Powered by Deep Web Technologies
Note: This page contains sample records for the topic "bed demonstration project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


1

NUCLA Circulating Atmospheric Fluidized Bed Demonstration Project  

Science Conference Proceedings (OSTI)

The objective of this DOE Cooperative Agreement is to conduct a cost-shared clean coal technology project to demonstrate the feasibility of circulating fluidized bed combustion technology and to evaluate economic, environmental, and operational benefits of CFB steam generators on a utility scale. At the conclusion of the Phase 2 program, testing related to satisfying these objectives was completed. Data analysis and reporting are scheduled for completion by October 1991. (VC)

Not Available

1992-02-01T23:59:59.000Z

2

Nucla circulating atmospheric fluidized bed demonstration project  

Science Conference Proceedings (OSTI)

Colorado-Ute Electric Association began a study to evaluate options for upgrading and extending the life of its Nucla power station in 1982. Located in southwestern Colorado near the town of Nucla, this station was commissioned in 1959 with a local bituminous coal as its design fuel for three identical stoker-fired units, each rated at 12.6 MW(e). Poor station efficiency, high fuel costs, and spiraling boiler maintenance costs forced the Nucla Station into low priority in the CUEA dispatch order as early as 1981. Among the options CUEA considered was to serve as a host utility to demonstrate Atmospheric Fluidized Bed Combustion (AFBC) technology. The anticipated environmental benefits and apparent attractive economics of a circulating AFBC led to Colorado-Ute's decision to proceed with the design and construction of a demonstration project in 1984 at the Nucla facility.

Not Available

1991-10-01T23:59:59.000Z

3

Nucla circulating atmospheric fluidized bed demonstration project  

Science Conference Proceedings (OSTI)

During the fourth quarter of 1990, steady-state performance testing at the Nucla Circulating Fluidized Bed (CFB) resumed under sponsorship of the US Department of Energy. Co-sponsorship of the Demonstration Test Program by the Electric Power Research Institute (EPRI) was completed on June 15, 1990. From October through December, 1990, Colorado-Ute Electric Association (CUEA) completed a total of 23 steady-state performance tests, 4 dynamic tests, and set operating records during November and December as the result of improved unit operating reliability. Highlight events and achievements during this period of operation are presented.

Not Available

1991-01-31T23:59:59.000Z

4

NUCLA Circulating Atmospheric Fluidized Bed Demonstration Project  

Science Conference Proceedings (OSTI)

This Annual Report on Colorado-Ute Electric Association's NUCLA Circulating Fluidized Bed (CFB) Demonstration Program covers the period from February 1987 through December 1988. The outline for presentation in this report includes a summary of unit operations along with individual sections covering progress in study plan areas that commenced during this reporting period. These include cold-mode shakedown and calibration, plant commercial performance statistics, unit start-up (cold), coal and limestone preparation and handling, ash handling system performance and operating experience, tubular air heater, baghouse operation and performance, materials monitoring, and reliability monitoring. During this reporting period, the coal-mode shakedown and calibration plan was completed. (VC)

Not Available

1991-01-01T23:59:59.000Z

5

NUCLA Circulating Atmospheric Fluidized Bed Demonstration Project  

SciTech Connect

The report summarizes unit operating experience and test program progress for 1989 on Colorado-Ute Electric Association's Nucla CFB Demonstration Program. During this period, the objectives of the Nucla Station operating group were to correct problems with refractory durability, resolve primary air fan capacity limitations, complete the high ash and high sulfur coal tests, switch to Salt Creek coal as the operating fuel, and make the unit available for testing without capacity restrictions. Each of these objectives was addressed and accomplished, to varying degrees, except for the completion of the high sulfur coal acceptance tests. (VC)

Not Available

1992-02-01T23:59:59.000Z

6

DMEC-1 Pressurized Circulating Fluidized-Bed Demonstration Project  

SciTech Connect

The DMEC-1 project will demonstrate the use of Pyropower`s PYROFLOW pressurized circulating fluidized bed technology to repower an existing coal fired generating station. This will be the first commercial application of this technology in the world. The project is now in budget period 1, the preliminary design phase.

Kruempel, G.E.; Ambrose, S.J. [Midwest Power, Des Moines, IA (United States); Provol, S.J. [Pyropower Corp., San Diego, CA (United States)

1992-12-01T23:59:59.000Z

7

NUCLA Circulating Atmospheric Fluidized Bed Demonstration Project. 1990 Annual report  

Science Conference Proceedings (OSTI)

The objective of this DOE Cooperative Agreement is to conduct a cost-shared clean coal technology project to demonstrate the feasibility of circulating fluidized bed combustion technology and to evaluate economic, environmental, and operational benefits of CFB steam generators on a utility scale. At the conclusion of the Phase 2 program, testing related to satisfying these objectives was completed. Data analysis and reporting are scheduled for completion by October 1991. (VC)

Not Available

1992-02-01T23:59:59.000Z

8

Nucla circulating atmospheric fluidized bed demonstration project. Final report  

Science Conference Proceedings (OSTI)

Colorado-Ute Electric Association began a study to evaluate options for upgrading and extending the life of its Nucla power station in 1982. Located in southwestern Colorado near the town of Nucla, this station was commissioned in 1959 with a local bituminous coal as its design fuel for three identical stoker-fired units, each rated at 12.6 MW(e). Poor station efficiency, high fuel costs, and spiraling boiler maintenance costs forced the Nucla Station into low priority in the CUEA dispatch order as early as 1981. Among the options CUEA considered was to serve as a host utility to demonstrate Atmospheric Fluidized Bed Combustion (AFBC) technology. The anticipated environmental benefits and apparent attractive economics of a circulating AFBC led to Colorado-Ute`s decision to proceed with the design and construction of a demonstration project in 1984 at the Nucla facility.

Not Available

1991-10-01T23:59:59.000Z

9

NUCLA Circulating Atmospheric Fluidized Bed Demonstration Project. Annual report, 1988  

Science Conference Proceedings (OSTI)

This Annual Report on Colorado-Ute Electric Association`s NUCLA Circulating Fluidized Bed (CFB) Demonstration Program covers the period from February 1987 through December 1988. The outline for presentation in this report includes a summary of unit operations along with individual sections covering progress in study plan areas that commenced during this reporting period. These include cold-mode shakedown and calibration, plant commercial performance statistics, unit start-up (cold), coal and limestone preparation and handling, ash handling system performance and operating experience, tubular air heater, baghouse operation and performance, materials monitoring, and reliability monitoring. During this reporting period, the coal-mode shakedown and calibration plan was completed. (VC)

Not Available

1991-01-01T23:59:59.000Z

10

The Nucla Circulating Fluidized-Bed Demonstration Project: A U.S. DOE post-project assessment  

Science Conference Proceedings (OSTI)

This report is a post-project assessment of the Nucla Circulating Fluidized-Bed (CFB) Demonstration Project, the second project to be completed in the DOE Clean Coal Technology Program. Nucla was the first successful utility repowering project in the US, increasing the capacity of the original power station from 36 MW(e) to 110 MW(e) and extending its life by 30 years. In the CFB boiler, combustion and desulfurization both take place in the fluidized bed. Calcium in the sorbent captures sulfur dioxide and the relatively low combustion temperatures limit NOx formation. Hot cyclones separate the larger particles from the gas and recirculates them to the lower zones of the combustion chambers. This continuous circulation of coal char and sorbent particles is the novel feature of CFB technology. This demonstration project significantly advanced the environmental, operational, and economic potential of atmospheric CFB technology, precipitating a large number of orders for atmospheric CFB equipment. By 1994, more than 200 atmospheric CFB boilers have been constructed worldwide. Although at least six CFB units have been operated, the Nucla project`s CFB database continues to be an important and unique resource for the design of yet larger atmospheric CFB systems. The post-project assessment report is an independent DOE appraisal of the success a completed project had in achieving its objectives and aiding in the commercialization of the demonstrated technology. The report also provides an assessment of the expected technical, environmental, and economic performance of the commercial version of the technology as well as an analysis of the commercial market.

NONE

1995-06-01T23:59:59.000Z

11

Nucla circulating atmospheric fluidized bed demonstration project. Quarterly technical progress report, October--December 1990  

Science Conference Proceedings (OSTI)

During the fourth quarter of 1990, steady-state performance testing at the Nucla Circulating Fluidized Bed (CFB) resumed under sponsorship of the US Department of Energy. Co-sponsorship of the Demonstration Test Program by the Electric Power Research Institute (EPRI) was completed on June 15, 1990. From October through December, 1990, Colorado-Ute Electric Association (CUEA) completed a total of 23 steady-state performance tests, 4 dynamic tests, and set operating records during November and December as the result of improved unit operating reliability. Highlight events and achievements during this period of operation are presented.

Not Available

1991-01-31T23:59:59.000Z

12

NUCLA Circulating Atmospheric Fluidized Bed Demonstration Project. 1989 Annual report, [January 1989--December 1989  

SciTech Connect

The report summarizes unit operating experience and test program progress for 1989 on Colorado-Ute Electric Association`s Nucla CFB Demonstration Program. During this period, the objectives of the Nucla Station operating group were to correct problems with refractory durability, resolve primary air fan capacity limitations, complete the high ash and high sulfur coal tests, switch to Salt Creek coal as the operating fuel, and make the unit available for testing without capacity restrictions. Each of these objectives was addressed and accomplished, to varying degrees, except for the completion of the high sulfur coal acceptance tests. (VC)

Not Available

1992-02-01T23:59:59.000Z

13

Nucla CFB Demonstration Project  

SciTech Connect

This report documents Colorado-Ute Electric Association's Nucla Circulating Atmospheric Fluidized-Bed Combustion (AFBC) demonstration project. It describes the plant equipment and system design for the first US utility-size circulating AFBC boiler and its support systems. Included are equipment and system descriptions, design/background information and appendices with an equipment list and selected information plus process flow and instrumentation drawings. The purpose of this report is to share the information gathered during the Nucla circulating AFBC demonstration project and present it so that the general public can evaluate the technical feasibility and cost effectiveness of replacing pulverized or stoker-fired boiler units with circulating fluidized-bed boiler units. (VC)

Not Available

1990-12-01T23:59:59.000Z

14

The Midwest Power PCFB demonstration projects: AHLSTROM PYROFLOW[reg sign] first and second generation pressurized circulating fluidized bed (PCFB) technology  

SciTech Connect

Midwest Power, Dairyland Power Cooperative, Pyropower Corporation (a subsidiary of Ahlstrom Pyropower Inc.), and Black Veatch, have embarked on the demonstration of Clean Coal Technology (CCT) at Midwest Power's Des Moines Energy Center (DMEC), in Pleasant Hill, Iowa. The DMEC-1 PCFB Demonstration Project was selected by the US Department of Energy for the demonstration of the First Generation Pressurized Circulating Fluidized Bed (PCFB) Technology. During Round 5 of the CCT Program, Midwest Power submitted a proposal for a second unit, to be known as DMEC-2. If selected by the DOE, the DMEC-2 unit will demonstrate Ahlstrom Pyropower's Second Generation (Advanced) PCFB technology which will incorporate a topping combustor fired on coal derived gas generated in a PCFB carbonizer, to raise the firing temperature of the gas turbine and the total net plant efficiency. The First Generation PCFB technology has the capability to achieve 40--42% efficiency, the Second Generation technology can obtain an efficiency in the range of 44--47% net. This paper will provide a comparison of the commercial versions of the First and Second Generation PCFB systems, and the plans for demonstrating these systems for repowering and new plant installations during the late 1990's and into the next century. A discussion of the DMEC-1 and DMEC-2 projects and their key technical features will be provided together with a projection of the future markets for these advanced clean coal technologies.

Ambrose, S.; Green, C.L.; Dryden, R.; Provol, S.J.

1993-01-01T23:59:59.000Z

15

The Midwest Power PCFB demonstration projects: AHLSTROM PYROFLOW{reg_sign} first and second generation pressurized circulating fluidized bed (PCFB) technology  

SciTech Connect

Midwest Power, Dairyland Power Cooperative, Pyropower Corporation (a subsidiary of Ahlstrom Pyropower Inc.), and Black & Veatch, have embarked on the demonstration of Clean Coal Technology (CCT) at Midwest Power`s Des Moines Energy Center (DMEC), in Pleasant Hill, Iowa. The DMEC-1 PCFB Demonstration Project was selected by the US Department of Energy for the demonstration of the First Generation Pressurized Circulating Fluidized Bed (PCFB) Technology. During Round 5 of the CCT Program, Midwest Power submitted a proposal for a second unit, to be known as DMEC-2. If selected by the DOE, the DMEC-2 unit will demonstrate Ahlstrom Pyropower`s Second Generation (Advanced) PCFB technology which will incorporate a topping combustor fired on coal derived gas generated in a PCFB carbonizer, to raise the firing temperature of the gas turbine and the total net plant efficiency. The First Generation PCFB technology has the capability to achieve 40--42% efficiency, the Second Generation technology can obtain an efficiency in the range of 44--47% net. This paper will provide a comparison of the commercial versions of the First and Second Generation PCFB systems, and the plans for demonstrating these systems for repowering and new plant installations during the late 1990`s and into the next century. A discussion of the DMEC-1 and DMEC-2 projects and their key technical features will be provided together with a projection of the future markets for these advanced clean coal technologies.

Ambrose, S.; Green, C.L.; Dryden, R.; Provol, S.J.

1993-04-01T23:59:59.000Z

16

Toms Creek IGCC Demonstration Project  

SciTech Connect

The Toms Creek Integrated Gasification Combined Cycle (IGCC) Demonstration Project was selected by DOE in September 1991 to participate in Round Four of the Clean Coal Technology Demonstration Program. The project will demonstrate a simplified IGCC process consisting of an air-blown, fluidized-bed gasifier (Tampella U-Gas), a gas cooler/steam generator, and a hot gas cleanup system in combination with a gas turbine modified for use with a low-Btu content fuel and a conventional steam bottoming cycle. The demonstration plant will be located at the Toms Creek coal mine near Coeburn, Wise County, Virginia. Participants in the project are Tampella Power Corporation and Coastal Power Production Company. The plant will use 430 tons per day of locally mined bituminous coal to produce 55 MW of power from the gasification section of the project. A modern pulverized coal fired unit will be located adjacent to the Demonstration Project producing an additional 150 MW. A total 190 MW of power will be delivered to the electric grid at the completion of the project. In addition, 50,000 pounds per hour of steam will be exported to be used in the nearby coal preparation plant. Dolomite is used for in-bed gasifier sulfur capture and downs cleanup is accomplished in a fluidized-bed of regenerative zinc titanate. Particulate clean-up, before the gas turbine, will be performed by high temperature candle filters (1020{degree}F). The demonstration plant heat rate is estimated to be 8,700 Btu/kWh. The design of the project goes through mid 1995, with site construction activities commencing late in 1995 and leading to commissioning and start-up by the end of 1997. This is followed by a three year demonstration period.

Virr, M.J.

1992-11-01T23:59:59.000Z

17

Toms Creek IGCC Demonstration Project  

SciTech Connect

The Toms Creek Integrated Gasification Combined Cycle (IGCC) Demonstration Project was selected by DOE in September 1991 to participate in Round Four of the Clean Coal Technology Demonstration Program. The project will demonstrate a simplified IGCC process consisting of an air-blown, fluidized-bed gasifier (Tampella U-Gas), a gas cooler/steam generator, and a hot gas cleanup system in combination with a gas turbine modified for use with a low-Btu content fuel and a conventional steam bottoming cycle. The demonstration plant will be located at the Toms Creek coal mine near Coeburn, Wise County, Virginia. Participants in the project are Tampella Power Corporation and Coastal Power Production Company. The plant will use 430 tons per day of locally mined bituminous coal to produce 55 MW of power from the gasification section of the project. A modern pulverized coal fired unit will be located adjacent to the Demonstration Project producing an additional 150 MW. A total 190 MW of power will be delivered to the electric grid at the completion of the project. In addition, 50,000 pounds per hour of steam will be exported to be used in the nearby coal preparation plant. Dolomite is used for in-bed gasifier sulfur capture and downs cleanup is accomplished in a fluidized-bed of regenerative zinc titanate. Particulate clean-up, before the gas turbine, will be performed by high temperature candle filters (1020[degree]F). The demonstration plant heat rate is estimated to be 8,700 Btu/kWh. The design of the project goes through mid 1995, with site construction activities commencing late in 1995 and leading to commissioning and start-up by the end of 1997. This is followed by a three year demonstration period.

Virr, M.J.

1992-01-01T23:59:59.000Z

18

Notice of Intent to Prepare an Environmental Impact Statement for the Proposed McIntosh Unit 4 Pressurized Circulating Fluidized Bed Demonstration Project, March 25, 1999  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

10 10 Federal Register / Vol. 64, No. 58 / Friday, March 26, 1999 / Notices DEPARTMENT OF ENERGY Notice of Intent To Prepare an Environmental Impact Statement for the Proposed McIntosh Unit 4 Pressurized Circulating Fluidized Bed Demonstration Project AGENCY: U.S. Department of Energy. ACTION: Notice of intent to prepare an Environmental Impact Statement. SUMMARY: The U.S. Department of Energy (DOE) announces its intent to prepare an Environmental Impact Statement (EIS) pursuant to the National Environmental Policy Act (NEPA), the Council on Environmental Quality (CEQ) NEPA regulations (40 CFR Parts 1500-1508), and the DOE NEPA regulations (10 CFR Part 1021), to assess the potential environmental and human health impacts of a proposed project to expand the C. D. McIntosh, Jr. Power

19

NAVAJO ELECTRIFICATION DEMONSTRATION PROJECT  

SciTech Connect

The Navajo Electrification Demonstration Project (NEDP) is a multi-year project which addresses the electricity needs of the unserved and underserved Navajo Nation, the largest American Indian tribe in the United States. The program serves to cumulatively provide off-grid electricty for families living away from the electricty infrastructure, line extensions for unserved families living nearby (less than 1/2 mile away from) the electricity, and, under the current project called NEDP-4, the construction of a substation to increase the capacity and improve the quality of service into the central core region of the Navajo Nation.

Terry W. Battiest

2008-06-11T23:59:59.000Z

20

TIDD PFBC Demonstration Project  

SciTech Connect

In fluidized bed combustion, coal and sorbent (dolomite or limestone) are fed into a boiler in which air, entering from the bottom, maintains the bed material in a highly turbulent suspended state called fluidization. This turbulence creates good contact between the air and fuel, allowing for high combustion efficiency and excellent adsorption of sulfur dioxide (SO{sub 2}) during the combustion process. In PFBC applications, pressurized air is supplied to the combustor. Pressurizing the air concentrates a larger quantity of oxygen per unit volume. This results in a lower velocity of air through the fuel bed. The lower velocity reduces the total height required for the bed and freeboard above the bed. Also, a smaller plan area is required for the bed area as compared to an atmospheric fluidized bed. This has the advantage of requiring a much smaller pressure vessel to contain the boiler enclosure. The mean bed temperature of a pressurized fluidized bed combustor is typically maintained in the range 1540 to 1580 F. This is well below the ash fusion temperature of coal, yet above the ignition temperature of the coal. Advantages of the low bed temperature are no slag formation and a reduction of NO{sub x} emissions to less than half that of a conventional boiler. The Tidd Plant is a combined cycle pressurized fluidized bed combustion system with a topping gas cycle and a bottoming steam cycle.

Not Available

1994-03-01T23:59:59.000Z

Note: This page contains sample records for the topic "bed demonstration project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


21

EIS-0289: JEA Circulating Fluidized Bed Combustor Project | Department of  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

289: JEA Circulating Fluidized Bed Combustor Project 289: JEA Circulating Fluidized Bed Combustor Project EIS-0289: JEA Circulating Fluidized Bed Combustor Project SUMMARY This EIS assesses environmental issues associated with constructing and demonstrating a project that would be cost-shared by DOE and JEA (formerly the Jacksonville Electric Authority) under the Clean Coal Technology Program. PUBLIC COMMENT OPPORTUNITIES None available at this time. DOCUMENTS AVAILABLE FOR DOWNLOAD December 7, 2000 EIS-0289: Record of Decision JEA Circulating Fluidized Bed Combustor Project, Jacksonville, Duval County, FL June 1, 2000 EIS-0289: Final Environmental Impact Statement JEA Circulating Fluidized Bed Combustor Project August 1, 1999 EIS-0289: Draft Environmental Impact Statement JEA Circulating Fluidized Bed Combustor

22

PFBC Utility Demonstration Project  

Science Conference Proceedings (OSTI)

This report provides a summary of activities by American Electric Power Service Corporation during the first budget period of the PFBC Utility Demonstration Project. In April 1990, AEP signed a Cooperative Agreement with the US Department of Energy to repower the Philip Sporn Plant, Units 3 4 in New Haven, West Virginia, with a 330 KW PFBC plant. The purpose of the program was to demonstrate and verify PFBC in a full-scale commercial plant. The technical and cost baselines of the Cooperative Agreement were based on a preliminary engineering and design and a cost estimate developed by AEP subsequent to AEP's proposal submittal in May 1988, and prior to the signing of the Cooperative Agreement. The Statement of Work in the first budget period of the Cooperative Agreement included a task to develop a preliminary design and cost estimate for erecting a Greenfield plant and to conduct a comparison with the repowering option. The comparative assessment of the options concluded that erecting a Greenfield plant rather than repowering the existing Sporn Plant could be the technically and economically superior alternative. The Greenfield plant would have a capacity of 340 MW. The ten additional MW output is due to the ability to better match the steam cycle to the PFBC system with a new balance of plant design. In addition to this study, the conceptual design of the Sporn Repowering led to several items which warranted optimization studies with the goal to develop a more cost effective design.

Not Available

1992-11-01T23:59:59.000Z

23

Circulating Fluidized Bed Combustion Boiler Project  

E-Print Network (OSTI)

The project to build a PYROFLOW circulating fluidized bed combustion (FBC) boiler at the BFGoodrich Chemical Plant at Henry, Illinois, is described. This project is being partially funded by Illinois to demonstrate the feasibility of utilizing high-sulfur Illinois coal. Design production is 125,000 pounds per hour of 400 psig saturated steam. An Illinois EPA construction permit has been received, engineering design is under way, major equipment is on order, ground breaking occurred in January 1984 and planned commissioning date is late 1985. This paper describes the planned installation and the factors and analyses used to evaluate the technology and justify the project. Design of the project is summarized, including the boiler performance requirements, the PYROFLOW boiler, the coal, limestone and residue handling systems and the pollutant emission limitations.

Farbstein, S. B.; Moreland, T.

1984-01-01T23:59:59.000Z

24

Solar energy demonstration project  

SciTech Connect

The solar heating demonstration system at the DOE cafeteria at Grand Junction, Colorado, is briefly described. The system will supply an estimated 40 percent of the energy required for domestic hot water and building heat. (WHK)

1978-01-01T23:59:59.000Z

25

LIMB Demonstration Project Extension  

Science Conference Proceedings (OSTI)

The basic goal of the Limestone Injection Multistage Burner (LIMB) demonstration is to extend LIMB technology development to a full- scale application on a representative wall-fired utility boiler. The successful retrofit of LIMB to an existing boiler is expected to demonstrate that (a) reductions of 50 percent or greater in SO{sub x} and NO{sub x} emissions can be achieved at a fraction of the cost of add-on FGD systems, (b) boiler reliability, operability, and steam production can be maintained at levels existing prior to LIMB retrofit, and (c) technical difficulties attributable to LIMB operation, such as additional slagging and fouling, changes in ash disposal requirements, and an increased particulate load, can be resolved in a cost-effective manner. The primary fuel to be used will be an Ohio bituminous coal having a nominal sulfur content of 3 percent or greater.

Not Available

1988-12-15T23:59:59.000Z

26

LIMB Demonstration Project Extension  

Science Conference Proceedings (OSTI)

The basic goal of the Limestone Injection Multistage Burner (LIMB) demonstration is to extend LIMB technology development to a full-scale application on a representative wall-fired utility boiler. The successful retrofit of LIMB to an existing boiler is expected to demonstrate that (a) reductions of 50 percent or greater in SO and NO emissions can be achieved at a fraction of the cost of add-on FGD systems, (b) boiler reliability, operability, and steam production can be maintained at levels existing prior to LIMB retrofit, and (c) technical difficulties attributable to LIMB operation, such as additional slagging and fouling, changes in ash disposal requirements, and an increased particulate load, can be resolved in a cost-effective manner. The primary fuel to be used will be an Ohio bituminous coal having a nominal sulfur content of 3 percent or greater.

Not Available

1988-09-15T23:59:59.000Z

27

Solar Thermal Demonstration Project  

SciTech Connect

HVAC Retrofit and Energy Efficiency Upgrades at Clark High School, Las Vegas, Nevada The overall objectives of this project are to increase usage of alternative/renewable fuels, create a better and more reliable learning environment for the students, and reduce energy costs. Utilizing the grant resources and local bond revenues, the District proposes to reduce electricity consumption by installing within the existing limited space, one principal energy efficient 100 ton adsorption chiller working in concert with two 500 ton electric chillers. The main heating source will be primarily from low nitrogen oxide (NOX), high efficiency natural gas fired boilers. With the use of this type of chiller, the electric power and cost requirements will be greatly reduced. To provide cooling to the information technology centers and equipment rooms of the school during off-peak hours, the District will install water source heat pumps. In another measure to reduce the cooling requirements at Clark High School, the District will replace single pane glass and metal panels with ??Kalwall?? building panels. An added feature of the ??Kalwall? system is that it will allow for natural day lighting in the student center. This system will significantly reduce thermal heat/cooling loss and control solar heat gain, thus delivering significant savings in heating ventilation and air conditioning (HVAC) costs.

Biesinger, K.; Cuppett, D.; Dyer, D.

2012-01-30T23:59:59.000Z

28

LIMB Demonstration Project Extension and Coolside Demonstration  

SciTech Connect

This report presents results from the limestone Injection Multistage Burner (LIMB) Demonstration Project Extension. LIMB is a furnace sorbent injection technology designed for the reduction of sulfur dioxide (SO[sub 2]) and nitrogen oxides (NO[sub x]) emissions from coal-fired utility boilers. The testing was conducted on the 105 Mwe, coal-fired, Unit 4 boiler at Ohio Edison's Edgewater Station in Lorain, Ohio. In addition to the LIMB Extension activities, the overall project included demonstration of the Coolside process for S0[sub 2] removal for which a separate report has been issued. The primary purpose of the DOE LIMB Extension testing, was to demonstrate the generic applicability of LIMB technology. The program sought to characterize the S0[sub 2] emissions that result when various calcium-based sorbents are injected into the furnace, while burning coals having sulfur content ranging from 1.6 to 3.8 weight percent. The four sorbents used included calcitic limestone, dolomitic hydrated lime, calcitic hydrated lime, and calcitic hydrated lime with a small amount of added calcium lignosulfonate. The results include those obtained for the various coal/sorbent combinations and the effects of the LIMB process on boiler and plant operations.

Goots, T.R.; DePero, M.J.; Nolan, P.S.

1992-11-10T23:59:59.000Z

29

DOD ESTCP Energy Test Bed Project | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

DOD ESTCP Energy Test Bed Project DOD ESTCP Energy Test Bed Project Presentation covers the DOD ESTCP Energy Test Bed Project, given at the May, 23 2012 Federal Technology...

30

Shallow Carbon Sequestration Demonstration Project  

NLE Websites -- All DOE Office Websites (Extended Search)

Shallow Carbon SequeStration Shallow Carbon SequeStration DemonStration ProjeCt Background The Shallow Carbon Sequestration Pilot Demonstration Project is a cooperative effort involving City Utilities of Springfield (CU); Missouri Department of Natural Resources (MDNR); Missouri State University (MSU); Missouri University of Science & Technology (MS&T); AmerenUE; Aquila, Inc.; Associated Electric Cooperative, Inc.; Empire District Electric Company; and Kansas City Power & Light. The purpose of this project is to assess the feasibility of carbon sequestration at Missouri power plant sites. The six electric utilities involved in the project account for approximately 90 percent of the electric generating capacity in Missouri. Description The pilot demonstration will evaluate the feasibility of utilizing the Lamotte and

31

Energy Storage Demonstration Project Locations | Department of...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Demonstration Project Locations Energy Storage Demonstration Project Locations Map of the United States showing the location of Energy Storage Demonstration projects created with...

32

Energy Storage Demonstration Project Locations | Department of...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Energy Storage Demonstration Project Locations Energy Storage Demonstration Project Locations Map of the United States showing the location of Energy Storage Demonstration projects...

33

DoD ESTCP Energy Test Bed Project  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

ESTCP Energy Test Bed Project ESTCP Energy Test Bed Project EW-201016 "High Efficiency - Reduced Emissions Boiler Controls" 23 May 2012 Dr. Jim Galvin ESTCP Program Manager for Energy & Water ESTCP Energy Test Bed Project Location 2 3 Boiler Efficiency Improvement Demo Oxygen Sensor Servo Controls * 90% of boilers lack automated controls * State of the art automated controls sense only oxygen * Demonstrated prototype sensed oxygen and carbon monoxide Prototype CO Sensor Key Findings Boiler Before Demo 4 * Size: 25 MMBtu * Age: 30 years * Fuel: Natural Gas or Oil * Demo performed by United Technologies Research Center * Technology demonstrated: Fireye PPC4000 (Oxygen trim control) * Upgraded PPC4000 tested as a prototype 5 Three Phased Test ● Test Phase 1: Existing Legacy System (baseline)

34

Independent Oversight Review, West Valley Demonstration Project...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Independent Oversight Review, West Valley Demonstration Project Transportation - September 2000 Independent Oversight Review, West Valley Demonstration Project Transportation -...

35

Demonstration Development Project: Oxy-Fired Circulating Fluidized Bed with Carbon Dioxide Capture and Storage at Holland Board of P ublic Works  

Science Conference Proceedings (OSTI)

Oxy-combustion of coal has been proposed as a way of reducing costs of capturing CO2 from coal-fired steam-electric power plants at a purity adequate for geological storage. To date only laboratory and test-stand studies have been conducted, primarily focusing on the combustion process. The next major development step is to field an integrated oxy-coal power plant. Such a project has been proposed and is being developed for deployment at the Holland (MI) Board of Public Works James De Young Power Station...

2009-12-11T23:59:59.000Z

36

Transportable Combustion Turbine Demonstration Project  

Science Conference Proceedings (OSTI)

New York State Electric and Gas Corporation (NYSEG) installed a 7.15-MW Solar Taurus 70 (nominal 7 MW) gas combustion turbine (CT) at its State Street substation in Auburn, New York. As a demonstration project supported through EPRI's Tailored Collaboration (TC) program, it is intended to aid in better understanding the "complete picture" for siting this particular technology as a distributed resource (DR).

2001-12-14T23:59:59.000Z

37

Clean Coal Diesel Demonstration Project  

DOE Green Energy (OSTI)

A Clean Coal Diesel project was undertaken to demonstrate a new Clean Coal Technology that offers technical, economic and environmental advantages over conventional power generating methods. This innovative technology (developed to the prototype stage in an earlier DOE project completed in 1992) enables utilization of pre-processed clean coal fuel in large-bore, medium-speed, diesel engines. The diesel engines are conventional modern engines in many respects, except they are specially fitted with hardened parts to be compatible with the traces of abrasive ash in the coal-slurry fuel. Industrial and Municipal power generating applications in the 10 to 100 megawatt size range are the target applications. There are hundreds of such reciprocating engine power-plants operating throughout the world today on natural gas and/or heavy fuel oil.

Robert Wilson

2006-10-31T23:59:59.000Z

38

The ITER Project: International Collaboration to Demonstrate...  

NLE Websites -- All DOE Office Websites (Extended Search)

ITER Project: International Collaboration to Demonstrate Nuclear Fusion American Fusion News Category: U.S. ITER Link: The ITER Project: International Collaboration to Demonstrate...

39

High-Temperature Superconductivity Cable Demonstration Projects...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

High-Temperature Superconductivity Cable Demonstration Projects High-Temperature Superconductivity Cable Demonstration Projects A National Effort to Introduce New Technology into...

40

Automated Demand Response Technology Demonstration Project for...  

NLE Websites -- All DOE Office Websites (Extended Search)

Demonstration Project for Small and Medium Commercial Buildings Title Automated Demand Response Technology Demonstration Project for Small and Medium Commercial Buildings...

Note: This page contains sample records for the topic "bed demonstration project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


41

Demonstration Project 111 ITS/CVO Technology Truck Final Project...  

NLE Websites -- All DOE Office Websites (Extended Search)

1277 Demonstration Project 111 ITSCVO Technology Truck Final Project Report December 2001 Prepared by G. J. Capps, ORNL Project Manager K. P. Gambrell, Technical Associate K. L....

42

Nuclear waste repository transparency technology test bed demonstrations at WIPP  

SciTech Connect

Secretary of Energy, Bill Richardson, has stated that one of the nuclear waste legacy issues is ``The challenge of managing the fuel cycle's back end and assuring the safe use of nuclear power.'' Waste management (i.e., the back end) is a domestic and international issue that must be addressed. A key tool in gaining acceptance of nuclear waste repository technologies is transparency. Transparency provides information to outside parties for independent assessment of safety, security, and legitimate use of materials. Transparency is a combination of technologies and processes that apply to all elements of the development, operation, and closure of a repository system. A test bed for nuclear repository transparency technologies has been proposed to develop a broad-based set of concepts and strategies for transparency monitoring of nuclear materials at the back end of the fuel/weapons cycle. WIPP is the world's first complete geologic repository system for nuclear materials at the back end of the cycle. While it is understood that WIPP does not currently require this type of transparency, this repository has been proposed as realistic demonstration site to generate and test ideas, methods, and technologies about what transparency may entail at the back end of the nuclear materials cycle, and which could be applicable to other international repository developments. An integrated set of transparency demonstrations was developed and deployed during the summer, and fall of 1999 as a proof-of-concept of the repository transparency technology concept. These demonstrations also provided valuable experience and insight into the implementation of future transparency technology development and application. These demonstrations included: Container Monitoring Rocky Flats to WIPP; Underground Container Monitoring; Real-Time Radiation and Environmental Monitoring; Integrated level of confidence in the system and information provided. As the world's only operating deep geologic repository, the Waste Isolation Pilot Plant (WIPP) offers a unique opportunity to serve as an international cooperative test bed for developing and demonstrating technologies and processes in a fully operational repository system setting. To address the substantial national security implications for the US resulting from the lack of integrated, transparent management and disposition of nuclear materials at the back-end of the nuclear fuel and weapons cycles, it is proposed that WIPP be used as a test bed to develop and demonstrate technologies that will enable the transparent and proliferation-resistant geologic isolation of nuclear materials. The objectives of this initiative are to: (1) enhance public confidence in safe, secure geologic isolation of nuclear materials; (2) develop, test, and demonstrate transparency measures and technologies for the back-end of nuclear fuel cycle; and (3) foster international collaborations leading to workable, effective, globally-accepted standards for the transparent monitoring of geological repositories for nuclear materials. Test-bed activities include: development and testing of monitoring measures and technologies; international demonstration experiments; transparency workshops; visiting scientist exchanges; and educational outreach. These activities are proposed to be managed by the Department of Energy/Carlsbad Area Office (DOE/CAO) as part of The Center for Applied Repository and Underground Studies (CARUS).

BETSILL,J. DAVID; ELKINS,NED Z.; WU,CHUAN-FU; MEWHINNEY,JAMES D.; AAMODT,PAUL

2000-01-27T23:59:59.000Z

43

West Valley Demonstration Project Transportation Emergency Management...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

West Valley Demonstration Project Transportation Emergency Management Program Independent Oversight Review of the Office of Independent Oversight and Performance Assurance...

44

Independent Oversight Review, West Valley Demonstration Project  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Independent Oversight Review, West Valley Demonstration Project Independent Oversight Review, West Valley Demonstration Project Transportation - September 2000 Independent Oversight Review, West Valley Demonstration Project Transportation - September 2000 September 2000 Transportation Emergency Management Review of the West Valley Demonstration Project (WVDP) and National Transportation Program (NTP)/Transportation Compliance Evaluation/Assistance Program (TCEAP) The U.S. Department of Energy (DOE) Office of Emergency Management Oversight, within the Secretary of Energy's Office of Independent Oversight and Performance Assurance, conducted a transportation emergency management review of the West Valley Demonstration Project (WVDP) and National Transportation Program (NTP)/Transportation Compliance Evaluation/Assistance Program (TCEAP) in September 2000.

45

Vehicle to Grid Demonstration Project  

SciTech Connect

This report summarizes the activities and accomplishments of a two-year DOE-funded project on Grid-Integrated Vehicles (GIV) with vehicle to grid power (V2G). The project included several research and development components: an analysis of US driving patterns; an analysis of the market for EVs and V2G-capable EVs; development and testing of GIV components (in-car and in-EVSE); interconnect law and policy; and development and filing of patents. In addition, development activities included GIV manufacturing and licensing of technologies developed under this grant. Also, five vehicles were built and deployed, four for the fleet of the State of Delaware, plus one for the University of Delaware fleet.

Willett Kempton; Meryl Gardner; Michael Hidrue; Fouad Kamilev; Sachin Kamboj; Jon Lilley; Rodney McGee; George Parsons; Nat Pearre; Keith Trnka

2010-12-31T23:59:59.000Z

46

LADWP FUEL CELL DEMONSTRATION PROJECT  

SciTech Connect

Los Angeles Department of Water and Power (LADWP) is currently one of the most active power utility companies in researching fuel cell technology. Fuel cells offer many benefits and are now used as an alternative to traditional internal combustion engines in power generation. In continuing it's role as the leader in fuel cell research, LADWP has installed a pre-commercial molten carbonate fuel cell on August 2001 at its headquarter, the John Ferraro Building (JFB). The goal of this project is to learn more about the actual behavior of the fuel cell running under real world conditions. The fuel cell ran smoothly through the first year of operation with very high efficiency, but with some minor setbacks. The JFB fuel cell project is funded by the City of Los Angeles Department of Water and Power with partial grant funding from the Department of Defense's Climate Change Fuel Cell Buydown Program. The technical evaluation and the benefit-cost evaluation of the JFB fuel cell are both examined in this report.

Thai Ta

2003-09-12T23:59:59.000Z

47

LADWP FUEL CELL DEMONSTRATION PROJECT  

DOE Green Energy (OSTI)

Los Angeles Department of Water and Power (LADWP) is currently one of the most active power utility companies in researching fuel cell technology. Fuel cells offer many benefits and are now used as an alternative to traditional internal combustion engines in power generation. In continuing it's role as the leader in fuel cell research, LADWP has installed a pre-commercial molten carbonate fuel cell on August 2001 at its headquarter, the John Ferraro Building (JFB). The goal of this project is to learn more about the actual behavior of the fuel cell running under real world conditions. The fuel cell ran smoothly through the first year of operation with very high efficiency, but with some minor setbacks. The JFB fuel cell project is funded by the City of Los Angeles Department of Water and Power with partial grant funding from the Department of Defense's Climate Change Fuel Cell Buydown Program. The technical evaluation and the benefit-cost evaluation of the JFB fuel cell are both examined in this report.

Thai Ta

2003-09-12T23:59:59.000Z

48

Navy fuel cell demonstration project.  

DOE Green Energy (OSTI)

This is the final report on a field evaluation by the Department of the Navy of twenty 5-kW PEM fuel cells carried out during 2004 and 2005 at five Navy sites located in New York, California, and Hawaii. The key objective of the effort was to obtain an engineering assessment of their military applications. Particular issues of interest were fuel cell cost, performance, reliability, and the readiness of commercial fuel cells for use as a standalone (grid-independent) power option. Two corollary objectives of the demonstration were to promote technological advances and to improve fuel performance and reliability. From a cost perspective, the capital cost of PEM fuel cells at this stage of their development is high compared to other power generation technologies. Sandia National Laboratories technical recommendation to the Navy is to remain involved in evaluating successive generations of this technology, particularly in locations with greater environmental extremes, and it encourages their increased use by the Navy.

Black, Billy D.; Akhil, Abbas Ali

2008-08-01T23:59:59.000Z

49

Independent Activity Report, West Valley Demonstration Project...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

West Valley Demonstration Project - July 2012 Independent Activity Report, New Brunswick Laboratory - November 2011 Orientation Visit to the Paducah Gaseous Diffusion Plant,...

50

CERTS Microgrid Laboratory Test Bed - PIER Final Project Report  

Science Conference Proceedings (OSTI)

The objective of the CERTS Microgrid Laboratory Test Bed project was to enhance the ease of integrating small energy sources into a microgrid. The project accomplished this objective by developing and demonstrating three advanced techniques, collectively referred to as the CERTS Microgrid concept, that significantly reduce the level of custom field engineering needed to operate microgrids consisting of small generating sources. The techniques comprising the CERTS Microgrid concept are: 1) a method for effecting automatic and seamless transitions between grid-connected and islanded modes of operation; 2) an approach to electrical protection within the microgrid that does not depend on high fault currents; and 3) a method for microgrid control that achieves voltage and frequency stability under islanded conditions without requiring high-speed communications. The techniques were demonstrated at a full-scale test bed built near Columbus, Ohio and operated by American Electric Power. The testing fully confirmed earlier research that had been conducted initially through analytical simulations, then through laboratory emulations, and finally through factory acceptance testing of individual microgrid components. The islanding and resychronization method met all Institute of Electrical and Electronics Engineers 1547 and power quality requirements. The electrical protections system was able to distinguish between normal and faulted operation. The controls were found to be robust and under all conditions, including difficult motor starts. The results from these test are expected to lead to additional testing of enhancements to the basic techniques at the test bed to improve the business case for microgrid technologies, as well to field demonstrations involving microgrids that involve one or mroe of the CERTS Microgrid concepts.

Eto, Joseph H.; Eto, Joseph H.; Lasseter, Robert; Schenkman, Ben; Klapp, Dave; Linton, Ed; Hurtado, Hector; Roy, Jean; Lewis, Nancy Jo; Stevens, John; Volkommer, Harry

2008-07-25T23:59:59.000Z

51

Categorical Exclusion Determinations: West Valley Demonstration Project |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Valley Demonstration Valley Demonstration Project Categorical Exclusion Determinations: West Valley Demonstration Project Categorical Exclusion Determinations issued by West Valley Demonstration Project. DOCUMENTS AVAILABLE FOR DOWNLOAD July 11, 2013 CX-010718: Categorical Exclusion Determination Replacement Ventilation System for the Main Plant Process Building CX(s) Applied: B6.3 Date: 07/11/2013 Location(s): New York Offices(s): West Valley Demonstration Project December 20, 2012 CX-009527: Categorical Exclusion Determination WVDP-2012-02 Routine Maintenance CX(s) Applied: B1.3 Date: 12/20/2012 Location(s): New York Offices(s): West Valley Demonstration Project August 2, 2012 CX-009528: Categorical Exclusion Determination WVDP-2012-01 WVDP Reservoir Interconnecting Canal Maintenance Activities

52

Milestone Project Demonstrates Innovative Mercury Emissions Reduction  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Milestone Project Demonstrates Innovative Mercury Emissions Milestone Project Demonstrates Innovative Mercury Emissions Reduction Technology Milestone Project Demonstrates Innovative Mercury Emissions Reduction Technology January 12, 2010 - 12:00pm Addthis Washington, DC - An innovative technology that could potentially help some coal-based power generation facilities comply with anticipated new mercury emissions standards was successfully demonstrated in a recently concluded milestone project at a Michigan power plant. Under a cooperative agreement with the U.S. Department of Energy's (DOE's) National Energy Technology Laboratory (NETL), WE Energies demonstrated the TOXECON(TM) process in a $52.9million project at the Presque Isle Power Plant in Marquette, Mich. TOXECON is a relatively cost-effective option for achieving significant reductions in mercury emissions and increasing the

53

Tidd PFBC Demonstration Project, A DOE Assessment  

Science Conference Proceedings (OSTI)

The Clean Coal Technology (CCT) Demonstration Program is a government and industry co-funded technology development effort to demonstrate a new generation of innovative coal utilization processes. One goal of the program is to furnish the energy marketplace with a variety of energy efficient, environmentally superior coal-based technologies. Demonstration projects seek to establish the commercial feasibility of the most promising coal technologies that have proceeded beyond the proof-of-concept stage. This report is a post-project assessment of the DOE CCT Demonstration Program, the Tidd PFBC Demonstration Project. A major objective of the CCT Program is to provide the technical data necessary for the private sector to proceed confidently with the commercial replication of the demonstrated technologies. An essential element of meeting this goal is the dissemination of results from the demonstration projects. This post-project assessment (PPA) report is an independent DOE appraisal of the successes that the completed project had in achieving its objectives and aiding in the commercialization of the demonstrated technology. The report also provides an assessment of the expected technical, environmental, and economic performance of the commercial version of the technology, as well as an analysis of the commercial market.

National Energy Technology Laboratory

2001-08-31T23:59:59.000Z

54

Power Plant Optimization Demonstration Projects Cover Photos:  

NLE Websites -- All DOE Office Websites (Extended Search)

5 SEPTEMBER 2007 5 SEPTEMBER 2007 Power Plant Optimization Demonstration Projects Cover Photos: * Top left: Coal Creek Station * Top right: Big Bend Power Station * Bottom left: Baldwin Energy Complex * Bottom right: Limestone Power Plant A report on four projects conducted under separate cooperative agreements between the U.S. Department of Energy and: * Great River Energy * Tampa Electric Company * Pegasus Technologies * NeuCo. , Inc.  Power Plant Optimization Demonstration Projects Executive Summary .......................................................................................4 Background: Power Plant Optimization ......................................................5 Lignite Fuel Enhancement Project ...............................................................8

55

Hampton Roads Demonstration Project | Open Energy Information  

Open Energy Info (EERE)

Roads Demonstration Project Roads Demonstration Project Jump to: navigation, search Name Hampton Roads Demonstration Project Facility Hampton Roads Demonstration Project Sector Wind energy Facility Type Offshore Wind Facility Status Proposed Developer Virginia State Government Location Chesapeake Bay VA Coordinates 36.965°, -76.289° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[{"text":"","title":"","link":null,"lat":36.965,"lon":-76.289,"alt":0,"address":"","icon":"","group":"","inlineLabel":"","visitedicon":""}]}

56

Grays Harbor Demonstration Project | Open Energy Information  

Open Energy Info (EERE)

Demonstration Project Demonstration Project Jump to: navigation, search Name Grays Harbor Demonstration Project Facility Grays Harbor Demonstration Project Sector Wind energy Facility Type Offshore Wind Facility Status Proposed Owner Grays Harbor Ocean Energy Company LLC Developer Grays Harbor Ocean Energy Company LLC Location Pacific Ocean Coordinates 46.858°, -124.187° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[{"text":"","title":"","link":null,"lat":46.858,"lon":-124.187,"alt":0,"address":"","icon":"","group":"","inlineLabel":"","visitedicon":""}]}

57

NETL: News Release - Milestone Project Demonstrates Innovative...  

