Sample records for 115-kilovolt kv transmission

  1. EIS-0379- Rebuild of the Libby (FEC) to Troy Section of BPA’s 115-kilovolt Transmission Line in Libby, Lincoln County, Montana

    Broader source: Energy.gov [DOE]

    This Environmental Impact Statement (EIS) assesses the potential environmental impacts that would result from a proposed Department of Energy (DOE) action on the proposed rebuilding, operation, and maintenance of a 17-mile-long portion of BPA’s Libby to Bonners Ferry 115-kilovolt (kV) Transmission Line in Lincoln County, Montana. The portion to be rebuilt would start at Flathead Electric Cooperative’s (FEC) Libby Substation, in the town of Libby, Montana, and proceed west along an existing right-of-way for about 17 miles, terminating at BPA’s Troy Substation just east of the town of Troy, Montana.

  2. EA-1967: Hills Creek-Lookout Point Transmission Line Rebuild, Lane County, Oregon

    Broader source: Energy.gov [DOE]

    Bonneville Power Administration is preparing an EA to assess potential environmental impacts of the proposed rebuild of its 26-mile 115 kilovolt (kV) wood-pole Hills Creek-Lookout Point transmission line, which is generally located between Lowell and Oakridge, in Lane County, Oregon.

  3. EA-1961: Kalispell-Kerr Transmission Line Rebuild Project, Kalispell and Polson, Montana

    Broader source: Energy.gov [DOE]

    Bonneville Power Administration is preparing an EA to evaluate potential environmental impacts of rebuilding its 41-mile long 115 kilovolt (kV) wood-pole Kalispell-Kerr transmission line between Kalispell and Polson, Montana. Additional information is available on the project website, http://efw.bpa.gov/environmental_services/Document_Library/KALISPELL_KERR/.

  4. EA-1950: Grand Coulee-Creston Transmission Line Rebuild; Grant and Lincoln Counties, Washington

    Broader source: Energy.gov [DOE]

    Bonneville Power Administration prepared this EA to evaluate potential environmental impacts of rebuilding approximately 28 miles of the Grand Coulee-Creston No. 1 115-kilovolt (kV) transmission line between Coulee Dam in Grant County and Creston in Lincoln County, Washington.

  5. Environmental Assessment of the Gering-Stegall 115-kV Transmission Line Consolidation Project, Scotts Bluff County, Nebraska

    SciTech Connect (OSTI)

    NONE

    1995-05-01T23:59:59.000Z

    The Department of Energy (DOE), Western Area Power Administration (Western) proposes to consolidate segments of two transmission lines near the Gering Substation in Gering, Nebraska. The transmission lines are both located in Scotts Bluff County, Nebraska. The transmission lines are both located in Scotts Bluff County, Nebraska, within the city of Gering. Presently, there are three parallel 115-kilovolt (kV) transmission lines on separate rights-of-way (ROW) that terminate at the Gering Substation. The project would include dismantling the Archer-Gering wood-pole transmission line and rebuilding the remaining two lines on single-pole steel double circuit structures. The project would consolidate the Gering-Stegall North and Gering-Stegall South 115-kV transmission lines on to one ROW for a 1.33-mile segment between the Gering Substation and a point west of the Gering Landfill. All existing wood-pole H-frame structures would be removed, and the Gering-Stegall North and South ROWs abandoned. Western is responsible for the design, construction, operation, and maintenance of the line. Western prepared an environmental assessment (EA) that analyzed the potential environmental impacts of the proposed construction, operation, and maintenance of the 115-kV transmission line consolidation. Based on the analyses in the EA, the DOE finds that the proposed action is not a major Federal action significantly affecting the quality of the human environment, within the meaning of the National Environmental Policy Act of 1969 (NEPA).

  6. Big George to Carter Mountain 115-kV transmission line project, Park and Hot Springs Counties, Wyoming. Environmental Assessment

    SciTech Connect (OSTI)

    Not Available

    1994-02-01T23:59:59.000Z

    The Western Area Power Administration (Western) is proposing to rebuild, operate, and maintain a 115-kilovolt (kV) transmission line between the Big George and Carter Mountain Substations in northwest Wyoming (Park and Hot Springs Counties). This environmental assessment (EA) was prepared in compliance with the National Environmental Policy Act (NEPA) and the regulations of the Council on Environmental Quality (CEQ) and the Department of Energy (DOE). The existing Big George to Carter Mountain 69-kV transmission line was constructed in 1941 by the US Department of Interior, Bureau of Reclamation, with 1/0 copper conductor on wood-pole H-frame structures without an overhead ground wire. The line should be replaced because of the deteriorated condition of the wood-pole H-frame structures. Because the line lacks an overhead ground wire, it is subject to numerous outages caused by lightning. The line will be 54 years old in 1995, which is the target date for line replacement. The normal service life of a wood-pole line is 45 years. Under the No Action Alternative, no new transmission lines would be built in the project area. The existing 69-kV transmission line would continue to operate with routine maintenance, with no provisions made for replacement.

  7. EA-1931: Keeler to Tillamook Transmission Line Rebuild Project, Washington and Tillamook Counties, Oregon

    Broader source: Energy.gov [DOE]

    Bonneville Power Administration prepared this EA to assess the potential environmental impacts of the proposed rebuild of the Keeler-Forest Grove and Forest Grove-Tillamook 115-kilovolt (kV) transmission lines between the cities of Hillsboro and Tillamook, in Washington and Tillamook Counties, Oregon. The 58-mile-long rebuild would include replacement of all wood-pole structures over 10 years in age. Some existing access roads would be improved to accommodate construction equipment and some new road access would be acquired or constructed in areas where access is not available.

  8. El Paso Electric Company Diablo Substation to the US-Mexico border 115kV transmission line project. Final Environmental Assessment

    SciTech Connect (OSTI)

    Not Available

    1992-04-01T23:59:59.000Z

    This Environmental Assessment documents the analysis of alternative corridors for development and operation of a proposed 115 kilovolt transmission line using private lands and transporting power to the US-Mexico international border. The project will require (1) an amendment to El Paso Electric Company`s existing export authorization to transfer power across this border, and (2) a Presidential Permit for construction of the transmission line. The project would be located in Dona Ana county in southern New Mexico, approximately five miles west of El Paso, Texas. The alternative corridors, specific locations within those corridors, and structure types are identified and analyzed in the environmental studies.

  9. Oracle-Saguaro 115-kV Transmission Line Routine Maintenance Project...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Oracle-Saguaro 115-kV Transmission Line Routine Maintenance Project, Mile 6 to Oracle Substation Categorical Exclusion Continuation Sheet Project Description Maintenance work at...

  10. EIS-0344: Grand Coulee-Bell 500 kV Transmission Line

    Broader source: Energy.gov [DOE]

    This EIS analyzes DOE's proposed action for the construction and operation of the proposed Grand Coulee-Bell 500-kV Transmission Line Project.

  11. Wild Horse 69-kV transmission line environmental assessment

    SciTech Connect (OSTI)

    NONE

    1996-12-01T23:59:59.000Z

    Hill County Electric Cooperative Inc. (Hill County) proposes to construct and operate a 69-kV transmission line from its North Gildford Substation in Montana north to the Canadian border. A vicinity project area map is enclosed as a figure. TransCanada Power Corporation (TCP), a Canadian power-marketing company, will own and construct the connecting 69-kV line from the international border to Express Pipeline`s pump station at Wild Horse, Alberta. This Environmental Assessment is prepared for the Department of Energy (DOE) as lead federal agency to comply with the requirements of the National Environmental Policy Act (NEPA), as part of DOE`s review and approval process of the applications filed by Hill County for a DOE Presidential Permit and License to Export Electricity to a foreign country. The purpose of the proposed line is to supply electric energy to a crude oil pump station in Canada, owned by Express Pipeline Ltd. (Express). The pipeline would transport Canadian-produced oil from Hardisty, Alberta, Canada, to Caster, Wyoming. The Express Pipeline is scheduled to be constructed in 1996--97 and will supply crude oil to refineries in Wyoming and the midwest.

  12. EA-1456: Final Environmental Assessment | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    Cheyenne- Miracle Mile (CH-MM) and Ault-Cheyenne (AU-CH) 115 kilovolt (115-kV ) transmission lines to 230-kV. The proposed project consists of rebuilding these transmission lines...

  13. Survey of Magnetic Fields Near BPA 230-kV and 500-kV Transmission Lines.

    SciTech Connect (OSTI)

    Perrin, Nancy; Aggarwal, Rajinder Pal; Bracken, T. Daniel

    1991-05-20T23:59:59.000Z

    The purpose of this study was to characterize typical levels and variability of 60Hz magnetic fields at the centerline and edge of right-of-way of Bonneville Power Administration (BPA) 230-kV and 500-kV transmission lines. This was accomplished by taking magnetic field measurements at over 800 spans in Oregon and Washington. The spans were sampled using a stratified random sampling procedure with region (East vs. West), voltage (230-kV vs 500-kV), and circuit configuration as strata. There were five different circuit configuration groups for each region/voltage category requiring a total of 200 strata. Magnetic field measurements were taken at 13 locations under each span using an EMDEX-C as a survey meter. Additional information recorded for each span included conductor height (at 10 locations), right-of-way width, longitudinal and lateral slope, time of day, vegetation, terrain, weather conditions, temperature, wind speed, span length and presence of other lines in the corridor. 9 refs., 17 figs., 26 tabs.

  14. EA-1665: Davis-Kingman 69-kV Transmission Line Rebuild Project, Arizona

    Broader source: Energy.gov [DOE]

    Western plans to rebuild a 26.6-mile-long portion of the existing 27.3-mile-long Davis–Kingman Tap 69-kV Transmission Line within the existing ROW in order to improve the reliability of the transmission service.

  15. Marys Lake 69/115-kV transmission line upgrade and substation expansion projects

    SciTech Connect (OSTI)

    NONE

    1996-05-01T23:59:59.000Z

    Western Area Power Administration (Western) and the Platte River Power Authority (Platte River) propose to upgrade portions of the existing electric transmission and substation system that serves the Town of Estes Park, Colorado. The existing transmission lines between the Estes Power Plant Switchyard and the Marys Lake Substation include a 115,000 volt (115-kV) line and 69,000 volt (69-kV) line. Approximately one mile is a double-circuit 115/69-kV line on steel lattice structures, and approximately two miles consists of separate single-circuit 115-kV and a 69-kV lines, constructed on wood H-Frame structures. Both lines were constructed in 1951 by the US Bureau of Reclamation. The existing transmission lines are on rights-of-way (ROW) that vary from 75 feet to 120 feet and are owned by Western. There are 48 landowners adjacent to the existing ROW. All of the houses were built adjacent to the existing ROW after the transmission lines were constructed. Upgrading the existing 69-kV transmission line between the Marys Lake Substation and the Estes Power Plant Switchyard to 115-kV and expanding the Marys Lake Substation was identified as the most effective way in which to improve electric service to Estes Park. The primary purpose and need of the proposed project is to improve the reliability of electric service to the Town of Estes Park. Lack of reliability has been a historical concern, and reliability will always be less than desired until physical improvements are made to the electrical facilities serving Estes Park.

  16. Development of a thyristor valve for next generation 500kV HVDC transmission systems

    SciTech Connect (OSTI)

    Hasegawa, T. [Kansai Electric Power Co., Inc., Osaka (Japan)] [Kansai Electric Power Co., Inc., Osaka (Japan); Yamaji, K. [Shikoku Electric Power Co., Inc., Takamatsu (Japan)] [Shikoku Electric Power Co., Inc., Takamatsu (Japan); Irokawa, H. [Electric Power Development Co., Ltd., Tokyo (Japan)] [Electric Power Development Co., Ltd., Tokyo (Japan); Shirahama, H.; Tanaka, C.; Akabane, K.

    1996-10-01T23:59:59.000Z

    A high voltage thyristor valve is the basic component of an HVDC transmission system. Development of a 500kV valve for next generation HVDC transmission systems is described. First, the power loss of the valve is analyzed to decide a reasonable wafer size for the light triggered thyristor. From these results, a six inch diameter wafer size is selected. The light triggered thyristor, with ratings of 8kV and 3.5kA, is developed using the six inch wafer. The designing of the valve employing the thyristor and test results with the prototype valve prove that a 500kV valve can be realized by the design method.

  17. EA-2007: Groton-Ordway 115-kV Transmission Line, Groton, South Dakota

    Broader source: Energy.gov [DOE]

    DOE’s Western Area Power Administration (Upper Great Plains Region) is preparing an EA that assesses the potential environmental impacts of a proposal to construct a new 115-kV transmission line that would connect Western’s existing Groton and Ordway Substations near Groton, South Dakota.

  18. EIS-0107: Mead-Phoenix +500-kV Direct Current Transmission Line

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy’s Western Area Power Administration (WAPA) prepared this statement to analyze the potential environmental and socioeconomic impacts arising from WAPA and regional project sponsors’ proposal to construct a 500 kilovolt (kV) alternating current (AC) transmission line with the capability to be upgraded later to 500kV direct current (DC), connecting the Westwing Substation, located north of Phoenix, Arizona, with a new McCullough II Substation, located approximately 14 miles west of Boulder City, Nevada. This statement modifies a previously prepared federal statement from which the participants' election to proceed had not occurred at the time this statement was prepared.

  19. EIS-0365: Imperial-Mexicali 230-kV Transmission Lines

    Broader source: Energy.gov [DOE]

    On February 27, 2001, Baja California Power, Inc. (hereafter referred to as Intergen), InterGen Aztec Energy, V.B.V., filed an application with DOE, Office of Fossil Energy, for a Presidential permit that would allow construction and connection of a double-circuit, 230-kV transmission line extending from the Imperial Valley Substation in California for a distance of about 6 mi (10 km) to a point west of Calexico at the U.S.-Mexico border.

  20. Sidney-North Yuma 230-kV Transmission Line Project, Colorado and Nebraska

    SciTech Connect (OSTI)

    Not Available

    1991-06-01T23:59:59.000Z

    This report describes the need for a 230-kV overhead transmission line to supply power from Sidney, Nebraska to eastern Colorado. The alternative scenario compared to construction of the line is No Action. Rejected alternatives include underground lines and different routing paths, with a possible extension to the Sterling area. Both scenarios are evaluated for environmental effects, cost, and consequences for the eastern Colorado region. The proposed route is determined to be the environmentally preferred choice. 120 refs., 6 figs., 13 tabs. (MHB)

  1. EIS-0505: Vantage to Pomona Heights 230 kV Transmission Line Project, Yakima, Grant, Benton and Kittitas Counties, Washington

    Broader source: Energy.gov [DOE]

    The Bureau of Land Management is preparing, with DOE’s Bonneville Power Administration (BPA) as a cooperating agency, an EIS that evaluates the potential environmental impacts of a proposal to construct a 60- to 67-mile long 230-kV transmission line. BPA’s proposed action is to interconnect the transmission line to an existing BPA substation.

  2. EIS-0483: Estes to Flatiron Substation Transmission Lines Rebuild Project, Larimer County, Colorado

    Broader source: Energy.gov [DOE]

    Western Area Power Administration (Western) – with USDA Forest Service, Arapaho and Roosevelt National Forest, as a cooperating agency – is preparing an EIS that analyzes the potential environmental impacts of a proposal to rebuild and upgrade two 115-kilovolt single-circuit transmission lines between the Flatiron Substation and the intersection of Mall Road and U.S. Highway 36 in Estes Park, Larimer County, Colorado. Additional information is available on Western’s project website.

  3. EA-1981: Bonneville-Hood River Transmission Line Rebuild, Multnomah and Hood River Counties, Oregon

    Broader source: Energy.gov [DOE]

    Bonneville Power Administration (BPA) is preparing an EA to assess potential environmental impacts of a proposal to rebuild its 24-mile long, 115 kilovolt Bonneville-Hood River transmission line. The existing line runs between the Bonneville Powerhouse at Bonneville Dam in Multnomah County, Oregon, and BPA's existing Hood River Substation in Hood River County, Oregon. The project would include replacing structures and conductor wires, improving access roads, and constructing new access roads or trails where needed.

  4. EA-1679: Grand Coulee's Third Powerplant 500-kV Transmission Line Replacement Project, Grant and Okanogon Counties, Washington

    Broader source: Energy.gov [DOE]

    This EA evaluates potential environmental impacts from the construction and operation of six new 500-kV overhead transmission lines to replace six existing underground lines at Grand Coulee Dam. DOE’s Bonneville Power Administration (BPA), a cooperating agency, was asked by the U. S. Department of the Interior’s Bureau of Reclamation to design and construct the proposed new transmission lines. A Finding of No Significant Impact was issued by BPA in December 2011.

  5. EIS-0159: Record of Decision

    Broader source: Energy.gov [DOE]

    Flatiron-Erie 115-kilovolt Transmission Line Project, Larimer County, Boulder County, Weld County, Colorado

  6. EIS-0025: Miles City-New Underwood 230-kV Electrical Transmission Line, Montana, North Dakota, and South Dakota

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy’s Western Area Power Administration prepared this statement to assess the environmental and socioeconomic implications of its proposed action to construct a 3.28-mile, 230-kV transmission line between Miles City and Baker, Montana , Hettinger, North Dakota , and New Underwood , South Dakota , in Custer and Fallon Counties in Montana, Adams , Bowman , and Slope Counties in North Dakota and Meade, Pennington, and Perkins Counties in South Dakota.

  7. Heavy duty insulator assemblies for 500-kV bulk power transmission line with large diameter octagonalbundled conductor

    SciTech Connect (OSTI)

    Tsujimoto, K.; Hayase, I.; Hirai, J.; Inove, M.; Naito, K.; Yukino, T.

    1982-11-01T23:59:59.000Z

    This paper describes the design procedure and the results of field tests on mechanical performances of insulator assemblies newly developed to support octagonal-bundled conductors for 500-kV bulk power transmission. Taking account of conductor-motion-induced peak tensile load, fatigue, torsional torque and others, a successful design has been achieved in two prototype assemblies for such heavy mechanical duties as encountered during conductor galloping or swing. This has been proved throughout three years of the field tests.

  8. Seasonal Patterns of Melatonin, Cortisol, and Progesterone Secretion in Female Lambs Raised Beneath a 500-kV Transmission Line.

    SciTech Connect (OSTI)

    Lee, Jack M.

    1992-06-01T23:59:59.000Z

    Although several kinds of biological effects of electric and magnetic fields have been reported from laboratory studies, few have been independently replicated. When this study was being planned, the suppression of nighttime melatonin in rodents was thought to represent one of the strongest known effects of these fields. The effect had been replicated by a single laboratory for 60-Hz electric fields, and by multiple laboratories for d-c magnetic fields. The primary objective of this study was to determine whether the effect of electric and magnetic fields on melatonin would also occur in sheep exposed to a high voltage transmission line. The specific hypothesis tested by this experiment was as follows: The electrical environment produced by a 60-Hz, 500-kV transmission line causes a depression in nocturnal melatonin in chronically exposed female lambs. This may mimic effects of pinealectomy or constant long-day photoperiods, thus delaying the onset of reproductive cycles. Results of the study do not provide evidence to support the hypothesis. Melatonin concentrations in the sheep exposed to the transmission line showed the normal pattern of low daytime and high nighttime serum levels. As compared to the control group, there were no statistically significant group differences in the mean amplitude, phase, or duration of the nighttime melatonin elevation.

  9. EIS-0078: Jonesboro-Hergett 161-kV Transmission Line

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy's Southwestern Power Administration developed this statement to assess the environmental and socioeconomic impacts of a 161-kilovolt transmission line in Craighead County, Arkansas, including its proposed and alternate routes.

  10. EIS-0399: Montana Alberta Tie Ltd. (MATL) 230-KV Transmission Line

    Broader source: Energy.gov [DOE]

    DOE, jointly with the Montana Department of Environmental Quality (MDEQ), prepared an EIS that evaluated the potential environmental impacts of a proposed international transmission line that would cross the U.S.-Canada border in northwest Montana.

  11. EIS-0011: New Melones 230-kV Electrical Transmission Line, Central Valley Project, California

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy's Western Area Power Administration prepared this statement to evaluate the environmental impacts of proposed development of an electrical transmission system for the New Melones Power Plant.

  12. International 345 kV transmission line to Highgate, Vermont: environmental assessment

    SciTech Connect (OSTI)

    Not Available

    1985-02-01T23:59:59.000Z

    The action under consideration is the issuance of a Presidential permit to the Vermont Electric Power Company, Inc. (VELCO) for the construction, operation, maintenance and connection of a facility that will cross the United States-Canada border for international transmission of electric energy. The proposed transmission facilities will consist of a 7.5 mile, alternating current (ac) transmission line and a 200 MW back-to-back direct current (dc) converter terminal station. None of the facilities will involve any polluting emissions. The construction and maintenance of the proposed converter terminal station and transmission facilities will have little or no impact on the geologic features of the region. The transmission line will have little or no effect on agricultural land. Impacts on commercial forestry in the area will be minimal. The proposed route will require clearing about 36 acres of forest. The proposed transmission line and converter terminal site will have no effect on recreational activities, mining activites, residential, commercial, or industrial land use. The proposed corridor will have a minimal impact on area terrestrial wildlife and plant communities. The proposed project will have little or no impact on future population distribution, the operation of local services, employment and economic benefit, or housing in either Franklin or Highgate. 16 references, 3 figures. (ACR)

  13. EIS-0103: New England/Hydro-Quebec 450-kV Direct Current Transmission Line Interconnection

    Broader source: Energy.gov [DOE]

    The Economic Regulatory Administration prepared this statement to evaluate the environmental impacts of the construction, maintenance and operation of a 57-mile transmission line from Monroe, New Hampshire, to the U.S./Canadian border for the purpose of economic exchange of power and increased reliability.

  14. EIS-0100: Liberty-Coolidge 230-kV Transmission Line, Arizona

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy’s Western Area Power Administration prepared this statement to assess the potential environmental and socioeconomic implications of various alternatives associated with an upgrade of electrical transmission capability between the Liberty and Coolidge Substations.

  15. EIS-0118: Proposed Eugene-Medford 500-kV Transmission Line

    Broader source: Energy.gov [DOE]

    The U.S. Department of Interior developed this statement to assess the environmental impact of a proposed 500-kilovolt transmission line linking Eugene and Medford, Oregon, that would cross through public lands. The Bonneville Power Administration (BPA) would provide service to the proposed line and is a cooperating agency in the statement. BPA adopted the EIS on 7/10/1985.

  16. EIS-0129: New England/Hydro-Quebec 450 kV Transmission Line Interconnection- Phase II

    Broader source: Energy.gov [DOE]

    The Economic Regulatory Administration issued this EIS to explore the impacts of amending Presidential Permit PP-76 to allow the Vermont Electrical Company to operate at power levels above those stipulated in the permit and to build additional transmission facilities to distribute the increased power.

  17. EA-1551: Montana Alberta Tie Ltd. (MATL) 230-KV Transmission Line

    Broader source: Energy.gov [DOE]

    DOE started to prepare, jointly with the Montana Department of Environmental Quality (MDEQ), an EA that would also serve as a state EIS. The document would evaluate the potential environmental impacts of a proposed international transmission line that would cross the U.S.-Canada border in northwest Montana. Based on comments received on the DOE Draft EA/MDEQ Draft EIS, DOE cancelled preparation of the EA and announced preparation of DOE/EIS-0399 (of the same title).

  18. EIS-0301: NRG Energy Services, Inc., Arizona-Baja California 500 kV Transmission Line

    Broader source: Energy.gov [DOE]

    This EIS analyzes DOE's decision to approve NRG Energy, Inc. (NRG) for a Presidential permit to construct a 500,000-volt transmission line originating at the switchyard of the Palo Verde Nuclear Generating Station near Phoenix, Arizona, and extending approximately 177 miles to the southwest, where it would cross the United States (U.S.) border with Mexico in the vicinity of Calexico, California.

  19. EIS-0091: Garrison-Spokane 500-kV Transmission Project

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy's Bonneville Power Administration (BPA) developed this statement to evaluate the environmental impacts of constructing between 254 and 271 miles of 500-kilovolt transmission line across western Montana and northern Idaho to the Spokane area in order to reinforce a section of the BPA electric power grid and to permit reliable integration of 1,240 megawatts of power produced by Colstrip Units 3 and 4, for use in Montana and throughout the Northwest.

  20. EIS-0112: Rifle to San Juan 345-kV Transmission Line and Associated Facilities

    Broader source: Energy.gov [DOE]

    The U.S. Department of Agriculture - Rural Electrification Administration developed this statement to evaluate the environmental impacts of the Colorado-Ute Electric Association Inc. and the U.s. Department of Energy's Western Area Power Administration (WAPA) constructing and operating a 345-kilovolt transmission line from Rifle, Colorado, to the San Juan Generating Station near Farmington, New Mexico. WAPA served as a cooperating agency in the preparation of this statement and adopted it on 10/30/1984. WAPA assumed the lead role for project implementation after issuance of the final statement.

  1. Development of NS-TACSR with extremely suppressed aeolian noise and its application to 500 kV overhead transmission lines

    SciTech Connect (OSTI)

    Tsujimoto, K.; Furukawa, S. (Kansai Electric Power Co., Inc., Osaka (Japan)); Shimojima, K.; Yamamoto, K. (Hitachi Cable, Ltd., Hitachi (JP))

    1991-10-01T23:59:59.000Z

    Recently in Japan, with the unprecedented advance of residential area development in the suburbs of large cities, it has become quite difficult to secure the routes of EHV transmission lines from nuclear power plants in remote places to the suburbs of large cities, urging resolution of environmental problems related to transmission lines. In Japan, aerodynamic sound produced by conductors and insulators frequently caused noise problems. Having an opportunity of constructing a 500 kV transmission line through a residential are, we made a research to resolve this noise problem. This paper describes the characteristics of aeolian noise and preventive measures against it.

  2. Environmental Assessment for Central Power and Light Company`s proposed Military Highway-CFE tie 138/69-kV transmission line project Brownsville, Cameron County, Texas

    SciTech Connect (OSTI)

    Not Available

    1992-04-01T23:59:59.000Z

    Central Power and Light Company (CPL) intends to upgrade its existing transmission line ties with the Commision Federal de Electricidad (CFE) system in Mexico. CPL currently has a single 69-kilovolt (kV) transmission line in the Brownsville area which connects CPL`s system with the system of CFE. This existing line runs between the Brownsville Switching Station, located on Laredo Road in Brownsville, Cameron County, Texas, and an existing CFE 69-kV line at the Rusteberg Bend of the Rio Grande in Cameron County. Under current conditions of need, the existing 69-kV line does not possess sufficient capability to engage in appropriate power exchanges. Therefore, CPL is proposing to build a new line to link up with CFE. This proposed line would be a double-circuit line, which would (1) continue (on a slightly relocated route) the existing 69-kV tie from CPL`s Brownsville Switching Station to CFE`s facilities, and (2) add a 138-kV tie from the Military Highway Substation, located on Military Highway (US Highway 281), to CFE`s facilities. The proposed 138/69-kV line, which will be constructed and operated by CPL, will be built primarily on steel single-pole structures within an average 60-foot (ft) wide right-of-way (ROW). It will be approximately 6900--9200 ft (1.3--1.7 miles) in length, depending on the alternative route constructed.

  3. Proposed amendment to presidential permit PP-63 and associated modifications to 500 kV international transmission line, Forbes, Minnesota to Manitoba, Canada. [Forbes Substation

    SciTech Connect (OSTI)

    Not Available

    1992-10-01T23:59:59.000Z

    This Addendum to the Final Environmental Assessment for the Proposed Amendment to Presidential Permit PP-63 and Associated Modifications to 500 kV International Transmission Line: Forbes, Minnesota to Manitoba, Canada (DOE/EA-587) addresses Northern States Power Company's (NSP) proposed expansion of the Forbes Substation. The applicant has requested that the expansion take place on the west side of the substation, within the existing property line, instead of on the north side as originally proposed. All of the proposed construction would take place on property already owned by NSP. DOE has reviewed the environmental impacts associated with this minor modification and has determined that the conclusions reached in the environmental assessment and Finding of No Significant Impact prepared in connection with NSP's original amendment request remain valid.

  4. EIS-0450: TransWest Express 600 kV Direct Current Transmission Project in Wyoming, Colorado, Utah, and Nevada

    Broader source: Energy.gov [DOE]

    This EIS, being prepared jointly by DOE’s Western Area Power Administration and the Department of the Interior’s Bureau of Land Management (Wyoming State Office), evaluates the environmental impacts of granting a right-of-way for the TransWest Express 600-kilovolt Direct Current Transmission Project and amending a land use plan. The project consists of an overhead transmission line that would extend approximately 725 miles from south-central Wyoming, through Colorado and Utah. Western proposes to be a joint owner of the project. Additional information is available at http://www.blm.gov/wy/st/en/info/NEPA/documents/hdd/transwest.html.

  5. The Cost of Transmission for Wind Energy: A Review of Transmission Planning Studies

    E-Print Network [OSTI]

    Mills, Andrew D.

    2009-01-01T23:59:59.000Z

    500 and 230 kV 765 kV and 800 kV HVDC 500 and 230 kV 500 kVmi) 138 and 345 kV 345 kV 345 kV 345 kV and HVDC 345kV and HVDC 345 kV 345 kV Note: Total transmission cost is

  6. Proposed amendment for Presidential Permit PP-63 and associated modifications to 500 kV international transmission line, Forbes, Minnesota to Manitoba, Canada Northern States Power Company. Final Environmental Assessment

    SciTech Connect (OSTI)

    Not Available

    1992-02-01T23:59:59.000Z

    Northern States Power Company, (NSP), a Minnesota investor owned utility has applied to the Office of Fossil Energy, United States Department of Energy, to amend Presidential Permit PP-63 to allow for alterations to the 500 kV transmission line and as sedated facilities currently regulated by this permit. The alterations proposed for the 500 kV line owned by NSP are part of a long term effort sponsored by NSP to upgrade the existing NSP transmission system to allow for increased exchange of electricity with the Manitoba Hydro-Electric Board. Presidential Permit PP-63 authorized NSP to construct, connect, operate and maintain a 500 kV line at the United States/Canadian border approximately seven-and-a-half miles west of Warroad in Roseau County, Minnesota. This line connects with a 500 kV line owned and operated by the Manitoba Hydro-Electric Board (MHEB), which extends from Dorsey, Manitoba, Canada to the United States/Canadian border. NSP proposes to increase the electricity transfer capability of this transmission facility by constructing a new 80-acre substation on the existing 500 kV line in Roseau County, Minnesota, and upgrading the existing substation at Forbes, Minnesota. The proposed Roseau substation would contain two 41.5 ohm series capacitor banks. In addition, static VAR compensators are to be installed at the existing Forbes Substation. Approximately 5 acres would be added to the 30-acre Forbes site to house the additional equipment. No new lines would enter or exit the facility. NSP proposes to place the new Roseau Substation in service in May 1993 and to complete the upgrading of the Forbes Substation in March 1994. The primary, initial purpose of these modifications is to enable NSP to import 400 megawatts of electric power from MHEB during the summer months to meet peak electrical demand in the Minneapolis-St. Paul area. It is expected that this power transfer would begin in 1993.

  7. CX-009514: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    the Franklin-Badger Canyon No. 2 and Grandview-Red Mountain No. 1 115 kilovolt transmission lines. CX-009514.pdf More Documents & Publications CX-005673: Categorical Exclusion...

  8. EIS-0032: 500 kV International Transmission Line NSP-TR-1, Forbes, Minnesota to Manitoba, Canada, Northern States Power Company

    Broader source: Energy.gov [DOE]

    The Economic Regulatory Administration developed this EIS to evaluate the environmental impacts of a 500-kilovolt transmission line proposed by the Northern States Power Company to provide a transmission facility for the exchange of electrical energy between Canada and the United States.

  9. Proposed Amendment to Presidential Permit PP-63 and Associated Modifications to 500-kV International Transmission Line: Forbes, Minnesota to Manitoba, Canada, Northern States Power Company. Addendum to the final Environmental Assessment

    SciTech Connect (OSTI)

    Not Available

    1992-10-01T23:59:59.000Z

    This Addendum to the Final Environmental Assessment for the Proposed Amendment to Presidential Permit PP-63 and Associated Modifications to 500 kV International Transmission Line: Forbes, Minnesota to Manitoba, Canada (DOE/EA-587) addresses Northern States Power Company`s (NSP) proposed expansion of the Forbes Substation. The applicant has requested that the expansion take place on the west side of the substation, within the existing property line, instead of on the north side as originally proposed. All of the proposed construction would take place on property already owned by NSP. DOE has reviewed the environmental impacts associated with this minor modification and has determined that the conclusions reached in the environmental assessment and Finding of No Significant Impact prepared in connection with NSP`s original amendment request remain valid.

  10. Proposed amendment to presidential permit PP-63 and associated modifications to 500 kV international transmission line, Forbes, Minnesota to Manitoba, Canada. Addendum to the final environmental assessment

    SciTech Connect (OSTI)

    Not Available

    1992-10-01T23:59:59.000Z

    This Addendum to the Final Environmental Assessment for the Proposed Amendment to Presidential Permit PP-63 and Associated Modifications to 500 kV International Transmission Line: Forbes, Minnesota to Manitoba, Canada (DOE/EA-587) addresses Northern States Power Company`s (NSP) proposed expansion of the Forbes Substation. The applicant has requested that the expansion take place on the west side of the substation, within the existing property line, instead of on the north side as originally proposed. All of the proposed construction would take place on property already owned by NSP. DOE has reviewed the environmental impacts associated with this minor modification and has determined that the conclusions reached in the environmental assessment and Finding of No Significant Impact prepared in connection with NSP`s original amendment request remain valid.

  11. Draft environmental impact statement for construction and operation of the proposed Bangor Hydro-Electric Company`s second 345-kV transmission tie line to New Brunswick

    SciTech Connect (OSTI)

    NONE

    1993-10-01T23:59:59.000Z

    This Draft Environmental Impact Statement (DEIS) was prepared by the US Department of Energy (US DOE). The proposed action is the issuance of Presidential Permit PP-89 by DOE to Bangor Hydro-Electric Company to construct and operate a new international transmission line interconnection to New Brunswick, Canada that would consist of an 83.8 mile (US portion), 345-kilovolt (kV) alternating current transmission line from the US-Canadian border at Baileyville, Maine to an existing substation at Orrington, Maine. The principal environmental impacts of the construction and operation of the transmission line would be incremental in nature and would include the conversion of forested uplands (mostly commercial timberlands) and wetlands to right-of-way (small trees, shrubs, and herbaceous vegetation). The proposed line would also result in localized minor to moderate visual impacts and would contribute a minor incremental increase in the exposure of some individuals to electromagnetic fields. This DEIS documents the purpose and need for the proposed action, describes the proposed action and alternatives considered and provides a comparison of the proposed and alternatives routes, and provides detailed information on analyses of the environmental consequences of the proposed action and alternatives, as well as mitigative measures to minimize impacts.

  12. EIS-0365: Draft Environmental Impact Statement for the Imperial-Mexicali 230-kV Transmission Lines, EIS-0365 (May 2004)

    Broader source: Energy.gov [DOE]

    A U.S. Department of Energy (DOE) Presidential permit is required to construct an electric transmission line across the U.S. international border. On February 27, 2001, Baja California Power, Inc. ...

  13. CX-010686: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Cheyenne Substation KV2A 115-kilovolt Tie Line Installation CX(s) Applied: B4.6 Date: 07/02/2013 Location(s): Wyoming Offices(s): Western Area Power Administration-Rocky Mountain Region

  14. EIS-0339: Presidential Permit Application, GenPower 500 kV Submarine Electric Transmission Cable from Nova Scotia to New York

    Broader source: Energy.gov [DOE]

    The Department of Energy (DOE) announced its intent to prepare an Environmental Impact Statement (EIS) in accordance with the National Environmental Policy Act of 1969 (NEPA) for GenPower New York, L.L.C.’s (GenPower) request for a Presidential permit for a proposed international electric transmission line.

  15. EA-2002: Right-of-Way Application for the Tucson-Apache 115-kV Transmission Line, Pima County, Arizona

    Broader source: Energy.gov [DOE]

    Western Area Power Administration (Western) and the Bureau of Indian Affairs (BIA), as joint lead agencies, prepared an EA that evaluates the potential environmental impacts of a proposal for BIA to grant Western a 150-foot right-of-way across tribal land along the existing Tucson-Apache Transmission Line to replace the previous 100-foot right-of-way, which has expired.

  16. EIS-0067: 230-kV International Transmission Line San Diego County, California to Tijuana, Mexico, San Diego Gas and Electric Company

    Broader source: Energy.gov [DOE]

    The Economic Regulatory Administration and the California Public Utilities Commission jointly prepared this EIS to evaluate the environmental impacts of the construction, maintenance and operation of a 10-mile, 230-kilovolt transmission line across the U.S./Mexico border for the purpose of economic exchange of power and increased reliability.

  17. EA-1899: Rerouting and Renovating of Estes-Flatiron Three Transmission Lines to Double Circuit 115-kV, Larimer County, Colorado

    Broader source: Energy.gov [DOE]

    DOE’s Western Area Power Administration started to prepare an EA to evaluate the environmental impacts of a proposal to reroute and renovate the Estes-Flatiron Three Transmission Lines in Larimer County, Colorado. Based on comments received during the scoping period, Western ended preparation of DOE/EA-1899 and announced its intent to prepare and environmental impact statement, DOE/EIS-0483.

  18. CX-008389: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    Danger Tree Management on Estes-Pole Hill and Pole Hill-Flatiron 115 Kilovolt Transmission Lines CX(s) Applied: B1.3 Date: 03092012 Location(s): Colorado Offices(s): Western...

  19. CX-008719: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    No. 1, Holcomb- Naselle No. 1, and Raymond-Willapa River No. 1, 115 Kilovolt Transmission Lines CX(s) Applied: B1.3 Date: 05162012 Location(s): Washington Offices(s):...

