National Library of Energy BETA

Sample records for gao high risk

  1. EM Makes Progress on GAO High-Risk List

    Broader source: Energy.gov [DOE]

    WASHINGTON, D.C. – The U.S. Government Accountability Office (GAO) has removed EM capital asset projects of $750 million or less from its high-risk list because of the nuclear cleanup program’s progress in completing that work.

  2. Report: Removal of EM Projects from the GAO High Risk List: Strategies for Improving the Effectiveness of Project and Contract Management in the Office of Environmental Management

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    U.S. Department of Energy REPORT TO THE ENVIRONMENTAL MANAGEMENT ADVISORY BOARD Removal of EM Projects from the GAO High Risk List: Strategies for Improving the Effectiveness of Project and Contract Management in the Office of Environmental Management Submitted by the EMAB Acquisition and Project Management Subcommittee December 5, 2011 Introduction: This report provides a comprehensive summary of the work performed by the Acquisition and Project Management Subcommittee (APMS) of the

  3. GAO Report Reflects Success Story for EM Sites

    Broader source: Energy.gov [DOE]

    In a report released earlier this year, the U.S. Government Accountability Office (GAO) said it recognized progress on EM projects of $750 million or less and was shifting the focus of EM's high-risk designation more to major contracts and projects greater than $750 million. This progress is evident at several EM sites.

  4. Jun Gao | Argonne National Laboratory

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Jun Gao Postdoctoral Appointee Telephone (630) 252-7405 E-mail jung@smu.edu

  5. GAO Cost Estimating and Assessment Guide | Department of Energy

    Energy Savers [EERE]

    Cost Estimating and Assessment Guide GAO Cost Estimating and Assessment Guide GAO Cost Estimating and Assessment Guide: Twelve Steps of a High-Quality Cost Estimating Process, from the first step of defining the estimate's purpose to the last step of updating the estimate to reflect actual costs and changes. Twelve Steps of a High-Quality Cost Estimating Process (75.75 KB) Key Resources PMCDP EVMS PARS IIe FPD Resource Center PM Newsletter Forms and Templates More Documents & Publications

  6. Report: Removal of EM Projects from the GAO High Risk List

    Office of Environmental Management (EM)

    Report: IG-0449 Report: IG-0449 July 19, 1999 The Office of Defense Programs Robotics and Intelligent Machines Projects Robotics and Intelligent Machines (RIM) are systems composed of machines, sensors, computers, and software capable of executing various tasks with minimal human intervention. They have wide range application for solving many operational challenges including nuclear waste cleanup and weapons manufacturing and dismantlement. RIM accelerates cleanup and reduces the amount of

  7. GAO Report -- National Environmental Policy Act: Little Information...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    GAO Report -- National Environmental Policy Act: Little Information Exists on NEPA Analyses A report by the United States Government Accountability Office (GAO) on the costs, time ...

  8. GAO 2010 Project Management Documents | Department of Energy

    Energy Savers [EERE]

    2010 Project Management Documents GAO 2010 Project Management Documents The following documents are included on this page: "DepSec Thank You Letter to GAO (19 May 2010)"; "GAO Thank You Letter to DepSec (6 Jul 2010)"; and "Letter to GAO on Contract & Project Management (8 Nov 2010)". Letter to GAO on Contract & Project Management (8 Nov 2010).pdf (1.44 MB) Key Resources PMCDP EVMS PARS IIe FPD Resource Center PM Newsletter Forms and Templates More Documents

  9. GAO Report -- National Environmental Policy Act: Little Information Exists

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    on NEPA Analyses | Department of Energy GAO Report -- National Environmental Policy Act: Little Information Exists on NEPA Analyses GAO Report -- National Environmental Policy Act: Little Information Exists on NEPA Analyses A report by the United States Government Accountability Office (GAO) on the costs, time frames, and benefits of the NEPA process. The report posted here has been modified through the addition of yellow highlighting to denote text referring to DOE or DOE data. The original

  10. GAO Audit Reports | U.S. DOE Office of Science (SC)

    Office of Science (SC) Website

    Fusion Energy - GAO-08-30 (October 2007) .pdf file (2.7MB) Climate Change Research Data Sharing - GAO-07-1172 (September 2007) .pdf file (1.3MB) SBIR - GAO-07-38 (October ...

  11. Ex Parte Memo for the Initial GAO Meeting on Part 810 | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy for the Initial GAO Meeting on Part 810 Ex Parte Memo for the Initial GAO Meeting on Part 810 The September 10, 2013, meeting between the U.S. Government Accountability Office (GAO) and the U.S. Department of Energy/National Nuclear Security Administration (DOE/NNSA) served as a first meeting between the GAO and DOE/NNSA program staff related to an upcoming GAO audit on Part 810 regulations. Ex Parte Part 810 Meeting with GAO (47.87 KB) More Documents & Publications MEMORANDUM OF

  12. High Risk Plan | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    PDF icon High Risk Plan More Documents & Publications DOE Site Facility Management Contracts Internet Posting DOE Head of Contracting Activity and Procurement Directors' Directory ...

  13. GAO-14-369, NATIONAL ENVIRONMENTAL POLICY ACT: Little Information Exists on NEPA Analyses

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    NATIONAL ENVIRONMENTAL POLICY ACT Little Information Exists on NEPA Analyses Report to Congressional Requesters April 2014 GAO-14-369 United States Government Accountability Office United States Government Accountability Office Highlights of GAO-14-369, a report to congressional requesters April 2014 NATIONAL ENVIRONMENTAL POLICY ACT Little Information Exists On NEPA Analyses Why GAO Did This Study NEPA requires all federal agencies to evaluate the potential environmental effects of proposed

  14. GAO-12-645, Federal Real Property, National Strategy and Better...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    2-645, Federal Real Property, National Strategy and Better Data Needed to Improve Management of Excess and Underutilized Property GAO-12-645, Federal Real Property, National...

  15. High risk of permafrost thaw

    SciTech Connect (OSTI)

    Schuur, E.A.G.; Abbott, B.; Koven, C.D,; Riley, W.J.; Subin, Z.M.; al, et

    2011-11-01

    In the Arctic, temperatures are rising fast, and permafrost is thawing. Carbon released to the atmosphere from permafrost soils could accelerate climate change, but the likely magnitude of this effect is still highly uncertain. A collective estimate made by a group of permafrost experts, including myself, is that carbon could be released more quickly than models currently suggest, and at levels that are cause for serious concern. While our models of carbon emission from permafrost thaw are lacking, experts intimately familiar with these landscapes and processes have accumulated knowledge about what they expect to happen, based on both quantitative data and qualitative understanding of these systems. We (the authors of this piece) attempted to quantify this expertise through a survey developed over several years, starting in 2009. Our survey asked experts what percentage of surface permafrost they thought was likely to thaw, how much carbon would be released, and how much of that would be methane, for three time periods and under four warming scenarios that are part of the new IPCC Fifth Assessment Report.

  16. Actions taken by DOD on GAO recommendations to improve spare parts requirements determination

    SciTech Connect (OSTI)

    Not Available

    1985-04-30

    GAO found that actions taken by the military services and DOD to improve the spare parts requirements determination process, in response to prior GAO report recommendations, have resulted in estimated cost savings of over $800 million during the past 5 years. Additional actions in process should result in further estimated savings of over $500 million.

  17. GAO-15-305, DOE Real Property, Better Data and a More Proactive Approach Needed to Facilitate Property Disposal

    Broader source: Energy.gov [DOE]

    GAO-15-305, DOE Real Property, Better Data and a More Proactive Approach Needed to Facilitate Property Disposal

  18. SPRU Removes High-Risk Radioactive Waste | Department of Energy

    Office of Environmental Management (EM)

    SPRU Removes High-Risk Radioactive Waste SPRU Removes High-Risk Radioactive Waste December 23, 2014 - 12:00pm Addthis A truck carrying the last two solidified liners from the SPRU ...

  19. General Accountability Office Report (GAO) final report entitled National Laboratories: DOE needs to Improve Oversight of Work performed for non-DOE Entities (GAO 14_78 October 2013).

    Broader source: Energy.gov [DOE]

    Recommendation 1 of GAO Report 14-78 directs DOE to, "Ensure compliance with the requirements in the Work for Others order for project approval." The basis for this recommendation was GAO's assertion that during interviews with DOE officials, 8 of 17 Site Office officials stated that DOE often accepted laboratory (contractor) provided justifications and determinations without taking steps to independently verify them.

  20. Eliminating High Risk Work at Hanford | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Eliminating High Risk Work at Hanford Eliminating High Risk Work at Hanford Presentation from the 2015 DOE National Cleanup Workshop by John Ciucci, President and CEO, CH2M HILL Plateau Remediation Company. Eliminating High Risk Work at Hanford (4.77 MB) More Documents & Publications 2013 Congressional Nuclear Cleanup Caucus Briefings 2014 Congressional Nuclear Cleanup Caucus Briefings 2014 Annual Workforce Analysis and Staffing Plan Report - Richland Operations Office

  1. Jie Gao > Sr. Electrochemist - Spectrum Brands > Center Alumni > The Energy

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Materials Center at Cornell Jie Gao Sr. Electrochemist - Spectrum Brands jiegaocn@gmail.com Jie was a former member of the Abruña Group as a postdoc. In May 2015, he joined Spectrum Brands as an electrochemist

  2. High-Impact, Low-Frequency Event Risk Report

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    nerc.com | www.doe.gov June 2010 High-Impact, Low-Frequency Event Risk to the North American Bulk Power System A Jointly-Commissioned Summary Report of the North American Electric Reliability Corporation and the U.S. Department of Energy's November 2009 Workshop About This Report High-Impact, Low-Frequency Event Risk to the North American Bulk Power System June 2010 2 About the High-Impact, Low-Frequency (HILF) Event Risk Effort The North American Electric Reliability Corporation (NERC) and the

  3. GAO; Venezuelan reforms do little to spark oil investiment by U. S. firms

    SciTech Connect (OSTI)

    Not Available

    1992-02-03

    This paper reports that Venezuela's 1991 foreign investment reforms did little to encourage U.S. oil companies to invest there despite the overall investment attractiveness of the country's oil sector, says the U.S. General Accounting Office. In a report to Congress, GAO noted Venezuela's oil production peaked in 1970, declined through 1985, and since then has increased by about 21% through 1990. The primary factors affecting continued increases in production through 1996 include Petroleos de Venezuela SA's ability to encourage investment capital, the cost of producing and refining heavy and extra heavy crude oil., and the level of production quotas imposed by the Organization of Petroleum Exporting Countries, of which Venezuela is a member. GAO noted Venezuela implemented policy reforms in 1991 to encourage some foreign and private investment petroleum related ventures. However, these reforms have not yet succeeded in attracting U.S. investment in oil exploration, production, or refining in Venezuela.

  4. Risk analysis for truck transportation of high consequence cargo.

    SciTech Connect (OSTI)

    Waters, Robert David

    2010-09-01

    The fixed facilities control everything they can to drive down risk. They control the environment, work processes, work pace and workers. The transportation sector drive the State and US highways with high kinetic energy and less-controllable risks such as: (1) other drivers (beginners, impaired, distracted, etc.); (2) other vehicles (tankers, hazmat, super-heavies); (3) road environments (bridges/tunnels/abutments/construction); and (4) degraded weather.

  5. High-Impact, Low-Frequency Risk to the North American Bulk Power...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    High-Impact, Low-Frequency Risk to the North American Bulk Power System (June 2010) High-Impact, Low-Frequency Risk to the North American Bulk Power System (June 2010) A ...

  6. GAO Cost Estimating and Assessment Guide Twelve Steps of a High-Quality Cost Estimating Process

    Office of Environmental Management (EM)

    - REVISED References: Federal Acquisition Regulation (FAR) Parts and Subparts  2.1 - Definitions  8.4 - Federal supply schedules  9.4 - Debarment, suspension, and ineligibility  9.6 - Contractor teaming arrangements  15.4 - Contract pricing  17.5 - Interagency acquisitions  31 - Contract cost principles and procedures  32 - Contract financing  34.2 - Earned value management system  42 - Contract administration and audit services  42.15 - Contractor performance

  7. Assessing ecological risks within a highly industrialized estuary

    SciTech Connect (OSTI)

    Bonnevie, N.L.; Iannuzzi, T.J.; Harman, C.H.

    1995-12-31

    Ecological assessment (EA) was conducted for a landfill located along an industrialized river within the NY/NJ Harbor Estuary. This estuary has been subjected to intense industrial and urban development throughout the past two centuries, resulting in alterations to the Site and regional ecology. For these reasons, consideration was given to the local and regional setting, and the relatively low quantity and degraded quality of habitats that exist in proximity to the Site. The EA focused on two ecological receptor groups: (1) aquatic receptors (i.e., benthic invertebrates and small forage fish) exposed primarily through direct contact with sediments and surface water; and (2) piscivorous species (i.e., great blue heron) for whom exposure is the result of trophic transfer through dietary intakes. Estimates of accumulation in prey species of the great blue heron were derived using a simplified food web model to predict trophic transfer. The primary chemicals of potential ecological concern (COPEC) included arsenic, selenium, mercury, as well as PCBs. Based on the results of this assessment, risk to piscivorous wildlife are very low; derived hazard quotients (HQ) were below one for all COPEC. HQ greater than one were observed for direct exposures to aquatic receptors, however, the HQ determined for exposures at the Site were generally within the range of those reported for sediments and surface waters throughout the NY/NJ Harbor Estuary. In addition, numerous non-chemical stressors were identified that likely significantly affect the health and abundance of aquatic organisms. For these reasons, the Site was determined not to contribute an increased risk to ecological receptors above a regional level.

  8. Merging high resolution geophysical and geochemical surveys to reduce exploration risk at Glass Buttes, Oregon

    Broader source: Energy.gov [DOE]

    DOE Geothermal Technologies Peer Review - 2010. The primary objective of this project is to combine a suite of high resolution geophysical and geochemical techniques to reduce exploration risk by characterizing hydrothermal alteration, fault geometries and relationships.

  9. A Procedure for Using FMECA to Assess High-Risk Healthcare Processes (PSAM-0266)

    SciTech Connect (OSTI)

    Coles, Garill A.

    2006-01-12

    An applied research firm collaborated with staff at three community hospitals to apply Failure Mode Effects and Criticality Analysis (FMECA) to reduce risk from several high-risk healthcare processes. This included medication ordering and delivery, X-Ray labelling, blood transfusion, prevention of wrong site surgery, prevention of patient falls and antibiotic IV administration. The collaborating team developed its own successful FMECA approach and an eight-step procedure to gather data, conduct FMECA sessions, identify medical process weaknesses and risk reduction measures.

  10. High-Impact, Low-Frequency Risk to the North American Bulk Power System

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    (June 2010) | Department of Energy High-Impact, Low-Frequency Risk to the North American Bulk Power System (June 2010) High-Impact, Low-Frequency Risk to the North American Bulk Power System (June 2010) A Jointly-Commissioned Summary Report of the North American Electric Reliability Corporation and the U.S. Department of Energy's November 2009 Workshop. The North American Electric Reliability Corporation (NERC) and the U.S. Department of Energy (DOE) partnered in July of 2009 on an effort to

  11. High-Dose-Rate Brachytherapy Alone for Localized Prostate Cancer in Patients at Moderate or High Risk of Biochemical Recurrence

    SciTech Connect (OSTI)

    Hoskin, Peter; Rojas, Ana; Lowe, Gerry; Bryant, Linda; Ostler, Peter; Hughes, Rob; Milner, Jessica; Cladd, Helen

    2012-03-15

    Purpose: To evaluate genitourinary (GU) and gastrointestinal (GI) morbidity and biochemical control of disease in patients with localized prostate adenocarcinoma treated with escalating doses per fraction of high-dose rate brachytherapy alone. Methods and Materials: A total of 197 patients were treated with 34 Gy in four fractions, 36 Gy in four fractions, 31.5 Gy in three fractions, or 26 Gy in two fractions. Median follow-up times were 60, 54, 36, and 6 months, respectively. Results: Incidence of early Grade {>=} 3 GU morbidity was 3% to 7%, and Grade 4 was 0% to 4%. During the first 12 weeks, the highest mean International Prostate Symptom Score (IPSS) value was 14, and between 6 months and 5 years it was 8. Grade 3 or 4 early GI morbidity was not observed. The 3-year actuarial rate of Grade 3 GU was 3% to 16%, and was 3% to 7% for strictures requiring surgery (4-year rate). An incidence of 1% Grade 3 GI events was seen at 3 years. Late Grade 4 GU or GI events were not observed. At 3 years, 99% of patients with intermediate-risk and 91% with high-risk disease were free of biochemical relapse (log-rank p = 0.02). Conclusions: There was no significant difference in urinary and rectal morbidity between schedules. Biochemical control of disease in patients with intermediate and high risk of relapse was good.

  12. High-Impact, Low-Frequency Risk to the North American Bulk Power System

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    (June 2010) | Department of Energy Impact, Low-Frequency Risk to the North American Bulk Power System (June 2010) High-Impact, Low-Frequency Risk to the North American Bulk Power System (June 2010) A Jointly-Commissioned Summary Report of the North American Electric Reliability Corporation and the U.S. Department of Energy's November 2009 Workshop. The North American Electric Reliability Corporation (NERC) and the U.S. Department of Energy (DOE) partnered in July of 2009 on an effort to

  13. Risk management & organizational uncertainty implications for the assessment of high consequence organizations

    SciTech Connect (OSTI)

    Bennett, C.T.

    1995-02-23

    Post hoc analyses have demonstrated clearly that macro-system, organizational processes have played important roles in such major catastrophes as Three Mile Island, Bhopal, Exxon Valdez, Chernobyl, and Piper Alpha. How can managers of such high-consequence organizations as nuclear power plants and nuclear explosives handling facilities be sure that similar macro-system processes are not operating in their plants? To date, macro-system effects have not been integrated into risk assessments. Part of the reason for not using macro-system analyses to assess risk may be the impression that standard organizational measurement tools do not provide hard data that can be managed effectively. In this paper, I argue that organizational dimensions, like those in ISO 9000, can be quantified and integrated into standard risk assessments.

  14. GAO-12-645, FEDERAL REAL PROPERTY: National Strategy and Better...

    Broader source: Energy.gov (indexed) [DOE]

    employee work space to use space more efficiently. However, they still face long-standing challenges to managing these properties, including the high cost of property...

  15. Likelihood of Bone Recurrence in Prior Sites of Metastasis in Patients With High-Risk Neuroblastoma

    SciTech Connect (OSTI)

    Polishchuk, Alexei L.; Li, Richard; Little, Anthony; Hawkins, Randall A.; Hamilton, Jeffrey; Lau, Michael; Tran, Hung Chi; Lemons, Richard S.; Matthay, Katherine K.; DuBois, Steven G.; and others

    2014-07-15

    Purpose/Objectives: Despite recent improvements in outcomes, 40% of children with high-risk neuroblastoma will experience relapse, facing a guarded prognosis for long-term cure. Whether recurrences are at new sites or sites of original disease may guide decision making during initial therapy. Methods and Materials: Eligible patients were retrospectively identified from institutional databases at first metastatic relapse of high-risk neuroblastoma. Included patients had disease involving metaiodobenzylguanidine (MIBG)-avid metastatic sites at diagnosis and first relapse, achieved a complete or partial response with no more than one residual MIBG-avid site before first relapse, and received no total body irradiation or therapy with {sup 131}I-MIBG before first relapse. Anatomically defined metastatic sites were tracked from diagnosis through first relapse to determine tendency of disease to recur at previously involved versus uninvolved sites and to assess whether this pattern was influenced by site irradiation. Results: Of 159 MIBG-avid metastatic sites identified among 43 patients at first relapse, 131 (82.4%) overlapped anatomically with the set of 525 sites present at diagnosis. This distribution was similar for bone sites, but patterns of relapse were more varied for the smaller subset of soft tissue metastases. Among all metastatic sites at diagnosis in our subsequently relapsed patient cohort, only 3 of 19 irradiated sites (15.8%) recurred as compared with 128 of 506 (25.3%) unirradiated sites. Conclusions: Metastatic bone relapse in neuroblastoma usually occurs at anatomic sites of previous disease. Metastatic sites identified at diagnosis that did not receive radiation during frontline therapy appeared to have a higher risk of involvement at first relapse relative to previously irradiated metastatic sites. These observations support the current paradigm of irradiating metastases that persist after induction chemotherapy in high-risk patients. Furthermore

  16. Preparation and composition of superconducting copper oxides based on Ga-O layers

    DOE Patents [OSTI]

    Dabrowski, Bogdan; Vaughey, J. T.; Poeppelmeier, Kenneth R.

    1994-01-01

    A high temperature superconducting material with the general formula GaSr.sub.2 Ln.sub.1-x MxCu.sub.2 O.sub.7.+-.w wherein Ln is selected from the group consisting of La, Ce, Pt, Sm, Eu, Gd, Tb, Dy, Ho, Er, Tm, Yb and Y and M is selected from the group consisting of Ca and Sr, 0.2.ltoreq.x.ltoreq.0.4 and w is a small fraction of one. A method of preparing this high temperature superconducting material is provided which includes heating and cooling a mixture to produce a crystalline material which is subsequently fired, ground and annealed at high pressure and temperature in oxygen to establish superconductivity.

  17. Preparation and composition of superconducting copper oxides based on Ga-O layers

    DOE Patents [OSTI]

    Dabrowski, B.; Vaughey, J.T.; Poeppelmeier, K.R.

    1994-12-20

    A high temperature superconducting material with the general formula GaSr[sub 2]Ln[sub 1[minus]x]M[sub x]Cu[sub 2]O[sub 7[+-]w] wherein Ln is selected from the group consisting of La, Ce, Pt, Sm, Eu, Gd, Tb, Dy, Ho, Er, Tm, Yb and Y and M is selected from the group consisting of C and Sr, 0.2[<=]x[<=]0.4 and w is a small fraction of one. A method of preparing this high temperature superconducting material is provided which includes heating and cooling a mixture to produce a crystalline material which is subsequently fired, ground and annealed at high pressure and temperature in oxygen to establish superconductivity. 14 figures.

  18. Chernobyl nuclear catastrophe and the high risk potential for mental retardation

    SciTech Connect (OSTI)

    Holowinsky, I.Z. )

    1993-02-01

    The nuclear explosion at Chernobyl nuclear reactor on April 26, 1986, continues to have wide political, social, and medical ramifications. Hot debris from the Chernobyl reactor covered an area of more than 5,000 square kilometers with nearly 20 million curies of radionuclides. Eleven regions with a population of nearly 17 million people, of whom 2.5 million were children below the age of 5 years, suffered some degree of radioactive contamination. These children are currently of elementary school age. One of the tragedies of the explosion is that thousands of these children are at high risk for mental retardation and learning disorders.

  19. Clinical Application of High-Dose, Image-Guided Intensity-Modulated Radiotherapy in High-Risk Prostate Cancer

    SciTech Connect (OSTI)

    Bayley, Andrew, E-mail: Andrew.Bayley@rmp.uhn.on.c [Radiation Medicine Program, Princess Margaret Hospital, Toronto, ON (Canada) and Department of Radiation Oncology, University of Toronto, Toronto, ON (Canada); Rosewall, Tara; Craig, Tim; Bristow, Rob; Chung, Peter; Gospodarowicz, Mary; Menard, Cynthia; Milosevic, Michael; Warde, Padraig; Catton, Charles [Radiation Medicine Program, Princess Margaret Hospital, Toronto, ON (Canada) and Department of Radiation Oncology, University of Toronto, Toronto, ON (Canada)

    2010-06-01

    Purpose: To report the feasibility and early toxicity of dose-escalated image-guided IMRT to the pelvic lymph nodes (LN), prostate (P), and seminal vesicles (SV). Methods and Materials: A total of 103 high-risk prostate cancer patients received two-phase, dose-escalated, image-guided IMRT with 3 years of androgen deprivation therapy. Clinical target volumes (CTVs) were delineated using computed tomography/magnetic resonance co-registration and included the prostate, portions of the SV, and the LN. Planning target volume margins (PTV) used were as follows: P (10 mm, 7 mm posteriorly), SV (10 mm), and LN (5 mm). Organs at risk (OaR) were the rectal and bladder walls, femoral heads, and large and small bowel. The IMRT was planned with an intended dose of 55.1 Gy in 29 fractions to all CTVs (Phase 1), with P+SV consecutive boost of 24.7 Gy in 13 fractions. Daily online image guidance was performed using bony landmarks and intraprostatic markers. Feasibility criteria included delivery of intended doses in 80% of patients, 95% of CTV displacements incorporated within PTV during Phase 1, and acute toxicity rate comparable to that of lower-dose pelvic techniques. Results: A total of 91 patients (88%) received the total prescription dose. All patients received at least 72 Gy. In Phase 1, 63 patients (61%) received the intended 55.1 Gy, whereas 87% of patients received at least 50 Gy. Dose reductions were caused by small bowel and rectal wall constraints. All CTVs received the planned dose in >95% of treatment fractions. There were no Radiation Therapy Oncology Group acute toxicities greater than Grade 3, although there were five incidences equivalent to Grade 3 within a median follow-up of 23 months. Conclusion: These results suggest that dose escalation to the PLN+P+SV using IMRT is feasible, with acceptable rates of acute toxicity.

  20. Risk perception on management of nuclear high-level and transuranic waste storage

    SciTech Connect (OSTI)

    Dees, L.A.

    1994-08-15

    The Department of Energy`s program for disposing of nuclear High-Level Waste (HLW) and transuranic (TRU) waste has been impeded by overwhelming political opposition fueled by public perceptions of actual risk. Analysis of these perceptions shows them to be deeply rooted in images of fear and dread that have been present since the discovery of radioactivity. The development and use of nuclear weapons linked these images to reality and the mishandling of radioactive waste from the nations military weapons facilities has contributed toward creating a state of distrust that cannot be erased quickly or easily. In addition, the analysis indicates that even the highly educated technical community is not well informed on the latest technology involved with nuclear HLW and TRU waste disposal. It is not surprising then, that the general public feels uncomfortable with DOE`s management plans for with nuclear HLW and TRU waste disposal. Postponing the permanent geologic repository and use of Monitored Retrievable Storage (MRS) would provide the time necessary for difficult social and political issues to be resolved. It would also allow time for the public to become better educated if DOE chooses to become proactive.

  1. Nuclear import strategies of high-risk HPV18 L2 minor capsid protein

    SciTech Connect (OSTI)

    Klucevsek, K.; Daley, J.; Darshan, M.S.; Bordeaux, J.; Moroianu, J. . E-mail: moroianu@bc.edu

    2006-08-15

    We have investigated the nuclear import strategies of high-risk HPV18 L2 minor capsid protein. HPV18 L2 interacts with Kap {alpha}{sub 2} adapter, and Kap {beta}{sub 2} and Kap {beta}{sub 3} nuclear import receptors. Moreover, binding of RanGTP to either Kap {beta}{sub 2} or Kap {beta}{sub 3} inhibits their interaction with L2, suggesting that these Kap {beta}/L2 complexes are import competent. Mapping studies show that HPV18 L2 contains two NLSs: in the N-terminus (nNLS) and in the C-terminus (cNLS), both of which can independently mediate nuclear import. Both nNLS and cNLS form a complex with Kap {alpha}{sub 2}{beta}{sub 1} heterodimer and mediate nuclear import via a classical pathway. The nNLS is also essential for the interaction of HPV18 L2 with Kap {beta}{sub 2} and Kap {beta}{sub 3}. Interestingly, both nNLS and cNLS interact with the viral DNA and this DNA binding occurs without nucleotide sequence specificity. Together, the data suggest that HPV18 L2 can interact via its NLSs with several Kaps and the viral DNA and may enter the nucleus via multiple import pathways mediated by Kap {alpha}{sub 2}{beta}{sub 1} heterodimers, Kap {beta}{sub 2} and Kap {beta}{sub 3}.

  2. High-Energy, Low-Frequency Risk to the North American Bulk Power...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    In August, NERC formed a steering committee made up of industry and risk experts to lead the development of an initial workshop on the subject, chaired by Scott Moore, VP ...

  3. High-Risk Components Removed from K-25’s Tc-99 Area

    Broader source: Energy.gov [DOE]

    Oak Ridge's EM program removes one of the highest risk components remaining in K-25 building with the successful crane removal of five components known as NaF traps.

  4. Framework for Modeling High-Impact, Low-Frequency Power Grid Events to Support Risk-Informed Decisions

    SciTech Connect (OSTI)

    Veeramany, Arun; Unwin, Stephen D.; Coles, Garill A.; Dagle, Jeffery E.; Millard, W. David; Yao, Juan; Glantz, Clifford S.; Gourisetti, Sri Nikhil Gup

    2015-12-03

    Natural and man-made hazardous events resulting in loss of grid infrastructure assets challenge the electric power grid’s security and resilience. However, the planning and allocation of appropriate contingency resources for such events requires an understanding of their likelihood and the extent of their potential impact. Where these events are of low likelihood, a risk-informed perspective on planning can be problematic as there exists an insufficient statistical basis to directly estimate the probabilities and consequences of their occurrence. Since risk-informed decisions rely on such knowledge, a basis for modeling the risk associated with high-impact low frequency events (HILFs) is essential. Insights from such a model can inform where resources are most rationally and effectively expended. The present effort is focused on development of a HILF risk assessment framework. Such a framework is intended to provide the conceptual and overarching technical basis for the development of HILF risk models that can inform decision makers across numerous stakeholder sectors. The North American Electric Reliability Corporation (NERC) 2014 Standard TPL-001-4 considers severe events for transmission reliability planning, but does not address events of such severity that they have the potential to fail a substantial fraction of grid assets over a region, such as geomagnetic disturbances (GMD), extreme seismic events, and coordinated cyber-physical attacks. These are beyond current planning guidelines. As noted, the risks associated with such events cannot be statistically estimated based on historic experience; however, there does exist a stable of risk modeling techniques for rare events that have proven of value across a wide range of engineering application domains. There is an active and growing interest in evaluating the value of risk management techniques in the State transmission planning and emergency response communities, some of this interest in the context of

  5. Merging high resolution geophysical and geochemical surveys to reduce exploration risk at glass buttes, Oregon

    SciTech Connect (OSTI)

    Walsh, Patrick; Fercho, Steven; Perkin, Doug; Martini, Brigette; Boshmann, Darrick

    2015-06-01

    The engineering and studies phase of the Glass Buttes project was aimed at reducing risk during the early stages of geothermal project development. The project’s inclusion of high resolution geophysical and geochemical surveys allowed Ormat to evaluate the value of these surveys both independently and in combination to quantify the most valuable course of action for exploration in an area where structure, permeability, and temperature are the most pressing questions. The sizes of the thermal anomalies at Glass Buttes are unusually large. Over the course of Phase I Ormat acquired high resolution LIDAR data to accurately map fault manifestations at the surface and collected detailed gravity and aeromagnetic surveys to map subsurface structural features. In addition, Ormat collected airborne hyperspectral data to assist with mapping the rock petrology and mineral alteration assemblages along Glass Buttes faults and magnetotelluric (MT) survey to try to better constrain the structures at depth. Direct and indirect identification of alteration assemblages reveal not only the geochemical character and temperature of the causative hydrothermal fluids but can also constrain areas of upflow along specific fault segments. All five datasets were merged along with subsurface lithologies and temperatures to predict the most likely locations for high permeability and hot fluids. The Glass Buttes temperature anomalies include 2 areas, totaling 60 km2 (23 mi2) of measured temperature gradients over 165° C/km (10° F/100ft). The Midnight Point temperature anomaly includes the Strat-1 well with 90°C (194 °F) at 603 m (1981 ft) with a 164 °C/km (10°F/100ft) temperature gradient at bottom hole and the GB-18 well with 71°C (160 °F) at 396 m (1300 ft) with a 182°C/km (11°F/100ft) gradient. The primary area of alteration and elevated temperature occurs near major fault intersections associated with Brothers Fault Zone and Basin and Range systems. Evidence for faulting is

  6. MRI screening for breast cancer in women at high risk; is the Australian breast MRI screening access program addressing the needs of women at high risk of breast cancer?

    SciTech Connect (OSTI)

    Schenberg, Tess; Mitchell, Gillian; Taylor, Donna; Saunders, Christobel

    2015-09-15

    Breast magnetic resonance imaging (MRI) screening of women under 50 years old at high familial risk of breast cancer was given interim funding by Medicare in 2009 on the basis that a review would be undertaken. An updated literature review has been undertaken by the Medical Services Advisory Committee but there has been no assessment of the quality of the screening or other screening outcomes. This review examines the evidence basis of breast MRI screening and how this fits within an Australian context with the purpose of informing future modifications to the provision of Medicare-funded breast MRI screening in Australia. Issues discussed will include selection of high-risk women, the options for MRI screening frequency and measuring the outcomes of screening.

  7. Study of Risk Assessment Programs at Federal Agencies and Commercial Industry Related to the Conduct or Regulation of High Hazard Operations

    SciTech Connect (OSTI)

    Bari, R.; Rosenbloom, S.; O'Brien, J.

    2011-03-13

    In the Department of Energy (DOE) Implementation Plan (IP) for Defense Nuclear Facilities Safety Board's Recommendation 2009-1, the DOE committed to studying the use of quantitative risk assessment methodologies at government agencies and industry. This study consisted of document reviews and interviews of senior management and risk assessment staff at six organizations. Data were collected and analyzed on risk assessment applications, risk assessment tools, and controls and infrastructure supporting the correct usage of risk assessment and risk management tools. The study found that the agencies were in different degrees of maturity in the use of risk assessment to support the analysis of high hazard operations and to support decisions related to these operations. Agencies did not share a simple, 'one size fits all' approach to tools, controls, and infrastructure needs. The agencies recognized that flexibility was warranted to allow use of risk assessment tools in a manner that is commensurate with the complexity of the application. The study also found that, even with the lack of some data, agencies application of the risk analysis structured approach could provide useful insights such as potential system vulnerabilities. This study, in combination with a companion study of risk assessment programs in the DOE Offices involved in high hazard operations, is being used to determine the nature and type of controls and infrastructure needed to support risk assessments at the DOE.

  8. High Power Performance Lithium Ion Battery - Energy Innovation Portal

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Energy Storage Energy Storage Advanced Materials Advanced Materials Find More Like This Return to Search High Power Performance Lithium Ion Battery Lawrence Berkeley National Laboratory Contact LBL About This Technology Hybrid Pulse Power Characterization Test (HPPC) results for 3 coin cells of various AB:PVDF ratios. Hybrid Pulse Power Characterization Test (HPPC) results for 3 coin cells of various AB:PVDF ratios. Technology Marketing SummaryGao Liu and colleagues at Berkeley Lab have

  9. Impact of High Solar Penetration in the Western Interconnection

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Impact of High Solar Penetration in the Western Interconnection Debra Lew National Renewable Energy Laboratory Nicholas Miller, Kara Clark, Gary Jordan, and Zhi Gao GE Energy Technical Report NREL/TP-5500-49667 December 2010 NREL is a national laboratory of the U.S. Department of Energy, Office of Energy Efficiency & Renewable Energy, operated by the Alliance for Sustainable Energy, LLC. National Renewable Energy Laboratory 1617 Cole Boulevard Golden, Colorado 80401 303-275-3000 *

  10. Risk Level Based Management System: a control banding model for occupational health and safety risk management in a highly regulated environment

    SciTech Connect (OSTI)

    Zalk, D; Kamerzell, R; Paik, S; Kapp, J; Harrington, D; Swuste, P

    2009-05-27

    The Risk Level Based Management System (RLBMS) is an occupational risk management (ORM) model that focuses occupational safety, hygeiene, and health (OSHH) resources on the highest risk procedures at work. This article demonstrates the model's simplicity through an implementation within a heavily regulated research institution. The model utilizes control banding strategies with a stratification of four risk levels (RLs) for many commonly performed maintenance and support activities, characterizing risk consistently for comparable tasks. RLBMS creates an auditable tracking of activities, maximizes OSHH professional field time, and standardizes documentation and control commensurate to a given task's RL. Validation of RLs and their exposure control effectiveness is collected in a traditional quantitative collection regime for regulatory auditing. However, qualitative risk assessment methods are also used within this validation process. Participatory approaches are used throughout the RLBMS process. Workers are involved in all phases of building, maintaining, and improving this model. This work participation also improves the implementation of established controls.

  11. Improved Survival Endpoints With Adjuvant Radiation Treatment in Patients With High-Risk Early-Stage Endometrial Carcinoma

    SciTech Connect (OSTI)

    Elshaikh, Mohamed A.; Vance, Sean; Suri, Jaipreet S.; Mahan, Meredith; Munkarah, Adnan

    2014-02-01

    Purpose/Objective(s): To determine the impact of adjuvant radiation treatment (RT) on recurrence-free survival (RFS), disease-specific survival (DSS), and overall survival (OS) in patients with high-risk 2009 International Federation of Gynecology and Obstetrics stage I-II endometrial carcinoma. Methods and Materials: We identified 382 patients with high-risk EC who underwent hysterectomy. RFS, DSS, and OS were calculated from the date of hysterectomy by use of the Kaplan-Meier method. Cox regression modeling was used to explore the risks associated with various factors on survival endpoints. Results: The median follow-up time for the study cohort was 5.4 years. The median age was 71 years. All patients underwent hysterectomy and salpingo-oophorectomy, 93% had peritoneal cytology, and 85% underwent lymphadenectomy. Patients with endometrioid histology constituted 72% of the study cohort, serous in 16%, clear cell in 7%, and mixed histology in 4%. Twenty-three percent of patients had stage II disease. Adjuvant management included RT alone in 220 patients (57%), chemotherapy alone in 25 patients (7%), and chemoradiation therapy in 27 patients (7%); 110 patients (29%) were treated with close surveillance. The 5-year RFS, DSS, and OS were 76%, 88%, and 73%, respectively. On multivariate analysis, adjuvant RT was a significant predictor of RFS (P<.001) DSS (P<.001), and OS (P=.017). Lymphovascular space involvement was a significant predictor of RFS and DSS (P<.001). High tumor grade was a significant predictor for RFS (P=.038) and DSS (P=.025). Involvement of the lower uterine segment was also a predictor of RFS (P=.049). Age at diagnosis and lymphovascular space involvement were significant predictors of OS: P<.001 and P=.002, respectively. Conclusion: In the treatment of patients with high-risk features, our study suggests that adjuvant RT significantly improves recurrence-free, disease-specific, and overall survival in patients with early-stage endometrial carcinoma

  12. Causes of Mortality After Dose-Escalated Radiation Therapy and Androgen Deprivation for High-Risk Prostate Cancer

    SciTech Connect (OSTI)

    Tendulkar, Rahul D.; Hunter, Grant K.; Reddy, Chandana A.; Stephans, Kevin L.; Ciezki, Jay P.; Abdel-Wahab, May; Stephenson, Andrew J.; Klein, Eric A.; Mahadevan, Arul; Kupelian, Patrick A.

    2013-09-01

    Purpose: Men with high-risk prostate cancer have other competing causes of mortality; however, current risk stratification schema do not account for comorbidities. We aim to identify the causes of death and factors predictive for mortality in this population. Methods and Materials: A total of 660 patients with high-risk prostate cancer were treated with definitive high-dose external beam radiation therapy (?74 Gy) and androgen deprivation (AD) between 1996 and 2009 at a single institution. Cox proportional hazards regression analysis was conducted to determine factors predictive of survival. Results: The median radiation dose was 78 Gy, median duration of AD was 6 months, and median follow-up was 74 months. The 10-year overall survival (OS) was 60.6%. Prostate cancer was the leading single cause of death, with 10-year mortality of 14.1% (95% CI 10.7-17.6), compared with other cancers (8.4%, 95% CI 5.7-11.1), cardiovascular disease (7.3%, 95% CI 4.7-9.9), and all other causes (10.4%, 95% CI 7.2-13.6). On multivariate analysis, older age (HR 1.55, P=.002) and Charlson comorbidity index score (CS) ?1 (HR 2.20, P<.0001) were significant factors predictive of OS, whereas Gleason score, T stage, prostate-specific antigen, duration of AD, radiation dose, smoking history, and body mass index were not. Men younger than 70 years of age with CS = 0 were more likely to die of prostate cancer than any other cause, whereas older men or those with CS ?1 more commonly suffered non-prostate cancer death. The cumulative incidences of prostate cancer-specific mortality were similar regardless of age or comorbidities (P=.60). Conclusions: Men with high-risk prostate cancer are more likely to die of causes other than prostate cancer, except for the subgroup of men younger than 70 years of age without comorbidities. Only older age and presence of comorbidities significantly predicted for OS, whereas prostate cancer- and treatment-related factors did not.

  13. Occult Breast Cancer: Scintimammography with High-Resolution Breast-specific Gamma Camera in Women at High Risk for Breast Cancer

    SciTech Connect (OSTI)

    Rachel F. Brem; Jocelyn A. Rapelyea; , Gilat Zisman; Kevin Mohtashemi; Joyce Raub; Christine B. Teal; Stan Majewski; Benjamin L. Welch

    2005-08-01

    To prospectively evaluate a high-resolution breast-specific gamma camera for depicting occult breast cancer in women at high risk for breast cancer but with normal mammographic and physical examination findings. MATERIALS AND METHODS: Institutional Review Board approval and informed consent were obtained. The study was HIPAA compliant. Ninety-four high-risk women (age range, 36-78 years; mean, 55 years) with normal mammographic (Breast Imaging Reporting and Data System [BI-RADS] 1 or 2) and physical examination findings were evaluated with scintimammography. After injection with 25-30 mCi (925-1110 MBq) of technetium 99m sestamibi, patients were imaged with a high-resolution small-field-of-view breast-specific gamma camera in craniocaudal and mediolateral oblique projections. Scintimammograms were prospectively classified according to focal radiotracer uptake as normal (score of 1), with no focal or diffuse uptake; benign (score of 2), with minimal patchy uptake; probably benign (score of 3), with scattered patchy uptake; probably abnormal (score of 4), with mild focal radiotracer uptake; and abnormal (score of 5), with marked focal radiotracer uptake. Mammographic breast density was categorized according to BI-RADS criteria. Patients with normal scintimammograms (scores of 1, 2, or 3) were followed up for 1 year with an annual mammogram, physical examination, and repeat scintimammography. Patients with abnormal scintimammograms (scores of 4 or 5) underwent ultrasonography (US), and those with focal hypoechoic lesions underwent biopsy. If no lesion was found during US, patients were followed up with scintimammography. Specific pathologic findings were compared with scintimammographic findings. RESULTS: Of 94 women, 78 (83%) had normal scintimammograms (score of 1, 2, or 3) at initial examination and 16 (17%) had abnormal scintimammograms (score of 4 or 5). Fourteen (88%) of the 16 patients had either benign findings at biopsy or no focal abnormality at US; in two

  14. Accelerating Clean-up at Savannah River

    Office of Environmental Management (EM)

    S. Department of Energy April 27, 2010 2 Outline of Presentation * Background - GAO High-Risk List - Root Cause Analysis (RCA) and Corrective Action Plan (CAP) * Current Status of...

  15. Risk-based high-throughput chemical screening and prioritization using exposure models and in vitro bioactivity assays

    SciTech Connect (OSTI)

    Shin, Hyeong -Moo; Ernstoff, Alexi; Arnot, Jon A.; Wetmore, Barbara A.; Csiszar, Susan A.; Fantke, Peter; Zhang, Xianming; McKone, Thomas E.; Jolliet, Olivier; Bennett, Deborah H.

    2015-05-01

    We present a risk-based high-throughput screening (HTS) method to identify chemicals for potential health concerns or for which additional information is needed. The method is applied to 180 organic chemicals as a case study. We first obtain information on how the chemical is used and identify relevant use scenarios (e.g., dermal application, indoor emissions). For each chemical and use scenario, exposure models are then used to calculate a chemical intake fraction, or a product intake fraction, accounting for chemical properties and the exposed population. We then combine these intake fractions with use scenario-specific estimates of chemical quantity to calculate daily intake rates (iR; mg/kg/day). These intake rates are compared to oral equivalent doses (OED; mg/kg/day), calculated from a suite of ToxCast in vitro bioactivity assays using in vitro-to-in vivo extrapolation and reverse dosimetry. Bioactivity quotients (BQs) are calculated as iR/OED to obtain estimates of potential impact associated with each relevant use scenario. Of the 180 chemicals considered, 38 had maximum iRs exceeding minimum OEDs (i.e., BQs > 1). For most of these compounds, exposures are associated with direct intake, food/oral contact, or dermal exposure. The method provides high-throughput estimates of exposure and important input for decision makers to identify chemicals of concern for further evaluation with additional information or more refined models.

  16. Risk-based high-throughput chemical screening and prioritization using exposure models and in vitro bioactivity assays

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Shin, Hyeong -Moo; Ernstoff, Alexi; Arnot, Jon A.; Wetmore, Barbara A.; Csiszar, Susan A.; Fantke, Peter; Zhang, Xianming; McKone, Thomas E.; Jolliet, Olivier; Bennett, Deborah H.

    2015-05-01

    We present a risk-based high-throughput screening (HTS) method to identify chemicals for potential health concerns or for which additional information is needed. The method is applied to 180 organic chemicals as a case study. We first obtain information on how the chemical is used and identify relevant use scenarios (e.g., dermal application, indoor emissions). For each chemical and use scenario, exposure models are then used to calculate a chemical intake fraction, or a product intake fraction, accounting for chemical properties and the exposed population. We then combine these intake fractions with use scenario-specific estimates of chemical quantity to calculate dailymore » intake rates (iR; mg/kg/day). These intake rates are compared to oral equivalent doses (OED; mg/kg/day), calculated from a suite of ToxCast in vitro bioactivity assays using in vitro-to-in vivo extrapolation and reverse dosimetry. Bioactivity quotients (BQs) are calculated as iR/OED to obtain estimates of potential impact associated with each relevant use scenario. Of the 180 chemicals considered, 38 had maximum iRs exceeding minimum OEDs (i.e., BQs > 1). For most of these compounds, exposures are associated with direct intake, food/oral contact, or dermal exposure. The method provides high-throughput estimates of exposure and important input for decision makers to identify chemicals of concern for further evaluation with additional information or more refined models.« less

  17. High Risk Material Studies

    Broader source: Energy.gov [DOE]

    Spent Fuel Working Group Report on inventory and storage of the Department's spent nuclear fuel and other reactor irradiated nuclear materials and their environmental, safety and health vulnerabilities.

  18. High Risk Plan

    Broader source: Energy.gov (indexed) [DOE]

    ... FY10 contracts include: Bank Card, Software & maintenance; ground fuels; travel, RSA tokens; lab equip & supplies; glasses; and, staff augmentation. FY11 adds: Industrial supplies; ...

  19. Long-Term Efficacy and Toxicity of Low-Dose-Rate {sup 125}I Prostate Brachytherapy as Monotherapy in Low-, Intermediate-, and High-Risk Prostate Cancer

    SciTech Connect (OSTI)

    Kittel, Jeffrey A.; Reddy, Chandana A.; Smith, Kristin L.; Stephans, Kevin L.; Tendulkar, Rahul D.; Ulchaker, James; Angermeier, Kenneth; Campbell, Steven; Stephenson, Andrew; Klein, Eric A.; Wilkinson, D. Allan; Ciezki, Jay P.

    2015-07-15

    Purpose/Objectives: To report long-term efficacy and toxicity for a single-institution cohort of patients treated with low-dose-rate prostate brachytherapy permanent implant (PI) monotherapy. Methods and Materials: From 1996 to 2007, 1989 patients with low-risk (61.3%), intermediate-risk (29.8%), high-intermediate-risk (4.5%), and high-risk prostate cancer (4.4%) were treated with PI and followed up prospectively in a registry. All patients were treated with {sup 125}I monotherapy to 144 Gy. Late toxicity was coded retrospectively according to a modified Common Terminology Criteria for Adverse Events 4.0 scale. The rates of biochemical relapse-free survival (bRFS), distant metastasis-free survival (DMFS), overall survival (OS), and prostate cancer–specific mortality (PCSM) were calculated. We identified factors associated with late grade ≥3 genitourinary (GU) and gastrointestinal (GI) toxicity, bRFS, DMFS, OS, PCSM, and incontinence. Results: The median age of the patients was 67 years, and the median overall and prostate-specific antigen follow-up times were 6.8 years and 5.8 years, respectively. The overall 5-year rates for bRFS, DMFS, OS, and PCSM were 91.9%, 97.8%, 93.7%, and 0.71%, respectively. The 10-year rates were 81.5%, 91.5%, 76.1%, and 2.5%, respectively. The overall rates of late grade ≥3 GU and GI toxicity were 7.6% and 0.8%, respectively. On multivariable analysis, age and prostate length were significantly associated with increased risk of late grade ≥3 GU toxicity. The risk of incontinence was highly correlated with both pre-PI and post-PI transurethral resection of the prostate. Conclusions: Prostate brachytherapy as monotherapy is an effective treatment for low-risk and low-intermediate-risk prostate cancer and appears promising as a treatment for high-intermediate-risk and high-risk prostate cancer. Significant long-term toxicities are rare when brachytherapy is performed as monotherapy.

  20. Correlation between Ga-O signature and midgap states at the Al{sub 2}O{sub 3}/In{sub 0.53}Ga{sub 0.47}As interface

    SciTech Connect (OSTI)

    Krylov, Igor; Gavrilov, Arkady; Eizenberg, Moshe; Ritter, Dan

    2012-08-06

    Al{sub 2}O{sub 3}/In{sub 0.53}Ga{sub 0.47}As gate stacks were fabricated using different concentrations of NH{sub 4}OH as a pre-deposition treatment. Increased NH{sub 4}OH concentrations significantly reduced the C-V weak inversion hump and the measured near midgap interface states density (D{sub it}). X-ray photoelectron spectroscopy (XPS) studies revealed that these changes in the electrical properties were accompanied by a reduction in the amount of the Ga-O bonding while As-As dimers as well as other XPS detected InGaAs surface species did not correlate with the observed D{sub it} trend. Possible explanations for these findings are suggested.