NLE Websites -- All DOE Office Websites (Extended Search)

the U.S. Department of Energy's (DOE's) National Energy Technology Laboratory (NETL), WE Energies demonstrated the TOXECON(TM) process in a 52.9million project at the Presque...

58

Smart Grid Demonstration Project Locations | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Smart Grid Demonstration Project Locations Smart Grid Demonstration Project Locations Map of the United States showing the location of Smart Grid Demonstration projects created...

59

LIMB Demonstration Project Extension and Coolside Demonstration. [Final report  

SciTech Connect

This report presents results from the limestone Injection Multistage Burner (LIMB) Demonstration Project Extension. LIMB is a furnace sorbent injection technology designed for the reduction of sulfur dioxide (SO{sub 2}) and nitrogen oxides (NO{sub x}) emissions from coal-fired utility boilers. The testing was conducted on the 105 Mwe, coal-fired, Unit 4 boiler at Ohio Edison`s Edgewater Station in Lorain, Ohio. In addition to the LIMB Extension activities, the overall project included demonstration of the Coolside process for S0{sub 2} removal for which a separate report has been issued. The primary purpose of the DOE LIMB Extension testing, was to demonstrate the generic applicability of LIMB technology. The program sought to characterize the S0{sub 2} emissions that result when various calcium-based sorbents are injected into the furnace, while burning coals having sulfur content ranging from 1.6 to 3.8 weight percent. The four sorbents used included calcitic limestone, dolomitic hydrated lime, calcitic hydrated lime, and calcitic hydrated lime with a small amount of added calcium lignosulfonate. The results include those obtained for the various coal/sorbent combinations and the effects of the LIMB process on boiler and plant operations.

Goots, T.R.; DePero, M.J.; Nolan, P.S.

1992-11-10T23:59:59.000Z

60

3M's Motor Challenge Showcase Demonstration Project  

E-Print Network (OSTI)

In January 1994, 3M began the task of optimizing the electric motor systems at 3M Center, a 26 building, 7 million square foot corporate campus. A cross-functional, cross-company team was established which included four 3M employees representing two different departments within 3M, an engineer specializing in demand side management programs from Northern States Power Company, and a sales engineer from General Electric Supply Company. The team was later joined by an engineering specialist from Landis & Staefa, Inc., a building automation controls supplier. The team began the task of identifying the projects that could save energy and provide a reasonable return on 3M's investment on a building by building approach. As surveys were completed, proposals were prepared and presented to management requesting funding. The team continued the process of identifying projects in remaining buildings and took on the responsibility of designing, contracting and implementing projects as funding was approved for those already studied. Follow-up measurements to ascertain that the savings predicted was actually achieved are done before project close-out. This project was submitted and accepted as a Motor Challenge Showcase Demonstration Project. The Motor Challenge is a U.S. Department of Energy initiative to promote the efficient use of energy in electric motor systems. Showcase Demonstration Projects are used to exemplify the benefits that motor system optimization can provide. This Showcase Project is different from most as it emphasizes the process that was developed to carry out a project of this magnitude rather than any single specific technologies or applications. The team has completed the project at 3M Center. Measured savings are $823,000 per year. This paper will discuss the Motor Challenge Showcase Demonstration project that was completed at 3M Center, the motor systems survey methodology the team developed, analysis tools and techniques and the results that have been attained.

Schultz, S. C.

1998-04-01T23:59:59.000Z

Note: This page contains sample records for the topic "bed demonstration project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


61

3M's Motor Challenge Showcase Demonstration Project  

E-Print Network (OSTI)

In January 1994, 3M began the task of optimizing the electric motor systems at 3M Center, a 26 building, 7 million square foot corporate campus. A cross-functional, cross-company team was established which included four 3M employees representing two different departments within 3M, an engineer specializing in demand side management programs from Northern States Power Company, and a sales engineer from General Electric Supply Company. The team was later joined by an engineering specialist from Landis & Gyr, Inc., a building automation controls supplier. The team began the task of identifying the projects that could save energy and provide a reasonable return on 3M's investment on a building by building approach. As surveys were completed, proposals were prepared and presented to management requesting funding. The team continued the process of identifying projects in remaining buildings and took on the responsibility of designing, contracting and implementing projects as funding was approved for those already studied. Follow-up measurements to ascertain that the savings predicted was actually achieved are done before project close-out. This project was submitted and has been accepted as a Motor Challenge Showcase Demonstration Project. The Motor Challenge is a U. S. Department of Energy initiative to promote the efficient use of energy in electric motor systems. Showcase Demonstration Projects are used to exemplify the benefits that motor system optimization can provide. This Showcase Project is different from most as it emphasizes the process that was developed to carry out a project of this magnitude rather than any single specific technologies or applications. The team has nearly completed the studies at 3M Center and is well into the implementation phase with six buildings being complete. Savings identified to date are approximately $810,000 per year. This paper will discuss the Motor Challenge Showcase Demonstration project currently underway at 3M Center, the motor systems survey methodology the team developed, analysis tools and techniques and the results that have been attained.

Schultz, S. C.

1996-04-01T23:59:59.000Z

62

York County Energy Partners DOE CCI ACFB demonstration project  

Science Conference Proceedings (OSTI)

The York County Energy Partners (YCEP) project, to be located in York County, Pennsylvania, will demonstrate the world`s largest atmospheric circulating fluidized bed boiler under sponsorship of the US Department of Energy`s Clean Coal Technology I Program. The single ACFB boiler, designed by Foster Wheeler Energy Corporation, will produce 227 MWe of net electrical power and export approximately 50,000 lb/hr of steam. This paper explains how the technical challenges to the design of a utility-scale ACFB boiler were met and presents the innovative features of this design.

Wang, S. [Air Products and Chemicals, Inc., Allentown, PA (United States); Cox, J.; Parham, D. [Foster Wheeler Energy Corp., Clinton, NJ (United States)

1992-09-01T23:59:59.000Z

63

York County Energy Partners DOE CCI ACFB demonstration project  

Science Conference Proceedings (OSTI)

The York County Energy Partners (YCEP) project, to be located in York County, Pennsylvania, will demonstrate the world's largest atmospheric circulating fluidized bed boiler under sponsorship of the US Department of Energy's Clean Coal Technology I Program. The single ACFB boiler, designed by Foster Wheeler Energy Corporation, will produce 227 MWe of net electrical power and export approximately 50,000 lb/hr of steam. This paper explains how the technical challenges to the design of a utility-scale ACFB boiler were met and presents the innovative features of this design.

Wang, S. (Air Products and Chemicals, Inc., Allentown, PA (United States)); Cox, J.; Parham, D. (Foster Wheeler Energy Corp., Clinton, NJ (United States))

1992-01-01T23:59:59.000Z

64

Western Greenbrier Co-Production Demonstration Project  

NLE Websites -- All DOE Office Websites (Extended Search)

contacts contacts Brad tomer Director Office of Major Demonstrations National Energy Technology Laboratory 3610 Collins Ferry Road P.O. Box 880 Morgantown, WV 26507-0880 304-285-4692 brad.tomer@netl.doe.gov nelson Rekos Project Manager National Energy Technology Laboratory 3610 Collins Ferry Road P.O. Box 880 Morgantown, WV 26507-0880 304-285-4066 nelson.rekos@netl.doe.gov PaRtIcIPant Western Greenbrier Co-Generation, LLC Lewisburg, WV Western Greenbrier Co-ProduCtion demonstration ProjeCt (disContinued) Project Description The Western Greenbrier Co-Production (WGC) project will generate about 100 megawatts of electricity and commercial quantities of salable ash by-products by burning waste coal presently contained in numerous coal refuse dumps in the vicinity of the plant. These refuse dumps, created by coal cleaning operations over

65

Pecan Street Project, Inc. Smart Grid Demonstration Project | Open Energy  

Open Energy Info (EERE)

Project, Inc. Smart Grid Demonstration Project Project, Inc. Smart Grid Demonstration Project Jump to: navigation, search Project Lead Pecan Street Project, Inc. Country United States Headquarters Location Austin, Texas Recovery Act Funding $10,403,570.00 Total Project Value $24,656,485.00 Coordinates 30.267153°, -97.7430608° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[]}

66

Advanced Coal Conversion Process Demonstration (Project)  

DOE Green Energy (OSTI)

This report contains a description of technical progress made on the Advanced Coal Conversion Process Demonstration Project (ACCP). The project is a US Department of Energy Innovative Clean Coal Technology Project. The cooperative agreement defining the project is between DOE and the Rosebud SynCoal Partnership RSCP. The RSCP is a partnership between Western Energy Company (WECo), a subsidiary of Entech, Montana Power's non-utility group, and NRG, a subsidiary of Northern States Power. The ACCP is a method of upgrading low ranked coals by reducing the moisture and sulfur content and increasing the heating value. The facility is being constructed at WECo's Rosebud No. 6 coal mine, west of Colstrip, Montana. This report contains both a history of the process development and a report of technical progress made since the beginning of the Clean Coal 1 cooperative agreement.

Not Available

1991-07-01T23:59:59.000Z

67

CALDERON COKEMAKING PROCESS/DEMONSTRATION PROJECT  

Science Conference Proceedings (OSTI)

This project deals with the demonstration of a coking process using proprietary technology of Calderon, with the following objectives geared to facilitate commercialization: (1) making coke of such quality as to be suitable for use in hard-driving, large blast furnaces; (2) providing proof that such process is continuous and environmentally closed to prevent emissions; (3) demonstrating that high-coking-pressure (non-traditional) coal blends which cannot be safely charged into conventional by-product coke ovens can be used in the Calderon process; (4) conducting a blast furnace test to demonstrate the compatibility of the coke produced; and (5) demonstrating that coke can be produced economically, at a level competitive with coke imports. The activities of the past quarter were focused on the following: Detailed studies of LTV's site for the installation of the commercial Demonstration Unit with site specific layouts; Environmental Work; Firm commitments for funding from the private sector; and Federal funding to complement the private contribution.

Albert Calderon

1999-06-23T23:59:59.000Z

68

Category:Smart Grid Projects - Regional Demonstrations | Open Energy  

Open Energy Info (EERE)

Demonstrations Demonstrations Jump to: navigation, search Smart Grid Regional Demonstrations Projects category. Pages in category "Smart Grid Projects - Regional Demonstrations" The following 16 pages are in this category, out of 16 total. B Battelle Memorial Institute, Pacific Northwest Division Smart Grid Demonstration Project C Center for the Commercialization of Electric Technologies Smart Grid Demonstration Project Columbus Southern Power Company (doing business as AEP Ohio) Smart Grid Demonstration Project Consolidated Edison Company of New York, Inc. Smart Grid Demonstration Project K Kansas City Power & Light Company Smart Grid Demonstration Project L Long Island Power Authority Smart Grid Demonstration Project L cont. Los Angeles Department of Water and Power Smart Grid Demonstration Project

69

Demonstration Development Project: Large-Scale Post-Combustion CO2 Capture Retrofit Demonstration Project Review  

Science Conference Proceedings (OSTI)

The Electric Power Research Institute (EPRI) has reviewed proposed demonstration sites for retrofitting post-combustion CO2 capture onto an existing coal-fired plant. This report discusses and reviews this set of demonstration projects to provide background information and the rationale for EPRI to pursue being involved in one or more of these projects.

2010-12-17T23:59:59.000Z

70

Duke Energy Notrees Wind Storage Demonstration Project  

Science Conference Proceedings (OSTI)

This EPRI technical update is an interim report summarizing the status of Duke Energys Notrees Wind Storage Demonstration Project, which involves integrating a 36-MW battery energy storage system (BESS) from Xtreme Power with the 152.6-MW Notrees Wind Farm. Xtreme Powers solid lead-acid battery represents one of an emerging number of energy storage devices endowed with the potential to serve multiple ...

2012-12-12T23:59:59.000Z

71

All-Electric Wendy's Restaurant Demonstration Project  

Science Conference Proceedings (OSTI)

How well can the power needs of a small restaurant be met by an all-electric solution? This demonstration project at a fast-food restaurant investigated the energy and economic performance of a suite of high-efficiency electro-technologies including an all-electric cookline; high efficiency lighting; and heat pumps for water heating, space heating, and cooling. The all-electric concept proved to be competitive with the more conventional gas/electric model.

1999-09-16T23:59:59.000Z

72

Session 9: Heber Geothermal Binary Demonstration Project  

DOE Green Energy (OSTI)

The Heber Binary Project had its beginning in studies performed for the Electric Power Research Institute (EPRI), which identified the need for commercial scale (50 Mw or larger) demonstration of the binary cycle technology. In late 1980, SDG&E and the Department of Energy (DOE) signed a Cooperative Agreement calling for DOE to share in 50 percent of the Project costs. Similarly, SDG&E signed Project participation agreements with EPRI, the Imperial Irrigation District, California Department of Water Resources, and Southern California Edison Company, which provided the remaining 50 percent of the required funding. In 1982, the State of California also joined the Project. The objectives of the Heber Binary Project are to demonstrate the potential of moderate-temperature (below 410 F) geothermal energy to produce economic electric power with binary cycle conversion technology, and to establish schedule, cost and equipment performance, reservoir performance, and the environmental acceptability of such plants. The plant will be the first large-scale power generating facility in the world utilizing the binary conversion process, and it is expected that information resulting from this Project will be applicable to a wide range of moderate-temperature hydrothermal reservoirs, which represent 80 percent of geothermal resources in the United States. To accomplish the plant engineering, design, and equipment procurement, SDG&E has hired Fluor Engineers, Inc., Power Division, of Irvine, California. In early 1982, SDG&E contracted for construction management services with Dravo Constructors, Inc. (DCI) of New York. DCI is responsible for casting the Fluor design into construction packages, letting the construction contracts, and overseeing the construction in the field.

Allen, Richard F.; Nelson, Tiffany T.

1983-12-01T23:59:59.000Z

73

Demonstration project Smart Charging (Smart Grid Project) | Open Energy  

Open Energy Info (EERE)

project Smart Charging (Smart Grid Project) project Smart Charging (Smart Grid Project) Jump to: navigation, search Project Name Demonstration project Smart Charging Country Netherlands Headquarters Location Noord-Brabant, Netherlands Coordinates 51.482655°, 5.232169° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[{"text":"","title":"","link":null,"lat":51.482655,"lon":5.232169,"alt":0,"address":"","icon":"","group":"","inlineLabel":"","visitedicon":""}]}

74

Heat Pump Water Heaters Demonstration Project  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Heat Pump Water Heaters Heat Pump Water Heaters Demonstration Project Building America Stakeholder Meeting Ron Domitrovic Ammi Amarnath 3/1/2012 Austin, TX 2 © 2011 Electric Power Research Institute, Inc. All rights reserved. HPWH Field Demonstration: Research Objectives * Assess heat pump water heater technology by measuring efficiency. * Provide credible data on the performance and reliability of heat pump water heaters. * Assess user satisfaction in a residential setting. 3 © 2011 Electric Power Research Institute, Inc. All rights reserved. Demonstration Host Utilities Target: 40 Units per Utility Installed and Potential Sites by Climate Zone Source: Department of Energy (DOE), Building America climate regions 4 © 2011 Electric Power Research Institute, Inc. All rights reserved. Installation Locations-Southern Company Region

75

Newberry EGS Demonstration Project Environmental Analysis (EA)  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Newberry Volcano Enhanced Geothermal System (EGS) Demonstration Project UNITED STATES DEPARTMENT OF THE INTERIOR BUREAU OF LAND MANAGEMENT (BLM) DOI-BLM-OR-P000-2011-0003-EA DOE/EA-1897 ENVIRONMENTAL ASSESSMENT DECEMBER 2011 Location: Federal Geothermal Leases on the West Flank of Newberry Volcano, Deschutes County, 22 miles south of Bend, Oregon Applicant: Davenport Newberry Holdings LLC and AltaRock Energy, Inc. 225 NW Franklin Avenue, Suite 1 Bend, OR 97701 Tel: 541-323-1190 Lead Agency: U.S. Department of the Interior,

76

CALDERON COKEMAKING PROCESS/DEMONSTRATION PROJECT  

Science Conference Proceedings (OSTI)

This project deals with the demonstration of a coking reactor (Process Development Unit-- PDU-11) using Calderon's proprietary technology for making commercially acceptable coke. The activities of the past quarter were focused on the following: 1. Testing and Designing of the Submerged Quenching Closed System for the Process; 2. Usage of the Cracked Desulfurized Gas as a Reducing Gas to Make Directly Reduced Iron (DRI) in Order to Make the Process Economics Viable; 3. Changes in the Ceramic Liners for Supporting Them in the Coking Reactor; 4. Work Towards Testing of U.S. Steel's Coal in the Existing Process Development Unit in Alliance (PDU-1); 5. Permitting.

Albert Calderon

1998-04-08T23:59:59.000Z

77

Landfill Gas-to-Electricity Demonstration Project  

DOE Green Energy (OSTI)

Medium Btu methane gas is a naturally occurring byproduct of anaerobic digestion of landfilled municipal solid waste. The energy potential of landfill gas in New York State is estimated to be 61 trillion Btu's per year or the equivalent of 10% of the natural gas used annually in the state. The 18-month Landfill Gas-to-Electricity Demonstration Project conducted at the Fresh Kills Landfill in Staten Island, New York conclusively demonstrated that landfill gas is an acceptable fuel for producing electricity using an internal combustion engine/generator set. Landfill gas proved to be a reliable and consistent fuel source during a six-month field test program. Engine exhaust emissions were determined to be comparable to that of natural gas and no unusually high corrosion rates on standard pipeline material were found.

Not Available

1982-10-01T23:59:59.000Z

78

Category:Smart Grid Projects - Energy Storage Demonstrations | Open Energy  

Open Energy Info (EERE)

Energy Storage Demonstrations Energy Storage Demonstrations Jump to: navigation, search Smart Grid Energy Storage Demonstration Projects category. Pages in category "Smart Grid Projects - Energy Storage Demonstrations" The following 16 pages are in this category, out of 16 total. 4 44 Tech Inc. Smart Grid Demonstration Project A Amber Kinetics, Inc. Smart Grid Demonstration Project B Beacon Power Corporation Smart Grid Demonstration Project C City of Painesville Smart Grid Demonstration Project D Duke Energy Business Services, LLC Smart Grid Demonstration Project E East Penn Manufacturing Co. Smart Grid Demonstration Project K Ktech Corporation Smart Grid Demonstration Project N New York State Electric & Gas Corporation Smart Grid Demonstration Project P Pacific Gas & Electric Company Smart Grid Demonstration Project

79

Brown Grease to Biodiesel Demonstration Project Report  

Science Conference Proceedings (OSTI)

Municipal wastewater treatment facilities have typically been limited to the role of accepting wastewater, treating it to required levels, and disposing of its treatment residuals. However, a new view is emerging which includes wastewater treatment facilities as regional resource recovery centers. This view is a direct result of increasingly stringent regulations, concerns over energy use, carbon footprint, and worldwide depletion of fossil fuel resources. Resources in wastewater include chemical and thermal energy, as well as nutrients, and water. A waste stream such as residual grease, which concentrates in the drainage from restaurants (referred to as Trap Waste), is a good example of a resource with an energy content that can be recovered for beneficial reuse. If left in wastewater, grease accumulates inside of the wastewater collection system and can lead to increased corrosion and pipe blockages that can cause wastewater overflows. Also, grease in wastewater that arrives at the treatment facility can impair the operation of preliminary treatment equipment and is only partly removed in the primary treatment process. In addition, residual grease increases the demand in treatment materials such as oxygen in the secondary treatment process. When disposed of in landfills, grease is likely to undergo anaerobic decay prior to landfill capping, resulting in the atmospheric release of methane, a greenhouse gas (GHG). This research project was therefore conceptualized and implemented by the San Francisco Public Utilities Commission (SFPUC) to test the feasibility of energy recovery from Trap Waste in the form of Biodiesel or Methane gas. The research goals are given below: ?¢???¢ To validate technology performance; ?¢???¢ To determine the costs and benefits [including economic, socioeconomic, and GHG emissions reduction] associated with co-locating this type of operation at a municipal wastewater treatment plant (WWTP); ?¢???¢ To develop a business case or model for replication of the program by other municipal agencies (as applicable). In order to accomplish the goals of the project, the following steps were performed: 1. Operation of a demonstration facility designed to receive 10,000 to 12,000 gallons of raw Trap Waste each day from private Trap Waste hauling companies. The demonstration facility was designed and built by Pacific Biodiesel Technologies (PBTech). The demonstration facility would also recover 300 gallons of Brown Grease per day from the raw Trap Waste. The recovered Brown Grease was expected to contain no more than 2% Moisture, Insolubles, and Unsaponifiables (MIU) combined. 2. Co-digestion of the side streams (generated during the recovery of 300 gallons of Brown Grease from the raw Trap Waste) with wastewater sludge in the WWTP?¢????s anaerobic digesters. The effects of the side streams on anaerobic digestion were quantified by comparison with baseline data. 3. Production of 240 gallons per day of ASTM D6751-S15 grade Biodiesel fuel via a Biodiesel conversion demonstration facility, with the use of recovered Brown Grease as a feedstock. The demonstration facility was designed and built by Blackgold Biofuels (BGB). Side streams from this process were also co-digested with wastewater sludge. Bench-scale anaerobic digestion testing was conducted on side streams from both demonstration facilities to determine potential toxicity and/or changes in biogas production in the WWTP anaerobic digester. While there is a lot of theoretical data available on the lab-scale production of Biodiesel from grease Trap Waste, this full-scale demonstration project was one of the first of its kind in the United States. The project?¢????s environmental impacts were expected to include: ?¢???¢ Reduction of greenhouse gas emissions by prevention of the release of methane at landfills. Although the combustion product of Biod

San Francisco Public Utilities Commission; URS Corporation; Biofuels, Blackgold; Carollo Engineers

2013-01-30T23:59:59.000Z

80

MHK Projects/Pulse Stream 100 Demonstration Project | Open Energy  

Open Energy Info (EERE)

Pulse Stream 100 Demonstration Project Pulse Stream 100 Demonstration Project < MHK Projects Jump to: navigation, search << Return to the MHK database homepage Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":5,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"500px","height":"350px","centre":false,"title":"","label":"","icon":"File:Aquamarine-marker.png","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[{"text":"","title":"","link":null,"lat":53.6405,"lon":-0.16257,"alt":0,"address":"","icon":"http:\/\/prod-http-80-800498448.us-east-1.elb.amazonaws.com\/w\/images\/7\/74\/Aquamarine-marker.png","group":"","inlineLabel":"","visitedicon":""}]}

Note: This page contains sample records for the topic "bed demonstration project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


81

The Southern California Conversion Technology Demonstration Project | Open  

Open Energy Info (EERE)

The Southern California Conversion Technology Demonstration Project The Southern California Conversion Technology Demonstration Project Jump to: navigation, search Tool Summary Name: The Southern California Conversion Technology Demonstration Project Agency/Company /Organization: The Southern California Conversion Technology Demonstration Project Sector: Energy, Land Focus Area: - Waste to Energy Phase: Create a Vision Resource Type: Publications User Interface: Website Website: www.socalconversion.org/resources.html Cost: Free The Southern California Conversion Technology Demonstration Project website is focused on a specific conversion technology demonstration project in L. A. County. Overview The Southern California Conversion Technology Demonstration Project website is focused on a specific conversion technology demonstration project in L.

82

Property:Did The Test Results Demonstrate Projected Performance...  

Open Energy Info (EERE)

Did The Test Results Demonstrate Projected Performance? Jump to: navigation, search Property Name Did The Test Results Demonstrate Projected Performance? Property Type Text...

83

DOE Funds 21 Research, Development and Demonstration Projects...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Development and Demonstration Projects for up to 78 Million to Promote Enhanced Geothermal Systems DOE Funds 21 Research, Development and Demonstration Projects for up to 78...

84

Smart Grid Regional and Energy Storage Demonstration Projects...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Regional and Energy Storage Demonstration Projects: Awards Smart Grid Regional and Energy Storage Demonstration Projects: Awards List of Smart Grid Regional and Energy Storage...

85

Controlled Hydrogen Fleet and Infrastructure Demonstration Project  

DOE Green Energy (OSTI)

This program was undertaken in response to the US Department of Energy Solicitation DE-PS30-03GO93010, resulting in this Cooperative Agreement with the Ford Motor Company and BP to demonstrate and evaluate hydrogen fuel cell vehicles and required fueling infrastructure. Ford initially placed 18 hydrogen fuel cell vehicles (FCV) in three geographic regions of the US (Sacramento, CA; Orlando, FL; and southeast Michigan). Subsequently, 8 advanced technology vehicles were developed and evaluated by the Ford engineering team in Michigan. BP is Ford's principal partner and co-applicant on this project and provided the hydrogen infrastructure to support the fuel cell vehicles. BP ultimately provided three new fueling stations. The Ford-BP program consists of two overlapping phases. The deliverables of this project, combined with those of other industry consortia, are to be used to provide critical input to hydrogen economy commercialization decisions by 2015. The program's goal is to support industry efforts of the US President's Hydrogen Fuel Initiative in developing a path to a hydrogen economy. This program was designed to seek complete systems solutions to address hydrogen infrastructure and vehicle development, and possible synergies between hydrogen fuel electricity generation and transportation applications. This project, in support of that national goal, was designed to gain real world experience with Hydrogen powered Fuel Cell Vehicles (H2FCV) 'on the road' used in everyday activities, and further, to begin the development of the required supporting H2 infrastructure. Implementation of a new hydrogen vehicle technology is, as expected, complex because of the need for parallel introduction of a viable, available fuel delivery system and sufficient numbers of vehicles to buy fuel to justify expansion of the fueling infrastructure. Viability of the fuel structure means widespread, affordable hydrogen which can return a reasonable profit to the fuel provider, while viability of the vehicle requires an expected level of cost, comfort, safety and operation, especially driving range, that consumers require. This presents a classic 'chicken and egg' problem, which Ford believes can be solved with thoughtful implementation plans. The eighteen Ford Focus FCV vehicles that were operated for this demonstration project provided the desired real world experience. Some things worked better than expected. Most notable was the robustness and life of the fuel cell. This is thought to be the result of the full hybrid configuration of the drive system where the battery helps to overcome the performance reduction associated with time related fuel cell degradation. In addition, customer satisfaction surveys indicated that people like the cars and the concept and operated them with little hesitation. Although the demonstrated range of the cars was near 200 miles, operators felt constrained because of the lack of a number of conveniently located fueling stations. Overcoming this major concern requires overcoming a key roadblock, fuel storage, in a manner that permits sufficient quantity of fuel without sacrificing passenger or cargo capability. Fueling infrastructure, on the other hand, has been problematic. Only three of a planned seven stations were opened. The difficulty in obtaining public approval and local government support for hydrogen fuel, based largely on the fear of hydrogen that grew from past disasters and atomic weaponry, has inhibited progress and presents a major roadblock to implementation. In addition the cost of hydrogen production, in any of the methodologies used in this program, does not show a rapid reduction to commercially viable rates. On the positive side of this issue was the demonstrated safety of the fueling station, equipment and process. In the Ford program, there were no reported safety incidents.

Dr. Scott Staley

2010-03-31T23:59:59.000Z

86

Controlled Hydrogen Fleet and Infrastructure Demonstration Project  

SciTech Connect

This program was undertaken in response to the US Department of Energy Solicitation DE-PS30-03GO93010, resulting in this Cooperative Agreement with the Ford Motor Company and BP to demonstrate and evaluate hydrogen fuel cell vehicles and required fueling infrastructure. Ford initially placed 18 hydrogen fuel cell vehicles (FCV) in three geographic regions of the US (Sacramento, CA; Orlando, FL; and southeast Michigan). Subsequently, 8 advanced technology vehicles were developed and evaluated by the Ford engineering team in Michigan. BP is Ford's principal partner and co-applicant on this project and provided the hydrogen infrastructure to support the fuel cell vehicles. BP ultimately provided three new fueling stations. The Ford-BP program consists of two overlapping phases. The deliverables of this project, combined with those of other industry consortia, are to be used to provide critical input to hydrogen economy commercialization decisions by 2015. The program's goal is to support industry efforts of the US President's Hydrogen Fuel Initiative in developing a path to a hydrogen economy. This program was designed to seek complete systems solutions to address hydrogen infrastructure and vehicle development, and possible synergies between hydrogen fuel electricity generation and transportation applications. This project, in support of that national goal, was designed to gain real world experience with Hydrogen powered Fuel Cell Vehicles (H2FCV) 'on the road' used in everyday activities, and further, to begin the development of the required supporting H2 infrastructure. Implementation of a new hydrogen vehicle technology is, as expected, complex because of the need for parallel introduction of a viable, available fuel delivery system and sufficient numbers of vehicles to buy fuel to justify expansion of the fueling infrastructure. Viability of the fuel structure means widespread, affordable hydrogen which can return a reasonable profit to the fuel provider, while viability of the vehicle requires an expected level of cost, comfort, safety and operation, especially driving range, that consumers require. This presents a classic 'chicken and egg' problem, which Ford believes can be solved with thoughtful implementation plans. The eighteen Ford Focus FCV vehicles that were operated for this demonstration project provided the desired real world experience. Some things worked better than expected. Most notable was the robustness and life of the fuel cell. This is thought to be the result of the full hybrid configuration of the drive system where the battery helps to overcome the performance reduction associated with time related fuel cell degradation. In addition, customer satisfaction surveys indicated that people like the cars and the concept and operated them with little hesitation. Although the demonstrated range of the cars was near 200 miles, operators felt constrained because of the lack of a number of conveniently located fueling stations. Overcoming this major concern requires overcoming a key roadblock, fuel storage, in a manner that permits sufficient quantity of fuel without sacrificing passenger or cargo capability. Fueling infrastructure, on the other hand, has been problematic. Only three of a planned seven stations were opened. The difficulty in obtaining public approval and local government support for hydrogen fuel, based largely on the fear of hydrogen that grew from past disasters and atomic weaponry, has inhibited progress and presents a major roadblock to implementation. In addition the cost of hydrogen production, in any of the methodologies used in this program, does not show a rapid reduction to commercially viable rates. On the positive side of this issue was the demonstrated safety of the fueling station, equipment and process. In the Ford program, there were no reported safety incidents.

Dr. Scott Staley

2010-03-31T23:59:59.000Z

87

High-Temperature Superconductivity Cable Demonstration Projects  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Temperature Temperature Superconductivity Cable Demonstration Projects Superconductivity Power Equipment www.oe.energy.gov Phone: 202-586-1411 Office of Electricity Delivery and Energy Reliability, OE-1 U.S. Department of Energy - 1000 Independence Avenue, SW - Washington, DC 20585. Plugging America Into the Future of Power "A National Effort to Introduce New Technology into the Power Delivery Infrastructure" "In order to meet President Obama's ambitious energy goals, we must modernize the nation's electrical grid to improve the transmission, storage and reliability of clean energy across the country and help to move renewable energy from the places it can be produced to the places it can be used. The Department of Energy is working with industry partners to develop the

88

Wave Power Demonstration Project at Reedsport, Oregon  

SciTech Connect

Ocean wave power can be a significant source of large?scale, renewable energy for the US electrical grid. The Electrical Power Research Institute (EPRI) conservatively estimated that 20% of all US electricity could be generated by wave energy. Ocean Power Technologies, Inc. (OPT), with funding from private sources and the US Navy, developed the PowerBuoy? to generate renewable energy from the readily available power in ocean waves. OPT's PowerBuoy converts the energy in ocean waves to electricity using the rise and fall of waves to move the buoy up and down (mechanical stroking) which drives an electric generator. This electricity is then conditioned and transmitted ashore as high?voltage power via underwater cable. OPT's wave power generation system includes sophisticated techniques to automatically tune the system for efficient conversion of random wave energy into low cost green electricity, for disconnecting the system in large waves for hardware safety and protection, and for automatically restoring operation when wave conditions normalize. As the first utility scale wave power project in the US, the Wave Power Demonstration Project at Reedsport, OR, will consist of 10 PowerBuoys located 2.5 miles off the coast. This U.S. Department of Energy Grant funding along with funding from PNGC Power, an Oregon?based electric power cooperative, was utilized for the design completion, fabrication, assembly and factory testing of the first PowerBuoy for the Reedsport project. At this time, the design and fabrication of this first PowerBuoy and factory testing of the power take?off subsystem are complete; additionally the power take?off subsystem has been successfully integrated into the spar.

Mekhiche, Mike [Principal Investigator] [Principal Investigator; Downie, Bruce [Project Manager] [Project Manager

2013-10-21T23:59:59.000Z

89

PFBC Utility Demonstration Project. Annual report, 1991  

Science Conference Proceedings (OSTI)

This report provides a summary of activities by American Electric Power Service Corporation during the first budget period of the PFBC Utility Demonstration Project. In April 1990, AEP signed a Cooperative Agreement with the US Department of Energy to repower the Philip Sporn Plant, Units 3 & 4 in New Haven, West Virginia, with a 330 KW PFBC plant. The purpose of the program was to demonstrate and verify PFBC in a full-scale commercial plant. The technical and cost baselines of the Cooperative Agreement were based on a preliminary engineering and design and a cost estimate developed by AEP subsequent to AEP`s proposal submittal in May 1988, and prior to the signing of the Cooperative Agreement. The Statement of Work in the first budget period of the Cooperative Agreement included a task to develop a preliminary design and cost estimate for erecting a Greenfield plant and to conduct a comparison with the repowering option. The comparative assessment of the options concluded that erecting a Greenfield plant rather than repowering the existing Sporn Plant could be the technically and economically superior alternative. The Greenfield plant would have a capacity of 340 MW. The ten additional MW output is due to the ability to better match the steam cycle to the PFBC system with a new balance of plant design. In addition to this study, the conceptual design of the Sporn Repowering led to several items which warranted optimization studies with the goal to develop a more cost effective design.

Not Available

1992-11-01T23:59:59.000Z

90

The Way Ahead - West Valley Demonstration Project  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Update Update Project Update The Way Ahead The Way Ahead West Valley Demonstration Project Not to be Considered as a Regulatory Submittal Pre-decisional Draft 19817_1 The Way Ahead The Way Ahead Bryan Bower, DOE Director HLW Corporate Board October 6, 2008 FY 2008 Accomplishments Safety Performance Planned vs Actual 2.1 2.3 2 2 2.3 1.9 1.9 1.5 2 2.5 Actual Performance 1 Million Hours (9/3/08) 2007 DOE complex avg. TRC Safety Performance Planned vs Actual 2.1 2.3 2 2 2.3 1.9 1.9 1.5 2 2.5 Actual Performance 1 Million Hours (9/3/08) 2007 DOE complex avg. TRC One Million One Million Safe Work Hours! Safe Work Hours! TRC 0.5 DART 0.0 No lost-time injuries in FY 2008 Not to be Considered as a Regulatory Submittal Pre-decisional Draft 19817_2 0 0.0 0.0 0.0 0.0 0.0 1.4 1.4 1.4 1.4 0.8 0.3 0.3 0.3 1.2 1.2 1.3 1.3 1.0 0.8 0.8 0.3 0.3 0.3 0.3 0 0.5 1 Sep -07 O ct-07 Nov-07 Dec-07 Jan-08 Feb-08 Mar-08 Apr-08 May-08 Ju n-08

91

WSF Biodiesel Demonstration Project Final Report  

Science Conference Proceedings (OSTI)

In 2004, WSF canceled a biodiesel fuel test because of product quality issues that caused the fuel purifiers to clog. The cancelation of this test and the poor results negatively impacted the use of biodiesel in marine application in the Pacific Northwest. In 2006, The U.S. Department of Energy awarded the Puget Sound Clean Air Agency a grant to manage a scientific study investigating appropriate fuel specifications for biodiesel, fuel handling procedures and to conduct a fuel test using biodiesel fuels in WSF operations. The Agency put together a project team comprised of experts in fields of biodiesel research and analysis, biodiesel production, marine engineering and WSF personnel. The team reviewed biodiesel technical papers, reviewed the 2004 fuel test results, designed a fuel test plan and provided technical assistance during the test. The research reviewed the available information on the 2004 fuel test and conducted mock laboratory experiments, but was not able to determine why the fuel filters clogged. The team then conducted a literature review and designed a fuel test plan. The team implemented a controlled introduction of biodiesel fuels to the test vessels while monitoring the environmental conditions on the vessels and checking fuel quality throughout the fuel distribution system. The fuel test was conducted on the same three vessels that participated in the canceled 2004 test using the same ferry routes. Each vessel used biodiesel produced from a different feedstock (i.e. soy, canola and yellow grease). The vessels all ran on ultra low sulfur diesel blended with biodiesel. The percentage of biodiesel was incrementally raised form from 5 to 20 percent. Once the vessels reached the 20 percent level, they continued at this blend ratio for the remainder of the test. Fuel samples were taken from the fuel manufacturer, during fueling operations and at several points onboard each vessel. WSF Engineers monitored the performance of the fuel systems and engines. Each test vessel did experience a microbial growth bloom that produced a build up of material in the fuel purifiers similar to material witnessed in the 2004 fuel test. A biocide was added with each fuel shipment and the problem subsided. In January of 2009, the WSF successfully completed an eleven month biodiesel fuel test using approximately 1,395,000 gallons of biodiesel blended fuels. The project demonstrated that biodiesel can be used successfully in marine vessels and that current ASTM specifications are satisfactory for marine vessels. Microbial growth in biodiesel diesel interface should be monitored. An inspection of the engines showed no signs of being negatively impacted by the test.

Washington State University; University of Idaho; The Glosten Associates, Inc.; Imperium Renewables, Inc.

2009-04-30T23:59:59.000Z

92

Small-Scale Hydroelectric Power Demonstration Project  

DOE Green Energy (OSTI)

The US Department of Energy Field Office, Idaho, Small-Scale Hydroelectric Power Program was initiated in conjunction with the restoration of three power generating plants in Idaho Falls, Idaho, following damage caused by the Teton Dam failure on June 5, 1976. There were many parties interested in this project, including the state and environmental groups, with different concerns. This report was prepared by the developer and describes the design alternatives the applicant provided in an attempt to secure the Federal Energy Regulatory Commission license. Also included are correspondence between the related parties concerning the project, major design alternatives/project plan diagrams, the license, and energy and project economics.

Gleeson, L.

1991-12-01T23:59:59.000Z

93

Water and Wastewater Technology Demonstration Projects  

Science Conference Proceedings (OSTI)

This project was funded jointly by the Electric Power Research Institute (EPRI), Southern California Edison (SCE), and the California Energy Commission (CEC), with project management by SCE. The primary objective was to identify and develop technologies that could help California's water/wastewater industry reduce the cost of water and wastewater treatment and improve the overall operation at treatment facilities. Metropolitan Water District (MWD) and Orange County Water District (OCWD) were commissioned...

2002-07-15T23:59:59.000Z

94

NETL: Clean Coal Demonstrations - Project Performance Summaries  

NLE Websites -- All DOE Office Websites (Extended Search)

Deepwater Technology Enhanced Oil Recovery Gas Hydrates Natural Gas Resources Contacts Coal & Power Systems Major Demonstrations Innovations for Existing Plants Gasification...

95

Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project  

DOE Green Energy (OSTI)

Graphs of composite data products produced by DOE's Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation project through September 2010.

Wipke, K.; Spirk, S.; Kurtz, J.; Ramsden, T.

2010-09-01T23:59:59.000Z

96

Project Green Thumb: A Demonstration in Wisconsin  

Science Conference Proceedings (OSTI)

A prototype of NOAA's proposed Green Thumb agricultural information dissemination system was demonstrated at five different sites across Wisconsin during the period JulyOctober 1979. Those viewing the system were asked to complete questionnaires ...

David Suchman

1980-04-01T23:59:59.000Z

97

Supplemental Comprehensive Report to Congress - Clean Coal Technology Program. Tidd Pressurized Fluidized Bed Combustion (PFBC) Project  

SciTech Connect

The Department of Energy (DOE) in February 1987 submitted a Comprehensive Report to Congress for a Clean Coal Technology (CCT) project entitled {open_quotes}Tidd PFBC (Pressurized Fluidized Bed Combustion) Demonstration Project.{close_quotes} In that document, DOE reported to Congress that the Government share of project costs would be $60,200,000 and that the participant agreed to absorb any cost overruns, even though the public law contained provisions which would allow DOE to share in project cost growths up to 25 percent of the original financial assistance. This Supplemental Report is being submitted because DOE now intends to increase its contribution to the project by approximately 11 percent to facilitate extension of the original 3-year operating period by one additional year. DOE`s overall percentage cost share resulting from this extension will not exceed DOE`s overall percentage cost share in the original agreement.

Not Available

1994-03-01T23:59:59.000Z

98

West Valley Demonstration Project Phase I Decommissioning - Facility  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Project Phase I Decommissioning - Project Phase I Decommissioning - Facility Disposition Partnering Performance Agreement West Valley Demonstration Project Phase I Decommissioning - Facility Disposition Partnering Performance Agreement The Department of Energy, West Valley Demonstration Project (DOE-WVDP) and CH2M Hill B&W West Valley (CHBWV) are committed to continuous improvement and will utilize principles of the DOE Environmental Management (DOE-EM) Partnering Policy to create and foster a team environment to successfully complete the West Valley Demonstration Project (WVDP) Phase I Decommissioning - Faciltiy Disposition. West Valley Demonstration Project Phase I Decommissioning - Facility Disposition Partnering Performance Agreement More Documents & Publications CX-009527: Categorical Exclusion Determination

99

Utility Scale Wind turbine Demonstration Project  

SciTech Connect

The purpose of the Three Affiliated Tribes proposing to Department of Energy was nothing new to Denmark. National Meteorological Studies have proved that North Dakota has some of the most consistence wind resources in the world. The Three Affiliated Tribes wanted to assess their potential and become knowledgeable to developing this new and upcoming resource now valuable. By the Tribe implementing the Utility-scale Wind Turbine Project on Fort Berthold, the tribe has proven the ability to complete a project, and has already proceeded in a feasibility studies to developing a large-scale wind farm on the reservation due to tribal knowledge learned, public awareness, and growing support of a Nation wanting clean renewable energy. The tribe is working through the various measures and regulations with the want to be self-sufficient, independent, and marketable with 17,000 times the wind energy needed to service Fort Berthold alone.

Terry Fredericks

2006-03-31T23:59:59.000Z

100

Operational results of National Solar Demonstration Projects  

Science Conference Proceedings (OSTI)

Included in the National Solar Demonstration Program are examples of earth-sheltered, passive solar designs. The data obtained from these sites presents an interesting look at what is both technically and economically feasible. Data from four demonstration sites that are members of the National Solar Data Network are utilized to present an economic and technical analyses of a group of four sites. Three of these sites are earth sheltered residential structures, the fourth is a commercial passive structure. This sample of four demonstration sites is not intended to provide a statistical representation of passive earth sheltered structures, but rather, an example of the type of information available through the National Solar Data Program and how this information may be utilized.

Waite, E.V.

1981-01-01T23:59:59.000Z

Note: This page contains sample records for the topic "bed demonstration project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


101

East Penn Manufacturing Co. Smart Grid Demonstration Project | Open Energy  

Open Energy Info (EERE)

Manufacturing Co. Smart Grid Demonstration Project Manufacturing Co. Smart Grid Demonstration Project Jump to: navigation, search Project Lead East Penn Manufacturing Co. Country United States Headquarters Location Lyon Station, Pennsylvania Recovery Act Funding $2,245,523.00 Total Project Value $4,491,046.00 References ARRA Smart Grid Demonstration Projects[1] This article is a stub. You can help OpenEI by expanding it. The East Penn Manufacturing Co. Smart Grid Demonstration Project is a U.S. Department of Energy Smart Grid Demonstration Project which is based in Lyon Station, Pennsylvania. Overview Demonstrate the economic and technical viability of a 3MW grid-scale, advanced energy storage system using the lead-carbon UltraBattery technology to regulate frequency and manage energy demand. This project

102

Newberry Volcano EGS Demonstration Geothermal Project | Open Energy  

Open Energy Info (EERE)

Volcano EGS Demonstration Geothermal Project Volcano EGS Demonstration Geothermal Project Jump to: navigation, search Last modified on July 22, 2011. Project Title Newberry Volcano EGS Demonstration Project Type / Topic 1 Recovery Act: Enhanced Geothermal System Demonstrations Project Type / Topic 2 EGS Demonstration Project Description The project will demonstrate EGS power generation from the Newberry Known Geothermal Resource Area ("Newberry"). Four deep, high temperature, very low permeability, production-size wells have been completed at Newberry, including two currently owned by Davenport. The Newberry project site exemplifies unparalleled EGS potential in the United States, with a large, high-temperature, conductive thermal anomaly yielding wells with permeability orders of magnitude less than conventional hydrothermal wells.

103

Innovative Manufactured Housing Urban Design Demonstration Project  

Science Conference Proceedings (OSTI)

One quarter of the new houses sold in the United States in 1999 were manufactured homes, and manufactured housing represents an important and growing market for power producers. One niche market opportunity for manufactured homes is in urban areas. EPRI facilitated the completion of two limited demonstrations of energy efficient manufactured homes designed specifically for urban neighborhoods.

2000-10-05T23:59:59.000Z

104

Newberry EGS Demonstration Project Environmental Analysis (EA...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

compl ex pathw ays, i s hi ghl y unl i kel y tracers w i l l be one of the onl y def i ni ti ve w ays to demonstrate communi cati on. 4 Suggested tracer analysis is...

105

Calderon Cokemaking Process/Demonstration Project  

Science Conference Proceedings (OSTI)

During this reporting period an agreement was entered into with Bechtel Corporation for design and construction of Calderon cokemaking facilities (see enclosed letter of February 28, 1997). A second agreement with Bechtel Enterprises to commercialize the Calderon technology as a worldwide business has progressed; during the forthcoming quarter, it is expected to have in place an agreement with Bechtel Enterprises (see attached letter of February 20, 1997). Thyssen Still Otto Anlagentechnik (TSOA), the world's largest builder of conventional cokemaking facilities indicated that it would be please to join Bechtel and Calderon in the demonstration and implementation of Calderon's cokemaking technology (see attached letter of January, 1997).

None

1998-04-08T23:59:59.000Z

106

Poland petroleum refinery sludge lagoon demonstration project  

SciTech Connect

The US Department of Energy and the Institute for Ecology of Industrial Area have been working together to develop mutually beneficial, cost-effective environmental remediation technologies such as the demonstration of bioremediation techniques for the clean up of acidic petroleum sludge impacted soils at an oil refinery in southern Poland. After an expedited site characterization, treatability study, and a risk assessment study, a remediation strategy was devised. The waste material was composed primarily of high molecular weight paraffinic and polynuclear aromatic hydrocarbons. A biopile design which employed a combination of passive and active aeration in conjunction with nutrient and surfactant application as used to increase the biodegradation of the contaminants of concern.

Altman, D.J.

