National Library of Energy BETA

Sample records for avoided cost level

  1. Avoiding Distribution System Upgrade Costs Using Distributed Generation

    SciTech Connect (OSTI)

    Schienbein, Lawrence A.; Balducci, Patrick J.; Nguyen, Tony B.; Brown, Daryl R.; DeSteese, John G.; Speer, Gregory A.

    2004-01-20

    PNNL, in cooperation with three utilities, developed a database and methodology to analyze and characterize the avoided costs of Distributed Generation (DG) deployment as an alternative to traditional distribution system investment. After applying a number of screening criteria to the initial set of 307 cases, eighteen were selected for detailed analysis. Alternative DG investment scenarios were developed for these cases to permit capital, operation, maintenance, and fuel costs to be identified and incorporated into the analysis. The “customer-owned” backup power generator option was also investigated. The results of the analysis of the 18 cases show that none yielded cost savings under the alternative DG scenarios. However, the DG alternative systems were configured using very restrictive assumptions concerning reliability, peak rating, engine types and acceptable fuel. In particular it was assumed that the DG alternative in each case must meet the reliability required of conventional distribution systems (99.91% reliability). The analysis was further constrained by a requirement that each substation meet the demands placed upon it by a one in three weather occurrence. To determine if, by relaxing these requirements, the DG alternative might be more viable, one project was re-examined. The 99.91% reliability factor was still assumed for normal operating conditions but redundancy required to maintain reliability was relaxed for the relatively few hours every three years where extreme weather caused load to exceed present substation capacity. This resulted in the deferment of capital investment until later years and reduced the number of engines required for the project. The cost of both the conventional and DG alternative also dropped because the centralized power generation, variable O&M, and DG fuels costs were calculated based on present load requirements in combination with long-term forecasts of load growth, as opposed to load requirements plus a buffer based on predictions of extraordinary weather conditions. Application of the relaxed set of assumptions reduced the total cost of the DG alternative by roughly 57 percent from $7.0 million to $3.0 million. The reduction, however, did not change the overall result of the analysis, as the cost of the conventional distribution system upgrade alternative remained lower at $1.7 million. This paper also explores the feasibility of using a system of backup generators to defer investment in distribution system infrastructure. Rather than expanding substation capacity at substations experiencing slow load growth rates, PNNL considered a scenario where diesel generators were installed on location at customers participating in a program designed to offer additional power security and reliability to the customer and connection to the grid. The backup generators, in turn, could be used to meet peak demand for a limited number of hours each year, thus deferring distribution system investment. Data from an existing program at one of the three participating utilities was used to quantify the costs associated with the backup generator scenario. The results of the “customer owned” backup power generator analysis showed that in all cases the nominal cost of the DG scenario is more than the nominal cost of the base-case conventional distribution system upgrade scenario. However, in two of the cases the total present value costs of the alternative backup generator scenarios were between 15 and 22% less than those for the conventional scenarios. Overall, the results of the study offer considerable encouragement that the use of DG systems can defer conventional distribution system upgrades under the right conditions and when the DG configurations are intelligently designed. Using existing customer-owned DG to defer distribution system upgrades appears to be an immediate commercially-viable opportunity.

  2. Determining Baseline and Avoided Costs for UESC Projects

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    for "normal" weather, hours of operation, occupancy, etc. From recent years' utility data (building level) or sub- metered utility consumption (system level) Base for...

  3. Avoided Cost Rates, Environmental Externalities | OpenEI Community

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on QA:QA J-E-1 SECTION JEnvironmental Jump to:EAandAmminex AAustria Geothermal Region JumpFacility | OpenPower,Avoided

  4. Avoided Costs and Competitive Negotiations for Power from Qualifying Facilities in Texas 

    E-Print Network [OSTI]

    Panjavan, S.; Al-Jabir, A.

    1992-01-01

    of contracts to those qualifying facilities who produce electricity through environmentally beneficial processes. These generation technologies include the burning of municipal solid waste and renewable fuel sources such as solar or wind power. Beyond...), describes the methodology that all utilities must use in calculating their avoided costs for firm capacity. The Commission requires that generating utilities use the Committed Unit Basis (CUB) methodology to calculate the avoided cost for firm power...

  5. User's guide to SERICPAC: A computer program for calculating electric-utility avoided costs rates

    SciTech Connect (OSTI)

    Wirtshafter, R.; Abrash, M.; Koved, M.; Feldman, S.

    1982-05-01

    SERICPAC is a computer program developed to calculate average avoided cost rates for decentralized power producers and cogenerators that sell electricity to electric utilities. SERICPAC works in tandem with SERICOST, a program to calculate avoided costs, and determines the appropriate rates for buying and selling of electricity from electric utilities to qualifying facilities (QF) as stipulated under Section 210 of PURA. SERICPAC contains simulation models for eight technologies including wind, hydro, biogas, and cogeneration. The simulations are converted in a diversified utility production which can be either gross production or net production, which accounts for an internal electricity usage by the QF. The program allows for adjustments to the production to be made for scheduled and forced outages. The final output of the model is a technology-specific average annual rate. The report contains a description of the technologies and the simulations as well as complete user's guide to SERICPAC.

  6. Levelized cost and levelized avoided cost of new generation resources in the Annual Energy Outlook 2014

    Annual Energy Outlook [U.S. Energy Information Administration (EIA)]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (BillionProved ReservesCubic Feet) Kenai, AK Liquefied Natural2009343 342 328 37056April 2014

  7. Levelized Cost and Levelized Avoided Cost of New Generation Resources in the Annual Energy Outlook 2015

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantityBonneville Power Administration would likeUniverseIMPACTThousand CubicResourcelogo and-E C H N13, 2009 In reply refer

  8. Levelized Cost and Levelized Avoided Cost of New Generation Resources in the Annual Energy Outlook 2015

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantityBonneville Power Administration would likeUniverseIMPACTThousand CubicResourcelogo and-E C H N13, 2009 In reply refer June 2015

  9. Submission of Final Scientific/Technical Report [Solar Avoided Cost Solution: SunShot 6 Final Report

    SciTech Connect (OSTI)

    Danziger, Eric

    2014-01-29

    The core objectives of this project were two separate but integrated products, collectively providing game-changing Avoided Cost capabilities. • The first was a kit of avoided cost tools and data that any solar provider can use a-lacarte or as a whole. It’s open and easily accessible nature allows the rapid and accurate calculation of avoided cost in whatever context and software that make sense (“Typical and Avoided Cost Tools”). This kit includes a dataset of typical energy rates, costs and usage that can be used for solar prospecting, lead generation and any situation where data about an opportunity is missing or imperfect. • The second is a web application and related APIs specifically built for solar providers to radically streamline their lead-to-sale process (“Solar Provider Module”). The typical and Avoided Cost tools are built directly into this, and allow for solar providers to track their opportunities, collaborate with their installers and financiers, and close more sales faster.

  10. Cutting-Edge Savannah River Site Project Avoids Millions in Costs, Removes Chemical Solvents from Underground: Project avoided costs totaling more than $15 million, removed tons of chemical solvents from beneath the Savannah River Site

    Broader source: Energy.gov [DOE]

    AIKEN, S.C. – Workers recently completed a multiyear project that removed more than 33,000 gallons of non-radioactive chemical solvents from beneath a portion of the Savannah River Site (SRS), preventing those pollutants from entering the local water table and helping the site avoid costs of more than $15 million.

  11. Estimating the Economic Cost of Sea-Level Rise

    E-Print Network [OSTI]

    Sugiyama, Masahiro.

    To improve the estimate of economic costs of future sea-level rise associated with global climate change,

  12. Weighing the Costs and Benefits of Renewables Portfolio Standards: A Comparative Analysis of State-Level Policy Impact Projections

    E-Print Network [OSTI]

    Chen, Cliff; Wiser, Ryan; Bolinger, Mark

    2007-01-01

    projections of renewable technology cost, fossil fuel priceboth renewable technology costs and avoided fuel costs. Theof future renewable technology cost and performance would

  13. Production Cost Modeling for High Levels of Photovoltaics Penetration

    SciTech Connect (OSTI)

    Denholm, P.; Margolis, R.; Milford, J.

    2008-02-01

    The goal of this report is to evaluate the likely avoided generation, fuels, and emissions resulting from photovoltaics (PV) deployment in several U.S. locations and identify new tools, methods, and analysis to improve understanding of PV impacts at the grid level.

  14. Survey of State-Level Cost and Benefit Estimates of Renewable Portfolio Standards

    SciTech Connect (OSTI)

    Heeter, J.; Barbose, G.; Bird, L.; Weaver, S.; Flores-Espino, F.; Kuskova-Burns, K.; Wiser, R.

    2014-05-01

    Most renewable portfolio standards (RPS) have five or more years of implementation experience, enabling an assessment of their costs and benefits. Understanding RPS costs and benefits is essential for policymakers evaluating existing RPS policies, assessing the need for modifications, and considering new policies. This study provides an overview of methods used to estimate RPS compliance costs and benefits, based on available data and estimates issued by utilities and regulators. Over the 2010-2012 period, average incremental RPS compliance costs in the United States were equivalent to 0.8% of retail electricity rates, although substantial variation exists around this average, both from year-to-year and across states. The methods used by utilities and regulators to estimate incremental compliance costs vary considerably from state to state and a number of states are currently engaged in processes to refine and standardize their approaches to RPS cost calculation. The report finds that state assessments of RPS benefits have most commonly attempted to quantitatively assess avoided emissions and human health benefits, economic development impacts, and wholesale electricity price savings. Compared to the summary of RPS costs, the summary of RPS benefits is more limited, as relatively few states have undertaken detailed benefits estimates, and then only for a few types of potential policy impacts. In some cases, the same impacts may be captured in the assessment of incremental costs. For these reasons, and because methodologies and level of rigor vary widely, direct comparisons between the estimates of benefits and costs are challenging.

  15. Estimating the economic cost of sea-level rise

    E-Print Network [OSTI]

    Sugiyama, Masahiro, Ph. D. Massachusetts Institute of Technology

    2007-01-01

    (cont.) In the case of a classical linear sea-level rise of one meter per century, the use of DIVA generally decreases the protection fraction of the coastline, and results in a smaller protection cost because of high ...

  16. Amygdala norepinephrine levels after training predict inhibitory avoidance retention performance in rats

    E-Print Network [OSTI]

    O'Toole, Alice J.

    ) reported that b-adrenoceptor antagonists infused into the amygdala immediately after inhibitory avoidance-training infusions of the b-adrenoceptor antagonist propranolol into the amygdala also block the memory enhancement). Moreover, post-training, intra-amygdala infusions of NE produce dose-dependent enhancement of memory (Liang

  17. Levelized cost of coating (LCOC) for selective absorber materials.

    SciTech Connect (OSTI)

    Ho, Clifford Kuofei; Pacheco, James Edward

    2013-09-01

    A new metric has been developed to evaluate and compare selective absorber coatings for concentrating solar power applications. Previous metrics have typically considered the performance of the selective coating (i.e., solar absorptance and thermal emittance), but cost and durability were not considered. This report describes the development of the levelized cost of coating (LCOC), which is similar to the levelized cost of energy (LCOE) commonly used to evaluate alternative energy technologies. The LCOC is defined as the ratio of the annualized cost of the coating (and associated costs such as labor and number of heliostats required) to the average annual thermal energy produced by the receiver. The baseline LCOC using Pyromark 2500 paint was found to be %240.055/MWht, and the distribution of LCOC values relative to this baseline were determined in a probabilistic analysis to range from -%241.6/MWht to %247.3/MWht, accounting for the cost of additional (or fewer) heliostats required to yield the same baseline average annual thermal energy produced by the receiver. A stepwise multiple rank regression analysis showed that the initial solar absorptance was the most significant parameter impacting the LCOC, followed by thermal emittance, degradation rate, reapplication interval, and downtime during reapplication.

  18. A SURVEY OF STATE-LEVEL COST ESTIMATES OF RENEWABLES PORTFOLIO STANDARDS

    E-Print Network [OSTI]

    Barbose, Galen

    2014-01-01

    LEVEL COST ESTIMATES OF RENEWABLES PORTFOLIO STANDARDS Galenthe incremental cost of renewables portfolio standards (RPS)Washington DC have adopted renewables portfolio standards (

  19. NREL: Energy Analysis - Levelized Cost of Energy Calculator

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    distributed generation data used within this calculator. If you are seeking utility-scale technology cost and performance estimates, please visit the Transparent Cost Database...

  20. Analyzing the level of service and cost trade-offs in cold chain transportation

    E-Print Network [OSTI]

    Liu, Saiqi

    2009-01-01

    This thesis discusses the tradeoff between transportation cost and the level of service in cold chain transportation. Its purpose is to find the relationship between transportation cost and the level of service in cold ...

  1. Landscape level planning in alluvial riparian floodplain ecosystems: Using geomorphic modeling to avoid conflicts between human infrastructure and habitat conservation

    E-Print Network [OSTI]

    Larsen, Eric W; Girvetz, E H; Fremier, A K

    2007-01-01

    the pump will likely outweigh the costs and maintenance ofpumps, the long-term maintenance and management costs of

  2. Landscape level planning in alluvial riparian floodplain ecosystems: Using geomorphic modeling to avoid conflicts between human infrastructure and habitat conservation

    E-Print Network [OSTI]

    Larsen, Eric W; Girvetz, E H; Fremier, A K

    2007-01-01

    off-channel pumps, the long-term maintenance and managementthe pump will likely outweigh the costs and maintenance of

  3. Level of Repair Analysis and Minimum Cost Homomorphisms of Graphs

    E-Print Network [OSTI]

    Gutin, Gregory

    of Lillian Barros Abstract. Level of Repair Analysis (LORA) is a prescribed procedure for defence logistics, LORA seeks to determine an optimal provision of repair and maintenance facilities to minimize overall on bipartite graphs is polynomial time solvable. Keywords: Computational Logistics; Level of Repair Analysis

  4. A LOW COST WAFER-LEVEL MEMS PACKAGING TECHNOLOGY Pejman Monajemi, Paul J. Joseph*

    E-Print Network [OSTI]

    Ayazi, Farrokh

    A LOW COST WAFER-LEVEL MEMS PACKAGING TECHNOLOGY Pejman Monajemi, Paul J. Joseph* , Paul A. Kohl-cost low-temperature packaging technique for wafer-level encapsulation of MEMS devices fabricated on any arbitrary substrate. The packaging process presented here does not involve wafer bonding and can be applied

  5. Waste Management Facilities cost information for mixed low-level waste. Revision 1

    SciTech Connect (OSTI)

    Shropshire, D.; Sherick, M.; Biadgi, C.

    1995-06-01

    This report contains preconceptual designs and planning level life-cycle cost estimates for managing mixed low-level waste. The report`s information on treatment, storage, and disposal modules can be integrated to develop total life-cycle costs for various waste management options. A procedure to guide the US Department of Energy and its contractor personnel in the use of cost estimation data is also summarized in this report.

  6. levelized cost of energy | OpenEI Community

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on QA:QA J-E-1 SECTION J APPENDIX ECoop IncIowa (UtilityMichigan)data book Homefuelleasing Home Alevine'slevelized cost of

  7. Low-Cost Options for Moderate Levels of Mercury Control

    SciTech Connect (OSTI)

    Sharon Sjostrom

    2008-02-09

    This is the final technical report for a three-site project that is part of an overall program funded by the U.S. Department of Energy's National Energy Technology Laboratory (DOE/NETL) and industry partners to obtain the necessary information to assess the feasibility and costs of controlling mercury from coal-fired utility plants. This report summarizes results from tests conducted at MidAmerican's Louisa Generating Station and Entergy's Independence Steam Electric Station (ISES) and sorbent screening at MidAmerican's Council Bluffs Energy Center (CBEC) (subsequently renamed Walter Scott Energy Center (WSEC)). Detailed results for Independence and Louisa are presented in the respective Topical Reports. As no full-scale testing was conducted at CBEC, screening updates were provided in the quarterly updates to DOE. ADA-ES, Inc., with support from DOE/NETL, EPRI, and other industry partners, has conducted evaluations of EPRI's TOXECON II{trademark} process and of high-temperature reagents and sorbents to determine the capabilities of sorbent/reagent injection, including activated carbon, for mercury control on different coals and air emissions control equipment configurations. An overview of each plant configuration is presented: (1) MidAmerican's Louisa Generating Station burns Powder River Basin (PRB) coal in its 700-MW Unit 1 and employs hot-side electrostatic precipitators (ESPs) with flue gas conditioning for particulate control. This part of the testing program evaluated the effect of reagents used in the existing flue gas conditioning on mercury removal. (2) MidAmerican's Council Bluffs Energy Center typically burns PRB coal in its 88-MW Unit 2. It employs a hot-side ESP for particulate control. Solid sorbents were screened for hot-side injection. (3) Entergy's Independence Steam Electric Station typically burns PRB coal in its 880-MW Unit 2. Various sorbent injection tests were conducted on 1/8 to 1/32 of the flue gas stream either within or in front of one of four ESP boxes (SCA = 542 ft{sup 2}/kacfm), specifically ESP B. Initial mercury control evaluations indicated that although significant mercury control could be achieved by using the TOXECON II{trademark} design, the sorbent concentration required was higher than expected, possibly due to poor sorbent distribution. Subsequently, the original injection grid design was modeled and the results revealed that the sorbent distribution pattern was determined by the grid design, fluctuations in flue gas flow rates, and the structure of the ESP box. To improve sorbent distribution, the injection grid and delivery system were redesigned and the effectiveness of the redesigned system was evaluated. This project was funded through the DOE/NETL Innovations for Existing Plants program. It was a Phase II project with the goal of developing mercury control technologies that can achieve 50-70% mercury capture at costs 25-50% less than baseline estimates of $50,000-$70,000/lb of mercury removed. Results from testing at Independence indicate that the DOE goal was successfully achieved. Further improvements in the process are recommended, however. Results from testing at Louisa indicate that the DOE goal was not achievable using the tested high-temperature sorbent. Sorbent screening at Council Bluffs also indicated that traditional solid sorbents may not achieve significant mercury removal in hot-side applications.

  8. Derivation of a Levelized Cost of Coating (LCOC) metric for evaluation of solar selective absorber materials

    SciTech Connect (OSTI)

    Ho, C. K.; Pacheco, J. E.

    2015-06-05

    A new metric, the Levelized Cost of Coating (LCOC), is derived in this paper to evaluate and compare alternative solar selective absorber coatings against a baseline coating (Pyromark 2500). In contrast to previous metrics that focused only on the optical performance of the coating, the LCOC includes costs, durability, and optical performance for more comprehensive comparisons among candidate materials. The LCOC is defined as the annualized marginal cost of the coating to produce a baseline annual thermal energy production. Costs include the cost of materials and labor for initial application and reapplication of the coating, as well as the cost of additional or fewer heliostats to yield the same annual thermal energy production as the baseline coating. Results show that important factors impacting the LCOC include the initial solar absorptance, thermal emittance, reapplication interval, degradation rate, reapplication cost, and downtime during reapplication. The LCOC can also be used to determine the optimal reapplication interval to minimize the levelized cost of energy production. As a result, similar methods can be applied more generally to determine the levelized cost of component for other applications and systems.

  9. System level design enhancements for cost effective renewable power generation by reverse electrodialysis

    E-Print Network [OSTI]

    Weiner, Adam Michael

    2015-01-01

    Studies of the future competitiveness of reverse electrodialysis (RED) with other energy technologies show that the projected levelized cost of electricity realized through current stack designs is prohibitively high. ...

  10. Supplementary Information Potential for Electricity Generation from Renewable Resources and Levelized Cost of Electricity (LCOE)

    E-Print Network [OSTI]

    Suo, Zhigang

    Supplementary Information Potential for Electricity Generation from Renewable Resources and Levelized Cost of Electricity (LCOE) Electrical energy can be generated from renewable resources the potential to meet the worldwide demand of electricity and they contribute to the total generation

  11. Derivation of a Levelized Cost of Coating (LCOC) metric for evaluation of solar selective absorber materials

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Ho, C. K.; Pacheco, J. E.

    2015-06-05

    A new metric, the Levelized Cost of Coating (LCOC), is derived in this paper to evaluate and compare alternative solar selective absorber coatings against a baseline coating (Pyromark 2500). In contrast to previous metrics that focused only on the optical performance of the coating, the LCOC includes costs, durability, and optical performance for more comprehensive comparisons among candidate materials. The LCOC is defined as the annualized marginal cost of the coating to produce a baseline annual thermal energy production. Costs include the cost of materials and labor for initial application and reapplication of the coating, as well as the costmore »of additional or fewer heliostats to yield the same annual thermal energy production as the baseline coating. Results show that important factors impacting the LCOC include the initial solar absorptance, thermal emittance, reapplication interval, degradation rate, reapplication cost, and downtime during reapplication. The LCOC can also be used to determine the optimal reapplication interval to minimize the levelized cost of energy production. As a result, similar methods can be applied more generally to determine the levelized cost of component for other applications and systems.« less

  12. A Survey of State-Level Cost and Benefit Estimates of Renewable Portfolio Standards

    Broader source: Energy.gov [DOE]

    This report surveys and summarizes existing state-level RPS cost and benefit estimates and examines the various methods used to calculate such estimates. The report relies largely upon data or results reported directly by electric utilities and state regulators. As such, the estimated costs and benefits itemized in this document do not result from the application of a standardized approach or the use of a consistent set of underlying assumptions. Because the reported values may differ from those derived through a more consistent analytical treatment, we do not provide an aggregate national estimate of RPS costs and benefits, nor do we attempt to quantify net RPS benefits at national or state levels.

  13. Estimating costs of low-level radioactive waste disposal alternatives for the Commonwealth of Massachusetts

    SciTech Connect (OSTI)

    Not Available

    1994-02-01

    This report was prepared for the Commonwealth of Massachusetts by the Idaho National Engineering Laboratory, National Low-Level Waste Management Program. It presents planning life-cycle cost (PLCC) estimates for four sizes of in-state low-level radioactive waste (LLRW) disposal facilities. These PLCC estimates include preoperational and operational expenditures, all support facilities, materials, labor, closure costs, and long-term institutional care and monitoring costs. It is intended that this report bc used as a broad decision making tool for evaluating one of the several complex factors that must be examined when deciding between various LLRW management options -- relative costs. Because the underlying assumptions of these analyses will change as the Board decides how it will manage Massachusett`s waste and the specific characteristics any disposal facility will have, the results of this study are not absolute and should only be used to compare the relative costs of the options presented. The disposal technology selected for this analysis is aboveground earth-mounded vaults. These vaults are reinforced concrete structures where low-level waste is emplaced and later covered with a multi-layered earthen cap. The ``base case`` PLCC estimate was derived from a preliminary feasibility design developed for the Illinois Low-Level Radioactive Waste Disposal Facility. This PLCC report describes facility operations and details the procedure used to develop the base case PLCC estimate for each facility component and size. Sensitivity analyses were performed on the base case PLCC estimate by varying several factors to determine their influences upon the unit disposal costs. The report presents the results of the sensitivity analyses for the five most significant cost factors.

  14. Weighing the Costs and Benefits of State Renewables Portfolio Standards in the United States: A Comparative Analysis of State-Level Policy Impact Projections

    E-Print Network [OSTI]

    Chen, Cliff

    2009-01-01

    in electricity sector generation costs. In addition, the5/MWh change in levelized generation costs. We find that thethe cost and potential of renewable generation technologies

  15. Nuclear Fuel Recycling - the Value of the Separated Transuranics and the Levelized Cost of Electricity

    E-Print Network [OSTI]

    Parsons, John E.

    We analyze the levelized cost of electricity (LCOE) for three different fuel cycles: a Once-Through Cycle, in which the spent fuel is sent for disposal after one use in a reactor, a Twice-Through Cycle, in which the spent ...

  16. Estimating the economic cost of sea-level rise Masahiro Sugiyama

    E-Print Network [OSTI]

    Estimating the economic cost of sea-level rise by Masahiro Sugiyama Bachelor of Science in Earth Fulfillment of the Requirements for the Degree of Master of Science in Technology and Policy at the Massachusetts Institute of Technology February 2007 ©2007 Massachusetts Institute of Technology. All rights

  17. A system-level cost-of-energy wind farm layout optimization with landowner modeling

    SciTech Connect (OSTI)

    Chen, Le [Ames Laboratory; MacDonald, Erin [Ames Laboratory

    2013-10-01

    This work applies an enhanced levelized wind farm cost model, including landowner remittance fees, to determine optimal turbine placements under three landowner participation scenarios and two land-plot shapes. Instead of assuming a continuous piece of land is available for the wind farm construction, as in most layout optimizations, the problem formulation represents landowner participation scenarios as a binary string variable, along with the number of turbines. The cost parameters and model are a combination of models from the National Renewable Energy Laboratory (NREL), Lawrence Berkeley National Laboratory, and Windustiy. The system-level cost-of-energy (COE) optimization model is also tested under two land-plot shapes: equally-sized square land plots and unequal rectangle land plots. The optimal COEs results are compared to actual COE data and found to be realistic. The results show that landowner remittances account for approximately 10% of farm operating costs across all cases. Irregular land-plot shapes are easily handled by the model. We find that larger land plots do not necessarily receive higher remittance fees. The model can help site developers identify the most crucial land plots for project success and the optimal positions of turbines, with realistic estimates of costs and profitability. (C) 2013 Elsevier Ltd. All rights reserved.

  18. Low-cost household paint abatement to reduce children's blood lead levels

    SciTech Connect (OSTI)

    Taha, T.; Kanarek, M.S.; Schultz, B.D.; Murphy, A.

    1999-11-01

    The purpose was to examine the effectiveness of low-cost abatement on children's blood lead levels. Blood lead was analyzed before and after abatement in 37 homes of children under 7 years old with initial blood lead levels of 25--44 {micro}g/dL. Ninety-five percent of homes were built before 1950. Abatement methods used were wet-scraping and repainting deteriorated surfaces and wrapping window wells with aluminum or vinyl. A control group was retrospectively selected. Control children were under 7 years old, had initial blood lead levels of 25--44 {micro}g/dL and a follow-up level at least 28 days afterward, and did not have abatements performed in their homes between blood lead levels. After abatement, statistically significant declines occurred in the intervention children's blood lead levels. The mean decline was 22%, 1 to 6 months after treatment. After adjustment for seasonality and child's age, the mean decline was 6.0 {micro}g/dL, or 18%. The control children's blood levels did not decline significantly. There was a mean decline of 0.25 {micro}g/dL, or 0.39%. After adjustment for seasonality and age, the mean decline for control children was 1.6 {micro}g/dL, or 1.8%. Low-cost abatement and education are effective short-term interim controls.

  19. Analyzing the Levelized Cost of Centralized and Distributed Hydrogen Production Using the H2A Production Model, Version 2

    SciTech Connect (OSTI)

    Ramsden, T.; Steward, D.; Zuboy, J.

    2009-09-01

    Analysis of the levelized cost of producing hydrogen via different pathways using the National Renewable Energy Laboratory's H2A Hydrogen Production Model, Version 2.

  20. POPCYCLE: a computer code for calculating nuclear and fossil plant levelized life-cycle power costs

    SciTech Connect (OSTI)

    Hardie, R.W.

    1982-02-01

    POPCYCLE, a computer code designed to calculate levelized life-cycle power costs for nuclear and fossil electrical generating plants is described. Included are (1) derivations of the equations and a discussion of the methodology used by POPCYCLE, (2) a description of the input required by the code, (3) a listing of the input for a sample case, and (4) the output for a sample case.

  1. Wind Levelized Cost of Energy: A Comparison of Technical and Financing Input Variables

    SciTech Connect (OSTI)

    Cory, K.; Schwabe, P.

    2009-10-01

    The expansion of wind power capacity in the United States has increased the demand for project development capital. In response, innovative approaches to financing wind projects have emerged and are proliferating in the U.S. renewable energy marketplace. Wind power developers and financiers have become more efficient and creative in structuring their financial relationships, and often tailor them to different investor types and objectives. As a result, two similar projects may use very different cash flows and financing arrangements, which can significantly vary the economic competitiveness of wind projects. This report assesses the relative impact of numerous financing, technical, and operating variables on the levelized cost of energy (LCOE) associated with a wind project under various financing structures in the U.S. marketplace. Under this analysis, the impacts of several financial and technical variables on the cost of wind electricity generation are first examined individually to better understand the relative importance of each. Then, analysts examine a low-cost and a high-cost financing scenario, where multiple variables are modified simultaneously. Lastly, the analysis also considers the impact of a suite of financial variables versus a suite of technical variables.

  2. Evaluation of the Super ESPC Program: Level 2 -- Recalculated Cost Savings

    SciTech Connect (OSTI)

    Shonder, John A [ORNL; Hughes, Patrick [ORNL

    2009-04-01

    This report presents the results of Level 2 of a three-tiered evaluation of the U.S. Department of Energy Federal Energy Management Program's Super Energy Savings Performance Contract (Super ESPC) Program. Level 1 of the analysis studied all of the Super ESPC projects for which at least one Annual Measurement & Verification (M&V) Report had been produced by April 2006. For those 102 projects in aggregate, we found that the value of cost savings reported by the energy service company (ESCO) in the Annual M&V Reports was 108% of the cost savings guaranteed in the contracts. We also compared estimated energy savings (which are not guaranteed, but are the basis for the guaranteed cost savings) to the energy savings reported by the ESCO in the Annual M&V Report. In aggregate, reported energy savings were 99.8% of estimated energy savings on the basis of site energy, or 102% of estimated energy savings based on source energy. Level 2 focused on a random sample of 27 projects taken from the 102 Super ESPC projects studied in Level 1. The objectives were, for each project in the sample, to: repeat the calculations of the annual energy and cost savings in the most recent Annual M&V Report to validate the ESCO's results or correct any errors, and recalculate the value of the reported energy, water, and operations and maintenance (O&M) savings using actual utility prices paid at the project site instead of the 'contract' energy prices - the prices that are established in the project contract as those to be used by the ESCO to calculate the annual cost savings, which determine whether the guarantee has been met. Level 3 analysis will be conducted on three to five projects from the Level 2 sample that meet validity criteria for whole-building or whole-facility data analysis. This effort will verify energy and cost savings using statistical analysis of actual utility use, cost, and weather data. This approach, which can only be used for projects meeting particular validity criteria, is described in Shonder and Florita (2003) and Shonder and Hughes (2005). To address the first objective of the Level 2 analysis, we first assembled all the necessary information, and then repeated the ESCOs' calculations of reported annual cost savings. Only minor errors were encountered, the most common being the use of incorrect escalation rates to calculate utility prices or O&M savings. Altogether, our corrected calculations of the ESCO's reported cost savings were within 0.6% of the ESCOs' reported cost savings, and errors found were as likely to favor the government as they were the ESCO. To address the second objective, we gathered data on utility use and cost from central databases maintained by the Department of Defense and the General Services Administration, and directly from some of the sites, to determine the prices of natural gas and electricity actually paid at the sites during the periods addressed by the annual reports. We used these data to compare the actual utility costs at the sites to the contract utility prices. For natural gas, as expected, we found that prices had risen much faster than had been anticipated in the contracts. In 17 of the 18 projects for which the comparison was possible, contract gas prices were found to be lower than the average actual prices being paid. We conclude that overall in the program, the estimates of gas prices and gas price escalation rates used in the Super ESPC projects have been conservative. For electricity, it was possible to compare contract prices with the actual (estimated) marginal prices of electricity in 20 projects. In 14 of these projects, the overall contract electricity price was found to be lower than the marginal price of electricity paid to the serving utility. Thus it appears that conservative estimates of electricity prices and escalation rates have been used in the program as well. Finally we calculated the value of the reported energy savings using the prices of utilities actually paid by the sites instead of the contract prices. In 16 of the 22 projects (

  3. A COST-EFFECTIVE TWO-LEVEL ADAPTIVE BRANCH PREDICTOR STEVEN, G. B., EGAN, C., SHIM, W. VINTAN, L.

    E-Print Network [OSTI]

    Vintan, Lucian N.

    - 1 - A COST-EFFECTIVE TWO-LEVEL ADAPTIVE BRANCH PREDICTOR STEVEN, G. B., EGAN, C., SHIM, W. VINTAN.B.Steven@herts.ac.uk wonshim@duck.snut.ac.kr vintan@cs.sibiu.ro ABSTRACT During the 1990s Two-level Adaptive Branch Predictors processors. However, while two-level adaptive predictors achieve very high prediction rates, they tend

  4. Comparison of SRP high-level waste disposal costs for borosilicate glass and crystalline ceramic waste forms

    SciTech Connect (OSTI)

    McDonell, W R

    1982-04-01

    An evaluation of costs for the immobilization and repository disposal of SRP high-level wastes indicates that the borosilicate glass waste form is less costly than the crystalline ceramic waste form. The wastes were assumed immobilized as glass with 28% waste loading in 10,300 reference 24-in.-diameter canisters or as crystalline ceramic with 65% waste loading in either 3400 24-in.-diameter canisters or 5900 18-in.-diameter canisters. After an interim period of onsite storage, the canisters would be transported to the federal repository for burial. Total costs in undiscounted 1981 dollars of the waste disposal operations, excluding salt processing for which costs are not yet well defined, were about $2500 million for the borosilicate glass form in reference 24-in.-diameter canisters, compared to about $2900 million for the crystalline ceramic form in 24-in.-diameter canisters and about $3100 million for the crystalline ceramic form in 18-in.-diameter canisters. No large differences in salt processing costs for the borosilicate glass and crystalline ceramic forms are expected. Discounting to present values, because of a projected 2-year delay in startup of the DWPF for the crystalline ceramic form, preserved the overall cost advantage of the borosilicate glass form. The waste immobilization operations for the glass form were much less costly than for the crystalline ceramic form. The waste disposal operations, in contrast, were less costly for the crystalline ceramic form, due to fewer canisters requiring disposal; however, this advantage was not sufficient to offset the higher development and processing costs of the crystalline ceramic form. Changes in proposed Nuclear Regulatory Commission regulations to permit lower cost repository packages for defense high-level wastes would decrease the waste disposal costs of the more numerous borosilicate glass forms relative to the crystalline ceramic forms.

  5. Cost of stockouts in the microprocessor business and its impact in determining the optimal service level/

    E-Print Network [OSTI]

    Sonnet, Maria Claudia

    2005-01-01

    In order to develop optimal inventory policies, it is essential to know the consequences of stockouts and the costs related to each kind of stockout; at Intel, however, such costs have not yet been quantified. The primary ...

  6. A SURVEY OF STATE-LEVEL COST ESTIMATES OF RENEWABLES PORTFOLIO STANDARDS

    E-Print Network [OSTI]

    Barbose, Galen

    2014-01-01

    Energy Efficiency and Renewable Energy (Solar TechnologiesRPS costs, per unit of renewable energy generation, rangedFlores-Espino National Renewable Energy Laboratory 15013

  7. Randomized min-max optimization: the exact risk of multiple cost levels Algo Car`e, Simone Garatti, Marco C. Campi

    E-Print Network [OSTI]

    Garatti, Simone

    . Our goal is to evaluate the risks associated to the various costs, where the risk associated to a cost. This evaluation characterizes completely the risks associated to the costs, and represents a full-fledged resultRandomized min-max optimization: the exact risk of multiple cost levels Algo Car`e, Simone Garatti

  8. Realistic costs of carbon capture

    SciTech Connect (OSTI)

    Al Juaied, Mohammed . Belfer Center for Science and International Affiaris); Whitmore, Adam )

    2009-07-01

    There is a growing interest in carbon capture and storage (CCS) as a means of reducing carbon dioxide (CO2) emissions. However there are substantial uncertainties about the costs of CCS. Costs for pre-combustion capture with compression (i.e. excluding costs of transport and storage and any revenue from EOR associated with storage) are examined in this discussion paper for First-of-a-Kind (FOAK) plant and for more mature technologies, or Nth-of-a-Kind plant (NOAK). For FOAK plant using solid fuels the levelised cost of electricity on a 2008 basis is approximately 10 cents/kWh higher with capture than for conventional plants (with a range of 8-12 cents/kWh). Costs of abatement are found typically to be approximately US$150/tCO2 avoided (with a range of US$120-180/tCO2 avoided). For NOAK plants the additional cost of electricity with capture is approximately 2-5 cents/kWh, with costs of the range of US$35-70/tCO2 avoided. Costs of abatement with carbon capture for other fuels and technologies are also estimated for NOAK plants. The costs of abatement are calculated with reference to conventional SCPC plant for both emissions and costs of electricity. Estimates for both FOAK and NOAK are mainly based on cost data from 2008, which was at the end of a period of sustained escalation in the costs of power generation plant and other large capital projects. There are now indications of costs falling from these levels. This may reduce the costs of abatement and costs presented here may be 'peak of the market' estimates. If general cost levels return, for example, to those prevailing in 2005 to 2006 (by which time significant cost escalation had already occurred from previous levels), then costs of capture and compression for FOAK plants are expected to be US$110/tCO2 avoided (with a range of US$90-135/tCO2 avoided). For NOAK plants costs are expected to be US$25-50/tCO2. Based on these considerations a likely representative range of costs of abatement from CCS excluding transport and storage costs appears to be US$100-150/tCO2 for first-of-a-kind plants and perhaps US$30-50/tCO2 for nth-of-a-kind plants.The estimates for FOAK and NOAK costs appear to be broadly consistent in the light of estimates of the potential for cost reductions with increased experience. Cost reductions are expected from increasing scale, learning on individual components, and technological innovation including improved plant integration. Innovation and integration can both lower costs and increase net output with a given cost base. These factors are expected to reduce abatement costs by approximately 65% by 2030. The range of estimated costs for NOAK plants is within the range of plausible future carbon prices, implying that mature technology would be competitive with conventional fossil fuel plants at prevailing carbon prices.

