Title: Development of a Remote External Repair Tool for Damaged or Defective Polyethylene Pipe

Technical Report ·
DOI:https://doi.org/10.2172/908747· OSTI ID:908747

Current procedures for repairing polyethylene (PE) gas pipe require excavation, isolation, and removal of the damaged section of pipe followed by fusing a new section of pipe into place. These techniques are costly and very disruptive. An alternative repair method was developed at Timberline Tool with support from Oregon State University (OSU) and funding by the U. S. Department of Energy National Energy Technology Laboratory (DOE/NETL). This project was undertaken to design, develop and test a tool and method for repairing damaged PE pipe remotely and externally in situ without squeezing off the flow of gas, eliminating the need for large-scale excavations. Through an iterative design and development approach, a final engineered prototype was developed that utilizes a unique thermo-chemical and mechanical process to apply a permanent external patch to repair small nicks, gouges and punctures under line pressure. The project identified several technical challenges during the design and development process. The repair tool must be capable of being installed under live conditions and operate in an 18-inch keyhole. This would eliminate the need for extensive excavations thus reducing the cost of the repair. Initially, the tool must be able to control the leak by encapsulating the pipe and apply slight pressure at the site of damage. Finally, the repair method must be permanent at typical operating pressures. The overall results of the project have established a permanent external repair method for use on damaged PE gas pipe in a safe and cost-effective manner. The engineered prototype was subjected to comprehensive testing and evaluation to validate the performance. Using the new repair tool, samples of 4-inch PE pipe with simulated damage were successfully repaired under line pressure to the satisfaction of DOE/NETL and the following natural gas companies: Northwest Natural; Sempra Energy, Southwest Gas Corporation, Questar, and Nicor. However, initial results of accelerated age testing on repaired pipe samples showed that the high density polyethylene (HDPE) pipe patch material developed a small crack at the high stress areas surrounding the patched hole within the first 48 hours of hot water testing, indicating that the patch material has a 25-year lifespan. Based on these results, further research is continuing to develop a stronger repair patch for a satisfactory 50-year patch system. Additional tests were also conducted to evaluate whether any of the critical performance properties of the PE pipe were reduced or compromised by the repair technique. This testing validated a satisfactory 50-year patch system for the pipe.

Research Organization:
Timberwolf Corp
Sponsoring Organization:
USDOE
DOE Contract Number:
FC26-03NT41879
OSTI ID:
908747
Country of Publication:
United States
Language:
English

Similar Records

UK's natural gas system combining the old and the new
Journal Article · Fri Jan 01 00:00:00 EST 1982 · Gas Ind.; () · OSTI ID:908747

INTERNAL REPAIR OF PIPELINES
Technical Report · Wed Jul 20 00:00:00 EDT 2005 · OSTI ID:908747

IMPROVED NATURAL GAS STORAGE WELL REMEDIATION
Technical Report · Sat Dec 01 00:00:00 EST 2001 · OSTI ID:908747