2000-05-05T23:59:59.000Z

107

Site Programs & Cooperative Agreements: West Valley Demonstration Project |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

West Valley Demonstration West Valley Demonstration Project Site Programs & Cooperative Agreements: West Valley Demonstration Project West Valley Demonstration Project The Seneca Nation of Indians has interests and concerns regarding the West Valley Demonstration Project Site. Like at Hanford, DOE environmental cleanup activities have the potential to impact natural and cultural resources and to interfere with American Indian religious practices. Through a cooperative agreement, tribal staff is engaged on a frequent basis with DOE and its contractors. The principle activities engaged by tribes include reviewing and commenting on plans and documents, participating in meetings at the request of DOE, monitoring cultural resource sites, participating in site surveys, and identifying issues that

108

Implementation of a Demonstration EGS Project at Naknek, Alaska...  

Open Energy Info (EERE)

Project Type Topic 2 EGS Demonstration Project Description NEA is about to begin drilling a deep, full-diameter well (Naknek-G 1, or simply G-1) that will be spudded in...

109

NETL: Clean Coal Demonstrations - Post-Project (DOE) Assessments  

NLE Websites -- All DOE Office Websites (Extended Search)

DOE Assessments DOE Assessments Clean Coal Demonstrations DOE Post-Project Assessments DOE Assessment of the Clean Coal Diesel Demonstration Project [PDF-590KB] DOE Assessment of the JEA Large-Scale CFB Combustion Demonstration Project [PDF-177KB] DOE Assessment of the Advanced Coal Conversion Process Demonstration [PDF-649KB] DOE Assessment of the Tampa Electric Integrated Gasification Combined-Cycle Demonstration Project [PDF-550KB] 500-MW Demonstration of Advanced Wall-Fired Combustion Techniques for the Reduction of Nitrogen Oxide (NOx) Emissions from Coal- Fired Boilers: A DOE Assessment [PDF-921KB] Commercial-Scale Demonstration of the Liquid Phase Methanol (LPMEOH™) Process [PDF-382KB] Healy Clean Coal Project: A DOE Assessment [PDF-713KB] Pulse Combustor Design: A DOE Assessment [PDF-569KB]

110

300kW Energy Storage Demonstration Project  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

kW Energy Storage Demonstration Project Technical Overview Presented at: Annual Doe Peer Review Meeting 2008 DOE Energy Storage & Power Electronics Research Programs By Ib I....

111

Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project (Presentation)  

DOE Green Energy (OSTI)

This presentation, which provides information on the Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project, was given at the Fuel Cell Seminar in November 2004.

Garbak, J.; Gronich, S.; Wipke, K.; Welch, C.

2004-11-01T23:59:59.000Z

112

RADIOACTIVE DEMONSTRATIONS OF FLUIDIZED BED STEAM REFORMING (FBSR) WITH HANFORD LOW ACTIVITY WASTES  

SciTech Connect

Several supplemental technologies for treating and immobilizing Hanford low activity waste (LAW) are being evaluated. One immobilization technology being considered is Fluidized Bed Steam Reforming (FBSR) which offers a low temperature (700-750C) continuous method by which wastes high in organics, nitrates, sulfates/sulfides, or other aqueous components may be processed into a crystalline ceramic (mineral) waste form. The granular waste form produced by co-processing the waste with kaolin clay has been shown to be as durable as LAW glass. The FBSR granular product will be monolithed into a final waste form. The granular component is composed of insoluble sodium aluminosilicate (NAS) feldspathoid minerals such as sodalite. Production of the FBSR mineral product has been demonstrated both at the industrial, engineering, pilot, and laboratory scales on simulants. Radioactive testing at SRNL commenced in late 2010 to demonstrate the technology on radioactive LAW streams which is the focus of this study.

Jantzen, C.; Crawford, C.; Burket, P.; Bannochie, C.; Daniel, G.; Nash, C.; Cozzi, A.; Herman, C.

2012-10-22T23:59:59.000Z

113

Radioactive Demonstrations Of Fluidized Bed Steam Reforming (FBSR) With Hanford Low Activity Wastes  

Science Conference Proceedings (OSTI)

Several supplemental technologies for treating and immobilizing Hanford low activity waste (LAW) are being evaluated. One immobilization technology being considered is Fluidized Bed Steam Reforming (FBSR) which offers a low temperature (700-750?C) continuous method by which wastes high in organics, nitrates, sulfates/sulfides, or other aqueous components may be processed into a crystalline ceramic (mineral) waste form. The granular waste form produced by co-processing the waste with kaolin clay has been shown to be as durable as LAW glass. The FBSR granular product will be monolithed into a final waste form. The granular component is composed of insoluble sodium aluminosilicate (NAS) feldspathoid minerals such as sodalite. Production of the FBSR mineral product has been demonstrated both at the industrial, engineering, pilot, and laboratory scales on simulants. Radioactive testing at SRNL commenced in late 2010 to demonstrate the technology on radioactive LAW streams which is the focus of this study.

Jantzen, C. M.; Crawford, C. L.; Burket, P. R.; Bannochie, C. J.; Daniel, W. G.; Nash, C. A.; Cozzi, A. D.; Herman, C. C.

2012-10-22T23:59:59.000Z

114

CERTS Microgrid Laboratory Test Bed - PIER Final Project Report  

E-Print Network (OSTI)

Laboratory Test Bed. California Energy Commission, PublicCERTS Microgrid, California Energy Commission R&D Forum, 4CERTS Microgrid, California Energy Commission R&D Forum, 4

Eto, Joseph H.

2008-01-01T23:59:59.000Z

115

Thanksgiving Goodwill: West Valley Demonstration Project Food Drive  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Thanksgiving Goodwill: West Valley Demonstration Project Food Drive Thanksgiving Goodwill: West Valley Demonstration Project Food Drive Provides 640 Turkeys to People in Need Thanksgiving Goodwill: West Valley Demonstration Project Food Drive Provides 640 Turkeys to People in Need November 26, 2013 - 12:00pm Addthis Volunteers from West Valley Demonstration Project gather before distributing items collected in an annual food drive. Volunteers from West Valley Demonstration Project gather before distributing items collected in an annual food drive. Volunteer John Schelble helps unload a delivery truck at a food pantry. Volunteer John Schelble helps unload a delivery truck at a food pantry. John Rizzo passes canned food to John Rendall to deliver to a food pantry. John Rizzo passes canned food to John Rendall to deliver to a food pantry.

116

Independent Activity Report, West Valley Demonstration Project - July 2012  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

West Valley Demonstration Project - West Valley Demonstration Project - July 2012 Independent Activity Report, West Valley Demonstration Project - July 2012 July 2012 Operational Awareness Oversight of the West Valley Demonstration Project [HIAR WVDP-2012-07-30] The purpose of this Office of Health, Safety and Security (HSS) activity was for the HS-45 Site Lead to meet with Department of Energy (DOE) site personnel, tour the facilities, and obtain a status report on the upcoming activities at the West Valley Demonstration Project (WVDP). In the fall of 2011, a new contractor, CH2M Hill-B&W West Valley (CHBWV), was selected to perform site operations for Phase 1 decommissioning and facility disposition, including the Main Plant Process Building, the Low-Level Waste Treatment Facility, and other facilities.

117

Independent Activity Report, West Valley Demonstration Project - November  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Activity Report, West Valley Demonstration Project - Activity Report, West Valley Demonstration Project - November 2011 Independent Activity Report, West Valley Demonstration Project - November 2011 November 2011 West Valley Demonstration Project Orientation Visit [HIAR-WVDP-2011-11-07] The U.S. Department of Energy (DOE) Office of Enforcement and Oversight, within the Office of Health, Safety and Security (HSS), conducted an orientation visit to the DOE West Valley Demonstration Project (WVDP) Office and the nuclear facility at West Valley, NY, on November 7, 2011. The purpose of the visit was to discuss the nuclear safety oversight strategy, describe the site lead program, increase HSS personnel's operational awareness of the site's activities, and identify specific activities that HSS can perform to carry out its independent oversight

118

Con Edison Smart Grid Demonstration Host-Site Project Description  

Science Conference Proceedings (OSTI)

This report provides a description of the Con Edison Smart Grid Demonstration Host-Site Project as part of the Electric Power Research Institute's (EPRI's) five-year smart grid demonstration initiative. The EPRI initiative includes core smart grid research and a number of large-scale smart grid projects with 19 funding utility members. The project is focused on integrating large-scale distributed energy resources (DER), including demand response, storage, distributed generation, and distributed renewable...

2009-09-16T23:59:59.000Z

119

ESB Networks Smart Grid Demonstration Host-Site Project Description  

Science Conference Proceedings (OSTI)

This report provides a description of the ESB Networks Smart Grid Demonstration Host-Site Project as part of EPRIs five-year Smart Grid demonstration initiative. The EPRI initiative includes core Smart Grid research and a number of large scale Smart Grid projects with 18 funding utility members. The project is focused on integrating large-scale distributed energy resources (DER) including demand response, storage, distributed generation, and distributed renewable generation into a virtual power plant to ...

2010-03-15T23:59:59.000Z

120

Exelon Smart Grid Demonstration Host-Site Project Description  

Science Conference Proceedings (OSTI)

This report provides a description of the Exelon Smart Grid Demonstration Host-Site Project as part of the Electric Power Research Institute's (EPRI's) five-year smart grid demonstration initiative. The EPRI initiative includes core smart grid research and a number of large-scale smart grid projects with 18 funding utility members. The project is focused on integrating large-scale distributed energy resources (DER) including demand response, storage, distributed generation, and distributed renewable gene...

2010-04-05T23:59:59.000Z

Note: This page contains sample records for the topic "bed demonstration project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


121

Duke Energy Smart Grid Demonstration Host-Site Project Description  

Science Conference Proceedings (OSTI)

This report provides a description of the Duke Energy Smart Grid Demonstration Host-Site Project as part of the Electric Power Research Institute's (EPRI's) multi-year smart grid demonstration initiative. The EPRI initiative includes core smart grid research and a number of large-scale smart grid projects currently with 18 funding utility members. The project is focused on integrating large-scale distributed energy resources (DER)including demand response, storage, distributed generation, and distributed...

2010-07-27T23:59:59.000Z

122

Southern Company Smart Grid Demonstration Host-Site Project Description  

Science Conference Proceedings (OSTI)

This report provides a description of the Southern Company Smart Grid Demonstration Host-Site Project as part of the Electric Power Research Institute's (EPRI's) multi-year smart grid demonstration initiative. The EPRI initiative includes core smart grid research and a number of large-scale smart grid projects currently with 18 funding utility members. The project is focused on integrating large-scale distributed energy resources (DER)including demand response, storage, distributed generation, and distri...

2010-07-27T23:59:59.000Z

123

PNM Smart Grid Demonstration Host-Site Project Description  

Science Conference Proceedings (OSTI)

This report provides a description of the PNM Smart Grid Demonstration Host-Site Project as part of the Electric Power Research Institute's (EPRI's) five-year smart grid demonstration initiative. The EPRI initiative includes core smart grid research and a number of large-scale smart grid projects with 19 funding utility members. The project is focused on integrating large-scale distributed energy resources (DER), including demand response, storage, distributed generation, and distributed renewable genera...

2009-09-16T23:59:59.000Z

124

Mercury Control Demonstration Projects Cover Photos: * Top: Limestone Power Plant  

NLE Websites -- All DOE Office Websites (Extended Search)

6 FEBRUARY 2008 6 FEBRUARY 2008 Mercury Control Demonstration Projects Cover Photos: * Top: Limestone Power Plant * Bottom left: AES Greenidge Power Plant * Bottom right: Presque Isle Power Plant A report on three projects conducted under separate cooperative agreements between the U.S. Department of Energy and: * Consol Energy * Pegasus Technologies * We Energies  Mercury Control Demonstration Projects Executive Summary ............................................................................ 4 Background ......................................................................................... 5 Mercury Removal Projects ................................................................ 7 TOXECON(tm) Retrofit For Mercury and Multi-Pollutant Control on Three 90-MW Coal-Fired Boilers ........................................7

125

Vitrification facility at the West Valley Demonstration Project  

SciTech Connect

This report is a description of the West Valley Demonstration Project`s vitrification facilities from the establishment of the West Valley, NY site as a federal and state cooperative project to the completion of all activities necessary to begin solidification of radioactive waste into glass by vitrification. Topics discussed in this report include the Project`s background, high-level radioactive waste consolidation, vitrification process and component testing, facilities design and construction, waste/glass recipe development, integrated facility testing, and readiness activities for radioactive waste processing.

DesCamp, V.A.; McMahon, C.L.

1996-07-01T23:59:59.000Z

126

EA-1116: Kalina Geothermal Demonstration Project, Steamboat Springs, Nevada  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

16: Kalina Geothermal Demonstration Project, Steamboat 16: Kalina Geothermal Demonstration Project, Steamboat Springs, Nevada EA-1116: Kalina Geothermal Demonstration Project, Steamboat Springs, Nevada SUMMARY This EA evaluates the environmental impacts of the proposal for the U.S. Department of Energy Golden Field Office to partially fund assistance for the construction and operation of a privately owned 6-megawatt geothermal power plant which includes one geothermal production well, one injection well, and ancillary facilities such as on-site access road(s) and interconnected to electric transmission lines to existing geothermal power plants. PUBLIC COMMENT OPPORTUNITIES None available at this time. DOCUMENTS AVAILABLE FOR DOWNLOAD February 22, 1999 EA-1116: Finding of No Significant Impact Kalina Geothermal Demonstration Project, Steamboat Springs, Nevada

127

Sydney 2000 Forecast Demonstration Project: Convective Storm Nowcasting  

Science Conference Proceedings (OSTI)

Five of the nowcasting systems that were available during the Sydney 2000 Forecast Demonstration Project (FDP) were selected for evaluation. These systems, from the United States, the United Kingdom, and Australia, had the capability to nowcast ...

James W. Wilson; Elizabeth E. Ebert; Thomas R. Saxen; Rita D. Roberts; Cynthia K. Mueller; Michael Sleigh; Clive E. Pierce; Alan Seed

2004-02-01T23:59:59.000Z

128

West Valley Demonstration Project Waste Incidental to Reprocessing Evaluation  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

West Valley Demonstration Project West Valley Demonstration Project Waste Incidental to Reprocessing Evaluation for the Concentrator Feed Makeup Tank and the Melter Feed Hold Tank February 2013 Prepared by the U.S. Department of Energy West Valley, New York This page is intentionally blank. WASTE-INCIDENTAL-TO-REPROCESSING EVALUATION FOR THE WVDP CFMT AND MFHT CONTENTS Revision 0 i NOTATION (Acronyms, Abbreviations, and Units).................................................. v 1.0 INTRODUCTION ...................................................................................................... 1 1.1 Purpose. ................................................................................................................. 2

129

The ethanol heavy-duty truck fleet demonstration project  

DOE Green Energy (OSTI)

This project was designed to test and demonstrate the use of a high- percentage ethanol-blended fuel in a fleet of heavy-duty, over-the- road trucks, paying particular attention to emissions, performance, and repair and maintenance costs. This project also represents the first public demonstration of the use of ethanol fuels as a viable alternative to conventional diesel fuel in heavy-duty engines.

NONE

1997-06-01T23:59:59.000Z

130

Hawaiian Electric Company (HECO) Smart Grid (SG) Demonstration Project Description  

Science Conference Proceedings (OSTI)

This report describes one smart grid demonstration host-site project. The Hawaiian Electric Company (HECO) host site is part of the Electric Power Research Institute's (EPRI's) seven-year Smart Grid Demonstration Initiative. The project is focused on integrating large-scale distributed energy resources (DER), including demand response, storage, distributed generation, and distributed renewable generation, into a "virtual power plant" to advance the widespread, efficient, and cost-effective deployment of ...

2012-08-13T23:59:59.000Z

131

ATTACHMENT O RECENT DEMONSTRATION PROJECTS FUNDED BY THE IAW PROGRAM  

E-Print Network (OSTI)

Generation in Parabolic Trough Solar Collectors This project is to demonstrate on a pilot scale the ability and demonstrate the direct steam generation (DSG) technology in the #12;receiver tube of a line focus parabolic trough collector, first in a single row, and then to simulate operations in multiple rows. From

132

Topic Area 1: Technology Demonstration Projects | Open Energy Information  

Open Energy Info (EERE)

1: Technology Demonstration Projects 1: Technology Demonstration Projects Jump to: navigation, search Geothermal ARRA Funded Projects for Topic Area 1: Technology Demonstration Projects Loading map... {"format":"googlemaps3","type":"ROADMAP","types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"limit":200,"offset":0,"link":"all","sort":[""],"order":[],"headers":"show","mainlabel":"","intro":"","outro":"","searchlabel":"\u2026 further results","default":"","geoservice":"google","zoom":false,"width":"600px","height":"350px","centre":false,"layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","icon":"","visitedicon":"","forceshow":true,"showtitle":true,"hidenamespace":false,"template":false,"title":"","label":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"locations":[{"text":"

133

DOE-Sponsored Project Begins Demonstrating CCUS Technology in Alabama |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Project Begins Demonstrating CCUS Technology in Project Begins Demonstrating CCUS Technology in Alabama DOE-Sponsored Project Begins Demonstrating CCUS Technology in Alabama August 22, 2012 - 1:00pm Addthis Washington, DC - Carbon dioxide (CO2) injection has begun at the world's first fully integrated coal power and geologic storage project in southwest Alabama, with the goals of assessing integration of the technologies involved and laying the foundation for future use of CO2 for enhanced oil recovery (EOR). The "Anthropogenic Test"--conducted by the Southeast Regional Carbon Sequestration Partnership (SECARB), one of seven partnerships in DOE's Regional Carbon Sequestration Partnerships program--uses CO2 from a newly constructed post-combustion CO2-capture facility at Alabama Power's 2,657-megawatt Barry Electric Generating Plant (Plant Barry). It will help

134

Plan for Demonstration of Online Monitoring for the Light Water Reactor Sustainability Online Monitoring Project  

SciTech Connect

Condition based online monitoring technologies and development of diagnostic and prognostic methodologies have drawn tremendous interest in the nuclear industry. It has become important to identify and resolve problems with structures, systems, and components (SSCs) to ensure plant safety, efficiency, and immunity to accidents in the aging fleet of reactors. The Machine Condition Monitoring (MCM) test bed at INL will be used to demonstrate the effectiveness to advancement in online monitoring, sensors, diagnostic and prognostic technologies on a pilot-scale plant that mimics the hydraulics of a nuclear plant. As part of this research project, INL will research available prognostics architectures and their suitability for deployment in a nuclear power plant. In addition, INL will provide recommendation to improve the existing diagnostic and prognostic architectures based on the experimental analysis performed on the MCM test bed.

Magdy S. Tawfik; Vivek Agarwal; Nancy J. Lybeck

2011-09-01T23:59:59.000Z

135

Technical Services Contract Awarded for West Valley Demonstration Project  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Technical Services Contract Awarded for West Valley Demonstration Technical Services Contract Awarded for West Valley Demonstration Project Support Services Technical Services Contract Awarded for West Valley Demonstration Project Support Services February 21, 2013 - 12:00pm Addthis Media Contact Bill Taylor, 803-952-8564 bill.taylor@srs.gov Cincinnati - The U.S. Department of Energy (DOE) today awarded a task order to Safety and Ecology Corporation of Knoxville, Tennessee, for technical services at the West Valley Demonstration Project, West Valley, New York. The task order has a three-year performance period with a $1.3 million value. The task order will be issued from the Indefinite Delivery/Indefinite Quantity (ID/IQ) master contract, firm-fixed-price and time and materials. Under the task order, Safety and Ecology Corporation will perform technical

136

Santa Clara County Planar Solid Oxide Fuel Cell Demonstration Project  

DOE Green Energy (OSTI)

The Santa Clara County Planar Solid Oxide Fuel Cell (PSOFC) project demonstrated the technical viability of pre-commercial PSOFC technology at the County 911 Communications headquarters, as well as the input fuel flexibility of the PSOFC. PSOFC operation was demonstrated on natural gas and denatured ethanol. The Santa Clara County Planar Solid Oxide Fuel Cell (PSOFC) project goals were to acquire, site, and demonstrate the technical viability of a pre-commercial PSOFC technology at the County 911 Communications headquarters. Additional goals included educating local permit approval authorities, and other governmental entities about PSOFC technology, existing fuel cell standards and specific code requirements. The project demonstrated the Bloom Energy (BE) PSOFC technology in grid parallel mode, delivering a minimum 15 kW over 8760 operational hours. The PSOFC system demonstrated greater than 81% electricity availability and 41% electrical efficiency (LHV net AC), providing reliable, stable power to a critical, sensitive 911 communications system that serves geographical boundaries of the entire Santa Clara County. The project also demonstrated input fuel flexibility. BE developed and demonstrated the capability to run its prototype PSOFC system on ethanol. BE designed the hardware necessary to deliver ethanol into its existing PSOFC system. Operational parameters were determined for running the system on ethanol, natural gas (NG), and a combination of both. Required modeling was performed to determine viable operational regimes and regimes where coking could occur.

Fred Mitlitsky; Sara Mulhauser; David Chien; Deepak Shukla; David Weingaertner

2009-11-14T23:59:59.000Z

137

Modular Pebble Bed Reactor Project, University Research Consortium Annual Report  

Science Conference Proceedings (OSTI)

This project is developing a fundamental conceptual design for a gas-cooled, modular, pebble bed reactor. Key technology areas associated with this design are being investigated which intend to address issues concerning fuel performance, safety, core neutronics and proliferation resistance, economics and waste disposal. Research has been initiated in the following areas: Improved fuel particle performance Reactor physics Economics Proliferation resistance Power conversion system modeling Safety analysis Regulatory and licensing strategy Recent accomplishments include: Developed four conceptual models for fuel particle failures that are currently being evaluated by a series of ABAQUS analyses. Analytical fits to the results are being performed over a range of important parameters using statistical/factorial tools. The fits will be used in a Monte Carlo fuel performance code, which is under development. A fracture mechanics approach has been used to develop a failure probability model for the fuel particle, which has resulted in significant improvement over earlier models. Investigation of fuel particle physio-chemical behavior has been initiated which includes the development of a fission gas release model, particle temperature distributions, internal particle pressure, migration of fission products, and chemical attack of fuel particle layers. A balance of plant, steady-state thermal hydraulics model has been developed to represent all major components of a MPBR. Component models are being refined to accurately reflect transient performance. A comparison between air and helium for use in the energy-conversion cycle of the MPBR has been completed and formed the basis of a masters degree thesis. Safety issues associated with air ingress are being evaluated. Post shutdown, reactor heat removal characteristics are being evaluated by the Heating-7 code. PEBBED, a fast deterministic neutronic code package suitable for numerous repetitive calculations has been developed. Use of the code has focused on scoping studies for MPBR design features and proliferation issues. Publication of an archival journal article covering this work is being prepared. Detailed gas reactor physics calculations have also been performed with the MCNP and VSOP codes. Furthermore, studies on the proliferation resistance of the MPBR fuel cycle has been initiated using these code Issues identified during the MPBR research has resulted in a NERI proposal dealing with turbo-machinery design being approved for funding beginning in FY01. Two other NERI proposals, dealing with the development of a burnup meter and modularization techniques, were also funded in which the MIT team will be a participant. A South African MPBR fuel testing proposal is pending ($7.0M over nine years).

Petti, David Andrew

2000-07-01T23:59:59.000Z

138

Demonstration of an advanced circulation fludized bed coal combustor phase 1: Cold model study. Final report  

Science Conference Proceedings (OSTI)

It was found that there was a strong dependence of the density profile on the secondary air injection location and that there was a pronounced solid separation from the conveying gas, due to the swirl motion. Furthermore, the swirl motion generated strong internal circulation patterns and higher slip velocities than in the case of nonswirl motion as in an ordinary circulating fluidized bed. Radial solids flux profiles were measured at different axial locations. The general radial profile in a swirling circulating fluidized bed indicated an increased downward flow of solids near the bed walls, and strong variations in radial profiles along the axial height. For swirl numbers less than 0.9, which is typical for swirling circulating fluidized beds, there is no significant increase in erosion due to swirl motion inside the bed. Pending further investigation of swirl motion with combustion, at least from our cold model studies, no disadvantages due to the introduction of swirl motion were discovered.

Govind, R. [Cincinnati Univ., OH (United States). Dept. of Chemical Engineering

1993-03-20T23:59:59.000Z

139

Tidd PFBC demonstration project. Quarterly report, October--December 1993  

SciTech Connect

This is the 27th Technical Progress Report submitted to the Department of Energy in connection with the Cooperative Agreement between the DOE and the Ohio Power Company for the Tidd PFBC Demonstration Plant. This report covers the period from October 1, 1993 to December 31, 1993. Major activities during this period involve: (1) The unit operated for 720 hours on coal. (2) There were five gas turbine starts, five bed preheater starts, and three operating periods on coal fire. (3) During the quarter, total gross generation was 36,672 MWH, the peak unit output for one hour was 64 MWH, and the coal consumption was 17,251 tons. (4) Six performance tests were run during this quarter. (5) The unit was tested with four sorbent feed points. (6) The gas turbine low pressure compressor was disassembled to repair cracks in the stationary guide vanes; and (7) a request was sent to the DOE requesting funding for an additional year of operation. Major items planned for the next period include: (a) Continuation of sorbent utilization tests at various bed levels and sulfur retention values and with different coals and adsorbents; and (b) operation at full load.

Not Available

1994-01-01T23:59:59.000Z

140

Waukesha Electric Systems Smart Grid Demonstration Project | Open Energy  

Open Energy Info (EERE)

Electric Systems Smart Grid Demonstration Project Electric Systems Smart Grid Demonstration Project Jump to: navigation, search Project Lead Waukesha Electric Systems Country United States Headquarters Location Waukesha, Wisconsin Recovery Act Funding $10,744,409.00 Total Project Value $21,548,821.00 Coordinates 43.0116784°, -88.2314813° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[]}

Note: This page contains sample records for the topic "bed demonstration project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


141

Long Island Power Authority Smart Grid Demonstration Project | Open Energy  

Open Energy Info (EERE)

Demonstration Project Demonstration Project Jump to: navigation, search Project Lead Long Island Power Authority Country United States Headquarters Location Uniondale, New York Recovery Act Funding $12,496,047.00 Total Project Value $25,293,735.00 Coordinates 40.7003793°, -73.5929056° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[]}

142

City of Painesville Smart Grid Demonstration Project | Open Energy  

Open Energy Info (EERE)

Painesville Smart Grid Demonstration Project Painesville Smart Grid Demonstration Project Jump to: navigation, search Project Lead City of Painesville Country United States Headquarters Location Painesville, Ohio Recovery Act Funding $3,743,570.00 Total Project Value $7,487,153.00 Coordinates 41.7244885°, -81.245657° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[]}

143

Primus Power Corporation Smart Grid Demonstration Project | Open Energy  

Open Energy Info (EERE)

Smart Grid Demonstration Project Smart Grid Demonstration Project Jump to: navigation, search Project Lead Primus Power Corporation Country United States Headquarters Location Alameda, California Recovery Act Funding $14,000,000.00 Total Project Value $46,700,000.00 Coordinates 37.7652065°, -122.2416355° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[]}

144

Duke Energy Business Services, LLC Smart Grid Demonstration Project | Open  

Open Energy Info (EERE)

Demonstration Project Demonstration Project Jump to: navigation, search Project Lead Duke Energy Business Services, LLC Country United States Headquarters Location Charlotte, North Carolina Recovery Act Funding $21,806,232.00 Total Project Value $43,612,464.00 Coordinates 35.2270869°, -80.8431267° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[]}

145

Seeo, Inc Smart Grid Demonstration Project | Open Energy Information  

Open Energy Info (EERE)

Seeo, Inc Smart Grid Demonstration Project Seeo, Inc Smart Grid Demonstration Project Jump to: navigation, search Project Lead Seeo, Inc Country United States Headquarters Location Berkeley, California Recovery Act Funding $6,196,060.00 Total Project Value $12,392,120.00 Coordinates 37.8715926°, -122.272747° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[]}

146

Ktech Corporation Smart Grid Demonstration Project | Open Energy  

Open Energy Info (EERE)

Ktech Corporation Smart Grid Demonstration Project Ktech Corporation Smart Grid Demonstration Project Jump to: navigation, search Project Lead Ktech Corporation Country United States Headquarters Location Albuquerque, New Mexico Recovery Act Funding $4,764,284.00 Total Project Value $9,528,567.00 Coordinates 35.0844909°, -106.6511367° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[]}

147

Premium Power Corporation Smart Grid Demonstration Project | Open Energy  

Open Energy Info (EERE)

Corporation Smart Grid Demonstration Project Corporation Smart Grid Demonstration Project Jump to: navigation, search Project Lead Premium Power Corporation Country United States Headquarters Location North Reading, Massachusetts Recovery Act Funding $7,320,000.00 Total Project Value $16,080,554.00 Coordinates 42.5750939°, -71.0786653° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[]}

148

Amber Kinetics, Inc. Smart Grid Demonstration Project | Open Energy  

Open Energy Info (EERE)

Kinetics, Inc. Smart Grid Demonstration Project Kinetics, Inc. Smart Grid Demonstration Project Jump to: navigation, search Project Lead Amber Kinetics, Inc. Country United States Headquarters Location Fremont, California Recovery Act Funding $4,000,000.00 Total Project Value $10,000,000.00 Coordinates 37.5482697°, -121.9885719° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[]}

149

Southern California Edison Company Smart Grid Demonstration Project (2) |  

Open Energy Info (EERE)

Company Smart Grid Demonstration Project (2) Company Smart Grid Demonstration Project (2) Jump to: navigation, search Project Lead Southern California Edison Company Country United States Headquarters Location Rosemead, California Recovery Act Funding $24,978,264.00 Total Project Value $53,510,209.00 Coordinates 34.0805651°, -118.072846° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[]}

150

Public Service Company of New Mexico Smart Grid Demonstration Project |  

Open Energy Info (EERE)

of New Mexico Smart Grid Demonstration Project of New Mexico Smart Grid Demonstration Project Jump to: navigation, search Project Lead Public Service Company of New Mexico Country United States Headquarters Location Albuquerque, New Mexico Recovery Act Funding $1,755,931.00 Total Project Value $5,851,303.00 Coordinates 35.0844909°, -106.6511367° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[]}

151

The Boeing Company Smart Grid Demonstration Project | Open Energy  

Open Energy Info (EERE)

The Boeing Company Smart Grid Demonstration Project The Boeing Company Smart Grid Demonstration Project Jump to: navigation, search Project Lead The Boeing Company Country United States Headquarters Location St. Louis, Missouri Recovery Act Funding $8,561,396.00 Total Project Value $17,172,844.00 Coordinates 38.646991°, -90.224967° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[]}

152

44 Tech Inc. Smart Grid Demonstration Project | Open Energy Information  

Open Energy Info (EERE)

Inc. Smart Grid Demonstration Project Inc. Smart Grid Demonstration Project Jump to: navigation, search Project Lead 44 Tech Inc. Country United States Headquarters Location Pittsburgh, Pennsylvania Recovery Act Funding $5,000,000.00 Total Project Value $10,000,000.00 Coordinates 40.4406248°, -79.9958864° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[]}

153

Oncor Electric Delivery Company, LLC Smart Grid Demonstration Project |  

Open Energy Info (EERE)

Company, LLC Smart Grid Demonstration Project Company, LLC Smart Grid Demonstration Project Jump to: navigation, search Project Lead Oncor Electric Delivery Company, LLC Country United States Headquarters Location Dallas, Texas Recovery Act Funding $3,471,681.00 Total Project Value $7,279,166.00 Coordinates 32.802955°, -96.769923° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[]}

154

Nome, Alaska, Wind Turbine Demonstration Project Final Environmental Assessment and  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Final Environmental Assessment and Final Environmental Assessment and Finding of No Significant Impact November 2000 Prepared for: U.S. Department of Energy Golden Field Office 1617 Cole Blvd. Golden, CO 80401 Prepared by: Battelle Memorial Institute 505 King Avenue Columbus, OH 43201 Nome, Alaska, Wind Turbine Demonstration Project Finding of No Significant Impact Nome, Alaska, Wind Turbine Demonstration Project FINDING OF NO SIGNIFICANT IMPACT S U M M A R Y The U.S. Department of Energy (DOE) has prepared this Environmental Assessment (EA) to provide DOE and other public agency decision makers witb tbe environmental documentation required to take informed discretionary action on the proposed Nome, Alaska, Wind Turbine Demonstration Project (DOE/EA-1280). The EA assesses the potential environmental impacts and cumulative i

155

West Valley Demonstration Project Waste Management Final Environmental Impact Statement  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

WEST VALLEY DEMONSTRATION PROJECT WEST VALLEY DEMONSTRATION PROJECT WASTE MANAGEMENT ENVIRONMENTAL IMPACT STATEMENT FINAL SUMMARY December 2003 Prepared by: U.S. Department of Energy West Valley Area Office West Valley, NY DOE/EIS - 0337F For general questions or to request a copy of this EIS, please contact: DANIEL W. SULLIVAN, DOCUMENT MANAGER DOE WEST VALLEY AREA OFFICE 10282 Rock Springs Road WEST VALLEY, NY 14171-0191 1-800-633-5280 COVER SHEET Lead Agency: U.S. Department of Energy Title: Final West Valley Demonstration Project Waste Management Environmental Impact Statement, Cattaraugus County, West Valley, New York. Contact: For further information about this Environmental Impact Statement, contact: For general information on the Department of Energy's process for implementing the National

156

West Valley Demonstration Project 10282 Rock Springs Road  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

West Valley Demonstration Project West Valley Demonstration Project 10282 Rock Springs Road West Valley, NY 141 71 -9799 Mr. Daniel W. Coyne President & General Manager CH2M HILL B&W West Valley, LLC West Valley Demonstration Project 10282 Rock Springs Road West Valley, NY 141 71 -9799 ATTENTION: J. D. Rendall, Regulatory Strategy, AC-EA SUBJECT: Environmental Checklist WVDP-20 12-0 1, " WVDP Reservoir Interconnecting Canal Maintenance Activities" REFERENCE: Letter WD:2012:0409 (357953), D. W. Coyne to R. W. Reffner, "CONTRACT NO. DE-EM000 1529, Section 5-3, Item 105, NEPA Documentation (Transmittal of Environmental Checklist WVDP-20 12-0 1, WVDP Reservoir Interconnecting Canal Maintenance Activities), Revision 1 ," dated July 24, 20 12 Dear Mr. Coyne:

157

DOE-Supported Project Demonstrates Benefits of Constructed Wetlands to  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Project Demonstrates Benefits of Constructed Wetlands Project Demonstrates Benefits of Constructed Wetlands to Treat Non-Traditional Water Sources DOE-Supported Project Demonstrates Benefits of Constructed Wetlands to Treat Non-Traditional Water Sources March 10, 2009 - 1:00pm Addthis Washington, DC -- In a pilot-scale test supported by the U.S. Department of Energy (DOE) Office of Fossil Energy, Clemson University researchers have shown that manmade or "constructed" wetlands can be used to treat non-traditional water sources which could then be used in power plants or for other purposes. The successful test, which was managed by DOE's National Energy Technology Laboratory (NETL), could help power plants economically meet criteria for water reuse or discharge established by the National Pollution Discharge Elimination System and the Clean Water Act.

158

Integrated monitoring and surveillance system demonstration project: Phase I accomplishments  

Science Conference Proceedings (OSTI)

The authors present the results of the Integrated Monitoring and Surveillance System (IMSS) demonstration project Phase I efforts. The rationale behind IMSS development is reviewed and progress in each of the 5 basic tasks is detailed. Significant results include decisions to use Echelon LonWorks networking protocol and Microsoft Access for the data system needs, a preliminary design for the plutonium canning system glovebox, identification of facilities and materials available for the demonstration, determination of possibly affected facility documentation, and a preliminary list of available sensor technologies. Recently imposed changes in the overall project schedule and scope are also discussed and budgetary requirements for competition of Phase II presented. The results show that the IMSS demonstration project team has met and in many cases exceeded the commitments made for Phase I deliverables.

Aumeier, S.E.; Walters, B.G.; Crawford, D.C. [and others

1997-01-15T23:59:59.000Z

159

Cool water demonstration project and its industrial applications  

SciTech Connect

This paper discusses the 100 MW coal gasification combined cycle demonstration project underway at the ''Cool Water'' site of Southern California Edison Company, including the technology, project participants, schedule and opportunities for future industrial users. Industrial applications with multiple product outputs, termed ''polygeneration'', are illustrated with examples for cogeneration and trigeneration. Finally, actions required for planning large-sized gas turbine installations are suggested for today in order to hold open the future options in coal gasification.

Alger, J.; Ahner, D.J.

1982-08-01T23:59:59.000Z

160

King County Carbonate Fuel Cell Demonstration Project: 2005 Update  

Science Conference Proceedings (OSTI)

This case study documents the ongoing demonstration experiences of a 1-MW carbonate fuel cell system operating on anaerobic digester gas at a wastewater treatment plant in King County, Washington. This is a follow-up to a previous EPRI report on the same project, 1011472, and summarizes operational experience and performance data obtained in 2005. The case study is one of several fuel cell project case studies under research by the EPRI Distributed Energy Resources Program. This case study is designed to...

2006-03-07T23:59:59.000Z

Note: This page contains sample records for the topic "bed demonstration project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


161

Final Report - Navajo Electrification Demonstration Project - FY2004  

SciTech Connect

The Navajo Electrification Demonstration Project (NEDP) is a multi-year projects which addresses the needs of unserved Navajo Nation residents without basic electricity services. The Navajo Nation is the United States' largest tribe, in terms of population and land. An estimated 18,000 Navajo Nation homes do not have basic grid-tied electricity--and this third year of funding, known as NEDP-3, provided 351 power line extensions to Navajo families.

Kenneth L. Craig, Interim General Manager

2007-03-31T23:59:59.000Z

162

Final Report - Navajo Electrification Demonstration Project - FY2004  

SciTech Connect

The Navajo Electrification Demonstration Project (NEDP) is a multi-year projects which addresses the needs of unserved Navajo Nation residents without basic electricity services. The Navajo Nation is the United States' largest tribe, in terms of population and land. An estimated 18,000 Navajo Nation homes do not have basic grid-tied electricity--and this third year of funding, known as NEDP-3, provided 351 power line extensions to Navajo families.

Kenneth L. Craig, Interim General Manager

2007-03-31T23:59:59.000Z

163

US Recovery Act Smart Grid Energy Storage Demonstration Projects | Open  

Open Energy Info (EERE)

Storage Demonstration Projects Storage Demonstration Projects Jump to: navigation, search CSV Loading map... {"format":"googlemaps3","type":"ROADMAP","types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"limit":500,"offset":0,"link":"all","sort":[""],"order":[],"headers":"show","mainlabel":"","intro":"","outro":"","searchlabel":"\u2026 further results","default":"","geoservice":"google","zoom":false,"width":"600px","height":"350px","centre":false,"layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","icon":"","visitedicon":"","forceshow":true,"showtitle":true,"hidenamespace":false,"template":false,"title":"","label":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"locations":[{"text":"

164

Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project  

NLE Websites -- All DOE Office Websites (Extended Search)

Workshop: Workshop: Compressed Natural Gas and Hydrogen Fuels: Lessons Learned for the Safe Deployment of Vehicles December 11, 2009 John Garbak, Todd Ramsden Keith Wipke, Sam Sprik, Jennifer Kurtz Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project National Renewable Energy Laboratory 2 Innovation for Our Energy Future Fuel Cell Vehicle Learning Demonstration Project Objectives and Targets * Objectives - Validate H 2 FC Vehicles and Infrastructure in Parallel - Identify Current Status and Evolution of the Technology - Objectively Assess Progress Toward Technology Readiness - Provide Feedback to H 2 Research and Development Photo: NREL Solar Electrolysis Station, Sacramento, CA Performance Measure

165

EPRI NMAC Maintainability Review of the Pebble Bed Modular Reactor Demonstration Plant  

Science Conference Proceedings (OSTI)

This report provides information to the designers of pebble bed reactor helium-driven gas turbine plants and to others who are considering the purchase of this type of plant.

2002-05-13T23:59:59.000Z

166

West Valley Demonstration Project Transportation Emergency Management Program  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

West West Valley Demonstration Project Transportation Emergency Management Program Independent Oversight Review of the Office of Independent Oversight and Performance Assurance September 2000 OVERSIGHT Table of Contents EXECUTIVE SUMMARY ................................................................... 1 1.0 INTRODUCTION ........................................................................... 4 2.0 RESULTS ......................................................................................... 7 Hazards Survey and Hazards Assessment .................................... 7 Program Plans and Procedures ..................................................... 8 Emergency Responder Performance .......................................... 10 Feedback and Continuous Improvement....................................

167

Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project: Project Overview and Fall 2006 Results (Presentation)  

DOE Green Energy (OSTI)

This presentation on NREL's Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project was given by Keith Wipke at the ZEV Technology Symposium on September 15, 2006.

Wipke, K.; Welch, C.; Thomas, H.; Sprik, S.; Gronich, S.; Garbak, J.; Hooker, D.

2006-09-01T23:59:59.000Z

168

West Valley Demonstration Project Administrative Consent Order, August 27, 1996  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Project (WVDP) Adminstrative Consent Order, August 27, 1.. Page 1 of 15 Project (WVDP) Adminstrative Consent Order, August 27, 1.. Page 1 of 15 EM Home | Regulatory Compliance | Environmental Compliance Agreements West Valley Demonstration Project (WVDP) Adminstrative Consent Order, August 27, 1996 NEW YORK STATE DEPARTMENT OF ENVIRONMENTAL CONSERVATION AND THE UNITED STATES DEPARTMENT OF ENERGY EPA ID NUMBER NYD980779540 In the Matter of | | UNITED STATES | ORDER DEPARTMENT OF ENERGY, | Docket No. __________ | RESPONDENT | ___________________________| Table of Contents Parties Jurisdiction Purpose and Scope Statement of Facts & Conclusions of Law I. Implementation of the STP II Annual Updates III. Establishing Milestones and Planning Schedule Activity IV. Covered Matters V. Inclusion of New Waste Streams VI. Amendments VII. Project Managers

169

RADIOACTIVE DEMONSTRATIONS OF FLUIDIZED BED STEAM REFORMING WITH ACUTAL HANFORD LOW ACTIVITY WASTES VERIFYING FBSR AS A SUPPLEMENTARY TREATMENT  

SciTech Connect

The U.S. Department of Energy's Office of River Protection is responsible for the retrieval, treatment, immobilization, and disposal of Hanford's tank waste. Currently there are approximately 56 million gallons of highly radioactive mixed wastes awaiting treatment. A key aspect of the River Protection Project cleanup mission is to construct and operate the Waste Treatment and Immobilization Plant (WTP). The WTP will separate the tank waste into high-level waste (HLW) and low-activity waste (LAW) fractions, both of which will subsequently be vitrified. The projected throughput capacity of the WTP LAW Vitrification Facility is insufficient to complete the cleanup mission in the time frame required by the Hanford Federal Facility Agreement and Consent Order, also known as the Tri-Party Agreement (TPA). Therefore, Supplemental Treatment is required both to meet the TPA treatment requirements as well as to more cost effectively complete the tank waste treatment mission. Fluidized Bed Steam Reforming (FBSR) is one of the supplementary treatments being considered. FBSR offers a moderate temperature (700-750 C) continuous method by which LAW and other secondary wastes can be processed irrespective of whether they contain organics, nitrates/nitrites, sulfates/sulfides, chlorides, fluorides, and/or radio-nuclides like I-129 and Tc-99. Radioactive testing of Savannah River LAW (Tank 50) shimmed to resemble Hanford LAW and actual Hanford LAW (SX-105 and AN-103) have produced a ceramic (mineral) waste form which is the same as the non-radioactive waste simulants tested at the engineering scale. The radioactive testing demonstrated that the FBSR process can retain the volatile radioactive components that cannot be contained at vitrification temperatures. The radioactive and nonradioactive mineral waste forms that were produced by co-processing waste with kaolin clay in an FBSR process are shown to be as durable as LAW glass.

Jantzen, C.; Crawford, C.; Burket, P.; Bannochie, C.; Daniel, G.; Nash, C.; Cozzi, A.; Herman, C.

2012-01-12T23:59:59.000Z

170

Solar Two: A successful power tower demonstration project  

DOE Green Energy (OSTI)

Solar Two, a 10MWe power tower plant in Barstow, California, successfully demonstrated the production of grid electricity at utility-scale with a molten-salt solar power tower. This paper provides an overview of the project, from inception in 1993 to closure in the spring of 1999. Included are discussions of the goals of the Solar Two consortium, the planned-vs.-actual timeline, plant performance, problems encountered, and highlights and successes of the project. The paper concludes with a number of key results of the Solar Two test and evaluation program.

REILLY,HUGH E.; PACHECO,JAMES E.

2000-03-02T23:59:59.000Z

171

Expedited Technology Demonstration Project Baseline Revision 3.0  

SciTech Connect

The Expedited Technology Demonstration Project Plan, MWNT Revised Baseline 3.0, replaces and significantly modifies the current baseline. The revised plan will focus efforts specifically on the demonstration of an integrated Molten Salt Oxidation (MSO) system. In addition to the MSO primary unit, offgas, and salt recycle subsystems, the demonstrations will include the generation of robust final forms from process mineral residues. A simplified process flow chart for the expedited demonstration is shown. To minimize costs and to accelerate the schedule for deployment, the integrated system will be staged in an existing facility at LLNL equipped to handle hazardous and radioactive materials. The MSO systems will be activated in FY97, followed by the activation of final forms in FY98.

Adamson, M.G.; Densley, P.J.

1996-10-01T23:59:59.000Z

172

Alaska village demonstration projects. Report to the Congress  

SciTech Connect

The Alaska Village Demonstration Projects (AVDP) were authorized by Section 113, P.L. 92-500 (86 STAT 816), for the purpose of demonstrating methods to improve sanitary conditions in native villages of Alaska. Central community facilities have been constructed in the native villages of Emmonak and Wainwright to provide a safe water supply; toilets, bathing, and laundry facilities; and sewage and solid waste disposal. Although there has not been enough time to allow full operation and evaluation of these facilities, it is apparent that the technology is available to provide these basic utility services to the demonstration villages. A major issue still to be addressed is the lack of clear responsibility for the operation and maintenance of the facilities after the Environmental Protection Agency demonstration program is completed. Adequate local resources to operate the installations are lacking. Continued experience with the AVDP is needed to complete evaluation and develop recommendations in relation to the establishment of a statewide program.