  9. Communication Avoiding and Overlapping for Numerical Linear Algebra

    E-Print Network [OSTI]

    Tourińo, Juan

    Communication Avoiding and Overlapping for Numerical Linear Algebra Evangelos Georganas1, Jorge exascale systems, communication cost must be avoided or overlapped. Communication-avoiding 2.5D algorithms. Communication overlap attempts to hide messaging latency by pipelining messages and overlapping

  10. Cost Savings and Energy Reduction: Bi-Level Lighting Retrofits in Multifamily Buildings 

    E-Print Network [OSTI]

    Ackley, J.

    2010-01-01

    through installation of Bi-Level Lighting systems. The results of this report demonstrate that common areas that are currently not making use of Bi-Level lighting systems would achieve significant financial and environmental benefits from Bi-Level focused...

  11. Electric power high-voltage transmission lines: Design options, cost, and electric and magnetic field levels

    SciTech Connect (OSTI)

    Stoffel, J.B.; Pentecost, E.D.; Roman, R.D.; Traczyk, P.A.

    1994-11-01

    This report provides background information about (1) the electric and magnetic fields (EMFs) of high-voltage transmission lines at typical voltages and line configurations and (2) typical transmission line costs to assist on alternatives in environmental documents. EMF strengths at 0 {+-} 200 ft from centerline were calculated for ac overhead lines, and for 345 and 230-kV ac underground line and for a {+-}450-kV dc overhead line. Compacting and height sensitivity factors were computed for the variation in EMFs when line conductors are moved closer or raised. Estimated costs for the lines are presented and discussed so that the impact of using alternative strategies for reducing EMF strengths and the implications of implementing the strategies can be better appreciated.

  12. Weighing the Costs and Benefits of Renewables Portfolio Standards: A Comparative Analysis of State-Level Policy Impact Projections

    E-Print Network [OSTI]

    Chen, Cliff; Wiser, Ryan; Bolinger, Mark

    2007-01-01

    factors: wind power capital costs and natural gas prices.key assumptions – wind capital cost and the duration of PTC47 7.3.2 Wind Capital Cost

  13. Weighing the Costs and Benefits of Renewables Portfolio Standards: A Comparative Analysis of State-Level Policy Impact Projections

    E-Print Network [OSTI]

    Chen, Cliff; Wiser, Ryan; Bolinger, Mark

    2007-01-01

    to RPS generation requirements, wind cost assumptions arethe sudden leap in wind costs over the past several years,especially if higher wind costs persist. However, most, if

  14. Weighing the Costs and Benefits of Renewables Portfolio Standards: A Comparative Analysis of State-Level Policy Impact Projections

    E-Print Network [OSTI]

    Chen, Cliff; Wiser, Ryan; Bolinger, Mark

    2007-01-01

    resource types and generation costs are estimated externallystudy reports cost and renewable generation results for thestudy reports cost and renewable generation results for the

  15. Reevaluation Of Vitrified High-Level Waste Form Criteria For Potential Cost Savings At The Defense Waste Processing Facility

    SciTech Connect (OSTI)

    Ray, J. W.; Marra, S. L.; Herman, C. C.

    2013-01-09

    At the Savannah River Site (SRS) the Defense Waste Processing Facility (DWPF) has been immobilizing SRS's radioactive high level waste (HLW) sludge into a durable borosilicate glass since 1996. Currently the DWPF has poured over 3,500 canisters, all of which are compliant with the U. S. Department of Energy's (DOE) Waste Acceptance Product Specifications for Vitrified High-Level Waste Forms (WAPS) and therefore ready to be shipped to a federal geologic repository for permanent disposal. Due to DOE petitioning to withdraw the Yucca Mountain License Application (LA) from the Nuclear Regulatory Commission (NRC) in 2010 and thus no clear disposal path for SRS canistered waste forms, there are opportunities for cost savings with future canister production at DWPF and other DOE producer sites by reevaluating high-level waste form requirements and compliance strategies and reducing/eliminating those that will not negatively impact the quality of the canistered waste form.

  16. Reevaluation of Vitrified High-Level Waste Form Criteria for Potential Cost Savings at the Defense Waste Processing Facility - 13598

    SciTech Connect (OSTI)

    Ray, J.W. [Savannah River Remediation (United States)] [Savannah River Remediation (United States); Marra, S.L.; Herman, C.C. [Savannah River National Laboratory, Savannah River Site, Aiken, SC 29808 (United States)] [Savannah River National Laboratory, Savannah River Site, Aiken, SC 29808 (United States)

    2013-07-01

    At the Savannah River Site (SRS) the Defense Waste Processing Facility (DWPF) has been immobilizing SRS's radioactive high level waste (HLW) sludge into a durable borosilicate glass since 1996. Currently the DWPF has poured over 3,500 canisters, all of which are compliant with the U. S. Department of Energy's (DOE) Waste Acceptance Product Specifications for Vitrified High-Level Waste Forms (WAPS) and therefore ready to be shipped to a federal geologic repository for permanent disposal. Due to DOE petitioning to withdraw the Yucca Mountain License Application (LA) from the Nuclear Regulatory Commission (NRC) in 2010 and thus no clear disposal path for SRS canistered waste forms, there are opportunities for cost savings with future canister production at DWPF and other DOE producer sites by reevaluating high-level waste form requirements and compliance strategies and reducing/eliminating those that will not negatively impact the quality of the canistered waste form. (authors)

  17. Weighing the Costs and Benefits of Renewables Portfolio Standards: A Comparative Analysis of State-Level Policy Impact Projections

    E-Print Network [OSTI]

    Chen, Cliff; Wiser, Ryan; Bolinger, Mark

    2007-01-01

    of Alternative Fossil Fuel Price and Carbon Regulationtechnology cost, fossil fuel price uncertainty, andtechnology cost, fossil fuel price uncertainty, and

  18. Cost savings associated with landfilling wastes containing very low levels of uranium

    SciTech Connect (OSTI)

    Boggs, C.J. [Argonne National Lab., Germantown, MD (United States); Shaddoan, W.T. [Lockheed Martin Energy Systems, Paducah, KY (United States)

    1996-03-01

    The Paducah Gaseous Diffusion Plant (PGDP) has operated captive landfills (both residential and construction/demolition debris) in accordance with the Commonwealth of Kentucky regulations since the early 1980s. Typical waste streams allowed in these landfills include nonhazardous industrial and municipal solid waste (such as paper, plastic, cardboard, cafeteria waste, clothing, wood, asbestos, fly ash, metals, and construction debris). In July 1992, the U.S. Environmental Protection Agency issued new requirements for the disposal of sanitary wastes in a {open_quotes}contained landfill.{close_quotes} These requirements were promulgated in the 401 Kentucky Administrative Record Chapters 47 and 48 that became effective 30 June 1995. The requirements for a new contained landfill include a synthetic liner made of high-density polyethylene in addition to the traditional 1-meter (3-foot) clay liner and a leachate collection system. A new landfill at Paducah would accept waste streams similar to those that have been accepted in the past. The permit for the previously existing landfills did not include radioactivity limits; instead, these levels were administratively controlled. Typically, if radioactivity was detected above background levels, the waste was classified as low-level waste (LLW), which would be sent off-site for disposal.

  19. Weighing the Costs and Benefits of Renewables Portfolio Standards: A Comparative Analysis of State-Level Policy Impact Projections

    E-Print Network [OSTI]

    Chen, Cliff; Wiser, Ryan; Bolinger, Mark

    2007-01-01

    impacts We converted other cost metrics to ˘/kWh retail ratePower System Operating Costs: Summary and Perspective onA. Bibliography of RPS Cost Studies Studies listed in

  20. Weighing the Costs and Benefits of Renewables Portfolio Standards: A Comparative Analysis of State-Level Policy Impact Projections

    E-Print Network [OSTI]

    Chen, Cliff; Wiser, Ryan; Bolinger, Mark

    2007-01-01

    45 7.3 Renewable Energy Costand future renewable energy costs, while less volatile thanResource Data Renewable Energy Cost Characterization

  1. The Outlook for CO2 Capture Costs

    E-Print Network [OSTI]

    Common Measures of CCS Cost · Capital cost · Increased cost of electricity · Cost of CO2 avoided · Cost of CO2 captured E.S. Rubin, Carnegie Mellon Elements of Capital Cost Note: · Nomenclature and cost items construction Total Capital Requirement (TCR) E.S. Rubin, Carnegie Mellon Cost of Electricity (COE) COE ($/MWh

  2. Weighing the Costs and Benefits of Renewables Portfolio Standards: A Comparative Analysis of State-Level Policy Impact Projections

    E-Print Network [OSTI]

    Chen, Cliff; Wiser, Ryan; Bolinger, Mark

    2007-01-01

    or clean energy policies, unless RPS-specific costs areCost Impacts of a Vermont Renewable Energy Portfolio Standard Economics of a Washington Energy Portfolio Standard: Effects on Ratepayers The Washington Clean Energy

  3. Environmental benefits and cost savings through market-based instruments : an application using state-level data from India

    E-Print Network [OSTI]

    Gupta, Shreekant

    2002-01-01

    This paper develops a methodology for estimating potential cost savings from the use of market-based instruments (MBIs) when local emissions and abatement cost data are not available. The paper provides estimates of the ...

  4. Integrating Volume Reduction and Packaging Alternatives to Achieve Cost Savings for Low Level Waste Disposal at the Rocky Flats Environmental Technology Site

    SciTech Connect (OSTI)

    Church, A.; Gordon, J.; Montrose, J. K.

    2002-02-26

    In order to reduce costs and achieve schedules for Closure of the Rocky Flats Environmental Technology Site (RFETS), the Waste Requirements Group has implemented a number of cost saving initiatives aimed at integrating waste volume reduction with the selection of compliant waste packaging methods for the disposal of RFETS low level radioactive waste (LLW). Waste Guidance Inventory and Shipping Forecasts indicate that over 200,000 m3 of low level waste will be shipped offsite between FY2002 and FY2006. Current projections indicate that the majority of this waste will be shipped offsite in an estimated 40,000 55-gallon drums, 10,000 metal and plywood boxes, and 5000 cargo containers. Currently, the projected cost for packaging, shipment, and disposal adds up to $80 million. With these waste volume and cost projections, the need for more efficient and cost effective packaging and transportation options were apparent in order to reduce costs and achieve future Site packaging a nd transportation needs. This paper presents some of the cost saving initiatives being implemented for waste packaging at the Rocky Flats Environmental Technology Site (the Site). There are many options for either volume reduction or alternative packaging. Each building and/or project may indicate different preferences and/or combinations of options.

  5. Estimating Renewable Energy Costs

    Broader source: Energy.gov [DOE]

    Some renewable energy measures, such as daylighting, passive solar heating, and cooling load avoidance, do not add much to the cost of a building. However, renewable energy technologies typically...

  6. Weighing the Costs and Benefits of Renewables Portfolio Standards: A Comparative Analysis of State-Level Policy Impact Projections

    E-Print Network [OSTI]

    Chen, Cliff; Wiser, Ryan; Bolinger, Mark

    2007-01-01

    on Average Retail Electricity Rates.. 14Projected RPS Electricity Rate Impacts by RPS CostRPS Targets and Retail Electricity Rate Impacts 16 Typical

  7. Weighing the Costs and Benefits of Renewables Portfolio Standards: A Comparative Analysis of State-Level Policy Impact Projections

    E-Print Network [OSTI]

    Chen, Cliff; Wiser, Ryan; Bolinger, Mark

    2007-01-01

    wholesale electricity price projections as a model output.in natural gas prices projections over the past severalprojections of renewable technology cost, fossil fuel price

  8. Weighing the Costs and Benefits of Renewables Portfolio Standards: A Comparative Analysis of State-Level Policy Impact Projections

    E-Print Network [OSTI]

    Chen, Cliff; Wiser, Ryan; Bolinger, Mark

    2007-01-01

    detailed wholesale electricity price projections as a modelelectricity bills, and renewable energy certificate (REC) prices. Developing a consistent set of metrics for comparing cost projections

  9. Levelized life-cycle costs for four residue-collection systems and four gas-production systems

    SciTech Connect (OSTI)

    Thayer, G.R.; Rood, P.L.; Williamson, K.D. Jr.; Rollett, H.

    1983-01-01

    Technology characterizations and life-cycle costs were obtained for four residue-collection systems and four gas-production systems. All costs are in constant 1981 dollars. The residue-collection systems were cornstover collection, wheat-straw collection, soybean-residue collection, and wood chips from forest residue. The life-cycle costs ranged from $19/ton for cornstover collection to $56/ton for wood chips from forest residues. The gas-production systems were low-Btu gas from a farm-size gasifier, solar flash pyrolysis of biomass, methane from seaweed farms, and hydrogen production from bacteria. Life-cycle costs ranged from $3.3/10/sup 6/ Btu for solar flash pyrolysis of biomass to $9.6/10/sup 6/ Btu for hydrogen from bacteria. Sensitivity studies were also performed for each system. The sensitivity studies indicated that fertilizer replacement costs were the dominate costs for the farm-residue collection, while residue yield was most important for the wood residue. Feedstock costs were most important for the flash pyrolysis. Yields and capital costs are most important for the seaweed farm and the hydrogen from bacteria system.

  10. Weighing the Costs and Benefits of State Renewables Portfolio Standards in the United States: A Comparative Analysis of State-Level Policy Impact Projections

    E-Print Network [OSTI]

    Chen, Cliff

    2009-01-01

    and future renewable energy costs, while less volatile thandifference between renewable energy costs and the cost ofto be the least-cost renewable energy source and, as noted

  11. Avoiding Predation Two Ways to Avoid Getting Eaten

    E-Print Network [OSTI]

    Brown, Christopher A.

    boatmen avoid areas with cannibalistic adults Forage in lower quality parts of pond #12;2 Predator tail-flagging and stotting Clockwise from left: monarch caterpillar; yellowjackets; giant mesquite bugs

  12. ISSUE PAPER METHANE AVOIDANCE FROM

    E-Print Network [OSTI]

    Brown, Sally

    ISSUE PAPER METHANE AVOIDANCE FROM COMPOSTING An Issue Paper for the: Climate Action Reserve...........................................................................................................39 6.2. Standard Methods for Quantifying Methane from Organic Waste in Landfills...40 6.3. GHG

  13. Vision-based obstacle avoidance

    DOE Patents [OSTI]

    Galbraith, John (Los Alamos, NM)

    2006-07-18

    A method for allowing a robot to avoid objects along a programmed path: first, a field of view for an electronic imager of the robot is established along a path where the electronic imager obtains the object location information within the field of view; second, a population coded control signal is then derived from the object location information and is transmitted to the robot; finally, the robot then responds to the control signal and avoids the detected object.

  14. This is a preprint of the following article, which is available from http://mdolab.engin.umich.edu/content/ multidisciplinary-design-optimization-offshore-wind-turbines-minimum-levelized-cost-energy. The published

    E-Print Network [OSTI]

    Papalambros, Panos

    ://mdolab.engin.umich.edu/content/ multidisciplinary-design-optimization-offshore-wind-turbines-minimum-levelized-cost-energy. The published article.A.M. van Kuik. Multidisciplinary Design Optimization of Offshore Wind Turbines for Minimum Levelized Cost of Energy. Renewable Energy (In press), 2014 Multidisciplinary Design Optimization of Offshore Wind Turbines

  15. Weighing the Costs and Benefits of State Renewables Portfolio Standards in the United States: A Comparative Analysis of State-Level Policy Impact Projections

    E-Print Network [OSTI]

    Chen, Cliff

    2009-01-01

    would stimulate wind technology cost reductions on theprojections of renewable technology costs, fossil fuel priceavailability. Renewable technology cost: Reflects changes to

  16. Weighing the Costs and Benefits of State Renewables Portfolio Standards in the United States: A Comparative Analysis of State-Level Policy Impact Projections

    E-Print Network [OSTI]

    Chen, Cliff

    2009-01-01

    New Jersey “high technology cost” scenario, which exceedsthan-expected solar technology costs would probably causeAvailability Renew able Technology Cost Fossil Fuel Price

  17. Constrained Nonlinear Control Allocation with Singularity Avoidance using Sequential Quadratic

    E-Print Network [OSTI]

    Johansen, Tor Arne

    of this paper is that the cost function used for optimizing control allocation includes a term that penalizes1 Constrained Nonlinear Control Allocation with Singularity Avoidance using Sequential Quadratic Programming Tor A. JohansenŁ , Thor I. FossenŁ and Svein P. BergeŁŁ Abstract-- Control allocation problems can

  18. Avoiding Lexical Ambiguities: Does Prior Experience Help? 

    E-Print Network [OSTI]

    Burns, Rebecca

    2008-06-27

    This study examined whether speakers avoid lexical ambiguities in a communication task by avoiding ambiguous descriptions when two interpretations are plausible and, furthermore, whether this avoidance is increased after ...

  19. Communication-avoiding Krylov subspace methods

    E-Print Network [OSTI]

    Hoemmen, Mark

    2010-01-01

    3.1.3 Avoiding communication in Arnoldi . . . . .CONTENTS iii 3 Communication-avoiding Arnoldi and GMRES 3.1CA-Lanczos . . 5 Communication-avoiding CG 5.1 Conjugate

  20. Weighing the Costs and Benefits of State Renewables Portfolio Standards in the United States: A Comparative Analysis of State-Level Policy Impact Projections

    E-Print Network [OSTI]

    Chen, Cliff

    2009-01-01

    Cost Studies en al ty CO2 Reduction Cost in 1st Peak Targetdo not represent the average costs of CO2 abatement over theestimated CO2 reductions. Since these are single-year costs,

  1. MLA Citation Style AVOIDING PLAGIARISM

    E-Print Network [OSTI]

    Kunkle, Tom

    MLA Citation Style AVOIDING PLAGIARISM The Definition of Plagiarism: According to the MLA Handbook for punctuation mark, etc. from the source. When you begin writing your paper, you will have to be selective in choosing your material, and you will have to give credit to the source of the material--whether summarized

  2. Study Traps Avoid to Succeed

    E-Print Network [OSTI]

    Kunkle, Tom

    Study Traps Avoid to Succeed Study traps are all around you! If you have found yourself saying any. Interrupt study time with planned breaks. Begin studying early, but increase study time as exams approach. "I've got so much to study... and so little time." Preview and skim your reading! Read chapter

  3. Aging in Utah: Avoid Crisis

    E-Print Network [OSTI]

    Tipple, Brett

    Aging in Utah: Avoid Crisis Maximize Opportunity UTAH COMMISSION ON AGING Annual Report 2010-2011 #12;Page 1Utah Commission on Aging 2010-2011 Interim Report The Commission's statutory purpose is to: a. increase public and government understanding of the current and future needs of the state's aging

  4. Life-Cycle Cost and Risk Analysis of Alternative Configurations for Shipping Low-Level Radioactive Waste to the Nevada Test Site

    SciTech Connect (OSTI)

    PM Daling; SB Ross; BM Biwer

    1999-12-17

    The Nevada Test Site (NTS) is a major receiver of low-level radioactive waste (LLW) for disposal. Currently, all LLW received at NTS is shipped by truck. The trucks use highway routes to NTS that pass through the Las Vegas Valley and over Hoover Dam, which is a concern of local stakeholder groups in the State of Nevada. Rail service offers the opportunity to reduce transportation risks and costs, according to the Waste Management Programmatic Environmental Impact Statement (WM-PEIS). However, NTS and some DOE LLW generator sites are not served with direct rail service so intermodal transport is under consideration. Intermodal transport involves transport via two modes, in this case truck and rail, from the generator sites to NTS. LLW shipping containers would be transferred between trucks and railcars at intermodal transfer points near the LLW generator sites, NTS, or both. An Environmental Assessment (EA)for Intermodal Transportation of Low-Level Radioactive Waste to the Nevada Test Site (referred to as the NTSIntermodal -M) has been prepared to determine whether there are environmental impacts to alterations to the current truck routing or use of intermodal facilities within the State of Nevada. However, an analysis of the potential impacts outside the State of Nevada are not addressed in the NTS Intermodal EA. This study examines the rest of the transportation network between LLW generator sites and the NTS and evaluates the costs, risks, and feasibility of integrating intermodal shipments into the LLW transportation system. This study evaluates alternative transportation system configurations for NTS approved and potential generators based on complex-wide LLW load information. Technical judgments relative to the availability of DOE LLW generators to ship from their sites by rail were developed. Public and worker risk and life-cycle cost components are quantified. The study identifies and evaluates alternative scenarios that increase the use of rail (intermodal where needed) to transport LLW from generator sites to NTS.

  5. Effects of protein and energy levels during the growing and laying periods on performance and egg production costs 

    E-Print Network [OSTI]

    Santana, Jose

    1968-01-01

    Ih O O I IA I O o 0' V V V V Al F! I nlI 0 o 0 0 a J2 nl 0 C4 H 0 I! I! IA O nl A u nl nl nl W A nl A nl nl I! Cl 4 W W 0 0 V 0 '0 cl nl u u V II nl Sl nl nl In n! nl m M nl g A CI CI nl ~ In 28... of diet to pullets from 8 to 21 weeks of age, combined with an all-mash and a mash plus unground milo free choice feeding system, in a factorial arrangement (3xZx2) had no effect on body weight, level of peak production or egg size during the laying...

  6. Weighing the Costs and Benefits of State Renewables Portfolio Standards in the United States: A Comparative Analysis of State-Level Policy Impact Projections

    E-Print Network [OSTI]

    Chen, Cliff

    2009-01-01

    Notable is that current wind costs are in the $1600-2000/kWin place. As a result, the wind cost assumptions employed inespecially if higher wind costs persist. Natural Gas Price

  7. Weighing the Costs and Benefits of State Renewables Portfolio Standards in the United States: A Comparative Analysis of State-Level Policy Impact Projections

    E-Print Network [OSTI]

    Chen, Cliff

    2009-01-01

    technology costs, fossil fuel price uncertainty, alternativeand performance assumptions. Fossil fuel price uncertainty:able Technology Cost Fossil Fuel Price Uncertainty Alternate

  8. Flight Test Evaluation of a Prototype Optical Instrument for Airborne Sense-and-Avoid Applications

    E-Print Network [OSTI]

    Hornsey, Richard

    Flight Test Evaluation of a Prototype Optical Instrument for Airborne Sense-and-Avoid Applications sense-and-avoid instrument was constructed from low-cost commercial off-the- shelf components 205 and the Bell 206 (intruder aircraft) were fully instrumented to record position and orientation

  9. Obstacle-avoiding navigation system

    DOE Patents [OSTI]

    Borenstein, Johann (Ann Arbor, MI); Koren, Yoram (Ann Arbor, MI); Levine, Simon P. (Ann Arbor, MI)

    1991-01-01

    A system for guiding an autonomous or semi-autonomous vehicle through a field of operation having obstacles thereon to be avoided employs a memory for containing data which defines an array of grid cells which correspond to respective subfields in the field of operation of the vehicle. Each grid cell in the memory contains a value which is indicative of the likelihood, or probability, that an obstacle is present in the respectively associated subfield. The values in the grid cells are incremented individually in response to each scan of the subfields, and precomputation and use of a look-up table avoids complex trigonometric functions. A further array of grid cells is fixed with respect to the vehicle form a conceptual active window which overlies the incremented grid cells. Thus, when the cells in the active window overly grid cell having values which are indicative of the presence of obstacles, the value therein is used as a multiplier of the precomputed vectorial values. The resulting plurality of vectorial values are summed vectorially in one embodiment of the invention to produce a virtual composite repulsive vector which is then summed vectorially with a target-directed vector for producing a resultant vector for guiding the vehicle. In an alternative embodiment, a plurality of vectors surrounding the vehicle are computed, each having a value corresponding to obstacle density. In such an embodiment, target location information is used to select between alternative directions of travel having low associated obstacle densities.

  10. Avoiding Lexical Ambiguities: Does Prior Experience Help? 

    E-Print Network [OSTI]

    Nierop, Katharine

    2008-06-27

    The present study examined whether speakers avoided the production of lexically ambiguous target labels in a referential communication task (e.g., avoiding the ambiguous bare homophone mouse when pictures of both a computer ...

  11. Startup Costs

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    This chapter discusses startup costs for construction and environmental projects, and estimating guidance for startup costs.

  12. Motivation Examples Star Avoiding Ramsey Numbers

    E-Print Network [OSTI]

    Isaak, Garth

    Motivation Examples Star Avoiding Ramsey Numbers Jonelle Hook, Garth Isaak Department and Cryptography Jonelle Hook, Garth Isaak Star Avoiding Ramsey Numbers #12;Motivation Examples Graph Ramsey-coloring of K13 has a red C5 or a blue K4. Jonelle Hook, Garth Isaak Star Avoiding Ramsey Numbers #12

  13. Energy Efficiency Improvement and Cost Saving Oportunities for the Concrete Industry

    E-Print Network [OSTI]

    Kermeli, Katerina

    2013-01-01

    concrete Process Water Multiple low volume drum washoutsconcrete is reused, disposal costs avoided and water use for truck washout

  14. Weighing the Costs and Benefits of State Renewables Portfolio Standards in the United States: A Comparative Analysis of State-Level Policy Impact Projections

    E-Print Network [OSTI]

    Chen, Cliff

    2009-01-01

    clean_energy_policies/increase-wisconsin- rps.html Table 1. State RPS Policies as Modeled by RPS Cost

  15. Avoid Nuisance Tripping with Premium Efficiency Motors

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Avoid Nuisance Tripping with Premium Efficiency Motors In most cases, upgrading to premium efficiency motors has no noticeable impact on the electrical system. However, in rare...

  16. Weighing the Costs and Benefits of State Renewables Portfolio Standards in the United States: A Comparative Analysis of State-Level Policy Impact Projections

    E-Print Network [OSTI]

    Chen, Cliff

    2009-01-01

    cost studies project retail electricity rate increases of nochanges in retail electricity rates, and (2) monthlydeployment on retail electricity rates and bills. Direct

  17. Operating Costs Estimates Cost Indices

    E-Print Network [OSTI]

    Boisvert, Jeff

    cost projections · Chemical Engineering (CE) Plant Construction Cost Index ­ Base value = 100 in 1957.0 in 2Q 2001 · Engineering News Record (ENR) · Nelson Refinery (NR) Construction Cost Index Cost Indices available for estimation are based upon the past · These data must be updated using cost indexes . · Cost

  18. Avoiding Mold Hazards In Your Flooded Home

    E-Print Network [OSTI]

    Avoiding Mold Hazards In Your Flooded Home A flood-damaged home requires special attention to avoid or correct a mold population explosion. Mold is likely to multiply on materials that stay wet for more than two or three days. The longer mold is allowed to grow, the greater the hazard and the harder

  19. Technical and economic assessments of electrochemical energy storage systems: Topical report on the potential for savings in load-leveling battery and balance of plant costs

    SciTech Connect (OSTI)

    Abraham, J.; Binas, G.; Del Monaco, J.L.; Pandya, D.A.; Sharp, T.E.; Consiglio, J.A.

    1985-08-31

    The battery technologies considered in this study are zinc-bromide, lead-acid, zinc-chloride and sodium sulfur. Results of the study are presented in self contained sections in the following order: Balance of Plant, Zinc-Bromide, Lead-Acid, Zinc-chloride, and Sodium-Sulfur. The balance of plant cost estimates are examined first since the results of this section are utilized in the following battery sections to generate cost reductions in the battery plant costs for each of the battery technologies.

  20. Abstract--In this paper, we present an collision avoidance algorithm for unmanned aerial vehicles (UAVs) based on model

    E-Print Network [OSTI]

    Sastry, S. Shankar

    Abstract-- In this paper, we present an collision avoidance algorithm for unmanned aerial vehicles in a head-on collision scenario using unmanned aerial vehicles. I. INTRODUCTION HE concept of a highly to avoid the impending collision at all cost. During this procedure, the unmanned vehicle must compute

  1. Statistics on pattern-avoiding permutations

    E-Print Network [OSTI]

    Elizalde, Sergi, 1979-

    2004-01-01

    This thesis concerns the enumeration of pattern-avoiding permutations with respect to certain statistics. Our first result is that the joint distribution of the pair of statistics 'number of fixed points' and 'number of ...

  2. SAVING MONEY & TIME (EFFICIENCY) UTILITY COST AVOIDANCE: From FY 2001 through FY2012, the UW Seattle campus has avoided

    E-Print Network [OSTI]

    Van Volkenburgh, Elizabeth

    : SmartGrid ­ Electrical meters are installed in all Seattle campus buildings and metering data is now with the College of Engineering, Battelle, Bonneville Power Administration, McKinstry and Seattle City Light. http

  3. Operating Costs

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    This chapter is focused on capital costs for conventional construction and environmental restoration and waste management projects and examines operating cost estimates to verify that all elements of the project have been considered and properly estimated.

  4. Transmission line capital costs

    SciTech Connect (OSTI)

    Hughes, K.R.; Brown, D.R.

    1995-05-01

    The displacement or deferral of conventional AC transmission line installation is a key benefit associated with several technologies being developed with the support of the U.S. Department of Energy`s Office of Energy Management (OEM). Previous benefits assessments conducted within OEM have been based on significantly different assumptions for the average cost per mile of AC transmission line. In response to this uncertainty, an investigation of transmission line capital cost data was initiated. The objective of this study was to develop a database for preparing preliminary estimates of transmission line costs. An extensive search of potential data sources identified databases maintained by the Bonneville Power Administration (BPA) and the Western Area Power Administration (WAPA) as superior sources of transmission line cost data. The BPA and WAPA data were adjusted to a common basis and combined together. The composite database covers voltage levels from 13.8 to 765 W, with cost estimates for a given voltage level varying depending on conductor size, tower material type, tower frame type, and number of circuits. Reported transmission line costs vary significantly, even for a given voltage level. This can usually be explained by variation in the design factors noted above and variation in environmental and land (right-of-way) costs, which are extremely site-specific. Cost estimates prepared from the composite database were compared to cost data collected by the Federal Energy Regulatory Commission (FERC) for investor-owned utilities from across the United States. The comparison was hampered because the only design specifications included with the FERC data were voltage level and line length. Working within this limitation, the FERC data were not found to differ significantly from the composite database. Therefore, the composite database was judged to be a reasonable proxy for estimating national average costs.

  5. Cost analysis guidelines

    SciTech Connect (OSTI)

    Strait, R.S.

    1996-01-10

    The first phase of the Depleted Uranium Hexafluoride Management Program (Program)--management strategy selection--consists of several program elements: Technology Assessment, Engineering Analysis, Cost Analysis, and preparation of an Environmental Impact Statement (EIS). Cost Analysis will estimate the life-cycle costs associated with each of the long-term management strategy alternatives for depleted uranium hexafluoride (UF6). The scope of Cost Analysis will include all major expenditures, from the planning and design stages through decontamination and decommissioning. The costs will be estimated at a scoping or preconceptual design level and are intended to assist decision makers in comparing alternatives for further consideration. They will not be absolute costs or bid-document costs. The purpose of the Cost Analysis Guidelines is to establish a consistent approach to analyzing of cost alternatives for managing Department of Energy`s (DOE`s) stocks of depleted uranium hexafluoride (DUF6). The component modules that make up the DUF6 management program differ substantially in operational maintenance, process-options, requirements for R and D, equipment, facilities, regulatory compliance, (O and M), and operations risk. To facilitate a consistent and equitable comparison of costs, the guidelines offer common definitions, assumptions or basis, and limitations integrated with a standard approach to the analysis. Further, the goal is to evaluate total net life-cycle costs and display them in a way that gives DOE the capability to evaluate a variety of overall DUF6 management strategies, including commercial potential. The cost estimates reflect the preconceptual level of the designs. They will be appropriate for distinguishing among management strategies.

  6. Avoiding a Train Wreck: Replacing Old Coal Plants with Energy...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Avoiding a Train Wreck: Replacing Old Coal Plants with Energy Efficiency, August 2011 Avoiding a Train Wreck: Replacing Old Coal Plants with Energy Efficiency, August 2011 This...

  7. Intelligent agent for aircraft collision avoidance 

    E-Print Network [OSTI]

    Shandy, Surya Utama

    2002-01-01

    instrument flight rules and choose their own flight path and speed in real time. One of the requirements to make the free flight environment feasible is an aircraft collision avoidance agent, also known as a traffic agent. One widely accepted concept...

  8. LIFE Cost of Electricity, Capital and Operating Costs

    SciTech Connect (OSTI)

    Anklam, T

    2011-04-14

    Successful commercialization of fusion energy requires economic viability as well as technical and scientific feasibility. To assess economic viability, we have conducted a pre-conceptual level evaluation of LIFE economics. Unit costs are estimated from a combination of bottom-up costs estimates, working with representative vendors, and scaled results from previous studies of fission and fusion plants. An integrated process model of a LIFE power plant was developed to integrate and optimize unit costs and calculate top level metrics such as cost of electricity and power plant capital cost. The scope of this activity was the entire power plant site. Separately, a development program to deliver the required specialized equipment has been assembled. Results show that LIFE power plant cost of electricity and plant capital cost compare favorably to estimates for new-build LWR's, coal and gas - particularly if indicative costs of carbon capture and sequestration are accounted for.

  9. Avoiding Communication in Dense Linear Algebra

    E-Print Network [OSTI]

    California at Berkeley, University of

    Theoretical Lower Bounds Algorithmic Innovation Optimized Implementation Improved Applications Grey Ballard 9) + · (# words) as measured in time and energy, and the relative cost of communication is increasing Grey Bandwidth 59% per year 23% per year 26% per year Energy cost comparisons Grey Ballard 6 Source: John

  10. Energy Efficiency Improvement and Cost Saving Oportunities for the Concrete Industry

    E-Print Network [OSTI]

    Kermeli, Katerina

    2013-01-01

    is a decrease in pump operating and maintenance costs. AvoidImplementing a pump system maintenance program will help youoptimally. Improved pump system maintenance can lead to pump

  11. Benefits to BPA will equal or exceed costs for the Extended Block...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    to BPA associated with the DSI Service. Tangible benefits include avoided transmission costs to BPA's power marketing function that would otherwise be incurred absent the sales to...

  12. Contracting with reading costs and renegotiation costs

    E-Print Network [OSTI]

    Brennan, James R.

    2007-01-01

    Reading Costs, Competition, and ContractReading Costs . . . . . . . . . . . . . . . . C. EquilibriumUnconscionability A?ect Reading Costs . . . . . . . . . .

  13. Avoided Gigawatts Through Utility Capital Recovery Fees 

    E-Print Network [OSTI]

    Frosenfeld, A. N.; Verdict, M. E.

    1985-01-01

    Electric rate structures can be used to provide customers with the proper pricing signals as well as provide economic incentives for increased market penetration for energy efficient new buildings. An innovative, marginal (replacement cost) rate...

  14. Mitigation potential and cost in tropical forestry - relative role for agroforestry

    SciTech Connect (OSTI)

    Makundi, Willy R.; Sathaye, Jayant A.

    2004-01-01

    This paper summarizes studies of carbon mitigation potential (MP) and costs of forestry options in seven developing countries with a focus on the role of agroforestry. A common methodological approach known as comprehensive mitigation assessment process (COMAP) was used in each study to estimate the potential and costs between 2000 and 2030. The approach requires the projection of baseline and mitigation land-use scenarios derived from the demand for forest products and forestland for other uses such as agriculture and pasture. By using data on estimated carbon sequestration, emission avoidance, costs and benefits, the model enables one to estimate cost effectiveness indicators based on monetary benefit per t C, as well as estimates of total mitigation costs and potential when the activities are implemented at equilibrium level. The results show that about half the MP of 6.9 Gt C (an average of 223 Mt C per year) between 2000 and 2030 in the seven countries could be achieved at a negative cost, and the other half at costs not exceeding $100 per t C. Negative cost indicates that non-carbon revenue is sufficient to offset direct costs of about half of the options. The agroforestry options analyzed bear a significant proportion of the potential at medium to low cost per t C when compared to other options. The role of agroforestry in these countries varied between 6% and 21% of the MP, though the options are much more cost effective than most due to the low wage or opportunity cost of rural labor. Agroforestry options are attractive due to the large number of people and potential area currently engaged in agriculture, but they pose unique challenges for carbon and cost accounting due to the dispersed nature of agricultural activities in the tropics, as well as specific difficulties arising from requirements for monitoring, verification, leakage assessment and the establishment of credible baselines.