  1. Biochemical Control With Radiotherapy Improves Overall Survival in Intermediate and High-Risk Prostate Cancer Patients Who Have an Estimated 10-Year Overall Survival of >90%

    SciTech Connect (OSTI)

    Herbert, Christopher; Liu, Mitchell; Tyldesley, Scott; Morris, W. James; Joffres, Michel; Khaira, Mandip; Kwan, Winkle; Moiseenko, Vitali; Pickles, Thomas

    2012-05-01

    Purpose: To identify subgroups of patients with carcinoma of the prostate treated with radical radiotherapy that have improved overall survival when disease is biochemically controlled. Methods and Materials: A cohort of 1,060 prostate cancer patients treated with radical radiotherapy was divided into nine subgroups based on National Comprehensive Cancer Network risk category and estimated 10-year overall survival (eOS 10y) derived from the age adjusted Charlson Comorbidity Index. Patients with and without biochemical control were compared with respect to overall survival. Actuarial estimates of overall survival were calculated using the Kaplan-Meier method. Univariate and multivariate Cox proportional hazards models were used for analysis of overall survival. Results: Median follow-up was 125 months (range, 51-176 months). Only the subgroups with high or intermediate risk disease and an eOS 10y of >90% had a statistically significantly improved overall survival when prostate cancer was biochemically controlled. In all other groups, biochemical control made no significant difference to overall survival. In the subgroup with high-risk disease and eOS 10y >90%, actuarial overall survival was 86.3% (95% confidence interval [CI] 78.5%-94.1%) and 62.1% (95% CI 52.9%-71.3%) for patients with biochemical control and biochemical relapse respectively (p = 0.002). In the intermediate risk group with eOS >90%, actuarial overall survival was 95.3% (95% CI 89.0%-100%) and 79.8% (95% CI 68.0%-91.6%) for biochemically controlled and biochemically relapsed patients (p = 0.033). On multivariate analysis, National Comprehensive Cancer Network risk group (p = 0.005), biochemical control (p = 0.033) and eOS 10y (p < 0.001) were statistically significant. Conclusion: Biochemical control translates into improved overall survival in patients with high or intermediate risk disease and an estimated 10-year overall survival of >90%.

  2. PSA Response to Neoadjuvant Androgen Deprivation Therapy Is a Strong Independent Predictor of Survival in High-Risk Prostate Cancer in the Dose-Escalated Radiation Therapy Era

    SciTech Connect (OSTI)

    McGuire, Sean E.; Lee, Andrew K.; Cerne, Jasmina Z.; Munsell, Mark F.; Levy, Lawrence B.; Kudchadker, Rajat J.; Choi, Seungtaek L.; Nguyen, Quynh N.; Hoffman, Karen E.; Pugh, Thomas J.; Frank, Steven J.; Corn, Paul G.; Logothetis, Christopher J.; Kuban, Deborah A.

    2013-01-01

    Purpose: The aim of the study was to evaluate the prognostic value of prostate-specific antigen (PSA) response to neoadjuvant androgen deprivation therapy (ADT) prior to dose-escalated radiation therapy (RT) and long-term ADT in high-risk prostate cancer. Methods and Materials: We reviewed the charts of all patients diagnosed with high-risk prostate cancer and treated with a combination of long-term ADT (median, 24 months) and dose-escalated (median, 75.6 Gy) RT between 1990 and 2007. The associations among patient, tumor, and treatment characteristics with biochemical response to neoadjuvant ADT and their effects on failure-free survival (FFS), time to distant metastasis (TDM), prostate cancer-specific mortality (PCSM) and overall survival (OS) were examined. Results: A total of 196 patients met criteria for inclusion. Median follow-up time for patients alive at last contact was 7.0 years (range, 0.5-18.1 years). Multivariate analysis identified the pre-RT PSA concentration (<0.5 vs {>=}0.5 ng/mL) as a significant independent predictor of FFS (P=.021), TDM (P=.009), PCSM (P=.039), and OS (P=.037). On multivariate analysis, pretreatment PSA (iPSA) and African-American race were significantly associated with failure to achieve a pre-RT PSA of <0.5 ng/mL. Conclusions: For high-risk prostate cancer patients treated with long-term ADT and dose-escalated RT, a pre-RT PSA level {>=}0.5 ng/mL after neoadjuvant ADT predicts for worse survival measures. Both elevated iPSA and African-American race are associated with increased risk of having a pre-RT PSA level {>=}0.5 ng/mL. These patients should be considered for clinical trials that test newer, more potent androgen-depleting therapies such as abiraterone and MDV3100 in combination with radiation.

  3. DOC-2/DAB2 Interacting Protein Status in High-Risk Prostate Cancer Correlates With Outcome for Patients Treated With Radiation Therapy

    SciTech Connect (OSTI)

    Jacobs, Corbin; Tumati, Vasu; Kapur, Payal; Yan, Jingsheng; Hong, David; Bhuiyan, Manzerul; Xie, Xian-Jin; Pistenmaa, David; Yu, Lan; Hsieh, Jer-Tsong; Saha, Debabrata; Kim, D. W. Nathan

    2014-07-15

    Purpose: This pilot study investigates the role of DOC-2/DAB2 Interacting Protein (DAB2IP) and enhancer of zeste homolog 2 (EZH2) as prognostic biomarkers in high-risk prostate cancer patients receiving definitive radiation therapy. Methods and Materials: Immunohistochemistry was performed and scored by an expert genitourinary pathologist. Clinical endpoints evaluated were freedom from biochemical failure (FFBF), castration resistance–free survival (CRFS), and distant metastasis–free survival (DMFS). Log-rank test and Cox regression were used to determine significance of biomarker levels with clinical outcome. Results: Fifty-four patients with high-risk prostate cancer (stage ≥T3a, or Gleason score ≥8, or prostate-specific antigen level ≥20 ng/mL) treated with radiation therapy from 2005 to 2012 at our institution were evaluated. Nearly all patients expressed EZH2 (98%), whereas 28% of patients revealed DAB2IP reduction and 72% retained DAB2IP. Median follow-up was 34.0 months for DAB2IP-reduced patients, 29.9 months for DAB2IP-retained patients, and 32.6 months in the EZH2 study. Reduction in DAB2IP portended worse outcome compared with DAB2IP-retained patients, including FFBF (4-year: 37% vs 89%, P=.04), CRFS (4-year: 50% vs 90%, P=.02), and DMFS (4-year: 36% vs 97%, P=.05). Stratified EZH2 expression trended toward significance for worse FFBF and CRFS (P=.07). Patients with reduced DAB2IP or highest-intensity EZH2 expression exhibited worse FFBF (4-year: 32% vs 95%, P=.02), CRFS (4-year: 28% vs 100%, P<.01), and DMFS (4-year: 39% vs 100%, P=.04) compared with the control group. Conclusion: Loss of DAB2IP is a potent biomarker that portends worse outcome despite definitive radiation therapy for patients with high-risk prostate cancer. Enhancer of zeste homolog 2 is expressed in most high-risk tumors and is a less potent discriminator of outcome in this study. The DAB2IP status in combination with degree of EZH2 expression may be useful for

  4. Pathways and barriers to genetic testing and screening: Molecular genetics meets the high-risk family. Final report

    SciTech Connect (OSTI)

    Duster, T.

    1998-11-01

    The proliferation of genetic screening and testing is requiring increasing numbers of Americans to integrate genetic knowledge and interventions into their family life and personal experience. This study examines the social processes that occur as families at risk for two of the most common autosomal recessive diseases, sickle cell disease (SC) and cystic fibrosis (CF), encounter genetic testing. Each of these diseases is found primarily in a different ethnic/racial group (CF in Americans of North European descent and SC in Americans of West African descent). This has permitted them to have a certain additional lens on the role of culture in integrating genetic testing into family life and reproductive planning. A third type of genetic disorder, the thalassemias was added to the sample in order to extent the comparative frame and to include other ethnic and racial groups.

  5. High-dose radioiodine treatment for differentiated thyroid carcinoma is not associated with change in female fertility or any genetic risk to the offspring

    SciTech Connect (OSTI)

    Bal, Chandrasekhar . E-mail: csbal@hotmail.com; Kumar, Ajay; Tripathi, Madhavi; Chandrashekar, Narayana; Phom, Hentok; Murali, Nadig R.; Chandra, Prem; Pant, Gauri S.

    2005-10-01

    Background: We tried to evaluate the female fertility and genetic risk to the offspring from the exposure to high-dose {sup 131}I by assessing the pregnancy outcomes and health status of the children of female patients with differentiated thyroid cancer who had received therapeutic doses of {sup 131}I. Materials and Methods: From 1967 to 2002, a total of 1,282 women had been treated with {sup 131}I. Of these patients, 692 (54%) were in the reproductive age group (18-45 years). Forty women had a total of 50 pregnancies after high-dose {sup 131}I. Age at presentation ranged from 16 to 36 years (mean, 23 {+-} 4 years). Histopathology was papillary thyroid cancer in 32 cases and follicular thyroid cancer in 8 cases. Results: Single high-dose therapy was given in 30 cases, 2 doses were given in 7 cases, 3 doses were given in 2 cases, and four doses were given in 1 case in which lung metastases had occurred. In 37 patients (92%), disease was successfully ablated before pregnancy. Ovarian absorbed-radiation dose calculated by the MIRD method ranged from 3.5 to 60 cGy (mean, 12 {+-} 11 cGy). The interval between {sup 131}I therapy and pregnancy varied from 7 to 120 months (37.4 {+-} 28.2 months). Three spontaneous abortions occurred in 2 women. Forty-seven babies (20 females and 27 males) were born. Forty-four babies were healthy with normal birth weight and normal developmental milestones. Twenty women delivered their first baby after {sup 131}I therapy. The youngest child in our series is 11 months of age, and the oldest is 8.5 years of age. Conclusions: Female fertility is not affected by high-dose radioiodine treatment, and the therapy does not appear to be associated with any genetic risks to the offspring.

  6. A Dosimetric Comparison of Tomotherapy and Volumetric Modulated Arc Therapy in the Treatment of High-Risk Prostate Cancer With Pelvic Nodal Radiation Therapy

    SciTech Connect (OSTI)

    Pasquier, David; Universite Lille Nord de France, Lille; Centre Galilee, Clinique de la Louviere, Lille ; Cavillon, Fabrice; Faculte Libre de Medecine, Lille ; Lacornerie, Thomas; Universite Lille Nord de France, Lille ; Touzeau, Claire; Tresch, Emmanuelle; Lartigau, Eric; Universite Lille Nord de France, Lille

    2013-02-01

    Purpose: To compare the dosimetric results of volumetric modulated arc therapy (VMAT) and helical tomotherapy (HT) in the treatment of high-risk prostate cancer with pelvic nodal radiation therapy. Methods and Materials: Plans were generated for 10 consecutive patients treated for high-risk prostate cancer with prophylactic whole pelvic radiation therapy (WPRT) using VMAT and HT. After WPRT, a sequential boost was delivered to the prostate. Plan quality was assessed according to the criteria of the International Commission on Radiation Units and Measurements 83 report: the near-minimal (D98%), near-maximal (D2%), and median (D50%) doses; the homogeneity index (HI); and the Dice similarity coefficient (DSC). Beam-on time, integral dose, and several organs at risk (OAR) dosimetric indexes were also compared. Results: For WPRT, HT was able to provide a higher D98% than VMAT (44.3 {+-} 0.3 Gy and 43.9 {+-} 0.5 Gy, respectively; P=.032) and a lower D2% than VMAT (47.3 {+-} 0.3 Gy and 49.1 {+-} 0.7 Gy, respectively; P=.005), leading to a better HI. The DSC was better for WPRT with HT (0.89 {+-} 0.009) than with VMAT (0.80 {+-} 0.02; P=.002). The dosimetric indexes for the prostate boost did not differ significantly. VMAT provided better rectum wall sparing at higher doses (V70, V75, D2%). Conversely, HT provided better bladder wall sparing (V50, V60, V70), except at lower doses (V20). The beam-on times for WPRT and prostate boost were shorter with VMAT than with HT (3.1 {+-} 0.1 vs 7.4 {+-} 0.6 min, respectively; P=.002, and 1.5 {+-} 0.05 vs 3.7 {+-} 0.3 min, respectively; P=.002). The integral dose was slightly lower for VMAT. Conclusion: VMAT and HT provided very similar and highly conformal plans that complied well with OAR dose-volume constraints. Although some dosimetric differences were statistically significant, they remained small. HT provided a more homogeneous dose distribution, whereas VMAT enabled a shorter delivery time.

  7. When the facts are just not enough: Credibly communicating about risk is riskier when emotions run high and time is short

    SciTech Connect (OSTI)

    Reynolds, Barbara J.

    2011-07-15

    When discussing risk with people, commonly subject matter experts believe that conveying the facts will be enough to allow people to assess a risk and respond rationally to that risk. Because of this expectation, experts often become exasperated by the seemingly illogical way people assess personal risk and choose to manage that risk. In crisis situations when the risk information is less defined and choices must be made within impossible time constraints, the thought processes may be even more susceptible to faulty heuristics. Understanding the perception of risk is essential to understanding why the public becomes more or less upset by events. This article explores the psychological underpinnings of risk assessment within emotionally laden events and the risk communication practices that may facilitate subject matter experts to provide the facts in a manner so they can be more certain those facts are being heard. Source credibility is foundational to risk communication practices. The public meeting is one example in which these best practices can be exercised. Risks are risky because risk perceptions differ and the psychosocial environment in which risk is discussed complicates making risk decisions. Experts who want to influence the actions of the public related to a threat or risk should understand that decisions often involve emotional as well as logical components. The media and other social entities will also influence the risk context. The Center for Disease Control and Prevention's crisis and emergency-risk communication (CERC) principles are intended to increase credibility and recognize emotional components of an event. During a risk event, CERC works to calm emotions and increase trust which can help people apply the expertise being offered by response officials.

  8. Posttraumatic Stress Disorder After High-Dose-Rate Brachytherapy for Cervical Cancer With 2 Fractions in 1 Application Under Spinal/Epidural Anesthesia: Incidence and Risk Factors

    SciTech Connect (OSTI)

    Kirchheiner, Kathrin; Czajka-Pepl, Agnieszka; Scharbert, Gisela; Wetzel, Léonore; Sturdza, Alina; Dörr, Wolfgang; Pötter, Richard

    2014-06-01

    Purpose: To investigate the psychological consequences of high-dose-rate brachytherapy with 2 fractions in 1 application under spinal/epidural anesthesia in the treatment of locally advanced cervical cancer. Methods and Materials: In 50 patients with locally advanced cervical cancer, validated questionnaires were used for prospective assessment of acute and posttraumatic stress disorder (ASD/PTSD) (Impact of Event Scale–Revision), anxiety/depression (Hospital Anxiety and Depression Scale), quality of life (European Organization for Research and Treatment of Cancer Quality of Life Questionnaire Core 30/Cervical Cancer 24), physical functioning (World Health Organization performance status), and pain (visual analogue scale), before and during treatment and 1 week and 3 months after treatment. Qualitative interviews were recorded in open format for content analysis. Results: Symptoms of ASD occurred in 30% of patients 1 week after treatment; and of PTSD in 41% 3 months after treatment in association with this specific brachytherapy procedure. Pretreatment predictive variables explain 82% of the variance of PTSD symptoms. Helpful experiences were the support of the treatment team, psychological support, and a positive attitude. Stressful factors were pain, organizational problems during treatment, and immobility between brachytherapy fractions. Conclusions: The specific brachytherapy procedure, as performed in the investigated mono-institutional setting with 2 fractions in 1 application under spinal/epidural anesthesia, bears a considerable risk of traumatization. The source of stress seems to be not the brachytherapy application itself but the maintenance of the applicator under epidural anesthesia in the time between fractions. Patients at risk may be identified before treatment, to offer targeted psycho-social support. The patients' open reports regarding helpful experiences are an encouraging feedback for the treatment team; the reported stressful factors

  9. Risk Analysis

    Broader source: Energy.gov [DOE]

    Almost any new technology involves some risk. Risks involved in working with hydrogen can be minimized through adherence to standard design parameters for equipment and procedures. The Fuel Cell...

  10. Sociocultural definitions of risk

    SciTech Connect (OSTI)

    Rayner, S.

    1990-10-01

    Public constituencies frequently are criticized by technical experts as being irrational in response to low-probability risks. This presentation argued that most people are concerned with a variety of risk attributes other than probability and that is rather irrational to exclude these from the definition and analysis of technological risk. Risk communication, which is at the heart of the right-to-know concept, is described as the creation of shared meaning rather than the mere transmission of information. A case study of utilities, public utility commissions, and public interest groups illustrates how the diversity of institutional cultures in modern society leads to problems for the creation of shared meanings in establishing trust, distributing liability, and obtaining consent to risk. This holistic approach to risk analysis is most appropriate under conditions of high uncertainty and/or decision stakes. 1 fig., 5 tabs.

  11. Biomedical Applications of Microfluidic Technology Gao, Jun ...

    Office of Scientific and Technical Information (OSTI)

    Science Abstract Not Provided Los Alamos National Laboratory (LANL) LDRD United States 2014-03-28 English Technical Report Medium: ED OSTI ID: 1126675, Legacy ID: OSTI ID: 1126675...

  12. GAO Protest to AMWTP Contract Withdrawn

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    challenges, we are pleased to be moving forward with the new contractor so that we can stay on schedule to meet our compliance milestone, said Office of Environmental...

  13. Retrospective Evaluation Reveals That Long-term Androgen Deprivation Therapy Improves Cause-Specific and Overall Survival in the Setting of Dose-Escalated Radiation for High-Risk Prostate Cancer

    SciTech Connect (OSTI)

    Feng, Felix Y.; Blas, Kevin; Olson, Karin; Stenmark, Matthew; Sandler, Howard; Hamstra, Daniel A.

    2013-05-01

    Purpose: To evaluate the role of androgen deprivation therapy (ADT) and duration for high-risk prostate cancer patients treated with dose-escalated radiation therapy (RT). Methods and Materials: A retrospective analysis of high-risk prostate cancer patients treated with dose-escalated RT (minimum 75 Gy) with or without ADT was performed. The relationship between ADT use and duration with biochemical failure (BF), metastatic failure (MF), prostate cancer-specific mortality (PCSM), non-prostate cancer death (NPCD), and overall survival (OS) was assessed as a function of pretreatment characteristics, comorbid medical illness, and treatment using Fine and Gray's cumulative incidence methodology. Results: The median follow-up time was 64 months. In men with National Comprehensive Cancer Network defined high-risk prostate cancer treated with dose-escalated RT, on univariate analysis, both metastasis (P<.0001; hazard ratio 0.34; 95% confidence interval 0.18-0.67; cumulative incidence at 60 months 13% vs 35%) and PCSM (P=.015; hazard ratio 0.41; 95% confidence interval 0.2-1.0; cumulative incidence at 60 months 6% vs 11%) were improved with the use of ADT. On multivariate analysis for all high-risk patients, Gleason score was the strongest negative prognostic factor, and long-term ADT (LTAD) improved MF (P=.002), PCSM (P=.034), and OS (P=.001). In men with prostate cancer and Gleason scores 8 to 10, on multivariate analysis after adjustment for other risk features, there was a duration-dependent improvement in BF, metastasis, PCSM, and OS, all favoring LTAD in comparison with STAD or RT alone. Conclusion: For men with high-risk prostate cancer treated with dose-escalated EBRT, this retrospective study suggests that the combination of LTAD and RT provided a significant improvement in clinical outcome, which was especially true for those with Gleason scores of 8 to 10.

  14. Subsets of Women With Close or Positive Margins After Breast-Conserving Surgery With High Local Recurrence Risk Despite Breast Plus Boost Radiotherapy

    SciTech Connect (OSTI)

    Lupe, Krystine; Truong, Pauline T.; Alexander, Cheryl; Lesperance, Mary; Speers, Caroline; Tyldesley, Scott

    2011-11-15

    Purpose: (1) To examine the effect of surgical margin status on local recurrence (LR) and survival following breast-conserving therapy; (2) To identify subsets with close or positive margins with high LR risk despite whole breast radiotherapy (RT) plus boost. Methods and Materials: Subjects were 2,264 women with pT1-3, any N, M0 invasive breast cancer, treated with breast-conserving surgery and whole breast {+-} boost RT. Five-year Kaplan-Meier (KM) LR, breast cancer-specific and overall survival (BCSS and OS) were compared between cohorts with negative (n = 1,980), close (n = 222), and positive (n = 62) margins. LR rates were analyzed according to clinicopathologic characteristics. Multivariable Cox regression modeling and matched analysis of close/positive margin cases and negative margin controls were performed. Results: Median follow-up was 5.2 years. Boost RT was used in 92% of patients with close or positive margins. Five-year KM LR rates in the negative, close and positive margin cohorts were 1.3%, 4.0%, and 5.2%, respectively (p = 0.001). BCSS and OS were similar in the three margin subgroups. In the close/positive margin cohort, LR rates were 10.2% with age <45 years, 11.8% with Grade III, 11.3% with lymphovascular invasion (LVI), and 26.3% with {>=}4 positive nodes. Corresponding rates in the negative margin cohort were 2.3%, 2.4%, 1.0%, and 2.4%, respectively. On Cox regression analysis of the entire cohort, close or positive margin, Grade III histology, {>=}4 positive nodes, and lack of systemic therapy were significantly associated with higher LR risk. When close/positive margin cases were matched to negative margin controls, the difference in 5-year LR remained significant (4.25% vs. 0.7%, p < 0.001). Conclusions: On univariable analysis, subsets with close or positive margins, in combination with age <45 years, Grade III, LVI, and {>=}4 positive nodes, have 5-year LR >10% despite whole breast plus boost RT. These patients should be considered for

  15. Sunitinib Plus Androgen Deprivation and Radiation Therapy for Patients With Localized High-Risk Prostate Cancer: Results From a Multi-institutional Phase 1 Study

    SciTech Connect (OSTI)

    Corn, Paul G.; Song, Danny Y.; Heath, Elisabeth; Maier, Jordan; Meyn, Raymond; Kuban, Deborah; DePetrillo, Thomas A.; Mathew, Paul

    2013-07-01

    Purpose: To evaluate the feasibility of administering sunitinib in combination with androgen deprivation therapy and external-beam intensity modulated radiation therapy (XRT) in patients with localized high-risk prostate cancer. Methods and Materials: Seventeen men with localized adenocarcinoma of the prostate with cT2c-cT4 or Gleason 8-10 or prostate-specific antigen >20 ng/mL received initial androgen deprivation (leuprolide 22.5 mg every 12 weeks plus oral bicalutamide 50 mg daily) for 4-8 weeks before oral sunitinib 12.5, 25, or 37.5 mg daily for 4 weeks as lead-in, then concurrently with and 4 weeks after XRT (75.6 Gy in 42 fractions to prostate and seminal vesicles). A 3+3 sequential dose-escalation design was used to assess the frequency of dose-limiting toxicity (DLT) and establish a maximal tolerated dose of sunitinib. Results: Sunitinib at 12.5- and 25-mg dose levels was well tolerated. The first 4 patients enrolled at 37.5 mg experienced a DLT during lead-in, and a drug interaction between sunitinib and bicalutamide was suspected. The protocol was revised and concurrent bicalutamide omitted. Of the next 3 patients enrolled at 37.5 mg, 2 of 3 receiving concurrent therapy experienced DLTs during radiation: grade 3 diarrhea and grade 3 proctitis, respectively. Only 1 of 7 patients completed sunitinib at 37.5 mg daily, whereas 3 of 3 patients (25 mg as starting dose) and 3 of 4 patients (25 mg as reduced dose) completed therapy. Conclusions: The feasibility of combined vascular endothelial growth factor receptor (VEGFR)/platelet-derived growth factor receptor (PDGFR) inhibitor therapy, androgen deprivation, and radiation therapy for prostate cancer was established. Using a daily dosing regimen with lead-in, concurrent, and post-XRT therapy, the recommended phase 2 dose of sunitinib is 25 mg daily.

  16. Phase II Trial of Radiosurgery to Magnetic Resonance Spectroscopy-Defined High-Risk Tumor Volumes in Patients With Glioblastoma Multiforme

    SciTech Connect (OSTI)

    Einstein, Douglas B.; Wessels, Barry; Bangert, Barbara; Fu, Pingfu; Nelson, A. Dennis; Cohen, Mark; Sagar, Stephen; Lewin, Jonathan; Sloan, Andrew; Zheng Yiran; Williams, Jordonna; Colussi, Valdir; Vinkler, Robert; Maciunas, Robert

    2012-11-01

    Purpose: To determine the efficacy of a Gamma Knife stereotactic radiosurgery (SRS) boost to areas of high risk determined by magnetic resonance spectroscopy (MRS) functional imaging in addition to standard radiotherapy for patients with glioblastoma (GBM). Methods and Materials: Thirty-five patients in this prospective Phase II trial underwent surgical resection or biopsy for a GBM followed by SRS directed toward areas of MRS-determined high biological activity within 2 cm of the postoperative enhancing surgical bed. The MRS regions were determined by identifying those voxels within the postoperative T2 magnetic resonance imaging volume that contained an elevated choline/N-acetylaspartate ratio in excess of 2:1. These voxels were marked, digitally fused with the SRS planning magnetic resonance image, targeted with an 8-mm isocenter per voxel, and treated using Radiation Therapy Oncology Group SRS dose guidelines. All patients then received conformal radiotherapy to a total dose of 60 Gy in 2-Gy daily fractions. The primary endpoint was overall survival. Results: The median survival for the entire cohort was 15.8 months. With 75% of recursive partitioning analysis (RPA) Class 3 patients still alive 18 months after treatment, the median survival for RPA Class 3 has not yet been reached. The median survivals for RPA Class 4, 5, and 6 patients were 18.7, 12.5, and 3.9 months, respectively, compared with Radiation Therapy Oncology Group radiotherapy-alone historical control survivals of 11.1, 8.9, and 4.6 months. For the 16 of 35 patients who received concurrent temozolomide in addition to protocol radiotherapeutic treatment, the median survival was 20.8 months, compared with European Organization for Research and Treatment of Cancer historical controls of 14.6 months using radiotherapy and temozolomide. Grade 3/4 toxicities possibly attributable to treatment were 11%. Conclusions: This represents the first prospective trial using selective MRS-targeted functional SRS

  17. Risk communication in environmental assessment

    SciTech Connect (OSTI)

    Rahm-Crites, L.

    1996-08-26

    Since the enactment of NEPA and other environmental legislation, the concept of `risk communication` has expanded from simply providing citizens with scientific information about risk to exploring ways of making risk information genuinely meaningful to the public and facilitating public involvement in the very processes whereby risk is analyzed and managed. Contemporary risk communication efforts attempt to find more effective ways of conveying increasingly complex risk information and to develop more democratic and proactive approaches to community involvement, in particular to ensuring the participation of diverse populations in risk decisions. Although considerable progress has been made in a relatively short time, risk communication researchers and practitioners currently face a number of challenges in a time of high expectations, low trust, and low budgets.

  18. Risk Code?

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Identify the Task Risk Code >2 Determine if a Work Control Document is needed What is the Unmitigated Risk Code? Rev.1 09/05/14 Read and Agree to Comply with appropriate mitigation and sign Work Control Documents Is there an approved Work Control Document (WCD)? WORK PLANNING, CONTROL AND AUTHORIZATION FLOW DIAGRAM 1. Define Scope of Work 2. Analyze Hazards 3. Develop and Implement Hazard Controls 4. Perform Work Within Controls 5. Feedback and Continuous Improvement Analyze Hazards and

  19. Successful Characterization Strategies for the Active High Risk Y-12 National Security Complex 9201-5 (Alpha-5) Facility, Oak Ridge, TN - 12164

    SciTech Connect (OSTI)

    Birchfield, Joseph W. III; Albrecht, Linda

    2012-07-01

    Building 9201-5 (Alpha 5) was completed in May 1944 and served as a production facility for National Nuclear Security Administration (NNSA) Y-12 Weapons Plant. During the Manhattan Project, it functioned as a uranium enrichment facility. The facility was renovated and altered over the years, converting the calutrons to support other missions. Alpha 5 consists of 4 floors and a basement measuring approximately 600,000 square feet. The facility contains various pieces of equipment remaining from legacy operations. A significant amount (approximately 200,000 kgs) of mercury (Hg) has been spilled in the facility over the operational history of the building. To further complicate matters, beryllium (Be) contamination in 9201-5 is found throughout approximately sixty percent of the facility. Concentrations varying from very low (< 0.2 micrograms (μg)/100 cm{sup 2}) to areas where concentrations are relatively high, approximately 600 μg/100 cm{sup 2}, in regulated beryllium areas. The primary site related contaminants (SRCs) for the waste in this facility are enriched uranium, depleted uranium, beryllium and mercury. This facility represents the highest environmental risk for DOE-ORO EM and NNSA at Y-12 and must be quickly addressed to minimize impacts to future Y-12 missions, as well as human health and the environment. As part of the American Recovery and Reinvestment Act (ARRA), approximately 700,000 cubic feet of legacy material was removed in 2010 and 2011. In addition, characterization of the 9201-5 facility was scheduled in the winter and spring of 2011. This activity was initiated in January 2011 and was completed in July 2011. Heavy schedule pressure was further complicated by the fact that this building has active utility, security and process systems. Given these complex variables, a unique, out of the box characterization strategy was forged in an effort to bound radiological and chemical contaminants, as well as providing the appropriate level of quality to

  20. Huizenga Kicks Off Waste Management Conference

    Broader source: Energy.gov [DOE]

    PHOENIX – EM Senior Advisor Dave Huizenga shared many accomplishments of the nuclear cleanup program in a speech at the annual Waste Management Conference today, including recent news of its progress on the U.S. Government Accountability Office’s (GAO) High-Risk List.

  1. Validation of mathematical models for the prediction of organs-at-risk dosimetric metrics in high-dose-rate gynecologic interstitial brachytherapy

    SciTech Connect (OSTI)

    Damato, Antonio L.; Viswanathan, Akila N.; Cormack, Robert A.

    2013-10-15

    Purpose: Given the complicated nature of an interstitial gynecologic brachytherapy treatment plan, the use of a quantitative tool to evaluate the quality of the achieved metrics compared to clinical practice would be advantageous. For this purpose, predictive mathematical models to predict the D{sub 2cc} of rectum and bladder in interstitial gynecologic brachytherapy are discussed and validated.Methods: Previous plans were used to establish the relationship between D2cc and the overlapping volume of the organ at risk with the targeted area (C0) or a 1-cm expansion of the target area (C1). Three mathematical models were evaluated: D{sub 2cc}=α*C{sub 1}+β (LIN); D{sub 2cc}=α– exp(–β*C{sub 0}) (EXP); and a mixed approach (MIX), where both C{sub 0} and C{sub 1} were inputs of the model. The parameters of the models were optimized on a training set of patient data, and the predictive error of each model (predicted D{sub 2cc}− real D{sub 2cc}) was calculated on a validation set of patient data. The data of 20 patients were used to perform a K-fold cross validation analysis, with K = 2, 4, 6, 8, 10, and 20.Results: MIX was associated with the smallest mean prediction error <6.4% for an 18-patient training set; LIN had an error <8.5%; EXP had an error <8.3%. Best case scenario analysis shows that an error ≤5% can be achieved for a ten-patient training set with MIX, an error ≤7.4% for LIN, and an error ≤6.9% for EXP. The error decreases with the increase in training set size, with the most marked decrease observed for MIX.Conclusions: The MIX model can predict the D{sub 2cc} of the organs at risk with an error lower than 5% with a training set of ten patients or greater. The model can be used in the development of quality assurance tools to identify treatment plans with suboptimal sparing of the organs at risk. It can also be used to improve preplanning and in the development of real-time intraoperative planning tools.

  2. Verbal risk in communicating risk

    SciTech Connect (OSTI)

    Walters, J.C.; Reno, H.W.

    1993-03-01

    When persons in the waste management industry have a conversation concerning matters of the industry, thoughts being communicated are understood among those in the industry. However, when persons in waste management communicate with those outside the industry, communication may suffer simply because of poor practices such as the use of jargon, euphemisms, acronyms, abbreviations, language usage, not knowing audience, and public perception. This paper deals with ways the waste management industry can communicate risk to the public without obfuscating issues. The waste management industry should feel obligated to communicate certain meanings within specific contexts and, then, if the context changes, should not put forth a new, more appropriate meaning to the language already used. Communication of the waste management industry does not have to be provisional. The authors suggest verbal risks in communicating risk can be reduced significantly or eliminated by following a few basic communication principles. The authors make suggestions and give examples of ways to improve communication with the general public by avoiding or reducing jargon, euphemisms, and acronyms; knowing the audience; avoiding presumptive knowledge held by the audience; and understanding public perception of waste management issues.

  3. Ecological Risk Assessments

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Ecological Risk Assessments Ecological Risk Assessments Ecological risk assessment is the appraisal of potential adverse effects of exposure to contaminants on plants and animals....

  4. Risk Management Process Overview

    Broader source: Energy.gov [DOE]

    The cybersecurity risk management process explained in the Electricity Sector Cybersecurity Risk Management Process (RMP) Guideline has two primary components: the risk management model and the the risk management cycle.

  5. Risk Management Guide

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2011-01-12

    The purpose of this guide is to describe effective risk management processes. The continuous and iterative process includes updating project risk documents and the risk management plan and emphasizes implementation communication of the risks and actions taken.

  6. Executive Order 13045, Protection of Children from Environmental Health Risks and Safety Risks

    Broader source: Energy.gov [DOE]

    Each Federal agency: (a) shall make it a high priority to identify and assess environmental health risks and safety risks that may disproportionately affect children; and (b) shall ensure that its...

  7. Program & Project Management For The Acquisition Of Capital Assets

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Office of Engineering and Construction Management Department of Energy Root Cause Analysis Corrective Action Plan ISSUE #3: Strengthen Risk Management November 4, 2009 Paul Bosco, PE, PMP, LEED-AP Director, Office of Engineering and Construction Management (OECM) U. S. Department of Energy Office of Management Office of Engineering and Construction Management 2 * Some Background - GAO High-Risk List - Root Cause Analysis and Corrective Action Plan - Issue Number THREE * Things We Have Done: Risk

  8. Risk Assessment & Management Information

    Broader source: Energy.gov [DOE]

    NRC - A Proposed Risk Management Regulatory Framework, April 2012 Risk Assessment Technical Experts Working Group (RWG) web page DOE Standard on Development and Use of Probabilistic Risk Assessment in DOE Nuclear Safety Applications (draft), December 2010 Consortium for Risk Evaluation with Stakeholder Participation Workshop on Risk Assessment and Safety Decision Making Under Uncertainty

  9. Risk assessment handbook

    SciTech Connect (OSTI)

    Farmer, F.G.; Jones, J.L.; Hunt, R.N.; Roush, M.L.; Wierman, T.E.

    1990-09-01

    The Probabilistic Risk Assessment Unit at EG G Idaho has developed this handbook to provide guidance to a facility manager exploring the potential benefit to be gained by performance of a risk assessment properly scoped to meet local needs. This document is designed to help the manager control the resources expended commensurate with the risks being managed and to assure that the products can be used programmatically to support future needs in order to derive maximum beneflt from the resources expended. We present a logical and functional mapping scheme between several discrete phases of project definition to ensure that a potential customer, working with an analyst, is able to define the areas of interest and that appropriate methods are employed in the analysis. In addition the handbook is written to provide a high-level perspective for the analyst. Previously, the needed information was either scattered or existed only in the minds of experienced analysts. By compiling this information and exploring the breadth of knowledge which exists within the members of the PRA Unit, the functional relationships between the customers' needs and the product have been established.

  10. Risk assessment handbook

    SciTech Connect (OSTI)

    Farmer, F.G.; Jones, J.L.; Hunt, R.N.; Roush, M.L.; Wierman, T.E.

    1990-09-01

    The Probabilistic Risk Assessment Unit at EG&G Idaho has developed this handbook to provide guidance to a facility manager exploring the potential benefit to be gained by performance of a risk assessment properly scoped to meet local needs. This document is designed to help the manager control the resources expended commensurate with the risks being managed and to assure that the products can be used programmatically to support future needs in order to derive maximum beneflt from the resources expended. We present a logical and functional mapping scheme between several discrete phases of project definition to ensure that a potential customer, working with an analyst, is able to define the areas of interest and that appropriate methods are employed in the analysis. In addition the handbook is written to provide a high-level perspective for the analyst. Previously, the needed information was either scattered or existed only in the minds of experienced analysts. By compiling this information and exploring the breadth of knowledge which exists within the members of the PRA Unit, the functional relationships between the customers` needs and the product have been established.

  11. Fuzzy Risk Analyzer

    Energy Science and Technology Software Center (OSTI)

    1994-03-04

    FRA is a general purpose code for risk analysis using fuzzy, not numeric, attributes. It allows the user to evaluate the risk associated with a composite system on the basis of the risk estimates of the individual components.

  12. Enterprise Risk Management Model

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Model The Enterprise Risk Management (ERM) Model is a system used to analyze the cost and benefit of addressing risks inherent in the work performed by the Department of Energy. This system measures risk using a combination of qualitative and quantitative methods to set a standard method for analyzing risk across the many functions within the department. Risks generally fall within five categories regardless ofthe subject matter ofthe subsystem. These categories are (1) risks to people, (2)

  13. Enterprise Risk Management Framework

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Framework The Enterprise Risk Management (ERM) framework includes four steps: identify the risks, determine the probability and impact of each one, identify controls that are...

  14. A Phase II Study of Preradiotherapy Chemotherapy Followed by Hyperfractionated Radiotherapy for Newly Diagnosed High-Risk Medulloblastoma/Primitive Neuroectodermal Tumor: A Report From the Children's Oncology Group (CCG 9931)

    SciTech Connect (OSTI)

    Allen, Jeffrey Donahue, Bernadine; Mehta, Minesh; Miller, Douglas C.; Rorke, Lucy B.; Jakacki, Regina; Robertson, Patricia; Sposto, Richard; Holmes, Emi; Vezina, Gilbert; Muraszko, Karin; Puccetti, Diane; Prados, Michael; Chan, K.-W.

    2009-07-15

    Purpose: To verify feasibility and monitor progression-free survival and overall survival in children with high-risk medulloblastoma and noncerebellar primitive neuroectodermal tumors (PNETs) treated in a Phase II study with preradiotherapy chemotherapy (CHT) followed by high-dose, hyperfractionated craniospinal radiotherapy (CSRT). Methods and Materials: Eligibility criteria included age >3 years at diagnosis, medulloblastoma with either high M stage and/or >1.5 cm{sup 2} postoperative residual disease, and all patients with noncerebellar PNET. Treatment was initiated with five alternating monthly cycles of CHT (A [cisplatin, cyclophosphamide, etoposide, and vincristine], B [carboplatin and etoposide], A, B, and A) followed by hyperfractionated CSRT (40 Gy) with a boost to the primary tumor (72 Gy) given in twice-daily 1-Gy fractions. Results: The valid study group consisted of 124 patients whose median age at diagnosis was 7.8 years. Eighty-four patients (68%) completed the entire protocol according to study guidelines (within 9 months), and the median time to complete CSRT was 1.6 months. Major reasons for failure to complete CHT included progressive disease (17%) and toxic death (2.4%). The 5-year progression-free survival and overall survival rates were 43% {+-} 5% and 52% {+-} 5%, respectively. No significant differences were detected in subset analysis related to response to CHT, site of primary tumor, postoperative residual disease, or M stage. Conclusions: The feasibility of this intensive multimodality protocol was confirmed, and response to pre-RT CHT did not impact on survival. Survival data from this protocol can not be compared with data from other studies, given the protocol design.

  15. Long-term Follow-up of the RTOG 9501/Intergroup Phase III Trial: Postoperative Concurrent Radiation Therapy and Chemotherapy in High-Risk Squamous Cell Carcinoma of the Head and Neck

    SciTech Connect (OSTI)

    Cooper, Jay S.; Zhang Qiang; Pajak, Thomas F.; Forastiere, Arlene A.; Jacobs, John; Saxman, Scott B.; Kish, Julie A.; Kim, Harold E.; Cmelak, Anthony J.; Rotman, Marvin; Lustig, Robert; Ensley, John F.; Thorstad, Wade; Schultz, Christopher J.; Yom, Sue S.; Ang, K. Kian

    2012-12-01

    Purpose: Previous analysis of this Intergroup trial demonstrated that with a median follow-up among surviving patients of 45.9 months, the concurrent postoperative administration of cisplatin and radiation therapy improved local-regional control and disease-free survival of patients who had high-risk resectable head-and-neck carcinomas. With a minimum of 10 years of follow-up potentially now available for all patients, these results are updated here to examine long-term outcomes. Methods and Materials: A total of 410 analyzable patients who had high-risk resected head-and-neck cancers were prospectively randomized to receive either radiation therapy (RT: 60 Gy in 6 weeks) or identical RT plus cisplatin, 100 mg/m{sup 2}i.v. on days 1, 22, and 43 (RT + CT). Results: At 10 years, the local-regional failure rates were 28.8% vs 22.3% (P=.10), disease-free survival was 19.1% vs 20.1% (P=.25), and overall survival was 27.0% vs 29.1% (P=.31) for patients treated by RT vs RT + CT, respectively. In the unplanned subset analysis limited to patients who had microscopically involved resection margins and/or extracapsular spread of disease, local-regional failure occurred in 33.1% vs 21.0% (P=.02), disease-free survival was 12.3% vs 18.4% (P=.05), and overall survival was 19.6% vs 27.1% (P=.07), respectively. Conclusion: At a median follow-up of 9.4 years for surviving patients, no significant differences in outcome were observed in the analysis of all randomized eligible patients. However, analysis of the subgroup of patients who had either microscopically involved resection margins and/or extracapsular spread of disease showed improved local-regional control and disease-free survival with concurrent administration of chemotherapy. The remaining subgroup of patients who were enrolled only because they had tumor in 2 or more lymph nodes did not benefit from the addition of CT to RT.

  16. Enterprise Risk Management Framework

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Framework The Enterprise Risk Management (ERM) framework includes four steps: identify the risks, determine the probability and impact of each one, identify controls that are already in place that mitigate that risk, and propose additional controls if needed. Step 1: Identify Risks - What can go wrong? This step should identify the negative outcomes that could result from an action or decision . It is important to consider a wide range of risks, and so the Department's ERM framework includes

  17. State Energy Risk Assessment Initiative - State Energy Risk Profiles...

    Energy Savers [EERE]

    Mission Energy Infrastructure Modeling and Analysis State Energy Risk Assessment Initiative - State Energy Risk Profiles State Energy Risk Assessment Initiative - State...

  18. GAO Protest to AMWTP Contract Withdrawn | Department of Energy

    Office of Environmental Management (EM)

    challenges, we are pleased to be moving forward with the new contractor so that we can stay on schedule to meet our compliance milestone," said Office of Environmental Management...

  19. GAO Challenges and Efforts to Secure Control Systems (March 2004)

    Broader source: Energy.gov [DOE]

    Computerized control systems perform vital functions across many of our nation’s critical infrastructures. For example, in natural gas distribution, they can monitor and control the pressure and...

  20. GAO-06-811 Information Security: Coordination of Federal Cyber...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    secure, networked computer systems in the federal government and in the private sector. ... Chairman: Dramatic increases in computer interconnectivity, especially in the use of the ...

  1. GAO-07-1036, CRITICAL INFRASTRUCTURE PROTECTION: Multiple Efforts...

    Energy Savers [EERE]

    ... to manage the complex activities of a municipal water system or a nuclear power plant. ... and control the generation, transmission, and distribution of electric power (see fig. 2). ...

  2. GAO-04-354, CRITICAL INFRASTRUCTURE PROTECTION: Challenges and...

    Energy Savers [EERE]

    ... IEEE Institute of Electrical and Electronics ... power generation, transmission, and distribution; oil and gas refining ... establish a cyber connection to the control network. ...

  3. Topographical Risk Assessment

    Energy Science and Technology Software Center (OSTI)

    2002-09-24

    TRA was developed as a computer tool for the DOE Office of River Protection (ORP) that will provides the capability to visualize and rapidly understand information about the risks associated with the River protection Project (RPP). Previously, technical and programmatic risk management within ORP had relied heavily on risk lists and other techniques that presented risk information but did not place it in perspective of the overall project. This made it difficult for ORP seniormore » management to understand the risk information presented, prioritize their activities, and provide direction to ORP staff and contractors about how to manage specific risk events. The TRA visualization tool, provides the appropriate context and perspective that allows senior management to effectively manage risks. Basically, the TRA overlays information about risks associated with specific activities and their magnitudes on top of the project baseline schedule. this provides senior management with information about the magnitudes of specific risk events as well as their timing, and allows them to focus their attention and resources on the risks that merit attention and possible further action. The TRA tool can also be used to display other types of information associated with scheduled activities, such as cost to date, technical performance, schedule performance, etc. Additionally, the base of the 3-dimensional representation can be changed to other types of graphics, such as maps, process flow diagrams, etc., which allows the display of other types of informatio, such as hazards, health and safety risks, and system availability.« less

  4. Risk and Realities | Jefferson Lab

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    » Risk Management Process Overview Risk Management Process Overview figure depicting three tier risk management process The cybersecurity risk management process explained in the Electricity Sector Cybersecurity Risk Management Process (RMP) Guideline has two primary components: the risk management model and the the risk management cycle. The risk management model reflects the organization as a three-tiered structure and provides a comprehensive view for the electricity sector organization and

  5. Ozone Risk Assessment Utilities

    Energy Science and Technology Software Center (OSTI)

    1999-08-10

    ORAMUS is a user-friendly, menu-driven software system that calculates and displays user-selected risk estimates for health effects attributable to short-term exposure to tropospheric ozone. Inputs to the risk assessment are estimates of exposure to ozone and exposure-response relationships to produce overall risk estimates in the form of probability distributions. Three fundamental models are included: headcount risk, benchmark risk, and hospital admissions. Exposure-response relationships are based on results of controlled human exposure studies. Exposure estimates aremore » based on the EPA''s probabilistic national ambient air quality standards (NAAQS) exposure model, pNEM/Osub3, which simulates air quality associated with attainment of alternative NAAQS. Using ORAMUS, risk results for 27 air quality scenarios, air quality in 9 urban areas, 33 health endpoints, and 4 chronic health endpoints can be calculated.« less

  6. Risk Identification and Assessment

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Risk Identification and Assessment [Sections in brackets are for instructions; these should be deleted or replaced with specifics in the template.] Subsystem Title or Section within Subsystem [In the first column, using short bullets, fill in "what can go wrong," or a brief description of a potential benefit from a program or action. Add additional rows as necessary. Fill in the other columns using the rating guidelines in the attached reference pages.] |Risk|Probability|Impact|Risk

  7. Enterprise Risk Management Specialist

    Broader source: Energy.gov [DOE]

    (See Frequently Asked Questions for more information). Where would I be working? Western Area Power Administration, Corporate Services Office, Office of the Chief Operating Officer, Risk and...

  8. Radiation risk management at DOE accelerator facilities

    SciTech Connect (OSTI)

    Dyck, O.B. van

    1997-01-01

    The DOE accelerator contractors have been discussing among themselves and with the Department how to improve radiation safety risk management. This activity-how to assure prevention of unplanned high exposures-is separate from normal exposure management, which historically has been quite successful. The ad-hoc Committee on the Accelerator Safety Order and Guidance [CASOG], formed by the Accelerator Section of the HPS, has proposed a risk- based approach, which will be discussed. Concepts involved are risk quantification and comparison (including with non-radiation risk), passive and active (reacting) protection systems, and probabilistic analysis. Different models of risk management will be presented, and the changing regulatory environment will also be discussed..

  9. Slide 1

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Doing Business with the Office of Environmental Management Christopher Honkomp Office Director Office of Procurement Planning December 12, 2013 Improve Contract and Project Management DOE EM Goal: Improve project and contract management with the objective of delivering results on time and within cost. * Strategy 1: Annually-assess contract and project management staffing and skills to build and sustain needed capacity for Federal oversight of EM mission. (GAO High Risk Criteria.) * Strategy 2:

  10. Revised Acquisition Guide Chapter 42.5, Contract Management Planning

    Broader source: Energy.gov [DOE]

    The Department of Energy (DOE) has been on GAO's High Risk List for the past several years as a result of inadequate contract and project management. Accordingly, the improvement of contract administration is a critical issue for DOE. The Acquisition Guide chapter on Contract Management Planning has been completely revised to address this matter. The revised chapter 42.5, entitled Contract Management Planning is attached.

  11. Asbestos exposure--quantitative assessment of risk

    SciTech Connect (OSTI)

    Hughes, J.M.; Weill, H.

    1986-01-01

    Methods for deriving quantitative estimates of asbestos-associated health risks are reviewed and their numerous assumptions and uncertainties described. These methods involve extrapolation of risks observed at past relatively high asbestos concentration levels down to usually much lower concentration levels of interest today--in some cases, orders of magnitude lower. These models are used to calculate estimates of the potential risk to workers manufacturing asbestos products and to students enrolled in schools containing asbestos products. The potential risk to workers exposed for 40 yr to 0.5 fibers per milliliter (f/ml) of mixed asbestos fiber type (a permissible workplace exposure limit under consideration by the Occupational Safety and Health Administration (OSHA) ) are estimated as 82 lifetime excess cancers per 10,000 exposed. The risk to students exposed to an average asbestos concentration of 0.001 f/ml of mixed asbestos fiber types for an average enrollment period of 6 school years is estimated as 5 lifetime excess cancers per one million exposed. If the school exposure is to chrysotile asbestos only, then the estimated risk is 1.5 lifetime excess cancers per million. Risks from other causes are presented for comparison; e.g., annual rates (per million) of 10 deaths from high school football, 14 from bicycling (10-14 yr of age), 5 to 20 for whooping cough vaccination. Decisions concerning asbestos products require participation of all parties involved and should only be made after a scientifically defensible estimate of the associated risk has been obtained. In many cases to date, such decisions have been made without adequate consideration of the level of risk or the cost-effectiveness of attempts to lower the potential risk. 73 references.

  12. Recognizing and Assigning ESPC Risks and Responsibilities Using the Risk,

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Responsibility, and Performance Matrix | Department of Energy Recognizing and Assigning ESPC Risks and Responsibilities Using the Risk, Responsibility, and Performance Matrix Recognizing and Assigning ESPC Risks and Responsibilities Using the Risk, Responsibility, and Performance Matrix Document offers guidance on how to recognize and assign energy savings performance contract (ESPC) risks and responsibilities using the risk, responsibility, and performance matrix, also known as RRPM.