1973-07-01T23:59:59.000Z

173

FISCHER-TROPSCH FUELS PRODUCTION AND DEMONSTRATION PROJECT  

DOE Green Energy (OSTI)

This project has two primary purposes: (1) Build a small-footprint (SFP) fuel production plant to prove the feasibility of this relatively transportable technology on an intermediate scale (i.e. between laboratory-bench and commercial capacity) and produce as much as 150,000 gallons of hydrogen-saturated Fischer-Tropsch (FT) diesel fuel; and (2) Use the virtually sulfur-free fuel produced to demonstrate (over a period of at least six months) that it can not only be used in existing diesel engines, but that it also can enable significantly increased effectiveness and life of the next-generation exhaust-after-treatment emission control systems that are currently under development and that will be required for future diesel engines. Furthermore, a well-to-wheels economic analysis will be performed to characterize the overall costs and benefits that would be associated with the actual commercial production, distribution and use of such FT diesel fuel made by the process under consideration, from the currently underutilized (or entirely un-used) energy resources targeted, primarily natural gas that is stranded, sub-quality, off-shore, etc. During the first year of the project, which is the subject of this report, there have been two significant areas of progress: (1) Most of the preparatory work required to build the SFP fuel-production plant has been completed, and (2) Relationships have been established, and necessary project coordination has been started, with the half dozen project-partner organizations that will have a role in the fuel demonstration and evaluation phase of the project. Additional project tasks directly related to the State of Alaska have also been added to the project. These include: A study of underutilized potential Alaska energy resources that could contribute to domestic diesel and distillate fuel production by providing input energy for future commercial-size SFP fuel production plants; Demonstration of the use of the product fuel in a heavy-duty diesel vehicle during the Alaska winter; a comparative study of the cold-starting characteristics of FT and conventional diesel fuel; and demonstration of the use of the fuel to generate electricity for rural Alaskan villages using both a diesel generator set, and a reformer-equipped fuel cell.

Stephen P. Bergin

2003-04-23T23:59:59.000Z

174

NETL: News Release - DOE-Supported Project Demonstrates Benefits of  

NLE Websites -- All DOE Office Websites (Extended Search)

DOE-Supported Project Demonstrates Benefits of Constructed Wetlands to Treat Non-Traditional Water Sources DOE-Supported Project Demonstrates Benefits of Constructed Wetlands to Treat Non-Traditional Water Sources Flue gas desulfurization water was treated in a constructed wetlands system consisting of five reactors planted with vegetation found in natural wetlands. The water to be treated was received from an operating coal-fired power plant in the south-eastern United States. Flue gas desulfurization water was treated in a constructed wetlands system consisting of five "reactors" planted with vegetation found in natural wetlands. The water to be treated was received from an operating coal-fired power plant in the south-eastern United States. Washington, DC - In a pilot-scale test supported by the U.S. Department of Energy (DOE) Office of Fossil Energy, Clemson University researchers

175

West Valley Demonstration Project High-Level Waste Management  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

DRAFT_19507_1 DRAFT_19507_1 High-Level Waste Management Bryan Bower, DOE Director - WVDP DOE High-Level Waste Corporate Board Meeting Savannah River Site April 1, 2008 West Valley Demonstration Project West Valley Demonstration Project DRAFT_19507_2 West Valley High-Level Waste To solidify the radioactive material from approximately 600,000 gallons of high-level radioactive waste into a durable, high-quality glass, both a pretreatment system to remove salts and sulfates from the waste and a vitrification system/process were designed. To solidify the radioactive material from approximately 600,000 gallons of high-level radioactive waste into a durable, high-quality glass, both a pretreatment system to remove salts and sulfates from the waste and a vitrification system/process were designed.

176

300kW Energy Storage Demonstration Project  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

kW Energy Storage Demonstration kW Energy Storage Demonstration Project Technical Overview Presented at: Annual Doe Peer Review Meeting ─ 2008 DOE Energy Storage & Power Electronics Research Programs By Ib I. Olsen September 29, 2008 116 John Street - Suite 2320 New York, New York 10038 (p) 1.212.732.5507 (f) 1.212.732.5597 www.gaiapowertech.com This project is part of the Joint Energy Storage Initiative between the New York State Energy Research and Development Authority (NYSERDA) and the Energy Storage Systems Program of the U.S. Department of Energy (DOE/ESS), and managed by Sandia National Laboratories (SNL). Sandia is a multi-program laboratory operated by Sandia Corporation, a Lockheed Martin Company, for the United States Department of Energy's National Nuclear Security Administration, under contract DE-AC04-94AL85000

177

Duke Energy Notrees Wind Storage Demonstration Project: 2013 Interim Report  

Science Conference Proceedings (OSTI)

This Electric Power Research Institute (EPRI) technical update is an interim report summarizing the status of Duke Energys Notrees Wind Storage Demonstration Project, which involves integrating a 36-MW battery energy storage system (BESS) from Xtreme Power with the152.6-MW Notrees Wind Farm. Xtreme Powers solid lead-acid battery represents one of an emerging number of energy storage devices endowed with the potential to serve multiple value-added utility applications. ...

2013-12-19T23:59:59.000Z

178

Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project  

DOE Green Energy (OSTI)

General Motors, LLC and energy partner Shell Hydrogen, LLC, deployed a system of hydrogen fuel cell electric vehicles integrated with a hydrogen fueling station infrastructure to operate under real world conditions as part of the U.S. Department of Energy's Controlled Hydrogen Fleet and Infrastructure Validation and Demonstration Project. This technical report documents the performance and describes the learnings from progressive generations of vehicle fuel cell system technology and multiple approaches to hydrogen generation and delivery for vehicle fueling.

Stottler, Gary

2012-02-08T23:59:59.000Z

179

Distributed Energy Resources Integration in the Smart Grid Demonstration Project  

Science Conference Proceedings (OSTI)

In an effort to answer some of the basic system architecture questions posed by members, EPRI undertook a survey to find, among members that have smart grid demonstration projects, what the basic system architecture strategy was and basic concerns that may have architectural implications for their Distributed Energy Resource (DER) deployments. To that end, a longitudinal survey was designed to determine the basic demographics of the community, e.g. number of DER devices being deployed, the basic ...

2012-11-14T23:59:59.000Z

180

Final Environmental Impact Statement for the JEA Circulating Fluidized Bed Combustor Project  

SciTech Connect

This EIS assesses environmental issues associated with constructing and demonstrating a project that would be cost-shared by DOE and JEA (formerly the Jacksonville Electric Authority) under the Clean Coal Technology Program. The project would demonstrate circulating fluidized bed (CFB) combustion technology at JEA's existing Northside Generating Station in Jacksonville, Florida, about 9 miles northeast of the downtown area of Jacksonville. The new CFB combustor would use coal and petroleum coke to generate nearly 300 MW of electricity by repowering the existing Unit 2 steam turbine, a 297.5-MW unit that has been out of service since 1983. The proposed project is expected to demonstrate emission levels of sulfur dioxide (SO{sub 2}), oxides of nitrogen (NO{sub x}), and particulate matter that would be lower than Clean Air Act limits while at the same time producing power more efficiently and at less cost than conventional coal utilization technologies. At their own risk, JEA has begun initial construction activities without DOE funding. Construction would take approximately two years and, consistent with the original JEA schedule, would be completed in December 2001. Demonstration of the proposed project would be conducted during a 2-year period from March 2002 until March 2004. In addition, JEA plans to repower the currently operating Unit 1 steam turbine about 6 to 12 months after the Unit 2 repowering without cost-shared funding from DOE. Although the proposed project consists of only the Unit 2 repowering, this EIS analyzes the Unit 1 repowering as a related action. The EIS also considers three reasonably foreseeable scenarios that could result from the no-action alternative in which DOE would not provide cost-shared funding for the proposed project. The proposed action, in which DOE would provide cost-shared finding for the proposed project, is DOE's preferred alternative. The EIS evaluates the principal environmental issues, including air quality, traffic, noise, and ecological resources, that could result from construction and operation of the proposed project. Key findings include that maximum modeled increases in ground-level concentrations of SO{sub 2} nitrogen dioxide (NO{sub 2}), and particulate matter (for the proposed project alone or in conjunction with the related action) would always be less than 10% of their corresponding standards for increases in pollutants. For potential cumulative air quality impacts, results of modeling regional sources and the proposed project indicate that the maximum 24-hour average SO{sub 2} concentration would closely approach (i.e., 97%) but not exceed the corresponding Florida standard. After the Unit 1 repowering, results indicate that the maximum 24-hour average SO{sub 2} concentration would be 91% of the Florida standard. Concentrations for other averaging periods and pollutants would be lower percentages of their standards. Regarding toxic air pollutants from the proposed project, the maximum annual cancer risk to a member of the public would be approximately 1 in 1 million; given the conservative assumptions in the estimate, the risk would probably be less. With regard to threatened and endangered species, impacts to manatees, gopher tortoises, and other species would be negligible or non-existent. Construction-induced traffic would result in noticeable congestion. In the unlikely event that all coal were transported by rail, up to 3 additional trains per week would exacerbate impacts associated with noise, vibration, and blocked roads at on-grade rail crossings. Additional train traffic could be minimized by relying more heavily on barges and ships for coal transport, which is likely to be a more economic fuel delivery mode. During construction of the proposed project, noise levels would increase from the current operational levels. Except possibly during steam blowouts and possibly during operation of equipment used to construct a nearby segment of a conveyor, construction noise should not appreciably affect the background noise of nearby residences or exceed local nois

N /A

2000-06-30T23:59:59.000Z

Note: This page contains sample records for the topic "bed demonstration project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


181

Automated Demand Response Technology Demonstration Project for Small and  

NLE Websites -- All DOE Office Websites (Extended Search)

Technology Demonstration Project for Small and Technology Demonstration Project for Small and Medium Commercial Buildings Title Automated Demand Response Technology Demonstration Project for Small and Medium Commercial Buildings Publication Type Report LBNL Report Number LBNL-4982E Year of Publication 2011 Authors Page, Janie, Sila Kiliccote, Junqiao Han Dudley, Mary Ann Piette, Albert K. Chiu, Bashar Kellow, Edward Koch, and Paul Lipkin Date Published 07/2011 Publisher CEC/LBNL Keywords demand response, emerging technologies, market sectors, medium commercial business, openadr, small commercial, small commercial business, technologies Abstract Small and medium commercial customers in California make up about 20-25% of electric peak load in California. With the roll out of smart meters to this customer group, which enable granular measurement of electricity consumption, the investor-owned utilities will offer dynamic prices as default tariffs by the end of 2011. Pacific Gas and Electric Company, which successfully deployed Automated Demand Response (AutoDR) Programs to its large commercial and industrial customers, started investigating the same infrastructures application to the small and medium commercial customers. This project aims to identify available technologies suitable for automating demand response for small-medium commercial buildings; to validate the extent to which that technology does what it claims to be able to do; and determine the extent to which customers find the technology useful for DR purpose. Ten sites, enabled by eight vendors, participated in at least four test AutoDR events per site in the summer of 2010. The results showed that while existing technology can reliably receive OpenADR signals and translate them into pre-programmed response strategies, it is likely that better levels of load sheds could be obtained than what is reported here if better understanding of the building systems were developed and the DR response strategies had been carefully designed and optimized for each site.

182

MHK Projects/Race Rocks Demonstration | Open Energy Information  

Open Energy Info (EERE)

Race Rocks Demonstration Race Rocks Demonstration < MHK Projects Jump to: navigation, search << Return to the MHK database homepage Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":5,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"500px","height":"350px","centre":false,"title":"","label":"","icon":"File:Aquamarine-marker.png","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[{"text":"","title":"","link":null,"lat":48.2844,"lon":-123.531,"alt":0,"address":"","icon":"http:\/\/prod-http-80-800498448.us-east-1.elb.amazonaws.com\/w\/images\/7\/74\/Aquamarine-marker.png","group":"","inlineLabel":"","visitedicon":""}]}

183

MHK Projects/MORILD Demonstration Plant | Open Energy Information  

Open Energy Info (EERE)

MORILD Demonstration Plant MORILD Demonstration Plant < MHK Projects Jump to: navigation, search << Return to the MHK database homepage Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":5,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"500px","height":"350px","centre":false,"title":"","label":"","icon":"File:Aquamarine-marker.png","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[{"text":"","title":"","link":null,"lat":69.8079,"lon":18.6795,"alt":0,"address":"","icon":"http:\/\/prod-http-80-800498448.us-east-1.elb.amazonaws.com\/w\/images\/7\/74\/Aquamarine-marker.png","group":"","inlineLabel":"","visitedicon":""}]}

184

LIMB Demonstraton Project Extension and Coolside Demonstration: A DOE Assessment  

NLE Websites -- All DOE Office Websites (Extended Search)

3 3 LIMB Demonstration Project Extension and Coolside Demonstration: A DOE Assessment April 2000 U.S. Department of Energy National Energy Technology Laboratory P.O. Box 880, 3610 Collins Ferry Road Morgantown, WV 26507-0880 and P.O. Box 10940, 626 Cochrans Mill Road Pittsburgh, PA 15236-0940 2 Disclaimer This report was prepared as an account of work sponsored by an agency of the United States Government. Neither the United States Government nor any agency thereof, nor any of their employees, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights. Reference therein to any specific commercial

185

West Valley Demonstration Project DOE Manual 435.1-1 Waste Incidental...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

West Valley Demonstration Project DOE Manual 435.1-1 Waste Incidental to Reprocessing Evaluations and Determinations West Valley Demonstration Project DOE Manual 435.1-1 Waste...

186

Northwest Open Automated Demand Response Technology Demonstration Project  

SciTech Connect

The Lawrence Berkeley National Laboratory (LBNL) Demand Response Research Center (DRRC) demonstrated and evaluated open automated demand response (OpenADR) communication infrastructure to reduce winter morning and summer afternoon peak electricity demand in commercial buildings the Seattle area. LBNL performed this demonstration for the Bonneville Power Administration (BPA) in the Seattle City Light (SCL) service territory at five sites: Seattle Municipal Tower, Seattle University, McKinstry, and two Target stores. This report describes the process and results of the demonstration. OpenADR is an information exchange model that uses a client-server architecture to automate demand-response (DR) programs. These field tests evaluated the feasibility of deploying fully automated DR during both winter and summer peak periods. DR savings were evaluated for several building systems and control strategies. This project studied DR during hot summer afternoons and cold winter mornings, both periods when electricity demand is typically high. This is the DRRC project team's first experience using automation for year-round DR resources and evaluating the flexibility of commercial buildings end-use loads to participate in DR in dual-peaking climates. The lessons learned contribute to understanding end-use loads that are suitable for dispatch at different times of the year. The project was funded by BPA and SCL. BPA is a U.S. Department of Energy agency headquartered in Portland, Oregon and serving the Pacific Northwest. BPA operates an electricity transmission system and markets wholesale electrical power at cost from federal dams, one non-federal nuclear plant, and other non-federal hydroelectric and wind energy generation facilities. Created by the citizens of Seattle in 1902, SCL is the second-largest municipal utility in America. SCL purchases approximately 40% of its electricity and the majority of its transmission from BPA through a preference contract. SCL also provides ancillary services within its own balancing authority. The relationship between BPA and SCL creates a unique opportunity to create DR programs that address both BPA's and SCL's markets simultaneously. Although simultaneously addressing both market could significantly increase the value of DR programs for BPA, SCL, and the end user, establishing program parameters that maximize this value is challenging because of complex contractual arrangements and the absence of a central Independent System Operator or Regional Transmission Organization in the northwest.

Kiliccote, Sila; Piette, Mary Ann; Dudley, Junqiao

2010-03-17T23:59:59.000Z

187

West Valley Demonstration Project Waste Management Environmental Impact Statement  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

SUMMARY April 2003 Prepared by: U.S. Department of Energy West Valley Area Office West Valley, NY For general questions or to request a copy of this EIS, please contact: DANIEL W. SULLIVAN, DOCUMENT MANAGER DOE WEST VALLEY AREA OFFICE P.O. BOX 191 WEST VALLEY, NY 14171-0191 1-800-633-5280 COVER SHEET Lead Agency: U.S. Department of Energy Title: Draft West Valley Demonstration Project Waste Management Environmental Impact Statement, Cattaraugus County, West Valley, New York. Contact: For further information about this Environmental Impact Statement, contact: For general information on the Department of Energy's process for implementing the National Environmental Policy Act, contact: Daniel W. Sullivan Document Manager DOE West Valley Area Office

188

LIFAC Sorbent Injection Desulfurization Demonstration Project: A DOE Assessment  

NLE Websites -- All DOE Office Websites (Extended Search)

41 41 LIFAC Sorbent Injection Desulfurization Demonstration Project: A DOE Assessment January 2001 U.S. Department of Energy National Energy Technology Laboratory P.O. Box 880, 3610 Collins Ferry Road Morgantown, WV 26507-0880 and P.O. Box 10940, 626 Cochrans Mill Road Pittsburgh, PA 15236-0940 website: www.netl.doe.gov Disclaimer 2 Disclaimer This report was prepared as an account of work sponsored by an agency of the United States Government. Neither the United States Government nor any agency thereof, nor any of their employees, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights. Reference

189

Advanced Flue Gas Desulfurization (AFGD) Demonstration Project, A DOE Assessment  

NLE Websites -- All DOE Office Websites (Extended Search)

8 8 Advanced Flue Gas Desulfurization (AFGD) Demonstration Project A DOE Assessment August 2001 U.S. Department of Energy National Energy Technology Laboratory P.O. Box 880, 3610 Collins Ferry Road Morgantown, WV 26507-0880 and P.O. Box 10940, 626 Cochrans Mill Road Pittsburgh, PA 15236-0940 website: www.netl.doe.gov 2 Disclaimer This report was prepared as an account of work sponsored by an agency of the United States Government. Neither the United States Government nor any agency thereof, nor any of their employees, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights. Reference

190

West Valley Demonstration Project Waste Management Environmental Impact Statement  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

April 2003 Prepared by: U.S. Department of Energy West Valley Area Office West Valley, NY For general questions or to request a copy of this EIS, please contact: DANIEL W. SULLIVAN, DOCUMENT MANAGER DOE-WEST VALLEY AREA OFFICE P.O. BOX 191 WEST VALLEY, NY 14171-0191 1-800-633-5280 COVER SHEET Lead Agency: U.S. Department of Energy Title: Draft West Valley Demonstration Project Waste Management Environmental Impact Statement, Cattaraugus County, West Valley, New York. Contact: For further information about this Environmental Impact Statement, contact: For general information on the Department of Energy's process for implementing the National Environmental Policy Act, contact: Daniel W. Sullivan Document Manager DOE-West Valley Area Office

191

Uranium soils integrated demonstration: Soil characterization project report  

Science Conference Proceedings (OSTI)

An Integrated Demonstration Program, hosted by the Fernald Environmental Management Project (FEMP), has been established for investigating technologies applicable to the characterization and remediation of soils contaminated with uranium. Critical to the design of relevant treatment technologies is detailed information on the chemical and physical characteristics of the uranium waste-form. To address this need a soil sampling and characterization program was initiated which makes use of a variety of standard analytical techniques coupled with state-of-the-art microscopy and spectroscopy techniques. Sample representativeness is evaluated through the development of conceptual models in an effort to identify and understand those geochemical processes governing the behavior of uranium in FEMP soils. Many of the initial results have significant implications for the design of soil treatment technologies for application at the FEMP.

Cunnane, J.C. [Argonne National Lab., IL (United States); Gill, V.R. [Fernald Environmental Restoration Management Corp., Cincinnati, OH (United States); Lee, S.Y. [Oak Ridge National Lab., TN (United States); Morris, D.E. [Los Alamos National Lab., NM (United States); Nickelson, M.D. [HAZWRAP, Oak Ridge, TN (United States); Perry, D.L. [Lawrence Berkeley Lab., CA (United States); Tidwell, V.C. [Sandia National Labs., Albuquerque, NM (United States)

1993-08-01T23:59:59.000Z

192

Electric G-Van demonstration and commercial assessment project  

DOE Green Energy (OSTI)

The Electric Power Research Institute was awarded this grant to continue the joint effort initiated by EPRI, and VE International to proceed beyond the prototype phase of the electric G-Van development. The goal of EPRI and VEHMA was to develop a market for the electric G-Van, and to distribute them to commercial fleet operators. The objective of this project was to produce G-Vans in a production facility that would be comparable to the GMC Truck internal combustion engine Vandura Van produced by General Motors in quality, reliability, durability and safety. An initial market assessment/demonstration phase of sixty (60) vehicles was to be undertaken, with the ability to expand production volume quickly to meet market demands. Brief description of each task of this grant is given and the actions taken by EPRI to complete them.

Braga, B.D. (Electric Power Research Inst., Palo Alto, CA (United States))

1992-12-01T23:59:59.000Z

193

Geothermal project summaries. Geothermal energy research, development, and demonstration program  

SciTech Connect

The Division of Geothermal Energy ''Geothermal Project Summaries'' provides pertinent information on each active ERDA Geothermal project, includes a listing of all contractors and a compilation of completed projects. New project summaries and necessary revisions to current project data will be prepared on a quarterly basis.

1976-04-01T23:59:59.000Z

194

Geothermal project summaries. Geothermal energy research, development, and demonstration program  

DOE Green Energy (OSTI)

The Division of Geothermal Energy ''Geothermal Project Summaries'' provides pertinent information on each active ERDA Geothermal project, includes a listing of all contractors and a compilation of completed projects. New project summaries and necessary revisions to current project data will be prepared on a quarterly basis.

Not Available

1976-04-01T23:59:59.000Z

195

NETL: Clean Coal Technology Demonstration Program (CCTDP) - Round...  

NLE Websites -- All DOE Office Websites (Extended Search)

3 Advanced Electric Power Generation - Fluidized Bed Combustion McIntosh Unit 4A PCFB Demonstration Project - Project Brief PDF-186KB Lakeland Department of Electric & Water,...

196

Construction Cost Analysis : Residential Construction Demonstration Project Cycle II.  

SciTech Connect

The Residential Construction Demonstration Project (RCDP) is designed to demonstrate new residential building techniques and product innovations which advance the stage-of-the-art in constructing energy-efficient electrically heated residences. A secondary purpose is to obtain documented cost and energy savings data from which to make accurate assessments of the cost-effectiveness of various conservation innovations. The project solicits participation of regional homebuilders by offering them financial incentives for constructing homes to the Model Conservation Standards (MCS) and including at least one innovation.'' The innovations are determined by BPA and the States prior to construction and represent construction techniques or energy saving products that might reduce the cost of building MCS homes, or expand the options available to builders in achieving MCS levels of energy efficiency in homes. Besides covering some of the additional risk for employing the innovation, the incentive payment guarantees that builders will provide certain amounts of information regarding the cost and acceptability of building the homes. In addition, an incentive is paid to homeowners for their participation in data collection efforts following construction. Several one-time'' tests were performed on the houses and homeowners were required to report energy consumption and temperature data on a weekly basis for approximately 18 months. BPA and the States compile the information obtained from the builders and homeowners. Access to this data is provided for the purpose of analyzing the cost and performance of the RCDP homes, as well as understanding the value of the various innovations that are tested. 25 tabs., 4 figs.

Barnett, Cole; Thor, Philip W.

1990-06-01T23:59:59.000Z

197

New Mexico State University Campus geothermal demonstration project  

DOE Green Energy (OSTI)

This report presents the design, construction highlights, and performance of the New Mexico State University Campus Geothermal Demonstration Project at Las Cruces, New Mexico. Construction started in July 1981, first system use was January 1982, and the system was dedicated on April 21, 1982. Included herein are summary observations after two years of use. The geothermal hot water from New Mexico State University wells is used to heat potable water, which in turn provides 83 percent of the domestic hot water on the New Mexico State University campus, as well as space heat to two buildings, and for two heated swimming pools. The original system is providing service to 30 total buildings, with two additional buildings (150,000 square feet) in process of geothermal conversion.) The system overall performance has been excellent, except for geothermal well pump problems. In terms of operating efficiency, the system has exceeded the design parameters. In spite of abnormally high costs for well and pump repairs, the system has shown a positive cost avoidance of more than $118,000 for the first year of operation. For the first two full years of operation, the system has produced a net positive cost avoidance of more than $200,000. Payback on the total investment of $1,670,000 is projected to be 6 to 10 years, depending on the future prices of natural gas and electricity.

Cuniff, R.A.; Fisher, K.P.; Chintawongvanich, P.

1984-04-01T23:59:59.000Z

198

PSNH's Northern Wood power project repowers coal-fired plant with new fluidized-bed combustor  

SciTech Connect

The Northern Wood Power project permanently replaced a 50-MW coal-burning boiler (Unit 5) at Public Service of New Hampshire's Schiller station with a state-of-the-art circulating fluidized bed wood-burning boiler of the same capacity. The project, completed in December 2006, reduced emissions and expanded the local market for low-grade wood. For planning and executing the multiyear, $75 million project at no cost to its ratepayers, PSNH wins Power's 2007 Marmaduke Award for excellence in O & M. The award is named for Marmaduke Surfaceblow, the fictional marine engineer/plant troubleshoot par excellence. 7 figs., 1 tab.

Peltier, R.

2007-08-15T23:59:59.000Z

199

Locomotive Emission and Engine Idle Reduction Technology Demonstration Project  

DOE Green Energy (OSTI)

In response to a United States Department of Energy (DOE) solicitation, the Maryland Energy Administration (MEA), in partnership with CSX Transportation, Inc. (CSXT), submitted a proposal to DOE to support the demonstration of Auxiliary Power Unit (APU) technology on fifty-six CSXT locomotives. The project purpose was to demonstrate the idle fuel savings, the Nitrous Oxide (NOX) emissions reduction and the noise reduction capabilities of the APU. Fifty-six CSXT Baltimore Division locomotives were equipped with APUs, Engine Run Managers (ERM) and communications equipment to permit GPS tracking and data collection from the locomotives. Throughout the report there is mention of the percent time spent in the State of Maryland. The fifty-six locomotives spent most of their time inside the borders of Maryland and some spent all their time inside the state borders. Usually when a locomotive traveled beyond the Maryland State border it was into an adjoining state. They were divided into four groups according to assignment: (1) Power Unit/Switcher Mate units, (2) Remote Control units, (3) SD50 Pusher units and (4) Other units. The primary data of interest were idle data plus the status of the locomotive--stationary or moving. Also collected were main engine off, idling or working. Idle data were collected by county location, by locomotive status (stationary or moving) and type of idle (Idle 1, main engine idling, APU off; Idle 2, main engine off, APU on; Idle 3, main engine off, APU off; Idle 4, main engine idle, APU on). Desirable main engine idle states are main engine off and APU off or main engine off and APU on. Measuring the time the main engine spends in these desirable states versus the total time it could spend in an engine idling state allows the calculation of Percent Idle Management Effectiveness (%IME). IME is the result of the operation of the APU plus the implementation of CSXT's Warm Weather Shutdown Policy. It is difficult to separate the two. The units demonstrated an IME of 64% at stationary idle for the test period. The data collected during calendar year 2004 demonstrated that 707,600 gallons of fuel were saved and 285 tons of NOX were not emitted as a result of idle management in stationary idle, which translates to 12,636 gallons and 5.1 tons of NOx per unit respectively. The noise reduction capabilities of the APU demonstrated that at 150 feet from the locomotive the loaded APU with the main engine shut down generated noise that was only marginally above ambient noise level.

John R. Archer

2005-03-14T23:59:59.000Z

200

U.S. Fuel Cell Electric Vehicle Demonstration Project 2010 Status Update (Presentation)  

DOE Green Energy (OSTI)

This presentation summarizes U.S. Fuel Cell Electric Vehicle Demonstration Project 2010 Status Update.

Wipke, K.; Sprik, S.; Kurtz, J.; Ramsden, T.

2010-10-21T23:59:59.000Z

Note: This page contains sample records for the topic "bed demonstration project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


201

INTEGRATED GASIFICATION COMBINED CYCLE PROJECT 2 MW FUEL CELL DEMONSTRATION  

DOE Green Energy (OSTI)

With about 50% of power generation in the United States derived from coal and projections indicating that coal will continue to be the primary fuel for power generation in the next two decades, the Department of Energy (DOE) Clean Coal Technology Demonstration Program (CCTDP) has been conducted since 1985 to develop innovative, environmentally friendly processes for the world energy market place. The 2 MW Fuel Cell Demonstration was part of the Kentucky Pioneer Energy (KPE) Integrated Gasification Combined Cycle (IGCC) project selected by DOE under Round Five of the Clean Coal Technology Demonstration Program. The participant in the CCTDP V Project was Kentucky Pioneer Energy for the IGCC plant. FuelCell Energy, Inc. (FCE), under subcontract to KPE, was responsible for the design, construction and operation of the 2 MW fuel cell power plant. Duke Fluor Daniel provided engineering design and procurement support for the balance-of-plant skids. Colt Engineering Corporation provided engineering design, fabrication and procurement of the syngas processing skids. Jacobs Applied Technology provided the fabrication of the fuel cell module vessels. Wabash River Energy Ltd (WREL) provided the test site. The 2 MW fuel cell power plant utilizes FuelCell Energy's Direct Fuel Cell (DFC) technology, which is based on the internally reforming carbonate fuel cell. This plant is capable of operating on coal-derived syngas as well as natural gas. Prior testing (1992) of a subscale 20 kW carbonate fuel cell stack at the Louisiana Gasification Technology Inc. (LGTI) site using the Dow/Destec gasification plant indicated that operation on coal derived gas provided normal performance and stable operation. Duke Fluor Daniel and FuelCell Energy developed a commercial plant design for the 2 MW fuel cell. The plant was designed to be modular, factory assembled and truck shippable to the site. Five balance-of-plant skids incorporating fuel processing, anode gas oxidation, heat recovery, water treatment/instrument air, and power conditioning/controls were built and shipped to the site. The two fuel cell modules, each rated at 1 MW on natural gas, were fabricated by FuelCell Energy in its Torrington, CT manufacturing facility. The fuel cell modules were conditioned and tested at FuelCell Energy in Danbury and shipped to the site. Installation of the power plant and connection to all required utilities and syngas was completed. Pre-operation checkout of the entire power plant was conducted and the plant was ready to operate in July 2004. However, fuel gas (natural gas or syngas) was not available at the WREL site due to technical difficulties with the gasifier and other issues. The fuel cell power plant was therefore not operated, and subsequently removed by October of 2005. The WREL fuel cell site was restored to the satisfaction of WREL. FuelCell Energy continues to market carbonate fuel cells for natural gas and digester gas applications. A fuel cell/turbine hybrid is being developed and tested that provides higher efficiency with potential to reach the DOE goal of 60% HHV on coal gas. A system study was conducted for a 40 MW direct fuel cell/turbine hybrid (DFC/T) with potential for future coal gas applications. In addition, FCE is developing Solid Oxide Fuel Cell (SOFC) power plants with Versa Power Systems (VPS) as part of the Solid State Energy Conversion Alliance (SECA) program and has an on-going program for co-production of hydrogen. Future development in these technologies can lead to future coal gas fuel cell applications.

FuelCell Energy

2005-05-16T23:59:59.000Z

202

DIMETHYL ETHER (DME)-FUELED SHUTTLE BUS DEMONSTRATION PROJECT  

DOE Green Energy (OSTI)

The objectives of this research and demonstration program are to convert a campus shuttle bus to operation on dimethyl ether, a potential ultra-clean alternative diesel fuel. To accomplish this objective, this project includes laboratory evaluation of a fuel conversion strategy, as well as field demonstration of the DME-fueled shuttle bus. Since DME is a fuel with no lubricity (i.e., it does not possess the lubricating quality of diesel fuel), conventional fuel delivery and fuel injection systems are not compatible with dimethyl ether. Therefore, to operate a diesel engine on DME one must develop a fuel-tolerant injection system, or find a way to provide the necessary lubricity to the DME. In this project, they have chosen the latter strategy in order to achieve the objective with minimal need to modify the engine. The strategy is to blend DME with diesel fuel, to obtain the necessary lubricity to protect the fuel injection system and to achieve low emissions. Within the Combustion Laboratory of the Penn State Energy Institute, they have installed and equipped a Navistar V-8 direct-injection turbodiesel engine for measurement of gaseous and particulate emissions and examination of the impact of fuel composition on diesel combustion. They have also reconfigured a high-pressure viscometer for studies of the viscosity, bulk modulus (compressibility) and miscibility of blends of diesel fuel, dimethyl ether and lubricity additives. The results include baseline emissions, performance and combustion measurements on the Navistar engine for operation on a federal low sulfur diesel fuel (300 ppm S). Most recently, they have examined blends of an oxygenated fuel additive (a liquid fuel called CETANER{trademark}) produced by Air Products, for comparison with dimethyl ether blended at the same weight of oxygen addition, 2 wt.%. While they have not operated the engine on DME yet, they are now preparing to do so. A fuel system for delivery of DME/Diesel blends has been configured and initial investigations at low DME blend ratios (around 5-10 vol%) will begin shortly. They have also performed viscosity measurements on diesel fuel, DME and 50-50 blends of DME in diesel. These tests have verified that DME has a much lower viscosity than the diesel fuel and that the viscosity of the blended fuel is also much lower than the diesel base fuel. This has implications for the injection and atomization of the DME/diesel blends.

Elana M. Chapman; Shirish Bhide; Andre L. Boehman; David Klinikowski

2003-04-01T23:59:59.000Z

203

West Valley Demonstration Project Waste Management Final Environmental Impact Statement  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

WVDP Waste Management EIS WVDP Waste Management EIS S-3 Figure S-1. Location of the West Valley Demonstration Project Not to scale Final WVDP Waste Management EIS S-23 Table S-2. Summary of Normal Operational Impacts at West Valley Impact Area Unit of Measure No Action Alternative Alternative A - Preferred Alternative B Human Health Impacts a Public Impacts from Ongoing Operations MEI LCF 3.7 × 10 -7 3.7 × 10 -7 3.7 × 10 -7 Population LCF 1.5 × 10 -3 1.5 × 10 -3 1.5 × 10 -3 Worker Impacts Involved worker MEI LCF 3.4 × 10 -4 1.3 × 10 -3 1.3 × 10 -3 Noninvolved worker MEI LCF 3.0 × 10 -4 3.0 × 10 -4 3.0 × 10 -4 Involved worker population LCF 2.1 × 10 -3 0.031 0.031 Noninvolved worker population LCF 0.075 0.075 0.075 Total worker population LCF 0.077 0.11 0.11

204

Demonstration Project 111, ITS/CVO Technology Truck, Final Project Report  

DOE Green Energy (OSTI)

In 1995, the planning and building processes began to design and develop a mobile demonstration unit that could travel across the nation and be used as an effective outreach tool. In 1997, the unit was completed; and from June 1997 until December 2000, the Federal Highway Administration (FHWA)/Federal Motor Carrier Safety Administration (FMCSA) mobilized the Technology Truck, also known as Demonstration Project No. 111, ''Advanced Motor Carrier Operations and Safety Technologies.'' The project featured the latest available state-of-the-practice intelligent transportation systems (ITS) technologies designed to improve both the efficiency and safety of commercial vehicle operations (CVO). The Technology Truck was designed to inform and educate the motor carrier community and other stakeholders regarding ITS technologies, thus gaining support and buy-in for participation in the ITS program. The primary objective of the project was to demonstrate new and emerging ITS/CVO technologies and programs, showing their impact on motor carrier safety and productivity. In order to meet the objectives of the Technology Truck project, the FHWA/FMCSA formed public/private partnerships with industry and with Oak Ridge National Laboratory to demonstrate and display available ITS/CVO technologies in a cooperative effort. The mobile demonstration unit was showcased at national and regional conferences, symposiums, universities, truck shows and other venues, in an effort to reach as many potential users and decision makers as possible. By the end of the touring phase, the ITS/CVO Technology Truck had been demonstrated in 38 states, 4 Canadian provinces, 88 cities, and 114 events; been toured by 18,099 people; and traveled 115,233 miles. The market penetration for the Technology Truck exceeded 4,000,000, and the website received more than 25,000 hits. In addition to the Truck's visits, the portable ITS/CVO kiosk was demonstrated at 31 events in 23 cites in 15 states.

Gambrell, KP

2002-01-11T23:59:59.000Z

205

Geothermal project summaries. Geothermal energy research, development and demonstration program  

DOE Green Energy (OSTI)

Summaries of all Division of Geothermal Energy supported projects for which contracts have been executed are compiled. Each summary includes pertinent statistical data for that project and an abstract summarizing the project plans and accomplishments. The projects summarized fall into six categories: engineering research and development, resource exploration and assessment, hydrothermal technology applications, advanced technology applications, utilization experiments, and environmental control and institutional studies. (MHR)

Not Available

1976-09-01T23:59:59.000Z

206

DIMETHYL ETHER (DME)-FUELED SHUTTLE BUS DEMONSTRATION PROJECT  

DOE Green Energy (OSTI)

The objectives of this research and demonstration program are to convert a campus shuttle bus to operation on dimethyl ether, a potential ultra-clean alternative diesel fuel. To accomplish this objective, this project includes laboratory evaluation of a fuel conversion strategy, as well as, field demonstration of the DME-fueled shuttle bus. Since DME is a fuel with no lubricity (i.e., it does not possess the lubricating quality of diesel fuel), conventional fuel delivery and fuel injection systems are not compatible with dimethyl ether. Therefore, to operate a diesel engine on DME one must develop a fuel-tolerant injection system, or find a way to provide the necessary lubricity to the DME. In this project, they have chosen the latter strategy in order to achieve the objective with minimal need to modify the engine. Their strategy is to blend DME with diesel fuel, to obtain the necessary lubricity to protect the fuel injection system and to achieve low emissions. The bulk of the efforts over the past year were focused on the conversion of the campus shuttle bus. This process, started in August 2001, took until April 2002 to complete. The process culminated in an event to celebrate the launching of the shuttle bus on DME-diesel operation on April 19, 2002. The design of the system on the shuttle bus was patterned after the system developed in the engine laboratory, but also was subjected to a rigorous failure modes effects analysis (FMEA, referred to by Air Products as a ''HAZOP'' analysis) with help from Dr. James Hansel of Air Products. The result of this FMEA was the addition of layers of redundancy and over-pressure protection to the system on the shuttle bus. The system became operational in February 2002. Preliminary emissions tests and basic operation of the shuttle bus took place at the Pennsylvania Transportation Institute's test track facility near the University Park airport. After modification and optimization of the system on the bus, operation on the campus shuttle route began in early June 2002. However, the work and challenges continued as it has been difficult to maintain operability of the shuttle bus due to fuel and component difficulties. In late June 2002, the pump head itself developed operational problems (loss of smooth function) leading to excessive stress on the magnetic coupling and excessive current draw to operate. A new pump head was installed on the system to alleviate this problem and the shuttle bus operated successfully on DME blends from 10-25 vol% on the shuttle bus loop until September 30, 2002. During the period of operation on the campus loop, the bus was pulled from service, operated at the PTI test track and real-time emissions measurements were obtained using an on-board emissions analyzer from Clean Air Technologies International, Inc. Particulate emissions reductions of 60% and 80% were observed at DME blend ratios of 12 vol.% and 25 vol.%, respectively, as the bus was operated over the Orange County driving cycle. Increases in NOx, CO and HC emissions were observed, however. In summary, the conversion of the shuttle bus was successfully accomplished, particulate emissions reductions were observed, but there were operational challenges in the field. Nonetheless, they were able to demonstrate reliable operation of the shuttle bus on DME-diesel blends.

Elana M. Chapman; Shirish Bhide; Jennifer Stefanik; Howard Glunt; Andre L. Boehman; Allen Homan; David Klinikowski

2003-04-01T23:59:59.000Z

207

RADIOACTIVE DEMONSTRATIONS OF FLUIDIZED BED STEAM REFORMING AS A SUPPLEMENTARY TREATMENT FOR HANFORD'S LOW ACTIVITY WASTE AND SECONDARY WASTES  

SciTech Connect

The U.S. Department of Energy's Office of River Protection (ORP) is responsible for the retrieval, treatment, immobilization, and disposal of Hanford's tank waste. Currently there are approximately 56 million gallons of highly radioactive mixed wastes awaiting treatment. A key aspect of the River Protection Project (RPP) cleanup mission is to construct and operate the Waste Treatment and Immobilization Plant (WTP). The WTP will separate the tank waste into high-level and low-activity waste (LAW) fractions, both of which will subsequently be vitrified. The projected throughput capacity of the WTP LAW Vitrification Facility is insufficient to complete the RPP mission in the time frame required by the Hanford Federal Facility Agreement and Consent Order, also known as the Tri-Party Agreement (TPA), i.e. December 31, 2047. Therefore, Supplemental Treatment is required both to meet the TPA treatment requirements as well as to more cost effectively complete the tank waste treatment mission. The Supplemental Treatment chosen will immobilize that portion of the retrieved LAW that is not sent to the WTP's LAW Vitrification facility into a solidified waste form. The solidified waste will then be disposed on the Hanford site in the Integrated Disposal Facility (IDF). In addition, the WTP LAW vitrification facility off-gas condensate known as WTP Secondary Waste (WTP-SW) will be generated and enriched in volatile components such as Cs-137, I-129, Tc-99, Cl, F, and SO4 that volatilize at the vitrification temperature of 1150 C in the absence of a continuous cold cap. The current waste disposal path for the WTP-SW is to recycle it to the supplemental LAW treatment to avoid a large steady state accumulation in the pretreatment-vitrification loop. Fluidized Bed Steam Reforming (FBSR) offers a moderate temperature (700-750 C) continuous method by which LAW and/or WTP-SW wastes can be processed irrespective of whether they contain organics, nitrates, sulfates/sulfides, chlorides, fluorides, volatile radionuclides or other aqueous components. The FBSR technology can process these wastes into a crystalline ceramic (mineral) waste form. The mineral waste form that is produced by co-processing waste with kaolin clay in an FBSR process has been shown to be as durable as LAW glass. Monolithing of the granular FBSR product is being investigated to prevent dispersion during transport or burial/storage but is not necessary for performance. A Benchscale Steam Reformer (BSR) was designed and constructed at the Savannah River National Laboratory (SRNL) to treat actual radioactive wastes to confirm the findings of the non-radioactive FBSR pilot scale tests and to qualify the waste form for applications at Hanford. Radioactive testing commenced in 2010 with a demonstration of Hanford's WTP-SW where Savannah River Site (SRS) High Level Waste (HLW) secondary waste from the Defense Waste Processing Facility (DWPF) was shimmed with a mixture of I-125/129 and Tc-99 to chemically resemble WTP-SW. Ninety six grams of radioactive product were made for testing. The second campaign commenced using SRS LAW chemically trimmed to look like Hanford's LAW. Six hundred grams of radioactive product were made for extensive testing and comparison to the non-radioactive pilot scale tests. The same mineral phases were found in the radioactive and non-radioactive testing.

Jantzen, C.; Crawford, C.; Cozzi, A.; Bannochie, C.; Burket, P.; Daniel, G.

2011-02-24T23:59:59.000Z

208

FCV Learning Demonstration: Project Midpoint Status and Fall 2007 Results  

DOE Green Energy (OSTI)

Status reoprt on NREL's fuel cell vehicle learning demonstration presented at the 2007 EVS-23 meeting in Anaheim, CA.

Wipke, K.; Sprik, S.; Kurtz, J.; Thomas, H.; Garbak, J.

2007-12-01T23:59:59.000Z

209

Northwest Open Automated Demand Response Technology Demonstration Project  

SciTech Connect

Lawrence Berkeley National Laboratory (LBNL) and the Demand Response Research Center (DRRC) performed a technology demonstration and evaluation for Bonneville Power Administration (BPA) in Seattle City Light's (SCL) service territory. This report summarizes the process and results of deploying open automated demand response (OpenADR) in Seattle area with winter morning peaking commercial buildings. The field tests were designed to evaluate the feasibility of deploying fully automated demand response (DR) in four to six sites in the winter and the savings from various building systems. The project started in November of 2008 and lasted 6 months. The methodology for the study included site recruitment, control strategy development, automation system deployment and enhancements, and evaluation of sites participation in DR test events. LBNL subcontracted McKinstry and Akuacom for this project. McKinstry assisted with recruitment, site survey collection, strategy development and overall participant and control vendor management. Akuacom established a new server and enhanced its operations to allow for scheduling winter morning day-of and day-ahead events. Each site signed a Memorandum of Agreement with SCL. SCL offered each site $3,000 for agreeing to participate in the study and an additional $1,000 for each event they participated. Each facility and their control vendor worked with LBNL and McKinstry to select and implement control strategies for DR and developed their automation based on the existing Internet connectivity and building control system. Once the DR strategies were programmed, McKinstry commissioned them before actual test events. McKinstry worked with LBNL to identify control points that can be archived at each facility. For each site LBNL collected meter data and trend logs from the energy management and control system. The communication system allowed the sites to receive day-ahead as well as day-of DR test event signals. Measurement of DR was conducted using three different baseline models for estimation peak load reductions. One was three-in-ten baseline, which is based on the site electricity consumption from 7 am to 10 am for the three days with the highest consumption of the previous ten business days. The second model, the LBNL outside air temperature (OAT) regression baseline model, is based on OAT data and site electricity consumption from the previous ten days, adjusted using weather regressions from the fifteen-minute electric load data during each DR test event for each site. A third baseline that simply averages the available load data was used for sites less with less than 10 days of historical meter data. The evaluation also included surveying sites regarding any problems or issues that arose during the DR test events. Question covered occupant comfort, control issues and other potential problems.

Kiliccote, Sila; Dudley, Junqiao Han; Piette, Mary Ann

2009-08-01T23:59:59.000Z

210

Design and demonstration of an immobilized-cell fluidized-bed reactor for the efficient production of ethanol  

DOE Green Energy (OSTI)

Initial studies have been carried out using a 4 inch ID fluidized bed reactor (FBR). This medium scale FBR was designed for scale-up. Present performance was compared with results from experiments using smaller FBRs. On-line and off-line measurement systems are also described. Zymomonas mobilis was immobilized in {kappa}-carrageenan at cell loadings of 15--50 g (dry weight) L{sup {minus}1}. The system is designed for determining optimal operation with high conversion and productivity for a variety of conditions including feedstocks, temperature, flow rate, and column sizes (from 2 to 5 meters tall). The demonstration used non-sterile feedstocks containing either industrial (light steep water) or synthetic nutrients and dextrose.

Webb, O.F.; Scott, T.C.; Davison, B.H.; Scott, C.D.

1994-06-01T23:59:59.000Z

211

Next Steps for the FCEV Learning Demonstration Project (Presentation)  

DOE Green Energy (OSTI)

This presentation summarizes project goals; vehicle and H2 station deployment status, critical performance compared to targets; highlights of latest vehicle and infrastructure analysis results and progress; learning demo next steps; highlights of partner activities and summary.

Wipke, K.; Sprik, S.; Kurtz, J.; Ramsden, T.; Ainscough, C.; Saur, G.

