skip to main content
OSTI.GOV title logo U.S. Department of Energy
Office of Scientific and Technical Information

Title: MH-1A Sturgis Decommissioning and Dismantlement - 20281

Conference ·
OSTI ID:23030467
;  [1]; ; ;  [2]
  1. U.S. Army Corps of Engineers - USACE (United States)
  2. Aptim Federal Services, LLC (United States)

The U.S. Army Corps of Engineers (USACE) with its prime contractor, Aptim Federal Services, LLC (APTIM), recycled 5,260 metric tons (11.6 million pounds) of material from Sturgis Barge (Sturgis) during the Decommissioning and Dismantlement of the MH-1A nuclear power reactor. The overall objective of the project was to reduce residual radioactivity associated with MH-1A to levels that permitted release of Sturgis for dismantlement and termination of the Army Reactor Office permit. By effectively applying waste hierarchy's three Rs - reduce, reuse and recycle - the Sturgis project not only minimized the amount of waste that required disposal at landfills, but also reduced the potential for long-term environmental liability emanating from these landfills. The project team completed the physical decommissioning efforts in June 2018 in Galveston, TX. In September 2018, radiological surveys were completed to demonstrate the vessel could be released for shipbreaking. Sturgis was towed from Galveston, TX to Brownsville, TX in late September 2018. Shipbreaking, dismantlement and recycling efforts began in early October 2018 and were completed on 15 March 2019. As part of the decommissioning effort in Galveston, the team shipped 69 shipments (860 metric tons) of low-level radioactive waste and radioactive components to the Waste Control Specialist (WCS) facility in Andrews TX for disposal. Certain radioactive components had to be transferred to the Department of Energy prior to placing the materials into the Federal Waste Facility located within WCS. However, most of the radioactive waste was characterized, profiled, approved and managed under the WCS permitted radioactive waste exemption process authorized and implemented by the Texas Commission on Environmental Quality (TCEQ) and the Radioactive Materials Division. This allows LLRW and LLMW to be shipped as regulated waste and then upon receipt at WCS through satisfying the relevant waste acceptance criteria the waste is exempted and placed into the WCS RCRA permitted cell. An additional 35 shipments (544 metric ton) of contaminated hazardous waste water were transported to U.S. Ecology in Robstown, TX for treatment/disposal. An additional 36 shipments (500 metric tons) of non-hazardous wastewater was sent to Republic Waste Services' facility in Fresno, TX. The disposal of these materials required close coordination with State of Texas regulators. During decommissioning, the project team recycled approximately 270 metric tons (600,000 pounds) of lead and steel. As part of the dismantlement in Brownsville, TX the team recycled approximately 5,000 metric tons (11 million pounds) of ferrous and non-ferrous material, limiting our disposal requirements to about 180 metric tons (400,000 pounds) of material (<4% from entire shipbreaking activity). Although the primary hazard being mitigated by this project was radiological, recycling was always a priority for the project. The team strived to achieve sustainability goals as we implemented this one of a kind project. Scrap metal recycling has a large positive impact on the environment and can also favorably impact project disposal costs. Steel is among the most recycled material in the world. Nearly 40% of the world's steel production is made from scrap. Recycling steel also requires 75% less energy than producing it from raw materials. By using recycled steel rather than virgin materials, 2.33 kg of carbon emissions are eliminated per kg of steel [1]. The project recycled more than 4,500 metric tons (10 million pounds) of steel, which eliminated about 10,400 metric tons (23 million pounds) of CO{sub 2}. By implementing a recycling initiative for the Sturgis project, the team was able to realize cost avoidance for disposal of scrap, cost savings from the metals recycled, plus the project provided benefits to the environment through our recycling efforts. Once the dismantlement was complete, the team prepared a detailed decommissioning closure report, which allowed for the termination of the Army Reactor Decommissioning Permit. While it not only reduced any potential long-term environmental liability, this project to decommission and dismantle a floating nuclear power plant is truly unprecedented - it is a prime example of the USACE mission which is: 'Engineering solutions for the Nation's toughest challenges'. This unique, one of a kind, historical power plant was never designed to be taken apart, and the available information about its construction was lacking in many details. The hazards that required mitigation dictated a painstaking and deliberate process in order to avoid any release to the environment and the community, and to protect the health and safety of the workers involved while keeping the waste hierarchy's three R's - reduce, reuse and recycle at the forefront. (authors)

Research Organization:
WM Symposia, Inc., PO Box 27646, 85285-7646 Tempe, AZ (United States)
OSTI ID:
23030467
Report Number(s):
INIS-US-21-WM-20281; TRN: US21V1590070819
Resource Relation:
Conference: WM2020: 46. Annual Waste Management Conference, Phoenix, AZ (United States), 8-12 Mar 2020; Other Information: Country of input: France; 4 refs.; available online at: https://www.xcdsystem.com/wmsym/2020/index.html
Country of Publication:
United States
Language:
English