Powered by Deep Web Technologies
Note: This page contains sample records for the topic "average installed capital" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


1

Advances in Energy Efficiency, Capital Cost, and Installation Schedules for Large Capacity Cooling Applications Using a Packaged Chiller Plant Approach  

E-Print Network [OSTI]

reductions in unit capital costs of installed chiller plant capacity on a dollar per ton basis, 2) marked improvements in total procurement and installation schedules, 3) significantly smaller space requirements, and 4) enhanced control over total system...

Pierson, T. L.; Andrepont, J. S.

2

Cost of a Ride: The Effects of Densities on Fixed-Guideway Transit Ridership and Capital Costs  

E-Print Network [OSTI]

transit – exceeded capital cost estimates by 40% duringfound that capital costs exceeded estimates by an averagesystems. We estimate the total capital cost, average weekday

Guerra, Erick; Cervero, Robert

2010-01-01T23:59:59.000Z

3

Transmission line capital costs  

SciTech Connect (OSTI)

The displacement or deferral of conventional AC transmission line installation is a key benefit associated with several technologies being developed with the support of the U.S. Department of Energy`s Office of Energy Management (OEM). Previous benefits assessments conducted within OEM have been based on significantly different assumptions for the average cost per mile of AC transmission line. In response to this uncertainty, an investigation of transmission line capital cost data was initiated. The objective of this study was to develop a database for preparing preliminary estimates of transmission line costs. An extensive search of potential data sources identified databases maintained by the Bonneville Power Administration (BPA) and the Western Area Power Administration (WAPA) as superior sources of transmission line cost data. The BPA and WAPA data were adjusted to a common basis and combined together. The composite database covers voltage levels from 13.8 to 765 W, with cost estimates for a given voltage level varying depending on conductor size, tower material type, tower frame type, and number of circuits. Reported transmission line costs vary significantly, even for a given voltage level. This can usually be explained by variation in the design factors noted above and variation in environmental and land (right-of-way) costs, which are extremely site-specific. Cost estimates prepared from the composite database were compared to cost data collected by the Federal Energy Regulatory Commission (FERC) for investor-owned utilities from across the United States. The comparison was hampered because the only design specifications included with the FERC data were voltage level and line length. Working within this limitation, the FERC data were not found to differ significantly from the composite database. Therefore, the composite database was judged to be a reasonable proxy for estimating national average costs.

Hughes, K.R.; Brown, D.R.

1995-05-01T23:59:59.000Z

4

2011 Strategic Capital Discussions  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Agenda Letter announcing September 2011 Strategic Discussions Fact Sheet Capital Follow Ups Background Information September 19th Overview Power Capital Transmission Capital...

5

CAPITAL REGION  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE:YearRound-Up fromDepartmentTie Ltd:June 2015 < prevBuildingBusinessC/OSectionCAP ProgramCAPITAL

6

North Carolina Capital Access Program (North Carolina)  

Broader source: Energy.gov [DOE]

The North Carolina Capital Access Program provides matching reserve funds for business loans that are beyond the traditional lending means of a lender’s usual standards. The average CAP loan is ...

7

Networks, Information & Social Capital  

E-Print Network [OSTI]

This paper investigates how information flows enable social networks to constitute social capital. By analyzing

Aral, Sinan

2008-01-26T23:59:59.000Z

8

Venture Capital Finance  

Broader source: Energy.gov [DOE]

Plenary III: Project Finance and Investment Venture Capital Finance Brian Baynes, Partner, Flagship Ventures

9

Developer Installed Treatment Plants  

E-Print Network [OSTI]

-installed treatment plants. These treatment plants are more commonly known as package wastewater treatment plants. 1

unknown authors

2008-01-01T23:59:59.000Z

10

Installation and Acceptance Stage  

Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

This chapter addresses activities required to install the software, data bases, or data that comprise the software product onto the hardware platform at sites of operation.

1997-05-21T23:59:59.000Z

11

Health Capital and Finance  

E-Print Network [OSTI]

Capital and Finance by Sara Bryant Holland A dissertationCopyright 2010 by Sara Bryant Holland Abstract Healthand Finance by Sara Bryant Holland Doctor of Philosophy in

Holland, Sara Bryant

2010-01-01T23:59:59.000Z

12

Capital Access Program (Vermont)  

Broader source: Energy.gov [DOE]

The Capital Access Program provides loan guarantees to small businesses seeking access to commercial credit. Premiums paid by the borrower and matched by Vermont Economic Development Authority fund...

13

Client Configuration and Installation  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Instructions below. In certain environments (e.g., if your installation is on a machine which has more than one network interface or has a high bandwidth network connection...

14

HVAC Installed Performance  

Broader source: Energy.gov [DOE]

This presentation was given at the Summer 2012 DOE Building America meeting on July 25, 2012, and addressed the question ŤHVAC proper installation energy savings: over-promising or under-delivering?"

15

Capital Access Program (CAP) (Michigan)  

Broader source: Energy.gov [DOE]

The Capital Access Program (CAP), utilizes public resources to generate private financing for small business in Michigan seeking access to capital. Funding from the Michigan Strategic Fund is...

16

Pennsylvania Capital Access Program (Pennsylvania)  

Broader source: Energy.gov [DOE]

The Pennsylvania Capital Access Program provides loan guarantees for all businesses for the purchase of land, buildings, machinery, equipment and working capital through participating banks. The...

17

Virginia Capital Access Program (Virginia)  

Broader source: Energy.gov [DOE]

The Virginia Capital Access Program (CAP), in partnership with Virginia’s Small Business Financing Authority, provides access to capital for small businesses. Businesses must apply to...

18

Essays in capital markets  

E-Print Network [OSTI]

This thesis consists of three essays in capital markets. The first essay presents a dynamic asset pricing model with heterogeneously informed agents. Unlike previous research, the general case where differential information ...

Makarov, Igor, 1976-

2006-01-01T23:59:59.000Z

19

Flexible Capital Fund (Vermont)  

Broader source: Energy.gov [DOE]

The Vermont Sustainable Jobs Fund's Flexible Capital Fund (the “Flex Fund”) is designed for companies in Vermont's rural areas that are smaller and work on a less-than global scale, offering a...

20

Texas Capital Fund (Texas)  

Broader source: Energy.gov [DOE]

The Texas Capital Fund is designed to promote growth in rural non-entitlement areas, generally defined as cities with less than 50,000 residents or counties with less than 200,000 residents....

Note: This page contains sample records for the topic "average installed capital" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


21

Capital Projects Delivery Procedures Manual  

E-Print Network [OSTI]

1 Capital Projects Delivery Procedures Manual September 4, 2008 Office of the CFO #12;2 Page I of the Capital Budget 11 B. Budget Approval 12 C. Setting Up Capital Projects 13 III. Procedures for Design ­ Office of the Chief Financial Officer Financial Policies and Procedures for the Capital Project Delivery

Alpay, S. Pamir

22

VAX/ASPEN installation guide  

SciTech Connect (OSTI)

Information necessary to install the ASPEN computerized simulation program on the VAX system is provided.

Williams, K.E.

1984-11-01T23:59:59.000Z

23

Innovation and Social Capital in Silicon Valley  

E-Print Network [OSTI]

Innovation and Social Capital in Silicon Valley * BRIEpath from social capital to innovation has been identified.social capital has for economic development and innovation.

Kenney, Martin; Patton, Donald

2003-01-01T23:59:59.000Z

24

Vermont Seed Capital Fund (Vermont)  

Broader source: Energy.gov [DOE]

The Vermont Seed Capital Fund increases the amount of investment capital available to new Vermont firms or to existing Vermont firms for the purpose of expansion. The first $5 million of...

25

Capital and revenue expenditures  

E-Print Network [OSTI]

T and Charaoteristios of Various Expenditures ~ ~ 7 III. Bases for Expenditure Classifioationi ~ ~ ~ ~ ~ ~ ~ ~ r ~ ' ~ IV ~ Methods of kooountiag for Capital and Revenue Expenditure( ~ ~ I CkPITLL ERE RKVRRUm bXPLM)ITURkiS ISTRORUGTIOR kn ?ttonpt will be made... not tahe tho plass of asy asset or part of aa asset already onistiag Ln a business, but give tho already sainting fined asset ealues an a44ed physioal value whioh they did not previously possess ~ Additions rosoable original oost in that both...

Owens, Jack Bailey

1948-01-01T23:59:59.000Z

26

Tracking the Sun III; The Installed Cost of Photovoltaics in the United States from 1998-2009  

E-Print Network [OSTI]

Investigation of Photovoltaic Cost Trends in California.photovoltaic (PV) systems has increased, so too has the desire to track the installed costPhotovoltaic Power Systems. Figure 13. Comparison of Average Installed Costs (

Barbose, Galen

2011-01-01T23:59:59.000Z

27

QGESS: Capital Cost Scaling Methodology  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

(costs and values of inputs, outputs, and processes, including capital and operating costs) and performance (mass conversion, energy efficiency, and, generally speaking,...

28

Florida Venture Capital Program (Florida)  

Broader source: Energy.gov [DOE]

The Florida Venture Capital Program provides equity investments and convertible debt instruments to emerging Florida companies and companies locating in Florida with long-term growth potential. ...

29

Human Capital Management Accountability Program  

Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

The Order establishes requirements, roles and responsibilities for the Human Capital Management Accountability Program (HCMAP) for human resources programs and personnel and ensures that human capital activities are regulatory and procedurally compliant with Federal statutes and Departmental policies. Does not cancel other directives.

2008-08-01T23:59:59.000Z

30

West Virginia Venture Capital (West Virginia)  

Broader source: Energy.gov [DOE]

The West Virginia Venture Capital provides investment funds to eligible businesses stimulating economic growth and providing or retaining jobs within the state through qualified venture capital...

31

Quick Estimate of IRR From Capital Estimate Ratios  

E-Print Network [OSTI]

assumptions, as A useful factor can be calculated from the Net Present Values calculated above. The ratio of the Net Present Values gives the so call "Investment Equivalent of a unit of Savings," thus: $2332/$821 = $2.84 Capital/$l of Revenue...(Saving) If 15% (the assumption for discount rate, see Table I) is the minimum acceptable average earnings rate ("Hurdle rate") for a company, then the Investment Equivalent calculated above can be interpreted to mean: "The maximum among or Capital...

Larson, R. J.

32

Magnet Girder Assembly and Installation  

ScienceCinema (OSTI)

It takes teamwork to assemble and install magnet girders for the storage ring of the National Synchrotron Light Source II. NSLS-II is now under construction at Brookhaven Lab.

None

2013-07-17T23:59:59.000Z

33

Solar Installation Labor Market Analysis  

SciTech Connect (OSTI)

The potential economic benefits of the growing renewable energy sector have led to increased federal, state, and local investments in solar industries, including federal grants for expanded workforce training for U.S. solar installers. However, there remain gaps in the data required to understand the size and composition of the workforce needed to meet the demand for solar power. Through primary research on the U.S. solar installation employer base, this report seeks to address that gap, improving policymakers and other solar stakeholders understanding of both the evolving needs of these employers and the economic opportunity associated with solar market development. Included are labor market data covering current U.S. employment, expected industry growth, and employer skill preferences for solar installation-related occupations. This study offers an in-depth look at the solar installation sectors. A study published by the Solar Foundation in October 2011 provides a census of labor data across the entire solar value chain.

Friedman, B.; Jordan, P.; Carrese, J.

2011-12-01T23:59:59.000Z

34

Magnet Girder Assembly and Installation  

SciTech Connect (OSTI)

It takes teamwork to assemble and install magnet girders for the storage ring of the National Synchrotron Light Source II. NSLS-II is now under construction at Brookhaven Lab.

None

2012-12-12T23:59:59.000Z

35

Net Zero Energy Installations (Presentation)  

SciTech Connect (OSTI)

A net zero energy installation (NZEI) is one that produces as much energy from on-site renewable sources as it consumes. NZEI assessment provides a systematic approach to energy projects.

Booth, S.

2012-05-01T23:59:59.000Z

36

Data Mining using Python --exercises for installation  

E-Print Network [OSTI]

ipython (e.g., by pip) Start with: ipython -pylab Once installed make sure you can write: In [1]: plot for installation Install IPython Notebook Check that you can run a IPython Notebook file. Test that the IPython

37

Nonlinear Capital Taxation Without Commitment  

E-Print Network [OSTI]

We study efficient non-linear taxation of labour and capital in a dynamic Mirrleesian model incorporating political economy constraints. Policies are chosen sequentially over time, without commitment. Our main result is ...

Werning, Ivan

38

Venture Capital Program (North Dakota)  

Broader source: Energy.gov [DOE]

The Venture Capital Program, provided by the ND Department of Commerce, is an innovative financial program that provides flexible financing through debt and equity investments for new or expanding...

39

Florida Capital Access Program (Florida)  

Broader source: Energy.gov [DOE]

The Florida Capital Access Program, run by the Florida Department of Economic Development, is a loan portfolio insurance program enabling lenders to make loans to credit-worthy small businesses. ...

40

Capital Investment Tax Credit (Florida)  

Broader source: Energy.gov [DOE]

The Capital Investment Tax Credit is an annual credit, provided for up to twenty years, against the corporate income tax. Eligible projects are those in designated high-impact portions of the...

Note: This page contains sample records for the topic "average installed capital" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


41

Social Capital and Growth Bryan R. Routledge ,  

E-Print Network [OSTI]

, labor mobility, and social capital. The key assumption is that technological innovation, which drivesSocial Capital and Growth Bryan R. Routledge , Joachim von Amsberg § March 2002 Revised July 2002 Abstract We define and characterize social capital in a simple growth model. We capture social capital

42

2014 State Capital Request Board of Regents  

E-Print Network [OSTI]

on FY 2015 capital budget Financial Summary Request dollars in thousands Location Project Total State U

Weiblen, George D

43

Facebook Applications' Installation and Removal: A Temporal Analysis  

E-Print Network [OSTI]

Facebook applications are one of the reasons for Facebook attractiveness. Unfortunately, numerous users are not aware of the fact that many malicious Facebook applications exist. To educate users, to raise users' awareness and to improve Facebook users' security and privacy, we developed a Firefox add-on that alerts users to the number of installed applications on their Facebook profiles. In this study, we present the temporal analysis of the Facebook applications' installation and removal dataset collected by our add-on. This dataset consists of information from 2,945 users, collected during a period of over a year. We used linear regression to analyze our dataset and discovered the linear connection between the average percentage change of newly installed Facebook applications and the number of days passed since the user initially installed our add-on. Additionally, we found out that users who used our Firefox add-on become more aware of their security and privacy installing on average fewer new application...

Kagan, Dima; Elyashar, Aviad; Elovici, Yuval

2013-01-01T23:59:59.000Z

44

Installation  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr MayAtmospheric Optical Depth7-1D: Vegetation ProposedUsingFunInfrared Land Surface Emissivity inFermilabWhich1the research community

45

STATE OF CALIFORNIA INSTALLATION CERTIFICATE  

E-Print Network [OSTI]

ENERGY COMMISSION INSTALLATION CERTIFICATE CF-6R-MECH-25-HERS Refrigerant Charge Verification ­ Standard to refrigerant charge verification for compliance, a MECH-24 Certificate (instead of this MECH-25 Certificate) should be used to demonstrate compliance with the refrigerant charge verification requirement. TMAH

46

STATE OF CALIFORNIA INSTALLATION CERTIFICATE  

E-Print Network [OSTI]

ENERGY COMMISSION INSTALLATION CERTIFICATE CF-6R-MECH-26-HERS Refrigerant Charge Verification ­ Alternate are specified in Reference Residential Appendix RA3.2. If refrigerant charge verification is requiredR-MECH-26-HERS Refrigerant Charge Verification ­ Alternate Measurement Procedure (Page 2 of 3) Site

47

Process Improvement at Army Installations  

E-Print Network [OSTI]

recommendations are for the Fill and Press line where most of the Level I focused LESSONS LEARNED On completion of the project, the researchers assessed the results and some of the 198 ESL-IE-97-04-31 Proceedings from the Nineteenth Industrial Energy.... Finally, the energy issues included initiate an energy team; install energy efficient lighting; and decommission unused steam lines. After the first cost, savings, and simple payback time was calculated for all of the proposed improvements, a...

Northrup, J.; Smith, E. D.; Lin, M.; Baird, J.

48

Averaging Hypotheses in Newtonian Cosmology  

E-Print Network [OSTI]

Average properties of general inhomogeneous cosmological models are discussed in the Newtonian framework. It is shown under which circumstances the average flow reduces to a member of the standard Friedmann--Lema\\^\\i tre cosmologies. Possible choices of global boundary conditions of inhomogeneous cosmologies as well as consequences for the interpretation of cosmological parameters are put into perspective.

T. Buchert

1995-12-20T23:59:59.000Z

49

Essays on information technology and intangible capital  

E-Print Network [OSTI]

This thesis consists of three essays related to information technology and intangible capital. The first essay, "Valuing IT-Related Intangible Capital," examines the value of intangible assets in the firm. Using a panel ...

Saunders, Adam

2011-01-01T23:59:59.000Z

50

Fixed Capital Investment Tax Credit (Connecticut)  

Broader source: Energy.gov [DOE]

The Fixed Capital Investment Tax Credit allows a tax credit of 5% of the amount paid for any new fixed capital investment. Companies with fewer than 800 full-time employees may take a tax credit...

51

Public Capital, Growth and Welfare  

E-Print Network [OSTI]

(t) + I(t) (0,1): depreciation rate. K(t+1) = (1 - )K(t) + I(t) (0,1): efficiency/governance services Private capital Rate of time preference Consumption saving decisions Investment in physical and sanitation--increase in enrolment rates (especially for girls, rural areas). 2. Electricity

52

Strategic Use of Human Capital | Department of Energy  

Broader source: Energy.gov (indexed) [DOE]

Human Capital Strategic Use of Human Capital A report on how the DOE uses and plans to reform their use of human capital. Strategic Use of Human Capital More Documents &...

53

A Capital Market Test of Representativeness  

E-Print Network [OSTI]

A CAPITAL MARKET TEST OF REPRESENTATIVENESS A Dissertation by MOHAMMAD URFAN SAFDAR Submitted to the Office of Graduate Studies of Texas A&M University in partial fulfillment of the requirements for the degree of DOCTOR... OF PHILOSOPHY May 2012 Major Subject: Accounting A Capital Market Test of Representativeness Copyright 2012 Mohammad Urfan Safdar A CAPITAL MARKET TEST OF REPRESENTATIVENESS A Dissertation...

Safdar, Mohammad

2012-07-16T23:59:59.000Z

54

Automated solar collector installation design  

DOE Patents [OSTI]

Embodiments may include systems and methods to create and edit a representation of a worksite, to create various data objects, to classify such objects as various types of pre-defined "features" with attendant properties and layout constraints. As part of or in addition to classification, an embodiment may include systems and methods to create, associate, and edit intrinsic and extrinsic properties to these objects. A design engine may apply of design rules to the features described above to generate one or more solar collectors installation design alternatives, including generation of on-screen and/or paper representations of the physical layout or arrangement of the one or more design alternatives.

Wayne, Gary; Frumkin, Alexander; Zaydman, Michael; Lehman, Scott; Brenner, Jules

2014-08-26T23:59:59.000Z

55

Low-Cost Installation of Concentrating Photovoltaic  

E-Print Network [OSTI]

Low-Cost Installation of Concentrating Photovoltaic Renewable Energy Research Renewable Energy inhibit the potential growth of the California photovoltaic market: high installation costs, expenses improvements have been made in recent years on the assembly and deployment of flatplate photovoltaic

56

ACS Installation During SM3B Introduction  

E-Print Network [OSTI]

ACS Installation During SM3B Introduction: · Installed during SM3B in March 2002 · Powerful 3rd · Over-voltage Protection kit installed · Optical Control Electronics connected · New Outer Blanket Layer, and coronagraph ­ Solar Blind Channel (SBC) : HST's most sensitive ultraviolet photon-counting detector 115-180 nm

Sirianni, Marco

57

ATLAS Installation Guide R. Clint Whaley  

E-Print Network [OSTI]

ATLAS Installation Guide R. Clint Whaley November 2, 2007 Abstract This note provides a brief overview of ATLAS, and describes how to install it. It includes extensive discussion of common configure to configure and build the ATLAS package, this note also describes how an installer can confirm

Whaley, R. Clint

58

Hazel Capital | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data CenterFranconia, Virginia: Energy Resources Jump to: navigation,Ohio:Greer CountyCorridorPart A Permit Application Jump to:Capital Place:

59

Evaluations of average level spacings  

SciTech Connect (OSTI)

The average level spacing for highly excited nuclei is a key parameter in cross section formulas based on statistical nuclear models, and also plays an important role in determining many physics quantities. Various methods to evaluate average level spacings are reviewed. Because of the finite experimental resolution, to detect a complete sequence of levels without mixing other parities is extremely difficult, if not totally impossible. Most methods derive the average level spacings by applying a fit, with different degrees of generality, to the truncated Porter-Thomas distribution for reduced neutron widths. A method that tests both distributions of level widths and positions is discussed extensivey with an example of /sup 168/Er data. 19 figures, 2 tables.

Liou, H.I.

1980-01-01T23:59:59.000Z

60

Focus Series: Maine-Residential Direct Install Program | Department...  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

Maine-Residential Direct Install Program Focus Series: Maine-Residential Direct Install Program Better Buildings Neighborhood Program Focus Series: MAINE-Residential Direct Install...

Note: This page contains sample records for the topic "average installed capital" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


61

Nite Capital | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data CenterFranconia, Virginia: Energy ResourcesLoading map...(Utility Company) Jump to:City) JumpOpenJV Jump to: navigation, searchNite Capital

62

Commons Capital | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home5b9fcbce19 NoPublic Utilities Address: 160Benin:EnergyWisconsin: Energy,(EC-LEDS)Columbus ElectricRefuse ToCommons Capital Jump

63

BEV Capital | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Office of InspectorConcentrating SolarElectricEnergyCT BiomassArnprior,Aurantia SACitas Jump to:PáginasBEV Capital

64

Earthrise Capital | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home5b9fcbce19 No revision has beenFfe2fb55-352f-473b-a2dd-50ae8b27f0a6 No revision hasESE Alcohol JumpEarthFirstEarthrise Capital

65

Capital Solar | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Office of Inspector GeneralDepartmentAUDIT REPORT Americium/CuriumSunways JV JumpBraselcoCMNACangnan GelinCapitalSolar

66

Infield Capital | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home5b9fcbce19 No revision hasInformation Earth's Heat JumpInc Place: Eden Prairie,Infield Capital Jump to: navigation, search

67

Capital Investment Incentive (Nova Scotia, Canada)  

Broader source: Energy.gov [DOE]

The Capital Investment Incentive (CII) is part of the Productivity Investment Program as outlined in the economic growth plan for Nova Scotia, jobsHere.

68

The Ohio Capital Access Program (OCAP) (Ohio)  

Broader source: Energy.gov [DOE]

The Ohio Capital Access Program (OCAP) encourages state depository financial institutions to make loans to for-profit or nonprofit small businesses that are having difficulty obtaining business...

69

Capital Cooking: Proposed Penalty (2014-CE-23008)  

Broader source: Energy.gov [DOE]

DOE alleged in a Notice of Proposed Civil Penalty that Capital Cooking Equipment, Inc. failed to certify cooking products as compliant with the applicable energy conservation standards.

70

Asymptotic Analysis of Sample Average Approximation for ...  

E-Print Network [OSTI]

Feb 23, 2012 ... Stochastic Optimization Problems with Joint Chance Constraints ...... in Matlab 7.9.0 installed in a PC with Windows XP operating system.

2012-02-23T23:59:59.000Z

71

Newport Power Meter Drivers CD Installation Software  

E-Print Network [OSTI]

Newport Power Meter Drivers CD Installation Software Version 2.3.1 Revision Date: October 16, 2008 IMPORTANT NOTES: The USB drivers on your CD must be installed before the Newport Power Meter is connected to your PC (via USB cable). Manual: The latest manuals for the Newport Power Meters can be found

Kleinfeld, David

72

Want to Install A Satellite Dish ?  

E-Print Network [OSTI]

listed below to ensure proper installation of your dish. 1. Permanent alterations or modification utility lines would be interfered with by satellite dish post installation. 6. Entry into the unit in case of nearby utility lines or other factors. 3--Point of entry for satellite dish cable

Maxwell, Bruce D.

73

A DISTRIBUTED AUTOMATION SYSTEM FOR ELECTROPHYSICAL INSTALLATIONS  

E-Print Network [OSTI]

A DISTRIBUTED AUTOMATION SYSTEM FOR ELECTROPHYSICAL INSTALLATIONS V.R. Kozak Budker Institute There was designed a set of devices for automation systems of physical installations. On this basis approach. KEY WORDS Automation, systems, applications, CANBUS, embedded, controller. 1. Introduction Budker

Kozak, Victor R.

74

Photovoltaic Installations at Williams College Ruth Aronoff  

E-Print Network [OSTI]

generation using solar power. Photovoltaic (PV) panel installations are a simple way for the College facilities, it is now evaluating in detail the environmental impact of these actions. In addition to making1 Photovoltaic Installations at Williams College Ruth Aronoff Williams Luce Project SUMMARY

Aalberts, Daniel P.

75

Avoided Gigawatts Through Utility Capital Recovery Fees  

E-Print Network [OSTI]

structure is possible through the use of capital recovery fees for new electric meter hookups similar to those commonly used for new water and wastewater hookups where the developer/owner is required to capitalize the marginal cost of new demand. By giving...

Frosenfeld, A. N.; Verdict, M. E.

1985-01-01T23:59:59.000Z

76

Arduino Tool: For Interactive Artwork Installations  

E-Print Network [OSTI]

The emergence of the digital media and computational tools has widened the doors for creativity. The cutting edge in the digital arts and role of new technologies can be explored for the possible creativity. This gives an opportunity to involve arts with technologies to make creative works. The interactive artworks are often installed in the places where multiple people can interact with the installation, which allows the art to achieve its purpose by allowing the people to observe and involve with the installation. The level of engagement of the audience depends on the various factors such as aesthetic satisfaction, how the audience constructs meaning, pleasure and enjoyment. The method to evaluate these experiences is challenging as it depends on integration between the artificial life and real life by means of human computer interaction. This research investigates "How Adriano fits for creative and interactive artwork installations?" using an artwork installation in the campus of NTNU (Norwegian University...

Shaikh, Murtaza Hussain

2012-01-01T23:59:59.000Z

77

Trade and Capital Flows: A Financial Frictions Perspective  

E-Print Network [OSTI]

The classical Heckscher?Ohlin?Mundell paradigm states that trade and capital mobility are substitutes in the sense that trade integration reduces the incentives for capital to flow to capital?scarce countries. In this paper ...

Antrŕs, Pol

78

Accessing Low-Cost Capital Through Securitization (Poster)  

SciTech Connect (OSTI)

Poster for Solar Power International conference presents information on NREL's effort to open capital markets through securitization via Solar Access to Public Capital (SAPC) working group's efforts.

Mendelsohn, M.

2014-10-01T23:59:59.000Z

79

Best Practices for Controlling Capital Costs in Net Zero Energy...  

Energy Savers [EERE]

Best Practices for Controlling Capital Costs in Net Zero Energy Design and Construction - 2014 BTO Peer Review Best Practices for Controlling Capital Costs in Net Zero Energy...

80

Structural considerations for solar installers : an approach for small, simplified solar installations or retrofits.  

SciTech Connect (OSTI)

Structural Considerations for Solar Installers provides a comprehensive outline of structural considerations associated with simplified solar installations and recommends a set of best practices installers can follow when assessing such considerations. Information in the manual comes from engineering and solar experts as well as case studies. The objectives of the manual are to ensure safety and structural durability for rooftop solar installations and to potentially accelerate the permitting process by identifying and remedying structural issues prior to installation. The purpose of this document is to provide tools and guidelines for installers to help ensure that residential photovoltaic (PV) power systems are properly specified and installed with respect to the continuing structural integrity of the building.

Richards, Elizabeth H.; Schindel, Kay (City of Madison, WI); Bosiljevac, Tom; Dwyer, Stephen F.; Lindau, William (Lindau Companies, Inc., Hudson, WI); Harper, Alan (City of Madison, WI)

2011-12-01T23:59:59.000Z

Note: This page contains sample records for the topic "average installed capital" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


81

Structural Code Considerations for Solar Rooftop Installations.  

SciTech Connect (OSTI)

Residential rooftop solar panel installations are limited in part by the high cost of structural related code requirements for field installation. Permitting solar installations is difficult because there is a belief among residential permitting authorities that typical residential rooftops may be structurally inadequate to support the additional load associated with a photovoltaic (PV) solar installation. Typical engineering methods utilized to calculate stresses on a roof structure involve simplifying assumptions that render a complex non-linear structure to a basic determinate beam. This method of analysis neglects the composite action of the entire roof structure, yielding a conservative analysis based on a rafter or top chord of a truss. Consequently, the analysis can result in an overly conservative structural analysis. A literature review was conducted to gain a better understanding of the conservative nature of the regulations and codes governing residential construction and the associated structural system calculations.

Dwyer, Stephen F.; Dwyer, Brian P.; Sanchez, Alfred

2014-12-01T23:59:59.000Z

82

AIR LEAKAGE OF NEWLY INSTALLED RESIDENTIAL WINDOWS  

E-Print Network [OSTI]

Tables 2.0.2a 2.0.2b PAGE Air Leakage Through Sash/FrameOperation Types . . . . . Air Leakage of Installed WindowsComparison of Window Types Air Leakage Performance of

Weidt, John

2013-01-01T23:59:59.000Z

83

Install an Automatic Blowdown Control System  

SciTech Connect (OSTI)

This revised ITP steam tip sheet on installing automatic blowdown controls provide how-to advice for improving industrial steam systems using low-cost, proven practices and technologies.

Not Available

2006-01-01T23:59:59.000Z

84

Peoples Gas – Single Family Direct Install (Illinois)  

Broader source: Energy.gov [DOE]

Owners of single-family homes, condos, townhomes and two-flats may be eligible for a free installation of new programmable thermostats, pipe insulation, showerheads, and faucet aerators through...

85

Install Removable Insulation on Valves and Fittings  

SciTech Connect (OSTI)

This revised ITP tip sheet on installing removable insulation on valves and fittings provides how-to advice for improving the system using low-cost, proven practices and technologies.