2011-02-01T23:59:59.000Z

212

Advanced Flue Gas Desulfurization (AFGD) demonstration project: Volume 2, Project performance and economics. Final technical report  

SciTech Connect

The project objective is to demonstrate removal of 90--95% or more of the SO{sub 2} at approximately one-half the cost of conventional scrubbing technology; and to demonstrate significant reduction of space requirements. In this project, Pure Air has built a single SO{sub 2} absorber for a 528-MWe power plant. The absorber performs three functions in a single vessel: prequencher, absorber, and oxidation of sludge to gypsum. Additionally, the absorber is of a co- current design, in which the flue gas and scrubbing slurry move in the same direction and at a relatively high velocity compared to conventional scrubbers. These features all combine to yield a state- of-the-art SO{sub 2} absorber that is more compact and less expensive than conventional scrubbers. The project incorporated a number of technical features including the injection of pulverized limestone directly into the absorber, a device called an air rotary sparger located within the base of the absorber, and a novel wastewater evaporation system. The air rotary sparger combines the functions of agitation and air distribution into one piece of equipment to facilitate the oxidation of calcium sulfite to gypsum. Additionally, wastewater treatment is being demonstrated to minimize water disposal problems inherent in many high-chloride coals. Bituminous coals primarily from the Indiana, Illinois coal basin containing 2--4.5% sulfur were tested during the demonstration. The Advanced Flue Gas Desulfurization (AFGD) process has demonstrated removal of 95% or more of the SO{sub 2} while providing a commercial gypsum by-product in lieu of solid waste. A portion of the commercial gypsum is being agglomerated into a product known as PowerChip{reg_sign} gypsum which exhibits improved physical properties, easier flowability and more user friendly handling characteristics to enhance its transportation and marketability to gypsum end-users.

NONE

1996-04-30T23:59:59.000Z

213

Status of U.S. FCEV and Infrastructure Learning Demonstration Project (Presentation)  

DOE Green Energy (OSTI)

Presented at the Japan Hydrogen and Fuel Cell Demonstration Project (JHFC), 1 March 2011, Tokyo, Japan. This presentation summarizes the status of U.S. fuel cell electric vehicles and infrastructure learning demonstration project.

Wipke, K.; Sprik, S.; Kurtz, J.; Ramsden, T.; Ainscough, C.; Saur, G.

2011-03-01T23:59:59.000Z

214

The Sydney 2000 Olympic Games Forecast Demonstration Project: Forecasting, Observing Network Infrastructure, and Data Processing Issues  

Science Conference Proceedings (OSTI)

The Sydney 2000 Olympic Games World Weather Research Programme Forecast Demonstration Project (WWRP FDP) aimed to demonstrate the utility and impact of modern nowcast systems. The project focused on the use of radar processing systems and ...

Peter T. May; Thomas D. Keenan; Rod Potts; James W. Wilson; Rob Webb; Andrew Treloar; Elly Spark; Sue Lawrence; Elizabeth Ebert; John Bally; Paul Joe

2004-02-01T23:59:59.000Z

215

West Valley Demonstration Project Annual Site Environmental Report Calendar Year 2004  

SciTech Connect

Annual Site Environmental Report for the West Valley Demonstration Project (WVDP) for Calendar Year 2004. The report summarizes the environmental protection program at the West Valley Demonstration Project for CY 2004.

West Valley Nuclear Services Company (WVNSCO) and URS Group, Inc.

2005-09-30T23:59:59.000Z

216

Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project: Fall 2008  

DOE Green Energy (OSTI)

Graphs of composite data products produced by DOE's Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation project through September 2008.

Wipke, K.; Sprik, S.; Kurtz, J.; Ramsden, T.

2008-10-01T23:59:59.000Z

217

Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project: Progress Update; Preprint  

DOE Green Energy (OSTI)

Summary of DOE's Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation project from initiation through January 2006.

Wipke, K.; Welch, C.; Thomas, H.; Sprik, S.; Gronich, S.; Garbak, J.; Hooker, D.

2006-03-01T23:59:59.000Z

218

US Recovery Act Smart Grid Demonstration Projects | Open Energy Information  

Open Energy Info (EERE)

Projects Projects Jump to: navigation, search CSV Loading map... {"format":"googlemaps3","type":"ROADMAP","types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"limit":500,"offset":0,"link":"all","sort":[""],"order":[],"headers":"show","mainlabel":"","intro":"","outro":"","searchlabel":"\u2026 further results","default":"","geoservice":"google","zoom":false,"width":"600px","height":"350px","centre":false,"layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","icon":"","visitedicon":"","forceshow":true,"showtitle":true,"hidenamespace":false,"template":false,"title":"","label":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"locations":[{"text":"

219

Use of Coal Ash in Highway Construction: Michigan Demonstration Project  

Science Conference Proceedings (OSTI)

This report documents the construction and performance testing of a 3000-ft length of fly ash base under a highway shoulder. Following three years of service, the road shoulder shows no signs of premature deterioration. This report should aid utilities seeking to increase ash-use rates in highway-related projects, as well as state highway design engineers responsible for preparing construction specifications.

1991-03-05T23:59:59.000Z

220

SRC-I Project Baseline. [SRC-I demonstration project near Owensboro, Kentucky  

SciTech Connect

The Process Design Criteria Specification forms the basis for process design for the 6000-TPSD SRC-I Demonstration Plant. It sets forth: basic engineering data, e.g., type and size of plant, feedstocks, product specifications, and atmospheric emission and waste disposal limits; utility conditions; equipment design criteria and sparing philosophy; and estimating criteria for economic considerations. Previously the formal ICRC Document No. 0001-01-002 has been submitted to DOE and revised, as necessary, to be consistent with the SRC-I Project Baseline. Revision 6, dated 19 March 1982, 51 pages, was forwarded to DOE on 19 March 1982.

None

1982-03-01T23:59:59.000Z

Note: This page contains sample records for the topic "bed demonstration project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


221

Comprehensive report to Congress: Clean Coal Technology Program: Arvah B. Hopkins circulating fluidized-bed repowering project: A project proposed by: The City of Tallahassee  

Science Conference Proceedings (OSTI)

The project involves the repowering of a 250-megawatt electrical (MWe) natural gas- or oil-fired boiler with a coal-fired atmospheric circulating fluidized-bed (CFB) boiler to provide steam to an existing turbine generator. The boiler will be the largest of its type. After construction and shakedown, the City of Tallahassee (CoT) plant will be operated for 24 months with at least three different eastern coals. Final coal selection will be based on the Fuels Selection Study, which is part of Phase I-A of the project. Cost, financial, and technical data from the CoT CFB will be provided the utility industry for evaluation of a 250-MWe CFB as a commercially viable clean coal alternative. The objective of the Arvah B. Hopkins CFB Repowering Project is to demonstrate an efficient, economical, and environmentally superior method of generating electric power from coal. The work to be performed under the Cooperative Agreement includes the design, construction, and operation of the demonstration plant. 4 figs.

Not Available

1990-10-01T23:59:59.000Z

222

Tidd PFBC Demonstration Project. Final report, March 1, 1994--March 30, 1995  

Science Conference Proceedings (OSTI)

The Tidd Pressurized Fluidized Bed Combustion (PFBC) Demonstration Plant was the first utility-scale pressurized fluidized bed combustor to operate in combined-cycle mode in the US. The 45-year old pulverized coal plant was repowered with PFBC components in order to demonstrate that PFBC combined-cycle technology is an economic, reliable, and environmentally superior alternative to conventional technology in using high-sulfur coal to generate electricity. The three-year demonstration period started on February 28, 1991 and terminated on February 28, 1994. The fourth year of testing started on March 1, 1994 and terminated on March 30, 1995. This report reviews the experience of the 70-MW(e), Tidd PFBC Demonstration Plant during the fourth year of operation.

Bauer, D.A.; Hoffman, J.D.; Marrocco, M.; Mudd, M.J.; Reinhart, W.P.; Stogran, H.K. [American Electric Power Service Corp., Columbus, OH (United States)

1995-08-01T23:59:59.000Z

223

West Valley Demonstration Project Prepares to Relocate High-Level Waste |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

West Valley Demonstration Project Prepares to Relocate High-Level West Valley Demonstration Project Prepares to Relocate High-Level Waste West Valley Demonstration Project Prepares to Relocate High-Level Waste December 24, 2013 - 12:00pm Addthis The West Valley Demonstration Project’s high-level waste canisters will be relocated to interim onsite storage. The West Valley Demonstration Project's high-level waste canisters will be relocated to interim onsite storage. The first group of eight concrete storage casks for the West Valley Demonstration Project’s high-level waste. The first group of eight concrete storage casks for the West Valley Demonstration Project's high-level waste. Site subcontractor American DND completed demolition of the contaminated 01-14 Building in 2013. Site subcontractor American DND completed demolition of the contaminated

224

West Valley Demonstration Project Prepares to Relocate High-Level Waste |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

West Valley Demonstration Project Prepares to Relocate High-Level West Valley Demonstration Project Prepares to Relocate High-Level Waste West Valley Demonstration Project Prepares to Relocate High-Level Waste December 24, 2013 - 12:00pm Addthis The West Valley Demonstration Project’s high-level waste canisters will be relocated to interim onsite storage. The West Valley Demonstration Project's high-level waste canisters will be relocated to interim onsite storage. The first group of eight concrete storage casks for the West Valley Demonstration Project’s high-level waste. The first group of eight concrete storage casks for the West Valley Demonstration Project's high-level waste. Site subcontractor American DND completed demolition of the contaminated 01-14 Building in 2013. Site subcontractor American DND completed demolition of the contaminated

225

Use of Coal Ash in Highway Construction: Michigan Demonstration Project  

Science Conference Proceedings (OSTI)

A 3000-ft-length fly ash base under a highway shoulder will help demonstrate the impact of reused ash on structural integrity and groundwater. This report provides valuable design details for utilities seeking to increase ash reuse and for state highway design engineers responsible for preparing construction specifications.

1989-01-10T23:59:59.000Z

226

Baca geothermal demonstration project. Power plant detail design document  

DOE Green Energy (OSTI)

This Baca Geothermal Demonstration Power Plant document presents the design criteria and detail design for power plant equipment and systems, as well as discussing the rationale used to arrive at the design. Where applicable, results of in-house evaluations of alternatives are presented.

Not Available

1981-02-01T23:59:59.000Z

227

Modular Pebble-Bed Reactor Project: Laboratory-Directed Research and Development Program FY 2002 Annual Report  

Science Conference Proceedings (OSTI)

This report documents the results of our research in FY-02 on pebble-bed reactor technology under our Laboratory Directed Research and Development (LDRD) project entitled the Modular Pebble-Bed Reactor. The MPBR is an advanced reactor concept that can meet the energy and environmental needs of future generations under DOEs Generation IV initiative. Our work is focused in three areas: neutronics, core design and fuel cycle; reactor safety and thermal hydraulics; and fuel performance.

Petti, David Andrew; Dolan, Thomas James; Miller, Gregory Kent; Moore, Richard Leroy; Terry, William Knox; Ougouag, Abderrafi Mohammed-El-Ami; Oh, Chang H; Gougar, Hans D

2002-11-01T23:59:59.000Z

228

Solar demonstration project in a fast-food restaurant  

Science Conference Proceedings (OSTI)

Results are given of a two-phase program in which the first phase included the successful use of heat reclamation equipment and energy conservation techniques at a typical fast-food restaurant. The project's second phase involved the engineering, designing, installation and interfacing of a solar collector system at the facility. The report will help to serve as a guide for other restaurants around the state, and possibly the nation, which wish to install energy saving systems, or adopt energy-saving techniques, geared to their special needs and equipment.

McClenahan, D.

1980-11-01T23:59:59.000Z

229

Lied Animal Shelter Animal campus Renewable Energy Demonstration Project  

DOE Green Energy (OSTI)

The Animal Shelter campus plan includes a new adoption center coupled with a dog adoption park, a wellness/veterinary technician education center, a show arena, and an addition to the existing shelter that will accommodate all animal control and sheltering for the Las Vegas Valley. The new facility will provide a sophisticated and innovative presentation of the animals to be adopted in an attempt to improve the public's perception of shelter animals. Additionally, the Regional Animal Campus will be a ''green building'', embodying a design intent on balancing environmental responsiveness, resource efficiency and cultural and community sensitivity. Designing an energy-efficient building helps reduce pollution from burning fossil fuels, reduce disturbance of natural habitats for the harvesting of resources and minimizes global warming. The project will be a leader in the use of renewable energy by relying on photovoltaic panels, wind turbines, and solar collectors to produce a portion of the project's energy needs The building will operate more efficiently in comparison to a typical shelter through the use of monitoring and specialized cooling/heating equipment. Windows bringing in natural daylight will reduce the center's demand for electricity.

Randy Spitzmesser, AIA

2005-11-22T23:59:59.000Z

230

Lied Animal Shelter Animal campus Renewable Energy Demonstration Project  

SciTech Connect

The Animal Shelter campus plan includes a new adoption center coupled with a dog adoption park, a wellness/veterinary technician education center, a show arena, and an addition to the existing shelter that will accommodate all animal control and sheltering for the Las Vegas Valley. The new facility will provide a sophisticated and innovative presentation of the animals to be adopted in an attempt to improve the public's perception of shelter animals. Additionally, the Regional Animal Campus will be a ''green building'', embodying a design intent on balancing environmental responsiveness, resource efficiency and cultural and community sensitivity. Designing an energy-efficient building helps reduce pollution from burning fossil fuels, reduce disturbance of natural habitats for the harvesting of resources and minimizes global warming. The project will be a leader in the use of renewable energy by relying on photovoltaic panels, wind turbines, and solar collectors to produce a portion of the project's energy needs The building will operate more efficiently in comparison to a typical shelter through the use of monitoring and specialized cooling/heating equipment. Windows bringing in natural daylight will reduce the center's demand for electricity.

Randy Spitzmesser, AIA

2005-11-22T23:59:59.000Z

231

International Smart Grid Demonstration Project Case Studies and Survey Analysis  

Science Conference Proceedings (OSTI)

Electric utilities around the world are assessing the technical issues and the prospective benefits and costs of modernizing the electric grid. This report summarizes research conducted on international smart grid demonstrations that were tasked with communicating results and lessons learned, and it highlightsthree case studies where this information has been conveyed. The research involved a literature review of publicly available information and a smart grid international survey answered by ...

2013-03-27T23:59:59.000Z

232

The Detroit Edison Company Smart Grid Demonstration Project | Open Energy  

Open Energy Info (EERE)

The Detroit Edison Company The Detroit Edison Company Country United States Headquarters Location Detroit, Michigan Recovery Act Funding $4,995,271.00 Total Project Value $10,877,258.00 Coordinates 42.331427°, -83.0457538° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[]}

233

Pacific Gas & Electric Company Smart Grid Demonstration Project | Open  

Open Energy Info (EERE)

Pacific Gas & Electric Company Pacific Gas & Electric Company Country United States Headquarters Location San Francisco, California Recovery Act Funding $25,000,000.00 Total Project Value $355,938,600.00 Coordinates 37.7749295°, -122.4194155° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[]}

234

NSTAR Electric & Gas Corporation Smart Grid Demonstration Project (2) |  

Open Energy Info (EERE)

Lead NSTAR Electric & Gas Corporation Lead NSTAR Electric & Gas Corporation Country United States Headquarters Location Westwood, Massachusetts Recovery Act Funding $5,267,592.00 Total Project Value $10,535,184.00 Coordinates 42.2139873°, -71.2244987° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[]}

235

Southern California Edison Company Smart Grid Demonstration Project | Open  

Open Energy Info (EERE)

Company Company Country United States Headquarters Location Rosemead, California Recovery Act Funding $40,134,700.00 Total Project Value $80,269,400.00 Coordinates 34.0805651°, -118.072846° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[]}

236

Beacon Power Corporation Smart Grid Demonstration Project | Open Energy  

Open Energy Info (EERE)

Beacon Power Corporation Beacon Power Corporation Country United States Headquarters Location Tyngsboro, Massachusetts Recovery Act Funding $24,063,978.00 Total Project Value $48,127,957.00 Coordinates 42.6767568°, -71.4245085° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[]}

237

NSTAR Electric & Gas Corporation Smart Grid Demonstration Project | Open  

Open Energy Info (EERE)

NSTAR Electric & Gas Corporation NSTAR Electric & Gas Corporation Country United States Headquarters Location Westwood, Massachusetts Recovery Act Funding $2,362,000.00 Total Project Value $4,724,000.00 Coordinates 42.2139873°, -71.2244987° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[]}

238

Energy Storage/Conservation and Carbon Emissions Reduction Demonstration Project  

SciTech Connect

The U.S. Department of Energy (DOE) awarded the Center for Transportation and the Environment (CTE) federal assistance for the management of a project to develop and test a prototype flywheel-?based energy recovery and storage system in partnership with Test Devices, Inc. (TDI). TDI specializes in the testing of jet engine and power generation turbines, which uses a great deal of electrical power for long periods of time. In fact, in 2007, the company consumed 3,498,500 kW-?hr of electricity in their operations, which is equivalent to the electricity of 328 households. For this project, CTE and TDI developed and tested a prototype flywheel-?based energy recovery and storage system. This technology is being developed at TDIs facilities to capture and reuse the energy necessary for the companys core process. The new technology and equipment is expected to save approximately 80% of the energy used in the TDI process, reducing total annual consumption of power by approximately 60%, saving approximately two million kilowatt-?hours annually. Additionally, the energy recycling system will allow TDI and other end users to lower their peak power demand and reduce associated utility demand charges. The use of flywheels in this application is novel and requires significant development work from TDI. Flywheels combine low maintenance costs with very high cycle life with little to no degradation over time, resulting in lifetimes measured in decades. All of these features make flywheels a very attractive option compared to other forms of energy storage, including batteries. Development and deployment of this energy recycling technology will reduce energy consumption during jet engine and stationary turbine development. By reengineering the current inefficient testing process, TDI will reduce risk and time to market of efficiency upgrades of gas turbines across the entire spectrum of applications. Once in place the results from this program will also help other US industries to utilize energy recycling technology to lower domestic energy use and see higher net energy efficiency. The prototype system and results will be used to seek additional resources to carry out full deployment of a system. Ultimately, this innovative technology is expected to be transferable to other testing applications involving energy-?based cycling within the company as well as throughout the industry.

Bigelow, Erik

2012-10-30T23:59:59.000Z

239

BACA Project: geothermal demonstration power plant. Final report  

DOE Green Energy (OSTI)

The various activities that have been conducted by Union in the Redondo Creek area while attempting to develop the resource for a 50 MW power plant are described. The results of the geologic work, drilling activities and reservoir studies are summarized. In addition, sections discussing the historical costs for Union's involvement with the project, production engineering (for anticipated surface equipment), and environmental work are included. Nineteen geothermal wells have been drilled in the Redondo Creek area of the Valles Caldera: a prominent geologic feature of the Jemez mountains consisting of Pliocene and Pleistocene age volcanics. The Redondo Creek area is within a complex longitudinal graben on the northwest flank of the resurgent structural dome of Redondo Peak and Redondo Border. The major graben faults, with associated fracturing, are geologically plausible candidates for permeable and productive zones in the reservoir. The distribution of such permeable zones is too erratic and the locations too imprecisely known to offer an attractive drilling target. Log analysis indicates there is a preferred mean fracture strike of N31W in the upper portion of Redondo Creek wells. This is approximately perpendicular to the major structure in the area, the northeast-striking Redondo Creek graben. The geothermal fluid found in the Redondo Creek reservoir is relatively benign with low brine concentrations and moderate H/sub 2/S concentrations. Geothermometer calculations indicate that the reservoir temperature generally lies between 500/sup 0/F and 600/sup 0/F, with near wellbore flashing occurring during the majority of the wells' production.

Not Available

1982-12-01T23:59:59.000Z

240

Heber geothermal binary demonstration project: Unavailability distributions for principal pumps  

DOE Green Energy (OSTI)

The purpose of this study has been to review data sources relevant to the failure rate and mean time to repair for the principal pumps of the Heber geothermal project. Based upon that review the distributions of failure rates, repair times and pump unavailability were established. A total of 16 pumps are represented in this study. The method used to develop data distributions has been to first review as many sources of pump data as are currently available. This review was followed by a study of the features of the pumps specified for the Heber installation and the effects of operation and the environment on those features as they relate to anticipated failure rates and repair times. From this, determinations were made for mean failure rate and repair time values appropriate to specific Heber pumps. Range factors are then selected and used to establish the expected variability of the data. Failure rates and repair times were then combined to obtain the unavailability distribution of each type of pump.

Mulvihill, Robert J.; Cleveland, Edward B.

1982-04-01T23:59:59.000Z

Note: This page contains sample records for the topic "bed demonstration project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


241

Integrated passive-solar demonstration project. Final report  

Science Conference Proceedings (OSTI)

The objectives of the study reported were to collect data on a combination of several passive solar heating and cooling systems. A passive solar test structure was constructed and monitored and the demonstration of passive systems designed into the structure was evaluated. Passive solar cooling principles include: shading all mass walls and windows from direct solar gain, maintaining cool attic and ceiling temperatures using solar induced ventilation, maintaining cool mean radiant wall temperatures, recirculating internal air, and using natural cross-ventilation through the conditioned space in spring and fall. Passive solar heating principles include: orientation of windows and sunspaces towards the south, providing double pane south windows, providing a double pane solar sunspace, using night insulation over glazing, extended thermal storage mass, and using a fan-forced rock/earth/air storage system. (LEW)

Garrison, M.L.

1982-09-01T23:59:59.000Z

242

BACA Project: geothermal demonstration power plant. Final report  

SciTech Connect

The various activities that have been conducted by Union in the Redondo Creek area while attempting to develop the resource for a 50 MW power plant are described. The results of the geologic work, drilling activities and reservoir studies are summarized. In addition, sections discussing the historical costs for Union's involvement with the project, production engineering (for anticipated surface equipment), and environmental work are included. Nineteen geothermal wells have been drilled in the Redondo Creek area of the Valles Caldera: a prominent geologic feature of the Jemez mountains consisting of Pliocene and Pleistocene age volcanics. The Redondo Creek area is within a complex longitudinal graben on the northwest flank of the resurgent structural dome of Redondo Peak and Redondo Border. The major graben faults, with associated fracturing, are geologically plausible candidates for permeable and productive zones in the reservoir. The distribution of such permeable zones is too erratic and the locations too imprecisely known to offer an attractive drilling target. Log analysis indicates there is a preferred mean fracture strike of N31W in the upper portion of Redondo Creek wells. This is approximately perpendicular to the major structure in the area, the northeast-striking Redondo Creek graben. The geothermal fluid found in the Redondo Creek reservoir is relatively benign with low brine concentrations and moderate H/sub 2/S concentrations. Geothermometer calculations indicate that the reservoir temperature generally lies between 500/sup 0/F and 600/sup 0/F, with near wellbore flashing occurring during the majority of the wells' production.

1982-12-01T23:59:59.000Z

243

SustainX, Inc. Smart Grid Demonstration Project | Open Energy Information  

Open Energy Info (EERE)

SustainX, Inc. Smart Grid Demonstration Project SustainX, Inc. Smart Grid Demonstration Project Jump to: navigation, search Project Lead SustainX, Inc. Country United States Headquarters Location West Lebanon, New Hampshire Recovery Act Funding $5,396,023.00 Total Project Value $10,792,045.00 References ARRA Smart Grid Demonstration Projects[1] This article is a stub. You can help OpenEI by expanding it. The SustainX, Inc. Smart Grid Demonstration Project is a U.S. Department of Energy Smart Grid Demonstration Project which is based in West Lebanon, New Hampshire. Overview Design, build, and deploy a utility-scale, low-cost compressed air energy storage system to support the integration of renewable energy sources onto the grid. The 1 MW/4hr system will store potential energy in the form of compressed air in above-ground industrial pressure facilities. The

244

Development of the Decontamination Approach for the West Valley Demonstration Project Decontamination Project Plan  

SciTech Connect

This paper details the development of a decontamination approach for the West Valley Demonstration Project (WVDP), Decontamination Project Plan (Plan). The WVDP is operated by West Valley Nuclear Services Company (WVNSCO), a subsidiary of Westinghouse Government and Environmental Services, and its parent companies Washington Group International and British Nuclear Fuels Limited (BNFL). The WVDP is a waste management effort being conducted by the United States Department of Energy (DOE) at the site of the only commercial nuclear fuel reprocessing facility to have operated in the United States. This facility is part of the Western New York Nuclear Service Center (WNYNSC), which is owned by the New York State Energy Research and Development Authority (NYSERDA). As authorized by Congress in 1980 through the West Valley Demonstration Project Act (WVDP Act, Public Law 96-368), the DOE's primary mission at the WVDP is to solidify high-level liquid nuclear waste safely; transport the high-level waste (HLW) to a federal repository; and decontaminate and decommission the facilities and hardware used to solidify the HLW and conduct the WVDP. This includes a provision for the disposal of low-level waste (LLW) and transuranic waste (TRU) produced during processing of the HLW. Continuation of the effort to reduce the hazard and risk associated with historic operations to the extent needed to ensure the health and safety of the public and the environment will see a change in focus from stabilization of liquid HLW to stabilization of former plutonium and uranium extraction (PUREX) reprocessing plant facilities. This will be achieved through the activities of in-cell component removal and packaging, and preparation for long-term disposal of the long- lived radionuclides. These radionuclides are associated with the former PUREX facility operations, including, and upstream from, facilities utilized in the primary separation and first plutonium/uranium split cycles. The closure strategy for the WVDP is subject to ongoing evaluation and decision-making involving DOE and NYSERDA. Implementation will be subject to a future Record of Decision (ROD) and an Environmental Impact Statement (EIS).

Milner, T. N.; Watters, W. T.

2002-02-25T23:59:59.000Z

245

D&D Toolbox Project - Technology Demonstration of Fixatives Applied to Hot  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Project - Technology Demonstration of Fixatives Applied Project - Technology Demonstration of Fixatives Applied to Hot Cell Facilities via Remote Sprayer Platforms D&D Toolbox Project - Technology Demonstration of Fixatives Applied to Hot Cell Facilities via Remote Sprayer Platforms Many facilities slated for D&D across the DOE complex pose hazards (radiological, chemical, and structural) which prevent the use of traditional manual techniques. D&D Toolbox Project - Technology Demonstration of Fixatives Applied to Hot Cell Facilities via Remote Sprayer Platforms More Documents & Publications Demonstration of Fixatives to Control Contamination and Accelerate D&D Demonstration of DeconGel (TM) at the Oak Ridge National Laboratory Building 2026 D&D Toolbox Project - Technology Demonstration of Fixatives Applied to Hot Cell Facilities via Remote Sprayer Platforms

246

Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project: Fall 2006 Progress Update (Presentation)  

DOE Green Energy (OSTI)

This presentation, given by NREL's Keith Wipke at EVS-22, provides an update on the Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project.

Wipke, K.; Welch, C.; Thomas, H.; Sprik, S.; Gronich, S.; Garbak, J.

2006-10-26T23:59:59.000Z

247

Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project: Data Analysis Overview; Preprint  

DOE Green Energy (OSTI)

Paper for the 2005 National Hydrogen Association conference provides an overview of the U.S. Department of Energy's Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project.

Welch, C.; Wipke, K.; Gronich, S.; Garbak, J.

2005-03-01T23:59:59.000Z

248

Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project: Progress Update (Presentation)  

DOE Green Energy (OSTI)

Presentation outlining the progress of DOE's Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project, prepared for the 2006 National Hydrogen Association Meeting.

Wipke, K.; Welch, C.; Thomas, H.; Sprik, S.; Gronich, S.; Garbak. J.; Hooker, D.

2006-03-13T23:59:59.000Z

249

Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project: Progress Update (Presentation)  

DOE Green Energy (OSTI)

Presentation outlining the progress of DOE's Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project, prepared for the 2006 National Hydrogen Association Meeting.

Wipke, K.; Welch, C.; Thomas, H.; Sprik, S.; Gronich, S.; Garbak. J.; Hooker, D.

2006-01-01T23:59:59.000Z

250

Southern California Edison (SCE) Smart Grid Demonstration Host-Site Project Description  

Science Conference Proceedings (OSTI)

This report provides a description of the Southern California Edison (SCE) Smart Grid Demonstration Host-Site Project as part of the Electric Power Research Institute's (EPRI's) multi-year smart grid demonstration initiative. The EPRI initiative includes core smart grid research and a number of large-scale smart grid projects currently with 18 funding utility members. The project is focused on integrating large-scale distributed energy resources (DER)including demand response, storage, distributed genera...

2010-07-27T23:59:59.000Z

251

Sacramento Municipal Utility District Smart Grid Demonstration Host-Site Project Description  

Science Conference Proceedings (OSTI)

This report provides a description of the Sacramento Municipal Utility District Smart Grid Demonstration Host-Site Project as part of the Electric Power Research Institutes (EPRIs) five-year smart grid demonstration initiative. The EPRI initiative includes core smart grid research and a number of large-scale smart grid projects with 21 funding utility members. The project is focused on integrating large-scale distributed energy resources (DER), including demand response, storage, distributed generation, ...

2011-08-05T23:59:59.000Z

252

KCP&L Smart Grid Demonstration Host-Site Project Description  

Science Conference Proceedings (OSTI)

This report describes the Kansas City Power and Light (KCP&L) Smart Grid demonstration host-site project as part of the Electric Power Research Institutes (EPRIs) five-year Smart Grid demonstration initiative. The EPRI initiative includes core Smart Grid research and several large-scale Smart Grid projects with 18 funding utility members. The project is focused on integrating large-scale distributed energy resources (DER)including demand response, storage, distributed generation, and distributed renewab...

2010-04-01T23:59:59.000Z

253

FirstEnergy Smart Grid Demonstration Host-Site Project Description  

Science Conference Proceedings (OSTI)

This report provides a description of the FirstEnergy Smart Grid Demonstration Host-Site Project as part of the Electric Power Research Institutes (EPRIs) five-year smart grid demonstration initiative. The EPRI initiative includes core smart grid research and a number of large-scale smart grid projects with 19 funding utility members. The project is focused on integrating large-scale distributed energy resources (DER), including demand response, storage, distributed generation, and distributed renewabl...

2009-09-24T23:59:59.000Z

254

Electricite' de France (EDF) Smart Grid Demonstration Host-Site Project Description  

Science Conference Proceedings (OSTI)

This report provides a description of the Electricit de France (EDF) Smart Grid Demonstration Host-Site Project as part of the Electric Power Research Institutes (EPRIs) five-year smart grid demonstration initiative. The EPRI initiative includes core smart grid research and a number of large-scale smart grid projects with 19 funding utility members. The project is focused on integrating large-scale distributed energy resources (DER), including demand response, storage, distributed generation, and dist...

2009-09-16T23:59:59.000Z

255

American Electric Power (AEP) Smart Grid Demonstration Host-Site Project Description  

Science Conference Proceedings (OSTI)

This report provides a description of the American Electric Power (AEP) Smart Grid Demonstration Host-Site Project as part of the Electric Power Research Institute's (EPRI's) five-year smart grid demonstration initiative. The EPRI initiative includes core smart grid research and a number of large-scale smart grid projects with 19 funding utility members. The project is focused on integrating large-scale distributed energy resources (DER), including demand response, storage, distributed generation, and di...

2009-09-16T23:59:59.000Z

256

Hydro-Quebec Smart Grid Demonstration Host-Site Project Description  

Science Conference Proceedings (OSTI)

This report describes the Hydro Qubec Smart Grid Demonstration Host-Site Project as part of the Electric Power Research Institute's (EPRI's) five-year smart grid demonstration initiative. The EPRI initiative includes core smart grid research and several large-scale smart grid projects with 21 funding utility members. The project is focused on integrating large-scale distributed energy resources (DER), including demand response, storage, distributed generation, and distributed renewable generation, into a...

2011-08-08T23:59:59.000Z

257

Five kW Solid Oxide Fuel Cell Demonstration Project: Case Study: Exit Glacier Nature Center Acumentrics Demonstration  

Science Conference Proceedings (OSTI)

This case study documents the demonstration experiences and lessons learned from a 5 kW solid oxide fuel cell system operating on propane at the Kenai Fiords National Park at the Exit Glacier Visitor Center, Seward, Alaska. The case study is one of several fuel cell project case studies under research by EPRI's Distributed Energy Resources Program. This case study is designed to help utilities and other interested parties understand the early applications of fuel cell systems to help them in their resour...

2005-02-17T23:59:59.000Z

258

Kentucky Pioneer Integrated Gasification Combined Cycle Demonstration Project, Final Environmental Impact Statement  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

A-1 A-1 APPENDIX A CONSULTATION LETTERS This appendix includes consultation/approval letters between the U.S. Department of Energy and the U.S. Fish and Wildlife Service regarding threatened and endangered species, and between other state and Federal agencies as needed. Consultation Letters A-2 Kentucky Pioneer IGCC Demonstration Project Final Environmental Impact Statement A-3 Consultation Letters A-4 Kentucky Pioneer IGCC Demonstration Project Final Environmental Impact Statement A-5 Consultation Letters A-6 Kentucky Pioneer IGCC Demonstration Project Final Environmental Impact Statement A-7 Consultation Letters A-8 Kentucky Pioneer IGCC Demonstration Project Final Environmental Impact Statement B-1 APPENDIX B NOTICE OF INTENT TO PREPARE AN ENVIRONMENTAL IMPACT STATEMENT FOR THE

259

The Sydney 2000 World Weather Research Programme Forecast Demonstration Project: Overview and Current Status  

Science Conference Proceedings (OSTI)

The first World Weather Research Programme (WWRP) Forecast Demonstration Project (FDP), with a focus on nowcasting, was conducted in Sydney, Australia, from 4 September to 21 November 2000 during a period associated with the Sydney 2000 Olympic ...

T. Keenan; P. Joe; J. Wilson; C. Collier; B. Golding; D. Burgess; P. May; C. Pierce; J. Bally; A. Crook; A. Seed; D. Sills; L. Berry; R. Potts; I. Bell; N. Fox; E. Ebert; M. Eilts; K. O'Loughlin; R. Webb; R. Carbone; K. Browning; R. Roberts; C. Mueller

2003-08-01T23:59:59.000Z

260

Verification of Nowcasts from the WWRP Sydney 2000 Forecast Demonstration Project  

Science Conference Proceedings (OSTI)

The verification phase of the World Weather Research Programme (WWRP) Sydney 2000 Forecast Demonstration Project (FDP) was intended to measure the skill of the participating nowcast algorithms in predicting the location of convection, rainfall ...

Elizabeth E. Ebert; Laurence J. Wilson; Barbara G. Brown; Pertti Nurmi; Harold E. Brooks; John Bally; Matthias Jaeneke

2004-02-01T23:59:59.000Z

Note: This page contains sample records for the topic "bed demonstration project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


261

FCV Learning Demonstration: Project Midpoint Status and First-Generation Vehicle Results; Preprint  

DOE Green Energy (OSTI)

This paper covers the progress accomplished by the U.S. DOE's Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project since inception, including results from analysis of six months of new data.

Wipke, K.; Sprik, S.; Kurtz, J.; Thomas, H.; Garbak, J.

2007-12-01T23:59:59.000Z

262

Hydrogen Learning Demonstration Project: Fuel Cell Efficiency and Initial Durability (Presentation)  

Science Conference Proceedings (OSTI)

This presentation by NREL's Keith Wipke at the 2006 Fuel Cell Seminar provides information about the Hydrogen Learning Demonstration Project, with a focus on fuel cell efficiency and durability.

Wipke, K.; Welch, C.; Thomas, H.; Sprik, S.; Gronich, S.; Garbak, J.

2006-11-15T23:59:59.000Z

263

Guidebook for Cost/Benefit Analysis of Smart Grid Demonstration Projects  

Science Conference Proceedings (OSTI)

This report presents a step-by-step process for estimating the costs and benefits associated with smart grid demonstration projects. The entire guidebook is meant to function as a stand-alone users manual for the analysis process, from the initial step of describing the project to the final step of communicating the results to all stakeholders. This version of the guidebook presents detailed instructions for describing the project objectives, the research plan, and the technologies deployed; ...

2013-12-16T23:59:59.000Z

264

Baca geothermal demonstration project. Quarterly technical progress report, October 1-December 31, 1980  

SciTech Connect

Work completed on the Baca 50 Megawatt (MWe) Geothermal Demonstration Power Plant Project, Baca Location No. 1, New Mexico is reported. Topics covered in this quarterly report include progress made in the well and steam production systems, the power plant and transmission systems, and in the project data management program.

1981-03-01T23:59:59.000Z

265

DOE/EIS-0289, Final Environmental Impact Statement for the JEA Circulating Fluidized Bed Combustor Project (June 1, 2000)  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

FINAL FINAL ENVIRONMENTAL IMPACT STATEMENT FOR THE JEA CIRCULATING FLUIDIZED BED COMBUSTOR PROJECT JACKSONVILLE, FLORIDA June 2000 U.S. DEPARTMENT OF ENERGY COVER SHEET June 2000 RESPONSIBLE AGENCY U.S. Department of Energy (DOE) TITLE Final Environmental Impact Statement for the JEA Circulating Fluidized Bed Combustor Project; Jacksonville, Duval County, Florida CONTACT Additional copies or information concerning this final environmental impact statement (EIS) can be obtained from Ms. Lisa K. Hollingsworth, National Environmental Policy Act (NEPA) Document Manager, U.S. Department of Energy, National Energy Technology Laboratory, 3610 Collins Ferry Road, P. O. Box 880, Morgantown, WV 26507-0880. Telephone: (304) 285-4992. Fax: (304) 285-4403. E-mail: lisa.hollingsworth@netl.doe.gov.

266

DOE/EIS-0289; Draft Environmental Impact Statement for the JEA Circulating Fluidized Bed Combustor Project, August 1999  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Draft Draft ENVIRONMENTAL IMPACT STATEMENT FOR THE JEA CIRCULATING FLUIDIZED BED COMBUSTOR PROJECT JACKSONVILLE, FLORIDA August 1999 U.S. DEPARTMENT OF ENERGY COVER SHEET August 1999 RESPONSIBLE AGENCY U.S. Department of Energy (DOE) TITLE Draft Environmental Impact Statement for the JEA Circulating Fluidized Bed Combustor Project; Jacksonville, Duval County, Florida CONTACT Additional copies or information concerning this draft environmental impact statement (EIS) can be obtained from Ms. Lisa K. Hollingsworth, National Environmental Policy Act (NEPA) Document Manager, U.S. Department of Energy, Federal Energy Technology Center, 3610 Collins Ferry Road, P. O. Box 880, Morgantown, WV 26507-0880. Telephone: (304) 285-4992. Fax: (304) 285-4403. E-mail: lisa.hollingsworth@fetc.doe.gov.

267

Technology Maturation Plan (TMP) Fluidized Bed Steam Reforming (FBSR) Technology for Tank 48H Treatment Project (TTP)  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

LWO-SPT-2007-00249 LWO-SPT-2007-00249 Rev. 1 Technology Maturation Plan (TMP) Fluidized Bed Steam Reforming (FBSR) For Tank 48H Treatment Project (TTP) November, 2007 Technology Maturation Plan (TMP) Fluidized Bed Steam Reforming (FBSR) Technology for Tank 48H Treatment Project (TTP) LWO-SPT-2007-00249 Rev. 1 DISCLAIMER This report was prepared by Washington Savannah River Company (WSRC) for the United States Department of Energy under Contract No. DEA-AC09-96SR18500 and is an account of work performed under that contract. Neither the United States Department of Energy, nor WSRC, nor any of their employees makes any warranty, expressed or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, or product or process

268

Heber Geothermal Binary Demonstration Project. Quarterly technical progress report, September 15, 1980-March 31, 1981  

DOE Green Energy (OSTI)

Work completed on the nominal 65 Megawatt (Mwe gross) Heber Geothermal Binary Demonstration Project, located at Heber, California, during the period of September 15, 1980, through March 31, 1981 is documented. Topics covered in this quarterly report include progress made in the areas of Wells and Fluids Production and Injection Systems, Power Plant Design and Construction, Power Plant Demonstration, and Data Acquisition and Dissemination.

Hanenburg, W.H.; Lacy, R.G.; Van De Mark, G.D.

1981-06-01T23:59:59.000Z

269

Heber geothermal binary demonstration project. Quarterly technical progress report, April 1, 1981-June 30, 1981  

SciTech Connect

Work completed on the nominal 65 Megawatt (Mwe gross) Heber Geothermal Binary Demonstration Project, located at Heber, California, during the period of April 1, 1981, through June 30, 1981 is documented. Topics covered include progress made in the areas of Wells and Fluid Production and Injection Systems, Power Plant Design and Construction, Power Plant Demonstration, and Data Acquisition and Dissemination.

Van De Mark, G.D.

1981-09-01T23:59:59.000Z

270

DOE-Sponsored Drilling Projects Demonstrate Significant CO2 Storage at  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

DOE-Sponsored Drilling Projects Demonstrate Significant CO2 Storage DOE-Sponsored Drilling Projects Demonstrate Significant CO2 Storage at Three Sites DOE-Sponsored Drilling Projects Demonstrate Significant CO2 Storage at Three Sites May 3, 2012 - 1:00pm Addthis Washington, DC - Evaluation-related test drilling at geologic sites in three states that could store a combined 64 million metric tons of carbon dioxide (CO2) emissions - an important component of carbon capture, utilization and storage (CCUS) technology development - has been completed in projects supported by the U.S. Department of Energy. If the potential of the sites is eventually fulfilled, they could safely and permanently store combined CO2 emissions equivalent to that produced by more than 11 million passenger vehicles annually or from the electricity use of more than 7 million homes for one year, according to Environmental

271

DOE-Sponsored Drilling Projects Demonstrate Significant CO2 Storage at  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Drilling Projects Demonstrate Significant CO2 Storage Drilling Projects Demonstrate Significant CO2 Storage at Three Sites DOE-Sponsored Drilling Projects Demonstrate Significant CO2 Storage at Three Sites May 3, 2012 - 1:00pm Addthis Washington, DC - Evaluation-related test drilling at geologic sites in three states that could store a combined 64 million metric tons of carbon dioxide (CO2) emissions - an important component of carbon capture, utilization and storage (CCUS) technology development - has been completed in projects supported by the U.S. Department of Energy. If the potential of the sites is eventually fulfilled, they could safely and permanently store combined CO2 emissions equivalent to that produced by more than 11 million passenger vehicles annually or from the electricity use of more than 7 million homes for one year, according to Environmental

272

Reasons for the termination of, and DOE losses in, a geothermal demonstration powerplant project  

DOE Green Energy (OSTI)

The 50-megawatt Baca geothermal demonstration powerplant project, located in northern New Mexico, was the Department of Energy's (DOE's) initial effort to demonstrate geothermal powerplant technology. The project, started in 1978, was believed to have a high probability of success, and its cost was to be shared equally with the industry participants. GAO's review showed that the project was terminated in January 1982 because sufficient geothermal steam to operate the powerplant could not be obtained. The early termination resulted in DOE paying a disproportionate share - $45 million, or 64% - of the $70 million spent on the project because it had paid the majority of the powerplant-related costs at that time. However, a portion of these costs may be recovered through the sale of powerplant equipment. DOE indicated that it learned lessons from this experience and will act to prevent these problems from occurring on other projects.

Not Available

1983-09-29T23:59:59.000Z

273

Shared savings and low income homeowners: Results of a demonstration project in Hennepin County  

SciTech Connect

In 1984 Hennepin County, with financial support from the US Department of Energy and as part of the Year Five energy program of the Urban Consortium's Energy Task Force, initiated a Residential Shared Savings Demonstration Project (RSSDP) for single family homeowners. Shared savings, or performance contracting, occurs when an energy service company (ESCo) finances and installs energy improvements in a customer's property and receives a share of the savings that result over time as their compensation. Chapter 1 of this report provides general background on the project, including a brief description of Hennepin County, the energy environment within which the project was conducted, and the Residential Shared Savings Demonstration Project. Chapter 2 describes the efforts to market the RSSDP to low income homeowners, the results of those efforts and the findings from an extensive market assessment effort. Chapter 3 summarizes the significant lessons learned during the project. 4 figs., 3 tabs.

Miller, R.D.; Ford, J.M.

1986-04-01T23:59:59.000Z

274

Clean Coal Power Initiative Round 1 Demonstration Projects Applying Advanced Technologies to Lower Emissions  

NLE Websites -- All DOE Office Websites (Extended Search)

7 JUNE 2012 7 JUNE 2012 Clean Coal Power Initiative Round 1 Demonstration Projects Applying Advanced Technologies to Lower Emissions and Improve Efficiency 2 Cover Photos: * Top left: Great River Energy's Coal Creek Station * Top right: We Energy's Presque Isle Power Plant * Bottom: Dynegy's Baldwin Energy Complex A report on three projects conducted under separate cooperative agreements between the U.S. Department of Energy and: * Great River Energy * NeuCo. , Inc. * WeEnergies 3 Executive Summary 4 Clean Coal Technology Demonstration Program 5 CCPI Program 6 Demonstration of Integrated Optimization Software at

275

DOE Funds 21 Research, Development and Demonstration Projects for up to $78  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Funds 21 Research, Development and Demonstration Projects for Funds 21 Research, Development and Demonstration Projects for up to $78 Million to Promote Enhanced Geothermal Systems DOE Funds 21 Research, Development and Demonstration Projects for up to $78 Million to Promote Enhanced Geothermal Systems October 6, 2008 - 4:14pm Addthis RENO, Nev. - Today at the National Geothermal Conference in Reno, Nev., Deputy Assistant Secretary for Renewable Energy Steve Chalk announced the U.S. Department of Energy's (DOE) awards under a Funding Opportunity Announcement (FOA) for research, development and demonstration of Enhanced Geothermal Systems (EGS) for next-generation geothermal energy technologies. Subject to annual appropriations, the Department will provide up to $43.1 million over four years to 21 awardees, including a

276

West Valley Demonstration Project DOE Manual 435.1-1 Waste Incidental to  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

West Valley Demonstration Project DOE Manual 435.1-1 Waste West Valley Demonstration Project DOE Manual 435.1-1 Waste Incidental to Reprocessing Evaluations and Determinations West Valley Demonstration Project DOE Manual 435.1-1 Waste Incidental to Reprocessing Evaluations and Determinations The U.S. Department of Energy (DOE) Manual 435.1-1, Radioactive Waste Management Manual, which accompanies DOE Order 435.1, provides that the DOE may determine that certain waste from reprocessing spent nuclear fuel is waste incidental to reprocessing, is not high-level waste and may be managed and disposed of as low-level waste if the waste meets the criteria in DOE Manual 435.1-1, Chapter II, Section B. To determine that waste is incidental to reprocessing using the evaluation process from the Manual, and shall be managed as low level waste, DOE must demonstrate three

277

Pacific Northwest GridWise Testbed Demonstration Projects; Part I. Olympic Peninsula Project  

Science Conference Proceedings (OSTI)

This report describes the implementation and results of a field demonstration wherein residential electric water heaters and thermostats, commercial building space conditioning, municipal water pump loads, and several distributed generators were coordinated to manage constrained feeder electrical distribution through the two-way communication of load status and electric price signals. The field demonstration took place in Washington and Oregon and was paid for by the U.S. Department of Energy and several northwest utilities. Price is found to be an effective control signal for managing transmission or distribution congestion. Real-time signals at 5-minute intervals are shown to shift controlled load in time. The behaviors of customers and their responses under fixed, time-of-use, and real-time price contracts are compared. Peak loads are effectively reduced on the experimental feeder. A novel application of portfolio theory is applied to the selection of an optimal mix of customer contract types.

