Powered by Deep Web Technologies
Note: This page contains sample records for the topic "facility disposition project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


1

Facility Disposition Projects  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Score Maturity Value Target Score Maturity Value Target Score A1 Cost Estimate H 7.5 1 7.5 5 37.5 5 37.5 A2 Cost Risk/Contingency Analysis P 3.0 1 3.0 5 15.0 5 15.0 A3 Funding Requirements/Profile H 7.5 1 7.5 4 30.0 5 37.5 A4 Independent Cost Estimate/Schedule Review P 3.0 N/A 0.0 5 15.0 5 15.0 A5 Life Cycle Cost P 3.0 1 3.0 4 12.0 5 15.0 A6 Forecast of Cost at Completion P 3.0 N/A 0.0 3 9.0 5 15.0 A7 Cost Estimate for Next Phase Work Scope P 3.0 5 15.0 5 15.0 5 15.0 Subtotal Cost 36.0 133.5 150.0 B1 Project Schedule H 7.5 1 7.5 4 30.0 5 37.5 B2 Major Milestones P 3.0 1 3.0 5 15.0 5 15.0 B3 Resource Loading P 3.0 1 3.0 4 12.0 5 15.0 B4 Critical Path Management H 7.5 1 7.5 4 30.0 5 37.5 B5 Schedule Risk/Contingency Analysis P 3.0 1 3.0 5 15.0 5 15.0 B6 Forecast of Schedule Completion P 3.0 N/A 0.0 3 9.0 5 15.0 B7 Schedule for Next Phase Work Scope P 3.0 5 15.0 5 15.0 5 15.0 Subtotal Schedule

2

Major Risk Factors Integrated Facility Disposition Project -...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

- Oak Ridge Summary - Major Risk Factors Integrated Facility Disposition Project (IFDP) Oak Ridge, TN More Documents & Publications Major Risk Factors to the Integrated...

3

Major Risk Factors to the Integrated Facility Disposition Project...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Facility Disposition Project The scope of the Integrated Facility Disposition Project (IFDP) needs to comprehensively address a wide range of environmental management risks at the...

4

Assessment of the Integrated Facility Disposition Project at Oak Ridge  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Assessment of the Integrated Facility Disposition Project at Oak Assessment of the Integrated Facility Disposition Project at Oak Ridge National Laboratory & Y-12 for Transfer of Facilities & Materials to EM Assessment of the Integrated Facility Disposition Project at Oak Ridge National Laboratory & Y-12 for Transfer of Facilities & Materials to EM In December 2007, the Assistant Secretary for Environmental Management (EM-1) invited the DOE Program Secretarial Offices (PSOs) of Nuclear Energy (NE), Science (SC), and the National Nuclear Security Administration (NNSA) to propose facilities and legacy waste for transfer to Environmental Management (EM) for final disposition or deactivation and decommissioning (D&D). Assessment of the Integrated Facility Disposition Project at Oak Ridge National Laboratory & Y-12 for Transfer of Facilities & Materials to EM

5

Assessment of the Integrated Facility Disposition Project at Oak Ridge  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

the Integrated Facility Disposition Project at Oak the Integrated Facility Disposition Project at Oak Ridge National Laboratory & Y-12 for Transfer of Facilities & Materials to EM Assessment of the Integrated Facility Disposition Project at Oak Ridge National Laboratory & Y-12 for Transfer of Facilities & Materials to EM In December 2007, the Assistant Secretary for Environmental Management (EM-1) invited the DOE Program Secretarial Offices (PSOs) of Nuclear Energy (NE), Science (SC), and the National Nuclear Security Administration (NNSA) to propose facilities and legacy waste for transfer to Environmental Management (EM) for final disposition or deactivation and decommissioning (D&D). Assessment of the Integrated Facility Disposition Project at Oak Ridge National Laboratory & Y-12 for Transfer of Facilities & Materials to EM

6

Major Risk Factors to the Integrated Facility Disposition Project  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Oak Ridge Reservation Tennessee Major Risk Factors to the Integrated Facility Disposition Project (IFDP) Challenge The scope of the Integrated Facility Disposition Project (IFDP) needs to comprehensively address a wide range of environmental management risks at the Oak Ridge Reservation (ORO). These include: environmental remediation, regulatory compliance, deactivation and decommissioning (D&D) activities, and disposition of legacy materials and waste, along with the ongoing modernization, reindustrialization, and reconfiguration initiatives at the Oak Ridge National Laboratory and at the Y-12 National Security Complex. The balancing of the broad nature of these activities and issues at ORO are a key challenge for the IFDP especially since their interrelationship is not always obvious.

7

Major Risk Factors Integrated Facility Disposition Project -...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

(Treatment Alternatives For Process Wastewater at ORNL, ORNLCF-0603-R1, November 2007; HFIR and REDC Process Waste Drains and Waste Treatment Plant, ORNL Facilities Development...

8

Major Risk Factors Integrated Facility Disposition Project - Oak Ridge  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

O O O f f f f i i c c e e o o f f E E n n v v i i r r o o n n m m e e n n t t a a l l M M a a n n a a g g e e m m e e n n t t ( ( E E M M ) ) E E n n g g i i n n e e e e r r i i n n g g a a n n d d T T e e c c h h n n o o l l o o g g y y External Technical Review (ETR) Report Major Risk Factors Integrated Facility Disposition Project (IFDP) Oak Ridge, TN AUGUST 1, 2008 Acknowledgement The External Technical Review of the Integrated Facility Disposition Project was conducted simultaneous to other assessments and visits. The ETR Team wishes to note the outstanding support received from all parties involved in the review, including the DOE Oak Ridge Office, the National Nuclear Security Administration Y-12 Site Office, UT-Battelle, B&W Y-12, and the Professional Project Services, Inc. (Pro2Serve). The ETR Team feels compelled to note, and

9

Master EM Project Definition Rating Index - Facility Disposition Definitions  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

43 43 Master EM Project Definition Rating Index - Facility Disposition Definitions The following definitions describe the criteria required to achieve a maximum rating or maturity value of 5. It should be assumed that maturity values of 1-5 represent a subjective assessment of the quality of definition and/or the degree to which the end-state or maximum criteria have been met, or the product has been completed in accordance with the definition of maturity values. Rating Element Criteria for Maximum Rating COST A1 Cost Estimate A cost estimate has been developed and formally approved by DOE and is the basis for the cost baselines. The cost estimate is a reasonable approximation of Total Project Costs, and covers all phases of the project. The estimate is prepared in

10

Facility Disposition Safety Strategy RM  

Energy.gov (U.S. Department of Energy (DOE))

The Facility Disposition Safety Strategy (FDSS) Review Module is a tool that assists DOE federal project review teams in evaluating the adequacy of the facility documentation, preparations or...

11

Integrated Facilities Disposition Program  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Facilities Facilities Disposition Program Tank Waste Corporate Board Meeting at ORNL Sharon Robinson Dirk Van Hoesen Robert Jubin Brad Patton July 29, 2009 2 Managed by UT-Battelle for the U.S. Department of Energy The Integrated Facility Disposition Program (IFDP) addresses the remaining EM Scope at both ORNL and Y-12 Cost Range: $7 - $14B Schedule: 26 Years 3 Managed by UT-Battelle for the U.S. Department of Energy Scope of work * Treatment and disposition of legacy materials and waste * D&D 327 (1.5 M ft 2 ) excess facilities generating >2 M yd 3 debris * Soil and groundwater remedial actions generating >1 M yd 3 soils * Facilities surveillance and maintenance * Reconfiguration of waste management facilities * Ongoing waste management operations * Project management

12

Assessment of the Integrated Facility Disposition Project at Oak Ridge National Laboratory & Y-12 for Transfer of Facilities & Materials to EM  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Integrated Facilities Disposition Project Integrated Facilities Disposition Project Technical Assistance Page 1 of 2 Oak Ridge National Laboratory Y-12 National Security Complex Tennessee Tennessee Assessment of the Integrated Facility Disposition Project at ORNL & Y-12 for Transfer of Facilities & Materials to EM Challenge In December 2007, the Assistant Secretary for Environmental Management (EM-1) invited the DOE Program Secretarial Offices (PSOs) of Nuclear Energy (NE), Science (SC), and the National Nuclear Security Administration (NNSA) to propose facilities and legacy waste for transfer to Environmental Management (EM) for final disposition or deactivation and decommissioning (D&D). In parallel with the EM-1 initiative, the Oak Ridge Reservation was conducting a Critical

13

Summary - Major Risk Factors Integrated Facility Disposition...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

& ORNL, Oak Ridge, TN EM Project: Integrated Facility Disposition Project (IFDP) ETR Report Date: August 2008 ETR-15 United States Department of Energy Office of Environmental...

14

Review of the Facility Centered Assessment of the Los Alamos National Laboratory Waste Disposition Project, September 2011  

NLE Websites -- All DOE Office Websites (Extended Search)

Facility Centered Assessment of the Facility Centered Assessment of the Los Alamos National Laboratory Waste Disposition Project September 2011 Office of Safety and Emergency Management Evaluations Office of Health, Safety and Security U.S. Department of Energy Table of Contents 1.0 Introduction ............................................................................................................................ 1 2.0 Background ............................................................................................................................ 1 3.0 Results .................................................................................................................................... 2 4.0 Conclusions ............................................................................................................................ 7

15

Review of the Facility Centered Assessment of the Los Alamos National Laboratory Waste Disposition Project, September 2011  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Facility Centered Assessment of the Facility Centered Assessment of the Los Alamos National Laboratory Waste Disposition Project September 2011 Office of Safety and Emergency Management Evaluations Office of Health, Safety and Security U.S. Department of Energy Table of Contents 1.0 Introduction ............................................................................................................................ 1 2.0 Background ............................................................................................................................ 1 3.0 Results .................................................................................................................................... 2 4.0 Conclusions ............................................................................................................................ 7

16

Facility Disposition Safety Strategy RM  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Facility Disposition Safety Strategy Review Module Facility Disposition Safety Strategy Review Module March 2010 CD-0 O 0 OFFICE OF Facilit C CD-1 F ENVIRO Standard R ty Dispos Rev Critical Decis CD-2 M ONMENTAL Review Plan sition Saf view Module sion (CD) Ap CD March 2010 L MANAGE n (SRP) fety Strat e pplicability D-3 EMENT tegy CD-4 Post Ope eration Standard Review Plan, 2 nd Edition, March 2010 i FOREWORD The Standard Review Plan (SRP) 1 provides a consistent, predictable corporate review framework to ensure that issues and risks that could challenge the success of Office of Environmental Management (EM) projects are identified early and addressed proactively. The internal EM project review process encompasses key milestones established by DOE O 413.3A, Change 1, Program and Project Management for the Acquisition of Capital Assets, DOE-STD-1189-2008,

17

Mission Need Statement: Calcine Disposition Project Major Systems Acquisition Project  

SciTech Connect

This document identifies the need to establish the Calcine Disposition Project to determine and implement the final disposition of calcine including characterization, retrieval, treatment (if necessary), packaging, loading, onsite interim storage pending shipment to a repository or interim storage facility, and disposition of related facilities.

J. T. Beck

2007-04-26T23:59:59.000Z

18

IX disposition project, project management plan  

SciTech Connect

This subproject management plan defines the roles, responsibilities, and actions required for the execution of the IX Disposition Project.

WILLIAMS, N.H.

1999-05-11T23:59:59.000Z

19

SLUDGE TREATMENT PROJECT KOP DISPOSITION - THERMAL AND GAS ANALYSIS FOR THE COLD VACUUM DRYING FACILITY  

DOE Green Energy (OSTI)

The purpose of this document is to present conceptual design phase thermal process calculations that support the process design and process safety basis for the cold vacuum drying of K Basin KOP material. This document is intended to demonstrate that the conceptual approach: (1) Represents a workable process design that is suitable for development in preliminary design; and (2) Will support formal safety documentation to be prepared during the definitive design phase to establish an acceptable safety basis. The Sludge Treatment Project (STP) is responsible for the disposition of Knock Out Pot (KOP) sludge within the 105-K West (KW) Basin. KOP sludge consists of size segregated material (primarily canister particulate) from the fuel and scrap cleaning process used in the Spent Nuclear Fuel process at K Basin. The KOP sludge will be pre-treated to remove fines and some of the constituents containing chemically bound water, after which it is referred to as KOP material. The KOP material will then be loaded into a Multi-Canister Overpack (MCO), dried at the Cold Vacuum Drying Facility (CVDF) and stored in the Canister Storage Building (CSB). This process is patterned after the successful drying of 2100 metric tons of spent fuel, and uses the same facilities and much of the same equipment that was used for drying fuel and scrap. Table ES-l present similarities and differences between KOP material and fuel and between MCOs loaded with these materials. The potential content of bound water bearing constituents limits the mass ofKOP material in an MCO load to a fraction of that in an MCO containing fuel and scrap; however, the small particle size of the KOP material causes the surface area to be significantly higher. This relatively large reactive surface area represents an input to the KOP thermal calculations that is significantly different from the calculations for fuel MCOs. The conceptual design provides for a copper insert block that limits the volume available to receive KOP material, enhances heat conduction, and functions as a heat source and sink during drying operations. This use of the copper insert represents a significant change to the thermal model compared to that used for the fuel calculations. A number of cases were run representing a spectrum of normal and upset conditions for the drying process. Dozens of cases have been run on cold vacuum drying of fuel MCOs. Analysis of these previous calculations identified four cases that provide a solid basis for judgments on the behavior of MCO in drying operations. These four cases are: (1) Normal Process; (2) Degraded vacuum pumping; (3) Open MCO with loss of annulus water; and (4) Cool down after vacuum drying. The four cases were run for two sets of input parameters for KOP MCOs: (1) a set of parameters drawn from safety basis values from the technical data book and (2) a sensitivity set using parameters selected to evaluate the impact of lower void volume and smaller particle size on MCO behavior. Results of the calculations for the drying phase cases are shown in Table ES-2. Cases using data book safety basis values showed dry out in 9.7 hours and heat rejection sufficient to hold temperature rise to less than 25 C. Sensitivity cases which included unrealistically small particle sizes and corresponding high reactive surface area showed higher temperature increases that were limited by water consumption. In this document and in the attachment (Apthorpe, R. and M.G. Plys, 2010) cases using Technical Databook safety basis values are referred to as nominal cases. In future calculations such cases will be called safety basis cases. Also in these documents cases using parameters that are less favorable to acceptable performance than databook safety values are referred to as safety cases. In future calculations such cases will be called sensitivity cases or sensitivity evaluations Calculations to be performed in support of the detailed design and formal safety basis documentation will expand the calculations presented in this document to include: additional features of th

SWENSON JA; CROWE RD; APTHORPE R; PLYS MG

2010-03-09T23:59:59.000Z

20

Uranium Downblending and Disposition Project Technology Readiness...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Simulated Operational Environment Environment that uses a range of waste simulants for testing of a virtual prototype. iv 233 Uranium Downblending and Disposition Project...

Note: This page contains sample records for the topic "facility disposition project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


21

Uranium Downblending and Disposition Project Technology Readiness...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Centers Field Sites Power Marketing Administration Other Agencies You are here Home Uranium Downblending and Disposition Project Technology Readiness Assessment Uranium...

22

Savannah River Site Waste Disposition Project  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Terrel J. Spears Terrel J. Spears Assistant Manager Waste Disposition Project DOE Savannah River Operations Office Savannah River Site Savannah River Site Waste Disposition Project Waste Disposition Project 2 Waste Disposition Project - Mission Radioactive Liquid Waste - Tank Waste Stabilization and Disposition - Disposition 36 million gallons of radioactive liquid waste - Close 49 underground storage tanks in which the waste now resides 3 36.7 Million 33.7 Mgal (92%) 3.0 Mgal (8%) Saltcake Sludge Salt Supernate Volume Curies 397 Million Curies (MCi) 212 MCi (54%) 185 MCi (46%) Gallons (Mgal) 36.5 Million 33.5 Mgal (92%) 3.0 Mgal (8%) Liquid Waste Background Liquid Waste Background * 2 tanks closed * 49 tanks remaining to close - aging, carbon steel - 27 compliant, 22 non-compliant - 12 have known leak sites

23

Hight-Level Waste & Facilities Disposition  

NLE Websites -- All DOE Office Websites (Extended Search)

High-Level Waste (HLW) and Facilities Disposition Final High-Level Waste (HLW) and Facilities Disposition Final Environmental Impact Statement You are here: DOE-ID Home > Environmental Management > Idaho High-Level Waste (HLW) Table of Contents Documents are in the Adobe® PDF format and require the Adobe® Reader to access them. If you do not currently have the Acrobat Reader, you can download the Free Adobe Reader at http://get.adobe.com/reader/ Icon link to Free Adobe Acrobat Reader software * Large chapters broken down into sections Summary* Cover [ Adobe Acrobat File Size 1.48 MB] Section, 1.0 [ Adobe Acrobat File Size 612 KB] Section, 2.0 [ Adobe Acrobat File Size 251 KB] Sections, 3.0 - 3.2.1a [ Adobe Acrobat File Size 1.4 MB] Section, 3.2.1b [ Adobe Acrobat File Size 2.0 MB] Sections, 3.2.2 - 4.0 [ Adobe Acrobat File Size 1.4 MB]

24

RECORDS DISPOSITION SCHEDULE: Year 2000 Project Records | Department...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Year 2000 Project Records RECORDS DISPOSITION SCHEDULE: Year 2000 Project Records Year 2000 (Y2K) Project records have been created to document the effort of the Department...

25

EIS-0287: Idaho High-Level Waste and Facilities Disposition Final...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Idaho High-Level Waste and Facilities Disposition Final Environmental Impact Statement, EIS-0287 (September 2002) EIS-0287: Idaho High-Level Waste and Facilities Disposition Final...

26

West Valley Demonstration Project Phase I Decommissioning - Facility  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Project Phase I Decommissioning - Project Phase I Decommissioning - Facility Disposition Partnering Performance Agreement West Valley Demonstration Project Phase I Decommissioning - Facility Disposition Partnering Performance Agreement The Department of Energy, West Valley Demonstration Project (DOE-WVDP) and CH2M Hill B&W West Valley (CHBWV) are committed to continuous improvement and will utilize principles of the DOE Environmental Management (DOE-EM) Partnering Policy to create and foster a team environment to successfully complete the West Valley Demonstration Project (WVDP) Phase I Decommissioning - Faciltiy Disposition. West Valley Demonstration Project Phase I Decommissioning - Facility Disposition Partnering Performance Agreement More Documents & Publications CX-009527: Categorical Exclusion Determination

27

IX Disposition Project - project management plan  

SciTech Connect

This report presents plans for resolving saving and disposal concerns for ion exchange modules, cartridge filters and columns. This plan also documents the project baselines for schedules, cost, and technical information.

Choi, I.G.

1994-12-08T23:59:59.000Z

28

WASTE DISPOSITION PROJECT MAKES GREAT STRIDES AT THE IDAHO SITE |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

WASTE DISPOSITION PROJECT MAKES GREAT STRIDES AT THE IDAHO SITE WASTE DISPOSITION PROJECT MAKES GREAT STRIDES AT THE IDAHO SITE WASTE DISPOSITION PROJECT MAKES GREAT STRIDES AT THE IDAHO SITE April 1, 2010 - 12:00pm Addthis An operator uses robotic manipulators to process RH TRU. An operator uses robotic manipulators to process RH TRU. Idaho - The Waste Disposition Project Team at the Department of Energy's Idaho Site has continued to keep its commitment to remove remote handled (RH) transuranic (TRU) waste out of Idaho, protecting the Snake River Plain Aquifer and keeping the Office of Environmental Management's commitment to environmental clean up. In 2007, the first shipment of RH TRU waste left the gates of the Idaho Site, headed to the Waste Isolation Pilot Plant (WIPP) for disposal. In the three years since, devoted individuals on the CH2M-WG, Idaho's (CWI)

29

WASTE DISPOSITION PROJECT MAKES GREAT STRIDES AT THE IDAHO SITE |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

WASTE DISPOSITION PROJECT MAKES GREAT STRIDES AT THE IDAHO SITE WASTE DISPOSITION PROJECT MAKES GREAT STRIDES AT THE IDAHO SITE WASTE DISPOSITION PROJECT MAKES GREAT STRIDES AT THE IDAHO SITE April 1, 2010 - 12:00pm Addthis An operator uses robotic manipulators to process RH TRU. An operator uses robotic manipulators to process RH TRU. Idaho - The Waste Disposition Project Team at the Department of Energy's Idaho Site has continued to keep its commitment to remove remote handled (RH) transuranic (TRU) waste out of Idaho, protecting the Snake River Plain Aquifer and keeping the Office of Environmental Management's commitment to environmental clean up. In 2007, the first shipment of RH TRU waste left the gates of the Idaho Site, headed to the Waste Isolation Pilot Plant (WIPP) for disposal. In the three years since, devoted individuals on the CH2M-WG, Idaho's (CWI)

30

DOE 2010 Safety and Security Reform Project - HSS Directives Disposition and Status (December 4, 2012)  

NLE Websites -- All DOE Office Websites (Extended Search)

10 Safety and Security Reform Project - HSS Directives Disposition and Status (December 4, 2012) 10 Safety and Security Reform Project - HSS Directives Disposition and Status (December 4, 2012) Page 1 of 3 2010 HSS Directives Disposition Status Secretary of Energy Notice SEN-35-91, Nuclear Safety Policy Revise Complete - see Policy 420.1. Order 5400.5, Radiation Protection of the Public and the Environment Revise Complete - see Order 458.1. Order 5480.19, Conduct of Operations Requirements for DOE Facilities Revise Complete - see Order 422.1. Order 5480.20A, Personnel Selection, Training, Qualification, and Certification Requirements Revise Complete - see Order 426.2. Order 5480.30, Nuclear Reactor Design Criteria Re-certify Complete - re-certified. Manual 140.1-1B, Interface with the Defense Nuclear Facilities Safety Board Re-certify Complete - re-certified.

31

Site Selection for Surplus Plutonium Disposition Facilities at the Savannah River Site  

Science Conference Proceedings (OSTI)

A site selection study was conducted to evaluate locations for the proposed Surplus Plutonium Disposition Facilities. Facilities to be located include the Mixed Oxide (MOX) Fuel Fabrication Facility, the Pit Disassembly and Conversion Facility (PDCF), and the Plutonium Immobilization Project (PIP) facility. Objectives of the study include: (1) Confirm that the Department of Energy (DOE) selected locations for the MOX and PDCF were suitable based on selected siting criteria, (2) Recommend a site in the vicinity of F Area that is suitable for the PIP, and (3) Identify alternative suitable sites for one or more of these facilities in the event that further geotechnical characterization or other considerations result in disqualification of a currently proposed site.

Wike, L.D.

2000-08-17T23:59:59.000Z

32

DOE standard: Integration of environment, safety, and health into facility disposition activities. Volume 2: Appendices  

SciTech Connect

This volume contains the appendices that provide additional environment, safety, and health (ES and H) information to complement Volume 1 of this Standard. Appendix A provides a set of candidate DOE ES and H directives and external regulations, organized by hazard types that may be used to identify potentially applicable directives to a specific facility disposition activity. Appendix B offers examples and lessons learned that illustrate implementation of ES and H approaches discussed in Section 3 of Volume 1. Appendix C contains ISMS performance expectations to guide a project team in developing and implementing an effective ISMS and in developing specific performance criteria for use in facility disposition. Appendix D provides guidance for identifying potential Applicable or Relevant and Appropriate Requirements (ARARs) when decommissioning facilities fall under the Comprehensive Environmental Response, Compensation, Liability Act (CERCLA) process. Appendix E discusses ES and H considerations for dispositioning facilities by privatization. Appendix F is an overview of the WSS process. Appendix G provides a copy of two DOE Office of Nuclear Safety Policy and Standards memoranda that form the bases for some of the guidance discussed within the Standard. Appendix H gives information on available hazard analysis techniques and references. Appendix I provides a supplemental discussion to Sections 3.3.4, Hazard Baseline Documentation, and 3.3.6, Environmental Permits. Appendix J presents a sample readiness evaluation checklist.

NONE

1998-05-01T23:59:59.000Z

33

Joel Case Calcine Disposition Project Federal Project Director  

Results in large life-cycle cost savings through final disposition. 6 6 Basic Hot Isostatic Pressing Process ... nuclear fuel in 1964.

34

Site Selection for Surplus Plutonium Disposition Facilities at the Savannah River Site  

Science Conference Proceedings (OSTI)

The purpose of this study is to identify, assess, and rank potential sites for the proposed Surplus Plutonium Disposition Facilities complex at the Savannah River Site.

Wike, L.D.

2000-12-13T23:59:59.000Z

35

EIS-0287: Idaho High-Level Waste and Facilities Disposition Final  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Idaho High-Level Waste and Facilities Disposition Final Idaho High-Level Waste and Facilities Disposition Final Environmental Impact Statement, EIS-0287 (September 2002) EIS-0287: Idaho High-Level Waste and Facilities Disposition Final Environmental Impact Statement, EIS-0287 (September 2002) This EIS analyzes the potential environmental consequences of alternatives for managing high-level waste (HLW) calcine, mixed transuranic waste/sodium bearing waste (SBW) and newly generated liquid waste at the Idaho National Engineering and Environmental Laboratory (INEEL) in liquid and solid forms. This EIS also analyzes alternatives for the final disposition of HLW management facilities at the INEEL after their missions are completed. Idaho High-Level Waste and Facilities Disposition Final Environmental Impact Statement, DOE/EIS-0287 (September 2002)

36

EIS-0287: Idaho High-Level Waste & Facilities Disposition | Department of  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

7: Idaho High-Level Waste & Facilities Disposition 7: Idaho High-Level Waste & Facilities Disposition EIS-0287: Idaho High-Level Waste & Facilities Disposition SUMMARY This EIS analyzes the potential environmental consequences of alternatives for managing high-level waste (HLW) calcine, mixed transuranic waste/sodium bearing waste (SBW) and newly generated liquid waste at the Idaho National Engineering and Environmental Laboratory (INEEL) in liquid and solid forms. This EIS also analyzes alternatives for the final disposition of HLW management facilities at the INEEL after their missions are completed. PUBLIC COMMENT OPPORTUNITIES None available at this time. DOCUMENTS AVAILABLE FOR DOWNLOAD January 12, 2010 EIS-0287: Amended Record of Decision Idaho High-Level Waste and Facilities Disposition January 4, 2010

37

EA-1410: Proposed Disposition of the Omega West Facility at Los Alamos  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

10: Proposed Disposition of the Omega West Facility at Los 10: Proposed Disposition of the Omega West Facility at Los Alamos National Laboratory, Los Alamos, New Mexico EA-1410: Proposed Disposition of the Omega West Facility at Los Alamos National Laboratory, Los Alamos, New Mexico SUMMARY This EA evaluates the environmental impacts for the proposal to remove the Omega West Facility and the remaining support structures from Los Alamos Canyon at the U.S. Department of Energy Los Alamos National Laboratory in Los Alamos, New Mexico. PUBLIC COMMENT OPPORTUNITIES None available at this time. DOCUMENTS AVAILABLE FOR DOWNLOAD March 28, 2002 EA-1410: Finding of No Significant Impact Proposed Disposition of the Omega West Facility at Los Alamos National Laboratory, Los Alamos, New Mexico March 28, 2002 EA-1410: Final Environmental Assessment

38

Summary - Uranium233 Downblending and Disposition Project  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Product Product EM wa in Buil to extr from 23 downb mitigat concer dispos downb WIPP condu the "ba allowin assess techno The as Techn Techn * An * C (T * Pr * O The Ele Site: O roject: 2 P Report Date: S ited States 233 Ura Why DOE t Packaging Syste as directed to t ding 3019 at O ract 229 Th (an is 33 U. The missi blend the inven te security and rns and prepar sal. The projec blended materia or the Nevada cted to coincid ack-end" of the ng observation sment team to ology maturity p What th ssessment team ology Element ology Readine nalytical Labor oncentration p TRL=4) roduct Packag ffgas Treatmen To view the full T http://www.em.doe. objective of a Tech ements (CTEs), usin Oak Ridge/OR 233 Uranium Do Project September 20 Departmen anium D E-EM Did This em and Interfaces ake ownership Oak Ridge that sotope used in

39

DOE standard: Integration of environment, safety, and health into facility disposition activities. Volume 1: Technical standard  

Science Conference Proceedings (OSTI)

This Department of Energy (DOE) technical standard (referred to as the Standard) provides guidance for integrating and enhancing worker, public, and environmental protection during facility disposition activities. It provides environment, safety, and health (ES and H) guidance to supplement the project management requirements and associated guidelines contained within DOE O 430.1A, Life-Cycle Asset Management (LCAM), and amplified within the corresponding implementation guides. In addition, the Standard is designed to support an Integrated Safety Management System (ISMS), consistent with the guiding principles and core functions contained in DOE P 450.4, Safety Management System Policy, and discussed in DOE G 450.4-1, Integrated Safety Management System Guide. The ISMS guiding principles represent the fundamental policies that guide the safe accomplishment of work and include: (1) line management responsibility for safety; (2) clear roles and responsibilities; (3) competence commensurate with responsibilities; (4) balanced priorities; (5) identification of safety standards and requirements; (6) hazard controls tailored to work being performed; and (7) operations authorization. This Standard specifically addresses the implementation of the above ISMS principles four through seven, as applied to facility disposition activities.

NONE

1998-05-01T23:59:59.000Z

40

DOE-STD-1120-2005; Integration of Environment Safety and Health into Facility Disposition Activities  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

20-2005 20-2005 Volume 1 of 2 April 2005 DOE STANDARD INTEGRATION OF ENVIRONMENT, SAFETY, AND HEALTH INTO FACILITY DISPOSITION ACTIVITIES Volume 1 of 2: Documented Safety Analysis for Decommissioning and Environmental Restoration Projects U.S. Department of Energy AREA SAFT Washington, D.C. 20585 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited. NOT MEASUREMENT SENSITIVE TS i This document has been reproduced directly from the best available copy. Available to DOE and DOE contractors from the Office of Scientific and Technical Information, P.O. Box 62, Oak Ridge, TN 37831; (423) 576-8401. Available to the public from the U.S. Department of Commerce, Technology Administration, National Technical Information Service, Springfield, VA 22161; (703) 605-6000.

Note: This page contains sample records for the topic "facility disposition project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


41

DOE G 430.1-2, Implementation Guide for Surveillance and Maintenance during Facility Transition and Disposition  

Directives, Delegations, and Requirements

As DOE facilities complete mission operations and are declared excess, they pass into a transition phase that ultimately prepares them for disposition. The ...

1999-09-29T23:59:59.000Z

42

THE NGA-DOE GRANT TO EXAMINE CRITICAL ISSUES RELATED TO RADIOACTIVE WASTE AND MATERIALS DISPOSITION INVOLVING DOE FACILITIES  

Science Conference Proceedings (OSTI)

Through the National Governors' Association (NGA) project ''Critical Issues Related to Radioactive Waste and Materials Disposition Involving DOE Facilities'' NGA brings together Governors' policy advisors, state regulators, and DOE officials to examine critical issues related to the cleanup and operation of DOE nuclear weapons and research facilities. Topics explored through this project include: Decisions involving disposal of mixed, low-level, and transuranic (TRU) waste and disposition of nuclear materials. Decisions involving DOE budget requests and their effect on environmental cleanup and compliance at DOE facilities. Strategies to treat mixed, low-level, and transuranic (TRU) waste and their effect on individual sites in the complex. Changes to the FFCA site treatment plans as a result of proposals in the Department's Accelerating Cleanup: Paths to Closure plan and contractor integration analysis. Interstate waste and materials shipments. Reforms to existing RCRA and CERCLA regulations/guidance to address regulatory overlap and risks posed by DOE wastes. The overarching theme of this project is to help the Department improve coordination of its major program decisions with Governors' offices and state regulators and to ensure such decisions reflect input from these key state officials and stakeholders. This report summarizes activities conducted during the period from April 1, 2001 through June 30, 2001, under the NGA grant.

Ethan W. Brown

2001-09-01T23:59:59.000Z

43

THE NGA-DOE GRANT TO EXAMINE CRITICAL ISSUES RELATED TO RADIOACTIVE WASTE AND MATERIALS DISPOSITION INVOLVING DOE FACILITIES  

SciTech Connect

Through the National Governors' Association (NGA) project ''Critical Issues Related to Radioactive Waste and Materials Disposition Involving DOE Facilities'' NGA brings together Governors' policy advisors, state regulators, and DOE officials to examine critical issues related to the cleanup and operation of DOE nuclear weapons and research facilities. Topics explored through this project include: Decisions involving disposal of mixed, low-level, and transuranic (TRU) waste and disposition of nuclear materials. Decisions involving DOE budget requests and their effect on environmental cleanup and compliance at DOE facilities. Strategies to treat mixed, low-level, and transuranic (TRU) waste and their effect on individual sites in the complex. Changes to the FFCA site treatment plans as a result of proposals in DOE's Accelerating Cleanup: Paths to Closure strategy and contractor integration analysis. Interstate waste and materials shipments. Reforms to existing RCRA and CERCLA regulations/guidance to address regulatory overlap and risks posed by DOE wastes. The overarching theme of this project is to help the Department improve coordination of its major program decisions with Governors' offices and state regulators and to ensure such decisions reflect input from these key state officials and stakeholders. This report summarizes activities conducted during the quarter from December 31, 1997 through April 30, 1998 under the NGA project. The work accomplished by the NGA project team during the past four months can be categorized as follows: maintained open communication with DOE on a variety of activities and issues within the DOE environmental management complex; and provided ongoing support to state-DOE interactions in preparation for the March 30-31, 1998 NGA Federal Facilities Compliance Task Force Meeting with DOE. maintained communication with NGA Federal Facilities Compliance Task Force members regarding DOE efforts to formulate a configuration for mixed low-level waste and low-level treatment and disposal, DOE's Environmental Management Budget, and DOE's proposed Intersite Discussions.

NONE

1998-04-01T23:59:59.000Z

44

Cost-effective facility disposition planning with safety and health lessons learned and good practices from the Oak Ridge Decontamination and Decommissioning Program  

SciTech Connect

An emphasis on transition and safe disposition of DOE excess facilities has brought about significant challenges to managing worker, public, and environmental risks. The transition and disposition activities involve a diverse range of hazardous facilities that are old, poorly maintained, and contain radioactive and hazardous substances, the extent of which may be unknown. In addition, many excess facilities do not have historical facility documents such as operating records, plant and instrumentation diagrams, and incident records. The purpose of this report is to present an overview of the Oak Ridge Decontamination and Decommissioning (D and D) Program, its safety performance, and associated safety and health lessons learned and good practices. Illustrative examples of these lessons learned and good practices are also provided. The primary focus of this report is on the safety and health activities and implications associated with the planning phase of Oak Ridge facility disposition projects. Section 1.0 of this report provides the background and purpose of the report. Section 2.0 presents an overview of the facility disposition activities from which the lessons learned and good practices discussed in Section 3.0 were derived.

NONE

1998-05-01T23:59:59.000Z

45

THE NGA-DOE GRANT TO EXAMINE CRITICAL ISSUES RELATED TO RADIOACTIVE WASTE AND MATERIALS DISPOSITION INVOLVING DOE FACILITIES  

Science Conference Proceedings (OSTI)

Through the National Governors' Association (NGA) project ''Critical Issues Related to Radioactive Waste and Materials Disposition Involving DOE Facilities'' NGA brings together Governors' policy advisors, state regulators, and DOE officials to examine critical issues related to the cleanup and operation of DOE nuclear weapons and research facilities. Topics explored through this project include: Decisions involving disposal of mixed, low-level, and transuranic (TRU) waste and disposition of nuclear materials. Decisions involving DOE budget requests and their effect on environmental cleanup and compliance at DOE facilities. Strategies to treat mixed, low-level, and transuranic (TRU) waste and their effect on individual sites in the complex. Changes to the FFCA site treatment plans as a result of proposals in DOE's Accelerating Cleanup: Paths to Closure strategy and contractor integration analysis. Interstate waste and materials shipments. Reforms to existing RCRA and CERCLA regulations/guidance to address regulatory overlap and risks posed by DOE wastes. The overarching theme of this project is to help the Department improve coordination of its major program decisions with Governors' offices and state regulators and to ensure such decisions reflect input from these key state officials and stakeholders. This report summarizes activities conducted during the quarter from April 30, 1998 through June 30, 1998 under the NGA project. The work accomplished by the NGA project team during the past four months can be categorized as follows: maintained open communication with DOE on a variety of activities and issues within the DOE environmental management complex; and provided ongoing support to state-DOE interactions. maintained communication with NGA Federal Facilities Compliance Task Force members regarding DOE efforts to formulate a configuration for mixed low-level waste and low-level treatment and disposal, DOE's Environmental Management Budget, and DOE's proposed Intersite Discussions.

NONE

1998-07-01T23:59:59.000Z

46

Alternatives for the disposition of fuel stored in the PUREX facility  

SciTech Connect

This document provides an evaluation of five alternatives for the disposition of 3.4 metric tons of irradiated fuel from PUREX to support facility turnover following deactivation. The alternatives for disposition of the fuel include transfer to the K Basins, transfer to T Plant, passivation and dry vault storage, and dissolution and underground tank storage. The five alternatives were compared and it was determined that the fuel should be transferred from PUREX to the K Basins where it would be placed into pool storage.

Enghusen, M.B.; Gore, D.B.

1995-01-01T23:59:59.000Z

47

THE NGA-DOE GRANT TO EXAMINE CRITICAL ISSUES RELATED TO RADIOACTIVE WASTE AND MATERIALS DISPOSITION INVOLVING DOE FACILITIES  

SciTech Connect

Through the National Governors' Association (NGA) project ''Critical Issues Related to Radioactive Waste and Materials Disposition Involving DOE Facilities'' NGA brings together Governors' policy advisors, state regulators, and DOE officials to examine critical issues related to the cleanup and operation of DOE nuclear weapons and research facilities. Topics explored through this project include: Decisions involving disposal of mixed, low-level, and transuranic (TRU) waste and disposition of nuclear materials; Decisions involving DOE budget requests and their effect on environmental cleanup and compliance at DOE facilities; Strategies to treat mixed, low-level, and transuranic (TRU) waste and their effect on individual sites in the complex; Changes to the FFCA site treatment plans as a result of proposals in the Department's Accelerating Cleanup: Paths to Closure plan and contractor integration analysis; Interstate waste and materials shipments; and Reforms to existing RCRA and CERCLA regulations/guidance to address regulatory overlap and risks posed by DOE wastes. The overarching theme of this project is to help the Department improve coordination of its major program decisions with Governors' offices and state regulators and to ensure such decisions reflect input from these key state officials and stakeholders. This report summarizes activities conducted during the quarter from May 1, 1999, through July 30, 1999, under the NGA grant. The work accomplished by the NGA project team during the past four months can be categorized as follows: maintained open communication with DOE on a variety of activities and issues within the DOE environmental management complex; maintained communication with NGA Federal Facilities Compliance Task Force members regarding DOE efforts to formulate a configuration for mixed low-level waste and low-level treatment and disposal, external regulation of DOE; and continued to facilitate interactions between the states and DOE to develop a foundation for an ongoing substantive relationship between the Governors of key states and Secretary Richardson.

Ann M. Beauchesne

1999-07-30T23:59:59.000Z

48

THE NGA-DOE GRANT TO EXAMINE CRITICAL ISSUES RELATED TO RADIOACTIVE WASTE AND MATERIALS DISPOSITION INVOLVING DOE FACILITIES  

Science Conference Proceedings (OSTI)

Through the National Governors' Association (NGA) project ''Critical Issues Related to Radioactive Waste and Materials Disposition Involving DOE Facilities'' NGA brings together Governors' policy advisors, state regulators, and DOE officials to examine critical issues related to the cleanup and operation of DOE nuclear weapons and research facilities. Topics explored through this project include: Decisions involving disposal of mixed, low-level, and transuranic (TRU) waste and disposition of nuclear materials; Decisions involving DOE budget requests and their effect on environmental cleanup and compliance at DOE facilities; Strategies to treat mixed, low-level, and transuranic (TRU) waste and their effect on individual sites in the complex; Changes to the FFCA site treatment plans as a result of proposals in the Department's Accelerating Cleanup: Paths to Closure plan and contractor integration analysis; Interstate waste and materials shipments; and Reforms to existing RCRA and CERCLA regulations/guidance to address regulatory overlap and risks posed by DOE wastes. The overarching theme of this project is to help the Department improve coordination of its major program decisions with Governors' offices and state regulators and to ensure such decisions reflect input from these key state officials and stakeholders. This report summarizes activities conducted during the quarter from February 1, 1999, through April 30, 1999, under the NGA grant. The work accomplished by the NGA project team during the past four months can be categorized as follows: maintained open communication with DOE on a variety of activities and issues within the DOE environmental management complex; maintained communication with NGA Federal Facilities Compliance Task Force members regarding DOE efforts to formulate a configuration for mixed low-level waste and low-level treatment and disposal, external regulation of DOE; and EM Integration activities; and continued to serve as a liaison between the NGA FFCA Task Force states and the Department.

Ann M. Beauchesne

1999-04-30T23:59:59.000Z

49

THE NGA-DOE GRANT TO EXAMINE CRITICAL ISSUES RELATED TO RADIOACTIVE WASTE AND MATERIALS DISPOSITION INVOLVING DOE FACILITIES  

SciTech Connect

Through the National Governors Association (NGA) project ``Critical Issues Related to Radioactive Waste and Materials Disposition Involving DOE Facilities'' NGA brings together Governors' policy advisors, state regulators, and DOE officials to examine critical issues related to the cleanup and operation of DOE nuclear weapons and research facilities. Topics explored through this project include: Decisions involving disposal of mixed, low-level, and transuranic (TRU) waste and disposition of nuclear materials; Decisions involving DOE budget requests and their effect on environmental cleanup and compliance at DOE facilities; Strategies to treat mixed, low-level, and transuranic (TRU) waste and their effect on individual sites in the complex; Changes to the FFCA site treatment plans as a result of proposals in the Department's Accelerating Cleanup: Paths to Closure plan and contractor integration analysis; Interstate waste and materials shipments; and Reforms to existing RCRA and CERCLA regulations/guidance to address regulatory overlap and risks posed by DOE wastes. The overarching theme of this project is to help the Department improve coordination of its major program decisions with Governors' offices and state regulators and to ensure such decisions reflect input from these key state officials and stakeholders. This report summarizes activities conducted during the period from October 1, 1999 through January 31, 2000, under the NGA grant. The work accomplished by the NGA project team during the past three months can be categorized as follows: maintained open communication with DOE on a variety of activities and issues within the DOE environmental management complex; convened and facilitated the October 6--8 NGA FFCA Task Force Meeting in Oak Ridge, Tennessee; maintained communication with NGA Federal Facilities Compliance Task Force members regarding DOE efforts to formulate a configuration for mixed low-level waste and low-level treatment and disposal, external regulation of DOE; and continued to facilitate interactions between the states and DOE to develop a foundation for an ongoing substantive relationship between the Governors of key states and the Department.

Ann M. Beauchesne

2000-01-01T23:59:59.000Z

50

THE NGA-DOE GRANT TO EXAMINE CRITICAL ISSUES RELATED TO RADIOACTIVE WASTE AND MATERIALS DISPOSITION INVOLVING DOE FACILITIES  

Science Conference Proceedings (OSTI)

Through the National Governors' Association (NGA) project ''Critical Issues Related to Radioactive Waste and Materials Disposition Involving DOE Facilities'' NGA brings together Governors' policy advisors, state regulators, and DOE officials to examine critical issues related to the cleanup and operation of DOE nuclear weapons and research facilities. Topics explored through this project include: (1) Decisions involving disposal of mixed, low-level, and transuranic (TRU) waste and disposition of nuclear materials; (2) Decisions involving DOE budget requests and their effect on environmental cleanup and compliance at DOE facilities; (3) Strategies to treat mixed, low-level, and transuranic (TRU) waste and their effect on individual sites in the complex; (4) Changes to the FFCA site treatment plans as a result of proposals in the Department's Accelerating Cleanup: Paths to Closure plan and contractor integration analysis; (5) Interstate waste and materials shipments; and (6) Reforms to existing RCRA and CERCLA regulations/guidance to address regulatory overlap and risks posed by DOE wastes. The overarching theme of this project is to help the Department improve coordination of its major program decisions with Governors' offices and state regulators and to ensure such decisions reflect input from these key state officials and stakeholders. This report summarizes activities conducted during the quarter from October 1, 1998 through January 31, 1999, under the NGA grant. The work accomplished by the NGA project team during the past four months can be categorized as follows: (1) maintained open communication with DOE on a variety of activities and issues within the DOE environmental management complex; (2) maintained communication with NGA Federal Facilities Compliance Task Force members regarding DOE efforts to formulate a configuration for mixed low-level waste and low-level treatment and disposal, external regulation of DOE; and EM Integration activities; and (3) continued to serve as a liaison between the NGA FFCA Task Force states and the Department.

Ann M. Beauchesne

1999-01-31T23:59:59.000Z

51

THE NGA-DOE GRANT TO EXAMINE CRITICAL ISSUES RELATED TO RADIOACTIVE WASTE AND MATERIALS DISPOSITION INVOLVING DOE FACILITIES  

SciTech Connect

Through the National Governors' Association (NGA) project ''Critical Issues Related to Radioactive Waste and Materials Disposition Involving DOE Facilities'' NGA brings together Governors' policy advisors, state regulators, and DOE officials to examine critical issues related to the cleanup and operation of DOE nuclear weapons and research facilities. Topics explored through this project include: (1) Decisions involving disposal of mixed, low-level, and transuranic (TRU) waste and disposition of nuclear materials; (2) Decisions involving DOE budget requests and their effect on environmental cleanup and compliance at DOE facilities; (3) Strategies to treat mixed, low-level, and transuranic (TRU) waste and their effect on individual sites in the complex; (4) Changes to the FFCA site treatment plans as a result of proposals in the Department's Accelerating Cleanup: Paths to Closure plan and contractor integration analysis; (5) Interstate waste and materials shipments; and (6) Reforms to existing RCRA and CERCLA regulations/guidance to address regulatory overlap and risks posed by DOE wastes. The overarching theme of this project is to help the Department improve coordination of its major program decisions with Governors' offices and state regulators and to ensure such decisions reflect input from these key state officials and stakeholders. This report summarizes activities conducted during the quarter from June 1, 1998 through September 30, 1998, under the NGA grant. The work accomplished by the NGA project team during the past four months can be categorized as follows: (1) maintained open communication with DOE on a variety of activities and issues within the DOE environmental management complex; (2) maintained communication with NGA Federal Facilities Compliance Task Force members regarding DOE efforts to formulate a configuration for mixed low-level waste and low-level treatment and disposal, external regulation of DOE; and EM Integration activities; and (3) continued to serve as a liaison between the NGA FFCA Task Force states and the Department.

