National Library of Energy BETA

Sample records for 685-g par pond

  1. Par Pond water balance

    SciTech Connect (OSTI)

    Hiergesell, R.A.; Dixon, K.L.

    1996-06-01

    A water budget for the Par Pond hydrologic system was established in order to estimate the rate of groundwater influx to Par Pond. This estimate will be used in modeling exercises to predict Par Pond reservoir elevation and spillway discharge in the scenario where Savannah River water is no longer pumped and discharged into Par Pond. The principal of conservation of mass was used to develop the water budget, where water inflow was set equal to water outflow. Components of the water budget were identified, and the flux associated with each was determined. The water budget was considered balanced when inflow and outflow summed to zero. The results of this study suggest that Par Pond gains water from the groundwater system in the upper reaches of the reservoir, but looses water to the groundwater system near the dam. The rate of flux of groundwater from the water table aquifer into Par Pond was determined to be 13 cfs. The rate of flux from Par Pond to the water table aquifer near the dam was determined to be 7 cfs.

  2. Par Pond vegetation status 1996

    SciTech Connect (OSTI)

    Mackey, H.E. Jr.; Riley, R.S.

    1996-12-01

    The water level of Par Pond was lowered approximately 20 feet in mid-1991 in order to protect downstream residents from possible dam failure suggested by subsidence on the downstream slope of the dam and to repair the dam. This lowering exposed both emergent and nonemergent macrophyte beds to drying conditions resulting in extensive losses. A survey of the newly emergent, shoreline aquatic plant communities of Par Pond began in June 1995, three months after the refilling of Par Pond to approximately 200 feet above mean sea level. These surveys continued in July, September, and late October, 1995, and into the early spring and late summer of 1996. Communities similar to the pre-drawdown, Par Pond aquatic plant communities continue to become re-established. Emergent beds of maidencane, lotus, waterlily, watershield, and Pontederia are extensive and well developed. Measures of percent cover, width of beds, and estimates of area of coverage with satellite data indicate regrowth within two years of from 40 to 60% of levels prior to the draw down. Cattail occurrence continued to increase during the summer of 1996, especially in the former warm arm of Par Pond, but large beds common to Par Pond prior to the draw down still have not formed. Lotus has invaded and occupies many of the areas formerly dominated by cattail beds. To track the continued development of macrophytes in Par Pond, future surveys through the summer and early fall of 1997, along with the evaluation of satellite data to map the extent of the macrophyte beds of Par Pond, are planned.

  3. Par Pond Fish, Water, and Sediment Chemistry

    SciTech Connect (OSTI)

    Paller, M.H.; Wike, L.D.

    1996-06-01

    The objectives of this report are to describe the Par Pond fish community and the impact of the drawdown and refill on the community, describe contaminant levels in Par Pond fish, sediments, and water and indicate how contaminant concentrations and distributions were affected by the drawdown and refill, and predict possible effects of future water level fluctuations in Par Pond.

  4. Par Pond vegetation status Summer 1995 -- Summary

    SciTech Connect (OSTI)

    Mackey, H.E. Jr.; Riley, R.S.

    1996-01-01

    The water level of Par Pond was lowered approximately 20 feet in mid-1991 in order to protect downstream residents from possible dam failure suggested by subsidence on the downstream slope of the dam and to repair the dam. This lowering exposed both emergent and nonemergent macrophyte beds to drying conditions resulting in extensive losses. A survey of the newly emergent, shoreline aquatic plant communities of Par Pond began in June 1995, three months after the refilling of Par Pond to approximately 200 feet above mean sea level. These surveys continued in July, September, and late October, 1995. Communities similar to the pre-drawdown, Par Pond aquatic plant communities are becoming re-established. Emergent beds of maidencane, lotus, waterlily, and watershield are extensive and well developed. Cattail occurrence continued to increase during the summer, but large beds common to Par Pond prior to the drawdown have not formed. Estimates from SPOT HRV, remote sensing satellite data indicated that as much as 120 hectares of emergent wetlands vegetation may have been present along the Par Pond shoreline by early October, 1995. To track the continued development of macrophytes in Par Pond, future surveys throughout 1996 and 1997, along with the continued evaluation of satellite data to map the areal extent of the macrophyte beds of Par Pond, are planned.

  5. Par Pond vegetation status Summer 1995 -- June survey descriptive summary

    SciTech Connect (OSTI)

    Mackey, H.E. Jr.; Riley, R.S.

    1995-06-01

    The water level of Par Pond was lowered approximately 20 feet in mid-1991 in order to protect downstream residents from possible dam failure suggested by subsidence on the downstream slope of the dam and to repair the dam. This lowering exposed both emergent and nonemergent macrophyte beds to drying conditions resulting in extensive losses. A survey of the shoreline aquatic plant communities in June 1995, three months after the refilling of Par Pond to approximately 200 feet above mean sea level, indicated that much of the original plant communities and the intermediate shoreline communities present on the exposed sediments have been lost. The extensive old-field and emergent marsh communities that were present on the exposed shoreline during the drawdown have been flooded and much of the pre-drawdown Par Pond aquatic plant communities have not had sufficient time for re-establishment. The shoreline does, however, have extensive beds of maidencane which extend from the shoreline margin to areas as deep as 2 and perhaps 3 meters. Scattered individual plants of lotus and watershield are common and may indicate likely directions of future wetland development in Par Pond. In addition, within isolated coves, which apparently received ground water seepage and/or stream surface flows during the period of the Par Pond draw down, extensive beds of waterlilies and spike rush are common. Invasion of willow and red maple occurred along the lake shoreline as well. Although not absent from this survey, evidence of the extensive redevelopment of the large cattail and eel grass beds was not observed in this first survey of Par Pond. Future surveys during the growing seasons of 1995, 1996, and 1997 along with the evaluation of satellite date to map the areal extent of the macrophyte beds of Par Pond are planned.

  6. Par Pond vegetation status Summer 1995 -- September survey descriptive summary

    SciTech Connect (OSTI)

    Mackey, H.E. Jr.; Riley, R.S.

    1995-09-01

    The water level of Par Pond was lowered approximately 20 feet in mid-1991 in order to protect downstream residents from possible dam failure suggested by subsidence on the downstream slope of the dam and to repair the dam. This lowering exposed both emergent and nonemergent macrophyte beds to drying conditions resulting in extensive losses. A survey of the emergent shoreline aquatic plant communities began in June 1995, three months after the refilling of Par Pond to approximately 200 feet above mean sea level and continued with this mid-September survey. Communities similar to the pre-drawdown Par Pond aquatic plant communities are becoming re-established; especially, beds of maidencane, lotus, waterlily, and watershield are now extensive and well established. Cattail occurrence continues to increase, but large beds common to Par Pond prior to the drawdown have not formed. Future surveys during the late growing seasons of 1995, and throughout 1996 and 1997, along with the evaluation of satellite data to map the areal extent of the macrophyte beds of Par Pond, are planned.

  7. Par Pond vegetation status Summer 1995 -- October survey descriptive summary

    SciTech Connect (OSTI)

    Mackey, H.E. Jr.; Riley, R.S.

    1995-11-01

    The water level of Par Pond was lowered approximately 20 feet in mid-1991 in order to protect downstream residents from possible dam failure suggested by subsidence on the downstream slope of the dam and to repair the dam. This lowering exposed both emergent and nonemergent macrophyte beds to drying conditions resulting in extensive losses. A survey of the emergent shoreline aquatic plant communities began in June 1995, three months after the refilling of Par Pond to approximately 200 feet above mean sea level and continued with this late October survey. Communities similar to the pre-drawdown Par Pond aquatic plant communities are becoming re-established; especially, beds of maiden cane, lotus, waterlily, and watershield are now extensive and well established. Cattail occurrence continues to increase, but large beds common to Par Pond prior to the drawdown have not formed. Future surveys throughout 1996 and 1997, along with the continued evaluation of satellite data to map the areal extent of the macrophyte beds of Par Pond, are planned.

  8. Par Pond phytoplankton in association with refilling of the pond: Final Report for sampling from February 1995 -- September 1996

    SciTech Connect (OSTI)

    Wilde, E.W.; Johnson, M.A.; Cody, W.C.

    1996-12-31

    This report describes the results of phytoplankton analyses from Par Pond samples collected between February 1995 and September 1996. The principal objective of the study was to determine the effect of refilling of Par Pond following repair of the dam on the phytoplankton community. Algal blooms are often responsible for fish kills and other detrimental effects in ponds and lakes, and it was postulated that decaying vegetation from formerly exposed sediments might trigger algal blooms that could result in fish kills in Par Pond following the refill. Sporadic algal blooms involving blue-green algae were detected, especially during the summer of 1996. However, the data derived from the study demonstrates that overall, the refilling effort caused no significant negative impact to the pond attributable to phytoplankton dynamics.

  9. Results of submerged sediment core sampling and analysis on Par Pond, Pond C, and L Lake: July 1995

    SciTech Connect (OSTI)

    Koch, J.W. II; Martin, F.D.; Friday, G.P.

    1996-06-01

    Sediment cores from shallow and deep water locations in Par Pond, Pond C, and L Lake were collected and analyzed in 1995 for radioactive and nonradioactive constituents. This core analysis was conducted to develop a defensible characterization of contaminants found in the sediments of Par Pond, Pond C, and L Lake. Mercury was the only nonradiological constituent with a nonestimated quantity that was detected above the U.S Environmental Protection Agency Region IV potential contaminants of concern screening criteria. It was detected at a depth of 0.3--0.6 meters (1.0--2.0 feet) at one location in L Lake. Cesium-137, promethium-146, plutonium-238, and zirconium-95 had significantly higher concentrations in Par Pond sediments than in sediments from the reference sites. Cobalt-60, cesium-137, plutonium-238, plutonium-239/240, and strontium-90 had significantly higher concentrations in L-Lake sediments than sediments from the reference sites.

  10. CERCLA interim action at the Par Pond unit: A case study

    SciTech Connect (OSTI)

    Hickey, H.M.; Matthews, S.S.; Neal, L.W.; Weiss, W.R.

    1993-11-01

    The Par Pond unit designated under CERCLA consists of sediments within a Savannah River Site (SRS) cooling water reservoir. The sediments are contaminated with radionuclides and nonradioactive constituents from nuclear production reactor operations. The mercury in Par Pond is believed to have originated from the Savannah River. Because of Par Pond Dam safety Issues, the water level of the reservoir was drawn down, exposing more than 1300 acres of contaminated sediments and triggering the need for CERCLA interim remedial action. This paper presents the interim action approach taken with Par Pond as a case study. The approach considered the complexity of the Par Pond ecosystem, the large size of Par Pond, the volume of contaminated sediments, and the institutional controls existing at SRS. The Environmental Protection Agency (EPA) considers units with large volumes of low-concentration wastes, as is the case with Par Pond, to be {open_quotes}special sites.{close_quotes} Accordingly, EPA guidance establishes that the range of alternatives developed focus primarily on containment options and other remedial approaches that mitigate potential risks associated with the {open_quotes}special site.{close_quotes} The remedial alternatives, according to EPA, are not to be prohibitively expensive or difficult to implement. This case study also is representative of the types of issues that will need to be addressed within the Department of Energy (DOE) complex as nuclear facilities are transitioned to inactive status and corrective/remedial actions are warranted.

  11. Quality control summary report for the RFI/RI assessment of the submerged sediment core samples taken at Par Pond, Pond C, and L-Lake

    SciTech Connect (OSTI)

    Koch, J. II

    1996-12-01

    This report presents a summary of the sediment characterization performed under the direction of the Westinghouse Savannah River Company`s (WSRC) Environmental Protection Department/Environmental Monitoring Section (EPD/EMS) in support of Par Pond, Pond C, and L- Lake. This characterization will be a screening study and will enable the Environmental Sciences Section (ESS) to develop a defensible contaminants of concern list for more extensive characterization of the Par Pond, Pond C, and L-Lake.

  12. Potential Ecological Effects of Contaminants in the Exposed Par Pond Sediments

    SciTech Connect (OSTI)

    Paller, M.H.; Wike, L.D.

    1996-08-01

    Sediment and small mammal samples were collected from the exposed sediments of Par Pond in early 1995, shortly before the reservoir was refilled after a 4-year drawdown. Sampling was confined to elevations between 58 and 61 meters (190 and 200 feet) above mean sea level, which includes the sediments likely to be exposed if the Par Pond water level is permitted to fluctuate naturally. Both soil and small mammal samples were analyzed for a number of radionuclides and metals. Some of the soil samples were also analyzed for organic contaminants. The objective of the study was to determine if contaminant levels in the Par Pond sediments were high enough to cause deleterious ecological effects.

  13. K-Area and Par Pond Sewage Sludge Application Sites groundwater monitoring reports, second quarter 1992

    SciTech Connect (OSTI)

    Not Available

    1992-10-01

    During second quarter 1992, the three wells at the K-Area Sewage Sludge Application Site (KSS wells) and the three wells at the Par Pond Sewage Sludge Application Site (PSS wells) were sampled for analyses required each quarter or annually by South Carolina Department of Health and Environmental Control Construction Permit 13, 173. This report includes the results of those analyses. None of the analyzed constituents exceeded the Primary Drinking Water Standard or the Savannah River Site Flag 2 criteria at either the K-Area Sewage Sludge Application Site or the Par Pond Sewage Sludge Application Site.

  14. K-Area and Par Pond Sewage Sludge Application Sites groundwater monitoring report, Third quarter 1992

    SciTech Connect (OSTI)

    Thompson, C.Y.

    1993-01-01

    During third quarter 1992, the three wells at the K-Area Sewage Sludge Application Site (KSS wells) and the three wells at the Par Pond Sewage Sludge Application Site (PSS wells) were sampled for analyses required each quarter or annually by South Carolina Department of Health and Environmental Control Construction Permit 13,173 and for base-neutral/acid semivolatile constituents. None of the analytical results exceeded standards.

  15. K-Area and Par Pond Sewage Sludge Application Sites Groundwater Monitoring Report

    SciTech Connect (OSTI)

    Thompson, C.Y.

    1993-04-01

    During fourth quarter 1992, samples from the three monitoring wells at the K-Area site (KSS series) and the three monitoring wells at the Par Pond site (PSS series) were analyzed for constituents required by South Carolina Department of Health and Environmental Control Construction Permit 13, 173 and for other constituents as part of the Savannah River Site (SRS) Groundwater Monitoring Program. This report describes monitoring results that exceeded the final Primary Drinking Water Standards (PDWS) or the SRS flagging criteria. During fourth quarter 1992, no constituents analyzed exceeded the PDWS or the SRS Flag 2 criteria at the K-Area and Par Pond Sewage Sludge Application Sites. In the KSS well series, the field measurement for alkalinity ranged as high as 26 mg/L in well KSS 1D. Alkalinity measurements were zero in the PSS wells. Historical and current water-level elevations at the K-Area and Par Pond Sewage Sludge Application Site indicate that the groundwater flow directions are south to southwest (SRS grid coordinates).

  16. A comparison of four aerial radiological surveys of Par Pond and the surrounding area, Savannah River Site, Aiken, South Carolina. Dates of surveys: 1989--1992

    SciTech Connect (OSTI)

    Feimster, E.L.

    1993-09-01

    A series of gamma radiation surveys was conducted over Par Pond at the Savannah River Site (SRS) in August 1993, October 1991, and August 1992 as part of an effort to monitor the radiological changes around Par Pond as its water level was lowered. The results of an April 1989 survey, which was about one-half the area of those surveys listed above, were used as baseline data for the comparison. Gamma energy spectrum analysis revealed that the only man-made gamma ray emitter detected during the four surveys in the Par Pond area was cesium-137. The comparisons revealed that: (1) significant change in the radiological environment occurred along the Par Pond shoreline as the water levels were lowered, (2) the activity in Lower Three Runs Creek varied slightly as the level/flow rate changed during the pumping process, (3) minor changes occurred in areas adjacent to the Par Pond, and (4) little or no change occurred between surveys in the spatial distribution or kind of sources detected. All changes were directly related to the moisture variations (Par Pond water lowering, rainfall, waterway flow rates) between the survey periods. The distribution, kind, and activity of sources detected beyond the pond bed were consistent between surveys. 60 figs., 14 tabs.

  17. Environmental assessment for the natural fluctuation of water level in Par Pond and reduced water flow in Steel Creek below L-Lake at the Savannah River Site

    SciTech Connect (OSTI)

    1995-08-01

    The Savannah River Operations Office Strategic Plan directs Savannah River Site (SRS) to find ways to reduce operating costs, and to determine what site infrastructure must be maintained and what infrastructure is surplus. Because of the mission change, L-Lake, Par Pond, and the river water system are no longer needed to support current missions and therefore provide an opportunity for operating cost reduction. If SRS determines that L-Lake, Par Pond, and the river water system are no longer needed to support future missions and are considered surplus, appropriate NEPA documentation will be prepared. The purpose of the proposed action in this Environmental Assessment is to begin an examination of the need for the Site`s river water system by (1) developing data needed to evaluate the potential environmental impacts of further reducing or eliminating the flow demands from the Site`s river water system and; (2) evaluating the potential of reducing operating costs by allowing the water level in Par Pond to fluctuate naturally through reduced pumping. This action also includes reducing the current flow rates from L-Lake to Steel Creek to natural stream flows while maintaining full pool. The recently approved Par Pond CERCLA Interim Action Proposed Plan (IAPP) committed to evaluate in a NEPA document the environmental consequences of this proposed action. This document evaluated the remediation of human health and ecological risks associated with the three year drawdown of Par Pond. Should any of the parameters sampled in the reservoir and streams (e.g., water quality, biota, etc.) exceed established threshold levels during the implementation of the proposed action, water would again be pumped into the reservoir to minimize any impacts by bringing the water level back to an appropriate level about 58.2 m (195 ft).

  18. H-Area, K-Area, and Par Pond Sewage Sludge Application Sites groundwater monitoring report. Third quarter 1994

    SciTech Connect (OSTI)

    1995-01-01

    Groundwater samples from the three wells at the H-Area Sewage Sludge Application Site (HSS wells) are analyzed quarterly for constituents as required by South Carolina Department of Health and Environmental Control (SCDHEC) Construction Permit 12,076. Samples from the three wells at the K-Area Sewage Sludge Application Site (KSS wells) and the three wells at the quired by SCDHEC Construction Permit 13,173. All samples are also analyzed as requested for other constituents as part of the Savannah River Site (SRS) Groundwater Monitoring Program. Annual analyses for other constituents, primarily metals, also are required by the permits. No constituents exceeded the SCDHEC final Primary Drinking Water Standard in any well from the H-Area, K-Area, and Par Pond Sewage Sludge Application Sites. Aluminum and iron were above Flag 2 criteria in one or more wells in the three sites during third quarter 1994. These constituents were not analyzed during the previous quarter. Third quarter results are similar to results for first quarter 1994.

  19. PAR Pond N Roads

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Vegetation Community D Sandhill Scrub oakPine ' 580 Compartment 56 290 o 290 Soils Soi I Sa-i es and Pha:;e o LaB sc Figure 26-1. Plant COl1ll1lllllities and soils associated ...

  20. Surface Sediments in Precooler Ponds 2, 4, and 5: March 2000

    SciTech Connect (OSTI)

    Dunn, D.L.

    2001-01-29

    Pond 2, Pond 4, and Pond 5 are inactive reactor cooling impoundments built in 1961 on the R-Reactor Effluent System in the east-central portion of the Department of Energy's Savannah River Site in Aiken, South Carolina. These precooler ponds are part of the Par Pond cooling water system and are considered part of the Par Pond operable unit. The intent was not to characterize the ponds, but to identify the maximum levels of contamination that could be exposed if the ponds are drained to remove the danger of dam failure.

  1. Measurements of radionuclides in Pond C with an underwater HPGe detector

    SciTech Connect (OSTI)

    Winn, W.G.

    1995-08-01

    This study on Pond C is part of a broader effort to appraise Savannah River Site (SRS) waterways impacted by the Par Pond Dam remediation program that commenced 1991. In addition, the results were sought to provide a more complete appraisal of the status of historical radioactive releases that remain in the Lower Three Runs system. Gamma emitting radionuclide concentrations in Pond C sediment were measured with an underwater HPGe detector. The predominant radionuclide was Cs-137 and the only other radionuclide detected was Co-60, which was only 1% as intense as the Cs-137. At the time of the measurements (November 1992), the total Pond C inventory of {sup 137}Cs was 4.5 {plus_minus} 0.8 Ci of which 0.30 {plus_minus} 0.09 Ci was exposed during a 6-ft drawdown for Par Pond Dam repairs. The Pond C inventory of Cs-137 is only 10% of that of Par Pond, primarily because of the much larger area of Par Pond. However, Pond C has a larger average sediment concentration of 8.1 {mu}Ci/m{sup 2} compared to 4.5 {mu}Ci/m{sup 2} for Par Pond, which is consistent with Pond C being closer to the origins of the earlier SRS reactor releases. The maximum Cs-137 concentration observed for Pond C was 55 {mu}Ci/m{sup 2}, which is about 10% higher than the maximum observed for Par Pond.

  2. PARS II

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... September 9, 2010 (V1.1) PARS II 103 Project Updating and Reporting Page 49 4. Click to begin entering funding values. 5. Click + sign to expand detail for OPC, TEC, and UND, if ...

  3. CX-010121: Categorical Exclusion Determination

    Office of Energy Efficiency and Renewable Energy (EERE)

    685-G Par Pond and 686-G L-Lake Sluice Gate Conduit Cleanouts/Inspections CX(s) Applied: B1.3 Date: 03/21/2013 Location(s): South Carolina Offices(s): Savannah River Operations Office

  4. CX-011819: Categorical Exclusion Determination

    Office of Energy Efficiency and Renewable Energy (EERE)

    685-G PAR Pond and 686-G L-Lake Sluice Gate Conduit Cleanouts/Inspections CX(s) Applied: B1.3 Date: 01/27/2014 Location(s): South Carolina Offices(s): Savannah River Operations Office

  5. PARS II TRAINING

    Broader source: Energy.gov [DOE]

    PARS II 102 Monthly Updating and Reporting Training Workbook (PARS II Release 1.1), September 13, 2010.

  6. Easton Pond Business Center | Open Energy Information

    Open Energy Info (EERE)

    Easton Pond Business Center Jump to: navigation, search Name Easton Pond Business Center Facility Easton Pond Business Center Sector Wind energy Facility Type Small Scale Wind...

  7. PARS II TRAINING

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    13, 2010 (V1.1) PARS II 102 Monthly Updating and Reporting i Project Assessment and Reporting System PARS II 102 Monthly Updating and Reporting Training Workbook (PARS II Release ...

  8. PARS II Course Descriptions

    Broader source: Energy.gov [DOE]

    Sign up for PARS 102 or PARS 103, depending on your project assessment role and function.  PARS 104 will be offered to site contractors as part of Dekker's Contractor deployment training.

  9. Utilization of saturated solar ponds

    SciTech Connect (OSTI)

    Loeb, S.

    1981-08-18

    A saturated non-convective solar pond is employed as an unmixing device in conjunction with reverse electrodialysis or pressureretarded osmosis for power generation.

  10. Control of a solar pond

    SciTech Connect (OSTI)

    Sherman, B.S.; Imberger, J. )

    1991-01-01

    Solar ponds hold the promise of providing an alternative to diesel generation of electricity at remote locations in Australia where fuel costs are high. However, to reliably generate electricity with a solar pond requires high temperatures to be maintained throughout the year; this goal had eluded the Alice Springs solar pond prior to 1989 because of double-diffusive convection within the gradient zone. This paper presents control strategies designed to provide successful high temperature operation of a solar pond year-round. The strategies, which consist mainly of manipulating upper surface layer salinity and extracting heat from the storage zone are well suited to automation. They were tested at the Alice Springs solar pond during the summer of 1989 and maintained temperatures in excess of 85{degree}C for several months without any gradient stability problems.

  11. Ultimate Heat Sink Cooling Pond and Spray Pond Analysis Models.

    Energy Science and Technology Software Center (OSTI)

    1999-05-02

    Version 00 Three programs model performance of an ultimate heat sink cooling pond. National Weather Service data is read and analyzed to predict periods of lowest cooling performance and highest evaporative loss. The data is compared to local site data for significant differences. Then the maximum pond temperature is predicted. Five programs model performance of an ultimate heat sink spray pond. The cooling performance, evaporative water loss, and drift water loss as a function ofmore » windspeed are estimated for a spray field. These estimates are used in conjunction with National Weather Service data to predict periods of lowest cooling performance and highest evaporative loss. This data is compared to local site data for significant differences. Then the maximum pond temperature is predicted.« less

  12. PARS II Training Materials | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    attachments, and running standard, pre-built reports. PARS 102 Presentation PARS 102 Workbook PARS 103 - Updating Projects and Reporting Introduction to PARS II, finding and...

  13. 216-B-3 expansion ponds closure plan

    SciTech Connect (OSTI)

    Not Available

    1994-10-01

    This document describes the activities for clean closure under the Resource Conservation and Recovery Act of 1976 (RCRA) of the 216-B-3 Expansion Ponds. The 216-B-3 Expansion Ponds are operated by the US Department of Energy, Richland Operations Office (DOE-RL) and co-operated by Westinghouse Hanford Company (Westinghouse Hanford). The 216-B-3 Expansion Ponds consists of a series of three earthen, unlined, interconnected ponds that receive waste water from various 200 East Area operating facilities. The 3A, 3B, and 3C ponds are referred to as Expansion Ponds because they expanded the capability of the B Pond System. Waste water (primarily cooling water, steam condensate, and sanitary water) from various 200 East Area facilities is discharged to the Bypass pipe (Project X-009). Water discharged to the Bypass pipe flows directly into the 216-B-3C Pond. The ponds were operated in a cascade mode, where the Main Pond overflowed into the 3A Pond and the 3A Pond overflowed into the 3C Pond. The 3B Pond has not received waste water since May 1985; however, when in operation, the 3B Pond received overflow from the 3A Pond. In the past, waste water discharges to the Expansion Ponds had the potential to have contained mixed waste (radioactive waste and dangerous waste). The radioactive portion of mixed waste has been interpreted by the US Department of Energy (DOE) to be regulated under the Atomic Energy Act of 1954; the dangerous waste portion of mixed waste is regulated under RCRA.

  14. Across the Pond Newsletters | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Services Communication & Engagement International Programs Across the Pond ... Communication & Engagement Intergovernmental Programs EMAB EM SSAB Tribal Programs ...

  15. PARS II Training Materials

    Broader source: Energy.gov [DOE]

    PARS II presentation hand-outs and step-by-step "how to" exercises for each course are available for download. Users who are attending Web classes should download these documents prior to attending...

