Structural analysis of the equipment removal system for tanks 241C106 and 241AY102
The calculations documented in this report show that the ERS major components are structurally qualified to complete the objective: install the removed equipment into a shipping container, transport and store the container at the Central Waste Complex (CWC). The analysis for the structural members of the ERS components considers live load with an impact factor of 125% and dead load. An allowable stress of 1/3 yield is used for all structural components carrying the load based on DOE-RL-92-36. Adherence to DOE-RL-92-36 is not a code requirement. However, due to the loads considered, this factor of safety is appropriate. The calculations meet the strength requirements of the American Institute for Steel Construction (AISC 1989) for all non-critical structural elements.
- Research Organization:
- Westinghouse Hanford Co., Richland, WA (United States)
- Sponsoring Organization:
- USDOE, Washington, DC (United States)
- DOE Contract Number:
- AC06-87RL10930
- OSTI ID:
- 10116034
- Report Number(s):
- WHC-SD-W320-DA-001; ON: DE95005289; TRN: 95:001500
- Resource Relation:
- Other Information: PBD: Oct 1994
- Country of Publication:
- United States
- Language:
- English
Similar Records
Analysis of the 241SY101 pump removal trailer and the 241SY101 strongback
Shot loading trainer analysis