Ann B. Beauchesne

1998-09-30T23:59:59.000Z

52

Supplement Analysis for the Idaho High-Level Waste and Facilities Disposition Final Environmental Impact Statement  

Science Conference Proceedings (OSTI)

In October 2002, DOE issued the Idaho High-Level Waste and Facilities Disposition Final Environmental Impact Statement (Final EIS) (DOE 2002) that provided an analysis of the potential environmental consequences of alternatives/options for the management and disposition of Sodium Bearing Waste (SBW), High-Level Waste (HL W) calcine, and HLW facilities at the Idaho Nuclear Technology and Engineering Center (INTEC) located at the Idaho National Engineering and Environmental Laboratory (INEEL), now known as the Idaho National Laboratory (INL) and referred to hereafter as the Idaho Site. Subsequent to the issuance of the Final EIS, DOE included the requirement for treatment of SBW in the Request for Proposals for Environmental Management activities on the Idaho Site. The new Idaho Cleanup Project (ICP) Contractor identified Steam Reforming as their proposed method to treat SBW; a method analyzed in the Final EIS as an option to treat SBW. The proposed Steam Reforming process for SBW is the same as in the Final EIS for retrieval, treatment process, waste form and transportation for disposal. In addition, DOE has updated the characterization data for both the HLW Calcine (BBWI 2005a) and SBW (BBWI 2004 and BBWI 2005b) and identified two areas where new calculation methods are being used to determine health and safety impacts. Because of those changes, DOE has prepared this supplement analysis to determine whether there are ''substantial changes in the proposed action that are relevant to environmental concerns'' or ''significant new circumstances or information'' within the meaning of the Council of Environmental Quality and DOE National Environmental Policy Act (NEPA) Regulations (40 CFR 1502.9 (c) and 10 CFR 1021.314) that would require preparation of a Supplemental EIS. Specifically, this analysis is intended to determine if: (1) the Steam Reforming Option identified in the Final EIS adequately bounds impacts from the Steam Reforming Process proposed by the new ICP Contractor using the new characterization data, (2) the new characterization data is significantly different than the data presented in the Final EIS, (3) the new calculation methods present a significant change to the impacts described in the Final EIS, and (4) would the updated characterization data cause significant changes in the environmental impacts for the action alternatives/options presented in the Final EIS. There are no other aspects of the Final EIS that require additional review because DOE has not identified any additional new significant circumstances or information that would warrant such a review.

N /A

2005-06-30T23:59:59.000Z

53

Canastota Renewable Energy Facility Project  

SciTech Connect

The project was implemented at the Madison County Landfill located in the Town of Lincoln, Madison County, New York. Madison County has owned and operated the solid waste and recycling facilities at the Buyea Road site since 1974. At the onset of the project, the County owned and operated facilities there to include three separate landfills, a residential solid waste disposal and recycled material drop-off facility, a recycling facility and associated administrative, support and environmental control facilities. This putrescible waste undergoes anaerobic decomposition within the waste mass and generates landfill gas, which is approximately 50% methane. In order to recover this gas, the landfill was equipped with gas collection systems on both the east and west sides of Buyea Road which bring the gas to a central point for destruction. In order to derive a beneficial use from the collected landfill gases, the County decided to issue a Request for Proposals (RFP) for the future use of the generated gas.

Blake, Jillian; Hunt, Allen

2013-12-13T23:59:59.000Z

54

PROJECT STRATEGY FOR THE REMEDIATION AND DISPOSITION OF LEGACY TRANSURANIC WASTE AT THE SAVANNAH RIVER SITE, South Carolina, USA  

Science Conference Proceedings (OSTI)

This paper discusses the Savannah River Site Accelerated Transuranic (TRU) Waste Project that was initiated in April of 2009 to accelerate the disposition of remaining legacy transuranic waste at the site. An overview of the project execution strategy that was implemented is discussed along with the lessons learned, challenges and improvements to date associated with waste characterization, facility modifications, startup planning, and remediation activities. The legacy waste was generated from approximately 1970 through 1990 and originated both on site as well as at multiple US Department of Energy sites. Approximately two thirds of the waste was previously dispositioned from 2006 to 2008, with the remaining one third being the more hazardous waste due to its activity (curie content) and the plutonium isotope Pu-238 quantities in the waste. The project strategy is a phased approach beginning with the lower activity waste in existing facilities while upgrades are made to support remediation of the higher activity waste. Five waste remediation process lines will be used to support the full remediation efforts which involve receipt of the legacy waste container, removal of prohibited items, venting of containers, and resizing of contents to fit into current approved waste shipping containers. Modifications have been minimized to the extent possible to meet the accelerated goals and involve limited upgrades to address life safety requirements, radiological containment needs, and handling equipment for the larger waste containers. Upgrades are also in progress for implementation of the TRUPACT III for the shipment of Standard Large Boxes to the Waste Isolation Pilot Plant, the US TRU waste repository. The use of this larger shipping container is necessary for approximately 20% of the waste by volume due to limited size reduction capability. To date, approximately 25% of the waste has been dispositioned, and several improvements have been made to the overall processing plan as well as facility processing rates. These lessons learned, challenges, and improvements will be discussed to aid other sites in their efforts to conduct similar activities.

Rodriguez, M.

2010-12-17T23:59:59.000Z

55

Preliminary Technology Readiness Assessment (TRA) for the Calcine Disposition Project Volume 1 (CDP)  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

TECHNOLOGY READINESS ASSESSMENT TECHNOLOGY READINESS ASSESSMENT OF THE CALCINE DISPOSITION PROJECT VOLUME ONE Anthony F. Kluk Hoyt C. Johnson Clyde Phillip McGinnis Michael Rinker Steven L. Ross Herbert G. Sutter John Vienna February 2011 Prepared by the U.S. Department of Energy Washington, DC February 2011 ii This page intentionally left blank. Review of Calcine Disposition Project Self-Assessment of Technology Maturation iii SIGNATURES ____________________________________ ____________________________________ Anthony F. Kluk, Team Lead Date ____________________________________ ____________________________________ Hoyt C. Johnson Date ____________________________________ ____________________________________ Clyde Phillip McGinnis Date ____________________________________ ____________________________________

56

PROJECTIZING AN OPERATING NUCLEAR FACILITY  

SciTech Connect

This paper will discuss the evolution of an operations-based organization to a project-based organization to facilitate successful deactivation of a major nuclear facility. It will describe the plan used for scope definition, staff reorganization, method estimation, baseline schedule development, project management training, and results of this transformation. It is a story of leadership and teamwork, pride and success. Workers at the Savannah River Site's (SRS) F Canyon Complex (FCC) started with a challenge--take all the hazardous byproducts from nearly 50 years of operations in a major, first-of-its-kind nuclear complex and safely get rid of them, leaving the facility cold, dark, dry and ready for whatever end state is ultimately determined by the United States Department of Energy (DOE). And do it in four years, with a constantly changing workforce and steadily declining funding. The goal was to reduce the overall operating staff by 93% and budget by 94%. The facilities, F Canyon and its adjoined sister, FB Line, are located at SRS, a 310-square-mile nuclear reservation near Aiken, S.C., owned by DOE and managed by Washington Group International subsidiary Washington Savannah River Company (WSRC). These facilities were supported by more than 50 surrounding buildings, whose purpose was to provide support services during operations. The radiological, chemical and industrial hazards inventory in the old buildings was significant. The historical mission at F Canyon was to extract plutonium-239 and uranium-238 from irradiated spent nuclear fuel through chemical processing. FB Line's mission included conversion of plutonium solutions into metal, characterization, stabilization and packaging, and storage of both metal and oxide forms. The plutonium metal was sent to another DOE site for use in weapons. Deactivation in F Canyon began when chemical separations activities were completed in 2002, and a cross-functional project team concept was implemented to successfully accomplish deactivation. This concept had to allow for continued operations in FB Line until 2005, while providing distinct task-oriented teams for deactivation of the FCC. Facility workers, always the most knowledgeable about any facility, were integral parts of the project team. The team defined the scope, developed a bottoms-up estimate, reorganized personnel to designated project teams, and developed a baseline schedule with about 12,000 activities. Training was implemented to prepare the facility workers to use project management tools and concepts, which were to execute the project, coordinate activities and track progress. The project budget was estimated at $579 million. The team completed F Canyon and FB Line deactivation in August 2006, four months ahead of schedule and under budget.

Adams, N

2007-07-08T23:59:59.000Z

57

Evaluation of Possible Surrogates for Validation of the Oxidation Furnace for the Plutonium Disposition Project  

Science Conference Proceedings (OSTI)

The Plutonium Disposition project (PuD) is considering an alternative furnace design for direct metal oxidation (DMO) of plutonium metal to use as a feed for potential disposition routes. The proposed design will use a retort to oxidize the feed at temperatures up to 500 C. The atmosphere will be controlled using a metered mixture of oxygen, helium and argon to control the oxidation at approximately 400 torr. Since plutonium melts at 664 C, and may potentially react with retort material to form a lower melting point eutectic, the oxidation process will be controlled by metering the flow of oxygen to ensure that the bulk temperature of the material does not exceed this temperature. A batch processing time of <24 hours is desirable to meet anticipated furnace throughput requirements. The design project includes demonstration of concept in a small-scale demonstration test (i.e., small scale) and validation of design in a full-scale test. These tests are recommended to be performed using Pu surrogates due to challenges in consideration of the nature of plutonium and operational constraints required when handling large quantities of accountable material. The potential for spreading contamination and exposing workers to harmful levels of cumulative radioactive dose are motivation to utilize non-radioactive surrogates. Once the design is demonstrated and optimized, implementation would take place in a facility designed to accommodate these constraints. Until then, the use of surrogates would be a safer, less expensive option for the validation phase of the project. This report examines the potential for use of surrogates in the demonstration and validation of the DMO furnace for PuD. This report provides a compilation of the technical information and process requirements for the conversion of plutonium metal to oxide by burning in dry environments. Several potential surrogates were evaluated by various criteria in order to select a suitable candidate for large scale demonstration. First, the structure of the plutonium metal/oxide interface was compared to potential surrogates. Second the data for plutonium oxidation kinetics were reviewed and rates for oxidation were compared with surrogates. The criteria used as a basis for recommendation was selected in order to provide a reasonable oxidation rate during the validation phase. Several reference documents were reviewed and used to compile the information in this report. Since oxidation of large monolithic pieces of plutonium in 75% oxygen is the preferable oxidizing atmosphere for the intended process, this report does not focus on the oxidation of powders, but focuses instead on larger samples in flowing gas.

Duncan, A.

2007-12-31T23:59:59.000Z

58

Summary - Preliminary TRA of the Calcine Disposition Project  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Calcine The Id materi Dec. 2 Press additiv form w those project anticip 2012 a CD-1 a selecte Level ( assess Eleme assign prepar The as below achiev * R * Ba * C The Ele Site: I...

59

DOE/EA-1651: FINDING OF NO SIGNIFICANT IMPACT Uranium-233 Material Downblending and Disposition Project at the Oak Ridge National Laboratory, Oak Ridge, Tennessee (01/13/10)  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

URANIUM-233 MATERIAL DOWNBLENDING AND DISPOSITION PROJECT URANIUM-233 MATERIAL DOWNBLENDING AND DISPOSITION PROJECT AT THE OAK RIDGE NATIONAL LABORATORY, OAK RIDGE, TENNESSEE AGENCY: U.S. Department of Energy (DOE) ACTION: Finding of No Significant Impact (FONSI) SUMMARY: DOE has completed the Final Environmental Assessment for U-233 Material Downblending and Disposition Project at the Oak Ridge National Laboratory [DOE/EA-1651]. This environmental assessment (EA) evaluates the impacts of planned activities to modify selected Oak Ridge National Laboratory (ORNL) facilities; process the ORNL inventory of uranium-233 (U-233); and transport the processed material to a long-term disposal facility. Small quantities of similar material currently stored at other DOE sites may also be included in this initiative. The

60

Preliminary Technology Readiness Assessment (TRA) for the Calcine Disposition Project Volume 2 (CDP)  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

PRELIMINARY TECHNOLOGY PRELIMINARY TECHNOLOGY OF THE CALCINE Prepared by the U.S. Department of Energy ECHNOLOGY READINESS ASSESSMENT ALCINE DISPOSITION PROJECT VOLUME TWO Anthony F. Kluk Hoyt C. Johnson Clyde Phillip McGinnis Michael Rinker Steven L. Ross Herbert G. Sutter John Vienna February 2011 Prepared by the U.S. Department of Energy Washington, DC SSESSMENT ROJECT 412.09 (06/03/2009 - Rev. 11) CALCINE DISPOSITION PROJECT TECHNOLOGY MATURATION PLAN Identifier: Revision*: Page: PLN-1482 2 C-1 of C-317 Appendix C Appendix C Checklists for Critical Technology Elements and Technology Readiness Levels This appendix provides the CTE and TRL checklists for the CTEs. For the TRL questions that receive a "Y" (yes) response, the supporting documentation is provided with a complete reference at the

Note: This page contains sample records for the topic "facility disposition project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


61

Capital Asset Project List 2013-07-08.xlsx  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

(ISFF) Project INL CD0 TBD ID-0014B.C2 Calcine Disposition Project (CDP) INL CD0 TBD IFDP Integrated Facility Disposition Project (IFDP) Oak Ridge CD1 TBD OR-0013B.C1 Sludge...

62

Request For Records Disposition | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Strategic Petroleum Reserve Request For Records Disposition More Documents & Publications Request For Records Disposition Authority: Strategic Petroleum Reserve Project Management...

63

Manhattan Project Signature Facilities | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Manhattan Manhattan Project Signature Facilities Manhattan Project Signature Facilities Manhattan Project Signature Facilities The Department of Energy, in the mid-1990s, developed a list of eight Manhattan Project properties that were designated as "Signature Facilities." These properties, taken together, provided the essential core for successfully interpreting for the American public the Manhattan Project mission of developing an atomic bomb. The Department's goal was to move foward in preserving and interpreting these properties by integrating departmental headquarters and field activities and joining in a working partnership with all interested outside entities, organizations, and individuals, including Congress, state and local governments, the Department's contractors, and various other stakeholders.

64

Summary - Preliminary TRA of the Calcine Disposition Project  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Calcine Calcine The Id materi Dec. 2 Press additiv form w those project anticip 2012 a CD-1 a selecte Level ( assess Eleme assign prepar The as below achiev * R * Ba * C The Ele Site: I roject: C Report Date: ited States Prelim Why DOE e HIP Treatment daho high-level al designated t 2009) to underg (HIP) process. ves, converts th with durability a of borosilicate t is currently in pates Critical D authorizing the approval, it is t ed technology (TRL) of 4 or h sment was to id ents (CTEs) of t n the TRLs that ration for CD-1 What th ssessment team along with the ved prior to CD etrieval//Pneum atching and Mi eramic Additive To view the full T http://www.em.doe. objective of a Tech ements (CTEs), usin daho Nationa Calcine Dispo February 201 Departmen minary T E-EM Did This t Process Flow D waste calcine through an am

65

Renewable Energy Project Development and Financing: Facility...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

DOE OFFICE OF INDIAN ENERGY Renewable Energy Project Development and Financing: Facility Scale Detailed Hypothetical Example of How to Use Renewable Power in Your Small to...

66

Mission Need Statement: Idaho Spent Fuel Facility Project  

SciTech Connect

Approval is requested based on the information in this Mission Need Statement for The Department of Energy, Idaho Operations Office (DOE-ID) to develop a project in support of the mission established by the Office of Environmental Management to "complete the safe cleanup of the environmental legacy brought about from five decades of nuclear weapons development and government-sponsored nuclear energy research". DOE-ID requests approval to develop the Idaho Spent Fuel Facility Project that is required to implement the Department of Energy's decision for final disposition of spent nuclear fuel in the Geologic Repository at Yucca Mountain. The capability that is required to prepare Spent Nuclear Fuel for transportation and disposal outside the State of Idaho includes characterization, conditioning, packaging, onsite interim storage, and shipping cask loading to complete shipments by January 1,2035. These capabilities do not currently exist in Idaho.

Barbara Beller

2007-09-01T23:59:59.000Z

67

Mission Need Statement: Idaho Spent Fuel Facility Project  

SciTech Connect

Approval is requested based on the information in this Mission Need Statement for The Department of Energy, Idaho Operations Office (DOE-ID) to develop a project in support of the mission established by the Office of Environmental Management to "complete the safe cleanup of the environmental legacy brought about from five decades of nuclear weapons development and government-sponsored nuclear energy research". DOE-ID requests approval to develop the Idaho Spent Fuel Facility Project that is required to implement the Department of Energy's decision for final disposition of spent nuclear fuel in the Geologic Repository at Yucca Mountain. The capability that is required to prepare Spent Nuclear Fuel for transportation and disposal outside the State of Idaho includes characterization, conditioning, packaging, onsite interim storage, and shipping cask loading to complete shipments by January 1,2035. These capabilities do not currently exist in Idaho.

Barbara Beller

2007-09-01T23:59:59.000Z

68

US ITER Project Providing a Facility for  

E-Print Network (OSTI)

US ITER Project Providing a Facility for Burning Plasma Research Ned Sauthoff Project Manager, US to position the US for Burning Plasma Research #12;U.S. ITER / Sauthoff Slide 2 Structure of the Talk... ITER

69

Project Hanford nuclear facilities list and authorization basis information  

SciTech Connect

Rev. 4 documents and updates the Nuclear Facilities list and associated Authorization Basis (AB) information for applicable Project Hanford facilities.

EVANS, C.B.

1999-03-03T23:59:59.000Z

70

Idaho Waste Vitrification Facilities Project Vitrified Waste Interim Storage Facility  

SciTech Connect

This feasibility study report presents a draft design of the Vitrified Waste Interim Storage Facility (VWISF), which is one of three subprojects of the Idaho Waste Vitrification Facilities (IWVF) project. The primary goal of the IWVF project is to design and construct a treatment process system that will vitrify the sodium-bearing waste (SBW) to a final waste form. The project will consist of three subprojects that include the Waste Collection Tanks Facility, the Waste Vitrification Facility (WVF), and the VWISF. The Waste Collection Tanks Facility will provide for waste collection, feed mixing, and surge storage for SBW and newly generated liquid waste from ongoing operations at the Idaho Nuclear Technology and Engineering Center. The WVF will contain the vitrification process that will mix the waste with glass-forming chemicals or frit and turn the waste into glass. The VWISF will provide a shielded storage facility for the glass until the waste can be disposed at either the Waste Isolation Pilot Plant as mixed transuranic waste or at the future national geological repository as high-level waste glass, pending the outcome of a Waste Incidental to Reprocessing determination, which is currently in progress. A secondary goal is to provide a facility that can be easily modified later to accommodate storage of the vitrified high-level waste calcine. The objective of this study was to determine the feasibility of the VWISF, which would be constructed in compliance with applicable federal, state, and local laws. This project supports the Department of Energys Environmental Management missions of safely storing and treating radioactive wastes as well as meeting Federal Facility Compliance commitments made to the State of Idaho.

Bonnema, Bruce Edward

2001-09-01T23:59:59.000Z

71

Tribal Renewable Energy Advanced Course: Facility Scale Project...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Facility Scale Project Development Tribal Renewable Energy Advanced Course: Facility Scale Project Development Watch the DOE Office of Indian Energy renewable energy course...

72

Idaho Spent Fuel Facility (ISFF) Project, Appropriate Acquisition...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Idaho Spent Fuel Facility (ISFF) Project, Appropriate Acquisition Strategy Lessons Learned Report, NNSA, Feb 2010 Idaho Spent Fuel Facility (ISFF) Project, Appropriate Acquisition...

73

Fast Flux Test Facility, Sodium Storage Facility project-specific project management plan  

SciTech Connect

This Project-Specific Project Management Plan describes the project management methods and controls used by the WHC Projects Department to manage Project 03-F-031. The Sodium Storage Facility provides for storage of the 260,000 gallons of sodium presently in the FFTF Plant. The facility will accept the molten sodium transferred from the FFTF sodium systems, and store the sodium in a solid state under an inert cover gas until such time as a Sodium Reaction Facility is available for final disposal of the sodium.

Shank, D.R.

1994-12-29T23:59:59.000Z

74

National Biomedical Tracer Facility: Project definition study  

SciTech Connect

The Los Alamos National Laboratory is an ideal institution and New Mexico is an ideal location for siting the National Biomedical Tracer Facility (NBTF). The essence of the Los Alamos proposal is the development of two complementary irradiation facilities that combined with our existing radiochemical processing hot cell facilities and waste handling and disposal facilities provide a low cost alternative to other proposals that seek to satisfy the objectives of the NBTF. We propose the construction of a 30 MeV cyclotron facility at the site of the radiochemical facilities, and the construction of a 100 MeV target station at LAMPF to satisfy the requirements and objectives of the NBTF. We do not require any modifications to our existing radiochemical processing hot cell facilities or our waste treatment and disposal facilities to accomplish the objectives of the NBTF. The total capital cost for the facility defined by the project definition study is $15.2 M. This cost estimate includes $9.9 M for the cyclotron and associated facility, $2.0 M for the 100 MeV target station at LAMPF, and $3.3 M for design.

Heaton, R.; Peterson, E. [Los Alamos National Lab., NM (United States); Smith, P. [Smith (P.A.) Concepts and Designs (United States)

1995-05-31T23:59:59.000Z

75

Review of the Facility Centered Assessment of the Los Alamos...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Facility Centered Assessment of the Los Alamos National Laboratory Waste Disposition Project September 2011 Office of Safety and Emergency Management Evaluations Office of Health,...

76

DOE/EA-1651: Final Environmental Assessment for U-233 Material Downblending and Disposition Project at the Oak Ridge National Laboratory Oak Ridge, Tennessee (January 2010)  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

51 51 Final Environmental Assessment for U-233 Material Downblending and Disposition Project at the Oak Ridge National Laboratory Oak Ridge, Tennessee U. S. Department of Energy Oak Ridge Office Oak Ridge, Tennessee January 2010 FINDING OF NO SIGNIFICANT IMPACT URANIUM-233 MATERIAL DOWNBLENDING AND DISPOSITION PROJECT AT THE OAK RIDGE NATIONAL LABORATORY, OAK RIDGE, TENNESSEE AGENCY: U.S. Department of Energy (DOE) ACTION: Finding of No Significant Impact (FONSI) SUMMARY: DOE has completed the Final Environmental Assessment for U-233 Material Downblending and Disposition Project at the Oak Ridge National Laboratory [DOE/EA-1651]. This environmental assessment (EA) evaluates the impacts of planned activities to modify selected

77

Plutonium Disposition Now!  

SciTech Connect

A means for use of existing processing facilities and reactors for plutonium disposition is described which requires a minimum capital investment and allows rapid implementation. The scenario includes interim storage and processing under IAEA control, and fabrication into MOX fuel in existing or planned facilities in Europe for use in operating reactors in the two home countries. Conceptual studies indicate that existing Westinghouse four-loop designs can safety dispose of 0.94 MT of plutonium per calendar year. Thus, it would be possible to consume the expected US excess stockpile of about 50 MT in two to three units of this type, and it is highly likely that a comparable amount of the FSU excess plutonium could be deposed of in a few VVER-1000`s. The only major capital project for this mode of plutonium disposition would be the weapons-grade plutonium processing which could be done in a dedicated international facility or using existing facilities in the US and FSU under IAEA control. This option offers the potential for quick implementation at a very low cost to the governments of the two countries.

Buckner, M.R.

1995-05-24T23:59:59.000Z

78

National Ignition Facility project acquisition plan  

SciTech Connect

The purpose of this National Ignition Facility Acquisition Plan is to describe the overall procurement strategy planned for the National Ignition Facility (NIF) Project. The scope of the plan describes the procurement activities and acquisition strategy for the following phases of the NIF Project, each of which receives either plant and capital equipment (PACE) or other project cost (OPC) funds: Title 1 and 2 design and Title 3 engineering (PACE); Optics manufacturing facilitization and pilot production (OPC); Convention facility construction (PACE); Procurement, installation, and acceptance testing of equipment (PACE); and Start-up (OPC). Activities that are part of the base Inertial Confinement Fusion (ICF) Program are not included in this plan. The University of California (UC), operating Lawrence Livermore National Laboratory (LLNL) and Los Alamos National Laboratory, and Lockheed-Martin, which operates Sandia National Laboratory (SNL) and the University of Rochester Laboratory for Laser Energetics (UR-LLE), will conduct the acquisition of needed products and services in support of their assigned responsibilities within the NIF Project structure in accordance with their prime contracts with the Department of Energy (DOE). LLNL, designated as the lead Laboratory, will have responsibility for all procurements required for construction, installation, activation, and startup of the NIF.

Callaghan, R.W.

1996-04-01T23:59:59.000Z

79

SAVANNAH RIVER SITE'S H-CANYON FACILITY: IMPACTS OF FOREIGN OBLIGATIONS ON SPECIAL NUCLEAR MATERIAL DISPOSITION  

SciTech Connect

The US has a non-proliferation policy to receive foreign and domestic research reactor returns of spent fuel materials of US origin. These spent fuel materials are returned to the Department of Energy (DOE) and placed in storage in the L-area spent fuel basin at the Savannah River Site (SRS). The foreign research reactor returns fall subject to the 123 agreements for peaceful cooperation. These 123 agreements are named after section 123 of the Atomic Energy Act of 1954 and govern the conditions of nuclear cooperation with foreign partners. The SRS management of these foreign obligations while planning material disposition paths can be a challenge.

Magoulas, V.

2013-06-03T23:59:59.000Z

80

2013 Community- and Facility-Scale Tribal Renewable Energy Project...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

2013 Community- and Facility-Scale Tribal Renewable Energy Project Development and Finance Workshop Presentations and Agenda 2013 Community- and Facility-Scale Tribal Renewable...

Note: This page contains sample records for the topic "facility disposition project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


81

MHK Projects/Bonnybrook Wastewater Facility Project 1 | Open Energy  

Open Energy Info (EERE)

Bonnybrook Wastewater Facility Project 1 Bonnybrook Wastewater Facility Project 1 < MHK Projects Jump to: navigation, search << Return to the MHK database homepage Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":5,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"500px","height":"350px","centre":false,"title":"","label":"","icon":"File:Aquamarine-marker.png","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[{"text":"","title":"","link":null,"lat":51.0097,"lon":-114.02,"alt":0,"address":"","icon":"http:\/\/prod-http-80-800498448.us-east-1.elb.amazonaws.com\/w\/images\/7\/74\/Aquamarine-marker.png","group":"","inlineLabel":"","visitedicon":""}]}

82

MHK Projects/Bonnybrook Wastewater Facility Project 2 | Open Energy  

Open Energy Info (EERE)

Bonnybrook Wastewater Facility Project 2 Bonnybrook Wastewater Facility Project 2 < MHK Projects Jump to: navigation, search << Return to the MHK database homepage Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":5,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"500px","height":"350px","centre":false,"title":"","label":"","icon":"File:Aquamarine-marker.png","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[{"text":"","title":"","link":null,"lat":51.0097,"lon":-114.02,"alt":0,"address":"","icon":"http:\/\/prod-http-80-800498448.us-east-1.elb.amazonaws.com\/w\/images\/7\/74\/Aquamarine-marker.png","group":"","inlineLabel":"","visitedicon":""}]}

83

MRAP MONTICELLO PROJECTS FEDERAL FACILITY AGREEMENT REPORT  

Office of Legacy Management (LM)

MRAP MRAP MONTICELLO PROJECTS FEDERAL FACILITY AGREEMENT REPORT May/June 2005 Report Period: May 1 -June 30, 2005 DOE Project Coordinator: Art Kleinrath HIGHLIGHTS DOE constmction, as identified in the Millsite Restoration Plan, was substantially completed on June 3. Seeding of disturbed areas was completed on June 15. MSG DOE completed constmction of the permeable reactive treatment cell and initiated operations in June. The cell is an enhancement to the existing pe1meable reactive ban·ier and was designed to alleviate ground water mounding. MVP Approximately one cubic yard of contaminated material was identified in a City of Monticello excavation near the golf course. This material was transferred to the Temporary Storage Facility located at the DOE Monticello Office.

84

The rare isotope accelerator (RIA) facility project  

DOE Green Energy (OSTI)

The envisioned Rare-Isotope Accelerator (RIA) facility would add substantially to research opportunities for nuclear physics and astrophysics by combining increased intensities with a greatly expanded variety of high-quality rare-isotope beams. A flexible superconducting driver linac would provide 100 kW, 400 MeV/nucleon beams of any stable isotope from hydrogen to uranium onto production targets. Combinations of projectile fragmentation, target fragmentation, fission, and spallation would produce the needed broad assortment of short-lived secondary beams. This paper describes the project's background, purpose, and status, the envisioned facility, and the key subsystem, the driver linac. RIA's scientific purposes are to advance current theoretical models, reveal new manifestations of nuclear behavior, and probe the limits of nuclear existence [3]. Figures 1 and 2 show, respectively, examples of RIA research opportunities and the yields projected for pursuing them. Figure 3 outlines a conceptual approach for delivering the needed beams.

Christoph Leemann

2000-08-01T23:59:59.000Z

85

MSG MONTICELLO PROJECTS FEDERAL FACILITY AGREEMENT REPORT  

Office of Legacy Management (LM)

November/December 2004 November/December 2004 Report Period: November 1- December 31, 2004 DOE Project Coordinator: Art Kleinrath HIGHLIGHTS The Program Directive for the wildlife survey is on schedule for completion by January 15. Comments from the Biological Technical Assistance group have been incorporated. MRAP A punchlist of mill site restoration items was prepared. DOE and the City of Monticello have agreed upon which entity will perform each item on the punchlist. MVP No significant activities to report. FF A Monthly Report November- December 2004 Page 2 of5 STATUS MONTICELLO PROJECTS FEDERAL FACILITIES AGREEMENT REPORT November/December 2004 Report Period: November 1- December 31, 2004 DOE Project Coordinator: Art Kleinrath Operable Units I and II DOE and the City of Monticello (City) are exploring the possibility of transferring the former

86

MSG MONTICELLO PROJECTS FEDERAL FACILITIES AGREEMENT REPORT  

Office of Legacy Management (LM)

FACILITIES AGREEMENT REPORT FACILITIES AGREEMENT REPORT Report Period: October 1- December 31, 2005 DOE Project Coordinator: Ray Plieness HIGHLIGHTS The Final Report-2005 Avian Wetland Surveys at the Monticello Mill Tailings Site and the Final Report-Monticello Mill Tailings Site Macroinvertebrate Sampling for 2005 were transmitted to the Environmental Protection Agency (EPA) and the Utah Department of Environmental Quality (UDEQ) on December 13. These reports are required under the Monticello Mill Tailings Site Operable Unit III Post-Record of Decision Monitoring Plan, Section 6.0 Biomonitoring Plan, to determine whether selenium levels are present in environmental media at concentrations that could cause adverse effects on ecological receptors. MRAP The draft-flnal2005 Annual Inspection of the Monticello Mill Tailings (USDOE) and

87

FACILITIES ENGINEER WEST CHICAGO Execute capital projects for manufacturing facilities and utilities systems: scope development, cost  

E-Print Network (OSTI)

improvements, including all stages of project engineering: scope development, cost estimation, system designFACILITIES ENGINEER ­ WEST CHICAGO OVERVIEW: Execute capital projects for manufacturing facilities and utilities systems: scope development, cost estimation, system design, equipment sizing

Heller, Barbara

88

Iraq nuclear facility dismantlement and disposal project (NDs Project).  

SciTech Connect

The Al Tuwaitha nuclear complex near Baghdad contains a number of facilities from Saddam Hussan's nuclear weapons program. Past military operations, lack of upkeep and looting have created an enormous radioactive waste problem at the Al Tuwaitha complex, which contains various, uncharacterized radioactive wastes, yellow cake, sealed radioactive sources, and contaminated metals that must be constantly guarded. Iraq has never had a radioactive waste disposal facility and the lack of a disposal facility means that ever increasing quantities of radioactive material must be held in guarded storage. The Iraq Nuclear Facility Dismantlement and Disposal Program (the NDs Program) has been initiated by the U.S. Department of State (DOS) to assist the Government of Iraq (GOI) in eliminating the threats from poorly controlled radioactive materials, while building human capacities so that the GOI can manage other environmental cleanups in their country. The DOS is funding the IAEA to provide technical assistance via Technical Cooperation projects. Program coordination will be provided by the DOS, consistent with GOI policies, and Sandia National Laboratories will be responsible for coordination of participants and waste management support. Texas Tech University will continue to provide in-country assistance, including radioactive waste characterization and the stand-up of the Iraq Nuclear Services Company. The GOI owns the problems in Iraq and will be responsible for implementation of the NDs Program.

Cochran, John Russell

2010-06-01T23:59:59.000Z

89

Recovery Act Workers Demolish Facility Tied to Project Pluto History |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Demolish Facility Tied to Project Pluto Demolish Facility Tied to Project Pluto History Recovery Act Workers Demolish Facility Tied to Project Pluto History Workers recently razed a facility used in the historic Project Pluto, the latest American Recovery and Reinvestment Act accomplishment helping clean up traces of past nuclear testing at the Nevada National Security Site (NNSS). Recovery Act workers safely hauled the last demolition waste from the Pluto Disassembly Facility to disposal facilities Jan. 11. The project is slated for completion this spring after workers finish installing a concrete cap over the below-ground level where the facility stood. Recovery Act Workers Demolish Facility Tied to Project Pluto History More Documents & Publications 2010 ARRA Newsletters 2011 ARRA Newsletters

90

Recovery Act Workers Demolish Facility Tied to Project Pluto History |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Recovery Act Workers Demolish Facility Tied to Project Pluto Recovery Act Workers Demolish Facility Tied to Project Pluto History Recovery Act Workers Demolish Facility Tied to Project Pluto History Workers recently razed a facility used in the historic Project Pluto, the latest American Recovery and Reinvestment Act accomplishment helping clean up traces of past nuclear testing at the Nevada National Security Site (NNSS). Recovery Act workers safely hauled the last demolition waste from the Pluto Disassembly Facility to disposal facilities Jan. 11. The project is slated for completion this spring after workers finish installing a concrete cap over the below-ground level where the facility stood. Recovery Act Workers Demolish Facility Tied to Project Pluto History More Documents & Publications 2010 ARRA Newsletters

91

Transmutation facility for weapons-grade plutonium disposition based on a tokamak fusion neutron source  

Science Conference Proceedings (OSTI)

It is suggested that weapons-grade plutonium could be processed through a transmutation facility to build up sufficient actinide and fission product inventories to serve as a deterrent to diversion or theft during subsequent storage, pending eventual use as fuel in commercial nuclear reactors. A transmutation facility consisting of a tokamak fusion neutron source surrounded by fuel assemblies containing the weapons-grade plutonium in the form of PuO{sub 2} pebbles in a lithium slurry is investigated. A design concept/operation scenario is developed for a facility that would be able to transmute the world`s estimated surplus inventory of weapons-grade plutonium to 11% {sup 240}Pu concentration in nearly 25 yr. The fusion neutron source would be based on plasma physics and plasma support technology being qualified in ongoing research and development (R&D) programs, and the plutonium fuel would be based on existing technology. A new R&D program would be required to qualify a refractory metal alloy structural material that would be needed to handle the high heat fluxes; otherwise, extensions of existing technologies and acceleration of existing R&D programs would seem to be adequate to qualify all required technologies. Such a facility might feasibly be deployed in 20 to 30 yr, or sooner with a crash program. 49 refs., 5 figs., 13 tabs.

Stacey, W.M.; Pilger, B.L.; Mowrey, J.A. [Georgia Inst. of Technology, Atlanta, GA (United States)] [and others

1995-05-01T23:59:59.000Z

92

Integration of health physics, safety and operational processes for management and disposition of recycled uranium wastes at the Fernald Environmental Management Project (FEMP)  

Science Conference Proceedings (OSTI)

Fluor Fernald, Inc. (Fluor Fernald), the contractor for the U. S. Department of Energy (DOE) Fernald Environmental Management Project (FEMP), recently submitted a new baseline plan for achieving site closure by the end of calendar year 2006. This plan was submitted at DOE's request, as the FEMP was selected as one of the sites for their accelerated closure initiative. In accordance with the accelerated baseline, the FEMP Waste Management Project (WMP) is actively evaluating innovative processes for the management and disposition of low-level uranium, fissile material, and thorium, all of which have been classified as waste. These activities are being conducted by the Low Level Waste (LLW) and Uranium Waste Disposition (UWD) projects. Alternatives associated with operational processing of individual waste streams, each of which poses potentially unique health physics, industrial hygiene and industrial hazards, are being evaluated for determination of the most cost effective and safe met hod for handling and disposition. Low-level Mixed Waste (LLMW) projects are not addressed in this paper. This paper summarizes historical uranium recycling programs and resultant trace quantity contamination of uranium waste streams with radionuclides, other than uranium. The presentation then describes how waste characterization data is reviewed for radiological and/or chemical hazards and exposure mitigation techniques, in conjunction with proposed operations for handling and disposition. The final part of the presentation consists of an overview of recent operations within LLW and UWD project dispositions, which have been safely completed, and a description of several current operations.

Barber, James; Buckley, James

2003-02-23T23:59:59.000Z

93

Amended Record of Decision: Idaho High-Level Waste and Facilities Disposition Final Environmental Impact Statement (DOE/EIS-0287) (11/28/06)  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

811 Federal Register 811 Federal Register / Vol. 71, No. 228 / Tuesday, November 28, 2006 / Notices Information Relay Service (FIRS) at 1-800-877-8339. [FR Doc. E6-20124 Filed 11-27-06; 8:45 am] BILLING CODE 4000-01-P DEPARTMENT OF ENERGY Amended Record of Decision: Idaho High-Level Waste and Facilities Disposition Final Environmental Impact Statement AGENCY: Department of Energy. ACTION: Amended Record of Decision. SUMMARY: The U.S. Department of Energy (DOE) is amending its Record of Decision (ROD) published December 19, 2005 (70 Federal Register [FR] 75165), pursuant to the Idaho High-Level Waste and Facilities Disposition Final Environmental Impact Statement (Final EIS) (DOE/EIS-0287, September 2002). The Final EIS analyzed two sets of alternatives for accomplishing DOE's

94

Independent Oversight Assessment, Salt Waste Processing Facility Project -  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Salt Waste Processing Facility Salt Waste Processing Facility Project - January 2013 Independent Oversight Assessment, Salt Waste Processing Facility Project - January 2013 January 2013 Assessment of Nuclear Safety Culture at the Salt Waste Processing Facility Project The U.S. Department of Energy (DOE) Office of Enforcement and Oversight (Independent Oversight), within the Office of Health, Safety and Security (HSS), conducted an independent assessment of nuclear safety culture at the Salt Waste Processing Facility (SWPF) Project. The primary objective of the evaluation was to provide information regarding the status of the safety culture at the SWPF Project. The data collection phase of the assessment occurred during August - September 2012. Independent Oversight Assessment, Salt Waste Processing Facility Project -

95

Community- and Facility-Scale Tribal Renewable Energy Project Development  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Community- and Facility-Scale Tribal Renewable Energy Project Community- and Facility-Scale Tribal Renewable Energy Project Development and Finance Workshop Agenda Community- and Facility-Scale Tribal Renewable Energy Project Development and Finance Workshop Agenda Downoad the agenda for the Office of Indian Energy's Community- and Facility-Scale Tribal Renewable Energy Project Development and Finance Workshop, which will be held September 18-20 at the National Renewable Energy Laboratory in Denver, Colorado. Workshop Agenda More Documents & Publications 2013 Community- and Facility-Scale Tribal Renewable Energy Project Development and Finance Workshop Presentations and Agenda Commercial-Scale Renewable Energy Project Development and Finance Workshop 2013 Commercial-Scale Tribal Renewable Energy Project Development and

96

Modernization Project Office, Facilities & Operations Directorate...  

NLE Websites -- All DOE Office Websites (Extended Search)

Welcome to the... Modernization Project Office The Modernization Project Office (MPO) is responsible for engineering, design, cost estimating, scheduling, and project controls,...

97

Tribal Renewable Energy Advanced Course: Facility Scale Project Development  

Energy.gov (U.S. Department of Energy (DOE))

Download the DOE Office of Indian Energy renewable energy course entitled "Tribal Renewable Energy Project Development and Financing: Facility Scale." The presentation provides in-depth information...

98

Fast Flux Test Facility project plan. Revision 2  

Science Conference Proceedings (OSTI)

The Fast Flux Test Facility (FFTF) Transition Project Plan, Revision 2, provides changes to the major elements and project baseline for the deactivation activities necessary to transition the FFTF to a radiologically and industrially safe shutdown condition.

Hulvey, R.K.

1995-11-01T23:59:59.000Z

99

Idaho High-Level Waste & Facilities Disposition, Final Environmental Impact Statement  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Appendix A Appendix A Site Evaluation Process A-iii DOE/EIS-0287 Idaho HLW & FD EIS TABLE OF CONTENTS Section Page Appendix A Site Evaluation Process A-1 A.1 Introduction A-1 A.2 Methodology A-1 A.3 High-Level Waste Treatment and Interim Storage Site Selection A-3 A.3.1 Identification of "Must" Criteria A-3 A.3.2 Identification of "Want" Criteria A-3 A.3.3 Identification of Candidate Sites A-3 A.3.4 Evaluation Process A-4 A.3.5 Results of Evaluation Process A-6 A.4 Low-Activity Waste Disposal Site Selection A-6 A.4.1 Identification of "Must" Criteria A-7 A.4.2 Identification of "Want" Criteria A-8 A.4.3 Identification of Candidate Sites A-8 A.4.4 Evaluation Process A-8 A.4.5 Results of Evaluation Process A-9 A.4.6 Final Selection of a Low-Activity Waste Disposal Facility

100

Vitrification facility at the West Valley Demonstration Project  

SciTech Connect

This report is a description of the West Valley Demonstration Project`s vitrification facilities from the establishment of the West Valley, NY site as a federal and state cooperative project to the completion of all activities necessary to begin solidification of radioactive waste into glass by vitrification. Topics discussed in this report include the Project`s background, high-level radioactive waste consolidation, vitrification process and component testing, facilities design and construction, waste/glass recipe development, integrated facility testing, and readiness activities for radioactive waste processing.

DesCamp, V.A.; McMahon, C.L.

1996-07-01T23:59:59.000Z

Note: This page contains sample records for the topic "facility disposition project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


101

200 Area Deactivation Project Facilities Authorization Envelope Document  

Science Conference Proceedings (OSTI)

Project facilities as required by HNF-PRO-2701, Authorization Envelope and Authorization Agreement. The Authorization Agreements (AA's) do not identify the specific set of environmental safety and health requirements that are applicable to the facility. Therefore, the facility Authorization Envelopes are defined here to identify the applicable requirements. This document identifies the authorization envelopes for the 200 Area Deactivation.

DODD, E.N.

2000-03-28T23:59:59.000Z

102

Renewable Energy Project Development and Financing: Facility Scale  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Facility Scale Facility Scale Detailed Hypothetical Example of How to Use Renewable Power in Your Small to Medium-Sized Tribal Facilities Course Outline What we will cover...  About the DOE Office of Indian Energy Education Initiative  Facility-Scale Process: Hypothetical Example - Project development and financing concepts - Project development and financing process and decision points - Facility-scale project as an investment (or commitment to an alternative utility payment) - How to pay for facility-scale project (or the renewable energy from it)  Additional Information and Resources 2 Introduction 3 The U.S. Department of Energy (DOE) Office of Indian Energy Policy and Programs is responsible for assisting Tribes with energy planning and

103

Protocol, High Hazard Nuclear Facility Project Oversight - November 2012 |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

High Hazard Nuclear Facility Project Oversight - November High Hazard Nuclear Facility Project Oversight - November 2012 Protocol, High Hazard Nuclear Facility Project Oversight - November 2012 November 2012 Protocol for High Hazard Nuclear Facility Project Oversight The purpose of this protocol is to establish the requirements and responsibilities for managing and conducting Office of Health, Safety and Security (HSS) independent oversight of high-hazard nuclear facility projects. As part of the Department of Energy's (DOE) self regulatory framework for safety and security, DOE Order 227.1, Independent Oversight Program, assigns HSS the responsibility for implementing an independent oversight program. It also requires the HSS Office of Enforcement and Oversight to conduct independent evaluations of safety and security. This

104

DOE Community-/Facility-Scale Tribal Renewable Energy Project Development  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

DOE Community-/Facility-Scale Tribal Renewable Energy Project DOE Community-/Facility-Scale Tribal Renewable Energy Project Development and Finance Workshop DOE Community-/Facility-Scale Tribal Renewable Energy Project Development and Finance Workshop September 18, 2013 (All day) to September 20, 2013 (All day) This interactive workshop will walk participants through five steps to help tribes understand the process for and potential pitfalls of developing community- and facility-scale renewable energy projects. Attendees will learn how the development of a renewable energy project could further a tribe's goals, and hear from other tribes about their experiences. This workshop is specifically designed for, and limited to, elected tribal leaders and tribal executives, accountants, and attorneys interested in gaining knowledge and confidence to develop community- and facility-scale

105

Project Eagle Phase 1 Direct Wafer/Cell Solar Facility  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Project Eagle Phase 1 Direct Wafer/Cell Solar Facility Project Eagle Phase 1 Direct Wafer/Cell Solar Facility 1366 Technologies Description of Proposed Action: The Department of Energy (DOE) proposed action is for the use of a federal loan guarantee by 1366 Technologies (1366) to support the renovation of an existing building, located at 159 Wells Avenue, Newton, Massachusetts, into a solar wafer production facility. The new facility would constitute Phase 1 of Project Eagle and accommodate 20 megawatts (MW) of multi crystalline silicon wafer production, laboratory areas, offices, and ancillary spaces. Phase 2 of Proje~y an existing DOE Categorical Exclusion and would occur at a site in _ _ _ _ . The Phase 1 facility in Newton, MA is an existing building of 50,600 square feet on a site approximately 4.7 acres. 1366 would renovate the interior of the facility to provide office

106

Recovery Act Workers Demolish Facility Tied to Project Pluto History  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

LAS VEGAS - Workers recently razed a facility used in the LAS VEGAS - Workers recently razed a facility used in the historic Project Pluto, the latest American Recovery and Rein- vestment Act accomplishment helping clean up traces of past nuclear testing at the Nevada National Security Site (NNSS). Recovery Act workers safely hauled the last demolition waste from the Pluto Disassembly Facility to disposal facilities Jan. 11. The project is slated for completion this spring after work- ers finish installing a concrete cap over the below-ground level where the facility stood. "Without Recovery Act funding, the demolition of Pluto would not have been feasible for several more years," Federal Sub- Project Director Kevin Cabble said. In the late 1950s and early 1960s, the Pluto facility was used to develop the world's first

107

Lopez Landfill Gas Utilization Project Biomass Facility | Open Energy  

Open Energy Info (EERE)

Lopez Landfill Gas Utilization Project Biomass Facility Lopez Landfill Gas Utilization Project Biomass Facility Jump to: navigation, search Name Lopez Landfill Gas Utilization Project Biomass Facility Facility Lopez Landfill Gas Utilization Project Sector Biomass Facility Type Landfill Gas Location Los Angeles County, California Coordinates 34.3871821°, -118.1122679° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[{"text":"","title":"","link":null,"lat":34.3871821,"lon":-118.1122679,"alt":0,"address":"","icon":"","group":"","inlineLabel":"","visitedicon":""}]}

108

Albany Landfill Gas Utilization Project Biomass Facility | Open Energy  

Open Energy Info (EERE)

Utilization Project Biomass Facility Utilization Project Biomass Facility Jump to: navigation, search Name Albany Landfill Gas Utilization Project Biomass Facility Facility Albany Landfill Gas Utilization Project Sector Biomass Facility Type Landfill Gas Location Albany County, New York Coordinates 42.5756797°, -73.9359821° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[{"text":"","title":"","link":null,"lat":42.5756797,"lon":-73.9359821,"alt":0,"address":"","icon":"","group":"","inlineLabel":"","visitedicon":""}]}

109

Fast flux test facility, transition project plan  

SciTech Connect

The FFTF Transition Project Plan, Revision 1, provides changes and project baseline for the deactivation activities necessary to transition the FFTF to a radiologically and industrially safe shutdown condition.