  16. Project 3: Pond Crash Forensics

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Project 3: Pond Crash Forensics 5/20/2013 Algae Peer Review Todd W. Lane Ph.D. Sandia National Laboratories This presentation does not contain any proprietary, confidential, or otherwise restricted information Sandia National Laboratories is a multi-program laboratory operated by Sandia Corporation, a wholly owned subsidiary of Lockheed Martin Corporation, for the U.S. Department of Energy's National Nuclear Security Administration under contract DE-AC04-94AL85000. Goal Statement * The goal of

  17. PARS IIe | Department of Energy

    Office of Environmental Management (EM)

    same time. New Users Request User Account Request Lessons Learned Access Email EITS Help Desk Existing Users Login to PARS IIe Password Self-Service (PSS) Email PARS IIe Support

  18. Operation of a commercial solar gel pond

    SciTech Connect (OSTI)

    Wilkens, E. )

    1991-01-01

    The solar gel pond is an innovative concept which overcomes many of the shortcomings of the conventional salt-gradient solar pond. In this paper, the design, construction and start-up details of a commercial scale pond (400 m{sup 2}), built for a publishing company in Albuquerque, New Mexico will be presented. A pond with trapezoidal cross section was designed so that shadowing could be minimized and also the ratio of surface area to the volume of the storage zone could be maximized. The publishing company required a minimum of 1 GJ/day (1MBTU/day). Generally it has been noted that in ponds with large volume a lesser percentage of retained energy is lost as edge losses. Based on the above considerations a pond size of 400 m{sup 2} and 5 m deep with a gel thickness of 60 cm and a mass flow rate (for the heat extraction loop) of 1 {times} 10{sup {minus}4} to 1 {times} 10{sup {minus}3} kg/m{sup 2} {center dot} sec was determined to be the optimum size for the publishing company's needs. Two to seven percent salt water was used mainly to keep the gel bags floating on the surface. Tedlar bags were used to contain the gel. During the first year of operation, while the pond was still heating up, the pond obtained a temperature of 60C and the gel showed no signs of degradation.

  19. PARS II Training Workbook (Course 103)

    Broader source: Energy.gov [DOE]

    PARS II 103 Updating Projects and Reporting Training Workbook (PARS II Release 1.1), September, 2010.

  20. SPACES Sandia Offices Par

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    a public face for Sandia National Laboratories, providing access to the Labs, and building linkages with the community. It will be a place where Sandians and their industrial, academic, and government par tners can interact easily and freely, outside the gates. Located in the Sandia Science & Technology Park (SS&TP), the new multi-tenant facility will be dedicated to increasing Sandia's collaboration and commercialization activities. C3 will offer spaces for lease along with programs and

  1. Solar ponds in hydrometallurgy and salt production

    SciTech Connect (OSTI)

    Lesino, G.; Saravia, L. )

    1991-01-01

    The possibilities of using solar ponds in the mining industry are explored. Their advantages are identified from an economic point of view and the main technical points for proper operation are discussed. A short account is given of the hydrometallurgical and salt production processes of interest from the point of view of solar ponds. Solar ponds can provide a working environment for many mineral processing systems, not only as a source of energy, but also as a large basin maintained at nearly constant temperature where different operations can be performed. Examples are described for applications in the production of sodium sulfate, boric acid, copper, potassium chloride, and sodium borate.

  2. PARS II 104 Contractor Monthly Upload | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    104 Contractor Monthly Upload PARS II 104 Contractor Monthly Upload PDF icon PARS II 104 Contractor Monthly Upload More Documents & Publications PARS II TRAINING PARS II Training ...

  3. Excavations in Hanford ponds, cribs, or ditches

    SciTech Connect (OSTI)

    Ryan, G.W., Westinghouse Hanford

    1996-09-20

    This document supports the development and presentation of the following accident scenario in the TWRS Final Safety Analysis Report: Unplanned Excavation/Drilling in Pond/Ditch/Crib. The calculations needed to quantify the risk associated with this accident scenario are included within.

  4. Engineered design of SSC cooling ponds

    SciTech Connect (OSTI)

    Bear, J.B.

    1993-05-01

    The cooling requirements of the SSC are significant and adequate cooling water systems to meet these requirements are critical to the project`s successful operation. The use of adequately designed cooling ponds will provide reliable cooling for operation while also meeting environmental goals of the project to maintain streamflow and flood peaks to preconstruction levels as well as other streamflow and water quality requirements of the Texas Water Commission and the Environmental Protection Agency.

  5. PARS IIe CUI Training Slides | Department of Energy

    Energy Savers [EERE]

    PARS IIe DMS. This enhancement DOES NOT require users to obtain new username or password. ... Existing PARS IIe Users Login to PARS IIe Password Self-Service (PSS) Email PARS IIe ...

  6. Across the Pond Newsletter Issue 3 | Department of Energy

    Office of Environmental Management (EM)

    Across the Pond Newsletter Issue 3 A Quarterly Update on Joint UK NDAUS DOE Activities ... Area Update: Continued Progress Being Made NDA Visits Thermal Treatment Technology Vendors ...

  7. Parallel Climate Analysis Toolkit (ParCAT)

    SciTech Connect (OSTI)

    Smith, Brian Edward

    2013-06-30

    The parallel analysis toolkit (ParCAT) provides parallel statistical processing of large climate model simulation datasets. ParCAT provides parallel point-wise average calculations, frequency distributions, sum/differences of two datasets, and difference-of-average and average-of-difference for two datasets for arbitrary subsets of simulation time. ParCAT is a command-line utility that can be easily integrated in scripts or embedded in other application. ParCAT supports CMIP5 post-processed datasets as well as non-CMIP5 post-processed datasets. ParCAT reads and writes standard netCDF files.

  8. Are surface coal mine sediment ponds working

    SciTech Connect (OSTI)

    Poe, M.L.; Betson, R.P.

    1985-12-09

    Flowrates and storm generated water quality data were collected at sedimentation ponds on four surface mines in the states of Pennsylvania, Maryland, and West Virginia. The water quality data were analyzed for suspended solids and settleable solids content, and particle size distribution. The results were compared to the effluent limitations guidelines for total suspended solids as promulgated under the Clean Water Act for Coal Mining Point Source Category and adopted under the Surface Mine Control and Reclamation Act of 1977 and the resulting state regulatory programs. 3 references, 1 figure, 2 tables.

  9. 2101-M Pond hydrogeologic characterization report

    SciTech Connect (OSTI)

    Chamness, M.A.; Luttrell, S.P.; Bates, D.J.; Martin, W.J.

    1990-09-01

    This report documents information collected by the Pacific Northwest Laboratory {sup (a)} at the request of Westinghouse Hanford Company. Presented in this report is the interpretation of the hydrogeologic environment at the 2101-M Pond, located in the 200-East Area of the Hanford Site. This information and its accompanying interpretation were derived from sampling and testing activities associated with the installation of four ground-water monitoring wells, in addition to data gathered from several previously existing wells. The new monitoring wells were installed as part of a groundwater monitoring program initiated in 1988. The four new monitoring wells were installed around the 2101-M Pond between May 23 and August 27, 1988. Geologic sampling, aquifer testing, and initial ground-water sampling were performed during the installation of these wells. Laboratory analyses of the sediment samples for particle size, calcium carbonate content, and selected natural and contaminant constituents were performed. A full year of quarterly ground-water sampling and the first statistical analysis of background and downgradient data have also been performed. 112 refs., 49 figs., 18 tabs.

  10. PARS IIe Training | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    IIe Training PARS IIe Training PARS IIe has adopted alternative training strategy that increases training efficiency while reducing time commitment required from our users. We no longer provide day-long training sessions and instead offer technology-driven on-demand training videos as well as short, targeted live webinar. PARS IIe Controlled Unclassified Information (CUI) Release New CUI capabilities were succesfully released into production environment and PM-30 held several webinars to

  11. LED PAR38 Lamps | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Research & Development » Technology Application R&D » CALiPER Testing » Application Reports » LED PAR38 Lamps LED PAR38 Lamps The following CALiPER reports provide a detailed investigation of LED PAR38 lamp performance, covering basic performance characteristics as well as subjective evaluation of beam, shadow, and color quality. Further analysis is provided on flicker, dimming, and power quality characteristics; stress testing; lumen and chromaticity maintenance; and chromaticity

  12. Fuel Pond Sludge - Lessons Learned from Initial De-sludging of Sellafield's Pile Fuel Storage Pond - 12066

    SciTech Connect (OSTI)

    Carlisle, Derek; Adamson, Kate

    2012-07-01

    The Pile Fuel Storage Pond (PFSP) at Sellafield was built and commissioned between the late 1940's and early 1950's as a storage and cooling facility for irradiated fuel and isotopes from the two Windscale Pile reactors. The pond was linked via submerged water ducts to each reactor, where fuel and isotopes were discharged into skips for transfer along the duct to the pond. In the pond the fuel was cooled then de-canned underwater prior to export for reprocessing. The plant operated successfully until it was taken out of operation in 1962 when the First Magnox Fuel Storage Pond took over fuel storage and de-canning operations on the site. The pond was then used for storage of miscellaneous Intermediate Level Waste (ILW) and fuel from the UK's Nuclear Programme for which no defined disposal route was available. By the mid 1970's the import of waste ceased and the plant, with its inventory, was placed into a passive care and maintenance regime. By the mid 1990s, driven by the age of the facility and concern over the potential challenge to dispose of the various wastes and fuels being stored, the plant operator initiated a programme of work to remediate the facility. This programme is split into a number of key phases targeted at sustained reduction in the hazard associated with the pond, these include: - Pond Preparation: Before any remediation work could start the condition of the pond had to be transformed from a passive store to a plant capable of complex retrieval operations. This work included plant and equipment upgrades, removal of redundant structures and the provision of a effluent treatment plant for removing particulate and dissolved activity from the pond water. - Canned Fuel Retrieval: Removal of canned fuel, including oxide and carbide fuels, is the highest priority within the programme. Handling and export equipment required to remove the canned fuel from the pond has been provided and treatment routes developed utilising existing site facilities to

  13. Algal bioflocculation and energy conservation in microalgal sewage ponds

    SciTech Connect (OSTI)

    Eisenberg, D.M.; Koopman, B.; Benemann, J.R.; Oswald, W.J.

    1981-01-01

    Controlled bioflocculation for harvesting of microalgae produced during municipal wastewater treatment in high-rate ponds was investigated. Nonflocculant algal cultures were produced in high-rate ponds operated at very high dilution rates or with poor mixing. Bioflocculation of such cultures was achieved by isolating them in secondary ponds, but isolation periods of up to 29 days were required. In-pond sedimentation of flocculant algal cultures produced by the isolation technique resulted in algal removals consistently exceeding 80%. When high-rate ponds were operated with improved mixing and at moderate-to-high dilution rates, flocculant algal cultures were developed. The settleability of flocculant algal cultures produced in this manner averaged 76 to 80% when measured in 24-h-detention Imhoff cones and 71% when measured in 48-h-detention settling ponds. It is estimated that, under suitable climate conditions, a high-rate pond system employing bioflocculation-sedimentation for algal removal would require less than one-half the direct energy input of an equivalently sized activated sludge or trickling filter plant. This requirement could be provided entirely through complete utilization of biogas produced from anaerobic digestion of primary (sewage) sludge.

  14. Solar pond research at the Los Alamos National Laboratory

    SciTech Connect (OSTI)

    Jones, G.F.; Meyer, K.A.; Hedstrom, J.C.; Grimmer, D.P.

    1984-01-01

    A description of solar pond research at Los Alamos National Laboratory is presented. The main issues in the theory of solar ponds are discussed. Among these are the interfacial-boundary-layer model, models for interface motion and pond performance, heat extraction, and ground heat loss. The core of the research effort at Los Alamos was the development of a one-dimensional computer program to accurately predict dynamic performance of a solar pond. The computer model and the experiments that were designed and performed to validate it are described. The experiments include two laboratory tanks wherein temperature, salinity, and flow visualization data were obtained and a 232 m/sup 2/ outdoor solar pond. Results from preliminary validation show good agreement between the pond's predicted dynamic behavior and that which actually occurred in the experiments. More validation using data from full-sized solar ponds is needed. A new correlation for the ratio of interfacial salt-flux to heat-flux is proposed which agrees well with our data. Recommendations for future research are given.

  15. Across the Pond Newsletter Issue 4 | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    4 Across the Pond Newsletter Issue 4 A Quarterly Update on Joint UK NDA/US DOE Activities and Initiatives Issue 4: Summer 2010. In this issue: DOE-NDA discuss Spent Fuel Shipments WIPP Program visit to NDA Topic Area Update: Continued Progress Being Made DOE-NDA collaborations associated with the DOE EM-32 Groundwater and Soil Remediation Program DOE Fellows Program Across the Pond Newsletter Issue 4 (923.32 KB) More Documents & Publications Deep Vadose Zone Across the Pond Newsletter Issue

  16. Across the Pond Newsletter Issue 7 | Department of Energy

    Energy Savers [EERE]

    Across the Pond Newsletter Issue 7 A Quarterly Update on Joint UK NDAUS DOE Activities and Initiatives Issue 7: Spring 2012. In this issue: DOE and UK NDA Renew Information ...

  17. Seawater as salt and water source for solar ponds

    SciTech Connect (OSTI)

    Folchitto, S. )

    1991-01-01

    This paper presents a method for preliminary design of a 1 km{sup 2} solar pond that will be supplied with salt and water from the sea. The evaporating basins, needed to concentrate the seawater are also included in the project. Starting from the experience that Agip Petroli gained in running the 25,000 m{sup 2} Solar Pond, built inside a salt-work in Margherita di Savoia, in southern Italy, two projects were worked out: the first one of 25,000 m{sup 2} and the second one of 1 km{sup 2} of surface. Making comparison between harvested energy cost of the solar pond, and the energy cost of alternative and traditional energy sources, the coastal Solar Pond of 1 km{sup 2} that utilizes seawater as salt and water source, is competitive.

  18. Across the Pond Newsletter Issue 9 | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Across the Pond Newsletter Issue 9 Across the Pond Newsletter Issue 9 A Quarterly Update on Joint UK NDA/US DOE Activities and Initiatives Issue 9: Winter 2014. In this issue: Plutonium Management Information Exchange Workshop held in Sellafield EM Delegation Tours UK Cleanup Program's Sellafield Site Savannah River and NDA Sellafield Host Exchange Visits for "Benchmarking" Discussions DOE / NDA Bilateral Agreement Highlighted at NDA Supply Chain Event Joint U.S. / UK Initiative

  19. Modeling a ponded infiltration experiment at Yucca Mountain, NV

    SciTech Connect (OSTI)

    Hudson, D.B.; Guertal, W.R. [Foothill Engineering, Inc., Mercury, NV (United States); Flint, A.L. [Geological Survey, Mercury, NV (United States)

    1994-12-31

    Yucca Mountain, Nevada is being evaluated as a potential site for a geologic repository for high level radioactive waste. As part of the site characterization activities at Yucca Mountain, a field-scale ponded infiltration experiment was done to help characterize the hydraulic and infiltration properties of a layered dessert alluvium deposit. Calcium carbonate accumulation and cementation, heterogeneous layered profiles, high evapotranspiration, low precipitation, and rocky soil make the surface difficult to characterize.The effects of the strong morphological horizonation on the infiltration processes, the suitability of measured hydraulic properties, and the usefulness of ponded infiltration experiments in site characterization work were of interest. One-dimensional and two-dimensional radial flow numerical models were used to help interpret the results of the ponding experiment. The objective of this study was to evaluate the results of a ponded infiltration experiment done around borehole UE25 UZN {number_sign}85 (N85) at Yucca Mountain, NV. The effects of morphological horizons on the infiltration processes, lateral flow, and measured soil hydaulic properties were studied. The evaluation was done by numerically modeling the results of a field ponded infiltration experiment. A comparison the experimental results and the modeled results was used to qualitatively indicate the degree to which infiltration processes and the hydaulic properties are understood. Results of the field characterization, soil characterization, borehole geophysics, and the ponding experiment are presented in a companion paper.

  20. 2101-M pond closure plan. Volume 1, Revision 2

    SciTech Connect (OSTI)

    Izatt, R. D.; Lerch, R. E.

    1993-06-01

    This document describes activities for the closure of a surface impoundment (2101-M Pond) at the Hanford Site. The 2101-H Pond was initially constructed in 1953 to serve as a drainage collection area for the 2101-H Building. (Until the Basalt Waste Isolation Project (BWIP) Laboratory was constructed in the 2101-M Building in 1979--1981, the only source contributing discharge to the pond was condensate water from the 2101-H Building heating, ventilation, and air conditioning (HVAC) system. The drains for the BWIP Laboratory rooms were plumbed into a 4-in., cast-iron, low-pressure drain pipe that carries waste water from the HVAC system to the pond. During the active life of the BWIP Laboratory, solutions of dissolved barium in groundwater samples were discharged to the 2101-M Pond via the laboratory drains. As a result of the discharges, a Part A permit application was initially submitted to the Washington State Department of Ecology (Ecology) in August 1986 which designates the 2101-M Pond as a surface impoundment.

  1. 2014 DOE Project Management Workshop Presentations: PARS II Enhancemen...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    2014 DOE Project Management Workshop Presentations: PARS II Enhancements - Igor Pedan, MA-63 2014 DOE Project Management Workshop Presentations: PARS II Enhancements - Igor Pedan, ...

  2. PARS II Course Registration | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    Click the link below to access the MS XL PARS II Course Registration Form. Select the Open option. Select the Save As option to save a copy of the registration form to your...

  3. Toxicity of stormwater treatment pond sediments to Hyalella azteca (Amphipoda)

    SciTech Connect (OSTI)

    Karouna-Renier, N.K.; Sparling, D.W.

    1997-04-01

    Stormwater runoff from highways and commercial, industrial, and residential areas contains a wide spectrum of pollutants including heavy metals, petroleum hydrocarbons, pesticides, herbicides, sediment, and nutrients. Recent efforts to reduce the impacts of urbanization on natural wetlands and other receiving waters have included the construction of stormwater treatment ponds and wetlands. These systems provide flood control and improve water quality through settling, adsorption, and precipitation of pollutants removing up to 95% of metals, nutrients and sediment before discharged from the site. The design of stormwater ponds to provide habitat for aquatic wildlife has prompted concern over the potential exposure of aquatic organisms to these contaminants. Aquatic sediments concentrate a wide array of organic and inorganic pollutants. Although water quality criteria may not be exceeded, organisms living in or near the sediments may be adversely affected. The availability of chemicals in sediments depends strongly on the prevailing chemistry. Physical conditions of the sediment and water quality characteristics including pH, redox potential and hardness, also influence contaminant availability. Studies have shown that heavy metals and nutrients carried by runoff concentrate in the sediment of stormwater ponds. Although several investigations have assessed the toxicity of sediments in streams receiving urban runoff, there have been few studies of the toxicity of stormwater treatment pond sediments to aquatic organisms. This study was part of a large-scale assessment of the contaminant hazards of stormwater treatment ponds. The objective of this study was to evaluate the toxicity of sediments and water from stormwater ponds over a 10-d period to juvenile Hyalella azteca. Bioassay results were related to concentrations of acid volatile sulfides and metals of the tested sediments. 17 refs., 4 tabs.

  4. Gradient zone boundary control in salt gradient solar ponds

    DOE Patents [OSTI]

    Hull, John R.

    1984-01-01

    A method and apparatus for suppressing zone boundary migration in a salt gradient solar pond includes extending perforated membranes across the pond at the boundaries, between the convective and non-convective zones, the perforations being small enough in size to prevent individual turbulence disturbances from penetrating the hole, but being large enough to allow easy molecular diffusion of salt thereby preventing the formation of convective zones in the gradient layer. The total area of the perforations is a sizable fraction of the membrane area to allow sufficient salt diffusion while preventing turbulent entrainment into the gradient zone.

  5. Surface and subsurface soils at the Pond B dam: July 1998

    SciTech Connect (OSTI)

    Halverson, N.V.

    1999-12-03

    Pond B, 685-13G, is an inactive reactor cooling impoundment built in 1961 on the Savannah River Site (SRS). Between 1961 and 1964, Pond B received R-Reactor cooling water discharges that were contaminated with {sup 137}Cs, {sup 90}Sr and plutonium. Though the pond has not been used since 1964, radionuclides from the contaminated cooling water remain in the water and in the surface sediments of the pond. The current proposal to fix and repair the Pond B dam structure includes installing a new drain system and monitoring equipment. The dam will be reinforced with additional previous material on the downstream face of the dam. The objectives of this report are to describe the sampling methodology used during the July 1998 sampling event at the downstream face of the Pond B dam and in Pond B, present the results of the sampling event, and compare, where possible, these results to related risk-based standards.

  6. Groundwater monitoring plan for the Hanford Site 216-B-3 pond RCRA facility

    SciTech Connect (OSTI)

    Barnett, D.B.; Chou, C.J.

    1998-06-01

    The 216-B-3 pond system was a series of ponds for disposal of liquid effluent from past Hanford production facilities. In operation since 1945, the B Pond system has been a RCRA facility since 1986, with Resource Conservation and Recovery Act (RCRA) interim-status groundwater monitoring in place since 1988. In 1994, discharges were diverted from the main pond, where the greatest potential for contamination was thought to reside, to the 3C expansion pond. In 1997, all discharges to the pond system were discontinued. In 1990, the B Pond system was elevated from detection groundwater monitoring to an assessment-level status because total organic halogens and total organic carbon were found to exceed critical means in two wells. Subsequent groundwater quality assessment failed to find any specific hazardous waste contaminant that could have accounted for the exceedances, which were largely isolated in occurrence. Thus, it was recommended that the facility be returned to detection-level monitoring.

  7. Par Pastoril e Agr cola S A | Open Energy Information

    Open Energy Info (EERE)

    Par Pastoril e Agr cola S A Jump to: navigation, search Name: Par Pastoril e Agr-cola SA Place: Catanduva, Sao Paulo, Brazil Product: Agrobusiness company which produces...

  8. Project Assessment and Reporting System (PARS II) Memo

    Broader source: Energy.gov [DOE]

    Project Assessment and Reporting System (PARS II) Memo from the deputy secretary of Energy, dated May 17, 2010.

  9. 2014 DOE Project Management Workshop Presentations: PARS II Enhancements -

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Igor Pedan, MA-63 | Department of Energy 2014 DOE Project Management Workshop Presentations: PARS II Enhancements - Igor Pedan, MA-63 2014 DOE Project Management Workshop Presentations: PARS II Enhancements - Igor Pedan, MA-63 2014 DOE Project Management Workshop presentation by Igor Pedan. Presentation (1.32 MB) Key Resources PMCDP EVMS PARS IIe FPD Resource Center PM Newsletter Forms and Templates More Documents & Publications 2014 DOE Project Management Workshop Presentations: PARS II

  10. Salinity gradient solar pond technology applied to potash solution mining

    SciTech Connect (OSTI)

    Martell, J.A.; Aimone-Martin, C.T.

    2000-06-12

    A solution mining facility at the Eddy Potash Mine, Eddy County, New Mexico has been proposed that will utilize salinity gradient solar pond (SGSP) technology to supply industrial process thermal energy. The process will include underground dissolution of potassium chloride (KCl) from pillars and other reserves remaining after completion of primary room and pillar mining using recirculating solutions heated in the SGSP. Production of KCl will involve cold crystallization followed by a cooling pond stage, with the spent brine being recirculated in a closed loop back to the SGSP for reheating. This research uses SGSP as a renewable, clean energy source to optimize the entire mining process, minimize environmental wastes, provide a safe, more economical extraction process and reduce the need for conventional processing by crushing, grinding and flotation. The applications of SGSP technology will not only save energy in the extraction and beneficiation processes, but also will produce excess energy available for power generation, desalination, and auxiliary structure heating.

  11. Across the Pond Newsletter Issue 2 | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    2 Across the Pond Newsletter Issue 2 A Quarterly Update on Joint UK NDA/US DOE Activities and Initiatives Issue 2: December 2009. In this issue: DOE - NDA relationship recognized at International Environmental Cleanup Conference NDA - DOE Standing Committee Meeting commends progress Topic Area Update: Significant Progress Being Made Information Exchange is one of "DOE's best business practices" Glass Chemistry - A Flagship of Progress Under the Statement of Intent US Nuclear Waste

  12. Across the Pond Newsletter Issue 5 | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    5 Across the Pond Newsletter Issue 5 A Quarterly Update on Joint UK NDA/US DOE Activities and Initiatives Issue 5: Winter 2010. In this issue: Introduction 7th Standing Committee Meeting between USDOE - UKNDA held in Sellafield. Topic Area Update Group From Sellafield Visits Idaho To Exchange Information On Hot Isostatic Pressing Glass Chemistry Collaboration Update International Partnership Workshop on DOE Used Nuclear Fuel & High Level Waste NWTRB Discusses Technical Lessons Gained From

  13. Turbidity study of solar ponds utilizing seawater as salt source

    SciTech Connect (OSTI)

    Li, Nan; Sun, Wence; Shi, Yufeng; Yin, Fang; Zhang, Caihong

    2010-02-15

    A series of experiments were conducted to study the turbidity reduction in solar ponds utilizing seawater as salt source. The experiment on the turbidity reduction efficiency with chemicals indicates that alum (KAl(SO{sub 4}){sub 2}.12H{sub 2}O) has a better turbidity control property because of its strongly flocculating and also well depressing the growing of algae and bacteria in the seawater. In comparison with bittern and seawater, our experiment shows that the residual brine after desalination can keep limpidity for a long time even without any chemical in it. Experiments were also conducted on the diffusion of turbidity and salinity, which show that the turbidity did not diffuse upwards in the solution. In the experiment on subsidence of soil in the bittern and saline with the same salinity, it was found that soil subsided quite quickly in the pure saline water, but very slowly in the bittern. In this paper we also proposed an economical method to protect the solar pond from the damage of rain. Finally, thermal performance of a solar pond was simulated in the conditions of different turbidities using a thermal diffusion model. (author)

  14. The Western Pond Turtle; Habitat and History, 1993-1994 Final Report.

    SciTech Connect (OSTI)

    Holland, Dan C.

    1994-08-01

    The western pond turtle is known from many areas of Oregon. The majority of sightings and other records occur in the major drainages of the Klamath, Rogue, Umpqua, Willamette and Columbia River systems. A brief overview is presented of the evolution of the Willamette-Puget Sound hydrographic basin. A synopsis is also presented of the natural history of the western pond turtle, as well as, the status of this turtle in the Willamette drainage basin. The reproductive ecology and molecular genetics of the western pond turtle are discussed. Aquatic movements and overwintering of the western pond turtle are evaluated. The effect of introduced turtle species on the status of the western pond turtle was investigated in a central California Pond. Experiments were performed to determine if this turtle could be translocated as a mitigation strategy.

  15. Temperature, thermal efficiency, and gradient performance from two seawater-SZ solar ponds

    SciTech Connect (OSTI)

    Collado, F.; Lowrey, P. )

    1991-01-01

    This paper presents 10 months of experience with two seawater-SZ (Storage Zone) solar ponds operated as a source of warm seawater which could have been used in an adjacent mariculture facility. Observations and extensive temperature, gradient and efficiency data are presented. This work demonstrated operation of and heat extraction from seawater-SZ solar ponds over a much longer interval than in previous work. It confirmed that seawater-SZ solar ponds can consistently give useful temperature elevations. A few phenomena not characteristic of conventional solar ponds were identified and are discussed.

  16. Description of work for 216-U-Pond cone penetrometer demonstration

    SciTech Connect (OSTI)

    Kelty, G.G.

    1993-08-01

    This description of work details the Proposed field activities associated with Cone Penetrometer (CPT) work at the 216-U-10 Pond (U-10 Pond) in the 200 West Area and will serve as a field guide for those performing the work. The U-10 Pond was constructed in 1944 to receive low-level liquid effluent from the various chemical reprocessing facilities within the 200 West Area. The U-10 Pond covered 30 acres and received approximately 4.3 {times} 10{sup 10} gal of contaminated liquid. Sampling conducted in 1980 indicated that the most significant radionuclides were {sup 90}Sr, {sup 137}Cs, plutonium, and uranium (DOE-RL 1993). The pond was deactivated and stabilized in 1985 with clean fill dirt. The thickness of the stabilization cover is variable across the former pond and ranges between 2 ft near the pond margins and delta area to 8 feet in the deepest section of the pond. The purpose of this work is to establish the extent of contamination beneath the U-10 pond.

