National Library of Energy BETA

Sample records for 685-g par pond

  1. PAR Pond N Roads

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    PAR Pond N Roads 11N Streams 870 Meters N A Vegetation Community D Sandhill Scrub oak/Pine '/ 580 Compartment 56 290 o 290 Soils Soi I Sa-i es and Pha:;e o LaB sc Figure 26-1. Plant COl1ll1lllllities and soils associated with the Sandhills Fire Site Set-Aside Area. 26-5 Set-Aside 26: Sandhills Fire Site

  2. Par Pond vegetation status Summer 1995 -- Summary

    SciTech Connect (OSTI)

    Mackey, H.E. Jr.; Riley, R.S.

    1996-01-01

    The water level of Par Pond was lowered approximately 20 feet in mid-1991 in order to protect downstream residents from possible dam failure suggested by subsidence on the downstream slope of the dam and to repair the dam. This lowering exposed both emergent and nonemergent macrophyte beds to drying conditions resulting in extensive losses. A survey of the newly emergent, shoreline aquatic plant communities of Par Pond began in June 1995, three months after the refilling of Par Pond to approximately 200 feet above mean sea level. These surveys continued in July, September, and late October, 1995. Communities similar to the pre-drawdown, Par Pond aquatic plant communities are becoming re-established. Emergent beds of maidencane, lotus, waterlily, and watershield are extensive and well developed. Cattail occurrence continued to increase during the summer, but large beds common to Par Pond prior to the drawdown have not formed. Estimates from SPOT HRV, remote sensing satellite data indicated that as much as 120 hectares of emergent wetlands vegetation may have been present along the Par Pond shoreline by early October, 1995. To track the continued development of macrophytes in Par Pond, future surveys throughout 1996 and 1997, along with the continued evaluation of satellite data to map the areal extent of the macrophyte beds of Par Pond, are planned.

  3. Quality control summary report for the RFI/RI assessment of the submerged sediment core samples taken at Par Pond, Pond C, and L-Lake

    SciTech Connect (OSTI)

    Koch, J. II

    1996-12-01

    This report presents a summary of the sediment characterization performed under the direction of the Westinghouse Savannah River Company`s (WSRC) Environmental Protection Department/Environmental Monitoring Section (EPD/EMS) in support of Par Pond, Pond C, and L- Lake. This characterization will be a screening study and will enable the Environmental Sciences Section (ESS) to develop a defensible contaminants of concern list for more extensive characterization of the Par Pond, Pond C, and L-Lake.

  4. H-Area, K-Area, and Par Pond Sewage Sludge Application Sites groundwater monitoring report. Third quarter 1994

    SciTech Connect (OSTI)

    1995-01-01

    Groundwater samples from the three wells at the H-Area Sewage Sludge Application Site (HSS wells) are analyzed quarterly for constituents as required by South Carolina Department of Health and Environmental Control (SCDHEC) Construction Permit 12,076. Samples from the three wells at the K-Area Sewage Sludge Application Site (KSS wells) and the three wells at the quired by SCDHEC Construction Permit 13,173. All samples are also analyzed as requested for other constituents as part of the Savannah River Site (SRS) Groundwater Monitoring Program. Annual analyses for other constituents, primarily metals, also are required by the permits. No constituents exceeded the SCDHEC final Primary Drinking Water Standard in any well from the H-Area, K-Area, and Par Pond Sewage Sludge Application Sites. Aluminum and iron were above Flag 2 criteria in one or more wells in the three sites during third quarter 1994. These constituents were not analyzed during the previous quarter. Third quarter results are similar to results for first quarter 1994.

  5. East Pond West Pond South Pond South Pond Southwest Pond

    Office of Legacy Management (LM)

    West Pond South Pond South Pond Southwest Pond Pond 5 15-M03D 14.97 15-M14D 14.65 15-M27D 14.1 15-M32D 14.53 18-0507 14.28 18-0509 14.3 18-0520 14.06 18-0523 14.22 20-0502 14.36 20-M005 14.64 20-M007 14.72 20-M011 14.9 20-M023 14.39 20-M028 14.81 20-M036 14.6 20-M40D 11.5 20-M41D 14.11 20-M059 14.53 12-0555C 13.55 12-0558C 13.6 12-0543 12.86 12-0520 14.45 15-0506 13.47 12-0514 13.44 12-0516 13.84 12-0522 14.45 12-0524 14.33 12-RW02 14.36 15-0518 13.92 15-0534 13.59 15-0535 14.21 18-0508 14.4

  6. PARS II

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... September 9, 2010 (V1.1) PARS II 103 Project Updating and Reporting Page 49 4. Click to begin entering funding values. 5. Click + sign to expand detail for OPC, TEC, and UND, if ...

  7. CX-010121: Categorical Exclusion Determination

    Office of Energy Efficiency and Renewable Energy (EERE)

    685-G Par Pond and 686-G L-Lake Sluice Gate Conduit Cleanouts/Inspections CX(s) Applied: B1.3 Date: 03/21/2013 Location(s): South Carolina Offices(s): Savannah River Operations Office

  8. CX-011819: Categorical Exclusion Determination

    Office of Energy Efficiency and Renewable Energy (EERE)

    685-G PAR Pond and 686-G L-Lake Sluice Gate Conduit Cleanouts/Inspections CX(s) Applied: B1.3 Date: 01/27/2014 Location(s): South Carolina Offices(s): Savannah River Operations Office

  9. Easton Pond Business Center | Open Energy Information

    Open Energy Info (EERE)

    Easton Pond Business Center Jump to: navigation, search Name Easton Pond Business Center Facility Easton Pond Business Center Sector Wind energy Facility Type Small Scale Wind...

  10. PARS II TRAINING

    Broader source: Energy.gov [DOE]

    PARS II 102 Monthly Updating and Reporting Training Workbook (PARS II Release 1.1), September 13, 2010.

  11. PARS II TRAINING

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    13, 2010 (V1.1) PARS II 102 Monthly Updating and Reporting i Project Assessment and Reporting System PARS II 102 Monthly Updating and Reporting Training Workbook (PARS II Release ...

  12. PARS II Course Descriptions

    Broader source: Energy.gov [DOE]

    Sign up for PARS 102 or PARS 103, depending on your project assessment role and function.  PARS 104 will be offered to site contractors as part of Dekker's Contractor deployment training.

  13. 216-B-3 expansion ponds closure plan

    SciTech Connect (OSTI)

    Not Available

    1994-10-01

    This document describes the activities for clean closure under the Resource Conservation and Recovery Act of 1976 (RCRA) of the 216-B-3 Expansion Ponds. The 216-B-3 Expansion Ponds are operated by the US Department of Energy, Richland Operations Office (DOE-RL) and co-operated by Westinghouse Hanford Company (Westinghouse Hanford). The 216-B-3 Expansion Ponds consists of a series of three earthen, unlined, interconnected ponds that receive waste water from various 200 East Area operating facilities. The 3A, 3B, and 3C ponds are referred to as Expansion Ponds because they expanded the capability of the B Pond System. Waste water (primarily cooling water, steam condensate, and sanitary water) from various 200 East Area facilities is discharged to the Bypass pipe (Project X-009). Water discharged to the Bypass pipe flows directly into the 216-B-3C Pond. The ponds were operated in a cascade mode, where the Main Pond overflowed into the 3A Pond and the 3A Pond overflowed into the 3C Pond. The 3B Pond has not received waste water since May 1985; however, when in operation, the 3B Pond received overflow from the 3A Pond. In the past, waste water discharges to the Expansion Ponds had the potential to have contained mixed waste (radioactive waste and dangerous waste). The radioactive portion of mixed waste has been interpreted by the US Department of Energy (DOE) to be regulated under the Atomic Energy Act of 1954; the dangerous waste portion of mixed waste is regulated under RCRA.

  14. Across the Pond Newsletters | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Services Communication & Engagement International Programs Across the Pond ... Communication & Engagement Intergovernmental Programs EMAB EM SSAB Tribal Programs ...

  15. PARS II Training Materials | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    attachments, and running standard, pre-built reports. PARS 102 Presentation PARS 102 Workbook PARS 103 - Updating Projects and Reporting Introduction to PARS II, finding and...

  16. PARS II Training Materials

    Broader source: Energy.gov [DOE]

    PARS II presentation hand-outs and step-by-step "how to" exercises for each course are available for download. Users who are attending Web classes should download these documents prior to attending...

  17. PARS IIe | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    IIe PARS IIe Project Assessment & Reporting System (PARS IIe) Office of Project Management Oversight & Assessments (PM) manages and operates Project Assessment and Reporting System (PARS IIe) - the Department's official "System of Record" for project information, documentation, and performance data of all non-IT Capital Asset Acquisitions. It is used by Federal and contractor personnel across the nation to record and track the progress of construction and environmental cleanup

  18. PARS II 104 Contractor Monthly Upload | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    104 Contractor Monthly Upload PARS II 104 Contractor Monthly Upload PDF icon PARS II 104 Contractor Monthly Upload More Documents & Publications PARS II TRAINING PARS II Training ...

  19. PARS IIe Training | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    IIe Training PARS IIe Training PARS IIe has adopted alternative training strategy that increases training efficiency while reducing time commitment required from our users. We no ...

  20. Excavations in Hanford ponds, cribs, or ditches

    SciTech Connect (OSTI)

    Ryan, G.W., Westinghouse Hanford

    1996-09-20

    This document supports the development and presentation of the following accident scenario in the TWRS Final Safety Analysis Report: Unplanned Excavation/Drilling in Pond/Ditch/Crib. The calculations needed to quantify the risk associated with this accident scenario are included within.

  1. PARS IIe Account Request | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    PARS IIe Account Request PARS IIe Account Request The account access process for PARS IIe relies on the Department of Energy's iManage system to verify the requestor's identity and to approve his/her request for access to a specific DOE Headquarters system, such as PARS IIe. Upon obtaining access to iManage Employee Self Service (ESS) system, PARS II login can be requested and the PARS IIe Help Desk Administrator will assign a new PARS IIe account to the requestor. Please follow the steps listed

  2. Engineered design of SSC cooling ponds

    SciTech Connect (OSTI)

    Bear, J.B.

    1993-05-01

    The cooling requirements of the SSC are significant and adequate cooling water systems to meet these requirements are critical to the project`s successful operation. The use of adequately designed cooling ponds will provide reliable cooling for operation while also meeting environmental goals of the project to maintain streamflow and flood peaks to preconstruction levels as well as other streamflow and water quality requirements of the Texas Water Commission and the Environmental Protection Agency.

  3. PARS II Training Workbook (Course 103) | Department of Energy

    Energy Savers [EERE]

    PARS II Training Workbook (Course 103) PARS II Training Workbook (Course 103) PARS II 103 Updating Projects and Reporting Training Workbook (PARS II Release 1.1), September, 2010. PDF icon Workbook More Documents & Publications PARS II TRAINING PARS II TRAINING PARS II 104 Contractor Monthly Upload

  4. PARS IIe CUI Training Slides | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    PARS IIe CUI Training Slides PARS IIe CUI Training Slides The PARS IIe has been enhanced with additional capabilities for handling Controlled Unclassified Information (CUI) has ...

  5. Across the Pond Newsletter Issue 4

    Office of Environmental Management (EM)

    Across The Pond 1 DOE-NDA discuss Spent Fuel Shipments Meeting with Dounreay Site Restoration Ltd. on Gap (non-US origin) Material Shipment: Environmental Management (EM) supported a National Nuclear Security Administration (NNSA) led team on a visit to the Dounreay Site, near Thurso, Scotland on July 14-15, 2010. The purpose of the visit was to meet with DSRL representatives on a potential Gap spent fuel (non U.S.- origin) shipment to the US at the Savannah River Site. The EM-HQ representatives

  6. Are surface coal mine sediment ponds working

    SciTech Connect (OSTI)

    Poe, M.L.; Betson, R.P.

    1985-12-09

    Flowrates and storm generated water quality data were collected at sedimentation ponds on four surface mines in the states of Pennsylvania, Maryland, and West Virginia. The water quality data were analyzed for suspended solids and settleable solids content, and particle size distribution. The results were compared to the effluent limitations guidelines for total suspended solids as promulgated under the Clean Water Act for Coal Mining Point Source Category and adopted under the Surface Mine Control and Reclamation Act of 1977 and the resulting state regulatory programs. 3 references, 1 figure, 2 tables.

  7. 2101-M Pond hydrogeologic characterization report

    SciTech Connect (OSTI)

    Chamness, M.A.; Luttrell, S.P.; Bates, D.J.; Martin, W.J.

    1990-09-01

    This report documents information collected by the Pacific Northwest Laboratory {sup (a)} at the request of Westinghouse Hanford Company. Presented in this report is the interpretation of the hydrogeologic environment at the 2101-M Pond, located in the 200-East Area of the Hanford Site. This information and its accompanying interpretation were derived from sampling and testing activities associated with the installation of four ground-water monitoring wells, in addition to data gathered from several previously existing wells. The new monitoring wells were installed as part of a groundwater monitoring program initiated in 1988. The four new monitoring wells were installed around the 2101-M Pond between May 23 and August 27, 1988. Geologic sampling, aquifer testing, and initial ground-water sampling were performed during the installation of these wells. Laboratory analyses of the sediment samples for particle size, calcium carbonate content, and selected natural and contaminant constituents were performed. A full year of quarterly ground-water sampling and the first statistical analysis of background and downgradient data have also been performed. 112 refs., 49 figs., 18 tabs.

  8. Parallel Climate Analysis Toolkit (ParCAT)

    Energy Science and Technology Software Center (OSTI)

    2013-06-30

    The parallel analysis toolkit (ParCAT) provides parallel statistical processing of large climate model simulation datasets. ParCAT provides parallel point-wise average calculations, frequency distributions, sum/differences of two datasets, and difference-of-average and average-of-difference for two datasets for arbitrary subsets of simulation time. ParCAT is a command-line utility that can be easily integrated in scripts or embedded in other application. ParCAT supports CMIP5 post-processed datasets as well as non-CMIP5 post-processed datasets. ParCAT reads and writes standard netCDF files.

  9. Fuel Pond Sludge - Lessons Learned from Initial De-sludging of Sellafield's Pile Fuel Storage Pond - 12066

    SciTech Connect (OSTI)

    Carlisle, Derek; Adamson, Kate

    2012-07-01

    The Pile Fuel Storage Pond (PFSP) at Sellafield was built and commissioned between the late 1940's and early 1950's as a storage and cooling facility for irradiated fuel and isotopes from the two Windscale Pile reactors. The pond was linked via submerged water ducts to each reactor, where fuel and isotopes were discharged into skips for transfer along the duct to the pond. In the pond the fuel was cooled then de-canned underwater prior to export for reprocessing. The plant operated successfully until it was taken out of operation in 1962 when the First Magnox Fuel Storage Pond took over fuel storage and de-canning operations on the site. The pond was then used for storage of miscellaneous Intermediate Level Waste (ILW) and fuel from the UK's Nuclear Programme for which no defined disposal route was available. By the mid 1970's the import of waste ceased and the plant, with its inventory, was placed into a passive care and maintenance regime. By the mid 1990s, driven by the age of the facility and concern over the potential challenge to dispose of the various wastes and fuels being stored, the plant operator initiated a programme of work to remediate the facility. This programme is split into a number of key phases targeted at sustained reduction in the hazard associated with the pond, these include: - Pond Preparation: Before any remediation work could start the condition of the pond had to be transformed from a passive store to a plant capable of complex retrieval operations. This work included plant and equipment upgrades, removal of redundant structures and the provision of a effluent treatment plant for removing particulate and dissolved activity from the pond water. - Canned Fuel Retrieval: Removal of canned fuel, including oxide and carbide fuels, is the highest priority within the programme. Handling and export equipment required to remove the canned fuel from the pond has been provided and treatment routes developed utilising existing site facilities to allow the fuel to be reprocessed or conditioned for long term storage. - Sludge Retrieval: In excess of 300 m{sup 3} of sludge has accumulated in the pond over many years and is made up of debris arising from fuel and metallic corrosion, wind blown debris and bio-organic materials. The Sludge Retrieval Project has provided the equipment necessary to retrieve the sludge, including skip washer and tipper machines for clearing sludge from the pond skips, equipment for clearing sludge from the pond floor and bays, along with an 'in pond' corral for interim storage of retrieved sludge. Two further projects are providing new plant processing routes, which will initially store and eventually passivate the sludge. - Metal Fuel Retrieval: Metal Fuel from early Windscale Pile operations and various other sources is stored within the pond; the fuel varies considerably in both form and condition. A retrieval project is planned which will provide fuel handling, conditioning, sentencing and export equipment required to remove the metal fuel from the pond for export to on site facilities for interim storage and disposal. - Solid Waste Retrieval: A final retrieval project will provide methods for handling, retrieval, packaging and export of the remaining solid Intermediate Level Waste within the pond. This includes residual metal fuel pieces, fuel cladding (Magnox, aluminium and zircaloy), isotope cartridges, reactor furniture, and miscellaneous activated and contaminated items. Each of the waste streams requires conditioning to allow it to be and disposed of via one of the site treatment plants. - Pond Dewatering and Dismantling: Delivery of the above projects will allow operations to progressively remove the radiological inventory, thereby reducing the hazard/risk posed by the plant. This will then allow subsequent dewatering of the pond and dismantling of the structure. (authors)

  10. Solar pond research at the Los Alamos National Laboratory

    SciTech Connect (OSTI)

    Jones, G.F.; Meyer, K.A.; Hedstrom, J.C.; Grimmer, D.P.

    1984-01-01

    A description of solar pond research at Los Alamos National Laboratory is presented. The main issues in the theory of solar ponds are discussed. Among these are the interfacial-boundary-layer model, models for interface motion and pond performance, heat extraction, and ground heat loss. The core of the research effort at Los Alamos was the development of a one-dimensional computer program to accurately predict dynamic performance of a solar pond. The computer model and the experiments that were designed and performed to validate it are described. The experiments include two laboratory tanks wherein temperature, salinity, and flow visualization data were obtained and a 232 m/sup 2/ outdoor solar pond. Results from preliminary validation show good agreement between the pond's predicted dynamic behavior and that which actually occurred in the experiments. More validation using data from full-sized solar ponds is needed. A new correlation for the ratio of interfacial salt-flux to heat-flux is proposed which agrees well with our data. Recommendations for future research are given.

  11. Algal bioflocculation and energy conservation in microalgal sewage ponds

    SciTech Connect (OSTI)

    Eisenberg, D.M.; Koopman, B.; Benemann, J.R.; Oswald, W.J.

    1981-01-01

    Controlled bioflocculation for harvesting of microalgae produced during municipal wastewater treatment in high-rate ponds was investigated. Nonflocculant algal cultures were produced in high-rate ponds operated at very high dilution rates or with poor mixing. Bioflocculation of such cultures was achieved by isolating them in secondary ponds, but isolation periods of up to 29 days were required. In-pond sedimentation of flocculant algal cultures produced by the isolation technique resulted in algal removals consistently exceeding 80%. When high-rate ponds were operated with improved mixing and at moderate-to-high dilution rates, flocculant algal cultures were developed. The settleability of flocculant algal cultures produced in this manner averaged 76 to 80% when measured in 24-h-detention Imhoff cones and 71% when measured in 48-h-detention settling ponds. It is estimated that, under suitable climate conditions, a high-rate pond system employing bioflocculation-sedimentation for algal removal would require less than one-half the direct energy input of an equivalently sized activated sludge or trickling filter plant. This requirement could be provided entirely through complete utilization of biogas produced from anaerobic digestion of primary (sewage) sludge.

  12. Across the Pond Newsletter Issue 4 | Department of Energy

    Energy Savers [EERE]

    4 Across the Pond Newsletter Issue 4 A Quarterly Update on Joint UK NDA/US DOE Activities and Initiatives Issue 4: Summer 2010. In this issue: DOE-NDA discuss Spent Fuel Shipments WIPP Program visit to NDA Topic Area Update: Continued Progress Being Made DOE-NDA collaborations associated with the DOE EM-32 Groundwater and Soil Remediation Program DOE Fellows Program PDF icon Across the Pond Newsletter Issue 4 More Documents & Publications Deep Vadose Zone Across the Pond Newsletter Issue 9

  13. LED PAR38 Lamps | Department of Energy

    Energy Savers [EERE]

    PAR38 Lamps LED PAR38 Lamps The following CALiPER reports provide a detailed investigation of LED PAR38 lamp performance, covering basic performance characteristics as well as subjective evaluation of beam, shadow, and color quality. Further analysis is provided on flicker, dimming, and power quality characteristics; stress testing; lumen and chromaticity maintenance; and chromaticity shift modes. These reports are intended to educate the industry on market trends, potential issues, and

  14. Across the Pond Newsletter Issue 7 | Department of Energy

    Energy Savers [EERE]

    7 Across the Pond Newsletter Issue 7 A Quarterly Update on Joint UK NDA/US DOE Activities and Initiatives Issue 7: Spring 2012. In this issue: DOE and UK NDA Renew Information Exchange Agreement Topic Area Update and Future Plans International Collaboration: Development of Cryograb Technology for Waste Retrieval Transferring Best Practice in Research and Development Collaboration in Plutonium Management Moves to the Next Level Organizational Changes in NDA and DOE-EM PDF icon Across the Pond

  15. Across the Pond Newsletter Issue 9 | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Across the Pond Newsletter Issue 9 Across the Pond Newsletter Issue 9 A Quarterly Update on Joint UK NDA/US DOE Activities and Initiatives Issue 9: Winter 2014. In this issue: Plutonium Management Information Exchange Workshop held in Sellafield EM Delegation Tours UK Cleanup Program's Sellafield Site Savannah River and NDA Sellafield Host Exchange Visits for "Benchmarking" Discussions DOE / NDA Bilateral Agreement Highlighted at NDA Supply Chain Event Joint U.S. / UK Initiative

  16. 2101-M pond closure plan. Volume 1, Revision 2

    SciTech Connect (OSTI)

    Izatt, R. D.; Lerch, R. E.

    1993-06-01

    This document describes activities for the closure of a surface impoundment (2101-M Pond) at the Hanford Site. The 2101-H Pond was initially constructed in 1953 to serve as a drainage collection area for the 2101-H Building. (Until the Basalt Waste Isolation Project (BWIP) Laboratory was constructed in the 2101-M Building in 1979--1981, the only source contributing discharge to the pond was condensate water from the 2101-H Building heating, ventilation, and air conditioning (HVAC) system. The drains for the BWIP Laboratory rooms were plumbed into a 4-in., cast-iron, low-pressure drain pipe that carries waste water from the HVAC system to the pond. During the active life of the BWIP Laboratory, solutions of dissolved barium in groundwater samples were discharged to the 2101-M Pond via the laboratory drains. As a result of the discharges, a Part A permit application was initially submitted to the Washington State Department of Ecology (Ecology) in August 1986 which designates the 2101-M Pond as a surface impoundment.

  17. Modeling a ponded infiltration experiment at Yucca Mountain, NV

    SciTech Connect (OSTI)

    Hudson, D.B.; Guertal, W.R. [Foothill Engineering, Inc., Mercury, NV (United States); Flint, A.L. [Geological Survey, Mercury, NV (United States)

    1994-12-31

    Yucca Mountain, Nevada is being evaluated as a potential site for a geologic repository for high level radioactive waste. As part of the site characterization activities at Yucca Mountain, a field-scale ponded infiltration experiment was done to help characterize the hydraulic and infiltration properties of a layered dessert alluvium deposit. Calcium carbonate accumulation and cementation, heterogeneous layered profiles, high evapotranspiration, low precipitation, and rocky soil make the surface difficult to characterize.The effects of the strong morphological horizonation on the infiltration processes, the suitability of measured hydraulic properties, and the usefulness of ponded infiltration experiments in site characterization work were of interest. One-dimensional and two-dimensional radial flow numerical models were used to help interpret the results of the ponding experiment. The objective of this study was to evaluate the results of a ponded infiltration experiment done around borehole UE25 UZN {number_sign}85 (N85) at Yucca Mountain, NV. The effects of morphological horizons on the infiltration processes, lateral flow, and measured soil hydaulic properties were studied. The evaluation was done by numerically modeling the results of a field ponded infiltration experiment. A comparison the experimental results and the modeled results was used to qualitatively indicate the degree to which infiltration processes and the hydaulic properties are understood. Results of the field characterization, soil characterization, borehole geophysics, and the ponding experiment are presented in a companion paper.

  18. 2014 DOE Project Management Workshop Presentations: PARS II Enhancemen...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    2014 DOE Project Management Workshop Presentations: PARS II Enhancements - Igor Pedan, MA-63 2014 DOE Project Management Workshop Presentations: PARS II Enhancements - Igor Pedan, ...

  19. PARS II Course Registration | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    Click the link below to access the MS XL PARS II Course Registration Form. Select the Open option. Select the Save As option to save a copy of the registration form to your...

  20. Toxicity of stormwater treatment pond sediments to Hyalella azteca (Amphipoda)

    SciTech Connect (OSTI)

    Karouna-Renier, N.K.; Sparling, D.W.

    1997-04-01

    Stormwater runoff from highways and commercial, industrial, and residential areas contains a wide spectrum of pollutants including heavy metals, petroleum hydrocarbons, pesticides, herbicides, sediment, and nutrients. Recent efforts to reduce the impacts of urbanization on natural wetlands and other receiving waters have included the construction of stormwater treatment ponds and wetlands. These systems provide flood control and improve water quality through settling, adsorption, and precipitation of pollutants removing up to 95% of metals, nutrients and sediment before discharged from the site. The design of stormwater ponds to provide habitat for aquatic wildlife has prompted concern over the potential exposure of aquatic organisms to these contaminants. Aquatic sediments concentrate a wide array of organic and inorganic pollutants. Although water quality criteria may not be exceeded, organisms living in or near the sediments may be adversely affected. The availability of chemicals in sediments depends strongly on the prevailing chemistry. Physical conditions of the sediment and water quality characteristics including pH, redox potential and hardness, also influence contaminant availability. Studies have shown that heavy metals and nutrients carried by runoff concentrate in the sediment of stormwater ponds. Although several investigations have assessed the toxicity of sediments in streams receiving urban runoff, there have been few studies of the toxicity of stormwater treatment pond sediments to aquatic organisms. This study was part of a large-scale assessment of the contaminant hazards of stormwater treatment ponds. The objective of this study was to evaluate the toxicity of sediments and water from stormwater ponds over a 10-d period to juvenile Hyalella azteca. Bioassay results were related to concentrations of acid volatile sulfides and metals of the tested sediments. 17 refs., 4 tabs.

  1. Gradient zone boundary control in salt gradient solar ponds

    DOE Patents [OSTI]

    Hull, John R.

    1984-01-01

    A method and apparatus for suppressing zone boundary migration in a salt gradient solar pond includes extending perforated membranes across the pond at the boundaries, between the convective and non-convective zones, the perforations being small enough in size to prevent individual turbulence disturbances from penetrating the hole, but being large enough to allow easy molecular diffusion of salt thereby preventing the formation of convective zones in the gradient layer. The total area of the perforations is a sizable fraction of the membrane area to allow sufficient salt diffusion while preventing turbulent entrainment into the gradient zone.

  2. Salinity gradient solar pond technology applied to potash solution mining

    SciTech Connect (OSTI)

    Martell, J.A.; Aimone-Martin, C.T.

    2000-06-12

    A solution mining facility at the Eddy Potash Mine, Eddy County, New Mexico has been proposed that will utilize salinity gradient solar pond (SGSP) technology to supply industrial process thermal energy. The process will include underground dissolution of potassium chloride (KCl) from pillars and other reserves remaining after completion of primary room and pillar mining using recirculating solutions heated in the SGSP. Production of KCl will involve cold crystallization followed by a cooling pond stage, with the spent brine being recirculated in a closed loop back to the SGSP for reheating. This research uses SGSP as a renewable, clean energy source to optimize the entire mining process, minimize environmental wastes, provide a safe, more economical extraction process and reduce the need for conventional processing by crushing, grinding and flotation. The applications of SGSP technology will not only save energy in the extraction and beneficiation processes, but also will produce excess energy available for power generation, desalination, and auxiliary structure heating.

  3. Across the Pond Newsletter Issue 1 | Department of Energy

    Energy Savers [EERE]

    1 Across the Pond Newsletter Issue 1 A Quarterly Update on Joint UK NDA/US DOE Activities and Initiatives Issue 1: Summer 2009. In this issue: The US Department of Energy (DOE) / UK Nuclear Decommissioning Authority (NDA) Bilateral Agreement Initial Topic Areas for Discussion US DOE Represented at NDA-Sponsored Pu Workshop DOE - NDA Implementation Plan (4th Standing Committee Meeting held in Phoenix ) SRNL and NNL Collaborate on RadBall Trials NDA Provides Support to EM in Prioritization of

  4. Across the Pond Newsletter Issue 2 | Department of Energy

    Energy Savers [EERE]

    2 Across the Pond Newsletter Issue 2 A Quarterly Update on Joint UK NDA/US DOE Activities and Initiatives Issue 2: December 2009. In this issue: DOE - NDA relationship recognized at International Environmental Cleanup Conference NDA - DOE Standing Committee Meeting commends progress Topic Area Update: Significant Progress Being Made Information Exchange is one of "DOE's best business practices" Glass Chemistry - A Flagship of Progress Under the Statement of Intent US Nuclear Waste

  5. Across the Pond Newsletter Issue 3 | Department of Energy

    Energy Savers [EERE]

    3 Across the Pond Newsletter Issue 3 A Quarterly Update on Joint UK NDA/US DOE Activities and Initiatives Issue 3: Spring 2010. In this issue: DOE Hosts Next Generation Melter Technology Workshop Advanced Thermal Treatment Studies At Sellafield Topic Area Update: Continued Progress Being Made NDA Visits Thermal Treatment Technology Vendors In The USA NDA To Progress UK Graphite Disposition Strategy With Transatlantic Support From Studsvik From The US To The UK ... And Back Again Waste Management

  6. Across the Pond Newsletter Issue 5 | Department of Energy

    Energy Savers [EERE]

    5 Across the Pond Newsletter Issue 5 A Quarterly Update on Joint UK NDA/US DOE Activities and Initiatives Issue 5: Winter 2010. In this issue: Introduction 7th Standing Committee Meeting between USDOE - UKNDA held in Sellafield. Topic Area Update Group From Sellafield Visits Idaho To Exchange Information On Hot Isostatic Pressing Glass Chemistry Collaboration Update International Partnership Workshop on DOE Used Nuclear Fuel & High Level Waste NWTRB Discusses Technical Lessons Gained From

  7. THERMAL PERFORMANCE MEASUREMENTS ON ULTIMATE HEAT SINKS - COOLING PONDS

    Office of Scientific and Technical Information (OSTI)

    PERFORMANCE MEASUREMENTS ON ULTIMATE HEAT SINKS - COOLING PONDS R. K. Hadlock 0 . B. Abbey Battelle Pacific Northwest Laboratories Prepared for U. S. Nuclear Regulatory Commission b + NOTICE This report was prepared as an account of work sponsored by the United States Government. Neither the United States nor the United States Nuclear Regulatory Commission, nor any of their employees, nor any of their contractors, subcontractors, or their employees, makes any warranty, express or implied, nor

  8. Turbidity study of solar ponds utilizing seawater as salt source

    SciTech Connect (OSTI)

    Li, Nan; Sun, Wence; Shi, Yufeng; Yin, Fang; Zhang, Caihong

    2010-02-15

    A series of experiments were conducted to study the turbidity reduction in solar ponds utilizing seawater as salt source. The experiment on the turbidity reduction efficiency with chemicals indicates that alum (KAl(SO{sub 4}){sub 2}.12H{sub 2}O) has a better turbidity control property because of its strongly flocculating and also well depressing the growing of algae and bacteria in the seawater. In comparison with bittern and seawater, our experiment shows that the residual brine after desalination can keep limpidity for a long time even without any chemical in it. Experiments were also conducted on the diffusion of turbidity and salinity, which show that the turbidity did not diffuse upwards in the solution. In the experiment on subsidence of soil in the bittern and saline with the same salinity, it was found that soil subsided quite quickly in the pure saline water, but very slowly in the bittern. In this paper we also proposed an economical method to protect the solar pond from the damage of rain. Finally, thermal performance of a solar pond was simulated in the conditions of different turbidities using a thermal diffusion model. (author)

  9. Par Pastoril e Agr cola S A | Open Energy Information

    Open Energy Info (EERE)

    Par Pastoril e Agr cola S A Jump to: navigation, search Name: Par Pastoril e Agr-cola SA Place: Catanduva, Sao Paulo, Brazil Product: Agrobusiness company which produces...

  10. 2014 DOE Project Management Workshop Presentations: PARS II Enhancements -

    Energy Savers [EERE]

    Igor Pedan, MA-63 | Department of Energy 4 DOE Project Management Workshop Presentations: PARS II Enhancements - Igor Pedan, MA-63 2014 DOE Project Management Workshop Presentations: PARS II Enhancements - Igor Pedan, MA-63 2014 DOE Project Management Workshop presentation by Igor Pedan. PDF icon Presentation More Documents & Publications 2014 DOE Project Management Workshop Presentations: PARS II Enhancements - Igor Pedan, MA-63 Advances in PARS IIe and Incorporating Automated Testing

  11. Project Assessment and Reporting System (PARS II) Memo

    Broader source: Energy.gov [DOE]

    Project Assessment and Reporting System (PARS II) Memo from the deputy secretary of Energy, dated May 17, 2010.

  12. Across the Pond Newsletter Issue 6 | Department of Energy

    Energy Savers [EERE]

    6 Across the Pond Newsletter Issue 6 A Quarterly Update on Joint UK NDA/US DOE Activities and Initiatives Issue 6: Spring 2011. In this issue: 8th Standing Committee Meeting A Great Success! Waste Management 2011 Highlights US DOE-UK NDA links US Congress Seeks Lessons Learned from UK Reprocessing Third International Technical Exchange on Long-term Glass Corrosion held January 25-28th, 2011 Web-based Information Exchange Portal being Developed NDA Builds Links to Savannah River! Developing the

  13. Across the Pond Newsletter Issue 8 | Department of Energy

    Energy Savers [EERE]

    8 Across the Pond Newsletter Issue 8 A Quarterly Update on Joint UK NDA/US DOE Activities and Initiatives Issue 8: Winter 2013. In this issue: UK Expertise Sought to Help Address Hanford Challenges US DOE - Developed Decon Gel Finds Application at Sellafield UK Office of Nuclear Regulation visits DOE HQ and DOE Hanford Head of US Cleanup Program visits Sellafield and Dounreay Successful US/UK Contracting Summit Hosted by UK NDA West Valley and Hanford host NDA and Dounreay Site Restoration Ltd.

  14. ELECTROKINETIC DENSIFICATION OF COAL FINES IN WASTE PONDS

    SciTech Connect (OSTI)

    E. James Davis

    1999-12-18

    The objective of this research was to demonstrate that electrokinetics can be used to remove colloidal coal and mineral particles from coal-washing ponds and lakes without the addition of chemical additives such as salts and polymeric flocculants. The specific objectives were: Design and develop a scaleable electrophoresis apparatus to clarify suspensions of colloidal coal and clay particles; Demonstrate the separation process using polluted waste water from the coal-washing facilities at the coal-fired power plants in Centralia, WA; Develop a mathematical model of the process to predict the rate of clarification and the suspension electrical properties needed for scale up.

  15. Trace metals in urban streams and detention ponds

    SciTech Connect (OSTI)

    Licsko, Z.J.; Struger, J.

    1995-12-31

    Trace metal levels were monitored over a nine month period in two urban creeks in the Hamilton Harbour watershed and in two urban stormwater retention ponds in Guelph, Ontario. Samples were collected both during dry or non-event periods and immediately after wet weather events. Both water and surficial sediment samples were collected and tested for cadmium, copper, lead, mercury, nickel, and zinc. In almost all cases during wet weather conditions, Canadian Water Quality Guidelines for the protection of freshwater aquatic life were exceeded in water for lead (>7 mg/L), copper (>4 mg/L), and zinc (>30 mg/L) . Both stormwater ponds accumulated trace metals in sediment to levels above the lowest effect level guideline for the protection and management of aquatic sediment in Ontario, and, in the case of zinc (> 820 ug/g), above the severe effect level guideline. These levels of contamination raise serious concerns about the use of these and similar facilities as habitat for biota.

  16. PARS II Enhancements - Igor Pedan, MA-63 | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Enhancements - Igor Pedan, MA-63 PARS II Enhancements - Igor Pedan, MA-63 2014 DOE Project Management Workshop PDF icon 28PedanPARSII Enhancements.pdf More Documents & ...

  17. Analysis of storm-water infiltration ponds on the North Carolina Outer Banks

    SciTech Connect (OSTI)

    Chescheir, G.M.; Fipps, G.; Skaggs, R.W.

    1990-09-01

    Increasing development along the North Carolina coast has been linked to the deterioration of water quality in adjacent sounds and estuaries. Degradation of water quality in sounds and estuaries threatens the coastal ecology which provides resources for the area's fishing and tourism industries. The state of N.C. adopted the current Stormwater Runoff Disposal Rules in 1988 requiring stormwater management plans for new development in 20 coastal counties. Stormwater infiltration pond systems are approved by the State as an option for retaining stormwater on the developed site; however, the long-term performance of these systems has not been measured or determined. The study was conducted to monitor the hydrology of stormwater infiltration ponds on the North Carolina barrier islands and to develop a model that continuously simulates the performance of these ponds. The hydrology of two operating infiltration ponds systems was evaluated in an 18-month field study. Rainfall, pond stage, and water table elevations at selected locations were monitored continuously. Water table elevations at additional locations were monitored on a biweekly basis. Soil hydraulic conductivities and soil water characteristic relationships were determined at both field sites. The subsurface geology was described at one site and an aquifer pump test was performed to determine aquifer transmissivity and specific yield. Both of the infiltration ponds in the field studies effectively served their primary purpose of retaining on site the stormwater runoff from the first 38 mm (1.5 in) of rainfall. In nearly every case, the pond seepage rate was sufficient to completely draw down the pond within 5 days. The hydrology of the infiltration ponds at the two research sites was very different.

  18. Commercial Cooling Par Engineering: Order (2013-CE-5312)

    Broader source: Energy.gov [DOE]

    DOE ordered Commercial Cooling Par Engineering, Inc. to pay a $8,000 civil penalty after finding Commercial Cooling Par Engineering had failed to certify that certain models of walk-in cooler and freezer components comply with the applicable energy conservation standards.

