National Library of Energy BETA

Sample records for acceptance test plan

  1. SAPHIRE 8 Software Acceptance Test Plan

    SciTech Connect (OSTI)

    Ted S. Wood; Curtis L. Smith

    2009-07-01

    This document describe & report the overall SAPHIRE 8 Software acceptance test paln to offically release the SAPHIRE version 8 software to the NRC custoer for distribution.

  2. Electromagnetic induction moisture measurement system acceptance test plan

    SciTech Connect (OSTI)

    Vargo, G.F., Westinghouse Hanford

    1996-08-01

    The purpose of this acceptance test plan (ATP) is to verify that the mechanical, electrical and software features of the ElectroMagnetic Induction (EMI) probe are operating as designed,and that the unit is ready for field service. The accepted EMI and Surface Moisture Measurement Systems (SMMS) will be used primarily in support of Tank Waste Remediation System (TWRS) Safety Programs for moisture measurement of organic and ferrocyanide watch list tanks.

  3. W-026 acceptance test plan plant control system hardware (submittal {number_sign} 216)

    SciTech Connect (OSTI)

    Watson, T.L., Fluor Daniel Hanford

    1997-02-14

    Acceptance Testing of the WRAP 1 Plant Control System Hardware will be conducted throughout the construction of WRAP I with the final testing on the Process Area hardware being completed in November 1996. The hardware tests will be broken out by the following functional areas; Local Control Units, Operator Control Stations in the WRAP Control Room, DMS Server, PCS Server, Operator Interface Units, printers, DNS terminals, WRAP Local Area Network/Communications, and bar code equipment. This document will contain completed copies of each of the hardware tests along with the applicable test logs and completed test exception reports.

  4. Syringe Pump Factory Acceptance Testing Review

    E-Print Network [OSTI]

    McDonald, Kirk

    Syringe Pump Factory Acceptance Testing Review V.B. Graves MERIT VRVS Meeting April 5, 2006 #12;2VRVS Meeting 5 Apr 2006 Acceptance Testing of Syringe Pump Completed · Factory acceptance testing of syringe pump completed March 30 at Airline Hydraulics Corp (AHC) Bensalem, PA facility · Test plan

  5. Independent Verification and Validation Of SAPHIRE 8 Software Acceptance Test Plan Project Number: N6423 U.S. Nuclear Regulatory Commission

    SciTech Connect (OSTI)

    Kent Norris

    2010-03-01

    The purpose of the Independent Verification and Validation (IV&V) role in the evaluation of the SAPHIRE 8 Software Acceptance Test Plan is to assess the approach to be taken for intended testing activities. The plan typically identifies the items to be tested, the requirements being tested, the testing to be performed, test schedules, personnel requirements, reporting requirements, evaluation criteria, and any risks requiring contingency planning. The IV&V team began this endeavor after the software engineering and software development of SAPHIRE had already been in production.

  6. Nevada Test Site Waste Acceptance Criteria (NTSWAC)

    SciTech Connect (OSTI)

    NNSA /NSO Waste Management Project

    2008-06-01

    This document establishes the U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office, Nevada Test Site Waste Acceptance Criteria (NTSWAC). The NTSWAC provides the requirements, terms, and conditions under which the Nevada Test Site will accept low-level radioactive (LLW) and LLW Mixed Waste (MW) for disposal.

  7. Nevada Test Site Waste Acceptance Criteria

    SciTech Connect (OSTI)

    U.S. Department of Energy, Nevada Operations Office, Waste Acceptance Criteria

    1999-05-01

    This document provides the requirements, terms, and conditions under which the Nevada Test Site will accept low-level radioactive and mixed waste for disposal; and transuranic and transuranic mixed waste for interim storage at the Nevada Test Site.

  8. NEVADA TEST SITE WASTE ACCEPTANCE CRITERIA

    SciTech Connect (OSTI)

    U.S. DEPARTMENT OF ENERGY, NATIONAL NUCLEAR SECURITY ADMINISTRATION, NEVADA SITE OFFICE

    2005-07-01

    This document establishes the U. S. Department of Energy, National Nuclear Security Administration Nevada Site Office (NNSA/NSO) waste acceptance criteria (WAC). The WAC provides the requirements, terms, and conditions under which the Nevada Test Site will accept low-level radioactive and mixed waste for disposal. Mixed waste generated within the State of Nevada by NNSA/NSO activities is accepted for disposal. It includes requirements for the generator waste certification program, characterization, traceability, waste form, packaging, and transfer. The criteria apply to radioactive waste received at the Nevada Test Site Area 3 and Area 5 Radioactive Waste Management Site for storage or disposal.

  9. Nevada Test Site Waste Acceptance Criteria

    SciTech Connect (OSTI)

    U. S. Department of Energy, National Nuclear Security Administration Nevada Site Office

    2005-10-01

    This document establishes the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office (NNSA/NSO) waste acceptance criteria (WAC). The WAC provides the requirements, terms, and conditions under which the Nevada Test Site (NTS) will accept low-level radioactive (LLW) and mixed waste (MW) for disposal. It includes requirements for the generator waste certification program, characterization, traceability, waste form, packaging, and transfer. The criteria apply to radioactive waste received at the NTS Area 3 and Area 5 Radioactive Waste Management Complex (RWMC) for storage or disposal.

  10. Nevada test site waste acceptance criteria

    SciTech Connect (OSTI)

    NONE

    1996-09-01

    This document provides the requirements, terms, and conditions under which the Nevada Test Site (NTS) will accept low-level radioactive and mixed waste for disposal; and transuranic and transuranic mixed waste for interim storage at the NTS. Review each section of this document. This document is not intended to include all of the requirements; rather, it is meant as a guide toward meeting the regulations. All references in this document should be observed to avoid omission of requirements on which acceptance or rejection of waste will be based. The Department of Energy/Nevada Operations Office (DOE/NV) and support contractors are available to assist you in understanding or interpreting this document.

  11. LMS Qualification and Flight Acceptance T /V Test Summary

    E-Print Network [OSTI]

    Rathbun, Julie A.

    LMS Qualification and Flight Acceptance T /V Test Summary and Thermal Design Final Report NO. ATMIIIIDe yablinaDhllalan LMS Qualification and Flight Acceptance T/V Test Summary and Thermal Design Final Report PAGI DATI SUMMARY The LMS maintains thermal control. within the -10 to +125°F operating temperature

  12. Rotary mode core sampling service trailer acceptance test report

    SciTech Connect (OSTI)

    Kostelnik, A.J.

    1996-02-12

    This Acceptance Test Report documents compliance with the requirements of specification WHC-S-056. The equipment was tested according to WHC-SD-WM-ATP-111 Rev.1.

  13. Acceptance Test Procedure for New Pumping Instrumentation & Control Skid V

    SciTech Connect (OSTI)

    KOCH, M.R.

    2000-08-14

    This Acceptance Test Procedure (ATP) provides for the inspection and testing of the new Pumping Instrumentation and Control (PIC) skid designated as ''V''. The ATP will be performed after the construction of the PIC skid in the fabrication shop.

  14. Acceptance test report for core sample trucks 3 and 4

    SciTech Connect (OSTI)

    Corbett, J.E.

    1996-04-10

    The purpose of this Acceptance Test Report is to provide documentation for the acceptance testing of the rotary mode core sample trucks 3 and 4, designated as HO-68K-4600 and HO-68K-4647, respectively. This report conforms to the guidelines established in WHC-IP-1026, ``Engineering Practice Guidelines,`` Appendix M, ``Acceptance Test Procedures and Reports.`` Rotary mode core sample trucks 3 and 4 were based upon the design of the second core sample truck (HO-68K-4345) which was constructed to implement rotary mode sampling of the waste tanks at Hanford. Successful completion of acceptance testing on June 30, 1995 verified that all design requirements were met. This report is divided into four sections, beginning with general information. Acceptance testing was performed on trucks 3 and 4 during the months of March through June, 1995. All testing was performed at the ``Rock Slinger`` test site in the 200 West area. The sequence of testing was determined by equipment availability, and the initial revision of the Acceptance Test Procedure (ATP) was used for both trucks. Testing was directed by ICF-KH, with the support of WHC Characterization Equipment Engineering and Characterization Project Operations. Testing was completed per the ATP without discrepancies or deviations, except as noted.

  15. Testing for a Conformance Relation Based on Acceptance*

    E-Print Network [OSTI]

    von Bochmann, Gregor

    Testing for a Conformance Relation Based on Acceptance* MingYu Yao and Gregorv. Bochmann D6 been gaining wide popularity in recent years, little work has been done on how to test object- oriented will also play important roles during the testing phase. In this paper, we propose a conformance testing

  16. ASME PTC 46 -- Acceptance test code for overall plant performance

    SciTech Connect (OSTI)

    Friedman, J.R. [Siemens-Westinghouse Power Corp., Orlando, FL (United States); Yost, J.G. [Sargent and Lundy, Chicago, IL (United States)

    1999-11-01

    ASME published PTC 46 in 1996 after five years of development. PTC 46 is the first industry standard providing explicit procedures for conducting acceptance tests to determine the overall thermal performance and output of power generating units. It is applicable to any heat cycle power generating unit. This survey paper provides an overview of PTC 46 and discusses how PTC 46 can be used for acceptance testing of new combined cycle and fossil steam power generating units. Several technical papers have been previously presented that provide more detailed information and discussion on the use of PTC 46 in acceptance testing.

  17. Product acceptance environmental and destructive testing for reliability.

    SciTech Connect (OSTI)

    Dvorack, Michael A.; Kerschen, Thomas J.; Collins, Elmer W.

    2007-08-01

    To determine whether a component is meeting its reliability requirement during production, acceptance sampling is employed in which selected units coming off the production line are subjected to additional environmental and/or destructive tests that are within the normal environment space to which the component is expected to be exposed throughout its life in the Stockpile. This report describes what these tests are and how they are scored for reliability purposes. The roles of screens, Engineering Use Only tests, and next assembly product acceptance testing are also discussed, along with both the advantages and disadvantages of environmental and destructive testing.

  18. WRAP low level waste (LLW) glovebox acceptance test report

    SciTech Connect (OSTI)

    Leist, K.J.

    1998-02-17

    In June 28, 1997, the Low Level Waste (LLW) glovebox was tested using glovebox acceptance test procedure 13031A-85. The primary focus of the glovebox acceptance test was to examine control system interlocks, display menus, alarms, and operator messages. Limited mechanical testing involving the drum ports, hoists, drum lifter, compacted drum lifter, drum tipper, transfer car, conveyors, lidder/delidder device and the supercompactor were also conducted. As of November 24, 1997, 2 of the 131 test exceptions that affect the LLW glovebox remain open. These items will be tracked and closed via the WRAP Master Test Exception Database. As part of Test Exception resolution/closure the responsible individual closing the Test Exception performs a retest of the affected item(s) to ensure the identified deficiency is corrected, and, or to test items not previously available to support testing. Test Exceptions are provided as appendices to this report.

  19. Operator coil monitoring acceptance test procedure

    SciTech Connect (OSTI)

    Erhart, M.F.

    1995-06-05

    The readiness of the Data Acquisition and Control System (DACS) to provide monitoring and control of the Programmable Logic Controller (PLC) abort coils from the Master and RSS stations will be systematically tested during performance of this procedure. It should be noted that these are not physical abort coils but software coils controlled by the software`s ladder logic. The readiness of the DACS to properly interface with the ENRAF wire level gauge installed in the SY101 storage tank will also be tested. During this test, a verification of all abort coil indications will be conducted at the DACS Development Facility in the 306E Building by injecting an input signal for each DACS sensor that has an associated abort coil until the abort coil actuates, and then ensuring that the status of the abort coil indicated at the Master and RSS stations correct. Each abort coil will also be tested to ensure that the ``ENABLE`` and ``DISABLE`` controls from the Master and RSS stations function correctly, and only with the use of proper passwords.

  20. Operator coil monitoring Acceptance Test Procedure

    SciTech Connect (OSTI)

    Erhart, M.F.

    1995-05-16

    The readiness of the Data Acquisition and Control System (DACS) to provide monitoring and control of the Programmable Logic Controller (PLC) abort coils from the Master and RSS stations will be systematically tested during performance of this procedure. It should be noted that these are not physical abort coils but software coils controlled by the software`s ladder logic. The readiness of the DACS to properly interface with the ENRAF wire level gauge installed in the SY-101 storage tank will also be tested. During this test, a verification of all abort coil indications will be conducted at the DACS Development Facility in the 306E Building by injecting an input signal for each DACS sensor that has an associated abort coil until the abort coil actuates, and then ensuring that the status of the abort coil indicated at the Master and RSS stations is correct. Each abort coil will also be tested to ensure that the ``ENABLE`` and ``DISABLE`` controls from the Master and RSS stations function correctly, and only with the use of proper passwords.

  1. Project W-320 acceptance test report for AY-farm electrical distribution

    SciTech Connect (OSTI)

    Bevins, R.R.

    1998-04-02

    This Acceptance Test Procedure (ATP) has been prepared to demonstrate that the AY-Farm Electrical Distribution System functions as required by the design criteria. This test is divided into three parts to support the planned construction schedule; Section 8 tests Mini-Power Pane AY102-PPI and the EES; Section 9 tests the SSS support systems; Section 10 tests the SSS and the Multi-Pak Group Control Panel. This test does not include the operation of end-use components (loads) supplied from the distribution system. Tests of the end-use components (loads) will be performed by other W-320 ATPs.

  2. The Murmansk Initiative - RF: Acceptance Testing

    SciTech Connect (OSTI)

    Czajkowski, C.; Wester, D. W.; Dyer, R. S.; Soerlie, A. A.; Moller, B.; Barnes, E.

    2002-02-26

    The Murmansk Initiative-RF (MI) was conceived to provide the Russian Federation (RF) with the capacity to manage low-level liquid radioactive waste (LLRW) and comply with the requirements of the London Convention that prohibit ocean dumping. The trilateral project among Norway, the RF, and the United States of America (U.S.) began in 1994 and was the first to utilize exclusively Russian subcontractors to upgrade and expand an existing LLRW treatment plant on the premises of RTP Atomflot in Murmansk, Russia. The project moved quickly through the design phase. Progress during the construction phase was somewhat slower because of difficulties with acquisition of hardware, inexperience with automated instrumentation and control equipment, and unexpected design changes in the cementation unit. The project advanced into the test-operation phase, which is currently underway, in June 2001. Initial runs with liquid waste have revealed that procedures for unloading spent ion-exchange sorbents could be improved and that sludges formed during removal of alkaline-earth metals should be compacted in order for the facility to operate at its full potential. Resolution of these issues is expected within the next few months.

  3. Vendor System Vulnerability Testing Test Plan

    SciTech Connect (OSTI)

    James R. Davidson

    2005-01-01

    The Idaho National Laboratory (INL) prepared this generic test plan to provide clients (vendors, end users, program sponsors, etc.) with a sense of the scope and depth of vulnerability testing performed at the INL’s Supervisory Control and Data Acquisition (SCADA) Test Bed and to serve as an example of such a plan. Although this test plan specifically addresses vulnerability testing of systems applied to the energy sector (electric/power transmission and distribution and oil and gas systems), it is generic enough to be applied to control systems used in other critical infrastructures such as the transportation sector, water/waste water sector, or hazardous chemical production facilities. The SCADA Test Bed is established at the INL as a testing environment to evaluate the security vulnerabilities of SCADA systems, energy management systems (EMS), and distributed control systems. It now supports multiple programs sponsored by the U.S. Department of Energy, the U.S. Department of Homeland Security, other government agencies, and private sector clients. This particular test plan applies to testing conducted on a SCADA/EMS provided by a vendor. Before performing detailed vulnerability testing of a SCADA/EMS, an as delivered baseline examination of the system is conducted, to establish a starting point for all-subsequent testing. The series of baseline tests document factory delivered defaults, system configuration, and potential configuration changes to aid in the development of a security plan for in depth vulnerability testing. The baseline test document is provided to the System Provider,a who evaluates the baseline report and provides recommendations to the system configuration to enhance the security profile of the baseline system. Vulnerability testing is then conducted at the SCADA Test Bed, which provides an in-depth security analysis of the Vendor’s system.b a. The term System Provider replaces the name of the company/organization providing the system being evaluated. This can be the system manufacturer, a system user, or a third party organization such as a government agency. b. The term Vendor (or Vendor’s) System replaces the name of the specific SCADA/EMS being tested.

  4. ISOLOK VALVE ACCEPTANCE TESTING FOR DWPF SME SAMPLING PROCESS

    SciTech Connect (OSTI)

    Edwards, T.; Hera, K.; Coleman, C.; Jones, M.; Wiedenman, B.

    2011-12-05

    Evaluation of the Defense Waste Processing Facility (DWPF) Chemical Process Cell (CPC) cycle time identified several opportunities to improve the CPC processing time. Of the opportunities, a focus area related to optimizing the equipment and efficiency of the sample turnaround time for DWPF Analytical Laboratory was identified. The Mechanical Systems & Custom Equipment Development (MS&CED) Section of the Savannah River National Laboratory (SRNL) evaluated the possibility of using an Isolok{reg_sign} sampling valve as an alternative to the Hydragard{reg_sign} valve for taking process samples. Previous viability testing was conducted with favorable results using the Isolok sampler and reported in SRNL-STI-2010-00749 (1). This task has the potential to improve operability, reduce maintenance time and decrease CPC cycle time. This report summarizes the results from acceptance testing which was requested in Task Technical Request (TTR) HLW-DWPF-TTR-2010-0036 (2) and which was conducted as outlined in Task Technical and Quality Assurance Plan (TTQAP) SRNL-RP-2011-00145 (3). The Isolok to be tested is the same model which was tested, qualified, and installed in the Sludge Receipt Adjustment Tank (SRAT) sample system. RW-0333P QA requirements apply to this task. This task was to qualify the Isolok sampler for use in the DWPF Slurry Mix Evaporator (SME) sampling process. The Hydragard, which is the current baseline sampling method, was used for comparison to the Isolok sampling data. The Isolok sampler is an air powered grab sampler used to 'pull' a sample volume from a process line. The operation of the sampler is shown in Figure 1. The image on the left shows the Isolok's spool extended into the process line and the image on the right shows the sampler retracted and then dispensing the liquid into the sampling container. To determine tank homogeneity, a Coliwasa sampler was used to grab samples at a high and low location within the mixing tank. Data from the two locations were compared to determine if the contents of the tank were well mixed. The Coliwasa sampler is a tube with a stopper at the bottom and is designed to obtain grab samples from specific locations within the drum contents. A position paper (4) was issued to address the prototypic flow loop issues and simulant selections. A statistically designed plan (5) was issued to address the total number of samples each sampler needed to pull, to provide the random order in which samples were pulled and to group samples for elemental analysis. The TTR required that the Isolok sampler perform as well as the Hydragard sampler during these tests to ensure the acceptability of the Isolok sampler for use in the DWPF sampling cells. Procedure No.L9.4-5015 was used to document the sample parameters and process steps. Completed procedures are located in R&D Engineering job folder 23269.

  5. Gas characterization system 241-AN-105 field acceptance test procedure

    SciTech Connect (OSTI)

    Schneider, T.C.

    1996-03-01

    This document details the field Acceptance Testing of a gas characterization system being installed on waste tank 241-AN-105. The gas characterization systems will be used to monitor the vapor spaces of waste tanks known to contain measurable concentrations of flammable gases.

  6. Gas characterization system 241-AW-101 field acceptance test procedure

    SciTech Connect (OSTI)

    Schneider, T.C.

    1996-03-01

    This document details the field Acceptance Testing of a gas characterization system being installed on waste tank 241-AW-101. The gas characterization systems will be used to monitor the vapor spaces of waste tanks known to contain measurable concentrations of flammable gases.

  7. Startup of the FFTF sodium cooled reactor. [Acceptance Test Program

    SciTech Connect (OSTI)

    Redekopp, R.D.; Umek, A.M.

    1981-03-01

    The Fast Flux Test Facility (FFTF), located on the Department of Energy (DOE) Hanford Reservation near Richland, Washington, is a 3 Loop 400 MW(t) sodium cooled fast reactor with a primary mission to test fuels and materials for development of the Liquid Metal Fast Breeder Reactor (LMFBR). Bringing FFTF to a condition to accomplish this mission is the goal of the Acceptance Test Program (ATP). This program was the mechanism for achieving startup of the FFTF. Highlights of the ATP involving the system inerting, liquid metal and inerted cell testing and initial ascent to full power are discussed.

  8. NEVADA TEST SITE WASTE ACCEPTANCE CRITERIA, JUNE 2006

    SciTech Connect (OSTI)

    U.S. DEPARTMENT OF ENERGY, NATIONAL NUCLEAR SECURITY ADMINISTRATION NEVADA SITE OFFICE

    2006-06-01

    This document establishes the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office (NNSA/NSO) waste acceptance criteria (WAC). The WAC provides the requirements, terms, and conditions under which the Nevada Test Site (NTS) will accept low-level radioactive (LLW) and mixed waste (MW) for disposal. It includes requirements for the generator waste certification program, characterization, traceability, waste form, packaging, and transfer. The criteria apply to radioactive waste received at the NTS Area 3 and Area 5 Radioactive Waste Management Complex (RWMC) for storage or disposal.

  9. Central Acceptance Testing for Camera Technologies for CTA

    E-Print Network [OSTI]

    Bonardi, A; Chadwick, P; Dazzi, F; Förster, A; Hörandel, J R; Punch, M

    2015-01-01

    The Cherenkov Telescope Array (CTA) is an international initiative to build the next generation ground based very-high energy gamma-ray observatory. It will consist of telescopes of three different sizes, employing several different technologies for the cameras that detect the Cherenkov light from the observed air showers. In order to ensure the compliance of each camera technology with CTA requirements, CTA will perform central acceptance testing of each camera technology. To assist with this, the Camera Test Facilities (CTF) work package is developing a detailed test program covering the most important performance, stability, and durability requirements, including setting up the necessary equipment. Performance testing will include a wide range of tests like signal amplitude, time resolution, dead-time determination, trigger efficiency, performance testing under temperature and humidity variations and several others. These tests can be performed on fully-integrated cameras using a portable setup at the came...

  10. Test Report for Acceptance Test Procedure for Pumping and Instrumentation Control Skid ''K''

    SciTech Connect (OSTI)

    JOHNS, B.R.

    1999-10-28

    This is a Test Report for Acceptance Test Procedure (ATP) HNF-4276. This test report provides the results of the inspection and testing of the new Pumping and Instrumentation Control (PIC) skid designed as ''K''. The ATP was successfully completed. A copy of the completed ATP is in the Appendix of this document.

  11. Test Report for Acceptance Test Procedure for Pumping Instrumentation and Control Skid L

    SciTech Connect (OSTI)

    KOCH, M.R.

    1999-11-09

    This is a Test Report for Acceptance Test Procedure (ATP) RPP-5055. This test report provides the results of the inspection and testing of the new Pumping Instrumentation and Control (PIC) skid designed as ''L''. The ATP was successfully completed. A copy of the completed ATP is in the Appendix of this document.

  12. Test Report for Acceptance Test Procedure for Pumping Instrumentation and Control Skid N

    SciTech Connect (OSTI)

    KOCH, M.R.

    2000-02-03

    This is a Test Report for Acceptance Test Procedure (ATP) RPP-5489. This test report provides the results of the inspection and testing of the new Pumping Instrumentation and Control (PIC) skid designed as ''N''. The ATP was successfully completed. A copy of the completed ATP is in the Appendix of this document.

  13. Test Report for Acceptance Test Procedure for Pumping Instrumentation and Control Skid M

    SciTech Connect (OSTI)

    KOCH, M.R.

    1999-12-13

    This is a Test Report for Acceptance Test Procedure (ATP) RPP-5073. This test report provides the results of the inspection and testing of the new Pumping Instrumentation and Control (PIC) skid designed as ''M''. The ATP was successfully completed. A copy of the completed ATP is in the Appendix of this document.

  14. Secondary Waste Cast Stone Waste Form Qualification Testing Plan

    SciTech Connect (OSTI)

    Westsik, Joseph H.; Serne, R. Jeffrey

    2012-09-26

    The Hanford Tank Waste Treatment and Immobilization Plant (WTP) is being constructed to treat the 56 million gallons of radioactive waste stored in 177 underground tanks at the Hanford Site. The WTP includes a pretreatment facility to separate the wastes into high-level waste (HLW) and low-activity waste (LAW) fractions for vitrification and disposal. The LAW will be converted to glass for final disposal at the Integrated Disposal Facility (IDF). Cast Stone – a cementitious waste form, has been selected for solidification of this secondary waste stream after treatment in the ETF. The secondary-waste Cast Stone waste form must be acceptable for disposal in the IDF. This secondary waste Cast Stone waste form qualification testing plan outlines the testing of the waste form and immobilization process to demonstrate that the Cast Stone waste form can comply with the disposal requirements. Specifications for the secondary-waste Cast Stone waste form have not been established. For this testing plan, Cast Stone specifications are derived from specifications for the immobilized LAW glass in the WTP contract, the waste acceptance criteria for the IDF, and the waste acceptance criteria in the IDF Permit issued by the State of Washington. This testing plan outlines the testing needed to demonstrate that the waste form can comply with these waste form specifications and acceptance criteria. The testing program must also demonstrate that the immobilization process can be controlled to consistently provide an acceptable waste form product. This testing plan also outlines the testing needed to provide the technical basis for understanding the long-term performance of the waste form in the disposal environment. These waste form performance data are needed to support performance assessment analyses of the long-term environmental impact of the secondary-waste Cast Stone waste form in the IDF

  15. Nevada Test Site waste acceptance criteria [Revision 1

    SciTech Connect (OSTI)

    None

    1997-08-01

    Revision one updates the requirements, terms, and conditions under which the Nevada Test Site (NTS) will accept low-level radioactive and mixed waste for disposal; and transuranic and transuranic mixed waste for interim storage at the NTS. Review each section of this document. This document is not intended to include all of the requirements; rather, it is meant as a guide toward meeting the regulations. All references in this document should be observed to avoid omission of requirements on which acceptance or rejection of waste will be based. The Department of Energy/Nevada Operations Office (DOE/NV) and support contractors are available to assist you in understanding or interpreting this document.

  16. Test Report for Acceptance Test Procedure for Pumping Instrumentation and Control Skid P

    SciTech Connect (OSTI)

    KOCH, M.R.

    2000-03-29

    This Acceptance Test Report (ATR) provides the test results for the inspection and testing of the new Pumping Instrumentation and Control (PIC) skid designed as ''P''. The ATR summaries the results and provides a copy of the ATP and inspections in the Appendix.

  17. Test Report for Acceptance Test Procedure for Pumping Instrumentation and Control Skid Q

    SciTech Connect (OSTI)

    KOCH, M.R.

    2000-05-11

    This Acceptance Test Report (ATR) provides the test results for the inspection and testing of the new Pumping Instrumentation and Control (PIC) skid designed as ''Q''. The ATR summaries the results and provides a copy of the ATP and inspections in the Appendix.

  18. Acceptance and operability test report for the 327 building retention process sewer diverter station

    SciTech Connect (OSTI)

    Olander, A.R.

    1996-09-04

    This test report includes the results of acceptance and operability testing of the 327 building diverter station. The test included steps for flushing, calibrating, and operating the system on backup power.

  19. Acceptance {ampersand} operability test report for the 324 building retention process sewer diverter station

    SciTech Connect (OSTI)

    Olander, A.R.

    1996-09-04

    This test report includes the results of acceptance and operability testing of the 324 building diverter station. The test included steps for flushing, calibrating, and operating the system on backup power.

  20. LSPE Qualification and Flight Acceptance T /V Test Su.m..mary and Thermal Design

    E-Print Network [OSTI]

    Rathbun, Julie A.

    LSPE Qualification and Flight Acceptance T /V Test Su.m..mary and Thermal Design Final Report NO. ATM 1110 This ATM Summarizes the analytical and test results of the Lunar Seismic Profiling Experiment summarizes the Qualification and Flight Acceptance thermal vacuum testing programs and the third section

  1. Systems acceptance and operability testing for rotary mode core sampling in flammable gas tanks

    SciTech Connect (OSTI)

    Corbett, J.E., Westinghouse Hanford

    1996-07-29

    This document provides instructions for the system acceptance and operability testing of the rotary mode core sampling system, modified for use in flammable gas tanks.

  2. EVALUATION OF ARG-1 SAMPLES PREPARED BY CESIUM CARBONATE DISSOLUTION DURING THE ISOLOK SME ACCEPTABILITY TESTING

    SciTech Connect (OSTI)

    Edwards, T.; Hera, K.; Coleman, C.

    2011-12-05

    Evaluation of Defense Waste Processing Facility (DWPF) Chemical Process Cell (CPC) cycle time identified several opportunities to improve the CPC processing time. The Mechanical Systems & Custom Equipment Development (MS&CED) Section of the Savannah River National Laboratory (SRNL) recently completed the evaluation of one of these opportunities - the possibility of using an Isolok sampling valve as an alternative to the Hydragard valve for taking DWPF process samples at the Slurry Mix Evaporator (SME). The use of an Isolok for SME sampling has the potential to improve operability, reduce maintenance time, and decrease CPC cycle time. The SME acceptability testing for the Isolok was requested in Task Technical Request (TTR) HLW-DWPF-TTR-2010-0036 and was conducted as outlined in Task Technical and Quality Assurance Plan (TTQAP) SRNLRP-2011-00145. RW-0333P QA requirements applied to the task, and the results from the investigation were documented in SRNL-STI-2011-00693. Measurement of the chemical composition of study samples was a critical component of the SME acceptability testing of the Isolok. A sampling and analytical plan supported the investigation with the analytical plan directing that the study samples be prepared by a cesium carbonate (Cs{sub 2}CO{sub 3}) fusion dissolution method and analyzed by Inductively Coupled Plasma - Optical Emission Spectroscopy (ICP-OES). The use of the cesium carbonate preparation method for the Isolok testing provided an opportunity for an additional assessment of this dissolution method, which is being investigated as a potential replacement for the two methods (i.e., sodium peroxide fusion and mixed acid dissolution) that have been used at the DWPF for the analysis of SME samples. Earlier testing of the Cs{sub 2}CO{sub 3} method yielded promising results which led to a TTR from Savannah River Remediation, LLC (SRR) to SRNL for additional support and an associated TTQAP to direct the SRNL efforts. A technical report resulting from this work was issued that recommended that the mixed acid method be replaced by the Cs{sub 2}CO{sub 3} method for the measurement of magnesium (Mg), sodium (Na), and zirconium (Zr) with additional testing of the method by DWPF Laboratory being needed before further implementation of the Cs{sub 2}CO{sub 3} method at that laboratory. While the SME acceptability testing of the Isolok does not address any of the open issues remaining after the publication of the recommendation for the replacement of the mixed acid method by the Cs{sub 2}CO{sub 3} method (since those issues are to be addressed by the DWPF Laboratory), the Cs{sub 2}CO{sub 3} testing associated with the Isolok testing does provide additional insight into the performance of the method as conducted by SRNL. The performance is to be investigated by looking to the composition measurement data generated by the samples of a standard glass, the Analytical Reference Glass - 1 (ARG-1), that were prepared by the Cs{sub 2}CO{sub 3} method and included in the SME acceptability testing of the Isolok. The measurements of these samples were presented as part of the study results, but no statistical analysis of these measurements was conducted as part of those results. It is the purpose of this report to provide that analysis, which was supported using JMP Version 7.0.2.

  3. Phased Startup Initiative Phases 3 and 4 Test Plan and Test Specification (OCRWM)

    SciTech Connect (OSTI)

    PITNER, A.L.

    2000-02-28

    Construction for the Spent Nuclear Fuel (SNF) Project facilities is continuing per the Level III Baseline Schedule, and installation of the Fuel Retrieval System (FRS) and Integrated Water Treatment System (IWTS) in K West Basin is now complete. In order to accelerate the project, a phased start up strategy to initiate testing of the FRS and IWTS early in the overall project schedule was proposed (Williams 1999). Wilkinson (1999) expands the definition of the original proposal into four functional testing phases of the Phased Startup Initiative (PSI). Phases 1 and 2 are based on performing functional tests using dummy fuel. These tests are described in separate planning documents. This test plan provides overall guidance for Phase 3 and 4 tests, which are performed using actual irradiated N fuel assemblies. The overall objective of the Phase 3 and 4 testing is to verify how the FRS and IWTS respond while processing actual fuel. Conducting these tests early in the project schedule will allow identification and resolution of equipment and process problems before they become activities on the start-up critical path. The specific objectives of this test plan are to: (1) Define the test scope for the FRS and IWTS; (2) Provide detailed test requirements that can be used to write the specific test procedures; (3) Define data required and measurements to be taken. Where existing methods to obtain these do not exist, enough detail will be provided to define required additional equipment; and (4) Define specific test objectives and acceptance criteria.

  4. EMERGENCY RESPONSE PLAN DEVINE TEST SITE

    E-Print Network [OSTI]

    Texas at Austin, University of

    HSE MANUAL EMERGENCY RESPONSE PLAN DEVINE TEST SITE EXPLORATION GEOPHYSICS LAB FIELD SITE MEDINA THE UNIVERSITY OF TEXAS AT AUSTIN 1 #12;TABLE OF CONTENTS MEMORANDUM PAGE 3 MEDICAL EMERGENCY RESPONSE PLANS PAGE LIST OF CONTACTS ­ SITE MANAGERS AND EMERGENCY RESPONSE PAGE 20 CERTIFICATE OF COMPLETION PAGE 21 2 #12

  5. Acceptance Test Procedure for New Pumping and Instrumentation Control Skid L

    SciTech Connect (OSTI)

    KOCH, M.R.

    1999-10-11

    This Acceptance Test Procedure (ATP) provides for the inspection and testing of the new Pumping and Instrumentation Control (PIC) skid designed as ''L''. The ATP will be performed after the construction of the PIC skid in the shop.

  6. Acceptance Test Procedure for New Pumping Instrumentation and Control Skid T

    SciTech Connect (OSTI)

    KOCH, M.R.

    2000-05-18

    This Acceptance Test Procedure (ATP) provides for the inspection and testing Of the new Pumping Instrumentation and Control (PIC) skid designed as ''T''. The ATP will be performed after the construction of the PIC skid in the fabrication shop.

  7. Acceptance Test Procedure for New Pumping Instrumentation and Control Skid V

    SciTech Connect (OSTI)

    KOCH, M.R.

    2000-05-18

    This Acceptance Test Procedure (ATP) provides for the inspection and testing of the new Pumping Instrumentation and Control. (PIC) skid designed as ''V''. The ATP will be performed after the construction of the PIC skid in the fabrication shop.

  8. Acceptance Test Procedure for New Pumping Instrumentation and Control Skid Q

    SciTech Connect (OSTI)

    KOCH, M.R.

    2000-03-27

    This Acceptance Test Procedure (ATP) provides for the inspection and testing of the new Pumping Instrumentation and Control (PIC) skid designed as ''Q''. The ATP will be performed after the construction of the PIC skid in the fabrication shop.

  9. Acceptance Test Procedure for New Pumping Instrumentation and Control Skid R

    SciTech Connect (OSTI)

    KOCH, M.R.

    2000-05-11

    This Acceptance Test Procedure (ATP) provides for the inspection and testing of the new Pumping Instrumentation and Control (PIC) skid designed as ''R''. The ATP will be performed after the construction of the PIC skid in the fabrication shop.

  10. Acceptance Test Procedure for New Pumping Instrumentation and Control Skid W

    SciTech Connect (OSTI)

    KOCH, M.R.

    2000-05-18

    This Acceptance Test Procedure (ATP) provides for the inspection and testing of the new Pumping Instrumentation and Control (PIC) skid designed as ''W''. The ATP will be performed after the construction of the PIC skid in the fabrication shop.

  11. Acceptance Test Procedure for New Pumping Instrumentation and Control Skid T

    SciTech Connect (OSTI)

    KOCH, M.R.

    2000-06-20

    This Acceptance Test Procedure (ATP) provides for the inspection and testing of the new Pumping Instrumentation and Control (PIC) skid designated as ''T''. The ATP will be performed after the construction of the PIC skid in the fabrication shop.

  12. Acceptance Test Procedure for New Pumping Instrumentation and Control Skid P

    SciTech Connect (OSTI)

    KOCH, M.R.

    2000-03-01

    This Acceptance Test Procedure (ATP) provides for the inspection and testing of the new Pumping Instrumentation and Control (PIC) skid designed as ''P''. The ATP will be performed after the construction of the PIC skid in the fabrication shop.

  13. Acceptance Test Procedure for New Pumping and Instrumentation Control Skid N

    SciTech Connect (OSTI)

    KOCH, M.R.

    1999-12-13

    This Acceptance Test Procedure (ATP) provides for the inspection and testing of the new Pumping and Instrumentation Control (PIC) skid designed as ''N''. The ATP will be performed after the construction of the PIC skid in the shop.

  14. WRAP low level waste restricted waste management (LLW RWM) glovebox acceptance test report

    SciTech Connect (OSTI)

    Leist, K.J.

    1997-11-24

    On April 22, 1997, the Low Level Waste Restricted Waste Management (LLW RWM) glovebox was tested using acceptance test procedure 13027A-87. Mr. Robert L. Warmenhoven served as test director, Mr. Kendrick Leist acted as test operator and test witness, and Michael Lane provided miscellaneous software support. The primary focus of the glovebox acceptance test was to examine glovebox control system interlocks, operator Interface Unit (OIU) menus, alarms, and messages. Basic drum port and lift table control sequences were demonstrated. OIU menus, messages, and alarm sequences were examined, with few exceptions noted. Barcode testing was bypassed, due to the lack of installed equipment as well as the switch from basic reliance on fixed bar code readers to the enhanced use of portable bar code readers. Bar code testing was completed during performance of the LLW RWM OTP. Mechanical and control deficiencies were documented as Test Exceptions during performance of this Acceptance Test. These items are attached as Appendix A to this report.

  15. Test Methods Standing Technical Committee Strategic Plan - February...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Test Methods Standing Technical Committee Strategic Plan - February 2012 Test Methods Standing Technical Committee Strategic Plan - February 2012 This document outlines gaps,...

  16. Test Plan for Solvent Extraction Data Acquisition to Support...

    Office of Scientific and Technical Information (OSTI)

    Technical Report: Test Plan for Solvent Extraction Data Acquisition to Support Modeling Efforts Citation Details In-Document Search Title: Test Plan for Solvent Extraction Data...

  17. Acceptance test report for the Tank 241-C-106 in-tank imaging system

    SciTech Connect (OSTI)

    Pedersen, L.T.

    1998-05-22

    This document presents the results of Acceptance Testing of the 241-C-106 in-tank video camera imaging system. The purpose of this imaging system is to monitor the Project W-320 sluicing of Tank 241-C-106. The objective of acceptance testing of the 241-C-106 video camera system was to verify that all equipment and components function in accordance with procurement specification requirements and original equipment manufacturer`s (OEM) specifications. This document reports the results of the testing.

  18. Phase Startup Initiative Phases 3 and 4 Test Plan and Test Specification ( OCRWM)

    SciTech Connect (OSTI)

    PAJUNEN, A.L.; LANGEVIN, M.J.

    2000-08-07

    Construction for the Spent Nuclear Fuel (SNF) Project facilities is continuing per the Level III Baseline Schedule, and installation of the Fuel Retrieval System (FRS) and Integrated Water Treatment System (IWTS) in K West Basin is now complete. In order to accelerate the project, a phased start up strategy to initiate testing of the FRS and IWTS early in the overall project schedule was proposed (Williams 1999). Wilkinson (1999) expands the definition of the original proposal into four functional testing phases of the Phased Startup Initiative (PSI). Phases 1 and 2 are based on performing functional tests using dummy fuel. This test plan provides overall guidance for Phase 3 and 4 tests, which are performed using actual irradiated N fuel assemblies. The overall objective of the Phase 3 and 4 testing is to verify how the FRS and IWTS respond while processing actual fuel. Conducting these tests early in the project schedule will allow identification and resolution of equipment and process problems before they become activities on the start-up critical path. The specific objectives of this test plan are to: Define the Phase 3 and 4 test scope for the FRS and IWTS; Provide detailed test requirements that can be used to write the specific test procedures; Define data required and measurements to be taken. Where existing methods to obtain these do not exist, enough detail will be provided to define required additional equipment; and Define specific test objectives and acceptance criteria.

  19. Waste retrieval sluicing system data acquisition system acceptance test report

    SciTech Connect (OSTI)

    Bevins, R.R.

    1998-07-31

    This document describes the test procedure for the Project W-320 Tank C-106 Sluicing Data Acquisition System (W-320 DAS). The Software Test portion will test items identified in the WRSS DAS System Description (SD), HNF-2115. Traceability to HNF-2115 will be via a reference that follows in parenthesis, after the test section title. The Field Test portion will test sensor operability, analog to digital conversion, and alarm setpoints for field instrumentation. The W-320 DAS supplies data to assist thermal modeling of tanks 241-C-106 and 241-AY-102. It is designed to be a central repository for information from sources that would otherwise have to be read, recorded, and integrated manually. Thus, completion of the DAS requires communication with several different data collection devices and output to a usable PC data formats. This test procedure will demonstrate that the DAS functions as required by the project requirements stated in Section 3 of the W-320 DAS System Description, HNF-2115.

  20. Building Energy Simulation Test for Existing Homes (BESTEST-EX): Instructions for Implementing the Test Procedure, Calibration Test Reference Results, and Example Acceptance-Range Criteria

    SciTech Connect (OSTI)

    Judkoff, R.; Polly, B.; Bianchi, M.; Neymark, J.; Kennedy, M.

    2011-08-01

    This publication summarizes building energy simulation test for existing homes (BESTEST-EX): instructions for implementing the test procedure, calibration tests reference results, and example acceptance-range criteria.

  1. Test Plan - Solids Accumulation Scouting Studies

    SciTech Connect (OSTI)

    Duignan, M. R.; Steeper, T. J.; Steimke, J. L.; Fowley, M. D.

    2012-05-10

    This plan documents the highlights of the Solids Accumulations Scouting Studies test; a project, from Washington River Protection Solutions (WRPS), that began on February 1, 2012. During the last 12 weeks considerable progress has been made to design and plan methods that will be used to estimate the concentration and distribution of heavy fissile solids in accumulated solids in the Hanford double-shell tank (DST) 241-AW-105 (AW-105), which is the primary goal of this task. This DST will be one of the several waste feed delivery staging tanks designated to feed the Pretreatment Facility (PTF) of the Waste Treatment and Immobilization Plant (WTP). Note that over the length of the waste feed delivery mission AW-105 is currently identified as having the most fill empty cycles of any DST feed tanks, which is the reason for modeling this particular tank. At SRNL an existing test facility, the Mixing Demonstration Tank, which will be modified for the present work, will use stainless steel particles in a simulant that represents Hanford waste to perform mock staging tanks transfers that will allow solids to accumulate in the tank heel. The concentration and location of the mock fissile particles will be measured in these scoping studies to produce information that will be used to better plan larger scaled tests. Included in these studies is a secondary goal of developing measurement methods to accomplish the primary goal. These methods will be evaluated for use in the larger scale experiments. Included in this plan are the several pretest activities that will validate the measurement techniques that are currently in various phases of construction. Aspects of each technique, e.g., particle separations, volume determinations, topographical mapping, and core sampling, have been tested in bench-top trials, as discussed herein, but the actual equipment to be employed during the full test will need evaluation after fabrication and integration into the test facility.

  2. Project B610 process control configuration acceptance test procedure

    SciTech Connect (OSTI)

    Silvan, G.R.

    1994-09-20

    The purpose of this test is to verify the Westinghouse configuration of the MICON A/S Distributed Control System for project B610. The following will be verified: proper assignment and operation of all field inputs to and outputs from the MICON Termination panels; proper operation of all display data on the operator`s console; proper operation of all required alarms; and proper operation of all required interlocks. The MICON A/S control system is configured to replace all the control, indication, and alarm panels now located in the Power Control Room. Nine systems are covered by this control configuration, 2736-ZB HVAC, 234-5Z HVAC, Process Vacuum, Dry Air, 291-Z Closed Loop Cooling, Building Accelerometer, Evacuation Siren, Stack CAMs, and Fire. The 2736-ZB HVAC system consists of the ventilation controls for 2736-ZB and 2736-Z as well as alarms for the emergency generators and 232-Z. The 234-5Z HVAC system is the ventilation controls for 235-5Z and 236-Z buildings. Process Vacuum covers the controls for the 26 inch vacuum system. Dry Air covers the controls for the steam and electric air dryers. The 291-Z Closed Loop Cooling system consists of the status indications and alarms for the 291-Z compressor and vacuum pump closed loop cooling system. The rest of closed loop cooling was tested earlier. The Building Accelerometer system consists of the status indications for the two seismic system accelerometers. The Evacuation Siren system includes the controls for the evacuation and take cover sirens. Stack CAMs cover the alarms for the various building ventilation stack continuous air monitors. Finally, the Fire system covers the various fire alarms now located in Room 321-A.

  3. Acceptance Test Procedure for New Pumping Instrumentation and Control Skid V

    SciTech Connect (OSTI)

    KOCH, M.R.

    2000-07-25

    This Acceptance Test Procedure (ATP) verifies proper construction per the design drawings and tests for proper functioning of the Pumping Instrumentation and Control (PIC) skid ''V''. The scope section lists the systems and functions to be checked. This ATP will be performed at the Site Fabrication Services (SFS) shop upon completion of the construction of the PIC skid.

  4. Acceptance Test Procedure for New Pumping and Instrumentation Control Skid M

    SciTech Connect (OSTI)

    KOCH, M.R.

    1999-11-09

    This Acceptance Test Procedure (ATP) verifies proper construction per the design drawings and tests for proper functioning of the Pumping and Instrumentation Control (PIC) skid ''M''. The Scope section lists the systems and functions to be checked. This ATP will be performed at the Site Fabrication Service's (SFS) shop upon completion of construction of the PIC skid.

  5. Test Plan: WIPP bin-scale CH TRU waste tests

    SciTech Connect (OSTI)

    Molecke, M.A.

    1990-08-01

    This WIPP Bin-Scale CH TRU Waste Test program described herein will provide relevant composition and kinetic rate data on gas generation and consumption resulting from TRU waste degradation, as impacted by synergistic interactions due to multiple degradation modes, waste form preparation, long-term repository environmental effects, engineered barrier materials, and, possibly, engineered modifications to be developed. Similar data on waste-brine leachate compositions and potentially hazardous volatile organic compounds released by the wastes will also be provided. The quantitative data output from these tests and associated technical expertise are required by the WIPP Performance Assessment (PA) program studies, and for the scientific benefit of the overall WIPP project. This Test Plan describes the necessary scientific and technical aspects, justifications, and rational for successfully initiating and conducting the WIPP Bin-Scale CH TRU Waste Test program. This Test Plan is the controlling scientific design definition and overall requirements document for this WIPP in situ test, as defined by Sandia National Laboratories (SNL), scientific advisor to the US Department of Energy, WIPP Project Office (DOE/WPO). 55 refs., 16 figs., 19 tabs.

  6. TESTING AND ACCEPTANCE OF FUEL PLATES FOR RERTR FUEL DEVELOPMENT EXPERIMENTS

    SciTech Connect (OSTI)

    J.M. Wight; G.A. Moore; S.C. Taylor

    2008-10-01

    This paper discusses how candidate fuel plates for RERTR Fuel Development experiments are examined and tested for acceptance prior to reactor insertion. These tests include destructive and nondestructive examinations (DE and NDE). The DE includes blister annealing for dispersion fuel plates, bend testing of adjacent cladding, and microscopic examination of archive fuel plates. The NDE includes Ultrasonic (UT) scanning and radiography. UT tests include an ultrasonic scan for areas of “debonds” and a high frequency ultrasonic scan to determine the "minimum cladding" over the fuel. Radiography inspections include identifying fuel outside of the maximum fuel zone and measurements and calculations for fuel density. Details of each test are provided and acceptance criteria are defined. These tests help to provide a high level of confidence the fuel plate will perform in the reactor without a breach in the cladding.

  7. Nevada Test Site Waste Acceptance Criteria (NTSWAC), Rev. 7-01

    SciTech Connect (OSTI)

    NSTec Environmental Management

    2009-05-01

    This document establishes the U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office, Nevada Test Site Waste Acceptance Criteria (NTSWAC). The NTSWAC provides the requirements, terms, and conditions under which the Nevada Test Site (NTS) will accept low-level radioactive waste and mixed low-level waste for disposal. The NTSWAC includes requirements for the generator waste certification program, characterization, traceability, waste form, packaging, and transfer. The criteria apply to radioactive waste received at the NTS Area 3 and Area 5 Radioactive Waste Management Complex for disposal.

  8. 118-B-1 excavation treatability test plan

    SciTech Connect (OSTI)

    Not Available

    1994-07-01

    The Hanford 118-B-1 Burial Ground Treatability Study has been required by milestone change request {number_sign}M-15-93-04, dated September 30, 1993. The change request requires that a treatability test be conducted at the 100-B Area to obtain additional engineering information for remedial design of burial grounds receiving waste from 100 Area removal actions. This treatability study has two purposes: (1) to support development of the Proposed Plan (PP) and Record of Decision (ROD), which will identify the approach to be used for burial ground remediation, and (2) to provide specific engineering information for receiving waste generated from the 100 Area removal actions. Data generated from this test also will provide critical performance and cost information necessary for remedy evaluation in the detailed analysis of alternatives during preparation of the focused feasibility study (FFS). This treatability testing supports the following 100 Area alternatives: (1) excavation and disposal, and (2) excavation, sorting, (treatment), and disposal.

  9. AGA 12, Part 2 Performance Test Plan (November 2006) | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AGA 12, Part 2 Performance Test Plan (November 2006) AGA 12, Part 2 Performance Test Plan (November 2006) Under the guidance and sponsorship of DOE's Office of Electricity Delivery...

  10. Utility-Scale Power Tower Solar Systems: Performance Acceptance Test Guidelines

    SciTech Connect (OSTI)

    Kearney, D.

    2013-03-01

    The purpose of these Guidelines is to provide direction for conducting performance acceptance testing for large power tower solar systems that can yield results of a high level of accuracy consistent with good engineering knowledge and practice. The recommendations have been developed under a National Renewable Energy Laboratory (NREL) subcontract and reviewed by stakeholders representing concerned organizations and interests throughout the concentrating solar power (CSP) community. An earlier NREL report provided similar guidelines for parabolic trough systems. These Guidelines recommend certain methods, instrumentation, equipment operating requirements, and calculation methods. When tests are run in accordance with these Guidelines, we expect that the test results will yield a valid indication of the actual performance of the tested equipment. But these are only recommendations--to be carefully considered by the contractual parties involved in the Acceptance Tests--and we expect that modifications may be required to fit the particular characteristics of a specific project.

  11. Test Plan to Assess Electric Vehicle Cell Degradation under Electric

    E-Print Network [OSTI]

    Test Plan to Assess Electric Vehicle Cell Degradation under Electric Utility Grid Operations. The U.S. Government assumes no liability for the contents or use thereof. #12;Test Plan to Assess EV. Abstract This report details the testing plan that will be used by the Hawaii Natural Energy Institute

  12. Nevada Test Site Groundwater Well Rehabilitation Plan

    SciTech Connect (OSTI)

    David B. Hudson

    2006-12-01

    This plan describes actions to improve the utility and credibility of the Nevada Test Site (NTS) interim groundwater monitoring program. The two principal actions are: (1) well maintenance/rehabilitation activities and (2) the deployment of dedicated low-cost and reliable jack-pumps for groundwater sampling from deep monitoring wells. The scope of this proposal is to perform these actions on some number of nine selected wells (Figure 1) to evaluate whether these actions are achievable, practical, cost effective, and result in improved groundwater data quality.

  13. Development of Performance Acceptance Test Guidelines for Large Commercial Parabolic Trough Solar Fields: Preprint

    SciTech Connect (OSTI)

    Kearney, D.; Mehos, M.

    2010-12-01

    Prior to commercial operation, large solar systems in utility-size power plants need to pass a performance acceptance test conducted by the EPC contractor or owners. In lieu of the present absence of engineering code developed for this purpose, NREL has undertaken the development of interim guidelines to provide recommendations for test procedures that can yield results of a high level of accuracy consistent with good engineering knowledge and practice. The fundamental differences between acceptance of a solar power plant and a conventional fossil-fired plant are the transient nature of the energy source and the necessity to utilize an analytical performance model in the acceptance process. These factors bring into play the need to establish methods to measure steady state performance, potential impacts of transient processes, comparison to performance model results, and the possible requirement to test, or model, multi-day performance within the scope of the acceptance test procedure. The power block and BOP are not within the boundaries of this guideline. The current guideline is restricted to the solar thermal performance of parabolic trough systems and has been critiqued by a broad range of stakeholders in CSP development and technology.

  14. The future potential of earth sheltered structures: cost, acceptability and planning considerations

    SciTech Connect (OSTI)

    Sterling, R.L.; Carmody, J.

    1980-12-01

    Earth sheltered structures have received an increasing amount of attention over the past few years. This has been primarily due to their typically low requirements for both heating and cooling energy. Their potential; however, not only lies in their energy performance but also in their ability to deal with a number of planning and design issues that must be faced in many locations. These issues include: noise protection, storm protection, saving a usable land area above the building and providing a minimum impact on the environment and ecology of a site. Against this promising potential must be weighed the factors which have made such structures undesirable from a designer's and user's point of view in the past. In addition, there are also a few new constraints which have arisen as the use of this building form has grown. This paper examines these issues and discusses the current acceptability and possible future potential of earth sheltered structures.

  15. Modeling of a Parabolic Trough Solar Field for Acceptance Testing: A Case Study

    SciTech Connect (OSTI)

    Wagner, M. J.; Mehos, M. S.; Kearney, D. W.; McMahan, A. C.

    2011-01-01

    As deployment of parabolic trough concentrating solar power (CSP) systems ramps up, the need for reliable and robust performance acceptance test guidelines for the solar field is also amplified. Project owners and/or EPC contractors often require extensive solar field performance testing as part of the plant commissioning process in order to ensure that actual solar field performance satisfies both technical specifications and performance guaranties between the involved parties. Performance test code work is currently underway at the National Renewable Energy Laboratory (NREL) in collaboration with the SolarPACES Task-I activity, and within the ASME PTC-52 committee. One important aspect of acceptance testing is the selection of a robust technology performance model. NREL1 has developed a detailed parabolic trough performance model within the SAM software tool. This model is capable of predicting solar field, sub-system, and component performance. It has further been modified for this work to support calculation at subhourly time steps. This paper presents the methodology and results of a case study comparing actual performance data for a parabolic trough solar field to the predicted results using the modified SAM trough model. Due to data limitations, the methodology is applied to a single collector loop, though it applies to larger subfields and entire solar fields. Special consideration is provided for the model formulation, improvements to the model formulation based on comparison with the collected data, and uncertainty associated with the measured data. Additionally, this paper identifies modeling considerations that are of particular importance in the solar field acceptance testing process and uses the model to provide preliminary recommendations regarding acceptable steady-state testing conditions at the single-loop level.

  16. Acceptance Test Procedure for New Pumping Instrumentation and Control Skid Q

    SciTech Connect (OSTI)

    KOCH, M.R.

    2000-02-14

    This Test Plan provides a test method to dedicate the leak detection relays used on the new Pumping Instrumentation and Control (PIC) skids. The new skids are fabricated on-site. The leak detection system is a safety class system per the Authorization Basis.

  17. Acceptance Test Procedure for New Pumping Instrumentation and Control Skid P

    SciTech Connect (OSTI)

    KOCH, M.R.

    2000-02-14

    This Test Plan provides a test method to dedicate the leak detection relays used on the new Pumping Instrumentation and Control (PIC) skids. The new skids are fabricated on-site. The leak detection system is a safety class system per the Authorization Basis.

  18. Test Plan for the overburden removal demonstration

    SciTech Connect (OSTI)

    Rice, P.; Thompson, D.; Winberg, M.; Skaggs, J.