Not Available

2006-01-01T23:59:59.000Z

86

Optimizing Installation, Operation, and Maintenance at Offshore...  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

wind industries, and significant first-hand knowledge of offshore installation, operation and maintenance (IO&M) activities. The aim of the GL GH study was to enable project...

87

SAMPLE AVERAGE APPROXIMATION METHOD FOR COMPOUND ...  

E-Print Network [OSTI]

Jun 30, 2013 ... bounds from (10) are much sharper than estimates obtained from (11), ..... X a vector of resources allocated at objects i = 1, ..., n to protect them from the .... and cost functions, IE denotes mathematical expectation over ?. ...... [29] H. Markowitz, Mean-Variance Analysis in Portfolio Choice and Capital Markets, ...

2013-06-30T23:59:59.000Z

88

Adage Capital Management, LP ADP Foundation  

E-Print Network [OSTI]

Adage Capital Management, LP ADP Foundation Agilent Technologies, Inc. Air Products Foundation Alcoa Foundation Alexander & Baldwin, Inc. AllianceBernstein Foundation Fund Allstate Foundation Alstom Power, Inc. Altria Group, Inc. American Express Foundation American Institute for Foreign Study American

Napier, Terrence

89

An Introduction to Venture Capital Granite representatives  

E-Print Network [OSTI]

May 2006 An Introduction to Venture Capital #12;2 Granite representatives Sam Kingsland ­ Managing;3 Introduction to Granite Ventures Founded in 1992 Granite has 9 investment professionals Over $1B under

Anderson, Richard

90

Capitalize on Existing Assets with Demand Response  

E-Print Network [OSTI]

Industrial facilities universally struggle with escalating energy costs. EnerNOC will demonstrate how commercial, industrial, and institutional end-users can capitalize on their existing assets—at no cost and no risk. Demand response, the voluntary...

Collins, J.

2008-01-01T23:59:59.000Z

91

Lining Over Refractory - Conserve Energy and Capital  

E-Print Network [OSTI]

.~. LINING OVER REFRACTORY - CONSERVE ENERGY & CAPITAL by Mark L. Jost Gerald L. Barrows The Carborundum Company Niagara Falls, New York INTRODUCTION Companies operating industrial heating equip Advantages ment find themselves coming under...

Jost, M. L.; Barrows, G. L.

1980-01-01T23:59:59.000Z

92

Social Capital in Professional Learning Communities  

E-Print Network [OSTI]

in sociology of education research. Drawing on organizational sociology, this research proposes a model of PLC social capital that treats brokerage (external ties) and closure (internal ties) as the key dimensions of team functioning as proposed by Ron Burt...

Conrady, David P.

2013-05-31T23:59:59.000Z

93

Favors from Facebook Friends: Unpacking Dimensions of Social Capital  

E-Print Network [OSTI]

capital [5, 14, 19]. Social capital is a conceptual framework that considers the resources held by thoseFavors from Facebook Friends: Unpacking Dimensions of Social Capital Yumi Jung, Rebecca Gray]@umich.edu ABSTRACT Past research has demonstrated a link between perceptions of social capital and use of the popular

Michigan, University of

94

Utility Scale Renewable Energy Development Near DOD Installations...  

Broader source: Energy.gov (indexed) [DOE]

Utility Scale Renewable Energy Development Near DOD Installations: Making the Case for Land Use Compatitbility Utility Scale Renewable Energy Development Near DOD Installations:...

95

Database (Report) of U.S. CHP Installations Incorporating Thermal...  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

Database (Report) of U.S. CHP Installations Incorporating Thermal Energy Storage (TES) andor Turbine Inlet Cooling (TIC), 2004 Database (Report) of U.S. CHP Installations...

96

Obama Administration Announces Plans to Install New Solar Panels...  

Broader source: Energy.gov (indexed) [DOE]

Plans to Install New Solar Panels on the White House Residence Obama Administration Announces Plans to Install New Solar Panels on the White House Residence October 5, 2010 -...

97

Building America Expert Meeting Report: Achieving the Best Installed...  

Broader source: Energy.gov (indexed) [DOE]

Achieving the Best Installed Performance from High-Efficiency Residential Gas Furnaces Building America Expert Meeting Report: Achieving the Best Installed Performance from...

98

H2-Assisted NOx Traps: Test Cell Results Vehicle Installations...  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

H2-Assisted NOx Traps: Test Cell Results Vehicle Installations H2-Assisted NOx Traps: Test Cell Results Vehicle Installations 2003 DEER Conference Presentation: ArvinMeritor...

99

Installation & Commissioning same basic idea as CTB  

E-Print Network [OSTI]

requires Freon-only gas system HV spare TCPU and one LV supply laptop with pcan dongle simple water flow though too heavy for two people need rail holder on the scissor lift or rail holder on spreader bar be installed beforehand, and "short" LV bus Canbus Data cables Water in/out HV (2) and Gas in/out attached

Llope, William J.

100

Installing Small Wind Turbines Seminar and Workshop  

E-Print Network [OSTI]

Seminar and Workshop Installing Small Wind Turbines Seminar and Workshop Location: Murdoch January 2011 Details for Registration and Payment: Mr Daniel Jones, National Small Wind Turbine Test: The National Small Wind Turbine Centre at Murdoch University is holding a Small Wind Turbine short training

Note: This page contains sample records for the topic "average installed capital" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


101

IEA HPP Annex 36 Installation/Quality  

E-Print Network [OSTI]

on installation of air to air heat pump The aim is to use an ergonomic approach, in order to reduce Laboratory European Heat Pump Summit Nuremberg, Germany October 15, 2013 #12;3 Managed by UT), USA 3 10-11 October 2013 EdF, France 4 12 May 2014 Workshop at IEA Heat Pump conference, Montreal

Oak Ridge National Laboratory

102

Standard hydrogen monitoring system equipment installation instructions  

SciTech Connect (OSTI)

This document provides the technical specifications for the equipment fabrication, installation, and sitework construction for the Standard Hydrogen Monitoring System. The Standard Hydrogen Monitoring System is designed to remove gases from waste tank vapor space and exhaust headers for continual monitoring and remote sample analysis.

Schneider, T.C.

1996-09-27T23:59:59.000Z

103

Capital gains tax treatment and the cattleman  

E-Print Network [OSTI]

Major Subject: Agricultural Economics CAPITAL GAINS TAX TREATMENT AND THE CATTLEMAN A Thesis by M I LTDN EDWARD R I STE R Approved as to style and content by: airman o ommi e Dr. Ronald R. Kay Head o D artment Dr. John opkin Mem er Dr. Donald... R. Levi e er Dr. Howard Hesby December 1976 ABSTRACT Capital Gains Tax Treatment and the Catt leman. (December 1976) Milton Edward Rister, B. S. , Texas ASM University Chairman of Advisory Committee: Or. Ronald D. Kay The federal tax...

Rister, M. Edward

1976-01-01T23:59:59.000Z

104

Essays on human capital and financial economics by Jialan Wang.  

E-Print Network [OSTI]

This thesis consists of three essays examining issues related to human capital, careers, and financial economics. In the first chapter, I examine how the process of corporate bankruptcy varies by human capital intensity ...

Wang, Jialan, Ph.D. Massachusetts Institute of Technology

2010-01-01T23:59:59.000Z

105

Capital Controls: Mud in the Wheels of Market Discipline  

E-Print Network [OSTI]

Widespread support for capital account liberalization in emerging markets has recently shifted to skepticism and even support for capital controls in certain circumstances. This sea-change in attitudes has been bolstered ...

Forbes, Kristin J.

2004-03-12T23:59:59.000Z

106

Updated Capital Cost Estimates for Utility Scale Electricity  

E-Print Network [OSTI]

Updated Capital Cost Estimates for Utility Scale Electricity Generating Plants April 2013 Information Administration | Updated Capital Cost Estimates for Utility Scale Electricity Generating Plants ii for Utility Scale Electricity Generating Plants ii Contents Introduction

107

2011-2015 Human Capital Management Plan | Department of Energy  

Broader source: Energy.gov (indexed) [DOE]

This Human Capital Management Plan (HCMP or Plan) shows how we intend to recruit, hire, train, develop, and retain such employees. 2011-2015 Human Capital Management Plan More...

108

Manuel pour installer une station sismologique OSIRIS  

E-Print Network [OSTI]

installation Tout d'abord, enterrer le sismom`etre, s'assurer de l'horizontalit´e du sismo c'est-`a-dire, bulle le c^able sur le sismo, v´erifier de nouveau l'horizontalit´e. GPS Batterie ` Station d "sismo" puis cd osiris puis ./nrtd -set eth0 #12;7- Lancer Firefox (web browser) depuis la barre de menu

Perrot, Julie

109

Soil as natural capital Ecosystem services and  

E-Print Network [OSTI]

threats Decline in: Lead to: soil carbon soil erosion biological ac2 tool box Information on sustainable soil use incentives After Daiily et al 2009 "decision loop" #12;Soil is a natural capital Ecosystem services Nutrient retention Carbon storage Water retention

110

Stress Testing Projected Capitalized Farmland Values  

E-Print Network [OSTI]

that current year real cash rent can be best explained by current year real net farm income, lagged real net farm income over a period of years, and real cash rent in the previous year. A spreadsheet simulation model is used to project capitalized farmland...

Gao, Bo 1988-

2012-11-12T23:59:59.000Z

111

Taxation and Capital Spending Alan J. Auerbach  

E-Print Network [OSTI]

of the Federal Reserve System, October 7, 2005. #12;I. Introduction Why should macroeconomists care about of capital accumulation and hence the rate of economic growth. Current discussions of fundamental tax reform of consumption and the health of the financial sector. I limit my focus to business fixed investment

Sadoulet, Elisabeth

112

FY95 capital asset implementation plan  

SciTech Connect (OSTI)

The Waste Isolation Division (WID) is committed to providing good stewardship for the capital assets under its operational and physical control. To achieve this goal, the WID has developed the Capital Asset Implementation Plan (CAIP) to continue to implement for FY95 Department of Energy (DOE) Order 4320.2A, Capital Asset Management Process (CAMP). The Order provides policy and elements needed to establish a credible, consistent, auditable, and technically sound process for the DOE to forecast, plan, and budget for capital assets on a functional unit level. The objective of the WIPP CAMP program is to meet the goals of DOE Order 4320.2A in the most effective and efficient manner possible in support of the Waste Isolation Pilot Plant (WIPP) mission. As a result, this CAIP provides a way to implement the CAMP Program using a graded approach. Continued implementation will be accomplished by improving the existing process, and establishing future goals to promote growth for the CAMP Program. The CAIP is issued annually by the WID with quarterly progress reports submitted to the DOE. This document describes the current-year program staffing, roles, responsibilities, funding, and near-term milestones. In addition, the results of past goals are discussed.

Not Available

1994-12-01T23:59:59.000Z

113

Capital controls and external debt term structure  

E-Print Network [OSTI]

short-term bonds and one long-term bond offered by the domestic banks to international lenders. First I look at a simple model were international lending is modeled exogenously. I consider explicitly the maturity composition of capital inflows to a...

Al Zein, Eza Ghassan

2005-11-01T23:59:59.000Z

114

A hedge fund business plan : investment theory, operations, and capital raising for Broadgates Capital Management  

E-Print Network [OSTI]

Launching a start-up hedge fund is a complex, multifaceted endeavor that requires an understanding of the interconnectivity between capital raising, investment strategy, regulation, and fund operations. The purpose of this ...

Mills, Jeffrey David

2014-01-01T23:59:59.000Z

115

Is the Insurance Cost-of-Capital Fair? Mathieu Gatumel  

E-Print Network [OSTI]

companies or on the modelling of insurance business profit and loss. We estimate a cost-of-capital rateIs the Insurance Cost-of-Capital Fair? Mathieu Gatumel CAHIER DE RECHERCHE n°2011-07 E2 Unité Mixte the Insurance Cost-of-Capital Fair? MathieuMathieuMathieuMathieu GatumelGatumelGatumelGatumel University

Boyer, Edmond

116

The University of Northern British Columbia Five Year Capital Plan  

E-Print Network [OSTI]

and for the regional campuses; · To estimate the cost of the recommended capital projects and to identify preferred its scope to recommending new capital projects with an estimated cost exceeding $1M. Other yet-to- be-completed capital projects with a cost below $1M previously reported to government are listed in Appendix 2

Northern British Columbia, University of

117

Tier I Canada Research Chair Human Capital and Productivity  

E-Print Network [OSTI]

Tier I Canada Research Chair in Human Capital and Productivity The University of Western Ontario and international candidates for a Tier I Canada Research Chair in the area of Human Capital and Productivity renowned group of economists who work on research related to human capital and productivity. This includes

Lennard, William N.

118

NSTAR (Electric)- Small Business Direct Install Program  

Broader source: Energy.gov [DOE]

The NSTAR Small Business Solutions Program offers incentives for business customers whose average monthly demand is 300 kW or less. The first step of the program is a free energy audit to identify...

119

First installation of an electrical submersible pump in a subsea well  

SciTech Connect (OSTI)

As offshore oil fields are being developed towards deeper and deeper waters, new technologies are required to curb capital expenditures. In Brazil, where oil consumption is increasing and huge oil fields lie in high water depths, the issue is particularly pressing. Earlier and higher oil production from those oil fields could be attained by the use of Electrical Submersible Pumps (ESP), so far restricted to dry completions. Also longer distances from well to platform would be made practical. For the initial phase of this development, Petrobras worked together with Tronic, Reda, Pirelli, Lasalle, Sade-Vigesa and Cooper. As a result, first-in-the-world ESP installation in a subsea well has been successfully achieved on October/1994 in RJS-221, located at Carapeba Field, Campos Basin, Brazil.

Mendonca, J.E.; Hodge, R.C.; Izetti, R. [Petrobras, Rio de Janeiro (Brazil); Nicholson, A.; Dwiggins, J.L.; Morrison, D.; Cia, M.; Alfano, P.P.

1995-12-31T23:59:59.000Z

120

File:Install.pdf | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home5b9fcbce19 NoPublicIDAPowerPlantSitingConstruction.pdf JumpApschem.pdf Jumptight-gas.pdfFut gaspHIak.pdfwy.pdf JumpInstall.pdf

Note: This page contains sample records for the topic "average installed capital" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


121

Installed Geothermal Capacity | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home5b9fcbce19 No revision hasInformation Earth's Heat JumpInc Place: Eden Prairie,InfieldInstalled Geothermal Capacity Jump to:

122

Helping Ensure High-Quality Installation of Solar Power Technologies...  

Energy Savers [EERE]

Ensure High-Quality Installation of Solar Power Technologies Helping Ensure High-Quality Installation of Solar Power Technologies April 15, 2013 - 12:00am Addthis The Midwest...

123

Solar Industry At Work: Streamlining Home Solar Installation...  

Broader source: Energy.gov (indexed) [DOE]

Solar Industry At Work: Streamlining Home Solar Installation Solar Industry At Work: Streamlining Home Solar Installation June 12, 2012 - 11:59am Addthis Sunrun is a home solar...

124

ARRA Program Celebrates Milestone 600,000 Smart Meter Installations...  

Broader source: Energy.gov (indexed) [DOE]

ARRA Program Celebrates Milestone 600,000 Smart Meter Installations ARRA Program Celebrates Milestone 600,000 Smart Meter Installations April 17, 2012 - 3:09pm Addthis On April 11,...

125

Net Zero Energy Military Installations: A Guide to Assessment...  

Broader source: Energy.gov (indexed) [DOE]

Net Zero Energy Military Installations: A Guide to Assessment and Planning Net Zero Energy Military Installations: A Guide to Assessment and Planning In 2008, DoD and DOE defined a...

126

PNNL Reports Distributed Wind Installations Down, Exports Up...  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

PNNL Reports Distributed Wind Installations Down, Exports Up in 2013 PNNL Reports Distributed Wind Installations Down, Exports Up in 2013 March 31, 2014 - 11:14am Addthis According...

127

Pasadena Water and Power- Solar Power Installation Rebate  

Broader source: Energy.gov [DOE]

Pasadena Water and Power (PWP) offers its electric customers a rebate for photovoltaic (PV) installations, with a goal of helping to fund the installation of 14 megawatts (MW) of solar power by...

128

Portland Advancing Green Image With Solar Installs | Department...  

Broader source: Energy.gov (indexed) [DOE]

Portland Advancing Green Image With Solar Installs Portland Advancing Green Image With Solar Installs February 22, 2010 - 12:10pm Addthis Laura Smoyer checks the net-metering...

129

Energy Saving "Cool Roofs" Installed at Y-12 | National Nuclear...  

National Nuclear Security Administration (NNSA)

Home Field Offices Welcome to the NNSA Production Office NPO News Releases Energy Saving "Cool Roofs" Installed at Y-12 Energy Saving "Cool Roofs" Installed at Y-12 The...

130

Energy Saving 'Cool Roofs' Installed at Y-12 | National Nuclear...  

National Nuclear Security Administration (NNSA)

Photo Gallery Jobs Apply for Our Jobs Our Jobs Working at NNSA Blog Home NNSA Blog Energy Saving 'Cool Roofs' Installed at Y-12 Energy Saving 'Cool Roofs' Installed at Y-12...

131

Energy Department Launches SunShot Prize Competition to Install...  

Broader source: Energy.gov (indexed) [DOE]

SunShot Prize Competition to Install Solar Energy Systems at a Fraction of Today's Price Energy Department Launches SunShot Prize Competition to Install Solar Energy Systems at a...

132

Secretary Chu Announces Two Million Smart Grid Meters Installed...  

Energy Savers [EERE]

Two Million Smart Grid Meters Installed Nationwide Secretary Chu Announces Two Million Smart Grid Meters Installed Nationwide August 31, 2010 - 12:00am Addthis Columbus, OH - At an...

133

STAFF FORECAST: AVERAGE RETAIL ELECTRICITY PRICES  

E-Print Network [OSTI]

CALIFORNIA ENERGY COMMISSION STAFF FORECAST: AVERAGE RETAIL ELECTRICITY PRICES 2005 TO 2018 Mignon Marks Principal Author Mignon Marks Project Manager David Ashuckian Manager ELECTRICITY ANALYSIS OFFICE Sylvia Bender Acting Deputy Director ELECTRICITY SUPPLY DIVISION B.B. Blevins Executive Director

134

Selling Geothermal Systems The "Average" Contractor  

E-Print Network [OSTI]

Selling Geothermal Systems #12;The "Average" Contractor · History of sales procedures · Manufacturer Driven Procedures · What makes geothermal technology any harder to sell? #12;"It's difficult to sell a geothermal system." · It should

135

NREL Job Task Analysis: Retrofit Installer Technician (Revised)  

SciTech Connect (OSTI)

A summary of job task analyses for the position of retrofit installer technician when conducting weatherization work on a residence.

Kurnik, C.; Woodley, C.

2012-04-01T23:59:59.000Z

136

North Cove Capital Advisors | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data CenterFranconia, Virginia: Energy ResourcesLoading map...(Utility Company) Jump to:City)Norristown,Braddock isStateCentralCapital Advisors

137

Conservation Capital LLC | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Office of InspectorConcentratingRenewable Solutions LLC Jump to: navigation,AreaHighInformationConservation Capital

138

Green Capital Management | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data CenterFranconia, Virginia: Energy Resources Jump to: navigation,Ohio: EnergyGrasslands RenewableGreatwood, Texas:Open EnergyGreen Capital

139

James Monroe Capital Corporation | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data CenterFranconia, Virginia: Energy Resources Jump to:46 - 429 Throttled (botOpen Energy2005)Jamaica Beach, Texas: EnergyJames Monroe Capital

140

Capital Energy SL | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Office of Inspector GeneralDepartmentAUDIT REPORT Americium/CuriumSunways JV JumpBraselcoCMNACangnan GelinCapital

Note: This page contains sample records for the topic "average installed capital" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


141

Impact Capital Partners Limited | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data CenterFranconia, Virginia: Energy Resources Jump to: navigation,Ohio:GreerHiCalifornia:ISI SolarIdanha,Information JumpMoroccoCapital

142

Performance of Installed Cooking Exhaust Devices  

SciTech Connect (OSTI)

The performance metrics of airflow, sound, and combustion product capture efficiency (CE) were measured for a convenience sample of fifteen cooking exhaust devices, as installed in residences. Results were analyzed to quantify the impact of various device- and installation-dependent parameters on CE. Measured maximum airflows were 70% or lower than values noted on product literature for 10 of the devices. Above-the-cooktop devices with flat bottom surfaces (no capture hood) – including exhaust fan/microwave combination appliances – were found to have much lower CE at similar flow rates, compared to devices with capture hoods. For almost all exhaust devices and especially for rear-mounted downdraft exhaust and microwaves, CE was substantially higher for back compared with front burner use. Flow rate, and the extent to which the exhaust device extends over the burners that are in use, also had a large effect on CE. A flow rate of 95 liters per second (200 cubic feet per minute) was necessary, but not sufficient, to attain capture efficiency in excess of 75% for the front burners. A-weighted sound levels in kitchens exceeded 57 dB when operating at the highest fan setting for all 14 devices evaluated for sound performance.

Singer, Brett C.; Delp, William W.; Apte, Michael G.; Price, Philip N.

2011-11-01T23:59:59.000Z

143

RMP Standard PreInstalled Software Page 1 of 2  

E-Print Network [OSTI]

RMP Standard PreInstalled Software Page 1 of 2 Standard Software PreInstalled with RMP Windows@lmu.edu or 310-338-7777 RMP Standard PreInstalled Software Page 2 of 2 · Photo Booth EndNote Apple DVD Player

Dahlquist, Kam D.

144

A GUIDE TO PHOTOVOLTAIC (PV) SYSTEM DESIGN AND INSTALLATION  

E-Print Network [OSTI]

CALIFORNIA ENERGY COMMISSION A GUIDE TO PHOTOVOLTAIC (PV) SYSTEM DESIGN AND INSTALLATION JUNE 2001 TO PHOTOVOLTAIC (PV) SYSTEM DESIGN AND INSTALLATION Prepared for: California Energy Commission Energy Technology installing photovoltaic (PV) systems under the Emerging Renewables Buydown Program. This is the first

145

IBM Systems Director Active Energy Manager Installation and User's Guide  

E-Print Network [OSTI]

IBM Systems Director Active Energy Manager Installation and User's Guide Version 4.3 #12;#12;IBM Systems Director Active Energy Manager Installation and User's Guide Version 4.3 #12;ii IBM Systems Director Active Energy Manager: Installation and User's Guide #12;About this book This book provides

146

Polarized electron beams at milliampere average current  

SciTech Connect (OSTI)

This contribution describes some of the challenges associated with developing a polarized electron source capable of uninterrupted days-long operation at milliAmpere average beam current with polarization greater than 80%. Challenges will be presented in the context of assessing the required level of extrapolation beyond the performance of today's CEBAF polarized source operating at ~ 200 uA average current. Estimates of performance at higher current will be based on hours-long demonstrations at 1 and 4 mA. Particular attention will be paid to beam-related lifetime-limiting mechanisms, and strategies to construct a photogun that operate reliably at bias voltage > 350kV.

Poelker, Matthew [JLAB

2013-11-01T23:59:59.000Z

147

Extracting gluon condensate from the average plaquette  

E-Print Network [OSTI]

The perturbative contribution in the average plaquette is subtracted using Borel summation and the remnant of the plaquette is shown to scale as a dim-4 condensate. A critical review is presented of the renormalon subtraction scheme that claimed a dim-2 condensate. The extracted gluon condensate is compared with the latest result employing high order (35-loop) calculation in the stochastic perturbation theory.

Lee, Taekoon

2015-01-01T23:59:59.000Z

148

Laser Fusion Energy The High Average Power  

E-Print Network [OSTI]

Laser Fusion Energy and The High Average Power Program John Sethian Naval Research Laboratory Dec for Inertial Fusion Energy with lasers, direct drive targets and solid wall chambers Lasers DPPSL (LLNL) Kr posters Snead Payne #12;Laser(s) Goals 1. Develop technologies that can meet the fusion energy

149

IT Capital Planning | Department of Energy  

Energy Savers [EERE]

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious RankCombustion |Energy UsageAUDITVehicles »Exchange Visitors HistoryHybrid Wind and SolarIT Capital Planning

150

New Energy Capital Corp | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data CenterFranconia, Virginia: Energy Resources Jump to:46 -Energieprojekte3InformationofServicesNeuCo620572°,York: EnergyCapital Corp

151

Human Capital Organization | Department of Energy  

Office of Environmental Management (EM)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr May Jun Jul(Summary) " ,"ClickPipelinesProvedDecember 2005DepartmentDecemberGlossaryEnergy andAction CenterHuman Capital

152

MVP Capital Partners | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home5b9fcbce19 No revision hasInformation Earth's Heat JumpIncMAKGalway Bay IEOWCCatcher.pngWavemill <MN OfficeMSEMVP Capital

153

Wind Farm Capital | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Office of Inspector GeneralDepartmentAUDIT REPORTOpenWende NewSowitec do BrasilGmbHWeardale TaskEnergyLtd JumpCapital

154

Black Coral Capital | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Office of Inspector GeneralDepartmentAUDIT REPORTOpenWendeGuo Feng Bio JumpVenturesCoral Capital Jump to: navigation,

155

Mont Vista Capital LLC | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home5b9fcbce19 No revision hasInformation Earth's HeatMexico: EnergyMithun Jump to:Moe WindMont Vista Capital LLC Place: New

156

Starlight Capital Advisors | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home5b9fcbce19 No revisionEnvReviewNonInvasiveExplorationUT-g GrantAtlas (PACA RegionSpringview IISt.Starlight Capital Advisors Jump

157

CAPITAL PROGRAMMING GUIDE | Department of Energy  

Office of Environmental Management (EM)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr May Jun Jul(Summary) "of Energy Power Systems EngineeringDepartment of4 Federal6Clean EnergyofF. 1400.12 (03-00)EnergyCAPITAL

158

Absolute Energy Capital | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Office of InspectorConcentrating SolarElectric Coop,SaveWhiskey FlatshydroMultiple2Abrams, Wisconsin:Capital Jump to:

159

Capital Sources and Providers | Department of Energy  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE:YearRound-Up fromDepartmentTie Ltd:June 20154:04-21-2014 (866) 448 - DEPOMeeting No.Capital Sources

160

Greenwood Capital Partners | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home5b9fcbce19 No revision hasInformation Earth's Heat Jump to:Photon Place: Golden,GreenVoltsGreenpeaceGreenwood Capital

Note: This page contains sample records for the topic "average installed capital" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


161

Climate Human Capital | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home5b9fcbce19 NoPublic Utilities Address: 160Benin:EnergyWisconsin: Energy ResourcesInformation is 045.Update Jump to:Capital

162

Memo Issuance of EM Capital and Major Operating Project Standard...  

Office of Environmental Management (EM)

Deputy Assistant Secretary for Human Capital and Corporate Services, EM-70 John Surash, Deputy Assistant Secretary for Acquisition and Contract Management, EM-80 Susan...

163

International Human Capital Formation, Brain Drain and Brain  

E-Print Network [OSTI]

systems, individuals' abilities, sunk educational investment costs, government grants, and expected capital formation, brain gain, brain drain, international migration, sunk costs, educational grants

Paris-Sud XI, Université de

164

Workplace Charging Challenge Partner: Capital One Financial Corporatio...  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

contribute to these emissions, Capital One developed a Sustainable Transportation Demand Management program which includes Flexible Work Solutions to enable associates to work...

165

Quantifying capital goods for waste incineration  

SciTech Connect (OSTI)

Highlights: • Materials and energy used for the construction of waste incinerators were quantified. • The data was collected from five incineration plants in Scandinavia. • Included were six main materials, electronic systems, cables and all transportation. • The capital goods contributed 2–3% compared to the direct emissions impact on GW. - Abstract: Materials and energy used for the construction of modern waste incineration plants were quantified. The data was collected from five incineration plants (72,000–240,000 tonnes per year) built in Scandinavia (Norway, Finland and Denmark) between 2006 and 2012. Concrete for the buildings was the main material used amounting to 19,000–26,000 tonnes per plant. The quantification further included six main materials, electronic systems, cables and all transportation. The energy used for the actual on-site construction of the incinerators was in the range 4000–5000 MW h. In terms of the environmental burden of producing the materials used in the construction, steel for the building and the machinery contributed the most. The material and energy used for the construction corresponded to the emission of 7–14 kg CO{sub 2} per tonne of waste combusted throughout the lifetime of the incineration plant. The assessment showed that, compared to data reported in the literature on direct emissions from the operation of incinerators, the environmental impacts caused by the construction of buildings and machinery (capital goods) could amount to 2–3% with respect to kg CO{sub 2} per tonne of waste combusted.

Brogaard, L.K., E-mail: lksb@env.dtu.dk [Department of Environmental Engineering, Building 115, Technical University of Denmark, DK-2800 Kongens Lyngby (Denmark); Riber, C. [Ramboll, Consulting Engineers, Hannemanns Allé 53, DK-2300 Copenhagen S (Denmark); Christensen, T.H. [Department of Environmental Engineering, Building 115, Technical University of Denmark, DK-2800 Kongens Lyngby (Denmark)

2013-06-15T23:59:59.000Z

166

Installation considerations for IGBT AC drives  

SciTech Connect (OSTI)

In the last four years, Adjustable Speed ac Drive (ASD) manufacturers have migrated from Bipolar Junction Transistor (BJT) semiconductors to Insulated Gate Bipolar Transistors (IGBTs) as the preferred Output switching device. The advantage of IGBTs over BJTs is that device rise and fall time switching capability is 5 - 10 times faster, resulting in lower device switching loss and a more efficient drive. However, for a similar motor cable length as the BJT drive, the faster output voltage risetime of the IGBT drive may increase the dielectric voltage stress on the motor and cable due to a phenomenon called reflected wave. Faster output dv/dt transitions of IGBT drives also increase the possibility for phenomenon such as increased Common Mode (CM) electrical noise, Electromagnetic Interference (EMI) problems and increased capacitive cable charging current problems. Also, recent experience suggests any Pulse Width Modulated (PWM) drive with a steep fronted output voltage wave form may increase motor shaft voltage and lead to a bearing current phenomenon known as fluting. This paper provides a basic understanding of these issues, as well as solutions, to insure a successful drive system installation.

Skibinski, G.L.