  20. CX-008708: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    on the Chehalis-Olympia No. 1 and Chehalis-Mayfield No. 1, 115 Kilovolt Transmission Lines CX(s) Applied: B1.3 Date: 05252012 Location(s): Washington, Washington...

  1. CX-011614: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Curecanti-Blue Mesa 115-kilovolt Transmission Line Danger Tree Management CX(s) Applied: B1.3 Date: 12/04/2013 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  2. CX-012092: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Tucson-Apache 115-Kilovolt Transmission Line Structure Stabilization Project CX(s) Applied: B1.3 Date: 09/06/2013 Location(s): Arizona, Arizona Offices(s): Western Area Power Administration-Desert Southwest Region

  3. CX-007985: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Acquisition of Cowlitz County Public Utility District's 115-Kilovolt Transmission Line CX(s) Applied: B1.24 Date: 02/24/2012 Location(s): Washington Offices(s): Bonneville Power Administration

  4. CX-012086: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Wray-Wray Tap 115-Kilovolt Transmission Line Construction CX(s) Applied: B4.12 Date: 02/28/2014 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  5. CX-012078: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Danger Tree Management on the Great Cut Tap 115-Kilovolt Transmission Line CX(s) Applied: B1.3 Date: 02/20/2014 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  6. CX-012072: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Archer-Cheyenne North/South 115-kilovolt Transmission Line Structure Replacement CX(s) Applied: B4.13 Date: 03/18/2014 Location(s): Wyoming Offices(s): Western Area Power Administration-Rocky Mountain Region

  7. CX-012084: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Snowy Range-Happy Jack 115-Kilovolt Transmission Line Structure Replacements CX(s) Applied: B1.3 Date: 03/10/2014 Location(s): Wyoming Offices(s): Western Area Power Administration-Rocky Mountain Region

  8. CX-006303: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Interconnection of the Pronghorn Gas Plant 115 Kilovolt Transmission LineCX(s) Applied: B4.11Date: 07/14/2011Location(s): MontanaOffice(s): Western Area Power Administration-Upper Great Plains Region

  9. CX-012734: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Bouse Hills Pumping Plant to Harcuvar 115 Kilovolt Transmission Line, Inset Structure Installation CX(s) Applied: B4.6Date: 41878 Location(s): ArizonaOffices(s): Western Area Power Administration-Desert Southwest Region

  10. EIS-0457: Albany-Eugene Rebuild Project, Lane and Linn Counties, OR

    Broader source: Energy.gov [DOE]

    This EIS evaluates the environmental impacts of a proposal by BPA to rebuild a 32-mile section of the Albany-Eugene 115-kilovolt No. 1 Transmission Line in Lane and Linn Counties, OR.

  11. EIS-0325: Schultz-Hanford Area Transmission Line Project, WA

    Broader source: Energy.gov [DOE]

    BPA proposes to construct a new 500-kilovolt (kV) transmission line in central Washington. This project would increase transmission system capacity north of Hanford.

  12. Electric Transmission Lines (Iowa)

    Broader source: Energy.gov [DOE]

    Electric transmission lines capable of operating at 69 kV or greater cannot be constructed along, across, or over any public highways or grounds outside of cities without a franchise from the...

  13. Malcolm, N. and Aggarwal, R.k. (2014) An Analysis of Reducing Back Flashover Faults with Surge Arresters on 69/138 kV Double

    E-Print Network [OSTI]

    McCusker, Guy

    Arresters on 69/138 kV Double Circuit Transmission Lines Due to Direct Lightning Strikes on the Shield Wires-EMTP, Back flashover faults, Lightning strokes, Surge arrester, Transmission lines. Abstract Back flashover causes of power interruptions on the double-circuit 69/138 kV overhead transmission lines in Jamaica

  14. Grand Coulee Transmission Line Replacement Project

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    by the Bureau of Reclamation to design and construct six new 500-kV overhead transmission lines at Grand Coulee Dam. BPA will replace the existing underground transmission...

  15. Florida Electric Transmission Line Siting Act (Florida)

    Broader source: Energy.gov [DOE]

    The Transmission Line Siting Act (TLSA) is the state’s centralized process for licensing electrical transmission lines which; (a) are 230 kV or larger; (b) cross a county line; and, (c) are 15...

  16. EIS-0231: Navajo Transmission Project

    Broader source: Energy.gov [DOE]

    This EIS evaluates the environmental impacts of a proposal to by Dine Power Authority, a Navajo Nation enterprise, to construct, operate, and maintain a 500 kilovolt (kV) transmission line planned...

  17. EIS-0486: Plains & Eastern Clean Line Transmission Project |...

    Broader source: Energy.gov (indexed) [DOE]

    project would include an overhead 600 kilovolt (kV) high voltage direct current (HVDC) electric transmission system and associated facilities with the capacity to deliver...

  18. EIS-0325: Schultz-Hanford Area Transmission Line Project Final Environmental Impact Statement, EIS-0325 (January 2003)

    Broader source: Energy.gov [DOE]

    BPA proposes to construct a new 500-kilovolt (kV) transmission line in central Washington. This project would increase transmission system capacity north of Hanford.

  19. EIS-0421: Big Eddy-Knight Transmission Line

    Broader source: Energy.gov [DOE]

    BPA is proposing to build a new 500 kilovolt (kV) transmission line in Wasco County, Oregon and Klickitat County, Washington and a new substation in Klickitat County. The new BPA transmission line...

  20. Biennial Assessment of the Fifth Power Plan Transmission Issues

    E-Print Network [OSTI]

    unscheduled electricity flows over transmission lines leading to increased risks to electric system by the partners in the Colstrip 500 kV transmission lines (Northwestern Energy, Puget Sound Energy, Portland

  1. Corona performance of a compact 230-kV line

    SciTech Connect (OSTI)

    Chartier, V.L.; Blair, D.E. [Bonneville Power Administration, Vancouver, WA (United States). Division of Laboratories; Easley, M.D.; Raczkowski, R.T. [Puget Sound Power and Light Co., Bellevue, WA (United States)

    1994-12-31T23:59:59.000Z

    Permitting requirements and the acquisition of new rights-of-way for transmission facilities has in recent years become increasingly difficult for most utilities, including Puget Sound Power and Light Company. In order to maintain a high degree of reliability of service while being responsive to public concerns regarding the siting of high voltage (HV) transmission facilities, Puget Power has found it necessary to more heavily rely upon the use of compact lines in franchise corridors. Compaction does, however, precipitant increased levels of audible noise (AN) and radio and TV interference (RI and TVI) due to corona on the conductors and insulator assemblies. Puget Power relies upon the Bonneville Power Administration (BPA) Corona and Field Effects computer program to calculate AN and RI for new lines. Since there was some question of the program`s ability to accurately represent quiet 230-kV compact designs, a joint project was undertaken with BPA to verify the program`s algorithms. Long-term measurements made on an operating Puget Power 230-kV compact line confirmed the accuracy of BPA`s AN model; however, the RI measurements were much lower than predicted by the BPA computer and other programs. This paper also describes how the BPA computer program can be used to calculate the voltage needed to expose insulator assemblies to the correct electric field in single test setups in HV laboratories.

  2. Corona performance of a compact 230-kV line

    SciTech Connect (OSTI)

    Chartier, V.L.; Blair, D.E. [Bonneville Power Administration, Vancouver, WA (United States). Division of Labs.] [Bonneville Power Administration, Vancouver, WA (United States). Division of Labs.; Easley, M.D.; Raczkowski, R.T. [Puget Sound Power and Light Co., Bellevue, WA (United States)] [Puget Sound Power and Light Co., Bellevue, WA (United States)

    1995-01-01T23:59:59.000Z

    Permitting requirements and the acquisition of new rights-of-way for transmission facilities has in recent years become increasingly difficult for most utilities, including Puget Sound Power and Light Company. In order to maintain a high degree of reliability of service while being responsive to public concerns regarding the siting of high voltage (HV) transmission facilities, Puget Power has found it necessary to more heavily rely upon the use of compact lines in franchise corridors. Compaction does, however, precipitate increased levels of audible noise (AN) and radio and TV interference (RI and TVI) due to corona on the conductors and insulator assemblies. Puget Power relies upon the Bonneville Power Administration (BPA) Corona and Field Effects computer program to calculate AN and RI for new lines. Since there was some question of the program`s ability to accurately represent quiet 230-kV compact designs, a joint project was undertaken with BPA to verify the program`s algorithms. Long-term measurements made on an operating Puget Power 230-kV compact line confirmed the accuracy of BPA`s AN model; however, the RI measurements were much lower than predicted by the BPA and other programs. This paper also describes how the BPA computer program can be used to calculate the voltage needed to expose insulator assemblies to the correct electric field in single test setups in HV laboratories.

  3. North Steens 230kV Transmission | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand Jump to: navigation, searchOfRoseConcerns Jumpsource History View New PagesRiver Shores,North

  4. EIS-0005-FS: Bonneville Power Administration Proposed FY 1979 Program, Facility Location on Supplement, Southwest Oregon Area Service, Buckley-Summer Lake 500 kV Line, Supplemental

    Broader source: Energy.gov [DOE]

    This Bonneville Power Administration document assesses the environmental impacts of constructing transmission facilities, which will coordinate with the Midpoint-Malin 500-kV line to be constructed by the Pacific Power and Light (PP&L) Company. The proposed action includes the construction of the 1.56-mile Buckley-Summer Lake 500-kV transmission line; the proposed Buckley Substation near Maupin, Oregon; and the proposed Summer Lake Substation near Silver Lake, Oregon.

  5. A multiconductor model for determining the response of power transmission and distribution lines to a high altitude electromagnetic pulse (HEMP)

    SciTech Connect (OSTI)

    Tesche, F.M.; Barnes, P.R.

    1988-01-01T23:59:59.000Z

    A calculation model for electromagnetic pulse coupling to transmission and transmission line is discussed. Sample calculations for a 345 kV transmission line are given. 3 refs., 8 figs.

  6. KV-tOOJHfe Metallurgy Department

    E-Print Network [OSTI]

    »KV-tOOJHfe RisB-R-547 Metallurgy Department Progress Report for the Period 1 January to 31 December 1986 Risř National Laboratory, DK-4000 Roskilde, Denmark April 1987 #12;Risř-R-547 METALLURGY.B. BiIde-Sřrensen Abstract. The activities of the Metallurgy Department at Risř during 1986

  7. The varistor protected series capacitors at the 500 KV broadview substation

    SciTech Connect (OSTI)

    Barcus, J.M. (General Electric Co., Hudson Falls, NY (US)); Miske, S.A. Jr. (General Electric Co., Schenectady, NY (US)); Vitols, A.P. (General Electric Co., Pittsfield, MA (US)); Maynard, H.M. (Montana Power Co., Butte, MT (US)); Peterson, W.G. (Bonneville Power Admin., Portland, OR (US))

    1988-10-01T23:59:59.000Z

    Two 235 Mvar series capacitors have been successfully applied at the 500 kV Broadview substation of the Colstrip Transmission Project. The series capacitors have an overvoltage protection system based on metal oxide varistors. The system provides instantaneous bypass and reinsertion of the capacitors following external line section faults. The excellent performance of the equipment was demonstrated during staged fault tests performed in October, 1985. The banks have been in successful operation since January, 1986.

  8. Commonwealth Edison 345kV L.P.P. splicing school

    SciTech Connect (OSTI)

    Johnsen, D.P. [ComEd, Chicago, IL (United States)

    1996-11-01T23:59:59.000Z

    The ComEd splicing school was held in January 1995 to train the work force for the installation of the first 345kV High Pressure Fluid Filled pipe type L.P.P. (Laminated Paper Polypropylene) insulated cable on the ComEd system. Construction is nearing completion on ComEd`s 345kV underground transmission line 17723 between Burnham TSS 177 and Taylor TSS 153 located just south of the Chicago Loop. Continued development and construction of the down-town Chicago Area and the south Loop has established the need for this line to reinforce the transmission network serving this critical area. 345kV transmission Line 17723 is a combination of overhead facility and HPFF (High Pressure Fluid Filled) pipe type L.P.P. cable with a summer normal rating of 900 MVA and a summer emergency rating of 1,200 MVA. This paper describes the training facility, innovative changes in tooling and the results of the training exercises.

  9. EA-1891: Alvey-Fairview Transmission Line Rebuild Project, Oregon

    Broader source: Energy.gov [DOE]

    This EA evaluates the environmental impacts of a proposal to rebuild DOE’s Bonneville Power Administration’s Alvey-Fairview No. 1 230-kV transmission line located between Eugene, Oregon, and Coquille, Oregon.

  10. Lovell-Yellowtail transmission line rebuild project, Western...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    on Flickr. Western is rebuilding the Lovell-to-Yellowtail No. 1 and No. 2 115-kV transmission lines. The 94-circuit-miles of lines are located between Lovell, Wyo., and Yellowtail...

  11. CX-011718: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Electrical District 2 to Saguaro #2 115 Kilovolt Transmission Line, Marker Ball Installation at Structure 26-10. CX(s) Applied: B1.3 Date: 01/09/2014 Location(s): Arizona Offices(s): Western Area Power Administration-Desert Southwest Region

  12. CX-005009: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Modify Two Structures Along the Vera Tap to Trentwood-Valley Way #1, 115 Kilovolt Transmission LineCX(s) Applied: B1.3, B4.6Date: 01/10/2011Location(s): Spokane County, WashingtonOffice(s): Bonneville Power Administration

  13. CX-012747: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Alcova-Miracle Mile East 115 Kilovolt Transmission Line Fiber Optic Ground Wire and Structure Replacement Project Natrona and Carbon Counties, Wyoming CX(s) Applied: B1.3, B4.7Date: 41855 Location(s): WyomingOffices(s): Western Area Power Administration-Rocky Mountain Region

  14. CX-010885: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Kiowa Creek-Weld 115-Kilovolt Transmission Line Culvert Replacement CX(s) Applied: B1.3, B1.33 Date: 08/06/2013 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  15. CX-011858: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Beaver Creek-Sterling 115 Kilovolt Transmission Line Structure Relocation, Morgan County, Colorado CX(s) Applied: B4.13 Date: 01/21/2014 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  16. CX-009227: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Beaver Creek- Big Sandy 115 Kilovolt Transmission Line Structure Replacements - Last Chance Fire CX(s) Applied: B4.13 Date: 08/31/2012 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  17. CX-012083: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Rosedale-Willowby-Kiowa Creek 115-Kilovolt Transmission Line Wood H-Structure Replacement CX(s) Applied: B1.3 Date: 04/10/2014 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  18. CX-012758: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Danger Tree Management on Curecanti to South Canal and South Canal to Montrose 115 Kilovolt Transmission Lines, Gunnison County, Colorado CX(s) Applied: B1.3Date: 41855 Location(s): ColoradoOffices(s): Western Area Power Administration-Rocky Mountain Region

  19. CX-010108: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Danger Tree Management on Curecanti-Crystal, 115 Kilovolt Transmission Line Danger Tree and Vegetation Management CX(s) Applied: B1.3 Date: 04/25/2013 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  20. CX-006816: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Line and Load Interconnection of Coos-Curry Electric Cooperative?s New Substation to Bonneville Power Administration?s Fairview-Bandon 115-Kilovolt Transmission LineCX(s) Applied: B4.6, B4.10Date: 09/26/2011Location(s): Coos County, OregonOffice(s): Bonneville Power Administration

  1. CX-005936: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Erie to Terry Street and Lyons to Longmont Northwest 115 Kilovolt Transmission Line Structure Replacements, Boulder and Broomfield Counties, ColoradoCX(s) Applied: B4.6Date: 05/16/2011Location(s): Boulder County, ColoradoOffice(s): Western Area Power Administration-Rocky Mountain Region

  2. CX-008166: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Amended: Acquisition of a Portion of Cowlitz County Public Utility District’s 115-Kilovolt Transmission Line Washington Way Substation CX(s) Applied: B1.24 Date: 03/22/2012 Location(s): Washington Offices(s): Bonneville Power Administration

  3. CX-011857: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Archer-Cheyenne North/South 115 Kilovolt Transmission Line Structure Replacement, Laramie County, Wyoming CX(s) Applied: B4.13 Date: 01/28/2014 Location(s): Wyoming Offices(s): Western Area Power Administration-Rocky Mountain Region

  4. CX-009088: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Curecanti-Crystal 115 Kilovolt Transmission Line Routine Maintenance of Existing Access Roads and Right-of-Ways CX(s) Applied: B1.3 Date: 08/07/2012 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  5. CX-008782: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Danger Tree Management on North Gunnison to Skito 115 Kilovolt Transmission Line Gunnison County, Colorado CX(s) Applied: B1.3 Date: 07/02/2012 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  6. CX-008781: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Danger Tree Management on Curecanti to Blue Mesa 115 Kilovolt Transmission Line Gunnison County, Colorado CX(s) Applied: B1.3 Date: 07/02/2012 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  7. CX-012356: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Lovell-Yellowtail No. 1 115-kilovolt Transmission Line Culvert Replacement Project, Big Horn County, Wyoming CX(s) Applied: B1.3 Date: 07/01/2014 Location(s): Wyoming Offices(s): Western Area Power Administration-Rocky Mountain Region

  8. Design and Overview of 100 kV Bushing for the DNB Injector of ITER

    SciTech Connect (OSTI)

    Shah, Sejal; Bandyopadhyay, M.; Rotti, C.; Singh, M. J.; Roopesh, G.; Chakraborty, A. K. [ITER-India, Institute for Plasma Research, Gandhinagar-382025, Gujarat (India); Rajesh, S. [ITER-India, Institute for Plasma Research, Gandhinagar-382025, Gujarat (India); Microelectronics and Materials Physics Labs, P.O.Box 4500, FIN-90014 University of Oulu (Finland); Nishad, S.; Srusti, B. [DesignTech Systems Ltd, Banjara Hills, Hyderabad, Andhra Pradesh-500034 (India); Schunke, B.; Hemsworth, R.; Chareyre, J.; Svensson, L. [ITER Organisation, Route de Vinon, CS 90 046, 13067 St. Paul lez Durance Cedex (France)

    2011-09-26T23:59:59.000Z

    The 100 kV bushing is one of the most important and technologically challenging Safety Important Class (SIC) components of the Diagnostic Neutral Beam (DNB) injector of ITER. It forms interface between gas insulated electrical transmission line and torus primary vacuum and acts as a vacuum feedthrough of ITER. Design optimization has been carried out to meet the electric and structural requirements based on its classification. Unlike HNB bushing, single stage bushing is designed to provide 100 kV isolation. Finite Element Analysis (FEA) based optimization has been carried out for electrostatic and structural analysis. Manufacturing assembly sequence is studied and presented in this paper. However validation of the same is foreseen from manufacturer.

  9. Type A Accident Investigation Report on the June 25, 1997, Contractor Inspector Fatality on the Satsop-Aberdeen #2 & #3 230 kV Line

    Broader source: Energy.gov [DOE]

    On June 27, 1997, I established a Type-A Accident Investigation Board to investigate the June 25, 1997 fatal contractor accident which occurred on BPA?s Satsop-Aberdeen #2 and #3 230-kV transmission lines right-of-way.

  10. Increasing the reliability of the shutdown of 500 - 750-kV overhead lines equipped with shunt reactors in an unsuccessful three-phase automatic repeated closure cycle

    SciTech Connect (OSTI)

    Kuz'micheva, K. I.; Merzlyakov, A. S.; Fokin, G. G. [JSC 'R and D Center at Federal Grid Company of the United Power System' (Russian Federation)

    2013-05-15T23:59:59.000Z

    The reasons for circuit-breaker failures during repeated disconnection of 500 - 750 kV overhead lines with shunt reactors in a cycle of unsuccessful three-phase automatic reconnection (TARC) are analyzed. Recommendations are made for increasing the operating reliability of power transmission lines with shunt reactors when there is unsuccessful reconnection.

  11. Type A Accident Investigation Board Report of the April 25, 1997, Contractor Fatality on the Olympia-White River #1 230 kV Line

    Broader source: Energy.gov [DOE]

    On April 25, 1997, at approximately 1510 hours, a lineman for Great Southwestern Construction Inc. was fatally electrocuted when he came in direct contact with a deenergized 230-kilovolt (kV) transmission power line conductor which contained an induced voltage.

  12. EIS-0124: Conrad-Shelby Transmission Line Project, Montana

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy's Western Area Power Administration developed this statement to assess the environmental impact of adding a 230 kV transmission line between Conrad and Shelby, Montana and a new substation near Shelby to update the stressed electrical transmission system.

  13. Waltz Mill testing of 345-kV PPP cable

    SciTech Connect (OSTI)

    Burghardt, R.R. (Westinghouse Electric Corp., Ruffs Dale, PA (United States))

    1991-09-01T23:59:59.000Z

    A 345-kV PPP-insulated cable was subjected to a two-year accelerated life test program at the EPRI Waltz Mill Cable Test Facility. Testing started in November 1985 and was successfully completed in September 1988. The program included conductor temperatures ranging from 85{degrees}C to 105{degrees}C and line-to-line voltages from 362 kV to 474 kV. Cyclic testing was performed during 17 of the 24 months. Dissipation factor measurements were made throughout the program. The measurements indicated no deterioration of the cable or splices as a consequence of the high temperatures and voltages applied to them in this test program. 2 refs., 24 figs.

  14. Blythe-Knob\t161-kV\tTransmission\tLine Cross\tArm\tReplacements\t...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    9 Blythe-Knob 161-kV Transmission Line Cross Arm Replacements - Continuation Sheet Project Description (continued) The wood cross arms on a number of wood H-frame structures have...

  15. EA-1960: Townsite Solar Project Transmission Line, Clark County, Nevada

    Broader source: Energy.gov [DOE]

    The Bureau of Land Management, with Western Area Power Administration as a cooperating agency, prepared an EA to evaluate potential impacts of a proposal to build and operate a 180-MW photovoltaic facility; a 220, 230, or 500 kV transmission line; and associated facilities in Clark County, Nevada.

  16. EIS-0090: Fort Peck-Havre Transmission Line Project, Montana

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy’s Western Area Power Administration prepared this statement to assess the potential environmental and socioeconomic implications of its proposed action to construct and operate a 230kV transmission line from Fort Peck to Havre, Montana, with three intermediate interconnecting substations.

  17. A 50 kV solid state multipulse kicker modulator

    SciTech Connect (OSTI)

    Walstrom, P. L. (Peter L.); Cook, E. G. (Edward G.)

    2003-01-01T23:59:59.000Z

    Performance requirements, design concepts, and test results for a prototype multipulse kicker modulator based on solid-state switches and a voltage-adding transformer topology are described. Tape-wound cores are stacked to form the transformer primary windings and a cylindrical pipe that passes through the circular inner diameters of the cores serves as the secondary winding of the step-up transformer. Boards containing MOSFET switches, trigger circuitry, and energy-storage capacitors plug into the core housings. A 50 kV prototype modulator that meets most of the facility requirements has been designed, fabricated, and tested at LLNL. More recent work has been concerned with designing and testing cores and boards with the full volt-second capability needed for 24-pulse operation. Results of the 50 kV prototype tests, preliminary tests of the full-volt-second cores and boards, and future development needs are described.

  18. CEBAF 200 kV Inverted Electron Gun

    SciTech Connect (OSTI)

    J.M. Grames, P.A. Adderley, J. Clark, J. Hansknecht, M. Poelker, M.L. Stutzman, R. Suleiman, K.E.L. Surles-Law

    2011-03-01T23:59:59.000Z

    Two DC high voltage GaAs photoguns have been built at Jefferson Lab based on a compact inverted insulator design. One photogun provides the polarized electron beam at CEBAF and operates at 130 kV bias voltage. The other gun is used for high average current lifetime studies at a dedicated test facility and has been operated at bias voltage up to 225 kV. The advantages of higher DC voltage for CEBAF include reduced space-charge emittance growth and the potential for prolonged photocathode lifetime. However, a consequence of operating at higher voltages is the increased likelihood of field emission or breakdown, both of which are unacceptable. Highlights of the R&D studies leading toward a production 200keV GaAs photogun for CEBAF will be presented.

  19. The design and construction of a 130 K.V. radio frequency Cockcroft Walton type generator

    E-Print Network [OSTI]

    Robba, William Augustus

    1951-01-01T23:59:59.000Z

    at 30 KV are rather expensive~ and a 500 KV generator of this type would cost several thousand dollars. Sesides thisc the rcgulaticu and efficienoy of suoh a generator leave such to be desired An exanple will nake this c3Alaro Lot v o 1$ f, Vi g x... ourrent~ voltage snd poser for various staok voltages, Steak Voltages (One Stags) 20 K+V+ 15KV 12 K+V+ 10 K Vo 7. $ K. V. 220 Rile 180 Rile 140 ILQs 120 RGs 100 Mile 1500 Stack Plate Current Plato Voltage Poser in Watts QS $0 Varies Set...

  20. EIS-0507: Boardman-Hemingway Transmission Line, Oregon and Idaho

    Broader source: Energy.gov [DOE]

    The Bureau of Land Management and the U.S. Forest Service are preparing, with DOE’s Bonneville Power Administration (BPA) as a cooperating agency, an EIS that evaluates the potential environmental impacts of a proposal to construct about 305 miles of 500-kV transmission line from northeast Oregon to southwest Idaho. BPA’s proposed action is to partially fund part the transmission line.

  1. Electrical and mechanical design criteria for EHV and UHV: overhead transmission lines

    SciTech Connect (OSTI)

    Not Available

    1980-06-01T23:59:59.000Z

    The results are presented of a program devoted to the selection of electrical and mechanical design criteria and parameters for overhead power transmission lines for ac systems rated at from 345 to 1100 kV and for dc systems rated at from 600 to 1200 kV. Information is included on the environmental effects, i.e., audible noise and electric fields, of the lines, mechanical and economic requirements, safety, failures, grounding, and lightning protection. (LCL)

  2. The 345 kV underground/underwater Long Island Sound cable project

    SciTech Connect (OSTI)

    Grzan, J.; Hahn, E.I. (New York Power Authority, White Plains, NY (United States)); Casalaina, R.V.; Kansog, J.O.C. (Ebasco Services Inc., Lyndhurst, NJ (United States))

    1993-07-01T23:59:59.000Z

    A high voltage underground/underwater cable system was installed to increase the transmission capacity from the mainland of New York to Long Island. In terms of weight and diameter, the self-contained, fluid-filled (SCFF) cable used for the underwater portion of the project is the largest underwater cable in the world. The use of high-pressure, fluid-filled (HPFF) pipe-type cable on the land portion represents the largest application of paper-polypropylene-paper (PPP) insulated cable in the United States. State-of-the-art technologies were implemented in the use of fiber optic cables for relay protection and SCADA/RTU, temperature monitoring and leak detection systems, SF[sub 6] gas-insulated substations, and underwater cable laying and embedment techniques. This paper discusses the design and installation of a 750 MVA, 43 km (26.6 mi), 345 kV underground/underwater electric transmission system installed by the New York Power Authority (NYPA).

  3. Microsoft Word - Deering Lake-Eckley 115-kV Transmission Line...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    window washing, lawn mowing, trash collection, painting, and snow removal). Routine maintenance activities, corrective (that is, repair), preventive, and predictive, are...

  4. EIS-0159: Flatiron-Erie 115-kV Transmission Line

    Broader source: Energy.gov [DOE]

    "The Western Area Power Administration proposes to build 27 new wood H-frame structures along the line, to replace or modify 45 of the existing structures and to remove 11 of them."

  5. Bouse Hills Pumping Plant to Harcuvar 115-kV Transmission Line

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    areas, and other water sources that are vital in a region); and X (vii) Tundra, coral reefs, or rain forests.; or X (5) Involve genetically engineered organisms, synthetic...

  6. Mead-Liberty 345-kV Transmission Line Access Road Maintenance...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    areas, and other water sources that are vital in a region); and X (vii) Tundra, coral reefs, or rain forests.; or X (5) Involve genetically engineered organisms, synthetic...

  7. EIS-0505: Vantage to Pomona Heights 230 kV Transmission Line Project;

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels DataDepartment of Energy Your Density Isn't Your Destiny:Revised FindingDepartmentDepartmentStatement | Department ofDepartmentDepartment

  8. Cameron to Milford-138kV Transmission Line | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand Jump to:EzfeedflagBiomassSustainableCSL GasPermits Manual Jump to:(RECP) inCounty, Texas:Cameron to

  9. Ashland Area Support Substation Project : Environmental Assessment.

    SciTech Connect (OSTI)

    United States. Bonneville Power Administration.

    1992-06-01T23:59:59.000Z

    The Bonneville Power Administration (BPA) provides wholesale electric service to the City of Ashland (the City) by transferring power over Pacific Power & Light Company`s (PP&L) 115-kilovolt (kV) transmission lines and through PP&L`s Ashland and Oak Knoll Substations. The City distributes power over a 12.5-kV system which is heavily loaded during winter peak periods and which has reached the limit of its ability to serve peak loads in a reliable manner. Peak loads under normal winter conditions have exceeded the ratings of the transformers at both the Ashland and Oak Knoll Substations. In 1989, the City modified its distribution system at the request of PP&L to allow transfer of three megawatts (MW`s) of electric power from the overloaded Ashland Substation to the Oak Knoll Substation. In cooperation with PP&L, BPA installed a temporary 6-8 megavolt-amp (MVA) 115-12.5-kV transformer for this purpose. This additional transformer, however, is only a temporary remedy. BPA needs to provide additional, reliable long-term service to the Ashland area through additional transformation in order to keep similar power failures from occurring during upcoming winters in the Ashland area. The temporary installation of another 20-MVA mobile transformer at the Ashland Substation and additional load curtailment are currently being studied to provide for sustained electrical service by the peak winter period 1992. Two overall electrical plans-of-service are described and evaluated in this report. One of them is proposed for action. Within that proposed plan-of-service are location options for the substation. Note that descriptions of actions that may be taken by the City of Ashland are based on information provided by them.

  10. Ashland Area Support Substation Project

    SciTech Connect (OSTI)

    Not Available

    1992-06-01T23:59:59.000Z

    The Bonneville Power Administration (BPA) provides wholesale electric service to the City of Ashland (the City) by transferring power over Pacific Power Light Company's (PP L) 115-kilovolt (kV) transmission lines and through PP L's Ashland and Oak Knoll Substations. The City distributes power over a 12.5-kV system which is heavily loaded during winter peak periods and which has reached the limit of its ability to serve peak loads in a reliable manner. Peak loads under normal winter conditions have exceeded the ratings of the transformers at both the Ashland and Oak Knoll Substations. In 1989, the City modified its distribution system at the request of PP L to allow transfer of three megawatts (MW's) of electric power from the overloaded Ashland Substation to the Oak Knoll Substation. In cooperation with PP L, BPA installed a temporary 6-8 megavolt-amp (MVA) 115-12.5-kV transformer for this purpose. This additional transformer, however, is only a temporary remedy. BPA needs to provide additional, reliable long-term service to the Ashland area through additional transformation in order to keep similar power failures from occurring during upcoming winters in the Ashland area. The temporary installation of another 20-MVA mobile transformer at the Ashland Substation and additional load curtailment are currently being studied to provide for sustained electrical service by the peak winter period 1992. Two overall electrical plans-of-service are described and evaluated in this report. One of them is proposed for action. Within that proposed plan-of-service are location options for the substation. Note that descriptions of actions that may be taken by the City of Ashland are based on information provided by them.

  11. EA-1617: Lovell-Yellowtail and Basin-Lovell Transmission Line Rebuild Project, Big Horn County, Wyoming, and Big Horn and Carbon Counties, Montana

    Broader source: Energy.gov [DOE]

    DOE’s Western Area Power Administration prepared this EA and a finding of no significant impact for a proposal to rebuild the Lovell-Yellowtail (LV-YT) No. 1 and No. 2 115-kV transmission lines, located in Big Horn County, Wyoming, and Big Horn and Carbon Counties in Montana, and the Basin-Lovell 115-kV transmission line in Big Horn County, Wyoming.

  12. Solid-State Fault Current Limiter Development : Design and Testing Update of a 15kV SSCL Power Stack

    SciTech Connect (OSTI)

    Dr. Ram Adapa; Mr. Dante Piccone

    2012-04-30T23:59:59.000Z

    ABSTRACT The Solid-State Fault Current Limiter (SSCL) is a promising technology that can be applied to utility power delivery systems to address the problem of increasing fault currents associated with load growth. As demand continues to grow, more power is added to utility system either by increasing generator capacity or by adding distributed generators, resulting in higher available fault currents, often beyond the capabilities of the present infrastructure. The SSCL is power-electronics based equipment designed to work with the present utility system to address this problem. The SSCL monitors the line current and dynamically inserts additional impedance into the line in the event of a fault being detected. The SSCL is based on a modular design and can be configured for 5kV through 69kV systems at nominal current ratings of 1000A to 4000A. Results and Findings This report provides the final test results on the development of 15kV class SSCL single phase power stack. The scope of work included the design of the modular standard building block sub-assemblies, the design and manufacture of the power stack and the testing of the power stack for the key functional tests of continuous current capability and fault current limiting action. Challenges and Objectives Solid-State Current Limiter technology impacts a wide spectrum of utility engineering and operating personnel. It addresses the problems associated with load growth both at Transmission and Distribution class networks. The design concept is pioneering in terms of developing the most efficient and compact power electronics equipment for utility use. The initial test results of the standard building blocks are promising. The independent laboratory tests of the power stack are promising. However the complete 3 phase system needs rigorous testing for performance and reliability. Applications, Values, and Use The SSCL is an intelligent power-electronics device which is modular in design and can provide current limiting or current interrupting capabilities. It can be applied to variety of applications from distribution class to transmission class power delivery grids and networks. It can also be applied to single major commercial and industrial loads and distributed generator supplies. The active switching of devices can be further utilized for protection of substation transformers. The stress on the system can be reduced substantially improving the life of the power system. It minimizes the voltage sag by speedy elimination of heavy fault currents and promises to be an important element of the utility power system. DOE Perspective This development effort is now focused on a 15kV system. This project will help mitigate the challenges of increasing available fault current. DOE has made a major contribution in providing a cost effective SSCL designed to integrate seamlessly into the Transmission and Distribution networks of today and the future. Approach SSCL development program for a 69kV SSCL was initiated which included the use of the Super GTO advanced semiconductor device which won the 2007 R&D100 Award. In the beginning, steps were identified to accomplish the economically viable design of a 69kV class Solid State Current Limiter that is extremely reliable, cost effective, and compact enough to be applied in urban transmission. The prime thrust in design and development was to encompass the 1000A and the 3000A ratings and provide a modular design to cover the wide range of applications. The focus of the project was then shifted to a 15kV class SSCL. The specifications for the 15kV power stack are reviewed. The design changes integrated into the 15kV power stack are discussed. In this Technical Update the complete project is summarized followed by a detailed test report. The power stack independent high voltage laboratory test requirements and results are presented. Keywords Solid State Current Limiter, SSCL, Fault Current Limiter, Fault Current Controller, Power electronics controller, Intelligent power-electronics Device, IED

  13. Kangley-Echo Lake Transmission Line Project Final Environmental Impact Statement

    SciTech Connect (OSTI)

    N /A

    2003-06-20T23:59:59.000Z

    BPA proposes to build a single-circuit 500-kV transmission line from a tap point on an existing 500-kV line near Kangley, Washington, to its Echo Lake Substation near North Bend, Washington. The proposed route for this line, also called Alternative 1, is about nine miles long. About five miles of the proposed route would go through the Cedar River Municipal Watershed. In addition, Echo Lake Substation would be expanded about three acres to the east and new equipment would be installed there to accommodate the new line (common to all transmission alternatives). This alternative was proposed because it would be located immediately parallel to an existing BPA existing 500-kV transmission line, the Raver-Echo Lake Transmission Line. Locating a new line next to an existing one reduces right-of-way (ROW) clearing needed for the new line and reduces the need for additional access roads. Lattice steel transmission towers would support the 500-kV transmission line. These structures average 135 feet high, with the average span between towers of about 1,150 feet.

  14. Transmission Services

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Return to Daylight Saving Time Posted: 2232015 Effective Date: 382015 This document provides the procedure for reserving and scheduling transmission that spans the time change...

  15. The Cost of Transmission for Wind Energy in the United States: A Review of Transmission Planning Studies.

    E-Print Network [OSTI]

    Wiser, Ryan

    2014-01-01T23:59:59.000Z

    kV JCSP 765 kV and 800 kV HVDC Southern California Edison (2 345 kV ERCOT - TOS - 3 345 kV and HVDC ERCOT - TOS - 4345 kV and HVDC Southwest Power Pool (SPP) SPP - 2 345 kV

  16. CEBAF 200 kV Inverted Electron Gun

    SciTech Connect (OSTI)

    Grames, J M; Clark, J; Hansknecht, J; Poelker, M; Stutzman, M L; Suleiman, R; Surles-Law, K.E.L.; BastaniNejad, M

    2011-03-01T23:59:59.000Z

    Two DC high volt­age GaAs pho­to­guns have been built at Jef­fer­son Lab based on a com­pact in­vert­ed in­su­la­tor de­sign. One pho­to­gun pro­vides the po­lar­ized elec­tron beam at CEBAF and op­er­ates at 130 kV bias volt­age. The other gun is used for high av­er­age cur­rent life­time stud­ies at a ded­i­cat­ed test fa­cil­i­ty and has been op­er­at­ed at bias volt­age up to 225 kV. The ad­van­tages of high­er DC volt­age for CEBAF in­clude re­duced space-charge emit­tance growth and the po­ten­tial for pro­longed pho­to­cath­ode life­time. How­ev­er, a con­se­quence of op­er­at­ing at high­er volt­ages is the in­creased like­li­hood of field emis­sion or break­down, both of which are un­ac­cept­able. High­lights of the R&D stud­ies lead­ing to­ward a pro­duc­tion 200keV GaAs pho­to­gun for CEBAF will be pre­sent­ed.

