National Library of Energy BETA

Sample records for area capital costs

  1. Transmission line capital costs

    SciTech Connect (OSTI)

    Hughes, K.R.; Brown, D.R.

    1995-05-01

    The displacement or deferral of conventional AC transmission line installation is a key benefit associated with several technologies being developed with the support of the U.S. Department of Energy`s Office of Energy Management (OEM). Previous benefits assessments conducted within OEM have been based on significantly different assumptions for the average cost per mile of AC transmission line. In response to this uncertainty, an investigation of transmission line capital cost data was initiated. The objective of this study was to develop a database for preparing preliminary estimates of transmission line costs. An extensive search of potential data sources identified databases maintained by the Bonneville Power Administration (BPA) and the Western Area Power Administration (WAPA) as superior sources of transmission line cost data. The BPA and WAPA data were adjusted to a common basis and combined together. The composite database covers voltage levels from 13.8 to 765 W, with cost estimates for a given voltage level varying depending on conductor size, tower material type, tower frame type, and number of circuits. Reported transmission line costs vary significantly, even for a given voltage level. This can usually be explained by variation in the design factors noted above and variation in environmental and land (right-of-way) costs, which are extremely site-specific. Cost estimates prepared from the composite database were compared to cost data collected by the Federal Energy Regulatory Commission (FERC) for investor-owned utilities from across the United States. The comparison was hampered because the only design specifications included with the FERC data were voltage level and line length. Working within this limitation, the FERC data were not found to differ significantly from the composite database. Therefore, the composite database was judged to be a reasonable proxy for estimating national average costs.

  2. Electric power substation capital costs (Technical Report) |...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    ... Subject: 24 POWER TRANSMISSION AND DISTRIBUTION; POWER SUBSTATIONS; CAPITALIZED COST; CALCULATION METHODS; PLANNING; COST ESTIMATION; MATHEMATICAL MODELS Word Cloud More Like This ...

  3. Electric power substation capital costs

    SciTech Connect (OSTI)

    Dagle, J.E.; Brown, D.R.

    1997-12-01

    The displacement or deferral of substation equipment is a key benefit associated with several technologies that are being developed with the support of the US Department of Energy`s Office of Utility Technologies. This could occur, for example, as a result of installing a distributed generating resource within an electricity distribution system. The objective of this study was to develop a model for preparing preliminary estimates of substation capital costs based on rudimentary conceptual design information. The model is intended to be used by energy systems analysts who need ``ballpark`` substation cost estimates to help establish the value of advanced utility technologies that result in the deferral or displacement of substation equipment. This cost-estimating model requires only minimal inputs. More detailed cost-estimating approaches are recommended when more detailed design information is available. The model was developed by collecting and evaluating approximately 20 sets of substation design and cost data from about 10 US sources, including federal power marketing agencies and private and public electric utilities. The model is principally based on data provided by one of these sources. Estimates prepared with the model were compared with estimated and actual costs for the data sets received from the other utilities. In general, good agreement (for conceptual level estimating) was found between estimates prepared with the cost-estimating model and those prepared by the individual utilities. Thus, the model was judged to be adequate for making preliminary estimates of typical substation costs for US utilities.

  4. QGESS: Capital Cost Scaling Methodology

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    the tonnes of CO2 utilized. The costs of the process are to include infrastructure, raw materials, processing, byproduct disposal, and utilities costs, as well as any other costs....

  5. LIFE Cost of Electricity, Capital and Operating Costs

    SciTech Connect (OSTI)

    Anklam, T

    2011-04-14

    Successful commercialization of fusion energy requires economic viability as well as technical and scientific feasibility. To assess economic viability, we have conducted a pre-conceptual level evaluation of LIFE economics. Unit costs are estimated from a combination of bottom-up costs estimates, working with representative vendors, and scaled results from previous studies of fission and fusion plants. An integrated process model of a LIFE power plant was developed to integrate and optimize unit costs and calculate top level metrics such as cost of electricity and power plant capital cost. The scope of this activity was the entire power plant site. Separately, a development program to deliver the required specialized equipment has been assembled. Results show that LIFE power plant cost of electricity and plant capital cost compare favorably to estimates for new-build LWR's, coal and gas - particularly if indicative costs of carbon capture and sequestration are accounted for.

  6. Project Profile: Concurrent Optimization of Component Capital Cost and

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Expected Operations and Management (SuNLaMP) | Department of Energy Project Profile: Concurrent Optimization of Component Capital Cost and Expected Operations and Management (SuNLaMP) Project Profile: Concurrent Optimization of Component Capital Cost and Expected Operations and Management (SuNLaMP) Funding Program: SuNLaMP SunShot Subprogram: CSP Location: National Renewable Energy Laboratory, Golden, CO SunShot Award Amount: $3,000,000 This project is developing and validating an open

  7. Discrete Event Modeling of Algae Cultivation and Harvesting at Commercial Scale: Capital Costs, Operating Costs, and System Bottlenecks

    SciTech Connect (OSTI)

    Lacey, Ph.D, P.E., Ronald E.

    2012-07-16

    Discrete Event Modeling of Algae Cultivation and Harvesting at Commercial Scale: Capital Costs, Operating Costs, and System Bottlenecks

  8. New developments in capital cost estimating

    SciTech Connect (OSTI)

    Stutz, R.A.; Zocher, M.A.

    1988-01-01

    The new developments in cost engineering revolve around the ability to capture information that in the past could not be automated. The purpose of automation is not to eliminate the expert cost engineer. The goal is to use available technology to have more information available to the professionals in the cost engineering field. In that sense, the demand for expertise increases in order to produce the highest quality estimate and project possible from all levels of cost engineers. We cannot overemphasize the importance of using a good source of expert information in building these types of programs. ''Garbage in, garbage out'' still applies in this form of programming. Expert systems technology will become commonplace in many vertical markets; it is important to undersand what can and cannot be accomplished in our field, and where this technology will lead us in the future.

  9. Accessing Low-Cost Capital Through Securitization (Poster)

    SciTech Connect (OSTI)

    Mendelsohn, M.

    2014-10-01

    Poster for Solar Power International conference presents information on NREL's effort to open capital markets through securitization via Solar Access to Public Capital (SAPC) working group's efforts.

  10. Wind-To-Hydrogen Project: Electrolyzer Capital Cost Study

    SciTech Connect (OSTI)

    Saur, G.

    2008-12-01

    This study is being performed as part of the U.S. Department of Energy and Xcel Energy's Wind-to-Hydrogen Project (Wind2H2) at the National Renewable Energy Laboratory. The general aim of the project is to identify areas for improving the production of hydrogen from renewable energy sources. These areas include both technical development and cost analysis of systems that convert renewable energy to hydrogen via water electrolysis. Increased efficiency and reduced cost will bring about greater market penetration for hydrogen production and application. There are different issues for isolated versus grid-connected systems, however, and these issues must be considered. The manner in which hydrogen production is integrated in the larger energy system will determine its cost feasibility and energy efficiency.

  11. Power plant capital investment cost estimates: current trends and sensitivity to economic parameters

    SciTech Connect (OSTI)

    Not Available

    1980-06-01

    This report describes power plant capital investment cost studies that were carried out as part of the activities of the Plans and Analysis Division, Office of Nuclear Energy Programs, US Department of Energy. The activities include investment cost studies prepared by an architect-engineer, including trends, effects of environmental and safety requirements, and construction schedules. A computer code used to prepare capital investment cost estimates under varying economic conditions is described, and application of this code is demonstrated by sensitivity studies.

  12. Table 1. Updated estimates of power plant capital and operating costs

    U.S. Energy Information Administration (EIA) Indexed Site

    Updated estimates of power plant capital and operating costs" ,"Plant Characteristics",,,"Plant Costs (2012$)" ,"Nominal Capacity (MW)","Heat Rate (Btu/kWh)",,"Overnight Capital Cost ($/kW)","Fixed O&M Cost ($/kW-yr)","Variable O&M Cost ($/MWh)" ,,,,,,,"NEMS Input" " Coal" "Single Unit Advanced PC",650,8800,,3246,37.8,4.47,"N" "Dual Unit Advanced

  13. Updated Capital Cost Estimates for Utility Scale Electricity Generating Plants

    Reports and Publications (EIA)

    2013-01-01

    The current and future projected cost and performance characteristics of new electric generating capacity are a critical input into the development of energy projections and analyses.

  14. Best Practices for Controlling Capital Costs in Net Zero Energy...

    Broader source: Energy.gov (indexed) [DOE]

    construction, it is necessary to demonstrate that NZE can be achieved cost effectively. This project aims to increase and accelerate the adoption of NZE design and construction ...

  15. Philadelphia gas works medium-Btu coal gasification project: capital and operating cost estimate, financial/legal analysis, project implementation

    SciTech Connect (OSTI)

    Not Available

    1981-12-01

    This volume of the final report is a compilation of the estimated capital and operating costs for the project. Using the definitive design as a basis, capital and operating costs were developed by obtaining quotations for equipment delivered to the site. Tables 1.1 and 1.2 provide a summary of the capital and operating costs estimated for the PGW Coal Gasification Project. In the course of its Phase I Feasibility Study of a medium-Btu coal-gas facility, Philadelphia Gas Works (PGW) identified the financing mechanism as having great impact on gas cost. Consequently, PGW formed a Financial/Legal Task Force composed of legal, financial, and project analysis specialists to study various ownership/management options. In seeking an acceptable ownership, management, and financing arrangement, certain ownership forms were initially identified and classified. Several public ownership, private ownership, and third party ownership options for the coal-gas plant are presented. The ownership and financing forms classified as base alternatives involved tax-exempt and taxable financing arrangements and are discussed in Section 3. Project implementation would be initiated by effectively planning the methodology by which commercial operation will be realized. Areas covered in this report are sale of gas to customers, arrangements for feedstock supply and by-product disposal, a schedule of major events leading to commercialization, and a plan for managing the implementation.

  16. A model of the Capital Cost of a natural gas-fired fuel cell based Central Utilities Plant

    SciTech Connect (OSTI)

    Not Available

    1993-06-30

    This model defines the methods used to estimate the cost associated with acquisition and installation of capital equipment of the fuel cell systems defined by the central utility plant model. The capital cost model estimates the cost of acquiring and installing the fuel cell unit, and all auxiliary equipment such as a boiler, air conditioning, hot water storage, and pumps. The model provides a means to adjust initial cost estimates to consider learning associated with the projected level of production and installation of fuel cell systems. The capital cost estimate is an input to the cost of ownership analysis where it is combined with operating cost and revenue model estimates.

  17. Controlling Capital Costs in High Performance Office Buildings: A Review of Best Practices for Overcoming Cost Barriers

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Controlling Capital Costs in High Performance Office Buildings: A Review of Best Practices for Overcoming Cost Barriers Preprint Shanti Pless and Paul Torcellini To be presented at the ACEEE Summer Study on Energy Efficiency in Buildings Pacific Grove, California August 12-17, 2012 Conference Paper NREL/CP-5500-55264 May 2012 NOTICE The submitted manuscript has been offered by an employee of the Alliance for Sustainable Energy, LLC (Alliance), a contractor of the US Government under Contract No.

  18. Controlling Capital Costs in High Performance Office Buildings: A Review of Best Practices for Overcoming Cost Barriers

    SciTech Connect (OSTI)

    Pless, S.; Torcellini, P.

    2012-05-01

    This paper presents a set of 15 best practices for owners, designers, and construction teams of office buildings to reach high performance goals for energy efficiency, while maintaining a competitive budget. They are based on the recent experiences of the owner and design/build team for the Research Support Facility (RSF) on National Renewable Energy Facility's campus in Golden, CO, which show that achieving this outcome requires each key integrated team member to understand their opportunities to control capital costs.

  19. Landed Costs of Imported Crude by Area

    U.S. Energy Information Administration (EIA) Indexed Site

    Area (Dollars per Barrel) Period: Monthly Annual Download Series History Download Series History Definitions, Sources & Notes Definitions, Sources & Notes Area Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 View History Average Landed Cost 27.34 26.97 31.99 35.42 40.63 43.87 1973-2016 Persian Gulf 30.92 30.69 34.60 38.00 42.33 45.05 1996-2016 Total OPEC 28.98 29.49 33.87 36.78 42.34 45.06 1973-2016 Non OPEC 26.25 25.42 30.39 34.42 39.56 43.08 1973-2016 Selected Countries Canada 26.21 24.61

  20. Access to Capital

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    IPR 2008 Capital Investment Review CIR 2012 Quarterly Business Review Focus 2028 2011 Strategic Capital Discussions Access to Capital Debt Optimization Asset Management Cost...

  1. 2011 Strategic Capital Discussions

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    IPR 2008 Capital Investment Review CIR 2012 Quarterly Business Review Focus 2028 2011 Strategic Capital Discussions Access to Capital Debt Optimization Asset Management Cost...

  2. Developing a Cost Model and Methodology to Estimate Capital Costs for Thermal Energy Storage

    SciTech Connect (OSTI)

    Glatzmaier, G.

    2011-12-01

    This report provides an update on the previous cost model for thermal energy storage (TES) systems. The update allows NREL to estimate the costs of such systems that are compatible with the higher operating temperatures associated with advanced power cycles. The goal of the Department of Energy (DOE) Solar Energy Technology Program is to develop solar technologies that can make a significant contribution to the United States domestic energy supply. The recent DOE SunShot Initiative sets a very aggressive cost goal to reach a Levelized Cost of Energy (LCOE) of 6 cents/kWh by 2020 with no incentives or credits for all solar-to-electricity technologies.1 As this goal is reached, the share of utility power generation that is provided by renewable energy sources is expected to increase dramatically. Because Concentrating Solar Power (CSP) is currently the only renewable technology that is capable of integrating cost-effective energy storage, it is positioned to play a key role in providing renewable, dispatchable power to utilities as the share of power generation from renewable sources increases. Because of this role, future CSP plants will likely have as much as 15 hours of Thermal Energy Storage (TES) included in their design and operation. As such, the cost and performance of the TES system is critical to meeting the SunShot goal for solar technologies. The cost of electricity from a CSP plant depends strongly on its overall efficiency, which is a product of two components - the collection and conversion efficiencies. The collection efficiency determines the portion of incident solar energy that is captured as high-temperature thermal energy. The conversion efficiency determines the portion of thermal energy that is converted to electricity. The operating temperature at which the overall efficiency reaches its maximum depends on many factors, including material properties of the CSP plant components. Increasing the operating temperature of the power generation

  3. FGD system capital and operating cost reductions based on improved thiosorbic scrubber system design and latest process innovations

    SciTech Connect (OSTI)

    Smith, K.; Tseng, S.; Babu, M.

    1994-12-31

    Dravo Lime Company has operated the Miami Fort wet scrubber FGD pilot test unit since late 1989 and has continued in-house R&D to improve the economics of the magnesium-enhanced scrubbing process. Areas investigated include the scrubber configuration, flue gas velocity, spray nozzle type, droplet size, mist eliminator design, additives to inhibit oxidation, improved solids dewatering, etc. Also tested was the forced oxidation Thioclear process. The data gathered from the pilot plant and in-house programs were used to evaluate the capital and operating costs for the improved systems. These evaluations were made with eye towards the choices electric utilities will need to make in the near future to meet the Phase II emission limits mandated by the 1990 Clean Air Act. Some of the process modifications investigated, for example, the dewatering improvements apply to potential beneficial retrofit of existing FGD systems today.

  4. A heat & mass integration approach to reduce capital and operating costs of a distillation configuration

    SciTech Connect (OSTI)

    Madenoor Ramapriya, Gautham; Jiang, Zheyu; Tawarmalani, Mohit; Agrawal, Rakesh

    2015-11-11

    We propose a general method to consolidate distillation columns of a distillation configuration using heat and mass integration. The proposed method encompasses all heat and mass integrations known till date, and includes many more. Each heat and mass integration eliminates a distillation column, a condenser, a reboiler and the heat duty associated with a reboiler. Thus, heat and mass integration can potentially offer significant capital and operating cost benefits. In this talk, we will study the various possible heat and mass integrations in detail, and demonstrate their benefits using case studies. This work will lay out a framework to synthesize an entire new class of useful configurations based on heat and mass integration of distillation columns.

  5. Major Capital Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    BPA on 242015 and does not contain Agency-approved Financial Information. 1 Includes capital projects authorized at the agency level since August 2007 2 Direct capital costs...

  6. Major Capital Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    BPA on 622014 and does not contain Agency-approved Financial Information. 1 Includes capital projects authorized at the agency level since August 2007 2 Direct capital costs...

  7. Major Capital Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    on 1142014 and does not contain Agency-approved Financial Information. 1 Includes capital projects authorized at the agency level since August 2007 2 Direct capital costs...

  8. Major Capital Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    on 2112014 and does not contain Agency-approved Financial Information. 1 Includes capital projects authorized at the agency level since August 2007 2 Direct capital costs...

  9. Yellowstone Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Logo: Yellowstone Capital Name: Yellowstone Capital Address: 5555 San Felipe, Suite 1650 Place: Houston, Texas Zip: 77056 Region: Texas Area...

  10. CMEA Capital | Open Energy Information

    Open Energy Info (EERE)

    CMEA Capital Jump to: navigation, search Logo: CMEA Capital Name: CMEA Capital Address: 1 Embarcadero Center Place: San Francisco, California Zip: 94111 Region: Bay Area Number of...

  11. EXPERT ELICITATION OF ACROSS-TECHNOLOGY CORRELATIONS FOR REACTOR CAPITAL COSTS

    SciTech Connect (OSTI)

    Brent Dixon; Various

    2014-06-01

    Calculations of the uncertainty in the Levelized Cost at Equilibrium (LCAE) of generating nuclear electricity typically assume that the costs of the system component, notably reactors, are uncorrelated. Partial cancellation of independent errors thus gives rise to unrealistically small cost uncertainties for fuel cycles that incorporate multiple reactor technologies. This summary describes an expert elicitation of correlations between overnight reactor construction costs. It also defines a method for combining the elicitations into a single, consistent correlation matrix suitable for use in Monte Carlo LCAE calculations. Both the elicitation and uncertainty propagation methods are demonstrated through a pilot study where cost correlations between eight reactor technologies were elicited from experts in the US DOE Fuel Cycle Research

  12. Cascadia Capital | Open Energy Information

    Open Energy Info (EERE)

    Cascadia Capital Jump to: navigation, search Name: Cascadia Capital Address: 701 Fifth Avenue Place: Seattle, Washington Zip: 98104 Region: Pacific Northwest Area Product:...

  13. Capital and operating cost estimates. Volume I. Preliminary design and assessment of a 12,500 BPD coal-to-methanol-to-gasoline plant. [Grace C-M-G Plant, Henderson County, Kentucky

    SciTech Connect (OSTI)

    Not Available

    1982-08-01

    This Deliverable No. 18b - Capital and Operating Cost Estimates includes a detailed presentation of the 12,500 BPD coal-to-methanol-to-gasoline plant from the standpoint of capital, preoperations, start-up and operations cost estimation. The base capital cost estimate in June 1982 dollars was prepared by the Ralph M. Parsons Company under the direction of Grace. The escalated capital cost estimate as well as separate estimates for preoperations, startup and operations activities were developed by Grace. The deliverable consists of four volumes. Volume I contains details of methodology used in developing the capital cost estimate, summary information on a base June 1982 capital cost, details of the escalated capital cost estimate and separate sections devoted to preoperations, start-up, and operations cost. The base estimate is supported by detailed information in Volumes II, III and IV. The degree of detail for some units was constrained due to proprietary data. Attempts have been made to exhibit the estimating methodology by including data on individual equipment pricing. Proprietary details are available for inspection upon execution of nondisclosure and/or secrecy agreements with the licensors to whom the data is proprietary. Details of factoring certain pieces of equipment and/or entire modules or units from the 50,000 BPD capital estimate are also included. In the case of the escalated capital estimate, Grace has chosen to include a sensitivity analysis which allows for ready assessment of impacts of escalation rates (inflation), contingency allowances and the construction interest financing rates on the escalated capital cost. Each of the estimates associated with bringing the plant to commercial production rates has as a basis the schedule and engineering documentation found in Deliverable No. 14b - Process Engineering and Mechanical Design Report, No. 28b - Staffing Plans, No. 31b - Construction Plan, and No. 33b - Startup and Operation Plan.

  14. TRANSMISSION AND DISTRIBUTION; POWER SUBSTATIONS; CAPITALIZED...

    Office of Scientific and Technical Information (OSTI)

    AND DISTRIBUTION; POWER SUBSTATIONS; CAPITALIZED COST; CALCULATION METHODS; PLANNING; COST ESTIMATION; MATHEMATICAL MODELS The displacement or deferral of substation...

  15. Cost of Capital

    Broader source: Energy.gov [DOE]

    This presentation summarizes the information given by PV Evolution Labs during the DOE SunShot Grand Challenge: Summit and Technology Forum, June 13-14, 2012.

  16. Direct Thin Film Path to Low Cost, Large Area III-V Photovoltaics...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Solar Photovoltaic Solar Photovoltaic Advanced Materials Advanced Materials Find More Like This Return to Search Direct Thin Film Path to Low Cost, Large Area III-V Photovoltaics ...

  17. (OECD Expert Group meeting on reduction of capital costs of nuclear power plants, Paris, France, July 21--26, 1989): Foreign trip report

    SciTech Connect (OSTI)

    Hudson, C.R. II

    1989-08-09

    The OECD initiated a study of means to reduce the capital costs of nuclear power plants in the latter part of 1988. To accomplish the study, an Expert Group consisting of representatives of OECD member countries was formed. The initial meeting of the Expert Group was held in November 1988. A second meeting, documented in an ORNL trip report by this author, was held in May 1989. This meeting represents the third follow-on meeting with the primary goal of reviewing the draft report written by members of the Expert Group.

  18. Microsoft PowerPoint - Cost Escalation.ppt

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Hydroelectric Design Center Hydroelectric Design Center " " Cost Trends for Cost Trends for Hydropower Capital Hydropower Capital Replacements" Replacements" Presentation Outline ...

  19. Cost and Performance Assumptions for Modeling Electricity Generation...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    ... 16 Figure 6. Overnight capital costs-coal ......22 Figure 8. Overnight capital costs-combustion turbine ......

  20. Marathon Capital LLC (California) | Open Energy Information

    Open Energy Info (EERE)

    Marathon Capital LLC (California) Name: Marathon Capital LLC (California) Address: 42 Miller Avenue Place: Mill Valley, California Zip: 94941 Region: Bay Area Product: Investment...

  1. Black Coral Capital | Open Energy Information

    Open Energy Info (EERE)

    Coral Capital Jump to: navigation, search Name: Black Coral Capital Address: 55 Union Street, 3rd Floor Place: Boston, Massachusetts Zip: 02108 Region: Greater Boston Area Product:...

  2. Jane Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    search Logo: Jane Capital Partners Name: Jane Capital Partners Address: 505 Montgomery, 2nd Floor Place: San Francisco, California Zip: 94111 Region: Bay Area Product:...

  3. EM Capital Asset Project List

    Broader source: Energy.gov [DOE]

    Read the EM Capital Asset Project List, which includes the project's name, site, current critical decision and current total project cost.

  4. Ardour Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Ardour Capital Investments LLC Address: 350 5th ave Place: New York, New York Zip: 10118 Region: Northeast - NY NJ CT PA Area Number of...

  5. Best Practices for Controlling Capital Costs in Net Zero Energy Design and Construction- 2014 BTO Peer Review

    Broader source: Energy.gov [DOE]

    Presenter: Shanti Pless, National Renewable Energy Laboratory For net zero energy (NZE) building performance to become the norm in new commercial construction, it is necessary to demonstrate that NZE can be achieved cost effectively.

  6. Operating Costs

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    This chapter is focused on capital costs for conventional construction and environmental restoration and waste management projects and examines operating cost estimates to verify that all elements of the project have been considered and properly estimated.

  7. Access to Capital | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Soft Costs Access to Capital Access to Capital Photo of a room full of people seated in rows with a few standing in the background. Two hands in the crowd are holding up sheets ...

  8. QGESS: Capital Cost Scaling Methodology

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    QUALITY GUIDELINES FOR ENERGY SYSTEM STUDIES Performing a Techno-economic Analysis for Power Generation Plants DOENETL-2010???? DOENETL-20151726 Techno-economic Analysis...

  9. Cost-benefit analysis of cosolvent flushing to treat groundwater contamination source areas

    SciTech Connect (OSTI)

    Anason, S.L.

    1999-03-01

    Dense non-aqueous phase liquids (DNAPLs) in the zone beneath the water table can be a virtually permanent source of groundwater contamination that cannot be remediated by currently available technologies. Cosolvent flushing is a new technology that has the potential to remediate these sites and could pose a solution to the problem of DNAPL source areas. A computer model was developed to determine the cost and time to remediate an aquifer using cosolvent flushing. Included in the model is a module to calculate the costs of recycling the alcohol that is used as the cosolvent. The model was validated using site conditions to a prior study. It was determined that recycling the cosolvent allows cosolvent flushing to be a cost effective alternative to surfactant flushing, another new technology being considered for DNAPL source remediation. Sensitivity analysis of the model was conducted by varying the saturation percentage of contaminant, percentage and type of alcohol used in the cosolvent mixture, site hydraulic conductivity, and the contaminant. Five alcohols were modeled: methanol, ethanol, 1-isopropanol, 2-isopropanol, and tert-butyl-alcohol (TBA). 1-Isopropanol, 2-isopropanol, and TBA were always more expensive than methanol and ethanol.

  10. Foundation Capital

    Broader source: Energy.gov (indexed) [DOE]

    FC, ORNL, MB Confidential 3 Foundation Capital Confidential Distribution of 1,500 reviewed ORNL IP Out of 3,000 Total Disclosures Filed Over 25 yrs FC, ORNL, MB Confidential Many ...

  11. Engineering Evaluation/Cost Analysis (EE/CA) for Decommissioning of TAN-607 Hot Shop Area

    SciTech Connect (OSTI)

    J. P. Floerke

    2007-02-05

    Test Area North (TAN) -607, the Technical Support Facility, is located at the north end of the Idaho National Laboratory (INL) Site. U.S. Department of Energy Idaho Operations Office (DOE-ID) is proposing to decommission the northern section of the TAN-607 facility, hereinafter referred to as TAN-607 Hot Shop Area, under a Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) non-time-critical removal action (NTCRA). Despite significant efforts by the United States (U.S.) Department of Energy (DOE) to secure new business, no future mission has been identified for the TAN-607 Hot Shop Area. Its disposition has been agreed to by the Idaho State Historical Preservation Office documented in the Memorandum of Agreement signed October 2005 and it is therefore considered a surplus facility. A key element in DOE's strategy for surplus facilities is decommissioning to the maximum extent possible to ensure risk and building footprint reduction and thereby eliminating operations and maintenance cost. In addition, the DOE's 2006 Strategic Plan is ''complete cleanup of the contaminated nuclear weapons manufacturing and testing sites across the United States. DOE is responsible for the risk reduction and cleanup of the environmental legacy of the Nation's nuclear weapons program, one of the largest, most diverse, and technically complex environmental programs in the world. The Department will successfully achieve this strategic goal by ensuring the safety of the DOE employees and U.S. citizens, acquiring the best resources to complete the complex tasks, and managing projects throughout the United States in the most efficient and effective manner.'' TAN-607 is designated as a historical Signature Property by DOE Headquarters Advisory Council on Historic Preservation and, as such, public participation is required to determine the final disposition of the facility. The decommissioning action will place the TAN-607 Hot Shop Area in a final configuration that

  12. Trends in U.S. Oil and Natural Gas Upstream Costs

    Reports and Publications (EIA)

    2016-01-01

    Average 2015 well drilling and completion costs in five onshore areas decline 25% and 30% below their level in 2012 The U.S. Energy Information Administration (EIA) commissioned IHS Global Inc. (IHS) to perform a study of upstream drilling and production costs. The IHS report assesses capital and operating costs associated with drilling, completing, and operating wells and facilities.

  13. Expansion Capital Partners LLC | Open Energy Information

    Open Energy Info (EERE)

    Area Product: Venture capital firm that invests in expansion-stage, clean technology enterprises Year Founded: 2001 Phone Number: (415) 788-8802 Website: www.expansioncapital.com...

  14. Sustainable Investments Capital SI Capital | Open Energy Information

    Open Energy Info (EERE)

    Investments Capital SI Capital Jump to: navigation, search Name: Sustainable Investments Capital (SI Capital) Place: Barcelona, Spain Zip: 8021 Sector: Renewable Energy, Services...

  15. Venture Capital Finance

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Venture Capital Finance DOE Biomass Conference July 2014 Priced Out of Oil ... Into What? Energy Source Commodity Price Sun: $0 / GJ Oil (6.2 GJ/bbl) $10/bbl = $1.6 / GJ (late 1990s) Coal: $3 - 6 / GJ Natural Gas (N America) $3 - 4 / GJ Biomass (15 GJ/dt) $60-100/dt = $4 - 6 / GJ Natural Gas (ex N America) $10 - 15 / GJ Oil (6.2 GJ/bbl) $100/bbl = $16 / GJ Corn $4-7/bu= $10 - 20 / GJ 2 * Higher oil prices create a disruptive opportunity for lower cost feedstocks * North American shale gas is a

  16. An Evaluation of the Total Cost of Ownership of Fuel Cell-Powered...

    Broader source: Energy.gov (indexed) [DOE]

    handling equipment, including the capital costs of battery and fuel cell systems, the cost of supporting infrastructure, maintenance costs, warehouse space costs, and labor costs. ...

  17. Capital Asset Project List.xls

    Broader source: Energy.gov (indexed) [DOE]

    as defined by DOE Order 413.3B, Program and Project Management for the Acquisition of Capital Assets. CD0 Approve Mission Need CD1 Approve Alternative Selection and Cost Range CD2...

  18. Office of the Chief Human Capital Officer | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    Office of the Chief Human Capital Officer Most Requested Benefits CHRIS (DOE Only) DOE & ... HR Contacts by Sub Agency Servicing Area HC Contacts by Functional Area Human Resource ...

  19. Marathon Capital LLC (New York) | Open Energy Information

    Open Energy Info (EERE)

    Marathon Capital LLC (New York) Name: Marathon Capital LLC (New York) Address: 245 Park Avenue, 24th Floor Place: New York, New York Zip: 10167 Region: Northeast - NY NJ CT PA Area...

  20. A Review of Cost Estimation in New Technologies - Implications for Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Process Plants | Department of Energy A Review of Cost Estimation in New Technologies - Implications for Energy Process Plants A Review of Cost Estimation in New Technologies - Implications for Energy Process Plants This report reviews literature on cost estimation in several areas involving major capital expenditure programs: energy process plants, major weapons systems acquisition, public works and larger construction projects, and cost estimating techniques and problems for chemical

  1. Cost avoidance techniques through the Fernald controlled area trash segregation program and the RIMIA solid waste reduction program

    SciTech Connect (OSTI)

    Menche, C.E.