1997-06-01T23:59:59.000Z

167

Gasket and snap ring installation tool  

DOE Patents [OSTI]

A tool for installing a gasket and a snap ring including a shaft, a first plate attached to the forward end of the shaft, a second plate slidably carried by the shaft, a spring disposed about the shaft between the first and second plates, and a sleeve that is free to slide over the shaft and engage the second plate. The first plate has a loading surface with a loading groove for receiving a snap ring and a shoulder for holding a gasket. A plurality of openings are formed through the first plate, communicating with the loading groove and approximately equally spaced about the groove. A plurality of rods are attached to the second plate, each rod slidable in one of the openings. In use, the loaded tool is inserted into a hollow pipe or pipe fitting having an internal flange and an internal seating groove, such that the gasket is positioned against the flange and the ring is in the approximate plane of the seating groove. The sleeve is pushed against the second plate, sliding the second plate towards the first plate, compressing the spring and sliding the rods forwards in the openings. The rods engage the snap ring and urge the ring from the loading groove into the seating groove.

Southerland, Jr., James M. (Aiken, SC); Barringer, Jr., Curtis N. (Orangeburg, SC)

1994-01-01T23:59:59.000Z

168

Polarized electron beams at milliampere average current  

SciTech Connect (OSTI)

This contribution describes some of the challenges associated with developing a polarized electron source capable of uninterrupted days-long operation at milliAmpere average beam current with polarization greater than 80%. Challenges will be presented in the context of assessing the required level of extrapolation beyond the performance of today’s CEBAF polarized source operating at ? 200 uA average current. Estimates of performance at higher current will be based on hours-long demonstrations at 1 and 4 mA. Particular attention will be paid to beam-related lifetime-limiting mechanisms, and strategies to construct a photogun that operate reliably at bias voltage > 350kV.

Poelker, M. [Thomas Jefferson National Accelerator Facility, Newport News, Virginia 23606 (United States)

2013-11-07T23:59:59.000Z

169

Installation package for a Sunspot Cascade Solar Water Heating System  

SciTech Connect (OSTI)

Elcam, Incorporated of Santa Barbara, California, has developed two solar water heating systems. The systems have been installed at Tempe, Arizona and San Diego, California. The systems consist of the following: collector, collector-tank water loop, solar tank, conventional tank and controls. General guidelines are provided which may be utilized in development of detailed instalation plans and specifications. In addition, it provides instruction on operation, maintenance and installation of solar hot water systems.

None

1980-09-01T23:59:59.000Z

170

Utility Scale Renewable Energy Development Near DOD Installations...  

Broader source: Energy.gov (indexed) [DOE]

Aimone, P.E. National Security Global Business Battelle Memorial Institute Utility Scale Renewable Energy Development near DOD Installations Making the Case for Land Use...

171

Electric Vehicle Grid Integration for Sustainable Military Installations (Presentation)  

SciTech Connect (OSTI)

This presentation discusses electric vehicle grid integration for sustainable military installations. Fort Carson Military Reservation in Colorado Springs is used as a case study.

Simpson, M.

2011-05-05T23:59:59.000Z

172

Plug and Play: Purchase, Install, and Connect Residential Solar...  

Energy Savers [EERE]

roof mounting system, eliminating the need for racking systems. Once the lightweight solar panels are in place, the system then self-tests for proper installation and...

173

Reviewing Post-Installation and Annual Reports for Federal ESPC...  

Broader source: Energy.gov (indexed) [DOE]

reviews of post-installation and annual reports for federal ESPC projects. These procedures will allow for consistent evaluations of performance reports, produce...

174

U.S. CHP Installations Incorporating Thermal Energy Storage ...  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

Company of Lisle, Illinois, for UT-Battelle, Oak Ridge National Laboratory. tictesdatabase.pdf More Documents & Publications Database (Report) of U.S. CHP Installations...

175

Pantex installs new meters to help to reduce energy consumption...  

National Nuclear Security Administration (NNSA)

installs new meters to help to reduce energy consumption | National Nuclear Security Administration Facebook Twitter Youtube Flickr RSS People Mission Managing the Stockpile...

176

Project examples Install new HVAC, electrical, fire protection,  

E-Print Network [OSTI]

Project examples Install new HVAC, electrical, fire protection, and plumbing systems in Mechanical. · Totransformthisspaceandincreaseaccessibility, anelevatorisrequired.Currently,Blakelydoesnot haveone. Replace HVAC and electrical system

Blanchette, Robert A.

177

Rhode Island Stormwater Design and Installation Standards Manual (Rhode Island)  

Broader source: Energy.gov [DOE]

Rhode Island's stormwater design and installation standards manual has been developed to describe mandatory and suggested stormwater design and performance criteria for applicants to the Department...

178

Consider Installing High-Pressure Boilers with BackpressureTurbine...  

Broader source: Energy.gov (indexed) [DOE]

High-Pressure Boilers with Backpressure Turbine-Generators Consider Installing High-Pressure Boilers with Backpressure Turbine-Generators This tip sheet outlines the benefits of...

179

NMDOT Application for Permit to Install Utility Facilities Within...  

Open Energy Info (EERE)

Reference LibraryAdd to library Legal Document- OtherOther: NMDOT Application for Permit to Install Utility Facilities Within Public ROWLegal Published NA Year Signed or Took...

180

Microsoft Word - CX-Ashe-CGSFiberInstallation_WEB.doc  

Broader source: Energy.gov (indexed) [DOE]

5, 2011 REPLY TO ATTN OF: KEP-4 SUBJECT: Environmental Clearance Memorandum Debbie Ruckwardt Electrical Engineer - TEP-CSB-1 Proposed Action: Installing fiber optic cables between...

Note: This page contains sample records for the topic "average installed capital" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


181

DOE-DOD Emergency Backup Power Fuel Cell Installations  

Fuel Cell Technologies Publication and Product Library (EERE)

Ths fact sheet describes a collaboration between the departments of Energy and Defense to install and operate 18 fuel cell backup power systems across the United States.

182

Permit for Charging Equipment Installation: Electric Vehicle Supply Equipment (EVSE)  

Broader source: Energy.gov [DOE]

Jurisdiction's can use this template to develop a standard permit for residential charging stations that allows for quick, safe installation of EVSE.

183

CATEGORICAL EXCLUSION TO INSTALL EMSL SUPER-COMPUTER POWER INFRASTRUCT...  

Broader source: Energy.gov (indexed) [DOE]

developing a Fee for Service agreement with the City of Richland to install a new transformer and high voltage switching yard from existing City electrical vaults capable of...

184

Revised Date September 18, 2013 Capital Project Planning  

E-Print Network [OSTI]

. Identify Funding Funding Source(s) 2. Cost Estimate Information (from preliminary estimate form): 3_- Project Name Cost Estimate Low Range High Range #12;Revised Date ­ January 25, 2013 Priority RankingRevised Date ­ September 18, 2013 Capital Project Planning Project Approval Form All capital

185

A Two State Capital Asset Pricing Model Moshe Fridman  

E-Print Network [OSTI]

as Hidden Markov Models (HMM). We apply the model to monthly return data for three oil industry corporation expected returns on capital assets investments with ex- pected market returns. Under the model, the returnA Two State Capital Asset Pricing Model Moshe Fridman Institute for Mathematics and its

186

Valuing Rail Transit: Comparing Capital and Operating Costs to Consumer Benefits  

E-Print Network [OSTI]

years gives an annual capital cost estimate of $321 million,further adjust the capital cost estimates for these systemscosts. In order to estimate capital costs for five systems

Guerra, Erick

2010-01-01T23:59:59.000Z

187

On the relation between expected returns and implied cost of capital  

E-Print Network [OSTI]

coef?cient estimate on implied cost of capital to be biased.the implied cost of capital literature estimates of the exestimates of ex ante risk premiums inferred from implied cost of capital

Hughes, John; Liu, Jing; Liu, Jun

2009-01-01T23:59:59.000Z

188

Is dark energy an effect of averaging?  

E-Print Network [OSTI]

The present standard model of cosmology states that the known particles carry only a tiny fraction of total mass and energy of the Universe. Rather, unknown dark matter and dark energy are the dominant contributions to the cosmic energy budget. We review the logic that leads to the postulated dark energy and present an alternative point of view, in which the puzzle may be solved by properly taking into account the influence of cosmic structures on global observables. We illustrate the effect of averaging on the measurement of the Hubble constant.

Nan Li; Marina Seikel; Dominik J. Schwarz

2008-01-22T23:59:59.000Z

189

Property:SalinityAverage | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home5b9fcbce19 No revisionEnvReviewNonInvasiveExploration Jump to:FieldProceduresFYID6/OrganizationID8/WebsiteSalinityAverage Jump

190

Targeting Net Zero Energy for Military Installations (Presentation)  

SciTech Connect (OSTI)

Targeting Net Zero Energy for Military Installations in Kaneohe Bay, Hawaii. A net zero energy installation (NZEI) is one that produces as much energy from on-site renewable sources as it consumes. NZEI assessment provides a systematic approach to energy projects.

Burman, K.

2012-05-01T23:59:59.000Z

191

Wall Sculpture by Ellsworth Kelly Installed on Dartmouth Campus  

E-Print Network [OSTI]

Wall Sculpture by Ellsworth Kelly Installed on Dartmouth Campus Dartmouth Panels will be dedicated District, a wall sculpture by renowned abstract artist Ellsworth Kelly has been installed on the eastern façade of the Hopkins Center for the Arts, facing the Visual Arts Center. Kelly was in attendance

Shepherd, Simon

192

Establishing and Sustaining System Integrity via Root of Trust Installation  

E-Print Network [OSTI]

integrity. The TPM-based integrity measurement approaches are effective for measuring well-known, staticEstablishing and Sustaining System Integrity via Root of Trust Installation Abstract Integrity the management of a system's integrity, we propose a Root of Trust Installation (ROTI) as a foundation for high

McDaniel, Patrick Drew

193

Lessons Learned During HVAC Installation Dept. of Computer Science  

E-Print Network [OSTI]

Lessons Learned During HVAC Installation Ian Watson AI-CBR Dept. of Computer Science University of HVAC equipment. It has been developed as an adjunct to an existing system that uses case-based reasoning to reuse previous HVAC installation specifications and designs. The system described lets

Watson, Ian

194

IBM Systems Director VMControl Installation and User's Guide  

E-Print Network [OSTI]

IBM Systems Director VMControl Installation and User's Guide Version 2 Release 2 #12;#12;IBM Systems Director VMControl Installation and User's Guide Version 2 Release 2 #12;ii IBM Systems Director read this book . . . . . . . . . 1 Conventions and terminology . . . . . . . . 1 Chapter 2. IBM Systems

195

Developing our human capital : a mixed-method study of teacher use of online communities  

E-Print Network [OSTI]

capital refers to interconnectivity or relations betweensocial capital, or interconnectivity is available to them.teachers were developing interconnectivity and relationships

Clark, Rebecca Peterson

2010-01-01T23:59:59.000Z

196

Average transverse momentum quantities approaching the lightfront  

E-Print Network [OSTI]

In this contribution to Light Cone 2014, three average transverse momentum quantities are discussed: the Sivers shift, the dijet imbalance, and the $p_T$ broadening. The definitions of these quantities involve integrals over all transverse momenta that are overly sensitive to the region of large transverse momenta, which conveys little information about the transverse momentum distributions of quarks and gluons inside hadrons. TMD factorization naturally suggests alternative definitions of such integrated quantities, using Bessel-weighting and rapidity cut-offs, with the conventional definitions as limiting cases. The regularized quantities are given in terms of integrals over the TMDs of interest that are well-defined and moreover have the advantage of being amenable to lattice evaluations.

Daniel Boer

2014-09-29T23:59:59.000Z

197

Install, both Arduino and AmaSeis software programs: Installing Arduino and drivers: Setting up AmaSeis  

E-Print Network [OSTI]

Install, both Arduino and AmaSeis software programs: Installing Arduino and drivers: Setting up Ama the Arduino drivers. Take note of the assigned com port number, and set up AmaSeis to that number. 3. Some computers will require the following. Keep in mind, Arduino, does not need to run or be involved. You just

Barrash, Warren

198

Installation and Commissioning Automated Demand Response Systems  

SciTech Connect (OSTI)

Demand Response (DR) can be defined as actions taken to reduce electric loads when contingencies, such as emergencies and congestion, occur that threaten supply-demand balance, or market conditions raise supply costs. California utilities have offered price and reliability DR based programs to customers to help reduce electric peak demand. The lack of knowledge about the DR programs and how to develop and implement DR control strategies is a barrier to participation in DR programs, as is the lack of automation of DR systems. Most DR activities are manual and require people to first receive notifications, and then act on the information to execute DR strategies. Levels of automation in DR can be defined as follows. Manual Demand Response involves a labor-intensive approach such as manually turning off or changing comfort set points at each equipment switch or controller. Semi-Automated Demand Response involves a pre-programmed demand response strategy initiated by a person via centralized control system. Fully-Automated Demand Response does not involve human intervention, but is initiated at a home, building, or facility through receipt of an external communications signal. The receipt of the external signal initiates pre-programmed demand response strategies. We refer to this as Auto-DR (Piette et. al. 2005). Auto-DR for commercial and industrial facilities can be defined as fully automated DR initiated by a signal from a utility or other appropriate entity and that provides fully-automated connectivity to customer end-use control strategies. One important concept in Auto-DR is that a homeowner or facility manager should be able to 'opt out' or 'override' a DR event if the event comes at time when the reduction in end-use services is not desirable. Therefore, Auto-DR is not handing over total control of the equipment or the facility to the utility but simply allowing the utility to pass on grid related information which then triggers facility defined and programmed strategies if convenient to the facility. From 2003 through 2006 Lawrence Berkeley National Laboratory (LBNL) and the Demand Response Research Center (DRRC) developed and tested a series of demand response automation communications technologies known as Automated Demand Response (Auto-DR). In 2007, LBNL worked with three investor-owned utilities to commercialize and implement Auto-DR programs in their territories. This paper summarizes the history of technology development for Auto-DR, and describes the DR technologies and control strategies utilized at many of the facilities. It outlines early experience in commercializing Auto-DR systems within PG&E DR programs, including the steps to configure the automation technology. The paper also describes the DR sheds derived using three different baseline methodologies. Emphasis is given to the lessons learned from installation and commissioning of Auto-DR systems, with a detailed description of the technical coordination roles and responsibilities, and costs.

Global Energy Partners; Pacific Gas and Electric Company; Kiliccote, Sila; Kiliccote, Sila; Piette, Mary Ann; Wikler, Greg; Prijyanonda, Joe; Chiu, Albert

2008-04-21T23:59:59.000Z

199

Fact #835: August 25, Average Annual Gasoline Pump Price, 1929...  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

5: August 25, Average Annual Gasoline Pump Price, 1929-2013 Fact 835: August 25, Average Annual Gasoline Pump Price, 1929-2013 When adjusted for inflation, the average annual...

200

Preliminary assessment report for Camp Swift Military Reservation, Installation 48070, Bastrop County, Texas. Installation Restoration Program  

SciTech Connect (OSTI)

This report presents the results of the preliminary assessment (PA) conducted by Argonne National Laboratory at the Texas Army National Guard property in Bastrop County, Texas. Preliminary assessments of federal facilities are being conducted to compile the information necessary for completing preremedial activities and to provide a basis for establishing corrective actions in response to releases of hazardous substances. The principal objective of the PA is to characterize the site accurately and determine the need for further action by examining site activities, quantities of hazardous substances present, and potential pathways by which contamination could affect public health and the environment. This PA satisfies, for the Camp Swift property, the requirement of the Department of Defense Installation Restoration Program (IRP). The review of both historical and current practices at the property indicated that the activities at Camp Swift include no operations considered to have an adverse impact to the environment. The recommendation, therefore, is that no further IRP action is necessary at this property.

Dennis, C.B.

1993-08-01T23:59:59.000Z

Note: This page contains sample records for the topic "average installed capital" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


201

Preliminary assessment report for National Guard Facility, Installation 25255, Rehoboth, Massachusetts. Installation Restoration Program  

SciTech Connect (OSTI)

This report presents the results of the preliminary assessment (PA) conducted by Argonne National Laboratory at the Massachusetts Army National Guard (MAARNG) property known as the Rehoboth National Guard Facility (RNGF) in Rehoboth, Massachusetts. Preliminary assessments of federal facilities are being conducted to compile the information necessary for completing preremedial activities and to provide a basis for establishing corrective actions in response to releases of hazardous substances. The principal objective of the PA is to characterize the site accurately and determine the need for ftirther action by examining site activities, quantities of hazardous substances present, and potential pathways by which contamination could affect public health and the environment. This PA satisfies, for the RNGF property, phase I of the Department of Defense Installation Restoration Program (IRP). The scope of this assessment is limited to the facilities under the control of the MAARNG and the past activities contained within that area.

Haffenden, R.; Flaim, S.; Krokosz, M.

1993-08-01T23:59:59.000Z

202

Solar hot water system installed at Mobile, Alabama. Final report  

SciTech Connect (OSTI)

This final report describes the solar energy hot water system installed at LaQuinta Motor Inn Inc., at Mobile, Alabama. The building is a 122 unit motel. The system consists of six rows of ten collectors and three rows of eleven collectors (1990 square feet) mounted on the roof. Griswald flow control valves were installed to regulate the flow to each row. Two Heliotrope electronic thermometers with a combined capability of measuring the temperatures of 22 different locations were installed for monitoring purposes. Engineering drawings, component specifications, and operator instructions are included.

None

1980-10-01T23:59:59.000Z

203

Fact #693: September 19, 2011 Average Vehicle Footprint for Cars...  

Energy Savers [EERE]

and the average track width of the vehicle. The upcoming Corporate Average Fuel Economy (CAFE) Standards have fuel economy targets based on the vehicle footprint. The...

204

average atom model: Topics by E-print Network  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

(chemical potential, average ionic charge, free electron density, bound and continuum wave-functions and occupation numbers) are obtained from the average-atom model. The...

205

Federal Aviation Administration's Airport Capital Improvement Program Development Process  

E-Print Network [OSTI]

The Airport Capital Improvement Program (ACIP) serves as the primary tool for project planning and formulation by the Federal Aviation Administration (FAA). The FAA relies on the ACIP to serve as the basis for the distribution of Aviation Trust...

Tener, Scott D.

2009-12-18T23:59:59.000Z

206

Human capital, institutions, and incentives : micro and macro perspectives  

E-Print Network [OSTI]

This dissertation consists of four essays on human capital, institutions, and incentives. In the first essay, I investigate the effects of voucher-school competition on educational outcomes in Chile. I present a theoretical ...

Gallego, Francisco A

2006-01-01T23:59:59.000Z

207

Women in engineering conference: capitalizing on today`s challenges  

SciTech Connect (OSTI)

This document contains the conference proceedings of the Women in Engineering Conference: Capitalizing on Today`s Challenges, held June 1-4, 1996 in Denver, Colorado. Topics included engineering and science education, career paths, workplace issues, and affirmative action.

Metz, S.S.; Martins, S.M. [eds.] [eds.

1996-06-01T23:59:59.000Z

208

Foundation Capital response to the Notice of Inquiry: Technology...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Foundation Capital.txt From: Michael Bauer MBauer@FoundationCap.com Sent: Thursday, April 16, 2009 11:20 AM To: GC-62 Subject: Fed Register comments Dear Sir or Lady, Per...

209

Lasting social impact : Community Development Venture Capital investing  

E-Print Network [OSTI]

Community Development Venture Capital Funds (CDVC) funds are an emerging group of Community Development Financial Institutions, that make equity investments in businesses in economically distressed areas. As equity investors, ...

Silberberg, Hattie Paige

2008-01-01T23:59:59.000Z

210

Fuel costs and the retirement of capital goods  

E-Print Network [OSTI]

This paper explores the effect that energy prices and market conditions have on the retirement rates of capital goods using new micro data on aircraft lifetimes and fuel costs. The oil shocks of the 1970s made fuel intensive ...

Goolsbee, Austan Dean

1993-01-01T23:59:59.000Z

211

Small Business Venture Capital Tax Credit Program (Manitoba, Canada)  

Broader source: Energy.gov [DOE]

The Small Business Venture Capital Tax Credit Program (SBVCTC) assists eligible small corporations to issue new equity to primarily new investors. The small corporation will be able to issue from ...

212

Tenant-in-common capital in value added transactions  

E-Print Network [OSTI]

Billions of dollars of equity is flowing into the emerging tenant-in-common (TIC) market, forcing demand for such investments to outweigh the current supply of TIC offerings. Investors seeking deferral of capital gains are ...

Smith, Jared Steven

2005-01-01T23:59:59.000Z

213

Project Management for the Acquisition of Capital Assets  

Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

The purpose of this Manual is to provide requirements and guidance to Department of Energy (DOE) employees, including National Nuclear Security Administration (NNSA) employees on the planning and acquisition of capital assets. Does not cancel other directives.

2003-03-28T23:59:59.000Z

214

UNITED STATES AIR FORCE OUTSIDE THE NATIONAL CAPITAL REGION  

E-Print Network [OSTI]

program in order to reduce Federal employee's contribution to traffic congestion and air pollutionUNITED STATES AIR FORCE OUTSIDE THE NATIONAL CAPITAL REGION PUBLIC TRANSPORTATION BENEFIT PROGRAM): ____________ City (Residence): __________________________State: _______________ Zip Code: ________________ Air Force

215

Job Maintenance and Capital Development Fund (North Carolina)  

Broader source: Energy.gov [DOE]

The Job Maintenance and Capital Development Fund provides annual grants to businesses which are located in Development Tier I counties. The Fund is intended to encourage the retention of...

216

Essays on the real and financial allocation of capital  

E-Print Network [OSTI]

This dissertation consists of three papers studying how firms allocate real and financial capital, and how taxes, the labor market and asymmetric information affect these allocation decisions. The first paper studies the ...

Ramírez Verdugo, Arturo

2006-01-01T23:59:59.000Z

217

Video Installation Design: Appropriation and Assemblage As Projection Surface Geometry  

E-Print Network [OSTI]

This area of research focuses on the use of video projections in the context of fine art. Emphasis is placed on creating a unique video installation work that incorporates assemblage and appropriation as a means to develop multiple complex...

Weaver, Timothy A.

2010-07-14T23:59:59.000Z

218

Defense Energy Support Center: Installation Energy Commodity Business Unit  

Broader source: Energy.gov [DOE]

Presentation—given at the Spring 2009 Federal Utility Partnership Working Group (FUPWG) meeting—discusses the Defense Energy Support Center's (DESC's) Installation Energy Commodity Business Unit (CBU) including its intent, commitment, pilot project, lessons learned, and impending barriers.

219

New Jersey SmartStart Buildings- Direct Install Program  

Broader source: Energy.gov [DOE]

The Direct Install program offers turn-key energy efficiency solutions to qualified industrial and commercial customers that, with some exceptions, have a peak electricity demand of 150 kilowatts ...

220

Seeing solar on campus : a visible photovoltaic installation on campus  

E-Print Network [OSTI]

This paper presents a methodology for selecting a site on the MIT campus for a visible solar photovoltaic installation. Visibility, solar exposure, advertising potential, aesthetics, interactivity and direct or important ...

Guarda, Daniel Jair Alves

2006-01-01T23:59:59.000Z

Note: This page contains sample records for the topic "average installed capital" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


221

North Shore Gas – Single Family Direct Install (Illinois)  

Broader source: Energy.gov [DOE]

Owners of single-family homes, condos, townhomes and two-flats may be eligible for a free installation of new programmable thermostats, pipe insulation, showerheads, and faucet aerators through...

222

Consider Installing Turbulators on Two- and Three-Pass Firetube...  

Broader source: Energy.gov (indexed) [DOE]

tip sheet outlines the benefits of turbulators on firetube boilers as part of optimized steam systems. STEAM TIP SHEET 25 Consider Installing Turbulators on Two- and Three-Pass...

223

Venture Capital Fund Performance and the IPO Market  

E-Print Network [OSTI]

). For example, Cochrane, 2000, Quigley and Woodward, 2003 and Hwang, Quigley and Woodward, 2005, infer aggregate information about the performance of private equity investing using data on the returns to individual venture capital projects. Peng, 2001, Chen... , Baeirl and Kaplan, 2002, Woodward and Hall, 2004, and Hwang, Quigley and Woodward, 2005 use a repeat valuation model to construct an index of venture capital from which overall industry performance may be inferred. A problem with these studies...

McKenzie, Michael; Janeway, William

2008-01-01T23:59:59.000Z

224

Performance Testing of Window Installation and Flashing Details  

E-Print Network [OSTI]

and proposed installation practices incorporating new flashing materials. This paper focuses specifically on the installation practices relating to windows with mounting fins or flanges. REVIEW OF CURRENT PRACTICES AND ATTITUDES Interviews with builders... into two categories based on the how the flashing and the rough opening is treated. g167g32 2-Dimensional Methods: using flashing to extend protection around the perimeter of the window flanges on to the face of the sheathing, and g167g32 3...

Weston, T. A.; Herrin, J.

2002-01-01T23:59:59.000Z

225

Installation of a high-precision Kirsten Hacker  

E-Print Network [OSTI]

Installation of a high-precision BPM in BC3 Kirsten Hacker 20-03-07 #12;BPM installed in BC2=T3*c dE/E=D/R16 EBPM T1 T2 T3 ~300mm 3um position resolution -> 1e-5 Energy resoution!!! BPM BPM #12;BPM for the Bunch Compressors beam stripline vacuumstripline vacuumStripline Vacuum Beam beam tapering

226

Renewable Energy Opportunities at the Kanto Installations, Japan  

SciTech Connect (OSTI)

This document provides an overview of renewable resource development potential at the U.S. Army installations in the Kanto region in Japan, which includes Camp Zama, Yokohama North Dock, Sagamihara Family Housing Area (SFHA), Sagami General Depot, and Akasaka Press Center. This effort focuses on grid-connected generation of electricity from renewable energy sources and also on ground source heat pumps for heating and cooling buildings. The effort was funded by the Huntsville Army Corps of Engineers, and includes the development of a methodology for renewable resource assessment at Army installations located on foreign soil. The methodology is documented in Renewable Energy Assessment Methodology for Japanese OCONUS Army Installations. The site visit to the Kanto installations took place on April 5 and 6, 2010. At the current time, there are some renewable technologies that show economic potential. Because of siting restrictions and the small size of these installations, development of most renewable energy technologies will likely be limited to Camp Zama. Project feasibility is based on installation-specific resource availability and energy costs and projections based on accepted life-cycle cost methods. Development of any renewable energy project will be challenging, as it will require investigation into existing contractual obligations, new contracts that could be developed, the legality of certain partnerships, and available financing avenues, which involves the U.S. Forces Japan (USFJ), the Government of Japan (GOJ), and a number of other parties on both sides. The Army will not be able to implement a project without involvement and approval from the other services and multiple levels of Japanese government. However, implementation of renewable energy projects could be an attractive method for GOJ to reduce greenhouse gas emissions and lower annual utility payments to USFJ. This report recommends projects to pursue and offers approaches to use. The most promising opportunities include waste-to-energy and ground source heat pumps. Solar photovoltaics (PV) may also prove successful. Other resources were found to be insufficient on the Kanto installations.

Solana, Amy E.; Horner, Jacob A.; Russo, Bryan J.; Gorrissen, Willy J.; Kora, Angela R.; Weimar, Mark R.; Hand, James R.; Orrell, Alice C.; Williamson, Jennifer L.

2010-09-24T23:59:59.000Z

227

Renewable Energy Assessment Methodology for Japanese OCONUS Army Installations  

SciTech Connect (OSTI)

Since 2005, Pacific Northwest National Laboratory (PNNL) has been asked by Installation Management Command (IMCOM) to conduct strategic assessments at selected US Army installations of the potential use of renewable energy resources, including solar, wind, geothermal, biomass, waste, and ground source heat pumps (GSHPs). IMCOM has the same economic, security, and legal drivers to develop alternative, renewable energy resources overseas as it has for installations located in the US. The approach for continental US (CONUS) studies has been to use known, US-based renewable resource characterizations and information sources coupled with local, site-specific sources and interviews. However, the extent to which this sort of data might be available for outside the continental US (OCONUS) sites was unknown. An assessment at Camp Zama, Japan was completed as a trial to test the applicability of the CONUS methodology at OCONUS installations. It was found that, with some help from Camp Zama personnel in translating and locating a few Japanese sources, there was relatively little difficulty in finding sources that should provide a solid basis for conducting an assessment of comparable depth to those conducted for US installations. Project implementation will likely be more of a challenge, but the feasibility analysis will be able to use the same basic steps, with some adjusted inputs, as PNNL’s established renewable resource assessment methodology.

Solana, Amy E.; Horner, Jacob A.; Russo, Bryan J.; Gorrissen, Willy J.; Kora, Angela R.; Weimar, Mark R.; Hand, James R.; Orrell, Alice C.; Williamson, Jennifer L.

2010-08-30T23:59:59.000Z

228

E-Print Network 3.0 - applicable aux installations Sample Search...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

and Thermal Simulation (Windows Only) 6-10 Chapter 7 Installing PTC Application Manager (UNIX Only... ) Installing PTC Application Manager 7-2 Configuring PTC Application...

229

Supersonic Air Jets Preserve Tree Roots in Underground Pipeline Installation1  

E-Print Network [OSTI]

Supersonic Air Jets Preserve Tree Roots in Underground Pipeline Installation1 Rob Gross 2 trenching operations for pipeline installation. Although mechanical soil excavation using heavy equipment

Standiford, Richard B.

230

Exploration for geothermal resources in the Capital District of New York. Volume 1. Final report  

SciTech Connect (OSTI)

Water chemistry, gas analyses, and geophysical methods including gravity and magnetic surveys, microseismic monitoring, and temperature gradient measurements were used in the Capital District area to evaluate the potential for a hydrothermal geothermal system. Water and gas chemistries provided indirect indicators, and temperature gradients provided direct indications of a geothermal system. Gravity results were supportive of gradient and chemistry data, but seismic and magnetic work have thus far provided little information on the potential system. Gradients throughout the area ranged from an average background value of about 10/sup 0/C/km to a high of roughly 44/sup 0/C/km. The highest gradient values, the most unusual water chemistries and largest carbon dioxide exhalations occur along the Saratoga and McGregor faults between Saratoga Springs and Schenectady, and indicate a good potential for a usable hydrothermal geothermal system at depth.