  17. On the hydrodynamics of salt-gradient solar ponds

    SciTech Connect (OSTI)

    Zangrando, F. )

    1991-01-01

    The objective of this paper is to discuss those hydrodynamical issues that affect the performance of the solar pond as an energy collector and storage system, e.g., mass and energy balance; formation, stability, and maintenance of the gradient layer; energy extraction from the bottom mixed layer; stability of stratified fluids to shearing flows; interface dynamics; and wall effects. Many of these topics are not fully understood and the discussion focuses on the present state of knowledge, some of the engineering correlations available at this time, and the research that is still required to resolve the relevant issues.

  18. Across the Pond Newsletter Issue 8 | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    8 Across the Pond Newsletter Issue 8 A Quarterly Update on Joint UK NDA/US DOE Activities and Initiatives Issue 8: Winter 2013. In this issue: UK Expertise Sought to Help Address Hanford Challenges US DOE - Developed Decon Gel Finds Application at Sellafield UK Office of Nuclear Regulation visits DOE HQ and DOE Hanford Head of US Cleanup Program visits Sellafield and Dounreay Successful US/UK Contracting Summit Hosted by UK NDA West Valley and Hanford host NDA and Dounreay Site Restoration Ltd.

  19. ELECTROKINETIC DENSIFICATION OF COAL FINES IN WASTE PONDS

    SciTech Connect (OSTI)

    E. James Davis

    1999-12-18

    The objective of this research was to demonstrate that electrokinetics can be used to remove colloidal coal and mineral particles from coal-washing ponds and lakes without the addition of chemical additives such as salts and polymeric flocculants. The specific objectives were: Design and develop a scaleable electrophoresis apparatus to clarify suspensions of colloidal coal and clay particles; Demonstrate the separation process using polluted waste water from the coal-washing facilities at the coal-fired power plants in Centralia, WA; Develop a mathematical model of the process to predict the rate of clarification and the suspension electrical properties needed for scale up.

  20. PARS II Enhancements - Igor Pedan, MA-63 | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Enhancements - Igor Pedan, MA-63 PARS II Enhancements - Igor Pedan, MA-63 2014 DOE Project Management Workshop PDF icon 28PedanPARSII Enhancements.pdf More Documents & ...

  1. Aerial radiological surveys of Steed Pond, Savannah River Site: Dates of surveys, 1984--1989

    SciTech Connect (OSTI)

    Fritzsche, A.E.; Jobst, J.E.

    1993-09-01

    From June 1984 to August 1985, three aerial radiological surveys were conducted over Steed Pond at the Savannah River Site in South Carolina. In addition, Steed Pond was included in larger-area surveys of the Savannah River Site in subsequent years. The surveys were conducted by the Remote Sensing Laboratory of EG&G Energy Measurements, Inc., Las Vegas, Nevada, for the US Department of Energy. Airborne measurements were obtained for both natural and man-made gamma radiation over Steed Pond and surrounding areas. The first survey was conducted when the pond was filled to normal capacity for the time of the year. On September 1, 1984, the Steed Pond dam spillway failed causing the pond to drain. The four subsequent surveys were conducted with the pond drained. The second survey and the third were conducted to study silt deposits exposed by the drop in water level after the spillway`s opening. Steed Pond data from the February 1987 and April 1989 Savannah River Site surveys have been included to bring this study up to date.

  2. Trace metals in urban streams and detention ponds

    SciTech Connect (OSTI)

    Licsko, Z.J.; Struger, J.

    1995-12-31

    Trace metal levels were monitored over a nine month period in two urban creeks in the Hamilton Harbour watershed and in two urban stormwater retention ponds in Guelph, Ontario. Samples were collected both during dry or non-event periods and immediately after wet weather events. Both water and surficial sediment samples were collected and tested for cadmium, copper, lead, mercury, nickel, and zinc. In almost all cases during wet weather conditions, Canadian Water Quality Guidelines for the protection of freshwater aquatic life were exceeded in water for lead (>7 mg/L), copper (>4 mg/L), and zinc (>30 mg/L) . Both stormwater ponds accumulated trace metals in sediment to levels above the lowest effect level guideline for the protection and management of aquatic sediment in Ontario, and, in the case of zinc (> 820 ug/g), above the severe effect level guideline. These levels of contamination raise serious concerns about the use of these and similar facilities as habitat for biota.

  3. Commercial Cooling Par Engineering: Order (2013-CE-5312)

    Broader source: Energy.gov [DOE]

    DOE ordered Commercial Cooling Par Engineering, Inc. to pay a $8,000 civil penalty after finding Commercial Cooling Par Engineering had failed to certify that certain models of walk-in cooler and freezer components comply with the applicable energy conservation standards.

  4. How to Submit a Request for a PARS II Account | Department of...

    Energy Savers [EERE]

    How to Submit a Request for a PARS II Account How to Submit a Request for a PARS II Account The account access process for PARS II relies on the Department of Energy's iManage...

  5. Spectral calculation of thermal performance of solar pond and comparison of the results with the experiments

    SciTech Connect (OSTI)

    Li, X.Y.; Kanayama, Kimio; Baba, Hiromu

    1999-07-01

    This paper deals with the method and the result of the spectroscopic calculation on the heat balance of a salt-gradient solar pond under the conditions of spectral solar radiation. Furthermore, the reflection of the rays incident upon the surface of the pond water, the refraction of the rays within the salt water layer and the diffusion of the salt in the pond water are considered. On the other hand, in order to make clear the mechanism of heat collection and heat storage of a solar pond, the authors conducted the indoor experiment and numerical analysis on a small scale model of salt-gradient solar pond with 2 m{sup 2} surface area and 1.6 m depth, under incident ray from a Xe-lamp solar simulator. According to above experimental analysis, the authors made a simulation model of thermal performance for a solar pond and calculated the heat balance in it. They found that the simulation calculations correspond well to the experimental result, so that their thermal simulation model might be correct. Furthermore, the authors also did the thermal calculation by changing the incident ray from Xe-lamp into natural ray, and found that the temperature distributions were notably different due to spectral characteristics of the incident ray. Therefore, the spectroscopic consideration for thermal performance of any solar pond is necessary to obtain a correct solution under the spectral incidence of special distributions.

  6. Analysis of storm-water infiltration ponds on the North Carolina Outer Banks

    SciTech Connect (OSTI)

    Chescheir, G.M.; Fipps, G.; Skaggs, R.W.

    1990-09-01

    Increasing development along the North Carolina coast has been linked to the deterioration of water quality in adjacent sounds and estuaries. Degradation of water quality in sounds and estuaries threatens the coastal ecology which provides resources for the area's fishing and tourism industries. The state of N.C. adopted the current Stormwater Runoff Disposal Rules in 1988 requiring stormwater management plans for new development in 20 coastal counties. Stormwater infiltration pond systems are approved by the State as an option for retaining stormwater on the developed site; however, the long-term performance of these systems has not been measured or determined. The study was conducted to monitor the hydrology of stormwater infiltration ponds on the North Carolina barrier islands and to develop a model that continuously simulates the performance of these ponds. The hydrology of two operating infiltration ponds systems was evaluated in an 18-month field study. Rainfall, pond stage, and water table elevations at selected locations were monitored continuously. Water table elevations at additional locations were monitored on a biweekly basis. Soil hydraulic conductivities and soil water characteristic relationships were determined at both field sites. The subsurface geology was described at one site and an aquifer pump test was performed to determine aquifer transmissivity and specific yield. Both of the infiltration ponds in the field studies effectively served their primary purpose of retaining on site the stormwater runoff from the first 38 mm (1.5 in) of rainfall. In nearly every case, the pond seepage rate was sufficient to completely draw down the pond within 5 days. The hydrology of the infiltration ponds at the two research sites was very different.

  7. HRE-Pond Cryogenic Barrier Technology Demonstration: Pre- and Post-Barrier Hydrologic Assessment

    SciTech Connect (OSTI)

    Moline, G.R.

    1999-06-01

    The Homogeneous Reactor Experiment (HRE) Pond is the site of a former impoundment for radioactive wastes on the Oak Ridge Reservation (ORR) in east Tennessee. The pond received radioactive wastes from 1957 to 1962, and was subsequently drained, filled with soil, and covered with an asphalt cap. The site is bordered to the east and south by an unnamed stream that contains significant concentrations of radioactive contaminants, primarily {sup 90}Sr. Because of the proximity of the stream to the HRE disposal site and the probable flow of groundwater from the site to the stream, it was hypothesized that the HRE Pond has been a source of contamination to the creek. The HRE-Pond was chosen as the site of a cryogenic barrier demonstration to evaluate this technology as a means for rapid, temporary isolation of contaminants in the type of subsurface environment that exists on the ORR. The cryogenic barrier is created by the circulation of liquid CO{sub 2} through a system of thermoprobes installed in boreholes which are backfilled with sand. The probes cool the subsurface, creating a vertical ice wall by freezing adjacent groundwater, effectively surrounding the pond on four sides. The purpose of this investigation was to evaluate the hydrologic conditions within and around the pond prior to, during, and after the cryogenic barrier emplacement. The objectives were (1) to provide a hydrologic baseline for post-banner performance assessment, (2) to confirm that the pond is hydraulically connected to the surrounding sediments, (3) to determine the likely contaminant exit pathways from the pond, and (4) to measure changes in hydrologic conditions after barrier emplacement in order to assess the barrier performance. Because relatively little information about the subsurface hydrology and the actual configuration of the pond existed, data from multiple sources was required to reconstruct this complex system.

  8. Microsoft PowerPoint - Snippet 5.2 PARS II Analysis-Data Validity...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    being reported reflects reality. 5 PARS II automatically issues warnings upon the ... The contractor may or may not take the opportunity to make corrections. The PARS II EV ...

  9. Groundwater Monitoring Plan for the Hanford Site 216-B-3 Pond RCRA Facility

    SciTech Connect (OSTI)

    Barnett, D BRENT.; Smith, Ronald M.; Chou, Charissa J.; McDonald, John P.

    2005-11-01

    The 216-B-3 Pond system was a series of ponds used for disposal of liquid effluent from past Hanford production facilities. In operation from 1945 to 1997, the B Pond System has been a Resource Conservation and Recovery Act (RCRA) facility since 1986, with RCRA interim-status groundwater monitoring in place since 1988. In 1994 the expansion ponds of the facility were clean closed, leaving only the main pond and a portion of the 216-B-3-3 ditch as the currently regulated facility. In 2001, the Washington State Department of Ecology (Ecology) issued a letter providing guidance for a two-year, trial evaluation of an alternate, intrawell statistical approach to contaminant detection monitoring at the B Pond system. This temporary variance was allowed because the standard indicator-parameters evaluation (pH, specific conductance, total organic carbon, and total organic halides) and accompanying interim status statistical approach is ineffective for detecting potential B-Pond-derived contaminants in groundwater, primarily because this method fails to account for variability in the background data and because B Pond leachate is not expected to affect the indicator parameters. In July 2003, the final samples were collected for the two-year variance period. An evaluation of the results of the alternate statistical approach is currently in progress. While Ecology evaluates the efficacy of the alternate approach (and/or until B Pond is incorporated into the Hanford Facility RCRA Permit), the B Pond system will return to contamination-indicator detection monitoring. Total organic carbon and total organic halides were added to the constituent list beginning with the January 2004 samples. Under this plan, the following wells will be monitored for B Pond: 699-42-42B, 699-43-44, 699-43-45, and 699-44-39B. The wells will be sampled semi-annually for the contamination indicator parameters (pH, specific conductance, total organic carbon, and total organic halides) and annually for

  10. A comparison of Nannochloropsis salina growth performance in two outdoor pond designs: conventional raceways versus the ARID pond with superior temperature management

    SciTech Connect (OSTI)

    Crowe, Braden J.; Attalah, Said; Agrawal, Shweta; Waller, Peter; Ryan, Randy; Van Wagenen, Jonathan M.; Chavis, Aaron R.; Kyndt, John; Kacira, Murat; Ogden, Kimberly L.; Huesemann, Michael H.

    2012-10-01

    The present study examines how climatic conditions and pond design affect the growth performance of microalgae. From January to April of 2011, outdoor batch cultures of Nannochloropsis salina were grown in three replicate 780 L conventional raceways, as well as in an experimental 7500 L ARID (Algae Raceway Integrated Design) pond. The ARID culture system utilizes a series of 8 to 20 cm deep basins and a 1.5 m deep canal to enhance light exposure and mitigate temperature variations and extremes. The ARID culture reached the stationary phase 27 days earlier than the conventional raceways, which can be attributed to its superior temperature management and shallower basins. On a night when the air temperature dropped to -9 C, the water temperature was 18 C higher in the ARID pond than in the conventional raceways. Lipid and fatty acid content ranged from 16 - 25 % and 5 - 15 %, respectively, as a percentage of AFDW. Palmitic, palmitoleic, and eicosapentaenoic acid comprised the majority of fatty acids. While the ARID culture system achieved nearly double the volumetric productivity relative to the conventional raceways (0.023 vs 0.013 g L-1day-1), areal biomass productivities were of similar magnitude in both pond systems (3.34 vs. 3.47 g m-2day-1), suggesting that the ARID pond design has to be further optimized, most likely by increasing the culture depth or operating at higher cell densities while maintaining adequate mixing.

  11. In re Kent Pond, No MLP-03-10, Findings of Fact, Conclusions...

    Open Energy Info (EERE)

    re Kent Pond, No MLP-03-10, Findings of Fact, Conclusions of Law, and Order at 8, 13 (Vt. Water Res. Bd. May, 2004) Jump to: navigation, search OpenEI Reference LibraryAdd to...

  12. Title 29 Chapter 11 Management of Lakes and Ponds | Open Energy...

    Open Energy Info (EERE)

    Title 29 Chapter 11 Management of Lakes and Ponds Jump to: navigation, search OpenEI Reference LibraryAdd to library Legal Document- StatuteStatute: Title 29 Chapter 11 Management...

  13. 40 CFR 265 interim-status ground-water monitoring plan for the 2101-M pond

    SciTech Connect (OSTI)

    Chamness, M.A.; Luttrell, S.P.; Dudziak, S.

    1989-03-01

    This report outlines a ground-water monitoring plan for the 2101-M pond, located in the southwestern part of the 200-East Area on the Hanford Site in south-central Washington State. It has been determined that hazardous materials may have been discharged to the pond. Installation of an interim-status ground-water monitoring system is required under the Resource Conservation and Recovery Act to determine if hazardous chemicals are moving out of the pond. This plan describes the location of new wells for the monitoring system, how the wells are to be completed, the data to be collected, and how those data can be used to determine the source and extent of any ground-water contamination from the 2101-M pond. Four new wells are planned, one upgradient and three downgradient. 35 refs., 12 figs., 9 tabs.

  14. Title 10 Chapter 11 Management of Lakes and Ponds | Open Energy...

    Open Energy Info (EERE)

    of Lakes and PondsLegal Published NA Year Signed or Took Effect 1985 Legal Citation 29 V.S.A 401 DOI Not Provided Check for DOI availability: http:crossref.org Online Internet...

  15. Commercial Cooling Par Engineering: Proposed Penalty (2013-CE-5312)

    Broader source: Energy.gov [DOE]

    DOE alleged in a Notice of Proposed Civil Penalty that Commercial Cooling Par Engineering failed to certify walk-in cooler or freezer components as compliant with the energy conservation standards.

  16. A lipid-accumulating alga maintains growth in outdoor, alkaliphilic raceway pond with mixed microbial communities

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Bell, Tisza A.S.; Prithiviraj, Bharath; Wahlen, Brad D.; Fields, Matthew W.; Peyton, Brent M.

    2016-01-07

    Algal biofuels and valuable co-products are being produced in both open and closed cultivation systems. Growing algae in open pond systems may be a more economical alternative, but this approach allows environmental microorganisms to colonize the pond and potentially infect or outcompete the algal “crop.” In this study, we monitored the microbial community of an outdoor, open raceway pond inoculated with a high lipid-producing alkaliphilic alga, Chlorella vulgaris BA050. The strain C. vulgaris BA050 was previously isolated from Soap Lake, Washington, a system characterized by a high pH (~9.8). An outdoor raceway pond (200 L) was inoculated with C. vulgarismore » and monitored for 10 days and then the culture was transferred to a 2,000 L raceway pond and cultivated for an additional 6 days. Community DNA samples were collected over the 16-day period in conjunction with water chemistry analyses and cell counts. Universal primers for the SSU rRNA gene sequences for Eukarya, Bacteria, and Archaea were used for barcoded pyrosequence determination. The environmental parameters that most closely correlated with C. vulgaris abundance were pH and phosphate. Community analyses indicated that the pond system remained dominated by the Chlorella population (93% of eukaryotic sequences), but was also colonized by other microorganisms. Bacterial sequence diversity increased over time while archaeal sequence diversity declined over the same time period. Using SparCC co-occurrence network analysis, a positive correlation was observed between C. vulgaris and Pseudomonas sp. throughout the experiment, which may suggest a symbiotic relationship between the two organisms. The putative relationship coupled with high pH may have contributed to the success of C. vulgaris. As a result, the characterization of the microbial community dynamics of an alkaliphilic open pond system provides significant insight into open pond systems that could be used to control photoautotrophic biomass

  17. Experiment and analysis of practical-scale solar pond stabilized with salt gradient

    SciTech Connect (OSTI)

    Kanayama, Kimio; Inaba, Hideo; Baba, Hiromu; Fukuda, Takeyuki )

    1991-01-01

    A large-scale solar pond with salty water was constructed in the suburbs of Kitami in 1985. Its performance has been measured and analyzed by the authors after that. The solar pond body is circular of 44 m diameter, and the pond water is of 3 min total depth. After, 15 months, the depth of the salt gradient zone (S.G.Z.) was thinned by 10 cm in the top and by 20 cm in the bottom due to convection of the top and bottom zones. The temperature in the convective storage zone (C.S.Z.) reached 70C, its maximum, at the beginning of September in 1985, however, it was not as high in 1986 due to contamination of the pond water. The temperature of the storage zone was reduced from November to April due to ice covering on the pond surface. The collected heat yielded largely and the collection efficiency reached more than 30% in summer, but decreased to negative values in winter. The thermal performance of the solar pond was predicted by a simulation calculation, and the calculated result compared well with the measurements.

  18. 216-U-10 Pond and 216-Z-19 Ditch characterization studies

    SciTech Connect (OSTI)

    Last, G.V.; Duncan, D.W.; Graham, M.J.; Hall, M.D.; Hall, V.W.; Landeen, D.S.; Leitz, J.G.; Mitchell, R.M.

    1994-02-01

    The chemical, reprocessing of spent nuclear fuels at the US Department of Energy`s Hanford Site has generated large volumes of radioactive liquid effluents. The majority of these effluents have been used strictly for cooling or other supportive functions and have been discharged to ditches and ponds. The 216-U-10 Pond and 216-Z-19 Ditch are two such disposal facilities. These facilities are components of an integrated system of ditches, ponds, and overflow facilities collectively referred to as the U-Pond disposal system. The U-Pond system has been used since 1943 and has received a large variety of radioisotopes from several sources. This study covered tho major aspects of the environment, including wind resuspension, biological uptake and transport, geologic distribution in surface and subsurface sediments, and ground-water impacts. The long-term use of U-Pond and the Z-19 Ditch has resulted in the localized accumulation of transuranic and fission product inventories as a result of sorption and filtration of particulates onto the uppermost sediments.

  19. Groundwater Monitoring Plan for the Hanford Site 216-B-3 Pond RCRA Facility

    SciTech Connect (OSTI)

    Barnett, D. Brent; Smith, Ronald M.; Chou, Charissa J.

    2000-11-28

    The 216-B-3 Pond was a series of ponds for disposal of liquid effluent from past Hanford production facilities. In 1990, groundwater monitoring at B Pond was elevated from "detection" to assessment status because total organic halides and total organic carbon were found to exceed critical means in two wells. Groundwater quality assessment, which ended in 1996, failed to find any specific hazardous waste contaminant that could have accounted for the isolated occurrences of elevated total organic halides and total organic carbon. Hence, the facility was subsequently returned to detection-level monitoring in 1998. Exhaustive groundwater analyses during the assessment period indicated that only two contaminants, tritium and nitrate, could be positively attributed to the B Pond System, with two others (arsenic and I-129) possibly originating from B Pond. Chemical and radiological analyses of soil at the main pond and 216-B-3-3 ditch has not revealed significant contamination. Based on the observed, minor contamination in groundwater and in the soil column, three parameters were selected for site-specific, semiannual monitoring; gross alpha, gross beta, and specific conductance. Total organic halides and total organic carbon are included as constituents because of regulatory requirements. Nitrate, tritium, arsenic, and iodine-129 will be monitored under the aegis of Hanford site-wide monitoring. Although the B Pond System is not scheduled to advance from RCRA interim status to final status until the year 2003, a contingency plan for an improved monitoring strategy, which will partially emulate final status requirements, will be contemplated before the official change to final status. This modification will allow a more sensible and effective screening of groundwater for the facility.

  20. A Comparison of Nannochloropsis salina Growth Performance in Two Outdoor Pond Designs: Conventional Raceways versus the ARID Pond with Superior Temperature Management

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Crowe, Braden; Attalah, Said; Agrawal, Shweta; Waller, Peter; Ryan, Randy; Van Wagenen, Jon; Chavis, Aaron; Kyndt, John; Kacira, Murat; Ogden, Kim L.; et al

    2012-01-01

    The present study examines how climatic conditions and pond design affect the growth performance of microalgae. From January to April of 2011, outdoor batch cultures of Nannochloropsis salina were grown in three replicate 780 L conventional raceways, as well as in an experimental 7500 L algae raceway integrated design (ARID) pond. The ARID culture system utilizes a series of 8-20 cm deep basins and a 1.5 m deep canal to enhance light exposure and mitigate temperature variations and extremes. The ARID culture reached the stationary phase 27 days earlier than the conventional raceways, which can be attributed to its superiormore » temperature management and shallower basins. On a night when the air temperature dropped to -9°C, the water temperature was 18°C higher in the ARID pond than in the conventional raceways. Lipid and fatty acid content ranged from 16 to 25% and from 5 to15%, respectively, as a percentage of AFDW. Palmitic, palmitoleic, and eicosapentaenoic acids comprised the majority of fatty acids. While the ARID culture system achieved nearly double the volumetric productivity relative to the conventional raceways (0.023 versus 0.013 g L-1day-1), areal biomass productivities were of similar magnitude in both pond systems (3.47 versus 3.34 g m-2day-1), suggesting that the ARID pond design has to be further optimized, most likely by increasing the culture depth or operating at higher cell densities while maintaining adequate mixing.« less

  1. A Comparison of Nannochloropsis salina Growth Performance in Two Outdoor Pond Designs: Conventional Raceways versus the ARID Pond with Superior Temperature Management

    SciTech Connect (OSTI)

    Crowe, Braden; Attalah, Said; Agrawal, Shweta; Waller, Peter; Ryan, Randy; Van Wagenen, Jon; Chavis, Aaron; Kyndt, John; Kacira, Murat; Ogden, Kim L.; Huesemann, Michael

    2012-01-01

    The present study examines how climatic conditions and pond design affect the growth performance of microalgae. From January to April of 2011, outdoor batch cultures of Nannochloropsis salina were grown in three replicate 780 L conventional raceways, as well as in an experimental 7500 L algae raceway integrated design (ARID) pond. The ARID culture system utilizes a series of 8-20 cm deep basins and a 1.5 m deep canal to enhance light exposure and mitigate temperature variations and extremes. The ARID culture reached the stationary phase 27 days earlier than the conventional raceways, which can be attributed to its superior temperature management and shallower basins. On a night when the air temperature dropped to -9C, the water temperature was 18C higher in the ARID pond than in the conventional raceways. Lipid and fatty acid content ranged from 16 to 25% and from 5 to15%, respectively, as a percentage of AFDW. Palmitic, palmitoleic, and eicosapentaenoic acids comprised the majority of fatty acids. While the ARID culture system achieved nearly double the volumetric productivity relative to the conventional raceways (0.023 versus 0.013 g L-1day-1), areal biomass productivities were of similar magnitude in both pond systems (3.47 versus 3.34 g m-2day-1), suggesting that the ARID pond design has to be further optimized, most likely by increasing the culture depth or operating at higher cell densities while maintaining adequate mixing.

  2. East Pond West Pond South Pond South Pond Southwest Pond

    Office of Legacy Management (LM)

    20-M38D 13.32 20-M054 14.66 20-M053 14.09 12-S67D 13.73 15-0566 14.33 12-S70D 13.31 12-S68D 13.41 12-S69D 13.02 12-S71D 13.36 12-S72D 12.99 12-S73D 12.92 20-M061 14.83 20-M063...

  3. East Pond West Pond South Pond South Pond Southwest Pond

    Office of Legacy Management (LM)

    12-S30B 713.6 12-S33C 1863 12-S35B 38320 15-0534 ND 20-M003 ND 20-M005 ND 20-M054 3.9 12-S68D 164.7 12-S69C ND 12-S70B 30 12-S70C 70 12-S71C 77 12-S72C 3.8 12-S73B ND 12-S73C 11.9 12-S67B 349.9 12-S67C 197.2 12-S67D 56.7 15-0566 101 12-0527 ND 12-S69D ND 12-S70D 43.2 12-S71D 28.2 12-S72D ND 12-S71B ND 12-S69B ND 20-M028 ND 20-M011 ND 20-M019 ND 20-0503 4.1 20-M024 ND 20-M025 ND 20-M035 2.9 20-M036 ND 20-M38D ND 20-M40S ND 20-M023 ND 20-M41D ND 15-0569 5.6 20-MWL3 996.1 20-M049 5.6 20-M22D 4.2

  4. East Pond West Pond South Pond South Pond Southwest Pond

    Office of Legacy Management (LM)

    06-0500 14.4 06-0501 14.53 15-M03S 14.97 18-0500 14.34 18-0502 14.23 18-0521 14.18 18-0525 14.31 18-0526 13.79 20-M025 14.26 20-M035 14.4 21-0502 12.66 21-0503 12.34 21-0504 13.12...

  5. Description of work for 100-N Hanford Generating Plant settling pond drilling and sampling

    SciTech Connect (OSTI)

    Galbraith, R.P.

    1993-09-01

    This description of work details the field activities associated with borehole drilling and sampling of the 100-N Hanford Generating Plant (HGP) Settling Pond and will serve as a field guide for those performing the work. It should be used in conjunction with the Environmental Investigations and Site Characterization Manual (WHC 1988a) for specific procedures. The borehole location is shown in Figure 1. The settling pond, the dimensions of which are 40 m by 16 m (131.3 ft by 52.5 ft), is located at the HGP adjacent to the 100-N Area. The pond received process water from the plant. The water contained trace oxygen scavenging conditioners such as morpholine, hydrazine, and ammonia. Surface radioactivity readings are 150 to 500 cpm. Trace levels of surface contamination are present. Drilling and sampling will be in accordance with procedures in the EII manual (WHC 1988a).

  6. Vitrification demonstration with surrogate Oak Ridge Reservation K-25 B and C pond sludge

    SciTech Connect (OSTI)

    Cicero, C.A.; Overcamp, T.J.; Erich, D.L.

    1996-07-01

    Surrogate Oak Ridge Reservation (ORR) K-25 B&C Pond sludge was vitrified in a pilot-scale EnVit Co melter operated by Clemson University at the DOE/Industrial Center for Vitrification Research Center. This demonstration was performed for the Savannah River Technology Center (SRTC) in support of a Department of Energy (DOE) - Office of Technology Development (OTD) Technical Task Plan. The intent of the demonstration was to determine the feasibility of vitrifying actual K-25 B&C Pond sludge in an EnVitCo type melter. B&C Pond sludge is a mixed waste consisting primarily of various amounts of Ca, Fe, and Si, with Ni and U as the principal hazardous and radioactive components. The demonstration was successfully completed and homogeneous, durable glass was produced. Characterization of the glass product, as well as details of the demonstration, will be discussed.