  17. Proposal for the award of a blanket purchase contract for the supply, installation, commissioning and maintenance of electrical switchgear operating at 18kV and 3.3 kV

    E-Print Network [OSTI]

    2015-01-01T23:59:59.000Z

    Proposal for the award of a blanket purchase contract for the supply, installation, commissioning and maintenance of electrical switchgear operating at 18kV and 3.3 kV

  18. Joint HVAC transmission EMF environmental study

    SciTech Connect (OSTI)

    Stormshak, F.; Thompson, J. (Oregon State Univ., Corvallis, OR (United States))

    1992-05-01T23:59:59.000Z

    This document describes the rationale, procedures, and results of a carefully controlled study conducted to establish whether chronic exposure of female (ewe) Suffolk lambs to the environment of a 500-kV 60-Hz transmission line would affect various characteristics of growth, endocrine function, and reproductive development. This experiment used identical housing and management schemes for control and line-exposed ewes, thus minimizing these factors as contributors to between-group experimental error. Further, throughout the 10-month duration of this study, changes in electric and magnetic fields, audible noise, and weather conditions were monitored continuously by a computerized system. Such measurements provided the opportunity to identify any relationship between environmental factors and biological responses. Because of reports in the literature that electric and magnetic fields alter concentrations of melatonin in laboratory animals, the primary objective of this study was to ascertain whether a similar effect occurs in lambs exposed to a 500-kV a-c line in a natural setting. In addition, onset of puberty, changes in body weight, wool growth, and behavior were monitored. To determine whether the environment of a 500-kV line caused stress in the study animals, serum levels of cortisol were measured. The study was conducted at Bonneville Power Administration's Ostrander Substation near Estacada, Oregon.

  19. Transmission Services J7000

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Transmission Business Unit - J7300 CRSP - DSW - RMR Open Access Transmission Tariff Management Transmission Service Requests Interconnection Requests OASIS...

  20. Increasing transmission loadability by the application of shunt capacitors

    SciTech Connect (OSTI)

    Palmer, R.

    1981-05-01T23:59:59.000Z

    The companies located in the eastern portion of the Pennsylvania-New Jersey-Maryland Interconnection (PJM) have installed oil-fired generation to meet strict environmental requirements. In an attempt to reduce the use of oil, PJM has been purchasing energy from systems to the west of PJM where the primary fuel is coal. These west-to-east energy transfers have increased the loading on the 500kV transmission system. The heavy loadings have resulted in voltage limitations on the 500kV system that limit flows to well below the thermal capability. Results of an analysis of this problem and recommendations for removing the voltage limitations are presented. It is primarily recommended to use shunt capacitors to supply the transmission system reactive losses.

  1. Tungsten anode spectral model using interpolating cubic splines: Unfiltered x-ray spectra from 20 kV to 640 kV

    SciTech Connect (OSTI)

    Hernandez, Andrew M. [Biomedical Engineering Graduate Group, University of California Davis, Sacramento, California 95817 (United States)] [Biomedical Engineering Graduate Group, University of California Davis, Sacramento, California 95817 (United States); Boone, John M., E-mail: john.boone@ucdmc.ucdavis.edu [Departments of Radiology and Biomedical Engineering, Biomedical Engineering Graduate Group, University of California Davis, Sacramento, California 95817 (United States)

    2014-04-15T23:59:59.000Z

    Purpose: Monte Carlo methods were used to generate lightly filtered high resolution x-ray spectra spanning from 20 kV to 640 kV. Methods: X-ray spectra were simulated for a conventional tungsten anode. The Monte Carlo N-Particle eXtended radiation transport code (MCNPX 2.6.0) was used to produce 35 spectra over the tube potential range from 20 kV to 640 kV, and cubic spline interpolation procedures were used to create piecewise polynomials characterizing the photon fluence per energy bin as a function of x-ray tube potential. Using these basis spectra and the cubic spline interpolation, 621 spectra were generated at 1 kV intervals from 20 to 640 kV. The tungsten anode spectral model using interpolating cubic splines (TASMICS) produces minimally filtered (0.8 mm Be) x-ray spectra with 1 keV energy resolution. The TASMICS spectra were compared mathematically with other, previously reported spectra. Results: Using pairedt-test analyses, no statistically significant difference (i.e., p > 0.05) was observed between compared spectra over energy bins above 1% of peak bremsstrahlung fluence. For all energy bins, the correlation of determination (R{sup 2}) demonstrated good correlation for all spectral comparisons. The mean overall difference (MOD) and mean absolute difference (MAD) were computed over energy bins (above 1% of peak bremsstrahlung fluence) and over all the kV permutations compared. MOD and MAD comparisons with previously reported spectra were 2.7% and 9.7%, respectively (TASMIP), 0.1% and 12.0%, respectively [R. Birch and M. Marshall, “Computation of bremsstrahlung x-ray spectra and comparison with spectra measured with a Ge(Li) detector,” Phys. Med. Biol. 24, 505–517 (1979)], 0.4% and 8.1%, respectively (Poludniowski), and 0.4% and 8.1%, respectively (AAPM TG 195). The effective energy of TASMICS spectra with 2.5 mm of added Al filtration ranged from 17 keV (at 20 kV) to 138 keV (at 640 kV); with 0.2 mm of added Cu filtration the effective energy was 9 keV at 20 kV and 169 keV at 640 kV. Conclusions: Ranging from 20 kV to 640 kV, 621 x-ray spectra were produced and are available at 1 kV tube potential intervals. The spectra are tabulated at 1 keV intervals. TASMICS spectra were shown to be largely equivalent to published spectral models and are available in spreadsheet format for interested users by emailing the corresponding author (JMB)

  2. 130kV 130A High Voltage Switching Mode Power Supply for Neutral Injections – Control Issues and Algorithms

    E-Print Network [OSTI]

    130kV 130A High Voltage Switching Mode Power Supply for Neutral Injections – Control Issues and Algorithms

  3. Deuterium Retention in Beryllium Exposed to a 60kV Deuterium Beam ­ Consequences for Next Step Devices

    E-Print Network [OSTI]

    Deuterium Retention in Beryllium Exposed to a 60kV Deuterium Beam ­ Consequences for Next Step Devices

  4. Transmission INTRODUCTION

    E-Print Network [OSTI]

    , to a significant degree, on a well-functioning wholesale power market. The transmission system is integral the consequences of a poorly designed wholesale power market, and the Council does not want to see those Regulatory Commission began taking actions to further facilitate competition in wholesale power supply. Today

  5. 150-kV, 80-A SOLID STATE POWER SUPPLY FOR NEUTRAL BEAM INJECTION

    E-Print Network [OSTI]

    Owren, H.

    2011-01-01T23:59:59.000Z

    owned rig 150-kV, 80-A SOLID STATE POWER SUPPLY FOR NEUTRALpaper describes an all solid state power supply designed forment and arc power supplies are also solid state. With the

  6. A SCR SWITCHED CAPACITOR VOLTAGE REGULATOR FOR 150 kV NEUTRAL BEAM POWER SUPPLY

    E-Print Network [OSTI]

    Milnes, K.A.

    2011-01-01T23:59:59.000Z

    et a1. , "150-kV, 80-A Solid State Power Supply for Neutral100% solid state and provides 1% regulation at power levelssolid state high voltage re- gulator. The block diagram of the power

  7. A 25 KV/10A PULSER FOR DRIVING A HIGH-POWER PIERCE ELECTRON GUN

    E-Print Network [OSTI]

    of short-circuits. Since the current capability of the tetrode is of the order of 10 A in the case of a short-circuit, the limit of the charging voltage is up to a maximum of 25 kV. The pulsed system has.0 A current and 10.0 kV beam voltage. Key words hard-tube pulser, Pierce electron gun, microwave tube

  8. Quality Assurance Plan for site electrical replacements at substation line item subproject: 69 KV Substation

    SciTech Connect (OSTI)

    Ohler, C.K.

    1991-05-21T23:59:59.000Z

    The 69 KV Substation Project is based on the recognized need to provide a continuous, reliable source of power and to improve the firm capacity of the electrical service to all production facilities at Mound. The project consists of the following major element: 69 KV Substation: (1) Install a 69 KV Substation and associated equipment with two parallel 18 MVA transformers. (2) Install duct bank as required and provide 15 KV feeder cable from new substation to existing Substation 95 for connection to Mound`s existing primary distribution system. (3) Install duct bank for underground routing of the 15 KV feeder cable from Manhole 5C to the existing power house cable pit. (4) Reconfigure existing Dayton Power and Light Co. 15 KV switchgear in P Building. The purpose of this Quality Assurance Plan (QA Plan) is to assure that the objectives of the United States Department of Energy (D.O.E.) and EG&G Mound Applied Technologies, Miamisburg, Ohio (Mound) are met for this non-weapons project relative to health and safety, protection of the environment, reliability and continuity of operations, and documentation of quality efforts. This QA Plan identifies the activities and responsibilities which are necessary in the design, procurement, fabrication, installation, and start up of this project in order to meet these objectives.

  9. Transmission Investment: A Primer

    SciTech Connect (OSTI)

    McGarvey, Joe

    2006-10-15T23:59:59.000Z

    This primer highlights recent trends in transmission investment, summarizes the division of jurisdictional authority over transmission, and presents four alternative models for transmission ownership. (author)

  10. Author's Copy: J.B. Bancroft, A. Morrison, G. Lachapelle, Validation of GNSS under 500,000 V Direct Current (DC) transmission lines, Computers and Electronics in Agriculture, Volume 83, April 2012, Pages 58-67, ISSN 0168-1699, 10.1016/j.compag.2012.01.013

    E-Print Network [OSTI]

    Calgary, University of

    masking by the towers. Tests were conducted under a set of three transmission lines, two 500 kV DC lines Current (DC) transmission lines, Computers and Electronics in Agriculture, Volume 83, April 2012, Pages 58 Validation of GNSS under 500,000 Volt Direct Current (DC) Transmission Lines J.B. Bancroft*, A. Morrison

  11. Transmission Workshop

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742EnergyOn April 23,EnergyChicopeeTechnologyfact sheetTransferring the Wayne,TRANSMISSION WORKSHOP

  12. Environmental Assessment and Finding of No Significant Impact: Wind Energy Center Edgeley/Kulm Project, North Dakota

    SciTech Connect (OSTI)

    N /A

    2003-04-15T23:59:59.000Z

    The proposed Edgeley/Kulm Project is a 21-megawatt (MW) wind generation project proposed by Florida Power and Light (FPL) Energy North Dakota Wind LLC (Dakota Wind) and Basin Electric Power Cooperative (Basin). The proposed windfarm would be located in La Moure County, south central North Dakota, near the rural farming communities of Kulm and Edgeley. The proposed windfarm is scheduled to be operational by the end of 2003. Dakota Wind and other project proponents are seeking to develop the proposed Edgeley/Kulm Project to provide utilities and, ultimately, electric energy consumers with electricity from a renewable energy source at the lowest possible cost. A new 115-kilovolt (kV) transmission line would be built to transmit power generated by the proposed windfarm to an existing US Department of Energy Western Area Power Administration (Western) substation located near Edgeley. The proposed interconnection would require modifying Western's Edgeley Substation. Modifying the Edgeley Substation is a Federal proposed action that requires Western to review the substation modification and the proposed windfarm project for compliance with Section 102(2) of the National Environmental Policy Act (NEPA) of 1969, 42 U.S.C. 4332, and Department of Energy NEPA Implementing Procedures (10 CFR Part 1021). Western is the lead Federal agency for preparation of this Environmental Assessment (EA). The US Fish and Wildlife Service (USFWS) is a cooperating agency with Western in preparing the EA. This document follows regulation issued by the Council on Environmental Quality (CEQ) for implementing procedural provisions of NEPA (40 CFR 1500-1508), and is intended to disclose potential impacts on the quality of the human environment resulting from the proposed project. If potential impacts are determined to be significant, preparation of an Environmental Impact Statement would be required. If impacts are determined to be insignificant, Western would complete a Finding of No Significant Impact (FONSI). Environmental protection measures that would be included in the design of the proposed project are included.

  13. 15-kV Single-Bias All-Optical ETO Thyristor A. Mojab and S.K. Mazumder

    E-Print Network [OSTI]

    Mazumder, Sudip K.

    15-kV Single-Bias All-Optical ETO Thyristor A. Mojab and S.K. Mazumder Laboratory for Energy 15 kV single bias and a current of 10 A. This ETO is completely controlled by two optical signals, one for the 15 kV SiC gate- turn-off (GTO) thyristor and the other one for a triggering low- voltage

  14. Waltz Mill testing of 765-kV paper-polypropylene-paper (PPP) cable

    SciTech Connect (OSTI)

    Burghardt, R.R. (Westinghouse Electric Corp., Ruffs Dale, PA (United States))

    1992-06-01T23:59:59.000Z

    A 765-kV PPP-insulated cable was subjected to a 27-month accelerated life test program at the EPRI Waltz Mill Cable Test Facility. Testing started in August 1981 and was successfully completed in January 1985. The program included conductor temperatures ranging from 85{degree}C to 105{degree}C and line-to-line voltages from 800 kV to 1050 kV. Cyclic testing was performed during 20 of the 27 months. Dissipation factor measurements were made throughout the program. The measurements indicated no deterioration of the cable or splices as a consequence of the high temperatures and voltages applied to them in this test program.

  15. Field Demonstration of a 24-kV Superconducting Cable at Detroit Edison

    SciTech Connect (OSTI)

    Kelley, Nathan; Corsaro, Pietro

    2004-12-01T23:59:59.000Z

    Customer acceptance of high temperature superconducting (HTS) cable technology requires a substantial field demonstration illustrating both the system's technical capabilities and its suitability for installation and operation within the utility environment. In this project, the world's first underground installation of an HTS cable using existing ductwork, a 120 meter demonstration cable circuit was designed and installed between the 24 kV bus distribution bus and a 120 kV-24 kV transformer at Detroit Edison's Frisbie substation. The system incorporated cables, accessories, a refrigeration system, and control instrumentation. Although the system was never put in operation because of problems with leaks in the cryostat, the project significantly advanced the state-of-the-art in the design and implementation of Warm Dielectric cable systems in substation applications. Lessons learned in this project are already being incorporated in several ongoing demonstration projects.

  16. Development of 275kV gas cooled type gas-insulated power transformer

    SciTech Connect (OSTI)

    Kudo, A.; Nishitani, T.; Yoshikawa, T. (Mitsubishi Electric Corp., Ako (Japan)); Wan, C.T. (Hongkong Electric Co., Ltd. (Hong Kong))

    1993-01-01T23:59:59.000Z

    A world's first 275kV gas cooled type gas insulated power transformer with a low sound level ideal for urban area, which depends on SF6 gas alone for both insulation and cooling, was developed and has been put into commercial service since 1990 in Hong Kong. This paper presents the design philosophy, the principal technical items, the rating and the feature of 275kV 30MVA transformer, the performance test results, and the long term energization test result of the transformer.

  17. Fort Peck-Havre transmission line project, Hill, Blaine, Phillips, Valley and McCone Counties, Montana

    SciTech Connect (OSTI)

    Not Available

    1982-09-01T23:59:59.000Z

    Construction and operation of a 180-mile, 230-kilovlt (kV) transmission line between Fort Peck and Havre, Montana is proposed to provide a replacement for the 161-kV line that currently runs between the two cities. The new line would be carried on woodpole, H-frame structures. The existing 161-kV line would be removed, and the Richardson Coulee Substation would be relocated. Intermediate facilities to be improved would include the Fort Peck Switchyard and the Richardson Coulee, Malta, Harlem, and Havre substations.Construction of the line would commence in August 1983, and operation would commence in January 1986. The expected life of the transmission system would be 100 years. Estimated cost of the project, in 1983 dollars, is $36.1 million. The project would upgrade an essential element of the Western Area Power Administration's electric power system and the Montana Power Company's interconnected transmission network. Continued electric service reliability would be improved, and safety conditions affecting personnel who maintain the line would be enhanced. Additional transmission capacity would be provided to accommodate future load growth, precluding the need for multiple transmission lines. The line would eleminate seven acres of productive land and create physical conflicts with present and future agricultural activities. The line would traverse areas characterized by concentrations of archaeological resources and cultural resources of importance to native Americans. Transmission structures could mar scenery in areas with historically significant architecture and would interfere with waterfowl.

  18. Performance of a technical and economical feasibility study of an HVDC compressed gas insulated transmission line. [600 kV

    SciTech Connect (OSTI)

    LaBarge, R.L.

    1980-12-15T23:59:59.000Z

    Progress in evaluating the technical feasibility of SF/sub 6/-insulated cables and circuit breakers for HVDC systems is reported. During this reporting period a new test setup was completed. An assembly jig was designed and fabricated. Model cable up to 20-ft length can be assembled complete outside the test tank. Components to extend the test tank to accommodate a 20-ft model cable have been obtained. A report was drafted on the effect of material selection as well as processing into insulators on the long-term dielectric performance of the insulator. The vertical leaf expansion joint design was improved by replacing the Alcuplate copper-to-aluminum transition piece with nickel plating on the aluminum parts. The joint was fatigue tested with condition which simulate almost 2 1/2 cycles of temperature excursions each day for the 40 year design life of the line. Electrical tests of the joint are in progress.

  19. EIS-0079: 300-kV International Submarine Transmission Line- Erie, Pennsylvania to Nanticoke, Ontario, Canada General Public Utilities Corporation

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy Office of Energy Emergency Operations developed this statement to assess the potential environmental and socioeconomic impacts of the construction and operation of 44 miles of cable between the Erie West Substation and the Canadian border.

  20. EA-2002: Right-of-Way Application for the Tucson-Apache 115-kV Transmission

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742Energy China U.S.ContaminationJulySavannah River Site for Use by the State of SouthLine, Pima

  1. A charge-pump 60kV modulator for the ISOLDE target extraction voltage

    E-Print Network [OSTI]

    Barlow, R A; Fowler, A; Gaudillet, H; Gharsa, T; Schipper, J

    2015-01-01T23:59:59.000Z

    The ISOLDE facility at CERN provides radioactive ion beams to a number of experimental stations. These ions are produced by a metal target, floating at 60 kV, which is impacted by a 1.4 GeV high intensity proton beam. The ions are then accelerated by a grounded extraction electrode to 60 keV, before transport to the experimental area. During proton beam impact extremely high ionisation of the volume around the target gives rise to significant leakage current which results in loss of charge on the effective target capacitance of approximately 6 nF. If short life-time isotopes are to be studied, the 60 kV must be re-established within a maximum of 10 ms. Recharging the target capacitance to 60 kV and to the required stability of better than 10-4 precludes a direct charging system and an alternative method of re-establishing the 60 kV is used. The present system [1], in operation since 1991, employs a resonant circuit which is triggered 35 µs prior to beam impact. This circuit transfers the charge on the effec...

  2. Survey of Transmission Cost Allocation Methodologies for Regional Transmission Organizations

    SciTech Connect (OSTI)

    Fink, S.; Porter, K.; Mudd, C.; Rogers, J.

    2011-02-01T23:59:59.000Z

    The report presents transmission cost allocation methodologies for reliability transmission projects, generation interconnection, and economic transmission projects for all Regional Transmission Organizations.

  3. FINAL PROJECT REPORT LOAD MODELING TRANSMISSION RESEARCH

    E-Print Network [OSTI]

    Lesieutre, Bernard

    2013-01-01T23:59:59.000Z

    communications in the substation Example Costs: Instrument115-kV “B” Substations SVC Unit Cost ($ Millions) Total115-kV “B” Substations SVC Unit Cost ($ Millions) Total SVC

  4. Electric power high-voltage transmission lines: Design options, cost, and electric and magnetic field levels

    SciTech Connect (OSTI)

    Stoffel, J.B.; Pentecost, E.D.; Roman, R.D.; Traczyk, P.A.

    1994-11-01T23:59:59.000Z

    This report provides background information about (1) the electric and magnetic fields (EMFs) of high-voltage transmission lines at typical voltages and line configurations and (2) typical transmission line costs to assist on alternatives in environmental documents. EMF strengths at 0 {+-} 200 ft from centerline were calculated for ac overhead lines, and for 345 and 230-kV ac underground line and for a {+-}450-kV dc overhead line. Compacting and height sensitivity factors were computed for the variation in EMFs when line conductors are moved closer or raised. Estimated costs for the lines are presented and discussed so that the impact of using alternative strategies for reducing EMF strengths and the implications of implementing the strategies can be better appreciated.

  5. Merchant transmission investment

    E-Print Network [OSTI]

    Joskow, Paul L.

    2003-01-01T23:59:59.000Z

    We examine the performance attributes of a merchant transmission investment framework that relies on "market driven" transmission investment to provide the infrastructure to support competitive wholesale markets for ...

  6. Economic Development from New Generation and Transmission in Wyoming and Colorado

    SciTech Connect (OSTI)

    Keyser, D.; Lantz, E.

    2013-03-01T23:59:59.000Z

    This report analyzes the potential economic impacts in Colorado and Wyoming of a 225 MW natural gas fired electricity generation facility and a 900 MW wind farm constructed in Wyoming as well as a 180 mile, 345 kV transmission line that runs from Wyoming to Colorado. This report and analysis is not a forecast, but rather an estimate of economic activity associated with a hypothetical scenario.

  7. Economic Development from New Generation and Transmission in Wyoming and Colorado (Fact Sheet)

    SciTech Connect (OSTI)

    Not Available

    2013-03-01T23:59:59.000Z

    This report analyzes the potential economic impacts in Colorado and Wyoming of a 225 MW natural gas fired electricity generation facility and a 900 MW wind farm constructed in Wyoming as well as a 180 mile, 345 kV transmission line that runs from Wyoming to Colorado. This report and analysis is not a forecast, but rather an estimate of economic activity associated with a hypothetical scenario.

  8. EA-1863: Vegetation Management on the Glen Canyon-Pinnacle Peak Transmission Lines Spanning the Coconino National Forest, Coconino County, Arizona

    Broader source: Energy.gov [DOE]

    DOE’s Western Area Power Administration is preparing this EA to evaluate the environmental impacts of updating the vegetation management and right-of-way maintenance program for Western’s Glen Canyon to Pinnacle Peak 345-kV transmission lines, which cross the Coconino National Forest, Coconino County, Arizona.

  9. Transmission grid access and pricing in Norway, Spain, and California: A comparative study

    SciTech Connect (OSTI)

    Gronli, H.; Gomez San Ramon, T.; Marnay, C.

    1999-09-01T23:59:59.000Z

    The openness of the transmission grid and the incentives given by transmission pricing form the foundation for retail and wholesale competition in the electricity market. The deregulated markets of Norway, Spain, and California all have introduced retail access and wholesale competition, although with different approaches to pricing of transmission grid services. This paper will briefly describe the three different solutions, and discuss some of their implications. Of the three electricity systems, Norway was the first to open the grid to competition in electricity trade. The Norwegian Energy Law of 1990 introduced open competition to wholesale and retail trade starting January 1991. In Spain, the Electricity Law of 1997 came into force early in 1998. Wholesale and retail markets in California were opened for competition on April 1, 1998, following the passage of Assembly Bill 1890, in August 1996. Introducing competition in electricity markets also implies introducing Third Party Access to the transmission grid. All potential competitors have to be given access to the grid in order to compete, no matter who owns the actual wires. This principle raises several challenges, notably, how to price transmission services. Who is to pay for which transmission services? The Norwegian grid is divided into three levels depending on its function. The transmission grid includes all parts of the national grid having a transmission function, meaning that some lower voltage levels also are included. In Spain, the definition of the transmission grid is similar, including the 400 kV and 220 kV national grid as well as lower voltage installations that could affect transmission operation or generation dispatch. For historic reasons, wholesale electricity transactions in the US are regulated by the federal government through the FERC. However, operations of utility systems within one state fall primarily under state jurisdiction. Because the utility systems in California generally are large and exchanges between them limited, the role of FERC was small prior to restructuring, although the state is a large importer of power.

  10. Development of 500 kV DC PPLP-insulated oil-filled submarine cable

    SciTech Connect (OSTI)

    Fujimori, A. [Kansai Electric Power Co., Inc., Osaka (Japan)] [Kansai Electric Power Co., Inc., Osaka (Japan); Tanaka, T. [Electric Power Development Co., Ltd., Tokyo (Japan)] [Electric Power Development Co., Ltd., Tokyo (Japan); Takashima, H. [Shikoku Electric Power Co., Inc., Kagawa (Japan)] [Shikoku Electric Power Co., Inc., Kagawa (Japan); Imajo, T. [Central Research Inst. of Electric Power Industry, Tokyo (Japan)] [Central Research Inst. of Electric Power Industry, Tokyo (Japan); Hata, R. [Sumitomo Electric Industries, Ltd., Osaka (Japan)] [Sumitomo Electric Industries, Ltd., Osaka (Japan); Tanabe, T. [Furukawa Electric Co., Ltd., Tokyo (Japan)] [Furukawa Electric Co., Ltd., Tokyo (Japan); Yoshida, S. [Fujikura, Ltd., Tokyo (Japan)] [Fujikura, Ltd., Tokyo (Japan); Kakihana, T. [Hitachi Cable, Ltd., Tokyo (Japan)] [Hitachi Cable, Ltd., Tokyo (Japan)

    1996-01-01T23:59:59.000Z

    This paper outlines the development of a 500 kV DC oil-filled submarine cable capable of transmitting 2,800 MW with {+-} 500 kV 2800A bipole system. Polypropylene Laminated Paper (PPL) was employed as the insulation material, which is the worlds first application to DC cables. The conductor size is 3,000 mm{sup 2}, which is the largest size for submarine cables ever put into practical use. Through various fundamental and prototype tests, the cable proved to have excellent electrical characteristics for DC voltage as well as transient overvoltage. The cable and accessories are currently undergoing a long-term accelerated aging test as the final confirmation of their reliability and stability.

  11. A 6 kV arbitrary waveform generator for the Tevatron Electron Lens

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Pfeffer, H.; Saewert, G.

    2011-11-01T23:59:59.000Z

    This paper reports on a 6 kV modulator built and installed at Fermilab to drive the electron gun anode for the Tevatron Electron Lens (TEL). The TEL was built with the intention of shifting the individual (anti)proton bunch tunes to even out the tune spread among all 36 bunches with the desire of improving Tevatron integrated luminosity. This modulator is essentially a 6 kV arbitrary waveform generator that enables the TEL to define the electron beam intensity on a bunch-by-bunch basis. A voltage waveform is constructed having a 7 {micro}s duration that corresponds to the tune shift requirements of amore »12-bunch (anti)proton beam pulse train. This waveform is played out for any one or all three bunch trains in the Tevatron. The programmed waveform voltages transition to different levels at time intervals corresponding to the 395 ns bunch spacing. Thus, complex voltage waveforms can be played out at a sustained rate of 143 kHz over the full 6 kV output range. This paper describes the novel design of the inductive adder topology employing five transformers. It describes the design aspects that minimize switching losses for this multi-kilovolt, high repetition rate and high duty factor application.« less

  12. Measurements on a FET based 1 MHz, 10 kV pulse generator

    SciTech Connect (OSTI)

    Wait, G.D.; Barnes, M.J.

    1995-08-01T23:59:59.000Z

    A prototype pulser, which incorporates thirty-two 1 kV Field-Effect Transistor (FET) modules, has been built and tested at TRIUMF. The pulser has been developed for application in a scheme for pulsed extraction from the TRIUMF 500 MeV cyclotron. Deflection of the beam will be provided by an electric field between a set of 1 in long deflector plates. The pulser generates a continuous, unipolar, pulse train at a fundamental frequency of approximately 1 MHz and a magnitude of 10 kV. The pulses have 38 ns rise and fall times and are stored on a low-loss coaxial cable which interconnects the pulse generator and the deflector plates. The circuit performance was evaluated with the aid of PSpice in the design stage and confirmed by measurements on the prototype. Temperature measurements have been performed on 1 kV FET modules under DC conditions and compared with temperatures under operating conditions to ensure that switching losses are acceptable. Results of various measurements are presented and compared with simulations.

  13. A 6 kV arbitrary waveform generator for the Tevatron Electron Lens

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Pfeffer, H.; Saewert, G.

    2011-11-01T23:59:59.000Z

    This paper reports on a 6 kV modulator built and installed at Fermilab to drive the electron gun anode for the Tevatron Electron Lens (TEL). The TEL was built with the intention of shifting the individual (anti)proton bunch tunes to even out the tune spread among all 36 bunches with the desire of improving Tevatron integrated luminosity. This modulator is essentially a 6 kV arbitrary waveform generator that enables the TEL to define the electron beam intensity on a bunch-by-bunch basis. A voltage waveform is constructed having a 7 {micro}s duration that corresponds to the tune shift requirements of a 12-bunch (anti)proton beam pulse train. This waveform is played out for any one or all three bunch trains in the Tevatron. The programmed waveform voltages transition to different levels at time intervals corresponding to the 395 ns bunch spacing. Thus, complex voltage waveforms can be played out at a sustained rate of 143 kHz over the full 6 kV output range. This paper describes the novel design of the inductive adder topology employing five transformers. It describes the design aspects that minimize switching losses for this multi-kilovolt, high repetition rate and high duty factor application.

  14. EA-1948: Gila-North Gila Transmission Line Rebuild and Upgrade Project, Yuma County, Arizona

    Broader source: Energy.gov [DOE]

    DOE’s Western Area Power Administration (Western) prepared this EA to analyze the potential environmental impacts of a proposal to rebuild and upgrade two parallel 4.8-mile transmission lines between the Gila and North Gila Substations and take actions in support of portions of Arizona Public Service’s construction of a new, 12.8 mile 230-kV transmission line between North Gila and a proposed substation in Yuma County, Arizona. The U.S. Bureau of Reclamation and U.S. Army Corps of Engineers are cooperating agencies.

  15. Canby Area Service Project substation and associated transmission line. Environmental Assessment

    SciTech Connect (OSTI)

    Not Available

    1992-02-01T23:59:59.000Z

    Bonneville Power Administration (BPA) provides power to Surprise Valley Electrification Corporation (SVEC) in Modoc County, California. BPA uses PacificCorp`s substation and transmission facilities between Alturas and Canby, California to transfer power to SVEC`s Canby Substation. In the next year, SVEC expects increased industrial, agricultural, and residential electric loads on their 69-kV transmission system south of Canby. SVEC`s substation can accommodate only about 10 percent of the expected additional electric load. BPA`s proposed action is intended to meet SVEC`s increasing electric load. BPA proposes to meet SVEC`s increasing energy load by tapping into BPA`s existing BPA Malin-Warner 230-kV transmission line, and building an 7.9-mile transmission line to a new BPA substation. BPA proposes to build the new substation next to the west side of SVEC`s Canby Substation (Figure 1). This new substation will allow SVEC to move the additional power over their existing transmission or distribution lines. This report is the environmental assessment of the potential impact of the proposed project. The assessment determined that no ``environmental impact statement`` is not required.

  16. Canby Area Service Project : Substation and Associated Transmission Line : Environmental Assessment.

    SciTech Connect (OSTI)

    United States. Bonneville Power Administration.

    1992-02-01T23:59:59.000Z

    Bonneville Power Administration (BPA) provides power to Surprise Valley Electrification Corporation (SVEC) in Modoc County, California. BPA uses PacificCorp's substation and transmission facilities between Alturas and Canby, California to transfer power to SVEC's Canby Substation. In the next year, SVEC expects increased industrial, agricultural, and residential electric loads on their 69-kV transmission system south of Canby. SVEC's substation can accommodate only about 10 percent of the expected additional electric load. BPA's proposed action is intended to meet SVEC's increasing electric load. BPA proposes to meet SVEC's increasing energy load by tapping into BPA's existing BPA Malin-Warner 230-kV transmission line, and building an 7.9-mile transmission line to a new BPA substation. BPA proposes to build the new substation next to the west side of SVEC's Canby Substation (Figure 1). This new substation will allow SVEC to move the additional power over their existing transmission or distribution lines. This report is the environmental assessment of the potential impact of the proposed project. The assessment determined that no environmental impact statement'' is not required.

  17. Supplement Analysis for the Transmission System Vegetation Management Program FEIS (DOE/EIS-0285/SA-15)

    SciTech Connect (OSTI)

    N /A

    2001-06-19T23:59:59.000Z

    BPA proposes to clear unwanted vegetation in the rights-of-ways and around tower structures that may impede the operation and maintenance of the subject transmission lines. Work also includes clearing of a small (<1/4 mile) section of access road. All work will be in accordance with the National Electrical Safety Code and BPA standards. See Section 1.1 of the attached checklist for detailed information on each section of the referenced transmission lines. BPA will conduct the vegetation control with the goal of removing tall-growing vegetation that is currently or will soon be a hazard to the transmission lines and where possible to promote low-growing plant communities in the right-of-way. This project meets the standards and guidelines for the Transmission System Vegetation Management Program Final Environmental Impact Statement (FEIS) and Record of Decision (ROD). The vegetation needing control is mainly Douglas Fir, Alder, and blackberries as indicated in Section 1.2 of the attached checklist. The work involved in the ROW includes: clearing tall growing vegetation that is currently or will soon pose a hazard to the lines; treating the associated stumps and re-sprouts with herbicide to ensure that the roots are killed preventing new sprouts; and selectively eliminating tall growing vegetation before it reaches a height or density to begin competing with low-growing vegetation. All work will take place in existing rights-of-ways and around transmission structures. All work will be accomplished by selective vegetation control methods to assure that there is little potential harm to non-target vegetation and to low-growing plants. The work will provide system reliability and fire protection. Also, all off right-of-way trees that are potentially unstable and will fall within a minimum distance or into the zone where the conductors swing will be removed. Access roads will be treated using mowing and herbicide applications. The work will provide system reliability. The subject transmission lines range from 115kV to 230kV and are made up of accompanying access roads, steel and wooden transmission line structures and associated switching platforms. The minimum clearance ranges from 21 feet for 115kV lines to 23 feet for 230kV lines. ROW easement widths vary along the length of the project. Vegetation control for this project is designed to provide a 3 year maintenance free interval. In summary, the overall vegetation management scheme will be to selectively remove tall growing vegetation then apply selective herbicide treatment using cut stump applications.

  18. Transmission Commercial Project Integration

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Improvement (CBPI) Customer Forum Energy Imbalance Market Generator Interconnection Reform Implementation Network Integration Transmission Service (NT Service) Network Open...

  19. Abstract Number #10041 A 150kV/300A/1s COAXIAL BLUMLEIN PULSER

    E-Print Network [OSTI]

    . They consist of pieces of transmission lines charged in parallel , which discharge synchronously in series generators made of pieces of transmission lines and normally used in a great variety of applications

  20. Automated manual transmission controller

    DOE Patents [OSTI]

    Lawrie, Robert E. (Whitmore Lake, MI); Reed, Jr., Richard G. (Royal Oak, MI); Bernier, David R. (Rochester Hills, MI)

    1999-12-28T23:59:59.000Z

    A powertrain system for a hybrid vehicle. The hybrid vehicle includes a heat engine, such as a diesel engine, and an electric machine, which operates as both an electric motor and an alternator, to power the vehicle. The hybrid vehicle also includes a manual-style transmission configured to operate as an automatic transmission from the perspective of the driver. The engine and the electric machine drive an input shaft which in turn drives an output shaft of the transmission. In addition to driving the transmission, the electric machine regulates the speed of the input shaft in order to synchronize the input shaft during either an upshift or downshift of the transmission by either decreasing or increasing the speed of the input shaft. When decreasing the speed of the input shaft, the electric motor functions as an alternator to produce electrical energy which may be stored by a storage device. Operation of the transmission is controlled by a transmission controller which receives input signals and generates output signals to control shift and clutch motors to effect smooth launch, upshift shifts, and downshifts of the transmission, so that the transmission functions substantially as an automatic transmission from the perspective of the driver, while internally substantially functioning as a manual transmission.

  1. Cost comparison of 138 kV relay at TSS Natoma

    SciTech Connect (OSTI)

    Whetter, A.J. [ComEd, Chicago, IL (United States)

    1996-10-01T23:59:59.000Z

    This paper compares the costs of retro-fitting an electro-mechanical directional comparison blocking scheme with a microprocessor based dual directional comparison and under-reaching direct transfer tripping scheme on an existing panel at a 138 kV substation. Comparison is between the material, fabrication, engineering, drafting, construction, and testing costs. The cost per function of each scheme will be defined and compared. The results of this comparison will demonstrate the advantages of the new microprocessor based schemes in material costs, labor costs, and cost per function.

  2. Failure evaluation of underground high voltage cables (115 kV) in Mazatlan, Sinaloa: Microscopic method

    SciTech Connect (OSTI)

    Valero-Huerta, M.A.; Ramirez-Delgado, R. [Lab. de Pruebas de Equipos y Materiales, Irapuato (Mexico)

    1995-11-01T23:59:59.000Z

    The present paper is a complete analysis of the failure which occurred to the 115 kV power cable installed between the Mazatlan Centro and Mazatlan Norte Substations. Laboratory analysis that established the causes of the failure are included. It was concluded that the failure of the cable was provoked by the entrance of sewage water to the screen, and due to the presence of anaerobic organisms, resulted in the formation of sulfidic acid, which caused the severe corrosion that can be observed in the screen. The resulting loss of conductivity provoked heating capable of melting the isolator until its rupture.

  3. Operating characteristics and modeling of the LLNL 100-kV electric gun

    SciTech Connect (OSTI)

    Osher, J.E.; Barnes, G.; Chau, H.H.; Lee, R.S.; Lee, C.; Speer, R.; Weingart, R.C.