    1997-05-14

    The Fernald Environmental Management Project is a Department of Energy owned facility that produced high quality uranium metals for military defense. The Fernald mission has changed from one of production to remediation. Remediation is intended to clean up legacy (primary) waste from past practices. Little opportunity is available to reduce the amount of primary waste. However, there is an opportunity to reduce secondary waste generation, primarily through segregation. Two programs which accomplish this are the Controlled Area Trash Segregation Program and the RIMIA Solid Waste Reduction Program. With these two programs now in place at the FEMP, it has been estimated that a 60% reduction has been achieved in unnecessary clean waste being disposed as Low Level Waste at the Nevada Test Site. The cost savings associated with these programs (currently 79,000 cubic feet, $428,000) could easily run into the millions of dollars based on the upcoming restoration activities to be undertaken. The segregation of non-radiological waste in the radiologically Controlled Area not only establishes a firm commitment to send only low-level radioactive waste to the Nevada Test Site, but also results in substantial cost avoidance.

  2. Report: EM Human Capital Initiatives

    Office of Environmental Management (EM)

    HUMAN CAPITAL September 25, 2008 Submitted by the EMAB Human Capital Subcommittee Background: The enhancement of the Office of Environmental Management's (EM) human capital has ...

  3. Greenworld Capital | Open Energy Information

    Open Energy Info (EERE)

    Greenworld Capital Jump to: navigation, search Name: Greenworld Capital Place: Pennsylvania Zip: 10000 Sector: Services Product: GreenWorld Capital provides investment banking...

  4. Greencore Capital | Open Energy Information

    Open Energy Info (EERE)

    Greencore Capital Jump to: navigation, search Name: Greencore Capital Place: San Diego, California Zip: 92121 Sector: Services Product: String representation "GreenCore Capit ... s...

  5. Nite Capital | Open Energy Information

    Open Energy Info (EERE)

    Nite Capital Jump to: navigation, search Name: Nite Capital Place: Libertyville, Illinois Zip: 60048 Product: Nite Capital provides private financing for small-cap and micro-cap...

  6. Greener Capital | Open Energy Information

    Open Energy Info (EERE)

    Greener Capital Jump to: navigation, search Name: Greener Capital Place: San Francisco, California Product: San Francisco-based clean technology VC. References: Greener Capital1...

  7. GGV Capital | Open Energy Information

    Open Energy Info (EERE)

    GGV Capital Jump to: navigation, search Name: GGV Capital Place: Menlo Park, California Zip: 94025 Product: String representation "GGV Capital" ... U.S. and China." is too...

  8. Clarey Capital | Open Energy Information

    Open Energy Info (EERE)

    Clarey Capital Jump to: navigation, search Name: Clarey Capital Place: Irvine, California Zip: 92617 Sector: Renewable Energy Product: String representation "Clarey Capital ... of...

  9. BEV Capital | Open Energy Information

    Open Energy Info (EERE)

    BEV Capital Jump to: navigation, search Logo: BEV Capital Name: BEV Capital Address: 263 Tresser Blvd., 9th Floor Place: Stamford, Connecticut Zip: 06901 Region: Northeast - NY NJ...

  10. Infield Capital | Open Energy Information

    Open Energy Info (EERE)

    Infield Capital Jump to: navigation, search Name: Infield Capital Place: Boulder, Colorado Product: Infield Capital was founded in 2008, and is focused on investment in early-stage...

  11. Greenview Capital | Open Energy Information

    Open Energy Info (EERE)

    Greenview Capital Jump to: navigation, search Name: Greenview Capital Place: Libertyville, Illinois Zip: 60048 Product: Greenview Capital is a U.S. based consulting firm and...

  12. Earthrise Capital | Open Energy Information

    Open Energy Info (EERE)

    Earthrise Capital Jump to: navigation, search Logo: Earthrise Capital Name: Earthrise Capital Address: 45 Rockefeller Plaza, 20th Floor Place: New York, New York Zip: 10111 Region:...

  13. Atrium Capital | Open Energy Information

    Open Energy Info (EERE)

    Atrium Capital Jump to: navigation, search Logo: Atrium Capital Name: Atrium Capital Address: 3000 Sand Hill Road, Building 2, Suite 240 Place: Menlo Park, California Zip: 94025...

  14. Commons Capital | Open Energy Information

    Open Energy Info (EERE)

    Commons Capital Jump to: navigation, search Logo: Commons Capital Name: Commons Capital Address: 320 Washington Street, 4th floor Place: Brookline, Massachusetts Zip: 02445 Region:...

  15. Capital Equity Partners LLC | Open Energy Information

    Open Energy Info (EERE)

    Partners LLC Jump to: navigation, search Name: Capital Equity Partners LLC Address: 410 Park Avenue Place: New York, New York Zip: 10022 Region: Northeast - NY NJ CT PA Area...

  16. Capital Reporting Company Quadrennial ...

    Broader source: Energy.gov (indexed) [DOE]

    Capital Reporting Company Quadrennial Energy Review Meeting No. 4 06-19-2014 (866) 448 - DEPO www.CapitalReportingCompany.com 2014 1 UNITED STATES DEPARTMENT OF ENERGY OFFICE OF ...

  17. Program and Project Management for the Acquisition of Capital...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    3.3B, Program and Project Management for the Acquisition of Capital Assets by Jay Glascock Functional areas: Acquisition, Defense Nuclear Facility Safety and Health Requirement,...

  18. Program and Project Management for the Acquisition of Capital...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    B Chg 1 (Admin Chg), Program and Project Management for the Acquisition of Capital Assets by Jay Glascock Functional areas: Acquisition, Defense Nuclear Facility Safety and Health ...

  19. An examination of the costs and critical characteristics of electric utility distribution system capacity enhancement projects

    SciTech Connect (OSTI)

    Balducci, Patrick J.; Schienbein, Lawrence A.; Nguyen, Tony B.; Brown, Daryl R.; Fathelrahman, Eihab M.

    2004-06-01

    This report classifies and analyzes the capital and total costs (e.g., income tax, property tax, depreciation, centralized power generation, insurance premiums, and capital financing) associated with 130 electricity distribution system capacity enhancement projects undertaken during 1995-2002 or planned in the 2003-2011 time period by three electric power utilities operating in the Pacific Northwest. The Pacific Northwest National Laboratory (PNNL), in cooperation with participating utilities, has developed a large database of over 3,000 distribution system projects. The database includes brief project descriptions, capital cost estimates, the stated need for each project, and engineering data. The database was augmented by additional technical (e.g., line loss, existing substation capacities, and forecast peak demand for power in the area served by each project), cost (e.g., operations, maintenance, and centralized power generation costs), and financial (e.g., cost of capital, insurance premiums, depreciations, and tax rates) data. Though there are roughly 3,000 projects in the database, the vast majority were not included in this analysis because they either did not clearly enhance capacity or more information was needed, and not available, to adequately conduct the cost analyses. For the 130 projects identified for this analysis, capital cost frequency distributions were constructed, and expressed in terms of dollars per kVA of additional capacity. The capital cost frequency distributions identify how the projects contained within the database are distributed across a broad cost spectrum. Furthermore, the PNNL Energy Cost Analysis Model (ECAM) was used to determine the full costs (e.g., capital, operations and maintenance, property tax, income tax, depreciation, centralized power generation costs, insurance premiums and capital financing) associated with delivering electricity to customers, once again expressed in terms of costs per kVA of additional capacity

  20. Solar Access to Public Capital | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Solar Access to Public Capital Solar Access to Public Capital The Solar Access to Public Capital (SAPC) working group has developed standard residential lease and commercial power purchase agreement (PPA) contracts available for use by solar developers, customers, and third-party finance providers. These documents are designed to improve consumer transparency, reduce transaction costs in the solar asset contracting process, and facilitate the pooling of associated cash flows so that they may be

  1. Energy Department Report Calculates Emissions and Costs of Power...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    does not consider other factors such as capital costs of construction for wind, solar, fossil-fueled power plants, or transmission. These costs are significant, but outside the...

  2. Capital Project Prioritization

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Capital-Project-Prioritization Sign In About | Careers | Contact | Investors | bpa.gov Search News & Us Expand News & Us Projects & Initiatives Expand Projects &...

  3. CAPITAL PROJECT PROPOSAL

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Non-Discretionary, please provide explanation: 07 Approval for: Ongoing Program 08 Investment Type: Capital Replacement 09 Emergency? YES NO 09A If "YES", please provide...

  4. Human Capital - DOE Directives, Delegations, and Requirements

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Human Capital by Website Administrator Back

  5. 2015-09-25 Capital Asset Project List.xls

    Broader source: Energy.gov (indexed) [DOE]

    as defined by DOE Order 413.3B, Program and Project Management for the Acquisition of Capital Assets. CD-0 Approve Mission Need CD-1 Approve Alternative Selection and Cost Range...

  6. BG Capital | Open Energy Information

    Open Energy Info (EERE)

    BG Capital Jump to: navigation, search Name: BG-Capital Place: Spain Zip: 8860 Product: BG-capital designs, installs and invests in PV medium scale (100-500kW) systems,...

  7. Hazel Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Hazel Capital Place: London, England, United Kingdom Zip: WC2A 1AL Sector: Efficiency, Renewable Energy Product: Hazel Capital is an asset...

  8. Carbon Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Carbon Capital Place: United Kingdom Sector: Carbon Product: Manages a carbon fund specialised in forestry projects References: Carbon...

  9. Gaian Capital | Open Energy Information

    Open Energy Info (EERE)

    Gaian Capital Jump to: navigation, search Name: Gaian Capital Place: Greater London, United Kingdom Product: London-based privately held firm aimed at assisting climate change...

  10. Arborview Capital | Open Energy Information

    Open Energy Info (EERE)

    Arborview Capital Jump to: navigation, search Name: Arborview Capital Place: Chevy Chase, Maryland Zip: 20815 Product: Maryland-based private equity firm that provides growth...

  11. Greenrock Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Greenrock Capital Place: San Francisco, California Zip: 94111 Sector: Renewable Energy Product: San Francisco-based, investment firm....

  12. Dragonfly Capital | Open Energy Information

    Open Energy Info (EERE)

    Dragonfly Capital Jump to: navigation, search Name: Dragonfly Capital Place: Charlotte, North Carolina Zip: 28203 Sector: Renewable Energy, Services Product: Charlotte-based...

  13. Renewable Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Renewable Capital Place: Las Vegas, Nevada Zip: 89109 Sector: Solar Product: Investment vehicle of Ed Stevenson, founder of Solar...

  14. Capital Connections | Open Energy Information

    Open Energy Info (EERE)

    Connections Jump to: navigation, search Name: Capital Connections Place: United Kingdom Product: Supplies fuel cell systems. References: Capital Connections1 This article is a...

  15. Peony Capital | Open Energy Information

    Open Energy Info (EERE)

    Peony Capital Jump to: navigation, search Name: Peony Capital Place: Dongcheng District Beijing, Beijing Municipality, China Zip: 100027 Product: Manages a fund dedicated to...

  16. Capital Point | Open Energy Information

    Open Energy Info (EERE)

    Point Jump to: navigation, search Name: Capital Point Place: Israel Sector: Services Product: General Financial & Legal Services ( Joint Venture Consortium ) References: Capital...

  17. Optimization and life-cycle cost of health clinic PV system for a rural area in southern Iraq using HOMER software

    SciTech Connect (OSTI)

    Al-Karaghouli, Ali; Kazmerski, L.L.

    2010-04-15

    This paper addresses the need for electricity of rural areas in southern Iraq and proposes a photovoltaic (PV) solar system to power a health clinic in that region. The total daily health clinic load is 31.6 kW h and detailed loads are listed. The National Renewable Energy Laboratory (NREL) optimization computer model for distributed power, ''HOMER,'' is used to estimate the system size and its life-cycle cost. The analysis shows that the optimal system's initial cost, net present cost, and electricity cost is US$ 50,700, US$ 60,375, and US$ 0.238/kW h, respectively. These values for the PV system are compared with those of a generator alone used to supply the load. We found that the initial cost, net present cost of the generator system, and electricity cost are US$ 4500, US$ 352,303, and US$ 1.332/kW h, respectively. We conclude that using the PV system is justified on humanitarian, technical, and economic grounds. (author)

  18. Delegation Order No. 00-002.13-01 to the Deputy Chief Human Capital...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    CURRENT 002.13-01, Delegation Order No. 00-002.13-01 to the Deputy Chief Human Capital Officer by Diane Johnson Functional areas: Human Capital 00-00213-01HC-DepChfHCO.pdf -- PDF...

  19. Capital Reporting Company Quadrennial ...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... The war on poverty, which was 20 initiated with very dramatics walks from 21 Appalachia ... 07-21-2014 (866) 448 - DEPO www.CapitalReportingCompany.com 2014 44 1 poverty there. ...

  20. Capital Reporting Company Quadrennial ...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ...CapitalReportingCompany.com 2014 120 1 how to adapt to the new oil which is, in New 2 Mexico, a sweet API 40, essentially similar to the 3 North Dakota oil. We have a sweet oil. ...

  1. Capital Project Authorization

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    This policy applies to capital projects in these asset categories: 1. Transmission investment in assets owned or leased by BPA, whether funded by bonds issued to the U.S....

  2. Wind energy`s declining costs

    SciTech Connect (OSTI)

    Gipe, P.

    1995-11-01

    Wind energy is competitive with traditional energy sources for the first time since European windmills graced the landscapes of the Old World. This article explores the current economics of wind power. Topics discussed include the following: standardizing cost of energy reporting and the cost of wind energy; wind power plant price; maintenance costs; effect of installed cost on the cost of energy; future costs; decommissioning; modularity; social or environmental costs; cost of capital; bidding and price.

  3. ASPEN costing manual

    SciTech Connect (OSTI)

    Schwint, K.J.

    1986-07-25

    The ASPEN program contains within it a Cost Estimation System (CES) which estimates the purchase cost and utility consumption rates for major pieces of equipment in a process flowsheet as well as installed equipment costs. These estimates are ''preliminary-study grade'' with an accuracy of plus or minus 30%. The ASPEN program also contains within it an Economic Evaluation System (EES) which estimates overall capital investment costs, annual operating expenses and profitability indices for a chemical plant. This ASPEN costing manual has been written as a guide for those inexperienced in the use of ASPEN and unfamiliar with standard cost estimating techniques who want to use the ASPEN CES and EES. The ASPEN Costing Manual is comprised of the following sections: (1) Introduction, (2) ASPEN Input Language, (3) ASPEN Cost Estimation System (CES), (4) ASPEN Cost Blocks; and (5) ASPEN Economic Evaluation System (EES).

  4. Non-Hardware ("Soft") Cost-Reduction Roadmap for Residential and Small Commercial Solar Photovoltaics, 2013-2020

    SciTech Connect (OSTI)

    Ardani, K.; Seif, D.; Margolis, R.; Morris, J.; Davidson, C.; Truitt, S.; Torbert, R.

    2013-08-01

    The objective of this analysis is to roadmap the cost reductions and innovations necessary to achieve the U.S. Department of Energy (DOE) SunShot Initiative's total soft-cost targets by 2020. The roadmap focuses on advances in four soft-cost areas: (1) customer acquisition; (2) permitting, inspection, and interconnection (PII); (3) installation labor; and (4) financing. Financing cost reductions are in terms of the weighted average cost of capital (WACC) for financing PV system installations, with real-percent targets of 3.0% (residential) and 3.4% (commercial).

  5. Walnut Capital Acquisitions | Open Energy Information

    Open Energy Info (EERE)

    Walnut Capital Acquisitions Jump to: navigation, search Name: Walnut Capital Acquisitions Place: Pittsburgh, Pennsylvania Zip: 15232 Product: Walnut Capital Acquisitions is the...

  6. American Wind Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: American Wind Capital Place: Essex, Connecticut Zip: 64260 Sector: Wind energy Product: Connecticut-based American Wind Capital buys wind...

  7. Sustainable Technology Capital, LP | Open Energy Information

    Open Energy Info (EERE)

    Capital, LP Jump to: navigation, search Logo: Sustainable Technology Capital, LP Name: Sustainable Technology Capital, LP Address: 625 Liberty Ave., Suite 3200 Place: Pittsburgh,...

  8. Long Branch Capital | Open Energy Information

    Open Energy Info (EERE)

    Branch Capital Jump to: navigation, search Name: Long Branch Capital Place: Austin, Texas Zip: 78744 Sector: Efficiency, Renewable Energy Product: Long Branch Capital makes...

  9. Tonga Capital Corporation | Open Energy Information

    Open Energy Info (EERE)

    Tonga Capital Corporation Jump to: navigation, search Name: Tonga Capital Corporation Place: Arvada, Colorado Sector: Biofuels Product: Capital pool company, which ran out of...

  10. Hereford Capital Advisors | Open Energy Information

    Open Energy Info (EERE)

    Hereford Capital Advisors Jump to: navigation, search Name: Hereford Capital Advisors Place: Denver, Colorado Product: US-based firm offering PV project management and capital...

  11. Prospect Capital Corporation | Open Energy Information

    Open Energy Info (EERE)

    Prospect Capital Corporation Jump to: navigation, search Logo: Prospect Capital Corporation Name: Prospect Capital Corporation Address: 10 East 40th Street, 44th Floor Place: New...

  12. Energy Capital Solutions | Open Energy Information

    Open Energy Info (EERE)

    Capital Solutions Jump to: navigation, search Logo: Energy Capital Solutions Name: Energy Capital Solutions Address: 2651 North Harwood Street, Suite 410 Place: Dallas, Texas Zip:...

  13. Beetle Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    Beetle Capital Partners Jump to: navigation, search Logo: Beetle Capital Partners Name: Beetle Capital Partners Address: Medici Court, 67-69 New Bond Street Place: London, United...

  14. KRK Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    KRK Capital Partners Jump to: navigation, search Name: KRK Capital Partners Place: Washington DC, Washington, DC Zip: 20002 Product: String representation "KRK Capital Par ......

  15. Chrysalix Energy Venture Capital | Open Energy Information

    Open Energy Info (EERE)

    Chrysalix Energy Venture Capital Jump to: navigation, search Logo: Chrysalix Energy Venture Capital Name: Chrysalix Energy Venture Capital Address: 1367 West Broadway, Suite 400...

  16. Temple Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    Temple Capital Partners Jump to: navigation, search Name: Temple Capital Partners Place: United Kingdom Product: Fund manager of Clean Energy Brazil. References: Temple Capital...

  17. New Energy Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Logo: New Energy Capital Name: New Energy Capital Address: 53 South Main Street, Third Floor Place: Hanover, New Hampshire Zip: 03755 Product:...

  18. Applied Intellectual Capital AIC | Open Energy Information

    Open Energy Info (EERE)

    Intellectual Capital AIC Jump to: navigation, search Name: Applied Intellectual Capital (AIC) Place: California Zip: 94501-1010 Product: Applied Intellectual Capital (AIC) was...

  19. Booner Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Booner Capital LLC Jump to: navigation, search Name: Booner Capital LLC Place: Florida Sector: Wind energy Product: Booner Capital LLC is PE investor in wind power companies....

  20. Chestnut Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Capital LLC Jump to: navigation, search Name: Chestnut Capital LLC Place: West Newton, Massachusetts Zip: 2465 Sector: Wind energy Product: Chestnut Capital is a wind energy...

  1. Cora Capital Advisors | Open Energy Information

    Open Energy Info (EERE)

    Cora Capital Advisors Jump to: navigation, search Logo: Cora Capital Advisors Name: Cora Capital Advisors Address: 445 Park Avenue, 9th Floor Place: New York Zip: 10022 Region:...

  2. Green Capital Management | Open Energy Information

    Open Energy Info (EERE)

    Capital Management Jump to: navigation, search Name: Green Capital Management Place: London, United Kingdom Zip: SW10 0BB Sector: Services Product: The Green Capital Management...

  3. The Capital Intensity of Photovoltaics Manufacturing

    SciTech Connect (OSTI)

    Basore, Paul

    2015-10-19

    Factory capital expenditure (capex) for photovoltaic (PV) module manufacturing strongly influences the per-unit cost of a c-Si module. This provides a significant opportunity to address the U.S. DOE SunShot module price target through capex innovation. Innovation options to reduce the capex of PV manufacturing include incremental and disruptive process innovation with c-Si, platform innovations, and financial approaches. and financial approaches.

  4. Development of surface mine cost estimating equations

    SciTech Connect (OSTI)

    Not Available

    1980-09-26

    Cost estimating equations were developed to determine capital and operating costs for five surface coal mine models in Central Appalachia, Northern Appalachia, Mid-West, Far-West, and Campbell County, Wyoming. Engineering equations were used to estimate equipment costs for the stripping function and for the coal loading and hauling function for the base case mine and for several mines with different annual production levels and/or different overburden removal requirements. Deferred costs were then determined through application of the base case depreciation schedules, and direct labor costs were easily established once the equipment quantities (and, hence, manpower requirements) were determined. The data points were then fit with appropriate functional forms, and these were then multiplied by appropriate adjustment factors so that the resulting equations yielded the model mine costs for initial and deferred capital and annual operating cost. (The validity of this scaling process is based on the assumption that total initial and deferred capital costs are proportional to the initial and deferred costs for the primary equipment types that were considered and that annual operating cost is proportional to the direct labor costs that were determined based on primary equipment quantities.) Initial capital costs ranged from $3,910,470 in Central Appalachia to $49,296,785; deferred capital costs ranged from $3,220,000 in Central Appalachia to $30,735,000 in Campbell County, Wyoming; and annual operating costs ranged from $2,924,148 in Central Appalachia to $32,708,591 in Campbell County, Wyoming. (DMC)

  5. Program and Project Management for the Acquisition of Capital...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    13.B, Chg 1 (PgChg), Program and Project Management for the Acquisition of Capital Assets by Jay Glascock Functional areas: Acquisition, Defense Nuclear Facility Safety and Health...

  6. Program and Project Management for the Acquisition of Capital...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    ARCHIVED DOE O 413.3A Chg 1, Program and Project Management for the Acquisition of Capital Assets by John Makepeace Functional areas: Acquisition, Defense Nuclear Facility Safety...

  7. Survey Results and Analysis of the Cost and Efficiency of Various Operating Hydrogen Fueling Stations

    SciTech Connect (OSTI)

    Cornish, John

    2011-03-05

    Existing Hydrogen Fueling Stations were surveyed to determine capital and operational costs. Recommendations for cost reduction in future stations and for research were developed.

  8. Osmosis Capital | Open Energy Information

    Open Energy Info (EERE)

    Osmosis Capital Jump to: navigation, search Name: Osmosis Capital Place: London, United Kingdom Zip: EC4M 9DN Sector: Carbon Product: An investment firm seeking low carbon economy...

  9. Greentech Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Place: Sao Paulo, Sao Paulo, Brazil Zip: 04536-001 Product: Brazilian investment group. References: Greentech Capital1 This article is a stub. You can help OpenEI...

  10. Best Practices for Net Zero Energy Cost Control

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    teams, which are key parties that influence construction capital cost. ... http:www1.eere.energy.govbuildingsalliancesmedia20111031webinarcontrollingcosts.wmv * Energy ...

  11. Replacement Cost of Domestic Crude

    Energy Science and Technology Software Center (OSTI)

    1994-12-01

    The DEEPWATER model forecasts the replacement cost of domestic crude oil for 13 offshore regions in the lower 48 states. The replacement cost of domestic crude oil is the constant or levelized selling price that will recover the full expense of exploration, development, and productions with a reasonable return on capital.

  12. U.S. Department of Energy Acquisition Strategy Guide for Capital...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    3, U.S. Department of Energy Acquisition Strategy Guide for Capital Assets Projects by John Makepeace Functional areas: Program Management, Project Management This Guide serves as...

  13. U.S. Department of Energy Project Review Guide for Capital Asset...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    9, U.S. Department of Energy Project Review Guide for Capital Asset Projects by John Makepeace Functional areas: Program Management, Project Management This Guide addresses the...

  14. PEM Electrolyzer Incorporating an Advanced Low-Cost Membrane

    SciTech Connect (OSTI)

    Hamdan, Monjid

    2013-08-29

    The Department of Energy (DOE) has identified hydrogen production by electrolysis of water at forecourt stations as a critical technology for transition to the hydrogen economy; however, the cost of hydrogen produced by present commercially available electrolysis systems is considerably higher than the DOE 2015 and 2020 cost targets. Analyses of proton-exchange membrane (PEM) electrolyzer systems indicate that reductions in electricity consumption and electrolyzer stack and system capital cost are required to meet the DOE cost targets. The primary objective is to develop and demonstrate a cost-effective energy-based system for electrolytic generation of hydrogen. The goal is to increase PEM electrolyzer efficiency and to reduce electrolyzer stack and system capital cost to meet the DOE cost targets for distributed electrolysis. To accomplish this objective, work was conducted by a team consisting of Giner, Inc. (Giner), Virginia Polytechnic Institute & University (VT), and domnick hunter group, a subsidiary of Parker Hannifin (Parker). The project focused on four (4) key areas: (1) development of a high-efficiency, high-strength membrane; (2) development of a long-life cell-separator; (3) scale-up of cell active area to 290 cm2 (from 160 cm²); and (4) development of a prototype commercial electrolyzer system. In each of the key stack development areas Giner and our team members conducted focused development in laboratory-scale hardware, with analytical support as necessary, followed by life-testing of the most promising candidate materials. Selected components were then scaled up and incorporated into low-cost scaled-up stack hardware. The project culminated in the fabrication and testing of a highly efficient electrolyzer system for production of 0.5 kg/hr hydrogen and validation of the stack and system in testing at the National Renewable Energy Laboratory (NREL).

  15. Program and Project Management for the Acquisition of Capital Assets -

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    DOE Directives, Delegations, and Requirements B, Program and Project Management for the Acquisition of Capital Assets by Jay Glascock Functional areas: Acquisition, Defense Nuclear Facility Safety and Health Requirement, Program Management The purpose of this Order is to a) provide the Department of Energy (DOE) Elements, including the National Nuclear Security Administration (NNSA), with program and project management direction for the acquisition of capital assets with the goal of

  16. Swiftsure Capital | Open Energy Information

    Open Energy Info (EERE)

    Place: San Francisco, California Product: Swiftsure Capital, US-based private investment corporation focusing on the financing of early-stage businesses in the software,...

  17. Principal Associate Director - Capital Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    As Principal Associate Director for Capital Projects (interim), Larry Simmons is responsible for institutional large-project construction and management and environmental cleanup ...

  18. Financing U.S. Renewable Energy Projects Through Public Capital Vehicles: Qualitative and Quantitative Benefits

    SciTech Connect (OSTI)

    Mendelsohn, M.; Feldman, D.

    2013-04-01

    This paper explores the possibility of financing renewable energy projects through raising capital in the public markets. It gives an overview of the size, structure, and benefits of public capital markets, as well as showing how renewable energy projects might take advantage of this source of new funds to lower the cost of electricity.

  19. Levelized Power Generation Cost Codes

    Energy Science and Technology Software Center (OSTI)

    1996-04-30

    LPGC is a set of nine microcomputer programs for estimating power generation costs for large steam-electric power plants. These programs permit rapid evaluation using various sets of economic and technical ground rules. The levelized power generation costs calculated may be used to compare the relative economics of nuclear and coal-fired plants based on life-cycle costs. Cost calculations include capital investment cost, operation and maintenance cost, fuel cycle cost, decommissioning cost, and total levelized power generationmore » cost. These programs can be used for quick analyses of power generation costs using alternative economic parameters, such as interest rate, escalation rate, inflation rate, plant lead times, capacity factor, fuel prices, etc. The two major types of electric generating plants considered are pressurized water reactor (PWR) and pulverized coal-fired plants. Data are also provided for the Large Scale Prototype Breeder (LSPB) type liquid metal reactor.« less

  20. EA-355 Scotia Capital Energy, Inc. | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    5 Scotia Capital Energy, Inc. EA-355 Scotia Capital Energy, Inc. Order authorizing Scotia Capital Energy, Inc. to export electric energy to Canada EA-355 Scotia Capital Energy, ...

  1. Hydrogen Production Cost Estimate Using Biomass Gasification: Independent Review

    Office of Energy Efficiency and Renewable Energy (EERE)

    This independent review report assesses the 2009 state-of-the-art and 2020 projected capital cost, energy efficiency, and levelized cost for hydrogen production from biomass via gasification.

  2. Human Capital Management Accountability Program

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2008-08-01

    The Order establishes requirements, roles and responsibilities for the Human Capital Management Accountability Program (HCMAP) for human resources programs and personnel and ensures that human capital activities are regulatory and procedurally compliant with Federal statutes and Departmental policies. Does not cancel other directives.

  3. Where might I find simplified Data on Capital, O&M, and fuel...

    Open Energy Info (EERE)

    Where might I find simplified Data on Capital, O&M, and fuel costs? Home I teach math to high school seniors. My students are studying energy in all their classes. I have just...

  4. Mont Vista Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Vista Capital LLC Jump to: navigation, search Name: Mont Vista Capital LLC Place: New York, New York Zip: 10167 Sector: Services Product: Mont Vista Capital is a leading global...

  5. EnerTech Capital | Open Energy Information

    Open Energy Info (EERE)

    EnerTech Capital Jump to: navigation, search Logo: EnerTech Capital Name: EnerTech Capital Address: 625 W. Ridge Pike, Building D, Suite 105 Place: Conshohocken, Pennsylvania Zip:...

  6. GreenCore Capital | Open Energy Information

    Open Energy Info (EERE)

    GreenCore Capital Jump to: navigation, search Logo: GreenCore Capital Name: GreenCore Capital Address: 10509 Vista Sorrento Parkway Place: San Diego, California Zip: 92121 Region:...

  7. EarthRise Capital | Open Energy Information

    Open Energy Info (EERE)

    EarthRise Capital Jump to: navigation, search Name: EarthRise Capital Place: New York, New York Zip: NY 10111 Sector: Efficiency Product: Venture capital fund focused on new...

  8. Soft Costs | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Soft Costs » Soft Costs Soft Costs The U.S. Department of Energy (DOE) SunShot Initiative's soft costs program works to lower the non-hardware costs of solar and accelerate the adoption of solar energy technologies throughout the United States. In support of the SunShot Initiative goals, the soft costs program works in the following strategic areas: networking and technical assistance, data analysis, business innovation, and training. Soft Costs Activity Areas, Business Innovation, Networking

  9. Ethanol Capital Funding | Open Energy Information

    Open Energy Info (EERE)

    Ethanol Capital Funding Jump to: navigation, search Name: Ethanol Capital Funding Place: Atlanta, Georgia Zip: 30328 Product: Provides funding for ethanol and biodiesel plants....

  10. Atlantic Ethanol Capital | Open Energy Information

    Open Energy Info (EERE)

    Ethanol Capital Jump to: navigation, search Name: Atlantic Ethanol Capital Place: Washington, Washington, DC Product: Biofuel Investor in Caribbean and Central American region....

  11. Carbon Credit Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Carbon Credit Capital Place: New York, New York Zip: 10012 Sector: Carbon, Services Product: Project Advisory Services and Carbon...