  13. Bio Risk Assessment Tool

    Energy Science and Technology Software Center (OSTI)

    2004-07-22

    The Biosecurity Risk Assessment Tool (BRAT) is a new type of computer application for the screening-level assessment of risk to dairy operations. BRAT for Dairies is designed to be intuitive and easy to use. Users enter basic data-property address, feed management, employee population, and so on - into the interface. Using these data and rules found in an expert system. BRAT for Dairies consults appropriate sections of its database. The expert system determines the riskmore » implications of the basic data, e.g. diseases are closely tied to pen location with respect to the outside world, When the analysis is complete, BRAT for Dairies evaluates and allocates the risk for each hazard, ranks the risks, and displays the results graphically.« less

  14. Risk Management Guide

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2011-01-18

    This Guide provides non-mandatory risk management approaches for implementing the requirements of DOE O 413.3B, Program and Project Management for the Acquisition of Capital Assets. Supersedes DOE G 413.3-7.

  15. Studies of single-photoelectron response and of performance in...

    Office of Scientific and Technical Information (OSTI)

    With appropriate shielding this PMT could function in high magnetic field environments. Authors: Malace, Simona P. 1 ; Sawatzky, Bradley D. 1 ; Gao, Haiyan 2 + Show Author ...

  16. Search for: All records | SciTech Connect

    Office of Scientific and Technical Information (OSTI)

    ... Circular' (HF2012) Blondel, Alain ; Chao, Alex ; Geneva U., astr SLAC ; Chou, Weiren ; Fermilab ; Gao, Jie ; Beijing, Inst. High Energy Phys. ; Schulte, Daniel ; CERN ; ...

  17. Molecular Foundry

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    ... Deep absorbing porphyrin molecules and their applications in organic solar cells Ke Gao, South China University of Technology Theory of Nanostructured Materials Facility High ...

  18. Report of the ICFA Beam Dynamics Workshop 'Accelerators for a...

    Office of Scientific and Technical Information (OSTI)

    Authors: Blondel, Alain ; Chao, Alex ; Geneva U., astr SLAC ; Chou, Weiren ; Fermilab ; Gao, Jie ; Beijing, Inst. High Energy Phys. ; Schulte, Daniel ; CERN ; Yokoya, Kaoru ; ...

  19. D.C.

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Alexander Wang, Micha Ben-Naim, Scott Carlsten, Lorenzo Venneri and Kevin Gao, and Coach, Paolo Venneri. Albuquerque Academy took second place and La Cueva High School in...

  20. Risk in the Weapons Stockpile

    SciTech Connect (OSTI)

    Noone, Bailey C

    2012-08-14

    When it comes to the nuclear weapons stockpile, risk must be as low as possible. Design and care to keep the stockpile healthy involves all aspects of risk management. Design diversity is a method that helps to mitigate risk.

  1. Determining risks for hazardous material operations

    SciTech Connect (OSTI)

    Cournoyer, M. E.; Dare, J. H.

    2002-01-01

    Integrated Safety Management (ISM) is structured to manage and control work at the activity level. Fundamental to ISM is that all work will be performed safely while meeting the applicable institutional-, facility-, and activity-level expectations. High and medium initial risk activities require certain levels of independent peer and/or Environmental, Health & Safety subject matter expert reviews prior to authorization. A key responsibility of line management and chemical workers is to assign initial risk adequately, so that the proper reviews are obtained. Thus, the effectiveness of an ISM system is largely dependent upon the adequacy and accuracy of this initial risk determination. In the following presentation, a Risk Determination Model (RDM) is presented for physical, health and ecological hazards associated with materials. Magnitude of exposure (Le., dose or concentration), frequency, duration, and quantity are the four factors most difficult to capture in a research and development setting. They are factored into the determination, as a function of the quantity of material. Quantity and magnitude of exposure components are simplified by using boundary criteria. This RDM will promote conformity and consistency in the assignment of risk to hazardous material activities. In conclusion, the risk assessors (line manager and chemical worker) should be capable of more accurately assessing the risk of exposure to a specific chemical with regard to the employee, public, and the environment.

  2. The Enterprise Risk Management Model

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Enterprise Risk Management Model Using the Risk Assessment Tool to Prepare a Justification Memorandum for the Development and Revision of Departmental Directives * On January 14,...

  3. EO 13045: Protection of Children from Environmental Health Risks and Safety Risks (1997) (As Amended by EO 13229 (2001) and EO 13296 (2003))

    Broader source: Energy.gov [DOE]

    Each Federal agency: (a) shall make it a high priority to identify and assess environmental health risks and safety risks that may disproportionately affect children; and (b) shall ensure that its...

  4. Risk Management Process Overview | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Risk Management Process Overview Risk Management Process Overview figure depicting three tier risk management process The cybersecurity risk management process explained in the ...

  5. Biosafety Risk Assessment Model

    Energy Science and Technology Software Center (OSTI)

    2011-05-27

    Software tool based on a structured methodology for conducting laboratory biosafety risk assessments by biosafety experts. Software is based upon an MCDA scheme and uses peer reviewed criteria and weights. The software was developed upon Microsoft’s .net framework. The methodology defines likelihood and consequence of a laboratory exposure for thirteen unique scenarios and provides numerical relative risks for each of the relevant thirteen. The software produces 2-d graphs reflecting the relative risk and a sensitivitymore » analysis which highlights the overall importance of each factor. The software works as a set of questions with absolute scales and uses a weighted additive model to calculate the likelihood and consequence.« less

  6. A Phase 3 Trial of 2 Years of Androgen Suppression and Radiation Therapy With or Without Adjuvant Chemotherapy for High-Risk Prostate Cancer: Final Results of Radiation Therapy Oncology Group Phase 3 Randomized Trial NRG Oncology RTOG 9902

    SciTech Connect (OSTI)

    Rosenthal, Seth A.; Hunt, Daniel; Sartor, A. Oliver; Pienta, Kenneth J.; Gomella, Leonard; Grignon, David; Rajan, Raghu; Kerlin, Kevin J.; Jones, Christopher U.; Dobelbower, Michael; Shipley, William U.; Zeitzer, Kenneth; Hamstra, Daniel A.; Donavanik, Viroon; Rotman, Marvin; Hartford, Alan C.; Michalski, Jeffrey; Seider, Michael; Kim, Harold; and others

    2015-10-01

    Purpose: Long-term (LT) androgen suppression (AS) with radiation therapy (RT) is a standard treatment of high-risk, localized prostate cancer (PCa). Radiation Therapy Oncology Group 9902 was a randomized trial testing the hypothesis that adjuvant combination chemotherapy (CT) with paclitaxel, estramustine, and oral etoposide plus LT AS plus RT would improve overall survival (OS). Methods and Materials: Patients with high-risk PCa (prostate-specific antigen 20-100 ng/mL and Gleason score [GS] ≥7 or clinical stage ≥T2 and GS ≥8) were randomized to RT and AS (AS + RT) alone or with adjuvant CT (AS + RT + CT). CT was given as four 21-day cycles, delivered beginning 28 days after 70.2 Gy of RT. AS was given as luteinizing hormone-releasing hormone for 24 months, beginning 2 months before RT plus an oral antiandrogen for 4 months before and during RT. The study was designed based on a 6% improvement in OS from 79% to 85% at 5 years, with 90% power and a 2-sided alpha of 0.05. Results: A total of 397 patients (380 eligible) were randomized. The patients had high-risk PCa, 68% with GS 8 to 10 and 34% T3 to T4 tumors, and median prostate-specific antigen of 22.6 ng/mL. The median follow-up period was 9.2 years. The trial closed early because of excess thromboembolic toxicity in the CT arm. The 10-year results for all randomized patients revealed no significant difference between the AS + RT and AS + RT + CT arms in OS (65% vs 63%; P=.81), biochemical failure (58% vs 54%; P=.82), local progression (11% vs 7%; P=.09), distant metastases (16% vs 14%; P=.42), or disease-free survival (22% vs 26%; P=.61). Conclusions: NRG Oncology RTOG 9902 showed no significant differences in OS, biochemical failure, local progression, distant metastases, or disease-free survival with the addition of adjuvant CT to LT AS + RT. The trial results provide valuable data regarding the natural history of high-risk PCa treated with LT AS + RT and have implications for

  7. Resources for global risk assessment: The International Toxicity Estimates for Risk (ITER) and Risk Information Exchange (RiskIE) databases

    SciTech Connect (OSTI)

    Wullenweber, Andrea Kroner, Oliver; Kohrman, Melissa; Maier, Andrew; Dourson, Michael; Rak, Andrew; Wexler, Philip; Tomljanovic, Chuck

    2008-11-15

    The rate of chemical synthesis and use has outpaced the development of risk values and the resolution of risk assessment methodology questions. In addition, available risk values derived by different organizations may vary due to scientific judgments, mission of the organization, or use of more recently published data. Further, each organization derives values for a unique chemical list so it can be challenging to locate data on a given chemical. Two Internet resources are available to address these issues. First, the International Toxicity Estimates for Risk (ITER) database ( (www.tera.org/iter)) provides chronic human health risk assessment data from a variety of organizations worldwide in a side-by-side format, explains differences in risk values derived by different organizations, and links directly to each organization's website for more detailed information. It is also the only database that includes risk information from independent parties whose risk values have undergone independent peer review. Second, the Risk Information Exchange (RiskIE) is a database of in progress chemical risk assessment work, and includes non-chemical information related to human health risk assessment, such as training modules, white papers and risk documents. RiskIE is available at (http://www.allianceforrisk.org/RiskIE.htm), and will join ITER on National Library of Medicine's TOXNET ( (http://toxnet.nlm.nih.gov/)). Together, ITER and RiskIE provide risk assessors essential tools for easily identifying and comparing available risk data, for sharing in progress assessments, and for enhancing interaction among risk assessment groups to decrease duplication of effort and to harmonize risk assessment procedures across organizations.

  8. NGNP Risk Management Database: A Model for Managing Risk

    SciTech Connect (OSTI)

    John Collins; John M. Beck

    2011-11-01

    The Next Generation Nuclear Plant (NGNP) Risk Management System (RMS) is a database used to maintain the project risk register. The RMS also maps risk reduction activities to specific identified risks. Further functionality of the RMS includes mapping reactor suppliers Design Data Needs (DDNs) to risk reduction tasks and mapping Phenomena Identification Ranking Table (PIRTs) to associated risks. This document outlines the basic instructions on how to use the RMS. This document constitutes Revision 1 of the NGNP Risk Management Database: A Model for Managing Risk. It incorporates the latest enhancements to the RMS. The enhancements include six new custom views of risk data - Impact/Consequence, Tasks by Project Phase, Tasks by Status, Tasks by Project Phase/Status, Tasks by Impact/WBS, and Tasks by Phase/Impact/WBS.

  9. Health risks in perspective: Judging health risks of energy technologies

    SciTech Connect (OSTI)

    Rowe, M.D.

    1992-09-18

    Almost daily, Americans receive reports from the mass news media about some new and frightening risk to health and welfare. Most such reports emphasize the newsworthiness of the risks -- the possibility of a crisis, disagreements among experts, how things happened, who is responsible for fixing them, how much will it cost, conflict among parties involved, etc. As a rule, the magnitudes of the risks, or the difficulty of estimating those magnitudes, have limited newsworthiness, and so they are not mentioned. Because of this emphasis in the news media, most people outside the risk assessment community must judge the relative significance of the various risks to which we all are exposed with only that information deemed newsworthy by reporters. This information is biased and shows risks in isolation. There is no basis for understanding and comparing the relative importance of risks among themselves, or for comparing one risk, perhaps a new or newly-discovered one, in the field of all risks. The purpose of this report is to provide perspective on the various risks to which we are routinely exposed. It serves as a basis for understanding the meaning of quantitative risk estimates and for comparing new or newly-discovered risks with other, better-understood risks. Specific emphasis is placed on health risks of energy technologies.

  10. Risk Assessment/Management Tool

    Energy Science and Technology Software Center (OSTI)

    2010-12-31

    RAMTool performs the following: • A tool to perform facility and programmatic risk assessments, produce risk registers, develop risk management plans (RMPs), link risks to improvement/risk-reduction projects, and actively manage risks • Ability to conduct risk assessments. Ease of determination of probability and consequence based on industry standard risk matrices. Complies with site risk management performance document. Provides multiple outputs/report for required risk forms. Conduct quick risk data analysis. • Performs/calculates a facility risk factormore » (RF) and a programmatic RF. Supports project and initiative prioritization and funding in order to make solid decisions on risk reduction. Assigns responsibility and accountability at a risk owner (RO) level. Monitors and tracks progress toward completing mitigation strategies. Ability to import massive amounts of data at the push of a button. Integrates development of a Risk Management Plan (RMP) Built for ease-of-use – design, built, and used by technical/management personnel. Can be customized (functions and/or reports) for further analysis« less

  11. Risk Management Guide

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2008-09-16

    This Guide provides a framework for identifying and managing key technical, schedule, and cost risks through applying the requirements of DOE O 413.3A, Program and Project Management for the Acquisition of Capital Assets, dated 7-28-06. Canceled by DOE G 413.3-7A, dated 1-12-11. Does not cancel other directives.

  12. Quantitative Risk Assessment

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Risk Assessment - Sandia Energy Energy Search Icon Sandia Home Locations Contact Us Employee Locator Energy & Climate Secure & Sustainable Energy Future Stationary Power Energy Conversion Efficiency Solar Energy Wind Energy Water Power Supercritical CO2 Geothermal Natural Gas Safety, Security & Resilience of the Energy Infrastructure Energy Storage Nuclear Power & Engineering Grid Modernization Battery Testing Nuclear Energy Defense Waste Management Programs Advanced Nuclear

  13. Probabilistic Risk Assessment

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Risk Assessment - Sandia Energy Energy Search Icon Sandia Home Locations Contact Us Employee Locator Energy & Climate Secure & Sustainable Energy Future Stationary Power Energy Conversion Efficiency Solar Energy Wind Energy Water Power Supercritical CO2 Geothermal Natural Gas Safety, Security & Resilience of the Energy Infrastructure Energy Storage Nuclear Power & Engineering Grid Modernization Battery Testing Nuclear Energy Defense Waste Management Programs Advanced Nuclear

  14. Security Risk Assessment

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Security Risk Assessment - Sandia Energy Energy Search Icon Sandia Home Locations Contact Us Employee Locator Energy & Climate Secure & Sustainable Energy Future Stationary Power Energy Conversion Efficiency Solar Energy Wind Energy Water Power Supercritical CO2 Geothermal Natural Gas Safety, Security & Resilience of the Energy Infrastructure Energy Storage Nuclear Power & Engineering Grid Modernization Battery Testing Nuclear Energy Defense Waste Management Programs Advanced

  15. Risk assessment meta tool LDRD final report.

    SciTech Connect (OSTI)

    Bouchard, Ann Marie; Osbourn, Gordon Cecil

    2006-12-01

    The goal of this project was to develop a risk analysis meta tool--a tool that enables security analysts both to combine and analyze data from multiple other risk assessment tools on demand. Our approach was based on the innovative self-assembling software technology under development by the project team. This technology provides a mechanism for the user to specify his intentions at a very high level (e.g., equations or English-like text), and then the code self-assembles itself, taking care of the implementation details. The first version of the meta tool focused specifically in importing and analyzing data from Joint Conflict and Tactical Simulation (JCATS) force-on-force simulation. We discuss the problem, our approach, technical risk, and accomplishments on this project, and outline next steps to be addressed with follow-on funding.

  16. Supervisory Loan Specialist (Strategic Risk)

    Broader source: Energy.gov [DOE]

    This position is located in the Department of Energy (DOE) Loans Programs Office (LPO), Risk Management Division (RMD or LP-40) Strategic Risk Group (LP-40). The incumbent is the supervisor for the...

  17. Budget Risk & Prioritization Analysis Tool

    Energy Science and Technology Software Center (OSTI)

    2010-12-31

    BRPAtool performs the following: ?Assists managers in making solid decisions on what scope/activities to reduce and/or eliminate, to meet constrained budgets, based on multiple risk factors ?Enables analysis of different budget scenarios ?Can analyze risks and cost for each activity based on technical, quantifiable risk criteria and management-determined risks ?Real-time analysis ?Enables managers to determine the multipliers and where funding is best applied ?Promotes solid budget defense

  18. Risk perception in developing countries

    SciTech Connect (OSTI)

    Wilbanks, T.J.; Rayner, S.F.

    1985-02-15

    The paper briefly reviews: (1) what risk perception means to most people in developing countries; (2) some of the modern-technology-related risks to which people in these countries are exposed; and (3) some research evidence about risk perception that gives hints about how such perceptions will evolve in developing countries. (ACR)

  19. Regulatory cost-risk study

    SciTech Connect (OSTI)

    Not Available

    1983-04-01

    This study is intended to provide some quantitative perspective by selecting certain examples of criteria for which estimates of risks and costs can be obtained, and the balance of the various risks, (i.e., internal versus external risks), can be put into perspective. 35 refs., 39 tabs. (JDB)

  20. NGNP Risk Management Database: A Model for Managing Risk

    SciTech Connect (OSTI)

    John Collins

    2009-09-01

    To facilitate the implementation of the Risk Management Plan, the Next Generation Nuclear Plant (NGNP) Project has developed and employed an analytical software tool called the NGNP Risk Management System (RMS). A relational database developed in Microsoft Access, the RMS provides conventional database utility including data maintenance, archiving, configuration control, and query ability. Additionally, the tools design provides a number of unique capabilities specifically designed to facilitate the development and execution of activities outlined in the Risk Management Plan. Specifically, the RMS provides the capability to establish the risk baseline, document and analyze the risk reduction plan, track the current risk reduction status, organize risks by reference configuration system, subsystem, and component (SSC) and Area, and increase the level of NGNP decision making.

  1. Ecological Risk Assessments

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Inorganic chemicals Dioxinsfurans High explosives Polycyclic aromatic hydrocarbons Other semivolatile organic compounds Polychlorinated biphenyls Pesticides Volatile organic ...

  2. Photovoltaic Degradation Risk: Preprint

    SciTech Connect (OSTI)

    Jordan, D. C.; Kurtz, S. R.

    2012-04-01

    The ability to accurately predict power delivery over the course of time is of vital importance to the growth of the photovoltaic (PV) industry. Important cost drivers include the efficiency with which sunlight is converted into power, how this relationship changes over time, and the uncertainty in this prediction. An accurate quantification of power decline over time, also known as degradation rate, is essential to all stakeholders - utility companies, integrators, investors, and researchers alike. In this paper we use a statistical approach based on historical data to quantify degradation rates, discern trends and quantify risks related to measurement uncertainties, number of measurements and methodologies.

  3. Eastern European risk management

    SciTech Connect (OSTI)

    Honey, J.A. )

    1992-01-01

    Here the authors assess Eastern European risk management practices through the evaluation of the nuclear power plants in the region. This evaluation is limited to the Soviet-designed and -built VVER-440 pressurized water reactors (PWRs) that are currently operating in Bulgaria, Czechoslovakia, Hungary, Russia, and the Ukraine and until recently operated at Greifswald in the former East Germany. This evaluation is based on the basic design of the plants, a safety evaluation of the Greifswald facility by representatives from the Federal Republic of Germany and personal visits by the author to Greifswald and Loviisa.

  4. Compliance & Risk Assessment | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    environmental hazards and risks to protect human health and safety and the environment. ... Plans. Risk evaluation tools such as the Human Health and Ecological Risk Methods ...

  5. Commentary: Risk Management and Reliability Design for Buildings

    SciTech Connect (OSTI)

    Berry, Dennis L.; Cranwell, Robert M.; Hunter, Regina L.

    1999-05-28

    Where there is a significant actuarial basis for decision making (e.g., the occurrence of fires in single-family dwellings), there is little incentive for formal risk management. Formal risk assessments are most useful in those cases where the value of the structure is high, many people may be affected, the societal perception of risk is high, consequences of a mishap would be severe, and the actuarial uncertainty is large. For these cases, there is little opportunity to obtain the necessary experiential data to make informed decisions, and the consequences in terms of money, lives, and societal confidence are severe enough to warrant a formal risk assessment. Other important factors include the symbolic value of the structure and vulnerability to single point failures. It is unlikely that formal risk management and assessment practices will or should replace the proven institutions of building codes and engineering practices. Nevertheless, formal risk assessment can provide valuable insights into the hazards threatening high-value and high-risk (perceived or actual) buildings and structures, which can in turn be translated into improved public health, safety, and security. The key is to choose and apply the right assessment tool to match the structure in question. Design-for-reliability concepts can be applied to buildings, bridges, transportation sys- tems, dams, and other structures. The use of these concepts could have the dual benefits of lowering life-cycle costs by reducing the necessity for maintenance and repair and of enhancing the saiiety and security of the structure's users.

  6. Risk Analysis Virtual ENvironment

    Energy Science and Technology Software Center (OSTI)

    2014-02-10

    RAVEN has 3 major functionalities: 1. Provides a Graphical User Interface for the pre- and post-processing of the RELAP-7 input and output. 2. Provides the capability to model nuclear power plants control logic for the RELAP-7 code and dynamic control of the accident scenario evolution. This capability is based on a software structure that realizes a direct connection between the RELAP-7 solver engine (MOOSE) and a python environment where the variables describing the plant statusmore » are accessible in a scripting environment. RAVEN support the generation of the probabilistic scenario control by supplying a wide range of probability and cumulative distribution functions and their inverse functions. 3. Provides a general environment to perform probability risk analysis for RELAP-7, RELAP-5 and any generic MOOSE based applications. The probabilistic analysis is performed by sampling the input space of the coupled code parameters and it is enhanced by using modern artificial intelligence algorithms that accelerate the identification of the areas of major risk (in the input parameter space). This environment also provides a graphical visualization capability to analyze the outcomes. Among other approaches, the classical Monte Carlo and Latin Hypercube sampling algorithms are available. For the acceleration of the convergence of the sampling methodologies, Support Vector Machines, Bayesian regression, and collocation stochastic polynomials chaos are implemented. The same methodologies here described could be used to solve optimization and uncertainties propagation problems using the RAVEN framework.« less

  7. Risk Analysis Virtual ENvironment

    SciTech Connect (OSTI)

    2014-02-10

    RAVEN has 3 major functionalities: 1. Provides a Graphical User Interface for the pre- and post-processing of the RELAP-7 input and output. 2. Provides the capability to model nuclear power plants control logic for the RELAP-7 code and dynamic control of the accident scenario evolution. This capability is based on a software structure that realizes a direct connection between the RELAP-7 solver engine (MOOSE) and a python environment where the variables describing the plant status are accessible in a scripting environment. RAVEN support the generation of the probabilistic scenario control by supplying a wide range of probability and cumulative distribution functions and their inverse functions. 3. Provides a general environment to perform probability risk analysis for RELAP-7, RELAP-5 and any generic MOOSE based applications. The probabilistic analysis is performed by sampling the input space of the coupled code parameters and it is enhanced by using modern artificial intelligence algorithms that accelerate the identification of the areas of major risk (in the input parameter space). This environment also provides a graphical visualization capability to analyze the outcomes. Among other approaches, the classical Monte Carlo and Latin Hypercube sampling algorithms are available. For the acceleration of the convergence of the sampling methodologies, Support Vector Machines, Bayesian regression, and collocation stochastic polynomials chaos are implemented. The same methodologies here described could be used to solve optimization and uncertainties propagation problems using the RAVEN framework.

  8. IEA-Risk Quantification and Risk Management in Renewable Energy...

    Open Energy Info (EERE)

    Energy Topics: Finance, Implementation, Market analysis Resource Type: Presentation, Lessons learnedbest practices Website: www.iea-retd.orgfilesRISK%20IEA-RETD%20(2011-6)....

  9. 2007 Wholesale Power Rate Case Final Proposal : Risk Analysis Study.

    SciTech Connect (OSTI)

    United States. Bonneville Power Administration.

    2006-07-01

    BPA's operating environment is filled with numerous uncertainties, and thus the rate-setting process must take into account a wide spectrum of risks. The objective of the Risk Analysis is to identify, model, and analyze the impacts that key risks have on BPA's net revenue (total revenues less total expenses). This is carried out in two distinct steps: a risk analysis step, in which the distributions, or profiles, of operating and non operating risks are defined, and a risk mitigation step, in which different rate tools are tested to assess their ability to recover BPA's costs in the face of this uncertainty. Two statistical models are used in the risk analysis step for this rate proposal, the Risk Analysis Model (RiskMod), and the Non-Operating Risk Model (NORM), while a third model, the ToolKit, is used to test the effectiveness of rate tools options in the risk mitigation step. RiskMod is discussed in Sections 2.1 through 2.4, the NORM is discussed in Section 2.5, and the ToolKit is discussed in Section 3. The models function together so that BPA can develop rates that cover all of its costs and provide a high probability of making its Treasury payments on time and in full during the rate period. By law, BPA's payments to Treasury are the lowest priority for revenue application, meaning that payments to Treasury are the first to be missed if financial reserves are insufficient to pay all bills on time. For this reason, BPA measures its potential for recovering costs in terms of probability of being able to make Treasury payments on time (also known as Treasury Payment Probability or TPP).

  10. Risk Management RM | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Risk Management RM Risk Management RM This tool is the process of continuous and iterative identification and control of project risks and opportunities. Risks can be technical, financial, or programmatic. The goal for the risk management system is to either avoid the risk's threat by taking preemptive action or to minimize the risks negative impacts on project performance. Project opportunities identified through the project risk management process can be handled in a similar manner with the

  11. DOE Releases Electricity Subsector Cybersecurity Risk Management...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Releases Electricity Subsector Cybersecurity Risk Management Process (RMP) Guideline DOE Releases Electricity Subsector Cybersecurity Risk Management Process (RMP) Guideline May ...

  12. AMERIND Risk Annual Conference and Trade Fair

    Broader source: Energy.gov [DOE]

    Hosted by the AMERIND Risk, this three-day conference includes risk management training, workers' safety, human resources, and more.

  13. Information needs for risk assessment

    SciTech Connect (OSTI)

    DeRosa, C.T.; Choudhury, H.; Schoeny, R.S.

    1990-12-31

    Risk assessment can be thought of as a conceptual approach to bridge the gap between the available data and the ultimate goal of characterizing the risk or hazard associated with a particular environmental problem. To lend consistency to and to promote quality in the process, the US Environmental Protection Agency (EPA) published Guidelines for Risk Assessment of Carcinogenicity, Developmental Toxicity, Germ Cell Mutagenicity and Exposure Assessment, and Risk Assessment of Chemical Mixtures. The guidelines provide a framework for organizing the information, evaluating data, and for carrying out the risk assessment in a scientifically plausible manner. In the absence of sufficient scientific information or when abundant data are available, the guidelines provide alternative methodologies that can be employed in the risk assessment. 4 refs., 3 figs., 2 tabs.

  14. Managing risk in software systems

    SciTech Connect (OSTI)

    Fletcher, S.K.; Jansma, R.M.; Murphy, M.D.

    1995-07-01

    A methodology for risk management in the design of software systems is presented. It spans security, safety, and correct operation of software within the context of its environment, and produces a risk analysis and documented risk management strategy. It is designed to be iteratively applied, to attain appropriate levels of detail throughout the analysis. The methodology and supporting tools are discussed. The methodology is critiqued relative to other research in the field. Some sample applications of the methodology are presented.

  15. EMAB Risk Subcommittee Interim Report

    Office of Environmental Management (EM)

    ADVISORY BOARD Incorporating Risk and Sustainability into Decision Making Submitted by the ... Secondly, the Subcommittee is tasked with reviewing"incorporating sustainability into the ...

  16. Budget Risk & Prioritization Analysis Tool

    Energy Science and Technology Software Center (OSTI)

    2010-12-31

    BRPAtool performs the following: •Assists managers in making solid decisions on what scope/activities to reduce and/or eliminate, to meet constrained budgets, based on multiple risk factors •Enables analysis of different budget scenarios •Can analyze risks and cost for each activity based on technical, quantifiable risk criteria and management-determined risks •Real-time analysis •Enables managers to determine the multipliers and where funding is best applied •Promotes solid budget defense

  17. ORISE: Crisis and Risk Communication

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    U.S. Department of Energy (DOE) Oak Ridge Office (ORO), ORISE provides crisis and risk communication support through the management of its Joint Information Center (JIC)...

  18. R00475--FM Risk Mgmt

    Energy Savers [EERE]

    to project success. The risk identification process on a project is typically one of brain- storming, and the usual rules of brainstorming apply: * The full project team should...

  19. Computer Security Risk Assessment

    Energy Science and Technology Software Center (OSTI)

    1992-02-11

    LAVA/CS (LAVA for Computer Security) is an application of the Los Alamos Vulnerability Assessment (LAVA) methodology specific to computer and information security. The software serves as a generic tool for identifying vulnerabilities in computer and information security safeguards systems. Although it does not perform a full risk assessment, the results from its analysis may provide valuable insights into security problems. LAVA/CS assumes that the system is exposed to both natural and environmental hazards and tomore » deliberate malevolent actions by either insiders or outsiders. The user in the process of answering the LAVA/CS questionnaire identifies missing safeguards in 34 areas ranging from password management to personnel security and internal audit practices. Specific safeguards protecting a generic set of assets (or targets) from a generic set of threats (or adversaries) are considered. There are four generic assets: the facility, the organization''s environment; the hardware, all computer-related hardware; the software, the information in machine-readable form stored both on-line or on transportable media; and the documents and displays, the information in human-readable form stored as hard-copy materials (manuals, reports, listings in full-size or microform), film, and screen displays. Two generic threats are considered: natural and environmental hazards, storms, fires, power abnormalities, water and accidental maintenance damage; and on-site human threats, both intentional and accidental acts attributable to a perpetrator on the facility''s premises.« less

  20. The risk assessment information system

    SciTech Connect (OSTI)

    Kerr, S.B.; Bonczek, R.R.; McGinn, C.W.; Land, M.L.; Bloom, L.D.; Sample, B.E.; Dolislager, F.G.

    1998-06-01

    In an effort to provide service-oriented environmental risk assessment expertise, the Department of Energy (DOE) Center for Risk Excellence (CRE) and DOE Oak Ridge Operations Office (ORO) are sponsoring Oak Ridge National Laboratory (ORNL) to develop a web-based system for disseminating risk tools and information to its users. This system, the Risk Assessment Information System (RAIS), was initially developed to support the site-specific needs of the DOE-ORO Environmental Restoration Risk Assessment Program. With support from the CRE, the system is currently being expanded to benefit all DOE risk information users and can be tailored to meet site-specific needs. Taking advantage of searchable and executable databases, menu-driven queries, and data downloads, using the latest World Wide Web technologies, the RAIS offers essential tools that are used in the risk assessment process or anywhere from project scoping to implementation. The RAIS tools can be located directly at http://risk.lsd.ornl.gov/homepage/rap{_}tool.htm or through the CRE`s homepage at http://www.doe.gov/riskcenter/home.html.

  1. Dynamical systems probabilistic risk assessment.

    SciTech Connect (OSTI)

    Denman, Matthew R.; Ames, Arlo Leroy

    2014-03-01

    Probabilistic Risk Assessment (PRA) is the primary tool used to risk-inform nuclear power regulatory and licensing activities. Risk-informed regulations are intended to reduce inherent conservatism in regulatory metrics (e.g., allowable operating conditions and technical specifications) which are built into the regulatory framework by quantifying both the total risk profile as well as the change in the risk profile caused by an event or action (e.g., in-service inspection procedures or power uprates). Dynamical Systems (DS) analysis has been used to understand unintended time-dependent feedbacks in both industrial and organizational settings. In dynamical systems analysis, feedback loops can be characterized and studied as a function of time to describe the changes to the reliability of plant Structures, Systems and Components (SSCs). While DS has been used in many subject areas, some even within the PRA community, it has not been applied toward creating long-time horizon, dynamic PRAs (with time scales ranging between days and decades depending upon the analysis). Understanding slowly developing dynamic effects, such as wear-out, on SSC reliabilities may be instrumental in ensuring a safely and reliably operating nuclear fleet. Improving the estimation of a plant's continuously changing risk profile will allow for more meaningful risk insights, greater stakeholder confidence in risk insights, and increased operational flexibility.

  2. Examining the Risk of Nuclear Trafficking

    SciTech Connect (OSTI)

    Balatsky, Galya; Severe, William R; Schoeneck, Jeffery

    2009-01-01

    The need to stop illicit trafficking of nuclear and radioactive materials around the world is undeniable and urgent. This issue is particularly evident due to the highly dangerous consequences of the risks involved, the known interest of terrorist groups in acquiring such materials and the vulnerability of theft and diversion of such materials. Yet the phenomenon of nuclear trafficking remains a subject where the unknown dominates what is known on the subject. The trafficking panel at the Institute for Nuclear Materials Management (INMM) Workshop on Reducing the Risk of Radioactive and Nuclear Materials that took place in Albuquerque, New Mexico, March 10-11, 2009, dealt with some of the issues associated with nuclear trafficking. Different points of view on how to better address trafficking and thwart perpetrator efforts were discussed. This paper presents some of these views and addresses practical measures that should be considered to improve the situation.

  3. High-Impact, Low-Frequency Event Risk Report

    Energy Savers [EERE]

    ... This upset may be severe, requiring the device to power down and restart, making IEMI a more significant threat to unmanned facilities, such as substations. Because of the use of ...

  4. Quantitative risk of oil tanker groundings. Master`s thesis

    SciTech Connect (OSTI)

    Amrozowicz, M.D.

    1996-06-01

    The culture, design, and operation of the maritime industry all contribute to create an error-inducing system. As oil tankers have become larger, the tolerance for error has decreased as the consequences have increased. Tankers are the largest contributor by vessel type to worldwide oil spill volume. Human error has consistently been attributed to 80 percent of the marine accidents. A closer look reveals that many accidents attributed to human error are system errors. In fact, the term human error is unwarranted in many high-risk accidents and its use is a perforation of the context. The maritime industry has been identified as a high risk operation, requiring an active risk management program. A probabilistic risk assessment (PRA) provides a formal process of determining the full range of possible adverse occurrences, probabilities, and expected costs for any undesirable event. A PRA can identify those areas that offer the greatest risk-reducing potential. This thesis focuses on the first level of a proposed three-level risk model to determine the probability of a tanker grounding. The approach utilizes fault trees and event trees and incorporates The Human Error Rate Prediction data to quantify individual errors. The result allows the identification of high-leverage factors in order to determine the most effective and efficient use of resources to reduce the probability of grounding; showing that the development of the Electronic Chart Display and Information System incorporated with the International Safety Management Code can significantly reduce the probability of grounding.

  5. Tank waste remediation system risk management list

    SciTech Connect (OSTI)

    Collard, L.B.

    1995-10-31

    The Tank Waste Remedation System (TWRS) Risk Management List and it`s subset of critical risks, the Critical Risk Management List, provide a tool to senior RL and WHC management (Level-1 and -2) to manage programmatic risks that may significantly impact the TWRS program. The programmatic risks include cost, schedule, and performance risks. Performance risk includes technical risk, supportability risk (such as maintainability and availability), and external risk (i.e., beyond program control, for example, changes in regulations). The risk information includes a description, its impacts, as evaluation of the likelihood, consequences and risk value, possible mitigating actions, and responsible RL and WHC managers. The issues that typically form the basis for the risks are presented in a separate table and the affected functions are provided on the management lists.

  6. PRA and Risk Informed Analysis

    SciTech Connect (OSTI)

    Bernsen, Sidney A.; Simonen, Fredric A.; Balkey, Kenneth R.

    2006-01-01

    The Boiler and Pressure Vessel Code (BPVC) of the American Society of Mechanical Engineers (ASME) has introduced a risk based approach into Section XI that covers Rules for Inservice Inspection of Nuclear Power Plant Components. The risk based approach requires application of the probabilistic risk assessments (PRA). Because no industry consensus standard existed for PRAs, ASME has developed a standard to evaluate the quality level of an available PRA needed to support a given risk based application. The paper describes the PRA standard, Section XI application of PRAs, and plans for broader applications of PRAs to other ASME nuclear codes and standards. The paper addresses several specific topics of interest to Section XI. Important consideration are special methods (surrogate components) used to overcome the lack of PRA treatments of passive components in PRAs. The approach allows calculations of conditional core damage probabilities both for component failures that cause initiating events and failures in standby systems that decrease the availability of these systems. The paper relates the explicit risk based methods of the new Section XI code cases to the implicit consideration of risk used in the development of Section XI. Other topics include the needed interactions of ISI engineers, plant operating staff, PRA specialists, and members of expert panels that review the risk based programs.

  7. Risk assessment in international operations

    SciTech Connect (OSTI)

    Stricklin, Daniela L.

    2008-11-15

    During international peace-keeping missions, a diverse number of non-battle hazards may be encountered, which range from heavily polluted areas, endemic disease, toxic industrial materials, local violence, traffic, and even psychological factors. Hence, elevated risk levels from a variety of sources are encountered during deployments. With the emphasis within the Swedish military moving from national defense towards prioritization of international missions in atypical environments, the risk of health consequences, including long term health effects, has received greater consideration. The Swedish military is interested in designing an optimal approach for assessment of health threats during deployments. The Medical Intelligence group at FOI CBRN Security and Defence in Umea has, on request from and in collaboration with the Swedish Armed Forces, reviewed a variety of international health threat and risk assessment models for military operations. Application of risk assessment methods used in different phases of military operations will be reviewed. An overview of different international approaches used in operational risk management (ORM) will be presented as well as a discussion of the specific needs and constraints for health risk assessment in military operations. This work highlights the specific challenges of risk assessment that are unique to the deployment setting such as the assessment of exposures to a variety of diverse hazards concurrently.

  8. Progress toward risk informed regulation

    SciTech Connect (OSTI)

    Rogers, K.C.

    1997-01-01

    For the last several years, the NRC, with encouragement from the industry, has been moving in the direction of risk informed regulation. This is consistent with the regulatory principle of efficiency, formally adopted by the Nuclear Regulatory Commission in 1991, which requires that regulatory activities be consistent with the degree of risk reduction they achieve. Probabilistic risk analysis has become the tool of choice for selecting the best of several alternatives. Closely related to risk informed regulation is the development of performance based rules. Such rules focus on the end result to be achieved. They do not specify the process, but instead establish the goals to be reached and how the achievement of those goals is to be judged. The inspection and enforcement activity is based on whether or not the goals have been met. The author goes on to offer comments on the history of the development of this process and its probable development in the future. He also addresses some issues which must be resolved or at least acknowledged. The success of risk informed regulation ultimately depends on having sufficiently reliable data to allow quantification of regulatory alternatives in terms of relative risk. Perhaps the area of human reliability and organizational performance has the greatest potential for improvement in reactor safety. The ability to model human performance is significantly less developed that the ability to model mechanical or electrical systems. The move toward risk informed, performance based regulation provides an unusual, perhaps unique, opportunity to establish a more rational, more effective basis for regulation.

  9. AVLIS Criticality risk assessment

    SciTech Connect (OSTI)

    Brereton, S.J., LLNL

    1998-04-29

    U-235 and uranium depleted in U-235) are cooled and accumulated in solid metallic form in canisters. The collected product and tails material is weighed and transferred into certified, critically safe, shipping containers (DOT specification 6M with 2R containment vessel). These will be temporarily stored, and then shipped offsite either for use by a fuel fabricator, or for disposal. Tails material will be packaged for disposal. A criticality risk assessment was performed for AVLIS IPD runs. In this analysis, the likelihood of occurrence of a criticality was examined. For the AVLIS process, there are a number of areas that have been specifically examined to assess whether or not the frequency of occurrence of a criticality is credible (frequency of occurrence > 10-6/yr). In this paper, we discuss only two of the areas: the separator and canister operations.

  10. Integrated risk information system (IRIS)

    SciTech Connect (OSTI)

    Tuxen, L.

    1990-12-31

    The Integrated Risk Information System (IRIS) is an electronic information system developed by the US Environmental Protection Agency (EPA) containing information related to health risk assessment. IRIS is the Agency`s primary vehicle for communication of chronic health hazard information that represents Agency consensus following comprehensive review by intra-Agency work groups. The original purpose for developing IRIS was to provide guidance to EPA personnel in making risk management decisions. This original purpose for developing IRIS was to guidance to EPA personnel in making risk management decisions. This role has expanded and evolved with wider access and use of the system. IRIS contains chemical-specific information in summary format for approximately 500 chemicals. IRIS is available to the general public on the National Library of Medicine`s Toxicology Data Network (TOXNET) and on diskettes through the National Technical Information Service (NTIS).

  11. Risk Informing Environmental Cleanup Priorities

    Broader source: Energy.gov [DOE]

    Presentation from the 2015 Annual Performance and Risk Assessment (P&RA) Community of Practice (CoP) Technical Exchange Meeting held in Richland, Washington on December 15-16, 2015.

  12. Federal Flood Risk Management Standard

    Broader source: Energy.gov [DOE]

    The Federal Flood Risk Management Standard builds upon Executive Order (E.O.) 11988 and is to be incorporated into existing Federal department and agency processes used to implement E.O. 11988.

  13. Proliferation and Terrorism Risk Assessment

    Broader source: Energy.gov [DOE]

    The objective of the PTRA program is to develop new tools and approaches for understanding, limiting, and managing the risks of proliferation and physical security for fuel cycle options. NE, in...

  14. Risk Management Tool Attributes: | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Risk Management Tool Attributes: Risk Management Tool Attributes: Risk Management Tool Attributes: (140.27 KB) More Documents & Publications Heating Ventilation and Air Conditioning Efficiency Idaho Operations AMWTP Fact Sheet Greenpower Trap Mufflerl System

  15. Mobius Risk Group LLC | Open Energy Information

    Open Energy Info (EERE)

    Mobius Risk Group LLC Jump to: navigation, search Name: Mobius Risk Group LLC Place: Houston, Texas Zip: TX 77056 Product: A risk advisor to energy-consuming companies, utilities...

  16. Conceptual Model of Offshore Wind Environmental Risk Evaluation System

    SciTech Connect (OSTI)

    Anderson, Richard M.; Copping, Andrea E.; Van Cleve, Frances B.; Unwin, Stephen D.; Hamilton, Erin L.

    2010-06-01

    In this report we describe the development of the Environmental Risk Evaluation System (ERES), a risk-informed analytical process for estimating the environmental risks associated with the construction and operation of offshore wind energy generation projects. The development of ERES for offshore wind is closely allied to a concurrent process undertaken to examine environmental effects of marine and hydrokinetic (MHK) energy generation, although specific risk-relevant attributes will differ between the MHK and offshore wind domains. During FY10, a conceptual design of ERES for offshore wind will be developed. The offshore wind ERES mockup described in this report will provide a preview of the functionality of a fully developed risk evaluation system that will use risk assessment techniques to determine priority stressors on aquatic organisms and environments from specific technology aspects, identify key uncertainties underlying high-risk issues, compile a wide-range of data types in an innovative and flexible data organizing scheme, and inform planning and decision processes with a transparent and technically robust decision-support tool. A fully functional version of ERES for offshore wind will be developed in a subsequent phase of the project.

  17. Qualitative methods for assessing risk

    SciTech Connect (OSTI)

    Mahn, J.A.; Hannaman, G.W.; Kryska, P.

    1995-04-01

    The Department of Energy`s (DOE) non-nuclear facilities generally require only a qualitative accident analysis to assess facility risks in accordance with DOE Order 5481.1B, Safety Analysis and Review System. Achieving a meaningful qualitative assessment of risk necessarily requires the use of suitable non-numerical assessment criteria. Typically, the methods and criteria for assigning facility-specific accident scenarios to the qualitative severity and likelihood classification system in the DOE order requires significant judgment in many applications. Systematic methods for more consistently assigning the total accident scenario frequency and associated consequences are required to substantiate and enhance future risk ranking between various activities at Sandia National Laboratories (SNL). SNL`s Risk Management and National Environmental Policy Act (NEPA) Department has developed an improved methodology for performing qualitative risk assessments in accordance wi the DOE order requirements. Products of this effort are an improved set of qualitative description that permit (1) definition of the severity for both technical and programmatic consequences that may result from a variety of accident scenarios, and (2) qualitative representation of the likelihood of occurrence. These sets of descriptions are intended to facilitate proper application of DOE criteria for assessing facility risks.

  18. Nuclear Facility Risk Ranking | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Facility Risk Ranking Nuclear Facility Risk Ranking Nuclear Facility Risk Ranking The CNS has purview of over ninety EM nuclear facilities across the DOE complex. To ensure that limited resources are applied in a risk-informed and balanced approach, the CNS performed a methodical assessment of the EM nuclear facilities. This risk-informed approach provides a data-driven foundation on which to construct a balanced set of operating plans and staff assignments. 2015 Risk Analysis Methodology.jpg

  19. Risk Assessment Technical Experts Working Group

    Broader source: Energy.gov [DOE]

    The Risk Assessment Technical Experts Working Group (RWG) was established to assist DOE in the appropriate and effective use of quantitative risk assessment in nuclear safety related activities.

  20. Envisory Financial Risk Management | Open Energy Information

    Open Energy Info (EERE)

    Envisory Financial Risk Management Jump to: navigation, search Name: Envisory Financial Risk Management Place: Mnchen, Bavaria, Germany Zip: 80331 Sector: Renewable Energy...

  1. Report: Technical Uncertainty and Risk Reduction

    Office of Environmental Management (EM)

    TECHNICAL UNCERTAINTY AND RISK REDUCTION Background In FY 2007 EMAB was tasked to assess EM's ability to reduce risk and technical uncertainty. Board members explored this topic ...

  2. AMERIND Risk Annual Conference and Trade Fair

    Broader source: Energy.gov [DOE]

    Hosted by the AMERIND Risk, this three-day conference includes trainings in risk management, workers' safety, human resources, and more.

  3. Uncertainties in risk assessment at USDOE facilities

    SciTech Connect (OSTI)

    Hamilton, L.D.; Holtzman, S.; Meinhold, A.F.; Morris, S.C.; Rowe, M.D.

    1994-01-01

    The United States Department of Energy (USDOE) has embarked on an ambitious program to remediate environmental contamination at its facilities. Decisions concerning cleanup goals, choices among cleanup technologies, and funding prioritization should be largely risk-based. Risk assessments will be used more extensively by the USDOE in the future. USDOE needs to develop and refine risk assessment methods and fund research to reduce major sources of uncertainty in risk assessments at USDOE facilities. The terms{open_quote} risk assessment{close_quote} and{open_quote} risk management{close_quote} are frequently confused. The National Research Council (1983) and the United States Environmental Protection Agency (USEPA, 1991a) described risk assessment as a scientific process that contributes to risk management. Risk assessment is the process of collecting, analyzing and integrating data and information to identify hazards, assess exposures and dose responses, and characterize risks. Risk characterization must include a clear presentation of {open_quotes}... the most significant data and uncertainties...{close_quotes} in an assessment. Significant data and uncertainties are {open_quotes}...those that define and explain the main risk conclusions{close_quotes}. Risk management integrates risk assessment information with other considerations, such as risk perceptions, socioeconomic and political factors, and statutes, to make and justify decisions. Risk assessments, as scientific processes, should be made independently of the other aspects of risk management (USEPA, 1991a), but current methods for assessing health risks are based on conservative regulatory principles, causing unnecessary public concern and misallocation of funds for remediation.

  4. 2007 Wholesale Power Rate Case Initial Proposal : Risk Analysis Study.

    SciTech Connect (OSTI)

    United States. Bonneville Power Administration.

    2005-11-01

    The Federal Columbia River Power System (FCRPS), operated on behalf of the ratepayers of the PNW by BPA and other Federal agencies, faces many uncertainties during the FY 2007-2009 rate period. Among these uncertainties, the largest revolve around hydro conditions, market prices and river operations for fish recovery. In order to provide a high probability of making its U.S. Treasury payments, BPA performs a Risk Analysis as part of its rate-making process. In this Risk Analysis, BPA identifies key risks, models their relationships, and then analyzes their impacts on net revenues (total revenues less expenses). BPA subsequently evaluates in the ToolKit Model the Treasury Payment Probability (TPP) resulting from the rates, risks, and risk mitigation measures described here and in the Wholesale Power Rate Development Study (WPRDS). If the TPP falls short of BPA's standard, additional risk mitigation revenues, such as PNRR and CRAC revenues are incorporated in the modeling in ToolKit until the TPP standard is met. Increased wholesale market price volatility and six years of drought have significantly changed the profile of risk and uncertainty facing BPA and its stakeholders. These present new challenges for BPA in its effort to keep its power rates as low as possible while fully meeting its obligations to the U.S. Treasury. As a result, the risk BPA faces in not receiving the level of secondary revenues that have been credited to power rates before receiving those funds is greater. In addition to market price volatility, BPA also faces uncertainty around the financial impacts of operations for fish programs in FY 2006 and in the FY 2007-2009 rate period. A new Biological Opinion or possible court-ordered change to river operations in FY 2006 through FY 2009 may reduce BPA's net revenues included Initial Proposal. Finally, the FY 2007-2009 risk analysis includes new operational risks as well as a more comprehensive analysis of non-operating risks. Both the operational

  5. Accelerated cleanup risk reduction

    SciTech Connect (OSTI)

    Knapp, R.B.; Aines, R.M.; Blake, R.G.; Copeland, A.B.; Newmark, R.L.; Tompson, A.F.B.