    1989-06-01T23:59:59.000Z

    In the electric gun, the explosion of an electrically heated metal foil and the accompanying magnetic forces drive a thin flyer plate up a short barrel. Flyer velocities of up to 18 km/s make the gun useful for hypervelocity impact studies. The authors briefly review the technological evolution of the exploding-metal circuit elements that power the gun, describe the 100-kV electric gun designed at Lawrence Livermore National Laboratory (LLNL) in some detail, and present the general principles of electric gun operation. They compare the experimental performance of the LLNL gun with a simple model and with predictions of a magnetohydrodynamics code.

  4. KvH Projekt GmbH Co KG | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand Jump to: navigation, searchOf Kilauea Volcano, Hawaii9969995°,I Jump to:Kumagai Gumi CoKuwaitKvH

  5. Cryogenic System for a High Temperature Superconducting Power Transmission Cable

    SciTech Connect (OSTI)

    Demko, J.A.; Gouge, M.J.; Hughey, R.L.; Lue, J.W.; Martin, R.; Sinha, U.; Stovall, J.P.

    1999-07-12T23:59:59.000Z

    High-temperature superconducting (HTS) cable systems for power transmission are under development that will use pressurized liquid nitrogen to provide cooling of the cable and termination hardware. Southwire Company and Oak Ridge National Laboratory have been operating a prototype HTS cable system that contains many of the typical components needed for a commercial power transmission application. It is being used to conduct research in the development of components and systems for eventual commercial deployment. The cryogenic system was built by Air Products and Chemicals, Allentown, Pennsylvania, and can circulate up to 0.35 kg/s of liquid nitrogen at temperatures as low as 67 K at pressures of 1 to 10 bars. Sufficient cooling is provided for testing a 5-m-long HTS transmission cable system that includes the terminations required for room temperature electrical connections. Testing of the 5-m HTS transmission cable has been conducted at the design ac conditions of 1250 A and 7.5 kV line to ground. This paper contains a description of the essential features of the HTS cable cryogenic system and performance results obtained during operation of the system. The salient features of the operation that are important in large commercial HTS cable applications will be discussed.

  6. Commissioning and Operation of 130kV/130A Switched-Mode HV Power Supplies with the Upgraded JET Neutral Beam Injectors

    E-Print Network [OSTI]

    Commissioning and Operation of 130kV/130A Switched-Mode HV Power Supplies with the Upgraded JET Neutral Beam Injectors

  7. Series Transmission Line Transformer

    DOE Patents [OSTI]

    Buckles, Robert A. (Livermore, CA); Booth, Rex (Livermore, CA); Yen, Boris T. (El Cerrito, CA)

    2004-06-29T23:59:59.000Z

    A series transmission line transformer is set forth which includes two or more of impedance matched sets of at least two transmissions lines such as shielded cables, connected in parallel at one end ans series at the other in a cascading fashion. The cables are wound about a magnetic core. The series transmission line transformer (STLT) which can provide for higher impedance ratios and bandwidths, which is scalable, and which is of simpler design and construction.

  8. 2012 Transmission Rate Schedules

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    2014 Transmission, Ancillary, and Control Area Service Rate Schedules and General Rate Schedule Provisions (FY 2014-2015) October 2013 United States Department of Energy...

  9. Electric Transmission Lines (Nebraska)

    Broader source: Energy.gov [DOE]

    The Public Service Commission has jurisdiction over all electricity transmission lines crossing over or under railroad tracks at public highway crossings. This section contains general regulations...

  10. Patterns of transmission investment

    E-Print Network [OSTI]

    Joskow, Paul L.

    2005-01-01T23:59:59.000Z

    This paper examines a number of issues associated with alternative analytical approaches for evaluating investments in electricity transmission infrastructure and alternative institutional arrangements to govern network ...

  11. Collaborative Transmission Technology Roadmap

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    techniques, and tools to analyze data from power quality recorders Size-up demand response opportunities Transmission level monitoring with PMUs is not sufficient and needs to...

  12. Revised Biological Assessment for the Carrizo-Midway 230kV Reconductor...

    Broader source: Energy.gov (indexed) [DOE]

    (CAISO) has determined that transmission upgrades will be required to deliver the energy generated by proposed the Topaz Solar Farm Project on the Carrizo Plain....

  13. 1.9 kV AlGaN/GaN Lateral Schottky Barrier Diodes on Silicon

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Zhu, Mingda [University of Notre Dame, IN (United States); Song, Bo [Cornell University, Ithaca, NY (United States); Qi, Meng [University of Notre Dame, IN (United States); Hu, Zongyang [University of Notre Dame, IN (United States); Nomoto, Kazuki [University of Notre Dame, IN (United States); Yan, Xiaodong [University of Notre Dame, IN (United States); Cao, Yu [IQE, Westborough, MA (United States); Johnson, Wayne [IQE, Westborough, MA (United States); Kohn, Erhard [University of Notre Dame, IN (United States); Jena, Debdeep [Cornell University, Ithaca, NY (United States); Xing, Grace Huili [Cornell University, Ithaca, NY (United States)

    2015-04-01T23:59:59.000Z

    In this letter, we present AlGaN/GaN lateral Schottky barrier diodes on silicon with recessed anodes and dual field plates. A low specific on-resistance RON,SP (5.12 m?{center_dot}cm2), a low turn-on voltage (1.9 kV), were simultaneously achieved in devices with a 25 ?m anode/cathode separation, resulting in a power figure-of-merit (FOM) BV2/RON,SP of 727 MW{center_dot}cm2. The record high breakdown voltage of 1.9 kV is attributed to the dual field plate structure.

  14. The design, construction, and operation of long-distance high-voltage electricity transmission technologies.

    SciTech Connect (OSTI)

    Molburg, J. C.; Kavicky, J. A.; Picel, K. C.

    2008-03-03T23:59:59.000Z

    This report focuses on transmission lines, which operate at voltages of 115 kV and higher. Currently, the highest voltage lines comprising the North American power grid are at 765 kV. The grid is the network of transmission lines that interconnect most large power plants on the North American continent. One transmission line at this high voltage was built near Chicago as part of the interconnection for three large nuclear power plants southwest of the city. Lines at this voltage also serve markets in New York and New England, also very high demand regions. The large power transfers along the West Coast are generally at 230 or 500 kV. Just as there are practical limits to centralization of power production, there are practical limits to increasing line voltage. As voltage increases, the height of the supporting towers, the size of the insulators, the distance between conductors on a tower, and even the width of the right-of-way (ROW) required increase. These design features safely isolate the electric power, which has an increasing tendency to arc to ground as the voltage (or electrical potential) increases. In addition, very high voltages (345 kV and above) are subject to corona losses. These losses are a result of ionization of the atmosphere, and can amount to several megawatts of wasted power. Furthermore, they are a local nuisance to radio transmission and can produce a noticeable hum. Centralized power production has advantages of economies of scale and special resource availability (for instance, hydro resources), but centralized power requires long-distance transfers of power both to reach customers and to provide interconnections for reliability. Long distances are most economically served at high voltages, which require large-scale equipment and impose a substantial footprint on the corridors through which power passes. The most visible components of the transmission system are the conductors that provide paths for the power and the towers that keep these conductors at a safe distance from each other and from the ground and the natural and built environment. Common elements that are generally less visible (or at least more easily overlooked) include the maintained ROW along the path of the towers, access roads needed for maintenance, and staging areas used for initial construction that may be restored after construction is complete. Also visible but less common elements along the corridor may include switching stations or substations, where lines of similar or different voltages meet to transfer power.

  15. EIS-0400: Granby Pumping Plant Switchyard-Windy Gap Substation Transmission Line Rebuild Project, Grand County, CO

    Broader source: Energy.gov [DOE]

    Western Area Power Administration prepared an EIS, with the U.S. Forest Service, Bureau of Land Management, and Grand County (Colorado) as cooperating agencies, to evaluate the potential environmental impacts of rebuilding a 12-mile, 69 kV electric transmission line in Grand County. The proposed project would rebuild the single-circuit line as a double-circuit transmission line and add a second power transformer. Western identified potentially significant impacts while preparing an EA for this proposal (DOE/EA-1520) and prepared an EIS instead of completing the EA. Further information about the project is available on the project website.

  16. Transmission Line Security Monitor

    ScienceCinema (OSTI)

    None

    2013-05-28T23:59:59.000Z

    The Transmission Line Security Monitor is a multi-sensor monitor that mounts directly on high-voltage transmission lines to detect, characterize and communicate terrorist activity, human tampering and threatening conditions around support towers. For more information about INL's critical infrastructure protection research, visit http://www.facebook.com/idahonationallaboratory.

  17. Transmission Line Security Monitor

    SciTech Connect (OSTI)

    None

    2011-01-01T23:59:59.000Z

    The Transmission Line Security Monitor is a multi-sensor monitor that mounts directly on high-voltage transmission lines to detect, characterize and communicate terrorist activity, human tampering and threatening conditions around support towers. For more information about INL's critical infrastructure protection research, visit http://www.facebook.com/idahonationallaboratory.

  18. Transmission Enhancement Technology Report

    E-Print Network [OSTI]

    of Existing Transmission 6 5. Potential New Equipment to Improve Transmission Capability 9 6. Potential New parties for the sites that should be studied as potential locations for new generation and to consult lignite and wind energy. " As per the requirements of the above-referenced Congressional direction

  19. A New 500-kV Ion Source Test Stand for HIF

    SciTech Connect (OSTI)

    Sangster, T.C.; Ahle, L.E.; Halaxa, E.F.; Karpenko, V.P.; Oldaker, M. E.; Mitchell, J.W.; Beck, D.N.; Bieniosek, F.M.; Henestroza, E.; Kwan, J.W.

    2000-10-05T23:59:59.000Z

    One of the most challenging aspects of ion beam driven inertial fusion energy is the reliable and efficient generation of low emittance, high current ion beams. The primary ion source requirements include a rise time of order 1-msec, a pulse width of at least 20-msec, a flattop ripple of less than 0.1% and a repetition rate of at least 5-Hz. Naturally, at such a repetition rate, the duty cycle of the source must be greater than 108 pulses. Although these specifications do not appear to exceed the state-of-the-art for pulsed power, considerable effort remains to develop a suitable high current ion source. Therefore, we are constructing a 500-kV test stand specifically for studying various ion source concepts including surface, plasma and metal vapor arc. This paper will describe the test stand design specifications as well as the details of the various subsystems and components.

  20. Transmission Cost Allocation Methodologies for Regional Transmission Organizations

    SciTech Connect (OSTI)

    Fink, S.; Rogers, J.; Porter, K.

    2010-07-01T23:59:59.000Z

    This report describes transmission cost allocation methodologies for transmission projects developed to maintain or enhance reliability, to interconnect new generators, or to access new resources and enhance competitive bulk power markets, otherwise known as economic transmission projects.

  1. Joint HVAC Transmission EMF Environmental Study : Final Report on Experiment 1.

    SciTech Connect (OSTI)

    United States. Bonneville Power Administration; Oregon Regional Primate Research Center

    1992-05-01T23:59:59.000Z

    This document describes the rationale, procedures, and results of a carefully controlled study conducted to establish whether chronic exposure of female (ewe) Suffolk lambs to the environment of a 500-kV 60-Hz transmission line would affect various characteristics of growth, endocrine function, and reproductive development. This experiment used identical housing and management schemes for control and line-exposed ewes, thus minimizing these factors as contributors to between-group experimental error. Further, throughout the 10-month duration of this study, changes in electric and magnetic fields, audible noise, and weather conditions were monitored continuously by a computerized system. Such measurements provided the opportunity to identify any relationship between environmental factors and biological responses. Because of reports in the literature that electric and magnetic fields alter concentrations of melatonin in laboratory animals, the primary objective of this study was to ascertain whether a similar effect occurs in lambs exposed to a 500-kV a-c line in a natural setting. In addition, onset of puberty, changes in body weight, wool growth, and behavior were monitored. To determine whether the environment of a 500-kV line caused stress in the study animals, serum levels of cortisol were measured. The study was conducted at Bonneville Power Administration`s Ostrander Substation near Estacada, Oregon.

  2. A novel voltage-gated potassium ion channel gene (Kv5.1): Molecular cloning and characterization

    SciTech Connect (OSTI)

    Beisel, K.W.; Lofton, N.C.; Kelley, P.M. Jr. [Boys Town National Research Hospital, Omaha, NE (United States)] [and others

    1994-09-01T23:59:59.000Z

    Voltage-activated potassium channels comprise a family of genes which play a role in the electrophysiological properties of neurosensory and neuronal tissue. We have recently identified a novel voltage-gated potassium ion channel (designated as Kv5.1) using the both RT-PCR with degenerative oligodeoxynucleotide primers and dideoxy sequence analyses. A full length sequence of the mature transcript was obtained by mRNA walking using gene-specific oligodeoxynucleotide primers. The deduced amino acid sequence suggested that this protein has six hydrophobic membrane spanning regions (S1-S6) and an ion-selective pore (P or H5) located between S5 and S6. This structural motif is found in other members of this gene family. Kv5.1 has an amino acid sequence homology of 55% with the Shab gene, Kv2.1, within the N-terminus and the membrane spanning regions. No sequence homology was found for the C-terminus. Northern analysis using mRNA isolated from a panel of rat tissues demonstrated that a 2.4 kb message was expressed in heart and cochlear tissue. Because of the low sequence homology and the unique tissue distribution, we have tentatively assigned the Kv5.1 gene as a new subfamily. Both the rat and human homologues were sequenced and the nucleotide and amino acid homologies were 88% and 96%, respectively. In the rat, the open reading frame encodes a 540-amino acid protein with a predicted molecular mass of 61,781 daltons. Interestingly, the human homologue is truncated by 83 residues in the C-terminus by a stop codon. We have recently isolated a human genomic {lambda} clone which contains the entire human gene and are now determining chromosomal location of Kv5.1 by in situ hybridization and PCR analysis of DNA from a panel of somatic cell hybrids.

  3. Designing electricity transmission auctions

    E-Print Network [OSTI]

    Greve, Thomas; Pollitt, Michael G.

    2012-10-26T23:59:59.000Z

    The UK has ambitious plans for exploiting offshore wind for electricity production in order to meet its challenging target under the EU Renewable Energy Directive. This could involve investing up to 20bn in transmission assets to bring electricity...

  4. Transmission Services Bulletin

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Standard Time On the first Sunday in November Transmission Services sets clocks from Daylight Savings Time (PD) back to Standard Time (PS). At 02:00 the time becomes 01:00. In...

  5. Downhole transmission system

    DOE Patents [OSTI]

    Hall, David R. (Provo, UT); Fox, Joe (Spanish Fork, UT)

    2008-01-15T23:59:59.000Z

    A transmission system in a downhole component comprises a data transmission element in both ends of the downhole component. Each data transmission element houses an electrically conducting coil in a MCEI circular trough. An electrical conductor connects both the transmission elements. The electrical conductor comprises at least three electrically conductive elements insulated from each other. In the preferred embodiment the electrical conductor comprises an electrically conducting outer shield, an electrically conducting inner shield and an electrical conducting core. In some embodiments of the present invention, the electrical conductor comprises an electrically insulating jacket. In other embodiments, the electrical conductor comprises a pair of twisted wires. In some embodiments, the electrical conductor comprises semi-conductive material.

  6. Down hole transmission system

    DOE Patents [OSTI]

    Hall, David R. (Provo, UT); Hall, Jr., H. Tracy (Provo, UT)

    2007-07-24T23:59:59.000Z

    A transmission system in a downhole component comprises a data transmission element in both ends of the downhole component. Each data transmission element houses an electrically conducting coil in a MCEI circular trough. The electrically conducting coil comprises at least two generally fractional loops. In the preferred embodiment, the transmission elements are connected by an electrical conductor. Preferably, the electrical conductor is a coaxial cable. Preferably, the MCEI trough comprises ferrite. In the preferred embodiment, the fractional loops are connected by a connecting cable. In one aspect of the present invention, the connecting cable is a pair of twisted wires. In one embodiment the connecting cable is a shielded pair of twisted wires. In another aspect of the present invention, the connecting cable is a coaxial cable. The connecting cable may be disposed outside of the MCEI circular trough.

  7. Flexible Transmission in the Smart Grid

    E-Print Network [OSTI]

    Hedman, Kory Walter

    2010-01-01T23:59:59.000Z

    Planning . 102 vi Transmission Line Maintenance Scheduling 103 Just-in-time Transmission 103 Flexible Transmission in the Smart Grid

  8. Honda Transmission Technical Center

    High Performance Buildings Database

    Russells Point, OH The Honda Transmission Technical Center is located on the Honda of America Manufacturing Plant facility site in Russells Point, Ohio. This facility is used for product engineering and market quality testing and analysis of automatic transmissions. The building contains a large workshop area for ten cars, a future dynamometer, two laboratories, an open office area, three conference rooms, a break room, restrooms, and related support areas.

  9. Bulk Power Transmission Study

    E-Print Network [OSTI]

    John, T.

    BULK POWER TRANSMISSION STUDY TOMMY JOH~ P. E. Manager of Resource Recovery Waste Management of North America, Inc. Houston, Texas Texans now have a choice. We can become more efficient and maintain our standard of living, or we can... continue business as usual and watch our standard of living erode from competition from other regions. In the past, except for improving reliability, there was no need for a strong transmission system. When Texas generation was primarily gas fueled...

  10. Number of lightning discharges causing damage to lightning arrester cables for aerial transmission lines in power systems

    SciTech Connect (OSTI)

    Nikiforov, E. P. [Electric Power Scientific Research Institute (VNIIE), branch of OAO 'NTTs Elektroenergetika' (Russian Federation)

    2009-07-15T23:59:59.000Z

    Damage by lightning discharges to lightning arrester cables for 110-175 kV aerial transmission lines is analyzed using data from power systems on incidents with aerial transmission lines over a ten year operating period (1997-2006). It is found that failures of lightning arrester cables occur when a tensile force acts on a cable heated to the melting point by a lightning current. The lightning currents required to heat a cable to this extent are greater for larger cable cross sections. The probability that a lightning discharge will develop decreases as the amplitude of the lightning current increases, which greatly reduces the number of lightning discharges which damage TK-70 cables compared to TK-50 cables. In order to increase the reliability of lightning arrester cables for 110 kV aerial transmission lines, TK-70 cables should be used in place of TK-50 cables. The number of lightning discharges per year which damage lightning arrester cables is lowered when the density of aerial transmission lines is reduced within the territory of electrical power systems. An approximate relationship between these two parameters is obtained.

  11. Hybrid Transmission Corridor study

    SciTech Connect (OSTI)

    Clairmont, B.A.; Johnson, G.B.; Zaffanella, L.E. (General Electric Co., Lenox, MA (United States))

    1992-06-01T23:59:59.000Z

    Hybrid Transmission Corridors are areas where High Voltage Alternating Current (HVAC) transmission lines and High Voltage Direct Current (HVDC) transmission lines exist in close proximity of each other. Because of the acceptance of HVDC as a means of transporting electric power over long distances and the difficulties associated with obtaining new right-of-ways, HVDC lines may have to share the same transmission corridor with HVAC lines. The interactions between conductors energized with different types of voltages causes changes in the electrical stresses applied to the conductors and insulators. As a result, corona phenomena, field effects and insulation performance can be affected. This report presents the results of an investigation of the HVAC-HVDC interaction and its effect on corona and AC and DC electric field phenomena. The method of investigation was based on calculation methods developed at the EPRI High Voltage Transmission Research Center (HVTRC) and supported by the results of full and reduced-scale line tests. Also, a survey of existing hybrid corridors is given along with the results of measurements made at one of those corridors. A number of examples in which an existing AC corridor may be transformed into a hybrid corridor are discussed. The main result of the research is an analytical/empirical model for predicting the electrical/environmental performance of hybrid corridors, a definition of ACDC interaction and a set of criteria for specifying when the interaction becomes significant, and a set of design rules.

  12. Printed circuit dispersive transmission line

    DOE Patents [OSTI]

    Ikezi, H.; Lin-Liu, Y.R.; DeGrassie, J.S.

    1991-08-27T23:59:59.000Z

    A printed circuit dispersive transmission line structure is disclosed comprising an insulator, a ground plane formed on one surface of the insulator, a first transmission line formed on a second surface of the insulator, and a second transmission line also formed on the second surface of the insulator and of longer length than the first transmission line and periodically intersecting the first transmission line. In a preferred embodiment, the transmission line structure exhibits highly dispersive characteristics by designing the length of one of the transmission line between two adjacent periodic intersections to be longer than the other. 5 figures.

  13. Low stored energy 100 kV regulator for ion sources at LANSCE

    SciTech Connect (OSTI)

    Jacobson, E.G.; Haffner, R.L.; Ingalls, W.B.; Meyer, B.J.; Stelzer, J.E.

    1998-12-31T23:59:59.000Z

    To minimize accelerating column damage caused by uncontrolled energy release during arc-downs, it is desirable to minimize the available stored electrical energy. For the Los Alamos Neutron Science Center (LANSCE) H{sup {minus}} ion sources, the stored energy includes, in addition to the charge in the power supply output capacitance, the charge on the electronics racks. They are supported and insulated from ground by PVC pipe and have a capacitance to ground of approximately 900 pf. In 1988 (LANSCE) personnel designed a high-voltage current source using a low-stored-energy power supply and planar triode with the goal of eliminating uncontrolled release of charge stored in the power supply. Construction and testing were performed intermittently as resources permitted until 1993. When work on the Short Pulse Spallation Source (SPSS) started on the LANSCE Ion Source Test Stand (ISTS) it was recognized that a higher current power supply would be needed and work resumed on the regulator circuitry. A 120 kV power supply having low output capacitance, and a planar triode have been used to supply 40 mA, 120 Hz, 12% duty-factor current for the ISTS beam. The triode`s cathode current is controlled by circuitry operating both at power-supply voltage level and at ground level via a fiber optic link. Voltage droop is approximately 600 V during the 1 ms beam pulse. The authors present the status of the regulator and its special challenges.

  14. Performance characteristics of the Atlas 60 kV, 60 kJ plastic capacitors

    SciTech Connect (OSTI)

    Reass, W.; Bennet, G.; Bowman, D.; Lopez, E.; Monroe, M.; Parsons, W.

    1997-12-01T23:59:59.000Z

    This paper provides the performance data of Atlas plastic capacitors as supplied by Maxwell Technologies and Aerovox Corporation. The fiberglass cases at 13 inches high by 29 inches wide and 28 inches in depth with a 2 inch by 18 inch bushing on each end. Two styles of the 33.5uF capacitors have been evaluated for Atlas use, a conventional paper-foil and a self-healing metalized-paper and plastic dielectric design. A test program to capacitor failure, is being used to evaluate capacitor lifetime at full voltage (60 kV) and a nominal 15% reversal. With the Atlas parameters, peak currents of {approximately} 340 kA are realized. In anticipation of faults, capacitors are capable, specified, and tested for 700 kA performance. Accurate methods are also utilized to determine capacitor inductance, less than 20 nH. The results of the various capacitor testing programs will be presented in addition to future directives for their R and D efforts.

  15. Low Frequency Transmission Final Project Report

    E-Print Network [OSTI]

    to HVDC transmission and conventional AC transmission in different configurations. The issue is quite

  16. Development and interrupting tests on 250KV 8KA HVDC circuit breaker

    SciTech Connect (OSTI)

    Tokuyama, S.; Arimatsu, K.; Hirata, K.; Kato, Y.; Yoshioka, Y.

    1985-09-01T23:59:59.000Z

    This paper describes the circuit and component selections, development and equivalent circuit test results on an HVDC circuit breaker for an HVDC transmission line. A puffer type SF/sub 6/ gas interrupter for AC circuit breakers is utilized for interrupting DC current with injection of high-frequency inverse current from a commutating capacitor precharged to HVDC line voltage. Also, the effectiveness of application of the HVDC breaker to an HVDC system with two parallel transmission lines is demonstrated through the EMTP simulation.

  17. Development and laboratory testing of a 138-kV PPP-insulated joint for commercial application

    SciTech Connect (OSTI)

    Walldorf, S.P. (MAC Products, Inc., Kearny, NJ (US)); Chu, H.; Elbadaly, H. (Consolidated Edison Co. of New York, Inc., New York, NY (USA))

    1990-04-01T23:59:59.000Z

    This paper describes the design, development and laboratory testing of a high voltage PPP (paper polypropylene/paper laminate) insulated joint for commercial application on 138-kV PPP-insulated cable. The design approach taken is conservative and addresses the typical variations in field conditions and in skill and workmanship of the splicing. Joint construction details, including choice of connector, taping structure, and joint mechanical reinforcement, are discussed. The test criteria are described and results are presented.

  18. Development and practical operation of perfluorocarbon immersed 275kV transformers with compressed SF6 gas insulation

    SciTech Connect (OSTI)

    Hiraishi, K.; Uwano, Y.; Shirakura, K.; Gotanda, Y.; Endoo, K. [Hitachi Ltd. (Japan)] [Hitachi Ltd. (Japan); Higaki, M. [Kyushu Kyoritu Univ., Kitakyushu (Japan)] [Kyushu Kyoritu Univ., Kitakyushu (Japan); Horikoshi, M.; Mizuno, K.; Hora, H. [Chubu Electric Power Co., Inc., Nagoya (Japan)] [Chubu Electric Power Co., Inc., Nagoya (Japan)

    1995-04-01T23:59:59.000Z

    A perfluorocarbon (PFC) immersed 275kV transformer with compressed SF6 gas insulation has been under development. This paper clarified the AC partial discharge inception voltage and time characteristics of PFC immersed insulation and also clarified that a prototype 275kV 100MVA three phase transformer could be worked without any trouble during the long-term over voltage test. This prototype proved that it had the AC partial discharge inception strength of higher than 1.5 times of the AC test voltage and the lightning impulse breakdown strength of 1.5 times of the test voltage. A 275kV 250MVA three phase transformer was developed and practically operated at the outdoor substation of Chubu Electric Power Co., Inc. This transformer has been successfully operated until now and the detailed internal inspection of the transformer was carried out after one year and 9 months of the successful practical operation and no significant abnormal condition was recognized.

  19. Omega Transmission Lines

    E-Print Network [OSTI]

    Vehmas, Joni

    2013-01-01T23:59:59.000Z

    In this paper, we show how bi-anisotropic media with omega-type response can be realized using periodically loaded transmission lines. General conditions for the needed unit cell circuit block are derived. Also, an implementation is shown and analyzed.

  20. Borehole data transmission apparatus

    DOE Patents [OSTI]

    Kotlyar, O.M.

    1993-03-23T23:59:59.000Z

    A borehole data transmission apparatus is described whereby a centrifugal pump impeller(s) is used to provide a turbine stage having substantial pressure characteristics in response to changing rotational speed of a shaft for the pressure pulsing of data from the borehole through the drilling mud to the surface of the earth.

  1. Borehole data transmission apparatus

    DOE Patents [OSTI]

    Kotlyar, Oleg M. (1739 Grandview #2, Idaho Falls, ID 83402)

    1993-01-01T23:59:59.000Z

    A borehole data transmission apparatus whereby a centrifugal pump impeller(s) is used to provide a turbine stage having substantial pressure characteristics in response to changing rotational speed of a shaft for the pressure pulsing of data from the borehole through the drilling mud to the surface of the earth.

  2. Autonomous data transmission apparatus

    DOE Patents [OSTI]

    Kotlyar, Oleg M. (4675 W. 3825 S, Salt Lake City, UT 84120)

    1997-01-01T23:59:59.000Z

    A autonomous borehole data transmission apparatus for transmitting measurement data from measuring instruments at the downhole end of a drill string by generating pressure pulses utilizing a transducer longitudinally responsive to magnetic field pulses caused by electrical pulses corresponding to the measured downhole parameters.

  3. Autonomous data transmission apparatus

    DOE Patents [OSTI]

    Kotlyar, O.M.

    1997-03-25T23:59:59.000Z

    A autonomous borehole data transmission apparatus is described for transmitting measurement data from measuring instruments at the downhole end of a drill string by generating pressure pulses utilizing a transducer longitudinally responsive to magnetic field pulses caused by electrical pulses corresponding to the measured downhole parameters. 4 figs.

  4. Schultz-Hanford Area Transmission Line Project Draft Environmental Impact Statement

    SciTech Connect (OSTI)

    N /A

    2002-02-08T23:59:59.000Z

    This summary covers the major points of the Draft Environmental Impact Statement (EIS) prepared for the BPA Schultz-Hanford Transmission Project proposed by the Bonneville Power Administration (BPA). The project involves constructing a new 500-kilovolt (kV) line in central Washington, north of Hanford. The new line would connect to an existing line at the Schultz Substation near Ellensburg and to a new or existing substation in the Hanford area (see Map 2 in EIS). The project may also involve constructing a new substation to accommodate the new transmission line. As a federal agency, BPA is required by the National Environmental Policy Act (NEPA) to take into account potential environmental consequences of its proposal and take action to protect, restore, and enhance the environment during and after construction. Preparation of this EIS assists in meeting those requirements.

  5. Pulsed Power for a Dynamic Transmission Electron Microscope

    SciTech Connect (OSTI)

    dehope, w j; browning, n; campbell, g; cook, e; king, w; lagrange, t; reed, b; stuart, b; Shuttlesworth, R; Pyke, B

    2009-06-25T23:59:59.000Z

    Lawrence Livermore National Laboratory (LLNL) has converted a commercial 200kV transmission electron microscope (TEM) into an ultrafast, nanoscale diagnostic tool for material science studies. The resulting Dynamic Transmission Electron Microscope (DTEM) has provided a unique tool for the study of material phase transitions, reaction front analyses, and other studies in the fields of chemistry, materials science, and biology. The TEM's thermionic electron emission source was replaced with a fast photocathode and a laser beam path was provided for ultraviolet surface illumination. The resulting photoelectron beam gives downstream images of 2 and 20 ns exposure times at 100 and 10 nm spatial resolution. A separate laser, used as a pump pulse, is used to heat, ignite, or shock samples while the photocathode electron pulses, carefully time-synchronized with the pump, function as probe in fast transient studies. The device functions in both imaging and diffraction modes. A laser upgrade is underway to make arbitrary cathode pulse trains of variable pulse width of 10-1000 ns. Along with a fast e-beam deflection scheme, a 'movie mode' capability will be added to this unique diagnostic tool. This talk will review conventional electron microscopy and its limitations, discuss the development and capabilities of DTEM, in particularly addressing the prime and pulsed power considerations in the design and fabrication of the DTEM, and conclude with the presentation of a deflector and solid-state pulser design for Movie-Mode DTEM.

  6. Drill string transmission line

    DOE Patents [OSTI]

    Hall, David R. (Provo, UT); Hall, Jr., H. Tracy (Provo, UT); Pixton, David S. (Lehi, UT); Bradford, Kline (Orem, UT); Fox, Joe (Spanish Fork, UT)

    2006-03-28T23:59:59.000Z

    A transmission line assembly for transmitting information along a downhole tool comprising a pin end, a box end, and a central bore traveling between the pin end and the box end, is disclosed in one embodiment of the invention as including a protective conduit. A transmission line is routed through the protective conduit. The protective conduit is routed through the central bore and the ends of the protective conduit are routed through channels formed in the pin end and box end of the downhole tool. The protective conduit is elastically forced into a spiral or other non-linear path along the interior surface of the central bore by compressing the protective conduit to a length within the downhole tool shorter than the protective conduit.

  7. Transmission line: design manual

    SciTech Connect (OSTI)

    Farr, H.H.

    1980-01-01T23:59:59.000Z

    The purpose of this manual is to outline the various requirements for, and the procedures to be followed in the design of power transmission lines by the Bureau of Reclamation, US Department of the Interior. Numerous design studies, which have been made on specific aspects of transmission line design, are included with explanations of their applications. Information is presented concerning such aspects as selection of type of construction, conductor sags and tensions, insulation, lightning protection, clearance patterns, galloping conductors, structure limitation and guying charts, and structure spotting. Structure design examples are limited to wood-pole construction. Interpretations of the National Electrical Safety Code and other codes are made as required. Some of the example problems were developed when the sixth edition of NESC was current, and are so noted; however, most examples use the 1977 edition of NESC.

  8. Patterns of Transmission Investment

    E-Print Network [OSTI]

    Joskow, Paul

    2006-03-14T23:59:59.000Z

    while providing imperfect protection against abusive self-dealing behavior by the TSO. The creation of truly independent TSOs reduces the regulatory burdens and creates entities whose management focuses on the transmission business. 15... of physical components that are to be added to the network or to replace components that are already in the network. They include: a. new relays and switches b. new remote monitoring and control equipment c. transformer upgrades d. substation...

  9. EA-0587: Proposed Amendment to Presidential Permit PP-63 and Associated Modification to 500 kV International Transmission Line: Forbes, Minnesota to Manitoba, Canada

    Broader source: Energy.gov [DOE]

    This EA evaluates the environmental impacts of Northern States Power Company's  proposal to expand the Forbes Substation in Minnesota.

  10. high-resolution transmission electron microscope operating at 200 kV; and photoluminescence (PL) spectra recorded on a Renishaw 2000 with an Ar ion

    E-Print Network [OSTI]

    Zubarev, Eugene

    , 40, 1861. [11] J. Hu, L.-S. Li, W. Yang, L. Manna, L.-W. Wang, A. P. Alivisatos, Science 2001, 292. [13] V. F. Puntes, K. M. Krishnan, A. P. Alivisatos, Science 2001, 291, 2115. [14] X. Duan, Y. Huang, 1389. [19] X. Peng, L. Manna, W. Yang, J. Wickham, E. Scher, A. Kadavanich, A. P. Alivisatos, Nature

  11. Geothermal Resources and Transmission Planning

    Broader source: Energy.gov [DOE]

    This project addresses transmission-related barriers to utility-scale deployment of geothermal electric generation technologies.

  12. Boardman to Hemingway Transmission Project

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Improvement (CBPI) Customer Forum Energy Imbalance Market Generator Interconnection Reform Implementation Network Integration Transmission Service (NT Service) Network Open...

  13. Transmission Issues Policy Steering Committee

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Business Practices CommitteesTeams Joint Operating Committee Transmission Issues Policy Steering Committee Customer Training Interconnection Notices Rates Standards of...

  14. Tucson Electric Power Company Sahuarita-Nogales Transmission Line Draft Environmental Impact Statement

    SciTech Connect (OSTI)

    N /A

    2003-08-27T23:59:59.000Z

    Tucson Electric Power Company (TEP) has applied to the U.S. Department of Energy (DOE) for a Presidential Permit to construct and operate a double-circuit, 345,000-volt (345-kV) electric transmission line across the United States border with Mexico. Under Executive Order (EO) 10485 of September 3, 1953, as amended by EO 12038 of February 3, 1978, a Presidential Permit is required to construct, connect, operate, or maintain facilities at the U.S. international border for the transmission of electric energy between the United States and a foreign country. DOE has determined that the issuance of a Presidential Permit to TEP for the proposed project would constitute a major Federal action that may have a significant impact on the environment within the meaning of the ''National Environmental Policy Act of 1969'' (NEPA) 42 United States Code (U.S.C.) {section}4321 et seq. For this reason, DOE has prepared this Draft Environmental Impact Statement (EIS) to evaluate potential environmental impacts from the proposed Federal action (granting a Presidential Permit for the proposed transmission facilities) and reasonable alternatives, including the No Action Alternative. This EIS was prepared in accordance with Section 102(2)(c) of NEPA, Council of Environmental Quality (CEQ) regulations (40 Code of Federal Regulations [CFR] 1500-1508), and DOE NEPA Implementing Procedures (10 CFR 1021). DOE is the lead Federal Agency, as defined by 40 CFR 1501.5. The U.S. Department of Agriculture Forest Service (USFS), the Bureau of Land Management (BLM) of the U.S. Department of the Interior, and the U.S. Section of the International Boundary and Water Commission, U.S. and Mexico (USIBWC), are cooperating agencies. Each of these organizations will use the EIS for its own NEPA purposes, as described in the Federal Agencies' Purpose and Need and Authorizing Actions section of this summary. The 345-kV double-circuit transmission line would consist of twelve transmission line wires, or conductors, and two neutral ground wires that would provide both lightning protection and fiber optic communications, on a single set of support structures. The transmission line would originate at TEP's existing South Substation (which TEP would expand), in the vicinity of Sahuarita, Arizona, and interconnect with the Citizens Communications (Citizens) system at a Gateway Substation that TEP would construct west of Nogales, Arizona. The double-circuit transmission line would continue from the Gateway Substation south to cross the U.S.-Mexico border and extend approximately 60 miles (mi) (98 kilometers [km]) into the Sonoran region of Mexico, connecting with the Comision Federal de Electricidad (CFE, the national electric utility of Mexico) at CFE's Santa Ana Substation.

  15. Automated manual transmission clutch controller

    DOE Patents [OSTI]

    Lawrie, Robert E. (9375 Kearney Rd., Whitmore Lake, MI 48189); Reed, Jr., Richard G. (3003 Bembridge, Royal Oak, MI 48073); Rausen, David J. (519 S. Gaylord St., Denver, CO 80209)

    1999-11-30T23:59:59.000Z

    A powertrain system for a hybrid vehicle. The hybrid vehicle includes a heat engine, such as a diesel engine, and an electric machine, which operates as both an electric motor and an alternator, to power the vehicle. The hybrid vehicle also includes a manual-style transmission configured to operate as an automatic transmission from the perspective of the driver. The engine and the electric machine drive an input shaft which in turn drives an output shaft of the transmission. In addition to driving the transmission, the electric machine regulates the speed of the input shaft in order to synchronize the input shaft during either an upshift or downshift of the transmission by either decreasing or increasing the speed of the input shaft. When decreasing the speed of the input shaft, the electric motor functions as an alternator to produce electrical energy which may be stored by a storage device. Operation of the transmission is controlled by a transmission controller which receives input signals and generates output signals to control shift and clutch motors to effect smooth launch, upshift shifts, and downshifts of the transmission, so that the transmission functions substantially as an automatic transmission from the perspective of the driver, while internally substantially functioning as a manual transmission.