    1993-06-01

    The removal of soil overburdens from contaminated pits and trenches involves using equipment that will remove a small layer of soil from 3 to 6 in. at any time. As a layer of soil is removed, overburden characterization techniques perform surveys to a depth that exceeds each overburden removal layer to ensure that the removed soil will be free of contamination. It is generally expected that no contamination will be found in the soil overburden, which was brought in after the waste was put in place. It is anticipated that some containers in the waste zone have lost their integrity, and the waste leakage from those containers has migrated by gravity downward into the waste zone. To maintain a safe work environment, this method of overburden removal should allow safe preparation of a pit or trench for final remediation. To demonstrate the soil overburden techniques, the Buried Waste Integrated Demonstration Program has contracted vendor services to provide equipment and techniques demonstrating soil overburden removal technology. The demonstration will include tests that will evaluate equipment performance and techniques for removal of overburden soil, control of contamination spread, and dust control. To evaluate the performance of these techniques, air particulate samples, physical measurements of the excavation soil cuts, maneuverability measurements, and time versus volume (rate) of soil removal data will be collected during removal operations. To provide a medium for sample evaluation, the overburden will be spiked at specific locations and depths with rare earth tracers. This test plan will be describe the objectives of the demonstration, data quality objectives, methods to be used to operate the equipment and use the techniques in the test area, and methods to be used in collecting data during the demonstration.

  19. Templates and Examples — Planning Your Test

    Office of Energy Efficiency and Renewable Energy (EERE)

    Here you will find custom templates and EERE-specific examples you can use to plan, conduct, and report on your usability and analysis activities.

  20. Utility-Scale Parabolic Trough Solar Systems: Performance Acceptance Test Guidelines, April 2009 - December 2010

    SciTech Connect (OSTI)

    Kearney, D.

    2011-05-01

    Prior to commercial operation, large solar systems in utility-size power plants need to pass a performance acceptance test conducted by the engineering, procurement, and construction (EPC) contractor or owners. In lieu of the present absence of ASME or other international test codes developed for this purpose, the National Renewable Energy Laboratory has undertaken the development of interim guidelines to provide recommendations for test procedures that can yield results of a high level of accuracy consistent with good engineering knowledge and practice. The Guidelines contained here are specifically written for parabolic trough collector systems with a heat-transport system using a high-temperature synthetic oil, but the basic principles are relevant to other CSP systems.

  1. Acceptance Performance Test Guideline for Utility Scale Parabolic Trough and Other CSP Solar Thermal Systems: Preprint

    SciTech Connect (OSTI)

    Mehos, M. S.; Wagner, M. J.; Kearney, D. W.

    2011-08-01

    Prior to commercial operation, large solar systems in utility-size power plants need to pass a performance acceptance test conducted by the engineering, procurement, and construction (EPC) contractor or owners. In lieu of the present absence of ASME or other international test codes developed for this purpose, the National Renewable Energy Laboratory has undertaken the development of interim guidelines to provide recommendations for test procedures that can yield results of a high level of accuracy consistent with good engineering knowledge and practice. Progress on interim guidelines was presented at SolarPACES 2010. Significant additions and modifications were made to the guidelines since that time, resulting in a final report published by NREL in April 2011. This paper summarizes those changes, which emphasize criteria for assuring thermal equilibrium and steady state conditions within the solar field.

  2. Treatability Test Plan for an In Situ Biostimulation Reducing Barrier

    SciTech Connect (OSTI)

    Truex, Michael J.; Vermeul, Vince R.; Long, Philip E.; Brockman, Fred J.; Oostrom, Mart; Hubbard, Susan; Borden, Robert C.; Fruchter, Jonathan S.

    2007-07-21

    This treatability test plan supports a new, integrated strategy to accelerate cleanup of chromium in the Hanford 100 Areas. This plan includes performing a field-scale treatability test for bioreduction of chromate, nitrate, and dissolved oxygen. In addition to remediating a portion of the plume and demonstrating reduction of electron acceptors in the plume, the data from this test will be valuable for designing a full-scale bioremediation system to apply at this and other chromium plumes at Hanford.

  3. Hierarchical GUI Test Case Generation Using Automated Planning

    E-Print Network [OSTI]

    Memon, Atif M.

    events in the GUI. The test designer defines the preconditions and effects of the hierarchical operatorsHierarchical GUI Test Case Generation Using Automated Planning Atif M. Memon, Student Member, IEEE challenges in testing the correctness of a GUI and its underlying software. We present a new technique

  4. Full-Scale Cask Testing and Public Acceptance of Spent Nuclear Fuel Shipments - 12254

    SciTech Connect (OSTI)

    Dilger, Fred; Halstead, Robert J.; Ballard, James D.

    2012-07-01

    Full-scale physical testing of spent fuel shipping casks has been proposed by the National Academy of Sciences (NAS) 2006 report on spent nuclear fuel transportation, and by the Presidential Blue Ribbon Commission (BRC) on America's Nuclear Future 2011 draft report. The U.S. Nuclear Regulatory Commission (NRC) in 2005 proposed full-scale testing of a rail cask, and considered 'regulatory limits' testing of both rail and truck casks (SRM SECY-05-0051). The recent U.S. Department of Energy (DOE) cancellation of the Yucca Mountain project, NRC evaluation of extended spent fuel storage (possibly beyond 60-120 years) before transportation, nuclear industry adoption of very large dual-purpose canisters for spent fuel storage and transport, and the deliberations of the BRC, will fundamentally change assumptions about the future spent fuel transportation system, and reopen the debate over shipping cask performance in severe accidents and acts of sabotage. This paper examines possible approaches to full-scale testing for enhancing public confidence in risk analyses, perception of risk, and acceptance of spent fuel shipments. The paper reviews the literature on public perception of spent nuclear fuel and nuclear waste transportation risks. We review and summarize opinion surveys sponsored by the State of Nevada over the past two decades, which show consistent patterns of concern among Nevada residents about health and safety impacts, and socioeconomic impacts such as reduced property values along likely transportation routes. We also review and summarize the large body of public opinion survey research on transportation concerns at regional and national levels. The paper reviews three past cask testing programs, the way in which these cask testing program results were portrayed in films and videos, and examines public and official responses to these three programs: the 1970's impact and fire testing of spent fuel truck casks at Sandia National Laboratories, the 1980's regulatory and demonstration testing of MAGNOX fuel flasks in the United Kingdom (the CEGB 'Operation Smash Hit' tests), and the 1980's regulatory drop and fire tests conducted on the TRUPACT II containers used for transuranic waste shipments to the Waste Isolation Pilot Plant in New Mexico. The primary focus of the paper is a detailed evaluation of the cask testing programs proposed by the NRC in its decision implementing staff recommendations based on the Package Performance Study, and by the State of Nevada recommendations based on previous work by Audin, Resnikoff, Dilger, Halstead, and Greiner. The NRC approach is based on demonstration impact testing (locomotive strike) of a large rail cask, either the TAD cask proposed by DOE for spent fuel shipments to Yucca Mountain, or a similar currently licensed dual-purpose cask. The NRC program might also be expanded to include fire testing of a legal-weight truck cask. The Nevada approach calls for a minimum of two tests: regulatory testing (impact, fire, puncture, immersion) of a rail cask, and extra-regulatory fire testing of a legal-weight truck cask, based on the cask performance modeling work by Greiner. The paper concludes with a discussion of key procedural elements - test costs and funding sources, development of testing protocols, selection of testing facilities, and test peer review - and various methods of communicating the test results to a broad range of stakeholder audiences. (authors)

  5. Long-term corrosion testing plan.

    SciTech Connect (OSTI)

    Wall, Frederick Douglas; Brown, Neil R. (Los Alamos National Laboratory, Los Alamos, NM)

    2009-02-01

    This document describes the testing and facility requirements to support the Yucca Mountain Project long-term corrosion testing program. The purpose of this document is to describe a corrosion testing program that will (a) reduce model uncertainty and variability, (b) reduce the reliance upon overly conservative assumptions, and (c) improve model defensibility. Test matrices were developed for 17 topical areas (tasks): each matrix corresponds to a specific test activity that is a subset of the total work performed in a task. A future document will identify which of these activities are considered to be performance confirmation activities. Detailed matrices are provided for FY08, FY09 and FY10 and rough order estimates are provided for FY11-17. Criteria for the selection of appropriate test facilities were developed through a meeting of Lead Lab and DOE personnel on October 16-17, 2007. These criteria were applied to the testing activities and recommendations were made for the facility types appropriate to carry out each activity. The facility requirements for each activity were assessed and activities were identified that can not be performed with currently available facilities. Based on this assessment, a total of approximately 10,000 square feet of facility space is recommended to accommodate all future testing, given that all testing is consolidated to a single location. This report is a revision to SAND2008-4922 to address DOE comments.

  6. Fast Flux Test Facility project plan. Revision 2

    SciTech Connect (OSTI)

    Hulvey, R.K.

    1995-11-01

    The Fast Flux Test Facility (FFTF) Transition Project Plan, Revision 2, provides changes to the major elements and project baseline for the deactivation activities necessary to transition the FFTF to a radiologically and industrially safe shutdown condition.

  7. Nitrate Salt Surrogate Blending Scoping Test Plan

    SciTech Connect (OSTI)

    Anast, Kurt Roy

    2015-11-13

    Test blending equipment identified in the “Engineering Options Assessment Report: Nitrate Salt Waste Stream Processing”. Determine if the equipment will provide adequate mixing of zeolite and surrogate salt/Swheat stream; optimize equipment type and operational sequencing; impact of baffles and inserts on mixing performance; and means of validating mixing performance

  8. Mixer pump test plan for double shell tank AZ-101

    SciTech Connect (OSTI)

    STAEHR, T.W.

    1999-05-12

    Mixer pump systems have been chosen as the method for retrieval of tank wastes contained in double shell tanks at Hanford. This document describes the plan for testing and demonstrating the ability of two 300 hp mixer pumps to mobilize waste in tank AZ-101. The mixer pumps, equipment and instrumentation to monitor the test were installed by Project W-151.

  9. Flammable gas interlock spoolpiece flow response test plan and procedure

    SciTech Connect (OSTI)

    Schneider, T.C., Fluor Daniel Hanford

    1997-02-13

    The purpose of this test plan and procedure is to test the Whittaker electrochemical cell and the Sierra Monitor Corp. flammable gas monitors in a simulated field flow configuration. The sensors are used on the Rotary Mode Core Sampling (RMCS) Flammable Gas Interlock (FGI), to detect flammable gases, including hydrogen and teminate the core sampling activity at a predetermined concentration level.

  10. Experimental Test Plan DOE Tidal and River Reference Turbines

    SciTech Connect (OSTI)

    Neary, Vincent S; Hill, Craig; Chamorro, Leonardo; Gunawan, Budi

    2012-09-01

    Our aim is to provide details of the experimental test plan for scaled model studies in St. Anthony Falls Laboratory (SAFL) Main Channel at the University of Minnesota, including a review of study objectives, descriptions of the turbine models, the experimental set-up, instrumentation details, instrument measurement uncertainty, anticipated experimental test cases, post-processing methods, and data archiving for model developers.

  11. Treatability Test Plan for an In Situ Biostimulation Reducing Barrier

    SciTech Connect (OSTI)

    Truex, Michael J.; Vermeul, Vince R.; Long, Philip E.; Brockman, Fred J.; Oostrom, Mart; Hubbard, Susan; Borden, Robert C.; Fruchter, Jonathan S.

    2007-10-26

    This treatability test plan supports a new, integrated strategy to accelerate cleanup of chromium in the 100 Areas at the Hanford Site. This plan includes performing a field-scale treatability test for bioreduction of chromate, nitrate, and dissolved oxygen. In addition to remediating a portion of the plume and demonstrating reduction of electron acceptors in the plume, the data from this test will be valuable for designing a full-scale bioremediation system to apply at this and other chromium plumes at the Hanford Site.

  12. IFE Chamber Technology Testing Program In NIF and Chamber Development Test Plan Mohamed A. Abdou

    E-Print Network [OSTI]

    Abdou, Mohamed

    chamber technology testing program in NIF involoving: criteria for evaluation to testing in ignition facility serves a critical role in chamber R&D test plans in order to reduce the risks for chamber technology testing in NIF might not be achievable because its integrated performance is evaluated

  13. Recent Advances in Test Planning for Modular Testing of Core-Based SOCs1 Vikram Iyengar?

    E-Print Network [OSTI]

    Chakrabarty, Krishnendu

    . In this paper, we sur- vey recent advances in test planning that address the problems of test access by research groups in industry and academia, as well as a wide range of methodologies for the optimization management of the test resources for core-based SOCs. This involves the design of core test wrappers and TAMs

  14. Waste Acceptance Testing of Secondary Waste Forms: Cast Stone, Ceramicrete and DuraLith

    SciTech Connect (OSTI)

    Mattigod, Shas V.; Westsik, Joseph H.; Chung, Chul-Woo; Lindberg, Michael J.; Parker, Kent E.

    2011-08-12

    To support the selection of a waste form for the liquid secondary wastes from WTP, Washington River Protection Solutions has initiated secondary-waste-form testing work at Pacific Northwest National Laboratory (PNNL). In anticipation of a down-selection process for a waste form for the Solidification Treatment Unit to be added to the ETF, PNNL is conducting tests on four candidate waste forms to evaluate their ability to meet potential waste acceptance criteria for immobilized secondary wastes that would be placed in the IDF. All three waste forms demonstrated compressive strengths above the minimum 3.45 MPa (500 psi) set as a target for cement-based waste forms. Further, none of the waste forms showed any significant degradation in compressive strength after undergoing thermal cycling (30 cycles in a 10 day period) between -40 C and 60 C or water immersion for 90 days. The three leach test methods are intended to measure the diffusion rates of contaminants from the waste forms. Results are reported in terms of diffusion coefficients and a leachability index (LI) calculated based on the diffusion coefficients. A smaller diffusion coefficient and a larger LI are desired. The NRC, in its Waste Form Technical Position (NRC 1991), provides recommendations and guidance regarding methods to demonstrate waste stability for land disposal of radioactive waste. Included is a recommendation to conduct leach tests using the ANS 16.1 method. The resulting leachability index (LI) should be greater than 6.0. For Hanford secondary wastes, the LI > 6.0 criterion applies to sodium leached from the waste form. For technetium and iodine, higher targets of LI > 9 for Tc and LI > 11 for iodine have been set based on early waste-disposal risk and performance assessment analyses. The results of these three leach tests conducted for a total time between 11days (ASTM C1308) to 90 days (ANS 16.1) showed: (1) Technetium diffusivity: ANSI/ANS 16.1, ASTM C1308, and EPA 1315 tests indicated that all the waste forms had leachability indices better than the target LI > 9 for technetium; (2) Rhenium diffusivity: Cast Stone 2M specimens, when tested using EPA 1315 protocol, had leachability indices better than the target LI > 9 for technetium based on rhenium as a surrogate for technetium. All other waste forms tested by ANSI/ANS 16.1, ASTM C1308, and EPA 1315 test methods had leachability indices that were below the target LI > 9 for Tc based on rhenium release. These studies indicated that use of Re(VII) as a surrogate for 99Tc(VII) in low temperature secondary waste forms containing reductants will provide overestimated diffusivity values for 99Tc. Therefore, it is not appropriate to use Re as a surrogate 99Tc in future low temperature waste form studies. (3) Iodine diffusivity: ANSI/ANS 16.1, ASTM C1308, and EPA 1315 tests indicated that the three waste forms had leachability indices that were below the target LI > 11 for iodine. Therefore, it may be necessary to use a more effective sequestering material than silver zeolite used in two of the waste forms (Ceramicrete and DuraLith); (4) Sodium diffusivity: All the waste form specimens tested by the three leach methods (ANSI/ANS 16.1, ASTM C1308, and EPA 1315) exceeded the target LI value of 6; (5) All three leach methods (ANS 16.1, ASTM C1308 and EPA 1315) provided similar 99Tc diffusivity values for both short-time transient diffusivity effects as well as long-term ({approx}90 days) steady diffusivity from each of the three tested waste forms (Cast Stone 2M, Ceramicrete and DuraLith). Therefore, any one of the three methods can be used to determine the contaminant diffusivities from a selected waste form.

  15. Closure Plan for the Area 5 Radioactive Waste Management Site at the Nevada Test Site

    SciTech Connect (OSTI)

    NSTec Environmental Management

    2008-09-01

    The Area 5 Radioactive Waste Management Site (RMWS) at the Nevada Test Site (NTS) is managed and operated by National Security Technologies, LLC (NSTec), for the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office (NNSA/NSO). This document is the first update of the preliminary closure plan for the Area 5 RWMS at the NTS that was presented in the Integrated Closure and Monitoring Plan (DOE, 2005a). The major updates to the plan include a new closure schedule, updated closure inventory, updated site and facility characterization data, the Title II engineering cover design, and the closure process for the 92-Acre Area of the RWMS. The format and content of this site-specific plan follows the Format and Content Guide for U.S. Department of Energy Low-Level Waste Disposal Facility Closure Plans (DOE, 1999a). This interim closure plan meets closure and post-closure monitoring requirements of the order DOE O 435.1, manual DOE M 435.1-1, Title 40 Code of Federal Regulations (CFR) Part 191, 40 CFR 265, Nevada Administrative Code (NAC) 444.743, and Resource Conservation and Recovery Act (RCRA) requirements as incorporated into NAC 444.8632. The Area 5 RWMS accepts primarily packaged low-level waste (LLW), low-level mixed waste (LLMW), and asbestiform low-level waste (ALLW) for disposal in excavated disposal cells.

  16. Acceptance criteria for the evaluation of Category 1 fuel cycle facility physical security plans

    SciTech Connect (OSTI)

    Dwyer, P.A.

    1991-10-01

    This NUREG document presents criteria developed from US Nuclear Regulatory Commission regulations for the evaluation of physical security plans submitted by Category 1 fuel facility licensees. Category 1 refers to those licensees who use or possess a formula quantity of strategic special nuclear material.

  17. IEEE TRANSACTIONS ON NUCLEAR SCIENCE, VOL. 52, NO. 6, DECEMBER 2005 2911 Acceptance Tests and Criteria of the ATLAS

    E-Print Network [OSTI]

    Eerola, Paula

    IEEE TRANSACTIONS ON NUCLEAR SCIENCE, VOL. 52, NO. 6, DECEMBER 2005 2911 Acceptance Tests and Criteria of the ATLAS Transition Radiation Tracker P. Cwetanski, T. Akesson, F. Anghinolfi, E. Arik, O. K of xenonfilled straw tubes with periodic radiator foils or fibers providing TR photon emission. The design

  18. Test Plan: Sludge Treatment Project Corrosion Process Chemistry Follow-on Testing

    SciTech Connect (OSTI)

    Delegard, Calvin H.; Schmidt, Andrew J.; Poloski, Adam P.

    2007-08-17

    This test plan was prepared by the Pacific Northwest National Laboratory (PNNL) under contract with Fluor Hanford (FH). The test plan describes the scope and conditions to be used to perform laboratory-scale testing of the Sludge Treatment Project (STP) hydrothermal treatment of K Basin sludge. The STP, managed for the U. S. Department of Energy (DOE) by FH, was created to design and operate a process to eliminate uranium metal from the sludge prior to packaging for Waste Isolation Pilot Plant (WIPP) by using high temperature liquid water to accelerate the reaction, produce uranium dioxide from the uranium metal, and safely discharge the hydrogen. The proposed testing builds on the approach and laboratory test findings for both K Basin sludge and simulated sludge garnered during prior testing from September 2006 to March 2007. The outlined testing in this plan is designed to yield further understanding of the nature of the chemical reactions, the effects of compositional and process variations and the effectiveness of various strategies to mitigate the observed high shear strength phenomenon observed during the prior testing. These tests are designed to provide process validation and refinement vs. process development and design input. The expected outcome is to establish a level of understanding of the chemistry such that successful operating strategies and parameters can be implemented within the confines of the existing STP corrosion vessel design. In July 2007, the DOE provided direction to FH regarding significant changes to the scope of the overall STP. As a result of the changes, FH directed PNNL to stop work on most of the planned activities covered in this test plan. Therefore, it is unlikely the testing described here will be performed. However, to preserve the test strategy and details developed to date, the test plan has been published.

  19. Test Plan: Phase 1, Hanford LLW melter tests, GTS Duratek, Inc.

    SciTech Connect (OSTI)

    Eaton, W.C.

    1995-06-14

    This document provides a test plan for the conduct of vitrification testing by a vendor in support of the Hanford Tank Waste Remediation System (TWRS) Low-Level Waste (LLW) Vitrification Program. The vendor providing this test plan and conducting the work detailed within it [one of seven selected for glass melter testing under Purchase Order MMI-SVV-384215] is GTS Duratek, Inc., Columbia, Maryland. The GTS Duratek project manager for this work is J. Ruller. This test plan is for Phase I activities described in the above Purchase Order. Test conduct includes melting of glass with Hanford LLW Double-Shell Slurry Feed waste simulant in a DuraMelter{trademark} vitrification system.

  20. Robust Design of Reliability Test Plans Using Degradation Measures.

    SciTech Connect (OSTI)

    Lane, Jonathan Wesley; Lane, Jonathan Wesley; Crowder, Stephen V.; Crowder, Stephen V.

    2014-10-01

    With short production development times, there is an increased need to demonstrate product reliability relatively quickly with minimal testing. In such cases there may be few if any observed failures. Thus, it may be difficult to assess reliability using the traditional reliability test plans that measure only time (or cycles) to failure. For many components, degradation measures will contain important information about performance and reliability. These measures can be used to design a minimal test plan, in terms of number of units placed on test and duration of the test, necessary to demonstrate a reliability goal. Generally, the assumption is made that the error associated with a degradation measure follows a known distribution, usually normal, although in practice cases may arise where that assumption is not valid. In this paper, we examine such degradation measures, both simulated and real, and present non-parametric methods to demonstrate reliability and to develop reliability test plans for the future production of components with this form of degradation.

  1. Review of the MERIT Experiment Magnet Status and Testing Plans

    E-Print Network [OSTI]

    McDonald, Kirk

    Review of the MERIT Experiment Magnet Status and Testing Plans Monday December 10, 2005 Peter H;CVIP Vessel Manufacturing Status Final alignment of terminations was made. Gland nut components assembled well ad will be readily changed-out if needed. Instrumentation was assembled, -Not soldered

  2. Test plan : reducing soft costs of rooftop solar installations attributed to structural considerations.

    SciTech Connect (OSTI)

    Dwyer, Stephen F.

    2013-05-01

    This test plan is a document that provides a systematic approach to the planned testing of rooftop structures to determine their actual load carrying capacity. This document identifies typical tests to be performed, the responsible parties for testing, the general feature of the tests, the testing approach, test deliverables, testing schedule, monitoring requirements, and environmental and safety compliance.

  3. Hanford Tank Farms Waste Certification Flow Loop Test Plan

    SciTech Connect (OSTI)

    Bamberger, Judith A.; Meyer, Perry A.; Scott, Paul A.; Adkins, Harold E.; Wells, Beric E.; Blanchard, Jeremy; Denslow, Kayte M.; Greenwood, Margaret S.; Morgen, Gerald P.; Burns, Carolyn A.; Bontha, Jagannadha R.

    2010-01-01

    A future requirement of Hanford Tank Farm operations will involve transfer of wastes from double shell tanks to the Waste Treatment Plant. As the U.S. Department of Energy contractor for Tank Farm Operations, Washington River Protection Solutions anticipates the need to certify that waste transfers comply with contractual requirements. This test plan describes the approach for evaluating several instruments that have potential to detect the onset of flow stratification and critical suspension velocity. The testing will be conducted in an existing pipe loop in Pacific Northwest National Laboratory’s facility that is being modified to accommodate the testing of instruments over a range of simulated waste properties and flow conditions. The testing phases, test matrix and types of simulants needed and the range of testing conditions required to evaluate the instruments are described

  4. Fabrication Control Plan for ORNL RH-LOCA ATF Test Specimens to be Irradiated in the ATR

    SciTech Connect (OSTI)

    Kevin G. Field; Richard Howard; Michael Teague

    2014-06-01

    The purpose of this fabrication plan is (1) to summarize the design of a set of rodlets that will be fabricated and then irradiated in the Advanced Test Reactor (ATR) and (2) provide requirements for fabrication and acceptance criteria for inspections of the Light Water Reactor (LWR) – Accident Tolerant Fuels (ATF) rodlet components. The functional and operational (F&OR) requirements for the ATF program are identified in the ATF Test Plan. The scope of this document only covers fabrication and inspections of rodlet components detailed in drawings 604496 and 604497. It does not cover the assembly of these items to form a completed test irradiation assembly or the inspection of the final assembly, which will be included in a separate INL final test assembly specification/inspection document. The controls support the requirements that the test irradiations must be performed safely and that subsequent examinations must provide valid results.

  5. Modular Operational Test Plans for Inferences on Software Reliability Based on a Markov Model

    E-Print Network [OSTI]

    Mazumdar, Mainak

    Modular Operational Test Plans for Inferences on Software Reliability Based on a Markov Model. Keywords: Software reliability; Modular Operational Tests; Sample Size Determination; Mathematical Programming #12;Modular Operational Test Plans for Inferences on Software Reliability Based on a Markov Model

  6. TRT meeting Oct 2002 Pauline Gagnon Indiana University Status of barrel acceptance tests

    E-Print Network [OSTI]

    Gagnon, Pauline

    154 Space has been emptied and cleaned Gas system being certified Four computers installed Status of facilities in building 154 Plans for near future First report from module 1.01 after Gagnon ­ Indiana University Plans for near future Finish installing/debugging leak, stringing

  7. DOE/OE National SCADA Test Bed Fiscal Year 2009 Work Plan | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    DOEOE National SCADA Test Bed Fiscal Year 2009 Work Plan DOEOE National SCADA Test Bed Fiscal Year 2009 Work Plan This document is designed to help guide and strengthen the DOE...

  8. TRUPACT-II Hydrogen G-Valve Program Test Plan

    SciTech Connect (OSTI)

    Mroz, Eugene J.

    1999-01-01

    This test plan describes the objectives, scope, participants, and components of the Transuranic Package Transporter-II (TRUPACT-II) Hydrogen G-Value Program (GH2P). The GH2P builds on the experience, results, and experimental setup of the TRUPACT-II Matrix Depletion Program (MDP) to establish effective hydrogen G-values (G-values) for additional waste matrices. This plan details the experimental design and test matrices for experiments to measure the G-value for additional waste matrices, including first- and second-stage sludges at the Idaho National Engineering and Environmental Laboratory, and molten salt extraction residues with varying amounts of residual moisture (i.e., unbound water). Data collected from the GH2P will be used to support an application to the US Nuclear Regulatory Commission for G-values and corresponding wattage limits for the TRUPACT-II payloads containing these waste matrices. The testing will also evaluate the ability to determine G-values on a waste stream basis.

  9. Updated FY12 Ceramic Fuels Irradiation Test Plan

    SciTech Connect (OSTI)

    Nelson, Andrew T.

    2012-05-24

    The Fuel Cycle Research and Development program is currently devoting resources to study of numerous fuel types with the aim of furthering understanding applicable to a range of reactors and fuel cycles. In FY11, effort within the ceramic fuels campaign focused on planning and preparation for a series of rabbit irradiations to be conducted at the High Flux Isotope Reactor located at Oak Ridge National Laboratory. The emphasis of these planned tests was to study the evolution of thermal conductivity in uranium dioxide and derivative compositions as a function of damage induced by neutron damage. Current fiscal realities have resulted in a scenario where completion of the planned rabbit irradiations is unlikely. Possibilities for execution of irradiation testing within the ceramic fuels campaign in the next several years will thus likely be restricted to avenues where strong synergies exist both within and outside the Fuel Cycle Research and Development program. Opportunities to augment the interests and needs of modeling, advanced characterization, and other campaigns present the most likely avenues for further work. These possibilities will be pursued with the hope of securing future funding. Utilization of synthetic microstructures prepared to better understand the most relevant actors encountered during irradiation of ceramic fuels thus represents the ceramic fuel campaign's most efficient means to enhance understanding of fuel response to burnup. This approach offers many of the favorable attributes embraced by the Separate Effects Testing paradigm, namely production of samples suitable to study specific, isolated phenomena. The recent success of xenon-imbedded thick films is representative of this approach. In the coming years, this strategy will be expanded to address a wider range of problems in conjunction with use of national user facilities novel characterization techniques to best utilize programmatic resources to support a science-based research program.

  10. International Fusion Materials Irradiation Facility injector acceptance tests at CEA/Saclay: 140 mA/100 keV deuteron beam characterization

    SciTech Connect (OSTI)

    Gobin, R., E-mail: rjgobin@cea.fr; Bogard, D.; Chauvin, N.; Chel, S.; Delferrière, O.; Harrault, F.; Mattei, P.; Senée, F. [Commissariat à l’Energie Atomique et aux Energies Alternatives, CEA/Saclay, DSM/IRFU, 91191-Gif/Yvette (France)] [Commissariat à l’Energie Atomique et aux Energies Alternatives, CEA/Saclay, DSM/IRFU, 91191-Gif/Yvette (France); Cara, P. [Fusion for Energy, BFD Department, Garching (Germany)] [Fusion for Energy, BFD Department, Garching (Germany); Mosnier, A. [Commissariat à l’Energie Atomique et aux Energies Alternatives, CEA/Saclay, DSM/IRFU, 91191-Gif/Yvette (France) [Commissariat à l’Energie Atomique et aux Energies Alternatives, CEA/Saclay, DSM/IRFU, 91191-Gif/Yvette (France); Fusion for Energy, BFD Department, Garching (Germany); Shidara, H. [IFMIF/EVEDA Project Team, Obuchi-Omotedate 2-166, Rokkasho, Aomori (Japan)] [IFMIF/EVEDA Project Team, Obuchi-Omotedate 2-166, Rokkasho, Aomori (Japan); Okumura, Y. [JAEA, Division of Rokkasho BA Project, Obuchi-Omotedate 2-166, Rokkasho, Aomori (Japan)] [JAEA, Division of Rokkasho BA Project, Obuchi-Omotedate 2-166, Rokkasho, Aomori (Japan)

    2014-02-15

    In the framework of the ITER broader approach, the International Fusion Materials Irradiation Facility (IFMIF) deuteron accelerator (2 × 125 mA at 40 MeV) is an irradiation tool dedicated to high neutron flux production for future nuclear plant material studies. During the validation phase, the Linear IFMIF Prototype Accelerator (LIPAc) machine will be tested on the Rokkasho site in Japan. This demonstrator aims to produce 125 mA/9 MeV deuteron beam. Involved in the LIPAc project for several years, specialists from CEA/Saclay designed the injector based on a SILHI type ECR source operating at 2.45 GHz and a 2 solenoid low energy beam line to produce such high intensity beam. The whole injector, equipped with its dedicated diagnostics, has been then installed and tested on the Saclay site. Before shipment from Europe to Japan, acceptance tests have been performed in November 2012 with 100 keV deuteron beam and intensity as high as 140 mA in continuous and pulsed mode. In this paper, the emittance measurements done for different duty cycles and different beam intensities will be presented as well as beam species fraction analysis. Then the reinstallation in Japan and commissioning plan on site will be reported.

  11. Corrosion testing of spent nuclear fuel performed at Argonne National Laboratory for repository acceptance

    SciTech Connect (OSTI)

    Goldberg, M. M.

    2000-07-20

    Corrosion tests of DOE-owned spent nuclear fuel are performed at Argonne National Laboratory to support the license application for the Yucca Mountain Repository. The tests are designed to determine corrosion rates and degradation products formed when fuel is reacted at elevated temperature in different aqueous environments, including vapor, dripping water, submersion, and liquid film contact. Corrosion rates are determined from the quantity of radionuclides released from wetted fuel and from the weight loss of the test fuel specimen as a function of time. Degradation products include secondary mineral phases and dissolved, adsorbed, and colloidal species. Solid phase examinations determine fuel/mineral interface relationships, characterize radionuclide incorporation into secondary phases, and determine corrosion mechanisms at grain interfaces within the fuel. Leachate solution analyses quantify released radionuclides and determine the size and charge distribution of colloids. This paper presents selected results from corrosion tests on metallic fuels.

  12. Acceptance Test Procedure for Project 251W, WBS 3, Substation A-8, Building 251-W, Bus {number_sign}2 switchgear replacement

    SciTech Connect (OSTI)

    VanBaalen, R.A.

    1995-02-01

    This document records the steps taken and results of the acceptance testing of the new 13.8kV switchgear installed at 251W. This gear is under the administrative control of Electrical Utilities.

  13. Test plan/procedure for the SPM-1 shipping container system. Revision 0

    SciTech Connect (OSTI)

    Flanagan, B.D.

    1995-07-01

    The 49 CFR 173.465 Type A packaging tests will verify that SPM-1 will provide adequate protection and pass as a Type A package. Test will determine that the handle of the Pig will not penetrate through the plywood spacer and rupture the shipping container. Test plan/procedure provides planning, pre-test, setup, testing, and post-testing guidelines and procedures for conducting the {open_quotes}Free Drop Test{close_quotes} procedure for the SPM-1 package.

  14. Acceptance test procedure for removal of CS1K circuit switcher block and trip schemes

    SciTech Connect (OSTI)

    HACHE, J.M.

    1999-08-25

    This supporting document provides a detailed process to test the functions of the circuit switcher, protective relays, alarms, SCADA and 125VDC control logic of 115kV and 13.8kV systems at B3S4 substation following the removal of trip and blocking schemes to Transformer No.1 Circuit Switcher B594.

  15. TRT meeting Feb 03 Pauline Gagnon Indiana University 1 Acceptance tests for barrel modules

    E-Print Network [OSTI]

    Gagnon, Pauline

    tension 90% 80% 100% stringing 80% 100% not tested HV checks 100% 20% not done HV conditioning in design 20% not done gain mapping designed 100% not done #12;TRT meeting ­ Feb 03 Pauline Gagnon ­ Indiana Circulate ventilation through 3 modules: type 1,2 3 Active gas in series through 2 modules of the same type

  16. Using Phased Array Ultrasonic Testing in Lieu of Radiography for Acceptance of Carbon Steel Piping Welds

    SciTech Connect (OSTI)

    Moran, Traci L.; Anderson, Michael T.; Cinson, Anthony D.; Crawford, Susan L.; Nove, Carol A.

    2014-08-01

    The Pacific Northwest National Laboratory (PNNL) is conducting studies for the U.S. Nuclear Regulatory Commission (NRC) to assess the capability, effectiveness, and reliability of ultrasonic testing (UT) as a replacement method for radiographic testing (RT) for volumetric examination of nuclear power plant (NPP) components. This particular study focused on evaluating the use of UT on carbon steel plate welds. Welding fabrication flaws included a combination of planar and volumetric types, e.g., incomplete fusion, lack of penetration, cracks, porosity, and slag inclusions. The examinations were conducted using phased-array (PA) UT techniques applied primarily for detection and flaw type characterization. This paper will discuss the results of using UT in lieu of RT for detection and classification of fabrication flaws in carbon steel plate welds.

  17. Test Plan for the Boiling Water Reactor Dry Cask Simulator

    SciTech Connect (OSTI)

    Durbin, Samuel; Lindgren, Eric R.

    2015-11-01

    The thermal performance of commercial nuclear spent fuel dry storage casks are evaluated through detailed numerical analysis . These modeling efforts are completed by the vendor to demonstrate performance and regulatory compliance. The calculations are then independently verified by the Nuclear Regulatory Commission (NRC). Carefully measured data sets generated from testing of full sized casks or smaller cask analogs are widely recognized as vital for validating these models. Recent advances in dry storage cask designs have significantly increased the maximum thermal load allowed in a cask in part by increasing the efficiency of internal conduction pathways and by increasing the internal convection through greater canister helium pressure. These same vertical, canistered cask systems rely on ventilation between the canister and the overpack to convect heat away from the canister to the environment for both above and below-ground configurations. While several testing programs have been previously conducted, these earlier validation attempts did not capture the effects of elevated helium pressures or accurately portray the external convection of above-ground and below-ground canistered dry cask systems. The purpose of the investigation described in this report is to produce a data set that can be used to test the validity of the assumptions associated with the calculations presently used to determine steady-state cladding temperatures in modern vertical, canistered dry cask systems. The BWR cask simulator (BCS) has been designed in detail for both the above-ground and below-ground venting configurations. The pressure vessel representing the canister has been designed, fabricated, and pressure tested for a maximum allowable pressure (MAWP) rating of 24 bar at 400 deg C. An existing electrically heated but otherwise prototypic BWR Incoloy-clad test assembly is being deployed inside of a representative storage basket and cylindrical pressure vessel that represents the canister. The symmetric single assembly geometry with well-controlled boundary conditions simplifies interpretation of results. Various configurations of outer concentric ducting will be used to mimic conditions for above and below-ground storage configurations of vertical, dry cask systems with canisters. Radial and axial temperature profiles will be measured for a wide range of decay power and helium cask pressures. Of particular interest is the evaluation of the effect of increased helium pressure on allowable heat load and the effect of simulated wind on a simplified below ground vent configuration. While incorporating the best available information, this test plan is subject to changes due to improved understanding from modeling or from as-built deviations to designs. As-built conditions and actual procedures will be documented in the final test report.

  18. Test plan for buried waste containment system materials

    SciTech Connect (OSTI)

    Weidner, J.; Shaw, P.

    1997-03-01

    The objectives of the FY 1997 barrier material work at the Idaho National Engineering and Environmental Laboratory are to (1) select a waste barrier material and verify that it is compatible with the Buried Waste Containment System Process, and (2) determine if, and how, the Buried Waste Containment System emplacement process affects the material properties and performance (on proof of principle scale). This test plan describes a set of measurements and procedures used to validate a waste barrier material for the Buried Waste Containment System. A latex modified proprietary cement manufactured by CTS Cement Manufacturing Company will be tested. Emplacement properties required for the Buried Waste Containment System process are: slump between 8 and 10 in., set time between 15 and 30 minutes, compressive strength at set of 20 psi minimum, and set temperature less than 100{degrees}C. Durability properties include resistance to degradation from carbonate, sulfate, and waste-site soil leachates. A set of baseline barrier material properties will be determined to provide a data base for comparison with the barrier materials when tested in the field. The measurements include permeability, petrographic analysis to determine separation and/or segregation of mix components, and a set of mechanical properties. The measurements will be repeated on specimens from the field test material. The data will be used to determine if the Buried Waste Containment System equipment changes the material. The emplacement properties will be determined using standard laboratory procedures and instruments. Durability of the barrier material will be evaluated by determining the effect of carbonate, sulfate, and waste-site soil leachates on the compressive strength of the barrier material. The baseline properties will be determined using standard ASTM procedures. 9 refs., 1 fig., 2 tabs.

  19. Laboratory test plan in-well vapor stripping system

    SciTech Connect (OSTI)

    Koegler, K.J

    1994-07-01

    This test plan describes the activities that will be conducted as a part of the laboratory testing of a full-scale mockup of the Stanford in-well vapor stripping system. These tests will be conducted to delineate design parameters for the in-well vapor stripping unit and to identify and quantify variables that are sensitive to the dynamic hydraulic effects induced by operation of the system. No radioactive materials are involved in this test. In-well vapor stripping has been used successfully as an alternative to conventional pump-and-treat technology for remediation of volatile organic compound (VOC) contaminated groundwater in Europe and more recently in the United States. In-well vapor stripping permits in situ remediation of VOC-contaminated groundwater by combining an in-well vapor stripping system with a treatment well is used to extract and discharge groundwater simultaneously, resulting in the establishment of a vertical circulation groundwater flow cell in the aquifer. Groundwater extracted from the aquifer via the lower screened interval is treated for VOCs by in-well vapor stripping within the treatment well. This stripping causes aqueous phase VOCs to partition preferentially into a vapor phase. Treated groundwater is discharged back to the aquifer via the upper screened interval of the treatment well, while the vapor phase VOCs are simultaneously removed from the well bore and contained at the surface with a vacuum extraction system. Groundwater entrained into the vertical circulation flow cell becomes sequentially cleaned of VOC contamination in an efficient manner without the need for surface treatment and handling of contaminated groundwater. An added benefit of in-well vapor stripping is the ability to perform vadose zone vapor extraction concurrently with groundwater remediation. This uses the vacuum extraction capabilities of the in-well vapor stripping configured with the upper screened interval placed into the vadose zone above the water table.

  20. Plan

    National Nuclear Security Administration (NNSA)

    Information P.O. Box 62 Oak Ridge, TN 37831-0062 (423) 576-8401 DOENV-11432-244 Nevada Test Site Routine Radiological Environmental Monitoring Plan December 1998 Work Performed...

  1. Closure Plan for the Area 3 Radioactive Waste Management Site at the Nevada Test Site

    SciTech Connect (OSTI)

    NSTec Environmental Management

    2007-09-01

    The Area 3 Radioactive Waste Management Site (RMWS) at the Nevada Test Site (NTS) is managed and operated by National Security Technologies, LLC (NSTec) for the U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office (NNSA/NSO). This document is the first update of the interim closure plan for the Area 3 RWMS, which was presented in the Integrated Closure and Monitoring Plan (ICMP) (DOE, 2005). The format and content of this plan follows the Format and Content Guide for U.S. Department of Energy Low-Level Waste Disposal Facility Closure Plans (DOE, 1999a). The major updates to the plan include a new closure date, updated closure inventory, the new institutional control policy, and the Title II engineering cover design. The plan identifies the assumptions and regulatory requirements, describes the disposal sites and the physical environment in which they are located, presents the design of the closure cover, and defines the approach and schedule for both closing and monitoring the site. The Area 3 RWMS accepts low-level waste (LLW) from across the DOE Complex in compliance with the NTS Waste Acceptance Criteria (NNSA/NSO, 2006). The Area 3 RWMS accepts both packaged and unpackaged unclassified bulk LLW for disposal in subsidence craters that resulted from deep underground tests of nuclear devices in the early 1960s. The Area 3 RWMS covers 48 hectares (119 acres) and comprises seven subsidence craters--U-3ax, U-3bl, U-3ah, U-3at, U-3bh, U-3az, and U-3bg. The area between craters U-3ax and U-3bl was excavated to form one large disposal unit (U-3ax/bl); the area between craters U-3ah and U-3at was also excavated to form another large disposal unit (U-3ah/at). Waste unit U-3ax/bl is closed; waste units U-3ah/at and U-3bh are active; and the remaining craters, although currently undeveloped, are available for disposal of waste if required. This plan specifically addresses the closure of the U-3ah/at and the U-3bh LLW units. A final closure cover has been placed on unit U-3ax/bl (Corrective Action Unit 110) at the Area 3 RWMS. Monolayer-evapotranspirative closure cover designs for the U-3ah/at and U-3bh units are provided in this plan. The current-design closure cover thickness is 3 meters (10 feet). The final design cover will have an optimized cover thickness, which is expected to be less than 3 m (10 ft). Although waste operations at the Area 3 RWMS have ceased at the end of June 2006, disposal capacity is available for future disposals at the U-3ah/at and U-3bh units. The Area 3 RWMS is expected to start closure activities in fiscal year 2025, which include the development of final performance assessment and composite analysis documents, closure plan, closure cover design for construction, cover construction, and initiation of the post-closure care and monitoring activities. Current monitoring at the Area 3 RWMS includes monitoring the cover of the closed mixed waste unit U-3ax/bl as required by the Nevada Department of Environmental Protection, and others required under federal regulations and DOE orders. Monitoring data, collected via sensors and analysis of samples, are needed to evaluate radiation doses to the general public, for performance assessment maintenance, to demonstrate regulatory compliance, and to evaluate the actual performance of the RWMSs. Monitoring provides data to ensure the integrity and performance of waste disposal units. The monitoring program is designed to forewarn management and regulators of any failure and need for mitigating actions. The plan describes the program for monitoring direct radiation, air, vadose zone, biota, groundwater, meteorology, and subsidence. The requirements of post-closure cover maintenance and monitoring will be determined in the final closure plan.

  2. BERLinPro Booster Cavity Design, Fabrication and Test Plans

    SciTech Connect (OSTI)

    Burrill, Andrew [HZB; Anders, W [HZB; Frahm, A. [HZB; Knobloch, Jens [HZB; Neumann, Axel [HZB; Ciovati, Gianluigi [JLAB; Kneisel, Peter K. [JLAB; Turlington, Larry D. [JLAB

    2014-12-01

    The bERLinPro project, a 100 mA, 50 MeV superconducting RF (SRF) Energy Recovery Linac (ERL) is under construction at Helmholtz-Zentrum Berlin for the purpose of studying the technical challenges and physics of operating a high current, c.w., 1.3 GHz ERL. This machine will utilize three unique SRF cryomodules for the injector, booster and linac module respectively. The booster cryomodule will contain three 2-cell SRF cavities, based on the original design by Cornell University, and will be equipped with twin 115 kW RF power couplers in order to provide the appropriate acceleration to the high current electron beam. This paper will review the status of the fabrication of the 4 booster cavities that have been built for this project by Jefferson Laboratory and look at the challenges presented by the incorporation of fundamental power couplers capable of delivering 115 kW. The test plan for the cavities and couplers will be given along with a brief overview of the cryomodule design.

  3. A Propellantless Propulsion Experiment Design and Testing Plan

    SciTech Connect (OSTI)

    Goodwin, David P. [United States Department of Energy, Office of High Energy Physics, SC-20/Germantown Building, 1000 Independence Ave SW, Washington, D.C. 20585-1290 (United States)

    2004-02-04

    A propellantless propulsion experiment design and testing plan are described. The concept was initially presented during the Space Technology and Applications International Forum of 2001 and the experiment was initially presented during the Joint Propulsion Conference of 2001. New information is provided on how the experiment relates to the Human Exploration of Development of Space, the results of peer reviews, a cost estimate performed by a major U.S. aerospace company, and an alternative magnet design to reduce the cost of the experiment and potentially improve the reliability of the system. Recent improvements in high power solid state switches and superconducting magnets may have made propellantless propulsion possible. Propulsion may occur during the non-steady state ramp-up of a very rapidly pulsed, high power magnet. Propulsion would not occur after the first 100 nanoseconds of each pulse, since the magnetic field will have reached steady state. The United States Department of Energy Office of High Energy Physics provided some of the funding for the developed a no maintenance superconducting magnet that can carry 2,000 amperes per square millimeter and a switch which can provide 100 nanosecond ramp-ups at a rate of 0.4 megahertz, and at 9,000 volts and 30 amperes.

  4. Engineering test plan for field radionuclide migration experiments in climax granite

    SciTech Connect (OSTI)

    Isherwood, D.; Raber, E.; Stone, R.; Lord, D.; Rector, N.; Failor, R.

    1982-05-01

    This Engineering Test Plan (ETP) describes field studies of radionuclide migration in fractured rock designed for the Climax grainite at the Nevada Test Site. The purpose of the ETP is to provide a detailed written document of the method of accomplishing these studies. The ETP contains the experimental test plans, an instrumentation plan, system schematics, a description of the test facility, and a brief outline of the laboratory support studies needed to understand the chemistry of the rock/water/radionuclide interactions. Results of our initial hydrologic investigations are presented along with pretest predictions based on the hydrologic test results.

  5. ORNL/TM-2012/301 Experimental Test Plan DOE Tidal

    E-Print Network [OSTI]

    Siefert, Chris

    ORNL/TM-2012/301 Experimental Test Plan ­ DOE Tidal And River Reference Turbines August 2012 Test Plan ­ DOE Tidal and River Reference Turbines Vincent S. Neary1 Craig Hill2 Leonardo P. Chamorro 2 16, 2012 Prepared for: Wind and Water Power Technologies Program Office of Energy Efficiency

  6. Test plan for the irradiation of nonmetallic materials.

    SciTech Connect (OSTI)

    Brush, Laurence H.; Farnum, Cathy Ottinger; Dahl, M.; Joslyn, C. C.; Venetz, T. J.

    2013-05-01

    A comprehensive test program to evaluate nonmetallic materials use in the Hanford tank farms is described in detail. This test program determines the effects of simultaneous multiple stressors at reasonable conditions on in-service configuration components by engineering performance testing.

  7. Test plan for the irradiation of nonmetallic materials.

    SciTech Connect (OSTI)

    Brush, Laurence H.; Farnum, Cathy Ottinger; Gelbard, Fred; Dahl, M.; Joslyn, C. C.; Venetz, T. J.

    2013-03-01

    A comprehensive test program to evaluate nonmetallic materials use in the Hanford Tank Farms is described in detail. This test program determines the effects of simultaneous multiple stressors at reasonable conditions on in-service configuration components by engineering performance testing.

  8. Beta Test Plan for Advanced Inverters Interconnecting Distributed Resources with Electric Power Systems

    SciTech Connect (OSTI)

    Hoke, A.; Chakraborty, S.; Basso, T.; Coddington, M.

    2014-01-01

    This document provides a preliminary (beta) test plan for grid interconnection systems of advanced inverter-based DERs. It follows the format and methodology/approach established by IEEE Std 1547.1, while incorporating: 1. Upgraded tests for responses to abnormal voltage and frequency, and also including ride-through. 2. A newly developed test for voltage regulation, including dynamic response testing. 3. Modified tests for unintentional islanding, open phase, and harmonics to include testing with the advanced voltage and frequency response functions enabled. Two advanced inverters, one single-phase and one three-phase, were tested under the beta test plan. These tests confirmed the importance of including tests for inverter dynamic response, which varies widely from one inverter to the next.

  9. High Burnup Dry Storage Cask Research and Development Project, Final Test Plan

    SciTech Connect (OSTI)

    2014-02-27

    EPRI is leading a project team to develop and implement the first five years of a Test Plan to collect data from a SNF dry storage system containing high burnup fuel.12 The Test Plan defined in this document outlines the data to be collected, and the storage system design, procedures, and licensing necessary to implement the Test Plan.13 The main goals of the proposed test are to provide confirmatory data14 for models, future SNF dry storage cask design, and to support license renewals and new licenses for ISFSIs. To provide data that is most relevant to high burnup fuel in dry storage, the design of the test storage system must mimic real conditions that high burnup SNF experiences during all stages of dry storage: loading, cask drying, inert gas backfilling, and transfer to the ISFSI for multi-year storage.15 Along with other optional modeling, SETs, and SSTs, the data collected in this Test Plan can be used to evaluate the integrity of dry storage systems and the high burnup fuel contained therein over many decades. It should be noted that the Test Plan described in this document discusses essential activities that go beyond the first five years of Test Plan implementation.16 The first five years of the Test Plan include activities up through loading the cask, initiating the data collection, and beginning the long-term storage period at the ISFSI. The Test Plan encompasses the overall project that includes activities that may not be completed until 15 or more years from now, including continued data collection, shipment of the Research Project Cask to a Fuel Examination Facility, opening the cask at the Fuel Examination Facility, and examining the high burnup fuel after the initial storage period.

  10. Pilot-scale treatability test plan for the 200-UP-1 groundwater Operable Unit

    SciTech Connect (OSTI)

    Wittreich, C.D.

    1994-05-01

    This document presents the treatability test plan for pilot-scale pump and treat testing at the 200-UP-1 Operable Unit. This treatability test plan has been prepared in response to an agreement between the US Department of Energy, the US Environmental Protection Agency, and the Washington State Department of Ecology, as documented in Hanford Federal Facility Agreement and Consent Order (Ecology et al. 1989a) Change Control Form M-13-93-03 (Ecology et al. 1994). The agreement also requires that, following completion of the activities described in this test plan, a 200-UP-1 Operable Unit interim remedial measure (IRM) proposed plan be developed for use in preparing an interim action record of decision (ROD). The IRM Proposed Plan will be supported by the results of the testing described in this treatability test plan, as well as by other 200-UP-1 Operable Unit activities (e.g., limited field investigation, development of a qualitative risk assessment). Once issued, the interim action ROD will specify the interim action for groundwater contamination at the 200-UP-1 Operable Unit. The approach discussed in this treatability test plan is to conduct a pilot-scale pump and treat test for the contaminant plume associated with the 200-UP-1 Operable Unit. Primary contaminants of concern are uranium and technetium-99; the secondary contaminant of concern is nitrate. The pilot-scale treatability testing presented in this test plan has as its primary purpose to assess the performance of aboveground treatment systems with respect to the ability to remove the primary contaminants in groundwater withdrawn from the contaminant plume.

  11. Vadose zone transport field study: Detailed test plan for simulated leak tests

    SciTech Connect (OSTI)

    AL Ward; GW Gee

    2000-06-23

    The US Department of Energy (DOE) Groundwater/Vadose Zone Integration Project Science and Technology initiative was created in FY 1999 to reduce the uncertainty associated with vadose zone transport processes beneath waste sites at DOE's Hanford Site near Richland, Washington. This information is needed not only to evaluate the risks from transport, but also to support the adoption of measures for minimizing impacts to the groundwater and surrounding environment. The principal uncertainties in vadose zone transport are the current distribution of source contaminants and the natural heterogeneity of the soil in which the contaminants reside. Oversimplified conceptual models resulting from these uncertainties and limited use of hydrologic characterization and monitoring technologies have hampered the understanding contaminant migration through Hanford's vadose zone. Essential prerequisites for reducing vadose transport uncertainly include the development of accurate conceptual models and the development or adoption of monitoring techniques capable of delineating the current distributions of source contaminants and characterizing natural site heterogeneity. The Vadose Zone Transport Field Study (VZTFS) was conceived as part of the initiative to address the major uncertainties confronting vadose zone fate and transport predictions at the Hanford Site and to overcome the limitations of previous characterization attempts. Pacific Northwest National Laboratory (PNNL) is managing the VZTFS for DOE. The VZTFS will conduct field investigations that will improve the understanding of field-scale transport and lead to the development or identification of efficient and cost-effective characterization methods. Ideally, these methods will capture the extent of contaminant plumes using existing infrastructure (i.e., more than 1,300 steel-cased boreholes). The objectives of the VZTFS are to conduct controlled transport experiments at well-instrumented field sites at Hanford to: identify mechanisms controlling transport processes in soils typical of the hydrogeologic conditions of Hanford's waste disposal sites; reduce uncertainty in conceptual models; develop a detailed and accurate database of hydraulic and transport parameters for validation of three-dimensional numerical models; identify and evaluate advanced, cost-effective characterization methods with the potential to assess changing conditions in the vadose zone, particularly as surrogates of currently undetectable high-risk contaminants. This plan provides details for conducting field tests during FY 2000 to accomplish these objectives. Details of additional testing during FY 2001 and FY 2002 will be developed as part of the work planning process implemented by the Integration Project.

  12. Sampling and Analysis Plan for Old Solvent Tanks S1-S22 to Address Waste Acceptance Criteria

    SciTech Connect (OSTI)

    Filpus-Luyckx, P.E. [Westinghouse Savannah River Company, AIKEN, SC (United States)

    1997-10-02

    The Environmental Restoration Department (ERD) assumed custody of the Old Solvent Tanks (Tanks S1-S22) in the Old Radioactive Waste Burial Ground (ORWBG, 643-E) from Waste Management in January 1991. The purpose of this Sampling and Analysis Plan (SAP) is to collect and analyze samples of the sludge solids, organic and aqueous phases to determine the level of radioactivity, the isotopic constituents, the specific gravity, and other physical parameters. These data must be obtained to evaluate the process safety of remediating the tanks, to determine the disposal path for the material in the tanks, and to determine the most viable closure technology for the tanks.

  13. Gearbox Reliability Collaborative Phase 3 Gearbox 2 Test Plan

    SciTech Connect (OSTI)

    Link, H.; Keller, J.; Guo, Y.; McNiff, B.

    2013-04-01

    Gearboxes in wind turbines have not been achieving their expected design life even though they commonly meet or exceed the design criteria specified in current design standards. One of the basic premises of the National Renewable Energy Laboratory (NREL) Gearbox Reliability Collaborative (GRC) is that the low gearbox reliability results from the absence of critical elements in the design process or insufficient design tools. Key goals of the GRC are to improve design approaches and analysis tools and to recommend practices and test methods resulting in improved design standards for wind turbine gearboxes that lower the cost of energy (COE) through improved reliability. The GRC uses a combined gearbox testing, modeling and analysis approach, along with a database of information from gearbox failures collected from overhauls and investigation of gearbox condition monitoring techniques to improve wind turbine operations and maintenance practices. Testing of Gearbox 2 (GB2) using the two-speed turbine controller that has been used in prior testing. This test series will investigate non-torque loads, high-speed shaft misalignment, and reproduction of field conditions in the dynamometer. This test series will also include vibration testing using an eddy-current brake on the gearbox's high speed shaft.

  14. Prototypical steam generator (MB-2) transient testing program. Task plan/scaling analysis report. [PWR

    SciTech Connect (OSTI)

    Young, M.Y.; Takeuchi, K.; Mendler, O.J.; Hopkins, G.W.

