data Set  

SciTech Connect (OSTI)

From 2000-2008, the NSA AERI hatch was determined to be indicated as open too frequently. Analysis suggests that the hatch was actually opening and closing properly but that its status was not being correctly reported by the hatch controller to the datastream. An algorithm was written to determine the hatch status from the observed

Turner, David

2012-03-23T23:59:59.000Z

255

Ostrogradsky's Hamilton formalism and quantum corrections  

E-Print Network [OSTI]

By means of a simple scalar field theory it is demonstrated that the Lagrange formalism and Ostrogradsky's Hamilton formalism in the presence of higher derivatives, in general, do not lead to the same results. While the two approaches are equivalent at the classical level, differences appear due to the quantum corrections.

J. Gegelia; S. Scherer

2010-03-23T23:59:59.000Z

256

Signatures of Correct Computation Charalampos Papamanthou  

E-Print Network [OSTI]

also show that signatures of correct computation imply Publicly Verifiable Computation (PVC), a model client can verify the signature and be convinced of some computation result, whereas in the PVC model to construct PVC schemes with adaptive security, efficient updates and without the random oracle model. 1

257

Electromagnetic corrections to light hadron masses  

E-Print Network [OSTI]

At the precision reached in current lattice QCD calculations, electromagnetic effects are becoming numerically relevant. We will present preliminary results for electromagnetic corrections to light hadron masses, based on simulations in which a $\\mathrm{U}(1)$ degree of freedom is superimposed on $N_f=2+1$ QCD configurations from the BMW collaboration.

A. Portelli; S. Dürr; Z. Fodor; J. Frison; C. Hoelbling; S. D. Katz; S. Krieg; T. Kurth; L. Lellouch; T. Lippert; K. K. Szabó; A. Ramos

2011-01-12T23:59:59.000Z

258

Explanation of Significant Differences for the Record of Decision for Interim Actions in Zone 1, East Tennessee Technology Park, Oak Ridge, Tennessee  

SciTech Connect (OSTI)

Zone 1 is a 1400-acre area outside the fence of the main plant at The East Tennessee Technology Park (ETTP) in Oak Ridge, Tennessee. The Record of Decision for Interim Actions in Zone, ETTP (Zone 1 Interim ROD) (DOE 2002) identifies the remedial actions for contaminated soil, buried waste, and subsurface infrastructure necessary to protect human health and to limit further contamination of groundwater. Since the Zone 1 Interim Record of Decision (ROD) was signed, new information has been obtained that requires the remedy to be modified as follows: (1) Change the end use in Contractor's Spoil Area (CSA) from unrestricted industrial to recreational; (2) Remove Exposure Units (EU5) ZI-50, 51, and 52 from the scope of the Zone I Interim ROD; (3) Change the end use of the duct bank corridor from unrestricted industrial to restricted industrial; and (4) Remove restriction for the disturbance of soils below 10 feet in Exposure Unit (EU) Z1-04. In accordance with 40 Code of Federal Regulations (CFR) 300.435, these scope modifications are a 'significant' change to the Zone 1 Interim ROD. In accordance with CERCLA Sect. 117 (c) and 40 CFR 300.435 (c)(2)(i), such a significant change is documented with an Explanation of Significant Differences (ESD). The purpose of this ESD is to make the changes listed above. This ESD is part of the Administrative Record file, and it, and other information supporting the selected remedy, can be found at the DOE Information Center, 475 Oak Ridge Turnpike, Oak Ridge, Tennessee 37830, from 8:00 a.m. to 5:00 p.m., Monday through Friday. The ORR is located in Roane and Anderson counties, within and adjacent to the corporate city limits of Oak Ridge, Tennessee. ETTP is located in Roane County near the northwest corner of the ORR. ETTP began operation during World War II as part of the Manhattan Project. The original mission of ETTP was to produce enriched uranium for use in atomic weapons. The plant produced enriched uranium from 1945 until 1985. Uranium production was terminated in 1987. ORR was placed on the National Priorities List in 1989, so remediation activities are conducted under CERCLA. The primary contaminants of concern at ETTP follow: (1) In groundwater - volatile organic compounds (VOCs) at multiple locations (trichloroethene is generally the most prevalent compound); (2) In sediment - inorganic elements, radionuclides, and polychlorinated biphenyls; (3) In soil - inorganic elements, radionuclides, semivolatile organic compounds (particularly the polycyclic aromatic hydrocarbons), and VOCs; and (4) In facilities - radionuclides and polychlorinated biphenyls (abandoned facilities also pose a safety and health hazard to workers.) The purposes of the remedial actions selected in the Zone 1 Interim ROD are to allow unrestricted industrial use down to 10 feet and to remediate potential sources of groundwater contamination. Following is a summary of the major components of the Zone 1 Interim ROD remedy: (1) Excavation of the Blair Quarry burial area and associated contaminated soil; (2) Excavation of miscellaneous contaminated soil in the K-895 Cylinder Destruct Facility area and in the Powerhouse Area; (3) Removal of sludge and demolition of the K-710 sludge beds and Imhoff tanks; (4) Implementation of land use controls (LUCs); and (5) Characterization of soil and remediation of areas that exceed remediation levels.

Bechtel Jacobs

2011-02-01T23:59:59.000Z

259

CORRECTIVE ACTION PLAN FOR CORRECTIVE ACTION UNIT 536: AREA 3 RELEASE SITE, NEVADA TEST SITE, NEVADA  

SciTech Connect (OSTI)

CAU 536 consists of CAS 03-44-02, Steam Jenny Discharge, located in Area 3 of the NTS. The site was characterized in 2004 according to the approved CAIP and the site characterization results are reported in the CAU 536 CADD. The purpose of this Corrective Action Plan (CAP) is to provide the detailed scope of work required to implement the recommended corrective actions as specified in the approved CAU 536 CADD.

NONE

2005-09-01T23:59:59.000Z

260

Quantum corrections to screening at strong coupling  

E-Print Network [OSTI]

We compute a certain class of corrections to (specific) screening lengths in strongly coupled nonabelian plasmas using the AdS/CFT correspondence. In this holographic framework, these corrections arise from various higher curvature interactions modifying the leading Einstein gravity action. The changes in the screening lengths are perturbative in inverse powers of the 't Hooft coupling or of the number of colours, as can be made precise in the context where the dual gauge theory is superconformal. We also compare the results of these holographic calculations to lattice results for the analogous screening lengths in QCD. In particular, we apply these results within the program of making quantitative comparisons between the strongly coupled quark-gluon plasma and holographic descriptions of conformal field theory.

Ajay Singh; Aninda Sinha

2012-04-23T23:59:59.000Z

Note: This page contains sample records for the topic "icm interim corrective" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


261

G-corrected holographic dark energy model  

E-Print Network [OSTI]

Here we investigate the holographic dark energy model in the framework of FRW cosmology where the Newtonian gravitational constant,$G$, is varying with cosmic time. Using the complementary astronomical data which support the time dependency of $G$, the evolutionary treatment of EoS parameter and energy density of dark energy model are calculated in the presence of time variation of $G$. It has been shown that in this case, the phantom regime can be achieved at the present time. We also calculate the evolution of $G$- corrected deceleration parameter for holographic dark energy model and show that the dependency of $G$ on the comic time can influence on the transition epoch from decelerated expansion to the accelerated phase. Finally we perform the statefinder analysis for $G$- corrected holographic model and show that this model has a shorter distance from the observational point in $s-r$ plane compare with original holographic dark energy model.

M. Malekjani; M. Honari-Jafarpour

2013-05-01T23:59:59.000Z

262

Higher-Order Corrections to Timelike Jets  

SciTech Connect (OSTI)

We present a simple formalism for the evolution of timelike jets in which tree-level matrix element corrections can be systematically incorporated, up to arbitrary parton multiplicities and over all of phase space, in a way that exponentiates the matching corrections. The scheme is cast as a shower Markov chain which generates one single unweighted event sample, that can be passed to standard hadronization models. Remaining perturbative uncertainties are estimated by providing several alternative weight sets for the same events, at a relatively modest additional overhead. As an explicit example, we consider Z {yields} q{bar q} evolution with unpolarized, massless quarks and include several formally subleading improvements as well as matching to tree-level matrix elements through {alpha}{sub s}{sup 4}. The resulting algorithm is implemented in the publicly available VINCIA plugin to the PYTHIA8 event generator.

Giele, W.T.; /Fermilab; Kosower, D.A.; /Saclay, SPhT; Skands, P.Z.; /CERN

2011-02-01T23:59:59.000Z

263

Interim salt disposition program macrobatch 6 tank 21H qualification monosodium titanate and cesium mass transfer tests  

SciTech Connect (OSTI)

Savannah River National Laboratory (SRNL) performed experiments on qualification material for use in the Interim Salt Disposition Program (ISDP) Batch 6 processing. This qualification material was a set of six samples from Tank 21H in October 2012. This sample was used as a real waste demonstration of the Actinide Removal Process (ARP) and the Extraction-Scrub-Strip (ESS) tests process. The Tank 21H sample was contacted with a reduced amount (0.2 g/L) of MST and characterized for strontium and actinide removal at 0 and 8 hour time intervals in this salt batch. {sup 237}Np and {sup 243}Am were both observed to be below detection limits in the source material, and so these results are not reported in this report. The plutonium and uranium samples had decontamination factor (DF) values that were on par or slightly better than we expected from Batch 5. The strontium DF values are slightly lower than expected but still in an acceptable range. The Extraction, Scrub, and Strip (ESS) testing demonstrated cesium removal, stripping and scrubbing within the acceptable range. Overall, the testing indicated that cesium removal is comparable to prior batches at MCU.

Washington, A. L. II; Peters, T. B.; Fink, S. D.

2013-02-25T23:59:59.000Z

264

Extended-burnup LWR (light-water reactor) fuel: The amount, characteristics, and potential effects on interim storage  

SciTech Connect (OSTI)

The results of a study on extended-burnup, light-water reactor (LWR) spent fuel are described in this report. The study was performed by Pacific Northwest Laboratory for the US Department of Energy (DOE). The purpose of the study was to collect and evaluate information on the status of in-reactor performance and integrity of extended-burnup LWR fuel and initiate the investigation of the effects of extending fuel burnup on the subsequent handling, interim storage, and other operations (e.g., rod consolidation and shipping) associated with the back end of the fuel cycle. The results of this study will aid DOE and the nuclear industry in assessing the effects on waste management of extending the useful in-reactor life of nuclear fuel. The experience base with extended-burnup fuel is now substantial and projections for future use of extended-burnup fuel in domestic LWRs are positive. The basic performance and integrity of the fuel in the reactor has not been compromised by extending the burnup, and the potential limitations for further extending the burnup are not severe. 104 refs., 15 tabs.

Bailey, W.J.

1989-03-01T23:59:59.000Z

265

A comprehensive program to develop correlations for the physical properties of Kraft black liquor. Interim report No. 3  

SciTech Connect (OSTI)

The black liquor properties program has been conducted over this last period so as to systematically collect data on properties, liquor composition, and lignin characteristics very carefully by methods that have developed during this program. Complete data has been collected for Slash Pine black liquors made by experimental pulping at different pulping conditions. In addition, data has been collected for mill liquors and partial properties or composition data has been collected on Slash Pine black liquors. Data reduction methods have been developed or extended for correlation of viscosity, heat capacity, heat of dilution, and density. Correlation of properties to pulping conditions and of composition to. pulping conditions has begun. In most cases, data reduction methods have been developed that are fundamentally based and that have been shown to be generally applicable to all black liquors. In the near future, we fully expect to accomplish our goal of developing generalized correlations relating physical properties of Slash Pine kraft black liquors to liquor composition. This interim report reviews the methods used, describes examples of data reduction methods that have been developed, and presents some preliminary results for correlation of liquor composition and properties to pulping conditions for Slash Pine black liquors.

Fricke, A.L.; Dong, D.J.; Schmidl, G.W.; Stoy, M.A.; Zaman, A.A.

1993-09-01T23:59:59.000Z

266

Review of holographic superconductors with Weyl corrections  

E-Print Network [OSTI]

A quick review on the analytical aspects of holographic superconductors (HSC) with Weyl corrections has been presented. Mainly we focus on matching method and variations approaches. Different types of such HSC have been investigated, s-wave, p-wave and St\\'{u}ckelberg ones. We also review the fundamental construction of a p-wave type , in which the non-Abelian gauge field is coupled to the Weyl tensor. The results are compared from numerics to analytical results.

Davood Momeni; Muhammad Raza; Ratbay Myrzakulov

2014-10-29T23:59:59.000Z

267

Electroweak Corrections to the Top Quark Decay  

E-Print Network [OSTI]

We have calculated the one-loop electroweak corrections to the decay t-> bW+, including the counterterm for the CKM matrix elements V(tb). Previous calculations used an incorrect delta V(tb) that led to a gauge dependent amplitude. However, since the contribution stemming from delta V(tb) is small, those calculations only underestimate the width by roughly one part in 10^5.

S. M. Oliveira; L. Bruecher; R. Santos; A. Barroso

2001-01-18T23:59:59.000Z

268

Clean slate corrective action investigation plan  

SciTech Connect (OSTI)

The Clean Slate sites discussed in this report are situated in the central portion of the Tonopah Test Range (TTR), north of the Nevada Test Site (NTS) on the northwest portion of the Nellis Air Force Range (NAFR) which is approximately 390 kilometers (km) (240 miles [mi]) northwest of Las Vegas, Nevada. These sites were the locations for three of the four Operation Roller Coaster experiments. These experiments evaluated the dispersal of plutonium in the environment from the chemical explosion of a plutonium-bearing device. Although it was not a nuclear explosion, Operation Roller Coaster created some surface contamination which is now the subject of a corrective action strategy being implemented by the Nevada Environmental Restoration Project (NV ERP) for the U.S. Department of Energy (DOE). Corrective Action Investigation (CAI) activities will be conducted at three of the Operation Roller Coaster sites. These are Clean Slate 1 (CS-1), Clean Slate 2 (CS-2), and Clean Slate 3 (CS-3) sites, which are located on the TTR. The document that provides or references all of the specific information relative to the various investigative processes is called the Corrective Action Investigation Plan (CAIP). This CAIP has been prepared for the DOE Nevada Operations Office (DOE/NV) by IT Corporation (IT).

NONE

1996-05-01T23:59:59.000Z

269

The Error-Pattern-Correcting Turbo Equalizer  

E-Print Network [OSTI]

The error-pattern correcting code (EPCC) is incorporated in the design of a turbo equalizer (TE) with aim to correct dominant error events of the inter-symbol interference (ISI) channel at the output of its matching Viterbi detector. By targeting the low Hamming-weight interleaved errors of the outer convolutional code, which are responsible for low Euclidean-weight errors in the Viterbi trellis, the turbo equalizer with an error-pattern correcting code (TE-EPCC) exhibits a much lower bit-error rate (BER) floor compared to the conventional non-precoded TE, especially for high rate applications. A maximum-likelihood upper bound is developed on the BER floor of the TE-EPCC for a generalized two-tap ISI channel, in order to study TE-EPCC's signal-to-noise ratio (SNR) gain for various channel conditions and design parameters. In addition, the SNR gain of the TE-EPCC relative to an existing precoded TE is compared to demonstrate the present TE's superiority for short interleaver lengths and high coding rates.

Alhussien, Hakim

2010-01-01T23:59:59.000Z

270

Corrective Action Plan for Corrective Action Unit 139: Waste Disposal Sites, Nevada Test Site, Nevada  

SciTech Connect (OSTI)

Corrective Action Unit (CAU) 139, Waste Disposal Sites, is listed in the Federal Facility Agreement and Consent Order (FFACO) of 1996 (FFACO, 1996). CAU 139 consists of seven Corrective Action Sites (CASs) located in Areas 3, 4, 6, and 9 of the Nevada Test Site (NTS), which is located approximately 65 miles (mi) northwest of Las Vegas, Nevada (Figure 1). CAU 139 consists of the following CASs: CAS 03-35-01, Burn Pit; CAS 04-08-02, Waste Disposal Site; CAS 04-99-01, Contaminated Surface Debris; CAS 06-19-02, Waste Disposal Site/Burn Pit; CAS 06-19-03, Waste Disposal Trenches; CAS 09-23-01, Area 9 Gravel Gertie; and CAS 09-34-01, Underground Detection Station. Details of the site history and site characterization results for CAU 139 are provided in the approved Corrective Action Investigation Plan (CAIP) (U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office [NNSA/NSO], 2006) and in the approved Corrective Action Decision Document (CADD) (NNSA/NSO, 2007). The purpose of this Corrective Action Plan (CAP) is to present the detailed scope of work required to implement the recommended corrective actions as specified in Section 4.0 of the approved CADD (NNSA/NSO, 2007). The approved closure activities for CAU 139 include removal of soil and debris contaminated with plutonium (Pu)-239, excavation of geophysical anomalies, removal of surface debris, construction of an engineered soil cover, and implementation of use restrictions (URs). Table 1 presents a summary of CAS-specific closure activities and contaminants of concern (COCs). Specific details of the corrective actions to be performed at each CAS are presented in Section 2.0 of this report.

NSTec Environmental Restoration

2007-07-01T23:59:59.000Z

271

Corrective Action Plan for Corrective Action Unit 417: Central Nevada Test Area Surface, Nevada  

SciTech Connect (OSTI)

This Corrective Action Plan provides methods for implementing the approved corrective action alternative as provided in the Corrective Action Decision Document for the Central Nevada Test Area (CNTA), Corrective Action Unit (CAU) 417 (DOE/NV, 1999). The CNTA is located in the Hot Creek Valley in Nye County, Nevada, approximately 137 kilometers (85 miles) northeast of Tonopah, Nevada. The CNTA consists of three separate land withdrawal areas commonly referred to as UC-1, UC-3, and UC-4, all of which are accessible to the public. CAU 417 consists of 34 Corrective Action Sites (CASs). Results of the investigation activities completed in 1998 are presented in Appendix D of the Corrective Action Decision Document (DOE/NV, 1999). According to the results, the only Constituent of Concern at the CNTA is total petroleum hydrocarbons (TPH). Of the 34 CASs, corrective action was proposed for 16 sites in 13 CASs. In fiscal year 1999, a Phase I Work Plan was prepared for the construction of a cover on the UC-4 Mud Pit C to gather information on cover constructibility and to perform site management activities. With Nevada Division of Environmental Protection concurrence, the Phase I field activities began in August 1999. A multi-layered cover using a Geosynthetic Clay Liner as an infiltration barrier was constructed over the UC-4 Mud Pit. Some TPH impacted material was relocated, concrete monuments were installed at nine sites, signs warning of site conditions were posted at seven sites, and subsidence markers were installed on the UC-4 Mud Pit C cover. Results from the field activities indicated that the UC-4 Mud Pit C cover design was constructable and could be used at the UC-1 Central Mud Pit (CMP). However, because of the size of the UC-1 CMP this design would be extremely costly. An alternative cover design, a vegetated cover, is proposed for the UC-1 CMP.

K. Campbell

2000-04-01T23:59:59.000Z

272

Corrective Action Investigation Plan for Corrective Action Unit 563: Septic Systems, Nevada Test Site, Nevada, with Errata Sheet, Revision 0  

SciTech Connect (OSTI)

Corrective Action Unit 563, Septic Systems, is located in Areas 3 and 12 of the Nevada Test Site, which is 65 miles northwest of Las Vegas, Nevada. Corrective Action Unit 563 is comprised of the four corrective action sites (CASs) below: • 03-04-02, Area 3 Subdock Septic Tank • 03-59-05, Area 3 Subdock Cesspool • 12-59-01, Drilling/Welding Shop Septic Tanks • 12-60-01, Drilling/Welding Shop Outfalls These sites are being investigated because existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend corrective action alternatives. Additional information will be obtained by conducting a corrective action investigation (CAI) before evaluating corrective action alternatives and selecting the appropriate corrective action for each CAS. The results of the field investigation will support a defensible evaluation of viable corrective action alternatives that will be presented in the Corrective Action Decision Document.

Alfred Wickline

2007-01-01T23:59:59.000Z

273

Corrective Action Plan for Corrective Action Unit 562: Waste Systems, Nevada National Security Site, Nevada  

SciTech Connect (OSTI)

This Corrective Action Plan has been prepared for Corrective Action Unit (CAU) 562, Waste Systems, in accordance with the Federal Facility Agreement and Consent Order (1996; as amended March 2010). CAU 562 consists of 13 Corrective Action Sites (CASs) located in Areas 2, 23, and 25 of the Nevada National Security Site. Site characterization activities were performed in 2009 and 2010, and the results are presented in Appendix A of the Corrective Action Decision Document for CAU 562. The scope of work required to implement the recommended closure alternatives is summarized. (1) CAS 02-26-11, Lead Shot, will be clean closed by removing shot. (2) CAS 02-44-02, Paint Spills and French Drain, will be clean closed by removing paint and contaminated soil. As a best management practice (BMP), asbestos tile will be removed. (3) CAS 02-59-01, Septic System, will be clean closed by removing septic tank contents. As a BMP, the septic tank will be removed. (4) CAS 02-60-01, Concrete Drain, contains no contaminants of concern (COCs) above action levels. No further action is required; however, as a BMP, the concrete drain will be removed. (5) CAS 02-60-02, French Drain, was clean closed. Corrective actions were completed during corrective action investigation activities. As a BMP, the drain grates and drain pipe will be removed. (6) CAS 02-60-03, Steam Cleaning Drain, will be clean closed by removing contaminated soil. As a BMP, the steam cleaning sump grate and outfall pipe will be removed. (7) CAS 02-60-04, French Drain, was clean closed. Corrective actions were completed during corrective action investigation activities. (8) CAS 02-60-05, French Drain, will be clean closed by removing contaminated soil. (9) CAS 02-60-06, French Drain, contains no COCs above action levels. No further action is required. (10) CAS 02-60-07, French Drain, requires no further action. The french drain identified in historical documentation was not located during corrective action investigation activities. (11) CAS 23-60-01, Mud Trap Drain and Outfall, will be clean closed by removing sediment from the mud trap. As a BMP, the mud trap and outfall pipe will be removed. (12) CAS 23-99-06, Grease Trap, will be clean closed by removing sediment from the grease trap and backfilling the grease trap with grout. (13) CAS 25-60-04, Building 3123 Outfalls, will be clean closed by removing contaminated soil and the sludge-containing outfall pipe.

NSTec Environmental Restoration

2011-04-30T23:59:59.000Z

274

Quantum Error Correcting Subsystem Codes From Two Classical Linear Codes  

E-Print Network [OSTI]

The essential insight of quantum error correction was that quantum information can be protected by suitably encoding this quantum information across multiple independently erred quantum systems. Recently it was realized that, since the most general method for encoding quantum information is to encode it into a subsystem, there exists a novel form of quantum error correction beyond the traditional quantum error correcting subspace codes. These new quantum error correcting subsystem codes differ from subspace codes in that their quantum correcting routines can be considerably simpler than related subspace codes. Here we present a class of quantum error correcting subsystem codes constructed from two classical linear codes. These codes are the subsystem versions of the quantum error correcting subspace codes which are generalizations of Shor's original quantum error correcting subspace codes. For every Shor-type code, the codes we present give a considerable savings in the number of stabilizer measurements needed in their error recovery routines.

Dave Bacon; Andrea Casaccino

2006-10-17T23:59:59.000Z

275

Hadronic ?Z box corrections in Møller scattering  

DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

The possibility of measuring the parity-violating asymmetry in Moller scattering with sufficient accuracy to determine sin2?W to 0.1% offers a complementary path to the discovery of new physics to that followed at high energy colliders. We present a new calculation of the ?Z box contribution to parity-violating electron-proton scattering, which constitutes an important uncertainty in computing the background to this process. We show that while the ?Z correction grows rapidly with energy, it can be relatively well constrained by data from parity-violating inelastic scattering and parton distribution functions.

Hall, Nathan L. [Adelaide U.; Blunden, Peter G. [Manitoba U.; Melnitchouk, Wally [JLAB; Thomas, Anthony W. [Adelaide U.; Young, Ross D. [Adelaide U.

2014-04-01T23:59:59.000Z

276

Electroweak Radiative Corrections to Muon Capture  

E-Print Network [OSTI]

Electroweak radiative corrections to muon capture on nuclei are computed and found to be sizable. They enhance the capture rates for hydrogen and helium by 2.8% and 3.0% respectively. As a result, the value of the induced pseudoscalar coupling, g_P^exp, extracted from a recent hydrogen 1S singlet capture experiment is increased by about 21% to g_P^exp = 7.3 +/- 1.2 and brought into good agreement with the prediction of chiral perturbation theory, g_P^theory=8.2 +/- 0.2. Implications for helium capture rate predictions are also discussed.

A. Czarnecki; W. J. Marciano; A. Sirlin

2007-04-30T23:59:59.000Z

277

Automation of one-loop QCD corrections  

E-Print Network [OSTI]

We present the complete automation of the computation of one-loop QCD corrections, including UV renormalization, to an arbitrary scattering process in the Standard Model. This is achieved by embedding the OPP integrand reduction technique, as implemented in CutTools, into the MadGraph framework. By interfacing the tool so constructed, which we dub MadLoop, with MadFKS, the fully automatic computation of any infrared-safe observable at the next-to-leading order in QCD is attained. We demonstrate the flexibility and the reach of our method by calculating the production rates for a variety of processes at the 7 TeV LHC.

Valentin Hirschi; Rikkert Frederix; Stefano Frixione; Maria Vittoria Garzelli; Fabio Maltoni; Roberto Pittau

2013-05-14T23:59:59.000Z

278

Quantum corrections to spin effects in general relativity  

E-Print Network [OSTI]

Quantum power corrections to the gravitational spin-orbit and spin-spin interactions, as well as to the Lense-Thirring effect, were found for particles of spin 1/2. These corrections arise from diagrams of second order in Newton gravitational constant G with two massless particles in the unitary cut in the t-channel. The corrections obtained differ from the previous calculation of the corrections to spin effects for rotating compound bodies with spinless constituents.