  7. DOE responses to Ecology review comments for ``Sampling and analysis plans for the 100-D Ponds voluntary remediation project``

    SciTech Connect (OSTI)

    NONE

    1996-12-31

    The Sampling and Analysis Plan describes the sampling and analytical activities which will be performed to support closure of the 100-D Ponds at the Hanford Reservation. This report contains responses by the US Department of Energy to Ecology review for ``Sampling and Analysis Plan for the 100-D Ponds Voluntary Remediation Project.``

  8. Gradient zone-boundary control in salt-gradient solar ponds

    DOE Patents [OSTI]

    Hull, J.R.

    1982-09-29

    A method and apparatus for suppressing zone boundary migration in a salt gradient solar pond includes extending perforated membranes across the pond at the boundaries, between the convective and non-convective zones, the perforations being small enough in size to prevent individual turbulence disturbances from penetrating the hole, but being large enough to allow easy molecular diffusion of salt thereby preventing the formation of convective zones in the gradient layer. The total area of the perforations is a sizeable fraction of the membrane area to allow sufficient salt diffusion while preventing turbulent entrainment into the gradient zone.

  9. Breeding pond selection and movement patterns by eastern spadefoot toads (Scaphiopus holbrookii) in relation to weather and edaphic conditions.

    SciTech Connect (OSTI)

    Greenberg, Cathyrn, H.; Tanner, George, W.

    2004-08-31

    Cathryn H. Greenberg and George W. Tanner. 2004. Breeding pond selection and movement patterns by eastern spadefoot toads (Scaphiopus holbrookii) in relation to weather and edaphic conditions. J. Herp. 38(4):569-577. Abstract: Eastern Spadefoot Toads (Scaphiopus holbrookii) require fish-free, isolated, ephemeral ponds for breeding but otherwise inhabit the surrounding uplands, commonly xeric longleaf pine (Pinus palustris) ?wiregrass (Aristida beyrichiana). Hence both pond and upland conditions can potentially affect their breeding biology, and population persistence. Hardwood invasion due to fire suppression in sandhills could alter upland and pond suitability by higher hardwood density and increased transpiration. In this paper we explore breeding and neonatal emigration movements in relation to weather, hydrological conditions of ponds, and surrounding upland matrices. We use 9 years of data from continuous monitoring with drift fences and pitfall traps at 8 ephemeral ponds in 2 upland matrices: regularly-burned, savanna-like sandhills (n = 4), and hardwood-invaded sandhills (n = 4). Neither adult nor neonate captures differed between ponds within the 2 upland matrices, suggesting that they are tolerant of upland heterogeneity created by fire frequency. Explosive breeding occurred during 9 periods and in all seasons; adults were captured rarely otherwise. At a landscape-level rainfall, maximum change in barometric pressure, and an interaction between those 2 variables were significant predictors of explosive breeding. At a pond-level, rainfall, change in pond depth during the month prior to breeding, and days since a pond was last dry were significant predictors of adult captures. Transformation date, rather than weather, was associated with neonatal emigrations, which usually were complete within a week. Movement by first-captured adults and neonates was directional, but adult emigrations were apparently not always toward their origin. Our results suggest that

  10. Microsoft PowerPoint - Snippet 5.4 PARS II Analysis-Variance...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    In PARS II under the SSS Reports selection on the left, there are folders to the right. ... warning signs of future problems. To drill down, we need to view other PARS II reports. ...

  11. Microsoft PowerPoint - Snippet 5.7 PARS II Analysis-OAPM Monthly...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Reports that are used to prepare the information are located in the PARS II SSS Reports ... Finally, the Project % Complete values calculated by PARS II are based on the contractor ...

  12. Report 20.5: Chromaticity Shift Modes of LED PAR38 Lamps Operated...

    Energy Savers [EERE]

    5: Chromaticity Shift Modes of LED PAR38 Lamps Operated in Steady-State Conditions Report 20.5: Chromaticity Shift Modes of LED PAR38 Lamps Operated in Steady-State Conditions PDF ...

  13. The L Prize PAR 38 Competition: A New Start | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    The L Prize PAR 38 Competition: A New Start The L Prize PAR 38 Competition: A New Start This March 27, 2012 webcast presented information on the newly reopened L Prize® PAR 38 competition. Moderated by James Brodrick, DOE Lighting Program Manager, the webcast featured an overview of the PAR 38 competition from Marc Ledbetter of Pacific Northwest National Laboratory, and explained key changes of the retooled competition requirements. Topics included performance specifications, U.S. content

  14. 2013 Radiological Monitoring Results Associated with the Advanced Test Reactor Complex Cold Waste Pond

    SciTech Connect (OSTI)

    Mike Lewis

    2014-02-01

    This report summarizes radiological monitoring performed of the Idaho National Laboratory Site’s Advanced Test Reactor Complex Cold Waste wastewater prior to discharge into the Cold Waste Pond and of specific groundwater monitoring wells associated with the Industrial Wastewater Reuse Permit (#LA-000161-01, Modification B). All radiological monitoring is performed to fulfill Department of Energy requirements under the Atomic Energy Act.

  15. 2011 Radiological Monitoring Results Associated with the Advanced Test Reactor Complex Cold Waste Pond

    SciTech Connect (OSTI)

    Mike Lewis

    2012-02-01

    This report summarizes radiological monitoring performed of the Idaho National Laboratory Site's Advanced Test Reactor Complex Cold Waste wastewater prior to discharge into the Cold Waste Pond and of specific groundwater monitoring wells associated with the Industrial Wastewater Reuse Permit (LA-000161-01, Modification B). All radiological monitoring is performed to fulfill Department of Energy requirements under the Atomic Energy Act.

  16. 2010 Radiological Monitoring Results Associated with the Advance Test Reactor Complex Cold Waste Pond

    SciTech Connect (OSTI)

    mike lewis

    2011-02-01

    This report summarizes radiological monitoring performed of the Idaho National Laboratory Site’s Advanced Test Reactor Complex Cold Waste wastewater prior to discharge into the Cold Waste Pond and of specific groundwater monitoring wells associated with the Industrial Wastewater Reuse Permit (#LA-000161-01, Modification B). All radiological monitoring is performed to fulfill Department of Energy requirements under the Atomic Energy Act.

  17. 2012 Radiological Monitoring Results Associated with the Advanced Test Reactor Complex Cold Waste Pond

    SciTech Connect (OSTI)

    Mike Lewis

    2013-02-01

    This report summarizes radiological monitoring performed of the Idaho National Laboratory Site’s Advanced Test Reactor Complex Cold Waste wastewater prior to discharge into the Cold Waste Pond and of specific groundwater monitoring wells associated with the Industrial Wastewater Reuse Permit (#LA-000161-01, Modification B). All radiological monitoring is performed to fulfill Department of Energy requirements under the Atomic Energy Act.

  18. Evaluation of remedial alternatives for the Solar Ponds Plume, Rocky Flats Environmental Technology Site

    SciTech Connect (OSTI)

    Hranac, K.C.; Chromec, F.W.; Fiehweg, R.; Hopkins, J.

    1998-07-01

    This paper describes the process used to select a remedial alternative for handling contaminated groundwater emanating from the Solar Evaporation Ponds (Solar Ponds) at the Rocky Flats Environmental Technology Site (RFETS) and prevent it from reaching the nearest surface water body, North Walnut Creek. Preliminary results of field investigations conducted to provide additional information for the alternatives analysis are also presented. The contaminated groundwater is referred to as the Solar Ponds Plume (SPP). The primary contaminants in the SPP are nitrate and uranium; however, some metals exceed the site action levels at several locations and volatile organic compounds, originating from other sources, also have been detected. Currently the SPP, local surface water runoff, and infiltrated precipitation are collected by a trench system located downgradient of the Solar Ponds and pumped to three storage tanks. The water (two to three million gallons annually) is then pumped to an on-site treatment plant for evaporation at an approximate cost of $7.57 per liter.

  19. 2014 Radiological Monitoring Results Associated with the Advanced Test Reactor Complex Cold Waste Pond

    SciTech Connect (OSTI)

    Lewis, Mike

    2015-02-01

    This report summarizes radiological monitoring performed of the Idaho National Laboratory Site’s Advanced Test Reactor Complex Cold Waste wastewater prior to discharge into the Cold Waste Pond and of specific groundwater monitoring wells associated with the Industrial Wastewater Reuse Permit (#LA-000161-01, Modification B). All radiological monitoring is performed to fulfill Department of Energy requirements under the Atomic Energy Act.

  20. Phytoplankton in the cooling pond of a nuclear fuel plant. II. Spectral analysis

    SciTech Connect (OSTI)

    Tokarskaya, Z.B.; Smagin, A.I.; Ryzhkov, E.G.; Nikitina, L.V.

    1995-09-01

    This study continues investigations into the development dynamics of phytoplankton and hydrochemical and meteorological factors over a periods of 26 years in the cooling pond of the Mayak Production Association in the Kyzyl-Trash Lake. The aim is to evaluate the long-term oscillations in phytoplankton owing to changes in hydrochemical and meteorological factors. 6 refs., 2 figs., 1 tab.

  1. Western Pond Turtle Head-starting and Reintroduction; 2003-2004 Annual Report.

    SciTech Connect (OSTI)

    Van Leuven, Susan; Allen, Harriet; Slavin, Kate

    2004-09-01

    This report covers the results of the western pond turtle head-starting and reintroduction project for the period of October 2003-September 2004. Wild hatchling western pond turtles from the Columbia River Gorge were reared at the Woodland Park and Oregon Zoos in 2003 and 2004 as part of the recovery effort for this Washington State endangered species. The objective of the program is to reduce losses to introduced predators like bullfrogs and largemouth bass by raising the hatchlings to a size where they are too large to be eaten by most of these predators. Sixty-nine turtles were over-wintered at the Woodland Park Zoo and 69 at the Oregon Zoo. Of these, 136 head-started juvenile turtles were released at three sites in the Columbia Gorge in 2004. Two were held back to attain more growth in captivity. Thirty-four were released at the Klickitat ponds, 19 at the Klickitat lake, 21 at the Skamania site, and 62 at Pierce National Wildlife Refuge (NWR). This brought the total number of head-start turtles released since 1991 to 246 for the Klickitat ponds, 114 for the Klickitat lake, 167 for the Skamania pond complex, and 250 at Pierce NWR. In 2004, 32 females from the two Columbia Gorge populations were equipped with transmitters and monitored for nesting activity. Twenty-one of the females nested and produced 85 hatchlings. The hatchlings were collected in September and October and transported to the Woodland Park and Oregon zoos for rearing in the head-start program. Data collection for a four-year telemetry study of survival and habitat use by juvenile western pond turtles at Pierce NWR concluded in 2004. Radio transmitters on study animals were replaced as needed until all replacements were in service; afterward, the turtles were monitored until their transmitters failed. The corps of study turtles ranged from 39 in August 2003 to 2 turtles at the end of August 2004. These turtles showed the same seasonal pattern of movements between summer water and upland winter

  2. Project Assessment and Reporting System (PARS II) Data Quality Memo

    Broader source: Energy.gov [DOE]

    While PARS II is but one of many tools used to monitor project performance, when information and earned value data in the system are deficient and do not accurately reflect current project status or provide acceptable forecasts, effective project management is impaired. If we are to demonstrate long-term improvement in contract and project management, we must insist on project information that facilitates management, not impedes it.

  3. Western Pond Turtle Head-starting and Reintroduction; 2004-2005 Annual Report.

    SciTech Connect (OSTI)

    Van Leuven, Susan; Allen, Harriet; Slavin, Kate

    2005-09-01

    This report covers the results of the western pond turtle head-starting and reintroduction project for the period of October 2004-September 2005. Wild hatchling western pond turtles from the Columbia River Gorge were reared at the Woodland Park and Oregon Zoos in 2004 and 2005 as part of the recovery effort for this Washington State endangered species. The objective of the program is to reduce losses to introduced predators like bullfrogs and largemouth bass by raising the hatchlings to a size where they are too large to be eaten by most of these predators. Thirty-five turtles were placed at the Woodland Park Zoo and 53 at the Oregon Zoo. Of these, 77 head-started juvenile turtles were released at three sites in the Columbia Gorge in 2005. Four were held back to attain more growth in captivity. Eleven were released at the Klickitat ponds, 22 at the Klickitat lake, 39 at the Skamania site, and 5 at Pierce National Wildlife Refuge (NWR). This brought the total number of head-start turtles released since 1991 to 257 for the Klickitat ponds, 136 for the Klickitat lake, 206 for the Skamania pond complex, and 255 at Pierce NWR. In 2005, 34 females from the two Columbia Gorge populations were equipped with transmitters and monitored for nesting activity. Twenty-four nests were located and protected; these produced 90 hatchlings. The hatchlings were collected in September and transported to the Oregon and Woodland Park zoos for rearing in the head-start program. During the 2005 field season trapping effort, 486 western pond turtles were captured in the Columbia Gorge, including 430 previously head-started turtles. These recaptures, together with confirmed nesting by head-start females and visual resightings, indicate the program is succeeding in boosting juvenile recruitment to increase the populations. Records were also collected on 216 individual painted turtles captured in 2005 during trapping efforts at Pierce NWR, to gather baseline information on this native

  4. Western Pond Turtle Head-starting and Reintroduction, 2005-2006 Annual Report.

    SciTech Connect (OSTI)

    Van Leuven, Susan; Allen, Harriet; Slavens, Kate

    2006-11-01

    This report covers the results of the western pond turtle head-starting and reintroduction project for the period of October 2005-September 2006. Wild hatchling western pond turtles from the Columbia River Gorge were reared at the Woodland Park and Oregon zoos in 2005 and 2006 as part of the recovery effort for this Washington State endangered species. The objective of the program is to reduce losses to introduced predators like bullfrogs and largemouth bass by raising the hatchlings to a size where they are too large to be eaten by most of these predators. Twenty-six turtles were placed at the Woodland Park Zoo and 62 at the Oregon Zoo in fall 2005. These turtles joined two that were held back from release in summer 2005 due to their small size. All 90 juvenile turtles were released at three sites in the Columbia Gorge in 2006. Twenty-eight juvenile turtles were released at the Klickitat ponds, 22 at the Klickitat lake, 21 at the Skamania site, and 19 at Pierce National Wildlife Refuge (NWR). This brought the total number of head-start turtles released since 1991 to 944; 285 for the Klickitat ponds, 158 for the Klickitat lake, 227 for the Skamania pond complex, and 274 at Pierce NWR. In 2006, 20 females from the Klickitat population were equipped with transmitters and monitored for nesting activity. Fifteen nests were located and protected; these produced 55 hatchlings. The hatchlings were collected in September and transported to the Oregon and Woodland Park zoos for rearing in the head-start program. One wild hatchling captured in spring 2006 was placed in the head-start program to attain more growth in captivity. During the 2006 field season trapping effort, 414 western pond turtles were captured in the Columbia Gorge, including 374 previously head-started turtles. These recaptures, together with confirmed nesting by head-start females and visual resightings, indicate the program is succeeding in boosting juvenile recruitment to increase the populations

  5. The absorption chiller in large scale solar pond cooling design with condenser heat rejection in the upper convecting zone

    SciTech Connect (OSTI)

    Tsilingiris, P.T. )

    1992-07-01

    The possibility of using solar ponds as low-cost solar collectors combined with commercial absorption chillers in large scale solar cooling design is investigated. The analysis is based on the combination of a steady-state solar pond mathematical model with the operational characteristics of a commercial absorption chiller, assuming condenser heat rejection in the upper convecting zone (U.C.Z.). The numerical solution of the nonlinear equations involved leads to results which relate the chiller capacity with pond design and environmental parameters, which are also employed for the investigation of the optimum pond size for a minimum capital cost. The derived cost per cooling kW for a 350 kW chiller ranges from about 300 to 500 $/kW cooling. This is almost an order of magnitude lower than using a solar collector field of evacuated tube type.

  6. Evaluation of the Eological Management and Enhancement Alernative for Remediation of the K1007-P1 Pond

    SciTech Connect (OSTI)

    Peterson, M.J.

    2005-10-31

    An evaluation of the human and ecological risks associated with the P1 Pond and surrounding environs was conducted as part of the ETTP Site-Wide Remedial Investigation. The RI provides the basis for the focus on PCBs as the most important unacceptable risk to human and ecological health in the pond. Other P1 contaminants, media, or pathways of risk to receptors are identified in the RI, but are not addressed as a major risk reduction goal for the ETTP Site-Wide Feasibility Study. Therefore, the goal of the Ecological Management alternative is to reduce unacceptable risks associated with PCBs in fish. Many of the actions proposed for this alternative, however, are likely to reduce risks associated with other contaminants and their pathways. The high PCB concentrations in fish from the P1 Pond are most certainly due in part to the current ecological condition of the pond that maximizes PCB biomagnification. This basic assumption and the factors contributing to it were evaluated by conducting an intensive field study of the P1 Pond in the summer of 2004 (for a thorough presentation of current P1 Pond biological conditions, see Peterson et al. 2005). Major hypotheses regarding the P1 Pond's current fish community, PCB fate and transport processes, pond vegetation, and limnological conditions that contribute to the high PCB levels in fish were validated by the study (Appendix A), The results of the 2004 ecological assessment, in concert with long-term datasets obtained as part of the ETTP Biological Monitoring and Abatement Program (BMAP) and recent abiotic sampling for the RI, provide the basis for the assessment of current conditions.

  7. Heat extraction from salinity-gradient solar ponds using heat pipe heat exchangers

    SciTech Connect (OSTI)

    Tundee, Sura; Terdtoon, Pradit; Sakulchangsatjatai, Phrut; Singh, Randeep; Akbarzadeh, Aliakbar

    2010-09-15

    This paper presents the results of experimental and theoretical analysis on the heat extraction process from solar pond by using the heat pipe heat exchanger. In order to conduct research work, a small scale experimental solar pond with an area of 7.0 m{sup 2} and a depth of 1.5 m was built at Khon Kaen in North-Eastern Thailand (16 27'N102 E). Heat was successfully extracted from the lower convective zone (LCZ) of the solar pond by using a heat pipe heat exchanger made from 60 copper tubes with 21 mm inside diameter and 22 mm outside diameter. The length of the evaporator and condenser section was 800 mm and 200 mm respectively. R134a was used as the heat transfer fluid in the experiment. The theoretical model was formulated for the solar pond heat extraction on the basis of the energy conservation equations and by using the solar radiation data for the above location. Numerical methods were used to solve the modeling equations. In the analysis, the performance of heat exchanger is investigated by varying the velocity of inlet air used to extract heat from the condenser end of the heat pipe heat exchanger (HPHE). Air velocity was found to have a significant influence on the effectiveness of heat pipe heat exchanger. In the present investigation, there was an increase in effectiveness by 43% as the air velocity was decreased from 5 m/s to 1 m/s. The results obtained from the theoretical model showed good agreement with the experimental data. (author)

  8. In-place stabilization of pond ash deposits by hydrated lime columns

    SciTech Connect (OSTI)

    Chand, S.K.; Subbarao, C.

    2007-12-15

    Abandoned coal ash ponds cover up vast stretches of precious land and cause environmental problems. Application of suitable in situ stabilization methods may bring about improvement in the geotechnical properties of the ash deposit as a whole, converting it to a usable site. In this study, a technique of in-place stabilization by hydrated lime columns was applied to large-scale laboratory models of ash ponds. Samples collected from different radial distances and different depths of the ash deposit were tested to study the improvements in the water content, dry density, particle size distribution, unconfined compressive strength, pH, hydraulic conductivity, and leachate characteristics over a period of one year. The in-place stabilization by lime column technique has been found effective in increasing the unconfined compressive strength and reducing hydraulic conductivity of pond ash deposits in addition to modifying other geotechnical parameters. The method has also proved to be useful in reducing the contamination potential of the ash leachates, thus mitigating the adverse environmental effects of ash deposits.

  9. Environmental Problems Associated With Decommissioning The Chernobyl Nuclear Power Plant Cooling Pond

    SciTech Connect (OSTI)

    Farfan, E. B.; Jannik, G. T.; Marra, J. C.; Oskolkov, B. Ya.; Bondarkov, M. D.; Gaschak, S. P.; Maksymenko, A. M.; Maksymenko, V. M.; Martynenko, V. I.

    2009-11-09

    Decommissioning of nuclear power plants and other nuclear fuel cycle facilities has been an imperative issue lately. There exist significant experience and generally accepted recommendations on remediation of lands with residual radioactive contamination; however, there are hardly any such recommendations on remediation of cooling ponds that, in most cases, are fairly large water reservoirs. The literature only describes remediation of minor reservoirs containing radioactive silt (a complete closure followed by preservation) or small water reservoirs resulting in reestablishing natural water flows. Problems associated with remediation of river reservoirs resulting in flooding of vast agricultural areas also have been described. In addition, the severity of environmental and economic problems related to the remedial activities is shown to exceed any potential benefits of these activities. One of the large, highly contaminated water reservoirs that require either remediation or closure is Karachay Lake near the MAYAK Production Association in the Chelyabinsk Region of Russia where liquid radioactive waste had been deep well injected for a long period of time. Backfilling of Karachay Lake is currently in progress. It should be noted that secondary environmental problems associated with its closure are considered to be of less importance since sustaining Karachay Lake would have presented a much higher radiological risk. Another well-known highly contaminated water reservoir is the Chernobyl Nuclear Power Plant (ChNPP) Cooling Pond, decommissioning of which is planned for the near future. This study summarizes the environmental problems associated with the ChNPP Cooling Pond decommissioning.

  10. ENVIRONMENTAL PROBLEMS ASSOCIATED WITH DECOMMISSIONING THE CHERNOBYL NUCLEAR POWER PLANT COOLING POND

    SciTech Connect (OSTI)

    Farfan, E.

    2009-09-30

    Decommissioning of nuclear power plants and other nuclear fuel cycle facilities has been an imperative issue lately. There exist significant experience and generally accepted recommendations on remediation of lands with residual radioactive contamination; however, there are hardly any such recommendations on remediation of cooling ponds that, in most cases, are fairly large water reservoirs. The literature only describes remediation of minor reservoirs containing radioactive silt (a complete closure followed by preservation) or small water reservoirs resulting in reestablishing natural water flows. Problems associated with remediation of river reservoirs resulting in flooding of vast agricultural areas also have been described. In addition, the severity of environmental and economic problems related to the remedial activities is shown to exceed any potential benefits of these activities. One of the large, highly contaminated water reservoirs that require either remediation or closure is Karachay Lake near the MAYAK Production Association in the Chelyabinsk Region of Russia where liquid radioactive waste had been deep well injected for a long period of time. Backfilling of Karachay Lake is currently in progress. It should be noted that secondary environmental problems associated with its closure are considered to be of less importance since sustaining Karachay Lake would have presented a much higher radiological risk. Another well-known highly contaminated water reservoir is the Chernobyl Nuclear Power Plant (ChNPP) Cooling Pond, decommissioning of which is planned for the near future. This study summarizes the environmental problems associated with the ChNPP Cooling Pond decommissioning.

  11. A Screening Model to Predict Microalgae Biomass Growth in Photobioreactors and Raceway Ponds

    SciTech Connect (OSTI)

    Huesemann, Michael H.; Van Wagenen, Jonathan M.; Miller, Tyler W.; Chavis, Aaron R.; Hobbs, Watts B.; Crowe, Braden J.

    2013-06-01

    A microalgae biomass growth model was developed for screening novel strains for their potential to exhibit high biomass productivities under nutrient-replete conditions in photobioreactors or outdoor ponds. Growth is modeled by first estimating the light attenuation by biomass according to Beer-Lamberts law, and then calculating the specific growth rate in discretized culture volume slices that receive declining light intensities due to attenuation. The model requires only two physical and two species-specific biological input parameters, all of which are relatively easy to determine: incident light intensity, culture depth, as well as the biomass light absorption coefficient and the specific growth rate as a function of light intensity. Roux bottle culture experiments were performed with Nannochloropsis salina at constant temperature (23 C) at six different incident light intensities (5, 10, 25, 50, 100, 250, and 850 ?mol/m2? sec) to determine both the specific growth rate under non-shading conditions and the biomass light absorption coefficient as a function of light intensity. The model was successful in predicting the biomass growth rate in these Roux bottle cultures during the light-limited linear phase at different incident light intensities. Model predictions were moderately sensitive to minor variations in the values of input parameters. The model was also successful in predicting the growth performance of Chlorella sp. cultured in LED-lighted 800 L raceway ponds operated at constant temperature (30 C) and constant light intensity (1650 ?mol/m2? sec). Measurements of oxygen concentrations as a function of time demonstrated that following exposure to darkness, it takes at least 5 seconds for cells to initiate dark respiration. As a result, biomass loss due to dark respiration in the aphotic zone of a culture is unlikely to occur in highly mixed small-scale photobioreactors where cells move rapidly in and out of the light. By contrast, as supported also by

  12. Text-Alternative Version: L Prize-PAR 38 Competition: A New Start

    Office of Energy Efficiency and Renewable Energy (EERE)

    Below is the text-alternative version of the "L Prize-PAR 38 Competition: A New Start" webcast, held March 27, 2012.

  13. DOE Publishes CALiPER Report on Chromaticity Shift Modes of LED PAR38 Lamps

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    | Department of Energy Chromaticity Shift Modes of LED PAR38 Lamps DOE Publishes CALiPER Report on Chromaticity Shift Modes of LED PAR38 Lamps March 23, 2016 - 11:33am Addthis The U.S. Department of Energy's CALiPER program has released Report 20.5, which is part of a series of investigations on LED PAR38 lamps. The new report builds on CALiPER Report 20.4 by providing a tear-down analysis of its 32 LED PAR38 lamp models and also performing additional analyses on the spectroradiometric data

  14. 2011 Annual Industrial Wastewater Reuse Report for the Idaho National Laboratory Site's Advanced Test Reactor Complex Cold Waste Pond

    SciTech Connect (OSTI)

    Mike Lewis

    2012-02-01

    This report describes conditions, as required by the state of Idaho Industrial Wastewater Reuse Permit (LA 000161 01, Modification B), for the wastewater land application site at the Idaho National Laboratory Site's Advanced Test Reactor Complex Cold Waste Pond from November 1, 2010 through October 31, 2011. The report contains the following information: Facility and system description Permit required effluent monitoring data and loading rates Groundwater monitoring data Status of compliance activities Noncompliance and other issues Discussion of the facility's environmental impacts During the 2011 permit year, approximately 166 million gallons of wastewater were discharged to the Cold Waste Pond. This is well below the maximum annual permit limit of 375 million gallons. As shown by the groundwater sampling data, sulfate and total dissolved solids concentrations are highest near the Cold Waste Pond and decrease rapidly as the distance from the Cold Waste Pond increases. Although concentrations of sulfate and total dissolved solids are elevated near the Cold Waste Pond, both parameters were below the Ground Water Quality Rule Secondary Constituent Standards in the down gradient monitoring wells.