  12. Capital Energy Offshore | Open Energy Information

    Open Energy Info (EERE)

    Sector: Wind energy Product: JV between Gamesa and Capital Energy to develop offshore wind farms References: Capital Energy Offshore1 This article is a stub. You can help...

  13. Viresco International Capital Management | Open Energy Information

    Open Energy Info (EERE)

    International Capital Management Jump to: navigation, search Name: Viresco International Capital Management Place: San Diego, California Zip: 92130 Product: San Diego-based hedge...

  14. Greenwood Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    Greenwood Capital Partners Jump to: navigation, search Name: Greenwood Capital Partners Place: Charlotte, North Carolina Zip: 28266 Product: Corporate finance boutique working on...

  15. Montauk Energy Capital | Open Energy Information

    Open Energy Info (EERE)

    Montauk Energy Capital Jump to: navigation, search Name: Montauk Energy Capital Place: Pittsburg, Pennsylvania Zip: 15220 Product: Owns and operates landfill gas plants across the...

  16. New Energy Capital Corp | Open Energy Information

    Open Energy Info (EERE)

    Capital Corp Jump to: navigation, search Name: New Energy Capital Corp. Place: Hanover, New Hampshire Zip: 3755 Sector: Renewable Energy Product: Private equity fund focused on...

  17. Quadrant Capital Advisors Inc | Open Energy Information

    Open Energy Info (EERE)

    Quadrant Capital Advisors Inc Jump to: navigation, search Name: Quadrant Capital Advisors Inc. Place: New York, New York Zip: 10022 Sector: Hydro, Wind energy Product: US based...

  18. Arctas Capital Group | Open Energy Information

    Open Energy Info (EERE)

    Arctas Capital Group Jump to: navigation, search Name: Arctas Capital Group Place: Houston, Texas Zip: 77056 Sector: Geothermal energy, Renewable Energy, Wind energy Product: A...

  19. Krass Capital Group AG | Open Energy Information

    Open Energy Info (EERE)

    Krass Capital Group AG Jump to: navigation, search Name: Krass Capital Group AG Place: Grfelfing, Bulgaria Zip: 82166 Sector: Renewable Energy Product: Grafelfing-based firm...

  20. North Cove Capital Advisors | Open Energy Information

    Open Energy Info (EERE)

    Cove Capital Advisors Jump to: navigation, search Name: North Cove Capital Advisors Place: Connecticut Sector: Carbon Product: North Cove is an advisory firm that works...

  1. Starlight Capital Advisors | Open Energy Information

    Open Energy Info (EERE)

    Starlight Capital Advisors Jump to: navigation, search Name: Starlight Capital Advisors Place: Carlsbad, California Zip: 92011 Sector: Renewable Energy Product: California-based...

  2. Climate Human Capital | Open Energy Information

    Open Energy Info (EERE)

    Human Capital Jump to: navigation, search Name: Climate Human Capital Place: London, United Kingdom Zip: W1K 6NG Sector: Carbon, Renewable Energy, Services Product: Green executive...

  3. Digital Power Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Capital LLC Jump to: navigation, search Name: Digital Power Capital LLC Place: Greenwich, Connecticut Zip: 6830 Product: A private equity firm focused on new technologies that...

  4. Solution Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    Solution Capital Partners Jump to: navigation, search Name: Solution Capital Partners Place: New York Zip: NY 10036 Product: A New York-based investment firm active in the...

  5. American Capital Energy | Open Energy Information

    Open Energy Info (EERE)

    Energy Jump to: navigation, search Logo: American Capital Energy Name: American Capital Energy Address: 15 Tyngsboro Rd. Suite 4A Place: North Chelmsford, Massachusetts Zip: 01863...

  6. Cape Verde Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Cape Verde Capital Place: Leatherhead, United Kingdom Zip: KT22 7SW Sector: Renewable Energy Product: The renewable energy investment arm...

  7. Greentech Capital Advisors GCA | Open Energy Information

    Open Energy Info (EERE)

    Capital Advisors GCA Jump to: navigation, search Name: Greentech Capital Advisors (GCA) Place: New York, New York Zip: 10017 Sector: Renewable Energy Product: New York-based...

  8. Transmission Capital Limited | Open Energy Information

    Open Energy Info (EERE)

    Transmission Capital Limited Jump to: navigation, search Name: Transmission Capital Limited Place: London, United Kingdom Zip: EC2V 7HR Sector: Renewable Energy, Services Product:...

  9. Sustainable Development Capital LLP | Open Energy Information

    Open Energy Info (EERE)

    Capital LLP Jump to: navigation, search Name: Sustainable Development Capital LLP Place: London, United Kingdom Zip: W1S 3AT Product: Investment bank working with financial...

  10. Conservation Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Conservation Capital LLC Jump to: navigation, search Name: Conservation Capital LLC Place: Houston, Texas Zip: 77018 Product: Houston-based land investment and consulting company...

  11. Longboard Capital Advisors | Open Energy Information

    Open Energy Info (EERE)

    Longboard Capital Advisors Jump to: navigation, search Name: Longboard Capital Advisors Place: Santa Monica, California Zip: 90405 Product: Longboard is a small hedge fund focused...

  12. Haywood Dorland Energy Capital | Open Energy Information

    Open Energy Info (EERE)

    Dorland Energy Capital Jump to: navigation, search Name: Haywood Dorland Energy Capital Place: New York, New York Sector: Renewable Energy Product: New York-based private equity...

  13. Energy Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    LLC Jump to: navigation, search Name: Energy Capital LLC Place: Ketchum, Idaho Zip: ID 83340 Sector: Renewable Energy Product: Energy Capital LLc is a financial catalyst focusing...

  14. Wind Farm Capital | Open Energy Information

    Open Energy Info (EERE)

    Farm Capital Jump to: navigation, search Name: Wind Farm Capital Place: Connecticut Sector: Wind energy Product: US-based company that buys wind leases from farmers and landowners,...

  15. Beijing Capital International Airport | Open Energy Information

    Open Energy Info (EERE)

    International Airport Jump to: navigation, search Name: Beijing Capital International Airport Place: Beijing, Beijing Municipality, China Zip: 100621 Product: Beijing Capital...

  16. Nimes Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Nimes Capital LLC Jump to: navigation, search Name: Nimes Capital LLC Place: Los Angeles, California Zip: 90067 Product: Los Angeles-based private equity firm that provides growth...

  17. Clean Earth Capital LLP | Open Energy Information

    Open Energy Info (EERE)

    Capital LLP Jump to: navigation, search Name: Clean Earth Capital LLP Place: EDINBURGH, United Kingdom Zip: EH6 4NW Sector: Renewable Energy Product: Edinburgh-based corporate...

  18. Sequoia Capital Ltda | Open Energy Information

    Open Energy Info (EERE)

    Capital Ltda Jump to: navigation, search Name: Sequoia Capital Ltda Place: Sao Paulo, Sao Paulo, Brazil Sector: Wind energy Product: Brazilian-based wind project developer....

  19. Wind Capital Group | Open Energy Information

    Open Energy Info (EERE)

    Capital Group Jump to: navigation, search Name: Wind Capital Group Place: St. Louis, Missouri Zip: 63101 Sector: Wind energy Product: Missouri-based wind project developer, focused...

  20. Impact Capital Partners Limited | Open Energy Information

    Open Energy Info (EERE)

    Capital Partners Limited Jump to: navigation, search Name: Impact Capital Partners Limited Place: Los Angeles, California Zip: CA 90067-1509 Product: Los Angeles-based, investment...

  1. Ambata Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    Ambata Capital Partners Jump to: navigation, search Name: Ambata Capital Partners Place: New York, New York Zip: 10169 Product: New York-based global investment and advisory firm...

  2. Strategic Capital Investments LLC | Open Energy Information

    Open Energy Info (EERE)

    Capital Investments LLC Jump to: navigation, search Name: Strategic Capital Investments LLC Place: Short Hills, New Jersey Zip: 7078 Product: New Jersey-based, project development...

  3. James Monroe Capital Corporation | Open Energy Information

    Open Energy Info (EERE)

    Monroe Capital Corporation Jump to: navigation, search Name: James Monroe Capital Corporation Place: United States Sector: Services Product: General Financial & Legal Services (...

  4. Birch Tree Capital | Open Energy Information

    Open Energy Info (EERE)

    Birch Tree Capital Jump to: navigation, search Name: Birch Tree Capital Place: Framingham, Massachusetts Zip: 1701 Sector: Renewable Energy Product: Financial advisory service with...

  5. American Capital Energy Inc | Open Energy Information

    Open Energy Info (EERE)

    Capital Energy Inc Jump to: navigation, search Name: American Capital Energy Inc Place: North Chelmsford, Massachusetts Zip: 1863 Sector: Services Product: Full-service PV...

  6. Bannockburn Capital LTD | Open Energy Information

    Open Energy Info (EERE)

    Bannockburn Capital LTD Jump to: navigation, search Name: Bannockburn Capital, LTD. Place: Newport Beach, California Zip: 92657 Sector: Carbon, Renewable Energy Product: String...

  7. Sustainable World Capital | Open Energy Information

    Open Energy Info (EERE)

    World Capital Jump to: navigation, search Name: Sustainable World Capital Place: Atlanta, Georgia Zip: 30326 Product: Atlanta-based firm that connects companies with institutional...

  8. West Mountain Energy Capital | Open Energy Information

    Open Energy Info (EERE)

    Energy Capital Jump to: navigation, search Name: West Mountain Energy Capital Place: Salisbury, Connecticut Zip: 6070 Sector: Renewable Energy Product: Provides renewable resource...

  9. Marathon Capital LLC (Illinois) | Open Energy Information

    Open Energy Info (EERE)

    Logo: Marathon Capital LLC (Illinois) Name: Marathon Capital LLC (Illinois) Address: 2801 Lakeside Drive, Suite 210 Place: Bannockburn, Illinois Zip: 60015 Product: Investment...

  10. Cate Street Capital Inc | Open Energy Information

    Open Energy Info (EERE)

    Cate Street Capital Inc Jump to: navigation, search Name: Cate Street Capital, Inc. Place: Portsmouth, New Hampshire Zip: 3801 Sector: Renewable Energy Product: New Hampshire-based...

  11. New Cycle Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Cycle Capital LLC Jump to: navigation, search Name: New Cycle Capital, LLC. Place: San Francisco, California Zip: 94103 Product: San Francisco-based venture capitalist firm...

  12. Nature Elements Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Nature Elements Capital Place: Beijing, Beijing Municipality, China Zip: 100125 Product: Beijing-based private equity firm investing in...

  13. Blue Green Capital | Open Energy Information

    Open Energy Info (EERE)

    Green Capital Jump to: navigation, search Name: Blue Green Capital Place: Spain Zip: 8860 Sector: Renewable Energy, Solar Product: String representation "Spanish develop ... their...

  14. Green Energy Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    Capital Partners Jump to: navigation, search Name: Green Energy Capital Partners Place: Plymouth Meeting, Pennsylvania Zip: 19462 Sector: Wind energy Product: Pennsylvania-based...

  15. L A Investment Capital | Open Energy Information

    Open Energy Info (EERE)

    A Investment Capital Jump to: navigation, search Name: L.A. Investment Capital Place: Beverly Hills, California Zip: CA 90210 Sector: Biofuels Product: Investment firm with funds...

  16. MVP Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    navigation, search Logo: MVP Capital Partners Name: MVP Capital Partners Address: 201 King of Prussia Road, Suite 240 Place: Radnor, Pennsylvania Zip: 19087 Region: Northeast -...

  17. Human Capital Management | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    human capital requires comprehensive planning and analysis in order to develop, implement, and evaluate programs that support every facet of employee work life. DOE human capital ...

  18. Startup Costs

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    This chapter discusses startup costs for construction and environmental projects, and estimating guidance for startup costs.

  19. Electricity Generation Cost Simulation Model

    Energy Science and Technology Software Center (OSTI)

    2003-04-25

    The Electricity Generation Cost Simulation Model (GENSIM) is a user-friendly, high-level dynamic simulation model that calculates electricity production costs for variety of electricity generation technologies, including: pulverized coal, gas combustion turbine, gas combined cycle, nuclear, solar (PV and thermal), and wind. The model allows the user to quickly conduct sensitivity analysis on key variables, including: capital, O&M, and fuel costs; interest rates; construction time; heat rates; and capacity factors. The model also includes consideration ofmore » a wide range of externality costs and pollution control options for carbon dioxide, nitrogen oxides, sulfur dioxide, and mercury. Two different data sets are included in the model; one from the U.S. Department of Energy (DOE) and the other from Platt's Research Group. Likely users of this model include executives and staff in the Congress, the Administration and private industry (power plant builders, industrial electricity users and electric utilities). The model seeks to improve understanding of the economic viability of various generating technologies and their emission trade-offs. The base case results using the DOE data, indicate that in the absence of externality costs, or renewable tax credits, pulverized coal and gas combined cycle plants are the least cost alternatives at 3.7 and 3.5 cents/kwhr, respectively. A complete sensitivity analysis on fuel, capital, and construction time shows that these results coal and gas are much more sensitive to assumption about fuel prices than they are to capital costs or construction times. The results also show that making nuclear competitive with coal or gas requires significant reductions in capital costs, to the $1000/kW level, if no other changes are made. For renewables, the results indicate that wind is now competitive with the nuclear option and is only competitive with coal and gas for grid connected applications if one includes the federal production tax

  20. Riba Capital | Open Energy Information

    Open Energy Info (EERE)

    Place: Spain Sector: Renewable Energy Product: Riba Capital is a fund developed to invest in renewable projects in Iberia. It raised 800 million euros of financing in 2003 and...

  1. Capital Solar | Open Energy Information

    Open Energy Info (EERE)

    Solar Jump to: navigation, search Name: Capital Solar Place: Lecce, Italy Sector: Solar Product: Lecce-based solar project developer. Coordinates: 40.357955, 18.16801 Show Map...

  2. Computerized operating cost model for industrial steam generation

    SciTech Connect (OSTI)

    Powers, T.D.

    1983-02-01

    Pending EPA regulations, establishing revised emission levels for industrial boilers are perceived to have an effect on the relative costs of steam production technologies. To aid in the comparison of competitive boiler technologies, the Steam Cost Code was developed which provides levelized steam costs reflecting the effects of a number of key steam cost parameters. The Steam Cost Code is a user interactive FORTRAN program designed to operate on a VAX computer system. The program requires the user to input a number of variables describing the design characteristics, capital costs, and operating conditions for a specific boiler system. Part of the input to the Steam Cost Code is the capital cost of the steam production system. The capital cost is obtained from a program called INDCEPT, developed by Oak Ridge National Laboratory under Department of Energy, Morgantown Energy Technology Center sponsorship.

  3. Breckinridge Project, initial effort. Report XI, Volume III. Critical design areas. [Identification of critical design areas; design or materials problems, trade-off areas, items affecting operability and reliability

    SciTech Connect (OSTI)

    1982-01-01

    Several meetings have been held with representatives from Ashland Synthetic Fuels, Inc.; Airco Energy Company, Inc.; Bechtel Group, Inc.; and HRI Engineering, Inc. to identify critical design areas in the Phase Zero work. (Critical design areas are defined as those requiring additional data or further work to finalize design or material selection, to optimize the trade-off between capital investment and operating cost, or to enhance system operability and reliability.) The critical design areas so identified are summarized by plant in this volume of Report XI. Items of a proprietary nature have been omitted from this report, but are included in the limited access version.

  4. IT Capital Planning | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    IT Capital Planning IT Capital Planning IT7 (003).jpg What is Capital Planning? The Office of Management and Budget (OMB) Circular A-11, defines capital planning as "a decision-making process for ensuring IT investments integrate strategic planning, budgeting, procurement, and IT management in support of agency missions and business needs." Who's Responsible for DOE Capital Planning? The Office of the Chief Information Officer (OCIO) oversees the DOE IT portfolio, while the Information

  5. Trends in U.S. Oil and Natural Gas Upstream Costs - Energy Information...

    U.S. Energy Information Administration (EIA) Indexed Site

    The IHS report assesses capital and operating costs associated with drilling, completing, and operating wells and facilities. The report focuses on five onshore regions, including ...

  6. ErgyCapital SpA formerly Greenergy Capital | Open Energy Information

    Open Energy Info (EERE)

    SpA formerly Greenergy Capital Jump to: navigation, search Name: ErgyCapital SpA (formerly Greenergy Capital) Place: Milan, Italy Zip: 20121 Sector: Efficiency, Renewable Energy...

  7. Capital Projects Estimated >$7 Million in Direct Costs Business

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Transformer Replacement G1, G3,G5-8 Federal Hydro *-- Sustain Replace the existing transformers. Black Canyon Units 1 & 2 Upgrades Federal Hydro *-- Sustain Upgrades to increase...

  8. Wind-To-Hydrogen Project: Electrolyzer Capital Cost Study

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    2008 Technical Report Wind-To-Hydrogen Project: NREL... H271.3730 National Renewable Energy Laboratory 1617 Cole ... hydrogen on a scale much greater than current production. ...

  9. Updated Capital Cost Estimates for Utility Scale Electricity...

    Annual Energy Outlook [U.S. Energy Information Administration (EIA)]

    ... update, the assumed characteristics of a coal plant with CCS in NEMS were assumed to be ... which is a nominal 650 MW coal-fired supercritical steam-electric generating ...

  10. Capital Sources and Providers | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Capital Sources and Providers Capital Sources and Providers An image of a blue diagram showing an arrow labeled "Lender" pointing to a rectangle labeled "Borrower" with a curved arrow labeled "Repayment" pointing back to "Lender." Another arrow labeled "Capital Sources" also points to the arrow labeled "Lender." The most important elements of a clean energy lending program are the capital source and the capital provider. The capital

  11. DOE Strategic Human Capital Plan (FY 2011 - 2015) | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Strategic Human Capital Plan (FY 2011 - 2015) DOE Strategic Human Capital Plan (FY 2011 - 2015) The Strategic Human Capital Plan sets forth the framework for managing the ...

  12. EA-185 Morgan Stanley Capital Group Inc. | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Morgan Stanley Capital Group Inc. EA-185 Morgan Stanley Capital Group Inc. Order authorizing Morgan Stanley Capital Group Inc. to export electric energy to Canada. EA-185 Morgan ...

  13. RockPort Capital Partners (California) | Open Energy Information

    Open Energy Info (EERE)

    RockPort Capital Partners (California) Jump to: navigation, search Logo: RockPort Capital Partners (California) Name: RockPort Capital Partners (California) Address: 3000 Sand Hill...

  14. Solar Access to Public Capital (SAPC) Mock Securitization Project

    SciTech Connect (OSTI)

    Mendelsohn, Michael; Lowder, Travis; Rottman, Mary; Borod, Ronald; Gabig, Nathan; Henne, Stephen; Caplin, Conrad; Notte, Quentin

    2015-12-21

    In late 2012, the National Renewable Energy Laboratory (NREL) initiated the Solar Access to Public Capital (SAPC) working group. Backed by a three-year funding facility from the U.S. Department of Energy (DOE), NREL set out to organize the solar, legal, banking, capital markets, engineering, and other relevant stakeholder communities in order to open lower-cost debt investment for solar asset deployment. SAPC engaged its members to standardize contracts, develop best practices, and comprehend how the rating agencies perceive solar project portfolios as an investment asset class. Rating agencies opine on the future creditworthiness of debt obligations. Issuers often seek investment-grade ratings from the rating agencies in order to satisfy the desires of their investors. Therefore, for the solar industry to access larger pools of capital at a favorable cost, it is critical to increase market participants' understanding of solar risk parameters. The process provided valuable information to address rating agency perceptions of risk that, without such information, could require costly credit enhancement or higher yields to attract institutional investors. Two different securities were developed--one for a hypothetical residential solar portfolio and one for a hypothetical commercial solar portfolio. Five rating agencies (Standard and Poor's, Moody's, KBRA, Fitch, and DBRS) participated and provided extensive feedback, some through conversations that extended several months. The findings represented in this report are a composite summary of that feedback and do not indicate any specific feedback from any single rating agency.

  15. Technical efforts focus on cutting LNG plant costs

    SciTech Connect (OSTI)

    Aoki, Ichizo; Kikkawa, Yoshitsugi

    1995-07-03

    LNG demand is growing due to the nuclear setback and environmental issues spurred by concern about the greenhouse effect and acid rain, especially in the Far East. However, LNG is expensive compared with other energy sources. Efforts continue to minimize capital and operating costs and to increase LNG plant availability and safety. Technical trends in the LNG industry aim at reducing plant costs in pursuit of a competitive LNG price on an energy value basis against the oil price. This article reviews key areas of technical development. Discussed are train size, liquefaction processes, acid gas removal, heavy end removal, nitrogen rejection, refrigeration compressor and drivers, expander application, cooling media selection, LNG storage and loading system, and plant availability.

  16. Sindicatum Carbon Capital SCC | Open Energy Information

    Open Energy Info (EERE)

    Sindicatum Carbon Capital SCC Jump to: navigation, search Name: Sindicatum Carbon Capital (SCC) Place: London, United Kingdom Zip: W1S 1HX Product: SCC is a specialist end-to-end...

  17. Carbon Capital Markets | Open Energy Information

    Open Energy Info (EERE)

    Capital Markets Jump to: navigation, search Name: Carbon Capital Markets Place: London, United Kingdom Zip: W1J 8DY Sector: Carbon Product: London-based fund manager and trader...

  18. Eco Drive Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    Capital Partners Jump to: navigation, search Name: Eco-Drive Capital Partners Place: New York Product: New York-based Eco-Drive is a European-American investment consortium,...

  19. Absolute Energy Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Absolute Energy Capital Place: London, United Kingdom Zip: SW1Y 5NQ Product: London-based private equity firm. Coordinates: 51.506325,...

  20. Englefield Capital LLP | Open Energy Information

    Open Energy Info (EERE)

    Englefield Capital LLP Jump to: navigation, search Name: Englefield Capital LLP Place: London, Greater London, United Kingdom Zip: SW3 6RD Product: London-based private equity fund...

  1. Emerging Edge Capital EEC | Open Energy Information

    Open Energy Info (EERE)

    Edge Capital EEC Jump to: navigation, search Name: Emerging Edge Capital (EEC) Place: London, United Kingdom Zip: SW1Y 4RS Sector: Renewable Energy Product: London-based company...

  2. Cinergy Capital & Trading, Inc | Open Energy Information

    Open Energy Info (EERE)

    Cinergy Capital & Trading, Inc Jump to: navigation, search Name: Cinergy Capital & Trading, Inc Place: Indiana Phone Number: (704) 382-3747 or (513) 287-2226 or (317) 838-1338...

  3. Eco Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Capital LLC Jump to: navigation, search Name: Eco Capital LLC Place: New York, New York Zip: 10166 Sector: Carbon, Renewable Energy Product: New York-based advisory and investment...

  4. Plane Tree Capital LLP | Open Energy Information

    Open Energy Info (EERE)

    Plane Tree Capital LLP Jump to: navigation, search Name: Plane Tree Capital LLP Place: London, United Kingdom Zip: W1J 8DY Sector: Carbon Product: London-based investment...

  5. Absolut Energy Capital | Open Energy Information

    Open Energy Info (EERE)

    Absolut Energy Capital Jump to: navigation, search Name: Absolut Energy Capital Place: London, England, United Kingdom Zip: W1H - 6HN Sector: Renewable Energy Product: London-based...

  6. Capital Cooking: Order (2014-CE-23008)

    Broader source: Energy.gov [DOE]

    DOE ordered Capital Cooking Equipment, Inc. to pay a $8,000 civil penalty after finding Capital Cooking had failed to certify that certain models of cooking products comply with the applicable energy conservation standards.

  7. Capital Asset Project List.xls

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... by DOE Order 413.3B, Program and Project Management for the Acquisition of Capital Assets. ... Start of Operations or Project Completion Capital Asset Project List 4112016 1 of 1

  8. EM Contractors for Capital Asset Projects

    Broader source: Energy.gov [DOE]

    Read the EM Contractors for Capital Asset Projects list, which includes the project name, number, site, and contractor.

  9. Venture Capital Finance | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Venture Capital Finance Venture Capital Finance Plenary III: Project Finance and Investment Venture Capital Finance Brian Baynes, Partner, Flagship Ventures baynes_biomass_2014.pdf (1.07 MB) More Documents & Publications Biomass 2011 Conference Agenda U.S. Biofuels Industry: Mind the Gap Review of Recent Pilot Scale Cellulosic Ethanol Demonstration

  10. Life Cycle Cost (LCC) Handbook Final Version 9-30-14

    Broader source: Energy.gov [DOE]

    This handbook provides procedures, information, examples, and tools to develop consistent and defensible life-cycle cost estimates (LCCE) and perform appropriate life-cycle cost analyses (LCCA) for capital projects. LCC Handbook – Final, September 2014

  11. National Lab Uses OGJ Data to Develop Cost Equations

    SciTech Connect (OSTI)

    Brown, Daryl R.; Cabe, James E.; Stout, Tyson E.

    2011-01-03

    For the past 30 years, the Oil and Gas Journal (OGJ) has published data on the costs of onshore and offshore oil and gas pipelines and related equipment. This article describes the methodology employed and resulting equations developed for conceptual capital cost estimating of onshore pipelines. Also described are cost trends uncovered during the course of the analysis.

  12. Offshore Wind Balance-of-System Cost Modeling

    SciTech Connect (OSTI)

    Maness, Michael; Stehly, Tyler; Maples, Ben; Mone, Christopher

    2015-09-29

    Offshore wind balance-of-system (BOS) costs contribute up to 70% of installed capital costs. Thus, it is imperative to understand the impact of these costs on project economics as well as potential cost trends for new offshore wind technology developments. As a result, the National Renewable Energy Laboratory (NREL) developed and recently updated a BOS techno-economic model using project cost estimates created from wind energy industry sources.

  13. Module process optimization and device efficiency improvement for stable, low-cost, large-area, cadmium telluride-based photovoltaic module production

    SciTech Connect (OSTI)

    Albright, S.P.; Ackerman, B.; Chamberlin, R.R.; Jordan, J.F. )

    1992-04-01

    This report describes work under a three-year phased subcontract to develop CdS/CdTe devices and modules and to further improve the technology base at Photon Energy, Inc. (PEI) to better address the commercialization issues and objectives of the PEI and the US Department of Energy. During this reporting period we (1) achieved efficiencies of 12.7% on small area devices, (2) achieved 1-ft{sup 2} modules with over 8% aperture-area efficiency (and active area efficiencies up to {approximately}10%), (3) tested 4-ft{sup 2} modules at NREL at 23.1 (21.3) watts, normalized (6.3% efficiency), and (4) found no inherent stability problems with CdTe technology during life testing, at both NREL and PEI. 7 refs.

  14. Trends in U.S. Venture Capital Investments Related to Energy: 1980-2007

    SciTech Connect (OSTI)

    Dooley, James J.

    2008-10-10

    This report documents trends in U.S. venture capital investments over the period 1980-2008. Particular attention is given to U.S. venture capital investments for “internet-specific”, biotechnology, and energy / industrial sectors over the period 1980-2007. During the early 1980s, U.S. venture capital investments in the energy / industrial area accounted for more than 20% of all venture capital investments. However subsequent periods of low energy prices and the emergence of fast growing new industries like computers (both hardware and software), biotechnology and the Internet quickly reduced the priority accorded to energy / industrial investments as by 2000 these investments accounted for only 1% of the $119 billion dollars invested that year by the U.S. venture capital community. The significant increase in the real price of oil that began in 2003-2004 correlates with renewed interest and increased investment by the venture capital community in energy / industrial investment opportunities. Venture capital investments in 2007 for the energy / industrial sector accounted for $3 billion or slightly more than 10% of all venture capital invested that year.

  15. Program and Project Management for the Acquisition of Capital Assets

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2010-11-29

    The purpose of this Order is to a) provide the Department of Energy (DOE) Elements, including the National Nuclear Security Administration (NNSA), with program and project management direction for the acquisition of capital assets with the goal of delivering projects within the original performance baseline (PB), cost and schedule, and fully capable of meeting mission performance, safeguards and security, and environmental, safety, and health requirements unless impacted by a directed change; and b) implement Office of Management and Budget (OMB) Circulars to include: A-11, Part 7, Capital Programming Guide, which prescribes new requirements and leading practices for project and acquisition management; A-123, Management's Responsibility for Internal Control, which defines management's responsibility for internal control in Federal agencies; and A-131, Value Engineering, which requires that all Federal agencies use Value Engineering (VE) as a management tool. Supersedes DOE O 413.3B Chg 1 (AdminChg)

  16. Program and Project Management for the Acquisition of Capital Assets

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2010-11-29

    The purpose of this Order is to a) provide the Department of Energy (DOE) Elements, including the National Nuclear Security Administration (NNSA), with program and project management direction for the acquisition of capital assets with the goal of delivering projects within the original performance baseline (PB), cost and schedule, and fully capable of meeting mission performance, safeguards and security, and environmental, safety, and health requirements unless impacted by a directed change; and b) implement Office of Management and Budget (OMB) Circulars to include: A-11, Part 7, Capital Programming Guide, which prescribes new requirements and leading practices for project and acquisition management; A-123, Management's Responsibility for Internal Control, which defines management's responsibility for internal control in Federal agencies; and A-131, Value Engineering, which requires that all Federal agencies use Value Engineering (VE) as a management tool.

  17. Heliostat cost reduction study.

    SciTech Connect (OSTI)

    Jones, Scott A.; Lumia, Ronald. (University of New Mexico, Albuquerque, NM); Davenport, Roger (Science Applications International Corporation, San Diego, CA); Thomas, Robert C. (Advanced Thermal Systems, Centennial, CO); Gorman, David; Kolb, Gregory J.; Donnelly, Matthew W.

    2007-06-01

    Power towers are capable of producing solar-generated electricity and hydrogen on a large scale. Heliostats are the most important cost element of a solar power tower plant. Since they constitute {approx} 50% of the capital cost of the plant it is important to reduce heliostat cost as much as possible to improve the economic performance of power towers. In this study we evaluate current heliostat technology and estimate a price of $126/m{sup 2} given year-2006 materials and labor costs for a deployment of {approx}600 MW of power towers per year. This 2006 price yields electricity at $0.067/kWh and hydrogen at $3.20/kg. We propose research and development that should ultimately lead to a price as low as $90/m{sup 2}, which equates to $0.056/kWh and $2.75/kg H{sup 2}. Approximately 30 heliostat and manufacturing experts from the United States, Europe, and Australia contributed to the content of this report during two separate workshops conducted at the National Solar Thermal Test Facility.