    1998-02-01

    There is no proven technology for remediating contaminant plume source regions in a heterogeneous subsurface. This project is an interdisciplinary effort to develop the requisite new technologies so that will be rapidly accepted by the remediation community. Our technology focus is hydrous pyrolysis/oxidation (HPO) which is a novel in situ thermal technique. We have expanded this core technology to leverage the action of steam injection and place an in situ microbial filter downstream to intercept and destroy the accelerated movement of contaminated groundwater. Most contaminant plume source regions, including the chlorinated solvent plume at LLNL, are in subsurface media characterized by a wide range in hydraulic conductivity. At LLNL, the main conduits for contaminant transport are buried stream channels composed of gravels and sands; these have a hydraulic conductivity in the range of 10{sup -1} to 10{sup -2} cm/s. Clay and silt units with a hydraulic conductivity of 10{sup -1} to 10{sup -6} cm/s bound these buried channels; these are barriers to groundwater movement and contain the highest contaminant concentrations in the source region. New remediation technologies are required because the current ones preferentially access the high conductivity units. HPO is an innovative process for the in situ destruction of contaminants in the entire subsurface. It operates by the injection of steam. We have demonstrated in laboratory experiments that many contaminants rapidly oxidize to harmless compounds at temperatures easily achieved by injecting steam, provided sufficient dissolved oxygen is present. One important challenge in a heterogeneous source region is getting heat, contaminants, and an oxidizing agent in the same place at the same time. We have used the NUFT computer program to simulate the cyclic injection of steam into a contaminated aquifer for design of a field demonstration. We used an 8 hour, steam/oxygen injection cycle followed by a 56 hour relaxation

  6. Risk assessment for the Waste Technologies Industries (WTI) hazardous waste incineration facility (East Liverpool, Ohio). Volume 5. Human health risk assessment; evaluation of potential risks from multipathway exposure to emissions

    SciTech Connect (OSTI)

    1997-05-01

    The report provide estimates of: (1) individual risks based on central tendency exposure; (2) individual risks based on maximum environmental concentrations; (3) risks to highly exposed or susceptible subgroups of the population (e.g., subsistence farmers and school children); (4) risks associated with specific activities that may result in elevated exposures (e.g., subsistence fishermen and deer hunters); and (5) population risk. This approach allows for the estimation of risks to specific segments of the population taking into consideration activity patterns, number of individuals, and actual locations of individuals in these subgroups with respect to the facility. The fate and transport modeling of emissions from the facility to estimate exposures to identified subgroups is described.

  7. EMAB Meeting - December 2011 | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    1 EMAB Meeting - December 2011 ENVIRONMENTAL MANAGEMENT ADVISORY BOARD US Department of Energy 1000 Independence Avenue, SW * Washington DC 20585 Forrestal Building Room 8E-089 Documents Available for Download EMAB Meeting Minutes for December 5, 2011 (246.28 KB) EMAB Meeting Agenda December 5, 2011 (49.14 KB) Tank Waste Strategy Update (2.23 MB) EM American Recovery and Reinvestment Act Update (7.26 MB) Report: Removal of EM Projects from the GAO High Risk List: Strategies for Improving the

  8. Role of LEPCs in risk management and risk communication

    SciTech Connect (OSTI)

    Mannan, M.

    1995-12-31

    Under Section 112(r) of Title III of the Clean Air Act Amendments, the US Environmental Protection Agency (EPA) is required to develop regulations that would require development and implementation of risk management programs at facilities that manufacture, process, use, store, or otherwise handle regulated substances in quantities that exceed specified threshold quantities. On January 31, 1994, EPA published the final rule establishing the List of Regulated Substances and Thresholds for Accidental Release Prevention. The proposed rule will require covered facilities to develop and implement a risk management program. The proposed rule will also require facilities to communicate various information to the local emergency planning committee (LEPC). This information may be provided in the form of consultation and communication during the development of various elements of the risk management program and/or by providing access to the risk management plan (RMP). These requirements not only place an additional regulatory burden on facilities but also create the need for the LEPCs to start planning for strategies to deal with significant amount of technical information in a meaningful and effective manner. This paper presents a summary of EPA`s proposed rule, the role of LEPCs in the implementation of many aspects of the rule, and a description of the potential contents of an RMP. Covered facilities as well as the LEPCs may gain a significant advantage by engaging in early dialogue and proactive education to determine mutual needs.

  9. Merging high resolution geophysical and geochemical surveys to...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    combine a suite of high resolution geophysical and geochemical techniques to reduce exploration risk by characterizing hydrothermal alteration, fault geometries and relationships. ...

  10. Air Risk Information Support Center

    SciTech Connect (OSTI)

    Shoaf, C.R.; Guth, D.J.

    1990-12-31

    The Air Risk Information Support Center (Air RISC) was initiated in early 1988 by the US Environmental Protection Agency`s (EPA) Office of Health and Environmental Assessment (OHEA) and the Office of Air Quality Planning and Standards (OAQPS) as a technology transfer effort that would focus on providing information to state and local environmental agencies and to EPA Regional Offices in the areas of health, risk, and exposure assessment for toxic air pollutants. Technical information is fostered and disseminated by Air RISCs three primary activities: (1) a {open_quotes}hotline{close_quotes}, (2) quick turn-around technical assistance projects, and (3) general technical guidance projects. 1 ref., 2 figs.

  11. Initial Decision and Risk Analysis

    SciTech Connect (OSTI)

    Engel, David W.

    2012-02-29

    Decision and Risk Analysis capabilities will be developed for industry consideration and possible adoption within Year 1. These tools will provide a methodology for merging qualitative ranking of technology maturity and acknowledged risk contributors with quantitative metrics that drive investment decision processes. Methods and tools will be initially introduced as applications to the A650.1 case study, but modular spreadsheets and analysis routines will be offered to industry collaborators as soon as possible to stimulate user feedback and co-development opportunities.

  12. Overview of the Hanford risk management plan

    SciTech Connect (OSTI)

    Halverson, T.G.

    1998-03-26

    The Project Hanford Management Contract called for the enhancement of site-wide decision processes, and development of a Hanford Risk Management Plan to adopt or develop a risk management system for the Hanford Site. This Plan provides a consistent foundation for Site issues and addresses site-wide management of risks of all types. It supports the Department of Energy planning and sitewide decision making policy. Added to this requirement is a risk performance report to characterize the risk management accomplishments. This paper presents the development of risk management within the context of work planning and performance. Also discussed are four risk elements which add value to the context.

  13. Managing risks and hazardous in industrial operations

    SciTech Connect (OSTI)

    Almaula, S.C.

    1996-12-31

    The main objective of this paper is to demonstrate that it makes good business sense to identify risks and hazards of an operation and take appropriate steps to manage them effectively. Developing and implementing an effective risk and hazard management plan also contibutes to other industry requirements and standards. Development of a risk management system, key elements of a risk management plan, and hazards and risk analysis methods are outlined. Comparing potential risk to the cost of prevention is also discussed. It is estimated that the cost of developing and preparing the first risk management plan varies between $50,000 to $200,000. 3 refs., 2 figs., 1 tab.

  14. Risk Management Techniques and Practice Workshop Workshop Report

    SciTech Connect (OSTI)

    Quinn, T; Zosel, M

    2008-12-02

    At the request of the Department of Energy (DOE) Office of Science (SC), Lawrence Livermore National Laboratory (LLNL) hosted a two-day Risk Management Techniques and Practice (RMTAP) workshop held September 18-19 at the Hotel Nikko in San Francisco. The purpose of the workshop, which was sponsored by the SC/Advanced Scientific Computing Research (ASCR) program and the National Nuclear Security Administration (NNSA)/Advanced Simulation and Computing (ASC) program, was to assess current and emerging techniques, practices, and lessons learned for effectively identifying, understanding, managing, and mitigating the risks associated with acquiring leading-edge computing systems at high-performance computing centers (HPCCs). Representatives from fifteen high-performance computing (HPC) organizations, four HPC vendor partners, and three government agencies attended the workshop. The overall workshop findings were: (1) Standard risk management techniques and tools are in the aggregate applicable to projects at HPCCs and are commonly employed by the HPC community; (2) HPC projects have characteristics that necessitate a tailoring of the standard risk management practices; (3) All HPCC acquisition projects can benefit by employing risk management, but the specific choice of risk management processes and tools is less important to the success of the project; (4) The special relationship between the HPCCs and HPC vendors must be reflected in the risk management strategy; (5) Best practices findings include developing a prioritized risk register with special attention to the top risks, establishing a practice of regular meetings and status updates with the platform partner, supporting regular and open reviews that engage the interests and expertise of a wide range of staff and stakeholders, and documenting and sharing the acquisition/build/deployment experience; and (6) Top risk categories include system scaling issues, request for proposal/contract and acceptance testing, and

  15. Truck transport of RAM: Risk effects of avoiding metropolitan areas

    SciTech Connect (OSTI)

    Mills, G.S.; Neuhauser, K.S.

    1997-11-01

    In the transport of radioactive material (RAM), e.g., spent nuclear fuel (SNF), stakeholders are generally most concerned about risks in high population density areas along transportation routes because of the perceived high consequences of potential accidents. The most significant portions of a transcontinental route and an alternative examined previously were evaluated again using population density data derived from US Census Block data. This method of characterizing population that adjoins route segments offers improved resolution of population density variations, especially in high population density areas along typical transport routes. Calculated incident free doses and accident dose risks for these routes, and the rural, suburban and urban segments are presented for comparison of their relative magnitudes. The results indicate that modification of this route to avoid major metropolitan areas through use of non-Interstate highways increases total risk yet does not eliminate a relatively small urban component of the accident dose risk. This conclusion is not altered by improved resolution of route segments adjoining high density populations.

  16. Integrated Disposal Facility Risk Assessment

    SciTech Connect (OSTI)

    MANN, F. M.

    2003-06-03

    An environmental risk assessment associated with the disposal of projected Immobilized Low-Activity Waste, solid wastes and failed or decommissioned melters in an Integrated Disposal Facility was performed. Based on the analyses all performance objectives associated with the groundwater, air, and intruder pathways were met.

  17. An Introduction to Risk with a Focus on Design Diversity in the Stockpile

    SciTech Connect (OSTI)

    Noone, Bailey C

    2012-08-13

    The maintenance and security of nuclear weapons in the stockpile involves decisions based on risk analysis and quantitative measures of risk. Risk is a factor in all decisions, a particularly important factor in decisions of a large scale. One example of high-risk decisions we will discuss is the risk involved in design diversity within the stockpile of nuclear weapons arsenal. Risk is defined as 'possibility of loss or injury' and the 'degree of probability of such loss' (Kaplan and Garrick 12). To introduce the risk involved with maintaining the weapons stockpile we will draw a parallel to the design and maintenance of Southwest Airlines fleet of Boeing 737 planes. The clear benefits for cost savings in maintenance of having a uniform fleet are what historically drove Southwest to have only Boeing 737s in their fleet. Less money and resources are need for maintenance, training, and materials. Naturally, risk accompanies those benefits. A defect in a part of the plane indicates a potential defect in that same part in all the planes of the fleet. As a result, safety, business, and credibility are at risk. How much variety or diversity does the fleet need to mitigate that risk? With that question in mind, a balance is needed to accommodate the different risks and benefits of the situation. In a similar way, risk is analyzed for the design and maintenance of nuclear weapons in the stockpile. In conclusion, risk must be as low as possible when it comes to the nuclear weapons stockpile. Design and care to keep the stockpile healthy involves all aspects of risk management. Design diversity is a method that helps to mitigate risk, and to help balance options in stockpile stewardship.

  18. A total risk assessment methodology for security assessment.

    SciTech Connect (OSTI)

    Aguilar, Richard; Pless, Daniel J.; Kaplan, Paul Garry; Silva, Consuelo Juanita; Rhea, Ronald Edward; Wyss, Gregory Dane; Conrad, Stephen Hamilton

    2009-06-01

    Sandia National Laboratories performed a two-year Laboratory Directed Research and Development project to develop a new collaborative risk assessment method to enable decision makers to fully consider the interrelationships between threat, vulnerability, and consequence. A five-step Total Risk Assessment Methodology was developed to enable interdisciplinary collaborative risk assessment by experts from these disciplines. The objective of this process is promote effective risk management by enabling analysts to identify scenarios that are simultaneously achievable by an adversary, desirable to the adversary, and of concern to the system owner or to society. The basic steps are risk identification, collaborative scenario refinement and evaluation, scenario cohort identification and risk ranking, threat chain mitigation analysis, and residual risk assessment. The method is highly iterative, especially with regard to scenario refinement and evaluation. The Total Risk Assessment Methodology includes objective consideration of relative attack likelihood instead of subjective expert judgment. The 'probability of attack' is not computed, but the relative likelihood for each scenario is assessed through identifying and analyzing scenario cohort groups, which are groups of scenarios with comparable qualities to the scenario being analyzed at both this and other targets. Scenarios for the target under consideration and other targets are placed into cohort groups under an established ranking process that reflects the following three factors: known targeting, achievable consequences, and the resources required for an adversary to have a high likelihood of success. The development of these target cohort groups implements, mathematically, the idea that adversaries are actively choosing among possible attack scenarios and avoiding scenarios that would be significantly suboptimal to their objectives. An adversary who can choose among only a few comparable targets and scenarios (a

  19. Mathematical models for risk assessment

    SciTech Connect (OSTI)

    Zaikin, S.A.

    1995-12-01

    The use of mathematical models in risk assessment results in the proper understanding of many aspects of chemical exposure and allows to make more actual decisions. Our project ISCRA (Integrated Systems of Complex Risk Assessment) has the aim to create integrated systems of algorythms for prediction of pollutants` exposure on human and environmental health and to apply them for environmental monitoring, and decision-making. Mathematical model {open_quotes}MASTER{close_quotes} (Mathematical Algorythm of SimulaTion of Environmental Risk) represents the complex of algorythmical blocks and is intended for the prediction of danger of pollutants` exposure for human and environmental risk. Model LIMES (LIMits EStimation) is developed for prognosis of safety concentrations of pollutants in the environment both in the case of isolated exposure and in the case of complex exposure for concrete location. Model QUANT (QUANtity of Toxicant) represents the multicompartmental physiological pharmacokinetic model describing absorption, distribution, fate, metabolism, and elimination of pollutants in the body of different groups of human population, as a result of the different kind of exposure. Decision support system CLEVER (Complex LEVE1 of Risk) predicts the probability and the degree of development of unfavourable effects as result of exposure of pollutant on human health. System is based on the data of epidemiological and experimental researches and includes several mathematical models for analysis of {open_quotes}dose-time-response{close_quotes} relations and information about clinical symptoms of diseases. Model CEP (Combination Effect Prognosis) contains probabilistic algorythms for forecasting the effect of simultaneous impact of several factors polluting the environment. The result of the program work is the prediction of an independent exposure of two or more factors, and intensification or weakening of exposure in depending on factors` interactions.

  20. Assuring quality in high-consequence engineering

    SciTech Connect (OSTI)

    Hoover, Marcey L.; Kolb, Rachel R.

    2014-03-01

    In high-consequence engineering organizations, such as Sandia, quality assurance may be heavily dependent on staff competency. Competency-dependent quality assurance models are at risk when the environment changes, as it has with increasing attrition rates, budget and schedule cuts, and competing program priorities. Risks in Sandia's competency-dependent culture can be mitigated through changes to hiring, training, and customer engagement approaches to manage people, partners, and products. Sandia's technical quality engineering organization has been able to mitigate corporate-level risks by driving changes that benefit all departments, and in doing so has assured Sandia's commitment to excellence in high-consequence engineering and national service.

  1. Gasbuggy Site Assessment and Risk Evaluation

    SciTech Connect (OSTI)

    2011-03-01

    The Gasbuggy site is in northern New Mexico in the San Juan Basin, Rio Arriba County (Figure 1-1). The Gasbuggy experiment was designed to evaluate the use of a nuclear detonation to enhance natural gas production from the Pictured Cliffs Formation, a tight, gas-bearing sandstone formation. The 29-kiloton-yield nuclear device was placed in a 17.5-inch wellbore at 4,240 feet (ft) below ground surface (bgs), approximately 40 ft below the Pictured Cliffs/Lewis shale contact, in an attempt to force the cavity/chimney formed by the detonation up into the Pictured Cliffs Sandstone. The test was conducted below the southwest quarter of Section 36, Township 29 North, Range 4 West, New Mexico Principal Meridian. The device was detonated on December 10, 1967, creating a 335-ft-high chimney above the detonation point and a cavity 160 ft in diameter. The gas produced from GB-ER (the emplacement and reentry well) during the post-detonation production tests was radioactive and diluted, primarily by carbon dioxide. After 2 years, the energy content of the gas had recovered to 80 percent of the value of gas in conventionally developed wells in the area. There is currently no technology capable of remediating deep underground nuclear detonation cavities and chimneys. Consequently, the U.S. Department of Energy (DOE) must continue to manage the Gasbuggy site to ensure that no inadvertent intrusion into the residual contamination occurs. DOE has complete control over the 1/4 section (160 acres) containing the shot cavity, and no drilling is permitted on that property. However, oil and gas leases are on the surrounding land. Therefore, the most likely route of intrusion and potential exposure would be through contaminated natural gas or contaminated water migrating into a producing natural gas well outside the immediate vicinity of ground zero. The purpose of this report is to describe the current site conditions and evaluate the potential health risks posed by the most plausible

  2. Development and validation of instantaneous risk model in nuclear power plant's risk monitor

    SciTech Connect (OSTI)

    Wang, J.; Li, Y.; Wang, F.; Wang, J.; Hu, L.

    2012-07-01

    The instantaneous risk model is the fundament of calculation and analysis in a risk monitor. This study focused on the development and validation of an instantaneous risk model. Therefore the principles converting from the baseline risk model to the instantaneous risk model were studied and separated trains' failure modes modeling method was developed. The development and validation process in an operating nuclear power plant's risk monitor were also introduced. Correctness of instantaneous risk model and rationality of converting method were demonstrated by comparison with the result of baseline risk model. (authors)

  3. High Cost/High Risk Components to Chalcogenide Molded Lens Model: Molding Preforms and Mold Technology

    SciTech Connect (OSTI)

    Bernacki, Bruce E.

    2012-10-05

    This brief report contains a critique of two key components of FiveFocal's cost model for glass compression molding of chalcogenide lenses for infrared applications. Molding preforms and mold technology have the greatest influence on the ultimate cost of the product and help determine the volumes needed to select glass molding over conventional single-point diamond turning or grinding and polishing. This brief report highlights key areas of both technologies with recommendations for further study.

  4. Transportation scenarios for risk analysis.

    SciTech Connect (OSTI)

    Weiner, Ruth F.

    2010-09-01

    Transportation risk, like any risk, is defined by the risk triplet: what can happen (the scenario), how likely it is (the probability), and the resulting consequences. This paper evaluates the development of transportation scenarios, the associated probabilities, and the consequences. The most likely radioactive materials transportation scenario is routine, incident-free transportation, which has a probability indistinguishable from unity. Accident scenarios in radioactive materials transportation are of three different types: accidents in which there is no impact on the radioactive cargo, accidents in which some gamma shielding may be lost but there is no release of radioactive material, and accident in which radioactive material may potentially be released. Accident frequencies, obtainable from recorded data validated by the U.S. Department of Transportation, are considered equivalent to accident probabilities in this study. Probabilities of different types of accidents are conditional probabilities, conditional on an accident occurring, and are developed from event trees. Development of all of these probabilities and the associated highway and rail accident event trees are discussed in this paper.

  5. Towards secure virtual directories : a risk analysis framework.

    SciTech Connect (OSTI)

    Claycomb, William R.

    2010-07-01

    Directory services are used by almost every enterprise computing environment to provide data concerning users, computers, contacts, and other objects. Virtual directories are components that provide directory services in a highly customized manner. Unfortunately, though the use of virtual directory services are widespread, an analysis of risks posed by their unique position and architecture has not been completed. We present a detailed analysis of six attacks to virtual directory services, including steps for detection and prevention. We also describe various categories of attack risks, and discuss what is necessary to launch an attack on virtual directories. Finally, we present a framework to use in analyzing risks to individual enterprise computing virtual directory instances. We show how to apply this framework to an example implementation, and discuss the benefits of doing so.

  6. Assessing Risk and Driving Risk Mitigation for First-of-a-Kind Advanced Reactors

    SciTech Connect (OSTI)

    John W. Collins

    2011-09-01

    Planning and decision making amidst programmatic and technological risks represent significant challenges for projects. This presentation addresses the four step risk-assessment process needed to determine clear path forward to mature needed technology and design, license, and construct advanced nuclear power plants, which have never been built before, including Small Modular Reactors. This four step process has been carefully applied to the Next Generation Nuclear Plant. STEP 1 - Risk Identification Risks are identified, collected, and categorized as technical risks, programmatic risks, and project risks, each of which result in cost and schedule impacts if realized. These include risks arising from the use of technologies not previously demonstrated in a relevant application. These risks include normal and accident scenarios which the SMR could experience including events that cause the disablement of engineered safety features (typically documented in Phenomena Identification Ranking Tables (PIRT) as produced with the Nuclear Regulatory Commission) and design needs which must be addressed to further detail the design. Product - Project Risk Register contained in a database with sorting, presentation, rollup, risk work off functionality similar to the NGNP Risk Management System . STEP 2 - Risk Quantification The risks contained in the risk register are then scored for probability of occurrence and severity of consequence, if realized. Here the scoring methodology is established and the basis for the scoring is well documented. Product - Quantified project risk register with documented basis for scoring. STEP 3 - Risk Handling Strategy Risks are mitigated by applying a systematic approach to maturing the technology through Research and Development, modeling, test, and design. A Technology Readiness Assessment is performed to determine baseline Technology Readiness Levels (TRL). Tasks needed to mature the technology are developed and documented in a roadmap

  7. RISK ASSESSMENT TECHNICAL EXPERT WORKING GROUP

    Office of Energy Efficiency and Renewable Energy (EERE)

    The Risk Assessment Technical Expert Working Group (RWG) is established to assist the Department of Energy (DOE) with the appropriate and effective use of quantitative risk assessment in nuclear...

  8. Nuclear Facility Risk Ranking | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    risk-informed and balanced approach, the CNS performed a methodical assessment of the EM nuclear facilities. This risk-informed approach provides a data-driven foundation on which...

  9. Evaluating the risk-reduction benefits of wind energy

    SciTech Connect (OSTI)

    Brower, M.C.; Bell, K.; Spinney, P.

    1997-05-01

    The question of uncertainty and risk in electric utility resource planning has received considerable attention in recent years. During the 1980s, many utilities suffered financial losses because of unexpectedly high plant construction costs and low growth in electricity demand. In addition, the introduction of competition to the electric industry is creating new risks for power companies. No longer will utilities be able to count on regulatory protections and a base of captive consumers to provide a stable market and adequate return on their investments. Alternative risk management strategies will have to be considered instead. One approach to managing risk is for a utility company to invest in diverse power sources such as wind power plants. Since wind plants consume no fuel, can be built in relatively small increments with short construction lead times, and generate no pollutants, it is often said that they offer significant protection from risks associated with conventional fossil-fuel power plants. So far there have been few efforts to quantify these benefits, however. The study compares the costs and risks of two competing resource options, a gas-fired combined cycle plant and a wind plant, both utility-owned, through decision analysis. The case study utility is Texas Utilities Electric, a very large investor-owned company serving an area with substantial, high-quality wind resources. The authors chose a specific moment in the future - the year 2003 - when the utility currently plans to build a large fossil-fueled power plant, and examined the implications for the utility`s expected revenues, costs, and profits if a wind plant were to be built instead.

  10. Improved understanding of geologic CO{sub 2} storage processes requires risk-driven field experiments

    SciTech Connect (OSTI)

    Oldenburg, C.M.

    2011-06-01

    The need for risk-driven field experiments for CO{sub 2} geologic storage processes to complement ongoing pilot-scale demonstrations is discussed. These risk-driven field experiments would be aimed at understanding the circumstances under which things can go wrong with a CO{sub 2} capture and storage (CCS) project and cause it to fail, as distinguished from accomplishing this end using demonstration and industrial scale sites. Such risk-driven tests would complement risk-assessment efforts that have already been carried out by providing opportunities to validate risk models. In addition to experimenting with high-risk scenarios, these controlled field experiments could help validate monitoring approaches to improve performance assessment and guide development of mitigation strategies.

  11. Risk-based inspection guide for Crystal River Unit 3 Nuclear Power Plant

    SciTech Connect (OSTI)

    Smith, B.W.; Dukelow, J.S.; Vo, T.V.; Harris, M.S.; Gore, B.F.; Hunt, S.T. )

    1991-06-01

    The Level 1 probabilistic risk assessment (PRA) for Crystal River Unit 3 (CR-3) has been analyzed to identify plant systems and components important to minimizing public risk, as measured by system contributions to plant core damage frequency, and to identify the primary failure modes for these components. The report presents a series of tables, organized by system and prioritized by risk importance, which identify components associated with 98% of the inspectable risk due to plant operation. The systems addressed, in descending order to risk importance are: Low Pressure Injection, AC Power, Service Water, Demineralized Water, High Pressure Injection, DC Power, Emergency Feedwater, Reactor Coolant Pressure Control, and Power Conversion. This ranking is based on the Fussell-Vesely measure of risk importance, i.e., the fraction of the total core damage frequency which involves failures of the system of interest. 3 refs., 9 figs., 13 tabs.

  12. United States Environmental Protection Agency: Use of risk assessment and risk management methodologies. Master's thesis

    SciTech Connect (OSTI)

    Lamuro, R.J.

    1992-09-30

    Make a full investigation of the policy implications and appropriate uses of risk assessment and risk management in regulatory programs under various Federal laws to prevent cancer and other chronic health effects which may result from exposure to hazardous substances. This is the primary mission of the Risk Assessment and Management Commission (Risk Commission). The Clean Air Act Amendments of 1990 (CAAA), created the Risk Commission reflecting Congress' concern over agency use of risk assessment and risk management techniques and methodologies to implement federal laws protective of human health. The Risk Commission is to consider: methods for measuring and describing risks of chronic health effects from hazardous substances; methods to reflect uncertainties associated with estimation techniques, and whether it is possible or desirable to develop a consistent risk assessment methodology or a consistent standard of acceptable risk for various federal programs.

  13. State and Regional Energy Risk Assessment Initiative

    Broader source: Energy.gov [DOE]

    OE is leading a State and Regional Energy Risk Assessment Initiative to help States better understand risks to their energy infrastructure so they can be better prepared to make informed decisions about their investments, resilience and hardening strategies, and asset management. As part of this Initiative, OE has developed a series of State and Regional Energy Risk Profiles that examine the relative magnitude of the risks that each State's energy infrastructure routinely encounters in comparison with the probable impacts.

  14. EPA`s risk assessment guidelines: Overview

    SciTech Connect (OSTI)

    Patton, D.E.

    1990-12-31

    The US Environmental Protection Agency (EPA) risk assessment guidelines for cancer, quantification, and exposure issues are discussed.

  15. Loan Specialist (Risk Management) | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Loan Specialist (Risk Management) Loan Specialist (Risk Management) Submitted by admin on Mon, 2016-08-08 00:15 Job Summary Organization Name Department Of Energy Agency SubElement Department of Energy Locations District of Columbia, District of Columbia Announcement Number DOE-MP-16-LP-00290-DE Job Summary This position is located in the U.S. Department of Energy (DOE), Loan Programs Office (LPO), Risk Management Division (RMD), and Enterprise Risk Management & Compliance Branch. The LPO

  16. Hydrogen Risk Assessment Model (HyRAM)

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Energy Storage Components and Systems Batteries Electric Drive Systems Hydrogen Materials & Components Compatibility Hydrogen Behavior Quantitative Risk Assessment Technical ...

  17. Advanced Test Reactor outage risk assessment

    SciTech Connect (OSTI)

    Thatcher, T.A.; Atkinson, S.A.

    1997-12-31

    Beginning in 1997, risk assessment was performed for each Advanced Test Reactor (ATR) outage aiding the coordination of plant configuration and work activities (maintenance, construction projects, etc.) to minimize the risk of reactor fuel damage and to improve defense-in-depth. The risk assessment activities move beyond simply meeting Technical Safety Requirements to increase the awareness of risk sensitive configurations, to focus increased attention on the higher risk activities, and to seek cost-effective design or operational changes that reduce risk. A detailed probabilistic risk assessment (PRA) had been performed to assess the risk of fuel damage during shutdown operations including heavy load handling. This resulted in several design changes to improve safety; however, evaluation of individual outages had not been performed previously and many risk insights were not being utilized in outage planning. The shutdown PRA provided the necessary framework for assessing relative and absolute risk levels and assessing defense-in-depth. Guidelines were written identifying combinations of equipment outages to avoid. Screening criteria were developed for the selection of work activities to receive review. Tabulation of inherent and work-related initiating events and their relative risk level versus plant mode has aided identification of the risk level the scheduled work involves. Preoutage reviews are conducted and post-outage risk assessment is documented to summarize the positive and negative aspects of the outage with regard to risk. The risk for the outage is compared to the risk level that would result from optimal scheduling of the work to be performed and to baseline or average past performance.

  18. A mathematically guided strategy for risk assessment and management.

    SciTech Connect (OSTI)

    Cooper, James Arlin

    2005-03-01

    Strategies for risk assessment and management of high consequence operations are often based on factors such as physical analysis, analysis of software and other logical processing, and analysis of statistically determined human actions. Conventional analysis methods work well for processing objective information. However, in practical situations, much or most of the data available are subjective. Also, there are potential resultant pitfalls where conventional analysis might be unrealistic, such as improperly using event tree and fault tree failure descriptions where failures or events are soft (partial) rather than crisp (binary), neglecting or misinterpreting dependence (positive, negative, correlation), and aggregating nonlinear contributions linearly. There are also personnel issues that transcend basic human factors statistics. For example, sustained productivity and safety in critical operations can depend on the morale of involved personnel. In addition, motivation is significantly influenced by 'latent effects', which are pre-occurring influences. This paper addresses these challenges and proposes techniques for subjective risk analysis, latent effects risk analysis and a hybrid analysis that also includes objective risk analysis. The goal is an improved strategy for risk management.

  19. Occult Breast Cancer: Scintimammography with High-Resolution...

    Office of Scientific and Technical Information (OSTI)

    Occult Breast Cancer: Scintimammography with High-Resolution Breast-specific Gamma Camera in Women at High Risk for Breast Cancer Citation Details In-Document Search Title: Occult ...

  20. GAO-04-986R Lawrence Livermore National Laboratory: Further Improvemen...

    Office of Environmental Management (EM)

    Security Administration (NNSA). 1 The University of California manages the lab under a cost-reimbursable contract with NNSA. The university is paid a management fee to operate the...

  1. Letter to GAO on Contract & Project Management (8 Nov 2010).pdf

    Office of Environmental Management (EM)

    Annual Financial Report | Department of Energy to Congress RE: Office of Civilian Radioactive Waste Management's Annual Financial Report Letter to Congress RE: Office of Civilian Radioactive Waste Management's Annual Financial Report The following document is a letter from the Secretary of Energy to the Honorable Joseph R. Biden regarding the U.S. Department of Energy's Office of Civilian Radioactive Waste Management's Annual Financial Report for the years ended September 30, 2009 and 2008

  2. Microsoft PowerPoint - Gao_2014_CINT-CNMS User Project Highlight...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Graphene oxide (GO) contains several chemical functional groups that are attached to the graphene basal plane and can be manipulated to tailor GO for specific applications. In this...

  3. GAO-11-879T Federal Real Property: Overreliance on Leasing Contributed...

    Office of Environmental Management (EM)

    enhance the use of real property by leasing nonexcess property to an individual or entity Food Conservation and Energy Act of 2008, P. L. No. 110-246, Section 7409 Department of...

  4. (SSS)GAO Metrics - Project Success 2015-04-29 1100.xls

    Broader source: Energy.gov (indexed) [DOE]

    ContractProject Management Performance Metrics FY 2015 Target FY 2015 Pre- & Post- CAP* Forecast Comment 1 Capital Asset Project Success: Complete 90% of capital asset projects at ...

  5. GAO-11-520T Federal Real Property: Progress Made on Planning...

    Broader source: Energy.gov (indexed) [DOE]

    Economic Development, Public Buildings and Emergency Management, Committee on Transportation and Infrastructure, House of Representatives FEDERAL REAL PROPERTY Progress Made on...

  6. GAO-15-305, DOE Real Property: Better Data and More Proactive...

    Office of Environmental Management (EM)

    DOE REAL PROPERTY Better Data and a More Proactive Approach Needed to Facilitate Property Disposal Report to the Chairman, Subcommittee on Energy and Water Development, Committee...

  7. Systems approach to project risk management

    SciTech Connect (OSTI)

    Kindinger, J. P.

    2002-01-01

    This paper describes the need for better performance in the planning and execution of projects and examines the capabilities of two different project risk analysis methods for improving project performance. A quantitative approach based on concepts and tools adopted from the disciplines of systems analysis, probabilistic risk analysis, and other fields is advocated for managing risk in large and complex research & development projects. This paper also provides an overview of how this system analysis approach for project risk management is being used at Los Alamos National Laboratory along with examples of quantitative risk analysis results and their application to improve project performance.

  8. Assessing Coal Unit Retirement Risk

    U.S. Energy Information Administration (EIA) Indexed Site

    Ventures Analysis 1901 N. Moore St. Arlington, VA 22209 (703) 276 8900 A S S E S S I N G C O A L U N I T R E T I R E M E N T R I S K Tom Hewson Principal June 14, 2016 Presentation for the US Energy Information Administration Workshop Coal Fleet Aging 1 COAL CAPACITY CHALLENGES E N E R G Y V E N T U R E S A N A L Y S I S , I N C .  Environmental Regulatory Risk-- Compliance often requires coal units to make large capital investment in additional retrofit control measures and/or increase their

  9. Recognizing and Assigning ESPC Risks and Responsibilities Using...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Using the Risk, Responsibility, and Performance Matrix Recognizing and Assigning ESPC Risks and Responsibilities Using the Risk, Responsibility, and Performance Matrix ...

  10. EO 13045: Protection of Children from Environmental Health Risks...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Environmental Health Risks and Safety Risks (1997) (As Amended by EO 13229 (2001) and EO 13296 (2003)) EO 13045: Protection of Children from Environmental Health Risks and ...

  11. First Capitol Risk Management LLC | Open Energy Information

    Open Energy Info (EERE)

    Capitol Risk Management LLC Jump to: navigation, search Name: First Capitol Risk Management, LLC Place: Galena, Illinois Zip: 61036 Product: First Capitol Risk Management...

  12. Risk Management Guide - DOE Directives, Delegations, and Requirements

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    7A, Risk Management Guide by John Makepeace Functional areas: Risk Management, Safety and Security This Guide provides non-mandatory risk management approaches for implementing the...

  13. Webinar: Genetically Modified Algae: A Risk-Benefit Assessment...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Algae: A Risk-Benefit Assessment Webinar: Genetically Modified Algae: A Risk-Benefit Assessment Genetically Modified (GM) Algae: A Risk-Benefit Assessment PDF icon...

  14. Seismic Analysis of Facilities and Evaluation of Risk | Department...

    Office of Environmental Management (EM)

    Seismic Analysis of Facilities and Evaluation of Risk Seismic Analysis of Facilities and Evaluation of Risk Seismic Analysis of Facilities and Evaluation of Risk Michael Salmon,...

  15. Microsoft PowerPoint - Financial Plan Risk Mitigation Master...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    within acceptable bounds BPA Financial Plan Workshop 5 Financial Plan Risk Metrics Agenda Origin of the Risk Metrics Issue History of risk mitigation measures and origin of...

  16. State and Regional Energy Risk Assessment Initiative | Department...

    Energy Savers [EERE]

    ... Energy Sector Risk Profile Nevada State of Nevada Energy Sector Risk Profile New Hampshire State of New Hampshire Energy Sector Risk Profile New Jersey State of New Jersey ...

  17. River Corridor Baseline Risk Assessment (RCBRA) Human Health...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    12, 2011 River Corridor Baseline Risk Assessment (RCBRA) Human Health Risk Assessment (Volume 2) * RCBRA Human Health Risk Assessment is final - Response provided to HAB ...

  18. State Energy Risk Assessment Initiative | Department of Energy

    Energy Savers [EERE]

    Mission Energy Infrastructure Modeling and Analysis State Energy Risk Assessment Initiative State Energy Risk Assessment Initiative OE is leading a State Energy Risk...

  19. Risk perception, risk evaluation and human values: cognitive bases of acceptability of a radioactive waste repository

    SciTech Connect (OSTI)

    Earle, T.C.; Lindell, M.K.; Rankin, W.L.

    1981-07-01

    Public acceptance of radioactive waste management alternatives depends in part on public perception of the associated risks. Three aspects of those perceived risks were explored in this study: (1) synthetic measures of risk perception based on judgments of probability and consequences; (2) acceptability of hypothetical radioactive waste policies, and (3) effects of human values on risk perception. Both the work on synthetic measures of risk perception and on the acceptability of hypothetical policies included investigations of three categories of risk: (1) Short-term public risk (affecting persons living when the wastes are created), (2) Long-term public risk (affecting persons living after the time the wastes were created), and (3) Occupational risk (affecting persons working with the radioactive wastes). The human values work related to public risk perception in general, across categories of persons affected. Respondents were selected according to a purposive sampling strategy.

  20. Initial Risk Analysis and Decision Making Framework

    SciTech Connect (OSTI)

    Engel, David W.

    2012-02-01

    Commercialization of new carbon capture simulation initiative (CCSI) technology will include two key elements of risk management, namely, technical risk (will process and plant performance be effective, safe, and reliable) and enterprise risk (can project losses and costs be controlled within the constraints of market demand to maintain profitability and investor confidence). Both of these elements of risk are incorporated into the risk analysis subtask of Task 7. Thus far, this subtask has developed a prototype demonstration tool that quantifies risk based on the expected profitability of expenditures when retrofitting carbon capture technology on a stylized 650 MW pulverized coal electric power generator. The prototype is based on the selection of specific technical and financial factors believed to be important determinants of the expected profitability of carbon capture, subject to uncertainty. The uncertainty surrounding the technical performance and financial variables selected thus far is propagated in a model that calculates the expected profitability of investments in carbon capture and measures risk in terms of variability in expected net returns from these investments. Given the preliminary nature of the results of this prototype, additional work is required to expand the scope of the model to include additional risk factors, additional information on extant and proposed risk factors, the results of a qualitative risk factor elicitation process, and feedback from utilities and other interested parties involved in the carbon capture project. Additional information on proposed distributions of these risk factors will be integrated into a commercial implementation framework for the purpose of a comparative technology investment analysis.

  1. Health risks in perspective: Judging health risks of energy technologies. Revision 5/94

    SciTech Connect (OSTI)

    Rowe, M.D.

    1992-09-01

    The purpose of this report is to provide perspective on the various risks to which man is routinely exposed. It serves as a basis for understanding the meaning of quantitative risk estimates and for comparing new or newly-discovered risks with other, better-understood risks. Specific emphasis is placed on health risks of energy technologies. This report is not a risk assessment; nor does it contain instructions on how to do a risk assessment. Rather, it provides background information on how most of us think about risks and why it is difficult to do it rationally, it provides a philosophy and data with which to do a better job of judging risks more rationally, and it provides an overview of where risks of energy technologies fit within the spectrum of all risks. Much of the quantitative information provided here is on relative risk of dying of various causes. This is not because risk of dying is seen as the most important kind of risk, but because the statistics on mortality rates by cause are the highest quality data available on health risks in the general population.

  2. High PRF high current switch

    DOE Patents [OSTI]

    Moran, Stuart L.; Hutcherson, R. Kenneth

    1990-03-27

    A triggerable, high voltage, high current, spark gap switch for use in pu power systems. The device comprises a pair of electrodes in a high pressure hydrogen environment that is triggered by introducing an arc between one electrode and a trigger pin. Unusually high repetition rates may be obtained by undervolting the switch, i.e., operating the trigger at voltages much below the self-breakdown voltage of the device.

  3. Development of a Risk-Based Comparison Methodology of Carbon Capture Technologies

    SciTech Connect (OSTI)

    Engel, David W.; Dalton, Angela C.; Dale, Crystal; Thompson, Julie; Leclaire, Rene; Edward, Bryan; Jones, Edward

    2014-06-01

    Given the varying degrees of maturity among existing carbon capture (CC) technology alternatives, an understanding of the inherent technical and financial risk and uncertainty associated with these competing technologies is requisite to the success of carbon capture as a viable solution to the greenhouse gas emission challenge. The availability of tools and capabilities to conduct rigorous, riskbased technology comparisons is thus highly desirable for directing valuable resources toward the technology option(s) with a high return on investment, superior carbon capture performance, and minimum risk. To address this research need, we introduce a novel risk-based technology comparison method supported by an integrated multi-domain risk model set to estimate risks related to technological maturity, technical performance, and profitability. Through a comparison between solid sorbent and liquid solvent systems, we illustrate the feasibility of estimating risk and quantifying uncertainty in a single domain (modular analytical capability) as well as across multiple risk dimensions (coupled analytical capability) for comparison. This method brings technological maturity and performance to bear on profitability projections, and carries risk and uncertainty modeling across domains via inter-model sharing of parameters, distributions, and input/output. The integration of the models facilitates multidimensional technology comparisons within a common probabilistic risk analysis framework. This approach and model set can equip potential technology adopters with the necessary computational capabilities to make risk-informed decisions about CC technology investment. The method and modeling effort can also be extended to other industries where robust tools and analytical capabilities are currently lacking for evaluating nascent technologies.

  4. Deciding which chemical mixtures risk assessment methods work best for what mixtures

    SciTech Connect (OSTI)

    Teuschler, Linda K.

    2007-09-01

    The most commonly used chemical mixtures risk assessment methods involve simple notions of additivity and toxicological similarity. Newer methods are emerging in response to the complexities of chemical mixture exposures and effects. Factors based on both science and policy drive decisions regarding whether to conduct a chemical mixtures risk assessment and, if so, which methods to employ. Scientific considerations are based on positive evidence of joint toxic action, elevated human exposure conditions or the potential for significant impacts on human health. Policy issues include legislative drivers that may mandate action even though adequate toxicity data on a specific mixture may not be available and risk assessment goals that impact the choice of risk assessment method to obtain the amount of health protection desired. This paper discusses three important concepts used to choose among available approaches for conducting a chemical mixtures risk assessment: (1) additive joint toxic action of mixture components; (2) toxicological interactions of mixture components; and (3) chemical composition of complex mixtures. It is proposed that scientific support for basic assumptions used in chemical mixtures risk assessment should be developed by expert panels, risk assessment methods experts, and laboratory toxicologists. This is imperative to further develop and refine quantitative methods and provide guidance on their appropriate applications. Risk assessors need scientific support for chemical mixtures risk assessment methods in the form of toxicological data on joint toxic action for high priority mixtures, statistical methods for analyzing dose-response for mixtures, and toxicological and statistical criteria for determining sufficient similarity of complex mixtures.

  5. Relative Hazard and Risk Measure Calculation Methodology

    SciTech Connect (OSTI)

    Stenner, Robert D.; Strenge, Dennis L.; Elder, Matthew S.

    2004-03-20

    The relative hazard (RH) and risk measure (RM) methodology and computer code is a health risk-based tool designed to allow managers and environmental decision makers the opportunity to readily consider human health risks (i.e., public and worker risks) in their screening-level analysis of alternative cleanup strategies. Environmental management decisions involve consideration of costs, schedules, regulatory requirements, health hazards, and risks. The RH-RM tool is a risk-based environmental management decision tool that allows managers the ability to predict and track health hazards and risks over time as they change in relation to mitigation and cleanup actions. Analysis of the hazards and risks associated with planned mitigation and cleanup actions provides a baseline against which alternative strategies can be compared. This new tool allows managers to explore “what if scenarios,” to better understand the impact of alternative mitigation and cleanup actions (i.e., alternatives to the planned actions) on health hazards and risks. This new tool allows managers to screen alternatives on the basis of human health risk and compare the results with cost and other factors pertinent to the decision. Once an alternative or a narrow set of alternatives are selected, it will then be more cost-effective to perform the detailed risk analysis necessary for programmatic and regulatory acceptance of the selected alternative. The RH-RM code has been integrated into the PNNL developed Framework for Risk Analysis In Multimedia Environmental Systems (FRAMES) to allow the input and output data of the RH-RM code to be readily shared with the more comprehensive risk analysis models, such as the PNNL developed Multimedia Environmental Pollutant Assessment System (MEPAS) model.

  6. Need for An Integrated Risk Model | Department of Energy

    Office of Environmental Management (EM)

    Need for An Integrated Risk Model Need for An Integrated Risk Model Need for An Integrated Risk Model Michael Salmon, LANL PDF icon Need for An Integrated Risk Model More Documents...

  7. Hanford Tank Farm interim storage phase probabilistic risk assessment outline

    SciTech Connect (OSTI)

    Not Available

    1994-05-19

    This report is the second in a series examining the risks for the high level waste (HLW) storage facilities at the Hanford Site. The first phase of the HTF PSA effort addressed risks from Tank 101-SY, only. Tank 101-SY was selected as the initial focus of the PSA because of its propensity to periodically release (burp) a mixture of flammable and toxic gases. This report expands the evaluation of Tank 101-SY to all 177 storage tanks. The 177 tanks are arranged into 18 farms and contain the HLW accumulated over 50 years of weapons material production work. A centerpiece of the remediation activity is the effort toward developing a permanent method for disposing of the HLW tank`s highly radioactive contents. One approach to risk based prioritization is to perform a PSA for the whole HLW tank farm complex to identify the highest risk tanks so that remediation planners and managers will have a more rational basis for allocating limited funds to the more critical areas. Section 3 presents the qualitative identification of generic initiators that could threaten to produce releases from one or more tanks. In section 4 a detailed accident sequence model is developed for each initiating event group. Section 5 defines the release categories to which the scenarios are assigned in the accident sequence model and presents analyses of the airborne and liquid source terms resulting from different release scenarios. The conditional consequences measured by worker or public exposure to radionuclides or hazardous chemicals and economic costs of cleanup and repair are analyzed in section 6. The results from all the previous sections are integrated to produce unconditional risk curves in frequency of exceedance format.

  8. Applications of risk management to waste combustion in boilers and industrial furnaces

    SciTech Connect (OSTI)

    Chrostowski, P.C.; Foster, S.A.; Kimball, H.J.

    1996-12-31

    Human health and ecological risk assessments have become routine for waste combustion in boilers and industrial furnaces (BIFs) as a result of USEPA`s Combustion Strategy, questions raised by citizens about the health effects of incineration, and the desire for the regulated community to have a level playing field regarding emissions regulations. The USEPA, National Academy of Sciences, various trade organizations, and individual researchers have published widely regarding methods for facility-specific risk assessments. Often these risk assessments are highly complex, site-specific documents that use advanced techniques such as Monte Carlo simulation. However, the risks that are calculated in these risk assessments are usually only used to compare to criteria for health effects and, thereby, develop permit conditions that are protective of health and the environment. Thus, the risk assessment is only used to derive a simple set of numbers and most of the information derived in the complex risk computations is lost. The object of this paper is to demonstrate how to derive more information from risk assessments that can be used in making management decisions. This paper will discuss the theory of risk management and present applications to combustion of waste in BIFs. For example, a permit applicant needed to make a decision among alternative air pollution control (APC) equipment sequences including scrubbers, fabric filters, and electrostatic precipitators. Limited life cycle analysis was used to determine the amount of direct and total waste produced by each of the alternatives. Monte Carlo risk assessment was used to determine the health risks associated with each of the alternatives and reliability analysis was employed to minimize both waste production and health risk.

  9. Information needs for risk management/communication

    SciTech Connect (OSTI)

    Bennett, D.A.

    1990-12-31

    The hazardous waste cleanup program under the Comprehensive Environmental Response, Compensation, and Liability Act (Superfund) is delegated to the ten Regions of the US Environmental Protection Agency (EPA) and has, to date, identified more than 33,000 sites for consideration. The size and complexity of the program places great demands on those who would provide information to achieve national consistency in application of risk assessment while meeting site-specific needs for risk management and risk communication.

  10. Cavity degradation risk insurance assessment. Final report

    SciTech Connect (OSTI)

    Hampson, C.; Neill, P.; de Bivort, L.

    1980-01-01

    This study examined the risks and risk management issues involved with the implementation by electric power utilities of compressed air energy storage and underground pumped hydro storage systems. The results are listed in terms of relative risks for the construction and operation of these systems in different geologic deposits, with varying amounts of pressurization, with natural or man-made disasters in the vicinity of the storage equipment, and with different modes of operating the facilities. (LCL)

  11. Hanford Waste Vitrification Systems Risk Assessment action plan

    SciTech Connect (OSTI)

    Miller, W.C.

    1990-11-01

    Recent events in the Hanford waste storage tanks and delays in the startup of US Department of Energy vitrification plans suggest that the schedule for waste vitrification activities at the Hanford Site should be reexamined. As a result, a Hanford Waste Vitrification Systems Risk Assessment will be performed to identify significant risks associated with the vitrification of Hanford high-level and transuranic wastes. This document defines the purpose, scope, plan of execution, responsibilities, reporting requirements, and preliminary schedule and cost estimate to complete this assessment. The study will identify and evaluate uncertainties, quantify potential consequences from these uncertainties, and identify the risks to successful completion of the Hanford vitrification mission. Waste characterization, retrieval, pretreatment, and vitrification will be addressed. Uncertainties associated with the vitrification of double-shell and single-shell tank wastes and cesium and strontium capsules, as well as a limited assessment of the grouting of low-level wastes, will be defined. Technical, regulatory (safety and environmental), and programmatic (cost and schedule) uncertainties will be defined. Recommendations for mitigating strategies and assessments of technical alternatives will be made to reduce substantial risks. 2 refs., 1 fig., 1 tab.

  12. ESPC Risk, Responsibility and Performance Matrix

    Broader source: Energy.gov [DOE]

    Document helps determine the risk, responsibility, and performance of a contractor's proposed approach under a Federal energy savings performance contract (ESPC).

  13. Summary - Major Risk Factors Integrated Facility Disposition...

    Office of Environmental Management (EM)

    Office of Environmental Management (DOE-EM) External Technical Review of the Major Risk Factors Integrated Facility Disposition Project (IFDP) Oak Ridge, TN Why DOE-EM Did...

  14. Innovative Computational Tools for Reducing Exploration Risk...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Computational Tools for Reducing Exploration Risk Through Integration of Water-Rock ... More Documents & Publications track 4: enhanced geothermal systems (EGS) | geothermal 2015 ...

  15. Use of Risk-Based End States

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2003-07-15

    The policy addresses conducting cleanup that is aimed at, and achieves, clearly defined, risk-based end states. Canceled by DOE N 251.106.

  16. Major Risk Factors Integrated Facility Disposition Project -...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Integrated Facility Disposition Project - Oak Ridge Major Risk Factors Integrated Facility Disposition Project - Oak Ridge Full Document and Summary Versions are available for ...