G. G. Kirilin

2005-07-16T23:59:59.000Z

279

Advanced Fuels for LWRs: Fully-Ceramic Microencapsulated and Related Concepts FY 2012 Interim Report  

SciTech Connect (OSTI)

This report summarizes the progress in the Deep Burn project at Idaho National Laboratory during the first half of fiscal year 2012 (FY2012). The current focus of this work is on Fully-Ceramic Microencapsulated (FCM) fuel containing low-enriched uranium (LEU) uranium nitride (UN) fuel kernels. UO2 fuel kernels have not been ruled out, and will be examined as later work in FY2012. Reactor physics calculations confirmed that the FCM fuel containing 500 mm diameter kernels of UN fuel has positive MTC with a conventional fuel pellet radius of 4.1 mm. The methodology was put into place and validated against MCNP to perform whole-core calculations using DONJON, which can interpolate cross sections from a library generated using DRAGON. Comparisons to MCNP were performed on the whole core to confirm the accuracy of the DRAGON/DONJON schemes. A thermal fluid coupling scheme was also developed and implemented with DONJON. This is currently able to iterate between diffusion calculations and thermal fluid calculations in order to update fuel temperatures and cross sections in whole-core calculations. Now that the DRAGON/DONJON calculation capability is in place and has been validated against MCNP results, and a thermal-hydraulic capability has been implemented in the DONJON methodology, the work will proceed to more realistic reactor calculations. MTC calculations at the lattice level without the correct burnable poison are inadequate to guarantee zero or negative values in a realistic mode of operation. Using the DONJON calculation methodology described in this report, a startup core with enrichment zoning and burnable poisons will be designed. Larger fuel pins will be evaluated for their ability to (1) alleviate the problem of positive MTC and (2) increase reactivity-limited burnup. Once the critical boron concentration of the startup core is determined, MTC will be calculated to verify a non-positive value. If the value is positive, the design will be changed to require less soluble boron by, for example, increasing the reactivity hold-down by burnable poisons. Then, the whole core analysis will be repeated until an acceptable design is found. Calculations of departure from nucleate boiling ratio (DNBR) will be included in the safety evaluation as well. Once a startup core is shown to be viable, subsequent reloads will be simulated by shuffling fuel and introducing fresh fuel. The PASTA code has been updated with material properties of UN fuel from literature and a model for the diffusion and release of volatile fission products from the SiC matrix material . Preliminary simulations have been performed for both normal conditions and elevated temperatures. These results indicated that the fuel performs well and that the SiC matrix has a good retention of the fission products. The path forward for fuel performance work includes improvement of metallic fission product release from the kernel. Results should be considered preliminary and further validation is required.

R. Sonat Sen; Brian Boer; John D. Bess; Michael A. Pope; Abderrafi M. Ougouag

2012-03-01T23:59:59.000Z

280

Deep Vadose Zone Treatability Test for the Hanford Central Plateau: Interim Post-Desiccation Monitoring Results, Fiscal Year 2014  

SciTech Connect (OSTI)

Over decades of operation, the U.S. Department of Energy (DOE) and its predecessors have released nearly 2 trillion L (450 billion gal.) of liquid into the vadose zone at the Hanford Site. Much of this discharge of liquid waste into the vadose zone occurred in the Central Plateau, a 200 km2 (75 mi2) area that includes approximately 800 waste sites. Some of the inorganic and radionuclide contaminants in the deep vadose zone at the Hanford Site are at depths below the limit of direct exposure pathways, but may need to be remediated to protect groundwater. The Tri-Party Agencies (DOE, U.S. Environmental Protection Agency, and Washington State Department of Ecology) established Milestone M 015 50, which directed DOE to submit a treatability test plan for remediation of technetium-99 (Tc-99) and uranium in the deep vadose zone. These contaminants are mobile in the subsurface environment and have been detected at high concentrations deep in the vadose zone, and at some locations have reached groundwater. Testing technologies for remediating Tc-99 and uranium will also provide information relevant for remediating other contaminants in the vadose zone. A field test of desiccation is being conducted as an element of the DOE test plan published in March 2008 to meet Milestone M 015 50. The active desiccation portion of the test has been completed. Monitoring data have been collected at the field test site during the post-desiccation period and are reported herein. This is an interim data summary report that includes about 3 years of post-desiccation monitoring data. The DOE field test plan proscribes a total of 5 years of post-desiccation monitoring.

Truex, Michael J.; Strickland, Christopher E.; Johnson, Christian D.; Johnson, Timothy C.; Clayton, Ray E.; Chronister, Glen B.

2014-09-01T23:59:59.000Z

Note: This page contains sample records for the topic "icm interim corrective" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


281

UNIVERSITY OF CONNECTICUT HEALTH CENTER CORRECTIONAL MANAGED HEALTH CARE  

E-Print Network [OSTI]

UNIVERSITY OF CONNECTICUT HEALTH CENTER CORRECTIONAL MANAGED HEALTH CARE POLICY AND PROCEDURES of Connecticut Health Center (UCHC), Correctional Managed Health Care (CMHC) shall establish and maintain in Prisons (P-B-01). 2008. National Commission on Correctional Health Care. Chicago, IL. Approved: UCHC

Oliver, Douglas L.

282

Conceptual waste package interim product specifications and data requirements for disposal of borosilicate glass defense high-level waste forms in salt geologic repositories  

SciTech Connect (OSTI)

The conceptual waste package interim product specifications and data requirements presented are applicable specifically to the normal borosilicate glass product of the Defense Waste Processing Facility (DWPF). They provide preliminary numerical values for the defense high-level waste form parameters and properties identified in the waste form performance specification for geologic isolation in salt repositories. Subject areas treated include containment and isolation, operational period safety, criticality control, waste form/production canister identification, and waste package performance testing requirements. This document was generated for use in the development of conceptual waste package designs in salt. It will be revised as additional data, analyses, and regulatory requirements become available.

Not Available

1983-06-01T23:59:59.000Z

283

CORRECTIVE ACTION PLAN FOR CORRECTIVE ACTION UNIT 224: DECON PAD AND SEPTIC SYSTEMS NEVADA TEST SITE, NEVADA  

SciTech Connect (OSTI)

The purpose of this Corrective Action Plan is to provide the detailed scope of work required to implement the recommended corrective actions as specified in the approved CAU 224 CADD.

NONE

2006-07-01T23:59:59.000Z

284

Corrective Action Decision Document/ Corrective Action Plan for Corrective Action Unit 443: Central Nevada Test Area-Subsurface Central Nevada Test Area, Nevada, Rev. No. 0  

SciTech Connect (OSTI)

This Corrective Action Decision Document/Corrective Action Plan (CADD/CAP) has been prepared for the subsurface at the Central Nevada Test Area (CNTA) Corrective Action Unit (CAU) 443, CNTA - Subsurface, Nevada, in accordance with the ''Federal Facility Agreement and Consent Order'' (FFACO) (1996). CAU 443 is located in Hot Creek Valley in Nye County, Nevada, north of U.S. Highway 6, about 48 kilometers north of Warm Springs, Nevada. The CADD/CAP combines the decision document (CADD) with the corrective action plan (CAP) and provides or references the specific information necessary to recommend corrective actions for the UC-1 Cavity (Corrective Action Site 58-57-001) at CAU 443, as provided in the FFACO. The purpose of the CADD portion of the document (Section 1.0 to Section 4.0) is to identify and provide a rationale for the selection of a recommended corrective action alternative for the subsurface at CNTA. To achieve this, the following tasks were required: (1) Develop corrective action objectives; (2) Identify corrective action alternative screening criteria; (3) Develop corrective action alternatives; (4) Perform detailed and comparative evaluations of the corrective action alternatives in relation to the corrective action objectives and screening criteria; and (5) Recommend a preferred corrective action alternative for the subsurface at CNTA. A Corrective Action Investigation (CAI) was performed in several stages from 1999 to 2003, as set forth in the ''Corrective Action Investigation Plan for the Central Nevada Test Area Subsurface Sites (Corrective Action Unit No. 443)'' (DOE/NV, 1999). Groundwater modeling was the primary activity of the CAI. Three phases of modeling were conducted for the Faultless underground nuclear test. The first involved the gathering and interpretation of geologic and hydrogeologic data into a three-dimensional numerical model of groundwater flow, and use of the output of the flow model for a transport model of radionuclide release and migration behavior (Pohlmann et al., 2000). The second modeling phase (known as a Data Decision Analysis [DDA]) occurred after the Nevada Division of Environmental Protection reviewed the first model and was designed to respond to concerns regarding model uncertainty (Pohll and Mihevc, 2000). The third modeling phase updated the original flow and transport model to incorporate the uncertainty identified in the DDA, and focused the model domain on the region of interest to the transport predictions. This third phase culminated in the calculation of contaminant boundaries for the site (Pohll et al., 2003).

Susan Evans

2004-11-01T23:59:59.000Z

285

Corrective Action Plan for Corrective Action Unit 543: Liquid Disposal Units, Nevada Test Site, Nevada  

SciTech Connect (OSTI)

Corrective Action Unit (CAU) 543, Liquid Disposal Units, is listed in Appendix III of the Federal Facility Agreement and Consent Order of 1996. CAU 543 consists of seven Corrective Action Sites (CASs) located in Areas 6 and 15 of the Nevada Test Site, which is approximately 65 miles northwest of Las Vegas, Nevada. CAU 543 consists of the following seven CASs: {sm_bullet} CAS 06-07-01, Decon Pad {sm_bullet} CAS 15-01-03, Aboveground Storage Tank {sm_bullet} CAS 15-04-01, Septic Tank {sm_bullet} CAS 15-05-01, Leachfield {sm_bullet} CAS 15-08-01, Liquid Manure Tank {sm_bullet} CAS 15-23-01, Underground Radioactive Material Area {sm_bullet} CAS 15-23-03, Contaminated Sump, Piping From January 24, 2005 through April 14, 2005, CAU 543 site characterization activities were conducted, and are reported in Appendix A of the CAU 543 Corrective Action Decision Document (CADD) (U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office [NNSA/NSO], 2005). The recommended corrective action as stated in the approved CADD is No Further Action for five of the CAU 543 CASs, and Closure In Place for the remaining two CASs.

NSTec Environmental Restoration

2006-09-01T23:59:59.000Z

286

Optics measurements and corrections at RHIC  

SciTech Connect (OSTI)

The further improvement of RHIC luminosity performance requires more precise understanding of the RHIC modeling. Hence, it is necessary to minimize the beta-beat, deviation of measured beta function from the calculated beta functions based on an model. The correction of betabeat also opens up the possibility of exploring operating RHIC polarized protons at a working point near integer, a prefered choice for both luminosity as well as beam polarization. The segment-by-segment technique for reducing beta-beat demonstrated in the LHC operation for reducing the beta-beat was first tested in RHIC during its polarized proton operation in 2011. It was then fully implemented during the RHIC polarized proton operation in 2012. This paper reports the commissioning results. Future plan is also presented.

Bai M.; Aronson, J.; Blaskiewicz, M.; Luo, Y.; Robert-Demolaize, G.; White, S.

2012-05-20T23:59:59.000Z

287

Quantum Error Correction with magnetic molecules  

E-Print Network [OSTI]

Quantum algorithms often assume independent spin qubits to produce trivial $|\\uparrow\\rangle=|0\\rangle$, $|\\downarrow\\rangle=|1\\rangle$ mappings. This can be unrealistic in many solid-state implementations with sizeable magnetic interactions. Here we show that the lower part of the spectrum of a molecule containing three exchange-coupled metal ions with $S=1/2$ and $I=1/2$ is equivalent to nine electron-nuclear qubits. We derive the relation between spin states and qubit states in reasonable parameter ranges for the rare earth $^{159}$Tb$^{3+}$ and for the transition metal Cu$^{2+}$, and study the possibility to implement Shor's Quantum Error Correction code on such a molecule. We also discuss recently developed molecular systems that could be adequate from an experimental point of view.

José J. Baldoví; Salvador Cardona-Serra; Juan M. Clemente-Juan; Luis Escalera-Moreno; Alejandro Gaita-Ariño; Guillermo Mínguez Espallargas

2014-08-22T23:59:59.000Z

288

Figure correction of multilayer coated optics  

DOE Patents [OSTI]

A process is provided for producing near-perfect optical surfaces, for EUV and soft-x-ray optics. The method involves polishing or otherwise figuring the multilayer coating that has been deposited on an optical substrate, in order to correct for errors in the figure of the substrate and coating. A method such as ion-beam milling is used to remove material from the multilayer coating by an amount that varies in a specified way across the substrate. The phase of the EUV light that is reflected from the multilayer will be affected by the amount of multilayer material removed, but this effect will be reduced by a factor of 1-n as compared with height variations of the substrate, where n is the average refractive index of the multilayer.

Chapman; Henry N. (Livermore, CA), Taylor; John S. (Livermore, CA)

2010-02-16T23:59:59.000Z

289

Final Report: Correctness Tools for Petascale Computing  

SciTech Connect (OSTI)

In the course of developing parallel programs for leadership computing systems, subtle programming errors often arise that are extremely difficult to diagnose without tools. To meet this challenge, University of Maryland, the University of Wisconsin—Madison, and Rice University worked to develop lightweight tools to help code developers pinpoint a variety of program correctness errors that plague parallel scientific codes. The aim of this project was to develop software tools that help diagnose program errors including memory leaks, memory access errors, round-off errors, and data races. Research at Rice University focused on developing algorithms and data structures to support efficient monitoring of multithreaded programs for memory access errors and data races. This is a final report about research and development work at Rice University as part of this project.

Mellor-Crummey, John [Rice University

2014-10-27T23:59:59.000Z

290

Information management architecture for an integrated computing environment for the Environmental Restoration Program. Environmental Restoration Program, Volume 3, Interim technical architecture  

SciTech Connect (OSTI)

This third volume of the Information Management Architecture for an Integrated Computing Environment for the Environmental Restoration Program--the Interim Technical Architecture (TA) (referred to throughout the remainder of this document as the ER TA)--represents a key milestone in establishing a coordinated information management environment in which information initiatives can be pursued with the confidence that redundancy and inconsistencies will be held to a minimum. This architecture is intended to be used as a reference by anyone whose responsibilities include the acquisition or development of information technology for use by the ER Program. The interim ER TA provides technical guidance at three levels. At the highest level, the technical architecture provides an overall computing philosophy or direction. At this level, the guidance does not address specific technologies or products but addresses more general concepts, such as the use of open systems, modular architectures, graphical user interfaces, and architecture-based development. At the next level, the technical architecture provides specific information technology recommendations regarding a wide variety of specific technologies. These technologies include computing hardware, operating systems, communications software, database management software, application development software, and personal productivity software, among others. These recommendations range from the adoption of specific industry or Martin Marietta Energy Systems, Inc. (Energy Systems) standards to the specification of individual products. At the third level, the architecture provides guidance regarding implementation strategies for the recommended technologies that can be applied to individual projects and to the ER Program as a whole.

Not Available

1994-09-01T23:59:59.000Z

291

Corrective Action Investigation Plan for Corrective Action Unit 554: Area 23 Release Site, Nevada Test Site, Nevada, Rev. No.: 0  

SciTech Connect (OSTI)

This Corrective Action Investigation Plan (CAIP) contains project-specific information for conducting site investigation activities at Corrective Action Unit (CAU) 554: Area 23 Release Site, Nevada Test Site, Nevada. Information presented in this CAIP includes facility descriptions, environmental sample collection objectives, and criteria for the selection and evaluation of environmental samples. Corrective Action Unit 554 is located in Area 23 of the Nevada Test Site, which is 65 miles northwest of Las Vegas, Nevada. Corrective Action Unit 554 is comprised of one Corrective Action Site (CAS), which is: 23-02-08, USTs 23-115-1, 2, 3/Spill 530-90-002. This site consists of soil contamination resulting from a fuel release from underground storage tanks (USTs). Corrective Action Site 23-02-08 is being investigated because existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend corrective action alternatives. Additional information will be obtained by conducting a corrective action investigation prior to evaluating corrective action alternatives and selecting the appropriate corrective action for this CAS. The results of the field investigation will support a defensible evaluation of viable corrective action alternatives that will be presented in the Corrective Action Decision Document for CAU 554. Corrective Action Site 23-02-08 will be investigated based on the data quality objectives (DQOs) developed on July 15, 2004, by representatives of the Nevada Division of Environmental Protection; U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office; and contractor personnel. The DQO process was used to identify and define the type, amount, and quality of data needed to develop and evaluate appropriate corrective actions for CAU 554.

David A. Strand

2004-10-01T23:59:59.000Z

292

Fast Correction Optics to Reduce Chromatic Aberrations in Longitudinally Compressed Ion Beams  

E-Print Network [OSTI]

FAST CORRECTION OPTICS TO REDUCE CHROMATIC ABERRATIONS INrecent work on fast correction optics that remove the time-EINZEL LENS CORRECTION OPTIC An electrostatic, Einzel lens [

Lidia, S.M.

2009-01-01T23:59:59.000Z

293

Corrective action decision document, Second Gas Station, Tonopah test range, Nevada (Corrective Action Unit No. 403)  

SciTech Connect (OSTI)

This Corrective Action Decision Document (CADD) for Second Gas Station (Corrective Action Unit [CAU] No. 403) has been developed for the U.S. Department of Energy`s (DOE) Nevada Environmental Restoration Project to meet the requirements of the Federal Facility Agreement and Consent Order (FFACO) of 1996 as stated in Appendix VI, {open_quotes}Corrective Action Strategy{close_quotes} (FFACO, 1996). The Second Gas Station Corrective Action Site (CAS) No. 03-02-004-0360 is the only CAS in CAU No. 403. The Second Gas Station CAS is located within Area 3 of the Tonopah Test Range (TTR), west of the Main Road at the location of former Underground Storage Tanks (USTs) and their associated fuel dispensary stations. The TTR is approximately 225 kilometers (km) (140 miles [mi]) northwest of Las Vegas, Nevada, by air and approximately 56 km (35 mi) southeast of Tonopah, Nevada, by road. The TTR is bordered on the south, east, and west by the Nellis Air Force Range and on the north by sparsely populated public land administered by the Bureau of Land Management and the U.S. Forest Service. The Second Gas Station CAS was formerly known as the Underground Diesel Tank Site, Sandia Environmental Restoration Site Number 118. The gas station was in use from approximately 1965 to 1980. The USTs were originally thought to be located 11 meters (m) (36 feet [ft]) east of the Old Light Duty Shop, Building 0360, and consisted of one gasoline UST (southern tank) and one diesel UST (northern tank) (DOE/NV, 1996a). The two associated fuel dispensary stations were located northeast (diesel) and southeast (gasoline) of Building 0360 (CAU 423). Presently the site is used as a parking lot, Building 0360 is used for mechanical repairs of vehicles.

NONE

1997-11-01T23:59:59.000Z

294

Correction due to finite speed of light in absolute gravimeters  

E-Print Network [OSTI]

Correction due to finite speed of light is among the most inconsistent ones in absolute gravimetry. Formulas reported by different authors yield corrections scattered up to 8 $\\mu$Gal with no obvious reasons. The problem, though noted before, has never been studied, and nowadays the correction is rather postulated than rigorously proven. In this paper we investigate the problem from several prospectives, find the corrections for different types of absolute gravimeters, and establish relationships between different ways of implement them. The obtained results enabled us to analyze and understand the discrepancies in the results of other authors. We found that the correction derived from the Doppler effect is accountable only for $\\tfrac{2}{3}$ of the total correction due to finite speed of light, if no signal delays are considered. Another major source of inconsistency was found in the tacit use of simplified trajectory models.

Nagornyi, V D; Zanimonskiy, Y Y

2010-01-01T23:59:59.000Z

295

Corrective Action Investigation Plan for Corrective Action Unit 560: Septic Systems, Nevada Test Site, Nevada with ROTC1, Revision 0  

SciTech Connect (OSTI)

Corrective Action Unit (CAU) 560 is located in Areas 3 and 6 of the Nevada Test Site, which is approximately 65 miles northwest of Las Vegas, Nevada. Corrective Action Unit 560 is comprised of the seven corrective action sites (CASs) listed below: • 03-51-01, Leach Pit • 06-04-02, Septic Tank • 06-05-03, Leach Pit • 06-05-04, Leach Bed • 06-59-03, Building CP-400 Septic System • 06-59-04, Office Trailer Complex Sewage Pond • 06-59-05, Control Point Septic System These sites are being investigated because existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend corrective action alternatives. Additional information will be obtained by conducting a corrective action investigation before evaluating corrective action alternatives and selecting the appropriate corrective action for each CAS. The results of the field investigation will support a defensible evaluation of viable corrective action alternatives that will be presented in the Corrective Action Decision Document. The sites will be investigated based on the data quality objectives (DQOs) developed on January 22, 2008, by representatives from the Nevada Division of Environmental Protection; U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office; Stoller-Navarro Joint Venture; and National Security Technologies, LLC. The DQO process was used to identify and define the type, amount, and quality of data needed to develop and evaluate appropriate corrective actions for CAU 560.

Grant Evenson

2008-05-01T23:59:59.000Z

296

Corrective Action Investigation plan for Corrective Action Unit 546: Injection Well and Surface Releases, Nevada Test Site, Nevada, Revision 0  

SciTech Connect (OSTI)

Corrective Action Unit (CAU) 546 is located in Areas 6 and 9 of the Nevada Test Site, which is approximately 65 miles northwest of Las Vegas, Nevada. Corrective Action Unit 546 is comprised of two Corrective Action Sites (CASs) listed below: •06-23-02, U-6a/Russet Testing Area •09-20-01, Injection Well These sites are being investigated because existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend corrective action alternatives. Additional information will be obtained by conducting a corrective action investigation (CAI) before evaluating corrective action alternatives and selecting the appropriate corrective action for each CAS. The results of the field investigation will support a defensible evaluation of viable corrective action alternatives that will be presented in the Corrective Action Decision Document. The sites will be investigated based on the data quality objectives (DQOs) developed on November 8, 2007, by representatives of the Nevada Division of Environmental Protection and U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office. The DQO process has been used to identify and define the type, amount, and quality of data needed to develop and evaluate appropriate corrective actions for CAU 546.

Alfred Wickline

2008-03-01T23:59:59.000Z

297

Spatial Corrections of ROSAT HRI Observations  

E-Print Network [OSTI]

X-ray observations with the ROSAT High Resolution Imager (HRI) often have spatial smearing on the order of 10 arcsec (Morse 1994). This degradation of the intrinsic resolution of the instrument (5 arcsec) can be attributed to errors in the aspect solution associated with the wobble of the space craft or with the reacquisition of the guide stars. We have developed a set of IRAF/PROS and MIDAS/EXSAS routines to minimize these effects. Our procedure attempts to isolate aspect errors that are repeated through each cycle of the wobble. The method assigns a 'wobble phase' to each event based on the 402 second period of the ROSAT wobble. The observation is grouped into a number of phase bins and a centroid is calculated for each sub-image. The corrected HRI event list is reconstructed by adding the sub-images which have been shifted to a common source position. This method has shown approx. 30% reduction of the full width half maximum (FWHM) of an X-ray observation of the radio galaxy 3C 120. Additional examples are presented.

D. E. Harris; J. D. Silverman; G. Hasinger; I. Lehmann

1998-11-08T23:59:59.000Z

298

Homological Error Correction: Classical and Quantum Codes  

E-Print Network [OSTI]

We prove several theorems characterizing the existence of homological error correction codes both classically and quantumly. Not every classical code is homological, but we find a family of classical homological codes saturating the Hamming bound. In the quantum case, we show that for non-orientable surfaces it is impossible to construct homological codes based on qudits of dimension $D>2$, while for orientable surfaces with boundaries it is possible to construct them for arbitrary dimension $D$. We give a method to obtain planar homological codes based on the construction of quantum codes on compact surfaces without boundaries. We show how the original Shor's 9-qubit code can be visualized as a homological quantum code. We study the problem of constructing quantum codes with optimal encoding rate. In the particular case of toric codes we construct an optimal family and give an explicit proof of its optimality. For homological quantum codes on surfaces of arbitrary genus we also construct a family of codes asymptotically attaining the maximum possible encoding rate. We provide the tools of homology group theory for graphs embedded on surfaces in a self-contained manner.

H. Bombin; M. A. Martin-Delgado

2006-05-10T23:59:59.000Z

299

Guidance on NEPA Review for Corrective Actions under the Resource...  

Broader source: Energy.gov (indexed) [DOE]

process for RCRA corrective actions, in response to a recommendation in the National Academy of Sciences Report on "Improving the Environment: An Evaluation of DOE'S...

300

A Parallel Line Search Subspace Correction Method for Composite ...  

E-Print Network [OSTI]

Oct 7, 2014 ... Abstract: In this paper, we investigate a parallel subspace correction framework for composite convex optimization. The variables are first ...

Qian Dong

2014-10-07T23:59:59.000Z

Note: This page contains sample records for the topic "icm interim corrective" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


301

Stabilized Semi-Implicit Spectral Deferred Correction Methods for ...  

E-Print Network [OSTI]

Key words and phrases. spectral defect correction, spectral-Galerkin method, method of lines, Allen-Cahn and ...... [21] Anita T. Layton and Michael L. Minion.

2012-08-17T23:59:59.000Z

302

Method of absorbance correction in a spectroscopic heating value sensor  

SciTech Connect (OSTI)

A method and apparatus for absorbance correction in a spectroscopic heating value sensor in which a reference light intensity measurement is made on a non-absorbing reference fluid, a light intensity measurement is made on a sample fluid, and a measured light absorbance of the sample fluid is determined. A corrective light intensity measurement at a non-absorbing wavelength of the sample fluid is made on the sample fluid from which an absorbance correction factor is determined. The absorbance correction factor is then applied to the measured light absorbance of the sample fluid to arrive at a true or accurate absorbance for the sample fluid.