Hammerstrom, Donald J.; Ambrosio, Ron; Carlon, Teresa A.; DeSteese, John G.; Horst, Gale R.; Kajfasz, Robert; Kiesling, Laura L.; Michie, Preston; Pratt, Robert G.; Yao, Mark; Brous, Jerry; Chassin, David P.; Guttromson, Ross T.; Jarvegren, Olof M.; Katipamula, Srinivas; Le, N. T.; Oliver, Terry V.; Thompson, Sandra E.

2008-01-09T23:59:59.000Z

278

Power Authority of the State of New York Smart Grid Demonstration Project |  

Open Energy Info (EERE)

of the State of New York Smart Grid Demonstration Project of the State of New York Smart Grid Demonstration Project Jump to: navigation, search Project Lead Power Authority of the State of New York Country United States Headquarters Location White Plains, New York Recovery Act Funding $720,000.00 Total Project Value $1,440,000.00 Coordinates 41.0339862°, -73.7629097° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[]}

279

New York State Electric & Gas Corporation Smart Grid Demonstration Project  

Open Energy Info (EERE)

New York State Electric & Gas Corporation Smart Grid Demonstration Project New York State Electric & Gas Corporation Smart Grid Demonstration Project Jump to: navigation, search Project Lead New York State Electric & Gas Corporation Country United States Headquarters Location Binghamton, New York Recovery Act Funding $29,561,142.00 Total Project Value $125,006,103.00 Coordinates 42.0986867°, -75.9179738° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[]}

280

Kansas City Power & Light Company Smart Grid Demonstration Project | Open  

Open Energy Info (EERE)

Demonstration Project Demonstration Project Jump to: navigation, search Project Lead Kansas City Power & Light Company Country United States Headquarters Location Kansas City, Missouri Recovery Act Funding $23,940,112.00 Total Project Value $48,125,315.00 Coordinates 39.0997265°, -94.5785667° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[]}

Note: This page contains sample records for the topic "bed demonstration project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


281

Los Angeles Department of Water and Power Smart Grid Demonstration Project  

Open Energy Info (EERE)

Angeles Department of Water and Power Smart Grid Demonstration Project Angeles Department of Water and Power Smart Grid Demonstration Project Jump to: navigation, search Project Lead Los Angeles Department of Water and Power Country United States Headquarters Location Los Angeles, California Recovery Act Funding $60,280,000.00 Total Project Value $120,560,000.00 Coordinates 34.0522342°, -118.2436849° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[]}

282

Operational Awareness Oversight of the West Valley Demonstration Project, July 2012  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

WVDP-2012-07-30 WVDP-2012-07-30 Site: West Valley Demonstration Project Subject: Office of Enforcement and Oversight's Office of Safety and Emergency Management Evaluations (HS-45) Activity Report for Operational Awareness Oversight of the West Valley Demonstration Project Dates of Activity : 07/30/2012 Report Preparer: Joseph P. Drago Activity Description/Purpose: The purpose of this Office of Health, Safety and Security (HSS) activity was for the HS-45 Site Lead to meet with Department of Energy (DOE) site personnel, tour the facilities, and obtain a status report on the upcoming activities at the West Valley Demonstration Project (WVDP). Major decommissioning activities underway include removal of asbestos-containing materials, disassembly of the dissolver,

283

Operational Awareness Oversight of the West Valley Demonstration Project, July 2012  

NLE Websites -- All DOE Office Websites (Extended Search)

WVDP-2012-07-30 WVDP-2012-07-30 Site: West Valley Demonstration Project Subject: Office of Enforcement and Oversight's Office of Safety and Emergency Management Evaluations (HS-45) Activity Report for Operational Awareness Oversight of the West Valley Demonstration Project Dates of Activity : 07/30/2012 Report Preparer: Joseph P. Drago Activity Description/Purpose: The purpose of this Office of Health, Safety and Security (HSS) activity was for the HS-45 Site Lead to meet with Department of Energy (DOE) site personnel, tour the facilities, and obtain a status report on the upcoming activities at the West Valley Demonstration Project (WVDP). Major decommissioning activities underway include removal of asbestos-containing materials, disassembly of the dissolver,

284

Executive summaries of reports leading to the construction of the Baca Geothermal Demonstration Project  

DOE Green Energy (OSTI)

Executive summaries have been written for 61 reports and compilations of data which in part, have led to the construction of the Baca 50 MW Geothermal Demonstration Project (GDP). The reports and data include environmental research, reservoir and feasibility studies, the project proposal to DOE and the Final Environmental Impact Statement. These executive summaries are intended to give the reader a general overview of each report prior to requesting the report from the GDP Data Manager.

Sherwood, P.B.; Newman, K.L.; Westermeier, J.F.; Giroux, H.D.; Lowe, G.D.; Nienberg, M.W.

1980-05-01T23:59:59.000Z

285

Executive summaries of reports leading to the construction of the Baca Geothermal Demonstration Project  

DOE Green Energy (OSTI)

Executive summaries have been written for 61 reports and compilations of data which, in part, have led to the construction of the Baca 50 MW Geothermal Demonstration Project (GDP). The reports and data include environmental research, reservoir and feasibility studies, the project proposal to DOE and the Final Environmental Impact Statement. These executive summaries are intended to give the reader a general overview of each report prior to requesting the report from the GDP Data Manager.

Sherwood, P.B.; Newman, K.L.; Westermeier, J.F.; Giroux, H.D.; Lowe, G.D.; Nienberg, M.W.

1980-05-01T23:59:59.000Z

286

Guidebook for Cost/Benefit Analysis of Smart Grid Demonstration Projects  

Science Conference Proceedings (OSTI)

This report presents a step-by-step process for estimating the costs and benefits associated with Smart Grid demonstration projects. In its entirety, the guidebook is meant to function as a standalone users manual for the analysis process, from the initial step of describing the project to the final step of communicating the results to all stakeholders. This revision of the Guidebook updates and supersedes the material in the original Volume 1, published in 2011, but goes further by adding ...

2012-12-12T23:59:59.000Z

287

Baker-Barry Tunnel Lighting: Evaluation of a Potential GATEWAY Demonstrations Project  

SciTech Connect

The U.S. Department of Energy (DOE) is evaluating the Baker-Barry Tunnel as a potential GATEWAY Demonstrations project for deployment of solid-state lighting (SSL) technology. The National Park Service (NPS) views this project as a possible proving ground and template for implementation of light-emitting diode (LED) luminaires in other NPS tunnels, thereby expanding the estimated 40% energy savings from 132 MWh/yr for this tunnel to a much larger figure national

Tuenge, Jason R.

2011-06-01T23:59:59.000Z

288

Final Report on the PREMIO Experimental Results: EDF Smart Grid Demonstration Project  

Science Conference Proceedings (OSTI)

PREMIO is a French acronym for Production Rpartie, Enr et MDE, Intgres et Optimises or in English, Integration and Optimization of DG, DSM & Renewable Energies. The term PREMIO is used in this document in reference to the project and the working consortium, as well as the Virtual Power Plant. Electricit de France (EDF) supports the PREMIO demonstration project in the south of France. PREMIO combines the control of installed ...

2013-11-25T23:59:59.000Z

289

Pressurized Circulating Fluidized Bed (PCFB) Repowering Project. Annual report, August 1991--December 1992  

SciTech Connect

This report provides a summary of activities, by the DMEC-1 Limited Partnership on the PCFB Repowering Project from project initiation in August 1991 through December 1992. The DMEC-1 project will demonstrate ``First Generation`` PCFB technology and will result in an existing steam turbine being repowered with steam from a PCFB boiler. Exhaust gases from the PCFB boiler will be expanded through a gas turbine to provide additional power output. The preliminary design is progressing. As the design is refined and modified, cost and schedule baselines will be updated. Environmental information has been obtained and submitted to The Department of Energy (DOE) with no obvious problems or concerns identified. Testing analysis and evaluations of systems continue. A key feature of design verification testing has been and will continue to be the testing of ceramic barrier filtration technologies including the Asahi Advanced Ceramic Tube Filter (ACTF) and Westinghouse`s Candle Filter. At the time of this report testing has been completed on the Asahi ACTF and tests have been initiated on the Westinghouse filters. In general terms, the Asahi design was successful in reducing the outlet dust loading to required levels but certain problems were encountered which led to some premature ceramic tube failures.

1993-04-01T23:59:59.000Z

290

CERTS Microgrid Laboratory Test Bed  

E-Print Network (OSTI)

Diagram of CERTS Microgrid Test Bed Figure 3. Tecogen Prime2009 CERTS Microgrid Laboratory Test Bed J. ETO, Lawrenceof the CERTS Microgrid Test Bed project was to enhance the

Eto, Joe

2009-01-01T23:59:59.000Z

291

CERTS Microgrid Laboratory Test Bed  

E-Print Network (OSTI)

Line Diagram of CERTS Microgrid Test Bed Figure 3. TecogenCALGARY 2009 CERTS Microgrid Laboratory Test Bed J. ETO,The objective of the CERTS Microgrid Test Bed project was to

Eto, Joe

2009-01-01T23:59:59.000Z

292

Los Alamos National Laboratory Tritium Technology Deployments Large Scale Demonstration and Deployment Project  

Science Conference Proceedings (OSTI)

This paper describes the organization, planning and initial implementation of a DOE OST program to deploy proven, cost effective technologies into D&D programs throughout the complex. The primary intent is to accelerate closure of the projects thereby saving considerable funds and at the same time being protective of worker health and the environment. Most of the technologies in the ''toolkit'' for this program have been demonstrated at a DOE site as part of a Large Scale Demonstration and Deployment Project (LSDDP). The Mound Tritium D&D LSDDP served as the base program for the technologies being deployed in this project but other LSDDP demonstrated technologies or ready-for-use commercial technologies will also be considered. The project team will evaluate needs provided by site D&D project managers, match technologies against those needs and rank deployments using a criteria listing. After selecting deployments the project will purchase the equipment and provide a deployment engineer to facilitate the technology implementation. Other cost associated with the use of the technology will be borne by the site including operating staff, safety and health reviews etc. A cost and performance report will be prepared following the deployment to document the results.

McFee, J.; Blauvelt, D.; Stallings, E.; Willms, S.

2002-02-26T23:59:59.000Z

293

Western Greenbrier Co-Production Demonstration Project Final Environmental Impact Statement  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

WESTERN WESTERN GREENBRIER CO-PRODUCTION DEMONSTRATION PROJECT FINAL ENVIRONMENTAL IMPACT STATEMENT VOLUME 1 OF 3 DOE / EIS-0361 U.S. Department of Energy Office of Fossil Energy National Energy Technology Laboratory NOVEMBER 2007 COVER SHEET Responsible Agency: U.S. Department of Energy Title: Western Greenbrier Co-Production Demonstration Project, Final Environmental Impact Statement (DOE/EIS-0361) Location: Rainelle, West Virginia Contact: For further information about this Environmental Impact Statement, contact: For general information on the Department of Energy's process for implementing the National Environmental Policy Act, contact: Roy Spears, Document Manager National Energy Technology Laboratory U.S. Department of Energy 3610 Collins Ferry Road

294

Kentucky Pioneer Integrated Gasification Combined Cycle Demonstration Project, Final Environmental Impact Statement  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

8 8 U.S. Department of Energy Kentucky Pioneer Integrated Gasification Combined Cycle Demonstration Project Final Environmental Impact Statement November 2002 U.S. Department of Energy National Energy Technology Laboratory COVER SHEET Responsible Agency: U.S. Department of Energy (DOE) Title: Kentucky Pioneer Integrated Gasification Combined Cycle (IGCC) Demonstration Project Final Environmental Impact Statement (EIS) (DOE/EIS-0318) Location: Clark County, Kentucky Contacts: For further information on this environmental For further information on the DOE National impact statement (EIS), call: Environmental Policy Act (NEPA) process, call: 1-800-432-8330 ext. 5460 1-800-472-2756 or contact: or contact: Mr. Roy Spears Ms. Carol Borgstrom

295

ULTRA-CLEAN FISCHER-TROPSCH FUELS PRODUCTION AND DEMONSTRATION PROJECT  

SciTech Connect

The Report Abstract provides summaries of the past year's activities relating to each of the main project objectives. Some of the objectives will be expanded on in greater detail further down in the report. The following objectives have their own addition sections in the report: SFP Construction and Fuel Production, Impact of SFP Fuel on Engine Performance, Fleet Testing at WMATA and Denali National Park, Demonstration of Clean Diesel Fuels in Diesel Electric Generators in Alaska, and Economic Analysis. ICRC provided overall project organization and budget management for the project. ICRC held meetings with various project participants. ICRC presented at the Department of Energy's annual project review meeting. The plant began producing fuel in October 2004. The first delivery of finished fuel was made in March of 2004 after the initial start-up period.

Steve Bergin

2004-10-18T23:59:59.000Z

296

ULTRA-CLEAN FISCHER-TROPSCH FUELS PRODUCTION AND DEMONSTRATION PROJECT  

DOE Green Energy (OSTI)

The Report Abstract provides summaries of the past year's activities relating to each of the main project objectives. Some of the objectives will be expanded on in greater detail further down in the report. The following objectives have their own addition sections in the report: SFP Construction and Fuel Production, Impact of SFP Fuel on Engine Performance, Fleet Testing at WMATA and Denali National Park, Demonstration of Clean Diesel Fuels in Diesel Electric Generators in Alaska, and Economic Analysis. ICRC provided overall project organization and budget management for the project. ICRC held meetings with various project participants. ICRC presented at the Department of Energy's annual project review meeting. The plant began producing fuel in October 2004. The first delivery of finished fuel was made in March of 2004 after the initial start-up period.

Steve Bergin

2004-10-18T23:59:59.000Z

297

Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project: Spring 2009; Composite Data Products, Final Version March 19, 2009  

DOE Green Energy (OSTI)

Graphs of composite data products produced by DOE's Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation project through March 2009.

Wipke, K.; Sprik, S.; Kurtz, J.; Ramsden, T.

2009-03-01T23:59:59.000Z

298

Entering a New Stage of Learning from the U.S. Fuel Cell Electric Vehicle Demonstration Project (Presentation)  

DOE Green Energy (OSTI)

This presentation summarizes Entering a New Stage of Learning from the U.S. Fuel Cell Electric Vehicle Demonstration Project.

Wipke, K.; Sprik, S.; Kurtz, J.; Ramsden, T.; Garbak, J.

2010-11-08T23:59:59.000Z

299

Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project: Spring 2010; Composite Data Products, Final Version March 29, 2010  

SciTech Connect

Graphs of composite data products produced by DOE's Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation project through March 2010.

Wipke, K.; Sprik, S.; Kurtz, J.; Ramsden, T.

2010-05-01T23:59:59.000Z

300

Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project; Spring 2008 Composite Data Products, Final Version: February 29, 2008  

DOE Green Energy (OSTI)

Graphs of composite data products produced by DOE's Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation project through February 2008.

Wipke, K.; Sprik, S.; Kurtz J.

2008-04-01T23:59:59.000Z

Note: This page contains sample records for the topic "bed demonstration project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


301

Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project: Fall 2009; Composite Data Products, Final Version September 11, 2009  

DOE Green Energy (OSTI)

Graphs of composite data products produced by DOE's Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation project through September 2009.

Wipke, K.; Sprik, S.; Kurtz, J.; Ramsden, T.

2009-09-01T23:59:59.000Z

302

Ultra-Clean Fischer-Tropsch Fuels Production and Demonstration Project  

DOE Green Energy (OSTI)

The Report Abstract provides summaries of the past year's activities relating to each of the main project objectives. Some of the objectives will be expanded on in greater detail further down in the report. The following objectives have their own addition sections in the report: Dynamometer Durability Testing, the Denali Bus Fleet Demonstration, Bus Fleet Demonstrations Emissions Analysis, Impact of SFP Fuel on Engine Performance, Emissions Analysis, Feasibility Study of SFPs for Rural Alaska, and Cold Weather Testing of Ultra Clean Fuel.

Steve Bergin

2005-10-14T23:59:59.000Z

303

West Valley Demonstration Project Annual Site Environmental Report Calendar Year 2007  

SciTech Connect

Annual Site Environmental Report for the West Valley Demonstration Project (WVDP) for Calendar Year 2007. The report summarizes the calendar year (CY) 2007 environmental protection program at the WVDP. Monitoring and surveillance of the facilities used by the DOE are conducted to verify protection of public health and safety and the environment.

West Valley Environmental Services LLC (WVES) and URS - Washington Division

2008-12-17T23:59:59.000Z

304

West Valley Demonstration Project Annual Site Environmental Report Calendar Year 2006  

SciTech Connect

Annual Site Environmental Report for the West Valley Demonstration Project (WVDP) for Calendar Year 2006. The report summarizes calendar year (CY) 2006 environmental monitoring data so as to describe the performance of the WVDPs environmental management system (EMS), confirm compliance with standards and regulations, and highlight important programs that protect public health and safety and the environment.

West Valley Nuclear Services Company (WVNSCO) and URS Group, Inc.

2007-09-27T23:59:59.000Z

305

Analysis and Forecasting of the Low-Level Wind during the Sydney 2000 Forecast Demonstration Project  

Science Conference Proceedings (OSTI)

During the Sydney 2000 Forecast Demonstration Project (FDP) a four-dimensional variational assimilation (4DVAR) scheme was run to analyze the low-level wind field with high spatial and temporal resolution. The 4DVAR scheme finds an optimal fit to ...

N. Andrew Crook; Juanzhen Sun

2004-02-01T23:59:59.000Z

306

Design of equipment used for high-level waste vitrification at the West Valley Demonstration Project  

SciTech Connect

The equipment as designed, started, and operated for high-level radioactive waste vitrification at the West Valley Demonstration Project in western New York State is described. Equipment for the processes of melter feed make-up, vitrification, canister handling, and off-gas treatment are included. For each item of equipment the functional requirements, process description, and hardware descriptions are presented.

Vance, R.F.; Brill, B.A.; Carl, D.E. [and others

1997-06-01T23:59:59.000Z

307

Environmental monitoring for the DOE coolside and LIMB demonstration extension projects  

Science Conference Proceedings (OSTI)

The purpose of this document is to present environmental monitoring data collected during the US Department of Energy Limestone Injection Multistage Burner (DOE LIMB) Demonstration Project Extension at the Ohio Edison Edgewater Generating Station in Lorain, Ohio. These data were collected by implementing the Environmental Monitoring Plan (EMP) for the DOE LIMB Demonstration Project Extension, dated August 1988. This document is the fifth EMP status report to be published and presents the data generated during November and December 1990, and January 1991. These reports review a three or four month period and have been published since the project's start in October 1989. The DOE project is an extension of the US Environmental Protection Agency's (EPA) original LIMB Demonstration. The program is operated under DOE's Clean Coal Technology Program of emerging clean coal technologies'' under the categories of in boiler control of oxides of sulfur and nitrogen'' as well as post-combustion clean-up.'' The objective of the LIMB program is to demonstrate the sulfur dioxide (SO{sub 2}) and nitrogen oxide (NO{sub x}) emission reduction capabilities of the LIMB system. The LIMB system is a retrofit technology to be used for existing coal-fired boilers equipped with electrostatic precipitators (ESPs). 5 figs., 12 tabs.

White, T.; Contos, L.

1991-09-01T23:59:59.000Z

308

West Valley Demonstration Project Annual Site Environmental Report Calendard Year 2005  

Science Conference Proceedings (OSTI)

Annual Site Environmental Report for the West Valley Demonstration Project (WVDP) for Calendar Year 2005. The report summarizes calendar year (CY) 2005 environmental monitoring data so as to describe the performance of the WVDP's environmental management system (EMS), confirm compliance with standards and regulations, and highlight important programs.

West Valley Nuclear Services Company (WVNSCO) and URS Group, Inc.

2006-09-21T23:59:59.000Z

309

LIFAC Sorbent Injection Desulfurization Demonstration Project. Quarterly report No. 13, October 1993--December 1993  

Science Conference Proceedings (OSTI)

In Dec 1989, the U.S. Department of Energy selected 13 projects for funding under the Federal Clean Coal Technology Program (Round III). One of the projects selected was the project sponsored by LIFAC North America, (LIFAC NA), titled {open_quotes}LIFAC Sorbent Injection Desulfurization Demonstration Project.{close_quotes} The host site for this $22 million, three-phase project is Richmond Power and Light`s Whitewater Valley Unit No. 2 in Richmond, Indiana. The LIFAC technology uses upper-furnace limestone injection with patented humidification of the flue gas to remove 75-85% of the sulfur dioxide (SO{sub 2}) in the flue gas. In November 1990, after a ten month negotiation period, LIFAC NA and the U.S. DOE entered into a Cooperative Agreement for the design, construction, and demonstration of the LIFAC system. This report is the thirteenth Technical Progress Report covering the period October 1, 1993 through the end of December 1993. Due to the power plant`s planned outage in March 1991, and the time needed for engineering, design and procurement of critical equipment, DOE and LIFAC NA agreed to execute the Design Phase of the project in Aug 1990, with DOE funding contingent upon final signing of the Cooperative Agreement.

Not Available

1994-05-01T23:59:59.000Z

310

West Valley Demonstration Project Administrative Consent Order, August 27, 1996 Summary  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

West Valley Demonstration Project (WVDP) West Valley Demonstration Project (WVDP) Adminstrative Consent Order, August 27, 1996 State New York Agreement Type Consent Order Legal Driver(s) FFCAct Scope Summary Establish commitments regarding compliance with the approved Site Treatment Plan (STP) regarding mixed waste stored and generated at the WVDP Parties DOE; New York State Department of Environmental Conservation (NYSDEC) Date 8/27/1996 SCOPE * Establish commitments regarding compliance with the approved Site Treatment Plan (STP) regarding mixed waste stored and generated at the WVDP. * Establish an enforceable framework in which DOE will develop and apply treatment or otherwise meet Land Disposal Restriction (LDR) requirements. * Provide for storage of current and projected LDR mixed wastes at the WVDP pending

311

Environmental Assessment for the Warren Station externally fired combined cycle demonstration project  

SciTech Connect

The proposed Penelec project is one of 5 projects for potential funding under the fifth solicitation under the Clean Coal Technology program. In Penelec, two existing boilers would be replaced at Warren Station, PA; the new unit would produce 73 MW(e) in a combined cycle mode (using both gas-fired and steam turbines). The project would fill the need for a full utility-size demonstration of externally fire combined cycle (EFCC) technology as the next step toward commercialization. This environmental assessment was prepared for compliance with NEPA; its purpose is to provide sufficient basis for determining whether to prepare an environmental impact statement or to issue a finding of no significant impact. It is divided into the sections: purpose and need for proposed action; alternatives; brief description of affected environment; environmental consequences, including discussion of commercial operation beyond the demonstration period.

NONE

1995-04-01T23:59:59.000Z

312

Electric Ground Support Equipment Advanced Battery Technology Demonstration Project at the Ontario Airport  

SciTech Connect

The intent of the electric Ground Support Equipment (eGSE) demonstration is to evaluate the day-to-day vehicle performance of electric baggage tractors using two advanced battery technologies to demonstrate possible replacements for the flooded lead-acid (FLA) batteries utilized throughout the industry. These advanced battery technologies have the potential to resolve barriers to the widespread adoption of eGSE deployment. Validation testing had not previously been performed within fleet operations to determine if the performance of current advanced batteries is sufficient to withstand the duty cycle of electric baggage tractors. This report summarizes the work performed and data accumulated during this demonstration in an effort to validate the capabilities of advanced battery technologies. This report summarizes the work performed and data accumulated during this demonstration in an effort to validate the capabilities of advanced battery technologies. The demonstration project also grew the relationship with Southwest Airlines (SWA), our demonstration partner at Ontario International Airport (ONT), located in Ontario, California. The results of this study have encouraged a proposal for a future demonstration project with SWA.

Tyler Gray; Jeremy Diez; Jeffrey Wishart; James Francfort

2013-07-01T23:59:59.000Z

313

RADIOACTIVE DEMONSTRATION OF MINERALIZED WASTE FORMS MADE FROM HANFORD LOW ACTIVITY WASTE (TANK FARM BLEND) BY FLUIDIZED BED STEAM REFORMATION (FBSR)  

Science Conference Proceedings (OSTI)

The U.S. Department of Energys Office of River Protection (ORP) is responsible for the retrieval, treatment, immobilization, and disposal of Hanfords tank waste. A key aspect of the River Protection Project (RPP) cleanup mission is to construct and operate the Hanford Tank Waste Treatment and Immobilization Plant (WTP). The WTP will separate the tank waste into high-level and low-activity waste (LAW) fractions, both of which will subsequently be vitrified. The projected throughput capacity of the WTP LAW Vitrification Facility is insufficient to complete the RPP mission in the time frame required by the Hanford Federal Facility Agreement and Consent Order, also known as the Tri-Party Agreement (TPA), i.e. December 31, 2047. Supplemental Treatment is likely to be required both to meet the TPA treatment requirements as well as to more cost effectively complete the tank waste treatment mission. The Supplemental Treatment chosen will immobilize that portion of the retrieved LAW that is not sent to the WTPs LAW Vitrification facility into a solidified waste form. The solidified waste will then be disposed on the Hanford site in the Integrated Disposal Facility (IDF). Fluidized Bed Steam Reforming (FBSR) offers a moderate temperature (700-750C) continuous method by which LAW can be processed irrespective of whether the waste contain organics, nitrates, sulfates/sulfides, chlorides, fluorides, volatile radionuclides or other aqueous components. The FBSR technology can process these wastes into a crystalline ceramic (mineral) waste form. The mineral waste form that is produced by co-processing waste with kaolin clay in an FBSR process has been shown to be comparable to LAW glass, i.e. leaches Tc-99, Re and Na at 6 (the Hanford IDF criteria for Na) in the first few hours. The granular and monolithic waste forms also pass the EPA Toxicity Characteristic Leaching Procedure (TCLP) for all Resource Conservation and Recovery Act (RCRA) components at the Universal Treatment Standards (UTS). Two identical Benchscale Steam Reformers (BSR) were designed and constructed at SRNL, one to treat non-radioactive simulants and the other to treat actual radioactive wastes. The results from the non-radioactive BSR were used to determine the parameters needed to operate the radioactive BSR in order to confirm the findings of non-radioactive FBSR pilot scale and engineering scale tests and to qualify an FBSR LAW waste form for applications at Hanford. Radioactive testing commenced using SRS LAW from Tank 50 chemically trimmed to look like Hanfords blended LAW known as the Rassat simulant as this simulant composition had been tested in the non-radioactive BSR, the non-radioactive pilot scale FBSR at the Science Applications International Corporation-Science and Technology Applications Research (SAIC-STAR) facility in Idaho Falls, ID and in the TTT Engineering Scale Technology Demonstration (ESTD) at Hazen Research Inc. (HRI) in Denver, CO. This provided a tie back between radioactive BSR testing and non-radioactive BSR, pilot scale, and engineering scale testing. Approximately six hundred grams of non-radioactive and radioactive BSR product were made for extensive testing and comparison to the non-radioactive pilot scale tests performed in 2004 at SAIC-STAR and the engineering scale test performed in 2008 at HRI with the Rassat simulant. The same mineral phases and off-gas species were found in the radioactive and non-radioactive testing. The granular ESTD and BSR products (radioactive and non-radioactive) were analyzed for to

Jantzen, C. M.; Crawford, C. L.; Bannochie, C. J.; Burket, P. R.; Cozzi, A. D.; Daniel, W. E.; Hall, H. K.; Miller, D. H.; Missimer, D. M.; Nash, C. A.; Williams, M. F.

2013-08-21T23:59:59.000Z

314

RADIOACTIVE DEMONSTRATION OF FINAL MINERALIZED WASTE FORMS FOR HANFORD WASTE TREATMENT PLANT SECONDARY WASTE BY FLUIDIZED BED STEAM REFORMING USING THE BENCH SCALE REFORMER PLATFORM  

Science Conference Proceedings (OSTI)

The U.S. Department of Energy's Office of River Protection (ORP) is responsible for the retrieval, treatment, immobilization, and disposal of Hanford's tank waste. Currently there are approximately 56 million gallons of highly radioactive mixed wastes awaiting treatment. A key aspect of the River Protection Project (RPP) cleanup mission is to construct and operate the Waste Treatment and Immobilization Plant (WTP). The WTP will separate the tank waste into high-level and low-activity waste (LAW) fractions, both of which will subsequently be vitrified. The projected throughput capacity of the WTP LAW Vitrification Facility is insufficient to complete the RPP mission in the time frame required by the Hanford Federal Facility Agreement and Consent Order, also known as the Tri-Party Agreement (TPA), i.e. December 31, 2047. Therefore, Supplemental Treatment is required both to meet the TPA treatment requirements as well as to more cost effectively complete the tank waste treatment mission. In addition, the WTP LAW vitrification facility off-gas condensate known as WTP Secondary Waste (WTP-SW) will be generated and enriched in volatile components such as {sup 137}Cs, {sup 129}I, {sup 99}Tc, Cl, F, and SO{sub 4} that volatilize at the vitrification temperature of 1150 C in the absence of a continuous cold cap (that could minimize volatilization). The current waste disposal path for the WTP-SW is to process it through the Effluent Treatment Facility (ETF). Fluidized Bed Steam Reforming (FBSR) is being considered for immobilization of the ETF concentrate that would be generated by processing the WTP-SW. The focus of this current report is the WTP-SW. FBSR offers a moderate temperature (700-750 C) continuous method by which WTP-SW wastes can be processed irrespective of whether they contain organics, nitrates, sulfates/sulfides, chlorides, fluorides, volatile radionuclides or other aqueous components. The FBSR technology can process these wastes into a crystalline ceramic (mineral) waste form. The mineral waste form that is produced by co-processing waste with kaolin clay in an FBSR process has been shown to be as durable as LAW glass. Monolithing of the granular FBSR product is being investigated to prevent dispersion during transport or burial/storage, but is not necessary for performance. A Benchscale Steam Reformer (BSR) was designed and constructed at the SRNL to treat actual radioactive wastes to confirm the findings of the non-radioactive FBSR pilot scale tests and to qualify the waste form for applications at Hanford. BSR testing with WTP SW waste surrogates and associated analytical analyses and tests of granular products (GP) and monoliths began in the Fall of 2009, and then was continued from the Fall of 2010 through the Spring of 2011. Radioactive testing commenced in 2010 with a demonstration of Hanford's WTP-SW where Savannah River Site (SRS) High Level Waste (HLW) secondary waste from the Defense Waste Processing Facility (DWPF) was shimmed with a mixture of {sup 125/129}I and {sup 99}Tc to chemically resemble WTP-SW. Prior to these radioactive feed tests, non-radioactive simulants were also processed. Ninety six grams of radioactive granular product were made for testing and comparison to the non-radioactive pilot scale tests. The same mineral phases were found in the radioactive and non-radioactive testing.

Crawford, C.; Burket, P.; Cozzi, A.; Daniel, W.; Jantzen, C.; Missimer, D.

2012-02-02T23:59:59.000Z

315

Nome, Alaska, Wind Turbine Demonstration Project Finding of No Significant Impact  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Finding of No Significant Impact Finding of No Significant Impact Nome, Alaska, Wind Turbine Demonstration Project FINDING OF NO SIGNIFICANT IMPACT S U M M A R Y The U.S. Department of Energy (DOE) has prepared this Environmental Assessment (EA) to provide DOE and other public agency decision makers witb tbe environmental documentation required to take informed discretionary action on the proposed Nome, Alaska, Wind Turbine Demonstration Project (DOE/EA-1280). The EA assesses the potential environmental impacts and cumulative i m p a c t s that would result from the jnstallation and operation of wind turbines in Nome, Alaska DOE'S role in the proposed action would be limited to providing ,$ding assistance for a portion of the construction and demonstration of wind energy technology in the

316

Environmental monitoring for the DOE coolside and LIMB demonstration extension projects  

SciTech Connect

The purpose of this document is to present environmental monitoring data collected during the US Department of Energy Limestone Injection Multistage Burner (DOE LIMB) Demonstration Project Extension at the Ohio Edison Edgewater Generating Station in Lorain, Ohio. The DOE project is an extension of the US Environmental Protection Agency's (EPA's) original LIMB Demonstration. The program is operated nuclear DOE's Clean Coal Technology Program of emerging clean coal technologies'' under the categories of in boiler control of oxides of sulfur and nitrogen'' as well as post-combustion clean-up.'' The objective of the LIMB program is to demonstrate the sulfur dioxide (SO{sub 2}) and nitrogen oxide (NO{sub x}) emission reduction capabilities of the LIMB system. The LIMB system is a retrofit technology to be used for existing coal-fired boilers equipped with electrostatic precipitators (ESPs).

White, T.; Contos, L.; Adams, L. (Radian Corp., Research Triangle Park, NC (United States))

1992-03-01T23:59:59.000Z

317

West Valley Demonstration Project Annual Site Environmental Report Calendar Year 2010  

SciTech Connect

The West Valley Demonstration Project (WVDP) Annual Site Environmental Report (ASER) for Calendar Year 2010. The report, prepared for the U.S. Department of Energy West Valley Demonstration Project office (DOE-WVDP), summarizes the environmental protection program at the WVDP for calendar year (CY) 2010. Monitoring and surveillance of the facilities used by the DOE are conducted to verify protection of public health and safety and the environment. The report is a key component of DOE's effort to keep the public informed of environmental conditions at the WVDP. The quality assurance protocols applied to the environmental monitoring program ensure the validity and accuracy of the monitoring data. In addition to demonstrating compliance with environmental laws, regulations and directives, evaluation of data collected in 2010 continued to indicate that WVDP activities pose no threat to public health or safety, or to the environment.

CH2MHILL B& W West Valley, LLC

2011-09-28T23:59:59.000Z

318

West Valley Demonstration Project Annual Site Environmental Report Calendar Year 2009  

SciTech Connect

The West Valley Demonstration Project (WVDP) Annual Site Environmental Report (ASER) for Calendar Year 2009. The report, prepared by the U.S. Department of Energy West Valley Demonstration Project office (DOE-WVDP), summarizes the environmental protection program at the WVDP for calendar year (CY) 2009. Monitoring and surveillance of the facilities used by the DOE are conducted to verify protection of public health and safety and the environment. The report is a key component of DOEs effort to keep the public informed of environmental conditions at the WVDP. The quality assurance protocols applied to the environmental monitoring program by the DOE ensure the validity and accuracy of the monitoring data. In addition to demonstrating compliance with environmental regulations and directives, evaluation of data collected in 2009 continued to indicate that WVDP activities pose no threat to public health or safety, or to the environment.

West Valley Environmental Services LLC (WVES) and URS Corporation

2010-09-17T23:59:59.000Z

319

West Valley Demonstration Project Annual Site Environmental Report Calendar Year 2011  

Science Conference Proceedings (OSTI)

The West Valley Demonstration Project (WVDP) Annual Site Environmental Report (ASER) for Calendar Year 2011. The report, prepared for the U.S. Department of Energy West Valley Demonstration Project office (DOE-WVDP), summarizes the environmental protection program at the WVDP for calendar year (CY) 2011. Monitoring and surveillance of the facilities used by the DOE are conducted to verify protection of public health and safety and the environment. The report is a key component of DOEs effort to keep the public informed of environmental conditions at the WVDP. The quality assurance protocols applied to the environmental monitoring program ensure the validity and accuracy of the monitoring data. In addition to demonstrating compliance with environmental laws, regulations, and directives, evaluation of data collected in 2011 continued to indicate that WVDP activities pose no threat to public health or safety, or to the environment.

CH2M HILL B& W West Valley, LLC

2012-09-27T23:59:59.000Z

320

West Valley Demonstration Project Annual Site Environmental Report Calendar Year 2012  

SciTech Connect

The West Valley Demonstration Project (WVDP) Annual Site Environmental Report (ASER) for Calendar Year 2012. The report, prepared for the U.S. Department of Energy West Valley Demonstration Project office (DOE-WVDP), summarizes the environmental protection program at the WVDP for calendar year (CY) 2012. Monitoring and surveillance of the facilities used by the DOE are conducted to verify protection of public health and safety and the environment. The report is a key component of DOEs effort to keep the public informed of environmental conditions at the WVDP. The quality assurance protocols applied to the environmental monitoring program ensure the validity and accuracy of the monitoring data. In addition to demonstrating compliance with environmental laws, regulations, and directives, evaluation of data collected in 2012 continued to indicate that WVDP activities pose no threat to public health or safety, or to the environment.

Rendall, John D. [CH2M HILL B& W West Valley, LLC (CHBWV); Steiner, Alison F. [URS Professional Solutions (URSPS); Klenk, David P. [CH2M HILL B& W West Valley, LLC (CHBWV)

2013-09-19T23:59:59.000Z

Note: This page contains sample records for the topic "bed demonstration project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


321

Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project: Fall 2006 Progress Update  

DOE Green Energy (OSTI)

The U.S. Department of Energy (DOE) initiated the Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project through a competitive solicitation process in 2003. The purpose of this project is to conduct an integrated field validation that simultaneously examines the performance of fuel cell vehicles and the supporting hydrogen infrastructure. Four industry teams have signed cooperative agreements with DOE and are supporting plans for more than 130 fuel cell vehicles and 20 hydrogen refueling stations over the 5-year project duration. This paper provides a status update covering the progress accomplished by the demonstration and validation project over the last six months; the first composite data products from the project were published in March 2006. The composite data products aggregate individual performance into a range that protects the intellectual property of the companies involved, while publicizing the progress the hydrogen and fuel cell industry is making as a whole relative to the program objectives and timeline. Updates to previously published composite data products, such as on-road fuel economy and vehicle/infrastructure safety, will be presented along with new composite data products, such as fuel cell stack efficiency and refueling behavior.

Wipke, K.; Welch, C.; Thomas, H.; Sprik, S.; Gronich, S.; Garbak, J.

2006-10-01T23:59:59.000Z

322

LIFAC Sorbent Injection Desulfurization Demonstration Project. Quarterly report No. 12, July--September 1993  

Science Conference Proceedings (OSTI)

In December 1989, the U.S. Department of Energy selected 13 projects for funding under the Federal Clean Coal Technology Program (Round III). One of the projects selected was the project sponsored by LIFAC North America, (LIFAC NA), titled {open_quotes}LIFAC Sorbent Injection Desulfurization Demonstration Project.{close_quotes} The LIFAC technology uses upper-furnace limestone injection with patented humidification of the flue gas to remove 75-85% of the sulfur dioxide (SO{sub 2}) in the flue gas. The host site for this $22 million, three-phase project is Richmond Power and Light`s Whitewater Valley Unit No. 2 in Richmond, Indiana. The three project phases are: (1) Design; (2A) Long Lead Procurement; (2B) Construction; and (3) Operations. The design phase began on August 8, 1990 and was scheduled to last six months. Phase 2A, long lead procurement, overlaps the design phase and was expected to require about four months to complete. The construction phase was then to continue for another seven months, while the operations phase was scheduled to last about twenty-six months. In November 1990, after a ten (10) month negotiation period, LIFAC NA and the U.S. DOE entered into a Cooperative Agreement for the design, construction, and demonstration of the LIFAC system. This report is the twelfth Technical Progress Report covering the period July 1, 1993 through the end of September 1993. Due to the power plant`s planned outage in March 1991, and the time needed for engineering, design and procurement of critical equipment, DOE and LIFAC NA agreed to execute the Design Phase of the project in August 1990, with DOE funding contingent upon final signing of the Cooperative Agreement.

Not Available

1993-12-31T23:59:59.000Z

323

Incidental-to-Reprocessing Evaluation for the West Valley Demonstration Project  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Responses to Public Comments on the Draft Waste- Responses to Public Comments on the Draft Waste- Incidental-to-Reprocessing Evaluation for the West Valley Demonstration Project Concentrator Feed Makeup Tank and Melter Feed Hold Tank 1 Introduction The U.S. Department of Energy (DOE) is providing responses to the comments received from the public and from state and county agencies on the West Valley Demonstration Project (WVDP) Draft Waste-Incidental-to-Reprocessing (WIR) Evaluation for the Concentrator Feed Makeup Tank (CFMT) and the Melter Feed Hold Tank (MFHT), referred to hereafter as the Draft Evaluation. As a matter of policy and to provide greater transparency in its efforts to cleanup waste at the WVDP, DOE made the Draft Evaluation available for public and state review and comment, as

324

2012 Annual Workforce Analysis and Staffing Plan Report - West Valley Demonstration Project  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

ATTACHMENT ATTACHMENT 1 Annual Workforce Analysis and Staffing Plan Report As ofDecember 31, 2012 Reporting Office: West Valley Demonstration Project Section 1: Current Mission(s) of the Organization and Potential Changes The mission of the WVDP as defined by the West Valley Demonstration Project Act (Public Law 96-368) is to accomplish five activities: 1) solidify high-level radioactive waste (HLW), 2) develop containers suitable for permanent disposal of the HLW, 3) transport the HLW to a Federal repository for permanent disposal, 4) dispose of low-level and transuranic waste produced by the solidification of the HLW, and 5) decontaminate and decommission the HLW tanks and facilities, materials and hardware used to solidify the HLW. DOE expects to accomplish these WVDP activities through proactive leadership, management, and implementation of safe and environmentally sound operations.

325

West Valley demonstration project: alternative processes for solidifying the high-level wastes  

SciTech Connect

In 1980, the US Department of Energy (DOE) established the West Valley Solidification Project as the result of legislation passed by the US Congress. The purpose of this project was to carry out a high level nuclear waste management demonstration project at the Western New York Nuclear Service Center in West Valley, New York. The DOE authorized the Pacific Northwest Laboratory (PNL), which is operated by Battelle Memorial Institute, to assess alternative processes for treatment and solidification of the WNYNSC high-level wastes. The Process Alternatives Study is the suject of this report. Two pretreatment approaches and several waste form processes were selected for evaluation in this study. The two waste treatment approaches were the salt/sludge separation process and the combined waste process. Both terminal and interim waste form processes were studied.

Holton, L.K.; Larson, D.E.; Partain, W.L.; Treat, R.L.

1981-10-01T23:59:59.000Z

326

Environmental Assessment and Finding of No Significant Impact: Kalina Geothermal Demonstration Project Steamboat Springs, Nevada  

DOE Green Energy (OSTI)

The Department of Energy (DOE) has prepared an Environmental Assessment (EA) to provide the DOE and other public agency decision makers with the environmental documentation required to take informed discretionary action on the proposed Kalina Geothermal Demonstration project. The EA assesses the potential environmental impacts and cumulative impacts, possible ways to minimize effects associated with partial funding of the proposed project, and discusses alternatives to DOE actions. The DOE will use this EA as a basis for their decision to provide financial assistance to Exergy, Inc. (Exergy), the project applicant. Based on the analysis in the EA, DOE has determined that the proposed action is not a major Federal action significantly affecting the quality of the human or physical environment, within the meaning of the National Environmental Policy Act (NEPA) of 1969. Therefore, the preparation of an environmental impact statement is not required and DOE is issuing this Finding of No Significant Impact (FONSI).

N /A

1999-02-22T23:59:59.000Z

327

Summary of Demonstration Projects Using Coal Combustion Residuals as Engineered Structural Fill  

Science Conference Proceedings (OSTI)

This report summarizes six demonstration projects in which coal combustion residuals (CCRs) were used as engineered structural fill to construct embankments for highways, a bridge approach, and an airport runway extension. The CCRs studied included coal fly ash, bottom ash, and stabilized flue gas desulfurization (FGD) material. Significant aspects of the design, construction, and performance of these structural fills are described. CCRs are often cost-effective substitutes for natural soils in structura...

2010-11-09T23:59:59.000Z

328

The integrated melter off-gas treatment systems at the West Valley Demonstration Project  

SciTech Connect

The West Valley Demonstration project was established by an act of Congress in 1980 to solidify the high level radioactive liquid wastes produced from operation of the Western New York Nuclear Services Center from 1966 to 1972. The waste will be solidified as borosilicate glass. This report describes the functions, the controlling design criteria, and the resulting design of the melter off-gas treatment systems.

Vance, R.F.

1991-12-01T23:59:59.000Z

329

SRC-1: coal liquefaction demonstration plant. Project Baseline assessment report supplement  

Science Conference Proceedings (OSTI)

ICRC issued a Revised Baseline for the SRC-I Demonstration Project in order to incorporate the results of these research activities and the changes in the design that had occurred since FY82. The Revised Baseline, prepared by ICRC, provides the necessary information for any future government or commercial decisions relating to the design, construction and operation of an SRC-I-type coal liquefaction facility. No further activities to complete the design of the demonstration plant, or to proceed with construction are planned by DOE. The Project Baseline is an ICRC-documented reference for controlling any future project work and cost. The original Baseline was issued in March 1982; this summary document is available from National Technical Information Service (NTIS) as document number DOE/ORO/030540-T13. The Revised Baseline (dated April 1984) is available as document numbers DOE/OR/03054-T14 and T16. Supporting documentation, in the main concerned with research activities undertaken in support of the design, is also available from NTIS as DOE/OR/03054-T1 through T10 and DOE/OR/03054-1 through 125. The Baseline itself is made up of a documented design configuration, a documented estimate, in First Quarter Fiscal Year 1982 Dollars (1QFY82$), and a detailed schedule of the activities required to complete the project as of 3QFY82. The Baseline design is embodied in the 26 process design packages and other support documentation identified in the Baseline, as well as preliminary engineering flow diagrams prepared for all of the major process areas of the plant. All elements of the Project Baseline were developed within the constraints of the project criteria.

Not Available

1984-09-01T23:59:59.000Z

330

Environmental assessment for the Waste Water Treatment Facility at the West Valley Demonstration Project and finding of no significant impact  

SciTech Connect

The possible environmental impacts from the construction and operation of a waste water treatment facility for the West Valley Demonstration Project are presented. The West Valley Project is a demonstration project on the solidification of high-level radioactive wastes. The need for the facility is the result of a rise in the work force needed for the project which rendered the existing sewage treatment plant incapable of meeting the nonradioactive waste water treatment needs.

1992-12-31T23:59:59.000Z

331

California Food Processing Industry Wastewater Demonstration Project: Phase I Final Report  

Science Conference Proceedings (OSTI)

Wastewater treatment is an energy-intensive process and electricity demand is especially high during the utilities summer peak electricity demand periods. This makes wastewater treatment facilities prime candidates for demand response programs. However, wastewater treatment is often peripheral to food processing operations and its demand response opportunities have often been overlooked. Phase I of this wastewater demonstration project monitored wastewater energy and environmental data at Bell-Carter Foods, Inc., California's largest olive processing plant. For this monitoring activity the project team used Green Energy Management System (GEMS) automated enterprise energy management (EEM) technologies. This report presents results from data collected by GEMS from September 15, 2008 through November 30, 2008, during the olive harvest season. This project established and tested a methodology for (1) gathering baseline energy and environmental data at an industrial food-processing plant and (2) using the data to analyze energy efficiency, demand response, daily peak load management, and environmental management opportunities at the plant. The Phase I goals were to demonstrate the measurement and interrelationship of electricity demand, electricity usage, and water quality metrics and to estimate the associated CO{sub 2} emissions.