  19. Groundwater Monitoring Plan for the Hanford Site 216-B-3 Pond RCRA Facility

    SciTech Connect (OSTI)

    Barnett, D BRENT.; Smith, Ronald M.; Chou, Charissa J.; McDonald, John P.

    2005-11-01

    The 216-B-3 Pond system was a series of ponds used for disposal of liquid effluent from past Hanford production facilities. In operation from 1945 to 1997, the B Pond System has been a Resource Conservation and Recovery Act (RCRA) facility since 1986, with RCRA interim-status groundwater monitoring in place since 1988. In 1994 the expansion ponds of the facility were clean closed, leaving only the main pond and a portion of the 216-B-3-3 ditch as the currently regulated facility. In 2001, the Washington State Department of Ecology (Ecology) issued a letter providing guidance for a two-year, trial evaluation of an alternate, intrawell statistical approach to contaminant detection monitoring at the B Pond system. This temporary variance was allowed because the standard indicator-parameters evaluation (pH, specific conductance, total organic carbon, and total organic halides) and accompanying interim status statistical approach is ineffective for detecting potential B-Pond-derived contaminants in groundwater, primarily because this method fails to account for variability in the background data and because B Pond leachate is not expected to affect the indicator parameters. In July 2003, the final samples were collected for the two-year variance period. An evaluation of the results of the alternate statistical approach is currently in progress. While Ecology evaluates the efficacy of the alternate approach (and/or until B Pond is incorporated into the Hanford Facility RCRA Permit), the B Pond system will return to contamination-indicator detection monitoring. Total organic carbon and total organic halides were added to the constituent list beginning with the January 2004 samples. Under this plan, the following wells will be monitored for B Pond: 699-42-42B, 699-43-44, 699-43-45, and 699-44-39B. The wells will be sampled semi-annually for the contamination indicator parameters (pH, specific conductance, total organic carbon, and total organic halides) and annually for water quality parameters (chloride, iron, manganese, phenols, sodium, and sulfate). This plan will remain in effect until superseded by another plan or until B Pond is incorporated into the Hanford Facility RCRA Permit.

  20. A comparison of Nannochloropsis salina growth performance in two outdoor pond designs: conventional raceways versus the ARID pond with superior temperature management

    SciTech Connect (OSTI)

    Crowe, Braden J.; Attalah, Said; Agrawal, Shweta; Waller, Peter; Ryan, Randy; Van Wagenen, Jonathan M.; Chavis, Aaron R.; Kyndt, John; Kacira, Murat; Ogden, Kimberly L.; Huesemann, Michael H.

    2012-10-01

    The present study examines how climatic conditions and pond design affect the growth performance of microalgae. From January to April of 2011, outdoor batch cultures of Nannochloropsis salina were grown in three replicate 780 L conventional raceways, as well as in an experimental 7500 L ARID (Algae Raceway Integrated Design) pond. The ARID culture system utilizes a series of 8 to 20 cm deep basins and a 1.5 m deep canal to enhance light exposure and mitigate temperature variations and extremes. The ARID culture reached the stationary phase 27 days earlier than the conventional raceways, which can be attributed to its superior temperature management and shallower basins. On a night when the air temperature dropped to -9 C, the water temperature was 18 C higher in the ARID pond than in the conventional raceways. Lipid and fatty acid content ranged from 16 - 25 % and 5 - 15 %, respectively, as a percentage of AFDW. Palmitic, palmitoleic, and eicosapentaenoic acid comprised the majority of fatty acids. While the ARID culture system achieved nearly double the volumetric productivity relative to the conventional raceways (0.023 vs 0.013 g L-1day-1), areal biomass productivities were of similar magnitude in both pond systems (3.34 vs. 3.47 g m-2day-1), suggesting that the ARID pond design has to be further optimized, most likely by increasing the culture depth or operating at higher cell densities while maintaining adequate mixing.

  1. How to Submit a Request for a PARS II Account | Department of...

    Energy Savers [EERE]

    How to Submit a Request for a PARS II Account How to Submit a Request for a PARS II Account The account access process for PARS II relies on the Department of Energy's iManage...

  2. Title 29 Chapter 11 Management of Lakes and Ponds | Open Energy...

    Open Energy Info (EERE)

    Title 29 Chapter 11 Management of Lakes and Ponds Jump to: navigation, search OpenEI Reference LibraryAdd to library Legal Document- StatuteStatute: Title 29 Chapter 11 Management...

  3. 40 CFR 265 interim-status ground-water monitoring plan for the 2101-M pond

    SciTech Connect (OSTI)

    Chamness, M.A.; Luttrell, S.P.; Dudziak, S.

    1989-03-01

    This report outlines a ground-water monitoring plan for the 2101-M pond, located in the southwestern part of the 200-East Area on the Hanford Site in south-central Washington State. It has been determined that hazardous materials may have been discharged to the pond. Installation of an interim-status ground-water monitoring system is required under the Resource Conservation and Recovery Act to determine if hazardous chemicals are moving out of the pond. This plan describes the location of new wells for the monitoring system, how the wells are to be completed, the data to be collected, and how those data can be used to determine the source and extent of any ground-water contamination from the 2101-M pond. Four new wells are planned, one upgradient and three downgradient. 35 refs., 12 figs., 9 tabs.

  4. In re Kent Pond, No MLP-03-10, Findings of Fact, Conclusions...

    Open Energy Info (EERE)

    re Kent Pond, No MLP-03-10, Findings of Fact, Conclusions of Law, and Order at 8, 13 (Vt. Water Res. Bd. May, 2004) Jump to: navigation, search OpenEI Reference LibraryAdd to...

  5. Title 10 Chapter 11 Management of Lakes and Ponds | Open Energy...

    Open Energy Info (EERE)

    of Lakes and PondsLegal Published NA Year Signed or Took Effect 1985 Legal Citation 29 V.S.A 401 DOI Not Provided Check for DOI availability: http:crossref.org Online Internet...

  6. A lipid-accumulating alga maintains growth in outdoor, alkaliphilic raceway pond with mixed microbial communities

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Bell, Tisza A.S.; Prithiviraj, Bharath; Wahlen, Brad D.; Fields, Matthew W.; Peyton, Brent M.

    2016-01-07

    Algal biofuels and valuable co-products are being produced in both open and closed cultivation systems. Growing algae in open pond systems may be a more economical alternative, but this approach allows environmental microorganisms to colonize the pond and potentially infect or outcompete the algal “crop.” In this study, we monitored the microbial community of an outdoor, open raceway pond inoculated with a high lipid-producing alkaliphilic alga, Chlorella vulgaris BA050. The strain C. vulgaris BA050 was previously isolated from Soap Lake, Washington, a system characterized by a high pH (~9.8). An outdoor raceway pond (200 L) was inoculated with C. vulgarismore » and monitored for 10 days and then the culture was transferred to a 2,000 L raceway pond and cultivated for an additional 6 days. Community DNA samples were collected over the 16-day period in conjunction with water chemistry analyses and cell counts. Universal primers for the SSU rRNA gene sequences for Eukarya, Bacteria, and Archaea were used for barcoded pyrosequence determination. The environmental parameters that most closely correlated with C. vulgaris abundance were pH and phosphate. Community analyses indicated that the pond system remained dominated by the Chlorella population (93% of eukaryotic sequences), but was also colonized by other microorganisms. Bacterial sequence diversity increased over time while archaeal sequence diversity declined over the same time period. Using SparCC co-occurrence network analysis, a positive correlation was observed between C. vulgaris and Pseudomonas sp. throughout the experiment, which may suggest a symbiotic relationship between the two organisms. The putative relationship coupled with high pH may have contributed to the success of C. vulgaris. As a result, the characterization of the microbial community dynamics of an alkaliphilic open pond system provides significant insight into open pond systems that could be used to control photoautotrophic biomass productivity in an open, non-sterile environment.« less

  7. Microsoft PowerPoint - Snippet 5.2 PARS II Analysis-Data Validity...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    being reported reflects reality. 5 PARS II automatically issues warnings upon the ... The contractor may or may not take the opportunity to make corrections. The PARS II EV ...

  8. Commercial Cooling Par Engineering: Proposed Penalty (2013-CE-5312)

    Broader source: Energy.gov [DOE]

    DOE alleged in a Notice of Proposed Civil Penalty that Commercial Cooling Par Engineering failed to certify walk-in cooler or freezer components as compliant with the energy conservation standards.

  9. A Comparison of Nannochloropsis salina Growth Performance in Two Outdoor Pond Designs: Conventional Raceways versus the ARID Pond with Superior Temperature Management

    SciTech Connect (OSTI)

    Crowe, Braden; Attalah, Said; Agrawal, Shweta; Waller, Peter; Ryan, Randy; Van Wagenen, Jon; Chavis, Aaron; Kyndt, John; Kacira, Murat; Ogden, Kim L.; Huesemann, Michael

    2012-01-01

    The present study examines how climatic conditions and pond design affect the growth performance of microalgae. From January to April of 2011, outdoor batch cultures of Nannochloropsis salina were grown in three replicate 780 L conventional raceways, as well as in an experimental 7500 L algae raceway integrated design (ARID) pond. The ARID culture system utilizes a series of 8-20 cm deep basins and a 1.5 m deep canal to enhance light exposure and mitigate temperature variations and extremes. The ARID culture reached the stationary phase 27 days earlier than the conventional raceways, which can be attributed to its superior temperature management and shallower basins. On a night when the air temperature dropped to -9C, the water temperature was 18C higher in the ARID pond than in the conventional raceways. Lipid and fatty acid content ranged from 16 to 25% and from 5 to15%, respectively, as a percentage of AFDW. Palmitic, palmitoleic, and eicosapentaenoic acids comprised the majority of fatty acids. While the ARID culture system achieved nearly double the volumetric productivity relative to the conventional raceways (0.023 versus 0.013 g L-1day-1), areal biomass productivities were of similar magnitude in both pond systems (3.47 versus 3.34 g m-2day-1), suggesting that the ARID pond design has to be further optimized, most likely by increasing the culture depth or operating at higher cell densities while maintaining adequate mixing.

  10. A Comparison of Nannochloropsis salina Growth Performance in Two Outdoor Pond Designs: Conventional Raceways versus the ARID Pond with Superior Temperature Management

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Crowe, Braden; Attalah, Said; Agrawal, Shweta; Waller, Peter; Ryan, Randy; Van Wagenen, Jon; Chavis, Aaron; Kyndt, John; Kacira, Murat; Ogden, Kim L.; et al

    2012-01-01

    The present study examines how climatic conditions and pond design affect the growth performance of microalgae. From January to April of 2011, outdoor batch cultures of Nannochloropsis salina were grown in three replicate 780 L conventional raceways, as well as in an experimental 7500 L algae raceway integrated design (ARID) pond. The ARID culture system utilizes a series of 8-20 cm deep basins and a 1.5 m deep canal to enhance light exposure and mitigate temperature variations and extremes. The ARID culture reached the stationary phase 27 days earlier than the conventional raceways, which can be attributed to its superiormore » temperature management and shallower basins. On a night when the air temperature dropped to -9°C, the water temperature was 18°C higher in the ARID pond than in the conventional raceways. Lipid and fatty acid content ranged from 16 to 25% and from 5 to15%, respectively, as a percentage of AFDW. Palmitic, palmitoleic, and eicosapentaenoic acids comprised the majority of fatty acids. While the ARID culture system achieved nearly double the volumetric productivity relative to the conventional raceways (0.023 versus 0.013 g L-1day-1), areal biomass productivities were of similar magnitude in both pond systems (3.47 versus 3.34 g m-2day-1), suggesting that the ARID pond design has to be further optimized, most likely by increasing the culture depth or operating at higher cell densities while maintaining adequate mixing.« less

  11. East Pond West Pond South Pond South Pond Southwest Pond

    Office of Legacy Management (LM)

    06-0500 14.4 06-0501 14.53 15-M03S 14.97 18-0500 14.34 18-0502 14.23 18-0521 14.18 18-0525 14.31 18-0526 13.79 20-M025 14.26 20-M035 14.4 21-0502 12.66 21-0503 12.34 21-0504 13.12 21-0505 13.23 18-0524 14.24 12-0539 12.86 18-RW02 14.09 18-RW03 14.16 12-0523 14.43 12-0525 13.7 12-S29C 14.25 12-S32B 14.4 12-S35B 14.18 12-S37B 14.59 15-0530 14.13 15-M14S 14.68 12-0509 14.52 12-0513 13.64 12-0517 14.08 12-0521 14.35 12-0526 12.88 12-RW01 14.55 12-S31B 14.25 12-S36B 13.99 12-TE03 13.95 15-0507 13.45

  12. East Pond West Pond South Pond South Pond Southwest Pond

    Office of Legacy Management (LM)

    12-S30B 713.6 12-S33C 1863 12-S35B 38320 15-0534 ND 20-M003 ND 20-M005 ND 20-M054 3.9 12-S68D 164.7 12-S69C ND 12-S70B 30 12-S70C 70 12-S71C 77 12-S72C 3.8 12-S73B ND 12-S73C 11.9 12-S67B 349.9 12-S67C 197.2 12-S67D 56.7 15-0566 101 12-0527 ND 12-S69D ND 12-S70D 43.2 12-S71D 28.2 12-S72D ND 12-S71B ND 12-S69B ND 20-M028 ND 20-M011 ND 20-M019 ND 20-0503 4.1 20-M024 ND 20-M025 ND 20-M035 2.9 20-M036 ND 20-M38D ND 20-M40S ND 20-M023 ND 20-M41D ND 15-0569 5.6 20-MWL3 996.1 20-M049 5.6 20-M22D 4.2

  13. Description of work for 100-N Hanford Generating Plant settling pond drilling and sampling

    SciTech Connect (OSTI)

    Galbraith, R.P.

    1993-09-01

    This description of work details the field activities associated with borehole drilling and sampling of the 100-N Hanford Generating Plant (HGP) Settling Pond and will serve as a field guide for those performing the work. It should be used in conjunction with the Environmental Investigations and Site Characterization Manual (WHC 1988a) for specific procedures. The borehole location is shown in Figure 1. The settling pond, the dimensions of which are 40 m by 16 m (131.3 ft by 52.5 ft), is located at the HGP adjacent to the 100-N Area. The pond received process water from the plant. The water contained trace oxygen scavenging conditioners such as morpholine, hydrazine, and ammonia. Surface radioactivity readings are 150 to 500 cpm. Trace levels of surface contamination are present. Drilling and sampling will be in accordance with procedures in the EII manual (WHC 1988a).

  14. Gradient zone-boundary control in salt-gradient solar ponds

    DOE Patents [OSTI]

    Hull, J.R.

    1982-09-29

    A method and apparatus for suppressing zone boundary migration in a salt gradient solar pond includes extending perforated membranes across the pond at the boundaries, between the convective and non-convective zones, the perforations being small enough in size to prevent individual turbulence disturbances from penetrating the hole, but being large enough to allow easy molecular diffusion of salt thereby preventing the formation of convective zones in the gradient layer. The total area of the perforations is a sizeable fraction of the membrane area to allow sufficient salt diffusion while preventing turbulent entrainment into the gradient zone.

  15. DOE responses to Ecology review comments for ``Sampling and analysis plans for the 100-D Ponds voluntary remediation project``

    SciTech Connect (OSTI)

    NONE

    1996-12-31

    The Sampling and Analysis Plan describes the sampling and analytical activities which will be performed to support closure of the 100-D Ponds at the Hanford Reservation. This report contains responses by the US Department of Energy to Ecology review for ``Sampling and Analysis Plan for the 100-D Ponds Voluntary Remediation Project.``

  16. Breeding pond selection and movement patterns by eastern spadefoot toads (Scaphiopus holbrookii) in relation to weather and edaphic conditions.

    SciTech Connect (OSTI)

    Greenberg, Cathyrn, H.; Tanner, George, W.

    2004-08-31

    Cathryn H. Greenberg and George W. Tanner. 2004. Breeding pond selection and movement patterns by eastern spadefoot toads (Scaphiopus holbrookii) in relation to weather and edaphic conditions. J. Herp. 38(4):569-577. Abstract: Eastern Spadefoot Toads (Scaphiopus holbrookii) require fish-free, isolated, ephemeral ponds for breeding but otherwise inhabit the surrounding uplands, commonly xeric longleaf pine (Pinus palustris) ?wiregrass (Aristida beyrichiana). Hence both pond and upland conditions can potentially affect their breeding biology, and population persistence. Hardwood invasion due to fire suppression in sandhills could alter upland and pond suitability by higher hardwood density and increased transpiration. In this paper we explore breeding and neonatal emigration movements in relation to weather, hydrological conditions of ponds, and surrounding upland matrices. We use 9 years of data from continuous monitoring with drift fences and pitfall traps at 8 ephemeral ponds in 2 upland matrices: regularly-burned, savanna-like sandhills (n = 4), and hardwood-invaded sandhills (n = 4). Neither adult nor neonate captures differed between ponds within the 2 upland matrices, suggesting that they are tolerant of upland heterogeneity created by fire frequency. Explosive breeding occurred during 9 periods and in all seasons; adults were captured rarely otherwise. At a landscape-level rainfall, maximum change in barometric pressure, and an interaction between those 2 variables were significant predictors of explosive breeding. At a pond-level, rainfall, change in pond depth during the month prior to breeding, and days since a pond was last dry were significant predictors of adult captures. Transformation date, rather than weather, was associated with neonatal emigrations, which usually were complete within a week. Movement by first-captured adults and neonates was directional, but adult emigrations were apparently not always toward their origin. Our results suggest that Spadefoot Toads are highly adapted to breeding conditions and upland habitat heterogeneity created by weather patterns and fire frequency in Florida sandhills.

  17. Evaluation of remedial alternatives for the Solar Ponds Plume, Rocky Flats Environmental Technology Site

    SciTech Connect (OSTI)

    Hranac, K.C.; Chromec, F.W.; Fiehweg, R.; Hopkins, J.

    1998-07-01

    This paper describes the process used to select a remedial alternative for handling contaminated groundwater emanating from the Solar Evaporation Ponds (Solar Ponds) at the Rocky Flats Environmental Technology Site (RFETS) and prevent it from reaching the nearest surface water body, North Walnut Creek. Preliminary results of field investigations conducted to provide additional information for the alternatives analysis are also presented. The contaminated groundwater is referred to as the Solar Ponds Plume (SPP). The primary contaminants in the SPP are nitrate and uranium; however, some metals exceed the site action levels at several locations and volatile organic compounds, originating from other sources, also have been detected. Currently the SPP, local surface water runoff, and infiltrated precipitation are collected by a trench system located downgradient of the Solar Ponds and pumped to three storage tanks. The water (two to three million gallons annually) is then pumped to an on-site treatment plant for evaporation at an approximate cost of $7.57 per liter.

  18. 2011 Radiological Monitoring Results Associated with the Advanced Test Reactor Complex Cold Waste Pond

    SciTech Connect (OSTI)

    Mike Lewis

    2012-02-01

    This report summarizes radiological monitoring performed of the Idaho National Laboratory Site's Advanced Test Reactor Complex Cold Waste wastewater prior to discharge into the Cold Waste Pond and of specific groundwater monitoring wells associated with the Industrial Wastewater Reuse Permit (LA-000161-01, Modification B). All radiological monitoring is performed to fulfill Department of Energy requirements under the Atomic Energy Act.

  19. 2010 Radiological Monitoring Results Associated with the Advance Test Reactor Complex Cold Waste Pond

    SciTech Connect (OSTI)

    mike lewis

    2011-02-01

    This report summarizes radiological monitoring performed of the Idaho National Laboratory Sites Advanced Test Reactor Complex Cold Waste wastewater prior to discharge into the Cold Waste Pond and of specific groundwater monitoring wells associated with the Industrial Wastewater Reuse Permit (#LA-000161-01, Modification B). All radiological monitoring is performed to fulfill Department of Energy requirements under the Atomic Energy Act.

  20. 2014 Radiological Monitoring Results Associated with the Advanced Test Reactor Complex Cold Waste Pond

    SciTech Connect (OSTI)

    Lewis, Mike

    2015-02-01

    This report summarizes radiological monitoring performed of the Idaho National Laboratory Site’s Advanced Test Reactor Complex Cold Waste wastewater prior to discharge into the Cold Waste Pond and of specific groundwater monitoring wells associated with the Industrial Wastewater Reuse Permit (#LA-000161-01, Modification B). All radiological monitoring is performed to fulfill Department of Energy requirements under the Atomic Energy Act.

  1. 2013 Radiological Monitoring Results Associated with the Advanced Test Reactor Complex Cold Waste Pond

    SciTech Connect (OSTI)

    Mike Lewis

    2014-02-01

    This report summarizes radiological monitoring performed of the Idaho National Laboratory Site’s Advanced Test Reactor Complex Cold Waste wastewater prior to discharge into the Cold Waste Pond and of specific groundwater monitoring wells associated with the Industrial Wastewater Reuse Permit (#LA-000161-01, Modification B). All radiological monitoring is performed to fulfill Department of Energy requirements under the Atomic Energy Act.

  2. Phytoplankton in the cooling pond of a nuclear fuel plant. II. Spectral analysis

    SciTech Connect (OSTI)

    Tokarskaya, Z.B.; Smagin, A.I.; Ryzhkov, E.G.; Nikitina, L.V.

    1995-09-01

    This study continues investigations into the development dynamics of phytoplankton and hydrochemical and meteorological factors over a periods of 26 years in the cooling pond of the Mayak Production Association in the Kyzyl-Trash Lake. The aim is to evaluate the long-term oscillations in phytoplankton owing to changes in hydrochemical and meteorological factors. 6 refs., 2 figs., 1 tab.

  3. 2012 Radiological Monitoring Results Associated with the Advanced Test Reactor Complex Cold Waste Pond

    SciTech Connect (OSTI)

    Mike Lewis

    2013-02-01

    This report summarizes radiological monitoring performed of the Idaho National Laboratory Site’s Advanced Test Reactor Complex Cold Waste wastewater prior to discharge into the Cold Waste Pond and of specific groundwater monitoring wells associated with the Industrial Wastewater Reuse Permit (#LA-000161-01, Modification B). All radiological monitoring is performed to fulfill Department of Energy requirements under the Atomic Energy Act.

  4. Microsoft PowerPoint - Snippet 5.4 PARS II Analysis-Variance...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    In PARS II under the SSS Reports selection on the left, there are folders to the right. ... warning signs of future problems. To drill down, we need to view other PARS II reports. ...

  5. Microsoft PowerPoint - Snippet 5.7 PARS II Analysis-OAPM Monthly...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Reports that are used to prepare the information are located in the PARS II SSS Reports ... Finally, the Project % Complete values calculated by PARS II are based on the contractor ...

  6. Report 20.5: Chromaticity Shift Modes of LED PAR38 Lamps Operated...

    Energy Savers [EERE]

    5: Chromaticity Shift Modes of LED PAR38 Lamps Operated in Steady-State Conditions Report 20.5: Chromaticity Shift Modes of LED PAR38 Lamps Operated in Steady-State Conditions PDF ...

  7. The L Prize PAR 38 Competition: A New Start | Department of Energy

    Energy Savers [EERE]

    The L Prize PAR 38 Competition: A New Start The L Prize PAR 38 Competition: A New Start This March 27, 2012 webcast presented information on the newly reopened L Prize® PAR 38 competition. Moderated by James Brodrick, DOE Lighting Program Manager, the webcast featured an overview of the PAR 38 competition from Marc Ledbetter of Pacific Northwest National Laboratory, and explained key changes of the retooled competition requirements. Topics included performance specifications, U.S. content

  8. The absorption chiller in large scale solar pond cooling design with condenser heat rejection in the upper convecting zone

    SciTech Connect (OSTI)

    Tsilingiris, P.T. )

    1992-07-01

    The possibility of using solar ponds as low-cost solar collectors combined with commercial absorption chillers in large scale solar cooling design is investigated. The analysis is based on the combination of a steady-state solar pond mathematical model with the operational characteristics of a commercial absorption chiller, assuming condenser heat rejection in the upper convecting zone (U.C.Z.). The numerical solution of the nonlinear equations involved leads to results which relate the chiller capacity with pond design and environmental parameters, which are also employed for the investigation of the optimum pond size for a minimum capital cost. The derived cost per cooling kW for a 350 kW chiller ranges from about 300 to 500 $/kW cooling. This is almost an order of magnitude lower than using a solar collector field of evacuated tube type.

  9. Project Assessment and Reporting System (PARS II) Data Quality Memo

    Broader source: Energy.gov [DOE]

    While PARS II is but one of many tools used to monitor project performance, when information and earned value data in the system are deficient and do not accurately reflect current project status or provide acceptable forecasts, effective project management is impaired. If we are to demonstrate long-term improvement in contract and project management, we must insist on project information that facilitates management, not impedes it.

  10. Evaluation of the Eological Management and Enhancement Alernative for Remediation of the K1007-P1 Pond

    SciTech Connect (OSTI)

    Peterson, M.J.

    2005-10-31

    An evaluation of the human and ecological risks associated with the P1 Pond and surrounding environs was conducted as part of the ETTP Site-Wide Remedial Investigation. The RI provides the basis for the focus on PCBs as the most important unacceptable risk to human and ecological health in the pond. Other P1 contaminants, media, or pathways of risk to receptors are identified in the RI, but are not addressed as a major risk reduction goal for the ETTP Site-Wide Feasibility Study. Therefore, the goal of the Ecological Management alternative is to reduce unacceptable risks associated with PCBs in fish. Many of the actions proposed for this alternative, however, are likely to reduce risks associated with other contaminants and their pathways. The high PCB concentrations in fish from the P1 Pond are most certainly due in part to the current ecological condition of the pond that maximizes PCB biomagnification. This basic assumption and the factors contributing to it were evaluated by conducting an intensive field study of the P1 Pond in the summer of 2004 (for a thorough presentation of current P1 Pond biological conditions, see Peterson et al. 2005). Major hypotheses regarding the P1 Pond's current fish community, PCB fate and transport processes, pond vegetation, and limnological conditions that contribute to the high PCB levels in fish were validated by the study (Appendix A), The results of the 2004 ecological assessment, in concert with long-term datasets obtained as part of the ETTP Biological Monitoring and Abatement Program (BMAP) and recent abiotic sampling for the RI, provide the basis for the assessment of current conditions.

  11. Heat extraction from salinity-gradient solar ponds using heat pipe heat exchangers

    SciTech Connect (OSTI)

    Tundee, Sura; Terdtoon, Pradit; Sakulchangsatjatai, Phrut; Singh, Randeep; Akbarzadeh, Aliakbar

    2010-09-15

    This paper presents the results of experimental and theoretical analysis on the heat extraction process from solar pond by using the heat pipe heat exchanger. In order to conduct research work, a small scale experimental solar pond with an area of 7.0 m{sup 2} and a depth of 1.5 m was built at Khon Kaen in North-Eastern Thailand (16 27'N102 E). Heat was successfully extracted from the lower convective zone (LCZ) of the solar pond by using a heat pipe heat exchanger made from 60 copper tubes with 21 mm inside diameter and 22 mm outside diameter. The length of the evaporator and condenser section was 800 mm and 200 mm respectively. R134a was used as the heat transfer fluid in the experiment. The theoretical model was formulated for the solar pond heat extraction on the basis of the energy conservation equations and by using the solar radiation data for the above location. Numerical methods were used to solve the modeling equations. In the analysis, the performance of heat exchanger is investigated by varying the velocity of inlet air used to extract heat from the condenser end of the heat pipe heat exchanger (HPHE). Air velocity was found to have a significant influence on the effectiveness of heat pipe heat exchanger. In the present investigation, there was an increase in effectiveness by 43% as the air velocity was decreased from 5 m/s to 1 m/s. The results obtained from the theoretical model showed good agreement with the experimental data. (author)

  12. Sandian Todd Lane's "Pond Crash Forensics" Project Receives

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Secretarial Notice Todd Lane's "Pond Crash Forensics" Project Receives Secretarial Notice - Sandia Energy Energy Search Icon Sandia Home Locations Contact Us Employee Locator Energy & Climate Secure & Sustainable Energy Future Stationary Power Energy Conversion Efficiency Solar Energy Wind Energy Water Power Supercritical CO2 Geothermal Natural Gas Safety, Security & Resilience of the Energy Infrastructure Energy Storage Nuclear Power & Engineering Grid

  13. In-place stabilization of pond ash deposits by hydrated lime columns

    SciTech Connect (OSTI)

    Chand, S.K.; Subbarao, C.

    2007-12-15

    Abandoned coal ash ponds cover up vast stretches of precious land and cause environmental problems. Application of suitable in situ stabilization methods may bring about improvement in the geotechnical properties of the ash deposit as a whole, converting it to a usable site. In this study, a technique of in-place stabilization by hydrated lime columns was applied to large-scale laboratory models of ash ponds. Samples collected from different radial distances and different depths of the ash deposit were tested to study the improvements in the water content, dry density, particle size distribution, unconfined compressive strength, pH, hydraulic conductivity, and leachate characteristics over a period of one year. The in-place stabilization by lime column technique has been found effective in increasing the unconfined compressive strength and reducing hydraulic conductivity of pond ash deposits in addition to modifying other geotechnical parameters. The method has also proved to be useful in reducing the contamination potential of the ash leachates, thus mitigating the adverse environmental effects of ash deposits.

  14. ENVIRONMENTAL PROBLEMS ASSOCIATED WITH DECOMMISSIONING THE CHERNOBYL NUCLEAR POWER PLANT COOLING POND

    SciTech Connect (OSTI)

    Farfan, E.

    2009-09-30

    Decommissioning of nuclear power plants and other nuclear fuel cycle facilities has been an imperative issue lately. There exist significant experience and generally accepted recommendations on remediation of lands with residual radioactive contamination; however, there are hardly any such recommendations on remediation of cooling ponds that, in most cases, are fairly large water reservoirs. The literature only describes remediation of minor reservoirs containing radioactive silt (a complete closure followed by preservation) or small water reservoirs resulting in reestablishing natural water flows. Problems associated with remediation of river reservoirs resulting in flooding of vast agricultural areas also have been described. In addition, the severity of environmental and economic problems related to the remedial activities is shown to exceed any potential benefits of these activities. One of the large, highly contaminated water reservoirs that require either remediation or closure is Karachay Lake near the MAYAK Production Association in the Chelyabinsk Region of Russia where liquid radioactive waste had been deep well injected for a long period of time. Backfilling of Karachay Lake is currently in progress. It should be noted that secondary environmental problems associated with its closure are considered to be of less importance since sustaining Karachay Lake would have presented a much higher radiological risk. Another well-known highly contaminated water reservoir is the Chernobyl Nuclear Power Plant (ChNPP) Cooling Pond, decommissioning of which is planned for the near future. This study summarizes the environmental problems associated with the ChNPP Cooling Pond decommissioning.

  15. Environmental Problems Associated With Decommissioning The Chernobyl Nuclear Power Plant Cooling Pond

    SciTech Connect (OSTI)

    Farfan, E. B.; Jannik, G. T.; Marra, J. C.; Oskolkov, B. Ya.; Bondarkov, M. D.; Gaschak, S. P.; Maksymenko, A. M.; Maksymenko, V. M.; Martynenko, V. I.

    2009-11-09

    Decommissioning of nuclear power plants and other nuclear fuel cycle facilities has been an imperative issue lately. There exist significant experience and generally accepted recommendations on remediation of lands with residual radioactive contamination; however, there are hardly any such recommendations on remediation of cooling ponds that, in most cases, are fairly large water reservoirs. The literature only describes remediation of minor reservoirs containing radioactive silt (a complete closure followed by preservation) or small water reservoirs resulting in reestablishing natural water flows. Problems associated with remediation of river reservoirs resulting in flooding of vast agricultural areas also have been described. In addition, the severity of environmental and economic problems related to the remedial activities is shown to exceed any potential benefits of these activities. One of the large, highly contaminated water reservoirs that require either remediation or closure is Karachay Lake near the MAYAK Production Association in the Chelyabinsk Region of Russia where liquid radioactive waste had been deep well injected for a long period of time. Backfilling of Karachay Lake is currently in progress. It should be noted that secondary environmental problems associated with its closure are considered to be of less importance since sustaining Karachay Lake would have presented a much higher radiological risk. Another well-known highly contaminated water reservoir is the Chernobyl Nuclear Power Plant (ChNPP) Cooling Pond, decommissioning of which is planned for the near future. This study summarizes the environmental problems associated with the ChNPP Cooling Pond decommissioning.

  16. A Screening Model to Predict Microalgae Biomass Growth in Photobioreactors and Raceway Ponds

    SciTech Connect (OSTI)

    Huesemann, Michael H.; Van Wagenen, Jonathan M.; Miller, Tyler W.; Chavis, Aaron R.; Hobbs, Watts B.; Crowe, Braden J.

    2013-06-01

    A microalgae biomass growth model was developed for screening novel strains for their potential to exhibit high biomass productivities under nutrient-replete conditions in photobioreactors or outdoor ponds. Growth is modeled by first estimating the light attenuation by biomass according to Beer-Lamberts law, and then calculating the specific growth rate in discretized culture volume slices that receive declining light intensities due to attenuation. The model requires only two physical and two species-specific biological input parameters, all of which are relatively easy to determine: incident light intensity, culture depth, as well as the biomass light absorption coefficient and the specific growth rate as a function of light intensity. Roux bottle culture experiments were performed with Nannochloropsis salina at constant temperature (23 C) at six different incident light intensities (5, 10, 25, 50, 100, 250, and 850 ?mol/m2? sec) to determine both the specific growth rate under non-shading conditions and the biomass light absorption coefficient as a function of light intensity. The model was successful in predicting the biomass growth rate in these Roux bottle cultures during the light-limited linear phase at different incident light intensities. Model predictions were moderately sensitive to minor variations in the values of input parameters. The model was also successful in predicting the growth performance of Chlorella sp. cultured in LED-lighted 800 L raceway ponds operated at constant temperature (30 C) and constant light intensity (1650 ?mol/m2? sec). Measurements of oxygen concentrations as a function of time demonstrated that following exposure to darkness, it takes at least 5 seconds for cells to initiate dark respiration. As a result, biomass loss due to dark respiration in the aphotic zone of a culture is unlikely to occur in highly mixed small-scale photobioreactors where cells move rapidly in and out of the light. By contrast, as supported also by the growth model, biomass loss due to dark respiration occurs in the dark zones of the relatively less well mixed pond cultures. In addition to screening novel microalgae strains for high biomass productivities, the model can also be used for optimizing the pond design and operation. Additional research is needed to validate the biomass growth model for other microalgae species and for the more realistic case of fluctuating temperatures and light intensities observed in outdoor pond cultures.

  17. PEP TALK "Policy - EVMS - PARS" Update, Mel Frank, Chief, Project Systems

    Energy Savers [EERE]

    Division, PM | Department of Energy PEP TALK "Policy - EVMS - PARS" Update, Mel Frank, Chief, Project Systems Division, PM PEP TALK "Policy - EVMS - PARS" Update, Mel Frank, Chief, Project Systems Division, PM Topics Discussed: New Handbooks New Terms and Definitions Training Opportunities/Snippets Data Driven Reviews Improvement Initiative Interpretation Handbook Current State/Challenges* Planned Enhancements Policy and Guidance / EVMS / PARS IIe PDF icon PEP Talk

  18. 2011 Annual Industrial Wastewater Reuse Report for the Idaho National Laboratory Site's Advanced Test Reactor Complex Cold Waste Pond

    SciTech Connect (OSTI)

    Mike Lewis

    2012-02-01

    This report describes conditions, as required by the state of Idaho Industrial Wastewater Reuse Permit (LA 000161 01, Modification B), for the wastewater land application site at the Idaho National Laboratory Site's Advanced Test Reactor Complex Cold Waste Pond from November 1, 2010 through October 31, 2011. The report contains the following information: Facility and system description Permit required effluent monitoring data and loading rates Groundwater monitoring data Status of compliance activities Noncompliance and other issues Discussion of the facility's environmental impacts During the 2011 permit year, approximately 166 million gallons of wastewater were discharged to the Cold Waste Pond. This is well below the maximum annual permit limit of 375 million gallons. As shown by the groundwater sampling data, sulfate and total dissolved solids concentrations are highest near the Cold Waste Pond and decrease rapidly as the distance from the Cold Waste Pond increases. Although concentrations of sulfate and total dissolved solids are elevated near the Cold Waste Pond, both parameters were below the Ground Water Quality Rule Secondary Constituent Standards in the down gradient monitoring wells.

  19. 2012 Annual Industrial Wastewater Reuse Report for the Idaho National Laboratory Site's Advanced Test Reactor Complex Cold Waste Pond

    SciTech Connect (OSTI)

    Mike Lewis

    2013-02-01

    This report describes conditions, as required by the state of Idaho Industrial Wastewater Reuse Permit (#LA 000161 01, Modification B), for the wastewater land application site at the Idaho National Laboratory Site’s Advanced Test Reactor Complex Cold Waste Pond from November 1, 2011 through October 31, 2012. The report contains the following information: Facility and system description Permit required effluent monitoring data and loading rates Groundwater monitoring data Status of compliance activities Noncompliance issues Discussion of the facility’s environmental impacts During the 2012 permit year, approximately 183 million gallons of wastewater were discharged to the Cold Waste Pond. This is well below the maximum annual permit limit of 375 million gallons. As shown by the groundwater sampling data, sulfate and total dissolved solids concentrations are highest near the Cold Waste Pond and decrease rapidly as the distance from the Cold Waste Pond increases. Although concentrations of sulfate and total dissolved solids are elevated near the Cold Waste Pond, both parameters were below the Ground Water Quality Rule Secondary Constituent Standards in the down gradient monitoring wells.

  20. Novel Adsorbent-Reactants for Treatment of Ash and Scrubber Pond Effluents

    SciTech Connect (OSTI)

    Bill Batchelor; Dong Suk Han; Eun Jung Kim

    2010-01-31

    The overall goal of this project was to evaluate the ability of novel adsorbent/reactants to remove specific toxic target chemicals from ash and scrubber pond effluents while producing stable residuals for ultimate disposal. The target chemicals studied were arsenic (As(III) and As(V)), mercury (Hg(II)) and selenium (Se(IV) and Se(VI)). The adsorbent/reactants that were evaluated are iron sulfide (FeS) and pyrite (FeS{sub 2}). Procedures for measuring concentrations of target compounds and characterizing the surfaces of adsorbent-reactants were developed. Effects of contact time, pH (7, 8, 9, 10) and sulfate concentration (0, 1, 10 mM) on removal of all target compounds on both adsorbent-reactants were determined. Stability tests were conducted to evaluate the extent to which target compounds were released from the adsorbent-reactants when pH changed. Surface characterization was conducted with x-ray photoelectron spectroscopy (XPS) to identify reactions occurring on the surface between the target compounds and surface iron and sulfur. Results indicated that target compounds could be removed by FeS{sub 2} and FeS and that removal was affected by time, pH and surface reactions. Stability of residuals was generally good and appeared to be affected by the extent of surface reactions. Synthesized pyrite and mackinawite appear to have the required characteristics for removing the target compounds from wastewaters from ash ponds and scrubber ponds and producing stable residuals.