Saveliev, Alexei; Jangale, Vilas Vyankatrao; Zelepouga, Sergeui; Pratapas, John

2013-09-17T23:59:59.000Z

303

Geothermal: Sponsored by OSTI -- FORTRAN algorithm for correcting...  

Office of Scientific and Technical Information (OSTI)

FORTRAN algorithm for correcting normal resistivity logs for borehold diameter and mud resistivity Geothermal Technologies Legacy Collection HelpFAQ | Site Map | Contact Us Home...

304

Corrective Action Investigation Plan for Corrective Action Unit 145: Wells and Storage Holes, Nevada Test Site, Nevada, Rev. No.: 0  

SciTech Connect (OSTI)

This Corrective Action Investigation Plan (CAIP) contains project-specific information for conducting site investigation activities at Corrective Action Unit (CAU) 145: Wells and Storage Holes. Information presented in this CAIP includes facility descriptions, environmental sample collection objectives, and criteria for the selection and evaluation of environmental samples. Corrective Action Unit 145 is located in Area 3 of the Nevada Test Site, which is 65 miles northwest of Las Vegas, Nevada. Corrective Action Unit 145 is comprised of the six Corrective Action Sites (CASs) listed below: (1) 03-20-01, Core Storage Holes; (2) 03-20-02, Decon Pad and Sump; (3) 03-20-04, Injection Wells; (4) 03-20-08, Injection Well; (5) 03-25-01, Oil Spills; and (6) 03-99-13, Drain and Injection Well. These sites are being investigated because existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend corrective action alternatives. Additional information will be obtained by conducting a corrective action investigation (CAI) prior to evaluating corrective action alternatives and selecting the appropriate corrective action for each CAS. The results of the field investigation will support a defensible evaluation of viable corrective action alternatives that will be presented in the Corrective Action Decision Document. One conceptual site model with three release scenario components was developed for the six CASs to address all releases associated with the site. The sites will be investigated based on data quality objectives (DQOs) developed on June 24, 2004, by representatives of the Nevada Division of Environmental Protection; U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office; Stoller-Navarro Joint Venture; and Bechtel Nevada. The DQOs process was used to identify and define the type, amount, and quality of data needed to develop and evaluate appropriate corrective actions for CAU 145.

David A. Strand

2004-09-01T23:59:59.000Z

305

Corrective Action Investigation Plan for Corrective Action Unit 552: Area 12 Muckpile and Ponds, Nevada Test Site, Nevada: Revision 0  

SciTech Connect (OSTI)

This Corrective Action Investigation Plan contains the U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office's approach for collecting the data necessary to evaluate corrective action alternatives appropriate for the closure of Corrective Action Unit (CAU) 552: Area 12 Muckpile and Ponds, Nevada Test Site (NTS), Nevada, under the Federal Facility Agreement and Consent Order. Located in Area 12 on the NTS, CAU 552 consists of two Corrective Action Sites (CASs): 12-06-04, Muckpile; 12-23-05, Ponds. Corrective Action Site 12-06-04 in Area 12 consists of the G-Tunnel muckpile, which is the result of tunneling activities. Corrective Action Site 12-23-05 consists of three dry ponds adjacent to the muckpile. The toe of the muckpile extends into one of the ponds creating an overlap of two CASs. The purpose of the investigation is to ensure that adequate data are collected to provide sufficient and reliable information to identify, evaluate, and select technic ally viable corrective actions. The results of the field investigation will support a defensible evaluation of corrective action alternatives in the corrective action decision document.

U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office

2004-04-06T23:59:59.000Z

306

Universite de Marne-La-Vallee Ecole Doctorale ICMS  

E-Print Network [OSTI]

dispens´es `a l'ESIEE le go^ut des math´e- matiques discr`etes, a encourag´e mon travail de recherche

Baudoin, Geneviève

307

Materials Informatics for the ICME CyberInfrastructure | Department of  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious RankCombustion | Department of EnergyDevelopment Accident TolerantDepartmentLaboratoryEnergy

308

Vehicle Technologies Office Merit Review 2014: Applied ICME for New  

Broader source: Energy.gov (indexed) [DOE]

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr May Jun Jul(Summary) "ofEarlyEnergyDepartment of EnergyProgram2-26TheUtility-ScaleofLab Benchmarking - Level 1 | Department

309

Diffusion Databases for Mg-ICME | Department of Energy  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE:YearRound-UpHeat Pump Models |Conduct, Parent(CRADA and DOW Automotive) |and DPF |

310

Integrated Computational Materials Engineering (ICME) for Mg: International  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE:YearRound-UpHeatMulti-Dimensionalthe U.S.Indianaof

311

Integrated Computational Materials Engineering (ICME) for Mg: International  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE:YearRound-UpHeatMulti-Dimensionalthe U.S.IndianaofPilot Project | Department of Energy 2 DOE

312

Integrated Computational Materials Engineering (ICME) for Mg: International  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE:YearRound-UpHeatMulti-Dimensionalthe U.S.IndianaofPilot Project | Department of Energy 2

313

Biomass IBR Fact Sheet: ICM, Inc. | Department of Energy  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE:YearRound-Up fromDepartmentTie Ltd: ScopeDepartment1, 2011 (BETO)and Fuel09 THIS MEETING

314

Interim Chronic Beryllium Disease  

Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

Establishes Departmental expectations for addressing chronic beryllium disease throughout the Department until a Departmental rule on beryllium is promulgated. This Notice was replaced by final rule 10 CFR Part 850, Chronic Beryllium Disease Prevention Program, published December 8, 1999.

1999-12-08T23:59:59.000Z

315

Interim activities report  

SciTech Connect (OSTI)

Several developments have occurred since the 32nd WANTO Meeting that effect the status of the Savannah River Site. A request to restart K-Reactor was issued after nearly three years of intensive engineering analysis, procedure revisions and enhanced operator training to upgrade all aspects of reactor operation. In early December 1991, the Westinghouse Savannah River Company requested permission from DOE to start the K-Reactor. In mid-December the DOE and the Defense Nuclear Facility Safety Board concurred with readiness to operate and a Federal Circuit Court of Appeals ruled against a lawsuit to delay restart until a cooling tower is completed. The K-Reactor was restarted and has been in an evaluation and testing mode. Full power operation at thirty percent of maximum capacity is projected for March 1992 after which actual tritium generation will begin. Operation will continue until October when the cooling tower will be tied into the reactor cooling system. In conjunction with the restart of K-Reactor, the P-Reactor has been placed in permanent shutdown status and the L-Reactor has been placed in warm stand-by. In another reactor related situation, the DOE will delay the decision on construction of the New Production Reactor (NPR) until 1993. The choice of reactor type and location of the NPR will be integrated into the overall programmatic decision on Reconfiguration of the Weapons Complex. Finally, construction of the Replacement Tritium Facility (RTF) was resumed in December 1991 after several months stoppage for evaluation and revision of project funding procedures.

Majzlik, E.H. Jr.

1992-05-01T23:59:59.000Z

316

Interim Action Determination  

Office of Environmental Management (EM)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr May Jun Jul(Summary) "of EnergyEnergyENERGY TAX POLICIES7.pdfFuel2007 | Department7 U.S. Department ofAboutWAPA

317

Interim Action Determination  

Office of Environmental Management (EM)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr May Jun Jul(Summary) "of EnergyEnergyENERGY TAX POLICIES7.pdfFuel2007 | Department7 U.S. Department ofAboutWAPAInterim Action

318

Interim DOE O 331  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE:YearRound-UpHeatMulti-Dimensionalthe U.S.IndianaofPilotControlPresentation from

319

Corrective Action Plan for Corrective Action Unit 543: Liquid Disposal Units, Nevada Test Site, Nevada  

SciTech Connect (OSTI)

Corrective Action Unit (CAU) 543: Liquid Disposal Units is listed in Appendix III of the ''Federal Facility Agreement and Consent Order'' (FFACO) which was agreed to by the state of Nevada, the U.S. Department of Energy (DOE), and the U.S. Department of Defense (FFACO, 1996). CAU 543 sites are located in Areas 6 and 15 of the Nevada Test Site (NTS), which is approximately 65 miles northwest of Las Vegas, Nevada. CAU 543 consists of the following seven Corrective Action Sites (CASs) (Figure 1): CAS 06-07-01, Decon Pad; CAS 15-01-03, Aboveground Storage Tank; CAS 15-04-01, Septic Tank; CAS 15-05-01, Leachfield; CAS 15-08-01, Liquid Manure Tank; CAS 15-23-01, Underground Radioactive Material Area; and CAS 15-23-03, Contaminated Sump, Piping. All Area 15 CASs are located at the former U.S. Environmental Protection Agency (EPA) Farm, which operated from 1963 to 1981 and was used to support animal experiments involving the uptake of radionuclides. Each of the Area 15 CASs, except CAS 15-23-01, is associated with the disposal of waste effluent from Building 15-06, which was the primary location of the various tests and experiments conducted onsite. Waste effluent disposal from Building 15-06 involved piping, sumps, outfalls, a septic tank with leachfield, underground storage tanks, and an aboveground storage tank (AST). CAS 15-23-01 was associated with decontamination activities of farm equipment potentially contaminated with radiological constituents, pesticides, and herbicides. While the building structures were removed before the investigation took place, all the original tanks, sumps, piping, and concrete building pads remain in place. The Area 6 CAS is located at the Decontamination Facility in Area 6, a facility which operated from 1971 to 2001 and was used to decontaminate vehicles, equipment, clothing, and other materials that had become contaminated during nuclear testing activities. The CAS includes the effluent collection and distribution systems for Buildings 6-605, 6-606, and 6-607, which consists of septic tanks, sumps, piping, floor drains, drain trenches, cleanouts, and a concrete foundation. Additional details of the site history are provided in the CAU 543 Corrective Action Investigation Plan (CAIP) (U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office [NNSA/NSO], 2004a), and the CAU 543 Corrective Action Decision Document (CADD) (NNSA/NSO, 2005).

NSTec Environmental Restoration

2007-04-01T23:59:59.000Z

320

Security Protocols and Their Correctness 1 L. C. Paulson Security Protocols and Their Correctness  

E-Print Network [OSTI]

? Secrecy: who can receive it? Threats: Active attacker Careless & compromised agents . . . NO code and Their Correctness 7 L. C. Paulson Lowe's Attack in Detail 67 8 9 @A BC¨D E F 8 CG H I 6QP 7 @ R 8 S 9 TA BC¨D E F 8 CG H U VP 7 T 9 @ R 8 S A BC¨D E FD WCG H X V7 @ 9 8A BC¨D E FD WCG H X Y7 8 9 @A BC¨D WCG H I YP 7

Paulson, Lawrence C.

Note: This page contains sample records for the topic "icm interim corrective" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


321

Corrective Action Plan for Corrective Action Unit 563: Septic Systems, Nevada Test Site, Nevada  

SciTech Connect (OSTI)

This Corrective Action Plan (CAP) has been prepared for Corrective Action Unit (CAU) 563, Septic Systems, in accordance with the Federal Facility Agreement and Consent Order. CAU 563 consists of four Corrective Action Sites (CASs) located in Areas 3 and 12 of the Nevada Test Site. CAU 563 consists of the following CASs: #2; CAS 03-04-02, Area 3 Subdock Septic Tank #2; CAS 03-59-05, Area 3 Subdock Cesspool #2; CAS 12-59-01, Drilling/Welding Shop Septic Tanks #2; CAS 12-60-01, Drilling/Welding Shop Outfalls Site characterization activities were performed in 2007, and the results are presented in Appendix A of the CAU 563 Corrective Action Decision Document. The scope of work required to implement the recommended closure alternatives is summarized below. #2; CAS 03-04-02, Area 3 Subdock Septic Tank, contains no contaminants of concern (COCs) above action levels. No further action is required for this site; however, as a best management practice (BMP), all aboveground features (e.g., riser pipes and bumper posts) will be removed, the septic tank will be removed, and all open pipe ends will be sealed with grout. #2; CAS 03-59-05, Area 3 Subdock Cesspool, contains no COCs above action levels. No further action is required for this site; however, as a BMP, all aboveground features (e.g., riser pipes and bumper posts) will be removed, the cesspool will be abandoned by filling it with sand or native soil, and all open pipe ends will be sealed with grout. #2; CAS 12-59-01, Drilling/Welding Shop Septic Tanks, will be clean closed by excavating approximately 4 cubic yards (yd3) of arsenic- and chromium-impacted soil. In addition, as a BMP, the liquid in the South Tank will be removed, the North Tank will be removed or filled with grout and left in place, the South Tank will be filled with grout and left in place, all open pipe ends will be sealed with grout or similar material, approximately 10 yd3 of chlordane-impacted soil will be excavated, and debris within the CAS boundary will be removed. #2; CAS 12-60-01, Drilling/Welding Shop Outfalls, contains no COCs above action levels. No further action is required for this site; however, as a BMP, three drain pipe openings will be sealed with grout.

NSTec Environmental Restoration

2009-03-31T23:59:59.000Z

322

Correctness of Program Transformations as a Termination Problem  

E-Print Network [OSTI]

Correctness of Program Transformations as a Termination Problem Conrad Rau, David Sabel,sabel,schauss}@ki.informatik.uni-frankfurt.de Abstract. The diagram-based method to prove correctness of program transformations includes the computation of (critical) overlappings be- tween the analyzed program transformation and the (standard) reduction rules

Schmidt-Schauss, Manfred

323

Correctness of Source-Level Safety Policies Ewen Denney  

E-Print Network [OSTI]

safety policy. Recent work has thus concentrated on ways to guarantee the correctness of safety policies safety policies [13]. However, all these approaches work on the object code level, and cannot di- rectlyCorrectness of Source-Level Safety Policies Ewen Denney and Bernd Fischer QSS / RIACS NASA Ames

324

CORRECTION OF BUTT-WELDING INDUCED DISTORTIONS BY LASER FORMING  

E-Print Network [OSTI]

CORRECTION OF BUTT-WELDING INDUCED DISTORTIONS BY LASER FORMING Peng Cheng, Andrew J. Birnbaum, Y Egland Technology and Solutions Division Caterpillar Inc. Peoria, IL KEYWORDS Welding, Distortion, Correction, Laser Forming ABSTRACT Welding-induced distortion is an intrinsic phenomenon arising due

Yao, Y. Lawrence

325

Construction of Anatomically Correct Models of Mouse Brain Networks 1  

E-Print Network [OSTI]

Construction of Anatomically Correct Models of Mouse Brain Networks 1 B. H. McCormick a, W. Koh a Y and Public Health, Texas A&M University, 4458 TAMU, College Station, TX 77843-4458 Abstract The Mouse Brain Web, a federated database, provides for the construction of anatomically correct models of mouse brain

Keyser, John

326

Self-interaction corrections in density functional theory  

SciTech Connect (OSTI)

Self-interaction corrections for Kohn-Sham density functional theory are reviewed for their physical meanings, formulations, and applications. The self-interaction corrections get rid of the self-interaction error, which is the sum of the Coulomb and exchange self-interactions that remains because of the use of an approximate exchange functional. The most frequently used self-interaction correction is the Perdew-Zunger correction. However, this correction leads to instabilities in the electronic state calculations of molecules. To avoid these instabilities, several self-interaction corrections have been developed on the basis of the characteristic behaviors of self-interacting electrons, which have no two-electron interactions. These include the von Weizsäcker kinetic energy and long-range (far-from-nucleus) asymptotic correction. Applications of self-interaction corrections have shown that the self-interaction error has a serious effect on the states of core electrons, but it has a smaller than expected effect on valence electrons. This finding is supported by the fact that the distribution of self-interacting electrons indicates that they are near atomic nuclei rather than in chemical bonds.

Tsuneda, Takao, E-mail: ttsuneda@yamanashi.ac.jp [Fuel Cell Nanomaterials Center, University of Yamanashi, Kofu 400-0021 (Japan)] [Fuel Cell Nanomaterials Center, University of Yamanashi, Kofu 400-0021 (Japan); Hirao, Kimihiko [Computational Chemistry Unit, RIKEN Advanced Institute for Computational Science, Kobe, Hyogo 650-0047 (Japan)] [Computational Chemistry Unit, RIKEN Advanced Institute for Computational Science, Kobe, Hyogo 650-0047 (Japan)

2014-05-14T23:59:59.000Z

327

Entanglement and Quantum Error Correction with Superconducting Qubits  

E-Print Network [OSTI]

Entanglement and Quantum Error Correction with Superconducting Qubits A Dissertation Presented David Reed All rights reserved. #12;Entanglement and Quantum Error Correction with Superconducting is to use superconducting quantum bits in the circuit quantum electro- dynamics (cQED) architecture. There

328

Accurate Visual Features for Automatic Tag Correction in Videos  

E-Print Network [OSTI]

Accurate Visual Features for Automatic Tag Correction in Videos Hoang-Tung Tran, Elisa Fromont-Etienne, Fr Abstract. We present a new system for video auto tagging which aims at correcting the tags provided by users for videos uploaded on the In- ternet. Unlike most existing systems, in our proposal, we

Paris-Sud XI, Université de

329

Quantum Error Correction of Continuous Variable States against Gaussian Noise  

E-Print Network [OSTI]

We describe a continuous variable error correction protocol that can correct the Gaussian noise induced by linear loss on Gaussian states. The protocol can be implemented using linear optics and photon counting. We explore the theoretical bounds of the protocol as well as the expected performance given current knowledge and technology.

T. C. Ralph

2011-05-22T23:59:59.000Z

330

New approximation for free surface flow of groundwater: capillarity correction  

E-Print Network [OSTI]

capillarity correction for free surface groundwater flow as modelled by the Boussinesq equation is re; Shallow flow expansion; Simplified approximation 1. Introduction Groundwater heads in coastal aquifersNew approximation for free surface flow of groundwater: capillarity correction D.-S. Jeng a,*, B

Walter, M.Todd

331

NDetermin: Inferring Nondeterministic Sequential Specifications for Parallelism Correctness  

E-Print Network [OSTI]

NDetermin: Inferring Nondeterministic Sequential Specifications for Parallelism Correctness Jacob and that copies bear this notice and the full citation on the first page. To copy otherwise, to republish, to post;NDetermin: Inferring Nondeterministic Sequential Specifications for Parallelism Correctness Jacob Burnim

Necula, George

332

Diesel Emission Control -- Sulfur Effects (DECSE) Program; Phase I Interim Date Report No. 3: Diesel Fuel Sulfur Effects on Particulate Matter Emissions  

SciTech Connect (OSTI)

The Diesel Emission Control-Sulfur Effects (DECSE) is a joint government/industry program to determine the impact of diesel fuel sulfur levels on emission control systems whose use could lower emissions of nitrogen oxides (NO{sub x}) and particulate matter (PM) from on-highway trucks in the 2002--2004 model years. Phase 1 of the program was developed with the following objectives in mind: (1) evaluate the effects of varying the level of sulfur content in the fuel on the emission reduction performance of four emission control technologies; and (2) measure and compare the effects of up to 250 hours of aging on selected devices for multiple levels of fuel sulfur content. This interim report covers the effects of diesel fuel sulfur level on particulate matter emissions for four technologies.

DOE; ORNL; NREL; EMA; MECA

1999-11-15T23:59:59.000Z

333

Final report of the independent counsel for Iran/Contra matters. Volume 2: Indictments, plea agreements, interim reports to the congress, and administrative matters  

SciTech Connect (OSTI)

In October and November 1986, two secret U.S. Government operations were publicly exposed, potentially implicating Reagan Administration officials in illegal activities. These operations were the provision of assistance to the military activities of the Nicaraguan contra rebels during an October 1984 to October 1986 prohibition on such aid, and the sale of U.S. arms to Iran in contravention of stated U.S. policy and in possible violation of arms-export controls. In late November 1986, Reagan Administration officials announced that some of the proceeds from the sale of U.S. arms to Iran had been diverted to the contras. As a result, Attorney General Edwin Meese III sought the appointment of an independent counsel to investigate and prosecute possible crimes. Volume II contains indictments, plea agreements, interim reports to Congress and administrative matters from that investigation.

Walsh, L.E.

1993-08-04T23:59:59.000Z

334

Holographic p-wave superconductor models with Weyl corrections  

E-Print Network [OSTI]

We study the effect of the Weyl corrections on the holographic p-wave dual models in the backgrounds of AdS soliton and AdS black hole via a Maxwell complex vector field model by using the numerical and analytical methods. We find that, in the soliton background, the Weyl corrections do not influence the properties of the holographic p-wave insulator/superconductor phase transition, which is different from that of the Yang-Mills theory. However, in the black hole background, we observe that similar to the Weyl correction effects in the Yang-Mills theory, the higher Weyl corrections make it easier for the p-wave metal/superconductor phase transition to be triggered, which shows that these two p-wave models with Weyl corrections share some similar features for the condensation of the vector operator.

Zhang, Lu; Jing, Jiliang

2015-01-01T23:59:59.000Z

335

Parton distribution function uncertainties & nuclear corrections for the LHC  

E-Print Network [OSTI]

We study nuclear effects of charged current deep inelastic neutrino-iron scattering in the framework of a chi^2 analysis of parton distribution functions (PDFs). We extract a set of iron PDFs which are used to compute x_Bj-dependent and Q^2-dependent nuclear correction factors for iron structure functions which are required in global analyses of free nucleon PDFs. We compare our results with nuclear correction factors from neutrino-nucleus scattering models and correction factors for charged lepton-iron scattering. We find that, except for very high x_Bj, our correction factors differ in both shape and magnitude from the correction factors of the models and charged-lepton scattering.

Schienbein, I; Keppel, C; Morfín, J G; Olness, Fredrick I; Owens, J F

2008-01-01T23:59:59.000Z

336

Corrective measures evaluation report for Tijeras Arroyo groundwater.  

SciTech Connect (OSTI)

This Corrective Measures Evaluation report was prepared as directed by a Compliance Order on Consent issued by the New Mexico Environment Department to document the process of selecting the preferred remedial alternative for Tijeras Arroyo Groundwater. Supporting information includes background concerning the site conditions and potential receptors and an overview of work performed during the Corrective Measures Evaluation. The evaluation of remedial alternatives included identifying and describing four remedial alternatives, an overview of the evaluation criteria and approach, comparing remedial alternatives to the criteria, and selecting the preferred remedial alternative. As a result of the Corrective Measures Evaluation, monitored natural attenuation of the contaminants of concern (trichloroethene and nitrate) is the preferred remedial alternative for implementation as the corrective measure for Tijeras Arroyo Groundwater. Design criteria to meet cleanup goals and objectives and the corrective measures implementation schedule for the preferred remedial alternative are also presented.

Witt, Johnathan L (North Wind, Inc., Idaho Falls, ID); Orr, Brennon R. (North Wind, Inc., Idaho Falls, ID); Dettmers, Dana L. (North Wind, Inc., Idaho Falls, ID); Hall, Kevin A. (North Wind, Inc., Idaho Falls, ID); Howard, M. Hope (North Wind, Inc., Idaho Falls, ID)

2005-08-01T23:59:59.000Z

337

Corrective Action Plan for Corrective Action Unit 151: Septic Systems and Discharge Area, Nevada Test Site, Nevada  

SciTech Connect (OSTI)

Corrective Action Unit (CAU) 151, Septic Systems and Discharge Area, is listed in the Federal Facility Agreement and Consent Order (FFACO) of 1996 (FFACO, 1996). CAU 151 consists of eight Corrective Action Sites (CASs) located in Areas 2, 12, and 18 of the Nevada Test Site (NTS), which is located approximately 65 miles northwest of Las Vegas, Nevada.

NSTec Environmental Restoration

2007-03-01T23:59:59.000Z

338

Corrective Action Investigation Plan for Corrective Action Unit 374: Area 20 Schooner Unit Crater Nevada Test Site, Nevada, Revision 0  

SciTech Connect (OSTI)

Corrective Action Unit 374 is located in Areas 18 and 20 of the Nevada Test Site, which is approximately 65 miles northwest of Las Vegas, Nevada. Corrective Action Unit 374 comprises the five corrective action sites (CASs) listed below: • 18-22-05, Drum • 18-22-06, Drums (20) • 18-22-08, Drum • 18-23-01, Danny Boy Contamination Area • 20-45-03, U-20u Crater (Schooner) These sites are being investigated because existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend corrective action alternatives (CAAs). Additional information will be obtained by conducting a corrective action investigation before evaluating CAAs and selecting the appropriate corrective action for each CAS. The results of the field investigation will support a defensible evaluation of viable CAAs that will be presented in the Corrective Action Decision Document. The sites will be investigated based on the data quality objectives (DQOs) developed on October 20, 2009, by representatives of the Nevada Division of Environmental Protection and the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office. The DQO process was used to identify and define the type, amount, and quality of data needed to develop and evaluate appropriate corrective actions for CAU 374.