  17. Modeling human risk: Cell & molecular biology in context

    SciTech Connect (OSTI)

    1997-06-01

    It is anticipated that early in the next century manned missions into outer space will occur, with a mission to Mars scheduled between 2015 and 2020. However, before such missions can be undertaken, a realistic estimation of the potential risks to the flight crews is required. One of the uncertainties remaining in this risk estimation is that posed by the effects of exposure to the radiation environment of outer space. Although the composition of this environment is fairly well understood, the biological effects arising from exposure to it are not. The reasons for this are three-fold: (1) A small but highly significant component of the radiation spectrum in outer space consists of highly charged, high energy (HZE) particles which are not routinely experienced on earth, and for which there are insufficient data on biological effects; (2) Most studies on the biological effects of radiation to date have been high-dose, high dose-rate, whereas in space, with the exception of solar particle events, radiation exposures will be low-dose, low dose-rate; (3) Although it has been established that the virtual absence of gravity in space has a profound effect on human physiology, it is not clear whether these effects will act synergistically with those of radiation exposure. A select panel will evaluate the utilizing experiments and models to accurately predict the risks associated with exposure to HZE particles. Topics of research include cellular and tissue response, health effects associated with radiation damage, model animal systems, and critical markers of Radiation response.

  18. Developing a Comprehensive Risk Assessment Framework for Geological Storage CO2

    SciTech Connect (OSTI)

    Duncan, Ian

    2014-08-31

    The operational risks for CCS projects include: risks of capturing, compressing, transporting and injecting CO₂; risks of well blowouts; risk that CO₂ will leak into shallow aquifers and contaminate potable water; and risk that sequestered CO₂ will leak into the atmosphere. This report examines these risks by using information on the risks associated with analogue activities such as CO2 based enhanced oil recovery (CO2-EOR), natural gas storage and acid gas disposal. We have developed a new analysis of pipeline risk based on Bayesian statistical analysis. Bayesian theory probabilities may describe states of partial knowledge, even perhaps those related to non-repeatable events. The Bayesian approach enables both utilizing existing data and at the same time having the capability to adsorb new information thus to lower uncertainty in our understanding of complex systems. Incident rates for both natural gas and CO2 pipelines have been widely used in papers and reports on risk of CO2 pipelines as proxies for the individual risk created by such pipelines. Published risk studies of CO2 pipelines suggest that the individual risk associated with CO2 pipelines is between 10-3 and 10-4, which reflects risk levels approaching those of mountain climbing, which many would find unacceptably high. This report concludes, based on a careful analysis of natural gas pipeline failures, suggests that the individual risk of CO2 pipelines is likely in the range of 10-6 to 10-7, a risk range considered in the acceptable to negligible range in most countries. If, as is commonly thought, pipelines represent the highest risk component of CCS outside of the capture plant, then this conclusion suggests that most (if not all) previous quantitative- risk assessments of components of CCS may be orders of magnitude to high. The potential lethality of unexpected CO2 releases from pipelines or wells are arguably the highest risk aspects of CO2 enhanced oil recovery (CO2-EOR), carbon capture

  19. Lessons Learned in Risk Management on NCSX

    SciTech Connect (OSTI)

    Neilson, G. H.; Gruber, C. O.; Harris, J. H.; Rej, D. J.; Simmons, R. T.; Strykowsky, R. L.

    2009-07-21

    The National Compact Stellarator Experiment (NCSX) was designed to test physics principles of an innovative stellarator design developed by the Princeton Plasma Physics Laboratory and Oak Ridge National Laboratory. Construction of some of the major components and sub-assemblies was completed, but the estimated cost and schedule for completing the project grew as the technical requirements and risks became better understood, leading to its cancellation in 2008. The project's risks stemmed from its technical challenges, primarily the complex component geometries and tight tolerances that were required. The initial baseline, established in 2004, was supported by a risk management plan and risk-based contingencies, both of which proved to be inadequate. Technical successes were achieved in the construction of challenging components and subassemblies, but cost and schedule growth was experienced. As part of an effort to improve project performance, a new risk management program was devised and implemented in 2007-08. It led to a better understanding of project risks, a sounder basis for contingency estimates, and improved management tools. Although the risks ultimately were unacceptable to the sponsor, valuable lessons in risk management were learned through the experiences with the NCSX project.

  20. Lessons Learned in Risk Management on NCSX

    SciTech Connect (OSTI)

    G.H. Neilson, C.O. Gruber, J.H. Harris, D.J. Rej, R.T. Simmons, and R.L. Strykowsky

    2009-02-11

    The National Compact Stellarator Experiment (NCSX) was designed to test physics principles of an innovative stellarator design developed by the Princeton Plasma Physics Laboratory and Oak Ridge National Laboratory. Construction of some of the major components and sub-assemblies was completed, but the estimated cost and schedule for completing the project grew as the technical requirements and risks became better understood, leading to its cancellation in 2008. The project's risks stemmed from its technical challenges, primarily the complex component geometries and tight tolerances that were required. The initial baseline, established in 2004, was supported by a risk management plan and risk-based contingencies, both of which proved to be inadequate. Technical successes were achieved in the construction of challenging components and subassemblies, but cost and schedule growth was experienced. As part of an effort to improve project performance, a new risk management program was devised and implemented in 2007-08. It led to a better understanding of project risks, a sounder basis for contingency estimates, and improved management tools. Although the risks ultimately were unacceptable to the sponsor, valuable lessons in risk management were learned through the experiences with the NCSX project.

  1. Lessons Learned in Risk Management on NCSX

    SciTech Connect (OSTI)

    Neilson, G. H.; Gruber, C. O.; Harris, Jeffrey H; Rej, D. J.; Simmons, R. T.; Strykowsky, R. L.

    2010-01-01

    The National Compact Stellarator Experiment (NCSX) was designed to test physics principles of an innovative stellarator design developed by Princeton Plasma Physics Laboratory and Oak Ridge National Laboratory. Construction of some of the major components and subassemblies was completed, but the estimated cost and schedule for completing the project grew as the technical requirements and risks became better understood, leading to its cancellation in 2008. The project's risks stemmed from its technical challenges, primarily the complex component geometries and tight tolerances that were required. The initial baseline, which was established in 2004, was supported by a risk management plan and risk-based contingencies, both of which proved to be inadequate. Technical successes were achieved in the construction of challenging components and subassemblies, but cost and schedule growth was experienced. As part of an effort to improve project performance, a new risk management program was devised and implemented in 2007-2008. It led to a better understanding of project risks, a sounder basis for contingency estimates, and improved management tools. Although the risks were ultimately unacceptable to the sponsor, valuable lessons in risk management were learned through the experiences with the NCSX project.

  2. Risk communication 101: Address fears, suppress chaos

    SciTech Connect (OSTI)

    Gots, R.E. )

    1993-01-01

    Improper risk communication can create more problems than the original event created and is a growing problem. Proper risk communication is a key area of crisis management and cannot be overlooked in this new age of chemical awareness. An environmental risk communicator should keep these factors in mind: never discount people's fears; rule out direct health threats, when possible; understand people's concerns; understand toxicology; be able to communicate. If you are responsible for hiring communicators, be sure to test them. Ask them how they would deal with a situation in which levels of a chemical are below those known to produce harm. A risk communicator must present this to people in an understanding fashion, be sensitive to human concerns and be knowledgeable about toxic risks.

  3. Geothermal Risk Reduction via Geothermal/Solar Hybrid Power Plants. Final

    Office of Scientific and Technical Information (OSTI)

    Report (Technical Report) | SciTech Connect Geothermal Risk Reduction via Geothermal/Solar Hybrid Power Plants. Final Report Citation Details In-Document Search Title: Geothermal Risk Reduction via Geothermal/Solar Hybrid Power Plants. Final Report There are numerous technical merits associated with a renewable geothermal-solar hybrid plant concept. The performance of air-cooled binary plants is lowest when ambient temperatures are high due to the decrease in air-cooled binary plant

  4. Pre-sealing risk analysis

    SciTech Connect (OSTI)

    Ensminger, D.A.; Hough, M.E.; Oston, S.G.

    1980-01-07

    This report describes studies of accidents involving high-level radioactive waste before sealing the waste into a repository. The report summarizes work done in this area during Fiscal Year 1978 and supplements previous work. Models of accident probability, severity, and consequences are refined and extended.

  5. Microsoft PowerPoint - Snippet 4.9 High Level EVM Expectations...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... Over fifty years of EVMS applications have also proven its value on high risk projects. A project is definitely better controlled when the contractor implements, uses, and ...

  6. Uraniferous Phosphates: Resource, Security Risk, or Contaminant

    SciTech Connect (OSTI)

    LeMone, D.V.; Goodell, Ph.C.; Gibbs, S.G.; Winston, J.W.

    2008-07-01

    The escalation of the price of uranium (U) yellow cake (summer high = $130/0.454 kg (lb) has called into question the continuing availability of sufficient stockpiles and ores to process. As was developed during the years following World War II, the establishment and maintenance of a strategic inventory is a reasonable consideration for today. Therefore, it becomes critical to look at potential secondary resources beyond the classical ore suites now being utilized. The most economically viable future secondary source seems to be the byproducts of the beneficiation of phosphoric acids derived from phosphate ores. Phosphorous (P) is an essential nutrient for plants; its deficiency can result in highly restrictive limitations in crop productivity. Acidic soils in tropical and subtropical regions of the world are often P deficient with high P-sorption (fixation) capacities. To correct this deficiency, efficient water-soluble P fertilizers are required. The use of raw phosphate rocks not only adds phosphate but also its contained contaminants, including uranium to the treated land. Another immediate difficulty is phosphogypsum, the standard byproduct of simple extraction. It, for practical purposes, has been selectively classified as TENORM by regulators. The imposition of these standards presents major current and future disposal and re-utilization problems. Therefore, establishing an economically viable system that allows for uranium byproduct extraction from phosphoric acids is desirable. Such a system would be dependent on yellow cake base price stability, reserve estimates, political conditions, nation-state commitment, and dependence on nuclear energy. The accumulation of yellow cake from the additional extraction process provides a valuable commodity and allows the end acid to be a more environmentally acceptable product. The phosphogypsum already accumulated, as well as that which is in process, will not make a viable component for a radiation disposal devise

  7. Comparison of AB2588 multipathway risk factors for California fossil-fuel power stations

    SciTech Connect (OSTI)

    Gratt, L.B.; Levin, L.

    1997-12-31

    Substances released from power plants may travel through various exposure pathways resulting in human health and environmental risks. The stack air emission`s primary pathway is inhalation from the ambient air. Multipathway factors (adjustment factors to the inhalation risk) are used to evaluate the importance of non-inhalation pathways (such as ingestion and dermal contact). The multipathway factor for a specific substance is the health risk by all pathways divided by the inhalation health risk for that substance. These factors are compared for fossil fuel power stations that submitted regulatory risk assessments in compliance with California Toxic Hot Spots Act (AB2588). Substances representing the largest contributions to the cancer risk are of primary concern: arsenic, beryllium, cadmium, chromium (+6), formaldehyde, nickel, lead, selenium, and PAHs. Comparisons of the chemical-specific multipathway factors show the impacts of regulatory policy decisions on the estimated health risk for trace substances. As an example, point estimates of the soil mixing depth, varying from 1 cm to 15 cm, relate to the relative importance of the pathway. For the deeper mixing depths, the root-zone uptake by homegrown tomato plants (for assumed consumption rate of 15% for San Diego) may result in high multipathway factors for several trace metals. For shallower mixing depths, soil ingestion may become the dominant non-inhalation pathway. These differences may lead to significantly different risk estimates for similar facilities located at different California locations such as to be under local regulatory authorities. The overall multipathway factor for the total cancer risk is about 2, much smaller than some of the chemical-specific factors. Science-based multipathway analysis should reduce much of the concern that may be due to policy-based decisions on pathway selection and high-value point-estimates of the parameters.

  8. EC Transmission Line Risk Identification and Analysis

    SciTech Connect (OSTI)

    Bigelow, Tim S

    2012-04-01

    The purpose of this document is to assist in evaluating and planning for the cost, schedule, and technical project risks associated with the delivery and operation of the EC (Electron cyclotron) transmission line system. In general, the major risks that are anticipated to be encountered during the project delivery phase associated with the implementation of the Procurement Arrangement for the EC transmission line system are associated with: (1) Undefined or changing requirements (e.g., functional or regulatory requirements) (2) Underperformance of prototype, first unit, or production components during testing (3) Unavailability of qualified vendors for critical components Technical risks associated with the design and operation of the system are also identified.

  9. NGNP Risk Management through Assessing Technology Readiness

    SciTech Connect (OSTI)

    John W. Collins

    2010-08-01

    Throughout the Next Generation Nuclear Plant (NGNP) project life cycle, technical risks are identified, analyzed, and mitigated and decisions are made regarding the design and selection of plant and sub-system configurations, components and their fabrication materials, and operating conditions. Risk resolution and decision making are key elements that help achieve project completion within budget and schedule constraints and desired plant availability. To achieve this objective, a formal decision-making and risk management process was developed for NGNP, based on proven systems engineering principles that have guided aerospace and military applications.

  10. Estimating Terrorist Risk with Possibility Theory

    SciTech Connect (OSTI)

    J.L. Darby

    2004-11-30

    This report summarizes techniques that use possibility theory to estimate the risk of terrorist acts. These techniques were developed under the sponsorship of the Department of Homeland Security (DHS) as part of the National Infrastructure Simulation Analysis Center (NISAC) project. The techniques have been used to estimate the risk of various terrorist scenarios to support NISAC analyses during 2004. The techniques are based on the Logic Evolved Decision (LED) methodology developed over the past few years by Terry Bott and Steve Eisenhawer at LANL. [LED] The LED methodology involves the use of fuzzy sets, possibility theory, and approximate reasoning. LED captures the uncertainty due to vagueness and imprecision that is inherent in the fidelity of the information available for terrorist acts; probability theory cannot capture these uncertainties. This report does not address the philosophy supporting the development of nonprobabilistic approaches, and it does not discuss possibility theory in detail. The references provide a detailed discussion of these subjects. [Shafer] [Klir and Yuan] [Dubois and Prade] Suffice to say that these approaches were developed to address types of uncertainty that cannot be addressed by a probability measure. An earlier report discussed in detail the problems with using a probability measure to evaluate terrorist risk. [Darby Methodology]. Two related techniques are discussed in this report: (1) a numerical technique, and (2) a linguistic technique. The numerical technique uses traditional possibility theory applied to crisp sets, while the linguistic technique applies possibility theory to fuzzy sets. Both of these techniques as applied to terrorist risk for NISAC applications are implemented in software called PossibleRisk. The techniques implemented in PossibleRisk were developed specifically for use in estimating terrorist risk for the NISAC program. The LEDTools code can be used to perform the same linguistic evaluation as

  11. 3210T3 Risk Code Assignment;

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    210 Appendix T3 Risk Code Assignment 1.0 Purpose Identification of work hazards and understanding their risks is an essential part of Jefferson Lab's work process as defined in ES&H Manual Chapter 3210 Appendix T1 Work Planning, Control, and Authorization Procedure. The purpose of this document is to demonstrate the accepted method for determining the Risk Code for task steps identified while completing Task Hazard Analysis (THA) Worksheet. 2.0 Scope This appendix describes the procedure for

  12. Fire Risk Implications in Safety Analysis Reports

    SciTech Connect (OSTI)

    Blanchard, A.

    1999-03-31

    Fire can be a significant risk for facilities that store and handle radiological material. Such events must be evaluated as part of a comprehensive safety analysis. SRS has been developing methods to evaluate radiological fire risk in such facilities. These methods combined with the analysis techniques proposed by DOE-STD-3009-94 have provided a better understanding of how fire risks in nuclear facilities should be managed. To ensure that these new insights are properly disseminated the DOE Savannah River Office and the Defense Nuclear Facility Safety Board (DNFSB) requested Westinghouse Savannah River Company (WSRC) prepare this paper.

  13. Approaches to acceptable risk: a critical guide

    SciTech Connect (OSTI)

    Fischhoff, B.; Lichtenstein, S.; Slovic, P.; Keeney, R.; Derby, S.

    1980-12-01

    Acceptable-risk decisions are an essential step in the management of technological hazards. In many situations, they constitute the weak (or missing) link in the management process. The absence of an adequate decision-making methodology often produces indecision, inconsistency, and dissatisfaction. The result is neither good for hazard management nor good for society. This report offers a critical analysis of the viability of various approaches as guides to acceptable-risk decisions. This report seeks to define acceptable-risk decisions and to examine some frequently proposed, but inappropriate, solutions. 255 refs., 22 figs., 25 tabs.

  14. Federal Flood Risk Management Standard (2015)

    Broader source: Energy.gov [DOE]

    The Federal Flood Risk Management Standard (FFRMS (2015)) expands upon E.O. 11988, Floodplain Management, (1977) by directing that federal agencies use a higher vertical flood elevation and...

  15. Need for an Integrated Risk Model

    Office of Environmental Management (EM)

    and collaboration on the use of an integrated risk model at sites * To propose a test case for use of a sample case 10222008 p. 3, LA-UR 11-06023 Observations * SAFER...

  16. Risk assessment as a framework for decisions.

    SciTech Connect (OSTI)

    Rechard, Robert Paul; McKenna, Sean Andrew; Borns, David James

    2010-12-01

    The risk assessment approach has been applied to support numerous radioactive waste management activities over the last 30 years. A risk assessment methodology provides a solid and readily adaptable framework for evaluating the risks of CO2 sequestration in geologic formations to prioritize research, data collection, and monitoring schemes. This paper reviews the tasks of a risk assessment, and provides a few examples related to each task. This paper then describes an application of sensitivity analysis to identify important parameters to reduce the uncertainty in the performance of a geologic repository for radioactive waste repository, which because of importance of the geologic barrier, is similar to CO2 sequestration. The paper ends with a simple stochastic analysis of idealized CO2 sequestration site with a leaking abandoned well and a set of monitoring wells in an aquifer above the CO2 sequestration unit in order to evaluate the efficacy of monitoring wells to detect adverse leakage.

  17. Federal Flood Risk Management Standard (FEMA, 2015)

    Broader source: Energy.gov [DOE]

    The Federal Flood Risk Management Standard (FFRMS (2015)) expands upon E.O. 11988, Floodplain Management, (1977) by directing that federal agencies use a higher vertical flood elevation and...

  18. RISK REDUCTION WITH A FUZZY EXPERT EXPLORATION TOOL

    SciTech Connect (OSTI)

    Robert S. Balch; Ron Broadhead

    2005-03-01

    Incomplete or sparse data such as geologic or formation characteristics introduce a high level of risk for oil exploration and development projects. ''Expert'' systems developed and used in several disciplines and industries have demonstrated beneficial results when working with sparse data. State-of-the-art expert exploration tools, relying on a database, and computer maps generated by neural networks and user inputs, have been developed through the use of ''fuzzy'' logic, a mathematical treatment of imprecise or non-explicit parameters and values. Oil prospecting risk has been reduced with the use of these properly verified and validated ''Fuzzy Expert Exploration (FEE) Tools.'' Through the course of this project, FEE Tools and supporting software were developed for two producing formations in southeast New Mexico. Tools of this type can be beneficial in many regions of the U.S. by enabling risk reduction in oil and gas prospecting as well as decreased prospecting and development costs. In today's oil industry environment, many smaller exploration companies lack the resources of a pool of expert exploration personnel. Downsizing, volatile oil prices, and scarcity of domestic exploration funds have also affected larger companies, and will, with time, affect the end users of oil industry products in the U.S. as reserves are depleted. The FEE Tools benefit a diverse group in the U.S., allowing a more efficient use of scarce funds, and potentially reducing dependence on foreign oil and providing lower product prices for consumers.

  19. Risk Management II Summit Agenda | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Risk Management II Summit Agenda Risk Management II Summit Agenda Risk Management Summit Agenda.pdf (171.41 KB) More Documents & Publications ICAM Workshop Radio and Spectrum Management Ad Hoc Meetings

  20. ELECTRICITY SUBSECTOR CYBERSECURITY RISK MANAGEMENT PROCESS

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    CYBERSECURITY RISK MANAGEMENT PROCESS U.S. Department of Energy May 2012 DOE/OE-0003 Acknowledgments This electricity subsector cybersecurity Risk Management Process (RMP) guideline was developed by the Department of Energy (DOE), in collaboration with the National Institute of Standards and Technology (NIST) and the North American Electric Reliability Corporation (NERC). Members of industry and utility-specific trade groups were included in authoring this guidance designed to be meaningful and

  1. High e

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    e ne rgy data s am ple ● NuMI beam events provide an useful calibration sample ● Collected over 70K candidates before shutdown The highest energy events are prim arily from kaon decays. Two sam ples at high energy provide normalization and shape inform ation for kaon backgrounds to oscillation analysis: ● ν e events passing oscillation event selection cuts ● ν µ induced CCQE, CCπ+events Reconstructed neutrino energy EνQE(GeV) ν from other particles ν from pions ν from Kaons -

  2. Idaho National Laboratory (INL) Seismic Risk Assessment Project:

    Office of Environmental Management (EM)

    Implementation of Proposed Methodology at INL and Associated Risk Studies | Department of Energy Risk Assessment Project: Implementation of Proposed Methodology at INL and Associated Risk Studies Idaho National Laboratory (INL) Seismic Risk Assessment Project: Implementation of Proposed Methodology at INL and Associated Risk Studies Presentation from the May 2015 Seismic Lessons-Learned Panel Meeting. INL Seismic Risk Assessment Project: Implementation of Proposed Methodology at INL and

  3. Highly Radioactive Sludge Removal Complete: Historic Cleanup Effort Reduces

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    the Risk along the Columbia River | Department of Energy Highly Radioactive Sludge Removal Complete: Historic Cleanup Effort Reduces the Risk along the Columbia River Highly Radioactive Sludge Removal Complete: Historic Cleanup Effort Reduces the Risk along the Columbia River September 13, 2012 - 12:00pm Addthis Media Contacts Cameron Salony, DOE Cameron.Salony@rl.doe.gov 509-376-0402 Dee Millikin, CH2M HILL Plateau Remediation Company Dee_Millikin@rl.gov 509-376-1297 RICHLAND, WASH. - The

  4. New Draft of Cybersecurity Risk Management Process (RMP) Guideline...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Draft of Cybersecurity Risk Management Process (RMP) Guideline Now Available for Public Comment (March 2012) New Draft of Cybersecurity Risk Management Process (RMP) Guideline Now ...

  5. Climate Risk and Financial Institutions | Open Energy Information

    Open Energy Info (EERE)

    Corporation Topics: Finance, Co-benefits assessment Website: www.ifc.orgifcextsustainability.nsfAttachmentsByTitlepClimateRisk Climate Risk and Financial Institutions...

  6. DOE Releases Filing Instructions for Federal Risk Insurance for...

    Energy Savers [EERE]

    Filing Instructions for Federal Risk Insurance for New Nuclear Power Plants DOE Releases Filing Instructions for Federal Risk Insurance for New Nuclear Power Plants December 21, ...

  7. Idaho National Laboratory (INL) Seismic Risk Assessment Project...

    Office of Environmental Management (EM)

    Seismic Risk Assessment Project: Implementation of Proposed Methodology at INL and Associated Risk Studies Presentation from the May 2015 Seismic Lessons-Learned Panel Meeting. ...

  8. Nuclear Risk Assessment for the Mars 2020 Mission Environmental...

    Office of Scientific and Technical Information (OSTI)

    Technical Report: Nuclear Risk Assessment for the Mars 2020 Mission Environmental Impact Statement Citation Details In-Document Search Title: Nuclear Risk Assessment for the Mars ...

  9. Effect Of Ventilation On Chronic Health Risks In Schools And...

    Office of Scientific and Technical Information (OSTI)

    Technical Report: Effect Of Ventilation On Chronic Health Risks In Schools And Offices Citation Details In-Document Search Title: Effect Of Ventilation On Chronic Health Risks In ...

  10. UNEP-GEF Renewable Energy Project Financial Risk Management in...

    Open Energy Info (EERE)

    GEF Renewable Energy Project Financial Risk Management in Developing Countries Jump to: navigation, search Name UNEP-GEF Renewable Energy Project Financial Risk Management in...

  11. Enterprise Risk Management (ERM) Model - DOE Directives, Delegations...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Enterprise Risk Management (ERM) Model by Website Administrator The Enterprise Risk Management Model is a new standardized framework that the Department will be using to develop,...

  12. Overview of HyRAM (Hydrogen Risk Assessment Models) Software...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    HyRAM (Hydrogen Risk Assessment Models) Software for Science-Based Safety, Codes, and Standards Webinar Overview of HyRAM (Hydrogen Risk Assessment Models) Software for ...

  13. State and Regional Energy Risk Assessment Initiative | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Mission Energy Infrastructure Modeling and Analysis State and Regional Energy Risk Assessment Initiative State and Regional Energy Risk Assessment Initiative The Office of...

  14. RAVEN and Dynamic Probabilistic Risk Assessment: Software overview...

    Office of Scientific and Technical Information (OSTI)

    RAVEN and Dynamic Probabilistic Risk Assessment: Software overview Citation Details In-Document Search Title: RAVEN and Dynamic Probabilistic Risk Assessment: Software overview ...

  15. State Energy Risk Assessment Initiative - State and Regional...

    Broader source: Energy.gov (indexed) [DOE]

    OE is leading a State Energy Risk Assessment Initiative to help States better understand risks to their energy infrastructure so they can be better prepared to make informed...

  16. Spent Fuel Transportation Risk Assessment | Department of Energy

    Office of Environmental Management (EM)

    Spent Fuel Transportation Risk Assessment Spent Fuel Transportation Risk Assessment SFTRA Overview Contents Project and review teams Purpose and goals Basic methodology ...

  17. Advanced Risk Management (FQN 301), SRS | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    The course also addresses representative project risk management software risk analysis ... wish to take this course for continuing education credit. Course Format: 3.5 days ...

  18. The Role Risk Assessments Have Played in Proposed CERCLA Decision...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Applicable Relevant and Appropriate Requirements Examples: Clean Water Act, Safe Drinking Water Act, Air Emissions Regulations * Policy * Risk Assessment * Risk Management *...

  19. Improving Risk Assessment to Support State Energy Infrastructure...

    Energy Savers [EERE]

    of the electric, petroleum, and natural gas infrastructures, and provide valuable ... A better understanding of risk facilitates integration of energy risk assessment into ...

  20. South Africa - Climate Change Risks and Opportunities for the...

    Open Energy Info (EERE)

    Climate Change Risks and Opportunities for the Economy Jump to: navigation, search Name South Africa - Climate Change Risks and Opportunities for the Economy AgencyCompany...

  1. Global Climate Change: Risk to Bank Loans | Open Energy Information

    Open Energy Info (EERE)

    Risk to Bank Loans Jump to: navigation, search Tool Summary LAUNCH TOOL Name: Global Climate Change: Risk to Bank Loans AgencyCompany Organization: United Nations...

  2. Risk Assessment in Support of DOE Nuclear Safety, Risk Information Notice, June 2010

    Broader source: Energy.gov [DOE]

    On August 12, 2009, the Defense Nuclear Facilities Safety Board(DNFSB) issued Recommendation 2009‐1, Risk Assessment Methodologies at Defense Nuclear Facilities. Thisrecommendation focused on the...

  3. A workshop on developing risk assessment methods for medical use of radioactive material. Volume 1: Summary

    SciTech Connect (OSTI)

    Tortorelli, J.P.

    1995-08-01

    A workshop was held at the Idaho National Engineering Laboratory, August 16--18, 1994 on the topic of risk assessment on medical devices that use radioactive isotopes. Its purpose was to review past efforts to develop a risk assessment methodology to evaluate these devices, and to develop a program plan and a scoping document for future methodology development. This report contains a summary of that workshop. Participants included experts in the fields of radiation oncology, medical physics, risk assessment, human-error analysis, and human factors. Staff from the US Nuclear Regulatory Commission (NRC) associated with the regulation of medical uses of radioactive materials and with research into risk-assessment methods participated in the workshop. The workshop participants concurred in NRC`s intended use of risk assessment as an important technology in the development of regulations for the medical use of radioactive material and encouraged the NRC to proceed rapidly with a pilot study. Specific recommendations are included in the executive summary and the body of this report. An appendix contains the 8 papers presented at the conference: NRC proposed policy statement on the use of probabilistic risk assessment methods in nuclear regulatory activities; NRC proposed agency-wide implementation plan for probabilistic risk assessment; Risk evaluation of high dose rate remote afterloading brachytherapy at a large research/teaching institution; The pros and cons of using human reliability analysis techniques to analyze misadministration events; Review of medical misadministration event summaries and comparison of human error modeling; Preliminary examples of the development of error influences and effects diagrams to analyze medical misadministration events; Brachytherapy risk assessment program plan; and Principles of brachytherapy quality assurance.

  4. Risk Estimation Methodology for Launch Accidents.

    SciTech Connect (OSTI)

    Clayton, Daniel James; Lipinski, Ronald J.; Bechtel, Ryan D.

    2014-02-01

    As compact and light weight power sources with reliable, long lives, Radioisotope Power Systems (RPSs) have made space missions to explore the solar system possible. Due to the hazardous material that can be released during a launch accident, the potential health risk of an accident must be quantified, so that appropriate launch approval decisions can be made. One part of the risk estimation involves modeling the response of the RPS to potential accident environments. Due to the complexity of modeling the full RPS response deterministically on dynamic variables, the evaluation is performed in a stochastic manner with a Monte Carlo simulation. The potential consequences can be determined by modeling the transport of the hazardous material in the environment and in human biological pathways. The consequence analysis results are summed and weighted by appropriate likelihood values to give a collection of probabilistic results for the estimation of the potential health risk. This information is used to guide RPS designs, spacecraft designs, mission architecture, or launch procedures to potentially reduce the risk, as well as to inform decision makers of the potential health risks resulting from the use of RPSs for space missions.

  5. A pilot exercise on comparative risk assessment in Mexico

    SciTech Connect (OSTI)

    Cebrian, M.E.; Albores, A.; Sierra, A.

    1996-12-31

    Concern in the Mexican government and academic institutions about human health problems derived from exposure to environmental contaminants has been increasing. This interest prompted us to perform a pilot study to identify and rank potentially problematic environmental situations. We were given access to files from the Instituto Nacional de Ecologia. We screened about 2,500 documents and selected about 200 reports for further analysis. We adapted methodologies developed by the U.S. Environmental Protection Agency (EPA 1993) and ATSDR (1992) to analyze environmental data. San Luis Potosi City and Region Lagunera were the areas posing greater risks. We chose San Luis Potosi City to perform a more detailed study, since here a smelting complex is located within an urban zone. The high levels of As, Pb, and Cd in environmental media resulted in a higher body burden in exposed children than children living 7 km away. Multiple regression analysis suggested that alterations in sensorial nerve transmission were mainly related to As in urine (AsU), whereas those in motor nerves were mainly related to Pb in blood (PbB). No apparent relationships associated with CdU were found. Slower auditory nerve conduction was associated with both AsU and PbB. These findings suggest that exposed children are also at high risk of suffering other adverse health effects. This exercise illustrates the need to perform studies aimed at identifying and ranking environmental contamination problems in industrializing countries. 5 refs., 1 tab.

  6. Sitewide biological risk assessment Eielson Air Force Base, Alaska: Risks to terrestrial receptors from diverse contaminants

    SciTech Connect (OSTI)

    Brandt, C.A.; Becker, J.M.

    1995-12-31

    Eielson Air Force Base (AFB) is located southeast of Fairbanks, Alaska. Eielson AFB was listed by the US Environmental Protection Agency on the National Priorities List with a total of 64 potential terrestrial and aquatic source areas. Contaminants of concern include fuel and fuel components, pesticides, polychlorinated biphenyls (PCBs), and lead. As part of the remedial investigations of these sites, a biological risk assessment (BRA) was conducted to estimate the risk of ecological effects on terrestrial receptors posed by contaminants in the Eielson environment. There are 32 mammal species, 117 bird species, 17 fish species, and 1 amphibian species known to inhabit Eielson AFB and vicinity. The BRA screened source areas based on completed biological exposure pathways, selected receptors for analysis, estimated exposure of receptors to contaminants, and compared these exposures to known toxicological effects. Lower Garrison Slough and Flightline Pond posed a substantial risk for shrikes and goshawks. Ingestion of PCBs constituted the primary pathway/contaminant combination contributing to this risk. The effects of the various sources of uncertainty in the ingestion exposure calculations for these sites were evaluated in a probabilistic risk assessment using Monte Carlo methods. There was an 11% risk of reproductive effects from PCBs for goshawks feeding from Flightline Pond and a 25 % risk from lower Garrison Slough. There was an 81 % risk of reproductive effects from PCB exposure for shrikes feeding near lower Garrison Slough.

  7. Radiological risk evaluation for risk-based design criteria of the multiple canister overpack packaging

    SciTech Connect (OSTI)

    Green, J.R., Westinghouse Hanford

    1996-07-18

    The Multiple Canister Overpack (MCO) cask will be used in the transportation of irradiated nuclear fuel from the K Basins to a Canister Storage Building. This report presents the radiological risk evaluation, which is used in the development of the design criteria for the MCO cask. The radiological risk evaluation ensures compliance with the onsite transportation safety program.

  8. JV Task 99-Integrated Risk Analysis and Contaminant Reduction, Watford City, North Dakota

    SciTech Connect (OSTI)

    Jaroslav Solc; Barry W. Botnen

    2007-05-31

    The Energy & Environmental Research Center (EERC) conducted a limited site investigation and risk analyses for hydrocarbon-contaminated soils and groundwater at a Construction Services, Inc., site in Watford City, North Dakota. Site investigation confirmed the presence of free product and high concentrations of residual gasoline-based contaminants in several wells, the presence of 1,2-dichloroethane, and extremely high levels of electrical conductivity indicative of brine residuals in the tank area south of the facility. The risk analysis was based on compilation of information from the site-specific geotechnical investigation, including multiphase extraction pilot test, laser induced fluorescence probing, evaluation of contaminant properties, receptor survey, capture zone analysis and evaluation of well head protection area for municipal well field. The project results indicate that the risks associated with contaminant occurrence at the Construction Services, Inc. site are low and, under current conditions, there is no direct or indirect exposure pathway between the contaminated groundwater and soils and potential receptors.

  9. Incinerator thermal release valve risk assessment

    SciTech Connect (OSTI)

    Stevens, J.B.

    1998-12-31

    Human health risk assessments were conducted on emissions from several types of incinerators--a hazardous waste combustor, a medical waste/tire combustor, and a refuse derived fuel combustor in three different states. As part of these studies, the short-term emissions from thermal release valves operating during upset conditions were additionally evaluated. The latter assessments addressed two specific risk-related questions: (1) what are the incremental long-term risks/hazards associated with these short-term emissions; (2) what are the acute health hazards associated with these emissions? For each study, emission estimates for both the incinerator stack and the thermal release valve were obtained from the facility. Stack testing was utilized to obtain stack gas concentrations of emissions at one facility; engineering estimates were used to ascertain emissions from the thermal release valve. The two facilities were proposed incinerators, so literature-derived emissions were used throughout.

  10. Chernobyl accident: A comprehensive risk assessment

    SciTech Connect (OSTI)

    Vargo, G.J.; Poyarkov, V.; Baryakhtar, V.; Kukhar, V.; Los, I.

    1999-01-01

    The authors, all of whom are Ukrainian and Russian scientists involved with Chernobyl nuclear power plant since the April 1986 accident, present a comprehensive review of the accident. In addition, they present a risk assessment of the remains of the destroyed reactor and its surrounding shelter, Chernobyl radioactive waste storage and disposal sites, and environmental contamination in the region. The authors explore such questions as the risks posed by a collapse of the shelter, radionuclide migration from storage and disposal facilities in the exclusion zone, and transfer from soil to vegetation and its potential regional impact. The answers to these questions provide a scientific basis for the development of countermeasures against the Chernobyl accident in particular and the mitigation of environmental radioactive contamination in general. They also provide an important basis for understanding the human health and ecological risks posed by the accident.

  11. Builtin vs. auxiliary detection of extrapolation risk.

    SciTech Connect (OSTI)

    Munson, Miles Arthur; Kegelmeyer, W. Philip,

    2013-02-01

    A key assumption in supervised machine learning is that future data will be similar to historical data. This assumption is often false in real world applications, and as a result, prediction models often return predictions that are extrapolations. We compare four approaches to estimating extrapolation risk for machine learning predictions. Two builtin methods use information available from the classification model to decide if the model would be extrapolating for an input data point. The other two build auxiliary models to supplement the classification model and explicitly model extrapolation risk. Experiments with synthetic and real data sets show that the auxiliary models are more reliable risk detectors. To best safeguard against extrapolating predictions, however, we recommend combining builtin and auxiliary diagnostics.

  12. Novel Threat-risk Index Using Probabilistic Risk Assessment and Human Reliability Analysis - Final Report

    SciTech Connect (OSTI)

    George A. Beitel

    2004-02-01

    In support of a national need to improve the current state-of-the-art in alerting decision makers to the risk of terrorist attack, a quantitative approach employing scientific and engineering concepts to develop a threat-risk index was undertaken at the Idaho National Engineering and Environmental Laboratory (INEEL). As a result of this effort, a set of models has been successfully integrated into a single comprehensive model known as Quantitative Threat-Risk Index Model (QTRIM), with the capability of computing a quantitative threat-risk index on a system level, as well as for the major components of the system. Such a threat-risk index could provide a quantitative variant or basis for either prioritizing security upgrades or updating the current qualitative national color-coded terrorist threat alert.

  13. Approach on environmental risk assessment of nanosilver released from textiles

    SciTech Connect (OSTI)

    Voelker, Doris; Schlich, Karsten; Hohndorf, Lars; Koch, Wolfgang; Kuehnen, Ute; Polleichtner, Christian; Kussatz, Carola; Hund-Rinke, Kerstin

    2015-07-15

    Based on the increased utilization of nanosilver (silver nanomaterials=AgNM) as antibacterial agent, there is the strong need to assess the potential environmental implication associated with its new application areas. In this study an exemplary environmental risk assessment (ERA) of AgNM applied in textiles was performed. Environmental exposure scenarios (via municipal sewage treatment plant (STP)) with wastewater supply from domestic homes) were developed for three different types of textiles equipped with AgNM. Based on these scenarios predicted environmental concentrations (PECs) were deduced for STPs and for the environmental compartments surface water, sediment as well as soil. These PECs were related to PNECs (predicted no effect concentrations). PNECs were deduced from results of ecotoxicity tests of a selected AgNM (NM-300K). Data on ecotoxicology were derived from various tests with activated sludge, cyanobacteria, algae, daphnids, fish, duckweed, macrophytes, chironomids, earthworms, terrestrial plants as well as soil microorganisms. Emission data for the AgNM NM-300K from textiles were derived from washing experiments. The performed ERA was based on the specifications defined in the ECHA Guidances on information requirements and chemical safety assessment. Based on the chosen scenarios and preconditions, no environmental risk of the AgNM NM-300K released from textiles was detected. Under conservative assumptions a risk quotient for surface water close to 1 indicated that the aquatic compartment may be affected by an increased emission of AgNM to the environment due to the high sensitivity of aquatic organisms to silver. Based on the successful retention of AgNM in the sewage sludge and the still ongoing continual application of sewage sludge on farmland it is recommended to introduce a threshold for total silver content in sewage sludge into the respective regulations. Regarding potential risk mitigation measures, it is emphasized to preferably directly

  14. Screening Risk Assessment for Possible Radionuclides in the Amchitka Marine Environment

    SciTech Connect (OSTI)

    NNSA /NV

    2002-10-31

    , the most conservative data were selected. Conservative assumptions and values were used for radionuclide uptake factors and for marine food ingestion rates by human receptors. The dispersion of material in the marine environment utilized a U.S. Environmental Protection Agency (EPA)-approved model (CORMIX). In addition, the screening level of 1 x 10{sup -6} or 1 excess cancer in 1 million is considered by the EPA to be below the level of concern. The end result, as presented in this report, is a highly conservative estimate of potential risks that are well below the EPA's most conservative risk threshold for both subsistence users and commercial-catch consumers.

  15. Risk assessment based on point source deposition

    SciTech Connect (OSTI)

    Chadwick, G.F.

    1997-12-31

    The International Joint Commission (IJC) in a recently published report states that various clean-up techniques have resulted in significantly cleaner lakes than 20 years ago. Both the US EPA and Environment Canada have passed laws that require emissions controls on significant sources of contaminants. Improved emission controls have played a large part in the reduced pollution levels to the Great Lakes. Improved controls have significantly reduced the pollutants deposited to both land and water. This paper will discuss a Risk Analysis for the emissions from a Hospital in Rochester, New York. Current New York Department of Environmental Conservation (DEC) regulations require emission controls on such incinerators. This hospital has added both a scrubber and a bag house to control emissions. Twenty years ago, such incinerators, like many other emission sources would not have had control devices. New York`s Department of Environmental Conservation requires, as part of the Permitting process, that an Impact Analysis and if required, a multipathway Health Risk Assessment (HRA) be performed for all Medical Waste Incinerators before a Permit can be issued. This insures that the emissions will not create a health hazard to humans. Such an analysis was performed for a new 1,000 lb/hr Medical Waste Incinerator (MWI) installed in the North-East part of Rochester, New York. An Air Quality Impact Assessment (AQIA) based on an actual stack test indicated that this facility`s dioxin emissions would exceed the NY DEC Guideline levels. The Carcinogenic Risk (of death) for our most exposed individual (MEI) was calculated to be 8.75 E{sup {minus}06} (<1:100,000). The Hazard Index calculated for this MEI was 0.43. Hazard Index`s less then 1 are considered a reasonable risk. Health risk assessments are by design, very conservative. EPA sources have concluded that calculated death risks between one (1) and one hundred (100) per million are not excessive.

  16. Code System for Seismic Probabilistic Risk Assessment.

    Energy Science and Technology Software Center (OSTI)

    2001-03-27

    Version 00 SEISIM1 calculates the probabilities of seismically induced failures for components and systems and propagates these calculations to determine the probability of accident sequences and the resulting total risk, which is quantified as an expected value of radiation release and exposure from a given nuclear power plant. SEISIM1 was developed as a fundamental tool for the systems analysis portion of the NRC's Seismic Safety Margins Research Program (SSMRP). The SSMRP provides a complete, self-containedmore » methodology to assess and quantify the risk to nuclear power plants from seismic events and seismically induced failures.« less

  17. Understanding and managing risk in software systems

    SciTech Connect (OSTI)

    Fletcher, S.K.; Jansma, R.; Lim, J.; Murphy, M.; Wyss, G.

    1995-07-01

    When software is used in safety-critical, security-critical, or mission-critical situations, it is imperative to understand and manage the risks involved. A risk assessment methodology and toolset have been developed which are specific to software systems. This paper describes the concepts of the methodology, with emphasis on the experience of designing a toolset to support the methodology. Also presented are results of applying the methodology to two real software-based products: the software toolset itself, and a network firewall.

  18. Predicting Pneumonitis Risk: A Dosimetric Alternative to Mean Lung Dose

    SciTech Connect (OSTI)

    Tucker, Susan L.; Mohan, Radhe; Liengsawangwong, Raweewan; Martel, Mary K.; Liao Zhongxing

    2013-02-01

    Purpose: To determine whether the association between mean lung dose (MLD) and risk of severe (grade {>=}3) radiation pneumonitis (RP) depends on the dose distribution pattern to normal lung among patients receiving 3-dimensional conformal radiation therapy for non-small-cell lung cancer. Methods and Materials: Three cohorts treated with different beam arrangements were identified. One cohort (2-field boost [2FB]) received 2 parallel-opposed (anteroposterior-posteroanterior) fields per fraction initially, followed by a sequential boost delivered using 2 oblique beams. The other 2 cohorts received 3 or 4 straight fields (3FS and 4FS, respectively), ie, all fields were irradiated every day. The incidence of severe RP was plotted against MLD in each cohort, and data were analyzed using the Lyman-Kutcher-Burman (LKB) model. Results: The incidence of grade {>=}3 RP rose more steeply as a function of MLD in the 2FB cohort (N=120) than in the 4FS cohort (N=138), with an intermediate slope for the 3FS group (N=99). The estimated volume parameter from the LKB model was n=0.41 (95% confidence interval, 0.15-1.0) and led to a significant improvement in fit (P=.05) compared to a fit with volume parameter fixed at n=1 (the MLD model). Unlike the MLD model, the LKB model with n=0.41 provided a consistent description of the risk of severe RP in all three cohorts (2FB, 3FS, 4FS) simultaneously. Conclusions: When predicting risk of grade {>=}3 RP, the mean lung dose does not adequately take into account the effects of high doses. Instead, the effective dose, computed from the LKB model using volume parameter n=0.41, may provide a better dosimetric parameter for predicting RP risk. If confirmed, these findings support the conclusion that for the same MLD, high doses to small lung volumes ('a lot to a little') are worse than low doses to large volumes ('a little to a lot').

  19. USDOE study: Human health and ecological risk assessment for produced water discharges

    SciTech Connect (OSTI)

    Meinhold, A.F.; Holtzman, S.; DePhillips, M.; Hamilton, L.D.

    1994-12-31

    Produced water generated during the production of oil and gas can contain high concentrations of radionuclides, organics and heavy metals. There are concerns about potential human health and ecological impacts from the discharge of these contaminants to the Gulf of Mexico. Data collected in the United States Department of Energy (USDOE) field study are being used in a series of human health and ecological risk assessments. These assessments will support scientifically-based regulation and risk management. This presentation: summarizes risk assessments performed for produced water discharges; describes how uncertainties in these assessments are guiding data collection efforts in the USDOE field study; and outlines ongoing risk assessment studies. In these studies, risk assessment is treated as an iterative process. An initial screening-level assessment is performed to identify important contaminants, transport and exposure pathways, and parameters. These intermediate results are used to guide data collection efforts and refinements to the analysis. At this stage in the analysis, risk is described in terms of probabilities; the uncertainties in each measured or modeled parameter are considered explicitly.

  20. A framework for assessing relative risks associated with multiple stressors in Port Valdez, Alaska

    SciTech Connect (OSTI)

    Wiegers, J.K.; Landis, W.G.; Mortensen, L.S.; Wilson, V.J.

    1995-12-31

    The purpose of this assessment is to develop a versatile process that will provide a mechanism for evaluating both present and future risks to this environment. Much of the regulatory and environmental interest in the port has centered around a Ballast Water Treatment facility that treats and discharges up to 30 mgd of oily ballast water brought in by crude oil tankers. However, six point discharges and other potential sources of pollution exist in the area. The authors have delineated eleven subareas in the port in order to identify the potential anthropogenic stressors, as well as the receptors that could be exposed to these stressors. Potential effects were then characterized for each exposure. Each component is ranked and integrated, resulting in a relative risk estimate in each subarea. Both the discernible risks, based on available data, and the data gaps are presented. Uncertainty is expressed as a range of high and low risk associated with each component. Results of the ranking indicate that hydrocarbons released through discharges, contaminated runoff and spills pose the most discernible risk to sediment quality and wildlife in the port. Undetermined, but potentially severe, risks to all ecological components include possible future oil spills, shoreline development, and the introduction of nonindigenous species. The final assessment provides a tool for current and future ecological monitoring efforts in the Port Valdez area.

  1. Communicating Health Risks Working Safely With Beryllium | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy Communicating Health Risks Working Safely With Beryllium Communicating Health Risks Working Safely With Beryllium April 2002 Training Reference for Beryllium Workers and Managers/Supervisors, Facilitator Manual Prepared by the Beryllium Health Risk Communication Task Force Communicating Health Risks Working Safely With Beryllium (1.03 MB) More Documents & Publications Communicating Health Risks Working Safely With Beryllium Beryllium Screening - Informed Choice Document 10 CFR

  2. Risk Assessment Tool - DOE Directives, Delegations, and Requirements

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Risk Assessment Technical Experts Working Group Risk Assessment Technical Experts Working Group The Risk Assessment Technical Experts Working Group (RWG) is established to assist DOE in the appropriate and effective use of quantitative risk assessment in nuclear safety related activities. The activities of the group will help DOE ensure that risk assessments supporting nuclear safety decisions are conducted in a consistent manner, of appropriate quality, properly tailored to the needs of the

  3. Simulation and Risk Assessment for Carbon Storage | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Science & Innovation » Carbon Capture and Storage » Simulation and Risk Assessment for Carbon Storage Simulation and Risk Assessment for Carbon Storage Research in simulation and risk assessment is focused on development of advanced simulation models of the subsurface and integration of the results into a risk assessment that includes both technical and programmatic risks. Simulation models are critical for predicting the flow of the CO2 in the target formations, chemical changes that may

  4. RISK REDUCTION THROUGH USE OF EXTERNAL TECHNICAL REVIEWS, TECHNOLOGY READINESS ASSESSMENTS AND TECHNICAL RISK RATINGS - 9174

    SciTech Connect (OSTI)

    Cercy, M; Steven P Schneider, S; Kurt D Gerdes, K

    2008-12-12

    The U.S. Department of Energy's Office of Environmental Management (DOE-EM) was established to achieve the safe and compliant disposition of legacy wastes and facilities from defense nuclear applications. A large majority of these wastes and facilities are 'one-of-a-kind' and unique to DOE. Many of the programs to treat these wastes have been 'first-of-a-kind' and unprecedented in scope and complexity. This has meant that many of the technologies needed to successfully disposition these wastes were not yet developed or required significant re-engineering to be adapted for DOE-EM's needs. The DOE-EM program believes strongly in reducing the technical risk of its projects and has initiated several efforts to reduce those risks: (1) Technology Readiness Assessments to reduce the risks of deployment of new technologies; (2) External Technical Reviews as one of several steps to ensure the timely resolution of engineering and technology issues; and (3) Technical Risk Ratings as a means to monitor and communicate information about technical risks. This paper will present examples of how Technology Readiness Assessments, External Technical Reviews, and Technical Risk Ratings are being used by DOE-EM to reduce technical risks.