  18. Novel Low Cost, High Reliability Wind Turbine Drivetrain

    SciTech Connect (OSTI)

    Chobot, Anthony; Das, Debarshi; Mayer, Tyler; Markey, Zach; Martinson, Tim; Reeve, Hayden; Attridge, Paul; El-Wardany, Tahany

    2012-09-13

    Clipper Windpower, in collaboration with United Technologies Research Center, the National Renewable Energy Laboratory, and Hamilton Sundstrand Corporation, developed a low-cost, deflection-compliant, reliable, and serviceable chain drive speed increaser. This chain and sprocket drivetrain design offers significant breakthroughs in the areas of cost and serviceability and addresses the key challenges of current geared and direct-drive systems. The use of gearboxes has proven to be challenging; the large torques and bending loads associated with use in large multi-MW wind applications have generally limited demonstrated lifetime to 8-10 years [1]. The large cost of gearbox replacement and the required use of large, expensive cranes can result in gearbox replacement costs on the order of $1M, representing a significant impact to overall cost of energy (COE). Direct-drive machines eliminate the gearbox, thereby targeting increased reliability and reduced life-cycle cost. However, the slow rotational speeds require very large and costly generators, which also typically have an undesirable dependence on expensive rare-earth magnet materials and large structural penalties for precise air gap control. The cost of rare-earth materials has increased 20X in the last 8 years representing a key risk to ever realizing the promised cost of energy reductions from direct-drive generators. A common challenge to both geared and direct drive architectures is a limited ability to manage input shaft deflections. The proposed Clipper drivetrain is deflection-compliant, insulating later drivetrain stages and generators from off-axis loads. The system is modular, allowing for all key parts to be removed and replaced without the use of a high capacity crane. Finally, the technology modularity allows for scalability and many possible drivetrain topologies. These benefits enable reductions in drivetrain capital cost by 10.0%, levelized replacement and O&M costs by 26.7%, and overall cost of

  19. HTGR Cost Model Users' Manual

    SciTech Connect (OSTI)

    A.M. Gandrik

    2012-01-01

    The High Temperature Gas-Cooler Reactor (HTGR) Cost Model was developed at the Idaho National Laboratory for the Next Generation Nuclear Plant Project. The HTGR Cost Model calculates an estimate of the capital costs, annual operating and maintenance costs, and decommissioning costs for a high-temperature gas-cooled reactor. The user can generate these costs for multiple reactor outlet temperatures; with and without power cycles, including either a Brayton or Rankine cycle; for the demonstration plant, first of a kind, or nth of a kind project phases; for a single or four-pack configuration; and for a reactor size of 350 or 600 MWt. This users manual contains the mathematical models and operating instructions for the HTGR Cost Model. Instructions, screenshots, and examples are provided to guide the user through the HTGR Cost Model. This model was design for users who are familiar with the HTGR design and Excel. Modification of the HTGR Cost Model should only be performed by users familiar with Excel and Visual Basic.

  20. Working Capital for Contractors | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Capital for Contractors Working Capital for Contractors Better Buildings Neighborhood Program Financing Peer Exchange Call: Working Capital for Contractors, Call Slides and Discussion Summary, August 30, 2012. Call Slides and Discussion Summary (673.52 KB) More Documents & Publications Streamline Service Delivery via Customer Communication and Contractor Coordination Focus Series: OREGON-On Bill Financing Program: On-Bill Financing Brings Lenders and Homeowners On Board Lessons from On-Bill

  1. GE Capital Partnership | GE Global Research

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Global Research and GE Capital: Middle Market Collaboration Click to email this to a friend (Opens in new window) Share on Facebook (Opens in new window) Click to share (Opens in new window) Click to share on LinkedIn (Opens in new window) Click to share on Tumblr (Opens in new window) Global Research and GE Capital: Middle Market Collaboration In 2013, a partnering initiative between Global Research and GE Capital resulted in dozens of middle market companies collaborating with Global Research

  2. Ethanol Capital Management | Open Energy Information

    Open Energy Info (EERE)

    Management Jump to: navigation, search Name: Ethanol Capital Management Place: Tucson, Arizona Zip: 85711 Product: Manages funds investing in Ethanol plants in the US Coordinates:...

  3. Persimmon Tree Capital | Open Energy Information

    Open Energy Info (EERE)

    Renewable Energy Product: Persimmon is a private equity fund established in 2008 to invest in renewable energy firms. References: Persimmon Tree Capital1 This article is a...

  4. Environmental Capital Partners LLC | Open Energy Information

    Open Energy Info (EERE)

    Partners LLC Jump to: navigation, search Name: Environmental Capital Partners LLC Place: New York, New York Zip: 10017 Sector: Services Product: Private equity firm funded with USD...

  5. Global Capital Finance | Open Energy Information

    Open Energy Info (EERE)

    Finance Jump to: navigation, search Name: Global Capital Finance Place: Purchase, New York Zip: 10577 Sector: Renewable Energy, Services Product: New York-based international...

  6. Environmental Capital Group LLC | Open Energy Information

    Open Energy Info (EERE)

    Group LLC Jump to: navigation, search Name: Environmental Capital Group LLC Place: Grass Valley, California Zip: 95945 Product: String representation "Environmental C ... tartup...

  7. Energy Capital Investments | Open Energy Information

    Open Energy Info (EERE)

    Investments Jump to: navigation, search Name: Energy Capital Investments Place: Phoenix, Arizona Zip: 85016 Product: An investment firm established by Najafi Companies with the...

  8. Solar Capital Inc | Open Energy Information

    Open Energy Info (EERE)

    Inc Jump to: navigation, search Name: Solar Capital Inc Place: Benicia, California Zip: 94510 Sector: Solar Product: Start-up investment firm seeking control positions in companies...

  9. Capital Electric Coop, Inc | Open Energy Information

    Open Energy Info (EERE)

    Capital Electric Coop, Inc Place: North Dakota Phone Number: 1.701.223.1513 Website: capitalelec.com Facebook: https:www.facebook.comcapitalelectricnd?refhl Outage Hotline:...

  10. RAM Capital Management Group | Open Energy Information

    Open Energy Info (EERE)

    Hydrogen Product: Private VC fund and investment banking advisory firm investing in fuel cells and hydrogen. References: RAM Capital Management Group1 This article is a...

  11. Capital Energy SL | Open Energy Information

    Open Energy Info (EERE)

    search Name: Capital Energy SL Place: Madrid, Spain Zip: 28016 Sector: Solar, Wind energy Product: Offshore wind farm, solar and biodiesel plant developer. Coordinates:...

  12. Capital Cooking: Proposed Penalty (2014-CE-23008)

    Broader source: Energy.gov [DOE]

    DOE alleged in a Notice of Proposed Civil Penalty that Capital Cooking Equipment, Inc. failed to certify cooking products as compliant with the applicable energy conservation standards.

  13. Human Capital Management Accountability Program (HCMAP) | Department...

    Broader source: Energy.gov (indexed) [DOE]

    Human Capital Management Accountability Program (HCMAP) is an online program which serves ... and financial HR metrics that assist human resources professionals in identifying ...

  14. Human Capital Organization | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    Human Capital Officer provides leadership to the Department of Energy (DOE) on the impact and use of policies, proposals, programs, and partnerships related to all aspects of Human ...

  15. Human Capital Management Accountability Program (HCMAP)

    Broader source: Energy.gov [DOE]

    Human Capital Management Accountability Program (HCMAP) is an online program which serves as the vehicle for identifying and measuring these three factors, effectiveness, efficiency, and timeliness...

  16. Copy of Capitalized Property RO23_120213_1.xlsx

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Capitalized Property 1 RO BARCODE DESCRIPTION MANUF. MODEL SN COST BLDG ROOM INVT_DATE 23 C5508 PRECISION ION POLISH GATAN INC 691 UNIT 427 01070301 $50,626.00 28 113 24-Sep-13 23 0000002116 TouchTable System TOUCHTABLE TT45 TT45S000378 $52,986.00 B03 134 19-Sep-13 23 0000002362 SYSTEM PUMP AMETEK Q AMETEK Q5000 CYL1A1308CYLIB1309CM $56,260.00 OFF TEXAS 11-Sep-12 23 0000000577 ANALYSIS SYSTEM BENC PFEIFFER GSD 301 C 44253789 $57,731.50 B25 115 30-Sep-13 23 0000002222 SLAVE NODES PSSC LABS PSSC

  17. EA-184-B MORGAN STANLEY CAPITAL GROUP | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    -B MORGAN STANLEY CAPITAL GROUP EA-184-B MORGAN STANLEY CAPITAL GROUP Order authorizing Morgan Stanley Capital Group to export electric energy to Mexico. EA-184-B MSCG MX.pdf ...

  18. Agri capital GmbH | Open Energy Information

    Open Energy Info (EERE)

    capital GmbH Jump to: navigation, search Name: agri.capital GmbH Place: Muenster, North Rhine-Westphalia, Germany Zip: 48155 Product: Muenster-based agri.capital develops and...

  19. BluePlanet Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    BluePlanet Capital LLC Jump to: navigation, search Name: BluePlanet Capital LLC Place: Washington, Connecticut Zip: 6793 Sector: Services Product: BluePlanet Capital is an...

  20. Pulsar Energy Capital L L P | Open Energy Information

    Open Energy Info (EERE)

    Pulsar Energy Capital L L P Jump to: navigation, search Name: Pulsar Energy Capital L.L.P. Place: London, United Kingdom Zip: SW20 0PU Product: Pulsar Energy Capital LLP is a...

  1. BPA's Costs

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    links Financial Information Financial Public Processes Asset Management Cost Verification Process Rate Cases BP-18 Rate Case Related Publications Meetings and Workshops Customer...

  2. Microsoft PowerPoint - Crouther.HumanCapitalInitiatives.042909

    Office of Environmental Management (EM)

    Human Capital Initiatives Presented to the Environmental Management Advisory Board (EMAB) By Desi Crouther, Acting Director Office of Human Capital Office of Environmental Management ...

  3. Grupo Maris Capital ethanol refinery | Open Energy Information

    Open Energy Info (EERE)

    Maris Capital ethanol refinery Jump to: navigation, search Name: Grupo Maris (Capital ethanol refinery) Place: Nuporanga, Brazil Product: 32,000 m3 ethanol refinery owner...

  4. Carbon Credit Capital and Feedback Ventures JV | Open Energy...

    Open Energy Info (EERE)

    Capital and Feedback Ventures JV Jump to: navigation, search Name: Carbon Credit Capital and Feedback Ventures JV Place: India Sector: Carbon Product: String representation "Carbon...

  5. Program & Project Management For The Acquisition Of Capital Assets...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Program & Project Management For The Acquisition Of Capital Assets Program & Project Management For The Acquisition Of Capital Assets 2014 DOE Project Management Workshop ...

  6. Maryland-National Capital Building Industry Association Regulatory...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Maryland-National Capital Building Industry Association Regulatory Burden RFI (Federal Register August 8, 2012) Maryland-National Capital Building Industry Association Regulatory ...

  7. Energy and Environmental Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Capital LLC Jump to: navigation, search Name: Energy and Environmental Capital LLC Place: Washington, DC Sector: Carbon Product: The company focuses on carbon trading in ex-Soviet...

  8. BlueWave Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    BlueWave Capital LLC Jump to: navigation, search Name: BlueWave Capital LLC Place: Boston, Massachusetts Sector: Renewable Energy Product: Knowledge-based investment firm focused...

  9. Ricmore Capital PLC Formerly Energy Asset Management Plc | Open...

    Open Energy Info (EERE)

    Ricmore Capital PLC Formerly Energy Asset Management Plc Jump to: navigation, search Name: Ricmore Capital PLC (Formerly Energy Asset Management Plc) Place: United Kingdom Sector:...

  10. MissionPoint Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    MissionPoint Capital Partners Jump to: navigation, search Name: MissionPoint Capital Partners Place: Norwalk, Connecticut Zip: CT 06854 Product: Private Investment company...

  11. Sustainable Energy Capital Partners SECP | Open Energy Information

    Open Energy Info (EERE)

    Capital Partners SECP Jump to: navigation, search Name: Sustainable Energy Capital Partners (SECP) Place: Santa Ana, California Zip: 92705 Sector: Renewable Energy Product:...

  12. Program & Project Management For The Acquisition Of Capital Assets...

    Broader source: Energy.gov (indexed) [DOE]

    More Documents & Publications Program & Project Management For The Acquisition Of Capital Assets Program & Project Management For The Acquisition Of Capital Assets PARS II...

  13. DTE Energy Venture formerly EdVenture Capital Corporation | Open...

    Open Energy Info (EERE)

    Venture formerly EdVenture Capital Corporation Jump to: navigation, search Name: DTE Energy Venture (formerly EdVenture Capital Corporation) Place: Detroit, Michigan Zip: 48226...

  14. Noventi Venture Capital formerly CIR Ventures | Open Energy Informatio...

    Open Energy Info (EERE)

    Noventi Venture Capital formerly CIR Ventures Jump to: navigation, search Name: Noventi Venture Capital (formerly CIR Ventures) Place: Menlo Park, California Zip: CA 94025 Product:...

  15. RockPort Capital Partners (Massachusetts) | Open Energy Information

    Open Energy Info (EERE)

    RockPort Capital Partners (Massachusetts) Name: RockPort Capital Partners (Massachusetts) Address: 160 Federal Street, 18th Floor Place: Boston, Massachusetts Zip: 02110 Region:...

  16. Sinopec Beijing Capital Sci Tech Group JV | Open Energy Information

    Open Energy Info (EERE)

    Sinopec Beijing Capital Sci Tech Group JV Jump to: navigation, search Name: Sinopec & Beijing Capital Sci Tech Group JV Place: Beijing Municipality, China Product: China-based...

  17. Acro Energy Technologies formerly Lonestar Capital | Open Energy...

    Open Energy Info (EERE)

    Energy Technologies formerly Lonestar Capital Jump to: navigation, search Name: Acro Energy Technologies (formerly Lonestar Capital) Place: Oakdale, California Zip: 95361 Sector:...

  18. Green Capital Consulting Company GCCC | Open Energy Information

    Open Energy Info (EERE)

    Consulting Company GCCC Jump to: navigation, search Name: Green Capital Consulting Company (GCCC) Place: Beijing, China Zip: 100022 Product: Green Capital Consulting Company (GCCC)...

  19. IFCI Venture Capital Funds Ltd | Open Energy Information

    Open Energy Info (EERE)

    IFCI Venture Capital Funds Ltd Jump to: navigation, search Name: IFCI Venture Capital Funds Ltd Place: New Delhi, Delhi (NCT), India Zip: 110019 Product: Manager of several funds...

  20. Clean World Capital A S | Open Energy Information

    Open Energy Info (EERE)

    World Capital A S Jump to: navigation, search Name: Clean World Capital AS Place: Lyngby, Denmark Sector: Carbon Product: A cleantech finance house based in Copenhagen and London....

  1. CE2 Capital Partners LLC | Open Energy Information

    Open Energy Info (EERE)

    Capital Partners LLC Jump to: navigation, search Name: CE2 Capital Partners LLC Place: Solana Beach, California Zip: 92075 Sector: Carbon, Renewable Energy Product:...

  2. Low Capital Photovoltaic Panel Electrical Output-Booster System...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Low Capital Photovoltaic Panel Electrical Output-Booster System Low Capital Photovoltaic Panel Electrical Output-Booster System This presentation summarizes the information given ...

  3. Free Stream Capital Partners Limited | Open Energy Information

    Open Energy Info (EERE)

    Capital Partners Limited Jump to: navigation, search Name: Free Stream Capital Partners Limited Place: London, Greater London, United Kingdom Zip: SW1Y 4AA Sector: Wind energy...

  4. TianDi Growth Capital | Open Energy Information

    Open Energy Info (EERE)

    Venture capital investor interested in projects in Wind energy, Electric vehicles, Energy-efficient lighting, Biodiesel and Clean water. References: TianDi Growth Capital1...

  5. Manager's Desk Reference on Human Capital Management Flexibilities...

    Broader source: Energy.gov (indexed) [DOE]

    that can be used in day-to-day human capital management activities, especially ... Manager's Desk Reference on Human Capital Management Flexibilities (640.69 KB) Responsible ...

  6. DOE Strategic Human Capital Plan | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    The current Strategic Human Capital Plan (SHCP) sets forth the framework for managing the Department of Energy's (DOE) human capital system through 2020. This Plan, which replaces ...

  7. Office of the Chief Human Capital Officer (HC-1) | Department...

    Broader source: Energy.gov (indexed) [DOE]

    HC-1 Mission and Function Statement The Office of the Chief Human Capital Officer (HC) ... agreementsrelationships related to all aspects of Human Capital Management (HCM). ...

  8. EGov PMA Scorecard Cost, Schedule & Performance Standard.tif | Department

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    of Energy EGov PMA Scorecard Cost, Schedule & Performance Standard.tif EGov PMA Scorecard Cost, Schedule & Performance Standard.tif EGov PMA Scorecard Cost, Schedule & Performance Standard.tif (1.8 MB) More Documents & Publications Program & Project Management For The Acquisition Of Capital Assets Program & Project Management For The Acquisition Of Capital Assets Program & Project Management For The Acquisition Of Capital Assets

  9. How three smart managers control steam costs

    SciTech Connect (OSTI)

    Kendall, R.

    1982-11-01

    Three steam-intensive companies report innovative ways to reduce steam-production costs. Goodyear Tire and Rubber Co. concentrated on regular maintenance, process modifications, and heat recovery, but also has an on-going policy of seeking further cost savings. Future efforts will explore computer-based boiler controls. Zenith Radio Corporation's color picture tube-making process uses 12% less steam after 700 mechanical steam traps were replaced with fixed-orifice traps. Petro-Tex Chemical Corp. reduced steam costs by monitoring and optimizing process units and by making capital investments to improve steam management. (DCK)

  10. Realistic costs of carbon capture

    SciTech Connect (OSTI)

    Al Juaied, Mohammed . Belfer Center for Science and International Affiaris); Whitmore, Adam )

    2009-07-01

    There is a growing interest in carbon capture and storage (CCS) as a means of reducing carbon dioxide (CO2) emissions. However there are substantial uncertainties about the costs of CCS. Costs for pre-combustion capture with compression (i.e. excluding costs of transport and storage and any revenue from EOR associated with storage) are examined in this discussion paper for First-of-a-Kind (FOAK) plant and for more mature technologies, or Nth-of-a-Kind plant (NOAK). For FOAK plant using solid fuels the levelised cost of electricity on a 2008 basis is approximately 10 cents/kWh higher with capture than for conventional plants (with a range of 8-12 cents/kWh). Costs of abatement are found typically to be approximately US$150/tCO2 avoided (with a range of US$120-180/tCO2 avoided). For NOAK plants the additional cost of electricity with capture is approximately 2-5 cents/kWh, with costs of the range of US$35-70/tCO2 avoided. Costs of abatement with carbon capture for other fuels and technologies are also estimated for NOAK plants. The costs of abatement are calculated with reference to conventional SCPC plant for both emissions and costs of electricity. Estimates for both FOAK and NOAK are mainly based on cost data from 2008, which was at the end of a period of sustained escalation in the costs of power generation plant and other large capital projects. There are now indications of costs falling from these levels. This may reduce the costs of abatement and costs presented here may be 'peak of the market' estimates. If general cost levels return, for example, to those prevailing in 2005 to 2006 (by which time significant cost escalation had already occurred from previous levels), then costs of capture and compression for FOAK plants are expected to be US$110/tCO2 avoided (with a range of US$90-135/tCO2 avoided). For NOAK plants costs are expected to be US$25-50/tCO2. Based on these considerations a likely representative range of costs of abatement from CCS excluding

  11. Landed Costs of Imported Crude by Area

    Gasoline and Diesel Fuel Update (EIA)

    Values shown for the current two months are preliminary. Values shown for the previous two months may be revised to account for late submissions and corrections. Final revisions to monthly and annual values are available upon publication of the June Petroleum Marketing Monthly. Annual averages that precede the release of the June Petroleum Marketing Monthly are calculated from monthly data. Data through 2015 are final.

  12. Landed Costs of Imported Crude by Area

    U.S. Energy Information Administration (EIA) Indexed Site

    107.07 103.00 88.29 1973-2014 Angola 61.32 80.61 114.05 114.95 110.81 99.25 1973-2014 Mexico 57.35 72.86 101.21 102.45 99.06 87.48 1973-2014 Nigeria 68.01 83.14 116.43 116.88...

  13. Beetle Capital Partners BCP | Open Energy Information

    Open Energy Info (EERE)

    Partners BCP Jump to: navigation, search Name: Beetle Capital Partners (BCP) Place: London, United Kingdom Zip: W1S 1UA Sector: Carbon Product: London-based asset management...

  14. Cora Capital Advisors LLC | Open Energy Information

    Open Energy Info (EERE)

    Advisors LLC Jump to: navigation, search Name: Cora Capital Advisors LLC Place: New York, New York Zip: 10022 Sector: Renewable Energy Product: New York-based investment bank and...

  15. Capital Equipment Validation Form | The Ames Laboratory

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Capital Equipment Validation Form Version Number: 2.0 Document Number: Form 48100.001 Effective Date: 02/2015 File (public): Office spreadsheet icon form_48100.001_rev2.xls

  16. 2011-2015 Human Capital Management Plan

    Broader source: Energy.gov [DOE]

    The Office of Legacy Management (LM) needs skilled and engaged staff to accomplish our mission and carry out our responsibilities to the American people. This Human Capital Management Plan (HCMP or...

  17. 2016-2020 Strategic Human Capital Plan

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    the Chief Human Capital Officer 2016-2020 Strategic Human Capital Plan Cover Photo Description Beyond Double-Pane Windows While the invention of double-pane windows dates back to 1935, a true turning point in the technology came in the 1980s with a collaboration between the Department of Energy, private industry, and Lawrence Berkeley National Lab. Initial research and development by Berkeley Lab and a start-up company, Suntek Research Associates (now called Southwall Technologies), led to the

  18. Understanding Cost Growth and Performance Shortfalls in Pioneer Process

    Office of Environmental Management (EM)

    Plants | Department of Energy Cost Growth and Performance Shortfalls in Pioneer Process Plants Understanding Cost Growth and Performance Shortfalls in Pioneer Process Plants This report presents an empirical and quantitative analysis of the misestimation of the capital costs and performance of innovative energy process plants and other chemical process facilities that create fundamental problems for government and industry in planning the development and commercialization of such plants.

  19. Building Life Cycle Cost Programs | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Building Life Cycle Cost Programs Building Life Cycle Cost Programs The National Institute of Standards and Technology (NIST) developed the Building Life Cycle Cost (BLCC) Programs to provide computational support for the analysis of capital investments in buildings. They include BLCC5, the Energy Escalation Rate Calculator, Handbook 135, and the Annual Supplement to Handbook 135. BLCC5 Program Register and download. BLCC 5.3-15 (for Windows or Mac OS X). BLCC version 5.3-15 contains the

  20. Building Life Cycle Cost Programs | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Building Life Cycle Cost Programs Building Life Cycle Cost Programs The National Institute of Standards and Technology (NIST) developed the Building Life Cycle Cost (BLCC) Programs to provide computational support for the analysis of capital investments in buildings. They include BLCC5, the Energy Escalation Rate Calculator, Handbook 135, and the Annual Supplement to Handbook 135. BLCC5 Program Register and download. BLCC 5.3-15 (for Windows or Mac OS X). BLCC version 5.3-15 contains the

  1. Decommissioning Unit Cost Data

    SciTech Connect (OSTI)

    Sanford, P. C.; Stevens, J. L.; Brandt, R.

    2002-02-26

    The Rocky Flats Closure Site (Site) is in the process of stabilizing residual nuclear materials, decommissioning nuclear facilities, and remediating environmental media. A number of contaminated facilities have been decommissioned, including one building, Building 779, that contained gloveboxes used for plutonium process development but did little actual plutonium processing. The actual costs incurred to decommission this facility formed much of the basis or standards used to estimate the decommissioning of the remaining plutonium-processing buildings. Recent decommissioning activities in the first actual production facility, Building 771, implemented a number of process and procedural improvements. These include methods for handling plutonium contaminated equipment, including size reduction, decontamination, and waste packaging, as well as management improvements to streamline planning and work control. These improvements resulted in a safer working environment and reduced project cost, as demonstrated in the overall project efficiency. The topic of this paper is the analysis of how this improved efficiency is reflected in recent unit costs for activities specific to the decommissioning of plutonium facilities. This analysis will allow the Site to quantify the impacts on future Rocky Flats decommissioning activities, and to develop data for planning and cost estimating the decommissioning of future facilities. The paper discusses the methods used to collect and arrange the project data from the individual work areas within Building 771. Regression and data correlation techniques were used to quantify values for different types of decommissioning activities. The discussion includes the approach to identify and allocate overall project support, waste management, and Site support costs based on the overall Site and project costs to provide a ''burdened'' unit cost. The paper ultimately provides a unit cost basis that can be used to support cost estimates for

  2. WREF 2012: THE PAST AND FUTURE COST OF WIND ENERGY

    SciTech Connect (OSTI)

    NREL,; Wiser, Ryan; Lantz, Eric; Hand, Maureen

    2012-03-26

    The future of wind power will depend on the ability of the industry to continue to achieve cost reductions. To better understand the potential for cost reductions, this report provides a review of historical costs, evaluates near-term market trends, and summarizes the range of projected costs. It also notes potential sources of future cost reductions. Our findings indicate that steady cost reductions were interrupted between 2004 and 2010, but falling turbine prices and improved turbine performance are expected to drive a historically low LCOE for current installations. In addition, the majority of studies indicate continued cost reductions on the order of 20%-30% through 2030. Moreover, useful cost projections are likely to benefit from stronger consideration of the interactions between capital cost and performance as well as trends in the quality of the wind resource where projects are located, transmission, grid integration, and other cost variables.

  3. Beyond Human Capital Development: Balanced Safeguards Workforce Metrics and the Next Generation Safeguards Workforce

    SciTech Connect (OSTI)

    Burbank, Roberta L.; Frazar, Sarah L.; Gitau, Ernest TN; Shergur, Jason M.; Scholz, Melissa A.; Undem, Halvor A.

    2014-03-28

    Since its establishment in 2008, the Next Generation Safeguards Initiative (NGSI) has achieved a number of objectives under its five pillars: concepts and approaches, policy development and outreach, international nuclear safeguards engagement, technology development, and human capital development (HCD). As a result of these efforts, safeguards has become much more visible as a critical U.S. national security interest across the U.S. Department of Energy (DOE) complex. However, limited budgets have since created challenges in a number of areas. Arguably, one of the more serious challenges involves NGSI’s ability to integrate entry-level staff into safeguards projects. Laissez fair management of this issue across the complex can lead to wasteful project implementation and endanger NGSI’s long-term sustainability. The authors provide a quantitative analysis of this problem, focusing on the demographics of the current safeguards workforce and compounding pressures to operate cost-effectively, transfer knowledge to the next generation of safeguards professionals, and sustain NGSI safeguards investments.

  4. cost savings

    National Nuclear Security Administration (NNSA)

    Savannah River Area had the opportunity to learn from the Savannah River Site's continuous improvement success stories when SRS management and operations contractor...

  5. Ocean Thermal Energy Conversion Life Cycle Cost Assessment, Final Technical Report, 30 May 2012

    SciTech Connect (OSTI)

    Martel, Laura; Smith, Paul; Rizea, Steven; Van Ryzin, Joe; Morgan, Charles; Noland, Gary; Pavlosky, Rick; Thomas, Michael; Halkyard, John

    2012-05-30

    The Ocean Thermal Energy Conversion (OTEC) Life Cycle Cost Assessment (OLCCA) is a study performed by members of the Lockheed Martin (LM) OTEC Team under funding from the Department of Energy (DOE), Award No. DE-EE0002663, dated 01/01/2010. OLCCA objectives are to estimate procurement, operations and maintenance, and overhaul costs for two types of OTEC plants: -Plants moored to the sea floor where the electricity produced by the OTEC plant is directly connected to the grid ashore via a marine power cable (Grid Connected OTEC plants) -Open-ocean grazing OTEC plant-ships producing an energy carrier that is transported to designated ports (Energy Carrier OTEC plants) Costs are developed using the concept of levelized cost of energy established by DOE for use in comparing electricity costs from various generating systems. One area of system costs that had not been developed in detail prior to this analysis was the operations and sustainment (O&S) cost for both types of OTEC plants. Procurement costs, generally referred to as capital expense and O&S costs (operations and maintenance (O&M) costs plus overhaul and replacement costs), are assessed over the 30 year operational life of the plants and an annual annuity calculated to achieve a levelized cost (constant across entire plant life). Dividing this levelized cost by the average annual energy production results in a levelized cost of electricity, or LCOE, for the OTEC plants. Technical and production efficiency enhancements that could result in a lower value of the OTEC LCOE were also explored. The thermal OTEC resource for Oahu, Hawaii and projected build out plan were developed. The estimate of the OTEC resource and LCOE values for the planned OTEC systems enable this information to be displayed as energy supplied versus levelized cost of the supplied energy; this curve is referred to as an Energy Supply Curve. The Oahu Energy Supply Curve represents initial OTEC deployment starting in 2018 and demonstrates the

  6. Load Leveling Battery System Costs

    Energy Science and Technology Software Center (OSTI)

    1994-10-12

    SYSPLAN evaluates capital investment in customer side of the meter load leveling battery systems. Such systems reduce the customer's monthly electrical demand charge by reducing the maximum power load supplied by the utility during the customer's peak demand. System equipment consists of a large array of batteries, a current converter, and balance of plant equipment and facilities required to support the battery and converter system. The system is installed on the customer's side of themore » meter and controlled and operated by the customer. Its economic feasibility depends largely on the customer's load profile. Load shape requirements, utility rate structures, and battery equipment cost and performance data serve as bases for determining whether a load leveling battery system is economically feasible for a particular installation. Life-cycle costs for system hardware include all costs associated with the purchase, installation, and operation of battery, converter, and balance of plant facilities and equipment. The SYSPLAN spreadsheet software is specifically designed to evaluate these costs and the reduced demand charge benefits; it completes a 20 year period life cycle cost analysis based on the battery system description and cost data. A built-in sensitivity analysis routine is also included for key battery cost parameters. The life cycle cost analysis spreadsheet is augmented by a system sizing routine to help users identify load leveling system size requirements for their facilities. The optional XSIZE system sizing spreadsheet which is included can be used to identify a range of battery system sizes that might be economically attractive. XSIZE output consisting of system operating requirements can then be passed by the temporary file SIZE to the main SYSPLAN spreadsheet.« less

  7. Benefits and Costs of Brine Extraction for Increasing Injection Efficiency In geologic CO2 Sequestration

    SciTech Connect (OSTI)

    Davidson, Casie L.; Watson, David J.; Dooley, James J.; Dahowski, Robert T.