Patrick Matthews

2010-02-01T23:59:59.000Z

339

Corrective Action Investigation Plan for Corrective Action Unit 551: Area 12 Muckpiles, Nevada Test Site, Nevada, Rev. No.: 0  

SciTech Connect (OSTI)

This Corrective Action Investigation Plan (CAIP) contains project-specific information including facility descriptions, environmental sample collection objectives, and criteria for conducting site investigation activities at Corrective Action Unit (CAU) 551, Area 12 muckpiles, Nevada Test Site (NTS), Nevada. This CAIP has been developed in accordance with the ''Federal Facility Agreement and Consent Order'' (FFACO) (1996) that was agreed to by the State of Nevada, the U.S. Department of Energy (DOE), and the U.S. Department of Defense. Corrective Action Unit 551 is located in Area 12 of the NTS, which is approximately 110 miles (mi) northwest of Las Vegas, Nevada (Figure 1-1). Area 12 is approximately 40 miles beyond the main gate to the NTS. Corrective Action Unit 551 is comprised of the four Corrective Action Sites (CASs) shown on Figure 1-1 and listed below: (1) 12-01-09, Aboveground Storage Tank and Stain; (2) 12-06-05, Muckpile; (3) 12-06-07, Muckpile; and (4) 12-06-08, Muckpile. Corrective Action Site 12-01-09 is located in Area 12 and consists of an above ground storage tank (AST) and associated stain. Corrective Action Site 12-06-05 is located in Area 12 and consists of a muckpile associated with the U12 B-Tunnel. Corrective Action Site 12-06-07 is located in Area 12 and consists of a muckpile associated with the U12 C-, D-, and F-Tunnels. Corrective Action Site 12-06-08 is located in Area 12 and consists of a muckpile associated with the U12 B-Tunnel. In keeping with common convention, the U12B-, C-, D-, and F-Tunnels will be referred to as the B-, C-, D-, and F-Tunnels. The corrective action investigation (CAI) will include field inspections, radiological surveys, and sampling of media, where appropriate. Data will also be obtained to support waste management decisions.

David A. Strand

2004-06-01T23:59:59.000Z

340

Corrective Action Investigation Plan for Corrective Action Unit 551: Area 12 Muckpiles, Nevada Test Site, Nevada, Rev. No. 0  

SciTech Connect (OSTI)

This Corrective Action Investigation Plan (CAIP) contains project-specific information including facility descriptions, environmental sample collection objectives, and criteria for conducting site investigation activities at Corrective Action Unit (CAU) 551, Area 12 muckpiles, Nevada Test Site (NTS), Nevada. This CAIP has been developed in accordance with the ''Federal Facility Agreement and Consent Order'' (FFACO) (1996) that was agreed to by the State of Nevada, the U.S. Department of Energy (DOE), and the U.S. Department of Defense. Corrective Action Unit 551 is located in Area 12 of the NTS, which is approximately 110 miles (mi) northwest of Las Vegas, Nevada (Figure 1-1). Area 12 is approximately 40 miles beyond the main gate to the NTS. Corrective Action Unit 551 is comprised of the four Corrective Action Sites (CASs) shown on Figure 1-1 and listed below: (1) 12-01-09, Aboveground Storage Tank and Stain; (2) 12-06-05, Muckpile; (3) 12-06-07, Muckpile; and (4) 12-06-08, Muckpile. Corrective Action Site 12-01-09 is located in Area 12 and consists of an above ground storage tank (AST) and associated stain. Corrective Action Site 12-06-05 is located in Area 12 and consists of a muckpile associated with the U12 B-Tunnel. Corrective Action Site 12-06-07 is located in Area 12 and consists of a muckpile associated with the U12 C-, D-, and F-Tunnels. Corrective Action Site 12-06-08 is located in Area 12 and consists of a muckpile associated with the U12 B-Tunnel. In keeping with common convention, the U12B-, C-, D-, and F-Tunnels will be referred to as the B-, C-, D-, and F-Tunnels. The corrective action investigation (CAI) will include field inspections, radiological surveys, and sampling of media, where appropriate. Data will also be obtained to support waste management decisions.

Robert F. Boehlecke

2004-06-01T23:59:59.000Z

Note: This page contains sample records for the topic "icm interim corrective" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


341

Corrective Action Investigation Plan for Corrective Action Unit 557: Spills and Tank Sites, Nevada Test Site, Nevada, Revision 0  

SciTech Connect (OSTI)

Corrective Action Unit (CAU) 557 is located in Areas 1, 3, 6, and 25 of the Nevada Test Site, which is approximately 65 miles northwest of Las Vegas, Nevada, and is comprised of the four corrective action sites (CASs) listed below: • 01-25-02, Fuel Spill • 03-02-02, Area 3 Subdock UST • 06-99-10, Tar Spills • 25-25-18, Train Maintenance Bldg 3901 Spill Site These sites are being investigated because existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend corrective action alternatives. Additional information will be obtained by conducting a corrective action investigation before evaluating corrective action alternatives and selecting the appropriate corrective action for each CAS. The results of the field investigation will support a defensible evaluation of viable corrective action alternatives that will be presented in the Corrective Action Decision Document. The sites will be investigated based on the data quality objectives (DQOs) developed on April 3, 2008, by representatives of the Nevada Division of Environmental Protection (NDEP); U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office; Stoller-Navarro Joint Venture; and National Security Technologies, LLC. The DQO process was used to identify and define the type, amount, and quality of data needed to develop and evaluate appropriate corrective actions for CAU 557. Appendix A provides a detailed discussion of the DQO methodology and the DQOs specific to each CAS. The scope of the corrective action investigation for CAU 557 includes the following activities: • Move surface debris and/or materials, as needed, to facilitate sampling. • Conduct radiological survey at CAS 25-25-18. • Perform field screening. • Collect and submit environmental samples for laboratory analysis to determine whether contaminants of concern are present. • If contaminants of concern are present, collect additional step-out samples to define the extent of the contamination. • Collect samples of investigation-derived waste, as needed, for waste management purposes.

Alfred Wickline

2008-07-01T23:59:59.000Z

342

Corrective Action Investigation Plan for Corrective Action Unit 139: Waste Disposal Sites, Nevada Test Site, Nevada, Rev. No.: 0  

SciTech Connect (OSTI)

Corrective Action Unit (CAU) 139 is located in Areas 3, 4, 6, and 9 of the Nevada Test Site, which is 65 miles northwest of Las Vegas, Nevada. Corrective Action Unit 139 is comprised of the seven corrective action sites (CASs) listed below: (1) 03-35-01, Burn Pit; (2) 04-08-02, Waste Disposal Site; (3) 04-99-01, Contaminated Surface Debris; (4) 06-19-02, Waste Disposal Site/Burn Pit; (5) 06-19-03, Waste Disposal Trenches; (6) 09-23-01, Area 9 Gravel Gertie; and (7) 09-34-01, Underground Detection Station. These sites are being investigated because existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend corrective action alternatives with the exception of CASs 09-23-01 and 09-34-01. Regarding these two CASs, CAS 09-23-01 is a gravel gertie where a zero-yield test was conducted with all contamination confined to below ground within the area of the structure, and CAS 09-34-01 is an underground detection station where no contaminants are present. Additional information will be obtained by conducting a corrective action investigation (CAI) before evaluating corrective action alternatives and selecting the appropriate corrective action for the other five CASs where information is insufficient. The results of the field investigation will support a defensible evaluation of viable corrective action alternatives that will be presented in the Corrective Action Decision Document. The sites will be investigated based on the data quality objectives (DQOs) developed on January 4, 2006, by representatives of the Nevada Division of Environmental Protection; U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office; Stoller-Navarro Joint Venture; and Bechtel Nevada. The DQO process was used to identify and define the type, amount, and quality of data needed to develop and evaluate appropriate corrective actions for CAU 139.

Grant Evenson

2006-04-01T23:59:59.000Z

343

Corrective Action Investigation Plan for Corrective Action Unit 562: Waste Systems Nevada Test Site, Nevada, Revision 0  

SciTech Connect (OSTI)

Corrective Action Unit 562 is located in Areas 2, 23, and 25 of the Nevada Test Site, which is approximately 65 miles northwest of Las Vegas, Nevada. Corrective Action Unit 562 is comprised of the 13 corrective action sites (CASs) listed below: • 02-26-11, Lead Shot • 02-44-02, Paint Spills and French Drain • 02-59-01, Septic System • 02-60-01, Concrete Drain • 02-60-02, French Drain • 02-60-03, Steam Cleaning Drain • 02-60-04, French Drain • 02-60-05, French Drain • 02-60-06, French Drain • 02-60-07, French Drain • 23-60-01, Mud Trap Drain and Outfall • 23-99-06, Grease Trap • 25-60-04, Building 3123 Outfalls These sites are being investigated because existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend corrective action alternatives. Additional information will be obtained by conducting a corrective action investigation before evaluating corrective action alternatives and selecting the appropriate corrective action for each CAS. The results of the field investigation will support a defensible evaluation of viable corrective action alternatives that will be presented in the Corrective Action Decision Document. The sites will be investigated based on the data quality objectives (DQOs) developed on December 11, 2008, by representatives of the Nevada Division of Environmental Protection; U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office; Stoller-Navarro Joint Venture; and National Security Technologies, LLC. The DQO process was used to identify and define the type, amount, and quality of data needed to develop and evaluate appropriate corrective actions for CAU 562. Appendix A provides a detailed discussion of the DQO methodology and the DQOs specific to each CAS. The scope of the corrective action investigation for CAU 562 includes the following activities: • Move surface debris and/or materials, as needed, to facilitate sampling. • Conduct radiological surveys. • Perform field screening. • Collect and submit environmental samples for laboratory analysis to determine the nature and extent of any contamination released by each CAS. • Collect samples of source material to determine the potential for a release. • Collect samples of potential remediation wastes. • Collect quality control samples. This Corrective Action Investigation Plan has been developed in accordance with the Federal Facility Agreement and Consent Order that was agreed to by the State of Nevada; DOE, Environmental Management; U.S. Department of Defense; and DOE, Legacy Management (FFACO, 1996; as amended February 2008). Under the Federal Facility Agreement and Consent Order, this Corrective Action Investigation Plan will be submitted to the Nevada Division of Environmental Protection for approval. Fieldwork will be conducted following approval of the plan.

Alfred Wickline

2009-04-01T23:59:59.000Z

344

Power Corrections in Electron-Positron Annihilation: Experimental Review  

E-Print Network [OSTI]

Experimental studies of power corrections with e+e- data are reviewed. An overview of the available data for jet and event shape observables is given and recent analyses based on the Dokshitzer-Marchesini-Webber (DMW) model of power corrections are summarised. The studies involve both distributions of the observables and their mean values. The agreement between perturbative QCD combined with DMW power corrections and the data is generally good, and the few exceptions are discussed. The use of low energy data sets highlights deficiencies in the existing calculations for some observables. A study of the finiteness of the physical strong coupling at low energies using hadronic $\\tau$ decays is shown.

Kluth, S

2006-01-01T23:59:59.000Z

345

Power Corrections in Electron-Positron Annihilation: Experimental Review  

E-Print Network [OSTI]

Experimental studies of power corrections with e+e- data are reviewed. An overview of the available data for jet and event shape observables is given and recent analyses based on the Dokshitzer-Marchesini-Webber (DMW) model of power corrections are summarised. The studies involve both distributions of the observables and their mean values. The agreement between perturbative QCD combined with DMW power corrections and the data is generally good, and the few exceptions are discussed. The use of low energy data sets highlights deficiencies in the existing calculations for some observables. A study of the finiteness of the physical strong coupling at low energies using hadronic $\\tau$ decays is shown.

Stefan Kluth

2006-06-20T23:59:59.000Z

346

Self-Correcting HVAC Controls Project Final Report  

SciTech Connect (OSTI)

This document represents the final project report for the Self-Correcting Heating, Ventilating and Air-Conditioning (HVAC) Controls Project jointly funded by Bonneville Power Administration (BPA) and the U.S. Department of Energy (DOE) Building Technologies Program (BTP). The project, initiated in October 2008, focused on exploratory initial development of self-correcting controls for selected HVAC components in air handlers. This report, along with the companion report documenting the algorithms developed, Self-Correcting HVAC Controls: Algorithms for Sensors and Dampers in Air-Handling Units (Fernandez et al. 2009), document the work performed and results of this project.

Fernandez, Nicholas; Brambley, Michael R.; Katipamula, Srinivas; Cho, Heejin; Goddard, James K.; Dinh, Liem H.

2010-01-04T23:59:59.000Z

347

Quantum Corrections in String Compactifications on SU(3) Structure Geometries  

E-Print Network [OSTI]

We investigate quantum corrections to the classical four-dimensional low-energy effective action of type II string theory compactified on SU(3) structure geometries. Various methods previously developed for Calabi-Yau compactifications are adopted to determine - under some simple assumptions about the low-energy degrees of freedom - the leading perturbative corrections to the moduli space metrics in both alpha' and the string coupling constant. We find - in complete analogy to the Calabi-Yau case - that the corrections take a universal form dependent only on the Euler characteristic of the six-dimensional compact space.

Mariana Grana; Jan Louis; Ulrich Theis; Daniel Waldram

2014-12-05T23:59:59.000Z

348

Corrective Action Investigation Plan for Corrective Action Unit 137: Waste Disposal Sites, Nevada Test Site, Nevada, Rev. No.:0  

SciTech Connect (OSTI)

This Corrective Action Investigation Plan (CAIP) contains project-specific information including facility descriptions, environmental sample collection objectives, and criteria for conducting site investigation activities at Corrective Action Unit (CAU) 137: Waste Disposal Sites. This CAIP has been developed in accordance with the ''Federal Facility Agreement and Consent Order'' (FFACO) (1996) that was agreed to by the State of Nevada, the U.S. Department of Energy (DOE), and the U.S. Department of Defense. Corrective Action Unit 137 contains sites that are located in Areas 1, 3, 7, 9, and 12 of the Nevada Test Site (NTS), which is approximately 65 miles (mi) northwest of Las Vegas, Nevada (Figure 1-1). Corrective Action Unit 137 is comprised of the eight corrective action sites (CASs) shown on Figure 1-1 and listed below: (1) CAS 01-08-01, Waste Disposal Site; (2) CAS 03-23-01, Waste Disposal Site; (3) CAS 03-23-07, Radioactive Waste Disposal Site; (4) CAS 03-99-15, Waste Disposal Site; (5) CAS 07-23-02, Radioactive Waste Disposal Site; (6) CAS 09-23-07, Radioactive Waste Disposal Site; (7) CAS 12-08-01, Waste Disposal Site; and (8) CAS 12-23-07, Waste Disposal Site. The Corrective Action Investigation (CAI) will include field inspections, radiological surveys, geophysical surveys, sampling of environmental media, analysis of samples, and assessment of investigation results, where appropriate. Data will be obtained to support corrective action alternative evaluations and waste management decisions. The CASs in CAU 137 are being investigated because hazardous and/or radioactive constituents may be present in concentrations that could potentially pose a threat to human health and the environment. Existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend corrective action alternatives for the CASs. Additional information will be generated by conducting a CAI before evaluating and selecting corrective action alternatives.

Wickline, Alfred

2005-12-01T23:59:59.000Z

349

Corrective Action Investigation Plan for Corrective Action Unit 365: Baneberry Contamination Area, Nevada National Security Site, Nevada, Revision 0  

SciTech Connect (OSTI)

Corrective Action Unit 365 comprises one corrective action site (CAS), CAS 08-23-02, U-8d Contamination Area. This site is being investigated because existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend corrective action alternatives (CAAs). Additional information will be obtained by conducting a corrective action investigation before evaluating CAAs and selecting the appropriate corrective action for the CAS. The results of the field investigation will support a defensible evaluation of viable CAAs that will be presented in the Corrective Action Decision Document. The site will be investigated based on the data quality objectives (DQOs) developed on July 6, 2010, by representatives of the Nevada Division of Environmental Protection and the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office. The DQO process was used to identify and define the type, amount, and quality of data needed to develop and evaluate appropriate corrective actions for the Baneberry site. The primary release associated with Corrective Action Unit 365 was radiological contamination from the Baneberry nuclear test. Baneberry was an underground weapons-related test that vented significant quantities of radioactive gases from a fissure located in close proximity to ground zero. A crater formed shortly after detonation, which stemmed part of the flow from the fissure. The scope of this investigation includes surface and shallow subsurface (less than 15 feet below ground surface) soils. Radionuclides from the Baneberry test with the potential to impact groundwater are included within the Underground Test Area Subproject. Investigations and corrective actions associated with the Underground Test Area Subproject include the radiological inventory resulting from the Baneberry test.

Patrick Matthews

2010-12-01T23:59:59.000Z

350

Quantum corrections to nonlinear ion acoustic wave with Landau damping  

SciTech Connect (OSTI)

Quantum corrections to nonlinear ion acoustic wave with Landau damping have been computed using Wigner equation approach. The dynamical equation governing the time development of nonlinear ion acoustic wave with semiclassical quantum corrections is shown to have the form of higher KdV equation which has higher order nonlinear terms coming from quantum corrections, with the usual classical and quantum corrected Landau damping integral terms. The conservation of total number of ions is shown from the evolution equation. The decay rate of KdV solitary wave amplitude due to the presence of Landau damping terms has been calculated assuming the Landau damping parameter ?{sub 1}=?(m{sub e}/m{sub i}) to be of the same order of the quantum parameter Q=?{sup 2}/(24m{sup 2}c{sub s}{sup 2}L{sup 2}). The amplitude is shown to decay very slowly with time as determined by the quantum factor Q.

Mukherjee, Abhik; Janaki, M. S. [Saha Institute of Nuclear Physics, Calcutta (India); Bose, Anirban [Serampore College, West Bengal (India)

2014-07-15T23:59:59.000Z

351

Passive background correction method for spatially resolved detection  

DOE Patents [OSTI]

A method for passive background correction during spatially or angularly resolved detection of emission that is based on the simultaneous acquisition of both the passive background spectrum and the spectrum of the target of interest.

Schmitt, Randal L. (Tijeras, NM); Hargis, Jr., Philip J. (Albuquerque, NM)

2011-05-10T23:59:59.000Z

352

CONCEPTUAL: A Network Correctness and Performance Testing Language Scott Pakin  

E-Print Network [OSTI]

CONCEPTUAL: A Network Correctness and Performance Testing Language Scott Pakin CCS-3: Modeling by a running application. Con- sider, for example, a bandwidth benchmark, which purport- edly measures data

353

Correctness of depiction in planar diagrams of spatial figures  

E-Print Network [OSTI]

We show that it is possible to decide whether a given planar diagram correctly depicts the spatial figure consisting of a planar quadrangle together with its shadow in another plane.

P. L. Robinson

2014-03-12T23:59:59.000Z

354

applying recirculation correction: Topics by E-print Network  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

nuclei Physics (arXiv) Summary: A contribution is presented to the application of fractal properties and log-periodic corrections to the masses of several nuclei (isotopes or...

355

Model Error Correction for Linear Methods in PET Neuroreceptor Measurements  

E-Print Network [OSTI]

Model Error Correction for Linear Methods in PET Neuroreceptor Measurements Hongbin Guo address: hguo1@asu.edu (Hongbin Guo) Preprint submitted to NeuroImage December 11, 2008 #12;reached. A new

Renaut, Rosemary

356

SCALE-CORRECTED ENSEMBLE KALMAN FILTER FOR OBSERVATIONS OF PRODUCTION  

E-Print Network [OSTI]

to introduce bias in production forecasts. The Scale-Corrected Ensemble Kalman Filter (SCEnKF) is a method is pressure at time t. Reservoir production properties at time t, such as gas-oil ratio (gor), bottom hole

Eidsvik, Jo

357

Corrective Action Investigation Plan for Corrective Action Unit 573: Alpha Contaminated Sites, Nevada National Security Site, Nevada, Revision 0  

SciTech Connect (OSTI)

Corrective Action Unit (CAU) 573 is located in Area 5 of the Nevada National Security Site, which is approximately 65 miles northwest of Las Vegas, Nevada. CAU 573 is a grouping of sites where there has been a suspected release of contamination associated with non-nuclear experiments and nuclear testing. This document describes the planned investigation of CAU 573, which comprises the following corrective action sites (CASs): • 05-23-02, GMX Alpha Contaminated Area • 05-45-01, Atmospheric Test Site - Hamilton These sites are being investigated because existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend corrective action alternatives.

Matthews, Patrick

2014-05-01T23:59:59.000Z

358

Well correction factors for three-dimensional reservoir simulation  

E-Print Network [OSTI]

of Advisory Committee: Dr. W. D. Von Gonten A three-dimensional reservoir simulation model does not calculate the correct bottomhole flowing pressure, p f, for a partially penetrating well. The simulator well cell pressure must be corrected ro obtain... an accurate value for p f. Simulation model results have wf' been used in this part to develop a new inflow equation relating cell pressure to actual bottomhole flowing pressure for a partially penetrating well. Based on the new inflow equation, an equation...

Fjerstad, Paul Albert

1985-01-01T23:59:59.000Z

359

An error correcting procedure for imperfect supervised, nonparametric classification  

E-Print Network [OSTI]

AN ERROR CORRECTING PROCEDJJRE FOR IMPERFECTI, Y SUPERVISED, NONPARAMETRIC CLASSIFICATION A Thesis by DENNIS RAY FERRELL Submitted to the Graduate College of Texas AAM University in partial fulfillment of the requirement for the degree...) (Head f Depart en ) (Member) (Member) PE y (Memb ei) (Member) August 1973 ABSTRACT An Error Correcting Procedure For Imperfectly Supervised, Nonparametric Classification (August 1973) Dennis Ray Ferrell, B. S. , I, omar University Directed by...

Ferrell, Dennis Ray

2012-06-07T23:59:59.000Z

360

Method and system for photoconductive detector signal correction  

DOE Patents [OSTI]

A corrective factor is applied so as to remove anomalous features from the signal generated by a photoconductive detector, and to thereby render the output signal highly linear with respect to the energy of incident, time-varying radiation. The corrective factor may be applied through the use of either digital electronic data processing means or analog circuitry, or through a combination of those effects.

Carangelo, Robert M. (Glastonbury, CT); Hamblen, David G. (East Hampton, CT); Brouillette, Carl R. (West Hartford, CT)

1992-08-04T23:59:59.000Z

Note: This page contains sample records for the topic "icm interim corrective" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


361

Method and system for photoconductive detector signal correction  

DOE Patents [OSTI]

A corrective factor is applied so as to remove anomalous features from the signal generated by a photoconductive detector, and to thereby render the output signal highly linear with respect to the energy of incident, time-varying radiation. The corrective factor may be applied through the use of either digital electronic data processing means or analog circuitry, or through a combination of those effects. 5 figs.

Carangelo, R.M.; Hamblen, D.G.; Brouillette, C.R.

1992-08-04T23:59:59.000Z

362

Systematic quantum corrections to screening in thermonuclear fusion  

E-Print Network [OSTI]

We develop a series expansion of the plasma screening length away from the classical limit in powers of $\\hbar^{2}$. It is shown that the leading order quantum correction increases the screening length in solar conditions by approximately 2% while it decreases the fusion rate by approximately $ 0.34%$. We also calculate the next higher order quantum correction which turns out to be approximately 0.05%.

Shirish M. Chitanvis

2006-06-13T23:59:59.000Z

363

Systematic quantum corrections to screening in thermonuclear fusion  

E-Print Network [OSTI]

We develop a series expansion of the plasma screening length away from the classical limit in powers of $\\hbar^{2}$. It is shown that the leading order quantum correction increases the screening length in solar conditions by approximately 2% while it decreases the fusion rate by approximately $ 0.34%$. We also calculate the next higher order quantum correction which turns out to be approximately 0.05%.

Chitanvis, S M

2006-01-01T23:59:59.000Z

364

Corrective Action Decision Document/Corrective Action Plan for Corrective Action Unit 547: Miscellaneous Contaminated Waste Sites, Nevada National Security Site, Nevada, Revision 0  

SciTech Connect (OSTI)

The purpose of this CADD/CAP is to present the corrective action alternatives (CAAs) evaluated for CAU 547, provide justification for selection of the recommended alternative, and describe the plan for implementing the selected alternative. Corrective Action Unit 547 consists of the following three corrective action sites (CASs): (1) CAS 02-37-02, Gas Sampling Assembly; (2) CAS 03-99-19, Gas Sampling Assembly; and(3) CAS 09-99-06, Gas Sampling Assembly. The gas sampling assemblies consist of inactive process piping, equipment, and instrumentation that were left in place after completion of underground safety experiments. The purpose of these safety experiments was to confirm that a nuclear explosion would not occur in the case of an accidental detonation of the high-explosive component of the device. The gas sampling assemblies allowed for the direct sampling of the gases and particulates produced by the safety experiments. Corrective Action Site 02-37-02 is located in Area 2 of the Nevada National Security Site (NNSS) and is associated with the Mullet safety experiment conducted in emplacement borehole U2ag on October 17, 1963. Corrective Action Site 03-99-19 is located in Area 3 of the NNSS and is associated with the Tejon safety experiment conducted in emplacement borehole U3cg on May 17, 1963. Corrective Action Site 09-99-06 is located in Area 9 of the NNSS and is associated with the Player safety experiment conducted in emplacement borehole U9cc on August 27, 1964. The CAU 547 CASs were investigated in accordance with the data quality objectives (DQOs) developed by representatives of the Nevada Division of Environmental Protection (NDEP) and the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office. The DQO process was used to identify and define the type, amount, and quality of data needed to determine and implement appropriate corrective actions for CAU 547. Existing radiological survey data and historical knowledge of the CASs were sufficient to meet the DQOs and evaluate CAAs without additional investigation. As a result, further investigation of the CAU 547 CASs was not required. The following CAAs were identified for the gas sampling assemblies: (1) clean closure, (2) closure in place, (3) modified closure in place, (4) no further action (with administrative controls), and (5) no further action. Based on the CAAs evaluation, the recommended corrective action for the three CASs in CAU 547 is closure in place. This corrective action will involve construction of a soil cover on top of the gas sampling assembly components and establishment of use restrictions at each site. The closure in place alternative was selected as the best and most appropriate corrective action for the CASs at CAU 547 based on the following factors: (1) Provides long-term protection of human health and the environment; (2) Minimizes short-term risk to site workers in implementing corrective action; (3) Is easily implemented using existing technology; (4) Complies with regulatory requirements; (5) Fulfills FFACO requirements for site closure; (6) Does not generate transuranic waste requiring offsite disposal; (7) Is consistent with anticipated future land use of the areas (i.e., testing and support activities); and (8) Is consistent with other NNSS site closures where contamination was left in place.