  15. Low cost electronic ultracapacitor interface technique to provide load leveling of a battery for pulsed load or motor traction drive applications

    DOE Patents [OSTI]

    King, Robert Dean (Schenectady, NY); DeDoncker, Rik Wivina Anna Adelson (Malvern, PA)

    1998-01-01

    A battery load leveling arrangement for an electrically powered system in which battery loading is subject to intermittent high current loading utilizes a passive energy storage device and a diode connected in series with the storage device to conduct current from the storage device to the load when current demand forces a drop in battery voltage. A current limiting circuit is connected in parallel with the diode for recharging the passive energy storage device. The current limiting circuit functions to limit the average magnitude of recharge current supplied to the storage device. Various forms of current limiting circuits are disclosed, including a PTC resistor coupled in parallel with a fixed resistor. The current limit circuit may also include an SCR for switching regenerative braking current to the device when the system is connected to power an electric motor.

  16. BOUNDS ON ZIMIN WORD AVOIDANCE JOSHUA COOPER* AND DANNY RORABAUGH*

    E-Print Network [OSTI]

    Cooper, Joshua N.

    BOUNDS ON ZIMIN WORD AVOIDANCE JOSHUA COOPER* AND DANNY RORABAUGH* Abstract. How long can a word be that avoids the unavoidable? Word W encounters word V provided there is a homomorphism defined by mapping letters to nonempty words such that (V ) is a subword of W. Otherwise, W is said to avoid V . If, on any

  17. Avoidable Sets in The Bicyclic Inverse Semigroup Nandor Sieben

    E-Print Network [OSTI]

    Sieben, Nándor

    Avoidable Sets in The Bicyclic Inverse Semigroup N´andor Sieben 9/2/2003 Abstract A subset U elements of B. The avoidable sets of the bicyclic inverse semigroup are classified. 1. Introduction If (S avoidable sets in the bicyclic inverse semigroup, which is perhaps the most important inverse semigroup. Its

  18. COMPARATIVE COSTS OF CALIFORNIA CENTRAL STATION ELECTRICITY

    E-Print Network [OSTI]

    CALIFORNIA ENERGY COMMISSION COMPARATIVE COSTS OF CALIFORNIA CENTRAL STATION ELECTRICITY GENERATION in this paper. #12;ABSTRACT In this 2007 report of the cost of generation of electricity for California located technologies, California Energy Commission staff provides levelized costs, including the cost assumptions

  19. Department of Energy Environmental Management cost infrastructure development program: Cost analysis requirements

    SciTech Connect (OSTI)

    Custer, W.R. Jr.; Messick, C.D.

    1996-03-31

    This report was prepared to support development of the Department of Energy Environmental Management cost infrastructure -- a new capability to independently estimate and analyze costs. Currently, the cost data are reported according to a structure that blends level of effort tasks with product and process oriented tasks. Also. the budgetary inputs are developed from prior year funding authorizations and from contractor-developed parametric estimates that have been adjusted to planned funding levels or appropriations. Consequently, it is difficult for headquarters and field-level activities to use actual cost data and technical requirements to independently assess the costs generated and identify trends, potential cost savings from process improvements, and cost reduction strategies.

  20. On the morphology of avoided crossings in the spectrum of irregular quantum systems

    SciTech Connect (OSTI)

    Yang, Xiazhou; Burgdoerfer, J.; Eschenazi, E. (Tennessee Univ., Knoxville, TN (USA). Dept. of Physics Oak Ridge National Lab., TN (USA))

    1990-01-01

    The deformation of the energy level spectra of quantum systems as a function of a control parameter governing the strength of a non- integrable perturbation can be determined by standard molecular dynamics techniques. This method is used to analyze the distribution and morphology of avoided crossings for a system of coupled Morse oscillators. 25 refs., 4 figs.

  1. The Threat to the Planet: How Can We Avoid Dangerous Human-Made Climate Change?

    E-Print Network [OSTI]

    Hansen, James E.

    The Threat to the Planet: How Can We Avoid Dangerous Human-Made Climate Change? Remarks of James E to the threat of climate change has been sudden and profound. Only in recent years has the extent and immediacy-made climate change, but what level is dangerous? Chart 4. Critical metrics defining dangerous, I believe

  2. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979Coal Consumers THURSDAY, APRILCustomersTotal

  3. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979Coal Consumers THURSDAY, APRILCustomersTotalHost and

  4. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979Coal Consumers THURSDAY, APRILCustomersTotalHost andFAQs 1

  5. Microsoft Word - Levelized Cost of Energy Analysis

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustmentsShirleyEnergyTher i nAand DOE SafetyofDepartment. " 21 ran PPPO-03-1RESEARCH CALL

  6. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1 Table 1.10 CoolingNotes &* j o n pTotalEnergy1

  7. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1 Table 1.10 CoolingNotes &* j o n pTotalEnergy1

  8. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1 Table 1.10 CoolingNotes &* j o n pTotalEnergy1012

  9. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1 Table 1.10 CoolingNotes &* j o n

  10. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1 Table 1.10 CoolingNotes &* j o n5 1 April 2015

  11. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1 Table 1.10 CoolingNotes &* j o n5 1 April 2015

  12. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1 Table 1.10 CoolingNotes &* j o n5 1 April 2015

  13. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1 Table 1.10 CoolingNotes &* j o n5 1 April 2015

  14. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1 Table 1.10 CoolingNotes &* j o n5 1 April 2015

  15. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1 Table 1.10 CoolingNotes &* j o n5 1 April 20151

  16. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1 Table 1.10 CoolingNotes &* j o n5 1 April

  17. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1 Table 1.10 CoolingNotes &* j o n5 1 April Market

  18. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1 Table 1.10 CoolingNotes &* j o n5 1 April Market

  19. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1 Table 1.10 CoolingNotes &* j o n5 1 April Market

  20. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1 Table 1.10 CoolingNotes &* j o n5 1 April Market

  1. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1 Table 1.10 CoolingNotes &* j o n5 1 April Market

  2. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1 Table 1.10 CoolingNotes &* j o n5 1 April Market4

  3. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1 Table 1.10 CoolingNotes &* j o n5 1 April Market4

  4. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1 Table 1.10 CoolingNotes &* j o n5 1 April Market4

  5. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1 Table 1.10 CoolingNotes &* j o n5 1 April Market4

  6. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1 Table 1.10 CoolingNotes &* j o n5 1 April Market4

  7. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1 Table 1.10 CoolingNotes &* j o n5 1 April Market4

  8. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1 Table 1.10 CoolingNotes &* j o n5 1 April Market4

  9. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1 Table 1.10 CoolingNotes &* j o n5 1 April

  10. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1 Table 1.10 CoolingNotes &* j o n5 1 April Market

  11. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1 Table 1.10 CoolingNotes &* j o n5 1 April Market3

  12. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1 Table 1.10 CoolingNotes &* j o n5 1 April

  13. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1 Table 1.10 CoolingNotes &* j o n5 1 April5 1

  14. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1 Table 1.10 CoolingNotes &* j o n5 1 April5 1

  15. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1 Table 1.10 CoolingNotes &* j o n5 1 April5 1

  16. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1 Table 1.10 CoolingNotes &* j o n5 1 April5 1

  17. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1 Table 1.10 CoolingNotes &* j o n5 1 April5 1About

  18. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1 Table 1.10 CoolingNotes &* j o n5 1 April5

  19. Levelized Cost of Energy: A Parametric Study

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantityBonneville Power Administration would likeUniverseIMPACTThousand CubicResourcelogo and-E C H N13, 2009 In reply refer June

  20. Levelized Cost of Energy: A Parametric Study

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantityBonneville Power Administration would likeUniverseIMPACTThousand CubicResourcelogo and-E C H N13, 2009 In reply refer

  1. 2017 Levelized Costs AEO 2012 Early Release

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry Natural Gas ReservesAlabama AlabamaSurvey Forms Proposed

  2. Advanced Fuel Cycle Cost Basis

    SciTech Connect (OSTI)

    D. E. Shropshire; K. A. Williams; W. B. Boore; J. D. Smith; B. W. Dixon; M. Dunzik-Gougar; R. D. Adams; D. Gombert; E. Schneider

    2008-03-01

    This report, commissioned by the U.S. Department of Energy (DOE), provides a comprehensive set of cost data supporting a cost analysis for the relative economic comparison of options for use in the Advanced Fuel Cycle Initiative (AFCI) Program. The report describes the AFCI cost basis development process, reference information on AFCI cost modules, a procedure for estimating fuel cycle costs, economic evaluation guidelines, and a discussion on the integration of cost data into economic computer models. This report contains reference cost data for 25 cost modules—23 fuel cycle cost modules and 2 reactor modules. The cost modules were developed in the areas of natural uranium mining and milling, conversion, enrichment, depleted uranium disposition, fuel fabrication, interim spent fuel storage, reprocessing, waste conditioning, spent nuclear fuel (SNF) packaging, long-term monitored retrievable storage, near surface disposal of low-level waste (LLW), geologic repository and other disposal concepts, and transportation processes for nuclear fuel, LLW, SNF, transuranic, and high-level waste.

  3. Advanced Fuel Cycle Cost Basis

    SciTech Connect (OSTI)

    D. E. Shropshire; K. A. Williams; W. B. Boore; J. D. Smith; B. W. Dixon; M. Dunzik-Gougar; R. D. Adams; D. Gombert

    2007-04-01

    This report, commissioned by the U.S. Department of Energy (DOE), provides a comprehensive set of cost data supporting a cost analysis for the relative economic comparison of options for use in the Advanced Fuel Cycle Initiative (AFCI) Program. The report describes the AFCI cost basis development process, reference information on AFCI cost modules, a procedure for estimating fuel cycle costs, economic evaluation guidelines, and a discussion on the integration of cost data into economic computer models. This report contains reference cost data for 26 cost modules—24 fuel cycle cost modules and 2 reactor modules. The cost modules were developed in the areas of natural uranium mining and milling, conversion, enrichment, depleted uranium disposition, fuel fabrication, interim spent fuel storage, reprocessing, waste conditioning, spent nuclear fuel (SNF) packaging, long-term monitored retrievable storage, near surface disposal of low-level waste (LLW), geologic repository and other disposal concepts, and transportation processes for nuclear fuel, LLW, SNF, and high-level waste.

  4. Advanced Fuel Cycle Cost Basis

    SciTech Connect (OSTI)

    D. E. Shropshire; K. A. Williams; W. B. Boore; J. D. Smith; B. W. Dixon; M. Dunzik-Gougar; R. D. Adams; D. Gombert; E. Schneider

    2009-12-01

    This report, commissioned by the U.S. Department of Energy (DOE), provides a comprehensive set of cost data supporting a cost analysis for the relative economic comparison of options for use in the Advanced Fuel Cycle Initiative (AFCI) Program. The report describes the AFCI cost basis development process, reference information on AFCI cost modules, a procedure for estimating fuel cycle costs, economic evaluation guidelines, and a discussion on the integration of cost data into economic computer models. This report contains reference cost data for 25 cost modules—23 fuel cycle cost modules and 2 reactor modules. The cost modules were developed in the areas of natural uranium mining and milling, conversion, enrichment, depleted uranium disposition, fuel fabrication, interim spent fuel storage, reprocessing, waste conditioning, spent nuclear fuel (SNF) packaging, long-term monitored retrievable storage, near surface disposal of low-level waste (LLW), geologic repository and other disposal concepts, and transportation processes for nuclear fuel, LLW, SNF, transuranic, and high-level waste.

  5. Cost effectiveness of recycling: A systems model

    SciTech Connect (OSTI)

    Tonjes, David J., E-mail: david.tonjes@stonybrook.edu [Department of Technology and Society, College of Engineering and Applied Sciences, Stony Brook University, Stony Brook, NY 11794-3560 (United States); Waste Reduction and Management Institute, School of Marine and Atmospheric Sciences, Stony Brook University, Stony Brook, NY 11794-5000 (United States); Center for Bioenergy Research and Development, Advanced Energy Research and Technology Center, Stony Brook University, 1000 Innovation Rd., Stony Brook, NY 11794-6044 (United States); Mallikarjun, Sreekanth, E-mail: sreekanth.mallikarjun@stonybrook.edu [Department of Technology and Society, College of Engineering and Applied Sciences, Stony Brook University, Stony Brook, NY 11794-3560 (United States)

    2013-11-15

    Highlights: • Curbside collection of recyclables reduces overall system costs over a range of conditions. • When avoided costs for recyclables are large, even high collection costs are supported. • When avoided costs for recyclables are not great, there are reduced opportunities for savings. • For common waste compositions, maximizing curbside recyclables collection always saves money. - Abstract: Financial analytical models of waste management systems have often found that recycling costs exceed direct benefits, and in order to economically justify recycling activities, externalities such as household expenses or environmental impacts must be invoked. Certain more empirically based studies have also found that recycling is more expensive than disposal. Other work, both through models and surveys, have found differently. Here we present an empirical systems model, largely drawn from a suburban Long Island municipality. The model accounts for changes in distribution of effort as recycling tonnages displace disposal tonnages, and the seven different cases examined all show that curbside collection programs that manage up to between 31% and 37% of the waste stream should result in overall system savings. These savings accrue partially because of assumed cost differences in tip fees for recyclables and disposed wastes, and also because recycling can result in a more efficient, cost-effective collection program. These results imply that increases in recycling are justifiable due to cost-savings alone, not on more difficult to measure factors that may not impact program budgets.

  6. 2010 Cost of Wind Energy Review

    SciTech Connect (OSTI)

    Tegen, S.; Hand, M.; Maples, B.; Lantz, E.; Schwabe, P.; Smith, A.

    2012-04-01

    This document provides a detailed description of NREL's levelized cost of wind energy equation, assumptions, and results in 2010, including historical cost trends and future projections for land-based and offshore utility-scale wind.

  7. 2010 Cost of Wind Energy Review

    SciTech Connect (OSTI)

    Tegen, S.; Hand, M.; Maples, B.; Lantz, E.; Schwabe, P.; Smith, A.

    2012-04-01

    This document provides a detailed description of NREL's levelized cost of wind energy equation, assumptions and results in 2010, including historical cost trends and future projections for land-based and offshore utility-scale wind.

  8. AVOID BECOMING A VICTIM OF COUNTERFEIT ITEMS

    SciTech Connect (OSTI)

    WARRINER RD

    2011-07-13

    In today's globalized economy, we cannot live without imported products. Most people do not realize how thin the safety net of regulation and inspection really is. Less than three percent of imported products receive any form of government inspection prior to sale. Avoid flea markets, street vendors and deep discount stores. The sellers of counterfeit wares know where to market their products. They look for individuals who are hungry for a brand name item but do not want to pay a brand name price for it. The internet provides anonymity to the sellers of counterfeit products. Unlike Europe, U.S. law does not hold internet-marketing organizations, responsible for the quality of the products sold on their websites. These organizations will remove an individual vendor when a sufficient number of complaints are lodged, but they will not take responsibility for the counterfeit products you may have purchased. EBay has a number of counterfeit product guides to help you avoid being a victim of the sellers of these products. Ten percent of all medications taken worldwide are counterfeit. If you do buy medications on-line, be sure that the National Association of Boards of Pharmacy Verified Internet Pharmacy Practice Sites (VIPPS) recommends the pharmacy you choose to use. Inspect all medication purchases and report any change in color, shape, imprinting or odor to your pharmacist. If you take generic medications these attributes may change from one manufacturer to another. Your pharmacist should inform you of any changes when you refill your prescription. If they do not, get clarification prior to taking the medication. Please note that the Federal Drug Administration (FDA) does not regulate supplements. The FDA only steps in when a specific supplement proves to cause physical harm or contains a regulated ingredient. Due to counterfeiting, Underwriters Laboratories (UL) changed their label design three times since 1996. The new gold label should be attached to the cord or body of most office and home electrical products (please see the picture to the left). Holiday lights may have the UL marking in red or green instead of the universal black. A red UL mark indicates the product is approved for outdoor as well as indoor service. The green UL mark indicates the product is only to be used indoors. A small number of home electrical products may bear an Interteck (ETL) approval. This label is also acceptable. An Interteck label includes black print on a white background bearing the circular ETL logo. Most manufacturers are proud of their products and strive to gain name recognition as well as foster repeat business. This is not true of counterfeiters. The very first thing most counterfeiters try to do is make their products untraceable. Their products may bear the nation of origin but that is all. This is a common practice with metal components such as pipe fittings and flanges. This is also true of hoisting and rigging equipment such as shackles, turnbuckles and chain. Sadly, this has also occurred with the purchase of some safety equipment such as arc-flash retardant coveralls. Learn the national standards associated with products you are purchasing. Clearly specify these requirements on the procurements you make.

  9. Estimating Specialty Costs

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    Specialty costs are those nonstandard, unusual costs that are not typically estimated. Costs for research and development (R&D) projects involving new technologies, costs associated with future regulations, and specialty equipment costs are examples of specialty costs. This chapter discusses those factors that are significant contributors to project specialty costs and methods of estimating costs for specialty projects.

  10. The economic impact of state ordered avoided cost rates for photovoltaic generated electricity

    E-Print Network [OSTI]

    Bottaro, Drew

    1981-01-01

    The Public Utility Regulatory Policies Act (PURPA) of 1978 requires that electric utilities purchase electricity generated by small power producers (QFs) such as photovoltaic systems at rates that will encourage the ...

  11. Impact of post-event avoidance behavior on commercial facilities sector venues-literature review.

    SciTech Connect (OSTI)

    Samsa, M. E.; Baldwin, T. E.; Berry, M. S.; Guzowski, L. B.; Martinez-Moyano, I.; Nieves, A. L.; Ramarasad, A.

    2011-03-24

    The terrorist attacks of September 11, 2001 (9/11), focused a great deal of interest and concern on how individual and social perceptions of risk change behavior and subsequently affect commercial sector venues. Argonne conducted a review of the literature to identify studies that quantify the direct and indirect economic consequences of avoidance behaviors that result from terrorist attacks. Despite a growing amount of literature addressing terrorism impacts, relatively little is known about the causal relationships between risk perception, human avoidance behaviors, and the economic effects on commercial venues. Nevertheless, the technical and academic literature does provide some evidence, both directly and by inference, of the level and duration of post-event avoidance behaviors on commercial venues. Key findings are summarized in this Executive Summary. Also included as an appendix is a more detailed summary table of literature findings reproduced from the full report.

  12. Costa Rica-Mitigation of Greenhouse Gas Emissions through Avoided...

    Open Energy Info (EERE)

    Costa Rica-Mitigation of Greenhouse Gas Emissions through Avoided Deforestation of Tropical Rainforests on Privately-owned Lands in High Conservation Value Areas Jump to:...

  13. Emissions Scenarios, Costs, and Implementation Considerations of REDD Programs

    SciTech Connect (OSTI)

    Sathaye, Jayant; Andrasko, Ken; Chan, Peter

    2011-04-11

    Greenhouse gas emissions from the forestry sector are estimated to be 8.4 GtCO2-eq./year or about 17percent of the global emissions. We estimate that the cost forreducing deforestation is low in Africa and several times higher in Latin America and Southeast Asia. These cost estimates are sensitive to the uncertainties of how muchunsustainable high-revenue logging occurs, little understood transaction and program implementation costs, and barriers to implementation including governance issues. Due to lack of capacity in the affected countries, achieving reduction or avoidance of carbon emissions will require extensive REDD-plus programs. Preliminary REDD-plus Readiness cost estimates and program descriptions for Indonesia, Democratic Republic of the Congo, Ghana, Guyana and Mexico show that roughly one-third of potential REDD-plus mitigation benefits might come from avoided deforestation and the rest from avoided forest degradation and other REDD-plus activities.

  14. Cost Sharing What is Cost Sharing?

    E-Print Network [OSTI]

    California at San Diego, University of

    into COEUS x OPAFS establishes project related IFIS fund and index numbers x Department tracks cost sharing sharing using various data fields (bin, fund, PI, index, etc.) x Create a Bin Generate a bin where cost1 Cost Sharing What is Cost Sharing? x Cost sharing is a commitment to use university resources

  15. AIAA-2001-4232 Severe Weather Avoidance Using Informed

    E-Print Network [OSTI]

    Valasek, John

    AIAA-2001-4232 Severe Weather Avoidance Using Informed Heuristic Search S. Bokadia and J. Valasek, Suite 500, Reston, VA, 20191-4344. #12;AIAA 2001-4232 SEVERE WEATHER AVOIDANCE USING INFORMED HEURISTIC airport's terminal space3 . But an important issue in free flight is the safety of an airplane. Weather

  16. Obstacle Avoidance and a Perturbation Sensitivity Model for Motor Planning

    E-Print Network [OSTI]

    Sabes, Philip

    Obstacle Avoidance and a Perturbation Sensitivity Model for Motor Planning Philip N. Sabes, Cambridge, Massachusetts 02139 A novel obstacle avoidance paradigm was used to investigate the planning of human reaching movements. We explored whether the CNS plans arm movements based entirely on the visual

  17. Food sensitizes C. elegans avoidance behaviours through acute dopamine signalling

    E-Print Network [OSTI]

    Schafer, William R.

    Food sensitizes C. elegans avoidance behaviours through acute dopamine signalling Marina Ezcurra1 at NOVUM, Karolinska Institute, Huddinge, Sweden Many behavioural states are modulated by food avail of an external food source enhances avoidance responses to soluble repellents sensed by the polymodal ASH neurons

  18. Fluctuation force exerted by a planar self-avoiding polymer

    E-Print Network [OSTI]

    Wiese, Kay Jörg

    OFFPRINT Fluctuation force exerted by a planar self-avoiding polymer P. Le Doussal and K. J. Wiese.1209/0295-5075/86/22001 Fluctuation force exerted by a planar self-avoiding polymer P. Le Doussal and K. J. Wiese(a) CNRS, and Brownian motion PACS 66.30.hk ­ Polymers Abstract ­ Using the results from Schramm L¨owner evolution (SLE

  19. Cost Sharing Basics Definitions

    E-Print Network [OSTI]

    Finley Jr., Russell L.

    Cost Sharing Basics Definitions Some funding agencies require the grantee institution the project costs. Cost sharing is defined as project costs not borne by the sponsor. Cost sharing funds may resources or facilities. If the award is federal, only acceptable non-federal costs qualify as cost sharing

  20. Renewable Portfolio Standards: Costs and Benefits (Poster)

    SciTech Connect (OSTI)

    Bird, L.; Heeter, J.; Barbose, G.; Weaver, S.; Flores, F.; Kuskova-Burns, K.; Wiser, R.

    2014-10-01

    This report summarizes state-level RPS costs to date, and considers how those costs may evolve going forward given scheduled increases in RPS targets and cost containment mechanisms. The report also summarizes RPS benefits estimates, based on published studies for individual states and discusses key methodological considerations.

  1. THE COST OF REDUCING VOC EMMISSIONS

    E-Print Network [OSTI]

    Bateman, Ian J.

    THE COST OF REDUCING VOC EMMISSIONS FROM 21 INDUSTRIES BY JONATHAN FISHER CSERGE WORKING PAPER WM 97-03 #12;THE COST OF REDUCING VOC EMISSIONS FROM 21 INDUSTRIES by Jonathan Fisher ERM Economics 8 and Industry to estimate the costs of various levels of controls on emissions of Volatile Organic Compounds

  2. Employee Replacement Costs

    E-Print Network [OSTI]

    Dube, Arindrajit; Freeman, Eric; Reich, Michael

    2010-01-01

    Samuel Schenker, “The Costs of Hir- u ing Skilled Workers”,Employee Replacement Costs Arindrajit Dube, Eric Freeman andof employee replacement costs, using a panel survey of

  3. Energy Efficiency Improvement and Cost Saving Opportunities for the Petrochemical Industry - An ENERGY STAR(R) Guide for Energy and Plant Managers

    E-Print Network [OSTI]

    Neelis, Maarten

    2008-01-01

    controls Pumps Pump system maintenance Avoiding throttlingInadequate maintenance at times lowers pump systempump system. Energy costs, and sometimes operations and maintenance

  4. Cost and Reliability Considerations in Designing the Next-Generation IP over WDM Backbone Networks

    E-Print Network [OSTI]

    Greenberg, Albert

    Cost and Reliability Considerations in Designing the Next-Generation IP over WDM Backbone Networks of the cost and reliability considerations involved in designing the next-generation backbone network. Our cost of the network. Hence, a fundamental redesign of the backbone network which avoids such redundant

  5. REGULAR ARTICLE The Sunk-cost Effect as an Optimal Rate-maximizing

    E-Print Network [OSTI]

    -term rate of gain; the entry cost of each new task is so great that the forager avoids ever returningREGULAR ARTICLE The Sunk-cost Effect as an Optimal Rate-maximizing Behavior Theodore P. Pavlic for underestimating patch exploitation time. However, proper modeling of costs not only answers these crit- icisms

  6. Construction Cost Growth for New Department of Energy Nuclear Facilities

    SciTech Connect (OSTI)

    Kubic, Jr., William L.

    2014-05-25

    Cost growth and construction delays are problems that plague many large construction projects including the construction of new Department of Energy (DOE) nuclear facilities. A study was conducted to evaluate cost growth of large DOE construction projects. The purpose of the study was to compile relevant data, consider the possible causes of cost growth, and recommend measures that could be used to avoid extreme cost growth in the future. Both large DOE and non-DOE construction projects were considered in this study. With the exception of Chemical and Metallurgical Research Building Replacement Project (CMRR) and the Mixed Oxide Fuel Fabrication Facility (MFFF), cost growth for DOE Nuclear facilities is comparable to the growth experienced in other mega construction projects. The largest increase in estimated cost was found to occur between early cost estimates and establishing the project baseline during detailed design. Once the project baseline was established, cost growth for DOE nuclear facilities was modest compared to non-DOE mega projects.

  7. Autonomous robotic wheelchair with collision-avoidance navigation 

    E-Print Network [OSTI]

    Hsieh, Pin-Chun

    2008-10-10

    The objective of this research is to demonstrate a robotic wheelchair moving in an unknown environment with collision-avoidance navigation. A real-time path-planning algorithm was implemented by detecting the range to obstacles and by tracking...

  8. Hazard Avoidance in Wireless Sensor and Actor Networks

    E-Print Network [OSTI]

    Sivakumar, Raghupathy

    Hazard Avoidance in Wireless Sensor and Actor Networks Ramanuja Vedantham Zhenyun Zhuang Prof [Akyildiz'04] Network Low bandwidth (Hazards Hazards undesirable changes in the environment Reason for hazards Different latencies For different sensors and actors

  9. Levelized cost and levelized avoiced cost of new generation resources in the Annual Energy Outlook 2014

    Annual Energy Outlook [U.S. Energy Information Administration (EIA)]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (BillionProved ReservesCubic Feet) Kenai, AK Liquefied Natural2009343 342 328 37056

  10. Quantifying the system balancing cost when wind energy is incorporated into electricity generation system 

    E-Print Network [OSTI]

    Issaeva, Natalia

    2009-01-01

    Incorporation of wind energy into the electricity generation system requires a detailed analysis of wind speed in order to minimize system balancing cost and avoid a significant mismatch between supply and demand. Power ...

  11. Dipolar Rydberg-atom gas prepared by adiabatic passage through an avoided crossing

    E-Print Network [OSTI]

    Wang, Limei; Zhang, Linjie; Li, Changyong; Yang, Yonggang; Zhao, Jianming; Raithel, Georg; Jia, Suotang

    2015-01-01

    The passage of cold cesium 49S$_{1/2}$ Rydberg atoms through an electric-field-induced multi-level avoided crossing with nearby hydrogen-like Rydberg levels is employed to prepare a cold, dipolar Rydberg atom gas. When the electric field is ramped through the avoided crossing on time scales on the order of 100~ns or slower, the 49S$_{1/2}$ population adiabatically transitions into high-\\emph{l} Rydberg Stark states. The adiabatic state transformation results in a cold gas of Rydberg atoms with large electric dipole moments. After a waiting time of about $1~\\mu$s and at sufficient atom density, the adiabatically transformed highly dipolar atoms become undetectable, enabling us to discern adiabatic from diabatic passage behavior through the avoided crossing. We attribute the state-selectivity to $m$-mixing collisions between the dipolar atoms. The data interpretation is supported by numerical simulations of the passage dynamics and of binary $m$-mixing collisions.

  12. Cost Model and Cost Estimating Software

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    This chapter discusses a formalized methodology is basically a cost model, which forms the basis for estimating software.

  13. Costing of Joining Methods -Arc Welding Costs

    E-Print Network [OSTI]

    Colton, Jonathan S.

    Costing of Joining Methods - Arc Welding Costs ver. 1 ME 6222: Manufacturing Processes and Systems.S. Colton © GIT 2009 5 #12;LaborLabor Di t ti f ldi· Direct time of welding ­ time to produce a length of weld ­ labor rate ­ multiplication gives labor cost per length · Set-up time, etc. · Personal time

  14. PHENIX Work Breakdown Structure. Cost and schedule review copy

    SciTech Connect (OSTI)

    Not Available

    1994-02-01

    The Work Breakdown Structure (WBS) Book begins with this Overview section, which contains the high-level summary cost estimate, the cost profile, and the global construction schedule. The summary cost estimate shows the total US cost and the cost in terms of PHENIX construction funds for building the PHENIX detector. All costs in the WBS book are shown in FY 1993 dollars. Also shown are the institutional and foreign contributions, the level of pre-operations funding, and the cost of deferred items. Pie charts are presented at PHENIX WBS level 1 and 2 that show this information. The PHENIX construction funds are shown broken down to PHENIX WBS level 3 items per fiscal year, and the resulting profile is compared to the RHIC target profile. An accumulated difference of the two profiles is also shown. The PHENIX global construction schedule is presented at the end of the Overview section. Following the Overview are sections for each subsystem. Each subsystem section begins with a summary cost estimate, cost profile, and critical path. The total level 3 cost is broken down into fixed costs (M&S), engineering costs (EDIA) and labor costs. Costs are further broken down in terms of PHENIX construction funds, institutional and foreign contributions, pre-operations funding, and deferred items. Also shown is the contingency at level 3 and the level 4 breakdown of the total cost. The cost profile in fiscal years is shown at level 3. The subsystem summaries are followed by the full cost estimate and schedule sheets for that subsystem. These detailed sheets are typically carried down to level 7 or 8. The cost estimate shows Total, M&S, EDIA, and Labor breakdowns, as well as contingency, for each WBS entry.

  15. PHENIX WBS notes. Cost and schedule review copy

    SciTech Connect (OSTI)

    Not Available

    1994-02-01

    The Work Breakdown Structure (WBS) Book begins with this Overview section, which contains the high-level summary cost estimate, the cost profile, and the global construction schedule. The summary cost estimate shows the total US cost and the cost in terms of PHENIX construction funds for building the PHENIX detector. All costs in the WBS book are shown in FY 1993 dollars. Also shown are the institutional and foreign contributions, the level of pre-operations funding, and the cost of deferred items. Pie charts are presented at PHENIX WBS level 1 and 2 that show this information. The PHENIX construction funds are shown broken down to PHENIX WBS level 3 items per fiscal year, and the resulting profile is compared to the RHIC target profile. An accumulated difference of the two profiles is also shown. The PHENIX global construction schedule is presented at the end of the Overview section. Following the Overview are sections for each subsystem. Each subsystem section begins with a summary cost estimate, cost profile, and critical path. The total level 3 cost is broken down into fixed costs (M&S), engineering costs (EDIA) and labor costs. Costs are further broken down in terms of PHENIX construction funds, institutional and foreign contributions, pre-operations funding, and deferred items. Also shown is the contingency at level 3 and the level 4 breakdown of the total cost. The cost profile in fiscal years is shown at level 3. The subsystem summaries are followed by the full cost estimate and schedule sheets for that subsystem. These detailed sheets are typically carried down to level 7 or 8. The cost estimate Total, M&S, EDIA, and Labor breakdowns, as well as contingency, for each WBS entry.

  16. Oxidative Alkaline leaching of Americium from simulated high-level nuclear waste sludges

    E-Print Network [OSTI]

    Reed, Wendy A.; Garnov, Alexander Yu.; Rao, Linfeng; Nash, Kenneth L.; Bond, Andrew H.

    2004-01-01

    vitrification process is very costly (it is estimated that a canister of vitrified high level waste costs

  17. Utility Cost Analysis 

    E-Print Network [OSTI]

    Horn, S.

    1984-01-01

    One of the first steps in setting up an energy management program in a commercial building is determining operating costs per energy consuming system through a utility cost analysis. This paper illustrates utility cost analysis methods used...

  18. Activity Based Costing

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    Activity Based Costing (ABC) is method for developing cost estimates in which the project is subdivided into discrete, quantifiable activities or a work unit. This chapter outlines the Activity Based Costing method and discusses applicable uses of ABC.

  19. Examples of Cost Estimation Packages

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    Estimates can be performed in a variety of ways. Some of these are for projects for an undefined scope, a conventional construction project, or where there is a level of effort required to complete the work. Examples of cost estimation packages for these types of projects are described in this appendix.

  20. Energy policies avoiding a tipping point in the climate system Olivier Bahn a,, Neil R. Edwards b

    E-Print Network [OSTI]

    Stocker, Thomas

    emission reduction from today's level, with transition to nuclear and/or renewable energy, possiblyEnergy policies avoiding a tipping point in the climate system Olivier Bahn a,Ă, Neil R. Edwards b rainforest, loss of Arctic summer sea ice, melting of the West Antarctic ice sheet, and a collapse

  1. Sharing Supermodular Costs

    E-Print Network [OSTI]

    2010-06-23

    For a particular class of supermodular cost cooperative games that arises from a scheduling ... the costs collectively incurred by a group of cooperating agents.

  2. Cartel Pricing Dynamics with Cost Variability and Endogenous Buyer Detection

    E-Print Network [OSTI]

    Niebur, Ernst

    Cartel Pricing Dynamics with Cost Variability and Endogenous Buyer Detection Joseph E. Harrington to cost shocks. During the stationary phase, price responds to cost but is much less sensitive than under of cost shocks. It is also shown that the cartel price path may overshoot its long-run level so that price

  3. Serial stimuli in the acquisition of discriminated avoidance 

    E-Print Network [OSTI]

    Hildbrand, Mary Kathleen

    1971-01-01

    higher rate of avoidance due to the efficacy of the first stimulus (Sl) in extending the length of the CS and avoiding the unconditioned stimulus (US), Purthermore, since anxiety is the basis of the efficiency of the conditioned stimulus (CS...) in producing behavior, and since this anxiety is classically conditioned to the CS, then after a large number of trials, the effects of higher-order conditioning ought to become manifest. Citations on the following pages follow the style of ~Ph 1 S Because...

  4. A VLSI structure for the deadlock avoidance problem

    SciTech Connect (OSTI)

    Bertolazzi, P.; Bongiovanni, G.

    1985-11-01

    In this paper the authors present two VLSI structures implementing the banker's algorithm for the deadlock avoidance problem, and we derive the area x (time)/sup 2/ lower bound for such an algorithm. The first structure is based on the VLSI mesh of trees. The second structure is a modification of the first one, and it approaches more closely the theoretical lower bound.

  5. BAAP: Blackhole Attack Avoidance Protocol for Wireless Network

    E-Print Network [OSTI]

    Dharmaraja, S.

    BAAP: Blackhole Attack Avoidance Protocol for Wireless Network Saurabh Gupta Indian Institute without the contraint of special hardware and dependency on physical medium of wireless network. BAAP and router at the same time. Most of the previous research has focused on problems of routing

  6. Packet Drop Avoidance for High-speed network transmission protocol

    SciTech Connect (OSTI)

    Jin, Guojun

    2004-05-01

    As network bandwidth continues to grow and longer paths are used to exchange large scientific data between storage systems and GRID computation, it has become increasingly obvious that there is a need to deploy a packet drop avoidance mechanism into network transmission protocols. Current end-to-end congestion avoidance mechanisms used in Transmission Control Protocol (TCP) have worked well on low bandwidth delay product networks, but with newer high-bandwidth delay networks they have shown to be inefficient and prone to unstable. This is largely due to increased network bandwidth coupled with changes in internet traffic patterns. These changes come from a variety of new network applications that are being developed to take advantage of the increased network bandwidth. This paper will examine the end-to-end congestion avoidance mechanism and perform a step-by-step analysis of its theory. In addition we will propose an alternative approach developed as part of a new network transmission protocol. Our alternative protocol uses a packet drop avoidance (PDA) mechanism built on top of the maximum burst size (MBS) theory combined with a real-time available bandwidth algorithm.

  7. Error Dynamics: The Dynamic Emergence of Error Avoidance and

    E-Print Network [OSTI]

    Bickhard, Mark H.