Guttenberg, S.

1994-11-15T23:59:59.000Z

110

Boston College Facilities Management Summer Projects 2013  

E-Print Network (OSTI)

# Building / Location Project Description Resp Mgr Project Mgr 1 8131515 2000 Comm Ave Cooling Towers : This project completes this phase of the renewal of 2000 Commonwealth Ave with cooling tower upgrades. Mike split system for the UPS room. Terence Leahy Terence Leahy 9 8141205 Carney Hall Cooling Tower Upgrades

Huang, Jianyu

111

Community- and Facility-Scale Tribal Renewable Energy Project Development  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Community- and Facility-Scale Tribal Renewable Energy Project Community- and Facility-Scale Tribal Renewable Energy Project Development and Finance Workshop Community- and Facility-Scale Tribal Renewable Energy Project Development and Finance Workshop September 18, 2013 8:00AM MDT to September 20, 2013 5:00PM MDT Presented by the DOE Office of Indian Energy and Office of Energy Efficiency and Renewable Energy's Tribal Energy Program with support from DOE's National Renewable Energy Laboratory, this interactive workshop will walk participants through five steps to help Tribes understand the process for and potential pitfalls of developing community- and facility-scale renewable energy projects. Attendees will learn how the development of a renewable energy project could further a Tribe's goals, and hear from other Tribes about their experiences.

112

DOE/EIS-0287-SA-01: Supplement Analysis for the Idaho High-Level Waste and Facilities Disposition Final Environmental Impact Statement (June 2005)  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

7 7 -SA-Ol SUPPLEMENT ANALYSIS For The Idaho High-Level Waste and Facilities Disposition Final Environmental Impact Statement June 2005 United States Department of Energy Idaho Operations Office 1.0 2.0 3.0 4.0 5.0 6.0 DOEÆIS-0287 -SA-O 1 TABLE OF CONTENTS Introduction......................................................................................................................... 4 Background......................................................................................................................... 4 Areas of Review.................................................................................................................. 6 3.1 3.2 3.3 3.4 Proposed Waste Treatment Technology.......... .......................................................

113

National Biomedical Tracer Facility. Project definition study  

Science Conference Proceedings (OSTI)

We request a $25 million government-guaranteed, interest-free loan to be repaid over a 30-year period for construction and initial operations of a cyclotron-based National Biomedical Tracer Facility (NBTF) in North Central Texas. The NBTF will be co-located with a linear accelerator-based commercial radioisotope production facility, funded by the private sector at approximately $28 million. In addition, research radioisotope production by the NBTF will be coordinated through an association with an existing U.S. nuclear reactor center that will produce research and commercial radioisotopes through neutron reactions. The combined facilities will provide the full range of technology for radioisotope production and research: fast neutrons, thermal neutrons, and particle beams (H{sup -}, H{sup +}, and D{sup +}). The proposed NBTF facility includes an 80 MeV, 1 mA H{sup -} cyclotron that will produce proton-induced (neutron deficient) research isotopes.

Schafer, R.

1995-02-14T23:59:59.000Z

114

Request For Records Disposition Authority: Strategic Petroleum...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Authority: Strategic Petroleum Reserve Project Management Office Request For Records Disposition Authority: Strategic Petroleum Reserve Project Management Office Paper case files...

115

2013 Community- and Facility-Scale Tribal Renewable Energy Project  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

3 Community- and Facility-Scale Tribal Renewable Energy Project 3 Community- and Facility-Scale Tribal Renewable Energy Project Development and Finance Workshop Presentations and Agenda 2013 Community- and Facility-Scale Tribal Renewable Energy Project Development and Finance Workshop Presentations and Agenda Download the agenda and available presentations from guest speakers at the Office of Indian Energy's Community- and Facility-Scale Tribal Renewable Energy Project Development and Finance workshop held September 18-20, 2013, at the National Renewable Energy Laboratory in Golden, Colorado. To access the training presentations, visit the National Training & Education Resource website. Agenda Alternative Development Partnerships: Ken Duncan, Jr., San Carlos Apache Tribe General Services Administration (GSA) Federal Acquisition Service: Cheryl

116

INDEPENDENT TECHNICAL ASSESSMENT OF MANAGEMENT OF STORMWATER AND WASTEWATER AT THE SEPARATIONS PROCESS RESEARCH UNIT (SPRU) DISPOSITION PROJECT, NEW YORK  

SciTech Connect

The U.S. Department of Energy (DOE) is currently evaluating the water management procedures at the Separations Process Research Unit (SPRU). The facility has three issues related to water management that require technical assistance: (1) due to a excessive rainfall event in October, 2010, contaminated water collected in basements of G2 and H2 buildings. As a result of this event, the contractor has had to collect and dispose of water offsite; (2) The failure of a sump pump at a KAPL outfall resulted in a Notice of Violation issued by the New York State Department of Environment and Conservation (NYSDEC) and subsequent Consent Order. On-site water now requires treatment and off-site disposition; and (3) stormwater infiltration has resulted in Strontium-90 levels discharged to the storm drains that exceed NR standards. The contractor has indicated that water management at SPRU requires major staff resources (at least 50 persons). The purpose of this review is to determine if the contractor's technical approach warrants the large number of staff resources and to ensure that the technical approach is compliant and in accordance with federal, state and NR requirements.

Abitz, R.; Jackson, D.; Eddy-Dilek, C.

2011-06-27T23:59:59.000Z

117

Strategic Petroleum Reserve: Facilities development project plan  

SciTech Connect

While the Strategic Petroleum Reserve (SPR) project is subject to future Administration policy decisions, budget proposals and Congressional actions, this Project Plan sets forth a feasible technical, cost, and schedule plan associated with the development of 750 million barrels of SPR crude oil storage and for enhancement of the SPR's distribution system to achieve a distribution capability of 4.5 million barrels per day. Assuming future adoption by the Administration and Congress of the project schedule identified in this Project Plan, The Total Project Cost (TPC) in program year dollars is $2,500,000,000. The TPC excludes post-development operations, capital improvement projects, terminal standby services, and oil acquisition. Under the same assumption, the schedule objectives of this project are: completion of the 750-million-barrel reserve, excluding oil fill, by September 30, 1992 in accordance with the storage capacity development schedule presented in Attachment 1. Completion of distribution enhancements to provide a distribution capability of 4.5 million barrels per day by September 30, 1992 in accordance with the following schedule: 3.0 million barrels per day by July 31, 1987; 3.5 million barrels per day by September 30, 1989; and 4.5 million barrels per day by September 30, 1992.

1986-10-01T23:59:59.000Z

118

Department of Energy National Nuclear Security Administration Finding of No Significant Impact for the Proposed Disposition of the Omega West Facility at Los Alamos National Laboratory, Los Alamos, New Mexico  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Finding of No Significant Impact for the Proposed Disposition of the Omega West Facility at Los Alamos National Laboratory, Los Alamos, New Mexico U. S. Department of Energy National Nuclear Security Administration Office of Los Alamos Site Operations 528 35th Street Los Alamos, NM 87544 DEPARTMENT OF ENERGY, NATIONAL NUCLEAR SECUIRTY ADMINISTRATION FINDING OF NO SIGNIFICANT IMPACT Proposed Disposition of the Omega West Facility at Los Alamos National Laboratory FINAL ENVIRONMENTAL ASSESSMENT: The Environmental Assessment (EA) for the Proposed Disposition of the Omega West Facility at Los Alamos National Laboratory [DOE/EA- 74 IO) (attached) provides sufficient evidence and analysis to determine that a Finding Of No Significant Impact is appropriate for the Proposed Action (Complete

119

Acquisition Strategy for the Idaho National Laboratory Remote-Handled Low-Level Waste Disposition Project  

Science Conference Proceedings (OSTI)

This document describes the design-build acquisition strategy that will be applied to the Remote Handled LLW Disposal Project. The design-build delivery method will be tailored, as appropriate, to integrate the requirements of Department of Energy (DOE) Order 413.3B, 'Program and Project Management for the Acquisition of Capital Assets,' with the DOE budget formulation process and the safety requirements of DOE-STD-1189, 'Integration of Safety into the Design Process.'

David Duncan

2011-05-01T23:59:59.000Z

120

Facility Software Quality Assurance for Capital Project Decisions RM  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Facility Software Quality Assurance (SQA) for Facility Software Quality Assurance (SQA) for Capital Project Critical Decisions Review Module March 2010 OFFICE OF ENVIRONMENTAL MANAGEMENT Standard Review Plan (SRP) Facility Software Quality Assurance (SQA) for Capital Project Critical Decisions Review Module Critical Decision (CD) Applicability CD-0 CD-1 CD-2 CD-3 CD-4 Post Operation March 2010 Standard Review Plan, 2 nd Edition, March 2010 FOREWORD The Standard Review Plan (SRP) 1 provides a consistent, predictable corporate review framework to ensure that issues and risks that could challenge the success of Office of Environmental Management (EM) projects are identified early and addressed proactively. The internal EM project review process encompasses key milestones established by DOE O 413.3A, Change 1,

Note: This page contains sample records for the topic "facility disposition project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


121

NEPA COMPLIANCE SURVEY Project Information Project Title: South Compost Facility #2 Da  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

South Compost Facility #2 Da South Compost Facility #2 Da te: 1-6-10 DOE Code: 6730.020.0000 Contracto r Code: 8067-788 Project Lead: Anthony Bowler Project Ove rview The purpose of the project is to build an additional compos ling facility at RMOTC to allow for 1. Bnef project description [include anything that increased soil remediation capabilities. The project will involve removing the top soil and placing could impact the environment] it adjacent to the operational area ,in a "signed" pile for reclamation . Additional scraping of the 2. Legal location area (6"-8'1 will generate material which will be used to erect a 2' berm around the location to 3. Duration of the project control runon/runoff. A perimeter fence and a locking gate will be installed around the facility's

122

Project Management Plan for the Isotopes Facilities Deactivation Project at Oak Ridge National Laboratory  

Science Conference Proceedings (OSTI)

The purpose of the Isotopes Facilities Deactivation Project (IFDP) is to place former isotopes production facilities at the Oak Ridge National Laboratory in a safe, stable, and environmentally sound condition suitable for an extended period of minimum surveillance and maintenance (S&M) and as quickly and economically as possible. Implementation and completion of the deactivation project will further reduce the already small risks to the environment and to public safety and health. Furthermore, the project should result in significant S&M cost savings in the future. The IFDP management plan has been prepared to document the project objectives, define organizational relationships and responsibilities, and outline the management control systems to be employed in the management of the project. The project has adopted a strategy to deactivate the simple facilities first, to reduce the scope of the project, and to gain experience before addressing more difficult facilities. A decision support system is being developed to identify those activities, that best promote the project mission and result in largest cost savings. The Work Plan for the Isotopes Facilities Deactivation Project at Oak Ridge National Laboratory (Energy Systems 1994) defines the project schedule, the cost estimate, and the technical approach for the project.

NONE

1995-04-01T23:59:59.000Z

123

Near-facility environmental monitoring quality assurance project plan  

SciTech Connect

This Quality Assurance Project Plan addresses the quality assurance requirements for the activities associated with the preoperational and near facility environmental monitoring performed by Waste Management Federal Services, Inc., Northwest Operations and supersedes WHC-EP-0538-2. This plan applies to all sampling and monitoring activities performed by waste management Federal Services, Inc., Northwest Operations in implementing facility environmental monitoring at the Hanford Site.

McKinney, S.M.

1997-11-24T23:59:59.000Z

124

MSG MONTICELLO PROJECTS FEDERAL FACILITY AGREEMENT REPORT  

Office of Legacy Management (LM)

August/September 2005 August/September 2005 Report Period: July 1- September 30, 2005 DOE Project Coordinator: Art Kleinrath HIGHLIGHTS The draft-final Monticello Long-Term Surveillance and Afaintenance Operating Procedures for Swface and Ground Water (Volume III) and draft-final Annual Data Summmy Report for Operable Unit Ill of the Monticello Mill Tailings Site, October 2004 through April 2005 were completed. MRAP The annual inspection of the Monticello Mill Tailings Site and the Monticello Vicinity Properties was conducted on September 14 and 15. Several high priority repair items (see page 3 of this report) were identified during the inspection and were repaired by September 30, 2005. MVP No significant activities to report. FFA Monthly Report July- September 2005

125

MSG MONTICELLO PROJECTS FEDERAL FACILITY AGREEMENT REPORT  

Office of Legacy Management (LM)

September/October 2004 September/October 2004 Report Period: September 1- October 31, 2004 DOE Project Coordinator: Art Kleinrath HIGHLIGHTS With the completion of all remedial action reports, installation of monitoring wells in accordance with the Remedial Design/Remedial Action Work Plan, and an onsite inspection by EPA and UDEQ, EPA was able tci write and sign the Preliminmy Closeout Report for the Monticello Mill Tailings Site (MMTS), Operable Units I, II, and III. With EPA's signature on this document (September 29, 2004), the MMTS was designated as "construction complete." MRAP The annual inspection oftheMMTS was conducted September 15-17,2004. With the exception of property now owned by the City of Monticello, the site is in good condition. Restoration and maintenance issues continue to exist on City owned property. DOE continues

126

MSG MONTICELLO PROJECTS FEDERAL FACILITY AGREEMENT REPORT  

Office of Legacy Management (LM)

May/June 2004 May/June 2004 Report Period: May 1- June 30, 2004 DOE Project Coordinator: Art Kleinrath HIGHLIGHTS The Record of Decision for the Monticello Mill Tailings (USDOE) Site Operable Unit IlL Swface Water and Ground Water, Monticello, Utah, was signed by DOE, UDEQ, and EPA. The last signature was obtained on June 2, 2004, seven days before the scheduled completion date. Monitored Natnral Attenuation is the selected remedy. MRAP The water level in the Pond 4 Leak Detection System is monitored daily; the level is static and pumping is no longer necessary. MVP Approximately 40 cubic yards of bricks and mortar were removed by the owner from the Park Plaza Apartments (MS-00057) and placed near a city utility excavation. The bricks and mortar exceed the soil standard of 5 pCi/g Ra-226 above background and were

127

MSG MONTICELLO PROJECTS FEDERAL FACILITY AGREEMENT REPORT  

Office of Legacy Management (LM)

January/February 2005 January/February 2005 Report Period: January 1 -February 28, 2005 DOE Project Coordinator: Art Kleinrath HIGHLIGHTS The Environmental Protection Agency (EPA), Utah Department of Environmental Quality (UDEQ), and U.S. Department ofEnergy (DOE) agreed that the Monticello Administrative Manual and Long-Term Surveillance and Maintenance Operating Procedures will not be combined into a single manual. Instead, the Monticello LTSM Operating Procedures for Swface and Ground Water will be written to address Operable Unit III requirements. A draft of this manual will be delivered to EPA and UDEQ by April14, 2005, and a draft-final version will be completed by August 12, 2005. A Program Directive for conducting wildlife surveys at the Monticello wetland areas has been

128

MSG MONTICELLO PROJECTS FEDERAL FACILITY AGREEMENT REPORT  

Office of Legacy Management (LM)

August 2004 August 2004 Report Period: July 1- August 31, 2004 DOE Project Coordinator: Art Kleinrath HIGHLIGHTS Two monitoring wells were installed, which completed the monitoring network for OU III. The following documents have been completed: * · Monticello Mill Tailings Site Operable Unit III Post-Record of Decision Monitoring Plan * Remedial Action/Remedial Design Workplan for the Monticello Mill Tailings Site Operable Unit III MRAP DOE is continuing discussions with the City of Monticello concerning adequate restoration of the former millsite. On July 27, the DOE Contracting Officer wrote a letter insisting that the City of Monticello explain its plans to remedy the failure of the restoration of the Monticello Millsite as required under a Cooperative Agreement between the City and DOE.

129

Controlling Beryllium Contaminated Material And Equipment For The Building 9201-5 Legacy Material Disposition Project  

SciTech Connect

This position paper addresses the management of beryllium contamination on legacy waste. The goal of the beryllium management program is to protect human health and the environment by preventing the release of beryllium through controlling surface contamination. Studies have shown by controlling beryllium surface contamination, potential airborne contamination is reduced or eliminated. Although there are areas in Building 9201-5 that are contaminated with radioactive materials and mercury, only beryllium contamination is addressed in this management plan. The overall goal of this initiative is the compliant packaging and disposal of beryllium waste from the 9201-5 Legacy Material Removal (LMR) Project to ensure that beryllium surface contamination and any potential airborne release of beryllium is controlled to levels as low as practicable in accordance with 10 CFR 850.25.

Reynolds, T. D.; Easterling, S. D.

2010-10-01T23:59:59.000Z

130

Contruction of User Facilities for the Proton Beam Utilization of PEFP (Proton Engineering Frontier Project)  

E-Print Network (OSTI)

Contruction of User Facilities for the Proton Beam Utilization of PEFP (Proton Engineering Frontier Project)

Kim, K R; Lee, H R; Nam, K Y; Park, B S

2003-01-01T23:59:59.000Z

131

SRS - Programs - Liquid Waste Disposition  

NLE Websites -- All DOE Office Websites (Extended Search)

Liquid Waste Disposition Liquid Waste Disposition This includes both the solidification of highly radioactive liquid wastes stored in SRS's tank farms and disposal of liquid low-level waste generated as a by-product of the separations process and tank farm operations. This low-level waste is treated in the Effluent Treatment Facility. High-activity liquid waste is generated at SRS as by-products from the processing of nuclear materials for national defense, research and medical programs. The waste, totaling about 36 million gallons, is currently stored in 49 underground carbon-steel waste tanks grouped into two "tank farms" at SRS. While the waste is stored in the tanks, it separates into two parts: a sludge that settles on the bottom of the tank, and a liquid supernate that resides on top of the sludge. The waste is reduced to about 30 percent of its original volume by evaporation. The condensed evaporator "overheads" are transferred to the Effluent Treatment Project for final cleanup prior to release to the environment. As the concentrate cools a portion of it crystallizes forming solid saltcake. The concentrated supernate and saltcake are less mobile and therefore less likely to escape to the environment in the event of a tank crack or leak.

132

Western Area Power Administration, Desert Southwest Region Facilities Ratings Project  

NLE Websites -- All DOE Office Websites (Extended Search)

Facilities Ratings Project Facilities Ratings Project Hoover-Mead #1 and #5 230-kV and Mead-Marketplace 500-kV Transmission Lines Continuation Sheet Project Description (Continued) Hoover-Mead # 1 230-kV Transmission Line Along the Hoover-Mead #1 230-kV transmission line, the existing line will be reconductored between structures 0/4 and 4/2, about 3.5 linear miles. Structure 0/4 is located northeast of Mead Substation; structure 4/2 is located southeast of Boulder City Tap. The scope of work for the reconductoring includes the following: * At tangent structures (where there is no change in the angle of the transmission line), pulleys or travelers will be installed where the existing conductor attaches to the insulator. The old conductor will be pulled out through the travelers and new wire will be pulled in. A bucket truck

133

Plutonium Disposition Program | National Nuclear Security Administration  

National Nuclear Security Administration (NNSA)

Plutonium Disposition Program Plutonium Disposition Program Home > About Us > Our Programs > Nonproliferation > Fissile Materials Disposition > Plutonium Disposition Program Plutonium Disposition Program The U.S.-Russia Plutonium Management and Disposition Agreement (PMDA), which entered into force on July 13, 2011, commits each country to dispose of at least 34 metric tons (MT) of weapon-grade plutonium withdrawn from their respective nuclear weapon programs. The U.S. remains firmly committed to its PMDA obligation to dispose of excess weapons plutonium. U.S. Plutonium Disposition The current U.S. plan to dispose of 34 MT of weapon-grade plutonium is to fabricate it into Mixed Oxide (MOX) fuel and irradiate it in existing light water reactors. This approach requires construction of new facilities

134

NOMINATION FOR THE PROJECT MANAGEMENT INSTITUTE (PMI) PROJECT OF THE YEAR AWARD INTEGRATED DISPOSAL FACILITY (IDF)  

Science Conference Proceedings (OSTI)

CH2M HILL Hanford Group, Inc. (CH2M HILL) is pleased to nominate the Integrated Disposal Facility (IDF) project for the Project Management Institute's consideration as 2007 Project of the Year, Built for the U.S, Department of Energy's (DOE) Office of River Protection (ORP) at the Hanford Site, the IDF is the site's first Resource Conservation and Recovery Act (RCRA)-compliant disposal facility. The IDF is important to DOE's waste management strategy for the site. Effective management of the IDF project contributed to the project's success. The project was carefully managed to meet three Tri-Party Agreement (TPA) milestones. The completed facility fully satisfied the needs and expectations of the client, regulators and stakeholders. Ultimately, the project, initially estimated to require 48 months and $33.9 million to build, was completed four months ahead of schedule and $11.1 million under budget. DOE directed construction of the IDF to provide additional capacity for disposing of low-level radioactive and mixed (i.e., radioactive and hazardous) solid waste. The facility needed to comply with federal and Washington State environmental laws and meet TPA milestones. The facility had to accommodate over one million cubic yards of the waste material, including immobilized low-activity waste packages from the Waste Treatment Plant (WTP), low-level and mixed low-level waste from WTP failed melters, and alternative immobilized low-activity waste forms, such as bulk-vitrified waste. CH2M HILL designed and constructed a disposal facility with a redundant system of containment barriers and a sophisticated leak-detection system. Built on a 168-area, the facility's construction met all regulatory requirements. The facility's containment system actually exceeds the state's environmental requirements for a hazardous waste landfill. Effective management of the IDF construction project required working through highly political and legal issues as well as challenges with permitting, scheduling, costs, stakeholders and technical issues. To meet the customer's needs and deadlines, the project was managed with conscientious discipline and application of sound project management principles in the Project Management Institute's Project Management Body of Knowledge. Several factors contributed to project success. Extensive planning and preparation were conducted, which was instrumental to contract and procurement management. Anticipating issues and risks, CH2M HILL prepared well defined scope and expectations, particularly for safety. To ensure worker safety, the project management team incorporated CH2M HILL's Integrated Safety Management System (ISMS) into the project and included safety requirements in contracting documents and baseline planning. The construction contractor DelHur Industries, Inc. adopted CH2M HILL's safety program to meet the procurement requirement for a comparable ISMS safety program. This project management approach contributed to an excellent safety record for a project with heavy equipment in constant motion and 63,555 man-hours worked. The project manager worked closely with ORP and Ecology to keep them involved in project decisions and head off any stakeholder or regulatory concerns. As issues emerged, the project manager addressed them expeditiously to maintain a rigorous schedule. Subcontractors and project contributors were held to contract commitments for performance of the work scope and requirements for quality, budget and schedule. Another element of project success extended to early and continual involvement of all interested in the project scope. Due to the public sensitivity of constructing a landfill planned for radioactive waste as well as offsite waste, there were many stakeholders and it was important to secure their agreement on scope and time frames. The project had multiple participants involved in quality assurance surveillances, audits and inspections, including the construction contractor, CH2M HILL, ORP, the Washington State Department of Ecology, and independent certified quality assurance an

MCLELLAN, G.W.

2007-02-07T23:59:59.000Z

135

Isotopes facilities deactivation project at Oak Ridge National Laboratory  

Science Conference Proceedings (OSTI)

The production and distribution of radioisotopes for medical, scientific, and industrial applications has been a major activity at Oak Ridge National Laboratory (ORNL) since the late 1940s. As the demand for many of these isotopes grew and their sale became profitable, the technology for the production of the isotopes was transferred to private industry, and thus, many of the production facilities at ORNL became underutilized. In 1989, the U.S. Department of Energy (DOE) instructed ORNL to identify and prepare various isotopes production facilities for safe shutdown. In response, ORNL identified 19 candidate facilities for shutdown and established the Isotopes Facilities Shutdown Program. In 1993, responsibility for the program was transitioned from the DOE Office of Nuclear Energy to the DOE Office of Environmental Management and Uranium Enrichment Operation`s Office of Facility Transition and Management. The program was retitled the Isotopes Facilities Deactivation Project (IFDP), and implementation responsibility was transferred from ORNL to the Lockheed Martin Energy Systems, Inc. (LMES), Environmental Restoration (ER) Program.

Eversole, R.E.

1997-05-01T23:59:59.000Z

136

SRS - Area Completion Projects - Federal Facility Agreement and Supporting  

NLE Websites -- All DOE Office Websites (Extended Search)

5/2013 5/2013 SEARCH GO spacer Administrative Record File/Information Repository File Federal Facility Agreement and Supporting Documentation General Information and Technologies Public Involvement Home SRS Home Area Completion Projects Federal Facility Agreement and Supporting Documentation * Federal Facility Agreement -The document that directs the comprehensive remediation of the Savannah River Site Appendix Affected by Modification: Appendix D Issuance of EPA and SCDHEC approved Revision.0 Appendix D for Fiscal Year 2013 (Print Date: 08/27/2013). The SCDHEC provided a comment on the Revision 0 Appendix D for Fiscal Year 2013 (Print Date: 08/27/2013) on Spetember 26, 2013. The EPA provided conditional approval, pending resolution of the SCDHEC's comment, of theRevision 0 Appendix D for Fiscal Year 2013 (Print Date: 08/27/2013) on October 30, 2013.

137

Mixed and Low-Level Waste Treatment Facility Project  

SciTech Connect

Mixed and low-level wastes generated at the Idaho National Engineering Laboratory (INEL) are required to be managed according to applicable State and Federal regulations, and Department of Energy Orders that provide for the protection of human health and the environment. The Mixed and Low-Level Waste Treatment Facility Project was chartered in 1991, by the Department of Energy to provide treatment capability for these mixed and low-level waste streams. The first project task consisted of conducting engineering studies to identify the waste streams, their potential treatment strategies, and the requirements that would be imposed on the waste streams and the facilities used to process them. This report documents those studies so the project can continue with an evaluation of programmatic options, system tradeoff studies, and the conceptual design phase of the project. This report, appendix B, comprises the engineering design files for this project study. The engineering design files document each waste steam, its characteristics, and identified treatment strategies.

1992-04-01T23:59:59.000Z

138

Mixed and Low-Level Waste Treatment Facility project  

SciTech Connect

Mixed and low-level wastes generated at the Idaho National Engineering Laboratory (INEL) are required to be managed according to applicable State and Federal regulations, and Department of Energy Orders that provide for the protection of human health and the environment. The Mixed and Low-Level Waste Treatment Facility Project was chartered in 1991, by the Department of Energy to provide treatment capability for these mixed and low-level waste streams. The first project task consisted of conducting engineering studies to identify the waste streams, their potential treatment strategies, and the requirements that would be imposed on the waste streams and the facilities used to process them. This report, Appendix A, Environmental Regulatory Planning Documentation, identifies the regulatory requirements that would be imposed on the operation or construction of a facility designed to process the INEL's waste streams. These requirements are contained in five reports that discuss the following topics: (1) an environmental compliance plan and schedule, (2) National Environmental Policy Act requirements, (3) preliminary siting requirements, (4) regulatory justification for the project, and (5) health and safety criteria.

1992-04-01T23:59:59.000Z

139

Near Facility Environmental Monitoring Quality Assurance Project Plan  

SciTech Connect

This Quality Assurance Project Plan addresses the quality assurance requirements for the activities associated with the preoperational and near-facility environmental monitoring directed by Waste Management Technical Services and supersedes HNF-EP-0538-4. This plan applies to all sampling and monitoring activities performed by Waste Management Technical Services in implementing near-facility environmental monitoring at the Hanford Site. This Quality Assurance Project Plan is required by U.S. Department of Energy Order 5400.1 (DOE 1990) as a part of the Environmental Monitoring Plan (DOE-RL 1997) and is used to define: Environmental measurement and sampling locations used to monitor environmental contaminants near active and inactive facilities and waste storage and disposal sites; Procedures and equipment needed to perform the measurement and sampling; Frequency and analyses required for each measurement and sampling location; Minimum detection level and accuracy; Quality assurance components; and Investigation levels. Near-facility environmental monitoring for the Hanford Site is conducted in accordance with the requirements of U.S. Department of Energy Orders 5400.1 (DOE 1990), 5400.5 (DOE 1993), 5484.1 (DOE 1990), and 435.1 (DOE 1999), and DOE/EH-O173T (DOE 1991). It is Waste Management Technical Services' objective to manage and conduct near-facility environmental monitoring activities at the Hanford Site in a cost-effective and environmentally responsible manner that is in compliance with the letter and spirit of these regulations and other environmental regulations, statutes, and standards.

MCKINNEY, S.M.

2000-05-01T23:59:59.000Z

140

Mixed and Low-Level Waste Treatment Facility project  

SciTech Connect

Mixed and low-level wastes generated at the Idaho National Engineering Laboratory (INEL) are required to be managed according to applicable State and Federal regulations, and Department of Energy Orders that provide for the protection of human health and the environment. The Mixed and Low-Level Waste Treatment Facility Project was chartered in 1991, by the Department of Energy to provide treatment capability for these mixed and low-level waste streams. The first project task consisted of conducting engineering studies to identify the waste streams, their potential treatment strategies, and the requirements that would be imposed on the waste streams and the facilities used to process them. The engineering studies, initiated in July 1991, identified 37 mixed waste streams, and 55 low-level waste streams. This report documents the waste stream information and potential treatment strategies, as well as the regulatory requirements for the Department of Energy-owned treatment facility option. The total report comprises three volumes and two appendices. This report consists of Volume 1, which explains the overall program mission, the guiding assumptions for the engineering studies, and summarizes the waste stream and regulatory information, and Volume 2, the Waste Stream Technical Summary which, encompasses the studies conducted to identify the INEL's waste streams and their potential treatment strategies.

1992-04-01T23:59:59.000Z

Note: This page contains sample records for the topic "facility disposition project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


141

Environmental Restoration Disposal Facility (Project W-296) Safety Assessment  

SciTech Connect

This Safety Assessment is based on information derived from the Conceptual Design Report for the Environmental Restoration Disposal Facility (DOE/RL 1994) and ancillary documentation developed during the conceptual design phase of Project W-296. The Safety Assessment has been prepared to support the Solid Waste Burial Ground Interim Safety Basis document. The purpose of the Safety Assessment is to provide an evaluation of the design to determine if the process, as proposed, will comply with US Department of Energy (DOE) Limits for radioactive and hazardous material exposures and be acceptable from an overall health and safety standpoint. The evaluation considered affects on the worker, onsite personnel, the public, and the environment.

Armstrong, D.L.

1994-08-01T23:59:59.000Z

142

ESTIMATING IMPURITIES IN SURPLUS PLUTONIUM FOR DISPOSITION  

Science Conference Proceedings (OSTI)

The United States holds at least 61.5 metric tons (MT) of plutonium that is permanently excess to use in nuclear weapons programs, including 47.2 MT of weapons-grade plutonium. Surplus inventories will be stored safely by the Department of Energy (DOE) and then transferred to facilities that will prepare the plutonium for permanent disposition. The Savannah River National Laboratory (SRNL) operates a Feed Characterization program for the Office of Fissile Materials Disposition of the National Nuclear Security Administration and the DOE Office of Environmental Management. Many of the items that require disposition are only partially characterized, and SRNL uses a variety of techniques to predict the isotopic and chemical properties that are important for processing through the Mixed Oxide Fuel Fabrication Facility and alternative disposition paths. Recent advances in laboratory tools, including Prompt Gamma Analysis and Peroxide Fusion treatment, provide data on the existing inventories that will enable disposition without additional, costly sampling and destructive analysis.

Allender, J.; Moore, E.

2013-07-17T23:59:59.000Z

143

Plutonium Disposition Program | National Nuclear Security Administrati...  

NLE Websites -- All DOE Office Websites (Extended Search)

Plutonium Disposition Program Home > About Us > Our Programs > Nonproliferation > Fissile Materials Disposition > Plutonium Disposition Program Plutonium Disposition Program The...

144

MSGOUID MONTICELLO PROJECTS ·FEDERAL FACILITIES AGREEMENT REPORT  

Office of Legacy Management (LM)

MSGOUID MSGOUID MONTICELLO PROJECTS ·FEDERAL FACILITIES AGREEMENT REPORT Report Period: Aprill -June 30, 2006 DOE Project Coordinator: Art Kleinrath HIGHLIGHTS DOE submitted the draft Consolidated LTSM Administrative mid Operating Procedures Manual to EPA and UDEQ on May 4, 2006. Document transmittal met the stipulated penalty milestone of May 6, 2006. Semi-annual ground water and surface water monitoring was completed in May 2006 as scheduled. Three FY 2006 Program Directives were prepared and issued for bio-monitoring tasks to assess selenium accumulation in the environment and identify potential ecological receptors. All field work for FY 2006 bio-monitoring task was completed (five waterfowl surveys in May and June, sediment and surface water sample collection in April for selenium analysis,

145

Natural Gas Procurement Challenges for a Project Financed Cogeneration Facility  

E-Print Network (OSTI)

A decision to project finance a 110 megawatt combined cycle cogeneration facility in 1986 in place of conventional internal financing greatly changed the way in which natural gas was normally procured by Union Carbide Corporation. Natural gas supply security for the term of financing was a major concern of the financing interest, while competitive fuel cost greatly concerned Union Carbide. In addition, the natural gas contract had to be in place prior to construction financing finalization. This paper will explore the thought process that went into evaluating the various natural gas supply proposals that ultimately resulted in the final contractual arrangements. While the information presented will be deliberately non-specific to the suppliers involved or the contractual terms, the discussion will cover the following areas: PROJECT FINANCING REQUIREMENTS, GAS SUPPLY CONSIDERATIONS, SUPPLY TRANSPORTATION EXPEDITIOUS INTERNAL APPROVAL, and SUPPLIER INTANGIBLES.

Good, R. L.; Calvert, T. B.; Pavlish, B. A.

1988-09-01T23:59:59.000Z

146

DOE/EIS-0287 Idaho High-Level Waste & Facilities Disposition Draft Environmental Impact Statement (December 1999)  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

HLW & FD EIS HLW & FD EIS 3-13 DOE/EIS-0287D Calcine storag e i n b i n s ets Calcine storag e i n b i n s et s Cesium ion exchange & grouting Cesium ion exchange & grouting NWCF* NWCF* Calcine Mixed transuranic waste/SBW Mixed transuranic waste/NGLW Low-level waste disposa l*** disposa l*** Tank heels Transuranic waste (from tank heels) * * * * Mixed transuranic waste/ NGLW Mixed transuranic waste/ NGLW M i x e d t r a nsuran ic w a s t e / M i x e d t r a nsuran ic w a s t e / S B W s t o rage in Ta n k F a r m S B W s t o rage in Ta n k F a r m Low-leve l waste Low-leve l waste FIGURE 3-2. Continued Current Operations Alternative. LEGEND * Including high-temperature and maximum achievable control technology upgrades. Mixed transuranic waste/ newly generated liquid waste New Waste Calcining Facility ** Calcine would be transferred from bin set #1 to bin set #6 or #7.

147

Tritium Facilities Modernization and Consolidation Project Process Waste Assessment (Project S-7726)  

Science Conference Proceedings (OSTI)

Under the Tritium Facility Modernization {ampersand} Consolidation (TFM{ampersand}C) Project (S-7726) at the Savannah River Site (SS), all tritium processing operations in Building 232-H, with the exception of extraction and obsolete/abandoned systems, will be reestablished in Building 233-H. These operations include hydrogen isotopic separation, loading and unloading of tritium shipping and storage containers, tritium recovery from zeolite beds, and stripping of nitrogen flush gas to remove tritium prior to stack discharge. The scope of the TFM{ampersand}C Project also provides for a new replacement R&D tritium test manifold in 233-H, upgrading of the 233- H Purge Stripper and 233-H/234-H building HVAC, a new 234-H motor control center equipment building and relocating 232-H Materials Test Facility metallurgical laboratories (met labs), flow tester and life storage program environment chambers to 234-H.

Hsu, R.H. [Westinghouse Savannah River Company, AIKEN, SC (United States); Oji, L.N.

1997-11-14T23:59:59.000Z

148

Facility stabilization project, fiscal year 1998 -- Multi-year workplan (MYWP) for WBS 1.4  

SciTech Connect

The primary Facility Stabilization mission is to provide minimum safe surveillance and maintenance of facilities and deactivate facilities on the Hanford Site, to reduce risks to workers, the public and environment, transition the facilities to a low cost, long term surveillance and maintenance state, and to provide safe and secure storage of special nuclear materials, nuclear materials, and nuclear fuel. Facility Stabilization will protect the health and safety of the public and workers, protect the environment and provide beneficial use of the facilities and other resources. Work will be in accordance with the Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement), local, national, international and other agreements, and in compliance with all applicable Federal, state, and local laws. The stakeholders will be active participants in the decision processes including establishing priorities, and in developing a consistent set of rules, regulations, and laws. The work will be leveraged with a view of providing positive, lasting economic impact in the region. Effectiveness, efficiency, and discipline in all mission activities will enable Hanford Site to achieve its mission in a continuous and substantive manner. As the mission for Facility Stabilization has shifted from production to support of environmental restoration, each facility is making a transition to support the Site mission. The mission goals include the following: (1) Achieve deactivation of facilities for transfer to EM-40, using Plutonium Uranium Extraction (PUREX) plant deactivation as a model for future facility deactivation; (2) Manage nuclear materials in a safe and secure condition and where appropriate, in accordance with International Atomic Energy Agency (IAEA) safeguards rules; (3) Treat nuclear materials as necessary, and store onsite in long-term interim safe storage awaiting a final disposition decision by US Department of Energy; (4) Implement nuclear materials disposition directives. In the near term these are anticipated to mostly involve transferring uranium to other locations for beneficial use. Work will be in accordance with the Tri-Party Agreement, and other agreements and in compliance with all applicable Federal, state and local laws. The transition to deactivation will be accomplished through a phased approach, while maintaining the facilities in a safe and compliant configuration. In addition, Facility Stabilization will continue to maintain safe long-term storage facilities for Special Nuclear Material (SNM), Nuclear Material (NM), and Nuclear Fuel (NF). The FSP deactivation strategy aligns with the deactivate facilities mission outlined in Hanford Site SE documentation. Inherent to the FSP strategies are specific Hanford Strategic Plan success indicators such as: reduction of risks to workers, the public and environment; increasing the amount of resources recovered for other uses; reduction/elimination of inventory and materials; and reduction/elimination of costly mortgages.

Floberg, W.C.

1997-09-30T23:59:59.000Z

149

Project definition study for research facility access and science education  

SciTech Connect

This UTA/SMU project definition study describes critical customer services and research programs which draw upon SSC assets to meet regional needs in two major components: Science Education; Academic/Small Business R and D Facility Access. The location of the SSC in Texas constituted a significant stimulus to R and D activities in Texas, encouraging new initiatives in high energy physics, as well as stimulating other areas of physics and related sciences. An important aspect of maximizing the utility of the investment in the SSC should be to re-allocate SSC assets in ways that maintain that momentum. This study addresses several ways to achieve that end, extending benefits to all of physics, the sciences in general and particularly, to science education.

Rosen, S.P. [Univ. of Texas, Arlington, TX (United States). Coll. of Science; Teplitz, V.L. [Southern Methodist Univ., Dallas, TX (United States). Physics Dept.

1994-10-01T23:59:59.000Z

150

Project management plan for the Isotopes Facilities Deactivation Project at Oak Ridge National Laboratory. Environmental Restoration Program  

Science Conference Proceedings (OSTI)

The purpose of the Isotopes Facilities Deactivation Project (IFDP) is to place nineteen former isotopes production facilities at the Oak Ridge National Laboratory in a safe, stable, and environmentally sound condition suitable for an extended period of minimum surveillance and maintenance (S&M) and as quickly and economically as possible. Implementation and completion of the deactivation project win further reduce the already small risks to the environment and to public safety and health. Furthermore, the project should result in significant S&M cost savings in the future. The IFDP management plan has been prepared to document the project objectives, define organizational relationships and responsibilities, and outline the management control systems to be employed in the management of the project. The project has adopted a strategy to deactivate the simple facilities first, to reduce the scope of the project, and to gain experience before addressing more difficult facilities. A decision support system is being developed to identify those activities that best promote the project mission and result in largest cost savings. The Work Plan for the Isotopes Facilities Deactivation Project at Oak Ridge National Laboratory (Energy Systems 1994) defines the project schedule, the cost estimate, and the technical approach for the project.

NONE

1995-04-01T23:59:59.000Z

151

Request For Records Disposition Authority: Strategic Petroleum Reserve  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Request For Records Disposition Authority: Strategic Petroleum Request For Records Disposition Authority: Strategic Petroleum Reserve Project Management Office Request For Records Disposition Authority: Strategic Petroleum Reserve Project Management Office Paper case files pertaining to environmental permit applications, permits and related correspondence as well as NEPA correspondence within of the Strategic Petroleum Reserve Project Management Office (SPRPMO) Request For Records Disposition Authority: Strategic Petroleum Reserve Project Management Office More Documents & Publications 2012 Annual Planning Summary for Fossil Energy, National Energy Technology Laboratory, RMOTC, and Strategic Petroleum Reserve Field Office CX-002673: Categorical Exclusion Determination CX-009794: Categorical Exclusion Determination

152

DOE Chooses Idaho Treatment Group, LLC to Disposition Waste at...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Chooses Idaho Treatment Group, LLC to Disposition Waste at the Advanced Mixed Waste Treatment Project: Contract will continue cleanup and waste operations at the Idaho Site DOE...

153

EA-0930: Facility Operations at the U.S. DOE Grand Junction Projects  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

30: Facility Operations at the U.S. DOE Grand Junction 30: Facility Operations at the U.S. DOE Grand Junction Projects Office, Grand Junction, Colorado EA-0930: Facility Operations at the U.S. DOE Grand Junction Projects Office, Grand Junction, Colorado SUMMARY This EA evaluates the environmental impacts of the proposal to expand and upgrade the U.S. Department of Energy's Grand Junction Projects Office facilities and operations in Grand Junction, Colorado. PUBLIC COMMENT OPPORTUNITIES None available at this time. DOCUMENTS AVAILABLE FOR DOWNLOAD June 8, 1996 EA-0930: Finding of No Significant Impact Facility Operations at the U.S. DOE Grand Junction Projects Office, Grand Junction, Colorado June 8, 1996 EA-0930: Final Environmental Assessment Facility Operations at the U.S. DOE Grand Junction Projects Office, Grand

154

Treatment Facility F: Accelerated Removal and Validation Project  

Science Conference Proceedings (OSTI)

The Accelerated Removal and Validation (ARV) phase of remediation at the Treatment Facility F (TFF) site at Lawrence Livermore National Laboratory (LLNL) was designed to accelerate removal of gasoline from the site when compared to normal, single shift, pump-and-treat operations. The intent was to take advantage of the in-place infrastructure plus the increased underground temperatures resulting from the Dynamic Underground Stripping Demonstration Project (DUSDP). Operations continued 24-hours (h) per day between October 4 and December 12, 1993. Three contaminant removal rate enhancement approaches were explored during the period of continuous operation. First, we tried several configurations of the vapor pumping system to maximize the contaminant removal rate. Second, we conducted two brief trials of air injection into the lower steam zone. Results were compared with computer models, and the process was assessed for contaminant removal rate enhancement. Third, we installed equipment to provide additional electrical heating of contaminated low-permeability soil. Four new electrodes were connected into the power system. Diagnostic capabilities at the TFF site were upgraded so that we could safely monitor electrical currents, soil temperatures, and water treatment system processes while approximately 300 kW of electrical energy was being applied to the subsurface.

Sweeney, J.J.; Buettner, M.H.; Carrigan, C.R. [and others

1994-04-01T23:59:59.000Z

155

Mixed and Low-Level Treatment Facility Project  

SciTech Connect

This appendix contains the mixed and low-level waste engineering design files (EDFS) documenting each low-level and mixed waste stream investigated during preengineering studies for Mixed and Low-Level Waste Treatment Facility Project. The EDFs provide background information on mixed and low-level waste generated at the Idaho National Engineering Laboratory. They identify, characterize, and provide treatment strategies for the waste streams. Mixed waste is waste containing both radioactive and hazardous components as defined by the Atomic Energy Act and the Resource Conservation and Recovery Act, respectively. Low-level waste is waste that contains radioactivity and is not classified as high-level waste, transuranic waste, spent nuclear fuel, or 11e(2) byproduct material as defined by DOE 5820.2A. Test specimens of fissionable material irradiated for research and development only, and not for the production of power or plutonium, may be classified as low-level waste, provided the concentration of transuranic is less than 100 nCi/g. This appendix is a tool that clarifies presentation format for the EDFS. The EDFs contain waste stream characterization data and potential treatment strategies that will facilitate system tradeoff studies and conceptual design development. A total of 43 mixed waste and 55 low-level waste EDFs are provided.

1992-04-01T23:59:59.000Z

156

Status of the National Ignition Facility Project, IG-0598 | Department...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

conventional facility; laser system; target experimental system; integrated computers and controls; assembly, installation, and refurbishment equipment; and utilities. To...

157

Office of UNF Disposition International Program - Strategic Plan |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

UNF Disposition International Program - Strategic Plan UNF Disposition International Program - Strategic Plan Office of UNF Disposition International Program - Strategic Plan The Department of Energy's Office of Nuclear Energy, Used Nuclear Fuel Disposition Research and Development Office (UFD), performs the critical mission of addressing the need for an integrated strategy that combines safe storage of spent nuclear fuel with expeditious progress toward siting and licensing a disposal facility or facilities. The UFD International Program plays a key role in this effort. International collaboration provides a forum for exchanging strategies, expertise, and technologies with other nations that have also been investigating solutions to the problems of nuclear waste disposal-information that otherwise would have

158

BIOLOGICAL EVIDENCE disposition process  

Science Conference Proceedings (OSTI)

... Notification of destruction sent per statutory requirements In-house tickler system tracks evidence and identifies upcoming disposition time ...

2013-05-14T23:59:59.000Z

159

PROJECT MANGEMENT PLAN EXAMPLES Facility End State Decisions Examples  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Facility End State Decisions Examples Facility End State Decisions Examples Example 3 3.0 POST DEACTIVATION END STATE VISION The Heavy Water Facility is scheduled to cease moderator operations and commence final shutdown of moderator processing and processing support systems. The Heavy Water Facility and supporting facilities will be declared excess. Deactivation will place the facilities into a passively safe, minimal cost, long term S&M mode. At the end of the deactivation period, the facilities will be categorized "Radiological" and "Other Industrial Use". The following deactivation end state is envisioned: Moderator Processing and Moderator Storage Buildings The deactivation of the moderator processing and storage buildings will remove the moderator storage drums

160

Assessment of Nuclear Safety Culture at the Salt Waste Processing Facility Project  

NLE Websites -- All DOE Office Websites (Extended Search)

Oversight Assessment of Oversight Assessment of Nuclear Safety Culture at the Salt Waste Processing Facility Project May 2011 January 2013 Office of Safety and Emergency Management Evaluations Office of Enforcement and Oversight Office of Health, Safety and Security U.S. Department of Energy Independent Oversight Assessment of Nuclear Safety Culture at the Salt Waste Processing Facility Project

Note: This page contains sample records for the topic "facility disposition project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


161

Assessment of Nuclear Safety Culture at the Salt Waste Processing Facility Project  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Oversight Assessment of Oversight Assessment of Nuclear Safety Culture at the Salt Waste Processing Facility Project May 2011 January 2013 Office of Safety and Emergency Management Evaluations Office of Enforcement and Oversight Office of Health, Safety and Security U.S. Department of Energy Independent Oversight Assessment of Nuclear Safety Culture at the Salt Waste Processing Facility Project

162

EM Opens New Waste Repackaging Facility at Laboratory | Department of  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Opens New Waste Repackaging Facility at Laboratory Opens New Waste Repackaging Facility at Laboratory EM Opens New Waste Repackaging Facility at Laboratory March 7, 2013 - 12:00pm Addthis A view of the new facility where transuranic waste will be repackaged at Los Alamos National Laboratory. A view of the new facility where transuranic waste will be repackaged at Los Alamos National Laboratory. EM Deputy Assistant Secretary for Waste Management Frank Marcinowski, left, talks with LANL’s Oversized Container Disposition Project Manager Mike Romero while on a tour of the 375 box line facility in late February. EM Deputy Assistant Secretary for Waste Management Frank Marcinowski, left, talks with LANL's Oversized Container Disposition Project Manager Mike Romero while on a tour of the 375 box line facility in late February.