Not Available

1981-11-01T23:59:59.000Z

231

Light weight underground pipe or cable installing device  

SciTech Connect (OSTI)

This invention pertains to a light weight underground pipe or cable installing device adapted for use in a narrow and deep operating trench. More particularly this underground pipe installing device employs a pair of laterally movable gates positioned adjacent the bottom of the operating trench where the earth is more solid to securely clamp the device in the operating trench to enable it to withstand the forces exerted as the actuating rod is forced through the earth from the so-called operating trench to the target trench. To accommodate the laterally movable gates positioned adjacent the bottom of the narrow pipe installing device, a pair of top operated double-acting rod clamping jaws, operated by a hydraulic cylinder positioned above the actuating rod are employed.

Schosek, W. O.

1985-01-08T23:59:59.000Z

232

Fact #744: September 10, 2012 Average New Light Vehicle Price...  

Broader source: Energy.gov (indexed) [DOE]

Light Vehicle Price In 2011 the average used light vehicle price was 36% higher than in 1990, while the average new light vehicle price was 67% higher than it was in 1990. The...

233

Fact #835: August 25, Average Historical Annual Gasoline Pump...  

Energy Savers [EERE]

5: August 25, Average Historical Annual Gasoline Pump Price, 1929-2013 Fact 835: August 25, Average Historical Annual Gasoline Pump Price, 1929-2013 When adjusted for inflation,...

234

Fact #835: August 25, 2014 Average Annual Gasoline Pump Price...  

Broader source: Energy.gov (indexed) [DOE]

5: August 25, 2014 Average Annual Gasoline Pump Price, 1929-2013 - Dataset Fact 835: August 25, 2014 Average Annual Gasoline Pump Price, 1929-2013 - Dataset Excel file with...

235

Fact #849: December 1, 2014 Midsize Hybrid Cars Averaged 51%...  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

9: December 1, 2014 Midsize Hybrid Cars Averaged 51% Better Fuel Economy than Midsize Non-Hybrid Cars in 2014 Fact 849: December 1, 2014 Midsize Hybrid Cars Averaged 51% Better...

236

Estimates of energy consumption by building type and end use at U.S. Army installations  

SciTech Connect (OSTI)

This report discusses the use of LBNL`s End-use Disaggregation Alogrithm (EDA) to 12 US Army installations nationwide in order to obtain annual estimates of electricity use for all major building types and end uses. The building types include barrack, dining hall, gymnasium, administration, vehicle maintenance, hospital, residential, warehouse, and misc. Up to 8 electric end uses for each type were considered: space cooling, ventilation (air handling units, fans, chilled and hot water pumps), cooking, misc./plugs, refrigeration, exterior and interior lighting, and process loads. Through building simulations, we also obtained estimates of natural gas space heating energy use. Average electricity use for these 12 installations and Fort Hood are: HVAC, misc., and indoor lighting end uses consumed the most electricity (28, 27, and 26% of total[3.8, 3.5, and 3.3 kWh/ft{sup 2}]). Refrigeration, street lighting, exterior lighting, and cooking consumed 7, 7, 3, and 2% of total (0.9, 0.9, 0.4, and 0.3 kWh/ft{sup 2})

Konopacki, S.J.; Akbari, H.

1996-08-01T23:59:59.000Z

237

Potential for Photovoltaic Solar Installation in Non-Irrigated Corners of Center Pivot Irrigation Fields in the State of Colorado  

SciTech Connect (OSTI)

The State of Colorado expressed an interest in assessing the potential for photovoltaic (PV) solar installations on non-irrigated corners of center-pivot irrigation (CPI) fields throughout the state. Using aerial imagery and irrigated land data available from the Colorado Water Conservation Board, an assessment of potentially suitable sites was produced. Productivity estimates were calculated from that assessment. The total area of non-irrigated corners of CPI fields in Colorado was estimated to be 314,674 acres, which could yield 223,418 acres of installed PV panels assuming 71% coverage in triangular plots. The total potential annual electricity production for the state was estimated to be 56,821 gigawatt hours (GWH), with an average of 1.3 GWH per available plot.

Roberts, B.

2011-07-01T23:59:59.000Z

238

Sustainability Research & Development Consortium for DoD Installations  

E-Print Network [OSTI]

Sustainability Research & Development Consortium for DoD Installations Warner College of Natural the growing need for sustainability planning, imple- mentation, and facilitation on United States military bases. CEMML is already a proven global provider of re- search and sustainable management of natural

239

RFAR installation for Buildings 703, 712, 747, 748 and 1163  

SciTech Connect (OSTI)

This document is to certify the installation and testing of the Radio Fire Alarm Reporting box (RFAR). The Hanford Fire Dept. will be notified of troubles via RFAR. The document outlines prerequisites, necessary equipment, and the fire alarm system test to insure the system is operating correctly.

Ferry, M.

1995-12-31T23:59:59.000Z

240

T-729: Mozilla Code Installation Through Holding Down Enter  

Broader source: Energy.gov [DOE]

Attackers can exploit this issue by enticing an unsuspecting victim into viewing and interacting with a malicious Web page. An attacker may be able to exploit this issue to bypass a confirmation dialog and install an arbitrary add-on. This may aid in further attacks.

Note: This page contains sample records for the topic "average installed capital" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


241

Sun N1 Grid Engine 6.1 Installation Guide  

E-Print Network [OSTI]

Sun N1 Grid Engine 6.1 Installation Guide Sun Microsystems, Inc. 4150 Network Circle Santa Clara, CA 95054 U.S.A. Part No: 820­0697 May 2007 #12;Copyright 2007 Sun Microsystems, Inc. 4150 Network Circle, Santa Clara, CA 95054 U.S.A. All rights reserved. Sun Microsystems, Inc. has intellectual

242

Decidability Results for Dynamic Installation of Compensation Handlers  

E-Print Network [OSTI]

that in a simple -like calculus with static compen- sations the termination of a process is decidable Zavattaro Focus Team, University of Bologna & INRIA, Italy Abstract. Dynamic compensation installation compensations, showing that process termination is decidable for parallel and replacing compensations while

Paris-Sud XI, Université de

243

WARNING: Improper installation, adjustment, alteration, service or maintenance can  

E-Print Network [OSTI]

INSTALLATION AND OPERATING INSTRUCTIONS FOR AUTOMATIC INSTANTANEOUS TYPE WATER HEATERS FOR USE WITH NATURAL(02.01)AL #12;2 This well engineered, gas water heater has all the fea- tures a water heater should have on the water heater, giving you control over your hot water energy use. Each time you turn off your hot water

Kostic, Milivoje M.

244

Systems study of drilling for installation of geothermal heat pumps  

SciTech Connect (OSTI)

Geothermal, or ground-source, heat pumps (GHP) are much more efficient than air-source units such as conventional air conditioners. A major obstacle to their use is the relatively high initial cost of installing the heat-exchange loops into the ground. In an effort to identify drivers which influence installation cost, a number of site visits were made during 1996 to assess the state-of-the-art in drilling for GHP loop installation. As an aid to quantifying the effect of various drilling-process improvements, we constructed a spread-sheet based on estimated time and material costs for all the activities required in a typical loop-field installation. By substituting different (improved) values into specific activity costs, the effect on total project costs can be easily seen. This report contains brief descriptions of the site visits, key points learned during the visits, copies of the spread-sheet, recommendations for further work, and sample results from sensitivity analysis using the spread-sheet.

Finger, J.T.; Sullivan, W.N.; Jacobson, R.D.; Pierce, K.G.

1997-09-01T23:59:59.000Z

245

FORSCOM installation characterization and ranking for water efficiency improvement  

SciTech Connect (OSTI)

On March 11, 1994, President Clinton signed Executive Order 12902-Energy Efficiency and Water Conservation at Federal Facilities. Section 302 of the Executive Order calls for energy and water prioritization surveys of federal facilities to be conducted. The surveys will be used to establish priorities for conducting comprehensive facility audits. In response to the requirements of the Executive Order, the U.S. Army Forces Command (FORSCOM) has tasked Pacific Northwest Laboratory (PNL) to initiate a broad study of the water savings potential at each of its major installations. This report provides an assessment of the water, sewer, energy (for hot water production and pumping), and associated cost savings potential at ten of the major FORSCOM installations. This assessment is meant to be a {open_quotes}first pass{close_quotes} estimate of the water savings potential, to assist FORSCOM in prioritizing installations for detailed water audits and potential water efficient retrofits. In addition, the end uses (toilets, sinks, showerheads, irrigation, etc.) with the greatest water savings potential are identified at each installation. This report is organized in the following manner. Following this Introduction, Section 2 provides important background information pertaining to the water analysis. Section 3 describes the methodology employed in the analysis, and Section 4 summarizes the study results. Section 5 prioritizes the installations based on both water/sewer savings and cost associated with water, sewer, and energy savings. Section 6 provides recommendations on where to start detailed water audits, as well as other recommendations. References are listed in Section 7. The appendices provide specific information on the analysis results and methodology, along with a discussion of special issues.

Fitzpatrick, Q.K.; McMordie, K.L.; Di Massa, F.V. [and others

1995-05-01T23:59:59.000Z

246

EA-1655: Berkeley Lab Laser Accelerator (BELLA) Laser Acquisition, Installation and Use for Research and Development  

Broader source: Energy.gov [DOE]

Berkeley Lab Laser Accelerator (BELLA) Laser Acquisition, Installation and Use for Research and Development

247

Data based on the MSc class of 2010/11 Number of all MSc students: Average age  

E-Print Network [OSTI]

HSBC RBC Global Asset Management Sage Capital Global Shell Sungard Swiss Finance Corporation The Bank

Weyde, Tillman

248

Measuring and managing intellectual capital in the U.S. aerospace industry  

E-Print Network [OSTI]

"Intellectual capital" has been heralded in business journals as an important component for successful business development in today's economy. Intellectual capital consists of knowledge-based assets -- including people, ...

Siegel, Lawrence R

2004-01-01T23:59:59.000Z

249

Program management systems for the semiconductor processing capital equipment supply chain  

E-Print Network [OSTI]

The Capital Equipment Procurement group of Intel Corporation is responsible for developing and procuring the semiconductor processing capital equipment that is used throughout all of the company's development and manufacturing ...

Chandler, Thomas B. (Thomas Brian), 1970-

2004-01-01T23:59:59.000Z

250

The New York Business Development Corporation (NYBDC) Loans for Working Capital (New York)  

Broader source: Energy.gov [DOE]

The New York Business Development Corporation (NYBDC) Loans for Working Capital provides working capital for long-term needs, repayable over three to seven years. The program works with partner...

251

Venture Capital and private equity in India : systems analysis and development framework  

E-Print Network [OSTI]

Venture Capital (VC) has been an important driver of innovation, entrepreneurship and economic growth in the U.S. and around the world for the past few decades. The astounding success of Venture Capital prompted various ...

Surineni, Shravan Kumar

2012-01-01T23:59:59.000Z

252

FACILITIES ENGINEER WEST CHICAGO Execute capital projects for manufacturing facilities and utilities systems: scope development, cost  

E-Print Network [OSTI]

facilities and utilities systems: scope development, cost estimation, system design, equipment sizing ENGINEERING: Lead capital project design, development and execution for facility and utility capital Utilities systems (Vacuum, Hydraulics, Waste Water treatment, etc.) o Buildings and grounds, including

Heller, Barbara

253

may 7, 2011 vol xlvi no 19 EPW Economic & Political Weekly12 The IMF, Capital Controls  

E-Print Network [OSTI]

for the global coordination of those controls. A fter more than a decade of advo- cating the liberalisation that the IMF has come to recognise the limits of capital account liberalisation and the merits of capital

Tufts University

254

Interaction model of private equity and venture capital developing factors in Chile and Latin America  

E-Print Network [OSTI]

Private equity and venture capital (PE/VC) are efficient resource allocation systems that provide equity capital to selected entrepreneurs, industries or firms that contribute to advance the economic welfare of society. ...

Sevil Esteban, Ángel

2012-01-01T23:59:59.000Z

255

University of Nebraska Lincoln Capital Project Planning Decision Flowchart  

E-Print Network [OSTI]

originator and CPC provides general sizing, implications, cost estimate, etc. for project. Consistency of continuing? Yes No1 Project proposal with costs estimates provided to Chancellor and Senior AdministrativeUniversity of Nebraska ­ Lincoln Capital Project Planning Decision Flowchart 1. Program Concept 2

Farritor, Shane

256

Tax policies, vintage capital, and exit and entry of plants  

E-Print Network [OSTI]

caused by different types of shocks. The simulation method used here is linear approximation. My results show that in the steady-state economy, given a fixed level of gov- ernment expenditure and a zero property tax rate, the capital-income tax rate...

Chang, Shao-Jung

2006-04-12T23:59:59.000Z

257

Brief description of Valuing Intellectual Capital, Multinationals and Taxhavens  

E-Print Network [OSTI]

methods for measuring the value of intangible assets within their company Author is an emeritus professor at Stanford University and a leading consultant on IP valuation Valuing Intellectual Capital provides readers that illustrates how large corporations need to measure the worth of their intangible assets. Each method

Pratt, Vaughan

258

Watershed Management: An Evaluation of the Mullen Slough Capital Improvement  

E-Print Network [OSTI]

and Action Plan King County, Washington, USA by Fiona Murray McNair B.Sc. McGill University 1995 RESEARCH Capital Improvement Project Study and Action Plan, King County, Washington, USA Examining Committee:_______________________________ #12;iii Abstract A watershed management process, for a sub-basin in King County, WA is examined

259

2013 Snapshot of NGSI Human Capital Development and Future Roadmap  

SciTech Connect (OSTI)

Since its creation in 2008, the Human Capital Development (HCD) subprogram of NNSA s Next Generation Safeguards Initiative (NGSI) has been striving to develop sustainable academic and technical programs that support the recruitment, education, training, and retention of the next generation of international safeguards professionals. This effort endeavors to develop additional human resources to equip a new cadre of safeguards and nonproliferation experts to meet the needs of both the United States and the International Atomic Energy Agency (IAEA) for decades to come, specifically in response to data that indicates that 82% of the 2009 safeguards experts at U.S. Laboratories will have left the workforce within 15 years. This paper provides an update on the status of the program since its last presentation at the INMM Annual Meeting in 2010, including strengthened and integrated efforts in the areas of graduate and post-doctoral fellowships, young and mid-career professional support, additional short safeguards coursework, and expanded university engagement. In particular, the paper will cover the NGSI Human Capital Roadmap currently being developed in safeguards and nonproliferation education, training, and knowledge retention. The NGSI Human Capital Roadmap aims to provide additional data points and metrics on where the human capital demand lies, which disciplines and skill sets are needed in the field, and how NGSI HCD can best address these issues to meet future demand.

Scholz, Melissa A [ORNL] [ORNL; Poe, Sarah M [ORNL] [ORNL; Dewji, Shaheen A [ORNL] [ORNL; Finklea, Lauren R [ORNL] [ORNL

2013-01-01T23:59:59.000Z

260

South African SKA Project Human Capital Development Programme  

E-Print Network [OSTI]

D and MSc Project List 1. Radio Astronomy Science 1.1 Radio Astronomy Science - PhD topics Project Title Project Description Qualifications and Skills Required Link to MeerKAT and/ or SKA Science Supervisor (andSouth African SKA Project Human Capital Development Programme Call for applications for 2014 Ph

Jarrett, Thomas H.

Note: This page contains sample records for the topic "average installed capital" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


261

Valuation of Capital Structure using Simulation Yevgeny Goncharov  

E-Print Network [OSTI]

] and Leland [L] we model securities in capital structure as derivatives on the asset value of the company bankruptcies that hurt many financial institutions( En- ron and MCI) and led to a search for better techniques different stature if the company goes bankrupt or liquidates. The division of Company property

Goncharov, Yevgeny

262

Genetic and Economic Interaction in the Formation of Human Capital.  

E-Print Network [OSTI]

Genetic and Economic Interaction in the Formation of Human Capital. The Case of Obesity Pietro by changes in the incentives to invest. I take the model to the data using the Avon Longitudinal Study regulation of food intake, and shed light on the interdependence between genes and economic choices regarding

Mateo, Jill M.

263

The Value of New Jersey's Ecosystem Services and Natural Capital  

E-Print Network [OSTI]

The Value of New Jersey's Ecosystem Services and Natural Capital Robert Costanza Matthew Wilson services are are mainly provided by ecosystems. Examples of ecosystem services ("ecoservices") include of ecoservices in a variety of locations using a variety of valuation methods and applies them to New Jersey

264

Optics and Fluid Dynamics Department Intellectual Capital Accounts 1998  

E-Print Network [OSTI]

Optics and Fluid Dynamics Department Intellectual Capital Accounts 1998 Resources, production and results RIS�-R-1108(EN) Risø National Laboratory Optics and Fluid Dynamics Department Building 128 P for optical information storage, · novel schemes for spatial cryptography, and · new models for surface

265

New Technology, Human Capital and Growth for Developing Countries.  

E-Print Network [OSTI]

New Technology, Human Capital and Growth for Developing Countries. Cuong Le Van, Manh-Hung Nguyen country with three sectors in economy: con- sumption goods, new technology, and education. Productivity of the con- sumption goods sector depends on new technology and skilled labor used for production of the new

Paris-Sud XI, Université de

266

Technical Analysis of Installed Micro-Combined Heat and Power Fuel-Cell System  

SciTech Connect (OSTI)

Combined heat and power fuel cell systems (CHP-FCSs) provide consistent electrical power and hot water with greater efficiency and lower emissions than alternative sources. These systems can be used either as baseload, grid-connected, or as off-the-grid power sources. This report presents a technical analysis of 5 kWe CHP-FCSs installed in different locations in the U.S. At some sites as many as five 5 kWe system is used to provide up to 25kWe of power. Systems in this power range are considered “micro”-CHP-FCS. To better assess performance of micro-CHP-FCS and understand their benefits, the U.S. Department of Energy worked with ClearEdge Power to install fifteen 5-kWe PBI high temperature PEM fuel cells (CE5 models) in the commercial markets of California and Oregon. Pacific Northwest National Laboratory evaluated these systems in terms of their economics, operations, and technical performance. These units were monitored from September 2011 until June 2013. During this time, about 190,000 hours of data were collected and more than 17 billion data points were analyzed. Beginning in July 2013, ten of these systems were gradually replaced with ungraded systems (M5 models) containing phosphoric acid fuel cell technology. The new units were monitored until June 2014 until they went offline because ClearEdge was bought by Doosan at the time and the new manufacturer did not continue to support data collection and maintenance of these units. During these two phases, data was collected at once per second and data analysis techniques were applied to understand behavior of these systems. The results of this analysis indicate that systems installed in the second phase of this demonstration performed much better in terms of availability, consistency in generation, and reliability. The average net electrical power output increased from 4.1 to 4.9 kWe, net heat recovery from 4.7 to 5.4 kWth, and system availability improved from 94% to 95%. The average net system electric efficiency, average net heat recovery efficiency, and overall net efficiency of the system increased respectively from 33% to 36%, from 38% to 41%, and from 71% to 76%. The temperature of water sent to sit however reduced by about 16% from 51?C to 43 ?C. This was a control strategy and the temperature can be controlled depending on building heat demands. More importantly, the number of shutdowns and maintenance events required to keep the systems running at the manufacturer’s rated performance specifications were substantially reduced by about 76% (for 8 to 10 units running over a one-year period). From July 2012 to June 2013, there were eight CE5 units in operation and a total of 134 scheduled and unscheduled shutdowns took place. From July 2013 to June 2014, between two to ten units were in operation and only 32 shutdowns were reported (all unscheduled). In summary, the number of shutdowns reduced from 10 shutdowns per month on average for eight CE5units to an average of 2.7 shutdowns per month for M5 units (between two to ten units).

Brooks, Kriston P.; Makhmalbaf, Atefe

2014-10-31T23:59:59.000Z

267

Does Corporate Social Responsibility Affect the Cost of Capital? * Sadok El Ghoul  

E-Print Network [OSTI]

capital for a large sample of U.S. firms. Using several approaches to estimate firms' ex ante costDoes Corporate Social Responsibility Affect the Cost of Capital? * Sadok El Ghoul University the effect of corporate social responsibility (CSR) on the cost of equity capital for a large sample of U

Saskatchewan, University of

268

CAMPUS PLANNING COMMITTEE PLANNING AND REVIEW PROCESS FOR MAJOR CAPITAL PROJECTS  

E-Print Network [OSTI]

, efficient and cost effective manner; · Maximize the capital dollars available to UCSB from all sources with other campuses for scarce resources.); · Optimize the use of capital dollars; · Establish a clear; whose total cost is over $400,000. #12;B. 5-YEAR STATE-FUNDED MAJOR CAPITAL IMPROVEMENT PROGRAM

California at Santa Barbara, University of

269

Capital accumulation and non-renewable energy resources: a special functions case  

E-Print Network [OSTI]

2007/9 Capital accumulation and non-renewable energy resources: a special functions case Agustin PĂ©rez-Barahona #12;CORE DISCUSSION PAPER 2007/9 Capital accumulation and non-renewable energy resources the implications of assuming different technologies for physical capital accumulation and consumption. More

Nesterov, Yurii

270

The Role of Venture Capital in Building Technology Companies in the Ottawa Region  

E-Print Network [OSTI]

The Role of Venture Capital in Building Technology Companies in the Ottawa Region John Callahan in building technology companies in the Ottawa region. We find four distinct periods of venture capital are relatively distinct in terms of the investors present in the market, the companies seeking capital

Callahan, John

271

Technology and Education: Putting it in context A summary of the final Capital Research Project report  

E-Print Network [OSTI]

Technology and Education: Putting it in context A summary of the final Capital Research Project-00593093,version1-13May2011 #12;1 Box 1: Capital Project Capital (Curriculum and Pedagogy in Technology media and research claims such as these about the educational value of new technologies. But often

Paris-Sud XI, Université de

272

average kinetic energy: Topics by E-print Network  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

energy by kinetic averaging Pierre-Emmanuel Jabin Ecole Normale Sup-Landau energy for two dimensional divergence free fields ap- pearing in the gradient theory of...

273

average power high: Topics by E-print Network  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Simultaneous Power Fluctuation and Average Power Minimization during Nano-CMOS Behavioral Synthesis Computer Technologies and Information Sciences Websites Summary: conversion 6....

274

LOW-HIGH VALUES FOR PETROLEUM AVERAGE INVENTORY RANGES (MILLION...  

Gasoline and Diesel Fuel Update (EIA)

ENERGY INFORMATION ADMINISTRATION LOW-HIGH VALUES FOR PETROLEUM AVERAGE INVENTORY RANGES (MILLION BARRELS) FILE UPDATED April 2004 Line Month Low High Number Product Name Geography...

275

Idaho National Engineering Laboratory installation roadmap document. Revision 1  

SciTech Connect (OSTI)

The roadmapping process was initiated by the US Department of Energy`s office of Environmental Restoration and Waste Management (EM) to improve its Five-Year Plan and budget allocation process. Roadmap documents will provide the technical baseline for this planning process and help EM develop more effective strategies and program plans for achieving its long-term goals. This document is a composite of roadmap assumptions and issues developed for the Idaho National Engineering Laboratory (INEL) by US Department of Energy Idaho Field Office and subcontractor personnel. The installation roadmap discusses activities, issues, and installation commitments that affect waste management and environmental restoration activities at the INEL. The High-Level Waste, Land Disposal Restriction, and Environmental Restoration Roadmaps are also included.

Not Available

1993-05-30T23:59:59.000Z

276

Technical oversight for installation of TNX piezometers, Final Report  

SciTech Connect (OSTI)

Science Applications International Corporation was tasked under subcontract C002025P to provide technical oversight for the drilling of one pilot borehole, and the drilling and installation of five piezometers in the TNX Area Swamp. The work was performed in accordance with the Statement of Work in Task Order Proposal No. ER39-129 dated August 6, 1996. This report describes the activities associated with the performance of the task.

Pidcoe, W.W. Jr. [Westinghouse Savannah River Company, Aiken, SC (United States)

1997-06-05T23:59:59.000Z

277

Open PV Project: Unlocking PV Installation Data (Brochure)  

SciTech Connect (OSTI)

This brochure summarizes the Open PV Project, a collaborative effort of government, industry, and the public to compile a comprehensive database of PV installations in the United States. The brochure outlines the purpose and history of the project as well as the main capabilities and benefits of the online Open PV tool. The brochure also introduces how features of the tool are used, and it describes the sources and characteristics of Open PV's data and data collection processes.

Not Available

2012-04-01T23:59:59.000Z

278

Solar space and water heating system installed at Charlottesville, Virginia  

SciTech Connect (OSTI)

The solar energy system located at David C. Wilson Neuropsychiatric Hospital, Charlottesville, Virginia, consists of 88 single glazed, Sunworks Solector copper base plate collector modules; hot water coils in the hot air ducts; a domestic hot water (DHW) preheat tank; a 3,000 gallon concrete urethane-insulated storage tank and other miscellaneous components. This report includes extracts from the site files, specifications, drawings, installation, operation and maintenance instructions.

Greer, Charles R.

1980-09-01T23:59:59.000Z

279

Solar heating system installed at Jackson, Tennessee. Final report  

SciTech Connect (OSTI)

The solar energy heating system installed at the Coca-Cola Bottling Works in Jackson, Tennessee is described. The system consists of 9480 square feet of Owens-Illinois evacuated tubular solar collectors with attached specular cylindrical reflectors and will provide space heating for the 70,000 square foot production building in the winter, and hot water for the bottle washing equipment the remainder of the year. Component specifications and engineering drawings are included. (WHK)

None

1980-10-01T23:59:59.000Z

280

CSP'960H/CSP-960S Installation Guide  

E-Print Network [OSTI]

CSP'960H/CSP-960S Installation Guide 4-634-979-01 TM Read First! 1^00 - 3lG - 755; #12;CSP-960H/CSP CSP-960H only) J Sony CDU926S CD-R Drive Unit User's Guide Use this manual as a guide to help you. If all the items are not found, please contact your Sony dealer before proceeding. G CSP-960H/960S CD

Kleinfeld, David

Note: This page contains sample records for the topic "average installed capital" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


281

New BPM installed in BC2 Jan Hauschildt  

E-Print Network [OSTI]

New BPM installed in BC2 Compact! Thanks to: Jan Hauschildt Dirk Noelle Silke Vilcins Holger 30 40 time (ns) Volts chicane BPM scope traces for 12-16 MV/m gradient Scope in tunnel ~ 150 um resolution => 5*10-4 resolution #12;-20 -15 -10 -5 0 0.9 1 1.1 1.2 1.3 1.4 1.5 BPM slope phase (deg

282

Install Electric Vehicle Charging at Work | Department of Energy  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE: AlternativeEnvironment, Safety andGeothermalGreen linkInitiatives InitiativesResearchInstall

283

Empirically Derived Strength of Residential Roof Structures for Solar Installations.  

SciTech Connect (OSTI)

Engineering certification for the installation of solar photovoltaic (PV) modules on wood roofs is often denied because existing wood roofs do not meet structural design codes. This work is intended to show that many roofs are actually sufficiently strong given the conservatism in codes, documented allowable strengths, roof structure system effects, and beam composite action produced by joist-sheathing interaction. This report provides results from a testing program to provide actual load carrying capacity of residential rooftops. The results reveal that the actual load carrying capacity of structural members and systems tested are significantly stronger than allowable loads provided by the International Residential Code (IRC 2009) and the national structural code found in Minimum Design Loads for Buildings and Other Structures (ASCE 7-10). Engineering analysis of residential rooftops typically ignores the system affects and beam composite action in determining rooftop stresses given a potential PV installation. This extreme conservatism combined with conservatism in codes and published allowable stress values for roof building materials (NDS 2012) lead to the perception that well built homes may not have adequate load bearing capacity to enable a rooftop PV installation. However, based on the test results presented in this report of residential rooftop structural systems, the actual load bearing capacity is several times higher than published values (NDS 2012).

Dwyer, Stephen F.; Sanchez, Alfred; Campos, Ivan A.; Gerstle, Walter H.

2014-12-01T23:59:59.000Z

284

Environmental assessment: Kotzebue Wind Installation Project, Kotzebue, Alaska  

SciTech Connect (OSTI)

The DOE is proposing to provide financial assistance to the Kotzebue Electric Association to expand its existing wind installation near Kotzebue, Alaska. Like many rural Alaska towns, Kotzebue uses diesel-powered generators to produce its electricity, the high cost of which is currently subsidized by the Alaska State government. In an effort to provide a cost effective and clean source of electricity, reduce dependence on diesel fuel, and reduce air pollutants, the DOE is proposing to fund an experimental wind installation to test commercially available wind turbines under Arctic conditions. The results would provide valuable information to other Alaska communities experiencing similar dependence on diesel-powered generators. The environmental assessment for the proposed wind installation assessed impacts to biological resources, land use, electromagnetic interference, coastal zone, air quality, cultural resources, and noise. It was determined that the project does not constitute a major Federal action significantly affecting the quality of the human environment. Therefore, the preparation of an environmental impact statement is not required, and DOE has issued a Finding of No Significant Impact.

NONE

1998-05-01T23:59:59.000Z

285

Design and installation manual for thermal energy storage  

SciTech Connect (OSTI)

The purpose of this manual is to provide information on the design and installation of thermal energy storage in active solar systems. It is intended for contractors, installers, solar system designers, engineers, architects, and manufacturers who intend to enter the solar energy business. The reader should have general knowledge of how solar heating and cooling systems operate and knowledge of construction methods and building codes. Knowledge of solar analysis methods such as f-Chart, SOLCOST, DOE-1, or TRNSYS would be helpful. The information contained in the manual includes sizing storage, choosing a location for the storage device, and insulation requirements. Both air-based and liquid-based systems are covered with topics on designing rock beds, tank types, pump and fan selection, installation, costs, and operation and maintenance. Topics relevant to latent heat storage include properties of phase-change materials, sizing the storage unit, insulating the storage unit, available systems, and cost. Topics relevant to heating domestic water include safety, single- and dual-tank systems, domestic water heating with air- and liquid-based space heating systems, and stand alone domestics hot water systems. Several appendices present common problems with storage systems and their solutions, heat transfer fluid properties, economic insulation thickness, heat exchanger sizing, and sample specifications for heat exchangers, wooden rock bins, steel tanks, concrete tanks, and fiberglass-reinforced plastic tanks.