Lewis, Glen; Atkinson, Barbara; Rhyne, Ivin

2009-09-09T23:59:59.000Z

332

Methodological Approaches for Estimating the Benefits and Costs of Smart Grid Demonstration Projects  

Science Conference Proceedings (OSTI)

This report presents a comprehensive framework for estimating the benefits and costs of Smart Grid projects and a step-by-step approach for making these estimates. The framework identifies the basic categories of benefits, the beneficiaries of these benefits, and the Smart Grid functionalities that lead to different benefits and proposes ways to estimate these benefits, including their monetization. The report covers cost-effectiveness evaluation, uncertainty, and issues in estimating baseline conditions against which a project would be compared. The report also suggests metrics suitable for describing principal characteristics of a modern Smart Grid to which a project can contribute. This first section of the report presents background information on the motivation for the report and its purpose. Section 2 introduces the methodological framework, focusing on the definition of benefits and a sequential, logical process for estimating them. Beginning with the Smart Grid technologies and functions of a project, it maps these functions to the benefits they produce. Section 3 provides a hypothetical example to illustrate the approach. Section 4 describes each of the 10 steps in the approach. Section 5 covers issues related to estimating benefits of the Smart Grid. Section 6 summarizes the next steps. The methods developed in this study will help improve future estimates - both retrospective and prospective - of the benefits of Smart Grid investments. These benefits, including those to consumers, society in general, and utilities, can then be weighed against the investments. Such methods would be useful in total resource cost tests and in societal versions of such tests. As such, the report will be of interest not only to electric utilities, but also to a broad constituency of stakeholders. Significant aspects of the methodology were used by the U.S. Department of Energy (DOE) to develop its methods for estimating the benefits and costs of its renewable and distributed systems integration demonstration projects as well as its Smart Grid Investment Grant projects and demonstration projects funded under the American Recovery and Reinvestment Act (ARRA). The goal of this report, which was cofunded by the Electric Power Research Institute (EPRI) and DOE, is to present a comprehensive set of methods for estimating the benefits and costs of Smart Grid projects. By publishing this report, EPRI seeks to contribute to the development of methods that will establish the benefits associated with investments in Smart Grid technologies. EPRI does not endorse the contents of this report or make any representations as to the accuracy and appropriateness of its contents. The purpose of this report is to present a methodological framework that will provide a standardized approach for estimating the benefits and costs of Smart Grid demonstration projects. The framework also has broader application to larger projects, such as those funded under the ARRA. Moreover, with additional development, it will provide the means for extrapolating the results of pilots and trials to at-scale investments in Smart Grid technologies. The framework was developed by a panel whose members provided a broad range of expertise.

Lee, Russell [ORNL

2010-01-01T23:59:59.000Z

333

2012 SG Peer Review - Recovery Act: Secure Interoperable Open Smart Grid Demonstration Project - Tom Magee, ConEd NY  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Demonstration Project Demonstration Project Patricia Robison Con Edison June 8, 2012 December 2008 Smart Grid Demonstration Project Objective Life-cycle Funding FY10 - FY13 $45.4 m Technical Scope (Insert graphic here) 2 *Integrate Legacy and Smart Grid information systems *Integrate external DR into distribution grid systems: - EV/Battery storage - Building Management Systems (BMS) - Standby generation - Photovoltaic Demonstrate secure interoperable services between utility distribution systems and customer owned distributed resources (DR) December 2008 Needs and Project Targets Integrate customer owned resources into distribution operations to enable customer participation and defer capital investment *Integrate DR resources into operator platform *Implement secure communications to DR resources

334

Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project: First Set of Composite Data Products for Publication - March 1, 2006  

DOE Green Energy (OSTI)

This presentation provides the initial composite data products available for publication from NREL's Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project.

Wipke, K.; Welch, C.; Thomas, H.; Sprik, S.

2007-02-01T23:59:59.000Z

335

Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project: Spring 2007 Composite Data Products; March 8, 2007  

DOE Green Energy (OSTI)

This presentation provides the composite data products from Spring 2007 from NREL's Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project.

Wipke, K.; Sprik, S.; Thomas, H.; Welch, C.

2007-04-01T23:59:59.000Z

336

Technical support to the Solvent Refined Coal (SRC) demonstration projects: assessment of current research and development  

SciTech Connect

A program to demonstrate Solvent Refined Coal (SRC) technology has been initiated by the US Department of Energy (DOE) in partnership with two industrial groups. Project management responsibility has been assigned to the Oak Ridge Operations Office (ORO) of DOE. ORO requested that the Oak Ridge National Laboratory assess current research and development (R and D) activities and develop recommendations for those activities that might contribute to successful completion of the SRC demonstration plant projects. The objectives of this final report are to discuss in detail the problem areas in SRC; to discuss the current and planned R and D investigations relevant to the problems identified; and to suggest appropriate R and D activities in support of designs for the SRC demonstration plants. Four types of R and D activities are suggested: continuation of present and planned activities; coordination of activities and results, present and proposed; extension/redirection of activities not involving major equipment purchase or modifications; and new activities. Important examples of the first type of activity include continuation of fired heater, slurry rheology, and slurry mixing studies at Ft. Lewis. Among the second type of activity, coordination of data acquisition and interpretation is recommended in the areas of heat transfer, vapor/liquid equilibria, and physical properties. Principal examples of recommendations for extension/redirection include screening studies at laboratory scale on the use of carbonaceous precoat (e.g., anthracite) infiltration, and 15- to 30-day continuous tests of the Texaco gasifier at the Texaco Montebello facility (using SRC residues).

Edwards, M.S.; Rodgers, B.R.; Brown, C.H.; Carlson, P.K.; Gambill, W.R.; Gilliam, T.M.; Holmes, J.M.; Krishnan, R.P.; Parsly, L.F.

1980-12-01T23:59:59.000Z

337

Renewable Energy Demonstration Project by the National Renewable Energy Laboratory and the General Services Administration  

DOE Green Energy (OSTI)

The Energy Policy Act of 1992 (EPACT) requires the General Services Administration (GSA) to implement a solar energy program to demonstrate and evaluate the performance of available technologies expected to have widespread commercial application. The GSA decided to carry out the project at the Denver Federal Center because of its proximity to the National Renewable Energy Laboratory (NREL). The location was thought to be of mutual benefit to NREL and the GSA: it provides NREL an opportunity to deploy technology and it provides the GSA an opportunity to gain a hands-on learning experience with renewables. The GSA plans to document their experience and use it as a case study in part of a larger training effort on renewable energy. This paper describes the technology selection process and provides an update on the status of the project.

Carlisle, N; Hoo, E; Westby, R [National Renewable Energy Lab., Golden, CO (United States); Hancock, E [Ed Hancock and Associates, Boulder, CO (United States); Lu, J [General Services Administration, Washington, DC (United States)

1994-11-01T23:59:59.000Z

338

ESS 2012 Peer Review - DOE-OE FY12 Electrical Energy Storage Demonstration Projects - Dan Borneo, SNL  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

DOE-OE FY12 Electrical DOE-OE FY12 Electrical Energy Storage Demonstration Projects The Renaissance Hotel Washington, D.C. September 2012 Presented by Dan Borneo SAND Document 5312608 SAND2012-7453 C Acknowledgements I would like to thank the DOE's Office of Electricity and Dr. Imre Gyuk, Program Manager of the Electrical Energy Storage Program, for their support and funding of the Energy Storage Demonstration Projects. 2 EES Emerging Technology Demonstrations Presentation Outline  Project Overview  Problem Statement  Approach  Current Status  Path Forward - Next Steps  Geographical Representation of Projects  Summary Chart of Projects  Brief Descriptions of Individual Projects  Concluding Remarks 3 EES Demonstrations Project Overview  Problem Statement

339

Investigation of Fuel Chemistry and Bed Performance in a Fluidized Bed Black Liquor Steam Reformer  

DOE Green Energy (OSTI)

University of Utah's project entitled 'Investigation of Fuel Chemistry and Bed Performance in a Fluidized Bed Black Liquor Steam Reformer' (DOE Cooperative Agreement DE-FC26-02NT41490) was developed in response to a solicitation released by the U.S. Department of Energy in December 2001, requesting proposals for projects targeted towards black liquor/biomass gasification technology support research and development. Specifically, the solicitation was seeking projects that would provide technical support for Department of Energy supported black liquor and biomass gasification demonstration projects under development at the time.

Kevin Whitty

2007-06-30T23:59:59.000Z

340

The Role of Occupant Behavior in Achieving Net Zero Energy: A Demonstration Project at Fort Carson  

SciTech Connect

This study, sponsored by the U.S. General Services Administrations Office of Federal High-Performance Green Buildings, aimed to understand the potential for institutional and behavioral change to enhance the performance of buildings, through a demonstration project with the Department of Defense in five green buildings on the Fort Carson, Colorado, Army base. To approach this study, the research team identified specific occupant behaviors that had the potential to save energy in each building, defined strategies that might effectively support behavior change, and implemented a coordinated set of actions during a three-month intervention.

Judd, Kathleen S.; Sanquist, Thomas F.; Zalesny, Mary D.; Fernandez, Nicholas

2013-09-30T23:59:59.000Z

Note: This page contains sample records for the topic "bed demonstration project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


341

RADIOACTIVE DEMONSTRATION OF MINERALIZED WASTE FORMS MADE FROM HANFORD LOW ACTIVITY WASTE (TANK FARM BLEND) BY FLUIDIZED BED STEAM REFORMATION (FBSR)  

SciTech Connect

The U.S. Department of Energys Office of River Protection (ORP) is responsible for the retrieval, treatment, immobilization, and disposal of Hanfords tank waste. A key aspect of the River Protection Project (RPP) cleanup mission is to construct and operate the Hanford Tank Waste Treatment and Immobilization Plant (WTP). The WTP will separate the tank waste into high-level and low-activity waste (LAW) fractions, both of which will subsequently be vitrified. The projected throughput capacity of the WTP LAW Vitrification Facility is insufficient to complete the RPP mission in the time frame required by the Hanford Federal Facility Agreement and Consent Order, also known as the Tri-Party Agreement (TPA), i.e. December 31, 2047. Supplemental Treatment is likely to be required both to meet the TPA treatment requirements as well as to more cost effectively complete the tank waste treatment mission. The Supplemental Treatment chosen will immobilize that portion of the retrieved LAW that is not sent to the WTPs LAW Vitrification facility into a solidified waste form. The solidified waste will then be disposed on the Hanford site in the Integrated Disposal Facility (IDF). Fluidized Bed Steam Reforming (FBSR) offers a moderate temperature (700-750C) continuous method by which LAW can be processed irrespective of whether the waste contain organics, nitrates, sulfates/sulfides, chlorides, fluorides, volatile radionuclides or other aqueous components. The FBSR technology can process these wastes into a crystalline ceramic (mineral) waste form. The mineral waste form that is produced by co-processing waste with kaolin clay in an FBSR process has been shown to be comparable to LAW glass, i.e. leaches Tc-99, Re and Na at <2g/m2 during ASTM C1285 (Product Consistency) durability testing. Monolithing of the granular FBSR product was investigated to prevent dispersion during transport or burial/storage. Monolithing in an inorganic geopolymer binder, which is amorphous, macro-encapsulates the granules, and the monoliths pass ANSI/ANS 16.1 and ASTM C1308 durability testing with Re achieving a Leach Index (LI) of 9 (the Hanford Integrated Disposal Facility, IDF, criteria for Tc-99) after a few days and Na achieving an LI of >6 (the Hanford IDF criteria for Na) in the first few hours. The granular and monolithic waste forms also pass the EPA Toxicity Characteristic Leaching Procedure (TCLP) for all Resource Conservation and Recovery Act (RCRA) components at the Universal Treatment Standards (UTS). Two identical Benchscale Steam Reformers (BSR) were designed and constructed at SRNL, one to treat non-radioactive simulants and the other to treat actual radioactive wastes. The results from the non-radioactive BSR were used to determine the parameters needed to operate the radioactive BSR in order to confirm the findings of non-radioactive FBSR pilot scale and engineering scale tests and to qualify an FBSR LAW waste form for applications at Hanford. Radioactive testing commenced using SRS LAW from Tank 50 chemically trimmed to look like Hanfords blended LAW known as the Rassat simulant as this simulant composition had been tested in the non-radioactive BSR, the non-radioactive pilot scale FBSR at the Science Applications International Corporation-Science and Technology Applications Research (SAIC-STAR) facility in Idaho Falls, ID and in the TTT Engineering Scale Technology Demonstration (ESTD) at Hazen Research Inc. (HRI) in Denver, CO. This provided a tie back between radioactive BSR testing and non-radioactive BSR, pilot scale, and engineering scale testing. Approximately six hundred grams of non-radioactive and radioactive BSR product were made for extensive testing and comparison to the non-radioactive pilot scale tests performed in 2004 at SAIC-STAR and the engineering scale test performed in 2008 at HRI with the Rassat simulant. The same mineral phases and off-gas species were found in the radioactive and non-radioactive testing. The granular ESTD and BSR products (radioactive and non-radioactive) were analyzed for to

Jantzen, C. M.; Crawford, C. L.; Bannochie, C. J.; Burket, P. R.; Cozzi, A. D.; Daniel, W. E.; Hall, H. K.; Miller, D. H.; Missimer, D. M.; Nash, C. A.; Williams, M. F.

2013-08-21T23:59:59.000Z

342

MHK Projects/NJBPU 1 5 MW Demonstration Program | Open Energy Information  

Open Energy Info (EERE)

NJBPU 1 5 MW Demonstration Program NJBPU 1 5 MW Demonstration Program < MHK Projects Jump to: navigation, search << Return to the MHK database homepage Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":5,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"500px","height":"350px","centre":false,"title":"","label":"","icon":"File:Aquamarine-marker.png","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[{"text":"","title":"","link":null,"lat":39.6032,"lon":-74.3401,"alt":0,"address":"","icon":"http:\/\/prod-http-80-800498448.us-east-1.elb.amazonaws.com\/w\/images\/7\/74\/Aquamarine-marker.png","group":"","inlineLabel":"","visitedicon":""}]}

343

MHK Projects/Evopod E35 35kW grid connected demonstrator | Open Energy  

Open Energy Info (EERE)

E35 35kW grid connected demonstrator E35 35kW grid connected demonstrator < MHK Projects Jump to: navigation, search << Return to the MHK database homepage Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":5,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"500px","height":"350px","centre":false,"title":"","label":"","icon":"File:Aquamarine-marker.png","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[{"text":"","title":"","link":null,"lat":55.3028,"lon":-5.59772,"alt":0,"address":"","icon":"http:\/\/prod-http-80-800498448.us-east-1.elb.amazonaws.com\/w\/images\/7\/74\/Aquamarine-marker.png","group":"","inlineLabel":"","visitedicon":""}]}

344

Heber geothermal binary demonstration project quarterly technical progress report, July 1, 1981--September 30, 1981  

DOE Green Energy (OSTI)

The purpose of this quarterly technical progress report is to document work completed on the nominal 65 Megawatt (Mwe gross) Heber Geothermal Binary Demonstration Project, located at Heber, California, during the period of July 1, 1981, through September 30, 1981. The work was performed by San Diego Gas and Electric Company under the support and cooperation of the US Department of Energy, the Electric Power Research Institute, the Imperial Irrigation District, the California Department of Water Resources, and the Southern California Edison Company. Topics covered in this quarterly report include progress made in the areas of Wells and Fluid production and Injection Systems, Power Plant Design and Construction, Power Plant Demonstration, and Data Acquisition and Dissemination.

Lacy, R.G.; Allen, R.F.; Alsup, R.A.; Liparidis, G.S.; Van De Mark, G.D.

1983-08-01T23:59:59.000Z

345

Heber geothermal binary demonstration project quarterly technical progress report, October 1, 1982--December 31, 1982  

DOE Green Energy (OSTI)

The purpose of this quarterly technical progress report is to document work completed on the nominal 65 Megawatt (Mwe gross) Heber Geothermal Binary Demonstration Project, located at Heber, California, during the period of October 1, 1982--December 31, 1982. The work was performed by San Diego Gas and Electric Company under the support and cooperation of the U.S. Department of Energy, the Electric Power Research Institute, the Imperial Irrigation District, the California Department of Water Resources, and the Southern California Edison Company. Topics covered in this quarterly report include progress made in the areas of Wells and Fluid Production and Injection Systems, Power Plant Design and Construction, Power Plant Demonstration, and Data Acquisition and Dissemination.

Lacy, R.G.; Allen, R.F.; Dixon, J.R.; Hsiao, W.P.; Liparidis, G.S.; Lombard, G.L.; Nelson, T.T.; Van De Mark, G.D.

1983-05-01T23:59:59.000Z

346

Heber geothermal binary demonstration project quarterly technical progress report, January 1, 1982--March 31, 1982  

DOE Green Energy (OSTI)

The purpose of this quarterly technical progress report is to document work completed on the nominal 65 Megawatt (Mwe gross) Heber Geothermal Binary Demonstration Project, located at Heber, California, during the period of January 1, 1982, through March 31, 1982. The work was performed by San Diego Gas and Electric Company under the support and cooperation of the U.S. Department of Energy, the Electric Power Research Institute, the Imperial Irrigation District, the California Department of Water Resources, and the Southern California Edison Company. Topics covered in this quarterly report include progress made in the areas of Wells and Fluid Production and Injection Systems, Power Plant Design and Construction, Power Plant Demonstration, and Data Acquisition and Dissemination.

Lacy, R.G.; Allen, R.F.; Alsup, R.A.; Liparidis, G.S.; Van De Mark, G.D.

1983-08-01T23:59:59.000Z

347

Heber geothermal binary demonstration project quarterly technical progress report, October 1, 1981--December 31, 1981  

DOE Green Energy (OSTI)

The purpose of this quarterly technical progress report is to document work completed on the nominal 65 Megawatt (Mwe gross) Heber Geothermal Binary Demonstration Project, located at Heber, California, during the period of October 1, 1981, through December 31, 1981. The work was performed by San Diego Gas and Electric Company under the support and cooperation of the U.S. Department of Energy, the Electric Power Research Institute, the Imperial Irrigation District, the California Department of Water Resources, and the Southern California Edison Company. Topics covered in this quarterly report include progress made in the areas of Wells and Fluid Production and Injection Systems, Power Plant Design and Construction, Power Plant Demonstration, and Data Acquisition and Dissemination.

Lacy, R.G.; Allen, R.F.; Alsup, R.A.; Liparidis, G.S.; Van De Mark, G.D.

1983-08-01T23:59:59.000Z

348

Heber geothermal binary demonstration project quarterly technical progress report, July 1, 1982--September 30, 1982  

DOE Green Energy (OSTI)

The purpose of this quarterly technical progress report is to document work completed on the nominal 65 Megawatt (Mwe gross) Heber Geothermal Binary Demonstration Project, located at Heber, California, during the period of July 1, 1982--September 30, 1982. The work was performed by San Diego Gas and Electric Company under the support and cooperation of the U.S. Department of Energy, the Electric Power Research Institute, the Imperial Irrigation District, the California Department of Water Resources, and the Southern California Edison Company. Topics covered in this quarterly report include progress made in the areas of Wells and Fluid Production and Injection Systems, Power Plant Design and Construction, Power Plant Demonstration, and Data Acquisition and Dissemination.

Lacy, R.G.; Allen, R.F.; Dixon, J.R.; Hsiao, W.P.; Liparidis, G.S.; Lombard, G.L.; Nelson, T.T.; Van De Mark, G.D.

1983-03-01T23:59:59.000Z

349

West Valley Demonstration Project Annual Site Environmental Report Calendar Year 2008  

SciTech Connect

Annual Site Environmental Report for the West Valley Demonstration Project (WVDP) for Calendar Year 2008. The report summarizes the calendar year (CY) 2008 environmental monitoring program data at the WVDP so as to describe the performance of the WVDPs environmental management system (EMS), confirm compliance with standards and regulations, and highlight important programs. Monitoring and surveillance of the facilities used by the DOE are conducted to verify protection of the environment, continual improvement, prevention and/or minimization of pollution, public outreach, and stakeholder involvement. In addition to demonstrating compliance with environmental regulations and directives, evaluation of data collected in 2008 continued to indicate that WVDP activities pose no threat to public health or safety, or to the environment.

West Valley Environmental Services LLC (WVES) and URS - Washington Division

2009-09-24T23:59:59.000Z

350

Heber geothermal binary demonstration project quarterly technical progress report, April 1, 1982--June 30, 1982  

DOE Green Energy (OSTI)

The purpose of this quarterly technical progress report is to document work completed on the nominal 65 Megawatt (Mwe gross) Heber Geothermal Binary Demonstration Project, located at Heber, California, during the period of April 1, 1982-June 30, 1982. The work was performed by San Diego Gas and Electric Company under the support and cooperation of the U.S. Department of Energy, the Electric Power Research Institute, the Imperial Irrigation District, the California Department of Water Resources, and the Southern California Edison Company. Topics covered in this quarterly report include progress made in the areas of Wells and Fluid Production and Injection Systems, Power Plant Design and Construction, Power Plant Demonstration, and Data Acquisition and Dissemination.

Lacy, R.G.; Allen, R.F.; Alsup, R.A.; Liparidis, G.S.; Van De Mark, G.D.

1983-08-01T23:59:59.000Z

351

MHK Projects/Evopod E1 1 10 scale grid connected demonstrator | Open Energy  

Open Energy Info (EERE)

Evopod E1 1 10 scale grid connected demonstrator Evopod E1 1 10 scale grid connected demonstrator < MHK Projects Jump to: navigation, search << Return to the MHK database homepage Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":5,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"500px","height":"350px","centre":false,"title":"","label":"","icon":"File:Aquamarine-marker.png","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[{"text":"","title":"","link":null,"lat":54.388,"lon":-5.566,"alt":0,"address":"","icon":"http:\/\/prod-http-80-800498448.us-east-1.elb.amazonaws.com\/w\/images\/7\/74\/Aquamarine-marker.png","group":"","inlineLabel":"","visitedicon":""}]}

352

MHK Projects/Minas Basin Bay of Fundy Commercial Scale Demonstration | Open  

Open Energy Info (EERE)

Minas Basin Bay of Fundy Commercial Scale Demonstration Minas Basin Bay of Fundy Commercial Scale Demonstration < MHK Projects Jump to: navigation, search << Return to the MHK database homepage Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":5,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"500px","height":"350px","centre":false,"title":"","label":"","icon":"File:Aquamarine-marker.png","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[{"text":"","title":"","link":null,"lat":45.3658,"lon":-64.4294,"alt":0,"address":"","icon":"http:\/\/prod-http-80-800498448.us-east-1.elb.amazonaws.com\/w\/images\/7\/74\/Aquamarine-marker.png","group":"","inlineLabel":"","visitedicon":""}]}

353

AFBC (atmospheric fluidized-bed combustion) conversion at Northern States Power Company: Volume 1, Project origins: Final report  

SciTech Connect

This is the first volume in a series of four reports detailing the conversion of Northern States Power Company's (NSP) Black Dog unit 2 from pulverized-coal firing to atmospheric fluidized-bed combustion (AFBC). This particular report describes the important events and decisions that led to NSP's selection of its Black Dog unit 2 for conversion to AFBC, and it provides an overview of AFBC technology and a discussion of the AFBC conversion market. The purpose of these reports is to disseminate the information gathered during the Black Dog AFBC Conversion Project to utilities evaluating the technical feasibility and cost effectiveness of converting units within their systems from pulverized-coal firing to AFBC. To this end, each volume in this series of reports presents material about a different aspect of the Black Dog project. Volume 2 - Unit Design describes the design of the new AFBC system and the important decisions that led to its final configuration; Volume 3 - Unit Demolition describes the major activities that occurred during the demolition and relocation phase; and Volume 4 - Unit Construction describes the major activities that occurred during the construction phase of the project. 17 refs., 9 figs., 12 tabs.

deBrun Duffy, J.; Hinrichsen, D.

1987-11-01T23:59:59.000Z

354

Western Greenbrier Co-Production Demonstration Project Draft Environmental Impact Statement  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Figure S-1. Figure S-1. General Location Map U.S. Department of Energy National Energy Technology Lab Western Greenbrier Co-Production Demonstration Project DEIS November 2006 WV 20 S 12 S 63 WV 39 Proposed Co- Production Facility Anjean and Joe Knob Coal Refuse Piles U S 6 0 U S 6 0 US 219 WV 20 WV 39 AN1 AN2 AN3 DN1 DN2 GV W V 2 0 U S 6 0 C R 1 Figure 1-1. General Location Map U.S. Department of Energy National Energy Technology Lab Western Greenbrier Co-Production Demonstration Project DEIS November 2006 WV 20 S 12 S 63 WV 39 Proposed Co- Production Facility Anjean and Joe Knob Coal Refuse Piles U S 6 0 U S 6 0 US 219 WV 20 WV 39 AN1 AN2 AN3 DN1 DN2 GV W V 2 0 U S 6 0 C R 1 S 63 Rainelle Anjean Quinwood Charmco Lewisburg Savannah Quarry Greystone Quarry Boxley Quarry Anjean and Joe Knob Coal Refuse Piles Green Valley Coal Refuse Pile

355

Solar hot water demonstration project at Red Star Industrial Laundry, Fresno, California  

SciTech Connect

The Final Report of the Solar Hot Water System located at the Red Star Industrial Laundry, 3333 Sabre Avenue, Fresno, California, is presented. The system was designed as an integrated wastewater heat recovery and solar preheating system to supply a part of the hot water requirements. It was estimated that the natural gas demand for hot water heating could be reduced by 56 percent (44 percent heat reclamation and 12 percent solar). The system consists of a 16,500 gallon tube-and-shell wastewater heat recovery subsystem combined with a pass-through 6,528 square foot flat plate Ying Manufacturing Company Model SP4120 solar collector subsystem, a 12,500 gallon fiber glass water storage tank subsystem, pumps, heat exchangers, controls, and associated plumbing. The design output of the solar subsystem is approximately 2.6 x 10/sup 9/ Btu/year. Auxiliary energy is provided by a gas fired low pressure boiler servicing a 4,000 gallon service tank. This project is part of the US Department of Energy's Solar Demonstration Program with DOE sharing $184,841 of the $260,693 construction cost. The system was turned on in July 1977, and acceptance tests completed in September 1977. The demonstration period for this project ends September 2, 1982.

1980-07-01T23:59:59.000Z

356

Over the energy edge: Results from a seven year new commercial buildings research and demonstration project  

SciTech Connect

Edge was a research oriented demonstration project that began in 1985. Twenty-eight commercial buildings were designed and constructed to use 30% less electricity than a hypothetical simulated baseline building. Average savings from the 18 buildings evaluated with post-occupancy, ``tuned`` simulation models were less, at 17%. The cost-effectiveness of the energy-efficiency measures at six of the 18 projects met the target cost-of-conserved (CCE) energy of 5.6cent/kWh for the total package of measures. The most important reason energy savings were not as great as predicted is that the actual, installed energy-efficiency measures and building characteristics changed from the design assumptions. The cost effectiveness of the measures would have been greater if the baseline was common practice rather than assumptions based on the regional building code. For example, the Energy Edge small offices use about 30% to 50% less energy than comparable new buildings. Savings also would have been greater if commissioning had been included within the program. Future projects should consider lower-cost ``hands-on`` evaluation techniques that provide direct feedback on measure performance based on functional and diagnostic testing, with annual check-ups to ensure persistence of savings.

Piette, M.A.; Nordman, B.; deBuen, O.; Diamond, R. [Lawrence Berkeley Lab., CA (United States); Codey, B. [Bonneville Power Administration, Portland, OR (United States)

1994-08-01T23:59:59.000Z

357

An evaluation of the Big Muddy Field low-tension flood demonstration project  

SciTech Connect

A commercial scale low-tension flood (micellar-polymer) demonstration project was conducted in the Second Wall Creek Reservoir in the Big Muddy Field in east central Wyoming. The cost-shared, low-tension flood used a 0.1 pore volume preflush and a 0.1 pore volume low-tension slug followed by a polymer drive bank. The sulfonate used in the low-tension slug was a blend of both low and high molecular weight synthetic sulfonates. Dow Pusher 500, a dry polyacrylamide polymer, was used in both the low-tension slug and polymer drive bank for mobility control. Although project oil recovery was or will be significantly less than originally predicted, the low-tension process successfully mobilized waterflood residual oil. The primary factor contributing to lower than anticipated recovery was lack of containment of the injected fluids in the reservoir. Behind-pipe communication in abandoned or reconditioned wellbores in the project area represented the most probable source of fluid migration from the reservoir. Fluid entry from other reservoirs occurred concurrently with migration of the fluids from the reservoir. Fluid containment deteriorated significantly when injection pressures during the polymer injection period were allowed to exceed the formation parting pressure. Injectivity in the relatively low permeability reservoir was a continuing operational problem. 6 refs., 78 figs., 19 tabs.

Cole, E.L.

1988-12-01T23:59:59.000Z

358

Introduction to the U.S. Department of Energy's Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project  

DOE Green Energy (OSTI)

Early in 2003, the U.S. Department of Energy (DOE) initiated the ''Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project'' solicitation. The purpose of this project is to examine the impact and performance of fuel cell vehicles and the requisite hydrogen infrastructure in real-world applications. The integrated nature of the project enables DOE to work with industry to test, demonstrate, and validate optimal system solutions. Information learned from the vehicles and infrastructure will be fed back into DOE's R&D program to guide and refocus future research as needed, making this project truly a ''learning demonstration''.

Wipke, K.; Welch, C.; Gronich, S.; Garbak, J.; Hooker, D.

2006-05-01T23:59:59.000Z

359

Kentucky Pioneer Integrated Gasification Combined Cycle Demonstration Project Draft Environmental Impact Statement  

DOE Green Energy (OSTI)

The Kentucky Pioneer IGCC Demonstration Project DEIS assesses the potential environmental impacts that would result from a proposed DOE action to provide cost-shared financial support for construction and operation of an electrical power station demonstrating use of a Clean Coal Technology in Clark County, Kentucky. Under the Proposed Action, DOE would provide financial assistance, through a Cooperative Agreement with Kentucky Pioneer Energy, LLC, for design, construction, and operation of a 540 megawatt demonstration power station comprised of two synthesis gas-fired combined cycle units in Clark County, Kentucky. The station would also be comprised of a British Gas Lurgi (BGL) gasifier to produce synthesis gas from a co-feed of coal and refuse-derived fuel pellets and a high temperature molten carbonate fuel cell. The facility would be powered by the synthesis gas feed. The proposed project would consist of the following major components: (1) refuse-derived fuel pellets and coal receipt and storage facilities; (2) a gasification plant; (3) sulfur removal and recovery facilities; (4) an air separation plant; (5) a high-temperature molten carbonate fuel cell; and (6) two combined cycle generation units. The IGCC facility would be built to provide needed power capacity to central and eastern Kentucky. At a minimum, 50 percent of the high sulfur coal used would be from the Kentucky region. Two No Action Alternatives are analyzed in the DEIS. Under the No Action Alternative 1, DOE would not provide cost-shared funding for construction and operation of the proposed facility and no new facility would be built. Under the No Action Alternative 2, DOE would not provide any funding and, instead of the proposed demonstration project, Kentucky Pioneer Energy, LLC, a subsidiary of Global Energy, Inc., would construct and operate, a 540 megawatt natural gas-fired power station. Evaluation of impacts on land use, socioeconomics, cultural resources, aesthetic and scenic resources, geology, air resources, water resources, ecological resources, noise, traffic and transportation, occupational and public health and safety, and environmental justice were included in the assessment.

N /A

2001-11-16T23:59:59.000Z

360

NETL: Clean Coal Technology Demonstration Program (CCTDP) - Round 3  

NLE Websites -- All DOE Office Websites (Extended Search)

3 3 Advanced Electric Power Generation - Fluidized Bed Combustion McIntosh Unit 4A PCFB Demonstration Project - Project Brief [PDF-186KB] Lakeland Department of Electric & Water, Lakeland, FL PROGRAM PUBLICATIONS Annual/Quarterly Technical Reports Pressurized Circulating Fluidized Bed (PCFB) Repowering Project, Annual Report, January - December 1993 (Apr 1994) -- Not Available Pressurized Circulating Fluidized Bed (PCFB) Repowering Project, Annual Report, August 1991 - December 1992 (Apr 1993) -- Not Available Interim Reports Karhula Hot Gas Cleanup Test Results (June 1994) -- Not Available PCFB Repowering Project 80 MW Plant Description (May 1994) -- Not Available Comprehensive Report to Congress Comprehensive Report to Congress on the Clean Coal Technology Progam: Pressurized Circulating Fluidized Bed Demonstration Project (June 1991) -- Not Available

Note: This page contains sample records for the topic "bed demonstration project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


361

Kentucky Pioneer Integrated Gasification Combined Cycle Demonstration Project Final Environmental Impact Statement  

Science Conference Proceedings (OSTI)

The abundance of coal in the United States makes it one of our Nation's most important strategic resources in building a secure energy future. With today's prices and technology, recoverable reserves located in the United States could supply the Nation's coal consumption for approximately 250 years at current usage rates. However, if coal is to reach its full potential as an environmentally acceptable source of energy, an expanded menu of advanced clean coal technologies must be developed to provide substantially improved options both for the consumer and private industry. Before any technology can be seriously considered for commercialization, it must be demonstrated at a sufficiently large-scale to develop industry confidence in its technical and economic feasibility. The implementation of a federal technology demonstration program is the established means of accelerating the development of technology to meet national energy strategy and environmental policy goals, to reduce the risk to human health and the environment to an acceptable level, to accelerate commercialization, and to provide the incentives required for continued activity in research and development directed at providing solutions to long-range energy problems. The U.S. Department of Energy (DOE) prepared this environmental impact statement (EIS) on the proposed Kentucky Pioneer Integrated Gasification Combined Cycle (IGCC) Demonstration Project in compliance with the National Environmental Policy Act (NEPA).

N /A

2002-12-13T23:59:59.000Z

362

Separation projects within the US Department of Energy`s Underground Storage Tank: Integrated Demonstration  

SciTech Connect

The greatest challenge facing the US Department of Energy is the remediation of the 1 {times} 10{sup 8} gal of high-level and low-level radioactive waste in the underground storage tanks (USTs) at its Hanford, Savannah River, Oak Ridge, Idaho, and Fernald sites. With current technologies, this remediation will cost at least 100 billion dollars. In an effort to reduce costs, improve safety, and minimize delays, the Underground Storage Tank--Integrated Demonstration was created for demonstration, testing, and evaluation (DT&E) of promising new technologies that can be used for UST remediation. These demonstrations, which are typically at the pilot-plant scale, will determine which processes will be used in the full-scale remediation of the USTs. These DT&E studies are performed by the Characterization and Waste Retrieval Program or by the Waste Processing and Disposal Program (WPDP). This paper presents the technical progress and future plans of the WPDP projects. The 11 WPDP programs in FY 1993 focused on three problem areas, which involve the treatment of supernate, the treatment of sludge, and nitrate destruction and subsequent waste forms. In addition, a planned Request for Expression of Interest on organic destruction techniques from private industries and universities and the WPDP`s future direction and programmatic issues are discussed.

McGinnis, C.P.; Hunt, R.D. [Oak Ridge National Lab., TN (United States); Gibson, S.M. [USDOE, Germantown, MD (United States); Gilchrist, R.L. [Westinghouse Hanford Co., Richland, WA (United States)

1993-12-01T23:59:59.000Z

363

Ultra-clean Fischer-Tropsch (F-T) Fuels Production and Demonstration Project  

DOE Green Energy (OSTI)

The objective of the DOE-NETL Fischer-Tropsch (F-T) Production and Demonstration Program was to produce and evaluate F-T fuel derived from domestic natural gas. The project had two primary phases: (1) fuel production of ultra-clean diesel transportation fuels from domestic fossil resources; and (2) demonstration and performance testing of these fuels in engines. The project also included a well-to-wheels economic analysis and a feasibility study of small-footprint F-T plants (SFPs) for remote locations such as rural Alaska. During the fuel production phase, ICRC partnered and cost-shared with Syntroleum Corporation to complete the mechanical design, construction, and operation of a modular SFP that converts natural gas, via F-T and hydro-processing reactions, into hydrogensaturated diesel fuel. Construction of the Tulsa, Oklahoma plant started in August 2002 and culminated in the production of over 100,000 gallons of F-T diesel fuel (S-2) through 2004, specifically for this project. That fuel formed the basis of extensive demonstrations and evaluations that followed. The ultra-clean F-T fuels produced had virtually no sulfur (less than 1 ppm) and were of the highest quality in terms of ignition quality, saturation content, backend volatility, etc. Lubricity concerns were investigated to verify that commercially available lubricity additive treatment would be adequate to protect fuel injection system components. In the fuel demonstration and testing phase, two separate bus fleets were utilized. The Washington DC Metropolitan Area Transit Authority (WMATA) and Denali National Park bus fleets were used because they represented nearly opposite ends of several spectra, including: climate, topography, engine load factor, mean distance between stops, and composition of normally used conventional diesel fuel. Fuel evaluations in addition to bus fleet demonstrations included: bus fleet emission measurements; F-T fuel cold weather performance; controlled engine dynamometer lab evaluation; cold-start test-cell evaluations; overall feasibility, economics, and efficiency of SFP fuel production; and an economic analysis. Two unexpected issues that arose during the project were further studied and resolved: variations in NOx emissions were accounted for and fuel-injection nozzle fouling issues were traced to the non-combustible (ash) content of the engine oil, not the F-T fuel. The F-T fuel domestically produced and evaluated in this effort appears to be a good replacement candidate for petroleum-based transportation fuels. However, in order for domestic F-T fuels to become a viable cost-comparable alternative to petroleum fuels, the F-T fuels will need to be produced from abundant U.S. domestic resources such as coal and biomass, rather than stranded natural gas.

Stephen P. Bergin

2006-06-30T23:59:59.000Z

364

Kentucky Pioneer Integrated Gasification Combined Cycle Demonstration Project, Final Environmental Impact Statement  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

S-1 S-1 SUMMARY The U.S. Department of Energy (DOE) prepared this environmental impact statement (EIS) on the proposed Kentucky Pioneer Integrated Gasification Combined Cycle (IGCC) Demonstration Project in compliance with the National Environmental Policy Act (NEPA). The National Environmental Policy Act Process NEPA is a federal law that serves as the basic national charter for protection of the environment. For major federal actions that may significantly affect the quality of the environment, NEPA requires federal agencies to prepare a detailed statement that includes the potential environmental impacts of the Proposed Action and reasonable alternatives. A fundamental objective of NEPA is to foster better decisionmaking by ensuring that high quality environmental information is available to public officials and members of the

365

Kentucky Pioneer Integrated Gasification Combined Cycle Demonstration Project, Final Environmental Impact Statement  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Comments Comments Kentucky Pioneer IGCC Demonstration Project Final Environmental Impact Statement Clark County Public Library Winchester, KY Page 1 of 5 D-1 Comment No. 1 Issue Code: 11 Gasification is different from incineration. It is a better, more environmentally responsible approach to generating energy from the use of fossil fuels and refuse derived fuel (RDF). Incineration produces criteria pollutants, semi-volatile and volatile organic compounds and dioxin/furan compounds. Ash from hazardous waste incinerators is considered a hazardous waste under the Resource Conservation and Recovery Act (RCRA). In contrast, gasification, which occurs at high temperatures and pressures, produces no air emissions, only small amounts of wastewater containing salts. Synthesis gas (syngas)

366

Blast Furnace Granulated Coal Injection System Demonstration Project: A DOE Assessment  

NLE Websites -- All DOE Office Websites (Extended Search)

2 2 Blast Furnace Granulated Coal Injection System Demonstration Project: A DOE Assessment June 2000 U. S. Department of Energy National Energy Technology Laboratory P.O. Box 880, 3610 Collins Ferry Road Morgantown, WV 26507-0880 and P.O. Box 10940, 626 Cochrans Mill Road Pittsburgh, PA 15236-0940 2 Disclaimer This report was prepared as an account of work sponsored by an agency of the United States Government. Neither the United States Government nor any agency thereof, nor any of their employees, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights. Reference therein

367

Solar heating and cooling demonstration project at the Florida Solar Energy Center  

DOE Green Energy (OSTI)

The retrofitted solar heating and cooling system installed at the Florida Solar Energy Center is described. Information is provided on the system's test, operation, controls, hardware and installation, including detailed drawings. The Center's office building, approximately 5000 square feet of space, with solar air conditioning and heating as a demonstration of the technical feasibility is located just north of Port Canaveral, Florida. The system was designed to supply approximately 70% of the annual cooling and 100% of the heating load. The project provides unique high-temperature, non-imaging, non-tracking, evacuated-tube collectors. The design of the system was kept simple and employs five hydronic loops. They are energy collection, chilled water production, space cooling, space heating and energy rejection.

Hankins, J.D.

1980-02-01T23:59:59.000Z

368

Northview Junior High solar energy demonstration project. Final report, 16 May 1974--16 May 1975  

DOE Green Energy (OSTI)

This report covers a one-year test and evaluation of the Northview Junior High School Solar Energy Demonstration Project. The system provided about 5 percent of the school's energy requirements for the year. This energy was used for space heating, domestic water heating, and pool water heating for a total of 629,000,000 solar supplied Btu's. Average collector efficiency for the year was 44 percent. Operating costs were less than 5 percent of the value of the collected energy. Solar insolation data and system performance data are presented for the various operating modes. Results and conclusions indicate that the supplemental heating of large-scale buildings is feasible and economical. An optimum performance requires a careful matching of load, collectors, and distribution system.

Merrill, G.; Dib, A.

1976-05-01T23:59:59.000Z

369

Operating experience during high-level waste vitrification at the West Valley Demonstration Project  

SciTech Connect

This report provides a summary of operational experiences, component and system performance, and lessons learned associated with the operation of the Vitrification Facility (VF) at the West Valley Demonstration Project (WVDP). The VF was designed to convert stored high-level radioactive waste (HLW) into a stable waste form (borosilicate glass) suitable for disposal in a federal repository. Following successful completion on nonradioactive test, HLW processing began in July 1995. Completion of Phase 1 of HLW processing was reached on 10 June 1998 and represented the processing of 9.32 million curies of cesium-137 (Cs-137) and strontium-90 (Sr-90) to fill 211 canisters with over 436,000 kilograms of glass. With approximately 85% of the total estimated curie content removed from underground waste storage tanks during Phase 1, subsequent operations will focus on removal of tank heel wastes.

Valenti, P.J.; Elliott, D.I.

1999-01-01T23:59:59.000Z

370

Northview Junior High solar energy demonstration project. Final report, 16 May 1974--16 May 1975  

SciTech Connect

This report covers a one-year test and evaluation of the Northview Junior High School Solar Energy Demonstration Project. The system provided about 5 percent of the school's energy requirements for the year. This energy was used for space heating, domestic water heating, and pool water heating for a total of 629,000,000 solar supplied Btu's. Average collector efficiency for the year was 44 percent. Operating costs were less than 5 percent of the value of the collected energy. Solar insolation data and system performance data are presented for the various operating modes. Results and conclusions indicate that the supplemental heating of large-scale buildings is feasible and economical. An optimum performance requires a careful matching of load, collectors, and distribution system.

Merrill, G.; Dib, A.

1976-05-01T23:59:59.000Z

371

Electric G-Van demonstration and commercial assessment project. Final report  

DOE Green Energy (OSTI)

The Electric Power Research Institute was awarded this grant to continue the joint effort initiated by EPRI, and VE International to proceed beyond the prototype phase of the electric G-Van development. The goal of EPRI and VEHMA was to develop a market for the electric G-Van, and to distribute them to commercial fleet operators. The objective of this project was to produce G-Vans in a production facility that would be comparable to the GMC Truck internal combustion engine Vandura Van produced by General Motors in quality, reliability, durability and safety. An initial market assessment/demonstration phase of sixty (60) vehicles was to be undertaken, with the ability to expand production volume quickly to meet market demands. Brief description of each task of this grant is given and the actions taken by EPRI to complete them.

Braga, B.D. [Electric Power Research Inst., Palo Alto, CA (United States)] [Electric Power Research Inst., Palo Alto, CA (United States)

1992-12-01T23:59:59.000Z

372

Home energy saver's program: a report on a demonstration project undertaken in Utah  

SciTech Connect

A demonstration project undertaken in Utah designed to test a Home Energy Saver Program (funded by the Federal Energy Administration) is described. The basic purposes of the program were: (1) to encourage and bring about a significant reduction in home energy use, and (2) to test the impact of various energy conservation research elements on homeowners' participation. The principal research elements tested were: direct mailing of HESP workbooks to single family homeowners; use of a telephone hotline; use of workshops; use of a coordinated media program; and use of church and community support. In addition, the impact of a contest drawing, designed to motivate homeowners to compute their potential annual energy savings, was tested. (MCW)

Jensen, G.F.

1977-06-01T23:59:59.000Z

373

Clean Coal Demonstration Projects -- Operation Experience and Risk Assessment Through September 1997, Interim Report  

Science Conference Proceedings (OSTI)

Clean coal technologies such as Integrated Gasification Combined Cycle and Pressurized Fluidized Bed Combustion can meet stringent emission standards and achieve high plant efficiencies. Commercial and near-commercial sized plants using these technologies have accumulated several years of operational experience and are serious candidates for new coal-based power plants.

1997-12-23T23:59:59.000Z

374

Clean Coal Technology Demonstration Projects -- Operating Experience and Risk Assessment Through September 1998  

Science Conference Proceedings (OSTI)

Clean coal technologies such as Integrated Gasification Combined Cycle (IGCC) and Pressurized Fluidized Bed Combustion (PFBC) can meet stringent emission standards and achieve high efficiencies. Commercial and near-commercial sized plants using these technologies have accumulated several years of operational experience and are serious candidates for new coal-based power plants.

1998-12-18T23:59:59.000Z

375

ULTRA-CLEAN FISCHER-TROPSCH FUELS PRODUCTION AND DEMONSTRATION PROJECT  

DOE Green Energy (OSTI)

The Syntroleum plant is mechanically complete and currently undergoing start-up. The fuel production and demonstration plan is near completion. The study on the impact of small footprint plant (SFP) fuel on engine performance is about half-completed. Cold start testing has been completed. Preparations have been completed for testing the fuel in diesel electric generators in Alaska. Preparations are in progress for testing the fuel in bus fleets at Denali National Park and the Washington Metropolitan Transit Authority. The experiments and analyses conducted during this project show that Fischer-Tropsch (FT) gas-to-liquid diesel fuel can easily be used in a diesel engine with little to no modifications. Additionally, based on the results and discussion presented, further improvements in performance and emissions can be realized by configuring the engine to take advantage of FT diesel fuel's properties. The FT fuel also shows excellent cold start properties and enabled the engine tested to start at more the ten degrees than traditional fuels would allow. This plant produced through this project will produce large amounts of FT fuel. This will allow the fuel to be tested extensively, in current, prototype, and advanced diesel engines. The fuel may also contribute to the nation's energy security. The military has expressed interest in testing the fuel in aircraft and ground vehicles.