  1. AmeriFlux US-Tw1 Twitchell Wetland West Pond

    DOE Data Explorer [Office of Scientific and Technical Information (OSTI)]

    Baldocchi, Dennis [University of California, Berkeley

    2016-01-01

    This is the AmeriFlux version of the carbon flux data for the site US-Tw1 Twitchell Wetland West Pond. Site Description - The Twitchell Wetland site is a 7.4-acre restored wetland on Twitchell Island, that is managed by the California Department of Water Resources (DWR) and the U.S. Geological Survey (USGS). In the fall of 1997, the site was permanently flooded to a depth of approximately 25 cm. The wetland was almost completely covered by cattails and tules by the third growing season. A flux tower equipped to analyze energy, H2O, CO2, and CH4 fluxes was installed on May 17, 2012.

  2. Report 20.5: Chromaticity Shift Modes of LED PAR38 Lamps Operated in

    Energy Savers [EERE]

    Steady-State Conditions | Department of Energy 5: Chromaticity Shift Modes of LED PAR38 Lamps Operated in Steady-State Conditions Report 20.5: Chromaticity Shift Modes of LED PAR38 Lamps Operated in Steady-State Conditions PDF icon Report 20.5: Chromaticity Shift Modes of LED PAR38 Lamps Operated in Steady-State Conditions More Documents & Publications Report 20.4: Lumen and Chromaticity Maintenance of LED PAR38 Lamps MARCH 2016 POSTINGS Retail Lamps Study 3.2: Lumen and Chromaticity

  3. DOE Publishes CALiPER Report on Chromaticity Shift Modes of LED PAR38 Lamps

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    | Department of Energy CALiPER Report on Chromaticity Shift Modes of LED PAR38 Lamps DOE Publishes CALiPER Report on Chromaticity Shift Modes of LED PAR38 Lamps March 23, 2016 - 11:33am Addthis The U.S. Department of Energy's CALiPER program has released Report 20.5, which is part of a series of investigations on LED PAR38 lamps. The new report builds on CALiPER Report 20.4 by providing a tear-down analysis of its 32 LED PAR38 lamp models and also performing additional analyses on the

  4. Text-Alternative Version: L Prize-PAR 38 Competition: A New Start

    Broader source: Energy.gov [DOE]

    Below is the text-alternative version of the "L Prize-PAR 38 Competition: A New Start" webcast, held March 27, 2012.

  5. Sampling and analysis plan for the 100-D Ponds voluntary remediation project

    SciTech Connect (OSTI)

    NONE

    1996-08-01

    This Sampling and Analysis Plan (SAP) describes the sampling and analytical activities which will be performed to support closure of the 100-D Ponds Resource Conservation and Recovery Act (RCRA) treatment, storage, and/or disposal (TSD) unit. This SAP includes the Field Sampling Plan (FSP) presented in Section 2.0, and the Quality Assurance Project Plan (QAPjP) described in Section 3.0. The FSP defines the sampling and analytical methodologies to be performed, and the QAPjP provides or includes information on the requirements for precision, accuracy, representativeness, comparability, and completeness of the analytical data. This sampling and analysis plan was developed using the Environmental Protection Agency`s Seven-Step Data Quality Objectives (DQO) Guidance (EPA, 1994). The purpose of the DQO meetings was (1) to identify the contaminants of concern and their cleanup levels under the Washington State Model Toxics Control Act (MTCA, WAC-173-340) Method B, and (2) to determine the number and locations of samples necessary to verify that the 100-D Ponds meet the cleanup criteria. The data collected will be used to support RCRA closure of this TSD unit.

  6. Development of baseline water quality stormwater detention pond model for Chesapeake Bay catchments

    SciTech Connect (OSTI)

    Musico, W.J.; Yoon, J.

    1999-07-01

    An environmental impact assessment is required for every proposed development in the Commonwealth of Virginia to help identify areas of potential concerns. The purpose of the Chesapeake Bay Local Assistance Department (CBLAD), Guidance Calculation Procedures is to ensure that development of previously constructed areas do not further exacerbate current problems of stormwater-induced eutrophication and downstream flooding. The methodology is based on the post development conditions that will not generate greater peak flows and will result in a 10% overall reduction of total phosphorus. Currently, several well-known models can develop hydrographs and pollutographs that accurately model the real response of a given watershed to any given rainfall event. However, conventional method of achieving the desired peak flow reduction and pollutant removal is not a deterministic procedure, and is inherently a trail and error process. A method of quickly and accurately determining the required size of stormwater easements was developed to evaluate the effectiveness of alternative stormwater collection and treatment systems. In this method, predevelopment conditions were modeled first to estimate the peak flows and subsequent pollutants generation that can be used as a baseline for post development plan. Resulting stormwater easement estimates facilitate decision-making processes during the planning and development phase of a project. The design can be optimized for the minimum cost or the smallest-possible pond size required for peak flow reduction and detention time given the most basic data such as: inflow hydrograph and maximum allowable pond depth.

  7. Post-Closure Groundwater Monitoring Plan for the 1324-N Surface Impoundment and 1324-NA Percolation Pond

    SciTech Connect (OSTI)

    Hartman, Mary J.

    2004-04-02

    The 1324-N Surface Impoundment and the 1324-NA Percolation Pond, located in the 100-N Area of the Hanford Site, are regulated under the Resource Consevation and Recovery Act (RCRA). Surface and underground features of the facilities have been removed and laboratory analyses showed that soil met the closure performance standards. These sites have been backfilled and revegetated.

  8. Corrective Action Investigation Plan for Corrective Action Unit 552: Area 12 Muckpile and Ponds, Nevada Test Site, Nevada: Revision 0

    SciTech Connect (OSTI)

    U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office

    2004-04-06

    This Corrective Action Investigation Plan contains the U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office's approach for collecting the data necessary to evaluate corrective action alternatives appropriate for the closure of Corrective Action Unit (CAU) 552: Area 12 Muckpile and Ponds, Nevada Test Site (NTS), Nevada, under the Federal Facility Agreement and Consent Order. Located in Area 12 on the NTS, CAU 552 consists of two Corrective Action Sites (CASs): 12-06-04, Muckpile; 12-23-05, Ponds. Corrective Action Site 12-06-04 in Area 12 consists of the G-Tunnel muckpile, which is the result of tunneling activities. Corrective Action Site 12-23-05 consists of three dry ponds adjacent to the muckpile. The toe of the muckpile extends into one of the ponds creating an overlap of two CASs. The purpose of the investigation is to ensure that adequate data are collected to provide sufficient and reliable information to identify, evaluate, and select technic ally viable corrective actions. The results of the field investigation will support a defensible evaluation of corrective action alternatives in the corrective action decision document.

  9. Post-Closure RCRA Groundwater Monitoring Plan for the 216-S-10 Pond and Ditch

    SciTech Connect (OSTI)

    Barnett, D BRENT.; Williams, Bruce A.; Chou, Charissa J.; Hartman, Mary J.

    2006-03-17

    The purpose of this plan is to provide a post-closure groundwater monitoring program for the 216-S-10 Pond and Ditch (S-10) treatment, storage, and/or disposal (TSD) unit. The plan incorporates the sum of knowledge about the potential for groundwater contamination to originate from the S-10, including groundwater monitoring results, hydrogeology, and operational history. The S-10 has not received liquid waste since October 1991. The closure of S-10 has been coordinated with the 200-CS-1 source operable unit in accordance with the Tri-Party Agreement interim milestones M-20-39 and M-15-39C. The S-10 is closely situated among other waste sites of very similar operational histories. The proximity of the S-10 to the other facilities (216-S-17 pond, 216-S-11 Pond, 216-S-5,6 cribs, 216-S-16 ditch and pond, and 216-U-9 ditch) indicate that at least some observed groundwater contamination beneath and downgradient of S-10 could have originated from waste sites other than S-10. Hence, it may not be feasible to strictly discriminate between the contributions of each waste site to groundwater contamination beneath the S-10. A post-closure groundwater monitoring network is proposed that will include the drilling of three new wells to replace wells that have gone dry. When completed, the revised network will meet the intent for groundwater monitoring network under WAC 173-303-645, and enable an improved understanding of groundwater contamination at the S-10. Site-specific sampling constituents are based on the dangerous waste constituents of concern relating to RCRA TSD unit operations (TSD unit constituents) identified in the Part A Permit Application. Thus, a constituent is selected for monitoring if it is: A dangerous waste constituent identified in the Part A Permit Application, or A mobile decomposition product (i.e., nitrate from nitrite) of a Part A constituent, or A reliable indicator of the site-specific contaminants (i.e., specific conductance). Using these criteria, the following constituent list and sampling schedule is proposed: Constituent; Sampling Frequency Site-Specific Parameters; Hexavalent chromium (a); Semiannual Chloride; Semiannual Fluoride; Semiannual Nitrate; Semiannual Nitrite; Semiannual Specific conductance (field)(a); Semiannual Ancillary Parameters; Anions; Annual Alkalinity Annual Metals, (in addition to chromium); Annual pH (field) Semiannual Temperature (field); Semiannual Turbidity (field) Semiannual (a). These constituents will be subject to statistical tests after background is established. It will be necessary to install new monitoring wells and accumulate background data on the groundwater from those wells before statistical comparisons can be made. Until then, the constituents listed above will be evaluated by tracking and trending concentrations in all wells and comparing these results with the corresponding DWS or Hanford Site background concentration for each constituent. If a comparison value (background or DWS) for a constituent is exceeded, DOE will notify Ecology per WAC 173-303-645 (9) (g) requirements (within seven days or a time agreed to between DOE and Ecology).

  10. Resistance and resilience of pond and stream ecosystems to toxicant stress: Project summary

    SciTech Connect (OSTI)

    Boston, H.L.; Stewart, A.J.; Johnson, A.R.; Bartell, S.M.

    1987-01-01

    This project will evaluate hypotheses concerning the resistance and resilience of aquatic ecosystems exposed to toxic chemicals. Our goals are to develop diagnostic criteria for ecosystem classification and to improve existing methods of ecological risk estimation. The development of models that predict ecosystem level effects requires quantifying the relationships between the underlying control structure of ecosystems (patterns of energy and material flux) and the contributions of thos structures to ecosystem resistance and resilience. We address these problems through an integration of manipulative experiments, multidimensional state space analysis, and ecosystem modeling. These studies will quantify the underlying rate structure in pond and stream systems (including, production, herbivory, nutrient uptake and recycling) and will measure changes in their structures in response to perturbations by toxicants.

  11. Thrombin induces rapid PAR1-mediated non-classical FGF1 release

    SciTech Connect (OSTI)

    Duarte, Maria; Kolev, Vihren; Soldi, Raffaella; Kirov, Alexander; Graziani, Irene; Oliveira, Silvia Marta; Kacer, Doreen; Friesel, Robert; Maciag, Thomas; Prudovsky, Igor . E-mail: prudoi@mmc.org

    2006-11-24

    Thrombin induces cell proliferation and migration during vascular injury. We report that thrombin rapidly stimulated expression and release of the pro-angiogenic polypeptide fibroblast growth factor 1 (FGF1). Thrombin failed to induce FGF1 release from protease-activated receptor 1 (PAR1) null fibroblasts, indicating that this effect was dependent on PAR1. Similarly to thrombin, FGF1 expression and release were induced by TRAP, a specific oligopeptide agonist of PAR1. These results identify a novel aspect of the crosstalk between FGF and thrombin signaling pathways which both play important roles in tissue repair and angiogenesis.

  12. DOE Publishes New CALiPER Report on Subjective Evaluation of LED PAR38 Lamps

    Broader source: Energy.gov [DOE]

    DOE has published the first in a series of four special investigations intended to extend the findings of CALiPER Application Summary Report 20: LED PAR38 Lamps, which was published late last year.

  13. CALiPER Report 20.5: Chromaticity Shift Modes of LED PAR38 Lamps...

    Energy Savers [EERE]

    ... Report 20.2: Dimming, Flicker, and Power Quality Characteristics of LED PAR38 Lamps (March 2014) 9 This report focused on the flicker and power quality performance of the Series 20 ...

  14. A validated model to predict microalgae growth in outdoor pond cultures subjected to fluctuating light intensities and water temperatures

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Huesemann, Michael H.; Crowe, Braden J.; Waller, Peter; Chavis, Aaron R.; Hobbs, Samuel J.; Edmundson, Scott J.; Wigmosta, Mark S.

    2015-12-11

    Here, a microalgae biomass growth model was developed for screening novel strains for their potential to exhibit high biomass productivities under nutrient-replete conditions in outdoor ponds subjected to fluctuating light intensities and water temperatures. Growth is modeled by first estimating the light attenuation by biomass according to a scatter-corrected Beer-Lambert Law, and then calculating the specific growth rate in discretized culture volume slices that receive declining light intensities due to attenuation. The model requires the following experimentally determined strain-specific input parameters: specific growth rate as a function of light intensity and temperature, biomass loss rate in the dark as amore » function of temperature and average light intensity during the preceding light period, and the scatter-corrected biomass light absorption coefficient. The model was successful in predicting the growth performance and biomass productivity of three different microalgae species (Chlorella sorokiniana, Nannochloropsis salina, and Picochlorum sp.) in raceway pond cultures (batch and semi-continuous) subjected to diurnal sunlight intensity and water temperature variations. Model predictions were moderately sensitive to minor deviations in input parameters. To increase the predictive power of this and other microalgae biomass growth models, a better understanding of the effects of mixing-induced rapid light dark cycles on photo-inhibition and short-term biomass losses due to dark respiration in the aphotic zone of the pond is needed.« less

  15. A validated model to predict microalgae growth in outdoor pond cultures subjected to fluctuating light intensities and water temperatures

    SciTech Connect (OSTI)

    Huesemann, Michael H.; Crowe, Braden J.; Waller, Peter; Chavis, Aaron R.; Hobbs, Samuel J.; Edmundson, Scott J.; Wigmosta, Mark S.

    2015-12-11

    Here, a microalgae biomass growth model was developed for screening novel strains for their potential to exhibit high biomass productivities under nutrient-replete conditions in outdoor ponds subjected to fluctuating light intensities and water temperatures. Growth is modeled by first estimating the light attenuation by biomass according to a scatter-corrected Beer-Lambert Law, and then calculating the specific growth rate in discretized culture volume slices that receive declining light intensities due to attenuation. The model requires the following experimentally determined strain-specific input parameters: specific growth rate as a function of light intensity and temperature, biomass loss rate in the dark as a function of temperature and average light intensity during the preceding light period, and the scatter-corrected biomass light absorption coefficient. The model was successful in predicting the growth performance and biomass productivity of three different microalgae species (Chlorella sorokiniana, Nannochloropsis salina, and Picochlorum sp.) in raceway pond cultures (batch and semi-continuous) subjected to diurnal sunlight intensity and water temperature variations. Model predictions were moderately sensitive to minor deviations in input parameters. To increase the predictive power of this and other microalgae biomass growth models, a better understanding of the effects of mixing-induced rapid light dark cycles on photo-inhibition and short-term biomass losses due to dark respiration in the aphotic zone of the pond is needed.

  16. Fractionation of heavy metals in sludge from anaerobic wastewater stabilization ponds in southern Spain

    SciTech Connect (OSTI)

    Alonso, E.

    2006-07-01

    The analysis of heavy metals is a very important task to assess the potential environmental and health risk associated with the sludge coming from wastewater treatment plants (WWTPs). However, it is necessary to apply sequential extraction techniques to obtain suitable information about their bioavailability or toxicity. In this paper, a sequential extraction scheme according to the Standard, Measurements and Testing Programme of the European Commission was applied to sludge samples collected from ten anaerobic wastewater stabilization ponds (WSPs) located in southern Spain. Al, Cd, Co, Cr, Cu, Fe, Hg, Mn, Mo, Ni, Pb, Ti and Zn were determined in the sludge extracts by inductively coupled plasma atomic emission spectrometry. In relation to current international legislation for the use of sludge for agricultural purposes, none of the metal concentrations exceeded maximum permitted levels. Overall, heavy metals were mainly associated with the two less-available fractions (34% oxidizable metal and 55% residual metal). Only Mn and Zn showed the highest share of the available (exchangeable and reducible) fractions (25-48%)

  17. Text-Alternative Version: CALiPER Report Series 20 on LED PAR38 Lamps |

    Energy Savers [EERE]

    Department of Energy Text-Alternative Version: CALiPER Report Series 20 on LED PAR38 Lamps Text-Alternative Version: CALiPER Report Series 20 on LED PAR38 Lamps Michael Royer, Lighting Engineer, Pacific Northwest National Laboratory: The CALiPER program looks at typical LED lamp performance attributes. As we've gone through the progression of reports, we've really seen that a lot of times we're coming to the same conclusions-- that based on basic performance, LED products, at least some of

  18. 2014 Annual Industrial Wastewater Reuse Report for the Idaho National Laboratory Site’s Advanced Test Reactor Complex Cold Waste Pond

    SciTech Connect (OSTI)

    Lewis, Mike

    2015-02-01

    This report describes conditions, as required by the state of Idaho Industrial Wastewater Reuse Permit (LA 000161 01, Modification B), for the wastewater land application site at the Idaho National Laboratory Site’s Advanced Test Reactor Complex Cold Waste Pond from November 1, 2013–October 31, 2014. The report contains the following information; Facility and system description; Permit required effluent monitoring data and loading rates; Permit required groundwater monitoring data; Status of compliance activities; Noncompliance issues; and Discussion of the facility’s environmental impacts. During the 2014 permit year, approximately 238 million gallons of wastewater were discharged to the Cold Waste Pond. This is well below the maximum annual permit limit of 375 million gallons. As shown by the groundwater sampling data, sulfate and total dissolved solids concentrations are highest near the Cold Waste Pond and decrease rapidly as the distance from the Cold Waste Pond increases. Although concentrations of sulfate and total dissolved solids are elevated near the Cold Waste Pond, both parameters are below the Ground Water Quality Rule Secondary Constituent Standards in the downgradient monitoring wells.

  19. 2010 Annual Industrial Wastewater Reuse Report for the Idaho National Laboratory Site’s Advanced Test Reactor Complex Cold Waste Pond

    SciTech Connect (OSTI)

    mike lewis

    2011-02-01

    This report describes conditions, as required by the state of Idaho Industrial Wastewater Reuse Permit (#LA 000161 01, Modification B), for the wastewater land application site at the Idaho National Laboratory Site’s Advanced Test Reactor Complex Cold Waste Pond from November 1, 2009 through October 31, 2010. The report contains the following information: • Facility and system description • Permit required effluent monitoring data and loading rates • Groundwater monitoring data • Status of compliance activities • Discussion of the facility’s environmental impacts During the 2010 permit year, approximately 164 million gallons of wastewater were discharged to the Cold Waste Pond. As shown by the groundwater sampling data, sulfate and total dissolved solids concentrations are highest near the Cold Waste Pond and decrease rapidly as the distance from the Cold Waste Pond increases. Although concentrations of sulfate and total dissolved solids are elevated near the Cold Waste Pond, both parameters were below the Ground Water Quality Rule Secondary Constituent Standards in the down gradient monitoring wells.

  20. 2013 Annual Industrial Wastewater Reuse Report for the Idaho National Laboratory Site’s Advanced Test Reactor Complex Cold Waste Pond

    SciTech Connect (OSTI)

    Mike Lewis

    2014-02-01

    This report describes conditions, as required by the state of Idaho Industrial Wastewater Reuse Permit (#LA 000161 01, Modification B), for the wastewater land application site at the Idaho National Laboratory Site’s Advanced Test Reactor Complex Cold Waste Pond from November 1, 2012–October 31, 2013. The report contains the following information: • Facility and system description • Permit required effluent monitoring data and loading rates • Groundwater monitoring data • Status of compliance activities • Noncompliance issues • Discussion of the facility’s environmental impacts. During the 2013 permit year, approximately 238 million gallons of wastewater was discharged to the Cold Waste Pond. This is well below the maximum annual permit limit of 375 million gallons. As shown by the groundwater sampling data, sulfate and total dissolved solids concentrations are highest near the Cold Waste Pond and decrease rapidly as the distance from the Cold Waste Pond increases. Although concentrations of sulfate and total dissolved solids are elevated near the Cold Waste Pond, both parameters are below the Ground Water Quality Rule Secondary Constituent Standards in the down gradient monitoring wells.

  1. A rational approach for evaluation and screening of treatment and disposal options for the solar pond sludges at Rocky Flats

    SciTech Connect (OSTI)

    Dickerson, K.S.

    1995-12-31

    This document consists of information about the treatment options for the sludge that is located in the evaporation ponds at the Rocky Flats Plant. The sludges are mixed low-level radioactive wastes whose composition and character were variable. Sludges similar to these are typically treated prior to ultimate disposal. Disposal of treated sludges includes both on-site and off-site options. The rational approach described in this paper is useful for technology evaluation and screening because it provides a format for developing objectives, listing alternatives, and weighing the alternatives against the objectives and against each other.

  2. Resource Conservation and Recovery Act industrial site environmental restoration site characterization report - area 6 steam cleaning effluent ponds

    SciTech Connect (OSTI)

    1996-09-01

    The Area 6 North and South Steam Cleaning Effluent Ponds (SCEPs) are historic disposal units located at the Nevada Test Site (NTS) in Nye County, Nevada. The NTS is operated by the U.S. Department of Energy, Nevada Operations Office (DOE/NV) which has been required by the Nevada Division of Environmental Protection (NDEP) to characterize the site under the requirements of the Resource Conservation and Recovery Act (RCRA) Part B Permit for the NTS and Title 40 Code of Federal Regulations, Part 265.

  3. Post-closure permit application for the Upper East Fork Poplar Creek hydrogeologic regime at the Y-12 Plant: New Hope Pond and Eastern S-3 ponds plume. Revision 2

    SciTech Connect (OSTI)

    1995-02-01

    The intent of this Post-Closure, Permit Application (PCPA) is to satisfy the post-closure permitting requirements of the Tennessee Department of Environment and Conservation (TDEC) Rule 1200-1-11. This application is for the entire Upper East Fork Poplar Creek Hydrogeologic Regime (East Fork Regime), which is within the Bear Creek Valley (BCV). This PCPA has been prepared to include the entire East Fork Regime because, although there are numerous contaminant sources within the regime, the contaminant plumes throughout the East Fork Regime have coalesced and can no longer be distinguished as separate plumes. This PCPA focuses on two recognized Resource Conservation and Recovery Act (RCRA) interim status units: New Hope Pond (NHP) and the eastern S-3 Ponds plume. This PCPA presents data from groundwater assessment monitoring throughout the regime, performed since 1986. Using this data, this PCPA demonstrates that NHP is not a statistically discernible source of groundwater contaminants and that sites upgradient of NHP are the likely sources of groundwater contamination seen in the NHP vicinity. As such, this PCPA proposes a detection monitoring program to replace the current assessment monitoring program for NHP.

  4. Report 20.3: Stress Testing of LED PAR38 Lamps

    Broader source: Energy.gov [DOE]

    A small sample of each of the Application Summary Report 20 PAR38 lamp types underwent stress testing that included substantial temperature and humidity changes, electrical variation, and vibration. The results do not directly address expected lifetime, but can be compared with one another, as well as with benchmark conventional products, to assess the relative robustness of the product designs. (24 pages, December 2014)

  5. CALiPER Report 20.3: Robustness of LED PAR38 Lamps

    SciTech Connect (OSTI)

    none,

    2014-12-30

    A small sample of each of the CALiPER Application Summary Report 20 PAR38 lamp types underwent stress testing that included substantial temperature and humidity changes, electrical variation, and vibration. The results do not directly address expected lifetime, but can be compared with one another, as well as with benchmark conventional products, to assess the relative robustness of the product designs.

  6. Project Plan 7930 Cell G PaR Remote Handling System Replacement

    SciTech Connect (OSTI)

    Kinney, Kathryn A

    2009-10-01

    For over 40 years the US Department of Energy (DOE) and its predecessors have made Californium-252 ({sup 252}Cf) available for a wide range of industries including medical, nuclear fuels, mining, military and national security. The Radiochemical Engineering Development Center (REDC) located within the Oak Ridge National Laboratory (ORNL) processes irradiated production targets from the High Flux Isotope Reactor (HFIR). Operations in Building 7930, Cell G provide over 70% of the world's demand for {sup 252}Cf. Building 7930 was constructed and equipped in the mid-1960s. Current operations for {sup 252}Cf processing in Building 7930, Cell G require use of through-the-wall manipulators and the PaR Remote Handling System. Maintenance and repairs for the manipulators is readily accomplished by removal of the manipulator and relocation to a repair shop where hands-on work can be performed in glove boxes. Contamination inside cell G does not currently allow manned entry and no provisions were created for a maintenance area inside the cell. There has been no maintenance of the PaR system or upgrades, leaving operations vulnerable should the system have a catastrophic failure. The Cell G PaR system is currently being operated in a run to failure mode. As the manipulator is now 40+ years old there is significant risk in this method of operation. In 2006 an assessment was completed that resulted in recommendations for replacing the manipulator operator control and power centers which are used to control and power the PaR manipulator in Cell G. In mid-2008 the chain for the bridge drive failed and subsequent examinations indicated several damaged links (see Figure 1). To continue operations the PaR manipulator arm is being used to push and pull the bridge as a workaround. A retrieval tool was fabricated, tested and staged inside Cell G that will allow positioning of the bridge and manipulator arm for removal from the cell should the PaR system completely fail. A fully functioning and reliable Par manipulator arm is necessary for uninterrupted {sup 252}Cf operations; a fully-functioning bridge is needed for the system to function as intended.

  7. Design and analysis of microalgal open pond systems for the purpose of producing fuels: A subcontract report

    SciTech Connect (OSTI)

    Weissman, J.C.; Goebel, R.P.

    1987-04-01

    The designs and systems developed include many innovative concepts and experiments, including the design and operation of a low-cost system. Cost-effectiveness is realized by minimizing capital costs of the system and achieving efficient use of inputs. Extensive engineering analysis of carbonation, mixing, and harvesting subsystems has elucidated both the lowest cost, most efficient options and the essential parameters needed to construct, test, and evaluate these subsystems. The use of growth ponds sealed with clay and lined with crushed rock results in construction cost savings of 50% over ponds lined with synthetic membranes. In addition a low-cost but efficient design allows improvements in technology to have maximum impact on final product cost reductions. In addition to the innovations in low-cost construction, the operational efficiency of the design is both higher and more feasible than that attained by any previous system concept of comparable scale. The water analysis has led to operational specifications that minimize water use and virtually eliminate losses of carbon dioxide to the atmosphere. The carbon dioxide injection system is designed for 95% efficiency, but is still low in cost. The construction of a large-scale, covered anaerobic lagoon to recycle carbon, nitrogen, and phosphorus has not been attempted at the scale analyzed here. Yet efficient recycling is essential for achieving economic affordability. 23 refs., 21 figs., 53 tabs.

  8. CALiPER Report 20.1: Quality of Beam, Shadow, and Color in LED PAR38 Lamps

    Energy Savers [EERE]

    | Department of Energy CALiPER Report 20.1: Quality of Beam, Shadow, and Color in LED PAR38 Lamps CALiPER Report 20.1: Quality of Beam, Shadow, and Color in LED PAR38 Lamps View the video about CALiPER Report 20.1 which focuses on human-evaluated characteristics, including beam quality, shadow quality, and color quality in LED PAR38 lamps. View the text-alternative version. Solid-State Lighting Home About the Solid-State Lighting Program Research & Development

  9. CALiPER Application Summary Report 20. LED PAR38 Lamps

    SciTech Connect (OSTI)

    none,

    2012-11-01

    This report analyzes the independently tested photometric performance of 38 LED PAR38 lamps. The test results indicate substantial improvement versus earlier CALiPER testing of similar products, and performance comparable to recent data from LED Lighting Facts and ENERGY STAR. Additional testing that focuses on performance attributes beyond those covered by LM-79-08 is planned for this group of lamps, and will be presented in subsequent reports.

  10. Exploring the Utilization of Complex Algal Communities to Address Algal Pond Crash and Increase Annual Biomass Production for Algal Biofuels

    SciTech Connect (OSTI)

    Hamilton, Cyd E.

    2014-03-25

    This white paper briefly reviews the research literature exploring complex algal communities as a means of increasing algal biomass production via increased tolerance, resilience, and resistance to a variety of abiotic and biotic perturbations occurring within harvesting timescales. This paper identifies what data are available and whether more research utilizing complex communities is needed to explore the potential of complex algal community stability (CACS) approach as a plausible means to increase biomass yields regardless of ecological context and resulting in decreased algal-based fuel prices by reducing operations costs. By reviewing the literature for what we do and do not know, in terms of CACS methodologies, this report will provide guidance for future research addressing pond crash phenomena.

  11. Application | SREL REU in Radioecology

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    boat ride on Par Pond ***APPLICATIONS FOR SUMMER 2016 ARE CLOSED*** We will begin taking applications for 2017 this fall.

  12. Waste Characteristics of the Former S-3 Ponds and Outline of Uranium Chemistry Relevant to NABIR Field Research Center Studies

    SciTech Connect (OSTI)

    Brooks, S.C.

    2001-06-29

    The Environmental Sciences Division at Oak Ridge National Laboratory (ORNL) was awarded the first Naturaland Accelerated Bioremediation Research (NABIR) Program, Field Research Center (FRC) based upon the recommendation of a review panel following a competitive peer-reviewed proposal process. The contaminated FRC site at ORNL is centered on groundwater plumes that originate from the former S-3 Waste Disposal Ponds located at the Y-12 Plant and the Y-12 Bone Yard/Bum Yard. Proposals for individual science research projects at the FRC were submitted in the spring of 2000 in response to a solicitation issued by the Department of Energy (DOE). Proposals selected for funding began work in Fiscal Year 2001 (October 1, 2000). The FRC staff have initiated several characterization efforts intended to support, inform, and educate individual FRC investigators, NABIR principal investigators (PIs), and the broader community of the specific conditions, opportunities, and challenges of this site. These efforts include both physical site characterization as well as numerical simulation (modeling) studies. Geochemical modeling has been conducted with the goal of: (1) providing a baseline understanding of the geochemical behavior of uranium (U); (2) examining the interaction of geochemistry and uranium transport in the subsurface; (3) elucidating some potential pitfalls for researchers with respect to manipulating subsurface environments for the purpose of demonstrating bacterially induced U immobilization. The geochemical modeling effort focused on using existing data and resources and did not involve the collection of new data or samples from the field site. Specifically, the following three tasks have been performed to date. (1) Searching for information on the wastes disposed in to the S-3 ponds. These data are typically found in internal technical reports at the labs and are rarely published in the peer-reviewed literature; thus, this information can be very difficult for the scientific community to access. Therefore, these searches may provide a nontrivial resource to investigators. To that end, some analytical data have already been located and the search for more data will continue. (2) Critical evaluation of thermodynamic data that are needed in the modeling calculations. (3) Generating model simulations to illustrate important aspects of U geochemistry and transport behavior in idealized solutions. This report summarizes the results of the geochemical modeling efforts.

  13. 2011 Annual Industrial Wastewater Reuse Report for the Idaho National Laboratory Site's Materials and Fuels Complex Industrial Waste Ditch and Industrial Waste Pond

    SciTech Connect (OSTI)

    David Frederick

    2012-02-01

    This report describes conditions, as required by the state of Idaho Industrial Wastewater Reuse Permit (LA-000160-01), for the wastewater reuse site at the Idaho National Laboratory Site's Materials and Fuels Complex Industrial Waste Ditch and Industrial Waste Pond from November 1, 2010 through October 31, 2011. The report contains the following information: (1) Facility and system description; (2) Permit required effluent monitoring data and loading rates; (3) Groundwater monitoring data; (4) Status of special compliance conditions; and (5) Discussion of the facility's environmental impacts. During the 2011 reporting year, an estimated 6.99 million gallons of wastewater were discharged to the Industrial Waste Ditch and Pond which is well below the permit limit of 13 million gallons per year. Using the dissolved iron data, the concentrations of all permit-required analytes in the samples from the down gradient monitoring wells were below the Ground Water Quality Rule Primary and Secondary Constituent Standards.

  14. 2014 Annual Industrial Wastewater Reuse Report for the Idaho National Laboratory Site’s Materials and Fuels Complex Industrial Waste Ditch and Industrial Waste Pond

    SciTech Connect (OSTI)

    Lewis, Mike

    2015-02-01

    This report describes conditions, as required by the state of Idaho Industrial Wastewater Reuse Permit (WRU-I-0160-01, formerly LA 000160 01), for the wastewater reuse site at the Idaho National Laboratory Site’s Materials and Fuels Complex Industrial Waste Ditch and Industrial Waste Pond from November 1, 2013 through October 31, 2014. The report contains the following information; Facility and system description; Permit required effluent monitoring data and loading rates; Groundwater monitoring data; Status of special compliance conditions; Noncompliance issues; and Discussion of the facility’s environmental impacts During the 2014 reporting year, an estimated 10.11 million gallons of wastewater were discharged to the Industrial Waste Ditch and Pond which is well below the permit limit of 17 million gallons per year. The concentrations of all permit-required analytes in the samples from the down gradient monitoring wells were below the applicable Idaho Department of Environmental Quality’s groundwater quality standard levels.

  15. 2012 Annual Industrial Wastewater Reuse Report for the Idaho National Laboratory Site’s Materials and Fuels Complex Industrial Waste Ditch and Industrial Waste Pond

    SciTech Connect (OSTI)

    Mike Lewis

    2013-02-01

    This report describes conditions, as required by the state of Idaho Industrial Wastewater Reuse Permit (WRU-I-0160-01, formerly LA 000160 01), for the wastewater reuse site at the Idaho National Laboratory Site’s Materials and Fuels Complex Industrial Waste Ditch and Industrial Waste Pond from November 1, 2011 through October 31, 2012. The report contains the following information: • Facility and system description • Permit required effluent monitoring data and loading rates • Groundwater monitoring data • Status of special compliance conditions • Discussion of the facility’s environmental impacts During the 2012 reporting year, an estimated 11.84 million gallons of wastewater were discharged to the Industrial Waste Ditch and Pond which is well below the permit limit of 17 million gallons per year. The concentrations of all permit-required analytes in the samples from the down gradient monitoring wells were below the Ground Water Quality Rule Primary and Secondary Constituent Standards.

  16. 2010 Annual Industrial Wastewater Reuse Report for the Idaho National Laboratory Site's Materials and Fuels Complex Industrial Waste Ditch and Industrial Waste Pond

    SciTech Connect (OSTI)

    David B. Frederick

    2011-02-01

    This report describes conditions, as required by the state of Idaho Industrial Wastewater Reuse Permit (#LA 000160 01), for the wastewater reuse site at the Idaho National Laboratory Site’s Materials and Fuels Complex Industrial Waste Ditch and Industrial Waste Pond from May 1, 2010 through October 31, 2010. The report contains the following information: • Facility and system description • Permit required effluent monitoring data and loading rates • Groundwater monitoring data • Status of special compliance conditions • Discussion of the facility’s environmental impacts During the 2010 partial reporting year, an estimated 3.646 million gallons of wastewater were discharged to the Industrial Waste Ditch and Pond which is well below the permit limit of 13 million gallons per year. The concentrations of all permit-required analytes in the samples from the down gradient monitoring wells were below the Ground Water Quality Rule Primary and Secondary Constituent Standards.

  17. Apparatus for in situ determination of burnup, cooling time and fissile content of an irradiated nuclear fuel assembly in a fuel storage pond

    DOE Patents [OSTI]

    Phillips, J.R.; Halbig, J.K.; Menlove, H.O.; Klosterbuer, S.F.

    1984-01-01

    A detector head for in situ inspection of irradiated nuclear fuel assemblies submerged in a water-filled nuclear fuel storage pond. The detector head includes two parallel arms which extend from a housing and which are spaced apart so as to be positionable on opposite sides of a submerged fuel assembly. Each arm includes an ionization chamber and two fission chambers. One fission chamber in each arm is enclosed in a cadmium shield and the other fission chamber is unshielded. The ratio of the outputs of the shielded and unshielded fission chambers is used to determine the boron content of the pond water. Correcting for the boron content, the neutron flux and gamma ray intensity are then used to verify the declared exposure, cooling time and fissile material content of the irradiated fuel assembly.

  18. Apparatus for in situ determination of burnup, cooling time and fissile content of an irradiated nuclear fuel assembly in a fuel storage pond

    DOE Patents [OSTI]

    Phillips, John R.; Halbig, James K.; Menlove, Howard O.; Klosterbuer, Shirley F.

    1985-01-01

    A detector head for in situ inspection of irradiated nuclear fuel assemblies submerged in a water-filled nuclear fuel storage pond. The detector head includes two parallel arms which extend from a housing and which are spaced apart so as to be positionable on opposite sides of a submerged fuel assembly. Each arm includes an ionization chamber and two fission chambers. One fission chamber in each arm is enclosed in a cadmium shield and the other fission chamber is unshielded. The ratio of the outputs of the shielded and unshielded fission chambers is used to determine the boron content of the pond water. Correcting for the boron content, the neutron flux and gamma ray intensity are then used to verify the declared exposure, cooling time and fissile material content of the irradiated fuel assembly.

  19. RADIATION DOSE ASSESSMENT FOR THE BIOTA OF TERRESTRIAL ECOSYSTEMS IN THE SHORELINE ZONE OF THE CHERNOBYL NUCLEAR POWER PLANT COOLING POND

    SciTech Connect (OSTI)

    Farfan, E.; Jannik, T.