    2014-12-31

    Pressure increases attendant with CO2 injection into the subsurface drive many of the risk factors associated with commercial-scale CCS projects, impacting project costs and liabilities in a number of ways. The area of elevated pressure defines the area that must be characterized and monitored; pressure drives fluid flow out of the storage reservoir along higher-permeability pathways that might exist through the caprock into overlying aquifers or hydrocarbon reservoirs; and pressure drives geomechanical changes that could potentially impact subsurface infrastructure or the integrity of the storage system itself. Pressure also limits injectivity, which can increase capital costs associated with installing additional wells to meet a given target injection rate. The ability to mitigate pressure increases in storage reservoirs could have significant value to a CCS project, but these benefits are offset by the costs of the pressure mitigation technique itself. Of particular interest for CO2 storage operators is the lifetime cost of implementing brine extraction at a CCS project site, and the relative value of benefits derived from the extraction process. This is expected to vary from site to site and from one implementation scenario to the next. Indeed, quantifying benefits against costs could allow operators to optimize their return on project investment by calculating the most effective scenario for pressure mitigation. This work builds on research recently submitted for publication by the authors examining the costs and benefits of brine extraction across operational scenarios to evaluate the effects of fluid extraction on injection rate to assess the cost effectiveness of several options for reducing the number of injection wells required. Modeling suggests that extracting at 90% of the volumetric equivalent of injection rate resulted in a 1.8% improvement in rate over a non-extraction base case; a four-fold increase in extraction rate results in a 7.6% increase in

  8. Benefits and Costs of Brine Extraction for Increasing Injection Efficiency In geologic CO2 Sequestration

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Davidson, Casie L.; Watson, David J.; Dooley, James J.; Dahowski, Robert T.

    2014-12-31

    Pressure increases attendant with CO2 injection into the subsurface drive many of the risk factors associated with commercial-scale CCS projects, impacting project costs and liabilities in a number of ways. The area of elevated pressure defines the area that must be characterized and monitored; pressure drives fluid flow out of the storage reservoir along higher-permeability pathways that might exist through the caprock into overlying aquifers or hydrocarbon reservoirs; and pressure drives geomechanical changes that could potentially impact subsurface infrastructure or the integrity of the storage system itself. Pressure also limits injectivity, which can increase capital costs associated with installing additionalmore » wells to meet a given target injection rate. The ability to mitigate pressure increases in storage reservoirs could have significant value to a CCS project, but these benefits are offset by the costs of the pressure mitigation technique itself. Of particular interest for CO2 storage operators is the lifetime cost of implementing brine extraction at a CCS project site, and the relative value of benefits derived from the extraction process. This is expected to vary from site to site and from one implementation scenario to the next. Indeed, quantifying benefits against costs could allow operators to optimize their return on project investment by calculating the most effective scenario for pressure mitigation. This work builds on research recently submitted for publication by the authors examining the costs and benefits of brine extraction across operational scenarios to evaluate the effects of fluid extraction on injection rate to assess the cost effectiveness of several options for reducing the number of injection wells required. Modeling suggests that extracting at 90% of the volumetric equivalent of injection rate resulted in a 1.8% improvement in rate over a non-extraction base case; a four-fold increase in extraction rate results in a 7

  9. Cost of presumptive source term Remedial Actions Laboratory for energy-related health research, University of California, Davis

    SciTech Connect (OSTI)

    Last, G.V.; Bagaasen, L.M.; Josephson, G.B.; Lanigan, D.C.; Liikala, T.L.; Newcomer, D.R.; Pearson, A.W.; Teel, S.S.

    1995-12-01

    A Remedial Investigation/Feasibility Study (RI/FS) is in progress at the Laboratory for Energy Related Health Research (LEHR) at the University of California, Davis. The purpose of the RI/FS is to gather sufficient information to support an informed risk management decision regarding the most appropriate remedial actions for impacted areas of the facility. In an effort to expedite remediation of the LEHR facility, the remedial project managers requested a more detailed evaluation of a selected set of remedial actions. In particular, they requested information on both characterization and remedial action costs. The US Department of Energy -- Oakland Office requested the assistance of the Pacific Northwest National Laboratory to prepare order-of-magnitude cost estimates for presumptive remedial actions being considered for the five source term operable units. The cost estimates presented in this report include characterization costs, capital costs, and annual operation and maintenance (O&M) costs. These cost estimates are intended to aid planning and direction of future environmental remediation efforts.

  10. An Evaluation of the Total Cost of Ownership of Fuel Cell-Powered Material

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Handling Equipment | Department of Energy An Evaluation of the Total Cost of Ownership of Fuel Cell-Powered Material Handling Equipment An Evaluation of the Total Cost of Ownership of Fuel Cell-Powered Material Handling Equipment This report by the National Renewable Energy Laboratory discusses an analysis of the total cost of ownership of fuel cell-powered and traditional battery-powered material handling equipment, including the capital costs of battery and fuel cell systems, the cost of

  11. levelized costs

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    levelized costs - Sandia Energy Energy Search Icon Sandia Home Locations Contact Us Employee Locator Energy & Climate Secure & Sustainable Energy Future Stationary Power Energy Conversion Efficiency Solar Energy Wind Energy Water Power Supercritical CO2 Geothermal Natural Gas Safety, Security & Resilience of the Energy Infrastructure Energy Storage Nuclear Power & Engineering Grid Modernization Battery Testing Nuclear Energy Defense Waste Management Programs Advanced Nuclear

  12. Cost Contributors to Geothermal Power Production

    SciTech Connect (OSTI)

    Nathwani, Jay; Mines, Greg

    2011-07-01

    The US Department of Energy Geothermal Technologies Office (DOE-GTO) has developed the tool Geothermal Electricity Technologies Evaluation Model (GETEM) to assess the levelized cost of electricity (LCOE) of power produced from geothermal resources. Recently modifications to GETEM allow the DOE-GTO to better assess how different factors impact the generation costs, including initial project risk, time required to complete a development, and development size. The model characterizes the costs associated with project risk by including the costs to evaluate and drill those sites that are considered but not developed for commercial power generation, as well as to assign higher costs to finance those activities having more risk. This paper discusses how the important parameters impact the magnitude project costs for different project scenarios. The cost distributions presented include capital cost recovery for the exploration, confirmation, well field completion and power plant construction, as well as the operation and maintenance (O&M) costs. The paper will present these cost distributions for both EGS and hydrothermal resources.

  13. 2011 Cost of Wind Energy Review

    SciTech Connect (OSTI)

    Tegen, S.; Lantz, E.; Hand, M.; Maples, B.; Smith, A.; Schwabe, P.

    2013-03-01

    This report describes the levelized cost of energy (LCOE) for a typical land-based wind turbine installed in the United States in 2011, as well as the modeled LCOE for a fixed-bottom offshore wind turbine installed in the United States in 2011. Each of the four major components of the LCOE equation are explained in detail, such as installed capital cost, annual energy production, annual operating expenses, and financing, and including sensitivity ranges that show how each component can affect LCOE. These LCOE calculations are used for planning and other purposes by the U.S. Department of Energy's Wind Program.

  14. Los Alamos National Laboratory Human and Intellectual Capital for Sustaining Nuclear Deterrence

    SciTech Connect (OSTI)

    McAlpine, Bradley

    2015-04-01

    This paper provides an overview of the current human and intellectual capital at Los Alamos National Laboratory, through specific research into the statistics and demographics as well as numerous personal interviews at all levels of personnel. Based on this information, a series of recommendations are provided to assist Los Alamos National Laboratory in ensuring the future of the human and intellectual capital for the nuclear deterrence mission. While the current human and intellectual capital is strong it stands on the precipice and action must be taken to ensure Los Alamos National Laboratory maintains leadership in developing and sustaining national nuclear capabilities. These recommendations may be applicable to other areas of the nuclear enterprise, including the Air Force, after further research and study.

  15. Least cost options for life extension

    SciTech Connect (OSTI)

    Davis, F.; Bradaric, M.

    1995-12-01

    Rehabilitation of existing electric generating capacity offers one of the most cost-effective ways of meeting near-term power needs in many Eastern and Central European countries. In particular, the uncertainty associated with other supply sources and severe capital constraints tends to favor investments which maximize the utilization of existing fossil-fired equipment. However, it is critical that least-cost planning principles, including the consideration of environmental impacts, be applied to the economic analysis of rehabilitation options. This paper draws on Bechtel`s experience in applying least-cost planning to plant rehabilitation studies in Bulgaria, Romania and Slovakia. The examples provided illustrate the importance of least-cost planning and the effect of the value placed on environmental emissions.

  16. CE2 Carbon Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Carbon Capital LLC Jump to: navigation, search Name: CE2 Carbon Capital LLC Place: California Sector: Carbon, Renewable Energy Product: US-based carbon trader that looks to take...

  17. Capital Asset Project List_rev1.xls

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... by DOE Order 413.3B, Program and Project Management for the Acquisition of Capital Assets. ... Start of Operations or Project Completion Capital Asset Project List 1152016 1 of 1

  18. FreshTracks Capital LP | Open Energy Information

    Open Energy Info (EERE)

    FreshTracks Capital LP Jump to: navigation, search Name: FreshTracks Capital LP Address: 29 Harbor Road, Suite 200 Place: Shelburne, New Hampshire Zip: 05482 Product: Venture...

  19. NewWorld Capital Group LLC | Open Energy Information

    Open Energy Info (EERE)

    NewWorld Capital Group LLC Jump to: navigation, search Name: NewWorld Capital Group LLC Place: New York, New York Zip: 10022 Sector: Efficiency Product: New York-based private...

  20. BioLogical Capital BLC | Open Energy Information

    Open Energy Info (EERE)

    BioLogical Capital BLC Jump to: navigation, search Name: BioLogical Capital (BLC) Place: Denver, Colorado Zip: 80202 Product: Denver Colorado-based group focusing on generating...

  1. CO2e Capital Limited | Open Energy Information

    Open Energy Info (EERE)

    e Capital Limited Jump to: navigation, search Name: CO2e Capital Limited Place: New York City, New York Zip: 10022 Product: New York based merchant bank focused on reducing global...

  2. Morgan Stanley Capital Grp Inc | Open Energy Information

    Open Energy Info (EERE)

    Capital Grp Inc Jump to: navigation, search Name: Morgan Stanley Capital Grp Inc Place: New York References: EIA Form EIA-861 Final Data File for 2010 - File1a1 EIA Form 861...

  3. Office of Executive Resources Office of the Chief Human Capital...

    Broader source: Energy.gov (indexed) [DOE]

    Office of Executive Resources Office of the Chief Human Capital Officer U.S. Department of ... The request must be submitted to the Office of the Chief Human Capital Officer, Office of ...

  4. Office of Executive Resources Office of the Chief Human Capital...

    Broader source: Energy.gov (indexed) [DOE]

    Office of Executive Resources Office of the Chief Human Capital Officer U.S. Department of ... Chief Human Capital Officer (CHCO) and Office of Executive Resources (OER). (1) Develop ...

  5. Energy prices and capital obsolescence: evidence from the oil embargo period

    SciTech Connect (OSTI)

    Gibbons, J.C.

    1984-01-01

    Energy costs replaced maintenance costs on existing fixed assets as a determinant of optimal retirement age after the 1973-74 oil embargo. The economic aging of manufacturing facilities was the product of both normal wear-and-tear and design obsolescence. The adjustment, however, was toward substitution of other factors for capital services and replacement of outmoded asset types by other more expensive ones. The author examines data derived from a dynamic regression model showing that between 8 and 10% of an aggregate plant of the US became obsolete as a result of the embargo. 9 references, 1 figure, 3 tables.

  6. EA-184 Morgan Stanley Capital Group Inc. | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Morgan Stanley Capital Group Inc. EA-184 Morgan Stanley Capital Group Inc. Order authorizing Morgan Stanley Capital Group Inc. to export electric energy to Mexico. EA-184 Morgan Stanley Capital Group Inc. (25.77 KB) More Documents & Publications EA-167 PG&E Energy Trading-Power, L.P EA-166 Duke Energy Trading and Marketing, L.L.C EA-181 H.Q Energy Services (U.S) Inc

  7. Program and Project Management for the Acquisition of Capital Assets |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy Program and Project Management for the Acquisition of Capital Assets Program and Project Management for the Acquisition of Capital Assets This Order provides project management direction for the acquisition of capital assets that are delivered on schedule, within budget, and capable of meeting mission performance and environmental safety and health standards. Program and Project Management for the Acquisition of Capital Assets More Documents & Publications Guiding

  8. Guide to IT Capital Planning and Investment Control

    Energy Savers [EERE]

    Guide to IT Capital Planning and Investment Control April 2014 i TABLE OF CONTENTS TABLE OF CONTENTS ......

  9. Estimating Specialty Costs

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    Specialty costs are those nonstandard, unusual costs that are not typically estimated. Costs for research and development (R&D) projects involving new technologies, costs associated with future regulations, and specialty equipment costs are examples of specialty costs. This chapter discusses those factors that are significant contributors to project specialty costs and methods of estimating costs for specialty projects.

  10. Cost Study Manual

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    2 Cost Study Manual Executive Summary This Cost Study Manual documents the procedures for preparing a Cost Study to compare the cost of a contractor's employee benefits to the industry average from a broad-based national benefit cost survey. The annual Employee Benefits Cost Study Comparison (Cost Study) assists with the analysis of contractors' employee benefits costs. The Contracting Officer (CO) may require corrective action when the average benefit per capita cost or the benefit cost as a

  11. Advanced Fuel Cycle Cost Basis

    SciTech Connect (OSTI)

    D. E. Shropshire; K. A. Williams; W. B. Boore; J. D. Smith; B. W. Dixon; M. Dunzik-Gougar; R. D. Adams; D. Gombert; E. Schneider

    2008-03-01

    This report, commissioned by the U.S. Department of Energy (DOE), provides a comprehensive set of cost data supporting a cost analysis for the relative economic comparison of options for use in the Advanced Fuel Cycle Initiative (AFCI) Program. The report describes the AFCI cost basis development process, reference information on AFCI cost modules, a procedure for estimating fuel cycle costs, economic evaluation guidelines, and a discussion on the integration of cost data into economic computer models. This report contains reference cost data for 25 cost modules—23 fuel cycle cost modules and 2 reactor modules. The cost modules were developed in the areas of natural uranium mining and milling, conversion, enrichment, depleted uranium disposition, fuel fabrication, interim spent fuel storage, reprocessing, waste conditioning, spent nuclear fuel (SNF) packaging, long-term monitored retrievable storage, near surface disposal of low-level waste (LLW), geologic repository and other disposal concepts, and transportation processes for nuclear fuel, LLW, SNF, transuranic, and high-level waste.

  12. Advanced Fuel Cycle Cost Basis

    SciTech Connect (OSTI)

    D. E. Shropshire; K. A. Williams; W. B. Boore; J. D. Smith; B. W. Dixon; M. Dunzik-Gougar; R. D. Adams; D. Gombert; E. Schneider

    2009-12-01

    This report, commissioned by the U.S. Department of Energy (DOE), provides a comprehensive set of cost data supporting a cost analysis for the relative economic comparison of options for use in the Advanced Fuel Cycle Initiative (AFCI) Program. The report describes the AFCI cost basis development process, reference information on AFCI cost modules, a procedure for estimating fuel cycle costs, economic evaluation guidelines, and a discussion on the integration of cost data into economic computer models. This report contains reference cost data for 25 cost modules—23 fuel cycle cost modules and 2 reactor modules. The cost modules were developed in the areas of natural uranium mining and milling, conversion, enrichment, depleted uranium disposition, fuel fabrication, interim spent fuel storage, reprocessing, waste conditioning, spent nuclear fuel (SNF) packaging, long-term monitored retrievable storage, near surface disposal of low-level waste (LLW), geologic repository and other disposal concepts, and transportation processes for nuclear fuel, LLW, SNF, transuranic, and high-level waste.

  13. Advanced Fuel Cycle Cost Basis

    SciTech Connect (OSTI)

    D. E. Shropshire; K. A. Williams; W. B. Boore; J. D. Smith; B. W. Dixon; M. Dunzik-Gougar; R. D. Adams; D. Gombert

    2007-04-01

    This report, commissioned by the U.S. Department of Energy (DOE), provides a comprehensive set of cost data supporting a cost analysis for the relative economic comparison of options for use in the Advanced Fuel Cycle Initiative (AFCI) Program. The report describes the AFCI cost basis development process, reference information on AFCI cost modules, a procedure for estimating fuel cycle costs, economic evaluation guidelines, and a discussion on the integration of cost data into economic computer models. This report contains reference cost data for 26 cost modules—24 fuel cycle cost modules and 2 reactor modules. The cost modules were developed in the areas of natural uranium mining and milling, conversion, enrichment, depleted uranium disposition, fuel fabrication, interim spent fuel storage, reprocessing, waste conditioning, spent nuclear fuel (SNF) packaging, long-term monitored retrievable storage, near surface disposal of low-level waste (LLW), geologic repository and other disposal concepts, and transportation processes for nuclear fuel, LLW, SNF, and high-level waste.

  14. NPR (New Production Reactor) capacity cost evaluation

    SciTech Connect (OSTI)

    1988-07-01

    The ORNL Cost Evaluation Technical Support Group (CETSG) has been assigned by DOE-HQ Defense Programs (DP) the task defining, obtaining, and evaluating the capital and life-cycle costs for each of the technology/proponent/site/revenue possibilities envisioned for the New Production Reactor (NPR). The first part of this exercise is largely one of accounting, since all NPR proponents use different accounting methodologies in preparing their costs. In order to address this problem of comparing ''apples and oranges,'' the proponent-provided costs must be partitioned into a framework suitable for all proponents and concepts. If this is done, major cost categories can then be compared between concepts and major cost differences identified. Since the technologies proposed for the NPR and its needed fuel and target support facilities vary considerably in level of technical and operational maturity, considerable care must be taken to evaluate the proponent-derived costs in an equitable manner. The use of cost-risk analysis along with derivation of single point or deterministic estimates allows one to take into account these very real differences in technical and operational maturity. Chapter 2 summarizes the results of this study in tabular and bar graph form. The remaining chapters discuss each generic reactor type as follows: Chapter 3, LWR concepts (SWR and WNP-1); Chapter 4, HWR concepts; Chapter 5, HTGR concept; and Chapter 6, LMR concept. Each of these chapters could be a stand-alone report. 39 refs., 36 figs., 115 tabs.

  15. Rough order of magnitude cost estimate for immobilization of 18.2 MT of plutonium using existing facilities at the Savannah River site: alternatives 3A/5A/6A/6B/7A/9A

    SciTech Connect (OSTI)

    DiSabatino, A., LLNL

    1998-06-01

    The purpose of this Cost Estimate Report is to identify preliminary capital and operating costs for a facility to immobilize 18.2 metric tons (nominal) of plutonium using ceramic in a new facility at Savannah River Site (SRS).

  16. Cost and Performance Assumptions for Modeling Electricity Generation Technologies

    SciTech Connect (OSTI)

    Tidball, Rick; Bluestein, Joel; Rodriguez, Nick; Knoke, Stu

    2010-11-01

    The goal of this project was to compare and contrast utility scale power plant characteristics used in data sets that support energy market models. Characteristics include both technology cost and technology performance projections to the year 2050. Cost parameters include installed capital costs and operation and maintenance (O&M) costs. Performance parameters include plant size, heat rate, capacity factor or availability factor, and plant lifetime. Conventional, renewable, and emerging electricity generating technologies were considered. Six data sets, each associated with a different model, were selected. Two of the data sets represent modeled results, not direct model inputs. These two data sets include cost and performance improvements that result from increased deployment as well as resulting capacity factors estimated from particular model runs; other data sets represent model input data. For the technologies contained in each data set, the levelized cost of energy (LCOE) was also evaluated, according to published cost, performance, and fuel assumptions.

  17. Evaluation of the Total Cost of Ownership of Fuel Cell-Powered Material Handling Equipment

    SciTech Connect (OSTI)

    Ramsden, T.

    2013-04-01

    This report discusses an analysis of the total cost of ownership of fuel cell-powered and traditional battery-powered material handling equipment (MHE, or more typically 'forklifts'). A number of fuel cell MHE deployments have received funding support from the federal government. Using data from these government co-funded deployments, DOE's National Renewable Energy Laboratory (NREL) has been evaluating the performance of fuel cells in material handling applications. NREL has assessed the total cost of ownership of fuel cell MHE and compared it to the cost of ownership of traditional battery-powered MHE. As part of its cost of ownership assessment, NREL looked at a range of costs associated with MHE operation, including the capital costs of battery and fuel cell systems, the cost of supporting infrastructure, maintenance costs, warehouse space costs, and labor costs. Considering all these costs, NREL found that fuel cell MHE can have a lower overall cost of ownership than comparable battery-powered MHE.

  18. Program and Project Management for the Acquisition of Capital Assets (Informational Purposes Only)

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2016-01-11

    The purpose of this Order is to a) provide the Department of Energy (DOE) Elements, including the National Nuclear Security Administration (NNSA), with program and project management direction for the acquisition of capital assets with the goal of delivering projects within the original performance baseline (PB), cost and schedule, and fully capable of meeting mission performance, safeguards and security, and environmental, safety, and health requirements unless impacted by a directed change; and b) implement Office of Management and Budget (OMB) Circulars to include: A-11, Part 7, Capital Programming Guide, which prescribes new requirements and leading practices for project and acquisition management; A-123, Management's Responsibility for Internal Control, which defines management's responsibility for internal control in Federal agencies; and A-131, Value Engineering, which requires that all Federal agencies use Value Engineering (VE) as a management tool. The Page Change is a limited update to incorporate recent Secretarial policies and issues raised by external stakeholders.

  19. Retrofit costs for lime/limestone FGD and lime spray drying at coal-fired utility boilers

    SciTech Connect (OSTI)

    Emmel, T.E.; Jones, J.W.

    1990-01-01

    The paper gives results of a research program the objective of which was to significantly improve engineering cost estimates currently being used to evaluate the economic effects of applying SO2 controls to existing coal-fired utility boilers. The costs of retrofitting conventional lime/limestone wet flue gas desulfurization (L/LS FGD) and lime spray drying (LSD) FGD at 100-200 coal-fired power plants are being estimated under this program. The retrofit capital cost estimating procedures used for L/LS FGD and LSD FGD make two cost adjustments to current procedures used to estimate FGD costs: cost adders (for items not normally included in FGD system costs; e.g., demolition and relocation of existing facilities) and cost multipliers (to adjust capital costs for site access, congestion, and underground obstructions).

  20. PAFC Cost Challenges

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    PAFC Cost Challenges Sridhar Kanuri Manager, PAFC Technology *Sridhar.Kanuri@utcpower.com 2 AGENDA Purecell® 400 cost challenge Cost reduction opportunities Summary 3 PURECELL ® FUEL CELL SYSTEM First cost 2010 cost reduction is being accomplished by incremental changes in technology & low cost sourcing Technology advances are required to reduce further cost and attain UTC Power's commercialization targets 2010 First unit 2010 Last unit Commercialization target Powerplant cost 4

  1. Analysis of Cycling Costs in Western Wind and Solar Integration Study

    SciTech Connect (OSTI)

    Jordan, G.; Venkataraman, S.

    2012-06-01

    The Western Wind and Solar Integration Study (WWSIS) examined the impact of up to 30% penetration of variable renewable generation on the Western Electricity Coordinating Council system. Although start-up costs and higher operating costs because of part-load operation of thermal generators were included in the analysis, further investigation of additional costs associated with thermal unit cycling was deemed worthwhile. These additional cycling costs can be attributed to increases in capital as well as operations and maintenance costs because of wear and tear associated with increased unit cycling. This analysis examines the additional cycling costs of the thermal fleet by leveraging the results of WWSIS Phase 1 study.

  2. Capital requirements and fuel-cycle energy and emissions impacts of potential PNGV fuels.

    SciTech Connect (OSTI)

    Johnson, L.; Mintz, M.; Singh, M.; Stork, K.; Vyas, A.; Wang, M.

    1999-03-11

    emissions relative to the reference scenario. The table clearly shows the trade-off between costs and benefits. For example, while H{sub 2} FCVs have the greatest incremental capital needs, they offer the largest energy and emissions benefits. On the basis of the cost and benefit changes shown, methanol and gasoline FCVs appear to have particularly promising benefits-to-costs ratios.

  3. Chemical coal cleaning process and costs refinement for coal-water slurry manufacture. Semi-annual progress report

    SciTech Connect (OSTI)

    Bhasin, A.K.; Berggren, M.H.; Smit, F.J.; Ames, L.B.; Ronzio, N.J.

    1985-03-01

    The Department of Energy, through the Morgantown Energy Technology Center (METC), has initiated a program to determine the feasibility and potential applications for direct firing of coal and coal-derived fuels in heat engines, specifically gas turbines and diesel engines. AMAX Extractive Research and Development, Inc. supplied METC with two lots of highly beneficiated coal slurry fuel for use in the Heat Engines programs. One of the lots was of ultra-clean coal-water slurry fuel (UCCSF) for which a two-stage caustic and acid leaching procedure was developed to chemically clean the coal. As a part of the contract, AMAX R and D developed a conceptual design and preliminary cost estimate for a commercial-scale process for UCCSF manufacture. The contract was extended to include the following objectives: define chemical cleaning and slurry preparation process conditions and costs more precisely; investigate methods to reduce the product cost; and determine the relationship, in dollars per million Btu, between product cost and fuel quality. Laboratory investigations have been carried out to define the chemical cleaning process conditions required to generate fuels containing from 0.17 to 1.0% ash. Capital and operating cost refinements are to be performed on the basis of the preferred process operating conditions identified during the laboratory investigations. Several such areas for cost reductions have been identified. Caustic strengths from 2 to 7% NaOH are currently anticipated while 25% NaOH was used as the basis for the preliminary cost estimate. In addition, leaching times for each of the process steps have been reduced to half or less of the times used for the preliminary cost estimate. Improvement of fuel quality has been achieved by use of a proprietary hot-water leaching step to reduce the residual alkali content to less than 250 ppM (Na/sub 2/O plus K/sub 2/O) on a dry coal basis. 2 refs., 3 figs., 24 tabs.

  4. Cost and Performance Model for Redox Flow Batteries

    SciTech Connect (OSTI)

    Viswanathan, Vilayanur V.; Crawford, Aladsair J.; Stephenson, David E.; Kim, Soowhan; Wang, Wei; Li, Bin; Coffey, Greg W.; Thomsen, Edwin C.; Graff, Gordon L.; Balducci, Patrick J.; Kintner-Meyer, Michael CW; Sprenkle, Vincent L.

    2014-02-01

    A cost model was developed for all vanadium and iron-vanadium redox flow batteries. Electrochemical performance modeling was done to estimate stack performance at various power densities as a function of state of charge. This was supplemented with a shunt current model and a pumping loss model to estimate actual system efficiency. The operating parameters such as power density, flow rates and design parameters such as electrode aspect ratio, electrolyte flow channel dimensions were adjusted to maximize efficiency and minimize capital costs. Detailed cost estimates were obtained from various vendors to calculate cost estimates for present, realistic and optimistic scenarios. The main drivers for cost reduction for various chemistries were identified as a function of the energy to power ratio of the storage system. Levelized cost analysis further guided suitability of various chemistries for different applications.

  5. Office of the Chief Human Capital Officer | Department of Energy

    Broader source: All U.S. Department of Energy (DOE) Office Webpages

    Human Capital Officer Search Search form Search Office of the Chief Human Capital Officer Office of the Chief Human Capital Officer Services Services Home Benefits Benefits Home DOE Workers' Compensation Program Insurance Military/Reservist Retirement Telework Thrift Savings Plan (TSP) Wellness Programs Executive Resources Learning and Workforce Development New Employee Orientation Policy and Guidance Policy and Guidance Home Compensation Employment/Staffing Employment/Staffing Home Recruitment

  6. Capitalizing on Multibenefits of Energy Upgrades at Multifamily Housing

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    (301) | Department of Energy Capitalizing on Multibenefits of Energy Upgrades at Multifamily Housing (301) Capitalizing on Multibenefits of Energy Upgrades at Multifamily Housing (301) Buildings Residential Network Peer Exchange Call Series: Capitalizing on Multibenefits of Energy Upgrades at Multifamily Housing (301), call slides and discussion summary. Call Slides and Discussion Summary (3.36 MB) More Documents & Publications Staged Upgrades as a Strategy for Residential Energy

  7. Utilization of UV Curing Technology to Significantly Reduce the Manufacturing Cost of LIB Electrodes

    SciTech Connect (OSTI)

    Voelker, Gary; Arnold, John

    2015-11-30

    Previously identified novel binders and associated UV curing technology have been shown to reduce the time required to apply and finish electrode coatings from tens of minutes to less than one second. This revolutionary approach can result in dramatic increases in process speeds, significantly reduced capital (a factor of 10 to 20) and operating costs, reduced energy requirements, and reduced environmental concerns and costs due to the virtual elimination of harmful volatile organic solvents and associated solvent dryers and recovery systems. The accumulated advantages of higher speed, lower capital and operating costs, reduced footprint, lack of VOC recovery, and reduced energy cost is a reduction of 90% in the manufacturing cost of cathodes. When commercialized, the resulting cost reduction in Lithium batteries will allow storage device manufacturers to expand their sales in the market and thereby accrue the energy savings of broader utilization of HEVs, PHEVs and EVs in the U.S., and a broad technology export market is also envisioned.

  8. Natural Capital Management: An Evolutionary Paradigm for Sustainable Restoration Investment - 13455

    SciTech Connect (OSTI)

    Koetz, Maureen T.

    2013-07-01

    Unlike other forms of capital assets (built infrastructure, labor, financial capital), the supply of usable or accessible air, land, and water elements (termed Natural Capital Assets or NCA) available to enterprise processes is structurally shrinking due to increased demand and regulatory restriction. This supply/demand imbalance is affecting all forms of public and private enterprise (including Federal Facilities) in the form of encroachment, production limits, cost increases, and reduced competitiveness. Department of Energy (DOE) sites are comprised of significant stocks of NCA that function as both conserved capital (providing ecosystem services and other reserve capacity), and as natural infrastructure (supporting major Federal enterprise programs). The current rubric of 'Environmental Stewardship' provides an unduly constrained management paradigm that is focused largely on compliance process metrics, and lacks a value platform for quantifying, documenting, and sustainably re-deploying re-capitalized natural asset capacity and capability. By adopting value-based system concepts similar to built infrastructure accounting and information management, 'stewarded' natural assets relegated to liability- or compliance-focused outcomes become 're-capitalized' operational assets able to support new or expanded mission. This growing need for new accounting and management paradigms to capture natural capital value is achieving global recognition, most recently by the United Nations, world leaders, and international corporations at the Rio+20 Summit in June of 2012. Natural Capital Asset Management (NCAM){sup TM} is such an accounting framework tool. Using a quantification-based design, NCAM{sup TM} provides inventory, capacity and value data to owners or managers of natural assets such as the DOE that parallel comparable information systems currently used for facility assets. Applied to Environmental Management (EM) and other DOE program activities, the natural asset

  9. Cost reduction ideas for LNG terminals

    SciTech Connect (OSTI)

    Habibullah, A.; Weldin, F.

