Wisconsin Section-ASCE Engineering Achievement Awards
 

Summary: Wisconsin Section-ASCE
Engineering Achievement Awards
Category
Category A: Construction Costs Under $2,000,000
Eligibility Statement
Construction of the capping project at the MMSD Lagoon Site began in January, 1999
and was completed in July, 2001. EPA conducted a formal post construction inspection
in the summer of 2001 and in November, 2001 provided notice that the construction
phase of the project was considered complete.
Project Team
Owner: Madison Metropolitan Sewerage District
Consultant/Designer: Tuncer B. Edil, Ph.D, P.E.
Assistant Engineer: Ahmet H. Aydilek, Ph.D.
Engineer: Madison Metropolitan Sewerage District
Project Manager: David S. Taylor, MMSD
Assistant Project Manager: Michael D. Northouse, MMSD
General Contractor: Madison Metropolitan Sewerage District
Subcontractors/Suppliers: Rice Grading, Inc.
Geosynthetics, Inc.
CRM Ecosystems, Inc.

  

Source: Aydilek, Ahmet - Department of Civil and Environmental Engineering, University of Maryland at College Park

 

Collections: Engineering