    1984-03-01

    This report describes the Westinghouse MB-2 model boiler test facility and the test program currently planned (with Westinghouse/EPRI/NRC funding) to investigate various types of possible accidents which might occur in a PWR steam generator. The planned tests will simulate loss of feedwater (LOF) transients, various steam generator tube rupture (SGTR) scenarios, and steamline breaks (SLB). The facility will be extensively modified to allow measurement of local wall and fluid temperatures, and to measure possible moisture carryover during the SLB and SGTR tests. This report is divided into six sections. The first three sections describe the facility and the new components and instrumentation to be installed. The next section is a detailed scaling analysis of MB-2. Section 5 describes the background and objectives of the tests, and section 6 describes the analysis of the data which if planned.

  15. R&D ERL: G5 test and commissioning plan

    SciTech Connect (OSTI)

    Kayran, D.; Pozdeyev, E.

    2010-02-10

    Gun-to-5-cell cavity (G5) setup (Fig 1-2) can be considered as the first stage of the final BNL ERL design. The goal of the G5 setup is to test critical ERL components with the beam and characterize the beam produced by the gun. Also, this test will be used to assess effectiveness of the zigzag merger, which will be installed later in the ERL setup. The major components under the test will include the SRF gun, the five-cell SRF cavity, vacuum components, parts of the control and diagnostic systems. G5 is designed to measure the following beam parameters: (1) projected bunch emittance (?) and Twiss parameters ({alpha}, {beta}); (2) slice emittance; (3) bunch length; and (4) longitudinal and transverse halo.

  16. EA-2012: Strategic Test Well (s) Planning and Drilling for Long-Term Methane Hydrate Production Testing in Alaska

    Broader source: Energy.gov [DOE]

    DOE is preparing an EA that evaluates the potential environmental impacts of providing financial support for planning, analysis, and engineering services to support a proposed project of Petrotechnical Resources of Alaska with Japan Oil, Gas and Metals National Corporation to perform gas hydrate drilling and testing on the North Slope of Alaska.

  17. NREL Next Generation Drivetrain: Mechanical Design and Test Plan (Poster)

    SciTech Connect (OSTI)

    Keller, J.; Halse, C.

    2014-05-01

    The Department of Energy and industry partners are sponsoring a $3m project for design and testing of a 'Next Generation' wind turbine drivetrain at the National Renewable Energy Laboratory (NREL). This poster focuses on innovative aspects of the gearbox design, completed as part of an end-to-end systems engineering approach incorporating innovations that increase drivetrain reliability, efficiency, torque density and minimize capital cost.

  18. Test Methods Standing Technical Committee Strategic Plan - February 2012 |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious RankADVANCEDInstallers/ContractorsPhotovoltaics »TanklessResearchEnergy Test Methods Standing

  19. An Empirical Evaluation of the Impact ofAn Empirical Evaluation of the Impact ofAn Empirical Evaluation of the Impact ofAn Empirical Evaluation of the Impact of TestTestTestTest----Driven Development onDriven Development onDriven Development onDriven Deve

    E-Print Network [OSTI]

    Janzen, David

    XP Scale----Defined PracticesDefined PracticesDefined PracticesDefined Practices1111 pair programming test-driven development metaphor continuous integration on-site customer collective ownership acceptance testing planning-site customer collective ownership acceptance testing planning game short releases seconds minutes hours days

  20. Powerline Conductor Operational Testing Facility (PCOT) The Powerline Conductor Operational Testing Facility (PCOT), currently planned for

    E-Print Network [OSTI]

    ) transmission system for long-term testing and evaluation. The HV transmission test network within PCOT a facility for realistic field testing of advanced sensors and communications that have been successfully for advanced sensors and communications. Sensors successfully developed and tested by industry or by the Indoor

  1. Underground Test Area Quality Assurance Project Plan Nevada National Security Site, Nevada, Revision 0

    SciTech Connect (OSTI)

    Irene Farnham

    2011-05-01

    This Quality Assurance Project Plan (QAPP) provides the overall quality assurance (QA) program requirements and general quality practices to be applied to the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office (NNSA/NSO) Underground Test Area (UGTA) Sub-Project (hereafter the Sub-Project) activities. The requirements in this QAPP are consistent with DOE Order 414.1C, Quality Assurance (DOE, 2005); U.S. Environmental Protection Agency (EPA) Guidance for Quality Assurance Project Plans for Modeling (EPA, 2002); and EPA Guidance on the Development, Evaluation, and Application of Environmental Models (EPA, 2009). The QAPP Revision 0 supersedes DOE--341, Underground Test Area Quality Assurance Project Plan, Nevada Test Site, Nevada, Revision 4.

  2. Technology development: HEPA filter service life test plan

    SciTech Connect (OSTI)

    Kirchner, K.N.; Cummings, K.G.; Leck, W.C.; Fretthold, J.K.

    1995-05-31

    Rocky Flats Environmental Technology Site (the Site) has approximately 10,000 High Efficiency Particulate Air (HEPA) Filters installed in a variety of filter plenums. These ventilation/filtration plenum systems are used to control the release of airborne particulate contaminates to the environment during normal operations and also during potential design-based accidents. The operational integrity of the HEPA filter plenums is essential to maintaining the margins of safety as required by building specific Final Safety Analysis Reports (FSARS) for protection of the public and environment. An Unreviewed Safety Question Determination (USQD), USDQ-RFP94.0615-ARS, was conducted in 1994 addressing the potential inadequacy of the safety envelope for Protected Area building HEPA plenums. While conducting this USQD, questions were raised concerning the maximum service life criteria for HEPA filters. Accident scenarios in existing FSARs identify conditions that could potentially cause plugging or damage of down stream HEPA filters as a result of impaction from failed filters. Additionally, available data indicates that HEPA filters experience structural degradation due to the effects of age. The Unresolved Safety Question (USQ) compensatory measures thus require testing and analysis of used HEPA filters in order to determine and implement service life criteria.

  3. OECD 2-D Core Concrete Interaction (CCI) tests : CCI-2 test plan, Rev. 0 January 31, 2004.

    SciTech Connect (OSTI)

    Farmer, M. T.; Kilsdonk, D. J.; Lomperski, S.; Aeschlimann, R. W.; Basu, S. (Nuclear Engineering Division)

    2011-05-23

    The Melt Attack and Coolability Experiments (MACE) program addressed the issue of the ability of water to cool and thermally stabilize a molten core-concrete interaction when the reactants are flooded from above. These tests provided data regarding the nature of corium interactions with concrete, the heat transfer rates from the melt to the overlying water pool, and the role of noncondensable gases in the mixing processes that contribute to melt quenching. As a follow-on program to MACE, The Melt Coolability and Concrete Interaction Experiments (MCCI) project is conducting reactor material experiments and associated analysis to achieve the following objectives: (1) resolve the ex-vessel debris coolability issue through a program that focuses on providing both confirmatory evidence and test data for the coolability mechanisms identified in MACE integral effects tests, and (2) address remaining uncertainties related to long-term two-dimensional molten core-concrete interactions under both wet and dry cavity conditions. Achievement of these two program objectives will demonstrate the efficacy of severe accident management guidelines for existing plants, and provide the technical basis for better containment designs for future plants. In terms of satisfying these objectives, the Management Board (MB) approved the conduct of two long-term 2-D Core-Concrete Interaction (CCI) experiments designed to provide information in several areas, including: (i) lateral vs. axial power split during dry core-concrete interaction, (ii) integral debris coolability data following late phase flooding, and (iii) data regarding the nature and extent of the cooling transient following breach of the crust formed at the melt-water interface. The first of these two tests, CCI-1, was conducted on December 19, 2003. This test investigated the interaction of a fully oxidized 400 kg PWR core melt, initially containing 8 wt % calcined siliceous concrete, with a specially designed two-dimensional siliceous concrete test section with an initial cross-sectional area of 50 cm x 50 cm. The second of these two planned tests, CCI-2, will be conducted with a nearly identical test facility and experiment boundary conditions, but with a Limestone/Common Sand (LCS) concrete test section to investigate the effect of concrete type on the two-dimensional core-concrete interaction and debris cooling behavior. The objective of this report is to provide the overall test plan for CCI-2 to enable pretest calculations to be carried out. The report begins by providing a summary description of the CCI-2 test apparatus, followed by a description of the planned test operating procedure. Overall specifications for CCI-2 are provided in Table 1-1.

  4. Deflagration studies on waste Tank 101-SY: Test plan

    SciTech Connect (OSTI)

    Cashdollar, K.L.; Zlochower, I.A.; Hertzberg, M.

    1991-07-01

    Waste slurries produced during the recovery of plutonium and uranium from irradiated fuel are stored in underground storage tanks. While a variety of waste types have been generated, of particular concern are the wastes stored in Tank 101-SY. A slurry growth-gas evolution cycle has been observed since 1981. The waste consists of a thick slurry, consisting of a solution high in NaOH, NaNO{sub 3}, NaAlO{sub 2}, dissolved organic complexants (EDTA, HEDTA, NTA, and degradation products), other salts (sulfates and phosphates), and radionuclides (primarily cesium and strontium). During a gas release the major gaseous species identified include: hydrogen and nitrous oxide (N{sub 2}O). Significant amounts of nitrogen may also be present. Traces of ammonia, carbon oxides, and other nitrogen oxides are also detected. Air and water vapor are also present in the tank vapor space. The purpose of the deflagration study is to determine risks of the hydrogen, nitrous oxide, nitrogen, and oxygen system. To be determined are pressure and temperature as a function of composition of reacting gases and the concentration of gases before and after the combustion event. Analyses of gases after the combustion event will be restricted to those tests that had an initial concentration of {le}8% hydrogen. This information will be used to evaluate safety issues related to periodic slurry growth and flammable gas releases from Tank 101-SY. the conditions to be evaluated will simulate gases in the vapor space above the salt cake as well as gases that potentially are trapped in pockets within/under the waste. The deflagration study will relate experimental laboratory results to conditions in the existing tanks.

  5. Pilot-scale treatability test plan for the 200-BP-5 operable unit

    SciTech Connect (OSTI)

    Not Available

    1994-08-01

    This document presents the treatability test plan for pilot-scale pump and treat testing at the 200-BP-5 Operable Unit. This treatability test plan has been prepared in response to an agreement between the U.S. Department of Energy (DOE), the U.S. Environmental Protection Agency (EPA), and the State of Washington Department of Ecology (Ecology), as documented in Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement, Ecology et al. 1989a) Change Control Form M-13-93-03 (Ecology et al. 1994) and a recent 200 NPL Agreement Change Control Form (Appendix A). The agreement also requires that, following completion of the activities described in this test plan, a 200-BP-5 Operable Unit Interim Remedial Measure (IRM) Proposed Plan be developed for use in preparing an Interim Action Record of Decision (ROD). The IRM Proposed Plan will be supported by the results of this treatability test plan, as well as by other 200-BP-5 Operable Unit activities (e.g., development of a qualitative risk assessment). Once issued, the Interim Action ROD will specify the interim action(s) for groundwater contamination at the 200-BP-5 Operable Unit. The treatability test approach is to conduct a pilot-scale pump and treat test for each of the two contaminant plumes associated with the 200-BP-5 Operable Unit. Primary contaminants of concern are {sup 99}Tc and {sup 60}Co for underwater affected by past discharges to the 216-BY Cribs, and {sup 90}Sr, {sup 239/240}Pu, and Cs for groundwater affected by past discharges to the 216-B-5 Reverse Well. The purpose of the pilot-scale treatability testing presented in this testplan is to provide the data basis for preparing an IRM Proposed Plan. To achieve this objective, treatability testing must: Assess the performance of groundwater pumping with respect to the ability to extract a significant amount of the primary contaminant mass present in the two contaminant plumes.

  6. Technical task plan for testing filter box sorbent-paint filter test

    SciTech Connect (OSTI)

    Kilpatrick, L.L.

    1993-09-01

    At the Savannah River Plant, High Level Waste Engineering (HLWE) asked Interim Waste Technology (IWT) to choose and test a sorbent to add to the ITP filter box that meets the EPA requirement for land disposal of containerized liquid hazardous wastes per Paint Filter Liquids (PFL) test method 9095. This report outlines the process to be used in accomplishing this task.

  7. Pilot-scale treatability test plan for the 100-HR-3 operable unit

    SciTech Connect (OSTI)

    Not Available

    1994-08-01

    This document presents the treatability test plan for pilot-scale pump-and-treat testing at the 100-HR-3 Operable Unit. The test will be conducted in fulfillment of interim Milestone M-15-06E to begin pilot-scale pump-and-treat operations by August 1994. The scope of the test was determined based on the results of lab/bench-scale tests (WHC 1993a) conducted in fulfillment of Milestone M-15-06B. These milestones were established per agreement between the U.S. Department of Energy (DOE), the Washington State Department of Ecology and the U.S. Environmental Protection Agency (EPA), and documented on Hanford Federal of Ecology Facility Agreement and Consent Order Change Control Form M-15-93-02. This test plan discusses a pilot-scale pump-and-treat test for the chromium plume associated with the D Reactor portion of the 100-HR-3 Operable Unit. Data will be collected during the pilot test to assess the effectiveness, operating parameters, and resource needs of the ion exchange (IX) pump-and-treat system. The test will provide information to assess the ability to remove contaminants by extracting groundwater from wells and treating extracted groundwater using IX. Bench-scale tests were conducted previously in which chromium VI was identified as the primary contaminant of concern in the 100-D reactor plume. The DOWEX 21K{trademark} resin was recommended for pilot-scale testing of an IX pump-and-treat system. The bench-scale test demonstrated that the system could remove chromium VI from groundwater to concentrations less than 50 ppb. The test also identified process parameters to monitor during pilot-scale testing. Water will be re-injected into the plume using wells outside the zone of influence and upgradient of the extraction well.

  8. Corrective Action Plan for Corrective Action Unit 424: Area 3 Landfill Complex, Tonopah Test Range, Nevada

    SciTech Connect (OSTI)

    Bechtel Nevada

    1998-08-31

    This corrective action plan provides the closure implementation methods for the Area 3 Landfill Complex, Corrective Action Unit (CAU) 424, located at the Tonopah Test Range. The Area 3 Landfill Complex consists of 8 landfill sites, each designated as a separate corrective action site.

  9. Batteries put to test in PV plan The technology could help utilities absorb

    E-Print Network [OSTI]

    Batteries put to test in PV plan The technology could help utilities absorb more power and assist to see whether battery technology can be effectively used to open the utility's grid to greater amounts statewide, investigating how battery technology can be used to overcome limits on the amount of intermittent

  10. Brine migration test for Asse Mine, Federal Republic of Germany: final test plan

    SciTech Connect (OSTI)

    Not Available

    1983-07-01

    The United States and the Federal Republic of Germany (FRG) will conduct a brine migration test in the Asse Salt Mine in the FRG as part of the US/FRG Cooperative Radioactive Waste Management Agreement. Two sets of two tests each will be conducted to study both liquid inclusion migration and vapor migration in the two salt types chosen for the experiments: (1) pure salt, for its characteristics similar to the salt that might occur in potential US repositories, and (2) transitional salt, for its similarity to the salt that might occur in potential repositories in Germany.

  11. Test plan: Laboratory-scale testing of the first core sample from Tank 102-AZ

    SciTech Connect (OSTI)

    Morrey, E.V.

    1996-03-01

    The overall objectives of the Radioactive Process/Product Laboratory Testing (RPPLT), WBS 1.2.2.05.05, are to confirm that simulated HWVP feed and glass are representative of actual radioactive HWVP feed and glass and to provide radioactive leaching and glass composition data to WFQ. This study will provide data from one additional NCAW core sample (102-AZ Core 1) for these purposes.

  12. AZ-101 Mixer Pump Demonstration and Tests Data Management Analysis Plan

    SciTech Connect (OSTI)

    DOUGLAS, D.G.

    2000-02-22

    This document provides a plan for the analysis of the data collected during the AZ-101 Mixer Pump Demonstration and Tests. This document was prepared after a review of the AZ-101 Mixer Pump Test Plan (Revision 4) [1] and other materials. The plan emphasizes a structured and well-ordered approach towards handling and examining the data. This plan presumes that the data will be collected and organized into a unified body of data, well annotated and bearing the date and time of each record. The analysis of this data will follow a methodical series of steps that are focused on well-defined objectives. Section 2 of this plan describes how the data analysis will proceed from the real-time monitoring of some of the key sensor data to the final analysis of the three-dimensional distribution of suspended solids. This section also identifies the various sensors or sensor systems and associates them with the various functions they serve during the test program. Section 3 provides an overview of the objectives of the AZ-101 test program and describes the data that will be analyzed to support that test. The objectives are: (1) to demonstrate that the mixer pumps can be operated within the operating requirements; (2) to demonstrate that the mixer pumps can mobilize the sludge in sufficient quantities to provide feed to the private contractor facility, and (3) to determine if the in-tank instrumentation is sufficient to monitor sludge mobilization and mixer pump operation. Section 3 also describes the interim analysis that organizes the data during the test, so the analysis can be more readily accomplished. Section 4 describes the spatial orientation of the various sensors in the tank. This section is useful in visualizing the relationship of the Sensors in terms of their location in the tank and how the data from these sensors may be related to the data from other sensors. Section 5 provides a summary of the various analyses that will be performed on the data during the test program. Finally, an appendix reviews the technical aspects of the key sensor systems that will be used in the program. This review focuses on the performance capabilities and limits of the sensing systems.

  13. Vadose Zone Transport Field Study: Detailed Test Plan for Simulated Leak Tests

    SciTech Connect (OSTI)

    Ward, Anderson L.; Gee, Glendon W.

    2000-06-23

    This report describes controlled transport experiments at well-instrumented field tests to be conducted during FY 2000 in support of DOE?s Vadose Zone Transport Field Study (VZTFS). The VZTFS supports the Groundwater/Vadose Zone Integration Project Science and Technology Initiative. The field tests will improve understanding of field-scale transport and lead to the development or identification of efficient and cost-effective characterization methods. These methods will capture the extent of contaminant plumes using existing steel-cased boreholes. Specific objectives are to 1) identify mechanisms controlling transport processes in soils typical of the hydrogeologic conditions of Hanford?s waste disposal sites; 2) reduce uncertainty in conceptual models; 3) develop a detailed and accurate data base of hydraulic and transport parameters for validation of three-dimensional numerical models; and 4) identify and evaluate advanced, cost-effective characterization methods with the potential to assess changing conditions in the vadose zone, particularly as surrogates of currently undetectable high-risk contaminants. Pacific Northwest National Laboratory (PNNL) manages the VZTFS for DOE.

  14. AFCI Fuel Irradiation Test Plan, Test Specimens AFC-1Æ and AFC-1F

    SciTech Connect (OSTI)

    D. C. Crawford; S. L. Hayes; B. A. Hilton; M. K. Meyer; R. G. Ambrosek; G. S. Chang; D. J. Utterbeck

    2003-11-01

    The U. S. Advanced Fuel Cycle Initiative (AFCI) seeks to develop and demonstrate the technologies needed to transmute the long-lived transuranic actinide isotopes contained in spent nuclear fuel into shorter-lived fission products, thereby dramatically decreasing the volume of material requiring disposition and the long-term radiotoxicity and heat load of high-level waste sent to a geologic repository (DOE, 2003). One important component of the technology development is actinide-bearing transmutation fuel forms containing plutonium, neptunium, americium (and possibly curium) isotopes. There are little irradiation performance data available on non-fertile fuel forms, which would maximize the destruction rate of plutonium, and low-fertile (i.e., uranium-bearing) fuel forms, which would support a sustainable nuclear energy option. Initial scoping level irradiation tests on a variety of candidate fuel forms are needed to establish a transmutation fuel form design and evaluate deployment of transmutation fuels.

  15. Resource Conservation and Recovery Act Industrial Sites quality assurance project plan: Nevada Test Site, Nevada

    SciTech Connect (OSTI)

    Not Available

    1994-06-01

    This quality assurance project plan (QAPjP) describes the measures that shall be taken to ensure that the environmental data collected during characterization and closure activities of Resource Conservation and Recovery Act (RCRA) Industrial Sites at the Nevada Test Site (NTS) are meaningful, valid, defensible, and can be used to achieve project objectives. These activities are conducted by the US Department of Energy Nevada Operations Office (DOE/NV) under the Nevada Environmental Restoration (ER) Project. The Nevada ER Project consists of environmental restoration activities on the NTS, Tonopah Test Range, Nellis Air Force Range, and eight sites in five other states. The RCRA Industrial Sites subproject constitutes a component of the Nevada ER Project. Currently, this QAPjP is limited to the seven RCRA Industrial Sites identified within this document that are to be closed under an interim status and pertains to all field-investigation, analytical-laboratory, and data-review activities in support of these closures. The information presented here supplements the RCRA Industrial Sites Project Management Plan and is to be used in conjunction with the site-specific subproject sampling and analysis plans.

  16. Status and Plans for an SRF Accelerator Test Facility at Fermilab

    SciTech Connect (OSTI)

    Church, M.; Leibfritz, J.; Nagaitsev, S.; /Fermilab

    2011-07-29

    A superconducting RF accelerator test facility is currently under construction at Fermilab. The accelerator will consist of an electron gun, 40 MeV injector, beam acceleration section consisting of 3 TTF-type or ILC-type cryomodules, and multiple downstream beam lines for testing diagnostics and performing beam experiments. With 3 cryomodules installed this facility will initially be capable of generating an 810 MeV electron beam with ILC beam intensity. The facility can accommodate up to 6 cryomodules for a total beam energy of 1.5 GeV. This facility will be used to test SRF cryomodules under high intensity beam conditions, RF power equipment, instrumentation, and LLRF and controls systems for future SRF accelerators such as the ILC and Project-X. This paper describes the current status and overall plans for this facility.

  17. Quality Assurance Program Plan for TRUPACT-II Gas Generation Test Program

    SciTech Connect (OSTI)

    Carlsbad Field Office

    2002-03-01

    The Gas Generation Test Program (GGTP), referred to as the Program, is designed to establish the concentration of flammable gases and/or gas generation rates in a test category waste container intended for shipment in the Transuranic Package Transporter-II (TRUPACT-II). The phrase "gas generationtesting" shall refer to any activity that establishes the flammable gas concentration or the flammable gas generation rate. This includes, but is not limited to, measurements performed directly on waste containers or during tests performed on waste containers. This Quality Assurance Program Plan (QAPP) documents the quality assurance (QA) and quality control (QC) requirements that apply to the Program. The TRUPACT-II requirements and technical bases for allowable flammable gas concentration and gas generation rates are described in the TRUPACT-II Authorized Methods for Payload Control (TRAMPAC).

  18. Test Planning for Mixed-Signal SOCs with Wrapped Analog Cores Anuja Sehgal, Fang Liu, Sule Ozev and Krishnendu Chakrabarty

    E-Print Network [OSTI]

    Paris-Sud XI, Université de

    Test Planning for Mixed-Signal SOCs with Wrapped Analog Cores Anuja Sehgal, Fang Liu, Sule Ozev. Even though the test cost for such mixed-signal SOCs is significantly higher than that for digital SOCs, most prior research in this area has focused exclusively on digital cores. We propose a low-cost test

  19. Status of the direct absorption receiver panel research experiment: Salt flow and solar test requirements and plans

    SciTech Connect (OSTI)

    Tyner, C.E.

    1989-03-01

    The Panel Research Experiment (PRE) is the first large-scale solar test of the molten nitrate salt direct absorption receiver (DAR) concept. The purpose of the PRE is to demonstrate the engineering feasibility and practicality of the DAR. We will conduct the test at the Central Receiver Test Facility in Albuquerque in two phases: salt flow testing and solar testing. This is a working document to define PRE test objectives and requirements, document the test hardware design, and define test plans. 13 refs., 12 figs., 1 tab.

  20. Status and Plans for a Superconducting RF Accelerator Test Facility at Fermilab

    SciTech Connect (OSTI)

    Leibfritz, J.; Andrews, R.; Baffes, C.M.; Carlson, K.; Chase, B.; Church, M.D.; Harms, E.R.; Klebaner, A.L.; Kucera, M.; Martinez, A.; Nagaitsev, S.; /Fermilab

    2012-05-01

    The Advanced Superconducting Test Accelerator (ASTA) is being constructed at Fermilab. The existing New Muon Lab (NML) building is being converted for this facility. The accelerator will consist of an electron gun, injector, beam acceleration section consisting of 3 TTF-type or ILC-type cryomodules, multiple downstream beam lines for testing diagnostics and conducting various beam tests, and a high power beam dump. When completed, it is envisioned that this facility will initially be capable of generating a 750 MeV electron beam with ILC beam intensity. An expansion of this facility was recently completed that will provide the capability to upgrade the accelerator to a total beam energy of 1.5 GeV. Two new buildings were also constructed adjacent to the ASTA facility to house a new cryogenic plant and multiple superconducting RF (SRF) cryomodule test stands. In addition to testing accelerator components, this facility will be used to test RF power systems, instrumentation, and control systems for future SRF accelerators such as the ILC and Project-X. This paper describes the current status and overall plans for this facility.

  1. Chemical Reactivity Testing for the National Spent Nuclear Fuel Program. Quality Assurance Project Plan

    SciTech Connect (OSTI)

    Newsom, H.C.

    1999-01-24

    This quality assurance project plan (QAPjP) summarizes requirements used by Lockheed Martin Energy Systems, Incorporated (LMES) Development Division at Y-12 for conducting chemical reactivity testing of Department of Energy (DOE) owned spent nuclear fuel, sponsored by the National Spent Nuclear Fuel Program (NSNFP). The requirements are based on the NSNFP Statement of Work PRO-007 (Statement of Work for Laboratory Determination of Uranium Hydride Oxidation Reaction Kinetics.) This QAPjP will utilize the quality assurance program at Y-12, QA-101PD, revision 1, and existing implementing procedures for the most part in meeting the NSNFP Statement of Work PRO-007 requirements, exceptions will be noted.

  2. Test plan for non-radioactive testing of vertical calciner for development of direct denitration conversion of Pu-bearing liquors to stable, storage solids

    SciTech Connect (OSTI)

    Fisher, F.D.

    1995-03-30

    Plutonium-bearing liquors, including ANL scrap liquors, will be used for development and demonstration of a vertical calciner direct denitration process for conversion of those liquors to stable, storable PuO{sub 2}-rich solids. This test plan is to test with non-radioactive stand-in materials to demonstrate adequate performance of the vertical calciner and ancillary equipment.

  3. Testing and monitoring plan for the permanent isolation surface barrier prototype

    SciTech Connect (OSTI)

    Gee, G.W.; Cadwell, L.L.; Freeman, H.D.; Ligotke, M.W.; Link, S.O.; Romine, R.A.; Walters, W.H. Jr.

    1993-06-01

    This document is a testing and monitoring plan for a prototype barrier to be constructed at the Hanford Site in 1993. The prototype barrier is an aboveground structure engineered to demonstrate the basic features of an earthen cover system, designed to permanently isolate waste from the biosphere. These features include multiple layers of soil and rock materials and a low-permeability asphalt sublayer. The surface of the barrier consists of silt loam soil, vegetated with plants. The barrier sides are reinforced with rock or coarse earthen-fill to protect against wind and water erosion. The sublayers inhibit plant and animal intrusion and percolation of water. A series of tests will be conducted on the prototype over the next several years to evaluate barrier performance under extreme climatic conditions.

  4. Accepted for publication Microelectronics Reliability February 1, 2014 Assessing the value of a lead-free solder control plan using cost-

    E-Print Network [OSTI]

    Sandborn, Peter

    of a lead-free solder control plan using cost- based FMEA Edwin Lilliea , Peter Sandborna , David Humphreyb choose or be required to perform to ensure product performance. This paper uses cost-based FMEA

  5. Supplemental Investigation Plan for FFACO Use Restrictions, Nevada Test Site, Nevada, Revision 0

    SciTech Connect (OSTI)

    Lynn Kidman

    2008-02-01

    This document is part of an effort to re-evaluate all FFACO URs against the current RBCA criteria (referred to in this document as the Industrial Sites [IS] RBCA process) as defined in the Industrial Sites Project Establishment of Final Action Levels (NNSA/NSO, 2006a). After reviewing all of the existing FFACO URs, the 12 URs addressed in this Supplemental Investigation Plan (SIP) could not be evaluated against the current RBCA criteria as sufficient information about the contamination at each site was not available. This document presents the plan for conducting field investigations to obtain the needed information. This SIP includes URs from Corrective Action Units (CAUs) 326, 339, 358, 452, 454, 464, and 1010, located in Areas 2, 6, 12, 19, 25, and 29 of the Nevada Test Site, which is approximately 65 miles northwest of Las Vegas, Nevada; and CAU 403, located in Area 3 of the Tonopah Test Range, which is approximately 165 miles north of Las Vegas, Nevada.

  6. HWMA/RCRA CLOSURE PLAN FOR THE MATERIALS TEST REACTOR WING (TRA-604) LABORATORY COMPONENTS VOLUNTARY CONSENT ORDER ACTION PLAN VCO-5.8 D REVISION2

    SciTech Connect (OSTI)

    KIRK WINTERHOLLER

    2008-02-25

    This Hazardous Waste Management Act/Resource Conservation and Recovery Act closure plan was developed for the laboratory components of the Test Reactor Area Catch Tank System (TRA-630) that are located in the Materials Test Reactor Wing (TRA-604) at the Reactor Technology Complex, Idaho National Laboratory Site, to meet a further milestone established under Voluntary Consent Order Action Plan VCO-5.8.d. The TRA-604 laboratory components addressed in this closure plan were deferred from the TRA-630 Catch Tank System closure plan due to ongoing laboratory operations in the areas requiring closure actions. The TRA-604 laboratory components include the TRA-604 laboratory warm wastewater drain piping, undersink drains, subheaders, and the east TRA-604 laboratory drain header. Potentially contaminated surfaces located beneath the TRA-604 laboratory warm wastewater drain piping and beneath the island sinks located in Laboratories 126 and 128 (located in TRA-661) are also addressed in this closure plan. The TRA-604 laboratory components will be closed in accordance with the interim status requirements of the Hazardous Waste Management Act/Resource Conservation and Recovery Act as implemented by the Idaho Administrative Procedures Act 58.01.05.009 and 40 Code of Federal Regulations 265, Subparts G and J. This closure plan presents the closure performance standards and the methods for achieving those standards.

  7. Corrective action investigation plan for Central Nevada Test Area, CAU No. 417

    SciTech Connect (OSTI)

    NONE

    1997-04-01

    This Corrective Action Investigation Plan (CAIP) is part of a US Department of Energy (DOE)-funded environmental investigation of the Central Nevada Test Area (CNTA). This CAIP addresses the surface investigation and characterization of 15 identified Corrective Action Sites (CASs). In addition, several other areas of the CNTA project area have surface expressions that may warrant investigation. These suspect areas will be characterized, if necessary, in subsequent CAIPs or addendums to this CAIP prepared to address these sites. This CAIP addresses only the 15 identified CASs as shown in Table 2-1 that are associated with the drilling and construction of a number of testing wells designed as part of an underground nuclear testing program. The purpose of the wells at the time of construction was to provide subsurface access for the emplacement, testing, and post detonation evaluations of underground nuclear devices. If contamination is found at any of the 15-surface CASs, the extent of contamination will be determined in order to develop an appropriate corrective action.

  8. Independent Verification and Validation Of SAPHIRE 8 System Test Plan Project Number: N6423 U.S. Nuclear Regulatory Commission

    SciTech Connect (OSTI)

    Kent Norris

    2010-02-01

    The purpose of the Independent Verification and Validation (IV&V) role in the evaluation of the SAPHIRE System Test Plan is to assess the approach to be taken for intended testing activities associated with the SAPHIRE software product. The IV&V team began this endeavor after the software engineering and software development of SAPHIRE had already been in production.

  9. Continuing the Validation of CCIM Processability for Glass Ceramic HLLW Forms: Plan for Test AFY14CCIM-GC1

    SciTech Connect (OSTI)

    Vince Maio

    2014-04-01

    This test plan covers test AFY14CCIM-GC1which is the first of two scheduled FY-2014 test runs involving glass ceramic waste forms in the Idaho National Laboratory’s Cold Crucible Induction Melter Pilot Plant. The test plan is based on the successes and challenges of previous tests performed in FY-2012 and FY-2013. The purpose of this test is to continue to collect data for validating the glass ceramic High Level Liquid Waste form processability advantages using Cold Crucible Induction Melter technology. The major objective of AFYCCIM-GC1 is to complete additional proposed crucible pouring and post tapping controlled cooling experiments not completed during previous tests due to crucible drain failure. This is necessary to qualify that no heat treatments in standard waste disposal canisters are necessary for the operational scale production of glass ceramic waste forms. Other objectives include the production and post-test analysis of surrogate waste forms made from separate pours into the same graphite mold canister, testing the robustness of an upgraded crucible bottom drain and drain heater assembly, testing the effectiveness of inductive melt initiation using a resistive starter ring with a square wave configuration, and observing the tapped molten flow behavior in pans with areas identical to standard High Level Waste disposal canisters. Testing conditions, the surrogate waste composition, key testing steps, testing parameters, and sampling and analysis requirements are defined.

  10. Underground Test Area Activity Quality Assurance Plan Nevada National Security Site, Nevada. Revision 1

    SciTech Connect (OSTI)

    Farnham, Irene; Krenzien, Susan

    2012-10-01

    This Quality Assurance Plan (QAP) provides the overall quality assurance (QA) requirements and general quality practices to be applied to the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office (NNSA/NSO) Underground Test Area (UGTA) activities. The requirements in this QAP are consistent with DOE Order 414.1C, Quality Assurance (DOE, 2005); U.S. Environmental Protection Agency (EPA) Guidance for Quality Assurance Project Plans for Modeling (EPA, 2002); and EPA Guidance on the Development, Evaluation, and Application of Environmental Models (EPA, 2009). NNSA/NSO, or designee, must review this QAP every two years. Changes that do not affect the overall scope or requirements will not require an immediate QAP revision but will be incorporated into the next revision cycle after identification. Section 1.0 describes UGTA objectives, participant responsibilities, and administrative and management quality requirements (i.e., training, records, procurement). Section 1.0 also details data management and computer software requirements. Section 2.0 establishes the requirements to ensure newly collected data are valid, existing data uses are appropriate, and environmental-modeling methods are reliable. Section 3.0 provides feedback loops through assessments and reports to management. Section 4.0 provides the framework for corrective actions. Section 5.0 provides references for this document.

  11. Underground Test Area Activity Quality Assurance Plan Nevada National Security Site, Nevada. Revision 2

    SciTech Connect (OSTI)

    Krenzien, Susan; Farnham, Irene

    2015-06-01

    This Quality Assurance Plan (QAP) provides the overall quality assurance (QA) requirements and general quality practices to be applied to the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Field Office (NNSA/NFO) Underground Test Area (UGTA) activities. The requirements in this QAP are consistent with DOE Order 414.1D, Change 1, Quality Assurance (DOE, 2013a); U.S. Environmental Protection Agency (EPA) Guidance for Quality Assurance Project Plans for Modeling (EPA, 2002); and EPA Guidance on the Development, Evaluation, and Application of Environmental Models (EPA, 2009). If a participant’s requirement document differs from this QAP, the stricter requirement will take precedence. NNSA/NFO, or designee, must review this QAP every two years. Changes that do not affect the overall scope or requirements will not require an immediate QAP revision but will be incorporated into the next revision cycle after identification. Section 1.0 describes UGTA objectives, participant responsibilities, and administrative and management quality requirements (i.e., training, records, procurement). Section 1.0 also details data management and computer software requirements. Section 2.0 establishes the requirements to ensure newly collected data are valid, existing data uses are appropriate, and environmental-modeling methods are reliable. Section 3.0 provides feedback loops through assessments and reports to management. Section 4.0 provides the framework for corrective actions. Section 5.0 provides references for this document.

  12. Industrial Sites Work Plan for Leachfield Corrective Action Units: Nevada Test Site and Tonopah Test Range, Nevada (including Record of Technical Change Nos. 1, 2, 3, and 4)

    SciTech Connect (OSTI)

    DOE/NV

    1998-12-18

    This Leachfield Corrective Action Units (CAUs) Work Plan has been developed in accordance with the Federal Facility Agreement and Consent Order (FFACO) that was agreed to by the U.S. Department of Energy, Nevada Operations Office (DOE/NV); the State of Nevada Division of Environmental Protection (NDEP); and the U.S. Department of Defense (FFACO, 1996). Under the FFACO, a work plan is an optional planning document that provides information for a CAU or group of CAUs where significant commonality exists. A work plan may be developed that can be referenced by leachfield Corrective Action Investigation Plans (CAIPs) to eliminate redundant CAU documentation. This Work Plan includes FFACO-required management, technical, quality assurance (QA), health and safety, public involvement, field sampling, and waste management documentation common to several CAUs with similar site histories and characteristics, namely the leachfield systems at the Nevada Test Site (NTS) and the Tonopah Test Range (TT R). For each CAU, a CAIP will be prepared to present detailed, site-specific information regarding contaminants of potential concern (COPCs), sampling locations, and investigation methods.

  13. Fuel and core testing plan for a target fueled isotope production reactor.

    SciTech Connect (OSTI)

    Coats, Richard Lee; Dahl, James J.; Parma, Edward J., Jr.

    2010-12-01

    In recent years there has been an unstable supply of the critical diagnostic medical isotope 99Tc. Several concepts and designs have been proposed to produce 99Mo the parent nuclide of 99Tc, at a commercial scale sufficient to stabilize the world supply. This work lays out a testing and experiment plan for a proposed 2 MW open pool reactor fueled by Low Enriched Uranium (LEU) 99Mo targets. The experiments and tests necessary to support licensing of the reactor design are described and how these experiments and tests will help establish the safe operating envelop for a medical isotope production reactor is discussed. The experiments and tests will facilitate a focused and efficient licensing process in order to bring on line a needed production reactor dedicated to supplying medical isotopes. The Target Fuel Isotope Reactor (TFIR) design calls for an active core region that is approximately 40 cm in diameter and 40 cm in fuel height. It contains up to 150 cylindrical, 1-cm diameter, LEU oxide fuel pins clad with Zircaloy (zirconium alloy), in an annular hexagonal array on a {approx}2.0 cm pitch surrounded, radially, by a graphite or a Be reflector. The reactor is similar to U.S. university reactors in power, hardware, and safety/control systems. Fuel/target pin fabrication is based on existing light water reactor fuel fabrication processes. However, as part of licensing process, experiments must be conducted to confirm analytical predictions of steady-state power and accident conditions. The experiment and test plan will be conducted in phases and will utilize existing facilities at the U.S. Department of Energy's Sandia National Laboratories. The first phase is to validate the predicted reactor core neutronics at delayed critical, zero power and very low power. This will be accomplished by using the Sandia Critical Experiment (CX) platform. A full scale TFIR core will be built in the CX and delayed critical measurements will be taken. For low power experiments, fuel pins can be removed after the experiment and using Sandia's metrology lab, relative power profiles (radially and axially) can be determined. In addition to validating neutronic analyses, confirming heat transfer properties of the target/fuel pins and core will be conducted. Fuel/target pin power limits can be verified with out-of-pile (electrical heating) thermal-hydraulic experiments. This will yield data on the heat flux across the Zircaloy clad and establish safety margin and operating limits. Using Sandia's Annular Core Research Reactor (ACRR) a 4 MW TRIGA type research reactor, target/fuel pins can be driven to desired fission power levels for long durations. Post experiment inspection of the pins can be conducted in the Auxiliary Hot Cell Facility to observe changes in the mechanical properties of the LEU matrix and burn-up effects. Transient tests can also be conducted at the ACRR to observe target/fuel pin performance during accident conditions. Target/fuel pins will be placed in double experiment containment and driven by pulsing the ACRR until target/fuel failure is observed. This will allow for extrapolation of analytical work to confirm safety margins.

  14. Modeling and Field Test Planning Activities in Support of Disposal of Heat-Generating Waste in Salt

    SciTech Connect (OSTI)

    Rutqvist, Jonny; Blanco Martin, Laura; Mukhopadhyay, Sumit; Houseworth, Jim; Birkholzer, Jens

    2014-09-26

    The modeling efforts in support of the field test planning conducted at LBNL leverage on recent developments of tools for modeling coupled thermal-hydrological-mechanical-chemical (THMC) processes in salt and their effect on brine migration at high temperatures. This work includes development related to, and implementation of, essential capabilities, as well as testing the model against relevant information and published experimental data related to the fate and transport of water. These are modeling capabilities that will be suitable for assisting in the design of field experiment, especially related to multiphase flow processes coupled with mechanical deformations, at high temperature. In this report, we first examine previous generic repository modeling results, focusing on the first 20 years to investigate the expected evolution of the different processes that could be monitored in a full-scale heater experiment, and then present new results from ongoing modeling of the Thermal Simulation for Drift Emplacement (TSDE) experiment, a heater experiment on the in-drift emplacement concept at the Asse Mine, Germany, and provide an update on the ongoing model developments for modeling brine migration. LBNL also supported field test planning activities via contributions to and technical review of framework documents and test plans, as well as participation in workshops associated with field test planning.

  15. Corrective Action Plan for Corrective Action Unit 417: Central Nevada Test Area Surface, Nevada

    SciTech Connect (OSTI)

    K. Campbell

    2000-04-01

    This Corrective Action Plan provides methods for implementing the approved corrective action alternative as provided in the Corrective Action Decision Document for the Central Nevada Test Area (CNTA), Corrective Action Unit (CAU) 417 (DOE/NV, 1999). The CNTA is located in the Hot Creek Valley in Nye County, Nevada, approximately 137 kilometers (85 miles) northeast of Tonopah, Nevada. The CNTA consists of three separate land withdrawal areas commonly referred to as UC-1, UC-3, and UC-4, all of which are accessible to the public. CAU 417 consists of 34 Corrective Action Sites (CASs). Results of the investigation activities completed in 1998 are presented in Appendix D of the Corrective Action Decision Document (DOE/NV, 1999). According to the results, the only Constituent of Concern at the CNTA is total petroleum hydrocarbons (TPH). Of the 34 CASs, corrective action was proposed for 16 sites in 13 CASs. In fiscal year 1999, a Phase I Work Plan was prepared for the construction of a cover on the UC-4 Mud Pit C to gather information on cover constructibility and to perform site management activities. With Nevada Division of Environmental Protection concurrence, the Phase I field activities began in August 1999. A multi-layered cover using a Geosynthetic Clay Liner as an infiltration barrier was constructed over the UC-4 Mud Pit. Some TPH impacted material was relocated, concrete monuments were installed at nine sites, signs warning of site conditions were posted at seven sites, and subsidence markers were installed on the UC-4 Mud Pit C cover. Results from the field activities indicated that the UC-4 Mud Pit C cover design was constructable and could be used at the UC-1 Central Mud Pit (CMP). However, because of the size of the UC-1 CMP this design would be extremely costly. An alternative cover design, a vegetated cover, is proposed for the UC-1 CMP.

  16. Project Management Plan for the Idaho National Engineering Laboratory Waste Isolation Pilot Plant Experimental Test Program

    SciTech Connect (OSTI)

    Connolly, M.J.; Sayer, D.L.

    1993-11-01

    EG&G Idaho, Inc. and Argonne National Laboratory-West (ANL-W) are participating in the Idaho National Engineering Laboratory`s (INEL`s) Waste Isolation Pilot Plant (WIPP) Experimental Test Program (WETP). The purpose of the INEL WET is to provide chemical, physical, and radiochemical data on transuranic (TRU) waste to be stored at WIPP. The waste characterization data collected will be used to support the WIPP Performance Assessment (PA), development of the disposal No-Migration Variance Petition (NMVP), and to support the WIPP disposal decision. The PA is an analysis required by the Code of Federal Regulations (CFR), Title 40, Part 191 (40 CFR 191), which identifies the processes and events that may affect the disposal system (WIPP) and examines the effects of those processes and events on the performance of WIPP. A NMVP is required for the WIPP by 40 CFR 268 in order to dispose of land disposal restriction (LDR) mixed TRU waste in WIPP. It is anticipated that the detailed Resource Conservation and Recovery Act (RCRA) waste characterization data of all INEL retrievably-stored TRU waste to be stored in WIPP will be required for the NMVP. Waste characterization requirements for PA and RCRA may not necessarily be identical. Waste characterization requirements for the PA will be defined by Sandia National Laboratories. The requirements for RCRA are defined in 40 CFR 268, WIPP RCRA Part B Application Waste Analysis Plan (WAP), and WIPP Waste Characterization Program Plan (WWCP). This Project Management Plan (PMP) addresses only the characterization of the contact handled (CH) TRU waste at the INEL. This document will address all work in which EG&G Idaho is responsible concerning the INEL WETP. Even though EG&G Idaho has no responsibility for the work that ANL-W is performing, EG&G Idaho will keep a current status and provide a project coordination effort with ANL-W to ensure that the INEL, as a whole, is effectively and efficiently completing the requirements for WETP.

  17. Integrated Closure and Monitoring Plan for the Area 3 and Area 5 Radioactive Waste Management Sites at the Nevada Test Site

    SciTech Connect (OSTI)

    Bechtel Nevada

    2005-06-01

    This document is an integrated plan for closing and monitoring two low-level radioactive waste disposal sites at the Nevada Test Site.

  18. Testing three health impact assessment tools in planning: A process evaluation

    SciTech Connect (OSTI)

    Schively Slotterback, Carissa; Forsyth, Ann; Krizek, Kevin J.; Johnson, Amanda; Pennucci, Aly

    2011-03-15

    There is increasing interest in Health Impact Assessment in planning. This paper describes the results of different approaches to health impact assessment (HIA) conducted in 10 municipalities and one county in Minnesota. The paper outlines the HIA processes, outputs, and short-term outcomes concluding that it is important to engage a diverse group of stakeholders. Overall, HIA is potentially an important new tool in the planning toolkit. Strategic use of HIA to evaluate draft plans and inform plan updates and project redesigns can help raise awareness about health issues and focus planning on important human problems.

  19. Milestone Report - M4FT-14OR0312022 - Co-absorption studies - Design system complete/test plan complete

    SciTech Connect (OSTI)

    Bruffey, Stephanie H.; Spencer, Barry B.; Jubin, Robert Thomas

    2013-12-01

    The objective of this test plan is to describe research that will determine the effectiveness of silver mordenite and molecular sieve beds to remove iodine and water (tritium) from off-gas streams arising from used nuclear fuel recycling processes, and to demonstrate that the iodine and water can be recovered separately from one another.

  20. Test plan for evaluation of plasma melter technology for vitrification of high-sodium content low-level radioactive liquid wastes

    SciTech Connect (OSTI)

    McLaughlin, D.F.; Lahoda, E.J.; Gass, W.R.; D`Amico, N.

    1994-10-20

    This document provides a test plan for the conduct of plasma arc vitrification testing by a vendor in support of the Hanford Tank Waste Remediation System (TWRS) Low-Level Waste (LLW) Vitrification Program. The vendor providing this test plan and conducting the work detailed within it [one of seven selected for glass melter testing under Purchase Order MMI-SVV-384212] is the Westinghouse Science and Technology Center (WSTC) in Pittsburgh, PA. WSTC authors of the test plan are D. F. McLaughlin, E. J. Lahoda, W. R. Gass, and N. D`Amico. The WSTC Program Manager for this test is D. F. McLaughlin. This test plan is for Phase I activities described in the above Purchase Order. Test conduct includes melting of glass frit with Hanford LLW Double-Shell Slurry Feed waste simulant in a plasma arc fired furnace.

  1. Test plan for glass melter system technologies for vitrification of high-sodium content low-level radioactive liquid waste, Project No. RDD-43288

    SciTech Connect (OSTI)

    Higley, B.A.

    1995-03-15

    This document provides a test plan for the conduct of combustion fired cyclone vitrification testing by a vendor in support of the Hanford Tank Waste Remediation System, Low-Level Waste Vitrification Program. The vendor providing this test plan and conducting the work detailed within it is the Babcock & Wilcox Company Alliance Research Center in Alliance, Ohio. This vendor is one of seven selected for glass melter testing.

  2. Barrier erosion control test plan: Gravel mulch, vegetation, and soil water interactions

    SciTech Connect (OSTI)

    Waugh, W.J.; Link, S.O. (Pacific Northwest Lab., Richland, WA (USA))

    1988-07-01

    Soil erosion could reduce the water storage capacity of barriers that have been proposed for the disposal of near-surface waste at the US Department of Energy's Hanford Site. Gravel mixed into the top soil surface may create a self-healing veneer that greatly retards soil loss. However, gravel admixtures may also enhance infiltration of rainwater, suppress plant growth and water extraction, and lead to the leaching of underlying waste. This report describes plans for two experiments that were designed to test hypotheses concerning the interactive effects of surface gravel admixtures, revegetation, and enhanced precipitation on soil water balance and plant abundance. The first experiment is a factorial field plot set up on the site selected as a soil borrow area for the eventual construction of barriers. The treatments, arranged in a a split-split-plot design structure, include two densities of gravel admix, a mixture of native and introduced grasses, and irrigation to simulate a wetter climate. Changes in soil water storage and plant cover are monitored with neutron moisture probes and point intercept sampling, respectively. The second experiment consists of an array of 80 lysimeters containing several different barrier prototypes. Surface treatments are similar to the field-plot experiment. Drainage is collected from a valve at the base of each lysimeter tube, and evapotranspiration is estimated by subtraction. The lysimeters are also designed to be coupled to a whole-plant gas exchange system that will be used to conduct controlled experiments on evapotranspiration for modeling purposes. 56 refs., 6 figs., 8 tabs.

  3. An experimental test plan for the characterization of molten salt thermochemical properties in heat transport systems

    SciTech Connect (OSTI)

    Pattrick Calderoni

    2010-09-01

    Molten salts are considered within the Very High Temperature Reactor program as heat transfer media because of their intrinsically favorable thermo-physical properties at temperatures starting from 300 C and extending up to 1200 C. In this context two main applications of molten salt are considered, both involving fluoride-based materials: as primary coolants for a heterogeneous fuel reactor core and as secondary heat transport medium to a helium power cycle for electricity generation or other processing plants, such as hydrogen production. The reference design concept here considered is the Advanced High Temperature Reactor (AHTR), which is a large passively safe reactor that uses solid graphite-matrix coated-particle fuel (similar to that used in gas-cooled reactors) and a molten salt primary and secondary coolant with peak temperatures between 700 and 1000 C, depending upon the application. However, the considerations included in this report apply to any high temperature system employing fluoride salts as heat transfer fluid, including intermediate heat exchangers for gas-cooled reactor concepts and homogenous molten salt concepts, and extending also to fast reactors, accelerator-driven systems and fusion energy systems. The purpose of this report is to identify the technical issues related to the thermo-physical and thermo-chemical properties of the molten salts that would require experimental characterization in order to proceed with a credible design of heat transfer systems and their subsequent safety evaluation and licensing. In particular, the report outlines an experimental R&D test plan that would have to be incorporated as part of the design and operation of an engineering scaled facility aimed at validating molten salt heat transfer components, such as Intermediate Heat Exchangers. This report builds on a previous review of thermo-physical properties and thermo-chemical characteristics of candidate molten salt coolants that was generated as part of the same project [1]. However, this work focuses on two materials: the LiF-BeF2 eutectic (67 and 33 mol%, respectively, also known as flibe) as primary coolant and the LiF-NaF-KF eutectic (46.5, 11.5, and 52 mol%, respectively, also known as flinak) as secondary heat transport fluid. At first common issues are identified, involving the preparation and purification of the materials as well as the development of suitable diagnostics. Than issues specific to each material and its application are considered, with focus on the compatibility with structural materials and the extension of the existing properties database.

  4. Multifunction Instrument Tree (MIT) Neutron and Gamma Probe Acceptance for Beneficial Use (ABU)

    SciTech Connect (OSTI)

    CANNON, N.S.

    1999-08-08

    The multifunction instrument tree (MIT) probe program has been developed to modify existing Liquid Observation Well (LOW) neutron and gamma probes for use in the validation shafts of the two MITs installed in Tank 241-SY-101. One of the program objectives is that the modified MIT probes be completely compatible with the existing LOW van instrumentation and procedures. The major program objective is to produce neutron and gamma scans from Tank 241-SY-101 that would assist in evaluating waste feature structure and elevation. The MIT probe program is described in greater detail in the engineering task plan (HNF-3322). In accordance with the engineering task plan, a test plan (HNF-3595) was written, reduced diameter (allowing insertion into the MIT validation tube) neutron and gamma probes were acquired, an acceptance and operational test procedure (HNF-3838) was written, acceptance and operational testing of the MIT probes was performed, and a report of these test results (HNF-4369) has been issued. A number of neutron and gamma probe scans have been obtained from the Tank 241-SY-101 MITs, starting on February 8, 1999, in cooperation with Operations. Now that the MIT probes are fully demonstrated, this document transfers ownership of these probes to Operations, utilizing the final acceptance for beneficial use (ABU) form that follows in Section 3.0.

  5. Coal combustion by wet oxidation. Wet oxidation of coal for energy production: test plan and partial results. Interim report

    SciTech Connect (OSTI)

    Bettinger, J.A.

    1980-07-10

    A test plan has been developed which will provide the data necessary to carry out design and economic studies of a steam generating facility, employing the wet oxidation of coal as a heat source. It is obvious, from the literature search and preliminary testing, that the higher the reaction temperature, the more complete the combustion of coal. However, operation at elevated temperatures and pressures present difficult design problems, and the necessary equipment is costly. Operation under these conditions can only be justified by the higher economic value of high pressure and temperature steam. With a reduction in temperature from 550/sup 0/F (228/sup 0/C) to 450/sup 0/F (232/sup 0/C), the operating pressure is reduced by more than half, thus holding down the overall cost of the system. For this reason, our plan is to study both the enhancement of low temperature wet oxidation of coal, and the higher operating regions. The coal selected for the first portion of this test is an Eastern Appalachian high-volatile-A Bituminous type, from the Upper Clarion seam in Pennsylvania. This coal was selected as being a typical high sulfur, eastern coal. The wet oxidation of coal to produce low pressure steam is a process suited for a high sulfur, low grade, coal. It is not intended that wet oxidation be used in all applications with all types of coals, as it does not appear to be competitive, economically, with conventional combustion, therefore the testing will focus on using high sulfur, low grade coals. In the later portion of testing all the available coals will be tested. In addition, a sample of Minnesota peat will be tested to determine if it also can be used in the process.

  6. CAREER PLANS Geographical Breakdown of Accepted Jobs

    E-Print Network [OSTI]

    Plotkin, Joshua B.

    Degree **Indicates "Continuing Current Employment" Adult-Gerontology Acute Care Nurse Practitioner,000 - $120,000 Adult Gerontology Clinical Nurse Specialist Hospital of the University of Pennsylvania ICU, Clinical Nurse Specialist, Philadelphia, PA Adult-Gerontology Primary Care Nurse Practitioner

  7. Corrective Action Investigation Plan for Corrective Action Unit 528: Polychlorinated Biphenyls Contamination, Nevada Test Site, Nevada, Rev. 0

    SciTech Connect (OSTI)

    U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office

    2003-05-08

    This Corrective Action Investigation Plan contains the U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office's approach to collect the data necessary to evaluate corrective action alternatives appropriate for the closure of Corrective Action Unit (CAU) 528, Polychlorinated Biphenyls Contamination (PCBs), Nevada Test Site (NTS), Nevada, under the Federal Facility Agreement and Consent Order. Located in the southwestern portion of Area 25 on the NTS in Jackass Flats (adjacent to Test Cell C [TCC]), CAU 528 consists of Corrective Action Site 25-27-03, Polychlorinated Biphenyls Surface Contamination. Test Cell C was built to support the Nuclear Rocket Development Station (operational between 1959 and 1973) activities including conducting ground tests and static firings of nuclear engine reactors. Although CAU 528 was not considered as a direct potential source of PCBs and petroleum contamination, two potential sources of contamination have nevertheless been identified from an unknown source in concentrations that could potentially pose an unacceptable risk to human health and/or the environment. This CAU's close proximity to TCC prompted Shaw to collect surface soil samples, which have indicated the presence of PCBs extending throughout the area to the north, east, south, and even to the edge of the western boundary. Based on this information, more extensive field investigation activities are being planned, the results of which are to be used to support a defensible evaluation of corrective action alternatives in the corrective action decision document.

  8. Field testing of an automated wood-combustion system and development of business plan for commercialization of production. Final report for period ending August 1, 1982

    SciTech Connect (OSTI)

    None

    1983-05-24

    A tunnel burner for burning wood chips has been installed and tested at a school building in Durham, NC. The test revealed many problems which did not exist while testing a prototype in laboratories. Controls were found to work reliably. A business plan was developed and is appended. (LEW)

  9. Planning, Execution, and Analysis of the Meridian UAS Flight Test Program Including System and Parameter Identification

    E-Print Network [OSTI]

    Tom, Jonathan

    2010-04-27

    systems must be thoroughly tested on the ground before the tested in flight. 3.1.2 Flight Test Limits The Phase I flight test limits for the Meridian are as follows: 1. Manual Flight Time Limit: 30 minutes 2. Maximum Crosswinds: 5 knots 3. Maximum...-of-sight. The maximum crosswinds are limited to 5 knots to ease the difficulty of landing the aircraft. The maximum constant winds are limited to 10 knots of head wind with 5 knots of gust to limit in flight turbulence. Having the wind out of the north...