    1999-07-01

    LNG projects are highly capital intensive and this has long been regarded as being inevitable. However, recent developments are forcing the LNG industry to aggressively seek cost reductions. For example, the gas-to-liquids (GTL) process is increasingly seen as a potential rival technology and is often being touted as an economically superior alternative fuel source. Another strong driving force behind needed cost reductions is the low crude oil price which seems to have settled in the $10--13/bb. range. LNG is well positioned as the fuel of choice for environmentally friendly new power projects. As a result of the projected demand for power especially in the Pacific Rim countries several LNG terminal projects are under consideration. Such projects will require a new generation of LNG terminal designs emphasizing low cost, small scale and safe and fully integrated designs from LNG supply to power generation. The integration of the LNG terminal with the combined cycle gas turbine (CCGT) power plant offers substantial cost savings opportunities for both plants. Various cost reduction strategies and their impact on the terminal design are discussed including cost reduction due to integration.

  10. Mexico-Capital Markets Climate Initiative | Open Energy Information

    Open Energy Info (EERE)

    Low emission development planning, -LEDS Website http:www.decc.gov.ukencont Country Mexico Central America References CMCI1 World Economic Forum2 The Capital Markets...

  11. Program & Project Management For The Acquisition Of Capital Assets...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Program & Project Management For The Acquisition Of Capital Assets (310.65 KB) More Documents & Publications "Paper" Energy Systems Acquisition Advisory Board Process ESAAB ...

  12. Webinar Announcement: Accessing Private Capital for Clean Energy...

    Open Energy Info (EERE)

    Webinar Announcement: Accessing Private Capital for Clean Energy Investments in Developing Countries (Webinar) Home > Groups > OpenEI Community Central Graham7781's picture...

  13. Delegation of Acquisition Executive Authority for Capital Asset...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Idaho Cleanup Project by cooper DelegationAcquisitionExecAuthorityCapitalAssetProjectsIDCleanupProject-CooperEM.pdf -- PDF Document, 256 KB ID: NA Type: Organizations' Assignment...

  14. Global Capital Finance Americas LLC | Open Energy Information

    Open Energy Info (EERE)

    Finance Americas LLC Jump to: navigation, search Name: Global Capital Finance Americas LLC Place: Purchase, New York Zip: 10577 Sector: Renewable Energy, Services Product: An...

  15. Financing U.S. Renewable Energy Projects Through Public Capital...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Financing U.S. Renewable Energy Projects Through Public Capital Vehicles: Qualitative and ... Energy, Office of Energy Efficiency & Renewable Energy, operated by the Alliance for ...

  16. Statement on Department of Energy's Major System Capital Asset...

    National Nuclear Security Administration (NNSA)

    Department of Energy's Major System Capital Asset Projects before the House Committee on Appropriations Subcommittee on Energy & Water Development March 20, 2013 INTRODUCTION ...

  17. Energy Department and GSA Assist in Capital Solar Challenge Industry...

    Office of Environmental Management (EM)

    General Services Administration (GSA) are charged with assisting agencies in leading the Capital Solar Challenge with the goal of developing solar renewable power on Federal sites. ...

  18. Human Capital: The Role of Ombudsmen in Dispute Resolution

    Broader source: Energy.gov (indexed) [DOE]

    United States General Accounting Office GAO April 2001 HUMAN CAPITAL The Role of Ombudsmen ... Accounting Office GS General Schedule HR human resource IBB International Broadcasting ...

  19. Human Capital Policy Division (HC-11) | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    Provide a full range of staff support to the Chief Human Capital Officer including support required for internal and external responsibilities. Develop and revise the agency human ...

  20. CRADA final report: Technical assessment of roll-to-roll operation of lamination process, thermal treatment, and alternative carbon fiber precursors for low-cost, high-efficiency manufacturing of flow battery stacks and other energy devices

    SciTech Connect (OSTI)

    Daniel, Claus; Madden, Thomas; Wood, III, David L; Muth, Thomas R.; Warrington, Curtis; Ozcan, Soydan; Manson, Hunter; Tekinalp, Halil L.; Smith, Mark A.; Lu, Yuan; Loretz, Jeremy

    2015-09-23

    Among the various stationary-storage technologies under development, redox flow batteries (RFBs) offer the greatest potential to deliver inexpensive, scalable, and efficient grid-scale electrical-energy storage. Unlike traditional sealed batteries, in a flow battery power and energy are decoupled. Cell area and cell count in the stack determine the device power, and the chemical storage volume determines the total energy. Grid-scale energy-storage applications require megawatt-scale devices, which require the assembly of hundreds of large-area, bipolar cells per power plant. The cell-stack is the single system component with the largest impact on capital cost (due to the large number of highly engineered components) and operating costs (determined by overall round-trip efficiency).

  1. Project Profile: Concurrent Optimization of Component Capital...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    solar power (CSP) plants by characterizing and forecasting operations and maintenance costs, component failure behavior, and the impact of design and maintenance policies. ...

  2. Cost Model and Cost Estimating Software

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    This chapter discusses a formalized methodology is basically a cost model, which forms the basis for estimating software.

  3. Capital intensity of photovoltaics manufacturing: Barrier to scale and opportunity for innovation

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Powell, Douglas M.; Fu, Ran; Horowitz, Kelsey; Basore, Paul A.; Woodhouse, Michael; Buonassisi, Tonio

    2015-09-07

    In this study, using a bottom-up cost model, we assess the impact of initial factory capital expenditure (capex) on photovoltaic (PV) module minimum sustainable price (MSP) and industry-wide trends. We find capex to have two important impacts on PV manufacturing. First, capex strongly influences the per-unit MSP of a c-Si module: we calculate that the capex-related elements sum to 22% of MSP for an integrated wafer, cell, and module manufacturer. This fraction provides a significant opportunity to reduce MSP toward the U.S. DOE SunShot module price target through capex innovation.

  4. Activity Based Costing

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    Activity Based Costing (ABC) is method for developing cost estimates in which the project is subdivided into discrete, quantifiable activities or a work unit. This chapter outlines the Activity Based Costing method and discusses applicable uses of ABC.

  5. Module process optimization and device efficiency improvement for stable, low-cost, large-area, cadmium telluride-based photovoltaic module production. Annual subcontract report, 1 July 1990--31 December 1991

    SciTech Connect (OSTI)

    Albright, S.P.; Ackerman, B.; Chamberlin, R.R.; Jordan, J.F.

    1992-04-01

    This report describes work under a three-year phased subcontract to develop CdS/CdTe devices and modules and to further improve the technology base at Photon Energy, Inc. (PEI) to better address the commercialization issues and objectives of the PEI and the US Department of Energy. During this reporting period we (1) achieved efficiencies of 12.7% on small area devices, (2) achieved 1-ft{sup 2} modules with over 8% aperture-area efficiency (and active area efficiencies up to {approximately}10%), (3) tested 4-ft{sup 2} modules at NREL at 23.1 (21.3) watts, normalized (6.3% efficiency), and (4) found no inherent stability problems with CdTe technology during life testing, at both NREL and PEI. 7 refs.

  6. Land-Based Wind Plant Balance-of-System Cost Drivers and Sensitivities (Poster)

    SciTech Connect (OSTI)

    Mone, C.; Maples, B.; Hand, M.

    2014-04-01

    With Balance of System (BOS) costs contributing up to 30% of the installed capital cost, it is fundamental to understand the BOS costs for wind projects as well as potential cost trends for larger turbines. NREL developed a BOS model using project cost estimates developed by industry partners. Aspects of BOS covered include engineering and permitting, foundations for various wind turbines, transportation, civil work, and electrical arrays. The data introduce new scaling relationships for each BOS component to estimate cost as a function of turbine parameters and size, project parameters and size, and geographic characteristics. Based on the new BOS model, an analysis to understand the non‐turbine wind plant costs associated with turbine sizes ranging from 1-6 MW and wind plant sizes ranging from 100-1000 MW has been conducted. This analysis establishes a more robust baseline cost estimate, identifies the largest cost components of wind project BOS, and explores the sensitivity of the capital investment cost and the levelized cost of energy to permutations in each BOS cost element. This presentation shows results from the model that illustrate the potential impact of turbine size and project size on the cost of energy from US wind plants.

  7. Next Generation Safeguards Initiative Efforts at Los Alamos National Laboratory: Developing Our Human Capital FY2015

    SciTech Connect (OSTI)

    Stevens, Rebecca S.; Hawkins Erpenbeck, Heather

    2015-10-13

    This report documents the accomplishments of the Safeguards HCD Fiscal Year 2015 (FY15) Project Work Plan, highlighting LANL’s work as well as the accomplishments of our NGSI-sponsored students, graduate and postdoctoral fellows, and mid-career professionals during this past year. While fiscal year 2015 has been a year of transition in the Human Capital Development area for LANL, we are working to revitalize our efforts to promote and develop Human Capital in Safeguards and Non-proliferation and are looking forward to implementing new initiatives in the coming fiscal year and continuing to transition the knowledge of staff who have been on assignment at IAEA and Headquarters to improve our support to HCD.

  8. Cellulosic Ethanol Cost Target

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Plenary Talk May 21, 2013 Cellulosic Ethanol Cost Target 2 | Biomass Program ... "Our goal is to make cellulosic ethanol practical and cost competitive within 6 ...

  9. DOE Guide to IT Capital Planning and Investment Control BY 2016...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Guide to IT Capital Planning and Investment Control BY 2016 DOE Guide to IT Capital Planning and Investment Control BY 2016 DOE Guide to IT Capital Planning and Investment Control...

  10. EA-184-A Morgan Stanley Capital Group Inc. | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    4-A Morgan Stanley Capital Group Inc. EA-184-A Morgan Stanley Capital Group Inc. Order authorizing Morgan Stanley Capital Group Inc. to export electric energy to Mexico. EA-184-A ...

  11. EA-185-D Morgan Stanley Capital Group Inc. | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    D Morgan Stanley Capital Group Inc. EA-185-D Morgan Stanley Capital Group Inc. Order authorizing MSCG to export electric energy to Canada. EA-185-D Morgan Stanley Capital Group.pdf ...

  12. EA-185-C Morgan Stanley Capital Group Inc. | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    C Morgan Stanley Capital Group Inc. EA-185-C Morgan Stanley Capital Group Inc. Order authorizing Morgan Stanley Capital Group Inc. to export electric energy to Canada. EA-185-C ...

  13. EA-185-A Morgan Stanley Capital Group Inc. | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    -A Morgan Stanley Capital Group Inc. EA-185-A Morgan Stanley Capital Group Inc. Order authorizing Morgan Stanley Capital Group Inc. to export electric energy to Canada. EA-185-A ...

  14. EA-260 EPCOR Merchant and Capital (US) Inc | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    EPCOR Merchant and Capital (US) Inc EA-260 EPCOR Merchant and Capital (US) Inc Order authorizing EPCOR Merchant and Capital (US) Inc to export electric energy to Canada. EA-260 ...

  15. EA-185-B Morgan Stanley Capital Group Inc. | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    B Morgan Stanley Capital Group Inc. EA-185-B Morgan Stanley Capital Group Inc. Order authorizing Morgan Stanley Capital Group Inc. to export electric energy to Canada. EA-185-B ...

  16. EA-260-A EPCOR Merchant and Capital (US) Inc | Department of...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    -A EPCOR Merchant and Capital (US) Inc EA-260-A EPCOR Merchant and Capital (US) Inc Order authorizing EPCOR Merchant and Capital (US) Inc to export electric energy to Canada. ...

  17. EA-260-C EPCOR Merchant and Capital (US) Inc | Department of...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    60-C EPCOR Merchant and Capital (US) Inc EA-260-C EPCOR Merchant and Capital (US) Inc Order authorizing EPCOR Merchant and Capital (US) Inc to export electric energy to Canada. ...

  18. Integration of Variable Generation and Cost-Causation (Fact Sheet)

    SciTech Connect (OSTI)

    Not Available

    2012-09-01

    Variable renewable energy generation sources, such as wind and solar energy, provide benefits such as reduced environmental impact, zero fuel consumption, and low and stable costs. Advances in both technologies can reduce capital costs and provide significant control capabilities. However, their variability and uncertainty - which change with weather conditions, time of day, and season - can cause an increase in power system operating costs compared to a fully controllable power plant. Although a number of studies have assessed integration costs, calculating them correctly is challenging because it is difficult to accurately develop a baseline scenario without variable generation that properly accounts for the energy value. It is also difficult to appropriately allocate costs given the complex, nonlinear interactions between resources and loads.

  19. Cost estimate for muddy water palladium production facility at Mound

    SciTech Connect (OSTI)

    McAdams, R.K.

    1988-11-30

    An economic feasibility study was performed on the ''Muddy Water'' low-chlorine content palladium powder production process developed by Mound. The total capital investment and total operating costs (dollars per gram) were determined for production batch sizes of 1--10 kg in 1-kg increments. The report includes a brief description of the Muddy Water process, the process flow diagram, and material balances for the various production batch sizes. Two types of facilities were evaluated--one for production of new, ''virgin'' palladium powder, and one for recycling existing material. The total capital investment for virgin facilities ranged from $600,000 --$1.3 million for production batch sizes of 1--10 kg, respectively. The range for recycle facilities was $1--$2.3 million. The total operating cost for 100% acceptable powder production in the virgin facilities ranged from $23 per gram for a 1-kg production batch size to $8 per gram for a 10-kg batch size. Similarly for recycle facilities, the total operating cost ranged from $34 per gram to $5 per gram. The total operating cost versus product acceptability (ranging from 50%--100% acceptability) was also evaluated for both virgin and recycle facilities. Because production sizes studied vary widely and because scale-up factors are unknown for batch sizes greater than 1 kg, all costs are ''order-of-magnitude'' estimates. All costs reported are in 1987 dollars.

  20. US nuclear power plant operating cost and experience summaries

    SciTech Connect (OSTI)

    Kohn, W.E.; Reid, R.L.; White, V.S.

    1998-02-01

    NUREG/CR-6577, U.S. Nuclear Power Plant Operating Cost and Experience Summaries, has been prepared to provide historical operating cost and experience information on U.S. commercial nuclear power plants. Cost incurred after initial construction are characterized as annual production costs, representing fuel and plant operating and maintenance expenses, and capital expenditures related to facility additions/modifications which are included in the plant capital asset base. As discussed in the report, annual data for these two cost categories were obtained from publicly available reports and must be accepted as having different degrees of accuracy and completeness. Treatment of inconclusive and incomplete data is discussed. As an aid to understanding the fluctuations in the cost histories, operating summaries for each nuclear unit are provided. The intent of these summaries is to identify important operating events; refueling, major maintenance, and other significant outages; operating milestones; and significant licensing or enforcement actions. Information used in the summaries is condensed from annual operating reports submitted by the licensees, plant histories contained in Nuclear Power Experience, trade press articles, and the Nuclear Regulatory Commission (NRC) web site (www.nrc.gov).

  1. U.S. Department of Energy Selects Venture Capital Firms to Accelerate...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Venture Capital Firms to Accelerate Adoption of Advanced Energy Technologies U.S. Department of Energy Selects Venture Capital Firms to Accelerate Adoption of Advanced Energy ...

  2. MicroPlanet Technology Corp formerly HF Capital Corp | Open Energy...

    Open Energy Info (EERE)

    Technology Corp formerly HF Capital Corp Jump to: navigation, search Name: MicroPlanet Technology Corp (formerly HF Capital Corp) Place: Seattle, Washington Zip: 98104 Sector:...

  3. Microsoft Word - DOE Human Capital Strategic Plan 2011-2015.docx

    Broader source: Energy.gov (indexed) [DOE]

    DOE HUMAN CAPITAL STRATEGIC PLAN FY 2011 - FY 2015 DOE HUMAN CAPITAL STRATEGIC PLAN FY 2011 - FY 2015 TABLE OF CONTENTS EXECUTIVE SUMMARY ......

  4. Survey of LWR environmental control technology performance and cost

    SciTech Connect (OSTI)

    Heeb, C.M.; Aaberg, R.L.; Cole, B.M.; Engel, R.L.; Kennedy, W.E. Jr.; Lewallen, M.A.

    1980-03-01

    This study attempts to establish a ranking for species that are routinely released to the environment for a projected nuclear power growth scenario. Unlike comparisons made to existing standards, which are subject to frequent revision, the ranking of releases can be used to form a more logical basis for identifying the areas where further development of control technology could be required. This report describes projections of releases for several fuel cycle scenarios, identifies areas where alternative control technologies may be implemented, and discusses the available alternative control technologies. The release factors were used in a computer code system called ENFORM, which calculates the annual release of any species from any part of the LWR nuclear fuel cycle given a projection of installed nuclear generation capacity. This survey of fuel cycle releases was performed for three reprocessing scenarios (stowaway, reprocessing without recycle of Pu and reprocessing with full recycle of U and Pu) for a 100-year period beginning in 1977. The radioactivity releases were ranked on the basis of a relative ranking factor. The relative ranking factor is based on the 100-year summation of the 50-year population dose commitment from an annual release of radioactive effluents. The nonradioactive releases were ranked on the basis of dilution factor. The twenty highest ranking radioactive releases were identified and each of these was analyzed in terms of the basis for calculating the release and a description of the currently employed control method. Alternative control technology is then discussed, along with the available capital and operating cost figures for alternative control methods.

  5. Geothermal Heat Pumps as a Cost Saving and Capital Renewal Too!

    SciTech Connect (OSTI)

    Hughes, P.J.

    1998-11-06

    An independent evaluation of the Fort Polk, Louisiana energy savings performance contract (ESPC) has verified the financial value of geothermal heat pump (GHP)-centered ESPCS to the federal government. The Department of Energy (DOE) Federal Energy Management Program (FEMP) has responded by issuing an RFP for the "National GHP-Technology-Specific Super ESPC Procurement." Federal agency sites anywhere in the nation will be able to implement GHP-centered ESPC projects as delivery orders against the awarded contracts.

  6. Wind Turbine Control Design to Reduce Capital Costs: 7 January 2009 - 31 August 2009

    SciTech Connect (OSTI)

    Darrow, P. J.

    2010-01-01

    This report first discusses and identifies which wind turbine components can benefit from advanced control algorithms and also presents results from a preliminary loads case analysis using a baseline controller. Next, it describes the design, implementation, and simulation-based testing of an advanced controller to reduce loads on those components. The case-by-case loads analysis and advanced controller design will help guide future control research.

  7. Life Cycle Cost Estimate

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    Life-cycle costs (LCCs) are all the anticipated costs associated with a project or program alternative throughout its life. This includes costs from pre-operations through operations or to the end of the alternative.This chapter discusses life cycle costs and the role they play in planning.

  8. Cost Estimation Package

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    This chapter focuses on the components (or elements) of the cost estimation package and their documentation.

  9. A chronicle of costs

    SciTech Connect (OSTI)

    Elioff, T.

    1994-04-01

    This report contains the history of all estimated costs associated with the superconducting super collider.

  10. Research Areas

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Research Areas Our Vision National User Facilities Research Areas In Focus Global Solutions ⇒ Navigate Section Our Vision National User Facilities Research Areas In Focus Global Solutions Biosciences The Biosciences Area forges multidisciplinary teams to solve national challenges in energy, environment and health issues; and to advance the engineering of biological systems for sustainable manufacturing. Biosciences Area research is coordinated through three divisions and is enabled by Berkeley

  11. Life-cycle cost comparisons of advanced storage batteries and fuel cells for utility, stand-alone, and electric vehicle applications

    SciTech Connect (OSTI)

    Humphreys, K.K.; Brown, D.R.

    1990-01-01

    This report presents a comparison of battery and fuel cell economics for ten different technologies. To develop an equitable economic comparison, the technologies were evaluated on a life-cycle cost (LCC) basis. The LCC comparison involved normalizing source estimates to a standard set of assumptions and preparing a lifetime cost scenario for each technology, including the initial capital cost, replacement costs, operating and maintenance (O M) costs, auxiliary energy costs, costs due to system inefficiencies, the cost of energy stored, and salvage costs or credits. By considering all the costs associated with each technology over its respective lifetime, the technology that is most economical to operate over any given period of time can be determined. An analysis of this type indicates whether paying a high initial capital cost for a technology with low O M costs is more or less economical on a lifetime basis than purchasing a technology with a low initial capital cost and high O M costs. It is important to realize that while minimizing cost is important, the customer will not always purchase the least expensive technology. The customer may identify benefits associated with a more expensive option that make it the more attractive over all (e.g., reduced construction lead times, modularity, environmental benefits, spinning reserve, etc.). The LCC estimates presented in this report represent three end-use applications: utility load-leveling, stand-alone power systems, and electric vehicles.

  12. Estimating Well Costs for Enhanced Geothermal System Applications

    SciTech Connect (OSTI)

    K. K. Bloomfield; P. T. Laney

    2005-08-01

    The objective of the work reported was to investigate the costs of drilling and completing wells and to relate those costs to the economic viability of enhanced geothermal systems (EGS). This is part of a larger parametric study of major cost components in an EGS. The possibility of improving the economics of EGS can be determined by analyzing the major cost components of the system, which include well drilling and completion. Determining what costs in developing an EGS are most sensitive will determine the areas of research to reduce those costs. The results of the well cost analysis will help determine the cost of a well for EGS development.

  13. Hydrogen Threshold Cost Calculation

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Program Record (Offices of Fuel Cell Technologies) Record #: 11007 Date: March 25, 2011 Title: Hydrogen Threshold Cost Calculation Originator: Mark Ruth & Fred Joseck Approved by: Sunita Satyapal Date: March 24, 2011 Description: The hydrogen threshold cost is defined as the hydrogen cost in the range of $2.00-$4.00/gge (2007$) which represents the cost at which hydrogen fuel cell electric vehicles (FCEVs) are projected to become competitive on a cost per mile basis with the competing

  14. OOTW COST TOOLS

    SciTech Connect (OSTI)

    HARTLEY, D.S.III; PACKARD, S.L.

    1998-09-01

    This document reports the results of a study of cost tools to support the analysis of Operations Other Than War (OOTW). It recommends the continued development of the Department of Defense (DoD) Contingency Operational Support Tool (COST) as the basic cost analysis tool for 00TWS. It also recommends modifications to be included in future versions of COST and the development of an 00TW mission planning tool to supply valid input for costing.

  15. Hydrogen Pathway Cost Distributions

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Pathway Cost Distributions Jim Uihlein Fuel Pathways Integration Tech Team January 25, 2006 2 Outline * Pathway-Independent Cost Goal * Cost Distribution Objective * Overview * H2A Influence * Approach * Implementation * Results * Discussion Process * Summary 3 Hydrogen R&D Cost Goal * Goal is pathway independent * Developed through a well defined, transparent process * Consumer fueling costs are equivalent or less on a cents per mile basis * Evolved gasoline ICE and gasoline-electric

  16. Life cycle cost study for coated conductor manufacture by metal organic chemical vapor deposition

    SciTech Connect (OSTI)

    Chapman, J.N.

    1999-07-13

    The purpose of this report is to calculate the cost of producing high temperature superconducting wire by the Metal Organic Chemical Vapor Deposition (MOCVD) process. The technology status is reviewed from the literature and a plant conceptual design is assumed for the cost calculation. The critical issues discussed are the high cost of the metal organic precursors, the material utilization efficiency and the capability of the final product as measured by the critical current density achieved. Capital, operating and material costs are estimated and summed as the basis for calculating the cost per unit length of wire. Sensitivity analyses of key assumptions are examined to determine their effects on the final wire cost. Additionally, the cost of wire on the basis of cost per kiloampere per meter is calculated for operation at lower temperatures than the liquid nitrogen boiling temperature. It is concluded that this process should not be ruled out on the basis of high cost of precursors alone.

  17. Low Cost Hydrogen Production Platform

    SciTech Connect (OSTI)

    Timothy M. Aaron, Jerome T. Jankowiak

    2009-10-16

    A technology and design evaluation was carried out for the development of a turnkey hydrogen production system in the range of 2.4 - 12 kg/h of hydrogen. The design is based on existing SMR technology and existing chemical processes and technologies to meet the design objectives. Consequently, the system design consists of a steam methane reformer, PSA system for hydrogen purification, natural gas compression, steam generation and all components and heat exchangers required for the production of hydrogen. The focus of the program is on packaging, system integration and an overall step change in the cost of capital required for the production of hydrogen at small scale. To assist in this effort, subcontractors were brought in to evaluate the design concepts and to assist in meeting the overall goals of the program. Praxair supplied the overall system and process design and the subcontractors were used to evaluate the components and system from a manufacturing and overall design optimization viewpoint. Design for manufacturing and assembly (DFMA) techniques, computer models and laboratory/full-scale testing of components were utilized to optimize the design during all phases of the design development. Early in the program evaluation, a review of existing Praxair hydrogen facilities showed that over 50% of the installed cost of a SMR based hydrogen plant is associated with the high temperature components (reformer, shift, steam generation, and various high temperature heat exchange). The main effort of the initial phase of the program was to develop an integrated high temperature component for these related functions. Initially, six independent concepts were developed and the processes were modeled to determine overall feasibility. The six concepts were eventually narrowed down to the highest potential concept. A US patent was awarded in February 2009 for the Praxair integrated high temperature component design. A risk analysis of the high temperature component was

  18. Delegation of Acquisition Executive Authority for Capital Asset...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    the Oak Ridge Office by whitney Delegation-AcquisitionExecAuthorityforCapitalAsset Projects-OR-WhitneyEM.pdf -- PDF Document, 627 KB ID: NA Type: Organizations' Assignment of...

  19. Delegation of Acquisition Executive Authority for Capital Asset...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Related to: DOE O 413.3B, Program and Project Management for the Acquisition of Capital Assets There is no history to display for this document. Document Actions Print this...

  20. ErgyCapital Beghelli JV | Open Energy Information

    Open Energy Info (EERE)

    & Beghelli JV Place: Italy Product: Italy-based JV, formed to design and install photovoltaic systems. References: ErgyCapital & Beghelli JV1 This article is a stub. You can...

  1. Three State Capitals to Receive Green Design Assistance from EPA

    Broader source: Energy.gov [DOE]

    The U.S. Environmental Protection Agency (EPA) on January 9 announced urban planning design assistance to help the capital cities of Michigan, Washington, and Wisconsin develop greener designs, including the use of renewable energy technologies.

  2. Workplace Charging Challenge Partner: Capital One Financial Corporatio...

    Energy Savers [EERE]

    As of early 2014, Capital One has installed 60 Level 2 plug-in electric vehicle (PEV) charging units at five company sites. These charging stations support associates who purchase ...

  3. Project Management for the Acquisition of Capital Assets

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2003-03-28

    The purpose of this Manual is to provide requirements and guidance to Department of Energy (DOE) employees, including National Nuclear Security Administration (NNSA) employees on the planning and acquisition of capital assets. Does not cancel other directives.

  4. Chief Human Capital Officer Memo on Improving DOE Recruitment...

    Broader source: Energy.gov (indexed) [DOE]

    Improving DOE Recruitment and Hiring Processes (540.02 KB) Responsible Contacts Kenneth Venuto Director, Office of Human Capital Management E-mail kenneth.venuto@hq.doe.gov More ...

  5. Human Capital: The Role of Ombudsmen in Dispute Resolution |...

    Broader source: Energy.gov (indexed) [DOE]

    Human Capital: The Role of Ombudsmen in Dispute Resolution (339.67 KB) More Documents & Publications The Role of Ombudsmen in Dispute Resolution TT Coordinator Ltr dated May 13 ...

  6. Women in engineering conference: capitalizing on today`s challenges

    SciTech Connect (OSTI)

    Metz, S.S.; Martins, S.M.

    1996-06-01

    This document contains the conference proceedings of the Women in Engineering Conference: Capitalizing on Today`s Challenges, held June 1-4, 1996 in Denver, Colorado. Topics included engineering and science education, career paths, workplace issues, and affirmative action.

  7. Tribal Renewable Energy Webinar: Accessing Capital for Tribal Energy and

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Economic Development | Department of Energy Accessing Capital for Tribal Energy and Economic Development Tribal Renewable Energy Webinar: Accessing Capital for Tribal Energy and Economic Development October 26, 2016 11:00AM to 12:30PM MDT Understand available financing mechanisms that can be used to make energy efficiency and renewable energy projects economically feasible, including utility community solar models, third-party vendors, green bonds, energy savings performance contracts, and

  8. Low Capital Photovoltaic Panel Electrical Output-Booster System |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy Low Capital Photovoltaic Panel Electrical Output-Booster System Low Capital Photovoltaic Panel Electrical Output-Booster System This presentation summarizes the information given during the DOE SunShot Grand Challenge: Summit and Technology Forum, June 13-14, 2012. ssgrandchallenge_finance_schrag.pdf (63.07 KB) More Documents & Publications The SunShot Vision Study SunShot Vision Study: February 2012 (Book), SunShot, Energy Efficiency & Renewable Energy (EERE)

  9. Direct/Indirect Costs

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    This chapter provides recommended categories for direct and indirect elements developed by the Committee for Cost Methods Development (CCMD) and describes various estimating techniques for direct and indirect costs.

  10. Vehicle Cost Calculator

    Alternative Fuels and Advanced Vehicles Data Center [Office of Energy Efficiency and Renewable Energy (EERE)]

    Annual Fuel Cost gal Annual GHG Emissions (lbs of CO2) Vehicle Cost Calculator See Assumptions and Methodology Back Next U.S. Department of Energy Energy Efficiency and ...

  11. Benchmarking for Cost Improvement. Final report

    SciTech Connect (OSTI)

    Not Available

    1993-09-01

    The US Department of Energy`s (DOE) Office of Environmental Restoration and Waste Management (EM) conducted the Benchmarking for Cost Improvement initiative with three objectives: Pilot test benchmarking as an EM cost improvement tool; identify areas for cost improvement and recommend actions to address these areas; provide a framework for future cost improvement. The benchmarking initiative featured the use of four principal methods (program classification, nationwide cost improvement survey, paired cost comparison and component benchmarking). Interested parties contributed during both the design and execution phases. The benchmarking initiative was conducted on an accelerated basis. Of necessity, it considered only a limited set of data that may not be fully representative of the diverse and complex conditions found at the many DOE installations. The initiative generated preliminary data about cost differences and it found a high degree of convergence on several issues. Based on this convergence, the report recommends cost improvement strategies and actions. This report describes the steps taken as part of the benchmarking initiative and discusses the findings and recommended actions for achieving cost improvement. The results and summary recommendations, reported below, are organized by the study objectives.

  12. Development of Advanced Technologies to Reduce Design, Fabrication and Construction Costs for Future Nuclear Power Plants

    SciTech Connect (OSTI)

    DiNunzio, Camillo A.; Gupta, Abhinav; Golay, Michael; Luk, Vincent; Turk, Rich; Morrow, Charles; Jin, Geum-Taek

    2002-11-30

    This report presents a summation of the third and final year of a three-year investigation into methods and technologies for substantially reducing the capital costs and total schedule for future nuclear plants. In addition, this is the final technical report for the three-year period of studies.

  13. Cost Estimating Guide - DOE Directives, Delegations, and Requirements

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    1, Cost Estimating Guide by Ruben Sanchez Functional areas: Budget and Financial Management, Financial Management This Guide provides uniform guidance and best practices that...