  5. RISK REDUCTION THROUGH USE OF EXTERNAL TECHNICAL REVIEWS, TECHNOLOGY READINESS ASSESSMENTS AND TECHNICAL RISK RATINGS - 9174

    SciTech Connect (OSTI)

    Cercy, M; Steven P Schneider, S; Kurt D Gerdes, K

    2009-01-15

    The U.S. Department of Energy's Office of Environmental Management (DOE-EM) was established to achieve the safe and compliant disposition of legacy wastes and facilities from defense nuclear applications. A large majority of these wastes and facilities are 'one-of-a-kind' and unique to DOE. Many of the programs to treat these wastes have been 'first-of-a-kind' and unprecedented in scope and complexity. This has meant that many of the technologies needed to successfully disposition these wastes were not yet developed or required significant re-engineering to be adapted for DOE-EM's needs. The DOE-EM program believes strongly in reducing the technical risk of its projects and has initiated several efforts to reduce those risks: (1) Technology Readiness Assessments to reduce the risks of deployment of new technologies; (2) External Technical Reviews as one of several steps to ensure the timely resolution of engineering and technology issues; and (3) Technical Risk Ratings as a means to monitor and communicate information about technical risks. This paper will present examples of how Technology Readiness Assessments, External Technical Reviews, and Technical Risk Ratings are being used by DOE-EM to reduce technical risks.

  6. Risk Evaluation for CO{sub 2} Geosequestration in the Knox Supergroup

    SciTech Connect (OSTI)

    Leetaru, Hannes

    2014-01-31

    This report describes a process and provides seed information for identifying and evaluating risks pertinent to a hypothetical carbon dioxide (CO{sub 2}) capture and sequestration (CCS) project. In the envisioned project, the target sequestration reservoir rock is the Potosi Formation of the Knox Supergroup. The Potosi is identified as a potential target formation because (1) at least locally, it contains vuggy to cavernous layers that have very high porosity, and (2) it is present in areas where the deeper Mt. Simon Sandstone (a known potential reservoir unit) is absent or nonporous. The key report content is discussed in Section 3.3, which describes two lists of Features, Events, and Processes (FEPs) that should be considered during the design stage of such a project. These lists primarily highlight risk elements particular to the establishment of the Potosi as the target formation in general. The lists are consciously incomplete with respect to risk elements that would be relevant for essentially all CCS projects regardless of location or geology. In addition, other risk elements specific to a particular future project site would have to be identified. Sources for the FEPs and scenarios listed here include the iconic Quintessa FEPs list developed for the International Energy Agency Greenhouse Gas (IEAGHG) Programme; previous risk evaluation projects executed by Schlumberger Carbon Services; and new input solicited from experts currently working on aspects of CCS in the Knox geology. The projects used as sources of risk information are primarily those that have targeted carbonate reservoir rocks similar in age, stratigraphy, and mineralogy to the Knox-Potosi. Risks of using the Potosi Formation as the target sequestration reservoir for a CCS project include uncertainties about the levels of porosity and permeability of that rock unit; the lateral consistency and continuity of those properties; and the ability of the project team to identify suitable (i

  7. Risk Evaluation for CO2 Geosequestration in the Knox Supergroup, Illinois Basin Final Report

    SciTech Connect (OSTI)

    Hnottavange-Telleen, Ken; Leetaru, Hannes

    2014-09-30

    This report describes a process and provides seed information for identifying and evaluating risks pertinent to a hypothetical carbon dioxide (CO2) capture and sequestration (CCS) project. In the envisioned project, the target sequestration reservoir rock is the Potosi Formation of the Knox Supergroup. The Potosi is identified as a potential target formation because (1) at least locally, it contains vuggy to cavernous layers that have very high porosity, and (2) it is present in areas where the deeper Mt. Simon Sandstone (a known potential reservoir unit) is absent or nonporous. The key report content is discussed in Section 3.3, which describes two lists of Features, Events, and Processes (FEPs) that should be considered during the design stage of such a project. These lists primarily highlight risk elements particular to the establishment of the Potosi as the target formation in general. The lists are consciously incomplete with respect to risk elements that would be relevant for essentially all CCS projects regardless of location or geology. In addition, other risk elements specific to a particular future project site would have to be identified. Sources for the FEPs and scenarios listed here include the iconic Quintessa FEPs list developed for the International Energy Agency Greenhouse Gas (IEAGHG) Programme; previous risk evaluation projects executed by Schlumberger Carbon Services; and new input solicited from experts currently working on aspects of CCS in the Knox geology. The projects used as sources of risk information are primarily those that have targeted carbonate reservoir rocks similar in age, stratigraphy, and mineralogy to the Knox-Potosi. Risks of using the Potosi Formation as the target sequestration reservoir for a CCS project include uncertainties about the levels of porosity and permeability of that rock unit; the lateral consistency and continuity of those properties; and the ability of the project team to identify suitable (i.e., persistently

  8. Environmental radiation standards and risk limitation

    SciTech Connect (OSTI)

    Kocher, D.C.

    1987-01-01

    The Environmental Protection Agency and Nuclear Regulatory Commission have established environmental radiation standards for specific practices which correspond to limits on risk to the public that vary by several orders of magnitude and often are much less than radiation risks that are essentially unregulated, e.g., risks from radon in homes. This paper discusses a proposed framework for environmental radiation standards that would improve the correspondence with limitation of risk. This framework includes the use of limits on annual effective dose equivalent averaged over a lifetime, rather than limits on dose equivalent to whole body or any organ for each year of exposure, and consideration of exposures of younger age groups as well as adults; limits on annual effective dose equivalent averaged over a lifetime no lower than 0.25 mSv (25 mrem) per practice; maintenance of all exposures as low as reasonably achievable (ALARA); and establishment of a generally applicable de minimis dose for public exposures. Implications of the proposed regulatory framework for the current system of standards for limiting public exposures are discussed. 20 refs.

  9. Resource handbook on transportation risk assessment.

    SciTech Connect (OSTI)

    Chen, S. Y.; Biwer, B. M.; Monette, F. A.; Environmental Assessment; SNL; BAPL; USOE; Battelle Memorial Inst.

    2003-01-01

    This resource handbook contains useful information to streamline radioactive material transportation risk assessments for National Environmental Policy Act (NEPA) documents prepared for U.S. Department of Energy (DOE) programs. Streamlining refers to instituting steps that can increase the efficiency of future assessments, reduce costs, and promote increased quality and consistency across the DOE complex. This handbook takes advantage of the wealth of information developed through decades of DOE's NEPA experience. It contains a review of historical assessments; a description of comprehensive and generally acceptable transportation risk assessment methodology (i.e., models); and a compilation of supporting data, parameters, and generally accepted assumptions. This handbook also includes a discussion paper that addresses cumulative impacts (Appendix A). The discussion paper illustrates the evolving and sometimes unresolved issues encountered in transportation risk assessment. Other topics, such as sabotage, environmental justice, and human factors, may be addressed in the future. This resource document was developed as the first primary reference book providing useful information for conducting transportation risk assessments for radioactive material in the NEPA context.

  10. Risk Communication Within the EM Program

    SciTech Connect (OSTI)

    Edelson, M.

    2003-02-26

    The U.S. Department of Energy Environmental Management program (EM) conducts the most extensive environmental remediation effort in the world. The annual EM budgets have exceeded $6,000,000,000 for approximately ten years and EM has assumed responsibility for the cleanup of the largest DOE reservations (i.e., at Hanford, Washington, Aiken, South Carolina, and Idaho Falls, Idaho) as well as the facilities at Rocky Flats, Colorado and in Ohio. Each of these sites has areas of extensive radioactive and chemical contamination, numerous surplus facilities that require decontamination and removal, while some have special nuclear material that requires secure storage. The EM program has been criticized for being ineffective (1) and has been repeatedly reorganized to address perceived shortcomings. The most recent reorganization was announced in 2001 to become effective at the beginning of the 2003 Federal Fiscal Year (i.e., October 2002). It was preceded by a ''top to bottom'' review (TTBR) of the program (2) that identified several deficiencies that were to be corrected as a result of the reorganization. One prominent outcome of the TTBR was the identification of ''risk reduction'' as an organizing principle to prioritize the activities of the new EM program. The new program also sought to accelerate progress by identifying a set of critical activities at each site that could be accelerated and result in more rapid site closure, with attendant risk, cost, and schedule benefits. This paper investigates how the new emphasis on risk reduction in the EM program has been communicated to EM stakeholders and regulators. It focuses on the Rocky Flats Environmental Technology Site (RFETS) as a case study and finds that there is little evidence for a new emphasis on risk reduction in EM communications with RFETS stakeholders. Discussions between DOE and RFETS stakeholders often refer to ''risk,'' but the word serves as a placeholder for other concepts. Thus ''risk'' communication

  11. RISK REDUCTION WITH A FUZZY EXPERT EXPLORATION TOOL

    SciTech Connect (OSTI)

    Robert Balch

    2003-04-15

    Incomplete or sparse information on types of data such as geologic or formation characteristics introduces a high level of risk for oil exploration and development projects. ''Expert'' systems developed and used in several disciplines and industries have demonstrated beneficial results. A state-of-the-art exploration ''expert'' tool, relying on a computerized database and computer maps generated by neural networks, is being developed through the use of ''fuzzy'' logic, a relatively new mathematical treatment of imprecise or non-explicit parameters and values. Oil prospecting risk can be reduced with the use of a properly developed and validated ''Fuzzy Expert Exploration (FEE) Tool.'' This FEE Tool can be beneficial in many regions of the U.S. by enabling risk reduction in oil and gas prospecting as well as decreased prospecting and development costs. In the 1998-1999 oil industry environment, many smaller exploration companies lacked the resources of a pool of expert exploration personnel. Downsizing, low oil prices, and scarcity of exploration funds have also affected larger companies, and will, with time, affect the end users of oil industry products in the U.S. as reserves are depleted. The pool of experts is much reduced today. The FEE Tool will benefit a diverse group in the U.S., leading to a more efficient use of scarce funds, and possibly decreasing dependence on foreign oil and lower product prices for consumers. This fourth of five annual reports contains a summary of progress to date, problems encountered, plans for the next year, and an assessment of the prospects for future progress. The emphasis during the April 2002 through March 2003 period was directed toward Silurian-Devonian geology, development of rules for the fuzzy system, and on-line software.

  12. RISK REDUCTION WITH A FUZZY EXPERT EXPLORATION TOOL

    SciTech Connect (OSTI)

    Robert Balch

    2004-04-08

    Incomplete or sparse information on types of data such as geologic or formation characteristics introduces a high level of risk for oil exploration and development projects. ''Expert'' systems developed and used in several disciplines and industries have demonstrated beneficial results. A state-of-the-art exploration ''expert'' tool, relying on a computerized database and computer maps generated by neural networks, is being developed through the use of ''fuzzy'' logic, a relatively new mathematical treatment of imprecise or non-explicit parameters and values. Oil prospecting risk can be reduced with the use of a properly developed and validated ''Fuzzy Expert Exploration (FEE) Tool.'' This FEE Tool can be beneficial in many regions of the U.S. by enabling risk reduction in oil and gas prospecting as well as decreased prospecting and development costs. In the 1998-1999 oil industry environment, many smaller exploration companies lacked the resources of a pool of expert exploration personnel. Downsizing, low oil prices, and scarcity of exploration funds have also affected larger companies, and will, with time, affect the end users of oil industry products in the U.S. as reserves are depleted. The FEE Tool will benefit a diverse group in the U.S., leading to a more efficient use of scarce funds, and possibly decreasing dependence on foreign oil and lower product prices for consumers. This fifth annual (and tenth of 12 semi-annual reports) contains a summary of progress to date, problems encountered, plans for the next year, and an assessment of the prospects for future progress. The emphasis during the March 2003 through March 2004 period was directed toward completion of the Brushy Canyon FEE Tool and to Silurian-Devonian geology, and development of rules for the Devonian fuzzy system, and on-line software.

  13. RISK REDUCTION WITH A FUZZY EXPERT EXPLORATION TOOL

    SciTech Connect (OSTI)

    Robert Balch

    2003-10-15

    Incomplete or sparse information on types of data such as geologic or formation characteristics introduces a high level of risk for oil exploration and development projects. ''Expert'' systems developed and used in several disciplines and industries have demonstrated beneficial results. A state-of-the-art exploration ''expert'' tool, relying on a computerized database and computer maps generated by neural networks, is being developed through the use of ''fuzzy'' logic, a relatively new mathematical treatment of imprecise or non-explicit parameters and values. Oil prospecting risk can be reduced with the use of a properly developed and validated ''Fuzzy Expert Exploration (FEE) Tool.'' This FEE Tool can be beneficial in many regions of the U.S. by enabling risk reduction in oil and gas prospecting as well as decreased prospecting and development costs. In the 1998-1999 oil industry environment, many smaller exploration companies lacked the resources of a pool of expert exploration personnel. Downsizing, low oil prices, and scarcity of exploration funds have also affected larger companies, and will, with time, affect the end users of oil industry products in the U.S. as reserves are depleted. The FEE Tool will benefit a diverse group in the U.S., leading to a more efficient use of scarce funds, and possibly decreasing dependence on foreign oil and lower product prices for consumers. This ninth of ten semi-annual reports contains a summary of progress to date, problems encountered, plans for the next year, and an assessment of the prospects for future progress. The emphasis during the March 2003 through September 2003 period was directed toward Silurian-Devonian geology, development of rules for the fuzzy system, and on-line software.

  14. RISK REDUCTION WITH A FUZZY EXPERT EXPLORATION TOOL

    SciTech Connect (OSTI)

    William W. Weiss

    2001-09-30

    Incomplete or sparse information on types of data such as geologic or formation characteristics introduces a high level of risk for oil exploration and development projects. ''Expert'' systems developed and used in several disciplines and industries have demonstrated beneficial results. A state-of-the-art exploration ''expert'' tool, relying on a computerized database and computer maps generated by neural networks, is being developed through the use of ''fuzzy'' logic, a relatively new mathematical treatment of imprecise or non-explicit parameters and values. Oil prospecting risk can be reduced with the use of a properly developed and validated ''Fuzzy Expert Exploration (FEE) Tool.'' This FEE Tool can be beneficial in many regions of the U.S. by enabling risk reduction in oil and gas prospecting as well as decreased prospecting and development costs. In the 1998-1999 oil industry environment, many smaller exploration companies lacked the resources of a pool of expert exploration personnel. Downsizing, low oil prices, and scarcity of exploration funds have also affected larger companies, and will, with time, affect the end users of oil industry products in the U.S. as reserves are depleted. As a result, today's pool of experts is much reduced. The FEE Tool will benefit a diverse group in the U.S., leading to a more efficient use of scarce funds and lower product prices for consumers. This fifth of ten semi-annual reports contains a summary of progress to date, problems encountered, plans for the next year, and an assessment of the prospects for future progress. The emphasis during the May 2001 through September 2001 was directed toward development of rules for the fuzzy system.

  15. Mathematics, Pricing, Market Risk Management and Trading Strategies for Financial Derivatives (2/3)

    ScienceCinema (OSTI)

    None

    2011-10-06

    Market Trading and Risk Management of Vanilla FX Options - Measures of Market Risk - Implied Volatility - FX Risk Reversals, FX Strangles - Valuation and Risk Calculations - Risk Management - Market Trading Strategies

  16. Risk transfer via energy savings insurance

    SciTech Connect (OSTI)

    Mills, Evan

    2001-10-01

    Among the key barriers to investment in energy efficiency improvements are uncertainties about attaining projected energy savings and apprehension about potential disputes over these savings. The fields of energy management and risk management are thus intertwined. While many technical methods have emerged to manage performance risks (e.g. building commissioning), financial risk transfer techniques are less developed in the energy management arena than in other more mature segments of the economy. Energy Savings Insurance (ESI) - formal insurance of predicted energy savings - is one method of transferring financial risks away from the facility owner or energy services contractor. ESI offers a number of significant advantages over other forms of financial risk transfer, e.g. savings guarantees or performance bonds. ESI providers manage risk via pre-construction design review as well as post-construction commissioning and measurement and verification of savings. We found that the two mos t common criticisms of ESI - excessive pricing and onerous exclusions - are not born out in practice. In fact, if properly applied, ESI can potentially reduce the net cost of energy savings projects by reducing the interest rates charged by lenders, and by increasing the level of savings through quality control. Debt service can also be ensured by matching loan payments to projected energy savings while designing the insurance mechanism so that payments are made by the insurer in the event of a savings shortfall. We estimate the U.S. ESI market potential of $875 million/year in premium income. From an energy-policy perspective, ESI offers a number of potential benefits: ESI transfers performance risk from the balance sheet of the entity implementing the energy savings project, thereby freeing up capital otherwise needed to ''self-insure'' the savings. ESI reduces barriers to market entry of smaller energy services firms who do not have sufficiently strong balance sheets to self

  17. Geographic resolution issues in RAM transportation risk analysis

    SciTech Connect (OSTI)

    MILLS,G. SCOTT; NEUHAUSER,SIEGLINDE

    2000-04-12

    Over the years that radioactive material (RAM) transportation risk estimates have been calculated using the RADTRAN code, demand for improved geographic resolution of route characteristics, especially density of population neighboring route segments, has led to code improvements that provide more specific route definition. With the advent of geographic information systems (GISs), the achievable resolution of route characteristics is theoretically very high. The authors have compiled population-density data in 1-kilometer increments for routes extending over hundreds of kilometers without impractical expenditures of time. Achievable resolution of analysis is limited, however, by the resolution of available data. U.S. Census data typically have 1-km or better resolution within densely-populated portions of metropolitan areas but census blocks are much larger in rural areas. Geographic resolution of accident-rate data, especially for heavy/combination trucks, are typically tabulated on a statewide basis. These practical realities cause one to ask what level(s) of resolution may be necessary for meaningful risk analysis of transportation actions on a state or interstate scale.

  18. High Energy Physics

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    High Energy Physics High Energy Physics Investigating the field of high energy physics ... Through the Office of High Energy Physics (HEP), Los Alamos conducts research in particle ...

  19. RISK-INFORMED BALANCING OF SAFETY, NONPROLIFERATION, AND ECONOMICS FOR THE SFR

    SciTech Connect (OSTI)

    Apostolakis, George; Driscoll, Michael; Golay, Michael; Kadak, Andrew; Todreas, Neil; Aldmir, Tunc; Denning, Richard; Lineberry, Michael

    2011-10-20

    , particularly concerning seismic and aircraft impactrelated risks. Most importantly, within the context of the TNF historical SFR safety concerns about energetic core disruptive accidents are seen to be unimportant, but those of rare scenarios mentioned above are seen to be of dominant concern. In terms of proliferation risks the SFR energy system is seen not to be of considerably greater concern than with other nuclear power technologies, providing that highly effective safeguards are employed. We find the economic performance of proposed SFRs likely, due to the problems of using sodium as a coolant, to be inferior to those of LWRs unless they can be credited for services to improve nuclear waste disposal, nuclear fuel utilization and proliferation risk reductions. None of the design innovations investigated offers the promise to reverse this conclusion. The most promising innovation investigated is that of improving the plant's thermodynamic efficiency via use of the supercritical CO{sub 2} (rather than steam Rankine) power conversion system. We were unable to reach conclusions about the economic and proliferation risk implications of competing nuclear fuel processing methods, as available designs are too little developed to justify any such results. Overall, we find the SFR to be a promising alternative to LWRs should the conditions governing the valuation change substantially from current ones.

  20. POTENTIAL HEALTH RISK REDUCTION ARISING FROM REDUCED MERCURY EMISSIONS FROM COAL FIRED POWER PLANTS.

    SciTech Connect (OSTI)

    Sullivan, T. M.; Lipfert, F. W.; Morris, S. C.; Moskowitz, P. D.

    2001-09-01

    The U.S. Environmental Protection Agency (EPA) has announced plans to regulate mercury (Hg) emissions from coal-fired power plants. EPA has not prepared a quantitative assessment of the reduction in risk that could be achieved through reduction in coal plant emissions of Hg. To address this issue, Brookhaven National Laboratory (BNL) with support from the U.S. Department of Energy Office of Fossil Energy (DOE FE) prepared a quantitative assessment of the reduction in human health risk that could be achieved through reduction in coal plant emissions of Hg. The primary pathway for Hg exposure is through consumption of fish. The most susceptible population to Hg exposure is the fetus. Therefore the risk assessment focused on consumption of fish by women of child-bearing age. Dose response factors were generated from studies on loss of cognitive abilities (language skills, motor skills, etc.) by young children whose mothers consumed large amounts of fish with high Hg levels. Population risks were estimated for the general population in three regions of the country, (the Midwest, Northeast, and Southeast) that were identified by EPA as being heavily impacted by coal emissions. Three scenarios for reducing Hg emissions from coal plants were considered: (1) A base case using current conditions; (2) A 50% reduction; and, (3) A 90% reduction. These reductions in emissions were assumed to translate linearly into a reduction in fish Hg levels of 8.6% and 15.5%, respectively. Population risk estimates were also calculated for two subsistence fisher populations. These groups of people consume substantially more fish than the general public and, depending on location, the fish may contain higher Hg levels than average. Risk estimates for these groups were calculated for the three Hg levels used for the general population analyses. Analysis shows that the general population risks for exposure of the fetus to Hg are small. Estimated risks under current conditions (i.e., no

  1. Reference manual for toxicity and exposure assessment and risk characterization. CERCLA Baseline Risk Assessment

    SciTech Connect (OSTI)

    1995-03-01

    The Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA, 1980) (CERCLA or Superfund) was enacted to provide a program for identifying and responding to releases of hazardous substances into the environment. The Superfund Amendments and Reauthorization Act (SARA, 1986) was enacted to strengthen CERCLA by requiring that site clean-ups be permanent, and that they use treatments that significantly reduce the volume, toxicity, or mobility of hazardous pollutants. The National Oil and Hazardous Substances Pollution Contingency Plan (NCP) (USEPA, 1985; USEPA, 1990) implements the CERCLA statute, presenting a process for (1) identifying and prioritizing sites requiring remediation and (2) assessing the extent of remedial action required at each site. The process includes performing two studies: a Remedial Investigation (RI) to evaluate the nature, extent, and expected consequences of site contamination, and a Feasibility Study (FS) to select an appropriate remedial alternative adequate to reduce such risks to acceptable levels. An integral part of the RI is the evaluation of human health risks posed by hazardous substance releases. This risk evaluation serves a number of purposes within the overall context of the RI/FS process, the most essential of which is to provide an understanding of ``baseline`` risks posed by a given site. Baseline risks are those risks that would exist if no remediation or institutional controls are applied at a site. This document was written to (1) guide risk assessors through the process of interpreting EPA BRA policy and (2) help risk assessors to discuss EPA policy with regulators, decision makers, and stakeholders as it relates to conditions at a particular DOE site.

  2. High Frequency Ground Motion Simulation for Seismic Hazard Analysis |

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Argonne Leadership Computing Facility Ground motion simulations reveal regions at risk Ground motion simulations reveal regions at risk of strong shaking during a possible magnitude-8 earthquake on the San Andreas fault. For the CyberShake project, reciprocal simulations of all known possible quakes are combined to estimate the total probabilistic hazard for California. Credit: Geoffrey Ely, Argonne National Laboratory High Frequency Ground Motion Simulation for Seismic Hazard Analysis PI

  3. High Frequency Physics-Based Earthquake System Simulations | Argonne

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Leadership Computing Facility Ground motion simulations reveal regions at risk of strong shaking during a possible magnitude-8 earthquake on the San Andreas fault Ground motion simulations reveal regions at risk of strong shaking during a possible magnitude-8 earthquake on the San Andreas fault. For the CyberShake project, reciprocal simulations of all known possible quakes are combined to estimate the total probabilistic hazard for California. Geoffrey Ely, Argonne National Laboratory High

  4. Risk Management Guide - DOE Directives, Delegations, and Requirements

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    G 413.3-7A Chg 1 (Admin Chg), Risk Management Guide by Diane Johnson Functional areas: Risk Management, Safety and Security The purpose of this guide is to describe effective risk management processes. The continuous and iterative process includes updating project risk documents and the risk management plan and emphasizes implementation communication of the risks and actions taken. g4133-7a_AdminChg1_10-22-2015.pdf -- PDF Document, 1.48 MB Writer: Diane Johnson Subjects: Management and

  5. Quantification of risks from technology for improved plant reliability

    SciTech Connect (OSTI)

    Rode, D.M.

    1996-12-31

    One of the least understood and therefore appreciated threats to profitability are risks from power plant technologies such as steam generators, turbines, and electrical systems. To effectively manage technological risks, business decisions need to be based on knowledge. The scope of the paper describes a quantification or risk process that combines technical knowledge and judgments with commercial consequences. The three principle alternatives to manage risks as well as risk mitigation techniques for significant equipment within a power plant are reported. The result is to equip the decision maker with a comprehensive picture of the risk exposures enabling cost effective activities to be undertaken to improve a plant`s reliability.

  6. Tank Waste Remediation System Characterization Project Programmatic Risk Management Plan

    SciTech Connect (OSTI)

    Baide, D.G.; Webster, T.L.

    1995-12-01

    The TWRS Characterization Project has developed a process and plan in order to identify, manage and control the risks associated with tank waste characterization activities. The result of implementing this process is a defined list of programmatic risks (i.e. a risk management list) that are used by the Project as management tool. This concept of risk management process is a commonly used systems engineering approach which is being applied to all TWRS program and project elements. The Characterization Project risk management plan and list are subset of the overall TWRS risk management plan and list.

  7. Risk-based evaluation of Allowed Outage Times (AOTs) considering risk of shutdown

    SciTech Connect (OSTI)

    Mankamo, T.; Kim, I.S.; Samanta, P.K.

    1992-12-31

    When safety systems fail during power operation, Technical Specifications (TS) usually limit the repair within Allowed Outage Time (AOT). If the repair cannot be completed within the AOT, or no AOT is allowed, the plant is required to be shut down for the repair. However, if the capability to remove decay heat is degraded, shutting down the plant with the need to operate the affected decay-heat removal systems may impose a substantial risk compared to continued power operation over a usual repair time. Thus, defining a proper AOT in such situations can be considered as a risk-comparison between the repair in frill power state with a temporarily increased level of risk, and the altemative of shutting down the plant for the repair in zero power state with a specific associated risk. The methodology of the risk-comparison approach, with a due consideration of the shutdown risk, has been further developed and applied to the AOT considerations of residual heat removal and standby service water systems of a boiling water reactor (BWR) plant. Based on the completed work, several improvements to the TS requirements for the systems studied can be suggested.

  8. Risk-based evaluation of Allowed Outage Times (AOTs) considering risk of shutdown

    SciTech Connect (OSTI)

    Mankamo, T. ); Kim, I.S.; Samanta, P.K. )

    1992-01-01

    When safety systems fail during power operation, Technical Specifications (TS) usually limit the repair within Allowed Outage Time (AOT). If the repair cannot be completed within the AOT, or no AOT is allowed, the plant is required to be shut down for the repair. However, if the capability to remove decay heat is degraded, shutting down the plant with the need to operate the affected decay-heat removal systems may impose a substantial risk compared to continued power operation over a usual repair time. Thus, defining a proper AOT in such situations can be considered as a risk-comparison between the repair in frill power state with a temporarily increased level of risk, and the altemative of shutting down the plant for the repair in zero power state with a specific associated risk. The methodology of the risk-comparison approach, with a due consideration of the shutdown risk, has been further developed and applied to the AOT considerations of residual heat removal and standby service water systems of a boiling water reactor (BWR) plant. Based on the completed work, several improvements to the TS requirements for the systems studied can be suggested.

  9. Supplemental Hazard Analysis and Risk Assessment - Hydrotreater

    SciTech Connect (OSTI)

    Lowry, Peter P.; Wagner, Katie A.

    2015-04-01

    A supplemental hazard analysis was conducted and quantitative risk assessment performed in response to an independent review comment received by the Pacific Northwest National Laboratory (PNNL) from the U.S. Department of Energy Pacific Northwest Field Office (PNSO) against the Hydrotreater/Distillation Column Hazard Analysis Report issued in April 2013. The supplemental analysis used the hazardous conditions documented by the previous April 2013 report as a basis. The conditions were screened and grouped for the purpose of identifying whether additional prudent, practical hazard controls could be identified, using a quantitative risk evaluation to assess the adequacy of the controls and establish a lower level of concern for the likelihood of potential serious accidents. Calculations were performed to support conclusions where necessary.

  10. Marine and Hydrokinetic Technology Development Risk Management Framework

    SciTech Connect (OSTI)

    Snowberg, David; Weber, Jochem

    2015-09-01

    Over the past decade, the global marine and hydrokinetic (MHK) industry has suffered a number of serious technological and commercial setbacks. To help reduce the risks of industry failures and advance the development of new technologies, the U.S. Department of Energy (DOE) and the National Renewable Energy Laboratory (NREL) developed an MHK Risk Management Framework. By addressing uncertainties, the MHK Risk Management Framework increases the likelihood of successful development of an MHK technology. It covers projects of any technical readiness level (TRL) or technical performance level (TPL) and all risk types (e.g. technological risk, regulatory risk, commercial risk) over the development cycle. This framework is intended for the development and deployment of a single MHK technology—not for multiple device deployments within a plant. This risk framework is intended to meet DOE’s risk management expectations for the MHK technology research and development efforts of the Water Power Program (see Appendix A). It also provides an overview of other relevant risk management tools and documentation.1 This framework emphasizes design and risk reviews as formal gates to ensure risks are managed throughout the technology development cycle. Section 1 presents the recommended technology development cycle, Sections 2 and 3 present tools to assess the TRL and TPL of the project, respectively. Section 4 presents a risk management process with design and risk reviews for actively managing risk within the project, and Section 5 presents a detailed description of a risk registry to collect the risk management information into one living document. Section 6 presents recommendations for collecting and using lessons learned throughout the development process.

  11. Hydrogen Risk Assessment Model (HyRAM)

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Risk Assessment Model (HyRAM) - Sandia Energy Energy Search Icon Sandia Home Locations Contact Us Employee Locator Energy & Climate Secure & Sustainable Energy Future Stationary Power Energy Conversion Efficiency Solar Energy Wind Energy Water Power Supercritical CO2 Geothermal Natural Gas Safety, Security & Resilience of the Energy Infrastructure Energy Storage Nuclear Power & Engineering Grid Modernization Battery Testing Nuclear Energy Defense Waste Management Programs

  12. Assessment of health risks of policies

    SciTech Connect (OSTI)

    Ádám, Balázs; Molnár, Ágnes; Ádány, Róza; Bianchi, Fabrizio; Bitenc, Katarina; Chereches, Razvan; Cori, Liliana; Fehr, Rainer; Kobza, Joanna; Kollarova, Jana; and others

    2014-09-15

    The assessment of health risks of policies is an inevitable, although challenging prerequisite for the inclusion of health considerations in political decision making. The aim of our project was to develop a so far missing methodological guide for the assessment of the complex impact structure of policies. The guide was developed in a consensual way based on experiences gathered during the assessment of specific national policies selected by the partners of an EU project. Methodological considerations were discussed and summarized in workshops and pilot tested on the EU Health Strategy for finalization. The combined tool, which includes a textual guidance and a checklist, follows the top-down approach, that is, it guides the analysis of causal chains from the policy through related health determinants and risk factors to health outcomes. The tool discusses the most important practical issues of assessment by impact level. It emphasises the transparent identification and prioritisation of factors, the consideration of the feasibility of exposure and outcome assessment with special focus on quantification. The developed guide provides useful methodological instructions for the comprehensive assessment of health risks of policies that can be effectively used in the health impact assessment of policy proposals. - Highlights: • Methodological guide for the assessment of health risks of policies is introduced. • The tool is developed based on the experiences from several case studies. • The combined tool consists of a textual guidance and a checklist. • The top-down approach is followed through the levels of the full impact chain. • The guide provides assistance for the health impact assessment of policy proposals.

  13. Health effects of risk-assessment categories

    SciTech Connect (OSTI)

    Kramer, C.F.; Rybicka, K.; Knutson, A.; Morris, S.C.

    1983-10-01

    Environmental and occupational health effects associated with exposures to various chemicals are a subject of increasing concern. One recently developed methodology for assessing the health impacts of various chemical compounds involves the classification of similar chemicals into risk-assessment categories (RACs). This report reviews documented human health effects for a broad range of pollutants, classified by RACs. It complements other studies that have estimated human health effects by RAC based on analysis and extrapolation of data from animal research.

  14. Aware of the risks, the Federal Aviation

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Aware of the risks, the Federal Aviation Administration (FAA) in 2013 announced a new policy that calls for quantified analysis of potential ocular hazards from glint and glare for PV installations planned at airports-and other organizations are calling for similar analyses. Commercial ray-tracing tools can be used to model glare occurrences, but are expensive and complicated to set-up, placing a significant burden on companies seeking to comply with the FAA requirement. New Tool Helps Private

  15. Assuaging Nuclear Energy Risks: The Angarsk International Uranium Enrichment Center

    SciTech Connect (OSTI)

    Myers, Astasia

    2011-06-28

    The recent nuclear renaissance has motivated many countries, especially developing nations, to plan and build nuclear power reactors. However, domestic low enriched uranium demands may trigger nations to construct indigenous enrichment facilities, which could be redirected to fabricate high enriched uranium for nuclear weapons. The potential advantages of establishing multinational uranium enrichment sites are numerous including increased low enrichment uranium access with decreased nuclear proliferation risks. While multinational nuclear initiatives have been discussed, Russia is the first nation to actualize this concept with their Angarsk International Uranium Enrichment Center (IUEC). This paper provides an overview of the historical and modern context of the multinational nuclear fuel cycle as well as the evolution of Russia's IUEC, which exemplifies how international fuel cycle cooperation is an alternative to domestic facilities.

  16. Environmental risk and the business bottom line

    SciTech Connect (OSTI)

    Wright, N.H.

    1996-12-31

    Demands for the integration of environmental considerations into the business priorities of leading companies are gathering momentum. Potentially devastating financial losses linked to environmental problems or mismanagement and perceptions of environmental issues, has alarmed the public, financial and insurance sectors together with key stakeholders. Expensive lessons have been learned in recent years - poor environmental design and management can undoubtedly lead to escalation of overall costs to meet changing standards and end of life cycle decommissioning bills. Environmental impact not only damages profitability but erodes the corporate asset base. Even suspicion of land contamination can wipe out market values of real estate. Comprehensive screening of business portfolios, investment plans, and existing assets for sources of environmental risk from concept to divestment, is crucial to ensure environmentally sound investment, to protect assets and minimize both environmental impact and future liability. Today`s key stakeholders and financial sectors are looking beyond the existing balance sheets of companies and now scrutinise their environmental credentials to ensure wise investment. Recent developments in environmental risk as a tool for placing environment on the balance sheet of private and public companies will be presented, using selected examples geared to the exploration and production business, together with the needs for a common, international framework for environmental risk strategies.

  17. Gasbuggy Site Assessment and Risk Evaluation

    SciTech Connect (OSTI)

    2011-03-01

    This report describes the geologic and hydrologic conditions and evaluates potential health risks to workers in the natural gas industry in the vicinity of the Gasbuggy, New Mexico, site, where the U.S. Atomic Energy Commission detonated an underground nuclear device in 1967. The 29-kiloton detonation took place 4,240 feet below ground surface and was designed to evaluate the use of a nuclear detonation to enhance natural gas production from the Pictured Cliffs Formation in the San Juan Basin, Rio Arriba County, New Mexico, on land administered by Carson National Forest. A site-specific conceptual model was developed based on current understanding of the hydrologic and geologic environment. This conceptual model was used for establishing plausible contaminant exposure scenarios, which were then evaluated for human health risk potential. The most mobile and, therefore, the most probable contaminant that could result in human exposure is tritium. Natural gas production wells were identified as having the greatest potential for bringing detonation-derived contaminants (tritium) to the ground surface in the form of tritiated produced water. Three exposure scenarios addressing potential contamination from gas wells were considered in the risk evaluation: a gas well worker during gas-well-drilling operations, a gas well worker performing routine maintenance, and a residential exposure. The residential exposure scenario was evaluated only for comparison; permanent residences on national forest lands at the Gasbuggy site are prohibited

  18. Evaluation of residue drum storage safety risks

    SciTech Connect (OSTI)

    Conner, W.V.

    1994-06-17

    A study was conducted to determine if any potential safety problems exist in the residue drum backlog at the Rocky Flats Plant. Plutonium residues stored in 55-gallon drums were packaged for short-term storage until the residues could be processed for plutonium recovery. These residues have now been determined by the Department of Energy to be waste materials, and the residues will remain in storage until plans for disposal of the material can be developed. The packaging configurations which were safe for short-term storage may not be safe for long-term storage. Interviews with Rocky Flats personnel involved with packaging the residues reveal that more than one packaging configuration was used for some of the residues. A tabulation of packaging configurations was developed based on the information obtained from the interviews. A number of potential safety problems were identified during this study, including hydrogen generation from some residues and residue packaging materials, contamination containment loss, metal residue packaging container corrosion, and pyrophoric plutonium compound formation. Risk factors were developed for evaluating the risk potential of the various residue categories, and the residues in storage at Rocky Flats were ranked by risk potential. Preliminary drum head space gas sampling studies have demonstrated the potential for formation of flammable hydrogen-oxygen mixtures in some residue drums.

  19. Designs for Risk Evaluation and Management

    SciTech Connect (OSTI)

    2015-12-01

    The Designs for Risk Evaluation and Management (DREAM) tool was developed as part of the effort to quantify the risk of geologic storage of carbon dioxide (CO2) under the U.S. Department of Energy’s National Risk Assessment Partnership (NRAP). DREAM is an optimization tool created to identify optimal monitoring schemes that minimize the time to first detection of CO2 leakage from a subsurface storage formation. DREAM acts as a post-processer on user-provided output from subsurface leakage simulations. While DREAM was developed for CO2 leakage scenarios, it is applicable to any subsurface leakage simulation of the same output format. The DREAM tool is comprised of three main components: (1) a Java wizard used to configure and execute the simulations, (2) a visualization tool to view the domain space and optimization results, and (3) a plotting tool used to analyze the results. A secondary Java application is provided to aid users in converting common American Standard Code for Information Interchange (ASCII) output data to the standard DREAM hierarchical data format (HDF5). DREAM employs a simulated annealing approach that searches the solution space by iteratively mutating potential monitoring schemes built of various configurations of monitoring locations and leak detection parameters. This approach has proven to be orders of magnitude faster than an exhaustive search of the entire solution space. The user’s manual illustrates the program graphical user interface (GUI), describes the tool inputs, and includes an example application.

  20. Policy Flash 2014-32 General Accountability Office Report (GAO) final report entitled National Laboratories: DOE needs to Improve Oversight of Work performed for non-DOE Entities (GAO 14_78 October 2013)

    Broader source: Energy.gov [DOE]

    Questions concerning this policy flash should be directed to Andrew Scott Geary, Office of Contract and Financial Assistance Policy in the Office of the Acquisition and Project management by phone...

  1. Milestone Reached: New Process Reduces Cost and Risk of Biofuel...

    Office of Environmental Management (EM)

    Risk of Biofuel Production from Bio-Oil Upgrading Milestone Reached: New Process Reduces Cost and Risk of Biofuel Production from Bio-Oil Upgrading May 6, 2015 - 11:29am Addthis ...

  2. Business risks to utilities as new nuclear power costs escalate

    SciTech Connect (OSTI)

    Severance, Craig A.

    2009-05-15

    A nuclear power megaproject carries with it severe business risks. Despite attempts to shift these risks to taxpayers and ratepayers, ultimately there are no guarantees for utility shareholders. Utility management needs to keep some core principles in mind. (author)

  3. Reducing Cyber Risk to Critical Infrastructure: NIST Framework

    Broader source: Energy.gov [DOE]

    The National Institute of Standards and Technology (NIST) works with stakeholders to develop a voluntary Framework for reducing cyber risks to critical infrastructure. The Framework aims to be flexible and repeatable, while helping asset owner and operators manage cybersecurity risk.

  4. Reduce Risk, Increase Clean Energy: How States and Cities are...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Reduce Risk, Increase Clean Energy: How States and Cities are Using Old Finance Tools to Scale Up a New Industry Reduce Risk, Increase Clean Energy: How States and Cities are Using ...

  5. Assistant Director, Credit Modeling and Transaction Risk Management Division

    Broader source: Energy.gov [DOE]

    The Risk Management Division (RMD) is the group within the U.S. Department of Energys Loan Program Office (LPO) that is responsible for oversight of all risks that have the potential to impede the...

  6. RAVEN, a New Software for Dynamic Risk Analysis (Conference)...

    Office of Scientific and Technical Information (OSTI)

    RAVEN, a New Software for Dynamic Risk Analysis Citation Details In-Document Search Title: RAVEN, a New Software for Dynamic Risk Analysis RAVEN is a generic software driver to ...

  7. Interagency Performance and Risk Assessment Community of Practice...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Interagency Performance and Risk Assessment Community of Practice (P&RA CoP) Charter Interagency Performance and Risk Assessment Community of Practice (P&RA CoP) Charter Charter ...

  8. List of Topics for Interagency Performance & Risk Assessment...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    & Risk Assessment Community of Practice (P&RA CoP) Discussion List of Topics for Interagency Performance & Risk Assessment Community of Practice (P&RA CoP) Discussion List of ...

  9. An Integrated Framework for CO2 Accounting and Risk Analysis...

    Office of Scientific and Technical Information (OSTI)

    An Integrated Framework for CO2 Accounting and Risk Analysis in CO2-EOR Sites Citation Details In-Document Search Title: An Integrated Framework for CO2 Accounting and Risk ...

  10. A classification scheme for risk assessment methods.

    SciTech Connect (OSTI)

    Stamp, Jason Edwin; Campbell, Philip LaRoche

    2004-08-01

    This report presents a classification scheme for risk assessment methods. This scheme, like all classification schemes, provides meaning by imposing a structure that identifies relationships. Our scheme is based on two orthogonal aspects--level of detail, and approach. The resulting structure is shown in Table 1 and is explained in the body of the report. Each cell in the Table represent a different arrangement of strengths and weaknesses. Those arrangements shift gradually as one moves through the table, each cell optimal for a particular situation. The intention of this report is to enable informed use of the methods so that a method chosen is optimal for a situation given. This report imposes structure on the set of risk assessment methods in order to reveal their relationships and thus optimize their usage.We present a two-dimensional structure in the form of a matrix, using three abstraction levels for the rows and three approaches for the columns. For each of the nine cells in the matrix we identify the method type by name and example. The matrix helps the user understand: (1) what to expect from a given method, (2) how it relates to other methods, and (3) how best to use it. Each cell in the matrix represent a different arrangement of strengths and weaknesses. Those arrangements shift gradually as one moves through the table, each cell optimal for a particular situation. The intention of this report is to enable informed use of the methods so that a method chosen is optimal for a situation given. The matrix, with type names in the cells, is introduced in Table 2 on page 13 below. Unless otherwise stated we use the word 'method' in this report to refer to a 'risk assessment method', though often times we use the full phrase. The use of the terms 'risk assessment' and 'risk management' are close enough that we do not attempt to distinguish them in this report. The remainder of this report is organized as follows. In Section 2 we provide context for this report

  11. Incidence, Risks, and Sequelae of Posterior Fossa Syndrome in Pediatric Medulloblastoma

    SciTech Connect (OSTI)

    Korah, Mariam P.; Esiashvili, Natia; Mazewski, Claire M.; Hudgins, Roger J.; Tighiouart, Mourad; Janss, Anna J.; Schwaibold, Frederick P.; Crocker, Ian R.; Curran, Walter J.; Marcus, Robert B.

    2010-05-01

    Purpose: To investigate the incidence, risks, severity, and sequelae of posterior fossa syndrome (PFS) in children with medulloblastoma. Methods and Materials: Between 1990 and 2007, 63 children with medulloblastoma at Emory University and Children's Healthcare of Atlanta were treated with craniectomy followed by radiation. Fifty-one patients were assigned to a standard-risk group, and 12 patients were assigned to a high-risk group. Five patients had <1.5-cm{sup 2} residual tumor, 4 had >=1.5-cm{sup 2} residual tumor, and the remainder had no residual tumor. Eleven patients had disseminated disease. Patients received craniospinal irradiation at a typical dose of 23.4 Gy or 36 Gy for standard- or high-risk disease, respectively. The posterior fossa was given a total dose of 54 or 55.8 Gy. Nearly all patients received chemotherapy following cooperative group protocols. Results: Median follow-up was 7 years. PFS developed in 18 patients (29%). On univariate analysis, brainstem invasion, midline tumor location, younger age, and the absence of radiographic residual tumor were found to be predictors of PFS; the last two variables remained significant on multivariate analysis. From 1990 to 2000 and from 2001 to 2007, the proportions of patients with no radiographic residual tumor were 77% and 94%, respectively. During the same eras, the proportions of patients with PFS were 17% and 39%. Only 4 patients had complete recovery at last follow-up. Conclusions: The incidence of PFS increased in the latter study period and is proportional to more aggressive surgery. Children with midline tumors exhibiting brainstem invasion are at increased risk. With the increased incidence of PFS and the permanent morbidity in many patients, the risks and benefits of complete tumor removal in all patients need to be reexamined.

  12. Major Risk Factors to the Integrated Facility Disposition Project |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy to the Integrated Facility Disposition Project Major Risk Factors to the Integrated Facility Disposition Project The scope of the Integrated Facility Disposition Project (IFDP) needs to comprehensively address a wide range of environmental management risks at the Oak Ridge Reservation (ORO). Major Risk Factors to the Integrated Facility Disposition Project (227.35 KB) More Documents & Publications Major Risk Factors Integrated Facility Disposition Project - Oak Ridge

  13. Sustainability for the Global Biofuels Industry Minimizing Risks...

    Office of Environmental Management (EM)

    Sustainability for the Global Biofuels Industry Minimizing Risks and Maximizing ... More Documents & Publications Sustainability for the Global Biofuels Industry: Minimizing ...

  14. Sustainability for the Global Biofuels Industry: Minimizing Risks...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Global Biofuels Industry: Minimizing Risks and Maximizing Opportunities Introduction slides for the webinar describing bioenergy and sustainability. sustainabilitybiofuelswebina...

  15. Sustainability for the Global Biofuels Industry: Minimizing Risks...

    Energy Savers [EERE]

    Sustainability for the Global Biofuels Industry: Minimizing Risks and Maximizing Opportunities Webinar Transcript Webinar transcript. sustainabilityglobalbiofuelswebinar.doc ...

  16. A Regulator's Perspective on Interpretation of Performance and Risk

    Office of Environmental Management (EM)

    Assessment Results | Department of Energy Interpretation of Performance and Risk Assessment Results A Regulator's Perspective on Interpretation of Performance and Risk Assessment Results Presentation from the 2015 Annual Performance and Risk Assessment (P&RA) Community of Practice (CoP) Technical Exchange Meeting held in Richland, Washington on December 15-16, 2015. A Regulator's Perspective on Interpretation of Performance and Risk Assessment Results (2.19 MB) More Documents &

  17. Managing the Risks of Climate Change and Terrorism

    SciTech Connect (OSTI)

    Rosa, Eugene; Dietz, Tom; Moss, Richard H.; Atran, Scott; Moser, Susanne

    2012-04-07

    Society has difficult decisions to make about how best to allocate its resources to ensure future sustainability. Risk assessment can be a valuable tool: it has long been used to support decisions to address environmental problems. But in a time when the risks to sustainability range from climate change to terrorism, applying risk assessment to sustainability will require careful rethinking. For new threats, we will need a new approach to risk assessment.

  18. TWRS safety and technical integration risk management plan

    SciTech Connect (OSTI)

    Fordham, R.A.

    1996-03-12

    The objectives of the Tank Waste Remediation System (TWRS) Safety and Technical Integration (STI) programmatic risk management program are to assess, analyze, and handle risks associated with TWRS STI responsibilities and to communicate information about the actions being taken and the results to enable decision making. The objective of this TWRS STI Risk Management Plan is to communicate a consistent approach to risk management that will be used by the organization.

  19. A comparison of risk assessment techniques from qualitative to...

    Office of Scientific and Technical Information (OSTI)

    Country of Publication: United States Language: English Subject: 99 MATHEMATICS, COMPUTERS, INFORMATION SCIENCE, MANAGEMENT, LAW, MISCELLANEOUS; RISK ASSESSMENT; STATISTICS; ...

  20. Phase 1 data summary report for the Clinch River Remedial Investigation: Health risk and ecological risk screening assessment

    SciTech Connect (OSTI)

    Cook, R.B.; Adams, S.M.; Beauchamp, J.J.; Bevelhimer, M.S.; Blaylock, B.G.; Brandt, C.C.; Ford, C.J.; Frank, M.L.; Gentry, M.J.; Holladay, S.K.; Hook, L.A.; Levine, D.A.; Longman, R.C.; McGinn, C.W.; Skiles, J.L.; Suter, G.W.; Williams, L.F.

    1992-12-01

    The Clinch River Remedial Investigation (CRRI) is designed to address the transport, fate, and distribution of waterborne contaminants released from the US Department of Energy's (DOE's) Oak Ridge Reservation (ORR) and to assess potential risks to human health and the environment associated with these contaminants. The contaminants released since the early 1940s include a variety of radionuclides, metals, and organic compounds. The purpose of this report is to summarize the results of Phase 1 of the CRRI. Phase 1 was designed to (1) obtain high-quality data to confirm existing historical data for contaminant levels in fish, sediment, and water from the CR/WBR; (2) determine the in the range of contaminant concentrations present river-reservoir system; (3) identify specific contaminants of concern; and (4) establish the reference (background) concentrations for those contaminants.