    . Standard such notions are, however, arguably limited and bad notions, being based on untenable models of learning about error and of handling error knowledge constitute a complex major theme in evolution VICARIANTS Avoiding Error. The central theme is a progressive elaboration of kinds of dynamics that manage

  8. Local Terrain Mapping for Obstacle Avoidance using Monocular Vision

    E-Print Network [OSTI]

    Langelaan, Jack W.

    a potential field obstacle avoidance routine are presented. Introduction Currently, many unmanned aerial Vehicles Specialist's Forum 1 #12;2 MARLOW AHS UNMANNED VEHICLES SPECIALIST'S FORUM all classes of unmanned unmanned rotorcraft through an unsurveyed envi- ronment consisting of forest and urban canyons. Optical

  9. Cost Estimation Package

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    This chapter focuses on the components (or elements) of the cost estimation package and their documentation.

  10. A chronicle of costs

    SciTech Connect (OSTI)

    Elioff, T.

    1994-04-01

    This report contains the history of all estimated costs associated with the superconducting super collider.

  11. Life Cycle Cost Estimate

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    Life-cycle costs (LCCs) are all the anticipated costs associated with a project or program alternative throughout its life. This includes costs from pre-operations through operations or to the end of the alternative.This chapter discusses life cycle costs and the role they play in planning.

  12. Communication-Avoiding Algorithms for Linear Algebra and Beyond ...

    E-Print Network [OSTI]

    $author.value

    2015-10-12

    Oct 12, 2015 ... Communication costs (measured in time or energy per operation) ... of mathematics and computer science at University of California, Berkeley.

  13. Tracking the Sun IV: An Historical Summary of the Installed Cost of Photovoltaics in the United States from 1998 to 2010

    E-Print Network [OSTI]

    Darghouth, Naim

    2012-01-01

    Research. Bloomberg New Energy Finance. 2011. Levelized Cost2011, and Bloomberg New Energy Finance 42 specifies a cost

  14. Avoiding climate change uncertainties in Strategic Environmental Assessment

    SciTech Connect (OSTI)

    Larsen, Sanne Vammen; Křrnřv, Lone; Driscoll, Patrick

    2013-11-15

    This article is concerned with how Strategic Environmental Assessment (SEA) practice handles climate change uncertainties within the Danish planning system. First, a hypothetical model is set up for how uncertainty is handled and not handled in decision-making. The model incorporates the strategies ‘reduction’ and ‘resilience’, ‘denying’, ‘ignoring’ and ‘postponing’. Second, 151 Danish SEAs are analysed with a focus on the extent to which climate change uncertainties are acknowledged and presented, and the empirical findings are discussed in relation to the model. The findings indicate that despite incentives to do so, climate change uncertainties were systematically avoided or downplayed in all but 5 of the 151 SEAs that were reviewed. Finally, two possible explanatory mechanisms are proposed to explain this: conflict avoidance and a need to quantify uncertainty.

  15. Procuring and Implementing Solar Projects on Public Buildings: How to Avoid Common Pitfalls

    Broader source: Energy.gov [DOE]

    Procuring and Implementing Solar Projects on Public Buildings: How to Avoid Common Pitfalls Webinar.

  16. Scaling behavior of self-avoiding walks on percolation clusters

    E-Print Network [OSTI]

    Viktoria Blavatska; Wolfhard Janke

    2008-07-23

    The scaling behavior of self-avoiding walks (SAWs) on the backbone of percolation clusters in two, three and four dimensions is studied by Monte Carlo simulations. We apply the pruned-enriched Rosenbluth chain-growth method (PERM). Our numerical results bring about the estimates of critical exponents, governing the scaling laws of disorder averages of the end-to-end distance of SAW configurations. The effects of finite-size scaling are discussed as well.

  17. The pathogen transmission avoidance theory of sexual selection

    SciTech Connect (OSTI)

    Loehle, C.

    1997-08-01

    The current theory that sexual selection results from female preference for males with good genes suffers from several problems. An alternative explanation, the pathogen transmission avoidance hypothesis, argues that the primary function of showy traits is to provide a reliable signal of current disease status, so that sick individuals can be avoided during mating. This study shows that a significant risk of pathogen transmission occurs during mating and that showy traits are reliable indicators of current disease status. The origin of female choosiness is argued to lie in a general tendency to avoid sick individuals, even in the absence of showy traits, which originate as exaggerations of normal traits that are indicative of good health (bright feathers, vigorous movement, large size). Thus, in this new model the origins of both showy traits and female choosiness are not problematic and there is no threshold effect. This model predicts that when the possession of male showy traits does not help to reduce disease in the female, showy traits are unlikely to occur. This case corresponds to thorough exposure of every animal to all group pathogens, on average, in large groups. Such species are shown with a large data set on birds to be less likely to exhibit showy traits. The good-genes model does not make this prediction. The pathogen transmission avoidance model can also lead to the evolution of showy traits even when selection is not effective against a given pathogen (e.g., when there is no heritable variation for resistance), but can result in selection for resistance if such genes are present. Monogamy is argued to reduce selection pressures for showy traits; data show monogamous species to be both less parasitized and less showy. In the context of reduction of pathogen transmission rates in showy populations, selection pressure becomes inversely frequency-dependent, which makes showy traits likely to be self-limiting rather than runaway.

  18. Self-avoiding effective strings in lattice gauge theories

    E-Print Network [OSTI]

    M. Caselle; F. Gliozzi

    1991-11-28

    It is shown that the effective string recently introduced to describe the long distance dynamics of 3D gauge systems in the confining phase has an intriguing description in terms of models of 2D self-avoiding walks in the dense phase. The deconfinement point, where the effective string becomes N=2 supersymmetric, may then be interpreted as the tricritical Theta point where the polymer chain undergoes a collapse transition. As a consequence, a universal value of the deconfinement temperature is predicted.

  19. Financing Program Pitfalls to Avoid | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE:FinancingPetroleum12, 2015Executive Order14,Energy 9,UNIVERSITYDepartmentPitfalls to Avoid

  20. Direct/Indirect Costs

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    This chapter provides recommended categories for direct and indirect elements developed by the Committee for Cost Methods Development (CCMD) and describes various estimating techniques for direct and indirect costs.

  1. Power Plant Cycling Costs

    SciTech Connect (OSTI)

    Kumar, N.; Besuner, P.; Lefton, S.; Agan, D.; Hilleman, D.

    2012-07-01

    This report provides a detailed review of the most up to date data available on power plant cycling costs. The primary objective of this report is to increase awareness of power plant cycling cost, the use of these costs in renewable integration studies and to stimulate debate between policymakers, system dispatchers, plant personnel and power utilities.

  2. Sixth Northwest Conservation and Electric Power Plan Appendix G: MCS Cost-effectiveness for

    E-Print Network [OSTI]

    , cost and savings assumptions used to establish the efficiency level that achieves all electricity.............................................................................................................. 1 Measure Cost Assumptions savings that are cost-effective to the region's power system. The second section describes the methodology

  3. Variability in the Initial Costs of Care and One-Year Outcomes of Observation Services

    E-Print Network [OSTI]

    Abbass, Ibrahim

    2015-01-01

    Variability in the initial costs of care across theVariability in the Initial Costs of Care and One-Yearis associated with lower costs and comparable level of care

  4. Cost Contributors to Geothermal Power Production

    SciTech Connect (OSTI)

    Nathwani, Jay; Mines, Greg

    2011-07-01

    The US Department of Energy Geothermal Technologies Office (DOE-GTO) has developed the tool Geothermal Electricity Technologies Evaluation Model (GETEM) to assess the levelized cost of electricity (LCOE) of power produced from geothermal resources. Recently modifications to GETEM allow the DOE-GTO to better assess how different factors impact the generation costs, including initial project risk, time required to complete a development, and development size. The model characterizes the costs associated with project risk by including the costs to evaluate and drill those sites that are considered but not developed for commercial power generation, as well as to assign higher costs to finance those activities having more risk. This paper discusses how the important parameters impact the magnitude project costs for different project scenarios. The cost distributions presented include capital cost recovery for the exploration, confirmation, well field completion and power plant construction, as well as the operation and maintenance (O&M) costs. The paper will present these cost distributions for both EGS and hydrothermal resources.

  5. What is the Economic Cost of Climate Change?

    E-Print Network [OSTI]

    Hanemann, W. Michael

    2008-01-01

    Sea Level, California Climate Change Center, Report CEC-500-in the assessment of climate change damages: illustrationThe Economic Cost of Climate Change Impact on California

  6. NUCLEAR ENERGY SYSTEM COST MODELING

    SciTech Connect (OSTI)

    Francesco Ganda; Brent Dixon

    2012-09-01

    The U.S. Department of Energy’s Fuel Cycle Technologies (FCT) Program is preparing to perform an evaluation of the full range of possible Nuclear Energy Systems (NES) in 2013. These include all practical combinations of fuels and transmuters (reactors and sub-critical systems) in single and multi-tier combinations of burners and breeders with no, partial, and full recycle. As part of this evaluation, Levelized Cost of Electricity at Equilibrium (LCAE) ranges for each representative system will be calculated. To facilitate the cost analyses, the 2009 Advanced Fuel Cycle Cost Basis Report is being amended to provide up-to-date cost data for each step in the fuel cycle, and a new analysis tool, NE-COST, has been developed. This paper explains the innovative “Island” approach used by NE-COST to streamline and simplify the economic analysis effort and provides examples of LCAE costs generated. The Island approach treats each transmuter (or target burner) and the associated fuel cycle facilities as a separate analysis module, allowing reuse of modules that appear frequently in the NES options list. For example, a number of options to be screened will include a once-through uranium oxide (UOX) fueled light water reactor (LWR). The UOX LWR may be standalone, or may be the first stage in a multi-stage system. Using the Island approach, the UOX LWR only needs to be modeled once and the module can then be reused on subsequent fuel cycles. NE-COST models the unit operations and life cycle costs associated with each step of the fuel cycle on each island. This includes three front-end options for supplying feedstock to fuel fabrication (mining/enrichment, reprocessing of used fuel from another island, and/or reprocessing of this island’s used fuel), along with the transmuter and back-end storage/disposal. Results of each island are combined based on the fractional energy generated by each islands in an equilibrium system. The cost analyses use the probability distributions of key parameters and employs Monte Carlo sampling to arrive at an island’s cost probability density function (PDF). When comparing two NES to determine delta cost, strongly correlated parameters can be cancelled out so that only the differences in the systems contribute to the relative cost PDFs. For example, one comparative analysis presented in the paper is a single stage LWR-UOX system versus a two-stage LWR-UOX to LWR-MOX system. In this case, the first stage of both systems is the same (but with different fractional energy generation), while the second stage of the UOX to MOX system uses the same type transmuter but the fuel type and feedstock sources are different. In this case, the cost difference between systems is driven by only the fuel cycle differences of the MOX stage.

  7. APT cost scaling: Preliminary indications from a Parametric Costing Model (PCM)

    SciTech Connect (OSTI)

    Krakowski, R.A.

    1995-02-03

    A Parametric Costing Model has been created and evaluate as a first step in quantitatively understanding important design options for the Accelerator Production of Tritium (APT) concept. This model couples key economic and technical elements of APT in a two-parameter search of beam energy and beam power that minimizes costs within a range of operating constraints. The costing and engineering depth of the Parametric Costing Model is minimal at the present {open_quotes}entry level{close_quotes}, and is intended only to demonstrate a potential for a more-detailed, cost-based integrating design tool. After describing the present basis of the Parametric Costing Model and giving an example of a single parametric scaling run derived therefrom, the impacts of choices related to resistive versus superconducting accelerator structures and cost of electricity versus plant availability ({open_quotes}load curve{close_quotes}) are reported. Areas of further development and application are suggested.

  8. Cost Model for Digital Curation: Cost of Digital Migration

    E-Print Network [OSTI]

    Kejser, Ulla Břgvad; Nielsen, Anders Bo; Thirifays, Alex

    2009-01-01

    Steece, B. 2000. Software cost estimation with COCOMO II.Developing a Framework of Cost Elements for PreservingAshley, K. 1999. Digital archive costs: Facts and fallacies.

  9. LEDSGP/Transportation Toolkit/Strategies/Avoid | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on QA:QA J-E-1 SECTION J APPENDIXsource History ViewInformation Actions(Redirected fromAvoid < LEDSGP‎ |

  10. Cost-Informed Operational Process Support M. T. Wynn1

    E-Print Network [OSTI]

    van der Aalst, Wil

    Cost-Informed Operational Process Support M. T. Wynn1 , H. A. Reijers2,3 , M. Adams1 , C. Ouyang1 operations in alignment with the true origins of costs, and to be informed about this on a real-time basis, allows businesses to increase profitability. In most organisations however, high-level cost

  11. Facility Location with Hierarchical Facility Costs Zoya Svitkina #

    E-Print Network [OSTI]

    Tardos, Ă?va

    Facility Location with Hierarchical Facility Costs Zoya Svitkina # â?? Eva Tardos + Abstract We consider the facility location problem with hierarchi­ cal facility costs, and give a (4 installation costs. Shmoys, Swamy and Levi [13] gave an approxi­ mation algorithm for a two­level version

  12. Future singularity avoidance in phantom dark energy models

    E-Print Network [OSTI]

    Jaume de Haro

    2012-06-11

    Different approaches to quantum cosmology are studied in order to deal with the future singularity avoidance problem. Our results show that these future singularities will persist but could take different forms. As an example we have studied the big rip which appear when one considers the state equation $P=\\omega\\rho$ with $\\omega<-1$, showing that it does not disappear in modified gravity. On the other hand, it is well-known that quantum geometric effects (holonomy corrections) in loop quantum cosmology introduce a quadratic modification, namely proportional to $\\rho^2$, in Friedmann's equation that replace the big rip by a non-singular bounce. However this modified Friedmann equation could have been obtained in an inconsistent way, what means that the obtained results from this equation, in particular singularity avoidance, would be incorrect. In fact, we will show that instead of a non-singular bounce, the big rip singularity would be replaced, in loop quantum cosmology, by other kind of singularity.

  13. WP2 IEA Wind Task 26:The Past and Future Cost of Wind Energy

    E-Print Network [OSTI]

    Lantz, Eric

    2014-01-01

    2011b). Development in LCOE for Wind Turbines in Denmark.levelized cost of energy (LCOE) analyses are shown in Tablethe levelized cost of energy (LCOE) for onshore wind energy.

  14. Environmental Cost Analysis 

    E-Print Network [OSTI]

    Edge, D.

    2000-01-01

    Analysis David Edge Texas Natural Resource Conservation Commission 131 ESL-IE-00-04-21 Proceedings from the Twenty-second National Industrial Energy Technology Conference, Houston, TX, April 5-6, 2000 Tuas Natural Resource Conservation Cor...DDliuion Environmental Cost Analysis Presented By David Edge Determine the Costs c> Input co Output c> Hidden c> Capital (non recurring) Envirormenlal Cost Analy.;is "There has to be a measurable result ofimprovement and it should be tied to dollars...

  15. PHEV Battery Cost Assessment

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Program Modeling Advanced Li-ion Couples 13 Courtesy of Junbing Yang & K. Amine Graphite with LNMO and LMRNMC similar in cost and energy density LMRNMC shows synergy...

  16. Hydrogen and Infrastructure Costs

    Broader source: Energy.gov (indexed) [DOE]

    FUEL CELL TECHNOLOGIES PROGRAM Hydrogen and Infrastructure Costs Hydrogen Infrastructure Market Readiness Workshop Washington D.C. February 17, 2011 Fred Joseck U.S. Department of...

  17. SOFT COST GRAND CHALLENGE

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    energycenter.org California Center for Sustainable Energy Soft Cost Grand Challenge May 22, 2014 Accelerating the transition to a sustainable world powered by clean energy 2...

  18. Apportioning Climate Change Costs

    E-Print Network [OSTI]

    Farber, Daniel A.

    2008-01-01

    Apportioning Climate Change Costs Daniel A. Farber* I. II.ON CLIMATE CHANGE FOUR QUESTIONS ABOUTof how to respond to climate change. Most public attention

  19. Avoiding and Managing Interruptions of Electric Service Under an Interruptible Contract or Tariff 

    E-Print Network [OSTI]

    Evans, G. W.

    1995-01-01

    the customer to verify, after the fact, that an actual interruption could not have been avoided. The industrial should have the right to verify that the utility made every reasonable effort to avoid the interruption. Hourly generation data, load data...

  20. Cost and Trust Issues in On-Line Auctions Lyle H. Ungar1, David C. Parkes2, and Dean P. Foster3

    E-Print Network [OSTI]

    Chen, Yiling

    , and avoiding the communication costs of the multiple bids of a rst-price ascending English" auction to a buyer of strategic bidding in an auction, given a reservation price, but the cost of deciding whatCost and Trust Issues in On-Line Auctions Lyle H. Ungar1, David C. Parkes2, and Dean P. Foster3 1

  1. Procuring and Implementing Solar Projects on Public Buildings: How to Avoid Common Pitfalls (Text Version)

    Broader source: Energy.gov [DOE]

    Transcript of the webinar, "Procuring and Implementing Solar Projects on Public Buildings: How to Avoid Common Pitfalls."

  2. AGRICULTURAL BMP PLACEMENT FOR COST-EFFECTIVE POLLUTION CONTROL

    E-Print Network [OSTI]

    Coello, Carlos A. Coello

    AGRICULTURAL BMP PLACEMENT FOR COST-EFFECTIVE POLLUTION CONTROL AT THE WATERSHED LEVEL Tamie Lynne-EFFECTIVE POLLUTION CONTROL AT THE WATERSHED LEVEL Tamie Lynne Veith Abstract The overall goal of this research was to increase, relative to targeting recommendations, the cost-effectiveness of pollution reduction measures

  3. Tracking the Sun III; The Installed Cost of Photovoltaics in the United States from 1998-2009

    E-Print Network [OSTI]

    Barbose, Galen

    2011-01-01

    level cost data provided by the California Solar Initiative,data for 2010 indicate that the average cost of systems installed through the California Solar

  4. An Analysis of the Costs, Benefits, and Implications of Different Approaches to Capturing the Value of Renewable Energy Tax Incentives

    E-Print Network [OSTI]

    Bolinger, Mark

    2014-01-01

    levelized cost of energy (“LCOE”). Tax Equity Yield (after-power closer to achieving LCOE goals (and at no additionallevelized cost of energy (“LCOE”). 3. Model Descriptions and

  5. Receiver Antenna Array for a Multichannel Sense-and-Avoid Radar for Small UAVs

    E-Print Network [OSTI]

    Kansas, University of

    Receiver Antenna Array for a Multichannel Sense-and-Avoid Radar for Small UAVs Jose Francisco for use in a sense-and-avoid radar for use in the Cessna C-172 and small Unmanned Aerial Vehicles (UAVs. . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . ..10 1.1.1 Multichannel Sense-and-Avoid Radar for UAVs. . . . . . . . . . . . . . . . . . . . . . ...10

  6. Three-dimensional terminally attached self-avoiding walks and bridges

    E-Print Network [OSTI]

    Nathan Clisby; Andrew R. Conway; Anthony J. Guttmann

    2015-07-24

    We study terminally attached self-avoiding walks and bridges on the simple cubic lattice, both by series analysis and Monte Carlo methods. We provide strong numerical evidence supporting a scaling relation between self-avoiding walks, bridges, and terminally attached self-avoiding walks, and posit that a corresponding amplitude ratio is a universal quantity.

  7. New Berkeley Lab Report Tracks a Decade of PV Installed Cost Trends

    SciTech Connect (OSTI)

    Barbose, Galen; Peterman, Carla; Wiser, Ryan

    2009-04-15

    Installations of PV systems have been expanding at a rapid pace in recent years. In the United States, the market for PV is driven by national, state, and local government incentives, including upfront cash rebates, production-based incentives, requirements that electricity suppliers purchase a certain amount of solar energy, and Federal and state tax benefits. These programs are, in part, motivated by the popular appeal of solar energy and by the positive attributes of PV - e.g., modest environmental impacts, avoidance of fuel price risks, coincidence with peak electrical demand, and the location of PV at the point of use. Given the relatively high cost of PV, however, a key goal of these policies is to encourage cost reductions over time. Therefore, as policy incentives have become more significant and as PV deployment has accelerated, so too has the desire to track the installed cost of PV systems over time, by system characteristics, by system location, and by component. A new Lawrence Berkeley National Laboratory report, 'Tracking the Sun: The Installed Cost of Photovoltaics in the U.S. from 1998-2007', helps to fill this need by summarizing trends in the installed cost (i.e., the cost paid by the system owner) of grid-connected PV systems in the U.S. The report is based on an analysis of project-level cost data from nearly 37,000 residential and non-residential PV systems completed from 1998-2007 and installed on the utility-customer-side of the meter. These systems total 363 MW, equal to 76% of all grid-connected PV capacity installed in the U.S. through 2007, representing the most comprehensive data source available on the installed cost of PV in the United States. The data were obtained from administrators of PV incentive programs around the country, who typically collect installed cost data for systems receiving incentives. A total of 16 programs, spanning 12 states, ultimately provided data for the study. Reflecting the broader geographical trends in the U.S. PV market, the vast majority of the systems in the data sample are located in California (83%, by capacity) and New Jersey (12%), The remaining systems are located in Arizona, Connecticut, Illinois, Massachusetts, Maryland, Minnesota, New York, Oregon, Pennsylvania, and Wisconsin. The PV systems in the dataset range in size from 100 W to 1.3 MW, almost 90% of which are smaller than 10 kW. This article briefly summarizes some of the key findings from the Berkeley Lab study (the full report can be downloaded at http://eetd.lbl.gov/ea/emp/re-pubs.html). The article begins by summarizing trends related to the installed cost of PV systems prior to receipt of any financial incentives, and then discusses how changes in incentive levels over time and variation across states have impacted the net installed cost of PV to the customer, after receipt of incentives. Note that all cost and incentive data are presented in real 2007 dollars (2007$), and all capacity and dollars-perwatt ($/W) data are presented in terms of rated module power output under Standard Test Conditions (DC-STC).

  8. NPR (New Production Reactor) capacity cost evaluation

    SciTech Connect (OSTI)

    1988-07-01

    The ORNL Cost Evaluation Technical Support Group (CETSG) has been assigned by DOE-HQ Defense Programs (DP) the task defining, obtaining, and evaluating the capital and life-cycle costs for each of the technology/proponent/site/revenue possibilities envisioned for the New Production Reactor (NPR). The first part of this exercise is largely one of accounting, since all NPR proponents use different accounting methodologies in preparing their costs. In order to address this problem of comparing ''apples and oranges,'' the proponent-provided costs must be partitioned into a framework suitable for all proponents and concepts. If this is done, major cost categories can then be compared between concepts and major cost differences identified. Since the technologies proposed for the NPR and its needed fuel and target support facilities vary considerably in level of technical and operational maturity, considerable care must be taken to evaluate the proponent-derived costs in an equitable manner. The use of cost-risk analysis along with derivation of single point or deterministic estimates allows one to take into account these very real differences in technical and operational maturity. Chapter 2 summarizes the results of this study in tabular and bar graph form. The remaining chapters discuss each generic reactor type as follows: Chapter 3, LWR concepts (SWR and WNP-1); Chapter 4, HWR concepts; Chapter 5, HTGR concept; and Chapter 6, LMR concept. Each of these chapters could be a stand-alone report. 39 refs., 36 figs., 115 tabs.

  9. Forecasting technology costs via the Learning Curve - Myth or Magic?

    E-Print Network [OSTI]

    Alberth, Stephan

    Gas Turbine (CCGT) where data provided by Colpier was already converted from ‘costs per installed capacity’ to ‘costs per electricity produced’ (2002). The focus has been on technologies that remained in their growth stages in order to avoid... Electricity Usc(90)/kWh - TWh 1981 1997 15 3.6 Cleason Colpier 2002 Nuclear Instalation US$(90)/W - GW 1975 1993 19 2.0 Kouvaritakis et al. (2000) in M&S 2001 SCGT Instalation US$(90)/W - GW 1956 1981 14 8.9 IIASA-WEC (1998), p.50 Solar Production $/Wp - MWp...

  10. Hydrogen refueling station costs in Shanghai

    E-Print Network [OSTI]

    Weinert, Jonathan X.; Shaojun, Liu; Ogden, Joan M; Jianxin, Ma

    2007-01-01

    station and equipment costs Capital equipment costs Non-a function of capital cost and is therefore represented intechnology and therefore capital cost and maintenance cost

  11. Cost Transfer Procedures How And When To Make Cost Transfers

    E-Print Network [OSTI]

    Hammack, Richard

    Cost Transfer Procedures How And When To Make Cost Transfers Effective February 9, 2003, cost elsewhere. Federal regulations require additional documentation to support cost transfers to sponsored program indexes. Costs may not be shifted to other research projects or from one budget period to the next

  12. Cost Estimating Guide

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2011-05-09

    This Guide provides uniform guidance and best practices that describe the methods and procedures that could be used in all programs and projects at DOE for preparing cost estimates. No cancellations.

  13. Vehicle Cost Calculator

    Alternative Fuels and Advanced Vehicles Data Center [Office of Energy Efficiency and Renewable Energy (EERE)]

    fuel cost and emissions with a conventional vehicle. Select FuelTechnology Electric Hybrid Electric Plug-in Hybrid Electric Natural Gas (CNG) Flex Fuel (E85) Biodiesel (B20)...

  14. cost.f

    E-Print Network [OSTI]

    SUBROUTINE COST (N,X,WSAVE) IMPLICIT DOUBLE PRECISION (A-H, O-Z) DIMENSION X(1) ,WSAVE(1) NM1 = N-1 NP1 = N+1 NS2 = N/2 IF (N-2) ...

  15. Implications of Cost Effectiveness Screening Practices in a Low Natural Gas Price Environment: Case Study of a Midwestern Residential Energy Upgrade Program

    E-Print Network [OSTI]

    Hoffman, Ian M.

    2014-01-01

    benefits, including avoided energy, capacity, transmissionKrop, R. (May 2010). Non-Energy Benefits: Status, Findings,costs. Screening a Home Energy Upgrade Program in a Low Gas

  16. Transparent Cost Database | Transparent Cost Database

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page| Open Energy Information Serbia-EnhancingEt Al., 2013)OpenEnergyTrail Canyonsource History View NewTransparent Cost

  17. Rocky Flats Closure Unit Cost Data

    SciTech Connect (OSTI)

    Sanford, P.C.; Skokan, B.

    2007-07-01

    The Rocky Flats Closure Project has completed the process of stabilizing residual nuclear materials, decommissioning nuclear facilities, remediating environmental media and closing the Rocky Flats Site (Site). The project cost approximately $4.1 B and included the decommissioning of over 700 structures including 5 major plutonium facilities and 5 major uranium facilities, shipping over 14,600 cubic meters of transuranic and 565,000 cubic meters of low level radioactive waste, and remediating a 385-acre industrial area and the surrounding land. Actual costs were collected for a large variety of closure activities. These costs can be correlated with metrics associated with the facilities and environmental media to capture cost factors from the project that could be applicable to a variety of other closure projects both within and outside of the Department of Energy's weapons complex. The paper covers four general topics: the process to correlate the actual costs and metrics, an example of the correlated data for one large sub-project, a discussion of the results, and the additional activities that are planned to correlate and make this data available to the public. The process to collect and arrange the project control data of the Closure Project relied on the actual Closure Project cost information. It was used to correlate these actual costs with the metrics for the physical work, such as building area or waste generated, to support the development of parametric cost factors. The example provides cost factors for the Industrial Sites Project. The discussion addresses the strengths and weaknesses of the data, followed by a section identifying future activities to improve and extend the analyses and integrate it within the Department's Environmental Cost Analysis System. (authors)

  18. Truck transport of RAM: Risk effects of avoiding metropolitan areas

    SciTech Connect (OSTI)

    Mills, G.S.; Neuhauser, K.S.

    1997-11-01

    In the transport of radioactive material (RAM), e.g., spent nuclear fuel (SNF), stakeholders are generally most concerned about risks in high population density areas along transportation routes because of the perceived high consequences of potential accidents. The most significant portions of a transcontinental route and an alternative examined previously were evaluated again using population density data derived from US Census Block data. This method of characterizing population that adjoins route segments offers improved resolution of population density variations, especially in high population density areas along typical transport routes. Calculated incident free doses and accident dose risks for these routes, and the rural, suburban and urban segments are presented for comparison of their relative magnitudes. The results indicate that modification of this route to avoid major metropolitan areas through use of non-Interstate highways increases total risk yet does not eliminate a relatively small urban component of the accident dose risk. This conclusion is not altered by improved resolution of route segments adjoining high density populations.

  19. Avoiding the Haircut: Potential Ways to Enhance the Value of the USDA's Section 9006 Program

    E-Print Network [OSTI]

    Bolinger, Mark

    2006-01-01

    at $1,600/kW capital cost) Wind Project Capital Cost ($/kW)depending on the wind project’s capital cost and capacitythat 90% of the total costs of a wind project qualify for 5-

  20. Innovative Feed-In Tariff Designs that Limit Policy Costs

    SciTech Connect (OSTI)

    Kreycik, Claire; Couture, Toby D.; Cory, Karlynn S.

    2011-06-01

    Feed-in tariffs (FITs) are the most prevalent policy used globally to reduce development risks, cut financing costs, and grow the renewable energy industry. However, concerns over escalating costs in jurisdictions with FIT policies have led to increased attention on cost control. Using case studies and market-focused analysis, this report from the National Renewable Energy Laboratory (NREL) examines strengths and weaknesses of three cost-containment tools: (1) caps, (2) payment level adjustment mechanisms, and (3) auction-based designs. The report provides useful insights on containing costs for policymakers and regulators in the United States and other areas where FIT policies are in development.

  1. Cost Model for Digital Curation: Cost of Digital Migration

    E-Print Network [OSTI]

    Kejser, Ulla Břgvad; Nielsen, Anders Bo; Thirifays, Alex

    2009-01-01

    Curation: Cost of Digital Migration Ulla Břgvad Kejser, Thefocus especially on costing digital migration activities. Inof the OAIS Model digital migration includes both transfer (

  2. Cost Model for Digital Curation: Cost of Digital Migration

    E-Print Network [OSTI]

    Kejser, Ulla Břgvad; Nielsen, Anders Bo; Thirifays, Alex

    2009-01-01

    and Monitor Technology functions each consists of two costinfluence, the fewer costs. Monitor Technology depends onCost Critical Activities Monitor community Report on monitoring Monitor technology

  3. QGESS: Capital Cost Scaling Methodology

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    the tonnes of CO2 utilized. The costs of the process are to include infrastructure, raw materials, processing, byproduct disposal, and utilities costs, as well as any other costs....

  4. Cost-effective ecological restoration

    E-Print Network [OSTI]

    2015-01-01

    whether the cost-effectiveness index in the all seed mixesRestoration cost-effectiveness (index calculated as percentwith the highest cost-effectiveness index values were drill

  5. Factors Impacting Decommissioning Costs - 13576

    SciTech Connect (OSTI)

    Kim, Karen; McGrath, Richard [Electric Power Research Institute, 3420 Hillview Ave., Palo Alto, California (United States)] [Electric Power Research Institute, 3420 Hillview Ave., Palo Alto, California (United States)

    2013-07-01

    The Electric Power Research Institute (EPRI) studied United States experience with decommissioning cost estimates and the factors that impact the actual cost of decommissioning projects. This study gathered available estimated and actual decommissioning costs from eight nuclear power plants in the United States to understand the major components of decommissioning costs. Major costs categories for decommissioning a nuclear power plant are removal costs, radioactive waste costs, staffing costs, and other costs. The technical factors that impact the costs were analyzed based on the plants' decommissioning experiences. Detailed cost breakdowns by major projects and other cost categories from actual power plant decommissioning experiences will be presented. Such information will be useful in planning future decommissioning and designing new plants. (authors)

  6. Renewable Energy Cost Modeling. A Toolkit for Establishing Cost-Based Incentives in the United States

    SciTech Connect (OSTI)

    Gifford, Jason S.; Grace, Robert C.; Rickerson, Wilson H.

    2011-05-01

    This report serves as a resource for policymakers who wish to learn more about levelized cost of energy (LCOE) calculations, including cost-based incentives. The report identifies key renewable energy cost modeling options, highlights the policy implications of choosing one approach over the other, and presents recommendations on the optimal characteristics of a model to calculate rates for cost-based incentives, FITs, or similar policies. These recommendations shaped the design of NREL's Cost of Renewable Energy Spreadsheet Tool (CREST), which is used by state policymakers, regulators, utilities, developers, and other stakeholders to assist with analyses of policy and renewable energy incentive payment structures. Authored by Jason S. Gifford and Robert C. Grace of Sustainable Energy Advantage LLC and Wilson H. Rickerson of Meister Consultants Group, Inc.

  7. Review of storage battery system cost estimates

    SciTech Connect (OSTI)

    Brown, D.R.; Russell, J.A.

    1986-04-01

    Cost analyses for zinc bromine, sodium sulfur, and lead acid batteries were reviewed. Zinc bromine and sodium sulfur batteries were selected because of their advanced design nature and the high level of interest in these two technologies. Lead acid batteries were included to establish a baseline representative of a more mature technology.

  8. NREL-Levelized Cost of Energy Calculator | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on QA:QAsource History ViewMayo, Maryland:NPI Ventures Ltd Jump to: navigation, search Name:NREL's RenewableOpen

  9. Levelized Cost of Energy in US | OpenEI Community

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on QA:QA J-E-1 SECTION J APPENDIX E LISTStar2-0057-EAInvervarLeeds, United Kingdom: Energy ResourcesEnergyCoAfrica

  10. Electricity production levelized costs for nuclear, gas and coal

    Office of Scientific and Technical Information (OSTI)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of NaturalDukeWakefield MunicipalTechnical Report:Speeding accessby aLED Street Lighting Host Site:ERDACarlo-integrated

  11. OpenEI Community - levelized cost of energy

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on QA:QA J-E-1 SECTION J APPENDIXsourceII JumpQuarterly Smart Grid Data available for download onst,/0 enBigWater Power

  12. Overview of Levelized Cost of Energy in the AEO

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming Dry NaturalPrices1Markets16 (next20, 20082008707

  13. Optimization Online - Sharing Supermodular Costs

    E-Print Network [OSTI]

    Andreas S. Schulz

    2007-08-28

    Aug 28, 2007 ... Abstract: We study cooperative games with supermodular costs. We show that supermodular costs arise in a variety of situations: in particular, ...

  14. Preemptive scheduling with position costs

    E-Print Network [OSTI]

    In most scheduling models presented in the literature [3, 10], the cost for ... Preemptive scheduling in order to minimize the total position costs also stems.

  15. OPTIONS - ALLOCATION FUNDS - TRANSACTION COSTS

    E-Print Network [OSTI]

    Admin

    2009-03-25

    One first problem to overcome is the impact of transaction costs. ... They entail a reduction of transaction costs and improve the investor's economic welfare.

  16. Cost Analysis of Mobility Management Entities of Md. Shohrab Hossain, Mohammed Atiquzzaman

    E-Print Network [OSTI]

    Atiquzzaman, Mohammed

    Cost Analysis of Mobility Management Entities of SINEMO Md. Shohrab Hossain, Mohammed Atiquzzaman results in higher level of signalling cost on the mobility agents in a mobility protocol. Previous cost analysis on mobility protocols have not considered all possible costs for mobility management, resulting

  17. Minimum-Cost Tolerance Allocation ADCATS Report No. 99-5

    E-Print Network [OSTI]

    Minimum-Cost Tolerance Allocation ADCATS Report No. 99-5 Kenneth W. Chase Department of Mechanical-all cost of production, while meeting target levels for quality. Using allocation tools, a designer may re and loosening tolerances on costly processes, for a net reduction in cost. Several algorithms are described

  18. Low Cost, Durable Seal

    SciTech Connect (OSTI)

    Roberts, George; Parsons, Jason; Friedman, Jake

    2010-12-17

    Seal durability is critical to achieving the 2010 DOE operational life goals for both stationary and transportation PEM fuel cell stacks. The seal material must be chemically and mechanically stable in an environment consisting of aggressive operating temperatures, humidified gases, and acidic membranes. The seal must also be producible at low cost. Currentlyused seal materials do not meet all these requirements. This project developed and demonstrated a high consistency hydrocarbon rubber seal material that was able to meet the DOE technical and cost targets. Significant emphasis was placed on characterization of the material and full scale molding demonstrations.

  19. Is There Still Time to Avoid `Dangerous Anthropogenic Interference' with Global Climate?*#

    E-Print Network [OSTI]

    Hansen, James E.