  14. Power Plant Cycling Costs

    SciTech Connect (OSTI)

    Kumar, N.; Besuner, P.; Lefton, S.; Agan, D.; Hilleman, D.

    2012-07-01

    This report provides a detailed review of the most up to date data available on power plant cycling costs. The primary objective of this report is to increase awareness of power plant cycling cost, the use of these costs in renewable integration studies and to stimulate debate between policymakers, system dispatchers, plant personnel and power utilities.

  15. Research Areas

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    in diverse research areas such as cell biology, lithography, infrared microscopy, radiology, and x-ray tomography. Time-Resolved These techniques exploit the pulsed nature of...

  16. Bay Area

    National Nuclear Security Administration (NNSA)

    8%2A en NNSA to Conduct Aerial Radiological Surveys Over San Francisco, Pacifica, Berkeley, And Oakland, CA Areas http:nnsa.energy.govmediaroompressreleasesamsca

  17. Exploration and drilling for geothermal heat in the Capital District, New York. Volume 4. Final report

    SciTech Connect (OSTI)

    Not Available

    1983-08-01

    The Capital District area of New York was explored to determine the nature of a hydrothermal geothermal system. The chemistry of subsurface water and gas, the variation in gravity, magnetism, seismicity, and temperature gradients were determined. Water and gas analyses and temperature gradient measurements indicate the existence of a geothermal system located under an area from Ballston Spa, southward to Altamont, and eastward toward Albany. Gravimetric and magnetic surveys provided little useful data but microseismic activity in the Altamont area may be significant. Eight wells about 400 feet deep, one 600 feet and one 2232 feet were drilled and tested for geothermal potential. The highest temperature gradients, most unusual water chemistries, and greatest carbon dioxide exhalations were observed in the vicinity of the Saratoga and McGregor faults between Saratoga Springs and Schenectady, New York, suggesting some fault control over the geothermal system. Depths to the warm fluids within the system range from 500 meters (Ballston Spa) to 2 kilometers (Albany).

  18. Exploration and drilling for geothermal heat in the Capital District, New York. Final report

    SciTech Connect (OSTI)

    Not Available

    1983-08-01

    The Capital District area of New York was explored to determine the nature of a hydrothermal geothermal system. The chemistry of subsurface water and gas, the variation in gravity, magnetism, seismicity, and temperature gradients were determined. Water and gas analyses and temperature gradient measurements indicate the existence of a geothermal system located under an area from Ballston Spa, southward to Altamont, and eastware toward Albany. Gravimetric and magnetic surveys provided little useful data but microseismic activity in the Altamont area may be significant. Eight wells about 400 feet deep, one 600 feet and one 2232 feet were drilled and tested for geothermal potential. The highest temperature gradients, most unusual water chemistries, and greatest carbon dioxide exhalations were observed in the vicinity of the Saratoga and McGregor faults between Saratoga Springs and Schenectady, New York, suggesting some fault control over the geothermal system. Depths to the warm fluids within the system range from 500 meters (Ballston Spa) to 2 kilometers (Albany).

  19. Application to Export Electric Energy OE Docket No. EA-355 Scotia Capital

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy | Department of Energy 5 Scotia Capital Energy Application to Export Electric Energy OE Docket No. EA-355 Scotia Capital Energy Application from Scotia Capital Energyto export electric energy to Canada Application to Export Electric Energy OE Docket No EA-355 Scotia Capital Energy (209.34 KB) More Documents & Publications EA-355 Scotia Capital Energy, Inc. Application to Export Electric Energy OE Docket No. EA-407 Vitol Inc.: Federal Register Notice, Volume 80, No. 42 - March 4,

  20. Comparison of financing costs for wind turbine and fossil powerplants

    SciTech Connect (OSTI)

    Kahn, E.

    1995-02-01

    This paper compares the financing costs of wind turbine powerplants with those of fossil powerplants. The goal of this examination is to determine the extent to which these costs differ and what the sources of such differences may be. The discussion is organized in the following fashion. Section 2 introduces basic terminology and concepts from finance, as they apply in the powerplant setting. Section 3 reviews available data from a variety of sources to estimate the magnitude of the variables identified in Section 2. In Section 4 we examine the effect of the production tax credit enacted in the Energy Policy Act of 1992 on the financing of wind turbine projects. Conclusions are offered in Section 5. In the past two years there have been only two wind turbine projects that have been financed, so the basis for broad conclusions is limited. Nonetheless, there appears to be a significant advantage in financing costs for conventional projects compared to wind turbines. The two sources of disadvantage to wind power are first, the cost of equity capital is significantly more expensive, and second, the capital structure of wind projects has a much greater fraction of expensive equity than conventional alternatives.

  1. Maximizing productivity & profitability through best cost shift schedules

    SciTech Connect (OSTI)

    Coleman, R.

    1996-12-31

    If you have the right equipment and employees at the right place, the fight time, and the right cost, you have the perfect business schedule. But, if you`re like most mines, you can probably improve your schedule, improvements that will reach all the way to the bottom line. And unlike adding employees, materials, or capital equipment, better scheduling is a cost-free way improve profitability. A good schedule can save millions. A bad schedule will cost money every year. A shift schedule is not a day off pattern or shift length. A shift schedule is a complete system deploying personnel and capital equipment. Most mining schedules are either copied from another operation, based on tradition or the result of a contract negotiation made far from the mine site. Unfortunately, most mine managers don`t give much thought to schedules until a crisis develops; at which point the tendency is to implement the first solution that comes along as quickly as possible. Costly mistakes are made.

  2. Low Cost Lithography Tool for High Brightness LED Manufacturing

    SciTech Connect (OSTI)

    Andrew Hawryluk; Emily True

    2012-06-30

    The objective of this activity was to address the need for improved manufacturing tools for LEDs. Improvements include lower cost (both capital equipment cost reductions and cost-ofownership reductions), better automation and better yields. To meet the DOE objective of $1- 2/kilolumen, it will be necessary to develop these highly automated manufacturing tools. Lithography is used extensively in the fabrication of high-brightness LEDs, but the tools used to date are not scalable to high-volume manufacturing. This activity addressed the LED lithography process. During R&D and low volume manufacturing, most LED companies use contact-printers. However, several industries have shown that these printers are incompatible with high volume manufacturing and the LED industry needs to evolve to projection steppers. The need for projection lithography tools for LED manufacturing is identified in the Solid State Lighting Manufacturing Roadmap Draft, June 2009. The Roadmap states that Projection tools are needed by 2011. This work will modify a stepper, originally designed for semiconductor manufacturing, for use in LED manufacturing. This work addresses improvements to yield, material handling, automation and throughput for LED manufacturing while reducing the capital equipment cost.

  3. Processing Cost Analysis for Biomass Feedstocks

    SciTech Connect (OSTI)

    Badger, P.C.

    2002-11-20

    The receiving, handling, storing, and processing of woody biomass feedstocks is an overlooked component of biopower systems. The purpose of this study was twofold: (1) to identify and characterize all the receiving, handling, storing, and processing steps required to make woody biomass feedstocks suitable for use in direct combustion and gasification applications, including small modular biopower (SMB) systems, and (2) to estimate the capital and operating costs at each step. Since biopower applications can be varied, a number of conversion systems and feedstocks required evaluation. In addition to limiting this study to woody biomass feedstocks, the boundaries of this study were from the power plant gate to the feedstock entry point into the conversion device. Although some power plants are sited at a source of wood waste fuel, it was assumed for this study that all wood waste would be brought to the power plant site. This study was also confined to the following three feedstocks (1) forest residues, (2) industrial mill residues, and (3) urban wood residues. Additionally, the study was confined to grate, suspension, and fluidized bed direct combustion systems; gasification systems; and SMB conversion systems. Since scale can play an important role in types of equipment, operational requirements, and capital and operational costs, this study examined these factors for the following direct combustion and gasification system size ranges: 50, 20, 5, and 1 MWe. The scope of the study also included: Specific operational issues associated with specific feedstocks (e.g., bark and problems with bridging); Opportunities for reducing handling, storage, and processing costs; How environmental restrictions can affect handling and processing costs (e.g., noise, commingling of treated wood or non-wood materials, emissions, and runoff); and Feedstock quality issues and/or requirements (e.g., moisture, particle size, presence of non-wood materials). The study found that over the

  4. MRS/IS facility co-located with a repository: preconceptual design and life-cycle cost estimates

    SciTech Connect (OSTI)

    Smith, R.I.; Nesbitt, J.F.

    1982-11-01

    A program is described to examine the various alternatives for monitored retrievable storage (MRS) and interim storage (IS) of spent nuclear fuel, solidified high-level waste (HLW), and transuranic (TRU) waste until appropriate geologic repository/repositories are available. The objectives of this study are: (1) to develop a preconceptual design for an MRS/IS facility that would become the principal surface facility for a deep geologic repository when the repository is opened, (2) to examine various issues such as transportation of wastes, licensing of the facility, and environmental concerns associated with operation of such a facility, and (3) to estimate the life cycle costs of the facility when operated in response to a set of scenarios which define the quantities and types of waste requiring storage in specific time periods, which generally span the years from 1990 until 2016. The life cycle costs estimated in this study include: the capital expenditures for structures, casks and/or drywells, storage areas and pads, and transfer equipment; the cost of staff labor, supplies, and services; and the incremental cost of transporting the waste materials from the site of origin to the MRS/IS facility. Three scenarios are examined to develop estimates of life cycle costs of the MRS/IS facility. In the first scenario, HLW canisters are stored, starting in 1990, until the co-located repository is opened in the year 1998. Additional reprocessing plants and repositories are placed in service at various intervals. In the second scenario, spent fuel is stored, starting in 1990, because the reprocessing plants are delayed in starting operations by 10 years, but no HLW is stored because the repositories open on schedule. In the third scenario, HLW is stored, starting in 1990, because the repositories are delayed 10 years, but the reprocessing plants open on schedule.

  5. Bonneville Power Administration's Power Function Review II Final...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    areas. * Changes in capital cost recovery o Amortization periods for conservation and Fish and Wildlife investments o Columbia Generating Station debt life and additional capital...

  6. Capital investment requirements for greenhouse gas emissions mitigation in power generation on near term to century time scales and global to regional spatial scales

    SciTech Connect (OSTI)

    Chaturvedi, Vaibhav; Clarke, Leon E.; Edmonds, James A.; Calvin, Katherine V.; Kyle, G. Page

    2014-11-01

    Electrification plays a crucial role in cost-effective greenhouse gas emissions mitigation strategies. Such strategies in turn carry implications for financial capital markets. This paper explores the implication of climate mitigation policy for capital investment demands by the electric power sector on decade to century time scales. We go further to explore the implications of technology performance and the stringency of climate policy for capital investment demands by the power sector. Finally, we discuss the regional distribution of investment demands. We find that stabilizing GHG emissions will require additional investment in the electricity generation sector over and above investments that would be need in the absence of climate policy, in the range of 16 to 29 Trillion US$ (60-110%) depending on the stringency of climate policy during the period 2015 to 2095 under default technology assumptions. This increase reflects the higher capital intensity of power systems that control emissions. Limits on the penetration of nuclear and carbon capture and storage technology could increase costs substantially. Energy efficiency improvements can reduce the investment requirement by 8 to21 Trillion US$ (default technology assumptions), depending on climate policy scenario with higher savings being obtained under the most stringent climate policy. The heaviest investments in power generation were observed in the China, India, SE Asia and Africa regions with the latter three regions dominating in the second half of the 21st century.

  7. Western Area Power Administration combined power system financial statements September 30, 1994 and 1993 and management overview and performance measurements

    SciTech Connect (OSTI)

    Marwick, P.

    1994-12-31

    The attached report presents the results of the independent certified public accountant`s audit of the Department of Energy`s Western Area Power Administration`s (Western) combined financial statements as of September 30, 1994. The auditors have expressed an unqualified opinion on Western`s 1994 statements. Their reports on Western`s internal control structure and on compliance with laws and regulations are also provided. Western was established in December 1977, and has the responsibility for the Federal electric power marketing and transmission functions in 15 central and western states. Western markets power, as required by existing law, at the lowest possible rates consistent with sound business principles to recover the costs of operation and capital invested in power facilities.

  8. Capital Asset Project List-June.xls

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Number Project Name Site Critical Decision Total Project Cost Approved Project End Date 15-D-411 Safety Significant Confinement Ventilation System Carlsbad CD-1 $280,000,000 3/31/2021 15-D-412 Exhaust Shaft Carlsbad CD-1 $118,000,000 3/31/2021 CBC-ETEC-0040.C1 Energy Technology Engineering Center Demolition Project ETEC CD-0 $29,000,000 9/30/2019 15-D-401 KW Basin Sludge Removal Project Hanford Site CD-3 $311,000,000 11/30/2019 RL-0011.C1 Plutonium Finishing Plant (PFP) Decontamination and

  9. Cost analysis guidelines

    SciTech Connect (OSTI)

    Strait, R.S.

    1996-01-10

    The first phase of the Depleted Uranium Hexafluoride Management Program (Program)--management strategy selection--consists of several program elements: Technology Assessment, Engineering Analysis, Cost Analysis, and preparation of an Environmental Impact Statement (EIS). Cost Analysis will estimate the life-cycle costs associated with each of the long-term management strategy alternatives for depleted uranium hexafluoride (UF6). The scope of Cost Analysis will include all major expenditures, from the planning and design stages through decontamination and decommissioning. The costs will be estimated at a scoping or preconceptual design level and are intended to assist decision makers in comparing alternatives for further consideration. They will not be absolute costs or bid-document costs. The purpose of the Cost Analysis Guidelines is to establish a consistent approach to analyzing of cost alternatives for managing Department of Energy`s (DOE`s) stocks of depleted uranium hexafluoride (DUF6). The component modules that make up the DUF6 management program differ substantially in operational maintenance, process-options, requirements for R and D, equipment, facilities, regulatory compliance, (O and M), and operations risk. To facilitate a consistent and equitable comparison of costs, the guidelines offer common definitions, assumptions or basis, and limitations integrated with a standard approach to the analysis. Further, the goal is to evaluate total net life-cycle costs and display them in a way that gives DOE the capability to evaluate a variety of overall DUF6 management strategies, including commercial potential. The cost estimates reflect the preconceptual level of the designs. They will be appropriate for distinguishing among management strategies.

  10. substantially reduced production costs

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    production costs - Sandia Energy Energy Search Icon Sandia Home Locations Contact Us Employee Locator Energy & Climate Secure & Sustainable Energy Future Stationary Power Energy ...

  11. SOFT COST GRAND CHALLENGE

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    energycenter.org California Center for Sustainable Energy Soft Cost Grand Challenge May 22, 2014 Accelerating the transition to a sustainable world powered by clean energy 2...

  12. Low Cost, Durable Seal

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    UTC Power Corporation February 14, 2007 This presentation does not contain any proprietary or confidential information 1 LOW COST, DURABLE SEAL Outline * Project Objective * ...

  13. Workplace Charging Installation Costs

    Broader source: Energy.gov [DOE]

    Installation costs and services vary considerably, so employers are encouraged to obtain a number of quotes before moving forward with any installation. An initial site investigation should include:

  14. DOE Hosts Festival to Collect Items for Area Food Banks

    Broader source: Energy.gov [DOE]

    WASHINGTON, D.C. – Deputy Secretary of Energy Daniel Poneman and a representative of the Capital Area Food Bank are among the guest speakers at an event this Tuesday, July 31, to collect food items for the DOE Feeds Families drive.

  15. Manufacturing Cost Levelization Model – A User’s Guide

    SciTech Connect (OSTI)

    Morrow, William R.; Shehabi, Arman; Smith, Sarah Josephine

    2015-08-01

    The Manufacturing Cost Levelization Model is a cost-performance techno-economic model that estimates total large-scale manufacturing costs for necessary to produce a given product. It is designed to provide production cost estimates for technology researchers to help guide technology research and development towards an eventual cost-effective product. The model presented in this user’s guide is generic and can be tailored to the manufacturing of any product, including the generation of electricity (as a product). This flexibility, however, requires the user to develop the processes and process efficiencies that represents a full-scale manufacturing facility. The generic model is comprised of several modules that estimate variable costs (material, labor, and operating), fixed costs (capital & maintenance), financing structures (debt and equity financing), and tax implications (taxable income after equipment and building depreciation, debt interest payments, and expenses) of a notional manufacturing plant. A cash-flow method is used to estimate a selling price necessary for the manufacturing plant to recover its total cost of production. A levelized unit sales price ($ per unit of product) is determined by dividing the net-present value of the manufacturing plant’s expenses ($) by the net present value of its product output. A user defined production schedule drives the cash-flow method that determines the levelized unit price. In addition, an analyst can increase the levelized unit price to include a gross profit margin to estimate a product sales price. This model allows an analyst to understand the effect that any input variables could have on the cost of manufacturing a product. In addition, the tool is able to perform sensitivity analysis, which can be used to identify the key variables and assumptions that have the greatest influence on the levelized costs. This component is intended to help technology researchers focus their research attention on tasks

  16. Rocky Flats Closure Unit Cost Data

    SciTech Connect (OSTI)

    Sanford, P.C.; Skokan, B.

    2007-07-01

    The Rocky Flats Closure Project has completed the process of stabilizing residual nuclear materials, decommissioning nuclear facilities, remediating environmental media and closing the Rocky Flats Site (Site). The project cost approximately $4.1 B and included the decommissioning of over 700 structures including 5 major plutonium facilities and 5 major uranium facilities, shipping over 14,600 cubic meters of transuranic and 565,000 cubic meters of low level radioactive waste, and remediating a 385-acre industrial area and the surrounding land. Actual costs were collected for a large variety of closure activities. These costs can be correlated with metrics associated with the facilities and environmental media to capture cost factors from the project that could be applicable to a variety of other closure projects both within and outside of the Department of Energy's weapons complex. The paper covers four general topics: the process to correlate the actual costs and metrics, an example of the correlated data for one large sub-project, a discussion of the results, and the additional activities that are planned to correlate and make this data available to the public. The process to collect and arrange the project control data of the Closure Project relied on the actual Closure Project cost information. It was used to correlate these actual costs with the metrics for the physical work, such as building area or waste generated, to support the development of parametric cost factors. The example provides cost factors for the Industrial Sites Project. The discussion addresses the strengths and weaknesses of the data, followed by a section identifying future activities to improve and extend the analyses and integrate it within the Department's Environmental Cost Analysis System. (authors)

  17. Simple Modular LED Cost Model

    Broader source: Energy.gov [DOE]

    The LED Cost Model, developed by the DOE Cost Modeling Working Group, provides a simplified method for analyzing the manufacturing costs of an LED package. The model focuses on the major cost...

  18. Changes in Delegations of Authority from the Office of Human Capital Management

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2016-02-23

    Rescinds specific delegation orders that are rescinded as a result of the restructuring of the human capital function under the Office of the Chief Human Capital Officer with the stand-up of the Shared Service Centers.

  19. Soft Costs Fact Sheet

    Broader source: Energy.gov (indexed) [DOE]

    Energy SunShot Initiative is a collaborative national effort to make solar energy technologies cost-competitive with conventional forms of energy by the end of the decade. ...

  20. Estimating Renewable Energy Costs

    Office of Energy Efficiency and Renewable Energy (EERE)

    Some renewable energy measures, such as daylighting, passive solar heating, and cooling load avoidance, do not add much to the cost of a building. However, renewable energy technologies typically...

  1. Vehicle Cost Calculator

    Alternative Fuels and Advanced Vehicles Data Center [Office of Energy Efficiency and Renewable Energy (EERE)]

    Choose a vehicle to compare fuel cost and emissions with a conventional vehicle. Select FuelTechnology Electric Hybrid Electric Plug-in Hybrid Electric Natural Gas (CNG) Flex Fuel ...

  2. Cost Estimating Guide

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2011-05-09

    This Guide provides uniform guidance and best practices that describe the methods and procedures that could be used in all programs and projects at DOE for preparing cost estimates.

  3. Cost Estimating Guide

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    The objective of this Guide is to improve the quality of cost estimates and further strengthen the DOE program/project management system. The original 25 separate chapters and three appendices have been combined to create a single document.

  4. Cost Estimating Guide

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2011-05-09

    This Guide provides uniform guidance and best practices that describe the methods and procedures that could be used in all programs and projects at DOE for preparing cost estimates. No cancellations.

  5. Liquefaction and Pipeline Costs

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Distribution Pipeline Costs Collected historical Oil & Gas Journal data, and surveyed for ... mile Downtown: 1 to 8 in. Downtown: 4 to 20 in. Urban H2A Right of Way Oil & Gas Journal

  6. INDEPENDENT COST REVIEW (ICR)

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... Report SOP Standard Operating Procedure TEC Total Estimated Cost TIPR Technical ... FY13 FY14 FY15 FY16 Total PED Construction TEC OPC TPC Note: above values include MR...

  7. System Cost Model

    Energy Science and Technology Software Center (OSTI)

    1996-03-27

    SCM is used for estimation of the life-cycle impacts (costs, health and safety risks) of waste management facilities for mixed low-level, low-level, and transuranic waste. SCM uses parametric cost functions to estimate life-cycle costs for various treatment, storage, and disposal modules which reflect planned and existing waste management facilities at Department of Energy (DOE) installations. SCM also provides transportation costs for intersite transfer of DOE wastes. SCM covers the entire DOE waste management complex tomore » allow system sensitivity analysis including: treatment, storage, and disposal configuration options; treatment technology selection; scheduling options; transportation options; waste stream and volume changes; and site specific conditions.« less

  8. Workplace Charging Equipment Costs

    Broader source: Energy.gov [DOE]

    Charging stations are available from a variety of manufacturers in a range of models for all charging applications. For a single port charging station, Level 1 hardware costs range from $300-$1,500...

  9. Power Plant Cycling Costs

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    ... Intertek APTECH has organized the cycling cost data in consultation with NREL and WECC by the following eight generator plant types: 1. Small coal-fired sub-critical steam (35-299 ...

  10. EM Capital and Major Operating Project Standard Review Plan Edition Two

    Broader source: Energy.gov [DOE]

    This memorandum introduces the Second Edition of the Capital and Major Operations Projects Standard Review Plan (SRP).

  11. Cost-Effective Consolidation of Fine Aluminum Scrap for Increased Remelting Effieciency

    SciTech Connect (OSTI)

    William Van Geertruyden

    2005-09-22

    The main objective of this research was to develop a new re-melting process for fine or light gauge aluminum scrap products that exhibits dramatic improvements in energy efficiency. Light gauge aluminum scrap in the form of chips, turnings, and borings has historically been underutilized in the aluminum recycling process due to its high surface area to volume ratio resulting in low melt recovery. Laboratory scale consolidation experiments were performed using loose aluminum powder as a modeling material as well as shredded aluminum wire scrap. The processing parameters necessary to create consolidated aluminum material were determined. Additionally, re-melting experiments using consolidated and unconsolidated aluminum powder confirmed the hypothesis that metal recovery using consolidated material will significantly improve by as much as 20%. Based on this research, it is estimated that approximately 495 billion Btu/year can be saved by implementation of this technology in one domestic aluminum rolling plant alone. The energy savings are realized by substituting aluminum scrap for primary aluminum, which requires large amounts of energy to produce. While there will be an initial capital investment, companies will benefit from the reduction of dependence on primary aluminum thus saving considerable costs. Additionally, the technology will allow companies to maintain in-house alloy scrap, rather than purchasing from other vendors and eliminate the need to discard the light gauge scrap to landfills.

  12. Vehicle Cost Calculator

    Alternative Fuels and Advanced Vehicles Data Center [Office of Energy Efficiency and Renewable Energy (EERE)]

    Choose a vehicle to compare fuel cost and emissions with a conventional vehicle. Select Fuel/Technology Electric Hybrid Electric Plug-in Hybrid Electric Natural Gas (CNG) Flex Fuel (E85) Biodiesel (B20) Next Vehicle Cost Calculator Update Your Widget Code This widget version will stop working on March 31. Update your widget code. × Widget Code Select All Close U.S. Department of Energy Energy Efficiency and Renewable Energy

  13. Independent Cost Estimate (ICE)

    Broader source: Energy.gov [DOE]

    Independent Cost Estimate (ICE). On August 8-12, the Office of Project Management Oversight and Assessments (PM) will conduct an ICE on the NNSA Albuquerque Complex Project (NACP) at Albuquerque, NM. This estimate will support the Critical Decision (CD) for establishing the performance baseline and approval to start construction (CD-2/3). This project is at CD-1, with a total project cost range of $183M to $251M.

  14. Technology choice in a least-cost expansion analysis framework: Effects of gas price, planning period, and system characteristics

    SciTech Connect (OSTI)

    Guziel, K.A.; South, D.W.; Bhatarakamol, S.; Poch, L.A.

    1990-04-01

    The current outlook for new capacity additions by electric utilities is uncertain and tenuous. The fundamental question about the additional capacity requirements center on technology choice and the factors influencing the decision process. Instead of building capital-intensive power plants, utilities have begun relying on natural gas technologies, which permit rapid construction and deployment and low capital investment. Of concern to policymakers and utility planners are the following questions: (1) What is the impact of alternative gas price projections on technology choice (2) What influence does the planning horizon have on technology choice (3) How important are existing system characteristics on technology choice (4) What effect does capital cost, when combined with other technology characteristics in a capacity expansion framework, have on technology choice In this study Argonne National Laboratory examined the impact of these concerns on technology choices in 10 representative power pools with a dynamic optimization expansion model, the Wien Automatic System Planning Package (WASP). At least-cost expansion plan was determined for each power pool with three candidate technologies--natural gas combustion turbine technology (GT), natural gas combined-cycle technology (NGCC), and integrated gasification combined-cycle technology (IGCC)--three alternative fuel price tracks, and two planning periods (10-yr versus 30-yr optimization) between the years 1995 and 2025. The three fuel price tracks represented scenarios for low, medium, and high gas prices. Sensitivity analyses were conducted on IGCC capital cost and unserved energy costs. 21 refs., 79 figs., 21 tabs.

  15. Capital Planning for DOE O 413.3B, Chicago | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Capital Planning for DOE O 413.3B, Chicago Capital Planning for DOE O 413.3B, Chicago March 30, 2016 8:00AM EDT to March 31, 2016 5:00PM EDT Capital Planning for DOE O 413.3B ...

  16. PACCOM: A nuclear waste packaging facility cost model: Draft technical report

    SciTech Connect (OSTI)

    Dippold, D.G.; Tzemos, S.; Smith, D.J.

    1985-05-01

    PACCOM is a computerized, parametric model used to estimate the capital, operating, and decommissioning costs of a variety of nuclear waste packaging facility configurations. The model is based upon a modular waste packaging facility concept from which functional components of the overall facility have been identified and their design and costs related to various parameters such as waste type, waste throughput, and the number of operational shifts employed. The model may be used to either estimate the cost of a particular waste packaging facility configuration or to explore the cost tradeoff between plant capital and labor. That is, one may use the model to search for the particular facility sizes and associated cost which when coupled with a particular number of shifts, and thus staffing level, leads to the lowest overall total cost. The functional components which the model considers include hot cells and their supporting facilities, transportation, cask handling facilities, transuranic waste handling facilities, and administrative facilities such as warehouses, security buildings, maintenance buildings, etc. The cost of each of these functional components is related either directly or indirectly to the various independent design parameters. Staffing by shift is reported into direct and indirect support labor. These staffing levels are in turn related to the waste type, waste throughput, etc. 2 refs., 11 figs., 3 tabs.

  17. Offshore Wind Plant Balance-of-Station Cost Drivers and Sensitivities (Poster)

    SciTech Connect (OSTI)

    Saur, G.; Maples, B.; Meadows, B.; Hand, M.; Musial, W.; Elkington, C.; Clayton, J.

    2012-09-01

    With Balance of System (BOS) costs contributing up to 70% of the installed capital cost, it is fundamental to understanding the BOS costs for offshore wind projects as well as potential cost trends for larger offshore turbines. NREL developed a BOS model using project cost estimates developed by GL Garrad Hassan. Aspects of BOS covered include engineering and permitting, ports and staging, transportation and installation, vessels, foundations, and electrical. The data introduce new scaling relationships for each BOS component to estimate cost as a function of turbine parameters and size, project parameters and size, and soil type. Based on the new BOS model, an analysis to understand the non-turbine costs associated with offshore turbine sizes ranging from 3 MW to 6 MW and offshore wind plant sizes ranging from 100 MW to 1000 MW has been conducted. This analysis establishes a more robust baseline cost estimate, identifies the largest cost components of offshore wind project BOS, and explores the sensitivity of the levelized cost of energy to permutations in each BOS cost element. This presentation shows results from the model that illustrates the potential impact of turbine size and project size on the cost of energy from US offshore wind plants.

  18. U.S. Balance-of-Station Cost Drivers and Sensitivities (Presentation)

    SciTech Connect (OSTI)

    Maples, B.

    2012-10-01

    With balance-of-system (BOS) costs contributing up to 70% of the installed capital cost, it is fundamental to understanding the BOS costs for offshore wind projects as well as potential cost trends for larger offshore turbines. NREL developed a BOS model using project cost estimates developed by GL Garrad Hassan. Aspects of BOS covered include engineering and permitting, ports and staging, transportation and installation, vessels, foundations, and electrical. The data introduce new scaling relationships for each BOS component to estimate cost as a function of turbine parameters and size, project parameters and size, and soil type. Based on the new BOS model, an analysis to understand the non‐turbine costs has been conducted. This analysis establishes a more robust baseline cost estimate, identifies the largest cost components of offshore wind project BOS, and explores the sensitivity of the levelized cost of energy to permutations in each BOS cost element. This presentation shows results from the model that illustrates the potential impact of turbine size and project size on the cost of energy from U.S. offshore wind plants.

  19. Retail Infrastructure Costs Comparison for Hydrogen and Electricity for Light-Duty Vehicles: Preprint

    SciTech Connect (OSTI)

    Melaina, M.; Sun, Y.; Bush, B.

    2014-08-01

    Both hydrogen and plug-in electric vehicles offer significant social benefits to enhance energy security and reduce criteria and greenhouse gas emissions from the transportation sector. However, the rollout of electric vehicle supply equipment (EVSE) and hydrogen retail stations (HRS) requires substantial investments with high risks due to many uncertainties. We compare retail infrastructure costs on a common basis - cost per mile, assuming fueling service to 10% of all light-duty vehicles in a typical 1.5 million person city in 2025. Our analysis considers three HRS sizes, four distinct types of EVSE and two distinct EVSE scenarios. EVSE station costs, including equipment and installation, are assumed to be 15% less than today's costs. We find that levelized retail capital costs per mile are essentially indistinguishable given the uncertainty and variability around input assumptions. Total fuel costs per mile for battery electric vehicle (BEV) and plug-in hybrid vehicle (PHEV) are, respectively, 21% lower and 13% lower than that for hydrogen fuel cell electric vehicle (FCEV) under the home-dominant scenario. Including fuel economies and vehicle costs makes FCEVs and BEVs comparable in terms of costs per mile, and PHEVs are about 10% less than FCEVs and BEVs. To account for geographic variability in energy prices and hydrogen delivery costs, we use the Scenario Evaluation, Regionalization and Analysis (SERA) model and confirm the aforementioned estimate of cost per mile, nationally averaged, but see a 15% variability in regional costs of FCEVs and a 5% variability in regional costs for BEVs.