Mark Krauss

2011-09-01T23:59:59.000Z

365

Relativistic corrections and non-Gaussianity in radio continuum surveys  

SciTech Connect (OSTI)

Forthcoming radio continuum surveys will cover large volumes of the observable Universe and will reach to high redshifts, making them potentially powerful probes of dark energy, modified gravity and non-Gaussianity. We consider the continuum surveys with LOFAR, WSRT and ASKAP, and examples of continuum surveys with the SKA. We extend recent work on these surveys by including redshift space distortions and lensing convergence in the radio source auto-correlation. In addition we compute the general relativistic (GR) corrections to the angular power spectrum. These GR corrections to the standard Newtonian analysis of the power spectrum become significant on scales near and beyond the Hubble scale at each redshift. We find that the GR corrections are at most percent-level in LOFAR, WODAN and EMU surveys, but they can produce O(10%) changes for high enough sensitivity SKA continuum surveys. The signal is however dominated by cosmic variance, and multiple-tracer techniques will be needed to overcome this problem. The GR corrections are suppressed in continuum surveys because of the integration over redshift — we expect that GR corrections will be enhanced for future SKA HI surveys in which the source redshifts will be known. We also provide predictions for the angular power spectra in the case where the primordial perturbations have local non-Gaussianity. We find that non-Gaussianity dominates over GR corrections, and rises above cosmic variance when f{sub NL}?>5 for SKA continuum surveys.

Maartens, Roy [Physics Department, University of the Western Cape, Cape Town 7535 (South Africa); Zhao, Gong-Bo; Bacon, David; Koyama, Kazuya [Institute of Cosmology and Gravitation, University of Portsmouth, Portsmouth PO1 3FX (United Kingdom); Raccanelli, Alvise, E-mail: Roy.Maartens@port.ac.uk, E-mail: Gong-bo.Zhao@port.ac.uk, E-mail: David.Bacon@port.ac.uk, E-mail: Kazuya.Koyama@port.ac.uk, E-mail: alvise@caltech.edu [Jet Propulsion Laboratory, California Institute of Technology, Pasadena CA 91109 (United States)

2013-02-01T23:59:59.000Z

366

Corrective Action Decision Document/Closure Report for Corrective Action Unit 370: T-4 Atmospheric Test Site, Nevada Test Site, Nevada, Revision 0  

SciTech Connect (OSTI)

This Corrective Action Decision Document/Closure Report has been prepared for Corrective Action Unit (CAU) 370, T-4 Atmospheric Test Site, located in Area 4 at the Nevada Test Site, Nevada, in accordance with the Federal Facility Agreement and Consent Order (FFACO). Corrective Action Unit 370 is comprised of Corrective Action Site (CAS) 04-23-01, Atmospheric Test Site T-4. The purpose of this Corrective Action Decision Document/Closure Report is to provide justification and documentation supporting the recommendation that no further corrective action is needed for CAU 370 due to the implementation of the corrective action of closure in place with administrative controls. To achieve this, corrective action investigation (CAI) activities were performed from June 25, 2008, through April 2, 2009, as set forth in the Corrective Action Investigation Plan for Corrective Action Unit 370: T-4 Atmospheric Test Site and Record of Technical Change No. 1.

Patrick Matthews

2009-05-01T23:59:59.000Z

367

Corrective Action Investigation Plan for Corrective Action Unit 190: Contaminated Waste Sites Nevada Test Site, Nevada, Rev. No.: 0  

SciTech Connect (OSTI)

Corrective Action Unit (CAU) 190 is located in Areas 11 and 14 of the Nevada Test Site, which is 65 miles northwest of Las Vegas, Nevada. Corrective Action Unit 190 is comprised of the four Corrective Action Sites (CASs) listed below: (1) 11-02-01, Underground Centrifuge; (2) 11-02-02, Drain Lines and Outfall; (3) 11-59-01, Tweezer Facility Septic System; and (4) 14-23-01, LTU-6 Test Area. These sites are being investigated because existing information is insufficient on the nature and extent of potential contamination to evaluate and recommend corrective action alternatives. Additional information will be obtained before evaluating corrective action alternatives and selecting the appropriate corrective action for each CAS by conducting a corrective action investigation (CAI). The results of the field investigation will support a defensible evaluation of viable corrective action alternatives that will be presented in the Corrective Action Decision Document. The sites will be investigated based on the data quality objectives (DQOs) developed on August 24, 2006, by representatives of the Nevada Division of Environmental Protection; U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office; Stoller-Navarro Joint Venture, and National Security Technologies, LLC. The DQO process was used to identify and define the type, amount, and quality of data needed to develop and evaluate appropriate corrective actions for CAU 190. The scope of the CAU 190 CAI includes the following activities: (1) Move surface debris and/or materials, as needed, to facilitate sampling; (2) Conduct radiological and geophysical surveys; (3) Perform field screening; (4) Collect and submit environmental samples for laboratory analysis to determine whether contaminants of concern (COCs) are present; (5) If COCs are present, collect additional step-out samples to define the lateral and vertical extent of the contamination; (6) Collect samples of source material, if present, to determine the potential for a release; (7) Collect samples of investigation-derived waste, as needed, for waste management and minimization purposes; and (8) Collect quality control samples. This Corrective Action Investigation Document (CAIP) has been developed in accordance with the Federal Facility Agreement and Consent Order (FFACO) agreed to by the State of Nevada, U.S. Department of Energy, and U.S. Department of Defense. Under the FFACO, this CAIP will be submitted to the Nevada Division of Environmental Protection for approval. Field work will be conducted following approval.

Wickline, Alfred

2006-12-01T23:59:59.000Z

368

Corrective Action Investigation Plan for Corrective Action Unit 309: Area 12 Muckpiles, Nevada Test Site, Nevada, Rev. No.: 0  

SciTech Connect (OSTI)

This Corrective Action Investigation Plan (CAIP) contains project-specific information including facility descriptions, environmental sample collection objectives, and criteria for conducting site investigation activities at Corrective Action Unit (CAU) 309, Area 12 Muckpiles, Nevada Test Site (NTS), Nevada. This CAIP has been developed in accordance with the Federal Facility Agreement and Consent Order (FFACO) (1996) that was agreed to by the State of Nevada, the U.S. Department of Energy (DOE), and the U.S. Department of Defense (DoD). Corrective Action Unit 309 is located in Area 12 of the NTS, which is approximately 65 miles (mi) northwest of Las Vegas, Nevada (Figure 1-1). Area 12 is approximately 40 mi beyond the main gate to the NTS. Corrective Action Unit 309 is comprised of the three Corrective Action Sites (CASs) shown on Figure 1-1 and listed below: CAS 12-06-09, Muckpile; CAS 12-08-02, Contaminated Waste Dump (CWD); and CAS 12-28-01, I, J, and K-Tunnel Debris. Corrective Action Sites 12-06-09 and 12-08-02 will be collectively referred to as muckpiles in this document. Corrective Action Site 12-28-01 will be referred to as the fallout plume because of the extensive lateral area of debris and fallout contamination resulting from the containment failures of the J-and K-Tunnels. The corrective action investigation (CAI) will include field inspections, radiological surveys, and media sampling, where appropriate. Data will also be obtained to support waste management decisions. The CASs in CAU 309 are being investigated because hazardous and/or radioactive constituents may be present in concentrations that could potentially pose a threat to human health and/or the environment. Existing information on the nature and extent of potential contamination at these sites are insufficient to evaluate and recommend corrective action alternatives for the CASs. Therefore, additional information will be obtained by conducting a CAI prior to evaluating corrective action alternatives and selecting the appropriate corrective action for each CAS.

David A. Strand

2004-12-01T23:59:59.000Z

369

Evaluation of Shear Strength Threshold of Concern for Retrieval of Interim-Stored K-Basin Sludge in the Hanford Site  

SciTech Connect (OSTI)

K-Basin sludge will be recovered into the Sludge Transport and Storage Containers (STSCs) and will be stored in the T Plant for interim storage (at least 10 years). Long-term sludge storage tests conducted by Pacific Northwest National Laboratory show that high uranium content K Basin sludge can self-cement and form a strong sludge with a bulk shear strength of up to 65 kPa. Some of this sludge has "paste" and "chunks" with shear strengths of approximately 3~5 kPa and 380 ~ 770 kPa, respectively. High uranium content sludge samples subjected to hydrothermal testing (e.g., 185°C, 10 h) have been observed to form agglomerates with a shear strength up to 170 kPa. After interim storage at T Plant, the sludge in the STSCs will be mobilized by water jets impinging the sludge. The objective of the evaluation was to determine the range of sludge shear strength for which there is high confidence that a water-jet retrieval system can mobilize stored K-Basin sludge from STSCs. The shear strength at which the sludge can be retrieved is defined as the "shear strength threshold of concern." If the sludge shear strength is greater than the value of the shear strength threshold of concern, a water-jet retrieval system will be unlikely to mobilize the sludge up to the container’s walls. The shear strength threshold of concern can be compared with the range of possible shear strengths of K-Basin stored sludge to determine if the current post interim-storage, water-jet retrieval method is adequate. Fourteen effective cleaning radius (ECR) models were reviewed, and their validity was examined by applying them to Hanford 241-SY-101 and 241-AZ-101 Tanks to reproduce the measured ECR produced by the mixer pumps. The validation test identified that the Powell-3 and Crowe-2 ECR models are more accurate than other ECR models reviewed. These ECR models were used to address a question as to whether the effective cleaning radius of a water jet is sufficient or if it can be readily expanded to cover the range of possible shear strengths. These results will assist CH2M HILL Plateau Remediation Company (CHPRC) to establish the technical basis of the feasibility of the sludge retrieval and storage plan and to develop an adequate water jet system to retrieve the stored K-Basin sludge in the STSCs. The STSCs are 2:1 elliptical-head vessels, 58 inches in diameter and 105 inches tall. Each STSC will contain 0.5 to 2.1 m3 of settled sludge with the specific loading dependent upon sludge type.

Onishi, Yasuo; Yokuda, Satoru T.; Schmidt, Andrew J.

2010-11-01T23:59:59.000Z

370

Corrective Action Decision Document/Closure Report for Corrective Action Unit 232: Area 25 Sewage Lagoons, Nevada Test Site, Nevada  

SciTech Connect (OSTI)

This Corrective Action Decision Document/Closure Report (CADD/CR) has been prepared for Corrective Action Unit (CAU) 232, Area 25 Sewage Lagoons, in accordance with the Federal Facility Agreement and Consent Order. Located at the Nevada Test Site in Nevada, approximately 65 miles northwest of Las Vegas, CAU 232 is comprised of Corrective Action Site 25-03-01, Sewage Lagoon. This CADD/CR identifies and rationalizes the U.S. Department of Energy, Nevada Operations Office's (DOE/NV's) recommendation that no corrective action is deemed necessary for CAU 232. The Corrective Action Decision Document and Closure Report have been combined into one report because sample data collected during the July 1999 corrective action investigation (CAI) activities disclosed no evidence of contamination at the site. Contaminants of potential concern (COPCs) addressed during the CAI included total volatile organic compounds, total semivolatile organic compounds, total Resource Conservation and Recovery Act metals, total pesticides, total herbicides, total petroleum hydrocarbons (gasoline and diesel/oil range), polychlorinated biphenyls, isotopic uranium, isotopic plutonium, strontium-90, and gamma-emitting radionuclides. The data confirmed that none of the COPCs identified exceeded preliminary action levels outlined in the CAIP; therefore, no corrective actions were necessary for CAU 232. After the CAI, best management practice activities were completed and included installation of a fence and signs to limit access to the lagoons, cementing Manhole No. 2 and the diverter box, and closing off influent and effluent ends of the sewage lagoon piping. As a result of the CAI, the DOE/NV recommended that: (1) no further actions were required; (2) no Corrective Action Plan would be required; and (3) no use restrictions were required to be placed on the CAU.

US Department of Energy Nevada Operations Office

1999-12-23T23:59:59.000Z

371

Corrective Action Decision Document for Corrective Action Unit 563: Septic Systems, Nevada Test Site, Nevada, Revision 0  

SciTech Connect (OSTI)

This Corrective Action Decision Document has been prepared for Corrective Action Unit (CAU) 563, Septic Systems, in accordance with the Federal Facility Agreement and Consent Order (FFACO, 1996; as amended January 2007). The corrective action sites (CASs) for CAU 563 are located in Areas 3 and 12 of the Nevada Test Site, Nevada, and are comprised of the following four sites: •03-04-02, Area 3 Subdock Septic Tank •03-59-05, Area 3 Subdock Cesspool •12-59-01, Drilling/Welding Shop Septic Tanks •12-60-01, Drilling/Welding Shop Outfalls The purpose of this Corrective Action Decision Document is to identify and provide the rationale for the recommendation of a corrective action alternative (CAA) for the four CASs within CAU 563. Corrective action investigation (CAI) activities were performed from July 17 through November 19, 2007, as set forth in the CAU 563 Corrective Action Investigation Plan (NNSA/NSO, 2007). Analytes detected during the CAI were evaluated against appropriate final action levels (FALs) to identify the contaminants of concern (COCs) for each CAS. The results of the CAI identified COCs at one of the four CASs in CAU 563 and required the evaluation of CAAs. Assessment of the data generated from investigation activities conducted at CAU 563 revealed the following: •CASs 03-04-02, 03-59-05, and 12-60-01 do not contain contamination at concentrations exceeding the FALs. •CAS 12-59-01 contains arsenic and chromium contamination above FALs in surface and near-surface soils surrounding a stained location within the site. Based on the evaluation of analytical data from the CAI, review of future and current operations at CAS 12-59-01, and the detailed and comparative analysis of the potential CAAs, the following corrective actions are recommended for CAU 563.

Grant Evenson

2008-02-01T23:59:59.000Z

372

Corrective Action Investigation Plan for Corrective Action Unit 555: Septic Systems Nevada Test Site, Nevada, Rev. No.: 0 with Errata  

SciTech Connect (OSTI)

This Corrective Action Investigation Plan (CAIP) contains project-specific information including facility descriptions, environmental sample collection objectives, and criteria for conducting site investigation activities at Corrective Action Unit (CAU) 555: Septic Systems, Nevada Test Site (NTS), Nevada. This CAIP has been developed in accordance with the ''Federal Facility Agreement and Consent Order'' (FFACO) (1996) that was agreed to by the State of Nevada, the U.S. Department of Energy (DOE), and the U.S. Department of Defense. Corrective Action Unit 555 is located in Areas 1, 3 and 6 of the NTS, which is approximately 65 miles (mi) northwest of Las Vegas, Nevada, and is comprised of the five corrective action sites (CASs) shown on Figure 1-1 and listed below: (1) CAS 01-59-01, Area 1 Camp Septic System; (2) CAS 03-59-03, Core Handling Building Septic System; (3) CAS 06-20-05, Birdwell Dry Well; (4) CAS 06-59-01, Birdwell Septic System; and (5) CAS 06-59-02, National Cementers Septic System. An FFACO modification was approved on December 14, 2005, to include CAS 06-20-05, Birdwell Dry Well, as part of the scope of CAU 555. The work scope was expanded in this document to include the investigation of CAS 06-20-05. The Corrective Action Investigation (CAI) will include field inspections, radiological surveys, geophysical surveys, sampling of environmental media, analysis of samples, and assessment of investigation results, where appropriate. Data will be obtained to support corrective action alternative evaluations and waste management decisions. The CASs in CAU 555 are being investigated because hazardous and/or radioactive constituents may be present in concentrations that could potentially pose a threat to human health and the environment. Existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend corrective action alternatives for the CASs. Additional information will be generated by conducting a CAI before the evaluation and selection of corrective action alternatives.

Pastor, Laura

2005-12-01T23:59:59.000Z

373

Corrective Action Plan for Corrective Action Unit 143: Area 25 Contaminated Waste Dumps, Nevada Test Site, Nevada  

SciTech Connect (OSTI)

This Corrective Action Plan (CAP) has been prepared for Corrective Action Unit (CAU) 143: Area 25 Contaminated Waste Dumps, Nevada Test Site, Nevada, in accordance with the Federal Facility Agreement and Consent Order of 1996. This CAP provides the methodology for implementing the approved corrective action alternative as listed in the Corrective Action Decision Document (U.S. Department of Energy, Nevada Operations Office, 2000). The CAU includes two Corrective Action Sites (CASs): 25-23-09, Contaminated Waste Dump Number 1; and 25-23-03, Contaminated Waste Dump Number 2. Investigation of CAU 143 was conducted in 1999. Analytes detected during the corrective action investigation were evaluated against preliminary action levels to determine constituents of concern for CAU 143. Radionuclide concentrations in disposal pit soil samples associated with the Reactor Maintenance, Assembly, and Disassembly Facility West Trenches, the Reactor Maintenance, Assembly, and Disassembly Facility East Trestle Pit, and the Engine Maintenance, Assembly, and Disassembly Facility Trench are greater than normal background concentrations. These constituents are identified as constituents of concern for their respective CASs. Closure-in-place with administrative controls involves use restrictions to minimize access and prevent unauthorized intrusive activities, earthwork to fill depressions to original grade, placing additional clean cover material over the previously filled portion of some of the trenches, and placing secondary or diversion berm around pertinent areas to divert storm water run-on potential.

D. L. Gustafason

2001-02-01T23:59:59.000Z

374

Corrective Action Investigation Plan for Corrective Action Unit 135: Area 25 Underground Storage Tanks Nevada Test Site, Nevada  

SciTech Connect (OSTI)

This Corrective Action Investigation Plan (CAIP) has been developed in accordance with the Federal Facility Agreement and Consent Order (FFACO) that was agreed to by the US Department of Energy, Nevada Operations Office (DOE/NV); the State of Nevada Division of Environmental Protection (NDEP); and the US Department of Defense (FFACO, 1996). The CAIP is a document that provides or references all of the specific information for investigation activities associated with Corrective Action Units (CAUs) or Corrective Action Sites (CASs). According to the FFACO, CASs are sites potentially requiring corrective action(s) and may include solid waste management units or individual disposal or release sites (FFACO, 1996). Corrective Action Units consist of one or more CASs grouped together based on geography, technical similarity, or agency responsibility for the purpose of determining corrective actions. This CAIP contains the environmental sample collection objectives and the criteria for conducting site investigation activities at CAU 135, Area 25 Underground Storage Tanks (USTs), which is located on the Nevada Test Site (NTS). The NTS is approximately 105 kilometers (km) (65 miles [mi]) northwest of Las Vegas, Nevada.

U.S. Department of Energy, Nevada Operations Office

1999-05-05T23:59:59.000Z

375

Corrective Action Investigation Plan for Corrective Action Unit 240: Area 25 Vehicle Washdown Nevada Test Site, Nevada  

SciTech Connect (OSTI)

This Corrective Action Investigation Plan (CAIP) has been developed in accordance with the Federal Facility Agreement and Consent Order (FFACO) that was agreed to by the US Department of Energy, Nevada Operations Office (DOE/NV); the State of Nevada Division of Environmental Protection (NDEP); and the US Department of Defense (FFACO, 1996). The CAIP is a document that provides or references all of the specific information for investigation activities associated with Corrective Action Units (CAUs) or Corrective Action Sites (CASs). According to the FFACO, CASs are sites potentially requiring corrective action(s) and may include solid waste management units or individual disposal or release sites (FFACO, 1996). Corrective Action Units consist of one or more CASs grouped together based on geography, technical similarity, or agency responsibility for the purpose of determining corrective actions. This CAIP contains the environmental sample collection objectives and the criteria for conducting site investigation activities at CAU 240, Area 25 Vehicle Washdown, which is located on the Nevada Test Site (NTS).

DOE/NV

1999-01-25T23:59:59.000Z

376

Corrective Action Investigation Plan for Corrective Action Unit 528: Polychlorinated Biphenyls Contamination, Nevada Test Site, Nevada, Rev. 0  

SciTech Connect (OSTI)

This Corrective Action Investigation Plan contains the U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office's approach to collect the data necessary to evaluate corrective action alternatives appropriate for the closure of Corrective Action Unit (CAU) 528, Polychlorinated Biphenyls Contamination (PCBs), Nevada Test Site (NTS), Nevada, under the Federal Facility Agreement and Consent Order. Located in the southwestern portion of Area 25 on the NTS in Jackass Flats (adjacent to Test Cell C [TCC]), CAU 528 consists of Corrective Action Site 25-27-03, Polychlorinated Biphenyls Surface Contamination. Test Cell C was built to support the Nuclear Rocket Development Station (operational between 1959 and 1973) activities including conducting ground tests and static firings of nuclear engine reactors. Although CAU 528 was not considered as a direct potential source of PCBs and petroleum contamination, two potential sources of contamination have nevertheless been identified from an unknown source in concentrations that could potentially pose an unacceptable risk to human health and/or the environment. This CAU's close proximity to TCC prompted Shaw to collect surface soil samples, which have indicated the presence of PCBs extending throughout the area to the north, east, south, and even to the edge of the western boundary. Based on this information, more extensive field investigation activities are being planned, the results of which are to be used to support a defensible evaluation of corrective action alternatives in the corrective action decision document.

U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office

2003-05-08T23:59:59.000Z

377

Corrective Action Decision Document for Corrective Action Unit 562: Waste Systems Nevada Test Site, Nevada, Revision 0  

SciTech Connect (OSTI)

This Corrective Action Decision Document (CADD) presents information supporting the selection of corrective action alternatives (CAAs) leading to the closure of Corrective Action Unit (CAU) 562, Waste Systems, in Areas 2, 23, and 25 of the Nevada Test Site, Nevada. This complies with the requirements of the Federal Facility Agreement and Consent Order (FFACO) that was agreed to by the State of Nevada; U.S. Department of Energy (DOE), Environmental Management; U.S. Department of Defense; and DOE, Legacy Management. Corrective Action Unit 562 comprises the following corrective action sites (CASs): • 02-26-11, Lead Shot • 02-44-02, Paint Spills and French Drain • 02-59-01, Septic System • 02-60-01, Concrete Drain • 02-60-02, French Drain • 02-60-03, Steam Cleaning Drain • 02-60-04, French Drain • 02-60-05, French Drain • 02-60-06, French Drain • 02-60-07, French Drain • 23-60-01, Mud Trap Drain and Outfall • 23-99-06, Grease Trap • 25-60-04, Building 3123 Outfalls The purpose of this CADD is to identify and provide the rationale for the recommendation of CAAs for the 13 CASs within CAU 562. Corrective action investigation (CAI) activities were performed from July 27, 2009, through May 12, 2010, as set forth in the CAU 562 Corrective Action Investigation Plan. The purpose of the CAI was to fulfill the following data needs as defined during the data quality objective (DQO) process: • Determine whether COCs are present. • If COCs are present, determine their nature and extent. • Provide sufficient information and data to complete appropriate corrective actions. A data quality assessment (DQA) performed on the CAU 562 data demonstrated the quality and acceptability of the data for use in fulfilling the DQO data needs. Analytes detected during the CAI were evaluated against appropriate final action levels (FALs) to identify the COCs for each CAS. The results of the CAI identified COCs at 10 of the 13 CASs in CAU 562, and thus corrective action is required. Assessment of the data generated from investigation activities conducted at CAU 562 is shown in Table ES-1. Based on the evaluation of analytical data from the CAI, review of future and current operations at the 13 CASs, and the detailed and comparative analysis of the potential CAAs, the following corrective actions are recommended for CAU 562. • No further action is the preferred corrective action for CASs 02-60-01, 02-60-06, and 02-60-07. • Clean closure is the preferred corrective action for CASs 02-26-11, 02-44-02, 02-59-01, 02-60-02, 02-60-03, 02-60-04, 02-60-05, 23-60-01, 23-99-06, and 25-60-04. The preferred CAAs were evaluated on technical merit focusing on performance, reliability, feasibility, safety, and cost. The alternatives were judged to meet all requirements for the technical components evaluated. The alternatives meet all applicable federal and state regulations for closure of the site and will reduce potential exposures to contaminated media to acceptable levels. The DOE, National Nuclear Security Administration Nevada Site Office provides the following recommendations: • No further corrective action is required at CASs 02-60-01, 02-60-06, and 02-60-07. • Clean closure is recommended for the remaining 10 CASs in CAU 562. • A Corrective Action Plan will be submitted to the Nevada Division of Environmental Protection that contains a detailed description of the proposed actions that will be taken to implement the selected corrective actions.

Mark Krause

2010-08-01T23:59:59.000Z

378

Prior-based artifact correction (PBAC) in computed tomography  

SciTech Connect (OSTI)

Purpose: Image quality in computed tomography (CT) often suffers from artifacts which may reduce the diagnostic value of the image. In many cases, these artifacts result from missing or corrupt regions in the projection data, e.g., in the case of metal, truncation, and limited angle artifacts. The authors propose a generalized correction method for different kinds of artifacts resulting from missing or corrupt data by making use of available prior knowledge to perform data completion. Methods: The proposed prior-based artifact correction (PBAC) method requires prior knowledge in form of a planning CT of the same patient or in form of a CT scan of a different patient showing the same body region. In both cases, the prior image is registered to the patient image using a deformable transformation. The registered prior is forward projected and data completion of the patient projections is performed using smooth sinogram inpainting. The obtained projection data are used to reconstruct the corrected image. Results: The authors investigate metal and truncation artifacts in patient data sets acquired with a clinical CT and limited angle artifacts in an anthropomorphic head phantom data set acquired with a gantry-based flat detector CT device. In all cases, the corrected images obtained by PBAC are nearly artifact-free. Compared to conventional correction methods, PBAC achieves better artifact suppression while preserving the patient-specific anatomy at the same time. Further, the authors show that prominent anatomical details in the prior image seem to have only minor impact on the correction result. Conclusions: The results show that PBAC has the potential to effectively correct for metal, truncation, and limited angle artifacts if adequate prior data are available. Since the proposed method makes use of a generalized algorithm, PBAC may also be applicable to other artifacts resulting from missing or corrupt data.