163

Capturing Process Knowledge for Facility Deactivation and Decommissioning  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Tech Assistance Tech Assistance Savannah River National Laboratory- Assess Adequacy of Process Knowledge for D&D Guidance for Determining Adequacy of Process Knowledge Page 1 of 2 Savannah River National Laboratory South Carolina Capturing Process Knowledge for Facility Deactivation and Decommissioning Challenge The Office of Environmental Management (EM) is responsible for the disposition of a vast number of facilities at numerous sites around the country which have been declared excess to current mission needs. When such excess facilities are scheduled for deactivation and decommissioning (D&D), among the tasks the responsible project team is faced with include the evaluation and planning for the removal, characterization, and disposition of all legacy

164

Community- and Facility-Scale Renewable Energy Project Development and Finance Workshop  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Community- and Facility-Scale Renewable Energy Project Development and Finance Workshop Community- and Facility-Scale Renewable Energy Project Development and Finance Workshop September 18-20, 2013 AGENDA (DRAFT September 5, 2013) Learning Objectives 1) Understand the process for and potential pitfalls of developing and financing community- and facility-scale renewable energy projects 2) Determine how the development of a renewable energy project could further a Tribe's goals 3) Learn from the experience of other Tribal efforts in renewable energy development Anticipated Results: Attendees will be comfortable discussing renewable energy project development possibilities with project developers and project financing options with potential investors. Potential Tribal roles will be clear and participants will better understand the five-step project development and financing process.

165

Idaho Spent Fuel Facility (ISFF) Project, Appropriate Acquisition...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Strategy Lessons Learned Report Feb 2011.pdf More Documents & Publications Highly Enriched Uranium Materials Facility, Major Design Changes Late...Lessons Learned Report, NNSA,...

166

EA-1917: Wave Energy Test Facility Project, Newport, OR | Department of  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

17: Wave Energy Test Facility Project, Newport, OR 17: Wave Energy Test Facility Project, Newport, OR EA-1917: Wave Energy Test Facility Project, Newport, OR SUMMARY This EA evaluates the potential environmental impacts of a Wave Energy Test Facility that will be located near Newport, Oregon. The testing facility will be located within Oregon territorial waters, near the Hatfield Marine Science Center and close to onshore roads and marine support services. The site will not only allow testing of new wave energy technologies, but will also be used to help study any potential environmental impacts on sediments, invertebrates and fish. The project is being jointly funded by the State of Oregon and DOE. PUBLIC COMMENT OPPORTUNITIES None available at this time. DOCUMENTS AVAILABLE FOR DOWNLOAD August 15, 2012 EA-1917: Mitigation Action Plan

167

EA-1917: Wave Energy Test Facility Project, Newport, OR | Department of  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

17: Wave Energy Test Facility Project, Newport, OR 17: Wave Energy Test Facility Project, Newport, OR EA-1917: Wave Energy Test Facility Project, Newport, OR SUMMARY This EA evaluates the potential environmental impacts of a Wave Energy Test Facility that will be located near Newport, Oregon. The testing facility will be located within Oregon territorial waters, near the Hatfield Marine Science Center and close to onshore roads and marine support services. The site will not only allow testing of new wave energy technologies, but will also be used to help study any potential environmental impacts on sediments, invertebrates and fish. The project is being jointly funded by the State of Oregon and DOE. PUBLIC COMMENT OPPORTUNITIES None available at this time. DOCUMENTS AVAILABLE FOR DOWNLOAD August 15, 2012 EA-1917: Mitigation Action Plan

168

Status Review of Wildlife Mitigation, Columbia Basin Hydroelectric Projects, Columbia River Mainstem Facilities, 1984 Final Report.  

DOE Green Energy (OSTI)

This report reviews the status of past, present, and proposed future wildlife planning and mitigation programs at existing hydroelectric projects in the Columbia River Basin. The project evaluations will form the basis for determining any needed remedial measures or additional project analysis. Each hydropower facility report is abstracted separately for inclusion in the Energy Data Base.

Howerton, Jack; Hwang, Diana

1984-11-01T23:59:59.000Z

169

Spent nuclear fuel project cold vacuum drying facility operations manual  

SciTech Connect

This document provides the Operations Manual for the Cold Vacuum Drying Facility (CVDF). The Manual was developed in conjunction with HNF-SD-SNF-SAR-002, Safety Analysis Report for the Cold Vacuum Drying Facility, Phase 2, Supporting Installation of Processing Systems (Garvin 1998) and, the HNF-SD-SNF-DRD-002, 1997, Cold Vacuum Drying Facility Design Requirements, Rev. 3a. The Operations Manual contains general descriptions of all the process, safety and facility systems in the CVDF, a general CVD operations sequence, and has been developed for the SNFP Operations Organization and shall be updated, expanded, and revised in accordance with future design, construction and startup phases of the CVDF until the CVDF final ORR is approved.

IRWIN, J.J.

1999-05-12T23:59:59.000Z

170

Projects at the Component Development and Integration Facility. Quarterly technical progress report, July 1--September 30, 1993  

DOE Green Energy (OSTI)

This quarterly technical progress report presents progress on the projects at the Component Development and Integration Facility (CDIF) during the first quarter of FY94. The CDIF is a major US Department of Energy test facility in Butte, Montana, operated by MSE, Inc. Projects in progress include: MHD Proof-of-Concept project; mine waste technology pilot program; plasma projects; resource recovery project; sodium sulfide/ferrous sulfate project; soil washing project; and spray casting project.

Not Available

1993-12-31T23:59:59.000Z

171

Projects at the Component Development and Integration Facility. Quarterly technical progress report, October 1--December 31, 1992  

DOE Green Energy (OSTI)

This quarterly technical progress report presents progress on the projects at the component Development and Integration Facility (CDIF) during the first quarter of FY93. The CDIF is a major US Department of Energy (DOE) test facility in Butte, Montana, operated by MSE, Inc. Projects in progress include: MHD proof-of-concept project; mine waste pilot program; plasma projects; resource recovery project; sodium sulfide/ferrous sulfate project; soil washing project; and spray casting project.

Not Available

1992-12-31T23:59:59.000Z

172

Projects at the Component Development and Integration Facility. Quarterly technical progress report, April 1--June 30, 1993  

DOE Green Energy (OSTI)

This quarterly technical progress report presents progress on the projects at the Component Development and Integration Facility (CDIF) during the third quarter of FY93. The CDIF is a major US Department of Energy test facility in Butte, Montana, operated by MSE, Inc. Projects in progress include: MHD Proof-of-Concept Project; Mine Waste Technology Program; Plasma Projects; Resource Recovery Project; Sodium Sulfide/Ferrous Sulfate Project; Soil Washing Project; and Spray Casting Project.

Not Available

1993-12-01T23:59:59.000Z

173

Projects at the Component Development and Integration Facility. Quarterly technical progress report, January 1, 1994--March 31, 1994  

Science Conference Proceedings (OSTI)

This quarterly technical progress report presents progress on the projects at the Component Development and Integration Facility (CDIF) during the second quarter of FY94. The CDIF is a major US Department of Energy test facility in Butte, Montana, operated by MSE, Inc. Projects in progress include: Biomass Remediation Project; Heavy Metal-Contaminated Soil Project; MHD Shutdown; Mine Waste Technology Pilot Program; Plasma Projects; Resource Recovery Project; Sodium Sulfide/Ferrous Sulfate Project; and Spray Casting Project.

Not Available

1994-08-01T23:59:59.000Z

174

Plutonium Consumption Program, CANDU Reactor Project: Feasibility of BNFP Site as MOX Fuel Supply Facility. Final report  

SciTech Connect

An evaluation was made of the technical feasibility, cost, and schedule for converting the existing unused Barnwell Nuclear Fuel Facility (BNFP) into a Mixed Oxide (MOX) CANDU fuel fabrication plant for disposition of excess weapons plutonium. This MOX fuel would be transported to Ontario where it would generate electricity in the Bruce CANDU reactors. Because CANDU MOX fuel operates at lower thermal load than natural uranium fuel, the MOX program can be licensed by AECB within 4.5 years, and actual Pu disposition in the Bruce reactors can begin in 2001. Ontario Hydro will have to be involved in the entire program. Cost is compared between BNFP and FMEF at Hanford for converting to a CANDU MOX facility.

1995-06-30T23:59:59.000Z

175

Work plan for the Isotopes Facilities Deactivation Project at Oak Ridge National Laboratory  

Science Conference Proceedings (OSTI)

The purpose of the Isotopes Facilities Deactivation Project (IFDP) is to place former isotopes production facilities at the Oak Ridge National Laboratory in a safe, stable, and environmentally sound condition; suitable for an extended period of minimum surveillance and maintenance (S&M) and as quickly and economical as possible. Implementation and completion of the deactivation project will further reduce the risks to the environment and to public safety and health. Furthermore, completion of the project will result in significant S&M cost savings in future years. The IFDP work plan defines the project schedule, the cost estimate, and the technical approach for the project. A companion document, the IFDP management plan, has been prepared to document the project objectives, define organizational relationships and responsibilities, and outline the management control systems to be employed in the management of the project. The project has adopted the strategy of deactivating the simple facilities first, to reduce the scope of the project and to gain experience before addressing more difficult facilities. A decision support system is being developed to identify the activities that best promote the project mission and result in the largest cost savings. This work plan will be reviewed and revised annually. Deactivation of IFDP facilities was initiated in FY 1994 and will be completed in FY 1999. The schedule for deactivation of facilities is shown. The total cost of the project is estimated to be $36M. The costs are summarized. Upon completion of deactivation, annual S&M costs of these facilities will be reduced from the current level of $5M per year to less than $1M per year.

NONE

1995-05-01T23:59:59.000Z

176

Work plan for the Isotopes Facilities Deactivation Project at Oak Ridge National Laboratory, Oak Ridge, Tennessee  

Science Conference Proceedings (OSTI)

The purpose of the Isotopes Facilities Deactivation Project (IFDP) is to place former isotopes production facilities at the Oak Ridge National Laboratory in a safe, stable, and environmentally sound condition; suitable for an extended period of minimum surveillance and maintenance (S and M) and as quickly and economical as possible. Implementation and completion of the deactivation project will further reduce the risks to the environment and to public safety and health. Furthermore, completion of the project will result in significant S and M cost savings in future years. The IFDP work plan defines the project schedule, the cost estimate, and the technical approach for the project. A companion document, the EFDP management plan, has been prepared to document the project objectives, define organizational relationships and responsibilities, and outline the management control systems to be employed in the management of the project. The project has adopted the strategy of deactivating the simple facilities first, to reduce the scope of the project and to gain experience before addressing more difficult facilities. A decision support system is being developed to identify the activities that best promote the project mission and result in the largest cost savings. This work plan will be reviewed and revised annually. Deactivation of EFDP Facilities was initiated in FY 1994 and will be completed in FY 2000. The schedule for deactivation of facilities is shown. The total cost of the project is estimated to be $51M. The costs are summarized. Upon completion of deactivation, annual S and M costs of these facilities will be reduced from the current level of $5M per year to less than $1M per year.

NONE

1995-08-01T23:59:59.000Z

177

Community- and Facility-Scale Tribal Renewable Energy Project Workshop to  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Community- and Facility-Scale Tribal Renewable Energy Project Community- and Facility-Scale Tribal Renewable Energy Project Workshop to be Held in September Community- and Facility-Scale Tribal Renewable Energy Project Workshop to be Held in September July 24, 2013 - 12:05pm Addthis The U.S. Department of Energy (DOE) Office of Indian Energy and Office of Energy Efficiency and Renewable Energy's Tribal Energy Program are pleased to present an interactive workshop from September 18-20 in Denver, Colorado, designed to walk tribal leaders and staff through the five steps of developing and financing community- and facility-scale projects on tribal lands. The workshop is part of the Office of Indian Energy's one-of-a-kind renewable energy development education and training curriculum created with support from DOE's National Renewable Energy Laboratory (NREL) to help

178

Preoperational Environmental Survey for the Spent Nuclear Fuel (SNF) Project Facilities  

Science Conference Proceedings (OSTI)

This document represents the report for environmental sampling of soil, vegetation, litter, cryptograms, and small mammals at the Spent Nuclear Fuel Project facilities located in 100 K and 200 East Areas in support of the preoperational environmental survey.

MITCHELL, R.M.

2000-09-28T23:59:59.000Z

179

Development of Facilities Master Plan and Laboratory Renovation Project  

SciTech Connect

Funding from this grant has allowed Morehouse School of Medicine to complete its first professionally developed, comprehensive campus master plan that is in alignment with the recently completed strategic plan. In addition to master planning activities, funds were used for programming and designing research renovations, and also to supplement other research facility upgrades by providing lighting and equipment. The activities funded by this grant will provide the catalyst for substantial improvement in the School??s overall facilities for biomedical education and research, and will also provide much of the information needed to conduct a successful campaign to raise funds for proposed buildings and renovations.

Andrea D. Fox

2011-10-03T23:59:59.000Z

180

Acceptance test procedure: RMW Land Disposal Facility Project W-025  

SciTech Connect

This ATP establishes field testing procedures to demonstrate that the electrical/instrumentation system functions as intended by design for the Radioactive Mixed Waste Land Disposal Facility. Procedures are outlined for the field testing of the following: electrical heat trace system; transducers and meter/controllers; pumps; leachate storage tank; and building power and lighting.

Roscha, V. [Westinghouse Hanford Co., Richland, WA (United States)

1994-12-12T23:59:59.000Z

Note: This page contains sample records for the topic "facility disposition project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


181

Plutonium Reclamation Facility incident response project progress report  

Science Conference Proceedings (OSTI)

This report provides status of Hanford activities in response to process deficiencies highlighted during and in response to the May 14, 1997, explosion at the Plutonium Reclamation Facility. This report provides specific response to the August 4, 1997, memorandum from the Secretary which requested a progress report, in 120 days, on activities associated with reassessing the known and evaluating new vulnerabilities (chemical and radiological) at facilities that have been shut down, are in standby, are being deactivated or have otherwise changed their conventional mode of operation in the last several years. In addition, this report is intended to provide status on emergency response corrective activities as requested in the memorandum from the Secretary on August 28, 1997. Status is also included for actions requested in the second August 28, 1997, memorandum from the Secretary, regarding timely notification of emergencies.

Austin, B.A.

1997-11-25T23:59:59.000Z

182

Beam dynamics simulations and measurements at the Project X Test Facility  

Science Conference Proceedings (OSTI)

Project X, under study at Fermilab, is a multitask high-power superconducting RF proton beam facility, aiming to provide high intensity protons for rare processes experiments and nuclear physics at low energy, and simultaneously for the production of neutrinos, as well as muon beams in the long term. A beam test facility - former known as High Intensity Neutrino Source (HINS) - is under commissioning for testing critical components of the project, e.g. dynamics and diagnostics at low beam energies, broadband beam chopping, RF power generation and distribution. In this paper we describe the layout of the test facility and present beam dynamics simulations and measurements.

Gianfelice-Wendt, E.; Scarpine, V.E.; Webber, R.C.; /Fermilab

2011-03-01T23:59:59.000Z

183

Advanced conceptual design report solid waste retrieval facility, phase I, project W-113  

SciTech Connect

Project W-113 will provide the equipment and facilities necessary to retrieve suspect transuranic (TRU) waste from Trench 04 of the 218W-4C burial ground. As part of the retrieval process, waste drums will be assayed, overpacked, vented, head-gas sampled, and x-rayed prior to shipment to the Phase V storage facility in preparation for receipt at the Waste Receiving and Processing Facility (WRAP). Advanced Conceptual Design (ACD) studies focused on project items warranting further definition prior to Title I design and areas where the potential for cost savings existed. This ACD Report documents the studies performed during FY93 to optimize the equipment and facilities provided in relation to other SWOC facilities and to provide additional design information for Definitive Design.

Smith, K.E.

1994-03-21T23:59:59.000Z

184

Assessment of Facilities, Materials, and Wastes Proposed for Transfer to EM  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Non-Integrated Facilities Disposition Non-Integrated Facilities Disposition Project Technical Assistance Page 1 of 2 Complex-Wide Multi-State Assessment of Facilities, Materials, and Wastes Proposed for Transfer to EM Challenge In December 2007 the Assistant Secretary for Environmental Management (EM-1) invited the DOE Program Secretarial Offices (PSOs) of Nuclear Energy (NE), Science (SC), and the National Nuclear Security Administration (NNSA) to propose facilities and legacy waste for transfer to Environmental Management (EM) for final disposition or deactivation and decommissioning (D&D). Transfers of facilities, materials, and waste to EM will generate liabilities that are currently unfunded. For purposes of overall planning, it is important to understand the impacts of proposed transfers with regard to technical

185

The Radioactive Liquid Waste Treatment Facility Replacement Project at Los Alamos National Laboratory  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Radioactive Liquid Waste Radioactive Liquid Waste Treatment Facility Replacement Project at Los Alamos National Laboratory OAS-L-13-15 September 2013 Department of Energy Washington, DC 20585 September 26, 2013 MEMORANDUM FOR THE ASSOCIATE ADMINISTRATOR FOR ACQUISITION AND PROJECT MANAGEMENT MANAGER LOS ALAMOS FIELD OFFICE FROM: David Sedillo Western Audits Division Office of Inspector General SUBJECT: INFORMATION: Audit Report on "The Radioactive Liquid Waste Treatment Facility Replacement Project at Los Alamos National Laboratory" BACKGROUND The Department of Energy's Los Alamos National Laboratory (Los Alamos) is a Government- owned, contractor operated Laboratory that is part of the National Nuclear Security Administration's (NNSA) nuclear weapons complex. Los Alamos' primary responsibility is to

186

FEDERAL FACILITY COMPLIANCE AGREEMENT (FFCA) STACK ISOLATION PROJECT FUNCTIONS & REQUIREMENTS  

SciTech Connect

This document delineates the functions and requirements for the FFCA Stack Isolation Project for the 244-A, 244-BX, 244-5, and 244-TX DCRTs. The isolation of each ventilation system and stack includes the electrical, instrumentation, and mechanical isolation of the ventilation system and the installation of primary and annulus breather filters to provide passive ventilation to meet the FFCA requirements.

TRANBARGER, R.K.

2003-12-16T23:59:59.000Z

187

Waste and Materials Disposition Information | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Waste and Materials Disposition Waste and Materials Disposition Information Waste and Materials Disposition Information Waste and Materials Disposition Information As the Office of Environmental Management (EM) fulfills its mission, waste and materials disposition plays a vital role in the cleanup of radioactive waste and the environmental legacy of nuclear weapons production and nuclear energy research. Disposal of waste frequently falls on the critical path of cleanup projects. Significant planning resources are spent to identify alternatives and find a path that is cost-effective and in the best interest of the Federal government. In many instances, waste disposition, (processing, treatment and disposal) is part of cleanup agreements and is of interest to stakeholders and requires the oversight of regulators.

188

Project Plan: Central and Eastern United States Seismic Source Characterization for Nuclear Facilities  

Science Conference Proceedings (OSTI)

This project plan outlines the Central and Eastern United States Seismic Source Characterization for Nuclear Facilities (CEUS SSC) Project, which will replace the Seismic Hazard Methodology for the Central and Eastern United States, EPRI report NP-4726, July 1986. The objective of the CEUS SSC project is to develop an up-to-date assessment of probabilistic seismic hazard analysis (PSHA) SSC for CEUS. Input to a PSHA consists of both seismic source and ground motion characterization. These two components ...

2008-06-16T23:59:59.000Z

189

National Ignition Facility Project Completion and Control System Status  

SciTech Connect

The National Ignition Facility (NIF) is the world's largest and most energetic laser experimental system providing a scientific center to study inertial confinement fusion (ICF) and matter at extreme energy densities and pressures. Completed in 2009, NIF is a stadium-sized facility containing a 1.8-MJ, 500-TW 192-beam ultraviolet laser and target chamber. A cryogenic tritium target system and suite of optical, X-ray and nuclear diagnostics will support experiments in a strategy to achieve fusion ignition starting in 2010. Automatic control of NIF is performed by the large-scale Integrated Computer Control System (ICCS), which is implemented by 2 MSLOC of Java and Ada running on 1300 front-end processors and servers. The ICCS framework uses CORBA distribution for interoperation between heterogeneous languages and computers. Laser setup is guided by a physics model and shots are coordinated by data-driven distributed workflow engines. The NIF information system includes operational tools and a peta-scale repository for provisioning experimental results. This paper discusses results achieved and the effort now underway to conduct full-scale operations and prepare for ignition.

Van Arsdall, P J; Azevedo, S G; Beeler, R G; Bryant, R M; Carey, R W; Demaret, R D; Fisher, J M; Frazier, T M; Lagin, L J; Ludwigsen, A P; Marshall, C D; Mathisen, D G; Reed, R K

2009-10-02T23:59:59.000Z

190

Surplus Plutonium Disposition (SPD) Environmental Data Summary  

Science Conference Proceedings (OSTI)

This document provides an overview of existing environmental and ecological information at areas identified as potential locations of the Savannah River Site's (SRS) Surplus Plutonium Disposition (SPD) facilities. This information is required to document existing environmental and baseline conditions from which SPD construction and operation impacts can be defined. It will be used in developing the required preoperational monitoring plan to be used at specific SPD facilities construction sites.

Fledderman, P.D.

2000-08-24T23:59:59.000Z

191

Solar project description for Ingham County Medical Care Facility  

SciTech Connect

Domestic hot water preheating is provided by a solar energy system utilizing 9425 square feet of liquid flat plate collectors. The collectors are double-glazed with tempered glass, have copper absorber plates and a non-selective black coating. A 50% propylene glycol/water solution protects the collectors from freezing down to -20/sup 0/F. A steam-fired heat exchanger and circulation pump with an emergency generator provide heat to protect the collectors below -20/sup 0/F. A 5000 gallon, currently uninsulated, steel storage tank, is located in the existing mechanical room. The preheated water in the tank is provided directly to a steam-fired hot water heater for use in the laundry facility. A heat exchanger provides preheated water to a steam-fired domestic hot water heater. A gas/oil fired boiler provides steam to the hot water heaters. (MHR)

1979-08-01T23:59:59.000Z

192

Mixed and low-level waste treatment facility project  

SciTech Connect

The technology information provided in this report is only the first step toward the identification and selection of process systems that may be recommended for a proposed mixed and low-level waste treatment facility. More specific information on each technology will be required to conduct the system and equipment tradeoff studies that will follow these preengineering studies. For example, capacity, maintainability, reliability, cost, applicability to specific waste streams, and technology availability must be further defined. This report does not currently contain all needed information; however, all major technologies considered to be potentially applicable to the treatment of mixed and low-level waste are identified and described herein. Future reports will seek to improve the depth of information on technologies.

Not Available

1992-04-01T23:59:59.000Z

193

Novel Muon Beam Facilities for Project X at Fermilab  

SciTech Connect

Innovative muon beam concepts for intensity-frontier experiments such as muon-to-electron conversion are described. Elaborating upon a previous single-beam idea, we have developed a design concept for a system to generate four high quality, low-energy muon beams (two of each sign) from a single beam of protons. As a first step, the production of pions by 1 and 3 GeV protons from the proposed Project X linac at Fermilab is being simulated and compared with the 8-GeV results from the previous study.

Neuffer, D.V.; /Fermilab; Ankenbrandt, C.M.; Abrams, R.; Roberts, T.J.; Yoshikawa, C.Y.; /MUONS Inc., Batavia

2012-05-01T23:59:59.000Z

194

Multi-Function Waste Tank Facility Quality Assurance Program Plan, Project W-236A. Revision 2  

SciTech Connect

This document describes the Quality Assurance (QA) program for the Multi-Function Waste Tank Facility (MWTF) Project. The purpose of this QA program is to control project activities in such a manner as to achieve the mission of the MWTF Project in a safe and reliable manner. The QA program for the MWTF Project is founded on DOE Order 5700.6C, Quality Assurance, and implemented through the use of ASME NQA-1, Quality Assurance Program Requirements for Nuclear Facilities (ASME 1989 with addenda la-1989, lb-1991 and lc-1992). This document describes the program and planned actions which the Westinghouse Hanford Company (WHC) will implement to demonstrate and ensure that the project meets the requirements of DOE Order 5700.6C through the interpretive guidance of ASME NQA-1.

Hall, L.R.

1995-05-30T23:59:59.000Z

195

SEISMIC DESIGN REQUIREMENTS SELECTION METHODOLOGY FOR THE SLUDGE TREATMENT & M-91 SOLID WASTE PROCESSING FACILITIES PROJECTS  

SciTech Connect

In complying with direction from the U.S. Department of Energy (DOE), Richland Operations Office (RL) (07-KBC-0055, 'Direction Associated with Implementation of DOE-STD-1189 for the Sludge Treatment Project,' and 08-SED-0063, 'RL Action on the Safety Design Strategy (SDS) for Obtaining Additional Solid Waste Processing Capabilities (M-91 Project) and Use of Draft DOE-STD-I 189-YR'), it has been determined that the seismic design requirements currently in the Project Hanford Management Contract (PHMC) will be modified by DOE-STD-1189, Integration of Safety into the Design Process (March 2007 draft), for these two key PHMC projects. Seismic design requirements for other PHMC facilities and projects will remain unchanged. Considering the current early Critical Decision (CD) phases of both the Sludge Treatment Project (STP) and the Solid Waste Processing Facilities (M-91) Project and a strong intent to avoid potentially costly re-work of both engineering and nuclear safety analyses, this document describes how Fluor Hanford, Inc. (FH) will maintain compliance with the PHMC by considering both the current seismic standards referenced by DOE 0 420.1 B, Facility Safety, and draft DOE-STD-1189 (i.e., ASCE/SEI 43-05, Seismic Design Criteria for Structures, Systems, and Components in Nuclear Facilities, and ANSI!ANS 2.26-2004, Categorization of Nuclear Facility Structures, Systems and Components for Seismic Design, as modified by draft DOE-STD-1189) to choose the criteria that will result in the most conservative seismic design categorization and engineering design. Following the process described in this document will result in a conservative seismic design categorization and design products. This approach is expected to resolve discrepancies between the existing and new requirements and reduce the risk that project designs and analyses will require revision when the draft DOE-STD-1189 is finalized.

RYAN GW

2008-04-25T23:59:59.000Z

196

Manhattan Project buildings and facilities at the Hanford Site: A construction history  

Science Conference Proceedings (OSTI)

This document thoroughly examines the role that the Hanford Engineer Works played in the Manhattan project. The historical aspects of the buildings and facilities are characterized. An in depth look at the facilities, including their functions, methods of fabrication and appearance is given for the 100 AREAS, 200 AREAS, 300 AREAS, 500, 800 and 900 AREAS, 600 AREA, 700 AREA, 1100 AREA and temporary construction structures.

Gerber, M.S.

1993-09-01T23:59:59.000Z

197

Facilities  

NLE Websites -- All DOE Office Websites (Extended Search)

Environment Feature Stories Public Reading Room: Environmental Documents, Reports LANL Home Phonebook Calendar Video About Operational Excellence Facilities Facilities...

198

disposition | OpenEI  

Open Energy Info (EERE)

disposition disposition Dataset Summary Description This dataset comes from the Energy Information Administration (EIA), and is part of the 2011 Annual Energy Outlook Report (AEO2011). This dataset is table 11, and contains only the reference case. The dataset uses million barrels per day. The data is broken down into crude oil, other petroleum supply, other non petroleum supply and liquid fuel consumption. Source EIA Date Released April 26th, 2011 (3 years ago) Date Updated Unknown Keywords 2011 AEO disposition EIA liquid fuels Supply Data application/vnd.ms-excel icon AEO2011: Liquid Fuels Supply and Disposition- Reference Case (xls, 117 KiB) Quality Metrics Level of Review Peer Reviewed Comment Temporal and Spatial Coverage Frequency Annually Time Period 2008-2035

199

Project Hanford management contract quality assurance program implementation plan for nuclear facilities  

SciTech Connect

During transition from the Westinghouse Hanford Company (WHC) Management and Operations (M and O) contract to the Fluor Daniel Hanford (FDH) Management and Integration (M and I) contract, existing WHC policies, procedures, and manuals were reviewed to determine which to adopt on an interim basis. Both WHC-SP-1131,Hanford Quality Assurance Program and Implementation Plan, and WHC-CM-4-2, Quality Assurance Manual, were adopted; however, it was recognized that revisions were required to address the functions and responsibilities of the Project Hanford Management Contract (PHMC). This Quality Assurance Program Implementation Plan for Nuclear Facilities (HNF-SP-1228) supersedes the implementation portion of WHC-SP-1 13 1, Rev. 1. The revised Quality Assurance (QA) Program is documented in the Project Hanford Quality Assurance Program Description (QAPD), HNF-MP-599. That document replaces the QA Program in WHC-SP-1131, Rev. 1. The scope of this document is limited to documenting the nuclear facilities managed by FDH and its Major Subcontractors (MSCS) and the status of the implementation of 10 CFR 830.120, Quality Assurance Requirements, at those facilities. Since the QA Program for the nuclear facilities is now documented in the QAPD, future updates of the information provided in this plan will be by letter. The layout of this plan is similar to that of WHC-SP-1 13 1, Rev. 1. Sections 2.0 and 3.0 provide an overview of the Project Hanford QA Program. A list of Project Hanford nuclear facilities is provided in Section 4.0. Section 5.0 provides the status of facility compliance to 10 CFR 830.120. Sections 6.0, 7.0, and 8.0 provide requested exemptions, status of open items, and references, respectively. The four appendices correspond to the four projects that comprise Project Hanford.

Bibb, E.K.

1997-10-15T23:59:59.000Z

200

Projects at the Component Development and Integration Facility. Quarterly technical progress report, January 1--March 31, 1993  

DOE Green Energy (OSTI)

This quarterly technical progress report presents progress on several different projects at the Component Development and Integration Facility (CDIF) during the second quarter of FY93. The CDIF is a major US Department of Energy test facility in Butte, Montana, operated by MSE, Inc. Projects in progress include: MHD Proof-of-Concept Project; Mine Waste Technology Pilot Program; Plasma Furnace Projects for waste destruction; Resource Recovery Project; Sodium Sulfide/Ferrous Sulfate Project; Soil Washing Project for removal of radioactive materials; and Spray Casting Project.

Not Available

1993-09-01T23:59:59.000Z

Note: This page contains sample records for the topic "facility disposition project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


201

Facility stabilization project fiscal year 1997 multi-year work plan (MYWP) for WBS 7.1  

SciTech Connect

This document contains the technical baseline, work breakdown structure, schedule baseline, cost baseline, and execution year for the facility stabilization project.

Cartmell, D.B.

1996-09-01T23:59:59.000Z

202

DOE Chooses Contractor to Disposition Waste at the Advanced Mixed...  

NLE Websites -- All DOE Office Websites (Extended Search)

U.S. DEPARTMENT OF ENERGY IDAHO FALLS, IDAHO, 83403 DOE Chooses Contractor to Disposition Waste at the Advanced Mixed Waste Treatment Project (AMWTP) CH2M Hill Newport News...

203

Evolution of Safeguards over Time: Past, Present, and Projected Facilities, Material, and Budget  

Science Conference Proceedings (OSTI)

This study examines the past trends and evolution of safeguards over time and projects growth through 2030. The report documents the amount of nuclear material and facilities under safeguards from 1970 until present, along with the corresponding budget. Estimates for the future amount of facilities and material under safeguards are made according to non-nuclear-weapons states (NNWS) plans to build more nuclear capacity and sustain current nuclear infrastructure. Since nuclear energy is seen as a clean and economic option for base load electric power, many countries are seeking to either expand their current nuclear infrastructure, or introduce nuclear power. In order to feed new nuclear power plants and sustain existing ones, more nuclear facilities will need to be built, and thus more nuclear material will be introduced into the safeguards system. The projections in this study conclude that a zero real growth scenario for the IAEA safeguards budget will result in large resource gaps in the near future.

Kollar, Lenka; Mathews, Caroline E.

2009-07-01T23:59:59.000Z

204

Immobilized low-activity waste interim storage facility, Project W-465 conceptual design report  

SciTech Connect

This report outlines the design and Total Estimated Cost to modify the four unused grout vaults for the remote handling and interim storage of immobilized low-activity waste (ILAW). The grout vault facilities in the 200 East Area of the Hanford Site were constructed in the 1980s to support Tank Waste disposal activities. The facilities were to serve project B-714 which was intended to store grouted low-activity waste. The existing 4 unused grout vaults, with modifications for remote handling capability, will provide sufficient capacity for approximately three years of immobilized low activity waste (ILAW) production from the Tank Waste Remediation System-Privatization Vendors (TWRS-PV). These retrofit modifications to the grout vaults will result in an ILAW interim storage facility (Project W465) that will comply with applicable DOE directives, and state and federal regulations.

Pickett, W.W.

1997-12-30T23:59:59.000Z

205

US Department of Energy Grand Junction Projects Office Remedial Action Project, final report of the decontamination and decommissioning of Building 36 at the Grand Junction Projects Office Facility  

SciTech Connect

The U.S. Department of Energy (DOE) Grand Junction Projects Office (GJPO) occupies a 61.7-acre facility along the Gunnison River near Grand Junction, Colorado. This site was contaminated with uranium ore and mill tailings during uranium refining activities of the Manhattan Engineer District and during pilot milling experiments conducted for the U.S. Atomic Energy Commission`s domestic uranium procurement program. The DOE Defense Decontamination and Decommissioning Program established the GJPO Remedial Action Project to clean up and restore the facility lands, improvements, and the underlying aquifer. The site contractor for the facility, Rust Geotech, also is the remedial action contractor. Building 36 was found to be radiologically contaminated and was demolished in 1996. The soil beneath the building was remediated in accordance with identified standards and can be released for unlimited exposure and unrestricted use. This document was prepared in response to a DOE request for an individual final report for each contaminated GJPO building.

Widdop, M.R.

1996-08-01T23:59:59.000Z

206

SELECTION OF SURPLUS PLUTONIUM MATERIALS FOR DISPOSITION TO WIPP  

SciTech Connect

The U.S. Department of Energy (DOE) is preparing a Surplus Plutonium Disposition (SPD) Supplemental Environmental Impact Statement (SEIS). Included in the evaluation are up to 6 metric tons (MT) of plutonium in the form of impure oxides and metals for which a disposition plan has not been decided, among options that include preparation as feed for the Mixed Oxide Fuel Fabrication Facility; disposing to high-level waste through the Savannah River Site (SRS) HB Line and H Canyon; can-in-canister disposal using the SRS Defense Waste Processing Facility; and preparation for disposal at the Waste Isolation Pilot Plant (WIPP). DOE and SRS have identified at least 0.5 MT of plutonium that, because of high levels of chemical and isotopic impurities, is impractical for disposition by methods other than the WIPP pathway. Characteristics of these items and the disposition strategy are discussed.

Allender, J.; Mcclard, J.; Christopher, J.

2012-06-08T23:59:59.000Z

207

Environmental assessment for the Waste Water Treatment Facility at the West Valley Demonstration Project and finding of no significant impact  

SciTech Connect

The possible environmental impacts from the construction and operation of a waste water treatment facility for the West Valley Demonstration Project are presented. The West Valley Project is a demonstration project on the solidification of high-level radioactive wastes. The need for the facility is the result of a rise in the work force needed for the project which rendered the existing sewage treatment plant incapable of meeting the nonradioactive waste water treatment needs.

1992-12-31T23:59:59.000Z

208

Spent Nuclear Fuel (SNF) Project Cold Vacuum Drying (CVD) Facility Operations Manual  

Science Conference Proceedings (OSTI)

This document provides the Operations Manual for the Cold Vacuum Drying Facility (CVDF). The Manual was developed in conjunction with HNF-SD-SNF-SAR-002, Safety Analysis Report for the Cold Vacuum Drying Facility, Phase 2, Supporting Installation of the Processing Systems (Garvin 1998) and, the HNF-SD-SNF-DRD-002, 1997, Cold Vacuum Drying Facility Design Requirements, Rev. 3a. The Operations Manual contains general descriptions of all the process, safety and facility systems in the CVDF, a general CVD operations sequence, and has been developed for the spent nuclear fuel project (SNFP) Operations Organization and shall be updated, expanded, and revised in accordance with future design, construction and startup phases of the CVDF until the CVDF final ORR is approved.

IRWIN, J.J.

2000-02-03T23:59:59.000Z

209

Proliferation resistance criteria for fissile material disposition issues  

Science Conference Proceedings (OSTI)

The 1994 National Acdaemy of Sciences study ``Management and Disposition of Excess Weapons Plutonium`` defined options for reducing the national and international proliferation risks of materials declared excess to the nuclear weapons program. This paper proposes criteria for assessing the proliferation resistance of these options as well defining the ``Standards`` from the report. The criteria are general, encompassing all stages of the disposition process from storage through intermediate processing to final disposition including the facilities, processing technologies and materials, the level of safeguards for these materials, and the national/subnational threat to the materials.

Rutherford, D.A.; Fearey, B.L.; Markin, J.T.; Close, D.A. [Los Alamos National Lab., NM (United States); Tolk, K.M.; Mangan, D.L. [Sandia National Labs., Albuquerque, NM (United States); Moore, L. [Lawrence Livermore National Lab., CA (United States)

1995-09-01T23:59:59.000Z

210

Benchmarking the Remote-Handled Waste Facility at the West Valley Demonstration Project  

Science Conference Proceedings (OSTI)

ABSTRACT Facility decontamination activities at the West Valley Demonstration Project (WVDP), the site of a former commercial nuclear spent fuel reprocessing facility near Buffalo, New York, have resulted in the removal of radioactive waste. Due to high dose and/or high contamination levels of this waste, it needs to be handled remotely for processing and repackaging into transport/disposal-ready containers. An initial conceptual design for a Remote-Handled Waste Facility (RHWF), completed in June 1998, was estimated to cost $55 million and take 11 years to process the waste. Benchmarking the RHWF with other facilities around the world, completed in November 1998, identified unique facility design features and innovative waste pro-cessing methods. Incorporation of the benchmarking effort has led to a smaller yet fully functional, $31 million facility. To distinguish it from the June 1998 version, the revised design is called the Rescoped Remote-Handled Waste Facility (RRHWF) in this topical report. The conceptual design for the RRHWF was completed in June 1999. A design-build contract was approved by the Department of Energy in September 1999.

O. P. Mendiratta; D. K. Ploetz

2000-02-29T23:59:59.000Z

211

Cost Transfers at the Department's Sodium Bearing Waste Treatment Facility Construction Project  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

U.S. Department of Energy U.S. Department of Energy Office of Inspector General Office of Audits and Inspections Audit Report Cost Transfers at the Department's Sodium Bearing Waste Treatment Facility Construction Project OAS-M-13-03 August 2013 Department of Energy Washington, DC 20585 August 8, 2013 MEMORANDUM FOR THE SENIOR ADVISOR FOR ENVIRONMENTAL MANAGEMENT FROM: Rickey R. Hass Deputy Inspector General for Audits and Inspections Office of Inspector General SUBJECT: INFORMATION: Audit Report on "Cost Transfers at the Department's Sodium Bearing Waste Treatment Facility Construction Project" BACKGROUND In 2005, the Department of Energy (Department) awarded the Idaho Cleanup Project contract to CH2M ♦ WG Idaho, LLC (CWI) to remediate the Idaho National Laboratory. The Sodium

212

Assessment of Facilities, Materials, and Wastes Proposed for Transfer to EM  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Facilities, Materials, and Wastes Proposed for Facilities, Materials, and Wastes Proposed for Transfer to EM Assessment of Facilities, Materials, and Wastes Proposed for Transfer to EM In December 2007 the Assistant Secretary for Environmental Management (EM-1) invited the DOE Program Secretarial Offices (PSOs) of Nuclear Energy (NE), Science (SC), and the National Nuclear Security Administration (NNSA) to propose facilities and legacy waste for transfer to Environmental Management (EM) for final disposition or deactivation and decommissioning (D&D). Assessment of Facilities, Materials, and Wastes Proposed for Transfer to EM More Documents & Publications Assessment of the Integrated Facility Disposition Project at Oak Ridge National Laboratory & Y-12 for Transfer of Facilities & Materials to EM

213

Conceptual design report: Nuclear materials storage facility renovation. Part 1, Design concept. Part 2, Project management  

Science Conference Proceedings (OSTI)

The Nuclear Materials Storage Facility (NMSF) at the Los Alamos National Laboratory (LANL) was a Fiscal Year (FY) 1984 line-item project completed in 1987 that has never been operated because of major design and construction deficiencies. This renovation project, which will correct those deficiencies and allow operation of the facility, is proposed as an FY 97 line item. The mission of the project is to provide centralized intermediate and long-term storage of special nuclear materials (SNM) associated with defined LANL programmatic missions and to establish a centralized SNM shipping and receiving location for Technical Area (TA)-55 at LANL. Based on current projections, existing storage space for SNM at other locations at LANL will be loaded to capacity by approximately 2002. This will adversely affect LANUs ability to meet its mission requirements in the future. The affected missions include LANL`s weapons research, development, and testing (WRD&T) program; special materials recovery; stockpile survelliance/evaluation; advanced fuels and heat sources development and production; and safe, secure storage of existing nuclear materials inventories. The problem is further exacerbated by LANL`s inability to ship any materials offsite because of the lack of receiver sites for mate rial and regulatory issues. Correction of the current deficiencies and enhancement of the facility will provide centralized storage close to a nuclear materials processing facility. The project will enable long-term, cost-effective storage in a secure environment with reduced radiation exposure to workers, and eliminate potential exposures to the public. This document provides Part I - Design Concept which describes the selected solution, and Part II - Project Management which describes the management system organization, the elements that make up the system, and the control and reporting system.

NONE

1995-07-14T23:59:59.000Z

214

As Built Verification Plan for Cask Transportation Facility Modifications (CTFM) Project A.5 and A.6  

Science Conference Proceedings (OSTI)

This document establishes an As-built Verification Plan (AVP) for implementing requirements in PHMC Engineering Requirements HNF-PRO-1819, Rev. 4, Sections 2.8.3.d and 2.10.8 and Spent Nuclear Fuels (SNF) Project Administrative Procedure EN-6-012-01. This AVP defines and implements approved processes to document the physical configuration of the project scope installed within the facility and identify discrepancies between the associated project engineering drawings and the field configuration, and the component index (CI) database as defined in AP EN 6-005-02. This AVP defines requirements for project activities verifying conformance of structures, systems, and components (SSCs) to project specified requirements.

LANE, K.I.

2000-04-20T23:59:59.000Z

215

CHARACTERIZATION OF SURPLUS PLUTONIUM FOR DISPOSITION OPTIONS  

SciTech Connect

The United States (U.S.) has identified 61.5 metric tons (MT) of plutonium that is permanently excess to use in nuclear weapons programs, including 47.2 MT of weapons-grade plutonium. Except for materials that remain in use for programs outside of national defense, including programs for nuclear-energy development, the surplus inventories will be stored safely by the Department of Energy (DOE) and then transferred to facilities that will prepare the plutonium for permanent disposition. Some items will be disposed as transuranic waste, low-level waste, or spent fuel. The remaining surplus plutonium will be managed through: (1) the Mixed Oxide (MOX) Fuel Fabrication Facility (FFF), to be constructed at the Savannah River Site (SRS), where the plutonium will be converted to fuel that will be irradiated in civilian power reactors and later disposed to a high-level waste (HLW) repository as spent fuel; (2) the SRS H-Area facilities, by dissolving and transfer to HLW systems, also for disposal to the repository; or (3) alternative immobilization techniques that would provide durable and secure disposal. From the beginning of the U.S. program for surplus plutonium disposition, DOE has sponsored research to characterize the surplus materials and to judge their suitability for planned disposition options. Because many of the items are stored without extensive analyses of their current chemical content, the characterization involves three interacting components: laboratory sample analysis, if available; non-destructive assay data; and rigorous evaluation of records for the processing history for items and inventory groups. This information is collected from subject-matter experts at inventory sites and from materials stabilization and surveillance programs, in cooperation with the design agencies for the disposition facilities. This report describes the operation and status of the characterization program.

Allender, J; Edwin Moore, E; Scott Davies, S

2008-07-15T23:59:59.000Z

216

Project C-018H, 242-A Evaporator/PUREX Plant Process Condensate Treatment Facility, functional design criteria. Revision 3  

Science Conference Proceedings (OSTI)

This document provides the Functional Design Criteria (FDC) for Project C-018H, the 242-A Evaporator and Plutonium-Uranium Extraction (PUREX) Plant Condensate Treatment Facility (Also referred to as the 200 Area Effluent Treatment Facility [ETF]). The project will provide the facilities to treat and dispose of the 242-A Evaporator process condensate (PC), the Plutonium-Uranium Extraction (PUREX) Plant process condensate (PDD), and the PUREX Plant ammonia scrubber distillate (ASD).

Sullivan, N.

1995-05-02T23:59:59.000Z

217

Project W-236A multi-function waste tank facility waste feed projections  

SciTech Connect

A review of Hanford Underground Waste Storage Tank Chemistry, coupled with planned remediation actions and retrieval sequences was conducted in order to predict the chemistry of the waste to be stored in the MWTF tanks. All projected waste solutions to be transferred to the MWTF tanks were found to be in compliance with current tank chemistry specifications; therefore, the waste and the tank materials of construction are expected to be compatible.

Larrick, A.P.

1994-12-22T23:59:59.000Z

218

Strategic Facilities Management Using Public and Private Funding for Energy Projects: A Case Study  

E-Print Network (OSTI)

The Alamo Community College District (ACCD) in San Antonio, Texas has a long history of participating in public and private sector loan programs for facilities energy projects. In its most recent experience, the District has demonstrated the value of these loans beyond simple kWh savings. In 2002, The District received $3.0 million in private sector loans for projects including indoor lighting retrofits, cooling tower upgrades, and Continuous Commissioning. Documented energy cost savings from this project exceeded the projected savings since its completion in early 2005. Now nearly a decade later, ACCD is participating in a State-funded revolving loan program for energy retrofits estimated at $10 million. A wide range of projects are proposed, including indoor and outdoor lighting retrofits, central plant upgrades, solar thermal pool heating, enhanced retrofit commissioning and installation of water based thermal storage systems. In addition, existing campus load profile analysis uncovered utility rate change options that yielded instant savings. In total, over $1 million per year in cost savings and 4 megawatts of mitigated power generation capacity are projected due to these projects. This paper presents the details of the loan procurement process as part of a state program designed for building energy efficiency retrofit projects, and how ACCD is using available resources to strategically integrate short-term systems upgrades with long-term infrastructure, energy management, and sustainability goals.

Khan, S.; Bible, M.; Strybos, J.