Cole, R L; Nield, K J; Rohde, R R; Wolosewicz, R M

1980-01-01T23:59:59.000Z

286

On average sampling restoration of Piranashvilitype harmonizable processes  

E-Print Network [OSTI]

; time shifted sam- pling; Piranashvili­, Lo`eve­, Karhunen­ harmonizable stochastic process; weakly.olenko@latrobe.edu.au, poganj@pfri.hr Abstract: The harmonizable Piranashvili ­ type stochastic pro- cesses are approximated stationary stochastic process; local averages; average sampling reconstruction. 1. Introduction

Paris-Sud XI, Université de

287

The global warming signal is the average of  

E-Print Network [OSTI]

, uncertainty in the isopycnal diffusivity causes uncertainty of up to 50% in the global warming signalThe global warming signal is the average of years 70-80 in the increasing CO2 run minus the average represent significant uncertainty in the global warming signal (Fig. 5). The differences at high latitudes

Jones, Peter JS

288

averaged energy minimization: Topics by E-print Network  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

averaged energy minimization First Page Previous Page 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Next Page Last Page Topic Index 1 Averaged Energy...

289

STATE OF CALIFORNIA AREA WEIGHTED AVERAGE CALCULATION WORKSHEET: RESIDENTIAL  

E-Print Network [OSTI]

STATE OF CALIFORNIA AREA WEIGHTED AVERAGE CALCULATION WORKSHEET: RESIDENTIAL CEC-WS-2R (Revised 08/09) CALIFORNIA ENERGY COMMISSION Area Weighted Average Calculation Worksheet WS-2R Residential (Page 1 of 1) Site/Time: ____________________ HERS Provider: __________________ 2008 Residential Compliance Forms August 2009 This worksheet should

290

Higher-order averaging, formal series and numerical integration II  

E-Print Network [OSTI]

systems of ordinary differential equations with d 1 non- resonant constant frequencies. Formal series frequency and four resonant fast frequencies. Keywords and sentences: Averaging, high-order averaging, quasi Schumann, 35170 Bruz, France. Email: Philippe.Chartier@inria.fr Konputazio Zientziak eta A. A. Saila

Murua, Ander

291

Averaged dynamics of ultra-relativisitc charged particles beams  

E-Print Network [OSTI]

In this thesis, we consider the suitability of using the charged cold fluid model in the description of ultra-relativistic beams. The method that we have used is the following. Firstly, the necessary notions of kinetic theory and differential geometry of second order differential equations are explained. Then an averaging procedure is applied to a connection associated with the Lorentz force equation. The result of this averaging is an affine connection on the space-time manifold. The corresponding geodesic equation defines the averaged Lorentz force equation. We prove that for ultra-relativistic beams described by narrow distribution functions, the solutions of both equations are similar. This fact justifies the replacement of the Lorentz force equation by the simpler {\\it averaged Lorentz force equation}. After this, for each of these models we associate the corresponding kinetic model, which are based on the Vlasov equation and {\\it averaged Vlasov equation} respectively. The averaged Vlasov equation is simpler than the original Vlasov equation. This fact allows us to prove that the differential operation defining the averaged charged cold fluid equation is controlled by the {\\it diameter of the distribution function}, by powers of the {\\it energy of the beam} and by the time of evolution $t$. We show that the Vlasov equation and the averaged Vlasov equation have similar solutions, when the initial conditions are the same. Finally, as an application of the {\\it averaged Lorentz force equation} we re-derive the beam dynamics formalism used in accelerator physics from the Jacobi equation of the averaged Lorentz force equation.

Ricardo Gallego Torromé

2012-06-19T23:59:59.000Z

292

LIFE Cost of Electricity, Capital and Operating Costs  

SciTech Connect (OSTI)

Successful commercialization of fusion energy requires economic viability as well as technical and scientific feasibility. To assess economic viability, we have conducted a pre-conceptual level evaluation of LIFE economics. Unit costs are estimated from a combination of bottom-up costs estimates, working with representative vendors, and scaled results from previous studies of fission and fusion plants. An integrated process model of a LIFE power plant was developed to integrate and optimize unit costs and calculate top level metrics such as cost of electricity and power plant capital cost. The scope of this activity was the entire power plant site. Separately, a development program to deliver the required specialized equipment has been assembled. Results show that LIFE power plant cost of electricity and plant capital cost compare favorably to estimates for new-build LWR's, coal and gas - particularly if indicative costs of carbon capture and sequestration are accounted for.

Anklam, T

2011-04-14T23:59:59.000Z

293

Social capital and participatory slum upgrading in Bangkok, Thailand  

E-Print Network [OSTI]

t i o n …………………… … … … … … … . . 39 Figure 3.2: A summary of the commun i t y partici p a t i o n paradig m ………………. . 42 Figure 3.3: The hierarc h i c a l oper ation of social capital …………………………... 49 Figure 3.4: Indicat o r s of social capital... the Baan Mankong (“secure housing”) programme in Bangkok. The Baan Mankong progra m me uses commun i t y par tic i p a t i o n to meet the housin g needs of the urban poor, with finan c i a l assis t a nc e from the state . Sin ce starti n g in 2003...

Archer, Diane

2010-02-09T23:59:59.000Z

294

Replacing the Rare Earth Intellectual Capital  

SciTech Connect (OSTI)

The rare earth crisis slowly evolved during a 10 to 15 year period beginning in the mid-1980s, when the Chinese began to export mixed rare earth concentrates. In the early 1990s, they started to move up the supply chain and began to export the individual rare earth oxides and metals. By the late 1990s the Chinese exported higher value products, such as magnets, phosphors, polishing compounds, catalysts; and in the 21st century they supplied finished products including electric motors, computers, batteries, liquid-crystal displays (LCDs), TVs and monitors, mobile phones, iPods and compact fluorescent lamp (CFL) light bulbs. As they moved to higher value products, the Chinese slowly drove the various industrial producers and commercial enterprises in the US, Europe and Japan out of business by manipulating the rare earth commodity prices. Because of this, the technically trained rare earth engineers and scientists who worked in areas from mining to separations, to processing to production, to manufacturing of semifinished and final products, were laid-off and moved to other fields or they retired. However, in the past year the Chinese have changed their philosophy of the 1970s and 1980s of forming a rare earth cartel to control the rare earth markets to one in which they will no longer supply the rest of the world (ROW) with their precious rare earths, but instead will use them internally to meet the growing demand as the Chinese standard of living increases. To this end, they have implemented and occasionally increased export restrictions and added an export tariff on many of the high demand rare earth elements. Now the ROW is quickly trying to start up rare earth mines, e.g. Molycorp Minerals in the US and Lynas Corp. in Australia, to cover this shortfall in the worldwide market, but it will take about five years for the supply to meet the demand, even as other mines in the ROW become productive. Unfortunately, today there is a serious lack of technically trained personnel to bring the entire rare earth industry, from mining to original equipment manufacturers (OEM), up to full speed in the next few years. Accompanying this decline in technical expertise, innovation and new products utilizing rare earth elements has slowed dramatically, and it may take a decade or more to recapture America's leading role in technological advancements of rare earth containing products. Before the disruption of the US rare earth industry, about 25,000 people were employed in all aspects of the industry from mining to OEM. Today, only about 1,500 people are employed in these fields. The ratio of non-technically trained persons to those with college degrees in the sciences or engineering varies from about 8 to 1 to about 4 to 1, depending on the particular area of the industry. Assuming an average of 6 to 1, the number of college degree scientists and engineers has decreased from about 4,000 to 250 employed today. In the magnetic industry the approximate numbers are: 6,000 total with 750 technically trained people in the 1980s to 500 totally employed today of which 75 have degrees. The paucity of scientists and engineers with experience and/or training in the various aspects of production and commercialization of the rare earths is a serious limitation to the ability of the US to satisfy its own needs for materials and technologies (1) to maintain our military strength and posture, (2) to assume leadership in critical energy technologies, and (3) to bring new consumer products to the marketplace. The lack of experts is of even greater national importance than the halting in the 1990s and the recent restart of the mining/benification/separation effort in the US; and thus governmental intervention and support for at least five to 10 years will be required to ameliorate this situation. To respond quickly, training programs should be established in conjunction with a national research center at an educational institution with a long tradition in multiple areas of rare earth and other critical elements research and technology. This center should

Gschneidner, Jr., Karl

2011-04-01T23:59:59.000Z

295

Some Observations on Energy Efficiency and Capital Cost  

E-Print Network [OSTI]

SO~ffi OBSERVATIONS ON ENERGY EFFICIENCY AND CAPITAL COST William F. Kenney Exxon Chemical Company Florham Park, ABSTRACT The usual expectation in the process indus tries is that improved energy efficiency requires increased investment..., ACS Symposium Series ~. (3) Exxon Chemical Internal Studies. ACKNOWLEDGEMENT The author is grateful to Exxon Chemical for permission to publish this study. Particular thanks go to A. P. Durso and W. J. O'Brien of the Central Engineering...

Kenney, W. F.

1982-01-01T23:59:59.000Z

296

Design approaches to achieve competitive LMFBR capital costs  

SciTech Connect (OSTI)

Through analysis of the essential functional elements of an LMFBR, numerous ways were found to simplify system design, reduce the size of components and equipment, and eliminate some components and systems. The projected capital cost per net kW of this design is competitive with that of current PWRs. RandD programs and the construction and operation of CRBRP now are needed to prove out the features of this new design.

Arnold, W.H.; Ehrman, C.S.; Sharbaugh, J.E.; Young, W.H.

1982-09-01T23:59:59.000Z

297

Program and Project Management for the Acquisition of Capital Assets  

Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

To provide the Department of Energy (DOE), including the National Nuclear Security Administration, with project management direction for the acquisition of capital assets with the goal of delivering projects on schedule, within budget, and fully capable of meeting mission performance, safeguards and security, and environmental, safety, and health standards. Cancels DOE O 413.3. Canceled by DOE O 413.3A Chg 1.

2011-05-18T23:59:59.000Z

298

Program and Project Management for the Acquisition of Capital Assets  

Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

The Order provides project management direction for the acquisition of capital assets that are delivered on schedule, within budget, and capable of meeting mission performance and environmental safety and health standards. The page change incorporates requirements of DOE-STD-1189-2008, Integration of Safety into the Design Process, mandatory for Hazard Category 1, 2 and 3 nuclear facilities. Cancels DOE O 413.3. Canceled by DOE O 413.3B dated 11-29-10.

2006-07-28T23:59:59.000Z

299

MissionPoint Capital Partners | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data CenterFranconia, Virginia: Energy Resources Jump to:46 -Energieprojekte GmbHMilo, Maine: EnergyMinnErgyTexas: EnergyMissionPoint Capital

300

Morgan Stanley Capital Grp Inc | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data CenterFranconia, Virginia: Energy Resources Jump to:46 -Energieprojekte3 Climate ZoneMontrose,Stanley Capital Grp Inc Jump to: navigation,

Note: This page contains sample records for the topic "average installed capital" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


301

India-Capital Markets Climate Initiative | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data CenterFranconia, Virginia: Energy Resources Jump to:46 - 429 Throttled (bot load) Error 429 Throttled (bot load) Throttled -DIR]Capital

302

Process Integration: Designing for Energy, Capital and Operability  

E-Print Network [OSTI]

INTEGRATED COMPUTER SOFTWARE FOR PROCESS DESIGN METHODOLOGY Rajeev Gautam Union Carbide Corporation South Charleston, West Virginia A computer-aided system for synthesis, simulation and optimization of heat exchanger networks will be described... as expert users. It uses a micro-computer based environment to provide an integrated system with an interactive graphics process engineering interface. Process Integration: Designing for Energy, Capital and Operability Bodo Linnhoff University...

Linnhoff, B.

303

Oil/gas separator for installation at burning wells  

SciTech Connect (OSTI)

An oil/gas separator is disclosed that can be utilized to return the burning wells in Kuwait to production. Advantageously, a crane is used to install the separator at a safe distance from the well. The gas from the well is burned off at the site, and the oil is immediately pumped into Kuwait`s oil gathering system. Diverters inside the separator prevent the oil jet coming out of the well from reaching the top vents where the gas is burned. The oil falls back down, and is pumped from an annular oil catcher at the bottom of the separator, or from the concrete cellar surrounding the well.

Alonso, C.T.; Bender, D.A.; Bowman, B.R. [and others

1991-12-31T23:59:59.000Z

304

Oil/gas separator for installation at burning wells  

DOE Patents [OSTI]

An oil/gas separator is disclosed that can be utilized to return the burning wells in Kuwait to production. Advantageously, a crane is used to install the separator at a safe distance from the well. The gas from the well is burned off at the site, and the oil is immediately pumped into Kuwait's oil gathering system. Diverters inside the separator prevent the oil jet coming out of the well from reaching the top vents where the gas is burned. The oil falls back down, and is pumped from an annular oil catcher at the bottom of the separator, or from the concrete cellar surrounding the well.

Alonso, C.T.; Bender, D.A.; Bowman, B.R.; Burnham, A.K.; Chesnut, D.A.; Comfort, W.J. III; Guymon, L.G.; Henning, C.D.; Pedersen, K.B.; Sefcik, J.A.; Smith, J.A.; Strauch, M.S.

1993-03-09T23:59:59.000Z

305

Installing a Subsurface Drip Irrigation System for Row Crops  

E-Print Network [OSTI]

. The manifold can be placed at the soil surface or buried. B-6151 7/04 Installing a Subsurface Drip Irrigation System for Row Crops Juan Enciso* *Assistant Professor and Extension Agricultural Engineer, The Texas A&M University System. Figure 1. Typical layout... of a drip irrigation system. Main Field block Flushing valve Valve Flushing manifold Water source Supplying manifold Lateral Tape injection The injector consists of a roll that holds the tape and a shank that opens the soil to bury the tape (Figs. 3...

Enciso, Juan

2004-09-07T23:59:59.000Z

306

Foldtrack Installation in C-110 | Department of Energy  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr MayAtmospheric Optical Depth7-1D: Vegetation ProposedUsing ZirconiaPolicyFeasibilityFieldMinds" |beam damageFlyer,Installation in

307

Installing a Light Source 'Racetrack' | Department of Energy  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE:Year in3.pdfEnergy Health andofIan Kalin About32 InspectionSummaryInstalling a Light Source

308

Installing and Maintaining a Home Solar Electric System | Department of  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE:Year in3.pdfEnergy Health andofIan Kalin About32 InspectionSummaryInstalling a Light

309

Installing and Operating an Efficient Swimming Pool Pump | Department of  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE:Year in3.pdfEnergy Health andofIan Kalin About32 InspectionSummaryInstalling a LightEnergy

310

Oil/gas separator for installation at burning wells  

DOE Patents [OSTI]

An oil/gas separator is disclosed that can be utilized to return the burning wells in Kuwait to production. Advantageously, a crane is used to install the separator at a safe distance from the well. The gas from the well is burned off at the site, and the oil is immediately pumped into Kuwait's oil gathering system. Diverters inside the separator prevent the oil jet coming out of the well from reaching the top vents where the gas is burned. The oil falls back down, and is pumped from an annular oil catcher at the bottom of the separator, or from the concrete cellar surrounding the well.

Alonso, Carol T. (Orinda, CA); Bender, Donald A. (Dublin, CA); Bowman, Barry R. (Livermore, CA); Burnham, Alan K. (Livermore, CA); Chesnut, Dwayne A. (Pleasanton, CA); Comfort, III, William J. (Livermore, CA); Guymon, Lloyd G. (Livermore, CA); Henning, Carl D. (Livermore, CA); Pedersen, Knud B. (Livermore, CA); Sefcik, Joseph A. (Tracy, CA); Smith, Joseph A. (Livermore, CA); Strauch, Mark S. (Livermore, CA)

1993-01-01T23:59:59.000Z

311

Designing, selecting and installing a residential ground-source heat pump system  

SciTech Connect (OSTI)

It's a compelling proposition: Use the near-constant-temperature heat underground to heat and cool your home and heat domestic water, slashing your energy bills. Yet despite studies demonstrating significant energy savings from ground-source heat pump (GSHP) systems, their adoption has been hindered by high upfront costs. Fewer than 1% of US homes use a GSHP system. However, compared to a minimum-code-compliant conventional space-conditioning system, when properly designed and installed, a GSHP retrofit at current market prices offers simple payback of 4.3 years on national average, considering existing federal tax credits. Most people understand how air-source heat pumps work: they move heat from indoor air to outdoor air when cooling and from outdoor air to indoor air when heating. The ground-source heat pump operates on the same principle, except that it moves heat to or from the ground source instead of outdoor air. The ground source is usually a vertical or horiontal ground heat exchanger. Because the ground usually has a more favorable temperature than ambient air for the heating and cooling operation of the vapor-compression refrigeration cycle, GSHP sysems can operate with much higher energy efficiencies than air-source heat pump systems when properly designed and installed. A GSHP system used in a residual building typically provides space conditioning and hot water and comprises three major components: a water-source heat pump unit designed to operate at a wider range of entering fluid temperatures (typically from 30 F to 110 F, or 1 C to 43 C) than a conventional water-source heat pump unit; a ground heat exchanger (GHX); and distribution systems to deliver hot water to the storage tank and heating or cooling to the conditioned rooms. In most residual GSHP systems, the circulation pumps and associated valves are integrated with the heat pump to circulate the heat-carrier fluid (water or aqueous antifreeze solution) through the heat pump and the GHX. A recent assessment indicates that if 20% of US homes replaced their existing space-conditioning and water-heating systems with properly designed, installed and operated state-of-the-art GSHP systems, it would yield significant benefits each year. These include 0.8 quad British thermal units (Btu) of primary energy savings, 54.3 million metric tons of CO{sub 2} emission reductions, $10.4 billion in energy cost savings and 43.2 gigawatts of reduction in summer peak electrical demand.

Hughes, Patrick [ORNL; Liu, Xiaobing [ORNL; Munk, Jeffrey D [ORNL

2010-01-01T23:59:59.000Z

312

Averaging Spacetime: Where do we go from here?  

E-Print Network [OSTI]

The construction of an averaged theory of gravity based on Einstein's General Relativity is very difficult due to the non-linear nature of the gravitational field equations. This problem is further exacerbated by the difficulty in defining a mathematically precise covariant averaging procedure for tensor fields over differentiable manifolds. Together, these two ideas have been called the averaging problem for General Relativity. In the first part of the talk, an attempt to review some the various approaches to this problem will be given, highlighting strengths, weaknesses, and commonalities between them. In the second part of the talk, an argument will be made, that if one wishes to develop a well-defined averaging procedure, one may choose to parallel transport along geodesics with respect to the Levi-Cevita connection or, use the Weitzenb\\"ock connection and ensure the transportation is independent of path. The talk concludes with some open questions to generate further discussion.

R. J. van den Hoogen

2010-04-15T23:59:59.000Z

313

averaged cross sections: Topics by E-print Network  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

14 15 16 17 18 19 20 21 22 23 24 25 Next Page Last Page Topic Index 1 Relations between fusion cross sections and average angular momenta Nuclear Theory (arXiv) Summary: We study...

314

averaged cross section: Topics by E-print Network  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

14 15 16 17 18 19 20 21 22 23 24 25 Next Page Last Page Topic Index 1 Relations between fusion cross sections and average angular momenta Nuclear Theory (arXiv) Summary: We study...

315

THE UNIVERSITY OF RHODE ISLAND FRINGE BENEFIT AVERAGE RATE  

E-Print Network [OSTI]

THE UNIVERSITY OF RHODE ISLAND FRINGE BENEFIT AVERAGE RATE FY 2015 Allocation Cost or Classified.2% URI Budget & Financial Planning Office 9.17.14 Office:fringebenefits:office of sponsored projects: FY2015 Allocation #12;

Rhode Island, University of

316

average effective dose: Topics by E-print Network  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

field theory, Chern-Simons theory is discussed in detail. M. Reuter 1996-02-04 2 Is dark energy an effect of averaging? CERN Preprints Summary: The present standard model of...

317

Probabilistic Wind Speed Forecasting using Ensembles and Bayesian Model Averaging  

E-Print Network [OSTI]

is to issue deterministic forecasts based on numerical weather prediction models. Uncertainty canProbabilistic Wind Speed Forecasting using Ensembles and Bayesian Model Averaging J. Mc discretization than is seen in other weather quantities. The prevailing paradigm in weather forecasting

Washington at Seattle, University of

318

Abstract Interpretation for Worst and Average Case Analysis  

E-Print Network [OSTI]

energy usage whilst bounding the average number of requests waiting to be served. PRISM is used phase extracts a control flow graph ­ for some classes of language this may already involve an abstract

Di Pierro, Alessandra

319

Does anyone have access to 2012 average residential rates by...  

Open Energy Info (EERE)

Does anyone have access to 2012 average residential rates by utility company? I'm seeing an inconsistency between the OpenEI website and EIA 861 data set. Home > Groups > Utility...

320

average glandular dose: Topics by E-print Network  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

doses and cancer rates to the workers m the first Soviet atom-bomb facility, near 2 Chelyabinsk and 4,600 at the plutonium sep- aration plant. If we allow for an average work...

Note: This page contains sample records for the topic "average installed capital" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


321

areally averaged heat: Topics by E-print Network  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Chulwoo Jung; Christoph Lehner 2014-02-18 56 The Fallacy of Averages University of Kansas - KU ScholarWorks Summary: of component variables as well, we found that ignoring...

322

From average case complexity to improper learning [Extended Abstract  

E-Print Network [OSTI]

is that the standard reduc- tions from NP-hard problems do not seem to apply in this context. There is essentially only.1145/2591796.2591820. Keywords Hardness of improper learning, DNFs, Halfspaces, Average Case complexity, CSP problems, Resolution

Linial, Nathan "Nati"

323

average power optical: Topics by E-print Network  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

systems, Multiple Subcarrier Strohmer, Thomas 3 June 1, 2000 Vol. 25, No. 11 OPTICS LETTERS 859 16.2-W average power from a diode-pumped Materials Science Websites...

324

Installing OMERO.searcher Local Client version 1.3 in MacOSX  

E-Print Network [OSTI]

the license 5. Install Enthought. It is Python distribution with a GUI, integrated code editor and IPython #12;console that comes with numpy+scipy+matplotlib+PIL+ipython. Before installing the software we need to make

Murphy, Robert F.

325

Flavor Physics Data from the Heavy Flavor Averaging Group (HFAG)  

DOE Data Explorer [Office of Scientific and Technical Information (OSTI)]

The Heavy Flavor Averaging Group (HFAG) was established at the May 2002 Flavor Physics and CP Violation Conference in Philadelphia, and continues the LEP Heavy Flavor Steering Group's tradition of providing regular updates to the world averages of heavy flavor quantities. Data are provided by six subgroups that each focus on a different set of heavy flavor measurements: B lifetimes and oscillation parameters, Semi-leptonic B decays, Rare B decays, Unitarity triangle parameters, B decays to charm final states, and Charm Physics.

326

Partial Averaging Near a Resonance in Planetary Dynamics  

E-Print Network [OSTI]

Following the general numerical analysis of Melita and Woolfson (1996), I showed in a recent paper that a restricted, planar, circular planetary system consisting of Sun, Jupiter and Saturn would be captured in a near (2:1) resonance when one would allow for frictional dissipation due to interplanetary medium (Haghighipour, 1998). In order to analytically explain this resonance phenomenon, the method of partial averaging near a resonance was utilized and the dynamics of the first-order partially averaged system at resonance was studied. Although in this manner, the finding that resonance lock occurs for all initial relative positions of Jupiter and Saturn was confirmed, the first-order partially averaged system at resonance did not provide a complete picture of the evolutionary dynamics of the system and the similarity between the dynamical behavior of the averaged system and the main planetary system held only for short time intervals. To overcome these limitations, the method of partial averaging near a resonance is extended to the second order of perturbation in this paper and a complete picture of dynamical behavior of the system at resonance is presented. I show in this study that the dynamics of the second-order partially averaged system at resonance resembles the dynamical evolution of the main system during the resonance lock in general, and I present analytical explanations for the evolution of the orbital elements of the main system while captured in resonance.

Nader Haghighipour

1999-02-03T23:59:59.000Z

327

Simulating environmental changes due to marine hydrokinetic energy installations.  

SciTech Connect (OSTI)

Marine hydrokinetic (MHK) projects will extract energy from ocean currents and tides, thereby altering water velocities and currents in the site's waterway. These hydrodynamics changes can potentially affect the ecosystem, both near the MHK installation and in surrounding (i.e., far field) regions. In both marine and freshwater environments, devices will remove energy (momentum) from the system, potentially altering water quality and sediment dynamics. In estuaries, tidal ranges and residence times could change (either increasing or decreasing depending on system flow properties and where the effects are being measured). Effects will be proportional to the number and size of structures installed, with large MHK projects having the greatest potential effects and requiring the most in-depth analyses. This work implements modification to an existing flow, sediment dynamics, and water-quality code (SNL-EFDC) to qualify, quantify, and visualize the influence of MHK-device momentum/energy extraction at a representative site. New algorithms simulate changes to system fluid dynamics due to removal of momentum and reflect commensurate changes in turbulent kinetic energy and its dissipation rate. A generic model is developed to demonstrate corresponding changes to erosion, sediment dynamics, and water quality. Also, bed-slope effects on sediment erosion and bedload velocity are incorporated to better understand scour potential.

Jones, Craig A. (Sea Engineering Inc., Santa Cruz, CA); James, Scott Carlton; Roberts, Jesse Daniel (Sandia National Laboratories, Albuquerque, NM); Seetho, Eddy

2010-08-01T23:59:59.000Z

328

THE LOW-TEMPERATURE THRESHOLD FOR PINK SALMON EGGS IN RELATION TO A PROPOSED HYDROELECTRIC INSTALLATION  

E-Print Network [OSTI]

THE LOW-TEMPERATURE THRESHOLD FOR PINK SALMON EGGS IN RELATION TO A PROPOSED HYDROELECTRIC INSTALLATION JACK E. BAILEY' AND DALE R. EVANS' ABSTRACT A proposed hydroelectric installation in southeastern hydroelectric installation could result in temperatures as low as 4.5 0 C during spawning and initial incubation

329

PIBASE.ligands installation guide. ver 200905 Fred P. Davis, HHMI-JFRC  

E-Print Network [OSTI]

SQL interface, a software package is also available that enables a web interface to the database. The database Web interface To install the web interface to the PIBASE.ligands database, you must first have a working PIBASE web server installed. Once you have the PIBASE web interface installed, download the PIBASE

Eddy, Sean

330

Solar Energy Development onSolar Energy Development on DoD Installations in the  

E-Print Network [OSTI]

Solar Energy Development onSolar Energy Development on DoD Installations in the Mojave & Colorado/how solar can contribute to installation level energy· Assess whether/how solar can contribute to installation-level energy security · Recommend policy and programmatic modifications to accelerate solar

331

STATE OF CALIFORNIA HSPP/PSPP INSTALLATION; COOLING COIL AIRFLOW & FAN WATT DRAW TEST  

E-Print Network [OSTI]

STATE OF CALIFORNIA HSPP/PSPP INSTALLATION; COOLING COIL AIRFLOW & FAN WATT DRAW TEST CEC- CF-4R TESTING CF-4R-MECH-22 HSPP/PSPP Installation; Cooling Coil Airflow & Fan Watt Draw Test (Page 1 of 3) Site of a Static Pressure Probe (HSPP), and Permanently installed Static Pressure Probe (PSPP) in the supply plenum

332

STATE OF CALIFORNIA HSPP/PSPP INSTALLATION; COOLING COIL AIRFLOW & FAN WATT DRAW TEST  

E-Print Network [OSTI]

STATE OF CALIFORNIA HSPP/PSPP INSTALLATION; COOLING COIL AIRFLOW & FAN WATT DRAW TEST CEC-CF-6R/PSPP Installation; Cooling Coil Airflow & Fan Watt Draw Test (Page 1 of 3) Site Address: Enforcement Agency: Permit), and Permanently installed Static Pressure Probe (PSPP) in the supply plenum When the Certificate of Compliance (CF

333

AN EXAMINATION OF BICYCLE COUNTS AND SPEEDS ASSOCIATED WITH THE INSTALLATION OF BIKE LANES  

E-Print Network [OSTI]

AN EXAMINATION OF BICYCLE COUNTS AND SPEEDS ASSOCIATED WITH THE INSTALLATION OF BIKE LANES IN ST An Examination of Bicycle Counts and Speeds Associated with the Installation of Bike Lanes in St. Petersburg It is assumed that installation of bicycle facilities will result in an increase in the number of bicyclists

North Carolina at Chapel Hill, University of

334

Average Soil Water Retention Curves Measured by Neutron Radiography  

SciTech Connect (OSTI)

Water retention curves are essential for understanding the hydrologic behavior of partially-saturated porous media and modeling flow transport processes within the vadose zone. In this paper we report direct measurements of the main drying and wetting branches of the average water retention function obtained using 2-dimensional neutron radiography. Flint sand columns were saturated with water and then drained under quasi-equilibrium conditions using a hanging water column setup. Digital images (2048 x 2048 pixels) of the transmitted flux of neutrons were acquired at each imposed matric potential (~10-15 matric potential values per experiment) at the NCNR BT-2 neutron imaging beam line. Volumetric water contents were calculated on a pixel by pixel basis using Beer-Lambert s law after taking into account beam hardening and geometric corrections. To remove scattering effects at high water contents the volumetric water contents were normalized (to give relative saturations) by dividing the drying and wetting sequences of images by the images obtained at saturation and satiation, respectively. The resulting pixel values were then averaged and combined with information on the imposed basal matric potentials to give average water retention curves. The average relative saturations obtained by neutron radiography showed an approximate one-to-one relationship with the average values measured volumetrically using the hanging water column setup. There were no significant differences (at p < 0.05) between the parameters of the van Genuchten equation fitted to the average neutron radiography data and those estimated from replicated hanging water column data. Our results indicate that neutron imaging is a very effective tool for quantifying the average water retention curve.