    2011-10-01

    Radiation exposure of the biota in the shoreline area of the Chernobyl Nuclear Power Plant Cooling Pond was assessed to evaluate radiological consequences from the decommissioning of the Cooling Pond. The article addresses studies of radioactive contamination of the terrestrial faunal complex and radionuclide concentration ratios in bodies of small birds, small mammals, amphibians, and reptiles living in the area. The data were used to calculate doses to biota using the ERICA Tool software. Doses from {sup 90}Sr and {sup 137}Cs were calculated using the default parameters of the ERICA Tool and were shown to be consistent with biota doses calculated from the field data. However, the ERICA dose calculations for plutonium isotopes were much higher (2-5 times for small mammals and 10-14 times for birds) than the doses calculated using the experimental data. Currently, the total doses for the terrestrial biota do not exceed maximum recommended levels. However, if the Cooling Pond is allowed to drawdown naturally and the contaminants of the bottom sediments are exposed and enter the biological cycle, the calculated doses to biota may exceed the maximum recommended values. The study is important in establishing the current exposure conditions such that a baseline exists from which changes can be documented following the lowering of the reservoir water. Additionally, the study provided useful radioecological data on biota concentration ratios for some species that are poorly represented in the literature.

  20. Recycled Water Reuse Permit Renewal Application for the Materials and Fuels Complex Industrial Waste Ditch and Industrial Waste Pond

    SciTech Connect (OSTI)

    No Name

    2014-10-01

    ABSTRACT This renewal application for the Industrial Wastewater Reuse Permit (IWRP) WRU-I-0160-01 at Idaho National Laboratory (INL), Materials and Fuels Complex (MFC) Industrial Waste Ditch (IWD) and Industrial Waste Pond (IWP) is being submitted to the State of Idaho, Department of Environmental Quality (DEQ). This application has been prepared in compliance with the requirements in IDAPA 58.01.17, Recycled Water Rules. Information in this application is consistent with the IDAPA 58.01.17 rules, pre-application meeting, and the Guidance for Reclamation and Reuse of Municipal and Industrial Wastewater (September 2007). This application is being submitted using much of the same information contained in the initial permit application, submitted in 2007, and modification, in 2012. There have been no significant changes to the information and operations covered in the existing IWRP. Summary of the monitoring results and operation activity that has occurred since the issuance of the WRP has been included. MFC has operated the IWP and IWD as regulated wastewater land treatment facilities in compliance with the IDAPA 58.01.17 regulations and the IWRP. Industrial wastewater, consisting primarily of continuous discharges of nonhazardous, nonradioactive, routinely discharged noncontact cooling water and steam condensate, periodic discharges of industrial wastewater from the MFC facility process holdup tanks, and precipitation runoff, are discharged to the IWP and IWD system from various MFC facilities. Wastewater goes to the IWP and IWD with a permitted annual flow of up to 17 million gallons/year. All requirements of the IWRP are being met. The Operations and Maintenance Manual for the Industrial Wastewater System will be updated to include any new requirements.

  1. DOE Publishes CALiPER Report on Dimming, Flicker, and Power Quality Characteristics of LED PAR38 Lamps

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy's CALiPER program has released Report 20.2, which is part of a series of investigations on LED PAR38 lamps. Report 20.2 focuses on dimming, flicker, and power quality...

  2. Corrective Action Investigation Plan for Corrective Action Unit 552: Area 12 Muckpile and Ponds, Nevada Test Site, Nevada, Rev. No.: 1 with ROTC 1 and 2

    SciTech Connect (OSTI)

    David A. Strand

    2005-01-01

    This Corrective Action Investigation Plan (CAIP) contains project-specific information including facility descriptions, environmental sample collection objectives, and criteria for conducting site investigation activities at Corrective Action Unit (CAU) 552: Area 12 Muckpile and Ponds, Nevada Test Site (NTS), Nevada. This CAIP has been developed in accordance with the ''Federal Facility Agreement and Consent Order'' (FFACO) (1996) that was agreed to by the State of Nevada, the U.S. Department of Energy (DOE), and the U.S. Department of Defense. The NTS is approximately 65 miles (mi) northwest of Las Vegas, Nevada (Figure 1-1). Corrective Action Unit 552 is comprised of the one Corrective Action Site which is 12-23-05, Ponds. One additional CAS, 12-06-04, Muckpile (G-Tunnel Muckpile), was removed from this CAU when it was determined that the muckpile is an active site. A modification to the FFACO to remove CAS 12-06-04 was approved by the Nevada Division of Environmental Protection (NDEP) on December 16, 2004. The G-Tunnel ponds were first identified in the 1991 Reynolds Electrical & Engineering Co., Inc. document entitled, ''Nevada Test Site Inventory of Inactive and Abandoned Facilities and Waste Sites'' (REECo, 1991). Corrective Action Unit 552 is being investigated because existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend corrective action alternatives. Therefore, additional information will be obtained by conducting a corrective action investigation (CAI) prior to evaluating and selecting the corrective action alternatives for the site. The CAI will include field inspections, radiological surveys, and sampling of appropriate media. Data will also be obtained to support investigation-derived waste (IDW) disposal and potential future waste management decisions.

  3. Portable instrument for inspecting irradiated nuclear-fuel assemblies in a water-filled storage pond by measurement of induced Cerenkov radiation

    DOE Patents [OSTI]

    Nicholson, N.; Dowdy, E.J.; Holt, D.M.; Stump, C.J. Jr.

    1982-05-13

    A portable instrument for measuring induced Cerenkov radiation associated with irradiated nuclear fuel assemblies in a water-filled storage pond is disclosed. The instrument includes a photomultiplier tube and an image intensifier which are operable in parallel and simultaneously by means of a field lens assembly and an associated beam splitter. The image intensifier permits an operator to aim and focus the apparatus on a submerged fuel assembly. Once the instrument is aimed and focused, an illumination reading can be obtained with the photomultiplier tube. The instrument includes a lens cap with a carbon-14/phosphor light source for calibrating the apparatus in the field.

  4. 2013 Annual Industrial Wastewater Reuse Report for the Idaho National Laboratory Site’s Materials and Fuels Complex Industrial Waste Ditch and Industrial Waste Pond

    SciTech Connect (OSTI)

    Mike Lewis

    2014-02-01

    This report describes conditions, as required by the state of Idaho Industrial Wastewater Reuse Permit (WRU-I-0160-01, formerly LA 000160 01), for the wastewater reuse site at the Idaho National Laboratory Site’s Materials and Fuels Complex Industrial Waste Ditch and Industrial Waste Pond from November 1, 2012 through October 31, 2013. The report contains the following information: • Facility and system description • Permit required effluent monitoring data and loading rates • Groundwater monitoring data • Status of special compliance conditions • Discussion of the facility’s environmental impacts During the 2013 reporting year, an estimated 9.64 million gallons of wastewater were discharged to the Industrial Waste Ditch and Pond which is well below the permit limit of 17 million gallons per year. The concentrations of all permit-required analytes in the samples from the down gradient monitoring wells were below the applicable Idaho Department of Environmental Quality’s groundwater quality standard levels.

  5. CALiPER Report 20.3: Robustness of LED PAR38 Lamps

    SciTech Connect (OSTI)

    Poplawski, Michael E.; Royer, Michael P.; Brown, Charles C.

    2014-12-31

    Three samples of 40 of the Series 20 PAR38 lamps underwent multi-stress testing, whereby samples were subjected to increasing levels of simultaneous thermal, humidity, electrical, and vibrational stress. The results do not explicitly predict expected lifetime or reliability, but they can be compared with one another, as well as with benchmark conventional products, to assess the relative robustness of the product designs. On average, the 32 LED lamp models tested were substantially more robust than the conventional benchmark lamps. As with other performance attributes, however, there was great variability in the robustness and design maturity of the LED lamps. Several LED lamp samples failed within the first one or two levels of the ten-level stress plan, while all three samples of some lamp models completed all ten levels. One potential area of improvement is design maturity, given that more than 25% of the lamp models demonstrated a difference in failure level for the three samples that was greater than or equal to the maximum for the benchmarks. At the same time, the fact that nearly 75% of the lamp models exhibited better design maturity than the benchmarks is noteworthy, given the relative stage of development for the technology.

  6. CALiPER Report 20.1: Subjective Evaluation of Beam Quality, Shadow Quality, and Color Quality for LED PAR38 Lamps

    Broader source: Energy.gov [DOE]

    This December 3, 2013 webinar explored the findings of CALiPER 20.1: Subjective Evaluation of Beam Quality, Shadow Quality, and Color Quality for LED PAR38 Lamps and discussed what attributes to...

  7. Radiological Monitoring Results For Groundwater Samples Associated with the Industrial Wastewater Reuse Permit for the Materials and Fuels Complex Industrial Waste Ditch and Pond: May 1, 2010-October 31, 2010

    SciTech Connect (OSTI)

    David B. Frederick

    2011-02-01

    This report summarizes radiological monitoring performed on samples from specific groundwater monitoring wells associated with the Industrial Wastewater Reuse Permit for the Materials and Fuels Complex Industrial Waste Ditch and Industrial Waste Pond (#LA-000160-01). The radiological monitoring was performed to fulfill Department of Energy requirements under the Atomic Energy Act.

  8. Radiological Monitoring Results for Groundwater Samples Associated with the Industrial Wastewater Reuse Permit for the Materials and Fuels Complex Industrial Waste Ditch and Pond: November 1, 2011-October 31, 2012

    SciTech Connect (OSTI)

    Mike lewis

    2013-02-01

    This report summarizes radiological monitoring performed on samples from specific groundwater monitoring wells associated with the Industrial Wastewater Reuse Permit for the Materials and Fuels Complex Industrial Waste Ditch and Industrial Waste Pond WRU-I-0160-01, Modification 1 (formerly LA-000160-01). The radiological monitoring was performed to fulfill Department of Energy requirements under the Atomic Energy Act.

  9. Radiological Monitoring Results For Groundwater Samples Associated with the Industrial Wastewater Reuse Permit for the Materials and Fuels Complex Industrial Waste Ditch and Pond: November 1, 2010-October 31, 2011

    SciTech Connect (OSTI)

    David Frederick

    2012-02-01

    This report summarizes radiological monitoring performed on samples from specific groundwater monitoring wells associated with the Industrial Wastewater Reuse Permit for the Materials and Fuels Complex Industrial Waste Ditch and Industrial Waste Pond (No.LA-000160-01). The radiological monitoring was performed to fulfill Department of Energy requirements under the Atomic Energy Act.

  10. Radiological Monitoring Results for Groundwater Samples Associated with the Industrial Wastewater Reuse Permit for the Materials and Fuels Complex Industrial Waste Ditch and Pond: November 1, 2012-October 31, 2013

    SciTech Connect (OSTI)

    Mike Lewis

    2014-02-01

    This report summarizes radiological monitoring performed on samples from specific groundwater monitoring wells associated with the Industrial Wastewater Reuse Permit for the Materials and Fuels Complex Industrial Waste Ditch and Industrial Waste Pond WRU-I-0160-01, Modification 1 (formerly LA-000160-01). The radiological monitoring was performed to fulfill Department of Energy requirements under the Atomic Energy Act.

  11. [Task 1.] Biodenitrification of low nitrate solar pond waters using sequencing batch reactors. [Task 2.] Solidification/stabilization of high strength and biodenitrified heavy metal sludges with a Portland cement/flyash system

    SciTech Connect (OSTI)

    Figueroa, L.; Cook, N.E.; Siegrist, R.L.; Mosher, J.; Terry, S.; Canonico, S.

    1995-09-22

    Process wastewater and sludges were accumulated on site in solar evaporation ponds during operations at the Department of Energy's Rocky Flats Plant (DOE/RF). Because of the extensive use of nitric acid in the processing of actinide metals, the process wastewater has high concentrations of nitrate. Solar pond waters at DOE/RF contain 300-60,000 mg NO{sub 3}{sup {minus}}/L. Additionally, the pond waters contain varying concentrations of many other aqueous constituents, including heavy metals, alkali salts, carbonates, and low level radioactivity. Solids, both from chemical precipitation and soil material deposition, are also present. Options for ultimate disposal of the pond waters are currently being evaluated and include stabilization and solidification (S/S) by cementation. Removal of nitrates can enhance a wastes amenability to S/S, or can be a unit operation in another treatment scheme. Nitrate removal is also a concern for other sources of pollution at DOE/RF, including contaminated groundwater collected by interceptor trench systems. Finally, nitrate pollution is a problem at many other DOE facilities where actinide metals were processed. The primary objective of this investigation was to optimize biological denitrification of solar pond waters with nitrate concentrations of 300--2,100 mg NO{sub 3}{sup {minus}}/L to below the drinking water standard of 45 mg NO{sub 3}{sup {minus}}/L (10 mg N/L). The effect of pH upon process stability and denitrification rate was determined. In addition, the effect Cr(VI) on denitrification and fate of Cr(VI) in the presence of denitrifying bacteria was evaluated.

  12. RCRA Facility Investigation Plan K-1004 Area Lab Drain and the K-1007-B Pond - Oak Ridge Gaseous Diffusion Plant - Oak Ridge, Tennessee

    SciTech Connect (OSTI)

    ORGDP, Martin Marietta Energy Systems Inc.

    1988-12-01

    Within the confines of the Oak Ridge Gaseous Diffusion Plant (ORGDP) are hazardous waste treatment, storage, and disposal facilities; some are in operation while others are no longer in use. these solid waste management units (SWMUs) are subject to assessment by the US Environmental Protection Agency (EPA). The RCRA Facility Investigation (RFI) Plans are scheduled to be submitted for all units during calendar years 1987 and 1988. The RFI Plan - General Document (K/HS-132) includes information applicable to all the ORGDP SMWUs and serves as a reference document for the site-specific RFI plans. This document is the site-specific RFI Plan for the K-1004 Area Lab Drain (ALD) and the K-1007-B Pond. This plan is based upon requirements described in the draft document, RFI Guidance, Vols. I-IV, December 1987 (EPA 530/SW-87-001). This unit is regulated by Section 3004(u) of the 1984 Hazardous and Solid Waste Amendments (HSWA) to the Resource Conservation Recovery Act (RCRA). Contained within this document are geographical, historical, operational, geological, and hydrological data specific to the K-1004 ALD and the K-1007-B Pond. The potential for release of contamination through the various media to receptors is addressed. A sampling plan is proposed to further determine the extent (if any) of release of contamination to the surrounding environment. Included are health and safety procedures to be followed when implementing the sampling plan. Quality control (QC) procedures for remedial action occurring on the Oak Ridge Reservation (ORR) are presented in 'The Environmental Surveillance Procedures Quality Control Program, Martin Marietta Energy Systems, Inc., (ESH/Sub/87-21706/1), and quality assurance (QA) guidelines for ORGDP investigations are contained in The K-25 Remedial Actions Program Quality Assurance Plan, K/HS-231.

  13. EA-1070: Revised Finding of No Significant Impact

    Broader source: Energy.gov [DOE]

    Natural Fluctuation of Water Level in Par Pond and Reduced Water Flow in Steel Creek below L Lake at the Savannah River Site

  14. CALiPER Report 20.4: Lumen and Chromaticity Maintenance of LED PAR38 Lamps Operated in Steady-State Conditions

    SciTech Connect (OSTI)

    none,

    2014-12-30

    This CALiPER report focuses on lumen maintenance, chromaticity maintenance, and catastrophic failure in 32 of the Series 20 LED PAR38 lamps and 8 benchmark lamps, which were monitored for nearly 14,000 hours at ambient temperatures between 44°C and 45°C.

  15. CALiPER Report 20.2: Dimming, Flicker, and Power Quality Characteristics of LED PAR38 Lamps

    SciTech Connect (OSTI)

    None, None

    2014-03-31

    This report focuses on the flicker and power quality performance of the Series 20 lamps at full output and various dimmed levels. All of the Series 20 PAR38 lamps that manufacturers claimed to be dimmable (including all halogen lamps) were evaluated individually (one lamp at a time) both on a switch and under the control of a phase-cut dimmer designed for use with "all classes of bulbs." Measurements of luminous flux, flicker, and power quality were taken at 10 target dimmed settings and compared with operation on a switch. Because only a single unit of each product was evaluated on a single dimmer that may or may not have been recommended by its manufacturer, this report focuses on the performance of the products relative to each other, rather than the best-case performance of each lamp or variation in performance delivered from each lamp. Despite these limitations, the results suggest that LED performance is improving, and performance trends are beginning to emerge, perhaps due in part to the identification of preferred LED driver strategies for lamp products.

  16. DOE CALiPER Program, Report 20.1 Subjective Evaluation of Beam Quality, Shadow Quality, and Color Quality for LED PAR38 Lamps

    SciTech Connect (OSTI)

    Royer, Michael P.; Poplawski, Michael E.; Miller, Naomi J.

    2013-10-01

    This report focuses on human-evaluated characteristics, including beam quality, shadow quality, and color quality. Using a questionnaire that included rank ordering, opinions on 27 of the Report 20 PAR38 lamps were gathered during a demonstration event for members of the local Illuminating Engineering Society (IES) chapter. This was not a rigorous scientific experiment, and the data should not be extrapolated beyond the scope of the demonstration. The results suggest that many of the LED products compared favorably to halogen PAR38 benchmarks in all attributes considered. LED lamps using a single-emitter design were generally preferred for their beam quality and shadow quality, and the IES members ranking of color quality did not always match the rank according to the color rendering index (CRI).

  17. CALiPER Report 20.1: Subjective Evaluation of Beam Quality, Shadow Quality, and Color Quality for LED PAR38 Lamps

    SciTech Connect (OSTI)

    None, None

    2013-11-07

    This report focuses on human-evaluated characteristics, including beam quality, shadow quality, and color quality. Using a questionnaire that included rank-ordering, opinions on 27 of the Report 20 PAR38 lamps were gathered during a demonstration event for members of the local Illuminating Engineering Society (IES) chapter. This was not a rigorous scientific experiment, and the data should not be extrapolated beyond the scope of the demonstration. The results suggest that many of the LED products compared favorably to halogen PAR38 benchmarks in all attributes considered. LED lamps using a single-emitter design were generally preferred for their beam quality and shadow quality, and the IES members' ranking of color quality did not always match the rank according to the color rendering index (CRI).

  18. ARM - Datastreams - pars2

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Atlantic ENA C1 Browse Data Graciosa Island, Azores, Portugal ARM Mobile Facility ACX S1 Browse Data ACX Supplemental Facility 1 MAG S1 Browse Data MAG Supplemental Facility 1...

  19. Remedial Investigation Report on Chestnut Ridge Operable Unit 2 (Filled Coal Ash Pond/Upper McCoy Branch) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee. Volume 1. Main Text

    SciTech Connect (OSTI)

    Not Available

    1994-08-01

    This document is a report on the remedial investigation (RI) of Chestnut Ridge Operable Unit (OU) 2 at the Oak Ridge Y-12 Plant. Chestnut Ridge OU 2 consists of Upper McCoy Branch (UMB), the Filled Coal Ash Pond (FCAP), and the area surrounding the Sluice Channel formerly associated with coal ash disposal in the FCAP. Chestnut Ridge OU 2 is located within the U.S. Department of Energy`s (DOE`s) Oak Ridge Reservation in Anderson County, Tennessee, approximately 24 miles west of Knoxville. The pond is an 8.5-acre area on the southern slope of Chestnut Ridge, 0.5 mile south of the main Y-12 Plant and geographically separated from the Y-12 Plant by Chestnut Ridge. The elevation of the FCAP is {approximately} 950 ft above mean sea level (msl), and it is relatively flat and largely vegetated. Two small ponds are usually present at the northeast and northwest comers of the FCAP. The Sluice Channel Area extends {approximately}1000 ft from the northern margin of the FCAP to the crest of Chestnut Ridge, which has an elevation of {approximately}1100 ft above msl. The Sluice Channel Area is largely vegetated also. McCoy Branch runs from the top of Chestnut Ridge across the FCAP into Rogers Quarry and out of the quarry where it runs a short distance into Milton Hill Lake at McCoy Embayment, termed UMB. The portion south of Rogers Quarry, within Chestnut Ridge OU 4, is termed Lower McCoy Branch. The DOE Oak Ridge Y-12 Plant disposed of coal ash from its steam plant operations as a slurry that was discharged into an ash retention impoundment; this impoundment is the FCAP. The FCAP was built in 1955 to serve as a settling basin after coal ash slurried over Chestnut Ridge from the Y-12 Plant. The FCAP was constructed by building an earthen dam across the northern tributary of McCoy Branch. The dam was designed to hold 20 years of Y-12 steam plant ash. By July 1967, ash had filled up the impoundment storage behind the dam to within 4 ft of the top.

  20. Tricyclic GyrB/ParE (TriBE) Inhibitors. A new class of broad-spectrum dual-targeting antibacterial agents

    SciTech Connect (OSTI)

    Tari, Leslie W.; Li, Xiaoming; Trzoss, Michael; Bensen, Daniel C.; Chen, Zhiyong; Lam, Thanh; Zhang, Junhu; Lee, Suk Joong; Hough, Grayson; Phillipson, Doug; Akers-Rodriguez, Suzanne; Cunningham, Mark L.; Kwan, Bryan P.; Nelson, Kirk J.; Castellano, Amanda; Locke, Jeff B.; Brown-Driver, Vickie; Murphy, Timothy M.; Ong, Voon S.; Pillar, Chris M.; Shinabarger, Dean L.; Nix, Jay; Lightstone, Felice C.; Wong, Sergio E.; Nguyen, Toan B.; Shaw, Karen J.; Finn, John

    2013-12-26

    Increasing resistance to every major class of antibiotics and a dearth of novel classes of antibacterial agents in development pipelines has created a dwindling reservoir of treatment options for serious bacterial infections. The bacterial type IIA topoisomerases, DNA gyrase and topoisomerase IV, are validated antibacterial drug targets with multiple prospective drug binding sites, including the catalytic site targeted by the fluoroquinolone antibiotics. Growing resistance to fluoroquinolones, frequently mediated by mutations in the drug-binding site, is increasingly limiting the utility of this antibiotic class, prompting the search for other inhibitor classes that target different sites on the topoisomerase complexes. The highly conserved ATP-binding subunits of DNA gyrase (GyrB) and topoisomerase IV (ParE) have long been recognized as excellent candidates for the development of dual-targeting antibacterial agents with broad-spectrum potential. However, to date, no natural product or small molecule inhibitors targeting these sites have succeeded in the clinic, and no inhibitors of these enzymes have yet been reported with broad-spectrum antibacterial activity encompassing the majority of Gram-negative pathogens. Using structure-based drug design (SBDD), we have created a novel dual-targeting pyrimidoindole inhibitor series with exquisite potency against GyrB and ParE enzymes from a broad range of clinically important pathogens. Inhibitors from this series demonstrate potent, broad-spectrum antibacterial activity against Gram-positive and Gram-negative pathogens of clinical importance, including fluoroquinolone resistant and multidrug resistant strains. Moreover, lead compounds have been discovered with clinical potential; they are well tolerated in animals, and efficacious in Gram-negative infection models.

  1. Tricyclic GyrB/ParE (TriBE) Inhibitors. A new class of broad-spectrum dual-targeting antibacterial agents

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Tari, Leslie W.; Li, Xiaoming; Trzoss, Michael; Bensen, Daniel C.; Chen, Zhiyong; Lam, Thanh; Zhang, Junhu; Lee, Suk Joong; Hough, Grayson; Phillipson, Doug; et al

    2013-12-26

    Increasing resistance to every major class of antibiotics and a dearth of novel classes of antibacterial agents in development pipelines has created a dwindling reservoir of treatment options for serious bacterial infections. The bacterial type IIA topoisomerases, DNA gyrase and topoisomerase IV, are validated antibacterial drug targets with multiple prospective drug binding sites, including the catalytic site targeted by the fluoroquinolone antibiotics. Growing resistance to fluoroquinolones, frequently mediated by mutations in the drug-binding site, is increasingly limiting the utility of this antibiotic class, prompting the search for other inhibitor classes that target different sites on the topoisomerase complexes. The highlymore » conserved ATP-binding subunits of DNA gyrase (GyrB) and topoisomerase IV (ParE) have long been recognized as excellent candidates for the development of dual-targeting antibacterial agents with broad-spectrum potential. However, to date, no natural product or small molecule inhibitors targeting these sites have succeeded in the clinic, and no inhibitors of these enzymes have yet been reported with broad-spectrum antibacterial activity encompassing the majority of Gram-negative pathogens. Using structure-based drug design (SBDD), we have created a novel dual-targeting pyrimidoindole inhibitor series with exquisite potency against GyrB and ParE enzymes from a broad range of clinically important pathogens. Inhibitors from this series demonstrate potent, broad-spectrum antibacterial activity against Gram-positive and Gram-negative pathogens of clinical importance, including fluoroquinolone resistant and multidrug resistant strains. Moreover, lead compounds have been discovered with clinical potential; they are well tolerated in animals, and efficacious in Gram-negative infection models.« less

  2. TITLE AUTHORS SUBJECT SUBJECT RELATED DESCRIPTION PUBLISHER AVAILABILI...

    Office of Scientific and Technical Information (OSTI)

    at Par Pond consists of fiberglass tanks that can maintain small organisms such as fish and amphibians Thirty of the tanks have sealed sup Cs sources suspended above them...

  3. "Title","Creator/Author","Publication Date","OSTI Identifier...

    Office of Scientific and Technical Information (OSTI)

    at Par Pond consists of 48 fiberglass tanks that can maintain small organisms such as fish and amphibians. Thirty of the tanks have sealed sup 137Cs sources suspended above...

  4. Savannah River Ecology Laboratory Annual Technical Progress Report...

    Office of Scientific and Technical Information (OSTI)

    at Par Pond consists of 48 fiberglass tanks that can maintain small organisms such as fish and amphibians. Thirty of the tanks have sealed sup 137Cs sources suspended above...

  5. Search for: All records | SciTech Connect

    Office of Scientific and Technical Information (OSTI)

    ... The 1-acre facility at Par Pond consists of 48 fiberglass tanks that can maintain small organisms such as fish and amphibians. Thirty of the tanks have sealed sup 137Cs sources ...

  6. Simulink/PARS Integration Support

    SciTech Connect (OSTI)

    Vacaliuc, B.; Nakhaee, N.

    2013-12-18

    The state of the art for signal processor hardware has far out-paced the development tools for placing applications on that hardware. In addition, signal processors are available in a variety of architectures, each uniquely capable of handling specific types of signal processing efficiently. With these processors becoming smaller and demanding less power, it has become possible to group multiple processors, a heterogeneous set of processors, into single systems. Different portions of the desired problem set can be assigned to different processor types as appropriate. As software development tools do not keep pace with these processors, especially when multiple processors of different types are used, a method is needed to enable software code portability among multiple processors and multiple types of processors along with their respective software environments. Sundance DSP, Inc. has developed a software toolkit called “PARS”, whose objective is to provide a framework that uses suites of tools provided by different vendors, along with modeling tools and a real time operating system, to build an application that spans different processor types. The software language used to express the behavior of the system is a very high level modeling language, “Simulink”, a MathWorks product. ORNL has used this toolkit to effectively implement several deliverables. This CRADA describes this collaboration between ORNL and Sundance DSP, Inc.

  7. Across the Pond Newsletter Issue 1

    Office of Environmental Management (EM)

    letter No. AL 2015-05 Acquisition letter No. AL 2015-05 DATE: May 12, 2015 TO: Procurement Directors/Contracting Officers FROM: Director Contract and Financial Assistance Policy Division Office of Policy Office of Acquisition and Project Management SUBJECT: Acquisition Letters Remaining in Effect SUMMARY: Acquisition letter 2015-05 has been issued. It lists ALs currently in effect and the discontinued ALs, along with the reason why the AL is no longer in effect. This Flash will be available

  8. Across the Pond Newsletter Issue 2

    Office of Environmental Management (EM)

    - NDA relationship recognized at International Environmental Cleanup Conference e ICEM '09 conference held in Liverpool, UK Oct 10-16th drew participants from all over the world including a high- level presence from DOE's Office of Environmental Management (EM). Dr. Samit K. Bhattacharyya, Laboratory Director, Savannah River National Laboratory, gave an opening session presentation on behalf of Dr. Inés R. Triay, Assistant Secretary for Environmental Management, who at the last minute was

  9. Across the Pond Newsletter Issue 6

    Office of Environmental Management (EM)

    Members of DOE's Office of Environmental Management (EM) and the UK's Nuclear Decommissioning Authority (NDA) held their 8th Standing Committee Meeting on March 2, 2011, at the annual Waste Management 2011 Conference in Phoenix, AZ. The meeting focused on the progress achieved since the last time the committee met in the UK in October 2010 as well as new areas for collaboration such as Project Management and Supply Chain Management. The general concensus was that the collaboration efforts are

  10. Construction of Ash Pond Isolation Dike.

    Office of Legacy Management (LM)

  11. Ordered structures in YBa/sub 2/Cu/sub 3/O/sub 7-y/, La/sub 2-x/Sr/sub x/CuO/sub 4-par. delta/ and related perovskites

    SciTech Connect (OSTI)

    Mitchell, T.E.; Roy, T.; Fisk, Z.; Smith, J.L.

    1988-01-01

    Electron microscopy and electron diffraction studies have been performed on the superconducting oxides YBa/sub 2/Cu/sub 3/O/sub 7-y/, GdBa/sub 2/Cu/sub 3/O/sub 7-y/ and La/sub 2-x/Sr/sub x/CuO/sub 4-par. delta/ as well as the related perovskites La/sub 2/CuO/sub 4/, Eu/sub 2/CuO/sub 4/ and Gd/sub 2/CuO/sub 4/. Extra reflections are commonly observed in all the cases. For example, in the 123 compounds, in situ heating leads to transformations from orthorhombic to tetragonal with a loss of twin structure; on cooling the oxygen vacancies re-order in the basal plane to give 1/3(100)* or 1/4(110)* diffraction spots. In tetragonal Eu/sub 2/CuO/sub 4/ and Gd/sub 2/CuO/sub 4/, the (001) diffraction patterns often have extra spots at 1/2(110)* or at 1/4(110)* positions. Extra spots are also observed in La/sub 2/CuO/sub 4/ (orthorhombic) but this is probably due to the space group being primitive rather than centered. These observations are discussed in terms of the ordering of oxygen vacancies in the Cu-O planes of the various perovskite structures. 6 figs.

  12. PARS II Training Materials | Department of Energy

    Energy Savers [EERE]

    "how to" exercises for each course are available for download. Users who are attending Web classes should download these documents prior to attending the class. Slides from the...

  13. Solar-thermal-energy collection/storage-pond system

    DOE Patents [OSTI]

    Blahnik, D.E.

    1982-03-25

    A solar thermal energy collection and storage system is disclosed. Water is contained, and the water surface is exposed directly to the sun. The central part of an impermeable membrane is positioned below the water's surface and above its bottom with a first side of the membrane pointing generally upward in its central portion. The perimeter part of the membrane is placed to create a watertight boundary separating the water into a first volume which is directly exposable to the sun and which touches the membranes first side, and a second volumn which touches the membranes second side. A salt is dissolved in the first water volume.

  14. Systems and economic analysis of microalgae ponds for conversion...

    Office of Scientific and Technical Information (OSTI)

    ... Subject: 01 COAL, LIGNITE, AND PEAT; 09 BIOMASS FUELS; BIOMASS; PRODUCTION; CARBON DIOXIDE; AIR POLLUTION CONTROL; METABOLISM; WASTE PRODUCT UTILIZATION; ALGAE; CULTIVATION; COAL; ...

  15. Sandia Energy - Sandian Todd Lane's "Pond Crash Forensics" Project...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    team, as well as a very strong example of how a technology platform developed by the RapTOR grand challenge can have multiple applications, such as algal biofuels (and central to...

  16. Systems and economic analysis of microalgae ponds for conversion...

    Office of Scientific and Technical Information (OSTI)

    W.J. 01 COAL, LIGNITE, AND PEAT; 09 BIOMASS FUELS; BIOMASS; PRODUCTION; CARBON DIOXIDE; AIR POLLUTION CONTROL; METABOLISM; WASTE PRODUCT UTILIZATION; ALGAE; CULTIVATION; COAL;...

  17. EA-1075: Proposed Casey's Pond Improvement Project, Batavia, Illinois

    Broader source: Energy.gov [DOE]

    This EA evaluates the environmental impacts of a proposed system upgrade to meet improved operational criteria on the current Industrial Cooling Water distribution system used in the fixed target...

  18. Engineers Drawing: Ash Pond Isolation Dike Plan. Revision 4.

    Office of Legacy Management (LM)

  19. Engineers Drawing: Ash Pond Isolation Dike Sections and Deetails

    Office of Legacy Management (LM)

  20. MHK Projects/Twin Pond | Open Energy Information

    Open Energy Info (EERE)

    itedicon":"","lines":,"polygons":,"circles":,"rectangles":,"copycoords":false,"static":false,"wmsoverlay":"","layers":,"controls":"pan","zoom","type","scale","streetview...

  1. Savannah River Technology Center monthly report, July 1995

    SciTech Connect (OSTI)

    Ferrell, J.M.

    1995-07-01

    Progress is reported in the context of: tritium, separations, environmental, waste management, and general affairs. Emphasized topics include: metal hydrides, valves, sampling, water contamination, Par pond, F and H canyon tanks, tritium transport models, landfill stabilization, pumps, waste storage, and chemical analyzers.

  2. PEP TALK "Policy - EVMS - PARS" Update, Mel Frank, Chief, Project...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    the 2016 Project Management Workshop, features and capabilities of the new PM Website, EVMS Roadside Assist visits, EVMS Training Snippets, PMCDP classroom and online training, ...

  3. fdm3da_parV1.0

    Energy Science and Technology Software Center (OSTI)

    2002-01-23

    FORTRAN90 software computes synthetic induction log responses in fully 3D anistropic geoelectric media.

  4. Remediation of a large contaminated reactor cooling reservoir: Resolving and environmental/regulatory paradox

    SciTech Connect (OSTI)

    Bowers, J.A.: Gladden, J.B.; Hickey, H.M.; Jones, M.P.; Mackey, H.E.; Mayer, J.J.; Doswell, A.

    1994-05-01

    This paper presents a case study of a former reactor cooling water reservoir, PAR Pond, located Savannah River Site. PAR Pond, a 2640 acre, man-made reservoir was built in 1958 and until 1988, received cooling water from two DOE nuclear production reactors, P and R. The lake sediments were contaminated with low levels of radiocesium (CS-137) and transuranics in the late 1950s and early 1960s because of leaking fuel elements. Elevated levels of mercury accumulated in the sediments from pumping water from the Savannah River to maintain a full pool. PAR Ponds` stability, size, and nutrient content made a significant, unique, and highly studied ecological resource for fish and wildlife populations until it was partially drained in 1991 due to a depression in the downslope of the earthen dam. The drawdown, created 1340 acres of exposed, radioactively contaminated sediments along 33 miles of shoreline. This led US EPA to declare PAR Pond as a CERCLA operable unit subject to remediation. The drawdown also raised concerns for the populations of aquatic plants, fish, alligators, and endangered species and increased the potential for off-site migration of contaminated wildlife from contact with the exposed sediments. Applicable regulations, such as NEPA and CERCLA, require wetland loss evaluations, human health and ecological risk assessments, and remediation feasibility studies. DOE is committed to spending several million dollars to repair the dam for safety reasons, even though the lake will probably not be used for cooling purposes. At the same time, DOE must make decisions whether to refill and expend additional public funds to maintain a full pool to reduce the risks defined under CERCLA or spend hundreds of millions in remediation costs to reduce the risks of the exposed sediments.

  5. Washington: Enabling the Successful Transition of Microalgae from Lab to Pond

    Broader source: Energy.gov [DOE]

    Pacific Northwest National Laboratory developed a promising technology that can accelerate the pace at which EERE reaches DOE's biofuel production targets.

  6. Letter: Approval for the Interim Response Action, Construction of the Ash Pond Isolation System.

    Office of Legacy Management (LM)

  7. Proposed Interim Response Action, Construction of Ash Pond Isolation System at the Weldon Spring Site.

    Office of Legacy Management (LM)

  8. Wastewater treatment lagoons (ponds). (Latest citations from the NTIS bibliographic database). Published Search

    SciTech Connect (OSTI)

    1995-09-01

    The bibliography contains citations concerning the treatment and storage of wastewaters in lagoons. The design, operation, and equipment for treatment and storage techniques, and associated pretreatment processes are discussed. Included in the references are treatment of wastewaters from industrial operations. Descriptions and evaluations of specific facilities are provided. (Contains 50-250 citations and includes a subject term index and title list.) (Copyright NERAC, Inc. 1995)

  9. GeoMelt{sup R} ICV{sup TM} Treatment of Sellafield Pond Solids Waste - 13414

    SciTech Connect (OSTI)

    Witwer, Keith; Woosley, Steve; Campbell, Brett [Kurion, Inc., GeoMelt Division, 3015 Horn Rapids Road, Richland, Washington (United States)] [Kurion, Inc., GeoMelt Division, 3015 Horn Rapids Road, Richland, Washington (United States); Wong, Martin; Hill, Joanne [AMEC Inc., Birchwood Park, 601 Faraday Street, Birchwood, Warrington, WA3 6GN (United Kingdom)] [AMEC Inc., Birchwood Park, 601 Faraday Street, Birchwood, Warrington, WA3 6GN (United Kingdom)

    2013-07-01

    Kurion, Inc., in partnership with AMEC Ltd., is demonstrating its GeoMelt{sup R} In-Container Vitrification (ICV){sup TM} Technology to Sellafield Ltd. (SL). SL is evaluating the proposition of directly converting a container (skip/box/drum) of raw solid ILW into an immobilized waste form using thermal treatment, such that the resulting product is suitable for interim storage at Sellafield and subsequent disposal at a future Geological Disposal Facility. Potential SL feed streams include sludges, ion-exchange media, sand, plutonium contaminated material, concrete, uranium, fuel cladding, soils, metals, and decommissioning wastes. The solid wastes have significant proportions of metallic constituents in the form of containers, plant equipment, structural material and swarf arising from the nuclear operations at Sellafield. GeoMelt's proprietary ICV process was selected for demonstration, with the focus being high and reactive metal wastes arising from solid ILW material. A composite surrogate recipe was used to demonstrate the technology towards treating waste forms of diverse types and shapes, as well as those considered difficult to process; all the while requiring few (if any) pre-treatment activities. Key strategic objectives, along with their success criterion, were established by SL for this testing, namely: 1. Passivate and stabilize the raw waste simulant, as demonstrated by the entire quantity of material being vitrified, 2. Immobilize the radiological and chemo-toxic species, as demonstrated via indicative mass balance using elemental analyses from an array of samples, 3. Production of an inert and durable product as evidenced by transformation of reactive metals to their inert oxide forms and satisfactory leachability results using PCT testing. Two tests were performed using the GeoMelt Demonstration Unit located at AMEC's Birchwood Park Facilities in the UK. Post-melt examination of the first test indicated some of the waste simulant had not fully processed, due to insufficient processing time and melt temperature. A second test, incorporating operational experience from the first test, was performed and resulted in all of the 138 kg of feed material being treated. The waste simulant portion, at 41 kg, constituted 30 wt% of the total feed mass, with over 90% of this being made up of various reactive and non-reactive metals. The 95 liters of staged material was volume reduced to 41 liters, providing a 57% overall feed to product volume reduction in a fully passivated two-phase glass/metal product. The GeoMelt equipment operated as designed, vitrifying the entire batch of waste simulant. Post-melt analytical testing verified that 91-99+% of the radiological tracer metals were uniformly distributed within the glass/cast refractory/metal product, and the remaining fraction was captured in the offgas filtration systems. PCT testing of the glass and inner refractory liner showed leachability results that outperform the DOE regulatory limit of 2 g/m{sup 2} for the radiological species of interest (Sr, Ru, Cs, Eu, Re), and by more than an order of magnitude better for standard reference analytes (B, Na, Si). (authors)

  10. SHOCKED AND SCORCHED: THE TAIL OF A TADPOLE IN AN INTERSTELLAR POND

    SciTech Connect (OSTI)

    Sahai, R.; Morris, M. R.; Claussen, M. J.