2012-01-01T23:59:59.000Z

219

Recovery Act: Hydroelectric Facility Improvement Project - Replacement of Current Mechanical Seal System with Rope Packing System  

SciTech Connect

On January 27, 2010 the City of North Little Rock, Arkansas received notification of the awarding of a Department of Energy (DOE) grant totaling $450,000 in funding from the American Recovery and Reinvestment Act (ARRA) under the Project Title: Recovery Act: Hydroelectric Facility Improvement Project Automated Intake Clearing Equipment and Materials Management. The purpose of the grant was for improvements to be made at the Citys hydroelectric generating facility located on the Arkansas River. Improvements were to be made through the installation of an intake maintenance device (IMD) and the purchase of a large capacity wood grinder. The wood grinder was purchased in order to receive the tree limbs, tree trunks, and other organic debris that collects at the intake of the plant during high flow. The wood grinder eliminates the periodic burning of the waste material that is cleared from the intake and reduces any additional air pollution to the area. The resulting organic mulch has been made available to the public at no charge. Design discussion and planning began immediately and the wood grinder was purchased in July of 2010 and immediately put to work mulching debris that was gathered regularly from the intake of the facility. The mulch is currently available to the public for free. A large majority of the design process was spent in discussion with the Corps of Engineers to obtain approval for drawings, documents, and permits that were required in order to make changes to the structure of the powerhouse. In April of 2011, the Citys Project Engineer, who had overseen the application, resigned and left the Citys employ. A new Systems Mechanical Engineer was hired and tasked with overseeing the project. The transfer of responsibility led to a re-examination of the original assumptions and research upon which the grant proposal was based. At that point, the project went under review and a trip was booked for July 2011 to visit facilities that currently had an IMD installed. This further study of facilities revealed that the implementation of the project as originally described, while proving the benefits described in the original grant application, would likely intensify sand intake. Increased sand intake would lead to an increase in required shutdowns for maintenance and more rapid depreciation of key equipment which would result in a loss of generation capacity. A better solution to the problem, one that continued to meet the criteria for the original grant and ARRA standards, was developed. A supporting day trip was planned to visit other facilities located on the Arkansas River to determine how they were coping with the same strong amounts of sand, silt, and debris. Upon returning from the trip to other Arkansas River facilities it was extremely clear what direction to go in order to most efficiently address the issue of generator capacity and efficiency. Of the plants visited on the Arkansas River, every one of them was running what is called a rope packing shaft sealing system as opposed to mechanical shaft seals, which the facility was running. Rope packing is a time proven sealing method that has been around for centuries. It has proved to perform very well in dirty water situations just like that of the Arkansas River. In April of 2012 a scope change proposal was submitted to the DOE for approval. In August of 2012 the City received word that the change of scope had been approved. Plans were immediately set in motion to begin the conversion from mechanical seals to a packing box at the facility. Contractors arrived on October 1st, 2012 and the project team began unwatering the unit for disassembly. The seal conversion was completed on February 29th, 2013 with start-up of the unit. Further testing and adjusting was done throughout the first two weeks of March.

Stephens, Jessica D.

2013-05-29T23:59:59.000Z

220

Upgrades to meet LANL SF, 121-2011, hazardous waste facility permit requirements  

Science Conference Proceedings (OSTI)

Members of San IIdefonso have requested information from LANL regarding implementation of the revision to LANL's Hazardous Waste Facility Permit (the RCRA Permit). On January 26, 2011, LANL staff from the Waste Disposition Project and the Environmental Protection Division will provide a status update to Pueblo members at the offices of the San IIdefonso Department of Environmental and Cultural Preservation. The Waste Disposition Project presentation will focus on upgrades and improvements to LANL waste management facilities at TA-50 and TA-54. The New Mexico Environment Department issued LANL's revised Hazardous Waste Facility permit on November 30, 2010 with a 30-day implementation period. The Waste Disposition Project manages and operates four of LANL's permitted facilities; the Waste Characterization, Reduction and Repackaging Facility (WCRRF) at TA-SO, and Area G, Area L and the Radioassay and Nondestructive Testing facility (RANT) at TA-54. By implementing a combination of permanent corrective action activities and shorter-term compensatory measures, WDP was able to achieve functional compliance on December 30, 2010 with new Permit requirements at each of our facilities. One component of WOP's mission at LANL is centralized management and disposition of the Laboratory's hazardous and mixed waste. To support this mission objective, WOP has undertaken a project to upgrade our facilities and equipment to achieve fully compliant and efficient waste management operations. Upgrades to processes, equipment and facilities are being designed to provide defense-in-depth beyond the minimum, regulatory requirements where worker safety and protection of the public and the environment are concerned. Upgrades and improvements to enduring waste management facilities and operations are being designed so as not to conflict with future closure activities at Material Disposal Area G and Material Disposal Area L.

French, Sean B [Los Alamos National Laboratory; Johns - Hughes, Kathryn W [Los Alamos National Laboratory

2011-01-21T23:59:59.000Z

Note: This page contains sample records for the topic "facility disposition project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


221

The mixed waste management facility. Project baseline revision 1.2  

Science Conference Proceedings (OSTI)

Revision 1.2 to the Project Baseline (PB) for the Mixed Waste Management Facility (MWMF) is in response to DOE directives and verbal guidance to (1) Collocate the Decontamination and Waste Treatment Facility (DWTF) and MWMF into a single complex, integrate certain and overlapping functions as a cost-saving measure; (2) Meet certain fiscal year (FY) new-BA funding objectives ($15.3M in FY95) with lower and roughly balanced funding for out years; (3) Reduce Total Project Cost (TPC) for the MWMF Project; (4) Include costs for all appropriate permitting activities in the project TPC. This baseline revision also incorporates revisions in the technical baseline design for Molten Salt Oxidation (MSO) and Mediated Electrochemical Oxidation (MEO). Changes in the WBS dictionary that are necessary as a result of this rebaseline, as well as minor title changes, at WBS Level 3 or above (DOE control level) are approved as a separate document. For completeness, the WBS dictionary that reflects these changes is contained in Appendix B. The PB, with revisions as described in this document, were also the basis for the FY97 Validation Process, presented to DOE and their reviewers on March 21-22, 1995. Appendix C lists information related to prior revisions to the PB. Several key changes relate to the integration of functions and sharing of facilities between the portion of the DWTF that will house the MWMF and those portions that are used by the Hazardous Waste Management (HWM) Division at LLNL. This collocation has been directed by DOE as a cost-saving measure and has been implemented in a manner that maintains separate operational elements from a safety and permitting viewpoint. Appendix D provides background information on the decision and implications of collocating the two facilities.

Streit, R.D.; Throop, A.L.

1995-04-01T23:59:59.000Z

222

Recovery Act: Hydroelectric Facility Improvement Project - Replacement of Current Mechanical Seal System with Rope Packing System  

DOE Green Energy (OSTI)

Plans were immediately set in motion to begin the conversion from mechanical seals to a packing box at the facility. Contractors arrived on October 1st, 2012 and the project team began unwatering the unit for disassembly. The seal conversion was completed on February 29th, 2013 with start-up of the unit. Further testing and adjusting was done throughout the first two weeks of March.

Stephens, Jessica D.

2013-05-29T23:59:59.000Z

223

REQUEST FOR RECORDS DISPOSITION AUTHORITY | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

FOR RECORDS DISPOSITION AUTHORITY REQUEST FOR RECORDS DISPOSITION AUTHORITY Atomic Energy Commission REQUEST FOR RECORDS DISPOSITION AUTHORITY More Documents & Publications...

224

REQUEST FOR RECORDS DISPOSITION AUTHORITY | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

RECORDS DISPOSITION AUTHORITY More Documents & Publications Disposition Schedule: Human Radiation Experiments REQUEST FOR RECORDS DISPOSITION AUTHORITY REQUEST FOR RECORDS...

225

Project of the Month | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

June 1, 2010 June 1, 2010 CONSTRUCTION OF KEY CLEANUP PROJECT GAINS GOOD GROUND AT SRS Aiken, SC - Construction of a key cleanup facility at the Savannah River Site (SRS) is gaining some serious ground given the remarkable building progress since Fall 2009. Construction and operation of the Salt Waste Processing Facility (SWPF) is among the U.S. Department of Energy's (DOE) highest cleanup priorities. April 1, 2010 An operator uses robotic manipulators to process RH TRU. WASTE DISPOSITION PROJECT MAKES GREAT STRIDES AT THE IDAHO SITE Idaho - The Waste Disposition Project Team at the Department of Energy's Idaho Site has continued to keep its commitment to remove remote handled (RH) transuranic (TRU) waste out of Idaho, protecting the Snake River Plain Aquifer and keeping the Office of Environmental Management's commitment

226

Used Fuel Disposition R&D Documents | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Technologies Used Fuel Disposition Research & Development Used Fuel Disposition R&D Documents Used Fuel Disposition R&D Documents April 30, 2012 Office of UNF Disposition...

227

Hanford Tank Waste Retrieval, Treatment and Disposition Framework |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Hanford Tank Waste Retrieval, Treatment and Disposition Framework Hanford Tank Waste Retrieval, Treatment and Disposition Framework Hanford Tank Waste Retrieval, Treatment and Disposition Framework Completing the Office of River Protection (ORP) mission of stabilizing 56 million gallons of chemical and radioactive waste stored in Hanford's 177 tanks is one of the Energy Department's highest priorities. This Framework document outlines a phased approach for beginning tank waste treatment while continuing to resolve technical issues with the Pretreatment and High-Level Waste Facilities. Hanford Tank Waste Retrieval, Treatment and Disposition Framework More Documents & Publications EIS-0391: Draft Environmental Impact Statement Waste Treatment Plant and Tank Farm Program EIS-0356: Notice of Intent to Prepare an Environmental Impact Statement

228

Hanford Tank Waste Retrieval, Treatment and Disposition Framework |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Hanford Tank Waste Retrieval, Treatment and Disposition Framework Hanford Tank Waste Retrieval, Treatment and Disposition Framework Hanford Tank Waste Retrieval, Treatment and Disposition Framework Completing the Office of River Protection (ORP) mission of stabilizing 56 million gallons of chemical and radioactive waste stored in Hanford's 177 tanks is one of the Energy Department's highest priorities. This Framework document outlines a phased approach for beginning tank waste treatment while continuing to resolve technical issues with the Pretreatment and High-Level Waste Facilities. Hanford Tank Waste Retrieval, Treatment and Disposition Framework More Documents & Publications EIS-0391: Draft Environmental Impact Statement Waste Treatment Plant and Tank Farm Program EIS-0356: Notice of Intent to Prepare an Environmental Impact Statement

229

PNC/DOE Remote Monitoring Project at Japan`s Joyo Facility  

Science Conference Proceedings (OSTI)

The Power Reactor and Nuclear Fuel Development Corporation (PNC) of Japan and the US Department of Energy (DOE) are cooperating on the development of a remote monitoring system for nuclear nonproliferation efforts. This cooperation is part of a broader safeguards agreement between PNC and DOE. A remote monitoring system is being installed in a spent fuel storage area at PNC`s experimental reactor facility Joyo in Oarai. The system has been designed by Sandia National Laboratories (SNL) and is closely related to those used in other SNL remote monitoring projects. The Joyo project will particularly study the unique aspects of remote monitoring in contribution to nuclear nonproliferation. The project will also test and evaluate the fundamental design and implementation of the remote monitoring system in its application to regional and international safeguards efficiency. This paper will present a short history of the cooperation, the details of the monitoring system and a general schedule of activities.

Ross, M.; Hashimoto, Yu [Power Reactor and Nuclear Fuel Development Corp., Oarai, Ibaraki (Japan). Oarai Engineering Center; Senzaki, Masao; Shigeto, Toshinori [Power Reactor and Nuclear Fuel Development Corp., Tokyo (Japan); Sonnier, C. [Jupiter Corp., Albuquerque, NM (United States); Dupree, S.; Ystesund, K.; Hale, W. [Sandia National Labs., Albuquerque, NM (United States)

1996-07-25T23:59:59.000Z

230

US Department of Energy Grand Junction Projects Office Remedial Action Project. Final report of the decontamination and decommissioning of Building 52 at the Grand Junction Projects Office Facility  

SciTech Connect

The U.S. Department of Energy (DOE) Grand Junction Projects Office (GJPO) occupies a 61.7-acre facility along the Gunnison River near Grand Junction, Colorado. This site was contaminated with uranium ore and mill tailings during uranium refining activities of the Manhattan Engineer District and during pilot milling experiments conducted for the U.S. Atomic Energy Commission`s domestic uranium procurement program. The DOE Defense Decontamination and Decommissioning Program established the GJPO Remedial Action Project to clean up and restore the facility lands, improvements, and the underlying aquifer. The site contractor for the facility, Rust Geotech, also was the remedial action contractor. Building 52 was found to be radiologically contaminated and was demolished in 1994. The soil area within the footprint of the building has been remediated in accordance with the identified standards and the area can be released for unlimited exposure and unrestricted use. This document was prepared in response to a DOE request for an individual final report for each contaminated GJPO building.

Krabacher, J.E.

1996-08-01T23:59:59.000Z

231

Facilities  

NLE Websites -- All DOE Office Websites (Extended Search)

Facilities Facilities Facilities LANL's mission is to develop and apply science and technology to ensure the safety, security, and reliability of the U.S. nuclear deterrent; reduce global threats; and solve other emerging national security and energy challenges. Contact Operator Los Alamos National Laboratory (505) 667-5061 Some LANL facilities are available to researchers at other laboratories, universities, and industry. Unique facilities foster experimental science, support LANL's security mission DARHT accelerator DARHT's electron accelerators use large, circular aluminum structures to create magnetic fields that focus and steer a stream of electrons down the length of the accelerator. Tremendous electrical energy is added along the way. When the stream of high-speed electrons exits the accelerator it is

232

Tuesday Webcast for Industry: Key Energy-Saving Projects for Smaller Facilities  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Key Energy-Saving Key Energy-Saving Projects for Smaller Facilities January 10, 2012 Program Name or Ancillary Text eere.energy.gov Key Energy-Saving Activities for Small and Medium Sized Facilities Thomas Wenning Oak Ridge National Laboratory Tuesday Webcast for Industry January 10, 2012 3 | Advanced Manufacturing Office eere.energy.gov Percent of Total U.S. Manufacturing Energy Small 5% Mid-Size 37% Large 58% 0 50000 100000 150000 200000 250000 U.S. Manufacturing Plants: By Size Small Plants Mid-Size Plants Large Plants Number of U.S. Plants All Plants 84,298 112,398 4,014 200,710 System-Specific Assessments Crosscutting Assessments Industry Breakdown 4 | Advanced Manufacturing Office eere.energy.gov 4,014 large plants use 58% of the energy Energy Saving

233

Assessment of Nuclear Safety Culture at the Y-12 National Security Complex Urnaium Processing Facility Project, June 2012  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Y-12 National Security Complex Y-12 National Security Complex Uranium Processing Facility Project May 2011 June 2012 Office of Safety and Emergency Management Evaluations Office of Enforcement and Oversight Office of Health, Safety and Security U.S. Department of Energy i Independent Oversight Assessment of Safety Culture at the Y-12 National Security Complex Uranium Processing Facility Project Table of Contents 1.0 Introduction ........................................................................................................................................... 1 2.0 Scope and Methodology ....................................................................................................................... 2 3.0 Results and Conclusions ....................................................................................................................... 3

234

Assessment of Nuclear Safety Culture at the Y-12 National Security Complex Urnaium Processing Facility Project, June 2012  

NLE Websites -- All DOE Office Websites (Extended Search)

Y-12 National Security Complex Y-12 National Security Complex Uranium Processing Facility Project May 2011 June 2012 Office of Safety and Emergency Management Evaluations Office of Enforcement and Oversight Office of Health, Safety and Security U.S. Department of Energy i Independent Oversight Assessment of Safety Culture at the Y-12 National Security Complex Uranium Processing Facility Project Table of Contents 1.0 Introduction ........................................................................................................................................... 1 2.0 Scope and Methodology ....................................................................................................................... 2 3.0 Results and Conclusions ....................................................................................................................... 3

235

Waste management project fiscal year 1998 multi-year work plan WBS 1.2  

SciTech Connect

The MYWP technical baseline describes the work to be accomplished by the Project and the technical standards which govern that work. The Waste Management Project manages and integrates (non-TWRS) waste management activities at the site. Activities include management of Hanford wastes as well as waste transferred to Hanford from other DOE, Department of Defense, or other facilities. This work includes handling, treatment, storage, and disposition of radioactive, nonradioactive, hazardous, and mixed solid and liquid wastes. Major Waste Management Projects are the Solid Waste Project (SW), Liquid Effluents Project (LEP), and Analytical Services. Existing facilities (e.g., grout vaults and canyons) shall be evaluated for reuse for these purposes to the maximum extent possible. The paper tabulates the major facilities that interface with this Project, identifying the major facilities that generate waste, materials, or infrastructure for this Project and the major facilities that will receive waste and materials from this Project.

Slaybaugh, R.R.

1997-08-29T23:59:59.000Z

236

Readiness Assessment for MF-628 Drum Treatment Facility - Advanced Mixed Waste Treatment Project … 5-07  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

CRITICALITY SAFETY CRITICALITY SAFETY OBJECTIVE CS.1 Facility safety documentation that describes the "safety envelope" for the AR Project II activities is in place and has been implemented and administrative and engineering controls to prevent and mitigate hazards associated with commencing the AR Project II activities are tailored to the work being performed and the associated hazards to meet the following criteria: CRITERIA: CS. 1.1 Criticality safety requirements are current, approved, and properly controlled. CS. 1.2 Facility safety and criticality requirements have been incorporated into applicable procedures and documents. REVIEW APPROACH: Document Reviews: * Review applicable CSEs for identification of facility hazards and development

237

SRS - Programs - H Area Nuclear Materials Disposition  

NLE Websites -- All DOE Office Websites (Extended Search)

H Area Nuclear Materials Disposition H Area Nuclear Materials Disposition The primary mission of the H-Canyon Complex is to dissolve, purify and blend-down surplus highly enriched uranium (HEU) and aluminum-clad foreign and domestic research reactor fuel to produce a low enriched uranium (LEU) solution suitable for conversion to commercial reactor fuel. A secondary mission for H-Canyon is to dissolve excess plutonium (Pu) not suitable for MOX and transfer it for vitrification in the Defense Waste Processing Facility at SRS. H Canyon was constructed in the early 1950s and began operations in 1955. The building is called a canyon because of its long rectangular shape and two continuous trenches that contains the process vessels. It is approximately 1,000 feet long with several levels to accommodate the various stages of material stabilization, including control rooms to monitor overall equipment and operating processes, equipment and piping gallery for solution transport, storage, and disposition, and unique overhead bridge cranes to support overall process operations. All work is remotely controlled, and employees are further protected from radiation by thick concrete walls.

238

Dismantlement and Disposition | National Nuclear Security Administrati...  

National Nuclear Security Administration (NNSA)

Employment Apply for Our Jobs Our Jobs Working at NNSA Blog Dismantlement and Disposition Home > Our Mission > Managing the Stockpile > Dismantlement and Disposition Dismantlement...

239

Progress and Lessons Learned in Transuranic Waste Disposition at The Department of Energy's Advanced Mixed Waste Treatment Project  

SciTech Connect

This paper provides an overview of the Department of Energy's (DOE) Advanced Mixed Waste Treatment Project (AMWTP) located at the Idaho National Laboratory (INL) and operated by Bechtel BWXT Idaho, LLC(BBWI) It describes the results to date in meeting the 6,000-cubic-meter Idaho Settlement Agreement milestone that was due December 31, 2005. The paper further describes lessons that have been learned from the project in the area of transuranic (TRU) waste processing and waste certification. Information contained within this paper would be beneficial to others who manage TRU waste for disposal at the Waste Isolation Pilot Plant (WIPP).

J.D. Mousseau; S.C. Raish; F.M. Russo

2006-05-18T23:59:59.000Z

240

Environmental Assessment for the Decontamination, Demolition, and Removal of Certain Facilities at the West Valley Demonstration Project  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

52 52 Environmental Assessment for the Decontamination, Demolition, and Removal of Certain Facilities at the West Valley Demonstration Project Final U.S. Department of Energy West Valley Demonstration Project West Valley, New York September 14, 2006 Final EA - Decontamination, Demolition, and Removal of Certain Facilities at WVDP i Table of Contents CHAPTER 1 INTRODUCTION AND PURPOSE AND NEED FOR AGENCY ACTION................ 1 1.1 Overview....................................................................................................................... 1 1.2 West Valley Demonstration Project.............................................................................. 2 1.3 Purpose and Need for Agency Action ..........................................................................

Note: This page contains sample records for the topic "facility disposition project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


241

Project Financial Summary Report Concerning Financing Surface Facilities for a 50 Megawatt Geothermal Electric Power Plant Facility in Utah  

DOE Green Energy (OSTI)

This report summarizes the economic and financial conditions pertaining to geothermal electric power plant utilization of geothermal fluids produced from the Roosevelt Hot springs area of Utah. The first year of electric power generation is scheduled to be 1982. The non-resource facilities will be called ''surface facilities'' and include the gathering system, the power plant, the substation, and the injection system.

None

1978-06-23T23:59:59.000Z

242

HAZWOPER project documents for demolition of the Waste Evaporator Facility, Building 3506, at Oak Ridge National Laboratory, Oak Ridge, Tennessee  

SciTech Connect

This document, in support of the Waste Evaporator Facility (WEF) demolition project and contains the Project Work Plan and the Project Health and Safety Plan for demolition and partial remediation actions by ATG at the Waste Evaporator Facility, Building 3506. Various activities will be conducted during the course of demolition, and this plan provides details on the work steps involved, the identification of hazards, and the health and safety practices necessary to mitigate these hazards. The objective of this document is to develop an approach for implementing demolition activities at the WEF. This approach is based on prior site characterization information and takes into account all of the known hazards at this facility. The Project Work Plan provides instructions and requirements for identified work steps that will be utilized during the performance of demolition, while the Health and Safety Plan addresses the radiological, hazardous material exposure, and industrial safety concerns that will be encountered.

NONE

1996-03-01T23:59:59.000Z

243

Lifecycle baseline summary for ADS 6504IS isotopes facilities Deactivation Project at Oak Ridge National Laboratory, Oak Ridge, Tennessee  

Science Conference Proceedings (OSTI)

The scope of this Activity Data Sheet (ADS) is to provide a detailed plan for the Isotopes Facilities Deactivation Project (IFDP) at the Oak Ridge National Laboratory (ORNL). This project places the former isotopes production facilities in a safe, stable, and environmentally sound condition suitable for an extended period of minimum surveillance and maintenance (S&M) until the facilities are included in the Decontamination and Decommissioning (D&D) Program. The facilities included within this deactivation project are Buildings 3026-C, 3026-D, 3028, 3029, 3038-AHF, 3038-E, 3038-M, 3047, 3517, 7025, and the Center Circle Facilities (Buildings 3030, 3031, 3032, 3033, 3033-A, 3034, and 3118). The scope of deactivation identified in this Baseline Report include surveillance and maintenance activities for each facility, engineering, contamination control and structural stabilization of each facility, radioluminescent (RL) light removal in Building 3026, re-roofing Buildings 3030, 3118, and 3031, Hot Cells Cleanup in Buildings 3047 and 3517, Yttrium (Y) Cell and Barricades Cleanup in Building 3038, Glove Boxes & Hoods Removal in Buildings 3038 and 3047, and Inventory Transfer in Building 3517. For a detailed description of activities within this Work Breakdown Structure (WBS) element, see the Level 6 and Level 7 Element Definitions in Section 3.2 of this report.

NONE

1995-08-01T23:59:59.000Z

244

WASTE TREATMENT AND IMMOBILIZATION PLANT U. S. DEPARTMENT OF ENERGY OFFICE OF RIVER PROTECTION SUBMERGED BED SCRUBBER CONDENSATE DISPOSITION PROJECT - ABSTRACT # 13460  

SciTech Connect

The Hanford Waste Treatment and Immobilization Plant (WTP) will generate an off-gas treatment system secondary liquid waste stream [submerged bed scrubber (SBS) condensate], which is currently planned for recycle back to the WTP Low Activity Waste (LAW) melter. This SBS condensate waste stream is high in Tc-99, which is not efficiently captured in the vitrified glass matrix. A pre-conceptual engineering study was prepared in fiscal year 2012 to evaluate alternate flow paths for melter off-gas secondary liquid waste generated by the WTP LAW facility. This study evaluated alternatives for direct off-site disposal of this SBS without pre-treatment, which mitigates potential issues associated with recycling.

YANOCHO RM; CORCORAN C

2012-11-15T23:59:59.000Z

245

Sludge treatment facility preliminary siting study for the sludge treatment project (A-13B)  

SciTech Connect

This study evaluates various sites in the 100 K area and 200 areas of Hanford for locating a treatment facility for sludge from the K Basins. Both existing facilities and a new standalone facility were evaluated. A standalone facility adjacent to the AW Tank Farm in the 200 East area of Hanford is recommended as the best location for a sludge treatment facility.

WESTRA, A.G.

1999-06-24T23:59:59.000Z

246

Project Financial Summary Report Concerning Financing Surface Facilities for a 50 Megawatt Geothermal Electric Power Plant Facility in Utah  

SciTech Connect

This report summarizes the economic and financial conditions pertaining to geothermal electric power plant utilization of geothermal fluids produced from the Roosevelt Hot springs area of Utah. The first year of electric power generation is scheduled to be 1982. The non-resource facilities will be called ''surface facilities'' and include the gathering system, the power plant, the substation, and the injection system.

1978-06-23T23:59:59.000Z

247

EM Makes Significant Progress on Dispositioning Transuranic Waste at Idaho  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

EM Makes Significant Progress on Dispositioning Transuranic Waste EM Makes Significant Progress on Dispositioning Transuranic Waste at Idaho Site EM Makes Significant Progress on Dispositioning Transuranic Waste at Idaho Site December 24, 2013 - 12:00pm Addthis Workers treat sludge-bearing, transuranic waste from the Advanced Mixed Waste Treatment Project. Workers treat sludge-bearing, transuranic waste from the Advanced Mixed Waste Treatment Project. A tank at the Materials and Fuels Complex containing residual sodium is moved prior to waste treatment. A tank at the Materials and Fuels Complex containing residual sodium is moved prior to waste treatment. Distillation equipment is shown prior to transport to the Idaho site. Distillation equipment is shown prior to transport to the Idaho site. In these 2010 photographs, unexploded ordnance were collected and then detonated onsite at the Mass Detonation Area.

248

EM Makes Significant Progress on Dispositioning Transuranic Waste at Idaho  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

EM Makes Significant Progress on Dispositioning Transuranic Waste EM Makes Significant Progress on Dispositioning Transuranic Waste at Idaho Site EM Makes Significant Progress on Dispositioning Transuranic Waste at Idaho Site December 24, 2013 - 12:00pm Addthis Workers treat sludge-bearing, transuranic waste from the Advanced Mixed Waste Treatment Project. Workers treat sludge-bearing, transuranic waste from the Advanced Mixed Waste Treatment Project. A tank at the Materials and Fuels Complex containing residual sodium is moved prior to waste treatment. A tank at the Materials and Fuels Complex containing residual sodium is moved prior to waste treatment. Distillation equipment is shown prior to transport to the Idaho site. Distillation equipment is shown prior to transport to the Idaho site. In these 2010 photographs, unexploded ordnance were collected and then detonated onsite at the Mass Detonation Area.

249

USE AND CALIBRATION OF A GAS CHROMATOGRAPH FOR GAS ANALYSIS AT THE PROJECT ROVER TEST FACILITY  

DOE Green Energy (OSTI)

A gas-chromatograph system operated by test site personnel was used for over a year to monitor the purity of gases used at the Project Rover test facilities at the Nuclear Rocket Development Station. Information was obtained on the efficiency of gas line purges, total impurities of frozen air in a large liquid hydrogen dewar, and the quality of room inerting systems. Daily monitoring of several block and bleed systems, which prevent hydrogen gas from entering a system through a leaky valve, and periodic monitoring of all gas added to the 10/sup 6/ cubic feet gas storage bottles are required for safe facilities operation. In addition the chromatograph proved useful in special cases for leak detection in vacuum and high pressure systems. The calibration and operation of the chromatograph system using a column of Linde 5A Molecular Sieve for analysis of H/sub 2/, N/sub 2/, land O/sub 2/ is described. Observations of a thermal conductivity reversal in the binary mixture He--H/sub 2/ is presented. (auth)

Liebenberg, D.H.; Edeskuty, F.J.

1963-10-31T23:59:59.000Z

250

Commercial Light Water Reactor -Tritium Extraction Facility Process Waste Assessment (Project S-6091)  

Science Conference Proceedings (OSTI)

The Savannah River Site (SRS) has been tasked by the Department of Energy (DOE) to design and construct a Tritium Extraction Facility (TEF) to process irradiated tritium producing burnable absorber rods (TPBARs) from a Commercial Light Water Reactor (CLWR). The plan is for the CLWR-TEF to provide tritium to the SRS Replacement Tritium Facility (RTF) in Building 233-H in support of DOE requirements. The CLWR-TEF is being designed to provide 3 kg of new tritium per year, from TPBARS and other sources of tritium (Ref. 1-4).The CLWR TPBAR concept is being developed by Pacific Northwest National Laboratory (PNNL). The TPBAR assemblies will be irradiated in a Commercial Utility light water nuclear reactor and transported to the SRS for tritium extraction and processing at the CLWR-TEF. A Conceptual Design Report for the CLWR-TEF Project was issued in July 1997 (Ref. 4).The scope of this Process Waste Assessment (PWA) will be limited to CLWR-TEF processing of CLWR irradiated TPBARs. Although the CLWR- TEF will also be designed to extract APT tritium-containing materials, they will be excluded at this time to facilitate timely development of this PWA. As with any process, CLWR-TEF waste stream characteristics will depend on process feedstock and contaminant sources. If irradiated APT tritium-containing materials are to be processed in the CLWR-TEF, this PWA should be revised to reflect the introduction of this contaminant source term.

Hsu, R.H.; Delley, A.O.; Alexander, G.J.; Clark, E.A.; Holder, J.S.; Lutz, R.N.; Malstrom, R.A.; Nobles, B.R. [Westinghouse Savannah River Co., Aiken, SC (United States); Carson, S.D. [Sandia National Laboratories, New Mexico, NM (United States); Peterson, P.K. [Sandia National Laboratories, New Mexico, NM (United States)

1997-11-30T23:59:59.000Z

251

Memo Issuance of EM Capital and Major Operating Project Standard Review Plan Edition Two  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

MAR 2 4 201011 MAR 2 4 201011 MEMORANDUM FOR DISTRIBUTION FROM: DR. STEVEN L. KRAHN DEPUTY ASSISTANT SAFETY AND SECU EIVVIROIVMENTAL MANAGEMENT SUBJECT: Issuance of Environmental Management Capital and Major Operating Project Standard Review Plan Edition Two The Office of Environmental Management (EM) is responsible for managing the design, construction, operation, and eventual disposition of mission critical projects/facilities. Effective management of these projects requires multiple disciplines to be integrated and engaged at various project lifecycle phases. These disciplines include project management, engineering, design, safety, environment, safeguards and security, and quality assurance. The lessons-learned to date from ongoing Headquarters (HQ) and Field project reviews [e.g., Construction Project

252

D&D Toolbox Project - Technology Demonstration of Fixatives Applied to Hot Cell Facilities via Remote Sprayer Platforms  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Demonstration Demonstration D&D Toolbox - FIU Tech Demo FIU Technology Demonstration - Selected technology platform(s) was demonstrated at the hot cell mockup facility at the FIU's Applied Research Center tech demo site in Miami, FL. Page 1 of 2 Oak Ridge National Laboratory Tennessee Florida New York D&D Toolbox Project - Technology Demonstration of Fixatives Applied to Hot Cell Facilities via Remote Sprayer Platforms Challenge Many facilities slated for D&D across the DOE complex pose hazards (radiological, chemical, and structural) which prevent the use of traditional manual techniques. Efficient and safe D&D of the facilities will require the use of remotely operated technologies. In addition, the D&D of a hot cell facility requires that each of the hot cells be

253

Independent Activity Report, West Valley Demonstration Project - July 2012  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

West Valley Demonstration Project - West Valley Demonstration Project - July 2012 Independent Activity Report, West Valley Demonstration Project - July 2012 July 2012 Operational Awareness Oversight of the West Valley Demonstration Project [HIAR WVDP-2012-07-30] The purpose of this Office of Health, Safety and Security (HSS) activity was for the HS-45 Site Lead to meet with Department of Energy (DOE) site personnel, tour the facilities, and obtain a status report on the upcoming activities at the West Valley Demonstration Project (WVDP). In the fall of 2011, a new contractor, CH2M Hill-B&W West Valley (CHBWV), was selected to perform site operations for Phase 1 decommissioning and facility disposition, including the Main Plant Process Building, the Low-Level Waste Treatment Facility, and other facilities.

254

disposition. prices | OpenEI  

Open Energy Info (EERE)

disposition. prices disposition. prices Dataset Summary Description This dataset comes from the Energy Information Administration (EIA), and is part of the 2011 Annual Energy Outlook Report (AEO2011). This dataset is Table 15, and contains only the reference case. The dataset uses gigawatts. The data is broken down into production, net imports, consumption by sector and price. Source EIA Date Released April 26th, 2011 (3 years ago) Date Updated Unknown Keywords 2011 AEO coal coal supply disposition. prices EIA Data application/vnd.ms-excel icon AEO2011: Coal Supply, Disposition, and Prices- Reference Case (xls, 91.7 KiB) Quality Metrics Level of Review Peer Reviewed Comment Temporal and Spatial Coverage Frequency Annually Time Period 2008-2035 License License Open Data Commons Public Domain Dedication and Licence (PDDL)

255

Safe, Cost Effective Management of Inactive Facilities at the Savannah River Site  

SciTech Connect

The Savannah River Site is part of the U.S. Department of Energy complex. It was constructed during the early 1950s to produce basic materials (such as plutonium-239 and tritium) used in the production of nuclear weapons. The 310-square-mile site is located in South Carolina, about 12 miles south of Aiken, South Carolina, and about 15 miles southeast of Augusta, Georgia. Savannah River Site (SRS) has approximately 200 facilities identified as inactive. These facilities range in size and complexity from large nuclear reactors to small storage buildings. These facilities are located throughout the site including three reactor areas, the heavy water plant area, the manufacturing area, and other research and support areas. Unlike DOE Closure Sites such as Hanford and Rocky Flats, SRS is a Project Completion Site with continuing missions. As facilities complete their defined mission, they are shutdown and transferred from operations to the facility disposition program. At the SRS, Facilities Decontamination and Decommissioning (FDD) personnel manage the disposition phase of a inactive facility's life cycle in a manner that minimizes life cycle cost without compromising (1) the health or safety of workers and the public or (2) the quality of the environment. The disposition phase begins upon completion of operations shutdown and extends through establishing the final end-state. FDD has developed innovative programs to manage their responsibilities within a constrained budget.

Austin, W. E.; Yannitell, D. M.; Freeman, D. W.

2002-02-25T23:59:59.000Z

256

EIS-0229: Storage and Disposition of Weapons-Usable Fissile Materials |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

29: Storage and Disposition of Weapons-Usable Fissile 29: Storage and Disposition of Weapons-Usable Fissile Materials EIS-0229: Storage and Disposition of Weapons-Usable Fissile Materials Summary The EIS will evaluate the reasonable alternatives and potential environmental impacts for the proposed siting, construction, and operation of three types of facilities for plutonium disposition. Public Comment Opportunities None available at this time. Documents Available For Download September 5, 2007 EIS-0229: Supplement Analysis (September 2007) Storage of Surplus Plutonium Materials at the Savannah River Site November 14, 2003 EIS-0229: Record of Decision (November 2003) Storage and Disposition of Weapons-Usable Fissile Materials November 7, 2003 EIS-0229-SA-03: Supplement Analysis Fabrication of Mixed Oxide Fuel Lead Assemblies in Europe

257

REQUEST FOR RECORDS DISPOSITION AUTHORITY | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

REQUEST FOR RECORDS DISPOSITION AUTHORITY REQUEST FOR RECORDS DISPOSITION AUTHORITY U. S. Atomic Energy Commision REQUEST FOR RECORDS DISPOSITION AUTHORITY More Documents &...

258

Request For Records Disposition Authority | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Oil and Gas Division Request For Records Disposition Authority More Documents & Publications REQUEST FOR RECORDS DISPOSITION AUTHORITY Request For Records Disposition Autnority...

259

Request For Records Disposition Authority | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Disposition Authority Request For Records Disposition Authority Naval Petroleum and Oil Shale Reserves Request For Records Disposition Authority More Documents & Publications...

260

Disposition of excess fissile materials in deep boreholes  

SciTech Connect

As a result of recent changes throughout the world, a substantial inventory of excess separated plutonium is expected to result from dismantlement of US nuclear weapons. The safe and secure management and eventual disposition of this plutonium, and of a similar inventory in Russia, is a high priority. A variety of options (both interim and permanent) are under consideration to manage this material. The permanent solutions can be categorized into two broad groups: direct disposal and utilization. Plutonium utilization options have in common the generation of high-level radioactive waste which will be disposed of in a mined geologic disposal system to be developed for spent reactor fuel and defense high level waste. Other final disposition forms, such as plutonium metal, plutonium oxide and plutonium immobilized without high-level radiation sources may be better suited to placement in a custom facility. This paper discusses a leading candidate for such a facility; deep (several kilometer) borehole disposition. The deep borehole disposition concept involves placing excess plutonium deep into old stable rock formations with little free water present. The safety argument centers around ancient groundwater indicating lack of migration, and thus no expected communication with the accessible environment until the plutonium has decayed.

Halsey, W.G. [Lawrence Livermore National Lab., CA (United States); Danker, W. [USDOE, Washington, DC (United States); Morley, R. [Los Alamos National Lab., NM (United States)

1995-09-01T23:59:59.000Z

Note: This page contains sample records for the topic "facility disposition project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


261

Life cycle baseline summary for ADS 6504IS Isotopes Facilities Deactivation Project at Oak Ridge National Laboratory, Oak Ridge, Tennessee  

Science Conference Proceedings (OSTI)

The purpose of the Isotopes Facility Deactivation Project (IFDP) is to place former isotopes production facilities at the Oak Ridge National Laboratory in a safe, stable, and environmentally sound condition; suitable for an extended period of minimum surveillance and maintenance (S&M) and as quickly and economically as possible. This baseline plan establishes the official target schedule for completing the deactivation work and the associated budget required for deactivation and the necessary S&M. Deactivation of the facilities 3026C, 3026D, 3028, 3029, 3038E, 3038M, and 3038AHF, the Center Circle buildings 3047, 3517, and 7025 will continue though Fiscal Year (FY) 1999. The focus of the project in the early years will be on the smaller buildings that require less deactivation and can bring an early return in reducing S&M costs. This baseline plan covers the period from FY1995 throughout FY2000. Deactivation will continue in various facilities through FY1999. A final year of S&M will conclude the project in FY2000. The estimated total cost of the project during this period is $51M.

NONE

1995-11-01T23:59:59.000Z

262

Disposition of DOE Excess Depleted Uranium, Natural Uranium, and  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Disposition of DOE Excess Depleted Uranium, Natural Uranium, and Disposition of DOE Excess Depleted Uranium, Natural Uranium, and Low-Enriched Uranium Disposition of DOE Excess Depleted Uranium, Natural Uranium, and Low-Enriched Uranium The U.S. Department of Energy (DOE) owns and manages an inventory of depleted uranium (DU), natural uranium (NU), and low-enriched uranium (LEU) that is currently stored in large cylinders as depleted uranium hexafluoride (DUF6), natural uranium hexafluoride (NUF6), and low-enriched uranium hexafluoride (LEUF6) at the DOE Paducah site in western Kentucky (DOE Paducah) and the DOE Portsmouth site near Piketon in south-central Ohio (DOE Portsmouth)1. This inventory exceeds DOE's current and projected energy and defense program needs. On March 11, 2008, the Secretary of Energy issued a policy statement (the

263

Fort Irwin integrated resource assessment. Volume 3: Sitewide Energy Project identification for buildings and facilities  

SciTech Connect

The U.S. Army Forces Command (FORSCOM) has tasked the U.S. Department of Energy (DOE) Federal Energy Management Program (FEMP), supported by the Pacific Northwest Laboratory, to identify, evaluate, and assist in acquiring all cost-effective energy projects at Fort Irwin. This is part of a model program that PNL is designing to support energy-use decisions in the federal sector. This report provides the results of the fossil fuel and electric energy resource opportunity (ERO) assessments performed by PNL at the FORSCOM Fort Irwin facility located near Barstow, California. It is a companion report to Volume 1, Executive Summary, and Volume 2, Baseline Detail. The results of the analyses of EROs are presented in 16 common energy end-use categories (e.g., boilers and furnaces, service hot water, and building lighting). A narrative description of each ERO is provided, along with a table detailing information on the installed cost, energy and dollar savings; impacts on operations and maintenance (O&M); and, when applicable, a discussion of energy supply and demand, energy security, and environmental issues. A description of the evaluation methodologies and technical and cost assumptions is also provided for each ERO. Summary tables present the cost-effectiveness of energy end-use equipment before and after the implementation of each ERO and present the results of the life-cycle cost (LCC) analysis indicating the net present valve (NPV) and savings-to-investment ratio (SIR) of each ERO.

Keller, J.M.; Dittmer, A.L.; Elliott, D.B.; McMordie, K.L.; Richman, E.E.; Stucky, D.J.; Wahlstrom, R.R.; Hadley, D.L.

1995-02-01T23:59:59.000Z

264

Cultural-resource survey report: Hoover Dam Powerplant Modification Project II. Associated transmission-line facility  

Science Conference Proceedings (OSTI)

The Bureau of Reclamation (Reclamation) is proposing to modify or install additional transmission facilities between the Hoover Dam hydroelectric plant and the Western Area Power Authority substation near Boulder City, Nevada. Reclamation has completed cultural resource investigations to identify historic or prehistoric resources in the project area that might be affected during construction of the transmission line. Four possible transmission corridors approximately 50 feet wide and between 9.5 and 11.5 miles long were investigated. The proposed transmission lines either parallel or replace existing transmission lines. The corridors generally have undergone significant disturbance from past transmission line construction. A Class II sampling survey covering approximately 242 acres was conducted. Access or construction roads have not been identified and surveys of these areas will have to be completed in the future. No historic or prehistoric archeological sites were encountered within the four corridor right-of-ways. It is believed that the probability for prehistoric sites is very low. Four historic period sites were recorded that are outside, but near, the proposed corridor. These sites are not individually eligible for the National Register of Historic Places, but may be associated with the construction of Hoover Dam and contribute to a historic district or multiple property resource area focusing on the dam and its construction.

Queen, R.L.

1991-06-01T23:59:59.000Z

265

Sampling and analysis plan for the preoperational environmental survey of the spent nuclear fuel project facilities  

Science Conference Proceedings (OSTI)

This sampling and analysis plan will support the preoperational environmental monitoring for construction, development, and operation of the Spent Nuclear Fuel (SNF) Project facilities, which have been designed for the conditioning and storage of spent nuclear fuels; particularly the fuel elements associated with the operation of N-Reactor. The SNF consists principally of irradiated metallic uranium, and therefore includes plutonium and mixed fission products. The primary effort will consist of removing the SNF from the storage basins in K East and K West Areas, placing in multicanister overpacks, vacuum drying, conditioning, and subsequent dry vault storage in the 200 East Area. The primary purpose and need for this action is to reduce the risks to public health and safety and to the environment. Specifically these include prevention of the release of radioactive materials into the air or to the soil surrounding the K Basins, prevention of the potential migration of radionuclides through the soil column to the nearby Columbia River, reduction of occupational radiation exposure, and elimination of the risks to the public and to workers from the deterioration of SNF in the K Basins.

MITCHELL, R.M.

1999-04-01T23:59:59.000Z

266

Environmental Management Construction Project Review of the Savannah River Site Salt Waste Processing Facility, July 19-22, 210  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Office of Independent Oversight's Office of Environment, Safety and Health Office of Independent Oversight's Office of Environment, Safety and Health Evaluations Activity Report for the Shadowing of the Environmental Management Construction Project Review of the Savannah River Site Salt Waste Processing Facility on July 19-22, 2010 A Department of Energy Construction Project Review (CPR) of the Salt Waste Processing Facility (SWPF) project was conducted on July 19-22, 2010, at the request of the Principal Deputy Secretary, Office of Environmental Management (EM-2). The purpose of the review was to assess the cost, schedule, and technical progress against the approved Performance Baseline. Specific review areas were Engineering; Commissioning; Environment, Safety, Health, and Quality Assurance; Cost, Schedule, and Risk; and Management and Acquisition.

267

NRC comprehensive records disposition schedule  

SciTech Connect

Title 44 United States Code, Public Printing and Documents,'' regulations cited in the General Services Administration's (GSA) Federal Information Resources Management Regulations'' (FIRMR), Part 201-9, Creation, Maintenance, and Use of Records,'' and regulation issued by the National Archives and Records Administration (NARA) in 36 CFR Chapter XII, Subchapter B, Records Management,'' require each agency to prepare and issue a comprehensive records disposition schedule that contains the NARA approved records disposition schedules for records unique to the agency and contains the NARA's General Records Schedules for records common to several or all agencies. The approved records disposition schedules specify the appropriate duration of retention and the final disposition for records created or maintained by the NRC. NUREG-0910, Rev. 2, contains NRC's Comprehensive Records Disposition Schedule,'' and the original authorized approved citation numbers issued by NARA. Rev. 2 totally reorganizes the records schedules from a functional arrangement to an arrangement by the host office. A subject index and a conversion table have also been developed for the NRC schedules to allow staff to identify the new schedule numbers easily and to improve their ability to locate applicable schedules.

Not Available

1992-03-01T23:59:59.000Z

268

SLUDGE TREATMENT PROJECT PHASE 1 SLUDGE STORAGE OPTIONS ASSESSMENT OF T PLANT VERSUS ALTERNATE STORAGE FACILITY  

Science Conference Proceedings (OSTI)

The CH2M HILL Plateau Remediation Company (CHPRC) has recommended to the U.S. Department of Energy (DOE) a two phase approach for removal and storage (Phase 1) and treatment and packaging for offsite shipment (Phase 2) of the sludge currently stored within the 105-K West Basin. This two phased strategy enables early removal of sludge from the 105-K West Basin by 2015, allowing remediation of historical unplanned releases of waste and closure of the 100-K Area. In Phase 1, the sludge currently stored in the Engineered Containers and Settler Tanks within the 105-K West Basin will be transferred into sludge transport and storage containers (STSCs). The STSCs will be transported to an interim storage facility. In Phase 2, sludge will be processed (treated) to meet shipping and disposal requirements and the sludge will be packaged for final disposal at a geologic repository. The purpose of this study is to evaluate two alternatives for interim Phase 1 storage of K Basin sludge. The cost, schedule, and risks for sludge storage at a newly-constructed Alternate Storage Facility (ASF) are compared to those at T Plant, which has been used previously for sludge storage. Based on the results of the assessment, T Plant is recommended for Phase 1 interim storage of sludge. Key elements that support this recommendation are the following: (1) T Plant has a proven process for storing sludge; (2) T Plant storage can be implemented at a lower incremental cost than the ASF; and (3) T Plant storage has a more favorable schedule profile, which provides more float, than the ASF. Underpinning the recommendation of T Plant for sludge storage is the assumption that T Plant has a durable, extended mission independent of the K Basin sludge interim storage mission. If this assumption cannot be validated and the operating costs of T Plant are borne by the Sludge Treatment Project, the conclusions and recommendations of this study would change. The following decision-making strategy, which is dependent on the confidence that DOE has in the long term mission for T Plant, is proposed: (1) If the confidence level in a durable, extended T Plant mission independent of sludge storage is high, then the Sludge Treatment Project (STP) would continue to implement the path forward previously described in the Alternatives Report (HNF-39744). Risks to the sludge project can be minimized through the establishment of an Interface Control Document (ICD) defining agreed upon responsibilities for both the STP and T Plant Operations regarding the transfer and storage of sludge and ensuring that the T Plant upgrade and operational schedule is well integrated with the sludge storage activities. (2) If the confidence level in a durable, extended T Plant mission independent of sludge storage is uncertain, then the ASF conceptual design should be pursued on a parallel path with preparation of T Plant for sludge storage until those uncertainties are resolved. (3) Finally, if the confidence level in a durable, extended T Plant mission independent of sludge storage is low, then the ASF design should be selected to provide independence from the T Plant mission risk.