    Is There Still Time to Avoid `Dangerous Anthropogenic Interference' with Global Climate on humans and wildlife, and constitute "dangerous anthropogenic interference" with nature. The Earth

  20. Swimming in Flavored Water Leads to Avoidance of that Flavor in Laboratory Rats (Rattus Norvegicus)

    E-Print Network [OSTI]

    Nakajima, Sadahiko

    2015-01-01

    study. The rat-in-flavored-water procedure, thus, departsreviewed Swimming in Flavored Water Leads to Avoidance ofthat swam in the flavored water. A statistically reliable

  1. Avoiding 100 New Power Plants by Increasing Efficiency of Room Air Conditioners in India: Opportunities and Challenges

    SciTech Connect (OSTI)

    Phadke, Amol; Abhyankar, Nikit; Shah, Nihar

    2014-06-19

    Electricity demand for room ACs is growing very rapidly in emerging economies such as India. We estimate the electricity demand from room ACs in 2030 in India considering factors such as weather and income growth using market data on penetration of ACs in different income classes and climatic regions. We discuss the status of the current standards, labels, and incentive programs to improve the efficiency of room ACs in these markets and assess the potential for further large improvements in efficiency and find that efficiency can be improved by over 40percent cost effectively. The total potential energy savings from Room AC efficiency improvement in India using the best available technology will reach over 118 TWh in 2030; potential peak demand saving is found to be 60 GW by 2030. This is equivalent to avoiding 120 new coal fired power plants of 500 MW each. We discuss policy options to complement, expand and improve the ongoing programs to capture this large potential.

  2. Avoiding 100 new power plants by increasing efficiency of room air conditioners in India: opportunities and challenges

    SciTech Connect (OSTI)

    Phadke, Amol; Abhyankar, Nikit; Shah, Nihar

    2013-10-15

    Electricity demand for room ACs is growing very rapidly in emerging economies such as India. We estimate the electricity demand from room ACs in 2030 in India considering factors such as weather and income growth using market data on penetration of ACs in different income classes and climatic regions. We discuss the status of the current standards, labels, and incentive programs to improve the efficiency of room ACs in these markets and assess the potential for further large improvements in efficiency and find that efficiency can be improved by over 40% cost effectively. The total potential energy savings from Room AC efficiency improvement in India using the best available technology will reach over 118 TWh in 2030; potential peak demand saving is found to be 60 GW by 2030. This is equivalent to avoiding 120 new coal fired power plants of 500 MW each. We discuss policy options to complement, expand and improve the ongoing programs to capture this large potential.

  3. Policy on Cost Sharing Policy on Cost Sharing

    E-Print Network [OSTI]

    Sridhar, Srinivas

    Policy on Cost Sharing 12/26/2014 Policy on Cost Sharing I. Purpose and Scope Northeastern University does not encourage cost sharing commitments in sponsored research, and generally will not commit for approval for cost sharing arrangements, and explains the requirements for how any such arrangements

  4. Policy on Cost Transfer Policy on Cost Transfer

    E-Print Network [OSTI]

    Sridhar, Srinivas

    Policy on Cost Transfer 12/22/2014 Policy on Cost Transfer I. Purpose and Scope The University has posting of a cost to the general ledger, initiated by payroll charges, purchase orders or check requests (and the purchasing card). Cost Transfer means any subsequent transfer of the original charge

  5. Cost Sharing -1 -Approved: 01/07/2013 Cost Sharing

    E-Print Network [OSTI]

    Hammack, Richard

    Cost Sharing - 1 - Approved: 01/07/2013 Cost Sharing Policy Type: Administrative Responsible Office and Purpose The purpose of this policy is to define VCU's cost-sharing policy for sponsored programs. The university will make a cost-sharing commitment only when required by the sponsor or by the competitive nature

  6. FACILITIES AND ADMINISTRATIVE (F&A) COST AND IDC RATES The cost of conducting research consists of two broad types of costs direct costs and facilities and

    E-Print Network [OSTI]

    Keinan, Alon

    FACILITIES AND ADMINISTRATIVE (F&A) COST AND IDC RATES The cost of conducting research consists of two broad types of costs ­ direct costs and facilities and administrative costs (F&A), also known as indirect costs. Direct

  7. Heliostat cost reduction study.

    SciTech Connect (OSTI)

    Jones, Scott A.; Lumia, Ronald. (University of New Mexico, Albuquerque, NM); Davenport, Roger (Science Applications International Corporation, San Diego, CA); Thomas, Robert C. (Advanced Thermal Systems, Centennial, CO); Gorman, David (Advanced Thermal Systems, Larkspur, CO); Kolb, Gregory J.; Donnelly, Matthew W.

    2007-06-01

    Power towers are capable of producing solar-generated electricity and hydrogen on a large scale. Heliostats are the most important cost element of a solar power tower plant. Since they constitute {approx} 50% of the capital cost of the plant it is important to reduce heliostat cost as much as possible to improve the economic performance of power towers. In this study we evaluate current heliostat technology and estimate a price of $126/m{sup 2} given year-2006 materials and labor costs for a deployment of {approx}600 MW of power towers per year. This 2006 price yields electricity at $0.067/kWh and hydrogen at $3.20/kg. We propose research and development that should ultimately lead to a price as low as $90/m{sup 2}, which equates to $0.056/kWh and $2.75/kg H{sup 2}. Approximately 30 heliostat and manufacturing experts from the United States, Europe, and Australia contributed to the content of this report during two separate workshops conducted at the National Solar Thermal Test Facility.

  8. Driving Demand for Home Energy Improvements: Motivating residential customers to invest in comprehensive upgrades that eliminate energy waste, avoid high utility bills, and spur the economy

    SciTech Connect (OSTI)

    Fuller, Merrian C.

    2010-09-20

    Policy makers and program designers in the U.S. and abroad are deeply concerned with the question of how to scale up energy efficiency to a level that is commensurate both to the scale of the energy and climate challenges we face, and to the potential for energy savings that has been touted for decades. When policy makers ask what energy efficiency can do, the answers usually revolve around the technical and economic potential of energy efficiency - they rarely hone in on the element of energy demand that matters most for changing energy usage in existing homes: the consumer. A growing literature is concerned with the behavioral underpinnings of energy consumption. We examine a narrower, related subject: How can millions of Americans be persuaded to divert valued time and resources into upgrading their homes to eliminate energy waste, avoid high utility bills, and spur the economy? With hundreds of millions of public dollars flowing into incentives, workforce training, and other initiatives to support comprehensive home energy improvements, it makes sense to review the history of these programs and begin gleaning best practices for encouraging comprehensive home energy improvements. Looking across 30 years of energy efficiency programs that targeted the residential market, many of the same issues that confronted past program administrators are relevant today: How do we cost-effectively motivate customers to take action? Who can we partner with to increase program participation? How do we get residential efficiency programs to scale? While there is no proven formula - and only limited success to date with reliably motivating large numbers of Americans to invest in comprehensive home energy improvements, especially if they are being asked to pay for a majority of the improvement costs - there is a rich and varied history of experiences that new programs can draw upon. Our primary audiences are policy makers and program designers - especially those that are relatively new to the field, such as the over 2,000 towns, cities, states, and regions who are recipients of American Reinvestment and Recovery Act funds for clean energy programs. This report synthesizes lessons from first generation programs, highlights emerging best practices, and suggests methods and approaches to use in designing, implementing, and evaluating these programs. We examined 14 residential energy efficiency programs, conducted an extensive literature review, interviewed industry experts, and surveyed residential contractors to draw out these lessons.

  9. adopt our eco-driving top tips to reduce fuel costs

    E-Print Network [OSTI]

    Harman, Neal.A.

    adopt our eco-driving top tips to reduce fuel costs and accident risk Drive smoothly · Anticipate this will activate the fuel cut-off switch, reducing fuel flow to virtually zero. Shift up early · When accelerating, when appropriate. Avoid excessive speed High speeds greatly increase fuel consumption. Keep tyres

  10. Costs, Savings and Financing Bulk Tanks on Texas Dairy Farms. 

    E-Print Network [OSTI]

    Moore, Donald S.; Stelly, Randall; Parker, Cecil A.

    1958-01-01

    ,s - / cwdh\\@ Costs, Savi~gs;.itd Financing Bulk Tanks on Texas Dairy Farms . ?. I I 1 i I I ! ,:ravings in hauling - 10 cents I \\ \\ 1 \\ savings in hauling - 15 cents -----------____--- 'savings in hauling - 20 cents Annual production..., 1,000 pounds Estimated number of years required for savings from a bulk tank to equal additional costs at different levels of production and savings in hauling costs. TEXAS AGRICULTURAL EXPERIMEN'T STATION R. D. LEWIS. DIRECTOR. COLLEGE STATION...

  11. Transaction Costs, Information Technology and Development

    E-Print Network [OSTI]

    Singh, Nirvikar

    2004-01-01

    Transaction Costs, Information Technology and Development 1.Transaction Costs, Information Technology and DevelopmentTransaction Costs, Information Technology and Development *

  12. Transaction Costs, Information Technology and Development

    E-Print Network [OSTI]

    Singh, Nirvikar

    2004-01-01

    Transaction Costs, Information Technology and Development 1.Transaction Costs, Information Technology and DevelopmentTransaction Costs, Information Technology and Development

  13. Cost and Potential of Monolithic CIGS Photovoltaic Modules

    SciTech Connect (OSTI)

    Horowitz, Kelsey; Woodhouse, Michael

    2015-06-17

    A bottom-up cost analysis of monolithic, glass-glass Cu(In,Ga)(Se,S)2 (CIGS) modules is presented, illuminating current cost drivers for this technology and possible pathways to reduced cost. At 14% module efficiency, for the case of U.S. manufacturing, a manufacturing cost of $0.56/WDC and a minimum sustainable price of $0.72/WDC were calculated. Potential for reduction in manufacturing costs to below $0.40/WDC in the long-term may be possible if module efficiency can be increased without significant increase in $/m2 costs. The levelized cost of energy (LCOE) in Phoenix, AZ under different conditions is assessed and compared to standard c-Si.

  14. Cost and Performance Assumptions for Modeling Electricity Generation Technologies

    SciTech Connect (OSTI)

    Tidball, R.; Bluestein, J.; Rodriguez, N.; Knoke, S.

    2010-11-01

    The goal of this project was to compare and contrast utility scale power plant characteristics used in data sets that support energy market models. Characteristics include both technology cost and technology performance projections to the year 2050. Cost parameters include installed capital costs and operation and maintenance (O&M) costs. Performance parameters include plant size, heat rate, capacity factor or availability factor, and plant lifetime. Conventional, renewable, and emerging electricity generating technologies were considered. Six data sets, each associated with a different model, were selected. Two of the data sets represent modeled results, not direct model inputs. These two data sets include cost and performance improvements that result from increased deployment as well as resulting capacity factors estimated from particular model runs; other data sets represent model input data. For the technologies contained in each data set, the levelized cost of energy (LCOE) was also evaluated, according to published cost, performance, and fuel assumptions.

  15. Transition-cost issues for a restructuring US electricity industry

    SciTech Connect (OSTI)

    NONE

    1997-03-01

    Utilities regulators can use a variety of approaches to calculate transition costs. We categorized these approaches along three dimensions. The first dimension is the use of administrative vs. market procedures to value the assets in question. Administrative approaches use analytical techniques to estimate transition costs. Market valuation relies on the purchase price of particular assets to determine their market values. The second dimension concerns when the valuation is done, either before or after the restructuring of the electricity industry. The third dimension concerns the level of detail involved in the valuation, what is often called top-down vs. bottom-up valuation. This paper discusses estimation approaches, criteria to assess estimation methods, specific approaches to estimating transition costs, factors that affect transition-cost estimates, strategies to address transition costs, who should pay transition costs, and the integration of cost recovery with competitive markets.

  16. MEMO OF UNDERSTANDING Service Cost

    E-Print Network [OSTI]

    Jacobs, Lucia

    MEMO OF UNDERSTANDING Service Cost July 2013 1/4 Thera Kalmijn Chief Operating Officer 1608 Fourth] [Division Name] Re: CSS Service Cost for Fiscal Year 2013 - 2015 Please find the service cost for [Division [Division Name] implements into CSS. The service cost for [Division Name] will remain fixed throughout

  17. Robust Cost Colorings Takuro Fukunaga

    E-Print Network [OSTI]

    Halldórsson, Magnús M.

    Robust Cost Colorings Takuro Fukunaga Magn´us M. Halld´orsson Hiroshi Nagamochi Abstract We consider graph coloring problems where the cost of a coloring is the sum of the costs of the colors, and the cost of a color is a monotone concave function of the total weight of the class. This models resource

  18. The Costs and Revenues of

    E-Print Network [OSTI]

    The Costs and Revenues of Transformation to Continuous Cover Forestry Owen Davies & Gary Kerr March 2011 #12;2 | Costs and Revenues of CCF | Owen Davies & Gary Kerr | March 2011 Costs and Revenues of CCF The costs and revenues of transformation to continuous cover forestry: Modelling silvicultural options

  19. Allocable costs What are they?

    E-Print Network [OSTI]

    Massachusetts at Lowell, University of

    Allocable costs What are they? The A-21 circular definition: a. A cost is allocable to a particular cost objective (i.e., a specific function, project, sponsored agreement, department, or the like) if the goods or services involved are chargeable or assignable to such cost objective in accordance

  20. 2011 Cost of Wind Energy Review

    SciTech Connect (OSTI)

    Tegen, S.; Lantz, E.; Hand, M.; Maples, B.; Smith, A.; Schwabe, P.

    2013-03-01

    This report describes the levelized cost of energy (LCOE) for a typical land-based wind turbine installed in the United States in 2011, as well as the modeled LCOE for a fixed-bottom offshore wind turbine installed in the United States in 2011. Each of the four major components of the LCOE equation are explained in detail, such as installed capital cost, annual energy production, annual operating expenses, and financing, and including sensitivity ranges that show how each component can affect LCOE. These LCOE calculations are used for planning and other purposes by the U.S. Department of Energy's Wind Program.

  1. Cost Estimating, Analysis, and Standardization

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1984-11-02

    To establish policy and responsibilities for: (a) developing and reviewing project cost estimates; (b) preparing independent cost estimates and analysis; (c) standardizing cost estimating procedures; and (d) improving overall cost estimating and analytical techniques, cost data bases, cost and economic escalation models, and cost estimating systems. Cancels DOE O 5700.2B, dated 8-5-1983; DOE O 5700.8, dated 5-27-1981; and HQ 1130.1A, dated 12-30-1981. Canceled by DOE O 5700.2D, dated 6-12-1992

  2. Use of depleted uranium metal as cask shielding in high-level waste storage, transport, and disposal systems

    SciTech Connect (OSTI)

    Yoshimura, H.R.; Ludwigsen, J.S.; McAllaster, M.E. [and others

    1996-09-01

    The US DOE has amassed over 555,000 metric tons of depleted uranium from its uranium enrichment operations. Rather than dispose of this depleted uranium as waste, this study explores a beneficial use of depleted uranium as metal shielding in casks designed to contain canisters of vitrified high-level waste. Two high-level waste storage, transport, and disposal shielded cask systems are analyzed. The first system employs a shielded storage and disposal cask having a separate reusable transportation overpack. The second system employs a shielded combined storage, transport, and disposal cask. Conceptual cask designs that hold 1, 3, 4 and 7 high-level waste canisters are described for both systems. In all cases, cask design feasibility was established and analyses indicate that these casks meet applicable thermal, structural, shielding, and contact-handled requirements. Depleted uranium metal casting, fabrication, environmental, and radiation compatibility considerations are discussed and found to pose no serious implementation problems. About one-fourth of the depleted uranium inventory would be used to produce the casks required to store and dispose of the nearly 15,400 high-level waste canisters that would be produced. This study estimates the total-system cost for the preferred 7-canister storage and disposal configuration having a separate transportation overpack would be $6.3 billion. When credits are taken for depleted uranium disposal cost, a cost that would be avoided if depleted uranium were used as cask shielding material rather than disposed of as waste, total system net costs are between $3.8 billion and $5.5 billion.

  3. Assessment of light water reactor power plant cost and ultra-acceleration depreciation financing

    E-Print Network [OSTI]

    El-Magboub, Sadek Abdulhafid.

    Although in many regions of the U.S. the least expensive electricity is generated from light-water reactor (LWR) plants, the fixed (capital plus operation and maintenance) cost has increased to the level where the cost ...

  4. The Program Administrator Cost of Saved Energy for Utility Customer-Funded Energy Efficiency Programs

    E-Print Network [OSTI]

    Billingsley, Megan A.

    2014-01-01

    CSE DOE DSM EIA EERS HVAC LCOE MUSH WACC American Councillevelized cost of energy (LCOE), which represents the per-the levelized cost of energy (LCOE), often is applied to

  5. Module Placement for Power Supply Noise and Wire Congestion Avoidance in 3D Packaging

    E-Print Network [OSTI]

    Swaminathan, Madhavan

    Module Placement for Power Supply Noise and Wire Congestion Avoidance in 3D Packaging Jacob Minz congestion minimization for 3D packaging. We employ decoupling capacitance insertion for noise suppression and 3D global routing for congestion avoidance. I. INTRODUCTION The m e potential of System-On-Package

  6. Cross-Contamination Avoidance for Droplet Routing in Digital Microfluidic Biochips

    E-Print Network [OSTI]

    Chakrabarty, Krishnendu

    Cross-Contamination Avoidance for Droplet Routing in Digital Microfluidic Biochips Yang Zhao- contamination between droplets of different biomolecules can lead to erroneous outcomes for bioassays, the avoidance of cross- contamination during droplet routing is a key design challenge for biochips. We propose

  7. Computational investigations of folded self-avoiding walks related to protein folding

    E-Print Network [OSTI]

    Paris-Sud XI, Université de

    Computational investigations of folded self-avoiding walks related to protein folding Jacques M, protein folding, protein structure prediction 1. Introduction Self-avoiding walks (SAWs) have been studied, 9], authors of this manuscript have investigated some dynamic protein folding models. They have

  8. PEDESTRIAN AVOIDANCE FOR UNMANNED GROUND VEHICLES BASED ON VELOCITY OCCUPANCY SPACE

    E-Print Network [OSTI]

    Peng, Huei

    PEDESTRIAN AVOIDANCE FOR UNMANNED GROUND VEHICLES BASED ON VELOCITY OCCUPANCY SPACE William J-time moving obstacle avoidance for Unmanned Ground Vehicles (UGVs). Pedestrian safety and comfort must be ensured by the guidance algorithm when UGVs operate near pedestrians. Studies on human interactions

  9. ORIGINAL PAPER Costly plastic morphological responses to predator

    E-Print Network [OSTI]

    Richner, Heinz

    ORIGINAL PAPER Costly plastic morphological responses to predator specific odour cues in three fixed anti-predator morphologies are favoured when predation level is consistently high, plastic plasticity. However, little is known about sticklebacks' plastic ability to react morpho- logically

  10. WREF 2012: THE PAST AND FUTURE COST OF WIND ENERGY

    E-Print Network [OSTI]

    Wiser, Ryan

    2013-01-01

    E. (2011). Development in LCOE for Wind Turbines in Denmark.to drive a historically low LCOE for current installations.the levelized cost of energy (LCOE) for onshore wind energy

  11. Geothermal probabilistic cost study

    SciTech Connect (OSTI)

    Orren, L.H.; Ziman, G.M.; Jones, S.C.; Lee, T.K.; Noll, R.; Wilde, L.; Sadanand, V.

    1981-08-01

    A tool is presented to quantify the risks of geothermal projects, the Geothermal Probabilistic Cost Model (GPCM). The GPCM model is used to evaluate a geothermal reservoir for a binary-cycle electric plant at Heber, California. Three institutional aspects of the geothermal risk which can shift the risk among different agents are analyzed. The leasing of geothermal land, contracting between the producer and the user of the geothermal heat, and insurance against faulty performance are examined. (MHR)

  12. REDUCTIONS WITHOUT REGRET: DETAILS - AVOIDING BOX CANYONS, ROACH MOTELS, AND WRONG TURNS

    SciTech Connect (OSTI)

    Swegle, John A.; Tincher, Douglas J.

    2013-08-09

    The United States is concurrently pursuing the goals of reducing the size of its nuclear weapons force – strategic and non-strategic, deployed and non-deployed – and of modernizing the weapons it continues to possess. Many of the existing systems were deployed 30 to 50 years ago, and the modernization process can be expected to extend over the next decade or more. Given the impossibility of predicting the future over the lifetime of systems that could extend to the end of this century, it is essential that dead ends in force development be avoided, and the flexibility and availability of options be retained that allow for • Scalability downward in the event that further reductions are agreed upon; • Reposturing to respond to changes in threat levels and to new nuclear actors; and • Breakout response in the event that a competitor significantly increases its force size or force capability, In this paper, we examine the current motivations for reductions and modernization; review a number of historical systems and the attendant capabilities that have been eliminated in recent decades; discuss the current path forward for the U.S. nuclear force; provide a view of the evolving deterrence situation and our assessment of the uncertainties involved; and present examples of possibly problematic directions in force development. We close with our thoughts on how to maintain flexibility and the availability of options for which a need might recur in the future.

  13. Avoid the Tsunami of the Dirac sea in the Imaginary Time Step method

    E-Print Network [OSTI]

    Ying Zhang; Haozhao Liang; Jie Meng

    2009-05-15

    The discrete single-particle spectra in both the Fermi and Dirac sea have been calculated by the imaginary time step (ITS) method for the Schr\\"{o}dinger-like equation after avoiding the "tsunami" of the Dirac sea, i.e., the diving behavior of the single-particle level into the Dirac sea in the direct application of the ITS method for the Dirac equation. It is found that by the transform from the Dirac equation to the Schr\\"{o}dinger-like equation, the single-particle spectra, which extend from the positive to the negative infinity, can be separately obtained by the ITS evolution in either the Fermi sea or the Dirac sea. Identical results with those in the conventional shooting method have been obtained via the ITS evolution for the equivalent Schr\\"{o}dinger-like equation, which demonstrates the feasibility, practicality and reliability of the present algorithm and dispels the doubts on the ITS method in the relativistic system.

  14. Controlling landfill closure costs

    SciTech Connect (OSTI)

    Millspaugh, M.P.; Ammerman, T.A. [Spectra Engineering, Latham, NY (United States)

    1995-05-01

    Landfill closure projects are significant undertakings typically costing well over $100,000/acre. Innovative designs, use of alternative grading and cover materials, and strong project management will substantially reduce the financial impact of a landfill closure project. This paper examines and evaluates the various elements of landfill closure projects and presents various measures which can be employed to reduce costs. Control measures evaluated include: the beneficial utilization of alternative materials such as coal ash, cement kiln dust, paper mill by-product, construction surplus soils, construction debris, and waste water treatment sludge; the appropriate application of Mandate Relief Variances to municipal landfill closures for reduced cover system requirements and reduced long-term post closure monitoring requirements; equivalent design opportunities; procurement of consulting and contractor services to maximize project value; long-term monitoring strategies; and grant loan programs. An analysis of closure costs under differing assumed closure designs based upon recently obtained bid data in New York State, is also provided as a means for presenting the potential savings which can be realized.

  15. New process to avoid emissions: Constant pressure in coke ovens

    SciTech Connect (OSTI)

    Giertz, J.; Huhn, F. [DMT-Gesellschaft fuer Forschung und Pruefung mbH, Essen (Germany). Inst. for Cokemaking and Fuel Technology; Hofherr, K. [Thyssen Stahl AG, Duisburg (Germany)

    1995-12-01

    A chamber pressure regulation (PROven), especially effective in regard to emission control problems of coke ovens is introduced for the first time. Because of the partial vacuum in the collecting main system, it is possible to keep the oven`s raw gas pressure constant on a low level over the full coking time. The individual pressure control for each chamber is assured directly as a function of the oven pressure by an immersion system controlling the flow resistance of the collecting main valve. The latter is a fixed-position design (system name ``FixCup``). By doing away with the interdependence of collecting main pressure and chamber pressure, a parameter seen as a coking constant could not be made variable. This opens a new way to reduce coke oven emissions and simultaneously to prevent the ovens from damage caused by air ingress into the oven.

  16. Variable Speed Pumping for Level Control 

    E-Print Network [OSTI]

    Vasel, M.

    1982-01-01

    analysis, and a brief discussion of variable frequency drive design considerations. Energy savings figures are based upon actual electricity costs at the plant involved. Process duty cycle and energy requirement levels were verified by a wattmeter...

  17. Investing in International Information Exchange Activities to Improve the Safety, Cost Effectiveness and Schedule of Cleanup - 13281

    SciTech Connect (OSTI)

    Seed, Ian; James, Paula; Mathieson, John; Judd, Laurie; Elmetti-Ramirez, Rosa; Han, Ana

    2013-07-01

    With decreasing budgets and increasing pressure on completing cleanup missions as quickly, safely and cost-effectively as possible, there is significant benefit to be gained from collaboration and joint efforts between organizations facing similar issues. With this in mind, the US Department of Energy (DOE) and the UK Nuclear Decommissioning Authority (NDA) have formally agreed to share information on lessons learned on the development and application of new technologies and approaches to improve the safety, cost effectiveness and schedule of the cleanup legacy wastes. To facilitate information exchange a range of tools and methodologies were established. These included tacit knowledge exchange through facilitated meetings, conference calls and Site visits as well as explicit knowledge exchange through document sharing and newsletters. A DOE web-based portal has been established to capture these exchanges and add to them via discussion boards. The information exchange is operating at the Government-to-Government strategic level as well as at the Site Contractor level to address both technical and managerial topic areas. This effort has resulted in opening a dialogue and building working relationships. In some areas joint programs of work have been initiated thus saving resource and enabling the parties to leverage off one another activities. The potential benefits of high quality information exchange are significant, ranging from cost avoidance through identification of an approach to a problem that has been proven elsewhere to cost sharing and joint development of a new technology to address a common problem. The benefits in outcomes significantly outweigh the costs of the process. The applicability of the tools and methods along with the lessons learned regarding some key issues is of use to any organization that wants to improve value for money. In the waste management marketplace, there are a multitude of challenges being addressed by multiple organizations and the effective pooling and exchange of knowledge and experience can only be of benefit to all participants to help complete the cleanup mission more quickly and more cost effectively. This paper examines in detail the tools and processes used to promote information exchange and the progress made to date. It also discusses the challenges and issues involved and proposes recommendations to others who are involved in similar activities. (authors)

  18. Electric Demand Cost Versus Labor Cost: A Case Study 

    E-Print Network [OSTI]

    Agrawal, S.; Jensen, R.

    1998-01-01

    Electric Utility companies charge industrial clients for two things: demand and usage. Depending on type of business and hours operation, demand cost could be very high. Most of the operations scheduling in a plant is achieved considering labor cost...

  19. Plastics Avoiding Bisphenol-A (BPA) Why is there concern? Researchers are concerned that even at low levels, environmental estrogens

    E-Print Network [OSTI]

    Chen, Tsuhan

    in the dishwasher. DO hand wash PC bottles in mild detergent. · DO NOT use PC plastic bottles that are worn

  20. Cover Sheet for Budget Item Predicted Cost Actual Cost Notes

    E-Print Network [OSTI]

    Cover Sheet for Budget Item Predicted Cost Actual Cost Notes Lodging $700.00 Three hotels: 1. $195, $154.00 was used for unintended transportations (taxi, train, bus, etc.) and lodging costs Meal Plan $1.70 10. Bus $1.70 11. Bus $2.83 12. Bus $4.53 13. Tram$3.28 = $96.11 These costs were paid

  1. Changes in the Economic Value of Variable Generation at High Penetration Levels: A Pilot Case Study of California

    E-Print Network [OSTI]

    Mills, Andrew D.

    2014-01-01

    AS CAISO CCGT CSP CT DA EUE LCOE LOLP LOLE NERC NREL O&M PHSthe levelized cost of energy (LCOE) or the cost of a power

  2. Lightweighting Impacts on Fuel Economy, Cost, and Component Losses

    SciTech Connect (OSTI)

    Brooker, A. D.; Ward, J.; Wang, L.

    2013-01-01

    The Future Automotive Systems Technology Simulator (FASTSim) is the U.S. Department of Energy's high-level vehicle powertrain model developed at the National Renewable Energy Laboratory. It uses a time versus speed drive cycle to estimate the powertrain forces required to meet the cycle. It simulates the major vehicle powertrain components and their losses. It includes a cost model based on component sizing and fuel prices. FASTSim simulated different levels of lightweighting for four different powertrains: a conventional gasoline engine vehicle, a hybrid electric vehicle (HEV), a plug-in hybrid electric vehicle (PHEV), and a battery electric vehicle (EV). Weight reductions impacted the conventional vehicle's efficiency more than the HEV, PHEV and EV. Although lightweighting impacted the advanced vehicles' efficiency less, it reduced component cost and overall costs more. The PHEV and EV are less cost effective than the conventional vehicle and HEV using current battery costs. Assuming the DOE's battery cost target of $100/kWh, however, the PHEV attained similar cost and lightweighting benefits. Generally, lightweighting was cost effective when it costs less than $6/kg of mass eliminated.

  3. User cost in oil production

    E-Print Network [OSTI]

    Adelman, Morris Albert

    1990-01-01

    The assumption of an initial fixed mineral stock is superfluous and wrong. User cost (resource rent) in mineral production is the present value of expected increases in development cost. It can be measured as the difference ...

  4. Machine Learning with Operational Costs

    E-Print Network [OSTI]

    Rudin, Cynthia

    This work proposes a way to align statistical modeling with decision making. We provide a method that propagates the uncertainty in predictive modeling to the uncertainty in operational cost, where operational cost is the ...

  5. Tracking the Sun III; The Installed Cost of Photovoltaics in the United States from 1998-2009

    SciTech Connect (OSTI)

    Barbose, Galen; Darghouth, Naim; Wiser, Ryan

    2010-12-13

    Installations of solar photovoltaic (PV) systems have been growing at a rapid pace in recent years. In 2009, approximately 7,500 megawatts (MW) of PV were installed globally, up from approximately 6,000 MW in 2008, consisting primarily of grid-connected applications. With 335 MW of grid-connected PV capacity added in 2009, the United States was the world's fourth largest PV market in 2009, behind Germany, Italy, and Japan. The market for PV in the United States is driven by national, state, and local government incentives, including up-front cash rebates, production-based incentives, requirements that electricity suppliers purchase a certain amount of solar energy, and federal and state tax benefits. These programs are, in part, motivated by the popular appeal of solar energy, and by the positive attributes of PV - modest environmental impacts, avoidance of fuel price risks, coincidence with peak electrical demand, and the possible deployment of PV at the point of use. Given the relatively high cost of PV, however, a key goal of these policies is to encourage cost reductions over time. Therefore, as policy incentives have become more significant and as PV deployment has accelerated, so too has the desire to track the installed cost of PV systems over time, by system characteristics, by system location, and by component. Despite the significant year-on-year growth, however, the share of global and U.S. electricity supply met with PV remains small, and annual PV additions are currently modest in the context of the overall electric system. To address this need, Lawrence Berkeley National Laboratory initiated a report series focused on describing trends in the installed cost of grid-connected PV systems in the United States. The present report, the third in the series, describes installed cost trends from 1998 through 2009, and provides preliminary cost data for systems installed in 2010. The analysis is based on project-level cost data from approximately 78,000 residential and non-residential PV systems in the U.S., all of which are installed at end-use customer facilities (herein referred to as 'customer-sited' systems). The combined capacity of systems in the data sample totals 874 MW, equal to 70% of all grid-connected PV capacity installed in the United States through 2009 and representing one of the most comprehensive sources of installed PV cost data for the U.S. The report also briefly compares recent PV installed costs in the United States to those in Germany and Japan. Finally, it should be noted that the analysis presented here focuses on descriptive trends in the underlying data, serving primarily to summarize the data in tabular and graphical form; later analysis may explore some of these trends with more-sophisticated statistical techniques. The report begins with a summary of the data collection methodology and resultant dataset (Section 2). The primary findings of the analysis are presented in Section 3, which describes trends in installed costs prior to receipt of any financial incentives: over time and by system size, component, state, system ownership type (customer-owned vs. third party-owned), host customer segment (residential vs. commercial vs. public-sector vs. non-profit), application (new construction vs. retrofit), and technology type (building-integrated vs. rack-mounted, crystalline silicon vs. thin-film, and tracking vs. fixed-axis). Section 4 presents additional findings related to trends in PV incentive levels over time and among states (focusing specifically on state and utility incentive programs as well as state and federal tax credits), and trends in the net installed cost paid by system owners after receipt of such incentives. Brief conclusions are offered in the final section, and several appendices provide additional details on the analysis methodology and additional tabular summaries of the data.

  6. Cost and Performance Model for Redox Flow Batteries

    SciTech Connect (OSTI)

    Viswanathan, Vilayanur V.; Crawford, Aladsair J.; Stephenson, David E.; Kim, Soowhan; Wang, Wei; Li, Bin; Coffey, Greg W.; Thomsen, Edwin C.; Graff, Gordon L.; Balducci, Patrick J.; Kintner-Meyer, Michael CW; Sprenkle, Vincent L.

    2014-02-01

    A cost model was developed for all vanadium and iron-vanadium redox flow batteries. Electrochemical performance modeling was done to estimate stack performance at various power densities as a function of state of charge. This was supplemented with a shunt current model and a pumping loss model to estimate actual system efficiency. The operating parameters such as power density, flow rates and design parameters such as electrode aspect ratio, electrolyte flow channel dimensions were adjusted to maximize efficiency and minimize capital costs. Detailed cost estimates were obtained from various vendors to calculate cost estimates for present, realistic and optimistic scenarios. The main drivers for cost reduction for various chemistries were identified as a function of the energy to power ratio of the storage system. Levelized cost analysis further guided suitability of various chemistries for different applications.

  7. Wind Integration Cost and Cost-Causation: Preprint

    SciTech Connect (OSTI)

    Milligan, M.; Kirby, B.; Holttinen, H.; Kiviluoma, J.; Estanqueiro, A.; Martin-Martinez, S.; Gomez-Lazaro, E.; Peneda, I.; Smith, C.

    2013-10-01

    The question of wind integration cost has received much attention in the past several years. The methodological challenges to calculating integration costs are discussed in this paper. There are other sources of integration cost unrelated to wind energy. A performance-based approach would be technology neutral, and would provide price signals for all technology types. However, it is difficult to correctly formulate such an approach. Determining what is and is not an integration cost is challenging. Another problem is the allocation of system costs to one source. Because of significant nonlinearities, this can prove to be impossible to determine in an accurate and objective way.

  8. Cost Effectiveness NW Energy Coalition

    E-Print Network [OSTI]

    1 Action 8 Cost Effectiveness Manual Kim Drury NW Energy Coalition Context · Inconsistent consistent understanding and application of how cost effectiveness is calculated and when and how to apply Action Plan for Energy Efficiency published a comprehensive guide on cost effectiveness: best practices

  9. Check Estimates and Independent Costs

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    Check estimates and independent cost estimates (ICEs) are tools that can be used to validate a cost estimate. Estimate validation entails an objective review of the estimate to ensure that estimate criteria and requirements have been met and well documented, defensible estimate has been developed. This chapter describes check estimates and their procedures and various types of independent cost estimates.