Heußer, Thorsten, E-mail: thorsten.heusser@dkfz-heidelberg.de; Brehm, Marcus [Medical Physics in Radiology, German Cancer Research Center (DKFZ), Im Neuenheimer Feld 280, 69120 Heidelberg (Germany)] [Medical Physics in Radiology, German Cancer Research Center (DKFZ), Im Neuenheimer Feld 280, 69120 Heidelberg (Germany); Ritschl, Ludwig [Ziehm Imaging GmbH, Donaustraße 31, 90451 Nürnberg (Germany)] [Ziehm Imaging GmbH, Donaustraße 31, 90451 Nürnberg (Germany); Sawall, Stefan; Kachelrieß, Marc [Medical Physics in Radiology, German Cancer Research Center (DKFZ), Im Neuenheimer Feld 280, 69120 Heidelberg, Germany and Institute of Medical Physics, Friedrich–Alexander–University (FAU) of Erlangen–Nürnberg, Henkestraße 91, 91052 Erlangen (Germany)] [Medical Physics in Radiology, German Cancer Research Center (DKFZ), Im Neuenheimer Feld 280, 69120 Heidelberg, Germany and Institute of Medical Physics, Friedrich–Alexander–University (FAU) of Erlangen–Nürnberg, Henkestraße 91, 91052 Erlangen (Germany)

2014-02-15T23:59:59.000Z

379

Threshold Corrections to the Bottom Quark Mass Revisited  

E-Print Network [OSTI]

Threshold corrections to the bottom quark mass are often estimated under the approximation that tan$\\beta$ enhanced contributions are the most dominant. In this work we revisit this common approximation made to the estimation of the supersymmetric threshold corrections to the bottom quark mass. We calculate the full one-loop supersymmetric corrections to the bottom quark mass and survey a large part of the phenomenological MSSM parameter space to study the validity of considering only the tan$\\beta$ enhanced corrections. Our analysis demonstrates that this approximation underestimates the size of the threshold corrections by $\\sim$12.5% for most of the considered parameter space. We discuss the consequences for fitting the bottom quark mass and for the effective couplings to Higgses. We find that it is important to consider the additional contributions when fitting the bottom quark mass but the modifications to the effective Higgs couplings are typically $\\mathcal{O}$(few)% for the majority of the parameter space considered.

Archana Anandakrishnan; B. Charles Bryant; Stuart Raby

2015-01-29T23:59:59.000Z

380

Corrective measures evaluation report for technical area-v groundwater.  

SciTech Connect (OSTI)

This Corrective Measures Evaluation Report was prepared as directed by the Compliance Order on Consent issued by the New Mexico Environment Department to document the process of selecting the preferred remedial alternative for contaminated groundwater at Technical Area V. Supporting information includes background information about the site conditions and potential receptors and an overview of work performed during the Corrective Measures Evaluation. Evaluation of remedial alternatives included identification and description of four remedial alternatives, an overview of the evaluation criteria and approach, qualitative and quantitative evaluation of remedial alternatives, and selection of the preferred remedial alternative. As a result of the Corrective Measures Evaluation, it was determined that monitored natural attenuation of all contaminants of concern (trichloroethene, tetrachloroethene, and nitrate) was the preferred remedial alternative for implementation as the corrective measure to remediate contaminated groundwater at Technical Area V of Sandia National Laboratories/New Mexico. Finally, design criteria to meet cleanup goals and objectives and the corrective measures implementation schedule for the preferred remedial alternative are presented.

Witt, Johnathan L (North Wind, Inc., Idaho Falls, ID); Orr, Brennon R. (North Wind, Inc., Idaho Falls, ID); Dettmers, Dana L. (North Wind, Inc., Idaho Falls, ID); Hall, Kevin A. (North Wind, Inc., Idaho Falls, ID); Howard, Hope (North Wind, Inc., Idaho Falls, ID)

2005-07-01T23:59:59.000Z

Note: This page contains sample records for the topic "icm interim corrective" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


381

The role of research evidence in school improvement : a case study of corrective action schools  

E-Print Network [OSTI]

knowledge, and innovation through the social networks inand innovation diffused throughout corrective action schools through socialand innovation diffused throughout corrective action schools through social

Salas, Minerva

2011-01-01T23:59:59.000Z

382

Correction of Magnetization Sextupole and Decapole in a 5 Centimeter Bore SSC Dipole Using Passive Superconductor  

E-Print Network [OSTI]

The Idea of Passive Superconductor Correction," presented aton the Fermilab Passive Superconductor Test," ICFA Workshop,methods of passive superconductor correction will reduce

Green, M.A.

2011-01-01T23:59:59.000Z

383

Etalon-induced Baseline Drift And Correction In Atom Flux Sensors...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Etalon-induced Baseline Drift And Correction In Atom Flux Sensors Based On Atomic Absorption Spectroscopy. Etalon-induced Baseline Drift And Correction In Atom Flux Sensors Based...

384

E-Print Network 3.0 - aberration corrected x-ray Sample Search...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Summary: ., "Enhancement of x-ray lasing due to wavefront correction of line-focusing optics with a large aperture... induced wave aberrations Vision correction using optical...

385

E-Print Network 3.0 - aberration correction algorithms Sample...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

correction algorithms Page: << < 1 2 3 4 5 > >> 1 Wavefront sensorless adaptive optics for large aberrations Summary: correction of N aberration modes is demonstrated with a...

386

A Computational Light Field Display for Correcting Visual Aberrations Fu-Chung Huang  

E-Print Network [OSTI]

. Correcting optical aberrations is traditionally done optically using eyeglasses, contact lenses, higher order aberrations are not correctable with eyeglasses. In this work, we introduce a new

O'Brien, James F.

387

Corrective Action Investigation Plan for Corrective Action Unit 556: Dry Wells and Surface Release Points Nevada Test Site, Nevada (Draft), Revision 0  

SciTech Connect (OSTI)

Corrective Action Unit  (CAU) 556, Dry Wells and Surface Release Points, is located in Areas 6 and 25 of the Nevada Test Site, 65 miles northwest of Las Vegas, Nevada. Corrective Action Unit 556 is comprised of four corrective action sites (CASs) listed below: •06-20-04, National Cementers Dry Well •06-99-09, Birdwell Test Hole •25-60-03, E-MAD Stormwater Discharge and Piping •25-64-01, Vehicle Washdown and Drainage Pit These sites are being investigated because existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend corrective action alternatives. Additional information will be obtained by conducting a corrective action investigation before evaluating corrective action alternatives and selecting the appropriate corrective action for each CAS. The results of the field investigation will support a defensible evaluation of viable corrective action alternatives that will be presented in the Corrective Action Decision Document.

Grant Evenson

2007-02-01T23:59:59.000Z

388

On Corrections to the Born-Oppenheimer Approximation  

E-Print Network [OSTI]

This report presents a new approach for treating the coupling of electrons and nuclei in quantum mechanical calculations for molecules and condensed matter. It includes the standard "Born-Oppenheimer approximation" as a special case but treats both adiabatic and non-adiabatic corrections using perturbation theory. The adiabatic corrections include all terms that do not explicitly involve the nuclear wavefunctions, so that the nuclei move on a single electronic potential surface. The non-adiabatic corrections, which allow the nuclei to move on more than one potential surface, include coupling between the electronic and nuclear wavefunctions. The method is related to an approach first proposed by Born and Huang, but it differs in the methodology and in the definition of the electronic wavefunctions and potential surfaces. A simple example is worked out to illustrate the mechanics of the technique. The report also includes a review of previous work.

Gerald I. Kerley

2013-06-24T23:59:59.000Z

389

Coordinated joint motion control system with position error correction  

DOE Patents [OSTI]

Disclosed are an articulated hydraulic machine supporting, control system and control method for same. The articulated hydraulic machine has an end effector for performing useful work. The control system is capable of controlling the end effector for automated movement along a preselected trajectory. The control system has a position error correction system to correct discrepancies between an actual end effector trajectory and a desired end effector trajectory. The correction system can employ one or more absolute position signals provided by one or more acceleration sensors supported by one or more movable machine elements. Good trajectory positioning and repeatability can be obtained. A two-joystick controller system is enabled, which can in some cases facilitate the operator's task and enhance their work quality and productivity.

Danko, George (Reno, NV)

2011-11-22T23:59:59.000Z

390

Interacting entropy-corrected holographic Chaplygin gas model  

E-Print Network [OSTI]

Holographic dark energy (HDE), presents a dynamical view of dark energy which is consistent with the observational data and has a solid theoretical background. Its definition follows from the entropy-area relation $S(A)$, where $S$ and $A$ are entropy and area respectively. In the framework of loop quantum gravity, a modified definition of HDE called "entropy-corrected holographic dark energy" (ECHDE) has been proposed recently to explain dark energy with the help of quantum corrections to the entropy-area relation. Using this new definition, we establish a correspondence between modified variable Chaplygin gas, new modified Chaplygin gas and the viscous generalized Chaplygin gas with the entropy corrected holographic dark energy and reconstruct the corresponding scalar potentials which describe the dynamics of the scalar field.

M. Umar Farooq; Muneer A. Rashid; Mubasher Jamil

2010-03-17T23:59:59.000Z

391

Nucleus-nucleus potential with shell-correction contribution  

E-Print Network [OSTI]

The full relaxed-density potential between spherical nuclei is considered as a sum of the macroscopic and shell-correction contributions. The macroscopic part of the potential is related to a nucleus-nucleus potential obtained in the framework of the extended Thomas-Fermi approach with the Skyrme and Coulomb forces and the relaxed-density ansatz for evaluation of proton and neutron densities of interacting nuclei. A simple prescription for the shell-correction part of the total potential is discussed. The parameters of the shell-correction and macroscopic parts of the relaxed-density potential are found by fitting the empirical barrier heights of the 89 nucleus-nucleus systems as well as macroscopic potentials evaluated for 1485 nucleus-nucleus systems at 12 distances around touching points.

V. Yu. Denisov

2015-02-04T23:59:59.000Z

392

Interim Report: 100-NR-2 Apatite Treatability Test: Low Concentration Calcium Citrate-Phosphate Solution Injection for In Situ Strontium-90 Immobilization  

SciTech Connect (OSTI)

Following an evaluation of potential Sr-90 treatment technologies and their applicability under 100-NR-2 hydrogeologic conditions, U.S. Department of Energy, Fluor Hanford, Inc., Pacific Northwest National Laboratory, and the Washington Department of Ecology agreed that the long-term strategy for groundwater remediation at 100-N Area will include apatite sequestration as the primary treatment, followed by a secondary treatment if necessary (most likely phytoremediation). Since then, the agencies have worked together to agree on which apatite sequestration technology has the greatest chance of reducing Sr-90 flux to the river at a reasonable cost. In July 2005, aqueous injection, (i.e., the introduction of apatite-forming chemicals into the subsurface) was endorsed as the interim remedy and selected for field testing. Studies are in progress to assess the efficacy of in situ apatite formation by aqueous solution injection to address both the vadose zone and the shallow aquifer along the 300 ft of shoreline where Sr-90 concentrations are highest. This report describes the field testing of the shallow aquifer treatment.

Williams, Mark D.; Fritz, Brad G.; Mendoza, Donaldo P.; Rockhold, Mark L.; Thorne, Paul D.; Xie, YuLong; Bjornstad, Bruce N.; Mackley, Rob D.; Newcomer, Darrell R.; Szecsody, James E.; Vermeul, Vincent R.

2008-07-11T23:59:59.000Z

393

Engineering evaluation/cost analysis-environmental assessment for the proposed decontamination of properties in the vicinity of the Hazelwood Interim Storage Site, Hazelwood, Missouri. Revision 1  

SciTech Connect (OSTI)

The US Department of Energy (DOE), under its Formerly Utilized Sites Remedial Action Program (FUSRAP), is implementing a cleanup program for three groups of properties in the St. Louis, Missouri, area. None of the properties is owned by DOE, but each property contains radioactive residues from federal uranium-processing activities conducted at the SLDS during and after World War II. This engineering evaluation/cost analysis (EE/CA) report has been prepared to support the interim cleanup measures for the contaminated properties in the Hazelwood and Berkeley, Missouri area. The near-term cleanup measures that may be necessary at the vicinity properties are evaluated in the main body of this report. Because of the range of active land uses in the Hazelwood and Berkeley areas and because of the extent of contamination on public and private properties, the potential exists for disturbance and spreading of soil contamination. Specifically, implementation of the proposed action would allow DOE to remove, transport, and safely store contaminated soils from properties where other activities (not involving DOE) are likely to result in either spreading contamination or otherwise complicating ultimate cleanup measures.

Picel, M.H.; Peterson, J.M. [Argonne National Lab., IL (United States). Environmental Assessment and Information Sciences Div.; Williams, M.J. [Bechtel National, Inc., Oak Ridge, TN (United States)

1992-03-01T23:59:59.000Z

394

Engineering evaluation/cost analysis for the proposed decontamination of properties in the vicinity of the Hazelwood Interim Storage Site, Hazelwood, Missouri -- environment assessment  

SciTech Connect (OSTI)

The US Department of Energy (DOE), under its Formerly Utilized Sites Remedial Action Program (FUSRAP), is implementing a cleanup program for three groups of properties in the St. Louis, Missouri, area. None of the properties is owned by DOE, but each property contains radioactive residues from federal uranium-processing activities conducted at the SLDS during and after World War II. This engineering evaluation/cost analysis (EE/CA) report has been prepared to support the interim cleanup measures for the contaminated properties in the Hazelwood and Berkeley, Missouri area. The near-term cleanup measures that may be necessary at the vicinity properties are evaluated in the main body of this report. Because of the range of active land uses in the Hazelwood and Berkeley areas and because of the extent of contamination on public and private properties, the potential exists for disturbance and spreading of soil contamination. Specifically, implementation of the proposed action would allow DOE to remove, transport, and safely store contaminated soils from properties where other activities (not involving DOE) are likely to result in either spreading contamination or otherwise complicating ultimate cleanup measures. 25 refs., 4 figs., 6 tabs.

Picel, M.H.; Peterson, J.M. (Argonne National Lab., IL (USA). Environmental Assessment and Information Sciences Div.); Williams, M.J. (Bechtel National, Inc., Oak Ridge, TN (USA))

1991-05-01T23:59:59.000Z

395

Engineering evaluation/cost analysis-environmental assessment for the proposed decontamination of properties in the vicinity of the Hazelwood Interim Storage Site, Hazelwood, Missouri  

SciTech Connect (OSTI)

The US Department of Energy (DOE), under its Formerly Utilized Sites Remedial Action Program (FUSRAP), is implementing a cleanup program for three groups of properties in the St. Louis, Missouri, area. None of the properties is owned by DOE, but each property contains radioactive residues from federal uranium-processing activities conducted at the SLDS during and after World War II. This engineering evaluation/cost analysis (EE/CA) report has been prepared to support the interim cleanup measures for the contaminated properties in the Hazelwood and Berkeley, Missouri area. The near-term cleanup measures that may be necessary at the vicinity properties are evaluated in the main body of this report. Because of the range of active land uses in the Hazelwood and Berkeley areas and because of the extent of contamination on public and private properties, the potential exists for disturbance and spreading of soil contamination. Specifically, implementation of the proposed action would allow DOE to remove, transport, and safely store contaminated soils from properties where other activities (not involving DOE) are likely to result in either spreading contamination or otherwise complicating ultimate cleanup measures.

Picel, M.H.; Peterson, J.M. (Argonne National Lab., IL (United States). Environmental Assessment and Information Sciences Div.); Williams, M.J. (Bechtel National, Inc., Oak Ridge, TN (United States))

1992-03-01T23:59:59.000Z

396

Maywood Interim Storage Site environmental report for calendar year 1992, 100 West Hunter Avenue, Maywood, New Jersey. Formerly Utilized Sites Remedial Action Program (FUSRAP)  

SciTech Connect (OSTI)

This report describes the environmental surveillance program at the Maywood Interim Storage Site (MISS) and provides the results for 1992. Environmental monitoring of MISS began in 1984, when the site was assigned to DOE by Congress through the Energy and Water Development Appropriations Act and was placed under DOE`s Formerly Utilized Sites Remedial Action Program (FUSRAP). FUSRAP was established to identify and decontaminate or otherwise control sites where residual radioactive materials remain from the early years of the nation`s atomic energy program or from commercial operations causing conditions that Congress has authorized DOE to remedy. MISS is part of a National Priorities List (NPL) site. The environmental surveillance program at MISS includes sampling networks for radon and thoron in air; external gamma radiation exposure; and radium-226, radium-228, thorium-232, and total uranium in surface water, sediment, and groundwater. Additionally, chemical analysis includes metals and organic compounds in surface water and groundwater and metals in sediments. This program assists in fulfilling the DOE objective of measuring and monitoring effluents from DOE activities and calculating hypothetical doses to members of the general public. Monitoring results are compared with applicable Environmental Protection Agency (EPA) and state standards, DOE derived concentration guides (DCGs), dose limits, and other DOE requirements. Environmental standards are established to protect public health and the environment. The radiological data for all media sampled support the conclusion that doses to the public are not distinguishable from natural background radiation.

Not Available

1993-05-01T23:59:59.000Z

397

Colonie Interim Storage Site environmental report for calendar year 1992, 1130 Central Avenue, Colonie, New York. Formerly Utilized Sites Remedial Action Program (FUSRAP)  

SciTech Connect (OSTI)

This report describes the environmental surveillance program at the Colonie Interim Storage Site (CISS) and provides the results for 1992. The site is located in eastern New York State, approximately 6.4 km (4.0 mi) northwest of downtown Albany. From 1958 to 1984, National Lead (NL) Industries used the facility to manufacture various components from depleted and enriched uranium natural thorium. Environmental monitoring of CISS began in 1984 when Congress added, the site to the US Department of Energy`s (DOE) Formerly Utilized Sites Remedial Action Program (FUSRAP). FUSRAP is a program established to identify and decontaminate or otherwise control sites where residual radioactive materials remain from the early years of the nation`s atomic energy program or from commercial operations causing conditions that Congress has authorized DOE to remedy. The environmental surveillance program at CISS includes sampling networks for external gamma radiation exposure and for thorium-232 and total uranium concentrations in surface water, sediment, and groundwater. Several chemical parameters are also measured in groundwater, including total metals, volatile organics, and water quality parameters. This surveillance program assists in fulfilling the DOE policy of measuring and monitoring effluents from DOE activities and calculating hypothetical doses. Results are compared with applicable Environmental Protection Agency (EPA) and New York State Department of Environmental Conservation (NYSDEC) standards, DOE derived concentration guides (DCGs), dose limits, and other DOE requirements.

Not Available

1993-05-01T23:59:59.000Z

398

Wayne Interim Storage Site environmental report for calendar year 1992, 868 Black Oak Ridge Road, Wayne, New Jersey. Formerly Utilized Sites Remedial Action Program (FUSRAP)  

SciTech Connect (OSTI)

This report describes the environmental surveillance program at the Wayne Interim Storage Site (WISS) and provides the results for 1992. The fenced, site, 32 km (20 mi) northwest of Newark, New Jersey, was used between 1948 and 1971 for commercial processing of monazite sand to separate natural radioisotopes - predominantly thorium. Environmental surveillance of WISS began in 1984 in accordance with Department of Energy (DOE) Order 5400.1 when Congress added the site to DOE`s Formerly Utilized Sites Remedial Action Program (FUSRAP). The environmental surveillance program at WISS includes sampling networks for radon and thoron in air; external gamma radiation exposure; radium-226, radium-228, thorium-230, thorium-232, total uranium, and several chemicals in surface water and sediment; and total uranium, radium-226, radium-228, thorium-230, thorium-232, and organic and inorganic chemicals in groundwater. Monitoring results are compared with applicable Environmental Protection Agency (EPA) and state standards, DOE derived concentration guides (DCGs), dose limits, and other DOE requirements. This monitoring program assists in fulfilling the DOE policy of measuring and monitoring effluents from DOE activities and calculating hypothetical doses. Results for environmental surveillance in 1992 show that the concentrations of all radioactive and most chemical contaminants were below applicable standards.

Not Available

1993-05-01T23:59:59.000Z

399

Colonie Interim Storage Site: Annual site environmental report, Colonie, New York, Calendar year 1986: Formerly Utilized Sites Remedial Action Program (FUSRAP)  

SciTech Connect (OSTI)

During 1986, the environmental monitoring program continued at the Colonie Interim Storage Site (CISS), a US Department of Energy (DOE) facility located in Colonie, New York. The CISS is part of the Formerly Utilized Sites Remedial Action Program (FUSRAP), a DOE program to decontaminate or otherwise control sites where residual radioactive materials remain from the early years of the nation's atomic energy program or from commercial operations causing conditions that Congress has mandated DOE to remedy. As part of the decontamination research and development project authorized by Congress under the 1984 Energy and Water Appropriations Act, remedial action is being conducted at the site and at vicinity properties by Bechtel National Inc. (BNI), Project Management Contractor for FUSRAP. The environmental monitoring program is also carried out by BNI. The monitoring program at the CISS measures external gamma radiation levels as well as uranium and radium-226 concentrations in surface water, groundwater, and sediment. To verify that the site is in compliance with the DOE radiation protection standard and to assess the potential effect of the site on public health, the radiation dose was calculated for the maximally exposed individual. Based on the conservative scenario described in the report, the maximally exposed individual would receive an annual external exposure approximately equivalent to 5% of the DOE radiation protection standard of 100 mrem/y. Results of 1986 monitoring show that the CISS is in compliance with the DOE radiation protection standard. 14 refs., 9 figs., 9 tabs.

Not Available

1987-06-01T23:59:59.000Z

400

Corrective Action Decision Document/Corrective Action Plan for Corrective Action Unit 104: Area 7 Yucca Flat Atmospheric Test Sites Nevada National Security Site, Nevada, Revision 0  

SciTech Connect (OSTI)

CAU 104 comprises the following corrective action sites (CASs): • 07-23-03, Atmospheric Test Site T-7C • 07-23-04, Atmospheric Test Site T7-1 • 07-23-05, Atmospheric Test Site • 07-23-06, Atmospheric Test Site T7-5a • 07-23-07, Atmospheric Test Site - Dog (T-S) • 07-23-08, Atmospheric Test Site - Baker (T-S) • 07-23-09, Atmospheric Test Site - Charlie (T-S) • 07-23-10, Atmospheric Test Site - Dixie • 07-23-11, Atmospheric Test Site - Dixie • 07-23-12, Atmospheric Test Site - Charlie (Bus) • 07-23-13, Atmospheric Test Site - Baker (Buster) • 07-23-14, Atmospheric Test Site - Ruth • 07-23-15, Atmospheric Test Site T7-4 • 07-23-16, Atmospheric Test Site B7-b • 07-23-17, Atmospheric Test Site - Climax These 15 CASs include releases from 30 atmospheric tests conducted in the approximately 1 square mile of CAU 104. Because releases associated with the CASs included in this CAU overlap and are not separate and distinguishable, these CASs are addressed jointly at the CAU level. The purpose of this CADD/CAP is to evaluate potential corrective action alternatives (CAAs), provide the rationale for the selection of recommended CAAs, and provide the plan for implementation of the recommended CAA for CAU 104. Corrective action investigation (CAI) activities were performed from October 4, 2011, through May 3, 2012, as set forth in the CAU 104 Corrective Action Investigation Plan.

Patrick Matthews

2012-10-01T23:59:59.000Z

Note: This page contains sample records for the topic "icm interim corrective" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


401

Corrective Action Investigation Plan for Corrective Action Unit 565: Stored Samples, Nevada Test Site, Nevada, Rev. No.: 0  

SciTech Connect (OSTI)

Corrective Action Unit (CAU) 565 is located in Area 26 of the Nevada Test Site, which is 65 miles northwest of Las Vegas, Nevada. Corrective Action Unit 565 is comprised of one corrective action site (CAS) listed--CAS 26-99-04, Ground Zero Soil Samples. This site is being investigated because existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend closure of CAU 565. Additional information will be obtained by conducting a corrective action investigation before evaluating closure objectives and selecting the appropriate corrective action. The results of the field investigation will support closure and waste management decisions that will be presented in the Corrective Action Decision Document/Closure Report. The site will be investigated based on the data quality objectives (DQOs) developed on June 1, 2006, by representatives of the Nevada Division of Environmental Protection; U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office; Stoller-Navarro Joint Venture; and Bechtel Nevada. The DQO process was utilized to identify and define the type, amount, and quality of data needed to develop and evaluate closure for CAU 565. Appendix A provides a detailed discussion of the DQO methodology and the DQOs specific to this CAS. The scope of the corrective action investigation for CAU 565 includes the following activities: (1) Remove stored samples, shelves, and debris from the interior of Building 26-2106. (2) Perform field screening on stored samples, shelves, and debris. (3) Dispose of stored samples, shelves, and debris. (4) Collect samples of investigation-derived waste, as needed, for waste management purposes. (5) Conduct radiological surveys of Building 26-2106 in accordance with the requirements in the ''NV/YMP Radiological Control Manual'' to determine if there is residual radiological contamination that would prevent the release of the building for unrestricted use. This Corrective Action Investigation has been developed in accordance with the ''Federal Facility Agreement and Consent Order'' that was agreed to by the State of Nevada, the U.S. Department of Energy, and the U.S. Department of Defense. Under the ''Federal Facility Agreement and Consent Order'', this Corrective Action Investigation Plan will be submitted to the Nevada Division of Environmental Protection for approval. Field work will be conducted following approval of the plan.