    2012-05-20

    We report multi-wavelength observations of the far-infrared source IRAS 20324+4057, including high-resolution optical imaging with the Hubble Space Telescope, and ground-based near-infrared, millimeter-wave and radio observations. These data show an extended, limb-brightened, tadpole-shaped nebula with a bright, compact, cometary nebula located inside the tadpole head. Our molecular line observations indicate that the Tadpole is predominantly molecular with a total gas mass exceeding 3.7 M{sub Sun }. Our radio continuum imaging and archival Spitzer IRAC images show the presence of additional tadpole-shaped objects in the vicinity of IRAS 20324+4057 that share a common east-west head-tail orientation: we propose that these structures are small, dense molecular cores that originated in the Cygnus cloud and are now being (1) photoevaporated by the ultraviolet radiation field of the Cyg OB2 No. 8 cluster located to the northwest; and (2) shaped by ram pressure of a distant wind source or sources located to the west, blowing ablated and photoevaporated material from their heads eastward. The ripples in the tail of the Tadpole are interpreted in terms of instabilities at the interface between the ambient wind and the dense medium of the former.

  11. Integration of geographic information systems and logistic multiple regression for aquatic macrophyte modeling

    SciTech Connect (OSTI)

    Narumalani, S.; Jensen, J.R.; Althausen, J.D.; Burkhalter, S.; Mackey, H.E. Jr.

    1994-06-01

    Since aquatic macrophytes have an important influence on the physical and chemical processes of an ecosystem while simultaneously affecting human activity, it is imperative that they be inventoried and managed wisely. However, mapping wetlands can be a major challenge because they are found in diverse geographic areas ranging from small tributary streams, to shrub or scrub and marsh communities, to open water lacustrian environments. In addition, the type and spatial distribution of wetlands can change dramatically from season to season, especially when nonpersistent species are present. This research, focuses on developing a model for predicting the future growth and distribution of aquatic macrophytes. This model will use a geographic information system (GIS) to analyze some of the biophysical variables that affect aquatic macrophyte growth and distribution. The data will provide scientists information on the future spatial growth and distribution of aquatic macrophytes. This study focuses on the Savannah River Site Par Pond (1,000 ha) and L Lake (400 ha) these are two cooling ponds that have received thermal effluent from nuclear reactor operations. Par Pond was constructed in 1958, and natural invasion of wetland has occurred over its 35-year history, with much of the shoreline having developed extensive beds of persistent and non-persistent aquatic macrophytes.

  12. Interim Response Action for the Ash Pond Isolation System. Letter transmits the revised Engineering Evaluation / Cost Analysis (EE/CA) for the construction of the Ash Pond Isolation System.

    Office of Legacy Management (LM)

  13. Systems and economic analysis of microalgae ponds for conversion of CO{sub 2} to biomass. Final report

    SciTech Connect (OSTI)

    Benemann, J.R.; Oswald, W.J.

    1996-03-21

    There is growing evidence that global warming could become a major global environmental threat during the 21st century. The precautionary principle commands preventive action, at both national and international levels, to minimize this potential threat. Many near-term, relatively inexpensive, mitigation options are available. In addition, long-term research is required to evaluate and develop advanced, possibly more expensive, countermeasures, in the eventuality that they may be required. The utilization of power plant CO{sub 2} and its recycling into fossil fuel substitutes by microalgae cultures could be one such long-term technology. Microalgae production is an expanding industry in the U.S., with three commercial systems (of approximately 10 hectare each) producing nutriceuticals, specifically beta-carotene, extracted from Dunaliella, and Spirulina biomass. Microalgae are also used in wastewater treatment. Currently production costs are high, about $10,000/ton of algal biomass, almost two orders of magnitude higher than acceptable for greenhouse gas mitigation. This report reviews the current state-of-the-art, including algal cultivation and harvesting-processing, and outlines a technique for achieving very high productivities. Costs of CO{sub 2} mitigation with microalgae production of oils ({open_quotes}biodiesel{close_quotes}) are estimated and future R&D needs outlined.

  14. Corrective Action Investigation Plan for Corrective Action Unit 552: Area 12 Muckpile and Ponds, Nevada Test Site, Nevada, Rev. 1

    SciTech Connect (OSTI)

    Robert F. Boehlecke

    2005-01-01

    Corrective Action Unit 552 is being investigated because man-made radionuclides and chemical contaminants may be present in concentrations that could potentially pose an unacceptable risk to human health and/or the environment. The CAI will be conducted following the data quality objectives (DQOs) developed by representatives of the Nevada Division of Environmental Protection (NDEP) and the DOE National Nuclear Security Administration Nevada Site Office (NNSA/NSO). The DQOs are used to identify the type, amount, and quality of data needed to define the nature and extent of contamination and identify and evaluate the most appropriate corrective action alternatives for CAU 552. The primary problem statement for the investigation is: ''Existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend corrective action alternatives for CAS 12-23-05.'' To address this problem statement, the resolution of the following two decision statements is required: (1) The Decision I statement is: ''Is a contaminant present within the CAU at a concentration that could pose an unacceptable risk to human health and the environment?'' Any site-related contaminant detected at a concentration exceeding the corresponding preliminary action level (PAL), as defined in Section A.1.4.2, will be considered a contaminant of concern (COC). A COC is defined as a site-related constituent that exceeds the screening criteria (PAL). The presence of a contaminant within each CAS is defined as the analytical detection of a COC. (2) The Decision II statement is: ''Determine the extent of contamination identified above PALs.'' This decision will be achieved by the collection of data that are adequate to define the extent of COCs. Decision II samples are used to determine the lateral and vertical extent of the contamination as well as the likelihood of COCs to migrate outside of the site boundaries. The migration pattern can be derived from the Decision II samples, since the analytical results of those samples will show how far the contamination has travelled in the time period since activities at the site ended. Most of the data necessary to resolve the decisions will be generated from the analysis of environmental samples collected during the CAI for CAU 552. The general purpose of the investigation is to: (1) Identify the presence and nature of COCs. (2) Determine the vertical and lateral extent of identified COCs. (3) Ensure sufficient data is collected to support the selection of a corrective action compliant with all NDEP, ''Resource Conservation and Recovery Act (RCRA), Toxic Substance Control Act (TSCA)'', and DOE requirements. In addition, data will be obtained to support (IDW) disposal and potential future waste management decisions.

  15. A Drop in the Bucket or a Pebble in a Pond: Commercial Building Partners Replication of EEMs Across Their Portfolios

    SciTech Connect (OSTI)

    Antonopoulos, Chrissi A.; Baechler, Michael C.; Dillon, Heather E.

    2014-08-18

    This study presents findings from questionnaire and interview data investigating replication efforts of Commercial Building Partnership (CBP) partners that worked directly with the Pacific Northwest National Laboratory (PNNL). PNNL partnered with 12 organizations on new and retrofit construction projects as part of the U.S. Department of Energy (DOE) CBP program. PNNL and other national laboratories collaborate with industry leaders that own large portfolios of buildings to develop high performance projects for new construction and renovation. This project accelerates market adoption of commercially available energy saving technologies into the design process for new and upgraded commercial buildings. The labs provide assistance to the partners design teams and make a business case for energy investments. From the owners perspective, a sound investment results in energy savings based on corporate objectives and design. Through a feedback questionnaire, along with personal interviews, PNNL gathered qualitative and quantitative information relating to replication efforts by each organization. Data through this process were analyzed to provide insight into two primary research areas: 1) CBP partners replication efforts of technologies and approaches used in the CBP project to the rest of the organizations building portfolio (including replication verification), and, 2) the market potential for technology diffusion into the total U.S. commercial building stock, as a direct result of the CBP entire program.

  16. Microsoft Word - S05212_2008 Post-Closure InspRpt.doc

    Office of Legacy Management (LM)

    ... B.R. Anderson Pond Lower Little Cr. 1 Lower Little Cr. 2 James Lowe Pond Nobles Pond Howard Smith Pond Figure 7. Tritium Decay Trend and Off-Site Surface Water Sample ...

  17. Paraho environmental data. Part I. Process characterization. Par II. Air quality. Part III. Water quality

    SciTech Connect (OSTI)

    Heistand, R.N.; Atwood, R.A.; Richardson, K.L.

    1980-06-01

    From 1973 to 1978, Development Engineering, Inc. (DEI), a subsidiary of Paraho Development Corporation, demostrated the Paraho technology for surface oil shale retorting at Anvil Points, Colorado. A considerable amount of environmentally-related research was also conducted. This body of data represents the most comprehensive environmental data base relating to surface retorting that is currently available. In order to make this information available, the DOE Office of Environment has undertaken to compile, assemble, and publish this environmental data. The compilation has been prepared by DEI. This report includes the process characterization, air quality, and water quality categories.

  18. Report 20.4: Lumen and Chromaticity Maintenance of LED PAR38 Lamps |

    Energy Savers [EERE]

    Renewable Jet Fuel Is Taking Flight Renewable Jet Fuel Is Taking Flight August 26, 2015 - 3:58pm Addthis Zia Haq Senior Analyst and Defense Production Act Coordinator, Bioenergy Technologies Office It's been one year since we at the Energy Department ramped up our efforts to develop renewable jet fuel for the military and commercial aviation industry. The Department's Bioenergy Technologies Office (BETO) joined Farm to Fly 2.0-a partnership with the U.S. Department of Agriculture (USDA), the

  19. MHK ISDB/Sensors/Photosynthetic Light (PAR) with 3m cable Smart...

    Open Energy Info (EERE)

    Radiation (Solar) (1) Solar Radiation Sensor ... further results Also made by Onset Computer Corporation HOBO RX3000 Remote Monitoring SystemHOBO RX3000 Remote Monitoring...

  20. Microsoft PowerPoint - Snippet 5.5 PARS II Analysis-Trends Reports...

    Broader source: Energy.gov (indexed) [DOE]

    use of reports to assist in determining trends at both the Performance Measurement ... SV, VAC, & EAC Trends report, the Management Reserve (MR) Log, the Performance Index ...

  1. Microsoft PowerPoint - Snippet 5.6 PARS II Analysis-EAC Reasonableness...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    The other subfolder is Predictive Analysis, and includes two reports: Funding Status ... This formula is of no value if the ACWP exceeds the BAC. A mathematical difference of plus ...

  2. Astronomie, écologie et poésie par Hubert Reeves

    ScienceCinema (OSTI)

    None

    2011-10-06

    Hubert ReevesL'astrophysicien donne une conférence puis s'entretient avec l'écrivain François Bon autour de :"Astronomie, écologie et poésie"Pour plus d'informations : http://outreach.web.cern.ch/outreach/FR/evenements/conferences.htmlNombre de places limité. Réservation obligatoire à la Réception du CERN : +41 22 767 76 76  Soirée diffusée en direct sur le Web : http://webcast.cern.ch/      

  3. CALiPER Application Summary Report 17. LED AR111 and PAR36 Lamps

    SciTech Connect (OSTI)

    none,

    2012-08-01

    Report 17 analyzes the performance of a group of six LED products labeled as AR111 lamps. Results indicate that this product category lags behind other types of directional LED lamps but may perform acceptably in some applications and provide some energy savings.

  4. Lumen and Chromaticity Maintenance of LED PAR38 Lamps Operated in Steady-State Conditions

    SciTech Connect (OSTI)

    Royer, Michael P.

    2014-12-01

    The lumen depreciation and color shift of 38 different lamps (32 LED, 2 CFL, 1 ceramic metal halide [CMH], 3 halogen) were monitored in a specially developed automated long-term test apparatus (ALTA2) for nearly 14,000 hours. Five samples of each lamp model were tested, with measurements recorded on a weekly basis. The lamps were operated continuously at a target ambient temperature between 44°C and 45°C.

  5. Savannah River Laboratory monthly report

    SciTech Connect (OSTI)

    Not Available

    1985-12-01

    Efforts in the area of nuclear reactors and scientific computations are reported, including: robotics; reactor irradiation of nonend-bonded target slugs; computer link with Los Alamos National Laboratory; L-reactor thermal mitigation; aging of carbon in SRP reactor airborne activity confinement systems; and reactor risk assessment for earthquakes. Activities in chemical processes and environmental technology are reported, including: solids formation in a plutonium product stream; revised safety analysis reporting for F and H-Canyon operations; organic carbon analysis of DWPF samples; applications of Fourier transform infrared spectrometry; water chemistry analyzer for SRP reactors; and study of a biological community in Par Pond. Defense waste and laboratory operations activities include: Pu-238 waste incinerator startup; experimental canister frit blaster; saltstone disposal area design; powder metallurgy core diameter measurement; and a new maintenance shop facility. Nuclear materials planning encompasses decontamination and decommissioning of SRP facilities and a comprehensive compilation of environmental and nuclear safety issues. (LEW)

  6. How did contaminants get there?

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    comparison of Ashley Pond in the 1940s and 60 years later. Ashley Pond was named after Detroit businessman Ashley Pond who started the Los Alamos Ranch School in 1917. A comparison...

  7. Microsoft Word - S03729_Dec2007.doc

    Office of Legacy Management (LM)

    ... The telemetry data is routinely monitored by on-site staff ... Department of Energy Doc. No. S0372900 December 2007 Page 10 3.1.6 Pond 4 Pond 4 is a lined solar evaporation pond ...

  8. Public Availability of Engineering Evaluation / Cost Analysis (EE/CA) for Ash Pond Isolation Dike. I-1600-1603-1.07

    Office of Legacy Management (LM)

  9. Basic Engineering Research for D and D of R Reactor Storage Pond Sludge: Electrokinetics, Carbon Dioxide Extraction, and Supercritical Water Oxidation

    SciTech Connect (OSTI)

    Michael A. Matthews; David A. Bruce,; Thomas A. Davis; Mark C. Thies; John W. Weidner; Ralph E. White

    2002-04-01

    Large quantities of mixed low level waste (MLLW) that fall under the Toxic Substances Control Act (TSCA) exist and will continue to be generated during D and D operations at DOE sites across the country. The standard process for destruction of MLLW is incineration, which has an uncertain future. The extraction and destruction of PCBs from MLLW was the subject of this research Supercritical Fluid Extraction (SFE) with carbon dioxide with 5% ethanol as cosolvent and Supercritical Waster Oxidation (SCWO) were the processes studied in depth. The solid matrix for experimental extraction studies was Toxi-dry, a commonly used absorbent made from plant material. PCB surrogates were 1.2,4-trichlorobenzene (TCB) and 2-chlorobiphenyl (2CBP). Extraction pressures of 2,000 and 4,000 psi and temperatures of 40 and 80 C were studied. Higher extraction efficiencies were observed with cosolvent and at high temperature, but pressure little effect. SCWO treatment of the treatment of the PCB surrogates resulted in their destruction below detection limits.

  10. Systems and economic analysis of microalgae ponds for conversion of CO{sub 2} to biomass. Quarterly technical progress report, September 1993--December 1993

    SciTech Connect (OSTI)

    Benemann, J.R.; Oswald, W.J.

    1994-01-15

    This report provides an economic analysis and feasibility study for the utilization by microalgal systems of carbon dioxide generated from coal-fired power plants. The resulting biomass could be a fuel substitute for fossil fuels.

  11. Scale-up of Algal Biofuel Production Using Waste Nutrients

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    * SNL (16%) * MicroBio Engineering, Inc. (cost share) * Delhi County Water District (site host) Partners ... Middle pond is fed from deep a Facultative pond with more ...

  12. Type A Investigation - Subcontractor Fatality at the Savannah...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Fatality at the Savannah River Site Pond B Dam Upgrade Project, July 26, 2004 Type A Investigation - Subcontractor Fatality at the Savannah River Site Pond B Dam Upgrade ...

  13. EERE Success Story-Washington: Enabling the Successful Transition...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Model prediction and subsequent validation in climate-simulation pond cultures will enable the rapid and efficient identification of high-productivity strains, respective pond ...

  14. LANL-NMC Photobioreactors

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    ePBRs that fully simulate a microalgal biofuel pond production environment April 12, ... Users are invited to take advantage of this simulated microalgal biofuel pond production ...

  15. Microsoft PowerPoint - CY09 Annual Report Presentation - final.ppt [Read-Only]

    Office of Legacy Management (LM)

    09 Rocky Flats Stewardship Council June 7, 2010 Surface Water Monitoring and Operations Calendar Year 2009 3 Pond Operations - Calendar Year 2009 Terminal Pond Discharges: * Pond B-5 May 19 through June 6, 2009 (12.63 MG) * Pond A-4 May 23 through June 5, 2009 (9.1 MG) December 12 through December 21, 2009 (7.17 MG) * Pond C-2 May 26 through June 4, 2009 (4.84 MG) Transfers: * Pond A-3 to A-4 Four periods (24.62 MG total) Pond Levels: * As of January 1, 2010, Ponds A-3, A-4, B-5, and C-2 and the

  16. Exploring the Utilization of Complex Algal Communities to Address...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Algal Pond Crash and Increase Annual Biomass Production for Algal Biofuels Exploring the Utilization of Complex Algal Communities to Address Algal Pond Crash and Increase ...

  17. Remedial investigation work plan for Bear Creek Valley Operable Unit 1 (S-3 Ponds, Boneyard/Burnyard, Oil Landfarm, Sanitary Landfill 1, and the Burial Grounds, including Oil Retention Ponds 1 and 2) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee. Volume 1, Main text

    SciTech Connect (OSTI)

    Not Available

    1993-09-01

    The intent and scope of the work plan are to assemble all data necessary to facilitate selection of remediation alternatives for the sites in Bear Creek Valley Operable Unit 1 (BCV OU 1) such that the risk to human health and the environment is reduced to acceptable levels based on agreements with regulators. The ultimate goal is to develop a final Record Of Decision (ROD) for all of the OUs in BCV, including the integrator OU. However, the initial aim of the source OUs is to develop a ROD for interim measures. For source OUs such as BCV OU 1, data acquisition will not be carried out in a single event, but will be carried out in three stages that accommodate the schedule for developing a ROD for interim measures and the final site-wide ROD. The three stages are as follows: Stage 1, Assemble sufficient data to support decisions such as the need for removal actions, whether to continue with the remedial investigation (RI) process, or whether no further action is required. If the decision is made to continue the RI/FS process, then: Stage 2, Assemble sufficient data to allow for a ROD for interim measures that reduce risks to the human health and the environment. Stage 3, Provide input from the source OU that allows a final ROD to be issued for all OUs in the BCV hydrologic regime. One goal of the RI work plan will be to ensure that sampling operations required for the initial stage are not repeated at later stages. The overall goals of this RI are to define the nature and extent of contamination so that the impact of leachate, surface water runoff, and sediment from the OU I sites on the integrator OU can be evaluated, the risk to human health and the environment can be defined, and the general physical characteristics of the subsurface can be determined such that remedial alternatives can be screened.

  18. Addendum to the remedial investigation work plan for Bear Creek Valley Operable Unit 1 (S-3 ponds, boneyard/burnyard, oil landfarm, sanitary landfill I, and the burial grounds, including oil retention ponds 1 and 2) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee. Volume 1. main text

    SciTech Connect (OSTI)

    Not Available

    1994-08-01

    The BCV OU 1 location poses two problems that Data Quality Objectives will address: (1) whether the wastes and soil contamination pose a risk to human health or the environment now or in the future and (2) if the wastes and contamination do pose a risk, what feasible alternatives exist for reducing the risk to acceptable levels?

  19. EIS-0169-SA-08: Supplement Analysis

    Broader source: Energy.gov [DOE]

    Yakima/Klickitat Fisheries Project, Boone Pond Acclimation Site, Cle Elum, Kittitas County, Washington

  20. EA-1444: Finding of No Significant Impact

    Broader source: Energy.gov [DOE]

    Construction of a New Office Building, Childcare Facility, Parking Garage, and Storm water Retention Pond

  1. EA-1444: Final Environmental Assessment

    Broader source: Energy.gov [DOE]

    Construction of New Office Building, Child-Care Facility, Parking Garage, And Storm Water Retention Pond

  2. Microsoft PowerPoint - 2nd Qtr 2010 Presentation _compressed tt mh.ppt [Compatibility Mode]

    Office of Legacy Management (LM)

    Second Quarter 2010 Surveillance and Maintenance Report for the LM Rocky Flats Site 2 Surface Water Monitoring and Operations Second Quarter 2010 3 Pond Operations - Second Quarter 2010 Terminal Pond Discharges: * Pond A-4: May 1 through May 19, 2010, 32.4 MG * Pond B-5: April 23 through May 16, 2010, 20.8 MG Transfers: * A-3 to A-4: intermittently during the quarter; total of 24.2 MG Pond Levels: * As of June 1, 2010, Ponds A-3, A-4, B-5, and C-2 and the Landfill Pond were holding approximately

  3. Effects of coal fly-ash disposal on water quality in and around the Indiana Dunes National Lakeshore, Indiana. Water-resources investigations (final)

    SciTech Connect (OSTI)

    Hardy, M.A.

    1981-04-01

    Dissolved constituents in seepage from fly-ash settling ponds bordering part of the Indiana Dunes National Lakeshore (the Lakeshore) have increased trace elements, and gross alpha and gross beta radioactivity in ground water and surface water downgradient from the settling ponds. Data suggest that concentrations of some dissolved trace elements may be greater beneath interdunal pond 2 than in the pond. The soil system downgradient from the settling ponds seems to have affected the concentrations of dissolved ions in the settling-pond seepage. Calcium concentrations were greater in ground water downgradient from the settling ponds than in the ponds. Where organic material was present downgradient from the settling ponds, concentrations of arsenic, fluoride, molybdenum, potassium, sulfate, and strontium were greater in the ground water than in the ponds. In contrast, the concentrations of cadmium, copper, nickel, aluminum, cobalt, lead, and zinc were less.

  4. Draft Title 40 CFR 191 compliance certification application for the Waste Isolation Pilot Plant. Volume 8: Appendices HYDRO, IRD, LTM, NUTS, PAR, PMR, QAPD, RBP

    SciTech Connect (OSTI)

    1995-03-31

    Geohydrologic data have been collected in the Los Medanos area at the US Department of Energy`s proposed Waste Isolation Pilot Plant (WIPP) site in southeastern New Mexico since 1975 as part of a study evaluating the feasibility of storing defense-associated nuclear wastes within the bedded salt of the Salado Formation of Permian age. Drilling and hydrologic testing have identified three principal water-bearing zones above the Salado Formation and one below that could potentially transport wastes to the biosphere if the proposed facility were breached. The zones above the Salado are the contact between the Rustler and Salado Formations and the Culebra and Magenta Dolomite Members of the Rustler Formation of Permian age. The zone below the Salado Formation consists of channel sandstones in the Bell Canyon Formation of the Permian Delaware Mountain Group. Determinations of hydraulic gradients, directions of flow, and hydraulic properties were hindered because of the negligible permeability of the water-bearing zones. Special techniques in drilling, well completion, and hydraulic testing have been developed to determine the hydrologic characteristics of these water-producing zones.

  5. untitled

    Office of Legacy Management (LM)

    10 Surveillance and Maintenance Report for the LM Rocky Flats Site Surface Water Monitoring and Operations First Quarter 2010 First Quarter 2010 3 Pond Operations - First Quarter 2010 Terminal Pond Discharges: * None Transfers: * A-3 to A-4; intermittently during the quarter; total of approximately12.6 MG Pond Levels: * As of April 1, 2010, Ponds A-3, A-4, B-5, and C-2 and the Landfill Pond were holding approximately 32.6 MG (32.9 percent of capacity) August 17, 2010, Pond Levels * Landfill

  6. Annual Report of Site Surveillance and Maintenance Activities at the Rocky Flats Site, Colorado Calendar Year 2015

    Office of Legacy Management (LM)

    96 Table 33. Sampling and Data Evaluation Protocols at Predischarge Monitoring Locations Location Code Location Description Sample Types/ Frequencies Analytes Data Evaluation A4 POND Pond A-4 at east end of pond near outlet works Prior to opening outlet valve Pu, Am, total U, nitrate a Review with regulators prior to initiating discharge B5 POND Pond B-5 at east end of pond near outlet works Prior to opening outlet valve Pu, Am, total U, nitrate a Review with regulators prior to initiating

  7. Microsoft PowerPoint - 3rd Quarter 2009 Presentation _final.ppt

    Office of Legacy Management (LM)

    09 Surveillance and Maintenance Report for the LM Rocky Flats Site Surface Water Monitoring and Operations Third Quarter 2009 Third Quarter 2009 3 Pond Operations - Third Quarter 2009 Terminal Pond Discharges: * None Transfers: * None Pond Levels: * As of October 1, 2009, Ponds A-3, A-4, B-5, and C-2 and the Landfill Pond were holding approximately 19.2 MG (19.4 percent of capacity) December 30, 2009, Pond Levels * Landfill (21.3 percent) * A-3 (11.2 percent) * A-4 (10.8 percent) * B-5 (26.0

  8. Microsoft Word - S09641_2012Annual.docx

    Office of Legacy Management (LM)

    05 Figure 59. Predischarge Sampling Locations Table 45. Sampling and Data Evaluation Protocols at Predischarge Monitoring Locations Location Code Location Description Sample Types/ Frequencies Analytes Data Evaluation A4 POND Pond A-4 at east end of pond near outlet works Prior to opening outlet valve Pu, Am, total U, nitrate a Review with regulators prior to initiating discharge B5 POND Pond B-5 at east end of pond near outlet works Prior to opening outlet valve Pu, Am, total U, nitrate a

  9. Overview of the Second Quarter 2011 Surveillance and Maintenance Report for the LM Rocky Flats Site

    Office of Legacy Management (LM)

    of the Second Quarter 2012 Surveillance and Maintenance Report for the LM Rocky Flats Site April-June 2012 Surface Water Monitoring and Operations 2 Second Quarter 2012 2 Pond Operations - Second Quarter 2012  Terminal Pond Discharges: * Valves at A-4, B-5, and C-2 were opened in 2011; all Terminal Ponds are now operated in a flow-through mode  Pond Levels: * As of June 30, 2012, the Terminal Ponds were holding approximately 5.0 MG (6.4 percent of capacity) 3 3 October 15, 2012, Pond

  10. Slide 1

    Office of Legacy Management (LM)

    0 Surveillance and Maintenance Report for the LM Rocky Flats Site 2 Surface Water Monitoring and Operations Third Quarter 2010 Third Quarter 2010 3 Pond Operations - Third Quarter 2010  Terminal Pond Discharges: * Pond C-2: July 31 through August 12, 2010, 7.0 MG  Transfers: * A-3 to A-4: intermittently during the quarter; total of 3.0 MG  Pond Levels: * As of October 1, 2010, Ponds A-3, A-4, B-5, and C-2 and the Landfill Pond were holding approximately 15.3 MG (15.4 percent of

  11. CX-013885: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    BH Anhydrite Pond Sample Collection and Analysis - Pilot Test and Full Pond Chlorides Wash CX(s) Applied: B1.3Date: 07/06/2015 Location(s): None ProvidedOffices(s): Strategic Petroleum Reserve Field Office

  12. CX-013884: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    BH Anhydrite Pond Chlorides Wash - Pilot Test and Full Pond Chlorides Wash CX(s) Applied: B1.3Date: 07/06/2015 Location(s): None ProvidedOffices(s): Strategic Petroleum Reserve Field Office

  13. Hadlock, R.K.; Abbey, O.B. 22 GENERAL STUDIES OF NUCLEAR REACTORS...

    Office of Scientific and Technical Information (OSTI)

    on ultimate heat sinks--cooling ponds Hadlock, R.K.; Abbey, O.B. 22 GENERAL STUDIES OF NUCLEAR REACTORS; 20 FOSSIL-FUELED POWER PLANTS; COOLING PONDS; PERFORMANCE TESTING; NUCLEAR...

  14. Microsoft Word - Apr-June 2012 Monticello Quarterly_S09178_FFA...

    Office of Legacy Management (LM)

    ... or October 2012. Site Management Plan, Section 5 update ... Repository LCRS 1 & 2 (no action level) 0 5,000 10,000 ... Pond 4 Surveillance Checklist Level of Water in Pond 4 ...

  15. Microsoft Word - u01493_July2002.doc

    Office of Legacy Management (LM)

    ... The surface area of the pond will be approximately 11 acres, measured at the top. Assuming an average reliability of 95 percent for the extraction system, a pond with an area of 11 ...

  16. Savannah River Ecology Laboratory

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Risher Pond and Expansion This Set-Aside was selected for the habitat reserve program in the 1960s to represent an abandoned farm pond community. It also historically was...

  17. REPLY TO AITN Of.

    Office of Legacy Management (LM)

    ... supply,' (2) eat plant foods'grown on the site,' (3) eat meat and m ilk from livestock grown on the site, (4) eat fish from the pond, and (5) obtain all needed water from the pond. ...

  18. Savannah River Ecology Laboratory. Annual technical progress report of ecological research, period ending July 31, 1994

    SciTech Connect (OSTI)

    Not Available

    1994-07-31

    The Savannah River Ecology Laboratory (SREL) is a research unit of the University of Georgia (UGA) that is managed in conjunction with the University`s Institute of Ecology. The laboratory`s overall mission is to acquire and communicate knowledge of ecological processes and principles. SREL conducts basic and applied ecological research, as well as education and outreach programs, under an M&O contract with the US Department of Energy at the Savannah River Site. Significant accomplishments were made during the year ending July 31, 1994 in the areas of research, education and service. Reviewed in this document are research projects in the following areas: Environmental Operations Support (impacted wetlands, streams, trace organics, radioecology, database synthesis, wild life studies, zooplankton, safety and quality assurance); wood stork foraging and breeding ecology; defence waste processing facility; environmental risk assessment (endangered species, fish, ash basin studies); ecosystem alteration by chemical pollutants; wetlands systems; biodiversity on the SRS; Environmental toxicology; environmental outreach and education; Par Pond drawdown studies in wildlife and fish and metals; theoretical ecology; DOE-SR National Environmental Research Park; wildlife studies. Summaries of educational programs and publications are also give.

  19. "Title","Creator/Author","Publication Date","OSTI Identifier...

    Office of Scientific and Technical Information (OSTI)

    TESTING; NUCLEAR POWER PLANTS; HEAT SINKS; HEAT TRANSFER; PERFORMANCE; SIMULATION; THERMAL EFFICIENCY; EFFICIENCY; ENERGY TRANSFER; NUCLEAR FACILITIES; PONDS; POWER PLANTS;...

  20. Real Time Diagnostics for Algae-final-sm

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Real-time Monitoring And Diagnostics Detecting pathogens and predators to quickly recover from pond crashes Algal Pond Crash Detection Sandia National Laboratories is developing a suite of complementary technologies to help the emerging algae industry detect and quickly recover from algal pond crashes, an obstacle to large-scale algae cultivation for biofuels. Because of the way algae is grown and produced in most algal ponds, they are prone to attack by fungi, rotifers, viruses or other

  1. Essex County, Vermont: Energy Resources | Open Energy Information

    Open Energy Info (EERE)

    Vermont Granby, Vermont Guildhall, Vermont Island Pond, Vermont Lemington, Vermont Lewis, Vermont Lunenburg, Vermont Maidstone, Vermont Norton, Vermont Victory, Vermont...

  2. Microsoft PowerPoint - 3rd Qtr 2011 Presentation - Final.ppt

    Office of Legacy Management (LM)

    1 Surveillance and Maintenance Report for the LM Rocky Flats Site July-September 2011 2 2 Surface Water Monitoring and Operations Third Quarter 2011 Third Quarter 2011 3 3 Pond Operations - Third Quarter 2011 Terminal Pond Discharges: * Valves at both A-4 and B-5 were opened on 9/12/11; A-4 and B-5 are now operated in a flow-through mode Transfers: * A-3 in flow-through to A-4 Pond Levels: * As of October 1, 2011, Ponds A-3, A-4, B-5, and C-2 and the Landfill Pond were holding approximately 8.4

  3. Microsoft PowerPoint - CY11 Annual Report Presentation

    Office of Legacy Management (LM)

    1 Rocky Flats Stewardship Council June 4, 2012 2 Surface Water Monitoring and Operations Calendar Year 2011 Calendar Year 2011 3 Selected Surface Water Monitoring Locations Indiana Street W al nu t Cr ee k W o m a n C r e e k W om an Cr ee k N . W a ln u t C r e e k S . W a l n u t C r e e k C e n t r a l O U B o u n d a r y Pond C-2 Landfill Pond Pond A-3 Pond A-4 Pond B-5 GS31 GS11 GS08 GS03 GS01 GS10 SW093 SW027 WOMPOC WALPOC 4 4 Pond Operations - Calendar Year 2011  Terminal Pond

  4. Enhancing Earned Value (EV) Analysis Using Project Assessment...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    & Reporting System (PARS II) - Road Show Presentation Enhancing Earned Value (EV) Analysis Using Project Assessment & Reporting System (PARS II) - Road Show Presentation This ...

  5. Optional 2012 Project Management Workshop Course | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    February 16, 2012 - 4:29pm Addthis Course Title: Enhanced Earned Value Analysis Using PARS ... relative to PARS II functionality, business rules, reporting and analysis ...

  6. Microsoft PowerPoint - Snippet 5.1 PARSII Overview 20140627 ...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    asset project performance information. PARS II uses the same data as maintained in our contractors' project management ... PARS II contains a wealth of information. This snippet group ...

  7. Mesure de la section efficace de production de paires de quarks top dans l'etat final di-electron avec les donnees collectees par l'experience D0 au RunIIa

    SciTech Connect (OSTI)

    Martin Dit Latour, Bertrand; /LPSC, Grenoble

    2008-09-01

    The top quark has been discovered in 1995 by CDF and D0 collaborations in proton-antiproton collisions at the Tevatron. The amount of data recorded by both experiments makes it possible to accurately measure the properties of this very massive quark. This thesis is devoted to the measurement of the top pair production cross-section via the strong interaction, in a final state composed of two electrons, two particle jets and missing transverse energy. It is based on a 1 fb{sup -1} data set collected by the D0 experiment between 2002 and 2006. The reconstruction and identification of electrons and jets is of major importance in this analysis, and have been studied in events where a Z boson is produced together with one or more jets. The Z+jets process is indeed the dominant physics background to top pair production in the dielectron final state. The primary goal of this cross-section measurement is to verify Standard Model predictions. In this document, this result is also interpreted to indirectly extract the top quark mass. Moreover, the cross-section measurement is sensitive to new physics such as the existence of a charged Higgs boson. The selection established for the cross-section analysis has been used to search for a H{sup +} boson lighter than the top quark, where the latter can decay into a W{sup +} or H{sup +} boson and a b quark. The model that has been studied makes the assumption that the H{sup +} boson can only decay into a tau lepton and a neutrino.

  8. Exploring the Utilization of Complex Algal Communities to Address Algal

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Pond Crash and Increase Annual Biomass Production for Algal Biofuels | Department of Energy Exploring the Utilization of Complex Algal Communities to Address Algal Pond Crash and Increase Annual Biomass Production for Algal Biofuels Exploring the Utilization of Complex Algal Communities to Address Algal Pond Crash and Increase Annual Biomass Production for Algal Biofuels white paper exploring complex algal communities as a means of increasing algal biomass production PDF icon

  9. Lab provides environmental support for county construction projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Lab provides environmental support for county construction projects Community Connections: Your link to news and opportunities from Los Alamos National Laboratory Latest Issue:May 2016 all issues All Issues » submit Lab provides environmental support for county construction projects A face-lift for Ashley Pond November 1, 2013 Ashley Pond in Los Alamos under construction in the fall of 2013 Ashley Pond in Los Alamos under construction in the fall of 2013 Contact Community Programs Office

  10. EERE Success Story-Washington: Enabling the Successful Transition of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Microalgae from Lab to Pond | Department of Energy Washington: Enabling the Successful Transition of Microalgae from Lab to Pond EERE Success Story-Washington: Enabling the Successful Transition of Microalgae from Lab to Pond August 21, 2013 - 12:00am Addthis Pacific Northwest National Laboratory (PNNL) and EERE's Bioenergy Technologies Office have developed a unique, high-resolution spatio-temporal Biomass Assessment Tool (BAT) that realistically addresses the critical questions of how much

  11. San Bernardino National Wildlife Refuge Well 10

    SciTech Connect (OSTI)

    Ensminger, J.T.; Easterly, C.E.; Ketelle, R.H.; Quarles, H.; Wade, M.C.

    1999-12-01

    The U.S. Geological Survey (USGS), at the request of the U.S. Fish and Wildlife Service, evaluated the water production capacity of an artesian well in the San Bernardino National Wildlife Refuge, Arizona. Water from the well initially flows into a pond containing three federally threatened or endangered fish species, and water from this pond feeds an adjacent pond/wetland containing an endangered plant species.

  12. http://emdev.apps.em.doe.gov/EMDEV/Pages/groundwaterReport.aspx

    Office of Environmental Management (EM)

    Solar Ponds Remediation Contractor: Unknown Report Last Updated: 2009 Contaminants Halogenated VOCsSVOCs Present? No Fuel Present? No Metals Present? No Isotopes Present? Yes...

  13. Cullman County, Alabama: Energy Resources | Open Energy Information

    Open Energy Info (EERE)

    Cullman, Alabama Dodge City, Alabama Fairview, Alabama Garden City, Alabama Good Hope, Alabama Hanceville, Alabama Holly Pond, Alabama South Vinemont, Alabama West Point,...