  20. Subsurface contaminants focus area

    SciTech Connect (OSTI)

    1996-08-01

    The US Department of Enregy (DOE) Subsurface Contaminants Focus Area is developing technologies to address environmental problems associated with hazardous and radioactive contaminants in soil and groundwater that exist throughout the DOE complex, including radionuclides, heavy metals; and dense non-aqueous phase liquids (DNAPLs). More than 5,700 known DOE groundwater plumes have contaminated over 600 billion gallons of water and 200 million cubic meters of soil. Migration of these plumes threatens local and regional water sources, and in some cases has already adversely impacted off-site rsources. In addition, the Subsurface Contaminants Focus Area is responsible for supplying technologies for the remediation of numerous landfills at DOE facilities. These landfills are estimated to contain over 3 million cubic meters of radioactive and hazardous buried Technology developed within this specialty area will provide efective methods to contain contaminant plumes and new or alternative technologies for development of in situ technologies to minimize waste disposal costs and potential worker exposure by treating plumes in place. While addressing contaminant plumes emanating from DOE landfills, the Subsurface Contaminants Focus Area is also working to develop new or alternative technologies for the in situ stabilization, and nonintrusive characterization of these disposal sites.

  1. ''Measuring the Costs of Climate Change Policies''

    SciTech Connect (OSTI)

    Montgomery, W. D.; Smith, A. E.; Biggar, S. L.; Bernstein, P.M.

    2003-05-09

    Studies of the costs of climate change policies have utilized a variety of measures or metrics for summarizing costs. The leading economic models have utilized GNP, GDP, the ''area under a marginal cost curve,'' the discounted present value of consumption, and a welfare measure taken directly from the utility function of the model's representative agent (the ''Equivalent Variation''). Even when calculated using a single model, these metrics do not necessarily give similar magnitudes of costs or even rank policies consistently. This paper discusses in non-technical terms the economic concepts lying behind each concept, the theoretical basis for expecting each measure to provide a consistent ranking of policies, and the reasons why different measures provide different rankings. It identifies a method of calculating the ''Equivalent Variation'' as theoretically superior to the other cost metrics in ranking policies. When regulators put forward new economic or regulatory policies, there is a need to compare the costs and benefits of these new policies to existing policies and other alternatives to determine which policy is most cost-effective. For command and control policies, it is quite difficult to compute costs, but for more market-based policies, economists have had a great deal of success employing general equilibrium models to assess a policy's costs. Not all cost measures, however, arrive at the same ranking. Furthermore, cost measures can produce contradictory results for a specific policy. These problems make it difficult for a policy-maker to determine the best policy. For a cost measures to be of value, one would like to be confident of two things. First one wants to be sure whether the policy is a winner or loser. Second, one wants to be confident that a measure produces the correct policy ranking. That is, one wants to have confidence in a policy measure's ability to correctly rank policies from most beneficial to most harmful. This paper analyzes

  2. Factory Cost Model

    Energy Science and Technology Software Center (OSTI)

    1996-12-17

    The Factory Cost Model (FCM) is an economic analysis tool intended to provide flat panel display (FPD) and other similar discrete component manufacturers with the ability to make first-order estimates of the cost of unit production. This software has several intended uses. Primary among these is the ability to provide first-order economic analysis for future factories. Consequently, the model requires a minimal level of input detail, and accomodates situations where actual production data are notmore » available. This software is designed to be activity based such that most of the calculated direct costs are associated with the steps of a manufacturibg process. The FCM architecture has the ability to accomodate the analysis of existing manufacturing facilities. The FCM can provide assistance with strategic economic decisions surrounding production related matters. For instance, the program can project the effect on costs and resources of a new product''s introduction, or it can assess the potential cost reduction produced by step yield improvements in the manufacturing process.« less

  3. Replacing the Rare Earth Intellectual Capital

    SciTech Connect (OSTI)

    Gschneidner, Jr., Karl

    2011-04-01

    The rare earth crisis slowly evolved during a 10 to 15 year period beginning in the mid-1980s, when the Chinese began to export mixed rare earth concentrates. In the early 1990s, they started to move up the supply chain and began to export the individual rare earth oxides and metals. By the late 1990s the Chinese exported higher value products, such as magnets, phosphors, polishing compounds, catalysts; and in the 21st century they supplied finished products including electric motors, computers, batteries, liquid-crystal displays (LCDs), TVs and monitors, mobile phones, iPods and compact fluorescent lamp (CFL) light bulbs. As they moved to higher value products, the Chinese slowly drove the various industrial producers and commercial enterprises in the US, Europe and Japan out of business by manipulating the rare earth commodity prices. Because of this, the technically trained rare earth engineers and scientists who worked in areas from mining to separations, to processing to production, to manufacturing of semifinished and final products, were laid-off and moved to other fields or they retired. However, in the past year the Chinese have changed their philosophy of the 1970s and 1980s of forming a rare earth cartel to control the rare earth markets to one in which they will no longer supply the rest of the world (ROW) with their precious rare earths, but instead will use them internally to meet the growing demand as the Chinese standard of living increases. To this end, they have implemented and occasionally increased export restrictions and added an export tariff on many of the high demand rare earth elements. Now the ROW is quickly trying to start up rare earth mines, e.g. Molycorp Minerals in the US and Lynas Corp. in Australia, to cover this shortfall in the worldwide market, but it will take about five years for the supply to meet the demand, even as other mines in the ROW become productive. Unfortunately, today there is a serious lack of technically trained

  4. Innovative Feed-In Tariff Designs that Limit Policy Costs

    SciTech Connect (OSTI)

    Kreycik, Claire; Couture, Toby D.; Cory, Karlynn S.

    2011-06-01

    Feed-in tariffs (FITs) are the most prevalent policy used globally to reduce development risks, cut financing costs, and grow the renewable energy industry. However, concerns over escalating costs in jurisdictions with FIT policies have led to increased attention on cost control. Using case studies and market-focused analysis, this report from the National Renewable Energy Laboratory (NREL) examines strengths and weaknesses of three cost-containment tools: (1) caps, (2) payment level adjustment mechanisms, and (3) auction-based designs. The report provides useful insights on containing costs for policymakers and regulators in the United States and other areas where FIT policies are in development.

  5. Factors Impacting Decommissioning Costs - 13576

    SciTech Connect (OSTI)

    Kim, Karen; McGrath, Richard

    2013-07-01

    The Electric Power Research Institute (EPRI) studied United States experience with decommissioning cost estimates and the factors that impact the actual cost of decommissioning projects. This study gathered available estimated and actual decommissioning costs from eight nuclear power plants in the United States to understand the major components of decommissioning costs. Major costs categories for decommissioning a nuclear power plant are removal costs, radioactive waste costs, staffing costs, and other costs. The technical factors that impact the costs were analyzed based on the plants' decommissioning experiences. Detailed cost breakdowns by major projects and other cost categories from actual power plant decommissioning experiences will be presented. Such information will be useful in planning future decommissioning and designing new plants. (authors)

  6. Soft Costs | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    costs program works to lower the non-hardware costs of ... data analysis, business innovation, and training. ... for as much as 64% of the total cost of a new solar system. ...

  7. Low Cost, Durable Seal

    SciTech Connect (OSTI)

    Roberts, George; Parsons, Jason; Friedman, Jake

    2010-12-17

    Seal durability is critical to achieving the 2010 DOE operational life goals for both stationary and transportation PEM fuel cell stacks. The seal material must be chemically and mechanically stable in an environment consisting of aggressive operating temperatures, humidified gases, and acidic membranes. The seal must also be producible at low cost. Currentlyused seal materials do not meet all these requirements. This project developed and demonstrated a high consistency hydrocarbon rubber seal material that was able to meet the DOE technical and cost targets. Significant emphasis was placed on characterization of the material and full scale molding demonstrations.

  8. Analysis of sheltering and evacuation strategies for a national capital region nuclear detonation scenario.

    SciTech Connect (OSTI)

    Yoshimura, Ann S.; Brandt, Larry D.

    2011-12-01

    Development of an effective strategy for shelter and evacuation is among the most important planning tasks in preparation for response to a low yield, nuclear detonation in an urban area. Extensive studies have been performed and guidance published that highlight the key principles for saving lives following such an event. However, region-specific data are important in the planning process as well. This study examines some of the unique regional factors that impact planning for a 10 kT detonation in the National Capital Region. The work utilizes a single scenario to examine regional impacts as well as the shelter-evacuate decision alternatives at one exemplary point. For most Washington, DC neighborhoods, the excellent assessed shelter quality available make shelter-in-place or selective transit to a nearby shelter a compelling post-detonation strategy.

  9. Turbine Cost Systems Engineering Model

    Energy Science and Technology Software Center (OSTI)

    2012-09-30

    turb_costSE is a set of models that link wind turbine component masses (and a few other key variables) to component costs.

  10. NREL Technology Transfer: Facilitating Capital Investment in Clean Energy Technology

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Technology Transfer Facilitating Capital Investment in Clean Energy Technology Tom A. Williams Director, Technology Transfer Office National Renewable Energy Laboratory We Are Unique * Only national laboratory dedicated to renewable energy and energy efficiency R&D * Research spans fundamental science to technology solutions * Collaboration with industry, university and international partners is a hallmark * Research is market relevant because of a systems focus and global perspective and

  11. Human Capital: The Role of Ombudsmen in Dispute Resolution

    Office of Environmental Management (EM)

    the Ranking Member, Subcommittee on International Security, Proliferation, and Federal Services, Committee on Government Affairs, U.S. Senate United States General Accounting Office GAO April 2001 HUMAN CAPITAL The Role of Ombudsmen in Dispute Resolution GAO-01-466 Page i GAO-01-466 The Role of Ombudsmen in Dispute Resolution Letter 1 Results in Brief 2 Background 5 Objectives, Scope, and Methodology 12 Some Agencies Use Ombudsmen to Deal With Workplace Issues 14 The Case Illustrations: Varied

  12. Program and Project Management for the Acquisition of Capital Assets

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2006-07-28

    The Order provides project management direction for the acquisition of capital assets that are delivered on schedule, within budget, and capable of meeting mission performance and environmental safety and health standards. The page change incorporates requirements of DOE-STD-1189-2008, Integration of Safety into the Design Process, mandatory for Hazard Category 1, 2 and 3 nuclear facilities. Cancels DOE O 413.3. Canceled by DOE O 413.3B dated 11-29-10.

  13. Program and Project Management for the Acquisition of Capital Assets

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2011-05-18

    To provide the Department of Energy (DOE), including the National Nuclear Security Administration, with project management direction for the acquisition of capital assets with the goal of delivering projects on schedule, within budget, and fully capable of meeting mission performance, safeguards and security, and environmental, safety, and health standards. Cancels DOE O 413.3. Canceled by DOE O 413.3A Chg 1.

  14. The Dog Days of Summer - Capitalizing on the Pet Market

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Dog Days of Summer - Capitalizing on the Pet Market July 9, 2015 Call Slides and Discussion Summary Agenda  Call Logistics and Opening Poll #1  Introductions  Residential Network and Peer Exchange Call Overview  Opening Poll #2 and #3  Setting the Stage: Pet Market Statistics  Featured Speaker  Julie Saporito, Program Administrator, City and County of Denver (Network Member)  Discussion  What opportunities exist for leveraging the pet market to promote residential

  15. Parabolic Trough Reference Plant for Cost Modeling with the Solar Advisor Model (SAM)

    SciTech Connect (OSTI)

    Turchi, C.

    2010-07-01

    This report describes a component-based cost model developed for parabolic trough solar power plants. The cost model was developed by the National Renewable Energy Laboratory (NREL), assisted by WorleyParsons Group Inc., for use with NREL's Solar Advisor Model (SAM). This report includes an overview and explanation of the model, two summary contract reports from WorleyParsons, and an Excel spreadsheet for use with SAM. The cost study uses a reference plant with a 100-MWe capacity and six hours of thermal energy storage. Wet-cooling and dry-cooling configurations are considered. The spreadsheet includes capital and operating cost by component to allow users to estimate the impact of changes in component costs.

  16. NREL Releases Updated Baseline of Cost and Performance Data for Electricity

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Generation Technologies - News Releases | NREL Releases Updated Baseline of Cost and Performance Data for Electricity Generation Technologies Webinar to be held on September 13 September 1, 2016 Graph-showing-NREL-2016-Annual-Technology-Baseline From NREL's 2016 Annual Technology Baseline, the projected Capital Expenditure (CAPEX) for electricity generating technologies in 2030. The Energy Department's National Renewable Energy Laboratory (NREL) has released the 2016 Annual Technology

  17. Industry-backed Best Practices Guides Aim to Lower Financing Costs for

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Solar Energy Systems - News Releases | NREL Industry-backed Best Practices Guides Aim to Lower Financing Costs for Solar Energy Systems March 31, 2015 The Solar Access to Public Capital (SAPC) working group has released new best practices guidelines for solar photovoltaic (PV) systems, with the goal of increasing investor confidence in the long-term viability of PV systems. The guides - SAPC Best Practices in PV System Installation and SAPC Best Practices in PV Operations and Maintenance -

  18. Systematic Approach to Better Understanding Integration Costs: Preprint

    SciTech Connect (OSTI)

    Stark, Gregory B.

    2015-09-28

    When someone mentions integration costs, thoughts of the costs of integrating renewable generation into an existing system come to mind. We think about how variability and uncertainty can increase power system cycling costs as increasing amounts of wind or solar generation are incorporated into the generation mix. However, seldom do we think about what happens to system costs when new baseload generation is added to an existing system or when generation self-schedules. What happens when a highly flexible combined-cycle plant is added? Do system costs go up, or do they go down? Are other, non-cycling, maintenance costs impacted? In this paper we investigate six technologies and operating practices--including VG, baseload generation, generation mix, gas prices, self-scheduling, and fast-start generation--and how changes in these areas can impact a system's operating costs. This paper provides a working definition of integration costs and four components of variable costs. It describes the study approach and how a production cost modeling-based method was used to determine the cost effects, and, as a part of the study approach section, it describes the test system and data used for the comparisons. Finally, it presents the research findings, and, in closing, suggests three areas for future work.

  19. Thermal Gradient Holes At Upper Hot Creek Ranch Area (Benoit...

    Open Energy Info (EERE)

    of Hot Creek Canyon where challenges such as topography, a wilderness study area, and wetlands issues will make further exploration time consuming and costly. References Dick...

  20. Cost Estimating, Analysis, and Standardization

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1984-11-02

    To establish policy and responsibilities for: (a) developing and reviewing project cost estimates; (b) preparing independent cost estimates and analysis; (c) standardizing cost estimating procedures; and (d) improving overall cost estimating and analytical techniques, cost data bases, cost and economic escalation models, and cost estimating systems. Cancels DOE O 5700.2B, dated 8-5-1983; DOE O 5700.8, dated 5-27-1981; and HQ 1130.1A, dated 12-30-1981. Canceled by DOE O 5700.2D, dated 6-12-1992

  1. Geothermal probabilistic cost study

    SciTech Connect (OSTI)

    Orren, L.H.; Ziman, G.M.; Jones, S.C.; Lee, T.K.; Noll, R.; Wilde, L.; Sadanand, V.

    1981-08-01

    A tool is presented to quantify the risks of geothermal projects, the Geothermal Probabilistic Cost Model (GPCM). The GPCM model is used to evaluate a geothermal reservoir for a binary-cycle electric plant at Heber, California. Three institutional aspects of the geothermal risk which can shift the risk among different agents are analyzed. The leasing of geothermal land, contracting between the producer and the user of the geothermal heat, and insurance against faulty performance are examined. (MHR)

  2. Hydrogen and Infrastructure Costs

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    FUEL CELL TECHNOLOGIES PROGRAM Hydrogen and Infrastructure Costs Hydrogen Infrastructure Market Readiness Workshop Washington D.C. February 17, 2011 Fred Joseck U.S. Department of Energy Fuel Cell Technologies Program Fuel Cells: Diverse Fuels and Applications More than $40 million from the 2009 American Recovery and Reinvestment Act to fund 12 projects to deploy up to 1,000 fuel cells Recovery Act Funding for Fuel Cells COMPANY AWARD APPLICATION Delphi Automotive $2.4 M Auxiliary Power FedEx

  3. Privatization Financing Alternatives: Blending Private Capital and Public Resources for a Successful Project

    SciTech Connect (OSTI)

    BT Oakley; JH Holbrook; L Scully; MR Weimar; PK Kearns; R DiPrinzio

    1998-10-19

    The U.S. Department of Energy (DOE) launched the Contract Reform Initiative in 1994 in order to improve the effectiveness and effkiency of managing major projects and programs. The intent of this initiative is to help DOE harness both technical and market forces to reduce the overall cost of accomplishing DOE's program goals. The new approach transfers greater risk to private contractors in order to develop incentives that align contractor performance with DOE's objectives. In some cases, this goal can be achieved through public-private partnerships wherein the govermhent and the contractor share risks associated with a project in a way that optimizes its economics. Generally, this requires that project risks are allocated to the party best equipped to manage and/or underwrite them. While the merits of privatization are well documented, the question of how privatized services should be financed is often debated. Given the cost of private sector equity and debt, it is difficult to ignore the lure of the government's "risk free" cost of capital. However, the source of financing for a project is an integral part of its overall risk allocation, and therefore, participation by the government as a financing source could alter the allocation of risks in the project, diminishing the incentive structure. Since the government's participation in the project's financing often can be a requirement for financial feasibility, the dilemma of structuring a role for the government without undermining the success of the project is a common and difficult challenge faced by policymakers around the world. However, before reverting to a traditional procurement approach where the government enters into a cost-plus risk profile, the government should exhaust all options that keep the private entity at risk for important aspects of the project. Government participation in a project can include a broad range of options and can be applied with precision to bridge a gap in the project

  4. Nuclear economics 2000: Deterministic and probabilistic projections of nuclear and coal electric power generation costs for the year 2000

    SciTech Connect (OSTI)

    Williams, K.A.; Delene, J.G.; Fuller, L.C.; Bowers, H.I.

    1987-06-01

    The total busbar electric generating costs were estimated for locations in ten regions of the United States for base-load nuclear and coal-fired power plants with a startup date of January 2000. For the Midwest region a complete data set that specifies each parameter used to obtain the comparative results is supplied. When based on the reference set of input variables, the comparison of power generation costs is found to favor nuclear in most regions of the country. Nuclear power is most favored in the northeast and western regions where coal must be transported over long distances; however, coal-fired generation is most competitive in the north central region where large reserves of cheaply mineable coal exist. In several regions small changes in the reference variables could cause either option to be preferred. The reference data set reflects the better of recent electric utility construction cost experience (BE) for nuclear plants. This study assumes as its reference case a stable regulatory environment and improved planning and construction practices, resulting in nuclear plants typically built at the present BE costs. Today's BE nuclear-plant capital investment cost model is then being used as a surrogate for projected costs for the next generation of light-water reactor plants. An alternative analysis based on today's median experience (ME) nuclear-plant construction cost experience is also included. In this case, coal is favored in all ten regions, implying that typical nuclear capital investment costs must improve for nuclear to be competitive.

  5. Cost Study Manual | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Cost Study Manual Cost Study Manual Update 62912. PDF icon Memo regarding Cost Study Manual PDF icon Cost Study Manual More Documents & Publications Contractor Human Resources ...

  6. The Dog Days of Summer - Capitalizing on the Pet Market | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy The Dog Days of Summer - Capitalizing on the Pet Market The Dog Days of Summer - Capitalizing on the Pet Market Better Buildings Residential Network Peer Exchange Call Series: The Dog Days of Summer - Capitalizing on the Pet Market, call slides and discussion summary. Call Slides and Discussion Summary (2.17 MB) More Documents & Publications Leveraging Seasonal Opportunities for Marketing Energy Efficiency Hit the Road: Applying Lessons from National Campaigns to a Local Context

  7. Program and Project Management Policy for the Planning, Programming, Budgeting, and Acquisition of Capital Assets

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2000-06-10

    To establish Department of Energy (DOE) program and project management policy for the planning, programming, budgeting, and acquisition of capital assets consistent with the following Office of Management and Budget (OMB) circulars: OMB Circular A-11, Part 3, Planning, Budgeting, and Acquisition of Capital Assets, and the supplement to Part 3, Capital Programming Guide; OMB Circular A-123; OMB Circular A-127; and OMB Circular A-130. Does not cancel other directives. Canceled by DOE N 251.99

  8. DOE Guide to IT Capital Planning and Investment Control BY 2016 |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy Guide to IT Capital Planning and Investment Control BY 2016 DOE Guide to IT Capital Planning and Investment Control BY 2016 DOE Guide to IT Capital Planning and Investment Control BY 2016 BY16 DOE IT CPIC Guide_Final.pdf (905.81 KB) More Documents & Publications BY16 DOE IT CPIC Guide_Final Audit Report: IG-0841 IT Reporting Format and Requirements for the BY 2017 Budget Submission

  9. Levelized cost and levelized avoided cost of new generation resources...

    Annual Energy Outlook [U.S. Energy Information Administration (EIA)]

    3 The importance of the factors varies among the technologies. For technologies such as solar and wind generation that have no fuel costs and relatively small variable O&M costs,...

  10. cost savings | National Nuclear Security Administration

    National Nuclear Security Administration (NNSA)

    cost savings NNSA's Nevada Field Office Transfers Two Armored Vehicles to FBI LAS VEGAS - The National Nuclear Security Administration's (NNSA) Nevada Field Office recently transferred two Advanced Concept Armored Vehicles (ACAVs) to The Department of Justice's local FBI office in Nevada. The transfer created $474,000 in savings to the government as the NFO security force no... Savannah River Site hosts regional Lean Alliance event Companies from around the Central Savannah River Area had the

  11. Native American Housing Stakeholder Meeting- Tribal Data: Building the Bridge to New Capital

    Broader source: Energy.gov [DOE]

    Hosted by the Housing Assistance Council, the Native American Housing Stakeholder Meeting will discuss effective strategies for tribally led data collection, ways to access and leverage new capital...

  12. Energy Department and GSA Assist in Capital Solar Challenge Industry Day

    Broader source: Energy.gov [DOE]

    The Energy Department and GSA are charged with assisting agencies in leading the Capital Solar Challenge with the goal of developing solar renewable power on Federal sites.

  13. Cost | OpenEI Community

    Open Energy Info (EERE)

    Cost Home Ocop's picture Submitted by Ocop(5) Member 15 July, 2014 - 07:07 MHK LCOE Reporting Guidance Draft Cost Current DOE LCOE numerical modeling Performance Tidal Wave To...

  14. Wind Integration Cost and Cost-Causation: Preprint

    SciTech Connect (OSTI)

    Milligan, M.; Kirby, B.; Holttinen, H.; Kiviluoma, J.; Estanqueiro, A.; Martin-Martinez, S.; Gomez-Lazaro, E.; Peneda, I.; Smith, C.

    2013-10-01

    The question of wind integration cost has received much attention in the past several years. The methodological challenges to calculating integration costs are discussed in this paper. There are other sources of integration cost unrelated to wind energy. A performance-based approach would be technology neutral, and would provide price signals for all technology types. However, it is difficult to correctly formulate such an approach. Determining what is and is not an integration cost is challenging. Another problem is the allocation of system costs to one source. Because of significant nonlinearities, this can prove to be impossible to determine in an accurate and objective way.

  15. Credit Enhancements and Capital Markets to Fund Solar Deployment: Leveraging Public Funds to Open Private Sector Investment

    SciTech Connect (OSTI)

    Mendelsohn, M.; Urdanick, M.; Joshi, J.

    2015-02-01

    Credit enhancements represent a variety of financial support structures that are designed to reduce risk to those holding the debt, including debt raised via a securitization process, and thus lower the required yield associated with the security. The purpose of all forms of credit enhancement is to increase the collateral against which notes are secured (Lin,1999). The following section evaluates is not guaranteed. Perceived risks of the solar asset class--including those related to technology, offtaker creditworthiness, and regulatory policy--can increase the required yield, increase probability of investor loss of interest and/or principal, or both. In many cases, this is a cyclical phenomenon: risk perception is fed by lack of historical knowledge, which is in turn fed by risk perception. Therefore, successful access to capital market investment in order to spur low-cost solar deployment depends on the success of this initial fledgling period.

  16. Results from the OECD report on international projections of electricity generating costs

    SciTech Connect (OSTI)

    Paffenbarger, J.A.; Bertel, E.

    1998-07-01

    The International Energy Agency and Nuclear Energy Agency of the OECD have periodically undertaken a joint study on electricity generating costs in OECD Member countries and selected non-Member countries. This paper presents key results from the 1998 update of this study. Experts from 19 countries drawn from electric utility companies and government provided data on capital costs, operating and maintenance costs, and fuel costs from which levelized electricity generating costs (US cents/kWh) for baseload power plants were estimated in each country using a common set of economic assumptions. Light water nuclear power plants, pulverized coal plants, and natural gas-fired combined cycle gas turbines were the principal options evaluated. five and 10% discount rates, 40-year operating lifetime, and 75% annual load factor were the base assumptions, with sensitivity analyses on operating lifetime and load factor. Fuel costs and fuel escalation were provided individually by country, with a sensitivity case to evaluate costs assuming no real fuel price escalation over plant lifetimes. Of the three principal fuel/technology options, none is predominantly the cheapest option for all economic assumptions. However, fossil-fueled options are generally estimated to be the least expensive option. The study confirms that gas-fired combined cycles have improved their economic performance in most countries in recent years and are strong competitors to nuclear and coal-fired plants. Eleven out of the 18 countries with two or more options show gas-fired plants to be the cheapest option at 10% discount rate. Coal remains a strong competitor to gas when lower discount rates are used. Nuclear is the least expensive at both 5 and 10% discount rate in only two countries. Generally, with gas prices above 5 US$/GJ, nuclear plants constructed at overnight capital costs below 1 650 $/kWe have the potential to be competitive only at lower discount rates.

  17. Check Estimates and Independent Costs

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    Check estimates and independent cost estimates (ICEs) are tools that can be used to validate a cost estimate. Estimate validation entails an objective review of the estimate to ensure that estimate criteria and requirements have been met and well documented, defensible estimate has been developed. This chapter describes check estimates and their procedures and various types of independent cost estimates.

  18. Hydropower Baseline Cost Modeling

    SciTech Connect (OSTI)

    O'Connor, Patrick W.; Zhang, Qin Fen; DeNeale, Scott T.; Chalise, Dol Raj; Centurion, Emma E.

    2015-01-01

    Recent resource assessments conducted by the United States Department of Energy have identified significant opportunities for expanding hydropower generation through the addition of power to non-powered dams and on undeveloped stream-reaches. Additional interest exists in the powering of existing water resource infrastructure such as conduits and canals, upgrading and expanding existing hydropower facilities, and the construction new pumped storage hydropower. Understanding the potential future role of these hydropower resources in the nation’s energy system requires an assessment of the environmental and techno-economic issues associated with expanding hydropower generation. To facilitate these assessments, this report seeks to fill the current gaps in publically available hydropower cost-estimating tools that can support the national-scale evaluation of hydropower resources.

  19. A Second Opinion is Worth the Cost - 12479

    SciTech Connect (OSTI)

    Madsen, Drew

    2012-07-01

    This paper, 'A Second Opinion is Worth the Cost', shows how a second opinion for a Department of Energy (DOE) Project helped prepare and pass a DOE Order 413.3A 'Program and Project Management for the acquisition of Capital Assets' Office of Engineering and Construction Management (OECM) required External Independent Review (EIR) in support of the approved baseline for Critical Decision (CD) 2. The DOE project personnel were informed that the project's Total Project Cost (TPC) was going to increase from $815 million to $1.1 billion due to unforeseen problems and unexplained reasons. The DOE Project Team determined that a second opinion was needed to review and validate the TPC. Project Time and Cost, Inc. (PT and C) was requested to evaluate the cost estimate, schedule, basis of estimate (BOE), and risk management plan of the Project and to give an independent assessment of the TPC that was presented to DOE. This paper will demonstrate how breaking down a project to the work breakdown structure (WBS) level allows a project to be analyzed for potential cost increases and/or decreases, thus providing a more accurate TPC. The review Team's cost analyses of Projects identified eight primary drivers resulting in cost increases. They included: - Overstatement of the effort required to develop drawings and specifications. - Cost allocation to 'Miscellaneous' without sufficient detail or documentation. - Cost for duplicated efforts. - Vendor estimates or quotations without sufficient detail. - The practice of using the highest price quoted then adding an additional 10% mark-up. - Application of Nuclear Quality Assurance (NQA) highest level quality requirements when not required. - Allocation of operational costs to the Project Costs instead of to the Operating Expenses (OPEX). OPEX costs come from a different funding source. - DOE had not approved the activities. By using a Team approach with professionals from cost, civil, mechanical, electrical, structural and nuclear

  20. Analysis of the Production Cost for Various Grades of Biomass Thermal Treatment

    SciTech Connect (OSTI)

    Robert S Cherry; Rick A. Wood; Tyler L Westover

    2013-12-01

    Process flow sheets were developed for the thermal treatment of southern pine wood chips at four temperatures (150, 180, 230, and 270 degrees C) and two different scales (20 and 100 ton/hour). The larger capacity processes had as their primary heat source hot gas assumed to be available in quantity from an adjacent biorefinery. Mass and energy balances for these flow sheets were developed using Aspen Plus process simulation software. The hot gas demands in the larger processes, up to 1.9 million lb/hour, were of questionable feasibility because of the volume to be moved. This heat was of low utility because the torrefaction process, especially at higher temperatures, is a net heat producer if the organic byproduct gases are burned. A thermal treatment flow sheet using wood chips dried in the biorefinery to 10% moisture content (rather than 30% for green chips) with transfer of high temperature steam from the thermal treatment depot to the biorefinery was also examined. The equipment size information from all of these cases was used in several different equipment cost estimating methods to estimate the major equipment costs for each process. From these, factored estimates of other plant costs were determined, leading to estimates (+ / - 30% accuracy) of total plant capital cost. The 20 ton/hour processes were close to 25 million dollars except for the 230 degrees C case using dried wood chips which was only 15 million dollars because of its small furnace. The larger processes ranged from 64-120 million dollars. From these capital costs and projections of several categories of operating costs, the processing cost of thermally treated pine chips was found to be $28-33 per ton depending on the degree of treatment and without any credits for steam generation. If the excess energy output of the two 20 ton/hr depot cases at 270 degrees C can be sold for $10 per million BTU, the net processing cost dropped to $13/ton product starting with green wood chips or only $3 per