Wickline, Alfred; McCall, Robert

2006-08-01T23:59:59.000Z

402

Corrective Action Decision Document/Closure Report for Corrective Action Unit 105: Area 2 Yucca Flat Atmospheric Test Sites, Nevada National Security Site, Nevada, Revision 1  

SciTech Connect (OSTI)

The purpose of this Corrective Action Decision Document/Closure Report is to provide justification and documentation supporting the recommendation that no further corrective action is needed for CAU 105 based on the implementation of the corrective actions. Corrective action investigation (CAI) activities were performed from October 22, 2012, through May 23, 2013, as set forth in the Corrective Action Investigation Plan for Corrective Action Unit 105: Area 2 Yucca Flat Atmospheric Test Sites; and in accordance with the Soils Activity Quality Assurance Plan, which establishes requirements, technical planning, and general quality practices.

Matthews, Patrick

2014-01-01T23:59:59.000Z

403

Corrective Action Decision Document/Closure Report for Corrective Action Unit 383: Area E-Tunnel Sites, Nevada Test Site  

SciTech Connect (OSTI)

This Corrective Action Decision Document/Closure Report (CADD/CR) was prepared by the Defense Threat Reduction Agency (DTRA) for Corrective Action Unit (CAU) 383, Area 12 E-Tunnel Sites, which is the joint responsibility of DTRA and the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office (NNSA/NSO). This CADD/CR is consistent with the requirements of the Federal Facility Agreement and Consent Order (FFACO) agreed to by the State of Nevada, the DOE, and the U.S. Department of Defense. Corrective Action Unit 383 is comprised of three Corrective Action Sites (CASs) and two adjacent areas: • CAS 12-06-06, Muckpile • CAS 12-25-02, Oil Spill • CAS 12-28-02, Radioactive Material • Drainage below the Muckpile • Ponds 1, 2, and 3 The purpose of this CADD/CR is to provide justification and documentation to support the recommendation for closure with no further corrective action, by placing use restrictions at the three CASs and two adjacent areas of CAU 383.

NSTec Environmental Restoration

2010-03-15T23:59:59.000Z

404

Thermodynamically constrained correction to ab initio equations of state  

SciTech Connect (OSTI)

We show how equations of state generated by density functional theory methods can be augmented to match experimental data without distorting the correct behavior in the high- and low-density limits. The technique is thermodynamically consistent and relies on knowledge of the density and bulk modulus at a reference state and an estimation of the critical density of the liquid phase. We apply the method to four materials representing different classes of solids: carbon, molybdenum, lithium, and lithium fluoride. It is demonstrated that the corrected equations of state for both the liquid and solid phases show a significantly reduced dependence of the exchange-correlation functional used.

French, Martin; Mattsson, Thomas R. [HEDP Theory, Sandia National Laboratories, Albuquerque, New Mexico 87185-1189 (United States)

2014-07-07T23:59:59.000Z

405

An energy spread correction for ERDA hydrogen depth profiling  

SciTech Connect (OSTI)

A technique for hydrogen depth profiling by reflection elastic recoil detection analysis called the channel-depth conversion was introduced by Verda, et al.' However, the energy spread in elastic recoil detection analysis spectra, which causes a broadening in the energy range and leads to errors in depth profiling, was not addressed by this technique. Here we introduce a technique to addresses this problem, called the energy spread correction. Together, the energy spread correction and the channel-depth conversion techniques comprise the depth profiling method presented in this work.

Verda, R. D. (Raymond D.); Nastasi, Michael Anthony,

2002-01-01T23:59:59.000Z

406

Correction-to-scaling exponent for two-dimensional percolation  

SciTech Connect (OSTI)

We show that the correction-to-scaling exponents in two-dimensional percolation are bounded by {Omega}{<=}72/91, {omega}=D{Omega}{<=}3/2, and {Delta}{sub 1}={nu}{omega}{<=}2, based upon Cardy's result for the crossing probability on an annulus. The upper bounds are consistent with many previous measurements of site percolation on square and triangular lattices and new measurements for bond percolation, suggesting that they are exact. They also agree with exponents for hulls proposed recently by Aharony and Asikainen, based upon results of den Nijs. A corrections scaling form evidently applicable to site percolation is also found.

Ziff, Robert M. [Center for the Study of Complex Systems and Department of Chemical Engineering, University of Michigan, Ann Arbor, Michigan 48109 (United States)

2011-02-15T23:59:59.000Z

407

Radiative corrections in fermion bags bound by Higgs boson exchange  

E-Print Network [OSTI]

Radiative corrections for several heavy fermions bound together via the Higgs boson exchange are studied. The fermion bags considered include 12, or fewer, fermions occupying the lowest S_{1/2} shell. It is shown that for `moderately heavy' fermions with masses 0.4< m c^2< 1 TeV the radiative corrections are small, 10^{-2}, and have an attractive nature. Therefore they do not put existence of the fermion bag in doubt. This proves that these fermion bags can exist in nature.

M. Yu. Kuchiev; V. V. Flambaum

2011-01-16T23:59:59.000Z

408

Universal Framework for Quantum Error-Correcting Codes  

E-Print Network [OSTI]

We present a universal framework for quantum error-correcting codes, i.e., the one that applies for the most general quantum error-correcting codes. This framework is established on the group algebra, an algebraic notation for the nice error bases of quantum systems. The nicest thing about this framework is that we can characterize the properties of quantum codes by the properties of the group algebra. We show how it characterizes the properties of quantum codes as well as generates some new results about quantum codes.

Zhuo Li; Li-Juan Xing

2009-01-04T23:59:59.000Z

409

Quantum error correcting codes and 4-dimensional arithmetic hyperbolic manifolds  

SciTech Connect (OSTI)

Using 4-dimensional arithmetic hyperbolic manifolds, we construct some new homological quantum error correcting codes. They are low density parity check codes with linear rate and distance n{sup ?}. Their rate is evaluated via Euler characteristic arguments and their distance using Z{sub 2}-systolic geometry. This construction answers a question of Zémor [“On Cayley graphs, surface codes, and the limits of homological coding for quantum error correction,” in Proceedings of Second International Workshop on Coding and Cryptology (IWCC), Lecture Notes in Computer Science Vol. 5557 (2009), pp. 259–273], who asked whether homological codes with such parameters could exist at all.

Guth, Larry, E-mail: lguth@math.mit.edu [Department of Mathematics, MIT, Cambridge, Massachusetts 02139 (United States); Lubotzky, Alexander, E-mail: alex.lubotzky@mail.huji.ac.il [Institute of Mathematics, Hebrew University, Jerusalem 91904 (Israel)

2014-08-15T23:59:59.000Z

410

Corrective Action Investigation Plan for Corrective Action Unit 542: Disposal Holes, Nevada Test Site, Nevada, Rev. No.: 0  

SciTech Connect (OSTI)

Corrective Action Unit (CAU) 542 is located in Areas 3, 8, 9, and 20 of the Nevada Test Site, which is 65 miles northwest of Las Vegas, Nevada. Corrective Action Unit 542 is comprised of eight corrective action sites (CASs): (1) 03-20-07, ''UD-3a Disposal Hole''; (2) 03-20-09, ''UD-3b Disposal Hole''; (3) 03-20-10, ''UD-3c Disposal Hole''; (4) 03-20-11, ''UD-3d Disposal Hole''; (5) 06-20-03, ''UD-6 and UD-6s Disposal Holes''; (6) 08-20-01, ''U-8d PS No.1A Injection Well Surface Release''; (7) 09-20-03, ''U-9itsy30 PS No.1A Injection Well Surface Release''; and (8) 20-20-02, ''U-20av PS No.1A Injection Well Surface Release''. These sites are being investigated because existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend corrective action alternatives. Additional information will be obtained by conducting a corrective action investigation before evaluating corrective action alternatives and selecting the appropriate corrective action for each CAS. The results of the field investigation will support a defensible evaluation of viable corrective action alternatives that will be presented in the Corrective Action Decision Document. The sites will be investigated based on the data quality objectives (DQOs) developed on January 30, 2006, by representatives of the Nevada Division of Environmental Protection; U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office; Stoller-Navarro Joint Venture; and Bechtel Nevada. The DQO process was used to identify and define the type, amount, and quality of data needed to develop and evaluate appropriate corrective actions for CAU 542. Appendix A provides a detailed discussion of the DQO methodology and the DQOs specific to each CAS. The scope of the CAI for CAU 542 includes the following activities: (1) Move surface debris and/or materials, as needed, to facilitate sampling. (2) Conduct radiological surveys. (3) Conduct geophysical surveys to locate previously unidentified features at CASs 03-20-07, 03-20-09, 03-20-10, 03-20-11, and 06-20-03. (4) Perform field screening. (5) Collect and submit environmental samples for laboratory analysis to determine whether contaminants of concern (COCs) are present. (6) Collect quality control samples for laboratory analyses to evaluate the performance of measurement systems and controls based on the requirements of the data quality indicators. (7) If COCs are present at the surface/near surface (< 15 feet below ground surface), collect additional step-out samples to define the extent of the contamination. (8) If COCs are present in the subsurface (i.e., base of disposal hole), collect additional samples to define the vertical extent of contamination. A conservative use restriction will be used to encompass the lateral extent of subsurface contamination. (9) Stake or flag sample locations in the field, and record coordinates through global positioning systems surveying. (10) Collect samples of investigation-derived waste, as needed, for waste management and minimization purposes. This Corrective Action Investigation Plan has been developed in accordance with the ''Federal Facility Agreement and Consent Order'' that was agreed to by the State of Nevada, the U.S. Department of Energy, and the U.S. Department of Defense. Under the ''Federal Facility Agreement and Consent Order'', this Corrective Action Investigation Plan will be submitted to the Nevada Division of Environmental Protection for approval. Field work will be conducted following approval of the plan.

Laura Pastor

2006-05-01T23:59:59.000Z

411

Corrective Action Investigation Plan for Corrective Action Unit 543: Liquid Disposal Units, Nevada Test Site, Nevada: Revision 0  

SciTech Connect (OSTI)

The general purpose of this Corrective Action Investigation Plan is to ensure that adequate data are collected to provide sufficient and reliable information to identify, evaluate, and select technically viable corrective action alternatives (CAAs) for Corrective Action Unit (CAU) 543: Liquid Disposal Units, Nevada Test Site (NTS), Nevada. Located in Areas 6 and 15 on the NTS, CAU 543 is comprised of a total of seven corrective action sites (CASs), one in Area 6 and six in Area 15. The CAS in Area 6 consists of a Decontamination Facility and its components which are associated with decontamination of equipment, vehicles, and materials related to nuclear testing. The six CASs in Area 15 are located at the U.S. Environmental Protection Agency Farm and are related to waste disposal activities at the farm. Sources of possible contamination at Area 6 include potentially contaminated process waste effluent discharged through a process waste system, a sanitary waste stream generated within buildings of the Decon Facility, and radiologically contaminated materials stored within a portion of the facility yard. At Area 15, sources of potential contamination are associated with the dairy operations and the animal tests and experiments involving radionuclide uptake. Identified contaminants of potential concern include volatile organic compounds, semivolatile organic compounds, petroleum hydrocarbons, pesticides, herbicides, polychlorinated biphenyls, metals, and radionuclides. Three corrective action closure alternatives - No Further Action, Close in Place, or Clean Closure - will be recommended for CAU 543 based on an evaluation of all the data quality objective-related data. Field work will be conducted following approval of the plan. The results of the field investigation will support a defensible evaluation of CAAs that will be presented in the Corrective Action Decision Document.

U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office

2004-05-03T23:59:59.000Z

412

Corrective Action Decision Document/Closure Report for Corrective Action Unit 504: 16a-Tunnel Muckpile, Nevada Test Site  

SciTech Connect (OSTI)

This Corrective Action Decision Document (CADD)/Closure Report (CR) was prepared by the Defense Threat Reduction Agency (DTRA) for Corrective Action Unit (CAU) 504, 16a-Tunnel Muckpile. This CADD/CR is consistent with the requirements of the Federal Facility Agreement and Consent Order (FFACO) agreed to by the State of Nevada; U.S. Department of Energy (DOE), Environmental Management; U.S. Department of Defense; and DOE, Legacy Management. Corrective Action Unit 504 is comprised of four Corrective Action Sites (CASs): • 16-06-01, Muckpile • 16-23-01, Contaminated Burial Pit • 16-23-02, Contaminated Area • 16-99-01, Concrete Construction Waste Corrective Action Site 16-23-01 is not a burial pit; it is part of CAS 16-06-01. Therefore, there is not a separate data analysis and assessment for CAS 16-23-01; it is included as part of the assessment for CAS 16-06-01. In addition to these CASs, the channel between CAS 16-23-02 (Contaminated Area) and Mid Valley Road was investigated with walk-over radiological surveys and soil sampling using hand tools. The purpose of this CADD/CR is to provide justification and documentation supporting the recommendation for closure in place with use restrictions for CAU 504. A CADD was originally submitted for CAU 504 and approved by the Nevada Division of Environmental Protection (NDEP). However, following an agreement between NDEP, DTRA, and the DOE, National Nuclear Security Administration Nevada Site Office to change to a risk-based approach for assessing the corrective action investigation (CAI) data, NDEP agreed that the CAU could be re-evaluated using the risk-based approach and a CADD/CR prepared to close the site.

NSTec Environmental Restoration

2010-03-15T23:59:59.000Z

413

Corrective Action Decision Document for Corrective Action Unit 254: Area 25 R-MAD Decontamination Facility, Nevada Test Site, Nevada  

SciTech Connect (OSTI)

This Corrective Action Decision Document identifies and rationalizes the US Department of Energy, Nevada Operations Office's selection of a recommended corrective action alternative (CAA) appropriate to facilitate the closure of Corrective Action Unit (CAU) 254, R-MAD Decontamination Facility, under the Federal Facility Agreement and Consent Order. Located in Area 25 at the Nevada Test Site in Nevada, CAU 254 is comprised of Corrective Action Site (CAS) 25-23-06, Decontamination Facility. A corrective action investigation for this CAS as conducted in January 2000 as set forth in the related Corrective Action Investigation Plan. Samples were collected from various media throughout the CAS and sent to an off-site laboratory for analysis. The laboratory results indicated the following: radiation dose rates inside the Decontamination Facility, Building 3126, and in the storage yard exceeded the average general dose rate; scanning and static total surface contamination surveys indicated that portions of the locker and shower room floor, decontamination bay floor, loft floor, east and west decon pads, north and south decontamination bay interior walls, exterior west and south walls, and loft walls were above preliminary action levels (PALs). The investigation-derived contaminants of concern (COCs) included: polychlorinated biphenyls, radionuclides (strontium-90, niobium-94, cesium-137, uranium-234 and -235), total volatile and semivolatile organic compounds, total petroleum hydrocarbons, and total Resource Conservation and Recovery Act (Metals). During the investigation, two corrective action objectives (CAOs) were identified to prevent or mitigate human exposure to COCs. Based on these CAOs, a review of existing data, future use, and current operations at the Nevada Test Site, three CAAs were developed for consideration: Alternative 1 - No Further Action; Alternative 2 - Unrestricted Release Decontamination and Verification Survey; and Alternative 3 - Unrestricted Release Decontamination and Verification Survey and Dismantling of Building 3126. These alternatives were evaluated based on four general corrective action standards and five remedy selection decision factors, and the preferred CAA chosen on technical merit was Alternative 2. This CAA was judged to meet all requirements for the technical components evaluated and applicable state and federal regulations for closure of the site, and reduce the potential for future exposure pathways.

U.S. Department of Energy, Nevada Operations Office

2000-06-01T23:59:59.000Z

414

Corrective Action and Involuntary Termination Policy 8.15  

E-Print Network [OSTI]

Corrective Action and Involuntary Termination Policy 8.15 Office of Human Resources Applies to list. Staff may be reprimanded, demoted or terminated for violation of university rules, policies and Process Guide. In appropriate cases, the university reserves the right to move to immediate termination

Howat, Ian M.

415

Solar Correction Factors of Building Envelope in Tebei  

E-Print Network [OSTI]

Tebei has very rich solar energy in China and needs heating in winter,but the present energy building design code has no solar correction factor for the overall heat transfer coefficient of building envelope for Tebei. Based on the typical year...

Wang, D.; Tang, M.

2006-01-01T23:59:59.000Z

416

Ecoulements multiphasiques TD1: tension de surface: Correction  

E-Print Network [OSTI]

Ecoulements multiphasiques TD1: tension de surface: Correction UMPC. NSF16. 2009-2010 Jérôme Hoepffner & Arnaud Antkowiak Ex1: Variation de la tension de surface et mouvements Film1: On chauffe la fluide qui les supporte. Schéma: Analyse: Nous avons vu en cours que la tension de surface pouvait varier

Hoepffner, Jérôme

417

Ocean effect correction in global inversion of geomagnetic  

E-Print Network [OSTI]

data: dcorr = dobs ­ ( F(mi) ­ F'(mi) ) ·invert corrected data: mi+1 = F'-1 (dcorr ) ·repeat until |mi+1 - mi | mi+1 ­ mi = F'-1 ( dobs ­ F(mi) ) ·then if mi+1 ­ mi 0, also mi F-1 (dobs ) Inverse problem with an approximate forward operator #12

Cerveny, Vlastislav

418

Political Correctness in the Science Classroom Noretta Koertge,  

E-Print Network [OSTI]

Political Correctness in the Science Classroom Noretta Koertge, Professor emeritus in History from the author Prepared for the American Enterprise Institute Conference, "Reforming the Politically and universalism would seem to inhibit the invasion by the local political agendas that are so influential

Koertge, Noretta

419

UNIVERSITY OF CONNECICUT HEALTH CENTER CORRECTIONAL MANAGED HEALTH CARE  

E-Print Network [OSTI]

UNIVERSITY OF CONNECICUT HEALTH CENTER CORRECTIONAL MANAGED HEALTH CARE POLICY AND PROCEDURES Managed Health Care (CMHC) shall ensure that newly admitted inmates to Connecticut Department include, but is not limited to, emergency health care, sick call, access to medication, dental and mental

Oliver, Douglas L.

420

The Ground State Energy of Heavy Atoms: the Leading Correction  

E-Print Network [OSTI]

For heavy atoms (large atomic number $Z$) described by no-pair operators in the Furry picture we find the ground state's leading energy correction. We compare the result with (semi-)empirical values and Schwinger's prediction showing more than qualitative agreement.

Michael Handrek; Heinz Siedentop

2014-11-21T23:59:59.000Z

Note: This page contains sample records for the topic "icm interim corrective" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


421

Modeling boundary measurements of scattered light using the corrected  

E-Print Network [OSTI]

to numerical solutions of the radiative transport equation. © 2012 Optical Society of America OCIS codes: (170Adams and B. J. Tromberg, "Boundary conditions for the diffusion equation in radiative transfer," J. Opt. Soc element method to solve the diffusion equation. We show that this corrected diffusion approximation models

Kim, Arnold D.

422

Emissivity corrected infrared method for imaging anomalous structural heat flows  

DOE Patents [OSTI]

A method for detecting flaws in structures using dual band infrared radiation. Heat is applied to the structure being evaluated. The structure is scanned for two different wavelengths and data obtained in the form of images. Images are used to remove clutter to form a corrected image. The existence and nature of a flaw is determined by investigating a variety of features.

Del Grande, Nancy K. (San Leandro, CA); Durbin, Philip F. (Livermore, CA); Dolan, Kenneth W. (Livermore, CA); Perkins, Dwight E. (Livermore, CA)

1995-01-01T23:59:59.000Z

423

Stochastic Systems Group MR Bias Correction and Reflectance  

E-Print Network [OSTI]

. Fisher, M. Cetin, S. Haker, A. Willsky #12;Stochastic Systems Group Outline 1. Introduction 2. MR) · Both maps will have edges #12;Stochastic Systems Group Outline 1. Introduction 2. MR measurement modelStochastic Systems Group MR Bias Correction and Reflectance and Illumination Separation Ayres Fan

Willsky, Alan S.

424

Corrections to Eikonal Approximation for Nuclear Scattering at Medium Energies  

E-Print Network [OSTI]

The upcoming Facility for Rare Isotope Beams (FRIB) at the National Superconducting Cyclotron Laboratory (NSCL) at Michigan State University has reemphasized the importance of accurate modeling of low energy nucleus-nucleus scattering. Such calculations have been simplified by using the eikonal approximation. As a high energy approximation, however, its accuracy suffers for the medium energy beams that are of current experimental interest. A prescription developed by Wallace \\cite{Wallace:1971zz,Wallace:1973iu} that obtains the scattering propagator as an expansion around the eikonal propagator (Glauber approach) has the potential to extend the range of validity of the approximation to lower energies. Here we examine the properties of this expansion, and calculate the first-, second-, and third-order corrections for the scattering of a spinless particle off of a ${}^{40}$Ca nucleus, and for nuclear breakup reactions involving ${}^{11}$Be. We find that, including these corrections extends the lower bound of the range of validity of the down to energies of 40 MeV. At that energy the corrections provide as much as a 15\\% correction to certain processes.

Micah Buuck; Gerald A. Miller

2014-06-12T23:59:59.000Z

425

Quasi-sparse eigenvector diagonalization and stochastic error correction  

E-Print Network [OSTI]

We briefly review the diagonalization of quantum Hamiltonians using the quasi-sparse eigenvector (QSE) method. We also introduce the technique of stochastic error correction, which systematically removes the truncation error of the QSE result by stochastically sampling the contribution of the remaining basis states.

Dean Lee

2000-08-30T23:59:59.000Z

426

Correct and incorrect nucleotide incorporation pathways in DNA polymerase b  

E-Print Network [OSTI]

Correct and incorrect nucleotide incorporation pathways in DNA polymerase b Ravi Radhakrishnan a nucleotide incorporations in the DNA by using a novel protocol involving energy minimizations, dynamics simu- sive transient intermediates, for nucleotide incorporation at the template/primer DNA junction. A large

Schlick, Tamar

427

Convergence properties of the local defect correction method for parabolic  

E-Print Network [OSTI]

and, for a one-dimensional heat equation, we study its properties analytically. Numerical experiment of adaptive grid techniques. In adaptive grid methods, a fine grid spacing and a relatively small time step requirements are minimized. An adaptive grid technique of particular interest is the Local Defect Correction

Eindhoven, Technische Universiteit

428

Power Corrections to Event Shapes with Mass-Dependent Operators  

E-Print Network [OSTI]

We introduce an operator depending on the "transverse velocity" r that describes the effect of hadron masses on the leading 1/Q power correction to event-shape observables. Here, Q is the scale of the hard collision. This work builds on earlier studies of mass effects by Salam and Wicke and of operators by Lee and Sterman. Despite the fact that different event shapes have different hadron mass dependence, we provide a simple method to identify universality classes of event shapes whose power corrections depend on a common nonperturbative parameter. We also develop an operator basis to show that at a fixed value of Q, the power corrections for many classic observables can be determined by two independent nonperturbative matrix elements at the 10% level. We compute the anomalous dimension of the transverse velocity operator, which is multiplicative in r and causes the power correction to exhibit non-trivial dependence on Q. The existence of universality classes and the relevance of anomalous dimensions are reproduced by the hadronization models in Pythia 8 and Herwig++, though the two programs differ in the values of their low-energy matrix elements.

Vicent Mateu; Iain W. Stewart; Jesse Thaler

2013-02-06T23:59:59.000Z

429

Correction to “Hyperspectral Aerosol Optical Depths from TCAP Flights”  

SciTech Connect (OSTI)

In the paper “Hyperspectral aerosol optical depths from TCAP flights” by Y. Shinozuka et al. (Journal of Geophysical Research: Atmospheres, 118, doi:10.1002/2013JD020596, 2013), Tables 1 and 2 were published with the column heads out of order. Tables 1 and 2 are published correctly here. The publisher regrets the error.

Shinozuka, Yohei; Johnson, Roy R.; Flynn, Connor J.; Russell, P. B.; Schmid, Beat; Redemann, Jens; Dunagan, Stephen; Kluzek, Celine D.; Hubbe, John M.; Segal-Rosenheimer, Michal; Livingston, J. M.; Eck, T.; Wagener, Richard; Gregory, L.; Chand, Duli; Berg, Larry K.; Rogers, Ray; Ferrare, R. A.; Hair, John; Hostetler, Chris A.; Burton, S. P.

2014-02-16T23:59:59.000Z

430

Power Grid Correction Using Sensitivity Analysis Meric Aydonat  

E-Print Network [OSTI]

Power Grid Correction Using Sensitivity Analysis Meric¸ Aydonat Department of ECE University University of Toronto Toronto, Ontario, Canada E-mail: f.najm@utoronto.ca Abstract--Power grid voltage integrity verification requires one to check if all the voltage drops on the grid are less than a certain

Najm, Farid N.

431

Two infinite families of nonadditive quantum error-correcting codes  

E-Print Network [OSTI]

We construct explicitly two infinite families of genuine nonadditive 1-error correcting quantum codes and prove that their coding subspaces are 50% larger than those of the optimal stabilizer codes of the same parameters via the linear programming bound. All these nonadditive codes can be characterized by a stabilizer-like structure and thus their encoding circuits can be designed in a straightforward manner.

Sixia Yu; Qing Chen; C. H. Oh

2009-01-14T23:59:59.000Z

432

The Self Attenuation Correction for Holdup Measurements, a Historical Perspective  

SciTech Connect (OSTI)

Self attenuation has historically caused both conceptual as well as measurement problems. The purpose of this paper is to eliminate some of the historical confusion by reviewing the mathematical basis and by comparing several methods of correcting for self attenuation focusing on transmission as a central concept.

Oberer, R. B.; Gunn, C. A.; Chiang, L. G.