RUTHERFORD WW; GEUTHER WJ; STRANKMAN MR; CONRAD EA; RHOADARMER DD; BLACK DM; POTTMEYER JA

2009-04-29T23:59:59.000Z

269

Status Review of Wildlife Mitigation, Columbia Basin Hydroelectric Projects, Washington Facilities (Intrastate) Final Report.  

DOE Green Energy (OSTI)

This report was prepared for BPA in fulfillment of section 1004 (b)(1) of the Pacific Northwest Electric Power Planning and Conservation Act of 1980, to review the status of past, present, and proposed future wildlife planning and mitigation program at existing hydroelectric projects in the Columbia River Basin. The project evaluations will form the basis for determining any needed remedial measures or additional project analysis. Projects addressed are: Merwin Dam; Swift Project; Yale Project; Cowlitz River; Boundary Dam; Box Canyon Dam; Lake Chelan; Condit Project; Enloe Project; Spokane River; Tumwater and Dryden Dam; Yakima; and Naches Project.

Howerton, Jack

1984-11-01T23:59:59.000Z

270

Central and Eastern United States (CEUS) Seismic Source Characterization (SSC) for Nuclear Facilities Project  

SciTech Connect

This report describes a new seismic source characterization (SSC) model for the Central and Eastern United States (CEUS). It will replace the Seismic Hazard Methodology for the Central and Eastern United States, EPRI Report NP-4726 (July 1986) and the Seismic Hazard Characterization of 69 Nuclear Plant Sites East of the Rocky Mountains, Lawrence Livermore National Laboratory Model, (Bernreuter et al., 1989). The objective of the CEUS SSC Project is to develop a new seismic source model for the CEUS using a Senior Seismic Hazard Analysis Committee (SSHAC) Level 3 assessment process. The goal of the SSHAC process is to represent the center, body, and range of technically defensible interpretations of the available data, models, and methods. Input to a probabilistic seismic hazard analysis (PSHA) consists of both seismic source characterization and ground motion characterization. These two components are used to calculate probabilistic hazard results (or seismic hazard curves) at a particular site. This report provides a new seismic source model. Results and Findings The product of this report is a regional CEUS SSC model. This model includes consideration of an updated database, full assessment and incorporation of uncertainties, and the range of diverse technical interpretations from the larger technical community. The SSC model will be widely applicable to the entire CEUS, so this project uses a ground motion model that includes generic variations to allow for a range of representative site conditions (deep soil, shallow soil, hard rock). Hazard and sensitivity calculations were conducted at seven test sites representative of different CEUS hazard environments. Challenges and Objectives The regional CEUS SSC model will be of value to readers who are involved in PSHA work, and who wish to use an updated SSC model. This model is based on a comprehensive and traceable process, in accordance with SSHAC guidelines in NUREG/CR-6372, Recommendations for Probabilistic Seismic Hazard Analysis: Guidance on Uncertainty and Use of Experts. The model will be used to assess the present-day composite distribution for seismic sources along with their characterization in the CEUS and uncertainty. In addition, this model is in a form suitable for use in PSHA evaluations for regulatory activities, such as Early Site Permit (ESPs) and Combined Operating License Applications (COLAs). Applications, Values, and Use Development of a regional CEUS seismic source model will provide value to those who (1) have submitted an ESP or COLA for Nuclear Regulatory Commission (NRC) review before 2011; (2) will submit an ESP or COLA for NRC review after 2011; (3) must respond to safety issues resulting from NRC Generic Issue 199 (GI-199) for existing plants and (4) will prepare PSHAs to meet design and periodic review requirements for current and future nuclear facilities. This work replaces a previous study performed approximately 25 years ago. Since that study was completed, substantial work has been done to improve the understanding of seismic sources and their characterization in the CEUS. Thus, a new regional SSC model provides a consistent, stable basis for computing PSHA for a future time span. Use of a new SSC model reduces the risk of delays in new plant licensing due to more conservative interpretations in the existing and future literature. Perspective The purpose of this study, jointly sponsored by EPRI, the U.S. Department of Energy (DOE), and the NRC was to develop a new CEUS SSC model. The team assembled to accomplish this purpose was composed of distinguished subject matter experts from industry, government, and academia. The resulting model is unique, and because this project has solicited input from the present-day larger technical community, it is not likely that there will be a need for significant revision for a number of years. See also Sponsors Perspective for more details. The goal of this project was to implement the CEUS SSC work plan for developing a regional CEUS SSC model. The work plan, formulated by the project manager and a

Kevin J. Coppersmith; Lawrence A. Salomone; Chris W. Fuller; Laura L. Glaser; Kathryn L. Hanson; Ross D. Hartleb; William R. Lettis; Scott C. Lindvall; Stephen M. McDuffie; Robin K. McGuire; Gerry L. Stirewalt; Gabriel R. Toro; Robert R. Youngs; David L. Slayter; Serkan B. Bozkurt; Randolph J. Cumbest; Valentina Montaldo Falero; Roseanne C. Perman' Allison M. Shumway; Frank H. Syms; Martitia (Tish) P. Tuttle

2012-01-31T23:59:59.000Z

271

Central and Eastern United States (CEUS) Seismic Source Characterization (SSC) for Nuclear Facilities Project  

Science Conference Proceedings (OSTI)

This report describes a new seismic source characterization (SSC) model for the Central and Eastern United States (CEUS). It will replace the Seismic Hazard Methodology for the Central and Eastern United States, EPRI Report NP-4726 (July 1986) and the Seismic Hazard Characterization of 69 Nuclear Plant Sites East of the Rocky Mountains, Lawrence Livermore National Laboratory Model, (Bernreuter et al., 1989). The objective of the CEUS SSC Project is to develop a new seismic source model for the CEUS using a Senior Seismic Hazard Analysis Committee (SSHAC) Level 3 assessment process. The goal of the SSHAC process is to represent the center, body, and range of technically defensible interpretations of the available data, models, and methods. Input to a probabilistic seismic hazard analysis (PSHA) consists of both seismic source characterization and ground motion characterization. These two components are used to calculate probabilistic hazard results (or seismic hazard curves) at a particular site. This report provides a new seismic source model. Results and Findings The product of this report is a regional CEUS SSC model. This model includes consideration of an updated database, full assessment and incorporation of uncertainties, and the range of diverse technical interpretations from the larger technical community. The SSC model will be widely applicable to the entire CEUS, so this project uses a ground motion model that includes generic variations to allow for a range of representative site conditions (deep soil, shallow soil, hard rock). Hazard and sensitivity calculations were conducted at seven test sites representative of different CEUS hazard environments. Challenges and Objectives The regional CEUS SSC model will be of value to readers who are involved in PSHA work, and who wish to use an updated SSC model. This model is based on a comprehensive and traceable process, in accordance with SSHAC guidelines in NUREG/CR-6372, Recommendations for Probabilistic Seismic Hazard Analysis: Guidance on Uncertainty and Use of Experts. The model will be used to assess the present-day composite distribution for seismic sources along with their characterization in the CEUS and uncertainty. In addition, this model is in a form suitable for use in PSHA evaluations for regulatory activities, such as Early Site Permit (ESPs) and Combined Operating License Applications (COLAs). Applications, Values, and Use Development of a regional CEUS seismic source model will provide value to those who (1) have submitted an ESP or COLA for Nuclear Regulatory Commission (NRC) review before 2011; (2) will submit an ESP or COLA for NRC review after 2011; (3) must respond to safety issues resulting from NRC Generic Issue 199 (GI-199) for existing plants and (4) will prepare PSHAs to meet design and periodic review requirements for current and future nuclear facilities. This work replaces a previous study performed approximately 25 years ago. Since that study was completed, substantial work has been done to improve the understanding of seismic sources and their characterization in the CEUS. Thus, a new regional SSC model provides a consistent, stable basis for computing PSHA for a future time span. Use of a new SSC model reduces the risk of delays in new plant licensing due to more conservative interpretations in the existing and future literature. Perspective The purpose of this study, jointly sponsored by EPRI, the U.S. Department of Energy (DOE), and the NRC was to develop a new CEUS SSC model. The team assembled to accomplish this purpose was composed of distinguished subject matter experts from industry, government, and academia. The resulting model is unique, and because this project has solicited input from the present-day larger technical community, it is not likely that there will be a need for significant revision for a number of years. See also Sponsors Perspective for more details. The goal of this project was to implement the CEUS SSC work plan for developing a regional CEUS SSC model. The work plan, formulated by the project manager and a

Kevin J. Coppersmith; Lawrence A. Salomone; Chris W. Fuller; Laura L. Glaser; Kathryn L. Hanson; Ross D. Hartleb; William R. Lettis; Scott C. Lindvall; Stephen M. McDuffie; Robin K. McGuire; Gerry L. Stirewalt; Gabriel R. Toro; Robert R. Youngs; David L. Slayter; Serkan B. Bozkurt; Randolph J. Cumbest; Valentina Montaldo Falero; Roseanne C. Perman' Allison M. Shumway; Frank H. Syms; Martitia (Tish) P. Tuttle

2012-01-31T23:59:59.000Z

272

Summary - Uranium233 Downblending and Disposition Project  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

and prepar sal. The projec blended materia or the Nevada cted to coincid ack-end" of the ng observation sment team to ology maturity p What th ssessment team ology Element ology...

273

EPRI Report on Solid Material Disposition: Evaluation to Assess Industry Impact  

Science Conference Proceedings (OSTI)

In March 2005, the NRC staff requested Commission approval for publication of a proposed rule in the Federal Register to amend 10CFR Part 20 to include criteria for controlling the disposition of solid materials. This report provides an initial analysis of whether or not methods of solid material assessment, currently practiced at nuclear power facilities, would be sufficient to meet the disposition limits in the proposed rule.

2005-12-01T23:59:59.000Z

274

REQUEST FOR RECORDS DISPOSITION AUTHORITY  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

LEAVE BLANK (NARA use only) LEAVE BLANK (NARA use only) JOB NUMBER To: NATIONAL ARCHIVES & RECORDS ADMINISTRATION 8601 ADELPHI ROAD, COLLEGE PARK, MD 20740-6001 Date Received 1. FROM (Agency or establishment) NOTIFICATION TO AGENCY In accordance with the provisions of 44 U.S.C 3303a, the disposition request, including amendments is approved except for items that may be marked "disposition not approved" or "withdrawn" in column 10. 2. MAJOR SUB DIVISION 3. MINOR SUBDIVISION 4. NAME OF PERSON WITH WHOM TO CONFER 5. TELEPHONE DATE ARCHIVIST OF THE UNITED STATES 6. AGENCY CERTIFICATION I hereby certify that I am authorized to act for this agency in matters pertaining to the disposition of its records and that the records proposed for disposal on the attached______page(s) are not needed now for the business of this agency or will not be

275

Cold test plan for the Old Hydrofracture Facility tank contents removal project, Oak Ridge National Laboratory, Oak Ridge, Tennessee  

SciTech Connect

This Old Hydrofracture Facility (OHF) Tanks Contents Removal Project Cold Test Plan describes the activities to be conducted during the cold test of the OHF sluicing and pumping system at the Tank Technology Cold Test Facility (TTCTF). The TTCTF is located at the Robotics and Process Systems Complex at the Oak Ridge National Laboratory (ORNL). The cold test will demonstrate performance of the pumping and sluicing system, fine-tune operating instructions, and train the personnel in the actual work to be performed. After completion of the cold test a Technical Memorandum will be prepared documenting completion of the cold test, and the equipment will be relocated to the OHF site.

1997-11-01T23:59:59.000Z

276

2013-12-16 Capital Asset Project List.xls  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Approved Project End Approved Project End Date Project Status Critical Decision Total Project Cost Site 01-D-416 Waste Treatment and Immobilization Plant (WTP) 11/30/2019 Active CD3 $12,263,000,000 Office of River Protection 05-D-405 Salt Waste Processing Facility (SWPF) 12/31/2018 Active CD3 $1,339,000,000 Savannah River Site 12-D-403 Savannah River Glass Waste Storage Building #3 TBD On Hold Pre CD-2 CD1 $103,000,000 Savannah River Site CBC-LBNL-0040 LBNL Old Town Demolition Project 3/30/2018 Active CD1 $49,000,000 Lawrence Berkely National Laboratory ID-0012B.C1 Idaho Spent Fuel Facility (ISFF) Project 12/30/2026 On Hold Pre CD-2 CD0 $560,000,000 Idaho National Laboratory ID-0014B.C2 Calcine Disposition Project (CDP) 2/3/2025 Active CD0 $16,000,000,000 Idaho National Laboratory IFDP Integrated Facility Disposition Project (IFDP)

277

(SSS)Capital Asset Project List_1.xls  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Approved Project Approved Project End Date Project Status Critical Decision Total Project Cost Site 01-D-416 Waste Treatment and Immobilization Plant (WTP) 11/30/2019 Active CD3 $12,263,000,000 Office of River Protection 05-D-405 Salt Waste Processing Facility (SWPF) 12/31/2018 Active CD3 $1,339,000,000 Savannah River Site 12-D-403 Savannah River Glass Waste Storage Building #3 TBD On Hold Pre CD-2 CD1 $103,000,000 Savannah River Site CBC-LBNL-0040 LBNL Old Town Demolition Project 9/30/2017 Active CD0 $45,000,000 Lawrence Berkely National Laboratory ID-0012B.C1 Idaho Spent Fuel Facility (ISFF) Project 12/30/2026 On Hold Pre CD-2 CD0 $560,000,000 Idaho National Laboratory ID-0014B.C2 Calcine Disposition Project (CDP) 2/3/2025 Active CD0 $16,000,000,000 Idaho National Laboratory IFDP Integrated Facility Disposition Project (IFDP)

278

Disposition Schedule: Human Radiation Experiments | Department...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Schedule: Human Radiation Experiments Disposition Schedule: Human Radiation Experiments This database contains information on records collections related to human radiation...

279

Material Removal and Disposition | National Nuclear Security...  

National Nuclear Security Administration (NNSA)

Removal and Disposition | National Nuclear Security Administration Our Mission Managing the Stockpile Preventing Proliferation Powering the Nuclear Navy Emergency Response...

280

Documentation assessment, Project C-018H, 200-E area effluent treatment facility  

Science Conference Proceedings (OSTI)

Project C-018H is one of the fourteen subprojects to the Hanford Environmental Compliance (HEC) Project. Project C-018H provides treatment and disposal for the 242-A Evaporator and PUREX plant process condensate waste streams. This project used the Integrated Management Team (IMT) approach proposed by RL. The IMT approach included all affected organizations on the project team to coordinate and execute all required project tasks, while striving to integrate and satisfy all technical, operational, functional, and organizational objectives. The HEC Projects were initiated in 1989. Project C-018H began in early 1990, with completion of construction currently targeted for mid-1995. This assessment was performed to evaluate the effectiveness of the management control on design documents and quality assurance records developed and submitted for processing, use, and retention for the Project. The assessment focused primarily on the overall adequacy and quality of the design documentation currently being submitted to the project document control function.

Peres, M.W.; Connor, M.D.; Mertelendy, J.I.

1994-12-21T23:59:59.000Z

Note: This page contains sample records for the topic "facility disposition project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


281

Special Projects Branch  

E-Print Network (OSTI)

On June 6, 2005, you submitted a U.S. Department of Energy (DOE) report providing the basis for DOEs cost estimate for dispositioning depleted uranium generated at your proposed uranium enrichment facility in

Dear Mr. Krich; Joseph G. Giitter; S Troy Harris/lovington; James Ferl; Cty John Parker/nmed

2006-01-01T23:59:59.000Z

282

RECORDS DISPOSITION AUTHORIZATION STATE AGENCIES  

E-Print Network (OSTI)

RECORDS DISPOSITION AUTHORIZATION ­ STATE AGENCIES Form RC-108 (Revised 07/2011) STATE, CT 06106 www.cslib.org/publicrecords AUTHORITY: State agencies in the Executive branch and certain or Transfer Agreement), and retain pursuant to S1-390. STATE AGENCY: DIVISION / UNIT: ADDRESS (for return

Oliver, Douglas L.

283

DOE/EIS-0415: Final Environmental Impact Statement Deer Creek Station Energy Facility Project Brookings County, South Dakota (April 2010)  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

ENVIRONMENTAL IMPACT STATEMENT Deer Creek Station Energy Facility Project Brookings County, South Dakota U.S. Department of Energy Western Area Power Administration Upper Great Plains Region Billings, Montana DOE/EIS-0415 April 2010 Final Environmental Impact Statement Cover Sheet i COVER SHEET Lead Federal Agency: U.S. Department of Energy, Western Area Power Administration Cooperating Agency: U.S. Department of Agriculture, Rural Utilities Service

284

Final report of the decontamination and decommission of Building 31 at the Grand Junction Projects Office Facility  

SciTech Connect

The U.S. Department of Energy (DOE) Grand Junction Projects Office (GJPO) occupies a 61.7-acre facility along the Gunnison River near Grand Junction, Colorado. This site was contaminated with uranium ore and mill tailings during uranium refining activities of the Manhattan Engineer District and during pilot milling experiments conducted for the domestic uranium procurement program funded by the U.S. Atomic Energy Commission. The DOE Defense Decontamination and Decommissioning Program established the GJPO Remedial Action Project to clean up and restore the facility lands, improvements, and the underlying aquifer. The site contractor for the facility, Rust Geotech, also was the remedial action contractor. Radiological contamination was identified in Building 31 and the building was demolished in 1992. The soil area within the footprint of the building has been remediated in accordance with the identified standards and the area can be released for unlimited exposure and unrestricted use. This area was addressed in the summary final report of the remediation of the exterior areas of the GJPO facility. This document was prepared in response to a DOE request for an individual final report for each contaminated GJPO building.

Krabacher, J.E.

1996-07-01T23:59:59.000Z

285

Final report of the decontamination and decommissioning of Building 34 at the Grand Junction Projects Office Facility  

SciTech Connect

The U.S. Department of Energy (DOE) Grand Junction Projects Office (GJPO) occupies a 61.7 acre facility along the Gunnison River near Grand Junction, Colorado. This site was contaminated with uranium ore and mill tailings during uranium refining activities of the Manhattan Engineer District and during pilot milling experiments conducted for the U.S. Atomic Energy Commission`s domestic uranium procurement program. The DOE Defense Decontamination and Decommissioning Program established the Grand Junction Projects Office Remedial Action Project to clean up and restore the facility lands, improvements, and the underlying aquifer. The site contractor for the facility, Rust Geotech, was also the remedial action contractor. Building 34 was radiologically contaminated and the building was demolished in 1996. The soil area within the footprint of the building was analyzed and found to be not contaminated. The area can be released for unlimited exposure and unrestricted use. This document was prepared in response to a DOE request for an individual closeout report for each contaminated GJPO building.

Widdop, M.R.

1996-08-01T23:59:59.000Z

286

Final report of the decontamination and decommissioning of Building 44 at the Grand Junction Projects Office Facility  

SciTech Connect

The U.S. Department of Energy (DOE) Junction Projects Office (GJPO) occupies a 61.7 acre facility along the Gunnison River near Grand Junction, Colorado. This site was contaminated with uranium ore and mill tailings during uranium refining activities of the Manhattan Engineer District and during pilot milling experiments conducted for the U.S. Atomic Energy Commission`s domestic uranium procurement program. The DOE Defense Decontamination and Decommissioning Program established the Grand Junction Projects Office Remedial Action Project to clean up and restore the facility lands, improvements, and the underlying aquifer. The site contractor for the facility, Rust Geotech, is also the remedial action contractor. Building 44 was radiologically contaminated and the building was demolished in 1994. The soil area within the footprint of the building was not contaminated; it complies with the identified standards and the area can be released for unlimited exposure and unrestricted use. This document was prepared in response to a DOE request for an individual final report for each contaminated GJPO building.

Widdop, M.R.

1996-07-01T23:59:59.000Z

287

Mixed and Low-Level Waste Treatment Facility project. Appendix A, Environmental and regulatory planning and documentation: Draft  

SciTech Connect

Mixed and low-level wastes generated at the Idaho National Engineering Laboratory (INEL) are required to be managed according to applicable State and Federal regulations, and Department of Energy Orders that provide for the protection of human health and the environment. The Mixed and Low-Level Waste Treatment Facility Project was chartered in 1991, by the Department of Energy to provide treatment capability for these mixed and low-level waste streams. The first project task consisted of conducting engineering studies to identify the waste streams, their potential treatment strategies, and the requirements that would be imposed on the waste streams and the facilities used to process them. This report, Appendix A, Environmental & Regulatory Planning & Documentation, identifies the regulatory requirements that would be imposed on the operation or construction of a facility designed to process the INEL`s waste streams. These requirements are contained in five reports that discuss the following topics: (1) an environmental compliance plan and schedule, (2) National Environmental Policy Act requirements, (3) preliminary siting requirements, (4) regulatory justification for the project, and (5) health and safety criteria.

1992-04-01T23:59:59.000Z

288

INFORMATION: Management Alert on Environmental Management's Select Strategy for Disposition of Savannah River Site Depleted Uranium Oxides  

SciTech Connect

The Administration and the Congress, through policy statements and passage of the American Recovery and Reinvestment Act of 2009 (Recovery Act), have signaled that they hope that proactive actions by agency Inspectors General will help ensure that Federal Recovery Act activities are transparent, effective and efficient. In that context, the purpose of this management alert is to share with you concerns that have been raised to the Office of Inspector General regarding the planned disposition of the Savannah River Site's (SRS) inventory of Depleted Uranium (DU) oxides. This inventory, generated as a by-product of the nuclear weapons production process and amounting to approximately 15,600 drums of DU oxides, has been stored at SRS for decades. A Department source we deem reliable and credible recently came to the Office of Inspector General expressing concern that imminent actions are planned that may not provide for the most cost effective disposition of these materials. During April 2009, the Department chose to use funds provided under the Recovery Act to accelerate final disposition of the SRS inventory of DU oxides. After coordination with State of Utah regulators, elected officials and the U.S. Nuclear Regulatory Commission, the Department initiated a campaign to ship the material to a facility operated by EnergySolutions in Clive, Utah. Although one shipment of a portion of the material has already been sent to the EnergySolutions facility, the majority of the product remains at SRS. As had been planned, both for the shipment already made and those planned in the near term, the EnergySolutions facility was to have been the final disposal location for the material. Recently, a member of Congress and various Utah State officials raised questions regarding the radioactive and other constituents present in the DU oxides to be disposed of at the Clive, Utah, facility. These concerns revolved around the characterization of the material and its acceptability under existing licensing criteria. As a consequence, the Governor of Utah met with Department officials to voice concerns regarding further shipments of the material and to seek return of the initial shipment of DU oxides to SRS. Utah's objections and the Department's agreement to accede to the State's demands effectively prohibit the transfer of the remaining material from South Carolina to Utah. In response, the Department evaluated its options and issued a draft decision paper on March 1, 2010, which outlined an alternative for temporary storage until the final disposition issue could be resolved. Under the terms of the proposed option, the remaining shipments from SRS are to be sent on an interim basis to a facility owned by Waste Control Specialists (WCS) in Andrews, Texas. Clearly, this choice carries with it a number of significant logistical burdens, including substantial additional costs for, among several items, repackaging at SRS, transportation to Texas, storage at the interim site, and, repackaging and transportation to the yet-to-be-determined final disposition point. The Department source expressed the concern that the proposal to store the material on an interim basis in Texas was inefficient and unnecessary, asserting: (1) that the materials could remain at SRS until a final disposition path is identified, and that this could be done safely, securely and cost effectively; and, (2) that the nature of the material was not subject to existing compliance agreements with the State of South Carolina, suggesting the viability of keeping the material in storage at SRS until a permanent disposal site is definitively established. We noted that, while the Department's decision paper referred to 'numerous project and programmatic factors that make it impractical to retain the remaining inventory at Savannah River,' it did not outline the specific issues involved nor did it provide any substantive economic or environmental analysis supporting the need for the planned interim storage action. The only apparent driver in this case was a Recovery Act-related goal esta

None

2010-04-01T23:59:59.000Z

289

Fissile Materials Disposition | National Nuclear Security Administration  

National Nuclear Security Administration (NNSA)

Fissile Materials Disposition | National Nuclear Security Administration Fissile Materials Disposition | National Nuclear Security Administration Our Mission Managing the Stockpile Preventing Proliferation Powering the Nuclear Navy Emergency Response Recapitalizing Our Infrastructure Continuing Management Reform Countering Nuclear Terrorism About Us Our Programs Our History Who We Are Our Leadership Our Locations Budget Our Operations Media Room Congressional Testimony Fact Sheets Newsletters Press Releases Speeches Events Social Media Video Gallery Photo Gallery NNSA Archive Federal Employment Apply for Our Jobs Our Jobs Working at NNSA Blog Fissile Materials Disposition Home > About Us > Our Programs > Nonproliferation > Fissile Materials Disposition Fissile Materials Disposition Since the end of the Cold War, significant quantities of plutonium and

290

Spent nuclear fuel project cold vacuum drying facility supporting data and calculation database  

Science Conference Proceedings (OSTI)

This document provides a database of supporting calculations for the Cold Vacuum Drying Facility (CVDF). The database was developed in conjunction with HNF-SD-SNF-SAR-002, ''Safety Analysis Report for the Cold Vacuum Drying Facility'', Phase 2, ''Supporting Installation of Processing Systems'' (Garvin 1998). The HNF-SD-SNF-DRD-002, 1997, ''Cold Vacuum Drying Facility Design Requirements'', Rev. 2, and the CVDF Summary Design Report. The database contains calculation report entries for all process, safety and facility systems in the CVDF, a general CVD operations sequence and the CVDF System Design Descriptions (SDDs). This database has been developed for the SNFP CVDF Engineering Organization and shall be updated, expanded, and revised in accordance with future design, construction and startup phases of the CVDF until the CVDF final ORR is approved.

IRWIN, J.J.

1999-02-26T23:59:59.000Z

291

Neutron Assay System for Confinement Vessel Disposition  

Science Conference Proceedings (OSTI)

Los Alamos National Laboratory has a number of spherical confinement vessels (CVs) remaining from tests involving nuclear materials. These vessels have an inner diameter of 6 feet with 1-inch thick steel walls. The goal of the Confinement Vessel Disposition (CVD) project is to remove debris and reduce contamination inside the CVs. The Confinement Vessel Assay System (CVAS) was developed to measure the amount of special nuclear material (SNM) in CVs before and after cleanout. Prior to cleanout, the system will be used to perform a verification measurement of each vessel. After cleanout, the system will be used to perform safeguards-quality assays of {le}100-g {sup 239}Pu equivalent in a vessel for safeguards termination. The CVAS has been tested and calibrated in preparation for verification and safeguards measurements.

Frame, Katherine C. [Los Alamos National Laboratory; Bourne, Mark M. [Los Alamos National Laboratory; Crooks, William J. [Los Alamos National Laboratory; Evans, Louise [Los Alamos National Laboratory; Mayo, Douglas R. [Los Alamos National Laboratory; Miko, David K. [Los Alamos National Laboratory; Salazar, William R. [Los Alamos National Laboratory; Stange, Sy [Los Alamos National Laboratory; Valdez, Jose I. [Los Alamos National Laboratory; Vigil, Georgiana M. [Los Alamos National Laboratory

2012-07-13T23:59:59.000Z

292

Categorical Exclusion Determinations: Portsmouth Paducah Project Office |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Portsmouth Paducah Project Portsmouth Paducah Project Office Categorical Exclusion Determinations: Portsmouth Paducah Project Office Categorical Exclusion Determinations issued by Portsmouth Paducah Project Office. DOCUMENTS AVAILABLE FOR DOWNLOAD August 9, 2012 CX-009253: Categorical Exclusion Determination Optimization of Electrical Power at the Portsmouth Gaseous Diffusion Facility CX(s) Applied: B4.6, B4.11 Date: 08/09/2012 Location(s): Ohio Offices(s): Portsmouth Paducah Project Office May 9, 2012 CX-008824: Categorical Exclusion Determination X-608 Well Field Transfer CX(s) Applied: B1.24 Date: 05/09/2012 Location(s): Ohio Offices(s): Portsmouth Paducah Project Office April 25, 2012 CX-009252: Categorical Exclusion Determination Disposition of Department of Energy Surplus or Excess Personal Property

293

Final report of the decontamination and decommissioning of Building 1 at the Grand Junction Projects Office Facility  

Science Conference Proceedings (OSTI)

The U.S. Department of Energy (DOE) Grand Junction Projects Office (GJPO) occupies a 61.7-acre facility along the Gunnison River near Grand Junction, Colorado. This site was contaminated with uranium ore and mill tailings during uranium refining activities of the Manhattan Engineer District and during pilot milling experiments conducted for the U.S. Atomic Energy Commission`s domestic uranium procurement program. The DOE Defense Decontamination and Decommissioning Program established the GJPO Remedial Action Project to clean up and restore the facility lands, improvements, and the underlying aquifer. The site contractor for the facility, Rust Geotech, also is the remedial action contractor. Building 1 was found to be radiologically contaminated and was demolished in 1996. The soil beneath and adjacent to the building was remediated in accordance with identified standards and can be released for unlimited exposure and unrestricted use. This document was prepared in response to a DOE request for an individual final report for each contaminated GJPO building.

Widdop, M.R.

1996-08-01T23:59:59.000Z

294

Final report of the decontamination and decommissioning of Building 18 at the Grand Junction Projects Office Facility  

Science Conference Proceedings (OSTI)

The U.S. Department of Energy (DOE) Grand Junction Projects Office (GJPO) occupies a 61.7-acre facility along the Gunnison River near Grand Junction, Colorado. This site was contaminated with uranium ore and mill tailings during uranium refining activities of the Manhattan Engineer District and during pilot milling experiments conducted for the U.S. Atomic Energy Commission`s domestic uranium procurement program. The DOE Defense Decontamination and Decommissioning Program established the GJPO Remedial Action Project to clean up and restore the facility lands, improvements, and the underlying aquifer. The site contractor for the facility, Rust Geotech, also is the remedial action contractor. The soil beneath Building 18 was found to be radiologically contaminated; the building was not contaminated. The soil was remediated in accordance with identified standards. Building 18 and the underlying soil can be released for unlimited exposure and unrestricted use. This document was prepared in response to a DOE request for an individual final report for each contaminated GJPO building.

Widdop, M.R.

1996-08-01T23:59:59.000Z

295

Final report of the decontamination and decommissioning of Building 6 at the Grand Junction Projects Office Facility  

SciTech Connect

The U.S. Department of Energy (DOE) Grand Junction Projects Office (GJPO) occupies a 61.7-acre facility along the Gunnison River near Grand Junction, Colorado. This site was contaminated with uranium ore and mill tailings during uranium refining activities of the Manhattan Engineer District and during pilot milling experiments conducted for the domestic uranium procurement program funded by the U.S. Atomic Energy Commission. The DOE Defense Decontamination and Decommissioning Program established the GJPO Remedial Action Project to clean up and restore the facility lands, improvements, and the underlying aquifer. The site contractor for the facility, Rust Geotech, is also the remedial action contractor. Radiological contamination was identified in Building 6, and the building was demolished in 1992. The soil area within the footprint of the building has been remediated in accordance with the identified standards and the area can be released for unlimited exposure and unrestricted use. This document was prepared in response to a DOE request for an individual final report for each contaminated GJPO building.

Widdop, M.R.

1996-07-01T23:59:59.000Z

296

Final report of the decontamination and decommissioning of Building 39 at the Grand Junction Projects Office Facility  

SciTech Connect

The U.S. Department of Energy (DOE) Grand Junction Projects Office (GJPO) occupies a 61.7-acre facility along the Gunnison River near Grand Junction, Colorado. This site was contaminated with uranium ore and mill tailings during uranium refining activities of the Manhattan Engineer District and during pilot milling experiments conducted for the U.S. Atomic Energy Commission`s domestic uranium procurement program. The DOE Defense Decontamination and Decommissioning Program established the GJPO Remedial Action Project to clean up and restore the facility lands, improvements, and the underlying aquifer. The site contractor for the facility, Rust Geotech, is also the remedial action contractor. The soil beneath Building 39 was radiologically contaminated and the building was demolished in 1992. The soil area within the footprint of the building has been remediated in accordance with the identified standards and the area can be released for unlimited exposure and unrestricted use. This document was prepared in response to a DOE request for an individual final report for each contaminated GJPO building.

Widdop, M.R.

1996-07-01T23:59:59.000Z

297

Developing Renewable Energy Projects Larger Than 10 MWs at Federal Facilities (Book)  

SciTech Connect

To accomplish Federal goals for renewable energy, sustainability, and energy security, large-scale renewable energy projects must be developed and constructed on Federal sites at a significant scale with significant private investment. The U.S. Department of Energy's Federal Energy Management Program (FEMP) helps Federal agencies meet these goals and assists agency personnel navigate the complexities of developing such projects and attract the necessary private capital to complete them. This guide is intended to provide a general resource that will begin to develop the Federal employee's awareness and understanding of the project developer's operating environment and the private sector's awareness and understanding of the Federal environment. Because the vast majority of the investment that is required to meet the goals for large-scale renewable energy projects will come from the private sector, this guide has been organized to match Federal processes with typical phases of commercial project development. The main purpose of this guide is to provide a project development framework to allow the Federal Government, private developers, and investors to work in a coordinated fashion on large-scale renewable energy projects. The framework includes key elements that describe a successful, financially attractive large-scale renewable energy project.

Not Available

2013-03-01T23:59:59.000Z

298

Environmental assessment of facility operations at the U.S. Department of Energy Grand Junction Projects Office, Grand Junction, Colorado  

SciTech Connect

The US Department of Energy (DOE) has prepared a sitewide environmental assessment (EA) of the proposed action to continue and expand present-day activities on the DOE Grand Junction Projects Office (GJPO) facility in Grand Junction, Colorado. Because DOE-GJPO regularly proposes and conducts many different on-site activities, DOE decided to evaluate these activities in one sitewide EA rather than in multiple, activity-specific documents. On the basis of the information and analyses presented in the EA, DOE has determined that the proposed action does not constitute a major Federal action significantly affecting the quality of the human environment, as defined by the National Environmental Policy Act (NEPA) of 1969. Therefore, preparation of an environmental impact statement is not required for facility operations, and DOE is issuing this Finding of No Significant Impact (FONSI).

NONE

1996-06-01T23:59:59.000Z

299

PROJECT MANGEMENT PLAN EXAMPLES Project Management Plan Examples  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Management Plan Examples Management Plan Examples The following material has been extracted from several project management plans. The order in which it is presented is arbitrary. The elements table below should be used to navigate to the subject of interest. Elements of Deactivation Project Planning Deactivation Project Key Planning Elements Reference DOE O 430.1A Reference DOE G 430.1-3 DOE G 430.1- 3 Fig. 1 Link to Examples Policy & Operational Decisions, Assumptions and Strategies Includes organizational responsibilities and structure, disposition path, future use of facility, S&S Reqs and plan, hazard elimination or mitigation, NEPA, RCRA, CERCLA, HVAC/lighting service reqs, structural integrity reqs, etc. Sect. 6.e.7.a Sect. 4.1.1 Step 1 1. Example 1

300

Project Definition Rating Index (PDRI) | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Project Definition Rating Index (PDRI) Project Definition Rating Index (PDRI) Project Definition Rating Index (PDRI) The Office of Environmental Management (EM) Project Definition Rating Index (EM-PDRI) is a modification of a commercially developed planning tool that has been tested by an EM team specifically for EM's projects. EM-PDRI Team members represent a number of EM sites, and have already used this project planning tool successfully. The EM-PDRI examines a wide range of project factors related to cost, scope, and schedule, and develops a numerical score as a measure of how well these factors are defined. It applies to all of EM's projects including Traditional/Construction; Environmental Remediation; and Facility Disposition (including Transition, Deactivation, and Decommissioning). If you have questions about the EM-PDRI, please

Note: This page contains sample records for the topic "facility disposition project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


301

Review of project definition studies of possible on-site uses of superconducting super collider assets and facilities  

SciTech Connect

This document reports on the results of a peer review and evaluation of studies made of potential uses of assets from the terminated Superconducting Super Collider (SSC) project. These project definition studies focused on nine areas of use of major assets and facilities at the SSC site near Waxahachie, Texas. The studies were undertaken as part of the effort to maximize the value of the investment made in the SSC and were supported by two sets of grants, one to the Texas National Research Laboratory Commission (TNRLC) and the second to various universities and other institutions for studies of ideas raised by a public call for expressions of interest. The Settlement Agreement, recently signed by the Department of Energy (DOE) and TNRLC, provides for a division of SSC property. As part of the goal of maximizing the value of the SSC investment, the findings contained in this report are thus addressed to officials in both the Department and TNRLC. In addition, this review had several other goals: to provide constructive feedback to those doing the studies; to judge the benefits and feasibility (including funding prospects) of the projects studied; and to help worthy projects become reality by matching projects with possible funding sources.

1994-12-01T23:59:59.000Z

302

Review of project definition studies of possible on-site uses of superconducting super collider assets and facilities. Final report  

Science Conference Proceedings (OSTI)

This document reports on the results of a peer review and evaluation of studies made of potential uses of assets from the terminated Superconducting Super Collider (SSC) project. These project definition studies focused on nine areas of use of major assets and facilities at the SSC site near Waxahachie, Texas. The studies were undertaken as part of the effort to maximize the value of the investment made in the SSC and were supported by two sets of grants, one to the Texas National Research Laboratory Commission (TNRLC) and the second to various universities and other institutions for studies of ideas raised by a public call for expressions of interest. The Settlement Agreement, recently signed by the Department of Energy (DOE) and TNRLC, provides for a division of SSC property. As part of the goal of maximizing the value of the SSC investment, the findings contained in this report are thus addressed to officials in both the Department and TNRLC. In addition, this review had several other goals: to provide constructive feedback to those doing the studies; to judge the benefits and feasibility (including funding prospects) of the projects studied; and to help worthy projects become reality by matching projects with possible funding sources.

NONE

1994-12-01T23:59:59.000Z

303

Status Review of Wildlife Mitigation at Columbia Basin Hydroelectric Projects, Oregon Facilities, Final Report.  

DOE Green Energy (OSTI)

The report presents a review and documentation of existing information on wildlife resources at Columbia River Basin hydroelectric facilities within Oregon. Effects of hydroelectric development and operation; existing agreements; and past, current and proposed wildlife mitigation, enhancement, and protection activities were considered. (ACR)

Bedrossian, Karen L.

1984-08-01T23:59:59.000Z

304

Readiness Assessment for MF-628 Drum Treatment Facility - Advanced Mixed Waste Treatment Project … 5-07  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Conduct of Operations (OP) Conduct of Operations (OP) OBJECTIVE OP.1 Resources are effectively allocated to address environmental, safety, health, and quality (ESH&Q), programmatic, and operational considerations required for commencing AR Project II activities to meet the following criteria: CRITERIA: OP.1.1. There are sufficient numbers of trained/qualified operations personnel to conduct and support the activity. OP. 1.2 There are adequate facilities and equipment available to ensure operational support is adequate for the activity. (Such support services include operations, training, maintenance, waste management, environmental protection, industrial safety and hygiene, radiological protection and health physics, emergency preparedness, fire protection, quality assurance, criticality safety, and

305

Facility Software Quality Assurance (SQA) for Captal Project Critical Decisions RM  

Energy.gov (U.S. Department of Energy (DOE))

The purpose of this Software Quality Assurance for Capital Project Critical Decision Review Module (SQA RM) is to identify, integrate, and clarify, in one EM document, the SQA performance...

306

EM Waste and Materials Disposition & Transportation | Department...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

and disposal alternatives in the 2 commercial sector Review current policies and directives Provide needed oversight EM Waste and Materials Disposition & Transportation More...

307

Fissile Materials Disposition | National Nuclear Security Administrati...  

NLE Websites -- All DOE Office Websites (Extended Search)

Materials Disposition Since the end of the Cold War, significant quantities of plutonium and highly enriched uranium have become surplus to the defense needs of both the...

308

Weapons Dismantlement and Disposition NNSS Capabilities  

Science Conference Proceedings (OSTI)

The U.S. Department of Energy (DOE) has tasked the WDD working group to disposition the large inventory of legacy classified weapon components scattered across the complex.

Pat Arnold

2011-12-01T23:59:59.000Z

309

Personal Property Disposition - Community Reuse Organizations...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Disposition of Excess Personal Property BACKGROUND AND PURPOSE CROs have been operating asset conversion and personal property transfer programs since shortly after the passage of...

310

C.2 analysis of the environmental effects of the Nuclear Facilities Modernization project  

Science Conference Proceedings (OSTI)

This analysis indicates that the potential impacts associated with the current/projected Mound tritium operations are adequately bounded by the existing environmental impacts analyzed in the FEIS. It also indicates that the incremental impacts of the NFM project will make a positive contribution to the overall impact of current/projected tritium operations. Except for minor and normal temporary conditions during the construction and demolition phases, the NFM project would measurably reduce the likelihood of adverse consequences to the environment. Relocation of the PE/PD laboratory operations from the SW/R Tritium Complex to the T Building will place these operations in a safer, state-of-the-art glovebox systems. Through the utilization of modern laboratory equipment and enhanced containment, the project will reduce the quantity of routine airborne tritium releases and volume of solid tritiated wastes resulting from routine PE/PD laboratory operations. The increased reliance placed on engineered safety aspects and stronger mitigative measures by the project will also reduce the risk associated with these operations by reducing both the probability and consequences of unusual occurrences involving uncontrolled tritium releases.

NONE

1991-04-01T23:59:59.000Z

311

Used Fuel Disposition R&D Documents | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Used Fuel Disposition Used Fuel Disposition Research & Development » Used Fuel Disposition R&D Documents Used Fuel Disposition R&D Documents December 4, 2013 Preliminary Report on Dual-Purpose Canister Disposal Alternatives (FY13) This report documents the first phase of a multi-year project to understand the technical feasibility and logistical implications of direct disposal of spent nuclear fuel in existing dual-purpose canisters (DPCs) and other types of storage casks. October 25, 2013 Deep Borehole Disposal Research: Demonstration Site Selection Guidelines, Borehole Seals Design, and RD&D Needs Deep borehole disposal is one alternative for the disposal of spent nuclear fuel and other radioactive waste forms; identifying a site or areas with favorable geological, hydrogeological, and geochemical conditions is one of

312

Preclosure radiological safety analysis for the exploratory shaft facilities; Yucca Mountain Site Characterization Project  

SciTech Connect

This study assesses which structures, systems, and components of the exploratory shaft facility (ESF) are important to safety when the ESF is converted to become part of the operating waste repository. The assessment follows the methodology required by DOE Procedure AP-6.10Q. Failures of the converted ESF during the preclosure period have been evaluated, along with other underground accidents, to determine the potential offsite radiation doses and associated probabilities. The assessment indicates that failures of the ESF will not result in radiation doses greater than 0.5 rem at the nearest unrestricted area boundary. Furthermore, credible accidents in other underground facilities will not result in radiation doses larger than 0.5 rem, even if any structure, system, or component of the converted ESF fails at the same time. Therefore, no structure, system, or component of the converted ESF is important to safety.

Ma, C.W.; Miller, D.D.; Jardine, L.J. [Bechtel National, Inc., San Francisco, CA (United States)

1992-06-01T23:59:59.000Z

313

Supplemental design requirements document, Multifunction Waste Tank Facility, Project W-236A. Revision 1  

SciTech Connect

The Multi-Function Waste Tank Facility (MWTF) consists of four, nominal 1 million gallon, underground double-shell tanks, located in the 200-East area, and two tanks of the same capacity in the 200-West area. MWTF will provide environmentally safe storage capacity for wastes generated during remediation/retrieval activities of existing waste storage tanks. This document delineates in detail the information to be used for effective implementation of the Functional Design Criteria requirements.

Groth, B.D.

1995-01-11T23:59:59.000Z

314

Conceptual design statement of work for the immobilized low-activity waste interim storage facility project  

SciTech Connect

The Immobilized Low-Activity Waste Interim Storage subproject will provide storage capacity for immobilized low-activity waste product sold to the U.S. Department of Energy by the privatization contractor. This statement of work describes the work scope (encompassing definition of new installations and retrofit modifications to four existing grout vaults), to be performed by the Architect-Engineer, in preparation of a conceptual design for the Immobilized Low-Activity Waste Interim Storage Facility.

Carlson, T.A., Fluor Daniel Hanford

1997-02-06T23:59:59.000Z

315

Supplement to the Surplus Plutonium Disposition Draft Environmental Impact Statement  

Science Conference Proceedings (OSTI)

On May 22, 1997, DOE published a Notice of Intent in the Federal Register (62 Federal Register 28009) announcing its decision to prepare an environmental impact statement (EIS) that would tier from the analysis and decisions reached in connection with the ''Storage and Disposition of Weapons-Usable Fissile Materials Final Programmatic EIS (Storage and Disposition PEIS)''. ''The Surplus Plutonium Disposition Draft Environmental Impact Statement'' (SPD Draft EIS) (DOWEIS-0283-D) was prepared in accordance with NEPA and issued in July 1998. It identified the potential environmental impacts of reasonable alternatives for the proposed siting, construction, and operation of three facilities for plutonium disposition. These three facilities would accomplish pit disassembly and conversion, immobilization, and MOX fuel fabrication. For the alternatives that included MOX fuel fabrication, the draft also described the potential environmental impacts of using from three to eight commercial nuclear reactors to irradiate MOX fuel. The potential impacts were based on a generic reactor analysis that used actual reactor data and a range of potential site conditions. In May 1998, DCE initiated a procurement process to obtain MOX fuel fabrication and reactor irradiation services. The request for proposals defined limited activities that may be performed prior to issuance of the SPD EIS Record of Decision (ROD) including non-site-specific work associated with the development of the initial design for the MOX fuel fabrication facility, and plans (paper studies) for outreach, long lead-time procurements, regulatory management, facility quality assurance, safeguards, security, fuel qualification, and deactivation. No construction on the proposed MOX facility would begin before an SPD EIS ROD is issued. In March 1999, DOE awarded a contract to Duke Engineering & Services; COGEMA, Inc.; and Stone & Webster (known as DCS) to provide the requested services. The procurement process included the environmental review specified in DOE's NEPA regulations in 10 CFR 1021.216. The six reactors selected are Catawba Nuclear Station Units 1 and 2 in South Carolina McGuire Nuclear Station Units 1 and 2 in North Carolina, and North Anna Power Station Units 1 and 2 in Virginia. The Supplement describes the potential environmental impacts of using MOX fuel in these six specific reactors named in the DCS proposal as well as other program changes made since the SPD Draft EIS was published.