  14. Sandia National Laboratories: News: Publications: Lab News

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    issue was identified as a key component in DOE's National Algal Biofuels Technology Roadmap. A three-pronged technical approach Sandia is addressing the algal pond crash issue...

  15. TITLE AUTHORS SUBJECT SUBJECT RELATED DESCRIPTION PUBLISHER AVAILABILI...

    Office of Scientific and Technical Information (OSTI)

    PLANTS HEAT SINKS HEAT TRANSFER PERFORMANCE SIMULATION THERMAL EFFICIENCY EFFICIENCY ENERGY TRANSFER NUCLEAR FACILITIES PONDS POWER PLANTS SURFACE WATERS TESTING THERMAL POWER...

  16. C:\\Imaging\\DOEID-11006.tif

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    soil . 88 acres of buried radioactive waste . Numerous wastewater ponds, underground storage tanks, unexploded ordnance sites, and uncharacterized landfills . 2.3 million gallons...

  17. Cellana | Open Energy Information

    Open Energy Info (EERE)

    Hwy 127 Place: Kailua-Kona, Hawaii Zip: 96740 Product: Hawaii-based JV between Shell and HR Biopetroleum focused on the development of Algae "Open pond" technologies....

  18. DG's Meeting

    ScienceCinema (OSTI)

    None

    2011-04-25

    Le DG H.Schopper informe et répond aux questions; l'association du personnel prend aussi la parole concernant salaires, pensions etc...

  19. Spruce Mountain | Open Energy Information

    Open Energy Info (EERE)

    In Service Owner Patriot Renewables Developer Patriot Renewables Energy Purchaser Energy New England Location Bryant Pond ME Coordinates 44.43443869, -70.55286884 Show Map...

  20. First Energy Solutions Corp. (New Jersey) | Open Energy Information

    Open Energy Info (EERE)

    Solutions Corp. Name: First Energy Solutions Corp. Abbreviation: FES Address: 341 White Pond Dr., Building B3 Place: Akron, Ohio Country: United States Zip: 44320 Service...

  1. Genome Science/Technologies

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    structure, splice variants, small RNAs) Biofuel production (pond health, strain ... Heavy computation is handled through a grid engine cluster and a Lustre-based distributed ...

  2. DISCLAIMER

    Office of Legacy Management (LM)

    ... in the Alluvial Aquifer-Data . . through September 1997 ... U.S. Department of Energy environmental assessment ... be collected on site in a solar evaporation pond; the ...

  3. Microsoft Word - S07118_IR

    Office of Legacy Management (LM)

    ... Mill tailings with low-level radioactivity were impounded at ... in Section III of the Annual Inspection Checklist. ... also includes the management and operation of Pond 4 ...

  4. Microsoft Word - Cover Page - Exhibit 8

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... Ragged Mountain State Forest Meadow Pond State Forest New Hampton Fish Hatchery Wilder Management Area Hamel State Forest Strawberry Hill State Forest Glencliff Home for the ...

  5. This Week In Petroleum Printer-Friendly Version

    Gasoline and Diesel Fuel Update (EIA)

    to cultivating algae. Open cultivation essentially grows algae much like it grows in nature. Open systems usually consist of one or more ponds exposed to the atmosphere, or...

  6. Type B Accident Investigation of the March 20, 2003, Stair Installatio...

    Broader source: Energy.gov (indexed) [DOE]

    More Documents & Publications Type A Investigation - Subcontractor Fatality at the Savannah River Site Pond B Dam Upgrade Project, July 26, 2004 Operating Experience Summary - ...

  7. TITLE

    Office of Legacy Management (LM)

    ... Act BLM U.S. Bureau of Land Management CERCLA ... Test Site, Colorado Rulison Gas Stimulation Test Site, ... wet meadows, river overflows. mudflats. and natural ponds. ...

  8. DOE/NV-441 Nevada Environmental Restoration Project Rulison Drilling...

    Office of Legacy Management (LM)

    ... monitoring requirements in Regulations ... device to increase natural gas production in ... The pond was left in place at the request of the land ...

  9. DOE/NV442 Environmental

    Office of Legacy Management (LM)

    ... device to increase natural gas production in ... The pond was left in place at the request of the land ... meet data quality requirements. 2.2 Personnel Training ...

  10. How did contaminants get there?

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    How did contaminants get there? How did contaminants get there? During the Manhattan Project, Los Alamos hosted thousands of employees, including many Nobel Prize-winning scientists. Historical operations used the best available waste handling methods for that time. August 1, 2013 A comparison of Ashley Pond in the 1940s and 60 years later. Ashley Pond was named after Detroit businessman Ashley Pond who started the Los Alamos Ranch School in 1917. A comparison of Ashley Pond in the 1940s and 60

  11. Sandia Energy - Better Monitoring and Diagnostics Tackle Algae...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Algae Biofuel Pond Crash Problem Home Renewable Energy Energy Transportation Energy Biofuels Capabilities News News & Events Research & Capabilities Systems Analysis Biomass...

  12. CX-011184: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Salmon Creek Pond Property Funding CX(s) Applied: B1.25 Date: 08/29/2013 Location(s): Washington Offices(s): Bonneville Power Administration

  13. Rapid ice-wedge melting accelerates permafrost decline

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    ... ponds result in more methane, but more drained land results in more carbon dioxide." ... unusually warm summer was enough to cause over 10 centimeters of surface subsidence. ...

  14. Women in STEM | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    Amanda Barry at Los Alamos National Laboratory's environmental photobioreactor matrix, which simulates microalgal biofuel pond conditions. Algal biofuels ...

  15. RAPID/Geothermal/Environment/Montana | Open Energy Information

    Open Energy Info (EERE)

    as surface disposal, septic systems, unlined ponds, overland flow, reuse and irrigation. Air Quality Assessment Process Developers may be required to obtain an air quality permit...

  16. Fourth Fridays Downtown - Under the Microscope

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    the Microscope: Explore the natural world through the eyes of microscopes. Examine pond water, plants, fibers, pollen, and more. August 28 - Robotics Night at the Museum: Try...

  17. Fourth Fridays Downtown - Exploring the Solar System

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    the Microscope: Explore the natural world through the eyes of microscopes. Examine pond water, plants, fibers, pollen, and more. August 28 - Robotics Night at the Museum: Try...

  18. Fourth Fridays Downtown

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    the Microscope: Explore the natural world through the eyes of microscopes. Examine pond water, plants, fibers, pollen, and more. August 28 - Robotics Night at the Museum: Try...

  19. Fourth Fridays Downtown - Working with Wind

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    the Microscope: Explore the natural world through the eyes of microscopes. Examine pond water, plants, fibers, pollen, and more. August 28 - Robotics Night at the Museum: Try...

  20. Limits to Growth

    ScienceCinema (OSTI)

    None

    2011-04-25

    Le Dr.Cole Thiemann, Directeur de l'Institut Battelle à Genève, fait un exposé et répond aux questions

  1. Related Links | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    July 2014 Exploring the Utilization of Complex Algal Communities to Address Algal Pond Crash and Increase Annual Biomass Production for Algal Biofuels National Algal Biofuels ...

  2. SREL Reprint #3260

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Hall, Ames, Iowa 50011-1210 USA Abstract: Terrestrial habitats surrounding isolated wetlands are a critical resource for many pond-breeding amphibian species, yet few studies...

  3. SREL Reprint #3290

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    University of Georgia, Aiken, South Carolina, USA Abstract: The creation of wetlands, such as urban and industrial ponds, has increased in recent decades, and these...

  4. EM International Program Action Table - June 2014 | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Action Table - June 2014 EM International Program Action Table - June 2014 EM International Program Action Table - June 2014 PDF icon EM International Program Action Table - June 2014 More Documents & Publications International Program Action Table - October 2012 Across the Pond Newsletter Issue 9 Across the Pond Newsletter Issue 3

  5. Shallow ground-water flow, water levels, and quality of water, 1980-84, Cowles Unit, Indiana Dunes National Lakeshore

    SciTech Connect (OSTI)

    Cohen, D.A.; Shedlock, R.J.

    1986-01-01

    The Cowles Unit of Indiana Dunes National Lakeshore in Porter County, northwest Indiana, contains a broad dune-beach complex along the southern shoreline of Lake Michigan and a large wetland, called the Great Marsh, that occupies the lowland between the shoreline dunes and an older dune-beach complex farther inland. Water levels and water quality in the surficial aquifer were monitored from 1977 to 1984 near settling ponds on adjacent industrial property at the western end of the Cowles Unit. Since 1980, when the settling pond bottoms were sealed, these intradunal lowlands contained standing water only during periods of high snowmelt or rainfall. Water level declines following the cessation of seepage ranged from 6 feet at the eastern-most settling pond to nearly 14 feet at the western-most pond. No general pattern of water table decline was observed in the Great Marsh or in the shoreline dune complex at distances > 3,000 ft east or north of the settling ponds. Since the settling ponds were sealed, the concentration of boron has decreased while concentrations of cadmium, arsenic, zinc, and molybdenum in shallow ground-water downgradient of the ponds show no definite trends in time. Arsenic, boron and molybdenum have remained at concentrations above those of shallow groundwater in areas unaffected by settling pond seepage. 11 refs., 10 figs., 1 tab.

  6. APPENDICES

    Office of Legacy Management (LM)

    WOMPOC: Woman Creek at Eastern COU Boundary A.1.4 WALPOC: Walnut Creek at Eastern COU Boundary A.1.5 GS05: Woman Creek at West Fenceline A.1.6 GS08: South Walnut Creek at Pond B-5 Outlet A.1.7 GS10: South Walnut Creek at B-1 Bypass A.1.8 GS11: North Walnut Creek at Pond A-4 Outlet A.1.9 GS12: North Walnut Creek at Pond A-3 Outlet A.1.10 GS13: North Walnut Creek Above Pond A-1 A.1.11 GS31: Woman Creek at Pond C-2 Outlet A.1.12 GS33: No Name Gulch at Walnut Creek A.1.13 GS51: Ditch South of Former

  7. Microsoft Word - appxa

    Office of Legacy Management (LM)

    GS05: Woman Creek at West Fenceline A.1.4 GS08: South Walnut Creek at Pond B-5 Outlet A.1.5 GS10: South Walnut Creek at B-1 Bypass A.1.6 GS11: North Walnut Creek at Pond A-4 Outlet A.1.7 GS12: North Walnut Creek at Pond A-3 Outlet A.1.8 GS13: North Walnut Creek Above Pond A-1 A.1.9 GS31: Woman Creek at Pond C-2 Outlet A.1.10 GS33: No Name Gulch at Walnut Creek A.1.11 GS51: Ditch South of Former 903 Pad A.1.12 GS59: Woman Creek Upstream of Antelope Springs Confluence A.1.13 B5INFLOW: South Walnut

  8. Microsoft Word - appxa.doc

    Office of Legacy Management (LM)

    GS05: Woman Creek at West Fenceline A.1.4 GS08: South Walnut Creek at Pond B-5 Outlet A.1.5 GS10: South Walnut Creek at B-1 Bypass A.1.6 GS11: North Walnut Creek at Pond A-4 Outlet A.1.7 GS12: North Walnut Creek at Pond A-3 Outlet A.1.8 GS13: North Walnut Creek above Pond A-1 A.1.9 GS31: Woman Creek at Pond C-2 Outlet A.1.10 GS33: No Name Gulch at Walnut Creek A.1.11 GS51: Ditch South of 903 Pad A.1.12 GS59: Woman Creek Upstream of Antelope Springs Confluence A.1.13 SW018: Functional Channel 2

  9. EVMS Training Snippet: 5.3 PARSII Analysis: Schedule Health Assessment

    Broader source: Energy.gov [DOE]

    This EVMS Training Snippet, sponsored by the Office of Project Management (PM) is one in a series regarding PARS II Analysis reports. PARS II offers direct insight into EVM project data from the...

  10. EVMS Training Snippet: 5.4 PARSII Analysis: Variance Reports

    Broader source: Energy.gov [DOE]

    This EVMS Training Snippet, sponsored by the Office of Project Management (PM) is one in a series regarding PARS II Analysis reports. PARS II offers direct insight into EVM project data from the...

  11. EVMS Training Snippet: 5.5 PARSII Analysis: Trend Reports

    Broader source: Energy.gov [DOE]

    This EVMS Training Snippet, sponsored by the Office of Acquisition and Project Management (OAPM) is one in a series regarding PARS II Analysis reports. PARS 2 offers direct insight into EVM project...

  12. EVMS Training Snippet: 5.6 PARSII Analysis: EAC Reasonableness and IEAC Development

    Broader source: Energy.gov [DOE]

    This EVMS Training Snippet, sponsored by the Office of Project Management (PM) is one in a series regarding PARS II Analysis reports. PARS II offers direct insight into EVM project data from the...

  13. EVMS Training Snippet: 5.4 PARSII Analysis: Variance Reports...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    sponsored by the Office of Project Management (PM) is one in a series regarding PARS II Analysis reports. PARS II offers direct insight into EVM project data from the...

  14. EVMS Training Snippet: 5.6 PARSII Analysis: EAC Reasonableness...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    sponsored by the Office of Project Management (PM) is one in a series regarding PARS II Analysis reports. PARS II offers direct insight into EVM project data from the...

  15. Product Efficiency Cases | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Standards). In its exception request, TLI requests exception relief for its principal product, a PAR-shaped daylight incandescent reflector lamp known as the SoLux PAR. September...

  16. DOE Publishes New CALiPER Report on Subjective Evaluation of...

    Energy Savers [EERE]

    New CALiPER Report on Subjective Evaluation of LED PAR38 Lamps DOE Publishes New CALiPER Report on Subjective Evaluation of LED PAR38 Lamps November 7, 2013 - 12:00am Addthis DOE...

  17. CALiPER Report 20.1: Subjective Evaluation of Beam Quality, Shadow...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Quality, Shadow Quality, and Color Quality for LED PAR38 Lamps CALiPER Report 20.1: Subjective Evaluation of Beam Quality, Shadow Quality, and Color Quality for LED PAR38 Lamps ...

  18. EVMS Training Snippet: 5.1 PARSII EVMS Reports Overview

    Broader source: Energy.gov [DOE]

    This EVMS Training Snippet, sponsored by the Office of Project Management (PM) provides an overview of the vast amount of data available in PARS II for EVMS analysis purposes. PARS II offers direct...

  19. Microsoft Word - Sept 2010.MeetingMinutes.FINAL

    Office of Environmental Management (EM)

    ... River Protection OSHA - Occupational Safety & Health Administration PARS - Project ... Moab remedial actions; Idaho cleanup project; Carlsbad carrier services and ...

  20. Improving Capital Assets Project Documentation | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    PARS II Data Quality Memorandum from Deputy Secretary Poneman (June 19, 2012) Smith Electric Vehicles: Advanced Vehicle Electrification + Transportation Sector...

  1. LA-UR-12-22318

    Office of Scientific and Technical Information (OSTI)

    PAR keyword enhanced New keyword LOC New keyword LOC New keyword DAT Benchmarking (NUSTLGoldhagen collaboration) Atmosphere (primary spectra, soon) ...

  2. Utilisation des défibrillateurs

    ScienceCinema (OSTI)

    None

    2011-10-06

    Information faite par le service medical et le service des pompiers sur l'utilisation des defibrillateurs.

  3. Annual Report

    Energy Savers [EERE]

    1 2011 Annual Report to the Oak Ridge Community Annual Report to the Oak Ridge Community DOE/ORO/2399 Progress Cleanup P Progress Cleanup P 2 This report was produced by URS | CH2M Oak Ridge LLC, DOE's Environmental Management contractor for the Oak Ridge Reservation. About the Cover After recontouring and revegetation, the P1 Pond at East Tennessee Technology Park is flourishing. The contaminated pond was drained, recontoured, and restocked with fish that would not disturb the pond sediment. 1

  4. Type A Investigation - Subcontractor Fatality at the Savannah River Site

    Energy Savers [EERE]

    Pond B Dam Upgrade Project, July 26, 2004 | Department of Energy - Subcontractor Fatality at the Savannah River Site Pond B Dam Upgrade Project, July 26, 2004 Type A Investigation - Subcontractor Fatality at the Savannah River Site Pond B Dam Upgrade Project, July 26, 2004 September 14, 2004 On July 26, 2004, at approximately 3:15 p.m., a truck driver (driver) was critically injured at the Savannah River Site, while loading a rented excavator onto a lowboy trailer for return to the rental

  5. Collection of High Energy Yielding Strains of Saline Microalgae from the Hawaiian Islands: Final Technical Report, Year 1

    SciTech Connect (OSTI)

    York, R. H.

    1986-01-01

    Microalgae were collected from 48 locations in the Hawaiian Islands in 1985. The sites were an aquaculture tank; a coral reef; bays; a geothermal steam vent; Hawaiian fish ponds; a Hawaiian salt punawai (well); the ocean; river mouths; saline lakes; saline pools; saline ponds; a saline swamp; and the ponds, drainage ditches and sumps of commercial shrimp farms. From 4,800 isolations, 100 of the most productive clones were selected to be maintained by periodic transfer to sterile medium. Five clones were tested for growth rate and production in a full-spectrum-transmitting solarium.

  6. Append_F_Stream Flow.xls

    Office of Legacy Management (LM)

    Date Surface ID Calculated Flow (ft 3 /sec) Comments 1/14/2000 CARB POND TRENCH OUT 0.25 Carb Pond trench outfall 1/14/2000 MNT CR E OF HWY CULV 0.22 MONTEZUMA CREEK 100 FT EAST OF HIGHWAY CULVERT 1/14/2000 MC>CUTOFFTRENCH CLAY 0.19 Montezuma Creek above ground water cutoff trench, clay bottom. 4/14/2000 MIDPOND OUTFALL PIPE 0.26 Middle Pond outfall pipe (groundwater impoundment in old Van Pile area) 4/14/2000 >VANPILE-STEEP/LINED 0.38 Montezuma Creek above old Vanadium Pile, where

  7. Appendix F Stream Flow.xls

    Office of Legacy Management (LM)

    Stream Flow Measurement Results Since 2000 This page intentionally left blank Appendix F Stream Flow Measurement Results Since 2000 Collect Date Surface ID Calculated Flow (ft 3 /sec) Comments 1/14/2000 CARB POND TRENCH OUT 0.25 Carb Pond trench outfall 1/14/2000 MNT CR E OF HWY CULV 0.22 MONTEZUMA CREEK 100 FT EAST OF HIGHWAY CULVERT 1/14/2000 MC>CUTOFFTRENCH CLAY 0.19 Montezuma Creek above ground water cutoff trench, clay bottom. 4/14/2000 MIDPOND OUTFALL PIPE 0.26 Middle Pond outfall pipe

  8. Microsoft Word - S02459_2006Annual GW Rpt.doc

    Office of Legacy Management (LM)

    Date Surface ID Calculated Flow (ft 3 /sec) Comments 1/14/2000 CARB POND TRENCH OUT 0.25 Carb Pond trench outfall 1/14/2000 MNT CR E OF HWY CULV 0.22 MONTEZUMA CREEK 100 FT EAST OF HIGHWAY CULVERT 1/14/2000 MC>CUTOFFTRENCH CLAY 0.19 Montezuma Creek above ground water cutoff trench, clay bottom. 4/14/2000 MIDPOND OUTFALL PIPE 0.26 Middle Pond outfall pipe (groundwater impoundment in old Van Pile area) 4/14/2000 >VANPILE-STEEP/LINED 0.38 Montezuma Creek above old Vanadium Pile, where

  9. Microsoft Word - S03623_2007AnnRep_091007.doc

    Office of Legacy Management (LM)

    Date Surface ID Calculated Flow (ft 3 /sec) Comments 1/14/2000 CARB POND TRENCH OUT 0.25 Carb Pond trench outfall 1/14/2000 MNT CR E OF HWY CULV 0.22 MONTEZUMA CREEK 100 FT EAST OF HIGHWAY CULVERT 1/14/2000 MC>CUTOFFTRENCH CLAY 0.19 Montezuma Creek above ground water cutoff trench, clay bottom. 4/14/2000 MIDPOND OUTFALL PIPE 0.26 Middle Pond outfall pipe (groundwater impoundment in old Van Pile area) 4/14/2000 >VANPILE-STEEP/LINED 0.38 Montezuma Creek above old Vanadium Pile, where

  10. Microsoft Word - S06596_GW.doc

    Office of Legacy Management (LM)

    Date Surface ID Calculated Flow (ft 3 /sec) Comments 1/14/2000 CARB POND TRENCH OUT 0.25 Carb Pond trench outfall 1/14/2000 MNT CR E OF HWY CULV 0.22 MONTEZUMA CREEK 100 FT EAST OF HIGHWAY CULVERT 1/14/2000 MC>CUTOFFTRENCH CLAY 0.19 Montezuma Creek above ground water cutoff trench, clay bottom. 4/14/2000 MIDPOND OUTFALL PIPE 0.26 Middle Pond outfall pipe (groundwater impoundment in old Van Pile area) 4/14/2000 >VANPILE-STEEP/LINED 0.38 Montezuma Creek above old Vanadium Pile, where

  11. DATE

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    7 SECTION A. Project Title: TRA-609 Compressed Air System Drain Line Modification and Valve Replacement SECTION B. Project Description: Due to periods of insufficient water flow to the sewer ponds, the clay liners in the ponds can dry out and crack. This proposed action is to add an additional drain line, which will allow clean well water that has been used to cool compressors to then be drained into the sewer system ponds during low flow periods in order to maintain a higher, more consistent

  12. DOE Publishes CALiPER Report on Lumen and Chromaticity Maintenance of LED

    Energy Savers [EERE]

    PAR38 Lamps | Department of Energy Lumen and Chromaticity Maintenance of LED PAR38 Lamps DOE Publishes CALiPER Report on Lumen and Chromaticity Maintenance of LED PAR38 Lamps February 11, 2015 - 2:54pm Addthis The U.S. Department of Energy's CALiPER program has released Report 20.4, which is part of a series of investigations on LED PAR38 lamps. Report 20.4 focuses on lumen maintenance, chromaticity maintenance, and catastrophic failure in 32 of the Series 20 LED PAR38 lamps and eight

  13. Simulation of water flow in terrestrial systems

    Energy Science and Technology Software Center (OSTI)

    2008-12-18

    ParFlow is a parallel, variabley saturated groundwater flow code that is especially suitable for large scale problem. ParFlow simulates the three-dimensional saturated and variably saturated subsurface flow in heterogeneous porous media in three spatial dimensions. ParFlow's developemt and appkication has been on-ging for more than 10 uear. ParFlow has recently been extended to coupled surface-subsurface flow to enabel the simulation of hillslope runoff and channel routing in a truly integrated fashion. ParFlow simulates the three-dimensionalmore » varably saturated subsurface flow in strongly heterogeneous porous media in three spatial dimension.« less

  14. SREL Reprint #3263

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    depleted and natural U, as well as other metals into the Tims Branch-Steed Pond water system. We investigated the current dynamics of this system for the purposes of...

  15. Central American

    Office of Scientific and Technical Information (OSTI)

    ... specialty crops.3 Geothermal energy is also being used in Nevada to w a m fish ponds for tropical fish prodction. One commercial plant, an onion dehydrating facility in Ne ...

  16. THERMAL PERFORMANCE MEASUREMENTS ON ULTIMATE HEAT SINKS - COOLING...

    Office of Scientific and Technical Information (OSTI)

    ... The spray pond and the fish tanks, illustrated in the figures, were dismantled prior to ... The water has been shown to be useful in the rearing of fish with the benefit that it ...

  17. CX-013882: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Replace Bayou Choctaw Brine Disposal/Recycle Piping in Pump/Pond Area CX(s) Applied: B1.3Date: 07/17/2015 Location(s): None ProvidedOffices(s): Strategic Petroleum Reserve Field Office

  18. SREL Reprint #3336

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    6 Temporal genetic and demographic monitoring of pond-breeding amphibians in three contrasting population systems Schyler O. Nunziata1, David E. Scott2, and Stacey L. Lance2...

  19. Recycling of Nutrients and Water in Algal Biofuels Production

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... Volatile Solids Steady-State period Pond culture crash Switch from peristaltic pump to rubber impeller pump 15 Milestone 1.4: Evaluate the need for a cell homogenizer April, 2013 ...

  20. 1

    Office of Environmental Management (EM)

    ... from the building conveys in an underground pipeline that discharges into a fire water retention pond. In compliance with Permit Section 9.4.7.1.ii, this closure plan will ...

  1. Vermont Individual Lake Encroachment Permit | Open Energy Information

    Open Energy Info (EERE)

    Abstract Submission of this application required for notice of intent to encroach beyond the mean water level of a lake or pond, and certify that the project will comply with...

  2. deb_pone.0065794 1..11

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... 12.5-112.5 kHz in the laboratory and found that during ... placed by the edge of a small pond, where nightly bat ... Our work did not require approval by an Institutional Animal ...

  3. N A

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    )000000000 000000 Chern Nuclear Property o 430 860 Meters Figure 17-2. Plant cOlIlIunities and soils associated with the Craig '.'I PondSarracenia Bay Set- Aside...

  4. Phase I A Phase I B Phase I C

    Office of Legacy Management (LM)

    300 Mag-82 Mag-81 Mag-80 Mag-83 Mag-84 Mound Closure Project - Current Parcels and Buildings FILE NAME: mndbldgparcelownerc.mxd DATE: Legend Parcel - DOE Parcel - MMCIC Pond...

  5. EA-1998: Upper Columbia Spring Chinook and Steelhead Acclimation...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    BPA is preparing an EA that will analyze the potential impacts of a proposal to fund the Yakama Nation to improve, develop, and use fish rearing acclimation ponds for hatchery ...

  6. DISCLAIMER

    Office of Legacy Management (LM)

    by U.S. Department of Energy Grand Junction Office ... in the Alluvial Aquifer-Data through September 1997 ... feed, will be pumped to a solar evaporation pond for final ...

  7. Microsoft Word - S04268_Mar07 thru Mar08.doc

    Office of Legacy Management (LM)

    ... at the U.S. Department of Energy (DOE) Office of Legacy ... An engineered solar evaporation pond receives the waste ... The data are then compared to baseline conditions determined ...

  8. Microsoft Word - toc.doc

    Office of Legacy Management (LM)

    ... Figure 3-6. Example Checklist for Monthly Pond 4 ... Hazardous waste-Waste material that is harmful to human ... LM-See Office of Legacy Management LM Records Collection-A ...

  9. 3 Reasons We're Closer to an Algae Future than You Think | Department...

    Broader source: Energy.gov (indexed) [DOE]

    carbon-neutral. In addition, algae can grow in a variety of environments -- including man-made ponds, brackish water and wastewater. While algae shows great potential as a...

  10. Tuba City, Arizona, Disposal Site Fact Sheet

    Office of Legacy Management (LM)

    ... A lined solar evaporation pond receives the waste liquid (brine) and the softener ... Disposal Cell Design The fve-sided disposal cell occupies an area of 50 acres on the ...

  11. CX-006032: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Building 850 Mitigation Pond, Site 300 Lawrence Livermore National LaboratoryCX(s) Applied: B1.20Date: 06/07/2011Location(s): CaliforniaOffice(s): Lawrence Livermore Site Office, NNSA-Headquarters

  12. Microsoft Word - Groundwater Discharge Permit

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    WIPP to discharge up to 23,000 gallons per day (gpd) of domestic wastewater to a sewage treatment system that consists of seven ponds, three of which may also be used for up to...

  13. Meat-, fish-, and poultry-processing wastes. [Industrial wastes

    SciTech Connect (OSTI)

    Litchfield, J.H.

    1982-06-01

    A review of the literature dealing with the effectiveness of various waste processing methods for meat-, fish,-, and poultry-processing wastes is presented. Activated sludge processes, anaerobic digestion, filtration, screening, oxidation ponds, and aerobic digestion are discussed.

  14. U0004500.DOC

    Office of Legacy Management (LM)

    ... regulatory requirements would not be met. ... water from the natural drainage that leads into the pond. 3.4 Land UsePopulation The ... there has been some oil and gas development. ...

  15. LiveFuels Inc | Open Energy Information

    Open Energy Info (EERE)

    Region: Bay Area Sector: Biofuels Product: Produces a biocrude from open-pond algae bioreactors Website: www.livefuels.com Coordinates: 37.500518, -122.246433 Show Map...

  16. CX-007514: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Record of Categorical Exclusion for Big Hill Anhydrite Pond Liner Replacement CX(s) Applied: B1.3 Date: 12/20/2011 Location(s): Texas Offices(s): Strategic Petroleum Reserve Field Office

  17. CX-011226: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Big Hill Anhydrite Pond Sampling and Analysis CX(s) Applied: B3.1 Date: 09/23/2013 Location(s): Texas Offices(s): Strategic Petroleum Reserve Field Office

  18. Microsoft Word - S04516_2008 GW Rpt Cover.doc

    Office of Legacy Management (LM)

    ... along the bank, and the pond becomes nearly choked with green algae in late summer. ... III Annual Groundwater Report October 2007-April 2008 U.S. Department of Energy Doc. No. ...

  19. EA-1959: Eightmile Ranch Coho Acclimation Site, Okanogan County...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    proved infeasible, so the Yakama Nation is proposing a new site at Eightmile Ranch. Young coho would be held in the pond from March to May and then released into the Chewuch...

  20. Savannah River Ecology Laboratory

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Like Rainbow Bay (Area 16), this temporary pond Set-Aside is one of the few Areas that has multiple plant communities associated with its basin. In addition, a significant portion ...

  1. Savannah River Ecology Laboratory

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Set-Aside is a 81.6-acre (33 ha) Area comprised of a semi-permanent, open-waterherbaceous pond surrounded by a partial buffer area of various pine and hardwood plant communities. ...

  2. Savannah River Ecology Laboratory

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    As a Set-Aside, this Area represents an isolated, semi-permanent rather than temporary, wetland pond. It is unique both for its lack of historical ditching and for the plant ...

  3. CX-013329: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Big Hill Anhydrite Pond 9 Closure CX(s) Applied: B1.23Date: 01/26/2015 Location(s): TexasOffices(s): Strategic Petroleum Reserve Field Office

  4. Microsoft Word - ENclosure 01 for TRANSMITTAL OF THE ENGINEERING...

    Office of Environmental Management (EM)

    ... The average annual temperature is 54 o F. Record high and low temperatures are 107 o F and -25 o F, ... of purposes, including a water treatment plant, holding ponds, sanitary ...

  5. DOE/PPPO/03-0098&D1/A1

    Office of Environmental Management (EM)

    ... The average annual temperature is 12.7 o C (55 o F). Record high and low temperatures are 39.4 o C (103 o F) and ... purposes, including a water treatment plant, holding ponds, ...

  6. Portsmouth/Paducah Project Office

    Energy Savers [EERE]

    ... The average annual temperature is 54 o F. Record high and low temperatures are 107 o F and -25 o F, ... of purposes, including a water treatment plant, holding ponds, sanitary ...

  7. APPENDICES

    Office of Legacy Management (LM)

    GS13: North Walnut Creek Above Pond A-1 A.1.11 GS31: Woman Creek at Pond C-2 Outlet A.1.12 GS33: No Name Gulch at Walnut Creek A.1.13 GS51: Ditch South of Former 903 Pad A.1.14 GS59: Woman Creek Upstream of Antelope Springs Confluence A.1.15 B5INFLOW: South Walnut Creek Above Pond B-5 A.1.16 SW027: South Interceptor Ditch at Pond C-2 A.1.17 SW093: North Walnut Creek 1,300 feet Upstream of A-1 Bypass A.2 Precipitation Data A.2.1 PG58: Gaging Station GS01 A.2.2 PG59: Gaging Station GS03 A.2.3

  8. Stephen Hawking

    ScienceCinema (OSTI)

    None

    2011-04-25

    Le grand astrophysicien S.Hawking, né le 08-01-1942 à Oxford, parle de "baby universes" et la gravitation et répond aux questions.

  9. LM 01-16

    Broader source: Energy.gov [DOE]

    NEPA ID: LM 01-16Short Title: Evaporation Pond Removal and Verification and Associated Road Maintenance, Durango, Colorado, Disposal SiteDetermination: B1.3 and B6.1

  10. Microsoft Word - NWTC Final SWEA 5.6.2014

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... as palustrine emergent: a small linear depression on the southern side of the NWTC, which ... Existing ponds would be graded to fill the depression to a depth of two feet above ...

  11. LANL

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Manhattan Project National Historical Park Pond Cabin, built in 1914, is listed on the New Mexico State Register of Historic Places and is the only surviving log structure at the Laboratory dating to the Homestead period. (Photo: Los Alamos) Plans for America's newest national park include admitting the public onto Laboratory property- without compromising national security or the Lab's mission. In 1914, Detroit businessman Ashley Pond constructed a log cabin on the Pajarito Plateau in

  12. Taylor-NERP.indd

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Publication of the Savannah River Ecology Laboratory National Environmental Research Park Program United States Department of Energy 2005 SRO-NERP-28 by: Adrienne E. DeBiase and Barbara E. Taylor Microcrustaceans (Branchiopoda and Copepoda) of Wetland Ponds and Impoundments on the Savannah River Site, Aiken, South Carolina Microcrustaceans (Branchiopoda and Copepoda) of Wetland Ponds and Impoundments on the Savannah River Site, Aiken, South Carolina by: Adrienne E. DeBiase and Barbara E. Taylor

  13. SREL Reprint #3149

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    9 Nesting Behavior of the Red-necked Pond Turtle (Mauremys [Chinemys] nigricans) in Captivity Andrew M. Grosse, Kurt A. Buhlmann, and Cris Hagen University of Georgia, Savannah River Ecology Laboratory, Building 737-A, Drawer E, Aiken, South Carolina 29802 Abstract: The Red-necked Pond Turtle (Mauremys [Chinemys] nigricans) is a small, semi-aquatic turtle known to occur in southern China (Guangdong Province) and perhaps in extreme northern Vietnam (Bonin et al., 2006; Fig. 1). This species is

  14. Symbiotically integrated organic recycling/renewable energy systems

    SciTech Connect (OSTI)

    Hamburg, R.A.

    1983-06-01

    Two operating systems designed for the integrated recycling of organic materials and production of renewable energy are described. Both systems include the Chinese design, water-pressure biogas digesters, a solar greenhouse and algae/aquatic plant ponds, all in passive symbiotic relationships with a minimum of high technology sophistication. A discussion of fish ponds and fuel alcohol production is also included since they offer many possibilities for expanded integration.

  15. Community Loblolly Pine Longleaf Pine D Mixed Pine/Hardwood

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    D Mixed Pine/Hardwood D Bottomland Hardwood _ Water _ Bottomland Hardwood/Pine IIIIiI Scrub/Shrub E2:I SRS Bays i&. Roads NUtility ROW EEl Hydric Soils 230 o 230 Vegetation Meters Soils Soil Series and Phase D BaB _w .Wm Figure 10-2. Plant communities and soils associated with the Risher Pond Set-Aside Area. 10-9 Set-Aside 10: Risher Pond

  16. Microsoft PowerPoint - 4A Craig Benson

    Office of Environmental Management (EM)

    Liners and Covers: Field Performance & Life Expectancy Craig H. Benson, PhD, PE, NAE Wisconsin Distinguished Professor University of Wisconsin-Madison Interagency Steering Committee on Performance and Risk Assessment Community of Practice Annual Technical Exchange Meeting 11-12 December 2014 Las Vegas, Nevada, USA Covers & Waste Containment Waste Groundwater Native soil Leachate storage pond Groundwater monitoring well Rainwater retention pond Gas vent or collection well Leachate

  17. Microsoft Word - S05993_CY2009 Annual Rpt.doc

    Office of Legacy Management (LM)

    7 3.1.2 Routine Monitoring 3.1.2.1 POC Monitoring This objective deals with monitoring discharges from the terminal ponds into Woman and Walnut creeks and streamflow at the additional POCs downstream at Indiana Street to demonstrate compliance with RFLMA surface-water-quality standards (see RFLMA Attachment 2, Table 1). Water-quality data at POCs are reportable under RFLMA when the applicable compliance parameters are greater than the corresponding Table 1 values (see Appendix D). Terminal pond

  18. Microsoft Word - S06584StSoil.doc

    Office of Legacy Management (LM)

    University of Arizona Letter This page intentionally left blank December 17, 2009 Memo to: Jody Waugh Regarding: Uranium in Former Evaporation Pond Area at Monument Valley We analyzed the stained surface soils in the former evaporation pond area and extended field west in the subpile soil area for a suite of heavy metals to determine if potential toxic substances were associated with the chemical stains observed in some areas of the site. This was part of Task 6, Mn Toxicity Field Study. Our

  19. Microsoft Word - S12421_2014 Annual Rpt.docx

    Office of Legacy Management (LM)

    92 Data Evaluation During CY 2014, no predischarge samples were collected from Ponds A-4, B-5, or C-2. All three terminal ponds were operated in a flow-through mode for all of CY 2014. 3.1.3 Rocky Flats Hydrology The following section provides information for all automated surface-water monitoring and precipitation gage locations at the Site that operated during CY 2014. For locations with continuous flow measurement, graphical discharge summaries are provided. Graphical summaries are also

  20. Steam-Electric Power-Plant-Cooling Handbook

    SciTech Connect (OSTI)

    Sonnichsen, J.C.; Carlson, H.A.; Charles, P.D.; Jacobson, L.D.; Tadlock, L.A.

    1982-02-01

    The Steam-Electric Power Plant Cooling Handbook provides summary data on steam-electric power plant capacity, generation and number of plants for each cooling means, by Electric Regions, Water Resource Regions and National Electric Reliability Council Areas. Water consumption by once-through cooling, cooling ponds and wet evaporative towers is discussed and a methodology for computation of water consumption is provided for a typical steam-electric plant which uses a wet evaporative tower or cooling pond for cooling.