Cheng, Chu-Lin [ORNL; Perfect, Edmund [University of Tennessee, Knoxville (UTK); Kang, Misun [ORNL; Voisin, Sophie [ORNL; Bilheux, Hassina Z [ORNL; Horita, Juske [Texas Tech University (TTU); Hussey, Dan [NIST Center for Neutron Research (NCRN), Gaithersburg, MD

2011-01-01T23:59:59.000Z

335

Data based on the MSc class of 2010/11 Number of all MSc students: Average age  

E-Print Network [OSTI]

Commerzbank Goldman Sachs HSBC J.P. Morgan Rabobank RS Platou Sapien Capital Siam Commercial Bank FINANCEMSc

Weyde, Tillman

336

Program and Project Management Policy for the Planning, Programming, Budgeting, and Acquisition of Capital Assets  

Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

To establish Department of Energy (DOE) program and project management policy for the planning, programming, budgeting, and acquisition of capital assets consistent with the following Office of Management and Budget (OMB) circulars: OMB Circular A-11, Part 3, Planning, Budgeting, and Acquisition of Capital Assets, and the supplement to Part 3, Capital Programming Guide; OMB Circular A-123; OMB Circular A-127; and OMB Circular A-130. Does not cancel other directives. Canceled by DOE N 251.99

2000-06-10T23:59:59.000Z

337

Retrofit SCADA installation combines SCADA and process control functions  

SciTech Connect (OSTI)

When Gulf States Utilities Company`s (now part of Entergy Operations, Inc.) River Bend Nuclear Plant, decided to add a closed cooling water system for the plant service water, a new SCADA system was required. Previously the normal service water system shared common cooling towers and flume with the plant`s circulating water system. Closing the system required a new cooling tower with pumps and heat exchangers to be constructed in a remote location. Existing equipment in the area was controlled via a multichannel tone SCADA system that did not have sufficient spare capacity for control of the new components. This paper will discuss how a new SCADA system was designed and installed, that also included process control. It will also address the operational experience to date.

Moffitt, T.O. [Entergy Operations, Inc., St. Francisville, LA (United States)

1995-09-01T23:59:59.000Z

338

Solar space heating installed at Kansas City, Kansas. Final report  

SciTech Connect (OSTI)

The solar energy system was constructed with the new 48,800 square feet warehouse to heat the warehouse area of about 39,000 square feet while the auxiliary energy system heats the office area of about 9800 square feet. The building is divided into 20 equal units, and each has its own solar system. The modular design permits the flexibility of combining multiple units to form offices or warehouses of various size floor areas as required by a tenant. Each unit has 20 collectors which are mounted in a single row. The collectors, manufactured by Solaron Corporation, are double glazed flat plate collectors with a gross area of 7800 ft/sup 2/. Air is heated either through the collectors or by the electric resistance duct coils. No freeze protection or storage is required for this system. Extracts from the site files, specifications, drawings, installation, operation and maintenance instructions are included.

Not Available

1981-05-01T23:59:59.000Z

339

Gas turbine nozzle vane insert and methods of installation  

DOE Patents [OSTI]

A pair of hollow elongated insert bodies are disposed in one or more of the nozzle vane cavities of a nozzle stage of a gas turbine. Each insert body has an outer wall portion with apertures for impingement-cooling of nozzle wall portions in registration with the outer wall portion. The insert bodies are installed into the cavity separately and spreaders flex the bodies toward and to engage standoffs against wall portions of the nozzle whereby the designed impingement gap between the outer wall portions of the insert bodies and the nozzle wall portions is achieved. The spreaders are secured to the inner wall portions of the insert bodies and the bodies are secured to one another and to the nozzle vane by welding or brazing.

Miller, William John (Simpsonville, SC); Predmore, Daniel Ross (Clifton Park, NY); Placko, James Michael (West Chester, OH)

2002-01-01T23:59:59.000Z

340

Monte Carlo Simulation Tool Installation and Operation Guide  

SciTech Connect (OSTI)

This document provides information on software and procedures for Monte Carlo simulations based on the Geant4 toolkit, the ROOT data analysis software and the CRY cosmic ray library. These tools have been chosen for its application to shield design and activation studies as part of the simulation task for the Majorana Collaboration. This document includes instructions for installation, operation and modification of the simulation code in a high cyber-security computing environment, such as the Pacific Northwest National Laboratory network. It is intended as a living document, and will be periodically updated. It is a starting point for information collection by an experimenter, and is not the definitive source. Users should consult with one of the authors for guidance on how to find the most current information for their needs.

Aguayo Navarrete, Estanislao; Ankney, Austin S.; Berguson, Timothy J.; Kouzes, Richard T.; Orrell, John L.; Troy, Meredith D.; Wiseman, Clinton G.

2013-09-02T23:59:59.000Z

Note: This page contains sample records for the topic "average installed capital" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


341

Installation of geosynthetic clay liners at California MSW landfills  

SciTech Connect (OSTI)

The California regulations for liner systems at municipal solid waste (MSW) landfills require that alternatives to the prescriptive federal Subtitle D liner system have a containment capability greater than that of the prescriptive system. Regulators may also require a demonstration that use of the prescriptive system is burdensome prior to approval of an alternative liner design. This paper presents seven case histories of the design and installation of geosynthetic clay liners (GCL) as an alternative to the low-permeability soil component of the prescriptive Subtitle D composite liner system at MSW landfills in California. These case histories cover GCLs from different manufacturers and landfill sites with a wide range of conditions including canyon landfills with slopes as steep as 1H:1V.

Snow, M.; Jesionek, K.S.; Dunn, R.J.; Kavazanjian, E. Jr.

1997-11-01T23:59:59.000Z

342

Information handbook on independent spent fuel storage installations  

SciTech Connect (OSTI)

In this information handbook, the staff of the U.S. Nuclear Regulatory Commission describes (1) background information regarding the licensing and history of independent spent fuel storage installations (ISFSIs), (2) a discussion of the licensing process, (3) a description of all currently approved or certified models of dry cask storage systems (DCSSs), and (4) a description of sites currently storing spent fuel in an ISFSI. Storage of spent fuel at ISFSIs must be in accordance with the provisions of 10 CFR Part 72. The staff has provided this handbook for information purposes only. The accuracy of any information herein is not guaranteed. For verification or for more details, the reader should refer to the respective docket files for each DCSS and ISFSI site. The information in this handbook is current as of September 1, 1996.

Raddatz, M.G.; Waters, M.D.

1996-12-01T23:59:59.000Z

343

Tracking the Sun: The Installed Cost of Photovoltaics in the U.S. from 1998-2007  

E-Print Network [OSTI]

The Installed Cost of Photovoltaics in the U.S. from 1998-The Installed Cost of Photovoltaics in the U.S. from 1998-The Installed Cost of Photovoltaics in the U.S. from 1998-

Wiser, Ryan

2009-01-01T23:59:59.000Z

344

Tracking the Sun II: The Installed Cost of Photovoltaics in the U.S. from 1998-2008  

E-Print Network [OSTI]

The Installed Cost of Photovoltaics in the U.S. from 1998-The Installed Cost of Photovoltaics in the U.S. from 1998-The Installed Cost of Photovoltaics in the U.S. from 1998-

Barbose, Galen L

2010-01-01T23:59:59.000Z

345

Tracking the Sun III; The Installed Cost of Photovoltaics in the United States from 1998-2009  

E-Print Network [OSTI]

The Installed Cost of Photovoltaics in the U.S. from 1998-The Installed Cost of Photovoltaics in the U.S. from 1998-The Installed Cost of Photovoltaics in the U.S. from 1998-

Barbose, Galen

2011-01-01T23:59:59.000Z

346

Tracking the Sun III; The Installed Cost of Photovoltaics in the United States from 1998-2009  

E-Print Network [OSTI]

from 1998-2009 Tracking the Sun III: The Installed Cost ofSystems MW Total Tracking the Sun III: The Installed Cost ofthrough 2009. Tracking the Sun III: The Installed Cost of

Barbose, Galen

2011-01-01T23:59:59.000Z

347

Installation of Window Air Conditioners Page 1 of 2 Virginia Polytechnic Institute and State University No. 5705 Rev.: 3  

E-Print Network [OSTI]

Installation of Window Air Conditioners Page 1 of 2 Virginia Polytechnic Institute and State __________________________________________________________________________________ Subject: Installation of Window Air Conditioners........................................................................................................................................1 1. Purpose To define a policy for installation of window air conditioners that avoids exterior

Buehrer, R. Michael

348

Comparing strategies: State funding of capital projects versus water conservation  

E-Print Network [OSTI]

?new water? is also just as permanent as a reservoir because the old, ine#16;cient plumbing is no longer available. Unless familiar with the billions of gallons of water produced by San Antonio?s or El Paso?s water conservation e orts, one might... of water produced and the time required to have the #30;rst water available would need to be included in any analysis. #31;e purpose of this discussion is not to dismiss the capital projects; it is to suggest that both types of projects must...

Finch, Dr. Calvin

2013-01-01T23:59:59.000Z

349

EM Capital Asset Project List | Department of Energy  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE:Year in Review: TopEnergy DOEDealingVehicle1:Energy Independence & SecurityEM Capital Asset

350

EM Contractors for Capital Asset Projects | Department of Energy  

Office of Environmental Management (EM)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr May Jun Jul(Summary) " ,"ClickPipelinesProvedDecember 2005Department ofDOEDisabilityContractors for Capital Asset Projects EM

351

Updated Capital Cost Estimates for Utility Scale Electricity Generating Plants  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr MayAtmosphericNuclear SecurityTensile Strain Switched Ferromagnetism inS-4500II Field Emission SEM with EDAXUpdated Capital Cost Estimates

352

Office of the Chief Human Capital Officer | Department of Energy  

Broader source: All U.S. Department of Energy (DOE) Office Webpages

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr May Jun Jul(Summary)morphinanInformation InInformation InExplosion Monitoring: InnovationISCNEPA Policy andHuman Capital Officer

353

BlueWave Capital LLC | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Office of InspectorConcentrating SolarElectricEnergyCTBarre BiomassTHIS PAGE ISJumpSphere Corp JumpBlueWave Capital LLC

354

CO2e Capital Limited | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Office of InspectorConcentrating SolarElectricEnergyCTBarreis a city in ChittendenPartners LLC JumpCO2e Capital Limited

355

RockPort Capital Partners (California) | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data CenterFranconia, Virginia:FAQ < RAPID Jump to: navigation, searchVirginia BlueRiverwoods,Rock Sampling DetailsRockPort Capital Partners

356

FreshTracks Capital LP | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home5b9fcbce19 No revision has beenFfe2fb55-352f-473b-a2dd-50ae8b27f0a6Theoretical vsFlintFluxInputDamFreshTracks Capital LP Jump

357

Copy of Capitalized Property RO23_120213_1.xlsx  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr MayAtmospheric Optical Depth7-1D: Vegetation Proposed Newcatalyst phases on &gamma;-Al2O3. | EMSL Coordinatively- EnergyCapitalized

358

Cinergy Capital & Trading, Inc | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home5b9fcbce19 NoPublic Utilities Address: 160Benin:Energy InformationLake SouthChroma ATE IncCimarronCapital & Trading, Inc

359

Clean World Capital A S | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home5b9fcbce19 NoPublic Utilities Address: 160Benin:EnergyWisconsin: Energy Resources JumpSouth Dakota:CleanCleanVitaWorld Capital A

360

Energy and Environmental Capital LLC | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home5b9fcbce19 NoPublic Utilities Address:011-DNA Jump37. It isInformation Contracts (ESPC) Webinar Jump to:S ADataTrustCapital

Note: This page contains sample records for the topic "average installed capital" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


361

Averaged equations for Josephson junction series arrays with LRC load  

E-Print Network [OSTI]

We derive the averaged equations describing a series array of Josephson junctions shunted by a parallel inductor-resistor-capacitor load. We assume that the junctions have negligable capacitance ($\\beta = 0$), and derive averaged equations which turn out to be completely tractable: in particular the stability of both in-phase and splay states depends on a single parameter, $\\del$. We find an explicit expression for $\\delta$ in terms of the load parameters and the bias current. We recover (and refine) a common claim found in the technical literature, that the in-phase state is stable for inductive loads and unstable for capacitive loads.

Kurt Wiesenfeld; James W. Swift

1994-08-26T23:59:59.000Z

362

Safety of Hydrogen Systems Installed in Outdoor Enclosures  

SciTech Connect (OSTI)

The Hydrogen Safety Panel brings a broad cross-section of expertise from the industrial, government, and academic sectors to help advise the U.S. Department of Energy’s (DOE) Fuel Cell Technologies Office through its work in hydrogen safety, codes, and standards. The Panel’s initiatives in reviewing safety plans, conducting safety evaluations, identifying safety-related technical data gaps, and supporting safety knowledge tools and databases cover the gamut from research and development to demonstration and deployment. The Panel’s recent work has focused on the safe deployment of hydrogen and fuel cell systems in support of DOE efforts to accelerate fuel cell commercialization in early market applications: vehicle refueling, material handling equipment, backup power for warehouses and telecommunication sites, and portable power devices. This paper resulted from observations and considerations stemming from the Panel’s work on early market applications. This paper focuses on hydrogen system components that are installed in outdoor enclosures. These enclosures might alternatively be called “cabinets,” but for simplicity, they are all referred to as “enclosures” in this paper. These enclosures can provide a space where a flammable mixture of hydrogen and air might accumulate, creating the potential for a fire or explosion should an ignition occur. If the enclosure is large enough for a person to enter, and ventilation is inadequate, the hydrogen concentration could be high enough to asphyxiate a person who entered the space. Manufacturers, users, and government authorities rely on requirements described in codes to guide safe design and installation of such systems. Except for small enclosures used for hydrogen gas cylinders (gas cabinets), fuel cell power systems, and the enclosures that most people would describe as buildings, there are no hydrogen safety requirements for these enclosures, leaving gaps that must be addressed. This paper proposes that a technical basis be developed to enable code bodies to write requirements for the range of enclosures from the smallest to the largest.

Barilo, Nick F.

2013-11-06T23:59:59.000Z

363

Experimental Evaluation of Installed Cooking Exhaust Fan Performance  

SciTech Connect (OSTI)

The installed performance of cooking exhaust fans was evaluated through residential field experiments conducted on a sample of 15 devices varying in design and other characteristics. The sample included two rear downdraft systems, two under-cabinet microwave over range (MOR) units, three different installations of an under-cabinet model with grease screens across the bottom and no capture hood, two devices with grease screens covering the bottom of a large capture hood (one under-cabinet, one wall-mount chimney), four under-cabinet open hoods, and two open hoods with chimney mounts over islands. Performance assessment included measurement of airflow and sound levels across fan settings and experiments to quantify the contemporaneous capture efficiency for the exhaust generated by natural gas cooking burners.Capture efficiency is defined as the fraction of generated pollutants that are removed through the exhaust and thus not available for inhalation of household occupants. Capture efficiency (CE) was assessed for various configurations of burner use (e.g., single front, single back, combination of one front and one back, oven) and fan speed setting. Measured airflow rates were substantially lower than the levels noted in product literature for many of the units. This shortfall was observed for several units costing in excess of $1000. Capture efficiency varied widely (from<5percent to roughly 100percent) across devices and across conditions for some devices. As expected, higher capture efficiencies were achieved with higher fan settings and the associated higher air flow rates. In most cases, capture efficiencies were substantially higher for rear burners than for front burners. The best and most consistent performance was observed for open hoods that covered all cooktop burners and operated at higher airflow rates. The lowest capture efficiencies were measured when a front burner was used with a rear backdraft system or with lowest fan setting for above the range systems that do not cover the front burners.

Singer, Brett C.; Delp, William W.; Apte, Michael G.

2010-11-01T23:59:59.000Z

364

Valuing Rail Transit: Comparing Capital and Operating Costs to Consumer Benefits  

E-Print Network [OSTI]

D.C. , 1994; Booz Allen Hamilton, Inc. Light rail transitD.C. , 2003; Booz Allen Hamilton, Inc. , Managing Capital

Guerra, Erick

2010-01-01T23:59:59.000Z

365

Appalachia's new region-wide CDFI : building local community with global capital?  

E-Print Network [OSTI]

The Appalachian Regional Commission is currently working with a major foundation on the development of a new regional Community Development Financial Institution (CDFI), Appalachian Community Capital. By connecting ...

Spicer, Jason S. (Jason Simpson)

2014-01-01T23:59:59.000Z

366

Native American Housing Stakeholder Meeting- Tribal Data: Building the Bridge to New Capital  

Broader source: Energy.gov [DOE]

Hosted by the Housing Assistance Council, the Native American Housing Stakeholder Meeting will discuss effective strategies for tribally led data collection, ways to access and leverage new capital...

367

A capital cost comparison of commercial ground-source heat pump systems  

SciTech Connect (OSTI)

The report provides a capital cost comparison of commercial ground source heat pump systems. The study includes groundwater systems, ground-coupled systems and hybrid systems.

Rafferty, K.

1994-06-01T23:59:59.000Z

368

Financial liberalisation and the capital structure of firms listed on the Johannesburg stock exchange.  

E-Print Network [OSTI]

??This thesis examines the impact of financial liberalisation on the capital structure of non-financial firms listed on the Johannesburg Stock Exchange (JSE). The research hypotheses… (more)

Chipeta, Chimwemwe

2012-01-01T23:59:59.000Z

369

Using Bayesian Model Averaging to Calibrate Forecast Ensembles 1  

E-Print Network [OSTI]

Using Bayesian Model Averaging to Calibrate Forecast Ensembles 1 Adrian E. Raftery, Fadoua forecasting often exhibit a spread-skill relationship, but they tend to be underdispersive. This paper of PDFs centered around the individual (possibly bias-corrected) forecasts, where the weights are equal

Washington at Seattle, University of

370

Disk-averaged Spectra & light-curves of Earth  

E-Print Network [OSTI]

We are using computer models to explore the observational sensitivity to changes in atmospheric and surface properties, and the detectability of biosignatures, in the globally averaged spectra and light-curves of the Earth. Using AIRS (Atmospheric Infrared Sounder) data, as input for atmospheric and surface properties, we have generated spatially resolved high-resolution synthetic spectra using the SMART radiative transfer model, for a variety of conditions, from the UV to the far-IR (beyond the range of current Earth-based satellite data). We have then averaged over the visible disk for a number of different viewing geometries to quantify the sensitivity to surface types and atmospheric features as a function of viewing geometry, and spatial and spectral resolution. These results have been processed with an instrument simulator to improve our understanding of the detectable characteristics of Earth-like planets as viewed by the first generation extrasolar terrestrial planet detection and characterization missions (Terrestrial Planet Finder/Darwin and Life finder). The wavelength range of our results are modelled over are applicable to both the proposed visible coronograph and mid-infrared interferometer TPF architectures. We have validated this model against disk-averaged observations by the Mars Global Surveyor Thermal Emission Spectrometer (MGS TES). This model was also used to analyze Earth-shine data for detectability of planetary characteristics and biosignatures in disk-averaged spectra.

G. Tinetti; V. S. Meadows; D. Crisp; W. Fong; N. Kiang; E. Fishbein; T. Velusamy; E. Bosc; M. Turnbull

2005-02-11T23:59:59.000Z

371

HIGH AVERAGE POWER UV FREE ELECTRON LASER EXPERIMENTS AT JLAB  

SciTech Connect (OSTI)

Having produced 14 kW of average power at {approx}2 microns, JLAB has shifted its focus to the ultraviolet portion of the spectrum. This presentation will describe the JLab UV Demo FEL, present specifics of its driver ERL, and discuss the latest experimental results from FEL experiments and machine operations.

Douglas, David; Evtushenko, Pavel; Gubeli, Joseph; Hernandez-Garcia, Carlos; Legg, Robert; Neil, George; Powers, Thomas; Shinn, Michelle D; Tennant, Christopher

2012-07-01T23:59:59.000Z

372

averaged lorentz dynamics: Topics by E-print Network  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

averaged lorentz dynamics First Page Previous Page 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Next Page Last Page Topic Index 1 Dynamics on Lorentz manifolds...

373

Probabilistic Wind Speed Forecasting Using Ensembles and Bayesian Model Averaging  

E-Print Network [OSTI]

distribution; Numerical weather prediction; Skewed distribution; Truncated data; Wind energy. 1. INTRODUCTION- native. Purely statistical methods have been applied to short-range forecasts for wind speed only a fewProbabilistic Wind Speed Forecasting Using Ensembles and Bayesian Model Averaging J. Mc

Raftery, Adrian

374

average energy losses: Topics by E-print Network  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

average energy losses First Page Previous Page 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Next Page Last Page Topic Index 1 Comparing energy loss...

375

average specific absorption: Topics by E-print Network  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

average specific absorption First Page Previous Page 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Next Page Last Page Topic Index 1 Original Research Specific...

376

IE 361 Module 15 The Average Run Length Concept  

E-Print Network [OSTI]

IE 361 Module 15 The Average Run Length Concept Reading: Section 3.5 of Statistical Quality Assurance Methods for Engineers Prof. Steve Vardeman and Prof. Max Morris Iowa State University Vardeman Electric set of alarm rules to a control charting scheme? The most e¤ective means known for making

Vardeman, Stephen B.

377

Rocky Flats CAAS System Recalibrated, Retested, and Analyzed to Install in the Criticality Experiments Facility at the Nevada Test Site  

E-Print Network [OSTI]

transferred from LLNL to NSTec for installation at the CEFSecurity Technologies (NSTec) is a great example of thetransferred from LLNL to NSTec for installation at the CEF

2009-01-01T23:59:59.000Z

378

Underground Storage Tank Regulations for the Certification of Persons Who Install, Alter, and Remove Underground Storage Tanks (Mississippi)  

Broader source: Energy.gov [DOE]

The Underground Storage Tank Regulations for the Certification of Persons who Install, Alter, and Remove Underground Storage Tanks applies to any project that will install, alter or remove...

379

Workload and transmission data for the installation of a digital breast tomosynthesis system  

SciTech Connect (OSTI)

Purpose: Digital breast tomosynthesis (DBT) differs from conventional mammography in target/filter, kVp range, and imaging geometry. The aim of this study was to assess the breast input exposure of a DBT system by completing a workload survey of DBT installations, and to determine the parameters {alpha}, {beta}, and {gamma} in the Archer equation for the primary radiation generated by the clinical workload distributions. Methods: The authors conducted a retrospective survey of the x-ray breast imaging performed between September 2011 and September 2012 in three clinical DBT rooms equipped with Selenia Dimensions systems (Hologic Inc., Bedford, MA). A total of 343 examinations were analyzed to calculate the workload (mA-minute) and the primary air kerma at 1 m from the source (K{sup 1}). Transmission curves were calculated for the primary radiation generated by the workload distributions of the DBT rooms, and were fitted to the Archer equation. Results: There were large variations in patient volume and workload in the three examination rooms. In all these rooms, the average tube voltage (kVp) was about 31, the average K{sup 1} per patient was 16-21 mGy, and the average mA-minute per patient was 1.4-2.2 times higher than that of the mammography room described in NCRP Report No. 147. Most DBT screening examinations consisted of four two-dimensional mammographic views plus four tomosynthesis scans; the numbers of views acquired in diagnostic examinations varied widely. Tomosynthesis scans contributed about 30% of total mA-minute and about 50% of K{sup 1}. For the primary radiation generated by the clinical workload distributions, {alpha} was similar to that of 40-45 kVp W/Al (target/filter), and {alpha}+{beta} was similar to that of 30 kVp W/Al. Conclusions: The workload (mA-minute and K{sup 1}) distributions of mammographic examinations with DBT differ from conventional mammography. A field survey of patient volume and x-ray tube usage is important for the shielding design of DBT facilities. The clinical workloads and transmission data presented in this paper may be useful for clinical medical physicists.

Li Xinhua; Zhang Da; Liu, Bob [Division of Diagnostic Imaging Physics and Webster Center for Advanced Research and Education in Radiation, Department of Radiology, Massachusetts General Hospital, Boston, Massachusetts 02114 (United States)

2013-06-15T23:59:59.000Z

380

Leveraging Inefficient and Failing Infrastructure to Accomplish Capital Improvements  

E-Print Network [OSTI]

an informational meeting and recognized the challenges and opportunities that existed at her facility. Specifically, major repairs were needed on one coal fired boiler in order to allow continuing operation. This need for repairs was following on the heals... it ESL-IC-10/05-09 1 provides both heating and cooling (via steam absorption chillers). The three existing coal fired boilers, installed in 1957, were still in their original condition. These boilers and the supporting balance of plant (BOP) were...

Mumper, M.; Taylor, C.

2005-01-01T23:59:59.000Z

Note: This page contains sample records for the topic "average installed capital" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


381

A Multivariate Moving Average Control Chart for Photovoltaic Processes  

E-Print Network [OSTI]

Abstract—For the electrical metrics that describe photovoltaic cell performance are inherently multivariate in nature, use of a univariate, or one variable, statistical process control chart can have important limitations. Development of a comprehensive process control strategy is known to be significantly beneficial to reducing process variability that ultimately drives up the manufacturing cost photovoltaic cells. The multivariate moving average or MMA chart, is applied to the electrical metrics of photovoltaic cells to illustrate the improved sensitivity on process variability this method of control charting offers. The result show the ability of the MMA chart to expand to as any variables as needed, suggests an application with multiple photovoltaic electrical metrics being used in concert to determine the processes state of control. Keywords—The multivariate moving average control chart, Photovoltaic processes control, Multivariate system. I.

Chunchom Pongchavalit

382

CAMPUS PLANNING COMMITTEE PLANNING AND REVIEW PROCESS FOR MAJOR CAPITAL PROJECTS  

E-Print Network [OSTI]

a detailed cost estimate. F. PROJECT PLANNING GUIDE (PPG): This document is required for all State fundedCAMPUS PLANNING COMMITTEE PLANNING AND REVIEW PROCESS FOR MAJOR CAPITAL PROJECTS (Revised June 2011) ___________________________________________________________________________________________ I. INTRODUCTION An effective major capital planning and review process will: Encourage appropriate

California at Santa Barbara, University of

383

Capital improvements can contribute greatly to an airport's future success, but  

E-Print Network [OSTI]

description, cost estimate, federal programming sheets (available at www.mnaero.com), and start date. FederalCapital improvements can contribute greatly to an airport's future success, but they require a serious financial commit- ment by the airport owner. Planning ahead for capital improvements is critical

Minnesota, University of

384

Debt Capacity and Optimal Capital Structure for Privately-Financed Infrastructure Projects  

E-Print Network [OSTI]

productivity, profitability, and private sector capital formation. He estimated, for example, that a 1 effective utilization of resources, when compared with the more flexible and cost conscious private sectorDebt Capacity and Optimal Capital Structure for Privately-Financed Infrastructure Projects

385

Political Studies Association 2012 Annual Conference Getting It, Spending It, Losing It: Exploring Political Capital  

E-Print Network [OSTI]

1 Political Studies Association 2012 Annual Conference Getting It, Spending It, Losing It: Exploring Political Capital Dr Mark Bennister Lecturer in Politics Canterbury Christ Church University Kent b.worthy@ucl.ac.uk PLEASE CONTACT THE AUTHORS FOR PERMISSION TO CITE Abstract Political capital

Saunders, Mark

386

Call for Partners: Increasing Affordable Farm Access: Putting Private Capital to  

E-Print Network [OSTI]

. Private investment capital put towards farm acquisition has the potential to increase affordable access to farmland if land arrangements enable farmers to have long-term tenure security, a cushion of time to build mechanisms for leveraging private capital to acquire working farm real-estate on behalf of farmers have been

Hayden, Nancy J.

387

The survival of venture capital backed companies : an analysis of the French case  

E-Print Network [OSTI]

The survival of venture capital backed companies : an analysis of the French case Sophie Pommet whether venture capital adds value to innovative French companies in terms of increasing their survival time. To this end, we use a hand-collected data set based on a sample of 139 French companies that went

Paris-Sud XI, Université de

388

Heterogeneous capital stocks and the optimal timing for CO2 abatement  

E-Print Network [OSTI]

Heterogeneous capital stocks and the optimal timing for CO2 abatement Mark Jaccard *, Nic Rivers a model and empirically estimated abatement costs. The results suggest that under many different assumptions, an early start at CO2 abatement for long-lived capital stocks would be economically optimal

389

Controlling a Stock Pollutant with Endogenous Abatement Capital and Asymmetric Information  

E-Print Network [OSTI]

Controlling a Stock Pollutant with Endogenous Abatement Capital and Asymmetric Information Larry have asymmetric information about abatement costs, and all agents use Markov Per- fect decision rules to represent the problem of controlling greenhouse gasses. The endogeneity of abatement capital favors taxes

Karp, Larry S.

390

Financing U.S. Renewable Energy Projects Through Public Capital Vehicles: Qualitative and Quantitative Benefits  

SciTech Connect (OSTI)

This paper explores the possibility of financing renewable energy projects through raising capital in the public markets. It gives an overview of the size, structure, and benefits of public capital markets, as well as showing how renewable energy projects might take advantage of this source of new funds to lower the cost of electricity.

Mendelsohn, M.; Feldman, D.

2013-04-01T23:59:59.000Z

391

The Ties That Bond: Re-Examining the Relationship between Facebook Use and Bonding Social Capital  

E-Print Network [OSTI]

The Ties That Bond: Re-Examining the Relationship between Facebook Use and Bonding Social Capital established a positive relationship between measures of Facebook use and perceptions of social capital. Like other social network sites, Facebook is especially well-positioned to enhance users' bridging social

Michigan, University of

392

The Externalities of Strong Social Capital: Post-Tsunami Recovery in Southeast India  

E-Print Network [OSTI]

1 The Externalities of Strong Social Capital: Post-Tsunami Recovery in Southeast India DANIEL P villages in Tamil Nadu, India following the 2004 Indian Ocean tsunami, this paper demonstrates that high findings have important implications for academic studies of social capital and policy formation for future

393

WORKING PAPER N 2008 -51 Human capital investment and long-term poverty  

E-Print Network [OSTI]

WORKING PAPER N° 2008 - 51 Human capital investment and long-term poverty reduction in rural Mexico SUPÉRIEURE halshs-00586227,version1-15Apr2011 #12;Human capital investment and long-term poverty reduction poor (World Bank, 2005). To address chronic poverty, the Mexican government has developed an overall

Paris-Sud XI, Université de

394

FY 2013 Major Capital Outlay Project Request and Five-Year Comprehensive Master Plan  

E-Print Network [OSTI]

in the following specific areas: Transmission & Distribution (smart grids technology, cyber-security) GenerationFY 2013 Major Capital Outlay Project Request and Five-Year Comprehensive Master Plan September 2011 ____ No _X__ Is There a Five-Year Capital Outlay Plan Available? Yes _X__ No ____ Are Professionally

395

42 UNIVERSITY OF CALIFORNIA -CAPITAL FINANCIAL PLAN 2012-22 Coastal Biology Building  

E-Print Network [OSTI]

42 UNIVERSITY OF CALIFORNIA - CAPITAL FINANCIAL PLAN 2012-22 Coastal Biology Building University&Figures SANTA CRUZ Coastal Biology Building Site #12;43UNIVERSITY OF CALIFORNIA - CAPITAL FINANCIAL PLAN 2012 C ­ multiple locations Coastal Biology Building - (Marine Science Campus) Infrastructure

California at Santa Cruz, University of

396

Better than Average? - Green Building Certification in International Projects  

E-Print Network [OSTI]

. An Enterprise of the Ebert-Consulting Group 1004 Pennsylvania Avenue, SE Washington, D.C. 20003, USA 00 12 02/ 6 08 - 13 34 o.baumann@eb-engineers.com Better than Average? - Green Building Certification in International Projects Green Building..., green building rating systems focus on sustainability for the entire life-cycle of buildings and therefore offer great opportunities for enhancing building operation, when applied and used appropriately. This presentation gives an overview...