  15. 2012 Annual Industrial Wastewater Reuse Report for the Idaho National Laboratory Site's Advanced Test Reactor Complex Cold Waste Pond

    SciTech Connect (OSTI)

    Mike Lewis

    2013-02-01

    This report describes conditions, as required by the state of Idaho Industrial Wastewater Reuse Permit (#LA 000161 01, Modification B), for the wastewater land application site at the Idaho National Laboratory Site’s Advanced Test Reactor Complex Cold Waste Pond from November 1, 2011 through October 31, 2012. The report contains the following information: Facility and system description Permit required effluent monitoring data and loading rates Groundwater monitoring data Status of compliance activities Noncompliance issues Discussion of the facility’s environmental impacts During the 2012 permit year, approximately 183 million gallons of wastewater were discharged to the Cold Waste Pond. This is well below the maximum annual permit limit of 375 million gallons. As shown by the groundwater sampling data, sulfate and total dissolved solids concentrations are highest near the Cold Waste Pond and decrease rapidly as the distance from the Cold Waste Pond increases. Although concentrations of sulfate and total dissolved solids are elevated near the Cold Waste Pond, both parameters were below the Ground Water Quality Rule Secondary Constituent Standards in the down gradient monitoring wells.

  16. Novel Adsorbent-Reactants for Treatment of Ash and Scrubber Pond Effluents

    SciTech Connect (OSTI)

    Bill Batchelor; Dong Suk Han; Eun Jung Kim

    2010-01-31

    The overall goal of this project was to evaluate the ability of novel adsorbent/reactants to remove specific toxic target chemicals from ash and scrubber pond effluents while producing stable residuals for ultimate disposal. The target chemicals studied were arsenic (As(III) and As(V)), mercury (Hg(II)) and selenium (Se(IV) and Se(VI)). The adsorbent/reactants that were evaluated are iron sulfide (FeS) and pyrite (FeS{sub 2}). Procedures for measuring concentrations of target compounds and characterizing the surfaces of adsorbent-reactants were developed. Effects of contact time, pH (7, 8, 9, 10) and sulfate concentration (0, 1, 10 mM) on removal of all target compounds on both adsorbent-reactants were determined. Stability tests were conducted to evaluate the extent to which target compounds were released from the adsorbent-reactants when pH changed. Surface characterization was conducted with x-ray photoelectron spectroscopy (XPS) to identify reactions occurring on the surface between the target compounds and surface iron and sulfur. Results indicated that target compounds could be removed by FeS{sub 2} and FeS and that removal was affected by time, pH and surface reactions. Stability of residuals was generally good and appeared to be affected by the extent of surface reactions. Synthesized pyrite and mackinawite appear to have the required characteristics for removing the target compounds from wastewaters from ash ponds and scrubber ponds and producing stable residuals.

  17. AmeriFlux US-Tw1 Twitchell Wetland West Pond

    DOE Data Explorer [Office of Scientific and Technical Information (OSTI)]

    Baldocchi, Dennis [University of California, Berkeley

    2016-01-01

    This is the AmeriFlux version of the carbon flux data for the site US-Tw1 Twitchell Wetland West Pond. Site Description - The Twitchell Wetland site is a 7.4-acre restored wetland on Twitchell Island, that is managed by the California Department of Water Resources (DWR) and the U.S. Geological Survey (USGS). In the fall of 1997, the site was permanently flooded to a depth of approximately 25 cm. The wetland was almost completely covered by cattails and tules by the third growing season. A flux tower equipped to analyze energy, H2O, CO2, and CH4 fluxes was installed on May 17, 2012.

  18. Development of baseline water quality stormwater detention pond model for Chesapeake Bay catchments

    SciTech Connect (OSTI)

    Musico, W.J.; Yoon, J.

    1999-07-01

    An environmental impact assessment is required for every proposed development in the Commonwealth of Virginia to help identify areas of potential concerns. The purpose of the Chesapeake Bay Local Assistance Department (CBLAD), Guidance Calculation Procedures is to ensure that development of previously constructed areas do not further exacerbate current problems of stormwater-induced eutrophication and downstream flooding. The methodology is based on the post development conditions that will not generate greater peak flows and will result in a 10% overall reduction of total phosphorus. Currently, several well-known models can develop hydrographs and pollutographs that accurately model the real response of a given watershed to any given rainfall event. However, conventional method of achieving the desired peak flow reduction and pollutant removal is not a deterministic procedure, and is inherently a trail and error process. A method of quickly and accurately determining the required size of stormwater easements was developed to evaluate the effectiveness of alternative stormwater collection and treatment systems. In this method, predevelopment conditions were modeled first to estimate the peak flows and subsequent pollutants generation that can be used as a baseline for post development plan. Resulting stormwater easement estimates facilitate decision-making processes during the planning and development phase of a project. The design can be optimized for the minimum cost or the smallest-possible pond size required for peak flow reduction and detention time given the most basic data such as: inflow hydrograph and maximum allowable pond depth.

  19. Deep subsurface life from North Pond: Enrichment, isolation, characterization and genomes of heterotrophic bacteria

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Russell, Joseph A.; Leon-Zayas, Rosa; Wrighton, Kelly; Biddle, Jennifer F.

    2016-05-10

    Studies of subsurface microorganisms have yielded few environmentally relevant isolates for laboratory studies. In order to address this lack of cultivated microorganisms, we initiated several enrichments on sediment and underlying basalt samples from North Pond, a sediment basin ringed by basalt outcrops underlying an oligotrophic watercolumn west of the Mid-Atlantic Ridge at 22° N. In contrast to anoxic enrichments, growth was observed in aerobic, heterotrophic enrichments from sediment of IODP Hole U1382B at 4 and 68 m below seafloor (mbsf). These sediment depths, respectively, correspond to the fringes of oxygen penetration from overlying seawater in the top of the sedimentmore » column and upward migration of oxygen from oxic seawater from the basalt aquifer below the sediment. Here we report the enrichment, isolation, initial characterization and genomes of three isolated aerobic heterotrophs from North Pond sediments; an Arthrobacter species from 4 mbsf, and Paracoccus and Pseudomonas species from 68 mbsf. These cultivated bacteria are represented in the amplicon 16S rRNA gene libraries created from whole sediments, albeit at low (up to 2%) relative abundance. We provide genomic evidence from our isolates demonstrating that the Arthrobacter and Pseudomonas isolates have the potential to respire nitrate and oxygen, though dissimilatory nitrate reduction could not be confirmed in laboratory cultures. Furthermore, the cultures from this study represent members of abundant phyla, as determined by amplicon sequencing of environmental DNA extracts, and allow for further studies into geochemical factors impacting life in the deep subsurface.« less

  20. Sampling and analysis plan for the 100-D Ponds voluntary remediation project

    SciTech Connect (OSTI)

    NONE

    1996-08-01

    This Sampling and Analysis Plan (SAP) describes the sampling and analytical activities which will be performed to support closure of the 100-D Ponds Resource Conservation and Recovery Act (RCRA) treatment, storage, and/or disposal (TSD) unit. This SAP includes the Field Sampling Plan (FSP) presented in Section 2.0, and the Quality Assurance Project Plan (QAPjP) described in Section 3.0. The FSP defines the sampling and analytical methodologies to be performed, and the QAPjP provides or includes information on the requirements for precision, accuracy, representativeness, comparability, and completeness of the analytical data. This sampling and analysis plan was developed using the Environmental Protection Agency`s Seven-Step Data Quality Objectives (DQO) Guidance (EPA, 1994). The purpose of the DQO meetings was (1) to identify the contaminants of concern and their cleanup levels under the Washington State Model Toxics Control Act (MTCA, WAC-173-340) Method B, and (2) to determine the number and locations of samples necessary to verify that the 100-D Ponds meet the cleanup criteria. The data collected will be used to support RCRA closure of this TSD unit.

  1. Phase structure within a fracture network beneath a surface pond: Field experiment

    SciTech Connect (OSTI)

    GLASS JR.,ROBERT J.; NICHOLL,M.J.

    2000-05-09

    The authors performed a simple experiment to elucidate phase structure within a pervasively fractured welded tuff. Dyed water was infiltrated from a surface pond over a 36 minute period while a geophysical array monitored the wetted region within vertical planes directly beneath. They then excavated the rock mass to a depth of {approximately}5 m and mapped the fracture network and extent of dye staining in a series of horizontal pavements. Near the pond the network was fully stained. Below, the phase structure immediately expanded and with depth, the structure became fragmented and complicated exhibiting evidence of preferential flow, fingers, irregular wetting patterns, and varied behavior at fracture intersections. Limited transient geophysical data suggested that strong vertical pathways form first followed by increased horizontal expansion and connection within the network. These rapid pathways are also the first to drain. Estimates also suggest that the excavation captured from {approximately}10% to 1% or less of the volume of rock interrogated by the infiltration slug and thus the penetration depth could have been quite large.

  2. Thrombin induces rapid PAR1-mediated non-classical FGF1 release

    SciTech Connect (OSTI)

    Duarte, Maria; Kolev, Vihren; Soldi, Raffaella; Kirov, Alexander; Graziani, Irene; Oliveira, Silvia Marta; Kacer, Doreen; Friesel, Robert; Maciag, Thomas; Prudovsky, Igor . E-mail: prudoi@mmc.org

    2006-11-24

    Thrombin induces cell proliferation and migration during vascular injury. We report that thrombin rapidly stimulated expression and release of the pro-angiogenic polypeptide fibroblast growth factor 1 (FGF1). Thrombin failed to induce FGF1 release from protease-activated receptor 1 (PAR1) null fibroblasts, indicating that this effect was dependent on PAR1. Similarly to thrombin, FGF1 expression and release were induced by TRAP, a specific oligopeptide agonist of PAR1. These results identify a novel aspect of the crosstalk between FGF and thrombin signaling pathways which both play important roles in tissue repair and angiogenesis.

  3. Report 20.5: Chromaticity Shift Modes of LED PAR38 Lamps Operated in

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Steady-State Conditions | Department of Energy 0.5: Chromaticity Shift Modes of LED PAR38 Lamps Operated in Steady-State Conditions Report 20.5: Chromaticity Shift Modes of LED PAR38 Lamps Operated in Steady-State Conditions Report 20.5: Chromaticity Shift Modes of LED PAR38 Lamps Operated in Steady-State Conditions (8.45 MB) More Documents & Publications MARCH 2016 POSTINGS Retail Lamps Study 3.2: Lumen and Chromaticity Maintenance of LED A Lamps Operated in Steady-State Conditions

  4. Corrective Action Investigation Plan for Corrective Action Unit 552: Area 12 Muckpile and Ponds, Nevada Test Site, Nevada: Revision 0

    SciTech Connect (OSTI)

    U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office

    2004-04-06

    This Corrective Action Investigation Plan contains the U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office's approach for collecting the data necessary to evaluate corrective action alternatives appropriate for the closure of Corrective Action Unit (CAU) 552: Area 12 Muckpile and Ponds, Nevada Test Site (NTS), Nevada, under the Federal Facility Agreement and Consent Order. Located in Area 12 on the NTS, CAU 552 consists of two Corrective Action Sites (CASs): 12-06-04, Muckpile; 12-23-05, Ponds. Corrective Action Site 12-06-04 in Area 12 consists of the G-Tunnel muckpile, which is the result of tunneling activities. Corrective Action Site 12-23-05 consists of three dry ponds adjacent to the muckpile. The toe of the muckpile extends into one of the ponds creating an overlap of two CASs. The purpose of the investigation is to ensure that adequate data are collected to provide sufficient and reliable information to identify, evaluate, and select technic ally viable corrective actions. The results of the field investigation will support a defensible evaluation of corrective action alternatives in the corrective action decision document.

  5. Post-Closure Groundwater Monitoring Plan for the 1324-N Surface Impoundment and 1324-NA Percolation Pond

    SciTech Connect (OSTI)

    Hartman, Mary J.

    2004-04-02

    The 1324-N Surface Impoundment and the 1324-NA Percolation Pond, located in the 100-N Area of the Hanford Site, are regulated under the Resource Consevation and Recovery Act (RCRA). Surface and underground features of the facilities have been removed and laboratory analyses showed that soil met the closure performance standards. These sites have been backfilled and revegetated.

  6. Resistance and resilience of pond and stream ecosystems to toxicant stress: Project summary

    SciTech Connect (OSTI)

    Boston, H.L.; Stewart, A.J.; Johnson, A.R.; Bartell, S.M.

    1987-01-01

    This project will evaluate hypotheses concerning the resistance and resilience of aquatic ecosystems exposed to toxic chemicals. Our goals are to develop diagnostic criteria for ecosystem classification and to improve existing methods of ecological risk estimation. The development of models that predict ecosystem level effects requires quantifying the relationships between the underlying control structure of ecosystems (patterns of energy and material flux) and the contributions of thos structures to ecosystem resistance and resilience. We address these problems through an integration of manipulative experiments, multidimensional state space analysis, and ecosystem modeling. These studies will quantify the underlying rate structure in pond and stream systems (including, production, herbivory, nutrient uptake and recycling) and will measure changes in their structures in response to perturbations by toxicants.

  7. Post-Closure RCRA Groundwater Monitoring Plan for the 216-S-10 Pond and Ditch

    SciTech Connect (OSTI)

    Barnett, D BRENT.; Williams, Bruce A.; Chou, Charissa J.; Hartman, Mary J.

    2006-03-17

    The purpose of this plan is to provide a post-closure groundwater monitoring program for the 216-S-10 Pond and Ditch (S-10) treatment, storage, and/or disposal (TSD) unit. The plan incorporates the sum of knowledge about the potential for groundwater contamination to originate from the S-10, including groundwater monitoring results, hydrogeology, and operational history. The S-10 has not received liquid waste since October 1991. The closure of S-10 has been coordinated with the 200-CS-1 source operable unit in accordance with the Tri-Party Agreement interim milestones M-20-39 and M-15-39C. The S-10 is closely situated among other waste sites of very similar operational histories. The proximity of the S-10 to the other facilities (216-S-17 pond, 216-S-11 Pond, 216-S-5,6 cribs, 216-S-16 ditch and pond, and 216-U-9 ditch) indicate that at least some observed groundwater contamination beneath and downgradient of S-10 could have originated from waste sites other than S-10. Hence, it may not be feasible to strictly discriminate between the contributions of each waste site to groundwater contamination beneath the S-10. A post-closure groundwater monitoring network is proposed that will include the drilling of three new wells to replace wells that have gone dry. When completed, the revised network will meet the intent for groundwater monitoring network under WAC 173-303-645, and enable an improved understanding of groundwater contamination at the S-10. Site-specific sampling constituents are based on the dangerous waste constituents of concern relating to RCRA TSD unit operations (TSD unit constituents) identified in the Part A Permit Application. Thus, a constituent is selected for monitoring if it is: A dangerous waste constituent identified in the Part A Permit Application, or A mobile decomposition product (i.e., nitrate from nitrite) of a Part A constituent, or A reliable indicator of the site-specific contaminants (i.e., specific conductance). Using these criteria

  8. CALiPER Report 20.5: Chromaticity Shift Modes of LED PAR38 Lamps...

    Energy Savers [EERE]

    ... Report 20.2: Dimming, Flicker, and Power Quality Characteristics of LED PAR38 Lamps (March 2014) 9 This report focused on the flicker and power quality performance of the Series 20 ...

  9. DOE Publishes CALiPER Report on Lumen and Chromaticity Maintenance of LED PAR38 Lamps

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy's CALiPER program has released Report 20.4, which is part of a series of investigations on LED PAR38 lamps. Report 20.4 focuses on lumen maintenance, chromaticity...

  10. DOE Publishes New CALiPER Report on Subjective Evaluation of LED PAR38 Lamps

    Broader source: Energy.gov [DOE]

    DOE has published the first in a series of four special investigations intended to extend the findings of CALiPER Application Summary Report 20: LED PAR38 Lamps, which was published late last year.

  11. Western Pond Turtle Head-starting and Reintroduction; 2002-2003 Progress Report.

    SciTech Connect (OSTI)

    Van Leuven, Susan; Allen, Harriet; Slavin, Kate

    2004-02-01

    This report covers the results of the western pond turtle head-starting and reintroduction project for the period of June 2002-September 2003. Wild hatchling western pond turtles from the Columbia River Gorge were reared at the Woodland Park and Oregon Zoos in 2002 and 2003 as part of the recovery effort for this Washington State endangered species. The objective of the program is to reduce losses to introduced predators like bullfrogs and largemouth bass by raising the hatchlings to a size where they are too large to be eaten by most of these predators. In 2002, 27 females from the two Columbia Gorge populations were equipped with transmitters and monitored until they nested. Four more females carrying old transmitters were also monitored; only one of these transmitters lasted through the nesting season. In 2003, 30 females were monitored. Twenty-three of the females monitored in 2002 nested and produced 84 hatchlings. The hatchlings were collected in fall 2002 and reared in captivity at the Woodland Park and Oregon zoos in the head-start program. Twenty-seven of the turtles monitored in 2003 nested. Six of the turtles nested twice, producing a total of 33 nests. The nests will be checked in September and October 2003 for hatchlings. Of 121 head-started juvenile western pond turtles collected in the Columbia Gorge during the 2001 nesting season, 119 were released at three sites in the Columbia Gorge in 2002, and 2 held over for additional growth. Of 86 turtles reared in the head-start program at the Woodland Park and Oregon Zoos fall 2002 through summer 2003, 67 were released at sites in the Columbia Gorge in summer of 2003, and 15 held over for more growth. Fifty-nine juveniles were released at Pierce National Wildlife Refuge in July 2002, and 51 released there in July 2003. Sixteen of those released in 2002 and 16 released in 2003 were instrumented with radio transmitters and monitored for varying amounts of time for survival and habitat use between the time of

  12. Radiological Control of Water in Reactor Pond of MR Reactor in NRC 'Kurchatov Institute', During Dismantling Work - 13462

    SciTech Connect (OSTI)

    Stepanov, Alexey; Simirsky, Yury; Semin, Ilya; Volkovich, Anatoly; Ivanov, Oleg

    2013-07-01

    The analysis of the activity and radionuclide composition of water from the MR reactor pond for α,β,γ-ray radionuclides was made. To solve this problem we use a wide range of laboratory equipment: gamma spectrometric complex, beta spectrometric complex, vacuum alpha spectrometer, and spectrometric complex with liquid scintillator. The water from MR reactor pond contains: Cs-137 (2,6*10{sup 2} Bq/g), Co-60(1,8 Bq/g), Sr-90 (1,0*10{sup 2} Bq/g), H-3 (7,0*10{sup 3} Bq/g), and components of nuclear fuel (U-232,U-234,U-235,U-236,U-238). Therefore the cleaning water from radioactivity waste occurs to be quite a complicated radiochemical task. (authors)

  13. Internal waves and K-H instability in thermal layers of the advanced solar pond (ASP). [Kelvin-Helmholtz

    SciTech Connect (OSTI)

    Bemporad, G.A.; Rubin, H. )

    1991-01-01

    The development of internal waves and instabilities of the Kelvin Helmholtz-type may prevent the density gradient maintenance which allows the proper functioning of the Advanced Solar Pond (ASP). The properties and characteristics of internal waves, of constant and growing amplitude, are quantitatively described in this paper. The numerical simulations made in this study are in good agreement with previous theoretical and experimental results.

  14. Borehole data package for the 216-S-10 pond and ditch well 299-W26-13

    SciTech Connect (OSTI)

    DG Horton; BA Williams; CS Cearlock

    2000-06-01

    One new Resource Conservation and Recovery Act (RCRA) groundwater monitoring well was installed at the 216-S-10 pond and ditch during November and December 1999 in fulfillment of Tri-Party Agreement (Ecology 1996) milestone M-24-42. The well is 299-W26-13 and is located at the northeast comer to the 216-S-10 pond, southwest of 200 West Area. The well is a new downgradient well in the monitoring network. A figure shows the locations of all wells in the 216-S-10 pond and ditch monitoring network. The new well was constructed to the specifications and requirements described in Washington Administrative Code (WAC) 173-160 and WAC 173-303, the groundwater monitoring plan for the 216-S-10 pond and ditch (Airhart et al. 1990), and the description of work for well drilling and installation. During drilling and construction of well 299-W26-13, sampling and analysis activities were done to support remedial action, closure decisions at treatment, storage and disposal facilities, and to confirm preliminary site conceptual models developed in the 200-CS-1 Work Plan (DOE/RL 1999). This document compiles information on the drilling and construction, well development, pump installation, and sediment and groundwater testing applicable to well 299-W26-13. Appendix A contains the Well Summary Sheet (as-built diagram), the Well Construction Summary Report, and the geologist's log. Appendix B contains results of field and laboratory determinations of physical and chemical properties of sediment samples. Appendix C contains borehole geophysical logs. Additional documentation concerning well construction is on file with Bechtel Hanford, Inc., Richland, Washington.

  15. Towards an improved LAI collection protocol via simulated field-based PAR sensing

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Yao, Wei; Van Leeuwen, Martin; Romanczyk, Paul; van Aardt, Jan; Kelbe, David

    2016-07-14

    In support of NASA’s next-generation spectrometer—the Hyperspectral Infrared Imager (HyspIRI)—we are working towards assessing sub-pixel vegetation structure from imaging spectroscopy data. Of particular interest is Leaf Area Index (LAI), which is an informative, yet notoriously challenging parameter to efficiently measure in situ. While photosynthetically-active radiation (PAR) sensors have been validated for measuring crop LAI, there is limited literature on the efficacy of PAR-based LAI measurement in the forest environment. This study (i) validates PAR-based LAI measurement in forest environments, and (ii) proposes a suitable collection protocol, which balances efficiency with measurement variation, e.g., due to sun flecks and various-sized canopymore » gaps. A synthetic PAR sensor model was developed in the Digital Imaging and Remote Sensing Image Generation (DIRSIG) model and used to validate LAI measurement based on first-principles and explicitly-known leaf geometry. Simulated collection parameters were adjusted to empirically identify optimal collection protocols. Furthermore, these collection protocols were then validated in the field by correlating PAR-based LAI measurement to the normalized difference vegetation index (NDVI) extracted from the “classic” Airborne Visible Infrared Imaging Spectrometer (AVIRIS-C) data (R2 was 0.61). The results indicate that our proposed collecting protocol is suitable for measuring the LAI of sparse forest (LAI < 3–5 ( m2/m2)).« less

  16. Area 6 Decontamination Pond Corrective Action Unit 92 Post-Closure Inspection Annual Report for the Period January 2000-December 2000

    SciTech Connect (OSTI)

    J. L. Traynor

    2001-03-01

    The Area 6 Decontamination Pond, Corrective Action Unit 92, was closed in accordance with the Resource Conservation and Recovery Act (RCRA) Part B Operational Permit (Nevada Division of Environmental Protection [NDEP, 1995]) and the Federal Facility Agreement and Consent Order (NDEP, 1996) on May 11, 1999. Historically the Decontamination Pond was used for the disposal of partially treated liquid effluent discharged from the Decontamination Facility (Building 6-05) and the Industrial Laundry (Building 6-07) (U.S. Department of Energy, Nevada Operations Office [DOE/NV], 1996). The Decontamination Pond was constructed and became operational in 1979. Releases of RCRA-regulated hazardous waste or hazardous waste constituents have not been discharged to the Decontamination Pond since 1988 (DOE/NV, 1996). The pipe connecting the Decontamination Pond and Decontamination Facility and Industrial Laundry were cut and sealed at the Decontamination Pad Oil/Water Separator in 1992. The Decontamination Pond was closed in place by installing a RCRA cover. Fencing was installed around the periphery to prevent accidental damage to the cover. Post-closure monitoring at the site consists of quarterly inspections of the RCRA cover and fencing, and a subsidence survey. Additional inspections are conducted if: Precipitation occurs in excess of 1.28 centimeters (cm) (0.50 inches [in]) in a 24-hour period, or An earthquake occurs with a magnitude exceeding 4.5 on the Richter scale within 100 kilometers (km) (62 miles [mi]) of the closure.

  17. A validated model to predict microalgae growth in outdoor pond cultures subjected to fluctuating light intensities and water temperatures

    SciTech Connect (OSTI)

    Huesemann, Michael H.; Crowe, Braden J.; Waller, Peter; Chavis, Aaron R.; Hobbs, Samuel J.; Edmundson, Scott J.; Wigmosta, Mark S.

    2015-12-11

    Here, a microalgae biomass growth model was developed for screening novel strains for their potential to exhibit high biomass productivities under nutrient-replete conditions in outdoor ponds subjected to fluctuating light intensities and water temperatures. Growth is modeled by first estimating the light attenuation by biomass according to a scatter-corrected Beer-Lambert Law, and then calculating the specific growth rate in discretized culture volume slices that receive declining light intensities due to attenuation. The model requires the following experimentally determined strain-specific input parameters: specific growth rate as a function of light intensity and temperature, biomass loss rate in the dark as a function of temperature and average light intensity during the preceding light period, and the scatter-corrected biomass light absorption coefficient. The model was successful in predicting the growth performance and biomass productivity of three different microalgae species (Chlorella sorokiniana, Nannochloropsis salina, and Picochlorum sp.) in raceway pond cultures (batch and semi-continuous) subjected to diurnal sunlight intensity and water temperature variations. Model predictions were moderately sensitive to minor deviations in input parameters. To increase the predictive power of this and other microalgae biomass growth models, a better understanding of the effects of mixing-induced rapid light dark cycles on photo-inhibition and short-term biomass losses due to dark respiration in the aphotic zone of the pond is needed.

  18. A validated model to predict microalgae growth in outdoor pond cultures subjected to fluctuating light intensities and water temperatures

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Huesemann, Michael H.; Crowe, Braden J.; Waller, Peter; Chavis, Aaron R.; Hobbs, Samuel J.; Edmundson, Scott J.; Wigmosta, Mark S.

    2015-12-11

    Here, a microalgae biomass growth model was developed for screening novel strains for their potential to exhibit high biomass productivities under nutrient-replete conditions in outdoor ponds subjected to fluctuating light intensities and water temperatures. Growth is modeled by first estimating the light attenuation by biomass according to a scatter-corrected Beer-Lambert Law, and then calculating the specific growth rate in discretized culture volume slices that receive declining light intensities due to attenuation. The model requires the following experimentally determined strain-specific input parameters: specific growth rate as a function of light intensity and temperature, biomass loss rate in the dark as amore » function of temperature and average light intensity during the preceding light period, and the scatter-corrected biomass light absorption coefficient. The model was successful in predicting the growth performance and biomass productivity of three different microalgae species (Chlorella sorokiniana, Nannochloropsis salina, and Picochlorum sp.) in raceway pond cultures (batch and semi-continuous) subjected to diurnal sunlight intensity and water temperature variations. Model predictions were moderately sensitive to minor deviations in input parameters. To increase the predictive power of this and other microalgae biomass growth models, a better understanding of the effects of mixing-induced rapid light dark cycles on photo-inhibition and short-term biomass losses due to dark respiration in the aphotic zone of the pond is needed.« less

  19. Fractionation of heavy metals in sludge from anaerobic wastewater stabilization ponds in southern Spain

    SciTech Connect (OSTI)

    Alonso, E.

    2006-07-01

    The analysis of heavy metals is a very important task to assess the potential environmental and health risk associated with the sludge coming from wastewater treatment plants (WWTPs). However, it is necessary to apply sequential extraction techniques to obtain suitable information about their bioavailability or toxicity. In this paper, a sequential extraction scheme according to the Standard, Measurements and Testing Programme of the European Commission was applied to sludge samples collected from ten anaerobic wastewater stabilization ponds (WSPs) located in southern Spain. Al, Cd, Co, Cr, Cu, Fe, Hg, Mn, Mo, Ni, Pb, Ti and Zn were determined in the sludge extracts by inductively coupled plasma atomic emission spectrometry. In relation to current international legislation for the use of sludge for agricultural purposes, none of the metal concentrations exceeded maximum permitted levels. Overall, heavy metals were mainly associated with the two less-available fractions (34% oxidizable metal and 55% residual metal). Only Mn and Zn showed the highest share of the available (exchangeable and reducible) fractions (25-48%)

  20. CALiPER Report 20.3: Robustness of LED PAR38 Lamps

    SciTech Connect (OSTI)

    none,

    2014-12-30

    A small sample of each of the CALiPER Application Summary Report 20 PAR38 lamp types underwent stress testing that included substantial temperature and humidity changes, electrical variation, and vibration. The results do not directly address expected lifetime, but can be compared with one another, as well as with benchmark conventional products, to assess the relative robustness of the product designs.