  16. Transmission - Contact Information

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office of ScienceandMesa del SolStrengthening a solidSynthesisAppliances » DataContact-Information-Transmission

  17. Transmission | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand Jump to:Ezfeedflag JumpID-f <MaintainedInformationThePtyTownTrama TecnoTransmission

  18. Transmission | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov YouKizildere IRaghuraji Agro IndustriesTown of Ladoga, Indiana (Utility Company) JumpTradeWindPrepared asTransmission

  19. Space charge measurements downwind from a monopolar 500 KV HVDC test line

    SciTech Connect (OSTI)

    Carter, P.J.; Johnson, G.B. (General Electric Co., EPRI-High Voltage Transmission, Research Center, Lenox, MA (US))

    1988-10-01T23:59:59.000Z

    One quantity that helps describe the electrical environment in the vicinity of a HVDC line is space charge, a quantity that consists of charged air ions and charged aerosols. This paper describes measurements made at the Electric Power Research Institute's High Voltage Transmission Research Center (HVTRC) in Lenox, MA to determine the concentration of space charge present downwind of a HVDC test line and the influence of wind on the space charge level. The instrumentation used to make the measurements of space charge downwind of the line is also described.

  20. Colorado Electrical Transmission Grid

    SciTech Connect (OSTI)

    Zehner, Richard E.

    2012-02-01T23:59:59.000Z

    Citation Information: Originator: Earth Science &Observation Center (ESOC), CIRES, University of Colorado at Boulder Originator: Xcel Energy Publication Date: 2012 Title: Colorado XcelEnergy NonXcel Transmission Network Edition: First Publication Information: Publication Place: Earth Science & Observation Center, Cooperative Institute for Research in Environmental Science (CIRES), University of Colorado, Boulder Publisher: Earth Science &Observation Center (ESOC), CIRES, University of Colorado at Boulder Description: This layer contains transmission network of Colorado Spatial Domain: Extent: Top: 4540689.017558 m Left: 160606.141934 m Right: 758715.946645 m Bottom: 4098910.893397m Contact Information: Contact Organization: Earth Science &Observation Center (ESOC), CIRES, University of Colorado at Boulder Contact Person: Khalid Hussein Address: CIRES, Ekeley Building Earth Science & Observation Center (ESOC) 216 UCB City: Boulder State: CO Postal Code: 80309-0216 Country: USA Contact Telephone: 303-492-6782 Spatial Reference Information: Coordinate System: Universal Transverse Mercator (UTM) WGS’1984 Zone 13N False Easting: 500000.00000000 False Northing: 0.00000000 Central Meridian: -105.00000000 Scale Factor: 0.99960000 Latitude of Origin: 0.00000000 Linear Unit: Meter Datum: World Geodetic System ’1984 (WGS ’1984) Prime Meridian: Greenwich Angular Unit: Degree Digital Form: Format Name: Shapefile

  1. Manual transmission shift linkage

    SciTech Connect (OSTI)

    Sewell, J.S.

    1991-10-01T23:59:59.000Z

    This patent describes a sliding gear manual transmission (10) for an automotive vehicle including a transmission housing (11), an input shaft (12) journalled in the housing, an output shaft (13) axially aligned with the input shaft and journalled in the housing, a countershaft (15) journalled in the housing and carrying a cluster gear (17) thereon, the input shaft (12) terminating in an input gear (14), a plurality of gears (26,27,28,29,31,31) on the output shaft (13) in meshing engagement with the cluster gear (17), and a plurality of synchronizing clutches (36,38,41,42) on the output shaft and countershaft for engagement of gear ratios of the meshing gears, and an axially movable and rotatable shift rail (81) located in the housing and operatively connected to a shift lever (82) actuated by the vehicle operator, the improvement comprising an auxiliary shift rail (98) located in the housing (11) generally paralleling the first mentioned shift rail (81) to provide for actuation of fifth, sixth and reverse gears the auxiliary shift rail (98) having a 5-6 shift arm (104) journalled thereon for axial movement relative thereto, and a reverse shift arm (99) rotatably mounted thereon for axial movement therewith.

  2. BPA/Puget Power Northwest Washington Transmission Project Final Environmental Impact Statement.

    SciTech Connect (OSTI)

    United States. Bonneville Power Administration.

    1995-08-01T23:59:59.000Z

    Bonneville Power Administration (BPA) and Puget Sound Power & Light Company (Puget Power) propose to upgrade the existing high-voltage transmission system in the Whatcom and Skagit counties area between the towns of Custer and Sedro Woolley, including some areas within the City of Bellingham, starting in 1995. A Draft Environmental Impact Statement (DEIS) for the project was issued in November 1993, followed by a 45-day public comment period. Public response to the DEIS included the identification of several new transmission route alternatives in the Lake Whatcom area. BPA issued a Supplemental DEIS in April 1995 to provide a second public review-and-comment period. Rebuilding an existing 230-kV line to a double-circuit 230-kV transmission line was identified in the Supplemental DEIS as the Proposed Action. The Supplemental DEIS also examined in detail a North Shore Road alternative which was proposed by some members of the public. Public comments on the EIS were listed and responded to in the Supplemental DEIS. In May 1995, a second set of open houses and public meetings was held to review the Supplemental DEIS. Electromagnetic field (EMF) effects raised as an issue in the DEIS continued to be an issue of public concern in the meetings. The EIS has identified impacts that would generally be classified as low to moderate and localized. Effects on soils and water resources in sensitive areas (e.g., near Lake Whatcom) would be low to moderate; there would be little change in magnetic fields; noise levels would remain at existing levels; and land use and property value impacts would be minimal. Threatened and endangered species would not be adversely affected, and all proposed actions in wetlands would be covered by a Corps of Engineers Nationwide Permit. Visual and socioeconomic would be low to moderate. There would be no effect on cultural resources.

  3. Factors influencing quantitative liquid (scanning) transmission...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Factors influencing quantitative liquid (scanning) transmission electron microscopy. Factors influencing quantitative liquid (scanning) transmission electron microscopy. Abstract:...

  4. OPERATIONAL RESULTS OF THE SPALLATION NEUTRON SOURCE (SNS) POLYPHASE CONVERTER-MODULATOR FOR THE 140 KV KLYSTRON RF SYSTEMS

    SciTech Connect (OSTI)

    W.A. REASS; J.D. DOSS; ET AL

    2001-06-01T23:59:59.000Z

    This paper describes the first operational results of the 140 kV, 1 MW average, 11 MW peak, zero-voltage-switching, 20 kHz polyphase bridge, boost converter-modulator for klystron pulse application. The DC-DC converter derives the buss voltages from a standard 13.8 kV to 2100 Y substation cast-core transformer. Energy storage and filtering is provided by self-clearing metallized hazy polypropylene traction capacitors. Three ''H-Bridge'' Insulated Gate Bipolar Transistor (IGBT) switching networks are used to generate the polyphase 20 kHz transformer primary drive waveforms. The 20 kHz drive waveforms are chirped the appropriate duration to generate the desired klystron pulse width. Pulse-Width Modulation (PWM) of the individual 20 kHz pulses is utilized to provide regulated output waveforms with adaptive feedforward and feedback techniques. The boost transformer design utilizes amorphous nanocrystalline material that provides the required low core loss at design flux levels and switching frequencies. Resonant shunt peaking is used on the transformer secondary to boost output voltage and resonate transformer leakage inductance. With the appropriate transformer leakage inductance and peaking capacitance, zero-voltage-switching of the IGBT's is attained, minimizing switching losses. Reviews of these design parameters and an examination of the first operational results will be performed.

  5. Operational results of the spallation neutron source (SNS) polyphase converter-modulator for the 140 KV klystron RF system

    SciTech Connect (OSTI)

    Reass, W. A. (William A.); Doss, James D.; Gribble, R. F. (Robert F.); Lynch, M. T. (Michael T.); Rees, D. E. (Daniel E.); Tallerico, P. J. (Paul J.); Borovina, D. L.

    2001-01-01T23:59:59.000Z

    This paper describes the first operational results of the 140 kV, 1 MW average, 11 MW peak, zero-voltageswitching, 20 kHz polyphase bridge, boost converter-modulator for klystron pulse application. The DC-DC converter derives the buss voltages from a standard 13.8 kV to 2100 Y substation cast-core transformer. Energy storage and filtering is provided by self-clearing metallized hazy polypropylene traction capacitors. Three 'H-Bridge' Insulated Gate Bipolar Transistor (IGBT) switching networks are used to generate the polyphase 20 kHz transformer primary drive waveforms. The 20 kHz drive waveforms are chirped the appropriate duration to generate the desired klystron pulse width. Pulse-Width Modulation (PWM) of the individual 20 kHz pulses is utilized to provide regulated output waveforms with adaptive feedforward and feedback techniques. The boost transformer design utilizes amorphous nanocrystalline material that provides the required low core loss at design flux levels and switching frequencies. Resonant shunt peaking is used on the transformer secondary to boost output voltage and resonate transformer leakage inductance. With the appropriate transformer leakage inductance and peaking capacitance, zero-voltage-switching of the IGBT's is attained, minimizing switching losses. Reviews of these design parameters and an examination of the first operational results will be performed.

  6. EIS-0470: U.S. Department of Energy Loan Guarantee for the Cape Wind Energy Project on the Outer Continental Shelf off Massachusetts, Nantucket Sound

    Broader source: Energy.gov [DOE]

    The DOE Loan Programs Office is proposing to offer a loan guarantee to Cape Wind Associates, LLC for the construction and start-up of the Cape Wind Energy Project in Nantucket Sound, offshore of Massachusetts. The proposed Cape Wind Energy Project would consist of up to 130, 3.6-MW turbine generators, in an area of roughly 25-square miles, and would include 12.5 miles of 115-kilovolt submarine transmission cable and an electric service platform. To inform DOE's decision regarding a loan guarantee, DOE adopted the Department of the Interior’s 2009 Final Cape Wind Energy Project EIS, in combination with two Cape Wind Environmental Assessments dated May 2010 and April 2011 (per 40 CFR 1506.4), as a DOE Final EIS (DOE/EIS-0470). The adequacy of the Department of the Interior final EIS adopted by DOE is the subject of a judicial action. This project is inactive.

  7. Transmission Planning | Department of Energy

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Improving Performance of Federal Permitting and Review of Infrastructure Projects Energy Corridors on Federal Lands Transmission Projects Proposed Under EPAct Section 1222 Activity...

  8. AGENDA: PETROLEUM PRODUCT TRANSMISSION & DISTRIBUTION

    Broader source: Energy.gov [DOE]

    The agenda for the Quadrennial Energy Review (QER) public stakeholder meeting in New Orleans on petroleum product transmission, distribution, and storage.

  9. Raj JainThe Ohio State University Data TransmissionData TransmissionData Transmission

    E-Print Network [OSTI]

    Jain, Raj

    The Ohio State University 2-14 Bit Error RateBit Error RateBit Error Rate Energy/bit Eb =STb, where TbRaj JainThe Ohio State University 2-1 Data TransmissionData TransmissionData Transmission Raj Jain Professor of CIS The Ohio State University Columbus, OH 43210 Jain@ACM.Org http://www.cis.ohio

  10. HVDC power transmission technology assessment

    SciTech Connect (OSTI)

    Hauth, R.L.; Tatro, P.J.; Railing, B.D. [New England Power Service Co., Westborough, MA (United States); Johnson, B.K.; Stewart, J.R. [Power Technologies, Inc., Schenectady, NY (United States); Fink, J.L.

    1997-04-01T23:59:59.000Z

    The purpose of this study was to develop an assessment of the national utility system`s needs for electric transmission during the period 1995-2020 that could be met by future reduced-cost HVDC systems. The assessment was to include an economic evaluation of HVDC as a means for meeting those needs as well as a comparison with competing technologies such as ac transmission with and without Flexible AC Transmission System (FACTS) controllers. The role of force commutated dc converters was to be assumed where appropriate. The assessment begins by identifying the general needs for transmission in the U.S. in the context of a future deregulated power industry. The possible roles for direct current transmission are then postulated in terms of representative scenarios. A few of the scenarios are illustrated with the help of actual U.S. system examples. non-traditional applications as well as traditional applications such as long lines and asynchronous interconnections are discussed. The classical ``break-even distance`` concept for comparing HVDC and ac lines is used to assess the selected scenarios. The impact of reduced-cost converters is reflected in terms of the break-even distance. This report presents a comprehensive review of the functional benefits of HVDC transmission and updated cost data for both ac and dc system components. It also provides some provocative thoughts on how direct current transmission might be applied to better utilize and expand our nation`s increasingly stressed transmission assets.

  11. Direct current power transmission systems

    SciTech Connect (OSTI)

    Padiyar, K.R.

    1991-01-01T23:59:59.000Z

    This book represents text on HVDC transmission available. It deals with the various aspects of the state of the art in HVDC transmission technology. This book presents many aspects of interactions of AC/DC systems. Modeling and analysis of DC systems are also discussed in detail.

  12. The Cost of Transmission for Wind Energy: A Review of Transmission Planning Studies

    E-Print Network [OSTI]

    Mills, Andrew D.

    2009-01-01T23:59:59.000Z

    Wind Energy Access, Transmission, and Intermittency Really Cost?transmission cost barrier for wind energy. A secondary goalfocus on the cost of transmission for wind energy does not

  13. EC Transmission Line Materials

    SciTech Connect (OSTI)

    Bigelow, Tim S [ORNL

    2012-05-01T23:59:59.000Z

    The purpose of this document is to identify materials acceptable for use in the US ITER Project Office (USIPO)-supplied components for the ITER Electron cyclotron Heating and Current Drive (ECH&CD) transmission lines (TL), PBS-52. The source of material property information for design analysis shall be either the applicable structural code or the ITER Material Properties Handbook. In the case of conflict, the ITER Material Properties Handbook shall take precedence. Materials selection, and use, shall follow the guidelines established in the Materials Assessment Report (MAR). Materials exposed to vacuum shall conform to the ITER Vacuum Handbook. [Ref. 2] Commercial materials shall conform to the applicable standard (e.g., ASTM, JIS, DIN) for the definition of their grade, physical, chemical and electrical properties and related testing. All materials for which a suitable certification from the supplier is not available shall be tested to determine the relevant properties, as part of the procurement. A complete traceability of all the materials including welding materials shall be provided. Halogenated materials (example: insulating materials) shall be forbidden in areas served by the detritiation systems. Exceptions must be approved by the Tritium System and Safety Section Responsible Officers.

  14. Key-shift transmission

    SciTech Connect (OSTI)

    Nemoto, S.

    1989-03-07T23:59:59.000Z

    A key-shift transmission is described, characterized by the speed-change shaft being divided into a pair of trough-shaped shaft halves each having an arched inner surface which defines a part of a cylindrical bore extending axially through the speed-change shaft thereby the shaft being formed into a hollow shaft, and by each of the shaft halves including a pair of flattened end surfaces which extend axially of each shaft half at both sides of the inner surface, one of the end surfaces having thereon an axially elongated projection and the other of the end surfaces having herein an axially elongated recess of a depth smaller than the height of the projection. The pair of shaft halves are engaged to each other co-rotatably by fitting the projections of the respective shaft halves into the recesses of the respective shaft halves so as to form in an outer surface of the speed-change shaft a pair of elongated axial grooves which are located radially outwardly of the elongated projections of the respective shaft halves and between the flattened end surfaces of the respective shaft halves. A pair of the shift keys are disposed within the pair of elongated axial grooves.

  15. Regional Transmission Projects: Finding Solutions

    SciTech Connect (OSTI)

    The Keystone Center

    2005-06-15T23:59:59.000Z

    The Keystone Center convened and facilitated a year-long Dialogue on "Regional Transmission Projects: Finding Solutions" to develop recommendations that will help address the difficult and contentious issues related to expansions of regional electric transmission systems that are needed for reliable and economic transmission of power within and across regions. This effort brought together a cross-section of affected stakeholders and thought leaders to address the problem with the collective wisdom of their experience and interests. Transmission owners sat at the table with consumer advocates and environmental organizations. Representatives from regional transmission organizations exchanged ideas with state and federal regulators. Generation developers explored common interests with public power suppliers. Together, the Dialogue participants developed consensus solutions about how to begin unraveling some of the more intractable issues surrounding identification of need, allocation of costs, and reaching consensus on siting issues that can frustrate the development of regional transmission infrastructure. The recommendations fall into three broad categories: 1. Recommendations on appropriate institutional arrangements and processes for achieving regional consensus on the need for new or expanded transmission infrastructure 2. Recommendations on the process for siting of transmission lines 3. Recommendations on the tools needed to support regional planning, cost allocation, and siting efforts. List of Dialogue participants: List of Dialogue Participants: American Electric Power American Transmission Company American Wind Energy Association California ISO Calpine Corporation Cinergy Edison Electric Institute Environmental Defense Federal Energy Regulatory Commission Great River Energy International Transmission Company ISO-New England Iowa Public Utility Board Kanner & Associates Midwest ISO National Association of Regulatory Utility Commissioners National Association of State Utility Consumer Advocates National Grid Northeast Utilities PA Office of Consumer Advocates Pacific Gas & Electric Corporation Pennsylvania Public Utility Commission PJM Interconnection The Electricity Consumers Resource Council U.S. Department of Energy US Department of the Interior Van Ness Feldman Western Interstate Energy Board Wind on the Wires Wisconsin Public Service Commission Xcel Energy

  16. Development of 500-kV AC cable employing laminar insulation of other than conventional cellulosic paper. Final report

    SciTech Connect (OSTI)

    Bahder, G.; Eager, G.S. Jr.; Walker, J.J.; Dima, A.F.

    1980-09-01T23:59:59.000Z

    The results of an investigation to develop a 500 kV ac laminar dielectric power cable and joint having insulation with lower losses than conventional cellulosic paper insulation are presented. Background information is presented on proposed low-loss synthetic and composite synthetic/cellulosic paper insulations. From these studies, fibrous polypropylene paper tape and cellulosic paper-polypropylene film-cellulosic paper composite paper (PPP) were chosen. Extensive testing of hand-wrapped cable models fabricated with each type of tape served to eliminate the fibrous polypropylene paper tape from further consideration. Cable model tests indicate that the PPP tape is satisfactory for insulation in 500 kV ac cable, and that oil impregnants now used in conventional cellulosic paper insulated cables are unsuitable, but that silicone oil with an additive is satisfactory for PPP tapes. Laboratory data indicate that it may be necessary with the PPP tapes to use a significantly lower viscosity impregnating oil which has a greater tendency to drain from pipe-type cables than conventional oil. This may require a modification of the moisture seal. Four final pipe-type cables having a conventional moisture seal were manufactured for possible future field testing. The dielectric loss of the final cables is one-fifth that of conventional cellulosic paper insulated cables. The estimated installed cost per MVA-mile of the PPP insulated cable, neglecting losses, is higher than cellulosic insulated cables impregnated with conventional mineral oil. However, the capacitance of the cable insulated with PPP tape is 25% lower than conventional cable, and therefore, the reactance necessary to compensate for the cable charging current is significantly reduced.

  17. NWCC Transmission Case Study III

    SciTech Connect (OSTI)

    Terry Allison, Steve Wiese

    2000-03-01T23:59:59.000Z

    OAK-B135 Transmission System Improvements for Wind Energy Development in the Upper Midwest and Great Plains: Opportunities and Obstacles. This case study set out to ascertain the validity of three assumptions from the perspectives of stakeholders involved in wind energy and transmission issues in the Upper Midwest and Great Plains. The assumptions, and the stakeholders' reactions to each, are summarized below: Assumption 1--Transmission system improvements would provide significant benefits to the electricity network and its customers. Respondents acknowledge the potential for overall system benefits in the form of reduced line losses, improved grid stability and reliability, and enhanced ability to conduct spot market transactions. They also agree that these benefits relate to specific regional needs. However, there is disagreement over the extent of other benefits such as efficiency gains and cost savings from reduced line losses. Further, environmental and community interest groups point out that none of these benefits are realized without significant financial, environmental and social costs. Assumption 2--The benefits of transmission improvements would be helpful, but not confined, to wind power. All respondents agree that wind energy could benefit from transmission system improvements. But they also acknowledge, reluctantly, in the case of environmental stakeholders, that the benefits of an improved transmission system cannot be limited to environmentally preferable forms of generation. Some environmental and community advocate respondents also feel that transmission system improvement projects can be avoided altogether through energy conservation and efficiency measures, and by substituting wind energy for fossil generation. Assumption 3--Transmission alliances among stakeholders within and external to the wind community can provide benefits in the public interest. The fractured, multi-jurisdictional governance of the regional transmission system, and the distrust and diversity of perspectives among affected stakeholders, may make the formation of multi-stakeholder alliances necessary to accomplishing transmission goals. If the wind industry and utilities want to partner with environmental and community advocate groups in supporting a transmission project, they may have to convince these groups that the project would result in a net environmental benefit. The project proponents would have to make the case that the benefits of the additional wind energy will at least offset the emissions of any additional fossil generation made possible by the transmission project, as well as offset the environmental impact of the transmission project itself.

  18. Energy Transmission and Infrastructure

    SciTech Connect (OSTI)

    Mathison, Jane

    2012-12-31T23:59:59.000Z

    The objective of Energy Transmission and Infrastructure Northern Ohio (OH) was to lay the conceptual and analytical foundation for an energy economy in northern Ohio that will: • improve the efficiency with which energy is used in the residential, commercial, industrial, agricultural, and transportation sectors for Oberlin, Ohio as a district-wide model for Congressional District OH-09; • identify the potential to deploy wind and solar technologies and the most effective configuration for the regional energy system (i.e., the ratio of distributed or centralized power generation); • analyze the potential within the district to utilize farm wastes to produce biofuels; • enhance long-term energy security by identifying ways to deploy local resources and building Ohio-based enterprises; • identify the policy, regulatory, and financial barriers impeding development of a new energy system; and • improve energy infrastructure within Congressional District OH-09. This objective of laying the foundation for a renewable energy system in Ohio was achieved through four primary areas of activity: 1. district-wide energy infrastructure assessments and alternative-energy transmission studies; 2. energy infrastructure improvement projects undertaken by American Municipal Power (AMP) affiliates in the northern Ohio communities of Elmore, Oak Harbor, and Wellington; 3. Oberlin, OH-area energy assessment initiatives; and 4. a district-wide conference held in September 2011 to disseminate year-one findings. The grant supported 17 research studies by leading energy, policy, and financial specialists, including studies on: current energy use in the district and the Oberlin area; regional potential for energy generation from renewable sources such as solar power, wind, and farm-waste; energy and transportation strategies for transitioning the City of Oberlin entirely to renewable resources and considering pedestrians, bicyclists, and public transportation as well as drivers in developing transportation policies; energy audits and efficiency studies for Oberlin-area businesses and Oberlin College; identification of barriers to residential energy efficiency and development of programming to remove these barriers; mapping of the solar-photovoltaic and wind-energy supply chains in northwest Ohio; and opportunities for vehicle sharing and collaboration among the ten organizations in Lorain County from the private, government, non-profit, and educational sectors. With non-grant funds, organizations have begun or completed projects that drew on the findings of the studies, including: creation of a residential energy-efficiency program for the Oberlin community; installation of energy-efficient lighting in Oberlin College facilities; and development by the City of Oberlin and Oberlin College of a 2.27 megawatt solar photovoltaic facility that is expected to produce 3,000 megawatt-hours of renewable energy annually, 12% of the College’s yearly power needs. Implementation of these and other projects is evidence of the economic feasibility and technical effectiveness of grant-supported studies, and additional projects are expected to advance to implementation in the coming years. The public has benefited through improved energydelivery systems and reduced energy use for street lighting in Elmore, Oak Harbor, and Wellington; new opportunities for assistance and incentives for residential energy efficiency in the Oberlin community; new opportunities for financial and energy savings through vehicle collaboration within Lorain County; and decreased reliance on fossil fuels and expanded production of renewable energy in the region. The dissemination conference and the summary report developed for the conference also benefited the public, but making the findings and recommendations of the regional studies broadly available to elected officials, city managers, educators, representatives of the private sector, and the general public.

  19. Multi-ratio transmission

    SciTech Connect (OSTI)

    Polak, J.C.

    1987-07-14T23:59:59.000Z

    A preselected multi-ratio power transmission is described comprising: input means for transmitting drive forces; output means; first, second and third friction clutch means each selectively engageable with the input means for accepting drive forces. First input gear means drivingly connects with the first friction clutch means; second input gear means drivingly connects with the second friction clutch means; third input gear means drivingly connects with the third clutch means; first output gear means drivingly connects with the first input gear means; second output gear means drivingly connects with the first and second input gear means; third output means drivingly connects between the third input gear means and the output means; and one double-acting synchronizer clutch for selectively engaging the first output gear means with the output means and alternately the second output gear means with the output means. The first friction clutch means and the one double-acting synchronizer clutch cooperates during engagement to establish two forward drive ratios between the input and output means. The second friction clutch means and the one double-acting synchronizer clutch cooperates during engagement to establish two other forward drive ratios between the input and output means. The third friction clutch means is engageable to provide another forward drive ratio between the input means and the output means; and the one double-acting synchronizer clutch is relieved of transmitting drive forces during the engagement of the third friction clutch means and being manipulable for alternate connection with either the first output gear or the second output gear while the third friction clutch means is engaged.

  20. Electrical transmission line diametrical retainer

    DOE Patents [OSTI]

    Hall, David R. (Provo, UT); Hall, Jr., H. Tracy (Provo, UT); Pixton, David (Lehi, UT); Dahlgren, Scott (Provo, UT); Sneddon, Cameron (Provo, UT); Briscoe, Michael (Lehi, UT); Fox, Joe (Spanish Fork, UT)

    2004-12-14T23:59:59.000Z

    The invention is a mechanism for retaining an electrical transmission line. In one embodiment of the invention it is a system for retaining an electrical transmission line within down hole components. In accordance with one aspect of the invention, the system includes a plurality of downhole components, such as sections of pipe in a drill string. The system also includes a coaxial cable running between the first and second end of a drill pipe, the coaxial cable having a conductive tube and a conductive core within it. The invention allows the electrical transmission line to with stand the tension and compression of drill pipe during routine drilling cycles.

  1. Midwest Transmission Workshop I Summary

    SciTech Connect (OSTI)

    Kevin Bryan

    2001-05-01T23:59:59.000Z

    OAK-B135 The meeting was opened with a review of the purposes of the workshop: (1) Present and discuss key studies and assessments of transmission upgrades, additions and related issues for the upper Midwest, including work that addresses the full range of views on these topics; (2) Understand the various transmission issues in the upper Midwest and discuss options for addressing the issues; and (3) Identify the decision makers and entities that need to play an active role if transmission issues are to be resolved, and agree on next steps for engaging these individuals and organizations through education, outreach, and information dissemination.

  2. AC and DC power transmission

    SciTech Connect (OSTI)

    Not Available

    1985-01-01T23:59:59.000Z

    The technical and economic assessment of AC and DC transmission systems; long distance transmission, cable transmission, system inter-connection, voltage support, reactive compensation, stabilisation of systems; parallel operation of DC links with AC systems; comparison between alternatives for particular schemes. Design and application equipment: design, testing and application of equipment for HVDC, series and shunt static compensated AC schemes, including associated controls. Installations: overall design of stations and conductor arrangements for HVDC, series and shunt static AC schemes including insulation co-ordination. System analysis and modelling.

  3. Final environmental impact statement, Washington Water Power/B.C. Hydro Transmission Interconnection Project

    SciTech Connect (OSTI)

    Not Available

    1992-10-01T23:59:59.000Z

    Washington Water Power (WWP) proposes to construct and operate an electric transmission line that would connect with the electrical system of the British Columbia Hydro and Power Authority (B.C. Hydro). The project would be composed of a double-circuit, 230-kilovolt (kV) transmission line from WWP`s existing Beacon Substation located northeast of Spokane, Washington to the international border located northwest of Metaline Falls, Washington. The original Presidential permit application and associated proposed route presented in the draft environmental impact statement (DEIS) have been modified to terminate at the Beacon Substation, instead of WWP`s initially proposed termination point at the planned Marshall Substation located southwest of Spokane. A supplemental draft EIS was prepared and submitted for review to not only examine the new proposed 5.6 miles of route, but to also compare the new Proposed Route to the other alternatives previously analyzed in the DEIS. This final EIS (FEIS) assesses the environmental effects of the proposed transmission line through construction, operation, maintenance, and abandonment activities and addresses the impacts associated with the Proposed Action, Eastern Alternative, Western Alternative, Northern Crossover Alternative, Southern Crossover Alternative, and No Action Alternative. The FEIS also contains the comments received and the responses to these comments submitted on the DEIS and Supplemental DEIS.

  4. Flexible Transmission in the Smart Grid

    E-Print Network [OSTI]

    Hedman, Kory Walter

    2010-01-01T23:59:59.000Z

    S. S. Oren, “Smart flexible just-in-time transmission andFlexible Transmission in the Smart Grid By Kory WalterAll rights reserved. A BSTRACT Flexible Transmission in the

  5. Transmission Workshop | Department of Energy

    Energy Savers [EERE]

    - November 1-2, 2012 On November 1-2, 2012, the GTT presented a workshop on grid integration on the transmission system at the DoubleTree Crystal City near Washington, DC. A...

  6. Video transmission over wireless networks 

    E-Print Network [OSTI]

    Zhao, Shengjie

    2005-08-29T23:59:59.000Z

    Compressed video bitstream transmissions over wireless networks are addressed in this work. We first consider error control and power allocation for transmitting wireless video over CDMA networks in conjunction with multiuser detection. We map a...

  7. Video transmission over wireless networks

    E-Print Network [OSTI]

    Zhao, Shengjie

    2005-08-29T23:59:59.000Z

    Compressed video bitstream transmissions over wireless networks are addressed in this work. We first consider error control and power allocation for transmitting wireless video over CDMA networks in conjunction with multiuser detection. We map a...

  8. Immunology of naturally transmissible tumours

    E-Print Network [OSTI]

    Siddle, Hannah V.; Kaufman, Jim

    2014-09-04T23:59:59.000Z

    in a graft. These APCs move to the draining lymph nodes of the host, after which primed effector T cells migrate back to the graft site and target foreign cells (reviewed in (10)). Alternatively, T cells can be primed with graft-derived peptides... transmissible venereal tumour at different stages of growth. Vet Immunol Immunopathol. 1998;64(2):133-47. 57. Chandler JP, Yang TJ. Canine transmissible venereal sarcoma: distribution of T and B lymphocytes in blood, draining lymph nodes and tumours...

  9. Transmission Workshop | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels DataDepartment of Energy Your Density Isn'tOriginEducationVideoStrategic|IndustrialCenter Gets PeopleTransmission Workshop Transmission

  10. Briefing Memo: Petroleum Product Transmission & Distribution...

    Energy Savers [EERE]

    Briefing Memo: Petroleum Product Transmission & Distribution Briefing Memo: Petroleum Product Transmission & Distribution Click below to download a PDF of the briefing memo....

  11. Agenda: Natural Gas: Transmission, Storage and Distribution ...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Natural Gas: Transmission, Storage and Distribution Agenda: Natural Gas: Transmission, Storage and Distribution A Public Meeting on the Quadrennial Energy Review, Hosted by the...

  12. July 2, 2007 1 Optimal Transmission Switching

    E-Print Network [OSTI]

    Mangasarian, Olvi L.

    d to node n. zk: binary variable indicating whether transmission line k is removed from the system limit on number of open transmission lines Manuscript received July 2, 2007. This work was supported-mail: ferris@cs.wisc.edu). Sets : Set of all transmission lines L: Set of open transmission lines in solution

  13. Development of a 33 kV, 20 A long pulse converter modulator for high average power klystron

    SciTech Connect (OSTI)

    Reghu, T.; Mandloi, V.; Shrivastava, Purushottam [Pulsed High Power Microwave Section, Raja Ramanna Centre for Advanced Technology, Indore 452013, M.P. (India)] [Pulsed High Power Microwave Section, Raja Ramanna Centre for Advanced Technology, Indore 452013, M.P. (India)

    2014-05-15T23:59:59.000Z

    Research, design, and development of high average power, long pulse modulators for the proposed Indian Spallation Neutron Source are underway at Raja Ramanna Centre for Advanced Technology. With this objective, a prototype of long pulse modulator capable of delivering 33 kV, 20 A at 5 Hz repetition rate has been designed and developed. Three Insulated Gate Bipolar Transistors (IGBT) based switching modules driving high frequency, high voltage transformers have been used to generate high voltage output. The IGBT based switching modules are shifted in phase by 120° with respect to each other. The switching frequency is 25 kHz. Pulses of 1.6 ms pulse width, 80 ?s rise time, and 70 ?s fall time have been achieved at the modulator output. A droop of ±0.6% is achieved using a simple segmented digital droop correction technique. The total fault energy transferred to the load during fault has been measured by conducting wire burn tests and is found to be within 3.5 J.

  14. Transmission Lines Emulating Moving Media

    E-Print Network [OSTI]

    Vehmas, Joni; Tretyakov, Sergei

    2014-01-01T23:59:59.000Z

    In this paper, we show how the electromagnetic phenomena in moving magnetodielectric media can be emulated using artificial composite structures at rest. In particular, we introduce nonreciprocal periodically loaded transmission lines which support waves obeying the same rules as plane electromagnetic waves in moving media. Because the actual physical structure is at rest, in these transmission lines there are no fundamental limitations on the velocity values, which may take values larger than the speed of light or even complex values (considering complex amplitudes in the time-harmonic regime). An example circuit of a unit cell of a "moving" transmission line is presented and analyzed both numerically and experimentally. The special case of composite right/left handed host line is also studied numerically. Besides the fundamental interest, the study is relevant for potential applications in realizing engineered materials for various transformations of electromagnetic fields.

  15. Midwest Transmission Workshop III Summary

    SciTech Connect (OSTI)

    Kevin Bryan

    2003-03-12T23:59:59.000Z

    OAK-B135 On March 12-13, 2002, the National Wind Coordinating Committee (NWCC), in cooperation with regional stakeholders, held a two-day workshop: Planning for Electrical Transmission Needs in the Upper Midwest. The workshop was the outgrowth of an effort to develop a forum and process for consideration of transmission options that strives for equitable allocation of benefits and impacts among all affected parties. The goal of this workshop was to provide a catalyst for an enhanced, inclusive process for transmission planning with participation of and acceptance by all affected stakeholders. Participants in the meeting included representatives of state and regional regulatory agencies, utilities and power generators, the wind industry, environmental and landowner interests, and other interested parties (see Attachment A for a list of meeting participants).

  16. ITC Transmission | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are8COaBulkTransmissionSitingProcess.pdfGetecGtel JumpCounty, Texas:ITC Transmission Jump to: navigation, search Name:

  17. The Centre for Power Transmission

    E-Print Network [OSTI]

    Burton, Geoffrey R.

    The Centre for Power Transmission and Motion Control Centre for PTMC Department of Mechanical) 1225 38-6371 Email: ptmc@bath.ac.uk Web: http://www.bath.ac.uk/ptmc/ Consultancy Project WAVE POWER SYSTEM SIMULATIONS Power take-off systems Wave power take-off systems are an exciting new development

  18. The Centre for Power Transmission

    E-Print Network [OSTI]

    Burton, Geoffrey R.

    precision and high bandwidth motion control In fluid power systems, seals are typically passive elements Bois) PTO #12;5. Modelling and Development of Low Noise Hydraulic Fluid Power Systems Hydraulic fluidThe Centre for Power Transmission and Motion Control The Centre for PTMC: analytical

  19. Power superconducting power transmission cable

    DOE Patents [OSTI]

    Ashworth, Stephen P. (Cambridge, GB)

    2003-01-01T23:59:59.000Z

    The present invention is for a compact superconducting power transmission cable operating at distribution level voltages. The superconducting cable is a conductor with a number of tapes assembled into a subconductor. These conductors are then mounted co-planarly in an elongated dielectric to produce a 3-phase cable. The arrangement increases the magnetic field parallel to the tapes thereby reducing ac losses.

  20. The Cost of Transmission for Wind Energy: A Review of Transmission Planning Studies

    E-Print Network [OSTI]

    Mills, Andrew D.

    2009-01-01T23:59:59.000Z

    analysis of the difference in transmission costs for wind andour meta-analysis on the unit cost of transmission for windanalysis of these studies reveals considerable differences in the implied unit cost of transmission for wind.

  1. A long-pulse repetitive operation magnetically insulated transmission line oscillator

    SciTech Connect (OSTI)

    Fan, Yu-Wei; Zhong, Hui-Huang; Zhang, Jian-De; Shu, Ting; Liu, Jin Liang [College of Optoelectric Science and Engineering, National University of Defense Technology, Changsha 410073 (China)

    2014-05-15T23:59:59.000Z

    The improved magnetically insulated transmission line oscillator (MILO) is a gigawatt-class L-band high power microwave tube. It has allowed us to generate 3.1 GW pulse of 40 ns duration in the single-pulse operation and 500 MW pulse of 25 ns duration in the repetition rate operation. However, because of the severe impedance mismatch, the power conversion efficiency is only about 4% in the repetition rate operation. In order to eliminate the impedance mismatch and obtain repetitive long-pulse high-power microwave (HPM), a series of experiments are carried out and the recent progress is presented in this paper. In the single-pulse operation, when the diode voltage is 466 kV and current is 41.6 kA, the radiated microwave power is above 2.2 GW, the pulse duration is above 102 ns, the microwave frequency is about 1.74 GHz, and the power conversion efficiency is about 11.5%. In the repetition rate operation, under the condition of the diode voltage about 400 kV, beam current about 38 kA, the radiated microwave power is about 1.0 GW, the pulse duration is about 85 ns. Moreover, the radiated microwave power and the pulse duration decline little by little when the shot numbers increase gradually. The experimental results show that the impedance matching is a vital factor for HPM systems and one of the major technical challenges is to improve the cathode for the repetition rate operation MILO.