  10. Overlay Costs National Concrete Consortium

    E-Print Network [OSTI]

    Overlay Costs National Concrete Consortium TTCC April 6, 2010 Savannah, Georgia Gary Fick Representing The National Concrete Pavement Technology Center #12;Overlay Cost Tech Brief · Developed to address common questions we have received during our implementation efforts #12;Overlay Cost Tech Brief

  11. Building Commissioning: A Golden Opportunity for Reducing Energy Costs and Greenhouse-gas Emissions

    SciTech Connect (OSTI)

    Mills, Evan

    2009-07-16

    The aim of commissioning new buildings is to ensure that they deliver, if not exceed, the performance and energy savings promised by their design. When applied to existing buildings, commissioning identifies the almost inevitable 'drift' from where things should be and puts the building back on course. In both contexts, commissioning is a systematic, forensic approach to quality assurance, rather than a technology per se. Although commissioning has earned increased recognition in recent years - even a toehold in Wikipedia - it remains an enigmatic practice whose visibility severely lags its potential. Over the past decade, Lawrence Berkeley National Laboratory has built the world's largest compilation and meta-analysis of commissioning experience in commercial buildings. Since our last report (Mills et al. 2004) the database has grown from 224 to 643 buildings (all located in the United States, and spanning 26 states), from 30 to 100 million square feet of floorspace, and from $17 million to $43 million in commissioning expenditures. The recorded cases of new-construction commissioning took place in buildings representing $2.2 billion in total construction costs (up from 1.5 billion). The work of many more commissioning providers (18 versus 37) is represented in this study, as is more evidence of energy and peak-power savings as well as cost-effectiveness. We now translate these impacts into avoided greenhouse gases and provide new indicators of cost-effectiveness. We also draw attention to the specific challenges and opportunities for high-tech facilities such as labs, cleanrooms, data centers, and healthcare facilities. The results are compelling. We developed an array of benchmarks for characterizing project performance and cost-effectiveness. The median normalized cost to deliver commissioning was $0.30/ft2 for existing buildings and $1.16/ft2 for new construction (or 0.4% of the overall construction cost). The commissioning projects for which data are available revealed over 10,000 energy-related problems, resulting in 16% median whole-building energy savings in existing buildings and 13% in new construction, with payback time of 1.1 years and 4.2 years, respectively. In terms of other cost-benefit indicators, median benefit-cost ratios of 4.5 and 1.1, and cash-on-cash returns of 91% and 23% were attained for existing and new buildings, respectively. High-tech buildings were particularly cost-effective, and saved higher amounts of energy due to their energy-intensiveness. Projects with a comprehensive approach to commissioning attained nearly twice the overall median level of savings and five-times the savings of the least-thorough projects. It is noteworthy that virtually all existing building projects were cost-effective by each metric (0.4 years for the upper quartile and 2.4 years for the lower quartile), as were the majority of new-construction projects (1.5 years and 10.8 years, respectively). We also found high cost-effectiveness for each specific measure for which we have data. Contrary to a common perception, cost-effectiveness is often achieved even in smaller buildings. Thanks to energy savings valued more than the cost of the commissioning process, associated reductions in greenhouse gas emissions come at 'negative' cost. In fact, the median cost of conserved carbon is negative - -$110 per tonne for existing buildings and -$25/tonne for new construction - as compared with market prices for carbon trading and offsets in the +$10 to +$30/tonne range. Further enhancing the value of commissioning, its non-energy benefits surpass those of most other energy-management practices. Significant first-cost savings (e.g., through right-sizing of heating and cooling equipment) routinely offset at least a portion of commissioning costs - fully in some cases. When accounting for these benefits, the net median commissioning project cost was reduced by 49% on average, while in many cases they exceeded the direct value of the energy savings. Commissioning also improves worker comfort, mitigates indoor air quality problems

  12. Hazard avoidance for high-speed rough-terrain unmanned ground vehicles

    E-Print Network [OSTI]

    Spenko, Matthew J. (Matthew Julius), 1976-

    2005-01-01

    High-speed unmanned ground vehicles have important applications in rough-terrain. In these applications unexpected and dangerous situations can occur that require rapid hazard avoidance maneuvers. At high speeds, there is ...

  13. Trait Approach and Avoidance Motivation: Lateralized Neural Activity Associated with Executive Function

    E-Print Network [OSTI]

    Banich, Marie T.

    Trait Approach and Avoidance Motivation: Lateralized Neural Activity Associated with Executive of Illinois at Urbana-Champaign Abstract Motivation and executive function are both necessary neural mechanisms. However, this research has focused on state motivation, and it has not examined

  14. Real-Time Obstacle and Collision Avoidance System for Fixed-Wing Unmanned Aerial Systems

    E-Print Network [OSTI]

    Esposito, Julien Florian

    2013-08-31

    The motivation for the research presented in this dissertation is to provide a two-fold solution to the problem of non-cooperative reactive mid-air threat avoidance for fixed-wing unmanned aerial systems. The first phase ...

  15. Collision avoidance system optimization for closely spaced parallel operations through surrogate modeling

    E-Print Network [OSTI]

    Smith, Kyle A. (Kyle Alexander)

    2013-01-01

    The Traffic Alert and Collision Avoidance System (TCAS) is mandated worldwide to protect against aircraft mid-air collisions. One drawback of the current TCAS design is limited support for certain closely spaced parallel ...

  16. Optimal planning and control for hazard avoidance of front-wheel steered ground vehicles

    E-Print Network [OSTI]

    Peters, Steven C. (Steven Conrad)

    2012-01-01

    Hazard avoidance is an important capability for safe operation of robotic vehicles at high speed. It is also an important consideration for passenger vehicle safety, as thousands are killed each year in passenger vehicle ...

  17. Sensor integration for implementation of obstacle avoidance in an autonomous helicopter system 

    E-Print Network [OSTI]

    Mentzer, Christopher Isaac

    2006-08-16

    This thesis describes the development of the Texas A&M University Autonomous Helicopter System and the integration of obstacle avoidance capabilities into that system. The helicopter system, composed of a Bergen Observer helicopter and a Rotomotion...

  18. Stay on marked paths to avoid poison ivy. Watch young children carefully around river and creeks.

    E-Print Network [OSTI]

    Shyy, Wei

    Caution · Stay on marked paths to avoid poison ivy. · Watch young children carefully around river or outdoor cooking are not permitted. Poison Ivy Hours · Trails and gardens open 8 am to dusk. · Conservatory

  19. HD Applications of Significantly Downsized SI Engines Using Alcohol DI for Knock Avoidance

    Broader source: Energy.gov [DOE]

    Direct injection of a second fuel (ethanol or methanol) is explored as a means of avoiding knock in turbocharged, high-compression ratio spark-ignited engines that could replace diesels in certain vocational applications.

  20. Hay Harvesting Costs $$$$$ in Texas. 

    E-Print Network [OSTI]

    Long, James T.; Taylor, Wayne D.

    1972-01-01

    would be approximately 34 cents. Labor cost was calculated at $1.50 per hour. Total operating cost, including labor and all equipmen! use, was 8.2 cents per bale and $5.73 per acre (a$ shown in Table 2). Assuming an average yieltl oi seventy 60.... averaged $5.73 per acre for each be 8.2 cents per bale. At a cost of 10 cents per baly cutting or $2.73 per ton. With an average of 70 for custom hauling, direct, out-of-pocket costs will be 18.2 cents per bale. I Table 3. Estimated Cost Per Ton and Per...

  1. The avoidance of a previously neutral stimulus paired with frustrative nonreward 

    E-Print Network [OSTI]

    Beard, William Washington

    1975-01-01

    involved pairing of a CS (light) with frustra- tive nonreward in Goal Box 1. During Phase III, Ss were tested in a separate hurdle-jump apparatus to de- monstrate avoidance of the now aversive CS by jumping at the sound of a buzzer. It was found... Ss conditioned to the CS jumped the hurdle significantly faster than any of the other subgroups. However, an analysis of the frequency of avoidance re- sponses revealed no statistically significant differ- ences between all subgroups...

  2. U.S. Department of Energy Hydrogen Storage Cost Analysis

    SciTech Connect (OSTI)

    Law, Karen; Rosenfeld, Jeffrey; Han, Vickie; Chan, Michael; Chiang, Helena; Leonard, Jon

    2013-03-11

    The overall objective of this project is to conduct cost analyses and estimate costs for on- and off-board hydrogen storage technologies under development by the U.S. Department of Energy (DOE) on a consistent, independent basis. This can help guide DOE and stakeholders toward the most-promising research, development and commercialization pathways for hydrogen-fueled vehicles. A specific focus of the project is to estimate hydrogen storage system cost in high-volume production scenarios relative to the DOE target that was in place when this cost analysis was initiated. This report and its results reflect work conducted by TIAX between 2004 and 2012, including recent refinements and updates. The report provides a system-level evaluation of costs and performance for four broad categories of on-board hydrogen storage: (1) reversible on-board metal hydrides (e.g., magnesium hydride, sodium alanate); (2) regenerable off-board chemical hydrogen storage materials(e.g., hydrolysis of sodium borohydride, ammonia borane); (3) high surface area sorbents (e.g., carbon-based materials); and 4) advanced physical storage (e.g., 700-bar compressed, cryo-compressed and liquid hydrogen). Additionally, the off-board efficiency and processing costs of several hydrogen storage systems were evaluated and reported, including: (1) liquid carrier, (2) sodium borohydride, (3) ammonia borane, and (4) magnesium hydride. TIAX applied a â��bottom-upâ� costing methodology customized to analyze and quantify the processes used in the manufacture of hydrogen storage systems. This methodology, used in conjunction with DFMA�® software and other tools, developed costs for all major tank components, balance-of-tank, tank assembly, and system assembly. Based on this methodology, the figure below shows the projected on-board high-volume factory costs of the various analyzed hydrogen storage systems, as designed. Reductions in the key cost drivers may bring hydrogen storage system costs closer to this DOE target. In general, tank costs are the largest component of system cost, responsible for at least 30 percent of total system cost, in all but two of the 12 systems. Purchased BOP cost also drives system cost, accounting for 10 to 50 percent of total system cost across the various storage systems. Potential improvements in these cost drivers for all storage systems may come from new manufacturing processes and higher production volumes for BOP components. In addition, advances in the production of storage media may help drive down overall costs for the sodium alanate, SBH, LCH2, MOF, and AX-21 systems.

  3. Survey of statistical and sampling needs for environmental monitoring of commercial low-level radioactive waste disposal facilities

    SciTech Connect (OSTI)

    Eberhardt, L.L.; Thomas, J.M.

    1986-07-01

    This project was designed to develop guidance for implementing 10 CFR Part 61 and to determine the overall needs for sampling and statistical work in characterizing, surveying, monitoring, and closing commercial low-level waste sites. When cost-effectiveness and statistical reliability are of prime importance, then double sampling, compositing, and stratification (with optimal allocation) are identified as key issues. If the principal concern is avoiding questionable statistical practice, then the applicability of kriging (for assessing spatial pattern), methods for routine monitoring, and use of standard textbook formulae in reporting monitoring results should be reevaluated. Other important issues identified include sampling for estimating model parameters and the use of data from left-censored (less than detectable limits) distributions.

  4. Letting The Sun Shine On Solar Costs: An Empirical Investigation Of Photovoltaic Cost Trends In California

    E-Print Network [OSTI]

    Wiser, Ryan; Bolinger, Mark; Cappers, Peter; Margolis, Robert

    2006-01-01

    Total Cost (CPUC) Module Cost Index (CEC, CPUC) CEC CPUC *an external index of worldwide module costs from Strategies

  5. Value of Demand Response: Quantities from Production Cost Modeling (Presentation)

    SciTech Connect (OSTI)

    Hummon, M.

    2014-04-01

    Demand response (DR) resources present a potentially important source of grid flexibility particularly on future systems with high penetrations of variable wind and solar power generation. However, managed loads in grid models are limited by data availability and modeling complexity. This presentation focuses on the value of co-optimized DR resources to provide energy and ancillary services in a production cost model. There are significant variations in the availabilities of different types of DR resources, which affect both the operational savings as well as the revenue for each DR resource. The results presented include the system-wide avoided fuel and generator start-up costs as well as the composite revenue for each DR resource by energy and operating reserves. In addition, the revenue is characterized by the capacity, energy, and units of DR enabled.

  6. Costs and benefits of energy efficiency improvements in ceiling fans

    SciTech Connect (OSTI)

    Shah, Nihar; Sathaye, Nakul; Phadke, Amol; Letschert, Virginie

    2013-10-15

    Ceiling fans contribute significantly to residential electricity consumption, especially in developing countries with warm climates. The paper provides analysis of costs and benefits of several options to improve the efficiency of ceiling fans to assess the global potential for electricity savings and green house gas (GHG) emission reductions. Ceiling fan efficiency can be cost-effectively improved by at least 50% using commercially available technology. If these efficiency improvements are implemented in all ceiling fans sold by 2020, 70 terawatt hours per year could be saved and 25 million metric tons of carbon dioxide equivalent (CO2-e) emissions per year could be avoided, globally. We assess how policies and programs such as standards, labels, and financial incentives can be used to accelerate the adoption of efficient ceiling fans in order to realize potential savings.

  7. Lower Cost Energy Options 

    E-Print Network [OSTI]

    Maze, M. E.

    1987-01-01

    , wh1ch means g01ng from 13.000 volts up to 39.000 volts and buy1ng the transformers, we can save nearly $180,000. The other th1ng I p01nted out before was the power factor penalty. By addIng capac1tors and ra1s1ng our power factor from 84% to 95...'s not as wIdely used, but revlta11zatlon rates are avaIlable. The last area 1s cogeneratIon. ThIs can be one of two thIngs. It can be an attractIve buy-back rate or av01ded cost rate, for cogenerated electrIcIty or 1t can be a r1der or rate where they w...

  8. Hydropower Baseline Cost Modeling

    SciTech Connect (OSTI)

    O'Connor, Patrick W.; Zhang, Qin Fen; DeNeale, Scott T.; Chalise, Dol Raj; Centurion, Emma E.

    2015-01-01

    Recent resource assessments conducted by the United States Department of Energy have identified significant opportunities for expanding hydropower generation through the addition of power to non-powered dams and on undeveloped stream-reaches. Additional interest exists in the powering of existing water resource infrastructure such as conduits and canals, upgrading and expanding existing hydropower facilities, and the construction new pumped storage hydropower. Understanding the potential future role of these hydropower resources in the nation’s energy system requires an assessment of the environmental and techno-economic issues associated with expanding hydropower generation. To facilitate these assessments, this report seeks to fill the current gaps in publically available hydropower cost-estimating tools that can support the national-scale evaluation of hydropower resources.

  9. Tracking the Sun II: The Installed Cost of Photovoltaics in the U.S. from 1998-2008

    SciTech Connect (OSTI)

    Barbose, Galen L; Wiser, Ryan; Peterman, Carla; Darghouth, Naim

    2009-10-05

    Installations of solar photovoltaic (PV) systems have been growing at a rapid pace in recent years. In 2008, 5,948 MW of PV was installed globally, up from 2,826 MW in 2007, and was dominated by grid-connected applications. The United States was the world's third largest PV market in terms of annual capacity additions in 2008, behind Spain and Germany; 335 MW of PV was added in the U.S. in 2008, 293 MW of which came in the form of grid-connected installations. Despite the significant year-on-year growth, however, the share of global and U.S. electricity supply met with PV remains small, and annual PV additions are currently modest in the context of the overall electric system. The market for PV in the U.S. is driven by national, state, and local government incentives, including up-front cash rebates, production-based incentives, requirements that electricity suppliers purchase a certain amount of solar energy, and Federal and state tax benefits. These programs are, in part, motivated by the popular appeal of solar energy, and by the positive attributes of PV - modest environmental impacts, avoidance of fuel price risks, coincidence with peak electrical demand, and the location of PV at the point of use. Given the relatively high cost of PV, however, a key goal of these policies is to encourage cost reductions over time. Therefore, as policy incentives have become more significant and as PV deployment has accelerated, so too has the desire to track the installed cost of PV systems over time, by system characteristics, by system location, and by component. To address this need, Lawrence Berkeley National Laboratory initiated a report series focused on describing trends in the installed cost of grid-connected PV systems in the U.S. The present report, the second in the series, describes installed cost trends from 1998 through 2008. The analysis is based on project-level cost data from more than 52,000 residential and non-residential PV systems in the U.S., all of which are installed at end-use customer facilities (herein referred to as 'customer-sited' systems). The combined capacity of systems in the data sample totals 566 MW, equal to 71% of all grid-connected PV capacity installed in the U.S. through 2008, representing the most comprehensive source of installed PV cost data for the U.S.9 The report also briefly compares recent PV installed costs in the U.S. to those in Germany and Japan. Finally, it should be noted that the analysis presented here focuses on descriptive trends in the underlying data, and is primarily summarized in tabular and graphical form; later analysis may explore some of these trends with more-sophisticated statistical techniques. The report begins with a summary of the data collection methodology and resultant dataset (Section 2). The primary findings of the analysis are presented in Section 3, which describes trends in installed costs prior to receipt of any financial incentives: over time and by system size, component, state, customer segment (residential vs. commercial vs. public-sector vs. non-profit), application (new construction vs. retrofit), and technology type (building-integrated vs. rack-mounted, crystalline silicon vs. thin-film, and tracking vs. rack-mounted). Section 4 presents additional findings related to trends in PV incentive levels over time and among states (focusing specifically on state and utility incentive programs as well as state and Federal tax credits), and trends in the net installed cost paid by system owners after receipt of such incentives. Brief conclusions are offered in the final section.

  10. A model for a national low level waste program

    SciTech Connect (OSTI)

    Blankenhorn, James A [Los Alamos National Laboratory

    2009-01-01

    A national program for the management of low level waste is essential to the success of environmental clean-up, decontamination and decommissioning, current operations and future missions. The value of a national program is recognized through procedural consistency and a shared set of resources. A national program requires a clear waste definition and an understanding of waste characteristics matched against available and proposed disposal options. A national program requires the development and implementation of standards and procedures for implementing the waste hierarchy, with a specitic emphasis on waste avoidance, minimization and recycling. It requires a common set of objectives for waste characterization based on the disposal facility's waste acceptance criteria, regulatory and license requirements and performance assessments. Finally, a national waste certification program is required to ensure compliance. To facilitate and enhance the national program, a centralized generator services organization, tasked with providing technical services to the generators on behalf of the national program, is necessary. These subject matter experts are the interface between the generating sites and the disposal facility(s). They provide an invaluable service to the generating organizations through their involvement in waste planning prior to waste generation and through championing implementation of the waste hierarchy. Through their interface, national treatment and transportation services are optimized and new business opportunities are identified. This national model is based on extensive experience in the development and on-going management of a national transuranic waste program and management of the national repository, the Waste Isolation Pilot Plant. The Low Level Program at the Savannah River Site also successfully developed and implemented the waste hierarchy, waste certification and waste generator services concepts presented below. The Savannah River Site services over forty generators and has historically managed over 12,000 cubic meters of low level waste annually. The results of the waste minimization program at the site resulted in over 900 initiatives, avoiding over 220,000 cubic meters of waste for a life cycle cost savings of $275 million. At the Los Alamos National Laboratory, the low level waste program services over 20 major generators and several hundred smaller generators that produce over 4,000 cubic meters of low level waste annually. The Los Alamos National Laboratory low level waste program utilizes both on-site and off-site disposal capabilities. Off-site disposal requires the implementation of certification requirements to utilize both federal and commercial options. The Waste Isolation Pilot Plant is the US Department of Energy's first deep geological repository for the permanent disposal of Transuanic waste. Transuranic waste was generated and retrievably stored at 39 sites across the US. Transuranic waste is defined as waste with a radionuclide concentration equal to or greater than 100 nCi/g consisting of radionuclides with half-lives greater than 20 years and with an atomic mass greater than uranium. Combining the lessons learned from the national transuranic waste program, the successful low level waste program at Savannah River Site and the experience of off-site disposal options at Los Alamos National Laboratory provides the framework and basis for developing a viable national strategy for managing low level waste.

  11. Changes in the Economic Value of Variable Generation at High Penetration Levels: A Pilot Case Study of California

    E-Print Network [OSTI]

    Mills, Andrew

    2013-01-01

    The variable O&M cost of wind and solar is assumed to bethe relative levelized cost of wind and solar supply. OneJ. Swider and C. Weber. The costs of wind’s intermittency in

  12. Changes in the Economic Value of Variable Generation at High Penetration Levels: A Pilot Case Study of California

    E-Print Network [OSTI]

    Mills, Andrew

    2013-01-01

    CEMS CSP CT DA EIA EPA EUE LCOE LOLP LOLE NERC NREL O&M PHSlevelized cost of energy (LCOE)). A missing part of simplethe levelized cost of energy (LCOE) or the cost of a power

  13. Cost-Constrained Selection of Strand Wire and Number in a Litz-Wire Transformer Winding

    E-Print Network [OSTI]

    Cost-Constrained Selection of Strand Wire and Number in a Litz-Wire Transformer Winding C. R. Design of litz-wire windings subject to cost constraints is analyzed. An approximation of nor- malized winding, in terms of a cost function. At the second level, results that are less general but are more

  14. Investigation to Discover Most Effective Method of Teaching Target Costing to Construction-Minded Individuals 

    E-Print Network [OSTI]

    Hullum, Joshua James

    2012-07-16

    and an increased level of detail, while keeping costs lower than ever. Therefore, to meet such demands contractors must turn to an alternative approach of improving product and process with target costing. However, the adoption of target costing by the construction...

  15. Lyra: Password-Based Key Derivation with Tunable Memory and Processing Costs

    E-Print Network [OSTI]

    International Association for Cryptologic Research (IACR)

    Lyra: Password-Based Key Derivation with Tunable Memory and Processing Costs Leonardo C. Almeida memory and processing costs according to the desired level of security against brute force pass- word that if we fix Lyra's total processing time t in a legitimate platform, the cost of a memory-free attack

  16. Hydrogen Refueling Station Costs in Shanghai

    E-Print Network [OSTI]

    Weinert, Jonathan X.; Shaojun, Liu; Ogden, Joan M; Jianxin, Ma

    2006-01-01

    04 Hydrogen Refueling Station Costs in Shanghai Jonathan X.Hydrogen Refueling Station Costs in Shanghai Jonathan X.voltage connections) Capital costs for this equipment must

  17. Hydrogen refueling station costs in Shanghai

    E-Print Network [OSTI]

    Weinert, Jonathan X.; Shaojun, Liu; Ogden, Joan M; Jianxin, Ma

    2007-01-01

    Kingdom; 2004. [8] Amos W. Costs of storing and transportingcon- nections). Capital costs for this equipment must bein an analysis of station costs. Total station construction

  18. Bisphenol-A rapidly enhanced passive avoidance memory and phosphorylation of NMDA receptor subunits in hippocampus of young rats

    SciTech Connect (OSTI)

    Xu Xiaohong, E-mail: xuxh63@zjnu.cn; Li Tao; Luo Qingqing; Hong Xing; Xie Lingdan; Tian Dong

    2011-09-01

    Bisphenol-A (BPA), an endocrine disruptor, is found to influence development of brain and behaviors in rodents. The previous study indicated that perinatal exposure to BPA impaired learning-memory and inhibited N-methyl-D-aspartate receptor (NMDAR) subunits expressions in hippocampus during the postnatal development in rats; and in cultured hippocampal neurons, BPA rapidly promotes dynamic changes in dendritic morphology through estrogen receptor-mediated pathway by concomitant phosphorylation of NMDAR subunit NR2B. In the present study, we examined the rapid effect of BPA on passive avoidance memory and NMDAR in the developing hippocampus of Sprague-Dawley rats at the age of postnatal day 18. The results showed that BPA or estradiol benzoate (EB) rapidly extended the latency to step down from the platform 1 h after footshock and increased the phosphorylation levels of NR1, NR2B, and mitogen-activated extracellular signal-regulated kinase (ERK) in hippocampus within 1 h. While 24 h after BPA or EB treatment, the improved memory and the increased phosphorylation levels of NR1, NR2B, ERK disappeared. Furthermore, pre-treatment with an estrogen receptors (ERs) antagonist, ICI182,780, or an ERK-activating kinase inhibitor, U0126, significantly attenuated EB- or BPA-induced phosphorylations of NR1, NR2B, and ERK within 1 h. These data suggest that BPA rapidly enhanced short-term passive avoidance memory in the developing rats. A non-genomic effect via ERs may mediate the modulation of the phosphorylation of NMDAR subunits NR1 and NR2B through ERK signaling pathway. - Highlights: > BPA rapidly extended the latency to step down from platform 1 h after footshock. > BPA rapidly increased pNR1, pNR2B, and pERK in hippocampus within 1 h. > ERs antagonist or MEK inhibitor attenuated BPA-induced pNR1, pNR2B, and pERK.

  19. Helicopter Brown-Out costs the US approximately $100 M per year in casualties/fatalities and signifi-

    E-Print Network [OSTI]

    Helicopter Brown-Out costs the US approximately $100 M per year in casualties be used not only for mitigation but also to predict and avoid brown-out conditions. Helicopter Brown) data from RADARSAT-2 is analyzed for detection of soils susceptible to helicopter brown-out. He

  20. Low Cost Heliostat Development Phase II Final Report

    SciTech Connect (OSTI)

    Kusek, Stephen M.

    2014-04-21

    The heliostat field in a central receiver plant makes up roughly one half of the total plant cost. As such, cost reductions for the installed heliostat price greatly impact the overall plant cost and hence the plant’s Levelized Cost of Energy. The general trend in heliostat size over the past decades has been to make them larger. One part of our thesis has been that larger and larger heliostats may drive the LCOE up instead of down due to the very nature of the precise aiming and wind-load requirements for typical heliostats. In other words, it requires more and more structure to precisely aim the sunlight at the receiver as one increases heliostat mirror area and that it becomes counter-productive, cost-wise, at some point.

  1. Avoidance Routing

    E-Print Network [OSTI]

    Kline, Erik A.

    2012-01-01

    Security Information . . . . . . . . . . . . . . . . .Security Information . . . . . . . . . . . . . . . . . . . . .there is too much information about security properties in

  2. Skepticism avoided

    E-Print Network [OSTI]

    Hawley, Patrick, 1964-

    2003-01-01

    I evaluate three replies to skepticism, drawing conclusions about the meaning of "justified", the viability of foundationalism, the value of knowledge, and the role of belief in rational action. In the first chapter, I ...

  3. Audit Costs for the 1986 Texas Energy Cost Containment Program 

    E-Print Network [OSTI]

    Heffington, W. M.; Lum, S. K.; Bauer, V. A.; Turner, W. D.

    1987-01-01

    Direct program costs for detailed audits of 13.5 million square feet of institutional building space in the 1986 Texas Energy Cost Containment Program were $0.047/SF. The building area was 63 percent simple (offices, schools, and universities...

  4. Stochastic Optimisation Methods for Cost-E ective Quality

    E-Print Network [OSTI]

    Fouskakis, Dimitris

    is traditionally measured by using logistic regression of mortality within 30 days of admission on O(100) sickness are sharply better than SA in this problem for all values of p studied; and (iii) optimal subsets of variables that compromise between data collection costs and predictive accuracy have the potential to generate large cost

  5. Cost Type Examples Salary costs for staff working

    E-Print Network [OSTI]

    Rambaut, Andrew

    in animal house facility standard charge-out rates (excluding building depreciation) which we will pay, delivery and freight. Animal research costs Animal purchase and transportation costs. Animal maintenance employed on the grant. Training on specific skills relevant to the research project (e.g. animal handling

  6. Cascaded Microinverter PV System for Reduced Cost

    SciTech Connect (OSTI)

    Bellus, Daniel R.; Ely, Jeffrey A.

    2013-04-29

    In this project, a team led by Delphi will develop and demonstrate a novel cascaded photovoltaic (PV) inverter architecture using advanced components. This approach will reduce the cost and improve the performance of medium and large-sized PV systems. The overall project objective is to develop, build, and test a modular 11-level cascaded three-phase inverter building block for photovoltaic applications and to develop and analyze the associated commercialization plan. The system will be designed to utilize photovoltaic panels and will supply power to the electric grid at 208 VAC, 60 Hz 3-phase. With the proposed topology, three inverters, each with an embedded controller, will monitor and control each of the cascade sections, reducing costs associated with extra control boards. This report details the final disposition on this project.

  7. JUMP DIFFUSION OPTION WITH TRANSACTION COSTS

    E-Print Network [OSTI]

    Mocioalca, Oana

    JUMP DIFFUSION OPTION WITH TRANSACTION COSTS "non-systematic" risk, inclusive of transaction costs. We compute the total transac- tion costs and the turnover for different options, transaction costs, and revision intervals

  8. Cost and quality of fuels for electric plants 1993

    SciTech Connect (OSTI)

    Not Available

    1994-07-01

    The Cost and Quality of Fuels for Electric Utility Plants (C&Q) presents an annual summary of statistics at the national, Census division, State, electric utility, and plant levels regarding the quantity, quality, and cost of fossil fuels used to produce electricity. The purpose of this publication is to provide energy decision-makers with accurate and timely information that may be used in forming various perspectives on issues regarding electric power.

  9. An Explanation of F&A Costs What are F&A Costs?

    E-Print Network [OSTI]

    Tipple, Brett

    An Explanation of F&A Costs What are F&A Costs? Costs involved in conducting sponsored projects are categorized in two ways: direct costs or indirect costs. The federal government refers officially to indirect costs as facilities and administrative (F&A) costs, sometimes simply called "overhead" costs. Direct

  10. Addressing Deferred Maintenance, Infrastructure Costs, and Excess...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Addressing Deferred Maintenance, Infrastructure Costs, and Excess Facilities at Portsmouth and Paducah Addressing Deferred Maintenance, Infrastructure Costs, and Excess Facilities...

  11. Hydrogen Production Cost Estimate Using Biomass Gasification: Independent Review

    SciTech Connect (OSTI)

    2011-10-01

    This independent review is the conclusion arrived at from data collection, document reviews, interviews and deliberation from December 2010 through April 2011 and the technical potential of Hydrogen Production Cost Estimate Using Biomass Gasification. The Panel reviewed the current H2A case (Version 2.12, Case 01D) for hydrogen production via biomass gasification and identified four principal components of hydrogen levelized cost: CapEx; feedstock costs; project financing structure; efficiency/hydrogen yield. The panel reexamined the assumptions around these components and arrived at new estimates and approaches that better reflect the current technology and business environments.

  12. Theoretical, Methodological, and Empirical Approaches to Cost Savings: A Compendium

    SciTech Connect (OSTI)

    M Weimar

    1998-12-10

    This publication summarizes and contains the original documentation for understanding why the U.S. Department of Energy's (DOE's) privatization approach provides cost savings and the different approaches that could be used in calculating cost savings for the Tank Waste Remediation System (TWRS) Phase I contract. The initial section summarizes the approaches in the different papers. The appendices are the individual source papers which have been reviewed by individuals outside of the Pacific Northwest National Laboratory and the TWRS Program. Appendix A provides a theoretical basis for and estimate of the level of savings that can be" obtained from a fixed-priced contract with performance risk maintained by the contractor. Appendix B provides the methodology for determining cost savings when comparing a fixed-priced contractor with a Management and Operations (M&O) contractor (cost-plus contractor). Appendix C summarizes the economic model used to calculate cost savings and provides hypothetical output from preliminary calculations. Appendix D provides the summary of the approach for the DOE-Richland Operations Office (RL) estimate of the M&O contractor to perform the same work as BNFL Inc. Appendix E contains information on cost growth and per metric ton of glass costs for high-level waste at two other DOE sites, West Valley and Savannah River. Appendix F addresses a risk allocation analysis of the BNFL proposal that indicates,that the current approach is still better than the alternative.

  13. Defining groundwater remediation objectives with cost-1 benefit analysis: does it work?2

    E-Print Network [OSTI]

    Paris-Sud XI, Université de

    1 Defining groundwater remediation objectives with cost-1 benefit analysis: does it work?2 3 J at the local (site) level. This paper questions whether12 CBA is relevant for evaluating groundwater management the cost of groundwater14 protection and remediation measures at the regional (water body) level. It also

  14. Computational investigations of folded self-avoiding walks related to protein folding

    E-Print Network [OSTI]

    Bahi, Jacques M; Mazouzi, Kamel; Philippe, Laurent

    2013-01-01

    Various subsets of self-avoiding walks naturally appear when investigating existing methods designed to predict the 3D conformation of a protein of interest. Two such subsets, namely the folded and the unfoldable self-avoiding walks, are studied computationally in this article. We show that these two sets are equal and correspond to the whole $n$-step self-avoiding walks for $n\\leqslant 14$, but that they are different for numerous $n \\geqslant 108$, which are common protein lengths. Concrete counterexamples are provided and the computational methods used to discover them are completely detailed. A tool for studying these subsets of walks related to both pivot moves and proteins conformations is finally presented.

  15. Cost Principles Policy Responsible Office: Cost Analysis Effective Date: November 1, 2013

    E-Print Network [OSTI]

    Hill, Jeffrey E.

    Cost Principles Policy Responsible Office: Cost Analysis Effective Date: November 1, 2013 Last-21, Cost Principles for Educational Institutions and the Cost Accounting Standards Board (CASB)) identify cost accounting policies that must be followed to receive federal awards. These regulations

  16. Production Costing Models 1 Introduction

    E-Print Network [OSTI]

    McCalley, James D.

    at each hour, The load is specified; A unit commitment decision is made; A dispatch decision is made. An important characterizing feature of PCMs is how it makes the unit commitment (UC) and dispatch decisions) such that units with lowest average cost are committed first. Startup costs are added when a unit #12;5 is started

  17. Turfgrass: Maintenance Costs in Texas. 

    E-Print Network [OSTI]

    Holt, Ethan C.; Allen, W. Wayne; Ferguson, Marvin H.

    1964-01-01

    LAW FOR VARIOUS M-AINTENANCE ITEMS BASED ON O\\!'\\'S. ERSHIP AND TYPE OF GRASS WITHIN EACH REGION Maintenance items TY PC Percent Lot size, Region of oz;r- of lawns square Com~osty Fertilizer Chemicals Water Average grass in region feet cost cost...

  18. Use of Cost Estimating Relationships

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    Cost Estimating Relationships (CERs) are an important tool in an estimator's kit, and in many cases, they are the only tool. Thus, it is important to understand their limitations and characteristics. This chapter discusses considerations of which the estimator must be aware so the Cost Estimating Relationships can be properly used.

  19. Entanglement, avoided crossings, and quantum chaos in an Ising model with a tilted magnetic field

    SciTech Connect (OSTI)

    Karthik, J.; Sharma, Auditya; Lakshminarayan, Arul [Department of Physics, Indian Institute of Technology Madras, Chennai 600036 (India)

    2007-02-15

    We study a one-dimensional Ising model with a magnetic field and show that tilting the field induces a transition to quantum chaos. We explore the stationary states of this Hamiltonian to show the intimate connection between entanglement and avoided crossings. In general, entanglement gets exchanged between the states undergoing an avoided crossing with an overall enhancement of multipartite entanglement at the closest point of approach, simultaneously accompanied by diminishing two-body entanglement as measured by concurrence. We find that both for stationary as well as nonstationary states, nonintegrability leads to a destruction of two-body correlations and distributes entanglement more globally.

  20. Innovative Feed-In Tariff Designs that Limit Policy Costs

    SciTech Connect (OSTI)

    Kreycik, C.; Couture, T. D.; Cory, K. S.

    2011-06-01

    Feed-in tariffs (FITs) are the most prevalent renewable energy policy used globally to date, and there are many benefits to the certainty offered in the marketplace to reduce development risks and associated financing costs and to grow the renewable energy industry. However, concerns over escalating costs in jurisdictions with FIT policies have led to increased attention on cost control in renewable energy policy design. In recent years, policy mechanisms for containing FIT costs have become more refined, allowing policymakers to exert greater control on policy outcomes and on the resulting costs to ratepayers. As policymakers and regulators in the United States begin to explore the use of FITs, careful consideration must be given to the ways in which policy design can be used to balance the policies' advantages while bounding its costs. This report explores mechanisms that policymakers have implemented to limit FIT policy costs. If designed clearly and transparently, such mechanisms can align policymaker and market expectations for project deployment. Three different policy tools are evaluated: (1) caps, (2) payment level adjustment mechanisms, and (3) auction-based designs. The report employs case studies to explore the strengths and weaknesses of these three cost containment tools. These tools are then evaluated with a set of criteria including predictability for policymakers and the marketplace and the potential for unintended consequences.

  1. A cost-benefit analysis of rural-urban migration decisions in less developed countries 

    E-Print Network [OSTI]

    Aste-Salazar, Juan Gerardo

    1973-01-01

    the 'predictive power of cost-benefit analysis and will avoid any measure- ment problem. In the case of perfect competition where all goods and services are priced, the results given by the cost-benefit tools are completely reliable. [49]. But under... in Africa. He has concluded that migration is primarily an economic phenomenon where the migrant, knowing his probability of getting a job is low, takes a chance and plays a "game of lottery" pulled by the rural-urban wage differential. The great wage...

  2. ANALYSIS OF SAFETY RELIEF VALVE PROOF TEST DATA TO OPTIMIZE LIFECYCLE MAINTENANCE COSTS

    SciTech Connect (OSTI)

    Gross, Robert; Harris, Stephen

    2007-08-01

    Proof test results were analyzed and compared with a proposed life cycle curve or hazard function and the limit of useful life. Relief valve proof testing procedures, statistical modeling, data collection processes, and time-in-service trends are presented. The resulting analysis of test data allows for the estimation of the PFD. Extended maintenance intervals to the limit of useful life as well as methodologies and practices for improving relief valve performance and reliability are discussed. A generic cost-benefit analysis and an expected life cycle cost reduction concludes that $90 million maintenance dollars might be avoided for a population of 3000 valves over 20 years.

  3. Geothermal Exploration Cost and Time

    SciTech Connect (OSTI)

    Jenne, Scott

    2013-02-13

    The Department of Energy’s Geothermal Technology Office (GTO) provides RD&D funding for geothermal exploration technologies with the goal of lowering the risks and costs of geothermal development and exploration. The National Renewable Energy Laboratory (NREL) was tasked with developing a metric in 2012 to measure the impacts of this RD&D funding on the cost and time required for exploration activities. The development of this cost and time metric included collecting cost and time data for exploration techniques, creating a baseline suite of exploration techniques to which future exploration cost and time improvements can be compared, and developing an online tool for graphically showing potential project impacts (all available at http://en.openei.org/wiki/Gateway: Geothermal). This paper describes the methodology used to define the baseline exploration suite of techniques (baseline), as well as the approach that was used to create the cost and time data set that populates the baseline. The resulting product, an online tool for measuring impact, and the aggregated cost and time data are available on the Open Energy Information website (OpenEI, http://en.openei.org) for public access. - Published 01/01/2013 by US National Renewable Energy Laboratory NREL.