  10. Test Plan: Phase 1 demonstration of 3-phase electric arc melting furnace technology for vitrifying high-sodium content low-level radioactive liquid wastes

    SciTech Connect (OSTI)

    Eaton, W.C.

    1995-05-31

    This document provides a test plan for the conduct of electric arc vitrification testing by a vendor in support of the Hanford Tank Waste Remediation System (TWRS) Low-Level Waste (LLW) Vitrification Program. The vendor providing this test plan and conducting the work detailed within it [one of seven selected for glass melter testing under Purchase Order MMI-SVV-384216] is the US Bureau of Mines, Department of the Interior, Albany Research Center, Albany, Oregon. This test plan is for Phase I activities described in the above Purchase Order. Test conduct includes feed preparation activities and melting of glass with Hanford LLW Double-Shell Slurry Feed waste simulant in a 3-phase electric arc (carbon electrode) furnace.

  11. Test Plan for Evaluating Hammer and Fixed Cutter Grinders Using Multiple Varieties and Moistures of Biomass Feedstock

    SciTech Connect (OSTI)

    Not listed

    2007-07-01

    Biomass preprocessing is a critical operation in the preparation of feedstock for the front-end of a cellulosic ethanol biorefinery. Its purpose is to chop, grind, or otherwise format the biomass material into a suitable feedstock for optimum conversion to ethanol and other bioproducts. Without this operation, the natural size, bulk density, and flowability characteristics of harvested biomass would decrease the capacities and efficiencies of feedstock assembly unit operations and biorefinery conversion processes to the degree that programmatic cost targets could not be met. The preprocessing unit operation produces a bulk flowable material that 1) improves handling and conveying efficiencies throughout the feedstock assembly system and biorefinery 2) increases biomass surface areas for improved pretreatment efficiencies, 3) reduces particle sizes for improved feedstock uniformity and density, and 4) fractionates structural components for improved compositional quality. The Idaho National Laboratory (INL) is tasked with defining the overall efficiency/effectiveness of current commercial hammer and fixed cutter grinding systems and other connecting systems such as harvest and collection, storage, transportation, and handling for a wide variety of feedstock types used in bioethanol or syngas production. This test plan details tasks and activities for two separate full-scale grinding tests: Material Characterization Test and Machine Characterization Test. For the Material Characterization Test, a small amount (~5-7 tons each) of several feedstock varieties will be ground. This test will define the fractionation characteristics of the grinder that affect the bulk density, particle size distribution, and quality of the size reduced biomass resulting from different separation screen sizes. A specific screen size will be selected based on the characteristics of the ground material. The Machine Characterization Test will then use this selected screen to grind several 30-ton batches of different feedstock varieties and moistures. This test will focus on identifying the performance parameters of the grinding system specific to the feed, fractionation, and screen separation components and their affect on machine capacity and efficiency.

  12. Streamlined Approach for Environmental Restoration Plan for Corrective Action Unit 116: Area 25 Test Cell C Facility, Nevada Test Site, Nevada, Revision 1

    SciTech Connect (OSTI)

    NSTec Environmental Restoration

    2008-12-01

    This Streamlined Approach for Environmental Restoration (SAFER) Plan identifies the activities required for the closure of Corrective Action Unit (CAU) 116, Area 25 Test Cell C Facility. The Test Cell C (TCC) Facility is located in Area 25 of the Nevada Test Site (NTS) approximately 25 miles northwest of Mercury, Nevada (Figure 1). CAU 116 is currently listed in Appendix III of the Federal Facility Agreement and Consent Order (FFACO) of 1996 (as amended February 2008) and consists of two Corrective Action Sites (CASs): (1) CAS 25-23-20, Nuclear Furnace Piping; and (2) CAS 25-41-05, Test Cell C Facility. CAS 25-41-05 is described in the FFACO as the TCC Facility but actually includes Building 3210 and attached concrete shield wall only. CAU 116 will be closed by demolishing Building 3210, the attached concrete shield wall, and the nuclear furnace piping. In addition, as a best management practice (BMP), Building 3211 (moveable shed) will be demolished due to its close proximity to Building 3210. This will aid in demolition and disposal operations. Radiological surveys will be performed on the demolition debris to determine the proper disposal pathway. As much of the demolition debris as space allows will be placed into the Building 3210 basement structure. After filling to capacity with demolition debris, the basement structure will be mounded or capped and closed with administrative controls. Prior to beginning demolition activities and according to an approved Sampling and Analysis Plan (SAP), representative sampling of surface areas that are known, suspected, or have the potential to contain hazardous constituents such as lead or polychlorinated biphenyls (PCBs) will be performed throughout all buildings and structures. Sections 2.3.2, 4.2.2.2, 4.2.2.3, 4.3, and 6.2.6.1 address the methodologies employed that assure the solid debris placed in the basement structure will not contain contaminants of concern (COCs) above hazardous waste levels. The anticipated post-closure-posting requirements for the mounded/capped basement structure, as well as for the entire CAU, are addressed in Section 4.2.10. The site contains radiologically impacted surfaces and hazardous materials. Based on review of the historical information for CAU 116 and recent site inspections, there is sufficient process knowledge to close CAU 116 using the SAFER process. CAUs that may be closed using the SAFER process have conceptual corrective actions that are clearly identified. Consequently, corrective action alternatives can be chosen prior to completing a corrective action investigation, given anticipated investigation results. The SAFER process combines elements of the data quality objective (DQO) process and the observational approach to plan and conduct closure activities. The DQOs are used to identify the problem and define the type and quality of data needed to complete the investigation phase of the SAFER process. The purpose of the investigation phase is to verify the adequacy of existing information used to determine the chosen corrective action. The observational approach provides a framework for managing uncertainty during the planning and decision-making phases of the project. The SAFER process allows for technical decisions to be made based on information gathered during site visits, interviews, meetings, research, and a consensus of opinion by the decontamination and decommissioning (D&D) team members. Any uncertainties are addressed by documented assumptions that are verified by sampling and analysis, data evaluation, onsite observations, and contingency plans, as necessary. Closure activities may proceed simultaneously with site characterization as sufficient data are gathered to confirm or disprove the assumptions made during selection of the corrective action. If, at any time during the closure process, new information is discovered that indicates that closure activities should be revised, closure activities will be reevaluated as appropriate. Based on a detailed review of historical documentation, there is sufficient process know

  13. Integrated test plan ResonantSonic drilling system technology demonstration-1995, at the Hanford Site: Revision 1

    SciTech Connect (OSTI)

    McLellan, G.W.

    1994-11-17

    This integrated test plan describes the demonstration test of the ResonantSonic drilling system. This demonstration is part of the Office of Technology Development`s Volatile Organic Compound Arid Integrated Demonstration (VOC-Arid ID). Two main purposes of this demonstration are (1) to continue testing the ResonantSonic drilling system compatibility with the Hanford Site waste characterization programs, and (2) to transfer this method for use at the Hanford Site, other government sites, and the private sector. The ResonantSonic method is a dry drilling technique. Field testing of this method began in July 1993. During the next four months, nine holes were drilled, and continuous core samples were retrieved. Penetration rates were 2 to 3 times the baseline, and the operational downtime rate was less than 10%. Successfully demonstrated equipment refinements included a prototype 300 series ResonantSonic head, a new drill rod design for 18-centimeter diameter pipe, and an automated pipe handling system. Various configurations of sampling equipment and drill bits were tested, depending on geologic conditions. The principal objective of the VOC-Arid ID is to determine the viability of emerging technologies that can be used to characterize, remediate, and/or monitor arid or semiarid sites containing VOCs (e.g., carbon tetrachloride) with or without associated metal and radionuclide contamination.

  14. Designing and testing the neutron source deployment system and calibration plan for a dark matter detector

    E-Print Network [OSTI]

    Westerdale, Shawn (Shawn S.)

    2011-01-01

    In this thesis, we designed and tested a calibration and deployment system for the MiniCLEAN dark matter detector. The deployment system uses a computer controlled winch to lower a canister containing a neutron source into ...

  15. Molten carbonate fuel cell product development test environmental assessment/protection plan

    SciTech Connect (OSTI)

    Not Available

    1992-11-01

    Objective of proposed action is to conduct a 250-kW product development test of M-C Power Corporation`s molten carbonate fuel cell concept, at the Kaiser Permanente San Diego Medical Center. Review of environmental impacts of this test indicate the following: no impact on solid waste disposal, water quality, noise levels, floodplains, wetlands, ecology, historic areas, or socioeconomic resources. Impact on air quality are expected to be positive.

  16. Molten carbonate fuel cell product development test environmental assessment/protection plan

    SciTech Connect (OSTI)

    Brunton, Jack; Furukawa, Vance; Frost, Grant; Danna, Mike; Figueroa, Al; Scroppo, Joseph

    1992-11-01

    Objective of proposed action is to conduct a 250-kW product development test of M-C Power Corporation's molten carbonate fuel cell concept, at the Kaiser Permanente San Diego Medical Center. Review of environmental impacts of this test indicate the following: no impact on solid waste disposal, water quality, noise levels, floodplains, wetlands, ecology, historic areas, or socioeconomic resources. Impact on air quality are expected to be positive.

  17. Plans for an ERL Test Facility at CERN (Conference) | SciTech Connect

    Office of Scientific and Technical Information (OSTI)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of NaturalDukeWakefieldSulfateSciTech ConnectSpeeding accessusers' guide.representation (Conference) | SciTechOhmicPlans

  18. Moving granular-bed filter development program topical report. Base contract test plan

    SciTech Connect (OSTI)

    Newby, R.A.; Dilmore, W.J.; Fellers, A.W.; Gasparovic, A.C.; Kittle, W.F.; Lippert, T.E.; Smeltzer, E.E.; Yang, W.C.

    1991-10-17

    The Westinghouse Science & Technology Center has proposed a novel moving granular-bed filter concept, the Standleg Moving Granular-Bed Filter (S-MGBF) system, that overcomes the inherent deficiencies of the current state-of-the-art moving granular-bed filter technology. The S-MGBF system combines two unique features that make it highly effective for use in advanced coal-fueled power plants. First, the S-MGBF system applies pelletization technology to generate filter pellets from the power plant solid waste materials, and uses these pellets as a ``once-through`` filtering media to eliminate the need for costly, complex, and large filter media recycling equipment. This pelletizing step also generates a more environmentally acceptable solid waste product and provides the potential to incorporate gas-phase contaminant sorbents into the filtering media. Secondly, the S-MGBF system passes these pellets and the flyash laden power plant gas through a highly compact S-MGBF that uses cocurrent gas-pellet contacting in an arrangement that greatly simplifies and enhances the distribution of dirty gas to the moving bed and the disengagement of clean gas from the moving bed.

  19. Quality Assurance Project Plan for the Gas Generation Testing Program at the INEL

    SciTech Connect (OSTI)

    NONE

    1994-10-01

    The data quality objectives (DQOs) for the Program are to evaluate compliance with the limits on total gas generation rates, establish the concentrations of hydrogen and methane in the total gas flow, determine the headspace concentration of VOCs in each drum prior to the start of the test, and obtain estimates of the concentrations of several compounds for mass balance purposes. Criteria for the selection of waste containers at the INEL and the parameters that must be characterized prior to and during the tests are described. Collection of gaseous samples from 55-gallon drums of contact-handled transuranic waste for the gas generation testing is discussed. Analytical methods and calibrations are summarized. Administrative quality control measures described in this QAPjP include the generation, review, and approval of project documentation; control and retention of records; measures to ensure that personnel, subcontractors or vendors, and equipment meet the specifications necessary to achieve the required data quality for the project.

  20. SU-E-T-508: End to End Testing of a Prototype Eclipse Module for Planning Modulated Arc Therapy On the Siemens Platform

    SciTech Connect (OSTI)

    Huang, L [Huntsman Cancer Hospital, Salt Lake City, UT (United States); Sarkar, V [University of Utah Hospitals, Salt Lake City, UT (United States); Spiessens, S [Varian Medical Systems France, Buc Cedex (France); Rassiah-Szegedi, P; Huang, Y; Salter, B [University Utah, Salt Lake City, UT (United States); Zhao, H [University of Utah, Salt Lake City, UT (United States); Szegedi, M [Huntsman Cancer Hospital, The University of Utah, Salt Lake City, UT (United States)

    2014-06-01

    Purpose: The latest clinical implementation of the Siemens Artiste linac allows for delivery of modulated arcs (mARC) using full-field flattening filter free (FFF) photon beams. The maximum doserate of 2000 MU/min is well suited for high dose treatments such as SBRT. We tested and report on the performance of a prototype Eclipse TPS module supporting mARC capability on the Artiste platform. Method: our spine SBRT patients originally treated with 12/13 field static-gantry IMRT (SGIMRT) were chosen for this study. These plans were designed to satisfy RTOG0631 guidelines with a prescription of 16Gy in a single fraction. The cases were re-planned as mARC plans in the prototype Eclipse module using the 7MV FFF beam and required to satisfy RTOG0631 requirements. All plans were transferred from Eclipse, delivered on a Siemens Artiste linac and dose-validated using the Delta4 system. Results: All treatment plans were straightforwardly developed, in timely fashion, without challenge or inefficiency using the prototype module. Due to the limited number of segments in a single arc, mARC plans required 2-3 full arcs to yield plan quality comparable to SGIMRT plans containing over 250 total segments. The average (3%/3mm) gamma pass-rate for all arcs was 98.5±1.1%, thus demonstrating both excellent dose prediction by the AAA dose algorithm and excellent delivery fidelity. Mean delivery times for the mARC plans(10.5±1.7min) were 50-70% lower than the SGIMRT plans(26±2min), with both delivered at 2000 MU/min. Conclusion: A prototype Eclipse module capable of planning for Burst Mode modulated arc delivery on the Artiste platform has been tested and found to perform efficiently and accurately for treatment plan development and delivered-dose prediction. Further investigation of more treatment sites is being carried out and data will be presented.

  1. Engineering design and test plan for demonstrating DETOX treatment of mixed wastes

    SciTech Connect (OSTI)

    Goldblatt, S.; Dhooge, P.

    1995-03-01

    DETOX is a cocatalyzed wet oxidation process in which the catalysts are a relatively great concentration of iron ions (typically as iron(III) chloride) in the presence of small amounts of platinum and ruthenium ions. Organic compounds are oxidized completely to carbon dioxide, water, and (if chlorinated) hydrogen chloride. The process has shown promise as a non-thermal alternative to incineration for treatment and/or volume reduction of hazardous, radioactive, and mixed wastes. Design and fabrication of a demonstration unit capable of destroying 25. Kg/hr of organic material is now in progress. This paper describes the Title 2 design of the demonstration unit, and the planned demonstration effort at Savannah River Site (SRS) and Weldon Spring Site Remedial Action Project (WSSRAP).

  2. Demonstration testing and evaluation of in situ soil heating. Health and safety plan (Revision 2)

    SciTech Connect (OSTI)

    Dev, H.

    1994-12-28

    This document is the Health and Safety Plan (HASP) for the demonstration of IITRI`s EM Treatment Technology. In this process, soil is heated in situ by means of electrical energy for the removal of hazardous organic contaminants. This process will be demonstrated on a small plot of contaminated soil located in the Pit Area of Classified Burial Ground K-1070-D, K-25 Site, Oak Ridge, TN. The purpose of the demonstration is to remove organic contaminants present in the soil by heating to a temperature range of 85{degrees} to 95{degrees}C. The soil will be heated in situ by applying 60-Hz AC power to an array of electrodes placed in boreholes drilled through the soil. In this section a brief description of the process is given along with a description of the site and a listing of the contaminants found in the area.

  3. Second Line of Defense, Megaports Initiative, Operational Testing and Evaluation Plan, Port of Lazaro Cardenas, Mexico

    SciTech Connect (OSTI)

    Hughes, Jamie D.

    2012-05-30

    The purpose of the Operational Testing and Evaluation (OT&E) phases of the project is to prepare for turnover of the Megaports System supplied by U.S. Department of Energy/National Nuclear Security Administration (DOE/NNSA)—located at the Export Lanes of the Port of Lazaro Cardenas, Mexico—to the Government of Mexico (GOM).

  4. Corrective Action Investigation Plan for Corrective Action Unit 543: Liquid Disposal Units, Nevada Test Site, Nevada: Revision 0

    SciTech Connect (OSTI)

    U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office

    2004-05-03

    The general purpose of this Corrective Action Investigation Plan is to ensure that adequate data are collected to provide sufficient and reliable information to identify, evaluate, and select technically viable corrective action alternatives (CAAs) for Corrective Action Unit (CAU) 543: Liquid Disposal Units, Nevada Test Site (NTS), Nevada. Located in Areas 6 and 15 on the NTS, CAU 543 is comprised of a total of seven corrective action sites (CASs), one in Area 6 and six in Area 15. The CAS in Area 6 consists of a Decontamination Facility and its components which are associated with decontamination of equipment, vehicles, and materials related to nuclear testing. The six CASs in Area 15 are located at the U.S. Environmental Protection Agency Farm and are related to waste disposal activities at the farm. Sources of possible contamination at Area 6 include potentially contaminated process waste effluent discharged through a process waste system, a sanitary waste stream generated within buildings of the Decon Facility, and radiologically contaminated materials stored within a portion of the facility yard. At Area 15, sources of potential contamination are associated with the dairy operations and the animal tests and experiments involving radionuclide uptake. Identified contaminants of potential concern include volatile organic compounds, semivolatile organic compounds, petroleum hydrocarbons, pesticides, herbicides, polychlorinated biphenyls, metals, and radionuclides. Three corrective action closure alternatives - No Further Action, Close in Place, or Clean Closure - will be recommended for CAU 543 based on an evaluation of all the data quality objective-related data. Field work will be conducted following approval of the plan. The results of the field investigation will support a defensible evaluation of CAAs that will be presented in the Corrective Action Decision Document.

  5. Streamlined Approach for Environmental Restoration Plan for Corrective Action Unit 107: Low Impact Soil Sites, Nevada Test Site, Nevada

    SciTech Connect (OSTI)

    NSTec Environmental Restoration

    2008-09-30

    This Streamlined Approach for Environmental Restoration Plan covers activities associated with Corrective Action Unit (CAU) 107 of the Federal Facility Agreement and Consent Order (FFACO, 1996 [as amended February 2008]). CAU 107 consists of the following Corrective Action Sites (CASs) located in Areas 1, 2, 3, 4, 5, 9, 10, and 18 of the Nevada Test Site. (1) CAS 01-23-02, Atmospheric Test Site - High Alt; (2) CAS 02-23-02, Contaminated Areas (2); (3) CAS 02-23-03, Contaminated Berm; (4) CAS 02-23-10, Gourd-Amber Contamination Area; (5) CAS 02-23-11, Sappho Contamination Area; (6) CAS 02-23-12, Scuttle Contamination Area; (7) CAS 03-23-24, Seaweed B Contamination Area; (8) CAS 03-23-27, Adze Contamination Area; (9) CAS 03-23-28, Manzanas Contamination Area; (10) CAS 03-23-29, Truchas-Chamisal Contamination Area; (11) CAS 04-23-02, Atmospheric Test Site T4-a; (12) CAS 05-23-06, Atmospheric Test Site; (13) CAS 09-23-06, Mound of Contaminated Soil; (14) CAS 10-23-04, Atmospheric Test Site M-10; and (15) CAS 18-23-02, U-18d Crater (Sulky). Based on historical documentation, personnel interviews, site process knowledge, site visits, photographs, engineering drawings, field screening, analytical results, and the results of data quality objectives process (Section 3.0), closure in place with administrative controls or no further action will be implemented for CAU 107. CAU 107 closure activities will consist of verifying that the current postings required under Title 10 Code of Federal Regulations (CFR) Part 835 are in place and implementing use restrictions (URs) at two sites, CAS 03-23-29 and CAS 18-23-02. The current radiological postings combined with the URs are adequate administrative controls to limit site access and worker dose.

  6. Recovery Efficiency Test Project: Phase 1, Activity report. Volume 1: Site selection, drill plan preparation, drilling, logging, and coring operations

    SciTech Connect (OSTI)

    Overbey, W.K. Jr.; Carden, R.S.; Kirr, J.N.

    1987-04-01

    The recovery Efficiency Test well project addressed a number of technical issues. The primary objective was to determine the increased efficiency gas recovery of a long horizontal wellbore over that of a vertical wellbore and, more specifically, what improvements can be expected from inducing multiple hydraulic fractures from such a wellbore. BDM corporation located, planned, and drilled a long radius turn horizontal well in the Devonian shale Lower Huron section in Wayne County, West Virginia, demonstrating that state-of-the-art technology is capable of drilling such wells. BDM successfully tested drilling, coring, and logging in a horizontal well using air as the circulating medium; conducted reservoir modeling studies to protect flow rates and reserves in advance of drilling operations; observed two phase flow conditions in the wellbore not observed previously; cored a fracture zone which produced gas; observed that fractures in the core and the wellbore were not systematically spaced (varied from 5 to 68 feet in different parts of the wellbore); observed that highest gas show rates reported by the mud logger corresponded to zone with lowest fracture spacing (five feet) or high fracture frequency. Four and one-half inch casting was successfully installed in the borehole and was equipped to isolate the horizontal section into eight (8) zones for future testing and stimulation operations. 6 refs., 48 figs., 10 tabs.

  7. Microsoft Word - AGA12 TestPlan 2-6-07.doc

    Energy Savers [EERE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on DeliciousMathematicsEnergyInterested Parties - WAPAEnergy May 28MarEnergyDanielJune ADM 16 RevSCADA Test

  8. Corrective action investigation plan for Corrective Action Unit 340, Pesticide Release Sites, Nevada Test Site, Nye County, Nevada

    SciTech Connect (OSTI)

    NONE

    1998-01-01

    This Correction Action Investigation Plan (CAIP) has been developed in accordance with the Federal Facility Agreement and Consent Order (FFACO) that was agreed to by the US Department of Energy, Nevada Operations Office (DOE/NV); the State of Nevada Division of Environmental Protection (NDEP); and the US Department of Defense. As required by the FFACO (1996), this document provides or references all of the specific information for planning investigation activities associated with three Corrective Action Sites (CASs) located at the Nevada Test Site (NTS). These CASs are collectively known as Corrective Action Unit (CAU) 340, Pesticide Release Sites. According to the FFACO, CASs are sites that may require corrective action(s) and may include solid waste management units or individual disposal or release sites. These sites are CAS 23-21-01, Area 23 Quonset Hut 800 (Q800) Pesticide Release Ditch; CAS 23-18-03, Area 23 Skid Huts Pesticide Storage; and CAS 15-18-02, Area 15 Quonset Hut 15-11 Pesticide Storage (Q15-11). The purpose of this CAIP for CAU 340 is to direct and guide the investigation for the evaluation of the nature and extent of pesticides, herbicides, and other contaminants of potential concern (COPCs) that were stored, mixed, and/or disposed of at each of the CASs.

  9. Test Plan for Field Experiments to Support the Immobilized Low-Activity Waste Disposal Performance Assessment at the Hanford Site

    SciTech Connect (OSTI)

    Meyer, Philip D.; McGrail, B. Peter; Bacon, Diana H.

    2001-09-01

    Much of the data collected to support the Immobilized Low-Activity Waste Performance Assessment (ILAW PA) simulations have been obtained in the laboratory on a relatively small scale (less than 10 cm). In addition, the PA simulations themselves are currently the only means available to integrate the chemical and hydrologic processes involved in the transport of contaminants from the disposal facility into the environment. This report describes the test plan for field experiments to provide data on the hydraulic, transport, and geochemical characteristics of the near-field materials on a more representative (i.e., larger) scale than the laboratory data currently available. The experiments will also provide results that encompass a variety of transport processes likely to occur within the actual disposal facility. These experiments will thus provide the first integrated data on the ILAW facility performance and will provide a crucial dataset to evaluate the simulation-based estimates of overall facility performance used in the PA.

  10. SUMMARY PLAN FOR BENCH-SCALE REFORMER AND PRODUCT TESTING TREATABILITY STUDIES USING HANFORD TANK WASTE

    SciTech Connect (OSTI)

    DUNCAN JB

    2010-08-19

    This paper describes the sample selection, sample preparation, environmental, and regulatory considerations for shipment of Hanford radioactive waste samples for treatability studies of the FBSR process at the Savannah River National Laboratory and the Pacific Northwest National Laboratory. The U.S. Department of Energy (DOE) Hanford tank farms contain approximately 57 million gallons of wastes, most of which originated during the reprocessing of spent nuclear fuel to produce plutonium for defense purposes. DOE intends to pre-treat the tank waste to separate the waste into a high level fraction, that will be vitrified and disposed of in a national repository as high-level waste (HLW), and a low-activity waste (LAW) fraction that will be immobilized for on-site disposal at Hanford. The Hanford Waste Treatment and Immobilization Plant (WTP) is the focal point for the treatment of Hanford tank waste. However, the WTP lacks the capacity to process all of the LAW within the regulatory required timeframe. Consequently, a supplemental LAW immobilization process will be required to immobilize the remainder of the LAW. One promising supplemental technology is Fluidized Bed Steam Reforming (FBSR) to produce a sodium-alumino-silicate (NAS) waste form. The NAS waste form is primarily composed of nepheline (NaAlSiO{sub 4}), sodalite (Nas[AlSiO{sub 4}]{sub 6}Cl{sub 2}), and nosean (Na{sub 8}[AlSiO{sub 4}]{sub 6}SO{sub 4}). Semivolatile anions such as pertechnetate (TcO{sub 4}{sup -}) and volatiles such as iodine as iodide (I{sup -}) are expected to be entrapped within the mineral structures, thereby immobilizing them (Janzen 2008). Results from preliminary performance tests using surrogates, suggests that the release of semivolatile radionuclides {sup 99}Tc and volatile {sup 129}I from granular NAS waste form is limited by Nosean solubility. The predicted release of {sup 99}Tc from the NAS waste form at a 100 meters down gradient well from the Integrated Disposal Facility (IDF) was found to be comparable to immobilized low-activity waste glass waste form in the initial supplemental LAW treatment technology risk assessment (Mann 2003). To confirm this hypothesis, DOE is funding a treatability study where three actual Hanford tank waste samples (containing both {sup 99}Tc and {sup 125}I) will be processed in Savannah River National Laboratory's (SRNL) Bench-Scale Reformer (BSR) to form the mineral product, similar to the granular NAS waste form, that will then be subject to a number of waste form qualification tests. In previous tests, SRNL have demonstrated that the BSR product is chemically and physically equivalent to the FBSR product (Janzen 2005). The objective of this paper is to describe the sample selection, sample preparation, and environmental and regulatory considerations for treatability studies of the FBSR process using Hanford tank waste samples at the SNRL. The SNRL will process samples in its BSR. These samples will be decontaminated in the 222-S Laboratory to remove undissolved solids and selected radioisotopes to comply with Department of Transportation (DOT) shipping regulations and to ensure worker safety by limiting radiation exposure to As Low As Reasonably Achievable (ALARA). These decontamination levels will also meet the Nuclear Regulatory Commission's (NRC's) definition of low activity waste (LAW). After the SNRL has processed the tank samples to a granular mineral form, SRNL and Pacific Northwest National Laboratory (PNNL) will conduct waste form testing on both the granular material and monoliths prepared from the granular material. The tests being performed are outlined in Appendix A.

  11. APEX: A Prime EXperiment at Jefferson Lab - Test Run Results and Full Run Plans; Update

    SciTech Connect (OSTI)

    Beacham, James

    2015-06-01

    APEX is an experiment at Thomas Jefferson National Accelerator Facility (JLab) in Virginia, USA, that searches for a new gauge boson (A') with sub-GeV mass and coupling to ordinary matter of g' ~ (10^-6 - 10?²)e. Electrons impinge upon a fixed target of high-Z material. An A' is produced via a process analogous to photon bremsstrahlung, decaying to an e?+e? pair. A test run was held in July of 2010, covering mA' = 175 to 250 MeV and couplings g'/e > 10?³. A full run is approved and will cover mA' ~ 65 to 525 MeV and g'/e > 2.3 x 10??, and is expected to occur sometime in 2016 or 2017.

  12. Irradiation Programs and Test Plans to Assess High-Fluence Irradiation Assisted Stress Corrosion Cracking Susceptibility.

    SciTech Connect (OSTI)

    Teysseyre, Sebastien

    2015-03-01

    . Irradiation assisted stress corrosion cracking (IASCC) is a known issue in current reactors. In a 60 year lifetime, reactor core internals may experience fluence levels up to 15 dpa for boiling water reactors (BWR) and 100+ dpa for pressurized water reactors (PWR). To support a safe operation of our fleet of reactors and maintain their economic viability it is important to be able to predict any evolution of material behaviors as reactors age and therefore fluence accumulated by reactor core component increases. For PWR reactors, the difficulty to predict high fluence behavior comes from the fact that there is not a consensus of the mechanism of IASCC and that little data is available. It is however possible to use the current state of knowledge on the evolution of irradiated microstructure and on the processes that influences IASCC to emit hypotheses. This report identifies several potential changes in microstructure and proposes to identify their potential impact of IASCC. The susceptibility of a component to high fluence IASCC is considered to not only depends on the intrinsic IASCC susceptibility of the component due to radiation effects on the material but to also be related to the evolution of the loading history of the material and interaction with the environment as total fluence increases. Single variation type experiments are proposed to be performed with materials that are representative of PWR condition and with materials irradiated in other conditions. To address the lack of IASCC propagation and initiation data generated with material irradiated in PWR condition, it is proposed to investigate the effect of spectrum and flux rate on the evolution of microstructure. A long term irradiation, aimed to generate a well-controlled irradiation history on a set on selected materials is also proposed for consideration. For BWR, the study of available data permitted to identify an area of concern for long term performance of component. The efficiency of hydrogen water chemistry mitigation technology may decrease as fluence increases for high-stress intensity factors. This report describes a program plan to determine the efficiency of hydrogen water chemistry as a function of the stress intensity factor applied and fluence. The use of existing, available, materials and the generation of additional materials via irradiation in a research reactor are considered.

  13. New Pump and Treat Facility Remedial Action Work Plan For Test Area North Final Groundwater Remediation, Operable Unit 1-07B

    SciTech Connect (OSTI)

    Nelson, L. O.

    2007-06-12

    This remedial action work plan identifies the approach and requirements for implementing the medial zone remedial action for Test Area North, Operable Unit 1-07B, at the Idaho National Laboratory. This plan details the management approach for the construction and operation of the New Pump and Treat Facility (NPTF). As identified in the remediatial design/remedial action scope of work, a separate remedial design/remedial action work plan will be prepared for each remedial component of the Operable Unit 1-07B remedial action.

  14. Streamlined approach for environmental restoration plan for corrective action unit 430, buried depleted uranium artillery round No. 1, Tonopah test range

    SciTech Connect (OSTI)

    NONE

    1996-09-01

    This plan addresses actions necessary for the restoration and closure of Corrective Action Unit (CAU) No. 430, Buried Depleted Uranium (DU) Artillery Round No. 1 (Corrective Action Site No. TA-55-003-0960), a buried and unexploded W-79 Joint Test Assembly (JTA) artillery test projectile with high explosives (HE), at the U.S. Department of Energy, Nevada Operations Office (DOE/NV) Tonopah Test Range (TTR) in south-central Nevada. It describes activities that will occur at the site as well as the steps that will be taken to gather adequate data to obtain a notice of completion from Nevada Division of Environmental Protection (NDEP). This plan was prepared under the Streamlined Approach for Environmental Restoration (SAFER) concept, and it will be implemented in accordance with the Federal Facility Agreement and Consent Order (FFACO) and the Resource Conservation and Recovery Act (RCRA) Industrial Sites Quality Assurance Project Plan.

  15. A STRATEGIC PLAN FOR A NEW UWMADISON

    E-Print Network [OSTI]

    Bohnhoff, David

    A STRATEGIC PLAN FOR A NEW UW­MADISON HUMAN RESOURCES SYSTEM Accepted to present the HR Design strategic plan for a new University of Wisconsin­Madison Human Resources System .......................................................................................... 17 The Components of the HR Strategic Plan

  16. Corrective Action Plan for Corrective Action Unit 262: Area 25 Septic Systems and Underground Discharge Point, Nevada Test Site, Nevada

    SciTech Connect (OSTI)

    K. B. Campbell

    2002-06-01

    This Corrective Action Plan (CAP) provides selected corrective action alternatives and proposes the closure methodology for Corrective Action Unit (CAU) 262, Area 25 Septic Systems and Underground Discharge Point. CAU 262 is identified in the Federal Facility Agreement and Consent Order (FFACO) of 1996. Remediation of CAU 262 is required under the FFACO. CAU 262 is located in Area 25 of the Nevada Test Site (NTS), approximately 100 kilometers (km) (62 miles [mi]) northwest of Las Vegas, Nevada. The nine Corrective Action Sites (CASs) within CAU 262 are located in the Nuclear Rocket Development Station complex. Individual CASs are located in the vicinity of the Reactor Maintenance, Assembly, and Disassembly (R-MAD); Engine Maintenance, Assembly, and Disassembly (E-MAD); and Test Cell C compounds. CAU 262 includes the following CASs as provided in the FFACO (1996); CAS 25-02-06, Underground Storage Tank; CAS 25-04-06, Septic Systems A and B; CAS 25-04-07, Septic System; CAS 25-05-03, Leachfield; CAS 25-05-05, Leachfield; CAS 25-05-06, Leachfield; CAS 25-05-08, Radioactive Leachfield; CAS 25-05-12, Leachfield; and CAS 25-51-01, Dry Well. Figures 2, 3, and 4 show the locations of the R-MAD, the E-MAD, and the Test Cell C CASs, respectively. The facilities within CAU 262 supported nuclear rocket reactor engine testing. Activities associated with the program were performed between 1958 and 1973. However, several other projects used the facilities after 1973. A significant quantity of radioactive and sanitary waste was produced during routine operations. Most of the radioactive waste was managed by disposal in the posted leachfields. Sanitary wastes were disposed in sanitary leachfields. Septic tanks, present at sanitary leachfields (i.e., CAS 25-02-06,2504-06 [Septic Systems A and B], 25-04-07, 25-05-05,25-05-12) allowed solids to settle out of suspension prior to entering the leachfield. Posted leachfields do not contain septic tanks. All CASs located in CAU 262 are inactive or abandoned. However, some leachfields may still receive liquids from runoff during storm events. Results from the 2000-2001 site characterization activities conducted by International Technology (IT) Corporation, Las Vegas Office are documented in the Corrective Action Investigation Report for Corrective Action Unit 262: Area 25 Septic Systems and Underground Discharge Point, Nevada Test Site, Nevada. This document is located in Appendix A of the Corrective Action Decision Document for CAU 262. Area 25 Septic Systems and Underground Discharge Point, Nevada Test Site, Nevada. (DOE/NV, 2001).

  17. Corrective Action Investigation Plan for Corrective Action Unit 232: Area 25 Sewage Lagoons Nevada Test Site, Nevada

    SciTech Connect (OSTI)

    DOE/NV Operations Office

    1999-05-01

    This Corrective Action Investigation Plan (CAIP) has been developed in accordance with the Federal Facility Agreement and Consent Order (FFACO) (1996) that was agreed to by the US Department of Energy, Nevada Operations Office (DOE/NV); the State of Nevada Division of Environmental Protection (NDEP); and the US Department of Defense. The CAIP is a document that provides or references all of the specific information for investigation activities associated with Corrective Action Units (CAUs) or Corrective Action Sites (CASs). According to the FFACO, CASs are sites potentially requiring corrective action(s) and may include solid waste management units or individual disposal or release sites. A CAU consists of one or more CASs grouped together based on geography, technical similarity, or agency responsibility for the purpose of determining corrective actions. This CAIP contains the environmental sample collection objectives and criteria for conducting site investigation activities at CAU 232, Area 25 Sewage Lagoons. Corrective Action Unit 232 consists of CAS 25-03-01, Sewage Lagoon, located in Area 25 of the Nevada Test Site (NTS). The NTS is approximately 65 miles (mi) northwest of Las Vegas, Nevada (Figure 1-1) (DOE/NV, 1996a). The Area 25 Sewage Lagoons (Figure 1-2) (IT, 1999b) are located approximately 0.3 mi south of the Test Cell 'C' (TCC) Facility and were used for the discharge of sanitary effluent from the TCC facility. For purposes of this discussion, this site will be referred to as either CAU 232 or the sewage lagoons.

  18. Plan for Using Solar-Powered Jack Pumps to Sample Groundwater at the Nevada Test Site

    SciTech Connect (OSTI)

    David Hudson, Charles Lohrstorfer, Bruce Hurley

    2007-05-03

    Groundwater is sampled from 39 monitoring wells on the Nevada Test Site (NTS) as part of the Routine Radiological Environmental Monitoring Program. Many of these wells were not designed or constructed for long-term groundwater monitoring. Some have extensive completion zones and others have obstructions such as pumps and tubing. The high-volume submersible pumps in some wells are unsuitable for long-term monitoring and result in large volumes of water that may have to be contained and characterized before subsequent disposition. The configuration of most wells requires sampling stagnant well water with a wireline bailer. Although bailer sampling allows for the collection of depth-discrete samples, the collected samples may not be representative of local groundwater because no well purging is done. Low-maintenance, solar-powered jack pumps will be deployed in nine of these onsite monitoring wells to improve sample quality. These pumps provide the lift capacity to produce groundwater from the deep aquifers encountered in the arid environment of the NTS. The water depths in these wells range from 700 to 2,340 ft below ground surface. The considerable labor and electrical power requirements of electric submersible pumps are eliminated once these pumps are installed. Access tubing will be installed concurrent with the installation of the pump string to provide downhole access for water-level measurements or other wireline instruments. Micro-purge techniques with low pump rates will be used to minimize purge volumes and reduce hydraulic gradients. The set depths of the pumps will be determined by the borehole characteristics and screened interval.

  19. Corrective Action Decision Document/Corrective Action Plan for Corrective Action Unit 104: Area 7 Yucca Flat Atmospheric Test Sites Nevada National Security Site, Nevada, Revision 0

    SciTech Connect (OSTI)

    Patrick Matthews

    2012-10-01

    CAU 104 comprises the following corrective action sites (CASs): • 07-23-03, Atmospheric Test Site T-7C • 07-23-04, Atmospheric Test Site T7-1 • 07-23-05, Atmospheric Test Site • 07-23-06, Atmospheric Test Site T7-5a • 07-23-07, Atmospheric Test Site - Dog (T-S) • 07-23-08, Atmospheric Test Site - Baker (T-S) • 07-23-09, Atmospheric Test Site - Charlie (T-S) • 07-23-10, Atmospheric Test Site - Dixie • 07-23-11, Atmospheric Test Site - Dixie • 07-23-12, Atmospheric Test Site - Charlie (Bus) • 07-23-13, Atmospheric Test Site - Baker (Buster) • 07-23-14, Atmospheric Test Site - Ruth • 07-23-15, Atmospheric Test Site T7-4 • 07-23-16, Atmospheric Test Site B7-b • 07-23-17, Atmospheric Test Site - Climax These 15 CASs include releases from 30 atmospheric tests conducted in the approximately 1 square mile of CAU 104. Because releases associated with the CASs included in this CAU overlap and are not separate and distinguishable, these CASs are addressed jointly at the CAU level. The purpose of this CADD/CAP is to evaluate potential corrective action alternatives (CAAs), provide the rationale for the selection of recommended CAAs, and provide the plan for implementation of the recommended CAA for CAU 104. Corrective action investigation (CAI) activities were performed from October 4, 2011, through May 3, 2012, as set forth in the CAU 104 Corrective Action Investigation Plan.

  20. Post-Service Examination of PWR Baffle Bolts, Part I. Examination and Test Plan

    SciTech Connect (OSTI)

    Leonard, Keith J.; Sokolov, Mikhail A.; Gussev, Maxim N.

    2015-04-30

    In support of extended service and current operations of the US nuclear reactor plants, the Oak Ridge National Laboratory (ORNL), through the Department of Energy (DOE), Light Water Reactor Sustainability (LWRS) Program, is coordinating with Ginna Nuclear Power Plant, The Westinghouse Electric Company, LLC, and ATI Consulting, the selective procurement of baffle bolts that were withdrawn from service in 2011 and currently stored on site at Ginna. The goal of this program is to perform detailed microstructural and mechanical property characterization of baffle former bolts following in-service exposures. This report outlines the selection criteria of the bolts and the techniques to be used in this study. The bolts available are the original alloy 347 steel fasteners used in holding the baffle plates to the baffle former structures within the lower portion of the pressurized water reactor vessel. Of the eleven possible bolts made available for this work, none were identified to have specific damage. The bolts, however, did show varying levels of breakaway torque required in their removal. The bolts available for this study varied in peak fluence (highest dose within the head of the bolt) between 9.9 and 27.8x1021 n/cm2 (E>1MeV). As no evidence for crack initiation was determined for the available bolts from preliminary visual examination, two bolts with the higher fluence values were selected for further post-irradiation examination. The two bolts showed different breakaway torque levels necessary in their removal. The information from these bolts will be integral to the LWRS program initiatives in evaluating end of life microstructure and properties. Furthermore, valuable data will be obtained that can be incorporated into model predictions of long-term irradiation behavior and compared to results obtained in high flux experimental reactor conditions. The two bolts selected for the ORNL study will be shipped to Westinghouse with bolts of interest to their collaborative efforts with the Electric Power Research Institute. Westinghouse will section the ORNL bolts into samples specified in this report and return them to ORNL. Samples will include bend bars for fracture toughness and crack propagation studies along with thin sections from which specimens for bend testing, subscale tensile and microstructural analysis can be obtained. Additional material from the high stress concentration region at the transition between the bolt head and shank will also be preserved to allow for further investigation of possible crack initiation sites.

  1. Corrective Action Investigation Plan for Corrective Action Unit 562: Waste Systems Nevada Test Site, Nevada, Revision 0

    SciTech Connect (OSTI)

    Alfred Wickline

    2009-04-01

    Corrective Action Unit 562 is located in Areas 2, 23, and 25 of the Nevada Test Site, which is approximately 65 miles northwest of Las Vegas, Nevada. Corrective Action Unit 562 is comprised of the 13 corrective action sites (CASs) listed below: • 02-26-11, Lead Shot • 02-44-02, Paint Spills and French Drain • 02-59-01, Septic System • 02-60-01, Concrete Drain • 02-60-02, French Drain • 02-60-03, Steam Cleaning Drain • 02-60-04, French Drain • 02-60-05, French Drain • 02-60-06, French Drain • 02-60-07, French Drain • 23-60-01, Mud Trap Drain and Outfall • 23-99-06, Grease Trap • 25-60-04, Building 3123 Outfalls These sites are being investigated because existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend corrective action alternatives. Additional information will be obtained by conducting a corrective action investigation before evaluating corrective action alternatives and selecting the appropriate corrective action for each CAS. The results of the field investigation will support a defensible evaluation of viable corrective action alternatives that will be presented in the Corrective Action Decision Document. The sites will be investigated based on the data quality objectives (DQOs) developed on December 11, 2008, by representatives of the Nevada Division of Environmental Protection; U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office; Stoller-Navarro Joint Venture; and National Security Technologies, LLC. The DQO process was used to identify and define the type, amount, and quality of data needed to develop and evaluate appropriate corrective actions for CAU 562. Appendix A provides a detailed discussion of the DQO methodology and the DQOs specific to each CAS. The scope of the corrective action investigation for CAU 562 includes the following activities: • Move surface debris and/or materials, as needed, to facilitate sampling. • Conduct radiological surveys. • Perform field screening. • Collect and submit environmental samples for laboratory analysis to determine the nature and extent of any contamination released by each CAS. • Collect samples of source material to determine the potential for a release. • Collect samples of potential remediation wastes. • Collect quality control samples. This Corrective Action Investigation Plan has been developed in accordance with the Federal Facility Agreement and Consent Order that was agreed to by the State of Nevada; DOE, Environmental Management; U.S. Department of Defense; and DOE, Legacy Management (FFACO, 1996; as amended February 2008). Under the Federal Facility Agreement and Consent Order, this Corrective Action Investigation Plan will be submitted to the Nevada Division of Environmental Protection for approval. Fieldwork will be conducted following approval of the plan.

  2. Corrective Action Investigation Plan for Corrective Action Unit 98: Frenchman Flat, Nevada Test Site, Nevada (Revision 1)

    SciTech Connect (OSTI)

    USDOE/NV

    1999-07-01

    This Corrective Action Investigation Plan (CAIP) has been developed for Frenchman Flat Corrective Action Unit (CAU) 98. The Frenchman Flat CAU is located along the eastern border of the Nevada Test Site (NTS) and includes portions of Areas 5 and 11. The Frenchman Flat CAU constitutes one of several areas of the Nevada Test Site used for underground nuclear testing in the past. The nuclear tests resulted in groundwater contamination in the vicinity as well as downgradient of the underground test areas. The CAIP describes the Corrective Action Investigation (CAI) to be conducted at the Frenchman Flat CAU to evaluate the extent of contamination in groundwater due to the underground nuclear testing. The Frenchman Flat CAI will be conducted by the Underground Test Area (UGTA) Project which is a part of the U.S. Department of Energy, Nevada Operations Office (DOE/NV) Environmental Restoration Project. The CAIP is a requirement of the Federal Facility Agreement and Consent Order (FFACO) (1996 ) agreed to by the U.S. Department of Energy (DOE), the Nevada Division of Environmental Protection (NDEP), and the U.S. Department of Defense (DoD). Based on the general definition of a CAI from Section IV.14 of the FFACO, the purpose of the CAI is ''...to gather data sufficient to characterize the nature, extent, and rate of migration or potential rate of migration from releases or discharges of pollutants or contaminants and/or potential releases or discharges from corrective action units identified at the facilities...'' (FFACO, 1996). However, for the Underground Test Area (UGTA) CAUs, ''...the objective of the CAI process is to define boundaries around each UGTA CAU that establish areas that contain water that may be unsafe for domestic and municipal use.'', as stated in Appendix VI of the FFACO (1996). According to the UGTA strategy (Appendix VI of the FFACO), the CAI of a given CAU starts with the evaluation of the existing data. New data collection activities are generally contingent upon the results of the modeling and may or may not be part of the CAI. Such is the case for the Frenchman Flat CAU. The current scope of the Frenchman Flat CAI includes the development and use of a three-dimensional (3-D), numerical, CAU-scale groundwater flow and contaminant transport model to predict the location of the contaminant boundary. The CAU model will be developed and used to predict the location of the contaminant boundary. The scope of this CAI does not currently include any characterization activities; however, such activities will be conducted if the CAU model results indicate that further characterization information is needed to develop a sufficiently reliable CAU model. Two areas of importance to the CAU model are the model area and the investigation area. The CAU-model area will be selected to encompass the Frenchman Flat CAU and the region located immediately downgradient where contamination may migrate. The extent of the CAU-model area is dependent on the extent of contamination and is uncertain at this point. The extent of the investigation area is not expected to increase during the CAI.

  3. Alternatives To the Use of Contractor's Quality Control Data For Acceptance and Payment Purposes 

    E-Print Network [OSTI]

    Wani, Sujay Sudhir

    2012-07-16

    ........................ 59 5.2. Skip-lot Sampling Plan-1 (SkSP-1) .................................................... 61 5.3. Skip-lot Sampling Plan-2 (SkSP-2) .................................................... 63 5.4. An Example Application of SkSP-2... ......... 100 Table C-4 Constants for SkSP-2 Plans Having Acceptance Constant of 3 ......... 101 Table C-5 Constants for SkSP-2 Plans Having Acceptance Constant of 4 ......... 103 Table C-6 Constants for SkSP-2 Plans Having Acceptance Constant of 5...

  4. Corrective Action Investigation Plan for Corrective Action Unit 321: Area 22 Weather Station Fuel Storage, Nevada Test Site, Nevada

    SciTech Connect (OSTI)

    DOE /NV

    1999-01-28

    This Corrective Action Investigation Plan (CAIP) has been developed in accordance with the Federal Facility Agreement and Consent Order (FFACO) that was agreed to by the US Department of Energy, Nevada Operations Office (DOE/NV); the State of Nevada Division of Environmental Protection (NDEP); and the US Department of Defense (FFACO, 1996). The CAIP is a document that provides or references all of the specific information for investigation activities associated with Corrective Action Units (CAUs) or Corrective Action Sites (CASs). According to the FFACO (1996), CASs are sites potentially requiring corrective action(s) and may include solid waste management units or individual disposal or release sites. A CAU consists of one or more CASs grouped together based on geography, technical similarity, or agency responsibility for the purpose of determining corrective actions. This CAIP contains the environmental sample collection objectives and the criteria for conducting site investigation activities at the CAU 321 Area 22 Weather Station Fuel Storage, CAS 22-99-05 Fuel Storage Area. For purposes of this discussion, this site will be referred to as either CAU 321 or the Fuel Storage Area. The Fuel Storage Area is located in Area 22 of the Nevada Test Site (NTS). The NTS is approximately 105 kilometers (km) (65 miles [mi]) northwest of Las Vegas, Nevada (Figure 1-1) (DOE/NV, 1996a). The Fuel Storage Area (Figure 1-2) was used to store fuel and other petroleum products necessary for motorized operations at the historic Camp Desert Rock facility which was operational from 1951 to 1958 at the Nevada Test Site, Nevada. The site was dismantled after 1958 (DOE/NV, 1996a).

  5. Corrective Action Plan for Corrective Action Unit 271: Areas 25, 26, and 27 Septic Systems, Nevada Test Site, Nevada

    SciTech Connect (OSTI)

    R. B. Jackson

    2003-05-01

    The Areas 25, 26 and 27 Septic Systems are in the Federal Facility Agreement and Consent Order (FFACO) of 1996 as Corrective Action Unit (CAU) 271. This Corrective Action Plan (CAP) provides selected corrective action alternatives and proposes the closure methodology for CAU 271. CAU 271 is located on the Nevada Test Site (NTS) approximately 105 kilometers (65 miles) northwest of Las Vegas, Nevada, and consists of the following 15 Corrective Action Sites (CAS): CAS 25-04-1, Septic System; CAS 25-04-03, Septic System; CAS25-04-04, Septic System; CAS 25-04-08, Septic System; CAS 25-04-09, Septic System; CAS 25-04-10, Septic System; CAS 25-04-11, Septic System; CAS 26-03-01, Contaminated Water Reservoir; CAS 26-04-1, Septic System; CAS 26-04-02, Septic System; CAS 26-05-01, Radioactive Leachfield; CAS-26-05-03, Septic System; CAS 26-05-04, Septic System; CAS 26-05-05, Septic System; and CAS 27-05-02, Leachfield.

  6. Corrective Action Investigation Plan for Corrective Action Unit 552: Area 12 Muckpile and Ponds, Nevada Test Site, Nevada: Revision 0

    SciTech Connect (OSTI)

    U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office

    2004-04-06

    This Corrective Action Investigation Plan contains the U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office's approach for collecting the data necessary to evaluate corrective action alternatives appropriate for the closure of Corrective Action Unit (CAU) 552: Area 12 Muckpile and Ponds, Nevada Test Site (NTS), Nevada, under the Federal Facility Agreement and Consent Order. Located in Area 12 on the NTS, CAU 552 consists of two Corrective Action Sites (CASs): 12-06-04, Muckpile; 12-23-05, Ponds. Corrective Action Site 12-06-04 in Area 12 consists of the G-Tunnel muckpile, which is the result of tunneling activities. Corrective Action Site 12-23-05 consists of three dry ponds adjacent to the muckpile. The toe of the muckpile extends into one of the ponds creating an overlap of two CASs. The purpose of the investigation is to ensure that adequate data are collected to provide sufficient and reliable information to identify, evaluate, and select technic ally viable corrective actions. The results of the field investigation will support a defensible evaluation of corrective action alternatives in the corrective action decision document.

  7. Corrective Action Plan for Corrective Action Unit 143: Area 25 Contaminated Waste Dumps, Nevada Test Site, Nevada

    SciTech Connect (OSTI)

    D. L. Gustafason

    2001-02-01

    This Corrective Action Plan (CAP) has been prepared for Corrective Action Unit (CAU) 143: Area 25 Contaminated Waste Dumps, Nevada Test Site, Nevada, in accordance with the Federal Facility Agreement and Consent Order of 1996. This CAP provides the methodology for implementing the approved corrective action alternative as listed in the Corrective Action Decision Document (U.S. Department of Energy, Nevada Operations Office, 2000). The CAU includes two Corrective Action Sites (CASs): 25-23-09, Contaminated Waste Dump Number 1; and 25-23-03, Contaminated Waste Dump Number 2. Investigation of CAU 143 was conducted in 1999. Analytes detected during the corrective action investigation were evaluated against preliminary action levels to determine constituents of concern for CAU 143. Radionuclide concentrations in disposal pit soil samples associated with the Reactor Maintenance, Assembly, and Disassembly Facility West Trenches, the Reactor Maintenance, Assembly, and Disassembly Facility East Trestle Pit, and the Engine Maintenance, Assembly, and Disassembly Facility Trench are greater than normal background concentrations. These constituents are identified as constituents of concern for their respective CASs. Closure-in-place with administrative controls involves use restrictions to minimize access and prevent unauthorized intrusive activities, earthwork to fill depressions to original grade, placing additional clean cover material over the previously filled portion of some of the trenches, and placing secondary or diversion berm around pertinent areas to divert storm water run-on potential.

  8. Test plan for the M-100 container, (model M-101/7A/12/90) docket 96-43-7A, type A container. Revision 1

    SciTech Connect (OSTI)

    Kelly, D.L.

    1997-07-22

    This report concerns the packaging configurations being tested by the U.S. DOE and its contractors, and according to U.S. DOT specification 7A Type A (DOT-7A) requirements. The objective of this Test Plan is to describe the testing for the qualification of the M-100 Container, Model M-101/7A/12/90 as a DOT-7A Type A packaging. This packaging system is designed to ship Type A solid radioactive materials, normal form, Form Number 1, Form Number 2, and Form Number 3.

  9. Streamlined Approach for Environmental Restoration (SAFER) Plan for Corrective Action Unit 114: Area 25 EMAD Facility Nevada Test Site, Nevada

    SciTech Connect (OSTI)

    Mark Krauss

    2010-06-01

    This Streamlined Approach for Environmental Restoration (SAFER) Plan addresses the actions needed to achieve closure for Corrective Action Unit (CAU) 114, Area 25 EMAD Facility, identified in the Federal Facility Agreement and Consent Order (FFACO). Corrective Action Unit 114 comprises the following corrective action site (CAS) located in Area 25 of the Nevada Test Site: • 25-41-03, EMAD Facility This plan provides the methodology for field activities needed to gather the necessary information for closing CAS 25-41-03. There is sufficient information and process knowledge from historical documentation and investigations of similar sites regarding the expected nature and extent of potential contaminants to recommend closure of CAU 114 using the SAFER process. Additional information will be obtained by conducting a field investigation before selecting the appropriate corrective action for CAS 25-41-03. It is anticipated that the results of the field investigation and implementation of corrective actions will support a defensible recommendation that no further corrective action is necessary. If it is determined that complete clean closure cannot be accomplished during the SAFER, then a hold point will have been reached and the Nevada Division of Environmental Protection (NDEP) will be consulted to determine whether the remaining contamination will be closed under the alternative corrective action of closure in place. This will be presented in a closure report that will be prepared and submitted to NDEP for review and approval. The CAS will be investigated based on the data quality objectives (DQOs) developed on April 30, 2009, by representatives of NDEP and the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office. The DQO process was used to identify and define the type, amount, and quality of data needed to determine and implement appropriate corrective actions for CAS 25-41-03. The following text summarizes the SAFER activities that will support the closure of CAU 114: • Perform site preparation activities (e.g., utilities clearances, radiological surveys). • Collect samples of materials to determine whether potential source material (PSM) is present that may cause the future release of a contaminant of concern to environmental media. • If no PSMs are present at the CAS, establish no further action as the corrective action. • If a PSM is present at the CAS, either: - Establish clean closure as the corrective action. The material to be remediated will be removed and disposed of as waste, or - Establish closure in place as the corrective action and implement the appropriate use restrictions. • Confirm the selected closure option is sufficient to protect human health and the environment.