  1. PART FIVE COMMON PROVISIONS ARTICLE XXIX. RECOVERY OF STATE COSTS

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    IIe Training PARS IIe Training PARS IIe has adopted alternative training strategy that increases training efficiency while reducing time commitment required from our users. We no longer provide day-long training sessions and instead offer technology-driven on-demand training videos as well as short, targeted live webinar. PARS IIe Controlled Unclassified Information (CUI) Release New CUI capabilities were succesfully released into production environment and PM-30 held several webinars to

  2. Enhancing Earned Value (EV) Analysis Using Project Assessment & Reporting

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    System (PARS II) - Road Show Presentation | Department of Energy Enhancing Earned Value (EV) Analysis Using Project Assessment & Reporting System (PARS II) - Road Show Presentation Enhancing Earned Value (EV) Analysis Using Project Assessment & Reporting System (PARS II) - Road Show Presentation This presentation was provided by the DOE Office of Project Management Oversight and Assessments (formerly DOE Office of Acquisition and Project Management) in January 2013. It is about the

  3. Retail Replacement Lamps | Department of Energy

    Energy Savers [EERE]

    CALiPER Testing » Application Reports » Retail Replacement Lamps Retail Replacement Lamps Annual CALiPER testing of A19, G25, candelabra, night light, MR16/PAR16, PAR20, and PAR30 replacement lamps - purchased directly from store shelves - offers insights on performance trends from year to year. The report findings offer valuable insights for manufacturers and retailers alike. Retail Lamps Study 3 (48 pages, February 2014) Retail Lamps Study 3.1: Dimming, Flicker, and Power Quality

  4. PF-2014-39b.pdf

    Office of Environmental Management (EM)

    Division, PM | Department of Energy PEP TALK "Policy - EVMS - PARS" Update, Mel Frank, Chief, Project Systems Division, PM PEP TALK "Policy - EVMS - PARS" Update, Mel Frank, Chief, Project Systems Division, PM Topics Discussed: New Handbooks New Terms and Definitions Training Opportunities/Snippets Data Driven Reviews Improvement Initiative Interpretation Handbook Current State/Challenges* Planned Enhancements Policy and Guidance / EVMS / PARS IIe PDF icon PEP Talk

  5. Microsoft PowerPoint - Snippet 3.3 Schedule Guidance & Resources...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Assessment and Reporting System (PARS II), and provides ... as well as to project performance and predictive analysis. ... for development and maintenance of integrated master ...

  6. Plant Physiology Data, Barrow, Alaska, 2013

    DOE Data Explorer [Office of Scientific and Technical Information (OSTI)]

    Alistair Rogers

    2015-01-13

    Survey measurements of photosynthetic rate and stomatal conductance together with carbon dioxide concentration, temperature, PAR, and relative humidity for 8 species on the BEO.

  7. "Title","Creator/Author","Publication Date","OSTI Identifier...

    Office of Scientific and Technical Information (OSTI)

    and PAR) records from Harvard Forest (Massachusetts) and Tapajos National Forest (Brazil) to establish empirical relationships among directly measured cloud type and cover...

  8. Evaluating the Contribution of Climate Forcing and Forest Dynamics...

    Office of Scientific and Technical Information (OSTI)

    and PAR) records from Harvard Forest (Massachusetts) and Tapajos National Forest (Brazil) to establish empirical relationships among directly measured cloud type and cover...

  9. TITLE AUTHORS SUBJECT SUBJECT RELATED DESCRIPTION PUBLISHER AVAILABILI...

    Office of Scientific and Technical Information (OSTI)

    and PAR records from Harvard Forest Massachusetts and Tapajos National Forest Brazil to establish empirical relationships among directly measured cloud type and cover...

  10. DI-MGMT-81861 DOE Changes Version | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Earned Value Management System Interpretation Handbook (EVMSIH) Enhancing Earned Value (EV) Analysis Using Project Assessment & Reporting System (PARS II) - Road Show Presentation...

  11. Evaluating the Contribution of Climate Forcing and Forest Dynamics...

    Office of Scientific and Technical Information (OSTI)

    direct and diffuse PAR. We developed a methodology for constructing synthetic incident ... DOE Contract Number: SC0004925 Resource Type: Technical Report Research Org: The Research ...

  12. "Paper" Energy Systems Acquisition Advisory Board Process | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Memo on "Paper" Energy Systems Acquisition Advisory Board Process from Jeffrey F. Kupper, dated January 14, 2009. PDF icon Memo Key Resources PMCDP EVMS PARS IIe FPD Resource ...

  13. Slide 1

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Page 5 Stage 2 Scope Meeting * Scope defined based on: - Stage 1 risk matrix and data analysis results - PARS II data verification - Contractor's Earned Value System description...

  14. EVMS and Project Analysis Standard Operating Procedure (EPASOP...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Enhancing Earned Value (EV) Analysis Using Project Assessment & Reporting System (PARS II) - Road Show Presentation Earned Value Management System Gold Card Integrated Program ...

  15. 2016 DOE Project Management Workshop - Area Restaurants | Department...

    Office of Environmental Management (EM)

    Area Restaurants 2016 DOE Project Management Workshop - Area Restaurants Information on surrounding area restaurants PDF icon Area restaurants Key Resources PMCDP EVMS PARS IIe FPD ...

  16. Quantum Well Thermoelectric Truck Air Conditioning

    Broader source: Energy.gov [DOE]

    Discusses advantages of quantum-well TE cooler, including no moving parts, no gases, performance on par with conventional, and easy switching to heat pump mode

  17. Slide 1

    Office of Environmental Management (EM)

    (i.e. DCMA 14 Point Assessment) * Document management - Updated Information Architecture (IA) - Advanced document search capabilities PARS IIe - Meeting the Challenge *...

  18. Plant Physiology Data, Barrow, Alaska, 2013

    DOE Data Explorer [Office of Scientific and Technical Information (OSTI)]

    Alistair Rogers

    Survey measurements of photosynthetic rate and stomatal conductance together with carbon dioxide concentration, temperature, PAR, and relative humidity for 8 species on the BEO.

  19. Slide 1

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Restructuring Project Assessment and Reporting System (PARS II) deployment completed JUN 10 SEP 10 EM Portfolio Management Framework developed for the EM ARRA program and...

  20. Program & Project Management For The Acquisition Of Capital Assets...

    Broader source: Energy.gov (indexed) [DOE]

    More Documents & Publications Program & Project Management For The Acquisition Of Capital Assets Program & Project Management For The Acquisition Of Capital Assets PARS II...

  1. KRK Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    KRK Capital Partners Jump to: navigation, search Name: KRK Capital Partners Place: Washington DC, Washington, DC Zip: 20002 Product: String representation "KRK Capital Par ......

  2. Slide 1

    Broader source: Energy.gov (indexed) [DOE]

    Stewardship- Providing the Value Proposition" PEP TALK Policy - EVMS - PARS Melvin Frank Chief, Project Systems DivisionMA-632 Office of Acquisition and Project ManagementMA-60...

  3. Midday Meeting- The Population Explosion

    ScienceCinema (OSTI)

    None

    2011-04-25

    Birth Control- Contraception- Family Planning (Inde, Chine....)- présenté par le Docteur A. Kessler, expert de ces problèmes

  4. This Week In Petroleum Summary Printer-Friendly Version

    Gasoline and Diesel Fuel Update (EIA)

    nonassociated gas field. Lack of foreign investment and insufficient financing, stemming from international sanctions, have slowed the development of South Pars. However,...

  5. Project Management Information Systems (PMIS) | Department of...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Project Management Information Systems (PMIS) Project Management Information Systems (PMIS) Project Assessment & Reporting System (PARS IIe) Office of Project Management Oversight...

  6. Enhancing Earned Value (EV) Analysis Using Project Assessment...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    FPD Resource Center PM Newsletter Forms and Templates More Documents & Publications DOE EVMS Risk Assessment Matrix PEP TALK "Policy - EVMS - PARS" Update, Mel Frank, Chief, ...

  7. Re-utilization of Industrial CO2 for Algae Production Using a Phase Change Material

    SciTech Connect (OSTI)

    Joseph, Brian

    2013-12-31

    This is the final report of a 36-month Phase II cooperative agreement. Under this project, Touchstone Research Laboratory (Touchstone) investigated the merits of incorporating a Phase Change Material (PCM) into an open-pond algae production system that can capture and re-use the CO2 from a coal-fired flue gas source located in Wooster, OH. The primary objective of the project was to design, construct, and operate a series of open algae ponds that accept a slipstream of flue gas from a coal-fired source and convert a significant portion of the CO2 to liquid biofuels, electricity, and specialty products, while demonstrating the merits of the PCM technology. Construction of the pilot facility and shakedown of the facility in Wooster, OH, was completed during the first two years, and the focus of the last year was on operations and the cultivation of algae. During this Phase II effort a large-scale algae concentration unit from OpenAlgae was installed and utilized to continuously harvest algae from indoor raceways. An Algae Lysing Unit and Oil Recovery Unit were also received and installed. Initial parameters for lysing nanochloropsis were tested. Conditions were established that showed the lysing operation was effective at killing the algae cells. Continuous harvesting activities yielded over 200 kg algae dry weight for Ponds 1, 2 and 4. Studies were conducted to determine the effect of anaerobic digestion effluent as a nutrient source and the resulting lipid productivity of the algae. Lipid content and total fatty acids were unaffected by culture system and nutrient source, indicating that open raceway ponds fed diluted anaerobic digestion effluent can obtain similar lipid productivities to open raceway ponds using commercial nutrients. Data were also collected with respect to the performance of the PCM material on the pilot-scale raceway ponds. Parameters such as evaporative water loss, temperature differences, and growth/productivity were tracked. The pond with the PCM material was consistently 2 to 5°C warmer than the control pond. This difference did not seem to increase significantly over time. During phase transitions for the PCM, the magnitude of the difference between the daily minimum and maximum temperatures decreased, resulting in smaller daily temperature fluctuations. A thin layer of PCM material reduced overall water loss by 74% and consistently provided algae densities that were 80% greater than the control pond.

  8. Preliminary characterization of the 100 area at Argonne National Laboratory

    SciTech Connect (OSTI)

    Biang, C.; Biang, R.; Patel, P.

    1994-06-01

    This characterization report is based on the results of sampling and an initial environmental assessment of the 100 Area of Argonne National Laboratory. It addresses the current status, projected data requirements, and recommended actions for five study areas within the 100 Area: the Lime Sludge Pond, the Building 108 Liquid Retention Pond, the Coal Yard, the East Area Burn Pit, and the Eastern Perimeter Area. Two of these areas are solid waste management units under the Resource Conservation and Recovery Act (the Lime Sludge Pond and the Building 108 Liquid Retention Pond); however, the Illinois Environmental Protection Agency has determined that no further action is necessary for the Lime Sludge Pond. Operational records for some of the activities were not available, and one study area (the East Area Burn Pit) could not be precisely located. Recommendations for further investigation include sample collection to obtain the following information: (1) mineralogy of major minerals and clays within the soils and underlying aquifer, (2) pH of the soils, (3) total clay fraction of the soils, (4) cation exchange capacity of the soils and aquifer materials, and (5) exchangeable cations of the soils and aquifer material. Various other actions are recommended for the 100 Area, including an electromagnetic survey, sampling of several study areas to determine the extent of contamination and potential migration pathways, and sampling to determine the presence of any radionuclides. For some of the study areas, additional actions are contingent on the results of the initial recommendations.

  9. Superfund Record of Decision (EPA Region 6): Mid-South Wood Products, Polk County, Arkansas, November 1986. First remedial action. Final report

    SciTech Connect (OSTI)

    Not Available

    1986-11-14

    The Mid-South Wood Products site is located in Polk County, Arkansas, approximately 1/2 mile southwest of Mena, Arkansas. The 57-acre site includes the following areas: the Old Plant site, the Small Old Pond and Old Pond areas, the North and South Landfarms, the landfill, Clear Lake and an existing chromated copper arsenate (CCA) treatment plant. The Old Plant site was used to treat wood with pentachlorophenol (PCP) and creosote; the Small Old Pond was the original impoundment for waste PCP and creosote. These two areas have been covered with soil. The Old Pond area was used to store PCP and creosote sludge and has since been graded and covered with soil; materials from the Old Pond were spread over the Landfarm areas and mixed into the soil; the Landfill area contains deposits of sawdust, woodchips, and other waste-wood products; Clear Lake receives runoff from all the above areas; the CCA treatment plant contains an ongoing wood-treating operation where the surface drainage from the plant is put in sumps.

  10. Chromium accumulation in three species of central Florida centrarchids

    SciTech Connect (OSTI)

    Campbell, K.R. |

    1995-02-01

    Stormwater ponds are required in Central Florida when land is developed to treat the resulting stormwater. The St. Johns River Water Management District, the agency that regulates stormwater discharges in Central Florida, frequently approves plans that create habitat for fish and wildlife by planting desirable wetland and aquatic vegetation in the littoral zones of stormwater ponds to compensate for the loss of wetlands. The various species of fish that inhabit stormwater ponds serve as a food source to wildlife, especially wading birds. The objective of this study was to determine if fish that live in stormwater treatment ponds in Orlando, Florida contained significant concentrations of chromium. In order to determine if there were differences in chromium concentrations in fish with different foraging strategies, three species of sunfish (Centrarchidae) with substantially different foraging strategies were selected for this study: largemouth bass (Micropterus salmoides), a predator; redear sunfish (Lepomis microlophus), a bottom feeder; and bluegill sunfish (Lepomis macrochirus), an omnivore. Many researchers have shown that large quantities of chromium are found in urban runoff. Chromium sources are largely associates with the operation of motor vehicles. Several investigators have determined that chromium from urban runoff concentrates in the sediment of stormwater ponds. Sediments represent the most concentrated physical pool of metals in aquatic environments, and they are ingested by many types of aquatic organisms. Most fish are capable of accumulating heavy metals from their diet and from water through their gills. 17 refs., 1 fig., 3 tabs.

  11. Use belowground storage tanks to manage stormwater

    SciTech Connect (OSTI)

    Nedrow, J.

    1996-01-01

    To meet performance and operating requirements under Resource Conservation and Recovery Act (RCRA), BP Oil`s Toledo Refinery installed two 10-million-gallon (MMgal) concrete belowground storage tanks to replace the existing impoundment ponds. Environmental, safety and operating criteria influenced how this older refinery could cost-effectively replace impoundment ponds without interrupting the production schedule. The north stormwater impoundment pond at BP Oil`s Toledo Refinery had received primary sludge, a RCRA-listed hazardous waste and material exceeding the toxic characteristic limit for benzene (0.5 ppm). Because the pond could not be adapted to meet RCRA standards, it had to be replaced by a system that met these standards and New Source Performance Standards (NSPS). Under normal operating conditions, stormwater was commingled with process wastewater and processed at the wastewater treatment unit (WWTU) before final disposal. However, when flow in the sewer system exceeded the capacity of the WWTU, excess flow was stored in an impoundment system. The case history shows how BP Oil`s project engineers, working with a consulting engineering group and a general contractor (GC), cost-effectively replaced the impoundment pond to handle stormwater runoff for the refinery.

  12. Savannah River Ecology Laboratory Annual Technical Progress Report of Ecological Research, June 30, 2001

    SciTech Connect (OSTI)

    Bertsch, Paul M.; Janecek, Laura; Rosier, Brenda

    2001-06-30

    The Savannah River Ecology Laboratory (SREL) is a research unit of the University of Georgia (UGA) and has been conducting ecological research on the Savannah River Site (SRS) in South Carolina for 50 years. The overall mission of the Laboratory is to acquire and communicate knowledge of ecological processes and principles. SREL conducts fundamental and applied ecological research, as well as education and outreach programs, under a Cooperative Agreement with the U.S. Department of Energy (DOE) SRS near Aiken, South Carolina. The Laboratory's research mission during the 2001 fiscal year was fulfilled with the publication of one book and 83 journal articles and book chapters by faculty, technical staff, students, and visiting scientists. An additional 77 journal articles have been submitted or are in press. Other noteworthy events took place as faculty members and graduate students received awards. These are described in the section Special Accomplishments of Faculty, Staff, Students, and Administration on page 54. Notable scientific accomplishments include work conducted on contaminant transport, global reptile decline, phytoremediation, and radioecology. Dr. Domy Adriano authored the second edition of his book ''Trace Elements in Terrestrial Environments: Biogeochemistry, Bioavailability, and Risks of Metals'', which was recently published by Springer-Verlag. The book provides a comprehensive treatment of many important aspects of trace elements in the environment. The first edition of the book, published in 1986, has become a widely acclaimed and cited reference. International attention was focused on the problem of reptile species decline with the publication of an article on this topic in the journal ''Bioscience'' in August, 2000. The article's authors included Dr. Whit Gibbons and a number of other SREL herpetologists who researched the growing worldwide problem of decline of reptile species. Factors related to these declines include habitat loss and degradation, introduction of invasive species, environmental pollution, disease, global climate change, and unsustainable commercial use. The conclusion reached by the article is that the disappearance of reptiles from the natural world is genuine and should be a matter of concern; current evidence suggests that these declines constitute a worldwide crisis. SREL's research in the area of phytoremediation was enhanced with the addition of Dr. Lee Newman as a faculty member in January 2001. Dr. Newman, an internationally recognized authority in the field, holds a joint appointment with the University of South Carolina and SREL. She is developing a collaborative program in phytoremediation on the SRS and offsite. Work is nearing completion on SREU s outdoor mesocosm irradiation facility, which is designed for studying the effects of low-level radiation doses on organisms. The 1-acre facility at Par Pond consists of 48 fiberglass tanks that can maintain small organisms such as fish and amphibians. Thirty of the tanks have sealed {sup 137}Cs sources suspended above them containing either 0.02,0.2, or 2.0 Ci. These sources can deliver average dose rates of 4, 40 and 400 mGy per day, respectively, to organisms under replicated conditions.

  13. Annual Report of Site Surveillance and Maintenance Activities at the Rocky Flats Site, Colorado Calendar Year 2015

    Office of Legacy Management (LM)

    A: Hydrologic Data A.1 Surface-Water Discharge Data A.1.1 GS01: Woman Creek at Indiana Street A.1.2 GS03: Walnut Creek at Indiana Street A.1.3 WOMPOC: Woman Creek at Eastern COU Boundary A.1.4 WALPOC: Walnut Creek at Eastern COU Boundary A.1.5 GS05: Woman Creek at West Fenceline A.1.6 GS08: South Walnut Creek at Pond B-5 Outlet A.1.7 GS10: South Walnut Creek at B-1 Bypass A.1.8 GS11: North Walnut Creek at Pond A-4 Outlet A.1.9 GS12: North Walnut Creek at Pond A-3 Outlet A.1.10 GS13: North Walnut

  14. Microsoft PowerPoint - CY12 Annual Report Presentation - final.ppt [Compatibility Mode]

    Office of Legacy Management (LM)

    2 Rocky Flats Stewardship Council June 3, 2013 2 Surface Water Monitoring Calendar Year 2012 3 RFLMA Surface Water Monitoring Locations " ) " ) # * # * # * # * ! ( ! ( ! ( Indiana Street W al nu t C re ek W o m a n C r e e k W om an C re ek N . W a ln u t C r e e k S . W a l n u t C r e e k C e n t r a l O U B o u n d a r y PLFTS Pond C-2 Pond A-4 Pond B-5 GS03 GS01 GS10 SW093 SW027 GS59 WOMPOC WALPOC Present Landfill Original Landfill Performance Monitoring at Original and Present

  15. Microsoft PowerPoint - FINAL 2014 Annual Present_RFSC-June 2015.pptx

    Office of Legacy Management (LM)

    Flats, Colorado, Site Annual Report of Site Surveillance and Maintenance Activities Calendar Year 2014 Rocky Flats Stewardship Council June 1, 2015 Surface Water Monitoring Calendar Year 2014 Selected Rocky Flats Legacy Management Agreement (RFLMA) Surface Water Monitoring Locations 3 Indiana Street W aln ut Cr ee k W o m a n C r e e k W om an Cr ee k N . W a ln u t C r e e k S . W a l n u t C r e e k C e n t r a l O U B o u n d a r y PLFTS Pond C-2 Pond A-4 Pond B-5 GS10 SW093 SW027 GS59 WOMPOC

  16. The clean water act -- (Federal Water Pollution Control Act), what it means to utilities

    SciTech Connect (OSTI)

    Talt, L.A.

    1996-10-01

    Departing from previous policy, in August 1993 the USEPA`s Water Office recommended that the agency regulate a proposed electric power plant`s cooling pond as a water of the US. At issue was a proposal by Florida Power corp. to build a new electric power plant in Polk County, Florida. A 2,600 acre cooling pond to collect heated and discharged water was included in the proposal. Region 4 USEPA staff asked USEPA Headquarters in Washington, DC to decide whether the pond was exempt from the CWA or a water of the US. The pond could be a habitat for migratory birds according to a memo prepared by Region 4 staff. The USEPA Water Office used the presence of migratory birds to claim a nexus to interstate commerce and therefore concluded that the pond should be regulated under the CWA. Electric power industry proponents have argued that an overly expansive definition of waters of the US may result in any new power plant being required to construct cooling towers. Cooling towers are said to be a more expensive and wasteful method to cool heated water. Region 4 ultimately recanted its earlier position after considerable discussions with various other Environmental Protection Agency offices and, no doubt industry pressure. Florida Power Corp. was not required to obtain an NPDES permit for the cooling pond. The lesson of Florida Power Corp. is that the regulatory environment for utilities can be uncertain under the Clean Water Act even in the face of a relatively straightforward exemption from regulation.

  17. Nanotechnology and algae biofuels exhibits open July 26 at the Bradbury

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Science Museum Nanotechnology and algae biofuels exhibits open July 26 Nanotechnology and algae biofuels exhibits open July 26 at the Bradbury Science Museum The Bradbury Science Museum is opening two new exhibits as part of the Laboratory's 70th Anniversary celebration. July 22, 2013 What if you could power your life using pond scum? Los Alamos researchers are working to make this a reality. What if you could power your life using pond scum? Los Alamos researchers are working to make this a

  18. 2015 Cleanup Progress

    Energy Savers [EERE]

    OREM-15-2526 leanup Annual Report to the Oak Ridge Regional Community P 2015 C rogress 2 About the Cover Wildlife is as much a part of the East Tennessee Technology Park landscape as the buildings and structures that are being demolished. The Tennessee Urban Forestry Council has designated a stretch of land near a remediated ETTP pond as a certified arboretum. The cover photo shows two tree swallows that nest in the birdhouses erected near the pond. 1 Message from the EM Manager Department of

  19. ALDUO(TM) Algae Cultivation Technology for Delivering Sustainable Omega-3s, Feed, and Fuel

    SciTech Connect (OSTI)

    Bai, Xuemei

    2012-09-24

    * ALDUO(TM) Algae Production Technology Cellana?s Proprietary, Photosynthetic, & Proven * ALDUO(TM) Enables Economic Algae Production Unencumbered by Contamination by Balancing Higher-Cost PBRs with Lower-Cost Open Ponds * ALDUO(TM) Advantages * ALDUO(TM) Today o Large collection of strains for high value co-products o Powerful Mid-scale Screening & Optimization System o Solution to a Conflicting Interest o Split Pond Yield Enhancement o Heterotrophy & mixotrophy as a "finishing step" o CO2 Mitigation-flue Gas Operation o Worldwide Feed Trials with Livestock & Aquatic Species * ALDUO(TM) Technology Summarized

  20. Integrated renewable energy/organic waste recycling system. Final report, July 31, 1982

    SciTech Connect (OSTI)

    Hamburg, R.A.; Davenport, S.

    1982-01-01

    Two operating systems for integrated recycling of organic materials are described. The systems include Chinese water-pressure design biogas digesters/solar greenhouses/and algae and aquatic plant ponds-all in passive symbiotic relationships with a minimum of technological sophistication. Economic, Financial and Net Energy Analyses of these systems have been done with concern toward long term environmental effects. A discussion of fish ponds and fuel alcohol production is also included since they offer much potential for expanded integration. 21 tabs.

  1. Los Alamos National Laboratory

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    In 1914, Detroit businessman Ashley Pond constructed a log cabin on the Pajarito Plateau in north-central New Mexico. The one-room structure served as the office for the Pajarito Club, a guest ranch for well-heeled city folk looking for a little Wild West adventure. Although the Pajarito Club was short-lived (it disbanded in 1916), Pond remained in the area and went on to found the Los Alamos Ranch School in 1917. The elite prep school offered classical education and rigorous outdoor activity

  2. Science and Suds

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Science and Suds Science and Suds WHEN: Jul 18, 2015 12:00 PM - 4:00 PM WHERE: Los Alamos ScienceFest Beer Garden Ashley Pond, Downtown Los Alamos, NM CONTACT: Jessica Privette 505 667-0375 CATEGORY: Bradbury INTERNAL: Calendar Login Science and Suds - Social Event Event Description Conversations with real scientists at the Los Alamos ScienceFest Beer Garden SCIENCE & SUDS Stop by the museum's tent in the beer garden at Ashley Pond during Los Alamos ScienceFest to visit with a scientist

  3. Microsoft Word - Exec Summ CR.doc

    Office of Legacy Management (LM)

    Durango, Colorado Page 4-1 4.0 Durango, Colorado, Disposal Site 4.1 Compliance Summary The Durango, Colorado, Disposal Site, inspected on June 7, 2005, was in good condition. The holding pond northeast of the disposal cell retains transient drainage water from the cell that has been collected and treated with zero-valent iron. Because the water level in the disposal cell has dropped, water currently is not being treated. Breaks in the holding pond drainpipes are not scheduled for repair because

  4. Water Analytical Data Tables for 1CQ11.xls

    Office of Legacy Management (LM)

    Analytical Results for Water Samples-First Quarter CY 2011 This page intentionally left blank Appendix C1 Analytical Results for Water Samples - First Quarter CY 2011 LOCATION_CODE LOCATION_TYPE DATE SAMPLED LAB REQUISITION NUMBER CAS ANALYTE SAMPLE ID RESULT UNITS LAB QUALIFIERS SAMPLE TYPE DETECTION LIMIT UNCER- TAINTY DATA VALIDATION QUALIFIERS A4 POND SL 1/12/2011 11013559 NO3+NO2 AS N Nitrate + Nitrite as Nitrogen N001 0.043 mg/L J F 0.019 valid A4 POND SL 1/12/2011 11013559 7440-61-1

  5. Algae to Biofuels

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Algae to Biofuels Algae to Biofuels What if you could power your life using pond scum? Algae, plant-like aquatic microorganisms, produce oil similar to petroleum and can be grown almost anywhere, don't need to be fed and actually remove pollution from the air. algae Squeezing Power from Pond Scum Near industrial plants on undesirable land, scientists raise algae that suck up harmful exhaust and thrive in the non-drinkable wastewater. algae Why Algae? Algae produce at least 32 times more oil than

  6. Effects from influent boundary conditions on tracer migration and spatial variability features in intermediate-scale experiments

    SciTech Connect (OSTI)

    Fuentes, H.R.; Polzer, W.L.; Springer, E.P.

    1987-04-01

    In previous unsaturated transport studies at Los Alamos dispersion coefficients were estimated to be higher close to the tracer source than at greater distances from the source. Injection of tracers through discrete influent outlets could have accounted for those higher dispersions. Also, a lack of conservation of mass of the tracers was observed and suspected to be due to spatial variability in transport. In the present study experiments were performed under uniform influent (ponded) conditions in which breakthrough of tracers was monitored at four locations at each of four depths. All other conditions were similar to those of the unsaturated transport experiments. A comparison of results from these two sets of experiments indicates differences in the parameter estimates. Estimates were made for the dispersion coefficient and the retardation factor by the one-dimensional steady flow computer code, CFITIM. Estimates were also made for mass and for velocity and the dispersion coefficient by the method of moments. The dispersion coefficient decreased with depth under discrete influent application and increased with depth under ponded influent application. Retardation was predicted better under the discrete influent application than under ponded influent application. Differences in breakthroughs and in estimated parameters among locations at the same depth were observed under ponded influent application. Those differences indicate that there is a lack of conservation of mass as well as significant spatial variability across the experimental domain. 14 refs., 9 figs., 8 tabs.

  7. Lawrence Co. Scioto Co. Greenup Co. Jack

    U.S. Energy Information Administration (EIA) Indexed Site

    NE BREEDEN MAR E CREEK SCHOOL FAR LEY C HUR CH W LON G R UN LICKBURG RPD-GALLIA-1 MIMA LEF ... HINDMAN E STAF FORD SPEIGHT E ST EPHENS JUM PIN G BR AN CH GRASSY CREEK RICH POND WH ITMER ...

  8. Final Technical Report, DE-SC0000581

    SciTech Connect (OSTI)

    Douglas C. Lynn, Executive Director

    2010-12-28

    The focus of the CEHMM award was alternative energy research and education. The objective of the CEHMM algae to biodiesel project was to determine the viability and feasibility of using algae as a feedstock for commercial biodiesel production. The project investigated the propagation, harvesting and extraction of oil from a salt/brine water algae in open raceway ponds.

  9. Savannah River Ecology Laboratory annual technical progress report of ecological research, period ending July 31, 1993

    SciTech Connect (OSTI)

    Vaitkus, M.R.; Wein, G.R.; Johnson, G.

    1993-11-01

    This progress report gives an overview of research programs at the Savannah River Site. Topics include; environmental operations support, wood stork foraging and breeding, defense waste processing, environmental stresses, alterations in the environment due to pollutants, wetland ecology, biodiversity, pond drawdown studies, and environmental toxicology.

  10. EIS-0384: Chief Joseph Hatchery Program, Washington

    Broader source: Energy.gov [DOE]

    This EIS analyzes DOE's approach and associated impacts of a comprehensive management program for summer/fall Chinook salmon in the Okanogan subbasin and the Columbia River between the confluence of the Okanogan River and Chief Joseph Dam including construction, operation, and maintenance of a hatchery and acclimation ponds.

  11. CX-005073: Categorical Exclusion Determination

    Office of Energy Efficiency and Renewable Energy (EERE)

    Energy Efficiency and Conservation Block Grant Subgrant: Lums Pond State Park Natural Gas ConversionCX(s) Applied: B2.5Date: 01/25/2011Location(s): DelawareOffice(s): Energy Efficiency and Renewable Energy, Golden Field Office

  12. EA-1998: Upper Columbia Spring Chinook and Steelhead Acclimation Project, Chelan County, Washington

    Broader source: Energy.gov [DOE]

    BPA is preparing an EA that will analyze the potential impacts of a proposal to fund the Yakama Nation to improve, develop, and use fish rearing acclimation ponds for hatchery raised steelhead and Chinook salmon in the Methow and Wenatchee watersheds. Additional information is available at http://efw.bpa.gov/environmental_services/Document_Library/ChinookSteelh....

  13. Sanitary Landfill Groundwater Monitoring Report - Fourth Quarter 1998 and 1998 Summary

    SciTech Connect (OSTI)

    Chase, J.

    1999-04-09

    A maximum of fifty-three wells of the LFW series monitor groundwater quality in the Steed Pond Aquifer (Water Table) beneath the Sanitary Landfill at the Savannah River Site (SRS). These wells are sampled quarterly to comply with the South Carolina Department of Health and Environmental Control Domestic Water permit and as part of the SRS Groundwater Monitoring Program.

  14. Portsmouth Decontamination & Decommissioning | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Decontamination & Decommissioning Portsmouth Decontamination & Decommissioning The Decontamination & Decommissioning (D&D) Program at the Portsmouth Site addresses potential future demolition and disposal of approximately 415 facilities (including buildings, utilities, systems, ponds and infrastructure units) currently identified on the Portsmouth site. This includes the three Gaseous Diffusion Process buildings that housed the process equipment and span the size of 158 football

  15. Treatability studies of actual listed waste sludges from the Oak Ridge Reservation (ORR)

    SciTech Connect (OSTI)

    Jantzen, C.M.; Peeler, D.K.; Gilliam, T.M.; Bleier, A.; Spence, R.D.

    1996-05-06

    Oak Ridge National Laboratory (ORNL) and Savannah River Technology Center (SRTC) are investigating vitrification for various low-level and mixed wastes on the Oak Ridge Reservation (ORR). Treatability studies have included surrogate waste formulations at the laboratory-, pilot-, and field-scales and actual waste testing at the laboratory- and pilot-scales. The initial waste to be processing through SRTC`s Transportable Vitrification System (TVS) is the K-1407-B and K-1407-C (B/C) Pond sludge waste which is a RCRA F-listed waste. The B/C ponds at the ORR K-25 site were used as holding and settling ponds for various waste water treatment streams. Laboratory-, pilot-, and field- scale ``proof-of-principle`` demonstrations are providing needed operating parameters for the planned field-scale demonstration with actual B/C Pond sludge waste at ORR. This report discusses the applied systems approach to optimize glass compositions for this particular waste stream through laboratory-, pilot-, and field-scale studies with surrogate and actual B/C waste. These glass compositions will maximize glass durability and waste loading while optimizing melt properties which affect melter operation, such as melt viscosity and melter refractory corrosion. Maximum waste loadings minimize storage volume of the final waste form translating into considerable cost savings.

  16. Water quality investigation of Kingston Fossil Plant dry ash stacking

    SciTech Connect (OSTI)

    Bohac, C.E.

    1990-04-01

    Changing to a dry ash disposal systems at Kingston Fossil Plant (KFP) raises several water quality issues. The first is that removing the fly ash from the ash pond could alter the characteristics of the ash pond discharge to the river. The second concerns proper disposal of the runoff and possibly leachate from the dry ash stack. The third is that dry ash stacking might change the potential for groundwater contamination at the KFP. This report addresses each of these issues. The effects on the ash pond and its discharge are described first. The report is intended to provide reference material to TVA staff in preparation of environmental review documents for new ash disposal areas at Kingston. Although the investigation was directed toward analysis of dry stacking, considerations for other disposal options are also discussed. This report was reviewed in draft form under the title Assessment of Kingston Fossil Plant Dry Ash Stacking on the Ash Pond and Groundwater Quality.'' 11 refs., 3 figs., 18 tabs.

  17. The Potential for Renewable Energy Development to Benefit Restoration of the Salton Sea. Analysis of Technical and Market Potential

    SciTech Connect (OSTI)

    Gagne, Douglas; Haase, Scott; Oakleaf, Brett; Hurlbut, David; Akar, Sertac; Wall, Anna; Turchi, Craig; Pienkos, Philip; Melius, Jennifer; Melaina, Marc

    2015-11-01

    This report summarizes the potential for renewable energy development in the Salton Sea region, as well as the potential for revenues from this development to contribute financially to Salton Sea restoration costs. It considers solar, geothermal, biofuels or nutraceutical production from algae pond cultivation, desalination using renewable energy, and mineral recovery from geothermal fluids.


  18. CX-009239: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Grazing Agreement Amendment to Legacy Management #8-12, Acid Pond Property Disposition Near the Spook, Wyoming, Disposal Site CX(s) Applied: B1.24 Date: 09/12/2012 Location(s): Wyoming Offices(s): Legacy Management

  19. CX-007509: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Record of Categorical Exclusion for Use of RW Surge Line to Big Hill Anhydrite Pond for Raw Water Intake Structure Recycle CX(s) Applied: B1.3 Date: 11/28/2011 Location(s): Texas Offices(s): Strategic Petroleum Reserve Field Office

  20. Biodetention: A best management practice for nonpoint source pollution

    SciTech Connect (OSTI)

    Murfee, G.; Scaief, J.; Whelan, M.

    1998-07-01

    Biodetention is an innovative nonpoint source (NPS) pollution control best management practice (BMP) developed as an alternative to sedimentation/filtration ponds. Biodetention is applicable as a runoff treatment system for concentrated point discharges from stormwater collection facilities. Treatment is facilitated by vegetative filter strips and stiff grass hedges.

  1. Woody biomass production in waste recycling systems

    SciTech Connect (OSTI)

    Rockwood, D.L.; Snyder, G.H.; Sprinkle, R.R.

    1994-12-31

    Combining woody biomass production with waste recycling offers many mutual advantages, including increased tree growth and nutrient and water reclamation. Three biomass/recycling studies collectively involving Eucalyptus amplifolia, E. camaldulensis, and E. grandis, rapidly growing species potentially tolerant of high water and nutrient levels, are (1) evaluating general potential for water/nutrient recycling systems to enhance woody biomass production and to recycle water and nutrients, (2) documenting Eucalyptus growth, water use, and nutrient uptake patterns, and (3) identifying Eucalyptus superior for water and nutrient uptake in central and southern Florida. In a 1992-93 study assessing the three Eucalyptus species planted on the outside berms of sewage effluent holding ponds, position on the berms (top to bottom) and genotypes influenced tree size. The potential of the trees to reduce effluent levels in the ponds was assessed. In a stormwater holding pond planted in 1993, these Eucalyptus genotypes varied significantly for tree size but not for survival. E. camaldulensis appears generally superior when flooded with industrial stormwater. Potential sizes of ponds needed for different stormwater applications were estimated. Prolonged flooding of 4- and 5-year-old E. camaldulensis with agricultural irrigation runoff has had no observable effects on tree growth or survival. Younger E. camaldulensis, E. amplifolia, and E. grandis were assessed for water use and nutrient uptake during a Summer 1994 flooding.

  2. EVMS Training Snippet Library: 6.2 Applied Predictive Analysis

    Broader source: Energy.gov [DOE]

    This EVMS Training Snippet, sponsored by the Office of Project Management (PM) provides examples of using PARS II analysis reports to examine current performance and use it to predict future...

  3. Telegdi's Birthday

    ScienceCinema (OSTI)

    None

    2011-04-25

    Célébration, organisée par ETH Zurich, à l'occasion du 65me anniversaire de Val Telegdi ou 3 intervenants prennent la parole

  4. Cyclocean LLC | Open Energy Information

    Open Energy Info (EERE)

    search Name: Cyclocean LLC Address: 3000 Par Drive Region: United States Sector: Marine and Hydrokinetic Phone Number: 561-317-1446 Website: www.cyclocean.com This company is...

  5. MIDC: Site Directory

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    and OTF) Spectral DataPlots Spectral Data Format Spectral Data: PAR Summation AOCS Metrologia Article (PDF) SRRL GPS Time GPS Real-Time Java Clock GPS Information Windows XP...

  6. Active Project Justification Statements

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    David Weitzman P1138-2007REV 3102014 DOE-STD-XXXX, DOE Environmental Laboratory Pro ciency Tes ng Program Administra on and Par cipa on AU-20 PJS Non Concurrence Resolu on ...

  7. GettingStartedGuide.PDF | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    GettingStartedGuide.PDF&0; GettingStartedGuide.PDF&0; PDF icon GettingStartedGuide.PDF&0; More Documents & Publications PARS II 104 Contractor Monthly Upload Home Energy Score...

  8. Earned Value (EV) Analysis and Project Assessment & Reporting...

    Office of Environmental Management (EM)

    staff to the Secretary of Energy will have easy access to the same data. EarnedValue-EV-AnalysisProjectAssessmentReportingSystem-PARS IIPresentationJanuary2013.pdf More...

  9. EVMS Training Snippet: 6.2 Applied Predictive Analysis

    Broader source: Energy.gov [DOE]

    This EVMS Training Snippet, sponsored by the Office of Project Management (PM) provides examples of using PARS II analysis reports to examine current performance and use it to predict future...