Baumann, O.

2008-01-01T23:59:59.000Z

397

A holographic proof of the averaged null energy condition  

E-Print Network [OSTI]

The averaged null energy conditions (ANEC) states that, along a complete null curve, the negative energy fluctuations of a quantum field must be balanced by positive energy fluctuations. We use the AdS/CFT correspondence to prove the ANEC for a class of strongly coupled conformal field theories in flat spacetime. A violation of the ANEC in the field theory would lead to acausal propagation of signals in the bulk.

William R. Kelly; Aron C. Wall

2014-11-03T23:59:59.000Z

398

Average dynamics of a finite set of coupled phase oscillators  

SciTech Connect (OSTI)

We study the solutions of a dynamical system describing the average activity of an infinitely large set of driven coupled excitable units. We compared their topological organization with that reconstructed from the numerical integration of finite sets. In this way, we present a strategy to establish the pertinence of approximating the dynamics of finite sets of coupled nonlinear units by the dynamics of its infinitely large surrogate.

Dima, Germán C., E-mail: gdima@df.uba.ar; Mindlin, Gabriel B. [Laboratorio de Sistemas Dinámicos, IFIBA y Departamento de Física, Facultad de Ciencias Exactas y Naturales, Universidad de Buenos Aires, Pabellón 1, Ciudad Universitaria, Buenos Aires (Argentina)] [Laboratorio de Sistemas Dinámicos, IFIBA y Departamento de Física, Facultad de Ciencias Exactas y Naturales, Universidad de Buenos Aires, Pabellón 1, Ciudad Universitaria, Buenos Aires (Argentina)

2014-06-15T23:59:59.000Z

399

Estimate of average freeze-out volume in multifragmentation events  

E-Print Network [OSTI]

An estimate of the average freeze-out volume for multifragmentation events is presented. Values of volumes are obtained by means of a simulation using the experimental charged product partitions measured by the 4pi multidetector INDRA for 129Xe central collisions on Sn at 32 AMeV incident energy. The input parameters of the simulation are tuned by means of the comparison between the experimental and simulated velocity (or energy) spectra of particles and fragments.

Piantelli, S; Borderie, B; Bougault, R; Chbihi, A; Dayras, R; Durand, D; Frankland, J D; Galíchet, E; Guinet, D; Lanzalone, G; Lautesse, P; Le Neindre, N; López, O; Pârlog, M; Rivet, M F; Rosato, E; Tamain, B; Vient, E; Vigilante, M; Volant, C; Wieleczko, J P

2005-01-01T23:59:59.000Z

400

Integrated dynamic landscape analysis and modeling system (IDLAMS) : installation manual.  

SciTech Connect (OSTI)

The Integrated Dynamic Landscape Analysis and Modeling System (IDLAMS) is a prototype, integrated land management technology developed through a joint effort between Argonne National Laboratory (ANL) and the US Army Corps of Engineers Construction Engineering Research Laboratories (USACERL). Dr. Ronald C. Sundell, Ms. Pamela J. Sydelko, and Ms. Kimberly A. Majerus were the principal investigators (PIs) for this project. Dr. Zhian Li was the primary software developer. Dr. Jeffrey M. Keisler, Mr. Christopher M. Klaus, and Mr. Michael C. Vogt developed the decision analysis component of this project. It was developed with funding support from the Strategic Environmental Research and Development Program (SERDP), a land/environmental stewardship research program with participation from the US Department of Defense (DoD), the US Department of Energy (DOE), and the US Environmental Protection Agency (EPA). IDLAMS predicts land conditions (e.g., vegetation, wildlife habitats, and erosion status) by simulating changes in military land ecosystems for given training intensities and land management practices. It can be used by military land managers to help predict the future ecological condition for a given land use based on land management scenarios of various levels of training intensity. It also can be used as a tool to help land managers compare different land management practices and further determine a set of land management activities and prescriptions that best suit the needs of a specific military installation.

Li, Z.; Majerus, K. A.; Sundell, R. C.; Sydelko, P. J.; Vogt, M. C.

1999-02-24T23:59:59.000Z

Note: This page contains sample records for the topic "average installed capital" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


401

Resource Form Factor and Installation of GFA Controllers  

SciTech Connect (OSTI)

The focus of this task is to optimize the form and placement of a controller comprising the Grid Friendly™ appliance (GFA) controller, power supply and power relay (and/or a solid-state power electronic switch) that would command a domestic water heater to shed its load in response to stress on the electric power grid. The GFA controller would disconnect the water heater from its supply circuit whenever it senses a low voltage signal or other indicators of system stress communicated via the electric power distribution system. Power would be reconnected to the appliance when the GFA controller senses the absence of these signals. This project has also considered more frequent cycling of this controller’s relay switch to perform demand-side frequency regulation. The principal criteria considered in this optimization are reliability, cost and life expectancy of the GFA components. The alternative embodiments of the GFA equipment under consideration are: Option 1- installation inside the insulation space of the water heater between the tank and jacket Option 2 containment in a separate nearby electrical enclosure Option 3 - as a modification or adjunct to the distribution panel housing and/or the breaker that protects the water heater supply circuit.

DeSteese, John G.; Hammerstrom, Donald J.

2009-11-15T23:59:59.000Z

402

Solar installer training: Home Builders Institute Job Corps  

SciTech Connect (OSTI)

The instructors describe the solar installation training program operated since 1979 by the Home Builders Institute, the Educational Arm of the National Association of Home Builders for the US Department of Labor, Job Corps in San Diego, CA. The authors are the original instructors and have developed the program since its inception by a co-operative effort between the Solar Energy Industries Association, NAHB and US DOL. Case studies of a few of the 605 students who have gone to work over the years after the training are included. It is one of the most successful programs under the elaborate Student Performance Monitoring Information System used by all Job Corps programs. Job Corps is a federally funded residential job training program for low income persons 16--24 years of age. Discussion details the curriculum and methods used in the program including classroom, shop and community service projects. Solar technologies including all types of hot water heating, swimming pool and spa as well as photovoltaics are included.

Hansen, K.; Mann, R. [San Diego Job Corps Center, Imperial Beach, CA (United States). Home Builders Inst.

1996-10-01T23:59:59.000Z

403

Expert Meeting Report: Achieving the Best Installed Performance from High-Efficiency Residential Gas Furnaces  

SciTech Connect (OSTI)

This report describes a Building America expert meeting hosted on July 28, 2011, by the Partnership for Advanced Residential Retrofit team. The purpose of this meeting was to identify installation practices that provide the best installed efficiency for residential gas furnaces, explain how AFUE and field efficiency can differ, and investigate the impact of installation practices on the efficiency and long-term durability of the furnace.

Brand, L.

2012-03-01T23:59:59.000Z

404

Gravity base foundations for offshore wind farms : marine operations and installation processes.  

E-Print Network [OSTI]

??ABSTRACT. Marine operations required in the installation of gravity base foundations for offshore wind farms were studied. This dissertation analyses the operations of transport, seabed… (more)

Ruiz de Temińo Alonso, Ismael

2013-01-01T23:59:59.000Z

405

Offshore Wind Turbine Transportation & Installation Analyses Planning Optimal Marine Operations for Offshore Wind Projects.  

E-Print Network [OSTI]

?? Transportation and installation of offshore wind turbines (Tower, Nacelle and Rotor) is a complete process conducted over several phases, usually in sequence. There are… (more)

Uraz, Emre

2011-01-01T23:59:59.000Z

406

H.A.R. 19-105 - Accommodation and Installation of Utilities on...  

Open Energy Info (EERE)

Accommodation and Installation of Utilities on State Highways and Federal Aid County Highways Jump to: navigation, search OpenEI Reference LibraryAdd to library Legal Document-...

407

E-Print Network 3.0 - air conditioning installations Sample Search...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Las Vegas, Nevada, to develop, design, procure, install, and operate an on-site hydrogen generation Source: DOE Office of Energy Efficiency and Renewable Energy, Hydrogen, Fuel...

408

Consider Installing Turbulators on Two- and Three-Pass Firetube Boilers  

SciTech Connect (OSTI)

This revised ITP tip sheet on installing turbulators on firetube boilers provides how-to advice for improving the system using low-cost, proven practices and technologies.

Not Available

2006-01-01T23:59:59.000Z

409

E-Print Network 3.0 - alcohol tank installed Sample Search Results  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

AND ENVIRONMENTAL SCIENCES Summary: inspection. Risers should be installed on all new tanks and can even be retrofitted for existing tanks. All... that the septic tank needs...

410

E-Print Network 3.0 - avoid radar installations Sample Search...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

to 9o differences in flow directions. 1. INTRODUCTION We installed the first HF radar at Coal Oil... Evaluating radial component current measurements from CODAR high frequency...

411

Program and Project Management for the Acquisition of Capital Assets  

Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

To provide Department of Energy (DOE), including the National Nuclear Security Administration (NNSA), project management direction for the acquisition of capital assets that are delivered on schedule, within budget, and fully capable of meeting mission performance and environmental, safety and health standards. (Cancels DOE O 430.1A, paragraphs 6e(7); 7a(3); 7b(11); 7b(14); 7c(4), (6), (7), (11) and (16); 7d(4) and (8); 7e(3), (10), and (17); Attachment 1, Definitions (items 30 - Line Item Project; item 42 - Project, item 48 - Strategic System); and Attachment 2, Contractor Requirements Document (paragraph 1d regarding a project management system). Cancels DOE N 430.1 and DOE O 430.1A (in part). Canceled by DOE O 413.3 Chg 1.

2000-10-13T23:59:59.000Z

412

Program and Project Management for the Acquisition of Capital Assets  

Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

To provide Department of Energy (DOE), including the National Nuclear Security Administration (NNSA), project management direction for the acquisition of capital assets that are delivered on schedule, within budget, and fully capable of meeting mission performance and environmental, safety and health standards. Cancels DOE O 430.1A, paragraphs 6e(7); 7a(3); 7b(11); 7b(14); 7c(4), (6), (7), (11) and (16); 7d(4) and (8); 7e(3), (10), and (17); Attachment 1, Definitions (items 30 - Line Item Project; item 42 - Project, item 48 - Strategic System; and Attachment 2, Contractor Requirements Document paragraph 1d regarding a project management system. Cancels DOE N 430.1 and DOE O 430.1A (in part). Canceled by DOE O 413.3A.

2000-10-13T23:59:59.000Z

413

Discrete Event Modeling of Algae Cultivation and Harvesting at Commercial Scale: Capital Costs, Operating Costs, and System Bottlenecks  

SciTech Connect (OSTI)

Discrete Event Modeling of Algae Cultivation and Harvesting at Commercial Scale: Capital Costs, Operating Costs, and System Bottlenecks

Lacey, Ph.D, P.E., Ronald E. [Texas A& M University

2012-07-16T23:59:59.000Z

414

Fig. 3. Averaged PSF of a whole eye without immersion (a), compared to average eye with corneal immersion (b). The degradation using immersion is mostly caused by  

E-Print Network [OSTI]

Fig. 3. Averaged PSF of a whole eye without immersion (a), compared to average eye with corneal of the complete eye was calculated by the averaged Zernike coefficients measured on 532 eyes. All PSFs were). The PSFs were calculated by averaging Zernike coefficients measured from 228 eyes. Both PSFs were

Ribak, Erez

415

Design and Installation of a Disposal Cell Cover Field Test  

SciTech Connect (OSTI)

The U.S. Department of Energy’s Office of Legacy Management (LM) initiated a cover assessment project in September 2007 to evaluate an inexpensive approach to enhancing the hydrological performance of final covers for disposal cells. The objective is to accelerate and enhance natural processes that are transforming existing conventional covers, which rely on low-conductivity earthen barriers, into water balance covers, that store water in soil and release it as soil evaporation and plant transpiration. A low conductivity cover could be modified by deliberately blending the upper layers of the cover profile and planting native shrubs. A test facility was constructed at the Grand Junction, Colorado, Disposal Site to evaluate the proposed methodology. The test cover was constructed in two identical sections, each including a large drainage lysimeter. The test cover was constructed with the same design and using the same materials as the existing disposal cell in order to allow for a direct comparison of performance. One test section will be renovated using the proposed method; the other is a control. LM is using the lysimeters to evaluate the effectiveness of the renovation treatment by monitoring hydrologic conditions within the cover profile as well as all water entering and leaving the system. This paper describes the historical experience of final covers employing earthen barrier layers, the design and operation of the lysimeter test facility, testing conducted to characterize the as-built engineering and edaphic properties of the lysimeter soils, the calibration of instruments installed at the test facility, and monitoring data collected since the lysimeters were constructed.

Benson, C.H. [University of Wisconsin–Madison, Madison, Wisconsin; Waugh, W.J. [S.M. Stoller Corporation, Grand Junction, Colorado; Albright, W.H. [Desert Research Institute, Reno, Nevada; Smith, G.M. [Geo-Smith Engineering, Grand Junction, Colorado; Bush, R.P. [U.S. Department of Energy, Grand Junction, Colorado

2011-02-27T23:59:59.000Z

416

Genetic algorithm evolved agent-based equity trading using Technical Analysis and the Capital Asset Pricing Model  

E-Print Network [OSTI]

Genetic algorithm evolved agent-based equity trading using Technical Analysis and the Capital Asset data using technical analysis, the capital asset pricing model and a hybrid model of the two approaches. Results indicated that the technical analysis based approach performed better than the capital asset

Aickelin, Uwe

417

Electronic copy available at: http://ssrn.com/abstract=2065816 Ultimate Ownership Structure and Bank Regulatory Capital Adjustment  

E-Print Network [OSTI]

their capital structure (debt/equity), firms in general and banks more specifically take control dilution costs into consideration, beyond the asymmetric information and transaction costs considered in prior research on capital and Bank Regulatory Capital Adjustment: Evidence from European Commercial Banks Laetitia Lepetita , Amine

Boyer, Edmond

418

The contribution of built, human, social and natural capital to quality of life in intentional and unintentional communities  

E-Print Network [OSTI]

have a better balance between built, human, social, and natural capital than unintentional communities ICs, social capital is substituted for built capital thereby reducing the level of material throughput. © 2005 Elsevier B.V. All rights reserved. Keywords: Quality of life survey Intentional communities Social

Vermont, University of

419

Average Fe K-alpha emission from distant AGN  

E-Print Network [OSTI]

One of the most important parameters in the XRB (X-ray background) synthesis models is the average efficiency of accretion onto SMBH (super-massive black holes). This can be inferred from the shape of broad relativistic Fe lines seen in X-ray spectra of AGN (active galactic nuclei). Several studies have tried to measure the mean Fe emission properties of AGN at different depths with very different results. We compute the mean Fe emission from a large and representative sample of AGN X-ray spectra up to redshift ~ 3.5. We developed a method of computing the rest-frame X-ray average spectrum and applied it to a large sample (more than 600 objects) of type 1 AGN from two complementary medium sensitivity surveys based on XMM-Newton data, the AXIS and XWAS samples. This method makes use of medium-to-low quality spectra without needing to fit complex models to the individual spectra but with computing a mean spectrum for the whole sample. Extensive quality tests were performed by comparing real to simulated data, and a significance for the detection of any feature over an underlying continuum was derived. We detect with a 99.9% significance an unresolved Fe K-alpha emission line around 6.4 keV with an EW ~ 90 eV, but we find no compelling evidence of any significant broad relativistic emission line in the final average spectrum. Deviations from a power law around the narrow line are best represented by a reflection component arising from cold or low-ionization material. We estimate an upper limit for the EW of any relativistic line of 400 eV at a 3 sigma confidence level. We also marginally detect the so-called Iwasawa-Taniguchi effect on the EW for the unresolved emission line, which appears weaker for higher luminosity AGN.

A. Corral; M. J. Page; F. J. Carrera; X. Barcons; S. Mateos; J. Ebrero; M. Krumpe; A. Schwope; J. A. Tedds; M. G. Watson

2008-10-02T23:59:59.000Z

420

Hilbert Space Average Method and adiabatic quantum search  

E-Print Network [OSTI]

We discuss some aspects related to the so-called Hilbert space Average Method, as an alternative to describe the dynamics of open quantum systems. First we present a derivation of the method which does not make use of the algebra satisfied by the operators involved in the dynamics, and extend the method to systems subject to a Hamiltonian that changes with time. Next we examine the performance of the adiabatic quantum search algorithm with a particular model for the environment. We relate our results to the criteria discussed in the literature for the validity of the above-mentioned method for similar environments.

A. Perez

2009-01-19T23:59:59.000Z

Note: This page contains sample records for the topic "average installed capital" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


421

W. R. Johnson An Average-Atom Model  

E-Print Network [OSTI]

W. R. Johnson An Average-Atom Model h0 - Z r + V (r) a(r) = aa(r) potential: V (r) = (r )/R d - (3) d 1 + exp[( - µ)/kT ] P 2 (r) norm: Z = R 0 4r 2 (r) dr ­ ND ­ 04/02 1 #12;W. R. Johnson Electron-Fermi contributions to continuum ­ ND ­ 04/02 2 #12;W. R. Johnson Phase shifts: Al - T=10eV 0 1 2 3 4 5 6 7 8 electron

Johnson, Walter R.

422

Table 14b. Average Electricity Prices, Projected vs. Actual  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr MayAtmosphericNuclear Security AdministrationcontrollerNanocrystallineForeign ObjectOUR Table 1. Summary statistics for0b. Average

423

Historical Average Priority Firm Power Rates (rates/previous)  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr MayAtmospheric Optical Depth7-1D: Vegetation ProposedUsingFun withconfinement plasmas in theinPlasticsreduction .HistoricHistorical Average

424

Table 14b. Average Electricity Prices, Projected vs. Actual  

U.S. Energy Information Administration (EIA) Indexed Site

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data CenterFranconia, Virginia:FAQ <Information Administration (EIA) 10 MECS Survey Data9c : U.S.Welcome to the1,033 15:b.b. Average

425

Table 17. Average Price of U.S. Coke Exports  

Gasoline and Diesel Fuel Update (EIA)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr May Jun Jul(Summary) " ,"Click worksheet9,1,50022,3,,,,6,1,,781 2,328AdministrationReleaseMetallurgical Coal Exports byAverage

426

Table 22. Average Price of U.S. Coke Imports  

Gasoline and Diesel Fuel Update (EIA)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr May Jun Jul(Summary) " ,"Click worksheet9,1,50022,3,,,,6,1,,781 2,328AdministrationReleaseMetallurgical Coal ExportsPriceAverage

427

Table 8. Average Price of U.S. Coal Exports  

Gasoline and Diesel Fuel Update (EIA)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr May Jun Jul(Summary) " ,"Click worksheet9,1,50022,3,,,,6,1,,781 2,328AdministrationReleaseMetallurgical CoalAverage Price

428

Yearly average performance of the principal solar collector types  

SciTech Connect (OSTI)

The results of hour-by-hour simulations for 26 meteorological stations are used to derive universal correlations for the yearly total energy that can be delivered by the principal solar collector types: flat plate, evacuated tubes, CPC, single- and dual-axis tracking collectors, and central receiver. The correlations are first- and second-order polynomials in yearly average insolation, latitude, and threshold (= heat loss/optical efficiency). With these correlations, the yearly collectible energy can be found by multiplying the coordinates of a single graph by the collector parameters, which reproduces the results of hour-by-hour simulations with an accuracy (rms error) of 2% for flat plates and 2% to 4% for concentrators. This method can be applied to collectors that operate year-around in such a way that no collected energy is discarded, including photovoltaic systems, solar-augmented industrial process heat systems, and solar thermal power systems. The method is also recommended for rating collectors of different type or manufacturer by yearly average performance, evaluating the effects of collector degradation, the benefits of collector cleaning, and the gains from collector improvements (due to enhanced optical efficiency or decreased heat loss per absorber surface). For most of these applications, the method is accurate enough to replace a system simulation.

Rabl, A.

1981-01-01T23:59:59.000Z

429

Average Fe K-alpha emission from distant AGN  

E-Print Network [OSTI]

One of the most important parameters in the XRB (X-ray background) synthesis models is the average efficiency of accretion onto SMBH (super-massive black holes). This can be inferred from the shape of broad relativistic Fe lines seen in X-ray spectra of AGN (active galactic nuclei). Several studies have tried to measure the mean Fe emission properties of AGN at different depths with very different results. We compute the mean Fe emission from a large and representative sample of AGN X-ray spectra up to redshift ~ 3.5. We developed a method of computing the rest-frame X-ray average spectrum and applied it to a large sample (more than 600 objects) of type 1 AGN from two complementary medium sensitivity surveys based on XMM-Newton data, the AXIS and XWAS samples. This method makes use of medium-to-low quality spectra without needing to fit complex models to the individual spectra but with computing a mean spectrum for the whole sample. Extensive quality tests were performed by comparing real to simulated data, a...

Corral, A; Carrera, F J; Barcons, X; Mateos, S; Ebrero, J; Krumpe, M; Schwope, A; Tedds, J A; Watson, M G

2008-01-01T23:59:59.000Z

430

Plasma dynamics and a significant error of macroscopic averaging  

E-Print Network [OSTI]

The methods of macroscopic averaging used to derive the macroscopic Maxwell equations from electron theory are methodologically incorrect and lead in some cases to a substantial error. For instance, these methods do not take into account the existence of a macroscopic electromagnetic field EB, HB generated by carriers of electric charge moving in a thin layer adjacent to the boundary of the physical region containing these carriers. If this boundary is impenetrable for charged particles, then in its immediate vicinity all carriers are accelerated towards the inside of the region. The existence of the privileged direction of acceleration results in the generation of the macroscopic field EB, HB. The contributions to this field from individual accelerated particles are described with a sufficient accuracy by the Lienard-Wiechert formulas. In some cases the intensity of the field EB, HB is significant not only for deuteron plasma prepared for a controlled thermonuclear fusion reaction but also for electron plasma in conductors at room temperatures. The corrected procedures of macroscopic averaging will induce some changes in the present form of plasma dynamics equations. The modified equations will help to design improved systems of plasma confinement.

Marek A. Szalek

2005-05-22T23:59:59.000Z

431

Planning and Installation Guide: North Carolina Compressed Natural Gas Fueling Stations  

E-Print Network [OSTI]

1 Planning and Installation Guide: North Carolina Compressed Natural Gas Fueling Stations Introduction Are you considering installing a compressed natural gas (CNG) fueling station for your fleet to provide your fleet with fuel. One resource for locating and identifying public compressed natural gas

432

Thermal Performance Impacts of Center-of-Glass Deflections in Installed Insulating  

E-Print Network [OSTI]

LBNL-5800E Thermal Performance Impacts of Center-of- Glass Deflections in Installed Insulating Laboratory Windows and Envelope Materials Group Building Technology and Urban Systems Department: temperature difference Thermal Performance Impacts of Center-of-Glass Deflections in Installed Insulating

433

INFO-F-309 Administration des Systmes TP1: Installation de Linux et gestion des packages  

E-Print Network [OSTI]

INFO-F-309 ­ Administration des Systčmes TP1: Installation de Linux et gestion des packagesBox. Ensuite nous verrons comment fonctionne la gestion de packages, la mise ŕ jour du systčme et l la gestion de packages. 2 Installation de Linux 2.1 Préparation Surtout lorsqu'il s'agit d'un serveur

Collette. Sébastien

434

Volume XIX, No. 1 A publication of the U.S. Army Installation Management Command  

E-Print Network [OSTI]

Volume XIX, No. 1 A publication of the U.S. Army Installation Management Command January -- the New Landscape #12;Public Works Digest · January/February 2007 Public Works Digest is an unofficial publication of the U.S. Army Installation Management Command, under AR 360-1, The Army Public Affairs Program

US Army Corps of Engineers

435

Lessons Learned from Net Zero Energy Assessments and Renewable Energy Projects at Military Installations  

SciTech Connect (OSTI)

Report highlights the increase in resources, project speed, and scale that is required to achieve the U.S. Department of Defense (DoD) energy efficiency and renewable energy goals and summarizes the net zero energy installation assessment (NZEI) process and the lessons learned from NZEI assessments and large-scale renewable energy projects implementations at DoD installations.

Callahan, M.; Anderson, K.; Booth, S.; Katz, J.; Tetreault, T.

2011-09-01T23:59:59.000Z

436

Average System Cost Methodology : Administrator's Record of Decision.  

SciTech Connect (OSTI)

Significant features of average system cost (ASC) methodology adopted are: retention of the jurisdictional approach where retail rate orders of regulartory agencies provide primary data for computing the ASC for utilities participating in the residential exchange; inclusion of transmission costs; exclusion of construction work in progress; use of a utility's weighted cost of debt securities; exclusion of income taxes; simplification of separation procedures for subsidized generation and transmission accounts from other accounts; clarification of ASC methodology rules; more generous review timetable for individual filings; phase-in of reformed methodology; and each exchanging utility must file under the new methodology within 20 days of implementation by the Federal Energy Regulatory Commission of the ten major participating utilities, the revised ASC will substantially only affect three. (PSB)

United States. Bonneville Power Administration.

1984-06-01T23:59:59.000Z

437

REVISITING THE SOLAR TACHOCLINE: AVERAGE PROPERTIES AND TEMPORAL VARIATIONS  

SciTech Connect (OSTI)

The tachocline is believed to be the region where the solar dynamo operates. With over a solar cycle's worth of data available from the Michelson Doppler Imager and Global Oscillation Network Group instruments, we are in a position to investigate not merely the average structure of the solar tachocline, but also its time variations. We determine the properties of the tachocline as a function of time by fitting a two-dimensional model that takes latitudinal variations of the tachocline properties into account. We confirm that if we consider the central position of the tachocline, it is prolate. Our results show that the tachocline is thicker at latitudes higher than the equator, making the overall shape of the tachocline more complex. Of the tachocline properties examined, the transition of the rotation rate across the tachocline, and to some extent the position of the tachocline, show some temporal variations.

Antia, H. M. [Tata Institute of Fundamental Research, Homi Bhabha Road, Mumbai 400005 (India); Basu, Sarbani, E-mail: antia@tifr.res.in, E-mail: sarbani.basu@yale.edu [Department of Astronomy, Yale University, P.O. Box 208101, New Haven, CT 06520-8101 (United States)

2011-07-10T23:59:59.000Z

438

Energy Office Grant Helps the Virgin Islands Environmental Resource Station Install Solar Panels, Improve Efficiency, and Cut Monthly Energy Use Nearly 30% (Fact Sheet)  

SciTech Connect (OSTI)

This fact sheet highlights the energy challenges faced by the Virgin Islands Environmental Resource Station (VIERS), the renewable energy and energy efficiency solutions implemented, the resulting energy efficiency savings, and other project benefits. In 2011, VIERS installed a 9.4 kW solar system funded by a $50,000 American Recovery and Reinvestment Act (ARRA) grant, which was administered by VIEO. To identify additional energy-saving opportunities, VIERS performed an energy audit of appliances, which resulted in the removal of two water coolers and the installation of a water meter to monitor water use and how it relates to electric pump use. VIERS also added an educational component to the project, developing a solar classroom near the original solar system. By building on previous energy conservation measures and making additional investments in renewable energy technology, VIERS has lowered its average monthly energy consumption nearly 30%, even with an increase in guests. The VIERS efforts are not limited to the technology installations, however. They also serve to impact the youth of the U.S. Virgin Islands (USVI) by educating young people about energy efficiency and renewable energy technologies and their energy and environmental impacts. VIERS solar system is connected to the Web via a live feed that posts solar output data in real time, increasing the VIERS solar classroom's potential educational impact exponentially.

Not Available

2012-03-01T23:59:59.000Z

439

On the Consequences of Eliminating Capital Tax Differentials  

E-Print Network [OSTI]

to eliminate these differentials. This paper analyzes the consequences of such a reform using an incomplete markets model with equipment-skill complementarity. We find that the reform increases average welfare by approximately 0.1%. Importantly, we find that the reform does not involve the usual efficiency vs. equality

Yanikoglu, Berrin

440

Implementation of Carbon Reduction in Capital Projects Introduction  

E-Print Network [OSTI]

means capping its total greenhouse gas emissions at 16,000 t/CO2 p.a. (see the College Carbon Management deliver a carbon emission p.a. reduction of at least 50% at design stage (with the aim of achieving operational reductions of at least 40%). This reduction should be below that of the average emission

Chittka, Lars

Note: This page contains sample records for the topic "average installed capital" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


441

Dynamic cycles of strategy, marketing and sales : a framework for capital goods industries  

E-Print Network [OSTI]

This thesis proposes a framework to help managers facing growth challenges or commoditization problems in business to business, particularly with capital goods. The framework is based on the proposition that strategy, ...

Rezende de Azevedo, Tadeu

2013-01-01T23:59:59.000Z

442

Essays using military-induced variation to study social interactions, human capital development, and labor markets  

E-Print Network [OSTI]

This dissertation consists of four empirical studies, each using military-induced variation to examine various aspects of human capital production and the U.S. labor market. The first two chapters study the effects of ...

Lyle, David S. (David Stephen), 1971-

2003-01-01T23:59:59.000Z

443

Seeds of growth : the challenges of venture capital in the Australian landscape  

E-Print Network [OSTI]

The Australian venture capital (VC) industry is young and relatively immature compared to the United States. Even though the first Australian VC firm appeared in 1970, the industry remained a niche with low levels of ...

Lu, Adrian C. (Adrian Chian)

2012-01-01T23:59:59.000Z

444

Dynamics of shared capitalism policies in a startup company by Joe C. Hsueh.  

E-Print Network [OSTI]

Shared capitalism is a diverse set of compensation practices through which worker pay, or wealth, depends on the performance of the firm or work group; compensation practices include employee ownership, stock options, and ...