  10. Automated Transportation Management System (ATMS) V2.0 logistics module PBI acceptance criteria

    SciTech Connect (OSTI)

    Weidert, R.S.

    1995-02-28

    This document defines the acceptance criteria for the Automated Transportation Management System V2.0 Logistics Module Performance Based Incentive (PBI). This acceptance criteria will be the primary basis for the generation of acceptance test procedures. The purpose of this document is to define the minimum criteria that must be fulfilled to guarantee acceptance of the Logistics Module.

  11. Subbasin Planning Public Involvement Plan 1 Last Revised: 4/4/2004

    E-Print Network [OSTI]

    Subbasin Planning Public Involvement Plan 1 Last Revised: 4/4/2004 Walla Walla, Tucannon, Asotin & Lower Snake River Subbasin Planning Public Involvement Plan Background Public outreach and involvement is key to the success of the subbasin planning process. Without public acceptance and support of the plan

  12. Integrated Closure and Monitoring Plan for the Area 3 and Area 5 Radioactive Waste Management Sites at the Nevada Test Site

    SciTech Connect (OSTI)

    S. E. Rawlinson

    2001-09-01

    Bechtel Nevada (BN) manages two low-level Radioactive Waste Management Sites (RWMSs) (one site is in Area 3 and the other is in Area 5) at the Nevada Test Site (NTS) for the U.S. Department of Energy's (DOE's) National Nuclear Security Administration Nevada Operations Office (NNSA/NV). The current DOE Order governing management of radioactive waste is 435.1. Associated with DOE Order 435.1 is a Manual (DOE M 435.1-1) and Guidance (DOE G 435.1-1). The Manual and Guidance specify that preliminary closure and monitoring plans for a low-level waste (LLW) management facility be developed and initially submitted with the Performance Assessment (PA) and Composite Analysis (CA) for that facility. The Manual and Guidance, and the Disposal Authorization Statement (DAS) issued for the Area 3 RWMS further specify that the preliminary closure and monitoring plans be updated within one year following issuance of a DAS. This Integrated Closure and Monitoring Plan (ICMP) fulfills both requirements. Additional updates will be conducted every third year hereafter. This document is an integrated plan for closing and monitoring both RWMSs, and is based on guidance issued in 1999 by the DOE for developing closure plans. The plan does not follow the format suggested by the DOE guidance in order to better accommodate differences between the two RWMSs, especially in terms of operations and site characteristics. The modification reduces redundancy and provides a smoother progression of the discussion. The closure and monitoring plans were integrated because much of the information that would be included in individual plans is the same, and integration provides efficient presentation and program management. The ICMP identifies the regulatory requirements, describes the disposal sites and the physical environment where they are located, and defines the approach and schedule for both closing and monitoring the sites.

  13. Complete Phase I Tests As Described in the Multi-lab Test Plan for the Evaluation of CH3I Adsorption on AgZ

    SciTech Connect (OSTI)

    Bruffey, S. H.; Jubin, R. T.

    2014-09-30

    Silver-exchanged mordenite (AgZ) has been identified as a potential sorbent for iodine present in the off-gas streams of a used nuclear fuel reprocessing facility. In such a facility, both elemental and organic forms of iodine are released from the dissolver in gaseous form. These species of iodine must be captured with high efficiency for a facility to avoid radioactive iodine release above regulatory limits in the gaseous effluent of the plant. Studies completed at Idaho National Laboratory (INL) examined the adsorption of organic iodine in the form of CH3I by AgZ. Upon breakthrough of the feed gas through the sorbent bed, elemental iodine was observed in the effluent stream, despite the fact that the only source of iodine in the system was the CH3I in the feed gas.1 This behavior does not appear to have been reported previously nor has it been independently confirmed. Thus, as a result of these prior studies, multiple knowledge gaps relating to the adsorption of CH3I by AgZ were identified, and a multi-lab test plan, including Oak Ridge National Laboratory (ORNL), INL, Pacific Northwest National Laboratory (PNNL), and Sandia National Laboratories, was formulated to address each in a systematic way.2 For this report, the scope of work for ORNL was further narrowed to three thin-bed experiments that would characterize CH3I adsorption onto AgZ in the presence of water, NO, and NO2. Completion of these three-thin bed experiments demonstrated that organic iodine in the form of CH3I was adsorbed by reduced silver mordenite (Ag0Z) to a 50% higher loading than that of I2 when adsorbed from a dry air stream. Adsorption curves suggest different adsorption mechanisms for I2 and CH3I. In the presence of NO and NO2 gas, the loading of CH3I onto Ag0Z is suppressed and may be reversible. Further, the presence of NO and NO2 gas appears to oxidize CH3I to I2; this is indicated by an adsorption curve similar to that of I2 on Ag0Z. Finally, the loss of organic iodine loading capacity by Ag0Z in the presence of NOx is unaffected by the addition of water vapor to the gas stream; no marked additional loss in capacity or retention was observed.

  14. Corrective Action Investigation Plan for Corrective Action Unit 137: Waste Disposal Sites, Nevada Test Site, Nevada, Rev. No.:0

    SciTech Connect (OSTI)

    Wickline, Alfred

    2005-12-01

    This Corrective Action Investigation Plan (CAIP) contains project-specific information including facility descriptions, environmental sample collection objectives, and criteria for conducting site investigation activities at Corrective Action Unit (CAU) 137: Waste Disposal Sites. This CAIP has been developed in accordance with the ''Federal Facility Agreement and Consent Order'' (FFACO) (1996) that was agreed to by the State of Nevada, the U.S. Department of Energy (DOE), and the U.S. Department of Defense. Corrective Action Unit 137 contains sites that are located in Areas 1, 3, 7, 9, and 12 of the Nevada Test Site (NTS), which is approximately 65 miles (mi) northwest of Las Vegas, Nevada (Figure 1-1). Corrective Action Unit 137 is comprised of the eight corrective action sites (CASs) shown on Figure 1-1 and listed below: (1) CAS 01-08-01, Waste Disposal Site; (2) CAS 03-23-01, Waste Disposal Site; (3) CAS 03-23-07, Radioactive Waste Disposal Site; (4) CAS 03-99-15, Waste Disposal Site; (5) CAS 07-23-02, Radioactive Waste Disposal Site; (6) CAS 09-23-07, Radioactive Waste Disposal Site; (7) CAS 12-08-01, Waste Disposal Site; and (8) CAS 12-23-07, Waste Disposal Site. The Corrective Action Investigation (CAI) will include field inspections, radiological surveys, geophysical surveys, sampling of environmental media, analysis of samples, and assessment of investigation results, where appropriate. Data will be obtained to support corrective action alternative evaluations and waste management decisions. The CASs in CAU 137 are being investigated because hazardous and/or radioactive constituents may be present in concentrations that could potentially pose a threat to human health and the environment. Existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend corrective action alternatives for the CASs. Additional information will be generated by conducting a CAI before evaluating and selecting corrective action alternatives.

  15. Hanford Site solid waste acceptance criteria

    SciTech Connect (OSTI)

    Ellefson, M.D.

    1998-07-01

    Order 5820.2A requires that each treatment, storage, and/or disposal facility (referred to in this document as TSD unit) that manages low-level or transuranic waste (including mixed waste and TSCA PCB waste) maintain waste acceptance criteria. These criteria must address the various requirements to operate the TSD unit in compliance with applicable safety and environmental requirements. This document sets forth the baseline criteria for acceptance of radioactive waste at TSD units operated by WMH. The criteria for each TSD unit have been established to ensure that waste accepted can be managed in a manner that is within the operating requirements of the unit, including environmental regulations, DOE Orders, permits, technical safety requirements, waste analysis plans, performance assessments, and other applicable requirements. Acceptance criteria apply to the following TSD units: the Low-Level Burial Grounds (LLBG) including both the nonregulated portions of the LLBG and trenches 31 and 34 of the 218-W-5 Burial Ground for mixed waste disposal; Central Waste Complex (CWC); Waste Receiving and Processing Facility (WRAP); and T Plant Complex. Waste from all generators, both from the Hanford Site and from offsite facilities, must comply with these criteria. Exceptions can be granted as provided in Section 1.6. Specific waste streams could have additional requirements based on the 1901 identified TSD pathway. These requirements are communicated in the Waste Specification Records (WSRds). The Hanford Site manages nonradioactive waste through direct shipments to offsite contractors. The waste acceptance requirements of the offsite TSD facility must be met for these nonradioactive wastes. This document does not address the acceptance requirements of these offsite facilities.

  16. Streamlined Approach for Environmental Restoration Plan for Corrective Action Unit 398: Area 25 Spill Sites, Nevada Test Site, Nevada

    SciTech Connect (OSTI)

    K. B. Campbell

    2001-11-01

    This Streamlined Approach for Environmental Restoration (SAFER) plan addresses the activities necessary to close Corrective Action Unit (CAU) 398: Area 25 Spill Sites. CAU 398, located in Area 25 of the Nevada Test Site, is currently listed in Appendix III of the Federal Facility Agreement and Consent Order (FFACO) (FFACO, 1996), and consists of the following 13 Corrective Action Sites (CASs) (Figure 1): (1) CAS 25-44-01 , a fuel spill on soil that covers a concrete pad. The origins and use of the spill material are unknown, but the spill is suspected to be railroad bedding material. (2) CAS 25-44-02, a spill of liquid to the soil from leaking drums. (3) CAS 25-44-03, a spill of oil from two leaking drums onto a concrete pad and surrounding soil. (4) CAS 25-44-04, a spill from two tanks containing sulfuric acid and sodium hydroxide used for a water demineralization process. (5) CAS 25-25-02, a fuel or oil spill from leaking drums that were removed in 1992. (6) CAS 25-25-03, an oil spill adjacent to a tipped-over drum. The source of the drum is not listed, although it is noted that the drum was removed in 1991. (7) CAS 25-25-04, an area on the north side of the Engine-Maintenance, Assembly, and Disassembly (E-MAD) facility, where oils and cooling fluids from metal machining operations were poured directly onto the ground. (8) CAS 25-25-05, an area of oil and/or hydraulic fluid spills beneath the heavy equipment once stored there. (9) CAS 25-25-06, an area of diesel fuel staining beneath two generators that have since been removed. (10) CAS 25-25-07, an area of hydraulic oil spills associated with a tunnel-boring machine abandoned inside X-Tunnel. (11) CAS 25-25-08, an area of hydraulic fluid spills associated with a tunnel-boring machine abandoned inside Y-Tunnel. (12) CAS 25-25-16, a diesel fuel spill from an above-ground storage tank located near Building 3320 at Engine Test Stand-1 (ETS-1) that was removed in 1998. (13) CAS 25-25-17, a hydraulic oil spill associated with the historical operations of a vacuum pump oil recovery system at the E-MAD facility.

  17. Generalized Test Plan for the Vitrification of Simulated High-Level -Waste Calcine in the Idaho National Laboratory‘s Bench -Scale Cold Crucible Induction Melter

    SciTech Connect (OSTI)

    Vince Maio

    2011-08-01

    This Preliminary Idaho National Laboratory (INL) Test Plan outlines the chronological steps required to initially evaluate the validity of vitrifying INL surrogate (cold) High-Level-Waste (HLW) solid particulate calcine in INL's Cold Crucible Induction Melter (CCIM). Its documentation and publication satisfies interim milestone WP-413-INL-01 of the DOE-EM (via the Office of River Protection) sponsored work package, WP 4.1.3, entitled 'Improved Vitrification' The primary goal of the proposed CCIM testing is to initiate efforts to identify an efficient and effective back-up and risk adverse technology for treating the actual HLW calcine stored at the INL. The calcine's treatment must be completed by 2035 as dictated by a State of Idaho Consent Order. A final report on this surrogate/calcine test in the CCIM will be issued in May 2012-pending next fiscal year funding In particular the plan provides; (1) distinct test objectives, (2) a description of the purpose and scope of planned university contracted pre-screening tests required to optimize the CCIM glass/surrogate calcine formulation, (3) a listing of necessary CCIM equipment modifications and corresponding work control document changes necessary to feed a solid particulate to the CCIM, (4) a description of the class of calcine that will be represented by the surrogate, and (5) a tentative tabulation of the anticipated CCIM testing conditions, testing parameters, sampling requirements and analytical tests. Key FY -11 milestones associated with this CCIM testing effort are also provided. The CCIM test run is scheduled to be conducted in February of 2012 and will involve testing with a surrogate HLW calcine representative of only 13% of the 4,000 m3 of 'hot' calcine residing in 6 INL Bin Sets. The remaining classes of calcine will have to be eventually tested in the CCIM if an operational scale CCIM is to be a feasible option for the actual INL HLW calcine. This remaining calcine's make-up is HLW containing relatively high concentrations of zirconium and aluminum, representative of the cladding material of the reprocessed fuel that generated the calcine. A separate study to define the CCIM testing needs of these other calcine classifications in currently being prepared under a separate work package (WP-0) and will be provided as a milestone report at the end of this fiscal year.

  18. ACCEPTANCE OF OFFER CLINICAL FACULTY

    E-Print Network [OSTI]

    ACCEPTANCE OF OFFER CLINICAL FACULTY 2015 - 2016 By accepting this appointment I represent of offer, I fail to satisfy the above requirements, I understand that this letter of offer obtained if it is required as a condition of my employment. #12;This offer and my acceptance are subject

  19. MEMBERSHIPS WITH A TAX FREE MEAL PLAN

    E-Print Network [OSTI]

    Boonstra, Rudy

    MEAL PLAN MEMBERSHIPS WITH A TAX FREE MEAL PLAN MEAL PLAN BENEFITS... WHERE MEAL PLANS ARE ACCEPTED. . . ELLESMERE ROAD ELLESMERE ROAD M ILITARY TRAIL N NR NR NR NR CC SL AA SW SY HW BV AC SRC JF SR SR SR SR SR SR, all Meal Plan Memberships are refundable but are subject to taxes (if applicable) and administration

  20. Streamlined Approach for (SAFER) Plan for Corrective Action Unit 566: E-MAD Compound, Nevada Test Site, Nevada, Revision 0

    SciTech Connect (OSTI)

    Mark Krauss

    2010-06-01

    This Streamlined Approach for Environmental Restoration (SAFER) Plan addresses the actions needed to achieve closure for Corrective Action Unit (CAU) 566, EMAD Compound, identified in the Federal Facility Agreement and Consent Order (FFACO). Corrective Action Unit 566 comprises the following corrective action site (CAS) located in Area 25 of the Nevada Test Site: • 25-99-20, EMAD Compound This plan provides the methodology for field activities needed to gather the necessary information for closing CAS 25-99-20. There is sufficient information and process knowledge from historical documentation and investigations of similar sites regarding the expected nature and extent of potential contaminants to recommend closure of CAU 566 using the SAFER process. Additional information will be obtained by conducting a field investigation before selecting the appropriate corrective action. It is anticipated that the results of the field investigation and implementation of a corrective action of clean closure will support a defensible recommendation that no further corrective action is necessary. If it is determined that complete clean closure cannot be accomplished during the SAFER, then a hold point will have been reached and the Nevada Division of Environmental Protection (NDEP) will be consulted to determine whether the remaining contamination will be closed under the alternative corrective action of closure in place. This will be presented in a closure report that will be prepared and submitted to NDEP for review and approval. The data quality objective (DQO) strategy for CAU 566 was developed at a meeting on April 30, 2009, by representatives of NDEP and the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office. The DQO process was used to identify and define the type, amount, and quality of data needed to determine and implement appropriate corrective actions for CAU 566. The following text summarizes the SAFER activities that will support the closure of CAU 566: • Perform site preparation activities (e.g., utilities clearances, radiological surveys). • Collect environmental samples from designated target populations (e.g., stained soil) to confirm or disprove the presence of contaminants of concern (COCs) as necessary to supplement existing information. • Collect samples of materials to determine whether potential source material (PSM) is present that may cause the future release of a COC to environmental media. • If no COCs or PSMs are present at a CAS, establish no further action as the corrective action. • If COCs exist, collect environmental samples from designated target populations (e.g., clean soil adjacent to contaminated soil) and submit for laboratory analyses to define the extent of COC contamination. • If a COC or PSM is present at a CAS, either: - Establish clean closure as the corrective action. The material to be remediated will be removed, disposed of as waste, and verification samples will be collected from remaining soil, or - Establish closure in place as the corrective action and implement the appropriate use restrictions. • Confirm the selected closure option is sufficient to protect human health and the environment.

  1. Test plan for the M-100 container model M-101/7A/12/90 Docket 96-43-7A, type A container

    SciTech Connect (OSTI)

    Kelly, D.L.

    1997-05-30

    This document describes the test plan for the M-100 Container, Model M-101/7A/12/90. This packaging system is designed to ship Type A solid, radioactive materials, normal form, Form Nos. 1, 2, and 3. The nominal overall dimensions, including risers, of the M-100 Container are 79 x 54 x 42 inches. The capacity of the container is approximately 89.9 ft. The estimated gross weight of the packaging and contents is 9,000 lb.

  2. Summary description of the Fast Flux Test Facility

    SciTech Connect (OSTI)

    Cabell, C.P.

    1980-12-01

    This document has been compiled and issued to provide an illustrated engineering summary description of the FFTF. The document is limited to a description of the plant and its functions, and does not cover the extensive associated programs that have been carried out in the fields of design, design analysis, safety analysis, fuels development, equipment development and testing, quality assurance, equipment fabrication, plant construction, acceptance testing, operations planning and training, and the like.

  3. EV Everywhere Consumer Acceptance and Charging Infrastructure...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Consumer Acceptance and Public Policy Group C Breakout Report EV Everywhere Consumer Acceptance and Charging Infrastructure Workshop: Consumer Acceptance and Public Policy Group C...

  4. EV Everywhere Consumer Acceptance and Charging Infrastructure...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Consumer Acceptance Group A Breakout Report EV Everywhere Consumer Acceptance and Charging Infrastructure Workshop: Consumer Acceptance Group A Breakout Report Breakout session...

  5. Corrective Action Investigation Plan for Corrective Action Unit 105: Area 2 Yucca Flat Atmospheric Test Sites Nevada National Security Site, Nevada, Revision 0

    SciTech Connect (OSTI)

    Patrick Matthews

    2012-09-01

    Corrective Action Unit (CAU) 105 is located in Area 2 of the Nevada National Security Site, which is approximately 65 miles northwest of Las Vegas, Nevada. CAU 105 is a geographical grouping of sites where there has been a suspected release of contamination associated with atmospheric nuclear testing. This document describes the planned investigation of CAU 105, which comprises the following corrective action sites (CASs): • 02-23-04, Atmospheric Test Site - Whitney • 02-23-05, Atmospheric Test Site T-2A • 02-23-06, Atmospheric Test Site T-2B • 02-23-08, Atmospheric Test Site T-2 • 02-23-09, Atmospheric Test Site - Turk These sites are being investigated because existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend corrective action alternatives (CAAs). Additional information will be obtained by conducting a corrective action investigation before evaluating CAAs and selecting the appropriate corrective action for each CAS. The results of the field investigation will support a defensible evaluation of viable CAAs that will be presented in the Corrective Action Decision Document. The sites will be investigated based on the data quality objectives (DQOs) developed on April 30, 2012, by representatives of the Nevada Division of Environmental Protection and the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office. The DQO process was used to identify and define the type, amount, and quality of data needed to develop and evaluate appropriate corrective actions for CAU 105. The site investigation process will also be conducted in accordance with the Soils Activity Quality Assurance Plan, which establishes requirements, technical planning, and general quality practices to be applied to this activity. The potential contamination sources associated with all CAU 105 CASs are from atmospheric nuclear testing activities. The presence and nature of contamination at CAU 105 will be evaluated based on information collected from a field investigation. Radiological contamination will be evaluated based on a comparison of the total effective dose at sample locations to the dose-based final action level. The total effective dose will be calculated as the total of separate estimates of internal and external dose. Results from the analysis of soil samples will be used to calculate internal radiological dose. Thermoluminescent dosimeters placed at the center of each sample location will be used to measure external radiological dose. Appendix A provides a detailed discussion of the DQO methodology and the DQOs specific to each CAS. This Corrective Action Investigation Plan has been developed in accordance with the Federal Facility Agreement and Consent Order that was agreed to by the State of Nevada; DOE, Environmental Management; U.S. Department of Defense; and DOE, Legacy Management. Under the Federal Facility Agreement and Consent Order, this Corrective Action Investigation Plan will be submitted to the Nevada Division of Environmental Protection for approval. Fieldwork will be conducted after the plan is approved.

  6. Streamlined Approach for Environmental Restoration (SAFER) Plan for Corrective Action Unit 124: Storage Tanks, Nevada Test Site, Nevada (Draft), Revision 0

    SciTech Connect (OSTI)

    Alfred Wickline

    2007-04-01

    This Streamlined Approach for Environmental Restoration (SAFER) Plan addresses closure for Corrective Action Unit (CAU) 124, Areas 8, 15, and 16 Storage Tanks, identified in the Federal Facility Agreement and Consent Order. Corrective Action Unit 124 consists of five Corrective Action Sites (CASs) located in Areas 8, 15, and 16 of the Nevada Test Site as follows: • 08-02-01, Underground Storage Tank • 15-02-01, Irrigation Piping • 16-02-03, Underground Storage Tank • 16-02-04, Fuel Oil Piping • 16-99-04, Fuel Line (Buried) and UST This plan provides the methodology of field activities necessary to gather information to close each CAS. There is sufficient information and process knowledge from historical documentation and investigations of similar sites regarding the expected nature and extent of potential contaminants to recommend closure of CAU 124 using the SAFER process.

  7. Streamlined Approach for Environmental Restoration Plan for Corrective Action Unit 113: Reactor Maintenance, Assembly, and Disassembly Building Nevada Test Site, Nevada

    SciTech Connect (OSTI)

    J. L. Smith

    2001-01-01

    This Streamlined Approach for Environmental Restoration (SAFER) Plan addresses the action necessary for the closure in place of Corrective Action Unit (CAU) 113 Area 25 Reactor Maintenance, Assembly, and Disassembly Facility (R-MAD). CAU 113 is currently listed in Appendix III of the Federal Facility Agreement and Consent Order (FFACO) (NDEP, 1996). The CAU is located in Area 25 of the Nevada Test Site (NTS) and consists of Corrective Action Site (CAS) 25-04-01, R-MAD Facility (Figures 1-2). This plan provides the methodology for closure in place of CAU 113. The site contains radiologically impacted and hazardous material. Based on preassessment field work, there is sufficient process knowledge to close in place CAU 113 using the SAFER process. At a future date when funding becomes available, the R-MAD Building (25-3110) will be demolished and inaccessible radiologic waste will be properly disposed in the Area 3 Radiological Waste Management Site (RWMS).

  8. Corrective Action Investigation Plan for Corrective Action Unit 541: Small Boy Nevada National Security Site and Nevada Test and Training Range, Nevada with ROTC 1

    SciTech Connect (OSTI)

    Matthews, Patrick

    2014-09-01

    Corrective Action Unit (CAU) 541 is co-located on the boundary of Area 5 of the Nevada National Security Site and Range 65C of the Nevada Test and Training Range, approximately 65 miles northwest of Las Vegas, Nevada. CAU 541 is a grouping of sites where there has been a suspected release of contamination associated with nuclear testing. This document describes the planned investigation of CAU 541, which comprises the following corrective action sites (CASs): • 05-23-04, Atmospheric Tests (6) - BFa Site • 05-45-03, Atmospheric Test Site - Small Boy These sites are being investigated because existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend corrective action alternatives (CAAs). Additional information will be obtained by conducting a corrective action investigation before evaluating CAAs and selecting the appropriate corrective action for each CAS. The results of the field investigation will support a defensible evaluation of viable CAAs that will be presented in the investigation report. The sites will be investigated based on the data quality objectives (DQOs) developed on April 1, 2014, by representatives of the Nevada Division of Environmental Protection; U.S. Air Force; and the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Field Office. The DQO process was used to identify and define the type, amount, and quality of data needed to develop and evaluate appropriate corrective actions for CAU 541. The site investigation process also will be conducted in accordance with the Soils Activity Quality Assurance Plan, which establishes requirements, technical planning, and general quality practices to be applied to this activity. The potential contamination sources associated with CASs 05-23-04 and 05-45-03 are from nuclear testing activities conducted at the Atmospheric Tests (6) - BFa Site and Atmospheric Test Site - Small Boy sites. The presence and nature of contamination at CAU 541 will be evaluated based on information collected from field investigations. Radiological contamination will be evaluated based on a comparison of the total effective dose at sample locations to the dose-based final action level. The total effective dose will be calculated as the total of separate estimates of internal and external dose. Results from the analysis of soil samples will be used to calculate internal radiological dose. Thermoluminescent dosimeters placed at the center of each sample location will be used to measure external radiological dose. Appendix A provides a detailed discussion of the DQO methodology and the DQOs specific to each CAS.

  9. ACCEPTANCE OF OFFER CLINICAL FACULTY

    E-Print Network [OSTI]

    ACCEPTANCE OF OFFER CLINICAL FACULTY 2015 - 2016 By accepting this appointment I represent and final approval by the Board of Supervisors of the letter of offer, I fail to satisfy the above requirements, I understand that this letter of offer will automatically be null, void, and is deemed rescinded

  10. Test Plan for the Demonstration of Geophysical Techniques for Single-Shell Tank Leak Detection at the Hanford Mock Tank Site: Fiscal Year 2001

    SciTech Connect (OSTI)

    Barnett, D. Brent; Gee, Glendon W.; Sweeney, Mark D.

    2001-07-31

    As part of the Leak Detection, Monitoring and Mitigation (LDMM) program conducted by CH2M HILL 105-A during FY 2001. These tests are being conducted to assess the applicability of these methods (Electrical Resistance Tomography [ERT], High Resolution Resistivity [HRR], Cross-Borehole Seismography [XBS], Cross-Borehole Radar [XBR], and Cross-Borehole Electromagnetic Induction [CEMI]) to the detection and measurement of Single Shell Tank (SST) leaks into the vadose zone during planned sluicing operations. The testing in FY 2001 will result in the selection of up to two methods for further testing in FY 2002. In parallel with the geophysical tests, a Partitioning Interwell Tracer Test (PITT) study will be conducted simultaneously at the Mock Tank to assess the effectiveness of this technology in detecting and quantifying tank leaks in the vadose zone. Preparatory and background work using Cone Penetrometer methods (CPT) will be conducted at the Mock Tank site and an adjacent test area to derive soil properties for groundtruthing purposes for all methods.

  11. Test Plan for Westinghouse Hanford Company`s Hedgehog Shielded Container, Docket 94-39-7A, Type A Container

    SciTech Connect (OSTI)

    Kelly, D.L.

    1995-02-27

    This report documents the US Department of Transportation Specification 7A Type A (DOT-7A) compliance testing to be followed for qualification of the Westinghouse Hanford Company`s Hedgehog Shielded Container for use as a Type A packaging. The packaging configurations being tested are intended for liquids and solids, and for air transportation.

  12. Record of Technical Change No.1 for ``Corrective Action Investigation Plan for Corrective Action Unit 321: Area 22 Weather Station Fuel Storage, Nevada Test Site, Nevada''

    SciTech Connect (OSTI)

    DOE /NV

    1999-02-16

    This Record of Technical Change provides updates to the technical information provided in ''Corrective Action Investigation Plan for Corrective Action Unit 321: Area 22 Weather Station Fuel Storage, Nevada Test Site, Nevada,'' Revision 0. The change specified is in Table 3-1 on page 11. The total lead analyte should specify a Minimum Reporting Limit for soil of 1.0 mg/kg instead of 0.3 mg/kg. The EMAX laboratory cannot meet the 0.3 mg/kg limit.

  13. Leak testing plan for the Oak Ridge National Laboratory liquid low-level waste systems (active tanks): Revision 2. Volume 1: Regulatory background and plan approach; Volume 2: Methods, protocols, and schedules; Volume 3: Evaluation of the ORNL/LT-823DP differential pressure leak detection method; Appendix to Revision 2: DOE/EPA/TDEC correspondence

    SciTech Connect (OSTI)

    Douglas, D.G.; Wise, R.F.; Starr, J.W.; Maresca, J.W. Jr. [Vista Research, Inc., Mountain View, CA (United States)

    1994-11-01

    This document, the Leak Testing Plan for the Oak Ridge National Laboratory Liquid Low-Level Waste System (Active Tanks), comprises three volumes. The first two volumes address the component-based leak testing plan for the liquid low-level waste system at Oak Ridge, while the third volume describes the performance evaluation of the leak detection method that will be used to test this system. Volume 1, describes that portion of the liquid low-level waste system at that will be tested; it provides the regulatory background, especially in terms of the requirements stipulated in the Federal Facilities Agreement, upon which the leak testing plan is based. Volume 1 also describes the foundation of the plan, portions of which were abstracted from existing federal documents that regulate the petroleum and hazardous chemicals industries. Finally, Volume 1 gives an overview the plan, describing the methods that will be used to test the four classes of components in the liquid low-level waste system. Volume 2 takes the general information on component classes and leak detection methods presented in Volume 1 and shows how it applies particularly to each of the individual components. A complete test plan for each of the components is presented, with emphasis placed on the methods designated for testing tanks. The protocol for testing tank systems is described, and general leak testing schedules are presented. Volume 3 describes the results of a performance evaluation completed for the leak testing method that will be used to test the small tanks at the facility (those less than 3,000 gal in capacity). Some of the details described in Volumes 1 and 2 are expected to change as additional information is obtained, as the viability of candidate release detection methods is proven in the Oak Ridge environment, and as the testing program evolves.

  14. Acceptable Documents for Identity Proofing

    Broader source: Energy.gov [DOE]

    It is a requirement that the identity of a DOE Digital Identity Subscriber be verified against acceptable identity source documents. A Subscriber must appear in person and present their Federal...

  15. Corrective Action Investigation Plan for Corrective Action Unit 99: Rainier Mesa/Shoshone Mountain, Nevada Test Site, Nevada with Errata and ROTC 1, Rev. No. 0

    SciTech Connect (OSTI)

    John McCord; Marutzky, Sam

    2004-12-01

    This Corrective Action Investigation Plan (CAIP) was developed for Corrective Action Unit (CAU) 99, Rainier Mesa/Shoshone Mountain. The CAIP is a requirement of the ''Federal Facility Agreement and Consent Order'' (FFACO) agreed to by the State of Nevada, the U.S. Department of Energy (DOE), and the U.S. Department of Defense (DoD) (FFACO, 1996). The FFACO addresses environmental restoration activities at U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office (NNSA/NSO) facilities and sites including the underground testing area(s) of the Nevada Test Site (NTS). This CAIP describes the investigation activities currently planned for the Rainier Mesa/Shoshone Mountain CAU. These activities are consistent with the current Underground Test Area (UGTA) Project strategy described in Section 3.0 of Appendix VI, Revision No. 1 (December 7, 2000) of the FFACO (1996) and summarized in Section 2.1.2 of this plan. The Rainier Mesa/Shoshone Mountain CAU extends over several areas of the NTS (Figure 1-1) and includes former underground nuclear testing locations in Areas 12 and 16. The area referred to as ''Rainier Mesa'' includes the geographical area of Rainier Mesa proper and the contiguous Aqueduct Mesa. Figure 1-2 shows the locations of the tests (within tunnel complexes) conducted at Rainier Mesa. Shoshone Mountain is located approximately 20 kilometers (km) south of Rainier Mesa, but is included within the same CAU due to similarities in their geologic setting and in the nature and types of nuclear tests conducted. Figure 1-3 shows the locations of the tests conducted at Shoshone Mountain. The Rainier Mesa/Shoshone Mountain CAU falls within the larger-scale Rainier Mesa/Shoshone Mountain Investigation Area, which also includes the northwest section of the Yucca Flat CAU as shown in Figure 1-1. Rainier Mesa and Shoshone Mountain lie adjacent to the Timber Mountain Caldera Complex and are composed of volcanic rocks that erupted from the caldera as well as from more distant sources. This has resulted in a layered volcanic stratigraphy composed of thick deposits of welded and nonwelded ash-flow tuff and lava flows. These deposits are proximal to the source caldera and are interstratified with the more distal facies of fallout tephra and bedded reworked tuff from more distant sources. In each area, a similar volcanic sequence was deposited upon Paleozoic carbonate and siliciclastic rocks that are disrupted by various thrust faults, normal faults, and strike-slip faults. In both Rainier Mesa (km) to the southwest, and Tippipah Spring, 4 km to the north, and the tunnel complex is dry. Particle-tracking simulations performed during the value of information analysis (VOIA) (SNJV, 2004b) indicate that most of the regional groundwater that underlies the test locations at Rainier Mesa and Shoshone Mountain eventually follows similar and parallel paths and ultimately discharges in Death Valley and the Amargosa Desert. Particle-tracking simulations conducted for the regional groundwater flow and risk assessment indicated that contamination from Rainier Mesa and Shoshone Mountain were unlikely to leave the NTS during the 1,000-year period of interest (DOE/NV, 1997a). It is anticipated that CAU-scale modeling will modify these results somewhat, but it is not expected to radically alter the outcome of these previous particle-tracking simulations within the 1,000-year period of interest. The Rainier Mesa/Shoshone Mountain CAIP describes the corrective action investigation (CAI) to be conducted at the Rainier Mesa/Shoshone Mountain CAU to evaluate the extent of contamination in groundwater due to the underground nuclear testing. The CAI will be conducted by the UGTA Project, which is part of the NNSA/NSO Environmental Restoration Project (ERP). The purpose and scope of the CAI are presented in this section, followed by a summary of the entire document.

  16. ORISE: Exercise Planning

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    exercises to test disaster preparedness plans, including full-function exercises, drills and tabletops to ready the U.S. Department of Energy (DOE) and other government...

  17. Acceptance Criteria Framework for Autonomous Biological Detectors

    SciTech Connect (OSTI)

    Dzenitis, J M

    2006-12-12

    The purpose of this study was to examine a set of user acceptance criteria for autonomous biological detection systems for application in high-traffic, public facilities. The test case for the acceptance criteria was the Autonomous Pathogen Detection System (APDS) operating in high-traffic facilities in New York City (NYC). However, the acceptance criteria were designed to be generally applicable to other biological detection systems in other locations. For such detection systems, ''users'' will include local authorities (e.g., facility operators, public health officials, and law enforcement personnel) and national authorities [including personnel from the Department of Homeland Security (DHS), the BioWatch Program, the Centers for Disease Control and Prevention (CDC), and the Federal Bureau of Investigation (FBI)]. The panel members brought expertise from a broad range of backgrounds to complete this picture. The goals of this document are: (1) To serve as informal guidance for users in considering the benefits and costs of these systems. (2) To serve as informal guidance for developers in understanding the needs of users. In follow-up work, this framework will be used to systematically document the APDS for appropriateness and readiness for use in NYC.

  18. Corrective Action Investigation Plan for Corrective Action Unit 570: Area 9 Yucca Flat Atmospheric Test Sites Nevada National Security Site, Nevada, Revision 0

    SciTech Connect (OSTI)

    Patrick Matthews

    2012-08-01

    CAU 570 comprises the following six corrective action sites (CASs): • 02-23-07, Atmospheric Test Site - Tesla • 09-23-10, Atmospheric Test Site T-9 • 09-23-11, Atmospheric Test Site S-9G • 09-23-14, Atmospheric Test Site - Rushmore • 09-23-15, Eagle Contamination Area • 09-99-01, Atmospheric Test Site B-9A These sites are being investigated because existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend corrective action alternatives (CAAs). Additional information will be obtained by conducting a corrective action investigation before evaluating CAAs and selecting the appropriate corrective action for each CAS. The results of the field investigation will support a defensible evaluation of viable CAAs that will be presented in the Corrective Action Decision Document. The sites will be investigated based on the data quality objectives (DQOs) developed on April 30, 2012, by representatives of the Nevada Division of Environmental Protection and the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office. The DQO process was used to identify and define the type, amount, and quality of data needed to develop and evaluate appropriate corrective actions for CAU 570. The site investigation process will also be conducted in accordance with the Soils Activity Quality Assurance Plan, which establishes requirements, technical planning, and general quality practices to be applied to this activity. The presence and nature of contamination at CAU 570 will be evaluated based on information collected from a field investigation. Radiological contamination will be evaluated based on a comparison of the total effective dose at sample locations to the dose-based final action level. The total effective dose will be calculated as the total of separate estimates of internal and external dose. Results from the analysis of soil samples will be used to calculate internal radiological dose. Thermoluminescent dosimeters placed near the center of each sample location will be used to measure external radiological dose. Appendix A provides a detailed discussion of the DQO methodology and the DQOs specific to each CAS.

  19. Energy Department Accepting Small Business Grant Applications...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Accepting Small Business Grant Applications for Low-Head Hydropower Turbines and MHK Monitoring Systems Energy Department Accepting Small Business Grant Applications for Low-Head...

  20. Initiating the Validation of CCIM Processability for Multi-phase all Ceramic (SYNROC) HLW Form: Plan for Test BFY14CCIM-C

    SciTech Connect (OSTI)

    Vince Maio

    2014-08-01

    This plan covers test BFY14CCIM-C which will be a first–of–its-kind demonstration for the complete non-radioactive surrogate production of multi-phase ceramic (SYNROC) High Level Waste Forms (HLW) using Cold Crucible Induction Melting (CCIM) Technology. The test will occur in the Idaho National Laboratory’s (INL) CCIM Pilot Plant and is tentatively scheduled for the week of September 15, 2014. The purpose of the test is to begin collecting qualitative data for validating the ceramic HLW form processability advantages using CCIM technology- as opposed to existing ceramic–lined Joule Heated Melters (JHM) currently producing BSG HLW forms. The major objectives of BFY14CCIM-C are to complete crystalline melt initiation with a new joule-heated resistive starter ring, sustain inductive melting at temperatures between 1600 to 1700°C for two different relatively high conductive materials representative of the SYNROC ceramic formation inclusive of a HLW surrogate, complete melter tapping and pouring of molten ceramic material in to a preheated 4 inch graphite canister and a similar canister at room temperature. Other goals include assessing the performance of a new crucible specially designed to accommodate the tapping and pouring of pure crystalline forms in contrast to less recalcitrant amorphous glass, assessing the overall operational effectiveness of melt initiation using a resistive starter ring with a dedicated power source, and observing the tapped molten flow and subsequent relatively quick crystallization behavior in pans with areas identical to standard HLW disposal canisters. Surrogate waste compositions with ceramic SYNROC forming additives and their measured properties for inductive melting, testing parameters, pre-test conditions and modifications, data collection requirements, and sampling/post-demonstration analysis requirements for the produced forms are provided and defined.

  1. Corrective Action Plan for Corrective Action Unit 321: Area 22 Weather Station Fuel Storage Nevada Test Site, Nevada

    SciTech Connect (OSTI)

    D. S. Tobiason

    2000-06-01

    The purpose of this Corrective Action Plan (CAP) is to provide the strategy and methodology to close the Area 22 Weather Station Fuel Storage. The CAU will be closed following state and federal regulations and the FFACO (1996). Site characterization was done during February 1999. Soil samples were collected using a direct-push method. Soil samples were collected at 0.6-m (2-ft) intervals from the surface to 1.8 m (6 ft) below ground surface. The results of the characterization were reported in the Corrective Action Decision Document (CADD) (DOE, 1999b). Soil sample results indicated that two locations in the bermed area contain total petroleum hydrocarbons (TPH) as diesel at concentrations of 124 milligrams per kilogram (mg/kg) and 377 mg/kg. This exceeds the Nevada Division of Environmental Protection (NDEP) regulatory action level for TPH of 100 mg/kg (Nevada Administrative Code, 1996). The TPH-impacted soil will be removed and disposed as part of the corrective action.

  2. Second Line of Defense, Port of Buenos Aires and Exolgan Container Terminal Operational Testing and Evaluation Plan, Buenos Aires, Argentina

    SciTech Connect (OSTI)

    Roberts, Bryan W.

    2012-08-23

    The Office of the Second Line of Defense (SLD) Megaports project team for Argentina will conduct operational testing and evaluation (OT&E) at Exolgan Container Terminal at the Port of Dock Sud from July 16-20, 2012; and at the Port of Buenos Aires from September 3-7, 2012. SLD is installing radiation detection equipment to screen export, import, and transshipment containers at these locations. The purpose of OT&E is to validate and baseline an operable system that meets the SLD mission and to ensure the system continues to perform as expected in an operational environment with Argentina Customs effectively adjudicating alarms.

  3. Proceedings of the 22nd Annual DoD/DOE Seismic Research Symposium: Planning for Verification of and Compliance with the Comprehensive Nuclear-Test-Ban Treaty (CTBT)

    SciTech Connect (OSTI)

    Nichols, James W., LTC

    2000-09-15

    These proceedings contain papers prepared for the 22nd Annual DoD/DOE Seismic Research Symposium: Planning for Verification of and Compliance with the Comprehensive Nuclear-Test-Ban Treaty (CTBT), held 13-15 September 2000 in New Orleans, Louisiana. These papers represent the combined research related to ground-based nuclear explosion monitoring funded by the National Nuclear Security Administration (NNSA), Defense Threat Reduction Agency (DTRA), Air Force Technical Applications Center (AFTAC), Department of Defense (DoD), US Army Space and Missile Defense Command, Defense Special Weapons Agency (DSWA), and other invited sponsors. The scientific objectives of the research are to improve the United States capability to detect, locate, and identify nuclear explosions. The purpose of the meeting is to provide the sponsoring agencies, as well as potential users, an opportunity to review research accomplished during the preceding year and to discuss areas of investigation for the coming year. For the researchers, it provides a forum for the exchange of scientific information toward achieving program goals, and an opportunity to discuss results and future plans. Paper topics include: seismic regionalization and calibration; detection and location of sources; wave propagation from source to receiver; the nature of seismic sources, including mining practices; hydroacoustic, infrasound, and radionuclide methods; on-site inspection; and data processing.

  4. Corrective Action Investigation Plan for Corrective Action Unit 545: Dumps, Waste Disposal Sites, and Buried Radioactive Materials Nevada Test Site, Nevada, Revision 0

    SciTech Connect (OSTI)

    Alfred Wickline

    2007-06-01

    Corrective Action Unit 545, Dumps, Waste Disposal Sites, and Buried Radioactive Materials, consists of seven inactive sites located in the Yucca Flat area and one inactive site in the Pahute Mesa area. The eight CAU 545 sites consist of craters used for mud disposal, surface or buried waste disposed within craters or potential crater areas, and sites where surface or buried waste was disposed. The CAU 545 sites were used to support nuclear testing conducted in the Yucca Flat area during the 1950s through the early 1990s, and in Area 20 in the mid-1970s. This Corrective Action Investigation Plan has been developed in accordance with the Federal Facility Agreement and Consent Order that was agreed to by the State of Nevada, the U.S. Department of Energy, and the U.S. Department of Defense. Under the Federal Facility Agreement and Consent Order, this Corrective Action Investigation Plan will be submitted to the Nevada Division of Environmental Protection for approval. Fieldwork will be conducted following approval.

  5. Project test plan for runoff and erosion on fine-soil barrier surfaces and rock-covered side slopes

    SciTech Connect (OSTI)

    Walters, W.H.; Hoover, K.A.; Cadwell, L.L.

    1990-06-01

    Pacific Northwest Laboratory (PNL) and Westinghouse Hanford Company are working together to develop protective barriers to isolate near-surface radioactive waste. The purpose of the barriers is to protect defense wastes at the US Department of Energy's (DOE) Hanford Site from infiltration of precipitation, biointrusion, and surficial erosion for up to 10,000 years without the need for long-term monitoring, maintenance, or institutional control. The barriers will be constructed of layered earth and rock material designed to direct surface and groundwater pathways away from the buried waste. To address soil erosion as it applies to barrier design and long-term stability, a task designed to study this problem has been included in the Protective Barriers Program at PNL. The barrier soil-erosion task will investigate the ability of the soil cover and side slopes to resist the erosional and destabilizing processes from externally applied water. The study will include identification and field testing of the dominant processes contributing to erosion and barrier failure. The effects of rock mulches, vegetation cover on the top fine-grained soil surface, as well as the stability of rock armoring on the side slopes, will be evaluated. Some of the testing will include the effects of animal intrusion on barrier erosion, and these will be coordinated with other animal intrusion studies. 6 refs., 4 figs., 1 tab.

  6. Safety Planning for the H-Prize Competition

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    are essential to establish public confidence and for reducing barriers to widespread acceptance of hydrogen technologies. Safety Planning * As part of the design submission...

  7. The 1993 baseline biological studies and proposed monitoring plan for the Device Assembly Facility at the Nevada Test Site

    SciTech Connect (OSTI)

    Woodward, B.D.; Hunter, R.B.; Greger, P.D.; Saethre, M.B.

    1995-02-01

    This report contains baseline data and recommendations for future monitoring of plants and animals near the new Device Assembly Facility (DAF) on the Nevada Test Site (NTS). The facility is a large structure designed for safely assembling nuclear weapons. Baseline data was collected in 1993, prior to the scheduled beginning of DAF operations in early 1995. Studies were not performed prior to construction and part of the task of monitoring operational effects will be to distinguish those effects from the extensive disturbance effects resulting from construction. Baseline information on species abundances and distributions was collected on ephemeral and perennial plants, mammals, reptiles, and birds in the desert ecosystems within three kilometers (km) of the DAF. Particular attention was paid to effects of selected disturbances, such as the paved road, sewage pond, and the flood-control dike, associated with the facility. Radiological monitoring of areas surrounding the DAF is not included in this report.

  8. Design, testing, and commercialization plans for the SAIC/STM 20 kW{sub e} solar dish/Stirling system

    SciTech Connect (OSTI)

    Beninga, K.J.; Davenport, R.L.; Johansson, S.N.

    1995-12-31

    As a part of the US Department of Energy`s (DOE) Utility-Scale Joint-Venture Program, Science Applications International Corporation (SAIC) and Stirling Thermal Motors (STM) have teamed to produce a solar dish/Stirling system for utility electricity generation. The 90 m{sup 2} dish concentrator consists of 16 stretched membrane mirror facets on a truss structure with an azimuth/elevation gear drive. The design modifies a faceted stretched membrane dish design developed previously by SAIC and WGA, Inc. in order to simplify the structure and reduce manufacturing costs, The Stirling engine used in the system is the STM 4-120 kinematic Stirling engine. It features variable swash plate control and a direct absorption solar receiver with hydrogen as the operating fluid. A prototype dish/Stirling system has been installed at a test site near Golden, Colorado and is now undergoing tests. The optical and thermal performance of the dish is being characterized using a Coldwater calorimeter and the optical Beam Characterization System (BCS) developed by Sandia National Labs in Albuquerque, New Mexico. After completion of the dish characterization tests, the STM engine will be installed on the dish and system power generation and efficiency will be measured. This paper presents a summary of the SAIC/STM dish/Stirling system design and gives results from initial testing of the system. Also described are SAIC`s plans for manufacturing and commercialization of the dish/Stirling system to utilities and other markets in the US and abroad.

  9. Budget & Planning Strategic Plan

    E-Print Network [OSTI]

    Harms, Kyle E.

    Budget & Planning Strategic Plan Strategic Goal 1: Maintain a suitably staffed, effective the budget and planning needs of the institution. Strategic Goal 5: Identify ways in which B&P information and training opportunities to remain at the forefront of national trends Strategic Goal 2: Continue to meet

  10. Management Plan Management Plan

    E-Print Network [OSTI]

    Management Plan Management Plan "Management and restoration programs for native salmonids have communities" J. Lichatowich et al. 1998. A Conceptual Foundation for the Management of Native Salmonids in the Deschutes River. The Management Plan consists of five elements described in the Council's program: 1

  11. Corrective Action Investigation Plan for Corrective Action Unit 190: Contaminated Waste Sites Nevada Test Site, Nevada, Rev. No.: 0

    SciTech Connect (OSTI)

    Wickline, Alfred

    2006-12-01

    Corrective Action Unit (CAU) 190 is located in Areas 11 and 14 of the Nevada Test Site, which is 65 miles northwest of Las Vegas, Nevada. Corrective Action Unit 190 is comprised of the four Corrective Action Sites (CASs) listed below: (1) 11-02-01, Underground Centrifuge; (2) 11-02-02, Drain Lines and Outfall; (3) 11-59-01, Tweezer Facility Septic System; and (4) 14-23-01, LTU-6 Test Area. These sites are being investigated because existing information is insufficient on the nature and extent of potential contamination to evaluate and recommend corrective action alternatives. Additional information will be obtained before evaluating corrective action alternatives and selecting the appropriate corrective action for each CAS by conducting a corrective action investigation (CAI). The results of the field investigation will support a defensible evaluation of viable corrective action alternatives that will be presented in the Corrective Action Decision Document. The sites will be investigated based on the data quality objectives (DQOs) developed on August 24, 2006, by representatives of the Nevada Division of Environmental Protection; U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office; Stoller-Navarro Joint Venture, and National Security Technologies, LLC. The DQO process was used to identify and define the type, amount, and quality of data needed to develop and evaluate appropriate corrective actions for CAU 190. The scope of the CAU 190 CAI includes the following activities: (1) Move surface debris and/or materials, as needed, to facilitate sampling; (2) Conduct radiological and geophysical surveys; (3) Perform field screening; (4) Collect and submit environmental samples for laboratory analysis to determine whether contaminants of concern (COCs) are present; (5) If COCs are present, collect additional step-out samples to define the lateral and vertical extent of the contamination; (6) Collect samples of source material, if present, to determine the potential for a release; (7) Collect samples of investigation-derived waste, as needed, for waste management and minimization purposes; and (8) Collect quality control samples. This Corrective Action Investigation Document (CAIP) has been developed in accordance with the Federal Facility Agreement and Consent Order (FFACO) agreed to by the State of Nevada, U.S. Department of Energy, and U.S. Department of Defense. Under the FFACO, this CAIP will be submitted to the Nevada Division of Environmental Protection for approval. Field work will be conducted following approval.

  12. Corrective Action Investigation Plan for Corrective Action Unit 262: Area 25 Septic Systems and Underground Discharge Point, Nevada Test Site, Nevada, Revision No. 1 (9/2001)

    SciTech Connect (OSTI)

    NNSA /NV

    2000-07-20

    This corrective action investigation plan contains the U.S. Department of Energy, Nevada Operations Office's approach to collect data necessary to evaluate corrective action alternatives appropriate for the closure of Corrective Action Unit (CAU) 262 under the Federal Facility Agreement and Consent Order. Corrective Action Unit 262 consists of nine Corrective Action Sites (CASs): Underground Storage Tank (25-02-06), Septic Systems A and B (25-04-06), Septic System (25-04-07), Leachfield (25-05-03), Leachfield (25-05-05), Leachfield (25-05-06), Radioactive Leachfield (25-05-08), Leachfield (25-05-12), and Dry Well (25-51-01). Situated in Area 25 at the Nevada Test Site (NTS), sites addressed by CAU 262 are located at the Reactor-Maintenance, Assembly, and Disassembly (R-MAD); Test Cell C; and Engine-Maintenance, Assembly, and Disassembly (E-MAD) facilities. The R-MAD, Test Cell C, and E-MAD facilities supported nuclear rocket reactor and engine testing as part of the Nuclear Rocket Development Station. The activities associated with the testing program were conducted between 1958 and 1973. Based on site history collected to support the Data Quality Objectives process, contaminants of potential concern (COPCs) for the site include oil/diesel-range total petroleum hydrocarbons, volatile organic compounds, semivolatile organic compounds, polychlorinated biphenyls, Resource Conservation and Recovery Act metals, and gamma-emitting radionuclides, isotopic uranium, isotopic plutonium, strontium-90, and tritium. The scope of the corrective action field investigation at the CAU will include the inspection of portions of the collection systems, sampling the contents of collection system features in situ of leachfield logging materials, surface soil sampling, collection of samples of soil underlying the base of inlet and outfall ends of septic tanks and outfall ends of diversion structures and distribution boxes, collection of soil samples from biased or a combination of biased and random locations within the boundaries of the leachfields, collection of soil samples at stepout locations (where needed) to further define lateral and vertical extent of contamination, conduction of discrete field screening, and logging of soil borings and collection of geotechnical samples to assess soil characteristics. Historical information indicates that significant quantities of radioactive material were produced during the rocket engine testing program, some of which was disposed of in radioactive waste disposal systems (posted leachfields) at each of these locations. Process and sanitary effluents were generated and disposed of in other leachfields. The results of this field investigation will be used to develop and evaluate corrective action alternatives for these CASs.

  13. Corrective Action Investigation Plan for Corrective Action Unit 374: Area 20 Schooner Unit Crater Nevada Test Site, Nevada, Revision 0

    SciTech Connect (OSTI)

    Patrick Matthews

    2010-02-01

    Corrective Action Unit 374 is located in Areas 18 and 20 of the Nevada Test Site, which is approximately 65 miles northwest of Las Vegas, Nevada. Corrective Action Unit 374 comprises the five corrective action sites (CASs) listed below: • 18-22-05, Drum • 18-22-06, Drums (20) • 18-22-08, Drum • 18-23-01, Danny Boy Contamination Area • 20-45-03, U-20u Crater (Schooner) These sites are being investigated because existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend corrective action alternatives (CAAs). Additional information will be obtained by conducting a corrective action investigation before evaluating CAAs and selecting the appropriate corrective action for each CAS. The results of the field investigation will support a defensible evaluation of viable CAAs that will be presented in the Corrective Action Decision Document. The sites will be investigated based on the data quality objectives (DQOs) developed on October 20, 2009, by representatives of the Nevada Division of Environmental Protection and the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office. The DQO process was used to identify and define the type, amount, and quality of data needed to develop and evaluate appropriate corrective actions for CAU 374.

  14. Streamlined Approach for Environmental Restoration (SAFER) Plan for Corrective Action Unit 408: Bomblet Target Area Tonopah Test Range (TTR), Nevada, Revision 1

    SciTech Connect (OSTI)

    Mark Krauss

    2010-03-01

    This Streamlined Approach for Environmental Restoration Plan addresses the actions needed to achieve closure of Corrective Action Unit (CAU) 408, Bomblet Target Area (TTR). Corrective Action Unit 408 is located at the Tonopah Test Range and is currently listed in Appendix III of the Federal Facility Agreement and Consent Order. Corrective Action Unit 408 comprises Corrective Action Site TA-55-002-TAB2, Bomblet Target Areas. Clean closure of CAU 408 will be accomplished by removal of munitions and explosives of concern within seven target areas and potential disposal pits. The target areas were used to perform submunitions related tests for the U.S. Department of Energy (DOE). The scope of CAU 408 is limited to submunitions released from DOE activities. However, it is recognized that the presence of other types of unexploded ordnance and munitions may be present within the target areas due to the activities of other government organizations. The CAU 408 closure activities consist of: • Clearing bomblet target areas within the study area. • Identifying and remediating disposal pits. • Collecting verification samples. • Performing radiological screening of soil. • Removing soil containing contaminants at concentrations above the action levels. Based on existing information, contaminants of potential concern at CAU 408 include unexploded submunitions, explosives, Resource Conservation Recovery Act metals, and depleted uranium. Contaminants are not expected to be present in the soil at concentrations above the action levels; however, this will be determined by radiological surveys and verification sample results.

  15. Pseudofunctional Delay Tests For High Quality Small Delay Defect Testing 

    E-Print Network [OSTI]

    Lahiri, Shayak

    2012-02-14

    Testing integrated circuits to verify their operating frequency, known as delay testing, is essential to achieve acceptable product quality. The high cost of functional testing has driven the industry to automatically-generated ...

  16. Streamlined Approach for Environmental Restoration (SAFER) Plan for Corrective Action Unit 118: Area 27 Super Kukla Facility, Nevada Test Site, Nevada, Rev. No.: 1

    SciTech Connect (OSTI)

    David Strand

    2006-09-01

    This Streamlined Approach for Environmental Restoration (SAFER) plan addresses closure for Corrective Action Unit (CAU) 118, Area 27 Super Kukla Facility, identified in the ''Federal Facility Agreement and Consent Order''. Corrective Action Unit 118 consists of one Corrective Action Site (CAS), 27-41-01, located in Area 27 of the Nevada Test Site. Corrective Action Site 27-41-01 consists of the following four structures: (1) Building 5400A, Reactor High Bay; (2) Building 5400, Reactor Building and access tunnel; (3) Building 5410, Mechanical Building; and (4) Wooden Shed, a.k.a. ''Brock House''. This plan provides the methodology for field activities needed to gather the necessary information for closing the CAS. There is sufficient information and process knowledge from historical documentation and site confirmation data collected in 2005 and 2006 to recommend closure of CAU 118 using the SAFER process. The Data Quality Objective process developed for this CAU identified the following expected closure option: closure in place with use restrictions. This expected closure option was selected based on available information including contaminants of potential concern, future land use, and assumed risks. There are two decisions that need to be answered for closure. Decision I is to determine the nature of contaminants of concern in environmental media or potential source material that could impact human health or the environment. Decision II is to determine whether or not sufficient information has been obtained to confirm that closure objectives were met. This decision includes determining whether the extent of any contamination remaining on site has been defined, and whether actions have been taken to eliminate exposure pathways.