2006-07-11T23:59:59.000Z

433

Generation of certifiably correct programs from formal models Alexei Iliasov  

E-Print Network [OSTI]

Generation of certifiably correct programs from formal models Alexei Iliasov Newcastle University techniques helps to deliver systems that are free from engineer- ing defects. A code generator quickly, consistently and reproducibly. Com- monly, a code generator is a program constructed informally

Southampton, University of

434

Record of Technical Change for Corrective Action Plan for Corrective Action Unit 140: Waste Dumps, burn Pits, and Storage Area, Nevada Test Site, Nevada  

SciTech Connect (OSTI)

Record of Technical Change for Corrective Action Plan for Corrective Action Unit 140: Waste Dumps, Burn Pits, and Storage Area, Nevada Test Site, Nevada (DOE/NV--963-Rev 2, dated November 2004).

U.S. Department of Energy, National Nuclear Security Administration, Nevada Site Office; Bechtel Nevada

2005-01-05T23:59:59.000Z

435

Closure report for housekeeping category, Corrective Action Unit 348, Nevada Test Site  

SciTech Connect (OSTI)

This Closure Report summarizes the corrective actions which were completed at twelve Corrective Action Sites within Corrective Action Unit 348 at the Nevada Test Site. Current site descriptions, observations and identification of wastes removed are included on FFACO Corrective Action Site housekeeping closure verification forms.

NONE

1998-01-01T23:59:59.000Z

436

ARM: Broadband Radiometer Station (BRS) broadband shortwave and longwave 1-min radiation data with Dutton correction  

DOE Data Explorer [Office of Scientific and Technical Information (OSTI)]

Broadband Radiometer Station (BRS) broadband shortwave and longwave 1-min radiation data with Dutton correction

Stoffel, Tom; Kay, Bev; Habte, Aron; Anderberg, Mary; Kutchenreiter, Mark

437

ARM: SIRS: derived, correction of downwelling shortwave diffuse hemispheric measurements using Dutton and full algorithm  

DOE Data Explorer [Office of Scientific and Technical Information (OSTI)]

SIRS: derived, correction of downwelling shortwave diffuse hemispheric measurements using Dutton and full algorithm

Stoffel, Tom; Kay, Bev; Habte, Aron; Anderberg, Mary; Kutchenreiter, Mark

438

Accelerating RCRA corrective action: The principles of the DOE approach  

SciTech Connect (OSTI)

The US Department of Energy (DOE) is involved in the remediation of environmental contamination at many of its facilities under the Resource Conservation and Recovery Act (RCRA). RCRA`s corrective action provisions were established by the Hazardous and Solid Waste Amendments of 1984 (HSWA). In response to the HSWA mandate, EPA established a program for the conduct of RCRA corrective action that was similar to that established under the Comprehensive Environmental Response Compensation and Liability Act (CERCLA). In addition, EPA developed and implemented its ``stabilization`` initiative as a means of quickly addressing immediate risks posed by releases until long term solutions can be applied. To improve the efficiency of environmental restoration at its facilities, DOE is developing guidance and training programs on accelerated environmental restoration under RCRA. A RCRA guidance document, entitled ``Accelerating RCRA Corrective Action at DOE Facilities,`` is currently being developed by DOE`s Office of Environmental Policy and Assistance. The new guidance document will outline a decision-making process for determining if acceleration is appropriate for individual facilities, for identifying, evaluating, and selecting options for program acceleration, and for implementing selected acceleration options. The document will also discuss management and planning strategies that provide a firm foundation for accelerating RCRA corrective action. These strategies include a number of very basic principles that have proven effective at DOE and other federal facilities, as well as some new approaches. The purpose of this paper is to introduce DOE`s new guidance document, discuss the general approach presented in the guidance for accelerating RCRA corrective action, and to emphasize some of the more important principles of effective management and planning.

Kimmell, T.A.; Green, D.R.; Ranek, N.L. [Argonne National Lab., IL (United States); Coalgate, J.L. [USDOE, Washington, DC (United States)

1995-03-01T23:59:59.000Z

439

Corrective Action Investigation Plan for Corrective Action Unit 219: Septic Systems and Injection Wells, Nevada Test Site, Nevada, Rev. No.: 0  

SciTech Connect (OSTI)

The Corrective Action Investigation Plan for Corrective Action Unit 219, Septic Systems and Injection Wells, has been developed in accordance with the ''Federal Facility Agreement and Consent Order'' (1996) that was agreed to by the State of Nevada, the U.S. Department of Energy, and the U.S. Department of Defense. The purpose of the investigation is to ensure that adequate data are collected to provide sufficient and reliable information to identify, evaluate, and select technically viable corrective actions. Corrective Action Unit 219 is located in Areas 3, 16, and 23 of the Nevada Test Site, which is 65 miles northwest of Las Vegas, Nevada. Corrective Action Unit 219 is comprised of the six Corrective Action Sites (CASs) listed below: (1) 03-11-01, Steam Pipes and Asbestos Tiles; (2) 16-04-01, Septic Tanks (3); (3) 16-04-02, Distribution Box; (4) 16-04-03, Sewer Pipes; (5) 23-20-01, DNA Motor Pool Sewage and Waste System; and (6) 23-20-02, Injection Well. These sites are being investigated because existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend corrective action alternatives. Additional information will be obtained by conducting a corrective action investigation prior to evaluating corrective action alternatives and selecting the appropriate corrective action for each CAS. The results of the field investigation will support a defensible evaluation of viable corrective action alternatives that will be presented in the Corrective Action Decision Document.

David A. Strand

2005-01-01T23:59:59.000Z

440

Corrective Action Decision Document for Corrective Action Unit 139: Waste Disposal Sites, Nevada Test Sites, Nevada with ROTC 1, Errata Sheet, Revision 0, January 2007  

SciTech Connect (OSTI)

The purpose of this CADD is to identify and provide the rationale for the recommendation of a corrective action alternative (CAA) for the seven CASs within CAU 139. Corrective action investigation activities were performed from June 26 through September 27, 2006, as set forth in the CAU 139 Corrective Action Investigation Plan (CAIP).

Grant Evenson

2007-01-01T23:59:59.000Z

Note: This page contains sample records for the topic "icm interim corrective" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


441

Corrective Action Plan for Corrective Action Unit 166: Storage Yards and Contaminated Materials, Nevada Test Site, Nevada  

SciTech Connect (OSTI)

Corrective Action Unit (CAU) 166, Storage Yards and Contaminated Materials, is listed in the Federal Facility Agreement and Consent Order (FFACO) of 1996 (FFACO, 1996). CAU 166 consists of seven Corrective Action Sites (CASs) located in Areas 2, 3, 5, and 18 of the Nevada Test Site (NTS), which is located approximately 65 miles northwest of Las Vegas, Nevada (Figure 1). CAU 166 consists of the following CASs: (1) CAS 02-42-01, Cond. Release Storage Yd - North; (2) CAS 02-42-02, Cond. Release Storage Yd - South; (3) CAS 02-99-10, D-38 Storage Area; (4) CAS 03-42-01, Conditional Release Storage Yard; (5) CAS 05-19-02, Contaminated Soil and Drum; (6) CAS 18-01-01, Aboveground Storage Tank; and (7) CAS 18-99-03, Wax Piles/Oil Stain. Details of the site history and site characterization results for CAU 166 are provided in the approved Corrective Action Investigation Plan (CAIP) (U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office [NNSA/NSO], 2006) and in the approved Corrective Action Decision Document (CADD) (NNSA/NSO, 2007).

NSTec Environmental Restoration

2007-10-01T23:59:59.000Z

442

Corrective action investigation plan for Corrective Action Unit 340, Pesticide Release Sites, Nevada Test Site, Nye County, Nevada  

SciTech Connect (OSTI)

This Correction Action Investigation Plan (CAIP) has been developed in accordance with the Federal Facility Agreement and Consent Order (FFACO) that was agreed to by the US Department of Energy, Nevada Operations Office (DOE/NV); the State of Nevada Division of Environmental Protection (NDEP); and the US Department of Defense. As required by the FFACO (1996), this document provides or references all of the specific information for planning investigation activities associated with three Corrective Action Sites (CASs) located at the Nevada Test Site (NTS). These CASs are collectively known as Corrective Action Unit (CAU) 340, Pesticide Release Sites. According to the FFACO, CASs are sites that may require corrective action(s) and may include solid waste management units or individual disposal or release sites. These sites are CAS 23-21-01, Area 23 Quonset Hut 800 (Q800) Pesticide Release Ditch; CAS 23-18-03, Area 23 Skid Huts Pesticide Storage; and CAS 15-18-02, Area 15 Quonset Hut 15-11 Pesticide Storage (Q15-11). The purpose of this CAIP for CAU 340 is to direct and guide the investigation for the evaluation of the nature and extent of pesticides, herbicides, and other contaminants of potential concern (COPCs) that were stored, mixed, and/or disposed of at each of the CASs.

NONE

1998-01-01T23:59:59.000Z

443

Corrective Action Plan for Corrective Action Unit 254: Area 25 R-MAD Decontamination Facility Nevada Test Site, Nevada  

SciTech Connect (OSTI)

The Area 25 Reactor Maintenance, Assembly, and Disassembly Decontamination Facility is identified in the Federal Facility Agreement and Consent Order (FFACO) as Corrective Action Unit (CAU) 254. CAU 254 is located in Area 25 of the Nevada Test Site and consists of a single Corrective Action Site CAS 25-23-06. CAU 254 will be closed, in accordance with the FFACO of 1996. CAU 254 was used primarily to perform radiological decontamination and consists of Building 3126, two outdoor decontamination pads, and surrounding soil within an existing perimeter fence. The site was used to decontaminate nuclear rocket test-car hardware and tooling from the early 1960s through the early 1970s, and to decontaminate a military tank in the early 1980s. The site characterization results indicate that, in places, the surficial soil and building materials exceed clean-up criteria for organic compounds, metals, and radionuclides. Closure activities are expected to generate waste streams consisting of nonhazardous construction waste. petroleum hydrocarbon waste, hazardous waste, low-level radioactive waste, and mixed waste. Some of the wastes exceed land disposal restriction limits and will require off-site treatment before disposal. The recommended corrective action was revised to Alternative 3- ''Unrestricted Release Decontamination, Verification Survey, and Dismantle Building 3126,'' in an addendum to the Correction Action Decision Document.

C. M. Obi

2000-12-01T23:59:59.000Z

444

Corrective Action Investigation Plan for Corrective Action Unit 335: Area 6 Injection Well and Drain Pit, Nevada Test Site, Nevada  

SciTech Connect (OSTI)

This Corrective Action Investigation Plan contains the U.S. Department of Energy, Nevada Operations Office's approach to collect the data necessary to evaluate corrective action alternatives appropriate for the closure of Corrective Action Unit (CAU) 335, Area 6 Injection Well and Drain Pit, under the Federal Facility Agreement and Consent Order. Corrective Action Unit 335 consists of three Corrective Action Sites (CASs). The CAU is located in the Well 3 Yard in Area 6 at the Nevada Test Site. Historical records indicate that the Drain Pit (CAS 06-23-03) received effluent from truck-washing; the Drums/Oil Waste/Spill (CAS 06-20-01) consisted of four 55-gallon drums containing material removed from the Cased Hole; and the Cased Hole (CAS 06-20-02) was used for disposal of used motor oil, wastewater, and debris. These drums were transported to the Area 5 Hazardous Waste Accumulation Site in July 1991; therefore, they are no longer on site and further investigation or remediation efforts are not required. Consequently, CAS 06-20-01 will be closed with no further action and details of this decision will be described in the Closure Report for this CAU. Any spills that may have been associated with this CAS will be investigated and addressed under CAS 06-20-02. Field investigation efforts will be focused on the two remaining CASs. The scope of the investigation will center around identifying any contaminants of potential concern (COPCs) and, if present, determining the vertical and lateral extent of contamination. The COPCs for the Drain Pit include: total volatile/ semivolatile organic compounds, total petroleum hydrocarbons (gasoline-and diesel-range organics), ethylene glycol monobutyl ether, polychlorinated biphenyls, total Resource Conservation and Recovery Act metals, and radionuclides. The COPCs for the Cased Hole include: total volatile/ semivolatile organic compounds, total petroleum hydrocarbons (diesel-range organics only), and total Resource Conservation an d Recovery Act metals. Both biased surface and subsurface soil sampling will be conducted, augmented by visual inspection, video surveys, and electromagnetic surveys. The results of this field investigation will support a defensible evaluation of corrective action alternatives in the corrective action decision document.

DOE/NV

2000-12-01T23:59:59.000Z

445

Corrective Action Investigation Plan for Corrective Action Unit 486: Double Tracks RADSAFE Area Nellis Air Force Range, Nevada  

SciTech Connect (OSTI)

This Corrective Action Investigation Plan (CAIP) has been developed in accordance with the Federal Facility Agreement and Consent Order (FFACO) that was agreed to by the US Department of Energy, Nevada Operations Office (DOE/NV); the State of Nevada Division of Environmental Protection (NDEP); and the US Department of Defense (FFACO, 1996). The CAIP is a document that provides or references all of the specific information for investigation activities associated with Corrective Action Units (CAUs) or Corrective Action Sites (CASs). According to the FFACO, CASs are sites potentially requiring corrective action(s) and may include solid waste management units or individual disposal or release sites (FFACO, 1996). Corrective Action Units consist of one or more CASs grouped together based on geography, technical similarity, or agency responsibility for the purpose of determining corrective actions. This CAIP contains the environmental sample collection objectives and the criteria for conducting site investigation activities at CAU 486, the Double Tracks Radiological Safety (RADSAFE) Area (DTRSA) which is located on the Nellis Air Force Range 71North (N), west of the Tonopah Test Range (TTR). The TTR, included in the Nellis Air Force Range Complex, is approximately 255 kilometers (km) (140 miles [mi]) northwest of Las Vegas, Nevada (Figure 1-1). Corrective Action Unit 486 is comprised of CAS 71-23-001-71DT consisting of two areas of concern referred to as the vehicle decontamination area and the animal burial pit. The DTRSA is located on the west side of the Cactus Range approximately 8 km (5 mi) southwest of the Cactus Spring gate at the intersection of the Cactus Spring Road and the Double Tracks Control Point Road (Figure 1-2). The DTRSA was used during May 1963 to decontaminate vehicles, equipment, personnel, and animals from the Double Tracks test. The DTRSA is one of three areas identified as a potential location for the disposal of radioactively contaminated materials from the Double Tracks experiment. The other two locations are the Cactus Spring Waste Trenches (CAU 426) and the Roller Coaster RADSAFE Area (CAU 407), both of which have been investigated. The surface and subsurface soils are likely to have been impacted by plutonium and other contaminants of potential concern (COPCs) associated with decontamination activities at this site.

IT Las Vegas

1998-10-15T23:59:59.000Z

446

Corrective Action Investigation Plan for Corrective Action Unit 375: Area 30 Buggy Unit Craters, Nevada Test Site, Nevada  

SciTech Connect (OSTI)

Corrective Action Unit (CAU) 375 is located in Areas 25 and 30 of the Nevada Test Site, which is approximately 65 miles northwest of Las Vegas, Nevada. Corrective Action Unit 375 comprises the two corrective action sites (CASs) listed below: • 25-23-22, Contaminated Soils Site • 30-45-01, U-30a, b, c, d, e Craters Existing information on the nature and extent of potential contamination present at the CAU 375 CASs is insufficient to evaluate and recommend corrective action alternatives (CAAs). This document details an investigation plan that will provide for the gathering of sufficient information to evaluate and recommend CAAs. Corrective Action Site 25-23-22 is composed of the releases associated with nuclear rocket testing at Test Cell A (TCA). Test Cell A was used to test and develop nuclear rocket motors as part of the Nuclear Rocket Development Station from its construction in 1958 until 1966, when rocket testing began being conducted at Test Cell C. The rocket motors were built with an unshielded nuclear reactor that produced as much as 1,100 kilowatts (at full power) to heat liquid hydrogen to 4,000 degrees Fahrenheit, at which time the expanded gases were focused out a nozzle to produce thrust. The fuel rods in the reactor were not clad and were designed to release fission fragments to the atmosphere, but due to vibrations and loss of cooling during some operational tests, fuel fragments in excess of planned releases became entrained in the exhaust and spread in the immediate surrounding area. Cleanup efforts have been undertaken at times to collect the fuel rod fragments and other contamination. Previous environmental investigations in the TCA area have resulted in the creation of a number of use restrictions. The industrial area of TCA is encompassed by a fence and is currently posted as a radioactive material area. Corrective Action Site 30-45-01 (releases associated with the Buggy Plowshare test) is located in Area 30 on Chukar Mesa. It was a Plowshare test where five nuclear devices were buried 140 feet (ft) deep in a row at 150-ft intervals. These devices were detonated on March 12, 1968, to produce a trench 254 ft wide, 865 ft long, and 70 ft deep. The mesa where the test was conducted is surrounded on three sides by ravines, and the entire end of the mesa is fenced and posted as a contamination area. These sites are being investigated because existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend CAAs. Additional information will be obtained by conducting a corrective action investigation before evaluating CAAs and selecting the appropriate corrective action for each CAS. The results of the field investigation will support a defensible evaluation of viable CAAs that will be presented in the Corrective Action Decision Document. The sites will be investigated based on the data quality objectives (DQOs) developed on December 2, 2009, by representatives of the Nevada Division of Environmental Protection and the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office. The DQO process was used to identify and define the type, amount, and quality of data needed to develop and evaluate appropriate corrective actions for CAU 375.

Patrick Matthews

2010-03-01T23:59:59.000Z

447

Interim measure conceptual design for remediation at the former CCC/USDA grain storage facility at Centralia, Kansas : pilot test and remedy implementation.  

SciTech Connect (OSTI)

This document presents an Interim Measure Work Plan/Design for the short-term, field-scale pilot testing and subsequent implementation of a non-emergency Interim Measure (IM) at the site of the former grain storage facility operated by the Commodity Credit Corporation of the U.S. Department of Agriculture (CCC/USDA) in Centralia, Kansas. The IM is recommended to mitigate both (1) localized carbon tetrachloride contamination in the vadose zone soils beneath the former facility and (2) present (and potentially future) carbon tetrachloride contamination identified in the shallow groundwater beneath and in the immediate vicinity of the former CCC/USDA facility. Investigations conducted on behalf of the CCC/USDA by Argonne National Laboratory have demonstrated that groundwater at the Centralia site is contaminated with carbon tetrachloride at levels that exceed the Kansas Tier 2 Risk-Based Screening Level (RBSL) and the U.S. Environmental Protection Agency's maximum contaminant level of 5.0 {micro}g/L for this compound. Groundwater sampling and analyses conducted by Argonne under a monitoring program approved by the Kansas Department of Health and Environment (KDHE) indicated that the carbon tetrachloride levels at several locations in the groundwater plume have increased since twice yearly monitoring of the site began in September 2005. The identified groundwater contamination currently poses no unacceptable health risks, in view of the absence of potential human receptors in the vicinity of the former CCC/USDA facility. Carbon tetrachloride contamination has also been identified at Centralia in subsurface soils at concentrations on the order of the Kansas Tier 2 RBSL of 200 {micro}g/kg in soil for the soil-to-groundwater protection pathway. Soils contaminated at this level might pose some risk as a potential source of carbon tetrachloride contamination to groundwater. To mitigate the existing contaminant levels and decrease the potential future concentrations of carbon tetrachloride in groundwater and soil, the CCC/USDA recommends initial short-term, field-scale pilot testing of a remedial approach that employs in situ chemical reduction (ISCR), in the form of a commercially available material marketed by Adventus Americas, Inc., Freeport, Illinois (http://www.adventusgroup.com). If the pilot test is successful, it will be followed by a request for KDHE authorization of full implementation of the ISCR approach. In the recommended ISCR approach, the Adventus EHC{reg_sign} material--a proprietary mixture of food-grade organic carbon and zero-valent iron--is introduced into the subsurface, where the components are released slowly into the formation. The compounds create highly reducing conditions in the saturated zone and the overlying vadose zone. These conditions foster chemical and biological reductive dechlorination of carbon tetrachloride. The anticipated effective lifetime of the EHC compounds following injection is 1-5 yr. Although ISCR is a relatively innovative remedial approach, the EHC technology has been demonstrated to be effective in the treatment of carbon tetrachloride contamination in groundwater and has been employed at a carbon tetrachloride contamination site elsewhere in Kansas (Cargill Flour Mill and Elevator, Wellington, Kansas; KDHE Project Code C209670158), with the approval of the KDHE. At Centralia, the CCC/USDA recommends use of the ISCR approach initially in a short-term pilot test addressing the elevated carbon tetrachloride levels identified in one of three persistently highly contaminated areas ('hot-spot areas') in the groundwater plume. In this test, a three-dimensional grid pattern of direct-push injection points will be used to distribute the EHC material (in slurry or aqueous form) throughout the volume of the contaminated aquifer and (in selected locations) the vadose zone in the selected hot-spot area. Injection of the EHC material will be conducted by a licensed contractor, under the supervision of Adventus and Argonne technical personnel. The contractor will be identified upon acceptanc

LaFreniere, L. M.; Environmental Science Division

2007-11-09T23:59:59.000Z

448

Corrective Action Plan for Corrective Action Unit 230: Area 22 Sewage Lagoons and Corrective Action Unit 320: Area 22 Desert Rock Airport Strainer Box, Nevada Test Site, Nevada  

SciTech Connect (OSTI)

The purpose of this Corrective Action Plan (CAP) is to provide the strategy and methodology to close the Area 22 Sewage Lagoons site. The CAU will be closed following state and federal regulations and the FFACO (1996). Site characterization was done during September 1999, Soil samples were collected using a direct-push method and a backhoe. Soil samples were collected from the sludge bed, sewage lagoons, strainer box, and Imhoff tank areas. Characterization of the manholes associated with the septic system leading to the Imhoff tank was done during March 2000. The results of the characterization were reported in the Corrective Action Decision Document (CADD) (DOE/NV, 2000). Soil sample results indicated that the only constituent of concern (COC) detected above Preliminary Action Levels (PALs) was total petroleum hydrocarbons (TPH) as diesel-range organics. This COC was detected in three samples from the sludge bed at concentrations up to 580 milligrams per kilogram (mg/kg). This exceeds the Nevada Division of Environmental Protection (NDEP) regulatory action level for TPH of 100 mg/kg (Nevada Administrative Code, 1996). Excavation of the area during characterization uncovered asphalt debris, four safety poles, and strands of barbed wire. The TPH-impacted soil and debris will be removed and disposed in the NTS Area 6 Hydrocarbon Landfill.

D. S. Tobiason

2000-09-01T23:59:59.000Z

449

Corrective Action Investigation Plan for Corrective Action Unit 309: Area 12 Muckpiles, Nevada Test Site, Nevada, Rev. No. 0  

SciTech Connect (OSTI)

This Corrective Action Investigation Plan (CAIP) for Corrective Action Unit (CAU) 309, Area 12 Muckpiles, Nevada Test Site (NTS), Nevada, has been developed in accordance with the ''Federal Facility Agreement and Consent Order'' (FFACO) that was agreed to by the State of Nevada, the U.S. Department of Energy, and the U.S. Department of Defense. The general purpose of the investigation is to ensure that adequate data are collected to provide sufficient and reliable information to identify, evaluate, and select technically viable corrective actions. Corrective Action Unit 309 is comprised of the following three corrective action sites (CASs) in Area 12 of the NTS: (1) CAS 12-06-09, Muckpile; (2) CAS 12-08-02, Contaminated Waste Dump (CWD); and (3) CAS 12-28-01, I-, J-, and K-Tunnel Debris. Corrective Action Site 12-06-09 consists of a muckpile and debris located on the hillside in front of the I-, J-, and K-Tunnels on the eastern slopes of Rainier Mesa in Area 12. The muckpile includes mining debris (muck) and debris generated during the excavation and construction of the I-, J-, and K-Tunnels. Corrective Action Site 12-08-02, CWD, consists of a muckpile and debris and is located on the hillside in front of the re-entry tunnel for K-Tunnel. For the purpose of this investigation CAS 12-28-01 is defined as debris ejected by containment failures during the Des Moines and Platte Tests and the associated contamination that is not covered in the two muckpile CASs. This site consists of debris scattered south of the I-, J-, and K-Tunnel muckpiles and extends down the hillside, across the valley, and onto the adjacent hillside to the south. In addition, the site will cover the potential contamination associated with ''ventings'' along the fault, fractures, and various boreholes on the mesa top and face. One conceptual site model was developed for all three CASs to address possible contamination migration pathways associated with CAU 309. The data quality objective (DQO) process was used to identify and define the type, quantity, and quality of data needed to complete the investigation phase of the corrective action process. The DQO process addresses the primary problem that sufficient information is not available to determine the appropriate corrective action for the CAU. Due to the practical constraints posed by steep slopes on and around the CAU 309 muckpiles, a conservative, simplifying strategy was developed to resolve the presence and nature of contaminants. This strategy includes the use of historical data from similar sites (i.e., previously investigated NTS muckpiles) and the collection of samples from accessible areas of the muckpiles. Based on site history, process knowledge, and previous investigations of similar sites, contaminants of potential concern for CAU 309 collectively include radionuclides, total petroleum hydrocarbons (diesel range only), polychlorinated biphenyls, ''Resource Conservation and Recovery Act'' metals, volatile organic compounds, and semivolatile organic compounds.

Robert F. Boehlecke

2004-12-01T23:59:59.000Z

450

Corrective Action Investigation Plan for Corrective Action Unit 529: Area 25 Contaminated Materials, Nevada Test Site, Nevada, Rev. 0, Including Record of Technical Change No. 1  

SciTech Connect (OSTI)

This Corrective Action Investigation Plan contains the U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office's approach to collect the data necessary to evaluate