  1. Report 20.3: Stress Testing of LED PAR38 Lamps

    Broader source: Energy.gov [DOE]

    A small sample of each of the Application Summary Report 20 PAR38 lamp types underwent stress testing that included substantial temperature and humidity changes, electrical variation, and vibration. The results do not directly address expected lifetime, but can be compared with one another, as well as with benchmark conventional products, to assess the relative robustness of the product designs. (24 pages, December 2014)

  2. Project Plan 7930 Cell G PaR Remote Handling System Replacement

    SciTech Connect (OSTI)

    Kinney, Kathryn A

    2009-10-01

    For over 40 years the US Department of Energy (DOE) and its predecessors have made Californium-252 ({sup 252}Cf) available for a wide range of industries including medical, nuclear fuels, mining, military and national security. The Radiochemical Engineering Development Center (REDC) located within the Oak Ridge National Laboratory (ORNL) processes irradiated production targets from the High Flux Isotope Reactor (HFIR). Operations in Building 7930, Cell G provide over 70% of the world's demand for {sup 252}Cf. Building 7930 was constructed and equipped in the mid-1960s. Current operations for {sup 252}Cf processing in Building 7930, Cell G require use of through-the-wall manipulators and the PaR Remote Handling System. Maintenance and repairs for the manipulators is readily accomplished by removal of the manipulator and relocation to a repair shop where hands-on work can be performed in glove boxes. Contamination inside cell G does not currently allow manned entry and no provisions were created for a maintenance area inside the cell. There has been no maintenance of the PaR system or upgrades, leaving operations vulnerable should the system have a catastrophic failure. The Cell G PaR system is currently being operated in a run to failure mode. As the manipulator is now 40+ years old there is significant risk in this method of operation. In 2006 an assessment was completed that resulted in recommendations for replacing the manipulator operator control and power centers which are used to control and power the PaR manipulator in Cell G. In mid-2008 the chain for the bridge drive failed and subsequent examinations indicated several damaged links (see Figure 1). To continue operations the PaR manipulator arm is being used to push and pull the bridge as a workaround. A retrieval tool was fabricated, tested and staged inside Cell G that will allow positioning of the bridge and manipulator arm for removal from the cell should the PaR system completely fail. A fully

  3. 2013 Annual Industrial Wastewater Reuse Report for the Idaho National Laboratory Site’s Advanced Test Reactor Complex Cold Waste Pond

    SciTech Connect (OSTI)

    Mike Lewis

    2014-02-01

    This report describes conditions, as required by the state of Idaho Industrial Wastewater Reuse Permit (#LA 000161 01, Modification B), for the wastewater land application site at the Idaho National Laboratory Site’s Advanced Test Reactor Complex Cold Waste Pond from November 1, 2012–October 31, 2013. The report contains the following information: • Facility and system description • Permit required effluent monitoring data and loading rates • Groundwater monitoring data • Status of compliance activities • Noncompliance issues • Discussion of the facility’s environmental impacts. During the 2013 permit year, approximately 238 million gallons of wastewater was discharged to the Cold Waste Pond. This is well below the maximum annual permit limit of 375 million gallons. As shown by the groundwater sampling data, sulfate and total dissolved solids concentrations are highest near the Cold Waste Pond and decrease rapidly as the distance from the Cold Waste Pond increases. Although concentrations of sulfate and total dissolved solids are elevated near the Cold Waste Pond, both parameters are below the Ground Water Quality Rule Secondary Constituent Standards in the down gradient monitoring wells.

  4. 2010 Annual Industrial Wastewater Reuse Report for the Idaho National Laboratory Site’s Advanced Test Reactor Complex Cold Waste Pond

    SciTech Connect (OSTI)

    mike lewis

    2011-02-01

    This report describes conditions, as required by the state of Idaho Industrial Wastewater Reuse Permit (#LA 000161 01, Modification B), for the wastewater land application site at the Idaho National Laboratory Site’s Advanced Test Reactor Complex Cold Waste Pond from November 1, 2009 through October 31, 2010. The report contains the following information: • Facility and system description • Permit required effluent monitoring data and loading rates • Groundwater monitoring data • Status of compliance activities • Discussion of the facility’s environmental impacts During the 2010 permit year, approximately 164 million gallons of wastewater were discharged to the Cold Waste Pond. As shown by the groundwater sampling data, sulfate and total dissolved solids concentrations are highest near the Cold Waste Pond and decrease rapidly as the distance from the Cold Waste Pond increases. Although concentrations of sulfate and total dissolved solids are elevated near the Cold Waste Pond, both parameters were below the Ground Water Quality Rule Secondary Constituent Standards in the down gradient monitoring wells.

  5. 2014 Annual Industrial Wastewater Reuse Report for the Idaho National Laboratory Site’s Advanced Test Reactor Complex Cold Waste Pond

    SciTech Connect (OSTI)

    Lewis, Mike

    2015-02-01

    This report describes conditions, as required by the state of Idaho Industrial Wastewater Reuse Permit (LA 000161 01, Modification B), for the wastewater land application site at the Idaho National Laboratory Site’s Advanced Test Reactor Complex Cold Waste Pond from November 1, 2013–October 31, 2014. The report contains the following information; Facility and system description; Permit required effluent monitoring data and loading rates; Permit required groundwater monitoring data; Status of compliance activities; Noncompliance issues; and Discussion of the facility’s environmental impacts. During the 2014 permit year, approximately 238 million gallons of wastewater were discharged to the Cold Waste Pond. This is well below the maximum annual permit limit of 375 million gallons. As shown by the groundwater sampling data, sulfate and total dissolved solids concentrations are highest near the Cold Waste Pond and decrease rapidly as the distance from the Cold Waste Pond increases. Although concentrations of sulfate and total dissolved solids are elevated near the Cold Waste Pond, both parameters are below the Ground Water Quality Rule Secondary Constituent Standards in the downgradient monitoring wells.

  6. Resource Conservation and Recovery Act industrial site environmental restoration site characterization report - area 6 steam cleaning effluent ponds

    SciTech Connect (OSTI)

    1996-09-01

    The Area 6 North and South Steam Cleaning Effluent Ponds (SCEPs) are historic disposal units located at the Nevada Test Site (NTS) in Nye County, Nevada. The NTS is operated by the U.S. Department of Energy, Nevada Operations Office (DOE/NV) which has been required by the Nevada Division of Environmental Protection (NDEP) to characterize the site under the requirements of the Resource Conservation and Recovery Act (RCRA) Part B Permit for the NTS and Title 40 Code of Federal Regulations, Part 265.

  7. A rational approach for evaluation and screening of treatment and disposal options for the solar pond sludges at Rocky Flats

    SciTech Connect (OSTI)

    Dickerson, K.S.

    1995-12-31

    This document consists of information about the treatment options for the sludge that is located in the evaporation ponds at the Rocky Flats Plant. The sludges are mixed low-level radioactive wastes whose composition and character were variable. Sludges similar to these are typically treated prior to ultimate disposal. Disposal of treated sludges includes both on-site and off-site options. The rational approach described in this paper is useful for technology evaluation and screening because it provides a format for developing objectives, listing alternatives, and weighing the alternatives against the objectives and against each other.

  8. Environmental Assessment and Finding of No Significant Impact: Pond B Dam Repair Project at the Savannah River Site

    SciTech Connect (OSTI)

    N /A

    1999-09-27

    The Department of Energy (DOE) has prepared an environmental assessment (EA) (DOE/EA-1285) for the proposed repair of the Pond B dam at the Savannah River Site (SRS), located near Aiken, South Carolina. Based on the analyses in the EA, DOE has determined that the proposed action is not a major Federal action significantly affecting the quality of the human environment within the meaning of the National Environmental Policy Act of 1969 (NEPA). Therefore, the preparation of an environmental impact statement (EIS) is not required, and DOE is issuing this Finding of No Significant Impact (FONSI) and Floodplain Statement of Findings.

  9. Post-closure permit application for the Upper East Fork Poplar Creek hydrogeologic regime at the Y-12 Plant: New Hope Pond and Eastern S-3 ponds plume. Revision 2

    SciTech Connect (OSTI)

    1995-02-01

    The intent of this Post-Closure, Permit Application (PCPA) is to satisfy the post-closure permitting requirements of the Tennessee Department of Environment and Conservation (TDEC) Rule 1200-1-11. This application is for the entire Upper East Fork Poplar Creek Hydrogeologic Regime (East Fork Regime), which is within the Bear Creek Valley (BCV). This PCPA has been prepared to include the entire East Fork Regime because, although there are numerous contaminant sources within the regime, the contaminant plumes throughout the East Fork Regime have coalesced and can no longer be distinguished as separate plumes. This PCPA focuses on two recognized Resource Conservation and Recovery Act (RCRA) interim status units: New Hope Pond (NHP) and the eastern S-3 Ponds plume. This PCPA presents data from groundwater assessment monitoring throughout the regime, performed since 1986. Using this data, this PCPA demonstrates that NHP is not a statistically discernible source of groundwater contaminants and that sites upgradient of NHP are the likely sources of groundwater contamination seen in the NHP vicinity. As such, this PCPA proposes a detection monitoring program to replace the current assessment monitoring program for NHP.

  10. Resource Conservation and Recovery Act corrective measures study: Area 6 decontamination pond facility, corrective action unit no. 92

    SciTech Connect (OSTI)

    1997-10-01

    Corrective Action Unit (CAU) No. 92, the Area 6 Decontamination Pond Facility (DPF), is an historic disposal unit located at the Nevada Test Site (NTS) in Nye County, Nevada (Figures 1 - 1, 1-2, and 1-3). The NTS is operated by the U.S. Department of Energy, Nevada Operations Office (DOE/NV), which has been required by the Nevada Division of Environmental Protection (NDEP) to characterize the DPF under the requirements of the Resource Conservation and Recovery Act (RCRA) Part A Permit (NDEP, 1995) for the NTS and Title 40 Code of Federal Regulations (CFR) Part 265 (1996c). The DPF is prioritized in the Federal Facility Agreement and Consent Order (FFACO, 1996) but is governed by the permit. The DPF was characterized through sampling events in 1994, 1996, and 1997. The results of these sampling events are contained in the Final Resource Conservation and Recovery Act Industrial Site Environmental Restoration Site Characterization Report, Area 6 Decontamination Pond Facility, Revision I (DOE/NV, 1997). This Corrective Measures Study (CMS) for the Area 6 DPF has been prepared for the DOE/NV`s Environmental Restoration Project. The CMS has been developed to support the preparation of a Closure Plan for the DPF. Because of the complexities of the contamination and regulatory issues associated with the DPF, DOE/NV determined a CMS would be beneficial to the evaluation and selection of a closure alternative.

  11. Design and analysis of microalgal open pond systems for the purpose of producing fuels: A subcontract report

    SciTech Connect (OSTI)

    Weissman, J.C.; Goebel, R.P.

    1987-04-01

    The designs and systems developed include many innovative concepts and experiments, including the design and operation of a low-cost system. Cost-effectiveness is realized by minimizing capital costs of the system and achieving efficient use of inputs. Extensive engineering analysis of carbonation, mixing, and harvesting subsystems has elucidated both the lowest cost, most efficient options and the essential parameters needed to construct, test, and evaluate these subsystems. The use of growth ponds sealed with clay and lined with crushed rock results in construction cost savings of 50% over ponds lined with synthetic membranes. In addition a low-cost but efficient design allows improvements in technology to have maximum impact on final product cost reductions. In addition to the innovations in low-cost construction, the operational efficiency of the design is both higher and more feasible than that attained by any previous system concept of comparable scale. The water analysis has led to operational specifications that minimize water use and virtually eliminate losses of carbon dioxide to the atmosphere. The carbon dioxide injection system is designed for 95% efficiency, but is still low in cost. The construction of a large-scale, covered anaerobic lagoon to recycle carbon, nitrogen, and phosphorus has not been attempted at the scale analyzed here. Yet efficient recycling is essential for achieving economic affordability. 23 refs., 21 figs., 53 tabs.

  12. CALiPER Report 20.1: Quality of Beam, Shadow, and Color in LED PAR38 Lamps

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    | Department of Energy CALiPER Report 20.1: Quality of Beam, Shadow, and Color in LED PAR38 Lamps CALiPER Report 20.1: Quality of Beam, Shadow, and Color in LED PAR38 Lamps View the video about CALiPER Report 20.1 which focuses on human-evaluated characteristics, including beam quality, shadow quality, and color quality in LED PAR38 lamps. View the text-alternative version. Solid-State Lighting Home About the Solid-State Lighting Program Research & Development

  13. CALiPER Application Summary Report 20. LED PAR38 Lamps

    SciTech Connect (OSTI)

    none,

    2012-11-01

    This report analyzes the independently tested photometric performance of 38 LED PAR38 lamps. The test results indicate substantial improvement versus earlier CALiPER testing of similar products, and performance comparable to recent data from LED Lighting Facts and ENERGY STAR. Additional testing that focuses on performance attributes beyond those covered by LM-79-08 is planned for this group of lamps, and will be presented in subsequent reports.

  14. Survey of Radionuclide Distributions Resulting from the Church Rock, New Mexico, Uranium Mill Tailings Pond Dam Failure

    SciTech Connect (OSTI)

    Weimer, W. C.; Kinnison, R. R.; Reeves, J. H.

    1981-12-01

    An intensive site survey and on-site analysis program were conducted to evaluate the distribution of four radionucliGes in the general vicinity of Gallup, New Mexico, subsequent to the accidental breach of a uranium mill tailings pond dam and the release of a large quantity of tailings pond materials. The objective of this work was to determine the distribution and concentration levels of {sup 210}Pb, {sup 226}Ra, {sup 230}Th, and {sup 238}U in the arroyo that is immediately adjacent to the uranium tailings pond (pipeline arroyo) and in the Rio Puerco arroyo into which the pipeline arroyo drains. An intensive survey between the United Nuclear Corporation (UNC) Church Rock Mill site and the New Mexico-Arizona state border was performed. Sampling locations were established at approximately 500-ft intervals along the arroyo. During the weeks of September 24 through October 5, 1979, a series of samples was collected from alternate sampling locations along the arroyo. The purpose of this collection of samples and their subsequent analysis was to provide an immediate evaluation of the extent and the levels of radioactive contamination. The data obtained from this extensive survey were then compared to action levels which had been proposed by the Nuclear Regulatory Commission and were adapted by the New Mexico Environmental Improvement Division (NMEID) for {sup 230}Th and {sup 226}Ra concentrations that would require site cleanup. The Pacific Northwest Laboratory/Nuclear Regulatory Commission mobile laboratory van was on-site at the UNC Church Rock Mill from September 22, 1979, through December 13, 1979, and was manned by one or more PNL personnel for all but four weeks of this time period. Approximately 1200 samples associated with the Rio Puerco survey were analyzed 1n the laboratory. An additional 1200 samples related to the Rio Puerco cleanup operations which the United Nuclear Corporation was conducting were analyzed on-site in the mobile laboratory. The purpose of

  15. Application | SREL REU in Radioecology

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    boat ride on Par Pond ***APPLICATIONS FOR SUMMER 2016 ARE CLOSED*** We will begin taking applications for 2017 this fall.

  16. Exploring the Utilization of Complex Algal Communities to Address Algal Pond Crash and Increase Annual Biomass Production for Algal Biofuels

    SciTech Connect (OSTI)

    Hamilton, Cyd E.

    2014-03-25

    This white paper briefly reviews the research literature exploring complex algal communities as a means of increasing algal biomass production via increased tolerance, resilience, and resistance to a variety of abiotic and biotic perturbations occurring within harvesting timescales. This paper identifies what data are available and whether more research utilizing complex communities is needed to explore the potential of complex algal community stability (CACS) approach as a plausible means to increase biomass yields regardless of ecological context and resulting in decreased algal-based fuel prices by reducing operations costs. By reviewing the literature for what we do and do not know, in terms of CACS methodologies, this report will provide guidance for future research addressing pond crash phenomena.

  17. Mammalian aPKC/Par polarity complex mediated regulation of epithelial division orientation and cell fate

    SciTech Connect (OSTI)

    Vorhagen, Susanne; Niessen, Carien M.

    2014-11-01

    Oriented cell division is a key regulator of tissue architecture and crucial for morphogenesis and homeostasis. Balanced regulation of proliferation and differentiation is an essential property of tissues not only to drive morphogenesis but also to maintain and restore homeostasis. In many tissues orientation of cell division is coupled to the regulation of differentiation producing daughters with similar (symmetric cell division, SCD) or differential fate (asymmetric cell division, ACD). This allows the organism to generate cell lineage diversity from a small pool of stem and progenitor cells. Division orientation and/or the ratio of ACD/SCD need to be tightly controlled. Loss of orientation or an altered ratio can promote overgrowth, alter tissue architecture and induce aberrant differentiation, and have been linked to morphogenetic diseases, cancer and aging. A key requirement for oriented division is the presence of a polarity axis, which can be established through cell intrinsic and/or extrinsic signals. Polarity proteins translate such internal and external cues to drive polarization. In this review we will focus on the role of the polarity complex aPKC/Par3/Par6 in the regulation of division orientation and cell fate in different mammalian epithelia. We will compare the conserved function of this complex in mitotic spindle orientation and distribution of cell fate determinants and highlight common and differential mechanisms in which this complex is used by tissues to adapt division orientation and cell fate to the specific properties of the epithelium.

  18. Apparatus for in situ determination of burnup, cooling time and fissile content of an irradiated nuclear fuel assembly in a fuel storage pond

    DOE Patents [OSTI]

    Phillips, John R.; Halbig, James K.; Menlove, Howard O.; Klosterbuer, Shirley F.

    1985-01-01

    A detector head for in situ inspection of irradiated nuclear fuel assemblies submerged in a water-filled nuclear fuel storage pond. The detector head includes two parallel arms which extend from a housing and which are spaced apart so as to be positionable on opposite sides of a submerged fuel assembly. Each arm includes an ionization chamber and two fission chambers. One fission chamber in each arm is enclosed in a cadmium shield and the other fission chamber is unshielded. The ratio of the outputs of the shielded and unshielded fission chambers is used to determine the boron content of the pond water. Correcting for the boron content, the neutron flux and gamma ray intensity are then used to verify the declared exposure, cooling time and fissile material content of the irradiated fuel assembly.

  19. 2014 Annual Industrial Wastewater Reuse Report for the Idaho National Laboratory Site’s Materials and Fuels Complex Industrial Waste Ditch and Industrial Waste Pond

    SciTech Connect (OSTI)

    Lewis, Mike

    2015-02-01

    This report describes conditions, as required by the state of Idaho Industrial Wastewater Reuse Permit (WRU-I-0160-01, formerly LA 000160 01), for the wastewater reuse site at the Idaho National Laboratory Site’s Materials and Fuels Complex Industrial Waste Ditch and Industrial Waste Pond from November 1, 2013 through October 31, 2014. The report contains the following information; Facility and system description; Permit required effluent monitoring data and loading rates; Groundwater monitoring data; Status of special compliance conditions; Noncompliance issues; and Discussion of the facility’s environmental impacts During the 2014 reporting year, an estimated 10.11 million gallons of wastewater were discharged to the Industrial Waste Ditch and Pond which is well below the permit limit of 17 million gallons per year. The concentrations of all permit-required analytes in the samples from the down gradient monitoring wells were below the applicable Idaho Department of Environmental Quality’s groundwater quality standard levels.

  20. Apparatus for in situ determination of burnup, cooling time and fissile content of an irradiated nuclear fuel assembly in a fuel storage pond

    DOE Patents [OSTI]

    Phillips, J.R.; Halbig, J.K.; Menlove, H.O.; Klosterbuer, S.F.

    1984-01-01

    A detector head for in situ inspection of irradiated nuclear fuel assemblies submerged in a water-filled nuclear fuel storage pond. The detector head includes two parallel arms which extend from a housing and which are spaced apart so as to be positionable on opposite sides of a submerged fuel assembly. Each arm includes an ionization chamber and two fission chambers. One fission chamber in each arm is enclosed in a cadmium shield and the other fission chamber is unshielded. The ratio of the outputs of the shielded and unshielded fission chambers is used to determine the boron content of the pond water. Correcting for the boron content, the neutron flux and gamma ray intensity are then used to verify the declared exposure, cooling time and fissile material content of the irradiated fuel assembly.

  1. 2012 Annual Industrial Wastewater Reuse Report for the Idaho National Laboratory Site’s Materials and Fuels Complex Industrial Waste Ditch and Industrial Waste Pond

    SciTech Connect (OSTI)

    Mike Lewis

    2013-02-01

    This report describes conditions, as required by the state of Idaho Industrial Wastewater Reuse Permit (WRU-I-0160-01, formerly LA 000160 01), for the wastewater reuse site at the Idaho National Laboratory Site’s Materials and Fuels Complex Industrial Waste Ditch and Industrial Waste Pond from November 1, 2011 through October 31, 2012. The report contains the following information: • Facility and system description • Permit required effluent monitoring data and loading rates • Groundwater monitoring data • Status of special compliance conditions • Discussion of the facility’s environmental impacts During the 2012 reporting year, an estimated 11.84 million gallons of wastewater were discharged to the Industrial Waste Ditch and Pond which is well below the permit limit of 17 million gallons per year. The concentrations of all permit-required analytes in the samples from the down gradient monitoring wells were below the Ground Water Quality Rule Primary and Secondary Constituent Standards.

  2. 2011 Annual Industrial Wastewater Reuse Report for the Idaho National Laboratory Site's Materials and Fuels Complex Industrial Waste Ditch and Industrial Waste Pond

    SciTech Connect (OSTI)

    David Frederick

    2012-02-01

    This report describes conditions, as required by the state of Idaho Industrial Wastewater Reuse Permit (LA-000160-01), for the wastewater reuse site at the Idaho National Laboratory Site's Materials and Fuels Complex Industrial Waste Ditch and Industrial Waste Pond from November 1, 2010 through October 31, 2011. The report contains the following information: (1) Facility and system description; (2) Permit required effluent monitoring data and loading rates; (3) Groundwater monitoring data; (4) Status of special compliance conditions; and (5) Discussion of the facility's environmental impacts. During the 2011 reporting year, an estimated 6.99 million gallons of wastewater were discharged to the Industrial Waste Ditch and Pond which is well below the permit limit of 13 million gallons per year. Using the dissolved iron data, the concentrations of all permit-required analytes in the samples from the down gradient monitoring wells were below the Ground Water Quality Rule Primary and Secondary Constituent Standards.

  3. 2010 Annual Industrial Wastewater Reuse Report for the Idaho National Laboratory Site's Materials and Fuels Complex Industrial Waste Ditch and Industrial Waste Pond

    SciTech Connect (OSTI)

    David B. Frederick

    2011-02-01

    This report describes conditions, as required by the state of Idaho Industrial Wastewater Reuse Permit (#LA 000160 01), for the wastewater reuse site at the Idaho National Laboratory Site’s Materials and Fuels Complex Industrial Waste Ditch and Industrial Waste Pond from May 1, 2010 through October 31, 2010. The report contains the following information: • Facility and system description • Permit required effluent monitoring data and loading rates • Groundwater monitoring data • Status of special compliance conditions • Discussion of the facility’s environmental impacts During the 2010 partial reporting year, an estimated 3.646 million gallons of wastewater were discharged to the Industrial Waste Ditch and Pond which is well below the permit limit of 13 million gallons per year. The concentrations of all permit-required analytes in the samples from the down gradient monitoring wells were below the Ground Water Quality Rule Primary and Secondary Constituent Standards.

  4. Corrective Action Decision Document/Closure Report for Corrective Action Unit 478: Area 12 T-Tunnel Ponds, Nevada Test Site

    SciTech Connect (OSTI)

    NSTec Environmental Restoration

    2010-03-15

    This Corrective Action Decision Document (CADD)/Closure Report (CR) was prepared by the Defense Threat Reduction Agency (DTRA) for Corrective Action Unit (CAU) 478, Area 12 T-Tunnel Ponds. This CADD/CR is consistent with the requirements of the Federal Facility Agreement and Consent Order (FFACO) agreed to by the State of Nevada, the U.S. Department of Energy (DOE), and the U.S. Department of Defense. Corrective Action Unit 478 is comprised of one corrective action site (CAS): • 12-23-01, Ponds (5) RAD Area The purpose of this CADD/CR is to provide justification and documentation supporting the recommendation for closure in place with use restrictions for CAU 478.

  5. Waste Characteristics of the Former S-3 Ponds and Outline of Uranium Chemistry Relevant to NABIR Field Research Center Studies

    SciTech Connect (OSTI)

    Brooks, S.C.

    2001-06-29

    The Environmental Sciences Division at Oak Ridge National Laboratory (ORNL) was awarded the first Naturaland Accelerated Bioremediation Research (NABIR) Program, Field Research Center (FRC) based upon the recommendation of a review panel following a competitive peer-reviewed proposal process. The contaminated FRC site at ORNL is centered on groundwater plumes that originate from the former S-3 Waste Disposal Ponds located at the Y-12 Plant and the Y-12 Bone Yard/Bum Yard. Proposals for individual science research projects at the FRC were submitted in the spring of 2000 in response to a solicitation issued by the Department of Energy (DOE). Proposals selected for funding began work in Fiscal Year 2001 (October 1, 2000). The FRC staff have initiated several characterization efforts intended to support, inform, and educate individual FRC investigators, NABIR principal investigators (PIs), and the broader community of the specific conditions, opportunities, and challenges of this site. These efforts include both physical site characterization as well as numerical simulation (modeling) studies. Geochemical modeling has been conducted with the goal of: (1) providing a baseline understanding of the geochemical behavior of uranium (U); (2) examining the interaction of geochemistry and uranium transport in the subsurface; (3) elucidating some potential pitfalls for researchers with respect to manipulating subsurface environments for the purpose of demonstrating bacterially induced U immobilization. The geochemical modeling effort focused on using existing data and resources and did not involve the collection of new data or samples from the field site. Specifically, the following three tasks have been performed to date. (1) Searching for information on the wastes disposed in to the S-3 ponds. These data are typically found in internal technical reports at the labs and are rarely published in the peer-reviewed literature; thus, this information can be very difficult for the

  6. Interim Control Strategy for the Test Area North/Technical Support Facility Sewage Treatment Facility Disposal Pond - Two-year Update

    SciTech Connect (OSTI)

    L. V. Street

    2007-04-01

    The Idaho Cleanup Project has prepared this interim control strategy for the U.S. Department of Energy Idaho Operations Office pursuant to DOE Order 5400.5, Chapter 11.3e (1) to support continued discharges to the Test Area North/Technical Support Facility Sewage Treatment Facility Disposal Pond. In compliance with DOE Order 5400.5, a 2-year review of the Interim Control Strategy document has been completed. This submittal documents the required review of the April 2005 Interim Control Strategy. The Idaho Cleanup Project's recommendation is unchanged from the original recommendation. The Interim Control Strategy evaluates three alternatives: (1) re-route the discharge outlet to an uncontaminated area of the TSF-07; (2) construct a new discharge pond; or (3) no action based on justification for continued use. Evaluation of Alternatives 1 and 2 are based on the estimated cost and implementation timeframe weighed against either alternative's minimal increase in protection of workers, the public, and the environment. Evaluation of Alternative 3, continued use of the TSF-07 Disposal Pond under current effluent controls, is based on an analysis of four points: - Record of Decision controls will protect workers and the public - Risk of increased contamination is low - Discharge water will be eliminated in the foreseeable future - Risk of contamination spread is acceptable. The Idaho Cleanup Project recommends Alternative 3, no action other than continued implementation of existing controls and continued deactivation, decontamination, and dismantlement efforts at the Test Area North/Technical Support Facility.