  4. Total Ownership Cost (TOC) Cost as an Independent Variable

    E-Print Network [OSTI]

    $ + procurement $ + operation $ + logistical support $ + disposal $ Linked - Indirect Direct Direct Cost Life with the research, development, procurement, operation, logistical support and disposal of an individual weapon, operation, logistical support and disposal of an individual weapon system including the total supporting

  5. Impact of contour on aesthetic judgments and approach-avoidance decisions in architecture

    E-Print Network [OSTI]

    Chatterjee, Anjan

    Department of Architecture, Design, and Media Technology, University of Aalborg, DK - 9000 Aalborg, DenmarkImpact of contour on aesthetic judgments and approach-avoidance decisions in architecture Oshin, Spain; h The Royal Danish Academy of Fine Arts, Schools of Architecture, Design, and Conservation

  6. Sterile Technique Sterile (aseptic) technique is essential to avoiding contamination in yeast chronological life span

    E-Print Network [OSTI]

    Aris, John P.

    Sterile Technique Sterile (aseptic) technique is essential to avoiding contamination in yeast experiments have increased risk for contamination because the same samples / tubes are opened repeatedly over containers are open. Keep air movement to a minimum to limit airborne contamination. 6. Do not pour sterile

  7. Synchronization of Washing Operations with Droplet Routing for Cross-Contamination Avoidance in Digital Microfluidic

    E-Print Network [OSTI]

    Chakrabarty, Krishnendu

    Synchronization of Washing Operations with Droplet Routing for Cross-Contamination Avoidance in many areas of biochemistry and biomedical sciences. Since cross-contamination between droplets-droplet routing with sample/reagent drop- let-routing steps by controlling the arrival order of droplets at cross-contamination

  8. Residual-Energy-Activated Cooperative Transmission (REACT) to Avoid the Energy Hole

    E-Print Network [OSTI]

    Ingram, Mary Ann

    Residual-Energy-Activated Cooperative Transmission (REACT) to Avoid the Energy Hole Jin Woo Jung of the excess energy to do cooperative transmission (CT) to hop directly to the Sink, thereby relieving residual energy than the current node. The paper considers several criteria for selecting the cooperators

  9. COMPREHENSIVE COLLISION AVOIDANCE SYSTEM FOR BURIED UTILITIES Sanat A. Talmaki 1

    E-Print Network [OSTI]

    Kamat, Vineet R.

    COMPREHENSIVE COLLISION AVOIDANCE SYSTEM FOR BURIED UTILITIES Sanat A. Talmaki 1 , Suyang Dong 2, University of Michigan, vkamat@umich.edu ABSTRACT Society is often guilty of taking our buried utilities utilities maintenance techniques. The underground world is sometimes denser than the above-ground world

  10. Evolution of Driving Agent, Remotely Operating a Scale Model of a Car with Obstacle Avoidance Capabilities

    E-Print Network [OSTI]

    Fernandez, Thomas

    Evolution of Driving Agent, Remotely Operating a Scale Model of a Car with Obstacle Avoidance present an approach for evolutionary design of an agent, remotely operating a scale model of a car running to the car via standard radio control transmitter. In order to cope with the video feed latency we propose

  11. Data Center Demand Response: Avoiding the Coincident Peak via Workload Shifting and Local Generation

    E-Print Network [OSTI]

    Wierman, Adam

    Data Center Demand Response: Avoiding the Coincident Peak via Workload Shifting and Local facilities. In this extended abstract we briefly de- scribe recent work in [1] on two demand response schemes Keywords Demand response, coincident peak pricing, data center, work- load shifting, online algorithm 1

  12. Avoiding the Rush Hours: WiFi Energy Management via Traffic Isolation

    E-Print Network [OSTI]

    Shihada, Basem

    Avoiding the Rush Hours: WiFi Energy Management via Traffic Isolation Justin Manweiler Duke in a proportional decrease in battery life. We design SleepWell, a system that achieves energy efficiency by evading to turn off the de- vice whenever beneficial. While WiFi energy efficiency has progressively improved

  13. Some new self-avoiding walk and polygon models Nicholas R Beaton

    E-Print Network [OSTI]

    Guttman, Tony

    3010 Australia and ARC Centre of Excellence for Mathematics and Statistics of Complex Systems + Algorithms Project, INRIA--Rocquencourt, 78513 Le Chesnay, France School of Mathematical Sciences, Monash) on a two-dimensional lattice, enumerated by length, and of self-avoiding polygons (SAP) enumerated

  14. Collapse transition of a hydrophobic self avoiding random walk in a coarse-grained model solvent

    E-Print Network [OSTI]

    Vinals, Jorge

    Collapse transition of a hydrophobic self avoiding random walk in a coarse-grained model solvent in a lattice model of a solvent. As expected, hydrophobic interactions lead to an attractive potential of mean force among chain segments. As a consequence, the random walk in solvent undergoes a collapse transition

  15. HOW TO AVOID OVERCOOKING: OPTIMAL YIELD OF B FROM THE CONSECUTIVE CHEMICAL REACTIONS ABC

    E-Print Network [OSTI]

    Salamon, Peter

    HOW TO AVOID OVERCOOKING: OPTIMAL YIELD OF B FROM THE CONSECUTIVE CHEMICAL REACTIONS A´B´C Thor A the consecutive chemical reactions A´B´C both numerically and analytically using temperature as the control. Keywords: Optimal control, Chemical reactions, Temperature control, Optimal yield INTRODUCTION Already half

  16. Export Control in a Nutshell Avoiding Severe Federal Penalties Short Briefing for Academic and Staff Personnel

    E-Print Network [OSTI]

    Derisi, Joseph

    Export Control in a Nutshell ­ Avoiding Severe Federal Penalties Short Briefing for Academic of the U.S. without first conferring with your campus export office to determine if a license is required. Export regulations govern any transfer of physical objects (be it equipment, compounds, materials

  17. Fractals Meet Fractals: Self-Avoiding Random Walks on Percolation Viktoria Blavatskaa,b

    E-Print Network [OSTI]

    Janke, Wolfhard

    polymers in disordered media, modelled by self-avoiding walks (SAWs) on the backbone of percolation-enriched Rosenbluth chain-growth method (PERM). Our numerical results yield estimates of critical exponents, governing the scaling laws of disorder averages of the configurational properties of SAWs, and clearly indicate

  18. SO2 as a proxy for volcanic ash in aviation hazard avoidance

    E-Print Network [OSTI]

    Oxford, University of

    SO2 as a proxy for volcanic ash in aviation hazard avoidance Infrared Atmospheric Sounding Interferometer - IASI ABSTRACT: Airborne volcanic ash poses a significant danger to aircraft but is difficult accurately. This paper looks at the reliability of using SO2 as a proxy for the location of volcanic ash

  19. INVASIVE RODENTS ON ISLANDS Avoiding surprise effects on Surprise Island: alien species

    E-Print Network [OSTI]

    Courchamp, Franck

    INVASIVE RODENTS ON ISLANDS Avoiding surprise effects on Surprise Island: alien species control Abstract Eradications of invasive alien species have generally benefited biodiversity. However, without following the sudden removal of an invasive alien that was exerting an ecological force on those species

  20. Multi-Layer Network Recovery: Avoiding Traffic Disruptions against Fiber Failures

    E-Print Network [OSTI]

    Ortega, Eusebi Calle

    Multi-Layer Network Recovery: Avoiding Traffic Disruptions against Fiber Failures Anna Urra, Eusebi 17071, Spain Abstract. The next generation backbone networks, optical IP/MPLS networks, enable increasingly higher volumes of information to be trans- ported. In this network architecture, a fiber failure

  1. (2013) 128 Data Center Demand Response: Avoiding the Coincident Peak via

    E-Print Network [OSTI]

    Wierman, Adam

    2013-01-01

    (2013) 1­28 Data Center Demand Response: Avoiding the Coincident Peak via Workload Shifting.chen@hp.com Abstract Demand response is a crucial aspect of the future smart grid. It has the potential to provide centers' participation in demand response is becoming increasingly important given their high

  2. Cost | OpenEI Community

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on QA:QA J-E-1 SECTION J APPENDIX E LISTStar EnergyLawler,CoalConcordiaConsumer ConnectionCoralCorvalenceCosoCostCostCost

  3. Facilities & Administrative (F&A) Costs at NIU F&A costs at NIU

    E-Print Network [OSTI]

    Karonis, Nicholas T.

    Facilities & Administrative (F&A) Costs at NIU #12;F&A costs at NIU What are Facilities & Administrative (F&A) Costs? F&A Costs (aka "indirect costs" or "overhead") are real institutional costs project, instructional or public service activity. Such costs include utilities, buildings and facilities

  4. Low-cost interference lithography

    E-Print Network [OSTI]

    Fucetola, Corey P.

    The authors report demonstration of a low-cost ( ? 1000 USD) interference lithography system based on a Lloyd’s mirror interferometer that is capable of ? 300?nm pitch patterning. The components include only a 405?nm GaN ...

  5. Memory cost of quantum protocols

    E-Print Network [OSTI]

    Alessandro Bisio; Giacomo Mauro D'Ariano; Paolo Perinotti; Michal Sedlak

    2011-12-16

    In this paper we consider the problem of minimizing the ancillary systems required to realize an arbitrary strategy of a quantum protocol, with the assistance of classical memory. For this purpose we introduce the notion of memory cost of a strategy, which measures the resources required in terms of ancillary dimension. We provide a condition for the cost to be equal to a given value, and we use this result to evaluate the cost in some special cases. As an example we show that any covariant protocol for the cloning of a unitary transformation requires at most one ancillary qubit. We also prove that the memory cost has to be determined globally, and cannot be calculated by optimizing the resources independently at each step of the strategy.

  6. Maximum output at minimum cost

    E-Print Network [OSTI]

    Firestone, Jeremy

    Gamesa G90-2.0 MW #12;Maximum output at minimum cost per kWh for low wind sites ®® Class IIIA mast and the electrical substation. This innovative modular design based on TCP/IP architecture has

  7. Letting The Sun Shine On Solar Costs: An Empirical Investigation Of Photovoltaic Cost Trends In California

    E-Print Network [OSTI]

    Wiser, Ryan; Bolinger, Mark; Cappers, Peter; Margolis, Robert

    2006-01-01

    THE SUN SHINE ON SOLAR COSTS: AN EMPIRICAL INVESTIGATION OFWe find that: (1) solar costs have declined substantially2004 $/W AC . 4. SOLAR COSTS HAVE DECLINED SUBSTANTIALLY In

  8. Letting The Sun Shine On Solar Costs: An Empirical Investigation Of Photovoltaic Cost Trends In California

    E-Print Network [OSTI]

    Wiser, Ryan; Bolinger, Mark; Cappers, Peter; Margolis, Robert

    2006-01-01

    infrastructure. Though PV cost reductions in California areworldwide. Data on PV capacity and costs are expresseddepth statistical analysis of PV system costs in California.

  9. Costing Summaries for Selected Water Treatment

    E-Print Network [OSTI]

    · Engineering News-Record Construction Cost Index · Consumer Prices Index · Year Index = average of the monthly values of the year )( )( )()( yyearIndexCost xyearIndexCost yyearCostxyearCostUpdated ×= #12;Slow SandCosting Summaries for Selected Water Treatment Processes Alix Montel Ecole Centrale de Nantes M

  10. CAS Indirect Cost Recovery Practices "Facilities and Administration" (F&A) Costs or, "Indirect Cost Recovery (ICR)," are costs incurred by the

    E-Print Network [OSTI]

    Vonessen, Nikolaus

    CAS Indirect Cost Recovery Practices "Facilities and Administration" (F&A) Costs or, "Indirect Cost Recovery (ICR)," are costs incurred by the University for common or joint projects and cannot be specifically attributed to an individual project. Some examples of indirect costs include accounting staff

  11. Wind power costs in Portugal Saleiro, Carla

    E-Print Network [OSTI]

    Wind power costs in Portugal Saleiro, Carla Department of Biological Engineering, University, following the European tendency. This analysis sets out to evaluate the total generating cost of wind power and CCGT in Portugal. A life cycle cost analysis was conducted, including investment costs, O&M costs, fuel

  12. Estimated Costs of Pasture and Hay Production

    E-Print Network [OSTI]

    Duffy, Michael D.

    Estimated Costs of Pasture and Hay Production This report summarizes estimated costs of improving pasture by five different systems. For each system, both the initial cost per acre and the annual maintenance cost per acre are presented. In addition, costs of establishing alfalfa or alfalfagrass hay

  13. Estimated Costs of Pasture and Hay Production

    E-Print Network [OSTI]

    Duffy, Michael D.

    Estimated Costs of Pasture and Hay Production This report summarizes estimated costs of improving pasture by five different systems. For each system, both the initial cost per acre and the annual maintenance cost per acre are presented. In addition, costs of establishing alfalfa or alfalfa-grass hay

  14. Optimal control of a large dam, taking into account the water costs [New Edition

    E-Print Network [OSTI]

    Abramov, Vyacheslav M

    2009-01-01

    This paper studies large dam models where the difference between lower and upper levels $L$ is assumed to be large. Passage across the levels leads to damage, and the damage costs of crossing the lower or upper level are proportional to the large parameter $L$. Input stream of water is described by compound Poisson process, and the water cost depends upon current level of water in the dam. The aim of the paper is to choose the parameters of output stream (specifically defined in the paper) minimizing the long-run expenses. The particular problem, where input stream is Poisson and water costs are not taken into account has been studied in [Abramov, \\emph{J. Appl. Prob.}, 44 (2007), 249-258]. The present paper partially answers the question \\textit{How does the structure of water costs affect the optimal solution?} In particular the case of linear costs is studied.

  15. Benefits and Costs of Aggressive Energy Efficiency Programs and the Impacts of Alternative Sources of Funding: Case Study of Massachusetts

    E-Print Network [OSTI]

    Cappers, Peter

    2010-01-01

    include different energy efficiency resource savings levels,bidding strategy of energy efficiency resources and receiveResource Costs and Benefits of Alternative Energy Efficiency

  16. Crickets groom to avoid lethal parasitoids Crystal M. Vincent*, Susan M. Bertram 1

    E-Print Network [OSTI]

    Bertram, Sue

    planidia tachinid Texas field cricket Hosts that are infected by parasitoids pay the ultimate cost: death into the cricket host where they feed and grow. Because parasitism invariably results in host death, there should be extremely costly. They can depress insect development and maturation rates (Smith 1988), and reduce mating

  17. Low-level waste program technical strategy

    SciTech Connect (OSTI)

    Bledsoe, K.W.

    1994-10-01

    The Low-Level Waste Technical Strategy document describes the mechanisms which the Low-Level Waste Program Office plans to implement to achieve its mission. The mission is to manage the receipt, immobilization, packaging, storage/disposal and RCRA closure (of the site) of the low-level Hanford waste (pretreated tank wastes) in an environmentally sound, safe and cost-effective manner. The primary objective of the TWRS Low-level waste Program office is to vitrify the LLW fraction of the tank waste and dispose of it onsite.

  18. Information, Diversification, and Cost of Capital

    E-Print Network [OSTI]

    Hughes, John S; Liu, Jing; Liu, Jun

    2005-01-01

    insider trading and cost of capital. ” Working paper, UCLA,Information and the cost of capital. ” Journal of Finance,in Determining Cost of Equity Capital,” Review of Accounting

  19. Total cost model for making sourcing decisions

    E-Print Network [OSTI]

    Morita, Mark, M.B.A. Massachusetts Institute of Technology

    2007-01-01

    This thesis develops a total cost model based on the work done during a six month internship with ABB. In order to help ABB better focus on low cost country sourcing, a total cost model was developed for sourcing decisions. ...

  20. Arbitration Costs and Contingent Fee Contracts

    E-Print Network [OSTI]

    Drahozal, Christopher R.

    2005-08-03

    A common criticism of arbitration is that its upfront costs (arbitrators' fees and administrative costs) may preclude consumers and employees from asserting their claims. Some commentators have argued further that arbitration costs undercut...

  1. Plant Energy Cost Optimization Program (PECOP) 

    E-Print Network [OSTI]

    Robinson, A. M.

    1980-01-01

    The Plant Energy Cost Optimization Program (PECOP) is a Management System designed to reduce operating cost in a continuous operating multi product plant by reviewing all cost factors and selecting plant wide production schedules which are most...

  2. USA oilgas production cost : recent changes

    E-Print Network [OSTI]

    Adelman, Morris Albert

    1991-01-01

    During 1984-1989, oil development investment cost in the USA fell, but only because of lower activity. The whole cost curve shifted unfavorably (leftward). In contrast, natural gas cost substantially decreased, the curve ...

  3. COMPARATIVE COSTS OF CALIFORNIA CENTRAL STATION ELECTRICITY

    E-Print Network [OSTI]

    CALIFORNIA ENERGY COMMISSION COMPARATIVE COSTS OF CALIFORNIA CENTRAL STATION ELECTRICITY GENERATIONCann Please use the following citation for this report: Klein, Joel. 2009. Comparative Costs of California............................................................................................................................1 Changes in the Cost of Generation Model

  4. COMPARATIVE COSTS OF CALIFORNIA CENTRAL STATION ELECTRICITY

    E-Print Network [OSTI]

    Laughlin, Robert B.

    CALIFORNIA ENERGY COMMISSION COMPARATIVE COSTS OF CALIFORNIA CENTRAL STATION ELECTRICITY GENERATION and Anitha Rednam, Comparative Costs of California Central Station Electricity Generation Technologies................................................................................................... 1 CHAPTER 1: Summary of Technology Costs

  5. Maintenance cost studies of present aircraft subsystems

    E-Print Network [OSTI]

    Pearlman, Chaim Herman Shalom

    1966-01-01

    This report describes two detailed studies of actual maintenance costs for present transport aircraft. The first part describes maintenance costs for jet transport aircraft broken down into subsystem costs according to an ...

  6. Cost-Effective Cable Insulation: Nanoclay Reinforced Ethylene-Propylene-Rubber for Low-Cost HVDC Cabling

    SciTech Connect (OSTI)

    2012-02-24

    GENI Project: GE is developing new, low-cost insulation for high-voltage direct current (HVDC) electricity transmission cables. The current material used to insulate HVDC transmission cables is very expensive and can account for as much as 1/3 of the total cost of a high-voltage transmission system. GE is embedding nanomaterials into specialty rubber to create its insulation. Not only are these materials less expensive than those used in conventional HVDC insulation, but also they will help suppress excess charge accumulation. The excess charge left behind on a cable poses a major challenge for high-voltage insulation—if it’s not kept to a low level, it could ultimately lead the insulation to fail. GE’s low-cost insulation is compatible with existing U.S. cable manufacturing processes, further enhancing its cost effectiveness.

  7. Virginia Offshore Wind Cost Reduction Through Innovation Study (VOWCRIS) (Poster)

    SciTech Connect (OSTI)

    Maples, B.; Campbell, J.; Arora, D.

    2014-10-01

    The VOWCRIS project is an integrated systems approach to the feasibility-level design, performance, and cost-of-energy estimate for a notional 600-megawatt offshore wind project using site characteristics that apply to the Wind Energy Areas of Virginia, Maryland and North Carolina.

  8. Cost and quality of fuels for electric utility plants, 1994

    SciTech Connect (OSTI)

    1995-07-14

    This document presents an annual summary of statistics at the national, Census division, State, electric utility, and plant levels regarding the quantity, quality, and cost of fossil fuels used to produce electricity. Purpose of this publication is to provide energy decision-makers with accurate, timely information that may be used in forming various perspectives on issues regarding electric power.

  9. An analysis of nuclear power plant operating costs: A 1995 update

    SciTech Connect (OSTI)

    1995-04-21

    Over the years real (inflation-adjusted) O&M cost have begun to level off. The objective of this report is to determine whether the industry and NRC initiatives to control costs have resulted in this moderation in the growth of O&M costs. Because the industry agrees that the control of O&M costs is crucial to the viability of the technology, an examination of the factors causing the moderation in costs is important. A related issue deals with projecting nuclear operating costs into the future. Because of the escalation in nuclear operating costs (and the fall in fossil fuel prices) many State and Federal regulatory commissions are examining the economics of the continued operation of nuclear power plants under their jurisdiction. The economics of the continued operation of a nuclear power plant is typically examined by comparing the cost of the plants continued operation with the cost of obtaining the power from other sources. This assessment requires plant-specific projections of nuclear operating costs. Analysts preparing these projections look at past industry-wide cost trends and consider whether these trends are likely to continue. To determine whether these changes in trends will continue into the future, information about the causal factors influencing costs and the future trends in these factors are needed. An analysis of the factors explaining the moderation in cost growth will also yield important insights into the question of whether these trends will continue.

  10. Land-Based Wind Plant Balance-of-System Cost Drivers and Sensitivities (Poster)

    SciTech Connect (OSTI)

    Mone, C.; Maples, B.; Hand, M.

    2014-04-01

    With Balance of System (BOS) costs contributing up to 30% of the installed capital cost, it is fundamental to understand the BOS costs for wind projects as well as potential cost trends for larger turbines. NREL developed a BOS model using project cost estimates developed by industry partners. Aspects of BOS covered include engineering and permitting, foundations for various wind turbines, transportation, civil work, and electrical arrays. The data introduce new scaling relationships for each BOS component to estimate cost as a function of turbine parameters and size, project parameters and size, and geographic characteristics. Based on the new BOS model, an analysis to understand the non?turbine wind plant costs associated with turbine sizes ranging from 1-6 MW and wind plant sizes ranging from 100-1000 MW has been conducted. This analysis establishes a more robust baseline cost estimate, identifies the largest cost components of wind project BOS, and explores the sensitivity of the capital investment cost and the levelized cost of energy to permutations in each BOS cost element. This presentation shows results from the model that illustrate the potential impact of turbine size and project size on the cost of energy from US wind plants.

  11. Cost Principles Directives & Procedures Responsible Office: Cost Analysis Effective Date: November 1, 2013

    E-Print Network [OSTI]

    Hill, Jeffrey E.

    1 Cost Principles Directives & Procedures Responsible Office: Cost Analysis Effective Date....................................................................................................................... 2 2. Guiding Principles to Determine the Charge of a Cost to a Sponosred Agreement ................................................................................................. 5 5.1. Personnel Costs

  12. Statistical Inference for Costs and Incremental Cost-Effectiveness Ratios with Censored Data 

    E-Print Network [OSTI]

    Chen, Shuai

    2012-07-16

    Cost-effectiveness analysis is widely conducted in the economic evaluation of new treatment options. In many clinical and observational studies of costs, data are often censored. Censoring brings challenges to both medical cost estimation and cost...

  13. Developing a Cost Model and Methodology to Estimate Capital Costs for Thermal Energy Storage

    SciTech Connect (OSTI)

    Glatzmaier, G.

    2011-12-01

    This report provides an update on the previous cost model for thermal energy storage (TES) systems. The update allows NREL to estimate the costs of such systems that are compatible with the higher operating temperatures associated with advanced power cycles. The goal of the Department of Energy (DOE) Solar Energy Technology Program is to develop solar technologies that can make a significant contribution to the United States domestic energy supply. The recent DOE SunShot Initiative sets a very aggressive cost goal to reach a Levelized Cost of Energy (LCOE) of 6 cents/kWh by 2020 with no incentives or credits for all solar-to-electricity technologies.1 As this goal is reached, the share of utility power generation that is provided by renewable energy sources is expected to increase dramatically. Because Concentrating Solar Power (CSP) is currently the only renewable technology that is capable of integrating cost-effective energy storage, it is positioned to play a key role in providing renewable, dispatchable power to utilities as the share of power generation from renewable sources increases. Because of this role, future CSP plants will likely have as much as 15 hours of Thermal Energy Storage (TES) included in their design and operation. As such, the cost and performance of the TES system is critical to meeting the SunShot goal for solar technologies. The cost of electricity from a CSP plant depends strongly on its overall efficiency, which is a product of two components - the collection and conversion efficiencies. The collection efficiency determines the portion of incident solar energy that is captured as high-temperature thermal energy. The conversion efficiency determines the portion of thermal energy that is converted to electricity. The operating temperature at which the overall efficiency reaches its maximum depends on many factors, including material properties of the CSP plant components. Increasing the operating temperature of the power generation system leads to higher thermal-to-electric conversion efficiency. However, in a CSP system, higher operating temperature also leads to greater thermal losses. These two effects combine to give an optimal system-level operating temperature that may be less than the upper operating temperature limit of system components. The overall efficiency may be improved by developing materials, power cycles, and system-integration strategies that enable operation at elevated temperature while limiting thermal losses. This is particularly true for the TES system and its components. Meeting the SunShot cost target will require cost and performance improvements in all systems and components within a CSP plant. Solar collector field hardware will need to decrease significantly in cost with no loss in performance and possibly with performance improvements. As higher temperatures are considered for the power block, new working fluids, heat-transfer fluids (HTFs), and storage fluids will all need to be identified to meet these new operating conditions. Figure 1 shows thermodynamic conversion efficiency as a function of temperature for the ideal Carnot cycle and 75% Carnot, which is considered to be the practical efficiency attainable by current power cycles. Current conversion efficiencies for the parabolic trough steam cycle, power tower steam cycle, parabolic dish/Stirling, Ericsson, and air-Brayton/steam Rankine combined cycles are shown at their corresponding operating temperatures. Efficiencies for supercritical steam and carbon dioxide (CO{sub 2}) are also shown for their operating temperature ranges.

  14. Self-Avoiding Modes of Motion in a Deterministic Lorentz Lattice Gas

    E-Print Network [OSTI]

    Benjamin Webb; E. G. D. Cohen

    2014-04-14

    We study the motion of a particle on the two-dimensional honeycomb lattice, whose sites are occupied by either flipping rotators or flipping mirrors, which scatter the particle according to a deterministic rule. For both types of scatterers we find a new type of motion that has not been observed in a Lorentz Lattice gas, where the particle's trajectory is a self-avoiding walk between returns to its initial position. We show that this behavior is a consequence of the deterministic scattering rule and the particular class of initial scatterer configurations we consider. Since self-avoiding walks are one of the main tools used to model the growth of crystals and polymers, the particle's motion in this class of systems is potentially important for the study of these processes.

  15. Cost objective PLM and CE

    E-Print Network [OSTI]

    Nicolas Perry; Alain Bernard

    2010-11-26

    Concurrent engineering taking into account product life-cycle factors seems to be one of the industrial challenges of the next years. Cost estimation and management are two main strategic tasks that imply the possibility of managing costs at the earliest stages of product development. This is why it is indispensable to let people from economics and from industrial engineering collaborates in order to find the best solution for enterprise progress for economical factors mastering. The objective of this paper is to present who we try to adapt costing methods in a PLM and CE point of view to the new industrial context and configuration in order to give pertinent decision aid for product and process choices. A very important factor is related to cost management problems when developing new products. A case study is introduced that presents how product development actors have referenced elements to product life-cycle costs and impacts, how they have an idea bout economical indicators when taking decisions during the progression of the project of product development.

  16. Fractals Meet Fractals: Self-Avoiding Random Walks on Percolation Clusters

    E-Print Network [OSTI]

    V. Blavatska; W. Janke

    2010-01-11

    The scaling behavior of linear polymers in disordered media, modelled by self-avoiding walks (SAWs) on the backbone of percolation clusters in two, three and four dimensions is studied by numerical simulations. We apply the pruned-enriched Rosenbluth chain-growth method (PERM). Our numerical results yield estimates of critical exponents, governing the scaling laws of disorder averages of the configurational properties of SAWs, and clearly indicate a multifractal spectrum which emerges when two fractals meet each other.

  17. Regulation, Unemployment, and Cost-Benefit Analysis

    E-Print Network [OSTI]

    Posner, Eric; Masur, Jonathan S.

    2011-01-01

    and Eric A. Posner, Regulation, Unemployment, and Cost-effects of environmental regulations for other industries.Paper Collection.   Regulation, Unemployment, and Cost-

  18. Example Cost Codes for Construction Projects

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    This chapter provides an example outline of cost items and their corresponding cost codes that may be used for construction projects.

  19. Multiperiod Portfolio Optimization with General Transaction Costs

    E-Print Network [OSTI]

    2013-07-17

    assets in the presence of general transaction costs such as proportional, market impact ... For proportional transaction costs, we find that a buy-and-hold policy is

  20. Lot Sizing with Piecewise Concave Production Costs

    E-Print Network [OSTI]

    2013-02-14

    Feb 14, 2013 ... procurement/shipment) and inventory holding costs, the aim of the ... is to propose a minimum cost production plan to satisfy the demand (see, ...

  1. Driltac (Drilling Time and Cost Evaluation)

    SciTech Connect (OSTI)

    None

    1986-08-01

    The users manual for the drill tech model for estimating the costs of geothermal wells. The report indicates lots of technical and cost detail. [DJE-2005

  2. Hydrogen Production Cost Estimate Using Biomass Gasification...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Cost Estimate Using Biomass Gasification: Independent Review Hydrogen Production Cost Estimate Using Biomass Gasification: Independent Review This independent review is the...

  3. Modifications to Replacement Costs System

    SciTech Connect (OSTI)

    Godec, M. [ICF Resources, Inc., Fairfax, VA (United States)

    1989-05-18

    The purpose of this memorandum is to document the improvements and modifications made to the Replacement Costs of Crude Oil (REPCO) Supply Analysis System. While some of this work was performed under our previous support contract to DOE/ASFE, we are presenting all modifications and improvements are presented here for completeness. The memo primarily documents revisions made to the Lower-48 Onshore Model. Revisions and modifications made to other components and models in the REPCO system which are documented elsewhere are only highlighted in this memo. Generally, the modifications made to the Lower-48 Onshore Model reflect changes that have occurred in domestic drilling, oil field costs, and reserves since 1982, the date of the most recent available data used for the original Replacement Costs report, published in 1985.

  4. The Amygdala Modulates Memory Consolidation of Fear-Motivated Inhibitory Avoidance Learning But Not Classical Fear Conditioning

    E-Print Network [OSTI]

    Schafe, Glenn

    -trial inhibitory avoidance learning. Immediate post-training infusions of musci- mol had no effect on Pavlovian conditioning but produced a dose-dependent effect on inhibitory avoidance. However, pre- training infusions pre-training infusions of drugs are inherently confounded because of the likelihood that these drugs

  5. To: Research Cost Fund Fieldwork Cost Fund Both Graduate Program in

    E-Print Network [OSTI]

    To: Research Cost Fund Fieldwork Cost Fund Both From: Graduate Program in: Date: Subject: Research Cost Fund/Fieldwork Cost Fund I am submitting the applications for the students listed on the attached spreadsheet for the Research Cost Fund/Fieldwork Cost Fund Competition I confirm that all applications meet

  6. Frequently Asked Questions about Patient Care Costs And a Quick Guide to Patient Care Costs

    E-Print Network [OSTI]

    Janssen, Michel

    Frequently Asked Questions about Patient Care Costs And a Quick Guide to Patient Care Costs questions regarding human research patient care costs. Human research patient care costs are the costs. The costs of these services normally are assigned to specific research projects through the development

  7. Cost-Causation and Integration Cost Analysis for Variable Generation

    SciTech Connect (OSTI)

    Milligan, M.; Ela, E.; Hodge, B. M.; Kirby, B.; Lew, D.; Clark, C.; DeCesaro, J.; Lynn, K.

    2011-06-01

    This report examines how wind and solar integration studies have evolved, what analysis techniques work, what common mistakes are still made, what improvements are likely to be made in the near future, and why calculating integration costs is such a difficult problem and should be undertaken carefully, if at all.

  8. Methodology for Prototyping Increased Levels of Automation

    E-Print Network [OSTI]

    Valasek, John

    Methodology for Prototyping Increased Levels of Automation for Spacecraft Rendezvous Functions of automation than previous NASA vehicles, due to program requirements for automation, including Automated Ren authority between humans and computers (i.e. automation) as a prime driver for cost, safety, and mission

  9. Entanglement cost in practical scenarios

    E-Print Network [OSTI]

    Francesco Buscemi; Nilanjana Datta

    2011-03-03

    We quantify the one-shot entanglement cost of an arbitrary bipartite state, that is the minimum number of singlets needed by two distant parties to create a single copy of the state up to a finite accuracy, using local operations and classical communication only. This analysis, in contrast to the traditional one, pertains to scenarios of practical relevance, in which resources are finite and transformations can only be achieved approximately. Moreover, it unveils a fundamental relation between two well-known entanglement measures, namely, the Schmidt number and the entanglement of formation. Using this relation, we are able to recover the usual expression of the entanglement cost as a special case.

  10. Quantum cost for sending entanglement

    E-Print Network [OSTI]

    Alexander Streltsov; Hermann Kampermann; Dagmar Bruß

    2012-03-07

    Establishing quantum entanglement between two distant parties is an essential step of many protocols in quantum information processing. One possibility for providing long-distance entanglement is to create an entangled composite state within a lab and then physically send one subsystem to a distant lab. However, is this the "cheapest" way? Here, we investigate the minimal "cost" that is necessary for establishing a certain amount of entanglement between two distant parties. We prove that this cost is intrinsically quantum, and is specified by quantum correlations. Our results provide an optimal protocol for entanglement distribution and show that quantum correlations are the essential resource for this task.

  11. Soft Costs | Department of Energy

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantityBonneville Power AdministrationRobust,Field-effect Photovoltaics -7541 *ImpactScience of SignaturesSoft Costs Soft Costs An

  12. Forestry mitigation potential and costs in developing countries - Preface

    SciTech Connect (OSTI)

    Sathaye, Jayant A.; Makundi, Willy; Andrasko, Kenneth

    2001-01-01

    The forest sector in Tanzania offers ample opportunities to reduce greenhouse gas emissions (GHG) and sequestered carbon (C) in terrestrial ecosystems. More than 90% of the country's demand for primary energy is obtained from biomass mostly procured unsustainably from natural forests. This study examines the potential to sequester C through expansion of forest plantations aimed at reducing the dependence on natural forest for wood fuel production, as well as increase the country's output of industrial wood from plantations. These were compared ton conservation options in the tropical and miombo ecosystems. Three sequestration options were analyzed, involving the establishment of short rotation and long rotation plantations on about 1.7 x 106 hectares. The short rotation community forest option has a potential to sequester an equilibrium amount of 197.4 x 106 Mg C by 2024 at a net benefit of $79.5 x 106, while yielding a NPV of $0.46 Mg-1 C. The long rotation options for softwood and hardwood plantations will reach an equilibrium sequestration of 5.6 and 11.8 x 106 Mg C at a negative NPV of $0.60 Mg-1 C and $0.32 Mg-1 C. The three options provide cost competitive opportunities for sequestering about 7.5 x 106 Mg C yr -1 while providing desired forest products and easing the pressure on the natural forests in Tanzania. The endowment costs of the sequestration options were all found to be cheaper than the emission avoidance cost for conservation options which had an average cost of $1.27 Mg-1 C, rising to $7.5 Mg-1 C under some assumptions on vulnerability to encroachment. The estimates shown here may represent the upper bound, because the actual potential will be influenced by market prices for inputs and forest products, land use policy constraints and the structure of global C transactions.

  13. A Second Opinion is Worth the Cost - 12479

    SciTech Connect (OSTI)

    Madsen, Drew [Project Time and Cost Inc. (United States)

    2012-07-01

    This paper, 'A Second Opinion is Worth the Cost', shows how a second opinion for a Department of Energy (DOE) Project helped prepare and pass a DOE Order 413.3A 'Program and Project Management for the acquisition of Capital Assets' Office of Engineering and Construction Management (OECM) required External Independent Review (EIR) in support of the approved baseline for Critical Decision (CD) 2. The DOE project personnel were informed that the project's Total Project Cost (TPC) was going to increase from $815 million to $1.1 billion due to unforeseen problems and unexplained reasons. The DOE Project Team determined that a second opinion was needed to review and validate the TPC. Project Time and Cost, Inc. (PT and C) was requested to evaluate the cost estimate, schedule, basis of estimate (BOE), and risk management plan of the Project and to give an independent assessment of the TPC that was presented to DOE. This paper will demonstrate how breaking down a project to the work breakdown structure (WBS) level allows a project to be analyzed for potential cost increases and/or decreases, thus providing a more accurate TPC. The review Team's cost analyses of Projects identified eight primary drivers resulting in cost increases. They included: - Overstatement of the effort required to develop drawings and specifications. - Cost allocation to 'Miscellaneous' without sufficient detail or documentation. - Cost for duplicated efforts. - Vendor estimates or quotations without sufficient detail. - The practice of using the highest price quoted then adding an additional 10% mark-up. - Application of Nuclear Quality Assurance (NQA) highest level quality requirements when not required. - Allocation of operational costs to the Project Costs instead of to the Operating Expenses (OPEX). OPEX costs come from a different funding source. - DOE had not approved the activities. By using a Team approach with professionals from cost, civil, mechanical, electrical, structural and nuclear disciplines and by performing a Line by Line, WBS element by WBS element review of the Projects' CD-2 baseline package helped the DOE Project Team experience success. The second opinion that PT and C provide by conducting a Pre-EIR review of the Project baseline package and the cost review of the TPC helped the DOE Team pass the CD-2 EIR and reduced the TPC. The Line-by-Line review of the DOE Project identified opportunities to reduce the TPC from $1.1 billion to $740.8 million, thus realizing a saving of approximately $359.2 million, or roughly 32% of the original TPC. This significant cost savings underscores the cost in obtaining the second opinion. This same Line by Line review can be applied to any DOE project in the Energy Management or Weapons complex. In the case of this DOE Project a second opinion was worth the cost. (authors)

  14. The social costs to the US of monopolization of the world oil market, 1972--1991

    SciTech Connect (OSTI)

    Greene, D.L.; Leiby, P.N.