  1. New risk metrics and mathematical tools for risk analysis: Current and future challenges

    SciTech Connect (OSTI)

    Skandamis, Panagiotis N. Andritsos, Nikolaos Psomas, Antonios Paramythiotis, Spyridon

    2015-01-22

    The current status of the food safety supply world wide, has led Food and Agriculture Organization (FAO) and World Health Organization (WHO) to establishing Risk Analysis as the single framework for building food safety control programs. A series of guidelines and reports that detail out the various steps in Risk Analysis, namely Risk Management, Risk Assessment and Risk Communication is available. The Risk Analysis approach enables integration between operational food management systems, such as Hazard Analysis Critical Control Points, public health and governmental decisions. To do that, a series of new Risk Metrics has been established as follows: i) the Appropriate Level of Protection (ALOP), which indicates the maximum numbers of illnesses in a population per annum, defined by quantitative risk assessments, and used to establish; ii) Food Safety Objective (FSO), which sets the maximum frequency and/or concentration of a hazard in a food at the time of consumption that provides or contributes to the ALOP. Given that ALOP is rather a metric of the public health tolerable burden (it addresses the total ‘failure’ that may be handled at a national level), it is difficult to be interpreted into control measures applied at the manufacturing level. Thus, a series of specific objectives and criteria for performance of individual processes and products have been established, all of them assisting in the achievement of FSO and hence, ALOP. In order to achieve FSO, tools quantifying the effect of processes and intrinsic properties of foods on survival and growth of pathogens are essential. In this context, predictive microbiology and risk assessment have offered an important assistance to Food Safety Management. Predictive modelling is the basis of exposure assessment and the development of stochastic and kinetic models, which are also available in the form of Web-based applications, e.g., COMBASE and Microbial Responses Viewer), or introduced into user

  2. A Resource Handbook on DOE Transportation Risk Assessment (DOE, 2002)

    Broader source: Energy.gov [DOE]

    This resource handbook was compiled for the DOE's Transportation Risk Assessment Working Group. This document includes the first of a planned series of discussion papers on topical aspects of transportation risk problems. These discussion papers are intended to provide practical advice to program managers and technical personnel responsible for preparing NEPA documents and other transportation risk assessments.

  3. Innovative Computational Tools for Reducing Exploration Risk Through

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Integration of Water-Rock Interactions and Magnetotelluric Surveys | Department of Energy Computational Tools for Reducing Exploration Risk Through Integration of Water-Rock Interactions and Magnetotelluric Surveys Innovative Computational Tools for Reducing Exploration Risk Through Integration of Water-Rock Interactions and Magnetotelluric Surveys Innovative Computational Tools for Reducing Exploration Risk Through Integration of Water-Rock Interactions and Magnetotelluric Surveys

  4. Sustainability for the Global Biofuels Industry Minimizing Risks and

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Maximizing Opportunities | Department of Energy Industry Minimizing Risks and Maximizing Opportunities Sustainability for the Global Biofuels Industry Minimizing Risks and Maximizing Opportunities Conservation International presentation for the May 17, 2011 webinar. conservation_international_presentation.pdf (4.85 MB) More Documents & Publications Sustainability for the Global Biofuels Industry: Minimizing Risks and Maximizing Opportunities Webinar Transcript Sustainability for the

  5. Tank waste remediation system tank waste retrieval risk management plan

    SciTech Connect (OSTI)

    Klimper, S.C.

    1997-11-07

    This Risk Management Plan defines the approach to be taken to manage programmatic risks in the TWRS Tank Waste Retrieval program. It provides specific instructions applicable to TWR, and is used to supplement the guidance given by the TWRS Risk Management procedure.

  6. The building codes and the forgotten basics of risk management

    SciTech Connect (OSTI)

    Norte, M.

    1995-12-01

    Building codes specifically developed to identify and manage chronic, endemic, facilities, risks, and the information and monitoring resources that must support them, are fundamental elements of a broadly based and comprehensive system of conventional risk management and compliance processes. This presentation discusses the proper role of building codes in atruly mature risk management and regulatory compliance strategy.

  7. Risks of LNG and LPG. [Review

    SciTech Connect (OSTI)

    Fay, J.A.

    1980-01-01

    Since the use of liquefied natural gas (LNG) and liquefied petroleum gases (LPG) as fuels is likely to increase and will certainly persist for some time to come, assessment of the safety of LNG/LPG systems will continue to draw attention and is quite likely to force continuing review of operating and design standards for LNG/LPG facilities. Scientific investigations to date appear to have identified the major hazards. Except for the dispersive behavior of vapor clouds - a not-insignificant factor in risk evaluation - the consequences of spills are well circumscribed by current analyses. The physically significant effects accompanying nonexplosive combustion of spilled material are fairly well documented; yet, potentially substantial uncertainties remain. Catastrophic spills of 10/sup 4/-10/sup 5/ m/sup 3/ on land or water are possible, given the current size of storage vessels. Almost all experimental spills have used less than 10 m/sup 3/ of liquid. There is thus some uncertainty regarding the accuracy and validity of extrapolation of current empirical information and physical models to spills of catastrophic size. The less-likely but still-possible explosive or fireball combustion modes are not well understood in respect to their inception. The troubling experience with such violent combustion of similar combustible vapors suggests that this possibility will need further definition. Extant LNG and LPG risk analyses illustrate the difficulties of substantiating the numerous event probabilities and the determination of all event sequences that can lead to hazardous consequences. Their disparate results show that significant improvements are needed. Most importantly, a detailed critique of past efforts and a determination of an exhaustive set of criteria for evaluating the adequacy of a risk analysis should precede any further attempts to improve on existing studies. 44 references, 1 table.

  8. Designs for Risk Evaluation and Management

    Energy Science and Technology Software Center (OSTI)

    2015-12-01

    The Designs for Risk Evaluation and Management (DREAM) tool was developed as part of the effort to quantify the risk of geologic storage of carbon dioxide (CO2) under the U.S. Department of Energy’s National Risk Assessment Partnership (NRAP). DREAM is an optimization tool created to identify optimal monitoring schemes that minimize the time to first detection of CO2 leakage from a subsurface storage formation. DREAM acts as a post-processer on user-provided output from subsurface leakagemore » simulations. While DREAM was developed for CO2 leakage scenarios, it is applicable to any subsurface leakage simulation of the same output format. The DREAM tool is comprised of three main components: (1) a Java wizard used to configure and execute the simulations, (2) a visualization tool to view the domain space and optimization results, and (3) a plotting tool used to analyze the results. A secondary Java application is provided to aid users in converting common American Standard Code for Information Interchange (ASCII) output data to the standard DREAM hierarchical data format (HDF5). DREAM employs a simulated annealing approach that searches the solution space by iteratively mutating potential monitoring schemes built of various configurations of monitoring locations and leak detection parameters. This approach has proven to be orders of magnitude faster than an exhaustive search of the entire solution space. The user’s manual illustrates the program graphical user interface (GUI), describes the tool inputs, and includes an example application.« less

  9. NREL: Speeches - Nation's Energy Future at Risk

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Energy Future at Risk, National Lab Director Says For more information contact: George Douglas, 303-275-4096 e:mail: George Douglas Washington, D.C., July 27, 1999 — America must invest in its energy future now, Richard Truly, director of the U.S. Department of Energy's National Renewable Energy Laboratory said today. Otherwise, he said, the nation could face supply shortages and fall behind foreign competitors. Truly, speaking at the National Press Club's Newsmakers program, said that U.S.

  10. Production Risk Evaluation Program (PREP) - summary

    SciTech Connect (OSTI)

    Kjeldgaard, E.A.; Saloio, J.H.; Vannoni, M.G.

    1997-03-01

    Nuclear weapons have been produced in the US since the early 1950s by a network of contractor-operated Department of Energy (DOE) facilities collectively known as the Nuclear Weapon Complex (NWC). Recognizing that the failure of an essential process might stop weapon production for a substantial period of time, the DOE Albuquerque Operations office initiated the Production Risk Evaluation Program (PREP) at Sandia National Laboratories (SNL) to assess quantitatively the potential for serious disruptions in the NWC weapon production process. PREP was conducted from 1984-89. This document is an unclassified summary of the effort.

  11. Session: Pre-development project risk assessment

    SciTech Connect (OSTI)

    Curry, Richard; Linehan, Andy

    2004-09-01

    This second session at the Wind Energy and Birds/Bats workshop consisted of two presentations followed by a discussion/question and answer period. The focus of the presentations was on the practices and methodologies used in the wind energy industry for assessing risk to birds and bats at candidate project sites. Presenters offered examples of pre-development siting evaluation requirements set by certain states. Presentation one was titled ''Practices and Methodologies and Initial Screening Tools'' by Richard Curry of Curry and Kerlinger, LLC. Presentation two was titled ''State of the Industry in the Pacific Northwest'' by Andy Linehan, CH2MHILL.

  12. Measure Guideline: High Efficiency Natural Gas Furnaces

    SciTech Connect (OSTI)

    Brand, L.; Rose, W.

    2012-10-01

    This Measure Guideline covers installation of high-efficiency gas furnaces. Topics covered include when to install a high-efficiency gas furnace as a retrofit measure, how to identify and address risks, and the steps to be used in the selection and installation process. The guideline is written for Building America practitioners and HVAC contractors and installers. It includes a compilation of information provided by manufacturers, researchers, and the Department of Energy as well as recent research results from the Partnership for Advanced Residential Retrofit (PARR) Building America team.

  13. Measure Guideline. High Efficiency Natural Gas Furnaces

    SciTech Connect (OSTI)

    Brand, L.; Rose, W.

    2012-10-01

    This measure guideline covers installation of high-efficiency gas furnaces, including: when to install a high-efficiency gas furnace as a retrofit measure; how to identify and address risks; and the steps to be used in the selection and installation process. The guideline is written for Building America practitioners and HVAC contractors and installers. It includes a compilation of information provided by manufacturers, researchers, and the Department of Energy as well as recent research results from the Partnership for Advanced Residential Retrofit (PARR) Building America team.

  14. A risk assessment software tool for evaluating potential risks to human health and the environment

    SciTech Connect (OSTI)

    Drendel, G.; Allen, B.; Gentry, R.; Shipp, A.; Van Landingham, C.

    1994-12-31

    The Ecology and National Environmental Policy Act Division (END), is providing a sitewide evaluation of alternative strategies for the final disposition of the Rocky Flats Plant material inventory. This analysis is known as the Systems Engineering Analysis (SEA) for the Rocky Flats Plant. The primary intent of the SEA is to support the Rocky Flats Plant decision-making. As part of the SEA project, a risk assessment software tool has been developed which will assist in the analysis by providing an evaluation of potential risks to human health and the environment for the purpose of augmenting future decisions at the site.

  15. Using Failure Mode Effects and Criticality Analysis for High-Risk Processes at Three Community Hospitals

    SciTech Connect (OSTI)

    Coles, Garill A.; Fuller, Becky; Nordquist, Kathleen; Kongslie, Anita

    2005-03-01

    The staff at three Washington State hospitals and Battelle Pacific Northwest Division have been collaborating to apply Failure Mode Effects and Criticality Analysis (FMECA) to assess several hospital processes. The staff from Kadlec Medical Center (KMC), located in Richland, Washington; Kennewick General Hospital (KGH), located in Kennewick, Washington; and Lourdes Medical Center (LMC), located in Pasco, Washington, along with staff from Battelle, which is located in Richland, Washington have been working together successfully for two and a half years. Tri-Cities Shared Services, a local organization which implements shared hospital services, has provided the forum for joint activity. This effort was initiated in response to the new JCAHO patient safety standards implemented in July 2001, and the hospitals’ desire to be more proactive in improving patient safety. As a result of performing FMECAs the weaknesses of six medical processes have been characterized and corresponding system improvements implemented. Based on this collective experience, insights about the benefits of applying FMECAs to healthcare processes have been identified.

  16. Towards improved characterization of high-risk releases using heterogeneous indoor sensor systems

    SciTech Connect (OSTI)

    Sreedharan, Priya; Sohn, Michael D.; Nazaroff, William W.; J. Gadgil, Ashok

    2010-06-30

    The sudden release of toxic contaminants that reach indoor spaces can be hazardous to building occupants. For an acutely toxic contaminant, the speed of the emergency response strongly influences the consequences to occupants. The design of a real time sensor system is made challenging both by the urgency and complex nature of the event, and by the imperfect sensors and models available to describe it. In this research, we use Bayesian modeling to combine information from multiple types of sensors to improve the characterization of a release. We discuss conceptual and algorithmic considerations for selecting and fusing information from disparate sensors. To explore system performance, we use both real tracer gas data from experiments in a three story building, along with synthetic data, including information from door position sensors. The added information from door position sensors is found to be useful for many scenarios, but not always. We discuss the physical conditions and design factors that affect these results, such as the influence of the door positions on contaminant transport. We highlight potential benefits of multisensor data fusion, challenges in realizing those benefits, and opportunities for further improvement.

  17. Reducing Risk for the Next Generation Nuclear Plant

    SciTech Connect (OSTI)

    John M. Beck II; Harold J. Heydt; Emmanuel O. Opare; Kyle B. Oswald

    2010-07-01

    The Next Generation Nuclear Plant (NGNP) Project, managed by the Idaho National Laboratory (INL), is directed by the Energy Policy Act of 2005, to research, develop, design, construct, and operate a prototype forth generation nuclear reactor to meet the needs of the 21st Century. As with all large projects developing and deploying new technologies, the NGNP has numerous risks that need to be identified, tracked, mitigated, and reduced in order for successful project completion. A Risk Management Plan (RMP) was created to outline the process the INL is using to manage the risks and reduction strategies for the NGNP Project. Integral to the RMP is the development and use of a Risk Management System (RMS). The RMS is a tool that supports management and monitoring of the project risks. The RMS does not only contain a risk register, but other functionality that allows decision makers, engineering staff, and technology researchers to review and monitor the risks as the project matures.

  18. Risk assessment of landfill disposal sites - State of the art

    SciTech Connect (OSTI)

    Butt, Talib E. Lockley, Elaine; Oduyemi, Kehinde O.K.

    2008-07-01

    A risk assessment process can assist in drawing a cost-effective compromise between economic and environmental costs, thereby assuring that the philosophy of 'sustainable development' is adhered to. Nowadays risk analysis is in wide use to effectively manage environmental issues. Risk assessment is also applied to other subjects including health and safety, food, finance, ecology and epidemiology. The literature review of environmental risk assessments in general and risk assessment approaches particularly regarding landfill disposal sites undertaken by the authors, reveals that an integrated risk assessment methodology for landfill gas, leachate or degraded waste does not exist. A range of knowledge gaps is discovered in the literature reviewed to date. From the perspective of landfill leachate, this paper identifies the extent to which various risk analysis aspects are absent in the existing approaches.

  19. Draugen HSE-case - occupational health risk management

    SciTech Connect (OSTI)

    Glas, J.J.P.; Kjaer, E.

    1996-12-31

    The Draugen HSE-Case serves as a risk management tool. Originally, risk management included only major safety hazards to personnel, environment and assets. Work Environment risks such as ergonomics, psycho-social factors and exposure to chemicals and noise, was not given the same attention. The Draugen HSE-Case addresses this weakness and extends all work environment risks. In order to promote line responsibility and commitment, relevant personnel is involved in the Case development. {open_quotes}THESIS{degrees}, a software application, is used to systematize input and to generate reports. The Draugen HSE-case encompasses: HSE risk analyses related to specific activities; Control of risk related to work environment; Established tolerability criteria; Risk reducing measures; Emergency contingency measures; and Requirements for Competence and Follow-up. The development of Draugen HSE-Case is a continuous process. It will serve to minimize the potential of occupational illnesses, raise general awareness, and make occupational health management more cost-effective.

  20. Modeling radiation pneumonitis risk with clinical, dosimetric, and spatial parameters

    SciTech Connect (OSTI)

    Hope, Andrew J.; Lindsay, Patricia E.; El Naqa, Issam; Alaly, James R.; Vicic, Milos; Bradley, Jeffrey D.; Deasy, Joseph O. . E-mail: jdeasy@radonc.wustl.edu

    2006-05-01

    Purpose: To determine the clinical, dosimetric, and spatial parameters that correlate with radiation pneumonitis. Methods and Materials: Patients treated with high-dose radiation for non-small-cell lung cancer with three-dimensional treatment planning were reviewed for clinical information and radiation pneumonitis (Rp) events. Three-dimensional treatment plans for 219 eligible patients were recovered. Treatment plan information, including parameters defining tumor position and dose-volume parameters, was extracted from non-heterogeneity-corrected dose distributions. Correlation to RP events was assessed by Spearman's rank correlation coefficient (R). Mathematical models were generated that correlate with RP. Results: Of 219 patients, 52 required treatment for RP (median interval, 142 days). Tumor location was the most highly correlated parameter on univariate analysis (R = 0.24). Multiple dose-volume parameters were correlated with RP. Models most frequently selected by bootstrap resampling included tumor position, maximum dose, and D{sub 35} (minimum dose to the 35% volume receiving the highest doses) (R 0.28). The most frequently selected two- or three-parameter models outperformed commonly used metrics, including V{sub 2} (fractional volume of normal lung receiving >20 Gy) and mean lung dose (R = 0.18). Conclusions: Inferior tumor position was highly correlated with pneumonitis events within our population. Models that account for inferior tumor position and dosimetric information, including both high- and low-dose regions (D{sub 35}, International Commission on Radiation Units and Measurements maximum dose), risk-stratify patients more accurately than any single dosimetric or clinical parameter.

  1. TECHNICAL RISK RATING OF DOE ENVIRONMENTAL PROJECTS - 9153

    SciTech Connect (OSTI)

    Cercy, M; Ronald Fayfich, R; Steven P Schneider, S

    2008-12-12

    The U.S. Department of Energy's Office of Environmental Management (DOE-EM) was established to achieve the safe and compliant disposition of legacy wastes and facilities from defense nuclear applications. The scope of work is diverse, with projects ranging from single acquisitions to collections of projects and operations that span several decades and costs from hundreds of millions to billions US$. The need to be able to manage and understand the technical risks from the project to senior management level has been recognized as an enabler to successfully completing the mission. In 2008, DOE-EM developed the Technical Risk Rating as a new method to assist in managing technical risk based on specific criteria. The Technical Risk Rating, and the criteria used to determine the rating, provides a mechanism to foster open, meaningful communication between the Federal Project Directors and DOE-EM management concerning project technical risks. Four indicators (technical maturity, risk urgency, handling difficulty and resolution path) are used to focus attention on the issues and key aspects related to the risks. Pressing risk issues are brought to the forefront, keeping DOE-EM management informed and engaged such that they fully understand risk impact. Use of the Technical Risk Rating and criteria during reviews provides the Federal Project Directors the opportunity to openly discuss the most significant risks and assists in the management of technical risks across the portfolio of DOE-EM projects. Technical Risk Ratings can be applied to all projects in government and private industry. This paper will present the methodology and criteria for Technical Risk Ratings, and provide specific examples from DOE-EM projects.

  2. Technical Risk Rating of DOE Environmental Projects - 9153

    SciTech Connect (OSTI)

    Cercy, Michael; Fayfich, Ronald; Schneider, Steven

    2009-02-11

    The U.S. Department of Energy's Office of Environmental Management (DOE-EM) was established to achieve the safe and compliant disposition of legacy wastes and facilities from defense nuclear applications. The scope of work is diverse, with projects ranging from single acquisitions to collections of projects and operations that span several decades and costs from hundreds of millions to billions US$. The need to be able to manage and understand the technical risks from the project to senior management level has been recognized as an enabler to successfully completing the mission. In 2008, DOE-EM developed the Technical Risk Rating as a new method to assist in managing technical risk based on specific criteria. The Technical Risk Rating, and the criteria used to determine the rating, provides a mechanism to foster open, meaningful communication between the Federal Project Directors and DOE-EM management concerning project technical risks. Four indicators (technical maturity, risk urgency, handling difficulty and resolution path) are used to focus attention on the issues and key aspects related to the risks. Pressing risk issues are brought to the forefront, keeping DOE-EM management informed and engaged such that they fully understand risk impact. Use of the Technical Risk Rating and criteria during reviews provides the Federal Project Directors the opportunity to openly discuss the most significant risks and assists in the management of technical risks across the portfolio of DOE-EM projects. Technical Risk Ratings can be applied to all projects in government and private industry. This paper will present the methodology and criteria for Technical Risk Ratings, and provide specific examples from DOE-EM projects.

  3. Risk, media, and stigma at Rocky Flats

    SciTech Connect (OSTI)

    Flynn, J.; Peters, E.; Mertz, C.K.; Slovic, P.

    1998-12-01

    Public responses to nuclear technologies are often strongly negative. Events, such as accidents or evidence of unsafe conditions at nuclear facilities, receive extensive and dramatic coverage by the news media. These news stories affect public perceptions of nuclear risks and the geographic areas near nuclear facilities. One result of these perceptions, avoidance behavior, is a form of technological stigma that leads to losses in property values near nuclear facilities. The social amplification of risk is a conceptual framework that attempts to explain how stigma is created through media transmission of information about hazardous places and public perceptions and decisions. This paper examines stigma associated with the US Department of energy`s Rocky Flats facility, a major production plant in the nation`s nuclear weapons complex, located near Denver, Colorado. This study, based upon newspaper analyses and a survey of Denver area residents, finds that the social amplification theory provides a reasonable framework for understanding the events and public responses that took place in regard to Rocky Flats during a 6-year period, beginning with an FBI raid of the facility in 1989.

  4. Hydrogen quantitative risk assessment workshop proceedings.

    SciTech Connect (OSTI)

    Groth, Katrina M.; Harris, Aaron P.

    2013-09-01

    The Quantitative Risk Assessment (QRA) Toolkit Introduction Workshop was held at Energetics on June 11-12. The workshop was co-hosted by Sandia National Laboratories (Sandia) and HySafe, the International Association for Hydrogen Safety. The objective of the workshop was twofold: (1) Present a hydrogen-specific methodology and toolkit (currently under development) for conducting QRA to support the development of codes and standards and safety assessments of hydrogen-fueled vehicles and fueling stations, and (2) Obtain feedback on the needs of early-stage users (hydrogen as well as potential leveraging for Compressed Natural Gas [CNG], and Liquefied Natural Gas [LNG]) and set priorities for %E2%80%9CVersion 1%E2%80%9D of the toolkit in the context of the commercial evolution of hydrogen fuel cell electric vehicles (FCEV). The workshop consisted of an introduction and three technical sessions: Risk Informed Development and Approach; CNG/LNG Applications; and Introduction of a Hydrogen Specific QRA Toolkit.

  5. Quantifying Unnecessary Normal Tissue Complication Risks due to Suboptimal Planning: A Secondary Study of RTOG 0126

    SciTech Connect (OSTI)

    Moore, Kevin L.; Schmidt, Rachel; Moiseenko, Vitali; Olsen, Lindsey A.; Tan, Jun; Xiao, Ying; Galvin, James; Pugh, Stephanie; Seider, Michael J.; Dicker, Adam P.; Bosch, Walter; Michalski, Jeff; Mutic, Sasa

    2015-06-01

    Purpose: The purpose of this study was to quantify the frequency and clinical severity of quality deficiencies in intensity modulated radiation therapy (IMRT) planning in the Radiation Therapy Oncology Group 0126 protocol. Methods and Materials: A total of 219 IMRT patients from the high-dose arm (79.2 Gy) of RTOG 0126 were analyzed. To quantify plan quality, we used established knowledge-based methods for patient-specific dose-volume histogram (DVH) prediction of organs at risk and a Lyman-Kutcher-Burman (LKB) model for grade ≥2 rectal complications to convert DVHs into normal tissue complication probabilities (NTCPs). The LKB model was validated by fitting dose-response parameters relative to observed toxicities. The 90th percentile (22 of 219) of plans with the lowest excess risk (difference between clinical and model-predicted NTCP) were used to create a model for the presumed best practices in the protocol (pDVH{sub 0126,top10%}). Applying the resultant model to the entire sample enabled comparisons between DVHs that patients could have received to DVHs they actually received. Excess risk quantified the clinical impact of suboptimal planning. Accuracy of pDVH predictions was validated by replanning 30 of 219 patients (13.7%), including equal numbers of presumed “high-quality,” “low-quality,” and randomly sampled plans. NTCP-predicted toxicities were compared to adverse events on protocol. Results: Existing models showed that bladder-sparing variations were less prevalent than rectum quality variations and that increased rectal sparing was not correlated with target metrics (dose received by 98% and 2% of the PTV, respectively). Observed toxicities were consistent with current LKB parameters. Converting DVH and pDVH{sub 0126,top10%} to rectal NTCPs, we observed 94 of 219 patients (42.9%) with ≥5% excess risk, 20 of 219 patients (9.1%) with ≥10% excess risk, and 2 of 219 patients (0.9%) with ≥15% excess risk. Replanning demonstrated the

  6. Radiological risk assessment of environmental radon

    SciTech Connect (OSTI)

    Khalid, Norafatin; Majid, Amran Ab; Yahaya, Redzuwan; Yasir, Muhammad Samudi

    2013-11-27

    Measurements of radon gas ({sup 222}Rn) in the environmental are important to assess indoor air quality and to study the potential risk to human health. Generally known that exposure to radon is considered the second leading cause of lung cancer after smoking. The environmental radon concentration depends on the {sup 226}Ra concentration, indoor atmosphere, cracking on rocks and building materials. This study was carried out to determine the indoor radon concentration from selected samples of tin tailings (amang) and building materials in an airtight sealed homemade radon chamber. The radiological risk assessment for radon gas was also calculated based on the annual exposure dose, effective dose equivalent, radon exhalation rates and fatal cancer risk. The continuous radon monitor Sun Nuclear model 1029 was used to measure the radon concentration emanates from selected samples for 96 hours. Five types of tin tailings collected from Kampar, Perak and four samples of building materials commonly used in Malaysia dwellings or building constructions were analysed for radon concentration. The indoor radon concentration determined in ilmenite, monazite, struverite, xenotime and zircon samples varies from 219.6 76.8 Bq m{sup ?3} to 571.1 251.4 Bq m{sup ?3}, 101.0 41.0 Bq m{sup ?3} to 245.3 100.2 Bq m{sup ?3}, 53.1 7.5 Bq m{sup ?3} to 181.8 9.7 Bq m{sup ?3}, 256.1 59.3 Bq m{sup ?3} to 652.2 222.2 Bq m{sup ?3} and 164.5 75.9 Bq m{sup ?3} to 653.3 240.0 Bq m{sup ?3}, respectively. Whereas, in the building materials, the radon concentration from cement brick, red-clay brick, gravel aggregate and cement showed 396.3 194.3 Bq m{sup ?3}, 192.1 75.4 Bq m{sup ?3}, 176.1 85.9 Bq m{sup ?3} and 28.4 5.7 Bq m{sup ?3}, respectively. The radon concentration in tin tailings and building materials were found to be much higher in xenotime and cement brick samples than others. All samples in tin tailings were exceeded the action level for radon gas of 148 Bq m

  7. Framework for Risk Analysis in Multimedia Environmental Systems: Modeling Individual Steps of a Risk Assessment Process

    SciTech Connect (OSTI)

    Shah, Anuj; Castleton, Karl J.; Hoopes, Bonnie L.

    2004-06-01

    The study of the release and effects of chemicals in the environment and their associated risks to humans is central to public and private decision making. FRAMES 1.X, Framework for Risk Analysis in Multimedia Environmental Systems, is a systems modeling software platform, developed by PNNL, Pacific Northwest National Laboratory, that helps scientists study the release and effects of chemicals on a source to outcome basis, create environmental models for similar risk assessment and management problems. The unique aspect of FRAMES is to dynamically introduce software modules representing individual components of a risk assessment (e.g., source release of contaminants, fate and transport in various environmental media, exposure, etc.) within a software framework, manipulate their attributes and run simulations to obtain results. This paper outlines the fundamental constituents of FRAMES 2.X, an enhanced version of FRAMES 1.X, that greatly improve the ability of the module developers to “plug” their self-developed software modules into the system. The basic design, the underlying principles and a discussion of the guidelines for module developers are presented.

  8. Exposure to residential electric and magnetic fields and risk of childhood leukemia

    SciTech Connect (OSTI)

    Peters, J.M.; Thomas, D.C.; Bowman, J.D.; Sobel, E.; London, S.J.; Cheng, T.C. )

    1991-11-01

    This study was conducted on 232 cases of childhood leukemia occurring in children age 10 and under between 1980 and 1987 in Los Angeles County. Two hundred thirty-two controls were selected from the same geographic area and were matched on sex, age and race. The parents of the 464 subjects were interviewed by telephone to elicit information on medical histories of the parents and child, residential histories of the subjects, occupational histories of both parents, environmental chemical histories, personal histories including drug use and smoking habits, and time and space occupancy of subjects, including exposures to electrical appliances. An extensive assessment of exposure to electric and magnetic fields was made by determining wiring configurations of most subjects (90%), by measuring electric and magnetic fields in various areas of the inside and outside of the home, and by measuring magnetic fields for 24 to 72 hours in the child's sleeping area (66%). We conclude that our data offer no support for a relationship between measured electric field exposure and leukemia risk, little support for the relationship between measured magnetic field exposure and leukemia risk, considerable support for a relationship between wiring configuration and leukemia risk, and considerable support for a relationship between children's electrical appliance use and leukemia risk. The reason(s) why wiring configuration correlates with leukemia risk better than measured exposure are not clear. It is also not clear whether short-term, very high exposure of children to magnetic (or electric) fields from electric appliances are responsible for the observed risk or whether associated exposures or recall biases are responsible. These latter two issues deserve continued research. 41 refs., 31 tabs.

  9. Exposure to residential electric and magnetic fields and risk of childhood leukemia

    SciTech Connect (OSTI)

    Peters, J.M.; Thomas, D.C.; Bowman, J.D.; Sobel, E.; London, S.J.; Cheng, T.C.

    1991-11-01

    This study was conducted on 232 cases of childhood leukemia occurring in children age 10 and under between 1980 and 1987 in Los Angeles County. Two hundred thirty-two controls were selected from the same geographic area and were matched on sex, age and race. The parents of the 464 subjects were interviewed by telephone to elicit information on medical histories of the parents and child, residential histories of the subjects, occupational histories of both parents, environmental chemical histories, personal histories including drug use and smoking habits, and time and space occupancy of subjects, including exposures to electrical appliances. An extensive assessment of exposure to electric and magnetic fields was made by determining wiring configurations of most subjects (90%), by measuring electric and magnetic fields in various areas of the inside and outside of the home, and by measuring magnetic fields for 24 to 72 hours in the child`s sleeping area (66%). We conclude that our data offer no support for a relationship between measured electric field exposure and leukemia risk, little support for the relationship between measured magnetic field exposure and leukemia risk, considerable support for a relationship between wiring configuration and leukemia risk, and considerable support for a relationship between children`s electrical appliance use and leukemia risk. The reason(s) why wiring configuration correlates with leukemia risk better than measured exposure are not clear. It is also not clear whether short-term, very high exposure of children to magnetic (or electric) fields from electric appliances are responsible for the observed risk or whether associated exposures or recall biases are responsible. These latter two issues deserve continued research. 41 refs., 31 tabs.

  10. Strategy Guideline. Partnering for High Performance Homes

    SciTech Connect (OSTI)

    Prahl, Duncan

    2013-01-01

    High performance houses require a high degree of coordination and have significant interdependencies between various systems in order to perform properly, meet customer expectations, and minimize risks for the builder. Responsibility for the key performance attributes is shared across the project team and can be well coordinated through advanced partnering strategies. For high performance homes, traditional partnerships need to be matured to the next level and be expanded to all members of the project team including trades, suppliers, manufacturers, HERS raters, designers, architects, and building officials as appropriate. This guide is intended for use by all parties associated in the design and construction of high performance homes. It serves as a starting point and features initial tools and resources for teams to collaborate to continually improve the energy efficiency and durability of new houses.

  11. Environmental restoration risk-based prioritization work package planning and risk ranking methodology. Revision 2

    SciTech Connect (OSTI)

    Dail, J.L.; Nanstad, L.D.; White, R.K.

    1995-06-01

    This document presents the risk-based prioritization methodology developed to evaluate and rank Environmental Restoration (ER) work packages at the five US Department of Energy, Oak Ridge Field Office (DOE-ORO) sites [i.e., Oak Ridge K-25 Site (K-25), Portsmouth Gaseous Diffusion Plant (PORTS), Paducah Gaseous Diffusion Plant (PGDP), Oak Ridge National Laboratory (ORNL), and the Oak Ridge Y-12 Plant (Y-12)], the ER Off-site Program, and Central ER. This prioritization methodology was developed to support the increased rigor and formality of work planning in the overall conduct of operations within the DOE-ORO ER Program. Prioritization is conducted as an integral component of the fiscal ER funding cycle to establish program budget priorities. The purpose of the ER risk-based prioritization methodology is to provide ER management with the tools and processes needed to evaluate, compare, prioritize, and justify fiscal budget decisions for a diverse set of remedial action, decontamination and decommissioning, and waste management activities. The methodology provides the ER Program with a framework for (1) organizing information about identified DOE-ORO environmental problems, (2) generating qualitative assessments of the long- and short-term risks posed by DOE-ORO environmental problems, and (3) evaluating the benefits associated with candidate work packages designed to reduce those risks. Prioritization is conducted to rank ER work packages on the basis of the overall value (e.g., risk reduction, stakeholder confidence) each package provides to the ER Program. Application of the methodology yields individual work package ``scores`` and rankings that are used to develop fiscal budget requests. This document presents the technical basis for the decision support tools and process.

  12. Development of Improved Caprock Integrity and Risk Assessment Techniques

    SciTech Connect (OSTI)

    Bruno, Michael

    2014-09-30

    GeoMechanics Technologies has completed a geomechanical caprock integrity analysis and risk assessment study funded through the US Department of Energy. The project included: a detailed review of historical caprock integrity problems experienced in the natural gas storage industry; a theoretical description and documentation of caprock integrity issues; advanced coupled transport flow modelling and geomechanical simulation of three large-scale potential geologic sequestration sites to estimate geomechanical effects from CO₂ injection; development of a quantitative risk and decision analysis tool to assess caprock integrity risks; and, ultimately the development of recommendations and guidelines for caprock characterization and CO₂ injection operating practices. Historical data from gas storage operations and CO₂ sequestration projects suggest that leakage and containment incident risks are on the order of 10-1 to 10-2, which is higher risk than some previous studies have suggested for CO₂. Geomechanical analysis, as described herein, can be applied to quantify risks and to provide operating guidelines to reduce risks. The risk assessment tool developed for this project has been applied to five areas: The Wilmington Graben offshore Southern California, Kevin Dome in Montana, the Louden Field in Illinois, the Sleipner CO₂ sequestration operation in the North Sea, and the In Salah CO₂ sequestration operation in North Africa. Of these five, the Wilmington Graben area represents the highest relative risk while the Kevin Dome area represents the lowest relative risk.

  13. Continuing Developments in PV Risk Management: Strategies, Solutions, and Implications

    SciTech Connect (OSTI)

    Lowder, T.; Mendelsohn, M.; Speer, B.; Hill, R.

    2013-02-01

    As the PV industry matures, successful risk management practices will become more imperative to ensure investor confidence, control costs, and facilitate further growth. This report discusses several key aspects of risk management during the commercial- and utility-scale project life cycle, from identification of risks, to the process of mitigating and allocating those risks among project parties, to transferring those risks through insurance. The report also explores novel techniques in PV risk management, options to offload risks onto the capital markets, and innovative insurance policies (namely warranty policies) that address risks unique to the PV sector. One of the major justifications for robust risk management in the PV industry is the cost-reduction opportunities it affords. If the PV industry can demonstrate the capability to successfully manage its risks, thereby inspiring confidence in financiers, it may be able to obtain a lower cost of capital in future transactions. A lower cost of capital translates to a lower cost of energy, which will in turn enhance PV?s competitiveness at a time when it will have to rely less on subsidies to support its market penetration.

  14. APPLICATION OF RISK MANAGEMENT PRACTICES TO NNSA TRITIUM READINESS SUBPROGRAM

    SciTech Connect (OSTI)

    Shete, S; Srini Venkatesh, S

    2007-01-31

    The National Nuclear Security Administration (NNSA), Office of Stockpile Technology (NNSA/NA-123) chartered a risk assessment of the Tritium Readiness (TR) Subprogram to identify risks and to develop handling strategies with specific action items that could be scheduled and tracked to completion in order to minimize program failures. This assessment was performed by a team of subject matter experts (SMEs) comprised of representatives from various organizations participating in the TR Subprogram. The process was coordinated by Savannah River Site, Systems Engineering (SRS/SE) with support from Subprogram Team. The Risk Management Process steps performed during this risk assessment were: Planning, Identification, Grading, Handling, and Impact Determination. All of the information captured during the risk assessment was recorded in a database. The team provided estimates for the cost and schedule impacts of implementing the recommended handling strategies and facilitated the risk based cost contingency analysis. The application of the Risk Management Practices to the NNSA Tritium Readiness Subprogram resulted in: (1) The quarterly review and update of the Risk Management Database to include an evaluation of all existing risks and the identification/evaluation of any potential new risks. (2) The risk status and handling strategy action item tracking mechanism that has visibility and buy-in throughout the Tritium Readiness Subprogram to ensure that approved actions are completed as scheduled and that risk reduction is being achieved. (3) The generation of a risk-based cost contingency estimate that may be used by the Tritium Readiness Subprogram Manager in establishing future year program budgets.

  15. Assessment of the risk of transporting liquid chlorine by rail

    SciTech Connect (OSTI)

    Andrews, W.B.

    1980-03-01

    This report presents the risk of shipping liquid chlorine by rail. While chlorine is not an energy material, there are several benefits to studying chlorine transportation risks. First, chlorine, like energy materials, is widely used as a feedstock to industry. Second, it is the major purification agent in municipal water treatment systems and therefore, provides direct benefits to the public. Finally, other risk assessments have been completed for liquid chlorine shipments in the US and Europe, which provide a basis for comparison with this study. None of the previous PNL energy material risk assessments have had other studies for comparison. For these reasons, it was felt that a risk assessment of chlorine transportation by rail could provide information on chlorine risk levels, identify ways to reduce these risks and use previous studies on chlorine risks to assess the strengths and weaknesses of the PNL risk assessment methodology. The risk assessment methodology used in this study is summarized. The methodology is presented in the form of a risk assessment model which is constructed for ease of periodic updating of the data base so that the risk may be reevaluated as additional data become available. The report is sectioned to correspond to specific analysis steps identified in the model. The transport system and accident environment are described. The response of the transport system to accident environments is described. Release sequences are postulated and evaluated to determine both the likelihood and possible consequences of a release. Supportive data and analyses are given in the appendices. The risk assessment results are related to the year 1985 to allow a direct comparison with other reports in this series.

  16. System Analysis and Risk Assessment System.

    Energy Science and Technology Software Center (OSTI)

    2000-11-20

    Version 00 SARA4.16 is a program that allows the user to review the results of a Probabilistic Risk Assessment (PRA) and to perform limited sensitivity analysis on these results. This tool is intended to be used by a less technical oriented user and does not require the level of understanding of PRA concepts required by a full PRA analysis tool. With this program a user can review the information generated by a PRA analyst andmore » compare the results to those generated by making limited modifications to the data in the PRA. Also included in this program is the ability to graphically display the information stored in the database. This information includes event trees, fault trees, P&IDs and uncertainty distributions. SARA 4.16 is incorporated in the SAPHIRE 5.0 code package.« less

  17. Risk analysis of an LPG facility

    SciTech Connect (OSTI)

    Daley, H.F.; Chapman, P.D.L.

    1986-01-01

    This paper describes methods used to conduct a safety review of an existing LPG loading, processing, and storage facility. An engineering team conducted a Hazard and Operability study of the plant to identify potential problems. A Probabilistic Risk Assessment was also made on the facility where the probability and consequences of worst case accidents were estimated. Stone and Webster recently completed an analysis of an LPG terminal to determine if there were any engineering, design, or operating deficiencies which could jeopardize the operability of the facility or make operation hazardous. The facility includes a dock for off-loading refrigerated propane and butane, transfer piping from the dock to storage, a heating system, pressurized storage, dehydration, product transfer and loading.

  18. Augmenting Probabilistic Risk Assesment with Malevolent Initiators

    SciTech Connect (OSTI)

    Curtis Smith; David Schwieder

    2011-11-01

    As commonly practiced, the use of probabilistic risk assessment (PRA) in nuclear power plants only considers accident initiators such as natural hazards, equipment failures, and human error. Malevolent initiators are ignored in PRA, but are considered the domain of physical security, which uses vulnerability assessment based on an officially specified threat (design basis threat). This paper explores the implications of augmenting and extending existing PRA models by considering new and modified scenarios resulting from malevolent initiators. Teaming the augmented PRA models with conventional vulnerability assessments can cost-effectively enhance security of a nuclear power plant. This methodology is useful for operating plants, as well as in the design of new plants. For the methodology, we have proposed an approach that builds on and extends the practice of PRA for nuclear power plants for security-related issues. Rather than only considering 'random' failures, we demonstrated a framework that is able to represent and model malevolent initiating events and associated plant impacts.

  19. Performing Probabilistic Risk Assessment Through RAVEN

    SciTech Connect (OSTI)

    A. Alfonsi; C. Rabiti; D. Mandelli; J. Cogliati; R. Kinoshita

    2013-06-01

    The Reactor Analysis and Virtual control ENviroment (RAVEN) code is a software tool that acts as the control logic driver and post-processing engine for the newly developed Thermal-Hydraulic code RELAP-7. RAVEN is now a multi-purpose Probabilistic Risk Assessment (PRA) software framework that allows dispatching different functionalities: Derive and actuate the control logic required to simulate the plant control system and operator actions (guided procedures), allowing on-line monitoring/controlling in the Phase Space Perform both Monte-Carlo sampling of random distributed events and Dynamic Event Tree based analysis Facilitate the input/output handling through a Graphical User Interface (GUI) and a post-processing data mining module

  20. Hanford Site baseline risk assessment methodology. Revision 2

    SciTech Connect (OSTI)

    Not Available

    1993-03-01

    This methodology has been developed to prepare human health and environmental evaluations of risk as part of the Comprehensive Environmental Response, Compensation, and Liability Act remedial investigations (RIs) and the Resource Conservation and Recovery Act facility investigations (FIs) performed at the Hanford Site pursuant to the Hanford Federal Facility Agreement and Consent Order referred to as the Tri-Party Agreement. Development of the methodology has been undertaken so that Hanford Site risk assessments are consistent with current regulations and guidance, while providing direction on flexible, ambiguous, or undefined aspects of the guidance. The methodology identifies Site-specific risk assessment considerations and integrates them with approaches for evaluating human and environmental risk that can be factored into the risk assessment program supporting the Hanford Site cleanup mission. Consequently, the methodology will enhance the preparation and review of individual risk assessments at the Hanford Site.

  1. Cancer risk estimates from radiation therapy for heterotopic ossification prophylaxis after total hip arthroplasty

    SciTech Connect (OSTI)

    Mazonakis, Michalis; Berris, Theoharris; Damilakis, John; Lyraraki, Efrossyni

    2013-10-15

    Purpose: Heterotopic ossification (HO) is a frequent complication following total hip arthroplasty. This study was conducted to calculate the radiation dose to organs-at-risk and estimate the probability of cancer induction from radiotherapy for HO prophylaxis.Methods: Hip irradiation for HO with a 6 MV photon beam was simulated with the aid of a Monte Carlo model. A realistic humanoid phantom representing an average adult patient was implemented in Monte Carlo environment for dosimetric calculations. The average out-of-field radiation dose to stomach, liver, lung, prostate, bladder, thyroid, breast, uterus, and ovary was calculated. The organ-equivalent-dose to colon, that was partly included within the treatment field, was also determined. Organ dose calculations were carried out using three different field sizes. The dependence of organ doses upon the block insertion into primary beam for shielding colon and prosthesis was investigated. The lifetime attributable risk for cancer development was estimated using organ, age, and gender-specific risk coefficients.Results: For a typical target dose of 7 Gy, organ doses varied from 1.0 to 741.1 mGy by the field dimensions and organ location relative to the field edge. Blocked field irradiations resulted in a dose range of 1.4146.3 mGy. The most probable detriment from open field treatment of male patients was colon cancer with a high risk of 564.3 10{sup ?5} to 837.4 10{sup ?5} depending upon the organ dose magnitude and the patient's age. The corresponding colon cancer risk for female patients was (372.2541.0) 10{sup ?5}. The probability of bladder cancer development was more than 113.7 10{sup ?5} and 110.3 10{sup ?5} for males and females, respectively. The cancer risk range to other individual organs was reduced to (0.00368.5) 10{sup ?5}.Conclusions: The risk for cancer induction from radiation therapy for HO prophylaxis after total hip arthroplasty varies considerably by the treatment parameters

  2. Assessing Vulnerabilities, Risks, and Consequences of Damage to Critical Infrastructure

    SciTech Connect (OSTI)

    Suski, N; Wuest, C

    2011-02-04

    Since the publication of 'Critical Foundations: Protecting America's Infrastructure,' there has been a keen understanding of the complexity, interdependencies, and shared responsibility required to protect the nation's most critical assets that are essential to our way of life. The original 5 sectors defined in 1997 have grown to 18 Critical Infrastructures and Key Resources (CIKR), which are discussed in the 2009 National Infrastructure Protection Plan (NIPP) and its supporting sector-specific plans. The NIPP provides the structure for a national program dedicated to enhanced protection and resiliency of the nation's infrastructure. Lawrence Livermore National Laboratory (LLNL) provides in-depth, multi-disciplinary assessments of threat, vulnerability, and consequence across all 18 sectors at scales ranging from specific facilities to infrastructures spanning multi-state regions, such as the Oil and Natural Gas (ONG) sector. Like many of the CIKR sectors, the ONG sector is comprised of production, processing, distribution, and storage of highly valuable and potentially dangerous commodities. Furthermore, there are significant interdependencies with other sectors, including transportation, communication, finance, and government. Understanding the potentially devastating consequences and collateral damage resulting from a terrorist attack or natural event is an important element of LLNL's infrastructure security programs. Our work began in the energy sector in the late 1990s and quickly expanded other critical infrastructure sectors. We have performed over 600 physical assessments with a particular emphasis on those sectors that utilize, store, or ship potentially hazardous materials and for whom cyber security is important. The success of our approach is based on building awareness of vulnerabilities and risks and working directly with industry partners to collectively advance infrastructure protection. This approach consists of three phases: The Pre

  3. Non-Rhabdomyosarcoma Soft Tissue Sarcomas in Children: A Surveillance, Epidemiology, and End Results Analysis Validating COG Risk Stratifications

    SciTech Connect (OSTI)

    Waxweiler, Timothy V.; Rusthoven, Chad G.; Proper, Michelle S.; Cost, Carrye R.; Cost, Nicholas G.; Donaldson, Nathan; Garrington, Timothy; Greffe, Brian S.; Heare, Travis; Macy, Margaret E.; Liu, Arthur K.

    2015-06-01

    Purpose: Non-rhabdomyosarcoma soft tissue sarcomas (NRSTS) are a heterogeneous group of sarcomas that encompass over 35 histologies. With an incidence of ∼500 cases per year in the United States in those <20 years of age, NRSTS are rare and therefore difficult to study in pediatric populations. We used the large Surveillance, Epidemiology, and End Results (SEER) database to validate the prognostic ability of the Children's Oncology Group (COG) risk classification system and to define patient, tumor, and treatment characteristics. Methods and Materials: From SEER data from 1988 to 2007, we identified patients ≤18 years of age with NRSTS. Data for age, sex, year of diagnosis, race, registry, histology, grade, primary size, primary site, stage, radiation therapy, and survival outcomes were analyzed. Patients with nonmetastatic grossly resected low-grade tumors of any size or high-grade tumors ≤5 cm were considered low risk. Cases of nonmetastatic tumors that were high grade, >5 cm, or unresectable were considered intermediate risk. Patients with nodal or distant metastases were considered high risk. Results: A total of 941 patients met the review criteria. On univariate analysis, black race, malignant peripheral nerve sheath (MPNST) histology, tumors >5 cm, nonextremity primary, lymph node involvement, radiation therapy, and higher risk group were associated with significantly worse overall survival (OS) and cancer-specific survival (CSS). On multivariate analysis, MPNST histology, chemotherapy-resistant histology, and higher risk group were significantly poor prognostic factors for OS and CSS. Compared to low-risk patients, intermediate patients showed poorer OS (hazard ratio [HR]: 6.08, 95% confidence interval [CI]: 3.53-10.47, P<.001) and CSS (HR: 6.27; 95% CI: 3.44-11.43, P<.001), and high-risk patients had the worst OS (HR: 13.35, 95% CI: 8.18-21.76, P<.001) and CSS (HR: 14.65, 95% CI: 8.49-25.28, P<.001). Conclusions: The current COG risk group

  4. Assessing human health risk in the USDA forest service

    SciTech Connect (OSTI)

    Hamel, D.R.

    1990-12-31

    This paper identifies the kinds of risk assessments being done by or for the US Department of Agriculture (USDA) Forest Service. Summaries of data sources currently in use and the pesticide risk assessments completed by the agency or its contractors are discussed. An overview is provided of the agency`s standard operating procedures for the conduct of toxicological, ecological, environmental fate, and human health risk assessments.