  7. RADIATION DOSE ASSESSMENT FOR THE BIOTA OF TERRESTRIAL ECOSYSTEMS IN THE SHORELINE ZONE OF THE CHERNOBYL NUCLEAR POWER PLANT COOLING POND

    SciTech Connect (OSTI)

    Farfan, E.; Jannik, T.

    2011-10-01

    Radiation exposure of the biota in the shoreline area of the Chernobyl Nuclear Power Plant Cooling Pond was assessed to evaluate radiological consequences from the decommissioning of the Cooling Pond. The article addresses studies of radioactive contamination of the terrestrial faunal complex and radionuclide concentration ratios in bodies of small birds, small mammals, amphibians, and reptiles living in the area. The data were used to calculate doses to biota using the ERICA Tool software. Doses from {sup 90}Sr and {sup 137}Cs were calculated using the default parameters of the ERICA Tool and were shown to be consistent with biota doses calculated from the field data. However, the ERICA dose calculations for plutonium isotopes were much higher (2-5 times for small mammals and 10-14 times for birds) than the doses calculated using the experimental data. Currently, the total doses for the terrestrial biota do not exceed maximum recommended levels. However, if the Cooling Pond is allowed to drawdown naturally and the contaminants of the bottom sediments are exposed and enter the biological cycle, the calculated doses to biota may exceed the maximum recommended values. The study is important in establishing the current exposure conditions such that a baseline exists from which changes can be documented following the lowering of the reservoir water. Additionally, the study provided useful radioecological data on biota concentration ratios for some species that are poorly represented in the literature.

  8. Best management practices plan for the Chestnut Ridge-Filled Coal Ash Pond at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee

    SciTech Connect (OSTI)

    1996-05-01

    The Chestnut Ridge Filled Coal Ash Pond (FCAP) Project has been established to satisfy Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) requirements for the Chestnut Ridge Operable Unit 2. FCAP is on Chestnut Ridge, approximately 0.5 miles south of the Y-12 Plant. A 62-foot high earthen dam across Upper McCoy Branch was constructed in 1955 to create a pond to serve as a settling basin for fly and bottom ashes generated by burning coal at the Y-12 Steam Plant. Ash from the steam was mixed with water to form a slurry and then pumped to the crest of Chestnut Ridge and released through a large pipe to flow across the Sluice Channel area and into the pond. The ash slurry eventually overtopped the dam and flowed along Upper McCoy Branch to Rogers Quarry. The purpose of this document is to provide a site-specific Best Management Practices (BMP) Plan for construction associated with environmental restoration activities at the FCAP Site.

  9. Technology for the Recovery of Fuel and Adsorbent Carbons from Coal Burning Utility Ash Ponds and Landfills

    SciTech Connect (OSTI)

    J.G. Groppo; T.L. Robl

    2005-09-30

    Several sampling techniques were evaluated to recover representative core samples from the ash ponds at Western Kentucky Energy's Coleman Station. The most successful was a combination of continuous-flight augers and specially designed soft-sediment sampling tubes driven by a Hammerhead drill mounted on an amphibious ARGO vehicle. A total of 51 core samples were recovered and analyzed in 3 ft sections and it was determined that there are 1,354,974 tons of ash in Pond C. Of the over 1.35M tons of ash present, 14% or 190K tons can be considered as coarse (+100 mesh). Pond C contains approximately 88K tons of carbon, nearly half of which is coarse and potentially recoverable with spiral concentration while the fine carbon (-100 mesh) is recoverable with froth flotation. There are 1.27M tons of carbon-free ash, 12% of which is coarse and potentially usable as block sand. Spiral concentration testing on bulk samples showed that product grade of 30 to 38% C (4200 to 5500 Btu/lb) was obtainable. When this product was cleaned again in an additional stage of spiral concentration, the product grade was improved to 7200 to 8200 Btu/lb with an accompanying 13 to 29% decrease in yield. Release analysis of hydraulically classified pond ash showed that froth flotation could provide froth products with as high a grade as 9000 Btu/lb with a yield of 5%. Increasing yield to 10% reduced froth grade to 7000 Btu/lb. Batch flotation provided froth grades as high as 6500 Btu/lb with yields of 7% with 1.5 lb/ton SPP and 1 lb/ton frother. Column flotation test results were similar to those achieved in batch flotation in terms of both grade and yield, however, carbon recoveries were lower (<70%). High airflow rate was required to achieve >50% carbon recovery and using wash water improved froth grade. Bottom ash samples were recovered from each of the units at Coleman Station. Characterization confirmed that sufficient quantity and quality of material is generated to produce a marketable

  10. Potential land competition between open-pond microalgae production and terrestrial dedicated feedstock supply systems in the U.S.

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Coleman, Andre M.; Wigmosta, Mark S.; Hellwinckel, Chad M.; Brandt, Craig C.; Langholtz, Matthew H.; Eaton, Laurence M.

    2016-03-03

    To date, feedstock resource assessments have evaluated cellulosic and algal feedstocks independently, without consideration of demands for, and resource allocation to, each other. We assess potential land competition between algal and terrestrial feedstocks in the United States, and evaluate a scenario in which 41.5 × 109 L yr–1 of second-generation biofuels are produced on pastureland, the most likely land base where both feedstock types may be deployed. Under this scenario, open-pond microalgae production is projected to use 1.2 × 106 ha of private pastureland, while terrestrial biomass feedstocks would use 14.0 × 106 ha of private pastureland. A spatial meta-analysismore » indicates that potential competition for land under this scenario would be concentrated in 110 counties, containing 1.0 and 1.7 × 106 ha of algal and terrestrial dedicated feedstock production, respectively. Furthermore, a land competition index applied to these 110 counties suggests that 38 to 59 counties could experience competition for upwards of 40% of a county's pastureland, representing 2%–5% of total pastureland in the U.S.; therefore suggesting little overall competition between algae production, terrestrial energy feedstocks and alternative uses for existing agricultural production such as livestock grazing.« less

  11. DOE Publishes CALiPER Report on Dimming, Flicker, and Power Quality Characteristics of LED PAR38 Lamps

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy's CALiPER program has released Report 20.2, which is part of a series of investigations on LED PAR38 lamps. Report 20.2 focuses on dimming, flicker, and power quality...

  12. Recycled Water Reuse Permit Renewal Application for the Materials and Fuels Complex Industrial Waste Ditch and Industrial Waste Pond

    SciTech Connect (OSTI)

    No Name

    2014-10-01

    ABSTRACT This renewal application for the Industrial Wastewater Reuse Permit (IWRP) WRU-I-0160-01 at Idaho National Laboratory (INL), Materials and Fuels Complex (MFC) Industrial Waste Ditch (IWD) and Industrial Waste Pond (IWP) is being submitted to the State of Idaho, Department of Environmental Quality (DEQ). This application has been prepared in compliance with the requirements in IDAPA 58.01.17, Recycled Water Rules. Information in this application is consistent with the IDAPA 58.01.17 rules, pre-application meeting, and the Guidance for Reclamation and Reuse of Municipal and Industrial Wastewater (September 2007). This application is being submitted using much of the same information contained in the initial permit application, submitted in 2007, and modification, in 2012. There have been no significant changes to the information and operations covered in the existing IWRP. Summary of the monitoring results and operation activity that has occurred since the issuance of the WRP has been included. MFC has operated the IWP and IWD as regulated wastewater land treatment facilities in compliance with the IDAPA 58.01.17 regulations and the IWRP. Industrial wastewater, consisting primarily of continuous discharges of nonhazardous, nonradioactive, routinely discharged noncontact cooling water and steam condensate, periodic discharges of industrial wastewater from the MFC facility process holdup tanks, and precipitation runoff, are discharged to the IWP and IWD system from various MFC facilities. Wastewater goes to the IWP and IWD with a permitted annual flow of up to 17 million gallons/year. All requirements of the IWRP are being met. The Operations and Maintenance Manual for the Industrial Wastewater System will be updated to include any new requirements.

  13. Corrective Action Investigation Plan for Corrective Action Unit 552: Area 12 Muckpile and Ponds, Nevada Test Site, Nevada, Rev. No.: 1 with ROTC 1 and 2

    SciTech Connect (OSTI)

    David A. Strand

    2005-01-01

    This Corrective Action Investigation Plan (CAIP) contains project-specific information including facility descriptions, environmental sample collection objectives, and criteria for conducting site investigation activities at Corrective Action Unit (CAU) 552: Area 12 Muckpile and Ponds, Nevada Test Site (NTS), Nevada. This CAIP has been developed in accordance with the ''Federal Facility Agreement and Consent Order'' (FFACO) (1996) that was agreed to by the State of Nevada, the U.S. Department of Energy (DOE), and the U.S. Department of Defense. The NTS is approximately 65 miles (mi) northwest of Las Vegas, Nevada (Figure 1-1). Corrective Action Unit 552 is comprised of the one Corrective Action Site which is 12-23-05, Ponds. One additional CAS, 12-06-04, Muckpile (G-Tunnel Muckpile), was removed from this CAU when it was determined that the muckpile is an active site. A modification to the FFACO to remove CAS 12-06-04 was approved by the Nevada Division of Environmental Protection (NDEP) on December 16, 2004. The G-Tunnel ponds were first identified in the 1991 Reynolds Electrical & Engineering Co., Inc. document entitled, ''Nevada Test Site Inventory of Inactive and Abandoned Facilities and Waste Sites'' (REECo, 1991). Corrective Action Unit 552 is being investigated because existing information on the nature and extent of potential contamination is insufficient to evaluate and recommend corrective action alternatives. Therefore, additional information will be obtained by conducting a corrective action investigation (CAI) prior to evaluating and selecting the corrective action alternatives for the site. The CAI will include field inspections, radiological surveys, and sampling of appropriate media. Data will also be obtained to support investigation-derived waste (IDW) disposal and potential future waste management decisions.

  14. Portable instrument for inspecting irradiated nuclear-fuel assemblies in a water-filled storage pond by measurement of induced Cerenkov radiation

    DOE Patents [OSTI]

    Nicholson, N.; Dowdy, E.J.; Holt, D.M.; Stump, C.J. Jr.

    1982-05-13

    A portable instrument for measuring induced Cerenkov radiation associated with irradiated nuclear fuel assemblies in a water-filled storage pond is disclosed. The instrument includes a photomultiplier tube and an image intensifier which are operable in parallel and simultaneously by means of a field lens assembly and an associated beam splitter. The image intensifier permits an operator to aim and focus the apparatus on a submerged fuel assembly. Once the instrument is aimed and focused, an illumination reading can be obtained with the photomultiplier tube. The instrument includes a lens cap with a carbon-14/phosphor light source for calibrating the apparatus in the field.

  15. CALiPER Report 20.3: Robustness of LED PAR38 Lamps

    SciTech Connect (OSTI)

    Poplawski, Michael E.; Royer, Michael P.; Brown, Charles C.

    2014-12-31

    Three samples of 40 of the Series 20 PAR38 lamps underwent multi-stress testing, whereby samples were subjected to increasing levels of simultaneous thermal, humidity, electrical, and vibrational stress. The results do not explicitly predict expected lifetime or reliability, but they can be compared with one another, as well as with benchmark conventional products, to assess the relative robustness of the product designs. On average, the 32 LED lamp models tested were substantially more robust than the conventional benchmark lamps. As with other performance attributes, however, there was great variability in the robustness and design maturity of the LED lamps. Several LED lamp samples failed within the first one or two levels of the ten-level stress plan, while all three samples of some lamp models completed all ten levels. One potential area of improvement is design maturity, given that more than 25% of the lamp models demonstrated a difference in failure level for the three samples that was greater than or equal to the maximum for the benchmarks. At the same time, the fact that nearly 75% of the lamp models exhibited better design maturity than the benchmarks is noteworthy, given the relative stage of development for the technology.

  16. The Role of Gamma-ray Imaging in Performing Radiological Characterisation at the Magnox Storage Ponds at the Bradwell Decommissioning Site - 13628

    SciTech Connect (OSTI)

    Hughes, Karl; Shaw, Tracey

    2013-07-01

    A gamma-ray imaging device has been used to perform radiological characterisation work at the spent fuel ponds complex at the site of the Bradwell Magnox Power Station, which is currently undergoing accelerated decommissioning. The objective of using a gamma-ray imaging system was to independently verify previous radiological survey work and to evaluate the adequacy of the random distribution of the destructive core sampling which had been performed. In performing this work the gamma-ray imager clearly identified the exact locations of the sources of radiation that gave rise to the elevated gamma dose rates measured by conventional health physics surveys of the area. In addition, the gamma-ray imager was able to characterise each hotspot as being either dominated by Cs-137 or by Co-60. The gamma imaging survey was undertaken with a RadScan gamma imaging system deployed on the walkways which run along the lengths of the ponds; this enabled the whole imaging survey to be performed with minimal dose uptake, demonstrating the ALARP principle within decommissioning. (authors)

  17. 2013 Annual Industrial Wastewater Reuse Report for the Idaho National Laboratory Site’s Materials and Fuels Complex Industrial Waste Ditch and Industrial Waste Pond

    SciTech Connect (OSTI)

    Mike Lewis

    2014-02-01

    This report describes conditions, as required by the state of Idaho Industrial Wastewater Reuse Permit (WRU-I-0160-01, formerly LA 000160 01), for the wastewater reuse site at the Idaho National Laboratory Site’s Materials and Fuels Complex Industrial Waste Ditch and Industrial Waste Pond from November 1, 2012 through October 31, 2013. The report contains the following information: • Facility and system description • Permit required effluent monitoring data and loading rates • Groundwater monitoring data • Status of special compliance conditions • Discussion of the facility’s environmental impacts During the 2013 reporting year, an estimated 9.64 million gallons of wastewater were discharged to the Industrial Waste Ditch and Pond which is well below the permit limit of 17 million gallons per year. The concentrations of all permit-required analytes in the samples from the down gradient monitoring wells were below the applicable Idaho Department of Environmental Quality’s groundwater quality standard levels.

  18. Radiological Monitoring Results for Groundwater Samples Associated with the Industrial Wastewater Reuse Permit for the Materials and Fuels Complex Industrial Waste Ditch and Pond: November 1, 2012-October 31, 2013

    SciTech Connect (OSTI)

    Mike Lewis

    2014-02-01

    This report summarizes radiological monitoring performed on samples from specific groundwater monitoring wells associated with the Industrial Wastewater Reuse Permit for the Materials and Fuels Complex Industrial Waste Ditch and Industrial Waste Pond WRU-I-0160-01, Modification 1 (formerly LA-000160-01). The radiological monitoring was performed to fulfill Department of Energy requirements under the Atomic Energy Act.

  19. Radiological Monitoring Results for Groundwater Samples Associated with the Industrial Wastewater Reuse Permit for the Materials and Fuels Complex Industrial Waste Ditch and Pond: November 1, 2011-October 31, 2012

    SciTech Connect (OSTI)

    Mike lewis

    2013-02-01

    This report summarizes radiological monitoring performed on samples from specific groundwater monitoring wells associated with the Industrial Wastewater Reuse Permit for the Materials and Fuels Complex Industrial Waste Ditch and Industrial Waste Pond WRU-I-0160-01, Modification 1 (formerly LA-000160-01). The radiological monitoring was performed to fulfill Department of Energy requirements under the Atomic Energy Act.

  20. Radiological Monitoring Results For Groundwater Samples Associated with the Industrial Wastewater Reuse Permit for the Materials and Fuels Complex Industrial Waste Ditch and Pond: May 1, 2010-October 31, 2010

    SciTech Connect (OSTI)

    David B. Frederick

    2011-02-01

    This report summarizes radiological monitoring performed on samples from specific groundwater monitoring wells associated with the Industrial Wastewater Reuse Permit for the Materials and Fuels Complex Industrial Waste Ditch and Industrial Waste Pond (#LA-000160-01). The radiological monitoring was performed to fulfill Department of Energy requirements under the Atomic Energy Act.

  1. Radiological Monitoring Results For Groundwater Samples Associated with the Industrial Wastewater Reuse Permit for the Materials and Fuels Complex Industrial Waste Ditch and Pond: November 1, 2010-October 31, 2011

    SciTech Connect (OSTI)

    David Frederick

    2012-02-01

    This report summarizes radiological monitoring performed on samples from specific groundwater monitoring wells associated with the Industrial Wastewater Reuse Permit for the Materials and Fuels Complex Industrial Waste Ditch and Industrial Waste Pond (No.LA-000160-01). The radiological monitoring was performed to fulfill Department of Energy requirements under the Atomic Energy Act.

  2. [Task 1.] Biodenitrification of low nitrate solar pond waters using sequencing batch reactors. [Task 2.] Solidification/stabilization of high strength and biodenitrified heavy metal sludges with a Portland cement/flyash system

    SciTech Connect (OSTI)

    Figueroa, L.; Cook, N.E.; Siegrist, R.L.; Mosher, J.; Terry, S.; Canonico, S.

    1995-09-22

    Process wastewater and sludges were accumulated on site in solar evaporation ponds during operations at the Department of Energy's Rocky Flats Plant (DOE/RF). Because of the extensive use of nitric acid in the processing of actinide metals, the process wastewater has high concentrations of nitrate. Solar pond waters at DOE/RF contain 300-60,000 mg NO{sub 3}{sup {minus}}/L. Additionally, the pond waters contain varying concentrations of many other aqueous constituents, including heavy metals, alkali salts, carbonates, and low level radioactivity. Solids, both from chemical precipitation and soil material deposition, are also present. Options for ultimate disposal of the pond waters are currently being evaluated and include stabilization and solidification (S/S) by cementation. Removal of nitrates can enhance a wastes amenability to S/S, or can be a unit operation in another treatment scheme. Nitrate removal is also a concern for other sources of pollution at DOE/RF, including contaminated groundwater collected by interceptor trench systems. Finally, nitrate pollution is a problem at many other DOE facilities where actinide metals were processed. The primary objective of this investigation was to optimize biological denitrification of solar pond waters with nitrate concentrations of 300--2,100 mg NO{sub 3}{sup {minus}}/L to below the drinking water standard of 45 mg NO{sub 3}{sup {minus}}/L (10 mg N/L). The effect of pH upon process stability and denitrification rate was determined. In addition, the effect Cr(VI) on denitrification and fate of Cr(VI) in the presence of denitrifying bacteria was evaluated.

  3. RCRA Facility Investigation Plan K-1004 Area Lab Drain and the K-1007-B Pond - Oak Ridge Gaseous Diffusion Plant - Oak Ridge, Tennessee

    SciTech Connect (OSTI)

    ORGDP, Martin Marietta Energy Systems Inc.

    1988-12-01

    Within the confines of the Oak Ridge Gaseous Diffusion Plant (ORGDP) are hazardous waste treatment, storage, and disposal facilities; some are in operation while others are no longer in use. these solid waste management units (SWMUs) are subject to assessment by the US Environmental Protection Agency (EPA). The RCRA Facility Investigation (RFI) Plans are scheduled to be submitted for all units during calendar years 1987 and 1988. The RFI Plan - General Document (K/HS-132) includes information applicable to all the ORGDP SMWUs and serves as a reference document for the site-specific RFI plans. This document is the site-specific RFI Plan for the K-1004 Area Lab Drain (ALD) and the K-1007-B Pond. This plan is based upon requirements described in the draft document, RFI Guidance, Vols. I-IV, December 1987 (EPA 530/SW-87-001). This unit is regulated by Section 3004(u) of the 1984 Hazardous and Solid Waste Amendments (HSWA) to the Resource Conservation Recovery Act (RCRA). Contained within this document are geographical, historical, operational, geological, and hydrological data specific to the K-1004 ALD and the K-1007-B Pond. The potential for release of contamination through the various media to receptors is addressed. A sampling plan is proposed to further determine the extent (if any) of release of contamination to the surrounding environment. Included are health and safety procedures to be followed when implementing the sampling plan. Quality control (QC) procedures for remedial action occurring on the Oak Ridge Reservation (ORR) are presented in 'The Environmental Surveillance Procedures Quality Control Program, Martin Marietta Energy Systems, Inc., (ESH/Sub/87-21706/1), and quality assurance (QA) guidelines for ORGDP investigations are contained in The K-25 Remedial Actions Program Quality Assurance Plan, K/HS-231.

  4. POST CLOSURE INSPECTION REPORT FOR CORRECTIVE ACTION UNIT 92: AREA 6 DECON POND FACILITY, NEVADA TEST SITE, NEVADA; FOR CALENDAR YEAR 2005

    SciTech Connect (OSTI)

    NA

    2006-03-01

    This Post-Closure Inspection Report provides an analysis and summary of inspections for Corrective Action Unit (CAU) 92, Area 6 Decon Pond Facility, Nevada Test Site, Nevada. CAU 92 was closed in accordance with the Resource Conservation and Recovery Act (RCRA) Part B Operational Permit (Nevada Division of Environmental Protection (NDEP), 1995) and the Federal Facility Agreement and Consent Order of 1996. Closure activities were completed on February 16, 1999, and the Closure Report (U.S. Department of Energy, Nevada Operations Office, 1999) was approved and a Notice of Completion issued by the NDEP on May 11, 1999. CAU 92 consists of two Corrective Action Sites (CASs): CAS 06-04-01, Decon Pad Oil/Water Separator; and CAS 06-05-02, Decontamination Pond (RCRA). Both CASs have use restrictions; however, only CAS 06-05-02 requires post-closure inspections. Visual inspections of the cover and fencing at CAS 06-05-02 are performed quarterly. Additional inspections are conducted if precipitation occurs in excess of 1.28 centimeters (cm) (0.50 inches [in]) in a 24-hour period. This report covers calendar year 2005. Quarterly site inspections were performed in March, June, September, and December of 2005. All observations indicated the continued integrity of the unit. No issues or concerns were noted, and no corrective actions were necessary. Copies of the inspection checklists and field notes completed during each inspection are included in Appendix A. Five additional inspections were performed after precipitation events that exceeded 1.28 cm (0.50 in) within a 24-hour period during 2005. No significant changes in site conditions were noted during these inspections, and no corrective actions were necessary. Copies of the inspection checklists and field notes completed during each inspection are included in Appendix A. Precipitation records for 2005 are included in Appendix C.

  5. Magi is associated with the par complex and functions antagonistically with bazooka to regulate the apical polarity complex

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Padash Barmchi, Mojgan; Samarasekera, Gayathri; Gilbert, Mary; Auld, Vanessa J.; Zhang, Bing; Nam, Sang -Chul

    2016-04-13

    The mammalian MAGI proteins play important roles in the maintenance of adherens and tight junctions. The MAGI family of proteins contains modular domains such as WW and PDZ domains necessary for scaffolding of membrane receptors and intracellular signaling components. Loss of MAGI leads to reduced junction stability while overexpression of MAGI can lead to increased adhesion and stabilization of epithelial morphology. However, how Magi regulates junction assembly in epithelia is largely unknown. We investigated the single Drosophila homologue of Magi to study the in vivo role of Magi in epithelial development. Magi is localized at the adherens junction and formsmore » a complex with the polarity proteins, Par3/Bazooka and aPKC. We generated a Magi null mutant and found that Magi null mutants were viable with no detectable morphological defects even though the Magi protein is highly conserved with vertebrate Magi homologues. However, overexpression of Magi resulted in the displacement of Baz/Par3 and aPKC and lead to an increase in the level of PIP3. Interestingly, we found that Magi and Baz functioned in an antagonistic manner to regulate the localization of the apical polarity complex. As a result, maintaining the balance between the level of Magi and Baz is an important determinant of the levels and localization of apical polarity complex.« less

  6. EA-1070: Revised Finding of No Significant Impact

    Broader source: Energy.gov [DOE]

    Natural Fluctuation of Water Level in Par Pond and Reduced Water Flow in Steel Creek below L Lake at the Savannah River Site

  7. Remedial investigation report on Chestnut Ridge Operable Unit 2 (filled coal ash pond/Upper McCoy Branch) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee. Volume 2: Appendixes

    SciTech Connect (OSTI)

    Not Available

    1994-08-01

    This report comprises appendices A--J which support the Y-12 Plant`s remedial action report involving Chestnut Ridge Operable Unit 2 (filled coal ash pond/Upper McCoy Branch). The appendices cover the following: Sampling fish from McCoy Branch; well and piezometer logs; ecological effects of contaminants in McCoy Branch 1989-1990; heavy metal bioaccumulation data; microbes in polluted sediments; and baseline human health risk assessment data.

  8. CALiPER Report 20.4: Lumen and Chromaticity Maintenance of LED PAR38 Lamps Operated in Steady-State Conditions

    SciTech Connect (OSTI)

    none,

    2014-12-30

    This CALiPER report focuses on lumen maintenance, chromaticity maintenance, and catastrophic failure in 32 of the Series 20 LED PAR38 lamps and 8 benchmark lamps, which were monitored for nearly 14,000 hours at ambient temperatures between 44°C and 45°C.

  9. Quality assurance project plan for the Chestnut Ridge Fly Ash Pond Stabilization Project at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee

    SciTech Connect (OSTI)

    1996-07-01

    The Chestnut Ridge Fly Ash Pond Stabilization (CRFAPS) Project will stabilize a 19-m-high (62-ft-high) earthen embankment across Upper McCoy Branch situated along the southern slope of Chestnut Ridge. This task will be accomplished by raising the crest of the embankment, reinforcing the face of the embankment, removing trees from the face and top of the embankment, and repairing the emergency spillway. The primary responsibilities of the team members are: Lockheed Martin Energy Systems, Inc., (Energy Systems) will be responsible for project integration, technical support, Title 3 field support, environmental oversight, and quality assurance (QA) oversight of the project; Foster Wheeler Environmental Corporation (FWENC) will be responsible for design and home office Title 3 support; MK-Ferguson of Oak Ridge Company (MK-F) will be responsible for health and safety, construction, and procurement of construction materials. Each of the team members has a QA program approved by the US Department of Energy (DOE) Oak Ridge Operations. This project-specific QA project plan (QAPP), which is applicable to all project activities, identifies and integrates the specific QA requirements from the participant`s QA programs that are necessary for this project.

  10. CALiPER Report 20.2: Dimming, Flicker, and Power Quality Characteristics of LED PAR38 Lamps

    SciTech Connect (OSTI)

    None, None

    2014-03-31

    This report focuses on the flicker and power quality performance of the Series 20 lamps at full output and various dimmed levels. All of the Series 20 PAR38 lamps that manufacturers claimed to be dimmable (including all halogen lamps) were evaluated individually (one lamp at a time) both on a switch and under the control of a phase-cut dimmer designed for use with "all classes of bulbs." Measurements of luminous flux, flicker, and power quality were taken at 10 target dimmed settings and compared with operation on a switch. Because only a single unit of each product was evaluated on a single dimmer that may or may not have been recommended by its manufacturer, this report focuses on the performance of the products relative to each other, rather than the best-case performance of each lamp or variation in performance delivered from each lamp. Despite these limitations, the results suggest that LED performance is improving, and performance trends are beginning to emerge, perhaps due in part to the identification of preferred LED driver strategies for lamp products.