N /A

1999-05-14T23:59:59.000Z

316

Cost Estimating for Decommissioning of a Plutonium Facility--Lessons Learned From The Rocky Flats Building 771 Project  

Science Conference Proceedings (OSTI)

The Rocky Flats Closure Site is implementing an aggressive approach in an attempt to complete Site closure by 2006. The replanning effort to meet this goal required that the life-cycle decommissioning effort for the Site and for the major individual facilities be reexamined in detail. As part of the overall effort, the cost estimate for the Building 771 decommissioning project was revised to incorporate both actual cost data from a recently-completed similar project and detailed planning for all activities. This paper provides a brief overview of the replanning process and the original estimate, and then discusses the modifications to that estimate to reflect new data, methods, and planning rigor. It provides the new work breakdown structure and discusses the reasons for the final arrangement chosen. It follows with the process used to assign scope, cost, and schedule elements within the new structure, and development of the new code of accounts. Finally, it describes the project control methodology used to track the project, and provides lessons learned on cost tracking in the decommissioning environment.

Stevens, J. L.; Titus, R.; Sanford, P. C.

2002-02-26T23:59:59.000Z

317

Sample Results from the Interim Salt Disposition Program Macrobatch 6 Tank 21H Qualification Samples  

SciTech Connect

Savannah River National Laboratory (SRNL) analyzed samples from Tank 21H in support of qualification of Macrobatch (Salt Batch) 6 for the Interim Salt Disposition Project (ISDP). This document reports partial results of the analyses of samples of Tank 21H. No issues with the projected Salt Batch 6 strategy are identified.

Peters, T. B.; Fink, S. D.

2012-12-11T23:59:59.000Z

318

Sample Results From The Interim Salt Disposition Program Macrobatch 6 Tank 21H Qualification Samples  

Science Conference Proceedings (OSTI)

Savannah River National Laboratory (SRNL) analyzed samples from Tank 21H in support of qualification of Macrobatch (Salt Batch) 6 for the Interim Salt Disposition Project (ISDP). This document reports partial results of the analyses of samples of Tank 21H. No issues with the projected Salt Batch 6 strategy are identified.

Peters, T. B.; Fink, S. D.

2012-12-20T23:59:59.000Z

319

Request for Reduction/Waiver of F&A Principal Investigators /Project Directors must budget Facilities and Administrative (F&A) costs in all grant, contract, and  

E-Print Network (OSTI)

Allowed By Sponsor (if known) Project Budget: Reason for Reduction/Waiver Request: Direct Costs (MTDC BaseRequest for Reduction/Waiver of F&A Principal Investigators /Project Directors must budget Facilities and Administrative (F&A) costs in all grant, contract, and cooperative agreement proposals using

Guenther, Frank

320

U.S. and Russia Sign Plutonium Disposition Agreement | National...  

National Nuclear Security Administration (NNSA)

Agreement U.S. and Russia Sign Plutonium Disposition Agreement September 01, 2000 Washington, DC U.S. and Russia Sign Plutonium Disposition Agreement After two years of...

Note: This page contains sample records for the topic "facility disposition project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


321

REQUEST FOR RECORDS DISPOSITION AUTHORITY | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

This disposition requests describe records of the History Division under the Office Executive Secretariat at the Department of Energy Headquarters REQUEST FOR RECORDS DISPOSITION...

322

Request For Records Disposition Authority | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Authority Request For Records Disposition Authority Office of Naval Petroleum and Shale Oil Reserves Request For Records Disposition Authority More Documents & Publications...

323

Request For Records Disposition Authority | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Naval Petroleum and Oil Shale Reserves Request For Records Disposition Authority More Documents & Publications Request For Records Disposition Authority Request For Records...

324

Request For Records Disposition Authority-Nuclear Weapons | Department...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

For Records Disposition Authority-Nuclear Weapons Request For Records Disposition Authority-Nuclear Weapons This document identifies the nuclear weapon records generated by the...

325

PROCEDURE FOR PREPARING RECORDS INVENTORY AND DISPOSITION SCHEDULES...  

NLE Websites -- All DOE Office Websites (Extended Search)

PREPARING RECORDS INVENTORY AND DISPOSITION SCHEDULES (RIDS) PROCEDURE FOR PREPARING RECORDS INVENTORY AND DISPOSITION SCHEDULES (RIDS) This document lists the procedures for...

326

Topic Index to the DOE Administrative Records Disposition Schedules...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Topic Index to the DOE Administrative Records Disposition Schedules Topic Index to the DOE Administrative Records Disposition Schedules Topic Index to the DOE Administrative...

327

EM Makes Significant Progress on Dispositioning Transuranic Waste...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Makes Significant Progress on Dispositioning Transuranic Waste at Idaho Site EM Makes Significant Progress on Dispositioning Transuranic Waste at Idaho Site December 24, 2013 -...

328

DOE Chooses Idaho Treatment Group, LLC to Disposition Waste at the Advanced  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Chooses Idaho Treatment Group, LLC to Disposition Waste at the Chooses Idaho Treatment Group, LLC to Disposition Waste at the Advanced Mixed Waste Treatment Project: Contract will continue cleanup and waste operations at the Idaho Site DOE Chooses Idaho Treatment Group, LLC to Disposition Waste at the Advanced Mixed Waste Treatment Project: Contract will continue cleanup and waste operations at the Idaho Site May 27, 2011 - 12:00pm Addthis Media Contact Brad Bugger (208) 526-0833 Idaho Falls - In order to further meet the U.S. Department of Energy's commitments to the citizens of the state of Idaho, the DOE today announced that it has selected Idaho Treatment Group, LLC (ITG) to perform waste processing at the Advanced Mixed Waste Treatment Project (AMWTP) at DOE's Idaho Site near Idaho Falls. The contract is estimated at approximately

329

Advanced Instrumentation, Information and Control (II&C) Research and Development Facility Buildout and Project Execution of LWRS II&C Pilot Projects 1 and 3  

SciTech Connect

The U.S. Department of Energy (DOE) is sponsoring research, development, and deployment on light water reactor sustainability (LWRS), in which the Idaho National Laboratory (INL) is working closely with nuclear utilities to develop technologies and solutions to help ensure the safe operational life extension of current reactors. As technologies are introduced that change the operation of the plant, the LWRS pilot projects can help identify their best-advanced uses and help demonstrate the safety of these technologies. In early testing of operator performance given these emerging technologies will ensure the safety and usability of systems prior to large-scale deployment and costly verification and validation at the plant. The aim of these collaborations, demonstrations, and approaches are intended to lessen the inertia that sustains the current status quo of today's II&C systems technology, and to motivate transformational change and a shift in strategy to a long-term approach to II&C modernization that is more sustainable. Research being conducted under Pilot Project 1 regards understanding the conditions and behaviors that can be modified, either through process improvements and/or technology deployment, to improve the overall safety and efficiency of outage control at nuclear facilities. The key component of the research in this pilot project is accessing the delivery of information that will allow researchers to simulate the control room, outage control center (OCC) information, and plant status data. The simulation also allows researchers to identify areas of opportunity where plant operating status and outage activities can be analyzed to increase overall plant efficiency. For Pilot Project 3 the desire is to demonstrate the ability of technology deployment and the subsequent impact on maximizing the 'Collective Situational Awareness' of the various stakeholders in a commercial nuclear power plant. Specifically, the desire is to show positive results in plant status control, information management, knowledge management, and 'Real-Time-Truth' as it relates to the current plant conditions. The following report includes two attachments; each attachment represents Pilot Project 1 and 3. The two attachments also provide a report on two distinct milestones that were completed and are described below: M3L11IN06030307 - Complete initiation of two pilot projects Complete initiation of pilot projects on real-time configuration management and control to overcome limitations with existing permanent instrumentation and real-time awareness of plant configurations; two candidate projects that consider low-cost wireless technology for in situ configuration monitoring and candidate technologies and an information architecture for outage management and control will be initiated with utilities. M3L11IN06030309 - Complete data collection, R&D plans, and agreements needed to conduct the two pilot projects Complete data collection conducted at pilot project utilities to support real-time configuration management and outage control center pilot studies conducted; R&D plan for pilot projects produced and needed agreements established to support R&D activities.

Ronald Farris; Johanna Oxstrand; Gregory Weatherby

2011-09-01T23:59:59.000Z

330

Evaluation of Calcine Disposition Path Forward  

SciTech Connect

This document describes an evaluation of the baseline and two alternative disposition paths for the final disposition of the calcine wastes stored at the Idaho Nuclear Technology and Engineering Center at the Idaho National Engineering and Environmental Laboratory. The pathways are evaluated against a prescribed set of criteria and a recommendation is made for the path forward.

Birrer, S.A.; Heiser, M.B.

2003-02-26T23:59:59.000Z

331

Evaluation of Calcine Disposition - Path Forward  

SciTech Connect

This document describes an evaluation of the baseline and two alternative disposition paths for the final disposition of the calcine wastes stored at the Idaho Nuclear Technology and Engineering Center at the Idaho National Engineering and Environmental Laboratory. The pathways are evaluated against a prescribed set of criteria and a recommendation is made for the path forward.

Steve Birrer

2003-02-01T23:59:59.000Z

332

DEVELOPING AN INTEGRATED NATIONAL STRATEGY FOR THE DISPOSITION OF SPENT NUCLEAR FUEL  

Science Conference Proceedings (OSTI)

This paper summarizes the Department of Energy's (DOE's) current efforts to strengthen its activities for the management and disposition of DOE-owned spent nuclear fuel (SNF). In August 2002 an integrated, ''corporate project'' was initiated by the Office of Environmental Management (EM) to develop a fully integrated strategy for disposition of the approximately {approx}250,000 DOE SNF assemblies currently managed by EM. Through the course of preliminary design, the focus of this project rapidly evolved to become DOE-wide. It is supported by all DOE organizations involved in SNF management, and represents a marked change in the way DOE conducts its business. This paper provides an overview of the Corporate Project for Integrated/Risk-Driven Disposition of SNF (Corporate SNF Project), including a description of its purpose, scope and deliverables. It also summarizes the results of the integrated project team's (IPT's) conceptual design efforts, including the identification of project/system requirements and alternatives. Finally, this paper highlights the schedule of the corporate project, and its progress towards development of a DOE corporate strategy for SNF disposition.

Gelles, C.M.

2003-02-27T23:59:59.000Z

333

SLUDGE TREATMENT PROJECT KOP CONCEPTUAL DESIGN CONTROL DECISION REPORT  

SciTech Connect

This control decision addresses the Knock-Out Pot (KOP) Disposition KOP Processing System (KPS) conceptual design. The KPS functions to (1) retrieve KOP material from canisters, (2) remove particles less than 600 {micro}m in size and low density materials from the KOP material, (3) load the KOP material into Multi-Canister Overpack (MCO) baskets, and (4) stage the MCO baskets for subsequent loading into MCOs. Hazard and accident analyses of the KPS conceptual design have been performed to incorporate safety into the design process. The hazard analysis is documented in PRC-STP-00098, Knock-Out Pot Disposition Project Conceptual Design Hazard Analysis. The accident analysis is documented in PRC-STP-CN-N-00167, Knock-Out Pot Disposition Sub-Project Canister Over Lift Accident Analysis. Based on the results of these analyses, and analyses performed in support of MCO transportation and MCO processing and storage activities at the Cold Vacuum Drying Facility (CVDF) and Canister Storage Building (CSB), control decision meetings were held to determine the controls required to protect onsite and offsite receptors and facility workers. At the conceptual design stage, these controls are primarily defined by their safety functions. Safety significant structures, systems, and components (SSCs) that could provide the identified safety functions have been selected for the conceptual design. It is anticipated that some safety SSCs identified herein will be reclassified based on hazard and accident analyses performed in support of preliminary and detailed design.

CARRO CA

2010-03-09T23:59:59.000Z

334

REQUEST FOR RECORDS DISPOSITION AUTHORITY  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

1nstrlrcrlons on reverts) 1nstrlrcrlons on reverts) ' 0 NATIONAL ARCMVES and RECORDS AD~~INISTRAT~ON (NIR) WASHINGTON, DC 20408 1. FROM (Agency or estabi~shment) Department of Energy Washington, DC 20585 . '2. MAJOR SUBDIVISION fn lccordance w i l h the provirions o f 4 4 DOE~NEVADA OPERATIONS OFFICE U.S.C. 3 3 0 3 r the disposition r e q u c ~ t , including rmtndments, i s approvtd n c t p l 3. MINOR SUBOlVlStON lor ilemr that mky be mrrkcd 'dir wition not approved' o r withdmwn' in c&mn lo. '4. NAME O F PERSON WITH WHOM TO CONFER 5. TELEPHONE Mary Ann Wallace -301 903 4353 6. AGENCY CERTIFICATION I hereby certify that I am authorized to a d for this to th#disposit-ion of its records and that the records roposed for disposal on the P now needed for the business of this agency or wil not be needed after the concurrence f

335

REQUEST FOR RECORDS DISPOSITION AUTHORITY  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

m m - REQUEST FOR RECORDS DISPOSITION AUTHORITY (See Instructions on reverse) GENERAL SERVICES ADMINISTRATION N A T I O N A L ARCHIVES AND RECORDS SERVICE, WASHINGTON, DC 20408 1. F R O M ( A g e n c y o r e s t a b l i s h m e n t ) jepartment of Energy 2. MAJOR S U B D I V I S I O N Oak Ridse Operations Office 3. M I N O R S U B D I V I S I O N 4 . N A M E O F PERSON W I T H W H O M T O C O N F E R ( 5 . T E L E P H O N E E X T . L E A V E B L A N K - JOB N O . d/-d33P PO- ZJ - - - - p p D A T E R E C E I V E D p - NOTIFICATION TO AGENCY In accordance with the provisions of 44 U.S.C. 3303a the disposal request, including amendments, is approved except for items that may be marked "disposition not approved" or "withdrawn" in column 10. If no records are proposed for disposal, the signature of the Archivist is not required. - DATE ARCHIVIST

336

I REQUEST FOR RECORDS DISPOSITION AUTHORITY  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

REQUEST FOR RECORDS DISPOSITION AUTHORITY REQUEST FOR RECORDS DISPOSITION AUTHORITY LEAVE BL ...A (NARA use only1 JOB NUMBER TO: NATIONAL ARCHIVES & RECORDS ADMINISTRATION In accordance with the provisions of 44 U.S.C. 3303a, the Office of the Chief Information Officer disposition request, including amendments, is approved except for items that may be marked "disposition not approved" or "withdrawn" in column 10. Records Management Division N1-434-02-2 Date received 860 1 ADELPHI ROAD COLLEGE PARK, MD 20740-600 1 1. FROM (Agency or establishment) Department of Energy , ( / I 4 30 -A&&& NOTIFICATION TO AGENCY 6. AGENCY CERTIFICATION I hereby certify that I am authorized to act for this agency in matters pertaining to the disposition of its records and that the

337

Nuclear Materials Disposition | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Nuclear Materials Disposition Nuclear Materials Disposition Nuclear Materials Disposition Nuclear Materials Disposition In fulfilling its mission, EM frequently manages and completes disposition of surplus nuclear materials and spent nuclear fuel. These are not waste. They are nuclear materials no longer needed for national security or other purposes, including spent nuclear fuel, special nuclear materials (as defined by the Atomic Energy Act) and other Nuclear Materials. Spent Nuclear Fuel Spent nuclear fuel (SNF) is fuel that has been withdrawn from a nuclear reactor following irradiation, the constituent elements of which have not been separated by reprocessing. SNF may include: (1) intact, non-defective fuel assemblies or fuel rods; (2) failed fuel assemblies or fuel rods; (3) segments of fuel rods or pieces of fuel derived from spent fuel rods; and

338

Lessons Learned from the 200 West Pump and Treatment Facility Construction Project at the US DOE Hanford Site - A Leadership for Energy and Environmental Design (LEED) Gold-Certified Facility  

SciTech Connect

CH2M Hill Plateau Remediation Company (CHPRC) designed, constructed, commissioned, and began operation of the largest groundwater pump and treatment facility in the U.S. Department of Energys (DOE) nationwide complex. This one-of-a-kind groundwater pump and treatment facility, located at the Hanford Nuclear Reservation Site (Hanford Site) in Washington State, was built to an accelerated schedule with American Recovery and Reinvestment Act (ARRA) funds. There were many contractual, technical, configuration management, quality, safety, and Leadership in Energy and Environmental Design (LEED) challenges associated with the design, procurement, construction, and commissioning of this $95 million, 52,000 ft groundwater pump and treatment facility to meet DOEs mission objective of treating contaminated groundwater at the Hanford Site with a new facility by June 28, 2012. The project teams successful integration of the projects core values and green energy technology throughout design, procurement, construction, and start-up of this complex, first-of-its-kind Bio Process facility resulted in successful achievement of DOEs mission objective, as well as attainment of LEED GOLD certification, which makes this Bio Process facility the first non-administrative building in the DOE Office of Environmental Management complex to earn such an award.

Dorr, Kent A.; Ostrom, Michael J.; Freeman-Pollard, Jhivaun R.

2013-01-11T23:59:59.000Z

339

RH-LLW Disposal Facility Project CD-2/3 to Design/Build Proposal Reconciliation Report  

SciTech Connect

A reconciliation plan was developed and implemented to address potential gaps and responses to gaps between the design/build vendor proposals and the Critical Decision-2/3 approval request package for the Remote-Handled Low Level Waste Disposal Facility Project. The plan and results of the plan implementation included development of a reconciliation team comprised of subject matter experts from Battelle Energy Alliance and the Department of Energy Idaho Operations Office, identification of reconciliation questions, reconciliation by the team, identification of unresolved/remaining issues, and identification of follow-up actions and subsequent approvals of responses. The plan addressed the potential for gaps to exist in the following areas: Department of Energy Order 435.1, Radioactive Waste Management, requirements, including the performance assessment, composite analysis, monitoring plan, performance assessment/composite analysis maintenance plan, and closure plan Environmental assessment supporting the National Environmental Policy Act Nuclear safety Safeguards and security Emplacement operations Requirements for commissioning General project implementation. The reconciliation plan and results of the plan implementation are provided in a business-sensitive project file. This report provides the reconciliation plan and non-business sensitive summary responses to identified gaps.

Annette L. Schafer

2012-06-01T23:59:59.000Z

340

Project Management Plan Examples 1 - 80 | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Project Management Plan Examples 1 - 80 Project Management Plan Examples 1 - 80 Project Management Plan Examples 1 - 80 The following material has been extracted from several project management plans. The order in which it is presented is arbitrary. The descriptions below should be used to navigate to the subject of interest. Policy & Operational Decisions, Assumptions and Strategies - Examples 1 & 2 - Includes organizational responsibilities and structure, disposition path, future use of facility, S&S Reqs and plan, hazard elimination or mitigation, NEPA, RCRA, CERCLA, HVAC/lighting service reqs, structural integrity reqs, etc. Facility End State Decisions - Examples 3, 4 & 5 - Includes expected conditions at completion of the deactivation, DOE mission use, extended S&M, decommissioned and/or dismantled, etc.

Note: This page contains sample records for the topic "facility disposition project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


341

Mixed and low-level waste treatment facility project. Volume 3, Waste treatment technologies (Draft)  

SciTech Connect

The technology information provided in this report is only the first step toward the identification and selection of process systems that may be recommended for a proposed mixed and low-level waste treatment facility. More specific information on each technology will be required to conduct the system and equipment tradeoff studies that will follow these preengineering studies. For example, capacity, maintainability, reliability, cost, applicability to specific waste streams, and technology availability must be further defined. This report does not currently contain all needed information; however, all major technologies considered to be potentially applicable to the treatment of mixed and low-level waste are identified and described herein. Future reports will seek to improve the depth of information on technologies.

1992-04-01T23:59:59.000Z

342

The North West Shelf Project; Australian LNG facility ahead of schedule  

Science Conference Proceedings (OSTI)

The LNG complex, one of the most important natural resource developments ever undertaken in Australia, will provide a major new export industry for the country. It is based on vast hydrocarbon resources, primarily natural gas, discovered in the early 1970s on the North West Continental Shelf. The project consists of the North Rankin A gas drilling and production platform, a 70-mile subsea pipeline carrying the gas to shore, a domestic gas plant and three LNG trains. A second drilling and production platform, to be located in the Goodwyn field about 23 km from the North Rankin A platform, is now in the development stages. The complex is detailed in this paper.

Not Available

1989-10-01T23:59:59.000Z

343

General Electric Company Hanford Works, Project C-431-A Production Facility-Section A, design report  

SciTech Connect

The 100-C project is to be located adjacent to the present 100-B Area. It is planned to build an addition to the present 181-B river pump house using the same elevations for pump settings, intakes, and floors as for the present pump house, thus maintaining the same suction conditions and flood protection as B Area. The 105 Building will be located on higher ground than B Area and therefore, protection against possible flood damage is assured. This report is divided into the following sections: (1) general description of project; (2) addition to existing river pump house; (3) raw water lines from 181-B addition to 183-C lead house; (4) the 183-C filter plant; (5) 190-C process pump house; (6) power house addition; (7) high tanks; (8) retention basins; (9) outside streamlines; (10) primary substation; (11) outside underground lines; (12) outside electric lines; (13) roads, railroads, walks, fences; (14) structural design of all buildings; and (15) architectural design of all buildings.

Colburn, R.T.

1951-03-29T23:59:59.000Z

344

Evaluation of the effects of underground water usage and spillage in the Exploratory Studies Facility; Yucca Mountain Site Characterization Project  

SciTech Connect

The Yucca Mountain Site Characterization Project is studying Yucca Mountain in southwestern Nevada as a potential site for a high-level radioactive waste repository. Analyses reported herein were performed to support the design of site characterization activities so that these activities will have a minimal impact on the ability of the site to isolate waste and a minimal impact on underground tests performed as part of the characterization process. These analyses examine the effect of water to be used in the underground construction and testing activities for the Exploratory Studies Facility on in situ conditions. Underground activities and events where water will be used include construction, expected but unplanned spills, and fire protection. The models used predict that, if the current requirements in the Exploratory Studies Facility Design Requirements are observed, water that is imbibed into the tunnel wall rock in the Topopah Springs welded tuff can be removed over the preclosure time period by routine or corrective ventilation, and also that water imbibed into the Paintbrush Tuff nonwelded tuff will not reach the potential waste storage area.

Dunn, E.; Sobolik, S.R.

1993-12-01T23:59:59.000Z

345

Solar Total Energy Test Facility Project. Semiannual report, October 1976--March 1977  

DOE Green Energy (OSTI)

The Solar Total Energy System will operate as follows: A heat transfer fluid (Therminol 66) is heated in the receiver tubes of the solar collectors by reflected and focused solar radiation. This fluid is pumped to the high-temperature storage subsystem. Fluid is extracted from this storage on a demand basis and pumped to the heat exchanger which produces superheated toluene vapor to power the turbine/generator. The boiler can also be operated from a fossil fuel-fired heater to insure continuity of operation during extended cloudy periods. Turbine condenser coolant is pumped to the low-temperature storage tank and becomes the energy source for heating and air-conditioning components of the system. Progress is reported on the design, fabrication, installation, and checkout of the first 200 m/sup 2/ collector field quadrant, a high-temperature stratified storage tank, a 32-kW turbine/generator and Therminol-to-toluene heat exchanger, an instrumentation and control subsystem, a cooling tower, the turbine and control building, and all necessary pumps and fluid loops to interconnect these subsystems. Also, experience with operating the facility in accordance with a detailed test plan to provide performance data on all subsystems and to accumulate operating and maintenance experience which can provide a basis for the design of large-scale experimental plants and future solar energy systems is described. (WHK)

Petterson, B. Jr. (ed.)

1977-08-01T23:59:59.000Z

346

CONSTRUCTION OF KEY CLEANUP PROJECT GAINS GOOD GROUND AT SRS | Department  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

CONSTRUCTION OF KEY CLEANUP PROJECT GAINS GOOD GROUND AT SRS CONSTRUCTION OF KEY CLEANUP PROJECT GAINS GOOD GROUND AT SRS CONSTRUCTION OF KEY CLEANUP PROJECT GAINS GOOD GROUND AT SRS June 1, 2010 - 12:00pm Addthis CONSTRUCTION OF KEY CLEANUP PROJECT GAINS GOOD GROUND AT SRS Aiken, SC - Construction of a key cleanup facility at the Savannah River Site (SRS) is gaining some serious ground given the remarkable building progress since Fall 2009. Construction and operation of the Salt Waste Processing Facility (SWPF) is among the U.S. Department of Energy's (DOE) highest cleanup priorities. When operational, SWPF will treat millions of gallons of salt waste currently stored in 49 underground tanks at SRS by removing radioactive constituents for vitrification at the nearby Defense Waste Processing Facility. Disposition of the salt waste inventory is a

347

CONSTRUCTION OF KEY CLEANUP PROJECT GAINS GOOD GROUND AT SRS | Department  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

CONSTRUCTION OF KEY CLEANUP PROJECT GAINS GOOD GROUND AT SRS CONSTRUCTION OF KEY CLEANUP PROJECT GAINS GOOD GROUND AT SRS CONSTRUCTION OF KEY CLEANUP PROJECT GAINS GOOD GROUND AT SRS June 1, 2010 - 12:00pm Addthis CONSTRUCTION OF KEY CLEANUP PROJECT GAINS GOOD GROUND AT SRS Aiken, SC - Construction of a key cleanup facility at the Savannah River Site (SRS) is gaining some serious ground given the remarkable building progress since Fall 2009. Construction and operation of the Salt Waste Processing Facility (SWPF) is among the U.S. Department of Energy's (DOE) highest cleanup priorities. When operational, SWPF will treat millions of gallons of salt waste currently stored in 49 underground tanks at SRS by removing radioactive constituents for vitrification at the nearby Defense Waste Processing Facility. Disposition of the salt waste inventory is a

348

Used Fuel Disposition Campaign Disposal  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Campaign Disposal Research and Development Roadmap Prepared for U.S. Department of Energy Used Fuel Disposition Campaign September 2012 FCR&D-USED-2011-000065 REV 1 DISCLAIMER This information was prepared as an account of work sponsored by an agency of the U.S. Government. Neither the U.S. Government nor any agency thereof, nor any of their employees, makes any warranty, expressed or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness, of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights. References herein to any specific commercial product, process, or service by trade name, trade mark, manufacturer, or

349

MSG MONTICELLO PROJECTS FEDERAL FACILITY AGREEMENT REPORT March!April2005  

Office of Legacy Management (LM)

March!April2005 March!April2005 Report Period: March 1 - April30, 2005 DOE Project Coordinator: Art Kleinrath HIGHLIGHTS Semi-annual ground water and surface water samples were collected during the week of April4, in accordance with the Monticello Mill Tailings Site Operational Unit III Post- Record of Decision Monitoring Plan. DOE initiated biomonitoring at the wetland areas on the former millsite and down-gradient at the sediment pond as required by the Record of Decision for the Monticello Mill Tailings (USDOE) Site Operable Unit Ill, Swface and Ground Water, Monticello, Utah (May 2004). MRAP DOE submitted the final 2004 Annual Inspection of the Monticello Mill Tailings (USDOE) and Monticello Radioactively Contaminated Properties Sites to the Environmental Protection

350

EIS-0283: Surplus Plutonium Disposition Environmental Impact Statement  

Energy.gov (U.S. Department of Energy (DOE))

This EIS analyzes the potential environmental impacts associated with alternatives for the disposition of surplus plutonium.

351

Waste Disposition Update by Christine Gelles  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Waste Disposition Update Waste Disposition Update Christine Gelles Associate Deputy Assistant Secretary for Waste Management (EM-30) EM SSAB Chairs Meeting Washington, DC 2 October 2012 www.em.doe.gov 2 o Waste Stream Highlights o DOE Transportation Update o Greater Than Class C (GTCC) Low Level Waste Environmental Impact Statement o Blue Ribbon Commission on America's Nuclear Future o Nuclear Regulatory Commission's LLW Regulatory Initiatives Discussion Topics www.em.doe.gov 3 Waste Stream Highlights www.em.doe.gov 4 o Within current budget outlook, it is especially critical that EM ensures safe, reliable and cost effective disposition paths exist. o The program's refocused organization and the detailed

352

Barriers and Issues Related to Achieving Final Disposition of Depleted Uranium  

Science Conference Proceedings (OSTI)

Approximately 750,000 metric tons (MT) of surplus depleted uranium (DU) in various chemical forms are stored at several Department of Energy (DOE) sites throughout the United States. Most of the DU is in the form of DU hexafluoride (DUF6) that resulted from uranium enrichment operations over the last several decades. DOE plans to convert the DUF6 to ''a more stable form'' that could be any one or combination of DU tetrafluoride (DUF4 or green salt), DU oxide (DUO3, DUO2, or DU3O8), or metal depending on the final disposition chosen for any given quantity. Barriers to final disposition of this material have existed historically and some continue today. Currently, the barriers are more related to finding uses for this material versus disposing as waste. Even though actions are beginning to convert the DUF6, ''final'' disposition of the converted material has yet to be decided. Unless beneficial uses can be implemented, DOE plans to dispose of this material as waste. This expresses the main barrier to DU disposition; DOE's strategy is to dispose unless uses can be found while the strategy should be only dispose as a last resort and make every effort to find uses. To date, only minimal research programs are underway to attempt to develop non-fuel uses for this material. Other issues requiring resolution before these inventories can reach final disposition (uses or disposal) include characterization, disposal of large quantities, storage (current and future), and treatment options. Until final disposition is accomplished, these inventories must be managed in a safe and environmentally sound manner; however, this is becoming more difficult as materials and facilities age. The most noteworthy final disposition technical issues include the development of reuse and treatment options.

Gillas, D. L.; Chambers, B. K.

2002-02-26T23:59:59.000Z

353

EIS-0283-S1: Supplement to the Surplus Plutonium Disposition Environmental  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

3-S1: Supplement to the Surplus Plutonium Disposition 3-S1: Supplement to the Surplus Plutonium Disposition Environmental Impact Statement EIS-0283-S1: Supplement to the Surplus Plutonium Disposition Environmental Impact Statement SUMMARY The Supplement evaluates the potential environmental impacts of using MOX fuel in these six specific reactors named in the DCS proposal as well as other program changes made since the SPD Draft EIS was published. PUBLIC COMMENT OPPORTUNITIES None available at this time. DOCUMENTS AVAILABLE FOR DOWNLOAD November 5, 1999 EIS-0236-S1: DOE Notice of Availability of the Draft Environmental Impact Statement National Ignition Facility Draft Environmental Impact Statement to the Stockpile Stewardship and Management November 5, 1999 EIS-0236-S1: Notice of Availability for the Draft Supplemental Programmatic

354

Disposition of Unirradiated Sodium Bonded EBR-II Driver Fuel Elements and HEU Scrap: Work Performed for FY 2007  

SciTech Connect

Specific surplus high enriched uranium (HEU) materials at the Idaho National Laboratory (INL) Materials and Fuels Complex (MFC) will be transferred to a designated off-site receiving facility. The DOE High Enriched Uranium Disposition Program Office (HDPO) will determine which materials, if any, will be prepared and transferred to an off-site facility for processing and eventual fabrication of fuel for nuclear reactors. These surplus HEU materials include approximately 7200 kg unirradiated sodium-bonded EBR-II driver fuel elements, and nearly 800 kg of HEU casting scrap from the process which formed various sodium-bonded fuels (including the EBR-II driver elements). Before the driver fuel can be packaged for shipment, the fuel elements will require removal of the sodium bond. The HEU scrap will also require repackaging in preparation for off-site transport. Preliminary work on this task was authorized by BWXT Y-12 on Nov 6, 2006 and performed in three areas: Facility Modifications Safety Documentation Project Management

Karen A Moore

2007-04-01T23:59:59.000Z

355

Transition projects FY 1995 multi-year program/fiscal year work plan WBS 1.3.1. and 7.1  

Science Conference Proceedings (OSTI)

The primary Transition Projects mission is to deactivate facilities on the Hanford site, in preparation for decontamination and decommissioning, and secondarily to provide safe and secure storage of special nuclear materials, nuclear materials, and nuclear fuel. Transition projects will protect the health and safety of the public and of workers, protect the environment, and provide beneficial use of the facilities and other resources. Goals include the following: Achieve deactivation of facilities for transfer to the Hanford Surplus Facility Program, suing PUREX plant deactivation as a model; Achieve excellence in the conduct of operations and maintenance of nuclear facilities in support of the Hanford Site Mission; manage nuclear materials in a safe and secure condition; treat nuclear materials as necessary and store onsite in long-term interim safe storage awaiting a final disposition decision. Description of the program and projects is included.

Not Available

1994-09-01T23:59:59.000Z

356

Draft Environmental Assessment on the Remote-handled Waste Disposition  

NLE Websites -- All DOE Office Websites (Extended Search)

Draft Environmental Assessment on the Remote-handled Waste Disposition Project available for public review and comment Draft Environmental Assessment on the Remote-handled Waste Disposition Project available for public review and comment The U.S. Department of Energy invites the public to review and comment on a draft environmental assessment that the Department issued today, for a proposal to process approximately 327 cubic meters of remote-handled waste currently stored at the Idaho National Laboratory. An additional five cubic meters of waste stored at the Hanford Site near Richland, Washington is also evaluated since it is reasonably foreseeable that a decision may be made in the future to send that waste to Idaho for treatment. The project is necessary to prepare the waste for legally-required disposal. Under the Department�s preferred alternative, workers would use sealed rooms called hot cells at the Idaho Nuclear Technology and Engineering Center (INTEC) to process the waste, treat it as necessary and repackage it so that it is ready for disposal. The document describes the modifications necessary to hot cells to perform the work.

357

Summary - Plutonium Preparation Project at the Savannah River Site  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Site Site EM Project: PuPP ETR Report Date: October 2008 ETR-17 United States Department of Energy Office of Environmental Management (DOE-EM) External Technical Review of the Plutonium Preparation Project at the Savannah River Site Why DOE-EM Did This Review The purpose of the Plutonium Preparation Project (PuPP) is to prepare for disposition of plutonium materials; for examination, re-stabilization, and disassembly of the Fast Flux Test Facility (FFTF) unirradiated fuel; and for repackaging of Pu stored in 3013 containers. Of ~12.8 MT of plutonium, ~4.1 MT will be directly transferred to the MOX Fuel Fabrication Facility (MFFF); ~3.7 MT will require processing prior to transfer to the MFFF; and ~5 MT was proposed to be processed in H-Canyon with the

358

REQUEST FOR RECORDS DISPOSITION AUTHORITY  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Instructions on reverse) Instructions on reverse) LEAVE BLANK - GENERAL SERVICES ADMINISTRATION NATIONAL ARCHIVES AND RECORDS SERVICE, WASHINGTON, DC 20408 I . F R O M (Agency or ertabluhmentJ D A T E RECEIVED NOTIF~CATION TO AGENCY Department of Energy 2. MAJ0.R S U B D I V I S I O N I 4 . N A M E O F PERSON W I T H W H O M T O CONFER 15. TELEPHONE E X T . \OATS l A R C H l V l S T O F T H E U N I T E D STATES In accordance with the provisions of 44 U.S.C. 3303 the dispoal request. including amendmentr, is approved . 3. M I N O R S U B D I V I S I O N except for items that may be marked "disposition not approved" or "withdrawn" in column 10. If no records are proposed for disposal, the signature of the Archivist is not required. I hereby certify that I am authorized to act for this agency in matters pertaining to the disposal of the agency's records;

359

Idaho Site Nuclear Facilities  

NLE Websites -- All DOE Office Websites (Extended Search)

Site Nuclear Facilities Idaho Idaho National Laboratorys (INL) Idaho Closure Project (ICP) This page was last updated on May 16...

360

Mixed and Low-Level Treatment Facility Project. Appendix B, Waste stream engineering files, Part 1, Mixed waste streams  

SciTech Connect

This appendix contains the mixed and low-level waste engineering design files (EDFS) documenting each low-level and mixed waste stream investigated during preengineering studies for Mixed and Low-Level Waste Treatment Facility Project. The EDFs provide background information on mixed and low-level waste generated at the Idaho National Engineering Laboratory. They identify, characterize, and provide treatment strategies for the waste streams. Mixed waste is waste containing both radioactive and hazardous components as defined by the Atomic Energy Act and the Resource Conservation and Recovery Act, respectively. Low-level waste is waste that contains radioactivity and is not classified as high-level waste, transuranic waste, spent nuclear fuel, or 11e(2) byproduct material as defined by DOE 5820.2A. Test specimens of fissionable material irradiated for research and development only, and not for the production of power or plutonium, may be classified as low-level waste, provided the concentration of transuranic is less than 100 nCi/g. This appendix is a tool that clarifies presentation format for the EDFS. The EDFs contain waste stream characterization data and potential treatment strategies that will facilitate system tradeoff studies and conceptual design development. A total of 43 mixed waste and 55 low-level waste EDFs are provided.

1992-04-01T23:59:59.000Z

Note: This page contains sample records for the topic "facility disposition project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


361

The 12 GeV CEBAF Upgrade Project at Thomas Jefferson National Accelerator Facility, OAS-RA-L-11-13  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

12 GeV CEBAF Upgrade 12 GeV CEBAF Upgrade Project at Thomas Jefferson National Accelerator Facility OAS-RA-L-11-13 September 2011 Department of Energy Washington, DC 20585 September 30, 2011 MEMORANDUM FOR THE DEPUTY DIRECTOR FOR SCIENCE PROGRAMS, OFFICE OF SCIENCE DIRECTOR, OFFICE OF RISK MANAGEMENT AND FINANCIAL POLICY, OFFICE OF THE CHIEF FINANCIAL OFFICER FROM: David Sedillo, Director NNSA & Science Audits Division Office of Inspector General SUBJECT: INFORMATION: Audit Report on "The 12 GeV CEBAF Upgrade Project at Thomas Jefferson National Accelerator Facility" Audit Report Number: OAS-RA-L-11-13 BACKGROUND In September 2008, the Department of Energy's (Department) Office of Science approved a construction project to double the electron beam energy of the Continuous Electron Beam

362

Disposition of ORNL's Spent Nuclear Fuel  

SciTech Connect

This paper describes the process of retrieving, repackaging, and preparing Oak Ridge spent nuclear fuel (SNF) for off-site disposition. The objective of the Oak Ridge SNF Project is to safely, reliably, and efficiently manage SNF that is stored on the Oak Ridge Reservation until it can be shipped off-site. The project required development of several unique processes and the design and fabrication of special equipment to enable the successful retrieval, transfer, and repackaging of Oak Ridge SNF. SNF was retrieved and transferred to a hot cell for repackaging. After retrieval of SNF packages, the storage positions were decontaminated and stainless steel liners were installed to resolve the vulnerability of water infiltration. Each repackaged SNF canister has been transferred from the hot cell back to dry storage until off-site shipments can be made. Three shipments of aluminum-clad SNF were made to the Savannah River Site (SRS), and five shipments of non-aluminum-clad SNF are planned to the Idaho National Engineering and Environmental Laboratory (INEEL). Through the integrated cooperation of several organizations including the U.S. Department of Energy (DOE), Bechtel Jacobs Company LLC (BJC), Oak Ridge National Laboratory (ORNL), and various subcontractors, preparations for the disposition of SNF in Oak Ridge have been performed in a safe and successful manner.

Turner, D. W.; DeMonia, B. C.; Horton, L. L.

2002-02-26T23:59:59.000Z

363

DISPOSITION OF THE DEPARTMENT'SEXCESS FACILITIES, IG-0550 | Department...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

ranging from temporary trailer-type buildings and office space to state-of-the-art nuclear reactors and laboratories. As the Department's mission has evolved, many of these...

364

NRC comprehensive records disposition schedule. Revision 2  

SciTech Connect

Title 44 United States Code, ``Public Printing and Documents,`` regulations cited in the General Services Administration`s (GSA) ``Federal Information Resources Management Regulations`` (FIRMR), Part 201-9, ``Creation, Maintenance, and Use of Records,`` and regulation issued by the National Archives and Records Administration (NARA) in 36 CFR Chapter XII, Subchapter B, ``Records Management,`` require each agency to prepare and issue a comprehensive records disposition schedule that contains the NARA approved records disposition schedules for records unique to the agency and contains the NARA`s General Records Schedules for records common to several or all agencies. The approved records disposition schedules specify the appropriate duration of retention and the final disposition for records created or maintained by the NRC. NUREG-0910, Rev. 2, contains ``NRC`s Comprehensive Records Disposition Schedule,`` and the original authorized approved citation numbers issued by NARA. Rev. 2 totally reorganizes the records schedules from a functional arrangement to an arrangement by the host office. A subject index and a conversion table have also been developed for the NRC schedules to allow staff to identify the new schedule numbers easily and to improve their ability to locate applicable schedules.

Not Available

1992-03-01T23:59:59.000Z

365

NRC comprehensive records disposition schedule. Revision 3  

Science Conference Proceedings (OSTI)

Title 44 US Code, ``Public Printing and Documents,`` regulations issued by the General Service Administration (GSA) in 41 CFR Chapter 101, Subchapter B, ``Management and Use of Information and Records,`` and regulations issued by the National Archives and Records Administration (NARA) in 36 CFR Chapter 12, Subchapter B, ``Records Management,`` require each agency to prepare and issue a comprehensive records disposition schedule that contains the NARA approved records disposition schedules for records unique to the agency and contains the NARA`s General Records Schedules for records common to several or all agencies. The approved records disposition schedules specify the appropriate duration of retention and the final disposition for records created or maintained by the NRC. NUREG-0910, Rev. 3, contains ``NRC`s Comprehensive Records Disposition Schedule,`` and the original authorized approved citation numbers issued by NARA. Rev. 3 incorporates NARA approved changes and additions to the NRC schedules that have been implemented since the last revision dated March, 1992, reflects recent organizational changes implemented at the NRC, and includes the latest version of NARA`s General Records Schedule (dated August 1995).

NONE

1998-02-01T23:59:59.000Z

366

Lessons Learned From The 200 West Pump And Treatment Facility Construction Project At The US DOE Hanford Site - A Leadership For Energy And Environmental Design (LEED) Gold-Certified Facility  

SciTech Connect

CH2M Hill Plateau Remediation Company (CHPRC) designed, constructed, commissioned, and began operation of the largest groundwater pump and treatment facility in the U.S. Department of Energy's (DOE) nationwide complex. This one-of-a-kind groundwater pump and treatment facility, located at the Hanford Nuclear Reservation Site (Hanford Site) in Washington State, was built in an accelerated manner with American Recovery and Reinvestment Act (ARRA) funds and has attained Leadership in Energy and Environmental Design (LEED) GOLD certification, which makes it the first non-administrative building in the DOE Office of Environmental Management complex to earn such an award. There were many contractual, technical, configuration management, quality, safety, and LEED challenges associated with the design, procurement, construction, and commissioning of this $95 million, 52,000 ft groundwater pump and treatment facility. This paper will present the Project and LEED accomplishments, as well as Lessons Learned by CHPRC when additional ARRA funds were used to accelerate design, procurement, construction, and commissioning of the 200 West Groundwater Pump and Treatment (2W P&T) Facility to meet DOE's mission of treating contaminated groundwater at the Hanford Site with a new facility by June 28, 2012.

Dorr, Kent A. [CH2M HILL Plateau Remediation Company, Richland, WA (United States); Ostrom, Michael J. [CH2M HILL Plateau Remediation Company, Richland, WA (United States); Freeman-Pollard, Jhivaun R. [CH2M HILL Plateau Remediation Company, Richland, WA (United States)

2012-11-14T23:59:59.000Z

367

Plutonium Disposition Program | National Nuclear Security Administration  

NLE Websites -- All DOE Office Websites (Extended Search)

Home > Media Room > Fact Sheets > Plutonium Disposition Program Home > Media Room > Fact Sheets > Plutonium Disposition Program Fact Sheet Plutonium Disposition Program Jun 26, 2013 SUPPORTING NUCLEAR NONPROLIFERATION Weapon-grade plutonium and highly enriched uranium (HEU) are the critical ingredients for making a nuclear weapon. With the end of the Cold War, hundreds of tons of these materials were determined to be surplus to U.S. and Russian defense needs. Denying access to plutonium and HEU is the best way to prevent nuclear proliferation to rogue states and terrorist organizations. The most certain method to prevent these materials from falling into the wrong hands is to dispose of them. During the April 2010 Nuclear Security Summit, Secretary of State Hillary Rodham Clinton and Russian Foreign Minister Sergey Lavrov signed a protocol

368

Excess plutonium disposition: The deep borehole option  

SciTech Connect

This report reviews the current status of technologies required for the disposition of plutonium in Very Deep Holes (VDH). It is in response to a recent National Academy of Sciences (NAS) report which addressed the management of excess weapons plutonium and recommended three approaches to the ultimate disposition of excess plutonium: (1) fabrication and use as a fuel in existing or modified reactors in a once-through cycle, (2) vitrification with high-level radioactive waste for repository disposition, (3) burial in deep boreholes. As indicated in the NAS report, substantial effort would be required to address the broad range of issues related to deep bore-hole emplacement. Subjects reviewed in this report include geology and hydrology, design and engineering, safety and licensing, policy decisions that can impact the viability of the concept, and applicable international programs. Key technical areas that would require attention should decisions be made to further develop the borehole emplacement option are identified.

Ferguson, K.L.

1994-08-09T23:59:59.000Z

369

ANL-W MOX fuel lead assemblies data report for the surplus plutonium disposition environmental impact statement  

SciTech Connect

The purpose of this document is to support the US Department of Energy (DOE) Fissile Materials Disposition Program`s preparation of the draft surplus plutonium disposition environmental impact statement (EIS). This is one of several responses to data call requests for background information on activities associated with the operation of the lead assembly (LA) mixed-oxide (MOX) fuel fabrication facility. The DOE Office of fissile Materials Disposition (DOE-MD) has developed a dual-path strategy for disposition of surplus weapons-grade plutonium. One of the paths is to disposition surplus plutonium through irradiation of MOX fuel in commercial nuclear reactors. MOX fuel consists of plutonium and uranium oxides (PuO{sub 2} and UO{sub 2}), typically containing 95% or more UO{sub 2}. DOE-MD requested that the DOE Site Operations Offices nominate DOE sites that meet established minimum requirements that could produce MOX LAs. The paper describes the following: Site map and the LA facility; process descriptions; resource needs; employment requirements; wastes, emissions, and exposures; accident analysis; transportation; qualitative decontamination and decommissioning; post-irradiation examination; LA fuel bundle fabrication; LA EIS data report assumptions; and LA EIS data report supplement.

O`Connor, D.G.; Fisher, S.E.; Holdaway, R. [and others

1997-08-01T23:59:59.000Z

370

Surplus Highly Enriched Uranium Disposition Program plan  

SciTech Connect

The purpose of this document is to provide upper level guidance for the program that will downblend surplus highly enriched uranium for use as commercial nuclear reactor fuel or low-level radioactive waste. The intent of this document is to outline the overall mission and program objectives. The document is also intended to provide a general basis for integration of disposition efforts among all applicable sites. This plan provides background information, establishes the scope of disposition activities, provides an approach to the mission and objectives, identifies programmatic assumptions, defines major roles, provides summary level schedules and milestones, and addresses budget requirements.