Hsueh, Joe C. (Joe Chiao-Jen)

2011-01-01T23:59:59.000Z

445

Agency conflicts in financial contracting with applications to venture capital and CDO markets  

E-Print Network [OSTI]

In these papers I examine efficient financial contracting when incentive problems play a significant role. In the first chapter (joint with Z. Fluck and S. Myers) we focus on the venture capital industry. We build a two-stage ...

Garrison, Kedran

2005-01-01T23:59:59.000Z

446

Relational Capital and Appropriate Incentives: A Recipe for Human Resource Sustainability?1  

E-Print Network [OSTI]

economic literature on incentives, experimental economics and research in cognitive psychology can provideRelational Capital and Appropriate Incentives: A Recipe for Human Resource Sustainability?1 Agnčs Festré University of Picardie Jules Verne, France Faculty of Economics Agnes

Paris-Sud XI, Université de

447

Social capital's dark side: knowledge, reciprocity, and the liability of relationships  

E-Print Network [OSTI]

follow that of the Academy of Management Journal. T 2 terms of connections within and across networks (Burt, 1992, 1997; Gulati, 1995a; Tsai & Ghoshal, 1998). These and other authors have presented a convincing argument that social capital can...

Collins, Jamie D.

2009-05-15T23:59:59.000Z

448

International Capital Flows and Financial Markets in Transition Economies: The Case of Croatia  

E-Print Network [OSTI]

of portfolio capital inflows to Croatia 1998- Table 4.Portfolio Investment in Croatia 1998-2003 ( in Mil US$) 1.reveals a surprising ratio in Croatia when compared to other

Sohinger, Jasminka; Horvatin, Darko

2006-01-01T23:59:59.000Z

449

International Capital Flows and Financial Markets in Transition Economies: The Case of Croatia  

E-Print Network [OSTI]

instruments TOTAL Source: Croatian National Bank (2005) TheFrankfurt, J2 / J2-2 Croatian National Bank (2005),capital flows had on the Croatian banking industry as well

Sohinger, Jasminka; Horvatin, Darko

2006-01-01T23:59:59.000Z

450

Venture Capital Institutions and Venture Capitalists’ Investment Activities: An Empirical Study on China   

E-Print Network [OSTI]

This thesis explores institutions under which venture capital investment operates in China and whether and how these institutions affect venture capitalists’ (VCs) investment preferences, ex-ante project screening ...

Guo, Di

2010-01-01T23:59:59.000Z

451

Spreading The Word: Capital Market Consequences of Business Press Coverage of Management Earnings Guidance  

E-Print Network [OSTI]

This study investigates the role of the business press in disseminating management earnings guidance news to capital market participants. Using a unique sample of over 55,000 articles that relate specifically to management guidance, I find that 48...

Twedt, Brady J

2013-06-21T23:59:59.000Z

452

Growth strategies : how software start-ups can leverage alliances, acquisitions, IPOs and venture capital  

E-Print Network [OSTI]

The identification of the different factors impacting a software start-up company's decision to pursue an alliance, acquisition, IPO or venture capital to sustain growth is the main objective of this research study. First ...

Ybanez, Sergio D

2007-01-01T23:59:59.000Z

453

Balancing capital and condition : an emerging approach to facility investment strategy  

E-Print Network [OSTI]

Capital facilities - land and buildings - provide a long-standing environment in which public and private enterprise works, communicates, and thrives. Aligning how facilities "fit" with the dynamic demands of enterprise ...

Wooldridge, Stephen C. (Stephen Craig), 1967-

2002-01-01T23:59:59.000Z

454

Structuring public REIT-sponsored private capital fund : the case of US industrial and retail REITs  

E-Print Network [OSTI]

The private capital business for public REITs was started by Kimco Realty, Developer Diversified, AMB and ProLogis during the years 1998-2000, at the time when the public equity was not easily available. Over the past ...

Lee, Cervantes (Cervantes Chih-Chieh), 1975-

2008-01-01T23:59:59.000Z

455

Operations improvement in a semiconductor capital equipment manufacturing plant : component level and assembly level inventory management  

E-Print Network [OSTI]

Semiconductor capital equipment is manufactured in a high-mix and low-volume environment at Varian Semiconductor Equipment business unit of Applied Materials. Due to the demand growth over the past years, Varian has been ...

Wu, Yiming, M. Eng. Massachusetts Institute of Technology

2012-01-01T23:59:59.000Z

456

Capital, labor, and energy cost prediction in timber harvesting: a microcomputer solution  

E-Print Network [OSTI]

Organization Capital. 17 17 Labor 22 Energy. III. CAPITAL COST CALCULATION. 22 25 Depreciation. Taxes, Insurance, and Interest. 25 30 IV. LABOR COST CALCULATION. 36 Nages and Salaries. Fringe Benefits. 36 38 Chapter Page V. ENERGY COST... Summary for Champion International Corporation's Harvesting Unit g2 60 15 List of Equipment in Champion's Harvesting Unit N2 61 Table page 16 Breakdown of Workers in Champion's Harvesting Unit 42 and Their Respective Salary or Wage. . 62 17 Monthly...

Kusmertz, Timothy Jon

1983-01-01T23:59:59.000Z

457

E-Print Network 3.0 - annual average daily traffic Sample Search...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Data Systems 2000. Annual Average Daily Truck Traffic on the California State... Lockout and Non-Lockout Weekdays Average Daily Traffic Volume (vehday) All Cars Trucks ......

458

E-Print Network 3.0 - average daily traffic Sample Search Results  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Data Systems 2000. Annual Average Daily Truck Traffic on the California State... Lockout and Non-Lockout Weekdays Average Daily Traffic Volume (vehday) All Cars Trucks...

459

E-Print Network 3.0 - averaged pulsar profiles Sample Search...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

for: averaged pulsar profiles Page: << < 1 2 3 4 5 > >> 1 astroph9911319 Pulsar Astronomy ---2000 and Beyond Summary: with higher than average surface dipole magnetic fields....

460

E-Print Network 3.0 - average power ratio Sample Search Results  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

a wind turbine Summary: of pairs of poles over the average power is also studied. Index Terms-- average wind power, battery... charging, permanent magnet synchronous machine. I....

Note: This page contains sample records for the topic "average installed capital" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


461

E-Print Network 3.0 - average high energy Sample Search Results  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

g Energy and power are time averaged and normally spatially... averaged g Relate energy (density) to power (intensity) The Energy Source Simulation Method 12;g... ms...

462

E-Print Network 3.0 - average body surface Sample Search Results  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

averages. The chemical... to the en- semble averages for pressure and configurational energy are summarized in Table II. Three-body... Three-body interactions in fluids from...

463

Ensemble bayesian model averaging using markov chain Monte Carlo sampling  

SciTech Connect (OSTI)

Bayesian model averaging (BMA) has recently been proposed as a statistical method to calibrate forecast ensembles from numerical weather models. Successful implementation of BMA however, requires accurate estimates of the weights and variances of the individual competing models in the ensemble. In their seminal paper (Raftery etal. Mon Weather Rev 133: 1155-1174, 2(05)) has recommended the Expectation-Maximization (EM) algorithm for BMA model training, even though global convergence of this algorithm cannot be guaranteed. In this paper, we compare the performance of the EM algorithm and the recently developed Differential Evolution Adaptive Metropolis (DREAM) Markov Chain Monte Carlo (MCMC) algorithm for estimating the BMA weights and variances. Simulation experiments using 48-hour ensemble data of surface temperature and multi-model stream-flow forecasts show that both methods produce similar results, and that their performance is unaffected by the length of the training data set. However, MCMC simulation with DREAM is capable of efficiently handling a wide variety of BMA predictive distributions, and provides useful information about the uncertainty associated with the estimated BMA weights and variances.

Vrugt, Jasper A [Los Alamos National Laboratory; Diks, Cees G H [NON LANL; Clark, Martyn P [NON LANL

2008-01-01T23:59:59.000Z

464

Long-term average performance benefits of parabolic trough improvements  

SciTech Connect (OSTI)

Improved parabolic trough concentrating collectors will result from better design, improved fabrication techniques, and the development and utilization of improved materials. The difficulty of achieving these improvements varies as does their potential for increasing parabolic trough performance. The purpose of this analysis is to quantify the relative merit of various technology advancements in improving the long-term average performance of parabolic trough concentrating collectors. The performance benefits of improvements are determined as a function of operating temperature for north-south, east-west, and polar mounted parabolic troughs. The results are presented graphically to allow a quick determination of the performance merits of particular improvements. Substantial annual energy gains are shown to be attainable. Of the improvements evaluated, the development of stable back-silvered glass reflective surfaces offers the largest performance gain for operating temperatures below 150/sup 0/C. Above 150/sup 0/C, the development of trough receivers that can maintain a vacuum is the most significant potential improvement. The reduction of concentrator slope errors also has a substantial performance benefit at high operating temperatures.

Gee, R.; Gaul, H.W.; Kearney, D.; Rabl, A.

1980-03-01T23:59:59.000Z

465

Nonlocal effective-average-action approach to crystalline phantom membranes  

SciTech Connect (OSTI)

We investigate the properties of crystalline phantom membranes, at the crumpling transition and in the flat phase, using a nonperturbative renormalization group approach. We avoid a derivative expansion of the effective average action and instead analyze the full momentum dependence of the elastic coupling functions. This leads to a more accurate determination of the critical exponents and further yields the full momentum dependence of the correlation functions of the in-plane and out-of-plane fluctuation. The flow equations are solved numerically for D=2 dimensional membranes embedded in a d=3 dimensional space. Within our approach we find a crumpling transition of second order which is characterized by an anomalous exponent {eta}{sub c}{approx_equal}0.63(8) and the thermal exponent {nu}{approx_equal}0.69. Near the crumpling transition the order parameter of the flat phase vanishes with a critical exponent {beta}{approx_equal}0.22. The flat phase anomalous dimension is {eta}{sub f}{approx_equal}0.85 and the Poisson's ratio inside the flat phase is found to be {sigma}{sub f}{approx_equal}-1/3. At the crumpling transition we find a much larger negative value of the Poisson's ratio {sigma}{sub c}{approx_equal}-0.71(5). We discuss further in detail the different regimes of the momentum dependent fluctuations, both in the flat phase and in the vicinity of the crumpling transition, and extract the crossover momentum scales which separate them.

Hasselmann, N. [Max Planck Institute for Solid State Research, Heisenbergstrasse 1, D-70569 Stuttgart (Germany); International Institute of Physics, Universidade Federal do Rio Grande do Norte, 59072-970, Natal, RN (Brazil); Braghin, F. L. [International Institute of Physics, Universidade Federal do Rio Grande do Norte, 59072-970, Natal, RN (Brazil); Instituto de Fisica, Universidade Federal de Goias, P. B. 131, Campus II, 74001-970, Goiania, GO (Brazil)

2011-03-15T23:59:59.000Z

466

Annual Report on U.S. Wind Power Installation, Cost, and Performance Trends: 2006  

E-Print Network [OSTI]

Annual Report on U.S. Wind Power Installation, Cost, and3 U.S. Wind Power Capacity Increased by 27% inAre Significant. . . . . . . 9 Wind Power Prices Are Up in

2008-01-01T23:59:59.000Z

467

INSTALLATION CERTIFICATE CF-6R-ENV-01 Envelope Insulation; Roofing; Fenestration (Page 1 of 3)  

E-Print Network [OSTI]

INSTALLATION CERTIFICATE CF-6R-ENV-01 Envelope ­ Insulation; Roofing; Fenestration (Page 1 of 3:__________________________________ Brand Name:_______________________________ Thickness (inches):_________________________ Thermal:_______________________________ Thickness (inches):_________________________ Thermal Resistance (R-Value):_________________ Perimeter

468

The LPMS-V installation and operational experience at Arkansas nuclear one  

SciTech Connect (OSTI)

This paper describes a new replacement system for the existing vibrations and loose parts monitoring system for the Arkansas Nuclear One (ANO) units 1 and 2, in Russellville, Arkansas. The installation and operational history are also discussed.

Lexa, A.F. [Babcock and Wilcox Company, Lynchburg, VA (United States)]: Hudson, E. [Entergy Operations, Inc., Russelville, AR (United States)

1995-12-31T23:59:59.000Z

469

Atomic Energy and Radioactive Substances: Licensing and Regulation of Sites: The Nuclear Installations Regulations, 1962   

E-Print Network [OSTI]

These regulations, made by the Minister of Power and the Secretary of State for Scotland acting jointly, prescribe for the purpose of subsection (1)(b) of section one of the Nuclear Installations (Licensing and Insurance) Act, 1959, certain classes...

Wood, Richard; Maclay, John. S.

1962-01-01T23:59:59.000Z

470

PV Installation Labor Market Analysis and PV JEDI Tool Developments (Presentation)  

SciTech Connect (OSTI)

The potential economic benefits of the growing renewable energy sector have led to increased federal, state, and local investments in solar industries, including federal grants for expanded workforce training for U.S. solar installers. However, there remain gaps in the data required to understand the size and composition of the workforce needed to meet the demand for solar power. Through primary research on the U.S. solar installation employer base, this report seeks to address that gap, improving policymakers and other solar stakeholders understanding of both the evolving needs of these employers and the economic opportunity associated with solar market development. Included are labor market data covering current U.S. employment, expected industry growth, and employer skill preferences for solar installation-related occupations. This study offers an in-depth look at the solar installation sectors. A study published by the Solar Foundation in October 2011 provides a census of labor data across the entire solar value chain.

Friedman, B.

2012-06-01T23:59:59.000Z

471

BUILDOUT AND UPGRADE OF CENTRAL EMERGENCY GENERATOR SYSTEM, GENERATOR 3 AND 4 ELECTRICAL INSTALLATION  

SciTech Connect (OSTI)

SECTION 01000—SUMMARY OF WORK PART 1—GENERAL 1.1 SUMMARY The work to be performed under this project consists of providing the labor, equipment, and materials to perform "Buildout and Upgrade of Central Emergency Generator System, Generator 3 and 4 Electrical Installation" for the National Aeronautics and Space Administration at the Dryden Flight Research Center (NASA/DFRC), Edwards, California 93523. All modifications to existing substations and electrical distribution systems are the responsibility of the contractor. It is the contractor’s responsibility to supply a complete and functionally operational system. The work shall be performed in accordance with these specifications and the related drawings. The work of this project is defined by the plans and specifications contained and referenced herein. This work specifically includes but is not limited to the following: Scope of Work - Installation 1. Install all electrical wiring and controls for new generators 3 and 4 to match existing electrical installation for generators 1 and 2 and in accordance with drawings. Contractor shall provide as-built details for electrical installation. 2. Install battery charger systems for new generators 3 and 4 to match existing battery charging equipment and installation for generators 1 and 2. This may require exchange of some battery charger parts already on-hand. Supply power to new battery chargers from panel and breakers as shown on drawings. Utilize existing conduits already routed to generators 3 and 4 to field route the new wiring in the most reasonable way possible. 3. Install electrical wiring for fuel/lube systems for new generators 3 and 4 to match existing installation for generators 1 and 2. Supply power to lube oil heaters and fuel system (day tanks) from panel and breakers as shown on drawings. Utilize existing conduits already routed to generators 3 and 4 to field route the new wiring in the most reasonable way possible. Add any conduits necessary to complete wiring to fuel systems. 4. Install power to new dampers/louvers from panel and breakers as shown on drawings. Wiring shall be similar to installation to existing dampers/louvers. Utilize existing conduits already routed to louver areas to field route the new wiring in the most reasonable way possible. Add any conduits necessary to complete wiring to new dampers/louvers. 5. Install power to jacket water heaters for new generators 3 and 4 from panel and breakers as shown on drawings. Utilize existing conduits already routed to generators 3 and 4 to field route the new wiring in the most reasonable way possible. 6. Install new neutral grounding resistor and associated parts and wiring for new generators 3 and 4 to match existing installation for generators 1 and 2. Grounding resistors will be Government Furnished Equipment (GFE). 7. Install two new switchgear sections, one for generator #3 and one for generator #4, to match existing generator #1 cubicle design and installation and in accordance with drawings and existing parts lists. This switchgear will be provided as GFE. 8. Ground all new switchgear, generators 3 and 4, and any other new equipment to match existing grounding connections for generators 1 and 2, switchgear and other equipment. See drawings for additional details. Grounding grid is already existing. Ensure that all grounding meets National Electrical Code requirements. 9. Cummins DMC control for the generator and switchgear syste

Gary D. Seifert; G. Shawn West; Kurt S. Myers; Jim Moncur

2006-07-01T23:59:59.000Z

472

Art installation of conic sea and peculiar angels and its affordances  

E-Print Network [OSTI]

Installations attempt to expose everyday space by depicting an environment that appears normal yet has been altered in perceptibly unexpected ways. Such environments are typically designed to re-orient participants, giving them the feeling...

Cooper, Trina Erica

2009-05-15T23:59:59.000Z

473

Behavior of 10 full-scale ground anchors installed in stiff clay  

E-Print Network [OSTI]

Results from load tests conducted on ten, full-scale instrumented ground anchors installed in stiff clay, illustrated that anchor performance is load-history dependent. Anchors having shorter bonded lengths performed significantly better than...

Powers, William Francis

1993-01-01T23:59:59.000Z

474

Monitoring and Mitigation Alternatives for Protection of North Atlantic Right Whales during Offshore Wind Farm Installation  

SciTech Connect (OSTI)

Progress report on defining and determining monitoring and mitigation measures for protecting North Atlantic Right Whales from the effects of pile driving and other activities associated with installation of offshore wind farms.

Carlson, Thomas J.; Halvorsen, Michele B.; Matzner, Shari; Copping, Andrea E.; Stavole, Jessica

2012-09-01T23:59:59.000Z

475

Building-Integrated Photovoltaics (BIPV) in the Residential Section: An Analysis of Installed Rooftop Prices (Presentation)  

SciTech Connect (OSTI)

This powerpoint presentation to be presented at the World Renewable Energy Forum on May 17, 2012, in Denver, CO, discusses building-integrated photovoltaics (BIPV) in the residential section and includes an analysis of installed rooftop prices.

James, T.; Goodrich, A.; Woodhouse, M.; Margolis, R.; Ong, S.

2012-06-01T23:59:59.000Z

476

Wildlife Photography for Fun and Profit: Constructing and Installing Wildlife Photography Blinds  

E-Print Network [OSTI]

. *Extension Ecotourism Program Specialist, The Texas A&M University System WILDLIFE Photography Miles Phillips* for Fun and Profit: Constructing and Installing Wildlife Photography Blinds B-6187 3/06 Types of Blinds Surface blinds Most photographers...

Phillips, Miles

2006-04-17T23:59:59.000Z

477

DCC Digital Curation Manual: Instalment on Open Source for Digital Curation   

E-Print Network [OSTI]

Instalment on the role of open source software within the digital curation lifecycle. Describes a range of explicit digital curation application areas for open source, some examples of existing uses of open source software, ...

McHugh, Andrew

2005-08-01T23:59:59.000Z

478

Analysis of heat pumps installed in family housing at Hunter Army Air Field  

SciTech Connect (OSTI)

The US Army Forces Command (FORSCOM) tasked Pacific Northwest Laboratory (PNL) in support of the US Department of Energy (DOE) Federal Energy Management Program (FEMP) to conduct a postconstruction evaluation of the air-source heat pumps installed in family housing at Hunter Army Air Field (AAF). The objective of this project was to investigate and resolve concerns about an increase in energy costs at Hunter AAF following the installation of heat pumps in November 1992. After completing several analyses and a field inspection of the heat pumps in family housing at Hunter AAF, the following conclusions were made: the installation of air-source heat pumps reduced the annual energy cost in family housing by $46,672 in 1993; the heat pump thermostat controls in Hunter AAF family housing appear to be incorrectly installed; and the Hunter AAF electric utility bill increased 10% during the first 6 months of 1993 compared to the first 6 months of 1992.

Parker, S.A.

1994-08-01T23:59:59.000Z

479

Permits to Install,New Source Review (PTI,NSR)  (Michigan)  

Broader source: Energy.gov [DOE]

Rule 201 of the Michigan Air Pollution Control Rules requires a person to obtain an approved Permit to Install for any potential source of air pollution unless the source is exempt from the...

480

Microsoft Word - CX-RossComplexComcastFiberInstall_WEB.doc  

Broader source: Energy.gov (indexed) [DOE]

1 REPLY TO ATTN OF: KEP-4 SUBJECT: Environmental Clearance Memorandum Dawneen Dostert Realty Specialist - TERR-LMT Proposed Action: Allow installation of new fiber optic cable PP&A...

Note: This page contains sample records for the topic "average installed capital" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


481

Net Zero Energy Military Installations: A Guide to Assessment and Planning  

SciTech Connect (OSTI)

The U.S. Department of Defense (DoD) recognizes the strategic importance of energy to its mission, and is working to reduce energy consumption and enhance energy self-sufficiency by drawing on local clean energy sources. A joint initiative formed between DoD and the U.S. Department of Energy (DOE) in 2008 to address military energy use led to a task force to examine the potential for net zero energy military installations, which would produce as much energy on site as they consume in buildings, facilities, and fleet vehicles. This report presents an assessment and planning process to examine military installations for net zero energy potential. Net Zero Energy Installation Assessment (NZEIA) presents a systematic framework to analyze energy projects at installations while balancing other site priorities such as mission, cost, and security.

Booth, S.; Barnett, J.; Burman, K.; Hambrick, J.; Westby, R.

2010-08-01T23:59:59.000Z

482

Net Zero Energy Military Installations: A Guide to Assessment and Planning  

Office of Energy Efficiency and Renewable Energy (EERE)

In 2008, DoD and DOE defined a joint initiative to address military energy use by identifying specific actions to reduce energy demand and increase use of renewable energy on DoD installations.

483

Tracking the Sun V An Historical Summary of the Installed Price  

E-Print Network [OSTI]

Tracking the Sun V An Historical Summary of the Installed Price of Photovoltaics in the United States from 1998 to 2011 Galen Barbose NaĂŻm Darghouth Ryan Wiser November 2012 #12;Tracking the Sun V

484

Consider Installing High-Pressure Boilers with Backpressure Turbine-Generators  

SciTech Connect (OSTI)

This revised ITP tip sheet on installing high-pressure boilers provides how-to advice for improving industrial steam systems using low-cost, proven practices and technologies.

Not Available

2006-01-01T23:59:59.000Z

485

The ATLAS Software Installation System v2: a highly available system to install and validate Grid and Cloud sites via Panda  

E-Print Network [OSTI]

The ATLAS Installation System v2 is the evolution of the original system, used since 2003. The original tool has been completely re-designed in terms of database backend and components, adding support for submission to multiple backends, including the original WMS and the new Panda modules. The database engine has been changed from plain MySQL to Galera/Percona and the table structure has been optimized to allow a full High-Availability (HA) solution over WAN. The servlets, running on each frontend, have been also decoupled from local settings, to allow an easy scalability of the system, including the possibility of an HA system with multiple sites. The clients can also be run in multiple copies and in different geographical locations, and take care of sending the installation and validation jobs to the target Grid or Cloud sites. Moreover, the Installation DB is used as source of parameters by the automatic agents running in CVMFS, in order to install the software and distribute it to the sites. The system i...

De Salvo, Alessandro; The ATLAS collaboration; Smirnov, Yuri; Sanchez, Arturo

2015-01-01T23:59:59.000Z

486

Facility Energy Decision System (FEDS) Assessment Report for US Army Garrison, Japan - Honshu Installations  

SciTech Connect (OSTI)

This report documents an assessment was performed by a team of engineers from Pacific Northwest National Laboratory (PNNL) under contract to the Installation Management Command (IMCOM) Pacific Region Office (PARO). The effort used the Facility Energy Decision System (FEDS) model to determine how energy is consumed at five U.S. Army Garrison-Japan (USAG-J) installations in the Honshu area, identify the most cost-effective energy retrofit measures, and calculate the potential energy and cost savings.

Kora, Angela R.; Brown, Daryl R.; Dixon, Douglas R.

2010-03-09T23:59:59.000Z

487

Installation Of Service Connections For Sensors Or Transmitters In Buried Water Pipes  

DOE Patents [OSTI]

A system for installing warning units in a buried pipeline. A small hole is drilled in the ground to the pipeline. A collar is affixed to one of the pipes of the pipeline. A valve with an internal passage is connected to the collar. A hole is drilled in the pipe. A warning unit is installed in the pipe by moving the warning unit through the internal passage, the collar, and the hole in the pipe.

Burnham, Alan K. (Livermore, CA); Cooper, John F. (Oakland, CA)

2006-02-21T23:59:59.000Z

488

PART 1 OF TUTORIAL ON EXTREMES TOOLKIT (1) Installation of R software  

E-Print Network [OSTI]

PART 1 OF TUTORIAL ON EXTREMES TOOLKIT (1) Installation of R software R-2.9.2-win32.exe Use default options (2) Installation of Extremes Toolkit extRemes (R package for extreme value analysis): extRemes_1.60.zip ismev (R package used by extRemes): ismev_1.34.zip Lmoments (R package used by extRemes): Lmoments

Katz, Richard

489

Proposal for the award of a contract for the design, supply and installation of piping and accessories at CERN  

E-Print Network [OSTI]

Proposal for the award of a contract for the design, supply and installation of piping and accessories at CERN

2014-01-01T23:59:59.000Z

490

Proposal for the award of a contract for the supply and installation of two thyristor-controlled reactors for LEP  

E-Print Network [OSTI]

Proposal for the award of a contract for the supply and installation of two thyristor-controlled reactors for LEP

1986-01-01T23:59:59.000Z

491

Proposal for the Award of a Contract for the Supply and Installation of Two Thyristor-Controlled Reactor Plants  

E-Print Network [OSTI]

Proposal for the Award of a Contract for the Supply and Installation of Two Thyristor-Controlled Reactor Plants

1991-01-01T23:59:59.000Z

492

Proposal for the Award of a Contract for Maintenance, Operation and Minor Installation Work for CERN Cooling and HVAC Systems  

E-Print Network [OSTI]

Proposal for the Award of a Contract for Maintenance, Operation and Minor Installation Work for CERN Cooling and HVAC Systems

1996-01-01T23:59:59.000Z

493

Certification for Small Wind Turbine Installers: What's the Hang Up?; Preprint  

SciTech Connect (OSTI)

Several programs have been implemented to support the advancement of a professional, mature small wind industry and to ensure that this industry moves forward in a sustainable direction. The development of a standard for small wind turbine systems and the creation of the Small Wind Certification Council support small wind technology that is reliable and safe. Consumers and incentive programs will ultimately rely on certification to differentiate among systems sold in the U.S. market. Certification of small wind installers is yet another component deemed necessary for this industry to expand. The National Renewable Energy Laboratory, under the guidance and funding support of the U.S. Department of Energy, supported the development of small wind system installer certification provided via the North American Board of Certified Energy Practitioners. However, the small wind community is not supportive of the installer certification. There are currently only nine certified installers in the U.S. pool. This paper provides an overview of the installer certification program and why more small wind turbine installers are not pursuing this certification.

Oteri, F.; Sinclair, K.

2012-03-01T23:59:59.000Z

494

Tracking the Sun: The Installed Cost of Photovoltaics in the U.S. from 1998-2007  

E-Print Network [OSTI]

10-100 kW >100 kW Tracking the Sun: The Installed Cost ofout over five years. Tracking the Sun: The Installed Cost ofU.S. from 1998-2007 Tracking the Sun: The Installed Cost of

Wiser, Ryan

2009-01-01T23:59:59.000Z

495

Tracking the Sun II: The Installed Cost of Photovoltaics in the U.S. from 1998-2008  

E-Print Network [OSTI]

2008 BACK PAGE Tracking the Sun II: The Installed Cost of10-100 kW >100 kW Tracking the Sun II: The Installed Cost ofSystems MW Total Tracking the Sun II: The Installed Cost of

Barbose, Galen L

2010-01-01T23:59:59.000Z

496

Cost of a Ride: The Effects of Densities on Fixed-Guideway Transit Ridership and Capital Costs  

E-Print Network [OSTI]

mile. Soaring capital investment costs are today’ s biggestof riders for the investment costs? If so, what minimumrelationship between investment costs and urban densities

Guerra, Erick; Cervero, Robert

2010-01-01T23:59:59.000Z

497

Assessment of capital requirements for alternative fuels infrastructure under the PNGV program  

SciTech Connect (OSTI)

This paper presents an assessment of the capital requirements of using six different fuels in the vehicles with tripled fuel economy (3X vehicles) that the Partnership for a new Generation of Vehicles is currently investigating. The six fuels include two petroleum-based fuels (reformulated gasoline and low-sulfur diesel) and four alternative fuels (methanol, ethanol, dimethyl ether, and hydrogen). This study develops estimates of cumulative capital needs for establishing fuels production and distribution infrastructure to accommodate 3X vehicle fuel needs. Two levels of fuel volume-70,000 barrels per day and 1.6 million barrels per day-were established for meeting 3X-vehicle fuel demand. As expected, infrastructure capital needs for the high fuel demand level are much higher than for the low fuel demand level. Between fuel production infrastructure and distribution infrastructure, capital needs for the former far exceed those for the latter. Among the four alternative fuels, hydrogen bears the largest capital needs for production and distribution infrastructure.

Stork, K.; Singh, M.; Wang, M.; Vyas, A.

1998-12-31T23:59:59.000Z

498

Tracking the Sun VI: An Historical Summary of the Installed Price of Photovoltaics in the United States from 1998 to 2012  

E-Print Network [OSTI]

Laboratory. Tracking the Sun VI: The Installed Price ofRange ?10 kW Tracking the Sun VI: The Installed Price ofRange ?10 kW Tracking the Sun VI: The Installed Price of

Barbose, Galen

2014-01-01T23:59:59.000Z

499

Tracking the Sun V: An Historical Summary of the Installed Price of Photovoltaics in the United States from 1998 to 2011  

E-Print Network [OSTI]

Council, Inc. Tracking the Sun V: The Installed Price ofapplications). Tracking the Sun V: The Installed Price ofEnergy Agency. Tracking the Sun V: The Installed Price of

Barbose, Galen

2014-01-01T23:59:59.000Z

500

Tracking the Sun IV: An Historical Summary of the Installed Cost of Photovoltaics in the United States from 1998 to 2010  

E-Print Network [OSTI]

The Installed Cost of Photovoltaics in the U.S. from 1998-The Installed Cost of Photovoltaics in the U.S. from 1998-The Installed Cost of Photovoltaics in the U.S. from 1998-

Darghouth, Naim

2012-01-01T23:59:59.000Z