  2. NREL: Transmission Grid Integration - Transmission Planning and Analysis

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What's Possible for Renewable Energy: Grid IntegrationReportTransmission Planning and Analysis Thumbnail

  3. The Cost of Transmission for Wind Energy: A Review of Transmission Planning Studies

    E-Print Network [OSTI]

    Mills, Andrew D.

    2009-01-01T23:59:59.000Z

    2007. “Inclusion of Wind in the MISO Transmission Expansionhttp://www.jcspstudy.org/ Midwest ISO (MISO). 2007. Midwest+Planning Midwest ISO (MISO). 2003. Midwest Transmission

  4. A CRITICAL REVIEW OF WIND TRANSMISSION COST ESTIMATES FROM MAJOR TRANSMISSION PLANNING EFFORTS

    E-Print Network [OSTI]

    Mills, Andrew; Wiser, Ryan; Porter, Kevin

    2007-01-01T23:59:59.000Z

    A CRITICAL REVIEW OF WIND TRANSMISSION COST ESTIMATES FROMof establishing a wind transmission cost adder with respectthat involve wind and divide the cost by the relative share

  5. A CRITICAL REVIEW OF WIND TRANSMISSION COST ESTIMATES FROM MAJOR TRANSMISSION PLANNING EFFORTS

    E-Print Network [OSTI]

    Mills, Andrew; Wiser, Ryan; Porter, Kevin

    2007-01-01T23:59:59.000Z

    in calculating the unit cost of wind energy transmissionimpacts of the cost of transmission for wind energy. Only inj = Transmission cost per unit of wind energy weighted by

  6. Proposal of a gigawatt-class L/Ku dual-band magnetically insulated transmission line oscillator

    SciTech Connect (OSTI)

    Ju, J.-C., E-mail: jujinchuan@126.com; Fan, Y.-W.; Shu, T.; Zhong, H.-H. [College of Optoelectronic Science and Engineering, National University of Defense Technology, Changsha 410073 (China)

    2014-10-15T23:59:59.000Z

    We present a gigawatt (GW)-class magnetically insulated transmission line oscillator (MILO) which is capable of generating dual-band high power microwaves (HPMs). The proposed device, deriving from previously studied complex MILO and dual-frequency MILO, is designed to produce two HPMs in L-band and Ku-band, respectively. It is found in particle-in-cell (PIC) simulation that when the diode voltage is 610?kV, HPMs with frequencies of 1.72 GHz and 14.6?GHz can be achieved with powers of 3.3?GW and 2.4?GW, respectively. The corresponding total power conversion efficiency is approximately 12.8%. Power difference of the two generated HPMs is approximately 1.4?dB, and frequency difference of them reaches a level as high as ?10?dB.

  7. Transmission

    Office of Environmental Management (EM)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33Frequently AskedEnergyIssuesEnergy SolarRadioactiveITransactional7AMelissa Howell |

  8. Transmission

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office of ScienceandMesa del SolStrengthening a solidSynthesisAppliances » Data ManagementTransit

  9. CX-002435: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Redmond Substation 230-115-Kilovolt Transformer AdditionCX(s) Applied: B4.6Date: 05/07/2010Location(s): Deschutes County, OregonOffice(s): Bonneville Power Administration

  10. CX-008382: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Bridgeport-Sidney 115 Kilovolt Line Rejected Pole Replacement CX(s) Applied: B1.3 Date: 03/16/2012 Location(s): Nebraska Offices(s): Western Area Power Administration-Rocky Mountain Region

  11. CX-011180: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Shelton-Fairmont Number 2 115-Kilovolt Tap CX(s) Applied: B4.11 Date: 09/12/2013 Location(s): Washington Offices(s): Bonneville Power Administration

  12. Midwest Transmission Workshop II Summary

    SciTech Connect (OSTI)

    Kevin Bryan

    2002-12-05T23:59:59.000Z

    OAK-B135 After introductions of all participants, Abby Arnold, RESOLVE, reviewed the purpose of the meeting and the agenda. The purpose of the workshop was to share the results of the Midwest Independent System Operator (MISO) scenario development for wind and other fuel sources and the corresponding implications for transmission throughout the MISO control area. The workshop agenda is included in Attachment A.

  13. NREL: Transmission Grid Integration - Webinars

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What's Possible for Renewable Energy: Grid IntegrationReportTransmission Planning and Analysis

  14. NREL: Transmission Grid Integration - Webmaster

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What's Possible for Renewable Energy: Grid IntegrationReportTransmission Planning and AnalysisWebmaster

  15. Scanning Transmission Electron Microscopy for Nanostructure

    E-Print Network [OSTI]

    Pennycook, Steve

    152 6 Scanning Transmission Electron Microscopy for Nanostructure Characterization S. J. Pennycook. Introduction The scanning transmission electron microscope (STEM) is an invaluable tool atom. The STEM works on the same principle as the normal scanning electron microscope (SEM), by forming

  16. Sandia National Laboratories: energy transmission and distribution

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    grid relies on power transmission from the production source-be it a coal-fired plant, solar array, or wind farm-to the consumer. Long-distance transmission results in...

  17. Sandia National Laboratories: transmission grid integration

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    grid relies on power transmission from the production source-be it a coal-fired plant, solar array, or wind farm-to the consumer. Long-distance transmission results in...

  18. Uncertain Power Flows and Transmission Planning

    E-Print Network [OSTI]

    capability and quantifying transmission revenues under uncertainty. Illustrative analyses demonstrated potential uses in transmission planning. Part I:Stochastic-Algebraic Evaluation of Available Transfer using a deterministic model for a given system state specified by given loads, generation, line

  19. Transmission Issues and Power Exchanges in Texas

    E-Print Network [OSTI]

    Hughes, H. L.

    on the transmission owning utilities by several parties, primary distribution cooperatives, cogenerators, and large industrial customers, to grant wider access to the system. This pressure is coming at a time when transmission lines are becoming increasingly difficult...

  20. Coiled transmission line pulse generators

    DOE Patents [OSTI]

    McDonald, Kenneth Fox (Columbia, MO)

    2010-11-09T23:59:59.000Z

    Methods and apparatus are provided for fabricating and constructing solid dielectric "Coiled Transmission Line" pulse generators in radial or axial coiled geometries. The pour and cure fabrication process enables a wide variety of geometries and form factors. The volume between the conductors is filled with liquid blends of monomers, polymers, oligomers, and/or cross-linkers and dielectric powders; and then cured to form high field strength and high dielectric constant solid dielectric transmission lines that intrinsically produce ideal rectangular high voltage pulses when charged and switched into matched impedance loads. Voltage levels may be increased by Marx and/or Blumlein principles incorporating spark gap or, preferentially, solid state switches (such as optically triggered thyristors) which produce reliable, high repetition rate operation. Moreover, these Marxed pulse generators can be DC charged and do not require additional pulse forming circuitry, pulse forming lines, transformers, or an a high voltage spark gap output switch. The apparatus accommodates a wide range of voltages, impedances, pulse durations, pulse repetition rates, and duty cycles. The resulting mobile or flight platform friendly cylindrical geometric configuration is much more compact, light-weight, and robust than conventional linear geometries, or pulse generators constructed from conventional components. Installing additional circuitry may accommodate optional pulse shape improvements. The Coiled Transmission Lines can also be connected in parallel to decrease the impedance, or in series to increase the pulse length.

  1. Articles about Grid Integration and Transmission

    Broader source: Energy.gov [DOE]

    Stories about grid integration and transmission featured by the U.S. Department of Energy (DOE) Wind Program.

  2. California - Establishing Transmission Project Review Streamlining...

    Open Energy Info (EERE)

    LibraryAdd to library PermittingRegulatory Guidance - Supplemental Material: California - Establishing Transmission Project Review Streamlining DirectivesPermitting...

  3. Discontinuities in transmission lines and wave guides

    E-Print Network [OSTI]

    Mathis, Harold Fletcher

    1952-01-01T23:59:59.000Z

    DISCONTINUITIES IN TRANSMISSION LINES AND WAVEGUIDES H. F. MATHIS DISCONTINUITIES IN TRANSMISSION LINES AND liVAVNGUIDBS A Thesis By Harola Fletcher htathis Approved as to style and content by: Chairman of Committee DISCONTINUITIES... Subject. Electrical Engineering COHERENT S PAGE I Introduct ion, II Dl. scontlnuit les in Transmission Lines 2 1. Some Seneral char aeter 1 st 1 ca of the transmission lines. . . , . . . , ~ 5 2 ~ 2. Types of dlscontlnuitles ln transmls- sl...

  4. Type B Accident Investigation Board Report on the July 25, 1997, Contract Brush Cutter Injury on the Ashe-Marion #2 500 kV Line

    Broader source: Energy.gov [DOE]

    On July 25, 1997, at 1205 hours, a contract hand brush cutter was seriously injured when he felled a tree close to a Bonneville Power Administration energized transmission power line, located within a BPA transmission-line corridor.

  5. Transmission Dr. Sandra Cruz-Pol

    E-Print Network [OSTI]

    Cruz-Pol, Sandra L.

    Transmission Lines Dr. Sandra Cruz-Pol ECE Dept. UPRM Exercise 11.3 n A 40-m long TL has Vg=15 Vrms to electric circuits! cmc kmc GHz Hz 15000,000,2000/ 000,560/ 2 60 == == Transmission Lines I. TL parameters-wave transformer ¨ Slotted line ¨ Single stub VI. Microstrips Transmission Lines (TL) n TL have two conductors

  6. Smart Grid Application of Optimal Transmission Switching

    E-Print Network [OSTI]

    Ferris, Michael C.

    ;6 Introduction continued Electric Transmission Network Flow Problem Optimal Power Flow (OPF) AlternatingSmart Grid Application of Optimal Transmission Switching By, Kory W. Hedman, et al.* University (Professor, UC Berkeley) #12;2 Motivation Co-optimize transmission topology and generation dispatch

  7. A Distributed System for Cooperative MIMO Transmissions

    E-Print Network [OSTI]

    Kalyanaraman, Shivkumar

    a distributed system for facilitating cooperative MIMO transmissions in networks without multiple antenna diversity can be leveraged at the network, link or physical layers to provide energy efficient transmissions for reliable low-power transmissions. The rest of this paper is organized as follows: the proposed system

  8. > MEPS06 Preprint Version Transmission Loss

    E-Print Network [OSTI]

    Paris-Sud XI, Université de

    .phulpin@supelec.fr Abstract - In the deregulated electrical power system, the allocation of transmission losses is becoming a key issue. The electric transmission power system is more and more constrained due to the increasing electrical power system, the allocation of transmission losses is becoming a key issue. The electric

  9. Integrated Transmission and Distribution Control

    SciTech Connect (OSTI)

    Kalsi, Karanjit; Fuller, Jason C.; Tuffner, Francis K.; Lian, Jianming; Zhang, Wei; Marinovici, Laurentiu D.; Fisher, Andrew R.; Chassin, Forrest S.; Hauer, Matthew L.

    2013-01-16T23:59:59.000Z

    Distributed, generation, demand response, distributed storage, smart appliances, electric vehicles and renewable energy resources are expected to play a key part in the transformation of the American power system. Control, coordination and compensation of these smart grid assets are inherently interlinked. Advanced control strategies to warrant large-scale penetration of distributed smart grid assets do not currently exist. While many of the smart grid technologies proposed involve assets being deployed at the distribution level, most of the significant benefits accrue at the transmission level. The development of advanced smart grid simulation tools, such as GridLAB-D, has led to a dramatic improvement in the models of smart grid assets available for design and evaluation of smart grid technology. However, one of the main challenges to quantifying the benefits of smart grid assets at the transmission level is the lack of tools and framework for integrating transmission and distribution technologies into a single simulation environment. Furthermore, given the size and complexity of the distribution system, it is crucial to be able to represent the behavior of distributed smart grid assets using reduced-order controllable models and to analyze their impacts on the bulk power system in terms of stability and reliability. The objectives of the project were to: • Develop a simulation environment for integrating transmission and distribution control, • Construct reduced-order controllable models for smart grid assets at the distribution level, • Design and validate closed-loop control strategies for distributed smart grid assets, and • Demonstrate impact of integrating thousands of smart grid assets under closed-loop control demand response strategies on the transmission system. More specifically, GridLAB-D, a distribution system tool, and PowerWorld, a transmission planning tool, are integrated into a single simulation environment. The integrated environment allows the load flow interactions between the bulk power system and end-use loads to be explicitly modeled. Power system interactions are modeled down to time intervals as short as 1-second. Another practical issue is that the size and complexity of typical distribution systems makes direct integration with transmission models computationally intractable. Hence, the focus of the next main task is to develop reduced-order controllable models for some of the smart grid assets. In particular, HVAC units, which are a type of Thermostatically Controlled Loads (TCLs), are considered. The reduced-order modeling approach can be extended to other smart grid assets, like water heaters, PVs and PHEVs. Closed-loop control strategies are designed for a population of HVAC units under realistic conditions. The proposed load controller is fully responsive and achieves the control objective without sacrificing the end-use performance. Finally, using the T&D simulation platform, the benefits to the bulk power system are demonstrated by controlling smart grid assets under different demand response closed-loop control strategies.

  10. EIS-0116-S1: Final Supplemental Environmental Impact Statement for the Blue River-Gore Pass Portion of the Hayden-Blue River Transmission Line Project, Grand and Summit Counties, Colorado

    Broader source: Energy.gov [DOE]

    This supplemental environmental impact statement by the Western Area Power Administration assesses the environmental effects of constructing, operating, and maintaining about 30 miles of 230/345-kV transmission line between the existing Gore Pass Substation northwest of Kremmling, Colorado, and a proposed new substation (not part of this action) near the Ute Pass Road. Alternatives assessed included routing and design alternatives plus the alternatives addressed in the Hayden-Blue River Final EIS, issued by the Rural Electrification Administration in July 1982 and adopted by DOE in June 1985 (see DOE/EIS-0116).

  11. Fact #850: December 8, 2014 Automatic Transmissions have closed...

    Broader source: Energy.gov (indexed) [DOE]

    Historically, manual transmissions have delivered better fuel economy than automatic transmissions. However, improvements in the efficiency of automatic transmissions have closed...

  12. Comments of New England Electric Transmission Corporation on...

    Broader source: Energy.gov (indexed) [DOE]

    out of time and comments of New England Electric Transmission Corporation, New England Hydro-Transmission Electric Company, Inc. and New England Hydro-Transmission Corporation and...

  13. Development of 230-kV high-pressure, gas-filled, pipe-type cable system: Model test program phase

    SciTech Connect (OSTI)

    Silver, D.A. (Pirelli Cable Corp., Florham Park, NJ (USA))

    1990-09-01T23:59:59.000Z

    The objective of this project was the development of a 230 kV high-pressure gas-filled (HPGF) pipe-type cable employing paper or laminate of paper-polypropylene-paper (PPP) insulation pressurized with N{sub 2} gas or a blend of 15% SF{sub 6}/85% N{sub 2} gas. Heretofore, HPGF pipe-type cables have been restricted to 138 kV ratings due to technical difficulties in achieving higher voltage ratings. In view of the high cost of manufacturing and testing a large number of full size cables, cable models with 2 mm (80 mils) and 2.5 mm (100 mils) wall thicknesses of insulation enclosed in a test fixture capable of withstanding a test pressure of 2070 kPa (300 psig) and high electrical stresses were employed for dissipation factor versus voltage measurements and for ac and impulse breakdown tests at rated and emergency operating temperatures. In addition, a 36 cm (14 in) full wall cable model enclosed in a pressure vessel was utilized for transient pressure response tests. The results of this investigation attest tot he technical feasibility of the design and manufacture of a 230 kV HPGF pipe-type cable employing paper or PPP insulation pressurized with 100% N{sub 2} gas or a blend of 15% SF{sub 6}/85% N{sub 2} gas for operation under normal and 100 hour emergency conditions at conductor temperatures of 85{degree} and 105{degree}C, respectively. The manufacture of a full size PPP insulated cable pressurized with a blend of 15% SF{sub 6}/85% N{sub 2} gas employing pre-impregnated PPP insulating tapes and an annular conductor based on the design stresses defined in this report is recommended for laboratory evaluation and extended life tests. 11 refs., 45 figs., 11 tabs.

  14. The Cost of Transmission for Wind Energy in the United States: A Review of Transmission Planning Studies.

    E-Print Network [OSTI]

    Wiser, Ryan

    2014-01-01T23:59:59.000Z

    on U. S . Wind Power Installation, Cost, and Performance30% wind penetration. Wind transmission costs in the severalof Transmission ($/kW-wind) Unit Cost of Transmission ($/

  15. Automated manual transmission mode selection controller

    DOE Patents [OSTI]

    Lawrie, Robert E. (Whitmore Lake, MI)

    1999-11-09T23:59:59.000Z

    A powertrain system for a hybrid vehicle. The hybrid vehicle includes a heat engine, such as a diesel engine, and an electric machine, which operates as both an electric motor and an alternator, to power the vehicle. The hybrid vehicle also includes a manual-style transmission configured to operate as an automatic transmission from the perspective of the driver. The engine and the electric machine drive an input shaft which in turn drives an output shaft of the transmission. In addition to driving the transmission, the electric machine regulates the speed of the input shaft in order to synchronize the input shaft during either an upshift or downshift of the transmission by either decreasing or increasing the speed of the input shaft. When decreasing the speed of the input shaft, the electric motor functions as an alternator to produce electrical energy which may be stored by a storage device. Operation of the transmission is controlled by a transmission controller which receives input signals and generates output signals to control shift and clutch motors to effect smooth launch, upshift shifts, and downshifts of the transmission, so that the transmission functions substantially as an automatic transmission from the perspective of the driver, while internally substantially functioning as a manual transmission.

  16. Automated manual transmission shift sequence controller

    DOE Patents [OSTI]

    Lawrie, Robert E. (Whitmore Lake, MI); Reed, Richard G. (Royal Oak, MI); Rausen, David J. (Denver, CO)

    2000-02-01T23:59:59.000Z

    A powertrain system for a hybrid vehicle. The hybrid vehicle includes a heat engine, such as a diesel engine, and an electric machine, which operates as both, an electric motor and an alternator, to power the vehicle. The hybrid vehicle also includes a manual-style transmission configured to operate as an automatic transmission from the perspective of the driver. The engine and the electric machine drive an input shaft which in turn drives an output shaft of the transmission. In addition to driving the transmission, the electric machine regulates the speed of the input shaft in order to synchronize the input shaft during either an upshift or downshift of the transmission by either decreasing or increasing the speed of the input shaft. When decreasing the speed of the input shaft, the electric motor functions as an alternator to produce electrical energy which may be stored by a storage device. Operation of the transmission is controlled by a transmission controller which receives input signals and generates output signals to control shift and clutch motors to effect smooth launch, upshift shifts, and downshifts of the transmission, so that the transmission functions substantially as an automatic transmission from the perspective of the driver, while internally substantially functioning as a manual transmission.

  17. Image-Guided Radiotherapy (IGRT) for Prostate Cancer Comparing kV Imaging of Fiducial Markers With Cone Beam Computed Tomography (CBCT)

    SciTech Connect (OSTI)

    Barney, Brandon M., E-mail: barney.brandon@mayo.ed [Department of Radiation Oncology, Mayo Clinic, Rochester, MN (United States); Lee, R. Jeffrey [Department of Radiation Oncology, Intermountain Medical Center, Salt Lake City, UT (United States); Handrahan, Diana [Department of Statistics, Intermountain Medical Center, Salt Lake City, UT (United States); Welsh, Keith T.; Cook, J. Taylor; Sause, William T. [Department of Radiation Oncology, Intermountain Medical Center, Salt Lake City, UT (United States)

    2011-05-01T23:59:59.000Z

    Purpose: To present our single-institution experience with image-guided radiotherapy comparing fiducial markers and cone-beam computed tomography (CBCT) for daily localization of prostate cancer. Methods and Materials: From April 2007 to October 2008, 36 patients with prostate cancer received intensity-modulated radiotherapy with daily localization by use of implanted fiducials. Orthogonal kilovoltage (kV) portal imaging preceded all 1244 treatments. Cone-beam computed tomography images were also obtained before 286 treatments (23%). Shifts in the anterior-posterior (AP), superior-inferior (SI), and left-right (LR) dimensions were made from kV fiducial imaging. Cone-beam computed tomography shifts based on soft tissues were recorded. Shifts were compared by use of Bland-Altman limits of agreement. Mean and standard deviation of absolute differences were also compared. A difference of 5 mm or less was acceptable. Subsets including start date, body mass index, and prostate size were analyzed. Results: Of 286 treatments, 81 (28%) resulted in a greater than 5.0-mm difference in one or more dimensions. Mean differences in the AP, SI, and LR dimensions were 3.4 {+-} 2.6 mm, 3.1 {+-} 2.7 mm, and 1.3 {+-} 1.6 mm, respectively. Most deviations occurred in the posterior (fiducials, 78%; CBCT, 59%), superior (79%, 61%), and left (57%, 63%) directions. Bland-Altman 95% confidence intervals were -4.0 to 9.3 mm for AP, -9.0 to 5.3 mm for SI, and -4.1 to 3.9 mm for LR. The percentages of shift agreements within {+-}5 mm were 72.4% for AP, 72.7% for SI, and 97.2% for LR. Correlation between imaging techniques was not altered by time, body mass index, or prostate size. Conclusions: Cone-beam computed tomography and kV fiducial imaging are similar; however, more than one-fourth of CBCT and kV shifts differed enough to affect target coverage. This was even more pronounced with smaller margins (3 mm). Fiducial imaging requires less daily physician input, is less time-consuming, and is our preferred method for prostate image-guided radiotherapy.

  18. Case Study of the Failure of two 13.8kV Control & Metering Transformers that caused significant Equipment Damage

    SciTech Connect (OSTI)

    Dreifuerst, G R; Chew, D B; Mangonon, H L; Swyers, P W

    2011-08-25T23:59:59.000Z

    The degradation and failure of cast-coil epoxy windings within 13.8kV control power transformers and metering potential transformers has been shown to be dangerous to both equipment and personnel, even though best industrial design practices were followed. Accident scenes will be examined for two events at a U.S. Department of Energy laboratory. Failure modes will be explained and current design practices discussed with changes suggested to prevent a recurrence and to minimize future risk. New maintenance philosophies utilizing partial discharge testing of the transformers as a prediction of end-of-life will be examined.

  19. Pulse shaping with transmission lines

    DOE Patents [OSTI]

    Wilcox, Russell B. (Oakland, CA)

    1987-01-01T23:59:59.000Z

    A method and apparatus for forming shaped voltage pulses uses passive reflection from a transmission line with nonuniform impedance. The impedance of the reflecting line varies with length in accordance with the desired pulse shape. A high voltage input pulse is transmitted to the reflecting line. A reflected pulse is produced having the desired shape and is transmitted by pulse removal means to a load. Light activated photoconductive switches made of silicon can be utilized. The pulse shaper can be used to drive a Pockels cell to produce shaped optical pulses.

  20. Pulse shaping with transmission lines

    DOE Patents [OSTI]

    Wilcox, R.B.

    1985-08-15T23:59:59.000Z

    A method and apparatus for forming shaped voltage pulses uses passive reflection from a transmission line with nonuniform impedance. The impedance of the reflecting line varies with length in accordance with the desired pulse shape. A high voltage input pulse is transmitted to the reflecting line. A reflected pulse is produced having the desired shape and is transmitted by pulse removal means to a load. Light activated photoconductive switches made of silicon can be utilized. The pulse shaper can be used to drive a Pockels cell to produce shaped optical pulses.

  1. Sandia Energy - Transmission Grid Integration

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office of ScienceandMesa del Sol Home Distribution GridDocumentsInstituteThree-DimensionalTransmission Grid

  2. Scanning/Transmission Electron Microscopes

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742EnergyOnItemResearch > TheNuclearHomeland andEffectsScanning/Transmission Electron Microscopes

  3. Transmission Workshop | Department of Energy

    Energy Savers [EERE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are being directedAnnual Siteof Energy 2, 2015 - JanuaryTankToledo, Ohio,Transmission

  4. History of wireless power transmission

    SciTech Connect (OSTI)

    Brown, W.C. [Microwave Power Transmission Systems, Weston, MA (United States)] [Microwave Power Transmission Systems, Weston, MA (United States)

    1996-12-31T23:59:59.000Z

    The history of wireless power transmission at microwave frequencies is reviewed with emphasis upon the time period starting with the post World War II efforts to use the new microwave technology developed during the war. A nationally televised demonstration of a microwave powered helicopter at the Spencer Laboratory of the Raytheon Co., in 1964 was the result of these early efforts and broadly introduced the concept of wireless power transmission to scientific and engineering communities and to the public. Subsequent development efforts centered on improving the efficiency of the interconversion of d.c. and microwave power at the ends of the system to reach a demonstrated overall d.c. to d.c. system efficiency of 54% in 1974. The response to the requirements of applications such as the Solar Power Satellite and high altitude microwave powered aircraft have changed the direction of technology development and greatly expanded the technology base. Recent and current efforts are centered on examining the use of higher frequencies than the baseline 2.45 GHz, and in reducing the system costs at 2.45 GHz. 26 refs., 14 figs.

  5. Recent Progress in Chromatic Aberration Corrected High-Resolution and Lorentz Transmission Electron Microscopy

    E-Print Network [OSTI]

    Dunin-Borkowski, Rafal E.

    80 and 65 pm detail at 80 and 300 kV, respectively. Figure 2 shows CC and CS corrected energy. 58 (2009) 147. [3] R. Leary and R. Brydson. Advances in Imaging and Electron Physics 165 (2011) 73. The smallest detected image spacing at 80 kV (left) is ~80 pm and at 300 kV (right) is ~65 pm. FIG. 2. Atomic

  6. Magnetically insulated transmission line oscillator

    DOE Patents [OSTI]

    Bacon, Larry D. (Albuquerque, NM); Ballard, William P. (Albuquerque, NM); Clark, M. Collins (Albuquerque, NM); Marder, Barry M. (Albuquerque, NM)

    1988-01-01T23:59:59.000Z

    A magnetically insulated transmission line oscillator employs self-generated magnetic fields to generate microwave energy. An anode of the oscillator includes slow-wave structures which are formed of a plurality of thin conductive vanes defining cavities therebetween, and a gap is formed between the anode and a cathode of the oscillator. In response to a pulsed voltage applied to the anode and cathode, self-generated magnetic fields arfe produced in a cross-field orientation with respect to the orientation of the electric field between the anode and the cathode. The cross-field magnetic fields insulate the flow of electrons in the gap and confine the flow of electrons within the gap.

  7. Superconducting transmission line particle detector

    DOE Patents [OSTI]

    Gray, Kenneth E. (Naperville, IL)

    1989-01-01T23:59:59.000Z

    A microvertex particle detector for use in a high energy physic collider including a plurality of parallel superconducting thin film strips separated from a superconducting ground plane by an insulating layer to form a plurality of superconducting waveguides. The microvertex particle detector indicates passage of a charged subatomic particle by measuring a voltage pulse measured across a superconducting waveguide caused by the transition of the superconducting thin film strip from a superconducting to a non-superconducting state in response to the passage of a charged particle. A plurality of superconducting thin film strips in two orthogonal planes plus the slow electromagnetic wave propogating in a superconducting transmission line are used to resolve N.sup.2 ambiguity of charged particle events.

  8. Superconducting transmission line particle detector

    DOE Patents [OSTI]

    Gray, K.E.

    1988-07-28T23:59:59.000Z

    A microvertex particle detector for use in a high energy physic collider including a plurality of parallel superconducting thin film strips separated from a superconducting ground plane by an insulating layer to form a plurality of superconducting waveguides. The microvertex particle detector indicates passage of a charged subatomic particle by measuring a voltage pulse measured across a superconducting waveguide caused by the transition of the superconducting thin film strip from a superconducting to a non- superconducting state in response to the passage of a charged particle. A plurality of superconducting thin film strips in two orthogonal planes plus the slow electromagnetic wave propagating in a superconducting transmission line are used to resolve N/sup 2/ ambiguity of charged particle events. 6 figs.

  9. Final Report Navajo Transmission Project (NTP)

    SciTech Connect (OSTI)

    Bennie Hoisington; Steven Begay

    2006-09-14T23:59:59.000Z

    The Diné Power Authority is developing the Navajo Transmission Project (NTP) to relieve the constraints on the transmission of electricity west of the Four Corners area and to improve the operation flexibility and reliability of the extra-high-voltage transmission system in the region. The NTP creates the wholesale transmission capacity for more economical power transfers, sales, and purchases in the region. It will facilitate the development of Navajo energy resources, improve economic conditions on the Navajo Nation as well as allow DPA to participate in the western electrical utility industry.

  10. Transmission Expansion Planning Using an AC Model ...

    E-Print Network [OSTI]

    Periodicals

    2013-01-02T23:59:59.000Z

    Western Interconnection” under contract DOE-FOA0000068. ... problem to determine locations for placing new transmission ... KNITRO and BONMIN are de

  11. Exploring the Business Link Opportunity: Transmission & Clean...

    Energy Savers [EERE]

    Jennifer Weddle, Greenberg Traurig LLP Rapid Response Team for Transmission: Laura Smith Morton, DOE Energy Storage: Michael Stosser, Day Pitney LLP Centennial West Clean...

  12. In Situ Electrochemical Transmission Electron Microscopy for...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    for Battery Research. Abstract: The recent development of in situ liquid stages for (scanning) transmission electron microscopes now makes it possible for us to study the details...

  13. Sandia National Laboratories: Transmission Grid Integration

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Transmission Grid Integration Wind Generator Modeling On June 26, 2014, in Computational Modeling & Simulation, Energy, Energy Surety, Grid Integration, Infrastructure Security,...

  14. Natural Gas Transmission Pipeline Siting Act (Florida)

    Broader source: Energy.gov [DOE]

    This Act establishes a centralized and coordinated permitting process for the location of natural gas transmission pipeline corridors and the construction and maintenance of natural gas...

  15. Natural Gas Transmission and Distribution Module This

    Annual Energy Outlook 2013 [U.S. Energy Information Administration (EIA)]

    They relate to (1) structural components of the model, (2) capacity expansion and pricing of transmission and distribution services, (3) Arctic pipelines, and (4) imports...

  16. Natural Gas Transmission and Distribution Module

    Annual Energy Outlook 2013 [U.S. Energy Information Administration (EIA)]

    They relate to (1) structural components of the model, (2) capacity expansion and pricing of transmission and distribution services, (3) Arctic pipelines, and (4) imports...

  17. Proponent's Environmental Assessment (PEA) Checklist for Transmission...

    Open Energy Info (EERE)

    Proponent's Environmental Assessment (PEA) Checklist for Transmission Line and Substation Projects Jump to: navigation, search OpenEI Reference LibraryAdd to library Permitting...

  18. Transmission Reassignment Reporting Requirement - April 2, 2014

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    CommitteesTeams Customer Training Interconnection Notices Rates Standards of Conduct Tariff TF Web Based Training Transmission Reassignment Reporting Requirement This notice...

  19. Transmission and Generation Investment in Electricity Markets

    E-Print Network [OSTI]

    Grimm Veronika

    2015-03-04T23:59:59.000Z

    Mar 4, 2015 ... The model incorporates investment decisions of the transmission operator and private firms in expectation of an energy-only market and ...

  20. 2006 National Electric Transmission Congestion Study Federal...

    Office of Environmental Management (EM)

    Comments to the Feb 06 FRN received after March 9, 2006 More Documents & Publications Proceedings of the March 29, 2006 Conference for the 2006 National Electric Transmission...

  1. Transmission Line Security Monitor: Final Report

    SciTech Connect (OSTI)

    John Svoboda

    2011-04-01T23:59:59.000Z

    The Electric Power Transmission Line Security Monitor System Operational Test is a project funded by the Technical Support Working Group (TSWG). TSWG operates under the Combating Terrorism Technical Support Office that functions under the Department of Defense. The Transmission Line Security Monitor System is based on technology developed by Idaho National Laboratory. The technology provides a means for real-time monitoring of physical threats and/or damage to electrical transmission line towers and conductors as well as providing operational parameters to transmission line operators to optimize transmission line operation. The end use is for monitoring long stretches of transmission lines that deliver electrical power from remote generating stations to cities and industry. These transmission lines are generally located in remote transmission line corridors where security infrastructure may not exist. Security and operational sensors in the sensor platform on the conductors take power from the transmission line and relay security and operational information to operations personnel hundreds of miles away without relying on existing infrastructure. Initiated on May 25, 2007, this project resulted in pre-production units tested in realistic operational environments during 2010. A technology licensee, Lindsey Manufacturing of Azusa California, is assisting in design, testing, and ultimately production. The platform was originally designed for a security monitoring mission, but it has been enhanced to include important operational features desired by electrical utilities.

  2. Coordinating Interstate Electric Transmission Siting: An Introduction...

    Open Energy Info (EERE)

    the near future. While improved demand-side management (including energy effi ciency and demand response), bett er utilization of the existing transmission grid, and other...

  3. Flexible Transmission in the Smart Grid

    E-Print Network [OSTI]

    Hedman, Kory Walter

    2010-01-01T23:59:59.000Z

    New England Outlook: Smart Grid is About Consumers,” Apr. [Transmission in the Smart Grid By Kory Walter Hedman ATransmission in the Smart Grid by Kory Walter Hedman Doctor

  4. Detonator comprising a nonlinear transmission line

    DOE Patents [OSTI]

    Elizondo-Decanini, Juan M

    2014-12-30T23:59:59.000Z

    Detonators are described herein. In a general embodiment, the detonator includes a nonlinear transmission line that has a variable capacitance. Capacitance of the nonlinear transmission line is a function of voltage on the nonlinear transmission line. The nonlinear transmission line receives a voltage pulse from a voltage source and compresses the voltage pulse to generate a trigger signal. Compressing the voltage pulse includes increasing amplitude of the voltage pulse and decreasing length of the voltage pulse in time. An igniter receives the trigger signal and detonates an explosive responsive to receipt of the trigger signal.

  5. A CRITICAL REVIEW OF WIND TRANSMISSION COST ESTIMATES FROM MAJOR TRANSMISSION PLANNING EFFORTS

    E-Print Network [OSTI]

    Mills, Andrew; Wiser, Ryan; Porter, Kevin

    2007-01-01T23:59:59.000Z

    Report.pdf Midwest ISO (MISO). 2003. Midwest TransmissionConference September 2007 MISO. 2007. Midwest Transmission2006 SDG&E Midwest ISO (MISO) ISO/RTO February 2007 MISO '06

  6. The Cost of Transmission for Wind Energy: A Review of Transmission Planning Studies

    E-Print Network [OSTI]

    Mills, Andrew D.

    2009-01-01T23:59:59.000Z

    on U.S. Wind Power Installation, Cost, and PerformanceTransmission ($/kW-wind) Unit Cost (Capacity-weighted) Windof Transmission ($/MWh- wind) Unit Cost (Capacity-weighted)

  7. The Cost of Transmission for Wind Energy: A Review of Transmission Planning Studies

    E-Print Network [OSTI]

    Mills, Andrew D.

    2009-01-01T23:59:59.000Z

    2006. Transmission and Wind Energy: Capturing the Prevailingand Renewable Energy (Wind & Hydropower Technologiesand Renewable Energy Wind & Hydropower Technologies Program

  8. Treatment of biodiversity issues in impact assessment of electricity power transmission lines: A Finnish case review

    SciTech Connect (OSTI)

    Soederman, Tarja [Senior Researcher, Lic. Phil., Finnish Environment Institute, Nature Division, P.O. Box 140, FIN-00251 Helsinki (Finland)]. E-mail: tarja.soderman@ymparisto.fi

    2006-05-15T23:59:59.000Z

    The Environmental Impact Assessment (EIA) process concerning the route of a 400 kV power transmission line between Loviisa and Hikiae in southern Finland was reviewed in order to assess how biodiversity issues are treated and to provide suggestions on how to improve the effectiveness of treatment of biodiversity issues in impact assessment of linear development projects. The review covered the whole assessment process, including interviews of stakeholders, participation in the interest group meetings and review of all documents from the project. The baseline studies and assessment of direct impacts in the case study were detailed but the documentation, both the assessment programme and the assessment report, only gave a partial picture of the assessment process. All existing information, baseline survey and assessment methods should be addressed in the scoping phase in order to promote interaction between all stakeholders. In contrast to the assessment of the direct effects, which first emphasized impacts on the nationally important and protected flying squirrel but later expanded to deal with the assessment of impacts on ecologically important sites, the indirect and cumulative impacts of the power line were poorly addressed. The public was given the opportunity to become involved in the EIA process. However, they were more concerned with impacts on their properties and less so on biodiversity and species protection issues. This suggests that the public needs to become more informed about locally important features of biodiversity.

  9. Probabilistic Reliable Message Transmission Subodh Kumar

    E-Print Network [OSTI]

    North Carolina at Chapel Hill, University of

    Probabilistic Reliable Message Transmission Subodh Kumar January 17, 1996 Abstract Most communication systems require reliable transmission of a sequence of messages over a physical network which can with messages by the sender and they are acknowledged by the receiver. It is known that protocols that use

  10. Empirical Analysis of Transmission Power Control Algorithms

    E-Print Network [OSTI]

    Culler, David E.

    Empirical Analysis of Transmission Power Control Algorithms for Wireless Sensor Networks Jaein · Power saving techniques in WSN ­ Duty-cycling, TX-power control, clustering ­ We study effect of TX-power transmission. End-to-end delivery rate TX Power Control Best of Fixed TX Power El Batt [1] 36.5% 35.5% PCBL [6

  11. A Transmission Control Framework Continuous Media

    E-Print Network [OSTI]

    Whitton, Mary C.