1996-10-01T23:59:59.000Z

371

Interim Report on the Disposition of Solid Material: Comparative Review of Three Published Clearance Guides  

Science Conference Proceedings (OSTI)

As part of the rulemaking process, the U.S. Nuclear Regulatory Commission (NRC) is currently evaluating alternative approaches to control the disposition of solid material at nuclear facilities. The proposed rule would likely incorporate a dose-based criterion. While the NRC has been developing the scope and details of a rule, various national and international organizations have reported dose-based activity concentration levels that utilities may apply to clearance. This document evaluates and discusses...

2004-11-15T23:59:59.000Z

372

Developing Renewable Energy Projects Larger Than 10 MWs at Federal Facilities (Book), Large-Scale Renewable Energy Guide, Federal Energy Management Program (FEMP)  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

LARGE-SCALE RENEWABLE ENERGY GUIDE LARGE-SCALE RENEWABLE ENERGY GUIDE Developing Renewable Energy Projects Larger Than 10 MWs at Federal Facilities A Practical Guide to Getting Large-Scale Renewable Energy Projects Financed with Private Capital Cover photos, clockwise from the top: Installing mirrored parabolic trough collectors - (January 19, 2012) Crews work around the clock installing mirrored parabolic trough collectors, built on site, that will cover 3 square miles at Abengoa's Solana Plant. Solana a 280 megawatt utility scale solar power plant (CSP) under construction in Gila Bend, Arizona, USA. When finished it will generate 280 MW 's of clean, sustainable power serving over 70,000 Arizona homes. Photo by Dennis Schroeder, NREL 20097 Dry Lake Wind Power Project in Arizona; Suzlon S88 wind turbines - The 63-MW Dry Lake Wind Power Project in Arizona is the first

373

Developing Renewable Energy Projects Larger Than 10 MWs at Federal Facilities (Book), Large-Scale Renewable Energy Guide, Federal Energy Management Program (FEMP)  

NLE Websites -- All DOE Office Websites (Extended Search)

LARGE-SCALE RENEWABLE ENERGY GUIDE LARGE-SCALE RENEWABLE ENERGY GUIDE Developing Renewable Energy Projects Larger Than 10 MWs at Federal Facilities A Practical Guide to Getting Large-Scale Renewable Energy Projects Financed with Private Capital Cover photos, clockwise from the top: Installing mirrored parabolic trough collectors - (January 19, 2012) Crews work around the clock installing mirrored parabolic trough collectors, built on site, that will cover 3 square miles at Abengoa's Solana Plant. Solana a 280 megawatt utility scale solar power plant (CSP) under construction in Gila Bend, Arizona, USA. When finished it will generate 280 MW 's of clean, sustainable power serving over 70,000 Arizona homes. Photo by Dennis Schroeder, NREL 20097 Dry Lake Wind Power Project in Arizona; Suzlon S88 wind turbines - The 63-MW Dry Lake Wind Power Project in Arizona is the first

374

Supply and Disposition of Crude Oil and Petroleum Products  

U.S. Energy Information Administration (EIA)

Supply Disposition Ending Stocks; Field Production Renewable Fuels & Oxygenate Plant New Production Refinery & Blender Net Production Imports Net Receipts

375

Supply and Disposition of Crude Oil and Petroleum Products  

U.S. Energy Information Administration (EIA)

Supply Disposition Ending Stocks; Field Production Renewable Fuels & Oxygenate Plant Net Production Refinery & Blender Net Production Imports Net Receipts

376

Supply and Disposition of Crude Oil and Petroleum Products  

U.S. Energy Information Administration (EIA)

Supply Disposition Ending Stocks; Field Production Renewable Fuels & Oxygenate Plant New Production Refinery & Blender Net Production Imports ...

377

U.S. and Russia Sign Plutonium Disposition Agreement | National...  

NLE Websites -- All DOE Office Websites (Extended Search)

Plutonium Disposition Agreement | National Nuclear Security Administration Our Mission Managing the Stockpile Preventing Proliferation Powering the Nuclear Navy Emergency Response...

378

Office of Fissile Materials Disposition | National Nuclear Security...  

NLE Websites -- All DOE Office Websites (Extended Search)

Fissile Materials Disposition | National Nuclear Security Administration Our Mission Managing the Stockpile Preventing Proliferation Powering the Nuclear Navy Emergency Response...

379

Storage and Disposition of Weapons-Usable Fissile Materials  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

86 86 Federal Register / Vol. 63, No. 156 / Thursday, August 13, 1998 / Notices 1 SRS has been identified by DOE as the preferred site for the immobilization disposition facility. responsibilities are to (1) evaluate the standards of accreditation applied to applicant foreign medical schools; and (2) determine the comparability of those standards to standards for accreditation applied to United States medical schools. For Further Information Contact: Bonnie LeBold, Executive Director, National Committee on Foreign Medical Education and Accreditation, 7th and D Streets, S.W., Room 3082, ROB #3, Washington, D.C. 20202-7563. Telephone: (202) 260-3636. Beginning September 28, 1998, you may call to obtain the identity of the countries whose standards are to be evaluated during this

380

Project Management Plan Examples 1 - 80 | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Examples 1 - 80 Examples 1 - 80 Project Management Plan Examples 1 - 80 The following material has been extracted from several project management plans. The order in which it is presented is arbitrary. The descriptions below should be used to navigate to the subject of interest. Policy & Operational Decisions, Assumptions and Strategies - Examples 1 & 2 - Includes organizational responsibilities and structure, disposition path, future use of facility, S&S Reqs and plan, hazard elimination or mitigation, NEPA, RCRA, CERCLA, HVAC/lighting service reqs, structural integrity reqs, etc. Facility End State Decisions - Examples 3, 4 & 5 - Includes expected conditions at completion of the deactivation, DOE mission use, extended S&M, decommissioned and/or dismantled, etc.

Note: This page contains sample records for the topic "facility disposition project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


381

Project management plan for Waste Area Grouping 5 Old Hydrofracture Facility tanks contents removal at Oak Ridge National Laboratory, Oak Ridge, Tennessee  

SciTech Connect

On January 1, 1992, the US Department of Energy (DOE), the US Environmental Protection Agency (EPA) Region IV, and the Tennessee Department of Environment and Conservation (TDEC) signed a Federal Facility Agreement (FFA) concerning the Oak Ridge Reservation. The FFA requires that inactive liquid low-level (radioactive) waste (LLLW) tanks at Oak Ridge National Laboratory (ORNL) be remediated in accordance with requirements of the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA). This revision is to update the schedule and designation of responsibilities for the Old Hydrofracture Facility (OHF) tanks contents removal project. The scope of this project is to transfer inventory from the five inactive LLLW tanks at the OHF into the active LLLW system.

1998-06-01T23:59:59.000Z

382

NIST Launches New Competition for Research Facility ...  

Science Conference Proceedings (OSTI)

... Candidate projects could include laboratories, test facilities, measurement facilities ... which must be institutions of higher education and nonprofit ...

2013-06-23T23:59:59.000Z

383

Mixed and Low-Level Waste Treatment Facility Project. Appendix B, Waste stream engineering files: Part 2, Low-level waste streams  

SciTech Connect

Mixed and low-level wastes generated at the Idaho National Engineering Laboratory (INEL) are required to be managed according to applicable State and Federal regulations, and Department of Energy Orders that provide for the protection of human health and the environment. The Mixed and Low-Level Waste Treatment Facility Project was chartered in 1991, by the Department of Energy to provide treatment capability for these mixed and low-level waste streams. The first project task consisted of conducting engineering studies to identify the waste streams, their potential treatment strategies, and the requirements that would be imposed on the waste streams and the facilities used to process them. This report documents those studies so the project can continue with an evaluation of programmatic options, system tradeoff studies, and the conceptual design phase of the project. This report, appendix B, comprises the engineering design files for this project study. The engineering design files document each waste steam, its characteristics, and identified treatment strategies.

1992-04-01T23:59:59.000Z

384

Fermilab | Directorate | Office of Project Management Oversight...  

NLE Websites -- All DOE Office Websites (Extended Search)

of Project Support Services (PSS) Projects Fermilab Scientific and Facility Projects (DOE 413 Projects) Fermilab Programs Fermilab Management Projects OPMO Projects Policies...

385

Observation challenges in a glovebox environment : behavior based safety at a plutonium facility.  

SciTech Connect

Los Alamos National Laboratory (LANL) is one of the Nation's leading scientific and defense laboratories, owned by the Department of Energy and managed by the University of California. LANL is one of the original weapons complex labs dating back to the days of the Manhattan Project during World War II. Since then, radioactive materials research has continued at LANLs Plutonium Facility, and remains a primary responsibility of the Laboratory. The Nuclear Materials Technology Division (NMT) is a multidisciplinary organization responsible for daily operations of the Plutonium Facility and the Chemistry Research Metallurgy Facility. NMT Division is responsible for the saence, engineering and technology of plutonium and other actinides in support of the Nation's nuclear weapons stockpile, nuclear materials disposition, and nuclear energy programs. A wide amy of activities are performed within NMT Division, such as analytical chemistry, metallurgical operations, actinide processes, waste operations, radioactive materials research and related administrative tasks.

Montalvo, M. L. (Maryrose L.)

2002-01-01T23:59:59.000Z

386

MANAGING HANFORD'S LEGACY NO-PATH-FORWARD WASTES TO DISPOSITION  

Science Conference Proceedings (OSTI)

The U.S. Department of Energy (DOE) Richland Operations Office (RL) has adopted the 2015 Vision for Cleanup of the Hanford Site. This vision will protect the Columbia River, reduce the Site footprint, and reduce Site mortgage costs. The CH2M HILL Plateau Remediation Company's (CHPRC) Waste and Fuels Management Project (W&FMP) and their partners support this mission by providing centralized waste management services for the Hanford Site waste generating organizations. At the time of the CHPRC contract award (August 2008) slightly more than 9,000 m{sup 3} of waste was defined as 'no-path-forward waste.' The majority of these wastes are suspect transuranic mixed (TRUM) wastes which are currently stored in the low-level Burial Grounds (LLBG), or stored above ground in the Central Waste Complex (CWC). A portion of the waste will be generated during ongoing and future site cleanup activities. The DOE-RL and CHPRC have collaborated to identify and deliver safe, cost-effective disposition paths for 90% ({approx}8,000 m{sup 3}) of these problematic wastes. These paths include accelerated disposition through expanded use of offsite treatment capabilities. Disposal paths were selected that minimize the need to develop new technologies, minimize the need for new, on-site capabilities, and accelerate shipments of transuranic (TRU) waste to the Waste Isolation Pilot Plant (WIPP) in Carlsbad, New Mexico.

WEST LD

2011-01-13T23:59:59.000Z

387

Complications Associated with Long-Term Disposition of Newly-Generated Transuranic Waste: A National Laboratory Perspective  

SciTech Connect

The Idaho National Laboratory (INL) is a multipurpose national laboratory delivering specialized science and engineering solutions for the U.S. Department of Energy (DOE). Sponsorship of INL was formally transferred to the DOE Office of Nuclear Energy, Science and Technology (NE) by Secretary Spencer Abraham in July 2002. The move to NE, and designation as the DOE lead nuclear energy laboratory for reactor technology, supports the nations expanding nuclear energy initiatives, placing INL at the center of work to develop advanced Generation IV nuclear energy systems; nuclear energy/hydrogen coproduction technology; advanced nuclear energy fuel cycle technologies; and providing national security answers to national infrastructure needs. As a result of the Laboratorys NE mission, INL generates both contact-handled and remote-handled transuranic (TRU) waste from ongoing operations. Generation rates are relatively small and fluctuate based on specific programs and project activities being conducted; however, the Laboratory will continue to generate TRU waste well into the future in association with the NE mission. Currently, plans and capabilities are being established to transfer INLs contact-handled TRU waste to the Advanced Mixed Waste Treatment Plant (AMWTP) for certification and disposal to the Waste Isolation Pilot Plant (WIPP). Remote-handled TRU waste is currently placed in storage at the Materials and Fuels Complex (MFC). In an effort to minimize future liabilities associated with the INL NE mission, INL is evaluating and assessing options for the management and disposition of all its TRU waste on a real-time basis at time of generation. This paper summarizes near-term activities to minimize future re handling of INLs TRU waste, as well as, potential complications associated with the long-term disposition of newly-generated TRU waste. Potential complications impacting the disposition of INL newly-generated TRU waste include, but are not limited to: 1) required remote-handled TRU packaging configuration(s) vs. current facility capabilities, 2) long-term NE mission activities, 3) WIPP certification requirements, and 4) budget considerations.

B.J. Orchard; L.A. Harvego; T.L. Carlson; R.P. Grant

2009-03-01T23:59:59.000Z

388

U.S. Environmental Protection Agency Clear Air Act notice of construction for the spent nuclear fuel project - Cold Vaccum Drying Facility, project W-441  

Science Conference Proceedings (OSTI)

This document provides information regarding the source and the estimated quantity of potential airborne radionuclide emissions resulting from the operation of the Cold Vacuum Drying (CVD) Facility. The construction of the CVD Facility is scheduled to commence on or about December 1996, and will be completed when the process begins operation. This document serves as a Notice of Construction (NOC) pursuant to the requirements of 40 Code of Federal Regulations (CFR) 61 for the CVD Facility. About 80 percent of the U.S. Department of Energy`s spent nuclear fuel (SNF) inventory is stored under water in the Hanford Site K Basins. Spent nuclear fuel in the K West Basin is contained in closed canisters, while the SNF in the K East Basin is in open canisters, which allow release of corrosion products to the K East Basin water. Storage of the current inventory in the K Basins was originally intended to be on an as-needed basis to sustain operation of the N Reactor while the Plutonium-Uranium Extraction (PUREX) Plant was refurbished and restarted. The decision in December 1992 to deactivate the PURF-X Plant left approximately 2,100 MT (2,300 tons) of uranium as part of the N Reactor SNF in the K Basins with no means for near-term removal and processing. The CVD Facility will be constructed in the 100 Area northwest of the 190 K West Building, which is in close proximity to the K East and K West Basins (Figures 1 and 08572). The CVD Facility will consist of five processing bays, with four of the bays fully equipped with processing equipment and the fifth bay configured as an open spare bay. The CVD Facility will have a support area consisting of a control room, change rooms, and other functions required to support operations.

Turnbaugh, J.E.

1996-11-25T23:59:59.000Z

389

PROJECT MANGEMENT PLAN EXAMPLES Project Execution Example  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Project Execution Example Project Execution Example Example 73 6.3 Project Approach The overall schedule strategy for the PFP project includes ongoing minimum safe activities, combined with stabilization of materials followed by materials disposition, and subsequent transition of the PFP complex to a decommissioned state. The PFP material stabilization baseline was developed using a functionally-based work WBS. The WBS defines all activities required to take each material stream from their current location/conditions through stabilization (as required), and disposition the stabilized material as solid waste for shipment to WIPP or as product material for shipment to SRS. Initially, workshops were held with subject matter experts, project managers, schedulers, and support personnel (experts in the

390

Readiness Assessment for MF-628 Drum Treatment Facility - Advanced Mixed Waste Treatment Project … 5-07  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

NUCLEAR SAFETY (NS) NUCLEAR SAFETY (NS) Objective: NS.1 Facility safety documentation is in place and has been implemented that describes the "safety envelope" of the facility. (CR 7) Criterion: An unreviewed safety question (USQ) screen/evaluation has been completed and approved for the installation and use of the DTF for drum treatment in the DTF. Objective: NS.2 The facility systems and procedures, for the DTF and drum treatment activities, are consistent with the description of the facility, procedures, and accident analysis included in the safety basis. (CR9) Criterion: The DTF and drum treatment activities are adequately described in the documented safety analysis (DSA) or changes have been identified for inclusion in the next annual update.

391

Disposal Of Irradiated Cadmium Control Rods From The Plumbrook Reactor Facility  

SciTech Connect

Innovative mixed waste disposition from NASA's Plum Brook Reactor Facility was accomplished without costly repackaging. Irradiated characteristic hardware with contact dose rates as high as 8 Sv/hr was packaged in a HDPE overpack and stored in a Secure Environmental Container during earlier decommissioning efforts, awaiting identification of a suitable pathway. WMG obtained regulatory concurrence that the existing overpack would serve as the macro-encapsulant per 40CFR268.45 Table 1.C. The overpack vent was disabled and the overpack was placed in a stainless steel liner to satisfy overburden slumping requirements. The liner was sealed and placed in shielded shoring for transport to the disposal site in a US DOT Type A cask. Disposition via this innovative method avoided cost, risk, and dose associated with repackaging the high dose irradiated characteristic hardware. In conclusion: WMG accomplished what others said could not be done. Large D and D contractors advised NASA that the cadmium control rods could only be shipped to the proposed Yucca mountain repository. NASA management challenged MOTA to find a more realistic alternative. NASA and MOTA turned to WMG to develop a methodology to disposition the 'hot and nasty' waste that presumably had no path forward. Although WMG lead a team that accomplished the 'impossible', the project could not have been completed with out the patient, supportive management by DOE-EM, NASA, and MOTA. (authors)

Posivak, E.J.; Berger, S.R.; Freitag, A.A. [WMG, Inc., Peekskill, NY (United States)

2008-07-01T23:59:59.000Z

392

Independent Oversight Review, Los Alamos National Laboratory- September 2011  

Energy.gov (U.S. Department of Energy (DOE))

Review of the Facility Centered Assessment of the Los Alamos National Laboratory Waste Disposition Project

393

Mixed and Low-Level Waste Treatment Facility project. Executive summary: Volume 1, Program summary information; Volume 2, Waste stream technical summary: Draft  

SciTech Connect

Mixed and low-level wastes generated at the Idaho National Engineering Laboratory (INEL) are required to be managed according to applicable State and Federal regulations, and Department of Energy Orders that provide for the protection of human health and the environment. The Mixed and Low-Level Waste Treatment Facility Project was chartered in 1991, by the Department of Energy to provide treatment capability for these mixed and low-level waste streams. The first project task consisted of conducting engineering studies to identify the waste streams, their potential treatment strategies, and the requirements that would be imposed on the waste streams and the facilities used to process them. The engineering studies, initiated in July 1991, identified 37 mixed waste streams, and 55 low-level waste streams. This report documents the waste stream information and potential treatment strategies, as well as the regulatory requirements for the Department of Energy-owned treatment facility option. The total report comprises three volumes and two appendices. This report consists of Volume 1, which explains the overall program mission, the guiding assumptions for the engineering studies, and summarizes the waste stream and regulatory information, and Volume 2, the Waste Stream Technical Summary which, encompasses the studies conducted to identify the INEL`s waste streams and their potential treatment strategies.

1992-04-01T23:59:59.000Z

394

LLNL MOX fuel lead assemblies data report for the surplus plutonium disposition environmental impact statement  

SciTech Connect

The purpose of this document is to support the US Department of Energy (DOE) Fissile Materials Disposition Program`s preparation of the draft surplus plutonium disposition environmental impact statement. This is one of several responses to data call requests for background information on activities associated with the operation of the lead assembly (LA) mixed-oxide (MOX) fuel fabrication facility. The DOE Office of Fissile Materials Disposition (DOE-MD) has developed a dual-path strategy for disposition of surplus weapons-grade plutonium. One of the paths is to disposition surplus plutonium through irradiation of MOX fuel in commercial nuclear reactors. MOX fuel consists of plutonium and uranium oxides (PuO{sub 2} and UO{sub 2}), typically containing 95% or more UO{sub 2}. DOE-MD requested that the DOE Site Operations Offices nominate DOE sites that meet established minimum requirements that could produce MOX LAs. LLNL has proposed an LA MOX fuel fabrication approach that would be done entirely inside an S and S Category 1 area. This includes receipt and storage of PuO{sub 2} powder, fabrication of MOX fuel pellets, assembly of fuel rods and bundles, and shipping of the packaged fuel to a commercial reactor site. Support activities will take place within a Category 1 area. Building 332 will be used to receive and store the bulk PuO{sub 2} powder, fabricate MOX fuel pellets, and assemble fuel rods. Building 334 will be used to assemble, store, and ship fuel bundles. Only minor modifications would be required of Building 332. Uncontaminated glove boxes would need to be removed, petition walls would need to be removed, and minor modifications to the ventilation system would be required.

O`Connor, D.G.; Fisher, S.E.; Holdaway, R. [and others

1998-08-01T23:59:59.000Z

395

PROGRESS IN REDUCING THE NUCLEAR THREAT: UNITED STATES PLUTONIUM CONSOLIDATION AND DISPOSITION  

SciTech Connect

Following the end of the Cold War, the United States identified 61.5 metric tons (MT) of plutonium and larger quantities of enriched uranium that are permanently excess to use in nuclear weapons programs. The Department of Energy (DOE) also began shutting down, stabilizing, and removing inventories from production facilities that were no longer needed to support weapons programs and non-weapons activities. The storage of 'Category I' nuclear materials at Rocky Flats, Sandia National Laboratories, and several smaller sites has been terminated to reduce costs and safeguards risks. De-inventory continues at the Hanford site and the Lawrence Livermore National Laboratory. Consolidation of inventories works in concert with the permanent disposition of excess inventories, including several tonnes of plutonium that have already been disposed to waste repositories and the preparation for transfers to the planned Mixed Oxide (MOX) Fuel Fabrication Facility (for the bulk of the excess plutonium) and alternative disposition methods for material that cannot be used readily in the MOX fuel cycle. This report describes status of plutonium consolidation and disposition activities and their impacts on continuing operations, particularly at the Savannah River Site.

Allender, J.; Koenig, R.; Davies, S.

2009-06-01T23:59:59.000Z

396

SOLERAS - Solar Controlled Environment Agriculture Project. Final report, Volume 7. Science Applications, Incorporated field test facility preliminary design  

DOE Green Energy (OSTI)

This report contains the preliminary design of an SCEAS Engineering Test Facility (ETF). The ETF is a 3600 m/sup 2/ fluid roof greenhouse with an inflated plastic film roof to maintain a clean environment for the fluid roof and to protect the inner glazing from hail and other small missiles. The objective of the design was the faithful scaling of the commercial facility to ensure that the ETF results could be extrapolated to a commercial facility of any size. Therefore, all major features, including the photovoltaic power system, an integral water desalination system and even the basic structural module have been retained. The design is described in substantial detail in the body of this report, with appendices giving the drawings and specifications.

Not Available

1985-01-01T23:59:59.000Z

397

ICPP Special Fuels Canning and Characterization Facility  

SciTech Connect

This report examines the functional mission of a Special Fuels Canning and Characterization Facility (SFCCF) for the Idaho Chemical Processing Plant (ICPP) and presents justification for its implementation as part of Westinghouse Idaho Nuclear Co., Inc. (WINCO) long-range plans. The SFCCF would be built as the first phase of an overall facility for dispositioning special fuels. Issues related to feasibility, cost, and preconceptual design criteria are also discussed in this report. A preconceptual facility layout based on existing information was developed to enhance the preconceptual design criteria and support a rough order-of-magnitude cost estimate for the construction of the SFCCF. The US Department of Energy (DOE) is the landlord of a large quantity of spent nuclear fuel and related materials. A significant quantity of this inventory, approximately 730,000 kg total fuel mass, is labeled as ``special fuel`` because no specific processing technique and/or facility to disposition this material is available in the NMP complex. The dispositioning of this fuel is especially complex because of the variety of fuel types. Of these special fuels, approximately 90 %wt are stored at the INEL. Timely dispositioning of the fuels would avoid expenditures of funds for a second generation of storage facilities at the INEL and other DOE facilities and would demonstrate to the public that solutions to nuclear fuel dispositioning exist and that a plan is being executed. The SFCCF is required to characterize, verify the storage can contents, and, if necessary, recan the special fuels to help assure safe, interim storage (i.e. fission product containment and criticality control) until the special fuels processing facility is operating.

Sire, D.L.; Bendixsen, C.L.; Armstrong, E.F.; Henry, R.N.; Frandsen, G.B.

1992-04-01T23:59:59.000Z

398

Design-only conceptual design report for pit disassembly and conversion facility. Rev 0  

Science Conference Proceedings (OSTI)

This design-only conceptual design report (DOCDR) was prepared to support a funding request by the Department of Energy (DOE)-Office of Fissile Material Disposition (OFMD) for engineering design of the Pit Disassembly and Conversion Facility (PDCF) Project No. 99-D-141. The PDCF will be used to disassemble the nation`s inventory of surplus nuclear weapons pits and convert the plutonium recovered from those pits into a form suitable for storage, international inspection, and final disposition. The PDCF is a complex consisting of a hardened building that will contain the plutonium processes in a safe and secure manner, and conventional buildings and structures that will house support personnel, systems, and equipment. The PDCF uses the Advanced Recovery and Integrated Extraction System (ARIES), a low waste, modular pyroprocessing system to convert pits to plutonium oxide. The PDCF project consists of engineering and design, and construction of the buildings and structures, and engineering and design, procurement, installation, testing and start-up of equipment to disassemble pits and convert plutonium in pits to oxide form. The facility is planned to operate for 10 years, averaging 3.5 metric tons (3.86 tons) of plutonium metal per year. On conclusion of operations, the PDCF will be decontaminated and decommissioned.

Zygmunt, S.; Christensen, L.; Richardson, C.

1997-12-12T23:59:59.000Z

399

Project Plan: Long-Term Surveillance Plan (LTSP) for the Piqua Nuclear Power Facility, Piqua, Ohio, April 1998 (minor revisions November 1999).  

NLE Websites -- All DOE Office Websites (Extended Search)

Long-Term Surveillance and Maintenance Program Long-Term Surveillance and Maintenance Program Long-Term Surveillance Plan for the Piqua Nuclear Power Facility Piqua, Ohio April 1998 (minor revisions November 1999) Prepared for U.S. Department of Energy Albuquerque Operations Office Grand Junction Office Prepared by MACTEC Environmental Restoration Services, LLC Grand Junction, Colorado Project Number LTS-111-0027-00-000 Document Number S0007600 Work Performed Under DOE Contract Number DE-AC13-96GJ87335 Task Order Number MAC98-06 This page intentionally blank Document Number S0007600 Contents DOE/Grand Junction Office LTSP for Piqua Nuclear Power Facility April 1998 Page iii Contents Page 1.0 Introduction...........................................................................................................................1B1

400

Disposition of Surplus Highly Enriched Uranium  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

@ @ Printed with soy ink on recycled paper. ,, ,, This report has been reproduced directly from the best available copy. Available to DOE and DOE contractors horn the Office of Scientific and Technical Information, P.O. Box 62, Oak Ridge, TN 37831; telephone (423) 576-8401 for prices, Available to the public from the National Technical Information Service, 5285 Port Royal Road, Springfield, VA 22161. Copies of this document are available (while supplies last) upon written request to: Office of Fissile Materials Disposition, MD-4 ' Forrestal Building United States Department of Energy 1000 Independence Avenue, SW Washington, DC 20585 Department of Energy Washington, DC 20585 June 1996 Dear hterested Party: The Disposition of Surplus Highly Enriched Uranium Final Environmental Impact Statemnt is enclosed for your information. This document has been prepared in accordance

Note: This page contains sample records for the topic "facility disposition project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


401

Disposition of Surplus Highly Enriched Uranium  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

. . ------- .--- --. ---- DOE/EIS-0240 I United States Department of Energy I For Further Information Contact: U.S. Department of Energy Otice of Fissile Materials Disposition, 1000 Independence Ave., SW, Washington, D.C. 20585 1 I ---- I I . I I I I This report has been reproduced directly from the best available copy. Available to DOE and DOE contractors from the Office of Scientific and Technical Information, P.O. Box 62, Oak Ridge, TN 37831; telephone (423) 576-8401 for prices. Available to the public from the National Technical Information Service, 5285 Port Royal Road, Springfield, VA 22161. Copies of this document are available (while supplies last) upon written request to: I Office of Fissile Materials Disposition, MD-4 Forrestal Building United States Department of Energy 1000 Independence Avenue, SW Washington, DC 20585 , @ Printed with soy ink on recycled paper. -_. - COVERS~ET

402

Disposition of Surplus Highly Enriched Uranium  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

EIS-0240-S EIS-0240-S For Further Information Contact: U.S. Departmel>t of Energy Office of Fissile Materials Disposition, 1000 Independence Ave., SW, Washington, D.C. 20585 . This report has been reproduced directly from the best available copy. Available to DOE and DOE contractors from the Office of Scientific and Technical Information, P.O. Box 62, Oak Ridge, TN 37831; telephone (423) 576-8401 for prices, Available to the public from the National Technical Information Service, 5285 Port Royal Road, Springfield, VA 22161. Copies of this document are available (while supplies last) upon written request to: Office of Fissile Materials Disposition, MD-4 Forrestal Building United States Department of Energy 1000 Independence Avenue, SW Washington, DC 20585 @ Printed with soy ink on recycled paper. .__- -. @ .: Depafimmt of Energy . i i~t " Wastin@on, DC 20585 June 1996 Dear hterested

403

Portugal Egypt Figure 2. Natural gas supply and disposition in the United States, 2012  

U.S. Energy Information Administration (EIA) Indexed Site

Portugal Egypt Figure 2. Natural gas supply and disposition in the United States, 2012 (trillion cubic feet) Natural Gas Plant Liquids Production Gross Withdrawals From Gas and Oil Wells Nonhydrocarbon Gases Removed Vented/Flared Reservoir Repressuring Production Dry Gas Imports Canada Trinidad/Tobago Natural Gas Storage Facilities Exports Japan Canada Mexico Additions Withdrawals Gas Industry Use Residential Commercial Industrial Vehicle Fuel Electric Power 29.5 0.8 0.2 3.3 2.963 0.112 0.620 0.971 0.014 24.1 1.3 2.9 2.8 2.5 2.9 7.2 0.03 9.1 0.003 Sources: Energy Information Administration (EIA), Form EIA-176, "Annual Report of Natural and Supplemental Gas Supply and Disposition"; Form EIA-895, "Annual Quantity and

404

Disposition and transportation of surplus radioactive low specific activity nitric acid. Volume 1, Environmental Assessment  

Science Conference Proceedings (OSTI)

DOE is deactivating the PUREX plant at Hanford; this will involve the disposition of about 692,000 liters (183,000 gallons) of surplus nitric acid contaminated with low levels of U and other radionuclides. The nitric acid, designated as low specific activity, is stored in 4 storage tanks at PUREX. Five principal alternatives were evaluated: transfer for reuse (sale to BNF plc), no action, continued storage in Hanford upgraded or new facility, consolidation of DOE surplus acid, and processing the LSA nitric acid as waste. The transfer to BNF plc is the preferred alternative. From the analysis, it is concluded that the proposed disposition and transportation of the acid does not constitute a major federal action significantly affecting the quality of the human environment within the meaning of NEPA; therefore an environmental impact statement is not required.

NONE

1995-05-01T23:59:59.000Z

405

Case Studies of Potential Facility-Scale and Utility-Scale Non-Hydro Renewable Energy Projects across Reclamation  

DOE Green Energy (OSTI)

This report summarizes the results of an assessment and analysis of renewable energy opportunities conducted for the U.S. Department of the Interior, Bureau of Reclamation by the National Renewable Energy Laboratory. Tasks included assessing the suitability for wind and solar on both a utility and facility scale.

Haase, S.; Burman, K.; Dahle, D.; Heimiller, D.; Jimenez, A.; Melius, J.; Stoltenberg, B.; VanGeet, O.

2013-05-01T23:59:59.000Z

406

Update of the Used Fuel Disposition Campaign Implementation Plan |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Update of the Used Fuel Disposition Campaign Implementation Plan Update of the Used Fuel Disposition Campaign Implementation Plan Update of the Used Fuel Disposition Campaign Implementation Plan The Used Fuel Disposition Campaign will identify alternatives and conduct scientific research and technology development to enable storage, transportation, and disposal of used nuclear fuel and wastes generated by existing and future nuclear fuel cycles. This Campaign Implementation Plan provides summary level detail describing how the Used Fuel Disposition Campaign supports achievement of the overarching Fuel Cycle Research and Development Program mission and objectives. Activities will be sufficiently flexible to accommodate any of the potential fuel cycle options for used fuel management. Update of the Used Fuel Disposition Campaign Implementation Plan

407

Biological restoration of major transportation facilities domestic demonstration and application project (DDAP): technology development at Sandia National Laboratories.  

SciTech Connect

The Bio-Restoration of Major Transportation Facilities Domestic Demonstration and Application Program (DDAP) is a designed to accelerate the restoration of transportation nodes following an attack with a biological warfare agent. This report documents the technology development work done at SNL for this DDAP, which include development of the BROOM tool, an investigation of surface sample collection efficiency, and a flow cytometry study of chlorine dioxide effects on Bacillus anthracis spore viability.

Ramsey, James L., Jr. (.,; .); Melton, Brad; Finley, Patrick; Brockman, John; Peyton, Chad E.; Tucker, Mark David; Einfeld, Wayne; Griffith, Richard O.; Brown, Gary Stephen; Lucero, Daniel A.; Betty, Rita G.; McKenna, Sean Andrew; Knowlton, Robert G.; Ho, Pauline

2006-06-01T23:59:59.000Z

408

Project management plan for Waste Area Grouping 5 Old Hydrofracture Facility tanks contents removal at Oak Ridge National Laboratory, Oak Ridge, Tennessee  

SciTech Connect

This revision (Rev. 1) updates the schedule and designation of responsibilities for the Old Hydrofracture Facility (OHF) tanks contents removal project. Ongoing and planned future activities include: cold testing of the sluicing and pumping system; readiness assessment; equipment relocation and assembly; isotopic dilution of fissile radionuclides; sluicing and transfer of the tanks contents; and preparation of the Removal Action Completion Report. The most significant change is that the sluicing and pumping system has been configured by and will be operated by CDM Federal Programs Corporation. In addition, a new technical lead and a new project analyst have been designated within Lockheed Martin Energy Systems, Inc. and Lockheed Martin Energy Research Corp. The schedule for tanks contents removal has been accelerated, with transfer of the final batch of tank slurry now scheduled for March 31, 1998 (instead of November 10, 1998). The OHF sluicing and pumping project is proceeding as a non-time-critical removal action under the Comprehensive Environmental Response, Compensation, and Liability Act. The purpose of the project is to remove the contents from five inactive underground storage tanks, designated T-1, T-2, T-3, T-4, and T-9. The tanks contain an estimated 52,700 gal of liquid and sludge, together comprising a radioactive inventory of approximately 30,000 Ci.

1998-02-01T23:59:59.000Z

409

AEO2011: Coal Supply, Disposition, and Prices This dataset comes...  

Open Energy Info (EERE)

Supply, Disposition, and Prices This dataset comes from the Energy Information Administration (EIA), and is part of the 2011 Annual Energy Outlook Report (AEO2011). This dataset is...

410

REQUEST FOR RECORDS DISPOSITION AUTHORITY | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Nuclear Power Plant Docket Records REQUEST FOR RECORDS DISPOSITION AUTHORITY More Documents & Publications PIA - Savannah River Remediation Accreditation Boundary (SRR AB) REQUEST...

411

Disposition Record Request: Oil Import Appeals Board | Department...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Record Request: Oil Import Appeals Board Disposition Record Request: Oil Import Appeals Board OIAB Case Files. Records consist of company requests for relief from hardship imposed...

412

Used Fuel Disposition Campaign Disposal Research and Development...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

the Used Fuel Disposition Campaign (UFDC) to conduct the research and development (R&D) activities related to storage, transportation and disposal of used nuclear fuel (UNF)...

413

EIA Data: 2011 United States Coal Supply, Disposition, and Price...  

Open Energy Info (EERE)

Search Share this page on Facebook icon Twitter icon EIA Data: 2011 United States Coal Supply, Disposition, and Price Dataset Summary Description This dataset is the 2011...

414

Used Fuel Disposition Campaign Phase I Ring Compression Testing...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Phase I Ring Compression Testing of High Burnup Cladding Used Fuel Disposition Campaign Phase I Ring Compression Testing of High Burnup Cladding The purpose of ring compression...

415

A Model Ceramic System for Plutonium Disposition - Programmaster ...  

Science Conference Proceedings (OSTI)

As-Cast Microstructures in Alloys of U, Pu, and Zr with Minor Actinides (Np, Am) ... Irradiation Effects in Ceramics for Inert Matrix Fuel and Plutonium Disposition.

416

REQUEST FOR RECORDS DISPOSITION AUTHORITY | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Crude Oil REQUEST FOR RECORDS DISPOSITION AUTHORITY More Documents & Publications Oil Overcharge Refund Cases 2003 Oil Overcharge Refund Cases 1996 Oil Overcharge Refund Cases 1999...

417

Additional public meeting on plutonium disposition on September...  

NLE Websites -- All DOE Office Websites (Extended Search)

produce an oxide form of plutonium suitable for disposition and the use of mixed oxide (MOX) fuel fabricated from surplus plutonium in domestic commercial nuclear power reactors...

418

AEO2011: Total Energy Supply, Disposition, and Price Summary...  

Open Energy Info (EERE)

Total Energy Supply, Disposition, and Price Summary This dataset comes from the Energy Information Administration (EIA), and is part of the 2011 Annual Energy Outlook Report...

419

DRAFT EM SSAB Chairs Meeting Waste Disposition Strategies...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

EM HQ Updates Waste Disposition Overview Christine Gelles Associate Deputy Assistant Secretary for Waste Management Office of Environmental Management EM SSAB Chairs Meeting 5...

420

Project  

NLE Websites -- All DOE Office Websites (Extended Search)

Exploring the Standard Model Exploring the Standard Model       You've heard a lot about the Standard Model and the pieces are hopefully beginning to fall into place. However, even a thorough understanding of the Standard Model is not the end of the story but the beginning. By exploring the structure and details of the Standard Model we encounter new questions. Why do the most fundamental particles have the particular masses we observe? Why aren't they all symmetric? How is the mass of a particle related to the masses of its constituents? Is there any other way of organizing the Standard Model? The activities in this project will elucidate but not answer our questions. The Standard Model tells us how particles behave but not necessarily why they do so. The conversation is only beginning. . . .

Note: This page contains sample records for the topic "facility disposition project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


421

Development of an alternate pathway for materials destined for disposition to WIPP  

Science Conference Proceedings (OSTI)

The Los Alamos National Laboratory currently has an inventory of process residues that may be viable candidates for disposition to the Waste Isolation Pilot Project (WIPP) located at Carlsbad, New Mexico. A recent 'Attractiveness Level D' exemption allows for the discard of specified intractable materials regardless of the percent plutonium. However, the limits with respect to drum loadings must be met. Cementation is a key component of the aqueous nitrate flowsheet and serves as a 'bleed-off' stream for impurities separated from the plutonium during processing operations. The main 'feed' to the cementation operations are the 'bottoms' from the evaporation process. In the majority of cases, the cemented bottoms contain less than the allowed amount per drum for WIPP acceptance. This project would expand the route to WIPP for items that have no defined disposition path, are difficult to process, have been through multiple passes, have no current recovery operations available to recover the plutonium and that are amenable to cementation. This initial work will provide the foundation for a full scale disposition pathway of the candidate materials. Once the pathway has been expanded and a cementation matrix developed, routine discard activities will be initiated.

Ayers, Georgette Y [Los Alamos National Laboratory; Mckerley, Bill [Los Alamos National Laboratory; Veazey, Gerald W [Los Alamos National Laboratory; Ricketts, Thomas E [Los Alamos National Laboratory

2010-01-01T23:59:59.000Z

422

Project Title  

NLE Websites -- All DOE Office Websites (Extended Search)

William Bourcier William Bourcier Lawrence Livermore National Laboratory U.S. Department of Energy National Energy Technology Laboratory Carbon Storage R&D Project Review Meeting Developing the Technologies and Infrastructure for CCS August 20-22, 2013 Saline Aquifer Brine Production Well Brine Injection Well Chiller Pretreatment Desalination Brine Permeate To power plant or other use Storage pump CO 2 injection Concept is to extract and desalinate aquifer brines to create fresh water and space for CO 2 storage cap-rock 3 Presentation Outline * Overview, Purpose, Goals and Benefits * Technical status - Brine treatment and disposition - Reservoir management * Accomplishments * Summary and Planned work Goals and Objectives Technical Goals Potential advantages of brine

423

EIS-0350-S1: Supplemental Environmental Impact Statement for the Nuclear Facility Portion of the Chemistry and Metallurgy Research Building Replacement Project at Los Alamos National Laboratory, New Mexico  

Energy.gov (U.S. Department of Energy (DOE))

This Supplemental EIS evaluates the completion of the Chemistry and Metallurgy Research Building Replacement (CMRR) Project, which consists of constructing the nuclear facility portion (CMRR-NF) at Los Alamos National Laboratory (LANL). The CMRR Project provides the analytical chemistry and materials characterization capabilities currently or previously performed in the existing Chemistry and Metallurgy Research (CMR) Building. Because of recent detailed site geotechnical investigations, certain aspects of the CMRR-NR project have changed resulting in change to the environmental impacts.

424

EM Waste and Materials Disposition & Transportation  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

On Closure Success On Closure Success 1 EM Waste and Materials Disposition & Transportation National Transportation Stakeholders Forum Chicago, Illinois May 26, 2010 Frank Marcinowski Acting Chief Technical Officer and Deputy Assistant Secretary for Technical and Regulatory Support Office of Environmental Management DOE's Radioactive Waste Management Priorities * Continue to manage waste inventories in a safe and compliant manner * Address high risk waste in a cost- ff ti effective manner * Maintain and optimize current disposal capability for future generations * Develop future disposal capacity in a complex environment * Promote the development of treatment and disposal alternatives in the 2 and disposal alternatives in the

425

SAMPLE RESULTS FROM THE INTEGRATED SALT DISPOSITION PROGRAM MACROBATCH 5 TANK 21H QUALIFICATION SAMPLES  

Science Conference Proceedings (OSTI)

Savannah River National Laboratory (SRNL) analyzed samples from Tank 21H in support of qualification of Macrobatch (Salt Batch) 5 for the Integrated Salt Disposition Project (ISDP). This document reports partial results of the analyses of samples of Tank 21H. No issues with the projected Salt Batch 5 strategy are identified. Results of the analyses of the Tank 21H samples from this report in conjunction with the findings of the previous report, indicates that the material does not display any unusual characteristics.

Peters, T.; Fink, S.

2012-03-26T23:59:59.000Z

426

State of Washington Department of Health Radioactive air emissions notice of construction phase 1 for spent nuclear fuel project - cold vacuum drying facility, project W-441  

SciTech Connect

This notice of construction (NOC) provides information regarding the source and the estimated annual possession quantity resulting from operation of the Cold Vacuum Drying Facility (CVDF). Additional details on emissions generated by the operation of the CVDF will be discussed again in the Phase 11 NOC. This document serves as a NOC pursuant to the requirements of WAC 246-247-060 for the completion of Phase I NOC, defined as the pouring of concrete for the foundation flooring, construction of external walls, and construction of the building excluding the installation of CVDF process equipment. A Phase 11 NOC will be submitted for approval prior to installing and is defined as the completion of the CVDF, which consisted installation of process equipment, air emissions control, and emission monitoring equipment. About 80 percent of the U.S. Department of Energy`s spent nuclear fuel (SNF) inventory is stored under water in the Hanford Site K Basins. Spent nuclear fuel in the K West Basin is contained in closed canisters while the SNF in the K East Basin is in open canisters, which allow free release of corrosion products to the K East Basin water.

Turnbaugh, J.E.

1996-08-15T23:59:59.000Z

427

Microsoft PowerPoint - FY09_11 Disposition Plan_090804  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

to 2011 FIMS Disposition to 2011 FIMS Disposition Plan Phil Dalby, P.E., LEED AP Facilities Engineer Office of Engineering and Construction Management U. S. Department of Energy August 4, 2009 2 FY 2009 to FY 2011 Disposition Plan RPV # Of Assets GSF RPV # Of Assets Gross Sq Feet FY 02 N/A N/A N/A $322,545,118 379 1,533,715 - $2,914,059 $322,545,118 FY 03 N/A N/A N/A $313,800,817 420 1,140,524 - $2,166,996 $636,345,935 FY 04 N/A N/A N/A $678,724,838 536 2,878,328 - $5,468,823 $1,315,070,773 FY 05 $1,029,311,442 473 4,111,764 $1,047,538,247 488 4,101,396 102% $7,792,652 $2,362,609,020 FY 06 $788,456,532 270 1,773,232 $1,352,580,138 625 2,800,679 172% $5,321,290 $3,715,189,158 FY 07 $550,347,778 208 1,414,961 $595,332,143 243 1,568,969 108% $2,981,041 $4,310,521,301 FY 08 $312,272,791 114 782,388 $1,029,579,616 219 1,418,007 330%

428

Lunch & Learn Facilities &  

E-Print Network (OSTI)

reimbursements to the University for costs incurred in support of sponsored projects Sponsor perspective: F&A represent the sponsor's fair share of facilities and administration as it relates to total project costs 7Lunch & Learn Facilities & Administrative (F&A) Costs #12;Today's Agenda What are F&A Costs? How

McQuade, D. Tyler

429

Mound facility physical characterization  

Science Conference Proceedings (OSTI)

The purpose of this report is to provide a baseline physical characterization of Mound`s facilities as of September 1993. The baseline characterizations are to be used in the development of long-term future use strategy development for the Mound site. This document describes the current missions and alternative future use scenarios for each building. Current mission descriptions cover facility capabilities, physical resources required to support operations, current safety envelope and current status of facilities. Future use scenarios identify potential alternative future uses, facility modifications required for likely use, facility modifications of other uses, changes to safety envelope for the likely use, cleanup criteria for each future use scenario, and disposition of surplus equipment. This Introductory Chapter includes an Executive Summary that contains narrative on the Functional Unit Material Condition, Current Facility Status, Listing of Buildings, Space Plans, Summary of Maintenance Program and Repair Backlog, Environmental Restoration, and Decontamination and Decommissioning Programs. Under Section B, Site Description, is a brief listing of the Site PS Development, as well as Current Utility Sources. Section C contains Site Assumptions. A Maintenance Program Overview, as well as Current Deficiencies, is contained within the Maintenance Program Chapter.

Tonne, W.R.; Alexander, B.M.; Cage, M.R.; Hase, E.H.; Schmidt, M.J.; Schneider, J.E.; Slusher, W.; Todd, J.E.

1993-12-01T23:59:59.000Z

430

Evaluation of nuclear facility decommissioning projects: Summary status report: Three Mile Island Unit 2. Radioactive waste and laundry shipments  

SciTech Connect

This document summarizes information concerning radioactive waste and laundry shipments from the Three Mile Island Nuclear Station Unit 2 to radioactive waste disposal sites and to protective clothing decontamination facilities (laundries) since the loss of coolant accident experienced on March 28, 1979. Data were collected from radioactive shipment records, summarized, and placed in a computerized data information retrieval/manipulation system which permits extraction of specific information. This report covers the period of April 9, 1979 through April 19, 1987. Included in this report are: waste disposal site locations, dose rates, curie content, waste description, container type and number, volumes and weights. This information is presented in two major categories: protective clothing (laundry) and radioactive waste. Each of the waste shipment reports is in chronological order.

Doerge, D. H.; Haffner, D. R.

1988-06-01T23:59:59.000Z

431

Disposition of nuclear waste using subcritical accelerator-driven systems  

Science Conference Proceedings (OSTI)

Studies have shown that the repository long-term radiological risk is from the long-lived transuranics and the fission products Tc-99 and I-129, thermal loading concerns arise mainly form the short-lived fission products Sr-90 and Cs-137. In relation to the disposition of nuclear waste, ATW is expected to accomplish the following: (1) destroy over 99.9% of the actinides; (2) destroy over 99.9% of the Tc and I; (3) separate Sr and Cs (short half-life isotopes); (4) separate uranium; (5) produce electricity. In the ATW concept, spent fuel would