Steve Bergin

2003-10-17T23:59:59.000Z

376

Fermilab Project X nuclear energy application: Accelerator, spallation target and transmutation technology demonstration  

SciTech Connect

The recent paper 'Accelerator and Target Technology for Accelerator Driven Transmutation and Energy Production' and report 'Accelerators for America's Future' have endorsed the idea that the next generation particle accelerators would enable technological breakthrough needed for nuclear energy applications, including transmutation of waste. In the Fall of 2009 Fermilab sponsored a workshop on Application of High Intensity Proton Accelerators to explore in detail the use of the Superconducting Radio Frequency (SRF) accelerator technology for Nuclear Energy Applications. High intensity Continuous Wave (CW) beam from the Superconducting Radio Frequency (SRF) Linac (Project-X) at beam energy between 1-2 GeV will provide an unprecedented experimental and demonstration facility in the United States for much needed nuclear energy Research and Development. We propose to carry out an experimental program to demonstrate the reliability of the accelerator technology, Lead-Bismuth spallation target technology and a transmutation experiment of spent nuclear fuel. We also suggest that this facility could be used for other Nuclear Energy applications.

Gohar, Yousry; /Argonne; Johnson, David; Johnson, Todd; Mishra, Shekhar; /Fermilab

2011-04-01T23:59:59.000Z

377

California Food Processing Industry Wastewater Demonstration Project: Phase I Final Report  

E-Print Network (OSTI)

Food and Drug Administration Green Energy Management Systemthe project team used Green Energy Management System (GEMS)the project team used Green Energy Management System (GEMS)

Lewis, Glen

2010-01-01T23:59:59.000Z

378

Environmental Assessment for the Decontamination, Demolition, and Removal of Certain Facilities at the West Valley Demonstration Project  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

52 52 Environmental Assessment for the Decontamination, Demolition, and Removal of Certain Facilities at the West Valley Demonstration Project Final U.S. Department of Energy West Valley Demonstration Project West Valley, New York September 14, 2006 Final EA - Decontamination, Demolition, and Removal of Certain Facilities at WVDP i Table of Contents CHAPTER 1 INTRODUCTION AND PURPOSE AND NEED FOR AGENCY ACTION................ 1 1.1 Overview....................................................................................................................... 1 1.2 West Valley Demonstration Project.............................................................................. 2 1.3 Purpose and Need for Agency Action ..........................................................................

379

Baker-Barry Tunnel Lighting: Evaluation of a Potential GATEWAY Demonstrations Project  

SciTech Connect

The U.S. Department of Energy is evaluating the Baker-Barry Tunnel as a potential GATEWAY Demonstrations project for deployment of solid-state lighting (SSL) technology. The National Park Service views this project as a possible proving ground and template for implementation of light-emitting diode (LED) luminaires in other tunnels, thereby expanding the estimated 40% energy savings from 132 MWh/yr to a much larger figure nationally. Most of the energy savings in this application is attributable to the instant-restrike capability of LED products and to their high tolerance for frequent on/off switching, used here to separately control either end of the tunnel during daytime hours. Some LED luminaires rival or outperform their high-intensity discharge (HID) counterparts in terms of efficacy, but options are limited, and smaller lumen packages preclude true one-for-one equivalence. However, LED products continue to improve in efficacy and affordability at a rate unmatched by other light source technologies; the estimated simple payback period of eight years (excluding installation costs and maintenance savings) can be expected to improve with time. The proposed revisions to the existing high-pressure sodium (HPS) lighting system would require slightly increased controls complexity and significantly increased luminaire types and quantities. In exchange, substantial annual savings (from reduced maintenance and energy use) would be complemented by improved quantity and quality of illumination. Although advanced lighting controls could offer additional savings, it is unclear whether such a system would prove cost-effective; this topic may be explored in future work.

Tuenge, Jason R.

2011-06-28T23:59:59.000Z

380

The Impact of Advanced Nowcasting Systems on Severe Weather Warning during the Sydney 2000 Forecast Demonstration Project: 3 November 2000  

Science Conference Proceedings (OSTI)

One of the principal aims of the Sydney 2000 Forecast Demonstration Project was to assess the utility of advanced nowcasting systems to operational severe weather forecasters. This paper describes the application of the products of a variety of ...

Neil I. Fox; Rob Webb; John Bally; Michael W. Sleigh; Clive E. Pierce; David M. L. Sills; Paul I. Joe; James Wilson; Chris G. Collier

2004-02-01T23:59:59.000Z

Note: This page contains sample records for the topic "bed demonstration project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


381

Introduction to the U.S. Department of Energy's Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project  

DOE Green Energy (OSTI)

This presentation, which provides information on the U.S. Department of Energy's Controlled Hydrogen Fleet and Infrastructure Demonstration and Validation Project, was given at EVS-21 in April 2005.;

Wipke, K.; Welch, C.; Thomas, H.; Gronich, S.; Garbak, J.; Hooker, D.

2005-04-01T23:59:59.000Z

382

Clean Coal Technology Demonstration Program: Project fact sheets 2000, status as of June 30, 2000  

SciTech Connect

The Clean Coal Technology Demonstration Program (CCT Program), a model of government and industry cooperation, responds to the Department of Energy's (DOE) mission to foster a secure and reliable energy system that is environmentally and economically sustainable. The CCT Program represents an investment of over $5.2 billion in advanced coal-based technology, with industry and state governments providing an unprecedented 66 percent of the funding. With 26 of the 38 active projects having completed operations, the CCT Program has yielded clean coal technologies (CCTs) that are capable of meeting existing and emerging environmental regulations and competing in a deregulated electric power marketplace. The CCT Program is providing a portfolio of technologies that will assure that U.S. recoverable coal reserves of 274 billion tons can continue to supply the nation's energy needs economically and in an environmentally sound manner. As the nation embarks on a new millennium, many of the clean coal technologies have realized commercial application. Industry stands ready to respond to the energy and environmental demands of the 21st century, both domestically and internationally, For existing power plants, there are cost-effective environmental control devices to control sulfur dioxide (S02), nitrogen oxides (NO,), and particulate matter (PM). Also ready is a new generation of technologies that can produce electricity and other commodities, such as steam and synthetic gas, and provide efficiencies and environmental performance responsive to global climate change concerns. The CCT Program took a pollution prevention approach as well, demonstrating technologies that remove pollutants or their precursors from coal-based fuels before combustion. Finally, new technologies were introduced into the major coal-based industries, such as steel production, to enhance environmental performance. Thanks in part to the CCT Program, coal--abundant, secure, and economical--can continue in its role as a key component in the U.S. and world energy markets. The CCT Program also has global importance in providing clean, efficient coal-based technology to a burgeoning energy market in developing countries largely dependent on coal. Based on 1997 data, world energy consumption is expected to increase 60 percent by 2020, with almost half of the energy increment occurring in developing Asia (including China and India). By 2020, energy consumption in developing Asia is projected to surpass consumption in North America. The energy form contributing most to the growth is electricity, as developing Asia establishes its energy infrastructure. Coal, the predominant indigenous fuel, in that region will be the fuel of choice in electricity production. The CCTs offer a means to mitigate potential environmental problems associated with unprecedented energy growth, and to enhance the U.S. economy through foreign equipment sales and engineering services.

NONE

2000-09-01T23:59:59.000Z

383

West Valley Demonstration Project vitrification process equipment Functional and Checkout Testing of Systems (FACTS)  

Science Conference Proceedings (OSTI)

The Vitrification Facility (VF) at the West Valley Demonstration Project was designed to convert stored radioactive waste into a stable glass for disposal in a federal repository. The Functional and Checkout Testing of Systems (FACTS) program was conducted from 1984 to 1989. During this time new equipment and processes were developed, installed, and implemented. Thirty-seven FACTS tests were conducted, and approximately 150,000 kg of glass were made by using nonradioactive materials to simulate the radioactive waste. By contrast, the planned radioactive operation is expected to produce approximately 500,000 kg of glass. The FACTS program demonstrated the effectiveness of equipment and procedures in the vitrification system, and the ability of the VF to produce quality glass on schedule. FACTS testing also provided data to validate the WVNS waste glass qualification method and verify that the product glass would meet federal repository acceptance requirements. The system was built and performed to standards which would have enabled it to be used in radioactive service. As a result, much of the VF tested, such as the civil construction, feed mixing and holding vessels, and the off-gas scrubber, will be converted for radioactive operation. The melter was still in good condition after being at temperature for fifty-eight of the sixty months of FACTS. However, the melter exceeded its recommended design life and will be replaced with a similar melter. Components that were not designed for remote operation and maintenance will be replaced with remote-use items. The FACTS testing was accomplished with no significant worker injury or environmental releases. During the last FACTS run, the VF processes approximated the remote-handling system that will be used in radioactive operations. Following this run the VF was disassembled for conversion to a radioactive process. Functional and checkout testing of new components will be performed prior to radioactive operation.

Carl, D.E.; Paul, J.; Foran, J.M.; Brooks, R.

1990-09-30T23:59:59.000Z

384

Baca Geothermal Demonstration project legal and regulatory challenges. First semi-annual report for period through June 30, 1980  

DOE Green Energy (OSTI)

The Legal and Regulatory Constraints Reports identify and describe the major legal and institutional constraints associated with the Baca Geothermal Demonstration Project. The impacts of these constraints on the Project in terms of cost, schedule, and technical design are also analyzed. The purpose of these reports is to provide a guide for future geothermal development.

Province, S.G.; Walter, K.M.; Miller, J.

1980-12-01T23:59:59.000Z

385

Small-Scale Hydroelectric Power Demonstration Project. Pennsylvania Hydroelectric Development Corporation Flat Rock Dam: Project summary report  

DOE Green Energy (OSTI)

The US Department of Energy Field Office, Idaho, Small-Scale Hydroelectric Power Program was initiated in conjunction with the restoration of three power generating plants in Idaho Falls, Idaho, following damage caused by the Teton Dam failure on June 5, 1976. There were many parties interested in this project, including the state and environmental groups, with different concerns. This report was prepared by the developer and describes the design alternatives the applicant provided in an attempt to secure the Federal Energy Regulatory Commission license. Also included are correspondence between the related parties concerning the project, major design alternatives/project plan diagrams, the license, and energy and project economics.

Gleeson, L.

1991-12-01T23:59:59.000Z

386

Toms Creek integrated gasification combined cycle demonstration project. Quarterly report, July 1--September 30, 1993  

SciTech Connect

The use of an upgraded version of General Electric`s Frame 6 gas turbine, which has been designated as Frame 6 (FA) will make a significant improvement to the thermal efficiency and overall economics of the Toms Creek Project. Replacing the smaller, less efficient Frame 6 (B) gas turbine with the new Frame 6 (FA) will increase the net power production from a nominal 55 MW to 105 MW. The coal feed rate will correspondingly increase from 430 tpd to 740 tpd. All process flows and equipment sizes will be increased accordingly. Selected process parameters for the original and revised Toms Creek IGCC plant configurations are compared in Table 2. There is an approximately 10% increase in net plant efficiency for the revised configuration. Using this increased plant size, the pressure vessels become larger due to an increased through-put, but are still dimensioned for shop fabrication and over-the-road shipment. The preliminary cost estimate for the enlarged demonstration plant was prepared by factoring the estimates for the original plant. Revised quotes for the larger equipment will be solicited and used to generate more accurate cost information for the revised plant.

Feher, G.

1993-11-30T23:59:59.000Z

387

A COMPLETE HISTORY OF THE HIGH-LEVEL WASTE PLANT AT THE WEST VALLEY DEMONSTRATION PROJECT  

SciTech Connect

The West Valley Demonstration Project (WVDP) vitrification melter was shut down in September 2002 after being used to vitrify High Level Waste (HLW) and process system residuals for six years. Processing of the HLW occurred from June 1996 through November 2001, followed by a program to flush the remaining HLW through to the melter. Glass removal and shutdown followed. The facility and process equipment is currently in a standby mode awaiting deactivation. During HLW processing operations, nearly 24 million curies of radioactive material were vitrified into 275 canisters of HLW glass. At least 99.7% of the curies in the HLW tanks at the WVDP were vitrified using the melter. Each canister of HLW holds approximately 2000 kilograms of glass with an average contact dose rate of over 2600 rem per hour. After vitrification processing ended, two more cans were filled using the Evacuated Canister Process to empty the melter at shutdown. This history briefly summarizes the initial stages of process development and earlier WVDP experience in the design and operation of the vitrification systems, followed by a more detailed discussion of equipment availability and failure rates during six years of operation. Lessons learned operating a system that continued to function beyond design expectations also are highlighted.

Petkus, Lawrence L.; Paul, James; Valenti, Paul J.; Houston, Helene; May, Joseph

2003-02-27T23:59:59.000Z

388

Benchmarking the Remote-Handled Waste Facility at the West Valley Demonstration Project  

Science Conference Proceedings (OSTI)

ABSTRACT Facility decontamination activities at the West Valley Demonstration Project (WVDP), the site of a former commercial nuclear spent fuel reprocessing facility near Buffalo, New York, have resulted in the removal of radioactive waste. Due to high dose and/or high contamination levels of this waste, it needs to be handled remotely for processing and repackaging into transport/disposal-ready containers. An initial conceptual design for a Remote-Handled Waste Facility (RHWF), completed in June 1998, was estimated to cost $55 million and take 11 years to process the waste. Benchmarking the RHWF with other facilities around the world, completed in November 1998, identified unique facility design features and innovative waste pro-cessing methods. Incorporation of the benchmarking effort has led to a smaller yet fully functional, $31 million facility. To distinguish it from the June 1998 version, the revised design is called the Rescoped Remote-Handled Waste Facility (RRHWF) in this topical report. The conceptual design for the RRHWF was completed in June 1999. A design-build contract was approved by the Department of Energy in September 1999.

O. P. Mendiratta; D. K. Ploetz

2000-02-29T23:59:59.000Z

389

A West Valley Demonstration Project Milestone - Achieving Certification to Ship Waste to the Nevada Test Site  

SciTech Connect

The West Valley Demonstration Project (WVDP) has successfully pretreated and vitrified nearly all of the 600,000 gallons of liquid high-level radioactive waste that was generated at the site of the only commercial nuclear fuel reprocessing plant to have operated in the United States. Low-level waste (LLW) generated during the course of the cleanup effort now requires disposal. Currently the WVDP only ships Class A LLW for off-site disposal. It has been shipping Class A wastes to Envirocare of Utah, Inc. since 1997. However, the WVDP may also have a future need to ship Class B and Class C waste, which Envirocare is not currently authorized to accept. The Nevada Test Site (NTS), a U.S. Department of Energy (DOE) facility, can accept all three waste classifications. The WVDP set a goal to receive certification to begin shipping Class A wastes to NTS by 2001. Formal certification/approval was granted by the DOE Nevada Operations Office on July 12, 2001. This paper discusses how the WVDP contractor, West Valley Nuclear Services Company (WVNSCO), completed the activities required to achieve NTS certification in 2001 to ship waste to its facility. The information and lessons learned provided are significant because the WVDP is the only new generator receiving certification based on an NTS audit in January 2001 that resulted in no findings and only two observations--a rating that is unparalleled in the DOE Complex.

Jackson, J. P.; Pastor, R. S.

2002-02-28T23:59:59.000Z

390

Entering a New Stage of Learning from the U.S. Fuel Cell Electric Vehicle Demonstration Project: Preprint  

DOE Green Energy (OSTI)

The National Fuel Cell Electric Vehicle Learning Demonstration is a U.S. Department of Energy (DOE) project that started in 2004. The purpose of this project is to conduct an integrated field validation that simultaneously examines the performance of fuel cell vehicles and the supporting hydrogen infrastructure. The DOE's National Renewable Energy Laboratory (NREL) has now analyzed data from over five years of the seven-year project. During this time, over 144 fuel cell electric vehicles have been deployed, and 23 project refueling stations were placed in use.

Wipke, K.; Sprik, S.; Kurtz, J.; Ramsden, T.; Garbak, J.

2010-10-01T23:59:59.000Z

391

Phase 1 Final status survey plan for the West Valley demonstration project.  

SciTech Connect

This plan provides the technical basis and associated protocols to support Phase 1 final status survey (FSS) data collection and interpretation as part of the West Valley Demonstration Project Phase 1 Decommissioning Plan process. This plan is consistent with the Multi-Agency Radiation Survey and Site Investigation Manual (MARSSIM). The Phase 1 Decommissioning Plan provides the relevant derived concentration guideline levels (DCGLs) for the Phase 1 radionuclides of interest. This plan includes protocols that will be applied to the deep excavations planned for Waste Management Area (WMA) 1 and WMA 2, for surface soils outside the WMA 1 and WMA 2 excavations that do not have contamination impacts at depths greater than one meter, and for areas that are used for Phase 1 contaminated soil lay-down purposes. All excavated and lay-down areas will be classified as MARSSIM Class 1 areas. Surface soils that have not been excavated, are not expected to exceed DCGLs, and do not have contamination impacts at depths greater than one meter will be divided into either Class 1 or Class 2 areas depending on the expected potential for surface soil contamination in those areas. The plan uses gamma scans combined with biased soil samples to address DCGLemc concerns. The plan uses systematic soil sampling combined with area factors to address DCGLw and DCGLemc concerns. The Sign test will be used to statistically evaluate DCGLw compliance. If the results from the characterization sampling and analysis plan (CSAP) data collection indicate that background may be a significant issue for Sign test implementation, the Wilcoxon rank sum (WRS) test will be used instead to demonstrate DCGLw compliance. A reference area will be selected on the basis of CSAP data results if the WRS test becomes a necessity. The WMA 1 excavation footprint includes approximately 476 foundation pilings that will be trimmed and left in place. Piling-specific systematic and biased sampling will be conducted to address concerns that these pilings may have served as preferential flow pathways into the underlying Lavery till. Phase 1 FSS data collection results will be summarized, presented, and interpreted in one or more FSS reports.

Johnson, R. L. (Environmental Science Division)

2011-05-31T23:59:59.000Z

392

Phase 1 Characterization sampling and analysis plan West Valley demonstration project.  

SciTech Connect

The Phase 1 Characterization Sampling and Analysis Plan (CSAP) provides details about environmental data collection that will be taking place to support Phase 1 decommissioning activities described in the Phase 1 Decommissioning Plan for the West Valley Demonstration Project, Revision 2 (Phase I DP; DOE 2009). The four primary purposes of CSAP data collection are: (1) pre-design data collection, (2) remedial support, (3) post-remediation status documentation, and (4) Phase 2 decision-making support. Data collection to support these four main objectives is organized into two distinct data collection efforts. The first is data collection that will take place prior to the initiation of significant Phase 1 decommissioning activities (e.g., the Waste Management Area [WMA] 1 and WMA 2 excavations). The second is data collection that will occur during and immediately after environmental remediation in support of remediation activities. Both data collection efforts have a set of well-defined objectives that encompass the data needs of the four main CSAP data collection purposes detailed in the CSAP. The main body of the CSAP describes the overall data collection strategies that will be used to satisfy data collection objectives. The details of pre-remediation data collection are organized by WMA. The CSAP contains an appendix for each WMA that describes the details of WMA-specific pre-remediation data collection activities. The CSAP is intended to expand upon the data collection requirements identified in the Phase 1 Decommissioning Plan. The CSAP is intended to tightly integrate with the Phase 1 Final Status Survey Plan (FSSP). Data collection described by the CSAP is consistent with the FSSP where appropriate and to the extent possible.

Johnson, R. L. (Environmental Science Division)

2011-06-30T23:59:59.000Z

393

Development of analytical cell support for vitrification at the West Valley Demonstration Project. Topical report  

SciTech Connect

Analytical and Process Chemistry (A&PC) support is essential to the high-level waste vitrification campaign at the West Valley Demonstration Project (WVDP). A&PC characterizes the waste, providing information necessary to formulate the recipe for the target radioactive glass product. High-level waste (HLW) samples are prepared and analyzed in the analytical cells (ACs) and Sample Storage Cell (SSC) on the third floor of the main plant. The high levels of radioactivity in the samples require handling them in the shielded cells with remote manipulators. The analytical hot cells and third floor laboratories were refurbished to ensure optimal uninterrupted operation during the vitrification campaign. New and modified instrumentation, tools, sample preparation and analysis techniques, and equipment and training were required for A&PC to support vitrification. Analytical Cell Mockup Units (ACMUs) were designed to facilitate method development, scientist and technician training, and planning for analytical process flow. The ACMUs were fabricated and installed to simulate the analytical cell environment and dimensions. New techniques, equipment, and tools could be evaluated m in the ACMUs without the consequences of generating or handling radioactive waste. Tools were fabricated, handling and disposal of wastes was addressed, and spatial arrangements for equipment were refined. As a result of the work at the ACMUs the remote preparation and analysis methods and the equipment and tools were ready for installation into the ACs and SSC m in July 1995. Before use m in the hot cells, all remote methods had been validated and four to eight technicians were trained on each. Fine tuning of the procedures has been ongoing at the ACs based on input from A&PC technicians. Working at the ACs presents greater challenges than had development at the ACMUs. The ACMU work and further refinements m in the ACs have resulted m in a reduction m in analysis turnaround time (TAT).

Barber, F.H.; Borek, T.T.; Christopher, J.Z. [and others

1997-12-01T23:59:59.000Z

394

Goose River, Maine, demonstration project, January 1978-October 1978. Final report  

DOE Green Energy (OSTI)

The proposed Goose River Project is a commercial power development consisting of 4 power dams and one storage dam. All available energy is to be wholesaled to the Central Maine Power Company, the utility holding the franchise for the area. A description of the economic feasibility of the proposed project is presented.

Not Available

1978-11-24T23:59:59.000Z

395

Geomechanical risks in coal bed carbon dioxide sequestration  

E-Print Network (OSTI)

its geomechanical impact. A coal bed methane production/CO 2should be applicable to coal bed methane CO 2 projects. Ifcompletion for a coal bed methane project involves

Myer, Larry R.

2003-01-01T23:59:59.000Z

396

Occupational Safety and Health Program at the West Valley Demonstration Project  

Science Conference Proceedings (OSTI)

The West Valley Nuclear Services Co. LLC (WVNS) is committed to provide a safe, clean, working environment for employees, and to implement U.S. Department of Energy (DOE) requirements affecting worker safety. The West Valley Demonstration Project (WVDP) Occupational Safety and Health Program is designed to protect the safety, health, and well-being of WVDP employees by identifying, evaluating, and controlling biological, chemical, and physical hazards in the work place. Hazards are controlled within the requirements set forth in the reference section at the end of this report. It is the intent of the WVDP Occupational Safety and Health Program to assure that each employee is provided with a safe and healthy work environment. This report shows the logical path toward ensuring employee safety in planning work at the WVDP. In general, planning work to be performed safely includes: combining requirements from specific programs such as occupational safety, industrial hygiene, radiological control, nuclear safety, fire safety, environmental protection, etc.; including WVDP employees in the safety decision-making processes; pre-planning using safety support re-sources; and integrating the safety processes into the work instructions. Safety management principles help to define the path forward for the WVDP Occupational Safety and Health Program. Roles, responsibilities, and authority of personnel stem from these ideals. WVNS and its subcontractors are guided by the following fundamental safety management principles: ''Protection of the environment, workers, and the public is the highest priority. The safety and well-being of our employees, the public, and the environment must never be compromised in the aggressive pursuit of results and accomplishment of work product. A graded approach to environment, safety, and health in design, construction, operation, maintenance, and deactivation is incorporated to ensure the protection of the workers, the public, and the environment.'' These principles are demonstrated through: Conducting all activities in an atmosphere of trust and confidence based on open, honest, and responsive communication. Using innovative and effective approaches to risk identification and management. Applying a systematic approach to planning and execution of all activities that affect the environment, safety, and health through use of the Integrated Environment, Safety, and Health Management System. Holding line management fully accountable to effectively plan and integrate environment, safety, and health activities into field activities. Providing clear policy and direction on environment, safety, and health issues to guide field work. Encouraging and promoting the sharing of environment, safety, and health information and resources. Empowering employees through training, information, tools, and program involvement to effectively protect themselves and the environment. Ensuring it is every employees' responsibility to identify and report potential safety and health hazards and environmental noncompliance. Together, as a team, we accomplish our mission while protecting the environment and preserving the safety and health of each employee and the public.

L. M. Calderon

1999-04-30T23:59:59.000Z

397

The Solar-to-Battery and Community Energy Storage Project Demonstrations at SolarTAC: 2013 Results and Findings  

Science Conference Proceedings (OSTI)

Xcel Energy and EPRI are jointly researching two battery-based energy storage projects at the Solar Technology Acceleration Center (SolarTAC) in Aurora, Colorado. Each pilot aims to discern the technical and economic value of utilizing energy storage as a tool for managing growing penetrations of variable renewable resources on the grid network, particularly distributed photovoltaics (PV).The first initiative, known as the Community Energy Storage (CES) project, is demonstrating a ...

2013-12-10T23:59:59.000Z

398

Self-scrubbing coal{sup TM}: An integrated approach to clean air. A proposed Clean Coal Technology Demonstration Project  

Science Conference Proceedings (OSTI)

This environmental assessment (EA) was prepared by the U.S.Department of Energy (DOE), with compliance with the National Environmental Policy Act (NEPA) of 1969, Council on Environmental Quality (CE) regulations for implementating NEPA (40 CFR 1500-1508) and DOE regulations for compliance with NEPA (10 CFR 1021), to evaluate the potential environmental impacts associated with a proposed demonstration project to be cost-shared by DOE and Custom Coals International (CCI) under the Clean Coal Technology (CCT) Demonstration Program of DOE`s Office of Fossil Energy. CCI is a Pennsylvania general partnership located in Pittsburgh, PA engaged in the commercialization of advanced coal cleaning technologies. The proposed federal action is for DOE to provide, through a cooperative agreement with CCI, cost-shared funding support for the land acquisition, design, construction and demonstration of an advanced coal cleaning technology project, {open_quotes}Self-Scrubbing Coal: An Integrated Approach to Clean Air.{close_quotes} The proposed demonstration project would take place on the site of the presently inactive Laurel Coal Preparation Plant in Shade Township, Somerset County, PA. A newly constructed, advanced design, coal preparation plant would replace the existing facility. The cleaned coal produced from this new facility would be fired in full-scale test burns at coal-fired electric utilities in Indiana, Ohio and PA as part of this project.

Not Available

1994-01-01T23:59:59.000Z

399

2012 SG Peer Review - Recovery Act: AEP Ohio gridSMART Demonstration Project - Karen Sloneker, Columbus Southern Power (AEP)  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Program Program Peer Review Meeting AEP Ohio gridSMART ® Demonstration Project Karen Sloneker AEP Ohio gridSMART Project Director ® December 2008 AEP Ohio gridSMART ® Demonstration Project Objectives * To build an integrated secure smart grid infrastructure. * Attract, educate, enlist and retain consumers using innovative business models that provide tools to reduce costs, consumption and peak demand. * Gather data on technology and smart grid business models to forecast national impact. Life-cycle Funding 2010 - 2013 $73,660,317 Technical Scope (Insert graphic here) * 110,000 AMI meters and associated infrastructure * Consumer Managed Energy Technology (experimental tariffs, consumer programs, web portal; smart appliances, and plug-in electric vehicles) * Innovative Demand Management * Distribution Automation and Reliability

400

2012 SG Peer Review - Recovery Act: Pacific Northwest Smart Grid Demonstration Project - Ron Melton, Battelle Memorial Institute  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Overview Overview Ron Melton, Ph.D., Project Director Don Hammerstrom, Ph.D., Principal Investigator Battelle, Pacific Northwest Division Presented at DOE-OE Smart Grid R&D Peer Review June 8, 2012 PNWD-SA-9876 Pacific Northwest Demonstration Project What: * $178M, ARRA-funded, 5-year demonstration * 60,000 metered customers in 5 states Why: * Quantify costs and benefits * Develop communications protocol * Develop standards * Facilitate integration of wind and other renewables Who: Led by Battelle and partners including BPA, 11 utilities, 2 universities, and 5 vendors 2 Project Basics 3 Transactive Control Operational objectives Manage peak demand Facilitate renewable resources Address constrained resources Improve system reliability and efficiency Select economical

Note: This page contains sample records for the topic "bed demonstration project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


401

Environmental monitoring for the DOE coolside and LIMB demonstration extension projects. Final report, May--August 1991  

SciTech Connect

The purpose of this document is to present environmental monitoring data collected during the US Department of Energy Limestone Injection Multistage Burner (DOE LIMB) Demonstration Project Extension at the Ohio Edison Edgewater Generating Station in Lorain, Ohio. The DOE project is an extension of the US Environmental Protection Agency`s (EPA`s) original LIMB Demonstration. The program is operated nuclear DOE`s Clean Coal Technology Program of ``emerging clean coal technologies`` under the categories of ``in boiler control of oxides of sulfur and nitrogen`` as well as ``post-combustion clean-up.`` The objective of the LIMB program is to demonstrate the sulfur dioxide (SO{sub 2}) and nitrogen oxide (NO{sub x}) emission reduction capabilities of the LIMB system. The LIMB system is a retrofit technology to be used for existing coal-fired boilers equipped with electrostatic precipitators (ESPs).

White, T.; Contos, L.; Adams, L. [Radian Corp., Research Triangle Park, NC (United States)

1992-03-01T23:59:59.000Z

402

Spent Nuclear Fuel Dry Transfer System Cold Demonstration Project Final Report  

SciTech Connect

The spent nuclear fuel dry transfer system (DTS) provides an interface between large and small casks and between storage-only and transportation casks. It permits decommissioning of reactor pools after shutdown and allows the use of large storage-only casks for temporary onsite storage of spent nuclear fuel irrespective of reactor or fuel handling limitations at a reactor site. A cold demonstration of the DTS prototype was initiated in August 1996 at the Idaho National Engineering and Environmental Laboratory (INEEL). The major components demonstrated included the fuel assembly handling subsystem, the shield plug/lid handling subsystem, the cask interface subsystem, the demonstration control subsystem, a support frame, and a closed circuit television and lighting system. The demonstration included a complete series of DTS operations from source cask receipt and opening through fuel transfer and closure of the receiving cask. The demonstration included both normal operations and recovery from off-normal events. It was designed to challenge the system to determine whether there were any activities that could be made to jeopardize the activities of another function or its safety. All known interlocks were challenged. The equipment ran smoothly and functioned as designed. A few "bugs" were corrected. Prior to completion of the demonstration testing, a number of DTS prototype systems were modified to apply lessons learned to date. Additional testing was performed to validate the modifications. In general, all the equipment worked exceptionally well. The demonstration also helped confirm cost estimates that had been made at several points in the development of the system.

Christensen, Max R; McKinnon, M. A.

1999-12-01T23:59:59.000Z

403

D&D Toolbox Project - Technology Demonstration of Fixatives Applied to Hot Cell Facilities via Remote Sprayer Platforms  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Demonstration Demonstration D&D Toolbox - FIU Tech Demo FIU Technology Demonstration - Selected technology platform(s) was demonstrated at the hot cell mockup facility at the FIU's Applied Research Center tech demo site in Miami, FL. Page 1 of 2 Oak Ridge National Laboratory Tennessee Florida New York D&D Toolbox Project - Technology Demonstration of Fixatives Applied to Hot Cell Facilities via Remote Sprayer Platforms Challenge Many facilities slated for D&D across the DOE complex pose hazards (radiological, chemical, and structural) which prevent the use of traditional manual techniques. Efficient and safe D&D of the facilities will require the use of remotely operated technologies. In addition, the D&D of a hot cell facility requires that each of the hot cells be

404

Economic assessment of geothermal direct heat technology: A review of five DOE demonstration projects  

DOE Green Energy (OSTI)

In this report the cost of using low temperature geothermal energy resources for direct heating applications is compared to the costs associated with conventional heating fuels. The projects compared all involved replacing conventional fuels (e.g., natural gas and fuel oils) with geothermal energy in existing heating systems. The cost of using geothermal energy in existing systems was also compared with the cost of new coal-fired equipment.

Hederman, William F. Jr.; Cohen, Laura A.

1981-06-01T23:59:59.000Z

405

Methodological Approach for Estimating the Benefits and Costs of Smart Grid Demonstration Projects  

Science Conference Proceedings (OSTI)

This report presents a comprehensive framework for estimating the benefits and costs of Smart Grid projects and a step-by-step approach for making these estimates. The framework identifies the basic categories of benefits, the beneficiaries of these benefits, and the Smart Grid functionalities that lead to different benefits and proposes ways to estimate these benefits, including their monetization. The report covers cost-effectiveness evaluation, uncertainty, and issues in estimating baseline conditions...

2010-01-26T23:59:59.000Z

406

Cummins Engine Company B5.9 Propane Engine Development, Certification, and Demonstration Project  

DOE Green Energy (OSTI)

The objective of this project was to successfuly develop and certify an LPG-dedicated medium-duty original equipment manufacturer (OEM) engine that could be put into production. The engine was launched into production in 1994, and more than 800 B5.9G engines are now in service in the United States and abroad. This engine is now offered by more than 30 bus and truck OEMs.

The ADEPT Group, Inc. (Los Angeles, California)

1998-12-18T23:59:59.000Z

407

2012 SG Peer Review - Recovery Act: Irvine Smart Grid Demonstration Project - Ardalan Kemiab, Southern California Edison  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Peer Peer Review Meeting Peer Review Meeting Irvine Smart Grid Demonstration (ISGD) ( ) Ed Kamiab Southern California Edison (SCE) 6/8/2012 ISGD Objective SCE' I i S t G id D t ti (ISGD) ill (Insert graphic here) SCE's Irvine Smart Grid Demonstration (ISGD) will demonstrate an integrated, scalable Smart Grid system that includes many of the interlocking pieces of an end- to-end Smart Grid system, from the transmission and distrib tion s stems to cons mer applications s ch as distribution systems to consumer applications such as smart appliances and plug-in electric vehicles. Life-cycle Funding ($K) FY2010 FY2015 1. Energy Smart Customer Devices 2 Year 2020 Distribution System Technical Scope FY2010 - FY2015 $39,612 2. Year 2020 Distribution System 3. Interoperability & Cyber Security 4. Workforce of the Future

408

CERTS Microgrid Laboratory Test Bed  

E-Print Network (OSTI)

CERTS Microgrid Laboratory Test Bed R. H. Lasseter, Fellow,play functionality. The tests demonstrated stable behaviorin an autonomous manner. All tests performed as expected and

Lasseter, R. H.

2010-01-01T23:59:59.000Z

409

LOS ANGELES DEPARTMENT OF WATER AND POWER FUEL CELL DEMONSTRATION PROJECT  

DOE Green Energy (OSTI)

The Los Angeles Department of Water and Power (LADWP) is currently one of the most active electric utility companies in deploying fuel cell technology. Fuel cells offer many benefits and are now used as an alternative to traditional internal combustion engines in power generation. In continuing it's role as the leader in fuel cell deploying, LADWP installed a Phosphoric Acid Fuel Cell (PAFC) in February 2002 at its Main Street service center. The goal of this project is to evaluate the PAFC's performance and cost benefits. This will provide LADWP an insight for future deployment of fuel cell technology. The fuel cell ran smoothly through the first year of operation with very high efficiency and availability, and only with some minor setbacks. The Main street fuel cell project is funded by LADWP with partial grant funding from the Department of Defense's Climate Change Fuel Cell Buydown Program. The technical evaluation and the benefit-cost evaluation of the Main Street fuel cell are both examined in this report.

William W. Glauz

2004-03-26T23:59:59.000Z

410

LIMB Demonstration Project Extension. Quarterly report no. 5, May, June and July 1988  

SciTech Connect

The basic goal of the Limestone Injection Multistage Burner (LIMB) demonstration is to extend LIMB technology development to a full-scale application on a representative wall-fired utility boiler. The successful retrofit of LIMB to an existing boiler is expected to demonstrate that (a) reductions of 50 percent or greater in SO and NO emissions can be achieved at a fraction of the cost of add-on FGD systems, (b) boiler reliability, operability, and steam production can be maintained at levels existing prior to LIMB retrofit, and (c) technical difficulties attributable to LIMB operation, such as additional slagging and fouling, changes in ash disposal requirements, and an increased particulate load, can be resolved in a cost-effective manner. The primary fuel to be used will be an Ohio bituminous coal having a nominal sulfur content of 3 percent or greater.

Not Available

1988-09-15T23:59:59.000Z

411

LIMB Demonstration Project Extension. Quarterly report No. 6, August--October, 1988  

Science Conference Proceedings (OSTI)

The basic goal of the Limestone Injection Multistage Burner (LIMB) demonstration is to extend LIMB technology development to a full- scale application on a representative wall-fired utility boiler. The successful retrofit of LIMB to an existing boiler is expected to demonstrate that (a) reductions of 50 percent or greater in SO{sub x} and NO{sub x} emissions can be achieved at a fraction of the cost of add-on FGD systems, (b) boiler reliability, operability, and steam production can be maintained at levels existing prior to LIMB retrofit, and (c) technical difficulties attributable to LIMB operation, such as additional slagging and fouling, changes in ash disposal requirements, and an increased particulate load, can be resolved in a cost-effective manner. The primary fuel to be used will be an Ohio bituminous coal having a nominal sulfur content of 3 percent or greater.

Not Available

1988-12-15T23:59:59.000Z

412

Environmental assessmental, geothermal energy, Heber geothermal binary-cycle demonstration project: Imperial County, California  

DOE Green Energy (OSTI)

The proposed design, construction, and operation of a commercial-scale (45 MWe net) binary-cycle geothermal demonstration power plant are described using the liquid-dominated geothermal resource at Heber, Imperial County, California. The following are included in the environmental assessment: a description of the affected environment, potential environmental consequences of the proposed action, mitigation measures and monitoring plans, possible future developmental activities at the Heber anomaly, and regulations and permit requirements. (MHR)

Not Available

1980-10-01T23:59:59.000Z

413

Geomechanical risks in coal bed carbon dioxide sequestration  

E-Print Network (OSTI)

SAF. 1958. The strength of coal in triaxial compression.Geomechanical Risks in Coal Bed Carbon Dioxide Sequestrationof leakage of CO 2 from coal bed sequestration projects. The

Myer, Larry R.

2003-01-01T23:59:59.000Z

414

Home Energy Savers' Program. A report on a demonstration project undertaken in Utah  

SciTech Connect

The Utah Home Energy Savers Program (HESP) is described and results are summarized. The project basically tested the impact of several research elements on homeowners participation through the use of: a direct mailing of 276,000 HESP workbooks to single-family homeowners; a telephone hotline to respond to incoming calls and to conduct an energy conservation survey; workshops to acquaint the citizenry with the facts of the national and statewide energy situation and the contents of the HESP workbook; a professional, commercial promotional firm to undertake a coordinated media program in support of the mailing of the HESP workbook; church and community sponshorship of the program; and selected methods of reaching sparsely populated areas.

Jensen, G.F.

1977-01-01T23:59:59.000Z

415

Green River Formation Water Flood Demonstration Project: Final report. [October 21, 1992-April, 30, 1996  

Science Conference Proceedings (OSTI)

The objectives were to understand the oil production mechanisms in the Monument Butte unit via reservoir characterization and reservoir simulations and to transfer the water flooding technology to similar units in the vicinity, particularly the Travis and the Boundary units. Comprehensive reservoir characterization and reservoir simulations of the Monument Butte, Travis and Boundary units were presented in the two published project yearly reports. The primary and the secondary production from the Monument Butte unit were typical of oil production from an undersaturated oil reservoir close to its bubble point. The water flood in the smaller Travis unit appeared affected by natural and possibly by large interconnecting hydraulic fractures. Water flooding the boundary unit was considered more complicated due to the presence of an oil water contact in one of the wells. The reservoir characterization activity in the project basically consisted of extraction and analysis of a full diameter c ore, Formation Micro Imaging logs from several wells and Magnetic Resonance Imaging logs from two wells. In addition, several side-wall cores were drilled and analyzed, oil samples from a number of wells were physically and chemically characterized (using gas chromatography), oil-water relative permeabilities were measured and pour points and cloud points of a few oil samples were determined. The reservoir modeling activity comprised of reservoir simulation of all the three units at different scales and near well-bore modeling of the wax precipitation effects. The reservoir characterization efforts identified new reservoirs in the Travis and the Boundary units. The reservoir simulation activities established the extent of pressurization of the sections of the reservoirs in the immediate vicinity of the Monument Butte unit. This resulted in a major expansion of the unit and the production from this expanded unit increased from about 300 barrels per day to about 2000 barrels per day.

Deo, M.D. [Dept. of Chemical and Fuels Engineering, University of Utah, Salt Lake City (US); Dyer, J.E.; Lomax, J.D. [Inland Resources, Inc., Lomax Exploration Co., Salt Lake City, UT (US); Nielson, D.L.; Lutz, S.J. [Energy and Geoscience Institute at the University of Utah, Salt Lake City (US)

1996-11-01T23:59:59.000Z

416

Western Greenbrier Co-Production Demonstration Project Draft Environmental Impact Statement  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

DRAFT ENVIRONMENTAL IMPACT STATEMENT SUMMARY S-1 SUMMARY This environmental impact statement (EIS) has been prepared by the United States Department of Energy (DOE), in compliance with the National Environmental Policy Act of 1969 (NEPA) as amended (42 USC 4321 et seq.), to evaluate the potential environmental impacts associated with the construction and demonstration of a 98-megawatt (MWe) net power plant and cement manufacturing facility (the "Co- Production Facility"). The responsible organization for the federal action is the National Energy Technology Laboratory (NETL), a multi-purpose laboratory owned and operated by DOE. Proposed Action The Proposed Action is for DOE to decide whether to provide financial assistance to Western

417

Performance-Based Technology Selection Filter description report. INEL Buried Waste Integrated Demonstration System Analysis project  

SciTech Connect

A formal methodology has been developed for identifying technology gaps and assessing innovative or postulated technologies for inclusion in proposed Buried Waste Integrated Demonstration (BWID) remediation systems. Called the Performance-Based Technology Selection Filter, the methodology provides a formalized selection process where technologies and systems are rated and assessments made based on performance measures, and regulatory and technical requirements. The results are auditable, and can be validated with field data. This analysis methodology will be applied to the remedial action of transuranic contaminated waste pits and trenches buried at the Idaho National Engineering Laboratory (INEL).

O`Brien, M.C.; Morrison, J.L.; Morneau, R.A.; Rudin, M.J.; Richardson, J.G.

1992-05-01T23:59:59.000Z

418

GLASS FORMULATION DEVELOPMENT AND TESTING FOR COLD CRUCIBLE INDUCTION MELTER (CCIM) ADVANCED REMEDIATION TECHNOLOGIES DEMONSTRATION PROJECT - 9208  

SciTech Connect

Over the past few years, Cold Crucible Induction Melter (CCIM) demonstrations have been completed using SRS sludge batches 2, 3 and 4 (SB2, SB3 and SB4) simulant compositions. These campaigns demonstrated the ability of the CCIM to effectively produce quality glasses at high waste loadings. The current Advanced Remediation Technology (ART) Phase II-A Project is aimed at demonstrating the CCIM technology under representative DWPF flowsheet conditions and to demonstrate extended operations of the melter. A glass composition development effort was completed to identify and recommend a frit composition and sludge batch 4 (SB4) simulant waste loading target for subsequent ART-Phase II-A CCIM demonstration testing. Based on the results of the glass formulation testing, it was recommended that the Frit 503-R6 composition (B{sub 2}O{sub 3} = 14 wt %; Li{sub 2}O = 9 wt %; Na{sub 2}O = 3 wt %; and SiO{sub 2} = 74 wt %) be utilized for the demonstration. Furthermore, a waste loading of 46 wt % was recommended. The recommended frit and waste loading would produce a glass with acceptable durability with a liquidus temperature adequately below the 1250 C nominal CCIM operating temperature. This frit composition and waste loading was found to result in a glass that met CCIM processing requirements for viscosity, electrical conductivity and thermal conductivity. The recommended frit and waste loading level should also provide a buffer for sludge product compositional variation to support the Phase II-A CCIM demonstration.

Marra, J; Amanda Billings, A; David Peeler, D; Michael Stone, M; Tommy Edwards, T

2008-08-27T23:59:59.000Z

419

Demand Management Demonstration Project, Stage 5: development of industrial load simulation model. Executive summary. Final report  

SciTech Connect

The purpose of this project was to design, develop, test and document a computer simulation model of electric utility generating costs required to meet industrial power demands and the effects of utility load management on these generating costs. The results showed that the model developed is a well conceived load management testing, marginal costing tool. What if situations can be readily tested to determine their impact on system profile and short run marginal costs. The terms unshaped and shaped refer to customers or system use patterns before and after some load management technique was tested. The total flexibility of the model is only apparent after the user has studied test runs in detail. Hourly marginal costs reveal many unexpected changes as a result of shaping loads. Other unexpected changes due to varying economic dispatch schedules while shaping, illustrate the unprecedental latitude for the user to explore optimum generation and load management combinations. The general concept of the model is depicted in the flow chart on the next page.

1977-04-01T23:59:59.000Z

420

Automated Demand Response Technology Demonstration Project for Small and Medium Commercial Buildings  

Science Conference Proceedings (OSTI)

Small and medium commercial customers in California make up about 20-25% of electric peak load in California. With the roll out of smart meters to this customer group, which enable granular measurement of electricity consumption, the investor-owned utilities will offer dynamic prices as default tariffs by the end of 2011. Pacific Gas and Electric Company, which successfully deployed Automated Demand Response (AutoDR) Programs to its large commercial and industrial customers, started investigating the same infrastructures application to the small and medium commercial customers. This project aims to identify available technologies suitable for automating demand response for small-medium commercial buildings; to validate the extent to which that technology does what it claims to be able to do; and determine the extent to which customers find the technology useful for DR purpose. Ten sites, enabled by eight vendors, participated in at least four test AutoDR events per site in the summer of 2010. The results showed that while existing technology can reliably receive OpenADR signals and translate them into pre-programmed response strategies, it is likely that better levels of load sheds could be obtained than what is reported here if better understanding of the building systems were developed and the DR response strategies had been carefully designed and optimized for each site.

Page, Janie; Kiliccote, Sila; Dudley, Junqiao Han; Piette, Mary Ann; Chiu, Albert K.; Kellow, Bashar; Koch, Ed; Lipkin, Paul

2011-07-01T23:59:59.000Z

Note: This page contains sample records for the topic "bed demonstration project" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


421

Wind energy demonstration project in cooperation with the City of Fairfield: negative declaration and initial study  

Science Conference Proceedings (OSTI)

The project is a joint venture between the California Energy Commission (CEC) and the City of Fairfield (the City). The City will sell the electricity to the Mid-Valley Dairy, which is currently under construction, and will sell any excess pow