  11. Review of the current status of reverse electrodialysis systems for salinity power systems using a stratified saturated solar pond. Final report. Report No. 220280

    SciTech Connect (OSTI)

    Not Available

    1980-02-22

    The overall objective of this study was to develop and place in operation a small salinity power heat engine of 100-watt capacity consisting of a saturated solar pond (SSP) coupled to a reverse electrodialysis (RED) membrane stack. The objectives of the contract were: (1) to demonstrate that a SSP can be used for unmixing of a mixed brine into a dilute and a concentrated brine stream, (2) to demonstrate that a RED stack can generate electrical power, and (3) to generate the necessary experimental data on the RED-SSP system which can be used to assess the potential of such a system for economical energy generation. The results of findings on the current status of ion-exchange membranes and RED stacks is summarized. It is shown that the electrical resistance of the present-day membranes, which are produced for electrodialysis and not reverse electrodialysis, and the solution compartments are very high. This causes the power density of present-day RED stacks, in terms of watts per unit membrane area, to be very low. This factor combined with the high cost of present-day membranes results in very high costs for the RED stack. Furthermore, present-day membranes as well as adhesives for membrane assemblies cannot operate at about 80/sup 0/C for any reasonable length of time without severe deterioration in performance. The areas that require development work include: (1) development of cheap ion-exchange membranes with low electrical resistance and high permselectivity; (2) development of very thin solution compartments; (3) development of RED stacks which can operate at high temperatures; and (4) laboratory testing of small RED stacks to investigate the effect of temperature on stack performance and the fouling of RED membranes with time, have been identified. (WHK)

  12. DOE CALiPER Program, Report 20.1 Subjective Evaluation of Beam Quality, Shadow Quality, and Color Quality for LED PAR38 Lamps

    SciTech Connect (OSTI)

    Royer, Michael P.; Poplawski, Michael E.; Miller, Naomi J.

    2013-10-01

    This report focuses on human-evaluated characteristics, including beam quality, shadow quality, and color quality. Using a questionnaire that included rank ordering, opinions on 27 of the Report 20 PAR38 lamps were gathered during a demonstration event for members of the local Illuminating Engineering Society (IES) chapter. This was not a rigorous scientific experiment, and the data should not be extrapolated beyond the scope of the demonstration. The results suggest that many of the LED products compared favorably to halogen PAR38 benchmarks in all attributes considered. LED lamps using a single-emitter design were generally preferred for their beam quality and shadow quality, and the IES members ranking of color quality did not always match the rank according to the color rendering index (CRI).

  13. CALiPER Report 20.1: Subjective Evaluation of Beam Quality, Shadow Quality, and Color Quality for LED PAR38 Lamps

    SciTech Connect (OSTI)

    None, None

    2013-11-07

    This report focuses on human-evaluated characteristics, including beam quality, shadow quality, and color quality. Using a questionnaire that included rank-ordering, opinions on 27 of the Report 20 PAR38 lamps were gathered during a demonstration event for members of the local Illuminating Engineering Society (IES) chapter. This was not a rigorous scientific experiment, and the data should not be extrapolated beyond the scope of the demonstration. The results suggest that many of the LED products compared favorably to halogen PAR38 benchmarks in all attributes considered. LED lamps using a single-emitter design were generally preferred for their beam quality and shadow quality, and the IES members' ranking of color quality did not always match the rank according to the color rendering index (CRI).

  14. ARM - Datastreams - pars2

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Atlantic ENA C1 Browse Data Graciosa Island, Azores, Portugal ARM Mobile Facility ACX S1 Browse Data ACX Supplemental Facility 1 MAG S1 Browse Data MAG Supplemental Facility 1...

  15. Superfund Record of Decision (EPA Region 8): Silver Bow Creek/Butte Area NPL site, Warm Springs Ponds Operable Unit, Upper Clark Fork River Basin, MT. (First remedial action), September 1990

    SciTech Connect (OSTI)

    Not Available

    1990-09-28

    The Silver Bow Creek site is a mining and processing area in the Upper Clark Fork River Basin, Deer Lodge County, Southwestern Montana. The Record of Decision (ROD) documents the selected interim remedial action for one of eleven operable units for the site, the Warm Springs Ponds operable unit, which covers approximately 2,500 acres just above the beginning of the Clark Fork River. Contamination at the site is the result of over 100 years of mining and process operations in the area. Mining, milling, and smelting waste were dumped directly into Silver Bow Creek and transported downstream to the Clark Fork River with final deposition downstream as far as 130 miles. Principal threats from the site include the possibility of pond berm failure due to flood and earthquake damage that could release millions of cubic yards of tailings and sediment to the river. Furthermore, the creeks are contaminated with dissolved metals, and exposed soil and tailings are contaminated with elevated levels of several metals. The primary contaminants of concern affecting the soil, sediment, ground water, and surface water are metals including arsenic, cadmium, copper, lead, and zinc.

  16. Remedial Investigation Report on Chestnut Ridge Operable Unit 2 (Filled Coal Ash Pond/Upper McCoy Branch) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee. Volume 1. Main Text

    SciTech Connect (OSTI)

    Not Available

    1994-08-01

    This document is a report on the remedial investigation (RI) of Chestnut Ridge Operable Unit (OU) 2 at the Oak Ridge Y-12 Plant. Chestnut Ridge OU 2 consists of Upper McCoy Branch (UMB), the Filled Coal Ash Pond (FCAP), and the area surrounding the Sluice Channel formerly associated with coal ash disposal in the FCAP. Chestnut Ridge OU 2 is located within the U.S. Department of Energy`s (DOE`s) Oak Ridge Reservation in Anderson County, Tennessee, approximately 24 miles west of Knoxville. The pond is an 8.5-acre area on the southern slope of Chestnut Ridge, 0.5 mile south of the main Y-12 Plant and geographically separated from the Y-12 Plant by Chestnut Ridge. The elevation of the FCAP is {approximately} 950 ft above mean sea level (msl), and it is relatively flat and largely vegetated. Two small ponds are usually present at the northeast and northwest comers of the FCAP. The Sluice Channel Area extends {approximately}1000 ft from the northern margin of the FCAP to the crest of Chestnut Ridge, which has an elevation of {approximately}1100 ft above msl. The Sluice Channel Area is largely vegetated also. McCoy Branch runs from the top of Chestnut Ridge across the FCAP into Rogers Quarry and out of the quarry where it runs a short distance into Milton Hill Lake at McCoy Embayment, termed UMB. The portion south of Rogers Quarry, within Chestnut Ridge OU 4, is termed Lower McCoy Branch. The DOE Oak Ridge Y-12 Plant disposed of coal ash from its steam plant operations as a slurry that was discharged into an ash retention impoundment; this impoundment is the FCAP. The FCAP was built in 1955 to serve as a settling basin after coal ash slurried over Chestnut Ridge from the Y-12 Plant. The FCAP was constructed by building an earthen dam across the northern tributary of McCoy Branch. The dam was designed to hold 20 years of Y-12 steam plant ash. By July 1967, ash had filled up the impoundment storage behind the dam to within 4 ft of the top.

  17. Tricyclic GyrB/ParE (TriBE) Inhibitors. A new class of broad-spectrum dual-targeting antibacterial agents

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Tari, Leslie W.; Li, Xiaoming; Trzoss, Michael; Bensen, Daniel C.; Chen, Zhiyong; Lam, Thanh; Zhang, Junhu; Lee, Suk Joong; Hough, Grayson; Phillipson, Doug; et al

    2013-12-26

    Increasing resistance to every major class of antibiotics and a dearth of novel classes of antibacterial agents in development pipelines has created a dwindling reservoir of treatment options for serious bacterial infections. The bacterial type IIA topoisomerases, DNA gyrase and topoisomerase IV, are validated antibacterial drug targets with multiple prospective drug binding sites, including the catalytic site targeted by the fluoroquinolone antibiotics. Growing resistance to fluoroquinolones, frequently mediated by mutations in the drug-binding site, is increasingly limiting the utility of this antibiotic class, prompting the search for other inhibitor classes that target different sites on the topoisomerase complexes. The highlymore » conserved ATP-binding subunits of DNA gyrase (GyrB) and topoisomerase IV (ParE) have long been recognized as excellent candidates for the development of dual-targeting antibacterial agents with broad-spectrum potential. However, to date, no natural product or small molecule inhibitors targeting these sites have succeeded in the clinic, and no inhibitors of these enzymes have yet been reported with broad-spectrum antibacterial activity encompassing the majority of Gram-negative pathogens. Using structure-based drug design (SBDD), we have created a novel dual-targeting pyrimidoindole inhibitor series with exquisite potency against GyrB and ParE enzymes from a broad range of clinically important pathogens. Inhibitors from this series demonstrate potent, broad-spectrum antibacterial activity against Gram-positive and Gram-negative pathogens of clinical importance, including fluoroquinolone resistant and multidrug resistant strains. Moreover, lead compounds have been discovered with clinical potential; they are well tolerated in animals, and efficacious in Gram-negative infection models.« less

  18. Tricyclic GyrB/ParE (TriBE) Inhibitors. A new class of broad-spectrum dual-targeting antibacterial agents

    SciTech Connect (OSTI)

    Tari, Leslie W.; Li, Xiaoming; Trzoss, Michael; Bensen, Daniel C.; Chen, Zhiyong; Lam, Thanh; Zhang, Junhu; Lee, Suk Joong; Hough, Grayson; Phillipson, Doug; Akers-Rodriguez, Suzanne; Cunningham, Mark L.; Kwan, Bryan P.; Nelson, Kirk J.; Castellano, Amanda; Locke, Jeff B.; Brown-Driver, Vickie; Murphy, Timothy M.; Ong, Voon S.; Pillar, Chris M.; Shinabarger, Dean L.; Nix, Jay; Lightstone, Felice C.; Wong, Sergio E.; Nguyen, Toan B.; Shaw, Karen J.; Finn, John

    2013-12-26

    Increasing resistance to every major class of antibiotics and a dearth of novel classes of antibacterial agents in development pipelines has created a dwindling reservoir of treatment options for serious bacterial infections. The bacterial type IIA topoisomerases, DNA gyrase and topoisomerase IV, are validated antibacterial drug targets with multiple prospective drug binding sites, including the catalytic site targeted by the fluoroquinolone antibiotics. Growing resistance to fluoroquinolones, frequently mediated by mutations in the drug-binding site, is increasingly limiting the utility of this antibiotic class, prompting the search for other inhibitor classes that target different sites on the topoisomerase complexes. The highly conserved ATP-binding subunits of DNA gyrase (GyrB) and topoisomerase IV (ParE) have long been recognized as excellent candidates for the development of dual-targeting antibacterial agents with broad-spectrum potential. However, to date, no natural product or small molecule inhibitors targeting these sites have succeeded in the clinic, and no inhibitors of these enzymes have yet been reported with broad-spectrum antibacterial activity encompassing the majority of Gram-negative pathogens. Using structure-based drug design (SBDD), we have created a novel dual-targeting pyrimidoindole inhibitor series with exquisite potency against GyrB and ParE enzymes from a broad range of clinically important pathogens. Inhibitors from this series demonstrate potent, broad-spectrum antibacterial activity against Gram-positive and Gram-negative pathogens of clinical importance, including fluoroquinolone resistant and multidrug resistant strains. Moreover, lead compounds have been discovered with clinical potential; they are well tolerated in animals, and efficacious in Gram-negative infection models.

  19. TITLE AUTHORS SUBJECT SUBJECT RELATED DESCRIPTION PUBLISHER AVAILABILI...

    Office of Scientific and Technical Information (OSTI)

    at Par Pond consists of fiberglass tanks that can maintain small organisms such as fish and amphibians Thirty of the tanks have sealed sup Cs sources suspended above them...

  20. "Title","Creator/Author","Publication Date","OSTI Identifier...

    Office of Scientific and Technical Information (OSTI)

    at Par Pond consists of 48 fiberglass tanks that can maintain small organisms such as fish and amphibians. Thirty of the tanks have sealed sup 137Cs sources suspended above...

  1. Savannah River Ecology Laboratory Annual Technical Progress Report...

    Office of Scientific and Technical Information (OSTI)

    at Par Pond consists of 48 fiberglass tanks that can maintain small organisms such as fish and amphibians. Thirty of the tanks have sealed sup 137Cs sources suspended above...

  2. Savannah River Ecology Laboratory Annual Technical Progress Report...

    Office of Scientific and Technical Information (OSTI)

    ... The 1-acre facility at Par Pond consists of 48 fiberglass tanks that can maintain small organisms such as fish and amphibians. Thirty of the tanks have sealed sup 137Cs sources ...

  3. Search for: All records | SciTech Connect

    Office of Scientific and Technical Information (OSTI)

    ... The 1-acre facility at Par Pond consists of 48 fiberglass tanks that can maintain small organisms such as fish and amphibians. Thirty of the tanks have sealed sup 137Cs sources ...

  4. Simulink/PARS Integration Support

    SciTech Connect (OSTI)

    Vacaliuc, B.; Nakhaee, N.

    2013-12-18

    The state of the art for signal processor hardware has far out-paced the development tools for placing applications on that hardware. In addition, signal processors are available in a variety of architectures, each uniquely capable of handling specific types of signal processing efficiently. With these processors becoming smaller and demanding less power, it has become possible to group multiple processors, a heterogeneous set of processors, into single systems. Different portions of the desired problem set can be assigned to different processor types as appropriate. As software development tools do not keep pace with these processors, especially when multiple processors of different types are used, a method is needed to enable software code portability among multiple processors and multiple types of processors along with their respective software environments. Sundance DSP, Inc. has developed a software toolkit called “PARS”, whose objective is to provide a framework that uses suites of tools provided by different vendors, along with modeling tools and a real time operating system, to build an application that spans different processor types. The software language used to express the behavior of the system is a very high level modeling language, “Simulink”, a MathWorks product. ORNL has used this toolkit to effectively implement several deliverables. This CRADA describes this collaboration between ORNL and Sundance DSP, Inc.

  5. Across the Pond Newsletter Issue 1

    Office of Environmental Management (EM)

    Templates Acquisition Templates On September 28, 2010, four draft acquisition templates (Competitive Range Exclusion Letter, Competitive Range Inclusion Letter - Written Discussions, Competitive Range Inclusion Letter - Written and Oral Discussions, and Proposal Receipt Checklist) were distributed for Procurement Director (PD) and Head of Contracting Activity (HCA) review and comment. All comments received were considered and changes were made as appropriate. The final versions of the four

  6. Across the Pond Newsletter Issue 2

    Office of Environmental Management (EM)

    - NDA relationship recognized at International Environmental Cleanup Conference e ICEM '09 conference held in Liverpool, UK Oct 10-16th drew participants from all over the world including a high- level presence from DOE's Office of Environmental Management (EM). Dr. Samit K. Bhattacharyya, Laboratory Director, Savannah River National Laboratory, gave an opening session presentation on behalf of Dr. Inés R. Triay, Assistant Secretary for Environmental Management, who at the last minute was

  7. Across the Pond Newsletter Issue 6

    Office of Environmental Management (EM)

    Members of DOE's Office of Environmental Management (EM) and the UK's Nuclear Decommissioning Authority (NDA) held their 8th Standing Committee Meeting on March 2, 2011, at the annual Waste Management 2011 Conference in Phoenix, AZ. The meeting focused on the progress achieved since the last time the committee met in the UK in October 2010 as well as new areas for collaboration such as Project Management and Supply Chain Management. The general concensus was that the collaboration efforts are

  8. Across the Pond Newsletter Issue 4

    Office of Environmental Management (EM)

    with the level of cooperation, integration, and teamwork between NNSA, EM, and the ... IRP are to: 1. Open the doors for the international radioactive waste management community ...

  9. Construction of Ash Pond Isolation Dike.

    Office of Legacy Management (LM)

  10. Sampling and Analysis of Pond 2, Pond 5, and the P-Reactor Canal Sediments

    SciTech Connect (OSTI)

    Halverson, N.V.

    1998-11-25

    This report discusses the procedures used to perform the sampling, the methods used to analyze the samples, and the results.

  11. Ordered structures in YBa/sub 2/Cu/sub 3/O/sub 7-y/, La/sub 2-x/Sr/sub x/CuO/sub 4-par. delta/ and related perovskites

    SciTech Connect (OSTI)

    Mitchell, T.E.; Roy, T.; Fisk, Z.; Smith, J.L.

    1988-01-01

    Electron microscopy and electron diffraction studies have been performed on the superconducting oxides YBa/sub 2/Cu/sub 3/O/sub 7-y/, GdBa/sub 2/Cu/sub 3/O/sub 7-y/ and La/sub 2-x/Sr/sub x/CuO/sub 4-par. delta/ as well as the related perovskites La/sub 2/CuO/sub 4/, Eu/sub 2/CuO/sub 4/ and Gd/sub 2/CuO/sub 4/. Extra reflections are commonly observed in all the cases. For example, in the 123 compounds, in situ heating leads to transformations from orthorhombic to tetragonal with a loss of twin structure; on cooling the oxygen vacancies re-order in the basal plane to give 1/3(100)* or 1/4(110)* diffraction spots. In tetragonal Eu/sub 2/CuO/sub 4/ and Gd/sub 2/CuO/sub 4/, the (001) diffraction patterns often have extra spots at 1/2(110)* or at 1/4(110)* positions. Extra spots are also observed in La/sub 2/CuO/sub 4/ (orthorhombic) but this is probably due to the space group being primitive rather than centered. These observations are discussed in terms of the ordering of oxygen vacancies in the Cu-O planes of the various perovskite structures. 6 figs.

  12. PARS II Training Materials | Department of Energy

    Energy Savers [EERE]

    "how to" exercises for each course are available for download. Users who are attending Web classes should download these documents prior to attending the class. Slides from the...

  13. PARS IIe Account Request | Department of Energy

    Energy Savers [EERE]

    Action Program | Department of Energy Overview of the U.S. Department of Energy Formerly Utilized Sites Remedial Action Program Overview of the U.S. Department of Energy Formerly Utilized Sites Remedial Action Program Paper presented at the Waste Management 2012 Conference. February 26 through March 1, 2012, Phoenix, Arizona. Christopher Clayton, Vijendra Kothari, and Ken Starr, U.S. Department of Energy Office of Legacy Management Joey Gillespie and Michael Widdop, S.M. Stoller Corporation,

  14. Savannah River Technology Center monthly report, July 1995

    SciTech Connect (OSTI)

    Ferrell, J.M.

    1995-07-01

    Progress is reported in the context of: tritium, separations, environmental, waste management, and general affairs. Emphasized topics include: metal hydrides, valves, sampling, water contamination, Par pond, F and H canyon tanks, tritium transport models, landfill stabilization, pumps, waste storage, and chemical analyzers.

  15. Systems and economic analysis of microalgae ponds for conversion...

    Office of Scientific and Technical Information (OSTI)

    W.J. 01 COAL, LIGNITE, AND PEAT; 09 BIOMASS FUELS; BIOMASS; PRODUCTION; CARBON DIOXIDE; AIR POLLUTION CONTROL; METABOLISM; WASTE PRODUCT UTILIZATION; ALGAE; CULTIVATION; COAL;...

  16. Across the Pond Newsletter Issue 1 | Department of Energy

    Office of Environmental Management (EM)

    on Joint UK NDAUS DOE Activities and Initiatives Issue 1: Summer 2009. In this issue: The US Department of Energy (DOE) UK Nuclear Decommissioning Authority (NDA) Bilateral ...

  17. EA-1075: Proposed Casey's Pond Improvement Project, Batavia, Illinois

    Broader source: Energy.gov [DOE]

    This EA evaluates the environmental impacts of a proposed system upgrade to meet improved operational criteria on the current Industrial Cooling Water distribution system used in the fixed target...

  18. Solar-thermal-energy collection/storage-pond system

    DOE Patents [OSTI]

    Blahnik, D.E.

    1982-03-25

    A solar thermal energy collection and storage system is disclosed. Water is contained, and the water surface is exposed directly to the sun. The central part of an impermeable membrane is positioned below the water's surface and above its bottom with a first side of the membrane pointing generally upward in its central portion. The perimeter part of the membrane is placed to create a watertight boundary separating the water into a first volume which is directly exposable to the sun and which touches the membranes first side, and a second volumn which touches the membranes second side. A salt is dissolved in the first water volume.

  19. Systems and economic analysis of microalgae ponds for conversion...

    Office of Scientific and Technical Information (OSTI)

    ... Subject: 01 COAL, LIGNITE, AND PEAT; 09 BIOMASS FUELS; BIOMASS; PRODUCTION; CARBON DIOXIDE; AIR POLLUTION CONTROL; METABOLISM; WASTE PRODUCT UTILIZATION; ALGAE; CULTIVATION; COAL; ...

  20. Sandia Energy - Sandian Todd Lane's "Pond Crash Forensics" Project...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    team, as well as a very strong example of how a technology platform developed by the RapTOR grand challenge can have multiple applications, such as algal biofuels (and central to...

  1. MHK Projects/Twin Pond | Open Energy Information

    Open Energy Info (EERE)

    itedicon":"","lines":,"polygons":,"circles":,"rectangles":,"copycoords":false,"static":false,"wmsoverlay":"","layers":,"controls":"pan","zoom","type","scale","streetview...

  2. Across the Pond Newsletter Issue 6 | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Waste Management 2011 Highlights US DOE-UK NDA links US Congress Seeks Lessons Learned from UK Reprocessing Third International Technical Exchange on Long-term Glass Corrosion held ...

  3. Engineers Drawing: Ash Pond Isolation Dike Plan. Revision 4.

    Office of Legacy Management (LM)

  4. Engineers Drawing: Ash Pond Isolation Dike Sections and Deetails

    Office of Legacy Management (LM)

  5. Remediation of a large contaminated reactor cooling reservoir: Resolving and environmental/regulatory paradox

    SciTech Connect (OSTI)

    Bowers, J.A.: Gladden, J.B.; Hickey, H.M.; Jones, M.P.; Mackey, H.E.; Mayer, J.J.; Doswell, A.

    1994-05-01

    This paper presents a case study of a former reactor cooling water reservoir, PAR Pond, located Savannah River Site. PAR Pond, a 2640 acre, man-made reservoir was built in 1958 and until 1988, received cooling water from two DOE nuclear production reactors, P and R. The lake sediments were contaminated with low levels of radiocesium (CS-137) and transuranics in the late 1950s and early 1960s because of leaking fuel elements. Elevated levels of mercury accumulated in the sediments from pumping water from the Savannah River to maintain a full pool. PAR Ponds` stability, size, and nutrient content made a significant, unique, and highly studied ecological resource for fish and wildlife populations until it was partially drained in 1991 due to a depression in the downslope of the earthen dam. The drawdown, created 1340 acres of exposed, radioactively contaminated sediments along 33 miles of shoreline. This led US EPA to declare PAR Pond as a CERCLA operable unit subject to remediation. The drawdown also raised concerns for the populations of aquatic plants, fish, alligators, and endangered species and increased the potential for off-site migration of contaminated wildlife from contact with the exposed sediments. Applicable regulations, such as NEPA and CERCLA, require wetland loss evaluations, human health and ecological risk assessments, and remediation feasibility studies. DOE is committed to spending several million dollars to repair the dam for safety reasons, even though the lake will probably not be used for cooling purposes. At the same time, DOE must make decisions whether to refill and expend additional public funds to maintain a full pool to reduce the risks defined under CERCLA or spend hundreds of millions in remediation costs to reduce the risks of the exposed sediments.

  6. fdm3da_parV1.0

    Energy Science and Technology Software Center (OSTI)

    2002-01-23

    FORTRAN90 software computes synthetic induction log responses in fully 3D anistropic geoelectric media.

  7. PEP TALK "Policy - EVMS - PARS" Update, Mel Frank, Chief, Project...

    Office of Environmental Management (EM)

    Workshop, features and capabilities of the new PM Website, EVMS Roadside Assist visits, EVMS Training Snippets, PMCDP classroom and online training, as well as other news. ...

  8. Pond Crash Forensics: Presumptive identification of pond crash agents by next generation sequencing in replicate raceway mass cultures of Nannochloropsis salina

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Carney, Laura T.; Wilkenfeld, Joshua S.; Lane, Pam D.; Solberg, Owen D.; Fuqua, Zachary B.; Cornelius, Nina G.; Gillespie, Shaunette; Williams, Kelly P.; Samocha, Tzachi M.; Lane, Todd W.

    2016-06-02

    Productivity of algal mass culture can be severely reduced by contaminating organisms. It is, therefore, important to identify contaminants, determine their effect on productivity and, ultimately, develop countermeasures against such contamination. In this paper, we utilized microbiome analysis by second-generation sequencing of small subunit rRNA genes to characterize the predator and pathogen burden of open raceway cultures of Nannochloropsis salina. Samples were analyzed from replicate raceways before and after crashes. In one culture cycle, we identified two algivorous species, the rotifer Brachionus and gastrotrich Chaetonotus, the presence of which may have contributed to the loss of algal biomass. In themore » second culture cycle, the raceways were treated with hypochlorite in an unsuccessful attempt to interdict the crash. Finally, our analyses were shown to be an effective strategy for the identification of the biological contaminants and the characterization of intervention strategies.« less

  9. Integration of geographic information systems and logistic multiple regression for aquatic macrophyte modeling

    SciTech Connect (OSTI)

    Narumalani, S.; Jensen, J.R.; Althausen, J.D.; Burkhalter, S.; Mackey, H.E. Jr.

    1994-06-01

    Since aquatic macrophytes have an important influence on the physical and chemical processes of an ecosystem while simultaneously affecting human activity, it is imperative that they be inventoried and managed wisely. However, mapping wetlands can be a major challenge because they are found in diverse geographic areas ranging from small tributary streams, to shrub or scrub and marsh communities, to open water lacustrian environments. In addition, the type and spatial distribution of wetlands can change dramatically from season to season, especially when nonpersistent species are present. This research, focuses on developing a model for predicting the future growth and distribution of aquatic macrophytes. This model will use a geographic information system (GIS) to analyze some of the biophysical variables that affect aquatic macrophyte growth and distribution. The data will provide scientists information on the future spatial growth and distribution of aquatic macrophytes. This study focuses on the Savannah River Site Par Pond (1,000 ha) and L Lake (400 ha) these are two cooling ponds that have received thermal effluent from nuclear reactor operations. Par Pond was constructed in 1958, and natural invasion of wetland has occurred over its 35-year history, with much of the shoreline having developed extensive beds of persistent and non-persistent aquatic macrophytes.

  10. SHOCKED AND SCORCHED: THE TAIL OF A TADPOLE IN AN INTERSTELLAR POND

    SciTech Connect (OSTI)

    Sahai, R.; Morris, M. R.; Claussen, M. J.

    2012-05-20

    We report multi-wavelength observations of the far-infrared source IRAS 20324+4057, including high-resolution optical imaging with the Hubble Space Telescope, and ground-based near-infrared, millimeter-wave and radio observations. These data show an extended, limb-brightened, tadpole-shaped nebula with a bright, compact, cometary nebula located inside the tadpole head. Our molecular line observations indicate that the Tadpole is predominantly molecular with a total gas mass exceeding 3.7 M{sub Sun }. Our radio continuum imaging and archival Spitzer IRAC images show the presence of additional tadpole-shaped objects in the vicinity of IRAS 20324+4057 that share a common east-west head-tail orientation: we propose that these structures are small, dense molecular cores that originated in the Cygnus cloud and are now being (1) photoevaporated by the ultraviolet radiation field of the Cyg OB2 No. 8 cluster located to the northwest; and (2) shaped by ram pressure of a distant wind source or sources located to the west, blowing ablated and photoevaporated material from their heads eastward. The ripples in the tail of the Tadpole are interpreted in terms of instabilities at the interface between the ambient wind and the dense medium of the former.