  17. Waste management plan for Hanford spent nuclear fuel characterization activities

    SciTech Connect (OSTI)

    Chastain, S.A. [Westinghouse Hanford Co., Richland, WA (United States); Spinks, R.L. [Pacific Northwest Lab., Richland, WA (United States)

    1994-10-17

    A joint project was initiated between Westinghouse Hanford Company (WHC) and Pacific Northwest Laboratory (PNL) to address critical issues associated with the Spent Nuclear Fuel (SNF) stored at the Hanford Site. Recently, particular attention has been given to remediation of the SNF stored in the K Basins. A waste management plan (WMP) acceptable to both parties is required prior to the movement of selected material to the PNL facilities for examination. N Reactor and Single Pass Reactor (SPR) fuel has been stored for an extended period of time in the N Reactor, PUREX, K-East, and K-West Basins. Characterization plans call for transport of fuel material form the K Basins to the 327 Building Postirradiation Testing Laboratory (PTL) in the 300 Area for examination. However, PNL received a directive stating that no examination work will be started in PNL hot cell laboratories without an approved disposal route for all waste generated related to the activity. Thus, as part of the Characterization Program Management Plan for Hanford Spent Nuclear Fuel, a waste management plan which will ensure that wastes generated as a result of characterization activities conducted at PNL will be accepted by WHC for disposition is required. This document contains the details of the waste handling plan that utilizes, to the greatest extent possible, established waste handling and disposal practices at Hanford between PNL and WHC. Standard practices are sufficient to provides for disposal of most of the waste materials, however, special consideration must be given to the remnants of spent nuclear fuel elements following examination. Fuel element remnants will be repackaged in an acceptable container such as the single element canister and returned to the K Basins for storage.

  18. Received 4 February 2003 Accepted 2 June 2003

    E-Print Network [OSTI]

    Reynolds, John D.

    Received 4 February 2003 Accepted 2 June 2003 Published online 20 August 2003 Migration route data storage tags, were used to test whether these fishes exhibited migration route and spawning area fidelity in successive spawning seasons. Depth and temperature data were recorded for each fish over 365

  19. Corrective Action Investigation Plan for Corrective Action Unit 34: Area 3 Contaminated Waste Site, Nevada Test Site, Nevada (Rev. 0, March 2001)

    SciTech Connect (OSTI)

    U.S. Department of Energy, National Nuclear Security Administration Nevada Operations Office

    2001-03-27

    This Corrective Action Investigation Plan contains the U.S. Department of Energy, National Nuclear Security Administration Nevada Operations Office's approach to collect the data necessary to evaluate corrective action alternatives appropriate for the closure of Corrective Action Unit (CAU) 34 under the Federal Facility Agreement and Consent Order. Corrective Action Unit 34 consists of four Corrective Action Sites (CASs). The CAU is located within the Area 3 Compound at the Nevada Test Site (NTS) in the vicinity of the Mud Plant Facility in Yucca Valley. Historically, CAS 03-09-07, Mud Pit, was used for disposal of excess mud from washing drilling equipment from 1968 to 1974, at which time it began to be used for excess mud disposal (currently inactive); CAS 03-44-01, Chromium Contamination Spill, was used to store additives used in the formulation of drilling mud from the early 1960s to the mid-1990s; CAS 03-47-02, Area 3 Mud Plant Pond, was used as a freshwater storage reservoir for the mud plant as well as supplied water for a number of activities including the mixing of mud, the rinsing and cleaning of tanks, and various washdowns from the 1960s through 1990s; and CAS 03-09-06, Mud Disposal Crater, was created in 1962 by an underground nuclear detonation (i.e., Chinchilla test) and was used to mix and store mud, dispose of receiving waste from the mud plant floor drains and excess drilling mud, and clean/flush mix tanks through the mid-1990s. Based on site history, the scope of this plan is to identify potentially contaminated ground soil at each of the four CASs and determine the quantity, nature, and extent of contaminants of potential concern (COPCs). The investigation will include systematic and biased surface and subsurface soil and mud sampling using hand-auguring and direct-push techniques; visual, video, and/or electromagnetic surveys of pipes; field screening for volatile organic compounds (VOCs) and alpha/beta-emitting radionuclides; and laboratory analysis to characterize any investigation-derived waste for disposal both on site at NTS and at off-site locations. Historical information provided by former NTS employees indicates that COPCs include VOCs, semivolatile organic compounds, Resource Conservation and Recovery Act metals, petroleum hydrocarbons, gamma-emitting radionuclides, isotopic plutonium, and strontium-90. The results of this field investigation will support a defensible evaluation of corrective action alternatives in the corrective action decision document.

  20. National Ignition Facility project acquisition plan

    SciTech Connect (OSTI)

    Callaghan, R.W.

    1996-04-01

    The purpose of this National Ignition Facility Acquisition Plan is to describe the overall procurement strategy planned for the National Ignition Facility (NIF) Project. The scope of the plan describes the procurement activities and acquisition strategy for the following phases of the NIF Project, each of which receives either plant and capital equipment (PACE) or other project cost (OPC) funds: Title 1 and 2 design and Title 3 engineering (PACE); Optics manufacturing facilitization and pilot production (OPC); Convention facility construction (PACE); Procurement, installation, and acceptance testing of equipment (PACE); and Start-up (OPC). Activities that are part of the base Inertial Confinement Fusion (ICF) Program are not included in this plan. The University of California (UC), operating Lawrence Livermore National Laboratory (LLNL) and Los Alamos National Laboratory, and Lockheed-Martin, which operates Sandia National Laboratory (SNL) and the University of Rochester Laboratory for Laser Energetics (UR-LLE), will conduct the acquisition of needed products and services in support of their assigned responsibilities within the NIF Project structure in accordance with their prime contracts with the Department of Energy (DOE). LLNL, designated as the lead Laboratory, will have responsibility for all procurements required for construction, installation, activation, and startup of the NIF.

  1. Addendum to Revision 1 of the Corrective Action Investigation Plan for Corrective Action Unit 98: Frenchman Flat, Nevada Test Site, Nevada (Addendum Revision No. 1)

    SciTech Connect (OSTI)

    U.S. Department of Energy, National Nuclear Security Administration Nevada Operations Office

    2001-06-06

    This document is submitted as an addendum to the Corrective Action Investigation Plan (CAIP) for Corrective Action Unit (CAU) 98: Frenchman Flat, Nevada Test Site (NTS), Nevada. The addendum was prepared to propose work activities in response to comments resulting from the U.S. Department of Energy's (DOE's) review of the draft Frenchman Flat CAU model of groundwater flow and contaminant transport completed in April 1999. The reviewers included an external panel of experts and the Nevada Division of Environmental Protection. As a result of the review, additional work scope, including new data-collection and modeling activities, has been identified for the Frenchman Flat CAU. The proposed work scope described in this addendum will be conducted in accordance with the revised Underground Test Area strategy contained in the December 2000 amendment to the Federal Facility Agreement and Consent Order. The Frenchman Flat CAU model is a group of interdependent models designed to predict the extent of contamination in groundwater due to the underground nuclear tests conducted within this CAU. At the time of the DOE review, the CAU model consisted of a CAU groundwater flow and transport model comprised of two major components: a groundwater flow model and a recharge model. The CAU groundwater flow model is supported by a hydrostratigraphic model and a recharge model, whereas the CAU transport model is supported by a source-term model. As part of the modeling activities proposed in this addendum, two new major components may be added to the Frenchman Flat CAU model: a total-system model and two local groundwater flow and transport models. The reviewers identified several issues relating to insufficiency of data and inadequacy of the modeling process that should be addressed to provide additional confidence in the modeling results with respect to the potential for contaminant migration to the Lower Carbonate Aquifer. The proposed additional work scope includes new data-collection activities, development and use of local-scale models of the two underground nuclear testing areas, and potential revisions of draft CAU groundwater flow and transport models. Upon completion of this work, an evaluation will be made by DOE to ensure that all issues have been resolved.

  2. Corrective Action Investigation Plan for Corrective Action Unit 552: Area 12 Muckpile and Ponds, Nevada Test Site, Nevada, Rev. No.: 1 with ROTC 1 and 2

    SciTech Connect (OSTI)

    David A. Strand

    2005-01-01

    This Corrective Action Investigation Plan (CAIP) contains project-specific information including facility descriptions, environmental sample collection objectives, and criteria for conducting site investigation activities at Corrective Action Unit (CAU) 552: Area 12 Muckpile and Ponds, Nevada Test Site (NTS), Nevada. This CAIP has been developed in accordance with the ''Federal Facility Agreement and Consent Order'' (FFACO) (1996) that was agreed to by the State of Nevada, the U.S. Department of Energy (DOE), and the U.S. Department of Defense. The NTS is approximately 65 miles (mi) northwest of Las Vegas, Nevada (Figure 1-1). Corrective Action Unit 552 is comprised of the one Corrective Action Site which is 12-23-05, Ponds. One additional CAS, 12-06-04, Muckpile (G-Tunnel Muckpile), was removed from this CAU when it was determined that the muckpile is an active site. A modification to the FFACO to remove CAS 12-06-04 was approved by the Nevada Division of Environmental Protection (NDEP) on December 16, 2004. The G-Tunnel ponds were first identified in the 1991 Reynolds Electrical & Engineering Co., Inc. document entitled, ''Nevada Test Site Inventory of Inactive and Abandoned Facilities and Waste Sites'' (REECo, 1991). Corrective Action Unit 552 is being investigated because existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend corrective action alternatives. Therefore, additional information will be obtained by conducting a corrective action investigation (CAI) prior to evaluating and selecting the corrective action alternatives for the site. The CAI will include field inspections, radiological surveys, and sampling of appropriate media. Data will also be obtained to support investigation-derived waste (IDW) disposal and potential future waste management decisions.

  3. Addendum to the Corrective Action Investigation Plan for Corrective Action Unit 321: Area 22 Weather Station Fuel Storage, Nevada Test Site, Nevada (Rev. 0, November 2000)

    SciTech Connect (OSTI)

    DOE /NV

    2000-11-03

    This addendum to the Corrective Action Investigation Plan (CAIP) contains the U.S. Department of Energy, Nevada Operations Office's approach to determine the extent of contamination existing at Corrective Action Unit (CAU) 321. This addendum was required when the extent of contamination exceeded the estimate in the original Corrective Action Decision Document (CADD). Located in Area 22 on the Nevada Test Site, Corrective Action Unit 321, Weather Station Fuel Storage, consists of Corrective Action Site 22-99-05, Fuel Storage Area, was used to store fuel and other petroleum products necessary for motorized operations at the historic Camp Desert Rock facility. This facility was operational from 1951 to 1958 and dismantled after 1958. Based on site history and earlier investigation activities at CAU 321, the contaminant of potential concern (COPC) was previously identified as total petroleum hydrocarbons (diesel-range organics). The scope of this corrective action investigation for the Fuel Storage Area will include the selection of biased sample locations to determine the vertical and lateral extent of contamination, collection of soil samples using rotary sonic drilling techniques, and the utilization of field-screening methods to accurately determine the extent of COPC contamination. The results of this field investigation will support a defensible evaluation of corrective action alternatives and be included in the revised CADD.

  4. Analysis and Design of Power Acceptability Curves

    E-Print Network [OSTI]

    Analysis and Design of Power Acceptability Curves for Industrial Loads Masters Thesis and Final Analysis and Design of Power Acceptability Curves for Industrial Loads Thesis and Final Report John Kyei

  5. Secretary Richardson Accepts Recommendations for Improving Security...

    National Nuclear Security Administration (NNSA)

    Secretary Richardson Accepts Recommendations for Improving Security at Nuclear Weapons Laboratories | National Nuclear Security Administration Facebook Twitter Youtube Flickr RSS...

  6. EV Everywhere Consumer Acceptance and Charging Infrastructure...

    Broader source: Energy.gov (indexed) [DOE]

    dreportoutcaci.pdf More Documents & Publications EV Everywhere Consumer Acceptance and Charging Infrastructure Workshop: Charging Infrastructure Group E...

  7. EV Everywhere Consumer Acceptance and Charging Infrastructure...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Workshop Introduction EV Everywhere Consumer Acceptance and Charging Infrastructure Workshop Introduction Presentation given at the EV Everywhere Grand Challenge: Consumer...

  8. ACCEPTANCE OF OFFER BASIC SCIENCE FACULTY

    E-Print Network [OSTI]

    ACCEPTANCE OF OFFER BASIC SCIENCE FACULTY 2015 - 2016 By accepting this appointment I represent of the letter of offer, I fail to satisfy the above requirements, I understand that this letter of offer obtained if it is required as a condition of my employment. This offer and my acceptance are subject

  9. Preliminary Assessment of the Hanford Tank Waste Feed Acceptance and Product Qualification Programs

    SciTech Connect (OSTI)

    Herman, C. C.; Adamson, Duane J.; Herman, D. T.; Peeler, David K.; Poirier, Micheal R.; Reboul, S. H.; Stone, M. E.; Peterson, Reid A.; Chun, Jaehun; Fort, James A.; Vienna, John D.; Wells, Beric E.

    2013-04-01

    The U.S. Department of Energy Office of Environmental Management (EM) is engaging the national laboratories to provide the scientific and technological rigor to support EM program and project planning, technology development and deployment, project execution, and assessment of program outcomes. As an early demonstration of this new responsibility, Savannah River National Laboratory (SRNL) and Pacific Northwest National Laboratory (PNNL) have been chartered to implement a science and technology program addressing Hanford Tank waste feed acceptance and product qualification. As a first step, the laboratories examined the technical risks and uncertainties associated with the planned waste feed acceptance and qualification testing for Hanford tank wastes. Science and technology gaps were identified for work associated with 1) feed criteria development with emphasis on identifying the feed properties and the process requirements, 2) the Tank Waste Treatment and Immobilization Plant (WTP) process qualification program, and 3) the WTP HLW glass product qualification program. Opportunities for streamlining the accetpance and qualification programs were also considered in the gap assessment. Technical approaches to address the science and technology gaps and/or implement the opportunities were identified. These approaches will be further refined and developed as strong integrated teams of researchers from national laboratories, contractors, industry, and academia are brought together to provide the best science and technology solutions. Pursuing the identified approaches will have immediate and long-term benefits to DOE in reducing risks and uncertainties associated with tank waste removal and preparation, transfers from the tank farm to the WTP, processing within the WTP Pretreatment Facility, and in producing qualified HLW glass products. Additionally, implementation of the identified opportunities provides the potential for long-term cost savings given the anticipated facility life of WTP.

  10. Corrective Action Investigation Plan for Corrective Action Unit 166: Storage Yards and Contaminated Materials, Nevada Test Site, Nevada, Rev. No.: 0

    SciTech Connect (OSTI)

    David Strand

    2006-06-01

    Corrective Action Unit 166 is located in Areas 2, 3, 5, and 18 of the Nevada Test Site, which is 65 miles northwest of Las Vegas, Nevada. Corrective Action Unit (CAU) 166 is comprised of the seven Corrective Action Sites (CASs) listed below: (1) 02-42-01, Cond. Release Storage Yd - North; (2) 02-42-02, Cond. Release Storage Yd - South; (3) 02-99-10, D-38 Storage Area; (4) 03-42-01, Conditional Release Storage Yard; (5) 05-19-02, Contaminated Soil and Drum; (6) 18-01-01, Aboveground Storage Tank; and (7) 18-99-03, Wax Piles/Oil Stain. These sites are being investigated because existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend corrective action alternatives. Additional information will be obtained by conducting a corrective action investigation (CAI) before evaluating corrective action alternatives and selecting the appropriate corrective action for each CAS. The results of the field investigation will support a defensible evaluation of viable corrective action alternatives that will be presented in the Corrective Action Decision Document. The sites will be investigated based on the data quality objectives (DQOs) developed on February 28, 2006, by representatives of the Nevada Division of Environmental Protection; U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office; Stoller-Navarro Joint Venture; and Bechtel Nevada. The DQO process was used to identify and define the type, amount, and quality of data needed to develop and evaluate appropriate corrective actions for CAU 166. Appendix A provides a detailed discussion of the DQO methodology and the DQOs specific to each CAS. The scope of the CAI for CAU 166 includes the following activities: (1) Move surface debris and/or materials, as needed, to facilitate sampling. (2) Conduct radiological surveys. (3) Perform field screening. (4) Collect and submit environmental samples for laboratory analysis to determine if contaminants of concern are present. (5) If contaminants of concern are present, collect additional step-out samples to define the extent of the contamination. (6) Collect samples of investigation-derived waste, as needed, for waste management and minimization purposes. This Corrective Action Investigation Plan has been developed in accordance with the ''Federal Facility Agreement and Consent Order'' that was agreed to by the State of Nevada, the U.S. Department of Energy, and the U.S. Department of Defense. Under the ''Federal Facility Agreement and Consent Order'', this Corrective Action Investigation Plan will be submitted to the Nevada Division of Environmental Protection, and field work will commence following approval.

  11. New Pump and Treat Facility Remedial Action Work Plan for Test Area North (TAN) Final Groundwater Remediation, Operable Unit 1-07B

    SciTech Connect (OSTI)

    L. O. Nelson

    2003-09-01

    This operations and maintenance plan supports the New Pump and Treat Facility (NPTF) remedial action work plan and identifies the approach and requirements for the operations and maintenance activities specific to the final medical zone treatment remedy. The NPTF provides the treatment system necessary to remediate the medical zone portion of the OU 1-07B contaminated groundwater plume. Design and construction of the New Pump and Treat Facility is addressed in the NPTF remedial action work plan. The scope of this operation and maintenance plan includes facility operations and maintenance, remedy five-year reviews, and the final operations and maintenance report for the NPTF.

  12. Phase II Corrective Action Investigation Plan for Corrective Action Units 101 and 102: Central and Western Pahute Mesa, Nevada Test Site, Nye County, Nevada, Revision 2

    SciTech Connect (OSTI)

    Jeff Wurtz

    2009-07-01

    This Phase II CAIP describes new work needed to potentially reduce uncertainty and achieve increased confidence in modeling results. This work includes data collection and data analysis to refine model assumptions, improve conceptual models of flow and transport in a complex hydrogeologic setting, and reduce parametric and structural uncertainty. The work was prioritized based on the potential to reduce model uncertainty and achieve an acceptable level of confidence in the model predictions for flow and transport, leading to model acceptance by NDEP and completion of the Phase II CAI stage of the UGTA strategy.

  13. Inelastic analysis acceptance criteria for radioactive material transportation containers

    SciTech Connect (OSTI)

    Ammerman, D.J.; Ludwigsen, J.S.

    1993-06-01

    The design criteria currently used in the design of radioactive material (RAM) transportation containers are taken from the ASME Boiler and Pressure Vessel Code (ASME, 1992). These load-based criteria are ideally suited for pressure vessels where the loading is quasistatic and all stresses are in equilibrium with externally applied loads. For impact events, the use of load-based criteria is less supportable. Impact events tend to be energy controlled, and thus, energy-based acceptance criteria would appear to be more appropriate. Determination of an ideal design criteria depends on what behavior is desired. Currently there is not a design criteria for inelastic analysis for RAM nation packages that is accepted by the regulatory agencies. This lack of acceptance criteria is one of the major factors in limiting the use of inelastic analysis. In this paper inelastic analysis acceptance criteria based on stress and strain-energy density will be compared for two stainless steel test units subjected to impacts onto an unyielding target. Two different material models are considered for the inelastic analysis, a bilinear fit of the stress-strain curve and a power law hardening model that very closely follows the stress-strain curve. It is the purpose of this paper to stimulate discussion and research into the area of strain-energy density based inelastic analysis acceptance criteria.

  14. Corrective Action Investigation Plan for Corrective Action Unit 224: Decon Pad and Septic Systems Nevada Test Site, Nevada, Rev. No.: 0, with ROTC 1 and 2

    SciTech Connect (OSTI)

    David A. Strand

    2004-04-01

    This Corrective Action Investigation Plan (CAIP) contains project-specific information including facility descriptions, environmental sample collection objectives, and criteria for conducting site investigation activities at Corrective Action Unit (CAU) 224: Decon Pad and Septic Systems, Nevada Test Site (NTS), Nevada. This CAIP has been developed in accordance with the ''Federal Facility Agreement and Consent Order'' (FFACO) (1996) that was agreed to by the State of Nevada, the U.S. Department of Energy (DOE), and the U.S. Department of Defense (DoD). The NTS is approximately 65 miles (mi) northwest of Las Vegas, Nevada (Figure 1-1). Corrective Action Unit 224 is comprised of the nine Corrective Action Sites (CASs) listed below: 02-04-01, Septic Tank (Buried); 03-05-01, Leachfield; 05-04-01, Septic Tanks (4)/Discharge Area; 06-03-01, Sewage Lagoons (3); 06-05-01, Leachfield; 06-17-04, Decon Pad and Wastewater Catch; 06-23-01, Decon Pad Discharge Piping; 11-04-01, Sewage Lagoon; and 23-05-02, Leachfield. Corrective Action Sites 06-05-01, 06-23-01, and 23-05-02 were identified in the 1991 Reynolds Electrical & Engineering Co., Inc. (REECo) inventory (1991). The remaining sites were identified during review of various historical documents. Additional information will be obtained by conducting a corrective action investigation (CAI) prior to evaluating and selecting a corrective action alternative for each CAS. The CAI will include field inspections, radiological and geological surveys, and sample collection. Data will also be obtained to support investigation-derived waste (IDW) disposal and potential future waste management decisions.

  15. Treatment Planning Constraints to Avoid Xerostomia in Head-and-Neck Radiotherapy: An Independent Test of QUANTEC Criteria Using a Prospectively Collected Dataset

    SciTech Connect (OSTI)

    Moiseenko, Vitali, E-mail: vmoiseenko@bccancer.bc.ca [Department of Medical Physics, Vancouver Cancer Centre, British Columbia Cancer Agency, Vancouver, BC (Canada); Wu, Jonn [Department of Radiation Oncology, Vancouver Cancer Centre, British Columbia Cancer Agency, Vancouver, BC (Canada); Hovan, Allan [Department of Oral Oncology, Vancouver Cancer Centre, British Columbia Cancer Agency, Vancouver, BC (Canada); Saleh, Ziad; Apte, Aditya; Deasy, Joseph O. [Department of Medical Physics, Memorial Sloan-Kettering Cancer Center, New York, NY (United States); Harrow, Stephen [Department of Radiation Oncology, Vancouver Cancer Centre, British Columbia Cancer Agency, Vancouver, BC (Canada); Rabuka, Carman; Muggli, Adam [Department of Oral Oncology, Vancouver Cancer Centre, British Columbia Cancer Agency, Vancouver, BC (Canada); Thompson, Anna [Department of Radiation Oncology, Vancouver Cancer Centre, British Columbia Cancer Agency, Vancouver, BC (Canada)

    2012-03-01

    Purpose: The severe reduction of salivary function (xerostomia) is a common complication after radiation therapy for head-and-neck cancer. Consequently, guidelines to ensure adequate function based on parotid gland tolerance dose-volume parameters have been suggested by the QUANTEC group and by Ortholan et al. We perform a validation test of these guidelines against a prospectively collected dataset and compared with a previously published dataset. Methods and Materials: Whole-mouth stimulated salivary flow data from 66 head-and-neck cancer patients treated with radiotherapy at the British Columbia Cancer Agency (BCCA) were measured, and treatment planning data were abstracted. Flow measurements were collected from 50 patients at 3 months, and 60 patients at 12-month follow-up. Previously published data from a second institution, Washington University in St. Louis (WUSTL), were used for comparison. A logistic model was used to describe the incidence of Grade 4 xerostomia as a function of the mean dose of the spared parotid gland. The rate of correctly predicting the lack of xerostomia (negative predictive value [NPV]) was computed for both the QUANTEC constraints and Ortholan et al. recommendation to constrain the total volume of both glands receiving more than 40 Gy to less than 33%. Results: Both datasets showed a rate of xerostomia of less than 20% when the mean dose to the least-irradiated parotid gland is kept to less than 20 Gy. Logistic model parameters for the incidence of xerostomia at 12 months after therapy, based on the least-irradiated gland, were D{sub 50} = 32.4 Gy and and {gamma} = 0.97. NPVs for QUANTEC guideline were 94% (BCCA data), and 90% (WUSTL data). For Ortholan et al. guideline NPVs were 85% (BCCA) and 86% (WUSTL). Conclusion: These data confirm that the QUANTEC guideline effectively avoids xerostomia, and this is somewhat more effective than constraints on the volume receiving more than 40 Gy.

  16. Corrective Action Investigation Plan for Corrective Action Unit 543: Liquid Disposal Units Nevada Test Site, Nevada, Rev. No.: 0 with ROTC 1 and 2

    SciTech Connect (OSTI)

    David A. Strand

    2004-05-01

    This Corrective Action Investigation Plan (CAIP) contains project-specific information including facility descriptions, environmental sample collection objectives, and criteria for conducting site investigation activities at Corrective Action Unit (CAU) 543: Liquid Disposal Units, Nevada Test Site (NTS), Nevada. This CAIP has been developed in accordance with the ''Federal Facility Agreement and Consent Order'' (FFACO) (1996) that was agreed to by the State of Nevada, the U.S. Department of Energy (DOE), and the U.S Department of Defense (DoD). Corrective Action Unit 543 is located in Area 6 and Area 15 of the NTS, which is approximately 65 miles (mi) northwest of Las Vegas, Nevada (Figure 1-1). Seven corrective action sites (CASs) comprise CAU 543 and are listed below: (1) 06-07-01, Decon Pad; (2) 15-01-03, Aboveground Storage Tank; (3) 15-04-01, Septic Tank; (4) 15-05-01, Leachfield; (5) 15-08-01, Liquid Manure Tank; (6) 15-23-01, Underground Radioactive Material Area; and (7) 15-23-03, Contaminated Sump, Piping. Corrective Action Site 06-07-01, Decon Pad, is located in Area 6 and consists of the Area 6 Decontamination Facility and its components that are associated with decontamination of equipment, vehicles, and materials related to nuclear testing. The six CASs in Area 15 are located at the U.S. Environmental Protection Agency (EPA) Farm and are related to waste disposal activities at the EPA Farm. The EPA Farm was a fully-functional dairy associated with animal experiments conducted at the on-site laboratory. The corrective action investigation (CAI) will include field inspections, video-mole surveys, and sampling of media, where appropriate. Data will also be obtained to support waste management decisions. The CASs within CAU 543 are being investigated because hazardous and/or radioactive constituents may be present at concentrations that could potentially pose a threat to human health and the environment. The seven CASs in CAU 543 primarily consist of sanitary and process waste collection, storage, and distribution systems (e.g., storage tanks, sumps, and piping). Existing information on the nature and extent of potential contamination at these sites is insufficient to evaluate and recommend corrective action alternatives for the CASs. Therefore, additional information will be obtained by conducting a CAI prior to evaluating corrective action alternatives and selecting the appropriate corrective action for each CAS.

  17. UNCW Pre-Law Information Unlike some other graduate programs, there is no set major that leads to acceptance by law schools.

    E-Print Network [OSTI]

    Olszewski Jr., Edward A.

    that leads to acceptance by law schools. Acceptance is usually based on the Law School Admission Test (LSAT rounded college years, being part of campus groups and showing a willingness to volunteer in the local

  18. Testing Documentation Create-A-Page

    E-Print Network [OSTI]

    Wolfgang, Paul

    /1/2009 This document defines the methods for testing Create-A-Page, as well as the results of those tests that other end users need to be aware of before release. The order of the acceptance tests is important as an admin. For reference later in the document, each test will be listed separately, and all the acceptance

  19. Engineering testing and technology projects FY 1996 Site Support Program Plan, WBS 6.3.3 and 6.3.8. Revision 1

    SciTech Connect (OSTI)

    Brown, L.C.

    1995-10-01

    The engineering laboratory services for development, assembly, testing, and evaluation to support the resolution of WHC, Hanford, and DOE complex wide engineering issues for 1996 are presented. Primary customers are: TWRS, spent nuclear fuels, transition projects, liquid effluent program, and other Hanford contractors and programs. Products and services provided include: fabrication and assembly facilities for prototype and test equipment, development testing, proof of principle testing, instrumentation testing, nondestructive examination application development and testing, prototype equipment design and assembly, chemical engineering unit operations testing, engineering test system disposal, and safety issue resolution.

  20. NETL Center Completes Site Acceptance Test for IGCC Dynamic Simulator

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Fuel Injector 9 Review Published of In-Situ Electromagnetic Techniques for Oil Shale Processing 10 New Book Published on Computational...

  1. USER ACCEPTANCE TESTING OF MOBILE PAYMENT IN VARIOUS SCENARIOS

    E-Print Network [OSTI]

    Fong, Chi Chiu "Simon"

    of mobile devices has already exceeded the number of personal computers. Contradictorily, the commerce conducted via the mobile devices ("M-Commerce") is far less than that of internet ("E-Commerce"). This paper, or the mobile devices limited its capability to develop further? What is the reason or limitation? This makes

  2. Standard-E hydrogen monitoring system shop acceptance test procedure

    SciTech Connect (OSTI)

    Schneider, T.C.

    1997-10-02

    The purpose of this report is to document that the Standard-E Hydrogen Monitoring Systems (SHMS-E), fabricated by Mid-Columbia Engineering (MCE) for installation on the Waste Tank Farms in the Hanford 200 Areas, are constructed as intended by the design. The ATP performance will verify proper system fabrication.

  3. Testing Monotonicity Oded Goldreich

    E-Print Network [OSTI]

    Goldreich, Oded

    to query an unknown function f : {0, 1}n {0, 1} at arguments of its choice, the test always accepts of the function to any monotone function. 1.1 Perspective Property Testing, as explicitly defined by Rubinfeld), and that such tests can be defined and performed also for other error-correcting codes such as the Hadamard code [ALM

  4. SOFTWARE TESTING Tester's Job

    E-Print Network [OSTI]

    Kundu, Sukhamay

    allows multiple different acceptable outputs for some inputs. #12;8.4 BLACK-BOX TESTING · Based a requirement of category 5 w.r.t this test case. #define WORDLEN 20 void WordCharCounts(FILE *inFile) { int iSOFTWARE TESTING Tester's Job: · Find as many faults of different kinds as he can. · Certify some

  5. Streamlined Approach for Environmental Restoration (SAFER) Plan for Corrective Action Unit 539: Area 25 and Area 26 Railroad Tracks, Nevada Test Site, Nevada, Revision 0

    SciTech Connect (OSTI)

    Mark Krauss

    2010-06-01

    This Streamlined Approach for Environmental Restoration (SAFER) Plan addresses the actions needed to achieve closure for Corrective Action Unit (CAU) 539, Areas 25 and 26 Railroad Tracks, as identified in the Federal Facility Agreement and Consent Order (FFACO). A modification to the FFACOwas approved in May 2010 to transfer the two Railroad Tracks corrective action sites (CASs) from CAU 114 into CAU539. The two CASs are located in Areas 25 and 26 of the Nevada Test Site: • 25-99-21, Area 25 Railroad Tracks • 26-99-05, Area 26 Railroad Tracks This plan provides the methodology for field activities needed to gather the necessary information for closing the two CASs. There is sufficient information and process knowledge from historical documentation and investigations of similar sites regarding the expected nature and extent of potential contaminants to recommend closure of the CAU 539 Railroad Tracks CASs using the SAFER process. Additional information will be obtained by conducting a field investigation before selecting the appropriate corrective action for each CAS. The results of the field investigation should support a defensible recommendation that no further corrective action is necessary. If it is determined that complete clean closure cannot be accomplished during the SAFER, then a hold point will have been reached and the Nevada Division of Environmental Protection (NDEP) will be consulted to determine whether the remaining contamination will be closed under the alternative corrective action of closure in place with use restrictions. This will be presented in a closure report that will be prepared and submitted to the NDEP for review and approval. The sites will be investigated based on the data quality objectives (DQOs) developed on December 14, 2009, by representatives of U.S.Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office; Navarro Nevada Environmental Services, LLC (NNES); and National Security Technologies, LLC. The DQO process has been used to identify and define the type, amount, and quality of data needed to determine and implement appropriate corrective actions for each Railroad Tracks CAS in CAU 539. The following text summarizes the SAFER activities that will support the closure of CAU 539: • Perform site preparation activities (e.g., utilities clearances, radiological surveys). • Collect in situ dose measurements. • Collect environmental samples from designated target populations (e.g., lead bricks) to confirm or disprove the presence of contaminants of concern (COCs) as necessary to supplement existing information. • If no COCs are present at a CAS, establish no further action as the corrective action. • If COCs exist, collect environmental samples from designated target populations (e.g., clean soil adjacent to contaminated soil) and submit for laboratory analyses to define the extent of COC contamination. If a COC is present at a CAS, NNES will consult NDEP to determine the path forward, then either: • Establish clean closure as the corrective action. The material to be remediated will be removed, disposed of as waste, and verification samples will be collected from remaining soil, or • Establish closure in place as the corrective action and implement the appropriate use restrictions.

  6. Streamlined Approach for Environmental Restoration (SAFER) Plan for Corrective Action Unit 114: Area 25 EMAD Facility Nevada Test Site, Nevada, Revision 0

    SciTech Connect (OSTI)

    Mark Burmeister

    2009-08-01

    This Streamlined Approach for Environmental Restoration (SAFER) Plan addresses the actions needed to achieve closure for Corrective Action Unit (CAU) 114, Area 25 EMAD Facility, identified in the Federal Facility Agreement and Consent Order (FFACO). Corrective Action Unit 114 comprises the following corrective action sites (CASs) located in Area 25 of the Nevada Test Site: • 25-41-03, EMAD Facility • 25-99-20, EMAD Facility Exterior Releases This plan provides the methodology for field activities needed to gather the necessary information for closing each CAS. There is sufficient information and process knowledge from historical documentation and investigations of similar sites regarding the expected nature and extent of potential contaminants to recommend closure of CAU 114 using the SAFER process. Additional information will be obtained by conducting a field investigation before selecting the appropriate corrective action for each CAS. It is anticipated that the results of the field investigation and implementation of a corrective action of clean closure will support a defensible recommendation that no further corrective action is necessary. If it is determined that complete clean closure cannot be accomplished during the SAFER, then a hold point will have been reached and the Nevada Division of Environmental Protection (NDEP) will be consulted to determine whether the remaining contamination will be closed under the alternative corrective action of closure in place. This will be presented in a closure report that will be prepared and submitted to NDEP for review and approval. The sites will be investigated based on the data quality objectives (DQOs) developed on April 30, 2009, by representatives of NDEP; U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office; Stoller-Navarro Joint Venture; and National Security Technologies, LLC. The DQO process was used to identify and define the type, amount, and quality of data needed to determine and implement appropriate corrective actions for each CAS in CAU 114. The following text summarizes the SAFER activities that will support the closure of CAU 114: • Perform site preparation activities (e.g., utilities clearances, radiological surveys). • Collect environmental samples from designated target populations (e.g., stained soil) to confirm or disprove the presence of contaminants of concern (COCs) as necessary to supplement existing information. • Collect samples of materials to determine whether potential source material (PSM) is present that may cause the future release of a COC to environmental media. • If no COCs or PSMs are present at a CAS, establish no further action as the corrective action. • If COCs exist, collect environmental samples from designated target populations (e.g., clean soil adjacent to contaminated soil) and submit for laboratory analyses to define the extent of COC contamination. • If a COC or PSM is present at a CAS, either: - Establish clean closure as the corrective action. The material to be remediated will be removed, disposed of as waste, and verification samples will be collected from remaining soil, or - Establish closure in place as the corrective action and implement the appropriate use restrictions. • Confirm the selected closure option is sufficient to protect human health and the environment.

  7. Lagoon Seepage Testing Procedures for Central Facilities Area (CFA) Sewage Lagoons at Idaho National Laboratory Butte County, Idaho April 2014

    SciTech Connect (OSTI)

    Alan Giesbrecht

    2014-05-01

    The lagoon seepage testing procedures are documented herein as required by the Wastewater Rules (IDAPA 58.01.16.493). The Wastewater Rules and Wastewater Reuse Permit LA-000141-03 require that the procedure used for performing a seepage test be approved by IDEQ prior to conducting the seepage test. The procedures described herein are based on a seepage testing plan that was developed by J-U-B ENGINEERS, Inc. (J-U-B) and has been accepted by several IDEQ offices for lagoons in Idaho.

  8. Task Plans

    Office of Environmental Management (EM)

    Task Plans This page contains links to a tentative listing of active and closed TEC Task Plans. Final status of these task plans will be determined after the July 2000 TEC meeting....

  9. Central Characterization Program (CCP), Acceptable Knowledge...

    Office of Environmental Management (EM)

    for Los Alamos National Laboratory, TA-55 Mixed Transuranic Waste Streams Central Characterization Program (CCP), Acceptable Knowledge Summary Report for Los Alamos National...

  10. Sample Acceptance Letter Ready Reference F-10

    E-Print Network [OSTI]

    Sample Acceptance Letter Ready Reference F-10 College of Engineering, Architecture & Technology Career Services Oklahoma State University College of College of Engineering, Architecture & Technology

  11. FBI officer accepts LANL counterintelligence post

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    LANL counterintelligence FBI officer accepts LANL counterintelligence post Cloyd has most recently served as assistant director of the Counterintelligence Division of the Federal...

  12. Nuclear Engineering Science Laboratory Synthesis program accepting...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Nuclear Engineering Science Laboratory Synthesis program accepting applications for spring, summer 2016 Opportunity provides students with research experience at Oak Ridge National...

  13. EV Everywhere Consumer Acceptance and Charging Infrastructure...

    Broader source: Energy.gov (indexed) [DOE]

    Backsplash for the EV Everywhere Grand Challenge: Consumer Acceptance and Charging Infrastructure Workshop on July 30, 2012 held at the LAX Marriott, Los Angeles, CA...

  14. EV Everywhere Consumer Acceptance and Charging Infrastructure...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    E Breakout Report EV Everywhere Consumer Acceptance and Charging Infrastructure Workshop: Charging Infrastructure Group E Breakout Report Breakout session presentation for the EV...

  15. Nevada National Security Site Waste Acceptance Criteria

    National Nuclear Security Administration (NNSA)

    Nevada National Security Site Waste Acceptance Criteria Prepared by U.S. Department of Energy National Nuclear Security Administration Nevada Field Office Environmental...

  16. Corrective Action Investigation Plan for Corrective Action Unit 490: Station 44 Burn Area, Tonopah Test Range, Nevada (with Record of Technical Change No.1)

    SciTech Connect (OSTI)

    U.S. Department of Energy, Nevada Operations Office

    2000-06-09

    This Corrective Action Investigation Plan (CAIP) contains the U.S. Department of Energy, Nevada Operations Office's approach to collect the data necessary to evaluate corrective action alternatives appropriate for the closure of Corrective Action Unit (CAU) 490 under the Federal Facility Agreement and Consent Order. Corrective Active Unit 490 consists of four Corrective Action Sites (CASs): 03-56-001-03BA, Fire Training Area (FTA); RG-56-001-RGBA, Station 44 Burn Area; 03-58-001-03FN, Sandia Service Yard; and 09-54-001-09L2, Gun Propellant Burn Area. These CASs are located at the Tonopah Test Range near Areas 3 and 9. Historically, the FTA was used for training exercises where tires and wood were ignited with diesel fuel. Records indicate that water and carbon dioxide were the only extinguishing agents used during these training exercises. The Station 44 Burn Area was used for fire training exercises and consisted of two wooden structures. The two burn areas (ignition of tires, wood, and wooden structures with diesel fuel and water) were limited to the building footprints (10 ft by 10 ft each). The Sandia Service Yard was used for storage (i.e., wood, tires, metal, electronic and office equipment, construction debris, and drums of oil/grease) from approximately 1979 to 1993. The Gun Propellant Burn Area was used from the 1960s to 1980s to burn excess artillery gun propellant, solid-fuel rocket motors, black powder, and deteriorated explosives; additionally, the area was used for the disposal of experimental explosive items. Based on site history, the focus of the field investigation activities will be to: (1) determine the presence of contaminants of potential concern (COPCs) at each CAS, (2) determine if any COPCs exceed field-screening levels and/or preliminary action levels, and (3) determine the nature and extent of contamination with enough certainty to support selection of corrective action alternatives for each CAS. The scope of this CAIP is to resolve the question of whether or not potentially hazardous wastes were generated at three of the four CASs within CAU 490, and whether or not potentially hazardous and radioactive wastes were generated at the fourth CAS in CAU 490 (CAS 09-54-001-09L2). Suspected CAS-specific COPCs include volatile organic compounds, semivolatile organic compounds, total petroleum hydrocarbons, polychlorinated biphenyls, pesticides, explosives, and uranium and plutonium isotopes. The results of this field investigation will support a defensible evaluation of corrective action alternatives in the corrective action decision document.

  17. Accepted for the CASCON 2006: Dublin Symposium Dublin, Ireland, October 17, 2006

    E-Print Network [OSTI]

    Power, James

    and unit-testing classes in turn. We aug- ment this approach by using Object Relation Diagrams to define used them to define an order for inter-class testing, and we extend this to test-driven porting. OneAccepted for the CASCON 2006: Dublin Symposium Dublin, Ireland, October 17, 2006 Ensuring

  18. Los Alamos National Laboratory transuranic waste quality assurance project plan. Revision 1

    SciTech Connect (OSTI)

    NONE

    1997-04-14

    This Transuranic (TRU) Waste Quality Assurance Project Plan (QAPjP) serves as the quality management plan for the characterization of transuranic waste in preparation for certification and transportation. The Transuranic Waste Characterization/Certification Program (TWCP) consists of personnel who sample and analyze waste, validate and report data; and provide project management, quality assurance, audit and assessment, and records management support, all in accordance with established requirements for disposal of TRU waste at the Waste Isolation Pilot Plant (WIPP) facility. This QAPjP addresses how the TWCP meets the quality requirements of the Carlsbad Area Office (CAO) Quality Assurance Program Description (QAPD) and the technical requirements of the Transuranic Waste Characterization Quality Assurance Program Plan (QAPP). The TWCP characterizes and certifies retrievably stored and newly generated TRU waste using the waste selection, testing, sampling, and analytical techniques and data quality objectives (DQOs) described in the QAPP, the Los Alamos National Laboratory Transuranic Waste Certification Plan (Certification Plan), and the CST Waste Management Facilities Waste Acceptance Criteria and Certification [Los Alamos National Laboratory (LANL) Waste Acceptance Criteria (WAC)]. At the present, the TWCP does not address remote-handled (RH) waste.

  19. GAP TESTS; COMPARISON BETWEEN UN GAP TEST AND CARD GAP TEST

    E-Print Network [OSTI]

    Paris-Sud XI, Université de

    98-36 GAP TESTS; COMPARISON BETWEEN UN GAP TEST AND CARD GAP TEST by R. BRANKA and C. MICHOT, FRANCE (tel.: 33 3 44 55 65 19, fax: 33 3 44 55 65 10) ABSTRACT: UN gap test, type 1(a) or 2(a), is the recommended test in the acceptance procedure for transport of explosives in class 1. Up to the revision

  20. Final closure plan for the high-explosives open burn treatment facility at Lawrence Livermore National Laboratory Experimental Test Site 300

    SciTech Connect (OSTI)

    Mathews, S.

    1997-04-01

    This document addresses the interim status closure of the HE Open Bum Treatment Facility, as detailed by Title 22, Division 4.5, Chapter 15, Article 7 of the Califonia Code of Regulations (CCR) and by Title 40, Code of Federal Regulations (CFR) Part 265, Subpart G, ``Closure and Post Closure.`` The Closure Plan (Chapter 1) and the Post- Closure Plan (Chapter 2) address the concept of long-term hazard elimination. The Closure Plan provides for capping and grading the HE Open Bum Treatment Facility and revegetating the immediate area in accordance with applicable requirements. The Closure Plan also reflects careful consideration of site location and topography, geologic and hydrologic factors, climate, cover characteristics, type and amount of wastes, and the potential for contaminant migration. The Post-Closure Plan is designed to allow LLNL to monitor the movement, if any, of pollutants from the treatment area. In addition, quarterly inspections will ensure that all surfaces of the closed facility, including the cover and diversion ditches, remain in good repair, thus precluding the potential for contaminant migration.

  1. Standardization of DOE Disposal Facilities Waste Acceptance Processes

    SciTech Connect (OSTI)

    Shrader, T. A.; Macbeth, P. J.

    2002-02-26

    On February 25, 2000, the U.S. Department of Energy (DOE) issued the Record of Decision (ROD) for the Waste Management Programmatic Environmental Impact Statement (WM PEIS) for low-level and mixed low-level wastes (LLW/ MLLW) treatment and disposal. The ROD designated the disposal sites at Hanford and the Nevada Test Site (NTS) to dispose of LLW/MLLW from sites without their own disposal facilities. DOE's Richland Operations Office (RL) and the National Nuclear Security Administration's Nevada Operations Office (NV) have been charged with effectively implementing the ROD. To accomplish this task NV and RL, assisted by their operating contractors Bechtel Nevada (BN), Fluor Hanford (FH), and Bechtel Hanford (BH) assembled a task team to systematically map out and evaluate the current waste acceptance processes and develop an integrated, standardized process for the acceptance of LLW/MLLW. A structured, systematic, analytical process using the Six Sigma system identified dispos al process improvements and quantified the associated efficiency gains to guide changes to be implemented. The review concluded that a unified and integrated Hanford/NTS Waste Acceptance Process would be a benefit to the DOE Complex, particularly the waste generators. The Six Sigma review developed quantitative metrics to address waste acceptance process efficiency improvements, and provides an initial look at development of comparable waste disposal cost models between the two disposal sites to allow quantification of the proposed improvements.

  2. Standardization of DOE Disposal Facilities Waste Acceptance Process

    SciTech Connect (OSTI)

    SHRADER, T.; MACBETH, P.

    2002-01-01

    On February 25, 2000, the US. Department of Energy (DOE) issued the Record of Decision (ROD) for the Waste Management Programmatic Environmental Impact Statement (WM PEIS) for low-level and mixed low-level wastes (LLW/ MLLW) treatment and disposal. The ROD designated the disposal sites at Hanford and the Nevada Test Site (NTS) to dispose of LLWMLLW from sites without their own disposal facilities. DOE's Richland Operations Office (RL) and the National Nuclear Security Administration's Nevada Operations Office (NV) have been charged with effectively implementing the ROD. To accomplish this task NV and RL, assisted by their operating contractors Bechtel Nevada (BN), Fluor Hanford (FH), and Bechtel Hanford (BH) assembled a task team to systematically map out and evaluate the current waste acceptance processes and develop an integrated, standardized process for the acceptance of LLWMLLW. A structured, systematic, analytical process using the Six Sigma system identified disposal process improvements and quantified the associated efficiency gains to guide changes to be implemented. The review concluded that a unified and integrated Hanford/NTS Waste Acceptance Process would be a benefit to the DOE Complex, particularly the waste generators. The Six Sigma review developed quantitative metrics to address waste acceptance process efficiency improvements, and provides an initial look at development of comparable waste disposal cost models between the two disposal sites to allow quantification of the proposed improvements.

  3. TENDER AND ACCEPTANCE FORM STIPULATED PRICE CONTRACT

    E-Print Network [OSTI]

    deYoung, Brad

    TENDER AND ACCEPTANCE FORM FOR STIPULATED PRICE CONTRACT June 2013 #12;Stipulated Price Contract with that of all Subcontractors working on the Project. (See Appendix "D" for sample schedule that must be submitted within 10 days #12;Stipulated Price Contract Tender and Acceptance Form Page 2 of contract award

  4. Unit Testing for Casl Architectural Specifications

    E-Print Network [OSTI]

    Sannella, Don

    and impractical activity. When only finite sets of interactions are considered, successful testing can accept Unit Testing for Casl Architectural Specifications. The problem of testing modular systems against algebraic specifications is discussed. We focus on systems

  5. Property Testing: Theory and Applications Sofya Raskhodnikova

    E-Print Network [OSTI]

    Smith, Adam D.

    properties require (n) queries, even for adaptive tests. We show that testing properties defined by 2CNFProperty Testing: Theory and Applications by Sofya Raskhodnikova Submitted to the Department. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Michael Sipser Professor of Mathematics Thesis Supervisor Accepted

  6. Property Testing: Theory and Applications Sofya Raskhodnikova

    E-Print Network [OSTI]

    Smith, Adam D.

    properties require ## n) queries, even for adaptive tests. We show that testing properties defined by 2CNFProperty Testing: Theory and Applications by Sofya Raskhodnikova Submitted to the Department by . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Michael Sipser Professor of Mathematics Thesis Supervisor Accepted

  7. Streamlined Approach for Environmental Restoration (SAFER) Plan for Corrective Action Unit 544: Cellars, Mud Pits, and Oil Spills, Nevada Test Site, Nevada, Revision 0

    SciTech Connect (OSTI)

    Mark Krauss

    2010-07-01

    This Streamlined Approach for Environmental Restoration (SAFER) Plan addresses the actions needed to achieve closure for Corrective Action Unit (CAU) 544, Cellars, Mud Pits, and Oil Spills, identified in the Federal Facility Agreement and Consent Order (FFACO). Corrective Action Unit 544 comprises the following 20 corrective action sites (CASs) located in Areas 2, 7, 9, 10, 12, 19, and 20 of the Nevada Test Site (NTS): • 02-37-08, Cellar & Mud Pit • 02-37-09, Cellar & Mud Pit • 07-09-01, Mud Pit • 09-09-46, U-9itsx20 PS #1A Mud Pit • 10-09-01, Mud Pit • 12-09-03, Mud Pit • 19-09-01, Mud Pits (2) • 19-09-03, Mud Pit • 19-09-04, Mud Pit • 19-25-01, Oil Spill • 19-99-06, Waste Spill • 20-09-01, Mud Pits (2) • 20-09-02, Mud Pit • 20-09-03, Mud Pit • 20-09-04, Mud Pits (2) • 20-09-06, Mud Pit • 20-09-07, Mud Pit • 20-09-10, Mud Pit • 20-25-04, Oil Spills • 20-25-05, Oil Spills This plan provides the methodology for field activities needed to gather the necessary information for closing each CAS. There is sufficient information and process knowledge from historical documentation and investigations of similar sites regarding the expected nature and extent of potential contaminants to recommend closure of CAU 544 using the SAFER process. Using the approach approved for previous mud pit investigations (CAUs 530–535), 14 mud pits have been identified that • are either a single mud pit or a system of mud pits, • are not located in a radiologically posted area, and • have no evident biasing factors based on visual inspections. These 14 mud pits are recommended for no further action (NFA), and further field investigations will not be conducted. For the sites that do not meet the previously approved closure criteria, additional information will be obtained by conducting a field investigation before selecting the appropriate corrective action for each CAS. The results of the field investigation will support a defensible recommendation for closure of the remaining CASs in CAU 544. This will be presented in a closure report (CR) that will be prepared and submitted to the Nevada Division of Environmental Protection (NDEP) for review and approval. The sites will be investigated based on the data quality objectives (DQOs) developed on April 27, 2010, by representatives of NDEP and the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office (NNSA/NSO). The DQO process was used to identify and define the type, amount, and quality of data needed to determine and implement appropriate corrective actions for each CAS in CAU 544. The DQO process developed for this CAU identified the following expected closure options: (1) investigation and confirmation that no contamination exists above the final action levels (FALs) leading to an NFA declaration, (2) characterization of the nature and extent of contamination leading to closure in place with use restrictions, (3) clean closure by remediation and verification, (4) closure in place with use restrictions with no investigation if CASs are in crater areas that have been determined to be unsafe to enter, or (5) NFA if the mud pit CAS meets the criteria established during the CAUs 530–535 SAFER investigation. The following summarizes the SAFER activities that will support the closure of CAU 544: • Perform visual inspection of all CASs. • Perform site preparation activities (e.g., utilities clearances, construction of temporary site exclusion zones). • Removal of easily managed, nonhazardous, and nonradioactive debris, including vegetation (e.g., tumbleweeds), at various CASs that interfere with sampling, if required to inspect soil surface or collect soil sample. • Collect environmental samples from designated target populations (e.g., mud pits, cellars, stained soil) to confirm or disprove the presence of contaminants of concern (COCs) as necessary to supplement existing information. • If no COCs are present at a CAS, establish NFA as the corrective action. • If COCs exist, collect environmental samples f

  8. SU-E-T-28: A Treatment Planning Comparison of Volumetric Modulated Arc Therapy Vs. Proton Therapy for Post-Mastectomy Radiotherapy

    SciTech Connect (OSTI)

    Hernandez, M; Zhang, R; Sanders, M; Newhauser, W

    2014-06-01

    Purpose: The delivery of post-mastectomy radiotherapy (PMRT) can be challenging for patients with left-sided breast cancer due to the PTV size and proximity to critical organs. This study investigates the use of protons for PMRT in a clinically-representative cohort of patients, and quantitatively compares volumetric modulated arc therapy (VMAT) to proton therapy to have an evidence-based rationale for selecting a treatment modality for these patients. Methods: Eight left-sided PMRT patients previously treated at our clinic with VMAT were identified for the study. PTVs included the chest wall and regional lymph nodes. Passively scattered (PS) and intensity modulated proton therapy (IMPT) plans were constructed using the Eclipse proton planning system. The resulting plans were compared to the original VMAT plan on the basis of PTV coverage; dose homogeneity index (DHI) and conformity index (CI); dose to organs at risk (OAR); tumor control probability (TCP), normal tissue complication probability (NTCP) and secondary cancer complication probability (SCCP). Differences were tested for significance using the paired Student's t-test (p<0.01). Results: All modalities produced clinically acceptable PMRT plans. The comparison demonstrated proton treatment plans provide significantly lower NTCP values for the heart and the lung while maintaining significantly better CI and DHI. At a prescribed dose of 50.4 Gy (RBE) in the PTV, the calculated mean NTCP value for the patients decreased from 1.3% to 0.05% for the whole heart (cardiac mortality) and from 3.8% to 1.1% for the lungs (radiation pneumonitis) for both proton therapy plans from VMAT plans. Both proton modalities showed a significantly lower SCCP for the contralateral breast compared to VMAT. Conclusion: All three plans (VMAT, PS, and IMPT) provide acceptable treatment plans for PMRT. However, proton therapy shows a significant advantage over VMAT with regards to sparing OARs and may be more advantageous for patients with unfavorable anatomy.

  9. STATE OF CALIFORNIA VALVE LEAKAGE TEST

    E-Print Network [OSTI]

    STATE OF CALIFORNIA VALVE LEAKAGE TEST CEC-MECH-8A (Revised 08/09) CALIFORNIA ENERGY COMMISSION CERTIFICATE OF ACCEPTANCE MECH-8A NA7.5.7 Valve Leakage Test (Page 1 of 3) Project Name/Address: System Name VALVE LEAKAGE TEST CEC-MECH-8A (Revised 08/09) CALIFORNIA ENERGY COMMISSION CERTIFICATE OF ACCEPTANCE

  10. Routine Radiological Environmental Monitoring Plan, Volume 2 Appendices

    SciTech Connect (OSTI)

    Bechtel Nevada

    1998-12-31

    Supporting material for the plan includes: QUALITY ASSURANCE, ANALYSIS, AND SAMPLING PLAN FOR NTS AIR; QUALITY ASSURANCE, ANALYSIS, AND SAMPLING PLAN FOR WATER ON AND OFF THE NEVADA TEST SITE; QUALITY ASSURANCE, ANALYSIS, AND SAMPLING PLAN FOR NTS BIOTA; QUALITY ASSURANCE, ANALYSIS, AND SAMPLING PLAN FOR DIRECT RADIATION MONITORING; DATA QUALITY OBJECTIVES PROCESS; VADOSE ZONE MONITORING PLAN CHECKLIST.

  11. Approaches to acceptable risk: a critical guide

    SciTech Connect (OSTI)

    Fischhoff, B.; Lichtenstein, S.; Slovic, P.; Keeney, R.; Derby, S.