    Rights Reserved #12;ABSTRACT A Transmission Control Framework for Continuous Media (Under the directionA Transmission Control Framework for Continuous Media by Terry Michael Talley A dissertation by integrating real-time two-way audio and video with the computer system. Unfortunately, the quality of video

  12. Method of calibrating clutches in transmissions

    SciTech Connect (OSTI)

    Bulgrien, G.H.

    1991-02-05T23:59:59.000Z

    This paper describes a microprocessor controlling a shuttle shift transmission programmed to effect a calibration of the final drive clutches in the transmission so that the microprocessor can efficiently effect engagement of each respective clutch by applying the proper hydraulic pressure to cause proper engagement thereof. This method of calibrating the final drive clutches in the transmission includes braking the output shaft of the transmission so that any engagement of the selected final drive clutch being calibrated will cause a load to be applied to the engine. The hydraulic pressure is then incrementally increased until the engine RPM's decrease because of the load being placed on the engine. The value of this engagement hydraulic pressure is stored in the microprocessor for use when effecting engagement of the selected clutch during operation of the transmission. Service indicators are programmed into the microprocessor should the selected clutch not be capable of being calibrated.

  13. Low cost Image Transmission System

    SciTech Connect (OSTI)

    Skogmo, D.

    1994-06-01T23:59:59.000Z

    Throughout the Department of Energy (DOE) complex, sites protect themselves with intrusion detection systems. Some of these systems have sensors in remote areas. These sensors frequently alarm -- not because they have detected a terrorist skulking around the area, but because they have detected a horse, or a dog, or a bush moving in the breeze. Even though the local security force is 99% sure there is no real threat, they must assess each of these nuisance or false alarms. Generally, the procedure consists of dispatching an inspector to drive to the area and make an assessment. This is expensive in terms of manpower and the assessment is not timely. Often, by the time the inspector arrives, the cause of the alarm has vanished. A television camera placed to view the area protected by the sensor could be used to help in this assessment, but this requires the installation of high-quality cable, optical fiber, or a microwave link. Further, to be of use at the present time, the site must have had the foresight to have installed these facilities in the past and have them ready for use now. What is needed is a device to place between the television camera and a modem connecting to a low-bandwidth channel such as radio or a telephone line. This paper discusses the development of such a device: an Image Transmission System, or ITS.

  14. Conductive Channel for Energy Transmission

    SciTech Connect (OSTI)

    Apollonov, Victor V. [A.M. Prokhorov General Physics Institute, Vavilov Str. 38, Moscow, 119991 (Russian Federation)

    2011-11-10T23:59:59.000Z

    For many years the attempts to create conductive channels of big length were taken in order to study the upper atmosphere and to settle special tasks, related to energy transmission. There upon the program of creation of 'Impulsar' represents a great interest, as this program in a combination with high-voltage high repetition rate electrical source can be useful to solve the above mentioned problems (N. Tesla ideas for the days of high power lasers). The principle of conductive channel production can be shortly described as follows. The 'Impulsar' - laser jet engine vehicle - propulsion take place under the influence of powerful high repetition rate pulse-periodic laser radiation. In the experiments the CO{sub 2}-laser and solid state Nd:YAG laser systems had been used. Active impulse appears thanks to air breakdown (<30 km) or to the breakdown of ablated material on the board (>30 km), placed in the vicinity of the focusing mirror-acceptor of the breakdown waves. With each pulse of powerful laser the device rises up, leaving a bright and dense trace of products with high degree of ionization and metallization by conductive nano-particles due to ablation. Conductive dust plasma properties investigation in our experiments was produced by two very effective approaches: high power laser controlled ablation and by explosion of wire. Experimental and theoretical results of conductive canal modeling will be presented. The estimations show that with already experimentally demonstrated figures of specific thrust impulse the lower layers of the Ionosphere can be reached in several ten seconds that is enough to keep the high level of channel conductivity and stability with the help of high repetition rate high voltage generator. Some possible applications for new technology are highlighted.

  15. Concurrent Wind Cooling in Power Transmission Lines

    SciTech Connect (OSTI)

    Jake P Gentle

    2012-08-01T23:59:59.000Z

    Idaho National Laboratory and the Idaho Power Company, with collaboration from Idaho State University, have been working on a project to monitor wind and other environmental data parameters along certain electrical transmission corridors. The combination of both real-time historical weather and environmental data is being used to model, validate, and recommend possibilities for dynamic operations of the transmission lines for power and energy carrying capacity. The planned results can also be used to influence decisions about proposed design criteria for or upgrades to certain sections of the transmission lines.

  16. MATHEMATICAL ANALYSIS OF CONDUCTING AND SUPERCONDUCTING TRANSMISSION LINES

    E-Print Network [OSTI]

    Ramdani, Karim - Institut de Mathématiques �lie Cartan, Université Henri Poincaré

    MATHEMATICAL ANALYSIS OF CONDUCTING AND SUPERCONDUCTING TRANSMISSION LINES ANNE-SOPHIE BONNET propagation in the microstrip transmission lines used in microelectronics. In the first part, the case of the perfectly conducting strip. Key words. superconducting transmission lines, waveguides, spectral analysis

  17. CHARACTERIZING LOSSES IN MICROSTRIP TRANSMISSION LINES Rashmi Pathak

    E-Print Network [OSTI]

    Timbie, Peter

    CHARACTERIZING LOSSES IN MICROSTRIP TRANSMISSION LINES by Rashmi Pathak A dissertation submitted . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4 2.1 Transmission Lines . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4 2 Engineering) at the UNIVERSITY OF WISCONSIN­MADISON Summer 2005 #12;i Characterizing Losses in Transmission

  18. Hydrogen Delivery Technologies and Pipeline Transmission of Hydrogen

    E-Print Network [OSTI]

    Hydrogen Delivery Technologies and Systems Pipeline Transmission of Hydrogen Strategic Initiatives, and Infrastructure Technologies Program #12;Pipeline Transmission of Hydrogen --- 2 Copyright: Design & Operation development) #12;Pipeline Transmission of Hydrogen --- 3 Copyright: Future H2 Infrastructure Wind Powered

  19. Electric Power Generation and Transmission (Iowa)

    Broader source: Energy.gov [DOE]

    Electric power generating facilities with a combined capacity greater than 25 MW, as well as associated transmission lines, may not be constructed or begin operation prior to the issuance of a...

  20. Articles about Grid Integration and Transmission | Department...

    Broader source: Energy.gov (indexed) [DOE]

    grid integration and transmission featured by the U.S. Department of Energy (DOE) Wind Program. May 18, 2015 New Report Says Western Grid Can Weather Disturbances with High Wind,...

  1. Efficient Spectral Methods for Transmission Eigenvalues and ...

    E-Print Network [OSTI]

    2014-03-24T23:59:59.000Z

    Mar 20, 2014 ... The scattered electric and magnetic fields Es and Hs satisfy the Silver-M¨uller radiation ... of k for which the (homogeneous) interior transmission problem ...... Mathematical methods in the applied sciences, 27(18):2111–. 2129 ...

  2. Scanning Transmission Electron Microscopy Investigations of Complex...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Scanning Transmission Electron Microscopy Investigations of Complex Oxides Monday, May 23, 2011 - 3:30pm SSRL Conference room 137-322 Professor Tom Vogt, NanoCenter & Department of...

  3. Data transmission element for downhole drilling components

    DOE Patents [OSTI]

    Hall, David R. (Provo, UT); Hall, Jr., H. Tracy (Provo, UT); Pixton, David S. (Lehi, UT); Dahlgren, Scott (Provo, UT); Fox, Joe (Spanish Fork, UT); Sneddon, Cameron (Provo, UT); Briscoe, Michael (Lehi, UT)

    2006-01-31T23:59:59.000Z

    A robust data transmission element for transmitting information between downhole components, such as sections of drill pipe, in the presence of hostile environmental conditions, such as heat, dirt, rocks, mud, fluids, lubricants, and the like. The data transmission element components include a generally U-shaped annular housing, a generally U-shaped magnetically conductive, electrically insulating element such as ferrite, and an insulated conductor. Features on the magnetically conducting, electrically insulating element and the annular housing create a pocket when assembled. The data transmission element is filled with a polymer to retain the components within the annular housing by filling the pocket with the polymer. The polymer can bond with the annular housing and the insulated conductor but preferably not the magnetically conductive, electrically insulating element. A data transmission element is mounted within a recess proximate a mating surface of a downhole drilling component, such as a section of drill pipe.

  4. Electrical Transmission Line Diametrical Retention Mechanism

    DOE Patents [OSTI]

    Hall, David R. (Provo, UT); Hall, Jr., H. Tracy (Provo, UT); Pixton, David (Lehi, UT); Dahlgren, Scott (Provo, UT); Sneddon, Cameron (Provo, UT); Briscoe, Michael (Lehi, UT); Fox, Joe (Spanish Fork, UT)

    2006-01-03T23:59:59.000Z

    The invention is a mechanism for retaining an electrical transmission line. In one embodiment of the invention it is a system for retaining an electrical transmission line within downhole components. The invention allows a transmission line to be attached to the internal diameter of drilling components that have a substantially uniform drilling diameter. In accordance with one aspect of the invention, the system includes a plurality of downhole components, such as sections of pipe in a drill string, drill collars, heavy weight drill pipe, and jars. The system also includes a coaxial cable running between the first and second end of a drill pipe, the coaxial cable having a conductive tube and a conductive core within it. The invention allows the electrical transmission line to withstand the tension and compression of drill pipe during routine drilling cycles.

  5. Load-resistant coaxial transmission line

    DOE Patents [OSTI]

    Hall, David R.; Fox, Joe

    2006-01-03T23:59:59.000Z

    A transmission line for downhole tools that make up all or part of a tool string for drilling and production of oil, gas, and geothermal wells that can withstand the dynamic gravitational forces and other accelerations associated with downhole excavations. The transmission line has a metal tube, or outer conductor, that houses a coaxial wire inner conductor. A non-metallic dielectric material is interposed between the inner and outer conductors. The outer and inner conductors and the dielectric are sufficiently compressed together so that independent motion between them is abated. Compression of the components of the transmission line may be achieved by drawing the transmission through one or more dies in order to draw down the outer conductor onto the dielectric, or by expanding the inner conductor against the dielectric using a mandrel or hydraulic pressure. Non-metallic bead segments may be used in aid of the compression necessary to resist the dynamic forces and accelerations of drilling.

  6. Transmission policy in the United States

    E-Print Network [OSTI]

    Joskow, Paul L.

    2004-01-01T23:59:59.000Z

    This paper provides an overview of the development of electric power transmission access, pricing and investment policies in the U.S. over the last 15 years and evaluates the current state of those policies. Pre-liberalization ...

  7. Infrastructure Needs: Natural Gas/Electricity Transmission,...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    4,200 miles of transmission lines, 72,000 miles of distribution lines, and 6,300 miles of natural gas pipelines. Our over 8,600 employees are committed to our mission to deliver...

  8. Polarization transmission at RHIC, numerical simulations

    SciTech Connect (OSTI)

    Meot F.; Bai, M.; Liu, C.; Minty, M.; Ranjbar, V.

    2012-05-20T23:59:59.000Z

    Typical tracking simulations regarding the transmission of the polarization in the proton-proton collider RHIC are discussed. They participate in general studies aimed at understanding and improving polarization performances during polarized proton-proton runs.

  9. X-ray transmissive debris shield

    DOE Patents [OSTI]

    Spielman, Rick B. (Albuquerque, NM)

    1994-01-01T23:59:59.000Z

    A composite window structure is described for transmitting x-ray radiation and for shielding radiation generated debris. In particular, separate layers of different x-ray transmissive materials are laminated together to form a high strength, x-ray transmissive debris shield which is particularly suited for use in high energy fluences. In one embodiment, the composite window comprises alternating layers of beryllium and a thermoset polymer.

  10. EIS-0365: EPA Notice of Availability of the Draft Environmental...

    Broader source: Energy.gov (indexed) [DOE]

    of the Draft Environmental Impact Statement Imperial-Mexicali 230-kV Transmission Lines Imperial-Mexicali 230-kV Transmission Lines, Construct a Double-Circuit 230-kV...

  11. Categorical Exclusion (CX) Determination Proposed Action: Elliot...

    Broader source: Energy.gov (indexed) [DOE]

    Elliot 115kV43.8kV Transmission Substation Construction and Elliot 43.8kV Transmission Line. Description of Proposed Action: The Central Power Electric Cooperative (Central Power)...

  12. MASe UCRL-15037 CONTINUOUSLY VARIABLE TRANSMISSIONS: THEORY AND...

    Office of Scientific and Technical Information (OSTI)

    transmission when operating in the power recirculation mode 20 Simple manual system to control the speed ratio of a variable V-belt continuously variable transmission 21 Schematic...

  13. EIS-0483: Estes to Flatiron Substation Transmission Lines Rebuild...

    Broader source: Energy.gov (indexed) [DOE]

    EIS-0483: Estes to Flatiron Substation Transmission Lines Rebuild Project, Larimer County, Colorado EIS-0483: Estes to Flatiron Substation Transmission Lines Rebuild Project,...

  14. OAHU Wind Integration And Transmission Study: Summary Report...

    Energy Savers [EERE]

    OAHU Wind Integration And Transmission Study: Summary Report, NREL (National Renewable Energy Laboratory) OAHU Wind Integration And Transmission Study: Summary Report, NREL...

  15. QER Public Meeting in Newark, NJ: Electricity Transmission and...

    Energy Savers [EERE]

    Newark, NJ: Electricity Transmission and Distribution - East QER Public Meeting in Newark, NJ: Electricity Transmission and Distribution - East New Jersey Institute of Technology...

  16. DOE EAC Electricity Adequacy Report. Transmission Chapter DRAFT...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    EAC Electricity Adequacy Report. Transmission Chapter DRAFT- September 18, 2008 DOE EAC Electricity Adequacy Report. Transmission Chapter DRAFT- September 18, 2008 The purpose of...

  17. Updating the Electric Grid: An Introduction to Non-Transmission...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    the transmission system. Updating the Electric Grid: An Introduction to Non-Transmission Alternatives for Policymakers More Documents & Publications EAC Recommendations for DOE...

  18. In-situ Transmission Electron Microscopy and Spectroscopy Studies...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Transmission Electron Microscopy and Spectroscopy Studies of Interfaces in Li-ion Batteries: Challenges and In-situ Transmission Electron Microscopy and Spectroscopy Studies of...

  19. Regulatory Roadmap Workshop for Federal Bulk Transmission Regulations...

    Open Energy Info (EERE)

    for bulk transmission. Date: Tuesday, 29 July, 2014 - 09:30 - 15:30 Location: NREL Education Center Auditorium Golden, Colorado Groups: Federal Bulk Transmission Regulatory...

  20. Request for Information on Permitting of Transmission Lines:...

    Energy Savers [EERE]

    Request for Information on Permitting of Transmission Lines: Federal Register Notice Volume 77, No. 38 - Feb. 27, 2012 Request for Information on Permitting of Transmission Lines:...

  1. An environmental sample chamber for reliable scanning transmission...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    environmental sample chamber for reliable scanning transmission x-ray microscopy measurements under water vapor. An environmental sample chamber for reliable scanning transmission...

  2. CFN | Hitachi HD2700C Scanning Transmission Electron Microscope

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Hitachi HD2700C Scanning Transmission Electron Microscope Contacts: Dong Su | Lihua Zhang | Huolin Xin The Hitachi 2700C is a dedicated Scanning Transmission Electron Microscope...

  3. EIS-0484: Montana-to-Washington Transmission System Upgrade Project...

    Energy Savers [EERE]

    4: Montana-to-Washington Transmission System Upgrade Project in Washington, Idaho, and Montana EIS-0484: Montana-to-Washington Transmission System Upgrade Project in Washington,...

  4. Integrating Renewable Energy into the Transmission and Distribution...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Integrating Renewable Energy into the Transmission and Distribution System of the U.S. Virgin Islands Integrating Renewable Energy into the Transmission and Distribution System of...

  5. EIS-0447: Champlain Hudson Power Express Transmission Line Project...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    47: Champlain Hudson Power Express Transmission Line Project, New York EIS-0447: Champlain Hudson Power Express Transmission Line Project, New York Summary This EIS evaluated the...

  6. EA-1880: Big Bend to Witten Transmission Line Project, South...

    Office of Environmental Management (EM)

    880: Big Bend to Witten Transmission Line Project, South Dakota EA-1880: Big Bend to Witten Transmission Line Project, South Dakota Summary The USDA Rural Utilities Service, with...

  7. Eastern Wind Integration and Transmission Study -- Preliminary Findings: Preprint

    SciTech Connect (OSTI)

    Corbus, D.; Milligan, M.; Ela, E.; Schuerger, M.; Zavadil, B.

    2009-09-01T23:59:59.000Z

    This paper reviews the Eastern Wind Integration and Transmission Study, the development of wind datasets, the transmission analysis, and the results of wind integration analysis for four scenarios.

  8. power transmission network design by a greedy randomized ...

    E-Print Network [OSTI]

    of new transmission facilities should be installed, i.e. the ... whole, much more complex, power transmission network ..... 17 new rights of way (corridors).

  9. 2006 National Electric Transmission Congestion Study and Related...

    Office of Environmental Management (EM)

    6 National Electric Transmission Congestion Study and Related Materials 2006 National Electric Transmission Congestion Study and Related Materials The 2006 National Congestion...

  10. Factsheet: An Initiative to Help Modernize Natural Gas Transmission...

    Energy Savers [EERE]

    An Initiative to Help Modernize Natural Gas Transmission and Distribution Infrastructure Factsheet: An Initiative to Help Modernize Natural Gas Transmission and Distribution...

  11. QER Public Meeting in Pittsburgh, PA: Natural Gas: Transmission...

    Office of Environmental Management (EM)

    Pittsburgh, PA: Natural Gas: Transmission, Storage and Distribution QER Public Meeting in Pittsburgh, PA: Natural Gas: Transmission, Storage and Distribution Meeting Date and...

  12. 9-26 QER Report: Energy Transmission, Storage, and Distribution...

    Office of Environmental Management (EM)

    -26 QER Report: Energy Transmission, Storage, and Distribution Infrastructure | April 2015 QER Report: Energy Transmission, Storage, and Distribution Infrastructure | April 2015...

  13. An Annotated Bibliography of High-Voltage Direct-Current Transmission and Flexible AC Transmission (FACTS) Devices, 1991-1993.

    SciTech Connect (OSTI)

    Litzenberger, Wayne; Lava, Val

    1994-08-01T23:59:59.000Z

    References are contained for HVDC systems, converter stations and components, overhead transmission lines, cable transmission, system design and operations, simulation of high voltage direct current systems, high-voltage direct current installations, and flexible AC transmission system (FACTS).

  14. Fact #850: December 8, 2014 Automatic Transmissions have closed the Fuel Economy Gap with Manual Transmissions- Dataset

    Broader source: Energy.gov [DOE]

    Excel file with dataset for Fact #850: December 8, 2014 Automatic Transmissions have closed the Fuel Economy Gap with Manual Transmissions

  15. Hydraulic system for a ratio change transmission

    DOE Patents [OSTI]

    Kalns, Ilmars (Northville, MI)

    1981-01-01T23:59:59.000Z

    Disclosed is a drive assembly (10) for an electrically powered vehicle (12). The assembly includes a transaxle (16) having a two-speed transmission (40) and a drive axle differential (46) disposed in a unitary housing assembly (38), an oil-cooled prime mover or electric motor (14) for driving the transmission input shaft (42), an adapter assembly (24) for supporting the prime mover on the transaxle housing assembly, and a hydraulic system (172) providing pressurized oil flow for cooling and lubricating the electric motor and transaxle and for operating a clutch (84) and a brake (86) in the transmission to shift between the two-speed ratios of the transmission. The adapter assembly allows the prime mover to be supported in several positions on the transaxle housing. The brake is spring-applied and locks the transmission in its low-speed ratio should the hydraulic system fail. The hydraulic system pump is driven by an electric motor (212) independent of the prime mover and transaxle.

  16. Abstract--Electric energy transmission is essential for the operation of competitive energy markets. Transmission

    E-Print Network [OSTI]

    Catholic University of Chile (Universidad Católica de Chile)

    TECHNIQUES Meta-heuristic techniques are a hybrid version of classical and heuristic optimization. Basically1 Abstract-- Electric energy transmission is essential for the operation of competitive energy markets. Transmission expansion planning has been defined as a complex combinatorial optimization problem

  17. How Compatible is Perfect Competition with Transmission Loss Allocation Methods?

    E-Print Network [OSTI]

    Boyer, Edmond

    the problem of transmission loss allocation in a power system where the generators, the demands and the system. INTRODUCTION IN power systems where generation and transmission are unbundled, the transmission operationalHow Compatible is Perfect Competition with Transmission Loss Allocation Methods? Jing Dai, Yannick

  18. Questions and Issues on Hydrogen Pipeline Transmission of Hydrogen

    E-Print Network [OSTI]

    Questions and Issues on Hydrogen Pipelines Pipeline Transmission of Hydrogen Doe Hydrogen Pipeline Working Group Meeting August 31, 2005 #12;Pipeline Transmission of Hydrogen --- 2 Copyright: Air Liquide Transmission of Hydrogen --- 3 Copyright: #12;Pipeline Transmission of Hydrogen --- 4 Copyright: 3. Special

  19. Intern experience at Electricity Directorate of Bahrain: an internship report

    E-Print Network [OSTI]

    Aljamea, Najeeb Ahmad

    2013-03-13T23:59:59.000Z

    n ......................................27 8. A VDU Picture of a Substation .............................................................. 35 9. A VDU Picutre of the Alarm List................................................................ 38 10... consists of : - Over-head lines : 33kv &66kv - Underground cables : 33kv & 66kv & 220kv - Substations: 33 /llkv & 66 /llkv & 220/66kv. Associated with this equipment is a protection system which utilises a network of pilot cables. The transmission...

  20. Operation of Lanzhou all permanent electron cyclotron resonance ion source No. 2 on 320 kV platform with highly charged ions

    SciTech Connect (OSTI)

    Lu, W., E-mail: luwang@impcas.ac.cn [Institute of Modern Physics, CAS, Lanzhou 730000 (China); University of Chinese Academy of Sciences, Beijing 100049 (China); Li, J. Y.; Kang, L.; Liu, H. P.; Li, H.; Li, J. D.; Sun, L. T.; Ma, X. W. [Institute of Modern Physics, CAS, Lanzhou 730000 (China)] [Institute of Modern Physics, CAS, Lanzhou 730000 (China)

    2014-02-15T23:59:59.000Z

    The 320 kV platform for multi-discipline research with highly charged ions is a heavy ion beam acceleration instrument developed by Institute of Modern Physics, which is dedicated to basic scientific researches such as plasma, atom, material physics, and astrophysics, etc. The platform has delivered ion beams of 400 species for 36?000 h. The average operation time is around 5000 h/year. With the beams provided by the platform, lots of outstanding progresses were made in various research fields. The ion source of the platform is an all-permanent magnet electron cyclotron resonance ion source, LAPECR2 (Lanzhou All Permanent ECR ion source No. 2). The maximum axial magnetic fields are 1.28 T at injection and 1.07 T at extraction, and the radial magnetic field is up to 1.21 T at the inner wall of the plasma chamber. The ion source is capable to produce low, medium, and high charge state gaseous and metallic ion beams, such as H{sup +}, {sup 40}Ar{sup 8+}, {sup 129}Xe{sup 30+}, {sup 209}Bi{sup 33+}, etc. This paper will present the latest result of LAPECR2 and the routine operation status for the high voltage platform.

  1. Solar light transmission of polymer optical fibers

    SciTech Connect (OSTI)

    Tekelioglu, Murat [Mechanical Engineering Department, University of Nevada, Reno, NV 89557 (United States); Wood, Byard D. [Mechanical and Aerospace Engineering Department, Utah State University, Logan, UT 84322 (United States)

    2009-11-15T23:59:59.000Z

    Light transfer (10 m) has been shown in recent experiments that used large-core optical fibers. Theoretical models are not extensive, however, and a further correlation between the theory and experiments has not been given. In this paper, straight and bent fiber subsystem models are introduced with skew and meridional rays to predict the light transmission of POFs (plastic optical fibers). Such fibers have been realized, for example, in HSL (hybrid solar lighting) systems. The purpose of this paper is to combine the straight and bent fiber subsystems to estimate the light transmission of HSL systems. It is shown that meridional rays, for which the optical-loss parameters were estimated, better represent the experimental results compared to skew rays ({+-}5.3% vs {+-}24.7% of %-difference). Model predictions were compared with the results of a commercial software. Sensitivity analysis on the subsystems indicated the most-to-least significant parameters in light transmission. (author)

  2. Downhole transmission system comprising a coaxial capacitor

    DOE Patents [OSTI]

    Hall, David R. (Provo, UT); Pixton, David S. (Lehi, UT); Johnson, Monte L. (Orem, UT); Bartholomew, David B. (Springville, UT); Hall, Jr., H. Tracy (Provo, UT); Rawle, Michael (Springville, UT)

    2011-05-24T23:59:59.000Z

    A transmission system in a downhole component comprises a plurality of data transmission elements. A coaxial cable having an inner conductor and an outer conductor is disposed within a passage in the downhole component such that at least one capacitor is disposed in the passage and having a first terminal coupled to the inner conductor and a second terminal coupled to the outer conductor. Preferably the transmission element comprises an electrically conducting coil. Preferably, within the passage a connector is adapted to electrically connect the inner conductor of the coaxial cable and the lead wire. The coaxial capacitor may be disposed between and in electrically communication with the connector and the passage. In another embodiment a connector is adapted to electrical connect a first and a second portion of the inner conductor of the coaxial cable and a coaxial capacitor is in electrical communication with the connector and the passage.

  3. EC Transmission Line Risk Identification and Analysis

    SciTech Connect (OSTI)

    Bigelow, Tim S [ORNL

    2012-04-01T23:59:59.000Z

    The purpose of this document is to assist in evaluating and planning for the cost, schedule, and technical project risks associated with the delivery and operation of the EC (Electron cyclotron) transmission line system. In general, the major risks that are anticipated to be encountered during the project delivery phase associated with the implementation of the Procurement Arrangement for the EC transmission line system are associated with: (1) Undefined or changing requirements (e.g., functional or regulatory requirements) (2) Underperformance of prototype, first unit, or production components during testing (3) Unavailability of qualified vendors for critical components Technical risks associated with the design and operation of the system are also identified.

  4. Idaho/Transmission | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are8COaBulkTransmissionSitingProcess.pdfGetecGtel JumpCounty, Texas:ITCSolid WasteIdahoTransmissionHeader.png Roadmap

  5. Idaho/Transmission/Roadmap | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are8COaBulkTransmissionSitingProcess.pdfGetecGtel JumpCounty, Texas:ITCSolidIdaho‎ | Transmission Jump to:

  6. Idaho/Transmission/Summary | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are8COaBulkTransmissionSitingProcess.pdfGetecGtel JumpCounty, Texas:ITCSolidIdaho‎ | Transmission JumpIdaho, the

  7. Radio-Frequency Interference (RFI) From Extra-High-Voltage (EHV) Transmission Lines

    E-Print Network [OSTI]

    Ellingson, Steven W.

    -current (HVAC) transmission lines; high-voltage direct-current (HVDC) transmission lines will be addressed

  8. 2.3-MW Medium-Voltage, Three-Level Wind Energy Inverter Applying a Unique Bus Structure and 4.5-kV Si/SiC Hybrid Isolated Power Modules: Preprint

    SciTech Connect (OSTI)

    Erdman, W.; Keller, J.; Grider, D.; VanBrunt, E.

    2014-11-01T23:59:59.000Z

    A high-efficiency, 2.3-MW, medium-voltage, three-level inverter utilizing 4.5-kV Si/SiC (silicon carbide) hybrid modules for wind energy applications is discussed. The inverter addresses recent trends in siting the inverter within the base of multimegawatt turbine towers. A simplified split, three-layer laminated bus structure that maintains low parasitic inductances is introduced along with a low-voltage, high-current test method for determining these inductances. Feed-thru bushings, edge fill methods, and other design features of the laminated bus structure provide voltage isolation that is consistent with the 10.4-kV module isolation levels. Inverter efficiency improvement is a result of the (essential) elimination of the reverse recovery charge present in 4.5-kV Si PIN diodes, which can produce a significant reduction in diode turn-off losses as well as insulated-gate bipolar transistor (IGBT) turn-on losses. The hybrid modules are supplied in industry-standard 140 mm x 130 mm and 190 mm x 130 mm packages to demonstrate direct module substitution into existing inverter designs. A focus on laminated bus/capacitor-bank/module subassembly level switching performance is presented.

  9. Robotic Platform for Monitoring Underground Cable Systems

    E-Print Network [OSTI]

    Mamishev, Alexander

    . to traverse and monitor fiber-optic overhead ground transmission wires (OPGW) above 66kV power transmission

  10. Transmission Expansion Planning with Re-design

    E-Print Network [OSTI]

    2010-05-17T23:59:59.000Z

    distribution sectors, with a centralized regulation for transmission. In this context, the regulating entity is in charge, not only of operating the grid while maximizing energy ... generation sites are usually far away from the consumption centers. .... Typical examples of commodities are passengers using public transportation,.

  11. Extraordinary acoustic transmission mediated by Helmholtz resonators

    SciTech Connect (OSTI)

    Koju, Vijay [Computation Science Program, Middle Tennessee State University, Murfreesboro, Tennessee 37132 (United States); Rowe, Ebony [Department of Physics and Astronomy, Middle Tennessee State University, Murfreesboro, Tennessee 37132 (United States); Robertson, William M., E-mail: William.Robertson@mtsu.edu [Computation Science Program, Middle Tennessee State University, Murfreesboro, Tennessee 37132 (United States); Department of Physics and Astronomy, Middle Tennessee State University, Murfreesboro, Tennessee 37132 (United States)

    2014-07-15T23:59:59.000Z

    We demonstrate perfect transmission of sound through a rigid barrier embedded with Helmholtz resonators. The resonators are confined within a waveguide and they are oriented such that one neck protrudes onto each side of the barrier. Perfect sound transmission occurs even though the open area of the necks is less than 3% of the barrier area. Maximum transmission occurs at the resonant frequency of the Helmholtz resonator. Because the dimensions of the Helmholtz resonators are much smaller than the resonant wavelength, the transmission is independent of the direction of sound on the barrier and of the relative placement of the necks. Further, we show that the transmitted sound experiences a continuous phase transition of ? radians as a function of frequency through resonance. In simulations of adjacent resonators with slightly offset resonance frequencies, the phase difference leads to destructive interference. By expanding the simulation to a linear array of tuned Helmholtz resonators we show that it is possible to create an acoustic lens. The ability of Helmholtz resonator arrays to manipulate the phase of a plane acoustic wave enables a new class of sonic beam-forming devices analogous to diffractive optics.

  12. Transmission-Planning Research & Development Scoping Project

    E-Print Network [OSTI]

    -99-013 Prepared For: Linda Kelly, Project Manager Energy Systems Integration Program Laurie ten Hope, PIER ProgramTransmission-Planning Research & Development Scoping Project CALIFORNIA ENERGY COMMISSION, California Institute for Energy and the Environment under Contract No. 500-99-013 and by the U.S. Department

  13. A MIXED INTEGER DISJUNCTIVE MODEL FOR TRANSMISSION ...

    E-Print Network [OSTI]

    Laura

    2001-10-26T23:59:59.000Z

    the transmission network expansion problem cannot guarantee ... disjunctive model, optimality can be proven for several hard ..... the size of the RCL list is dynamically self-adjusted (the so ... the RCL size is controlled by the parameter ?, where 0 ? ? ?. 1. ... and senior researcher in power system planning and operation.

  14. ADAPTIVE MULTIMEDIA TRANSMISSION OVER THE INTERNET

    E-Print Network [OSTI]

    Bouras, Christos

    Chapter 20 ADAPTIVE MULTIMEDIA TRANSMISSION OVER THE INTERNET CHRISTOS BOURAS and APOSTOLOS GKAMAS that are available to multimedia applications can be modified very quickly. Multimedia applications must have to multimedia applications, we can use techniques both at the network and application layers. Adaptive

  15. DISTRIBUTED OPPORTUNISTIC TRANSMISSION FOR WIRELESS SENSOR NETWORKS

    E-Print Network [OSTI]

    Islam, M. Saif

    DISTRIBUTED OPPORTUNISTIC TRANSMISSION FOR WIRELESS SENSOR NETWORKS Qing Zhao and Lang Tong School Strategy We consider the problem of information retrieval in sensor networks with mobile access points on Communica- tion and Networks under Grant DAAD19-01-2-0011. ˘ Fig. 1: Sensor networks with mobile access

  16. A neutron transmission study of environmental Gd

    E-Print Network [OSTI]

    Cristiana Oprea; Ioan Alexandru Oprea; Alexandru Mihul

    2014-06-02T23:59:59.000Z

    A new method for the determination of environmental Gd by neutron transmission (NT) experiments is proposed. The NT method is based on the measurements of neutron spectra passing through a target. From the attenuation neutron spectra new data as concentration, width, resonance energies and cross section have been obtained.

  17. WEYL ASYMPTOTICS OF THE TRANSMISSION EIGENVALUES ...

    E-Print Network [OSTI]

    2014-09-02T23:59:59.000Z

    plex internal transmission eigenvalues when the domain is a ball and the index ..... parameter in the operators in a non-linear way; and the implicit choice of the .... in the interior of I, and thus, q ?p ITEs in I, since we include the right endpoint in.

  18. Transmission line environmental assessment guidance document

    SciTech Connect (OSTI)

    Jackson, J.; Pentecost, E.; Muzzarelli, J.

    1994-01-01T23:59:59.000Z

    Since 1939, U.S. utility companies have been required to obtain a Presidential Permit to construct electric transmission lines that cross a U.S. border and connect with a foreign utility. The purpose of this document is to provide Presidential Permit applicants with two types of guidance: (1) on the type of environmental and project descriptive information needed to assess the potential impacts of the proposed and alternative actions and (2) on compliance with applicable federal and state regulations. The main three chapters present information on the purpose and content of this document (Chapter 1); legislative, regulatory, and consultation requirements for transmission line interconnect projects (Chapter 2); and identification of basic transmission system design parameters and environmental data requirements for analysis of potential impacts of the proposed action (Chapter 3). Chapter 3 also includes information on possible techniques or measures to mitigate impacts. Appendix A presents an overview of NEPA requirements and DOE`s implementing procedures. Appendix B summarizes information on legislation that may be applicable to transmission line projects proposed in Presidential Permit applications.

  19. Nanolithography Using High Transmission Nanoscale Bowtie

    E-Print Network [OSTI]

    Xu, Xianfan

    Nanolithography Using High Transmission Nanoscale Bowtie Apertures Liang Wang, Sreemanth M demonstrate that bowtie apertures can be used for contact lithography to achieve nanometer scale resolution. The bowtie apertures with a 30 nm gap size are fabricated in aluminum thin films coated on quartz substrates

  20. Neurons and Neural Transmission Part I / IV

    E-Print Network [OSTI]

    of neurons ­ Classification of neurons ­ Neuron Doctrine "Father of modern neuroscience" #12;Ramon y CajalNeurons and Neural Transmission Part I / IV Anton Kapliy February 24, 2009 #12;Nervous system of optical nerve #12;Ramon y Cajal's neurons Information in neurons flows in one direction: "from dendrites

  1. HVDC transmission: a path to the future?

    SciTech Connect (OSTI)

    Teichler, Stephen L.; Levitine, Ilia

    2010-05-15T23:59:59.000Z

    Direct current transmission has been the poor stepchild of the U.S. electric industry. Although early-generation plants were based on DC technology, it was soon deemed uneconomical to transmit electricity over long distances, but it now appears poised for a change. Both the increasing technical potential and changing economics of HVDC lines promise a growing role in the future. (author)

  2. Policy Issues for Retail Beamed Power Transmission

    E-Print Network [OSTI]

    solar electric power using retail delivery of beamed power. Recent advances in power beaming have made to enable widespread adoption of this clean and sustainable contribution to meeting energy needs. It is seen to micro-renewable energy resource exploitation since wired power transmission is only cost effective over

  3. Methods and systems for micro transmissions

    DOE Patents [OSTI]

    Stalford, Harold L

    2014-12-23T23:59:59.000Z

    Methods and systems for micro transmissions for a micro machine may comprise an input shaft assembly coupled to a micro actuator, an output shaft assembly coupled to a micro shaft, and one or more power conversion elements operable to convert a first type of movement from the micro actuator into a second, disparate type of movement for the micro shaft.

  4. Bordereau de transmission accident du travail

    E-Print Network [OSTI]

    Pouyanne, Nicolas

    Bordereau de transmission accident du travail Service des pensions et accidents du travail accidents du travail du CNRS Accompagné des pièces requises Nom .................................................... Prénom ........................ Matricule ...... Composition du dossier Observations Déclaration d'accident

  5. Oahu Wind Integration and Transmission Study (OWITS): Hawaiian Islands Transmission Interconnection Project

    SciTech Connect (OSTI)

    Woodford, D.

    2011-02-01T23:59:59.000Z

    This report provides an independent review included an initial evaluation of the technical configuration and capital costs of establishing an undersea cable system and examining impacts to the existing electric transmission systems as a result of interconnecting the islands.