  5. Energy Risk Predictions for the 2015 Hurricane Season (June 2015) |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy Risk Predictions for the 2015 Hurricane Season (June 2015) Energy Risk Predictions for the 2015 Hurricane Season (June 2015) This presentation is from a DOE-NASEO webinar held June 23, 2015, on forecasting energy infrastructure risk for the 2015 hurricane season. A variety of sources predict a below-normal season, with hurricane intensity lower than the 1981-2010 averages. The presentation includes an overview of hurricane season classification, historic impacts, and

  6. Extreme Temperature Energy Storage and Generation, for Cost and Risk

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Reduction in Geothermal Exploration | Department of Energy Extreme Temperature Energy Storage and Generation, for Cost and Risk Reduction in Geothermal Exploration Extreme Temperature Energy Storage and Generation, for Cost and Risk Reduction in Geothermal Exploration Extreme Temperature Energy Storage and Generation, for Cost and Risk Reduction in Geothermal Exploration presentation at the April 2013 peer review meeting held in Denver, Colorado. fast_cap_sys_peer2013.pdf (1.51 MB) More

  7. Preliminary Technical Risk Analysis for the Geothermal Technologies Program

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    | Department of Energy Technical Risk Analysis for the Geothermal Technologies Program Preliminary Technical Risk Analysis for the Geothermal Technologies Program This report explains the goals, methods, and results of a probabilistic analysis of technical risk for a portfolio of R&D projects in the DOE Geothermal Technologies Program. 41156.pdf (1.37 MB) More Documents & Publications U.S. DOE Geothermal Electricity Technology Evaluation Model (GETEM) Webinar Presentation Geothermal

  8. EM Risk and Cleanup Decision Making Presentation by Mark Gilbertson

    Office of Environmental Management (EM)

    RISK AND CLEANUP DECISION MAKING www.em.doe.gov 1 Mark Gilbertson Deputy Assistant Secretary for Site Restoration Office of Environmental Management May 31, 2012 Presented to Environmental Management Advisory Board Topics * How we got to where we are * Existing environment and health risk www.em.doe.gov 2 * Existing environment and health risk analysis to support decision-making * Considerations going forward The Past Five Years * FY2008 budget assumed ~$6 billion escalated for inflation over

  9. Cybersecurity Risk Management Process (RMP) Guideline - Final (May 2012) |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy Risk Management Process (RMP) Guideline - Final (May 2012) Cybersecurity Risk Management Process (RMP) Guideline - Final (May 2012) This electricity subsector cybersecurity Risk Management Process (RMP) guideline was developed by the Department of Energy, in collaboration with the National Institute of Standards and Technology (NIST) and the North American Electric Reliability Corporation (NERC). The RMP is written with the goal of enabling organizations- regardless of

  10. DOE Releases Electricity Subsector Cybersecurity Risk Management Process

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    (RMP) Guideline | Department of Energy Electricity Subsector Cybersecurity Risk Management Process (RMP) Guideline DOE Releases Electricity Subsector Cybersecurity Risk Management Process (RMP) Guideline May 23, 2012 - 9:30am Addthis News Media Contact: (202) 586-4940 For Immediate Release: May 23, 2012 Department of Energy Releases Electricity Subsector Cybersecurity Risk Management Process (RMP) Guideline Public-Private Sector Collaboration Produces Guidance to Help Electric Utilities

  11. Financial Risk, Policy & Controls | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Financial Risk, Policy & Controls Financial Risk, Policy & Controls The mission of the Office of Financial Risk, Policy and Controls (CF-50) is to contribute to the effective management of the financial resources of the Department of Energy by working in collaboration with our stakeholders, we will achieve the shared goal of continuous process improvement while complying with federal regulations. As stewards of taxpayers' money, we will be an objective source of internal controls

  12. Supply Chain Risk Management (SCRM) Awareness Toolkit | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy Supply Chain Risk Management (SCRM) Awareness Toolkit Supply Chain Risk Management (SCRM) Awareness Toolkit The Office of the Chief Information Officer (OCIO) Supply Chain Risk Management (SCRM) Resource Center developed the SCRM Awareness Toolkit to introduce DOE employees to the basic terms and concepts of the technology supply chain and associated threats. For additional information on the DOE Enterprise SCRM Resource Center and program initiatives, please contact Sue Farrand at

  13. Applying Risk Communication to the Transportation of Radioactive Materials

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    | Department of Energy Applying Risk Communication to the Transportation of Radioactive Materials Applying Risk Communication to the Transportation of Radioactive Materials Participants should expect to gain the following skills: How to recognize how the stakeholders prefer to receive information How to integrate risk communication principles into individual communication How to recognize the importance of earning trust and credibility How to identify stakeholders How to answer questions

  14. DOE Draft Standard, Development and Use of Probabilistic Risk Assessments

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    in Department of Energy Nuclear Safety Applications, 12/10 | Department of Energy DOE Draft Standard, Development and Use of Probabilistic Risk Assessments in Department of Energy Nuclear Safety Applications, 12/10 DOE Draft Standard, Development and Use of Probabilistic Risk Assessments in Department of Energy Nuclear Safety Applications, 12/10 The Department has taken several actions to provide an infrastructure for providing appropriate controls and support for use of risk assessments and

  15. A Resource Handbook on DOE Transportation Risk Assessment

    Broader source: Energy.gov [DOE]

    This resource handbook was compiled for the U.S. Department of Energy’s (DOE’s) Transportation Risk Assessment Working Group. This document includes the first of a planned series of discussion papers on topical aspects of transportation risk problems. These discussion papers are intended to provide practical advice to program managers and technical personnel responsible for preparing NEPA documents and other transportation risk assessments.

  16. High efficiency and high concentration in photovoltaics

    SciTech Connect (OSTI)

    Yamaguchi, Masafumi; Luque, A.

    1999-10-01

    In this paper, the authors present the state-of-the-art of multijunction solar cells and the future prospects of this technology. Their use in terrestrial applications will likely be for concentrators operating at very high concentrations. Some trends are also discussed and the authors present a cost calculation showing that highly efficient cells under very high concentration would be able to produce electricity at costs competitive with electricity generation costs for some utilities.

  17. Simulating Pelletization Strategies to Reduce the Biomass Supply Risk at America’s Biorefineries

    SciTech Connect (OSTI)

    Jacob J. Jacobson; Shane Carnohan; Andrew Ford; Allyson Beall

    2014-07-01

    Demand for cellulosic ethanol and other advanced biofuels has been on the rise, due in part to federal targets enacted in 2005 and extended in 2007. The industry faces major challenges in meeting these worthwhile and ambitious targets. The challenges are especially severe in the logistics of timely feedstock delivery to biorefineries. Logistical difficulties arise from seasonal production that forces the biomass to be stored in uncontrolled field-side environments. In this storage format physical difficulties arise; transportation is hindered by the low bulk density of baled biomass and the unprotected material can decay leading to unpredictable losses. Additionally, uncertain yields and contractual difficulties can exacerbate these challenges making biorefineries a high-risk venture. Investors’ risk could limit business entry and prevent America from reaching the targets. This paper explores pelletizer strategies to convert the lignocellulosic biomass into a denser form more suitable for storage. The densification of biomass would reduce supply risks, and the new system would outperform conventional biorefinery supply systems. Pelletizer strategies exhibit somewhat higher costs, but the reduction in risk is well worth the extra cost if America is to grow the advanced biofuels industry in a sustainable manner.

  18. The Department of Energy Releases Draft of Cybersecurity Risk...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    The Department of Energy Releases Draft of Cybersecurity Risk Management Process (RMP) Guideline for Public Comment (September 2011) The Department of Energy Releases Draft of ...

  19. Global Framework for Climate Risk Exposure | Open Energy Information

    Open Energy Info (EERE)

    October 2006. Investors require this information in order to analyze a company's business risks and opportunities resulting from climate change, as well as the company's...

  20. PROJECT MANAGEMENT RISK COMMITTEE (PMRC) STANDARD OPERATING PROCEDURE

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Version: April 21, 2016 PROJECT MANAGEMENT RISK COMMITTEE (PMRC) STANDARD OPERATING PROCEDURE FOR PLANNING AND ... and Review The review process will be carried out at PMRC ...

  1. Sustainability for the Global Biofuels Industry Minimizing Risks...

    Broader source: Energy.gov (indexed) [DOE]

    y: .18" Sustainability for the Global Biofuels Industry Minimizing Risks and Maximizing ... policy Community level workshops on biofuels, climate change, and agriculture held in ...

  2. Sandia Energy - DHS Mulls Updates to Chemical Site Risk Assessments

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    DHS Mulls Updates to Chemical Site Risk Assessments Home Infrastructure Security Infrastructure Assurance Facilities News NISAC News & Events Research & Capabilities Modeling...

  3. Integrated Waste Treatment Unit GFSI Risk Management Plan

    SciTech Connect (OSTI)

    W. A. Owca

    2007-06-21

    This GFSI Risk Management Plan (RMP) describes the strategy for assessing and managing project risks for the Integrated Waste Treatment Unit (IWTU) that are specifically within the control and purview of the U.S. Department of Energy (DOE), and identifies the risks that formed the basis for the DOE contingency included in the performance baseline. DOE-held contingency is required to cover cost and schedule impacts of DOE activities. Prior to approval of the performance baseline (Critical Decision-2) project cost contingency was evaluated during a joint meeting of the Contractor Management Team and the Integrated Project Team for both contractor and DOE risks to schedule and cost. At that time, the contractor cost and schedule risk value was $41.3M and the DOE cost and schedule risk contingency value is $39.0M. The contractor cost and schedule risk value of $41.3M was retained in the performance baseline as the contractor's management reserve for risk contingency. The DOE cost and schedule risk value of $39.0M has been retained in the performance baseline as the DOE Contingency. The performance baseline for the project was approved in December 2006 (Garman 2006). The project will continue to manage to the performance baseline and change control thresholds identified in PLN-1963, ''Idaho Cleanup Project Sodium-Bearing Waste Treatment Project Execution Plan'' (PEP).

  4. EMGeo: Risk Minimizing Software for Finding Offshore Fossil Fuels...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Find More Like This Return to Search EMGeo: Risk Minimizing Software for Finding Offshore ... developed advanced software for discovering and mapping offshore fossil fuel deposits. ...

  5. Milestone Reached: New Process Reduces Cost and Risk of Biofuel...

    Broader source: Energy.gov (indexed) [DOE]

    a bio-oil intermediate into biofuel, making the conversion process expensive. Battelle's new process substantially reduces the cost and risk of biofuel production and helps make ...

  6. The Low Risk Site Handbook for Erosion Prevention and Sediment...

    Open Energy Info (EERE)

    Low Risk Site Handbook for Erosion Prevention and Sediment Control Jump to: navigation, search OpenEI Reference LibraryAdd to library PermittingRegulatory Guidance - Guide...

  7. Enterprise Risk Management Framework - DOE Directives, Delegations, and

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Requirements Framework by Website Administrator PDF document icon Enterprise_Risk_Managment_Framework.pdf - PDF document, 359 KB (368207

  8. Enterprise Risk Management Model - DOE Directives, Delegations, and

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Requirements Model by Website Administrator PDF document icon Enterprise_Risk_Management_Model.pdf - PDF document, 863 KB (884517

  9. October 13, 2015 Webinar - EPA Radiation Risk Assessment Approach |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy 3, 2015 Webinar - EPA Radiation Risk Assessment Approach October 13, 2015 Webinar - EPA Radiation Risk Assessment Approach Performance & RIsk Assessment (P&RA) Community of Practice (CoP) Webinar - October 13, 2015 - EPA Radiation Risk Assessment Approach by Mr. Stuart Walker, U.S. Environmental Protection Agency, 2-3 pm Eastern Time. Agenda - October 13, 2015 - P&RA CoP Webinar (284.55 KB) Presentation - U.S. EPA Superfund Remedial Program's Approach for

  10. A phased approach to induced seismicity risk management

    SciTech Connect (OSTI)

    White, Joshua A.; Foxall, William

    2014-01-01

    This work describes strategies for assessing and managing induced seismicity risk during each phase of a carbon storage project. We consider both nuisance and damage potential from induced earthquakes, as well as the indirect risk of enhancing fault leakage pathways. A phased approach to seismicity management is proposed, in which operations are continuously adapted based on available information and an on-going estimate of risk. At each project stage, specific recommendations are made for (a) monitoring and characterization, (b) modeling and analysis, and (c) site operations. The resulting methodology can help lower seismic risk while ensuring site operations remain practical and cost-effective.

  11. Risk Analysis, Grid Integration, and Resiliency - State and Federal...

    Broader source: Energy.gov (indexed) [DOE]

    IN ENERGY SYSTEMS RISK AND RESILIENCE Tribal Energy Systems: Climate Preparedness and Resiliency Tribal Leader Forum Series Office of Electricity Delivery and Energy ...

  12. Reducing Cyber Risk to Critical Infrastructure: NIST Framework...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Cyber Community C Voluntary Program Electricity Subsector Cybersecurity Risk Management ... November 3, 2015 National Critical Infrastructure Security and Resilience Month: Improving ...

  13. "Insurance as a Risk Management Instrument for Energy Infrastructure...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    "Insurance as a Risk Management Instrument for Energy Infrastructure Security and Resilience" Report (March 2013) The Office of Electricity Delivery and Energy Reliability has ...

  14. New Flood Risk Management Standard Responds to Effects of Climate...

    Energy Savers [EERE]

    and resilience against flooding." The principal change is the establishment of the Federal Flood Risk Management Standard, "a flexible framework to increase resilience against ...

  15. New Executive Order Establishes a Federal Flood Risk Management...

    Office of Environmental Management (EM)

    Executive Order Establishes a Federal Flood Risk Management Standard New Executive Order ... Input, on January 30, 2015. The new E.O. amends E.O. 11988, "Floodplain ...

  16. A phased approach to induced seismicity risk management

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    White, Joshua A.; Foxall, William

    2014-01-01

    This work describes strategies for assessing and managing induced seismicity risk during each phase of a carbon storage project. We consider both nuisance and damage potential from induced earthquakes, as well as the indirect risk of enhancing fault leakage pathways. A phased approach to seismicity management is proposed, in which operations are continuously adapted based on available information and an on-going estimate of risk. At each project stage, specific recommendations are made for (a) monitoring and characterization, (b) modeling and analysis, and (c) site operations. The resulting methodology can help lower seismic risk while ensuring site operations remain practical andmore » cost-effective.« less

  17. Proliferation Risk Reduction Study of Alternative Spent Fuel Processing

    SciTech Connect (OSTI)

    Bari,R.A.; Phillips, J.; Pilat, J.; Rochau, G.; Therios, I.; Wigeland, R.; Wonder, E.; Zentner, M.

    2009-07-12

    This paper presents the results of an evaluation of the relative proliferation risks of particular reprocessing technologies focusing on COEX, UREX+, and pyroprocessing

  18. DOE Draft Standard, Development and Use of Probabilistic Risk...

    Office of Environmental Management (EM)

    Draft Standard, Development and Use of Probabilistic Risk Assessments in Department of Energy Nuclear Safety Applications, 1210 DOE Draft Standard, Development and Use of ...

  19. DOE (Department of Energy) risk assessment worksheets: A structured approach

    SciTech Connect (OSTI)

    Not Available

    1989-09-01

    This volume consists of the worksheets for each step in completing the guideline. This guideline outlines the approach to conducting risk assessments of computer security. (JEF)

  20. Security Risk Assessment Methodologies (RAM) for Critical Infrastructu...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Building Energy Efficiency Find More Like This Return to Search Security Risk Assessment Methodologies (RAM) for Critical Infrastructures Sandia National Laboratories...

  1. Testing the cultural theory of risk in France

    SciTech Connect (OSTI)

    Brenot, J.; Bonnefous, S.; Marris, C.

    1998-12-01

    Cultural Theory, as developed by Mary Douglas, argues that differing risk perceptions can be explained by reference to four distinct cultural biases: hierarchy, egalitarianism, individualism, and fatalism. This paper presents empirical results from a quantitative survey based on a questionnaire devised by Karl Dake to measure these cultural biases. A large representative sample was used to test this instrument in the French social context. Correlations between cultural biases and perceptions of 20 social and environmental risks were examined. These correlations were very weak, but were statistically significant: cultural biases explained 6%, at most, of the variance in risk perceptions. Standard socio-demographic variables were also weakly related to risk perceptions (especially gender, social class, and education), and cultural biases and socio-demographic variables were themselves intercorrelated (especially with age, social class, and political outlook). The authors compare these results with surveys conducted in other countries using the same instrument and conclude that new methods, more qualitative and contextual, still need to be developed to investigate the cultural dimensions of risk perceptions. The paper also discusses relationships between perceptions of personal and residual risk, and between perceived risk and demand for additional safety measures. These three dimensions were generally closely related, but interesting differences were observed for some risk issues. Included in the list of risk perceptions were pollution, hazardous materials, and radioactive wastes.

  2. Climate Change: Risks and Opportunities for the Finance Sector...

    Open Energy Info (EERE)

    Finance Sector Online Course Jump to: navigation, search Tool Summary LAUNCH TOOL Name: Climate Change: Risks and Opportunities for the Finance Sector Online Course Agency...

  3. Proliferation and Terrorism Risk Assessment | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    These assessments will: Exploit science-based approaches for analyzing difficult-to-quantify proliferation risk factors or indicators (e.g., capabilities, motivations and ...

  4. Using Measurement and Verification to Manage Risk in Federal...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Assumption of risk implies acceptance of the potential monetary consequences. Energy service companies (ESCOs) and agencies are reluctant to assume responsibility for factors they ...

  5. Secretary Bodman Announces Federal Risk Insurance for Nuclear...

    Energy Savers [EERE]

    The rule will be available on DOE's web site soon. "Providing federal risk insurance is an important step in speeding the nuclear renaissance in this country," Secretary Bodman ...

  6. Risk Informed Margins Management as part of Risk Informed Safety Margin Characterization

    SciTech Connect (OSTI)

    Curtis Smith

    2014-06-01

    The ability to better characterize and quantify safety margin is important to improved decision making about Light Water Reactor (LWR) design, operation, and plant life extension. A systematic approach to characterization of safety margins and the subsequent margin management options represents a vital input to the licensee and regulatory analysis and decision making that will be involved. In addition, as research and development in the LWR Sustainability (LWRS) Program and other collaborative efforts yield new data, sensors, and improved scientific understanding of physical processes that govern the aging and degradation of plant SSCs needs and opportunities to better optimize plant safety and performance will become known. To support decision making related to economics, readability, and safety, the Risk Informed Safety Margin Characterization (RISMC) Pathway provides methods and tools that enable mitigation options known as risk informed margins management (RIMM) strategies.

  7. Yucca Mountain transportation routes: Preliminary characterization and risk analysis; Volume 2, Figures [and] Volume 3, Technical Appendices

    SciTech Connect (OSTI)

    Souleyrette, R.R. II; Sathisan, S.K.; di Bartolo, R.

    1991-05-31

    This report presents appendices related to the preliminary assessment and risk analysis for high-level radioactive waste transportation routes to the proposed Yucca Mountain Project repository. Information includes data on population density, traffic volume, ecologically sensitive areas, and accident history.

  8. Integrated Risk Assessment for the LaSalle Unit 2 Nuclear Power Plant, Phenomenology and Risk Uncertainty Evaluation Program (PRUEP), MELCOR code calculations. Volume 3

    SciTech Connect (OSTI)

    Shaffer, C.J. [Science and Engineering Associates, Albuquerque, NM (United States); Miller, L.A.; Payne, A.C. Jr.

    1992-10-01

    A Level III Probabilistic Risk Assessment (PRA) has been performed for LaSalle Unit 2 under the Risk Methods Integration and Evaluation Program (RMIEP) and the Phenomenology and Risk Uncertainty Evaluation Program (PRUEP). This report documents the phenomenological calculations and sources of. uncertainty in the calculations performed with HELCOR in support of the Level II portion of the PRA. These calculations are an integral part of the Level II analysis since they provide quantitative input to the Accident Progression Event Tree (APET) and Source Term Model (LASSOR). However, the uncertainty associated with the code results must be considered in the use of the results. The MELCOR calculations performed include four integrated calculations: (1) a high-pressure short-term station blackout, (2) a low-pressure short-term station blackout, (3) an intermediate-term station blackout, and (4) a long-term station blackout. Several sensitivity studies investigating the effect of variations in containment failure size and location, as well as hydrogen ignition concentration are also documented.

  9. Integrated Risk Assessment for the LaSalle Unit 2 Nuclear Power Plant, Phenomenology and Risk Uncertainty Evaluation Program (PRUEP), MELCOR code calculations

    SciTech Connect (OSTI)

    Shaffer, C.J. (Science and Engineering Associates, Albuquerque, NM (United States)); Miller, L.A.; Payne, A.C. Jr.

    1992-10-01

    A Level III Probabilistic Risk Assessment (PRA) has been performed for LaSalle Unit 2 under the Risk Methods Integration and Evaluation Program (RMIEP) and the Phenomenology and Risk Uncertainty Evaluation Program (PRUEP). This report documents the phenomenological calculations and sources of. uncertainty in the calculations performed with HELCOR in support of the Level II portion of the PRA. These calculations are an integral part of the Level II analysis since they provide quantitative input to the Accident Progression Event Tree (APET) and Source Term Model (LASSOR). However, the uncertainty associated with the code results must be considered in the use of the results. The MELCOR calculations performed include four integrated calculations: (1) a high-pressure short-term station blackout, (2) a low-pressure short-term station blackout, (3) an intermediate-term station blackout, and (4) a long-term station blackout. Several sensitivity studies investigating the effect of variations in containment failure size and location, as well as hydrogen ignition concentration are also documented.

  10. Influence of Pulmonary Nodules on Chest Computed Tomography and Risk of Recurrence in Stage IV Wilms Tumor

    SciTech Connect (OSTI)

    Kirkland, Robert S.; Nanda, Ronica H.; Alazraki, Adina; Esiashvili, Natia

    2015-06-01

    Purpose: Chest computed tomography (CT) is currently accepted as the main modality for initial disease staging and response assessment in Wilms tumor (WT). However, there is great variability in the number and size of lung metastases at the time of diagnosis and after induction chemotherapy. There is a lack of clinical evidence as to how this variability in tumor burden affects choice of therapy and disease outcome. This study sought to evaluate a previously proposed lung metastases risk stratification system based on CT findings and clinical outcomes in stage IV WT patients. Methods and Materials: Thirty-five pediatric patients with a diagnosis of stage IV WT with evaluable pre- and postdiagnosis CT scans between 1997 and 2012 were included in the analysis. Patients were divided into low-, intermediate-, and high-risk categories based on the size and number of pulmonary metastases before and after 6 weeks of chemotherapy. Association of the lung risk groups with lung recurrence-free survival and overall survival at each time point was analyzed with relevant covariates. Results: Risk group distribution both at diagnosis and after induction chemotherapy was not influenced by tumor histology. Initial risk grouping suggested an association with disease-free survival at 5 years (P=.074); however, the most significant correlation was with postinduction chemotherapy disease status (P=.027). In patients with an intermediate or high burden of disease after 6 weeks of chemotherapy, despite receiving whole-lung and boost irradiation, survival outcomes were poorer. Conclusions: Pulmonary tumor burden in stage IV WT on chest CT can predict disease outcome. Patients with intermediate- or low-risk disease, especially after induction therapy, have a higher risk for recurrence. After prospective validation, this method may become a valuable tool in adaptation of therapy to improve outcome.

  11. High Performance Computing

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    HPC INL Logo Home High-Performance Computing INL's high-performance computing center provides general use scientific computing capabilities to support the lab's efforts in advanced...

  12. High pressure, high current, low inductance, high reliability sealed terminals

    DOE Patents [OSTI]

    Hsu, John S [Oak Ridge, TN; McKeever, John W [Oak Ridge, TN

    2010-03-23

    The invention is a terminal assembly having a casing with at least one delivery tapered-cone conductor and at least one return tapered-cone conductor routed there-through. The delivery and return tapered-cone conductors are electrically isolated from each other and positioned in the annuluses of ordered concentric cones at an off-normal angle. The tapered cone conductor service can be AC phase conductors and DC link conductors. The center core has at least one service conduit of gate signal leads, diagnostic signal wires, and refrigerant tubing routed there-through. A seal material is in direct contact with the casing inner surface, the tapered-cone conductors, and the service conduits thereby hermetically filling the interstitial space in the casing interior core and center core. The assembly provides simultaneous high-current, high-pressure, low-inductance, and high-reliability service.

  13. Risk Due to Radiological Terror Attacks With Natural Radionuclides

    SciTech Connect (OSTI)

    Friedrich, Steinhaeusler; Lyudmila, Zaitseva; Stan, Rydell

    2008-08-07

    The naturally occurring radionuclides radium (Ra-226) and polonium (Po-210) have the potential to be used for criminal acts. Analysis of international incident data contained in the Database on Nuclear Smuggling, Theft and Orphan Radiation Sources (CSTO), operated at the University of Salzburg, shows that several acts of murder and terrorism with natural radionuclides have already been carried out in Europe and Russia. Five different modes of attack (T) are possible: (1) Covert irradiation of an individual in order to deliver a high individual dose; (2) Covert irradiation of a group of persons delivering a large collective dose; (3) Contamination of food or drink; (4) Generation of radioactive aerosols or solutions; (5) Combination of Ra-226 with conventional explosives (Dirty Bomb).This paper assesses the risk (R) of such criminal acts in terms of: (a) Probability of terrorist motivation deploying a certain attack mode T; (b) Probability of success by the terrorists for the selected attack mode T; (c) Primary damage consequence (C) to the attacked target (activity, dose); (d) Secondary damage consequence (C') to the attacked target (psychological and socio-economic effects); (e) Probability that the consequences (C, C') cannot be brought under control, resulting in a failure to manage successfully the emergency situation due to logistical and/or technical deficits in implementing adequate countermeasures. Extensive computer modelling is used to determine the potential impact of such a criminal attack on directly affected victims and on the environment.

  14. Tank Waste Remediation System decisions and risk assessment

    SciTech Connect (OSTI)

    Johnson, M.E.

    1994-09-01

    The Tank Waste Remediation System (TWRS) mission is to store, treat, and immobilize the highly radioactive Hanford Site tank wastes and encapsulated cesium and strontium materials in an environmentally sound, safe, and cost effective manner. Additionally, the TWRS conducts, as part of this mission, resolution of safety issues associated with the wastes within the 177 underground radioactive waste tanks. Systems engineering principles are being applied to determine the functions and establish requirements necessary for accomplishing the TWRS mission (DOE 1994 draft). This systematic evaluation of the TWRS program has identified key decisions that must be executed to establish mission scope, determine requirements, or select a technical solution for accomplishing identified functions and requirements. Key decisions identified through the systematic evaluation of the TWRS mission are presented in this document. Potential alternative solutions to each decision are discussed. After-discussion and evaluation of each decision with effected stakeholder groups, the US Department of Energy (DOE) will select a solution from the identified alternatives for implementation. In order to proceed with the development and execution of the tank waste remediation program, the DOE has adopted a planning basis for several of these decisions, until a formal basis is established. The planning bases adopted by the DOE is continuing to be discussed with stakeholder groups to establish consensus for proceeding with proposed actions. Technical and programmatic risks associated with the planning basis adopted by the DOE are discussed.

  15. A Risk Management Approach to the "Insider Threat"

    SciTech Connect (OSTI)

    Bishop, Matt; Engle, Sophie J.; Frincke, Deborah A.; Gates, Carrie; Greitzer, Frank L.; Peisert, Sean; Whalen, Sean

    2010-09-01

    Abstract Recent surveys indicate that the financial impact and operating losses due to insider intrusions are increasing. But these studies often disagree on what constitutes an insider; indeed, many define it only implicitly. In theory, appropriate selection of, and enforcement of, properly specified security policies should prevent legitimate users from abusing their access to computer systems, information, and other resources. However, even if policies could be expressed precisely, the natural mapping between the natural language expression of a security policy, and the expression of that policy in a form that can be implemented on a computer system or network, creates gaps in enforcement. This paper defines insider precisely, in terms of these gaps, and explores an access-based model for analyzing threats that include those usually termed insider threats. This model enables an organization to order its resources based on the business value for that resource and of the information it contains. By identifying those users with access to high-value resources, we obtain an ordered list of users who can cause the greatest amount of damage. Concurrently with this, we examine psychological indicators in order to determine which users are at the greatest risk of acting inappropriately.We conclude by examining how to merge this model with one of forensic logging and auditing.

  16. GTRI's Convert Program: Minimizing the Use of Highly Enriched Uranium |

    National Nuclear Security Administration (NNSA)

    National Nuclear Security Administration | (NNSA) GTRI's Convert Program: Minimizing the Use of Highly Enriched Uranium May 29, 2014 Mission In 2004 NNSA established the Global Threat Reduction Initiative (GTRI) in the Office of Defense Nuclear Nonproliferation to, as quickly as possible, identify, secure, remove and/or facilitate the disposition of high risk vulnerable nuclear and radiological materials around the world that pose a threat to the United States and the international

  17. Highly Enriched Uranium Transparency Program | National Nuclear Security

    National Nuclear Security Administration (NNSA)

    Administration | (NNSA) Highly Enriched Uranium Transparency Program November 13, 2013 The U.S. National Nuclear Security Administration's (NNSA) Highly Enriched Uranium (HEU) Transparency Program reduces nuclear risk by monitoring the conversion of 500 metric tons (MT) of Russian HEU, enough material for 20,000 nuclear weapons, into low enriched uranium (LEU). This LEU is put into peaceful use in the United States, generating nearly 10% of all U.S. electrical power. The HEU Purchase

  18. An association between the risk of ovarian cancer and rare HRAS1 alleles

    SciTech Connect (OSTI)

    Weitzel, J.N.; Patel, J.; Smith, D.M.

    1994-09-01

    The highly polymorphic HRAS1 minisatellite locus just downstream from the proto-oncogene H-ras-1 on chromosome 11p consists of four common progenitor alleles and several dozen rare alleles, which apparently derive from mutations of the progenitors. Mutant alleles of this locus represent a major risk factor for common types of cancer. Rare-sized HRAS1 alleles have been found more frequently in patients with carcinoma of the breast, colorectum, and urinary bladder and acute leukemia, compared to cancer-free controls. This highly significant association (p<1.001) results in a modest relative risk for patients with one rare allele, but the prevalence of this class of mutant alleles implies an important attributable risk: 1 in 11 cancers of the breast, colorectum, and bladder. Therefore, we performed a case-control study using conventional (Southern blot) and PCR-based methods to score HRAS1 alleles in the leukocyte DNA from 59 patients with ovarian cancer, and 51 cancer-free controls. Our preliminary data suggest an increased incidence of rare and intermediate HRAS1 alleles in caucasian ovarian cancer patients (13%) compared to cancer-free controls (4%). These results parallel the allele distribution seen in the large published series, and lend support for a significant association between rare HRAS1 alleles and ovarian cancer predisposition.

  19. Risk assessment compatible fire models (RACFMs)

    SciTech Connect (OSTI)

    Lopez, A.R.; Gritzo, L.A.; Sherman, M.P.

    1998-07-01

    A suite of Probabilistic Risk Assessment Compatible Fire Models (RACFMs) has been developed to represent the hazard posed by a pool fire to weapon systems transported on the B52-H aircraft. These models represent both stand-off (i.e., the weapon system is outside of the flame zone but exposed to the radiant heat load from fire) and fully-engulfing scenarios (i.e., the object is fully covered by flames). The approach taken in developing the RACFMs for both scenarios was to consolidate, reconcile, and apply data and knowledge from all available resources including: data and correlations from the literature, data from an extensive full-scale fire test program at the Naval Air Warfare Center (NAWC) at China Lake, and results from a fire field model (VULCAN). In the past, a single, effective temperature, T{sub f}, was used to represent the fire. The heat flux to an object exposed to a fire was estimated using the relationship for black body radiation, {sigma}T{sub f}{sup 4}. Significant improvements have been made by employing the present approach which accounts for the presence of temperature distributions in fully-engulfing fires, and uses best available correlations to estimate heat fluxes in stand-off scenarios.

  20. Risk Management for Sodium Fast Reactors.

    SciTech Connect (OSTI)

    Denman, Matthew R; Groth, Katrina; Cardoni, Jeffrey N; Wheeler, Timothy A.

    2015-01-01

    Accident management is an important component to maintaining risk at acceptable levels for all complex systems, such as nuclear power plants. With the introduction of self - correcting, or inherently safe, reactor designs the focus has shifted from management by operators to allowing the syste m's design to manage the accident. While inherently and passively safe designs are laudable, extreme boundary conditions can interfere with the design attributes which facilitate inherent safety , thus resulting in unanticipated and undesirable end states. This report examines an inherently safe and small sodium fast reactor experiencing a beyond design basis seismic event with the intend of exploring two issues : (1) can human intervention either improve or worsen the potential end states and (2) can a Bayes ian Network be constructed to infer the state of the reactor to inform (1). ACKNOWLEDGEMENTS The author s would like to acknowledge the U.S. Department of E nergy's Office of Nuclear Energy for funding this research through Work Package SR - 14SN100303 under the Advanced Reactor Concepts program. The authors also acknowledge the PRA teams at A rgonne N ational L aborator y , O ak R idge N ational L aborator y , and I daho N ational L aborator y for their continue d contributions to the advanced reactor PRA mission area.

  1. Using fire tests for quantitative risk analysis

    SciTech Connect (OSTI)

    Ling, W.C.T.; Williamson, R.B.

    1980-03-01

    Fires can be considered a causal chain-of-events in which the growth and spread of fire may cause damage and injury if it is rapid enough to overcome the barriers placed in its way. Fire tests for fire resistance of the barriers can be used in a quantitative risk assessment. The fire growth and spread is modelled in a State Transition Model (STM). The fire barriers are presented as part of the Fire Protection Model (FPM) which is based on a portion of the NFPA Decision Tree. An Emergency Equivalent Network is introduced to couple the Fire Growth Model (FGM) and the FPM so that the spread of fire beyond the room-of-origin can be computed. An example is presented in which a specific building floor plan is analyzed to obtain the shortest expected time for fire to spread between two points. To obtain the probability and time for each link in the network, data from the results of fire tests were used. These results were found to be lacking and new standards giving better data are advocated.

  2. Limiting Future Proliferation and Security Risks

    SciTech Connect (OSTI)

    Bari, R.

    2011-03-13

    A major new technical tool for evaluation of proliferation and security risks has emerged over the past decade as part the activities of the Generation IV International Forum. The tool has been developed by a consensus group from participating countries and organizations and is termed the Proliferation Resistance and Physical Protection (PR&PP) Evaluation Methodology. The methodology defines a set of challenges, analyzes system response to these challenges, and assesses outcomes. The challenges are the threats posed by potential actors (proliferant states or sub-national adversaries). It is of paramount importance in an evaluation to establish the objectives, capabilities, resources, and strategies of the adversary as well as the design and protection contexts. Technical and institutional characteristics are both used to evaluate the response of the system and to determine its resistance against proliferation threats and robustness against sabotage and terrorism threats. The outcomes of the system response are expressed in terms of a set of measures, which thereby define the PR&PP characteristics of the system. This paper summarizes results of applications of the methodology to nuclear energy systems including reprocessing facilities and large and small modular reactors. The use of the methodology in the design phase a facility will be discussed as it applies to future safeguards concepts.

  3. WM2014 Conference- Building the Community of Practice for Performance and Risk Assessment in Support of Risk-Informed Environmental Management Decisions

    Broader source: Energy.gov [DOE]

    WM2014 Conference - Building the Community of Practice for Performance and Risk Assessment in Support of Risk-Informed Environmental Management Decisions - 14575

  4. July 24, 2009, Visiting Speakers Program - Regulation and High Reliability Organizations by Dr. Jerry Ellig

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Regulation and High Reliability Organizations Jerry Ellig Senior Research Fellow Prepared for the U.S. Department of Energy Office of Health, Safety, and Security Visiting Speakers Program National Academy of Public Administration July 24, 2009 High Reliability Organizations � "Avoid catastrophes in high-risk, complex operating environments ... consistently deliver year-in/year-out high value and high performance regardless of their operating environment." � Key principle: Reality

  5. 7th Workshop on Risk Informed Regulation and Safety Culture

    Office of Energy Efficiency and Renewable Energy (EERE)

    The 7th Workshop on Risk Informed Regulation and Safety Culture was one of a series of workshops designed by the Office of Nuclear Energy in concert with experts from the Idaho National Laboratory to assist China in developing a comprehensive, successful and efficient Risk-Informed Regulatory framework.

  6. Embedding climate change risk assessment within a governance context

    SciTech Connect (OSTI)

    Preston, Benjamin L

    2011-01-01

    Climate change adaptation is increasingly being framed in the context of climate risk management. This has contributed to the proliferation of climate change vulnerability and/or risk assessments as means of supporting institutional decision-making regarding adaptation policies and measures. To date, however, little consideration has been given to how such assessment projects and programs interact with governance systems to facilitate or hinder the implementation of adaptive responses. An examination of recent case studies involving Australian local governments reveals two key linkages between risk assessment and the governance of adaptation. First, governance systems influence how risk assessment processes are conducted, by whom they are conducted, and whom they are meant to inform. Australia s governance system emphasizes evidence-based decision-making that reinforces a knowledge deficit model of decision support. Assessments are often carried out by external experts on behalf of local government, with limited participation by relevant stakeholders and/or civil society. Second, governance systems influence the extent to which the outputs from risk assessment activities are translated into adaptive responses and outcomes. Technical information regarding risk is often stranded by institutional barriers to adaptation including poor uptake of information, competition on the policy agenda, and lack of sufficient entitlements. Yet, risk assessments can assist in bringing such barriers to the surface, where they can be debated and resolved. In fact, well-designed risk assessments can contribute to multi-loop learning by institutions, and that reflexive problem orientation may be one of the more valuable benefits of assessment.

  7. Evaluation of severe accident risks: Surry Unit 1

    SciTech Connect (OSTI)

    Breeding, R.J. ); Helton, J.C. ); Murfin, W.B. ); Smith, L.N. )

    1990-10-01

    In support of the Nuclear Regulatory Commission's (NRC's) assessment of the risk from severe accidents at commercial nuclear power plants in the US reported in NUREG-1150, the Severe Accident Risk Reduction Program (SARRP) has completed a revised calculation of the risk to the general public from severe accidents at the Surry Power Station, Unit 1. This power plant, located in southeastern Virginia, is operated by the Virginia Electric Power Corp. The emphasis in this risk analysis was not on determining a so-called'' point estimate of risk. Rather, it was to determine the distribution of risk, and to discover the uncertainties that account for the breadth of this distribution. Off-site risk initiation by events, both internal to the power station and external to the power station were assessed. This document, Volume 3, Revision 1, Part 2, provides Appendices A through E to this report. These appendices contain: supporting information for the accident progression analysis; the source term analysis; the consequence analysis; risk results; and sampling information.

  8. Sustainability for the Global Biofuels Industry: Minimizing Risks and

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Maximizing Opportunities Webinar Transcript | Department of Energy Opportunities Webinar Transcript Sustainability for the Global Biofuels Industry: Minimizing Risks and Maximizing Opportunities Webinar Transcript Webinar transcript. sustainability_global_biofuels_webinar.doc (148 KB) More Documents & Publications Sustainability for the Global Biofuels Industry Minimizing Risks and Maximizing Opportunities 2009 National Electric Transmission Congestion Study - Chicago Workshop 2009

  9. Sustainability for the Global Biofuels Industry: Minimizing Risks and

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Maximizing Opportunities | Department of Energy Opportunities Sustainability for the Global Biofuels Industry: Minimizing Risks and Maximizing Opportunities Introduction slides for the webinar describing bioenergy and sustainability. sustainability_biofuels_webinar_intro.pdf (759.43 KB) More Documents & Publications Sustainability for the Global Biofuels Industry: Minimizing Risks and Maximizing Opportunities Webinar Transcript Market Drivers for Biofuels Biomass Program Perspectives on

  10. Risk assessment for produced water discharges to Louisiana Open Bays

    SciTech Connect (OSTI)

    Meinhold, A.F.; DePhillips, M.P.; Holtzman, S.

    1995-06-23

    Data were collected prior to termination of discharge at three sites (including two open bay sites at Delacroix Island and Bay De Chene) for the risk assessments. The Delacroix Island Oil and Gas Field has been in production since the first well drilling in 1940; the Bay De Chene Field, since 1942. Concentrations of 226Ra, 228Ra, 210Po, and 228Th were measured in discharges. Radium conc. were measured in fish and shellfish tissues. Sediment PAH and metal conc. were also available. Benthos sampling was conducted. A survey of fishermen was conducted. The tiered risk assessment showed that human health risks from radium in produced water appear to be small; ecological risk from radium and other radionuclides in produced water also appear small. Many of the chemical contaminants discharged to open Louisiana bays appear to present little human health or ecological risk. A conservative screening analysis suggested potential risks to human health from Hg and Pb and a potential risk to ecological receptors from total effluent, Sb, Cd, Cu, Pb, Ni, Ag, Zn, and phenol in the water column and PAHs in sediment; quantitiative risk assessments are being done for these contaminants.

  11. RELATIVE PROLIFERATION RISKS FOR NUCLEAR FUEL LEASING ARRANGEMENT

    SciTech Connect (OSTI)

    CHENG,L.Y.; YUE, M.; BARI, R.A.

    2007-10-01

    The present study demonstrates a probabilistic approach to quantify the proliferation risks of fuel leasing and recycling. A Markov model approach is applied to evaluate the probability of proliferation success by diversion or theft. Proliferation risk is calculated as a product of the probability of success and the corresponding consequences.

  12. The effect of bright lines in environmental risk communication

    SciTech Connect (OSTI)

    Wilson, K.N.; Desvousges, W.H.; Smith, K.V.; Payne, J. )

    1993-01-01

    Bright lines in environmental risk communication refer to the specific levels at which an environmental risk becomes a serious health threat and action should be taken to mitigate its effects. This study examined the effect of bright lines'' in risk communication by emphasizing the radon exposure threshold level of 4 picocuries per liter. Specifically, the authors developed a computer-assisted interview containing bright-line versions of risk information. The bright-line version contained a range of possible radon levels, the corresponding number of estimated lung cancer cases, the relative health risk from radon compared to other health risks, and the EPA guidelines for mitigating levels above 4 picocuries in the home. The non-bright line version was identical to the bright-line version, except it did not include the EPA's mitigation recommendations. Effect measures included respondents' change in perceived risk after reading their materials, intended testing behavior, and advice to their neighbor for a specified radon level either above or below the 4 picocury threshold level. This paper discusses broader policy implications for designing effective risk communication programs.

  13. Risk communications and the Chemical Stockpile Emergency-Planning Program

    SciTech Connect (OSTI)

    Vogt, B.M.; Sorensen, J.H.

    1994-09-01

    The CSEPP (Chemical Stockpile Emergency Preparedness Program) was created to improve emergency planning and response capabilities at the eight sites around the country that store chemical weapons. These weapons are scheduled to be destroyed in the near future. In preparation of the Draft Programmatic Environmental Impact Statement (DPEIS) for the Chemical Stockpile Disposal Program (CSDP), it was proposed that the Army mitigate accidents through an enhanced community emergency preparedness program at the eight storage sites. In 1986, the Army initiated the development of an Emergency Response Concept Plan (ERCP) for the CSDP, one of 12 technical support studies conducted during preparation of the Final Programmatic Environmental Impact Statement (FPEIS). The purpose of this document is to provide a fairly comprehensive source book on risk, risk management, risk communication research and recommended risk communication practices. It does not merely summarize each publication in the risk communication literature, but attempts to synthesize them along the lines of a set of organizing principles. Furthermore, it is not intended to duplicate other guidance manuals (such as Covello et al.`s manual on risk comparison). The source book was developed for the CSEPP in support of the training module on risk communications. Although the examples provided are specific to CSEPP, its use goes beyond that of CSEPP as the findings apply to a broad spectrum of risk communication topics. While the emphasis is on communication in emergency preparedness and response specific to the CSEPP, the materials cover other non-emergency communication settings. 329 refs.

  14. Taking Risk Assessment and Management to the Next Level: Program-Level Risk Analysis to Enable Solid Decision-Making on Priorities and Funding

    SciTech Connect (OSTI)

    Nelson, J. G.; Morton, R. L.; Castillo, C.; Dyer, G.; Johnson, N.; McSwain, J. T.

    2011-02-01

    A multi-level (facility and programmatic) risk assessment was conducted for the facilities in the Nevada National Security Site (NNSS) Readiness in Technical Base and Facilities (RTBF) Program and results were included in a new Risk Management Plan (RMP), which was incorporated into the fiscal year (FY) 2010 Integrated Plans. Risks, risk events, probability, consequence(s), and mitigation strategies were identified and captured, for most scope areas (i.e., risk categories) during the facilitated risk workshops. Risk mitigations (i.e., efforts in addition to existing controls) were identified during the facilitated risk workshops when the risk event was identified. Risk mitigation strategies fell into two broad categories: threats or opportunities. Improvement projects were identified and linked to specific risks they mitigate, making the connection of risk reduction through investments for the annual Site Execution Plan. Due to the amount of that was collected, analysis to be performed, and reports to be generated, a Risk Assessment/ Management Tool (RAMtool) database was developed to analyze the risks in real-time, at multiple levels, which reinforced the site-level risk management process and procedures. The RAMtool database was developed and designed to assist in the capturing and analysis of the key elements of risk: probability, consequence, and impact. The RAMtool calculates the facility-level and programmatic-level risk factors to enable a side-by-side comparison to see where the facility manager and program manager should focus their risk reduction efforts and funding. This enables them to make solid decisions on priorities and funding to maximize the risk reduction. A more active risk management process was developed where risks and opportunities are actively managed, monitored, and controlled by each facility more aggressively and frequently. risk owners have the responsibility and accountability to manage their assigned risk in real-time, using the

  15. CCSI Risk Estimation: An Application of Expert Elicitation

    SciTech Connect (OSTI)

    Engel, David W.; Dalton, Angela C.

    2012-10-01

    The Carbon Capture Simulation Initiative (CCSI) is a multi-laboratory simulation-driven effort to develop carbon capture technologies with the goal of accelerating commercialization and adoption in the near future. One of the key CCSI technical challenges is representing and quantifying the inherent uncertainty and risks associated with developing, testing, and deploying the technology in simulated and real operational settings. To address this challenge, the CCSI Element 7 team developed a holistic risk analysis and decision-making framework. The purpose of this report is to document the CCSI Element 7 structured systematic expert elicitation to identify additional risk factors. We review the significance of and established approaches to expert elicitation, describe the CCSI risk elicitation plan and implementation strategies, and conclude by discussing the next steps and highlighting the contribution of risk elicitation toward the achievement of the overarching CCSI objectives.

  16. Overview of DOE-NE Proliferation and Terrorism Risk Assessment

    SciTech Connect (OSTI)

    Sadasivan, Pratap

    2012-08-24

    Research objectives are: (1) Develop technologies and other solutions that can improve the reliability, sustain the safety, and extend the life of current reactors; (2) Develop improvements in the affordability of new reactors to enable nuclear energy; (3) Develop Sustainable Nuclear Fuel Cycles; and (4) Understand and minimize the risks of nuclear proliferation and terrorism. The goal is to enable the use of risk information to inform NE R&D program planning. The PTRA program supports DOE-NE's goal of using risk information to inform R&D program planning. The FY12 PTRA program is focused on terrorism risk. The program includes a mix of innovative methods that support the general practice of risk assessments, and selected applications.

  17. High strength and high toughness steel

    DOE Patents [OSTI]

    Parker, Earl R.; Zackay, Victor F.

    1979-01-01

    A structural steel which possess both high strength and high toughness and has particular application of cryogenic uses. The steel is produced by the utilization of thermally induced phase transformation following heating in a three-phase field in iron-rich alloys of the Fe-Ni-Ti system, with a preferred composition of 12% nickel, 0.5% titanium, the remainder being iron.

  18. High strength, high ductility low carbon steel

    DOE Patents [OSTI]

    Koo, Jayoung; Thomas, Gareth

    1978-01-01

    A high strength, high ductility low carbon steel consisting essentially of iron, 0.05-0.15 wt% carbon, and 1-3 wt% silicon. Minor amounts of other constituents may be present. The steel is characterized by a duplex ferrite-martensite microstructure in a fibrous morphology. The microstructure is developed by heat treatment consisting of initial austenitizing treatment followed by annealing in the (.alpha. + .gamma.) range with intermediate quenching.

  19. The polymorphisms of P53 codon 72 and MDM2 SNP309 and renal cell carcinoma risk in a low arsenic exposure area

    SciTech Connect (OSTI)

    Huang, Chao-Yuan; Department of Urology, National Taiwan University Hospital, College of Medicine National Taiwan University, Taipei, Taiwan ; Su, Chien-Tien; Chu, Jan-Show; Department of Pathology, College of Medicine, Taipei Medical University, Taipei, Taiwan ; Huang, Shu-Pin; Pu, Yeong-Shiau; Yang, Hsiu-Yuan; Chung, Chi-Jung; Department of Health Risk Management, College of Public Health, China Medical University, Taichung, Taiwan ; Wu, Chia-Chang; Department of Urology, Taipei Medical Universtiy-Shuang Ho Hospital, Taipei, Taiwan ; Hsueh, Yu-Mei; Department of Public Health, School of Medicine, College of Medicine, Taipei Medical University, Taipei, Taiwan

    2011-12-15

    Our recent study demonstrated the increased risk of renal cell carcinoma (RCC) associated with high urinary total arsenic levels among people living in a low arsenic exposure area. Genomic instability is important in arsenic carcinogenesis. This study evaluated the relationship between the polymorphisms of p53, p21, and MDM2, which plays a role in gene stability, and the arsenic-related RCC risk. Here, we found that p53 Pro/Pro genotype and MDM2 SNP309 GG genotype significantly increased RCC risk compared to the p53 Arg/Arg genotype and MDM2 SNP309 TT genotype. RCC patients with the p53Arg/Arg genotype had a signicantly low percentage of inorganic arsenic, a low percentage of monomethylarsonic acid (MMA), and a high percentage of dimethylarsinic acid (DMA), which indicates efcient arsenic methylation capacity. Subjects with the p53 Arg/Pro + Pro/Pro genotype or MDM2 SNP309 TG + GG genotype, in conjunction with high urinary total arsenic ({>=} 14.02 {mu}g/L), had a signicantly higher RCC risk than those with the p53 Arg/Arg or MDM2 SNP309 TT genotypes and low urinary total arsenic. Taken together, this is the first study to show that a variant genotype of p53 Arg{sup 72}Pro or MDM2 SNP309 may modify the arsenic-related RCC risk even in a non-obvious arsenic exposure area. -- Highlights: Black-Right-Pointing-Pointer Subjects with p53 Pro/Pro or MDM2 GG genotype significantly increased RCC risk. Black-Right-Pointing-Pointer A significant multiplicative joint effect of p53 and p21 on RCC risk. Black-Right-Pointing-Pointer RCC patients with p53 Arg/Arg genotype had efficient arsenic methylation capacity. Black-Right-Pointing-Pointer Joint effect of p53 or MDM2 genotype and high urinary total arsenic on RCC risk.

  20. An example postclosure risk assessment using the potential Yucca Mountain Site

    SciTech Connect (OSTI)

    Doctor, P.G.; Eslinger, P.W.; Elwood, D.M.; Engel, D.W.; Freshley, M.D.; Liebetrau, A.M.; Reimus, P.W.; Strenge, D.L.; Tanner, J.E.; Van Luik, A.E.

    1992-05-01

    The risk analysis described in this document was performed for the US Department of Energy`s (DOE) Office of Civilian Radioactive Waste Management (OCRWM) over a 2-year time period ending in June 1988. The objective of Pacific Northwest Laboratory`s (PNL) task was to demonstrate an integrated, though preliminary, modeling approach for estimating the postclosure risk associated with a geologic repository for the disposal of high-level nuclear waste. The modeling study used published characterization data for the proposed candidate site at Yucca Mountain, Nevada, along with existing models and computer codes available at that time. Some of the site data and conceptual models reported in the Site Characterization Plan published in December 1988, however, were not yet available at the time that PNL conducted the modeling studies.