    1980-12-01

    Acceptable-risk decisions are an essential step in the management of technological hazards. In many situations, they constitute the weak (or missing) link in the management process. The absence of an adequate decision-making methodology often produces indecision, inconsistency, and dissatisfaction. The result is neither good for hazard management nor good for society. This report offers a critical analysis of the viability of various approaches as guides to acceptable-risk decisions. This report seeks to define acceptable-risk decisions and to examine some frequently proposed, but inappropriate, solutions. 255 refs., 22 figs., 25 tabs.

  12. Hanford Site Solid Waste Acceptance Criteria

    SciTech Connect (OSTI)

    Not Available

    1993-11-17

    This manual defines the Hanford Site radioactive, hazardous, and sanitary solid waste acceptance criteria. Criteria in the manual represent a guide for meeting state and federal regulations; DOE Orders; Hanford Site requirements; and other rules, regulations, guidelines, and standards as they apply to acceptance of radioactive and hazardous solid waste at the Hanford Site. It is not the intent of this manual to be all inclusive of the regulations; rather, it is intended that the manual provide the waste generator with only the requirements that waste must meet in order to be accepted at Hanford Site TSD facilities.

  13. 2013 Annual Planning Summary for the National Energy Technology...

    Office of Environmental Management (EM)

    for the New Brunswick Laboratory 2013 Annual Planning Summary for the Rocky Mountain Oilfield Testing Center 2013 Annual Planning Summary for the Strategic Petroleum Reserve...

  14. Test Plan for Lockheed Idaho Technologies Company (LITCO), ARROW-PAK Packaging, Docket 95-40-7A, Type A Container

    SciTech Connect (OSTI)

    Kelly, D.L.

    1995-10-23

    This report documents the U.S. Department of Transportation Specification 7A Type A (DOT-7A) compliance testing to be followed for qualification of the Lockheed Idaho Technologies Company, ARROW-PAK, for use as a Type A Packaging. The packaging configuration being tested is intended for transportation of radioactive solids, Form No. 1, Form No. 2, and Form No. 3.

  15. Investigation of Variables Associated with Vaccine Acceptance

    E-Print Network [OSTI]

    Black, Lora L.

    2011-12-31

    Abstract The current study investigated the relationship between the Health Belief Model (HBM) framework, social variables, personality factors, and H1N1 flu vaccine acceptance. Four hundred thirty two undergraduate students completed online...

  16. Corrective Action Investigation Plan for Corrective Action Unit 104: Area 7 Yucca Flat Atmospheric Test Sites, Nevada National Security Site, Nevada, Revision 0

    SciTech Connect (OSTI)

    Patrick Matthews

    2011-08-01

    CAU 104 comprises the 15 CASs listed below: (1) 07-23-03, Atmospheric Test Site T-7C; (2) 07-23-04, Atmospheric Test Site T7-1; (3) 07-23-05, Atmospheric Test Site; (4) 07-23-06, Atmospheric Test Site T7-5a; (5) 07-23-07, Atmospheric Test Site - Dog (T-S); (6) 07-23-08, Atmospheric Test Site - Baker (T-S); (7) 07-23-09, Atmospheric Test Site - Charlie (T-S); (8) 07-23-10, Atmospheric Test Site - Dixie; (9) 07-23-11, Atmospheric Test Site - Dixie; (10) 07-23-12, Atmospheric Test Site - Charlie (Bus); (11) 07-23-13, Atmospheric Test Site - Baker (Buster); (12) 07-23-14, Atmospheric Test Site - Ruth; (13) 07-23-15, Atmospheric Test Site T7-4; (14) 07-23-16, Atmospheric Test Site B7-b; (15) 07-23-17, Atmospheric Test Site - Climax These sites are being investigated because existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend corrective action alternatives (CAAs). Additional information will be obtained by conducting a corrective action investigation before evaluating CAAs and selecting the appropriate corrective action for each CAS. The results of the field investigation will support a defensible evaluation of viable CAAs that will be presented in the Corrective Action Decision Document. The sites will be investigated based on the data quality objectives (DQOs) developed on April 28, 2011, by representatives of the Nevada Division of Environmental Protection and the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office. The DQO process was used to identify and define the type, amount, and quality of data needed to develop and evaluate appropriate corrective actions for CAU 104. The releases at CAU 104 consist of surface-deposited radionuclides from 30 atmospheric nuclear tests. The presence and nature of contamination at CAU 104 will be evaluated based on information collected from a field investigation. Radiological contamination will be evaluated based on a comparison of the total effective dose (TED) to the dose-based final action level (FAL). The presence of TED exceeding the FAL is considered a radiological contaminant of concern (COC). Anything identified as a COC will require corrective action. The TED will be calculated as the total of separate estimates of internal and external dose. Results from the analysis of soil samples will be used to calculate internal radiological dose. Thermoluminescent dosimeters will be used to measure external radiological dose. Based on process knowledge of the releases associated with the nuclear tests and radiological survey information about the location and shape of the resulting contamination plume, it was determined that the releases from the nuclear tests are co-located and will be investigated concurrently. A field investigation will be performed to define areas where TED exceeds the FAL and to determine whether other COCs are present at the site. The investigation will also collect information to determine the presence and nature of contamination associated with migration and excavation, as well as any potential releases discovered during the investigation. Appendix A provides a detailed discussion of the DQO methodology and the DQOs specific to each CAS.

  17. Proactive Planning 

    E-Print Network [OSTI]

    Wythe, Kathy

    2008-01-01

    an opportunity to voice their opinions and help draft the watershed protection plan for the reservoir. The plan, which will outline ways to reduce pollution and improve water quality, is an outgrowth of years of water quality monitoring and research by TRWD... in stakeholder-based watershed protection planning focused on holistic solutions to water pollution by exam- ining the impacts of upstream activities. Watershed-based planning is a relatively new approach to pollution reduction in all sizes of water bodies...

  18. Urban climate resilience : a global assessment of city adaptation plans

    E-Print Network [OSTI]

    Katich, Kristina Noel

    2009-01-01

    As policy makers accept climate change as an irrefutable threat, adaptation planning has emerged as a necessary action for countries, states, and municipalities. This thesis explores adaptive responses to climate change ...

  19. Robust, goal-directed plan execution with bounded risk

    E-Print Network [OSTI]

    Ono, Masahiro, Ph. D. Massachusetts Institute of Technology

    2012-01-01

    There is an increasing need for robust optimal plan execution for multi-agent systems in uncertain environments, while guaranteeing an acceptable probability of success. For example, a fleet of unmanned aerial vehicles ...

  20. Documentation of acceptable knowledge for LANL Plutonium Facility transuranic waste streams

    SciTech Connect (OSTI)

    Montoya, A.J.; Gruetzmacher, K.; Foxx, C.; Rogers, P.S.Z.

    1998-07-01

    Characterization of transuranic waste from the LANL Plutonium Facility for certification and transportation to WIPP includes the use of acceptable knowledge as specified in the WIPP Quality Assurance Program Plan. In accordance with a site-specific procedure, documentation of acceptable knowledge for retrievably stored and currently generated transuranic waste streams is in progress at LANL. A summary overview of the transuranic waste inventory is complete and documented in the Sampling Plan. This document also includes projected waste generation, facility missions, waste generation processes, flow diagrams, times, and material inputs. The second part of acceptable knowledge documentation consists of assembling more detailed acceptable knowledge information into auditable records and is expected to require several years to complete. These records for each waste stream must support final assignment of waste matrix parameters, EPA hazardous waste numbers, and radionuclide characterization. They must also include a determination whether waste streams are defense waste streams for compliance with the WIPP Land Withdrawal Act. The LANL Plutonium Facility`s mission is primarily plutonium processing in basic special nuclear material (SNM) research activities to support national defense and energy programs. It currently has about 100 processes ranging from SNM recovery from residues to development of plutonium 238 heat sources for space applications. Its challenge is to characterize and certify waste streams from such diverse and dynamic operations using acceptable knowledge. This paper reports the progress on the certification of the first of these waste streams to the WIPP WAC.

  1. Documentation of acceptable knowledge for Los Alamos National Laboratory Plutonium Facility TRU waste stream

    SciTech Connect (OSTI)

    Montoya, A.J.; Gruetzmacher, K.M.; Foxx, C.L.; Rogers, P.Z.

    1998-03-01

    Characterization of transuranic waste from the LANL Plutonium Facility for certification and transportation to WIPP includes the use of acceptable knowledge as specified in the WIPP Quality Assurance Program Plan. In accordance with a site specific procedure, documentation of acceptable knowledge for retrievably stored and currently generated transuranic waste streams is in progress at LANL. A summary overview of the TRU waste inventory is complete and documented in the Sampling Plan. This document also includes projected waste generation, facility missions, waste generation processes, flow diagrams, times, and material inputs. The second part of acceptable knowledge documentation consists of assembling more detailed acceptable knowledge information into auditable records and is expected to require several years to complete. These records for each waste stream must support final assignment of waste matrix parameters, EPA hazardous waste numbers, and radionuclide characterization. They must also include a determination whether waste streams are defense waste streams for compliance with the WIPP Land Withdrawal Act. The LANL Plutonium Facility`s mission is primarily plutonium processing in basic special nuclear material (SNM) research activities to support national defense and energy programs. It currently has about 100 processes ranging from SNM recovery from residues to development of plutonium 238 heat sources for space applications. Its challenge is to characterize and certify waste streams from such diverse and dynamic operations using acceptable knowledge. This paper reports the progress on the certification of the first of these waste streams to the WIPP WAC.

  2. Integration of Nevada Test Site (NTS) Work Control Programs and Incorporating Integrated Safety Management (ISM) into Activity Level Work Planning and Control

    SciTech Connect (OSTI)

    Mike Kinney and Kevin Breen

    2008-08-30

    This session will examine a method developed by Federal and Contractor personnel at the Nevada Site Office (NSO) to improve the planning and execution of work activities utilizing an Activity Level Work Control process in response to Defense Nuclear Facilities Safety Board (DNFSB) Recommendation 2004-1, Oversight of Complex, High-Hazard Nuclear Operations. The process was initially developed during Fiscal Year (FY) 2007, and implementation is commencing during the fourth quarter of FY 2008. This process will significantly enhance the flexibility and the appropriate rigor in the performance of work activities.

  3. Corrective Action Decision Document/Corrective Action Plan for the 92-Acre Area and Corrective Action Unit 111: Area 5 WMD Retired Mixed Waste Pits, Nevada Test Site, Nevada

    SciTech Connect (OSTI)

    NSTec Environmental Restoration

    2009-07-31

    This Corrective Action Decision Document/Corrective Action Plan (CADD/CAP) has been prepared for the 92-Acre Area, the southeast quadrant of the Radioactive Waste Management Site, located in Area 5 of the Nevada Test Site (NTS). The 92-Acre Area includes Corrective Action Unit (CAU) 111, 'Area 5 WMD Retired Mixed Waste Pits.' Data Quality Objectives (DQOs) were developed for the 92-Acre Area, which includes CAU 111. The result of the DQO process was that the 92-Acre Area is sufficiently characterized to provide the input data necessary to evaluate corrective action alternatives (CAAs) without the collection of additional data. The DQOs are included as Appendix A of this document. This CADD/CAP identifies and provides the rationale for the recommended CAA for the 92-Acre Area, provides the plan for implementing the CAA, and details the post-closure plan. When approved, this CADD/CAP will supersede the existing Pit 3 (P03) Closure Plan, which was developed in accordance with Title 40 Code of Federal Regulations (CFR) Part 265, 'Interim Status Standards for Owners and Operators of Hazardous Waste Treatment, Storage, and Disposal Facilities.' This document will also serve as the Closure Plan and the Post-Closure Plan, which are required by 40 CFR 265, for the 92-Acre Area. After closure activities are complete, a request for the modification of the Resource Conservation and Recovery Act Permit that governs waste management activities at the NTS will be submitted to the Nevada Division of Environmental Protection to incorporate the requirements for post-closure monitoring. Four CAAs, ranging from No Further Action to Clean Closure, were evaluated for the 92-Acre Area. The CAAs were evaluated on technical merit focusing on performance, reliability, feasibility, safety, and cost. Based on the evaluation of the data used to develop the conceptual site model; a review of past, current, and future operations at the site; and the detailed and comparative analysis of the potential CAAs, Closure in Place with Administrative Controls is the preferred CAA for the 92-Acre Area. Closure activities will include the following: (1) Constructing an engineered evapotranspiration cover over the 92-Acre Area; (2) Installing use restriction (UR) warning signs, concrete monuments, and subsidence survey monuments; (3) Establishing vegetation on the cover; (4) Implementing a UR; and (5) Implementing post-closure inspections and monitoring. The Closure in Place with Administrative Controls alternative meets all requirements for the technical components evaluated, fulfills all applicable federal and state regulations for closure of the site, and will minimize potential future exposure pathways to the buried waste at the site.

  4. The MUSE Data Reduction Pipeline: Status after Preliminary Acceptance Europe

    E-Print Network [OSTI]

    Weilbacher, Peter M; Urrutia, Tanya; Pécontal-Rousset, Arlette; Jarno, Aurélien; Bacon, Roland

    2015-01-01

    MUSE, a giant integral field spectrograph, is about to become the newest facility instrument at the VLT. It will see first light in February 2014. Here, we summarize the properties of the instrument as built and outline functionality of the data reduction system, that transforms the raw data that gets recorded separately in 24 IFUs by 4k CCDs, into a fully calibrated, scientifically usable data cube. We then describe recent work regarding geometrical calibration of the instrument and testing of the processing pipeline, before concluding with results of the Preliminary Acceptance in Europe and an outlook to the on-sky commissioning.

  5. Test Automation Test Automation

    E-Print Network [OSTI]

    Mousavi, Mohammad

    Test Automation Test Automation Mohammad Mousavi Eindhoven University of Technology, The Netherlands Software Testing 2013 Mousavi: Test Automation #12;Test Automation Outline Test Automation Mousavi: Test Automation #12;Test Automation Why? Challenges of Manual Testing Test-case design: Choosing inputs

  6. Boston College Comprehensive Emergency Management Plan January 2014 BOSTON COLLEGE

    E-Print Network [OSTI]

    Huang, Jianyu

    9 Meetings 10 Plans Development and Maintenance 10 Plan Review, Testing, and Exercises 11 Training Additional Command Staff 19 Operations Staff 19 Logistics Staff 19 Planning Staff 20 Finance & Administration

  7. Improved Planning Time and Plan Quality Through Multicriteria Optimization for Intensity-Modulated Radiotherapy

    SciTech Connect (OSTI)

    Craft, David L.; Hong, Theodore S.; Shih, Helen A.; Bortfeld, Thomas R.

    2012-01-01

    Purpose: To test whether multicriteria optimization (MCO) can reduce treatment planning time and improve plan quality in intensity-modulated radiotherapy (IMRT). Methods and Materials: Ten IMRT patients (5 with glioblastoma and 5 with locally advanced pancreatic cancers) were logged during the standard treatment planning procedure currently in use at Massachusetts General Hospital (MGH). Planning durations and other relevant planning information were recorded. In parallel, the patients were planned using an MCO planning system, and similar planning time data were collected. The patients were treated with the standard plan, but each MCO plan was also approved by the physicians. Plans were then blindly reviewed 3 weeks after planning by the treating physician. Results: In all cases, the treatment planning time was vastly shorter for the MCO planning (average MCO treatment planning time was 12 min; average standard planning time was 135 min). The physician involvement time in the planning process increased from an average of 4.8 min for the standard process to 8.6 min for the MCO process. In all cases, the MCO plan was blindly identified as the superior plan. Conclusions: This provides the first concrete evidence that MCO-based planning is superior in terms of both planning efficiency and dose distribution quality compared with the current trial and error-based IMRT planning approach.

  8. Public Acceptability of Sustainable Transport Measures: A Review...

    Open Energy Info (EERE)

    Public Acceptability of Sustainable Transport Measures: A Review of the Literature Jump to: navigation, search Tool Summary LAUNCH TOOL Name: Public Acceptability of Sustainable...

  9. EV Everywhere Grand Challenge: Consumer Acceptance and Charging...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Agenda EV Everywhere Grand Challenge: Consumer Acceptance and Charging Infrastructure Workshop Agenda Agenda for the EV Everywhere Grand Challenge: Consumer Acceptance and Charging...

  10. Acceptance Priority Ranking & Annual Capacity Report

    SciTech Connect (OSTI)

    2004-07-31

    The Nuclear Waste Policy Act of 1982, as amended (the Act), assigns the Federal Government the responsibility for the disposal of spent nuclear fuel and high-level waste. Section 302(a) of the Act authorizes the Secretary to enter into contracts with the owners and generators of commercial spent nuclear fuel and/or high-level waste. The Standard Contract for Disposal of Spent Nuclear Fuel and/or High-Level Radioactive Waste (Standard Contract) established the contractual mechanism for the Department's acceptance and disposal of spent nuclear fuel and high-level waste. It includes the requirements and operational responsibilities of the parties to the Standard Contract in the areas of administrative matters, fees, terms of payment, waste acceptance criteria, and waste acceptance procedures. The Standard Contract provides for the acquisition of title to the spent nuclear fuel and/or high-level waste by the Department, its transportation to Federal facilities, and its subsequent disposal.

  11. SOFTWARE TESTING, VERIFICATION AND RELIABILITY Softw. Test. Verif. Reliab. (2014)

    E-Print Network [OSTI]

    2014-01-01

    June 2014; Accepted 8 August 2014 KEY WORDS: automated test case generation; function block diagram defined by the International Electrotechnical Commission (IEC). Industrial FBD testing relies mostly criteria defined by Jee et al. [1]. Given a unit FBD program, test requirements expressed in logical

  12. Accepted to International Journal of Internet Manufacturing and Services (Accepted Feb 11, 2009)

    E-Print Network [OSTI]

    California at Los Angeles, University of

    to manufacturers, suppliers, retailers, ant transportation carriers etc.). It is captured, processed, and exchangedAccepted to International Journal of Internet Manufacturing and Services (Accepted Feb 11, 2009) A Rule Language and Framework for RFID Data Capture and Processing in Manufacturing Enterprise System

  13. Functional Coverage Driven Test Generation for Validation of Pipelined Processors

    E-Print Network [OSTI]

    Mishra, Prabhat

    to define the functional coverage for pipelined architectures. Fi- nally, test generation procedures are presented that accept the graph model of the architecture as input and generate test pro- grams to detect of random or constrained-random test sequences. We have developed test generation procedures that accept

  14. Phase 2 Methyl Iodide Deep-Bed Adsorption Tests

    SciTech Connect (OSTI)

    Soelberg, Nick; Watson, Tony

    2014-09-01

    Nuclear fission produces fission products (FPs) and activation products, including iodine-129, which could evolve into used fuel reprocessing facility off-gas systems, and could require off-gas control to limit air emissions to levels within acceptable emission limits. Research, demonstrations, and some reprocessing plant experience have indicated that diatomic iodine can be captured with efficiencies high enough to meet regulatory requirements. Research on the capture of organic iodides has also been performed, but to a lesser extent. Several questions remain open regarding the capture of iodine bound in organic compounds. Deep-bed methyl iodide adsorption testing has progressed according to a multi-laboratory methyl iodide adsorption test plan. This report summarizes the second phase of methyl iodide adsorption work performed according to this test plan using the deep-bed iodine adsorption test system at the Idaho National Laboratory (INL), performed during the second half of Fiscal Year (FY) 2014. Test results continue to show that methyl iodide adsorption using AgZ can achieve total iodine decontamination factors (DFs, ratios of uncontrolled and controlled total iodine levels) above 1,000, until breakthrough occurred. However, mass transfer zone depths are deeper for methyl iodide adsorption compared to diatomic iodine (I2) adsorption. Methyl iodide DFs for the Ag Aerogel test adsorption efficiencies were less than 1,000, and the methyl iodide mass transfer zone depth exceeded 8 inches. Additional deep-bed testing and analyses are recommended to (a) expand the data base for methyl iodide adsorption under various conditions specified in the methyl iodide test plan, and (b) provide more data for evaluating organic iodide reactions and reaction byproducts for different potential adsorption conditions.

  15. Systematic Testing Henrik Brbak Christensen

    E-Print Network [OSTI]

    Christensen, Henrik Bærbak

    not enough. We need to define some commonly accepted measurable quantity that we can use as yardstick. To test the System.abs(int a) you could define a test case like Input: -37 Expected Output: +37 The notionSystematic Testing Henrik Bærbak Christensen Department of Computer Science University of Aarhus

  16. Nevada National Security Site Waste Acceptance Criteria

    SciTech Connect (OSTI)

    none,

    2013-06-01

    This document establishes the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Field Office (NNSA/NFO), Nevada National Security Site Waste Acceptance Criteria (NNSSWAC). The NNSSWAC provides the requirements, terms, and conditions under which the Nevada National Security Site (NNSS) will accept the following: • DOE hazardous and non-hazardous non-radioactive classified waste • DOE low-level radioactive waste (LLW) • DOE mixed low-level waste (MLLW) • U.S. Department of Defense (DOD) classified waste The LLW and MLLW listed above may also be classified waste. Classified waste is the only waste accepted for disposal that may be non-radioactive and shall be required to meet the waste acceptance criteria for radioactive waste as specified in this document. Classified waste may be sent to the NNSS as classified matter. Section 3.1.18 provides the requirements that must be met for permanent burial of classified matter. The NNSA/NFO and support contractors are available to assist the generator in understanding or interpreting this document. For assistance, please call the NNSA/NFO Environmental Management Operations (EMO) at (702) 295-7063, and the call will be directed to the appropriate contact.

  17. Nevada National Security Site Waste Acceptance Criteria

    SciTech Connect (OSTI)

    NSTec Environmental Management

    2012-02-28

    This document establishes the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office (NNSA/NSO), Nevada National Security Site Waste Acceptance Criteria (NNSSWAC). The NNSSWAC provides the requirements, terms, and conditions under which the Nevada National Security Site (NNSS) will accept DOE non-radioactive classified waste, DOE non-radioactive hazardous classified waste, DOE low-level radioactive waste (LLW), DOE mixed low-level waste (MLLW), and U.S. Department of Defense (DOD) classified waste for permanent disposal. Classified waste is the only waste accepted for disposal that may be non-radioactive and will be required to meet the waste acceptance criteria for radioactive waste as specified in this document. The NNSA/NSO and support contractors are available to assist you in understanding or interpreting this document. For assistance, please call the NNSA/NSO Waste Management Project (WMP) at (702) 295-7063, and your call will be directed to the appropriate contact.

  18. Undergraduate Accepted Salaries Rensselaer Polytechnic Institute

    E-Print Network [OSTI]

    Linhardt, Robert J.

    Undergraduate Accepted Salaries Rensselaer Polytechnic Institute Class of 2014 Overall Average Bachelor's Degree Salary--$66,467 Architecture Average Range Architecture $45,375 $37 Salaries (All Majors) Co-Terminal BS/MS/ME $72,188 $52,000--$113,000 MBA $67,045 $55,000--$90,500 MS/ME $72

  19. AVTA: Transit Vehicle Specifications and Test Procedures

    Broader source: Energy.gov [DOE]

    All Advanced Vehicle Testing Activity transit projects follow a rigorous data collection and analysis protocol. Refer to "General Evaluation Plan: Fleet Test and Evaluation Projects" for...

  20. POSTGRADUATE UAC OFFERS 2015 Acceptance and Enrolment Information

    E-Print Network [OSTI]

    Fleming, Andrew J.

    POSTGRADUATE UAC OFFERS 2015 Acceptance and Enrolment Information How do I accept my offer? When you receive a Universities Admissions Centre (UAC) offer to study at the University of Newcastle, you must first accept your offer online if you intend to enrol. To accept your offer you will need

  1. Corrective Action Investigation Plan for Corrective Action Unit 106: Areas 5, 11 Frenchman Flat Atmospheric Sites, Nevada Test Site, Nevada, Revision 0

    SciTech Connect (OSTI)

    Patrick Matthews

    2010-04-01

    Corrective Action Unit (CAU) 106 is located in Area 5 of the Nevada Test Site, which is approximately 65 miles northwest of Las Vegas, Nevada. Corrective Action Unit 106 comprises the five corrective action sites (CASs) listed below: •05-23-02, GMX Alpha Contaminated Area •05-23-05, Atmospheric Test Site - Able •05-45-01, Atmospheric Test Site - Hamilton •05-45-04, 306 GZ Rad Contaminated Area •05-45-05, 307 GZ Rad Contaminated Area These sites are being investigated because existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend corrective action alternatives (CAAs). Additional information will be obtained by conducting a corrective action investigation before evaluating CAAs and selecting the appropriate corrective action for each CAS. The results of the field investigation will support a defensible evaluation of viable CAAs that will be presented in the Corrective Action Decision Document. The sites will be investigated based on the data quality objectives (DQOs) developed on January 19, 2010, by representatives of the Nevada Division of Environmental Protection and the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Site Office. The DQO process was used to identify and define the type, amount, and quality of data needed to develop and evaluate appropriate corrective actions for CAU 106. The presence and nature of contamination at CAU 106 will be evaluated based on information collected from a field investigation. The CAU includes land areas impacted by the release of radionuclides from a weapons-effect tower test (CAS 05-45-01), a weapons-related airdrop test (CAS 05-23-05), “equation of state” experiments (CAS 05-23-02), and unknown support activities at two sites (CAS 05-45-04 and CAS 05-45-05). Surface-deposited radiological contamination will be evaluated based on a comparison of the total effective dose (TED) at sample plot locations to the dose-based final action level. The TED will be calculated as the total of separate estimates of internal and external doses. Results from the analysis of soil samples collected from sample plots will be used to calculate internal radiological dose. Thermoluminescent dosimeters placed at the center of each sample plot will be used to measure external radiological dose. The presence and nature of contamination from other types of releases (such as migration and excavation as well as any potential releases discovered during the investigation) will be evaluated using soil samples collected from the locations most likely containing contamination, if present. Appendix A provides a detailed discussion of the DQO methodology and the DQOs specific to each CAS. The scope of the corrective action investigation for CAU 106 includes the following activities: •Conduct radiological surveys. •Collect and submit environmental samples for laboratory analysis to determine internal dose rates and the presence of contaminants of concern. •If contaminants of concern are present, collect additional samples to define the extent of the contamination and determine the area where TED at the site exceeds final action levels (i.e., corrective action boundary). •Collect samples of investigation-derived waste, as needed, for waste management purposes.

  2. ISDSN Sensor System Phase One Test Report

    SciTech Connect (OSTI)

    Gail Heath

    2011-09-01

    This Phase 1 Test Report documents the test activities and results completed for the Idaho National Laboratory (INL) sensor systems that will be deployed in the meso-scale test bed (MSTB) at Florida International University (FIU), as outlined in the ISDSN-MSTB Test Plan. This report captures the sensor system configuration tested; test parameters, testing procedure, any noted changes from the implementation plan, acquired test data sets, and processed results.

  3. Building Registration Plans (Plan Ahead)

    E-Print Network [OSTI]

    Pavlov, Ronnie

    or edit plans you've already created. #12;Now enter your course search requirements. Then click the Search not be offered in the term you are creating. You can search by Subject, Course Number, Keyword, Title, Level to the Registration Screen, click on Plan Ahead. Next, you need to select the term for which you wish to create

  4. Rulison Monitoring Plan

    SciTech Connect (OSTI)

    2010-07-01

    The Project Rulison Monitoring Plan has been developed as part of the U.S. Department of Energy (DOE) Office of Legacy Management's mission to protect human health and the environment. The purpose of the plan is to monitor fluids from gas wells for radionuclides that would indicate contamination is migrating from the Rulison detonation zone to producing gas wells, allowing action to be taken before the contamination could pose a risk. The Monitoring Plan (1) lists the contaminants present and identifies those that have the greatest potential to migrate from the detonation zone (radionuclide source term), (2) identifies locations that monitor the most likely transport pathways, (3) identifies which fluids will be sampled (gas and liquid) and why, (4) establishes the frequency of sampling, and (5) specifies the most practical analyses and where the analysis results will be reported. The plan does not affect the long-term hydrologic sampling conducted by DOE since 1972, which will continue for the purpose of sampling shallow groundwater and surface water near the site. The Monitoring Plan was developed in anticipation of gas wells being drilled progressively nearer the Rulison site. DOE sampled 10 gas wells in 1997 and 2005 at distances ranging from 2.7 to 7.6 miles from the site to establish background concentrations for radionuclides. In a separate effort, gas industry operators and the Colorado Oil and Gas Conservation Commission (COGCC) developed an industry sampling and analysis plan that was implemented in 2007. The industry plan requires the sampling of gas wells within 3 miles of the site, with increased requirements for wells within 1 mile of the site. The DOE plan emphasizes the sampling of wells near the site (Figure 1), specifically those with a bottom-hole location of 1 mile or less from the detonation, depending on the direction relative to the natural fracture trend of the producing formation. Studies indicate that even the most mobile radionuclides created by the test are unlikely to migrate appreciable distances (hundreds of feet) from the detonation zone (Cooper et al. 2007, 2009). The Monitoring Plan was developed to provide a cautious and comprehensive approach for detecting any potential contaminant migration from the Rulison test site. It also provides an independent confirmation of results from the industry sampling and analysis plan while effectively increasing the sampling frequency of wells near the site.

  5. Plan for characterization of K Basin spent nuclear fuel and sludge

    SciTech Connect (OSTI)

    Lawrence, L.A.; Marschman, S.C.

    1995-06-01

    This plan outlines a characterization program that supports the accelerated Path Forward scope and schedules for the Spent Nuclear Fuel stored in the Hanford K Basins. This plan is driven by the schedule to begin fuel transfer by December 1997. The program is structured for 4 years and is limited to in-situ and laboratory examinations of the spent nuclear fuel and sludge in the K East and K West Basins. The program provides bounding behavior of the fuel, and verification and acceptability for three different sludge disposal pathways. Fuel examinations are based on two shipping campaigns for the K West Basin and one from the K East Basin. Laboratory examinations include physical condition, hydride and oxide content, conditioning testing, and dry storage behavior.

  6. Graphite Technology Development Plan

    SciTech Connect (OSTI)

    W. Windes; T. Burchell; M.Carroll

    2010-10-01

    The Next Generation Nuclear Plant (NGNP) will be a helium-cooled High Temperature Gas Reactor (HTGR) with a large graphite core. Graphite physically contains the fuel and comprises the majority of the core volume. Graphite has been used effectively as a structural and moderator material in both research and commercial high-temperature gas-cooled reactors. This development has resulted in graphite being established as a viable structural material for HTGRs. While the general characteristics necessary for producing nuclear grade graphite are understood, historical “nuclear” grades no longer exist. New grades must be fabricated, characterized, and irradiated to demonstrate that current grades of graphite exhibit acceptable non-irradiated and irradiated properties upon which the thermomechanical design of the structural graphite in NGNP is based. This Technology Development Plan outlines the research and development (R&D) activities and associated rationale necessary to qualify nuclear grade graphite for use within the NGNP reactor.

  7. Primer on gas integrated resource planning

    SciTech Connect (OSTI)

    Goldman, C.; Comnes, G.A.; Busch, J.; Wiel, S. [Lawrence Berkeley Lab., CA (United States)

    1993-12-01

    This report discusses the following topics: gas resource planning: need for IRP; gas integrated resource planning: methods and models; supply and capacity planning for gas utilities; methods for estimating gas avoided costs; economic analysis of gas utility DSM programs: benefit-cost tests; gas DSM technologies and programs; end-use fuel substitution; and financial aspects of gas demand-side management programs.

  8. Nevada National Security Site Waste Acceptance Criteria

    SciTech Connect (OSTI)

    NSTec Environmental Management

    2011-01-01

    This document establishes the U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office (NNSA/NSO) Nevada National Security Site Waste Acceptance Criteria (NNSSWAC). The NNSSWAC provides the requirements, terms, and conditions under which the Nevada National Security Site (NNSS) will accept low-level radioactive waste and mixed low-level waste for disposal. The NNSSWAC includes requirements for the generator waste certification program, characterization, traceability, waste form, packaging, and transfer. The criteria apply to radioactive waste received at the NNSS Area 3 and Area 5 Radioactive Waste Management Complex for disposal. The NNSA/NSO and support contractors are available to assist you in understanding or interpreting this document. For assistance, please call the NNSA/NSO Waste Management Project at (702) 295-7063 or fax to (702) 295-1153.

  9. Nevada National Security Site Waste Acceptance Criteria

    SciTech Connect (OSTI)

    NSTec Environmental Management

    2010-09-03

    This document establishes the U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office (NNSA/NSO) Nevada National Security Site Waste Acceptance Criteria (NNSSWAC). The NNSSWAC provides the requirements, terms, and conditions under which the Nevada National Security Site (NNSS) will accept low-level radioactive waste and mixed low-level waste for disposal. The NNSSWAC includes requirements for the generator waste certification program, characterization, traceability, waste form, packaging, and transfer. The criteria apply to radioactive waste received at the NNSS Area 3 and Area 5 Radioactive Waste Management Complex for disposal. The NNSA/NSO and support contractors are available to assist you in understanding or interpreting this document. For assistance, please call the NNSA/NSO Waste Management Project at (702) 295-7063 or fax to (702) 295-1153.

  10. SPECTR System Operational Test Report

    SciTech Connect (OSTI)

    W.H. Landman Jr.

    2011-08-01

    This report overviews installation of the Small Pressure Cycling Test Rig (SPECTR) and documents the system operational testing performed to demonstrate that it meets the requirements for operations. The system operational testing involved operation of the furnace system to the design conditions and demonstration of the test article gas supply system using a simulated test article. The furnace and test article systems were demonstrated to meet the design requirements for the Next Generation Nuclear Plant. Therefore, the system is deemed acceptable and is ready for actual test article testing.

  11. Streamlined Approach for Environmental Restoration (SAFER) Plan for Corrective Action Unit 357: Mud Pits and Waste Dump, Nevada Test Site, Nevada: Revision 0, Including Record of Technical Change No. 1

    SciTech Connect (OSTI)

    U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office

    2003-06-25

    This Streamlined Approach for Environmental Restoration (SAFER) plan was prepared as a characterization and closure report for Corrective Action Unit (CAU) 357, Mud Pits and Waste Dump, in accordance with the Federal Facility Agreement and Consent Order. The CAU consists of 14 Corrective Action Sites (CASs) located in Areas 1, 4, 7, 8, 10, and 25 of the Nevada Test Site (NTS). All of the CASs are found within Yucca Flat except CAS 25-15-01 (Waste Dump). Corrective Action Site 25-15-01 is found in Area 25 in Jackass Flat. Of the 14 CASs in CAU 357, 11 are mud pits, suspected mud pits, or mud processing-related sites, which are by-products of drilling activities in support of the underground nuclear weapons testing done on the NTS. Of the remaining CASs, one CAS is a waste dump, one CAS contains scattered lead bricks, and one CAS has a building associated with Project 31.2. All 14 of the CASs are inactive and abandoned. Clean closure with no further action of CAU 357 will be completed if no contaminants are detected above preliminary action levels. A closure report will be prepared and submitted to the Nevada Division of Environmental Protection for review and approval upon completion of the field activities. Record of Technical Change No. 1 is dated 3/2004.

  12. Editor's Note Owing to the increasing length of algorithms accepted for publication in ACM

    E-Print Network [OSTI]

    Hoffman, Karla

    Editor's Note Owing to the increasing length of algorithms accepted for publication in ACM,D.R. A test problem generator for discrete linear LI approximation problems. ACM Trans. Math. Softw. 6, 4 (Dec part of the listing is printed here. The complete listing is available from the ACM Algorithms

  13. Tolerant Versus Intolerant Testing for Boolean Properties Eldar Fischer

    E-Print Network [OSTI]

    Fortnow, Lance

    a question formulated in terms of property testing, and Rubinfeld and Sudan [21] formally defined Research recently started investigating property testing algorithms which are guaranteed to accept (with high R, an -test for R is a randomized algorithm that is guaranteed to accept with probability at least 2

  14. RELAP-7 SOFTWARE VERIFICATION AND VALIDATION PLAN

    SciTech Connect (OSTI)

    Smith, Curtis L; Choi, Yong-Joon; Zou, Ling

    2014-09-01

    This INL plan comprehensively describes the software for RELAP-7 and documents the software, interface, and software design requirements for the application. The plan also describes the testing-based software verification and validation (SV&V) process—a set of specially designed software models used to test RELAP-7.

  15. Palouse Subbasin Management Plan 3. Management Plan

    E-Print Network [OSTI]

    Palouse Subbasin Management Plan 3. Management Plan FINAL DRAFT ~ May 2004 Project Lead: Palouse-Rock Lake Conservation District Trevor Cook, Project Manager PO Box 438 St. John WA 99171 (509) 648;Palouse Subbasin Plan: MANAGEMENT PLAN Management Plan: Page 3 - 1 3. Management Plan 3.1 Background

  16. Web Application Testing with Customized Test Requirements--An Experimental Comparison Study Technical Report No. 2006-330

    E-Print Network [OSTI]

    Sampath, Sreedevi

    - quirements. 1.. Introduction Test requirement coverage is an important and well accepted measure for deciding when to stop testing, selecting test cases, and reducing test suites. Test coverage criteria defineWeb Application Testing with Customized Test Requirements--An Experimental Comparison Study

  17. Lawrence Livermore National Laboratory (LLNL) Experimental Test Site (Site 300) Salinity Evaluation and Minimization Plan for Cooling Towers and Mechanical Equipment Discharges

    SciTech Connect (OSTI)

    Daily III, W D

    2010-02-24

    This document was created to comply with the Central Valley Regional Water Quality Control Board (CVRWQCB) Waste Discharge Requirement (Order No. 98-148). This order established new requirements to assess the effect of and effort required to reduce salts in process water discharged to the subsurface. This includes the review of technical, operational, and management options available to reduce total dissolved solids (TDS) concentrations in cooling tower and mechanical equipment water discharges at Lawrence Livermore National Laboratory's (LLNL's) Experimental Test Site (Site 300) facility. It was observed that for the six cooling towers currently in operation, the total volume of groundwater used as make up water is about 27 gallons per minute and the discharge to the subsurface via percolation pits is 13 gallons per minute. The extracted groundwater has a TDS concentration of 700 mg/L. The cooling tower discharge concentrations range from 700 to 1,400 mg/L. There is also a small volume of mechanical equipment effluent being discharged to percolation pits, with a TDS range from 400 to 3,300 mg/L. The cooling towers and mechanical equipment are maintained and operated in a satisfactory manner. No major leaks were identified. Currently, there are no re-use options being employed. Several approaches known to reduce the blow down flow rate and/or TDS concentration being discharged to the percolation pits and septic systems were reviewed for technical feasibility and cost efficiency. These options range from efforts as simple as eliminating leaks to implementing advanced and innovative treatment methods. The various options considered, and their anticipated effect on water consumption, discharge volumes, and reduced concentrations are listed and compared in this report. Based on the assessment, it was recommended that there is enough variability in equipment usage, chemistry, flow rate, and discharge configurations that each discharge location at Site 300 should be considered separately when deciding on an approach for reducing the salt discharge to the subsurface. The smaller units may justify moderate changes to equipment, and may benefit from increased cleaning frequencies, more accurate and suitable chemical treatment, and sources of make up water and discharge re-use. The larger cooling towers would be more suitable for automated systems where they don't already exist, re-circulation and treatment of blow down water, and enhanced chemical dosing strategies. It may be more technically feasible and cost efficient for the smaller cooling towers to be replaced by closed loop dry coolers or hybrid towers. There are several potential steps that could be taken at each location to reduce the TDS concentration and/or water use. These include: sump water filtration, minimization of drift, accurate chemical dosing, and use of scale and corrosion coupons for chemical calibration. The implementation of some of these options could be achieved by a step-wise approach taken at two representative facilities. Once viable prototype systems have been proven in the field, systematic implementation should proceed for the remaining systems, with cost, desired reduction, and general feasibility taken into consideration for such systems.

  18. Helium bombardment leak testing of the closure disk weld for MC2949, MC3004, and MC3095 pyrotechnic devices

    SciTech Connect (OSTI)

    Dudley, W.A.

    1980-03-31

    A helium bombardment leak test procedure was developed to determine the leak level of the closure disk weld performed on three nearly identical pyrotechnic actuators. The inspection procedure is capable of leak testing any of the three product types at a rate better than 120 units per 8-hr work shift. Testing is performed on a 100% sample plan and employs a go/no-go bombardment leak rate acceptance specification of 3 x 10/sup -9/ atm-cm/sup 3/-sec/sup -1/. In addition to the current test procedure and results, this report includes a description of procedure and results associated with the test as initially performed. Other applications of the current technique are also listed.

  19. Fast 3D Triangle-Box Overlap Testing Tomas Akenine-Moller

    E-Print Network [OSTI]

    acceptance/rejection tests early on, and then testing each triangle edge for intersection with the cube faces. They also use fast acceptance/rejectance tests, but recast the testing of an edge against the cubeFast 3D Triangle-Box Overlap Testing Tomas Akenine-M¨oller Department of Computer Engineering

  20. Acceptance and Rejection of IGPPS Proposals

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity ofkandz-cm11 Outreach Home Room News Publications Traditional Knowledge KiosksAbout UsAbout NewAcceleratorAccepting, Rejecting

  1. Testing Juntas (draft) Carnegie Mellon University

    E-Print Network [OSTI]

    Goldreich, Oded

    a 1-junta tester: simply run the dictator test on f and ¯f, and also test if f is constant; acceptTesting Juntas (draft) Eric Blais Carnegie Mellon University eblais@cs.cmu.edu February 3, 2010. The problem of testing whether a function is a k-junta or is "far" from being a k-junta is a central problem

  2. Consumer Acceptance of GMO Cowpeas in Sub-Sahara Africa

    E-Print Network [OSTI]

    Ginzel, Matthew

    Consumer Acceptance of GMO Cowpeas in Sub-Sahara Africa Saket Kushwaha, A.S. Musa, James Lowenberg Professor at Purdue University, West Lafayette, IN. #12;Consumer Acceptance of GMO Cowpeas in Sub

  3. Testing Formula Satisfaction Eldar Fischer

    E-Print Network [OSTI]

    Fischer, Eldar

    of testing for properties defined by read once formulae, as instances of massively parametrized propertiesTesting Formula Satisfaction Eldar Fischer Oded Lachish Abstract We study the query complexity, and prove several testability and non-testability results. First we prove that any property accepted

  4. Corrective Action Investigation Plan for Corrective Action Unit 165: Areas 25 and 26 Dry Well and Washdown Areas, Nevada Test Site, Nevada (including Record of Technical Change Nos. 1, 2, and 3) (January 2002, Rev. 0)

    SciTech Connect (OSTI)

    U.S. Department of Energy, National Nuclear Security Administration Nevada Operations Office (NNSA/NV)

    2002-01-09

    This Corrective Action Investigation Plan contains the U.S. Department of Energy, National Nuclear Security Administration Nevada Operations Office's approach to collect the data necessary to evaluate corrective action alternatives appropriate for the closure of Corrective Action Unit (CAU) 165 under the Federal Facility Agreement and Consent Order. Corrective Action Unit 165 consists of eight Corrective Action Sites (CASs): CAS 25-20-01, Lab Drain Dry Well; CAS 25-51-02, Dry Well; CAS 25-59-01, Septic System; CAS 26-59-01, Septic System; CAS 25-07-06, Train Decontamination Area; CAS 25-07-07, Vehicle Washdown; CAS 26-07-01, Vehicle Washdown Station; and CAS 25-47-01, Reservoir and French Drain. All eight CASs are located in the Nevada Test Site, Nevada. Six of these CASs are located in Area 25 facilities and two CASs are located in Area 26 facilities. The eight CASs at CAU 165 consist of dry wells, septic systems, decontamination pads, and a reservoir. The six CASs in Area 25 are associated with the Nuclear Rocket Development Station that operated from 1958 to 1973. The two CASs in Area 26 are associated with facilities constructed for Project Pluto, a series of nuclear reactor tests conducted between 1961 to 1964 to develop a nuclear-powered ramjet engine. Based on site history, the scope of this plan will be a two-phased approach to investigate the possible presence of hazardous and/or radioactive constituents at concentrations that could potentially pose a threat to human health and the environment. The Phase I analytical program for most CASs will include volatile organic compounds, semivolatile organic compounds, Resource Conservation and Recovery Act metals, total petroleum hydrocarbons, polychlorinated biphenyls, and radionuclides. If laboratory data obtained from the Phase I investigation indicates the presence of contaminants of concern, the process will continue with a Phase II investigation to define the extent of contamination. Based on the results of Phase I sampling, the analytical program for Phase II investigation may be reduced. The results of this field investigation will support a defensible evaluation of corrective action alternatives in the corrective action decision document.

  5. RERTR Fuel Developmemt and Qualification Plan

    SciTech Connect (OSTI)

    Dan Wachs

    2007-01-01

    In late 2003 it became evident that U-Mo aluminum fuels under development exhibited significant fuel performance problems under the irradiation conditions required for conversion of most high-powered research reactors. Solutions to the fuel performance issue have been proposed and show promise in early testing. Based on these results, a Reduced Enrichment Research and Test Reactor (RERTR) program strategy has been mapped to allow generic fuel qualification to occur prior to the end of FY10 and reactor conversion to occur prior to the end of FY14. This strategy utilizes a diversity of technologies, test conditions, and test types. Scoping studies using miniature fuel plates will be completed in the time frame of 2006-2008. Irradiation of larger specimens will occur in the Advanced Test Reactor (ATR) in the United States, the Belgian Reactor-2 (BR2) reactor in Belgium, and in the OSIRIS reactor in France in 2006-2009. These scoping irradiation tests provide a large amount of data on the performance of advanced fuel types under irradiation and allow the down selection of technology for larger scale testing during the final stages of fuel qualification. In conjunction with irradiation testing, fabrication processes must be developed and made available to commercial fabricators. The commercial fabrication infrastructure must also be upgraded to ensure a reliable low enriched uranium (LEU) fuel supply. Final qualification of fuels will occur in two phases. Phase I will obtain generic approval for use of dispersion fuels with density less than 8.5 g-U/cm3. In order to obtain this approval, a larger scale demonstration of fuel performance and fabrication technology will be necessary. Several Materials Test Reactor (MTR) plate-type fuel assemblies will be irradiated in both the High Flux Reactor (HFR) and the ATR (other options include the BR2 and Russian Research Reactor, Dmitrovgrad, Russia [MIR] reactors) in 2008-2009. Following postirradiation examination, a report detailing very-high density fuel behavior will be submitted to the U.S. Nuclear Regulatory Commission (NRC). Assuming acceptable fuel behavior, it is anticipated that NRC will issue a Safety Evaluation Report granting generic approval of the developed fuels based on the qualification report. It is anticipated that Phase I of fuel qualification will be completed prior to the end of FY10. Phase II of the fuel qualification requires development of fuels with density greater than 8.5 g-U/cm3. This fuel is required to convert the remaining few reactors that have been identified for conversion. The second phase of the fuel qualification effort includes both dispersion fuels with fuel particle volume loading on the order of 65 percent, and monolithic fuels. Phase II presents a larger set of technical unknowns and schedule uncertainties than phase I. The final step in the fuel qualification process involves insertion of lead test elements into the converting reactors. Each reactor that plans to convert using the developed high-density fuels will develop a reactor specific conversion plan based upon the reactor safety basis and operating requirements. For some reactors (FRM-II, High-Flux Isotope Reactor [HFIR], and RHF) conversion will be a one-step process. In addition to the U.S. fuel development effort, a Russian fuel development strategy has been developed. Contracts with Russian Federation institutes in support of fuel development for Russian are in place.

  6. ForPeerReview PUBLIC ACCEPTANCE OF OFFSHORE WIND POWER

    E-Print Network [OSTI]

    Firestone, Jeremy

    ForPeerReview PUBLIC ACCEPTANCE OF OFFSHORE WIND POWER PROJECTS IN THE UNITED STATES Journal: Wind, Andrew; Minerals Management Service Keywords: offshore wind power, public opinion, social acceptancePeerReview 1 PUBLIC ACCEPTANCE OF OFFSHORE WIND POWER PROJECTS IN THE UNITED STATES Jeremy Firestone*, Willett

  7. Social Acceptance of Wind: A Brief Overview (Presentation)

    SciTech Connect (OSTI)

    Lantz, E.

    2015-01-01

    This presentation discusses concepts and trends in social acceptance of wind energy, profiles recent research findings, and discussions mitigation strategies intended to resolve wind power social acceptance challenges as informed by published research and the experiences of individuals participating in the International Energy Agencies Working Group on Social Acceptance of Wind Energy

  8. STATE OF CALIFORNIA DISTRIBUTED ENERGY STORAGE DX AC SYSTEMES ACCEPTANCE

    E-Print Network [OSTI]

    STATE OF CALIFORNIA DISTRIBUTED ENERGY STORAGE DX AC SYSTEMES ACCEPTANCE CEC-MECH-14A (Revised 08/09) CALIFORNIA ENERGY COMMISSION CERTIFICATE OF ACCEPTANCE MECH-14A NA7.5.13 Distributed Energy Storage DX AC DISTRIBUTED ENERGY STORAGE DX AC SYSTEMES ACCEPTANCE CEC-MECH-14A (Revised 08/09) CALIFORNIA ENERGY COMMISSION

  9. STATE OF CALIFORNIA THERMAL ENERGY STORAGE (TES) SYSTEM ACCEPTANCE

    E-Print Network [OSTI]

    STATE OF CALIFORNIA THERMAL ENERGY STORAGE (TES) SYSTEM ACCEPTANCE CEC-MECH-15A (Revised 07/10) CALIFORNIA ENERGY COMMISSION CERTIFICATE OF ACCEPTANCE MECH-15A NA7.5.14 Thermal Energy Storage (TES) System THERMAL ENERGY STORAGE (TES) SYSTEM ACCEPTANCE CEC-MECH-15A (Revised 07/10) CALIFORNIA ENERGY COMMISSION

  10. Carlsbad Area Office strategic plan

    SciTech Connect (OSTI)

    NONE

    1995-10-01

    This edition of the Carlsbad Area Office Strategic Plan captures the U.S. Department of Energy`s new focus, and supercedes the edition issued previously in 1995. This revision reflects a revised strategy designed to demonstrate compliance with environmental regulations earlier than the previous course of action; and a focus on the selected combination of scientific investigations, engineered alternatives, and waste acceptance criteria for supporting the compliance applications. An overview of operations and historical aspects of the Waste Isolation Pilot Plant near Carlsbad, New Mexico is presented.

  11. THE ENVIRONMENTAL TECHNOLOGIES ACCEPTANCE (ETA) PROGRAM

    SciTech Connect (OSTI)

    Christina B. Behr-Andres

    2001-10-01

    The objective of the Environmental Technologies Acceptance (ETA) Program at the Energy & Environmental Research Center (EERC) is to advance the development, commercial acceptance, and timely deployment of selected private sector technologies for the cleanup of sites in the nuclear defense complex as well as the greater market. As a result of contract changes approved by National Energy Technology Laboratory (NETL) representatives to incorporate activities previously conducted under another NETL agreement, there are now an additional task and an expansion of activities within the stated scope of work of the ETA program. As shown in Table 1, this cooperative agreement, funded by NETL (No. DE-FC26-00NT40840), consists of four tasks: Technology Selection, Technology Development, Technology Verification, and System Engineering. As currently conceived, ETA will address the needs of as many technologies as appropriate under its current 3-year term. There are currently four technical subtasks: Long-Term Stewardship Initiative at the Mound Plant Site; Photocatalysis of Mercury-Contaminated Water; Subcritical Water Treatment of PCB and Metal-Contaminated Paint Waste; and Vegetative Covers for Low-Level Waste Repositories. This report covers activities during the second six months of the three-year ETA program.

  12. Long-Term Ecological Monitoring Field Sampling Plan for 2007

    SciTech Connect (OSTI)

    T. Haney R. VanHorn

    2007-07-31

    This field sampling plan describes the field investigations planned for the Long-Term Ecological Monitoring Project at the Idaho National Laboratory Site in 2007. This plan and the Quality Assurance Project Plan for Waste Area Groups 1, 2, 3, 4, 5, 6, 7, 10, and Removal Actions constitute the sampling and analysis plan supporting long-term ecological monitoring sampling in 2007. The data collected under this plan will become part of the long-term ecological monitoring data set that is being collected annually. The data will be used t determine the requirements for the subsequent long-term ecological monitoring. This plan guides the 2007 investigations, including sampling, quality assurance, quality control, analytical procedures, and data management. As such, this plan will help to ensure that the resulting monitoring data will be scientifically valid, defensible, and of known and acceptable quality.

  13. Estimation of Distribution Algorithms for Testing Object Oriented Ramon Sagarna, Andrea Arcuri and Xin Yao, Fellow, IEEE

    E-Print Network [OSTI]

    Yao, Xin

    defined by the testing problem and thus could provide some insight into the problem. Firstly, we show. Additionally, tests may be applied at different levels, ranging from unit testing to acceptance testing. A unit refers to the minimal software module that can be tested, e.g. a code function. Acceptance testing

  14. Corrective Action Investigation Plan for Corrective Action Unit 321: Area 22 Weather Station Fuel Storage, Nevada Test Site, Nevada, Revision 0. UPDATED WITH RECORD OF TECHNICAL CHANGE No.1

    SciTech Connect (OSTI)

    U.S. DOE /NV

    1999-02-08

    This Corrective Action Investigation Plan (CAIP) has been developed in accordance with the Federal Facility Agreement and Consent Order (FFACO) that was agreed to by the US Department of Energy, Nevada Operations Office (DOE/NV); the State of Nevada Division of Environmental Protection (NDEP); and the US Department of Defense (FFACO, 1996). The CAIP is a document that provides or references all of the specific information for investigation activities associated with Corrective Action Units (CAUs) or Corrective Action Sites (CASs). According to the FFACO (1996), CASs are sites potentially requiring corrective action(s) and may include solid waste management units or individual disposal or release sites. A CAU consists of one or more CASs grouped together based on geography, technical similarity, or agency responsibility for the purpose of determining corrective actions. This CAIP contains the environmental sample collection objectives and the criteria for conducting site investigation activities at the CAU 321 Area 22 Weather Station Fuel Storage, CAS 22-99-05 Fuel Storage Area. For purposes of this discussion, this site will be referred to as either CAU 321 or the Fuel Storage Area. The Fuel Storage Area is located in Area 22 of the Nevada Test Site (NTS). The NTS is approximately 105 kilometers (km) (65 miles [mi]) northwest of Las Vegas, Nevada (DOE/NV, 1996a). The Fuel Storage Area was used to store fuel and other petroleum products necessary for motorized operations at the historic Camp Desert Rock facility which was operational from 1951 to 1958 at the Nevada Test Site, Nevada. The site was dismantled after 1958 (DOE/NV, 1996a).

  15. Corrective Action Investigation Plan for Corrective Action Unit 527: Horn Silver Mine, Nevada Test Site, Nevada: Revision 1 (Including Records of Technical Change No.1, 2, 3, and 4)

    SciTech Connect (OSTI)

    U.S. Department of Energy, National Nuclear Security Administration Nevada Operations Office

    2002-12-06

    This Corrective Action Investigation Plan contains the U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Operations Office's approach to collect the data necessary to evaluate corrective action alternatives appropriate for the closure of Corrective Action Unit (CAU) 527, Horn Silver Mine, Nevada Test Site, Nevada, under the Federal Facility Agreement and Consent Order. Corrective Action Unit 527 consists of one Corrective Action Site (CAS): 26-20-01, Contaminated Waste Dump No.1. The site is located in an abandoned mine site in Area 26 (which is the most arid part of the NTS) approximately 65 miles northwest of Las Vegas. Historical documents may refer to this site as CAU 168, CWD-1, the Wingfield mine (or shaft), and the Wahmonie mine (or shaft). Historical documentation indicates that between 1959 and the 1970s, nonliquid classified material and unclassified waste was placed in the Horn Silver Mine's shaft. Some of the waste is known to be radioactive. Documentation indicates that the waste is present from 150 feet to the bottom of the mine (500 ft below ground surface). This CAU is being investigated because hazardous constituents migrating from materials and/or wastes disposed of in the Horn Silver Mine may pose a threat to human health and the environment as well as to assess the potential impacts associated with any potential releases from the waste. The results of this field investigation will support a defensible evaluation of corrective action alternatives in the corrective action decision document.

  16. Tritium High Vacuum Pump Test Plan

    Office of Environmental Management (EM)

    of Normetex vs. Eumeca Air Squared Edwards Busch * Ultimate Vacuum * Develop Flow Curve * Provide basis for selecting the Normetex Pump Replacement Performance * Flow...