  6. A CRITICAL REVIEW OF WIND TRANSMISSION COST ESTIMATES FROM MAJOR TRANSMISSION PLANNING EFFORTS

    E-Print Network [OSTI]

    Mills, Andrew; Wiser, Ryan; Porter, Kevin

    2007-01-01T23:59:59.000Z

    Contingency Analysis Cost Model Flow Analysis Non-Wind Windthe cost of transmission for wind through a meta-analysis ofanalysis in Section 4. Although the results focus on the unit cost of wind

  7. A CRITICAL REVIEW OF WIND TRANSMISSION COST ESTIMATES FROM MAJOR TRANSMISSION PLANNING EFFORTS

    E-Print Network [OSTI]

    Mills, Andrew; Wiser, Ryan; Porter, Kevin

    2007-01-01T23:59:59.000Z

    179c/179c9e0086c0.pdf National Wind CoordinatingTransmission Planning and Wind Energy. Issue Brief. August.and Renewable Energy, Wind & Hydropower Technologies Program

  8. The Cost of Transmission for Wind Energy: A Review of Transmission Planning Studies

    SciTech Connect (OSTI)

    Mills, Andrew D.; Wiser, Ryan; Porter, Kevin

    2009-02-02T23:59:59.000Z

    The rapid development of wind power that the United States has experienced over the last several years has been coupled with a growing concern that wind development will require substantial additions to the nation's transmission infrastructure. Transmission is particularly important for wind power due to the locational dependence of wind resources, the relatively low capacity factor of wind plants, and the mismatch between the short lead time to build a new wind project and the longer lead time often needed to plan, permit, and construct transmission. It is clear that institutional issues related to transmission planning, siting, and cost allocation will pose major obstacles to accelerated wind power deployment, but also of concern is the potential cost of this infrastructure build out. Simply put, how much extra cost will society bear to deliver wind power to load centers? Without an answer to this question, there can be no consensus on whether or not the cost of developing transmission for wind will be a major barrier to further wind deployment, or whether the institutional barriers to transmission expansion are likely to be of more immediate concern. In this report, we review a sample of 40 detailed transmission studies that have included wind power. These studies cover a broad geographic area, and were completed from 2001-2008. Our primary goal in reviewing these studies is to develop a better understanding of the transmission costs needed to access growing quantities of wind generation. A secondary goal is to gain a better appreciation of the differences in transmission planning approaches in order to identify those methodologies that seem most able to estimate the incremental transmission costs associated with wind development. Finally, we hope that the resulting dataset and discussion might be used to inform the assumptions, methods, and results of higher-level assessment models that are sometimes used to estimate the cost of wind deployment (e.g. NEMS and WinDS). The authors and general location of the 40 detailed transmission studies included in our review are illustrated in Figure ES-1. As discussed in the body of the report, these studies vary considerably in scope, authorship, objectives, methodology, and tools. Though we recognize this diversity and are cognizant that comparisons among these studies are therefore somewhat inappropriate, we nonetheless emphasize such simple comparisons in this report. We do so in order to improve our understanding of the range of transmission costs needed to access greater quantities of wind, and to highlight some of the drivers of those costs. In so doing, we gloss over many important details and differences among the studies in our sample. In emphasizing simple comparisons, our analysis focuses primarily on the unit cost of transmission implied by each of the studies. The unit cost of transmission for wind in $/kW terms on a capacity-weighted basis is estimated by simply dividing the total transmission cost in a study by the total amount of incremental generation capacity (wind and non-wind) modeled in that study. In so doing, this metric assumes that within any individual study all incremental generation capacity imposes transmission costs in proportion to its nameplate capacity rating. The limitations to this approach are described in some detail in the body of the report.

  9. Phase 2 Report: Oahu Wind Integration and Transmission Study (OWITS); Hawaiian Islands Transmission Interconnection Project

    SciTech Connect (OSTI)

    Woodford, D.

    2011-02-01T23:59:59.000Z

    This report provides an independent review including an initial evaluation of the technical configuration and capital costs of establishing an undersea cable system and examining impacts to the existing electric transmission systems as a result of interconnecting the islands

  10. Regulations for Electric Transmission and Fuel Gas Transmission Lines Ten or More Miles Long (New York)

    Broader source: Energy.gov [DOE]

    Any person who wishes to construct an electric or gas transmission line that is more than ten miles long must file documents describing the construction plans and potential land use and...

  11. A CRITICAL REVIEW OF WIND TRANSMISSION COST ESTIMATES FROM MAJOR TRANSMISSION PLANNING EFFORTS

    E-Print Network [OSTI]

    Mills, Andrew; Wiser, Ryan; Porter, Kevin

    2007-01-01T23:59:59.000Z

    factor of individual wind farms leads to concerns thatplants. The location of wind farms is dependent on the winda lower-performing wind farm than to build new transmission

  12. Great Plains Wind Energy Transmission Development Project

    SciTech Connect (OSTI)

    Brad G. Stevens, P.E.; Troy K. Simonsen; Kerryanne M. Leroux

    2012-06-09T23:59:59.000Z

    In fiscal year 2005, the Energy & Environmental Research Center (EERC) received funding from the U.S. Department of Energy (DOE) to undertake a broad array of tasks to either directly or indirectly address the barriers that faced much of the Great Plains states and their efforts to produce and transmit wind energy at the time. This program, entitled Great Plains Wind Energy Transmission Development Project, was focused on the central goal of stimulating wind energy development through expansion of new transmission capacity or development of new wind energy capacity through alternative market development. The original task structure was as follows: Task 1 - Regional Renewable Credit Tracking System (later rescoped to Small Wind Turbine Training Center); Task 2 - Multistate Transmission Collaborative; Task 3 - Wind Energy Forecasting System; and Task 4 - Analysis of the Long-Term Role of Hydrogen in the Region. As carried out, Task 1 involved the creation of the Small Wind Turbine Training Center (SWTTC). The SWTTC, located Grand Forks, North Dakota, consists of a single wind turbine, the Endurance S-250, on a 105-foot tilt-up guyed tower. The S-250 is connected to the electrical grid on the 'load side' of the electric meter, and the power produced by the wind turbine is consumed locally on the property. Establishment of the SWTTC will allow EERC personnel to provide educational opportunities to a wide range of participants, including grade school through college-level students and the general public. In addition, the facility will allow the EERC to provide technical training workshops related to the installation, operation, and maintenance of small wind turbines. In addition, under Task 1, the EERC hosted two small wind turbine workshops on May 18, 2010, and March 8, 2011, at the EERC in Grand Forks, North Dakota. Task 2 involved the EERC cosponsoring and aiding in the planning of three transmission workshops in the midwest and western regions. Under Task 3, the EERC, in collaboration with Meridian Environmental Services, developed and demonstrated the efficacy of a wind energy forecasting system for use in scheduling energy output from wind farms for a regional electrical generation and transmission utility. With the increased interest at the time of project award in the production of hydrogen as a critical future energy source, many viewed hydrogen produced from wind-generated electricity as an attractive option. In addition, many of the hydrogen production-related concepts involve utilization of energy resources without the need for additional electrical transmission. For this reason, under Task 4, the EERC provided a summary of end uses for hydrogen in the region and focused on one end product in particular (fertilizer), including several process options and related economic analyses.

  13. Dispersion-free radial transmission lines

    DOE Patents [OSTI]

    Caporaso, George J. (Livermore, CA); Nelson, Scott D. (Patterson, CA)

    2011-04-12T23:59:59.000Z

    A dispersion-free radial transmission line ("DFRTL") preferably for linear accelerators, having two plane conductors each with a central hole, and an electromagnetically permeable material ("EPM") between the two conductors and surrounding a channel connecting the two holes. At least one of the material parameters of relative magnetic permeability, relative dielectric permittivity, and axial width of the EPM is varied as a function of radius, so that the characteristic impedance of the DFRTL is held substantially constant, and pulse transmission therethrough is substantially dispersion-free. Preferably, the EPM is divided into concentric radial sections, with the varied material parameters held constant in each respective section but stepwise varied between sections as a step function of the radius. The radial widths of the concentric sections are selected so that pulse traversal time across each section is the same, and the varied material parameters of the concentric sections are selected to minimize traversal error.

  14. Acoustic data transmission through a drillstring

    DOE Patents [OSTI]

    Drumheller, Douglas S. (Cedar Crest, NM)

    1992-01-01T23:59:59.000Z

    A method and apparatus for acoustically transmitting data along a drillstring is presented. In accordance with one embodiment of the present invention, acoustic data signals are conditioned to counteract distortions caused by the drillstring. Preferably, this conditioning step comprises multiplying each frequency component of the data signal by exp (-ikL) where L is the transmission length of the drillstring, k is the wave number in the drillstring at the frequency of each component and i is (-1).sup.1/2. In another embodiment of this invention, data signals having a frequency content in at least one passband of the drillstring are generated preferably traveling in only one direction (e.g., up the drillstring) while echoes in the drillstring resulting from the data transmission are suppressed.

  15. Acoustic data transmission through a drillstring

    DOE Patents [OSTI]

    Drumheller, D.S.

    1992-07-07T23:59:59.000Z

    A method and apparatus for acoustically transmitting data along a drillstring are presented. In accordance with one embodiment of the present invention, acoustic data signals are conditioned to counteract distortions caused by the drillstring. Preferably, this conditioning step comprises multiplying each frequency component of the data signal by exp ([minus]ikL) where L is the transmission length of the drillstring, k is the wave number in the drillstring at the frequency of each component and i is ([minus]1)[sup 1/2]. In another embodiment of this invention, data signals having a frequency content in at least one passband of the drillstring are generated preferably traveling in only one direction (e.g., up the drillstring) while echoes in the drillstring resulting from the data transmission are suppressed. 20 figs.

  16. Transmissive optomechanical platforms with engineered spatial defects

    E-Print Network [OSTI]

    Edoardo Tignone; Guido Pupillo; Claudiu Genes

    2014-06-23T23:59:59.000Z

    We investigate the optomechanical photon-phonon coupling of a single light mode propagating through an array of vibrating mechanical elements. As recently shown for the particular case of a periodic array of membranes embedded in a high-finesse optical cavity [A. Xuereb, C. Genes and A. Dantan, Phys. Rev. Lett., \\textbf{109}, 223601, (2012)], the intracavity linear optomechanical coupling can be considerably enhanced over the single element value in the so-called \\textit{transmissive regime}, where for motionless membranes the whole system is transparent to light. Here, we extend these investigations to quasi-periodic arrays in the presence of engineered spatial defects in the membrane positions. In particular we show that the localization of light modes induced by the defect combined with the access of the transmissive regime window can lead to additional enhancement of the strength of both linear and quadratic optomechanical couplings.

  17. Secure sequential transmission of quantum information

    E-Print Network [OSTI]

    Kabgyun Jeong; Jaewan Kim

    2015-01-19T23:59:59.000Z

    We propose a quantum communication protocol that can be used to transmit any quantum state, one party to another via several intermediate nodes, securely on quantum communication network. The scheme makes use of the sequentially chained and approximate version of private quantum channels satisfying certain commutation relation of $n$-qubit Pauli operations. In this paper, we study the sequential structure, security analysis, and efficiency of the quantum sequential transmission (QST) protocol in depth.

  18. NREL: Transmission Grid Integration - Wholesale Electricity Market

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What's Possible for Renewable Energy: Grid IntegrationReportTransmission Planning andStudy Phase

  19. NREL: Transmission Grid Integration - Working With Us

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What's Possible for Renewable Energy: Grid IntegrationReportTransmission Planning andStudy

  20. NREL: Transmission Grid Integration Home Page

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What's Possible for Renewable Energy: Grid IntegrationReportTransmission Planning andStudyPhoto of

  1. Mode conversation losses in overmolded millimeter wave transmission lines

    E-Print Network [OSTI]

    Tax, David S. (David Samuel)

    2008-01-01T23:59:59.000Z

    Millimeter wave transmission lines are integral components for many important applications like nuclear fusion and NMR spectroscopy. In low loss corrugated transmission lines propagating the HE,1 mode with a high waveguide ...

  2. Statistical Image Reconstruction Algorithms Using Paraboloidal Surrogates for PET Transmission

    E-Print Network [OSTI]

    Fessler, Jeffrey A.

    Statistical Image Reconstruction Algorithms Using Paraboloidal Surrogates for PET Transmission Reconstruction Algorithms Using Paraboloidal Surrogates for PET Transmission Scans by Hakan Erdogan Chair: Jeffrey A. Fessler Positron Emission Tomography (PET) is a diagnostic imaging tool that provides images

  3. 20% Wind Energy by 2030 - Chapter 4: Transmission and Integration...

    Energy Savers [EERE]

    4: Transmission and Integration into the U.S. Electric System Summary Slides 20% Wind Energy by 2030 - Chapter 4: Transmission and Integration into the U.S. Electric System Summary...

  4. Forced cooling of underground electric power transmission lines : design manual

    E-Print Network [OSTI]

    Brown, Jay A.

    1978-01-01T23:59:59.000Z

    The methodology utilized for the design of a forced-cooled pipe-type underground transmission system is presented. The material is divided into three major parts: (1) The Forced-cooled Pipe-Type Underground Transmission ...

  5. An improved speech transmission index for intelligibility prediction Belinda Schwerin

    E-Print Network [OSTI]

    transmission index; Modulation transfer function; Speech enhancement; Objective evaluation; Speech intelligibility; Short-time modulation spectrum 1. Introduction The enhancement of speech corrupted by noise hasAn improved speech transmission index for intelligibility prediction Belinda Schwerin , Kuldip

  6. Electric Transmission One Year after the Energy Bill

    SciTech Connect (OSTI)

    Gray, Ed

    2006-08-15T23:59:59.000Z

    The Energy Policy Act of 2005 embodies numerous provisions that will increase investment in the electric transmission grid. Many actions have occurred in the first year of implementation that should strengthen the transmission system in the United States. (author)

  7. Sandia National Laboratories: long-distance power transmission

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    grid relies on power transmission from the production source-be it a coal-fired plant, solar array, or wind farm-to the consumer. Long-distance transmission results in...

  8. Transmission System Performance Analysis for High-Penetration Photovoltaics

    SciTech Connect (OSTI)

    Achilles, S.; Schramm, S.; Bebic, J.

    2008-02-01T23:59:59.000Z

    This study is an assessment of the potential impact of high levels of penetration of photovoltaic (PV) generation on transmission systems. The effort used stability simulations of a transmission system with different levels of PV generation and load.

  9. Investigation of Multi-Frequency Power Transmission and System

    E-Print Network [OSTI]

    Barazarte Conte, Ronald

    2012-10-19T23:59:59.000Z

    This dissertation presents a new power system transmission concept based on frequency selectivity named Multi-Frequency Power System (MFPS). This system allows for selective power transmission among terminals in an interconnected system...

  10. 1996 Wholesale Power and Transmission Rate Schedules.

    SciTech Connect (OSTI)

    United States. Bonneville Power Administration.

    1996-10-01T23:59:59.000Z

    Bonneville Power Administration`s (BPA) 1996 Wholesale Power Rate Schedules, 1996 Ancillary Products and Services Rate Schedule, 1996 Transmission Rate Schedules, and General Rate Schedule Provisions, contained herein, were approved on an interim basis effective October 1, 1996. These rate schedules and provisions were approved by the Federal Energy Regulatory Commission (FERC), United States Department of Energy, in September 1996 (Docket Nos EF96-2011-000 and EF96f-2021-000). These rate schedules and General Rate Schedule Provisions were approved on a final basis by the FERC July 30, 1997, in Dept. of Energy--Bonneville Power Administration, Docket Nos. EF96-2011-000 and EF96-2021-000. Except as noted elsewhere, these 1996 rate schedules and provisions supersede BPA`s Wholesale Power Rate Schedules and General Rate Schedule Provisions, and Transmission Rate Schedules and General Transmission Rate Schedule Provisions, effective October 1, 1995. These rate schedules and general rate schedule provisions include all errata.

  11. Hybrid powertrain system including smooth shifting automated transmission

    DOE Patents [OSTI]

    Beaty, Kevin D.; Nellums, Richard A.

    2006-10-24T23:59:59.000Z

    A powertrain system is provided that includes a prime mover and a change-gear transmission having an input, at least two gear ratios, and an output. The powertrain system also includes a power shunt configured to route power applied to the transmission by one of the input and the output to the other one of the input and the output. A transmission system and a method for facilitating shifting of a transmission system are also provided.

  12. Transmission Project Reporting FPA 216h | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Disturbance Events Incident Reporting Emergency Situation Reports Energy Assurance Daily Transmission Project Reporting Library New Reports & Other Materials Meetings & Events...

  13. Reference: RGL 83-09 Subject: POWER TRANSMISSION LINES

    E-Print Network [OSTI]

    US Army Corps of Engineers

    Reference: RGL 83-09 Subject: POWER TRANSMISSION LINES Title: MARKING OF AERIAL POWER TRANSMISSION. 1. The marking of aerial power transmission lines, cables, and structures over the navigable waters LINES, CABLES, & STRUCTURES Issued: 07/13/83 Expires: 12/31/85 Originator: DAEN-CWO-N Description: ARMY

  14. Using Transmission Lines for Global On-Chip Communication

    E-Print Network [OSTI]

    Huang, Michael C.

    1 Using Transmission Lines for Global On-Chip Communication Aaron Carpenter, Jianyun Hu, Jie Xu-switched network-on-chip a less attractive option. An alternative solution uses well-engineered transmission lines as communication links. These transmission lines, along with simple, practical circuits using modern CMOS technol

  15. Asymmetric parametric amplification in nonlinear left-handed transmission lines

    E-Print Network [OSTI]

    Asymmetric parametric amplification in nonlinear left-handed transmission lines David A. Powell amplification in nonlinear left-handed transmission lines, which serve as model systems for nonlinear negative-handed regime. © 2009 American Institute of Physics. DOI: 10.1063/1.3089842 Left-handed transmission lines

  16. Multifrequency Wilkinson Power Divider Using Microstrip Nonuniform Transmission Lines

    E-Print Network [OSTI]

    Paris-Sud XI, Université de

    Multifrequency Wilkinson Power Divider Using Microstrip Nonuniform Transmission Lines Mohammad desired frequencies. The proposed structure contains two Microstrip Nonuniform Transmission Lines (MNTLs­6] and using composite right/left-handed transmission line (CRLH) [7]. The main disadvantage of multistage

  17. New approach for modelling distributed MEMS transmission lines

    E-Print Network [OSTI]

    Akin, Tayfun

    New approach for modelling distributed MEMS transmission lines K. Topalli, M. Unlu, S. Demir, O for the distributed MEMS transmission line (DMTL) structures. In this new model, the MEMS bridges that are used as the loading elements of the DMTL structures are represented as low-impedance transmission lines, rather than

  18. Empirical Analysis of Transmission Power Control Algorithms for Wireless

    E-Print Network [OSTI]

    California at Berkeley, University of

    Empirical Analysis of Transmission Power Control Algorithms for Wireless Sensor Networks CENTS sensor network testbed. #12;Related Work · Some number of works tried to adjust radio transmission power command in WSN. · Many-to-one · In-network processing. #12;Index · Description of transmission power

  19. Network Coding for Joint Storage and Transmission with Minimum Cost

    E-Print Network [OSTI]

    Jiang, Anxiao "Andrew"

    transmission and data storage in networks. Its power comes from the improved flexibility that codeword symbolsNetwork Coding for Joint Storage and Transmission with Minimum Cost Anxiao (Andrew) Jiang@cs.tamu.edu. Abstract-- Network coding provides elegant solutions to many data transmission problems. The usage

  20. Sixth Northwest Conservation and Electric Power Plan Chapter 7: Transmission

    E-Print Network [OSTI]

    Sixth Northwest Conservation and Electric Power Plan Chapter 7: Transmission Summary of Key, both in operating the existing system and in planning for new major transmission lines. Since then transmission system is an integral part of the regional power system. It functions roughly like the highway

  1. Transmission power control game with SINR as objective function

    E-Print Network [OSTI]

    Avrachenkov, Konstantin

    Transmission power control game with SINR as objective function E. Altman1 , K. Avrachenkov1 State University, Russia agarnaev@rambler.ru Abstract. We consider the transmission power control networks, Power Control, Nash Equilibrium, Co- operation 1 Introduction We consider the transmission power

  2. Application of High-Angle Annular Dark Field Scanning Transmission

    E-Print Network [OSTI]

    Utsunomiya, Satoshi

    Transmission Electron Microscopy-Energy Dispersive X-ray Spectrometry, and Energy-Filtered Transmission field scanning transmission electron microscopy (HAADF-STEM), STEM-energy-dispersive X-ray spectrometry). Techniquesthatareusefulinanalyzingultrafineatmospheric particles, such as STEM, EELS (electron energy loss spec- trometry), AFM, and mass spectrometry

  3. Electricity generation with looped transmission networks: Bidding to an ISO

    E-Print Network [OSTI]

    Ferris, Michael C.

    on a transmission network from net generation nodes to net consumption nodes is governed by the Kirchoff Laws [45Electricity generation with looped transmission networks: Bidding to an ISO Xinmin Hu Daniel Ralph to model markets for delivery of electrical power on looped transmission networks. It analyzes

  4. EIS-0474: Southline Transmission Line Project; Arizona and New Mexico

    Broader source: Energy.gov [DOE]

    DOE’s Western Area Power Administration is preparing this EIS to evaluate the environmental impacts of the proposed Southline Transmission Project, which would consist of a new 225-mile transmission line between existing substations at Afton, New Mexico, and Apache, Arizona, and improvements to approximately 130 miles of existing transmission lines between the Apache and Saguaro, Arizona substations.

  5. Structural Optimization of High Voltage Transmission Line Towers considering

    E-Print Network [OSTI]

    Colominas, Ignasi

    Structural Optimization of High Voltage Transmission Line Towers considering Continuum and Discrete/or to common designs largely repeated (e.g. automotive compo- nents), and high voltage transmission towers can than conventional designs of high voltage transmission line towers. The optimization model proposed

  6. Classification of the Visual Landscape for Transmission Planning1

    E-Print Network [OSTI]

    Standiford, Richard B.

    . The third concept is that the specific design of transmission towers can result in a negative re- sponseClassification of the Visual Landscape for Transmission Planning1 Curtis Miller2/ , Nargis Jetha3 can be made of the visual change to the landscape due to the introduction of transmission facilities

  7. Transmission and Generation Investment In a Competitive Electric Power Industry

    E-Print Network [OSTI]

    California at Berkeley. University of

    .3 Transmission Property Rights and Congestion Contracts . . . . . . . . . . . . . . . . . 7 2.4 How TransmissionPWP-030 Transmission and Generation Investment In a Competitive Electric Power Industry James of California Energy Institute 2539 Channing Way Berkeley, California 94720-5180 www.ucei.berkeley.edu/ucei #12

  8. EIS-0390: Eastern Plains Transmission Project, Colorado and Kansas.

    Broader source: Energy.gov [DOE]

    This EIS is for Western Area Power Administration's proposal to participate with Tri-State Generation and Transmission Association, Inc. (Tri-State), to construct the proposed Eastern Plains Transmission Project (Project). Western’s participation with Tri-State would be in exchange for capacity rights on the transmission lines.

  9. Capturing the cloud of MRSA diversity after transmission and during infection 2 reveals complex and heterogenous carriage and transmission

    E-Print Network [OSTI]

    Paterson, Gavin K.; Harrison, Ewan M.; Murray, Gemma G.R.; Welch, John J.; Warland, James H.; Holden, Matthew T.G.; Morgan, Fiona J.E.; Ba, Xiaoliang; Koop, Gerrit; Harris, Simon R.; Maskell, Duncan J.; Peacock, Sharon J.; Herrtage, Michael E.; Parkhill, Julian; Holmes, Mark A.

    2015-01-01T23:59:59.000Z

    1 Capturing the cloud of MRSA diversity after transmission and during infection 1 reveals complex and heterogenous carriage and transmission 2 3 Running title: MRSA tracking and the cloud of diversity 4 5 Gavin K. Paterson 1#¶, Ewan M... transmission event. To 55 further understand the cloud of diversity that exists within colonized individuals and 56 5 during transmission, we undertook deep sequencing of a methicillin-resistant S. aureus 57 (MRSA) ‘outbreak’ at a veterinary hospital...

  10. Evaluation of a EMCCD detector for emission-transmission computed tomography

    E-Print Network [OSTI]

    Teo, B K; Shestakova, I; Sun, M; Barber, W C; Nagarkar, V V; Hasegawa, B H

    2006-01-01T23:59:59.000Z

    emission-transmission computed-tomography imaging system,”for Emission-Transmission Computed Tomography B. K. Teo, I.sion-transmission computed tomography. The detector has an

  11. Method for bonding a transmission line to a downhole tool

    DOE Patents [OSTI]

    Hall, David R. (Provo, UT); Fox, Joe (Spanish Fork, UT)

    2007-11-06T23:59:59.000Z

    An apparatus for bonding a transmission line to the central bore of a downhole tool includes a pre-formed interface for bonding a transmission line to the inside diameter of a downhole tool. The pre-formed interface includes a first surface that substantially conforms to the outside contour of a transmission line and a second surface that substantially conforms to the inside diameter of a downhole tool. In another aspect of the invention, a method for bonding a transmission line to the inside diameter of a downhole tool includes positioning a transmission line near the inside wall of a downhole tool and placing a mold near the transmission line and the inside wall. The method further includes injecting a bonding material into the mold and curing the bonding material such that the bonding material bonds the transmission line to the inside wall.

  12. Ponderomotive phase plate for transmission electron microscopes

    DOE Patents [OSTI]

    Reed, Bryan W. (Livermore, CA)

    2012-07-10T23:59:59.000Z

    A ponderomotive phase plate system and method for controllably producing highly tunable phase contrast transfer functions in a transmission electron microscope (TEM) for high resolution and biological phase contrast imaging. The system and method includes a laser source and a beam transport system to produce a focused laser crossover as a phase plate, so that a ponderomotive potential of the focused laser crossover produces a scattering-angle-dependent phase shift in the electrons of the post-sample electron beam corresponding to a desired phase contrast transfer function.

  13. The year in review: Electric transmission

    SciTech Connect (OSTI)

    Hebert, C. Jr.

    1999-12-01T23:59:59.000Z

    This writing and the comments contained herein support the conclusion that mandating a solution to transmission woes is not the proper choice. Even if it were the right choice, it would not be the way to go. FERC exists in a sophisticated energy world and must comprehend that without the help of the energy industry it is doomed to fail. Technology changes, economies change, and even the FERC itself changes, and will again. This is all part of the energy journey. RTOs, pools, ISOs, RTOs, and, yes, Transcos are a part of the evolution of energy regulation and perhaps deregulation to some degree.

  14. California/Transmission/Summary | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand Jump to:EzfeedflagBiomassSustainableCSL Gas RecoveryInformationTransmission Permitting at a Glance

  15. Transmission SEAB Presentation | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742EnergyOn April 23,EnergyChicopeeTechnologyfact sheetTransferring the Wayne, NJ,Know?'Transmission

  16. Eldorado Ivanpah Transmission Project | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand JumpConceptual Model,DOEHazel Crest, Illinois:EdinburghEldorado Ivanpah Transmission Project Jump to:

  17. Richard Shaheen named Senior VP of Transmission

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What's PossibleRadiation Protection TechnicalResonant SoftRichard-Shaheen-named-Senior-VP-of-Transmission

  18. American Transmission Systems Inc | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are being directedAnnualProperty EditCalifornia: Energy Resources Jump to:Almo,Transmission Systems Inc Jump to:

  19. NREL: Transmission Grid Integration - Wind Integration Datasets

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What's Possible for Renewable Energy: Grid IntegrationReportTransmission Planning andStudy PhaseWind

  20. Transmission Capital Limited | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand Jump to:Ezfeedflag JumpID-f <MaintainedInformationThePtyTownTrama TecnoTransmission Capital

  1. Gateway West Transmission Line | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are8COaBulkTransmissionSitingProcess.pdf Jump1946865°,Park, Texas: EnergyGarvin County,|GasconadeOhio:Gateway

  2. Georgia Transmission Corp | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are8COaBulkTransmissionSitingProcess.pdf Jump1946865°,Park,2005) | Open

  3. Transmission/Nepa Database | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov YouKizildere IRaghuraji Agro IndustriesTown of Ladoga, Indiana (Utility Company) JumpTradeWindPrepared asTransmissionNepa

  4. Transmission/Resource Library | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov YouKizildere IRaghuraji Agro IndustriesTown of Ladoga, Indiana (Utility Company)Library < Transmission Jump to:

  5. Moving Beyond Paralysis: How States and Regions Are Creating Innovative Transmission Projects; May 2009 - May 2010

    SciTech Connect (OSTI)

    Schumacher, A.; Fink, S.; Porter, K.

    2009-10-01T23:59:59.000Z

    This report profiles certain state and regional transmission policy initiatives aimed at promoting transmission development, mainly to access renewable resources.

  6. Exploration of Resource and Transmission Expansion Decisions in the Western Renewable Energy Zone Initiative

    E-Print Network [OSTI]

    Mills, Andrew

    2010-01-01T23:59:59.000Z

    based on existing transmission corridors or rights of way.The transmission costs also include right-of-way costs,

  7. Radio frequency communication system utilizing radiating transmission lines

    DOE Patents [OSTI]

    Struven, Warren C. (San Carlos, CA)

    1984-01-01T23:59:59.000Z

    A radio communication system for use in tunnels, mines, buildings or other shielded locations in which a pair of radiating transmission lines (30), (31) extend through such location in spaced coextensive relation to each other. Each transmission line (30), (31) has at least one unidirectional amplifier (32), (33) interposed therein with the sense of the unidirectional amplifier (32) of one transmission line (30) being opposite to the sense of the unidirectional amplifier (33) of the other transmission line (31). Each of the amplifiers (32), (33) has a gain which is less than the coupling loss between the transmission lines (30), (31). Two or more mobile transceivers (35) in the location served by the system are coupled to the transmission lines (30), (31) by electromagnetic wave propagation in space in order to communicate directly with each other at a given radio frequency within the frequency range of the system.

  8. Multi-transmission-line-beam interactive system

    SciTech Connect (OSTI)

    Figotin, Alexander; Reyes, Guillermo [Department of Mathematics, University of California at Irvine, Irvine, California 92697-3875 (United States)] [Department of Mathematics, University of California at Irvine, Irvine, California 92697-3875 (United States)

    2013-11-15T23:59:59.000Z

    We construct here a Lagrangian field formulation for a system consisting of an electron beam interacting with a slow-wave structure modeled by a possibly non-uniform multiple transmission line (MTL). In the case of a single line we recover the linear model of a traveling wave tube due to J. R. Pierce. Since a properly chosen MTL can approximate a real waveguide structure with any desired accuracy, the proposed model can be used in particular for design optimization. Furthermore, the Lagrangian formulation provides: (i) a clear identification of the mathematical source of amplification, (ii) exact expressions for the conserved energy and its flux distributions obtained from the Noether theorem. In the case of uniform MTLs we carry out an exhaustive analysis of eigenmodes and find sharp conditions on the parameters of the system to provide for amplifying regimes.

  9. Nonlinear transmission line based electron beam driver

    SciTech Connect (OSTI)

    French, David M.; Hoff, Brad W.; Tang Wilkin; Heidger, Susan; Shiffler, Don [Directed Energy Directorate, Air Force Research Laboratory, Kirtland AFB, New Mexico 87117 (United States); Allen-Flowers, Jordan [Program in Applied Mathematics, University of Arizona, Tucson, Arizona 85721 (United States)

    2012-12-15T23:59:59.000Z

    Gated field emission cathodes can provide short electron pulses without the requirement of laser systems or cathode heating required by photoemission or thermionic cathodes. The large electric field requirement for field emission to take place can be achieved by using a high aspect ratio cathode with a large field enhancement factor which reduces the voltage requirement for emission. In this paper, a cathode gate driver based on the output pulse train from a nonlinear transmission line is experimentally demonstrated. The application of the pulse train to a tufted carbon fiber field emission cathode generates short electron pulses. The pulses are approximately 2 ns in duration with emission currents of several mA, and the train contains up to 6 pulses at a frequency of 100 MHz. Particle-in-cell simulation is used to predict the characteristic of the current pulse train generated from a single carbon fiber field emission cathode using the same technique.

  10. Giant vacuum forces via transmission lines

    E-Print Network [OSTI]

    Ephraim Shahmoon; Igor Mazets; Gershon Kurizki

    2014-07-23T23:59:59.000Z

    Quantum electromagnetic fluctuations induce forces between neutral particles, known as the van der Waals (vdW) and Casimir interactions. These fundamental forces, mediated by virtual photons from the vacuum, play an important role in basic physics and chemistry, and in emerging technologies involving, e.g. micro-electromechanical systems or quantum information processing. Here we show that these interactions can be enhanced by many orders of magnitude upon changing the character of the mediating vacuum-modes. By considering two polarizable particles in the vicinity of any standard electric transmission line, along which photons can propagate in one dimension (1d), we find a much stronger and longer-range interaction than in free-space. This enhancement may have profound implications on many-particle and bulk systems, and impact the quantum technologies mentioned above. The predicted giant vacuum force is estimated to be measurable in a coplanar waveguide line.

  11. QER Public Meeting: Petroleum Product Transmission & Distribution

    Broader source: Energy.gov [DOE]

    May 27, 2014 Public Meeting: Petroleum Product Transmission & Distribution (including CO2/EOR) On May 27, 2014, the DOE will hold a public meeting in New Orleans, Louisiana. The May 27, 2014 public meeting will feature facilitated panel discussions, followed by an open microphone session. Persons desiring to speak during the 6 open microphone session at the public meeting should come prepared to speak for no more than 3 minutes and will be accommodated on a first- come, first- serve basis, according to the order in which they register to speak on a sign-in sheet available at the meeting location, on the morning of the meeting. In advance of the meeting, DOE anticipates making publicly available a briefing memorandum providing useful background information regarding the topics under discussion at the meeting. DOE will post this memorandum on its website: http://energy.gov

  12. Boost type PWM HVDC transmission system

    SciTech Connect (OSTI)

    Ooi, B.T.; Wang, X. (McGill Univ., Montreal, PQ (Canada). Dept. of Electrical Engineering)

    1991-10-01T23:59:59.000Z

    This paper reports that conventional HVdc is built around the mercury arc rectifier or the thyristor which requires line commutation. The advances of fast, high power GTO's and future devices such as MCT's with turn off capabilities, are bringing PWM techniques within the range of HVdc applications. By combining PWM techniques to the boost type bridge topology, one has an alternate system of HVdc Transmission. On the ac side, the converter station has active controls over: the voltage amplitude, the voltage angle and the frequency. On the dc side, parallel connections facilitate multi-terminal load sharing by simple local controls so that redundant communication channels are not required. Bidirectional power through each station is accomplished by the reversal of the direction of dc current flow. These claims have been substantiated by experimental results from laboratory size multi-terminal models.

  13. GTO thyristor applications for HVDC transmission systems

    SciTech Connect (OSTI)

    Yamada, H.; Sampei, M. (Electric Power Development Co. Ltd., Tokyo (Japan)); Kashiwazaki, H.; Tanaka, C. (Hitachi Ltd., Tokyo (Japan)); Takahashi, T.; Horivchi, T. (Toshiba Corp., Tokyo (JP))

    1990-07-01T23:59:59.000Z

    The development of a large capacity gate turn off thyristor (GTO) has made it possible to manufacture self-commutated convertors employing GTO for power applications. In this paper, conceptual designs for convertor station equipment for a HVDC transmission system employing current as well as voltage source type GTO convertors (simply referred to as VSTGC and CSTGC) are presented. The study result indicates that the VSTGC is preferable over the CSTGC. Also presented in this paper is a preliminary economic comparison between two HVDC system alternatives for applying power to a weak ac system, one employing a self-commutated GTO convertor and the other employing a combination of line-commutated convertor and a synchronous condenser. The result indicates that the two HVDC convertor station alternatives cost about the same.

  14. Methods, apparatus, and systems for monitoring transmission systems

    DOE Patents [OSTI]

    Polk, Robert E. (Idaho Falls, ID) [Idaho Falls, ID; Svoboda, John M. (Idaho Falls, ID) [Idaho Falls, ID; West, Phillip B. (Idaho Falls, ID) [Idaho Falls, ID; Heath, Gail L. (Iona, ID) [Iona, ID; Scott, Clark L. (Idaho Falls, ID) [Idaho Falls, ID

    2010-08-31T23:59:59.000Z

    A sensing platform for monitoring a transmission system, and method therefor, may include a sensor that senses one or more conditions relating to a condition of the transmission system and/or the condition of an environment around the transmission system. A control system operatively associated with the sensor produces output data based on an output signal produced by the sensor. A transmitter operatively associated with the control system transmits the output data from the control system.

  15. Microsoft PowerPoint - WAPA Transmission Developments in NM ...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    NM, CO, WY, KS, ND, UT, SD & ID Tasked with planning and financing of transmission lines within their respective states RETA has the additional requirement that 30% of...

  16. DOE/EA-1366; Environmental Assessment Santiam-Bethel Transmission...

    Broader source: Energy.gov (indexed) [DOE]

    "Plans should designate sites of power generation and the location of electric transmission lines in areas intended to support desired levels of urban and rural development." The...

  17. Wind Integration, Transmission, and Resource Assessment andCharacteri...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    totaling more than 25 million for 41 projects focused on integration, transmission, and resource assessment and characterization. This report highlights each of these R&D...

  18. Report on Transmission Cost Allocation for RTOs and Others (Presentation)

    SciTech Connect (OSTI)

    Coles, L.; Porter, K.

    2011-05-01T23:59:59.000Z

    This presentation describes in summary fashion some present transmission cost allocation methods, especially as this relates to the development of utility-scale renewable power sources.

  19. Coordinating Interstate ElectricTransmission Siting: An Introduction...

    Broader source: Energy.gov (indexed) [DOE]

    the near future. While improved demand-side management (including energy effi ciency and demand response), bett er utilization of the existing transmission grid, and other...

  20. In-Situ Transmission Electron Microscopy Probing of Native Oxide...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Probing of Native Oxide and Artificial Layers on Silicon Nanoparticles for Lithium Ion In-Situ Transmission Electron Microscopy Probing of Native Oxide and Artificial...