  10. C Example MUMPS

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    a MUMPS instance. Use MPICOMMWORLD * id.jobJOBINIT; id.par1; id.sym0;id.commfortranUSECOMMWORLD; dmumpsc(&id); * Define the problem on the host * if (myid 0) ...

  11. WAR DEPARTaMMeNT

    Office of Legacy Management (LM)

    10 tom as BX0683. p 5 Production of heels at Ravsre Coppsr & Brass Comsaay: ExLrwion ia axpested to continua at 30 tons par waskand, whioh ..-,: is squix&mt to 130 tons per...

  12. Advances in Chip Technology, Packaging Enable White LED Breakthroughs

    Broader source: Energy.gov [DOE]

    Significant advances in chip technology have enabled Cree, Inc.'s Santa Barbara Technology Center to demonstrate white LEDs with record efficacies as high as 74 lumens per watt - on par with...

  13. Lessons Learned | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Within 90 days of Critical Decision (CD-4) approval-- Lessons learned from project execution and facility start-up All PMLLs submitted to OAPM are filed in PARS II under their ...

  14. St Paul's cathedral

    ScienceCinema (OSTI)

    None

    2011-04-25

    Visite de la cathédrale Saint-Paul au centre de Londres. Le révérend Bill Atkins commente cette magnifique église baroque, dessinée par Sir Christopher Wren en 1673

  15. 2

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    3 grid of points (2) (1) (3) 2 2 2 2 2 FEAP FEAP FEAP FEAP FEAP FEAP FEAP FEAP FEAP Prometheus ParMetis METIS METIS METIS METIS METIS METIS METIS METIS Prometheus . . . . PETSc...

  16. News | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    and based on experience from CALiPER testing and GATEWAY demonstrations. November 7, 2013 DOE Publishes New CALiPER Report on Subjective Evaluation of LED PAR38 Lamps DOE...

  17. NCAR Multi-core 5 Workshop!

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    CPU Bound Likely parRally memory latency Bound (assuming not IO or communicaRon ... ongoing): * Refer to NERSC "Nested OpenMP" web page for achieving process and thread ...

  18. DOE Publishes CALiPER Report on Chromaticity Shift Modes of LED...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    The focus of the new report is to investigate causes of color shift and parametric failures within these lamps. In general, samples of the same PAR38 lamp model usually exhibited ...

  19. Organization | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    About Us » Organization Organization Organization Download Printable PDF PDF icon Organization Chart - Dated: 07/12/2015 Key Resources PMCDP EVMS PARS IIe FPD Resource Center PM Newsletter Forms and Templates Leadership Organization History Contact Us

  20. MHK ISDB/Sensors/Solar Radiation Sensor | Open Energy Information

    Open Energy Info (EERE)

    Light (PAR) with 3m cable Smart Sensor ... further results Also made by Onset Computer Corporation HOBO RX3000 Remote Monitoring SystemHOBO RX3000 Remote Monitoring...

  1. Multinational societies and syndicates

    ScienceCinema (OSTI)

    None

    2011-04-25

    Monsieur Charles Levinson, par la longue expérience qu'il a acquise au contact des sociétés multinationales et syndicats, nous en parle ce soir

  2. DuraLamp USA: Order (2010-CE-0912)

    Broader source: Energy.gov [DOE]

    DOE ordered DuraLamp USA, Inc. to pay a $2,500 civil penalty after finding DuraLamp USA had failed to certify that model PAR 30, an incandescent reflector lamp, complies with the applicable energy conservation standards.

  3. DOE Publishes CALiPER Report on Dimming, Flicker, and Power Quality...

    Broader source: Energy.gov (indexed) [DOE]

    Report 20.2 focuses on dimming, flicker, and power quality characteristics evaluated with a single dimmer. The dimming, flicker, and power quality behavior of the LED PAR38 lamps ...

  4. DOE Publishes CALiPER Report on the Photoelectric Performance...

    Broader source: Energy.gov (indexed) [DOE]

    on Retail Lamps DOE Publishes CALiPER Application Summary Report on LED MR16 Lamps DOE Publishes CALiPER Report on Dimming, Flicker, and Power Quality Characteristics of LED PAR3

  5. CALiPER Report 20.4: Lumen and Chromaticity Maintenance of LED...

    Energy Savers [EERE]

    ... Report 20.2: Dimming, Flicker, and Power Quality Characteristics of LED PAR38 Lamps (March 2014) 9 This report focused on the flicker and power quality performance of the Series 20 ...

  6. EVMS Training Snippet: 4.1 The Over Target Baseline (OTB) and...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    PDF icon Slides Only PDF icon Slides with Notes Key Resources PMCDP EVMS PARS IIe FPD ... 4.6 Baseline Control Methods EVMS Training Snippet: 4.9 High-level EVM Expectations

  7. EVMS Training Snippet: 4.4 Undistributed Budget (UB) | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    PDF icon Slides Only PDF icon Slides with Notes Key Resources PMCDP EVMS PARS IIe FPD ... EVMS Training Snippet: 4.6 Baseline Control Methods EVMS Training Snippet: 4.9 High-level ...

  8. EVMS Training Snippet: 4.3 Management Reserve Versus Contingency...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    PDF icon Slides Only PDF icon Slides with Notes Key Resources PMCDP EVMS PARS IIe FPD ... 4.4 Undistributed Budget (UB) EVMS Training Snippet: 4.9 High-level EVM Expectations

  9. EVMS Training Snippet: 4.7 FFP Subcontracting and Prime EVM ...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Slides with Notes Key Resources PMCDP EVMS PARS IIe FPD Resource Center PM Newsletter Forms and Templates More Documents & Publications EVMS Training Snippet: 4.9 High-level EVM ...

  10. CX-007691: Categorical Exclusion Determination | Department of...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Funding will support development of Compact Dynamic Phase Angle Regulators (CD-PAR), a compact, low-cost power flow controller integrated with custom-wound transformers to control ...

  11. LED Directional Lamps

    SciTech Connect (OSTI)

    2012-11-01

    Solid-state lighting program technology fact sheet that provides an overview of the current performance of LED PAR-, BR-, R-, and AR-shaped lamps, which were all investigated by CALiPER in 2012.

  12. Technical Sessions J. C. Doran Pacific; Northwest Laboratory

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    a site, we hoped to see a clear signature of the effElcts of surface inhomogeneities, test one or more par;metric schemes relating turbulent fluxes to vertical gr;dients of...

  13. Promising Technology: Parabolic Aluminized Reflector Light-Emitting Diodes

    Broader source: Energy.gov [DOE]

    Parabolic aluminized reflectors, or PARs, are directional lamps typically used in recessed lighting. In contrast to CFLs, LEDs offer additional advantages including no warm up time, improved dimming and control capabilities, and for some products much greater efficacy ratings.

  14. Postings | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    on Sky Factory February Feb. 24, 2015: SSL Is Stepping Up to the Plate in the Sports World Feb. 18, 2015: A Candid Look at LED PAR38 Lamps Feb. 10, 2015: LED Adoption by...

  15. Gregory Lecture

    ScienceCinema (OSTI)

    None

    2011-04-25

    Conférence donné par Benoît Mandelbrot, brillant mathématicien et professeur de mathématique à l'Université Yale

  16. CALiPER Report 20.1: Subjective Evaluation of Beam Quality, Shadow...

    Office of Scientific and Technical Information (OSTI)

    1: Subjective Evaluation of Beam Quality, Shadow Quality, and Color Quality for LED PAR38 Lamps Citation Details In-Document Search Title: CALiPER Report 20.1: Subjective...

  17. Parallel Power Grid Simulation Toolkit

    Energy Science and Technology Software Center (OSTI)

    2015-09-14

    ParGrid is a 'wrapper' that integrates a coupled Power Grid Simulation toolkit consisting of a library to manage the synchronization and communication of independent simulations. The included library code in ParGid, named FSKIT, is intended to support the coupling multiple continuous and discrete even parallel simulations. The code is designed using modern object oriented C++ methods utilizing C++11 and current Boost libraries to ensure compatibility with multiple operating systems and environments.

  18. Slide 1

    Energy Savers [EERE]

    PARS IIE CONTROLLED UNCLASSIFIED INFORMATION (CUI) TRAINING Two-Factor Authentication (TFA) Document Marking, Encryption, and Access OVERVIEW - TWO-FACTOR AUTHENTICATION (TFA)  No changes to URL (https://pars2e.doe.gov)  No changes to current username/password  Additional authentication step  Time-based Security Token delivered to registered email, or  Registered equipment (laptop/desktop) with unique IP  No other changes to timeout, password expiration, or account deactivation

  19. EVMS Training Snippet: 5.7 PARSII Analysis: OAPM Red Yellow Report |

    Energy Savers [EERE]

    Department of Energy 7 PARSII Analysis: OAPM Red Yellow Report EVMS Training Snippet: 5.7 PARSII Analysis: OAPM Red Yellow Report This EVMS Training Snippet, sponsored by the Office of Project Management (PM) is one in a series regarding PARS II Analysis reports. PARS II offers direct insight into EVM project data from the contractor's internal systems. The reports were developed with the users in mind, organized and presented in an easy to follow manner, with analysis results and key

  20. DNA-Binding Mechanism in Prokaryotic Partition Complex Formation

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    DNA-Binding Mechanism in Prokaryotic Partition Complex Formation Print The faithful inheritance of genetic information, essential for all organisms, requires accurate movement and positioning of replicated DNA to daughter cells during cell division. In cells without distinct nuclei (prokaryotes), this process, called partition or segregation, is mediated by par systems. The prototype system of prokaryotic partition is the Escherichia coli P1 plasmid par system, which consists of a centromere

  1. Localization and proliferation of lymphatic vessels in the tympanic membrane in normal state and regeneration

    SciTech Connect (OSTI)

    Miyashita, Takenori; Burford, James L.; Hong, Young-Kwon; Gevorgyan, Haykanush; Lam, Lisa; Mori, Nozomu; Peti-Peterdi, Janos

    2013-10-25

    Highlights: •We newly developed the whole-mount imaging method of the tympanic membrane. •Lymphatic vessel loops were localized around the malleus handle and annulus tympanicus. •In regeneration, abundant lymphatic vessels were observed in the pars tensa. •Site-specific lymphatic vessels may play an important role in the tympanic membrane. -- Abstract: We clarified the localization of lymphatic vessels in the tympanic membrane and proliferation of lymphatic vessels during regeneration after perforation of the tympanic membrane by using whole-mount imaging of the tympanic membrane of Prox1 GFP mice. In the pars tensa, lymphatic vessel loops surrounded the malleus handle and annulus tympanicus. Apart from these locations, lymphatic vessel loops were not observed in the pars tensa in the normal tympanic membrane. Lymphatic vessel loops surrounding the malleus handle were connected to the lymphatic vessel loops in the pars flaccida and around the tensor tympani muscle. Many lymphatic vessel loops were detected in the pars flaccida. After perforation of the tympanic membrane, abundant lymphatic regeneration was observed in the pars tensa, and these regenerated lymphatic vessels extended from the lymphatic vessels surrounding the malleus at day 7. These results suggest that site-specific lymphatic vessels play an important role in the tympanic membrane.

  2. Review: Weldon Spring Site Remedial Action Project Second Five Year Review. Revision 0. DOE/OR/21548-891 review dated August 2001. The results of the five year review indicate that the remedies are functioning as intended in the four operable units. The operable units are Quarry Bulk Waste, Chemical Plant, Quarry Residuals, and Groundwater. Review contents include remedial actions in quarry bulk wastes, chemical plant (vicinity properties, southeast drainage, frog pond drainage, busch lakes, and site remediation), quarry residuals, environmental monitoring (radon gas monitoring, gamma radiation monitoring, radioactive air particulate monitoring, airborne asbestos monitoring, surfact water protection, and groundwater monitoring), applicable or relevant and appriopriate requirements (ARAR) for chemical plant, quarry residuals, and interim groundwater operable units. Figures include location maps, plan layouts, and charts. Tables include contaminant cleanup standards, summary data for uranium, nitroaromatic compound, and analytical, summary results for asbestos air monitoring, annual averages for monitoring locations, averages for uranium concentrations, and summary of detection monitoring data.

    Office of Legacy Management (LM)

  3. Novel Americium Treatment Process for Surface Water and Dust Suppression Water

    SciTech Connect (OSTI)

    Tiepel, E.W.; Pigeon, P.; Nesta, S.; Anderson, J.

    2006-07-01

    The Rocky Flats Environmental Technology Site (RFETS), a former nuclear weapons production plant, has been remediated under CERCLA and decommissioned to become a National Wildlife Refuge. The site conducted this cleanup effort under the Rocky Flats Cleanup Agreement (RFCA) that established limits for the discharge of surface and process waters from the site. At the end of 2004, while a number of process buildings were undergoing decommissioning, routine monitoring of a discharge pond (Pond A-4) containing approximately 28 million gallons of water was discovered to have been contaminated with a trace amount of Americium-241 (Am-241). While the amount of Am-241 in the pond waters was very low (0.5 - 0.7 pCi/l), it was above the established Colorado stream standard of 0.15 pCi/l for release to off site drainage waters. The rapid successful treatment of these waters to the regulatory limit was important to the site for two reasons. The first was that the pond was approaching its hold-up limit. Without rapid treatment and release of the Pond A-4 water, typical spring run-off would require water management actions to other drainages onsite or a mass shuttling of water for disposal. The second reason was that this type of contaminated water had not been treated to the stringent stream standard at Rocky Flats before. Technical challenges in treatment could translate to impacts on water and secondary waste management, and ultimately, cost impacts. All of the technical challenges and specific site criteria led to the conclusion that a different approach to the treatment of this problem was necessary and a crash treatability program to identify applicable treatment techniques was undertaken. The goal of this program was to develop treatment options that could be implemented very quickly and would result in the generation of no high volume secondary waste that would be costly to dispose. A novel chemical treatment system was developed and implemented at the RFETS to treat Am-241 contaminated pond water, surface run-off and D and D dust suppression water during the later stages of the D and D effort at Rocky Flats. This novel chemical treatment system allowed for highly efficient, high-volume treatment of all contaminated waste waters to the very low stream standard of 0.15 pCi/1 with strict compliance to the RFCA discharge criteria for release to off-site surface waters. The rapid development and implementation of the treatment system avoided water management issues that would have had to be addressed if contaminated water had remained in Pond A-4 into the Spring of 2005. Implementation of this treatment system for the Pond A-4 waters and the D and D waters from Buildings 776 and 371 enabled the site to achieve cost-effective treatment that minimized secondary waste generation, avoiding the need for expensive off-site water disposal. Water treatment was conducted for a cost of less than $0.20/gal which included all development costs, capital costs and operational costs. This innovative and rapid response effort saved the RFETS cleanup program well in excess of $30 million for the potential cost of off-site transportation and treatment of radioactive liquid waste. (authors)

  4. Development of Direct-Use Projects: Preprint

    SciTech Connect (OSTI)

    Lund, J.

    2011-01-01

    A geothermal direct-use project utilizes a natural resource, a flow of geothermal fluid at elevated temperatures, which is capable of providing heat and/or cooling to buildings, greenhouses, aquaculture ponds, and industrial processes. Geothermal utilization requires matching the varied needs of the user and characteristics of the resource in order to development a successful project. Each application is unique; guidelines are provided for the logical steps required to implement a project. Recommended temperature and flows are suggested for spas and pools, space and district heating, greenhouse and aquaculture pond heating, and industrial applications. Guidelines are provided for selecting the necessary equipment for successfully implementing a direct-use project, including downhole pumps, piping, heat exchangers, and heat convectors. Additionally, the relationship between temperature, flow rate, and the use of heat exchangers to provide heat to a space with hot water or hot air is provided for a number of applications, with suggested 'rules of thumb'.

  5. Microsoft Word - Action Plan Appendix B as of 02-25-2014

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    B Listing of Treatment, Storage, and Disposal Groups/Units (sheet 1 of 19) B-1 Treatment, Storage, and Disposal Planned Action Group Number Group/Units Operable Unit (if applicable) Closure* Operating Permit D-1-1 100-D Ponds (120-D-1) 100-DR-1 X T-1-1 105-DR (122-DR-1) Sodium Fire Facility X D-1-2 1301-N/1325-N Liquid Waste Disposal Facilities 116-N-1 Crib 116-N-3 Crib 100-NR-1 X T-1-2 1324-N/1324-NA Liquid Waste Facilities 120-N-1 Pond 120-N-2 Neutralization Unit 100-NR-1 X T-1-3** 1706-KE

  6. Development of value-added products from alumina industry mineral wastes using low-temperature-setting phosphate ceramics

    SciTech Connect (OSTI)

    Wagh, A.S.; Jeong, Seung-Young; Singh, D.

    1996-01-01

    A room-temperature process for stabilizing mineral waste streams has been developed, based on acid-base reaction between MgO and H3PO4 or acid phosphate solution. The resulting waste form sets into a hard ceramic in a few hours. In this way, various alumina industry wastes, such as red mud and treated potliner waste, can be solidified into ceramics which can be used as structural materials in waste management and construction industry. Red mud ceramics made by this process were low-porosity materials ({approx}2 vol%) with a compression strength equal to portland cement concrete (4944 psi). Bonding mechanism appears to be result of reactions of boehmite, goethite, and bayerite with the acid solution, and also encapsulation of red mud particles in Mg phosphate matrix. Possible applications include liners for ponds and thickned tailings disposal, dikes for waste ponds, and grouts. Compatability problems arising at the interface of the liner and the waste are avoided.

  7. EA-1959: Eightmile Ranch Coho Acclimation Site; Okanogan County, Washington

    Broader source: Energy.gov [DOE]

    Bonneville Power Administration and USDA Forest Service, Okanogan-Wenatchee National Forest, are jointly preparing an EA to assess the potential environmental impacts of funding a proposal by the Confederated Tribes and Bands of the Yakama Nation to construct and operate a coho salmon acclimation pond at Eightmile Ranch, which is owned and operated by the Forest Service. BPA's Mid-Columbia Coho Restoration Program EIS (DOE/EIS-0425) addressed the overall coho restoration program, with 11 acclimation sites. Some of these sites proved infeasible, so the Yakama Nation is proposing a new site at Eightmile Ranch. Young coho would be held in the pond from March to May and then released into the Chewuch River approximately 10 miles above its confluence with the Methow River.

  8. Microsoft Word - Cover Page - Exhibit 13

    Energy Savers [EERE]

    3 Northern Pass Project Visual Simulations and Methodology Description Exhibit 13 Visual Simulations and Methodology Description As noted in the DOE application, visual simulations were developed to provide a sense of what the Project will look like from various locations. In addition to the simulations that are listed below and part of this Exhibit 13, additional simulations can be found on the Northern Pass website. Simulation sites: Diamond Pond Road Colebrook Stark Highway Stark Lancaster

  9. SAS Output

    U.S. Energy Information Administration (EIA) Indexed Site

    3. Quantity and Net Summer Capacity of Operable Cooling Systems, by Energy Source and Cooling System Type, 2004 - 2014 Once-Through Cooling Systems Recirculating Cooling Systems Cooling Ponds Dry Cooling Systems Hybrid Wet and Dry Cooling Systems Other Cooling System Types Energy Source Quantity Associated Net Summer Capacity (MW) Quantity Associated Net Summer Capacity (MW) Quantity Associated Net Summer Capacity (MW) Quantity Associated Net Summer Capacity (MW) Quantity Associated Net Summer

  10. UTSI/CFFF MHD Program Completion and Related Activity

    SciTech Connect (OSTI)

    1997-04-01

    Routine preventive maintenance of the DOE Coal Fired Flow Facility (CFFF) is being performed. Modernization programs, being funded under subcontract from Foster Wheeler Development by the DOE HIPPS Program, are being implemented on the coal processing system, the data acquisition and control system and control room. Environmental restoration actions continued with monitoring of groundwater wells and holding pond effluent. Actions are under way to dispose of spent seed/ash mixtures and excess coal remaining from the MHD POC program.

  11. Microalgae as a source of liquid fuels. Final technical report. [200 references

    SciTech Connect (OSTI)

    Benemann, J.R.; Goebel, R.P.; Weissman, J.C.; Augenstein, D.C.

    1982-05-15

    The economics of liquid-fuels production from microalgae was evaluated. A detailed review of published economic analyses of microalgae biomass production revealed wide variations in the published costs, which ranged from several dollars per pound for existing commercial health-food production in the Far East, to less than .05/lb costs projected for microalgae biomass for fuel conversion. As little design information or specific cost data has been published, a credible cost estimate required the conceptual engineering design and cost estimating of microalgae to liquid-fuels processes. Two systems were analyzed, shallow (2 to 3'') covered ponds and deeper (1 ft) open ponds. Only the latter was selected for an in-depth analysis due to the many technical shortcomings of the former approach. Based on the cost analysis of a very simple and low cost process, the most optimistic costs extrapolated were about $60/barrel. These were based on many optimistic assumptions. Additional, more detailed, engieering and cost analyses would be useful. However, the major emphasis in future work in this area should be on demonstrating the basic premises on which this design was based: high productivity and oil content of microalgae strains that can dominate in open ponds and which can be harvested by a simple bioflocculation process. Several specific basic research needs were identified: (1) Fundamentals of species selection and control in open pond systems. Effects of environmental variables on species dominance is of particular interest. (2) Mechanisms of algae bioflocculation. (3) Photosynthetic pathways and efficiency under conditions of high lipid production. (4) Effects of non-steady state operating conditions, particularly pH (CO/sub 2/ availability), on productivity. 18 figures, 47 tables.

  12. Hanford Facility Beryllium Fact Sheet Building Number/Name:

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Responsible Contractor: Contact: 2714W March 25, 1998 February 9, 2012 N/A Kristy Kimmerle, CIH PAST OPERATIONS Beryllium brought in facility: Potential Form of beryllium: SOLID (trace on coveralls) Period of beryllium operations (dates): Mid 1960s End: 1991 Location(s) in facility that contained beryllium materials: Laundering area and exterior settling pond. Description of beryllium activities: Potentially beryllium-contaminated laundry was laundered in the facility and wash water was

  13. Techno-Economic, Sustainability, and Market Analysis | Bioenergy | NREL

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Techno-Economic, Sustainability, and Market Analysis NREL conducts techno-economic analyses (TEAs) for algal biofuels, thermochemical conversion, and biochemical conversion. Photo of two algae raceway ponds that show large-scale algae biomass production in the form of two oval-shaped pools filled with dark green liquid and a paddle-wheel in each pool that is agitating the liquid as it flows around. Algal Biofuels Techno-Economic Analysis NREL's Algae Techno-Economic Analysis group employs

  14. Thomas Veselka | Argonne National Laboratory

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Thomas R. Cech, RNA, and Ribozymes Resources with Additional Information * Videos Thomas Cech Courtesy of Glenn Asakawa/ University of Colorado Thomas R. Cech conducted ground-breaking research that ‘established that RNA, like a protein, can act as a catalyst in living cells.'1 'Prior to Cech's research, most scientists believed that proteins were the only catalysts in living cells. In 1982, his research group showed that an RNA molecule from Tetrahymena, a single-celled pond organism, cut and

  15. Riparian and Upland Restoration at the U.S. Department of Energy Rocky Flats, Colorado, Site - 12360

    SciTech Connect (OSTI)

    Nelson, Jody K.

    2012-07-01

    Remedial investigation and cleanup at the Rocky Flats, Colorado, Site was completed in 2005. Uplands, riparian, and wetland habitat were disturbed during cleanup and closure activities and required extensive revegetation. Unavoidable disturbances to habitat of the Preble's meadow jumping mouse (a federally listed species) and wetlands required consultation with regulatory agencies and mitigation. Mitigation wetlands were constructed in two drainages, and a third developed naturally where a soil borrow area intercepted the groundwater table. During the 50-plus years of site operations, 12 ponds were constructed in three drainages to manage and retain runoff and sewage treatment plant discharges prior to release off site. A batch-release protocol has been used for the past several decades at the terminal ponds, which has affected the riparian communities downstream. To return the hydrologic regime to a more natural flow-through system similar to the pre-industrial-use conditions, seven interior dams (of 12) have been breached, and the remaining five dams are scheduled for breaching between 2011 and 2020. At the breached dams, the former open water areas have transformed to emergent wetlands, and the stream reaches have returned to a flow-through system. Riparian and wetland vegetation has established very well. The valves of the terminal ponds were opened in fall 2011 to begin flow-through operations and provide water to the downstream plant communities while allowing reestablishment of vegetation in the former pond bottoms prior to breaching. A number of challenges and issues were addressed during the revegetation effort. These included reaching an agreement on revegetation goals, addressing poor substrate quality and soil compaction problems, using soil amendments and topsoil, selecting seeds, determining the timing and location of revegetation projects relative to continuing closure activities, weed control, erosion control, revegetation project field oversight, and contractual limitations. A variety of ecological restoration techniques were conducted at the site to meet these challenges. These efforts have resulted in vegetation becoming well established in most locations. (author)

  16. 8 Questions for a Scientist: Molecular Biologist Dr. Amanda Barry |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy for a Scientist: Molecular Biologist Dr. Amanda Barry 8 Questions for a Scientist: Molecular Biologist Dr. Amanda Barry August 13, 2015 - 9:45am Addthis Molecular biologist Dr. Amanda Barry at Los Alamos National Laboratory's environmental photobioreactor matrix, which simulates microalgal biofuel pond conditions. <a href="/node/1143116">Algal biofuels have big potential</a> for America's clean energy future. | <a

  17. Effects of copper exposure on hatching success and early larval survival in marbled salamanders, Ambystoma opacum

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    COPPER EXPOSURE ON HATCHING SUCCESS AND EARLY LARVAL SURVIVAL IN MARBLED SALAMANDERS, AMBYSTOMA OPACUM DIANA L. SOTEROPOULOS, STACEY L. LANCE, R. WESLEY FLYNN, and DAVID E. SCOTT* Savannah River Ecology Laboratory, University of Georgia, Aiken, South Carolina, USA (Submitted 4 October 2013; Returned for Revision 24 November 2013; Accepted 27 March 2014) Abstract: The creation of wetlands, such as urban and industrial ponds, has increased in recent decades, and these wetlands often become

  18. Direct use of low temperature geothermal water by Aquafarms International, Inc. for freshwater aquaculture (prawns and associated species). An operations and maintenance manual

    SciTech Connect (OSTI)

    Broughton, R.; Price, M.; Price, V.; Grajcer, D.

    1984-04-01

    In connection with an ongoing commercial aquaculture project in the Coachella Valley, California; a twelve month prawn growout demonstration project was conducted. This project began in August, 1979 and involved the use of low temperature (85/sup 0/F) geothermal waters to raise freshwater prawns, Macrobrachium rosenbergii (deMan), in earthen ponds. The following publication is an operations and maintenance guide which may by useful for those interested in conducting similar enterprises.

  19. T.G. Hinton: Remediation of Radioactively Contaminated Ecosystems |

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Savannah River Ecology Laboratory Remediation of Radioactively Contaminated Ecosystems Thomas G. Hinton Savannah River Ecology Laboratory P O Drawer E, Aiken, SC 29802 (803) 725-7454 office (803) 725-3309 fax thinton(at)uga.edu Dr. Hinton has received numerous grants from the Department of Energy to develop a remediation technique that is less damaging to contaminated lakes, ponds and wetlands than the traditional method of complete removal of contaminated sediments and subsequent burial

  20. Borehole Completion and Conceptual Hydrogeologic Model for the IFRC Well Field, 300 Area, Hanford Site

    SciTech Connect (OSTI)

    Bjornstad, Bruce N.; Horner, Jacob A.; Vermeul, Vincent R.; Lanigan, David C.; Thorne, Paul D.

    2009-04-20

    A tight cluster of 35 new wells was installed over a former waste site, the South Process Pond (316-1 waste site), in the Hanford Site 300 Area in summer 2008. This report documents the details of the drilling, sampling, and well construction for the new array and presents a summary of the site hydrogeology based on the results of drilling and preliminary geophysical logging.

  1. 8,000 visitors tour Jefferson Lab: Electron accelerator shut down for

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Department of Energy for a Scientist: Molecular Biologist Dr. Amanda Barry 8 Questions for a Scientist: Molecular Biologist Dr. Amanda Barry August 13, 2015 - 9:45am Addthis Molecular biologist Dr. Amanda Barry at Los Alamos National Laboratory's environmental photobioreactor matrix, which simulates microalgal biofuel pond conditions. <a href="/node/1143116">Algal biofuels have big potential</a> for America's clean energy future. | <a

  2. Fermilab | Tritium at Fermilab | Kress Creek Results

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Kress Creek Results chart This chart (click chart for larger version) shows the levels of tritium in Kress Creek since January 2006. To date, Fermilab has not detected tritium in Kress Creek. The detection limit is one picocurie per milliliter (see footnote). Increased monitoring began on Kress Creek following detection of low levels of tritium in Indian Creek in November 2005. The levels of tritium measured in the Fermilab cooling ponds and in Indian Creek are well below federal water standards

  3. Characterization of uranium and plutonium in surface-waters and sediments collected at the Rocky Flats Facility

    SciTech Connect (OSTI)

    Efurd, D.W.; Rokop, D.J.; Aguilar, R.D.; Roensch, F.R.; Perrin, R.E.; Banar, J.C.

    1994-05-01

    This study was initiated to characterize actinides in environmental samples collected at the Rocky Flats Plant (RFP). Thermal Ionization Mass Spectrometry (TIMS) measurement techniques were used to measure the plutonium and uranium content of water and sediment samples collected from the ponds used to control surface-waters on-site at RFP. TIMS was also used to separate the uranium into anthropogenic and naturally occurring components. The results of these studies are presented.

  4. 2015 Annual Site Inspection and Monitoring Report for Uranium Mill Tailings Radiation Control Act Title II Disposal Sites

    Office of Legacy Management (LM)

    Bluewater, New Mexico Page 1-1 1.0 Bluewater, New Mexico, Disposal Site 1.1 Compliance Summary The Bluewater, New Mexico, Uranium Mill Tailings Radiation Control Act (UMTRCA) Title II Disposal Site was inspected on August 19 and 20, 2015. A significant pond was present on the top slope of the main tailings disposal cell cover in an area where shallow depressions are present; disposal cell performance is being evaluated to determine if additional monitoring or cover enhancement is necessary.

  5. Thermoelectric energy converter for generation of electricity from low-grade heat

    DOE Patents [OSTI]

    Jayadev, T.S.; Benson, D.K.

    1980-05-27

    A thermoelectric energy conversion device which includes a plurality of thermoelectric elements is described. A hot liquid is supplied to one side of each element and a cold liquid is supplied to the other side of each element. The thermoelectric generator may be utilized to produce power from low-grade heat sources such as ocean thermal gradients, solar ponds, and low-grade geothermal resources. (WHK)

  6. EA-1959: Draft Environmental Assessment | Department of Energy

    Energy Savers [EERE]

    9: Draft Environmental Assessment EA-1959: Draft Environmental Assessment Eightmile Ranch Coho Acclimation Site; Okanogan County, Washington Bonneville Power Administration and USDA Forest Service, Okanogan-Wenatchee National Forest, jointly issued a draft EA that assesses the potential environmental impacts of a proposal by the Confederated Tribes and Bands of the Yakama Nation to construct and operate a coho salmon acclimation pond at Eightmile Ranch, which is owned and operated by the Forest

  7. Aquaculture information package

    SciTech Connect (OSTI)

    Boyd, T.; Rafferty, K.

    1998-08-01

    This package of information is intended to provide background information to developers of geothermal aquaculture projects. The material is divided into eight sections and includes information on market and price information for typical species, aquaculture water quality issues, typical species culture information, pond heat loss calculations, an aquaculture glossary, regional and university aquaculture offices and state aquaculture permit requirements. A bibliography containing 68 references is also included.

  8. New Microbiome Center to combine UChicago, Marine Biological Laboratory and

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Argonne expertise | Argonne National Laboratory Filamentous cyanobacteria from a tidal pond at Little Sippewissett salt marsh, Falmouth, Mass. Microbial communities - bacteria, viruses and fungi - affect every ecosystem on earth, including human bodies, oceans, our homes and the land around us, and are the focus of a new Microbiome Center jointly headed by Argonne, the Marine Biological Laboratory and the University of Chicago. (Image: S. Emil Ruff, Marine Biological Laboratory) Filamentous

  9. April 2012 Groundwater and Surface Water Sampling at the Salmon, Mississippi, Site (Data Validation Package)

    SciTech Connect (OSTI)

    2012-10-12

    Sampling and analysis were conducted on April 16-19, 2012, as specified in the Sampling and Analysis Plan for U.S. Department of Energy Office Of Legacy Management Sites (LMS/PLN/S04351, continually updated). Duplicate samples were collected from locations SA1-1-H, HMH-5R, SA3-4-H, SA1-2-H, Pond W of GZ, and SA5-4-4. One trip blank was collected during this sampling event.

  10. Most Viewed Documents - Power Generation and Distribution | OSTI, US Dept

    Office of Scientific and Technical Information (OSTI)

    of Energy, Office of Scientific and Technical Information - Power Generation and Distribution Electric power high-voltage transmission lines: Design options, cost, and electric and magnetic field levels Stoffel, J.B.; Pentecost, E.D.; Roman, R.D.; et al. (1994) ASPEN Plus Simulation of CO2 Recovery Process Charles W. White III (2003) Systems and economic analysis of microalgae ponds for conversion of CO{sub 2} to biomass. Quarterly technical progress report, September 1993--December 1993

  11. NEPA Determination: LM-08-12 Amendment | Department of Energy

    Energy Savers [EERE]

    8-12 Amendment NEPA Determination: LM-08-12 Amendment Grazing Agreement Amendment, Acid Pond, Spook, Wyoming CX(s) Applied: B1.24 Date: 09/12/2012 Location(s): Spook, WY Offices(s): Legacy Management PDF icon LM-08-12 Amendment More Documents & Publications CX-009239: Categorical Exclusion Determination CX-008762: Categorical Exclusion Determination CX-009264: Categorical Exclusion Determination

  12. Venkat Subramanian | Bioenergy | NREL

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Venkat Subramanian Venkat Subramanian Research Scientist Venkat.Subramanian@nrel.gov | 303-384-7719 Research Interests Algal biofuels (hydrogen and biodiesel) Characterizing metabolic pathways leading to biofuel production in the green alga Chlamydomonas reinhardtii Genetic engineering of algae to improve their harvesting properties to reduce the cost of algal harvesting from open-pond bioreactors for commercial-scale biofuel/biodiesel production Screening new algal strains with improved lipid

  13. Microsoft Word - Appendix G.doc

    Office of Legacy Management (LM)

    09 are included in this appendix. Appendix G, Page 1 RFLMA Contact Record 2009-01 1 of 5 ROCKY FLATS SITE REGULATORY CONTACT RECORD Purpose: Phase II and III Upgrades to Solar Ponds Plume Treatment System Contact Record Approval Date: February 17, 2009 Site Contact(s) / Affiliation(s): Scott Surovchak / DOE; Linda Kaiser / Stoller; Rick DiSalvo / Stoller; John Boylan / Stoller Regulatory Contact(s) / Affiliation(s): Carl Spreng / CDPHE Discussion: As approved in Rocky Flats Legacy Management

  14. Microsoft Word - DUR 2007 CR-final.doc

    Office of Legacy Management (LM)

    Durango, Colorado Page 4-1 4.0 Durango, Colorado, Disposal Site 4.1 Compliance Summary The Durango, Colorado, Disposal Site, inspected on August 14, 2007, is in good condition. In June 2006, the criteria for permanent closure of the transient drainage water collection and treatment system were met; however, an increased uranium concentration reported downgradient needs to be evaluated. In 2007, a solar-powered water management system was installed to distribute retention pond water to drip lines

  15. Microsoft Word - S07121_CY2010 Annual Rpt

    Office of Legacy Management (LM)

    98 Data Evaluation During CY 2010, pre-discharge samples were collected during at Ponds A-4, B-5, and C-2 prior to discharge. All predischarge sample results indicated that water quality was acceptable for discharge. Subsequent POC sampling during discharge also indicated acceptable water quality for the discharged water. 3.1.3 Rocky Flats Hydrology The following section provides information for all automated surface-water monitoring and precipitation gage locations at the Site that operated

  16. Microsoft Word - S08568_CY2011 Annual Rpt

    Office of Legacy Management (LM)

    128 Data Evaluation During CY 2011, predischarge samples were collected during at Ponds A-4, B-5, and C-2 prior to opening the outlet valve to initiate discharge. All predischarge sample results indicated that water quality was acceptable for discharge. Subsequent POC sampling during discharge also indicated acceptable water quality for the discharged water. 3.1.3 Rocky Flats Hydrology The following section provides information for all automated surface-water monitoring and precipitation gage

  17. Albany, OR * Anchorage, AK * Morgantown, WV * Pittsburgh, PA * Sugar Land, TX

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    and multi-stage hydraulic fracturing, two processes that have been known for many years but have only recently become common practice. In addition, fugitive atmospheric emissions can result from a variety of other operational elements (e.g., volatiles that escape from the wellhead during the drilling and production operations, large stationary power generators, increased truck traffic, water separation tanks, holding ponds, etc.); these emissions can negatively impact air quality. The

  18. Albany, OR * Anchorage, AK * Morgantown, WV * Pittsburgh, PA * Sugar Land, TX

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    and multi-stage hydraulic fracturing, two processes that have been known for many years but have only recently become common practice. In addition, fugitive atmospheric emissions can result from a variety of other operational elements (e.g., volatiles that escape from the wellhead during the drilling and production operations, large stationary power generators, increased truck traffic, water separation tanks, holding ponds, etc.); these emissions can negatively impact air quality. The

  19. Connections: November 2013

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    November 2013 Community Connections: Your link to news and opportunities from Los Alamos National Laboratory Latest Issue:May 2016 all issues All Issues » submit IN THIS ISSUE Ribbon cutting marks chemistry laboratory upgrades at Northern New Mexico College Los Alamos National Security, LLC provides support Lab transitions employee giving campaigns This year's theme: "I Give Because..." Lab provides environmental support for county construction projects A face-lift for Ashley Pond New

  20. ARM - Events Article

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    14, 2012 [Events, Facility News] Outreach Extends to European Geosciences Union Bookmark and Share Attending their first EGU General Assembly, ARM Facility staff shared facility availability and resources with mostly European scientists, students, and teachers who stopped by the booth. Making its debut at the European Geosciences Union (EGU) General Assembly, the ARM Climate Research Facility "crossed the pond" to attend Europe's leading forum for Earth and space sciences during the