  17. Tritium High Vacuum Pump Test Plan

    Broader source: Energy.gov [DOE]

    Presentation from the 33rd Tritium Focus Group Meeting held in Aiken, South Carolina on April 22-24, 2014.

  18. An economic approach to acceptance sampling 

    E-Print Network [OSTI]

    Ruth, Robert Justin

    1973-01-01

    Engineering Graduate Program. He is grateful to the United States Army for the opportunity to partioipate in this program. A final note of' thanks 1s eztended to the author' s wife, Deborah Ruth, for her ass1stanoe in typing this manusoript. The ideas... would be one which minimizes the average or expected opportunity loss. A method for evaluating sampling plans on the basis of opportunity loss is detailed and. results 15 obtained from an "experimental computer program" are given. The model...

  19. Advanced Technology Vehicle Testing

    SciTech Connect (OSTI)

    James Francfort

    2004-06-01

    The goal of the U.S. Department of Energy's Advanced Vehicle Testing Activity (AVTA) is to increase the body of knowledge as well as the awareness and acceptance of electric drive and other advanced technology vehicles (ATV). The AVTA accomplishes this goal by testing ATVs on test tracks and dynamometers (Baseline Performance testing), as well as in real-world applications (Fleet and Accelerated Reliability testing and public demonstrations). This enables the AVTA to provide Federal and private fleet managers, as well as other potential ATV users, with accurate and unbiased information on vehicle performance and infrastructure needs so they can make informed decisions about acquiring and operating ATVs. The ATVs currently in testing include vehicles that burn gaseous hydrogen (H2) fuel and hydrogen/CNG (H/CNG) blended fuels in internal combustion engines (ICE), and hybrid electric (HEV), urban electric, and neighborhood electric vehicles. The AVTA is part of DOE's FreedomCAR and Vehicle Technologies Program.

  20. Strategic Planning for Landowners 

    E-Print Network [OSTI]

    Johnson, Jason; Polk, Wade

    2008-09-16

    Strategic planning is crucial to the success of any business. This publication explains the planning process, from establishing the mission, to setting goals, to developing a business plan....

  1. Guidance for Planning Exercises

    Office of Environmental Management (EM)

    blank table of contents Transportation Emergency Preparedness Program (TEPP) planning tools planning tools Guidance f Guidance f Guidance f Guidance f Guidance for Planning,...

  2. Walkability Planning in Jakarta

    E-Print Network [OSTI]

    Lo, Ria S. Hutabarat

    2011-01-01

    key goals in relation to pedestrian planning? What trends dotransportation and planning in Jakarta in the future?pedestrian research or planning in Indonesia, the notion of

  3. Using different ELECTRE methods in strategic planning in the presence of human behavioral resistance

    E-Print Network [OSTI]

    Shanian, A.

    2006-01-01

    In the multicriteria strategic planning of an organization, management should often be aware of employees' resistance to change before making new decisions; otherwise, a chosen strategy, though technologically acceptable, ...

  4. Adaptation Plan 

    E-Print Network [OSTI]

    Durnbaugh, A.

    2011-01-01

    Response Update the extreme weather operation plan, focusing on vulnerable populations. Add climate-sensitive disease surveillance. Roads Pilot & implement new road materials to manage stormwater, decrease urban heat island effect, & maintain... and dry summers Source: Hayhoe et al. Journal of Great Lakes Research, 2010. Summers % changes relative to a 1961-1990 average ESL-KT-11-11-16 6 What is CCAP? Our goals to reduce Chicago?s greenhouse gas emissions and prepare for climate change?s...

  5. STRATEGIC PLAN

    Energy Savers [EERE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on DeliciousMathematics AndBeryllium Disease |Records Management FieldSOLANA SOLANA SOLANA SOLANA-2020 STRATEGIC PLAN and

  6. Plan Execution Failure Analysis Using Plan Deconstruction 

    E-Print Network [OSTI]

    McNeill, F.; Bundy, Alan; Walton, Ch.; Schorlemmer, Marco

    We consider the challenges that arise when plans are based on an incorrect representation of the domain in which they are executed. We describe how information about plan formation, and how the way in which each plan step ...

  7. Phase II Corrective Action Investigation Plan for Corrective Action Units 101 and 102: Central and Western Pahute Mesa, Nevada Test Site, Nye County, Nevada, Revision 2 with ROTC 1 and 2

    SciTech Connect (OSTI)

    Marutzky, Sam

    2009-07-01

    This Phase II CAIP describes new work needed to potentially reduce uncertainty and achieve increased confidence in modeling results. This work includes data collection and data analysis to refine model assumptions, improve conceptual models of flow and transport in a complex hydrogeologic setting, and reduce parametric and structural uncertainty. The work was prioritized based on the potential to reduce model uncertainty and achieve an acceptable level of confidence in the model predictions for flow and transport, leading to model acceptance by NDEP and completion of the Phase II CAI stage of the UGTA strategy.

  8. CHEMICAL HYGIENE PLAN HAZARD COMMUNICATION PLAN

    E-Print Network [OSTI]

    Kim, Duck O.

    Biological Safety Officer Ergonomic Specialist 2723 Radiation Safety 2250 Facilities Management Office 2125. ANNUAL REVIEW AND EVALUATION OF EFFECTIVENESS OF THE CHEMICAL HYGIENE PLAN 9. HAZARD COMMUNICATION PLAN

  9. Tolerant Versus Intolerant Testing for Boolean Properties Eldar Fischer #

    E-Print Network [OSTI]

    Fortnow, Lance

    , as defined by Parnas, Ron and Rubinfeld, must also accept inputs that are close enough to satisfying­ vestigate a question formulated in terms of property testing, and Rubinfeld and Sudan [21] formally defined. Given a property R, an #­test for R is a randomized algorithm that is guaranteed to accept

  10. ENHANCING STAKEHOLDER ACCEPTANCE OF BIOREMEDIATION TECHNOLOGIES

    SciTech Connect (OSTI)

    Focht, Will; Albright, Matt; Anex, Robert P., Jr., ed.

    2009-04-21

    This project inquired into the judgments and beliefs of people living near DOE reservations and facilities at Oak Ridge, Tennessee; Hanford, Washington; and Los Alamos, Tennessee about bioremediation of subsurface contamination. The purpose of the investigation was to identify strategies based on these judgments and beliefs for enhancing public support of bioremediation. Several methods were used to collect and analyze data including content analysis of transcripts of face-to-face personal interviews, factor analysis of subjective perspectives using Q methodology, and statistical analysis of results from a large-sample randomized telephone survey. Content analysis of interview transcripts identified themes about public perceptions and constructions of contamination risk, risk management, and risk managers. This analysis revealed that those who have no employment relationship at the sites and are not engaged in technical professions are most concerned about contamination risks. We also found that most interviewees are unfamiliar with subsurface contamination risks and how they can be reduced, believe they have little control over exposure, are frustrated with the lack of progress in remediation, are concerned about a lack of commitment of DOE to full remediation, and distrust site managers to act in the public interest. Concern is also expressed over frequent site management turnover, excessive secrecy, ineffective and biased communication, perceived attempts to talk the public into accepting risk, and apparent lack of concern about community welfare. In the telephone survey, we asked respondents who were aware of site contamination about their perceptions of risk from exposure to subsurface contamination. Response analysis revealed that most people believe that they are at significant risk from subsurface contamination but they acknowledge that more education is needed to calibrate risk perceptions against scientific risk assessments. Most rate their personal control over exposure as low. Slightly more than half believe that risk reduction should be balanced against cost. We also found that distrust of DOE and its contractors exists, primarily due to the perception that site managers do not share public values; hence, the public is generally unwilling to defer to DOE in its decision-making. The concomitant belief of inefficacy confounds distrust by generating frustration that DOE does not care. Moreover, the public is split with respect to trust of each other, primarily because of the belief that citizens lack technical competence. With respect to bioremediation support, we found that more than 40% of the public has no opinion. However, of those who do, 3 of 4 are favorably disposed – particularly among those who believe that risk is lower and who are more trusting of site management. We presented survey respondents with four alternative participation strategies based on the results of the Q analysis and asked their judgments of each. The public prefers strategies that shifts power to them. The least empowered strategy (feedback) was supported by 46%; support grew as public power increased, reaching 66% support for independently facilitated deliberation. More DOE distrust generates more support for high power strategies. We offer the following recommendations to enhance public acceptance. First, and perhaps most importantly, site managers should pursue robust trust-building efforts to gain public confidence in DOE risk management that meets public expectations. Public trust decreases risk perception, which increases public willingness to defer to site managers’ discretion in decision-making, which in turn increases public acceptance of the decisions that result. Second, site managers should address public concerns about bioremediation such as its effectiveness in reducing risk, performance compared to other remediation alternatives, costs compared against benefits, time required to start and complete remediation, level of risk that is currently posed by contamination, and scope of application. Third, more should be d

  11. Business Services Strategic Plan

    E-Print Network [OSTI]

    Pittendrigh, Barry

    Business Services Strategic Plan Updated September 2008 New Synergies: Launching Tomorrow's Leaders. Facilitate implementation of the University Strategic Plan 2. Analyze, plan, and manage University finances, processes, and contracts in global and strategic partnerships 3. Review existing capital financing plans

  12. Introduction to Transportation Planning

    E-Print Network [OSTI]

    Tipple, Brett

    Introduction to Transportation Planning CMP 4710/6710 Fall 2012 3 Credit Hours Room: ARCH 229 of City & Metropolitan Planning; Associate Dean, College of Architecture + Planning; former associate, social equity, fiscal health, and public health. Unfortunately, most transportation planning processes

  13. Generalized partition testing via Bayes linear methods

    E-Print Network [OSTI]

    Munro, Malcolm

    subset of all possible test cases should be chosen. An accepted approach is to partition the input domain, and the art of testing that of defining subdomains. Partitioning can be based either on a black box view to difficulties of ill defined and overlapping subdomains [17] which can possibly invalidate any analysis of test

  14. Unit Testing for Casl Architectural Specifications

    E-Print Network [OSTI]

    Sannella, Don

    and impractical activity. When only finite sets of interactions are considered, successful testing can acceptUnit Testing for Casl Architectural Specifications Patricia D.L. Machado 1 and Donald Sannella 2 1 Science, University of Edinburgh Abstract. The problem of testing modular systems against algebraic

  15. Algebraic Property Testing: The Role of Invariance

    E-Print Network [OSTI]

    Sudan, Madhu

    -locally testable if there exists a randomized test that queries the value of a function f on k inputs and accepts f of the linearity test of Blum, Luby, and Rubinfeld [4] and was defined formally in Rubinfeld and Sudan [19Algebraic Property Testing: The Role of Invariance Tali Kaufman Madhu Sudan November 2, 2007

  16. Efficient Systematic Testing for Dynamically Updatable Software

    E-Print Network [OSTI]

    Hicks, Michael

    could be ap- plied, we define an update test tµ that runs t on the old version of P and applies at µ or feature addition), we can construct a hybrid update test that accepts both the old and the new versionEfficient Systematic Testing for Dynamically Updatable Software Christopher M. Hayden Eric A

  17. Testing Monotonicity \\Lambda Oded Goldreich y

    E-Print Network [OSTI]

    Goldreich, Oded

    function f : f0; 1g n 7! f0; 1g at arguments of its choice, the test always accepts a monotone f monotone function. 1.1 Perspective Property Testing, as explicitly defined by Rubinfeld and Sudan [31 this case of BCH codes), and that such tests can be defined and performed also for other error

  18. Unit Testing for Casl Architectural Specifications

    E-Print Network [OSTI]

    Sannella, Don

    and impractical activity. When only finite sets of interactions are considered, successful testing can acceptUnit Testing for Casl Architectural Specifications Patricia D.L. Machado1 and Donald Sannella2 1 Science, University of Edinburgh Abstract. The problem of testing modular systems against algebraic

  19. Characterize and explore potential sites and prepare research and development plan (site investigation study). Final draft. Task 2. Milestone report

    SciTech Connect (OSTI)

    1980-12-01

    A specific research and development plan to investigate the behavior and suitability of aquifers as compressed air energy storage (CAES) sites is presented. The proposed effort will evaluate present uncertainties in the performance of the underground energy storage subsystem and its impact on above ground plant design and cost. The project is planned to provide the utility industry with a quantitative basis for confidence that financial commitment to a demonstration plant and subsequent expansion is justified and poses acceptable risks. Activities in Phase II of a 5-phase overall CAES development program are reported. Information is included on the development of field testing specifications and schedules; selection of specific site for the conceptual design; development plan and schedule for the media site; development of analytical models of aquifer airflow; and well drilling requirements. As a result of these studies 14 sites in Illinois and Indiana were evaluated, 7 were ranked for suitability for CAES, and 4 were selected for possible use in the field testing program. Test procedures, the mathematical models and drilling requirments were developed. (LCL)

  20. Strategic Plan

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of NaturalDukeWakefieldSulfateSciTechtail.Theory ofDidDevelopment TopMetathesis and Oxidation of MetalStrategic Plan

  1. Dental Plan

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity ofkandz-cm11 Outreach Home Room NewsInformation Current HAB Packet HanfordDOEDanielDe novo DesignNeudeckerDental Plan Dental

  2. Work Plan

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantityBonneville Power AdministrationRobust,Field-effectWorking WithTelecentricNCubictheThepresented in the7 Table7Work &Work Plan

  3. Retirement Plans

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity ofkandz-cm11 Outreach Home RoomPreservation of Fe(II) byMultiday ProductionDesigningResources Thomas JeffersonRetirement Plan

  4. Retirement Plans

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity ofkandz-cm11 Outreach Home RoomPreservation of Fe(II) byMultiday ProductionDesigningResources Thomas JeffersonRetirement Plan

  5. Plans, Procedures

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity ofkandz-cm11 Outreach Home Room NewsInformationJesseworkSURVEYI/OPerformancePi Day Pi Day Pi Day isPlanning for Life On

  6. IN SITU FIELD TESTING OF PROCESSES

    SciTech Connect (OSTI)

    J.S.Y. YANG

    2004-11-08

    The purpose of this scientific analysis report is to update and document the data and subsequent analyses from ambient field-testing activities performed in underground drifts and surface-based boreholes through unsaturated zone (UZ) tuff rock units. In situ testing, monitoring, and associated laboratory studies are conducted to directly assess and evaluate the waste emplacement environment and the natural barriers to radionuclide transport at Yucca Mountain. This scientific analysis report supports and provides data to UZ flow and transport model reports, which in turn contribute to the Total System Performance Assessment (TSPA) of Yucca Mountain, an important document for the license application (LA). The objectives of ambient field-testing activities are described in Section 1.1. This report is the third revision (REV 03), which supercedes REV 02. The scientific analysis of data for inputs to model calibration and validation as documented in REV 02 were developed in accordance with the Technical Work Plan (TWP) ''Technical Work Plan for: Performance Assessment Unsaturated Zone'' (BSC 2004 [DIRS 167969]). This revision was developed in accordance with the ''Technical Work Plan for: Unsaturated Zone Flow Analysis and Model Report Integration'' (BSC 2004 [DIRS 169654], Section 1.2.4) for better integrated, consistent, transparent, traceable, and more complete documentation in this scientific analysis report and associated UZ flow and transport model reports. No additional testing or analyses were performed as part of this revision. The list of relevant acceptance criteria is provided by ''Technical Work Plan for: Unsaturated Zone Flow Analysis and Model Report Integration'' (BSC 2004 [DIRS 169654]), Table 3-1. Additional deviations from the TWP regarding the features, events, and processes (FEPs) list are discussed in Section 1.3. Documentation in this report includes descriptions of how, and under what conditions, the tests were conducted. The descriptions and analyses provide data useful for refining and confirming the understanding of flow, drift seepage, and transport processes in the UZ. The UZ testing activities included measurement of permeability distribution, quantification of the seepage of water into the drifts, evaluation of fracture-matrix interaction, study of flow along faults, testing of flow and transport between drifts, characterization of hydrologic heterogeneity along drifts, estimation of drying effects on the rock surrounding the drifts due to ventilation, monitoring of moisture conditions in open and sealed drifts, and determination of the degree of minimum construction water migration below drift. These field tests were conducted in two underground drifts at Yucca Mountain, the Exploratory Studies Facility (ESF) drift, and the cross-drift for Enhanced Characterization of the Repository Block (ECRB), as described in Section 1.2. Samples collected in boreholes and underground drifts have been used for additional hydrochemical and isotopic analyses for additional understanding of the UZ setting. The UZ transport tests conducted at the nearby Busted Butte site (see Figure 1-4) are also described in this scientific analysis report.

  7. The Department of Energy Respiratory Acceptance Program for Supplied-Air Suits

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2004-02-04

    The supplied-air suits that protect DOE contractor and federal employees from exposure to harmful atmospheres and radioactive contaminants are not included in the National Institute for Occupational Safety and Health (NIOSH) certification process for respiratory protective devices. Therefore, with the awareness and acknowledgement of NIOSH and the Occupational Safety and Health Administration (OSHA), the Department established a system for acceptance testing of supplied-air suits.

  8. Perfectionism and acceptance: perspective taking and implicit beliefs 

    E-Print Network [OSTI]

    Lowdon, Rachel

    research examines associations between perfectionism and acceptance for the self and towards others, alongside their link with psychological health. Reported beliefs are compared with underlying implicit beliefs, as ...

  9. EV Everywhere Grand Challenge: Consumer Acceptance and Charging...

    Broader source: Energy.gov (indexed) [DOE]

    Attnedance list for the EV Everywhere Grand Challenge: Consumer Acceptance and Charging Infrastructure Workshop on July 30, 2012 held at the LAX Marriott, Los Angeles, CA...

  10. EV Everywhere Consumer Acceptance Workshop: Breakout Group B...

    Office of Environmental Management (EM)

    Workshop: Breakout Group B Report Out Group B breakout session presentation for the EV Everywhere Grand Challenge: Consumer Acceptance and Charging Infrastructure Workshop on...

  11. Increasing the Market Acceptance of Smaller CHP Systems

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Packaged Combined Heat and Power System ADVANCED MANUFACTURING OFFICE Increasing the Market Acceptance of Smaller CHP Systems This project is developing a flexible, packaged...

  12. Benchmarking of Multiparticle Phase Scan and Acceptance Scan...

    Office of Scientific and Technical Information (OSTI)

    of Multiparticle Phase Scan and Acceptance Scan techniques for the Spallation Neutron Source linac Citation Details In-Document Search Title: Benchmarking of Multiparticle...

  13. Guidelines and Checklist for Commissioning and Government Acceptance...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    and Contract Clauses for Government Acceptance of ESPC Projects Commissioning Guidance for ESPCs Study Guide for Photovoltaic System Installers and Sample Examination Questions...

  14. Wind Power Siting: Public Acceptance and Land Use

    Wind Powering America (EERE)

    by the Alliance for Sustainable Energy, LLC. Wind Power Siting: Public Acceptance and Land Use Suzanne Tegen WINDExchange Webinar June 17, 2015 2 Overview * Current NREL Research *...

  15. Public Acceptance of Wind: Foundational Study Near US Wind Facilities

    Wind Powering America (EERE)

    Group * Energy Analysis and Environmental Impacts Department Public Acceptance of Wind Power Ben Hoen Lawrence Berkeley National Laboratory WindExchange Webinar June 17, 2015...

  16. Sandia Energy - CRF Experiment Confirms Accepted Oxidation Scheme...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Experiment Confirms Accepted Oxidation Scheme of Proposed Diesel Alternative: Dimethyl Ether Home Energy Transportation Energy CRF Facilities Capabilities News News & Events...

  17. Prototype heater test of the environment around a simulated waste...

    Office of Scientific and Technical Information (OSTI)

    Barrier Systems Field Tests (EBSFT) planned for the Exploratory Shaft Facility in Yucca Mountain. The EBSFT will consist of in situ tests of the geohydrologic and...

  18. Global Threat Reduction Initiative Fuel Thermo-Physical Characterization Project: Sample Management Plan

    SciTech Connect (OSTI)

    Casella, Amanda J.; Pereira, Mario M.; Steen, Franciska H.

    2013-01-01

    This sample management plan provides guidelines for sectioning, preparation, acceptance criteria, analytical path, and end-of-life disposal for the fuel element segments utilized in the Global Threat Reduction Initiative (GTRI), Fuel Thermo-Physical Characterization Project. The Fuel Thermo-Physical Characterization Project is tasked with analysis of irradiated Low Enriched Uranium (LEU) Molybdenum (U-Mo) fuel element samples to support the GTRI conversion program. Sample analysis may include optical microscopy (OM), scanning electron microscopy (SEM) fuel-surface interface analysis, gas pycnometry (density) measurements, laser flash analysis (LFA), differential scanning calorimetry (DSC), thermogravimetry and differential thermal analysis with mass spectroscopy (TG /DTA-MS), Inductively Coupled Plasma Spectrophotometry (ICP), alpha spectroscopy, and Thermal Ionization Mass Spectroscopy (TIMS). The project will utilize existing Radiochemical Processing Laboratory (RPL) operating, technical, and administrative procedures for sample receipt, processing, and analyses. Test instructions (TIs), which are documents used to provide specific details regarding the implementation of an existing RPL approved technical or operational procedure, will also be used to communicate to staff project specific parameters requested by the Principal Investigator (PI). TIs will be developed, reviewed, and issued in accordance with the latest revision of the RPL-PLN-700, RPL Operations Plan. Additionally, the PI must approve all project test instructions and red-line changes to test instructions.

  19. Venus Technology Plan Venus Technology Plan

    E-Print Network [OSTI]

    Rathbun, Julie A.

    Venus Technology Plan May 2014 #12; ii Venus Technology Plan At the Venus Exploration Survey priorities, and (3) develop a Technology Plan for future Venus missions (after a Technology Forum at VEXAG Meeting 11 in November 2013). Here, we present the 2014 Venus Technology Plan

  20. Strategic Plan Strategic Plan 20102015 1

    E-Print Network [OSTI]

    Strategic Plan 2010­2015 #12;#12;#12;#12;Strategic Plan 2010­2015 1 Table of Contents Message from. . . . . . . . 36 #12;2 College of Geosciences Message from the Dean This strategic plan has come together in an era and #12;Strategic Plan 2010­2015 3 human capital. With respect to research it is clear that the College

  1. Strategic Plan update Strategic Plan 201020

    E-Print Network [OSTI]

    Rambaut, Andrew

    Strategic Plan update Strategic Plan 2010­20: Two-year update February 2012 #12;1 Strategic-year Wellcome Trust Strategic Plan for 2010­20. It describes how we will work to further our vision of achieving in our Annual Review and Assessment Framework Reports. Implementing our Strategic Plan ­ highlights

  2. Privacy Management Plan 1 Privacy Management Plan

    E-Print Network [OSTI]

    University of Technology, Sydney

    Privacy Management Plan 1 Privacy Management Plan Abstract The Privacy Management Plan outlines how Impact Assessment Tool (.docm) (staff only) Records Management Vice-Chancellor's Directive Handling Management Plan 2 Legislation Privacy and Personal Information Protection Act 1998 (NSW) (PPIPIA) Health

  3. McDonnell 40-kW Giromill Wind System. Phase II. Fabrication and test

    SciTech Connect (OSTI)

    Brulle, R

    1980-06-01

    A 40 kW vertical axis windmill called a ''Giromill'' was fabricated, erected, and tested. The system design is described as well as some design changes made during fabrication. Manufacturing cost estimates are updated. Fabrication of the turbine blades, support arms, and fixed and rotating tower is described as well as the tests. Testing included control systems acceptance tests; Giromill system acceptance tests; structural, mechanical, control system and electric generation operational tests; and performance tests connected to the utility grid. (LEW)

  4. Recommended Underground Test Area Activity Reference Documents

    National Nuclear Security Administration (NNSA)

    Rainier MesaShoshone Mountain Rev 0, Nevada Test Site, Nevada, DOENV-1031, December 2004. (838783) o Phase II Corrective Action Investigation Plan for Corrective Action Units...

  5. Acceptability-Oriented Computing Martin Rinard

    E-Print Network [OSTI]

    Rinard, Martin

    Engineering]: Requirements/Specifications; D.2.3 [Software Engineering]: Coding Tools and Tech- niques; D.2.3 [Software Engineering]: Software/Program Verifi- cation; D.2.3 [Software Engineering]: Testing and Debugging demands for more useful or usable computer software. In the future, several trends will increase the pres

  6. Waste acceptance criteria for the Waste Isolation Pilot Plant

    SciTech Connect (OSTI)

    NONE

    1996-04-01

    The Waste Isolation Pilot Plant (WIPP) Waste Acceptance Criteria (WAC), DOE/WIPP-069, was initially developed by a U.S. Department of Energy (DOE) Steering Committee to provide performance requirements to ensure public health and safety as well as the safe handling of transuranic (TRU) waste at the WIPP. This revision updates the criteria and requirements of previous revisions and deletes those which were applicable only to the test phase. The criteria and requirements in this document must be met by participating DOE TRU Waste Generator/Storage Sites (Sites) prior to shipping contact-handled (CH) and remote-handled (RH) TRU waste forms to the WIPP. The WIPP Project will comply with applicable federal and state regulations and requirements, including those in Titles 10, 40, and 49 of the Code of Federal Regulations (CFR). The WAC, DOE/WIPP-069, serves as the primary directive for assuring the safe handling, transportation, and disposal of TRU wastes in the WIPP and for the certification of these wastes. The WAC identifies strict requirements that must be met by participating Sites before these TRU wastes may be shipped for disposal in the WIPP facility. These criteria and requirements will be reviewed and revised as appropriate, based on new technical or regulatory requirements. The WAC is a controlled document. Revised/changed pages will be supplied to all holders of controlled copies.

  7. DOE to accept bids for Elk Hills crude

    SciTech Connect (OSTI)

    Not Available

    1992-05-04

    This paper reports that the Department of Energy will accept bids in a reoffering sale covering 53,400 b/d of Elk Hills field oil but later may exercise an option to cut sales volumes and ship 20,000 b/d to Strategic Petroleum Reserve sites in Texas. DOE rejected all 19 bids submitted in an earlier semiannual sale of crude oil from the California naval petroleum reserve, saying they were too low. DOE the, The unique combination of federal and state government policies affecting the movement of oil into and out of the California market has contributed to a situation in which it apparently is very difficult for the government to receive a price for Elk Hills oil that satisfies the minimum price tests that govern the sale of Elk Hills oil. The 12 winning bids in the reoffering sale averaged $13.58/bbl, with bids for the higher quality Stevens zone crude averaging $13.92/bbl, about 67 cents/bbl higher than bids rejected last month. DOE the 20,000 b/d is all local pipelines can ship to the interstate All-American pipeline for transfer to Texas beginning in June.

  8. Consumer Acceptance and Public Policy Consumer Acceptance Group C Breakout Session

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustmentsShirleyEnergyTher i n c i p aDepartmentEnergy comparing LEDCSAC CharterConsumer Acceptance

  9. Applying radiological emergency planning experience to hazardous materials emergency planning within the nuclear industry

    SciTech Connect (OSTI)

    Foltman, A.; Newsom, D.; Lerner, K.

    1988-01-01

    The nuclear industry has extensive radiological emergency planning (REP) experience that is directly applicable to hazardous materials emergency planning. Recently, the Feed Materials Production Center near Cincinnati, Ohio, successfully demonstrated such application. The REP experience includes conceptual bases and standards for developing plans that have been tested in hundreds of full-scale exercises. The exercise program itself is also well developed. Systematic consideration of the differences between chemical and radiological hazards shows that relatively minor changes to the REP bases and standards are necessary. Conduct of full-scale, REP-type exercises serves to test the plans, provide training, and engender confidence and credibility.

  10. IEEE COMMUNICATIONS LETTERS, ACCEPTED FOR PUBLICATION 1 Planning of Cellular Networks Enhanced by Energy Harvesting

    E-Print Network [OSTI]

    Langendoen, Koen

    significantly reducing capital and operational expenditure (CAPEX and OPEX, respectively). Therefore, in- spired that the proposed heuristic brings CAPEX and OPEX savings in comparison to traditional network deployment methods

  11. Microsoft Word - final financial plan v4 edits accepted.doc

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantityBonneville Power Administration wouldMass map shines light on77 PAGE OFDetection ofOctober 28,Catastrophicthe NationalFINANCIAL

  12. DOE Does Not Accept SPR Bids and Suspends Plans for Future Purchases |

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustmentsShirleyEnergy A plug-in electric vehicle10 DOEEnvironmentalwith Recovery Act

  13. Structural acceptance criteria Remote Handling Building Tritium Extraction Facility

    SciTech Connect (OSTI)

    Mertz, G.

    1999-12-16

    This structural acceptance criteria contains the requirements for the structural analysis and design of the Remote Handling Building (RHB) in the Tritium Extraction Facility (TEF). The purpose of this acceptance criteria is to identify the specific criteria and methods that will ensure a structurally robust building that will safely perform its intended function and comply with the applicable Department of Energy (DOE) structural requirements.

  14. Mature and Transfer Student Guide Accept Your Offer of

    E-Print Network [OSTI]

    Lennard, William N.

    Mature and Transfer Student Guide #12;Accept Your Offer of Admission to Western's Best Student Experience By offering diverse programs, a flexible curriculum, world-renowned facilities days April 9-30 · Final exams Page 2 | Mature and Transfer Student Guide #12;Step 1 accept Your offer

  15. SAMPLE LETTER ACCEPTING OFFER #1 October 10, 2014

    E-Print Network [OSTI]

    Shyu, Mei-Ling

    #12;SAMPLE LETTER ACCEPTING OFFER #1 NAME ADDRESS TELEPHONE EMAIL October 10, 2014 Mr. Richard 20000 Dear Mr. Cunningham: Thank you for your offer of summer employment with the Civil Rights Division of the United States Department of Justice. I am pleased to accept your offer at a salary of $1,200.00 per week

  16. March 25, 2011 Acceptance of donations for the Tohoku Earthquake

    E-Print Network [OSTI]

    Yamamoto, Hirosuke

    March 25, 2011 Acceptance of donations for the Tohoku Earthquake Director, Headquarters The University of Tokyo has established the following bank account to accept donations for the relief of victims of the March 11 Tohoku Earthquake. Donations will be sent to the affected area through the local governments

  17. Introduction Result Bibliography Accepted Elasticity in Local Arithmetic

    E-Print Network [OSTI]

    Ponomarenko, Vadim

    Introduction Result Bibliography Accepted Elasticity in Local Arithmetic Congruence Monoids Vadim, 2014 http://www-rohan.sdsu.edu/~vadim/ accepted-talk.pdf #12;Introduction Result Bibliography Shameless one property, in the one class not yet understood, called "local". gcd(a, b) = p i.e. a = p, b = pn

  18. Plan for characterization of K Basin Spent Nuclear Fuel and sludge. Revision 1

    SciTech Connect (OSTI)

    Lawrence, L.A.

    1995-10-05

    This plan outlines a Characterization Program that provides the necessary data to support the Integrated Process Strategy scope and schedules for the Spent Nuclear Fuel (SNF) and sludge stored in the Hanford K Basins. The plan is driven by the schedule to begin fuel transfer by December 1997. The program is structured for 4 years (i.e., FY 1995 through FY 1998) and is limited to in-situ and laboratory examinations of the SNF and sludge in the K East and K West Basins. In order to assure the scope and schedule of the Characterization Program fully supports the Integrated Process Strategy, key project management has approved the plan. The intent of the program is to provide bounding behavior for the fuel, and acceptability for the transfer of the sludge to the Double Shell Tanks. Fuel examinations are based on two shipping compains from the K West Basin and one from the K East Basin with coincident sludge sampling campaings for the associated canister sludge. Sampling of the basin floor and pit sludge will be conducted independent of the fuel and canister sludge shipping activities. Fuel behavior and properties investigated in the laboratory include physical condition, hydride and oxide content, conditioning testing, oxidation kinetics, and dry storage behavior. These laboratory examinations are expected to provide the necessary data to establish or confirm fuel conditioning process limits and support safety analysis. Sludge laboratory examinations include measurement of quantity and content, measurement of properties for equipment design and recovery process limits and support safety analysis. Sludge laboratory examinations include measurement of quantity and content, measurement of properties for equipment design and recovery precesses, tank farm acceptance, simulant development, measurement of corrosion products, and measurements of drying behavior.

  19. Accepted for Presentation at IEEE Power Engineering Society 2006 General Meeting, Montreal , Quebec, June 18-22, 2006 Abstract--This paper presents experimental results associated

    E-Print Network [OSTI]

    Operations and Planning, Power System Visualization, 3D, Human Factors I. INTRODUCTION Power system analysis is to present the results of human factor experiments comparing 2D versus 3D power system one-linAccepted for Presentation at IEEE Power Engineering Society 2006 General Meeting, Montreal , Quebec

  20. Hanford Site Development Plan

    SciTech Connect (OSTI)

    Rinne, C.A.; Curry, R.H.; Hagan, J.W.; Seiler, S.W.; Sommer, D.J. ); Yancey, E.F. )

    1990-01-01

    The Hanford Site Development Plan (Site Development Plan) is intended to guide the short- and long-range development and use of the Hanford Site. All acquisition, development, and permanent facility use at the Hanford Site will conform to the approved plan. The Site Development Plan also serves as the base document for all subsequent studies that involve use of facilities at the Site. This revision is an update of a previous plan. The executive summary presents the highlights of the five major topics covered in the Site Development Plan: general site information, existing conditions, planning analysis, Master Plan, and Five-Year Plan. 56 refs., 67 figs., 31 tabs.

  1. School of Nursing MSN/PhD Career Plans Survey

    E-Print Network [OSTI]

    Plotkin, Joshua B.

    % of respondents accepted positions in the Delaware Valley area. Adult Acute Care Nurse Practitioner Doylestown, Bethesda, MD* Average Salary: $98,200 Salary Range: $90,000 - $120,000 Adult Health Nurse Practitioner1 School of Nursing MSN/PhD Career Plans Survey Class of 2011 RESPONSE RATE Master's degrees given

  2. School of Nursing MSN/PhD Career Plans Survey

    E-Print Network [OSTI]

    Plotkin, Joshua B.

    % Continuing Current 29% Still Seeking 13% #12;POSITIONS ACCEPTED BY PROGRAM Adult Acute Care Nurse IV, Philadelphia, PA Adult Health Nurse Practitioner Hospital of the University of PennsylvaniaSchool of Nursing MSN/PhD Career Plans Survey Class of 2009 This report summarizes

  3. Eligibility for GT Housing All applicants must have been accepted to Georgia Tech and accepted their offer of admission

    E-Print Network [OSTI]

    Li, Mo

    Eligibility for GT Housing All applicants must have been accepted to Georgia Tech and accepted their offer of admission before they can apply for Georgia Tech Housing. Applicants must be at least 16 years of age on the date of application for Georgia Tech Housing. Applicants over 29 years of age must work

  4. Wesbrook Place Neighbourhood Plan

    E-Print Network [OSTI]

    .4 The Approach to Plan Making 1.4.1 Planning Objectives that Support the University Vision 1.4.2 Planning Objectives from Guiding Land Use Planning Documents 1.4.3 Planning Objectives from Public Consultation 1.4.5 Interface with Green Academic Lands 2.5 Circulation and Transportation 2.5.1 Transportation Objectives 2

  5. 2011 Strategic Plan Computing Services 2011 Strategic Plan 2

    E-Print Network [OSTI]

    Spirtes, Peter

    2011 Strategic Plan #12;Computing Services 2011 Strategic Plan 2 #12;3 Computing Services 2011 Strategic Plan Contents Introduction ................................................................................................................ 7 The 2011 Strategic Plan

  6. DRAFT Fifteenmile Management Plan 5. Fifteenmile Subbasin Management Plan

    E-Print Network [OSTI]

    DRAFT Fifteenmile Management Plan 5. Fifteenmile Subbasin Management Plan DRAFT May 25 2004 Group 5. FIFTEENMILE SUBBASIN MANAGEMENT PLAN Management Plans

  7. Plan Merging & Plan Reuse As Satis ability

    E-Print Network [OSTI]

    Mali, Amol D.

    Plan Merging & Plan Reuse As Satis#12;ability #3; Amol Dattatraya Mali Dept. of Elect. Engg. & Computer Science, P.O.Box 784 University of Wisconsin, Milwaukee, WI 53201, USA mali@miller.cs.uwm.edu July

  8. Full-Scale Accident Testing in Support of Used Nuclear Fuel Transportation.

    SciTech Connect (OSTI)

    Durbin, Samuel G.; Lindgren, Eric R.; Rechard, Rob P.; Sorenson, Ken B.

    2014-09-01

    The safe transport of spent nuclear fuel and high-level radioactive waste is an important aspect of the waste management system of the United States. The Nuclear Regulatory Commission (NRC) currently certifies spent nuclear fuel rail cask designs based primarily on numerical modeling of hypothetical accident conditions augmented with some small scale testing. However, NRC initiated a Package Performance Study (PPS) in 2001 to examine the response of full-scale rail casks in extreme transportation accidents. The objectives of PPS were to demonstrate the safety of transportation casks and to provide high-fidelity data for validating the modeling. Although work on the PPS eventually stopped, the Blue Ribbon Commission on America’s Nuclear Future recommended in 2012 that the test plans be re-examined. This recommendation was in recognition of substantial public feedback calling for a full-scale severe accident test of a rail cask to verify evaluations by NRC, which find that risk from the transport of spent fuel in certified casks is extremely low. This report, which serves as the re-assessment, provides a summary of the history of the PPS planning, identifies the objectives and technical issues that drove the scope of the PPS, and presents a possible path for moving forward in planning to conduct a full-scale cask test. Because full-scale testing is expensive, the value of such testing on public perceptions and public acceptance is important. Consequently, the path forward starts with a public perception component followed by two additional components: accident simulation and first responder training. The proposed path forward presents a series of study options with several points where the package performance study could be redirected if warranted.

  9. STRATEGIC PLAN PREAMBLE:...................................................................................... 6

    E-Print Network [OSTI]

    2014­2019 STRATEGIC PLAN #12; 2 CONTENTS PREAMBLE.......................................... 29 THE STRATEGIC PLANNING PROCESS............................................. 30 Topic Committees................................................................ 32 OLD DOMINION UNIVERSITY STRATEGIC PLAN 2014-2019 GOALS, OBJECTIVES AND ACTION ITEMS

  10. Using Simulation for Assessing the Real Impact of Test Coverage on Defect Lionel C. Briand

    E-Print Network [OSTI]

    Carleton University

    AT acceptance test IT integration test UT unit test Notation dc defect coverage tc test coverage ti test coverage measures) Test coverage is measured as the percentage of constructs - as defined by the coverageUsing Simulation for Assessing the Real Impact of Test Coverage on Defect Coverage Lionel C. Briand

  11. ACQUISITION PLANNING | Department of Energy

    Energy Savers [EERE]

    ACQUISITION PLANNING ACQUISITION PLANNING ACQUISITION PLANNING More Documents & Publications ACQUISITION PLANNING Attachment FY2011-13 Attachment FY2011-40(3)...

  12. Neutral-beam development plan, FY 1982-1987

    SciTech Connect (OSTI)

    Not Available

    1981-09-01

    The following chapters are included: (1) status of BNL negative ion source development, (2) source development program plan, (3) status of beam transport and acceleration, (4) accelerator development program plan, (5) neutralizer concepts, (6) neutralization program plan, (7) neutral beam systems, (8) test facilities, (9) program milestones and time schedules, (10) organization and Grumman participation, and (11) funding tables. (MOW)

  13. STORM WATER POLLUTION PREVENTION PLAN (RISK LEVEL 1)

    E-Print Network [OSTI]

    Eisen, Michael

    STORM WATER POLLUTION PREVENTION PLAN (RISK LEVEL 1) for BUILDING 90 USER TEST BED FACILITY.G., GEOLOGIST/QSD (530) 222-4339 SWPPP Preparation Date: JUNE 10, 2012 #12;Storm Water Pollution Prevention Plan) 222-4339 Name and Title Telephone Number #12;Storm Water Pollution Prevention Plan Building 90 User

  14. ASSESSING THE PERFORMANCE OF HUMAN-AUTOMATION COLLABORATIVE PLANNING SYSTEMS

    E-Print Network [OSTI]

    Cummings, Mary "Missy"

    to perform high-level task planning for deck operations on United States Naval aircraft carriers is utilized in a testing program that utilizes three different planning conditions, with a focus on validat- ingASSESSING THE PERFORMANCE OF HUMAN- AUTOMATION COLLABORATIVE PLANNING SYSTEMS by Jason C. Ryan B. S

  15. Routine Radiological Environmental Monitoring Plan. Volume 1

    SciTech Connect (OSTI)

    Bechtel Nevada

    1999-12-31

    The U.S. Department of Energy manages the Nevada Test Site in a manner that meets evolving DOE Missions and responds to the concerns of affected and interested individuals and agencies. This Routine Radiological Monitoring Plan addressess complicance with DOE Orders 5400.1 and 5400.5 and other drivers requiring routine effluent monitoring and environmental surveillance on the Nevada Test Site. This monitoring plan, prepared in 1998, addresses the activities conducted onsite NTS under the Final Environmental Impact Statement and Record of Decision. This radiological monitoring plan, prepared on behalf of the Nevada Test Site Landlord, brings together sitewide environmental surveillance; site-specific effluent monitoring; and operational monitoring conducted by various missions, programs, and projects on the NTS. The plan provides an approach to identifying and conducting routine radiological monitoring at the NTS, based on integrated technical, scientific, and regulatory complicance data needs.

  16. Report: Strategic Planning Impacts

    Office of Environmental Management (EM)

    Strategic Planning Impacts September 30, 2009 Submitted by the EMAB ARRA Implementation and Oversight Subcommittee Background: EM plans to use the influx of stimulus funding from...

  17. Digital Data Management Plans

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Digital Data Management Plans Digital Data Management Plans Investigating the field of high energy physics through experiments that strengthen our fundamental understanding of...

  18. LDRD Program Plan master

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    LDRD plan and supporting documents: our LDRD Proposal Guidance, Proposal Template, and Budget Template. The final plan will be subject to DOE site office for concurrence. LDRD...

  19. Plans, Updates, Regulatory Documents

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Permit for Storm Water Documents Individual Permit NPDES No. NM0030759 (pdf) Storm Water Plans Site Discharge Pollution Prevention Plan (SDPPP) Volume 1 - Los AlamosPueblo...

  20. SchlumbergerRES/Field-Test-Plan.PPT/18/06/00/1 Field Test Plan Michigan

    E-Print Network [OSTI]

    /06/00/8 Imaging TargetsImaging TargetsImaging TargetsImaging Targets 0 - 330 - 660 - 1500 - 1600 Depth in m 500 m (fractured Antrim Shales) Burch Well Shell Well Stech Well T 3 : Glacial Till Multi-C. Statics #12;9 La

  1. Testing Monotonicity Oded Goldreich Shafi Goldwassery Eric Lehmany Dana Ronyz

    E-Print Network [OSTI]

    Goldreich, Oded

    to query an unknown function f : f0; 1gn 7! f0; 1gat arguments of its choice, the test always accepts function. 1.1 Perspective Property Testing, as explicitly defined by Rubinfeld and Sudan [RS96 in this context are actually codeword tests (in this case of BCH codes), and that such tests can be defined

  2. VERIFICATION AND DIAGNOSIS OF TESTING PREORDER 4.1. Introduction

    E-Print Network [OSTI]

    von Bochmann, Gregor

    specifications are testing equivalent: first the two specifications are transformed into acceptance graphs, which92], although similar to the testing equivalence and the testing preorder defined in [Brin87CHAPTER 4 VERIFICATION AND DIAGNOSIS OF TESTING PREORDER 4.1. Introduction In protocol engineering

  3. Three Theorems Regarding Testing Graph Properties*

    E-Print Network [OSTI]

    Trevisan, Luca

    Three Theorems Regarding Testing Graph Properties* Oded Goldreich,1, Luca Trevisan2 1 Department-mail: luca@eecs.berkeley.edu Received 9 December 2001; accepted 18 September 2002 DOI 10.1002/rsa.10078 ABSTRACT: Property testing is a relaxation of decision problems in which it is required to distinguish YES

  4. Author's Accepted Manuscript ORBIT-CENTERED ATMOSPHERIC DENSITY

    E-Print Network [OSTI]

    Wohlberg, Brendt

    solar and geomagnetic activities and different prediction windows. Compar- ison with previouslyAuthor's Accepted Manuscript ORBIT-CENTERED ATMOSPHERIC DENSITY PREDICTION USING ARTIFICIAL NEURAL Shoemaker, Riccardo Bevilacqua, ORBIT-CENTERED ATMOSPHERIC DENSITY PREDICTION USING ARTIFICIAL NEURAL

  5. EM Waste Acceptance Product Specification (WAPS) for Vitrified...

    Office of Environmental Management (EM)

    EM Waste Acceptance Product Specification (WAPS) for Vitrified High-Level Waste Forms Presentation to the HLW Corporate Board July 24, 2008 By Tony KlukKen Picha 2 Background *...

  6. Energy dependence of acceptance-corrected dielectron excess mass...

    Office of Scientific and Technical Information (OSTI)

    Energy dependence of acceptance-corrected dielectron excess mass spectrum at mid-rapidity in Au+Au collisions at sNN19.6 and 200 GeV Citation Details In-Document Search Title:...

  7. CHANGE IN ACCEPTABLE ID DOCUMENTS FOR JLAB ACCESS:

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    JLAB ACCESS: The REAL ID Act (Public Law 109-13) now determines which state driver's license can be presented and accepted as a valid ID document for access to Jefferson Lab. The...

  8. Idaho CERCLA Disposal Facility Complex Waste Acceptance Criteria

    SciTech Connect (OSTI)

    W. Mahlon Heileson

    2006-10-01

    The Idaho Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) Disposal Facility (ICDF) has been designed to accept CERCLA waste generated within the Idaho National Laboratory. Hazardous, mixed, low-level, and Toxic Substance Control Act waste will be accepted for disposal at the ICDF. The purpose of this document is to provide criteria for the quantities of radioactive and/or hazardous constituents allowable in waste streams designated for disposal at ICDF. This ICDF Complex Waste Acceptance Criteria is divided into four section: (1) ICDF Complex; (2) Landfill; (3) Evaporation Pond: and (4) Staging, Storage, Sizing, and Treatment Facility (SSSTF). The ICDF Complex section contains the compliance details, which are the same for all areas of the ICDF. Corresponding sections contain details specific to the landfill, evaporation pond, and the SSSTF. This document specifies chemical and radiological constituent acceptance criteria for waste that will be disposed of at ICDF. Compliance with the requirements of this document ensures protection of human health and the environment, including the Snake River Plain Aquifer. Waste placed in the ICDF landfill and evaporation pond must not cause groundwater in the Snake River Plain Aquifer to exceed maximum contaminant levels, a hazard index of 1, or 10-4 cumulative risk levels. The defined waste acceptance criteria concentrations are compared to the design inventory concentrations. The purpose of this comparison is to show that there is an acceptable uncertainty margin based on the actual constituent concentrations anticipated for disposal at the ICDF. Implementation of this Waste Acceptance Criteria document will ensure compliance with the Final Report of Decision for the Idaho Nuclear Technology and Engineering Center, Operable Unit 3-13. For waste to be received, it must meet the waste acceptance criteria for the specific disposal/treatment unit (on-Site or off-Site) for which it is destined.

  9. Solid Waste Assurance Program Implementation Plan

    SciTech Connect (OSTI)

    Irons, L.G.

    1995-06-19

    On June 6, 1995, a waiver to Hanford Site Solid Waste Acceptance Criteria, was approved by the US Department of Energy Richland Operations Office (RL) to replace the low-level, mixed, and transuranic (TRU) generator assessment programs with the Solid Waste Assurance Program (SWAP). This is associated with a waiver that was approved on March 16, 1995 to replace the Storage/Disposal Approval Record (SDAR) requirements with the Waste Specification System (WSS). This implementation plan and the SWAP applies to Solid Waste Disposal (SWD) functions, facilities, and personnel who perform waste acceptance, verification, receipt, and management functions of dangerous, radioactive, and mixed waste from on- and off-site generators who ship to or within the Hanford Site for treatment, storage, and/or disposal (TSD) at SWD TSD facilities.

  10. Performance Demonstration Program Plan for Nondestructive Assay of Boxed Wastes for the TRU Waste Characterization Program

    SciTech Connect (OSTI)

    Carlsbad Field Office

    2001-01-31

    The Performance Demonstration Program (PDP) for nondestructive assay (NDA) consists of a series of tests to evaluate the capability for NDA of transuranic (TRU) waste throughout the Department of Energy (DOE) complex. Each test is termed a PDP cycle. These evaluation cycles provide an objective measure of the reliability of measurements obtained from NDA systems used to characterize the radiological constituents of TRU waste. The primary documents governing the conduct of the PDP are the Waste Acceptance Criteria for the Waste Isolation Pilot Plant (WAC; DOE 1999a) and the Quality Assurance Program Document (QAPD; DOE 1999b). The WAC requires participation in the PDP; the PDP must comply with the QAPD and the WAC. The WAC contains technical and quality requirements for acceptable NDA. This plan implements the general requirements of the QAPD and applicable requirements of the WAC for the NDA PDP for boxed waste assay systems. Measurement facilities demonstrate acceptable performance by the successful testing of simulated waste containers according to the criteria set by this PDP Plan. Comparison among DOE measurement groups and commercial assay services is achieved by comparing the results of measurements on similar simulated waste containers reported by the different measurement facilities. These tests are used as an independent means to assess the performance of measurement groups regarding compliance with established quality assurance objectives (QAO’s). Measurement facilities must analyze the simulated waste containers using the same procedures used for normal waste characterization activities. For the boxed waste PDP, a simulated waste container consists of a modified standard waste box (SWB) emplaced with radioactive standards and fabricated matrix inserts. An SWB is a waste box with ends designed specifically to fit the TRUPACT-II shipping container. SWB’s will be used to package a substantial volume of the TRU waste for disposal. These PDP sample components are distributed to the participating measurement facilities that have been designated and authorized by the Carlsbad Field Office (CBFO). The NDA Box PDP materials are stored at these sites under secure conditions to protect them from loss, tampering, or accidental damage. Using removable PDP radioactive standards, isotopic activities in the simulated waste containers are varied to the extent possible over the range of concentrations anticipated in actual waste characterization situations. Manufactured matrices simulate expected waste matrix configurations and provide acceptable consistency in the sample preparation process at each measurement facility. Analyses that are required by the Waste Isolation Pilot Plant (WIPP) to demonstrate compliance with various regulatory requirements and that are included in the PDP may only be performed by measurement facilities that demonstrate acceptable performance in the PDP. These analyses are referred to as WIPP analyses, and the wastes on which they are performed are referred to as WIPP wastes in this document.

  11. SU-E-T-580: Comparison of Cervical Carcinoma IMRT Plans From Four Commercial Treatment Planning Systems (TPS)

    SciTech Connect (OSTI)

    Cao, Y; Li, R; Chi, Z; Zhu, S

    2014-06-01

    Purpose: Different treatment planning systems (TPS) use different treatment optimization and leaf sequencing algorithms. This work compares cervical carcinoma IMRT plans optimized with four commercial TPSs to investigate the plan quality in terms of target conformity and delivery efficiency. Methods: Five cervical carcinoma cases were planned with the Corvus, Monaco, Pinnacle and Xio TPSs by experienced planners using appropriate optimization parameters and dose constraints to meet the clinical acceptance criteria. Plans were normalized for at least 95% of PTV to receive the prescription dose (Dp). Dose-volume histograms and isodose distributions were compared. Other quantities such as Dmin(the minimum dose received by 99% of GTV/PTV), Dmax(the maximum dose received by 1% of GTV/PTV), D100, D95, D90, V110%, V105%, V100% (the volume of GTV/PTV receiving 110%, 105%, 100% of Dp), conformity index(CI), homogeneity index (HI), the volume of receiving 40Gy and 50 Gy to rectum (V40,V50) ; the volume of receiving 30Gy and 50 Gy to bladder (V30,V50) were evaluated. Total segments and MUs were also compared. Results: While all plans meet target dose specifications and normal tissue constraints, the maximum GTVCI of Pinnacle plans was up to 0.74 and the minimum of Corvus plans was only 0.21, these four TPSs PTVCI had significant difference. The GTVHI and PTVHI of Pinnacle plans are all very low and show a very good dose distribution. Corvus plans received the higer dose of normal tissue. The Monaco plans require significantly less segments and MUs to deliver than the other plans. Conclusion: To deliver on a Varian linear-accelerator, the Pinnacle plans show a very good dose distribution. Corvus plans received the higer dose of normal tissue. The Monaco plans have faster beam delivery.

  12. Acceptance by proxy : analyzing perceptions of hydraulic fracturing to better understand public acceptance for geologic storage of carbon dioxide

    E-Print Network [OSTI]

    Wolff, Joshua Michael

    2015-01-01

    Carbon capture and storage (CCS) represents an important pathway for reducing greenhouse gas emissions in order to mitigate climate change. However, there is significant uncertainty about how the technology will be accepted ...

  13. Strategic Plan Core strategies

    E-Print Network [OSTI]

    Oxford, University of

    Strategic Plan 2013­18 Vision Priorities Core strategies Enabling strategies #12;Strategic Plan on the Strategic Plan, ensuring that it continues to meet academic needs, enables us to respond to the external the framework for making the Strategic Plan operational at divisional and service level. ©UniversityofOxford #12

  14. Business Services Strategic Plan

    E-Print Network [OSTI]

    Pittendrigh, Barry

    Business Services Strategic Plan 2008-2014 New Synergies: Launching Tomorrow's Leaders Discovery implementation of the University Strategic Plan Analyze, plan, and manage University finances, processes, and contracts in global and strategic partnerships Review existing capital financing plans and the process

  15. Strategic Plan November 2011

    E-Print Network [OSTI]

    Johnson Jr.,, Ray

    Strategic Plan 2012­2016 #12;November 2011 Dear Friends, I am pleased to present the Graduate Center Strategic Plan for 2012­2016. This plan is the result of a broadly consultative process that began in Spring 2010 when I convened the Strategic Planning Council, which included faculty, students, staff

  16. 6 Management Plan Introduction

    E-Print Network [OSTI]

    147 6 Management Plan Introduction The management plan integrates the vision for the White Salmon for restoration of fish and wildlife habitat and populations which form the bulk of the management plan is derived from that input. The scope of the management plan is somewhat narrower than the scope of the assessment

  17. Climate change action plan

    E-Print Network [OSTI]

    Delivery Climate change action plan 2009-2011 #12;2 | Climate change action plan ©istockphoto.com #12;Climate Change Action Plan Climate change action plan | 3 Contents Overview 4 Preface and Introduction 5 Climate change predictions for Scotland 6 The role of forestry 7 Protecting and managing

  18. NevadaTestSiteCMP.pdf | Department of Energy

    Energy Savers [EERE]

    NevadaTestSiteCMP.pdf NevadaTestSiteCMP.pdf NevadaTestSiteCMP.pdf More Documents & Publications CMPforLANL.pdf Sample Project Execution Plan Microsoft Word - PEP-EM-4028.doc...

  19. Quality assurance plan for Final Waste Forms project in support of the development, demonstration, testing and evaluation efforts associated with the Oak Ridge reservation`s LDR/FFCA compliance

    SciTech Connect (OSTI)

    Gilliam, T.M.; Mattus, C.H.

    1994-07-01

    This quality assurance project plan specifies the data quality objectives for Phase I of the Final Waste Forms Project and defines specific measurements and processes required to achieve those objectives. Although the project is funded by the U.S. Department of Energy (DOE), the ultimate recipient of the results is the U.S. Environmental Protection Agency (EPA). Consequently, relevant quality assurance requirements from both organizations must be met. DOE emphasizes administrative structure to ensure quality; EPA`s primary focus is the reproducibility of the generated data. The ten criteria of DOE Order 5700.6C are addressed in sections of this report, while the format used is that prescribed by EPA for quality assurance project plans.

  20. Final Report - LAW Envelope A and B Glass Formulations Testing in Increase Waste Loading. VSL-06R6900-1

    SciTech Connect (OSTI)

    Kruger, Albert A.; Joseph, I.; Muller, I. S.; Gong, W.; Gan, H.; Pegg, I. L.; Matlack, K. S.

    2013-12-03

    This report describes the results of testing specified by the Test Plan VSL-06R6900-1 Rev 0. The work was performed in compliance with quality assurance requirements specified in the Test Plan. Results required by the Test Plan are reported. The test results and this report have been reviewed for correctness, technical adequacy, completeness, and accuracy.