    1993-03-01

    The partial monopolization of the world oil market by the OPEC cartel has produced significant economic costs to the economies of the world. This paper reports estimates of the costs of monopolization of oil to the US over the period 1972--1991. Two fundamental assumptions of the analysis are, (1) that OPEC has acted as a monopoly, albeit with limited control, knowledge, and ability to act and, (2) that the US and other consuming nations could, through collective (social) action affect the cartel`s ability to act as a monopoly. We measure total costs by comparing actual costs for the 1972--1991 period to a hypothetical ``more competitive`` world oil market scenario. By measuring past costs we avoid the enormous uncertainties about the future course of the world oil market and leave to the reader`s judgment the issue of how much the future will be like the past. We note that total cost numbers cannot be used to determine the value of reducing US oil use by one barrel. They are useful for describing the overall size of the petroleum problem and are one important factor in deciding how much effort should be devoted to solving it. Monopoly pricing of oil transfers wealth from US oil consumers to foreign oil producers and, by increasing theeconomic scarcity of oil, reduces the economy`s potential to produce. The actions of the OPEC cartel have also produced oil price shocks, both upward and downward, that generate additional costs because of the economy`s inherent inability to adjust quickly to a large change in energy prices. Estimated total costs to the United States from these three sources for the 1972--1991 period are put at $4.1 trillion in 1990$($1.2 T wealth transfer, $0.8 T macroeconomic adjustment costs, $2.1 T potential GNP losses). The cost of the US`s primary oil supply contingency program is small ($10 B) by comparison.

  15. The social costs to the US of monopolization of the world oil market, 1972--1991

    SciTech Connect (OSTI)

    Greene, D.L.; Leiby, P.N.

    1993-03-01

    The partial monopolization of the world oil market by the OPEC cartel has produced significant economic costs to the economies of the world. This paper reports estimates of the costs of monopolization of oil to the US over the period 1972--1991. Two fundamental assumptions of the analysis are, (1) that OPEC has acted as a monopoly, albeit with limited control, knowledge, and ability to act and, (2) that the US and other consuming nations could, through collective (social) action affect the cartel's ability to act as a monopoly. We measure total costs by comparing actual costs for the 1972--1991 period to a hypothetical more competitive'' world oil market scenario. By measuring past costs we avoid the enormous uncertainties about the future course of the world oil market and leave to the reader's judgment the issue of how much the future will be like the past. We note that total cost numbers cannot be used to determine the value of reducing US oil use by one barrel. They are useful for describing the overall size of the petroleum problem and are one important factor in deciding how much effort should be devoted to solving it. Monopoly pricing of oil transfers wealth from US oil consumers to foreign oil producers and, by increasing theeconomic scarcity of oil, reduces the economy's potential to produce. The actions of the OPEC cartel have also produced oil price shocks, both upward and downward, that generate additional costs because of the economy's inherent inability to adjust quickly to a large change in energy prices. Estimated total costs to the United States from these three sources for the 1972--1991 period are put at $4.1 trillion in 1990$($1.2 T wealth transfer, $0.8 T macroeconomic adjustment costs, $2.1 T potential GNP losses). The cost of the US's primary oil supply contingency program is small ($10 B) by comparison.

  16. Cost-Effective Silicon Wafers for Solar Cells: Direct Wafer Enabling Terawatt Photovoltaics

    SciTech Connect (OSTI)

    2010-01-15

    Broad Funding Opportunity Announcement Project: 1366 is developing a process to reduce the cost of solar electricity by up to 50% by 2020—from $0.15 per kilowatt hour to less than $0.07. 1366’s process avoids the costly step of slicing a large block of silicon crystal into wafers, which turns half the silicon to dust. Instead, the company is producing thin wafers directly from molten silicon at industry-standard sizes, and with efficiencies that compare favorably with today’s state-of-the-art technologies. 1366’s wafers could directly replace wafers currently on the market, so there would be no interruptions to the delivery of these products to market. As a result of 1366’s technology, the cost of silicon wafers could be reduced by 80%.

  17. Smog Check II Evaluation Part IV: Smog Check Costs and

    E-Print Network [OSTI]

    Denver, University of

    Smog Check II Evaluation Part IV: Smog Check Costs and Cost Effectiveness Are the Overall Costs of Smog Check? __________________ 2 2.1. Vehicle Testing Costs____________________________________________ 3 2.2. Repair Costs ___________________________________________________ 5 2.3. Administrative Costs

  18. Onboard Flow Sensing for Downwash Detection and Avoidance with a Small Quadrotor Helicopter

    E-Print Network [OSTI]

    Shapiro, Benjamin

    variations cause unexpected aerodynamic forces through changes in thrust conditions and unmodeled blade input K Control gain J Cost function kJ Optimization weighting variable x, y Quadrotor position

  19. Wind Electrolysis: Hydrogen Cost Optimization

    SciTech Connect (OSTI)

    Saur, G.; Ramsden, T.

    2011-05-01

    This report describes a hydrogen production cost analysis of a collection of optimized central wind based water electrolysis production facilities. The basic modeled wind electrolysis facility includes a number of low temperature electrolyzers and a co-located wind farm encompassing a number of 3MW wind turbines that provide electricity for the electrolyzer units.

  20. Pollution prevention cost savings potential

    SciTech Connect (OSTI)

    Celeste, J.

    1994-12-01

    The waste generated by DOE facilities is a serious problem that significantly impacts current operations, increases future waste management costs, and creates future environmental liabilities. Pollution Prevention (P2) emphasizes source reduction through improved manufacturing and process control technologies. This concept must be incorporated into DOE`s overall operating philosophy and should be an integral part of Total Quality Management (TQM) program. P2 reduces the amount of waste generated, the cost of environmental compliance and future liabilities, waste treatment, and transportation and disposal costs. To be effective, P2 must contribute to the bottom fine in reducing the cost of work performed. P2 activities at LLNL include: researching and developing innovative manufacturing; evaluating new technologies, products, and chemistries; using alternative cleaning and sensor technologies; performing Pollution Prevention Opportunity Assessments (PPOAs); and developing outreach programs with small business. Examples of industrial outreach are: innovative electroplating operations, printed circuit board manufacturing, and painting operations. LLNL can provide the infrastructure and technical expertise to address a wide variety of industrial concerns.

  1. Regulatory cost-risk study

    SciTech Connect (OSTI)

    Not Available

    1983-04-01

    This study is intended to provide some quantitative perspective by selecting certain examples of criteria for which estimates of risks and costs can be obtained, and the balance of the various risks, (i.e., internal versus external risks), can be put into perspective. 35 refs., 39 tabs. (JDB)

  2. Retail Infrastructure Costs Comparison for Hydrogen and Electricity for Light-Duty Vehicles: Preprint

    SciTech Connect (OSTI)

    Melaina, M.; Sun, Y.; Bush, B.

    2014-08-01

    Both hydrogen and plug-in electric vehicles offer significant social benefits to enhance energy security and reduce criteria and greenhouse gas emissions from the transportation sector. However, the rollout of electric vehicle supply equipment (EVSE) and hydrogen retail stations (HRS) requires substantial investments with high risks due to many uncertainties. We compare retail infrastructure costs on a common basis - cost per mile, assuming fueling service to 10% of all light-duty vehicles in a typical 1.5 million person city in 2025. Our analysis considers three HRS sizes, four distinct types of EVSE and two distinct EVSE scenarios. EVSE station costs, including equipment and installation, are assumed to be 15% less than today's costs. We find that levelized retail capital costs per mile are essentially indistinguishable given the uncertainty and variability around input assumptions. Total fuel costs per mile for battery electric vehicle (BEV) and plug-in hybrid vehicle (PHEV) are, respectively, 21% lower and 13% lower than that for hydrogen fuel cell electric vehicle (FCEV) under the home-dominant scenario. Including fuel economies and vehicle costs makes FCEVs and BEVs comparable in terms of costs per mile, and PHEVs are about 10% less than FCEVs and BEVs. To account for geographic variability in energy prices and hydrogen delivery costs, we use the Scenario Evaluation, Regionalization and Analysis (SERA) model and confirm the aforementioned estimate of cost per mile, nationally averaged, but see a 15% variability in regional costs of FCEVs and a 5% variability in regional costs for BEVs.

  3. Offshore Wind Plant Balance-of-Station Cost Drivers and Sensitivities (Poster)

    SciTech Connect (OSTI)

    Saur, G.; Maples, B.; Meadows, B.; Hand, M.; Musial, W.; Elkington, C.; Clayton, J.

    2012-09-01

    With Balance of System (BOS) costs contributing up to 70% of the installed capital cost, it is fundamental to understanding the BOS costs for offshore wind projects as well as potential cost trends for larger offshore turbines. NREL developed a BOS model using project cost estimates developed by GL Garrad Hassan. Aspects of BOS covered include engineering and permitting, ports and staging, transportation and installation, vessels, foundations, and electrical. The data introduce new scaling relationships for each BOS component to estimate cost as a function of turbine parameters and size, project parameters and size, and soil type. Based on the new BOS model, an analysis to understand the non-turbine costs associated with offshore turbine sizes ranging from 3 MW to 6 MW and offshore wind plant sizes ranging from 100 MW to 1000 MW has been conducted. This analysis establishes a more robust baseline cost estimate, identifies the largest cost components of offshore wind project BOS, and explores the sensitivity of the levelized cost of energy to permutations in each BOS cost element. This presentation shows results from the model that illustrates the potential impact of turbine size and project size on the cost of energy from US offshore wind plants.

  4. U.S. Balance-of-Station Cost Drivers and Sensitivities (Presentation)

    SciTech Connect (OSTI)

    Maples, B.

    2012-10-01

    With balance-of-system (BOS) costs contributing up to 70% of the installed capital cost, it is fundamental to understanding the BOS costs for offshore wind projects as well as potential cost trends for larger offshore turbines. NREL developed a BOS model using project cost estimates developed by GL Garrad Hassan. Aspects of BOS covered include engineering and permitting, ports and staging, transportation and installation, vessels, foundations, and electrical. The data introduce new scaling relationships for each BOS component to estimate cost as a function of turbine parameters and size, project parameters and size, and soil type. Based on the new BOS model, an analysis to understand the non?turbine costs has been conducted. This analysis establishes a more robust baseline cost estimate, identifies the largest cost components of offshore wind project BOS, and explores the sensitivity of the levelized cost of energy to permutations in each BOS cost element. This presentation shows results from the model that illustrates the potential impact of turbine size and project size on the cost of energy from U.S. offshore wind plants.

  5. Novel, Low-Cost Nanoparticle Production

    SciTech Connect (OSTI)

    2011-05-31

    Fact sheet describing a modular hybrid plasma reactor and process to manufacture low-cost nanoparticles

  6. Optimal Average Cost Manufacturing Flow Controllers

    E-Print Network [OSTI]

    Veatch, Michael H.

    policy the differ- ential cost is C1 on attractive control switching boundaries. Index Terms Average costOptimal Average Cost Manufacturing Flow Controllers: Convexity and Differentiability Michael H and differentiability of the differential cost function are investigated. It is proven that under an optimal control

  7. COST 227/08 1 European Cooperation

    E-Print Network [OSTI]

    Henderson, Gideon

    COST 227/08 1 DG C II EN European Cooperation in the field of Scientific and Technical Research - COST - -------------------- Secretariat ------- Brussels, 2 July 2008 COST 227/08 MEMORANDUM Action designated as COST Action ES0801: The ocean chemistry of bioactive trace elements and paleoclimate

  8. CPRIT Cost Matching Endorsement Investigator Name

    E-Print Network [OSTI]

    Nicholson, Bruce J.

    CPRIT Cost Matching Endorsement Investigator Name: Department: Project Title: Proposal Deadline regarding demonstration of available funding. To satisfy this cost matching requirement, the university is able to claim unrecovered indirect costs (i.e. the difference between the 5.263% of direct costs

  9. On production costs in vertical differentiation models

    E-Print Network [OSTI]

    Paris-Sud XI, Université de

    EA 4272 On production costs in vertical differentiation models Dorothée BRECARD(*) 2009,version1-1Oct2009 #12;1 On production costs in vertical differentiation models Dorothée Brécard production cost beside a fixed cost of quality improvement in a duopoly model of vertical product

  10. FLORIDA STATE UNIVERSITY Participant Support Costs

    E-Print Network [OSTI]

    Weston, Ken

    FLORIDA STATE UNIVERSITY Policy on Participant Support Costs Effective: May 15, 2006 Purpose costs are separately accounted for, and expended for appropriate and intended objectives. Background in the conference, workshop or training activity. Participant supports costs are defined as direct costs for items

  11. SPONSORSHIP LEVELS GOLF PARTICIPATION

    E-Print Network [OSTI]

    Salvaggio, Carl

    as exemplary and regards RIT as a role model for other organizations. Can you putt? WIN your 2016 entry fee so eld , New York GOLF REGISTRATION SPONSOR REGISTRATION Registration Deadline: September 3, 2015 Standard Cost: Student Cost: $95.00 per person $75.00 per person

  12. The Minimal Work Cost of Information Processing

    E-Print Network [OSTI]

    Philippe Faist; Frédéric Dupuis; Jonathan Oppenheim; Renato Renner

    2015-07-07

    Irreversible information processing cannot be carried out without some inevitable thermodynamical work cost. This fundamental restriction, known as Landauer's principle, is increasingly relevant today, as the energy dissipation of computing devices impedes the development of their performance. Here we determine the minimal work required to carry out any logical process, for instance a computation. It is given by the entropy of the discarded information conditional to the output of the computation. Our formula takes precisely into account the statistically fluctuating work requirement of the logical process. It enables the explicit calculation of practical scenarios, such as computational circuits or quantum measurements. On the conceptual level, our result gives a precise and operationally justified connection between thermodynamic and information entropy, and explains the emergence of the entropy state function in macroscopic thermodynamics.

  13. Hydroblasting permits safe, cost-effective dam rehabilitation

    SciTech Connect (OSTI)

    Lever, G. [Cavi-Tech Inc., Kennesaw, GA (United States)

    1996-04-01

    The cost of using traditional methods to remove lead-based paint from structures subject to strict environmental regulations can be prohibitive, leaving many rehabilitation projects undone. However, alternative methods, including hydroblasting, can reduce debris containment and disposal costs to a tolerable level. This article describes a project which involved the removal of old lead paint and the repainting of a dam situated in a populated recreational area. It details the budgetary, environmental, and public health issues that led to strict specifications and oversight requirements, which saved money and protected the area from lead contamination.

  14. Demand response compensation, net Benefits and cost allocation: comments

    SciTech Connect (OSTI)

    Hogan, William W.

    2010-11-15

    FERC's Supplemental Notice of Public Rulemaking addresses the question of proper compensation for demand response in organized wholesale electricity markets. Assuming that the Commission would proceed with the proposal ''to require tariff provisions allowing demand response resources to participate in wholesale energy markets by reducing consumption of electricity from expected levels in response to price signals, to pay those demand response resources, in all hours, the market price of energy for such reductions,'' the Commission posed questions about applying a net benefits test and rules for cost allocation. This article summarizes critical points and poses implications for the issues of net benefit tests and cost allocation. (author)

  15. Measuring Cost Variability in Provision of Transit Service

    E-Print Network [OSTI]

    Taylor, Brian D.; Garrett, Mark; Iseki, Hiroyuki

    2010-01-01

    include both operating costs and capital costs, though mostof semi?xed operating and capital-cost allocation generallyresearch, both operating and capital costs are combined, and

  16. GM-Ford-Chrysler: ATV Proposed Product Costs | Department of...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ATV Proposed Product Costs GM-Ford-Chrysler: ATV Proposed Product Costs "Proposed Product Cost for Advanced Technology Vehicles" GM-Ford-Chrysler: ATV Proposed Product Costs More...

  17. The cost of silicon nitride powder: What must it be to compete?

    SciTech Connect (OSTI)

    Das, S.; Curlee, T.R.

    1992-02-01

    The ability of advanced ceramic components to compete with similar metallic parts will depend in part on current and future efforts to reduce the cost of ceramic parts. This paper examines the potential reductions in part cost that could result from the development of less expensive advanced ceramic powders. The analysis focuses specifically on two silicon nitride engine components -- roller followers and turbocharger rotors. The results of the process-cost models developed for this work suggest that reductions in the cost of advanced silicon nitride powder from its current level of about $20 per pound to about $5 per pound will not in itself be sufficient to lower the cost of ceramic parts below the current cost of similar metallic components. This work also examines if combinations of lower-cost powders and further improvements in other key technical parameters to which costs are most sensitive could push the cost of ceramics below the cost of metallics. Although these sensitivity analyses are reflective of technical improvements that are very optimistic, the resulting part costs are estimated to remain higher than similar metallic parts. Our findings call into question the widely-held notion that the cost of ceramic components must not exceed the cost of similar metallic parts if ceramics are to be competitive. Economic viability will ultimately be decided not on the basis of which part is less costly, but on an assessment of the marginal costs and benefits provided by ceramics and metallics. This analysis does not consider the benefits side of the equation. Our findings on the cost side of the equation suggest that the competitiveness of advanced ceramics will ultimately be decided by our ability to evaluate and communicate the higher benefits that advanced ceramic parts may offer.

  18. The cost of silicon nitride powder: What must it be to compete

    SciTech Connect (OSTI)

    Das, S.; Curlee, T.R.

    1992-02-01

    The ability of advanced ceramic components to compete with similar metallic parts will depend in part on current and future efforts to reduce the cost of ceramic parts. This paper examines the potential reductions in part cost that could result from the development of less expensive advanced ceramic powders. The analysis focuses specifically on two silicon nitride engine components -- roller followers and turbocharger rotors. The results of the process-cost models developed for this work suggest that reductions in the cost of advanced silicon nitride powder from its current level of about $20 per pound to about $5 per pound will not in itself be sufficient to lower the cost of ceramic parts below the current cost of similar metallic components. This work also examines if combinations of lower-cost powders and further improvements in other key technical parameters to which costs are most sensitive could push the cost of ceramics below the cost of metallics. Although these sensitivity analyses are reflective of technical improvements that are very optimistic, the resulting part costs are estimated to remain higher than similar metallic parts. Our findings call into question the widely-held notion that the cost of ceramic components must not exceed the cost of similar metallic parts if ceramics are to be competitive. Economic viability will ultimately be decided not on the basis of which part is less costly, but on an assessment of the marginal costs and benefits provided by ceramics and metallics. This analysis does not consider the benefits side of the equation. Our findings on the cost side of the equation suggest that the competitiveness of advanced ceramics will ultimately be decided by our ability to evaluate and communicate the higher benefits that advanced ceramic parts may offer.

  19. ECONOMIC AND FINANCIAL ANALYSIS OF INCREASING COSTS IN THE GULF SHRIMP FLEETI,2

    E-Print Network [OSTI]

    of construction, length ofkeel, and index ofeffort. In 1973, class II vessels were the only vessels ableECONOMIC AND FINANCIAL ANALYSIS OF INCREASING COSTS IN THE GULF SHRIMP FLEETI,2 WADE L. GRi flow for 1974. Increasing input cost another 10% above the 1974 level, and assuming normal production

  20. A Novel Low Cost Solar Central Inverters Topology With 99.2 % Efficiency Heiko Preckwinkel and

    E-Print Network [OSTI]

    Noé, Reinhold

    A Novel Low Cost Solar Central Inverters Topology With 99.2 % Efficiency Heiko Preckwinkel IGBT-based 3-level modules are limited to about 300- 600 A nominal current. A Novel Low Cost Solar)», «Transformer», Abstract For solar central inverters, high efficiency is still a very important issue

  1. COST ACCOUNTING IN US CITIES: TRANSACTION COSTS AND GOVERNANCE FACTORS AFFECTING COST ACCOUNTING DEVELOPMENT AND USE

    E-Print Network [OSTI]

    Mohr, Zachary Thomas

    2013-05-31

    Cost accounting in government is a topic that has an oddly uncertain place in public financial management. Many people know what it is as an ideal construct but do not know what it is in practice. This uncertainty of practice and strong expectations...

  2. Ocean Thermal Energy Conversion Life Cycle Cost Assessment, Final Technical Report, 30 May 2012

    SciTech Connect (OSTI)

    Martel, Laura; Smith, Paul; Rizea, Steven; Van Ryzin, Joe; Morgan, Charles; Noland, Gary; Pavlosky, Rick; Thomas, Michael

    2012-06-30

    The Ocean Thermal Energy Conversion (OTEC) Life Cycle Cost Assessment (OLCCA) is a study performed by members of the Lockheed Martin (LM) OTEC Team under funding from the Department of Energy (DOE), Award No. DE-EE0002663, dated 01/01/2010. OLCCA objectives are to estimate procurement, operations and maintenance, and overhaul costs for two types of OTEC plants: -Plants moored to the sea floor where the electricity produced by the OTEC plant is directly connected to the grid ashore via a marine power cable (Grid Connected OTEC plants) -Open-ocean grazing OTEC plant-ships producing an energy carrier that is transported to designated ports (Energy Carrier OTEC plants) Costs are developed using the concept of levelized cost of energy established by DOE for use in comparing electricity costs from various generating systems. One area of system costs that had not been developed in detail prior to this analysis was the operations and sustainment (O&S) cost for both types of OTEC plants. Procurement costs, generally referred to as capital expense and O&S costs (operations and maintenance (O&M) costs plus overhaul and replacement costs), are assessed over the 30 year operational life of the plants and an annual annuity calculated to achieve a levelized cost (constant across entire plant life). Dividing this levelized cost by the average annual energy production results in a levelized cost of electricity, or LCOE, for the OTEC plants. Technical and production efficiency enhancements that could result in a lower value of the OTEC LCOE were also explored. The thermal OTEC resource for Oahu, Hawai�¢����i and projected build out plan were developed. The estimate of the OTEC resource and LCOE values for the planned OTEC systems enable this information to be displayed as energy supplied versus levelized cost of the supplied energy; this curve is referred to as an Energy Supply Curve. The Oahu Energy Supply Curve represents initial OTEC deployment starting in 2018 and demonstrates the predicted economies of scale as technology and efficiency improvements are realized and larger more economical plants deployed. Utilizing global high resolution OTEC resource assessment from the Ocean Thermal Extractable Energy Visualization (OTEEV) project (an independent DOE project), Global Energy Supply Curves were generated for Grid Connected and Energy Carrier OTEC plants deployed in 2045 when the predicted technology and efficiencies improvements are fully realized. The Global Energy Supply Curves present the LCOE versus capacity in ascending order with the richest, lowest cost resource locations being harvested first. These curves demonstrate the vast ocean thermal resource and potential OTEC capacity that can be harvested with little change in LCOE.

  3. Low cost multi-channel GPS receiver 

    E-Print Network [OSTI]

    Painter, John H.; Tachita, R.; Ikeda, K.; Teranishi, A.; Noe, P.S.

    1988-11-29

    An investigation was conducted on compact, multichannel GPS (global positioning system) receivers. The code generator and correlation equipment were simplified, attempting to avoid downgrading the properties possessed by multichannel receivers...

  4. Supplemental report on cost estimates'

    SciTech Connect (OSTI)

    NONE

    1992-04-29

    The Office of Management and Budget (OMB) and the U.S. Army Corps of Engineers have completed an analysis of the Department of Energy's (DOE) Fiscal Year (FY) 1993 budget request for its Environmental Restoration and Waste Management (ERWM) program. The results were presented to an interagency review group (IAG) of senior-Administration officials for their consideration in the budget process. This analysis included evaluations of the underlying legal requirements and cost estimates on which the ERWM budget request was based. The major conclusions are contained in a separate report entitled, ''Interagency Review of the Department of Energy Environmental Restoration and Waste Management Program.'' This Corps supplemental report provides greater detail on the cost analysis.

  5. Entanglement Cost of Nonlocal Measurements

    E-Print Network [OSTI]

    Somshubhro Bandyopadhyay; Gilles Brassard; Shelby Kimmel; William K. Wootters

    2009-03-30

    For certain joint measurements on a pair of spatially separated particles, we ask how much entanglement is needed to carry out the measurement exactly. For a class of orthogonal measurements on two qubits with partially entangled eigenstates, we present upper and lower bounds on the entanglement cost. The upper bound is based on a recent result by D. Berry [Phys. Rev. A 75, 032349 (2007)]. The lower bound, based on the entanglement production capacity of the measurement, implies that for almost all measurements in the class we consider, the entanglement required to perform the measurement is strictly greater than the average entanglement of its eigenstates. On the other hand, we show that for any complete measurement in d x d dimensions that is invariant under all local Pauli operations, the cost of the measurement is exactly equal to the average entanglement of the states associated with the outcomes.

  6. Entanglement Cost of Quantum Channels

    E-Print Network [OSTI]

    Mario Berta; Fernando Brandao; Matthias Christandl; Stephanie Wehner

    2012-03-23

    The entanglement cost of a quantum channel is the minimal rate at which entanglement (between sender and receiver) is needed in order to simulate many copies of a quantum channel in the presence of free classical communication. In this paper we show how to express this quantity as a regularized optimization of the entanglement formation over states that can be generated between sender and receiver. Our formula is the channel analog of a well-known formula for the entanglement cost of quantum states in terms of the entanglement of formation; and shares a similar relation to the recently shattered hope for additivity. The entanglement cost of a quantum channel can be seen as the analog of the quantum reverse Shannon theorem in the case where free classical communication is allowed. The techniques used in the proof of our result are then also inspired by a recent proof of the quantum reverse Shannon theorem and feature the one-shot formalism for quantum information theory, the post-selection technique for quantum channels as well as von Neumann's minimax theorem. We discuss two applications of our result. First, we are able to link the security in the noisy-storage model to a problem of sending quantum rather than classical information through the adversary's storage device. This not only improves the range of parameters where security can be shown, but also allows us to prove security for storage devices for which no results were known before. Second, our result has consequences for the study of the strong converse quantum capacity. Here, we show that any coding scheme that sends quantum information through a quantum channel at a rate larger than the entanglement cost of the channel has an exponentially small fidelity.

  7. Entanglement Cost of Quantum Channels

    E-Print Network [OSTI]

    Mario Berta; Fernando Brandao; Matthias Christandl; Stephanie Wehner

    2015-11-02

    The entanglement cost of a quantum channel is the minimal rate at which entanglement (between sender and receiver) is needed in order to simulate many copies of a quantum channel in the presence of free classical communication. In this paper we show how to express this quantity as a regularised optimisation of the entanglement formation over states that can be generated between sender and receiver. Our formula is the channel analog of a well-known formula for the entanglement cost of quantum states in terms of the entanglement of formation; and shares a similar relation to the recently shattered hope for additivity. The entanglement cost of a quantum channel can be seen as the analog of the quantum reverse Shannon theorem in the case where free classical communication is allowed. The techniques used in the proof of our result are then also inspired by a recent proof of the quantum reverse Shannon theorem and feature the one-shot formalism for quantum information theory, the post-selection technique for quantum channels as well as Sion's minimax theorem. We discuss two applications of our result. First, we are able to link the security in the noisy-storage model to a problem of sending quantum rather than classical information through the adversary's storage device. This not only improves the range of parameters where security can be shown, but also allows us to prove security for storage devices for which no results were known before. Second, our result has consequences for the study of the strong converse quantum capacity. Here, we show that any coding scheme that sends quantum information through a quantum channel at a rate larger than the entanglement cost of the channel has an exponentially small fidelity.

  8. 5. ESTIMATING THE COSTS OF DIGITAL PRESERVATION 5.1 Isolating a `preservation cost'

    E-Print Network [OSTI]

    Carr, Leslie

    44 5. ESTIMATING THE COSTS OF DIGITAL PRESERVATION 5.1 Isolating a `preservation cost' Deciding preservation is--how much will it cost? One of the problems encountered in trying to answer this question costs do relate specifically to preservation, but this does not mean that those are the only costs

  9. INDIRECT COST CALCULATION [IN REVERSE] YOU WANT TO CALCULATE THE DIRECT COSTS

    E-Print Network [OSTI]

    Finley Jr., Russell L.

    INDIRECT COST CALCULATION [IN REVERSE] YOU WANT TO CALCULATE THE DIRECT COSTS YOU KNOW WHAT THE TUITION, STIPEND AND EQUIPMENT COSTS ARE YOU KNOW WHAT THE TOTAL COST IS CALCULATION IS USING THE 2010 FED F&A RATE FOR WSU OF 52% (.52) [ DIRECT COST ­ TUITION ­ STIPEND ­ EQUIPMENT] (.52 ) + DIRECT

  10. Federal Indirect Costs Program Definition of the indirect costs of research

    E-Print Network [OSTI]

    Doedel, Eusebius

    Federal Indirect Costs Program Definition of the indirect costs of research Concordia University defines "Indirect Costs" as costs which cannot be associated specifically with a particular research program or other activity. Indirect costs include the provision and maintenance of physical space

  11. Pre-Award Costs Pre-award costs are incurred at the risk of the University.

    E-Print Network [OSTI]

    Hammack, Richard

    Pre-Award Costs Pre-award costs are incurred at the risk of the University. The principal supply an alternate index number to charge in the event the project is not funded. Note: Pre-award costs are costs incurred prior to the beginning date of a budget period. Pre-award cost incurred more than 90 days

  12. Biodiesel: Cost and reactant comparison 1 Biodiesel: Cost and reactant comparison

    E-Print Network [OSTI]

    and reactant comparison 2 Questions and Hypotheses Question 1 Can we make biodiesel at a lower cost than at a lower cost than buying fuel at a gas station. ii. Alternative hypothesis: Buying fuel at the pump costsBiodiesel: Cost and reactant comparison 1 Biodiesel: Cost and reactant comparison Burke Anderson

  13. A faster implementation of the pivot algorithm for self-avoiding walks

    E-Print Network [OSTI]

    Tom Kennedy

    2001-09-17

    The pivot algorithm is a Markov Chain Monte Carlo algorithm for simulating the self-avoiding walk. At each iteration a pivot which produces a global change in the walk is proposed. If the resulting walk is self-avoiding, the new walk is accepted; otherwise, it is rejected. Past implementations of the algorithm required a time O(N) per accepted pivot, where N is the number of steps in the walk. We show how to implement the algorithm so that the time required per accepted pivot is O(N^q) with q<1. We estimate that q is less than 0.57 in two dimensions, and less than 0.85 in three dimensions. Corrections to the O(N^q) make an accurate estimate of q impossible. They also imply that the asymptotic behavior of O(N^q) cannot be seen for walk lengths which can be simulated. In simulations the effective q is around 0.7 in two dimensions and 0.9 in three dimensions. Comparisons with simulations that use the standard implementation of the pivot algorithm using a hash table indicate that our implementation is faster by as much as a factor of 80 in two dimensions and as much as a factor of 7 in three dimensions. Our method does not require the use of a hash table and should also be applicable to the pivot algorithm for off-lattice models.

  14. Incorporating psychological influences in probabilistic cost analysis

    SciTech Connect (OSTI)

    Kujawski, Edouard; Alvaro, Mariana; Edwards, William

    2004-01-08

    Today's typical probabilistic cost analysis assumes an ''ideal'' project that is devoid of the human and organizational considerations that heavily influence the success and cost of real-world projects. In the real world ''Money Allocated Is Money Spent'' (MAIMS principle); cost underruns are rarely available to protect against cost overruns while task overruns are passed on to the total project cost. Realistic cost estimates therefore require a modified probabilistic cost analysis that simultaneously models the cost management strategy including budget allocation. Psychological influences such as overconfidence in assessing uncertainties and dependencies among cost elements and risks are other important considerations that are generally not addressed. It should then be no surprise that actual project costs often exceed the initial estimates and are delivered late and/or with a reduced scope. This paper presents a practical probabilistic cost analysis model that incorporates recent findings in human behavior and judgment under uncertainty, dependencies among cost elements, the MAIMS principle, and project management practices. Uncertain cost elements are elicited from experts using the direct fractile assessment method and fitted with three-parameter Weibull distributions. The full correlation matrix is specified in terms of two parameters that characterize correlations among cost elements in the same and in different subsystems. The analysis is readily implemented using standard Monte Carlo simulation tools such as {at}Risk and Crystal Ball{reg_sign}. The analysis of a representative design and engineering project substantiates that today's typical probabilistic cost analysis is likely to severely underestimate project cost for probability of success values of importance to contractors and procuring activities. The proposed approach provides a framework for developing a viable cost management strategy for allocating baseline budgets and contingencies. Given the scope and magnitude of the cost-overrun problem, the benefits are likely to be significant.

  15. PROJECT PROFILE: High-Efficiency, Low-Cost, One-Sun, III-V Photovoltaics

    Broader source: Energy.gov [DOE]

    Low-cost III-V photovoltaics have the potential to lower the levelized cost of energy (LCOE) because III-V cells outperform silicon in terms of efficiency and annual energy harvesting efficiency. In this project, researchers will address both the high costs of III-V epitaxy and single crystal substrates. Hydride vapor phase epitaxy (HVPE) is the most promising inexpensive, rapid-growth technique for high efficiency, III-V materials. The continued development of high-throughput HVPE, will be coupled with novel epitaxial liftoff strategies to enable III-V solar cells that are cost-competitive under one-sun conditions.

  16. Carbon mitigation potential and costs of forestry options in Brazil, China, India, Indonesia, Mexico, the Philippines and Tanzania

    SciTech Connect (OSTI)

    Sathaye, J.; Makundi, W.; Andrasko, K.; Boer, R.; Ravindranath, N.; Sudha, P.; Rao, S.; Lasco, R.; Pulhin, F.; Masera, O.; Ceron, A.; Ordonez, J.; Deying, X.; Zhang, X.; Zuomin, S.

    2001-01-01

    This paper summarizes studies of carbon (C) mitigation potential and costs of about 40 forestry options in seven developing countries. Each study uses the same methodological approach - Comprehensive Mitigation Assessment Process (COMAP) - to estimate the above parameters between 2000 and 2030. The approach requires the projection of baseline and mitigation land-use scenarios. Coupled with data on a per ha basis on C sequestration or avoidance, and costs and benefits, it allows the estimation of monetary benefit per Mg C, and the total costs and carbon potential. The results show that about half (3.0 Pg C) the cumulative mitigation potential of 6.2 Petagram (Pg) C between 2000 and 2030 in the seven countries (about 200 x 106 Mg C yr-1) could be achieved at a negative cost and the remainder at costs ranging up to $100 Mg C-1. About 5 Pg C could be achieved, at a cost less than $20 per Mg C. Negative cost potential indicates that non-carbon revenue is sufficient to offset direct costs of these options. The achievable potential is likely to be smaller, however, due to market, institutional, and sociocultural barriers that can delay or prevent the implementation of the analyzed options.

  17. CBE UFAD cost analysis tool: Life cycle cost model, issues and assumptions

    E-Print Network [OSTI]

    Webster, Tom; Benedek, Corinne; Bauman, Fred

    2008-01-01

    Building Maintenance and Repair Cost Reference. ” WhitestoneJ. Wallis and H. Lin. 2008. “CBE UFAD Cost Analysis Tool:UFAD First Cost Model, Issues and Assumptions. ” Center for

  18. NWEC Comments: Environmental Costs and Benefits 1 Methodology for Determining Quantifiable Environmental Costs

    E-Print Network [OSTI]

    NWEC Comments: Environmental Costs and Benefits 1 Methodology for Determining Quantifiable Environmental Costs and Benefits Comments of the NW Energy Coalition October 31, 2014 Introduction: Applying (Council) to include a methodology for determining quantifiable environmental costs and benefits in its

  19. Melanoma costs: A dynamic model comparing estimated overall costs of various clinical stages

    E-Print Network [OSTI]

    Alexandrescu, Doru Traian

    2009-01-01

    AL. Trends in treatment costs for localized prostate cancer:R, Elkin EP, et al. Cumulative cost pattern comparison ofAn estimate of the annual direct cost of treating cutaneous

  20. Determining benefits and costs of improved central air conditioner efficiencies

    E-Print Network [OSTI]

    Rosenquist, G.

    2010-01-01

    calculation include the installed consumer cost (purchase price plus installation cost), operating expenses (energy and